EPA 910/9-77-039
AUGUST, 1977
         MONITORING OF TRACE CONSTITUENTS
                      DURING PCB  RECOVERY
                      DREDGING OPERATIONS

                       DUWAMISH WATERWAY
                                  Joseph N. Blazevich
                                  Arnold R. Gahler
                                  George J. Vasconcelos
                                  Robert H. Rieck
                                  Stephen V. W. Pope
         \
          ui
          O
U.S. ENVIRONMENTAL PROTECTION AGENCY REGION X
      SURVEILLANCE AND ANALYSIS DIVISION
            LABORATORY BRANCH
  1200 SIXTH AVENUE SEATTLE, WASHINGTON 98101

-------
EPA 910/9-77-039
August, 1977
                    MONITORING OF TRACE CONSTITUENTS
                           DURING PCB RECOVERY
                           DREDGING OPERATIONS

                            DUWAMISH WATERWAY
                                   By
                           Joseph N. Blazevich
                            Arnold R. Gahler
                          George J. Vasconcelos
                             Robert H. Rieck
                           Stephen V. W. Pope
                  U. S.  Environmental  Protection Agency
                   Surveillance and Analysis  Division
                             Laboratory Branch
                1200 Sixth Avenue, Seattle, Washington 98101

-------
                        DISCLAIMER





     This report has been reviewed by Region X, U. S.



Environmental Protection Agency, and is approved for



publication.  Mention of trade names or commercial products



does not constitute endorsement or recommendation for use.

-------
                               ABSTRACT


     This report describes the monitoring program conducted after a spill
of 255 gallons of transformer fluid, Aroclor 1242, occurred in the Duwamish
River in Seattle, Washington.  A detailed evaluation is presented of data
acquired prior to, during, and after recovery operations.  An initial
recovery effort conducted by EPA resulted in a 30 percent removal of the
PCB.  The Department of Defense, acting through the Corps of Engineers,
removed the remaining Aroclor using a Pneuma dredge.  This removal operation
increased the total PCB recovered to approximately 92 percent.

     The second recovery effort was conducted without significant redistri-
bution of toxic materials and bacteria associated with the dredged sediments.
No appreciable amount of PCB returned from the disposal ponds to the river
because of the design of the land disposal area and of the use of a
filtration-adsorption treatment unit.  Water, which drained from the dredged
spoils in the disposal pond, contained some Mn, N-NH3, N-TKN, oil and grease,
and total coliform, but only traces of Cd, Fe, Zn and total P.  Apparently
most of the pollutants and bacteria were associated with or scavenged by
particulate matter and settled in the disposal ponds.  Only small concen-
trations of toxic materials, nutrients, and suspended solids were observed to
be released into the overlying river water during dredging operations.

     The release of pollutants from sediments during dredging could be  only
partially predicted by use of the elutriate test and evaluation of the
interstitial water.  The elutriate test was valid for most metals, nutrients,
and oil and grease.  However, both tests failed to preduct the amount of
PCB released.
                                  m

-------
                        TABLE OF CONTENTS

                                                                    Page
 Abstract                                                             11i

 List  of Figures                                                        v

 List  of Tables                                                        vi

 Part  I.   Introduction                                                  1

             Background                                                 1
             Objective                                                  1
             Scope                                                      3

 Part  II.   Conclusions                                                  5

 Part  III.  Experimental                                                7

              Sampling                                                 7
              Sample Preparation                                      22
              Laboratory Analysis                                     24

 Part  IV.   Results and Discussion                                      27

             Phase I.  Pre-dredge Activities                          27
             Phase II.  Dredge Monitoring Activities                  50
             Phase III.  Post-dredge                                  59

 References                                                            66

Appendices
   A.   Outline of project scope                                       69
   B.   Gas chromatography/mass spectrometry results                   74
   C.   Monitoring study results                                       90
   D.   Results and calculations of predictive test studies           129
   E.   Calculations for estimation of PCB removed by analysis of     142
       disposal  pond spoils
   F.   Hydrolab results                                              147
                             IV

-------
                          LIST OF FIGURES

Figure
                                                                    Page
  1            PCS spill  location                                      2
  2           Station numbers at Slip 1                                3
  3           Pre and post sediment analysis  sampling  stations        10
              (Composite)
  4           Dredge efficiency sediment sampling stations            11
  5           Composite dredge spoils sampling sites for Pond  1       13
  6           Dredge spoil topography pond 1                          14
  7           Overview of disposal  ponds and  treatment               18
              facilities
  8           Ambient water column  sampling area (Slip 1)             19
  9           PCB sediment concentration (Pre-cleanup),               29
              Sept, 18, 1974
 10           PCB sediment concentration, Sept,  25,  1976             31
 11           PCB sediment concentration, Oct. 18, 1974              33
 12           PCB sediment concentration, Nov. 4, 1974               35
 13           PCB sediment concentration in cores, Nov.  4,  1974       36
 14           PCB surface sediment concentration, June 2,  1975        39
 15           PCB sediment concentration (Bottom 1/3 of cores),       41
              Aug. 18, 1975
 16           PCB sediment concentration (Bottom 1/3 cores),          42
              Aug. 18, 1975
 17           PCB sediment concentration, Jan. 16, 1976              45
 18           PCB sediment concentration, Jan. 16, 1976              46
 19           PCB sediment concentration (Post dredge),              61
              May 4, 1976

-------
                            LIST OF TABLES


 Table
 	                                                                 Page
  1             Frequency of river surveys for  PCB  in  Duwamish            9
                sediments

  2             Dredge spoil  pond influent sampling frequency            15

  3             Dredging production report Pneuma North  America          16

  4             Cruise schedule  for monitoring  river water  at            20
                dredge site

  5             Composite sampling scheme  for monitoring river           21
                water  at dredge  site

  6             Summary of sample storage  and preservation               23

  7             Analytical method for monitoring activities              25

  8             Analysis  for  PCB's  in sediments taken  from               30
                Slip 1  (9-20-74)

  9              PCB in  sediments  taken  from Slip 1  (9-25-74)             32

 10              PCB in  sediment  taken from Slip 1 (10-18-74)             34

 11              PCB in  sediment  taken from Slip 1 (11-4-74)              37

 12              PCB in  sediments  at selected stations                    38

 13              PCB in  sediments  taken  from Slip 1  (6-2-75)              40

 14              PCB in  sediment  cores (8-18-75)                          43

 15              PCB in  Slip 1 sediments  (1-16-76)                        47

 16              Predictive test  analysis summary                         48

 17              Comparison of predictive test accuracy                   49

 18              Bacterial  content of post  and pre-dredge sediment        51
                samples taken from  six zonal areas  in Slip 1


19              PCB in sediments  taken during dredging  operations        52

-------
                     LIST OF TABLES (Continued)


Table
                                                                   Page
 20            PCB in effluent from filter system                   56

 21            PCB results for miscellaneous samples                57

 22            Bacterial content of influent into disposal pond 1   60
               and effluent out of disposal pond 2

 2-"            Results of analysis of PCB's in Duwaniish River post  62
               dredge survey (5-4-76)

 24            Results of analysis of pond 1 dredge spoils          64

 25            Dredge spoils collected from disposal pond ^1        65
               approximately two months after dredge operation
                              VI 1

-------
                         ACKNOWLEDGMENTS
     The technical assistance and contributions of the following
individuals and organizations are gratefully acknowledged:  Messrs.
Nathaniel Anthony, Roy L.  Arp, Gary Burns, Phil Davis, Nick Malueg,
Francis Nelson, Leroy Loiselle and Robert Ralston and Mrs. Linda
Montgomery, U. S. Environmental  Protection Agency, Surveillance
and Analysis Division, Seattle,  Washington;  Mr. Ron Hoeppel , U. S.
Corps of Engineers, Waterways Experiment Station, Vicksburg,
Mississippi; Messrs.  Leonard Juhnke and Robert Parker, U. S. Army
Corps of Engineers, Seattle District, Seattle, Washington.  Co-joint
support for this study was made  available through an interagency
agreement between the U.  S. Environmental Protection Agency, the
U. S. Army Materials  Command, and the U. S. Army Corps of Engineers,
Waterways Experiment  Station.  This interagency agreement was
administered by the Seattle District U. S. Army Corps of Engineers.
                            Viii

-------
                         Part I.   INTRODUCTION
(A)   BACKGROUND
          On September 13, 1974, an electric transformer destined for
     arctic service was dropped and broken on the north pier of Slip 1
     of the Duwamish River, Seattle, Washington (Figure 1).   As a
     result, PCS transformer fluid, Aroclor 1242, was discharged onto
     the pier and into the water.   After becoming aware of the type
     and quantity of fluid spilled, EPA acted to determine the extent
     of pollution.   Once determined feasible, clean up of the fluid
     was attempted using several hand dredges (1).

          Results from EPA Region X Laboratory's monitoring of this
     clean up operation indicated only eighty of an estimated 255
     gallons of PCB were recovered and the remaining fluid had begun
     to spread throughout the slip and into the river channel (2).
     Recognizing the seriousness of this problem, DOD and the Army
     Corps of Engineers conducted a second recovery operation to
     remove the remaining PCB using a Pneuma Model  600 dredge.

          The Corps of Engineers piped the contaminated sediments to
     a disposal site prepared on land 2,000 feet north of the slip.
     All dredge spoil  water was treated with Nalco  #7134 flocculent,
     passed through two disposal ponds and filtered through both a
     particle filter containing Filterite 7?264MSO and EPA's activated
     carbon treatment unit.
(B)  OBJECTIVE

          The primary purpose of the Region X Laboratory's involvement
     in the second clean up was to assist the Army Corps of Engineers'
     Seattle district by monitoring the Corps recovery of the remaining
     PCB.  A monitoring scheme was designed to evaluate the hydraulic
     dredging of PCB polluted sediments in Slip 1  to determine the
     amount of PCB removed, the extent of PCB translocation and the
     amount of PCB remaining on the river bottom after dredging.
     Also, an attempt was made to evaluate the usefulness of predictive
     methods such as the "Standard Elutriate Test" and "Interstitial
     Water Evaluation" as important procedures for determining the impact
     of a dredging operation on dredge and disposal site water quality.

-------
        ELLIOTT BAY

                                         INDUSTRIAL
                                           ERCIAL AREA
                               DREDGE SPOILS
                              DISPOSAL  PONDS
                                           GEORGETOWN
                                                Mil
                                           1st Ave. Bridge
            P C B  SPILL LOCATION

SEPT. 13, 1974                                 FIGURE 1

-------
         Both dredge  and  disposal  sites were monitored  extensively
    during  the  dredge operation  for  PCB's, metals,  nutrients  and
    other potentially harmful materials,  including  microorganisms
    of public health  significance.   Also, a pre-dredge  and  post-
    dredge  pollutant  monitoring  program with emphasis on  predictive
    testing and subsequent  evaluation was carried out.

         EPA Region X Laboratory's objectives  for monitoring  the Corps
    PCB  clean up operation  at Slip 1 were:

          (1) Map and assess the amount of PCB on the river bottom
              prior to  the  clean-up  effort.

          (2) Estimate  the  amount of PCB  removed from the river bottom
              as a result of the Corps dredging operation.

          (3) Estimate  the  extent of PCB  pollution  remaining  on the
              river bottom  after dredging.

          (4) Determine the extent of PCB translocation resulting  from
              the recovery  operation.

          (5) Determine amounts  of deleterious materials  released  into
              the water column at the dredge site as a  result of the
              clean-up  operation.

          (6) Predict and compare quantities of pollutants  returning  to
              the river from dredge  spoil disposal  ponds.
(C)   SCOPE
     Phase I:   Pre-Dredge  Monitoring

          The  objectives necessitated  a  comprehensive monitoring  program
     that allowed the observer  to  detect environmental  disturbances
     directly  attributable to the  dredging  operation.   A  pre-dredge
     evaluation of Slip  1  sediments was  made  to  determine PCB,  trace
     metals,  nutrients,  oil  and grease,  water quality,  and microbiological
     parameters.   Determination of PCB in surface  sediments was performed
     to map the extent of  contamination  prior to the Corps  dredging
     operation.  Data obtained  from PCB  and other  measurements  afforded
     an opportunity to assess the  effects of  sediment disturbances
     during a  hydraulic  dredging operation.   Predictive tests,  "Standard
     Elutriate Test"  and  "Interstitial Water  Evaluation", were  conducted
     to determine the potential  release  of  pollutants to  the water column.

          A river water  evaluation program  was initiated  by monitoring
     background water at the dredge site for  future reference to  any
     plume created by the  dredging, operation.   Composite  samples  of

-------
suspended particulate matter (SPM) and whole water were collected
at two depths, surface and eight meters,  over desired time intervals
and analyzed for PCB's.  Whole water composite samples were monitored
for trace metals, nutrients, oil and grease and other water quality
parameters.  Collection of samples from surface and eight meters was
desirable since the Duwamish is a salt wedge estuary possessing both
fresh surface and deep salt water layers  usually separated by a
strong pycnocline.

Phase II:  Dredge Monitoring

     Disposal pond influent and effluent  were evaluated by analyzing
several  whole water composites while the  dredging operation was in
progress.  At the same time, sediments from dredged area were analyzed
for Aroclor 1242 to determine the success of the PCB removal  operation.
The effect of dredging on river water near the dredge site was estab-
lished by monitoring SPM and whole water  samples.

Phase III:  Post-Dredge Monitoring

     A post-dredge survey of remaining Slip 1  sediments, consisting
of analysis of bulk sediments and interstitial  water, was necessary
to determine if pollutants such as PCB remained on the river bottom
in substantial  quantities and if translocation of Aroclor 1242
occurred during the dredging operation.   Also, an attempt was made
to determine if water quality comparable  to pre-dredge conditions
existed  at Slip 1  after completion of dredging activities and to
establish the success of PCB removal  from Slip 1.

-------
                          Part II.  CONCLUSIONS


     The recovery effort resulted in the removal of most of the spilled
Aroclor from Slip 1 without evidence of significant PCB translocation.
Two independent methods were used to calculate the amount of PCB recovered.
The first utilized an estimate of the amount of PCB contaminated dredged
materials removed from designated areas within the spill site.  The second
method was based on the concentration of PCB found in the dredged materials
actually deposited in the disposal pond.  Estimates of the amount of PCB
recovered using these methods are 220 and 250 gallons, respectively.  The
average value of PCB removed 235 gallons, represents a 92% recovery.  It
follows that approximately 20 of the 255 gallons of PCB spilled are assumed
to be on the river bottom or unaccounted for at this time.  Substantially
reduced levels of PCB were detected in the impact area and only trace amounts
of the substance were found to be present in the remaining portion of the
slip.  The river channel remained free of the spilled Aroclor indicating
that less than a detectable amount of the pollutant was transported out of
the spill site during the final clean-up operation.

     In comparison, analysis of survey data obtained during the first
three month period after the spill indicates that some translocation
of Aroclor 1242 into the river channel occurred during the first clean-up
operation.  Apparently, divers with hand held dredges disturbed the
pollutant, allowing transport of the material to occur.  This situation
was further aggravated by natural dispersal forces acting on the trans-
former oil which laid unprotected on the river bottom.

     Subsequent surveys during the months that followed demonstrated
that normal river sedimentation tended to cover the contaminated sediments
and that the spread of PCB occurred mainly toward the back .portion of the
slip.  Also, the force of a "20 year flood" experienced in the Duwamish
Estuary during the winter of 1976 either diluted or scoured the contaminated
river channel sediments such that no detectable amount of PCB remained in
the channel.  However, no significant changes attributable to the flood were
noted in sediment concentrations within the slip proper.  The continual
migration of Aroclor 1242 towards the back of the slip appears to have been
influenced by docking and embarking activities of ships in the area and
other factors such as tidal action.

     A slow but persistent movement of transformer fluid could have
eventually contaminated the entire slip and polluted much of the Duwamish
River if the spilled PCB was allowed to remain on the slip bottom.  Successful
completion of the removal operation terminated that migration and dramatically
lessened possible serious long term effects of the spill.

-------
      Levels  of  several  pollutants in dredge spoil return water and dredge
 site  water  remained  near  background during the dredging operation.  Although
 substantial  quantities  of PCB, As, Cd, Cu, Fe, Mn3 Hg, Ni, Zn, N-NHs,
 N-TKN and oil and  grease  were detected in the dredge spoils entering the
 disposal area,  only  Mn, N-NHs, N-TKN and oil and grease were observed in
 high  concentrations  along with slightly elevated values of Cd, Fe, Zn
 and Total P  in  effluent returning to the river.  Apparently, most pollutants
 were  associated with or scavenged by particulate matter and settled, with
 the aid  of  a flocculent,  to the bottom of the disposal ponds.  Comparison
 of these observations with predictive tests used to estimate the amount of
 a  pollutant  released during dredging is good.  Considering the degree of
 accuracy possible  for this type of estimate, the "Standard Elutriate Test"
 appears  to  be valid  for most metals, nutrients and oil and grease.  However,
 "interstitial water  evaluation" of sediments employed in this study met
 with  only limited  success.  Both tests failed to accurately predict the
 amount of PCB released.

      As our  results  indicate, a large number of bacteria of public health
 significance can be  removed from both sediments and interstitial waters
 by a  properly monitored hydraulic dredging operation.  In most instances,
 a  significant reduction was obtained in total coliform (TC), fecal
 coliform (FC),  and clostridium perfringen (C. perfringens) populations
 from  all sampling  locations surrounding the impacted area.  The removal
 of C_.  perfringens was of  particular importance because of its known patho-
 genicity and close association with organic material originating from human
 fecal  waste.  The removal  of sediment bound bacteria by passage through
 disposal  ponds  1 and 2 was effective for the elimination of FC, fecal
 streptococci (FS) and C_.  perfringens but not TC and organisms enumerated
 by  the 20° C plate count.   The reason for this disparity is still unclear,
 but may relate  to the lack of aggregate formation or adsorption to sediment
 particulates.   Nevertheless,  it still  appears that large portions of the
 enteric bacterial population  can be effectively removed from bottom sediments
 and eliminated  by proper  land disposal.   The fate or survivance of these
 bacteria  on  land, however, is quite variable and dependent upon a multitude
of environmental and nutritional  factors.

-------
                       Part III.   EXPERIMENTAL
(A)   SAMPLING
     (1)   Slip 1  Sediments

               River bottom sediments were sampled over a two and one half
          mile reach of the Duwamish River shown in Figure 1.  The sampling
          area extended north from the First Avenue Street Bridge to the
          south portion of the West Waterway.   Sample station locations
          in and  around Slip 1 (shown in Figure 2) included four transects
          centered at station 225 (location of the spill) proceeding out to
          stations 229, 230, 209, 220 and additional  stations which were
          used to provide more complete coverage of the area.  All  other
          stations were taken at mid-channel with sample intervals ranging
          from 250 feet within 2,000 feet of the spill  site to 1,000 feet
          beyond  this point.  Surveys of river bottom sediments were made
          over a  two year period (see Table 1).  Surface sediment samples
          were taken using a Van Veen sampler.   The top five centimeter
          section of the sample was carefully removed from the sampler,
          placed  in a pretreated 8 oz. jar, capped with a teflon-lined lid
          and stored at 4° C until analysis was performed.   This method was
          used to detect translocation of PCB associated with movement of
          fines or flocculent sediment.  Core samples were also taken on at
          least two occasions using a Phleger coring device in order to
          define  the extent of vertical migration of the pollutant.

               Originally, composite samples were obtained from six areas
          in Slip 1 thought to be dissimilar in chemical composition using
          a Van Veen sampler and a Phleger coring device.  Sample stations
          used to make up the composites are shown in Figure 3.  The samples
          were mixed, capped, held at 4° C and taken to the laboratory for
          evaluation using the Standard Elutriate Test, interstitial water
          evaluation and bulk sediment analysis.  Since areas three and four
          were later found to be similar in chemical  composition, they
          were combined.

               Several sets of Slip 1 sediments were analyzed during the
          second  removal effort to determine the degree of success of the
          clean up operation.  Dredged areas,  thought to be free of spilled
          Aroclor, were sampled using a Van Veen sampler while the removal
          effort  was in progress.  A representative portion of each grab
          sample  was removed and analysis was  initiated within one hour
          after collection.  Sampling points used to check dredging efficiency
          are shown in Figure 4.

-------
                   WATER
                   DEPTH
                    26 ft.
STATION NUMBERS  AT SLIP 1
                                       FIGURE 2

-------
Table 1.  FREQUENCY OF RIVER SURVEYS FOR PCB IN DUWAMISH SEDIMENTS
Extent
Survey Number of Survey
1
2
3
4
5
6
7
8
9
10
Full
Partial
Partial
Full
Partial
Full
Partial
Full
Partial
Full
Sept.
Sept.
Oct.
Nov.
Feb.
June
Aug.
Jan.
Feb.
May 3
Date
18
25
18,
4,
20,
2-4
18,
16,
5
5
1
Elapsed Time From Date
of Spill Sept. 13, 1974
1974
1974
974
1974
1
,
1
1
23-25
, 4
&
975
1975
975
976
, 1976
11, 1976
5
12
35
52
159
263
338
489
527
605
days
days
days
days
days
days
days
days
days
days

-------
                                                ^
                                      COMPOSITE
                                      SAMPLING STATIONS
                                      MICROBIOLOGICAL

                                      SAMPLING STATIONS
PRE AND POST SEDIMENT ANALYSIS

  SAMPLING STATIONS (COMPOSITE)
                                                   FIGURE 3

-------
                        WATER
                        DEPTH
                         26 ft.
                                EXTENSIVE DREDGING
                                    SEDIMENT
                                    SAMPLING STATIONS
                                    DURING DREDGE
                                    OPERATIONS
                                      AREA DREDGED
                                      Scale in Feet
DREDGE  EFFICIENCY SEDIMENT
         SAMPLING  STATIONS
                                                   FIGURE4

-------
(2)   Disposal  Pond  Sediments

          The  Corps  constructed  two  large  dredge  spoil  disposal  ponds
     based on  the estimated amount of  PCB  contaminated  sediments to
     be  removed  from Slip  1.  Only the  first of the  two ponds  received
     any appreciable amount of solids  which was estimated  to be  7,000
     yd3 (L. Juhnke, Personal Communication, 1977).   The pond  was divided
     into three  areas  for  the purpose  of sampling  and sampled  on June 3,
     1976 after  most of  the water had  been removed.   Sampling  points used
     to  obtain composites  of disposal  pond spoils  are shown in Figure 5.
     A vertical  profile  of the diagonal transect  of  the disposal  pond is
     shown in  Figure 6.  The first area (Al),  see  Figure 5, located at
     the mouth of the  input pipe, consisted of sand  and gravel on the
     surface with a  gradual increase in clay-like  material with  increasing
     depth.  This material was difficult to penetrate with available
     coring devices  so holes up  to three feet  deep were dug in order to
     obtain samples  for  a  composite.   The  second  sample area (A2), located
     between the first and the water line, consisted  mainly of mud which
     ranged from firm to very soft as  one moved out  over the transect
     lines.  This material was easily  sampled  using  a six  foot aluminum
     coring tube.   The third area (A3) was under water.  Composite samples
     were obtained  by boat using a six  foot aluminum  coring tube and a
     hand-held Van  Veen  grab sampler.

          Nine composite samples were  obtained from  the pond.  Although
     only one  surface composite  was made for area  Al, three surface
     and three total core  composites (one  pair per transect shown in
     Figure 5) were  taken  for Area A2.  Also,  one  surface  and  one total
     core composite  were obtained from  the area AS.

(3)   Influents to Disposal Ponds

          Collection of  composite disposal pond influents was  accomplished
     in  the following  manner.  A sample taken  from the  influent  stream
     using a pretreated  three liter bucket was distributed into  containers
     specially treated for holding metal, nutrient, oil  and grease and
     chlorinated hydrocarbons samples  starting with that designated for
     metals.   A  second sample was taken and distributed beginning at the
     nutrient  container.   The process was repeated, each time  advancing
     the start to the  next container,  until the vessels  were filled to
     the desired volume.   A sampling period of fifteen  to  twenty five
     minutes was used  to insure a representative sample of the dredging
     activities  for  the  time of sampling.   The composites were sealed
     and returned to the laboratory for immediate  analysis.

          Influent sampling dates along with areas in which the  dredge
     was  working at  time of sampling are shown in  Table 2  (See Figure 3).
     Originally, the influent sampling scheme  included  taking  pairs of
     samples at  the  start, in the middle and toward the end of the dredge
     activities.   Unfortunately, several dredge equipment failures made
     it  impossible to  predict when influent sampling  could be  carried out.
     The  "Dredging Production Report" shown in Table  3  illustrates the
     problem.   Therefore,  samplings were spaced randomly.
                                12

-------
FIGURE 5
            INLET PIPE
                                               0
                                               0
                                               •
                                               D
                                               O
                                                 \
SAMPLE POINTS
FOR EACH
COMPOSITE
SAMPLE
                                     )  C
                                    EXIT WEIR
                    WATER LINE
                    AREA BOUNDARY
                 COMPOSITE DREDGE SPOILS
                SAMPLING SITES FOR POND 1

-------
FIGURE  6
  1ST
  10- •
       DIAGONAL TRANSECT
ACTUAL HEIGHT AT END OF DREDGE
HEIGHT USED IN VOLUME CALCULATIONS
MEASURED HEIGHT (1-17-77)
                             TOP VIEW
          DREDGE SPOIL  TOPOGRAPHY POND 1

-------
Table 2.  DREDGE SPOIL POND INFLUENT SAMPLING  FREQUENCY
Date
March 16, 1976
March 19, 1976
March 22, 1976
March 22, 1976
March 23, 1976
Dredge Working in Area
      5 and 6
      3 and 4
         3
      1  and 2
      1  (near spill  site)
                         15

-------
           TABLE 3.   DREDGING  PRODUCTION  REPORT  PNEUMA  NORTH AMERICA
Date
Working Hours
Dredging Hours
Delays
Dredging
March 4, 1976
March 53 1976
March 6, 1976
March 8, 1976
March 9, 1976
March 10, 1976
March 11 , 1976
March 12, 1976
March 13, 1976
March 15, 1976
March 16, 1976
March 17, 1976
March 18, 1976
March 19, 1976
March 20, 1976
March 21 , 1976
March 22, 1976
March 23, 1976
March 24, 1976
March 25, 1976
March 26, 1976
March 27, 1976
March 29, 1976
March 30, 1976

9-50/60
8-15/60
10
10
10-40/60
10-30/60
10
10
10
10-30/60
10
10
10
10-30/60
5
5
10
10
10
9
9
10
10
5 (up to demobil-
ization)
	
4-5/60
3-5/60
4-15/60
3-24/60
0
3-12/60
5-53/60
3-12/60
2-4/60
4-23/60
0
37/60
6-23/60
0
3-6/60
5-15/60
6-42/60
3-16/60
0
7-2/60
5-11/60
6-11/60
3-56/60

Total working hours 223%
Total dredging
Total delays
hours 81-1/5 = 36%
142-1/20
actual dredging


4-10/60
6-55/60
5-45/60
7-16/60
10-30/60
6-48/60
4-7/60
6-48/60
8-26/60
5-37/60
10
9-23/60
4-17/60
5
1-54/60
4-45/60
3-18/60
6-44/60
9
1-58/60
4-49/60
3-49/60
1-4/60
Test Water
49%
31%
42%
31%
0%
32%
59%
32%
19%
43%
0%
6%
62%
0%
62%
52%
67%
32%
0%
78%
51%
61%
78%
                                      16

-------
(4)   Effluents from Dredge Disposal  Ponds

          Collection of disposal  pond effluents and filtered waters
     returning to the Duwamish River were made with respect to time
     and volume.   Chlorinated hydrocarbon and oil  and grease samples
     were composited in pretreated two gallon glass jars.   Samples
     used for all other parameters were collected  using an ISCO model
     1392 auto sampler.  Effluent samples were taken only  when filter
     truck pumps  were returning disposal  pond water to the river.
     Due to the lack of continuous dredging activity, water from the
     first of two disposal ponds  did not come over the weir until
     March 12, 1976, eight days after dredging was initiated.   Both
     influent and effluent flow were discontinuous and erratic.

          An overview of the disposal site is shown in Figure  7.
     This includes placement of the filter truck,  a small  holding
     pond located between pond 2  and the large EPA carbon  filter
     truck along  with influent and effluent sampling points.

(5)   River Water

          Standard hydrographic samples were collected and analyzed
     for salinity and dissolved oxygen.  Temperature was noted.
     Nutrient, sulfide, metal and chlorinated hydrocarbon  samples
     were collected by University of Washington personnel  under EPA
     contracts WY-6-00-0451-J and 68-01-3369.  Sample collection and
     handling procedures are outlined in the final  report  of the
     contract (3).(See Figure 8 and Tables 4 and 5).

(6)   Hydrography

          Hydrographic parameters (conductivity and dissolved  oxygen)
     along with pH of pond 2 effluents were monitored continuously
     using a Model  6 Hydrolab Surveyor equipped with a continuous
     recorder.

(7)   Microbiological

          Dredge  sediment samples from Slip 1 were withdrawn from  each
     of the six stations with the aid of a Van Veen Sampler.   Once on
     the deck of  the boat, a small portion (100-200 g) was transferred
     to a sterile 8 02. plastic container using sterile metal  spoons.
     All samples  were immediately placed in an ice chest and transported
     to the laboratory for processing within 2-3 hours.

          Samples of dredge spoils (water and/or sediment  mixed) were
     collected during dredging from two locations:   (1)  the influent
     pipe to disposal pond number one (outlet pipe from dredge)  and
     (2)  the effluent pipe from  disposal pond number two.

          Samples of post-dredge  sediments from disposal pond  number
     one were obtained from composites of whole core and surface grab
     materials.   In each case, a  100-200 g.  portion of the composite
                              17

-------
FIGURE 7
           1. INFLUENT PIPE
           2. INFLUENT SAMPLE POINT
           3. HOLDING POND 1
           4. OVERFLOW WEIR
             POND 1 EFFLUENT SAMPLE POINT
           5. HOLDING POND 2
           6. POND 2 EFFLUENT SAMPLE POINT
             (AT PUMP INTAKE)
           7. COARSE PARTICLE FILTER WITH PUMP
           8. LINED HOLDING POND 3
           9. EPA FILTER TRUCK
          10. FILTER EFFLUENT SAMPLE POINT
           11. RETURN TO RIVER
c
           OVERVIEW  OF  DISPOSAL  PONDS
              AND TREATMENT FACILITIES

-------
                          WATER

                          DEPTH

                          26 ft.
                           INITIAL SPILL AREA
AMBIENT  WATER COLUMN  SAMPLING


                  AREA (SLIP 1)
                                                FIGURE 8

-------
    TABLE 4.   CRUISE  SCHEDULE  FOR MONITORING RIVER WATER AT DREDGE SITE
Cruise No.

   1

   2

   3

   4

   5

   6

   7
      Date

February 25, 1976

March 6, 1976

March 8, 1976

March 18, 1976

March 22, 1976

March 23, 1976

April 20, 1976
Time of
Ebb Tide

0405 - 0941

0736 - 1427

0849 - 1610

0551   1229

0859   1610

1009 - 1719

0832 - 1533
Sampling
Time Interval

0507 - 1003

0815   1453

0901 - 1517

0835 - 1343

0934 - 1631

1014 - 1733

0904   1440
                                  20

-------
Table 5.  COMPOSITE SAMPLING SCHEME FOR MONITORING RIVER WATER AT DREDGE SITE

                                                            Reference
  Hr. Interval of Ebb            Dredge Site Station*       Station £
  at Which Sub Sample
  was Taken                  0-1 1-2 2-3   3-4 4-5 5-6        6-7

  Surface (Number
  of Composites
  per Cruise)                     1             1              1

  Deep  (Number of
  Composites per
  Cruise)                         2             2              1
  *  Dredge site samples were taken every hour to generate two 3-hour composites

  £  Located at 2.99 miles from mouth of Duwamish River.
                                     21

-------
          was  placed  in  a  sterile  8  oz.  container  and  immediately  trans-
          ported  to the  laboratory for analysis.


(B)   SAMPLE  PREPARATION

          Samples  were received  from the field  and held  at  4   C.   Sample
     preparation  included  separation and stabilization steps  when  necessary.
     An  outline of containers  and  preservatives  used by  sample type is
     found in  Table 6.

     (1)  River Bottom Sediments

              Samples of  river  bottom sediments collected  for the purpose
          of detecting the translocation of  PCB's  from the  Slip 1  spill
          site into the  Duwamish River were  homogenized  before analysis
          was  conducted.   No  further preparation was made.

     (2)  Slip 1  Sediments and Interstitial  Hater

               Composite samples of  five areas  within  Slip  1  were  homogenized
          separately  before analysis.  A portion of each well  mixed sediment
          was  set aside  for bulk analysis and another  portion  was  centrifuged
          using a Sorvall  RC2-B  high speed refrigerated  centrifuge equipped
          with a  GSA  rotor operating at  12,500  RPM and 4° C for twenty
          minutes. Stainless  steel  or polycarbonate centrifuge tubes were
          employed for preparation of interstitial  water samples for organic
          chemical analyses and  all  other parameters,  respectively.  Inter-
          stitial  water  destined for organic analyses was decanted into glass
          jars, stored at  4°  C and analyzed  within 24  hours.   The  remaining
          solid was also stored  at 4° C  in a pretreated  glass  jar  until
          analysis was performed.  Interstitial  water  destined for other
          analyses (e.g.  metals, nutrients,  etc.)  was  filtered through a
          0.45 micron filter,  preserved  and  stored at  4° C  in  plastic
          containers. A portion of  the  interstitial water  was left unpreserved
          and  immediate  analysis of  some parameters (e.g. N02-) was performed.

     (3)  Standard Elutriate  Test

              Portions  of the same  composite samples  used  for interstitial
          water and bulk sediment  analyses were  used for the  standard
          elutriate test.   The test  was  performed  according to the procedures
          outlined by the  U.  S.  Army Corps of Engineers  (4, 5, 6 and 7),
          except  centrifugates used  for  determination  of organic parameters
          were not filtered.   The  centrifugates  or filtrates  obtained from
          this procedure were  stabilized and/or  held at  4°  C  until analysis
          was  performed.
                                  22

-------
        Table 6.  SUMMARY OF SAMPLE STORAGE AND PRESERVATION
Analysis
            Sampling  Amount
Container   Device    (Total)
              Storage
Preservative  Condition
(A)
















(B)


Water Samples
Oil & Grease Glass

PCB Glass

N-TKN Plastic
N-NH3
P-Total
N-N03
o-p Plastic
N-N02
Sulfide
Turbidity
Metals Plastic



Sediment Samples
All parameters Glass


SS* or
Glass
SS or
Glass
Plastic



Plastic



Plastic




SS


2 gal.

2 gal.

1 qt.



1 qt.



1 gal.




8 oz. to
3 gallons

1 ml. H2S04
per liter
None

1 ml . cone.
H2S04 per
liter

None



25 ml . re-
di stilled
NH03 per
liter

None


4° C

4° C

4° C



4° C



RT




4° C

(C)  Hydrolab on Ship to Measure Conductivity, P.O.,  Temperature,  and pH
*  SS - Stainless steel
                                 23

-------
     (4)  Disposal  Pond Sediments

               Composite pond sediments  were mixed thoroughly, subsampled
          and stored at 4° C.  Analysis  of the composites was performed
          within two weeks of sample  collection.

     (5)  DisposaJ  Porid Jnfluent and  Effluent

               All  samples were resuspended prior to analysis.  A portion
          of the mixture was  analyzed immediately for some parameters
          (e.g.  settleable solids,  etc.)    Other  portions were centri fugecl,
          decanted, filtered  through  a 0.45 micron filter and preserved
          as described above  (See  "Slip  1  Sediments and Interstitial  Water").
          Centrifugate destined for analysis of organic parameters was not
          filtered.  Centrifuged influent  solids  were stored at 4° C  in
          pre-treated containers.   Since  little solid was obtained from
          routine centrifugation of effluents, a  continuous high speed
          Sharpies  centrifuge was  used to  collect effluent solids. Approx-
          imately 500 liters  of effluent  was processed at the disposal  site
          over a six day period.  Rate of  feed of pond effluent to the
          centrifuge was adjusted  so  that  turbidity of the centrifugate
          did not exceed 4 JTU. The  solids were  stored at 4° C until
          analyses  were performed.

     (6)  Rj ver Water

               Samples of whole river water and SPM destined for PCB  analysis
          were stored at 4° C until analysis was  performed (3).   Portions of
          whole water samples used  for all  other  determinations were  preserved
          when necessary and  stored at 4°  C.   Determination of some parameters
          subject to rapid degradation was  conducted upon receipt of  samples.

     (7)  Microbiological

               All  sediment and dredge spoil  materials were processed in the
          same manner following recommended procedures (8, 9).  Samples were
          weighed to nearest  gram and aseptically transferred to sterile
          blender jars to  which an  equal amount,  by weight, of 0.1% sterile
          peptone dilution water was  added.   The  mixture was then blended at
          ca_.  14,000 rpm for  60-120 seconds.   Within 2 minutes of the blending
          period appropriate  volumes  (or dilutants) were transferred  with
          pipets to the appropriate culture media.


(C)   LABORATORY  ANALYSIS

     (1)   ChernicaJ

              A variety of chemical  and physical  parameters were measured  in
          water  and sediment  samples.  Analyses were performed according to
          methods found in Table 7
                                 24

-------
         Table 7.  ANALYTICAL METHODS FOR MONITORING  ACTIVITIES


Parameter                 Sample Type                   References

(A)  Metals (Total)

     As, Cd, Cr, Cu,      FW, SW                        10,  11
     Fe, Pb, Mn, Ni,
     Zn

                          Sd                            11,  12

     Hg                   FW, SW, Sd                    10,  11


(B)  Nutrients

     N-NH3, N02 , N03 ,    FW, SW                        10
     Total  P, Dissolved
     Ortho P


(C)  Organochlorine Compounds

     PCB                  FW, SW, Sd, Fh                 13,  14


(D)  Miscellaneous

     TOC, COD, Turbidity,  FW, SW, Sd                    10
     N-Kjeldahl, Total
     Volatile Solids,
     Total  Solids

     Settleable Solids     FW, SW                        15A

     Total  Sulfide        FW, SW                        15A

                          Sd                            15B

     Salinity             SW
FW  Freshwater
SW  Seawater
Sd  Sediment
Fh  Fish
                                 25

-------
M icrobiological

     Total coliform (TC), fecal coliform  (FC) and fecal  strepto-
coccus (F8) determinations were performed according to Standard
Methods (9) using the 5 tube, multi-dilution MPN procedure.
Bacteriological analysis also included the anaerobic enumeration
of Cl osjridjum perfrjngjjnjs (welchii) on sul f i te-polymyxin-
sulfadiazine fSPSy^agar  "All confirmatory steps employed for
C. perfringens followed those outlined in the Ba_cterj_ological
Anajytica] ~MarujaJ (16) published by the Food and Drug Administration
In addition to an anaerobic determination, a 5 day, 20°  C aerobic
plate count was performed on all samples using tryptone  glucose
yeast (TGY) agar

-------
                     Part IV.  RESULTS AND DISCUSSION


     An extensive monitoring effort was initiated only days after PCB's
were accidentally spilled into the Duwamish River at Slip 1.  Significant
amounts of PCB's remained in the sediment after the original clean-up
and a dredging operation was planned and conducted by the Corps of
Engineers.  Since appreciable time elapsed between the initial clean-up
and final removal, extensive monitoring was required to identify movement
of the toxic material.  The results of the entire monitoring program is
described best in terms of three phases:  pre-dredge activities, monitoring
during dredging, and post-dredge evaluation.


(A)  PHASE I.  PRE-DREDGE ACTIVITIES

     (1)  Identification of Pollutant

               Questions regarding the type of Aroclor spill at Slip 1
          were raised when laboratory results conflicted with transformer
          label information.  As a consequence, gas chromatography/mass
          spectrometry (GC/MS) analysis was performed on extracts of
          bottom sediments saturated with the spilled fluid, recovered
          sludge and a standard of Aroclor 1242.  Results of GC/MS analysis
          are presented in Appendix B.  Figures B-l, B-2, B-3 and B-4 show
          constructed gas chromatograms (RGC) of the three samples.   Limited
          mass chromatograms (Figures B-5, B-6, B-7 and B-8) with M+/e=256-261
          show patterns indicative of Aroclor 1242 PCB isomers containing 3
          chlorine atoms.  Similarly, limited mass chromatograms (Figures
          B-9, B-10, B-ll and B-12) using M+/e=290-300 give patterns expected
          for Aroclor 1242 PCB isomers with 4 chlorine atoms.  Corresponding
          mass spectra for each sample type are shown in Figures B-l3,  B-l4
          and B-15.  The spectra are identical.  Analysis of the spectra
          show molecular ion clusters typical of chlorinated biphenyls  with
          3 chlorine atoms along with strong P-70 cluster beginning at
          M+/e=186.  This is indicative of the loss of Cl2-  Comparison of
          above RGC's and spectra of sediment and sludge sample extracts with
          those of Aroclor 1242 PCB standard shows Aroclor 1242 PCB to be
          present in both.

               Analysis by gas chromatography/electron capture (GC/EC)  gave
          similar results.  Chromatograms of the transformer fluid, extracts
          of bottom sediments, recovered sludge and of standard Aroclor 1242
          were identical.  The spilled fluid was identified as Aroclor 1242
          by both GC/MS and GC/EC.

     (2)  Translocation of PCB's

               An initial survey of PCB burden in sediments in and around
          Slip 1 was conducted within five days after the spill occurred
          on September 13, 1974.  Analysis of survey results indicated two
          areas of high PCB concentration, one at the impact site and another
                                  27

-------
approximately 300 feet to the west (Table 8, Figure 9).  Sub-
sequent surveys of September 25, 1974 and October 18, 1974,
conducted during initial  clean up efforts, indicated some
movement of PCB's in the  slip and river channel (See Tables
9 and 10, Figures 10 and  11).  This was in agreement with
observations of divers, who noted movement of PCB pools on the
river bottom.

     A discrepancy between initially reported low PCB levels
at the spill site and higher values of later surveys was noted.
This anomaly can be accounted for by considering the manner in
which the samples were taken.  The initial survey was conducted
without knowledge of the  exact point of transformer impact.  As
a consequence, a fringe area fifty feet west of the spill site
was sampled but later surveys produced samples from the center of
the impact site.  The result was similar sediment samples with
divergent PCB concentrations.  Another survey designed to detect
translocation of PCB into the river was conducted after initial
clean up operations were  completed (See Table II and Figures 12
and 13).  Movement of PCB contaminated sediment was found to have
occurred.  Analysis of results indicate some of the material
made its way into the river channel during the first clean up
operation.

     Three surveys of PCB burden in the river bottom sediment were
made during the time period after the first clean up attempt to the
start of the second.  On  February 20, 1975, a limited survey of
the spill site, consisting of stations 225 and 231, was performed
to determine if PCB had in fact migrated out of the slip.  Comparison
of this data with that obtained from previous surveys shows little
change in sediment PCB burden since termination of initial clean up
operations on October 31, 1974 (See Table 12).  Translocation of
PCB's on the river bottom, first noted on November 4, 1974, was
studied again in 1975.  Analysis of surface sediment (See Tables
13 and 14, Figures 14, 15, and 16) indicates some Aroclor 1242
movement into the river and upstream to a point just south of Slip
1 between 81 + 00 feet and 91 + 00 feet.   Also, it is evident
that Aroclor 1242 had migrated towards the back of the Slip and
that observed surface values of PCB in the sediments were much
lower than previously reported.   Since only the top few centimeters
of sediment were analyzed, it was possible to detect not only
the translocation of PCB  but also dilution of PCB "hot spots"
by sedimentation from spring run off.  Analysis of the bottom
one third portion of core samples at the spill site show elevated
PCB levels.   It appears that two phenomena were occurring.
First,  normal sedimentation, 15 cm/yr. at the First Avenue
Bridge  (17), was covering up contaminated sediments.  Second,
some force was present to account for mixing and spreading
the contaminated sediments throughout the slip.  It is known from
observation  that the Bureau of Indian Affairs (BIA) ship Northstar
                       28

-------
                                 WATER
                                 DEPTH
                                            VALUES IN PARTS
                                            PER MILLION
                                          (2) CONTOUR LINES =
                                            25PPM (APPROXIMATE)
                                          (3) PCB 1242

                                               Scale in Feet
     PCB   SEDIMENT  CONCENTRATION
                      (PRE CLEANUP)
SEPT. 18, 1974
FIGURE 9

-------
Table 8.   ANALYSIS FOR PCB'S IN SEDIMENTS TAKEN FROM SLIP 1  (9-20-74)
Station
Number
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
1248/54
0.192
-
0.34
0.43
0.39
0.09
-
4.25
0.11
0.15
0.35
-
-
0.40

0.28
-
-

0.27
1242
0.33
-
0.24
0.23
0.35
0.06
0.50*
1.9
0.11
0.06
0.30
-
-
0.20
0.50*
0.11
0.20*
6.3*
87*
0.12
Station
Number 1248/54 1242
221 0.30 0.20
222 0.18 0.14
223 - 5.0*
224 - 5.0*
225 - 190*
226 - 2.0*
227 - 0.80*
228 - 0.30*
229 - 0.40*











 *   PCB  concentrations  based only on Aroclor  1242
 =£  Concentrations  expressed in microgram/gram, wet weight  (ppm)
                                 30

-------
                                 (I) VALUES IN PARTS
                                    PER MILLION
P C B  SEDIMENT CONCENTRATION
SEPT,
     1974
FIGURE 10

-------
Table 9.   PCB IN SEDIMENTS TAKEN FROM SLIP 1  (9-25-74)*


    Station
    Number                1248/54           1242

     209                     0.56             1.3

     216                     0.61             1.07

     217                     0.25             0.25

     219                     0.27             0.23

     222                     0.69             0.76

     225                      -           30,900

     230                      -               15

     231                      -              140


 *  Concentrations expressed in microgram/gram,  wet weight (ppm)
                         32

-------
                               WATER
                               DEPTH
                               26 ft.
                                       (I) VALUES IN PARTS

                                          PER MILLION
     P C B  SEDIMENT  CONCENTRATION
OCT. 18, 1974
FIGURE 11

-------
Table 10.   PCB IN SEDIMENT TAKEN FROM SLIP 1  (10-18-74)*


     Station
     Number                1248/54            1242

      218                     -               64

      219                     -                2.0

      222                     -                3.0

      223                                      0.8

      224                     -               25

      225                     -            2,000

      231                      -               50


*  Concentrations expressed in microgram/gram,  wet weight (ppm)
                            34

-------
                                   WATER
                                   DEPTH
                                            (I) VALUES">m, PARTS
                                               PER MILLIO
                                            (2)  SHADED BOUNDAR
                                               OF HIGHEST
                                               CONCENTRATIONS
                                               RECORDED THIS DATE
                                               (PCB 1242)
                                                  Scale in Feet
      PCB   SEDIMENT CONCENTRATION
NOV.  4, 1974
FIGURE 12

-------
                                              I) VALUES IN
                                                PARTS PER MILLION
                                             (2) CORES AT 1-1.5 FT.
                                                DEPTH
                                             (3) VALUES FOR PCB 1242
                                                AND 1248/54
                                                   Scale in Feet
PCB  SEDIMENT CONCENTRATION IN CORES
  NOV.  4, 1974
FIGURE 13

-------
        Table  11.   PCB  IN  SEDIMENT TAKEN  FROM SLIP  1  (11-4-74)*
Station
Number
201
202
203
204
205
206
207
208
209
211
212
213
214
215
216
217
218
219
220
221
222
223
1248/54
0.25
0.32
0.23
0.28
0.19
0.36
0.35
0.36
0.28
0.49
0.29
0.41
0.52
0.37
0.28
0.40
-
0.23
0.09
0.34
0.25
_
1242
0.69
0.41
1.2
0.43
1.5
1.2
1.6
1.2
0.45
0.48
0.57
0.35
0.44
0.33
0.38
0.29
185
0.58
0.09
0.34
0.44
12
Station
Number
224
225
226
227
228
229
230
231
232
233
234
235
236 '

218 core
219 core
222 core
223 core
225 core
230 core
231 core

1248/54
-
-
0.12
0.13
0.20
0.73
1.23

0.29
0.15
1.11
-
0.34

0.6
1.4
0.8
1.7
1.5
1.2
2.1

1242
50
1200
0.70
0.09
0.16
0.25
18
13
0.97
0.36
0.22
0.03
0.28

0.6
2.8
0.8
2.3
1.6
1.1
1.5

*  Concentrations expressed in microgram/gram,  wet weight (ppm)





                                   37

-------
    Table 12.  PCB IN SEDIMENTS  AT SELECTED  STATIONS*



  Time               Station  225          Station  231
9-25-74
10-18-74
11-4-74
2-20-75
30,900
1 ,900
1,200
1,300
                                             140

                                              50

                                              13

                                              60
* Concentrations  Aroclor  1242 expressed  in micrograms/gram,
  wet weight (ppm)
                          38

-------
                                  WATER
                                  DEPTH
                                   26 ft.
                                            (I) VALUES IN
                                              PARTS PER  MILLION
                                           (2) SHADED BOUNDARY OF
                                              HIGHEST CONCEN-
                                              TRATIONS RECORDED
                                              THIS DATE (PCB 1242)
                                                 Scale in Feet
JUN. 2, 1975
            PCB   SURFACE SEDIMENT
                     CONCENTRATION
FIGURE 14

-------
Table 13.  PCB IN SEDIMENTS TAKEN FROM SLIP 1  (6-2-75)*
   Station
   Number               1248/54            1242

    202                  0.06               0.15
    203                  0.16               0.37
    205                  0.05               0.17
    207                  0.12               0.35
    208                  0.17               0.56
    209                  -—               o.07
    213                  0.02               0.18
    215                  0.11               0.24
    216                  0.04               0.12
    217                  0.06               0.22
    218                  0.01               0.75
    219                  0.05               0 19
    222                  0.06               0.28
    223                  0.14               0.61
    224                  - -              23
    225                  - -              50
    226                  	             42
    227                  	            390
    228                  0.07               0.46
    229                  0.14               0.64
    230                  -__               6
    231                   __.             21
    Recoveries                            76-96%
    Blanks              ^0.10            
-------
                              WATER
                              DEPTH
                              26 ft.
             0.44-
             0.25
                                      (I) VALUES IN
                                        PARTS PER MILLION
                                      (2) VALUES FOR PCB 1242 AND/1248/
                                           Scale in Feet
     PCB  SEDIMENT CONCENTRATION

AUG. ,s, 197s  (BOTTOM 1/3 OF CORES)    pIGURE

-------
  BOTTOM
  CONTOUR
  30 FOOT
  DEPTH
                                        (I) VALUES IN PARTS
                                          PER MILLION
                                        (2) VALUES FOR PCB 1242 AND 1248/54
                                        (3) SHADED BOUNDARY
                                           OF HIGHEST
                                           CONCENTRATIONS
                                           RECORDED THIS DATE
                                               Scale in Feet
      P C B  SEDIMENT  CONCENTRATION
           (BOTTOM  ONE-THIRD CORES)
AUG. 18, 1975

-------
        Table 14.   PCB IN SEDIMENT CORES (8-18-75)**
                                                     Cone,  in  PPM
                         Core Depth in Inches            Wet Wt.
Station Number           Inside/Outside	      1248/54      1242

    202                        7/22               <0.2       <0.2
    203                        9/22               <0.2       <0.2
    205                        7/22                 0.55       1.2
    206                        8/16                 0.9         1.8
    206E                       8.5/28               0.45       0.59
    206W                       7/16                 1.3         1.7
    207                        8/18                 1.1         1.9
    207E                       8/24                 0.62       0.82
    207W                       8/20                 0.85       1.2
    208                        9/25                 0.63       1.1
    208E                       7/24               <:0.2       <0.2
    208W                       10/24              <10.2       <0.2
    215                        7/22                 0.92       1.2
    217                        10/22              <0.2       <0.2
    218                        6/18                 0.44       0.54
    219                        6/18                 0.23     <0.2
    222                        9/23                 0.25       0.44
    223                        8/19                 0.52       0.63
    224                        7/14                 0.8         1.5
    225                        8/18                 —       131
    226                        9/19.5               0.9         0.8
    231                        8/18                 0.12       0.04

    Blank]
    Blank2
    Recovery]                  —                  —       103%
    Recovery2                  —                  —       106%
    Recoverys                  —                  —       102%


*  Concentrations expressed in microgram/gram,  wet weight  (ppm)

=fc Values are for bottom one third of core sample only
                             43

-------
     moved  into  and  out  of  the  slip  directly  over  the  impact area
     several  times during this  period.   It  is  postulated  that prop-
     wash  from attempts  to  maneuver  the  ship  and tidal  action were
     the responsible  mixing forces.   Yet another survey of sediment
     PCB burden  was  carried out on January  16,  1976  before the
     second clean up  effort began.   Since the  winter of 1975/1976
     brought a   "20-year flood"  with  all  its  effects upon  the Duwamish
     River, it was felt  that the spilled PCB's  might have  been spread
     by flood action  throughout the  river channel.   Comparison of
     results of  the  January 16,  1976  survey (See Table  15, Figures
     17 and 18)  with  previously obtained data  indicate  that substantial
     diluting, scouring, and spreading of PCB  contaminated surface
     sediments did occur.   The  flood  action either removed or diluted
     Aroclor 1242 in  river  channel sediments  between river markers
     81 +  00 to  91 +  00  feet.

(3)   Characterization of Sediments

          Analysis of composite samples  representative  of  Slip 1
     sediments one foot  deep indicated that several  pollutants were
     present in  large quantities (See Table 16,Appendix C  and D).
     For example, the portion of Slip 1  sediments  that  was dredged
     contained 2.6 tons  of  Mn,  3.6 tons  of  Zn,  6.3 tons of Total-P,
     8 tons of oil and grease and 250 tons  of  Fe along  with smaller
     amounts of  Hg,  Cd and  As.   Taken altogether,  the amount of
     pollutants  were  approximately 300 of an  estimated  8,000 tons
     of material  dredged, or 4% by weight.

(4)   Predictive  Test

          The pre-dredqe survey  on February 23, 1976 was made
     to provide  information regarding the suitability of Slip 1
     sediments for dredge spoil  disposal.   The  Corps of Engineers
     planned to  dispose  of  the  sediments on land.  This presented
     an opportunity  to check the validity of  the Standard  Elutriate
     and other tests  currently  used  by the  Corps to  predict the amount
     of pollution released  into return waters  resulting from a hydraulic
     pipeline dredge.  Two  tests, the "Standard Elutriate  Test" and
     "interstitial water evaluation", were  studied.  A  comparison  of
     test  results with observed  levels of pollution  in  return waters
     is found in  Table 16.   (See Appendices C  and  D  for supporting
     data  and formula  used  to arrive  at  values  found in Table 16).
     In general,  observed values of  pollutants  returning to the river
     fall  between those  predicted by  either test.  The  values obtained
     using  "interstitial water  evaluation"  are  lower than  observed
     and those values  obtained  using  the "Standard Elutriate Test" give
     mixed  results (See  Table 17).   50%  of  the  pollutants  tested are
     predicted correctly by the  "Standard Elutriate  Test"  within + two
     times  (2X)  the observed amount.  Only  8%  tested by the "interstitial
                             44

-------
                                  WATER
                                  DEPTH
                                           (I) VALUES IN
                                              PARTS PER MILLION
                                           (2) SHADED BOUNDARY OF
                                              HIGHEST CONCENT-
                                              RATIONS RECORDED
                                              THIS DATE (PCB 1242)
                                                 Scale in Feet
     PCB  SEDIMENT  CONCENTRATION
JAN. 16, 1976
FIGURE 17

-------
      X
  BOTTOM
  CONTOUR
  30 FOOT
  DEPTH
                                        (I) VALUES IN PARTS

                                          PER MILLION (PCB  1242)
                                                Scale in Feet
       PCB  SEDIMENT  CONCENTRATION
JAN. 16, 1976                                               FIGURE 18

-------
         Table 15.  PCB IN SLIP 1 SEDIMENTS (1-16-76)*
Station
Number
203
205
206
206W
207
207W
208
209
211
213
215
216
217
218
219
222
223
224
225
226
227
228
229
230
231
250
206 Dup.
223 Dup.
Recoveries 80.5-95%
Blanks

1248/54
0.05
0.08
0.06
0.05
0.06
0.08
0.09
0.05
0.03
0.11
0.08
0.11
0.19
_
0.15
0.08
-
_
-
-
_
-
-
0.06
-
-
0.10
0.20

<0.01
                                        1242

                                        0.03
                                        0.08
                                        0.05
                                        0.04
                                        0.06
                                        0.08
                                        0.07
                                       <0.01
                                        0.04
                                        0.09
                                        0.03
                                        0.12
                                        0.16
                                        2.7
                                        0.08
                                        0.07
                                        0.70
                                        6.0
                                       42.
                                        1.2
                                        3.2
                                        0.8
                                        1.8
                                        0.04
                                       18.
                                       17.
                                         .04
                                        0.30

                                       <0.01
Total PCB

  0.08
  0.16
  0.11
  0.09
  0.12
  0.16
  0.16
  0.05
  0.07
  0.20
  0.11
  0.23
  0.35
  2.7
  0.23
  0.15
  0.70
  6.0
 42.
  1.2
  3.2
  0.8
  1.8
  0.10
 18.
 17.
  0.14
  0.50

 <0.01
* Concentrations expressed in microgram/gram, wet weight (ppm)
                            47

-------
                                                         Table 16.  PREDICTIVE TEST ANALYSIS SUMMARY


Parameter
V As
Cd
Cr
V
Cu
^ Fe
^ Mn
Hg
o Ni
y zn
PCB
Oil/Grease
Total P

N-NHs
TKN
COD
Total
Possi ble
Rel ease
(grams)
73,000
17,000
240,000

440,000
230,000,000
2,400,000
1,000
150,000
3,300,000
280,000*
7,300,000
5,700,000

280,000
6,100,000
280,000,000
Predicted
Elutriate
grams
450
160
1 ,500

200
14,000
72,000
6

-------
                                    Table 17.   COMPARISON OF PREDICTIVE TEST ACCURACY
          Comparison
UD
Number Parameters With
Higher Predicted
Values Than Observed

Number Parameters With
Lower Predicted Values
Than Observed

Number of Predicted
Values Same as
Observed
                           Observed Return Flow Values
                                     versus
                           Standard       Interstitial
                           Elutriate      Water Eval-
                           Test           uation
                           No.   (%)      No.      (%)
                   Adjusted Observed Return Flow Values
                                   versus
                     Standard              Interstitial
                     Elutriate             Water Eval-
                     Test                  uation
                     No.    (%)	No.       (%)
                                           (36%)
                                       6   (43%)
                                       3   (21%)
10
       (15%)
(77%)
        (8%)
                    (50%)
(43%)
                     (7%)
                        (23%)
(69%)
                         (8%)
Number Parameters With
Predicted Value
(A) Within +_ 2X
(observed value)
(B) Within ± 3X
(observed value)
(C) Within + 10X
(observed value)
(D) Within +_ 25X
(observed value)
Total Number of
Parameters


7

9

11

13

14



(50%)

(64%)

(79%)

(93%)

(100%)



1

3

9

9

13



(8%)

(23%)

(69%)

(69%)

(100%)



4

7

10

12

14



(29%)

(50%)

(71%)

(86%)

(100%)



3

4

8

8

13



(23%)

(31%)

(62%)

(62%)

(100%)


-------
         water evaluation" meet this criteria.  64% of pollutants  give
         results that fall within +_ three times (+3X) the values using
         the "Standard Elutriate Test" but only 23% do so for  "interstitial
         water evaluation".  The "Standard Elutriate Test" appears  to be
         valid for most metals, grease and oil and nutrients.   "Interstitial
         water evaluation" appears to be useful only for some  metals and
         nutrients.  Both tests failed to predict PCB release  accurately.
         Interstitial water evaluation predictive capabilities  generally
         increase when effects due to river water used in the  dredging
         operation are considered (See Table  16).

     (5)  Microbiological Enumeration

              Table  18 lists the bacteriological results from  the  six
         stations located in the Slip 1 study area.  Samples collected
         before dredging  (pre-dredge) and approximately nine weeks  later
         (post-dredge) showed a significant removal in all bacterial
         groups, particularly C_. perfringens.  The only area not to show
         a  decrease  in C_. perfringens was area 1 (Figure 3), which  happens
         to be the location of the PCB spill  and closest to the main
         channel of  the Duwamish Waterway.  Considering this area  was
         dredged to  a greater depth (10 feet) than the surrounding
         areas, backwater currents may have re-deposited sediments  from
         the main channel during the three month interim between the pre
         and post dredge  visits.  Samples collected from the main  channel
         18 months earlier  (August 1974) had  shown a high background level
         of C_. perfringens  ranging from 60-35,000 organisms/g.

              Besides C_.  perfringens, there was a significant  reduction
         in FC densitites which often indicate the presence of fecal
         waste material.  Since it is known that most enteric  bacteria
         as well as  viruses eventually end up in bottom sediments  after
         they are discharged into either fresh or marine waters, determination
         of public health hazards should include a concern for their presence
         and removal from bottom sediments.
(B)   PHASE  II.   DREDGE MONITORING ACTIVITIES

     (1)  Estimation  of  PCB  Removal  by Analysis  of  Slip  1  Sediments

               Approximately 86-98%  of the  spilled  Aroclor was  removed
         from  Slip  1.   Several  samples  of  dredged  area  sediments  were
         analyzed for PCB contamination while the  dredging operation was
         in  progress.   Most areas proved to  be  relatively free of the
         contaminant after  one  pass of  the dredge  (Table  19,  Figure 4),
         but the area near  the  impact site was  redredged  several  times
         to  achieve  maximum removal of  the Aroclor.   The  result of  this
         continual  redredging was the formation of a  hole approximately
                                 50

-------
        TABLE  18.   BACTERIAL  CONTENT  OF  POST  AND  PRE-DREDGE SEDIMENT SAMPLES
                   TAKEN FROM SIX  ZONAL  AREAS IN  SLIP ONE
Station

  1
  2
  3
  4
  5
  6
  1
  2
  3
  4
  5
  6
PRE-DREDGE
Date
2/23/76
2/23/76
2/23/76
2/23/76
2/23/76
2/23/76
Total
Coliforms
/TOO g.
350,000
54,000
9,000
35,000
4,900
54,000
Fecal
Coliforms
/TOO g.
7,900
7,900
1,300
790
4,900
13,000
Fecal
Strep-
tococci
/1 00 g.
350,000
170,000
46,000
170,000 .
92,000
350,000
20° C
Plate
Count/g
1,600,000
1,800,000
1,100,000
1,000,000
1 ,800,000
3,200,000
Clostridium
Perfringens/g
6,000
5,500
10,000
11,000
15,000
8,200
POST-DREDGE

 5/3/76
 5/3/76
 5/3/76
 5/3/76
 5/3/76
 5/3/76
 2,400
    18
    20
 4,600
 4,600
35,000
2,400
   18
   18
2,400
  490
1,700
 2,800
 1,400
   130
54,000
11,000
92,000
140,000
210,000
  7,600
620,000
360,000
360,000
17,000
   400
    93
 2,700
   790
 4,000
                                        51

-------
   Table 19.  PCB IN SEDIMENTS TAKEN DURING DREDGING OPERATIONS*
  Date            Description          1248/54      1242     Total PCB

3-10-76     Station 231 (30 ft. from     1.6        2.5        4.1
            pier off riverside
            ladder)

3-10-76     30ft. north of Station      0.8        3.3        4.1
            231

3-10-76     30 ft. south of Station      1.8        2.3        4.1
            231

3-15-76     20ft. northeast of          2.7        1.2        2.9
            Station 226

3-15-76     100 ft. south of Station     1.4        0.9        2.3
            225

3-15-76     Station 224                  1.1        1.1        2.2

3-22-76     70 ft. southwest of          0.4       <0.1        0.4
            northeast corner of
            Slip 1

3-22-76     30 ft. west of Station       1.8        1.1        2.9
            227

3-22-76     Station 225 off pier          -     2,400      2,400
            side ladder (north side
            of Slip 1  entrance)

3-23-76     Composite of four grabs       -       112        112
            taken (1)  at Station 225
            (2) 25 ft.  east of 225
            (3) 25 ft.  west of 225
            and (4) 25  ft.  south of
            225

3-26-76     25 ft. south of Station 225   -       184        184

3-26-76     Composite of three grabs      -        16         16
            taken (1)  at Station 225
            (2) 25 ft.  east of 225 and
            (3) 25 ft.  west of 225

3-27-76     30 ft. south and 30. ft.       -        13         13
            west of Station 225
                              52

-------
                        TABLE 19 (Continued)
3-27-76     30 ft. south of Station        -          43          43
            225

3-27-76     30 ft. south and 30 ft.        -          41          41
            east of Station 225

3-29-76     30 ft. south of Station        -          17          17
            225

3-29-76     30 ft. south and 30 ft.       0.5          0.3         0.8
            east of Station 225

*  Results expressed in microgram/gram, wet weight (ppm)
                                  53

-------
                                                       area if
                                                        This
                                                       the levels
                                                       process.
60'  X 30'  X 10'  deep.   The concentration  of PCB in sediment varied
over a wide range.   It can be shown  that  approximately 100 gallons
of Aroclor 1242  were removed with  the  sediment in this
one assumes the  average PCB concentration was  760 ppm.
concentration (760  ppm) is reasonable  if  one considers
of PCB contamination encountered during  the redredging
Most of the impact  area sediment was  removed before March 23, 1976
during one day of dredging.   The remaining material was removed
using a dredge operating at one third  capacity over a two day period.
The ratio of volumes of sediment dredged  during these time periods
may be calculated by comparing the number of days of dredging
activity for each time period adjusted to account for differences
in dredge capacity  during the same time periods (See Equation A).
Therefore, (1.0  day) (1.0):(2.0 day)  (0.33) becomes 60% sediment
volume:  40% sediment volume for the  two  time  periods.
     Eqn. A.  (Days)(cap.):(Days)(Cap. )

     Values of PCB between 112 to  2400 ppm were encountered at
the impact area during removal of  the first 60% of the sediment
and between 0.8 and 43 ppm for the remainder.  If an average
value of 1,256 ppm of PCB is used  for the first 60% of the volume
of sediment removed from the area  and 22 ppm for the remaining
40%, then one arrives at the overall  average of approximately
760 ppm PCB in the sediment.   Since the  sediment density was 85
lbs/ft.3, it follows that approximately  100 gallons of PCB were
removed with the sediment (See Equation  B).

     Eqn. B.  Amount of PCB recovered from impacted area

     760 X IP"6 1b. PCB  85 Ib.  sed.   10X30X60 ft.3  1  gal. PCB
         Ib. sed.
     - 101 gallons
                           ft.3  sed.
11.5 Ib.  PCB
     An estimate of the amount of PCB removed from the remaining
area of the slip was made by difference.  In an internal  memo to
F. Nelson, Chief of EPA Technical Support Branch, J.  N. Blazevich
calculated the amount of PCB in Slip 1  (minus that in the impact
area) to be approximately 40 gallons on November 4, 1974 (2).
Assuming all  40 gallons were removed from the remaining portion of
the slip, the amount of PCB recovered by the second cleanup operation
would be 140 gallons.  When added to the 80 gallons removed during
the first clean-up effort (1), the total amount of PCB recovered
becomes approximately 220 gallons.
                          54

-------
(2)   Disposal  Pond Influent

          Disposal pond influents were collected and analyzed
     for several pollutants (See Appendix C, Sections II, V and
     VI for results).  Analysis of tha  data will be made in detail
     by Mr. Ron Hoeppel of the Army Corps of Engineers, Waterways
     Experiment   Station at Vicksburg, Mississippi.

(3)   Disposal  Pond Effluent

          Unfiltered disposal  pond effluents were monitored during
     the dredging operation.  Estimates of quantities of various
     pollutants returning to the river based on the number of
     gallons of return water and the concentration of pollutant
     present in representative composite samples are found in Table
     16.   (See Appendix C, Section II and Appendix D, Table D-7).
     See Part IVA, Phase I (4) for discussion.   Filtered disposal
     pond effluents were monitored to determine the amount of PCB
     returning to the river (See Table 20).  Less than 11 grams of
     PCB were found in the effluent.

(4)   Water Column at the Dredge Site^

          Analysis of water collected at the dredge site was performed
     Comparison of background and dredge site monitoring station data
     indicate little, if any, increase in pollutants in the water
     column at Slip 1 during the dredging activities, except for a
     transient PCB pulse that was observed in samples collected almost
     exclusively  in the dredge vehicle prop wash while work in the
     area of highest PCB concentrations was in progress.  The results
     are reported in Appendix C, Section IV.

(5)   Miscellaneous Results

          Several other samples of water and sediment were analyzed
     during the course of the dredging operation (See Table 21).
     These analyses were performed to help determine the impact of
     the dredging project on the environment.

          Water samples from several points within the disposal
     treatment process were analyzed for PCB's in order to determine
     if the facility was working as designed.  Some points (i.e.
     effluent from Pond 1) were monitored regularly for metals,
     nutrients and PCB's  (See Appendix C, Section II).

          Samples of sediment and solids from influent and effluent
     were  used to determine the amount of easily reduced metals,
     etc., present in each. These data are found  in Appendix C,
     Section V.
                            55

-------
Table 20.    PCB IN EFFLUENT FROM FILTER SYS I EM*
Date of
Sampling
3-13-76
3-14-76
3-14-76
3-15-76
3-16-76
3-16-76
3-17-76
3-17-76
3-17-76
3-18-76
3-18-76
3-18-76
3-20-76
3-20-76
3-21-76
3-21-76
3-22-76
3-23-76
3-24-76
3-25-76
3-26-76
3-27-76
3-28-76
3-29-76
3-30-76
3-31-76
4-1-76
4-2-76
4-3-76
4-4-76
4-6-76
4-7-76
Total
Gallons
Pumped $
100,000
45,000
48,000
65,000
115,000
108,000
120,000
48,000
25,000
46,000
3 carbon column
in parallel
169,000
66,000
230,000
300,000
216,000
543,000
432,000
432,000
432,000
432,000
828,000
624,000
408,000
696,000
504,000
678,000
810,000
378,000
432,000
504,000
9,834,000

1248/54
.
-
0.3

0.7
cO.05
^0.05
cO. 1
CO.l
0.06
0.05
0.07
< 0.05
CO. 08
CO. 05
CO. 05
< 0.05
<0.05
<- 0. 1
0.33
0.25
0.35
0.16
1.1
0.07
0.03
0.08
0.03
<0.16
0.22
C.0.01
0.1


1242
^0.5
C2.4
^0.01
Lost
0.04
CO.05
CO. 05
CO.l
< 0 . 1

-------
               Table 21.  PCB RESULTS FOR MISCELLANEOUS SAMPLES*

Date              Description               1248/54        1242       Total  PCB
3-12-76     Effluent from pond 1 to         <0.05         2.1           2.1
            pond 2
3-16-76     Effluent from carbon            
-------
                          TABLE 21 (Continued)
4-7-76     Composite pond 3 (before
           Corps filter)

4-7-76     Solids from high speed
           centrifugation of pond 2
           effluent
0.16
 NA
0.19
 NA
0.35
 NA
*   Results expressed in microgram/1iter, except where noted
*   Results expressed in microgram/gram,  wet weight (ppm)
NA  Mot Available
                                58

-------
     (6)   Microbiological  Enumeration

               The results of bacteriological  monitoring during the actual
          dredging operation are shown on Table 22.   With the exception
          of TC's, all  bacterial indices were  reduced by passage through
          disposal ponds 1 and 2.   Many microorganisms found  in sediments
          are bound to  solids or occur as aggregates adsorbed  to solids  and
          simply settle out in slow moving or  static water systems.   The
          survival and  movement of microorganisms  adsorbed to solids  are
          quite variable and influenced by such environmental  conditions
          as pH, temperature, antagonisms, nutrient  availability,  etc.
          Furthermore,  sporeforms  such as C_. perfringens and  certain
          cocci such as FS survive better in sediment environments than
          either TC or  FC and consequently may be  more associated  with
          dredge materials.  This  combination  of factors may  have  been
          responsible for the great reduction  in the FS and C^.  perfringens
          population as opposed to the corresponding TC and FC  populations.


(C)   PHASE III.  POST-DREDGE

          Post-dredge monitoring activities, including analysis of river
     bottom sediments,  disposal pond sludges and stratified dredge site
     water column samples, were conducted in order to assess  the
     effectiveness of the recovery effort and  the  environmental  effects
     of the project.

     (1)   Slip 1 Sediments

               A post-dredge survey of Slip 1  and  river channel  sediments
          was made on May 4, 1976.  Evaluation of  survey results indicates
          that a large  portion of  the slip is  free of Aroclor 1242 (See
          Table 23, Figure 19).  Only the area in  the impact  site  shows
          elevated Aroclor 1242 levels in the  sediment.   When compared  to
          the higher levels observed during the second clean  up effort
          (2400 ppm) (See Table 19), one notes a 50  fold reduction of the
          pollutant.  The impact area was sampled  twice using two  different
          sampling methods.  The first method  required use of the  top 5 cm
          of sediment to determine the extent  of translocation  and dilution
          of PCB contaminated sediment.  The second  method required
          compositing of several grab samples  in order to formulate a more
          accurate description of  the PCB burden in  the impact  area.  Of
          course, localized effects are minimized  using the latter method.

               Analyses of other pollutants in sediments and  interstitial
          water were performed.  The results are tabulated in Appendix  C,
          Section III.
                                59

-------
                             TABLE 22.  BACTERIAL CONTENT OF INFLUENT INTO DISPOSAL POND 1 AND
                                        EFFLUENT OUT OF DISPOSAL POND 2.
                                                                                                           Clos-
            Location
01
o
Date
Influent to
Pond No. 1



Effluent
from Pond
No. 2


3/16/77
3/22/76
3/23/76
3/30/76
4/5/76
3/16/77
3/22/76
3/23/76
3/23/76
3/30/76


Dredge
Area
5 & 6
3
1
1
1
5 & 6
3
1
1
1

Total
Col i forms/
100 ml.
220
790
14,000
220
49
920
2,800
7,900
1,400
68

Fecal
Coliforms/
100 ml.
220
40
490
18
18
18
18
18
18
18
Fecal
Strep-
tococci
/100 ml.
2,400
330
2,400
170
18
18
18
18
18
18
20U C
Plate
Count
/ml .
44,000
7,900
35,000
4,000
19,000
14,000
22,000
3,000
9,100
19,000
tridium
per-
fringens
/ml.
3,000
690
370
88
2
10
1
7
2
2

-------
                               WATER
                               DEPTH
                               26 ft.
                                        (I) VALUES IN

                                           PARTS PER MILLION
      P C  B  SEDIMENT CONCENTRATION

                      (POST DREDGE)
MAY 4, 1976
FIGURE 19

-------
RESULTS OF ANALYSIS OF PCB'S
(5-4-76)*
 Table 23
IN DUMAMISH RIVER POST DREDGE SURVEY
Station
Number
211
212
213
214
202
203
204
206
207
208
209
218
219
222
223
224
225
226
227
228
229
230
232
233
250
Composite of area
in and around 225
Blanks

1248/54
0.2
0.2
0.2
0.3
0.4
0.3
0.2
0.2
0.2
0.2
0.2
0.5
0.3
0.4
-
0.5
-
0.4
1.4
1.5
0.5
0.6
0.3
0.2
<0.6
-

<0.01
                                         1242
 0.
 0.
 0.
 0.
<0.
<0.
<0.
<0.
<0.
CO.
<0.
   .05
   .03
   .09
    15
   .01
   .01
   .01
   .01
   .01
   .01
   .01
  3.2
 <0.01
  0.4
  8
  2.3
140
  0.4
  0.
  0.
  0.
  1
  0.
  0.
 <0.
 50
   ,3
   1
   .4
   .0
   ,1
   ,1
   .6
                                       <0.01
                            Total  PCB
                                                           0.
                                                           0.
                                                           0.3
                                                           0.4
                                                           0.4
                                                           0.
                                                           0.
                                                           0.
                                                           0.
                                                           0.
                                                           0.
                               .3
                               .2
                               .2
                               .2
                               .2
                               .2
                                                           3.7
                                                           0.3
                                                           0.8
                              2.8
                            140
                              0.8
                              1
                              1
                              0.9
                              1.6
                              0.4
                              0.3
                                                            .7
                                                            .5
                             50

                            <0.01
    Results  expressed  in microgram/gram,  wet weight  (ppm)
                              62

-------
(2)   Estimation of PCB Removal  by Analysis of Disposal Pond Sediments

          An attempt was made to determine the amount of PCB trapped
     in the first disposal pond.  Analysis of nine composite samples
     consisting of 166 separate grab samples and a land survey of
     the spoils were used to estimate the amount of PCB removed from
     Slip 1 (See Figures 5 & 6).  Since the BIA ship, the Northstar,
     was berthed near the impact area during the first half of the
     operation, only a portion of the highly contaminated sediments
     were initially dredged.  The dredge was returned to the impact
     site after working in a less polluted area only after the
     Northstar was moved.  Surface and total core samples were
     composited in an attempt to detect stratification of highly
     polluted sediments due to the order in which sediments were
     dredged.  Evaluation of survey results indicated that even
     though some stratification exists the spoils may be considered
     well mixed (Table 24, Figure 5).  Therefore, averages of PCB
     values from two areas in Pond 1, area 1 (146 ppm) and areas
     2 and 3 (33 ppm), were used along with estimated total yardage
     (area 1 = 5280 yd3 and area (2 + 3) = 1880 yd3) to calculate
     the amount of PCB (170 gallons) in the disposal pond sediments
     (See Appendix E, Figure E-l).   When added to the 80  gallons
     removed during the first clean up, the total amount of PCB
     recovered becomes 250 gallons or a 98% recovery.

(3)   Water Column at the Dredge Site

          Evaluation of water column data (See Appendix C, Section 4)
     indicates no measurable amount of pollutants were introduced
     into the water column at the dredge site by the dredge operation.

(4)   Microbiological Enumeration

          The dredge spoils sampled from the first disposal pond are
     shown in Table 25.  Except for the SW corner, all five bacterial
     indices appear well dispersed throughout the entire area of the
     pond.  Since the SW corner was the location of the outlet pipe
     from the dredge, it is not surprising to find higher numbers
     of most parameters at this location.

          FC populations in the pond were low while  the  FS and 20° C
     plate counts were quite high.  This disparity in numbers could be
     attributed to the relative survivability of each in dry sediments
     lacking a complete water cover.  Surprisingly, only the S.E.
     transect and S.W. corner contained high residual levels of C_.
     perfringens.  The adaptability of this sporeforming organism to
     harsh environments is well documented  (18) as is it's  association
     with organic material originating from treated human  sewage waste.
     This organism is perhaps the most widely spread pathogenic bacterium
     in the Puget Sound and directly relates to the amount of pollution
     present (19).
                           63

-------
       Table 24.   RESULTS  OF  ANALYSIS  OF  POND  1  DREDGE  SPOILS*
Sample Number



  23400



  23401



  23402



  23403



  23404



  23405



  23406



  23407



  23408
           Description



Whole core - southeast transect



Surface - southeast transect



Whole core   middle transect



Surface - middle transect



Whole core - west transect



Surface - west transect



Whole core - northeast section



Surface   northeast section



Surface - southwest corner
Aroclor 1242



   158



   178



   165



    50



   140



   185



    35



    31



   150
  *   Expressed  in microgram/gram, wet weight (ppm)
                               64

-------
                           TABLE 25.   DREDGE SPOILS COLLECTED FROM DISPOSAL POND #1 APPROXIMATELY
                                             TWO MONTHS AFTER DREDGE OPERATION
cr>
en
Location
S.E. Transect
Middle Transect
West Transect
N.E. Section
N.E. Section
S.W. Corner
Type of Sample
Hold Core
Hold Core
Hold Core
Hold Core
Surface Grab
Surface Grab
Total
Col i forms
/lOOg
270
7,900
490
78
230
79,000
Fecal
Col i forms
/lOOg
18
20
20
18
20
18
Fecal
Strep-
tococci
/lOOg
4,600
2,100
1,700
790
1,300
1,400
20° C
Plate
Count/g
3,800,000
2,200,000
1 ,600,000
210,000
11,000,000
15,000,000
Clos-
tridium
per-
fringens/g
2,200
10
10
10
11
4,000

-------
                              REFERENCES
 (1)   Region  X  On-Scene  Coordinator Report.  PCB,  Duwamish  Waterway,
      Seattle,  WA,  September  13-October 31,  1974.

 (2)   Blazevich,  J.  N.,  memo  to F. Nelson, U. S. Environmental  Protection
      Agency, Region  X.   February 10, 1975.

 (3)   Pavlou, S.  et.  al.   University of Washington Special  Report  No.  66.
      PCB  Monitoring  in  the Duwamish River,  A Study of Their  Release
      Induced by  the  Dredging Activities in  Slip 1.  July 1976.

 (4)   U. S. Environmental  Protection Agency, Ocean Dumping  Final Criteria,
      Federal Register 38_ (94), 12872-12877, 1973.

 (5)   U. S. Environmental  Protection Agency, Ocean Dumping  Final Criteria,
      Federal Register 38  (198), 28610-28621, 1973.

 (6)   Keeley, J.  W.  and  R. M. Engler.  Discussion  of Regulatory Criteria
      for  Ocean Disposal  of Dredged Materials Elutriate Test  Rationale
      and  Implementation  Guidelines.  U. S.  Army Waterways  Experiment
      Station Misc.  Paper  D-74-14, 13 p.,  1974.

 (7)   Elutriate Test  Implementation Guidelines, Ocean Dumping Criteria  for
      Dredged Material.   ER 1130-2-408, Jan. 17, 1974.  Department of  the
      Army, Office  of the  Chief of Engineers, Washington, D.C.  20314.

 (8)   Recommended Procedures  for the Bacteriological Examination of Sea
      Water and Shellfish.  4th Ed., American Public Health Association,
      American  Public Health  Association,  New York, N.Y., 1970.

 (9)   Standard  Methods for the Examination of Water and Wastewater.   14th
      Ed., American Public Health Association,  1015 Eighteenth  St., N.W.,
      Washington, D.C.,   1975.

(10)   Methods for Chemical Analysis of Water and Wastes, EPA  Office of
      Technology  Transfer, Washington, D.C.  20460.  1974.

(11)   Analytical  Methods  for  Atomic Absorption  Spectrophotometry,  Perkin-
      Elmer,  Norwalk, Connecticut  06856.  1976.

(12)   Krishnamurty, K. V., E. Shpirt, and  M. M. Reddy, Atomic Absorption
      Newsletter, J5_, (3), 68, 1976.

(13)   Analysis  of Pesticide Residues in Human and  Environmental Samples.
      U. S. Environmental  Protection Agency.  J. F. Thompson, Editor.
      Research  Triangle  Park, N. C.  1974.

(14)   Determination of Pesticide and PCB in  Sediments, U. S.  Environmental
      Protection  Agency,  Region X Laboratory, 1975.
                                   66

-------
(15)   Green, E.  J.  and D.  Schnitker.   Marine Chemistry,  2,  111,  1974.

(16)   Bacteriological  Analytical  Manual.   U. S.  Food and Drug Administration,
      Washington, D.C., 1972.

(17)   Sound Survey Photo Maps of Duwamish River.   U. S.  Army Engineers
      Seattle District, File No.  E-12-2.1-70 and E12-2.1-71, U.  S.  Army
      Corps of Engineers, 1973, 1974.

(18)   Bonde, 6.  J.  Pollution of a Marine Environment.  J.  Water  Pollution
      Cont. Fed. 39, 45-63, 1967.

(19)   Matches, Jack R., John Listen and Donald Curran.   Clostridium
      perfringens in the Environment.  Appl. Microbiol.   28, 655-660,
      1974.
                                     67

-------
Appendix A

-------
                             Appendix A


Scope:  The monitoring program was carried out in three phases.   Phase I
included monitoring activities before dredging, Phase II during  dredging
and Phase III after dredging.

I.   Phase I:  Predredge Analysis

    A.  Sediment evaluation was performed before dredging to determine
        the extent of pollution in Slip 1.

        1 -   Slip } Sediments

            (a)  PCBs in 29 grab samples and 6 composite samples
            (b)  Metals:  Hg, Cd, Pb, Zn, Fe, Mn, Cr, As and Cu  in  6
                 composite samples
            (c)  Oil and grease and COD in 6 composite samples
            (d)  Sulfide ion and volatile solids, in  6 composite  samples
            (e)  Nutrients:  P, NH3, and TKN in 6 composite  samples
            (f)  Microbiology:  TC, FC, FS and Clostridium perfringens
                 (anaerobe)

        2.   Interstitial Water

            (a)  PCBs in 6 composite samples
            (b)  Metals:  Hg, Cd, Zn, Fe, Mn, Cr, Ni, As and Cu  in  6
                 composite samples
            (c)  Nutrients:  P, NH3, N03, TKN and TOC in 6 composite
                 samples
            (d)  pH and conductivity in 6 composite samples

        3.   Elutriate Test Water with Slip 1 Sediments

            (a)  PCBs in 6 composite samples
            (b)  Metals:  Hg, Cd, Zn, Fe, Mn, As, Cr, Ni and Cu  in
                 6 composite samples
            (c)  Oil and grease in 6 composite samples
            (d)  Nutrients:  P, NH3, N03, TKN and TOC in 6 composite
                 samples
                                69

-------
         4.   On Site Monitoring  of  Interfacial  Water  Quality at Time
             of Sediment Collection

             (a)  Hydrolab:   pH,  DO,  conductivity,  and  temperature at
                  each station  in or  near  Slip  1

         Water Evaluation

         1.   Suspended Particulate Matter  (SPM)

             (a)'  PCBs were  determined  in  six composite  samples collected
                  during the large ebb  of  the semi-diurnal  tide.   One set
                  of samples, consisting of  a surface and  two eight meter
                  deep composites, was  acquired over  the three hour period
                  just prior to  slack water.  Another set  was obtained in
                  a  similar  manner during  the three hour period immediately
                  after the  flood crest.
2.







3.
Whole Water
(a)
(b)

(c)

(d)


On
PCBs were determined in six composite samples collected
at depth and time intervals described in IBla.
Metals: Water samples were composited according to the
scheme outlined in IBla for determination of Hg, Cd,
Zn, Fe, Mn, As, Cr
Nutrients: P, NH3,
six composites coll
Oil and grease and
on six samples coll
interval described
Site Determinations
and Cu.
N03, TKN and TOC were determined in
ected in a manner similar to IBla.
sulfide determinations were performed
ected at the center of each sampling
in IBla.

             (a)   Hydrolab:   DO,  pH, conductivity and  temperature were
                  monitored  continuously during sample collection.

II.   Phase  II:  Analysis  During Dredging Operation

     A.   Sediment  Evaluation

         1.   Sediments

             (a)   PCBs were  determined  in sediment samples  taken from
                  dredged areas in order to estimate the  relative success
                  of  the  dredging operation.

     B.   Water  Evaluation:   Disposal Pond Influent and Effluent

         1.   Whole Water

             (a)   PCBs were  determined  in several samples of disposal pond
                  effluent composited daily according  to  time and volume.
                                 70

-------
              (b)   Metals:   Hg,  Cd,  Zn,  Fe,  Mn,  As  and  Cu  were  determined
                   in  samples  composited automatically  using  an ISCO
                   sampler.
              (c)   Nutrients:   P,  NHs,  NOs,  TKN, and  TOC were determined
                   in  composite  samples  collected in  a  manner similar
                   to  that  used  in IIBlb.
              (d)   Oil  and  grease  and suspended  solids  were determined  in
                   composite samples collected according to the method  used
                   in  IIBla.
              (e)   Microbiology:   TC, FC,  FS and C. perfringens (anaerobe).

          2.   On Site  Monitoring

              (a)   Hydrolab:  The  pH, conductivity, DO  and temperature  of
                   disposal  pond effluent  were monitored continuously during
                   the dredging  operation.

      C.   Water Evaluation:   River Water at  the  Dredge  Site

          1.   Suspended Particulate  Matter

              (a)   PCBs were determined  according to  IBla.

          2.   Whole Water

              (a)   PCBs were analyzed according  to  IB2a.
              (b)   Metals as per IB2b.
              (c)   Nutrients as  per  IB2c.
              (d)   Oil  and  Grease, Sulfide,  TKN  and TOC according to IB2d.

          3.   On Site  Determinations

              (a)   Hydrolab as per IB3a.

III.   Phase  III.  Post Dredge  Evaluation

      A.   Sediment Evaluation:  Slip 1

          Evaluation of Slip 1 sediments was performed  after  termination
          of dredging  in order to  determine  the  efficiency of the dredging
          operation and the extent of pollutant  translocation.

          1.   River Bottom  Sediments:
              Determination of PCBs,  metals,  etc.  was  made  according  to
              IA1.

          2.   Interstitial  Water:    PCB metals,  etc. were determined
              according to  IA2.
                                  71

-------
B.  Sediment Evaluation:   Disposal  Ponds

    1.   Disposal  Pond 1

        (a)  Determination of PCBs  in disposal  Pond 1  sediments was
             made in order to estimate the amount of PCB in that pond
        (b)  Microbiology;  TC,  FC,  FS and C.  perfringens

    2.   Disposal  Pond 2:   Since  Pond 2 received less than one percent
        of the total  dredge spoil sediment,  no  evaluation of its
        sediments was attempted.

C.  Water Evaluation:  River Water  at Dredge Site

    1.   Suspended Particulate Matter

        (a)  PCBs were determined according  to  IBla

    2.   Whole Water

        (a)  All  parameters  were determined  as  in IB2.

    3.   On Site Determinations

        (a)  Hydrolab as  per IB3a.
                              72

-------
APPENDIX B

-------
                   FIGURE B-l


Figures B-2, B-3 and  B-4 Combined

RECONSTRUCTED GAS CHROMATOGRAMS
PCS 1242 STO

       SED- TflKEN FTT POINT OF PCB SPILL - SLIP  1  -

                               - SLIP 1 - ON 9-13-74
   10   23   38    10   SO   60    70
   SPECTRUh NIM3EB
80   90   130  110  120
                  74

-------
                     FIGURE B-2
   RECONSTRUCTED  GAS CHROMATOGRAM
   310330 SLUDGE PROM PCB SPILL - SLIP 1 - ON 3-13-71
0    10   20   30   10   SO   80   70   80   30    100  110  120
     SPECTRUM NUGER
                   75

-------
                   FIGURE B-3


 RECONSTRUCTED GAS CHROMATOGRAM
1S22S SED- TfKEN flT POINT OF PCB SPILL - SLIP 1 -
0
Tfffln^^WWfVj
 10   20   aa
 SPECTHLH NLf«ER
                      S0   68   70   80   90   180  110  120
                     76

-------
                        FIGURE B-4
      RECONSTRUCTED GAS CHROMATOGRAM
      PCS 1212 STD
8_

8_
O
                  T
T
T
        10   20   30   10   SO
        SPECTRUM NUhBER
           60   70   90   30    100  110  120
                           77

-------
                  Figure B-5
 Figures  B-6, B-7 and B-8  Combined
 RECONSTRUCTED GAS CHROMATOGRAMS
 MASS RANGE:  256-261
PCB 1212 STO

1S22S SED.  TflKEN FTC POINT OF PCB SPILL - SLIP 1 -

310830 SLUDGE FRdh PCB SPILL - SLIP 1 -  ON 9-13-71
  10   20   30   10   SO   60   70   90   98   100  110  120
  SPECTRUM NUTTER
                       78

-------
                        FIGURE  B-6
       RECONSTRUCTED GAS CHROMAT06RAM
       MASS RANGE:  256-261
      318330 SUO3E FfCM PCB SP1UL - SLIP 1 - ON 9-13-71
8_
•"•I"
0
10
J V*
""I 	 "
20
"l""1"
30
*. m A. JMM
10
«•*
"T"'1"
SO
^ta^
"I""1"
60
"I""1"
70
80
30
"I""1"
100
..,....,.. ..1
110 120
                           79

-------
                         FIGURE B-7
      RECONSTRUCTED GAS CHROMATOGRAM
      MASS RANGE:  256-261
      1S22S SED-  TFKEN FIT POINT OF PCB SPILL - SLIP 1 -
§L
o
S3.
   0     10   20   30   10   SO   60   70   80   90    100  110  120
         SPECTRUM NLICBR
                             80

-------
                       FIGURE B-8
       RECONSTRUCTED GAS CHROMATOGRAM
       MASS RANGE:  256-261
      PCB 1212 STD
g
0
        10   20   30    10   SO
        SPECTRM NUMBER
70   80   30   180   110  120
                          81

-------
                   FIGURE B-9
Figures B-10, B-ll  and B-12 Combined
RECONSTRUCTED GAS CHROMATOGRAMS
MASS RANGE:  290-300
PCB 1212 STO

1S22S SED- TflKEN FT  POINT OF PCB SPILL - SLIP  1 -

318930 SLUDGE FROM PCB SfllLL - SLIP 1  - ON H-13-71
   102038*35060708030
   SPECTRUM NUMBER
100  110   120
                        82

-------
                          FIGURE B-10
        RECONSTRUCTED GAS CHROMATOGRAM
        MASS RANGE:  290-300
        310330 SLUDGE FROM PCB SPILL -  SLIP 1 - ON 9-13-71
  o
  <£-
 !§_
I—«

fc.
   I
    Q
T
I
 10   20   30
 SPECTPU1 NUMBER
F	I  '
10   SO
                60   70   80    30   100  110  120
                            83

-------
                        FIGURE B-ll
       RECONSTRUCTED GAS CHROMATOGRAM
       MASS RANGE:  290-300
      1S22S SED-  TflKEN fTT POINT OF PCB SPILL - SLIP 1 -
8.
S3
         10   20   30   10   SO   60   70
         SPECTRU1 NUMBER
80   90    100  110   120
                           84

-------
                          FIGURE B-12
      RECONSTRUCTED GAS CHROMATOGRAM
      MASS RANGE:  290-300
      PCS 1212 STD
S3
CM.
        T
T
         10   20   30
         SPECTRUM
            10   SO    60   70    80   90    100  110   120
                            85

-------
               FIGURE  8-13





SPECTRLM MJflER 10  -  31
g 310330
8.
s.
S_
S?

R_
2_
0_







30 10
M/ E
3-.IDS





|

50

3 FFEM ^





.
||| |
a TO

IB 3'lU-





llf

- 3.1P 1 - ON 3-13-71





ll I! i
l.lllll ,lll,l ,l!ll. II II, .,:!


I ,
90 90 100 110 120 130 11O ISO


O













160 170 190 ISO 260 210 220 230 Z1O 250






||

af
E
fe
_U)UJ



'"I" 	 I 	 '"I 	 I 	 I 	 I 	 I 	 I 	 I 	 I 	 |"'i|i"i| 	 | 	 | 	 |ini|iiii| 	
283270280230300310323330316350363370390330100110


-------
             SPECTRM NLTBER
00
g 1SZZ53:
8.
8.
P-
8.
Q

CM-
0







I 	 .|....,.".|
3B 10
MX E
D. TfKEN fTT POINT DF PCS




I,
,1 1

ll 1
!, . ill. III.
SO 60 70 80 30

S'ILL





|l ll
100

- SLIP 1 -





ll llllllll l|lll ill


I I
110 120 130 110 ISO

0





II 	 |,| 	 |





11, hi
160 170 180 130 ZOO 210 220 230 210 2SO




1
1,
260 270 230 230 300 310 320 3303^0350360370380390 100

t-
fe
1


»10


-------
00
00
                                 FIGURE B-15



              SPECTflLM NJ-BER IB  - 31



              PCB 1212 STD
        XED


        Q_

        LJD
                                                   Lj
ai
6
            30   18   S0   SB   78   88  30   100  118  120  130  110  ISO  160  178  188  138  298  218  228  238 218  2S8  268  270 288  238  380  313  328  330 318  3S0  368  370  380  330  1O8  110

                 M^ E

-------
Appendix C

-------
Section I

Section II


Section III

Section IV

Section V
           TABLE OF CONTENTS


Predredge analysis of sediments at Slip 1

Analysis of influent to pond 1  and effluents from
holding ponds 1 and 2

Post-dredge analysis of sediments at Slip  1

Water analysis at dredge and background sites

Exchange analysis and exchange capacity of sediments
and solids
Section VI    Miscellaneous materials
                                 90

-------
    Section I
     Results
       of
Predredge Analysis
       of
     Slip 1
    Sediments
      91

-------
    TABLE C-l.  COMPOSITION OF SEDIMENTS IN SLIP 1  BEFORE DREDGING
                                  Composite Samples from Designated Areas
Parameter
PCB ug/g
As ug/g
Cd
Cr
Cu
Fe
Pb
Mn
Hg
Zn
P ug/g
N-TKN
N-NHs
COD ug/g
Grease/Oil
Sulfide
Solids %
Solids-Volatile %
En volts
Density g/ml
1
72
8
0.5
21
39
25,100
44
250
0.1
110
590
630
14
28,200
715
42
42.5
8.9
+0.084
1.36
2
8
7
1.4
37
42
21 ,800
235
250
0.1
310
530
690
17
28,400
737
42
44.1
9.3
+0.022
1.32
3 & 4
2
8
5.0
20
59
21,000
84
220
0.1
1,000
520
460
15
28,700
1,120
86
40.7
10.4
-0.059
1.36
5
< 1
5
2.8
22
52
24,500
67
240
0.1
610
540
580
23
20,900
700
99
47.7
7.5
+0.006
1.36
6
1
6
0.6
15
32
18,300
44
180
< 0.1
120
510
480
69
26,200
361
53
46.5
7.1
+0.015
1.36
Units  expressed on  wet  weight  basis
                                      92

-------
                                  Table C-2
   COMPOSITION  OF ELUTRIATE WATER FROM PREDREDGED SEDIMENT  SAMPLES  FROM  SLIP  1
Parameter
PCB ug/1
As ug/1
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn
P-Total (a) mg/1
(b)
N-TKN
N-NH3
N-NOs + N02
Grease/Oil mg/1
TOC
Dredge Site
Water
<0.010
2.1
8.
16
7.2
1,300
80
0.4
<10
20.
_
0.098
0.17
0.04
0.41
< 1
3.
Compos i
1
158
16.2
4.
45
6.0
560
2,880
0.1
< 10
12.
0.19
0.11
4.5
3.3
1.4
1.9
17.
te Sample
2
29
12.2
8.
43
7.2
300
1,320
0.1
<"|0
4.
0.80
0.39
5.8
3.8
0.20
7.6
24.
from Designated Areas
3 + 4 5 6
30
15.9
4.
43
3.6
240
224
0.2
<10
<2
0.81
0.52
4.8
2.6
0.30
13
42
13
6.9
4.
47
18.0
260
1,920 3
0.6
<10
8.
0.24
0.19
3.0
2.2
0.29
3.0
15.
8
11.7
4.
47
9.0
540
,360
0.1
<10
4.
0.12
0.07
5.0
3.0
0.31
1.2
15.
PH
(a)   Sample centrifuged but not filtered
(b)   Sample centrifuged and filtered thru 0.45 u membrane
                                      93

-------
                                    Table C-3
  COMPOSITION OF INTERSTITIAL WATER FROM PREDREDGED SEDIMENT SAMPLES FROM SLIP
Parameter
PCB ug/1
As ug/1
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn
P-Total (a) mg/1
(b)
N-TKN
N-NHs
N-N03 + N02
N-N02
Grease/Oil mg/1
TOC
PH
Dredge Site
Water
<0.010
2.1
8.
16
7.2
1,300
80
0.4
<10
20.

0.098
0.17
0.04
0.41
-
-
3.
7.45
Composite Sample from Designated Areas
1 2 3 + 4 5 6
1,700
21.2
6.
15
6.0
4,000
1,640
0.4
<10
38.
3.32
1.8
12.
9.0
0.23
0.16
_
46.
6.9
143
32.3
4.
34
7.2
410
1,920
0.1
<10
10.
4.50
1.76
17.
11.
0.22
0.16

79.
7.8
147
21.5
4.
43
4.8
200
220
0.3

-------
               Section II

                Results
                  of
                Analysis
                  of
        Influent to Pond 1  and
Effluents from Holding Ponds 1 and 2
                     95

-------
TABLE C-4.   ANALYSIS OF INFLUENT TO POND 1

                   Date of Sampling
              16 March 1976 (076 Julian)
Influent
Parameter Wet Wt.
PCB
Na
K
Ca
Mg
As
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn
P-0
P-Total
N-TKN
N-NHs
N-N03
N-N02
Alkalinity
Chloride
COD
TOC
Grease/Oil 795 mg/Kg
Sulfate
Sulfide 71 mg/Kg
Solids-Settleable 300 ml/1
Solids-Total 125,600 mg/1
Solids 10.5 %
Centrifuged
Water
37 ug/1




84 ug/1
^2
-
72
250
100
0.2
20
6
0.39 mg/1
0.43
8.2
7.8
0.29
0.075
367 mg/1
15,800
-
11
41.5
2,000
^-0.02
_
-
Influent
Solids
Wet wt.
7.2
6.9
1.8
13.8
14.5
11
4.6
_
87
24,770
270
0.2
39
1,030
_
800
480





55,000

3,324


845
B2.fi


ug/g
mg/g



ug/g









mg/Kg






mg/Kg

mg/Kg


mg/Kg
1
                          96

-------
TABLE C-5.  ANALYSIS OF INFLUENT TO POND 1

                   Date of Sampling
              19 March 1976 (079 Julian)
Parameter
PCB
Na
K
Ca
Mg
As
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn
P-0
P-Total
N-TKN
N-NH3
N-NOs
N-N02
Alkalinity
Chloride
COD
TOC
Grease/Oil
Sulfate
Sulfide
Solids-Settleable
Sol ids -Total
Solids
Influent Centrifuged
Wet wt. Water
4.1 ug/1




117 ug/1
<2
-
48
240
78
^0.2
<10
6
0.40 mg/1
0.49
16
16
0.31
0.024
552 mg/1
16,000

19
183 mg/Kg 48
1,800
99 mg/Kg 0.08
300 ml/1
64,800 mg/1
3.2 %
Influent
Solids
Wet wt
7.7
6.2
1.5
14.1
18.3
9
3.5
-
73
24,200
121
0.5
49
480
_
792
1,230





59,100

4,110




48.4


ug/g
mg/g



ug/g









mg/Kg






mg/Kg







                         97

-------
TABLE C-6.    ANALYSIS  OF INFLUENT TO POND 1

                    Date of  Sampling
                  22 March  1976  (0830)
                        082.3
Influent Centrifuged Influent
Parameter
PCB
Na
K
Ca
Mg
As
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn
P-0
P-Total
N-TKN
N-NHs
N-NOa
N-N02
Alkalinity
Chloride
COD
TOC
Grease/Oil
Sulfate
Sulfide
Solids-Settleable
Solids-Total
Solids
Wet Wt. Water
10.6 ug/1




19 ug/1
<2
_
46
250
260
<0.2
30
8
0.45 mg/1
0.44
4.8
3.4
0.3
0.04
197 mg/1
16,200

6
147 mg/Kg 2.8
2,100
27 mg/Kg <0.02
220 ml/1
95,800 mg/1
3.8 %
Solids
Wet wt.
52.1
5.3
1.8
7.8
8.7
10
2.3
_
62
26,100
274
0.3
29
365

721
333





48,400

2,780




52. 9°/

ug/g
mg/g



ug/g









mg/Kg





mg/Kg







                           98

-------
TABLE C-7.   ANALYSIS OF INFLUENT TO POND 1

                    Date of Sampling
                  22 March 1976 (1400)
                        082.5
Parameter
PCB
Na
K
Ca
Mg
As
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn
P-0
P-Total
N-TKN
N-NHs
N-N03
N-N02
Alkalinity
Chloride
COD
TOC
Grease/Oil
Sulfate
Sulfide
Solids-Settleable
Solids-Total
Solids
Influent Centrifuged
Wet wt. Water
54 ug/1




88 ug/1
<2
-
44
270
208
<0.2
20
^2
3.1 mg/1
3.1
27
14
0.1
0.03
466 mg/1
16,300

14
1,497 mg/Kg 12
1 ,950
45 mg/Kg 0.02
800 ml /I
152,500 mg/1
12.4 %
Influent
Solids
Wet wt
51
6.
-
5.
7.
8
2.
-
63
22,200
230
0.
22
274

727
463





55,940

4,149




56.


ug/g
5 mg/g

8
0
ug/g
6




4



mg/Kg






mg/Kg






8
-------
TABLE C-8.   ANALYSIS OF INFLUENT TO POND  1

                   Date of Sampling
               23 March 1976  (083 Julian)
Influent
Parameter Wet wt.
PCB
Na
K
Ca
Mg
As
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn
P-0
P-Total
N-TKN
N-NHa
N-NOs
N-N02
Alkalinity
Chloride
COD
TOC
Grease/Oil 288 mg/Kg
Sulfate
Sulfide 28 mg/Kg
Solids-Settleable 140 ml/1
Solids-Total 54,990 mg/1
Solids 3.5 %
Centrifuged
Water
13 ug/1




14 ug/1
<2
_
52
360
340
<0.2
20
16
0.31 mg/1
0.34
3.8
3.6
0.14
0.03
158 mg/1
16,200

6
2
1,930
<0.02



Influent
Solids
Wet wt.
150
5.8
_
6.1
6.1
7.9
2.4
_
74
26,700
255
0.3
23
319

736
413




52,246

1,669



57.0


ug/g
mg/g



ug/g









mg/Kg





mg/Kg

mg/Kg



%
                          100

-------
         TABLE C-9.  ANALYSIS OF EFFLUENTS FROM POND 1
Parameter
PCB
Turbidity
As
Cd
Cr
Cu
Fe
Mn
Hg
Zn
P-0
P-Total
N-TKN
N-NH3
N-N03
N-N02
Alkalinity
Chloride
TOC
Grease/Oil
Sulfate
Effluent
4-3
094.5
ug/1 1.2
NTU 11
ug/1 16
<2
28
56
460
166
0.2
16
mg/1
0.35
-
-
-
-
mg/1
-
-
3
-
Centrifuged
Effluent
4-3
094.5
0.48
-
16
< 2
26
52
200
162
0.2
14
0.30
0.30
4.2
4.1
0.36
0.024
177
15,700
6
6
2,130
Effluent
4-4
095.5
6
21
8
< 2
24
54
540
184
0.2
24
_
0.39
-
-
-
-
-
-
-
7
-
Centrifuged
Effluent
4-4
095.5
0.39
-
14
< 2
24
60
200
176
0.2
16
0.30
0.31
4.1
4.2
0.34
0.023
179
15,700
6
5
2,150
Sulfide
Solids-Settleable ml/1       <0.01
Solids-NF, %                   .01
Solids, Total     mg/1   29,800
     0.6

29,570
                <0.02
                                   101

-------
   TABLE C-10.    ANALYSIS  OF  EFFLUENTS  FROM  POND  1
Parameter
PCB (ppb) ug/1
Turbidity NTU
As ug/1
Cd
Cr
Cu
Fe
Mn
Hg
Zn
P-0 mg/1
P-Total
N-TKN
N-NH3
N-N03
N-N02
Alkalinity mg/1
Chloride
TOC
Grease/Oil
Sulfate
r* . . i -c _• j _
Effluent
4-6
097.5
16
36
5.5
5
56
120
4,900
660
1.1
273
.
1.1
_
_
_
-

_
_
256

Centrifuged
Effluent
4-6
097.5
1.9
-
6.0
<3
25
58
175
430
0.3
48
0.27
0.28
7.2
7.1
0.33
0.022
193
15,500
12
4
1,900
Sulfide
Solids-Settleable ml/1                1.2
Solids-NF, %                         0.03
Solids, Total      mg/1           33,948
                                102

-------
TABLE C-ll.    ANALYSIS OF EFFLUENTS FROM POND  2
Parameter
PCB ug/1
Turbidity NTU
As ug/1
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn
P-0 mg/1
P-Total
N-TKN
N-NH3
N-NOo
N-N02
Alkalinity mg/1
Chloride
TOC
Grease/Oil
Sulfate
Sulfide
Solids-Settleable ml/1
Solids-NF, %
Solids-Total mg/1
Effluent
3-16
076.5
<0.08
48
9
8
_
36
4,800
1,520
0.1
10
252
_
0.19
-
-
-
-
-
-
-
5.4
-
<0.02
0.4
<0.01
20,330
Centrifuged
Effluent
3-16
076.5
< 0.08
-
3
4
_
34
740
1 .,400
0.1
10
228
< 0.01
0.01
7.5
7.2
0.36
0.02
206
8,800
16
4.1
1,200
<0.02
-
-
-
Effluent
3-19
079.5
1.1
26
5
6
_
48
1,800
1,320
< 0.2
<10
480
-
0.15
-
-
-
-
-
-
-
4.4
-
<0.02
0.2
<0.01
23,090
Centrifuged
Effluent
3-19
079.5
0.25
-
3
4
-
36
200
1,280
< 0.2
00
216
0.02
0.03
7.8
7.4
0.34
0.02
209
10,600
14
3.6
1,500
< 0.02
-
-
-
                              103

-------
TABLE C-12.   ANALYSIS OF EFFLUENTS FROM POND 2
Parameter
PCB ug/1
Turbidity NTU
As ug/1
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn
P-0 mg/1
P-Total
N-TKN
N-NH3
N-N03
N-N02
Alkalinity mg/1
Chloride
TOC
Grease/Oil
Sulfate
Sulfide
Solids-Settleable ml/1
Solids-NF, %
Solids-Total mg/1
Effluent
3-22
082.4
v 0.05
17
12
8
_
36
1,560
1,120
< 0.2
30
400
_
0.17
-
-
-
-

-
-
3.9
_
0.02
< 0.1
< 0.01
22,850
Centrifuged
Effluent
3-22
082.4
< 0.05
-
21
4
_
32
140
1,060
< 0.2
30
148
0.06
0.06
8.2
7.6
0.32
0.035
220
11,800
12
3.5
1,500
<0.02

_
-
Effluent
3-22
082.7
< 0.1
18
13
8
_
42
1,300
900
< 0.2
20
224

0.21
_
_
_
-

_
_
3.6

< 0.02
< 0.1
< 0.01
25,720
Centrifuged
Effluent
3-22
082.7
< 0.08
-
11
< 2

28
180
840
< 0.2
20
100
0.1
0.11
8.2
7.7
0.34
0.02
237
12,400
11
4.0
1 ,700
< 0.02


-
                            104

-------
           TABLE C-13.   ANALYSIS OF EFFLUENTS FROM POND 2
Parameter

PCB

Turbidity

As
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn

P-0
P-Total
N-TKN
ug/1

NTU

ug/1
mg/1
N-NOs
N-N02

Alkalinity
Chloride
TOC
Grease/Oil
Sulfate
Sulfide
Solids-Settle-
   able
Solids-NF, %
Solids-Total
mg/1
ml/1
 Effluent
  3-23
  083.4

  <0.6

  27

  19
   4

  48
,140
 840
 < 0.2
  20
 174
           0.25
           8.2
  2.6

< 0.02
  0.1
               Centrifuged
                Effluent
                  3-23
                  083.4

                  <  1.2
                   16
                  <2

                   48
                  280
                  750
                  <  0.
                   20
                   52
                    0.
                    0.
                    8.
                    7.
                    0.
       15
       15
       0
       7
       35
     0.019

   249
13,100
    11
     3.2
 1,650
   < 0.02
                    Effluent
                      4-1
                     092.5

                      2.8

                     54

                      4
                      2
                     24
                     60
                  3,600
                    740
                      0.2

                    152
0.21
           0.01
mg/1  25,990
                      1.0

                      0.01
                 27,680
            Centrifuged
             Effluent
               4-1
              092.5

               0.19
    2
  <2
   24
   52
  200
  760
  < 0.2

   70

    0.03
    0.04
    6.5
    6.8
    0.44
    0.023

  188

    9

1,930
                                         105

-------
TABLE C-14.    ANALYSIS  OF  EFFLUENTS  FROM POND 2
Parameter
PCB ug/1
Turbidity NTU
As ug/1
Cd
Cr
Cu
Fe
Mn
Hg
Zn
P-0 mg/1
P-Total
N-TKN
N-NH3
N-N03
N-N02
Alkalinity mg/1
Chloride
TOC
Grease/Oil
Sulfate
Sulfide
Solids-Settleable ml/1
Solids-NF, %
Solids, Total mg/1
Effluent
4-3
094.5
0.52
96
6
<2
28
70
14,000
1,120
0.2
-

0.43




_
-
-
_
_
-
1.8
0.01
24,500
Centrifuged
Effluent
4-3
094.5
0.29
-
0.5
< 2
20
46
180
104
0.2
-
<0.01
0.01
6.5
5.4
0.29
0.02
154
12,700
7
,_
1,680
CO. 02
_
_
-
Effluent
4-4
095.5
0.45
68
13
< 2
29
65
8,400
640
0.3
214
_
0.41
_
_
_
-

_

_
_
—
1 .4
0.01
27,560
Centrifuged
Effluent
4-4
095.5
0.22
-
0.5
<2
24
53
170
630
0.2
55
0.02
0.03
5.2
5.1
0.31
0.023
172
14,300
7

1 ,830
<0.02


-
                             106

-------
TABLE C-15.   ANALYSIS OF EFFLUENT FROM POND 2
Parameter
PCB ug/1
Turbidity NTU
As ug/1
Cd
Cr
Cu
Fe
Mn
Hg
Zn
P-0 mg/1
P-Total
N-TKN
N-NHs
N-N03
N-N02
Alkalinity mg/1
Chloride
TOC
Grease/Oil
Sulfate
Sulfide
Solids-Settle- ml/1
able
Solids-NF, %
Solids, Total mg/1
Effluent
4-5
096.5
-
36
8.
<2
25
65
4,000
730
0.2
134
_
0.26
5.2
-
_
0.1
-
-
_
-
-
-
0.1

_
28,060
Centrifuged
Effluent
4-5
096.5
-
-
1.
<2
24
42
140
600
0.3
44
0.03
0.04
5.8
5.3
0.30
0.023
175
14,400
6
-
2,000
<0.02
-

-
-
Effluent
4-6
097.5
0.80
18
3.
<4
36
58
1,890
680
0.4
105
_
0.21
5.5
-
-
-
-
-
-
122
-
-
0.2

0.01
30,410
Centrifuged
Effluent
4-6
097.5
0.47
-
0.5
3
33
50
200
640
0.3
60
0.05
0.06
5.5
5.4
0.25
0.028
184
14,600
9
13
1,850
-
-

-
-
                              107

-------
 Section III
 Post-Dredge
  Analysis
of Sediments
  at Slip 1
      108

-------
TABLE C-16.  COMPOSITION OF POST DREDGE SEDIMENT SAMPLES
                             Composite Sample from Designated Areas
Parameter
PCB
As
Cd
Cr
Cu
Fe
Pb
Mn
Hg
Zn
P-Total
N-TKN
N-NH3
Grease/Oil
PH
Sulfide
% Solids
% Volatile
COD
Eh volts

ug/g
ug/gm






ug/g

ug/g


mg/Kg

ug/g

Solids


1
50
8
1.
27
52
21,300
61
186
0.
1,390
580
-
25
2,445
7.
170
45.
8.
40,100
0.
2
10
7.3
0 3.0
-
56
16,350
109
173
2 0.5
3,270
550
820
320
4,060
5 9.1
470
4 39.5
2 10.8
45,100
026 -0.008
3
3
6.9
3.2
18
48
12,700
84
156
0.3
458
460
630
20
2,255
9.4
310
25.9
14.7
33,200
-0.166
4
2
8
9
20
82
21,200
274
215
0
2,550
540
600
15
2,035
8
190
37
10
37,500
-0
5
2
.6 9.3
.9 3.0
-
58
19,770 21
107
217
.2 0.2
650
550
660
85
1,525 1
.9 7.9
170
.9 48
.9 8.5
36,000 39
.088 0.007
6
3
6
0.8
23
44
,200
60
196
0.2
126
530
810
30
,720
7.3
180
46.1
8.9
,500
0.033
                                   109

-------
                              TABLE C-17
COMPOSITION  OF  INTERSTITIAL WATER FROM SEDIMENT SAMPLES AFTER DREDGING
                          Composite Sample from Designated Areas
Parameter
PCB
As
Cd
Cr
Cu
Fe
Mn
Hg
Zn
P-Total
Filter
Unfiltered
Filtered/He
N-TKN
N-NHs
N-N03
N-N02
TOC
Grease/Oil
PH
Conductivity
1
ug/1 260
ug/1 28
<4
32
56
10,200
2,040
ug/1 0.6
4
(mg/1)
3.0
0.96
4.3
18
12
0.10
0.200
(mg/1) 35
74
7.5
39,300 39
_ \
2
590
104
4
-
50
840
162
0.5
8

4.7
4.9
3.7
79
32
0.07
0.014
58
157
8.6
,050
3
220
180
<4
24
44
680
54
0.6
<4

0.75
0.77
0.80
76
34
0.10
0.040
29
305
9.1
33,300 37
4
75
26
C4
28
52
760 1
156 1
0.6
<4

2.1
2.0
2.0
39
12
0.12
0.120
96
278
8.2
,900 35
5
80
48
<4
_
56
,020
,520
0.3
<:4

3.5
4.8
3.6
40
12
0.25
0.150
72
87
7.7
,800
6
140
22
<4
32
56
1,860
2,280
0.8
4

0.38
0.81
0.93
35
16
0.27
0.310
50
31
7.9
34,300
                                no

-------
Section IV

  Water
 Analysis
   at
  Dredge
   and
Background
  Sites
    in

-------
       TABLE  C-18.   WATER ANALYSIS AT DREDGE AND BACKGROUND  SITES

                                 Predredge - Cruise  1
                            25 Feb. 1976 - Julian date 058
                          Dredge Site
As
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn

P-Ortho
P-Total
N-TKN
N-NHs
N-N03
N-NOz

Grease/Oil
TOC
Sulfide
ug/1
mg/1
mg/1
Fresh
Water
0.020
3.6
<1
•^2
12.
5.
620
52
0.1
11
0.08
0.15
0.42
0.30
0.49
0.009
0.4
5.
<0.02
Salt
Water
0.014
1.1
12
<2
48
4.
300
48
<0.1
<3
0.08
0.08
0.13
0.03
0.41
0.009
0.1
4.
<--0.02
                                                Background
Fresh
Water
RM-2.99
0.022
4.4
3
<2
7
2.
700
48
0.1
20
0.08
0.15
0.51
0.41
0.50
0.008
0.3
4.
<0.02

Salt
Water
0.013
0.8
9
4
41
4.
300
48
0.3
2
0.08
0.08
0.84
0.04
0.41
0.009
0.2
2.
^.0.02
Fresh
Water
RM-5.47
0.020
3.3

-------
     TABLE C-19.   WATER ANALYSIS AT DREDGE AND BACKGROUND SITES

                                   Dredge - Cruise 2
                            6 Mar. 1976 - Julian Date 066
                               Dredge Site
Parameter

PCB
Turbidity

As
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn

P-Ortho
P-Total
N-TKN
N-NH3
N-N03
N-N02

Grease/Oil
TOC
Sulfide

ug/1
NTU
Fresh
Water
0.027
2.4
Salt
Water
0.018
1.3
                                            Background
ug/1
mg/1
mg/1
          <2
          10
           4.
         460
          64
           0.

          12
 0.04
 0.11
 0.45
 0.44
 0.51
 0.008

 0.2
 3.
:0.02
             38
              6.
            310
             56
              0.
0.05
0.09
0.04
0.04
0.39
0.010
                        2.
                       :0.02
Fresh
Water
RM-2.99
0.022
2.7
Salt
Water
RM-5.47
0.014
1.4
                 1.

                 7
                 2.
               520
                72
                 0.

                10
0.04
0.11
0.49
0.48
0.51
0.008

0.2
3.
                                             1
             37
              5.
            480
             72
              0.3
 0.04
 0.09
 0.04
 0.04
 0.36
 0.011

 0.1
 3.
.0.02
                                       113

-------
      TABLE  C-20.   WATER ANALYSIS AT DREDGE AND BACKGROUND SITES

                                 Dredge - Cruise 3
                           8 March 1976 - Julian Date  068
                                                          Background
Parameter

PCB
Turbidity

As
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn

P-Ortho
P-Total
N-TKN
N-NH3
N-NOs
N-N02

Grease/Oil
TOC
Sulfide
ug/1
NTU

ug/1
mg/1
mg/1
  Fresh
  Water

  0.026
  2.3

  1.
 <2
 10
  5.
415
 73
  0.1
<10
 10

  0.08
  0.16
  0.39
  0.35
  0.52
  0.009
           3.
          <0.02
  Salt
  Water

  0.040
  1.3

  1.
 <2
 36
  8.
360
 61
  0.2
  0.08
  0.09
  0.04
  0.03
  0.41
  0.010

 CO.l
  2.
 <0.02
Fresh
Water
RM-2.99
0.011
3.1
2.
<2
3
3.
460
84
0.2
< 10
10
0.09
0.17
0.52
0.46
0.52
0.009
<0.3
3.
<0.02
Salt
Water
RM-5.47
0.024
2.0
1.
<2
33
6.
420
62
0.2
<10
< 2
0.07
0.09
0.14
0.05
0.40
0.010
0.1
2.
<0.02
                                       114

-------
       TABLE C-21.  WATER ANALYSIS AT DREDGE AND BACKGROUND SITES

                                 Dredge - Cruise 4
                         18 March 1976   Julian Date 078
Parameter

PCB
Turbidity

As
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn

P-Ortho
P-Total
N-TKN
N-NH3
N-N03
N-N02

Grease/Oil
TOC
Sulfide
ug/1
NTU

ug/1
mg/l
mg/1
Fresh
Water

0.036
2.0
          9
         19
        410
         67
          0.

         14
0.09
0.15
0.40
0.40
0.47
0.009

0.1
5
0.02
                       Salt
                       Water

                       0.034
                       1 .0
            30
            46
           390
            68
             0.2
0.08
0.09
0.06
0.04
0.40
0.009
Fresh
Water
RM-2.99
0.021
2.2
Salt
Water
RM-5.47
0.007
1.6
                       4
                      .0.02
                            2
                          <2
                           10
                           16
                          450
                           62
                            0.2
                         
-------
      TABLE C-22.   WATER ANALYSIS AT DREDGE AND BACKGROUND SITES

                                 Dredge - Cruise 5
                          22 March 1976 - Julian Date 082
                                 Dredge Site
Parameter

PCB
Turbidity

As
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn

P-Ortho
P-Total
N-TKN
N-NHs
ug/1
mg/1
N-N02

Grease/Oil
TOC
mg/1
Fresh
Water
0.021
1.8
2
<2
9
11
430
53
0.4
^~\ n
< 1 U
9
0.09
0.15
0.34
0.26
0.40
0.008
0.4
4
Salt
Water
0.021
1.1
2
^ 2
31
40
380
65
0.2
< 2
0.06
0.12
0.22
0.12
0.39
0.008
0.2
3
                                           Background
Fresh
Water
RM-2.99
0.014
1.3
Salt
Water
RM-5.47
0.013
0.6
                                         8
                                        12
                                       440
                                        62
                                         0.
                                      -clO
                                        22
0.08
0.17
0.43
0.37
0.39
0.009
0.
4
  1
            36
            44
           320
            64
             0.
          = 10
             6
0.06
0.10
0.07
0.03
0.39
0.006

0.1
3
                                       116

-------
        TABLE  C-23.  WATER ANALYSIS AT DREDGE AND BACKGROUND  SITES

                                   Dredge - Cruise 6
                            23 March 1976 - Julian Date 083
                              Dredge Site
Parameter

PCB
Turbidity

As
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn

P-Ortho
P-Total
N-TKN
N-NH3
N-N03
N-N02

Grease/Oil
TOC
ug/1


ug/l
mg/l
mg/1
Fresh
Water
0.140
1.6
3
<2
9
16
460
54
-. 0.2
12
0.09
0.16
0.44
0.35
0.40
0.010
0.3
4
Salt
Water
0.460
3.2
5
< 2
31
36
490
56
0.2
7
0.06
0.10
0.09
0.04
0.39
0.007
0.3
4
Background
Fresh
Water
RM-2.99
0.016
2.0
3
x: 2 <
8
12
Salt
Water
RM-5.47
0.010
0.7
3
2
34
36
540 400
54
<' 0.2
<~\Q <
26
0.08
0.15
0.40
0.34
0.40
0.010
0.1 <:
5
54
0.2
10
6
0.06
0.09
0.06
0.04
0.39
0.007
0.1
3
                                          117

-------
      TABLE  C-24.  WATER ANALYSIS AT DREDGE AND BACKGROUND SITES

                              Post Dredge - Cruise 7
                           20 April 1976 - Julian Date 111
                               Dredge Site
Parameter

PCB
Turbidity

As
Cd
Cr
Cu
Fe
Mn
Hg
Ni
Zn

P-Ortho
P-Total
N-TKN
N-NOs
N-N02

Grease/Oil
TOC
ug/1
mg/1
mg/1
Fresh
Water
0.009
2.3
^
6
17
330
47
0.4
_
19
0.09
0.15
0.38
0.36
0.33
0.008
0.3
4
Salt
Water
0.006
1.8
1
<2
28
54
310
36
0.6
35
4
0.06
0.08
0.10
0.04
0.34
0.010
0.2
3
Background
Fresh
Water
RM-2.99
0.009
2.8
<1
<2
6
14
Salt
Water
RM-5.47
0.007
2.1
2
<2
28
60
400 360
52
0.6
30
16
0.09
0.16
0.48
0.38
0.33
0.007
0.2
4
36
1.0
_
6
0.06
0.09
0.10
0.04
0.34
-
x O.l
3"
                                       118

-------
     Section V

 Exchange Analysis
    and Exchange
Capacity of Sediments
     and Solids
           119

-------
                            TABLE C-25.  EXCHANGE CAPACITY OF SEDIMENTS AND SOLIDS
ro
o
    Parameter
Sediment from Slip 1 Site
Solids from Influent
Solids from Pond #2 Effluent
Cation Exchange Capacity
Wet wt . , ug/g
Dry wt., ug/g
Meq/100 g ( dry wt . )
Exchangeable Ammonium
Wet, mg NH^-N/Kg
Dry, mg NH^-N/Kg

105-40
16310
70.9

30.4
47

8410
16090
70.0

5
10

9290
20230
88.0

56
122

-------
TABLE C-26. SEDIMENT-EXCHANGE ANALYSIS
            SEDIMENT FROM SLIP 1 SITE
Parameter
Concn.
ug/g
K wet
dry
Ca wet
dry
Ha wet
dry
Mg wet
dry
Fe wet
dry
Ni wet
dry
Mn wet
dry
Cu wet
dry
Cr wet
dry
Cd wet
dry
Zn wet
dry
As wet
dry
Hg wet
dry
Pb wet
dry
Sediment NH^OAc HOAc Extract HONH2 Ex- l^Cb + HNO'3 H202+HN03
Extract of of MH^OAc tract of Digest NH^- Digest HN03
Sediment Extracted HOAc Ex- OAc + HNC>3 Extract of
Sediment tracted Extract of HONH2 Sed.
Sediment HONHp Sed.
2311
13300
20600
10390
178150"
10300
15960
24000
37150
22
34
303
470
51
78~
-
-
< 0.9
<1.4
147
227
7.3
11.3
0.19
0.29
67
103
1004
1550
1180
1500
4067
5300"
2000
2500
8.6
13.4
0.5
18
2F
0.2
0.3
0.06
0.10
<0.01
<0.02
0.4
0.7
0.10
0.15
~
0.4
0.7
119
205
3970
222
JSO
500
TBTJ
3500
5000
2.4
4.1
50
8£
0.2
0.3
0.8
1.4
<0.04
<0.07
13
23
<0.08
<0 . 14
—
1.0
1.7
52
94
960
1700
27
43"
100
130
840
1500
0.8
1.5
11
20
0.1
0.2
0.5
1.0
< 0.04
<0.07
8.3
15
< 0.08
<0.14
•~
1.3
2.3
152
275
3910
7100
283
510
4200
7500
5100
9200
8.7
71
123"
28
51
_9.8_
18"
0.4
0.78
48
0.43
0.78
~
23
42
159
28T
3710
293
530
2800
5100
5400
"9800
9.9
69
125
40
72
9.6
17
0.7
1.32
51
105"
2.5
4.5
—
30
55
HF+HN03 HF + HN03
Digest Digest of
of NHOAc HNC>3
+ HN03 Extract
4934
6900
8810
16000
11010
20000
6200
11000
18900
34000
31
~%~
187
333
26
48
23
42
< 0.2"
< 0.40
55
99
3-96
7.1
—
33
5780
10400
10960
9300
17000
6200
11000
10000
18000
32
219
39&
27
49
24
43
< 0.17
< 0.30
68
123
2.66
~
37

-------
                                    TABLE C-27.
SEDIMENT-EXCHANGE ANALYSIS

   SOLIDS FROM INFLUENT
ro
PO
Parameter
Concn.
ug/g
}f
Ca
Na
Mg
Fe
Mi
.Yii
Gu
Cr
Cd
Zn
As
TCT
- -o
Pb
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
viet
dry
wet
dry
wet
dry
wet
dry
wet
dry
viet
dry
wet
dry
wet
dry
wet
dry
Sediment NH^OAc Ex-
tract of
Sediment
1874
3530"
9660
18470
12000
21390
9900
1^40
25100
48030
29
55
209
400
78
150
-
-
2.9
5.5
319
509
7.9
15.1
0.35
0.6₯
109
20~8~
819
1570
1440
2800
4720
9000
1900
3500
253
483
0.
1.
6
12
0.
0.
<0.

-------
TABLE C-28.  SEDIMENT-EXCHANGE ANALYSIS
             SOLIDS FROM POND 2 EFFLUENT
Parameter
Cone .
ug/g
K
Ca
Na
Mg
Fe
Ni
coMn
Cu
Cr
Cd
Zn
As
Hg
Pb
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
Sediment
1308
2850
7580
16520
13270
25470
8900
19400
37400
81600
35
77
203
440
79
171
-
-
6.2
13.4
500
1090
19
41
0.47
1.02
164
356
NH40AC
Extract
of
Sediment
396
362
1220
2700
3474
7500
1500
3300
1.5
3.3
2.8
5
11
0.3
0.1
0.2
0.02
0.05
4.0
4.0
7.1
—
0.35
0.77


HOAc Extract HONH2 Ex-
of NH^OAc tract of
Extracted HOAc Ex-
Sediment tracted
Sediment
53
96
1510
2700
165
300
1100
2000
3700
6500
8.5
15
50
91
14
26
1.4
2.5
3.1
5.5
324
585
<0.08

-------
                         TABLE C-29
LOSS OF METALS FROM A DE-IONIZED WATER RINSE OF SEDIMENTS AFTER
               AMMONIUM ACETATE AND ACID EXTRACTIONS
Parameter
Cone.
ug/gm
K

Ca

Na

Mg

Fe

Ni

Mn

Cu

Cr

Cd

Zn

As

Pb

wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
wet
dry
Sediment Sediment
from Slip 1 from Slip
After NH^OAc 1 After
Extraction HOAc Extn
0
0
75
117
502
780
70
103
0
0
<0
<0
0
0
0
0
< 0
< 0
< 0
< 0
0
0
0
0
<0

-------
       Section VI
Miscellaneous Materials
            125

-------
                                   TABLE C-30
                                Sample Collection
                                     Scheme
                            Influents and Effluents
     Date
Julian   Gregorian
             Influent
                                             Effluent
                               Pond 1  Pond 2
                        Area of
                    Dredge Activity
76.4
76.5
79.4
79.5
82.3
82.4
82.5
82.7
83.3
83.4
92.5
93 to 98
3-16
3-16
3-19
3-19
3-22
3-22
3-22
3-22
3-23
3-23
4-1
4-2 to 4-7
X

X

X

X

X




X

X

X

X

X
X
X
5, 6

3

3.

1, 2

1 (at spill


Solids from high








site )


speed
94.5
95.5
96.5
97.5
                                                                  centrifugation of 500 1
                                                                  effluent
4-3
4-4
4-5
4-6
X
X

X
X
X
X
X
                                          126

-------
     TABLE C-31.   SEDIMENT EXCHANGE  FLOW DIAGRAM
                               SAMPLE
                                  I
                       Centrifuge  and  separate

                                  •	> Interstitial water (discard)
                                 V
                               RESIDUE
                                  I
                             (1)   NH^OAc
                             (2)   Centrifuge and separate
          NH^OAc EXTRACT
            (Analyze)
HOAc EXTRACT  tr
  (Analyze)
           HONH2 EXTRACT
             (Analyze)
                              RESIDUE
                                  I
                             (l)   Wash with deionized water
                             (2)   Centrifuge and separate
                                            DEIONIZED WATER WASH (Analyze)
                              RESIDUE
                             (1)  HOAc
                             (2)  Centrifuge and separate
                                 V
                              RESIDUE
                                  I
                             (l)   Wash with deionized water
                             (2)   Centrifuge and separate
                                  !
                              RESIDUE
                                 > DEIONIZED WATER WASH  (Analyze)
                             (1)  HONH2
                             (2)  Centrifuge and separate
                              RESIDUE
(1)  H202 +  HNOo  digest
(2)  NH^OAc  +  HN03
(3)  Centrifuge and  separate

     NH^OAc +  HN03
     EXTRACT 4r	
     (Analyze)
                    V
                   RESIDUE
               HF  +  fuming HN03
                  digest
                    ^
                DIGESTED SAMPLE
                  (Analyze)
                                   !l)  H202  + HN03 digest
                                   ;2)  HN03
                                   [3]  Centrifuge and separate

                                              HN03
                                          	> EXTRACT
                                              (Analyze)
                                       \/
                                       RESIDUE

                                   HF + fuming HN03
                                      digest
                                       •4?
                                   DIGESTED SAMPLE
                                     (Analyze)
                                127

-------
Appendix D

-------
                             APPENDIX D
     Using "Predredge Analysis of Sediment at Slip 1" data, found in
Appendix C, Section I, and formulae "A", "B", and "C" shown below,
it is possible to predict the amount of pollutant released from 0.2 1.
of sediment via  the "Standard Elutriate Test" and "interstitial water
monitoring".  Also, an estimate of the amount of a pollutant in 0.2 1.
of sediment considered for dredging may be made in a similar manner.
     (A)  Shake Test

          Amount of Pollutant
          Released per  0.2 1.
          Sediment

     (B)  Interstitial Water

          Amount of Pollutant
          Released per  0.2 1.
          Sediment

     (C)  Sediment

          Amount of Pollutant
          in 0.2 1.  sediment
= (Cone, poll.) ((1  l.)-(0.2 1.  X % sol.  by Vol))
=  (Cone,  poll.)  (0.2 1.)  (100-% sol.  by  vol.)
= (Cone,  poll.)  (0.2 1.)  (Density  sed.)
          % solids by volume = volume solid (after centrifugation)
                               Volume sediment (before centrifugation)

          where:

               Volume solid (after centrifugation) = difference  between
          volume sediment (before centrifugation)  and volume  of  water
          obtained from centrifugation of sediment at 9,000 RPM  for  20
          minutes.

     The results of these calculations are found in Tables  D-l through
D-5.  In order to estimate the total  pollutant burden for the dredge
sediment or predict the amount of pollutant to be  released  via the
"Standard Elutriate Test" or by "interstitial  water monitoring", it  is
necessary to know the volume of sediments to be dredged.   The volumes
may be calculated by estimating the area to be dredged within each of
six sample areas of Slip 1 (see Figure D-l) and using an  estimated dredge
depth of one foot.  The total  dredge  volume is found by summing  the
volumes calculated for each area (see equation D).
                                   129

-------
     (D)  vTotal  = VT  + V2 + V3 + V4 + V5 + V6

          vTotal  = (3'30° + 2'200 + 1'100 + 30° + l

          vTotal    10'000 yd-3

     The amount of a pollutant to be released during dredging of each
area may be predicted using the above volumes along  with the amount of
pollutant released via each  predictive test (see Tables D-l through
D-5) and equation "E".  It follows that the total  amount of pollutant
predicted to be released for the whole dredge operation is  given by the
sum of amounts predicted to be released from each area.

     (E)

        Amount of pollutant
        predicted to be                                                        3
        released  or total     (Amount of Poll.) (3.79 1) (202 gal)  (Vol.  in yd.  )
        pollutant burden of      0.2 1.  sed.       gal        yd.^
        dredge sediments

The pollutant burden of the dredged sediments for each area and the area
taken as a whole   is  calculated in a similar manner.   Results of calculations
for pollutant sediment burden and amounts predicted  to be released  for each
predictive test by area are found in Tables D-6,  D-7 and D-8.

     The amount of each pollutant returning to the river from pond  2 may
be estimated using measured pumped volumes of pond 2 water  (see Table D-9)
and pond 2 effluent data found in Appendix C, Section II.   The amount of
pollutant present in dredge return water due to river water dredged with
Slip 1  sediments  was established using pumped volumes of pond 2 water (see
Table D-9) and the average pollutant concentration found in the saline
river water background site during the dredge (see Appendix C, Section IV).
Totals  of each pollutant in Tables D-6, D-7 and D-8,  along  with estimated
amounts of each pollutant returning to the river with pond  2 water  (both
corrected for contribution of each pollutant present in the river water
and uncorrected)  are summarized in Table 16 found in the body of the text.
                                130

-------
                Table D-l.   RESULTS OF PREDREDGE ANALYSIS SLIP 1  COMPOSITE  #1
Metals
As
Cd
Cr
Cu
Fe
Pb
Mn
Hg
Ni
Zn
Elutriate
Test ug/1
16.2
4.0
45
6.0
560

2,880
0.1
OO
12.
Amt. Rel.
200 ml . sed
in uq/0.2 1
14.1
3.5
39.2
5.2
488

2,508
0.09
<8.7
10.4
. Int. H20
. uq/1
21.2
6.0
15
6.0
4,000

1,640
0.4
OO
38.
Amt. Rel.
200 ml . sed.
in ug/0.2 1 .
1.5
0.4
1.1
0.42
283

116
0.03
<0.71
2.7
Sed.
wet wt.
ug/g
7.8
0.51
21
39.0
25,100
44
250
0.1
15
110
Total in q/0.2 1
2.12 X 10~3
1.39 X 10-4
5.71 X 10'3
1.06 X 10"2
6.8
1.2 X 10"2
6.8 X 10"2
2.7 X 10~5
4.1 X 10~3
3.0 X 10"2

PCB
Oil /Grease
Total P
N-NH^
TKN
COD
158
1.9 X 10+3
0.11 X 10+3U
3.3 X 10+3
4.5 X 103
360
138
1.7 X 10+3
0.10 X 10+3U
2.9 X 10+3
3.9 X 103
313
1,700
_
3.320 X 10+3U
1.8F
9. X 10+3
12 X 103
490
120
_
.2350 X 10+
.13F
.64 X 10+3
0.85 X 103
34.7
72
715
^ 590
14
630
28,200
2.0 X 10"2
1.9 X 10"1
1.6 X 10"1
3.8 X 10"3
1.7 X 10"1
7.67
U - unfiltered           Density =1.36 g/ml.
F - filtered             % Solids by volume =  64.62%
                                             131

-------
                 Table D-2.   RESULTS  OF  PREDREDGE  ANALYSIS  SLIP  1  COMPOSITE #2
Amt. Rel.
Elutriate 200 ml . sed.
Metals Test uq/1 in uq/0.2 1.
As 12.2 10.7
Cd 8.0 7.0
Cr 43 38
Cu 7.2 6.3
Fe 300 264
Pb
Mn 1,320 1,162
Hg 0.1 0.09
Ni <10 <8.8
Zn 20 18
Amt. Rel.
Int. H20 200 ml . sed.
uq/1 in uq/0.2 1 .
32.3
4.0
34
7.2
410

1,920
0.1
<10
00
2
0
2

33

154
0

-------
               Table D-3.   RESULTS OF PREDREDGE  ANALYSIS  SLIP  1  COMPOSITE #3 & 4
Metals
As
Cd
Cr
Cu
Fe
Pb
Mn
Hg
Ni
Zn
Elutriate
Test ug/1
15.9
4.0
43
3.6
240

224
0.2

-------
                Table D-4.  RESULTS OF PREDREDGE ANALYSIS SLIP 1  COMPOSITE #5
Metals
As
Cd
Cr
Cu
Fe
Pb
Mn
Hg
Ni
Zn
Elutriate
Test ug/1
6.9
4.0
47
18
260

1,920
0.6
<10
8.0
Amt. Rel .
200 ml . sed.
in ug/0.2 1 .
6
3
42
1
230

1,700
0
(8
7
.1
.5

.6



.5
.9
.1
Int.
ug/1
20
6
44
9
8,400

5,280
1
<10
74
Amt. Rel.
H20 200 ml . sed.
in ug/0.2 1 .
.4 1
.0 0
3
.6 0
716

450
.0 0
<0
6
.74
.5
.8
.82
24


.09
.9
.31
Sed. wet
wt. ug/g
5.3
2.83
22
51.7
,500
67
240
0.1
10
610
Total
in
g/0.2 1.
1
7
6
1

1
6
2
2
1
.44
.70
.0 X
.40
6.
.8 X
.52
.7 X
.7 X
.65
X 1
o-3
X 10~4
10
X 1
66
10
-3
o-2

-2
x io"2
10
10
X 1
-5
-3
o-1

PCB
Oil /Grease
Total P
N-NHs
TKN
COD
13
3.0 X 103
.24U
.19 X 103F
2.2 X 103
3.0 X 103
270
12
2.7 X 1
0
0.17 X
1.9X1
2.7 X 1
239

o3
.21U
103F
O3
O3

85

3
0.26
5.5
12 X
430
7

.94U 0
X 103F 0.
X 103 0.
103 1.
36
.2

.336U
02 X lO^F
47 X 103
02 X 103
.7 20
0.82
700
540
23
580
,900
2
1
1
6
1

.23
.9 X
.5 X
.3 X
.6 X
5.
X 1
10
10
10
10
68
o-4
-1
-1
-3
-1

U = unfiltered
F = filtered
Density = 1.36 g/ml.
% Solids = 57.38
                                               134

-------
                 Table D-5.   RESULTS OF PREDREDGE ANALYSIS  SLIP 1  COMPOSITE  #6
Metals
As
Cd
Cr
Cu
Fe
Pb
Mn
Hg
Ni
Zn
Elutriate
Test ug/1
11.7
4
47
9.0
540

3,360
0.1
<10
4.
Amt. Rel.
200 ml sed.
in uq/0.2 1 .
10.5
3.6
42
8.0
483

3,003
0.09
<8.9
3.6
Int. H20
ug/1
26.5
4
48
9.0
40,000

9,760
0.1
oo
10.
Amt. Rel.
200 ml. sed.
in ug/0.2 1 .
2.48
0.37
4.5
0.8
3,750 18

906
0.009
<0.9
0.9
Sed. wet
wt. ug/g
6.4
0.57
15
31.5
,300
440
183
<0.1
<10
120
Total in
q/0.2 1.
1.74 X 10"3
1.55 X 10'4
4.1 X 10"3
8.57 X 10"3
4.98
1.20 X 10"1
4.98 X 10"
2.7 X 10"5
<2.7 X 10"3
3.3 X 10"

PCB
Oil/Grease
Total P
N-NHs
TKN
COD
8
1.2 X 103
• 12U
.065 X 103F
3.0 X 103
5.0 X 103
C250
7.1
1.1 X 103
.11U
0.058 X 10T
2.7 X 103
4.5 X 10
<223
51
_,
1.36U
.20F
8.2 X 103
12 X 103
340
4.8
m
0.127U ~
0.02 X 10T
.77 X 103
1.1 X 103
31.8 26
1.0
361
510
69
480
,200,
2.72 X 10"4
9.8 X 10"2
1.4 X 10'1
1.9 X 10"2
1.3 X 10"1
7.13
U = unfiltered
F = filtered
Density = 1.36 g/ml.
% Solids = 53.13%
                                            135

-------
               Table D-6.   AMOUNT OF POLLUTANT PRESENT IN DREDGE SEDIMENTS*
Area
As
Cd
Cr
Cu
Fe
Pb
Mn
Hg
Ni
Zn
PCB
Oil &
Grease
Total P
N-NHs
TKN
COD
1
26,700
1,750
72,000
134,000
86,000,000
151,000
860,000
340
52,000
380,000
252,000
2,394,000

2,016,000
48,000
2,142,000
97,000,000
2
16,000
3,000
83,000
93,000
49,000,000
522,000
545,000
220
34,000
690,000
17,000
1,684,000

1,180,000
38,000
1,520,000
65,000,000
3 & 4
11,000
7,200
29,000
86,000
31 ,000,000
123,000
3-26,000
145
32,000
1,242,000
3,400
1 ,600,000

750,000
22,000
700,000
42,000,000
5
6,600
3,500
28,000
64,000
31,000,000
83,000
300,000
125
12,000
760,000
1,000
874,000

690,000
29,000
740,000
26,000,000
6
12,600
1,100
30,000
62,000
36,000,000
870,000
362,000
200
20,000
240,000
2,000
712,000

1 ,020,000
138,000
950,000
52,000,000
Total
72,900
16,550
242,000
439,000
233,000,000
1,749,000
2,393,000
1 ,030
150,000
3,312,000
275,400
7,264,000

5,656,000
275,000
6,052,000
282,000,000
Results expressed in grams
                                             136

-------
                   Table  D-7.   PREDICTED  RELEASE  BY ELUTRIATE TEST*
Area
As
Cd
Cr
Cu
Fe
Pb
Mn
Hg
Ni
Zn
PCB
Oil/Grease
Total P

N-NHs
TKN
COD
1
178
44
494
66
6,150
5,050
31,600
1.1
no
131
1,740
21,420
U 2,500
F 1,260
37,000
49,000
3,940
2
90
59
320
53
2,220
2,960
9,800
0.8
75
152
220
56,400
U 5,900
F 2,900
28,800
43,000
2,670
3 & 4
77
19
210
17
1,160
2,165
1,080
1.0
48
10
145
64,300
U 3,900
F 2,500
12,300
23,000
1,265
5
28
16
195
7
1,060
1,795
7,820
2.3
41
33
55
12,400
U 970
F 780
8,740
12,400
1,100
6
76
26
305
58
3,510
1,690
21,800
0.7
65
26
52
8,000
U 800
F 420
19,600
32,700
1,620
Total
449
164
1,524
201
14,100
13,660
72,100
5.9
no
309
2,212
162,520
14,070
7,860
106,440
160,100
8,975
* Results expressed in grams

U = unfiltered
F - filtered
                                           137

-------
             Table D-8.  PREDICTED RELEASE BY INTERSTITIAL WATER MONITORING*
Area
As
Cd
Cr
Cu
Fe
Pb
Mn
Hg
Ni
Zn
PCB
Oil /Grease
Total P

N-NH3
TKN
COD
1
19
5
14
5.3
3,570
360
1,460
0.4
9
34
1,510

U2,960
Fl,640
8,060
10,700
440
2
22
2.5
23
4.9
280
190
1,300
0.1
7
7
97
-
U3,030
Fl,200
7,500
12,000
260
3 & 4
11
2.1
23
2.5
100
140
120
.2
5
1
78
-
Ul,500
F720
3,270
8,600
140
5
8
2.3
17
3.8
3,300
170
2,100
.4
4
29
33
_
Ul,550
F90
2,160
4,690
170
6
18
2.7
33
5.8
27,300
250
6,600
0.1
7
7
35
_
U920
F145
5,600
8,000
230
Total
78
14.6
no
22.3
34,550
1,110
11,580
1.2
9
70
1,753
_
9,960
3,795
26,590
43,990
1,240
* Results expressed in grams
U (Jnfiltered
F Filtered
                                        138

-------
Table D-9.  FLOW VOLUMES OUT OF POND 2 VS DATE
Sample
12503
12611
12617
13626
13636
14604
15610
15616
15620
15625

Date
3-16-75
3-19-76
3-22-76
3-22-76
3-23-76
4-1-76
4-3-76
4-4-76
4-5-76
4-6-76

Gallons
481,000
239,000

981 ,000
543,000
4,788,000
1,488,000
378,000

936,000
Total 9,834,000
                    139

-------
                                     (I) DISTANCES IN
                                       FEET
                                         SPECIFIED DREDGING
                                         BOUNDARY
                                         ACTUAL DREDGING
                                         BOUNDARY
                                          Scale in Feet
                                           100   200   300
OVERVIEW  OF COMPOSITE SAMPLING
                 AREAS AT SLIP 1
                                                     FIGURE D-l

-------
Appendix E

-------
                             APPENDIX E
     The amount of PCB in pond 1  may be estimated using survey data
supplied by the Corps of Engineers Seattle District and results of
PCB analysis of composite pond 1  samples taken by EPA personnel.
Results of EPA analysis are found in Table 22.

     An estimate of the total volume of dredge spoils in pond 1 may
be made in the following manner.   Pond 1 was divided into three areas
(AI, A2, and A3) shown in Figure E-l.   The volume of spoils for each
area of pond 1 was calculated using survey results found in Figure 6.
The total volume (Vj) was obtained by summing the volumes of each area

     Vy = Vi + V2 + V3

     Vi = Via (top) V]b (bottom)

     Vl =
     Vl = 2  (110 ft.)2 (7.5 ft.) + 2  (110 ft.)2 (5 ft.)
      1         3 (4)4
     Vi = 47,500 + 95,000 = 142,500 ft.3

     V1 = 5,280 yd.


     V2 = h wlh

     V2 = (0.5) (65 ft.) (120 ft.) (4 ft.)

     V2 = 15,600 ft.3

     V2 = 580 yd.3
     V3 = wlh

     V3 = (65 ft.) (180 ft.) (3 ft.)

     V3 = 35,100 ft.3

     V3 - 1,300 yd.3
                                   o            3
     VT - (5,280 + 580 + 1,300) yd.  = 7,160 yd.
                                   142

-------
     The total  volume of spoils  calculated for pond 1  appears to be
less than that  removed from Slip 1  (see Appendix D).   The difference
(10,000 yds.3 - 7,200 yds.3 = 2,800 yds.3) is  significant.   Since the
volume of spoils of pond 1  calculated in this  appendix is based on a
land survey, it is assumed  to be accurate.  It is possible  that either
the estimated area dredged  in Slip  1  (see Appendix D)  or the average
depth of dredge could be in error and therefore give  rise to the
calculated difference.  But it is known that an attempt was  made to
dredge only the top portion of the  sediments in Slip  1.   Of  course,
this represents the lighter more flocculent fraction  of the  sediment
which may be expected to compact readily upon  dewatering.  Indeed,
this was the case.  Analysis of  land survey results just after dredging
but before dewatering indicate a greater volume of spoils in pond 1.
Using this post dredge survey data  (See Figure 6), the actual volume of
spoils in pond  1 at the end of the  dredge operation is estimated to be
9,400 yd.3.

     Vl = 2  (110 ft.)2 (8  ft.)  + 2  (110 ft.)2 (7 ft.)
       1          3~~{l1                     4
     V] = 50,685 ft.3 + 133,050  ft.3 = 183,735 ft.3

     V1 = 6,805 yd.3


     V2 = (0.5) (65 ft.) (120 ft.)  (6 ft.) = 23,400 ft.3

     V2 = 870 yd.3


     V3 = (65 ft.) (180 ft.) (4  ft.)  = 46,800  ft.3

     V3 = 1,730 yd.3


     Vj = Vi +  V2 + Vs

     VT = (6,805 + 870 + 1,730)  yds.

     VT =    9,400 yd.3

This is in agreement with the estimated volume of sediment  found in
Appendix D.

     Therefore, it appears  that  approximately  10,000  yds. of material
was dredged from Slip 1 and placed  in pond 1.   After dewatering and
standing for several months, the spoil volume  decreased to  approximately
7,200 yds.3 (a  28% reduction in  volume).  The total PCB burden of pond 1
                                 143

-------
was calculated using the results of the land survey taken after the
spoils were allowed to stand and dewater.

     The total PCB burden (PCB total) can be expressed as a function
of PCB concentration and pond 1  volume in the following manner.  The
amount of PCB in the individual  areas is calculated using the PCB con-
centrations for each area and volumes of each area.  The total PCB
burden is then obtained by summing the amounts of PCB calculated for
each area.

     PCB Total = (PCB)] V-| + (PCB)2 V2 + (PCB)a Va

     (PCB)i Vi =('145 X 10-6 ib.  PCB\  1 gallon PCBV90 Ib. sed.\[142,500 ft.3.'
           1   '  v      Ib. sed.     A n.5 ib. PCB.A ft.-* sed. /
     (PCB)i V] = 160 gallons

     (PCB)? V? + (PCBh Vq = f30 X IP"6 Ib. PCBW 1 gal. PCB y/90 Ib  sed.\C50.700
     v   it v2   \r  ,3 vj   I   lb_ sed>       j( 11>5 lb PCBK  ft.j sed.)

     (PCB)2 V2 + (PCB)3 Vs = 10 gallons

     (PCB) Total = 160 + 10 = 170 gallons

The total amount of PCB found in pond 1 by this method is estimated to be
170 gallons.
                                   144

-------
FIGURE E-1
           INLET PIPE

                                EXIT WEIR

                  	BOUNDARY LINES

                  	 WATER LINE
             AREAS OF HOLDING POND USED
       TO  CALCULATE VOLUME  OF DREDGE SPOILS

-------
Appendix F

-------
                              Appendix F



                           HydroLab Results





     Water quality parameters temperature,  dissolved oxygen (DO),



pH and conductivity of Pond 2 effluent were monitored continuously



during the dredge operation.   Daily averages of each are plotted versus



Julian date in Figures F-l  and F-2.  Temperature,  DO, pH and conductivity



are expressed in °C, ppm, standard pH units and micromhos respectively.



Even though the instrument was calibrated daily, occasional  instrument



problems necessitated deletion of some data.
                                    147

-------
      FIGURE F-1
  50 -
  40 -
o
o
o
  30 -
O
X


O
Of.
u
20 -
  10 -
                                                                           O
                                             HARD DATA


                                             EXTRAPOLATION
    MARCH 15
                                     MARCH 25
APRIL 4
                         CONDUCTIVITY-EFFLUENT POND 2

-------
FIGURE F-2
g	|
                HARD DATA
              - EXTRAPOLATION
              D TEMPERATURE, DEGREES CENTIGRADE
              0 DISSOLVED OXYGEN, PARTS PER MILLION
              O pH, pH UNITS
	1	
MARCH 25
 MARCH 15
	T
APRIL 4
   TEMPERATURE, DISSOLVED OXYGEN AND pH - EFFLUENT POND 2

-------