-------

-------
     \       UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
      8                       REGION 6
     f                1445 ROSS AVENUE, SUITE 1200
                         DALLAS, TX 75202-2733


              EXPLANATION OF SIGNIFICANT DIFFERENCES
INTRODUCTION

Site  name  and  location

PAB Oil  and  Chemical Services,  Incorporated
Abbeville, Louisiana

Identification of lead agencies and support agencies

Lead:      U.S.  Environmental Protection Agency (EPA)
Support:   Louisiana  Department  of Fnvironmental Quality (LDEQ)

Citation of CERCLA Section 117fcl and NCP Section 300.435rd m(i)

This  Explanation of  Significant Differences  (ESD)  is prepared  in
fulfillment  of EPA's public participation  responsibilities  under
Section  117(c)   of   the  Comprehensive  Environmental  Response,
Compensation,  and Liability Act of  1980  (CERCLA),  42 U.S.C.  §
9617(c), which provides that after adoption of a  final remedial
action plan,  if any remedial  action, enforcement action, settlement
or consent decree under section  106  or Section 122  of  CERCLA  is
entered into, and if such action, settlement, or decree differs in
any significant respects from the final  plan, the lead agency shall
publish an explanation of significant differences and the reasons
such  changes  were  made.    Moreover,  pursuant to the  National
Contingency  Plan (NCP), 40  C.F.R.  Part  300,  EPA  is  required  to
publish  an ESD  when,  after  adoption of the  Record  of Decision
(ROD), the remedial  action  or enforcement action  taken, or the
settlement or  consent decree entered into,  differs significantly
from  the  remedy  selected   in  the  ROD  with  rpspect  to  scope,
performance, or  cost (40 C.F.R. S 300.435(c)(2)(i)).

Summary of the circumstances that gave rise to the need  for an ESD

On September 23, 1993, EPA  issued  a ROD which  presented the EPA
selected remedy  for the PAB Oil site clean up. The selected remedy
includes excavation and biological treatment for contaminated site
soils  and sludges  followed by  solidification/stabilization  of
biologically treated residues and disposal of treated residuals in
an onsite disposal unit.

On September 27, 1994, pursuant to Section 106  of CERCLA, 42 U.S.C.
S 9606,  EPA  issued a  Unilateral Administrative Order (UAO)  to  a
number of Potentially Responsible Parties (PRPs) directing them to
perform the  remedial design and remedial action.  A group of PRPs
known  as  PAB  Site   Remediation Group,  L.L.C.,   has  undertaken
     Rccyctod/ftocyclable • Printed with Vegetable Oil Based Inks on 100% Recycled Paper (4O% Postconsumer)

-------
additional  site investigations and treatability  studies,  and is
preparing preliminary plans and specifications for implementation
of the selected remedy.  In the course of conducting these predesign
studies, data has been collected using  new EPA-approved laboratory
procedures  not  previously available during Remedial Investigation
and  Feasibility Study  (RI/FS)  activities.  This  data  shows that
implementation  of  the biological treatment  step  of  the selected
remedy  is  not  necessary  since  the  concentrations  of  organic
pollutants  in  the  site soils and sludges are below  the remedial
action objectives  (RAOs)  for  biological treatment established in
the ROD.

Statement that the  ESP will become  part of  the Administrative
Record File

This document presents only a  summary of the  changes to the remedy
and a synopsis  of  available information on  the site.  Pursuant to
the  requirements  of  Section  300.825(a) (2)  of the  NCP,   40  CFR
§300.825(a)  (2),  this  BSD will become  part  of the Administrative
Record for the  PAB Oil site.

Address of  locations where the file  is available and hours of
availability of the file

U.S. Environmental Protection Agency
1445 Ross Avenue
Dallas,  Texas   75202
(214) 665-6427
Monday - Friday 8 a.m. to 4:30 p.m.

Louisiana Department of Environmental Quality
7290 Bluebonnet Road
Baton Rouge, Louisiana 70809
(504) 765-0487
Monday - Friday 8 a.m. to 4 p.m.

Vermilion Parish Library
200 North Street
Abbeville, Louisiana 75010
(318) 893-2674
Monday - Friday 8a.m. to 5 p.m.
Saturday 9 a.m. to 4 p.m.

SUMMARY OF  SITE  HISTORY,  CONTAMINATION PROBLEMS, AND SELECTED
REMEDY

Site history and contamination problems

The PAB Oil site  is  located  approximately  three miles north of
Abbeville,  Louisiana,  adjacent  to U.S.  Route 167  in Vermilion
Parish (Figure 1).  The site encompasses approximately 16.7  acres of
land located in a rural  area. The site was used for the disposal of

-------
                  f        .

                    /zs '^ •;.-,,.•""
                                          2 Ğ •'	 ^ ^
                              	 i.:.: *
                                                              '^^-i-^^^^^^^^^.-^f^'^^' - ••-
                                                           *j ^ *ğ-==     ^—"'^  k    - —
                                                         SITE LOCATION MAP
                                                   PAB OIL AND CHEMICAL SERVICES, INC
                                                       VERMILION PARISH, LOUISIANA
REFERENCE JSGS 7 5 MINUTE TOPOGRAPHIC QUADRANGLE MAPS OF
        L-IROY AND MILTON. LOUISIANA. DATED 1983

-------
oil and gas exploration and production wastes,  including drilling
muds, drilling fluids and produced waters, from 1979 to 1983. The
site  consists  of three  impoundments or  pits  which  were  used to
receive drilling wastes. Another impoundment,  referred to as the
saltwater pond, was used to receive produced waters.  Because of its
inability to meet the requirements of statewide order 29-B and lack
of funds for a  proper closure, Pab Oil went out of  business in 1983
and the  site was abandoned. The  site  was added  to the National
Priorities List  (NPL) by EPA in March 1989.

EPA conducted the RI/FS between January 1991 and March 1993. All of
the contaminants  found  at  the  site  are  related to drilling muds,
drilling fluids,  produced water and other associated wastes such as
workover fluids and tank bottoms.  Contaminants detected  in the pit
soils/sludges,  pond sediments,  and surface water include petroleum
hydrocarbons such as ethylbenzene,  fluorene, methylnaphthalene,
phenanthrene, toluene,  and  xylene and heavy metals  such as arsenic,
barium, chromium, copper, lead, and zinc.
                                  \
Selected remedy,  as described in the ROD

The major components of the selected remedy include the following:

 • Excavation and onsite biological treatment  of organic
   contaminated sludges, soils, and sediments;

 • Solidification/stabilization of biologically treated residuals
   to address inorganic contamination (metals) and,  if necessary,
   any remaining organic contaminants;

 • Final disposal of treated residuals in an  onsite disposal unit;

 • Placement of a compacted clay cover over  the disposal unit;

 • Removal and onsite treatment of all surface water with final
   discharge to site drainage ditches;

 • Long-term ground water monitoring; and

 • Long-term site operation and maintenance.

DESCRIPTION OF  SIGNIFICANT DIFFERENCES  AND THE  BASIS  FOR THOSE
DIFFERENCES

Information that gave rise to significant differences

The Baseline  Risk  Assessment,  dated January 1993,  was  used to
establish the following RAOs in the ROD  for  site  clean  up:

 • Arsenic - less than 10 parts per million  (ppm)
 • Barium - less than 5400 ppm
 • Carcinogenic Polynuclear Hydrocarbons (cPAHs) - less than 3 ppm

-------
   as benzo(a)pyrene (BAP) equivalent
 • Polynuclear Hydrocarbons (PAHs) - less than or equal to 1 Hazard
   Index  (HI)

Because of limitations in laboratory procedures  at that time (i.e.
prior to  1991),  the  RI  activities  could not determine whether or
not  the  actual  cPAHs  and  PAHs  concentrations  of site  soils,
sludges, and sediments were above or below the RAOs. Instead,  the
laboratory data  showed  only nondetect values of  less  than 15 to
less  than 58  ppm  for  cPAHs  and  PAHs in  the site media.  To be
conservative,  the  Risk  Assessment  and  FS estimated  that cPAHs
concentration  was about  20  ppm as  BAP equivalent (about half the
average detection limit and substantially above  the  RAO value of 3
ppm) and the  PAHs hazard  index was about 400. Therefore, biological
treatment was  selected  as  the remedy in  the ROD  to  reduce  the
concentrations of cPAHs  and PAHs to acceptable levels.

The predesign  investigation activities conducted in 1993 and 1995
by the  PRPs  used revised EPA analytical  techniques  (EPA method
8270-A,  revised in 1993) for the determination of PAHs and cPAHs.
Site sludges, soils,  and  sediments sampling results have shown that
the cPAHs concentration is well below  (less than 1 ppm) the RAO of
3 ppm as  BAP equivalent. Also, the PAHs  concentrations are well
below the hazard index of 1.  Therefore,  biological treatment is
unwarranted since the site soils,  sludges, and sediments PAHs and
cPAHs concentrations are  well below the  RAOs  established  for
biological treatment.

Description of the significant differences between the remedy as
presented in the ROD and the action now proposed

Original ROD Remedy

The 1993 ROD selected the following remedy:

 • Excavation and onsite biological treatment of organic
   contaminated sludges, soils, and sediments;

 • Solidification/stabilization of biologically treated residuals
   to address  inorganic  contamination  (metals) and, if necessary,
   any remaining organic contc>minants;

 • Final disposal of  treated residuals in an onsite  disposal unit;

 • Placement of a compacted clay cover over the disposal unit;

 • Removal and onsite treatment of all surface water with  final
   discharge to site drainage  ditches;

 • Long-term ground water monitoring; and

 • Long-term site operation and maintenance.

                                5

-------
Modified Remedy

Extensive sampling of site soils,  sludges,  and sediments conducted
during 1993 and 1995 has  indicated that concentrations of cPAHs and
PAHs are well below the RAOs and therefore  biological treatment is
not necessary. The  following is the modified remedy:

 • Excavation and onsite solidification/stabilization of site
   soils, sludges,  and sediments containing arsenic and
   barium above RAO  levels of 10 ppm and 5400 ppm, respectively.
   Also an organiophilic clay must be used in the
   solidification/stabilization mix to chemically stabilize organic
   compounds contained in the wastes;

 • Disposal of treated residuals in an onsite disposal unit;

 • Placement of a compacted clay cover over the disposal unit;

 • Removal and onsite treatment, jf all surface water with final
   discharge to site drainage ditches;

 • Long-term ground water monitoring; and

 • Long-term site operation and maintenance.

The modified remedy is similar to the 1993 ROD remedy except that
biological treatment is not a component of the modified remedy.

SUPPORT AGENCY COMMENTS

Louisiana Department  of  Environmental Quality  has  reviewed this
ESD. The State's acceptance of this ESD can be found in
Attachment l.

AFFIRMATION OF THE STATUTORY DETERMINATIONS

Considering the  new information that has  been  developed and the
changes  that have  been made  to  the selected  remedy, the EPA
believes that the remedy  remains protective of human health and the
environment, complies with Federal and State requirements that were
identified as applicable or relevant and appropriate in the ROD and
at  the time  tğvs  ESD  was signed,  and  is cost-effective.   In
addition, the revised  remedy  utilizes  permanent  solutions and
alternative   treatment  technologies   to  the   maximum  extent
practicable for this site.

PUBLIC PARTICIPATION ACTIVITIES

The requirements of CERCLA Sections 113(K)(2)(B)(i-v)  and 177,  42
U.S.C. SS 9613(K)(2)(B)(i-v) and 9617, were met  as  illustrated  in
the following discussion.

-------
   In December 1996,  the Remedial Project Manager  met  with  the Mayor
   of Abbeville,  Police  Jury representatives, the Parish Sheriff,  the
   City Fire Marshall, and the Vermilion  Association  to  Protect  the
   Environment (VAPE) Technical  Assistance Grant  (TAG)  advisor  to
   explain the proposed change to the remedy, obtain  their input to
   the proposed change,  and to inform them that  EPA would be holding
   an open  house in Abbeville in mid January  1997 to  explain  the
   proposed change and to obtain  citizen  comments.  The  response  was
   very positive  and  there were no objections to the proposed change.

   A Superfund Site Update.Fact Sheet on  the proposed change to  the
   remedy was  mailed to the citizens on January 6, 1997. An open house
   was held in Abbeville on January 16,  1997 to  explain the proposed
   change to the  remedy, answer  questions, and to  solicit comments
   from community members. Also, a 2-week  comment period (from January
   16th through  3lst,  1997)  was  provided. The community  commented
   through its TAG  advisor (Attachment  2) stating that it  had  no
   objection to the  proposed change provided that  solidification  and
   stabilization  is  conducted  ex-situ.
t\  Regional  Administrator


   Date

-------
Attachment 1

-------
                                    COMPANY
3008 SOUTHWEST DRIVE • SOUTHWEST INDUSTRIAL PARK • P.O. BOX 9813 • NEW IBERIA, LA 70562-9813 • (318) 367-2216
                                                    "•  ; •-•• '-J U/-C\
                                      January  21,  1997
    M. S. Ramesh (6SF-LL)
    Remedial Project Manager
    US EPA,  Region 6
    1445 Ross Avenue
    Dallas,  TX  75202-2733

    Re:   PAB Superfund Site - Remedy Change

    Dear Mr.  Ramesh:

          Or behalf of Vermilion Association to Protect the
    Environment  (VAPE),  I would like to offer the following comments
    in response  to the PAB change in remedy.

          The second step of the remedial process was #2  Excavation
    and  on s*te  biological treatment for soils and sludges to degrade
    organics such as naphthalene and xylene.  With the removal of
    biological treatment the excavation phase should still be
    required.

          The sludges and soils should  be required  to be  excavated,
    stabilized with an appropriate solidifying agent to bind the
    organic  fraction of the waste,  and solidified with appropriate
    materials to address the heavy metals.

          Excavation in ex-sites solidification  should  be required.
    This would enable complete removal of contaminated sludges and
    soils from the waste impoundments areas.  This  is an  important

-------
                                    COMPANY
3008 SOUTHWEST DRIVE • SOUTHWEST INDUSTRIAL PARK • P.O. BOX 9813 • NEW IBERIA, LA 70562-9813 • (318) 367-22^6

    requirement  to insure appropriate removal  and treatment prior to
    the treated  and solidification waste being placed back in the
    impounded areas for  final  disposal.

           If additional  information is required, please contact me.
    Thank you for  the opportunity to participate in this process.

                                      Sincerely,

                                      \O 
-------
Attachment 2

-------
          , .T-.V ;r> ;:•••.•• ••-.•",-••: ).
          :<. ....-• .•..,,• •
Stabilization/           f';
Solidification of
CERCLA and RCRA Wastes

Physical Tests, Chemical
Testing Procedures,
Technology
Screening, and
Field Activities

-------
 lized waste. II the unstabilized,product is soil-like and
 the stabilized product is cement-like, there should be
 a marked increase in the  Unconfined Compressive
 Strength (10 to 20 psi).

 4.5.2 Unconfined Compresslve Strength of
 Cylindrical Cement Specimens (ASTM 01633-84)

 For stabilized cement-like wastes, the Unconfined
 Compressive Strength test can provide several pieces
 of useful information, including the following:

       The ability of the stabilized waste to with-
       stand overburden loads.

       The optimum water/additive ratios and
       curing times for cement setting reactions.

       The improvement in strength characteristics
       from the unstabilized to the stabilized waste.

 This test also is often conducted  on  samples sub-
 jected to durability tests (Subsection 4.6).

 4.5.2.1  Test Description

 The test is completed on a cylindrical  sample of the
 materials (ASTM  D1632-87).  It can  be completed
 with two different cylinder height-to-diameter ratios:
 1.15 and 2.0 (Methods A and B). The cylindrical test
 specimen must be cured for a specified time in a room
with 100 percent humidity.  Typical curing times for
cement are 1, 7,  14, and 28 days.  The age of the
 tested sample should be noted.

The two height-to-diameter ratios cause several dif-
ferences in testing and in  results.   Method A  uses
equipment  more readily available in soil-testing labo-
 ratories; however, this test method may lead to more
complex stress conditions  during crushing.  There-
fore, Method A gives a relative measure of strength
 rather than a rigorous determination as found in Method
 B.  Method A normally yields a higher compressive
 strength than an identical sample tested by Method B.
 Although no cons.stent preferences in test methods
 are noted in the literature, comparisons in Unconfined
 Compressive Strength should only be completed for
 samples tested by the same method.

 The testing apparatus is commonly called a "Com-
 pression Testing Machine." The machine may take
 on several forms, but most  important, it must be able
 to control the rate at which load (stress) is applied.
 The machine has an upper and lower plate, and the
 sample is placed upright (long axis vertically) on the
 lower plate.

 The upper plate is lowered and brought into contact
 with the sample. Load is added continuously without
 shock by a screw.  A sample fails when it loses its
 physical integrity by falling apart.  The  total load at
 failure of the test specimen is recorded to the nearest
 10  pounds of force.  The Unconfined Compressive
 Strength is the ratio of force applied at failure to the
 original cross-sectional area of the cylinder, usually
 expressed in pounds per square inch (psi).  Uncon-
 fined Compressive Strength  is often  expressed  in
 other units. Table 4-3 presents conversion factors for
 the more common units.

 In its methods description, ASTM reports that the
 average strength difference of two duplicate samples
 is 8.1 percent. The samples should be tested by the
 same person to give the maximum precision when
 interpreting the failure of the sample.

 4.5.2.2  Interpretation and Application of Results

 The EPA considers a stabilized/solidified material with
 a strength of 50 psi to have a satisfactory Unconfined
 Compressive Strength  (USEPA OWSER Directive,
 No. 9437.00-2A).  This minimum guideline of 50 psi
 has been suggested to provide a stable foundation for
 materials placed upon it, including construction equip-
 ment and  impermeable caps and cover material.  A
 study by Stegemann et at. (1988) reported Uncon-
fined Compressive Strength values for 69 stabilized/
 solidified wastes ranging from 10 to 2900 psi.

The minimum  required  Unconfined  Compressive
 Strength for a stabilized/ solidified material should be
evaluated on the basis  of the design loads to which
the material will be subjected. The anticipated over-
 burden pressure and other loads, along with appropri-
 ate safety factors, can be used to calculate this.

 Typical construction and compaction equipment can
 generate very high contact pressures of 1000 psi or
 more (e.g.. sheepsfoot rollers), but  surface contact
 pressures on the order of 50 to 100  psi are more
 common.  This surface  load is attenuated with depth
 so that bearing pressures are reduced to values on
 the order of 10 to 20 psi at a depth of 2 feet and 3 to 7
 psi  at a depth of 5 feet below grade.  Overburden
 pressures will usually be on the order of 0.75 to 1.0
 psi  per foot of depth.  If guidelines such as these are
 used, the stresses to which the stabilized/solidified
 waste will be subjected can be predicted, and design
 criteria can be selected accordingly.

 Martin et al  (1987) suspect that one-dimensional
 compressibility  may  be a more useful  indicator of
 mechanical stabilization/solidification in some situ-
 ations than is Unconfined Compressive Strength. The
 one-dimensional  compressibility  test  (e.g., ASTM
 02435-80) allows a prediction of fluid expulsion dur-
 ing  consolidation and  evaluation of cover support.
 For stabilized/solidified waste forms that are relatively
 soft or ductile, this test can provide useful perform-
 ance information; however, for stiff, cement-like, sta-
 bilized/solidified waste, the Unconfined Compressive
 Strength with a  rational design criterion  is probably
: I

i
                                                4-13

-------