United States                   EPA- 600 ' 8~ 87-027
            Environmental Protection
            Agencv                      Julv 1987
&EPA     Research and
            Development
            DEVELOPMENT AND DEMONSTRATION

            OF INDOOR RADON REDUCTION MEASURES

            FOR 10 HOMES IN CLINTON, NEW JERSEY
            Prepared for
            Office of Radiation Programs
            Prepared by
            Air and Energy Engineering Research
            Laboratory
            Research Triangle Park NC 27711

-------
                  RESEARCH REPORTING SERIES


Research reports of the Office of Research and Development, U.S. Environmental
Protection Agency, have been grouped into nine series. These nine broad cate-
gories  were established to facilitate  further  development and  application  of
environmental technology. Elimination of traditional grouping was consciously
planned to foster technology transfer and a maximum interface in related fields.
The nine series are:

     1.  Environmental Health Effects  Research

     2.  Environmental Protection Technology

     3.  Ecological Research

     4.  Environmental Monitoring

     5.  Socioeconomic Environmental Studies

     6.  Scientific and Technical Assessment  Reports (STAR)

     7.  Interagency Energy-Environment Research and Development

     8.  "Special" Reports

     9.  Miscellaneous Reports

This report has been assigned to the  SPECIAL REPORTS series. This series is
reserved for reports which are intended to meet the technical information needs
of specifically targeted user groups. Reports in this series include Problem Orient-
ed Reports, Research Application Reports, and Executive Summary Documents.
Typical of these reports include state-of-the-art analyses, technology assess-
ments, reports on the results of major research and development efforts, design
manuals, and user manuals.
                        EPA REVIEW NOTICE

This report has been reviewed by the U.S. Environmental Protection Agency, and
approved for publication. Approval does not signify that the contents necessarily
reflect the views and  policy of the Agency, nor does mention of trade names or
commercial products  constitute endorsement or recommendation for use.
This document is available to the public through the National Technical Informa-
tion Service. Springfield, Virginia 22161.

-------

-------
                                  ABSTRACT
    In the spring of 1986, the New Jersey Department of Environmental Protec-
tion located a cluster of homes with extremely high radon levels in the town
of Clinton, New Jersey.   Research Triangle Institute was contracted to develop
and demonstrate radon reduction techniques in 10 of these homes.  The work was
to be completed before the 1986-87 winter heating season began.
    The demonstration homes were selected from among 56 homes in the subdivi-
sion of Clinton Knolls.   All of these homes had shown radon concentrations in
excess of 64 pCi/1 when monitored in the spring of 1986.  Each of the homes
was inspected and a representative sample of 10 homes was selected for the
radon reduction demonstration project.
    Following intensive diagnostic work and monitoring in each of the homes, a
rs.don reduction plan was developed.  With the agreement of the homeowners,
installation of radon reduction systems was carried out during the summer of
1986.  All of the 10 homes had radon concentrations reduced significantly by
the fall of 1986.  The average cost of radon reduction was $3,127.
                                     11

-------
                              TABLE OF CONTENTS

Section                                                                   Page

       List of Figures [[[   V
       List of Tables .................. . ..................................
  1.0  Introduction [[[   1

  2.0  Background. ... .............................................. .......   2

  3 . 0  Selection of Demonstration Homes ........... . .......................   3

  4.0  Diagnostic Procedures . Used Prior to Radon Reduction ................  24
       4. 1     Radon Grab Sample Measurements ............... .' .............  26
       4.2     Qualitative Measurements of Soil Gas Entry .................  27
       4.3     Characterization of Subslab Aggregate ......................  27
       4.4     Measurement of House "Tightness" ...........................  28
       4 . 5     Whole House Fan Test .......................................  32
       4.6     Investigations of Negative Pressure Induced on
               Basements ..................................................  32
       4.7     Simulation of Winter Conditions ............................  35
       4.8     Increasing Makeup Air ......................................  43

  5.0  Radon Monitoring ...... -. ............................................  47
       5 . 1     Continuous Radon Monitoring ................................  47
       5.2     Charcoal Canister Monitoring ...............................  47
       5 . 3     Monitoring Conditions ......................................  52
       5.4     Control Homes ..............................................  54

  6 . 0  Development of Radon Reduction Plans ...............................  60

  7 . 0  Installation of Radon Reduction Measures ...........................  63
       7 . 1     Installation Materials .....................................  63
       7.2     Estimate of Installation Costs .............................  63
       7.3     Diagnostic Proceudres used Following Radon Reduction
               Efforts ........... ... .............. . . ......................  68

  &. 0  Quality Assurance ....................................... _ ..........  69
       8.1     Quality Assurance Objectives for Passive Scintillation
               Cell Radon Monitoring ......................................  69
       8.2     Quality Assurance Objectives for Charcoal Canisters ........  77
       8 . 3     Systems Audits .............................................  78
       8.4     Seasonal Indoor Radon Variations ...........................  78
       8.5     Control Homes ..............................................  79

  9 . 0  Results and Conclusions ............................................  81

-------
                        TABLE OF CONTENTS (continued)

Section                                                                    Page

       9.2     House C30A	   81
       9.3     House C39A					..   81
       9.4     House CA6A	...	.	   95
       9.5     House C10B.........	....	..		   95
       9.6     House C31B......	   96
       9.7     House CA9B	.'...   96
       9.8     House C33C	   96
       9.9     House C32D	   96
       9.10    House C24E	   97

  10.0 Recommendations	   98

       REFERENCES	   99

APPENDIXES

   A   Radon Reduction Plans	A-i

   B   Homeowner Permission Form.	 B-l
                                    IV

-------
                             LIST  OF FIGURES


Number                                                                  Page

  1    Houses selected for radon screening	«	   4

  2    Floorplan "A"	   6

  2    Floorplan "B"	   7

  2    Floorplan "C" and "D"	   8

  3    Pre-selection site survey checklist	   9

  4    Estimates of  air infiltration rates by home using four different
       models	  29

  5    Radon  concentration vs. air  exchanger rate for Clinton homes	  30

  6    Radon  concentration vs. air  infiltration rates for Clinton
       homes	  31

  7    Effect of whole house fan use with all windows open, on radon
       concentration	  33

  8    Fan flow curve for House C48B	  34

  9    Premitigation radon concentration, House C48B	  37

 10    Premitigation radon concentration, House C48B and Control
        House C31B	  38

 11    Premitigation radon concentration, House C30A	.	  39

 12    Premitigation radon concentration, House C33C	•	  41

 13    Premitigation radon concentration, House C8A	  42

 14    The effect on radon concentration of producing a heat
       differential  to simulate winter conditions	  44

 15    PRO #123 response to  temporal variations	  48

 16    PRO #124 response to  temporal variations	  49

 17    PRD #125 response to  temporal variations	  50

 18    PRD #127 response to  temporal variations	  51

-------
LIST OF FIGURES (continued)
Number
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35

Premitigation monitoring results for House C48B and control
Ambient radon concentrations, Hebgen Park Monitoring Station,


C-i n-vr ,...•-._ j_r,,. AR-S #255 PRD #125 	
Pal •f'krat-i'nn data- AR-5 #258 PRD #127 	 	 	 	

House C30A: pre- and post-mitigation reduction results. ...«*...«

House C46A: pre- and post-radon reduction results 	 	

House C31B: pre- and post-radon reduction results 	 »....
House C48B: pre- and post-mitigation reduction results, .........
House C33C: pre- and post-radon reduction results. ..............
House C32D: pre- and post-radon reduction results 	 	
House C24E: pre- and post-radon reduction results. ..............
Page
,. 53
. 57
. 59
73
74
75
76
82
83
84
85
86
87
88
89
90
. 91

-------
                               LIST OF TABLES


Number                                                                    Page

   1     Clinton Radon Levels	 ...	       5

   2     Assessment Summaries—Clinton	      12

   3     Distribution of Homes Included in Radon Screening by
         Floorplan	      22

   4     Distribution Homes Selected for Demonstration.....	      23

   5     Pressure Difference Measurements for Two Homes	      45

   6     Control Homes Paired with Demonstration Homes	      55

   7     Summary of Radon Reduction Plans	      61

   8     Standard Parts Used in Installation of Radon Reduction
         Systems	      64

   9     Cost of Radon Reduction Installations	      65

   10    Quality Assurance Objectives....	      70

   11    Passive Scintillation Cell Radon Monitor Calibration
         Constants	.	      71

   12    Charcoal Canister Quality Assurance Samples	      72

   13    Approximate Reduction in Radon Concentrations Using
         Charcoal Canister Data Following Application of
         Radon Reduction Techniques (pCi/1)	      80

   14    Radon Concentrations as Determined with Charcoal Canisters...      92
                                        vu

-------
                              1.0  INTRODUCTION

    The discovery of high indoor concentrations of radon gas in the Reading
Prong area of New Jersey, New York, and Pennsylvania, and in other locations
in the United States, has raised serious concerns about a large number of
people being exposed to the radioactive gas.  In response, the U. S. Environ-
mental Protection Agency (EPA) issued a guidance booklet, "A Citizen's Guide
to Radon:  What It is and What to Do About It" (EPA, 1986a).  EPA guidelines
recommend initiating corrective action in homes with radon concentrations in
excess of 4 picocuries per liter (pCi/1), or 148 Becquerels per cubic meter,
of air.  At radon concentrations of 200 pCi/1, temporary relocation is recom-
mended.
    In the early spring of 1986, a preliminary survey of homes in Clinton, New
Jersey, conducted by the New Jersey Department of Environmental Protection
(DEP), identified more than 50 homes with indoor radon concentrations greater
than 100 pCi/1 in the subdivision of Clinton Knolls.  Many of these homes had
radon concentrations of 600 pCi/1 or higher.
    The primary purpose of the work described in this report was to develop
and demonstrate cost-effective radon reduction techniques in 10 representative
Clinton Knolls homes.  Radon reduction measures were to be completed before
the beginning of the 1986-1987 heating season to keep the exposures of
residents to a minimum.  Additional data were collected to add to the general
body of information on radon transport and its control in homes; however, this
data collection was secondary to the pressing need to demonstrate effective
radon reduction techniques by the Fall.

-------
                               2.0  BACKGROUND

    The subdivision of Clinton Knolls is located near the center of  the  town
of Clinton, New Jersey.  The neighborhood is dominated by frame houses with
floorplans of approximately 139 m2 (1500 ft2).  This uniformity is due to
development of the subdivision by a single builder.  Some custom-built homes,
similar in style and size to the developer-built homes, are scattered among
those built by the prime contractor.  While most of the houses are approxi-
mately 18 years old, many of the 56 volunteer homes that were surveyed were
still occupied by their original owners, making this neighborhood a  stable
one.
    The development is built on a dolomitic limestone hill that rises above
Main Street and ends at the edge of an abandoned quarry.  The hill crests at
the interior streets of the subdivision with bedrock rising to the surface in
the area.   Several homeowners  reported that the bedrock beneath their homes
had to be  blasted before basements could be built or before sewer lines could
be placed.  Residents  also  reported the appearance of sinkholes throughout the
neighborhood where the formation of underground caves had caused the earth to
subside.

-------
                    3.0  SELECTION OF DEMONSTRATION HOMES

    One hundred three homeowners who had participated in the DEP radon  survey
in March and April of  1986 were asked to volunteer their homes for the  radon
reduction demonstration effort.  Fifty-six of the homeowners who volunteered
were selected for screening.  Figure 1 demonstrates the proximity of the 56
homes participating in EPA's radon screening effort and Table 1 shows the
range of radon concentrations among the 103 homes participating in the  DEP
radon survey.
    Three basic floorplans repeated throughout the subdivision are reproduced
from the original developer's promotional brochure in Figure 2.  In addition,
a small number of diverse floorplans built by independent contractors were
also investigated.  For the purposes of this report, the floorplans have been
assigned the following letter designations:
    •   Split level with half basement (combination of slab-on-grade
        and block basement)                                           - A
    •   Bi-level  (slab-below-grade)                                   - B
    •   Two story with no basement (slab-on-grade)                    - C
    •   Two story with basement (concrete block basement)             - D
    •   Independent builder floorplans (variety of substrates)        - E
    During a one week period, each of these homes was investigated t>y a diag-
nostic team of EPA and RTI personnel.  Figure 3 reproduces the checklist that
was used to assess each of the homes.  The objective of EPA's home screening
effort was to characterize the pool of homes and select  10 homes as repre-
sentative of the Clinton housing stock which could be used to demonstrate
radon reduction measures.  Table 2 is a summary of findings; Table 3 shows the
distribution of survey houses by floorplan.  Selection of 10 demonstration
homes from among the volunteers homes was done using the criteria below:
    •    The ability to identify and to access the location of radon entry
         into the house.
    •    The ease of worker access to the home during the workday.
    •    The ability to reduce radon levels in the home with few
         potentially unknown factors affecting the outcome, such as
         fireplaces, woodstoves, etc.

-------
    xxxxxx
                                   Participated in
                                   EPA radon screening
Figure 1. Houses selected for radon screening.

-------
                   TABLE 1.  CLINTON RADON LEVELS
 Concentration                 No. of Houses                % of Sample
    pCi/1
  >2048                               2                          1-9
1024-2047                             3                          2.9
 512-1023                            13                         12.6
 256-511                             17                         16.5
 128-255                             17                         16.5
  64-127                             12                         11.7
  32-63                              12                         11.7
  16-31                              14                         13.6
   8-15                               5                          A.9
   4-7                                6                          5.8
   <4                                 2                          1.9

-------
            '  I  '  '	LL  Family Room
            	Kitchen  (J   15'x14'
             Lavl14'9"x10'10"
              Garage
            20'x10'4"
                              Down
               Bedroom

                12* x 9'
        Bath/
                       klE
               Bedroom
             12'8"x12'8'
 Dining
 Room   Foyer

1Vx11' Ic
        I    ^
                           Portico
Down
                                         Living Room

                                         18'4"x13'
                                  c \  C
                Bedroom
                12'xir
Source: Clinton Knolls subdivision advertising brochure


                       Figure 2-a.  Floorplan "A"

-------
Recreation Room
  20'4"x 11'6"
                T
                          Laur
 Garage
23'4" x
       Bedroom \
                 Storage
                 11*6" x
Source:  Clinton Knolls subdivision advertising brochure
             Dining
              Room
             9'0" x
              10'0"
 Kitchen
 13'6" x
 10'0"

IT
                                                                      Bath1!
                                                                     Bath
                                                                             Bedroom
                                                                           14'8"x 11'
                                                                                 C  I C
            Living Room
            8'4"x 11*3"
                                                            UpDn
                       u
        Bedroom |C| Bedroom
         10'2"x
          9'0"
                                   Figure 2-b. Floorplan "B".

-------
Dining Room
25'4" x 13'4"
Living Room
I P I
Kit Dinette
^ 21 '4" x 9'0"
PanM D|
— I
C , Family Room
	 18'0" x 15*8"
Up

Laundry
n
i — ' —
Garage

Bedroom
1VO"x
10'0"
Hfltn urBss ** i
. i Bedroom
\I TWalkT 15'0"x
IB| | inC 1T6"
C T Hall Dn '
Bedroom ~~ /
I3'4"x11'8" c C Bedroom
j-L 15'8" x 10'0"

Storage
Source:  Clinton Knolls subdivision advertising brochure
                                   Figure 2-c. Floorplan "C" and "D'

-------
Survey Crew Members
                              General  Instructions

     Thia checklist  is  designed  to ensure that each house is thoroughly
evaluated.  FILL  IN  ALL SPACES ON  THIS CHECKLIST.  All sketches, notes, and
»easure»ent results  should  be recorded in the field notebook along with the
house address and survey number, date, time,  and names of the crew members.


I. Sketch a floor plan  of the house.   Also provide a sketch of the house
elevation.  If a  house  lacks one of the features listed then write MNA" in the
space provided.   Otherwise  sketch  the dimensions of the Basement and/or Crawl
Space.  Check off each  item as it  is  completed.


     	 Floor plan

          	 Basement

          _„_, Crawl Space

          	 Fireplace(s)  and  Chimneys

          	 Stairwell(s)

          	 Bathrooms

          ______ Overall  floor plan  dimensions  (length x width)

          	 Basement dimensions (length x  width)

     	 Elevation

     	 Interior block walls

     	 Structures penetrating basenent slab

     	 Exterior slabs: patios

     	 Exterior slabs: attached garage



                        Figure 3. Pre-selection site survey checklist.

-------
II.  Provide a detailed sketch of the Basement  and/or Crawl Space.  Check off
each item as that ha« been included or write  "NA"  if it ia not present.

     	 Sump pump

     	 Floor drain .

          Windows/vents

     	 Pipe penetrations

     	 Cracks in floor/walls

     ____ Outside door to basement

     ____ Crawl apace door to inside


III.  Miscellaneous Information.  Answer as indicated or write "NA" if the
question is not appropriate.

Is the basement finished? 
-------
IV.  Measurement checkliat.   Check  off each measurement as it is taken or
write "NA" if not applicable.   Record the tine and location of each
measurement in the field notebook.

Integrated Samples  (Charcoal  canniaters/bags)

     	 Basement

     	 Crawl Space

     	 Living/Family Room
Grab Samples

     Air samples  (Scintillation  cells)

          	  Sump  pump

          _rm_ja_  Floor drain

          	  Wall/Floor cracks

          ____  Crawl space

          	  Other:   	   	
     Working  Level  measurements (Filter samples)

          _     Sump pump

          	  Floor drain

          	  Wall/Floor cracks

          _____  Crawl space

                Other:
                                 Figure 3 (continued)
                                       11

-------
                                        TABLE 2.  ASSESSMENT SUMMARIES—CLINTON
         Radon
      concentration
        lowest
House    f'loor     Number    Number of
nniiihor  (|>CI/I)   of adults   smokers
                                Number and ages
                                  of children         Type
                                           Features
CIU'
C2A
160
103
           89
16.  19
18.  20
                                  17. 14. 10
two-story colonial,
no basement

split level with
basement—
unfinished

bl-level
                                                                        standard
sump with pump; attic fan; open
block-plaster
                                      has photos of house being built;
                                      block halfway up front and one
                                      aide;  good access to block wall
                                      from closet; water closet leak;
                                      negative pressure hot air furnace/
                                      dryer/bath fan upstairs; thermal
                                      bypass-kitchen soffits/chimney/
                                      bath chase (tub); pipe penetra-
                                      tions with wood stakes
C4A 676 3 0 0 split level-
unfinished
C5D 114 2 0 15. 13 bl-level
<:<>A 25S 2 0 0 split level



addition over patio; many cracks
poured concrete floor
concrete block; whole house fan
eight months In house; many wall
cracks and floor/wall seam/floor
cracks; some open blocks/poles
(support); no sump at floor draii
In





n
    <; denotes Clinton study
    number (1-56) denotes assigned project number
    letter (A-K) denotes floor plan
                                                                                                    (continued)

-------
TABLE 2.  ASSESSMENT SUMMARIES—CLINTON (continued)
House
number
C7E
C8A
C9B
C10U
c 1 1 it
C1D2
ciai;
Radon
concentration
lowest
floor Number Number of Number and ages
(pCl/1) of adults smokers of children
250 2 0 6. 9
791 2 0 6, 7, 10. 13
186 2 1 6
418 2 0 0
250 2 1 0
608 2 0 12, 9
lf)T> 2 1 0
Type
bl-level
split level —
finished
bl-level
bl-level
bl-level
colonial with
basement —
unfinished
other-multilevel —
finished with
crawlspace
Features.
homeowner capable of doing variation
remediation work has repaired rotted
sill; all at grade level
basement finished but owner willing
to remove wall paneling, etc.
standard
owners both work — willing to vacate
house to have work done
block front; wood stove In family
room; closet access to block
whole house fan; several large
cracks and openings; coal stove;
bedrock In northeast corner of lot
woodstove; all abovegrade; slab
poured against 4 Inch block;
2 ft x 3 ft chase at head of
bathtub
                                                                           (continued)

-------
                                  TABLE 2.  ASSESSMENT SUMMARIES—CLINTON (continued)
         nation
      concenlrutlun
        lowest
House    floor     Number
number  (pCl/1)   of adults
Number of    Number and ages
 snokers       of children         Type
                          Features
CHI)      437
C15E      411
TlfiE      495
               6. 10
                                bi-level
bl-level, but
not Lackland;

other, finished
basement
coal stove In basement;   penetration
(water plpe/tollet/perlraeter crack)-
closet access to 1/2 block wall;
negative pressure (furnace/dryer/
bath fan/coal stove); bypasses:
whole house fan/chlnney/kltchen
soffit/bath chase; stone wall behind
brick surround  for coal stove

owners scheduled to relocate soon;
block wall to grade

standard
C17A      150
               4.5
split level with
unfinished basement
basement entry  from  first-level  garage
penetrations:   open  blocks  (1/2).
Jackposts,  cracks  In floor,  two  oil
lines;  negative pressure-boiler/
dryer/chimney bypass/whole  house fan;
AC  In  attic; may be  easy to isolate
attic
                                                                                                              (continued)

-------
                                  TABLE  2.   ASSESSMENT  SUMMARIES—CLINTON  (continued)
         Rndon
      conconlrutlon
        lowest
House    floor     Number    Number of
number  (pCi/1)   of adults   smokers
                               Number  and  agea
                                 of children          Type
                          Features
CI8A
79
CI9A      163
C2AO      150
          122
          101
split level on
slab, no basement
                                 17.  16.  13.  7




                                 19,  17.  8


                                 1.  4




                                 18.  14
split level,
partially finished
basement
split level with
basement

split level with
basement
slab on grade; penetrations:  main
In laundry/outside faucet from
bath/two toilets; dishwasher/bath
sinks/kitchen sinks/shower and tub
drains; negative pressure-one bath
fan/dryer/attlc scuttle soil vent/
kitchen soffit

hot water heater; two sump holes;
finished garage (two steps down);
horizontal break In block at back
of house approximately 1/4 Inch

finished basement; added on garage
and basement for garage

block open at top; fan moves air
from basement to upstairs;
basement partially finished;
wood stove
split level,  base-   two bathtubs on slab (currently
ment under addition,  being renovated);  wood stove and
unfinished           fireplace;  no expansion Joint;
                     garage converted to bedroom; HV
                     ducts above slab
                                                                                                             (continued)

-------
                                  TABLE 2.  ASSESSMENT SUMMARIES—CLINTON (continued)
         Radon
      concentration
        lowest
House    floor     Number    Number of
number  (pCl/1)   of adults   snokers
                                Number and ages
                                  of children         Type
     Features
C23B
C24E
423
          426
                                  18. 20
                                                             bl-level
                                                             bl-level
C25B
C2(iU
C27B
C2HC
C2A9
C.'tOA
252
249
93
720
148
2.254
2
1
2
2
2
2
1
1
2
1
0
0
0
4
7. 12. 17
2
3 Months
0
bl-level
bl-level
bl-level
colonial, no
basement
split level
split level
coal stove; block In front;  reno-
vating lower level;  all  ventilated

different from Lackland  houses;
a true split with earth  floor
crawlspace

crawlspace

wood »tove and reclrculatlng
exhaust fan; French drain
approximately 12 feet from front;
block front; two-story addition
on  patio;  electric heat

one bath  upstairs (not  two)

wood  stove
                                                                                   finished basement

                                                                                   duct  under  slab  upper  level;  two
                                                                                   elderly people do  crafts  In base-
                                                                                   ment;  several top  of block openings/
                                                                                   sump  hole/wall cracks;  high pitched
                                                                                   roof;  windows never opened, some
                                                                                   sealed; owners not likely to do
                                                                                   much  on own

-------
TABLE 2.  ASSESSMENT SUMMARIES—CLINTON (continued)
Radon
concentration
lowest
House floor Number Number of
iiiiinbur (pCl/l) of adults smokers
C3B1 691 2 1
<::ii!li 1.357 3 0




(J.IJC 1.190 3 0

i::tlH GI9 3 1


C35A 1,250 2 0

C3B6 360 3 0






Number and ages
of children Type Features
8, 6. 4, 2 bl-level block front, partially below grade
0 colonial unfinished add on room with crawlapace; concrete
basement, added slab; original owner; a good
crawlspace candidate to confirm the effective-
ness of remediation methods at
Boyestown
3 grown colonial, no remedial measures begun
basement
17. 10 bl-level concrete patio slab; music teacher's
house; block front, partially below
grade
0 split level translte all along back wall behind
garage
1, 5 bl-level ten-year residents both work; wood
stove In corner; 1/2 block In front
(front only, approximately 1/3 dirt
or block); blocks exposed under front
foyer; open stone patio off family
room; only central opening to wall,
no side closet
                                                                           (continued)

-------
                                             TABLE  2.  ASSESSMENT SUMMARIES—CLINTON (continued)
CD
                    Radon
                 concentration
                    lowest
           House    floor     Number
           number   (pCl/1)   of Adults
Number of    Number and ages
 smokers       of children         Type
                                                                  Features
           <::JB7      440
           t30A      321
           i::i'JA     1.500
                      120
                      500
                      265
3
               none under 7
                       10. 12
                       15. 12. 9
                       9. 5
                       respiratory
                       problems

                       17
bl-level
                                split level
                                split level,
                                unfinished

                                bl-level
                                large, old, custom
                                house

                                split  level
bath tub on slab; sample taken at
water stake hole through slab; block
on front; wall to grade

12 ft x 16 ft addition behind family
room with crawlspace and vents; sump
open; attic fan  (not whole house)
typical basement openings; typical
subfloor ductwork; coalstove  In
addition

daycare. two  children  under age  7
                                                                                              laundry slightly different
                      Interior  block walls  under  fireplace;
                      root  cellar

                      attic fan; basement door to outside
                      with  concrete; steps  to cellar door-
                      Inside door  cut  through block
                                                                                              (continued)

-------
                                  TABLE 2.   ASSESSMENT SUMMARIES—CLINTON (continued)
         Radon
      concentration
        lowest
llinisi!    floor     Numher    Number of
number  (pCl/1)   of adults   smokers
                                Number and ages
                                  of children         Type
                                           Features
 -inn
           99
                                                   bl-level
I.-I5B


( ICfiA



IM7B




(MSB
451



226

635



686




936
0

0


21. 16



19. 18.  14
split level


bl-level

split level


bl-level



bl-level
1/2 block wall on front with closet
access; entry points-toilet/
showers/water pipes (two stakes);
negative pressure (furnace/dryer/
cold air return/bath fan/gas DHW/
normal bylead bypasser; lived here 2
years; asbestos shingles

fireplace (but not a significant
factor)

fireplace

original owner; partially finished
basement

original owner, witnessed construc-
tion; bedrock close to surface; block
wall grade

fifteen-year resident; plan with back-
to-front family room; raised bl-level;
15x15 foot patio; asphalt drive and
carport to wall; son sleeps In
basement; cracks on concrete slnb
visible on patio
                                                                                                             (continued)

-------
                                  TABLE 2.  ASSESSMENT SUMMARIES—CLINTON (continued)
         Radon
      concentration
        lowest
House    floor     Number    Number of
number  (pCl/1)   of adults   smokers
           Number and ages
             of children         Type
                                           Features
iMA'J
          823
          135
 C5HA
          157
          403
0

0
1 Month. 2

0
                              split level.          one adult works at hone;  1/2  bath
                              unfinished basement  off kitchen removed;  leakage  and
                                                   cracks In basement-house  and  garage-
                                                   house; open sump
                              colonial, no base-
                              ment
                                                             bi-level
                                                              bl-level
                              split level,
                              finished basement
subslab heat ducts;  whole house has
wallpaper and paneling;  garage
converted to bedroon; stone fire-
place; potentially many entries;
slab penetration-toilets/ductwork/
water main; negative pressure-
furnace/fIreplace/bath fan/bypass

block in front

fireplace-raised hearth with  ashpit.
outside access; block at  front

fireplace;  renovated both bathrooms
covered register In  bathroom  off
kitchen; no chase in bathroom
                                                                                                              (continued)

-------
                                  TABLE 2.   ASSESSMENT SUMMARIES—CLINTON (continued)
         Radon
      couoontration
        lowest
         Door     Number
     r  (pCl/J)   of adults
Number of    Number and ages
 smokers       of children         Type
                          Features
('."> IA
          400
split level with
unfinished basement
<;r>f>A
          131
split level
          252
bl-level
                                                     owner attempting subslab vents (5);
                                                     has  garage In 1/2 of basement;
                                                     basement  penetrations but solid top
                                                     course;  runs  coal stove In winter
                                                     (added room up on posts, open
                                                     beneath);  negative pressure furnace;  -
                                                     has  soil  pipe and AC drain

                                                     full  basement and garage under house;
                                                     floor drain-to daylight-fan
                                                     currently sucking;  fan on kitchen
                                                     hood; whole house attic fan;  plaster
                                                     gap;  pipes sealed

                                                     similar construction details  to house
                                                     C23B

-------
  TABLE 3.  DISTRIBUTION OF HOMES INCLUDED IN RADON SCREENING BY FLOOR PLAN
Floorplan
A B C
Number 22 22 3
of houses

D E
3 6

     •    The  radon concentration in the home must be above 64 pCi/1
         according to the DEP screening measurements.

     •    The  10 homes should show an even distribution of substructures,
         that  is, approximately half should be slab-on-grade construction
         and  half should have basements.  At least one of the
         demonstration homes should have a crawlspace.

     •    A high degree of homeowner cooperation.

     •    Homes with young children whose lungs are still developing should
         be well represented in the. selection.

     •    Special consideration should be given to homes that are occupied
         a large portion of the day,  especially if a basement or slab
         level is used as a play area or sleeping area.  Duration of
         residency is also considered.

     •    The presence of smokers is considered as a positive factor in
         home selection because of possible synergistic effects.

     •    Some of the selected homes should be more difficult to achieve
         radon reduction in because of finished lowest floor space.

    Table 4 shows the distribution by floorplan of the homes selected for the

demonstration study.   All of these homes had radon concentrations in excess of

200 pCi/1 in the DEP screening,  and four of the houses had concentration in
excess of 1000 pCi/1.
                                    22

-------
          TABLE 4.  DISTRIBUTION OF HOMES SELECTED FOR DEMONSTRATION
Construction Design
   (substructure)                         House Number
Split Level                                     C8A
 (combination slab-on-grade                     C39A
  and block basement)                           C30A
                                                C46A
Bi-level                                        C31B
 (slab-below-grade)                             C10B
                                                CA8B
Two-story
 (slab-on-grade)                                 C33C
 (block basement)                                C32D
Other
 (combination slab-on-grade                      C2AE
  and dirt crawlspace)
                                     23

-------
          4.0  DIAGNOSTIC PROCEDURES USED PRIOR TO RADON REDUCTION


    At the time work was initiated on the homes in Clinton, only a small

amount of experimental data was available to assist in selecting techniques

for assessing suitable radon reduction methods in homes.  The EPA guidance
document, "Radon Reduction Methods:  A Homeowner's Guide" (EPA, 1986b) and

publications describing similar radon reduction efforts (NYSERDA, 1985; EPA,

1983; Nazaroff, 1985; Turk, 1986; Henschel, 1986; Nitschke and Brennan, 1986)

provided a basis for the development of diagnostic and radon reduction

approaches.  Diagnostic techniques focused on the detection and isolation of

three main mechanisms of radon entry and transport in a structure:

    •    Simple transfer through substructure openings.  Radon enters into
         a house through openings connecting the house substructure to the
         soil.  These entrance ways need not be very large to constitute a
         significant radon pathway.  Small slab-cracks, hollow pipes, sump
         holes, or any other features that penetrate the foundation of the
         house are likely sources.

    •    Negative pressure driven transport.  Negative air pressure over
         the portion of the structure with soil contact results in a
         pressure-driven transport of radon and other soil gases into the
         house.  Negative pressure can be induced by the use of fans,
         appliances, and natural ventilation in the house.

    •    Thermally driven transport.  Differences in temperature between
         the soil-contacting portions of the building and the rest of the
         structure due to normal heating of the home may give rise to the
         thermally driven 'transport of radon from the soil into the house.

    Although numerous sources have confirmed these general mechanisms, little
information is available on the effect on indoor radon levels as the three

mechanisms interact with one another in a house, nor are there data describing
the interactive effects of other factors such as the tightness of a house or

the operation of an assortment of common indoor venting devices such as a
whole house fan.

    Consequently, diagnosis of the 10 homes in Clinton was performed using two
approaches.  The first approach was to identify and characterize all possible
sources of in-leakage, negative pressure, and thermally induced transport in

each house.  The second approach was to simulate, in isolation, conditions
                                       24

-------
that might enhance or reduce radon transport and then measure the actual
effect.  The second approach was used in a small number of homes.  Experiments
in this latter category include:
    •    Measuring the effect of whole house fan operations
    •    Investigating the negative pressure induced on the basement by
         the use of various household appliances
    •    Using a high volume fan to simulate winter-time stack effect
    •    Measuring the effect that furnace operation has on basement
         pressure.
    •    Experimenting with supplied outdoor makeup air to reduce negative
         pressure.
    In all cases, the objective of the diagnostic procedure was to understand
the mechanism and identify sources of radon infiltration to develop a low-cost
and effective radon reduction strategy for each of the demonstration homes.
4.1  RADON GRAB SAMPLE MEASUREMENTS
    Radon grab samples were obtained using a Pylon scintillation cell in con-
junction with a Pylon AB-5 fitted with a Lucas cell adapter.  Procedures as
described in the EPA document "Interim Indoor Radon and Radon Decay Products
Measurement Protocols" (EPA, 1986c) were followed.  Grab samples were used to
identify suspected soil gas entry routes.  In all homes with sump holes, grab
samples were taken in the stream of air exiting the footer drain pipe.  Other
common locations for effective grab sample collection were:
     •    Air spaces in unpaved crawlspaces
     •    Wall cavities
     •    Inside open cinder blocks
     •    Air exiting a hole drilled in a concrete block wall or slab floor
     •    Air in subslab heating ducts.
    Although grab sampling can be misleading, in combination with other meas-
urements, it proved very useful in identifying major soil gas entry routes.
Appendix A provides a detailed summary of each of the 10 demonstration homes
                                      25

-------
 and lists the results  of  individual  grab  samples  taken in each of the homes in
 the "Diagnostic Investigation"  section  of the  summary.
     If the grab sample concentration can  be  combined with the measurement of
 soil gas flowrate from an opening  to the  soil,  then a source strength can be
 calculated (for the  conditions  under which the  measurement was taken).  The
 concentration and flowrate are  dynamic  and are  affected by air pressure dif-
 ferentials,  snow cover, precipitation,  and even by  time of day.   An example
 source term calculation was made for house C30A.  A soil gas flowrate of 2,550
 pCi/1 was measured entering the building  from  the footer drains  in the sump
 hole.  The radon concentration  in  a  grab  sample of  the air from the sump hole
 was 36,000 pCi/1.  Under  the measurement  conditions (approximately 2 to 3
 pascals of negative  pressure due to  both  the furnace and clothes dryer opera-
 tion) , this  measurement corresponded to a source  term of over 91 million pCi/1
 and would account for  an  indoor concentration of  between 600 to  1,200 pCi/1
 given an air exchange  rate from 0.5  to  1.0 air  changes  per hour  (ACH) .  Be-
 cause air concentrations  of radon  were  from  1,400 to 2,700 pCi/1 in this home,
 the sump hole was  considered to be the  largest  but  not  the only  source of soil
 gas infiltration to  the house.
     Efforts  were made  to  measure the difference in  pressure between the inside
 and outside  of the house  while  grab  samples  were  being taken.   Because factors
 such as windspeed, and furnace  or  fan operation can affect the flow of soil
 gas substantially, pressure difference  information  allows a reasonable inter-
 pretation of seemingly anomolous radon  grab  sample  results and results from
 other techniques  designed  to determine  the rate and location of  radon entry.
 Pressure difference measurements were made using  low range 1.24  to 62.0 pas-
 cals  (0.005  to  0.25 inches  of water) magnahelic gauges.
 4.2   QUALITATIVE MEASUREMENTS OF SOIL GAS  ENTRY
     In  all cases,  extensive visual examinations were made of the floors,
 joints,  and undergrade walls of each home  to identify potential  entry points.
A simple  smoke  tube test was then made  at  any potential site of  entry to
determine the direction of  airflow.   If the  smoke was blown back into the
room, the opening was considered to  be  a possible point  of radon entry.
Although this test does not determine the  radon content  of the incoming air
stream, it does locate potential influx sites.  Because  factors  such  as
                                      26

-------
windspeed and direction can greatly  affect smoke tube  results, outdoor and
indoor conditions were noted  and pressure difference measurements were made
wherever possible.
4.3  CHARACTERIZATION OF  SUBSLAB AGGREGATE
    Because of  the high radon concentrations  encountered  in the  10 demon-
stration homes,  it seemed likely that  soil depressurization techniques would
be necessary.   Consequently,  all houses were  inspected  in an attempt to
determine the composition of  the subslab aggregate.
    The subslab material  was  inspected visually by  drilling holes in the slab
with a hammer drill.  A flashlight through a  1-inch hole  was frequently suf-
ficient to view the  subslab material.
    When an actual visual inspection of the subslab was impossible or uninfor-
mative, several indirect  methods were  used to determine if the material was
porous enough to allow effective soil  depressurization.
    With a hole drilled through the  slab and  negative  pressure applied to the
basement using  a fan or some  other technique,  a smoke  tube over  the hole was
used as a visual inspection technique.  If the smoke was  forced  out of the
hole, subslab entry  of soil gases was  suspected.  At this point, an additional
technique might be used.
    To determine the subslab  characteristics,  a second  slab hole was drilled.
At one hole, a  vacuum cleaner was sealed over the hole  to apply  suction on the
subslab material.  At the other hole,  a smoke tube  was  used to determine the
effect of suction through the aggregate.  More quantitative results were
achieved with the substitution of an inclined manometer for the  smoke tube to
actually measure the pressure gradient through the  subslab material.
    A more elaborate method of assessing subslab material was developed using
freon gas (standard  15-pound  cylinder) as a tracer  and  a  halogen detector (TIF
model 5500:  TIF, 9109 N.W. 7th Ave.,  Miami,  FL, 33150) to follow the freon
transfer into the building.   Freon is  injected through a  hole in the subslab,
and the detector is  used  as a sniffer  to locate relative  changes in freon
concentrations  in the building. A low  concentration of  the gas is sufficient,
and the lowest  detectable concentration should be used  at all times.  This
technique was particularly useful in detecting problems in already installed
radon reduction systems.
                                       27

-------
4.4 MEASUREMENT OF HOUSE "TIGHTNESS"
    House tightness is used, in the context of this report, to indicate rela-
tive leakage area in a house.  Air exchange rate measurements were made on
each of the 10 homes in Clinton using a standard blower door test (ASTM Method
No. E779-81).   The measurement results, forming part of each home's profile,
are presented in Appendix A.  One purpose of these measurements was to deter-
mine if high indoor radon levels in the Clinton homes could be attributed to
the tightness of the structure.  The major objective, however, was to deter-
mine the extent of leakage into the house.  If the leakage was extensive,
structural rebuilding might have been necessary in order for the radon reduc-
tion efforts to be effective.  If tightness showed a good correlation with
high radon levels, radon reduction measures might concentrate on compensating
for the low volume of available dilution air 'in a house.
    Data from blower door measurements were fitted using various models for
the prediction of air exchange" rates.  Figure 4 compares the results of four
of these models using data from the 10 demonstration homes.  A brief descrip-
tion of each of the models used is provided in "Indoor Air Quality, Infiltra-
tion and Ventilation in Residences" (NYSERDA, 1985).  Predicted air exchange
rates using the Shaw model were higher in all cases and considerably higher
for eight of the ten homes than were the air exchange rates predicted by the
three other models.  Consequently, the Shaw model results air exchange rates
were not used in the following dicussion.
    Infiltration rates predicted by the models range from 0.4 to 1.1 ACH with
an average of 0.62 ACH (excluding results from the Shaw combined modal).
Figure 5 shows a plot of the estimated air exchange rates in the ten houses
using the results of the Sherman (1980) model versus the DEP screening study
charcoal canister radon concentration results for each home.  Figure 6 shows
        *
the same plot, superimposing a curve that represents the best fit to the data.
Correlation was low with a coefficient of correlation value of 0.60.
    On the basis of these results, it was concluded that the extremely high
radon concentrations encountered in the Clinton homes were not due to the
tightness of the structures, but were more likely due to the unusually high
source strength.  For dilution ventilation alone to provide a sufficient
reduction in radon concentrations, the airflow through these homes would have
                                      28

-------
z
0
   3.0
   2.5-
   2.0-
u
 Modal Nam«

|  Kronval, 1980
3  Shaw,1981
H  Shaw/Brennan*
3  Sherman, 1980
         C24E      C39A    C10B     C32D    C31B     C46H     C3B

                                            HousalD
C4SB
C33C
C30A
       * in NYSERDA,  1935
             Figure 4. Estimates of air infiltration rates by home using four different models.
                                             29

-------
    3000
    2000
 o


1
o

o

•g
DC
1000
       0.0        0.2       0.4        0.6       0.8         1.0       1.2        1.4


                                    Air Exchange Rate (ACH)**




          •Activated carbon detectors from New Jersey DEP.

          "Infiltration estimates from  LBL model.


          Error estimation for air exchange rates. Personal communication with

            Andrew Persily, NBS
            Figure 5. Radon concentration vs, air exchange rate for Clinton homes.
                                           30

-------
X
u
w
I
*»
w
7:

e
u
S
3000
2000-
1000-
                y » 3375.6082 • 10'(-0.8914x) R * 0.72
    0.0       0.2       0.4       0.6       0.8        1.0

                           Air Exchange Rat*  (ACH)
                                                                       1.2
1.4
    Figure 6.  Radon concentration versus air infiltration rates for Clinton homes.
                                31

-------
to be increased from approximately 5.66 m /min (200 cfm) to a rate of 707.9
 3
m /min (25,000 cfm).  The cost and discomfort presented by this option indi-
cated that radon reduction methods that concentrated on lowering the entry
rate of gas to the homes would be more effective and practical.
A.5  WHOLE HOUSE FAN TEST
    A test was made to gain some insight into the potentially competing ef-
fects of increased soil gas entry versus added dilution air when a whole house
fan was used to ventilate a building.  The results are shown in Figure 7.  Al-
though the fan dramatically increased ventilation (in the neighborhood of 57%
[2,000 cfm]) the large negative pressure differential (^28 pascals) increased
the rate of soil gas entry sufficiently to overwhelm the diluting effect.
This test was made in only one house and the results depend upon factors that
may be peculiar to the individual building, soil gas and soil characteristics.
4.6  INVESTIGATIONS OF NEGATIVE PRESSURE INDUCED ON BASEMENTS
    In the majority  of houses, differential air pressure measurements between
basement air and outside air were made.  Temperature-driven stack effects and
mechanical equipment effects were isolated and the induced pressure differ-
ences measured.  It was found that:
     •    Dryers and bathroom fans resulted in a 1 pascal or less negative
          pressure on a basement.
     •    Furnaces in the 17,612 to 21,134 joules/sec (100,000 to 120,000
          British thermal units per hour [Btu/h] range put 2 to 3 pascals
          (0.008 to 0.012 inches water) negative pressure on a basement.
     •    Differential temperatures of -6.7 to -1.1 *C  (20 - 30 *F) resulted
          in 1 - 3 pascals (0.004 to 0.012 inches water) of negative pressure
          on a basement.
    During the AP measurements described above with a furnace running, makeup
air was drawn from the attic down the cavity around the chimney.  In building
C48B, this amounted to approximately 1.42 m /h (50 cfm).  Measurement of the
airflow from the furnace exhaust at the chimney top showed airflow rates of
between 2.8 and 5c7 m /h (100 and 200 cfm).  Figure 8 (a fan-flow curve for
House C48B) shows an induced negative pressure of 1 to  2 pascals (0.004 to
0.009 inches water) at 5.7 m /h  (200 cfm), reflecting the pressure difference
actually measured in the house when neither the furnace nor the clothes dryer
                                     32

-------
           5-20 7:30  9:30  11:30 1:30  3:30. 5:20 7:30  9:30 11:30 1:30  3:30
           P.M.
Figure 7. Effect of whole house fan use with all windows open on radon concentration.
                                      33

-------
z
u.
u
c

<
                      10         20         30         40


                             Pressure Dif«r«ntial (Pascals)
50
60
                      Figure 8. Fan flow curve for house C48B.
                                     34

-------
were in operation.  Blower door  generated  fan-flow  curves  (as measured with
blower door tests) were  found  to be useful in  estimating the volume  of makeup
air required to compensate for basement  negative  pressures.  The  curves, when
put to this use, were most accurate when generated  from data collected with
the blower door placed in a basement  access  door.
    To reduce  a negative pressure  of  3  to  4  pascals (0.012 to 0.016  inches
water) to 0 pascals  (0 inches  water), it was found  that between 0.65  and 0.93
 22          2
m   (7 ft  to 10 ft ) of  window area must be  opened  to  the  outside.
    It is difficult  to make low  AP measurements  in  the field.  Field  instru-
ments are only reliable  to a  lower limit of  about 1 pascal (0.004 inches
water).  Even  low  windspeeds  have  a large  impact  on the pressure  fields
surrounding a  house.  Measurements were  made when windspeeds were undetectable
to  avoid the confounding effects of wind.   Toward the  end  of the  diagnostic
work, these measurements were made using a more  sensitive  electronic  device
assembled using standard pressure  transducer and  digital display  components
purchased from Modus Instruments (481 Gleason  Rd.,  Stow, MA, 01775).  This
system has a lower detection  limit of 0.25 pascals  (0.001  in water).
4.7  SIMULATION OF WINTER CONDITIONS
    Data from  a variety  of sources have  confirmed that winter-time indoor air
concentrations of  radon  are higher than  even those  taken under closed house
conditions in  other  seasons  (Turk, 1986).   It  has been speculated that ele-
vated winter concentrations may  result  from:
     •    The  formation  of a  nearly  impermeable  cap of either frost  in the
          upper soil or  a  layer  of melting snow  inhibits diffusion of radon
          into the air  from the  ground  surface and  results in high
          concentrations of radon  in  the soil  gas.
     •    Combustion heating  equipment  and a temperature-induced  stack effect
          in a house produces a  negative pressure on the basement.   Makeup air
          for  this suction is drawn  into the house  from outside above grade,
          but  some fraction of it  is  drawn through  cracks  and holes  in the
          belowgrade foundation  (Turk,  1986).
    Pre-radon  reduction  continuous monitoring  measurements in the 10 homes
were made in the early to  late summer.   Post-radon  reduction continuous  moni-
toring measurements  were made in the  early to  late  fall.   Because these  meas-
urements spanned a variety of weather conditions  but never winter conditions,
an  attempt was made  to simulate  winter  conditions during some of  the pre-radon
                                       35

-------
reduction monitoring.  It was not possible to induce ground-freezing condi-
tions; however, it was possible to simulate basement depressurization  and  a
temperature-induced stack effect.
    A 50.8 cm  (20-inch) diameter three-speed window fan was placed  in  a
livingspace window while radon was monitored continuously using  a Pylon AB-5
and passive scintillation cell.  For one-third of the monitoring period, the
house was in closed conditions with the fan off; during the second  third of
the sampling period, conditions were identical except with the fan  on; and
during the third part windows were opened with no fan operating.
    In the first house monitored CA8B (Figure 9), the fan was on with  the
house closed,  followed by the fan off with the house open.  The  sampling on
this house did not include a period when the house was closed and the  fan was
off.  The average concentration for the first period was approximately 700
pCi/1, which compares favorably with the values of 964 and 542 pCi/1 measured
with activated carbon in the same location by DEP two months earlier (April 6
to 9 and April 16 to 19).  During monitoring in June, the outside temperature
averaged approximately 22.8 *C (73 *F).  DEP monitoring periods  were 9.4 *C
and 10 *C (49  *F to 50 *F).  The fan induced 7 pascals (0.03 inches water) of
negative pressure across the building shell.  When the fan was shut off, the
concentration  dropped quickly to less than 10 pCi/1, then for .the remainder of
the fan off, house open period, radon concentrations varied in a distinctive
diurnal cycle with peaks in the early part of the day and minimum levels in
the late afternoon.  Control homes, selected for proximity and construction
detail similarity to a demonstration home, were monitored simultaneously.  As
can be seen in Figure 10, this same diurnal cycle was observed over the same
time period in the control house C31B.
    The second house, C30A, was monitored from June 7 through 14 using the
Pylon passive  radon monitor.  Samples were taken during three monitoring
periods (fan off, house closed; fan on, house closed; and fan off,  house
open).   The results are shown in Figure 11.  During the first period,  the
concentration rose quickly after the windows were closed and peaked at 1,300
pCi/1 near 5:00 a.m. on June 8, followed by a drop until 11:00 a.m. on June 8
when the window fan was turned on, producing a negative pressure of 8 pascals
(.032 inches water) on the building.  At this point, the level of radon
increased very quickly to a much higher peak of 2,600 pCi/1 and  averaged
                                       36

-------
   1500
«  1000
e
    500
                                                     Fan Off — Windows Open
5/29       5/30
5/31
                                         6/1         6/2        6/3
                                         Days (end of day is midnight)
                      Figure 9.  Premitigation radon concentration, house C48B.
                                             37

-------
  10,000
   1,000
o

a
CC
       PM	AM	PM	AM	PM	AM	PM	AM	PM	AM	PM	AM-
5/29 5/30
"VVV" Te« Home
+ 4 % Control Home
5/31 6/1 6/2
Time
6/3
       Figure 10. Premitigation radon concentrations, house C48B and control house C31B.
                                    38

-------
      3000
S    2500-
U
 e

4*
 L
 e
u
 g
2000-
      1300-
1000-
       500-
                                                        F an Off - Windows Open
           6/7        6/8         6/9       6/10       6/11       6/12

                                     Days (End of Oiy is Midnight)
                                                                   6/13
6/14
6/15
                      Figure 11.  Premitigation radon concentration, house C30A.
                                                39

-------
approximately 2,075 pCi/1 for the monitoring period.  This compares well with
the DEP (activated carbon) values of 2,254 and 2,141 pCi/1 for the same loca-
tions on April 7 to April 14 and April 16 to April 19, respectively.  At 3:00
p.m. on June 10, the fan was removed and the windows opened.  The radon level
in the house plummeted to a low of 60 pCi/1 at 7:00 p.m. and then showed the
familiar diurnal cycle seen in all the houses monitored in Clinton.
    The third house, C33C (Figure 12), was monitored June 16 to June 24 using
three monitoring periods — fan off, house closed; fan on, house closed; and fan
off, house open.  The effect of the fan-induced negative pressure was drama-
tically different in this house from that in either of the first two homes
monitored.  When the fan was turned on, it caused very wide radon con-
centration excursions, ranging from a low of 100 pCi/1 to a maximum of 2,500
pCi/1 over a period of 12 hours.  The average concentration during the fan-
off, house-closed periods was about 1,375 pCi/1 as compared with 1,530 pCi/1
measured by DEP (activated carbon) in the same location on March 14 to 17-
For the fan-on, house-closed period, the average was 922 pCi/1.  In this
house, the floor was a slab-on-grade with heating ducts under the slab.  When
examining the holes in the slab made for the warm air grills, it was found
that all of the soil beneath the slab had subsided, leaving a 2.5-10.2-cm (1
to 4 inches) cavity between the bottom 'of the slab and the earth surface
(except where there were grade beams under the load-bearing walls).  A poly-
ethylene vapor barrier was found in very good condition stuck to the bottom of
the concrete slab.  This left a large surface area of exposed earth in direct
convective contact with the living space air.  When the fan was shut off and
the windows opened, the average concentration dropped to about 300 pCi/1 and
the familiar diurnal cycle was seen, even in this unoccupied house.
    The results from house C8A are shown in Figure 13.  The average concen-
tration for the fan-on, house-closed period was 465 pCi/1 compared to DEP
measurements of 791 and 1650 pCi/1 taken at the same location on March 22 to
25 and March 28 to 31.   The average concentration for the fan-off, house-
closed period was  415 pCi/1.  After the fan was turned off and the windows
opened,  the average concentration dropped to 250 pCi/1 and the diurnal cycle
reappeared.
    An experiment  to simulate thermally driven effects was also made.  The
temperature in one of the buildings was raised to induce stack effect negative

-------
      3000
^    2500 -
                                        Fm On
§
e
      2000-
      1500
0
      1000-
       500-
                                                                      Fan Off - Windows Open
                                                                             Activated Carbon
           6/16    6/17      6/18      6/19     6/20      6/21      6/22     6/23      6/24     6/25

                                          Days (and of day is midnight)
                     Figure 12. Premitigation radon concentration, house C33C.
                                             41

-------
e
e

fit
800




700




600




500




400




300




200




100
                               Fan Off - windows Still Closed
                Fan On


               Windows Closed
                                                                             Windows Open
                                  Activated Carbon
          6/25
               6/26        6/27        6/28        6/29


                              Days (Day Ends at Midnight)
                                                                      6/30
7/1
7/2
                        Figure 13.  Premitigation radon concentration, house C8A.
                                                42

-------
pressures by running the  furnace simulating combustion  appliance draft.  The
results are shown in Figure  14.  Radon  concentrations were  continuing to rise
when the experiment was interrupted.
    Negative pressures were  induced by  both the  furnace and the temperature
differential in house C48B as shown in  Table 5.  Essentially, the furnace
produced on indoor/outdoor temperature  differential of  22 *C  (71.6 *F)
resulting in approximately 4 pascals  (0.016 inches water) negative pressure on
                                 2       2
the basement.  Opening the 0.65 m   (7 ft ) of  attic hatch in  the ceiling
appeared to increase the  negative pressure 1 or  2 pascals (0.004 or 0.008)
from 4 pascals (0.016 in  water) to 5  or 6 pascals (0.020 to 0.024 in water).
Due to the difficulties in measuring  small pressure differences across
building shells, these measurements are preliminary.
    It is clear that a fan-induced negative pressure on a house has an impact
on the radon concentrations  in that house.  In some houses,  the technique
appears to adequately simulate winter-time entry rates  even in the summer,
while in others there is  little to distinguish a house  monitored under simu-
lated winter conditions from the same house monitored under closed-house con-
ditions.  Winter conditions  cannot be uniformly  simulated during the summer.
The ground is not capped  with snow or frost.   A  fan induces a negative pres-
sure over the entire building shell whereas in typical  winter conditions the
basement is under the highest negative  pressure  and the top of the house is
under positive pressure due  to the buoyancy of the warmed air that is driving
the stack effect.  A fan  will bring in  approximately twice  as much dilution
air as the temperature-driven stack effect for the same negative pressure put
on the basement.  Running the house at  22 *C (71.6 *F)  warmer than the outside
air will reduce the artificial introduction of dilution air.  However, the
method is impractical for summer use  because of  comfort and possible damage to
temperature-sensitive plants, furniture, or musical instruments.
4.8  INCREASING MAKEUP AIR
    Additional negative pressure in basement areas produced by the normal
operation of furnaces can result in increased  indoor radon  levels.  One
approach to controlling this effect is  the introduction of  makeup air to the
basement or the furnace itself.  Several methods of providing makeup air were
tested in house C30A.
                                       43

-------
a
   300.0 i
   250.0 -
o  200.0-
n
   150.0 -I
P
C  100.0 -

1   50.0-
     0.0
            Date: 5/28
                   Furnace Off
 Closed Doors and
Windows and Turned
 Up Heat
                                            Windows Opened
       9:30 AM   11:00 AM 12:30 PM   2:00 PM  3:30 PM   5:00 PM  6:30 PM   8:00 PM   9:30 PM
                                                 Time
            Figure 14.  The effect on radon concentration of producing a heat differential
                                   to simulate winter conditions.
                                            44

-------
           TABLE 5.  PRESSURE DIFFERENCE MEASUREMENTS FOR TWO HOMES
       Condition
                                  House C30A

House closed, outside temperature = 16.6 C (62 F)
              inside temperature = 19.4 C (67 F)

Dryer + bath fan on

Furnace + dryer + bath fan on

Furnace +• dryer + bath fan on
 inside temperature = 26.7 C (80 F)
0 Pascals


1 Pascals

2 Pascals

3 to 4 Pascals
                                  House C48B

House closed, outside temperature = 16.6 C (62 F)
              inside temperature = 17.8 C (64 F)

Furnace on

Furnace on, inside temperature = 33.8 C (92 F)

Furnace on, inside temperature = 33.8 C (92 F)
 •*• attic hatch open

Furnace on, inside temperature = 33.8 C (92 F)
 + attic hatch open
0 Pascals


3 Pascals

4 Pascals

5 to 6 Pascals


4 Pascals
                                       45

-------
    A fan 2.27 m /h (80 cfm in free air) was used to push air down the thermal
bypass surrounding the chimney.  This size fan had an almost imperceptible
impact on the negative pressure between the basement and outside air.
    A second effort involved blowing air directly into the basement with a fan
mounted in a basement window.   This method was marginally more successful but
required the use of a fan which had to be switched on and off by the home-
owner.
    A third method used a 6-inch insulated duct to supply intake air to the
return air plenum of the furnace distribution system.  When the furnace blower
was running, about 2.83 m /h (100 cfm)  of outside air was introduced into the
34.0 m /h (1,200 cfm)  flow in  the plenum.  The simplicity,  effectiveness, and
passive nature of this technique make it preferable over the use of active
methods of supplying makeup air.   Active introduction of outside air into a
house may produce excessive basement cooling when operated  in the winter;
consequently, the passive technique was adopted for use in  the 10 homes when
the reduction of negative pressure using dilution air was required.
                                  46

-------
                            5.0  RADON MONITORING

    Two radon monitoring techniques were used during this program:  continuous
radon monitoring using a Pylon AB-5 monitor together with a passive radon
scintillation cell detector  (PRD)  (Pylon Model AB-5 & Accessories Instruction
Manual Pylon Instruments, Ottawa,  Canada) and an integrating short-term
technique using charcoal canisters  (George, 1984).  Protocols for the use of
these techniques are detailed  in the project Quality Assurance Project Plan
(QAPP) and will not be repeated in this report.
5.1  CONTINUOUS RADON MONITORING
    Continuous monitoring results  were helpful in understanding the daily
variations in radon concentration  in a house and how this pattern, as well as
overall radon levels, were affected by natural and powered ventilation, heat-
ing systems, and other factors that might influence radon levels.
    The ability of the passive monitoring system to respond to temporal
variations in radon concentration  was tested in the Department of the Energy,
Environmental Measurement Laboratory  (EML) exposure chamber.  The results 'of
this test are shown in Figures 15  through 18 for each of the PRD scintillation
cells.  The lower curve in each of these figures is the radon concentration
recorded by the chamber monitoring devices (four 2-liter active scintillation
cell-based monitors).  The upper curve is the response, in counts per minutes
(cpm), of the AB-5 and PRD monitoring system.  In all cases, the field moni-
toring device was able to track the laboratory equipment response to concen-
tration changes reliably (on the basis of visual inspection of the super-
imposed curves).
    The continuous monitoring  system was set to count collected air samples  at
30-minute intervals.  Three  48-hour sampling periods were used to monitor pre-
and post-radon reduction gas concentrations.
5.2  CHARCOAL CANISTER MONITORING
    Short-term integrating monitoring, using activated charcoal monitors, is
the method most commonly used  in radon screening and assessment studies.  In
                                    47

-------
I
s
IT
56
55 -
54 -
53 -
52 -
51 -
50 -
49 -
48 '
47 -
46 -
45 -
44 -
43 -
42 -
41 -
40 -
39' -
38 '
37
           EML Lab 8/14-8/15/86
                                              55
       1200
                                                                              - 50
                                                                              r 45
                                                  u
                                                  a
                                                                                     3
                                                                              - 40
                1600
2000
2400
                                                              400
                                                                        800
                                         Time
                  Figure 15.  PRD#123 response to temporal variations.
                                   48

-------
                                                                               . 55
e

o
o
                 EM LLab 8/14-8/15/86
      1200
800
                   Figure 16.  PRO #124 response to temporal variations.
                                      49

-------
                                                                            .55
2
ff
      1200
1600
2000
2400
400
800
                                       Time
                  Figure 17.  PRO #125 response to temporal variations.
                                 50

-------
I
s
c
§
u
52
51
50
49
48
47
46
45
44 -
43 -
42 -
41 -
40 -
39 -
38 -
37
          EM L Lab 8/14-8/15/86
      120O
                                                                              -50
                                           -45
                                                 u
                                                 a
                                                  i
                                                 I
                                                                              h40
                 1600
2000
2400
400
800
                                         Time
                Figure 18. PRO #127 response to temporal variations.
                                        51

-------
addition, the simplicity and low cost of charcoal canister monitoring made  it
an attractive confirmatory measurement technique in the current work.  The
canisters and continuous monitoring devices were routinely deployed simul-
taneously in the same locations to allow comparison of monitoring results.
    In the Clinton homes, radon concentrations varied by as much as a factor
of 20 in a 24-hour period prior to the installation of radon reduction equip-
ment.  Similar wide swings in radon concentration have been observed in other
locations found to be in close proximity to significant soil concentration  of
radon.  Figure 19 illustrates this phenomenon in house C33C.  The ability of
charcoal canisters to provide reliable measurement information under these
conditions is uncertain.  George (1984) describes tests of the response by
charcoal canisters to radon concentrations that varied by two times the lowest
concentration during the monitoring period.  Analyses of the canisters found
radon concentrations to be representative of the average chamber concentra-
tion.  However, no reports of tests at the larger concentration differences
encountered in Clinton were located in a review of the literature.
5.3  MONITORING CONDITIONS
    The concentration of radon measured in a house is strongly dependent on
the condition under which the measurement is made.  The most reproducible
conditions are those found in winter, when doors and windows are closed for
long periods and thermally driven negative pressure is applied at soil contact
points.  A statistical study of available monitoring data conducted by the EPA
found that radon measurement variance was lowest when houses were monitored in
the winter (Ronca-Batista, 1986).  This study led to the recommendation that
winter conditions be simulated when monitoring for radon.  As discussed in
Section 4 of this report, efforts to simulate winter conditions using a
variety of techniques were at best unreliable.
    Radon concentrations in houses show both a daily and seasonal variation.
Measurements were taken within the 2-week period immediately preceding instal-
lation of radon reduction equipment wherever possible.  Post-radon reduction
measurements, were made as soon after installation of the radon reduction
equipment as possible.  It was hoped that this short time delay between pre-
and post-radon reduction measurements would reduce the effect of seasonal
variation on the measurement; however, in some of the homes requiring three
                                     52

-------
   7 -
••  a -
•n  O
£  5 -
   3

 9
 U


 §  2
o  *
   1 -
                                       Day
            Figure 19.  Preradon reduction monitoring results. House C33C.
                                53

-------
levels of radon reduction, this was not possible.  Pre-radon reduction con-
tinuous monitor measurements were made in full summer while post-radon reduc-
tion continuous monitor and charcoal measurements were made under the condi-
tions shown in Figure 19 during the November through January timeframe.  In
most cases, baseline data collected under attempted simulated winter con-
ditions did not produce radon levels comparable to those measured during the
DEP radon survey.   Initial continuous monitor data were collected when radon
levels were at a seasonal low and the data after radon reduction were col-
lected when indoor radon levels were increasing due to the onset of winter.
Consequently, in some cases, interpretation of radon reduction effectiveness
via continuous monitor data was inconclusive.
5.4  CONTROL HOMES
    In an effort to differentiate between random fluctuations in concentration
levels and any real reductions due to the radon reduction efforts, control
homes were selected for simultaneous monitoring with radon reduction demon-
stration homes to be mitigated.  Control homes were chosen on the basis of
proximity and similarity in floorplan to the radon reduction demonstration
home.  An ideal control home would not receive radon reduction techniques
until work was completed on its corresponding demonstration home.  The demon-
stration home would, in addition, have similar baseline radon concentrations
to those found in the corresponding control home.  Unfortunately, equipment
and time constraints together with some concern about the high radon exposures
that might occur in control homes where radon has not been reduced led to the
selection of control homes from among the 10 demonstration homes.  Conse-
quently, no control home was left in an undisturbed state for the full dura-
tion of the project.  Table 6 shows the actual schedule of control home pair-
ings to demonstration homes.
    Figure 20 is a log plot showing the before radon reduction measurements on
house C48B and its corresponding control home, house C31B.  House C48B was
closed and unoccupied during the first three days of monitoring.  For the
remainder of the time it was monitored under normal living conditions.  House
C31B was occupied and monitored under normal living conditions for the entire
time period plotted.  The pattern of diurnal radon concentration buildup and
decline can be clearly seen in this plot.  This phenomenon appears to be
                                     54

-------
TABLE 6.  CONTROL HOMES PAIRED WITH DEMONSTRATION HOMES
House Code
C30A
C31B
C33C
C39A
C46A
C48B
Sample Dates
06/07 to 06/09
06/09 to 06/14
06/27 to 07/02
07/03 to 07/09
08/07 to 08/11
11/17 to 11/20
06/06 to 06/13
06/07 to 06/11
08/07 to 08/13
08/09 to 08/13
08/15 to 08/17
09/21 to 09/24
11/17 to 11/21
06/16 to 06/24
06/19 to 06/22
06/22 to 06/24
09/11 to 09/16
11/17 to 11/20
06/06 to 06/13
06/07 to 06/11
08/09 to 08/12
08/07 to 08/13
09/21 to 09/24
11/04 to 11/12
11/17 to 11/21
06/25 to 07/01
06/25 to 06/27
06/27 to 06/29
07/15 to 07/18
08/07 to 08/09
08/07 to 08/13
11/21 to 11/23
12/09 to 12/11
05/29 to 06/05
05/30 to 06/01
06/01 to 06/04
06/04 to 06/05
07/10 to 07/13
11/07 to 11/20
Control House
C39A
C39A
C46A
C46A
C46A
C39A
C30A
C30A
C30A
C46A
C8A
C39A
C30A
C32D
C32D
C32D
C32D
C32D
C30A
C30A
C30A
C8A
C46A
C48B
C30A
C8A
C8A
C8A
C8A
C39A
C39A
C32D
C24E
C31B
C31B
C31B
C31B
C31B
C31B
                                                          (continued'
                         55

-------
      TABLE 6.   CONTROL HOMES PAIRED WITH DEMONSTRATION HOMES (continued)
House Code
 Sample Dates
Control House
  C24E
08/15 to 08/17
08/17 to 08/19
08/19 to 08/21
12/09 to 12/11
      C8A
      C8A
      C8A
      C46A
  C8A
06/25 to 07/01
06/25 to 06/27
07/15 to 07/19
08/15 to 08/17
08/19 to 08/21
      C46A
      C46A
      C46A
      C24E
      C24E
  C10B
08/15 to 08/17
08/19 to 08/21
09/14 to 09/17
09/11 to 09/23
      C31B
      C31B
      C31B
      C31B
  C32D
06/16 to 06/25
06/19 to 06/21
06/21 to 06/24
09/21 to 09/24
11/17 to 11/21
      C33C
      C33C
      C33C
      C33C
      C33C
                                    56

-------
10,000
 1,000
   100
     1
     5:00
     prr
5:00=5:00^5:00=5:00=5:00^5:00=5:00=5:00=5:00=5:00^5:00:
"ATI     Pfl     AM     Pf1~~~~AT1PH     AM     Ptt    AH    Ptl    AM"
     5/29   5/30
              5/31
6/1
6/2
6/3
6/4
       -<>   Test Home
                Control Home
                               Time
    Figure 20.  Premitigation monitoring results for house C48B and control house C31B.
                                      57

-------
independent of the building structure.   The synchronicity of this pattern is
striking and it was repeated throughout demonstration-control home sampling in
Clinton, New Jersey.
    Figure 21 is a plot of ambient radon concentration versus time, reproduced
from the report, "Evaluation of Radon Sources and Phosphate Slag in Butte,
Montana" (EPA 1983).   The same pattern showing gas concentration peaking near
6 AM, followed by a minimum concentration reached roughly twelve hours later
is seen in outdoor air.  This diurnal cycle may be useful in fingerprinting
soil gas radon sources in the diagnostic phases of future radon reduction work
if other sources do not show a similar  daily outgassing fluctuation.
                                    58

-------
   5.0 —
   4.5
   4.0 —<
   3.5 —
   3.0 —
S.  2.5 H
   2.0 —



   1.5 —




   1.0 -^



   0.5
   0.0
          T   f    i    t   i    i   i   i   [    i    i   r   T    i   i   t   r   i    i    i    i   i    i   -r   I    i    r   r  T
          24   6   12  18  24  6   12  18  24  6   12  18  24   6  12   18  24   6   12  18  24   6   12  18  24   6   12  18 24
                  8/28/80        8/29/80         8/30/80         8/31/80           9/1/80           9/2/80          9/3/80
                      Figure 21. Ambient radon concentrations, Hebgen Park Monitoring Station, August 8-September 4, 1980.

-------
                 6.0  DEVELOPMENT OF RADON REDUCTION  PLANS

    Radon reduction plans were developed for each of the 10 homes based upon
the prior diagnostic assessment,  discussions with the homeowners and con-
struction contractor,  and available  information about effective radon reduc-
tion techniques.
    Summary radon reduction plans were prepared for discussion with the home-
owner and construction contractor to describe the installation that would be
necessary.  Appendix A includes copies of the radon reduction plans for each
house.  The plans included three levels of radon reduction.   The first level
was the lowest cost technique considered likely to succeed.   Levels two and
three were upgrades from level one.   The contractor was to complete level one
before monitoring began.  On the basis of post-level one monitoring, a deci-
sion would be made concerning the need for further radon reduction.  When
radon concentrations remained elevated, additional diagnostic measurements
were performed to determine the effectiveness of the installation.  The second
level of radon reductions was revised based on the results of these diagnostic
measurements.  The levels of the radon reduction plan were installed, moni-
tored, and diagnosed in this manner  until either the radon concentration was
reduced to an acceptable level or the third level of the plan had been com-
pleted.
    Homeowner involvement in the selection, development, and implementation of
the plan was encouraged.  A homeowner permission form, reproduced in Appendix
B, was discussed with each of the homeowners before proceeding with the
installation.
    Table 7 is a summary matrix showing the important construction features
and the general radon reduction options selected for each of the 10 homes.
                                   60

-------
TABLE 7.  SUMMARY OP RADON REDUCTION PLANS


.



Radon Reduction Method
Perimeter suction
Sump hole suction

Subslnb suction
(exterior)
.Subslab suction
( interior)

Sea) perimeter crack-
no suction on crack


Rerouting, sealing
biibslab ducts, and
applying suction
to the ducts
House Type



Bl-level
(totally finished)
slab below grade
C48B


C10B
C31B
C48B


C31B
C10B







Split level
1/2 basement,
below grade
heating duct
under slab

C39A
C30A


C46A
C8A

C39A
C46A
C8A
C30A
C30A
C39A
C46A
C8A
Two-story,
no baaenent.
subsided
subslab
heating duct
under slab
C33C




C33C







C33C






Two-story, basement
sump hole-drain tile

C32D



C32D













Split level
1/2 slab on grade
earth crawl-space





C24E
(also on block above
footer)








                                                                       (continued)

-------
TABLE 7.  SUMMARY OF RADON REDUCTION PLANS (continued)

Radon Reduction Method
Supplied nakeup air to
furnace (dilution)
Ventilation and isolation
of crawlspace
House Type
Bl-level
totally finished)
slab below grade


Split level
1/2 basement,
below grade
heating duct
under slab
C30A
C46A
C39A

Two-story,
no basement.
subsided
subslab
heating duct
under slab
C33C

Two-story, basement
sump hole-drain tile


Split level
1/2 slab on grade
earth crawl-space

C24E

-------
                7.0   INSTALLATION  OF  RADON REDUCTION MEASURES

7.1  INSTALLATION MATERIALS
    Installation of radon reduction measures in each of the  10 homes followed
the development of radon reduction plans as shown in Appendix A and the
techniques generally documented in the literature.  Table 8  is a summary of
principle materials used in the 10 home radon reduction demonstrations.
7.2  ESTIMATE OF INSTALLATION COSTS
    Table 9 shows the estimated cost of installation by home.  The goal of an
average cost of $2,500 per home was exceeded.  This was due primarily to the
cost associated with the radon reduction of house C33C.
    Two factors contributed to this large excess.  House C33C had essentially
no subslab aggregate.  The soil had subsided to from 1 to 4  inches below the
slab.  Depressurizing the soil was complicated by the existence of this air
space.
    The two highest cost houses shared a common feature—the subslab aggregate
was poor.  In the case of C43B, little aggregate was found and airflow from
the central hole punched in the slab was only partially successful.  House
C48B had an incomplete foundation in a small crawlspace accessed through the
back of a closet.  Radon concentrations in the crawlspace were found to be
elevated.  The repair of the foundation was not anticipated  in the cost esti-
mate.
    Another cause for elevated cost can be attributed to the use of a novel
method of perimeter suction that was used in both house C33C and house C48B
(the second highest cost house).  This technique required the labor-intensive
work of cleaning out the perimeter crack and filling it with backer rod and
sealing with pourable polyurethane.  The perimeter wall was  then ventilated.
The cost of this method was excessive; therefore, other houses, specifically
C10B and C31B, had their radon levels reduced with an alternative, novel
system.
                                      63

-------
   TABLE 8.   STANDARD PARTS USED IN INSTALLATION OF RADON REDUCTION SYSTEMS
   Duct Fans
   Supplier:
RB Kanalflakt Inc.
1121 Lewis Avenue
Sarasota, Florida  33577

(813) 366-7505
Cost:  K4 " $ 87 each
       K6 " $100 each
*  Ducts

- 6 in.  oval ducts - exterior - sheet metal
- 6 in.  flue ducts (insulated) - ceiling runs (flexduct plastic film inside;
                                               vinyl core)
- 3 in.  x 12 in.  ducts - ceiling traverses
*  Duct Accessories

         - 6 in.  ceiling diffuser boxes and plates for air outlets

         - 4 in.  dryer vents with wire mesh screen to direct outlet airflow on
         exterior of house

         - 4 in.  rain cap to cover open exterior ducts

         - 4 in.  dripless roof flashing to seal around roof exiting ducts
   Sealants
         Acryl 60 by ThoroSeal for sealing voids-following manufacturer's
         instructions,  was used for sealing larger openings, such as the cavity
         around electrical outlets; sealing voids and cracks-used primarily to
         seal dug out perimeter or patching block and slab holes.

         To fill dug out perimeter, hardware cloth was rolled and then crushed.
         It was placed in the dug out perimeter so that a 5 to 7 cm cavity was
         maintained in the crack.  The perimeter was then sealed with Acryl 60
         cement .

         Urethane caulking for general sealing-urethane caulking was used for
         sealing around fans, ducts,  pipes, and slab penetrations.

-------
                   TABLE 9.   COST OF RADON REDUCTION INSTALLATIONS
                         (breakdowns by house are estimates)
House          Radon
Code     Reduction Methods
Labor*   Materials
         Heating
         System**   Electrical   Total
C30A     sump hole suction
         sealed subslab
          duct suction
         sealed perimeter
          crack
         supplied makeup
          air to furnace
2.460
200
490
150     3,300
C39A     sealed perimeter
          crack
         sump hole suction
         sealed subslab
          duct suction
         supplied makeup
          air to furnace
1.560
300
490
120     2.470
C8A      interior subslab     1,150
          suction
         sealed perimeter
          crack
         sealed subslab
          duct suction

C46A     sealed perimeter     1.700
          crack
         supplied makeup
          air to furnace
         interior subslab
          suction

C10B     exterior subslab     1,040
          suction
         sealed perimeter
          crack
             150
            490
             400
            490
             400
            140     1.930
            150     2.740
                        400     1,840
C31B     sealed perimeter
          crack
         exterior subslab
          suction
1,250
400
            220     1,870
C48B     perimeter suction    3,000      1,000
         subslab suction
                         170
                        360     4,530
                                                                      (continued)
                                         65

-------
              TABLE 9.  COST OF RADON REDUCTION INSTALLATIONS (continued)
                          (breakdowns by house are estimates)


House          Radon                                Heating
Code     Reduction Methods    Labor*   Materials    System**   Electrical   Total


C33C     perimeter suction    6,650        400       1,310         140     8,500
         interior subslab
          suction
         sealed subslab
          duct suction
         supplied makeup
          air to furnace

C32D     sump hole suction    2,860        150         —         170     3,180
         interior subslab
          suction

C24E     interior subslab       900        400         	         200     1,500
          suction           	      _____	       		
         ventilation and
          isolation of       22,568      3,509       3,453       1,737     31,267.00
          crawlspace


*   This is only installation cost (subcontractor).

**  Rerouting ducts and addition of dilution air.
                                      66

-------
    These two houses had their floor/wall cracks sealed, but the primary  radon
reduction technique was applied from the exterior of the houses.  Along one
side of the two houses, a trench was dug to the level of the first hollow core
foundation block.  Three different penetrations were made  in blocks along this
wall.  Two penetrations made at the corners of the side wall, entered the void
space in the foundation blocks on the front and rear walls.  These penetra-
tions permitted block-wall suction on the front, side, and  rear walls.  In the
center of the side wall, a penetration was made through the block and into the
loose backfill soil near the floor/wall crack beneath the house floor slab.
By tying all three penetrations along the side wall into a  common vertical
plastic vent pipe equipped with an in-line fan, suction could be applied
simultaneously to three walls and the sub-slab.  This method was found to be
one of the fastest, least disruptive, and most cost-effective of the methods
used.
    A learning curve is evident in the distribution of costs per house.
Houses C30A, C33C, and CA8B were the first three houses where radon reduction
techniques were applied.  All subsequent houses show a lower cost for radon
reduction than do these three.  The radon reduction plan employed in house
C30A for $3,300 was virtually repeated in houses C8A, CA6A, and C39A at
reductions of $500 or more per house.
    House C32D was originally considered to be one of the  least costly to
demonstrate radon reduction.  Simple sump hole suction and  good sealing of
openings and cracks in the basement slab were recommended.  When the work was
completed, monitoring indicated that the radon concentration was still
excessive.  Measurement of pressure differences between room air and sub-slab
air in the basement showed that suction did not extend to  the side of the
house opposite the sump hole.  A second sub-slab suction system was installed
to correct this.  When monitoring showed that radon levels  in the basement had
doubled after installation of the second fan, intensive diagnostic examination
of the basement was begun.  Two factors contributed to the  elevation in radon
concentration after radon reduction techniques were applied:  (1) a tiny  fan
leak was allowing radon-rich sub-slab air into the basement and  (2) the fan
exhausts on the outside of the house had been placed at ground level allowing
radon-rich air to leak back into the basement.  When these  two problems were
remedied, basement air radon was significantly reduced.
                                    67

-------
7.3  DIAGNOSTIC PROCEDURES USED FOLLOWING RADON REDUCTION EFFORTS
    Additional diagnostic procedures were required when radon concentrations
were considered to be excessive following the completion of any radon reduc-
tion plan level.  Initially, diagnostic procedures focused on the function of
the installed system checking ducts, fan, seals, and airflow through the
system.  If elevated radon concentrations could not be linked to a failure or
weakness in the installed system, post-diagnostic procedures were directed
toward the identification of secondary fadon routes that may have been missed
during earlier inspections.   This process involved a repetition of the basic
pre-radon reduction diagnostic efforts.
    In many cases, secondary sources of radon infiltration were discovered and
the subsequent radon reduction plan level was re-evaluated.   In some cases,
particularly in homes with finished basements or slab-on-grade levels,  no
secondary sources were located, and installed soil depressurization systems
were functioning to specifications.  In these cases,  the addition of dilution
air was required to produce  any further reduction in radon concentration.
                                  68

-------
                           8.0  QUALITY ASSURANCE

     The Quality Assurance Project Plan (QAPP) dated June 11, 1986, was
approved by the AEERL Project Officer and Quality Assurance Officer prior to
initiation of data-gathering activities.  The objective of this project was to
demonstrate radon reduction by use of low-cost mitigation techniques in up to
ten homes.  Charcoal canister and passive scintillation cell measurement meth-
ods were identified as the methods of choice for determining the extent of
radon reduction in the homes.  Data quality objectives (DQOs) for the quality
of these two methods were established in the approved QAPP.  The DQOs are
shown in Table 10.
     Precision, accuracy, and completeness objectives were met for measure-
ments made using charcoal canisters and passive scintillation cell radon moni-
tors.  Tables 11 and 12 show the actual performance with respect to the DQOs.
Details are provided in Sections 8.1 and 8.2.  Sections 8.3 through 8.5 detail
other QA information including results of audits, the impact of seasons on
radon concentration, and the use of control homes.
8.1  QUALITY ASSURANCE OBJECTIVES FOR PASSIVE SCINTILLATION CELL RADON
     MONITORING
    Four Pylon AB-5 radon monitors fitted with Pylon passive radon detector
cells were used in the course of the project.  Protocols detailed in the QAPP
were followed at all times.  Monitoring is discussed in Section 6 of this
report.
    The instruments were calibrated in the radon chamber at the EML twice
during the project.  Two of the monitoring systems were used only for post-
radon reduction sampling and were calibrated once during the course of the
project.  The calibration procedure is described in the QAPP.  Figures 22
through 25 show the calibration curves for the four devices.  Table 11 shows
the calibration constants and a calculation constant over the period between
calibrations.  Accuracy is calculated to be well within the objective of *20
percent bias.
    This measurement technique relies on the counting of radon events  (alpha
particle scintillations) and can therefore be described by Poisson statistics.
                                     69

-------
                                   TABLE 10.   QUALITY ASSURANCE OBJECTIVES
                                                                  Precision    Accuracy
Measurement  Method                            Conditions           (RSD)    (Percent Bias)    Completeness


Passive scintillation cell radon      indoor atmospheres (living     20%       +/- 20*             90*
 monitor                               conditions pre- and post-
                                       radon reduction)

Charcoal canisters                    indoor atmospheres (living     10%       +/- 10*             90*
                                       conditions pre- and post-
                                       radon reduction)

-------
   TABLE  11.   PASSIVE  SCINTILLATION CELL RADON MONITOR CALIBRATION CONSTANTS
                                 Calibration:
                    6/4 to 6/5/86           8/14 to 8/15/86
Equipment ID*
                           (Correction factor:       '
                                                pCi/1
Percent Bias
AB-5
PRO
PRO
AB-5
PRO
PRO
AB-5
PRO
AB-5
PRO
#250
#123 1.270
#124 1.197
#244 1.278
#125 1.204
#123
#255 not in use
#125 1.117
#258 not in use
#127 1.116
5.7*
5.8*
n/a
n/a
                                      71

-------
                      TABLE 12.   CHARCOAL CANISTER QUALITY ASSURANCE SAMPLES

Number of
samples
Concentrat ion
(PCI/1)






Blanks
6
1) 6 days d.l.  = 4 pCi/1.
**   These RSD values are for two "spiked" samples  colocated in the chamber.

-------
a
u
55
54  -
53  -
52  -
51  -
50  -
49  -
48  -
47  -
46  -
45  -
    44
           EML Lab 3/14-8/15/86
       37
                                                          Slope - 1.197 cpm/pCi/l
                                                          R2 - 0.82
                  39
   41            43
Radon Concentration (pCi/1).
45
47
                  Figure 22.  Calibration data:  AB-5 #250, PRO #124.
                                73

-------
IB
ec
56
55  -
54  -
53  -
52  -
51  -
50  -
49  -
48  -
47  -
46  -
45  -
44  -
    43
             EML Lab 8/14-3/15/86
       37
                                                    S1ope-1.204cpm/pCi/l
                                                    R2 - 0.735
                  39
   41             43
Radon Concentration (pCi/l)
                                                                 45
                  Figure 23.  Calibration data:  AB-5 #244, PRO #123.
                                                                           47
                                         74

-------
a
u
10
tr
*•

3
         EML Lab 8/14-8/15/86
                                                      Slope - 1.117 cpm/pCi/I
       37
39
   41            43

Radon Concentration (pCi/I)
                                                                 45
                  Figure 24.  Calibration data: AB-5 #255, PRO #125.
                                        75

-------
   52

   51 -

   50 -

   49 -
a.
u

I47'
**

I46'

   45 -
   44 .

   43 -

   42
EML Lab 8/14-3/15/86
      37
                                           Slope - 1.116 cpm/pCi/1
                                           R2 - 0.72
                        (       1
                      41
    39            41            43             45
               Radon Concentration (pCi/1)
Figure 25. Calibration data: AB-5 #258, PRO #127.
47
                                     76

-------
For a Poisson distribution, the variance of a population  is equal to the mean
of that population.  If single measurements are made from a Poisson distri-
bution, then it must be assumed that the measured value is the mean of the
distribution.  By the nature of Poisson distributions, the precision of such a
measurement will be determined by the size of the population.  Specifically,
the precision of measurement will be equal to the standard deviation for the
measured value, which can best be described as the square root of the mean
value.  As a result, precision of a measurement can be fixed by specifying a
minimum count.  To maintain a precision of +20 percent, a count of at least 25
is necessary.  The sample duration of 30 minutes used in  all field measure-
ments ensured that this minimum count was down to a concentration of less than
1 pCi/1 for calibration factors that are greater than 1 cpm/pCi/1.  Because
the critical guidance level for action on radon-contaminated homes is A pCi/1,
the precision goal was met at all times during sampling.
    The QAPP called for a minimum of one pre-radon reduction sampling period
consisting of three 48-hour sampling periods and a second post-radon reduction
sampling period of the same duration.  This minimum was met in the case of all
but house C24E.  Since completeness was 90 percent, the quality assurance goal
for this measurement technique was achieved.
8.2  QUALITY ASSURANCE OBJECTIVES FOR CHARCOAL CANISTERS
    Charcoal canister sampling and analysis were completed following pro-
cedures prescribed in the QAPP-  Table 12 details quality control and assur-
ance samples collected using this technique.
    Overall precision and completeness goals were met.  However, accuracy
goals were not met in the case of one set of three simultaneously chamber-
exposed canisters.  In investigating the reason for the large negative bias in
these canisters, it was found that the analytical laboratory determined the
relative humidity based upon the charcoal weight gain to  have been approxi-
mately half of the chamber recorder value, 68 percent.  Some loose charcoal
was reported when the canisters were returned from the exposure chamber, and
charcoal loss would reduce the weight of the canister and mask the effect of
adsorbed water vapor.  Since quality assurance samples were handled in the
same way, a similar bias might occur in some of the field samples due to loss
of charcoal.  However, when charcoal canister results are compared to continu-
ous monitoring results, no clear bias is seen.  When the  concentrations deter-
mined by the analytical laboratory were recalculated using the actual chamber
                                     77

-------
relative humidity,  accuracy for the technique was well within the quality
assurance goals for the project.
8.3  SYSTEMS AUDITS
    An audit of project records was conducted by Keith Daum (RTI) during July
1986.  Five sets of records were reviewed, namely:  field notebooks (house
sections), house files, instrument log, sample log, and pre-selection check-
lists.  No major deficiencies were identified by the audit.  Mr. Daum did
identify some minor inconsistencies in the notebooks and files which were
corrected following this audit.  These corrections included:
     •    Floorplans drawn in the notebooks are now identified as soil
          contact floors.
     •    All pages of graphed data are now dated.
     •    All manual calculations were checked and the pages were
          initialed.
     •    A project decision was made to discontinue pre-radon reduction
          alpha-track monitoring so Mr. Damn's comments on these entries
          were not addressed.
     As a follow-on to Mr. Damn's audit, a review was conducted onsite at the
end of September by Ms. Judy Ford, Quality Assurance Officer for AEERL, RTF,
and Mr. Michael Messner, the RTI project Quality Assurance Officer.  The
reviewers determined that approved quality assurance procedures were being
followed and that minor recordkeeping inconsistencies had been corrected.
8.4  SEASONAL INDOOR RADON VARIATIONS
    The factor having the greatest impact on the assessment of radon reduction
technique effectiveness is the lack of information concerning the seasonal
indoor radon variations in the Clinton area.  Sampling results, discussed
elsewhere in this report show that radon concentrations tend to increase sig-
nificantly during the heating season, even if summer-collected samples are
taken following the EPA-prescribed procedures with the house completely
closed.  Efforts to simulate winter conditions (as discussed in Section  4)
showed variable success.  In two cases, measurements matched the levels  of
radon recorded by the New Jersey DEP in their March and April screening  study.
Because pre-radon reduction sampling was done in early summer, when levels
                                      78

-------
were expected to be at their  lowest, and post-radon  reduction  sampling was
completed in December, direct comparison of pre-  and post-radon  reduction
monitoring results are misleading.  Table  13  shows estimates of  the maximum
and minimum possible reductions.  Minimum  reductions were  similarly calculated
subtracting results of post-radon reduction canister monitoring  from  the pre-
radon reduction closed house  charcoal  canister  results.  Maximum post-radon
reduction calculations were made using the difference between  the New Jersey
DEP collected data and post-radon reduction monitoring  results.  In the worst
case, radon reduction rates ranged  from 0  to  97.6 percent  (house C10B) and in
the best case, from 99.7  to 99.8 percent  (house C30A).   Because  minimum reduc-
tions are based on pre- and post-radon reduction  canister  results, the accu-
racy  (bias) of the canister measurements  is not a factor.  Under these circum-
stances, the accuracy achieved  in charcoal canister  sampling was more than
sufficient to meet the project  goals.
8.5   CONTROL HOMES
    Control homes were selected for simultaneous  sampling  from among  the 10
homes involved in the demonstration work.  Consequently, control homes for
post-radon reduction sampling were  often  houses where radon had  already been
reduced.  There is some evidence that  installation of radon reduction techni-
ques  will affect not only the radon level  but the daily pattern  of radon
buildup on a home  (NYSERDA,  1986),  making  homes where radon has  not been
reduced the preferred controls.  In this  project  it  was necessary to  use 10
demonstration homes also  as control homes  because of the time  schedule and
available equipment.
                                       79

-------
  TABLE 13.  APPROXIMATE REDUCTION IN RADON CONCENTRATION USING  CHARCOAL CANISTER DATA
              FOLLOWING APPLICATION OF RADON REDUCTION TECHNIQUES
                                         (pCi/1)
               Before
           Radon Reduction
           (Early Spring)
House Code     (DEP)*
A8

A46

BIO
791

635

418
              Before
          Radon Reduction
            (Summer)
          (Closed House)
                      After
                 Radon Reduction**
                   (Late Fall)
                  (Closed House)
               Minimum      Maximum
               Percent      Percent
              Reduction    Reduction
A30
A39
2,254
1.500
1,450
10.4
4.1
4.3
99.7
58.7
99.8
99.7
(1,250 w/Pylon)

     409

     772

      15.8
   (70 w/Pylon)
 2.9

 9.0

16.0
99.3

98.8

 0
99.6

99.2

97.6
B31
848
C33
D32
E24
691
936
1,190
1,357
426
89.0
771
304
29.0
(130 w/Pylon)
91.0
(210 w/Pylon)
5.8
11.1
4.7
11.3
12.3
93.5
98.6
98.5
61.0
86.5
99.2
98.8
99.7
99.2
97.2
    *    DEP screening study charcoal canister measurements taken  in March  and  April of
         1986.

    **   Highest post-radon reduction charcoal canister measurements taken  in August 1985
         through January 1986.
                                           80

-------
                        9.0  RESULTS AND CONCLUSIONS

    Figures 26 through 35 plot before and after radon reduction continuous
monitoring results for each of the 10 homes.  Results of the highest before
radon reduction charcoal canister monitoring  (including DEP screening results)
and the last before radon reduction charcoal  canister monitoring are also
shown on these plots.  Table 14 is a complete listing of charcoal canister
monitoring results for the 10 homes.
9.1  HOUSE C8A
    Monitoring results from house C8A are shown in Figure 26.  This is a
split-level house that had a finished basement with bedroom space in the
basement.  Radon reduction results were highly satisfactory and a reduction in
average radon concentration by any measure was large.  The cost associated
with this house was slightly higher than average due to the need to route duct
work through the finished portions of the house.
9.2  HOUSE C30A
    Figure 27 shows the monitoring results for this split-level house.  House
C30A received radon reducing measures early in the project and the reduction
plan was copied in the other A-floor plan homes, obtaining substantial reduc-
tions in all cases.  The C30A homeowners preferred to keep their house very
warm in the winter and extra attic insulation was noted during pre-radon
reduction inspections.  Consequently, to prevent an excessive stack effect a
passive makeup air duct was connected from the outside of the house to the
furnace return duct which provided dilution air without cooling the house
excessively.  The dilution air will be introduced only when the furnace is
running.
9.3  HOUSE C39A
    Figure 28 shows the results of monitoring in this split-level house.
Estimation of real reductions in this house was complicated by the lack of
success in simulating winter conditions during pre-radon reduction sampling.

-------
    10,000

     1,000 -
      100-
       10 -
         1 -
       O.T
NJDEP
                                                            Post-RR
                                          Day Number
Note: NJ DEP measurements were made using homeowner-located charcoal
      canister monitoring devices.
      Pre-RR refers to Pre-Radon Reduction measurements
      Post-RR refers to Post-Radon Reduction measurements
      CC refers to RTI Charcoal Canister measurements.

               Figure 26. House C8A: pre- and post-radon reductions results.
                                               82

-------
   10,000 -
            NJDEP
             1.000,
-s    100 -
 
-------
3
w
O>
o
o
Q.
3.6
3.4
3~.2
3.0
2.8
2.6
2.4
2.2
2.0
1.8
1.6
1.4
1.2
1.0
0.8
0.6
0.4
0.2
0.0
        0.5
                    1.5
2.5
Day Number
3.5
                                                                         4.5
            Figure 28.  House C39A: pre- and post-radon reduction results.
                                    84

-------
10,000
  1,000 .
 e> 100
 o
o
a
    10  -
NJDEP
                                                        Pre-RR
                        2              4


                            Day Number
                                                   —  CC
         Figure 29.  House C46A:  pre- and post-radon reduction results.
                               85

-------
                        Day Number
Figure 30. House C10B: pre- and post-radon reduction results.
                          86

-------
10,000
 1.000  _
   100  -
    10  -
     1  -
   0.1  -
                                    Day Number
            Figure 31. House C31B:  pre- and post-radon reduction results.
                                    87

-------
   10,000-
     1.000-
            NJDEP
      100-
o
a
       1  -
      0.1
                                                     I        I
                                       Day Number




              Figure 32. House C48B:  pre- and post-mitigation results.
                                    88

-------
10.000'
            Figure 33. House C33C: pre- and post-radon reduction results.
                                   89

-------
50
    45 -




    40 -




    35- -




-   30-

u
a

7   25 -
o
*-


I   20 -

S


I   15-




    10 -




     5 -
              NJOEP
    Post-RR
 0 +-

   0
                              —i	1	r

                               2            3


                                 Day Number
                                                      "AT/00
                                                          n/
        Figure 34. House C32D: pre- and post-radon reduction results.
                           90

-------
210
           Figure 35.  House C24E:  pre- and post-radon reduction results.
                                  91

-------
TABLE 14.   RADON CONCENTRATIONS AS DETERMINED WITH CHARCOAL CANISTERS
House code
C30A
Before
After
C31B
Before
After
C33C
Before
After
C39A
Before
After
Sample date
4/7
6/7 to 6/9
6/9 to 6/14
6/27 to 7/2
6/27 to 7/2
7/3 to 7/5
7/5 to 7/7
7/7 to 7/9
11/17 to 11/20
3/22
5/28 to 6/1
6/1 to 6/4
8/15 to 8/17
8/15 to 8/21
8/19 to 8/21
9/11 to
9/11 to
11/17 to 11/20
3/15
6/22 to 6/24
7/23 to 7/25
7/25 to 7/27
7/27 to 8/1
10/4 to 10/10
10/4 to 10/10
11/17 to 11/20
11/17 to 11/20
4/7
8/19 to
9/21 to
6/7 to 6/11
11/17 to 11/20
Concentration (pCi/1)
2,254
1,450
498
2
4
3.5
2.4
3.4
4.1
691
8.2
4.4
89
76.6
1.3
4.0
4.0
5.8
1,190
304.2
8
106
8.7
8.5
5.8
4.7
4.7
1,523
7.5
8.3
10.4
4.3
Comments
early spring
closed house
dining room
early spring
house closed
with heat on
late winter
living room
small bedroom
furnace room
living room
living room
early spring
basement
( continued)
                                    92

-------
    TABLE 14.   RADON CONCENTRATIONS AS DETERMINED WITH CHARCOAL CANISTERS
                                 (continued)
House code
Sample date
Concentration (pCi/1)
Comments
C46A



Before
After

C48B


Before
After

C24E


Before
After


C8A



Before
After


4/7
6/25 to 6/27
6/27 to 6/29
7/31 to
8/7 to 8/9
12/9 to 12/11
1/3/87 to 1/5/87
4/7
5/30 to 6/1
6/1 to 6/4
6/4 to 6/5
11/17 to 11/20
12/9 to 12/11
4/16
8/15 to 8/17
8/17 to 8/19
8/19 to 8/21
9/25 to 9/30
12/9 to 12/11
12/9 to 12/11
3/22
6/25 to 6/27
6/27 to 7/1
7/31 to
8/15 to 8/17
8/17 to 8/19
8/19 to 8/21
11/17 to 11/20
635
771.9
433
157
238.5
5.3
9.0
936
771.9
37.6
4
12
11.1
426
90.9
2.5
1.3
3.0
7.2
12.3
791
409.2
241
3
5
4.2
2.8
2.9
early spring
basement





early spring
basement


heat on

early spring
house closed



downstairs
living room
early spring
house closed






 [continued)
                                     93

-------
    TABLE 14.   RADON CONCENTRATIONS AS DETERMINED WITH CHARCOAL CANISTERS
                                 (continued)
House code
 Sample date
Concentration (pCi/1)
    Comments
C10B
Before
     4/18
 8/15 to 8/17
 8/17 to 8/19
 8/17 to 8/19
 8/17 to 8/19
          418
           15.8
            9.8
            4.2
            2.5
early spring
After
 9/11 to 9/16
11/17 to 11/19
            4.0
           16.12
                                                               heat on
C32D
Before
After
3/22
6/19 to 6/21
6/21 to 6/24
9/21 to 9/26
11/17 to 11/20
12/9 to 12/11
12/9 to 12/11
1,357
29.1
7.2
20.1
8
5.1
11.3
early spring
family room
basement
                                   94

-------
In addition, post-radon reduction monitoring only covered a 3-day period.
However, both the before- and after-radon reduction changes shown by the
charcoal canister results and the averages of the continuous monitoring
results suggest substantial reductions were made.  In this home, a passive
dilution air system was attached to the furnace air handler similar to house
C30A.  The same techniques used in the other A-floor plan homes was used in
this home.
9.4  HOUSE CA6A
    Monitoring results for this split-level house shown  in Figure 29 indicate
two levels of radon reduction.  The first level "shows the monitoring results
with two smaller sized fans in place.  The second shows  the effect of upgrad-
ing the fans to the next largest fan size.  Since this home was generally kept
warm, dilution air was added to the furnace air handler.  The post-radon
reduction charcoal canister results shown on this plot were taken in January
when demand on the passive system would be supplying dilution air to the
hous e.
9.5  HOUSE C10B
    Figure 30 shows the results of monitoring in this bi-level home.  Inter-
pretation of the results are difficult due to the low pre-radon reduction
continuous monitor concentrations measured.  In this home, because of active
occupants and a continuously occupied house, full closed house conditions were
not maintained.  The  radon reduction plan for this home  took into account the
very high usage of space and the active life of the family occupying the
house.  Consequently, the radon reduction plan called for an outside radon
reduction system that would involve a minimum of disruption in the house.  The
fan and all the ductwork were outside of the house.  An  electrical code re-
quirement included a  cutoff switch on the outdoor system; therefore, a warning
light was wired inside the house to show when the fan had been cut off allow-
ing the homeowner to  reactivate the system.  The middle  charcoal canister line
on this plot shows the increased radon concentrations in this house due to
winter conditions.  This home may be a candidate for the addition of a passive
fresh air vent to the furnace air handler to provide dilution air to the house
in the winter.
                                    95

-------
9.6  HOUSE C31B
    This bi-level house was continuously occupied with four small children.
The same approach that was taken with house C10B was applied to this home.
Figure 31 shows the monitoring results for this bi-level home.  Again, winter
monitoring may show that this house requires the addition of a passive fresh
air vent to the furnace to provide dilution air during winter-time conditions.
9.7  HOUSE C48B
    House C48B shown in Figure 32 was the first of the B-floor plans to re-
ceive radon reduction techniques.  The techniques attempted in this bi-level
home proved to be both more costly and less effective than the outdoor methods
used in the other two B-floor plan homes.  Subslab suction was installed using
one hole drilled through the slab in the furnace room.  A tunnel was dug out
for approximately 1 meter (3.3 ft) out from the hole, under the slab.  The
subslab aggregate was insufficient to provide adequate subslab suction.  Con-
sequently, a labor intensive method of creating perimeter suction was at-
tempted.  This method was partially successful in further reducing the indoor
radon levels.  Finally, an unfinished portion of the foundation behind the
earth filled front steps was repaired to prevent exposed earth contact with  .
living space air.
9.8  HOUSE C33C
    Results of monitoring in this slab-on-grade house are shown in Figure 33.
This house was the most difficult of the 10 demonstration homes to achieve
reduced radon levels.  The subslab ducts had to be rerouted between the two
floors of the house requiring considerable repair of finished space.  No
subslab aggregate was present and the earth had subsided under the slab leav-
ing a substantial air space.  Through perimeter suction, rerouting and sealing
of subslab ducts, and a passive fresh air vent system to the furnace, signifi-
cant radon reductions were achieved in this house.
9.9  HOUSE C32D
    Radon reduction in this block-basement home involved sump hole suction,  a.
secondary sub-slab suction at the opposite end from the basement of the sump
hole, and extensive sealing.  After application of radon reducing techniques
difficulties were encountered due to the placement of fan exhausts at ground
                                     96

-------
level where radon-rich air was permitted to leak back into the basement.
Figure 34 shows the large radon reductions that were achieved in this house.
9.10  HOUSE C24E
    House C24E was the only home selected that was not built by the subdivi-
sion developer and the only home with a crawlspace.  In this split-level home,
the crawlspace had earth exposure and a doorway which opened on to the lowest
level of the house.  Radon reduction in this home concentrated on isolating
and ventilating the crawlspace.  Figure 35 shows the results of this radon
reduction effort.  Due to the project time constraints continuous monitoring
results were not collected for the period following radon reduction.
                                   97

-------
                  10.0   RECOMMENDATIONS
A database of all homes receiving the application of radon reduction
techniques in Clinton Knoll should be maintained and analyzed.  The
database should contain pre- and post-radon reduction radon levels.
A summary of the radon reduction method used, the house floorplan
and any unusual features of the house or the property on which it is
built should be included.

Long-term followup monitoring should be carried out in each of the
mitigated homes to determine the average annual radon levels.  This
monitoring should be carried out for a period of at least two years
and should include continuous monitoring for a period of 1 week in
each season in an effort to identify seasonal effects on the radon
concentrations in the homes and peak exposures.

In future radon reduction projects at least 1 control home for each
10 demonstration homes should be monitored continuously during the
entire period that radon reduction work and monitoring is being
done.  The control home should not be subjected to radon reduction
methods during this time.

Investigation into the mechanisms controlling the strong diurnal
variation in radon concentration in indoor air should be pursued.
If periods of high radon levels during the day can be reliably
predicted, radon reduction techniques could be directed toward
reducing or eliminating those peaks.
                          98

-------
                                 REFERENCES
Benton, 1981
Benton, E. V., R. Oswald, and A. Frank, "Proton Recoil Neutron Dosimeter for
     Personnel Monitoring," Health Physics, Vol. 40, pp. 801-809, June 1981.

EPA, 1978
U. S. Environmental Protection Agency, Office of Radiation Programs, "The
     Effects of Home Ventilation Systems on Indoor Radon-Radon Daughter
     Levels," EPA-520/5-77-011, (NTIS PB291925), October 1978.

EPA, 1983
U. S. Environmental Protection Agency, "Evaluation of Radon Sources and Phos-
     phate Slag in Butte, Montana," Office of Radiation Programs.

EPA, 1986a
U. S. Environmental Protection Agency, "A Citizen's Guide to Radon:  What It
     Is and What To Do About It," OPA-86-004, August 1986.

EPA, 1986b
D. S. Environmental Protection Agency, "Radon Reduction Methods:  A Home-
     owner's Guide," OPA-86-005, August 1986.

EPA, 1986c
U. S. Environmental Protection Agency, Office of Radiation Programs, "Interim
     Indoor Radon and Radon Decay Product Measurement Protocols," EPA-520/
     1-86-04, February 1986.                '  .

EPA, 1986d
U. S. Environmental Protection Agency, "Radon Reduction Techniques for
     Detached Houses:  Technical Guidance,"•Office of Research and Develop-
     ment, Washington, D. C., EPA/625/5-86/019, June 1986.

George, 1984
George, A. C., "Passive Integrated Measurement of Indoor Radon Using Activated
     Carbon," Health Physics, Vol. 46, No.4 4, pp. 867-872, 1984.

Henschel, 1986
Henschel, B., A. Scott, "The EPA Program to Demonstrate Mitigation Measures
     for  Indoor Radon:  Initial Results," Proceedings, Indoor Radon, APCA
     Specialty Conference, Philadelphia, 1986.

Kronval,  1980
Kronval, J., "Correlating Pressurization and Infiltration Rate Data Tests of
     Heuristic Model," Lund Institute of Technology, Division of Building
     Technology, Lund, Sweden.

Sherman,  1980
Sherman, M. "Air Infiltration in Buildings," Ph.D. thesis, report No. 10712,
     Lawrence Berkeley Laboratory, University of California,  1980.
                                     99

-------
Nazaroff, 1985
Nazaroff, W.  W.,  H.  Feustel,  A.  V.  Aero, K. L. Revzan, D. T. Grimsrud, M. A.
     Essling, and R. E.  Toohey,  "Radon Transport Into a Detached One-Story
     House with a Basement,"  Atmospheric Environment, Vol.  19, No. 1,
     pp. 31-46,  1985.

Nitschke, 1986
Nitschke, I., T.  Brennan,  J.  Wadach, and R. O'Neil, "The Radon House Doctor,"
     Indoor Radon, APCA Specialty Conference, Philadelphia, 1986.

NYSERDA, 1985
N. Y. State Energy Research and  Development Authority, "Indoor Air Quality,
     Infiltration, and Ventilation in Residential Building," Report 85-10,
     March 1985.

Ronca-Battista,  1986
Ronca-Battista,  M.,  and S.  Windham,  "Uncertainties of Estimating Average Radon
     and Radon Decay Product  Concentrations in Occupied Houses," Proceedings,
     Indoor Radon, APCA Specialty Conference, Philadelphia, 1986.

Shaw, 1981
Shaw, J. , "A Correlation Between Air Infiltration and Air Tightness for Houses
     in a Developed Residential  Area," ASHRAE Transactions, 1981, Vol. 87,
     Part 2,  pp.  333-341.

Turk, 1986
Turk, B. H.,  R.  J. Prell,  W.  J.  Fisk, D. T. Grimsrud, B.  A. Moed, and R. G.
     Sextro,  "Radon and Remedial Action in Spokane River  Valley Residences:
     An Interim Report," Draft Report, Department of Energy Contract No.
     DE-AC03-76SF00098 [no final report intended].
                                      100

-------
                                 APPENDIX A




                            RADON REDUCTION PLANS




                                                                           Page




House Code:   C8A	    A2




House Code:   C30A	    A8




House Code :   C39A	   A15




House Code:   C46A	   A23




House Code:   C10B	   A30




House Code:   C31B	   A34




House Code:   C48B	   A40




House Code:   C33C	   A46




House Code:   C32D	   A53




House Code :   C24E	   A59
                                       A-i

-------
House Code:   C8A
       A-l

-------
               REPORT ON MEASUREMENTS AND RADON REDUCTION PLAN
HOUSE CODE:    C8A


DESCRIPTION:  C8A is a classic split level with a finished half basement.   The
basement is  divided into three rooms .  the largest of which is a  family  room.
One room is  used as a child's bedroom,  and the third room is used as  a
storage/workshop area and houses the furnace.


DIAGNOSTIC INVESTIGATION:  A substantial leak of radon was found  in a transite
pipe in the  bedroom showing a canister concentration of 1600 pCi/1. A
scintillation cell grab sample was taken from electrical outlet in the block
wall and showed a concentration of 1700 pCi/1. Pressure dry and blower door
measurements were taken.  The plumbing chase was considered a good option  for
suction fan  ductwork to the attic.  A hole was drilled In the slab and sub-
slab pebbles were found to a depth of 3-4 inches.


                           BEFORE RADON REDUCTION

a)   CHARCOAL CANISTERS

EARLY SPRING CONCENTRATION:(State of New Jersey): 791 pCi/1

DATE                        LOCATION                       CONCENTRATION
                                                              (pCi/1)
  6/25 to 6/27                 On bar in basement                  409
                            (house closed)

  6/27  to  7/1               On bar in basement                  241
                            (house open)
                                     A-2

-------
b)     PYLON AB5 WITH PASSIVE RADON DETECTOR  CONTINUOUS  MONITOR:
DATE
LOCATION
CONCENTRATION
   (pCi/1)
6/25 to 7/1
7/15 to 7/18
On bar in basement
(house closed )

On bar in basement
'450  avg.
'720  max.

'3.5  avg.
'13   max.
a)   CHARCOAL CANISTERS
                            AFTER RADON  REDUCTION
DATE
LOCATION
CONCENTRATION
   (PCI/1)
7/31
8/15
8/17
8/18
11/17
to
to
to
to
to
8/2
8/17
8/19
8/21
11/20
On bar in basement
same
same
same
same-heat on
3
5
4
2.
2



.8
.9
 b)     PYLON AB5 WITH  PASSIVE  RADON  DETECTOR CONTINUOUS  MONITOR:
DATE
LOCATION
CONCENTRATION
   (pCl/1)
 8/15  to  8/21
On bar in basement
(house closed  )
"0 min.
12 max.
*4 avg.
                                      A-3

-------
                       If A It
                        A"  Floorplan
Kitchen
Lav
                           Family
                            Room
                                  Down
                                       Bedroom
                 Dining Room
                                     li
0
                                                           New Heating Supply Ducts
                                                                       Master
                                                                      Bedroom
                                                   thru closet
                                           Down
                                                 Living Room
          nT
                                                                         CT.
                                                                       c
                                                                            »T.
                                                                Duct thru Closet'


                                                                   Bedroom
                                               •To fans in attic.

', 1
: P









•; ' ;•;•










. . • . Floor Grills Sealed
Slab on Grade

./*




i 1M



i

'




J-






y








































































Basement

\U\ Chimney
H 	 Up

Sub Slab Ventilation Du
\
L

Sump Hole






rt
I
\n

•







f

-

                                                    Footer Drains
                            A-4

-------
                            RADON REDUCTION PLAN

House Code:      CAS

Phase I

Basement Area

    Since this house has a finished basement, special effort will be made to
cover or enclose duct and pipe work.

1.  Seal sub-slab heating ducts.

2.  Seal wall and floor crack penetrations  (several large openings around
    existing ducts).

3.  Punch hole in floor of furnace room and evacuate.

    a.  exhaust pipe to exit building via roof.

Slab-on-Grade Area

1.  Seal and depressurize sub-slab ductwork.

    a.   drill openings "1.3 cm  ("1/2") through transite duct where access
         allows.  EPA Guidelines should be  followed for this activity.

2.  run new heating ducts to the kitchen and living room area.


Phase II

Basement Area

1.  Ventilate block wall either actively or passively.

Slab on Grade Area

1.  Seal perimeter crack at slab-block intersection being careful to allow for
active or passive ventilation of the perimeter crack at a later date.
                                     A-5

-------
                                                        HOUSE TESTS
                                                         House  C8A
                                                         (4/30/Bfi|
(ft!
Temperature   Temperature   Barometric
    In           out         pressure    Correlation
  'C I'M      'C CFI       Pascals     coefficient
                  Effective
                 Leakage Area
  ACII at         (I.HI. Method)
50 Pascals    cm^ (square inches)
     Equivalent
    Leakiige  Area
 (Canadian Method)
c«' (square  Inches I
iMsencnl
fill
(21 .
Uasc
6)1
(21 .
Undo
6)1
(21 .
.6
600)
•lent
.6
600)
door
.6
600)
door open : * ' '
21

(70) 21 (701 30.00 0.999 420 0.533 9.40

1 . 608 .
(249.
7
35)
2.719
(421
4
.51)
door closed: ' ^1
21

closed
21

(70) 21 (70) 30.00 0.985 357.50 0.533 8.01

: (3)
170) 21 (70) 30.00 0.998 353.93 0.544 8.26

1.369.
(212.

1.375
(2)3
7
30)

.5
21)
2.315
(358

2.347
(363
.6
.92)

.7
.89)
                                                     41*      •*  1

                                                     HOUSE FUSSUKE if»*cm
                                                                                                  I  -
                                                                                                                  4   u>      n •>
                                                                                                                 uoust russuu (F..C.I.)
           (I)

-------
House Code:  C30A
       A-7

-------
               REPORT ON MEASUREMENTS AND RADON REDUCTION PLAN
HOUSE CODE:      C30A

DESCRIPTION:   This is a split-level house with an unfinished half-basement.
An enclosed patio was added to the back of the house behind the family  room.
The residents prefer their home to be very warm (about 24'C, 75°F),  and heavy
insulation was found in the attic.

DIAGNOSTIC INVESTIGATION:    Leakage was found at the uncapped block tops  and
in the space around the utility meter window.  A major crack below grade was
located on the front wall of the house and a baseball-sized hole was located
between the internal basement wall and the back wall of the house. Upstairs,
further leakage was found around the kitchen and bathroom.  Access to the
attic is through the garage.  Chimney stack to the basement was located in the
plumbing chase.  The force air heating ducts ran under the slab.  Grab  sample
measurement of air in these ducts showed concentrations as high as 53.000
pCi/1.  Concentrations in the drain tile around the sump were 36,000 pCi/1 and
in the sump hole itself they were 2100 pCi/1.
                           BEFORE RADON REDUCTION

a)   CHARCOAL CANISTERS

-LATE SPRING CONCENTRATION:(State of New Jersey): 2254 pCi/1
DATE                        LOCATION                       CONCENTRATION
                                                                (pCi/1)
 6/7  to 6/9                  basement-house closed                1450

 6/9  to 6/14                 basement                             498



 b)    PYLON AB5 WITH PASSIVE RADON DETECTOR  CONTINUOUS  MONITOR:
 DATE                         LOCATION                        CONCENTRATION
                                                                (pCi/1)
  6/6  to  6/13                 Basement                        max.  "  2600
                                                            min.  '   75
                                     A-8

-------
                            AFTER RADON REDUCTION
a)   CHARCOAL CANISTERS
DATE                        LOCATION                       CONCENTRATION
                                                                (pCi/1)
6/27 to 7/2
6/27 to 7/2
7/3 to 7/5
7/5 to 7/7
7/7 to 7/9
11/17 to 11/20
dining room 2
4
3.
2.
3.
4.


5
4
4
1
b)    PYLON AB5 WITH PASSIVE RADON DETECTOR CONTINUOUS MONITOR:
DATE                                LOCATION                CONCENTRATION
                                                                (pCi/1)
6/26 to 6/27                        basement                max " 8
                                     level I radon          min " 0
                                             reduction
                                             plan

7/3 to 7/10                         basement                max " 20
                                     level II radon         min " 2
                                              reduction
                                              plan

8/7 to 8/3                          basement                max " 20
                                                            min " 0
                                     A-9

-------
                         11,11
                          A" Floorplan
     Kitchen
Lav
Family
 Room
                                     Down
                                               Bedroom
                  Dining Room
                                                               New Heating Supply Ducts
                                                                            Master
                                                                           Bedroom
                                                       Duct thru closet
                                                   Down
                                                     Living Room
                                        •     T c  T.  c •
                                        1   r   '<=     «
                                            Duct thru Closet'


                                               Bedroom
                                                   *To fans in attic.


1

: |
Basement

-T-I-T— I !*i Chimney
* 	 -Up




                        Floor Grills Sealed

                    Slab on Grade
                                           I
                                                                Sub Slab Ventilation Duct ;'
                                             Sump Hole 1 •{
                                                        Footer Drains
                             A-10

-------
                            RADON REDUCTION PLAN


House Code:     C30A

Phase I

Basement Area


1.  Seal and evacuate sump hole (see attached diagram).

    (a)  exhaust pipe to exit building through roof with care taken to
         minimize visual impact on living areas

2.  Seal wall and floor cracks and penetrations

         (specifically seal open block tops on each side of basement window,
         at corner where slab level attaches to basement wall and other
         locations where open blocks are found during site inspection.

3.  Supply makeup combustion air to furnace area  (passively)

Slab-on-Grade Area

1.  Seal and depressurize sub-slab duct work

    (a)  drill openings ("1/2") through transit duct where access allows.  EPA
         guidelines should be followed for this activity.

2.  Run new heating ducts to the kitchen and living room area.

3.  Seal perimeter crack at slab-block intersection being careful to do  it in
    such a way as to allow future active or passive ventilation of the
    perimeter crack at a later date.
                                     A-ll

-------
          Mop Board
   Expansion Joint
   (With Homosote F1
   Concrete Slab
                          Sheetrock
     Earth Fill
Scale
  \- = r
             Pipe To Outside
                       Fan
                  4" PVC Pipe
            Galvanized Cover
      Slab
                         Sump Hole

  '2 Stone
1/2" Plywood
2x4 Stud Wall
2x4 Sill
                                        Solid L - Block
                                        8" Concrete Block
                                        (Hollow Core)
                                           J
             Block Wall
                           Clay Weeping Tile
                             A-12

-------
IIODSK TKSTS
llouau C30A
(4/30/B(i|
Ti-«|jei aim c Te>perature Baroaetrlc
Vuliix: In (ml pressure Correlation
•3 (fi3) 'C CM *C CFI Pascals coefficient
ll.isi.-mont door cloned: '''
•107. B 21 (70) 21 (70) 30.00 0.993
( 14 .400)
( refer to gruuh (2) )
611 6 21 (70) 21 (70) 30.00 0.999
(21 .600)
Effective
Leakage Area
ACII at (I.HI. Method)
C N 50 Pascals cm2 (square Inches)
353.30 0.536 12.03 1.359.6
(210.74)
335.86 0.568 8.63 1.351.0
(209.40)
Equivalent
Leakage Area
(Canadian Method)
c«2 (square Inches)
2.305.48
(357.35)
2.358.6
(365.59)
0)

-------
House Code:  C39A
     A-14

-------
                    REPORT ON MEASUREMENTS AND MITIGATION
HOUSE CODE:     C39A

DESCRIPTION:    This is a split level house with half-basement. The basement
is not finished.  The house has a garage. The basement was built with sump
hole. Forced air heating ducts pass under the slab.

DIAGNOSTIC INVESTIGATION:    Potential areas of infiltration were found in
open block, 2 large cracks along the front basement wall.  Leaks around
ventiliation ducts and sewer lines were sampled and showed a concentration of
2900 pCi/1. Grab samples ranged from 140-800 pCi/1.  The air duct register in
the family room read 7 pCi/1.
                     BEFORE RADON REDUCTION MEASUREMENTS

a)   CHARCOAL CANISTERS

EARLY SPRING CONCENTRATION:(State of New Jersey): 1500 pCi.l
DATE     LOCATION                                            CONCENTRATION
                                                               (pCi/1)
6/70 to 6/11                                                 basement
    10.4

8/19 to 8/21                                                 basement
    7.5

9/21 to 9/23                                                 basement
    8.3
                                     A-15

-------
b)
PYLON AB5 WITH PASSIVE RADON DETECTOR CONTINUOUS MONITOR:
DATE
         LOCATION
CONCENTRATION
   (pCi/1)
6/6 to 6/13
    max " 230
8/7 to 8/13
    max " 1250
                                                       basement
                                                             mm
                                                             avg
                                                               o
                                                              40
                                                       basement

                                                       min
                                                       avg "
                                                                     10
                                                                     30
                                     A-16

-------
                     AFTER RADON REDUCTION MEASUREMENTS
a)   CHARCOAL CANISTERS
DATE
LOCATION
CONCENTRATION
   (PCI/1)
11/17 to 11/20
basement- (heating on)       4.3
b)    PYLON AB5 WITH PASSIVE RADON DETECTOR CONTINUOUS MONITOR:
DATE
LOCATION
CONCENTRATION
   (pCi/1)
8/29. to 9/3
 11/4 to 11/17
basement -
  Level I radon         max " 14
          reduction     min "  1
          plan          avg "  9

basement -
 Level II radon         max " 14
          reduction     min "  0
          plan          avg "  7
                                     A-17

-------
                         'A"  Floorplan
     Kitchen
Lav
          Family
          Room
                                    Down
                                             Bedroom
                  Dining Room
                                                             New Heating Supply Ducts
                                                               cfl
                                                       Master
                                                      Bedroom
                              4..L-Duct thru closet*
                                                                          Ltl
                                                 Down
                                                   Living Room
                                                              . C
                                                                              C
                                                                       Duct thru Closet*
                                                       Bedroom
                                                 •To fans in attic.
-.  .  Floor Grills Sealed

Slab on Grade
                                                            Basement
                                                                   Chimney
                                                              •Up
                                                              Sub Slab Ventilation Duct ;'
                                                                                 I  /
                                                                          	
                                                      Footer Drains
                          A-18

-------
                            RADON REDUCTION PLAN
House Code:     C39A

Phase I

Basement Area
1.  Seal and evacuate sump hole (see attached diagram).
    (a)  exhaust pipe to exit building through roof with care taken to
         minimize visual impact on living areas

2.  Seal wall and floor cracks and penetrations

         (specifically seal open block tops on each side of basement window,
         at corner where slab level attaches to basement wall and other
         locations where open blocks are found during site inspection.

3.  Supply makeup combustion air to furnace area  (passively)

Slab on Grade Area

1.  Seal and depressurize sub-slab duct work
    (a)  drill openings "1.3 cm ("1/2") through transit duct where access
         allows.  EPA guidelines should be followed for this activity.

2.  Run new heating ducts to the kitchen and living room area.

3.  Seal perimeter crack at slab-block intersection being careful to do it in
such a way as to allow future active or passive ventilation of the perimeter
crack at a later date.

Phase II

1.  Increase fan to "15.2 cm (6") diameter

2.  Inspect for holes and cracks previously missed and seal.
                                    A-19

-------
          Mop Board
   Expansion Joint
   (With Homosote  Fill) x
   Concrete Slab
                          Sheetrock
     Earth Fill
Scale
  r = r
              Pipe To Outside
                        Fan
                  4' PVC Pipe
            Galvanized Cover
      Slab
              \T
                         Sump Hole
  f2 Stone
1/2" Plywood
2x4 Stud Wall
2x4 Sill
                                         Solid L - Block
                                         8" Concrete Block
                                         (Hollow Core)
                           Clay Weeping Tile
             Block Wall
                              A-20

-------
                                                                   IIOIISK  TKSTS
                                                                   Hauae  C39A
                                                                     (4/30/86)
          Temperature  Temperature    Barometric
 Volume        In           out          pressure   Correlation
m3 (fi3)     'C CKJ      *C  (*IM        Pascals    coefficient
                          Effective                Equivalent
                         Leakuye  Area             Leakage Area
          ACM  at         (I.HI.  Method)          (Canadian Method)
N       50  Pascals   c«2 (square Inches)    cm^  (square inches)
Iliiscmrnl door closed: '''
1.1 1
(21.
Hu.Si:
61 J
(21.
.6 21 (70) 15.6 (60) 30.00 0.996 324.14 0.506 6.52
600)
mi.'iit door o|ien: ''I
.6 21 (70) 15.6 (60) 30.00 0.907 283.35 0.589 7.89
600)
1 .263
(185

1.172
(181
.1
.29)

4
73)
1 .970
(305

2.085
(323
.8
.47)

.6
.27)
                                 41*     «•  »»

                                llOUSl fKXSSUIE (r»»c«IO
                            ^   to      > •>
                           uuusc riussuu (P..t.i»)

-------
House Code:   C46A
        A-22

-------
                    REPORT ON MEASUREMENTS AND MITIGATION
HOUSE CODE:   C46A

DESCRIPTION:  This is a split-level with half slab and a, half, semi-finished
basement.  The basement has been divided into 2 rooms with the larger of the
two with indoor/outdoor carpeting and wall panelling covering the cinder
block.  An attached garage is approximately 6" below the slab of the house.

DIAGNOSTIC INVESTIGATION:  No major cracks or openings were found in the
basement, although it was impossible to investigate walls and floor in the
finished portion of the basement.  A floor drain was concealed in a closet.
Grab samples in the floor drain ranged from 13,000 to 19,000 pCi/1.
                     BEFORE RADON REDUCTION MEASUREMENTS

a)   CHARCOAL CANISTERS

WINTER CONCENTRATION:(State of New Jersey):.635 pCi/1
DATE                                LOCATION                CONCENTRATION
                                                                (PCi/1)
6/25 to 6/27                        basement  (house closed)      771.9

6/27 to 6/29                        basement                     433

7/31 to 8/9                         basement                     157


b)    PYLON AB5 WITH PASSIVE RADON DETECTOR CONTINUOUS MONITOR:
DATE                                LOCATION                CONCENTRATION
                                                                (PCi/1)
6/25 to 7/1                         basement  -  closed        max.  "  1100
                                                             min.  *  900
                                                             avg.  "  950

8/7  to 8/13                        basement                 max.  *  600
                                                             min.  "   30
                                                                  *  220
                                     A-2 3

-------
                     AFTER RADON REDUCTION MEASUREMENTS
a)   CHARCOAL CANISTERS
DATE
                                    LOCATION
                        CONCENTRATION
                            (pCi/1)
8/7  to 8/9


12/9 to 12/11

1/3/87 to 1/5/87
basement (After Level 1)     238.5
 radon reduction

family room                    5.3

basement
b)    PYLON AB5 WITH PASSIVE RADON DETECTOR CONTINUOUS MONITOR:
DATE
LOCATION
CONCENTRATION
   (PCi/1)
 8/7  to 8/13
11/21 to 11/23
basement
basement
max.
min.
avg.

max.
min.
avg.
30
 3
13
 17
  4
  9
                                   A-24

-------
                         'A"  Floorplan
     Kitchen
Lav
Family
 Room
                                     Down
                                              Bedroom
                  Dining Room
                                                              New Heating Supply Ducts
                                                                cfl
                                              Master
                                             Bedroom
                                                 Vr— Duct thru closet4
                                                  Down
                                                    Living Room
                                                C  "[.  C
                                                                        Duct thru Closet*
                                              Bedroom
                                                  *To fans in attic.
                        Floor Grills Sealed

                    Slab on Grade


1

*

r





V


































Basement

j BJ Chimney
^ 	 Up







1
1
i
                                                               Sub Slab Ventilation Duct »
                                                                                   \   ffl  !
                                                                         Sump Hole
                                                       Footer Drains
                             A-25

-------
          Mop Board
   Expansion Joint
   (With Homosote F1
   Concrete Slab
                         Sheetrock
     Earth Fin
Scale
  r= r
             Pipe To Outside
                       Fan
                 4- PVC Pipe
            Galvanized Cover
      Slab
1/2" Plywood
2x4 Stud Wall
2x4 Sill
                                        Solid L - Block
                                        8" Concrete Block
                                        (Hollow Core)
                                          J
                         Sump Hole
  '2 Stone
                           Clay Weeping Tile
             Block Wall
                            A-26

-------
                            RADON REDUCTION PLAN
House Code:

Phase I

Basement Area
C46A
1.  Seal and evacuate sump hole  (see attached diagram).
    (a)  exhaust pipe to exit building through roof with care taken to
         minimize visual impact  on living areas

2.  Seal wall and floor cracks and penetrations

         (specifically seal open block tops on each side of basement window,
         at corner where slab level attaches to basement wall and other
         location that open blocks are found in during site inspection.
Slab on Grade Area

1.  Seal and depressurize sub-slab duct work

    (a) drill openings "1.3 cm  ("1/2") through transit duct where access
        allows.  EPA guidelines should be followed for this activity.

2.  Run new heating ducts to the kitchen and  living room area.

3.  Seal perimeter crack at slab-block intersection being careful to do it in
such a way as to allow future active or passive ventilation of the perimeter
crack at a later date.

Phase II

1.  Increase fan to 15.24 (6")  diameter

2.  Inspect for holes and cracks previously missed and seal.
                                    A-27

-------
                                                                          HOUSE TESTS
                                                                          House C46A
                                                                           <4/30/8fi|
                   Tca|>er<)i
-------
House Code:  C10B
     A-29

-------
              REPORT ON MEASUREMENTS AND READON REDUCTION PLAN
HOUSE CODE:   C10B

DESCRIPTION:  This is a split foyer house with a finished lower level divided
into a family room,  2 bedrooms,  a 2 piece bathroom and a utility room.  The
family room has a woodstove and poured concrete patio behind the family room.

DIAGNOSTIC INVESTIGATION:  Few entry routes were located due to the finish on
the slab level floor.  A grab sample in the plumbing access in upstairs
bedroom tub showed a concentration of 0 pCi/1.  The slab perimeter crack was
exposed in places showing one likely source of infiltration.
                     BEFORE RADON REDUCTION MEASUREMENTS

a)   CHARCOAL CANISTERS

EARLY SPRING CONCENTRATION:(State of New Jersey):.  670 pCi/1
DATE
LOCATION
CONCENTRATION
   (pCi/1)
8/15  to  8/17

8/17  to  8/19

8/17  to  8/19

8/17  to  8/19
family room

family room

family room

family room
     15.8

      9.8

      4.2

      2.5
                                   A-30

-------
  Fan
Undergrade
Pipes
Lav.
                            Family Room
                                                     Utility
                                                                  Garage
                                       A-31

-------
                                                                            HOUSE TESTS
                                                                            House C1OU
                                                                             14/30/80)
 Volume
*3 (fi:>)
                      apiH-iit in e   Temperature   Baroiietrlc
                        In           out          pressure   Correlaliun
                      T. CKI      *C ('I-')        Pascals    coefficient
                 Effective
                Leakage  Area
  ACH at        |I.HI.  Method)
50 Pascals   c»2 (square Inches)
     Equivalent.
    Leakage Area
 (Canaillan Netluid)
:a2  (s<|iiare Incites)
           JO-i .5
          (14,
                          (70)
                                    21.1  (70)
                                                 30.00
                                                            0. 905
                                                                             255.77   0.667
                                                                                               14.63
                                                                                                      I.179.80
                                                                                                       (182.87)
 2.255.16
  (349.55)
OJ
CO

-------
House Code:   C31B
        A-33

-------
               REPORT ON MEASUREMENTS AND RADON REDUCTION PLAN
HOUSE CODE:   C31B

DESCRIPTION:  This is a bi-level home.   The downstairs portion is divided  into
general use rooms.  The utility room and furnace is located here.  The garage
has been partially finished with a raised wooden floor.  A storage room has
been added on behind the utility room.   All living areas are finished.

DIAGNOSTIC INVESTIGATION:  Grab samples were taken under wood floor above
garage slab: 3000 pCi/1; and in various walls,  all less than 40 pCi/1.  A  grab
sample in an open block was 5 pCi/1.
                     BEFORE RADON REDUCTION MEASUREMENTS

a)   CHARCOAL CANISTERS

EARLY SPRING CONCENTRATION:(State of New Jersey):.   691 pCi/1
DATE
LOCATION
CONCENTRATION
   (PCi/1)
5/28 to 6/1

6/1  to 6/4

8/15 to 8/17

8/17 to 8/21
lower level                  8.2

lower level                  4.4

lower level - house closed   89.

lower level                  76.6
                                    A-34

-------
b)    PYLON AB5 WITH PASSIVE RADON DETECTOR  CONTINUOUS  MONITOR:
DATE
LOCATION
CONCENTRATION
   (pCi/1)
8/15 to 8/21
Lower Level
     max. " 260
     min. "   5
     avg. "  65
                     AFTER RADON REDUCTION MEASUREMENTS
a)   CHARCOAL CANISTERS
DATE
LOCATION
CONCENTRATION
   (PCi/1)
11/9

11/9 to 11/15

11/17 to 11/20
Music Room

Music Room

Music Room (Heat on)
     4.0

     4.0

     5.8
b)    PYLON AB5 WITH PASSIVE RADON DETECTOR CONTINUOUS MONITOR:
DATE
                                    LOCATION
                        CONCENTRATION
                           (pCi/1)
11/9 to 11/15
                                    Music Room
                             5.8
                                      A-3<

-------
   Fan
Undergrade
Pipes
Lav.
                            Family Room
                                                    Utility
                                                                Garage
                                     A-36

-------
                            RADON REDUCTION PLAN
House Code:
Phase I
C31B
1.  In a trench about 2.54 cm.  (I1) deep  (below slab level), lay PVC pipe
around the outside of three block walls of the house.  One connection on each
of the three walls to a fan will provide  suction on the block walls.  (See
attached diagram).

2.  Seal perimeter crack on the lower level with polyurethane caulk.

3.  Seal all plumbing penetrations.

Phase II

1.  Supply makeup air to the  furnace.

2.  Passively supply dilution air to the  cold air return ducts.  When the
circulating system is on,  it  should draw  in approximately 100 cfm of outside
air to dilute radon levels.
                                     A-37

-------
                                                                            HOUSK TKSTS
                                                                            House C31B
                                                                             14/30/86)
         Teupcruture  Tenperature   Barometric
Viiliinu:        In           out         pressure    Correlation
                                      Pascals     coefficient
m3 (fi31     •(:  CF)      •(: (•(••)
                                                                                                 ACII at
                                                                                               50 Pascals
                                                                                                                 Effective
                                                                                                                Leakage Area
                                                                                                                (I.HI, Method)
                                                                        Equivalent
                                                                       Leakage Area
                                                                    (Canadian Method)
                                           en2  (si|uare  Inches)     cm2 (square  Inches)
           464 .4
          I 16.400)
                       21 (70)
                                    21.1  (70)
                                                 30.00
                                                            0 907
                                                                             305.01    0.585
                                                                                               11 .03
                                               1 .254.8
                                                (194.50)
                                                                                                                          2.223.8
                                                                                                                            (344.69)
OJ
CO
S
|

I   -,,
                                                                          4   *•

                                                                          HOUSE PRESSURE

-------
House Code:   C48B
        A-39

-------
               REPORT ON MEASUREMENTS AND RADON REDUCTION PLAN
HOUSE CODE:      C48B

DESCRIPTION:    This is a bi-level home.   The lower level is slab-partially-
below-grade  with only a small utility room and attached garage in an
unfinished state.  An enclosure was added over a poured concrete patio behind
the front-to-back family room.   A low crawl space under the ground level
entrance at  the front of the house gives  access to the front portion of the
foundation.

DIAGNOSTIC INVESTIGATION:     Few slab or wall penetrations were found. A hole
was drilled  in the floor of the front downstairs bedroom closet and a grab
sample showed a. concentration of 16,000 pCi/1. The foundation under the front
stoop was found to be incomplete causing earth to be exposed to the interior
structures of the house via the crawl space.  A small amount of crushed stone
was found under the slab.  The perimeter crack was a potential source of
infiltration.
                         PREMITIGATION MEASUREMENTS

a)   CHARCOAL CANISTERS

EARLY SPRING CONCENTRATION:(State of New Jersey): 936 pCi/1
DATE                                LOCATION                CONCENTRATION
                                                               (PCi/1)
5/30  to 6/1                         downstairs- house closed     771.9

6/1 to 6/4                          downstairs                   37.6

6/4 to 6/5                          downstairs                   4
                                    A-40

-------
b)    PYLON AB5 WITH PASSIVE RADON DETECTOR CONTINUOUS MONITOR:
DATE
LOCATION
CONCENTRATION
   (pCi/1)
11/4 to 11/9
downstairs
max " 30
ave."  8
                                     A-41

-------
                    B1-Level
                    i/8"= r
    Family Room
Bedroom
                         Lav
                        Storage
                                      Garage
Diningroom
             Kitchen
 Lwingroom
                          Lav
                          Lav
naster
Bedroom
                                            I
     C    C
                       Bedroom
                                       Bedroom
                      A-42

-------
                            RADON REDUCTION PLAN
House Code:
                C48B
                                                 a slab-partially-below-grade
    Bi-level with finished lower level.  This is
house with few penetrations through the slab.

Phase I
1.   Because there is some crushed stone under the slab the first attempt will
be to use sub-slab ventilation.  If at any point of installation this is not
effective then Phase II shall be implemented with the remainder of Phase I.

2.   The perimeter crack shall be sealed using backer rod or equivalent and
pourable polyurethane in such a way that the crack can later be ventilated.
See Figure 1 for details.
3.  All other slab penetrations shall be revealed and sealed.
plumbing stack, toilet soil pipe and water entry pipes.
                                                               These include
Phase II

1.  In addition to Phase I, the perimeter crack shall be evacuated (Another
alternative here is to go directly to air-to-air heat exchanger ventilation)

2.  Fault in the original construction affecting the foundation under the
steps will be repaired, replacing the present dirt and plywood portion with
block, then sealing any cracks.
                                     A-43

-------
                                                                 MOUSE TESTS
                                                                 House C488
                                                                  15/2/871
          Temperature  Temperature    Barometric
 Volnm:       in          out          pressure    Correlation
   (fi'M    'C (•!••)
*C CF)
                                      Pascals     coefficient
                         Effective
                        Leakage Area
          ACII at        (LBL Method)
N       50 Pascals   cm2 (square Inches)
    Equivalent
   Leakage Area
(Canadian Method)
m^ (square inrlics)
 3
-------
House Code:   C33C
        A-45

-------
                      REPORT ON MEASUREMENTS AND RADON REDUCTION PLAN
HOUSE CODE:     C33C

DESCRIPTION:    This is a 2 story colonial house on slab with attached double
garage and add-on room behind the garage.   Heating ducts run under the slab.
Soil was found to have substantially sub-sided under the slab.-  A continuous
perimeter crack was located around the slab.

DIAGNOSTIC INVESTIGATION:  Cracks in the floor tested with the smoke tube
showed air infiltration.  Similarly, air entered from a hole drilled in the
floor.  Air flow  was from the interior to the exterior at the baseboard.
Grab samples taken of family room air show 0  pCi/1 of radon.  Thermal by-
passes were found around the chimney, the attic scuttle and the plumbing
chase.


                          BEFORE RADON REDUCTION MEASUREMENTS

a)   CHARCOAL CANISTERS

EARLY SPRING CONCENTRATION:(State of New Jersey): 1190 pCi/1


DATE                                LOCATION                CONCENTRATION
                                                               (pCi/1)


6/22 to 6/24                        livingroom
                                     house closed                304.2

7/23 to 7/25                        livingroom
                                     house closed                106

7/25 to 7/27                        livingroom
                                     house closed                  8.7

7.27 to 8/1                         livingroom
                                     house closed                  8.5
                                    A-46

-------
b)    PYLON AB5 WITH PASSIVE RADON DETECTOR  CONTINUOUS  MONITOR:
DATE
LOCATION
                     AFTER  RADON  REDUCTION  MEASUREMENTS
a)   CHARCOAL CANISTERS
                                                             CONCENTRATION
                                                                (PCI/1)
6/16 to 6/24


7/23 to 8/1


livingroom max "
min ~
avg ~
livingroom max "
min "
avg
7500
0
2000
280
0
30
 DATE
LOCATION
CONCENTRATION
   (PCI/1)
 10/4  to  10/10


 10/4  to  10/10


 11/17  to  11/20



 11/17  to  11/20
small bedroom-
 R. R. Plan Level I

furnace room-
 R. R. Plan Level I

livingroom-
 R. R. Plan Level II
livingroom-
 R. R. Plan Level  II
     8.5
     5.8
     4.7
       calculated
       samples

     4.7
 R.  R.  = Radon Reduction
                                      A-4 7

-------
b)    PYLON AB5 WITH PASSIVE RADON DETECTOR CONTINUOUS MONITOR:
DATE
LOCATION
CONCENTRATION
    (pCi/1)
9/11 to 9/16
10/3 to 10/16
R. R. Plan Level I
R. R. Plan Level II
max
min
avg

max
min
avg
33
1
14

14
0
5
R.R.  = Radon Reduction
                                   A-48

-------
 C" and "D" Floorplan

Dining Room


















_
r












Up


Kitche










L






n






























r *t
ramHy
Room

W D
Bedroom

9 Sub
9 ,. Cl-ih
• Suctioc -'
Ducts








~
oarage



Bedroom

c





Bedroom

B
Ba









ath
th

Down





Q


C




C


c

Master
Bedroom







Bedroom


o — -- Fan in Attic

™ I thru rioor i







A-49

-------
                               RADON REDUCTION PLAN

House Code:     C33C

Phase I

    Slab-on-Grade-Area

I.  Seal heating grills from the sub-slab ductwork with plasticized concrete,

2.  Vent sub-slab ductwork through storage area over garage to roof turbine.
    Use 15.3 cm (6") duct and K-6 fan mounted in attic.

3.  Seal floor cracks and penetrations
    (specifically seal perimeter crack at wall slab joint, leaving a small
    cavity beneath the seal that could later be ventilated, and plumbing
    penetrations through slab)

4.  Supply makeup combustion air to furnace area.

5.  Run new heating ducts to the kitchen and livingroom areas.

Phase II

    Slab on grade area

1.  Ventilate perimeter crack with small fan.

2.  Add heat recovery ventilation.

Phase 111
3.  Increase fan on perimeter crack to 6" diameter size.
                                    A-50

-------
IIOUSK TESTS
House C33C
(5/2/86)
Temperature Temperature Barometric
Volume hi o»l pressure Correlation
m3 Ifl3) *C Cl-'l *c <"F) Pascals coerflcient
.IB9.9 2) (70) 21.1 (70) 30.00 0.9U2
( 17.300)
Effective
Leakage Area
ACII at (I.U1. Method)
C N SO Pascals cm^ (square Inches)
142.74 0.776 10.34 776.06
(118.74)
Equivalent
Leakage Area
(Canadian Method)
cm (square inches)
1 .618.38
(250.85)
  «     »        fc  »»
HOUSE russuu  (r..c.i.)

-------
House Code:   C32D
      A-52

-------
               REPORT ON MEASUREMENTS AND RADON REDUCTION PLAN


HOUSE CODE:   C32D

DESCRIPTION:  This is a 2 story colonial with basement and garage.  An
enclosed deck with crawlspace attaching to the basement through a former
exterior window was added on.  A sump hole was located in the basement.

DIAGNOSTIC INVESTIGATION:  The block wall was extremely porous with several
large cracks.  Pressure under the slab was found to be different on opposite
sides of the basement implying some sub-slab blockage.  Several major floor
cracks were found.  Grab sampling in the air above the sump hole showed a 1200
pCi/1 level.  Interior basement air that was grab sampled was found to range
from 3 - 360 pCi/1.  Post-level I diagnostics revealed in leakage around
basement windows and at the  block to wood juncture of the building.


                     BEFORE  RADON REDUCTION MEASUREMENTS

a)   CHARCOAL CANISTERS

EARLY SPRING CONCENTRATION:(State of New Jersey):.  1357 pCi/1


DATE                                LOCATION                CONCENTRATION
                                                                (pCi/1)
6/19 to 6/21                         basement                      29.1

6/21 to 6/24                         living  room                    7.2
                                      A-53

-------
b)    PYLON AB5 WITH PASSIVE RADON DETECTOR CONTINUOUS MONITOR:
DATE
                                    LOCATION
                        CONCENTRATION
                            (pCi/1)
6/16 to 6/25


8/29 to 9/3


7/23 to 8/11


living room max.
min.
avg.
living room max.
min.
avg
basement min.
max.
avg.
" 120
0
" 30
" 44
3
	
0
' 130
' 43
                     AFTER RADON REDUCITON MEASUREMENTS
a)   CHARCOAL CANISTERS
DATE
LOCATION
CONCENTRATION
   (PCi/1)
9/21 to  9/26
11/17 to 11/20
12/9 to 12/11
12/9 to 12/11
basement
 level I R.R.

basement
 fans sealed

family room
 level II R.R. heat on

basement
      20.1


       8


       5.1

      11.3
R.R.  = Radon Reduction
                                    A-54

-------
b)    PYLON AB5 WITH PASSIVE RADON DETECTOR  CONTINUOUS  MONITOR:
DATE
LOCATION
CONCENTRATION
   (pCi/1)
8/29  to  9/3
9/3   to  9/20
11/17 to 11/21
Level II - 1 fan
 R.R.
      II - 2 fans
                                     R.R.
Level II -
 R.R. exhaust raised
mm.
max.
avg.

min.
max.
avg.
                                                            min.
                                                            max.
                                                            avg.
  3
 55
 20

  5
180
 73
          3
         10
          5.7
R.R. = Radon Reduction
                                     A-55

-------
                      «r«  —J  »r\"
                       C"  and  "D" Floorplan
                                                        W   D
 Dining Room
                      Kitchen
                                    Bedroom







1 * * D










r















Up













L







































Room

9 Sub
^— — z^j- - • Slab
• f _ . •,
1 Suctmr -

Ducts








GdT3Q6



Bedroom
  Bedroom
               Bath
              Bath
                Down
                ;  c  •
   Master
   Bedroom
Bedroom
                                                             Fan in Attic
                                                               thru Roof
                                                             Storage
                     A-56

-------
                                                                 HOUSE TESTS
                                                                 House C34D
                                                                  (5/2/66)
          Temperature  Temperature
 Volume       In          (nit
•3 (ft3)    *C ('I-')     'C CF)
            Barometric
             pressure   Correlation
             Pascals    coefficient
                 Effective
                Leakage Area
  ACH at        (LBL Method)
50 Pascals   cm2 (square  Inches)
     Equivalent
    Leakage Area
 (Canadian Method)
:m'  (si|uarc Inches)
 636. B
(22.488)
             21 (70)
17.8 (64)
                                      30.00
                                                 0.997
                                         295.65    0.591
                                                           7.96
                                                                           1.227.6
                                                                            (190.28)
 2.188.9
  (339.28)
                                                                 HOUSE russuu; (r..c.i.)

-------
House Code:   C24E
        A-58

-------
                    REPORT ON MEASUREMENTS AND MITIGATION
HOUSE CODE:   C24E
DESCRIPTION:  This is a split level with open earth crawlspace under the
living room and kitchen.  The lower slab on grade level is 1/2 finished.  The
interior of this house has been recently renovated.  The finished slab on
grade portion has a fireplace and woodstove.

DIAGNOSTIC INVESTIGATION:  The crawlspace area is open earth and extremely
damp.  It is the principle location of soil gas entry to the house.
Foundation was blasted out of bedrock.
                     BEFORE RADON REDUCTION MEASUREMENTS

a)   CHARCOAL CANISTERS

WINTER CONCENTRATION:(State of New Jersey): 426 pCi/1
DATE
LOCATION
CONCENTRATION
   (PCi/1)
8/15 to '8/17



8/17 to 8/19

8/19 to 8/21
lower level
 near crawlspace
 (house closed)

lower level

lower level
     90.9

      2.5

      1.3
                                    A-59

-------
b)    PYLON AB5 WITH PASSIVE RADON DETECTOR CONTINUOUS MONITOR:
DATE
                                    LOCATION
                        CONCENTRATION
                            (pCi/1)
9/3  to 9/9
                                    lower  level
                        min. "    7
                        max  " 210
                        avg. "   73
                     AFTER RADON REDUCTION  MEASUREMENTS
a)   CHARCOAL CANISTERS
DATE
LOCATION
CONCENTRATION
   (pCl/1)
9/25  to  9/30


12/9  to 12/1



12/9  to 12/11
lower level
 near crawlspace

lower level
 near crawl space
 heat on

living room
 above crawlspace
 heat on
      3.0
      7.2
                                                                 12.3
                                  A-60

-------
                            RADON REDUCTION PLAN

House Code:     C24E

Level I

1.   Work will concentrate on sealing and isolating the crawlspace.

2.   Two layers of six mil plastic will be supported by a ankadrain fiber mat
and roofing paper.  This entire assembly will be sealed to the block walls of
the crawlspace using first a caulking compound and then fir wood trim nailed
through the three layers to the block.

3.   The block wall will be punctured at the back of the house and pipe will be
set in puncture and fitted with a fan.  The fan will vent to the outside of
the house  and be  covered with a shield.

4.   The interior  opening to the crawlspace will be fitted with rubber sealing
so as to allow access but prevent in-leakage of air to room.

Level II

1.   Increase fan  to 15.24 cm (6") diameter.

2.   Three  wall suction  from the exterior of the slab-on-grade level of the
house on three walls.

3.   Sealing around the  interior perimeter.
                                     A-61

-------
HOUSE TESTS
House C24E
Tenpei aim c Temperature Baroaetrlc
Voliion- in out pressure Correlation
•3 (fr'l *C CM 'C Cfl Pascals coefficient
35B .8 21 (70) 21.1 (70) 30.00 O.U96
( 12,67;;)
Effective
Leakage Area
ACH at (I.BL Method!
C N 50 Pascals cm2 (square inches)
3A4.S3 0.596 17 . 7fi 1.522.45
(235.9B)
Equivalent
Leakage Area
(Canadian Method)
cm2 (square inches)
2.724 .96
(422.37)
M
                                                                                             4   t.       •• ••
                                                                                           MOUSE rustuu (r»»u)

-------
            APPENDIX B




HOMEOWNER PERMISSION FORM
                B-l

-------
                            AGREEMENT NO.  	

                                   BETWEEN

                      RESEARCH TRIANGLE INSTITUTE (RTI)

                                     AND

                 OWNER(S) AND/OR TENANT(S) OF OCCUPIED HOME

                              NAME(S) - OWNERS
                              NAME(S) - TENANTS

             I/We, as owners of the house and lands located at:


                                 Clinton. NJ

           or I/We, as tenants of the house and lands located at:
                                 Clinton. NJ


agree to participate in a study sponsored by the U.S. Environmental Protection
Agency (EPA) and the New Jersey Department for Environmental Protection and
conducted by Research Triangle Institute (RTI), to develop experimental low-
cost radon mitigation methods for these premises; and I/we, hereby authorize
Research Triangle Institute's authorized representatives to install mitigation
devices or otherwise take any necessary steps to attempt to mitigate the  radon
presence, if any. within the house and/or on the premises of the address  given
above.

    I/we understand that this authorization will allow Research Triangle
Institute's representatives to have access to this house and its surroundings
during reasonable working hours during a period beginning 	 and
continuing through 	,  at no cost to RTI, to the EPA. the  U.S.
Government, and the State of New Jersey.

    I/we realize that for effective mitigation RTI may be required to modify
the house design and/or structure for a reasonable period of time agreed  upon
between the parties to this agreement, in writing, and that with its "Best
Efforts" RTI will attempt to return the house to an "as found" condition, at
no charge to the Homeowner(s) and/or Tenant(s).  In consideration for my/our
being selected to participate in this study and other considerations. I/we
agree to indemnify and hold harmless RTI. the U.S. Government, and the State
of New Jersey for any injury to person or damage to property that may occur as
a result of the work done or omitted by or for RTI and/or the U.S. Government
and/or the State of New Jersey in connection with this study, including
without limitation, modifications to the house design and structure and the
installation of mitigation devices.  I/we have been advised that the process
                                        B-2

-------
of installing mitigation equipment may result in a temporary increase in radon
concentrations on the premises and that I/we may temporarily vacate the
premises during the mitigation process at no cost to RTI, the U.S. Government
or the State of New Jersey, or I/we may accept the inconvenience of the
process and remain on the premises, understanding that all steps reasonably
necessary will be taken to minimize these inconveniences.

    RTI will treat the data and resident locations as confidential.  All
reports to parties other than the EPA will be coded to prevent recognition of
the premises participating in the study.

    I/we understand that any mitigation devices or installations will remain
attached to the premises and become the property of the owner,  and RTI, the
U.S. Government, and the State of New Jersey shall have no responsibility for
the maintenance of such devices or the subsequent use or removal of such
devices: and we further understand that these procedures are experimental in
nature and that RTI, the U.S. Government, and the State of New Jersey make no
promises, nor accept any liability nor have responsibility for the success or
failure of the mitigation process, and I/we hereby agree to hold RTI and the
Government harmless for any of the possible detrimental effects of radon
exposure directly resulting from the performance of the process outlined
herein.

    Subscribed to the 	day of            , 1986.
                                                 Research Triangle Institute
                                                 Authorized Agent
Homeownerfs]
Tenant(s)
Witness
                                   B-3

-------
                                TECHNICAL REPORT DATA
                          (Please read Instructions on the reverse before completing)
 1 REPORT NO.
 EPA-600/8-87-027
                                                       3. RECIPIENT'S ACCESSION NO.
 4. TITLE AND SUBTITLE
 Development and Demonstration of Indoor Radon
  Reduction Measures for 10 Homes in Clinton, New
  jersey            ___^_	
                                                      5. REPORT DATE
                                                       July 1987
                                                      6. PERFORMING ORGANIZATION CODE
7.
          Linda D. Michaels, Terry Brennan,
 Andrew Viner, Arthur Mattes,  ana William Turner
             8. PERFORMING ORGA
             471U-3065-52
 g PERFORMING ORGANIZATION NAME AND ADDRESS
 Research Triangle Institute
 P.O. Box 12194
 Research Triangle Park, North Carolina 27709
                                                       10. PROGRAM ELEMENT NO.
                                                      11. CONTRACT/GRANT NO.
                                                       68-02-3992, Task 5
 12. SPONSORING AGENCY NAME AND ADDRESS
 EPA, Office of Research and Development
 Air and Energy Engineering Research Laboratory
 Research Triangle Park, NC 27711
                                                      13. TYP6 OF REPORT AND PERIOD COVERED
                                                       Task Final; 4/86 -  1/87
                                                      14. SPONSORING AGENCY CODE
                                                        EPA/600/13
 15. SUPPLEMENTARY NOTES AEERL project officer is Michael
 919/541-4113.
                                                     C.  Osborne,  Mail Drop 54,
 16. ABSTRACT
               repOr^- discusses the development and demonstration of indoor radon
 reduction methods for 10 houses in Clinton,  New Jersey,  where (in the spring of 1986)
 the New Jersey Department of Environmental Protection  (DEP) located a. cluster of
 houses with extremely high radon levels. The work was to be completed before the
 1986-87 winter heating season began.  The demonstration  houses were selected from
 56 in the Clinton Knolls subdivision.  All of these houses had shown radon concentra-
 tions in excess  of 64 pCi/1 when monitored in the spring of 1986.  Each house was
 inspected,  and 10 representative houses were selected for the radon reduction demon-
 stration project. Following intensive diagnostic work and monitoring in each house,
 house- specific radon reduction plans were developed.  With the  agreement of the
 homeowners,  radon reduction systems were installed during the summer of 1986.
 All 10 of the houses had radon concentrations reduced significantly by the fall of 1986.
 The average cost  of radon reduction was S3, 127.
 7.
                             KEY WORDS AND DOCUMENT ANALYSIS
                DESCRIPTORS
                                          b.lDENTIFIERS/OPEN ENDED TERMS
                                                                    c.  COSATI Field/Group
 Pollution
 Radon
 Atmosphere Con-
 tamination Control
 Residential Buildings
 Monitors
                   Ventilation
Pollution Control
Stationary Sources
Indoor Air
Soil Gas
13B
07B

06K
13 M
14G
                                                                          13 A
 Release to Public
                                           19. SECURITY CLASS (This Report)
                                           Unclassified
                                          20. SECURITY CLASS (This page)
                                          Unclassified
                          1. NO. OF PAGES'
                              174
                         22. PRICE '	
EPA Form 2220-1 O-73)
                                         B-4

-------