EPA/ROD/R03-95/187
                                December 1994
EPA Superfund
      Record of Decision:
       USA Aberdeen Proving Ground
       Operable Unit 2, MD
       10/11/1994

-------
Interim Remedial-Action
U.S. ARMY ABERDEEN PROVING GROUND
OLD O-FIELD SOURCE AREA
(O-Field Operable Unit 2)

Aberdeen Proving Ground, Maryland
      RECORD OF DECISION
                 FINAL DOCUMENT
                   September 1994
  In accordance with Army Regulation 200-2, this document is
  intended to comply with the National Environmental Policy Act
  (NEPA) of 1969.

-------
                       DECLARATION FOR THE RECORD OF DECISION


SITE NAME AND LOCATION

Old O-Field Source Area, Edgewood Area, U.S. Army Aberdeen Proving Ground, Maryland.

STATEMENT OF BASIS AND PURPOSE

       This decision document presents a selected interim remedial action for the Old O-Field Source
Area, which is Operable Unit 2 (OU2) of the O-Field Area at Aberdeen Proving Ground, MD. The selected
remedial action was chosen in accordance with the requirements of the Comprehensive Environmental
Response,  Compensation, and Liability Act  of  1980 (CERCLA), as amended  by the Superfund
Amendments and Reauthorization Act of 1986 (SARA), and to the extent practicable, the National Oil and
Hazardous Substances Pollution Contingency Plan (40 CFR 300). This decision document explains the
factual basis for selecting the remedy for OU2 and the rationale for the final decision. The information
supporting this remedial action decision is contained In the Administrative Record for this site.

       The State of Maryland Department of the Environment concurs with the selected remedy.

ASSESSMENT OF THE SITE

       Actual  or threatened  releases of hazardous substances from the site, if not  addressed by
implementing the response actions selected In this Record of Decision (ROD), may present an imminent
and substantial endangerment to public health, welfare, or the environment

DESCRIPTION OF THE REMEDY

       This operable unit is the second of four that are planned for the site. The first operable unit (OU1)
addresses the contaminated  groundwater emanating from Old O-Field, and the remedy for OU1 is
currently under construction. This Record of Decision has been developed for Operable Unit 2 (OU2) of
the O-Fleld area This remedy addresses the principal threat posed by the site, which is the potential for
an accidental release of chemicals into the air. The function of this operable unit is to reduce the risk of
an accidental release of chemical warfare materials (CWM) from the site by minimizing the possibility of
a fire at the site, reducing the likelihood and potential effects of an unplanned detonation of ordnance,
and minimizing both the likelihood and the potential  effects of evaporative release of CWM from a
subsurface release.  The selected remedial action is an interim remedy, and will allow for continued
investigation into a more permanent remedy.

       The major components of the selected remedy include:

       A Permeable Infiltration  Unit (PIU) Witt be constructed  on top of the sfta  The PIU will be
       constructed principally of sand and other granular materials. Construction of the PIU will reduce
       the threat of a release of CWM by covering the site with non-flammable materials, which will serve
       to cut off the air flow to the surface of Old 0-FIeld, stop erosion and stabilize the soil, provide a
       blast-resistant layer on top of the ordnance, and provide a vapor barrier to reduce the emission
       of CWM from an underground releasa

  •    An air monitoring system will be installed within the PIU to detect the presence of CWM within the
       pore spaces of the sand.

  •    A sprinkler system win be constructed on top of the PIU that will be capable of quickly spraying
       water or other solutions on the PIU.  If a CWM release is  detected by the air monitoring system,
       then the sprinkler system will be activated.  The water sprayed onto the  PIU will form a vapor
       barrier within the sand to prevent an air release of CWM and will also hasten the degradation of
       CWM.

-------
        Treatabiirty studies will be performed using the sprinkler system to apply water or other solutions
        to the PIU.  The results of these studies will be used to evaluate the feasibility of enhanced
        leaching of the contaminants from soil and buried containers to the groundwater. In addition, the
        surface of the PIU will be monitored to evaluate the rate of subsidence of Old 0-Field.

   •     The ability of the groundwater extraction and treatment system that is under construction for OU1
        (contaminated groundwatsr emanating from OW 0-Field) to capture arid treat the contaminated
        groundwater emanating from Old 0-Field will be verified.  In addition, the effectiveness of the
        groundwater monitoring program to detect  changes in the site hydrogeology and groundwater
        chemistry will be verified.

        The remedy specified herein will be one component of the overall remedy for the 0-Field area
This action will be consistent with any current or planned future remedial actions for the site to the extent
practicable.

STATUTORY DETERMINATIONS

        This selected remedy is protective of human health and the environment, complies with Federal
and State requirements that are legally applicable or relevant and appropriate to this remedial action, and
is cost effective.   Although this action  Is not intended  to  fully address the statutory mandate  for
permanence and treatment to the maximum extent practicable, this interim action is in furtherance of that
statutory mandate.  Because  this action does not constitute the final remedy for OU2, the statutory
preference for remedies that employ treatment that reduces toxicrty, mobility, or volume as a principal
element, although partially addressed by this remedy, will be addressed more fully by the final response
action.  Subsequent actions will address the threats posed by the conditions at the site to the maximum
extent practicable.

        Because this action will result in hazardous substances remaining on-site above health-based
levels, a review win be conducted within five years after implementation of this remedy to ensure that the
remedy continues to provide adequate protection of human health and the environment  Because this
is an interim action,  review of this site and of this remedy  will continue as the Army and the U.S.
Environmental Protection Agency (EPA) continue to develop final remedial alternatives for the O-Field area
                         Richard WJragemann
                        Major Genual, U.S. Army
             Commander, U.S. Acm/Aberdeen Proving Ground
                            Lewis D. Walker                                     Date
                  Deputy Assistant Secretary of the Army
              (Environment, Safety, and Occupational Health)
                                  Kostmayer                                   Date
                         Regional Administrator
             U.S. Environmental Protection Agency, Region III

-------
                               TABLE OF CONTENTS

Section                 -                                                    Page

DECLARATION FOR THE RECORD OF DECISION	  j

1.0 SITE NAME, LOCATION, AND DESCRJPTION	  1-1

2.0 SITE HISTORY AND ENFORCEMENT ACTIVITIES	  2-1
      Z1    HISTORY OF OLD O-FIELD 	2-1
      2.2    CLEANUP ACTIVITIES AT OLD O-FIELD	  2-2
             221  UC Dean Dickey's Affidavit 	  2-2
             2.22  U.S. Army Technical Escort Unit Surface Sweeps of Old O-Field	2-3
      23    PRESENT CONDfTION OF OLD O-FIELD 	  2-3
      2.4    PREVIOUS INVESTIGATIONS	  2-3
             2.4.1  Environmental Survey	2-3
             2.4.2  Records Review	  2-4
             2.4.3  Surface Water Quality Study	2-4
             2.4.4  Hydrogeologic Investigation	2-4
             2.4.5  RCRA Facility Assessment	  2-4
             24.6  Focused Feasibility Study of Old O-Field Source Removal Options  	2-4
             2.4.7  Old O-Field Groundwater Treatment Remedy 	2-5
             2.4.8  Groundwater and Surface Water Sampling, FalM991  	2-5
             2.4.9  O-Field Area Remedial Investigation/Feasibility Study  	2-5

3.0 HIGHLIGHTS OF COMMUNITY PARTICIPATION	  3-1

4.0 SCOPE AND ROLE OF OPERABLE UNIT OR RESPONSE ACTION	4-1

5.0 SUMMARY OF SITE CHARACTERISTICS	  5-1
      5.1     CONTAMINANTS AT OLD O-FIELD	5-1
      5.2    POTENTIAL  ROUTES OF CONTAMINANT MIGRATION AND ROUTES OF
             EXPOSURE	  5-1
      5.3    POPULATION AND ENVIRONMENTAL AREAS THAT COULD BE AFFECTED BY
             THE CONTAMINANTS ATTHE SITE	5-2
      5.4    SITE-SPECIFIC FACTORS THAT MAY AFFECT REMEDIAL ACTIONS AT THE
           .  SITE	5-2

6.0 SUMMARY OF SITE RISKS	  6-1
      6.1     EVALUATION OF EXPLOSIVE HAZARD AT OLD O-FIELD	  6-1
      6.2    EVALUATION OF CWM HAZARD AT OLD O-FIELD	6-1
      6.3    RISKS ASSOCIATED WITH ACUTE EXPOSURES TO CHEMICAL AGENTS
             RELEASED AS A RESULT OF AN EXPLOSION OR SPILL	  6-2
      6.4    SUMMARY OF HAZARDS POSED BY OLD 0-FIELD	6^

7.0 DESCRIPTION OF ALTERNATIVES	7-1
      7.1    APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS	7-1
      7.2   ALTERNATIVE A: NO ACTION	7-1
      7.3   ALTERNATIVE B: LIMITED ACTION  	7-2
      7.4   ALTERNATIVE C: PERMEABLE INFILTRATION UNIT (PIU)	7-3
      7.5   ALTERNATIVE D: FOAM CAP	7-5
      7.6   ALTERNATIVE E: MULTI-MEDIA CAP	7-6

                                       iii

-------
                         TABLE OF CONTENTS (Continued)

Section            -                                                       Page


8.0 SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES	 3.-)
      8.1    NINE EVALUATION CRITERIA  	 8-1
      8.2    PROTECTION OF HUMAN HEALTH AND THE ENVIRONMENT	 8-2
      8.3    COMPLIANCE WITH ARARS	 8-3
      8.4    LONG-TERM EFFECTIVENESS AND PERMANENCE	 8-4
      8.5    REDUCTION OF TOXICITY, MOBILITY OR VOLUME THROUGH TREATMENT .... 84
      8.6    SHORT-TERM EFFECTIVENESS	 8-5
      8.7    IMPLEMENTABIUTY	 8-5
      8.8    COST	 8-6
      8.9    STATE ACCEPTANCE	 8-6
      8.10   COMMUNITY ACCEPTANCE  	 8-8
      8.11   SUMMARY OF DETAILED EVALUATION	 8-8

9.0 SELECTED REMEDY	 9-t
      9.1    REMEDIATION GOALS	 9-1
      9.2    COST OF SELECTED REMEDY	 9-1

10.0 STATUTORY DETERMINATIONS	 10-1
      10.1   PROTECTION OF HUMAN HEALTH AND THE ENVIRONMENT	 10-1
      10.2   COMPLIANCE  WITH  APPLICABLE  OR  RELEVANT  AND APPROPRIATE
            REQUIREMENTS	 10-1
            10.2,1  Chemical-Specific ARARs	 10-1
            10.Z2 Location-Specific ARARs	 10-1
            10.Z3 Action-Specific ARARs	 10-2
            10.2.4 Other Criteria, Advisories, or Guidance To Be Considered for the
                  Remedial Action (TBCs)	 10-2
      10.3   COST EFFECTIVENESS	 10-2
      10.4   UTILIZATION OF PERMANENT SOLUTIONS AND ALTERNATIVE TREATMENT
            TECHNOLOGIES (OR RESOURCE RECOVERY TECHNOLOGIES) TO THE
            MAXIMUM EXTENT PRACTICABLE (MEP)	 10-2
      10.5   PREFERENCE FOR TREATMENT AS A PRINCIPAL ELEMENT	,	 10-2

11.0 SELECTED REMEDY	,	 11-1

1ZO REFERENCES	 12-1


APPENDIX A: RESPONSIVENESS SUMMARY
                                      IV

-------
                                     LIST OF FIGURES

Figure                                                                               Page

1 -1     Location of U.S. Army Aberdeen Proving Ground	  1-2
1-2    Location of the 0-Fie!d Area within the Edgewood Area of APQ 	  1-3
1-3    Location of C-Field Disposal Sites  	  1-4
                                     UST OF TABLES

Table                                                                                Page

8-1     Comparison of Costs for Old 0-Field Remedial Alternatives  	  8-7
9-1     Summary of Costs for the Selected Remedy-Alternative C: Permeable Infiltration Unit	9-3

-------
 1.0 SITE NAME. LOCATION. AND DESCRIPTION

                    »

        The U.S. Army Aberdeen Proving Ground (APG)  is a  72,516-acre installation located in
 southeastern Baltimore County and southern Harford County, Maryland, on the western shore of the upper
 Chesapeake! Bay (Figure 1-1). Tfc9 installation is bordered to the east and south by the Chesapeake Bay,
 to the west by Gunpowder Falls State Park, the Crane Power Plant and residential areas; and to the north
 by the towns of  Edgewood, Magnolia, Perryman, and Aberdeen. APG is divided into two areas by the
 Bush River the Edgewocd Area of APG lies to the west of the river and the Aberdeen Area lies to the
 east.

        The 0-Field area is an area of approximately 259 acres located on the Gunpowder Neck peninsula
 in the Edgewood Area (Figure 1-2). It is bordered on the north and east by Watson Creek, on the south
 by H-Field, and on the west by the Gunpowder River.  Watson Creek drains into the Gunpowder River
 through a narrow culvert under Watson Creek Road  The Gunpowder  River,  in turn, drains into
 Chesapeake Bay.

        The O-Field area contains two (2) known disposal areas and one (1) suspected disposal area
 (Figure 1-3). The northern disposal area is designated as Old O-Field,  and this area was used for
 disposal activities from the late 1930s to 1953. Old O-Field is located adjacent to Watson Creek and east
 of Watson Creek Road. South of Old O-Field and east of Watson Creek Road is the second area, known
 as New O-Field New O-Field was used from the mid-1950s to the earty 1980s as a destruction and
 disposal area  The suspected disposal area known as the 'Pit Site* Is on the west side of Watson Creek
 Road near the Gunpowder River. The 'Pit Site* was reportedly used from the late 1930s to mid-1950s as
 a disposal area.

        Old O-Field is a 4.5-acre site that was used by the Army for the storage, handling, disposal, and
 destruction of  chemical warfare materials  (CWM), decontaminating chemicals, ordnance, laboratory
 samples, and contaminated equipment The site is located within a restricted area of APG, and access
 to the site is strictly controlled The site is surrounded by a chain-link fence, which is supplemented by
 other physical security countermeasures, and is patrolled on a 24-hour basis.

       Old O-Field is located on a local topographic high, approximately 15 feet above sea level There
 is approximately 4 to 6 feet of relief across Old O-Field  The terrain slopes toward the east, to Watson
 Creek, and toward the west, to the Gunpowder River.  The area around Old O-Field is wooded and much
 of the .area around Watson Creek is a marsh. The groundwater underlying Old O-Field flows toward the
 east and northeast, and discharges to Watson Creek.

       At present, the construction of the Operable Unit 1 (OU1) groundwater extraction and treatment
system is underway, so workers are present at Firing Position 5 (located to the Immediate northwest of
Old O-Field). In addition, workers are present at H-Field (south of New O-Field) and M-Field (north of Old
O-Field). Large numbers of civilian and military personnel work on the northern Gunpowder Neck and
within the industrial areas of Edgewood Area

       The  residential areas closest to Old O-Field  lie approximately 2.7  miles norm (on-post military
housing within the Edgewood Area of APG), 3  miles to the west (Graces Quarters, Maryland)  and 4.5
miles to the north-northwest (Edgewood Maryland and Joppatowne, Maryland). In addition, Kent County,
Maryland lies 6 miles west of Old O-Field
                                             1-1

-------
          CMMUS

       0          10 MHJ*

10   •  0     lOMLOMintt
                                Figure 1-1
              Location of U.S. Army Aberdeen Proving Ground
                                   1-2

-------
                     PENNSYLVANIA
39
                                                                  76'l5'
                             MARYLAND

                               Baltimore
                       Washington DC


                      VIRGINIA
     White
     Marsh
Edgewood
  area
                                               PROVING S GROUND
     Base from US. Geological Survey. 1:100.000.
                                                  1
   2 MILES
                                            0^23 KILOMETERS
                                 Rgure 1-2
              Location of the O-Reld Area Within the Edgewood Area of APG
                                   1-3

-------
           76V
76°17'30"
39'20'45"
39°20'30"
          US6S, 1991
                                               Figure 1-3
                                     Location of O-Field Disposal Sites

-------
 2.0  SITE HISTORY AND ENFORCEMENT ACTIVITIES

                    »
        APG was established in 1917 as the Ordnance Proving Ground and was designated a formal
 military post in 1919. Testing of ammunition and other equipment and operation of training schools began
 at APG in 1918- Between this time and the onset of World War II, activities at APG included research and
 development and large-scale testing of a wide variety of munitions, weapons, and other equipment
 immediately prior to and during World War II, the pace of testing increased greatly.  During the war,
 personnel strength at APG exceeded 30,000. Similar but smaller-scale increases in development and
 testing activities were experienced during the Korean and Vietnam conflicts.

       APG's primary mission continues to be the testing and  development of weapons, munitions,
 vehicles, and a wide variety of support equipment Within the Edgewood Area, chemical warfare research,
 development,  and related activities  have occurred.  Specific activities at Edgewood have included
 laboratory research, field testing of chemical munitions, pilot-scale manufacturing, and production-scale
 chemical agent manufacturing.

       Many areas of the Gunpowder Neck of the Edgewood Area have been used as impact areas for
 the testing of ordnance; as such, ordnance have been tested and fired into various areas and there is the
 potential for encountering unexploded ordnance (UXO) and/or intact or leaking liquid-filled rounds
 deposited during testing and firing. Disposal and testing activities have also taken place in areas along
 the Gunpowder Neck.  O-Field and J-Field were the major disposal areas (the disposal history of O-Pield
 is discussed in more detail below). Currently, testing of combat tracked vehicles occurs at H-Field (to the
 south of O-Field), and testing of obscurants  (e.g., smoke screens) takes place at M-Field (immediately
 north of O-Field).


 2.1    HISTORY OF OLD O-FIELD

       Periodic disposal of waste materials at the O-Field area began before World War II; the first
 documented usage of Old O-Field occurred in May 1941  (Yon et ai, 1978), although other records
 suggest that disposal  activities occurred in the late 1930s.  Disposal consisted of placing the items in
 excavated trenches and  then covering the trenches with soil.  Records indicate that some of the burial
trenches were  100 yards long, 10 feet deep, and 10 feet wide; however, most known trenches are much
shorter. The existence of 35 trenches  is documented in the historical records (Yon et aL, 1978). However,
inspection of survey notes and historical aerial photographs reveals that the trenches and pits are not
distinct As disposal activities continued, trenches were created which appear to overlay and intersect
other trenches. Because of this, the total number of trenches and their locations is not known. The last
pit used for disposal of materials within Old O-FIeid was closed in June, 1953.

       During  the  period  of 1941 to  1949, tons  of chemlcal-filled/explosJve-toaded munitions,
contaminated plant equipment, pipes, and tanks were buried or placed on the ground surface in the area
of Old  O-Field  Interviewed personnel stated that the area contained 55-galton drums of mustard and
lewisite (blistering agents); items filled with chloroacetophenone, chtoroacetophenone in chloroform (tear
agents), and adamsfte (vomiting agent); munitions containing explosive charges; and munitions filled with
white phosphorus and other CWM.

       During August 1946, the unloading and decontamination operations of the SS Francis L Lee, a
Liberty ship containing mustard-filled  German munitions captured during World War II, were conducted
at Edgewood Arsenal  The ship was  anchored in the eastern channel of the Chesapeake Bay between
Worton Point and Stoops Point The material was then loaded onto barges and towed up the Bush River
                                            2-1

-------
to the Edgewood dock.  Contaminated empty German bombs (formerly mustard-filled), contaminated
wood, and dunnage were placed at Old 0-Field for disposal.
                          *
       In June 1949, a spontaneous ignition occurred in one of the disposal pits at Old 0-Field where
a large variety of chemical-filled/explosive loaded munitions had been buried. As a result of this explosion,
a broad area was contaminated with CWM. and unsxploded ordnance was dispersed around the araa.
Immediately  after this incident, an inspection was conducted by the Armed Services Explosive Safety
Board A directive was issued cabling for a thorough cleanup of the contaminated area In November
19
-------
        Other portions of LTC Dickey's affidavit indicate that, although a large quantity of disposed
 materials have been recovered from the surface of Old O-Field and some of the pits,  a much larger
 quantity of munitions, .bulk containers, and other items potentially remain buried  at the site.


 2.2.2  U.S. Army Technical Facort Unit Surface Sweeps of Old O-F!eld

        From the late 1960s io the early 1970s, the U.S. Army Technical Escort Unit performed surface
 sweeps of the area A number of suspect CWM-filled rounds were recovered from Old O-Field, temporarily
 stored in Conex containers at Old O-Field, and then transported and stored in the storage bunkers at N-
 Field.


 2.3     PRESENT CONDITION OF OLD O-FIELD

        At present, Old O-Field Is heavily vegetated.  Some of the trees have diameters as large as 8
 inches and are more than 20 feet in height; this indicates that their tap roots probably extend through the
 upper confining unit  Smaller bushes cover and obscure the remainder of the field. Small animals such
 as foxes have been observed inside the fenced area

       The surface of the field is highly irregular; there are areas where deep subsidence has occurred.
 This indicates that the trenches and pits are eroding and collapsing.  Currently, the remains of four
 trenches are visible in the field.  A large number of ordnance  items, drums, pipes, ammunition crates,
 canisters, and miscellaneous scrap metal items are visible on the surface of the field and within the open
 trenches. •

       In addition to the items present within the fenced area of Old 0-Fleld, a large number of UXO
 items were encountered outside of Old O-Field during the construction of access roads in support of the
 Operable Unit 1 groundwater treatment system project The presence of these items outside of Old O-
 Field is most likely due to the 'kick-out* of items during  past  detonation events and to past disposal
 activities. These items pose a hazard to workers engaged in any project in the vicinity of Old O-Field, and
 an accident involving these items may have an impact on Old O-Field, Including the initiation of fires or
 detonations.
2.4    PREVIOUS INVESTIGATIONS

       This section summarizes the results of the environmental studies that have been conducted at
Old O-Field. Because this ROD is focused on the source area of Old O-Field, existing groundwater and
surface water quality data are not presented in this summary.

2.4.1  Environmental Survey

       An Environmental Survey of the Edgewood Area of APQ was conducted in 1977 and 1978 by the
U.S. Army Toxic and Hazardous Materials Agency  (USATHAMA), now known  as the U.S.  Army
Environmental Center (AEC)  (Nemeth et aL, 1983), to determine 8 chemical contamination from past
operations was presenting a hazard to  the off-post environment  Analysis of a groundwater sample
collected from a monitoring well located immediately east of Old O-Field contained arsenic, volatile organic
compounds (VOCs), and 1,4-dithiane (a thermal breakdown product of mustard) at concentrations above
1,000 Ajg/L; semi-volatile compounds were detected at lower levels. These results indicate that VOCs and
chemical agent degradation products are being released by Old O-Field into the groundwater.
                                             2-3

-------
 2.4.2  Records Review

        A records review (Yon et aJ., 1978) used available documents  and personnel  interviews to
 reconstruct a general history of site operations at 0-Field. 'The investigation found that Old 0-Field
 contained 35 disposal pits, and 3 additional pits exist on the west side of Watson Creek Road. A later
 ravrew o? historical survey nctas showed that only one pit may have been west of Watson Cree« floaa,
 whereas two of the suspected pits were within Old 0-Field (Parks. 1986).

 2.4 3 Surface Water Quality Study

        The U.S. Army Environmental Hygiene Agency (AEHA) conducted a surface water quality and
 biological study of Watson Creek and nearby creeks (U.S. Army Environmental Hygiene Agency, 1977}.
 Due to a lack of tidal flushing in Watson Creek, unusually high organic loading was detected.

 2.4.4 HvdrooeoloQlc Investigation

        In 1984, the U.S. Geological Survey (USGS) began a study to investigate the source, extent, and
 possible migration of contaminants from the Old O-Field site. The final report by Vroblesky et al. (USGS,
 1991) presents a preliminary characterization of the contamination of the groundwater, surface water, and
 bottom sediment in the O-Field area of APG, and describes the probable hydrologic and chemical effects
 of relevant remedial actions on the groundwater at the site.

 2.4.5 RCRA Facility Assessment

        In 1986, while the USGS study was ongoing, the U.S. Environmental Protection Agency (EPA)
 issued a Resource Conservation and Recovery Act (RCRA) permit to APG to address  Solid Waste
 Management Units (SWMUs) with potential to release hazardous wastes to the environment  A RCRA
 Facility Assessment (RFA) report by Nemeth (1989) documents historical activities at the Edgewood Area
 of APQ related to solid waste management, and Identifies and describes SWMUs.   One of the
 recommendations of the report is that consideration be given to additional investigative work addressing
 the New O-Field area (Nemeth, 1989).

 2.4.6 Focused Feasibility Study of  Old O-Fleld Source Removal Options

       In 1987, the Army performed  an engineering study for Old O-Field that addressed the feasibility
 of implementing source control (ICF Technology, 1987). This work was performed for the Environmental
 Management Office of Aberdeen Proving Ground (now part of the Directorate of Safety,  Health, and
 Environment [OSHE]). The study identified remedial alternatives that Included source removal, in-place
destruction, and permanent isolation. More than a dozen remedial alternatives were evaluated in this
study; in addition, a variety of innovative excavation techniques were considered and screened. The
technologies evaluated as being potentially Implementable and effective are the following:

  •    In-situ vitrification of the entire mass of soil and materials contained within the limits of burial sites
       at Old O-Field;

  •    Entombment .of ail wastes and hazardous materials at the site;

  •    Mechanical excavation, sorting, and disposal or treatment of hazardous items at the site using
       remote-controlled equipment; and

  •    Hydraulic excavation of wastes and munitions at the field.
                                            2-4

-------
 The following conclusions were reached about the condition of Old O-Field and the need for a source
 control action such as would be accomplished by the above technologies:
                     *
        •      Based on the current state of understanding of Old O-Field, the total risk posed by the
               site to human health and the environment is lower than the risks posed by any corrective
               action at the site that involves destruction or removal activities.

        •      There are significant short-term risks posed by implementation of any of the considered
               technologies.

               None of the technoiogies considered is sufficiently developed to allow immediate selection
               and implementation at Old O-Field.  Research, development  and proof-testing of the
               technology would be required prior to implementation.

 2.4.7  Old O-Fleld Groundwater Treatment Remedy

        A Focused Feasibility Study (FFS)  was performed to evaluate remedial alternatives for the
 groundwater (OU1) at Old O-Field (USATHAMA, 1990). As part of this study, aquifer tests were performed
 to aid in designing  a groundwater extraction  system (USATHAMA,  1991b).   Treatabilrty tests were
 conducted to evaluate the implementability of various groundwater treatment technoiogies. A number of
 promising technologies were tested at both the bench- and pilot-scale.

        The data obtained from the treatability tests were used to select a preferred remedial technology.
 Groundwater extraction and treatment using chemical precipitation for removal of the inorganic analytes
 followed by ultraviolet oxidation for removal of the organic contaminants was selected as the proposed
 remedial treatment technology (USATHAMA, 1991c).  Treated groundwater will be discharged to the
 Gunpowder River. Based on the  results of the FFS, the aquifer tests, and the treatability studies, a
 Proposed Plan was developed which addresses groundwater extraction and treatment for the Old O-Field
 area (U.S. Department of the Army,  1991 a). A Record of Decision which documents the remedy selection
 was signed by the Army and U.S. EPA Region III in September 1991 (U.S. Department of the Army,
 199lb).

       The Army then developed the Conceptual Design for the groundwater extraction, treatment and
 discharge system (USATHAMA, 1991 d). Construction of the treatment plant is currently underway. Based
 on data gathered after completion of the Conceptual Design, air stripping and  carbon adsorption units
 have been added to the treatment train to provide greater flexibility in treating the organic compounds.
 When completed, this system will intercept and treat the contaminated groundwater emanating from Old
 O-Field. The purpose of the action is to prevent loading of contaminants into Watson Creek.

 2.4.8 Groundwater and Surface Water Sampling. Fall 1991

       In November 1991, the Army collected groundwater samples from all existing monitoring wells.
 Surface water samples were also collected from Watson Creek and the Gunpowder River. The purpose
 of the  investigation was  to obtain information  regarding present  levels of contamination for use in
 completing the design of the OU1 treatment plant

 2.4.9 O-Fleld Area Remedial Investigation/Feasibility Study

       Presently, the Army is performing an RI/FS of the entire O-Field study area The Rl consists of
the  installation of monitoring  wells and the collection and  analysis  of samples  from surface water,
sediment groundwater, air, and soil  Extensive soil gas surveys and geophysical surveys were also
                                            2-5

-------
performed. Surface soil samples were collected immediately outside the fence surrounding Old 0-Field
(due to safety restrictions on Old O-Field, personnel were not allowed inside the fence).

        Because the toxicfty of the military-specific compounds is not well known, toxicity tests were
conducted to evaluate potential impacts to aquatic life.  Macroinvertebrates were collected in sediment
in Watson Creek and the Gunpowder River and analyzed to eva/uate the potential for bioaccumulation
of contaminants.  Further hydrogeologic investigation of the area has been performed through aquifer
testing and groundwator flow modeling. Additional information concerning the RI/PS may be obtained
from the RI/FS Work  Plan (USATHAMA, 1992) and the Phase I Rl Report (APQ, 1994a).

        A Focused Feasibility Study for the Old 0-Field Source Area was developed (APQ, 1994b). This
report evaluated the risks posed by Old 0-Field and the potentially applicable remedial technologies for
mitigating these risks. The Proposed Plan for the Old O-Field source area (APQ, 1994c) and this Record
of Decision are based on the results of the Focused Feasibility Study report
                                             2-6

-------
3.0  HIGHLIGHTS OF COMMUNITY PARTICIPATION
                   *

       The Focused Feasibility Study Report and Proposed Plan for OU2 were released to the public in
June 1994.  Both of these documents are available in the Administrative Record and the information
repositories maintained at tha Harford County Library - Aberdeen Branch, Aberdeen, MD; Hajford County
Library - Edgewood Branch, Edgewood, MO; Washington College • Miller Library, Chestertown, MD; and,
Essex Community College Library, Baltimore, MD.  The notice of availability of these documents was
published in the Aegis (Harford County) on June 22, 1994; the Baltimore Sun on June 26, 1994; the
Avenue (Baltimore County) on June 30,1994; and the Kent County News on June 29,1994.

       The 45-day comment period was extended an additional 30 days based on a timely request This
75-day public comment period was held from June 22,1994 through September 5,1994. In addition, a
public meeting was held on July 14,  1994. At this meeting, representatives from APG, EPA, and MDE
presented a summary of the site conditions and remedial alternatives under consideration. A response
to the comments received  during this period is included in the Responsiveness Summary, which is part
of this Record of Decisioa

       This decision document presents the selected remedial action for OU2 of the Old O-Field area,
Aberdeen Proving Ground, Maryland. The remedy  has been  chosen in accordance with CERCLA, as
amended  by SARA, and,  to the extent practicable, the National Contingency Plaa  In addition, this
decision incorporates the findings of the FFS, which evaluated the remedial alternatives for OU2. The
decision for this operable unit is based on the Administrative Record.
                                           3-1

-------
 4.0 SCOPE AND ROLE OF OPERABLE UNIT OR RESPONSE ACTION


        Past disposal operations at the Old 0-Field area has led to contaminated soil and groundwater
 at and near Old 0-Field.  The Army has decided to manage the environmental contamination in the
 different .-r.edia at the Old 0-F:s!d a-oa in a phased approach. This separation of environmental meJia
 into Operable Units allows the U.S. Army to begin remediation prior to full assessment of the O-Field area
 Section 300.430(a)(1)(ii)(A) ot the NCR, 40 CFR 430(a)(1)(ii)(A), provides that CERCLA NPL sites 'should
 generally be remediated in operable units when early actions are necessary or appropriate to achieve
 significant risk reduction quickly, when phased analysis or response is necessary or appropriate given
 the -site or complexity of the site, or to expedite the completion of a total cleanup.* The Army's phased
 approach to O-Field is consistent with these objectives.

        An Operable Unit (OU) is  defined by the National  Oil and  Hazardous Substance  Pollution
 Contingency Plan (40 CFR 300.5) as a discrete action which is an incremental step toward comprehen-
 sively mitigating site problems.  The Operable Units for the O-Field area at APQ have been defined as
 follows:

        OU1:   Contaminated groundwater beneath and immediately downgradient of the Old O-Field
               disposal trenches which has been contaminated from past disposal practices;

        OU2;   Contaminant source area within the trenches at Old O-Field;

        OU3:   Contaminated surface water and sediment within Watson Creek; and

        OU4:   Contaminated soil and groundwater at New O-Field,

        The Army has already selected a remedy for OU1. The contaminated groundwater is a potential
 threat at this site because of the high levels of solvents and chemical agent degradation products
 detected in groundwater samples collected downgradient of Old 0-Field. Lower levels of explosives
 compounds and toxic metals have also been detected in downgradient groundwater. This project is in
 the construction phase and startup  and operation of the groundwater extraction and treatment system
 is scheduled to begin in December, 1994.  OU3 and OU4 require additional investigations and will be
 handled in separate actions.

        This remedy for OU2 addresses the principal threat posed by the site, which is the potential for
 an accidental release of CWM into the air. The function of this operable unit is to reduce the risk of an
 accidental release of CWM from the site by minimizing the possibility of a flre at the site, reducing the
 likelihood and effects of an unplanned detonation of ordnance, and minimizing both the likelihood and
 the potential effects of evaporative release of CWM from a surface or subsurface spilt The primary CWM
 at the site are believed to be mustard, phosgene, lewisite, and white phosphorus.

        Access to the  Old O-Fleld area is  currently restricted  by a  number  of  physical  security
 countermeasures.  Institutional controls are in place to preclude the possibility of trespassers and
 residential or industrial use of the area,

        This interim remedial action win  eliminate surface soil exposure pathways within the Old 0-FiekJ
area and reduce the threat of a catastrophic event due to an explosion and subsequent CWM release.
 It will also allow for continued study and testing  of approaches to reducing or  eliminating the toxic
contaminants at the site. The final remedy will be selected after an appropriate technology is identified
or developed. The interim action will be consistent with future actions.
                                            4-1

-------
 5.0 SUMMARY OF SITE CHARACTERISTICS

        This section  provides a summary of the nature and extent of contamination at Old O-Field, a
 discussion of potential routes of contaminant migration and routes of exposure, the population and
 environmental areas that could be affected by a release at the site, and site-specific factors that may affect
 rsmsdial actions at the sire.
 5.1     CONTAMINANTS AT OLD O-FIELD

        The available historical records concerning disposal and recovery of items at Old O-Field have
 been evaluated to identify the types and quantities of chemical agents expected to be in place at Old O-
 Field.   This information has been supplemented with data regarding the range of chemical agents
 contained in ordnance during the time period in which disposal took place at Old O-Field.

        Based on available historical information regarding disposal activities at Old O-Field, it is likely that
 mustard is the predominant CWM at Old O-FJeld (Yon, 1994).  Mustard was the most widely-deployed
 chemical agent during World War II, and historical records indicate that mustard was disposed at Old O-
 Field both in ordnance and in bulk quantities. Phosgene (a choking agent) was also commonly used, and
 historical records verify its disposal at Old O-Field.  The disposal of lewisite, tear agents, and adamsite
 (a vomiting agent) at Old O-Field has also been documented

        There are no data to indicate that  nerve agent-filled ordnance were disposed at Old O-Field.
 However, this does not rule out the possibility that nerve agents were disposed at Old O-Field in lab
 containers or other non-ordnance containers. Organophosphoms compounds have been detected in
 groundwater downgradient of Old O-Field, indicating the presence of nerve agent-related materials; this
 may be due to disposal of waste sludge from a pilot plant, disposal of nerve agent simulants, or the
 disposal of nerve agents. It is considered likely that the number  of nerve agent-filled containers at Old
 O-Field is very small because these items were produced at the Edgewood Area only for field testing, and
 items which did not function in testing were routinely destroyed In place on the test ranges. '

        In addition to  the above, it is believed that white phosphorus  exists at Old O-Field both in
 ordnance and other containers.  Because  white phosphorus spontaneously ignites and bums when
 exposed to air, the presence of white phosphorus leads to an elevated risk of spontaneous fire at Old 0-
 Field, which may result in detonation or other types of release.

        The primary non-CWM  chemicals disposed or used at Old 0-FIeld include DANC (principally
 1,1,2,2-tetrachloroethane), lime, and fuel oil  used in decontaminating activities.


 5.2     POTENTIAL ROUTES OF CONTAMINANT MIGRATION AND ROUTES OF EXPOSURE

        The analysis of groundwater samples collected from monitoring wells downgradient of Old O-Field
 indicate that high levels of chemical agent degradation products and VOCs exist at these locations.
 Lower levels of explosives compounds and toxic metals have also been detected in downgradient
 groundwater.  These results imply that the buried containers are leaking, and  the contaminants are
 percolating to the water table and migrating In groundwater toward Watson Creek.

       The construction and operation of the groundwater extraction and treatment system (as part of
the OU1  remedy) will eliminate this pathway of contaminant transport by intercepting the contaminated
 groundwater, treating it, and discharging the treated groundwater to the Gunpowder River.
                                             5-1

-------
        The types of CWM disposed at Old 0-Field hydrolyze readily when in contact with water, and the
 hydrolysis products are far less toxic than the original compounds. Therefore, the leaking of CWM from
 Old O-Field into the groundwater presents no threat to human health.

        The potential route of contaminant migration that poses the principal threat to human health and
 the environment is  an air release of CWM resulting from fire, accidental detonation of ordnance, or
 evaporative release.


 5.3     POPULATION AND ENVIRONMENTAL AREAS THAT  COULD  BE  AFFECTED BY THE
        CONTAMINANTS AT THE SITE

        The construction of the Operable Unit 1 (OU1) groundwater extraction and treatment system is
 presently underway, so workers are located at Firing Position 5 (immediately northwest of Old 0-Field).
 After construction is complete, full-time operators will be present at Firing Position 5 to operate the
 treatment plant These personnel will be within 100 yards of Old O-Field.

        In addition, workers are present at H-Field (south of New O-Field) and M-Field (north of Old 0-
 Field).  These workers are within 1/2 mile of Old 0-Field. Large numbers of civilian and military personnel
work on the northern Gunpowder Neck and In the industrial areas of the Edgewood Area, which is within
2 miles of Old 0-Field.

        The residential areas closest to Old O-Field He approximately 2.7 miles to the north (on-post
military housing within the Edgewood Area of APG), 3 miles to the west (Graces Quarters, Maryland) and
4.5 miles to the north-northwest (Edgewood, Maryland, and Joppatowne, Maryland). In addition, Kent
County, Maryland, lies 6 miles west of Old 0-Field


5.4     SITE-SPECIFIC FACTORS THAT MAY AFFECT REMEDIAL ACTIONS AT THE SITE

       The existence of both live ordnance and CWM at Old O-Field presents serious safety and security
concerns.  The protection of site workers and the community is of primary importance in this action.

  •     Ordnance may be shock- or pressure-sensitive, so actions that involve handling of ordnance and
        direct contact with the field must be minimized and carefully planned Invasive activities present
       the risk of accidental detonation and/or evaporative release of CWM.

  •    White phosphorus is known to be present within Old O-Reld   White phosphorus will bum if
       exposed to air. Therefore, clearing and grubbing of the Old O-Ffeld surface should be minimized

  •     Because the disposal and recovery activities have resulted in the creation of underground pits
       and trenches which may overlap, the surface soil at Old O-Reld is believed to be susceptible to
       collapse.  Trench collapse could  result in the shearing or  puncturing of ordnance or bulk
       containers, and potential release of CWM. To prevent this, the  weight placed on Old  O-Field
       should be minimized and controlled to the extent possible.
                                            5-2

-------
 6.0  SUMMARY OF SITE RISKS

        This section contains an evaluation of human health and environmental impacts associated with
 contamination in the Old O-Field source area  The Old 0-Fieid source area poses a challenge to risk-
 based decision making because of the unconventional hazards at the site.  The risks cannot be quantified
 by st3nr;arc< risk assessment techniques.  Nonetheless, the existence of a iarge volume and large variety
 of unexploded ordnance items, CWM in ordnance and bulk containers, and other items (contaminated
 equipment and lab samples) pose potential risks to human health and the environment

        The hazard posed by a situation consists of a combination of the probability of an event occurring
 and the effects of that event, as follows:

                                 Hazard =»  Probability X Effect

 In other words, if an event is not likely to occur (small probability) but the potential effects are very large,
 then that event may still dominate the total risk posed by the site. In this section, the following information
 is presented and evaluated:

   •     Potential explosive risks associated with unexploded ordnance;

   •     Potential risks posed by the CWM;

   •    Summary of risks.


 6.1    EVALUATION OF EXPLOSIVE HAZARD AT OLD O-FIELD

       The expected frequency and magnitude of a potential explosive event is evaluated in this section.
An explosive event consists of the unplanned detonation or burning of an explosiva The key factors that
may lead to an explosive event are shock/pressure, condition of the explosive, thermal effects, and time.

       The historical  data  concerning Old O-Field Include documentation of a number of explo-
sive/thermal events.  In addition, it is likely that  a number of undocumented events have occurred, and
the explosive reaction of a small item of ordnance may go unnoticed. However, based on available data
and judgment concerning the stability of the field, it has been estimated that the expected frequency of
explosive events at Old O-Field  is 1 to 3 events per ten-year period (APQ, 1994b).


6.2    EVALUATION OF CWM HAZARD AT OLD O-FIELD

       Historical data regarding disposal  and recovery activities at Old O-Field have been evaluated to
assess the relative amounts of CWM currently within Old O-Field. Because the data may be incomplete,
quantitative estimates cannot be derived with total accuracy. However, based on the Old O-Field historical
records and the Army records on testing and use of CWM-filled munitions, the following estimates on the
relative amounts of CWM at Old O-Field have been made:

       •      Approximately 90% of the  CWM-filled ordnance and bulk containers at Old O-Field may
              contain mustard;

       •      Between 5 to 10% of the remainder of the CWM-filled ordnance and bulk containers may
              contain phosgene;
                                            6-1

-------
        •      The remainder of CWM-filled ordnance and bulk containers may contain lewisite and other
               materials.  These other materials may include cyanogen  chloride, tear agents, and
               adamsite.

        •      A conservative estimate for the potential number of nerve agent-filled ordnance is 0.3%
               of the total number of ordnance Kerns.

 The majority of ordnance items have been buried for more than 40 years.


 6.3     RISKS ASSOCIATED WITH ACUTE EXPOSURES TO CHEMICAL AGENTS RELEASED AS A
        RESULT OF AN EXPLOSION OR SPILL

        The history of Old  0-Field Indicates that explosions and fires have occurred in the past  The
 nature of the site indicates that, In the absence of site remediation, it Is likely that explosions or fires may
 occur in the future. Furthermore, the potential presence of CWM In ordnance and bulk containers poses
 the possible hazard of a release of chemical agents to the atmosphere with resulting airborne migration
 to nearby areas.

        Because of the large number of uncertainties concerning the quantity, condition, and location of
 ordnance within Old O-Field, definitive statements regarding the effect that fires and explosions would
 have on human health and the environment cannot be made. However, a qualitative assessment of the
 CWM hazards posed by the field in the event of a fire or explosive release was performed.

        If a release occurs, individuals working at the nearby fields (H-FIeld, M-Field, and New O-Field)
 would be the  most likely receptors. However, human populations in areas considered relatively remote
 to Old O-Field could potentially be exposed to a vapor cloud. These populations include the following:

        •       Workers on the Gunpowder Neck and nearby ranges;

        •       Personnel working within the Industrial areas of Edgewood Area and civilians and troops
               housed at Edgewood Area;

        •       People  involved in commercial  or recreational fishing or boating activities  on the
               Gunpowder River or Upper Chesapeake Bay; and

        •       People living off-post near Graces Quarters and the towns of Edgewood and Magnolia

       The magnitude and duration of exposures depend on the specific situation (e.g.,  type of release,
 amount of agent released, type of agent, wind speed and direction, and weather conditions).  However,
even under worst-case weather conditions, the effects of a release at Old O-FiekJ would most likely not
be detected in areas beyond H-FIeid and M-Field.  The more remote off-site locations would not be
affected by an explosion or fire event at Old O-Field unless a large quantity of CWM-filled rounds detonate
under stable weather conditions, which is highly unlikely.

       Even though the likelihood that an explosion or fire would cause adverse human health effects
in off-site communities is small, the  hazards posed to on-site workers and the environment may be
significant
                                            6-2

-------
6.4    SUMMARY OF HAZARDS POSED BY OLD O-FIELD
                    f
       The contaminant transport pathway that  poses the highest  n'sk to  human health  and the
environment consists of a release of CWM as the result of fire or explosion. The probability of such an
gvsnt is lo-.v tut not insignificant and the history of Old O-Fie'd includes a number of unplai med explosion
and fire events. In addition, the potential results of a catastrophic event are of such a high magnitude
that the possible consequences must be addressed.

       The presence of both CWM and ordnance presents the possibility of an explosion with ensuing
dispersal of toxic chemicals into the atmosphere.  This possibility poses  high risks to nearby populations
and ecosystems. From numerous discussions with experts Knowledgeable about the condition of Old 0-
Field, the following are potential causes of an explosion at Old 0-Field:

       • Fire. The exposed rounds on the surface and/or rounds which are just below the surface may
       detonate if subjected to fire. Because Old 0-Fleld is heavily vegetated and there is a substantial
       amount of organic detritus on the ground, it Is expected that Old O-Field will bum vigorously and
       that a fire started on any side could  consume the field. Although the field  is surrounded by a
       road, the gap (approximately 12 feet on the north, east, and south sides) may not be enough to
       stop a brush fire. The proximity of Old O-Field to H-Field, where  active testing of combat tracked
       vehicles occurs and where brush fires  occasionally  are  started  accidentally, increases  the
       possibility of a fire.  The recent addition of a narrow  access road along the perimeter of the
       existing road most likely will not significantly reduce the spread of a fire because in many places,
       there is no gap between the branches of trees on opposite sides of the road. In addition to the
       possibility that a fire may start outside the field, it is also possible that a fire could start inside the
       field. This is due to the presence of white phosphorus and other incendiary materials. When
       exposed to air (e.g., during trench collapse or soil shifting), white phosphorus will spontaneously
       ignita  Recent observations suggest that items continue to be  exposed through erosion, frost
       heave,  or other mechanisms.  The most likely stimulus for explosive release or rupture would be
       from fires.

       •  Shock or pressure.  Fuzes and initiating devices are far more sensitive to shock or pressure
       than high explosives. The stockpile configuration of many ordnance items was with a burster and
       point-detonation fuze.  While most of these fuzes would be unarmed, it Is possible that a small
       number of items in Old O-Field have been armed by forces such as historical detonations.  Any
       item with an armed  fuze would be very  hazardous and sensitive to shock and pressure. In
       addition, LTC Dickey reported that some of the Japanese munitions originally disposed at Old O-
       Field used picric acid as bursters.  When the picric add deteriorates into picrate salts, they are
       shock sensitive. LTC Dickey also reported that there were many metal boxes filled with fuzes; one
       was accidentally dropped and detonated as a result of the shock from impact with the ground.

       •  Ordnance Exposure. The processes of erosion, corrosion, and waste settling has resulted in
       the  formation of voids and the structural weakening of portions of the buried waste volume. With
       continual action of these  processes, there will be collapse of material into voids and set-
       tling/consolidation of wastes.   Erosional  holes to the surface may form, exposing white
       phosphorus ordnance to oxygen and providing a pathway for  CWM vapor release. It is also
       possible that movement of wastes and soil may result in impact, shearing, and crushing of the
       buried items,  which may result In release of CWM from corrosion-weakened items and which
       could initiate detonation of ordnance items that are sensitive; however, this initiation source is less
       likely than the thermal ignition  hazard. The other possible causes of ordnance exposure at the
       surface are the following:
                                             6-3

-------
               •  Honeycombing of trenches.  The historical aerial photographs show that as available
               space became more scarce at Old 0-Field, the trenches began to overlap. This would
               result in very unstable soil conditions.

               •  Density differences. The difference in densities between some types of ordnance and
               soil sometimes allows munitions to work their way up through the soil, rescuing in
               eventual exposure to the atmosphere.

               •  Presence of animals.  If animals are burrowing through the soil or are allowed to run
               on top of the filled trenches, their movement may cause the soil to shift.

               •  FrostAhaw cycles may aid in trench erosion and the mobilization and movement 
-------
 7.0  ngSCRIPTION OF ALTERNATIVES

        During  the technology screening conducted as part of the Focused Feasibility Study (APG,
 19945), applicable  remedial technologies were identified, evaluated, and assembled into remedial
 alternatives. These remedial alternatives address the following general response actions:

        •       No Action;
        •       Limited Action;
        •       Containment (two alternatives); and
        •       Permeable Infiltration Unit (PIU).

 This section describes the alternatives that were considered for remediating OU2.


 7.1     APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS

        As required by the NCR, the selected alternative must be in compliance with all applicable or
 relevant and appropriate requirements (ARARs).  ARARs are the cleanup standards, standards of control,
 and  other substantive environmental requirements, criteria, or limitations promulgated under Federal or
 State law  that specifically addresses a hazardous substance, pollutant, contaminant remedial action,
 location, or other circumstance of a Superfund site.

        Chemical-specific ARARs include State of Maryland standards for air releases of hazardous
 substances, including some substances which can potentially be emitted from Old O-Reld. The State of
 Maryland also has requirements for participate emissions in air and the discharge of organic and inorganic
 analytes to surface water.

       Capping involves covering a site to reduce direct human and animal exposure to contaminants
 and  to  minimize infiltration of precipitation and subsequent vertical migration.  Federal and State
 regulations set standards for cap requirements when a landfill is permanently closed. These standards
 would apply to any final remedy in which buried materials are allowed to remain at the site, but would not
 apply to an interim remedy.
7.2    ALTERNATIVE A: NO ACTION

       Under this alternative, no action would be taken to address the source of contamination at Old
O-Field.  The No Action alternative is intended to serve as a baseline with which to compare the risk
reduction effectiveness of the other alternatives that are under consideration. Continued maintenance of
existing institutional controls (access restricted by the existing fence system and other Institutional
controls) are not assumed under this alternative. The land-use condition assumed under the No Action
scenario includes unrestricted land use.  Because Old O-Field contains munitions, chemical agents,
chemicals associated with decontamination activities, and other hazardous materials, the risks associated
with the unrestricted land use scenario is unacceptably high. Over a long period of time, the chemical
concentrations in the soil may decline due to natural biodegradation, hydrolysis, and leaching,  but the
site will still pose risks  due to UXO and chemical contamination

       The No Action alternative would not involve active treatment or containment Therefore, there
would be no reduction  in toxicity, mobility, or volume of contaminants at Old O-Field There would be no
implementation  time or cost associated with the No Action alternative because no additional remedial
                                             7-1

-------
 activities would be implemented at the site.  Because of the likelihood of an eventual air release of CWM
 or other air pollutants, this alternative would not comply with chemical-specific ARARs.


 7.3    ALTERNATIVE B: LIMITED ACTION

        The Limited Actiqn alternative would continue the current restrictions at the site, and would include
 implementation of the following actions:

        •      Institutional restrictions;
        •      Maintenance of existing physical security countermeasures;
        •      Public education programs;  and
        •      Continued monitoring of site conditions and five-year reviews.

        Institutional controls include access restrictions, deed restrictions,  and land use restrictions.
 Access restrictions include long-term maintenance of the existing fence system,  use of supplemental
 physical security countermeasures, and regulations and enforcement to prevent trespassing. Deed and
 land use restrictions would limit the future uses at the site and require permits, qualified supervision, and
 health and safety precautions for any activities conducted near Old O-Field. Education programs would
 be developed to inform workers and local residents of the potential site dangers. Five-year reviews are
 required by the NCP at all sites where hazardous chemicals  remain untreated.  Such reviews would
 analyze available monitoring data to make a determination as to whether additional remedial actions or
 site controls would be required

       This alternative would provide a minimal reduction in human health risks beyond the risks posed
 by the baseline conditions (No Action) by limiting future use and development of the affected area through
 written regulations. Limited Action would include no further actions to reduce or eliminate the source, or
 to reduce migratioa This alternative would be protective of human health and the environment only under
 undisturbed site conditions. However, this alternative would not reduce the risk of a fire or explosive event
 and would not be protective in the case of a fire or explosive event with associated air release of CWM.

       The Limited Action alternative would not involve active treatment or containment Therefore, there
 would be no reduction in toxicity, mobility, or volume of contaminants at Old O-Fteld. Because of the
 likelihood of an eventual air release of CWM or other air pollutants, this alternative would not comply with
 chemical-specific ARARs.

       Because no measures to treat or contain the contaminated soil would be implemented, risks
 would not be reduced beyond the current risks posed by the site. However, the chemical concentrations
 in the soil may be reduced over many years by natural degradation mechanisms and the continued
 operation of the groundwater treatment system.  The institutional controls proposed for this alternative
 would not as effective as active engineering controls because these controls could be ignored by
 individuals unfamiliar  with them; however, continued maintenance of the existing fence system  and
 warning signs may provide  effective tang-term control of human contact with soil contaminants and the
 surface of the field  Although this alternative would prevent direct contact with the site, it would not
 mitigate potential impacts of aJr releases from the site. Because air releases are a possibility, the long-
 term effectiveness of the Limited Action alternative is uncertain.

       Aside from the natural attenuation discussed above, there would  be no further reduction in the
toxicity, mobility, or volume of the contaminant source at Old O-Field because removal and/or treatment
 of contaminated materials are not components of this alternative.  Mobility of contaminants in bulk or in
soil at Old O-Field is uncertain and uncontrolled under tills  alternative. The potential would remain for
                                             7-2

-------
 spontaneous white phosphorus ignition or UXO detonation with resulting release of contaminants from
 the site.

        In addition, because the surface of Old O-Field would not be covered under the Limited Action
 alternative, animal intrusion may occur with the potential for the collapse of trenches or the exposure of
 v/hrts phosphorus.

        Most components of Alternative B have been implemented and are being maintained at the site.
 Institutional controls and other provisions of this alternative would likely be effective in minimizing short-
 term risks.  However, given the unpredictable nature of the site,  and its past history  of spontaneous
 detonations, this is not certain. Exposures to airborne contaminants could occur if there is a detonation
 or fire at the site.

        All components of Alternative B are feasible and easily implemented. All necessary equipment
 and materials  required for implementation  of  this  alternative are readily available.   Administrative
 implementation of this alternative would require coordination between APQ, the State of Maryland, and
 the EPA to ensure continuity of the long-term management and monitoring of the site.

        The cost estimate for this alternative is based on the assumption that groundwater and surface
 water monitoring at O-Field will be performed as part of the  OU1 groundwater remediation and the
 ongoing Rl for O-Field.  Capital costs are estimated to be $690,000, and annual O&M costs are $180,000.
 Total present worth costs for this alternative based on a 30 year (5% discount rate) implementation period
 are $2,168,000. Maintenance of the existing fence system is included In the annual operating cost for this
 alternative. Contingencies associated with the alternative would be minimal because the alternative does
 not include any treatment or design components.  Costs could be  affected significantly if periodic
 groundwater or surface water monitoring is included  in this alternative.


 7.4    ALTERNATIVE C: PERMEABLE INFILTRATION UNIT (PIU)

       Under this alternative, the surface of Old O-Field would be overlain with materials that would
 reduce releases due to fires or explosions, but would be permeable to water.  The  layer would be
 designed to allow infiltration of water or the application of solutions through the wastes, thus allowing
further testing of processes to treat the soil and wastes. This alternative would work In conjunction with
the downgradient groundwater treatment system to promote leaching of contaminants and produce an
 ultimate reduction in the volume of the wastes.

       The PIU would  be constructed using sand or other granular materials to reduce the risks from
vapor emission caused by fire or explosions, and to act  as a barrier between ordnance, wastes, and
contaminated soil and the surface environment A permeable layer of moderate thickness would attenuate
the effects from exploding munitions and reduce CWM emissions from the burial pits and trenches. In
addition, the layer would tend to flow and fill in gaps if an explosion or collapse of a trench occurs, so
repair of the PIU would be simpler than repair of other types of covers. The buried materials would be
insulated from the effects of surface fires by the sand  or other  granular material  In  addition, the
possibility that exposed white phosphorus would serve  as an ignition source would be reduced by
isolating the wastes from air contact

       Sand or other mineral-based granular materials would provide resistance to fire/explosive releases,
and the layer design would include erosion  control layers to prevent wind and water erosion. The
permeable structure would not lower the water table and would keep the subsurface moist, which would
reduce the  possibility of igniting buried white phosphorus.
                                             7-3

-------
        Other components of this alternative include:

   •    An air monitoring system would be installed within the PIU to detect the presence of CWM within
        the pore spaces of the sand.

        A sprinkler system would be constructed en tcp of the PIU that would be capauw of quickly
        spraying water or other solutions on the PIU. If a CWM release is detected by the air monitoring
        system, then the sprinkler system would be activated.  The water sprayed onto the PIU would
        form a vapor barrier within the sand to prevent an air release of CWM and would also hasten the
        hydrolysis of CWM.

   •    Treatability studies would be performed using the sprinkler system to apply water or other
        solutions  to the PIU.  The results of these studies would be used to evaluate the feasibility of
        enhanced leaching of the contaminants from soil and buried containers to the groundwater.  In
        addition, the surface of the PIU would be monitored to evaluate the rate of subsidence of Old 0-
        Field.

   •    The ability of the groundwater extraction and treatment system that is under construction for OU1
        (contaminated groundwater emanating from Old 0-Field) to capture and treat the contaminated
        groundwater emanating from Old 0-Field would be verified.  In addition, the effectiveness of the
        groundwater monitoring program to detect changes in the site hydrogeology and groundwater
        chemistry would be verified.

        The chemical-specific ARARs that apply to this remedial action are surface water criteria and air
pollution standards. The quality of surface water in Watson Creek and the Gunpowder River would be
protected during the construction of this alternative by implementing proper runoff controls and sediment
and erosion control measures. Airborne emission of particulates during the PIU construction would be
managed by controlling the moisture content of the sand and gravel However, there could be a potential
for releases of chemical agents and other contaminants from Old 0-Field during implementation.
Although all pertinent air monitoring  requirements would be met and all measures for preventing such
releases would be taken, the unpredictable nature of the site does not allow certainties in estimating
effects of placing the PIU on Old O-Field.

        The PIU would comply with ARARs after implementation. Runoff and erosion from the site would
be controlled, thereby protecting nearby surface water quality. ARARs governing atmospheric release of
contaminants (especially agents) would be met through the use of an integral air monitoring system
combined with emergency response capability (La, the sprinkler system) to detect and minimize potential
agent releases to the atmosphere.

        Implementation of this option would take approximately 12 to 18 months for the design phase and
approximately 24 months for the construction phase. These time estimates Include regulatory review of
the design.

       The total capital costs for installation of the PIU (assuming construction as stated) is estimated
at $11,041,000. The total annual  costs are estimated at $269,000, and the total present worth of these
costs, calculated with a 5% discount  rate over a lifetime of 30 years, is $15,175,000.  Earthen materials,
such as sand and gravel, are expected to be brought on site rather than borrowed from elsewhere at
APQ.
                                             7-4

-------
 7.5    ALTERNATIVE D: FOAM CAP

        This alternative would stabilize the soil and prevent human and animal contact with munitions and
 contaminated material buried in the disposal pits at Old O-Field by covering the field with spray-on foam,
 si.rh as 3 polymerizing urethane foam. A pciysuificte coating could be spra/ed on the top surface of the
 foam to prevent degradation of the foam by sunlight  The low density of the foam would result in a
 relatively small amount of pressure on the trenches and buried items.  The foam surface would allow foot
 traffic and light equipment with minimal pressure applied to the buried materials. This remedy could be
 accomplished remotely, without excavation or soil compaction, thereby minimizing exposure of workers
 to the field and the disturbance of the surface and subsurface soil. In addition,  the foam cap would
 prevent air from  reaching the buried materials, thus reducing the fire hazard posed by ignition of
 incendiary materials, such as white phosphorus. The principal drawback of the foam cap is that ft would
 provide little shrapnel resistance in the event of a detonation; however, the likelihood of an accidental
 explosion or fire occurring is minimized by this alternative.

        This alternative would not by itself provide complete protection of human  health and the
 environment. A foam cap would prevent vertical infiltration of water through the contaminated soil and
 reduce release of vapors to the atmosphere. It is expected that this  remedy would greatly  reduce, but
 not eliminate, the mass loading of contaminants into the aquifer. The foam cap would reduce the risks
 of atmospheric releases of contaminants from the surface of Old O-Field by stabilizing the soil, preventing
 human and animal access to the field, preventing  air contact with the soil,  and eliminating infiltration of
 stormwater through the contaminated soil.  In addition, the  cap would  be  constructed of a lightweight
 material which would reduce the risk of trench and/or thin-walled shell collapse.

        Other components of the foam cap alternative would include:

  •    Air monitoring within the foam/soil interface; and

  •    Stormwater runoff control.

       Implementation of this remedy would prevent the release of CWM and other contaminants to the
 atmosphere because of the low gas permeability of the cap material, except in the case of a detonation.
 In this event containment of the detonation and contaminant vapors would be doubtful because of the
 likelihood that the foam cover would be breached. The risk, however,  of accidental detonation of the
 munitions would be reduced because the surface soil of the field would be stabilized  and the flow of
 oxygen to the surface of the field would be cut off.  The risk of fire at the  site would also be reduced, but
 the effects of a subsurface detonation are unknown. Construction and disposal of the cap would result
 in the release of VOCs to the atmosphere.

       The chemical-specific ARARs that apply to this remedial action are surface water criteria and air
 pollution standards. The  quality of surface water in Watson  Creek and  the Gunpowder River would be
 protected during the implementation of this alternative by proper runoff control and implementation of
 sediment and erosion control measures. Although all pertinent air monitoring requirements would be met
 and ail measures for preventing air releases would be taken, the unpredictable nature of the site does not
 allow certainties in estimating effects of placing a cap on Old O-FieWL Once the cap is safely constructed,
 it would ensure compliance with  air quality ARARs by providing an impermeable boundary to vapor
transport from the current surface of Old O-Field, and prevent any contaminated surface runoff to nearby
 surface water.

       If property maintained, this  option would provide long-term soil stabilization and reduction of
contaminant mobility. Maintenance would consist of inspecting and periodically repairing the foam layer,

                                            7-5

-------
 maintaining the perimeter fence system, and continued use of the groundwater extraction and treatment
 facility.              •        ..

        Implementation of this option would take approximately 12 to 18 months for the design phase and
 48 months for the construction phase.

        For the installation of the foam cap, the costs were estimated considering the use of remotely
 operated, roootic equipment The total capital costs are estimated to be $18,421,000, and the total annual
 costs are estimated at $275,000.  With a 5% discount rste, the present worth of total capital and annual
 costs is $22,647,000.
 7.6    ALTERNATIVE E: MULTI-MEDIA CAP

        This remedy would consist of the construction of a multi-media cap to cover the surface of Old
 0-Field. The highly-engineered cap structure would consist of several layers of crushed stone, synthetic
 fabric sheets, a clay liner, a drainage layer, low-permeability soil fill, and topsoil to support vegetation.
 Construction of this cap would stabilize the soil and trenches; prevent stormwater infiltration through the
 source area; eliminate human and animal contact with the surface of the field; reduce the possibility of
 a fire by cutting off oxygen to the current field surface; and reduce the likelihood and potential effects of
 accidental detonation and evaporative release. To reduce the overall weight of the cap, a combination
 of natural and synthetic materials may be used in cap construction. Construction methods would also
 be tailored to minimize the disturbance of the field, although soil compaction would  be needed to form
 the upper topsoil layer.
        Other components of the multi-media cap alternative include:

        An air monitoring system within the foundation layer; and

        Stormwater runoff control and drainage control;
        The relatively large weight of this cap would pose a safety concern. Because of the instability of
the trenches and the presence of thin-walled munitions and containers within the landfill, it is possible that
cap construction would cause collapse of trenches or buried drums within the field. This event, should
it occur, could possibly result In sheU rupture and release  of its contents or may result In the triggering
of a pressure-sensitive fuse and detonation of thai round. The use of heavy earthmoving equipment on
.the field may compound this risk.  However, if the cap can be constructed without an incident, then it
should be capable of providing the desired protection.

        The chemical-specific ARARs that apply to this remedial action are surface water criteria and air
pollution standards.  The quality of surface water In Watson Creek and the Gunpowder River would be
protected during the implementation of this alternative by proper runoff control and implementation of
sediment and erosion control measures. The air emission of particulates during cap construction would
be managed by controlling the moisture content of the multi-media cap construction materials. However,
potential releases of chemical agents and other contaminants from Old O-FIeld during Implementation may
not be prevented.  Although all pertinent air monitoring requirements would be met and all measures for
preventing such releases will be taken, the unpredictable nature, of the site does not allow certainties in
estimating the potential releases and effects of constructing a multi-media cap on Old O-Field. Agent
releases to air would be controlled except in the case of detonation or subsidence in which the cap is
breached.
                                              7-6

-------
        If properly maintained, this option would provide long-term soil stabilization and reduction of
contaminant mobility.  Maintenance would consist of mowing and repairing the topsoil, maintaining the
existing  fence  system, and continued  use  of the groundwater  extraction and treatment facility.
Additionally, subsidence caused by settlements in the landfill would be addressed.  If the impermeable
layers of the cap are breached by ground motions caused by subsidence, the cap would require repair.
In this case, contaminants may be released to the air. Effective repair is uncertain and wcuid subject
workers to additional risks.

        Implementation of this option would take approximately 12 to 1S months for the design phase and
24 months for the construction phase.

        If the cap  is completed, additional actions, such as maintaining erosion  control, or periodic
maintenance of the vegetative cover, would not be difficult to implement, although repairing the multiple
layers may be difficult if the cap is breached by subsidence or detonation.  Periodic  monitoring and
maintenance would include visual inspection of  the entire cap to ensure it Is intact, and that erosion
controls are functioning property.  Growth of grasses and other vegetation on the top layer of the cap
must be controlled to prevent deep root growth, which could compromise the cap effectiveness.

       The total capital cost for installation of the cap, assuming construction as stated, is estimated at
$11,215,000.  The total annual O&M costs are estimated at $460,000.  The total present  worth of capital
and annual O&M costs are estimated at $18,285,000, calculated  over 30 years at a discount rate of 5%.
Earthen materials, such as sand and gravel, are expected to be brought on site rather than borrowed from
elsewhere at APQ.
                                             7-7

-------
8.0  SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES

       This section evaluates and compares each of the alternatives described in Section 7.0 with
respect to nine criteria used to assess remedial alternatives as outlined in Section 300.430(e) of the NCR.
Each of the nine criteria are briefly described below. All of the alternatives were evaluated for their ability
to meet the threshold criteria of protection of human health and the environrrisnt and compliance with
ARARs. The alternatives meet the other criteria to varying degrees. To aid in identifying and assessing
relative strengths and weaknesses of the remedial alternatives, this section provides a comparative
analysis of alternatives. As previously discussed, tha alternatives are as follows:

              Alternative A, No Action
              Alternative B, Limited Action
              Alternative C, Permeable Infiltration Unit
              Alternative 0, Construction of Foam Cap
              Alternative E, Construction of Multi-Media Cap

These five alternatives are compared to highlight the differences between the alternatives and to identify
trade-offs in meeting the criteria


8.1    NINE EVALUATION CRITERIA

       Section 300.430(e) of the NCP lists nine criteria by  which each remedial alternative must be
assessed.  The acceptability or performance of each alternative against  the  criteria Is evaluated
individually so that relative strengths and weaknesses may be identified

       The detailed criteria are briefly defined as follows:

       •      Overall Protection of Human Health and the Environment Is used to denote whether
              a remedy provides adequate protection against harmful effects and describes how human
              health or environmental risks are eliminated,  reduced, or controlled through treatment,
              engineering controls, or institutional controls.

       •      Compliance with ARARs addresses whether a remedy will meet all of the applicable or
              relevant and appropriate requirements of Federal and State environmental statutes or
              provides a basis for invoking a waiver.

       •      Long-term Effectiveness and Performance refers to the magnitude of residual risk and
              the ability  of a remedy to maintain reliable  protection of human  health and the
              environment, over time, once clean-up goals have been met

       •      Reduction of Toxlcity, Mobility, or Volume  through Treatment is the  anticipated
              performance of the remedial actions as  employed for each alternative.

       •      Short-term Effectiveness refers to the speed with which the remedy achieves protection,
              as well as the remedy's potential to create adverse Impacts on human health and the
              environment that may result during the construction and implementation period.

       •       Implementabllfty is the technical and administrative feasibility of a remedy, including the
              availability of materials and services needed to implement the chosen solution.

       •       Cost includes both capital and operation and maintenance costs.

                                            8-1

-------
        •      State Acceptance indicates whether, based on its review of the FS Report and Proposed
               Plan, the State concurs with, opposes, or has no comment on the preferred alternative.

        •      Community Acceptance assesses the public comments received on the FS Report and
               the Proposed Plan for the Operable Unit

        The NCP (Section 300.430(f)) states that the first two criteria, protection of human health and the
 environment and compliance with ARAHs,  are the threshold criteria' which must be met by the selected
 remedial action.  The next five criteria are the 'primary balancing criteria1, and the trade-offs within this
 group must be weighed.  The preferred alternative is that alternative which is protective of human health
 ana the environment, is ARAR-compliant, and provides the best combination of primary balancing criteria
 attributes.  The final two criteria state and community acceptance, are 'modifying criteria' which arc
 evaluated following comments from the FS report and the Proposed Plan.


 8.2     PROTECTION OF HUMAN HEALTH AND THE ENVIRONMENT

        Alternative A, No Action, would allow for unrestricted future land use.  For this alternative, no
 actions would be taken to  eliminate, reduce, or control  exposures to  hazardous  materials  and
 contaminants. An unacceptably high level of risk would result  The threshold criterion of protection of
 human health and the environment would  not be achieved  by Alternative A.

        Alternative 8, Limited Action, would provide some protection from contaminants and hazards at
 the site by maintaining a high level of physical security. These actions would continue to limit site access
 and direct exposures. Alternative B would pose no additional risks during implementation because no
 additional construction activities would be undertaken at the site.  However, Alternative B would not
 prevent future releases due to fires, explosions, or even slow leakage from buried containers. Alternative
 B would result in unacceptable human health and environmental risks to site workers and surrounding
 populations if a release occurs. Therefore, Limited Action would not meet the threshold criterion of
 protection of human health and the environment

        Implementation of Alternative C, Alternative D or Alternative E would reduce the  potential for
 release of vapors (CWM and other volatile contaminants) to the atmosphere. Any of these alternatives
 would prevent direct human and animal contact with Old O-Field, and reduce transport of contaminants
 in windblown dust or surface runoff.  Alternatives D and E would make use of non-flammable or flame-
 retardartt materials and would cut off oxygen to the field, which would decrease the probability of fires.
 Alternative C would reduce the probability of fires by minimizing the oxygen supply to burnable materials
 and by maintaining a moist subsurface environment  Under all three of these alternatives, the risk of
 spontaneous ignition, as well as the effects of a fire, would be reduced. Erosion of the field surface would
 also be reduced.  These alternatives would result in some short-term risks during construction, but these
 risks could be minimized and controlled by selection of proper construction techniques during the concept
 design  phasa The overall long-term  risks would be reduced.  Both the extraction system and the
 treatment system would be evaluated to ensure overall compliance with the groundwater treatment goals.

        Alternatives D and E include Impermeable cover layers and would prevent vertical infiltration of
 water through the contaminated soil Either of these capping remedies would stop or reduce leaching
 and reduce the transport of contaminants into the aquifer.  However, the impermeable covers would lower
the water table  beneath  the  field and could potentially interfere  with operation of the groundwater
 extraction system.

       Alternative C, the permeable infiltration unit would enhance degradation and leaching of the
wastes.  Short-term risks during  construction could be controlled by property  selecting application

                                            8-2

-------
 methods during the concept design phase.  The permeable layer would stabilize the existing surface of
 the field and offer increased protection against fires and explosions. The layer would allow infiltration of
 precipitation and additional water provided by a sprinkler system. Saturation of the permeable layer would
 reduce CWM vapor emissions.  Treatment processes could be tested by adding chemical reagents to the
 applied water. Continued or accelerated leaching of contaminants would occur, and the leachate would
 ba reflected by tte grourrtwser extraction and treatment system. Although somewhat giwater flow into
 the extraction system would be expected, the groundwater treatment plant was designed with the reserve
 capacity and  backup systems to handle the greater flows and potentially higher concentrations of
 contaminants.

        The self-healing properties of the sand is an advantage of Alternative C over Alternatives 0 and
 E. Both Alternatives C and 0 would allow easier repair compared to Alternative 0.

        In addition, construction of Alternative C would allow greater flexibility in the overall remedial action
 by allowing for treatability studies to evaluate enhanced degradation of the wastes.  Such studies would
 be difficult or impossible under Alternatives D and E. Alternative C also allows monitoring and evaluation
 of the rate of subsidence of the landfill.

        Alternative D, the impermeable foam cap, would provide some protection of human health and
 the environment,  but would not provide the same level of protection against explosive releases as
 Alternatives C or E Construction of this cap would have relatively low short-term risks from explosive
 hazards because it can be remotely installed.  However, construction of the foam cap would  release
 ozone-depleting fluorocarbons  and other air pollutants. The foam cap would contain vapors released by
 leakage of wastes within the disposal site, but would offer little protection against an explosive event below
 the cap or a large fire.

       Alternative E, an impermeable multi-media cap, would provide blast protection similar to that
 provided by Alternative C.  Alternative E would contain vapors and reduce the frequency and severity of
 fires and explosions. However,  construction of a multi-media cap would have higher short-term risks than
Alternative C because it would require compaction of materials on Old O-Field. The multi-media cap also
would be more difficult to repair because of the more complex structure. Overall, this alternative provides
 protection of human health and the environment, but to a lesser degree than Alternative C.


 8.3    COMPLIANCE WITH ARARS

       Compliance with ARARs is a threshold criterion which must be met by the selected remedial
action. Alternatives A and B (No Action and Limited Action scenarios) do not meet this criterion because
releases due to fires or explosions, with resulting air releases, would not be prevented.

       The three remaining alternatives are capable of meeting ARARs.  The quality of nearby surface
water would be protected by proper runoff control and Implementation of sediment and erosion control
measures. The emission  of particulates during  construction would be managed by controlling the
moisture content of earthen materials that are placed for Alternatives C and E. Release of VOCs during
foam application would be a concern for Alternative D, and will be managed by controlling the amount
of spraying per day. Alternatives 0 and E would meet all applicable requirements for impermeable covers
at closed hazardous waste landfills. This ARAR does not apply to Alternative C because it is an interim
action to minimize air releases  and explosive hazards at the site and is not final site closure.
                                             8-3

-------
 8.4    LONG-TERM EFFECTIVENESS AND PERMANENCE

        Alternatives A and B would not provide long-term effectiveness and permanence. The No Action
 alternative provides minimal protection of human health  and the environment.  The Limited Action
. alternative provides some protection through continuous control of human contact with the source area
 However, Limited Action would not stabilize the field, and the possibility of releases by fire/explosion would
 continue, because the field would remain in an unstabilized and uncontrolled condition.

        Alternatives C, D, and E provide varying degrees of long-term effectiveness and permanence.
 These alternatives would assist in preventing an explosive event and also would help control the adverse
 effects if a fire or explosion occurs.  Each of these alternatives would stabilize the current surface of Old
 O-Field and provide a more stable working surface for future investigations and remedial actions.  The
 layers placed over the field surface would minimize the risks of fire from outside sources or from exposed
 white phosphorus.  Each alternative would curtail the supply of oxygen to the wastes, reducing the
 possibility of white phosphorus ignitioa  Alternative C  also  would  maintain a  moist  subsurface
 environment, which would further reduce the chances of white phosphorus ignition.

        Alternative C would provide the best long-term effectiveness in stabilizing the field conditions and
 reducing the probability of a fire or explosion. This option would provide better stabilization of the field
 surface than the cap alternatives.  Because Alternative C would use granular material as the cover,
 breaches caused by trench settlements or collapses would be largely self-healing and easily repaired.
 Once settlement has stabilized, the permeable layer could  become the base for a permanent cover or
 cap. Alternative D (foam cap) would place the lowest loading on the field and would stabilize the surface.
Both the foam cap and the multi-media cap may fail if large settlements or collapses occur, although the
foam cap would be easier to repair. If settlement occurs and the multi-media cap is damaged, repair of
the multi-media cap would be very difficult

        If a significant explosion occurs, Alternative C would provide the best long-term effectiveness and
permanence.   The sand used in Alternative C would better absorb explosive energy than the rigid
materials used in Alternatives 0 and E. For Alternative E, explosions could seriously damage the layers
of this cap, destroying its effectiveness in preventing air releases.  Repairing this cap would  be very
difficult because of the complex layering system and the specialized materials used. Alternative 0 would
be ineffective in containing releases caused by explosions.  The foam will melt or bum in the event of a
large fire or explosion, potentially destroying major portions of the cap.  Repairing smaller damaged areas
would be a relatively simple process, but large breaches will be more difficult to repair.

       Overall, Alternative C  results In the best long-term effectiveness of the three active alternatives.
The permeable system would promote degradation of the wastes, and would work well with the
groundwater treatment system.  The  permeable structure  would be easier to maintain than the cap
alternatives, and would be less affected by settlements or explosions,


8.5    REDUCTION OF TOXICJTY, MOBILITY OR VOLUME THROUGH TREATMENT

       If possible, alternatives that reduce the toxicity, mobility or volume of wastes through treatment
are preferred.  Alternatives A and B provide no reduction in contaminant toxicity,  mobility,  or volume.
Alternatives C,  D and E will reduce mobility by exercising control over air releases and surface runoff.
Alternatives D and E also will reduce mobility by stopping or reducing the leaching of contamination into
groundwater, but these  actions would not reduce the toxicity or volume of  wastes.  Alternative C
potentially results in reduced toxicity or volume, by promoting interaction of water or added chemicals with
the waste materials. However, at this time, the extent to which this will occur is not knowa

                                              8-4

-------
 8.6     SHORT-TERM EFFECTIVENESS

        Alternatives A and B do not create any additional risks during implementation because neither
 alternative would  require direct  operations within Old O-Field.   Alternative  A would require no
 implementation time because no actions are taken.  Alternative B could be implemented in a very snort
 time because most of the provisions are already in place at the site.

        For Alternatives C, 0 and E, protection would be achieved as soon as the actions are completed.
 Alternative C would require 12 to 18 months to design, and approximately 24 months to prepare the site
 and construct the sand cover.  Alternative D would require about 12 to 18 months to design and 48
 months to construct the foam  cap.  Alternative  E would require  12  to 18  months for design, and
 approximately 24 months to prepare the site and construct the multi-media cap.

        During construction, each alternative would create disturbances and additional pressure on the
 field, which would increase the risk of initiating a fire or explosion. This would increase the short-term
 risks for site workers and surrounding communities.  There is an added risk that CWM and other
 contaminants could be released from Old O-Field during implementation of any of these options. Under
 Alternative 0, workers could be  subjected to fluorocarbon exposures during foam application, and the
 environment would be subjected to the deleterious effects of fluorocarbons.

        In terms of loading on the field, Alternative D would create less short-term risk than Alternatives
 C or E because lighter-weight materials would be used.  Alternatives C and  E would have potentially
 significant short-term risks because they require moving and placement of earthen materials above the
 present surface of Old O-Field.  Alternative E would create higher short-term risks than Alternative C
 because of the larger quantity of material placed and the need for compaction  with mechanical
 earthmoving  equipment  It  may  be possible to place materials under Alternative  C without using
 equipment directly on the field, although this is not possible for Alternative E.

       The development of safe  and effective ways to  construct the remedial action  would be an
 important part of the concept design phasa Site safety, health,  and emergency response plans would
 be developed which minimize all potential exposures to site workers.  Although measures for preventing
 releases and exposures would be incorporated Into the remedial design, the unpredictable nature of the
 site does not allow certainties in estimating effects of constructing any of these alternatives at Old O-Field
These short-term risks must be weighed against the longer-term risk reduction offered by each alternative.


 8.7    IMPLEMENTABIUTY

       Alternative A would be the most easily implemented alternative because it requires no actions at
the site and does not require maintenance of existing institutional controls. Alternative B would require
 no more than continuation and upgrade  of the access controls and air monitoring equipment that are in
 place at Old O-FJeld. Construction of Alternatives C, D or E at Old O-Field would be complicated by the
 unique and unknown hazards posed by the site. The stability and foundation  conditions of the site are
 uncertain. Site preparation and construction activities would be necessary in the presence of unexploded
ordnance, CWM, and white phosphorus, which may cause dangerous construction conditions.

       Between Alternatives C,  D, and E, Alternative C would be the easiest  to implement and would
 require the least amount of specialized materials and equipment AH materials  required for construction
 are readily available.. Materials placement would require less sophisticated equipment than Alternatives
D or E.  Required maintenance would be relatively simple, consisting of filling  in depressions that form
in the sand layer and maintaining the air monitoring and sprinkler systems.

                                             8-5

-------
        Alternative E would also be implementable. All materials and equipment required for the multi-
 media cap (foundation materials, synthetic layers, top soil, low ground pressure earthmoving equipment,
 etc.) could be readily, obtained near APG.  Maintenance of the multi-media cap would be the most
 complicated of the three cover alternatives due to the relative complexity of the layering system.

        Alternative 0 would bo the most difficult of the alternatives to implement  A foam cap of this size
 and specialized use has not been previously attempted. The remote and robot-controlled construction
 methods that have been assumed will enhance safety, but are not readily available.  These methods
 would require development and testing prior to implementation. The foam cap also would require a longer
 time to construct than Alternatives C or E because of the remote-controlled and innovative equipment
 used.
 8.8    COST

        Table 8-1 provides a comparison of the costs of the five alternatives that are under consideration.
 Total capital,  annual O&M costs, and present worth (discount rate of 5%)  for each alternative are
 presented. The progression of total present worth from least expensive to most expensive alternative is:
 Alternative A (no cost), Alternative B, Alternative C, Alternative E, and Alternative 0. Alternative C is the
 least costly of the three containment alternatives because it requires the least specialized equipment.
 Alternative E is similar to Alternative C in methods of construction and in some of the materials, but more
 materials are required for Alternative E Alternative 0 is the most costly because of the large quantities
 of specialized materials and equipment that have been assumed for remote construction of the foam cap
 and the longer construction time.


 8.9     STATE ACCEPTANCE

        The Maryland Department of the Environment (MDE), Waste Management Administration, concurs
 with the selection of Alternative C, Permeable Infiltration Unit (PIU), as an interim action for the Old 0-Field
 source area (Operable Unit 2) at Edgewood. The acceptance of this option is based on the PIU system's
 resistance  to  potential explosive events and its  ability to  detect and mitigate  the  release of  CWM.
Additionally, the PIU will provide the opportunity to conduct and evaluate in situ treatment atematives,
 monitor long-term stability of the waste, and evaluate the rate of subsidence and physical dynamics of
the fill area

        In conjunction with the groundwater treatment system currently being constructed (Operable Unit
 1),  the  PIU will provide isolation of the waste,  effectively  controlling inhalation and ingestion  of
contaminated material and the discharge of contaminated groundwater to Watson Creek. Furthermore,
the Department considers the permeable material, principally sand, to provide an acceptable •first* layer
of cover for the foundation of an impermeable cap, should such an option be considered more practical
at a future date.
                                             8-6

-------
                      TABLE 8-1
Comparison of Costs for Old O-Fleld Remedial Alternatives
Alternative
8
C
D
E '
;f If DwiclrtpWoriill;:
:'v-:':::-''i -.•.•£'£ -;'';v:-.v.:;^ •£'£:::*:/" • :'. ' '•£":'
w v-' - :.|. *:>•:••>;': V-:--> : " :'^ •:••'• '-'•'•'•••''•:•'•::
• Umited Action
• Permeable Cover
• Foam Cap
• Multi-Media Cap
.rscfp^,^^ boats; lit:1994 Dollars
11111:
Capital Cost
$690,000
$11,041,000
$18,421,000
$11,215,000
Annual
0AM Cost
$180,000
$269,000
$275,000
$460,000
Present
Worth
(30 years,
5%)
$2,168.000
$15,175,000
$22,647,000
$18,285,000
                         8-7

-------
8.10   COMMUNITY ACCEPTANCE
                     *
       Comments and responses from the July 14, 1994, Public Meeting were transcribed and are
included in the Responsiveness Summary (Appendix A). In addition, all written comments received from
the community are addressed in the Responsiveness Summary.


8.11    SUMMARY OF DETAILED EVALUATION

       Based on the comparison of alternatives that has been conducted in this chapter, the following
general conclusions may be drawn:

       •      Alternatives A and B would not meet the threshold evaluation criteria Alternative A would
              provide no protection of  human health and the  environment.  Implementation  of
              Alternative B (continue existing institutional controls, public education, continuous air
              monitoring, and periodic review of site conditions) would provide incomplete long-term
              protection of human health and the environment

       •      Alternatives C, D, and E would achieve the remedial action objectives by stabilizing the
              surface, cutting off oxygen to the field, and reducing the risk of fire and explosions at the
              site. Alternatives 0 and E would not actively treat the contamination at the site, but would
              rely on isolation of waste materials within the site to reduce the potential risks.

       •.      Alternative C would provide the  best long-term protection of human health and the
              environment and the best protection against potential agent releases from the site.  In
              addition, Alternative C includes the potential for treatment as a component of the remedy.
                                           8-8

-------
 9.0  SELECTED REMEDY
                           «
        Based  upon  consideration of the requirements of CERCLA, the  detailed analysis of the
 alternatives, and public comments, the U.S. Army, with the concurrence of the USEPA and MDE, has
 chosen Alternative C,  the construction of a Permeable Infiltration Unit, as the  most appropriate remedy
 for GU2 at the Old 0-Fieid soureo area of Aberdeen Proving Ground, Aberdeen, MO.

        The Permeable Infiltration Unit will be composed of sand or other granular materials. This sand
 layer will cover the entire surface of Old O-Field and be of sufficient depth to reduce both the likelihood
 and  potential effects of an explosive or evaporative release of CWM from the site.  The thickness of the
 PIU  would be determined during the remedial design phase to balance the  blast-resistant and vapor
 attenuating properties of the cover versus the risk posed  by  excess weight on  Old 0>Field.  An air
 monitoring system will ba built into the PIU to allow monitoring for CWM within the pore space of the PIU.
 A sprinkler system will be constructed that will be capable of quickly wetting the surface of the PIU. In
 case significant levels of CWM are detected within the PIU, the sprinkler will be activated. In addition, the
 sprinkler system will be used to conduct a series of treatability studies to evaluate the feasibility of
 enhanced  leaching of the  contaminants to groundwater, where  they  will be captured  by the  OU1
 groundwater extraction system and treated The subsidence of the field will be  monitored to evaluate the
 stability of Old O-Field and its ability to bear a load.

        The OU1  groundwater  extraction and treatment system  will be Devaluated to ensure that
 contaminated groundwater emanating from Old O-Field will continue to be captured and treated.

        Institutional controls will be Implemented to limit access to the site, prevent disturbance of the
 sand layer, and provide long-term maintenance of the PIU. Land use restrictions will be implemented to
 limit  the future land use of the  site and require permits,  qualified supervision, and  health and safety
 precautions for any activities conducted at the site.


 9.1      REMEDIATION GOALS

       The purpose of this interim response action is to control the risks associated with exposure to
 CWM and other chemicals within the Old O-Field surface and subsurface soil.  This response-action will
 central these risks by covering the site with non-flammable materials, minimizing the air flow to the surface
 c- Old O-Field, stopping erosion and stabilizing the soil, providing a blast-resistant layer on top of the
c:. -ance, and providing a vapor  barrier to reduce the concentration of CWM from an underground
release. Existing conditions at the site have been determined to pose a hazard to human health and the
environment at an unacceptable level  Although the possibility of a CWM release is small, the potential
 effects of a release are large enough to justify the need for an interim remedial action at this tima

       To evaluate the feasibility of enhanced in-situ leaching, treatability studies will be performed using
the sprinkler system and the OU1 groundwater monitoring system In addition, the subsidence of the PIU
will be monitored to evaluate the ability of Old O-Field to bear a load. These data will be used to evaluate
the final remedy for the site.
                                                                       i

9.2    COST OP SELECTED REMEDY

       The total capital costs for installation of the PIU is estimated at $11.041,000,  The total annual
costs are estimated at $269,000, and the total present worth of these costs, calculated with a 5% discount
                                             9-1

-------
rate over a lifetime of 30 years, is $15,175,000. These costs are outlined in Table 9-1.  The time and cost
estimates for this alternative are highly dependent on several factors, including:

               construction methods;
               health and safety considerations;
               sssur-pt'ons made for stability/setttements of Old 0-Fie!d surface;
               amount of time required for surface investigations/clearance prior to construction;
               assumptions made for topography; and
               delays due to clearance or other range operations.
                                             9-2

-------
               TABLE S-t
Summary of Costs for the Selected Remedy
 Alternative C: Permeable Infiltration Unit
-;••• •-?>' ; .:*'-••• " .' n1-; -6;-- JTEMN& ™^€;r •=• ttfr: -;;--l-/'
Capital Costs
Administrative Actions
Site Preparation and General Actions
Surface UXO Clearance
Permeable Infiltration Unit Construction
Long-Term Monitoring
Contingencies (60% of Capital Subtotal)
Engineering & Design (25% of Capital Subtotal plus
Contingencies)
Permitting & Coordination
COST

$50,000
$1,097,000
$700,000
$3,847,000
$485,000
$3,708,000
$962,000
$192,000
Annual Operation and Maintenance Costs
Program Oversight
Long-Term Monitoring & Five-Year Reviews
Contingencies (25% of Annual Subtotal)
Present Worth of Annual O&M (30 years, 5% discount rate)
Total Present Worth (Capital and Annual Costs, 30 years at 5%
discount rate)
$78,000
$137,000
$54,000
$4,134,000
$15,175,000
                  9-3

-------
 10.0  STATUTORY DETERMINATIONS

       The Army's primary responsibility at its NPL sites is to undertake remedial actions that achieve
 adequate protection of human health and the environment When complete, the selected remedial action
 for this site must comply with applicable or relevant and appropriate environmental standards established
 Lnds»r Federal and State environmental laws unless a statutory waiver is justified. The selected remedy
 also must be cost-effective and utilize permanent solutions and  alternative treatment technologies or
 resource recovery technologies to the maximum extent practicable.  Finally, the statutory preference for
 remedies that employ treatment that permanently and significantly reduce the volume, toxicity, or mobility
 of hazardous waste as  their principal element should be satisfied, if feasible. The following sections
 discuss how the selected remedy meets these statutory requirements.


 10.1   PROTECTION OF HUMAN HEALTH AND THE ENVIRONMENT

       The selected interim remedy protects human hearth and the environment  by  reducing the
 probability and severity of releases due to fire or explosions, while maintaining a moist subsurface and
 enhancing  degradation and leaching of  the wastes.  Short-term risks during  construction could  be
 controlled by property selecting application methods during the concept design phase.  Alternative C will
 therefore not present unacceptable short-term risks when weighed against the risks posed if additional
 action is  not  taken.  The permeable  layer would  stabilize  the existing surface of the field and offer
 increased protection against fires and explosions. The layer would allow Infiltration of precipitation and
 additional water provided by a sprinkler system. Saturation  of the permeable layer would  reduce CWM
 vapor emissions. Treatment processes could be tested by adding chemical reagents to the applied water.
 Continued or accelerated leaching of contaminants would occur, and the leachate would be collected by
 the groundwater extraction and treatment system.


 10.2   COMPLIANCE WITH APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS

       The selected  remedy, construction of a PIU,  will comply with all applicable or  relevant and
 appropriate chemical-, action-, and location-specific requirements (ARARs). The remedy will achieve the
 chemical-specific ARARs through the use of surface water runoff controls and use of construction
 methods that  minimize the generation of dust There are no location-specific or action-specific ARARs
for this interim remedial actioa  The ARARs are presented below.

 10.2.1  Chemical-Specific ARAR«

       The State of Maryland has promulgated surface water quality standards and use classifications
       for surface waters (COMAR 26.08.02)  (applicable).

       The State of Man/land regulation which sets the primary standard for paniculate matter (COMAR
       26.11.03) (applicable).

       The State of Maryland regulation  establishing ambient air quality standards to protect public
       health and welfare (COMAR 26.11.15) (applicable).

10.2.2 Location-Specific ARARs

       None.
                                            10-1

-------
 10.2.3  Action-Specific ARARs

        None.

 10.2.4  Other Criteria. Advisories, or Guidance To Be Considered for the Remedial Action (TBCajt

        Institutional controls will be implemented to limit access to the site, prevent disturbance of the
 sand layer, and provide long-term maintenance of the PIU. Land use restrictions will be implemented to
 limit the Mure land use of the site and require permits, qualified supervision, and health arid safety
 precautions for any activities conducted at the site.


 10.3   COST EFFECTIVENESS

        The selected  remedy is  cost-effective because it  has been  determined  to provide  overall
 effectiveness proportional to its costs, the net present worth being $15,175,000. The estimated costs of
 the selected remedy are less than the cost of the foam cap and multi-media cap.


 10.4   UTILIZATION   OF   PERMANENT  SOLUTIONS   AND   ALTERNATIVE  TREATMENT
        TECHNOLOGIES (OR RESOURCE RECOVERY TECHNOLOGIES) TO THE MAXIMUM EXTENT
        PRACTICABLE (MEP)

        The Army, EPA, and the State of Maryland have determined that the selected remedy represents
 the maximum extent to which permanent solutions and treatment technologies can be utilized In  a cost-
 effective manner for the source control interim action at Old O-Fleld.  Of those alternatives that are
 protective of human health and the environment and comply with ARARs, the Army, EPA, and the State
 of Maryland have determined that this selected remedy provides the best balance of tradeoffs in terms
 of long-term effectiveness and permanence, reduction in toxicity, mobility, or volume achieved through
 treatment, short-term effectiveness, implemerttability, cost, also considering the statutory preference for
 treatment as a principal element and considering community acceptance. The PIU will allow continued
 migration of contaminants to the groundwater treatment system, and offers flexibility in the overall remedial
 action by allowing the  performance of treatability studies and subsidence monitoring that will lead to a
 final remedy for the site.

        Excavation and treatment options were considered in the Feasibility Study for this project,  and
 these alternatives were judged as being too dangerous to implement at this time, due  to unknown
 conditions and the risk of release of CWM during invasive activities. Therefore, the alternatives considered
 in the detailed evaluation consisted of containment options, in addition to No Action and Limited Action.

       Without the construction of this remedy, Old 0-Field poses the potential threat of an explosion
 and  air  release of CWM or the rupture of a buried container and evaporative release of CWM.  The
 possibility of this occurring is small, but not insignificant, while the effects of such an event, should it
 occur, could be severe. The construction of a PIU will minimize the potential for an air release to occur
 and will  also reduce the effects of such a release,


 10.5   PREFERENCE FOR TREATMENT AS A PRINCIPAL ELEMENT

       The statutory preference for remedies that employ treatment as a principal element is satisfied by
this remedial action. Treatability studies of in-situ enhanced  leaching will be performed to  evaluate the
ability of water and other solutions to flush the contaminants from soil The construction of a permeable

                                           10-2

-------
infiltration unit will allow rainwater and applied solutions to percolate to the buried materials and contin, ,o
the-natural degradation of the buried materials.  Further treatment may be addressed by the final remedy
                                           10-3

-------
11.0 SELECTED REMEDY
       TTie proposed plan for Operable Unit Two, Old 0-Field, Aberdeen Proving Ground, Aberdeen
MD, was released for public comment on June 22,1994.  The Proposed Plan identified Alternative C'
the Permeable Infiltration Unit, as the preferred alternative. The U.S. Army, USEPA. and the State of
Maryland Cepartrr.snt of the Environment reviewed and considered aJi comments receivea during the
public meeting and during the public comment period. Upon review of these comments, it was
determined that  no significant changes to the remedy, as it was originally identified in the Proposed
Plan, were necessary.
                                          11-1

-------
 12.0 REFERENCES


 APG, U.S. Army Aberdeen Proving Ground.  1994a Phase I Remedial Investigation Report for the 0-Field
       Area, Aberdeen Proving Ground, MD. Prepared by ICF Kaiser Engineers.

 APG, U.S. Army Aberdeen Proving Ground.. 1994b. Focused Feasibility Study for the Old 0-Field Source
       Area, Aberdeen Proving Ground, MO. Prepared by ICF Kaiser Engineers.

 APG, U.S. Army Aberdeen Proving Ground. 1994c.  Proposed Plan for the Old  O-Field Source Area,
       Aberdeen Proving Ground,  MO. Prepared by ICF Kaiser Engineers.

 ICF Technology, Inc.  1987. Feasibility Study of Excavation and Clean-Up Options for the Old 'O* Field,
       "Edgewood Area-Aberdeen Proving Ground, Final Report  T. Wpp, et al., Fairfax, VA.  Prepared
       for Environmental Management Office, Aberdeen Proving Ground, U.S. Army Materiel Command,
       Aberdeen Proving Ground,  MD.

 Nemeth, G., Murphy, J.M, Jr., and J.H. Zarzyckl.  1983.  Environmental Survey of the Edgewood Area of
       Aberdeen Proving Ground, Maryland:  U.S. Army Toxic and  Hazardous  Materials  Agency,
       Aberdeen Proving Ground,  Maryland, Report No. DRXTH-AS-FR-82185.

 Nemeth, G.  1989.  RCRA Facility Assessment Report, Edgewood Area Aberdeen Proving  Ground,
       Maryland. U.S. Army Environmental Hygiene Agency, Aberdeen Proving Ground, Maryland.

 Parks, D.M. 1986.  O-Field Modification to Historical Location of Disposal Pits. Unpublished memorandum
       to Installation Environmental Quality Coordinator, Aberdeen Proving Ground, Maryland.

 U.S.  Army Environmental Hygiene Agency. 1977. An Assessment of Surface Waters, Aberdeen Proving
       Ground- Edgewood Area, Maryland. Water Quality Biological Survey No. 24-0043-78.

 U.S.  Department of the Army. 1991 a. Interim Action Proposed Plan, Old O-Field Site, Aberdeen Proving
       Ground, MO.  Prepared by ICF Kaiser Engineers.       ,

 U.S.  Department of the Army.  1991tx  Interim Action Record of Decision, Old O-Field Site, Aberdeen
       Proving Ground, MO. Prepared by ICF Kaiser Engineers.

 USATHAMA, U.S. Army Toxic and Hazardous Materials Agency, U.S.  Department of the Army. 1990.
       Focused  Feasibility Study of Groundwater Treatment Alternatives for Old O-Field, Aberdeen
       Proving Ground. Prepared  by ICF Kaiser Engineers.

USATHAMA, U.S. Army Toxic and Hazardous Materials Agency, U.S. Department  of the Army. 1991b.
       Old O-Field Aquifer Testing  Program. Prepared by ICF Kaiser Engineers.

USATHAMA, U.S. Army Toxic and Hazardous Materials Agency, U.S. Department  of the Army.  1991c.
       Old O-Field Groundwater Treatability Studies.  Prepared by ICF Kaiser Engineers.

USATHAMA, U.S. Army Toxic and Hazardous Materials Agency, U.S. Department  of the Army. 1991d.
       Old O-Field Groundwater Extraction and Treatment System Conceptual Desiga Prepared by ICF
       Kaiser Engineers.

USATHAMA, U.S. Army Toxic and Hazardous Materials Agency, U.S. Department of the Army. 1992. O-
       Field Remedial Investigation/Feasibility Study Work Plan.  Prepared by ICF Kaiser Engineers.

                                           12-1

-------
USGS, U.S. Geological Survey, U.S. Department of the Interior.  1991. Ground-Water, Surface-Water and
       Bottom-Sediment Contamination in the 0-Field Area Aberdeen Proving Ground, Maryland' and
       the Possible Effects of Selected Remedial Actions on Ground-Water. Open-File Report 89^399

Yon. R.L, Wenz, D.J., and C. Brenner.  1978. Information Relevant to Disposal of Hazardous Material at
       O-Field, Abardeen Proving Ground, Maryland.  Record Evaluation Report 1973-1!, Chemical
       Systems Laboratory, Aberdeen Proving Ground, Maryland.

Yon, Roy.  1994.  SciTech Services, Inc. Various written and personal communications.
                                           12-2

-------
                             APPENDIX A
                     RESPONSIVENESS SUMMARY
I.    TRANSCRIPT OF THE PUBUC MEETING

II.    RESPONSES TO COMMENTS RECEIVED AT THE PUBUC MEETING

III.    RESPONSES TO WRITTEN COMMENTS RECEIVED DURING THE PUBUC COMMENT
     PERIOD

     A.    COMMENTS RECEIVED FROM THE ABERDEEN PROVING GROUND SUPERFUND
           CITIZEN'S COALITION

     B.    COMMENTS RECEIVED FROM MR. GAIBROIS

IV.    RESPONSES TO SURVEY FORM SENT TO ALL CITIZENS ON THE APG MAIUNG LJST

V.    RESPONSES TO SURVEY FORM SENT TO ALL TECHNICAL REVIEW COMMITTEE MEMBERS

-------
                             RESPONSIVENESS SUMMARY

                        I. TRANSCRIPT OF THE PUBLIC MEETING
       The transcript of the Public Meeting (July 14,1994) for the Proposed Plan is attached. During the
question and answer session, Army, EPA, and State of Maryland representatives responded to questions
from the audience.

-------
  i




  2




  3




  4




  5




  6




  7




  8




  9




10




11




12




13




14




15




16




17




18




19




20




21
                  ABERDEEN PROVING  GROUND




                       PUBLIC  MEETING









                            FOR









                  OLD 0-FIELD  SOURCE  AREA
                MAGNOLIA ELEMENTARY SCHOOL




                     901 TRIMBLE ROAD




                     JOPPA, MARYLAND









                      July 14, 1994




                        6:30 p.m.
Reported by:



Heather R. McLauchlin
                    TOWSON REPORTING COMPANY

-------
 2                      PROCEEDINGS



 3            BARBARA FILBERT:   Welcome to  our  public  meeting



 4    tonight.   We appreciate your taking the time  to  learn more



 5    about our environmental program.   The purpose of this



 6    particular meeting is  to  discuss  one  of the proposed



 7    cleanup  actions at the Old 0-Field area/  which is on the



 8    Gunpowder Neck peninsula  in Aberdeen  Proving  Ground's



 9    Edgewood area.



10             I'm Barbara Filbert from the Aberdeen Proving



11    Ground Public Affairs  Office.   First/  I'd like to



12    introduce several  people  here  tonight who can answer



13    questions you might have  about this project or others:



14    Mr. Joe  Craten/  who's  Director of APG's Directorate of



15    Safety/  Health and Environment; Ken Stachiw/  who's Chief



16    of the Environmental Restoration  and  Conservation



17    Division;  John Paul, who's  project officer for risk



18    assessments;  Cindy Powels/  who's  the  project  engineer for



19    0-Field.



20             Also with us  this  evening is  Steve Hirsh and



21    Kathy Davies  from  the  US  Environmental Protection Agency
                   TOWSON REPORTING COMPANY. INC.

-------
 1    and John Fairbank from the Maryland  Department  of  the



 2    Environment.   I would also like to point  out  that  Chris



 3    Grochowski of the APG Superfund Citizens  Coalition is here



 4    this evening.  The citizens coalition  is  an active



 5    citizens group involved in our  environmental  cleanup



 6    program.



 7             Since this is a required meeting, we have a court



 8    reporter present to record all  of our  proceedings.  The



 9    transcript from tonight's  meeting will be available for



10    your review at the Aberdeen and Edgewood  branches  of the



11    Harford  County Library,  Washington College in Chestertown,



12    and Essex Community College in  Essex.



13             After Cindy Powels completes  her presentation, we



14    will open the meeting for  questions  and comment.   We have



15    index cards at the entrance of  the room.  If you didn't



16    already  receive one,  we'd  be glad to give you one.  And



17    you can  write questions  on the  card, and  we'll  collect



18    them at  the end of the presentation.   However,  of  course,



19    we  will  still try to address your verbal  questions  or



20    comments.



21             I hope everyone picked up one of the fact  sheets
                    TOWSON REPORTING  COMPANY,  INC,

-------
      that was at the demonstration table back here.   It  more  or



 2    less gives an overview of the proposed cleanup  actions



 3    that we're going to present tonight.



 4             If you have questions on other areas of our



 5    environmental program/  please see myself or any of  the



 6    individuals from Aberdeen Proving Ground that I



 7    introduced.  We will be glad to answer your questions.



 8    And  if  we don't have the answer/  we'll certainly get back



 9    to you.   We also have an information  line available



10    twenty-four hours a day.   If you're not aware of the



11    number/  the local number is 272-8842.   For Kent and



12    Baltimore County residents/ we have an 800 number.  It is



13    800-APG-9998.



14             Now I  will turn the meeting  over to Ken Stachiw/



15    who  will give you an overview of  APG's installation and



16    restoration program.



17             KEN STACHIW:   Good evening again and welcome to



18    our  presentation about  Old 0-Field.   What I'd like  to do



19    is perhaps  give a setting of what we're talking about to



20    bring the big picture into a narrow focus.  Aberdeen



21    Proving  Ground  has a .fairly comprehensive environmental
                    TOWSON  REPORTING  COMPANY/  INC,

-------
      program which we more or less define with four pillars.



      It is defined by prevention,  conservation,  compliance and



      restoration.



  4             Prevention is our attempt to try — our attempt



  5    before a project begins such  as  to do a test or to  do an



  6    operation or to build a building or something of this



  7    nature.   We're increasing the mission capacity of APG.  We



  8    study it and determine its environmental impact before we



  9    actually complete the task.



10     .        Conservation is our  attempt to manage wildlife



11    and other types of our ecosystem at APG.  Frequently  the



12    environmentalists get so hung up on hazardous  materials



13    that we  can't see the forest  for the trees  so  to speak.



14    And we feel that it's very important that we manage life



15    as  opposed to just having a sterile environment/  you  know,



16    chemical free.



17             We're  trying to create  something that enhances



18    life and allows life  to propagate,  you  know, both in  the



19    Chesapeake Bay  and on the terrestrial areas  of  APG.



20    That's the ultimate goal of the  environmental  program.  It



21    should be the ultimate goal of the  environmentalists  in
                    TOWSON REPORTING roMoawv.  rwr

-------
  I    general.
        i

  2             Compliance is part of the program that is


  3    dedicated toward having all of the emissions  and concerns


  4    of this nature in compliance with regulations.   Things


  5    like air pollution control, permits from incinerators,


  6    permits from existing landfills,  the management and


  7    regulation of existing facilities.   That's  pretty much


  8    what compliance is dealing with.


  9             Within the realm of this,  things  such  as the Ghent


10    Derail facility falls under this realm.   Tonight's topic


11    will not discuss things like the  Chera Oemil or  the


12    stockpile disposal.   We're not here to  address  that


13    particular issue tonight/  but if  there  is  sufficient


14    interest/  we can always get those people together to have


15    a  meeting and discuss that further.


16             Things such as the UNDEX pond  or some  other


17    concerns have been raised in the  past/  or radiation/ they


18    are  all various topics  which are  not really what  this


19    evening was  scheduled for.   We don't have the experts


20    assembled for that,   we're here to  focus on restoration


21    tonight.   I'll speak a  little bit about that program and
                   TOWSON REPORTING COMPANY, INC.

-------
  1    then narrow the focus down from that to Old 0-Field.



  2             Now, restoration is a program that's designed to



  3    take past contamination and restore it back to — as  best



  4    we can — conditions in accordance with various laws  and



  5    so forth.



  6             Just to give you a history of APG,  the Aberdeen



  7    area here was first established in 1917-1918 time frame



  8    and was dedicated to the use of — for testing military



  9    equipment,  testing weapons and the like,  as  you're



10    probably familiar with/  those who live in this area.   The



11    Edgewood area was devoted primarily to research and



12    development,  testing and production of chemical warfare



13    and related materials,  chemical warfare agents.   Both,  as



14    you can imagine, are highly industrial activities.  Both



15    required the  use of lots of hazardous  materials.   And,



16    obviously,  both resulted in the use and disposal  of



17    various types  of hazardous waste,  both in the  Aberdeen



18    area and the  Edgewood area,  different  types  perhaps, but



19    still hazardous.



20             Back  in 1917 through roughly  1970,  okay,  the



21    environmental  laws  were  not that many.  There  wasn't that
                    TOWSON  REPORTING  COMPANY.  INC.

-------
  1    much in the way of regulations for the disposal of
  2    hazardous materials at that time.   So people did what  they
  3    thought best at that time in terms of burial or other
  4    means of disposal.  As time went on and environmental
  5    science grew/  we began to realize  that some  of  the past
  6    activities were not good enough.
  7             They did what was best, and I don't judge their
  8    intentions of their hearts.   But as it turns out/  some of
  9    the way they managed their waste products at that  time
10    ended up in contamination.
11             In roughly the mid-80s to late-80s,  the EPA
12    charged us to look back in our history and determine what
13    kinds of contamination may have resulted from all  our past
14    operations.   And we did that/  and  we did a two-and-a-half
15    year study in both areas.
16             With the studies  — and you can find these
17    studies  in the libraries we  talked about at  Edgawood and
18    Aberdeen/  you  can read these studies.  And there are the
19    two  major studies.   They determine in total  three  hundred
20    eighteen —  roughly — solid waste management units.
21             By  a  "solid waste management unit/*  I mean a unit
                   TOWSON REPORTING COMPANY/ INC.

-------
 1    with solid — a location where solid waste was  managed,



 2    not necessarily disposed,  but managed.   Okay.   A place



 3    where they may have stored a rack of drums of solid  waste,



 4    a place where they may have disposed of  something,



 5    incinerated something.  Primarily the idea being that



 6    while solid waste was managed there,  the potential exists



 7    for there being a release  of hazardous materials  in  that



 8    location.



 9             So some of these  sites  may  be no bigger  than this



10    table,  and some of the sites are as  big  as this  room, and



11    some of the sites are as big as  a 30-acre landfill.  So



12    there is a whole variety.   They  are  not  the same  size.



13    Some you couldn't get them on a  map  because they  are so



14    small.



15             But we do have these, and all of them by



16    regulation,  by law, have to be addressed.  We don't know



17    whether anything has been  released into  the environment



18    because of these things or not.   But  we  have to at least



19    investigate,  go back,  look into  them  and make a



20    determination as to whether or not something took place



21    that needs to be fixed.
                    TOWSON  REPORTING  COMPANY,  INC.

-------
                                                              10
  1             For the sake of management, okay,  these were  sort



  2    of clustered into thirteen study areas.   Here'3 a map



  3    of — you can't tell completely by this  map,  but it's



  4    color coded, the whole map is divided up into thirteen



  5    particular units.  At each of them we're going to have to



  6    do a fairly detailed investigation,  and  we're regulated by



  7    the EPA to come up: with a set of documents  that defines



  8    the problems,  okay,  presents  solutions,  works with the



  9    public to come up with a final decision,  and  then an



10    implementation of that decision,  and then monitoring.   Let



11    me show you a  diagram of this.



12             This  is the process  by law that we have to go



13    through for these thirteen study areas.   The  first step is



14    preliminary assessment and site investigation.   This is



15    primarily handled by the documents  that  I talked about



16    that are in the library that  identify them.



17             The next step is what is termed "remedial



18    investigation.*  And that's where we do  in-depth



19    environmental  sampling.   We sample  the ground water.   We



20    look at the site,  and we determine was there  a  release  to



21    the  environment.   If there was a  release, how far did  it
                    TOWSON  REPORTING  COMPANY,  INC.

-------
                                                              11
  2
  3
  4
 5
 6
 7
 8
 9
10
11
12
13
14
15
16
17
18
19
20
21
    i
 go  and where is  it going to  go in  the  future.



          We also do what's termed  a  "feasibility  study."



 And in this feasibility study,  we're determining, okay,



 now that we know what  the contamination  is, what  is a



 proper solution  to this problem.   Will it solve itself.



 Do  we  need to dig it up.  Do we need to  put a barrier



 around it to contain it.  What's the proper solution to



 this.   That's called a "feasibility study."



          The feasibility study and remedial investigation



 also include a thing called  a  "risk assessment," which



 helps  us  determine exactly what we need  to do to clean up.



 It  determines the  risk involved so we can determine if



 cleanup  is  necessary or not.



          The end result,  of  these  documents is called the



 "proposed plan."   The  feasibility  study makes a



 recommendation and says,  We  think  this is what should



 happen at this site.   The proposed plan tells the world,



 This is what we  propose  to do.  Does anyone want to change



 this?  Do you have any objections  to this?  If you do,



please speak now and put  input  into this particular



decision-making  process.
                    TOWSON REPORTING  COMPANY,  INC.

-------
                                                              12
 i             Once a meeting is held like tonight,
 2    information is gathered together/  the material  comes
 3    back to ourselves  and the EPA and  AP6 and a  decision  is
 4    made based upon all these things together as to what  is
 5    the wisest solution to that particular problem  and  that
 6    leads to what is termed a "record  of decision."  The
 7    decision is published in the newspapers saying.  Based upon
 8    all the studies and input, we think this is  the best  thing
 9   .to  do in this situation.
   *
10             At that point,  a design is made on  whatever  the
11    decision is.   It's called a "remedial design.*   That  has
12    public review time as well.   Once  the design is  completed
13    and the design is  put into place,  built,  constructed, the
14    remedial action begins.
15             This could take  place in  all of six months and be
16    completed.   It may take fifteen years for the action  to be
17    totally completed.   During that time,  monitoring is done,
IS    as  well as  a  five-year assessment,  to see, you  know,  we
19    thought this  was the right move/ was it correct  indeed.
20    We  go back  and reevaluate it and make sure the
21    contamination that we proposed to  manage in  this way  is
                                   !  rriwoauv

-------
                                                              13
      baing effectively managed.



               If not,  then we have to go back and begin the



      process all over again so to speak, at least to make a



 4    determination as  to what we need to do to amplify or



 5    enhance the system.



 6'             If it's  working,  we bring it to completion.   If



 7    the site seems to be totally cleaned up, we  make a



 8    proposal that the thing be considered done.



 9             Now, we're 'supposed to do this for  all of the



10    thirteen study areas.   Unfortunately,  they are  so big and



11    complex,  all right, that sometimes it would  take years and



12    years and years before we  come to a final decision on the



13    entire piece of property that we're trying to dearl with.



14             So the laws allow us to do what are termed



15    "interim actions."   Actions which make sense to do now.



16    It's  not necessarily the final solution,  the most



17    comprehensive solution,  but it's something that makes



18    sense to. do now while  you're coming to grips with the



19    final solution.   And that's what we're going to be talking



20    about tonight when  we  talk about an interim  action.   It's



21    something that makes sense to do now for environmental
                    TOWSON REPORTING  COMPANY,  INC.

-------
                                                              14
 I    protection so that further degradation of  the  environment



 2    and safety is promoted while  we're  continuing  to make a



 3    full determination as  to  what the final solution should



 4    be.



 5             The  law allows us to do what  are  termed "interin;



 6    RODs/"  and "early action  RODs."  And that's part of this



 7    process.   Right  now we're in  the process of coming to a



 8    recommendation decision about a location.called 0-Field.



 9    Cindy is  going to describe this to  you in  depth/ but for



10    now/  we're just  focused on this.  And  I want to make a



11    point that this  is  not the only problem here at APG.



12    There are lots of study areas.  There  are  lots of



13    decisions to  be  made/  but this is only one.  And'we're



14    focusing  on this effort tonight.  It doesn't mean we're



15    not  going to  look at what's going on up here/ it means



16    we're focusing on this red dot that's  Old O-Field tonight.



17             We're going to try to focus our discussion on



18    that  tonight  itself.   If  for  some reason you have



19    questions about  some of the other sites, we're more than



20    happy to  address those perhaps on the  side after the



21    meeting or perhaps  in  our offices later on.  We're more
                   TOWSON REPORTING COMPANY/ INC.

-------
                                                              15
  I    tnan happy to address those.  As Barbara said,  we have an



  2    information line.  All you have to do is pick up the phone



  3    and ask the question, and we'll get back to you with an



  4    answer.  So, once again, we'll focus on Old 0-Field.



  5            Cindy, are you ready to go now?  Okay.



  6            BARBARA FILBERT:  As Ken said,  Cindy will be



  7    giving us an overview of the cleanup actions that are



  8    proposed for this particular site.  She's been  an



  9    environmental engineer for over thirteen years,  and  she



10    joined Aberdeen Proving Ground in 1985.  She is



11    responsible for overseeing all actions  at 0-Field as  well



12    as  the Westwood area of APG.  Now she will give  a



13    presentation.



14             CINOT POWELS:  If we leave these lights  on,  can



15    everyone see okay to read these?  If not,  just please let



16    me  know.  If you can't hear me,  please  let me know.



17             For my presentation,  what I'd  like to do is



18    briefly go through a little bit about the location and



19    history of the site and then get into what we've  done as



20    far as our feasibility study to look at the hazard



21    assessment,  the goals that we want our  proposed  actions to
                    TOWSON REPORTING  COMPANY,.  INC.

-------
                                                              16
 1    accomplish,  and then look at the alternatives that we



 2    evaluated.   And then I'll briefly go through a schedule  of



 3    some of our  future activities that we're planning for this



 4    site.




 5             As  Ken mentioned,  the site that we're going  to  be



 6    talking about is called Old 0-Field.  The 0-Field area is,



 7    again/  located in the Edgewood area about two-thirds  of



 8    the  way down the Gunpowder  Neck.   We right now are located



 9    here at the  Magnolia Elementary School.   It's about five



10    miles  from 0-Field to where we are now,  just to give  you



11    an idea of some- distances there.



12             This shows the O-Field study area/  and the



13    0-Field area has two major  disposal sites.   The Old



14    0-Field area,  which is what we're  going  to talk about



15    today/  and then the New 0-Field area.  Historically these



16    areas were used — this Old 0-Field area was  used from the



17    late 1930s until 1953.   It's a four-and-a-half  acre



18    landfill.  It was  used for  disposal of chemical  munitions/



19    chemical  warfare agents/  wastes  from the research and



20    development  operations that were conducted in Edgewood.



21    Contaminated equipment was  disposed of at the site/ and
                   TOWSON REPORTING COMPANY/  INC.

-------
                                                              17
  1    other miscellaneous hazardous wastes.  There was also some



  2    burning and some detonations that were done in the Old



  3    0-Field area.



  4             After this area closed in the early '50s,  the New



  5    0-Field area was established to get rid of some of the



  6    wastes that were being taken out of here,  they were being



  7    taken here and were being disposed and detonated and open



  8    burned.  There was also some limited disposal  at the new



  9    area.  We know that the ground water has been



10    contaminated, and it's migrating towards Watson Creek and



11    will then be discharged .into the Gunpowder River.



12             In 1991 we went through this exact process that



13    we're going through now, and we made the decision" to  treat



14    the  contaminated ground water as it's migrating from  Old



15    0-Field toward Watson Creek.   And the way  we're doing that



16    is by installing extraction  wells along here in between



17    the  landfill site and where  the water discharges  into



18    Watson Creek.   So we're basically stopping that water,



19    taking it out of the ground.   We then run  it through  the



20    ground water treatment plant to remove all the



21    contamination,  and that clean water will then be
                    TOWSOM REPORTING  COMPANY,  INC.

-------
                                                              18
  1    discharged into the Gunpowder River.



  2             Right now we're also continuing environmental



  3    studies of the whole area/  principally focusing on  New



  4    0-Field and Watson Creek,  and those studies  will continue.



  5    Today,  again,  I want to focus on this  landfill  site here



  6    and the feasibility study that we've recently just



  7    accomplished.



  8             As I  mentioned,  the Old 0-Field area here,  there



  9    have been several attempts  in the past to clean up  this



10    area; however,  they have been very limited to mostly



11    disposal  and cleaning up of surface debris.  There  hasn't



12    been a  lot of  excavation.   So a lot of those munitions are



13    still in  place out there.



14             We know there have been several unplanned



15    detonations and fires out there,  one of  them as  late as



16    1984 where there was a fire.   One of the munitions  caught



17    fire and  set the field on fire.



18             Because we feel  that there is a continuing risk



19    from detonations and from fires  on the site, we  feel tnat



20    we  need to do  something to  control those risks,  and



21    that's why we  conducted this  feasibility study  to further
                    TOWSON REPORTING COMPANY,  INC.

-------
  1
  2
  3
  4
  5
  6
  7
 8
 9
10
11
12
13
14
15
16
17
18
19
20
21
                                                              19
 reduce the risks from these areas.



          The first step  in  the  process  was  to  conduct  a



 hazard analysis, and what we did  is  we  used the  worst  case



 scenarios and calculated the risk.   So  any  actual  risk



 would be much less than  the risk  that we  calculated.   The



 bottom line is that there is a  risk  from  a  fire, from  a



 detonation causing effects  to nearby workers and on-post



 residents.   It would take a very  large  event to  occur  to



.actually effect off-post citizens; however, any  risks, we



 feel,  are unacceptable.  And that's  why we  want  to take



 these  actions to try to  protect the  public  as much as



 possible.



          The  chances  of  a catastrophic  event happening are



very  low.   You would  have to have the right conditions.



You would have to  have exact weather conditions to have



off-post releases,  but,  still,  we feel  we need to do



something to  prevent  those  from occurring.



          Currently we're addressing the hazard at the site



by restricting access to the  area.  Mo  one has access to



the area without going through  a lot of health and safety



plans being prepared.  Security at the  area has been
                    TOWSON REPORTING COMPANY,  INC.

-------
                                                              20
 i    upgraded quite a bit recently/  and we've  got a  lot  of



 2    security measures out there  now.



 3             Also,  we're installing some  air  monitoring



 4    systems  out  there around  the perimeters of  the  field.



 5    We've  got five units that are being installed,  one  is also



 6    already  on line.   And they will run continuously taking



 7    samples  every eleven to fifteen minutes.  They  will be



 8    monitoring for nerve agents  as  well as mustard.  Once



 9    that's running smoothly,  we  plan to upgrade  that system



10    for other types  of chemicals as well.  And  emergency



11    response procedures  are,  of  course, in place in case there



12    was an incident.



13             In  order to further reduce the risks,  our



14    feasibility  study established some  goals  that we want each



15    alternative  to meet,  and  those  goals  are  shown  here.



16    Basically we want to make  sure  we reduce  the risks from



17    allowing a fire or a detonation to  occur.  We want to



18    prevent  these things as much as possible.  We also want to



19    reduce the risk from evaporation.   If something starts to



20    surface  out  there/ we want to prevent evaporation from



21    that leak occurring.  Further,  we also want  to  reduce or
                   TOWSON REPORTING COMPANY, INC.

-------
                                                              21
      e.liininate any effects if there was a fire or if there  was



 2    a detonation.  So we have not only prevention of a fire  or



 3    detonation but also a way to try to contain it or control



 4    it.



 5             Our next step in our feasibility study was  to



 6    perform an initial screening of alternatives.   We looked



 7    at quite a few, and two key factors that  we used to



 8    evaluate them were whether or not they would protect the



 9    public,  the workers here/  and the environment/  not only



10    over time but also during implementation.   This is where



11    we construct or implement one of the alternatives and  see



12    is it going to protect human health to the workers and to



13    off-site residents and then make sure that the  technology



14    was  reliable in meeting the goals that we  just  discussed.



15             We looked through quite a few alternatives/ and



16    some of  the ones that we screened out I'm  going to go



17    through  just briefly.   .Basically they were eliminated



18    either because they had unacceptably high  short-term risks



19    for  implementation or because they had questionable  or



20    uncertain effectiveness in whether or not  they'd be  able



21    to meet  the goals that I discussed.
                    TOWSON REPORTING COMPANY/  INC.

-------
                                                              22
  1             Excavation is one option I think all of us  would



  2    like to see.   We'd like to see that thing dug up and go



  3    away.   But/  unfortunately, we feel the risks of doing that



  4    are just much too great.   And we can't subject either the



  5    workers or the off-site residents to the risks involved  in



  6    trying to excavate this area.   You've got munitions  which



  7    could  be explosive.   You've got chemical warfare agents.



  8    If  you had a  fire and a release during the excavation/ we



  9    would  be concerned with off-post migration of the chemical



10    agent.



11             There is a lot of a substance called white



12    phosphorous out there.   White phosphorous was used by the



13    military to create smoke.   When it's exposed to air/  white



14    phosphorous will start  burning.   It was  also used by the



15    military for  its effectiveness at causing fires.   We don't



16    want white phosphorous  starting to become exposed and



17    being  in contact with air  and  catching fire.



18             There are also other  items out  there that could



19    be  shock sensitive and  cause explosions.   To excavate/



20    unfortunately/  right now would be much too much risk that



21    we  wouldn't be able  to  implement.
                    TOWSON REPORTING  COMPANY/  INC.

-------
                                                              23.
  i             Some of the other alternatives that we looked at



  2    included various types of explosion resistant caps as well



  3    as vertical barriers.  The ones that we screened out had



  4    unacceptable short-term risk or we are uncertain about



  5    their effectiveness.



  6             Other options included cutoff floors,  entombment,



  7    containment structures.  Again, these had questionable



  8    effectiveness and/or unacceptable short-term risks.



  9             In-situ treatment was another alternative that we



10    looked at that was screened out.  That would be trying to



11    treat the waste in place.  And that was screened out



12    because of unacceptable short-term risks and effective



13    technology currently being unavailable.



14             Off-site treatment was also considered;  however,



15    that  would have required excavation.



16             And, finally, ex-situ treatment was considered.



17    That's treatment on-site, but that would,  again,  require



18    this  being dug up.   That would require excavation and



19    involve high short-term risks.



20             The alternatives that we came down  to  for our



21    detailed evaluation are shown here,  and we've got five
                    TOWSON REPORTING COMPANY,  INC.

-------
                                                              24
 1    alternatives here.   And I'm going to  go  through  each  one


 2    in  further detail just a little.


 3             The no-action alternative is required by  law to


 4    be  evaluated primarily as a base  line for  the other


 5    alternatives.   The  limited-action alternative is basically


 6    what  we  already have.   It would require  long-term


 7    monitoring,  access  restrictions similar  to what we have,


 8    and land-use restrictions as far  as future use.


 9    .         The next alternative that I  want  to talk  about is


10    what  we  call a "permeable infiltration unit."  It  would


11    basically consist of covering the surface  with sand which


12    would provide a barrier to animal intrusion/ a barrier to


13    oxygen getting to white phosphorous and  possibly'causing


14    fires.   It would help  give protection if there was a  fire.


15             Plus,  the  key feature here that is different than


16    the other two options  I'm going to talk  about next/ is it


17    would allow  water to infiltrate or permeate through the
                                                            t

18    sand  and through the waste material underneath.  And  the


19    water then that would  go through  the  sand  would then  be


20    captured by  our ground water treatment plant which is now


21    being installed.  And  the positive feature here that's a
                    TOWSON  REPORTING  COMPANY/  INC.

-------
                                                              25
  1    little different than the other two alternatives I'm going



  2    to go through is that this would allow us to perform



  3    further studies to evaluate,  can we do enhanced leaching



  4    or enhanced degradation by applying water or solutions  on



  5    top of the sand to percolate  through the waste to



  6    encourage the natural degradation that's currently taking



  7    place.



  8             Based on what we see now in the ground water/  we



  9    can see that a lot of these agents are naturally degrading



10    and then going into the ground water,  and we're going to



11    pick that up through our treatment system.



12             This would be considered an interim action



13    because it would require us to further study treating the



14    waste in place through enhanced leaching and enhanced



15    degradation.



16             This is a cross-section to  give you an idea of



17    what this might look like —  and this  is just an initial



18    idea.   You would have several feet of  sand on top of the



19    landfill.   The sand would be  allowed to  fill in the voids



20    where there are trenches,  holes,  erosion.  The sand would



21    tend to fill  in these areas and stabilize the surface of
                    TOWSON  REPORTING COMPANY,  INC.

-------
                                                              26
 1    the field.   We would have the air-monitoring system in

 2    here where  we would be able to pick up any vapors  if there

 3    were any in the area.   So we would be able to pick them  up

 4    early and detect them right away.

 5             Then we have more sand.   Then we  have a

 6    geotextile  fabric followed by gravel or crushed stone to

 7    prevent wind or soil erosion on top of the sand.   And then

 8    we  would have a sprinkler system which we  would use  so if
                       \
 9    there is an air release or fire we could quickly quench  it

10    by  getting  a barrier to the site.   Plus we could use this

11    to  further  study ways  to treat the waste in place  and to

12    encourage the waste to degrade.  But that  would have to  be

13    studied in  further  detail after we've got  the cover

14    ins-tailed.

15             The next option that I want to talk about would

16    be  considered a final  action/  and  this would be covering

17    the field with an impermeable foam cap that would  not

IS    allow water to get  through the waste.   Basically we  would

19    spray a. thin layer  of  polymerizing urethane foam over the

20    surface of  the field.   This would  give us  very similar

21    protection  as far as preventing a  fire or  preventing an
                   TOWROM TJWOnoi'TMr'  rnwnnMV   r\if

-------
  1
  2
  3
  4
  5
  6
  7
  8
 9
10
11
12
13
14
15
16
17
18
19
20
21
                                                              27
 explosion,  but it would  not  contain  a  fire or explosion as



 the  sand cover would.  We  would  then have a polysulfide



 coating applied to the top so  that it  would not break
down.
          This  would  provide the  same good protection that
the permeable  infiltration unit would.  The foam would



basically  cover  the  field followed by the lining to



prevent  sun  from degrading the foam.



         One of  the  benefits or positive features of the



foam is  that it's very light weight.  It won't create a



high load  on the field as far as weight.  Plus, this is



something  that could be sprayed on.  We won't have to



have heavy equipment running over the top of the field,



and we would remotely apply that using robotics.  However,



we would have to remove the vegetation from the site



similar to what  we would do with the permeable



infiltration unit.   The short-term risk here would be less



because you  would not have so much direct work on the



field surface itself.



         The last alternative that we looked at is a



hazardous waste  landfill cap which would be constructed to
                    TOWSON  REPORTING COMPANY,  INC.

-------
  1
  2
  3
 4
 5
 6
 7
 8
 9
10
11
12
13
14
15
16
17
18
19
20
21
                                                              28
be  impermeable/  again/  to prevent water from infiltrating
into  the  site.   This  one, again/  as  the other ones,  would
help  prevent  fires  and  help prevent  explosions.   This
would give  us better  blast protection  than the foam  cap
but not quite as good as  the sand does  because the
complex layering system would be  a little easier  to  breach
than  the  thick  layers of  sand.
          To give you  an idea of what a  cross-section might
look  like through the hazardous waste  landfill cap,  you
would have  several  feet of crushed sand and  gravel at the
bottom, followed by geograde for  stabilization/ and  then
some  more sand.   And  this would basically be  your
impermeable layer.  You would also have gas venting  strips
and a  drainage system to  collect  any water that would get
through this upper  layer  which would be soil.  And that
would  be  followed by  vegetation along the top.
          The five alternatives were then evaluated against
nine  criteria which are already established in the EPA's
regulations on conducting feasibility studies.  The  first
one is the most  important/ which  is the  overall protection
to human  health  and the environment.  The second one we
                           BPonofTwr:  rnvmawv   r\rr>

-------
                                                              29
  i    looked at is whether or not the alternative complies with



  2    environmental laws and regulations,  both state and



  3    federal.  We also thirdly looked at  long-term



  4    effectiveness and whether or not it  would be a permanent



  5    solution to our problem.



  6             Another important criteria  was  whether or not  the



  7    alternative would reduce  the toxicity and mobility and



  8    volume of waste through treatment.   Short-term



  9    effectiveness was probably one of our most critical



10    criteria we looked at because we don't want to make the



11    risks  any greater than they already  are.   And then,



12    finally,  we looked at whether or not we  could implement



13    the  alternative, whether  or not it was feasible.



14             We also looked at cost.  We looked at whether  or



15    not  the state accepted the alternative.   And,  finally,



16    we're  at this stage which is community acceptance.   And



17    that will be evaluated at the end of the  public comment



18    period.



19             We've got a quick summary here which shows  the



20    alternatives — which helps to show  the alternative  and



21    how  we evaluated it against some  of  the criteria.   Of
                    TOWSON REPORTING COMPANY,  INC.

-------
                                                              30
  1    course the no action and limited action are not acceptable
  2    because they don't meet the first criteria which is  the
  3    protection of human health.  So they didn't need to  be
  4    evaluated any further.
  5             The permeable  infiltration unit and hazardous
  6    waste landfill cap would both meet the criteria because  it
  7    would give you that blast protection.   The impermeable
  8    foam cap partially met  the requirement because  it  would
  9    not give you as much blast protection.  It would still
10    give you good protection as far as preventing a fire or  an
11    explosion,  but it would not give you the blast  protection.
12             And one of the things that I  should have
13    mentioned earlier — I  forgot — is that any of these
14    options  would not only  address the imminent explosion
15    hazards/  but it would also address the hazards  associated
16    with the low levels of  contamination that would be in
17    soil,  that  would be induced in the animals that might be
18    exposed  here.   I'm not  discussing that in great detail
19    because  the real high risks would be if there was a  fire
20    or  an  explosion.
21             As far as federal and state laws,  all  the

-------
                                                              31
  1    alternatives meet chose requirements.   With regard to



  2    short-term risks and short-term effectiveness,  all of  them



  3    have drawbacks.  The foam cap would have the least amount



  4    of short-term risk because it would be sprayed  on  by



  5    remote techniques without heavy equipment directly on  the



  6    field.



  7             Next, the permeable infiltration unit  which would



  8    have some short-term risks but not quite as much as the



  9    hazardous waste landfill cap which would have more



10    short-term risk than the other two primarily because it's



11    a  more complex layering system,  and it would be a  little



12    more difficult to install.



13             The permeable infiltration unit,  because  we would



14    be applying sand,  there would be a lot of  techniques that



15    would be evaluated in the concept design that we would be



16    able to evaluate the risks on how best to  apply that sand



17    so we could control the short-term risks.   For  example, we



18    might want to use water to slurry the  sand on the  field so



19    we wouldn't have to have heavy equipment out on the field.



20    We could use low ground pressure vehicles  which would have



21    less direct pressure on the field by distributing  the
                    TOWSON REPORTING  COMPANY,  INC.

-------
                                                              32
 1    weight more evenly.   In addition,  we would also  consider



 2    putting the sand on  in layers  where you push  the sand  out



 3    before you actually  drive out  onto the  field  to  apply  it.



 4             With regard to long-term  effectiveness,  the



 5    permeable infiltration unit  would  give  you the best blast



 6    protection but similar protection  as far as prevention.



 7    The  foam cap would give you  the  least amount  because it



 8    would not give you blast protection.  And the hazardous



 9    waste landfill cap would be  somewhere in the  middle as far



10    as blast protection/  not quite as  much  as the permeable



11    infiltration unit/ but better  than the  foam cap.



12             With regard to reducing toxicity and volume of



13    the  waste/  we felt that the  foam cap and the  hazardous



14    waste landfill cap only partially  meet  these  requirements



15    because  they would reduce the  mobility  of the waste/ but



16    it would not help  reduce the toxicity or the  volume as



17    would the permeable  infiltration unit.



IS             As  far as implementation/  the  permeable



19    infiltration unit  would be the simplest and easiest to



20    install.   Next would  be the  hazardous waste landfill cap



21    which is  a  little  more complex because  of the layering

-------
                                                              33
  1    system.   And the foam cap would be very implementable  but



  2    would only partially meet the criteria because you  would



  3    have an  extra six months involved in developing the



  4    technology.



  5             Cost effectiveness/  this just shows  the capital



  6    costs.   There would also be operation and maintenance



  7    costs, and those would be in the fact sheets  for the



  8    feasibility study.



  9             Based on our evaluation, we feel that the



10    permeable infiltration unit is  our preferred  alternative



11    because  it gives us the best  balance of features with



12    regard to the overall protection, of human health and the



13    environment.   It would reduce the risk of fires  as  we've



14    discussed,  and it would reduce  the risk of detonation as



15    we've discussed.  And it would  reduce the risks  associated



16    with a fire or detonation if  one would occur.  Plus it



17    would reduce  the risk of evaporation.



18             Also,  an added feature to this option would be



19    the  fact that you've got an air monitoring system.  So if



20    there was an  air release,  we  could try to contain that



21    vapor release.   Plus it would allow us to treat  the waste
                    TOWSON REPORTING  COMPANY,  INC.

-------
                                                              34
 1    in place by encouraging the natural  degradation  and



 2    breakdown of the waste in place.



 3             Our original comment  period was  scheduled to end



 4    September 5th.   We've received a  request  to  extend that



 5    comment period,  and it will be extended to at  least



 6    September 6th at this point.   We'll  review the comments as



 7    they come in.   We plan to try  to  make our decision early



 8    this fall and publish a record of the decision.  The



 9    immediate remedial design would then be conducted this



10    fall/  this winter/  and into the summer.   And we  would hope



11    to get a remedial action — start accomplishing  that in



12    the fall of '95.



13      .      Some of the activities which would  have to be



14    conducted as part of the design would include  some field



15    activities.   Of  course we'd have  to  have  a health and



16    safety plan prepared in order  to  go  out there  which would



17    insure the safety of the on-site  workers  as  well as the



18    community.   The  types of data  to  be  collected  would



19    include topographic surveys/ site inspection/  soil



20    sampling/  as well as physical  parameters.



21             Some  of  the components of the concept design that
                    TOWSON REPORTING COMPANY, INC,

-------
                                                              35
      I want to touch on so people are aware of what  they should



 2    expect when we go to design would be a detailed evaluation



 3    of the specific risks that  would be involved  with  each



 4    stage of the construction process.   We have to  look at  the



      risks and say "What is the  safest way to  do what we need



 6    to do?"



 7             I think we would also  then select our  cap



 8    materials and the actual thickness  of the cover system



 9    based on looking at the hazards and the risk  at the site.



10    We would also then select the method for  how  are we going



11    to remove the vegetation and things like  that.  Those



12    would all be part of the concept design.   We  would also do



13    a preliminary work plan to  look at  how we treat the  waste



14    in place and also to look at how the landfill is shifting



15    over  time.



16             Then,  finally, the  final design  would cover any



17    responses that we would get  to  the  concept design  as well



18    as the specifications,  the  cost estimates, the



19    construction schedule,  the engineering report and  final



20    health and safety plan for implementing that.



21             In addition to the  information that we've  gone
                    TOWSON REPORTING COMPANY,  INC.

-------
                                                              36
 1    through today/  as  Barbara mentioned,  there are  some



 2    documents  that  are out there in the public libraries,  and



 3    there  is a lot  out there.  We would encourage you, if



 4    you've got questions,  to go through those  documents, call



 5    our  information line.   We've got information displayed in



 6    the  back.   This is just some more of  the information that



 7    is in  the  public record.   We've got a fact sheet, and



 8    we've  got  the proposed plan which is  a nice concise



 9    summary of what we're  proposing,  and  a summary  of the



10    feasibility study  and  the rationale that we went through



11    to come up with- this preferred alternative.



12            Again,  those  are at the back.  I  would encourage



13    anyone who's interested to please take one and  please  give



14    us your input.   Public input is very  critical to our



15    decision-making process.   And that basically concludes my



16    formal presentation.   I'll now turn it over to  Barbara.  I



17    think  wa want to allow the state and  EPA to make a



IS    comment.



19            STEVE  HIRSH:   The EPA has been working with the



20    Army with  Edgewood since  about 1986.   In 1987 we saw the



21    first  feasibility  study for the source at  Old 0-Field, and

-------
                                                              37
  1    basically it looked at all the options that Cindy had up



  2    here,  and the decision at that time was that none of  these



  3    were developed enough to do anything about 0-Field at that



  4    time.   In 1991/ as Cindy said, our ground water  ROD was



  5    written.   At that time it seemed like that was the most



  6    critical  threat to health and the environment.   So a  ROD



  7    was written and a decision was made to put in that



  8    treatment plant.   And I want to tell you that the



  9    .construction of that is ongoing and completion of that is



10    rather close,  sometime early in the fall.



11             Again/ in '87 they first looked at this  and  the



12    Army looked at it again/  and we did the hazard assessment.



13    We  reviewed all that data/  and the EPA believes that  the



14    most significant  threat for 0-Field right  now is  the



15    explosion threat  or a vapor release.   We evaluated the



16    excavation option,  and something that Cindy didn't mention



17    is  that if we  could excavate all this waste out of there,



18    we  would  still have an explosion problem.   Right  now  there



19    is  no  way to do that.   There is no system.   There  is  no



20    off-site  disposal facility for that waste.



21             So at this time  the EPA agrees with the Army that
                    TOWSON REPORTING  COMPANY,  INC.

-------
                                                              38
      this  is the right action to take.   We  concur with  it,  and



 2    we look forward to evaluating the  comments  that  you'd  like



 3    to submit.



 4             JOHN FAIRBANKS:   I'm John Fairbanks.  I'm with



 5    the State of Maryland.   As you can see from Cindy's



 6    presentation,  0-Field is  a very complex and difficult  site



 7    to work on.   The state  has been working with the Army  and



 8    the EPA since 1990.   We took a little  bite  at  the  ground



 9    water.   The state views this as a  little bite  at the



10    source.   We've concurred  with what the Army wants-  to do.



11    But like the EPA/  we'll certainly  consider  any of  the



12    comments that you have.



13-            BARBARA FILBERT:   Now we'll take any  comments or



14    questions you might  have.   Please  raise your hand  if you'd



15    like  an  index card to write the question on and get back



16    to us.   Or,  to make  it  easier for  the  court reporter, we



17    do ask  that  you need to stand up when  you state the



18    question and state your name and where you're  from before



19    you ask  your question.  I'd also ask that just one person



20    speaks  at a  time so  the reporter can take everything down.



21    Does  anyone  have any questions?
                   TOWSON REPORTING COMPANY, INC.

-------
  I             CHARLES GRACE:  Charles Grace.  G-r-a-c-e.   I



 • 2    live over in the Joppa area on Joppa Road and Fountain



  3    Road.  You know, it seems to me in driving here I don't



  4    get over into the east side of Pulaski Highway quite as



  5    much as the west; however,  I see new developments.   I see



  6    this school.  We're setting off like a Love Canal.   And



  7    it's incredible to me that  all the years up through  what



  8    we are today since 1954,  that that existed and that  any



  9    time we could have had an explosion, we could have had a



 10    fire.  And all of this is reinforced by what we received



 11    from Harford County emergency evacuation plan.'



 12             And we're talking  about now you're looking  at



 13    options.   Options that may  or may not be something that's



 14    prudent,  and we're looking  at the state.  They are



 15    agreeing  to something that  they don't know will work.   And



 16    I  guess I'll close on my  horn here,  but I don't really



 17    trust the Army.   We had several years ago,  you might



 18    recall, a chemical area building that was just horrendous



 19    in as far as any protection to workers, 'environment and/or



20    containment.



21             The Army let two of our Harford Countians hang in
                    TOWSON REPORTING  mMPaWY.  TMP

-------
                                                              40
  !    the wind,  and you might all recall this,  right.   from
  2    that,  when I hear this presentation,  when I see  now that
  3    they are going to come and make a decision, how  can we
  4    possibly at this point — we,  speaking for myself,  not  say
  5    an expert, you know,  in design,  but how can we possibly
  6    confute or refute anything that you have  there.
  7        .     And my ultimate question,  those  three options,
  8    have they  been tested?  Are they new technology?  So I
  9    think  what I'm saying is that  we in Harford County,  we
10    honestly,  although we love this  county, we honestly have
11    been sitting on a powder keg here,  and the Army  has
12    allowed it.
13            They have not done one  earthly thing, obviously,
14    from their testimony  here.   And  if  we may have
15    explosions — unplanned explosions  — vapors or
16    phosphorous  or whatever,  then  I  suggest we all look  at
17    that emergency evacuation plan.   I  think  that it should be
18    more than  what we have/ and we should have a critical
19    analysis from someone that is  not connected with the Army,
20    not  connected with the state and not  connected with  the
21    EPA.
                    TOWSOM REPORTING COMPANY,  INC.

-------
                                                              41
  1     .        CINDY POWELS:  Thank you for your comments.   I



  2    appreciate that input.



  3             BRIAN FEENEY:  I have a question.   Brian Feeney.



  4    F-e-e-n-e-y.  And my involvement in this is as  the



  5    technical adviser to the Aberdeen Proving Ground Citizens



  6    Coalition.  I hope to allay some of the gentleman's



  7    concerns that we are independent of the Army and EPA,  and



  8    we represent the citizens'  concerns.   And I will have



  9    written comments later.



10             I just have one simple question now, and that is,!



11    the operation and maintenance portion of units  one and two



12    may go on for a very,  very  long time.   Have any



13    contingencies been developed or considered  for  the



14    possibility of global  warming causing sea-level rises



15    which  might increase the trench area  of Old 0-Field and



16    might  also inundate the  treatment system at operable unit



17    one?



18             CINDY POWELS:   I don't know  how to say it except



19    that we have not considered that.



20             BRIAN FEENEY:   And would the  Army  consider that



21    worth  looking into and responding to?
                    TOWSON  REPORTING  COMPANY,  INC.

-------
                                                              42
               CINDY POWELS:   At this point in time,  it's  hard



  2    to say whether or not it is.   I'd have to talk  to our



  3    consultants as well and evaluate,  you know,  what the risks



  4    would be if we did have such  climate  changes, how it would



  5    affect the system.   I don't know if Nora can add anything



  6    more.   It's just something brand new.



  7            BRIAN FEENEY:  I would like to emphasize that



  8    while this may sound out of left field/  it's something
                 \


  9    that  the Army Corps of  Engineers is already  analyzing as



10    relevant to maintaining the superstructure of the United



11    States,  the roadways and rails and so  forth.



12             CINDY POWELS:   That's a brand new idea  that we



13    have  not considered..  I would imagine  that we have not



14    considered that for the other study areas that we're



15    looking  at.   But I'd certainly like to talk  about it some



16    more because I'd like to learn more about it and see how



17    it would apply to some  of our study areas.



18             JOHN PAUL:   Cindy/ it might be  useful for you to



19    tell people how high above sea level the actual  0-Field



20    site is.



21             CINDY POWELS:   0-Field is a local high  there.
                   TOwsnu pWDOBTTun rnwoawv   rwr

-------
                                                              43
      It's ebcut ten to fifteen feet above sea  level.



 2             BRIAN FEENEY:   What's the  elevation  of  the  waste



 3    water treatment system?



 4             CINDY POWELS:   Similar.  I'll  say  about fifteen



 5    feet.   I couldn't say for sure, but both  that and the



 6    ground water treatment system  are local highs in the



 7    area«



 8             BRIAN FEENEY:   A related question  is:   It's



 9    fairly well known as  a concern related  to sea-level  rise,



10    the  inundation of hazardous waste dumps up  and down  the



11    East Coast.  And this/ of course, would be  one of those.



12    And  what happens when you have inundation,  you have  a



13    brand  new site of hydrological effects that may  affect



14    that site.



15             CINDY POWELS:   It would totally change  the  ground



16    water  treatment system because right now we are  influenced



17    by the surface water  because it's shallow.



18             BRIAN FEENEY:   And it would have a lot  of very



19    complicated effects.



20             KEN STACHIW:  Let me  address that.  We  view this



21    as one of the remedies for a planning stage scenario that
                    TOWSON  REPORTING COMPANY,  INC.

-------
                                                              44
 1    projects options that would be eicher to dig it out  and



 2    move it, or some sort of institution for utilization.  We



 3    view this particular step as an interim phase in that



 4    direction.   Once we're able to put  a cap on  it,  it allows



 5    us  to be able to maneuver on top of it.   The possibility



 6    to  institute further work or for that matter even in the



 7    future having a dig-out of that,  is much more feasible



 8    under any of these scenarios than it is  in the current



 9    position.   So we see that as an interim  step in  that



10    direction if that's what we end up  doing.



11             BARBARA FILBERT:   Are there any other questions?



12    If  there are no more questions,  I would  like to  remind



13    you,  as  Cindy said,  the public comment period which began



14    on  June  22nd ends on September 6th.   Written comments must



15    be  postmarked no later than September 6th.   They can be



16    sent to  Ms.  Cindy Powels,  Directorate of Safety,  Health



17    and Environment,  U.S.  Army,  Aberdeen Proving Ground



18    Support  Activity.   The complete address  is in the fact



19    sheet.



20             BRIAN F.EENEY:   I  was  going to ask you,  there was



21    an  overhead  with a series  of task completion dates on
                   TOWSON REPORTING COMPANY,  INC.

-------
                                                              45
  1    rhem,  and it would be helpful if we could see that  again.



  2             CINDY POWELS:   I  think this is  what  you  wanted.




  3    If there are no further  questions or comments,  then this




  4    will conclude our meeting.   We'll be available  afterward



  5    at the information display for anyone who has further



  6    questions



  7             BARBARA FILBERT:   And there is  a short evaluation



  8    form in the back of the  room,  or at the  entrance, rather.



  9    And-we would appreciate  if  you could just take a  minute to



10    fill it out before you leave.   Again,  thank you for your




11    interest and time in the Proving Ground's installation and



12    restoration program.



13             (Proceeding was concluded at 8:30 p.m.)



14



15




16



17



18




19



20



21
                    TOWSON REPORTING COMPANY,  INC.

-------
                                RESPONSIVENESS SUMMARY

             II. RESPONSES TO COMMENTS RECEIVED AT THE PUBLIC MEETING
Response to Mr. Grace:

       The Army will continue to seek and incorporate the participation of the public in decisions related
to the Installation Restoration Program at APQ. The Army desires to gain the confidence of the public that
their best interests have been considered. Also, the Army wishes to emphasize that the overall protection
of human  health and the environment is the principal goal of all Army environmental actions.

       The remedy proposed for the Old O-Field source area, construction of a Permeable Infiltration
Unit, is a new technology that has been developed specifically for this unique site.  Based on our best
understanding of the physical characteristics of the site and the risks posed by the site, this remedy will
greatly reduce the possibility that dangerous chemicals will be released from the site in the future. The
remedy will accomplish this by stabilizing  the site, minimizing the possibility of a fire of explosion,
providing blast protection, and attenuating any vapors that could be released from the site. This remedy
also allows the Army to continue to test more permanent remedial technologies by evaluating the stability
of the site  and the effect of enhanced leaching of the contaminants from soil This remedy, although not
tested at other sites, offers many advantages over the other technologies considered because it offers
better protection of human health and the environment with smaller short-term risks.


Response to Mr. Feeney:

       Global warming may certainly have far-reaching  effects on environmental actions at APG in the
future. As the implementation of the remedies for OU1 and OU2 continues, the Army will consider the
effects of a potential rise In the sea level on both the Old O-Field source area and the OU1 treatment
system.

-------
                               RESPONSIVENESS SUMMARY

 III. RESPONSES TO WRITTEN COMMENTS RECEIVED DURING THE PUBUC COMMENT PERIOD
A.     COMMENTS RECEIVED FROM THE ABERDEEN PROVING GROUND SUPERFUND CITIZEN'S
       COAUTION
General Comment
Comment:     Although APGSCC concurs with the U.S. Army and the U.S. Environmental Protection
              Agency (EPA) that the Permeable Infiltration Unit (PIU) appears to be the most protective
              of human health and the environment of the five proposed alternative actions, members
              of APGSCC continue to have a number of questions and concerns regarding this
              proposed action. Old 0-Field is a very complex site; not only because of the wide variety
              of toxic as well as explosive compounds present on the site, but also because of the
              many uncertainties associated with the site. It is difficult to make accurate predictions on
              many aspects, including the potential for explosions, the human and ecological risk, and
              the impact of proposed actions on the stability of the site.  Thus, APGSCC believes we
              must proceed carefully and cautiously, being sure that tax dollars are being spent wisely.

Response:     The Army agrees that the action must proceed cautiously and that wise expenditure of
              public funds is paramount  The Army believes that the risk reduction  benefits that will
              result from construction of the PIU on Old 0-Field greatly outweigh the short-term risks
              associated with the construction process. During construction, the risks will be minimized
              by selection of the safest construction and monitoring methods.  After the PIU has been
              built, it will stabilize the site and minimize the likelihood of an explosive release from Old
              O-Field. The conceptual design phase for the PIU will evaluate all possible construction
              methods to control and minimize the risks during construction.

-------
                               RESPONSIVENESS SUMMARY

III. RESPONSES TO WRITTEN COMMENTS RECEIVED DURING THE PUBLIC COMMENT PERIOD
Comment 1.
Comment:     A primary concern of APGSCC Is whether the Army has adequately considered the
              impact of the proposed action at OU2 (i.e. placement of the PIU) on the OU1 groundwater
              treatments system that is currently being constructed at Old 0-Field.  It is important to
              consider the extent to which placement of the PIU will alter 1) the rate and/or direction of
              flow of the contaminated groundwater and 2) the types and concentrations of chemicals
              present in the groundwater. Enlargement of the contaminant plume that presently exists
              under Old O-Field will most  likely occur  after placement of the cap due to increased
              pressure from the weight of the sand and due to the additional water that will be pumped
              onto the field to maintain the desired level of moisture.  Will the OU1 groundwater
              treatment system be able to capture and adequately treat all contaminants emanating
              from Old O-Field after Installation of the PIU? Have estimates been made of the amount
              of water that will need to be pumped onto the capped area? The effectiveness of the IRA
              proposed for OU2 is, in large part, dependent upon the efficacy of the  OU1 water
              treatment system.  It Is not  clear to APGSCC that APG has  considered all  possible
              scenarios for changes that might be needed in the OU1 treatment plant after placement
              of the PIU.

              Related to this Issue is the fact that the Army may also use the OU1 water treatment
              facility to treat contaminated groundwater from other source areas at APG (e.g. New O-
              Field, an unnamed site west of Old O-Field and the J-Field Toxic Bum Pits). Citizens must
              be assured that the OU1 plant will not be loaded beyond capacity, and that any increases
              in treated gallons/day will not occur at a faster rate than the plant can be redesigned and
            .  enlarged.

              APGSCC is also concerned  about what affects potential explosions may have on the
              integrity of the OU1 water treatment system and the monitoring wells surrounding Old 0-
              Field Has the Army considered possible scenarios In this area? If so, please explain in
              detail

Response:    The potential impact of the proposed action on the OU1 treatment system is a matter of
              prime importance to the Army. As noted in the comment, the OU1 groundwater treatment
              system has been overdesigned purposely, and the treatment facility building has been
              oversized to allow further increase in plant capacity if necessary.  Preliminary assessment
              of PIU operations (including addition of water) indicates that the design capacity of the
              treatment system will not be exceeded However, the OU1 groundwater monitoring and
              extraction systems will be reevaluated during the design phase for the PIU to assess the
              need for additional wells. This evaluation will be performed in two ways. First, computer
              simulations of the PIU are being conducted to model the effect of the application of water
              to Old O-Field on groundwater flow. The model results will be used to plan the locations
              and depths of new extraction wells, if any are required Secondly, data will continue to
              be collected from the  existing monitoring and extraction wells to  assess the exact

-------
                               RESPONSIVENESS SUMMARY

III.  RESPONSES TO WRITTEN COMMENTS RECEIVED DURING THE PUBLIC COMMENT PERIOD


              changes to groundwater flow direction and changes in contaminant concentrations when
              water is applied. These data will be used to confirm that the treatment system capacity
              is not being exceeded.

              The preliminary model scenarios have incorporated application rates of water in the range
              of 20-40 gallons per minute, without yielding significant impact on groundwater flow
              direction or the water table. Estimates of probable water application rates and the effect
              on the existing and expanded extraction system will depend on details of the PIU, which
              will be considered during the design phase.

              With the addition of the air stripping and carbon adsorption units, the OU1 groundwater
              treatment system has evolved into a very flexible system that is capable of handling high
              concentrations of organic and inorganic contaminants. At present, the capacity of the
              system is twice what is needed for the OU1 extraction system. Therefore, the Army
              expects that the OU1 system will be capable of handling the additional load resulting from
              the addition of the PIU. To ensure that the OU1 system will operate within its limits, the
              design phase for OU2 will include an evaluation of all credible scenarios and potential
              effects  on the OU1  treatment system.  Any required  upgrades or changes  to the
              extraction  and  treatment system  will be considered  in  the  OU2 design  and
              implementation.

              The Army has considered the possible effects of explosions on the integrity and operation
              of the groundwater  treatment system.  For the current condition of  the field,  it  is
              conceivable,  although unlikely, that an explosion could damage the wells or  piping
              systems and temporarily interfere with operation of the system.  One of the primary
              benefits of the PIU is that It will reduce the likelihood that an explosion will take place  at
              Old O-Field.  The primary potential cause of an explosion at Old O-Field is fire, and the
              chance of fire will be minimized by greatly reducing the flow of air to the buried materials
              through construction of the PIU. Shock or pressure on ordnance are other potential
              causes of an explosion at the site, and this will be eliminated by placement of the sand,
              which attenuates transmission of applied forces to the ordnance items. In addition, the
              design of the PIU will attenuate fragment velocities and blast pressure if an explosion
              does occur,  which reduces or eliminates the damage such an event would cause.
              Therefore, the PIU win afford protection to the treatment system and  wells from an
              explosive event  During construction of the PIU, contingency plans will  be in effect to
              address any potential effects on the OU1 treatment system.

-------
                               RESPONSIVENESS SUMMARY
                             t

III.  RESPONSES TO WRITTEN COMMENTS RECEIVED DURING THE PUBUC COMMENT PERIOD
Comment 2.
Comment:     It is very important that a good monitoring program be established following this interim
              action to assure that placement of the PIU does not cause contaminants to escape from
              Old O-Field in higher concentrations or via different pathways than those currently under
              investigation.  Groundwater from monitoring wells around Old O-Field and the wells
              pumping water to the treatment plant must be tested on a regular basis for the full suite
              of possible contaminants and for all forms of radloactivftv to be sure that changes in
              groundwater contamination are detected eariy.   Additional  monitoring  wells and
              piezometers might well be needed to adequately monitor groundwater  flow and
              contaminant migration. Sediments, benthlc organisms and pore water from Watson Creek
              and the Gunpowder River should also be monitored to measure changes in contaminant
              inputs in areas  near Old  O-Field.   These results  will safeguard against  increased
              environmental contamination which could result from changes In the rate or direction of
              groundwater flow or from a greater release of contaminants from ruptured vessels within
              the landfill

Response:     The Army believes that a comprehensive program to monitor groundwater, surface water,
              air, and PIU stability is a critical part of the proposed interim actioa As discussed in the
              response to Comment 1, the ability of  the existing  groundwater extraction system to
              capture all of the contaminated water emanating from Old O-Field will be assessed.  If
              needed, the extraction  system  will  ba upgraded  to ensure  capture of the  entire
              contaminated plume, which will be verified by regular performance monitoring of the OU1
              system.  There is less need to continue monitoring of sediment, benthlc organisms, and
              pore water from  Watson Creek and the Gunpowder Rh/er because the only transport
              pathway from Old O-FIeld to these media, after completion of the PIU, is via groundwater
              and therefore contaminants win  no longer continue to migrate to Watson Creek.  In
              addition, potential contamination within these media is being investigated as part of the
              overall RI/FS for O-FiekL

-------
                               RESPONSIVENESS SUMMARY

III.  RESPONSES TO WRITTEN COMMENTS RECEIVED DURING THE PUBLIC COMMENT PERIOD
Comment 3.
Comment:     APGSCC is concerned about potential radiation contamination within the fenced area of
              Old O-Field.  Historical documents indicate that radioactive waste in the form of animal
              carcasses were once buried at Old O-Field.  Has past sampling in this area included
              monitoring for radioactivity? If so, what monitoring wells were tested and when did this
              sampling take place? Was radioactivity ever detected in either soil or groundwater at Old
              O-Field? If so, what were the levels of radiation found and what background levels were
              they compared to? APGSCC would like to know whether the Army has ever conducted
              a thorough search of  its Atomic Energy Commission (AEC) or National Radiation
              Commission (NRC) licenses to determine where radioisotopes were used, stored and
              disposed of on base.

Response:    The historical information indicates that the animal carcasses were removed from Old O-
              Field shortly after burial there to prevent other animals from digging them up. Therefore,
              there is no reason to suspect radiological contamination. During the USGS  Investigation
              of Old  O-Field conducted In 1985-1986, groundwater samples were collected from
              monitoring wells OF6A, OF6B, OF6C, and OF17A (located downgradient of Old O-Field)
              and analyzed for gross alpha, gross beta, tritium, and cesium-137. These anafytes were
              not detected at significant levels.

-------
                               RESPONSIVENESS SUMMARY

III.  RESPONSES TO WRITTEN COMMENTS RECEIVED DURING THE PUBLJC COMMENT PERIOD
Comment 4.
Comment:     The stability of the cap placed on Old O-Field Is an important issue in the selection of the
              best alternative as the Interim remedial action for the Old O-Field source area  One
              reason for selecting the PIU cap over the foam and RCRA caps is that damage due to
              settling,  trench  collapses, and  explosions  can be repaired  most easily.   What
              consideration has been given to the general stability of the PIU cap? The sand cap will
              be much more prone to erosion and will probably require a significant amount of 'routine'
              repair. Has this been adequately calculated into maintenance costs? Will the sand cap
              be stable enough to function as intended?

Response:    The PIU is expected to require smaller amounts of care and maintenance than the other
              caps under consideration because of its 'self-healing* capability. In the event of a trench
              collapse or other subsurface movement, the sand will tend to flow and fill in depressions.
              During construction of the PIU, it is likely that hydraulic compaction will be used, where
              the sand layer is alternately wetted and allowed to dry.  Hydraulic compaction will greatly
              increase the stability of the PIU. Erosion control will be an integral part of the PIU design.
              One option under consideration is the use of a geotextile layer on top of the sand to
              prevent erosion by wind and water, and a layer of gravel on the geotextile to protect it
              and allow drainage into the PIU. The estimated costs  for maintenance of the cap have
              been included in the cost estimate presented In the Focused Feasibility Study Report

-------
                              •RESPONSIVENESS SUMMARY

III.  RESPONSES TO WRITTEN COMMENTS RECEIVED DURING THE PUBLIC COMMENT PERIOD
Comment 5.
Comment:    APGSCC is concerned that health risks associated with the Old O-Field Source Area
              (OU2) have not been properly estimated because of the inability of the Army to collect soil
              samples from within the fenced-in area  The difference in contaminant levels between
              outside the fence and the center of the 4.5 acre area could be very large. Could robotics
              sampling methods be used to obtain samples from within Old O-Field? If so, is there a
              danger that the robotics device might ignite a fire or  initiate an explosion that could
              release chemical  agents into the atmosphere?  If robotics are not used, what is the
              degree of danger faced by site workers walking on the  surface of Old O-Field?

Response:    As discussed in the Focused Feasibility Study Report, the risks posed to human health
              and the environment by the contaminants in surface soil within Old O-Ftald are far less
              than the risks posed by the potential for an explosive release of CWM from Old O-Field.
              In addition, any action taken to mitigate the explosive risk would also mitigate the risk
              posed  by contaminants in soil.   By constructing the PIU on Old O-Field, humans and
              animals would not be directly exposed to the contaminants. Leaching of contaminants
              from soil into the groundwater would not pose risks because the groundwater extraction
              and treatment system would remove the contaminated water from the aquifer and treat
              it to levels safe for discharge to the Gunpowder River.  Therefore, the need to directly
              sample the field (with the corresponding risks associated with such an invasive activity)
              is eliminated by construction of the PIU.

              The risks associated with direct sampling of soil within the field, even using robotics, are
              not justified, given that the data collected by such sampling will pertain to the less serious
              risks (posed by the contaminants in soil), which will be mitigated by the PIU concurrently
              with the more serious risk of an explosion or fire.

-------
                              RESPONSIVENESS SUMMARY

III.  RESPONSES TO WRITTEN COMMENTS RECEIVED DURING THE PUBLIC COMMENT PERIOD
Comment 6.
Comment:    APGSCC would like to have the Army make new data that is derived through the ongoing
             RI/FS process for Old O-Field available to the public in a timely manner. Any changes
             in the logic of this alternative selection or changes in the implementation of this selected
             alternative that are suggested by new data must be made known to citizens in time to be
             included in the public process, For example, APGSCC would like to know more about
             the contributory role of the other two contaminated O-Field areas, the New O-Field and
             the unnamed area,  and whether the groundwater treatment system will intercept
             contaminants from these areas.

Response:    The Army will continue to  make every effort to keep the community and APGSCC
             informed of new findings at the O-Field area For example, the draft Rl report for Phase
             I of the ongoing RI/FS effort has been sent to Army, EPA, and State of Maryland reviewers
             and will be released to the public as soon as review comments have been received by
             DSHE and addressed The Focused Feasibility Study report for Old O-Field was sent to
             APGSCC reviewers immediately after comments by the Army, EPA, and State were
             incorporated.

             The 'pit site* is under Investigation, initially by  performing geophysical surveys and
             sampling of  nearby monitoring wells.   From  available data,  it appears that  the
             groundwater emanating  from the 'pit site* is not contaminated at levels of concern and
             is flowing toward the Gunpowder River. The groundwater from the 'pit site* will not be
             captured by the OU1 extraction system as currently designed.

             The nature and extent of contamination at New O-Fleld has been the focus of the Phase
             I Rl effort Groundwater from New O-Field flows toward the east  and discharges into
             Watson Creek.   The current OU1  groundwater extraction system will not capture
             contaminated groundwater emanating from New O-Field.

-------
                               RESPONSIVENESS SUMMARY

III.  RESPONSES TO WRITTEN COMMENTS RECEIVED DURING THE PUBLIC COMMENT PERIOD
Comment 7.
Comment:     In the APG fact sheet on Old O-Field, the Army mentions the human population that could
              potentially be exposed to contamination present at the Edgewood Area of APG. There
              is no mention  of the 10,000+ population in the Joppatowne area, despite the fact that
              APGSCC has  continually brought this oversight to the attention of the Army.  The
              Joppatowne area has a large population that is, in some instances, closer to the
              contaminated  areas at APG than either Edgewood or Magnolia  One cannot help but
              wonder whether this community is considered when the Army conducts its studies. Such
              an oversight  casts doubt  on the thoroughness  and thus the  credibility of the
              investigations.   Also, without mention of the community in  the APG public fact sheet,
              many citizens  in this area may be misled into believing that they are not a potentially
              exposed population.

Response:     In the Record of Decision for OU2, Joppatowne, Edgewood, Magnolia, and Graces
              Quarters  are  denoted as the off-post areas closest  to  Old O-Reld  All nearby
              communities are considered in the risk assessments performed by the Army.

              In the Focused Feasibility Study report for Old O-Reld (APG, 1994b), preliminary air
              modeling was  performed to assess the risks posed by an explosive release at Old 0-
              Field.  It was concluded that the chance that off-post communities could be affected by
              an event at Old O-Field is very small It is more likely that nearby on-post areas such as
              H-Field, N-Field, and J-Field would be impacted due to proximity to Old O-Field.

-------
                               RESPONSIVENESS SUMMARY

III.  RESPONSES TO WRITTEN COMMENTS RECEIVED DURING THE PUBUC COMMENT PERIOD
Comment 8.
Comment:     This interim action, as with so many others, is a "cap it and wait* action because our
              hazardous waste technologies are not sufficiently developed to handle the chemical
              wastes present at this site. This Is a very important issue that must be addressed
              immediately.  We  must place every effort on developing new techniques for treating
              hazardous wastes  if we are to do more than just 'contain* our problems.  At this time it
              appears that the Army is willing to wait until the private sector develops new techniques,
              but there is little incentive for private industries to spend money on treatment systems that
              are suitable for Army specific chemicals.  It is time for the U.S. government to take
              responsibility and devote resources to this need In the past the U.S. government was
              more than willing to spend money developing, designing and manufacturing the various
              munitions needed  to defend our country.  They must now commit their resources to
              developing final solutions to our hazardous  waste problems.

              APGSCC would like total clean-up and remediation of APG's hazardous waste sites, not
              interim, less than ideal solutions.

Response:    The Army prefers remedies that effectively mitigate the risks in the long term, and will
              choose such final  remedies where possible. The Army has established research and
              development programs to  develop technologies potentially applicable to CWM and
              ordnance disposal sites, such as robotic excavation, in situ remediation techniques,
              incineration of CWM, and others. However,  the currently available permanent-treatment
              technologies pose short-term risks that the Army believes are  unacceptabry high for
             .application at the Old 0-Field site.  0-Fleld  poses unique hazards to remedial workers
              because of the presence of potentially live ordnance and CWM.  Although construction
              of the PIU would not eliminate the risks posed by an explosive release, it will reduce the
              likelihood that such an event would occur In the future, as well as the possible effects.
              Many contaminant release and exposure pathways (vaporization of CWM to air, explosive
              releases, direct exposure to the wastes, and  exposure to contaminated groundwater) are
              removed or minimized by construction of the PIU and the OU1 interim action.  For this
              site,  selection  of the  PIU  represents the use of risk management decision-making,
              whereby the short-term risks have been weighed against the potential long-term risk
              reduction that would result from stabilizing Old O-Fiekt

              In addition, unlike other capping actions, this interim action includes active elements. The
              design of the PIU specifically allows and promotes testing of both in-srtu treatment and
              degradation of the buried materials and geotechnical evaluation of Old O-Field to assess
              future excavation options.

-------
                               RESPONSIVENESS SUMMARY

 III. RESPONSES TO^WRnTEN COMMENTS RECEIVED DURING THE PUBUC COMMENT PERIOD





 B.  COMMENTS RECEIVED FROM MR. GAIBROIS





 Comment 9.
Comment:     Question 5 Comments - Aft C 'install a permeable infiltration unit1 It is noted that this 'unit*
              is not specified as a semi permeable barrier which would only infiltration of material in one
              direction, that the item as described could allow gross transfer of gases and liquids
              through the barrier,  the identification of a infiltration * means that materials can pass
              through the system.  That is not containment of a hazardous waste by RCRA. The use
              of 'unit* implies a mechanical/chemical device to use top process material That may be
              'treatment* of a hazardous waste IAW RCRA for which a permit would be required.

Response:    The PIU has been designed to allow the flow of water down through the unit This will
              allow rainwater and other solutions to percolate through the unit and into the buried
              materials. This process will allow the natural degradation of the buried materials to
              continue.

              For on-site treatment under a CERCLA response action, a permit is not required, although
              all substantive requirements of such a permit, if issued, would be met by any remedy
              selected by the Army.
Comment 10.
Comment:     Comments and Suggestions • I would recommend a combination of alt ,D. and E Aft A -
              no action, and B-flmited action are totally not appropriate. With the rejection of Alt A and
              B, unlimited or fun action has already been agreed to by APQ, EPA, and the State no
              matter which alternative is used.

Response:     The Army believes that selection of Alternative C (construction of the PIU) offers significant
              advantages over those offered by Alternatives D (foam cap) and E (multi-media cap). The
              PIU would stabilize the surface of Old O-fieto, minimize the likelihood of a fire and
              explosive release, and allow the natural degradation of the buried materials to continue.
              The PIU also offers advantages in ease of construction and maintenance, which reduces
              the tang-term risks even further.  Therefore, the Army, with the concurrence of EPA and
              the State of Maryland, will implement Alternative C.

-------
                        RESPONSIVENESS SUMMARY

!V. RESPONSES TO SURVEY FORM SENT TO CITIZENS ON THE APQ MAIUNG UST
 Survey forms were sent to over 300 citizens on the APQ Installation Restoration Program (IRP)
 mailing list of interested community members.  A total of 45 responses were received during the
 Public Comment Period. Of the 45 responders, 33 people supported the selection of Alternative
 C. Several community members indicated no preference among the remedial alternatives, and
 several people preferred Alternative E

-------
                          RESPONSIVENESS SUMMARY

V.  RESPONSES TO SURVEY FORM SENT TO ALL TECHNICAL REVIEW COMMITTEE MEMBERS


     A total of five responses were received from Technical Review Committee Members during the
     Public Comment Period. All five responders fully support the proposed action.

-------