PB95-963921
                                 EPA/ROD/R03-95/211
                                 February 1996
EPA  Superfund
       Record of Decision:
       Brodhead Creek Site,
       (O.U. 2) Stroudsburg, PA
       6/30/1995

-------
                        RECORD OP DECISION
                        BRODHEAD  CREEK  SITE
                        OPERABLE UNIT  TWO
                            DECLARATION
Site Name and Location
Brodhead Creek  Site
Stroudsburg,  Pennsylvania
Operable Unit Two

Statement of  Baais and Purpose

This decision document: presents a selected remedy for residual
coal tar contamination and ground water contamination in the
subsurface soils at the Brodhead Creek Site  (the "Site") in
Stroudsburg,  Pennsylvania, which was chosen in accordance with
the requirements of the Comprehensive Environmental Response,
Compensation and Liability Act of 1980 (CERCLA) ,  as amended "by
the Superfund Amendments and Reauthorization Act of 1986 (SARA),
and, to the extent practicable, the National Oil and Hazardous
Substances .Pollution Contingency Plan (NCP), 40 CFR Part 300.
The information supporting this decision is contained in the '
administrative record for this Site.

The Commonwealth of Pennsylvania concurs with the selected
remedy.          ."  •    .

Description of the Remedy

     The'Brodhead Creek Site is the location of a former coal
gasification plant which operated along the west  bank of Brodhead
Creek in the Borough of Stroudsburg, Monroe County,  Pennsylvania,
from approximately 1888 to .1944.  A waste product from these
operation^ was coal tar, a black tar-like liquid which had a
density greater than water and was principally composed of
polynuclear aromatic hydrocarbons ("PAHs").  This coal tar was
placed in an open pit located on the property.   This practice
continued until the mid-1940s when the plant was  abandoned.

       A previous Record of Decision ("ROD")., issued on March 29,
1991,  selected an enhanced recovery process as an interim
remedial action for Operable Unit One ("OU-l")xat the Site which
addressed free coal tar in the subsurface soils at the..Site.   As
part of the OU-1 interim remedial action,  deed restrictions will
be imposed to limit future use of the Site.  The  shallow ground
water and Brodhead Creek will continue to be monitored to verify
that no unacceptable risks posed by conditions at the Site occur
in the future.

    This ROD addresses ground water contamination and residual
coal tar contamination in the subsurface soils (Operable Unit Two
or "OU-2") .  No further action is necessary for Operable Unit
Two.
                                          AR302000

-------
 Statutory Determinations

      The selected remedy  is protective of human health and the
 environment,  complies  with  (or waives) federal and state
 requirements that are  legally applicable or relevant and
 appropriate to the remedial action, and is cost effective.

      Because the interim  remedy for Operable Unit One selected in
 the previous ROD will  result in hazardous substances remaining
 on-site above health based levels, a review will be conducted
 within five years after commencement of the interim remedy   The
 review will be conducted  to ensure that the interim'remedy
 continues to provide adequate protection of human health and the
 environment.   Review of this Site, the interim remedy for
 Operable Unit One and  EPA's decision for Operable Unit Two  will
 be  continuing as part  of  the development of a final remedy'for
 Operable Unit One.
'Thomas  C. VbltaSgio/^  J                         Date
Division Director-
Hazardous Waste Management Division
Region  III
                                           AR30200I

-------
                        RECORD OP DECISION
                       BRODHEAD CREEK SITE


                        TABLE OP CONTENTS

SECTION                                    .                 PAGE

    I.   SITE NAME, LOCATION, AND DESCRIPTION	.1

   II.   SITE HISTORY AND ENFORCEMENT ACTIVITIES	2

 III.   HIGHLIGHTS OF COMMUNITY PARTICIPATION	5

   IV.   SCOPE AND ROLE OF RESPONSE ACTION	6

   V.   SUMMARY OF SITE CHARACTERISTICS	6

  VI.   SUMMARY OF SITE RISKS	.•	14

 VII.   DESCRIPTION OF ALTERNATIVES	18

VIII.   SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES.  .  .  .20

  IX.   SELECTED REMEDY.	  .24

...  X.   STATUTORY DETERMINATIONS.	25

  XI.   EXPLANATION OF SIGNIFICANT CHANGES. .	27

        APPENDIX A:  FIGURES

          Figure 1:      Brodhead Creek Site Location Map

          Figure 2:      Site Plan

          Figure 3:      Maximum Probable Extent of Free  Coal Tar
                         Surface

          Figure 4:      General Site Stratigraphic Column

          Figure 5:      Lateral Extent of Stream Gravel  Unit

          Figure 6:      Top of Silty Sand Unit

          Figure 7:      Schematic of Extent of Free and  Residual
                         Coal Tar

          Figure 8:      Water Supply Well Locations

          Figure 9:      Ground Water Flow Schematic

          Figure 10:     Log of Sum of Total Detected Organics
                                         AR302002

-------
  Figure 11

  Figure 12

  Figure 13

APPENDIX B:

  Table .1:


  Table 2:

  Table 3:

  Table 4:



  Table 5:

  Table 6:



  Table 7:


  Table 8:



  Table 9:
    Site.Plan with  Monitoring Well  Locations

    Flow in Bedrock System

    Regional Fracture  Pattern

TABLES

    Relevant and Appropriate Requirements
    for Ground Water

    Summary of Ground  Water Analyses

    Shallow Aquifer Screening Analysis

    Justification Table  for the Selection of
    Constituents of Potential Concern in the
    Shallow Aquifer

    Deep Aquifer Screening Analysis

    Justification Table  for the Selection of
    Constituents of Potential Concern in the
    Deep Aquifer

    Summary of Toxicity  Data for
    Constituents of Potential Concern

    Intake/Risk  Calculations for
    Hypothetical Residential Use of Shallow
    Ground Water by an Adult

    Intake/Risk  Calculations for
    Hypothetical Residential Use of Shallow
    Ground Water by a  Child (0-6)
APPENDIX C:  RESPONSIVENESS SUMMARY
                                   AR302003

-------
                        RECORD OP DECISION
                       BRODHEAD CREEK SITE
                         DECISION SUMMARY
I.  SITE NAME.  LOCATION.  AND DESCRIPTION

     The Brodhead  Creek  Site  ("the Site") encompasses
approximately  12 acres in the Borough of Stroudsburg in Monroe
County, Pennsylvania  (Figure 1).  The Site lies on the west bank
of Brodhead Creek  between the bridges of Route 209 and Interstate
80.  The detailed  site plan is  shown on Figure 2.

     The Site  occupies the flood plain area at the confluence of
Brodhead Creek and McMichael Creek.  As a result, the natural
topography over most  of  the Site is one of low relief.  Surface
elevations in  the  flood  plain area range from about 377_feet
above mean sea level  at  the Creek banks to 381 feet in the flood
plain interior.  In the  northern one-third of the Site by
contrast, the  land surface rises abruptly from the flood plain to
an elevation of about 400 feet.                               .

     Superimposed  over the natural topography is a large man-made
earthen levee  constructed to protect the Stroudsburg Municipal
Sewage Treatment Plant,  which is located on the western boundary
of the Site, from  flood  waters  such as those experienced in the
aftermath of Hurricane Hazel in 1955 (See Figure 2) .  On the Site
proper, this levee is arcuate in plan, curving from out of the
north and to the west, effectively blocking any potential
flooding from  either  Brodhead Creek or McMichael Creek. The levee
crown  (elevation of 408  feet) is about 25 to 30 feet above the
surrounding flood  plain.   The Creek side of. the levee is sloped
at a ratio of  2.5:1 while the opposite side is sloped at a ratio
of 2:1. •

     To the west,  the levee extends out of the Site area.  To the
north, the levee abuts the natural land surface and a concrete
flood wall which protects a Pennsylvania Power and Light Company
("PP&L") substation.  The concrete flood wall extends from the
levee embankment northward and  is keyed into the west abutment
for the Route  209  bridge.  The  flood wall is a 22-foot tall
reinforced, cast-in-place concrete wall constructed on top of an
interlocking sheet pile  foundation which extends down to
elevation 361  feet.   The  elevation at the top of the "concrete
wall is about  407  feet above mean sea level.

     A smaller, and presumably  older earthen levee, which extends
northward from the main  flood control levee, separates the flood
plain area of  the  Site from the grounds of the Stroudsburg
Municipal Sewage Treatment Plant.  This smaller levee rises about
13 feet above  the  flood  plain with its crown reaching about
elevation 394  feet above  mean sea level.

-------
     Two  small  drainage channels enter the Site, join in the Site
interior,  and continue through the flood plain area.  Flow in the
smaller of the  two  is intermittent in nature, as that channel
carries storm run-off, entering the Site at the northeast corner
via a storm sewer outfall.  The smaller channel is not considered
to be a major Site  feature for this reason.  The larger channel
is perennial in nature and enters the Site from the west-
northwest,  continuing across the central portion of the Site
through a  flood gate in the levee to its outlet on Brodhead
Creek.  It is referred to herein as the urban run-off channel.

     The northern Site boundary is -a combination of private
commercial properties and a cemetery located along Main Street in
Stroudsburg.

     The Borough of Stroudsburg has zoned the Creek, its eastern
and western banks, and the small promontory at the confluence of
Brodhead and McMichael Creeks as open space.   The land from the
top of the flood control levee westward through Main street is
zoned as general commercial land.  Land use at the Brodhead Creek
Site is categorized primarily as undeveloped.  Those areas
containing the  sewage treatment plant and the Stroudsburg Gas
Company are classified as utilities.
II.  SITE HISTORY AND ENFO^CiMKMT ACTIVITIES

     Union Gas Company is a successor company to companies which
operated a coal gasification plant along the west bank of
Brodhead Creek in Stroudsburg, Pennsylvania, from approximately
1838 to 1244.  A waste product from these operations was coal
tar, a black tar- like liquid which had a density greater than
water and was principally composed of polynuclear aromatic
hydrocarbons ("PAHs") .  This coal tar was placed in an open pit
located on the property.  This practice continued until the mid-
19403 when the plant was abandoned.

     In 1917, Pennsylvania Power & Light Company ("PP&L")
purchased the electrical section of the Union Gas Company
facilities.  From 1917 until the 1960's, PP&L acquired adjoining
properties, including some of the property owned by Union Gas
Company.

     On October 7, 1980, during construction repairs to the toe
of a flood control levee at the Site, materials identified as
coal tar were observed seeping into Brodhead Creek.   As a result,
several investigations and emergency response measures were
initiated from 1981 through 1984, including:

     o    Installation of temporary filter fences and underflow
          dams by PADER and EPA to intercept coal tar seepage;
                                            RR30Z005

-------
     o    Installation of a temporary coal tar recovery pit by
          PADER on the bank of Brodhead Creek;

     o    Construction of a slurry wall by EPA to mitigate coal
          tar migration from the Site toward Brodhead Creek;

     o    Excavation of a backwater channel area where coal tar
          seepage appeared to be particularly significant; and

     o    Installation of recovery wells in the main coal tar
          pool by PP&L, with the subsequent recovery of
          approximately 8,000 gallons of coal tar.

     The Site was placed on the National Priorities List  ("NPL")
in December, 1982 with a hazard ranking score ("HRS")  of 31.09.
The regulations enacted pursuant to CERCLA require that a
Remedial Investigation and Feasibility Study ("RI/FS")  and
baseline risk assessment be conducted at each NPL site.  The
purpose of an RI is to characterize conditions at the site.  The
subsequent PS then develops,  screens, and analyzes a series of
remedial alternatives for addressing contamination at the site.
On August 20, 1987,  PP&L and Union Gas Company entered into a
Consent Order and Agreement with PADER to conduct the original
RI/FS for the Brodhead .Creek Site.

     Results of th« Original RI

     The original RI, completed in 1989, indicated the following:

     o    The Site is underlain by the following distinct strata
          (in descending order):   fill,  floodplain deposits,
         . stream gravels,  silty sands, and bedrock.

     o    The principal shallow water-bearing strata at the Site
          are the stream gravel unit and the underlying silty
          sand unit.

     o    Soil contamination due to coal tar-related compounds is
          limited both horizontally and vertically, to the stream
          gravel unit.

     o    The total area of contamination is approximately 4.28
          acres containing an estimated maximum volume of 418,000
          gallons of coal tar.

     o    The likely extent of free coal tar accumulations is
          limited to a small area of a stratigraphic depression
          east of the slurry wall (the area around MW-2)  and to
          the lowest portion of the stratigraphic depression
          located west of the slurry wall (the RCC area).  (See
          Figure 3.)  These two areas contain an estimated volume
          of 338 gallons and 8715 gallons of free coal tar,
                                            AR302006

-------
           respectively.   Free coal tar is defined as 100% of pore
           volume  saturation  in  the soil.  Coal tar at residual
           saturation levels  is  more extensive but limited to the
           extent  of  the  stream  gravel unit.  Residual coal tar is
           defined as less  than  100% of pore volume saturation in
           the  soil.

     o     Ground  water flow  from the upgradient side of the
           slurry  wall is both downward beneath the slurry wall
           and  southward  to Brodhead Creek.

     o     Migration  of coal  tar constituents as dissolved
           constituents in  ground water may be constrained by
           upward  flow gradients and by the hydraulic boundaries
           represented by Brodhead Creek and McMichael Creek.

     o     RI data suggest  that  surface waters of Brodhead Creek
           are  not affected by the discharge of coal tar
           constituents. However, some sediment areas within the
           Creek channel are  slightly contaminated with coal tar.

     o     There are  currently no significant risks associated
           with the recreational use of Brodhead Creek or the
           ingestion  of fish  from the Creek.

     Following completion  of the original RI/FS in 1991, EPA
divided the remedial work  to be undertaken, at the Site into two
manageable components called "operable units (OUs)".  These were
as follows:           -

     OU-1:     Contaminated subsurface soils containing free  coal
               tar in the  stream gravel unit

     OU-2.:     Ground water  in  the stream gravel unit to and
               including bedrock
                                           ^
    . EPA determined  that an interim remedial action should be
taken for OU-1 to initiate reduction of the toxicity,  mobility,
and volume of  contaminants in the stream gravel unit at the Site.
In a Record of Decision issued on March 29, 1991,  EPA selected an
interim remedial  action which included the following components:

(1)  Installation of extraction wells and injection wells in  the
     free  coal tar areas of the subsurface soils;
(2)  Recovery of coal tar and process water from the extraction
     wells by using the innovative technology of enhanced
     recovery;

(3)  Separation of the coal tar from the process water followed
     by treatment of the process water;
                                            AR302007

-------
 (4)   Discharge  of  a  portion of  the  treated process water to
      Brodhead Creek  and  the reinjection of the remaining process
      water  into the  subsurface  soils  to enhance coal tar
      recovery;

 (5)   Disposal of the recovered  coal tar at an off-site permitted
      incineration  facility;

 (6)   Installation  of a fence to prevent public access during
      remedial activities;

 (7)   Imposition of deed  restrictions  to limit future use of the
      Site;  and

 (8)   Monitoring of ground water and biota in Brodhead Creek to
      ensure protection to human health and the environment.

      EPA entered' into a  Consent Decree with PP&L and Union Gas
Company on  September 2,  1992, under which PP&L and Union Gas
Company agreed  to  implement the remedial design/remedial action
 ("RD/RA") for OU-1 at the Site.  On July 14, 1994, an Explanation
of Significant  Differences ("BSD") was issued by EPA to revise
the performance standards for the interim selected remedy for OU-
1.  The enhanced recovery process (referred to as the Contained
Recovery of Oily Waste Process, or  "CROW" process) has been
constructed and is expected to  become operational in the summer
of 1995.

      On June 3, 1992, PP&L and  Union Gas Company entered into a
Consent Order with EPA to conduct a Focused RI/FS for OU-2 to
further investigate  ground water contamination at the Site.  This
Record of Decision discusses the results of the Focused RL/FS.

III.  HIGHLIGHTS OP  COMMUNITY PARTICIPATION

      The Focused RI/FS and the  Proposed Remedial Action Plan
 ("Proposed  Plan")  for OU-^2 were released for public comment on
May 25, 1995, in. accordance with Sections 113(k)(2) (B),  117(a),
and 121  (f) (1) (G)  of CERCLA.  These and other related documents
were  made available  to the public in the administrative record
file  located in the  EPA  Region  III office in Philadelphia and at
the Stroudsburg Borough  Building in Stroudsburg,  Pennsylvania.  A
notice of their availability was published in the Pocono Record
on May 25,  1995.   A  public meeting to discuss the Proposed Plan
for OU-2 was held  on June 6,  1995 in  Stroudsburg, Pennsylvania.
EPA's response  to  all comments  on the Proposed Plan received
during the  comment period is included in the Responsiveness
Summary section of this  ROD.  In addition,  a copy of the
transcript of the  public meeting has been placed in the
administrative  record file and  information repository located at
the Stroudsburg Borough  Building.
                                          AR302008

-------
 IV.  SCOPE AND ROLE O7 RESPONSE ACTION

      As discussed above,  Che interim remedial  action previously
 selected for Operable Unit Qne (enhanced recovery)  addresses  the
 areas of free coal tar contamination in the subsurface  soils  on-
 site.  A final ROD for the Site addressing free  coal tar
 contamination will be issued following completion of the OU-1
..enhanced recovery program.

      Once the enhanced recovery program is completed, there
 should be no principal threats from the former areas of  coal  tar
 accumulation at the Site  since they should contain only  residual
 levels of coal tar contamination.   However,  contaminants are
 leaching and will continue to leach from the -subsurface  soils
 containing residual coal  tar at the Site.   These contaminants
 will continue to contribute to ground water contamination on-
 site.                                       .            '

      This second operable unit addresses ground  water
 contamination and residual coal tar contamination in the
 subsurface soils on-site.

 V.   SUMMARY OF 3ITS CHARACTERISTICS

      A.   Waste Characterisation

      The coal tar disposed of in the subsurface  soils at the
 Brodhead Creek Site was the waste  product  of a coal  gasification
 plant which operated at the Site between 1888  and 1944.   No
 factual  accounts of actual operations at the plant exist nor  is
 there any certainty of the actual  process  or processes used to
 manufacture the gas.  However,  the tars generated by gas
 manufacturing plants have several  general  characteristics
 including:  (1)  a density slightly greater than  water; and (2) a
 composition lacking tar acids (primarily phenolics)  but
 containing large amounts  of high molecular weight residual
 material with 40-75% of the tars boiling above 300°C.

      The chemical constituents of  coal tars are  primarily
 polynuclear aromatic hydrocarbons  (PAHs),  including  heterocyclic
 compounds.  Coal tars typically consist of the following:

                     Distillation
 Compos it ion           Range	            Typical-Composition
 Light Oil           Up to 200°C             Monocyclic  Aromatics

 Middle Oil          200-250°C               Substituted
                                             monocyclic  and
                                             dicyclic aromatics

 Heavy Oil           250-300°C               Substituted dicyclic
                                             aromatics
                                      AR302009

-------
Anthracene Oil    .   300-350°C                Substituted dicyclic
                                             aromatics; tri- and
                                             polycyclic aromatics

Pitch                                        Carbon, wax, bottoms

     During the RI at the Site, a sample of coal tar from well
RCC-C was collected  and submitted for percent water and
fractional distillation testing.  The distillation data and
specific gravity  (which approached that of water)  indicate that
the coal tar at the  Brodhead Creek Site consists of approximately
50% light and middle oil components.

     Metals analysis of the coal tar revealed slightly elevated
arsenic concentrations in the tar.  The remaining metals values
were below average concentrations observed in the natural soil
environment occupied by the coal tar.

     Coal tar is not 'a Resource Conservation and Recovery Act,  as
amended, ("RCRA") listed waste.  However, subsequent testing of
the coal tar utilizing the toxicity characteristic leaching
procedure ("TCLP") during the remedial desi'gn phase of the OU-1
interim remedy revealed that the coal tar is a RCRA
characteristic waste for toxicity.

     B.  Regional Geology

     The Brodhead Creek Site is located within the Valley and
Ridge physiographic  province of the Appalachian Mountains.
Bedrock at the Site  is the Devonian Age Marcellus Shale which is
described as a dark,, fissile,  carbonaceous shale,  with some
notably calcerous zones.   Directly underlying the Marcellus Shale
in the vicinity of the Brodhead Creek Site is. the Devonian Age
Buttermilk Falls Formation,  which is a viable water supply.   This
formation supplies water for the. City of East Stroudsburg
municipal wells #1 and #2.

     The wide valley through -which Brodhead Creek flows has been
filled by up to 100  feet of unconsolidated glacial deposits.  The
Brodhead Creek Site  is underlain by at least 60 feet of
unconsolidated sediments of both glacial, recent fluvial,  and
human origin.   The geology at  the Site can be divided into the
following distinct strata (in descending order):  surficial fill,
floodplain deposits, stream gravels,  silty sands,  glacial till,
and bedrock (See Figure 4).

     The surficial fill is comprised of earthen fill material
which was deposited  for land reclamation and levee construction
as well as stream bed modifications.   Fine sands and silts
deposited during flood events  of Brodhead and McMichael Creeks
comprise the flood plain deposits.  Fluvial origin stream gravels
underlie the flood plain/fill  deposits beneath much of the Site,
                                            AR3020IO

-------
and  are  Che  surficial  materials in some areas of the Site.  The
lithology  of the  stream gravels can be characterized as loosely
consolidated,  stratified, well rounded, coarse gravels.  These
gravels  are  most  likely reworked glacial drift transported and
deposited  by the  streams as they migrated across the valley floor
during the past;  therefore, this gravel deposit correlates with
the  streambed gravels  in the Brodhead Creek channel .

     Historic site borings and test pit observations indicate
that the stream gravel deposits are limited in horizontal extent,
pinching out in the west -central and southern portion of the
study area (See Figure 5) .  The stream gravel thickness averages
about 10 to  15 feet, but ranges from absent in some parts of the
study area to a maximum, of over 25 feet in a stratigraphic
depression near the center of the Site.  Figure 6 shows a contour
map of the base of the stream gravels (or the top of the
underlying silty  sands) which shows this stratigraphic
depression.   The  shape and location of the stratigraphic
depression suggest that it may have been coincident with a
confluence of  the ancestral Brodhead Creek and another ancestral
drainage.  -However, it is postulated that the depression is a
kettle feature created by the melting of a large block of glacial
ice embedded in the silty sand.

     The thickness of the stream gravel unit beneath and
immediately  east  of Brodhead Creek is well defined.  However,  the
extent of  the  stream gravel east of the eastern levee is not
known.  Because the stream gravel is a channel deposit, it is not
expected to  be extensive.  The unit is thin in this area,  ranging
between approximately 10 feet thick on the north near the
Interborough Bridge to approximately 16 feet thick across from
the island located in Brodhead Creek.   Borings and backhoe pits
on the island  indicated a significant thinning of the gravel unit
beneath Brodhead  Creek due to downcutting by erosion and/or
dredging.  Under  the island, the unit thins to 4 to 6 feet thick.
Since the  stream  bed itself is at a lower elevation than the
island surface, the unit is even thinner under the stream,  and
may possibly be absent in some areas.

     A deposit of stratified fine sands and silts,  with some
clayey and gravelly lenses underlies the stream gravels at the
Site.  These sediments have been described as fairly uniform
silty sands  with  virtually no clay fraction present.   Underlying
the deposits  is a glacial till deposit.
     C.  MachanJi^f *pft Extent of Coal Tar Migration

     The coal tar at the Brodhead Creek Site has a density
slightly greater than water.  Once coal tar was introduced into
the subsurface at the Site, the density differential caused the
coal' tar to sink downward through both the unsaturated and
                                          AR3020II

-------
saturated  sections  of  the stream gravel unit to the interface
with  the silty  sand unit.

      The coal tar movement downward into the finer grained silty
sand  is prevented by the higher capillary pressures within the
much  smaller diameter  pores of that unit.  From the source area,
continued  migration has been lateral downgradient along the
•sloping surfaces of the silty sand unit to lower points where it
accumulated if  sufficient coal tar volume was present.  This
process accounts for the historic .accumulation -of recoverable
volumes of coal tar within the stratigraphic depression in the
silty sand unit located directly downgradient of the former
gasification plant  facilities.  Recovering the free coal tar is
the focus  of the interim remedy for OU-1.

      Figure 3 depicts  the spatial area defined as. the extent of
the subsurface  coal tar presence, based on all available
information.  The area defined as the extent of the coal tar
presence encompasses all historical subsurface coal tar
observations, but it cannot be inferred that the entire area is
contaminated by a continuous _ layer of mobile coal tar.  It is the
area  where coal tar may have migrated through coarser grained
material in the stream gravel unit in the past and where coal tar
may remain at residual saturation levels.  The region of the Site
outside of the area defining the extent of coal tar presence
appears to be unaffected by coal tar; the coal tar does not
appear to  have migrated into these areas in the past .No coal
tar was found to be present east of Brodhead Creek.  This is
consistent with the configuration of the surface of the silty
sand  unit .                .       •     •

      The extent of  subsurface stream gravels affected by coal tar
at residual saturation levels (coal tar at less than 100% pore
volume saturation) , is  estimated to be 128,702 square feet (2.96
acres), and the volume is estimated at 27,558 cubic yards.   The
total volume of residual coal tar at the Site is estimated to
range from 303,000  gallons to 409,348 gallons.   Figure 7 presents
a 3 -dimensional representation of the extent of the coal tar
contamination.                      .

     D .
         Ground Water Clarification and Local Water U««

     It is EPA' s Superfund policy to use EPA' s Ground Water
Protection Strategy and Ground Water Classification Guidelines  to
assist in determining the appropriate type of remediation for a
Superfund Site.  Three classes of ground water have been
established on the basis of the value of ground water and its
vulnerability to contamination.  Ground water at the Brodhead
Creek Site may be classified as Class II.  Class II ground water
                                           AR3020I2

-------
 is ground  water which is  a  current or potential source of
 drinking water or a  water that has other beneficial uses.

     The urban areas of Stroudsburg and East Stroudsburg are
 supplied by surface  and ground water.  Stroudsburg Borough is
 served by  a public water  supply owned by the Stroudsburg
 Municipal  Authority.   The Municipal Authority obtains its water
 supply from Brodhead Creek  (upstream of the Site).   The water is
 pumped directly to the Municipal Authority Plant.

     The Borough of  East  Stroudsburg receives its water via a
 gravity. feed from two impoundment reservoirs in Smithfield
 Township,  and from three  wells located in the City of East
 Stroudsburg.   Two of the  wells are on the campus of East
 Stroudsburg University (indicated as "State Teacher's College" on
 Figure 8)  while the  third is a well screened at the top of
 bedrock and located  over  2,000 feet upstream of the Site, on the
 opposite side of Brodhead Creek in Dansbury Park.   These three
 wells are  used on an intermittent basis only.  One  of the wells
 on the campus is only for emergency use (i.e.,  fire protection),
 and the second well  was not used in 1994 except to  exercise the
pump.  The well in Dansbury Park is used on-an as-needed basis to
 supplement the surface water supplies.  The location of the water
 supply wells  is presented in Figure 8.

     The Dansbury Park Well was examined closely during the
original RI.   The original RI concluded that migration,of coal-
tar constituents from the Site to the well was not  possible for
several reasons:   (1)  the well pumps water from a lower gravel
unit and the  upper portions of a limestone bedrock  over 11,0 feet
below the  surface; (2) the lower gravel unit is not the same unit
as the stream gravel  unit of concern at the Site (the lower
gravel unit  is confined by less permeable overlying silts and
 clays)  and it is not  subject to contamination by the Site;  and
 (3)  significant hydraulic boundaries (Brodhead and  Little Sambo
Creeks) lie between  the Site and the well.   Furthermore,  a review
of the sampling data  from the Dansbury Park well and the other
 two East Stroudsburg  municipal supply wells did not reveal the
presence of any coal  tar-related compounds.

                       Shallow Ground Water

     The principal shallow water bearing strata at  the Site are
 the stream gravel unit and the underlying silty sand unit.
Together,  they comprise a water table aquifer.   While the two
stratigraphic units  of the water table aquifer differ with
respect to hydraulic  characteristics,  they may be considered to
be a single aquifer with  regard to ground water flow direction
and gradient  as they  are  not separated by any intervening
confining  layers.
                                10
                                                RR3020I3

-------
     The median depth  to ground water at the Site was 10 feet
prior to the  construction of the slurry wall.  Construction of
the slurry wall at the Site as a response measure to prevent coal
tar migration has resulted in a significant alteration of the
water table flow regimes.  At present, the water table is nearly
coincident with the ground surface in the flood plain areas
upgradient of the slurry wall, and 3 to 7 feet below surface
downgradient  of the slurry wall.  A ground water head loss of 2
to 3 feet across the slurry wall is present.  To a -lesser extent,
the sheet pile base of the concrete flood wall extends the head
loss effect of the slurry wall northward from the slurry wall to
at least the  Route 209 bridge abutment.

     Hydraulic head levels appear to indicate:  (1) that an
upward flow component exists between the water table and the
underlying strata; (2) that the urban run-off channel likely
recharges the ground water system; (3) that Brodhead Creek and
McMichael Creek are hydraulic boundaries; and (4)  along Brodhead
Creek the majority of this boundary is characterized by ground
water discharge conditions.

     Ground water flow from the upgradient side of the slurry
wall is both  downward beneath the slurry wall/flood wall and
southward to  Brodhead Creek south of the urban run-off channel
outlet.   .This ground water flow does carry some dissolved coal
tar constituents from the upgradient side of the slurry wall to
the downgradient side, with subsequent discharge to Brodhead
Creek.  North of the urban run-off channel outlet,  the ground
water system  on the downgradient side of the slurry wall
discharges to Brodhead Creek in the northern most portion of the
Site,  is recharged by Brodhead Creek in the middle portion,  and
discharges to Brodhead Creek in the southern portion.   South of
the urban run-off channel outlet to the confluence with McMichael
Creek, the ground water system discharges to Brodhead Creek.

     The recharge/discharge conditions along Brodhead Creek are
altered when  the Creek rises at times of high precipitation.   RI
data indicates that at these times, the ground water system is
recharged along the entire length of Brodhead Creek.

     Figure 9 is a 3-dimensional cross-section across the
southern third of the Site that depicts the conceptual ground
water, flow paths resulting from all of the influences discussed
above.

     The shallow aquifer was extensively studied during the
original RI/FS and is being monitored as part of the interim
remedial action for OU-1..  No additional data for the shallow
aquifer was obtained during the OU-2 RI.   The data from the
original RI,   the OU-1 monitoring program,  and the OU-1 interim
remedial action were  evaluated in order to establish the most
                                11
                                             &R3020U

-------
 appropriate  data set for  the  OU-2  risk  assessment for the shallow
 aquifer.

      The  principal  contaminants of  concern in the ground water in
 the  shallow  aquifer are polynuclear aromatic hydrocarbons
 ("PAHs"),  benzene,  and arsenic.  The  concentrations of
 contaminants detected in  the  shallow  aquifer during the original
 RI may be  found in  Table  1.   Federal  Maximum Contaminant Levels
 ("MCLs")  for drinking water are exceeded for benzene, a range of
 PAHs, pentachlorophenol,  cyanide and  arsenic.  These MCLs are
 codified  at  40  C.F.R.  Part 141 pursuant to the Safe Drinking
 Water Act, 42 U.S.C.  § 300f et seqi.  and are indicated on Table
 1.

      The highest concentrations of  organic coal tar-related
 constituents dissolved in ground water are centered around the
 areas of known  coal  tar presence near MW-2 and RCC (See Figure
 10}.  Vertical  distribution of dissolved-phase contamination is
 limited to the  shallow aquifer and  possibly to the uppermost
portions of  the silty sand unit.

                        D««p  Ground Water

      The purpose of  the Focused RI  for OU-2 was to further
characterize the ground water contamination at the Site--in
particular,  the quality of the bedrock aquifer at the Site.
The investigation of  the  bedrock aquifer included the
installation of three  bedrock wells at the Site,  measurement of
ground water elevations of the shallow, intermediate,  and bedrock
wells, and ground water sampling and  analysis of the bedrock
wells.

      The installation  of  the  three bedrock wells (designated as
BR-1, BR-2,  and BR-3)  at  the  Brodhead Creek Site was completed in
May of 1993.  The purpose of  the bedrock wells was to determine
if the ground water  in the bedrock aquifer was being impacted by
the contamination at the  Site.  To the extent possible,  the
bedrock wells were to  be  located outside the shallow coal tar
accumulation, so as  to minimize the risk of cross-contaminating
the deeper aquifer.   In addition,  bedrock wells were to be  -
located'adjacent to  existing  shallow  wells, when possible.   The
location of  the bedrock wells is presented in Figure 11.

      Based on water  level measurements, the bedrock system flow
is southward (See Figure  12).   On initial evaluation,  this is not
an expected  condition, as flow would  be expected northeastward
either to discharge  locally at Brodhead Creek,  or deeper along
the bedrock  structural trend  of the valley towards the Delaware
River.  However,  a closer look at Regional structure explains
this  flow, as described below.
                                12

-------
     The  topographic  quadrangle of  the area shows a regional
fracture  set oriented north-northwest/south-southeast
perpendicular  to  regional  bedrock orientation.  The regional
fracture  pattern  is shown  in  Figure  13.  Along the course of
Brodhead  Creek north  of  Stroudsburg, one large fracture cuts
across the  regional structural trend,'forming water gaps north of
Stroudsburg.   South of the Site, Brodhead Creek follows an
apparent  fracture orientation, and  then turns 90 degrees toward
the east  at the contact  with  the resistant bedrock ridge to the
south.  However,  the  fracture appears to continue even across the
bedrock ridge  to  the  south.

     Given  the above  structural conditions, it appears likely
that bedrock flow from the Site follows the fracture south-
southeastward, flowing beneath and parallel to Brodhead Creek.
Discharge is likely to Brodhead Creek at or near contact with the
ridge.  The apparent  southerly flow direction beneath the Site is
probably  a  function of triangulation of the potentiometrie
surface of  the three  wells.  Flow is-actually either south-
southeastward  along the  fracture, or southeastward into the
fracture, if the  Site does not lie directly on the fracture.

     Two rounds of ground  water sampling were conducted of the
bedrock wells  BR-1, BR-2,  BR-3, and a residential well (herein-
after referred to as  the "CS" well)  during the weeks of June 1,
1993 and December 9,..  1993,  respectively.  A third round of. ground
water sampling of the bedrock wells only was conducted on May 8
and 9, 1995.   The CS  well  is a domestic well located in
Smithfield Township,  approximately 1-1/2 miles east of'the
Brodhead .Creek Site.   Based on a well survey conducted during the
original RI, the  CS well is the closest residential well to the
Site that remains in  use.   For this reason, the CS well was
selected as a  monitoring point for the Brodhead Creek Site.

     Ground water was sampled for volatile organic compounds
("VOCs"), semivolatile organic compounds ("SVOCs"),  dissolved
metals (on the first  round of sampling only),  and cyanide.   With
the exception  of  trichloroethene ("TCE")  at well BR-3 and 1,1-
dichloroethane at the CS well, no VOCs were detected at greater
than 1 ug/1.   TCE and 1,1-dichloroethane are not constituents of
coal tar, and  were not detected in any ground water samples taken
during the original RI.

     Trace levels of  xylene and 1,2,4-trimethylbenzene were
detected in BR-1  and  BR-3, but not in BR-2 or the CS well.
Naphthalene was detected at trace levels in BR-1,  BR-2,  and BR-3.
Trace levels of toluene were detected in BR-1 and BR-2.   In
addition, arsenic and cyanide, two Brodhead Creek Site
contaminants,   were absent  from all samples collected during the
first round of sampling.    Detected concentrations of contaminants
for the bedrock wells are  summarized -in Table 2.
                                13

                                             AR3020I6

-------
VI.   SUMMARY OF SITE RISKS

      As part of the  Focused Remedial Investigation performed for
OU-2  at the  Brodhead Creek Site, a Risk Assessment ("RA") was
conducted  to evaluate the potential impacts of the Site on human
health and the  environment.  In the RA, chemicals of potential
concern were identified for detailed evaluation based on the OU-2
and OU-1 sampling  results.  The Risk Assessment then evaluated
the potential health and environmental risks associated with
exposure to  these  chemicals.

      The risk assessment for OU-2 at the Brodhead Creek Site
focused on the  potential human health risks associated with
ground water in both the shallow and deep aquifers underlying the
Site.  The potential for ground water discharges to Brodhead
Creek and  other surface water bodies was addressed during the
original risk assessment and therefore was not re-evaluated.
(See  the Brodhead  Creek Risk Assessment dated September 1990.)
Likewise,  potential  impacts to ecological receptors were
extensively  evaluated during the original risk assessment and
were  not re-evaluated.  The risks associated with ingesting
ground water bn-site are summarized below. ,

      A.  Indicator Chemical Selection

      The contaminants identified .in the Brodhead Creek Site RI
are comprised of a diverse group of compounds with different
physical,  chemical,  environmental,  and toxicological properties.
The extent of contamination varied widely in concentration and
occurrence throughout the Brodhead Creek Site.  The first step
involved in  selecting indicator chemicals involved a comparison
of reported  constituent concentrations from upgradient sampling
locations.   Constituents which did not exceed background
concentrations  were  not evaluated further. .

      For those  constituents detected at concentrations greater
than  background concentrations, a comparison was made between the
maximum downgradient  concentrations and risk based screening
levels developed by  U.S. EPA Region III.   This comparison was
made  to evaluate the  potential for adverse human health effects
resulting  from  the hypothetical use of ground water.

      Based on a review of the data from'the original and the
focused RIs, a  set of chemicals of potential concern were
selected for detailed evaluation in the risk assessment.   The
results of the  screening analysis for the shallow aquifer is
presented  in Table 3.  Table 4 provides a justification for the
selection  or rejection of individual constituents from the risk
assessment for  the shallow ground water.   The results of the deep
aquifer screening  is  presented in Table 5.  Table 6 provides a
justification for  the elimination of individual constituents from
the risk assessment  for the deep aquifer.  No constituents of

                                14
                                           AR3020I7

-------
potential concern  were  identified in the deep aquifer.
Therefore, a  quantitative risk assessment was not performed to
evaluate potential exposures to ground water in the deep aquifer.

     B.  Exposure  Pathways

     This step  in  the risk assessment process involves.
determining the potential routes of exposure to the human
population, the estimated concentrations to which the population
is exposed, and the.population at risk.  Currently,  there are no
users of the  ground water on-site.  The risk assessment for OU-2
evaluated the potential risks associated with the hypothetical
future use of on-site ground water as a residential water supply.
The RA considered  on-site ground water use by both adults and •
young children  and evaluated all three potential routes of
exposure associated with the residential use of ground water
(i.e., ingestion,  dermal contact during bathing, and inhalation  .
of VOCs during  showering).

     C.  Toxicity  Assessment

     Cancer potency factors ("CPFs")  have been developed by'EPA
for estimating  excess lifetime cancer risks associated with
exposure to potentially carcinogenic chemicals.  CPFs, which are
expressed in  units  of (mg/kg-day) "1,  are  multiplied  by the
estimated intake of a potential carcinogen,  in mg/kg-day,  to
provide an upper-bound estimate of the excess lifetime cancer
risk associated with exposure at that intake level.   The term
"upper bound" reflects the conservative estimate of the risks
calculated from the CPF.  Use of this approach makes
underestimation of  the actual cancer risk highly unlikely.
Cancer potency  factors are derived from the results of human
epidemiological studies or chronic animal bioassay to which
animal-to-human extrapolation and uncertainty factors have  been
applied.

     Reference  doses ("RfDs")  have been developed by EPA for
indicating the  potential for adverse health effects from exposure
to chemicals  exhibiting noncarcinogenic effects.  RfDs are
exposure levels for humans,  including sensitive individuals,  that
are likely .to be without.an appreciable risk of adverse health
effects.  Estimated intakes  of chemicals from environmental
media (e.g.,   the amount of  a chemical ingested from contaminated
drinking water) can be compared to the RfD.   RfDs are derived
from human epidemiological  studies or animal studies to which
uncertainty factors have been applied (e.g.,  to account for the
use of animal data  to predict effects on humans).   These
uncertainty factors help ensure that the RfDs will not
underestimate the potential for adverse noncarcinogenic effects.

     Potential  concern for noncarcinogenic effects of a single
contaminant in  a single medium is  expressed as the hazard
                                15
                                         AR3020I8

-------
quotient  (HQ)  (or the  ratio  of  the estimated intake to the
reference dose) .   By adding  the HQs for all contaminants within a
medium  or across  all media to.which a given population may
reasonably be  exposed,  the Hazard Index  ("HI") can be generated.
The HI  provides a useful  reference point  for gauging the
potential significance  of multiple contaminant exposures within a
single  medium  or  across media.

     Excess  lifetime cancer  risks are determined by multiplying
the intake level  with  the cancer potency  factor.  These risks are
probabilities  that are  generally expressed in scientific notation
(e.g.,  IxlO"6 or  1E-6).  An excess lifetime cancer risk of IxlO'6
indicates that, as a plausible upper bound, an individual has a
one in  one million chaihce of developing cancer as a result of
site-related exposure to a carcinogen over a 70-year lifetime
under the specific exposure  conditions at a site.

     A  summary of the toxicological indices for the indicator
chemicals selected for  the Brodhead Creek Site are presented in
Table 7.

     D.  Riak  Characterization              .

     The potential carcinogenic risks associated with the
Brodhead Creek Site  were calculated by multiplying the calculated
intakes by the appropriate carcinogenic potency factors.
Concurrent exposures to more than one carcinogen or to one
chemical .through  multiple exposure routes were evaluated by
adding  the individual risk estimates.   Potential carcinogenic
risks are identified by the  risk level (i.e.,  a 1.0 x 10"6 risk
level indicates one  additional chance in 1,000,000 that an
.individual will develop cancer).  EPA's acceptable risk range for
Superfund cleanups is between 1.0 x 10"4  to 1.0  x 10"6.  If the
risk exceeds 1.0  x 10"4, EPA will  generally take action to reduce
the risk to  within the  acceptable risk range.

     The potential risks associated with exposure to
noncarcinogens were  estimated by the calculation of the Hazard
Index.   An HI is equal to the estimated intake for a specific
chemical divided  by  the appropriate RfD.   Hi's may be summed for
each constituent  and exposure route to which a receptor may be
simultaneously exposed  in order to evaluate exposure to multiple
chemicals or exposure via multiple routes.  The HI identifies the
potential for  the most  sensitive individuals to be adversely
affected by  non-carcinogenic chemicals that damage human organs.
If the HI exceeds one  (1.0), there may be concern for potential
systematic effects.  As a rule,  the greater the value of the HI
above 1.0, the greater  the level of concern.

     The Risk Assessment used a statistical analysis concept
called Reasonable Maximum Exposure ("RME") to predict the highest
expected concentrations that a receptor might be exposed to,  for

                                16
                                           AR3020I9

-------
use  in  Che  Risk  Assessment.  The  risk assessment estimates the
reasonable  maximum  exposure  for possible receptors.  This concept
produces a  very  conservative and  protective estimate of risk.

The  risk calculations  for both carcinogens and noncarcinogens are
presented in Tables 8  and 9, and  are summarized as follows:

      (1)  The estimated carcinogenic risks associated with the
          hypothetical residential use of shallow ground water by
          an adult  and a child are 2.49 x 10*2 and 9.57  x  10~3,
          respectively.

      (2)  The hazard indices calculated for the. hypothetical
          residential use of shallow ground water by an adult
          and a  child are 114 and 311, respectively.

     E.  Uncertainty in Exposure Assessment

     It should be re-emphasized that, under current use
conditions, there are no users of ground water from either the
shallow or  deep  aquifers in the immediate vicinity of the
Brodhead Creek Site.  The Borough of East Stroudsburg does
receive water from  two wells located on the campus of East
Stroudsburg University, and a.third shallow gravel well located
2,000 feet  from  the  Brodhead Creek Site,  in Dansbury Park.
However, the original RI concluded that the migration of coal
tar-related constituents in ground water beyond Brodhead Creek to
any nearby wells east of the Site is not possible under the
hydraulic conditions at the Site.  The water supply well located
in Dansbury Park is  separated from the Site by Brodhead Creek and
draws its yield  from a separate deeper gravel unit.  A review of
the sampling data from the Dansbury Park well and the other two
East Stroudsburg municipal supply wells did not reveal the
presence of any coal tar-related compounds.

     Although hypothetical future use of on-site ground water
would result in an unacceptable risk, such a scenario is
extremely unlikely for several reasons.   Several site-specific
constraints limit the practicality .of using the ground water at
the Site as a drinking water source.   These include the flood
control levee and wetlands located on-site.   In addition,  the
gravel unit is too limited in extent to serve as a viable  long-
term-ground water supply at the Site.  Brodhead Creek serves as a
hydraulic boundary for shallow ground water contamination; it is
not possible for ground water in the shallow aquifer to migrate
east of Brodhead Creek.  Furthermore, the Focused RI  reaffirmed
that upward flow gradients exist at the Site.  Therefore,  there
is little probability that the bedrock aquifer underneath  the
Site will be impacted.

     Finally, any use of ground water from the shallow aquifer is
very unlikely in light of a municipal ordinance in the Borough of

                                17


                                          AR302020

-------
Ease  Stroudsburg which requires mandatory connection to the
municipal  water distribution system  (East Stroudsburg Code §154-
4).   EPA understands  that  the Borough of Stroudsburg is presently
in the  process  of developing a similar ordinance.  in addition,
deed  restrictions will be  imposed to limit future use of the Site
as part of the  OU-1  interim remedial action.

VII.  DESCRIPTION OP  ALTERNATIVES

      The Superfund statute and regulations (NCP) require that the
alternative chosen to clean up a hazardous waste site meet
several criteria.  The alternative must protect human health and
the environment,  be cost effective,  .and meet the requirements of
environmental regulations.  Permanent solutions to contamination
problems should be developed wherever possible.  The solutions
should  reduce the volume, toxlcity,  or mobility of the
contaminants.   Emphasis is also placed on treating the wastes at
the site,  whenever this is possible, and on applying innovative
technologies to clean up the contaminants.

      The Focused FS studied a variety of technologies to see if
they  met these  criteria and were applicable for addressing the
contamination at  the  Site.  The technologies determined to be
most  applicable to these materials were developed into remedial
alternatives.   These  alternatives are presented and discussed
below.   Many other technologies were screened out.  This process
is fully detailed in  the original FS dated January 1991 and the
Focused FS for  Operable Unit Two.

      All costs  and implementation timeframes specified below are
estimates  based on best available information.  Present worth is
the total  cost  of  the remedy including capital costs and 30 years
of operation and maintenance of the remedial action,  in current
dollars.

      Regardless of the alternative chosen, EPA will review the
Site  every five years to ensure the continued protection of human
health  and the  environment, as required by the ROD for OU-1.

     Alternative 1:   No Further Action

           Time  to  Implement:             0 month*
           Capital  Cost:                 $0
           Annual  Ground Water O&M:      $0
           Annual  Site Maintenance:      $0
           Present  Worth:                $0

      Under this alternative, no further action, beyond the OU-1
activities, would be  taken to reduce the amount of residual coal
tar in  the subsurface soils or to remediate ground water.   The
ROD for OU-1 addressed free coal tar contamination at the Site.
The enhanced recovery system to remove the free coal tar has been

                                18
                                          AR30202I

-------
constructed and  should become operational in the summer of 1995.
Deed restrictions to limit future use of the Site will be imposed
as part of the OU-l interim remedial action.  The OU-1 ground
water and Creek  monitoring will continue.

          Alternative 2:  In-Situ Stabilization/Solidification

          Time to Implement:                  21 months
          Capital Coat:                     $11,830,000
          Annual Ground Water O&M:              $35,000
          Annual Site Maintenance:              $25,575
          Present Worth:                    $13,066,100

     This alternative would include the in-place mixing of
stabilizing agents into the contaminated soils,  thereby fixating
the contaminants in an inert matrix and reducing their ability to
leach into the ground water.  A mathematical model was used to
determine the extent of the coal tar-contaminated soil that would
need to be treated in order to achieve cleanup criteria that
would be protective of ground water.  The results of this model
revealed that all areas contaminated with residual coal tar would
need to be remediated.  The maximum extent of this area is
depicted in Figure 3 and Figure 7.  These areas include the soils
beneath Brodhead Creek, the fill/highlands,  the wetlands and the
flood control levee pn-sitei  A treatability study and pilot
study t.o select the most appropriate stabilizing reagents for the
soils and to determine the leachability of coal tar-related
constituents from the stabilized/solidified soils would be
required.

     Alternative 3:  In-Situ Bioremediation

          Time to Implement:                  26 months
          Capital Cost:                      $3,515,000
          Annual Bioremediation O&Ms           $241,000
          Annual Ground Water O&M:              $35,000
          Annual Site Maintenance:              $25,575
          Present Worth:                     $6,617,100

    . In-situ bioremediation involves enhancing the natural
microbial degradation of contaminants in the subsurface soils and
ground water without excavation of the overlying soil.   This
technology usually involves adding nutrients,  oxygen,  and in some
cases microorganisms to stimulate biodegradation of the
contaminants.  A treatability study would be necessary to
determine the rate and extent of biodegradation achievable and
the oxygen and nutrient addition requirements of the
biodegradation process.  In addition, a pilot study would be
necessary to confirm the results of the treatability study and to
determine if the hydrogeplogic conditions at the Site (e.g.  well
spacings, iron fouling problems)  are amenable to in-situ
bioremediation.  As in Alternative 2, the maximum extent of coal
                               19
                                               AR302022

-------
 tar-contaminated soils  would need to be treated.  The remediation
 process  would include a network of air sparging wells to
 stimulate  bioremediation of the residual levels of coal tar in
 the  subsurface soils.   The Focused FS assumed that multiple
 treatment  "cells"  would be required, that two cells would be
 operated simultaneously and that the well spacings would be
 approximately fifty  feet.  Approximately 100 wells would be
 required to  remediate the entire Site.  The wells would range in
 depth  from 20 feet to 40 feet.  The 40-foot wells would penetrate
 the  levee.

 VIII.  SUMMARY OP  COMPARATIVE ANALYSIS OP ALTERNATIVES

     The Superfund process requires that the alternative chosen
 to cleanup a hazardous  waste site meet, two threshold criteria:
 protect  human health and the environment,  and meet the
 requirements of environmental regulations (Applicable or Relevant
 and Appropriate Requirements--"ARARs").   EPA's primary balancing
 criteria are:   long-term effectiveness and permanence, short-term
 effectiveness,  reduction of volume,  toxicity,  or mobility of the
 contaminants,  cost effectiveness,  and implementability.   EPA's
 modifying  criteria are  state and community acceptance.

    A detailed analysis  was performed on the three alternatives
 using these  nine evaluation criteria.  The following is a
 comparison of  the  alternatives with respect to these criteria.

     Protection of Human Health and th« Environment

     All of  the alternatives,  including Alternative 1 (No Further
Action), would provide protection to human health and the
 environment  by eliminating,  reducing, or controlling risk through
 treatment,  engineering controls,  or institutional controls.
 Implementing Alternatives 2 or 3  would not increase human health
 protection over Alternative 1,  as there  is currently no
 significant  potential for human health impact  and no significant
 risk related to ground water exposure.   Ground water is  not
 currently  used at  the Site.  Although hypothetical future use of
 on-site  ground water could result in an unacceptable risk,  such
use is highly  unlikely,   as discussed in the section on "Summary
of Site  Risks," above.   Brodhead Creek serves  as a regional
boundary to  ground water flow;  thus,  no  ground water across  the
 Creek from the Site would be impacted by the Site.  Upward flow
gradients  at  the Site decrease the likelihood that the bedrock
aquifer  beneath the Site will be  impacted.   A municipal  ordinance
 in the Borough of East Stroudsburg requires mandatory connection
 to the municipal water distribution system.   EPA understands that
 the Borough  of  Stroudsburg is presently in the process of
 developing a  similar ordinance.   Finally,  deed restrictions  to
 limit future use of the  Site will be imposed as part of  the  OU-1
 interim  remedial action.
                                20
                                       AR302023

-------
      Compliance with ARARs

      CERCLA requires EPA to conduct its remedial actions in
compliance with all environmental laws identified before the
Record  of Decision, if they are applicable or relevant and
appropriate for the situation. These requirements are commonly
referred to as ARARs.

              Drinking Water and Ground Water ARARs

      Alternative 1 would be in compliance with all identified
ARARs except federal MCLs for drinking water and Pennsylvania's
"background" ARAR which requires that contaminated ground water
be restored to "background" levels.  For the Brodhead Creek Site,
"background" would be defined as the method detection limit for
the method of analysis utilized with respect to a particular
contaminant.  The appropriate methods for the Brodhead Creek Site
would be EPA Methods 524.2 and 525.1.

    The results of the ground water modeling in the Focused RI/FS
for OU-2 revealed that all areas contaminated with residual coal
tar would need to be remediated to even attempt to meet MCLs or
background levels.  These areas include soils beneath Brodhead
Creek arid beneath the fill/highlands, the wetlands and the levee
on-site.

     Remediation of areas contaminated with residual coal tar is
not technically practicable for a number of reasons.  The
existing earthen levee could be damaged during the stabilization
process of Alternative 2 and might need to be removed and
replaced.  Implementation of either Alternative 2 or Alternative
3 would severely impact and/or destroy the wetland areas at the
Site and on the south fork of Brodhead Creek,  which would in turn
impact the existing wildlife at the .Site.   The wetlands would
need  to be restored.  In addition,  it would be necessary to
reroute Brodhead Creek temporarily to divert water from the south
fork in order to access coal tar-impacted soils beneath the Creek
bed.   This would increase the flow velocity and height of the
Creek.  Therefore, it might be necessary to reinforce the
existing 1-80 bridge abutments in order to reduce scour.   Work on
Brodhead Creek would temporarily impact the aquatic habitat.

      If, despite these problems,  Alternatives 2 or 3_were
implemented, they would provide some, reduction in the
concentrations of coal tar constituents in ground water over the
long term.  However, it is not likely that either Alternative 2
or 3  would allow reduction of the concentrations of coal
tar-related constituents to background or MCL levels within a
reasonable timeframe.   Low levels of coal tar-related
constituents would continue to leach from the stabilized soils
and some constituents would remain recalcitrant to
bioremediation.

                               21
                                          AR30202U

-------
      Therefore,  EPA is waiving  Che  federal MCLs for drinking
water and Pennsylvania's  "background" ARAR on the basis of
technical impracticability.  Use of the "Technical
Impracticability"  (TI)  waiver is appropriate when attainment of
an ARAR would be illogical or infeasible from an engineering
perspective  and  therefore would be  "impracticable."   (See
"Technical  Impracticability of  Ground Water Restoration, Brodhead
Creek Site"  dated  June 29, 1995)

                          Other ARARi

      Alternatives  2  and 3 would comply with PADER requirements
for air emissions  set  forth in  25 Pa. Code §§ 123.1 et.  sea. .
Off-site transportation of wastes would be conducted in
accordance with  the  Department  of Transportation Rules for
Hazardous Materials  Transport and Pennsylvania Hazardous
Substance Transport  regulations.  Disposal of hazardous waste
from  the Site would  be conducted in accordance with the
requirements  of  the  Resource Conservation and Recovery Act,
Pennsylvania  Solid Waste Management Act, and/or Pennsylvania
Residual Waste Management Act.  All discharges of treated process
water under Alternative 3 would be conducted in accordance with
the National  Pollution Discharge Elimination System (NPDES)
requirements  developed pursuant to the Clean Water Act and PADER
Bureau of Water  Quality Standards.                .'....

      As  discussed  above, implementation of Alternatives 2 or 3
would severely impact  and/or destroy the wetland areas at the
Site  and the  south fork of Brodhead Creek,  which would in turn
impact  the existing  wildlife at the Site.   All regulatory
requirements  for the construction activities in the wetlands and
the Creek would  have to be met.  Alternative 1 would not impact
Site  wetlands.

      Long-Term Effectiveness and Permanence

      Alternative 1 would be effective in the long term for
several  reasons.   The  slurry wall installed at the Site will
continue to prevent  free coal tar from discharging to Brodhead
Creek. 'Implementation of the OU-1 enhanced recovery program for
the free coal tar  areas on-site will reduce the areas of highest
subsurface soil  contamination to residual  saturation JLevels,
which is expected  to improve conditions for natural microbial
degradation.   The  OU-1  monitoring program will provide the data
required to evaluate the fate of the coal  tar-related
constituents,  the  integrity of  the slurry wall and the "health"
of the biological  community in Brodhead Creek.

      Alternatives  2  and 3 would both be effective in the long
term  in  that  both  will  reduce the amount of coal tar constituents
in ground water.   However, coal tar at residual saturation levels

                                22
                                             AR302025

-------
would continue  to be a source for the release of low levels of
coal tar-related constituents to the ground water in the shallow
aquifer, thus precluding compliance with MCLs and Pennsylvania's
"background" ARAR.

     Reduction  of Toxicity, Mobility, or Volume Through Treatment

     Alternative 1 would not reduce the toxicity, mobility, or
volume of the contaminants. However, the OU-1 enhanced recovery
program will provide for reduction in the toxicity, mobility,  and
volume of the contaminants by removing the free coal tar and the
source of the highest ground water contamination.

     Alternative 2 would not reduce the toxicity or the volume of
the residual coal tar.  However, the mobility of the contaminants
in the subsurface soils would, be significantly reduced, thereby
reducing their  impact on ground water in the shallow aquifer.

     Alternative 3 would reduce the toxicity and mobility of the
coal tar contaminants in ground water in the long term.  However,
in the short term,  the mobility of the contaminants could
increase as a result of microorganisms producing surfactants as a
"food source."  Alternative 3 would not be expected to
significantly reduce the volume of residual coal tar since some
constituents would remain recalcitrant to bibremediation.  -

     Short-Term Effectiveness

     There are  no short-term risks associated with implementing
Alternative 1.

     Potential  risks to on^site workers and/or the community
might occur dufing implementation of'Alternatives 2 and 3.
Exposure to releases of coal tar-related constituents could be
minimized by the use of proper operating procedures and personal
protective gear for on-site workers.  Some emission of VOCs .
during the treatment activities is likely to occur.  Precautions
would have to be taken to ensure that these emissions would not
impact off-site populations.  Off-site transportation of any
recovered coal  tar and wastewater during the implementation of
Alternatives 2  and 3 could create the potential for accidental
releases, with  attendant human health and environmental risks.

     The wetland areas at the Site and the south fork'of Brodhead
Creek would be  destroyed during implementation of Alternatives 2
and 3,  which could subsequently impact the existing wildlife
habitat.

     Xmplementability

     Each of the alternatives under consideration would be
implementable at the Site.   Alternative 1,  No Further Action,

                                23
                                               AR302026

-------
would  be  Che  easiest  to  implement.  The equipment and labor
required  for  the  implementation of Alternatives 2 and 3 is
readily available.  RCRA-permitted hazardous waste facilities are
available to  receive  the recovered coal tar and wastewater.

     Several  Site-specific constraints would make the
implementation  of Alternatives 2 and 3 difficult.  These include
the need  to:   (1) reroute Brodhead Creek temporarily to divert
water  from the  south  fork in order to access coal tar-impacted
soils .beneath the Creek bed;  (2) reinforce the existing 1-80
bridge abutments  in order to reduce scour due to the increased
flow velocity and height of the Creek; and (3) restore wetlands
which would be  impacted by the implementation of Alternatives 2
and 3.  In addition,  the existing earthen levee could be damaged
during the stabilization process of Alternative 2 and might need
to be removed and replaced.

     Cost

     The  present worth cost for Alternative 1 is $0,  which is the
lowest cost alternative.  The highest cost alternative is in-situ
stabilization (Alternative 2)  at $13,066,10.0.

     State Acceptance

     The  Commonwealth of Pennsylvania has concurred with the
remedy.

     Community Acceptance

     Community acceptance of the various alternatives is
reflected in  the attached Responsiveness Summary.  The
Responsiveness Summary presents all of the public comments
received  on the RI/FS and the Proposed Plan,  and EPA's responses
to the comments.

IX.  SELECTED REMEDY

     After careful consideration of the requirements  of CERCLA,
the detailed  analysis of the alternatives,  and public comments,
EPA has selected Alternative 1, No Further Action,  for Operable
Unit Two  at this Site.

     Although the hypothetical ingestion of on-site ground water
reveals a risk above IxlO"4, this  scenario  is  highly  unlikely.
As mentioned  previously, several Site specific constraints limit
the practicality of using the ground water at the Site as a
drinking  water source.  These include the levee and wetlands
located on-site.  Furthermore, it should be noted that any use of
ground water  from the shallow aquifer is very unlikely in light
of a municipal ordinance in the Borough of East Stroudsburg which
requires  mandatory connection to the municipal water  distribution

                                24
                                         UR302027

-------
system  (East Stroudsburg Code §154-4).  EPA understands that the
Borough of Stroudsburg  is presently  in the process of developing
a similar ordinance.

     In addition, 'the gravel unit is  too limited in extent to
serve as a viable ground water supply at the Site.  Brodhead
Creek serves as a hydraulic boundary  for shallow ground water
contamination; it is not possible for ground water in the shallow
aquifer to migrate east of Brodhead Creek.   Furthermore, the
Focused RI reaffirmed that upward flow gradients exist at the .
Site.  Therefore, there, is little probability that the bedrock
aquifer underneath the  Site will be impacted.

X.  STATUTORY DETERMINATIONS



     The No Further Action Alternative, in conjunction with the
OU-1 remedy, will be protective of human health and the
environment.  Implementation of the OU-1 enhanced recovery
program for the free coal tar areas on-site will reduce the areas
of highest subsurface soil contamination to residual saturation
levels,  which is expected to improve  conditions for natural
microbial degradation.  The OU-1 monitoring program will provide
the data required to evaluate the fate of the coal tar related
constituents, the integrity of the slurry wall and the "health"
of the biological community iii Brodhead Creek.  This will provide
long term protection against the unlikely event that Site
conditions might change and potential exposures increase.  In
addition, the slurry wall installed at the Site will continue to
prevent free coal tar from discharging to Brodhead Creek.

     There is currently no significant potential for human health
impact and no significant risk related to ground water exposure.
Ground water is not currently used at the Site. Although
hypothetical future use of on-site ground water could result in
an unacceptable risk, such use is highly unlikely,  as discussed
in.the section on "Summary of Site Risks,"  above.   Brodhead Creek
serves as a regional boundary to ground water flow; thus, no
ground water across the Creek from the Site would be impacted by
the Site.  Upward flow gradients at the Site decrease the
likelihood that the bedrock aquifer beneath the Site will be
impacted.  A municipal ordinance in the Borough of East
Stroudsburg requires mandatory connection to the municipal water
distribution system.  EPA understands that  the Borough of
Stroudsburg is presently in the process of  developing a similar
ordinance.   Finally, deed restrictions to limit future use of the
Site will be imposed as part of the OU-1 interim remedial action.
                                25
                                             AR302028

-------
      B.   Complianca with Applicable or Relevant; and Appropriate
      Requirementa

      The  Record of  Decision  for Operable Unit One  (March 29,
1991)  addressed all the  ARARs  concerning the Site except for
ARARs relating  to ground water or drinking water.  Reference can
be made to  the  ROD  for OU-1  for a full discussion of the ARARs
discussed therein.

      Since  the  selected  remedy requires no further action for
residual  coal tar contamination and ground water contamination,
action specific ARARs  do not apply.  The only ARARs that apply to
ground water are the Safe Drinking Water Act MCLs promulgated at
40 C.F.R. 141 and the * Pennsylvania ARAR-for ground water which
requires  that all ground water be remediated to "background"
quality,  as specified  by 25 PA Code §§ 264.90-264.100 and in
particular  25 PA Code  §§ 264.97(i), (j),  and 264.100 (a) (9) .    EPA
is waiving  Federal  MCLs  and Pennsylvania's "background"  ARAR on
the basis of "Technical  Impracticability."  Several site specific
constraints as  discussed earlier make the implementation of
engineering solutions  to the contamination impracticable.

    The horizontal  and vertical extent for which the TI  waiver
will be invoked is  the shallow aquifer at the Site, including
the area  containing free and residual coal tar depicted  in Figure
3, and the  zones beneath Brodhead Creek,  the island, the levee,
the wetlands, and the  fill/highlands on-site.  The vertical
extent includes the stream gravel unit between the fill  and the
silty  sand units as depicted in Figure 7.

     Several intermediate wells screened in the silty sand unit
of the Site are currently being used to monitor the shallow
aquifer (TI zone) .   In the Proposed Remedial Action Plan for the
final  ROD on OU-1,  EPA will recommend adding more intermediate
wells  to  the long-term monitoring network.  These wells  will
monitor the TI  zone and  will also serve as early indicators  in
the unlikely event  that  contamination moves vertically downward
toward the deeper ground water in bedrock.

     C.   Coat-Effactivenesa

     No additional  cost  would  be incurred by the selected remedy.
     This remedy is No Further Action and is not intended to
utilize permanent solutions and alternative treatment (or
resource recovery) technologies to the maximum extent practicable
for this operable unit.
                                26
                                             RR302029

-------
XI.  DOCUMENTATION OP SIGNIFICANT  CHANGES PROM THE PROPOSED PLAN

     The Proposed Plan for  the  Brodhead Creek Site was released
for comment in May of 1995.   It described the alternatives
evaluated in the Focused FS for OU-2 and identified Alternative 1
as EPA's Preferred Alternative.  After reviewing all of the
written and verbal comments submitted during the comment period
and at the public meeting,   EPA has determined that no
significant changes to the  Proposed Plan remedy are necessary.
                               27
                                             AR302030

-------
APPENDIX A

-------
                                FIGURE  1
                 Brodhead Creek Site Location Map
                        Stroudsburg, Pennsylvania
         ®
                                            N
W0«

 2S3J3.CC.C1
0*«-»r/0itt: P.MicAll.n 7/18/90    j
                        C.licttl It
           «,,„•« >T,0.,.:.M.Smlth a. 17 90
                                                  B.I790
                                           SR302032

-------
CO
o
ro
C5
CO
CO
                                                   Figure   2
                                                    Site Plan
                                      Brodhead Creek Remedial Investigation
                                            Stroudsburg, Pennsylvania
                »,...»,/«.u  CMi'fl/ii/aa	I C...L. >, / »M. » Kan
jf  •» IM* **•' • V«* *•••*

-------
CO
CD
ro
CD
co
                                             FIGURE 3
                                   Maximum Probable Extent of
                                       Free Coal-Tar Surface
                                  Brodhead Creek Remedial Investigation
                                           Stroudsburg, PA
                fc^t,'*"* CMt» a/I 1/09
»M n Kan a/I 1/89

-------
                            General  Site  Stratographlc  Column
                                         Brodh««d Cr««k  Sit*
                                     Stroudtburg, Pennsylvania
           20'
          80'
         ISO1
                 .. . v • i.  . •- . -. ,  •.. .
                 '*.•''*.•"»..'*»."'••' •'•*.'"•
                 •.•-  .;> ..•. !•• •.."'•,'•,'  *
                 •*•'/ • '•,• •*. - •  ;.. «


                 '•-/ . '.'.•./.••••'.."'-I'*'»
                .-• 'V.  •  »'•  ••.  t'  :
                                                   fn
                                             flood Piam Otoo«rt
                                             Strnm
1 73 i IQ -* ft/
      Ovrt  in
                                                                    from ' J • '0  -i '!/«« ia
                                                                    <  .• i»ml«4  :*t int.
                                            T>
-------
CO
C3
ro
o
CO
cr»
                                              FIGURE 5
                                         Lateral Extent of
                                       Stream Gravel Unit
                                 Brodhead Creek Remedial Investigation
                                           Stroudsburg, PA
    I «J 4J CS I k L I




\\\l  !•!••• *l il>««n> t-,
v>*   tMMl *M«IMI«I «.«.!
             Nltlllt k| ( •<)•	
       253 2!> 05

-------
30
CO
CD
ro
CD
CO
                                                FIGURE  6
                                        Top of Silly Sand Unit
                                   Brodhead Creek Remedial Investigation
                                         Stroudsburg, Pennsylvania
lo
-------
                                                  Figure 7
                           Schematic off Extent off Free and Residual Coal Tar
                                             Brodh«ad Cr««k SIU
                                           Stroudsburg, Pennsylvania
                                   E«l«nl ol Rcwduol
                                  Subwirloc* Cool Tor
                                                                                     flooo Control Wull
CO
CD
DO
CD
CO
CO


-------
                                     FIGURE  8

                             Water Supply Well Locations
                                Brodhead Creek Site OU-2
                                Stroudsburg, Pennsylvania
                                                                              -•(
     |L'"__ '• •  It  '  "-
                '

             Borou^i ot East
             SlrouCJburg Wattr
             SuopV Wdl 3
             Oinlxry Ptrk
                         Source: U.S.G.S.Tooograohic Quadrangles. East Stroudsburg. PA and Stroudaburg. PA-N
EXM J
                                                       RR302039

-------
                                                  Figure 9
                                       Ground Water Flow Schematic
                                              Brodhead Creek Site
                                            Stroudsburg, Pennsylvania
                                                    - £«l«nl ol Ruidual
                                                                               Flood Control Wull
CO
o
ro
                                                         B1
                                                                                        I  ^>

-------
                                         FIGURE  10
                                    Log off Sum of Total
                                     Detected Organics
                              Brodhead Creek Remedial Investigation
                                        Stroudsburg, PA
   locjerxJ

U I •"•
CO
CD
ro
CD

-------
              FIGURE  11
Site Plan with Monitoring Well Locations
           Brodhaad Craak SIU
         Stroudtburg, Pennsylvania

-------
CO
O   8
ro   s
o   g
jr*   o
CO   |
                                                 FIGURE  12
                                          Flow In Bedrock System
                                              7 September 1003
                                           Brodh«*d Cr««k  SIU OU-2
                                            Stroudtburg, P«nn§ylvenla
                                                 Scwoge Treatment Plant
JS) PaUnlMMixKK Surtac* IW.

        w«clM>n ol Iki.
                                                                                                  !•••!•

                                                                                              nIJtn ol (low
                                                                                        Slu Mai.

-------
                   FIGURE  13
~r-^:   -—  ;'N Regional Fracture Pattern-~^   "..  ,._\.    **?•
-.-^-^-S^.-1    Brodhead Creek Site       *#*  *:'.   '.">^<"
                                            1-* %t" '
         • • --^
*. W^iS^^'W I!

                                    LgCEND

                                 — Apprexinwti Fracturt Ori«ntation ^.

              ?jplu ViUty Or- .

-------
APPENDIX B
           AR3020U5

-------
                       Rtlrruttutd Appmpmw Rtqairroiena forGiaand W(wr
                             Sradhtad Cmk Sit* Fnubility Study
                       iill conetntntiom *" >* **ffl- mum* ethtmruM i
CHEMICAL
A:cicr.e
Cirton Duulfid*
Chioroiorai
Methyl (thvl keton*
1 . 1 . 1 •ThcrUorocuxut*
Bnutnt
Tolutnt
3\jofobcnunc
Ethytbatzew
Styrcnt
Xyltn*
PhwoJ
Ac0upnuiy')Uki
AccniphthM
Fniofvw


Phfluwthfw
AnthnccM
Fluanmhai*
Pywnt
BcmUtatthnctn*
OUfMfM

Binio(b>a«QMHlh«M
BMBoOdflaoaMlMM
BOTMWpjmm
lndtneprnM
B0izo(ghi)pvfyftBi0
NiphttulM
2-MfthyiNaphttukM
Dibuty) phdulitt
Butyl bvizyl phdulitt
Amnk
auiun
Beryllium
Zadatiuni
OwonuumVI
Copptr
Iran
L««d
MangiiMM aid coafeund*
Mtroiry , morjmjc
Nidul
SeUfUua
Siivtr and eea^eundt
Sodium
Thallium
Vvudixm
Zinc
Cytntd*
Ground Waitr
Conc«nmhon»
Muimam Avtngt
8.50E-02 9.43E-01
4.20E-02 6.29E-03
2.ME-02 S.44E-03
J OOE-03 9 70E-03
JOOE-OJ SJUE-U3
i.ioE*oo rioe-ot
1.40E-01 1-24E-02
2.JOEXS 5^6E-03
4.00E-01 9.1SE-02
2.70E-02 6.UE-09
6.10E-01 1.14E-01
2JOE42 6. 12-03
8.70E-01 1.17E-01
1.40E*00 1.04E-01
l.«OE*00 U 6.13EXn
NA NA
NA NA
Utt-m 3.UI4B
5.9SE41 I.9JE-01
3JOC-M SJOEMM
115I-OS LISl-O
UR-OS L3OMB
1J9B4B 1J9B-03
177E« i.aoe*oo
4JOB-03
SJOe-03 1.008-01
1J»-01 5JJOM2
U* IJOI-rtO
NA J.OOE-01
ojns* sjot-oa
NA SJOMI
2JMB-03
l.OOE-01
5JBC-
-------
                Summary of Ground Water Analyses
                Brodhead Creek Site Oil-2
TABLE 2
CO
CD
l\3
CD
JT
ORCANICS
VOC»(ngll)
Carbon Disulfide
Trichloroethene
m&pxylene
1,2,4 trimethylbeiuene
Chloromethane
Trichlorofluorometnane
1.1-Dichloroethane
1,1,1 Trichkmxrthane
Benzene
Toluene
SVOC«
2-Methylnaphlhafene
Naphthalene
Diethylphthalale
Butylbenzylphthalate
Bistf-ethylhexyDphlhalate
Dimethylphinalate
Pentachlorophenpl
Phenanlhrene
Di-n-butylphthalate
Bis (2-ethylhexyUadipate
BR-1
6/3/93 12/10/93 5/8/95
0.2 NA ND
0.6 ND ND
ND 0.1 ND
0.1 ND ND
ND ND ND
ND ND ND
ND ND ND
ND ND ND
ND 0.1 ND
ND 03 ND

0.09 0.1 ND
0.1 0.1 ND
03 0.2 0.06
ND 04)8 ND
21 8.0 0.8
ND 0.06 ND
ND ND ND
ND 04)5 ND
ND 0.4 ND
ND 0.3 ND
BR-2
6/3/93 12/9/93 5/9/95
0.4 NA ND
03 ND ND
ND ND ND
ND ND ND
ND ND ND
ND ND ND
ND ND ND
ND ND ND
ND ND ND
ND 0.2 ND

ND ND ND
ND 0.08 0.04
0.2 tt3 0.09
ND 0.1 ND
ND 10 04
ND OS* ND
ND 01 ND
ND ND Om
ND 0.1 ND
ND as ND
BK3
6/4/93 12/9/91' 5/8/95
0.2 NA ND
5.1 ND ND
0.2 ND ND
0.1 ND NO
ND 0.2 NO
ND ND ND
ND ND ND
ND ND ND
ND ND ND
ND ND ND

0.09 ND ND
0.2 ND ND
0.3 ND ND
0.1 ND ND
ND ND ND
ND ND ND
ND ND ND
ND ND ND
ND ND ND
ND ND ND

-------
 Shallow
SrodMiaM Cftik Sit* I f*D "•"
itroudsbvrf. Prmsylvamt
Constituent
VoUnle Compound*
C-Butanone
8«(uene
Toluene
Ethylbenzer.t
To.tal Xvlenes
Seyrtnt
Semi* Volatile Campetiade
Naphthiknt
2-Methylniphthaltnt tt
Acenaphthylent tt
Acenaphthtnt
Dibtnxofunn tt
Fluorent
Phtnanthrtnt t
Anthracene
FIuonnthtM
Pyrtnt
8tfuo(a)anmnctM
Chryitnt
n't/5 MliifUuwltaHthmlBM
Btnzo(b or k)fiuonnmtjM*
BenzoUtpyrtnt
tndtno( 1 -13-cdlp)rtg»
OibtnXaJtianthnetnt
B«nzo
129141
'
.
.
•
9331*01
4J9B42
.
IJ7M2
V^58-03
1161-01

* Serttning Itvtl btatd on pywnt teoOOtr *•»
NA«Notamlyud
NO'NotdtMatd

8 • compound ww dettcttd in blank umplt at • «0uUr eonocrandon
- • no nsk-eated «a*ewng tovil It avukblt tor itni compound
                                                          ittvo)

-------
                                                                            TABLE   4
       Conjtirufttt
                        Stckpoimd
                        concmndon                atuimuB    R«i»in«d tor
                        frtiitr dun  CicMdi RMJIOII  dracad to   rxliuoon in
                        downgndicnt   III ruk-e
2.M«fiylniptitfukf»
Actruph*yl«no
A^MUBfertW^M
AC VTtdl^lU mt W
Dibtntofunn

Ftuoiw
Phtmmhrtnv
Arthrmnt
FTuofwichtm
r. l>a.
rjri»Tw
BcnsofftlttttnncoW
6^2^lllO«rl)pMttlM
Btruoik or klfluotmdvno
BtnMi)p7>w
Indonol liKdlpr1""*
Oibtro( i Jittntfuioono
Bfnxofgjulporytam
Phnwl
PtntocMorophoMt
atrayl Alcohol

N'o
No
No
No
No

No
No
No
No

No
MA
•^•Q
NO
No
No
No
No
No
No
No
No
No
No
No
No
No
Sfo
i'W
NO

No
Yoi
No
No
No
No

. *•
Yo)
So

So
Sa
i*W
TO)
No
No
No
TO)
Yo)

TO)
TO)
TOI
Toi
No
No
No
No

Vo
Y«
No
YM
No
No

Yoi
Yoi
Toi

Toi
T«M
^
Toi
No
Toi
YM
Toi
YM
Toi
TOJ
Toi
Toi
Toi
No .
No
Toi
No
No

No
YM
No
No
No

Yoi
Toi
Toi
YM

YM
YM
Toi
No
Toi
Y«
Toi
Toi
"»
Toi
Toi
Toi
Toi
NO
NO
Toi
MM
• »*r
No

Did not ftu icnwuif ipinw ruk-btMd d not fad icrwnutg tpinn nik-6u*d tcnvrvrf !«v«
Rjno 01 juiioiuffi conctntnaon to CM KnMnui| w«i u
Did not fill xntrung ipimt nak-b*Md lomun; l«vt<
Did not fail tcnnunf ipuui njk-ouM icrttniri l«v«i

F«M Krominc tpirM nik-dMOd icnvrup j l«vti
Fiilod icronnt tpirot rak-o«od KiHninf |M«!
FuM tenojunf ifiuM nk-MMd KTMiunf Irnl
gnstv tfuw 0.1


gfMtvthinai

Old not fell ni'^uif jpirat rvk-biMd aoiwinf kfvti
ttidocrftiuxoffiuaaaKvwmanra^ftTivu^irr^ut

FtiW KMRiaf tfurot rMfOMod laoaung tenl
Not t omatuom of cotl w (MO apart tnt) .
FII)O *MI«^HB> Mtfk jM^oaaA 	 laaa«4
W^ (W BHl IBWV^ o^MW nK*WB IQvWnB lonrV-
FtiM KMninf tfurm mk-ooMd tcnmrtf tani
Old not htl MMninf ipinoi nMoMd icnomni M*4
Aluaunum
Anonie
Suium

^"ilriufli
Iran
VfagnoRum
SUnfUMM
Nickol
Sodium
                           No
                           No
                           No

                           No
                           No
                           No
                           No
                           No
                           No
                           No
            To)
            NO
            Toi
            No
                                                   Toi
                                                   No
                                                              No
                                   No
                                                              No
                                                               No
                                                               No
            Toi
            No
            No
                                                                                           trtmitaMtfor
                                                                anMUMoLowmul
                                                                       ofpeonul
FtiM MOI
Old not M
No
huarnnuMom.net
ZiiK
Cyuud*
No
No
No
                                        No
                                        No
                                        No
No
No
Toi
                                                               No
                                                               No
                                                               Toi
                                                                      Old not Ml *ao
                                                                      DMnottMliawnnf
                                                                                           rtbMrti
                                                                         rur» to«l
  > no rak-6«od laomnf K*e1 • (vuitol* 

-------
Deep Aquifer Screening Analysis
Bredhead Creek Site
Stroudsbvrg, Pennsylvania
TABLE  5
Maximum
Downgradient Background
Constituent Concentration Concentration
Volatile Compounds
Benzene
Carbon disuifide
Trichloroe there
Toluene
m+p Xylene *
1 .2,-t-Trimethy Ibenzene
Semi* Volatile Compounds
Naphthalene
2-Methylnaphthalene tt
Diethylphthalate
Di-n-butylphthalate
Dimethylphthalate
Butylbenzylphthalate
Bis (2-ethylhexyl)adipate
8is(2-ethylhexyl)phthalate
Pentachlorophenol
Phenanthrene t
Total Metals (unfiltend)
Calcium
Iron
Magnesium
Manganese
Notes:
J = quantitative estimate
ND » Not detected

0.1
0.4
0.6
0.5
O.I
0.1

0.1
0.1
03
0.4
0.06
0.1
0.5
21
0.1
0.05

58100
9600
5080
347




J
J


J
J

J
J
J
J
J
J
J
J
J
J


J
-





ND
0.2
5.1
0.3 B
0.2
0.1

0.2
0.09
03
03 B
ND
0.1
0.2 B
12 B
ND
ND

40800
33600
10900
354



Ratio of
USEPA Region Maximum
(II Risk-Based Detected/
Concentration Screening
Table Level

0.36
21
1.6
750
520
3

1500
1500
29000
3700
370000
7300
56
48
0.56
1100

_
.
-
180




2.78E-01
1.90E-02
N/ A
6.67E-04
1.92E-04
3.33E-02

6.67E-05
6.67E-05
1.03E-05
1.08E-04
1.62E-07
1.37E-05
8.93E-03
4.38E+00
1.79E-01
4.55E-05

,
.
.
N/ A



- = no risk-based screening level is available for this compound
tt Screening level based on withdrawn naphthalene toxicity data
. p • i i ^ j *
t screening level oases on pyrnte ton
* Screening level based on p-Xyiene
idrydata









N / A Not applicable; Did not exceed the background concentration
All values in iig/L






-------
          Tttlt for tlu itlfCtiam of CamttinrmU of fotnliMl Camcom im Ifc* Otff A^mtftr
                           conctttmio*                 dMMttd M   fUtiuwd for
                                r HIM  ruiirti topM III Kiwuof k»«l tvahutiM IB
                                         nik-tand     pmiMrtkM      ink
                                                         0.1? _ «M«M»«n*i
                              No           No           No         No    Did not tad KIWI* «|MM n*k-bM*J Iwt.
                              No           No           No         No    Did not <•! Kmmnf ifairai ntk-bwd tovri
                              No           Yoi           Y«         No    Not •cantiiaMmaicuiuriM* noon tot)
                              No           No           No         No    Old an f«< cnnnf >(>irai r*k-b«» !)•*««
                              No           No           Yoi         No    OhiiwWKnMn|ifMMlf«k-bM»Jli««i«^
                                                                           pom w |m«d wmr • MOM (M* npait
                               No           No           No         No    DtfMfiilaaMMVifaMr.ik-bM>:ilmi
                               No           No           No         No    DMli«fMlnMiia|ip««mk-»MtJlw«l
Tom i
                               No            •            -No    riin|niiMHiil»i nmut) intern in mnlilili
                                                                           •MMttl huoun nuinmt not luMonui conunucm
                                                                           afpOMMMlc
                                                                     No    NoauMMMlvtHudtjrindieHifttvuUM*.
                                                                           oipaMMiitcaneMi
tlignniiim                      Y«>            •  .          -          No    NoquMiwiliv*Munyindien«n>JvUliMt.
                                                                                 l huauo nuuvm. not hiMoncal canHaunu
                                           N/A         N/A         No    OMKMd in bickpoundM higher
   no   -     jcmnm  ^          far
 N/A • Not ippbribir. did not tm«d bottyound conctntr juon.
                                                                flR30205l

-------
Summary of Toxicity Data for Constituents of Potential Concern
Brodhtad Crttk Site
Stroudabtirg, Pennsylvania
TABLE  7
Constituent
Volatile Compounds
Benzene
Ethy [benzene
Semi- Volatile Compounds
Naphthalene
2-Methylnaphthalene
Acenaphthylene
Acenaphthene
Dibenzofunn
Fluorene
Phenanthrene
Fluoranthene
Pyrene
Benzo(a)anthracene
Quysene
Benzo(b or k)fluoranthene
Benzo(a)pyrene
Indeno(lZ3-cd)pyTene
Dibenz(ajt)anthncene
Pentachlorephenol
Dissolved Metals
Arsenic
Barium
Lead
Manganese
Cyanide
Inhalation
RfD
mg/kg/day

1.7TE-03
2.36E-01

NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA

NA
1.43E-04
NA
1.43E-09
NA
RfD
mg/Vs/dav

(6) NA
(I) l.OOE-01

4.00E-02
4.00E-02
4.00E-02
6.00E-02
4.00E-02
4.00E-02
3.00E-02
4.00E-02
3.00E-02
NA
NA
NA
NA
NA
NA
0.03

3.00E-04
(2) 7.00EXB
NA
(1) 5JXE-03
rOOE-02


(1)

(4)
(4)
(4)
(D
(4)
(D
(5)
(1)
(1)






(1)

(1)
(1)

(D
(1)
Inhalation Oral US EPA
CP? CPF Carcinogenic
1/mf/ki/dav iymcAft/day ClawinVation

2.90E-02
NA

NA
NA
NA
NA
NA
NA
NA
NA
NA
6.10E41
6.10E-03
6.10E-01
6.10E>00
6.10E-01
6.10E-M30
NA

U1E*01
NA
NA
NA
NA

(1) 2.90E-02 (1)
NA

NA
NA
NA
NA
NA
NA
NA
NA
NA
(3) 730E-01 (3)
(3) 7.30E-03 (3)
(3) 7JOE-01 (3)
(2) 730E*00 (1)
(3) 7JOE-01 (3)
(3) 7JOE*00 (3)
1.20E41 (1)

(1) 1.75E>00 (1)
NA
NA
NA
NA

A
0

D
•
D
•
D
D
D
D
D
B2
B2
82
B2
82
82
82

A
»
82
D
0
Note*
NA » Not available from UUS or HEAST
I . IRIS (USEP A. 1994)
2 - HEAST (U5EPA, 1994b)
3 =. BenwXaJPyrtne Emnvitane* (USEPA. 1993)
4 * Baaed on wimdnwn naphthalene value from OUS/HEAST.
5 » Baaed on tontitf dtft far pyrene.
6 » EPA-ECAO, 1994
A * Human carcinogen.
B 2 « Probablt human carcinogen; sufficient evidence in animals or no evidence in humans
D » Not dassinabl* as to human eareinogtnidty
••Notdassifitd
                                                             AR302052

-------
              Stt»
                                                                               TABLE   8
            KUfc
  &IOOMU*
CaactnoraM
               Ont
               OT
   Conjom*m
                                                 (auk* Fioor   Uitua f
                                                  InfMM     Otimtt
                                      I90E-OZ
  4*4842
  460C42
  460E42
                                   4.93E44

                                   1.90C42
             TVf.09
             7XC41
                                                  t.17142
  CUTOTW
  ObmflUV
                                   U2E42
                                   190*42
                           9X149
                                      i.at-n
                        I.17E42
                        1.17142
                        1.17142

                        1.17B42
                         190E42

                         410841
                        i 101.49
                        410*41
                        ». 10143
                        i.Ut«00
                                   44*142
                                   I.DI42

                                   USE-OS
                         I J7C42

                          N/A
                          N/A
                          N/A
                          N/A
                          N/A
                         N/A
                         N/A

                         N/A

                        TottlRhfa
                                                                                               S06E-04
                                                                                               149C43
                        iM£4)
                        14IS09
                        5IOE43
                        314604
                        IfTt-OS

                        2.S243
                                                                                               2.WC-02
                                       UD
                                                                         to
                                                                                              Hauri
 940*41
 490*41

 taoc«OB
             N/A
            LOOM!

            40*01
                          1.65141
 Ftuotm
 FluonnMn*
                          140141
                         5.731.00
                         aaoc^o
                         1001^0
                         938*42
            400(42
            40*02
            400*42
            40*02
           10*02
Ar
3*miai
101*41
3.95*41
                                    700*41
Cyiiud*
 174(42
 174*42

 174(42
 174(41
 174(42
 174142
 17U42
 174(42
 174(42
 174*42
 174(42
 174*42

 174*42
 174*42
174*42
174(42
I.I5I43
408*41

523*41
                                  901(41
                                  l.«*42
                                  1.97*42
                                  178*4S
                                  1.1A42
                                  L4H42
                                  1.7W42
                                  JJU42
1«*41

 NA
 NA
 NA
 NA
 NA
 NA
 NA
 NA
 NA
 NA

 NA
                                             1.43*41
                                              NA
14*142
1J1I42

 N/A
 N/A
 N/A
 N/A
 N/A
 N/A
 N/A
 N/A
N/A
N/A

N/A
N/A
N/A
N/A
                                                                                              1OT41
                                  116C41
                                  1.30E41
                                  9»IE4l
                                                                    IJ1H-D
                                                                    I 41141
                                                                    I JH-02
                                                                   U3I4I
                                                                   4.sf^n
                                                                   199C41
                                                                                             t 141.42
                                                                     AR302053

-------
                                        (Itt of Sk«
 3 40-01

 54H41
                                                            161E-04
 4ISE43
 91RE4)
 6.20E41
 107E42
 1.4SC42
 4.97Y4)

 7&SI4*
                                                                       190E-CZ

                                                                       «loe-oi
                                                                                    1 4AE-02
              N/A
              N/A
 6.10E4I        N/A
 6.IOE41        N/A
4.10E^»        N/A
 4.10E41        N/A
  NA          N/A
                                                                                     N/A
            SRE04

            JME-04
            «»^-03
            «72EiM
            113E-04
            1 I3E-05

            194E43
                                      wo
                                                                         UD
                       4.90*41

                       ia««oo
                       3.&3E4I
                       1.45141
                       8.49*41
                        5.73ZWS
             N/A
            1.00*41

            40*41
            6.00*49
            4.00*41
            400*49
            4.00*43
            4,00*42
4JH4J
6J9I49

4J9MI
6JN4I
4J9f4J
6J9*4Z
4J9V42
6JH42
                                                           1.CT4J
&5ZS49
1J3*42
1.47149
3-3*01
U1S42
11U4S
t9042
Cyvrad*
                       93M42
                       900*49

                       1J38*41
                       3.95*41
                       1.13IWH
                       1.4
           3.00*42
           300*42

           340*44
           700*41
           340*41
           U10K42
6JK4Z
4J»MJ

09*41
                                                           191141
                                                           3JO*42
                                                           1*2*41
I.HI4J
LMC41

 NA
 NA
 NA
 NA
 NA
 NA
 NA
 NA
 NA
 NA
                                                                        NA
«J**41
«J»*41
                                                                        NA
IJ1E41
14H4Z

 N/A
 N/A
 N/A
 N/A
 N/A
 N/A
 N/A
                                                                                               4.90E4I
                                                                                               4WC-01
                                                                                             104E.OO
                                                                                             37M4I
                                                                                             1.00C«01
                         N/A
                         N/A

                         N/A
                         N/A
                         N/A
                         N/A
           1911-01
           34*1-0:
                                                                                              34a-01
                                                                                              1.471 wa
                                                                                              4.63*41
                                                                        flR30205U

-------
                           APPENDIX  C

                     RESPONSIVENESS SUMMARY
                  BROOHEAD  CREEK  SUPERFUND SITE
                        OPERABLE UNIT TWO
     This Responsiveness Summary for Operable Unit Two of the
Brodhead Creek Superfund Site  ("the Site") in Stroudsburg,
Pennsylvania, is divided into  the following sections:
Section I
Section II
Section III
          Overview - A summary of the
          public's reaction to EPA's
          preferred alternative for Operable
          Unit Two.

          Background on Community Involvement
          A discussion of community interest
          in the Site and of information
          provided to the community by EPA
          and the media.

          Summary of Public Comment* and
          Agency Response* - A summary of
          comments received during the public
          comment period on the Proposed
          Remedial Action Plan for Operable
          Unit Two and EPA's responses
I.
OVERVIEW
     On March 29, 1991, EPA issued a Record of Decision ("ROD")
on Operable Unit One ("OU-1")  at the Brodhead Creek Superfund
Site.  This ROD contained EPA's selected interim remedy for the
free coal tar accumulation in the subsurface soils at the  Site.
The interim remedy consisted of an enhanced recovery program for
the free coal tar and attendant ground water monitoring.

     On May 25, 1995, EPA issued a Proposed Remedial Action Plan
("Proposed Plan") for Operable Unit Two C'OU-211)  at the Site.
The Proposed Plan addressed residual coal tar in the subsurface
soils and ground water contamination.  In the Proposed Plan,  EPA
identified its preferred alternative for OU-2 as no further
action.  The Agency determined that the work already being done
under OU-1 should be sufficient to protecf-human health^ arrifthe
environment..

     A public comment period on the Proposed Plan was held from
May 25 through June 23, 1995.   On June 6,  1995,  a public meeting
was held which provided an opportunity for the public to ask
questions and express opinions on the Proposed Plan.   Attendance
at the meeting was moderate.  Based on input received during the
                                       AR302055

-------
 public  meeting,  EPA believes  the community members are generally
 supportive  of  the  no-further-action alternative for OU-2

 II.   BACKGROUND  Of COMMUNITY  INVOLVEMENT

 The  Brodhead Creek Superfund  Site is  located in the Borough of
 Stroudsburg, Monroe County,' Pennsylvania.  This area of
 Pennsylvania is  located between the Pocono Mountains and the
 Delaware River and is a popular winter and summer resort area
 with tourism as  the mainstay  of the area's economy.  Brodhead
 Creek,  which originates in the Pocono Mountains and flows past
 the  Site, has  been identified as one of the best cold water trout
 fishing streams  in Pennsylvania.  Many of the area's conservation
 groups  and  tourism groups, as well as the local and county
 officials,  are aware of the problems at the Site.   However, there
 have  been few  expressions of  community interest or inquiries to
 EPA  about the  Site.

 Besides the meeting on June 6, 1995,  EPA held public meetings to
 update  the  community on the progress of site activities in
 February of 1991 and February of 1994.  In April of 1995,  EPA
 conducted interviews with community residents and officials to
 determine the  community's awareness of, and concerns about the
 Site.  EPA has also kept community members informed of ongoing
work  through informational fact sheets and announcements in the
 Pocono Record.   In  addition,  the community has access to EPA's
 local information repository at the Stroudsburg Borough Building.

Media coverage of the Site was extensive in the early 1980 's when
 the contamination was first discovered, but has decreased to
 sporadic newspaper  articles.   The media did cover the public
meeting held on February 27,  1991 on the Proposed Remedial Action
 Plan  for Operable Unit One and the meeting held on June 6,  1995,
on the Proposed Remedial Action Plan for Operable  Unit Two.

The comments made during the public comment period and EPA's
 responses to those  comments are described in the following
summary .

III. SUMMARY OP PUBLIC COMMENTS AND AGENCY RESPONSES

 1.  A community member  asked if the pocket of coal tar
accumulation located outside the slurry wall is a  result of a
defect in the  slurry wall.
EPA RESPONSE s  No.  The slurry wall is working as
However, when the slurry wall was originally constructed,  a  small
area of free coal tar was inadvertently trapped outside of the
wall.  This free coal tar accumulation is effectively contained
by the elevation of the silty sand unit in this area because the
free coal tar cannot move through the silty sand,  and therefore
it should not pose a threat to Brodhead Creek.  The OU-1 remedy
                                          AR302056

-------
addresses  this  area (MW-2  area)  of  free  coal  car.   In addition,
the  incegrity of  che  slurry wall will  concinue  Co be monicored as
pare of  che  OU-1  remedy.

2 .  A  communicy member  commenced on che  coses of che Alternatives
for OU-1 and OU-2  and questioned why EPA did noc selecc a no-
furcher-accion  alcernacive for Operable  Unic One as well.

EPA RESPONSE:   1C  was determined Chat  the free  coal Car present
ac che Sice  was a  principal chreat  to  ground water.  EPA defines
a principal  threat as a high volume, high toxicity waste.
Therefore, EPA  determined  that the  free  coal tar in the
stratigraphic depression on-site (RCC  area) and the MW-2 area of
the Site should be removed.  This will be accomplished by the OU-
1 enhanced recovery program.  Once  the enhanced recovery program
is completed, there should be no principal threat from the former
areas of free coal tar  accumulation at the Site since they should
contain only residual levels of  coal tar contamination.

3 .  A community member  asked if  the residual coal tar will remain
unchanged or if nature  will  take care of it.

EPA RESPONSE:   Over the long-term,  natural breakdown of the coal
tar contaminants in the soils would be expected to occur.
Unfortunately,  there  is no way to determine accurately how long
these natural processes will take.  The  removal of free coal tar
from the subsurface soils  may improve conditions for the natural
degradation  of  the contaminants.

4 .  A community member  asked what would prompt EPA to take action
at the Site  in  the future.

EPA RESPONSE:  The ground  water  and Brodhead Creek will  continue
to be monitored under the  OU-1 remedial program.  Should these
monitoring results  reveal  that Site conditions have changed,  EPA
will reevaluate its selected remedies and determine if  they are
still protective of human  health and the environment or  if
further action  is  needed.   In addition, EPA will conduct a formal
review of the Site  every five years to ensure that the  selected
remedies continue  to protect human health and the environment.
Finally,  if  EPA determines that Site conditions represent an
imminent and substantial endangerment to the public health or
welfare,  it  has authority  to take action under Section 106 of the
Comprehensive Environmental Response, Compensation and Liability
Act,  42 U.S.C.  § 9601 et sea. .  and Secticmu7;003 of the
Conservation and Recovery Act,  42 U.S.C.  § 6901 at
5.  A community member questioned what types of deed restrictions
would be placed on the Site property and whether the property
could be put to beneficial use.

EPA RESPONSE:  The property owners will be required to place deed
                                     AR302Q57

-------
 restrictions on the property to  prevent  the disturbance of
 material.below the surface  and to  prevent  the use of ground water
 on-site.   Possible future uses of  the Site will be considered
 when structuring the deed restriction.

 6.   A community member asked what  the classification of Brodhead
 Creek was  and if the levels  of contaminants entering the stream
 are  below  the levels necessary to  maintain that classification.

 EPA  RESPONSE:   Brodhead Creek is classified by Pennsylvania as a
 high quality cold water stream.  A high quality cold water stream
 is a stream  or watershed which has excellent quality waters and
 environmental  or other features that require special water
 quality protection and maintains and/or propagates fish species
 and  additional flora and fauna which are indigenous to a cold
 water habitat.   Although dissolved coal tar contaminants are
 discharging  to the Creek via  ground water, upon entering the
 Creek these  contaminants are  being diluted to a level which
 cannot be  detected.   EPA has  determined that there are currently
 no significant risks associated with the recreational use of
 Brodhead Creek or the ingestion of fish from the Creek.

 7.  A community member asked  if the coal tar contaminants
 entering Brodhead Creek are being  carried downstream and
 affecting  other areas.

 EPA RESPONSE:   Current  information indicates that for the reason
 discussed  in EPA's response to comment 6 above,  there is no risk
 associated with the use of Brodhead Creek either at the Site or
 downstream of  the  Site.

 3.  A community member asked, if severe disturbance to the creek
 bed were to  occur  from natural excavations or a  flood,  would that
 allow dangerous  levels  of coal tar contaminants  to enter Brodhead
 Creek?

 EPA RESPONSE:   The possibility of a flood was considered during
 the original remedial  investigation and feasibility study
 conducted  for  the  Site.  A worst case scenario of a 1,000  year
 flood event was  assumed.  Computer modeling revealed that
 approximately  two  feet  of the creek bed would be eroded.   Under
 that  scenario,  there would not be a significant  release of coal
 tar contaminants to  the Creek.

 9.  A community member  asked if the Stroudsburg  sewage  treatment
plant  (on  the  western boundary of the SifeeU,is impactecWby^ihe
 Site.

 EPA RESPONSE:  No.  The sewage treatment plant is not  impacted  by
 the Site.

 10.   A community member asked if potential development  upstream

                                4
                                          AR302058

-------
would be restricted because of the Site.

EPA RESPONSE:  EPA does not foresee that.any restrictions at the
Site will limit other activities upstream; i.e.,  there is no need
for restrictions upstream of the Site.

11.  A community member asked who is bearing the  cost of the
remedy for Operable Unit 1.

EPA RESPONSE:  Pennsylvania Power and Light Company and Union Gas
Company are paying for the cleanup work.

12.  A community member asked when EPA will make  a final decision
on Operable Unit Two and notify the public.

EPA RESPONSE:  EPA is hoping to make a decision on Operable  Unit
Two as soon as possible.  However,  EPA wants to ensure that  it
has considered all available information and evaluate public
comments prior to making a final decision.   EPA will  also consult
with the Commonwealth of Pennsylvania prior to finalizing its
decision.   EPA will publish a public notice in the Pocono Record
when it has finalized its decision for Operable Unit  Two of  the
Brodhead Creek Site.
                                          flR302059

-------