PB96-963115
                            EPA/AMD/R03-96/235
                            March 1997
EPA  Superfund
      Record of Decision Amendment:
      Rentokil, Inc.,
      (VA Wood Preserving Division)
      Richmond, VA
      8/27/1996

-------
                   RECORD OF DECISION AMENDMENT
                          RENTOKIL, INC.

                            Declaration
 Site Name  and  Location

 Rentokil,  Inc.
 Henrico County, Virginia

 Statement  of Basis  and  Purpose

 This decision  document  revises  the Record of Decision  (ROD)
 signed on  June 22,  1993,  for  the  Rentokil,  Inc. Site  (Site),  in
 Henrico County, Virginia.   The  revised  remedy was chosen in
•accordance with the requirements  of  the Comprehensive
 Environmental  Response, Compensation, and Liability Act of 1980,
 as amended (CERCLA),  42 U.S.C.  §  9601 et seg.r and, to the extent
 practicable, the National Oil and Hazardous Substances Pollution-
 Contingency Plan  (NCP), 40  C.F.R. Part  300.  This decision     	
 document explains the factual and legal basis for revising the
 remedy for this Site.   The  information  supporting this remedial
 action decision is  contained  in the  Administrative Record for
 this Site.

 The Virginia Department of  Environmental Quality concurs with the
 amended remedy.

 Assessment of  the Site

 Pursuant to duly delegated .authority, I hereby determine,
 pursuant to Section 106 of  CERCLA, 42 U.S.C. §9606, that actual
 or threatened  releases  of hazardous  substances,' pollutants or
 contaminants from this  Site,  if not  addressed by implementing the
 response action selected  in this  Record of  Decision, may present
 an imminent and substantial endangerment to public health,
 welfare, or the environment.

 Description of the  Selected Remedy

 This ROD•Amendment  revises  the  remedy previously selected by
 deleting the requirement  for  treatment  of "hot spots" at the
 Site.  This ROD Amendment will  be the final Record of Decision
 for the Site.   The  principal  threats associated with the "hot

-------
 spots" are contaminated soils containing hazardous substances.

 The amended remedy includes the following major components:

 (1)  Demolition of Existing Structures
 (2)  Removal of Unlined Pond
 (3)  Drum disposal
 (4)  Soil Consolidation Prior to Capping
 (5)  Construction of Multilayer Cap, Slurry Wall, and Dewatering
      System
 (6)  Sediment Excavation and Disposal
 (7)  Institutional Controls
 (8) Ground Water Monitoring

 Declaration of Statutory Determinations

 The selected remedy is protective of human health and the
 environment,  complies with Federal and State requirements that
 are legally applicable or relevant and appropriate to the
 remedial.action,  and is cost-effective.  This remedy utilizes
.permanent solutions and alternative treatment (or resource
 recovery)  technologies to the maximum extent practicable, and it
 satisfies the statutory preference for remedies that employ
 treatment that reduces toxicity,  mobility,  or volume as a
 principal element.

 Because this  remedy will result  in hazardous substances remaining
 onsite above  health-based levels,  a review will be conducted
 within five years after commencement of remedial action to ensure
 that the remedy continues to provide adequate protection of human
 health and the environment.   Such reviews will be conducted every
 five years thereafter until  EPA  determines that the cleanup
 levels set forth in this ROD have been achieved,  or that the
 hazardous substances remaining at the Site do not prevent
 unlimited use and unrestricted exposure at the Site.
 Thomas  C. Voltag/fio  S   ~.^>                     Date
 Director, Hazardowe-(Wa>fetf"*Management
 Region  III

-------
                         DECISION SUMMARY
A.   INTRODUCTION

     The Rentolcil Inc. Site  (the Site) is located at 3000 Peyton
Street at the intersection of Peyton Street and Ackley Avenue in
Henrico County, near Richmond, Virginia  (see Figure 1 - Regional
Location Map).   The Site is a former wood treating facility which
ceased operating in January 1990.  The land immediately
surrounding the Site is mostly open space/woodlands.  Nearby
development is comprised of light industrial, commercial, and low
density residential.  The Site and surrounding land are presently
zoned for light and general industry.  For more information on
the Site name,  Site location, Site description, Site history,
enforcement activities, and community participation activities
conducted prior to June 1993 refer to Sections A through C of the
Record of Decision issued on June 22, 1993.

     The U.S. Environmental Protection Agency  (EPA) is the lead  *
agency for response activities at the Site.  The Virginia
Department of Environmental Quality  (VDEQ) is the support agency
for this response action.

     On January 8, 1993, EPA released the original Proposed Plan
for the Site, requesting public comment on the alternatives
identified at that time to remediate contamination at the Site,
as well as the EPA preferred alternative.  Based on comments
received, EPA,  in consultation with VDEQ, selected the remedy to
clean up the Site on June 22, 1993 in the Record of Decision
("ROD").   The ROD describes the remedial action to be taken to
address contamination at the Site.  A description of the major
components of the remedy is provided in Section C, below.

     The requirement for treatment of hot spots has been deleted
because ground water modeling demonstrates that, following
construction of the cap and slurry wall and operation of the
dewatering system, contaminants in .the soil will be effectively
immobilized and will not move away from the Site in the
groundwater.   Thus, treatment of hot spots is unnecessary.

B.   Community Participatipn and Information Availability

     The Proposed Plan describing the amended remedy was released
to the public for comment on May 4, 1996.  The Proposed Plan was

-------
      FIGUHI  1
REGIONAL LOCATION MAT

-------
made available to the community in the information repositories
maintained at the EPA Docket Room in Region III and at the
Henrico County Municipal Reference and Law Library.  The. notice
of availability was published in the Richmond Times on May 4,
1996.  In addition, a public meeting was held on May 14, 1996 in
the Board of Supervisors Board Room at the Henrico County
Government Complex, Parham Road at Hungary Spring Road.  At this
meeting, representatives from EPA and the VDEQ answered questions
about conditions at the Site and the amended remedial alternative
preferred by EPA.  The public comment period on the Proposed.Plan
was held from May 4, 1996 to June 4, 1996.  A response to the
comments received during this period is included in the
Responsiveness Summary, which is part of this ROD Amendment.
These activities were undertaken by EPA as part of its public
participation responsibilities under Section 117(a) of the
Comprehensive Environmental Response, Compensation and Liability
Act of 1980 (CERCLA), and Section 300.435(c) (2) (ii) of the
National Oil and Hazardous Substances Pollution Contingency Plan
(NCP).
                                                                 •
     The Administrative Record for this Site' is maintained at the
following information repositories:

Henrico County Municipal                U.S. EPA Docket Room
 Reference and Law Library              Ms. Anna Butch  (3HW14)
County Government Complex               Region III
Parham Road at Hungary Spring Road      841 Chestnut Building
Richmond, VA 23228                      Philadelphia, PA 19107
Phone ft: 804 672-4780                   Phone ft: 215 566-3157

     The Administrative Record includes all documents upon which
the selection of the amended response action is based.  In
accordance with Section 300.825(a)(2) of the NCP,  this ROD
Amendment will become part of the Administrative Record.

C.   SUMMARY OP ORIGINAL REMEDY

The remedy selected in the June 1993 ROD contained the following
major components:

(1)  Demolition of Existing Structures

(2)  Removal of Unlined Pond

-------
 (3)   Excavation  and onsite  treatment  of  "hot  spots"

 (4)   Drum disposal

 (5)   Soil-Consolidation  Prior  to  Capping

 (6)   Construction of a Multilayer Cap, Slurry Wall, and
      Dewatering  System

 (7)   Sediment Excavation and Disposal

 (8)   Institutional  Controls to prevent residential use of the
      Site and use of the ground water.

 (9)   Ground water monitoring


D.    RATIONALE FOR  CHANGING REMEDY SELECTED IN 1993 ROD

     As part of  the remedial design, Rentokil, Inc. performed a  -
Value Engineering analysis to  evaluate the cost-effectiveness of"
the design.  Ground water modeling was performed as part of this
analysis to evaluate the movement of the existing
pentachlorophenol contaminated ground water plume.  This modeling
demonstrated that,  following construction of  the containment
system-cap and slurry wall-and operation of the dewatering
system, ccr.'-.aminants in  the soil will be effectively immobilized
and will n~- move away from the containment area in the ground
water.  E?« has  reviewed the ground water modeling and agrees
wit.h  its conclusions.

     Because the Site is underlain with a tight bedrock, keying
the slurry wall  into the bedrock near the perimeter of the Site
will form, a low permeability barrier.  Construction of a RCRA
Subtitle C cap- over the  area of the former wood treatment
facility will effectively prevent precipitation from permeating
through the- soil.   Finally, operation of the  dewatering system
will  remove whatever ground water is present  under the cap.

     Once all of the.presently existing ground water is removed,
the dewatering system will form an inward gradient of ground
water into the containment area.  Thus, contaminants in the
ground water will be prevented from dispersing away from the

-------
containment area.  At the time EPA issued the ROD, EPA required
treatment of soils in areas where the highest levels of
contamination were expected.  The findings from the ground water
modeling have demonstrated, however, that the containment system
designed for this Site would effectively prevent migration of the
existing contamination under the former wood treating a'rea and
that treatment of the "hot spots" is not warranted.  As a result,
EPA has evaluated and agreed to change the cleanup plan for the
Site, removing the requirement for treatment of "hot spots" prior
to construction of the cap and slurry wall.

E.   DESCRIPTION OF REVISED REMEDY

     The proposed amended remedy contains the following major
components (all of which were part of the originally selected
remedy):

(1)  Demolition of Existing Structures:  Existing structures at
     the Site will be demolished, decontaminated, and transported
     offsite for disposal.

(2)  Removal of Unlined Pond:  Surface water in the unlined pond
     will be removed, treated to safe levels through onsite
     carbon adsorption,  and discharged to North Run Creek.
     Approximately 70 cubic yards of K001 waste will be excavated
     and transported offsite to be incinerated (onsite
     dechlorination of waste will be performed if required prior
     to offsite incineration).  The unlined pond will then be
     closed in accordance with Virginia Hazardous Waste
     Management Regulations  (VHWMR).

(3)  Drum disposal:  Any drums excavated from the Fill Area will
     be disposed offsite.

(4)  Soil Consolidation Prior to Capping:  Site surface soils (0-
     2 feet in depth) which lie outside the area to be capped and
     exceed Site-specific cleanup levels (approximately 7,200
     cubic yards) will be excavated and placed in the area of the
     Site to be capped (generally, these soils occur in Wetlands
     A, B, and C).

     Soils in Wetlands A, B, and C will require dewatering prior
     to excavation.  Water from this process will be treated in

-------
     the onsite water treatment system (discussed below)  prior to
     discharge to North Run Creek.  Excavated wetlands will be
     revegetated with appropriate plant species as approved by
     EPA.

(5)   Multilayer Cap,  Slurry Wall, and Dewatering System
     Construction:  A multilayer RCRA Subtitle C cap will be
     constructed over approximately ten acres of the Site where
     contamination in the surface soil exceeds the Site-specific
     cleanup levels.   The cap will extend into the wetlands to
     the extent possible.  Wetlands lost due to capping will be
     replaced.   A slurry wall will be constructed around the
     perimeter of the cap to ensure the contamination is
     adequately contained.   A dewatering system will be
     constructed inside of  cap/slurry wall to keep groundwater
     within the slurry wall from building up and creating
     pressure on the  slurry wall and to treat any DNAPL
     collected.  Water from the system will be treated onsite by
     carbon adsorption and,  if necessary,  precipitation of
     metals.   Treated ground water will be discharged to  North  -
     Run Creek.  The  water  will be treated to levels that meet	
     the substantive  requirements of a Virginia Pollution
     Discharge Elimination  System (VPDES)  permit.

(6)   Sediment Excavation and Disposal:  Sediments in the  oxbow of
     North Run Creek  north  of the Site will be excavated  and
     disposed in the  area onsite to be capped.   Sediments in
     Talley's Pond and sediments previously dredged by the owner
     of the Pond will be sampled.  Sediments in or previously
     dredged from Talley's  Pond which exceed.the Site-specific
     cleanup goals will be  excavated,  treated onsite by Low
     Temperature Thermal Desorption (LTTD),  and disposed  offsite.

(7)   Institutional Controls:   Deed restrictions will be required
     to prohibit residential development  of the Site and/or use
     of the ground water.

(8)   Ground Water Monitoring:  Long-term ground water monitoring
     will be performed for  at least 30 years.

-------
F.   EVALUATION OF ALTERNATIVES

     The following summary discusses the performance of the
proposed cleanup plan in terms of the nine evaluation criteria,
noting how it compares to the originally selected remedy.  This
summary focuses only on the issue of how treating or not treating
the "hot spots" prior to capping affects the overall performance
of the cleanup plan since this is the only change proposed to the
remedy for the Site.  The nine criteria can be categorized into
three groups: threshold criteria, primary balancing criteria, and
modifying criteria.  The criteria associated with each category
are as follows:

     THRESHOLD CRITERIA

          Overall protection of human health and the environment

          Compliance with applicable or relevant and appropriate
          requirements (ARARs)

     PRIMARY BALANCING CRITERIA                               	

          Long-term effectiveness

          Reduction of toxicity, mobility, or volume through
          treatment

          Short-term effectiveness

          Implementability

          Cost

     MODIFYING CRITERIA

          Community acceptance

          State acceptance

     These evaluation criteria relate directly to the
requirements of Section 121 of CERCLA 42 U.S.C. § 9621 which are.
used to determine the overall feasibility and acceptability of
the remedy.  Threshold criteria must be satisfied in order for a

-------
remedy to-be eligible  for selection.  Primary balancing criteria
are used to-weigh major trade-offs between remedies.  Support
agency and community acceptance are modifying criteria which are
taken into account after public comment is received on the
Proposed Plan.

Overall Protection of  Human Health and the Environment

Both the original and  the revised cleanup plan provide overall
protection of human health and the environment.  Under both
plans, the area of contaminated soil will be .covered with a RCRA
Subtitle C cap, thereby eliminating any direct contact with the
soil.  Both plans are  also effective in protecting further
migration of contamination to the groundwater.

Compliance with ARARs

     The key ARARs associated with contaminated soil at the Site
are the RCRA Land Disposal Restrictions, 40 C.F.R. Part 268, that
limit the type and concentration of hazardous wastes that can be-
land disposed.  These  requirements are applicable when hazardous-
wastes regulated under RCRA are present at a Site and are being
placed in a land disposal unit or facility.  Virginia also has
similar land disposal  restrictions under its hazardous waste
management regulations.  Although the Site soils contain
hazardous wastes regulated under RCRA (i.e. F032, F034,  and F035
listed wastes which are drippage from wood treatment processes
which utilize PCP,  creosote, or arsenic solutions, respectively),
RCRA Land Disposal Restrictions for these F wastes have not yet
been promulgated.  The original cleanup plan, including the
provision of consolidating the wetland soil under the cap,
complied with all ARARs, including the RCRA land Disposal
Restrictions and the Virginia requirements.  The RCRA Land
Disposal Restrictions and equivalent state regulations would not
apply since soils from the "hot spots" would not be excavated and
treated under the revised cleanup plan.

Long-Term Effectiveness and Permanence

     The original cleanup plan provided a higher degree of long-
term effectiveness and permanence than- the revised remedy because-
the highest levels of contamination in the soil would have been
eliminated through treatment.  However,  the ground water modeling

-------
demonstrates that, because the hydrogeology of the area limits
migration of contaminated ground water, the cap and slurry wall
system, in conjunction with the dewatering system, will
effectively prevent further migration of contaminated ground
water at the Site because an inward gradient of ground water into
the Site will be created.  Therefore, the revised cleanup plan is
considered equally protective over the long term as the original
plan.  Both alternatives include treatment of the ground water
recovered by the dewatering system within the cap and slurry wall
and institutional controls prohibiting use of ground water and
residential development at the Site.  In addition, because high
levels of contamination in the soil remain and there have been
discussions concerning non-residential development of the Site
after construction of the remedy is complete, design and
construction of the cap will take into account future development
of the Site so that the cap will not be disrupted after
construction is completed.  Institutional controls will be
implemented to ensure that the integrity of the cap is
maintained.  These requirements ensure the long-term
effectiveness and permanence of the selected remedy.

Short-Term Effectiveness

     The revised cleanup plan would have fewer short-term impacts
than the original plan because the revised plan would take less
time to implement and will not create disruptions associated with
soil treatment (e.g. truck traffic, dust associated with
excavation, staging of the soil prior to and after treatment, and
the noise and emissions associated with the treatment system
itself).

Reduction of Toxicity, Mobility, or Volume through Treatment

     The original cleanup plan would reduce the toxicity and
volume (though not mobility) of Site contaminants through
treatment to? a greater extent than the revised plan because the
highest levelsr of soil contamination would have been treated and
removed usincp low temperature thermal desorption.  This added
reduction would not, however, increase the overall effectiveness
because, as discussed previously, the ground water modeling shows
mobility of contaminants in the ground water away from the Site
would be- the same under either action.

-------
 Implementability

     Overall, both the original cleanup plan and the revised plan
 can be readily implemented, however, the revised plan is easier
 to implement because on-site treatment of soils is not required.
 Regarding the original cleanup plan, bench-scale treatability
 testing conducted during the pre-design phase has shown that low
 temperature thermal desorption can meet the health-based cleanup
 levels for organics set forth in the ROD.  If treatment standards
 for F032, F034, and F035 listed wastes are promulgated prior to
 cleanup at the Site,.the contaminated soil would have to be
 treated to these new levels.  Although low temperature thermal
 desorption is likely to meet the new levels for organic
 contaminants, treatment levels established for arsenic could be a
 problem because arsenic is not effectively removed in the low
 temperature thermal desorption process.

 Cost

     The .cost of the revised cleanup plan is approximately
 $12,000,000 while the present estimate of the cost of the     	
 original cleanup plan is approximately $22,500,000.

 State Acceptance

     VDEQ served as the lead agency for the Commonwealth of
Virginia for the C2RCLA response activities at the Rentokil, Inc.
 Site.  VDEQ has raviewed the remedial alternatives under
 consideration for the Site and has provided EPA with technical
 and administrative requirements for the Commonwealth of Virginia.
VDEQ has reviewed the amended ROD and concurs with the amendment
as discussed below.

Community Acceptance

     The Proposed Plan to Amend the ROD was released on May 4,
 1996 to solicit public comment regarding the proposed revised
 cleanup plan. . At that time a 30-day comment period was opened.
A public meeting on the Proposed Plan was held on May 14,  1996 at
 the Henrico County Government Complex.  Although comments were
 raised at the public meeting, no objections were voiced.  The
comments are summarized in the Responsiveness Summary which is
 included in this ROD Amendment.  No written comments were

-------
submitted to EPA during the public comment period.

G.   AMENDED REMEDY

     Following review and consideration of the information in the
Administrative Record file, the requirements of CERCLA, the NCP,
and public comment, EPA has selected the revised cleanup plan as
the .selected remedy.  Specifically, the selected remedy, which
satisfies Section 121 of CERCLA, 42 U.S.C. §9621 includes:

(1) Existing Structures

     Demolition, decontamination, and offsite disposal of the
     existing structures at the Site.

(2) Unlined Pond

     Excavation and offsite incineration of approximately 70
     cubic yards of K001 waste  (including onsite dechlorination
     if the level of dioxins/furans in the waste would cause a
     violation of the incinerator's RCRA"permit if incinerated	
     without prior treatment).

     Removal and onsite carbon adsorption treatment of the
     surface water in the unlined pond with discharge to North
     Run Creek; and closure of the 'unlined pond.

(3) Soil

     Movement of Site surface soils  (0-2 feet--approximately
     7,200 cubic yards) which lie outside the area to be capped,
     and which exceed any Site-specific cleanup level, to the
     area of the Site to be capped (generally these soils occur
     in Wetlands A, B, and C).

     Offsite disposal of all drums excavated from the Fill Area.
     Dewatering of contaminated soil in Wetlands A, B, and C
     prior to excavation, and treatment of the water in the
     onsite water treatment system prior to discharge to North
     Run Creek.  The discharge of treated water will meet the
     substantive requirements of a VPDES permit.  Planting of
     excavated wetlands with wetland vegetation as approved by
     EPA.  Mitigation of wetland loss due to capping with

                                10

-------
     creation of wetlands of equal or better value, as approved
     by EPA-.

 (4) Containment

     Construction of a RCRA Subtitle C cap over the Site where
     the surface soil exceeds the Site-specific cleanup levels
     stated above and as far into the wetlands as possible.

     Construction of a slurry wall around the perimeter of the
     cap.  Construction of a dewatering system inside of
     cap/slurry wall to produce an intragradient condition with
     onsite treatment of ground water by carbon adsorption and,
     if necessary, precipitation of metals; discharge of treated
     ground water to North Run Creek;

 (5) North Run Creek and Talley's Pond

     Excavation and onsite disposal of sediments in the oxbow ofr
     North Run Creek north of the Site.

     Sampling of sediments in Talley's Pond and sediments
     previously dredged by the owner of the Pond.  Excavation,
     treatment,  and offsite disposal of the sediments in or
     previously dredged from Talley's Pond which exceed the Site-
     specific cleanup goals.

 (6) Institutional Controls

     Implement institutional controls to prohibit residential
     development of the Site and use of ground water at the Site,

 (7) Ground Water Monitoring

     Long-term ground water monitoring (at least 30 years).
Performance Standards

     The selected remedy addresses all of the contaminated media
at the Site.  By instituting all of these components, the Site  .
risks'will be reduced to witihin EPA's acceptable risk range.  The
performance standards for the major components of the selected

                                11

-------
remedy include Che following:

(1)  Existing Structures

      To reduce the risk to human health and the environment via
     the exposure pathways attributed to the existing structures
     on the Site, the concrete drip pad, holding pond,  shop,
     office,  and shed will be demolished, cleaned of any residual
     soil,  decontaminated, and disposed of in accordance with
     Part VIII of the Virginia Solid Waste Management Regulations
     (VSWMR)  and as approved by EPA.   Decontamination and
     disposal must also meet the requirements of 40 C.F.R. Part
     268.  Waste water generated during the decontamination will
     be collected, treated and discharged to North Run Creek.
     The discharge of treated water will meet the substantive
     requirements of a VPDES permit.

(2)  Unlined Pond

      To reduce the risk to human health and the environment via-
     the exposure pathways attributed to the unlined pond,
     surface water in the pond will be removed, treated, and
     discharged to North Run Creek.  Closure and post closure of
     the unlined pond will be performed in accordance with the
     VHWMR.  The discharge of treated water from the unlined pond
     will meet the substantive requirements of a VPDES permit.

      To reduce the risk to human health and the environment via
     the exposure pathways attributed to the K001 waste,
     approximately 70 cubic yards of K001 waste will be excavated
     from the unlined pond and incinerated (the Best Demonstrated
     Available Technology for K001 waste) at an offsite facility
     approved by EPA and operating in accordance with,  among
     other things, 40 C.F.R. Part 264, Subpart 0.  If the level
     of dioxins/furans in the K001 waste exceeds the level which
     the incinerator is permitted to accept,  the K001 waste will
     be dechlorinated onsite to bring the level of dioxins/furans
     down to a level at or below that specified in the
     incinerator's permit prior to shipment.

(3)  Soil

      To reduce the risk to human health and the environment via

                                12

-------
     the exposure pathways attributed to  the  surface  soil  in
     areas beyond the extent  of the  cap that  exceed the  cleanup
     levels of 5.1 mg/kg carcinogenic PAHs, 48  mg/kg  PCP,  or 33
     mg/kg arsenic,  approximately 7,200 cubic yards of soil will
     be moved to the area to  be capped prior  to construction of
     the cap.   Excavated wetlands will be restored  to the
     appropriate contours and revegetated with  a diverse
     community of indigenous  species as approved by EPA.

(4)  Containment

      To reduce the  risk to human health  and  the environment via
     the exposure pathways attributed to  the  surface  soil  at the
     Site,  a cap will be constructed over a portion of the Site
     which meets the requirements of RCRA Subtitle  C, and
     regulations promulgated  thereunder,  particularly the  closure
     requirements at 40  C.F.R.  Part  264,  Subparc N.   Because the
     soils in  areas  with the  highest levels of  contamination
     would remain under  the cap,  the design and construction of
     any planned development  of the  Site  must be incorporated
     into the  design and construction of  the  cap to prevent   	
     exposure  to these soils.   The cap will be  approximately 11.5
     acres in  size.   The cap  is not  expected  to cover all  of the
     contaminated portions of Wetlands A,  B,  and C.   The loss of
     wetlands  through capping will be mitigated by  the creation
     of  wetlands of  equal or  better  value.  All wetland
     restoration and monitoring must be approved of by EPA.

      :--  reduce the  risk to human health  and  the environment via
  .   tha  exposure pathways attributed to  the  migracion of  ground
     water from the  Site,  a slurry wall will  be constructed
     around the perimeter of  the cap and  a dewatering system will
     be  constructed  within the slurry wall to create  an
     intragradient condition.   The dewatering system  will  consist
     of  two vertical caissons constructed to  the bedrock with
     horizontal laterals installed on top of  the hardpan and on
     top of the bedrock.   Construction techniques will be
     implemented to  prevent the migration of  ground water  or
     DNAPLs along the caissons through the hardpan.   The
     horizontal laterals will be installed with clean washed
     gravel or gravel packs.   The ground  water  collected in the
     horizontal laterals will be treated  via  carbon adsorption
     and,  if necessary,  precipitation of  metals,  pr.i.r to

                               13

-------
     discharge to North Run Creek.   The ground water will  be
     treated to comply with the substantive requirements of a
     VPDES permit'for discharge to  North Run Creelc.   The carbon
     from the carbon adsorption will be regenerated  at an  offsite
     facility approved by EPA.   All sludges generated will be
     disposed of at an offsite  facility approved by  EPA.

(5)  North Run Creek and Talley's Pond

      To reduce the risk to human health and the environment via
     the exposure pathways attributed to sediments in the  oxbow
     of  North Run Creek north of the Site>  sediments exceeding
     the cleanup levels of 5.1  mg/kg carcinogenic PAHs,  48 mg/kg
     PCP,  and/or 33 mg/kg arsenic will be moved to the area of
     the Site to. be capped.

      To ascertain that the remedy  is protective of  human  health
     and the environment,  the sediments in Talley's  Pond and the
     sediments that were previously dredged by the owner of
     Talley's Pond will be sampled  to determine whether they
     exceed any cleanup levels  for  the Site.  If the sediments	
     exceed a cleanup level (s), the sediments will be excavated,,
     treated,  and disposed of at an offsite facility approved  of
     by  EPA.

(6)  Institutional Controls

      To restrict access to the soil at the Site,  institutional
     controls prohibiting residential development at the Site
     will be implemented.

    .  To restrict access to the contaminated ground  water  under
     the Site,  institutional controls prohibiting use of the
     ground water will- be implemented.
(7)  Ground Water Monitoring

      To determine if MCLs are being met at the boundary of the
     Site,  long-term ground water monitoring will be performed
     for.at least thirty years.  The ground water"monitoring will'
     include sampling for arsenic,  chromium,  copper,  zinc,  PAHs,
     and PCP.   The appropriate number and location of the

                               14

-------
     monitoring wells will be determined during the design phase.

     EPA may modify or refine the selected remedy during the
remedial design and construction.  Such modifications or
refinements, if any, would generally reflect results of the
engineering design process.

H.   DOCUMENTATION OF SIGNIFICANT CHANGES

     The Proposed Plan, which identified the revised cleanup plan
as EPA's preferred alternative for the Site, was released for
public comment on May 4, 1996.  EPA has reviewed the verbal
comments expressed at the May 14, 1996 public meeting (no written
comments were submitted to EPA during the 30-day public comment
period which ended June 4, 1996)  and determined that no
significant change to the remedy identified in the Proposed Plan
is necessary.
                                15

-------
                       RENTOKIL, INC. SITE
                    HENRICO  COUNTY,  VIRGINIA

                     RESPONSIVENESS  SUMMARY
                           August 1996
     This Responsiveness Summary documents public concerns and
comments expressed during the public comment period.  The Summary
also provides EPA's responses to those comments.  The information
is organized as follows:

     Overview

     Summary of Comments and Questions Expressed During Public
     Meeting and EPA Responses

I.   Overview

     The 30-day public comment period for the amended remedy for.-
the Rentolcil, Inc. Site began on May 4, 1996 and ended on June 4,
1996.  To facilitate commenting, EPA'held a public meeting at the
Board of Supervisors Board Room at the Henrico County Government
Complex.on May 14, 1996.

     At the meeting, EPA discussed the ground water modeling
performed for the Site as part of the Value Engineering analysis
during the design phase.  EPA also presented the Proposed Plan
for deleting treatment of "hot spots" at the Site.  EPA explained
that the ground water modeling indicated that the "hot spots"
treatment had virtually no impact on the ground water
contamination at the Site.  EPA also explained that the remainder
of the previously selected.remedy would be implemented as
originally planned, including:

          demolition of existing structures on the Site;

          removal of the unlined pond;

          drum disposal;

          soil consolidation prior to capping;

          construction of multilayer cap, slurry wall, and
          dewatering system;

-------
          sediment excavation and disposal;

          institutional controls; and

          -long-term ground water monitoring.

     The May 14, 1996 public meeting also provided the
opportunity for the public to ask questions and express opinions
and concerns.  During the meeting, residents expressed concerns
on the limits of sampling down stream of the Site, the depth-and
width of the slurry wall, the possibility of re-use of the Site,
the capping of wells where public water was installed, the length
of monitoring the ground water at the Site, and who is
responsible to pay for the cleanup of the Site.

The comments and questions expressed during that meeting and
EPA's responses to those comments and questions are described in
the following summary-

II.  Summary of Comments and Questions Expressed During Public
Meeting and EPA's Responses

Questions presented at the May 14, 1996 public meeting are
summarized briefly in this section and are grouped according to
subject.  The EPA response follows each question presented.

1.    A resident asked if the sediments in the wetland on the
other side of Ackley Avenue and down stream of the wetland were
sampled for contamination from the Site.

EPA Response:  The wetland on the other side of Ackley Avenue and
the down stream areas were not sampled for the reason indicated
below.   As shown on Figure-1, Wetland C is located at the
southwest corner of Ackley Avenue and Peyton Street,  across
Peyton Street from Wetland B.  The wetland the resident refers to
is at the southeast corner of Ackley Avenue and Peyton Street,
across from Wetland C.  Wetlands B and C are connected by two 18"
culverts under Peyton Street.  Surface runoff discharges from the
Site through a ditch to Wetland B, where it is retained and
discharges to Wetland C when flow is high.  Ditches have been
artificially cut into Wetland C approximately 60 feet south of
the outlet of each culvert.   A ditch parallel to the south side
of Peyton Street carries runoff from Wetland C to the east and

-------
                    EXPLANATION: ,
                    — «• »ImrrmiiMni SliMm
                    —"—— Contour lm*v«l
                    ——AMM oalMMM LoccK
                         COAMM*)
                     NOTfcS:
                     I. Co.t|guf Intofvri «wo IMI.
                      NW«NM« (Ml.
                                 200 FMI
                          KALE
            FIGURE 1
 lRFArpA^ ROWING PRIMARY
SURFACE WATER DRAINAGE AREAS

-------
 ultimately to a 24" culvert under Ackley Avenue.   Because the
 invert of the 24" culvert is about 2 feet above the flow line of
 the south ditch arid the normal elevation of Wetland C,  Site-
 related runoff waters are retained within Wetland C.

 2.    A resident asked if the slurry wall proposed to be
 constructed at the perimeter of the Site would be 25-foot deep.

 EPA Response!  The slurry wall will be keyed into the granite
 bedrock,  which varies between 25 to 30 feet deep.

 3.    A resident asked how do we know that contamination will  not
 escape through the slurry wall.

 EPA Response:  B:i3ed on actual treatability testing of  the Site
 soil with differ^t types of bentonite,  permeabilities  in the 10"
 7 to 10"8 cm/sec vange can be achieved.   Also,  once the area
 within the slurry wall and cap is drained,  an inward gradient of
 ground, water will be created.  At that time,  the  level  of ground?
 water in  .the area outside the slurry wall will be higher than the
•level within the slurry wall.  As such,  any flow  of ground water"
 through the. slurry wall would be into the slurry  wall/cap area
 rather than to the outlying aquifer.

 4.    A resident asked what happens to the soil that is  excavated
 to  install the slurry wall.

 EPA Response:  Most of the excavated soil from the slurry wall
 trench will be used to form the slurry wall.   The slurry wall mix
 contains  only 1% bentonite.   If there are any soils remaining
 after construction of the slurry wall,  they will  also be
 consolidated onto the surface of the Site prior to construction
 of  the cap.

 5.    A resident asked how long will the site remain contaminated.

 EPA Responger  It is conceivable that the organic contamination
 (i.e.,  pentachlorophenol as well as the PAHs associated with
 creosote),  will biodegrade over time.   In addition,  some
 scientists theorize that DNAPLs move more freely  when they are
 taken out of the water phase, such as what will occur when the
 dewatering system Bowers the ground water level within  the area
 of  the slurry wai, and cap".   If the DNAPLs do move more freely, a

-------
substantial amount of contamination will be collected in the
dewatering system.  The inorganic contamination  (i.e., arsenic,
copper, chromium,'and zinc associated with the CCA and CZA
treatment solutions) might never be removed since they do not
biodegrade and they tend to strongly adhere to soil particles.
Although the purpose of this ROD Amendment is to delete treatment
of the "hot spots", EPA believes the Site would remain
contaminated for just as long as under the original ROD since the
original ROD also did not include treatment of all of the soils
at the Site.

6.   A resident asked if it will be safe to allow people to work
at the Site after remediation is completed.

EPA Response:  It will be safe for people to work at the Site
after the cap is constructed since the cap will prevent direct
exposure to the Site contaminants.

7.   A resident asked whether the $10,500,000 difference between'
the cost of the original cleanup plan and the cost of this
'revised cleanup plan is due entirely to the excavation and
treatment of the "hot spots."

EPA Response:   Most of the cost difference is associated with
excavation, sampling, and staging the "hot spot" soil requiring
treatment.  At the time of the original ROD, the amount of soil
requiring treatment was estimated to be 5,150 cubic yards.  Based
on more precise measurements during the design, that amount had
increased to 12,000 cubic yards.  Another large portion of the
cost difference is the cost of treating surface water during
remediation.  It should be noted that the cost of treating
surface water during remediation was not included in the original
cost estimate.

8.   A resident asked whether their domestic wells should be
abandoned where public water was made available.

E;PA Responses. • Since the ground water contamination did not reach
these wells, there is no reason to abandon these wells.  However,
the monitoring wells installed during the investigation of the
Site should be abandoned in accordance with Henrico County
requirements.             .

-------
 9.   A resident asked how additions/modifications or new
 construction is handled.
                  *
 EPA Response,:  Rentokil, Inc. is legally responsible to maintain
 the integrity of the cap.  Since contamination will remain at the
 Site after remediation is complete, a review of the Site will be
 performed at least every five years to determine if the remedy is
 still protective of human health and the environment.  This will
 include a review of whether the cap is still being maintained.

 10.  A resident asked who will make sure the contamination is
 still being contained at the Site.

 EPA Response;  As stated in the response to Number 9 above, a
 review of the Site will be performed at least every five years to
 assure that the remedial action remains protective of human
 health and the environment, including whether the cap is being
 maintained.  An analysis of whether the ground water
 contamination is being contained will be part of this review.
                                                                •
 11.  A resident asked why the long-term ground water monitoring
 extends for only for 30 years.

 EPA Response:  The original ROD actually states that the long-
 term ground water monitoring shall be performed for at least 30
years.  .The period over which a remedial action requires
maintenance and/or operation (the period of performance)  is an
 important factor in present worth analyses.  It is EPA policy
 that the period of performance for remedial action alternatives
requiring perpetual care should not be costed beyond thirty
years.   Therefore,  the 30-year period is the timeframe EPA uses
 in order to compare differing remedial alternatives to cleanup
Superfund sites.

As stated in the response to Number 9 above, a review of the Site
will be performed at least every five years to assure that the
remedial action remains protective of human health and the
environment.  -In accordance with Paragraph IX of the Consent
Decree between EPA and Virginia Properties, Inc. (VPI),  VPI shall
conduct any studies and investigations as requested by EPA in
order to permit EPA to conduct reviews at least every five years.
Further,  the Consent Decree states that if the Regional
Administrator,  EPA Region III,  or his/her delegate determines

-------
that information received, in whole or in part, during the review
conducted indicates that the Remedial Action is not protective of
human health and tihe environment, VPI shall undertake any further
response actions EPA has determined are appropriate and that are
not barred by the Covenant Not to Sue.  Should EPA determine that
the remedy selected for the Site is no longer protective of human
health and the environment, EPA shall direct VPI to perform
additional response actions.

12.  A resident asked who is responsible for the Site
contaminants after the buildings have outlasted their longevity?

EPA Response:  As a requirement of the Consent Decree, VPI shall
record a certified copy of the Consent Decree with the Recorder's
Office (or Register of Deeds or other appropriate office),
Henrico County, Virginia.  Thereafter, each deed, title, or other
instrument of conveyance for property included in the Site shall
contain a notice stating that the property is subject to this
Consent Decree...and shall reference the recorded location of the
Consent Decree and any restrictions applicable to the property
under this Consent Decree.  The obligations of VPI with respect ^
to the provision of access and the implementation of
institutional controls shall be binding upon VPI and any and all
persons who subsequently acquire such interest.

13.  A resident asked whether the ground water contaminants would
move while the slurry wall is being constructed.

EPA Response:  Contaminant movement has been slow to date and it
is unlikely that contaminants would move beyond their present
location because of construction of the slurry wall.
Construction of a slurry wall is a very dynamic operation.  As
the trench is being excavated, the previously excavated soil is
being mixed with bentonite, tested, and then re-deposited back
into the trench.  Testing of the mixture of soil and bentonite
must be done prior to re-depositing back into the trench to make
sure the mixture meets or exceeds the performance standards of
permeability^  As a precaution, ground water monitoring is
performed during the construction of the entire remedy to monitor
for accelerated movement of the ground .water plume.

14.  A resident asked whether Henrico County taxpayers are paying
for the Site cleanup.

-------
EPA Response;  Through the Consent Decree between EPA and VPI,
VPI agreed to pay all costs associated with the Site cleanup
including the construction costs, the engineering costs, and the
oversight costs incurred by EPA, their contractors, and VDEQ.

15.  A resident made a comment that she supported the idea of re-
using the Site by constructing buildings on top of the cap which
could generate both jobs and tax revenues for Henrico County.

EPA Response:  Comment noted.

-------