EPA  Superfund
       Record of Decision:
       Goldisc Recordings, Inc.,
       Holbrook, NY
       9/29/1995
                                 PB95-963813
                                 EPA/ROD/R02-95/259
                                 March 1996

-------
        RECORD OF DECISION



         Operable Unit  1



       Goldisc Recordings



Holbrook, Suffolk County,  New York

-------
              DECLARATION FOR THE RECORD OF DECISION

SITE NAME AND LOCATION

Goldisc Recordings
Holbrook, Suffolk County,  New York

STATEMENT OF BASIS AND PURPOSE

This Record of Decision (ROD)  documents the U.S. Environmental
Protection Agency's (EPA's) selection of the remedial action for
the Goldisc Recordings Superfund site in accordance with the
requirements of the Comprehensive Environmental Response,
Compensation and Liability Act of 1980, as amended (CERCLA), 42
U.S.C. §9601 et seq. and to the extent practicable the National
Oil and Hazardous Substances Pollution Contingency Plan  (NCP), 40
CFR Part 300.  An administrative record for the site, established
pursuant to the NCP, 40 CFR 300.800, contains the documents that
form the basis for EPA's selection of the remedial action (see
Appendix III).

The New York State Department of Environmental Conservation
(NYSDEC) has been consulted on the planned remedial action in
accordance with CERCLA §121(f), 42 U.S.C. §9621(f), and  it
concurs with the selected remedy (see Appendix IV).

ASSESSMENT OF THE SITE

Actual or threatened releases of hazardous substances from the
site, if not addressed by implementing the response action
selected in this ROD, may present an imminent and substantial
endangerment to public health, welfare, or the environment.

DESCRIPTION OF THE SELECTED REMEDY

The selected remedy pertains to the first of two operable units
for the site and addresses the contaminated sediments and soils
located on the Goldisc property.

The major components of the selected remedy include the
following:

•    Excavation via a vacuum truck and off-site disposal of
     approximately 56 cubic yards of sediments and soils from the
     six dry wells in that portion of the site designated as Area
     of Environmental Concern 2 and drywell DW-2 in Area of
     Environmental Concern 14;

•    Excavation and off-site disposal of approximately 215 cubic
     yards of surface soils within Area of Environmental
     Concern 8;

-------
     Abandonment of the on-site production well including
     excavation and off-site disposal of sediments and soils from
     the well vault; and

     Taking steps to secure the placement of a deed restriction
     be placed on the property to limit it to a nonresidential
     use.

Although a groundwater investigation was included in the first
operable unit investigation, it has been determined that
selection of a groundwater remedy should be deferred until
additional groundwater monitoring data can be collected and
evaluated.  A remedy for groundwater will be selected in a second
operable unit ROD subsequent to additional groundwater
monitoring.

DECLARATION OF STATUTORY DETERMINATIONS

The selected remedy meets the requirements for remedial actions
set forth in CERCLA §121, 42 U.S.C. §9621:  (1)  it is protective
of human health and the environment; (2) it attains a level or
standard of control of the hazardous substances, pollutants and
contaminants, which at least attains the legally applicable or
relevant and appropriate requirements (ARARs)  under federal and
state laws; (3)  it is cost-effective; (4) it utilizes permanent
solutions and alternative treatment (or resource recovery)
technologies to the maximum extent practicable;  and (5) it
satisfies the statutory preference for remedies that employ
treatment to reduce the toxicity, mobility, or volume of the
hazardous substances, pollutants or contaminants at a site.

Although this alternative would result in no contamination
remaining on-site above health-based levels for the current
property use, the remedy does not allow for unlimited use and
unrestricted exposure; therefore, a review of the remedial action
pursuant to CERCLA §121(c), 42 U.S.C. §9621(c),  will be conducted
five years after the commencement of the remedial action to
ensure that the remedy continues to provide adequate protection
to human health and the environment.
Jeanne M. Fox /   ^ r /^f\7                Date
Regional Administrate

-------
              RECORD OF  DECISION
               DECISION  SUMMARY

             Goldisc Recordings

      Holbrook,  Suffolk  County, New  York
United States Environmental Protection Agency
                  Region II
              New York,  New York
                September 1995

-------
                        TABLE OF CONTENTS

Section                                                     Page

SITE NAME, LOCATION AND DESCRIPTION 	   1

HISTORY AND ENFORCEMENT ACTIVITIES 	   1

HIGHLIGHTS OF COMMUNITY PARTICIPATION 	   3

SCOPE AND ROLE OF OPERABLE UNIT 	   3

SUMMARY OF SITE CHARACTERISTICS 	   3

SUMMARY OF SITE RISKS 	   8.

REMEDIAL ACTION OBJECTIVES 	  11

DESCRIPTION OF REMEDIAL ALTERNATIVES	  12

SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES 	  13

SELECTED REMEDY 	  16

STATUTORY DETERMINATIONS 	 	  17

DOCUMENTATION OF SIGNIFICANT CHANGES 	  19



ATTACHMENTS

APPENDIX I.    FIGURES
APPENDIX II.   TABLES
APPENDIX III.  ADMINISTRATIVE RECORD INDEX
APPENDIX IV.   STATE LETTER OF CONCURRENCE
APPENDIX V.    RESPONSIVENESS SUMMARY

-------
SITE NAME, LOCATION AND DESCRIPTION

The Goldisc Recordings Superfund site (Site)  is located at the
northeast corner of Veterans Memorial Highway and Broadway Avenue
in the Village of Holbrook, Town of Islip,  New York.   The 34-acre
Site consists of two one-story buildings that occupy six acres,
three acres of pavement surrounding the buildings,  and twenty-
five acres of undeveloped land (see Figure 1 for the general Site
vicinity).  Current zoning at the Site is commercial/industrial.
The area surrounding the Site is primarily residential and mixed
forest, with some commercial and light industrial development.
The Village of Holbrook has an estimated population of 20,525.
The Site is bordered to the north and east by mixed forest, to
the south by Veterans Memorial Highway, and to the west by
Broadway Avenue (see Figure 2 for the Site layout).

A municipal water supply wellfield, which provides drinking water
for the Suffolk County Water Authority (SCWA),  is located
approximately 1,200 feet south of the Site on Church Street.  All
residents of the Town of Islip depend on groundwater as their
potable water supply.  The closest dwellings are located about
700 feet north of the Site.  A New York State and federally
regulated wetland is located approximately one-half mile south of
the Site.  A Sunoco gasoline station is located on the southeast
corner of Veterans Memorial Highway and Broadway Avenue, just
south of the Site.  Soil and groundwater remediation systems are
currently in operation at the station, to address a release of
petroleum product to the groundwater.

SITE HISTORY AND ENFORCEMENT ACTIVITIES

From 1968 to 1990, the two buildings were occupied by several
different companies that generated and stored hazardous
substances on the Site.  These companies included Goldisc
Recordings, Inc.  (Goldisc), which produced phonographic records;
ElectroSound Group, Inc.  (Electrosound), a company that
manufactured audio visual and optical devices; and Genco Auto
Electric, Inc. (Genco), which rebuilt automotive engine parts.
The First Holbrook Company (First Holbrook) owned the property
from 1973 to 1985.  In 1985, the Red Ground Corporation became
the owner of the property.  In 1989, Red Ground Corporation sold
the property to a partnership named Red Ground Company.  The two
tenants occupying the buildings since 1990 are dry goods
merchants and do not perform any manufacturing.

The substances known to have been disposed of on the Site between
1968 and 1990 include wastewater from the various production
processes, waste oils, metals, solutions containing high
concentrations of xylene and trichloroethylene, and other
degreasing agents.  These substances were reportedly discharged
to the environment through dry wells, leaching pools, storm
drains, and leaking storage containers located around the
buildings.

-------
Since the late 1970s, the Suffolk County Department of Health
Services  (SCDHS), the New York State Department of Environmental
Conservation  (NYSDEC), and EPA have conducted various inspections
and environmental protection enforcement activities at the Site.
In 1978, a representative from the SCDHS inspected the Site and
noted stains, puddles, and leaking drums suspected to be related
to industrial wastes.  In the early 1980s, the SCDHS collected
samples from leaching pools, storm drains, and cesspools located
on the Site.  Laboratory analyses of the samples revealed
violations of New York State Groundwater Effluent Guidelines.
Between 1981 and 1983, laboratory analyses of groundwater samples
collected from monitoring wells located on-site revealed elevated
levels of solvents and metals, including: trichloroethane,
trichloroethylene, tetrachloroethylene, lead, nickel, chromium,
and silver.  Analyses of samples obtained from the Church Street
wellfield showed concentrations of tetrachloroethylene slightly
exceeding the state and federal Maximum Contaminant Level (MCL)
of 5 parts per billion (ppb) for public drinking water.  Based on
these findings, the Site was proposed for inclusion on the
National Priorities List (NPL) in October 1984 and was added to
the NPL in June 1986.

In 1988, DEC entered into an Administrative Order on Consent
(AOC)  with two of the potentially responsible parties (PRPs),
namely,  First Holbrook and ElectroSound.  The AOC required the
two PRPs to conduct an RI at the Site.  The RI (Phase I RI)  was
conducted in 1988 and included the investigation of nineteen
areas of potential contamination.  Groundwater and soil samples
were collected and analyzed to determine the nature and extent of
contamination in these areas.  Elevated levels of lead and
tetrachloroethylene were found in groundwater samples.  Soil
samples were found to contain elevated levels of several metals,
volatile organic compounds,  and semi-volatile organic compounds.

Based on a review of the results, EPA and DEC determined that
additional information was necessary in order to better define
the extent of contamination at the Site.  In late 1990, DEC
requested that EPA take over as lead agency for the Site.  EPA
notified First Holbrook,  ElectroSound, Genco, and Red Ground of
their potential liability at the Site and requested they finance
or undertake the continuing RI/FS.  Subsequently, in 1991, EPA
entered into an AOC with First Holbrook and ElectroSound.  This
AOC specifically required the PRPs to conduct a supplemental
RI/FS (or Phase II RI/FS).   A subsequent notification of
potential liability was issued on August 17, 1995 to an
additional seven individuals who are partners of First Holbrook.

-------
HIGHLIGHTS OF COMMUNITY PARTICIPATION

The RI, FS, and Baseline Risk Assessment reports, as well as the
Proposed Plan, for the Site were released to the public for
comment on August 26, 1995.  These documents were made available
to the public at information repositories located at the Islip
Town Hall and Sachem Public Library.  The notice of availability
for the above-referenced documents was published in the Suffolk
County News on September 7, 1995 and a press release was issued
on August 30, 1995. The public comment period on these documents
was held from August 26, 1995 to September 26, 1995.

On September 11, 1995, EPA conducted a public meeting at the
Islip Town Hall West Auditorium to inform local officials and
interested citizens about the Superfund process, to review
current and planned remedial activities at the Site, and to
respond to any questions from area residents and other attendees.

Responses to the comments received at the public meeting and in
writing during the public comment period are included in the
Responsiveness Summary  (see Appendix V).

SCOPE AND ROLE OF OPERABLE UNIT

It was EPA's original intention to supplement previous data
collected under state and county investigations in order to
address sediment, soil and groundwater contamination at the Site.
However, due to circumstances which occurred as the Phase II
RI/FS progressed, EPA and DEC have decided to defer the decision
regarding groundwater remediation.  The MCL for nickel, which is
the primary contaminant at the Site, was remanded in February
1995.  In addition, the concentration of nickel has fluctuated in
the groundwater.  While the Church Street wellfield has been
impacted by nickel contamination, recent data indicate that
nickel concentrations have dropped below the current (July 10,
1995) Interim Health Advisory level of 100 ppb.  As a result, EPA
and DEC decided to postpone the selection of a remedy for the
groundwater until additional information and data on the nickel
contamination in the groundwater are obtained.  This remedy will
be documented in a second operable unit Record of Decision (ROD).

The selected remedy described in this document addresses the
contamination associated with Site sediments and soils.

SUMMARY OF SITE CHARACTERISTICS

Under the direction of EPA, the PRPs1 contractor, ERM-Northeast,
implemented the Phase II RI to characterize further the sediments
and soils, and groundwater at the Site.  The intent of the study
was to fill data gaps identified during review of the DEC Phase  I
RI report.  Sediments and soils data collected as part of both

-------
the Phase I and Phase II RI/FS are provided below, as are data
for groundwater.

Sediments. Soils. Storm Drains, and Dryvells

The Phase I RI identified 19 separate soil Areas of Environmental
Concern  (AEC)  (see Figure 2), which included storm drains,
drywells, a sump, drum storage areas, sanitary discharge areas, a
transfer pad area, and a former production well.  Phase I
sampling of AECs 3, 4, 6, 7, 9, 17, and 18 determined that these
areas had not been significantly impacted.  Therefore, no
additional Phase II sampling was performed in these areas.
Likewise, Phase I sampling adequately defined the impacts to AECs
2, 11, and 12.  Therefore, no additional Phase II sampling was
performed in these areas.

The Phase I data indicated that the highest levels of
contamination were found in AEC 2 (see Table 1).  AEC 2 consists
of an interconnected system of six drywells which allegedly
received direct discharges from the Goldisc building, as well as
spillage from a drum storage area.  Chromium was detected in
sediments and soils at levels ranging from 30 parts per million
(ppm)  to 195 ppm.  Nickel was found at levels ranging from 25 ppm
to 1,120 ppm.

Phase I data indicated the presence of total petroleum
hydrocarbons (TPHCs) ranging from 31 ppm to 2,980 ppm in surface
soils in AEC 11, where a concrete pad once holding an electrical
transformer is located.

Phase I data indicated the presence of heavy metals above typical
background ranges in AEC 12, which is the location of the former
production well.  A sediment sample collected from the base of
the concrete vault housing the well detected nickel at 606 ppm.

Phase II involved the collection of additional surface and
subsurface soil samples from 9 AECs.  During May 1993, seven soil
borings were drilled, three test trenches were excavated, and 46
surface and subsurface samples were collected for physical and
chemical analyses.  Together with earlier data, Phase II sampling
data confirmed that AECs 1,  5, 8, 10, 13, and 14 were also
impacted by Site-related contamination.  Based on the Phase II
data,  AECs la, 15 and 16 were not considered to have been
significantly impacted.

The Phase II results for AEC 1 confirmed the presence of TPHCs in
the three solid-bottom storm drains and the base of the receiving
drywell.

Previous data for AEC 5 indicated nickel in sediments slightly
above Site background and TPHCs at levels up to 93,000 ppm at the
drainage pipe outfall.  Phase II involved collection of samples

-------
from the base of two drywells and two storm drains to
characterize the TPHC content.  The samples contained TPHCs
ranging from 406 ppm to 5,780 ppm.  In addition,  it appeared that
the drainage system had been impacted by a petroleum release
emanating from the oil-fired boilers within the former Goldisc
building.  Because response actions for petroleum releases are
excluded under CERCLA, this AEC has been referred to the NYSDEC
spills program for evaluation and possible remediation.

Locations which previously indicated high levels of nickel and
chromium in AEC 8 were resampled.  Maximum detected levels for
nickel and chromium in Phase II sampling were 33 ppm and 80 ppm,
respectively, in surface soils.  Phase I and Phase II results
confirm that this reported discharge area had contamination
related to Site operations.

A soil boring was taken and analyzed for TPHCs in AEC 10.  The
highest concentration of TPHCs was detected in the 10-foot to 12-
foot interval at 9,240 ppm.  Concentrations decreased
significantly with depth to 84 ppm in the 20-foot to 22-foot
interval, and were not detected at lower intervals.

Phase II analyses were performed to complete the delineation of
soils impacted by TPHCs in AEC 13.  In one boring, the TPHCs
extended to the water table.  It is believed that oil reached
this area through the Area 5 drainage system pipe.  This AEC has
also been referred to the DEC spills program.  In the event that
further testing identifies additional Site related hazardous
wastes, EPA may reconsider addressing these areas.

Phase II sampling for AEC 14 included borings and analyses from
three drywells.  The uppermost sediments contained several metals
at concentrations slightly above background.  Deeper samples were
within background ranges.  The highest VOC detected was acetone
at 0.44 ppm.  Polychlorinated biphenyls (PCBs) were detected in
all three drywells, the highest concentration at 0.41 ppm.
Drywell 2 (DW-2) in this area contained levels of chrysene at a
concentration of 0.77 ppm and benzo(a)anthracene at a
concentration of 0.5 ppm in the 15-foot to 17-foot interval,
above the recommended New York State cleanup guidelines of 0.4
ppm and 0.224 ppm, respectively  (see Table 2).

Groundwater

The Phase I RI involved the collection of groundwater samples
from 18 on-site monitoring wells, one on-site production well,
one off-site upgradient well, and the three SCWA Church Street
supply wells (see Figure 3 for groundwater well locations).  Of
the 18 on-site monitoring wells sampled, 14 are shallow  (less
than 50 feet deep), two are intermediate (75 to 90 feet deep),
and two are deep  (over 100 feet deep).  All on-site monitoring
wells are installed in the shallow aquifer, the Upper Glacial

-------
aquifer.  The thickness of the Upper Glacial underlying the Site
is approximately 135 feet.  Depth from the surface to the water
table ranged across the Site from 18 to 32 feet.  Church Street
wells #1 and #2 (CS-1 and CS-2) are both shallow; installed in
the Upper Glacial aquifer.  Church Street well #3 (CS-3) is much
deeper, screened in the lower Magothy aquifer.  The groundwater
flow direction in the northern portion of the Site is generally
south to southeast.  However, the southeast portion of the Site
shows a shift in flow direction to the southwest in response to
the radial drawdown resulting from to operation of the Church
Street supply wellfield.  The groundwater flow velocity, ranging
between 1.3 to 1.7 feet/day during nonpumping periods, increases
to 2.4 to 2.9 feet/day during Church Street pumping operations.

The initial Phase II groundwater sampling effort, performed in
April 1993, included collection of samples from eight of the on-
site monitoring wells.  Two of these monitoring wells required
replacement.  The groundwater samples were analyzed for Target
Analyte List (TAL) metals and/or Target Compound List (TCL)
volatile organic compounds (VOCs),  to fill data gaps or to
Confirm Phase I analytical results.  After review of these
results, an additional round of groundwater samples was collected
from 15 on-site wells in order to investigate further the
presence of heavy metals.  In September 1994, ERM-Northeast
collected samples from the 15 monitoring wells and analyzed these
samples for nickel, chromium, iron, and manganese.  All 15
samples were split with ICF Technology Corp., EPA's oversight
contractor, and analyzed by EPA for all TAL metals.

Comparison of the Phase II groundwater sampling results with
Phase I indicated that the VOC concentrations had decreased.  For
the Phase II data, the only VOC detected at a concentration above
its drinking water standard was carbon disulfide in monitoring
well 17D (MW-17D).  Analytical results for the split sample from
MW-17D did not indicate the presence of carbon disulfide above
its drinking water standard.   Carbon disulfide has been
determined to be a laboratory artifact and not a contaminant of
concern.

Results of the Phase II first round of metal analyses of samples
collected from eight monitoring wells did not indicate the
presence of metals above any drinking water standards (see
Table 3).   The Phase II second round of metals analysis,
performed on samples collected from 15 monitoring wells, detected
high levels of nickel, ranging from 13.3 ppb to 959'ppb (see
Tables 4a and 4b).  At the time the sampling was performed, the
federal MCL for nickel, which had become effective on June 17,
1992,  was 100 ppb.  In February 1995, in response to on-going
litigation over its validity, EPA filed a joint motion to remand
the nickel MCL voluntarily.  On June 29, 1995, EPA issued a
Federal Register notice formally removing the nickel MCL from the
Code of Federal Regulations.   Currently, no federal or state

-------
drinking water standard exists for nickel.  However, on July 10,
1995, EPA issued a Health Advisory of 100 ppb for nickel,  while a
new MCL for nickel is being reestablished.  This Health Advisory
is intended to serve as informal technical guidance only and is
not to be construed as setting legally enforceable federal
standards.  Of the fifteen wells sampled during Phase II,  only 3
had levels of nickel above 100 ppb, namely, MW-11 (140 ppb),
MW-12 (959 ppb) and MW-16 (278 ppb).   Since an MCL for nickel
does not exist, a health-based action level was developed for the
Site utilizing Superfund risk assessment methodologies.  This
health-based action level, detailed further in the risk
discussion, was calculated to be 730 ppb.  Only one sample,
collected from MW-12 (959 ppb), exceeded this level.

In late 1993, routine monitoring performed by SCWA on the Church
Street wellfield detected the presence of nickel in CS-2 in
excess of the then existing 100 ppb MCL.  This prompted SCWA to
remove CS-2 from service and conduct testing to determine a
suitable method of remediation for the well.  Sampling of CS-2 in
July 1995 and August 1995 revealed decreasing nickel
concentrations of 98 ppb and 95 ppb,  respectively.  Since the
remand of the nickel MCL, SCWA has put CS-2 back into service,
blending it with the other wells, resulting in drinking water
which is still well below the former MCL and current Health
Advisory level of 100 ppb.

Based on its frequent detection at elevated concentrations at the
Site, its former MCL, and the impact to the Church Street
wellfield, nickel has been deemed to be the major contaminant of
concern at the Site.

The Phase II second round of metal analyses also detected the
presence of both iron and manganese above their respective
secondary drinking water standards.  Split samples verified these
results.  The secondary federal and state MCLs for iron and
manganese are both based on aesthetic properties and are intended
to prevent potential problems, such as poor taste, odor, and
staining of plumbing fixtures, and do not specifically present a
health risk.  The highest concentrations were reported for the
unfiltered sample collected from MW-llR.  For this sample, iron
was detected at a concentration of 34,900 ppb and manganese at a
concentration of 2,840 ppb.  The federal secondary MCLs for iron
and manganese are 300 ppb and 50 ppb, respectively.  A filtered
sample collected from MW-llR detected iron and manganese at
reduced levels of 185 ppb and 459 ppb, respectively.  In the
filtered sample, manganese was still in excess of the drinking
water standard.  However, manganese is not a contaminant of
concern and does not present a risk; the levels detected
represent background conditions in the area.

-------
SUMMARY OF SITE RISKS

Based upon the results of the RI, a baseline risk assessment was
conducted to estimate the risks associated with current and
future site conditions.  The baseline risk assessment estimates
the human health and ecological risk which could result from the
contamination at the site, if no remedial action were taken.

Human Health Risk Assessment

A four-step process is utilized for assessing site-related human
health risks for a reasonable maximum exposure scenario:  Hazard
Identification—identifies the contaminants of concern at the
Site based on several factors such as toxicity, frequency of
occurrence, and concentration.  Exposure Assessment—estimates
the magnitude of actual and/or potential human exposures, the
frequency and duration of these exposures, and the pathway  (e.g,
ingesting contaminated well-water)  by which humans are
potentially exposed.  Toxicity Assessment—determines the types
of adverse health effects associated with chemical exposures, and
the relationship between magnitude of exposure (dose) and
severity of adverse effects (response).   Risk Characterization—
summarizes and combines outputs of the exposure and toxicity
assessments to provide a quantitative (e.g., one-in-a-million
excess cancer risk) assessment of site-related risks.

EPA conducted a baseline risk assessment to evaluate the
potential risks to human health and the environment associated
with the Goldisc Recordings property in its current state.  The
Risk Assessment began with selecting contaminants of concern
which would likely pose significant risks to human health and the
environment.  These contaminants included tetrachloroethylene,
1,1-dichloroethane, 1,1,1-trichloroethane, vinyl chloride,
benzo(a)anthracene, chrysene, cadmium, copper, lead, nickel, and
zinc (see Table 5).

Four exposure pathways were evaluated under possible on-site
present and future land use conditions;  it was assumed that the
property's current zoning status as commercial/industrial would
not change.  The exposure pathways considered were: dermal
absorption of chemicals in the soil by children trespassing on
the Site, direct contact (including incidental ingestion and
dermal absorption)  with soils by on-site commercial/industrial
employees, direct contact with soil by future short-term
construction workers, and domestic use of groundwater (including
ingestion and inhalation of volatiles by nearby residents using
the Church Street wellfield as the exposure point).  All pathways
were based on current Site conditions, except the future short-
term construction worker scenario.

EPA's acceptable cancer risk range is 10"4 to 10'6 which can be
interpreted to mean that an individual may have a one in ten

-------
thousand to a one in a million increased chance of developing
cancer as a result of a site-related exposure to a carcinogen
over a 70-year lifetime under the specific exposure conditions at
a site.  The results of the baseline risk assessment indicate
that the soils and groundwater at the Site pose no unacceptable
carcinogenic risk to human health.  The overall carcinogenic risk
for on-site workers, through direct contact with soils,  is
estimated to be 8.5 x 10"8 (risk of 8.5  in 100 million)  (see  Table
6).   The overall carcinogenic risk for future construction
workers, through ingestion and dermal contact with soils,  is
estimated to be 4.3 x 10'9 (risk of 4.3  in a billion)  (see  Table
7).   The overall carcinogenic risk for domestic use of
groundwater, through ingestion and inhalation, is estimated to be
9.5 x 10"6 (risk of 9.5 in a million)  (see Table 8).   Much  of this
risk is attributable to vinyl chloride, which was not detected in
recent sampling events at the Church Street supply wellfield or
on the Site.  The preceding risk values indicate that the Site
poses no unacceptable carcinogenic risk to human health.  The
dermal exposure pathway for children was evaluated but not
quantified, as there were no contaminants of concern detected
which are considered to be potential carcinogens via dermal
exposure.  Therefore, no adverse carcinogenic effects are
expected to result from chronic exposure to chemicals from the
Site.

To assess the overall potential for noncarcinogenic effects posed
by the contaminants at a site, EPA has developed the hazard index
(HI).  The HI measures the assumed simultaneous subthreshold
exposures to several chemicals which could result in an adverse
health effect.  When the HI exceeds 1.0, there may be concern for
potential noncarcinogenic health effects.

The calculated HI values for the dermal absorption and direct
contact pathways were all calculated to be less than 1.  Dermal
absorption by nearby children contributed to an HI value of
0.0002  (see Table 9), direct contact by on-site workers
contributed to an HI value of 0.002 (see Table 10) and direct
contact by future workers contributed to an HI value of 0.03  (see
Table 11).  Domestic use of groundwater contributed to an HI
value of 0.26 (see Table 12); nickel was the major contributor to
this HI.  As noted below, this calculation assumes that there are
no appreciable sources of nickel exposure outside of groundwater
ingestion.

As noted in the Summary of Site Characteristics section, the MCL
for nickel was remanded in February 1995.  Due to the fact that
significant nickel contamination exists in the Upper Glacial
Aquifer, potential risks related to this contamination were
closely evaluated.  An acceptable health-based action level was
developed for nickel in groundwater at the Site.  Assuming that
the groundwater would be used for domestic purposes, it was
determined that groundwater concentrations of nickel below 730

-------
ppb would result in an acceptable HI for the Site (i.e., an HI
less than or equal to 1.0); conversely, levels above 730 ppb
could present an unacceptable noncarcinogenic risk for the Site.
Consistent with EPA guidance for conducting Superfund risk
assessments, this calculated value assumes that there are no
other significant sources of nickel exposure from other
environmental media (e.g., air, soil, diet).  As a point of
reference, the 95% Upper Confidence Level (UCL) of the arithmetic
mean, calculated utilizing nickel data from all of the on-site
wells sampled during Phase II was 480 ppb, well below the 730 ppb
action level.  As noted previously, EPA has issued a Health
Advisory for nickel of 100 ppb which is the same level as the
former MCL.  The Health Advisory incorporates additional
conservative safety factors to account for potential nickel
exposure from media other than drinking water; this very
conservative level of safety assumes that drinking water only
contributes 20% of the expected nickel exposure.

Ecological Assessment

The ecological risk assessment considered potential exposure
routes of Site contamination to terrestrial wildlife.  Much of
the Site is paved or covered by structures and there is little,
if any, potential for wildlife to be exposed to contaminated
subsurface soils on-site.  The only potential route of exposure
to wildlife in the Site vicinity is if contaminants were
transported through groundwater and discharged via groundwater
into surface waters, particularly the state wetland located one-
half mile south of the Site.  Phase II sampling shows that the
wetland has not been impacted by Site contaminants.  Therefore,
it was determined that no significant effects on aquatic
organisms in the wetland in the vicinity of the Site could be
attributed to groundwater discharge from the Site.

Since significant contamination, specifically nickel, was
detected in the soils at the Site, there is a high potential for
cross-media impacts as nickel can migrate into the groundwater
via fluctuations of the water table and precipitation.  This is
supported by the detection of high levels of nickel in the
groundwater.  The maximum concentration of nickel in one on-site
well was detected at 959 ppb.  Furthermore, Site-related nickel
contamination has impacted the nearby Church Street supply wells.
Due to these circumstances, remedial action alternatives were
developed for the Site sediments and soils.

Uncertainties

The procedures and inputs used to assess risks in this
evaluation, as in all such assessments, are subject to a wide
variety of uncertainties.  In general, the main sources of
uncertainty include:


                                10

-------
     environmental chemistry sampling and analysis
     environmental parameter measurement
     fate and transport modeling
     exposure parameter estimation
     toxicological data.

Uncertainty in environmental sampling arises in part from the
potentially uneven distribution of chemicals in the media
sampled.  Consequently, there is significant uncertainty as to
the actual levels present.  Environmental chemistry-analysis
error can stem from several sources including the errors inherent
in the analytical methods and characteristics of the matrix being
sampled.

Uncertainties in the exposure assessment are related to estimates
of how often an individual would actually come in contact with
the chemicals of concern, the period of time over which such
exposure would occur, and in the models used to estimate the
concentrations of the chemicals of concern at the point of
exposure.

Uncertainties in toxicological data occur in extrapolating both
from animals to humans and from high to low doses of exposure, as
well as from the difficulties in assessing the toxicity of a
mixture of chemicals.  These uncertainties are addressed by
making conservative assumptions concerning risk and exposure
parameters throughout the assessment.  As a result, the Risk
Assessment provides upper-bound estimates of the risks to
populations near the Site, and is highly unlikely to
underestimate actual risks related to the Site.

More specific information concerning public health risks,
including a quantitative evaluation of the degree of risk
associated with various exposure pathways, is presented in the
Risk Assessment Report.

Actual or threatened releases of hazardous substances from this
Site, if not addressed by implementing the response action
selected in the ROD, may present an imminent and substantial
endangerment to the public health, welfare, or the environment.

REMEDIAL ACTION OBJECTIVES

Remedial action objectives are specific goals to protect human
health and the environment.  These objectives are based on
available information and standards such as ARARs and risk-based
levels established in the risk assessment.

The following remedial action objective was established:

•  minimize leaching of contaminants, particularly nickel, in
   the subsurface soils and sediments to the groundwater.

                                11

-------
DESCRIPTION OF REMEDIAL ALTERNATIVES

CERCLA §121(b)(l), 42 U.S.C. §9621(b)(l), mandates that a
remedial action must be protective of human health and the
environment, cost-effective, and utilize permanent solutions and
alternative treatment technologies or resource recovery
technologies to the maximum extent practicable.  Section
121(b)(l) also establishes a preference for remedial actions
which employ, as a principal element, treatment to permanently
and significantly reduce the volume, toxicity, or mobility of the
hazardous substances, pollutants and contaminants at a site.
CERCLA §121(d), 42 U.S.C. §9621(d), further specifies that a
remedial action must attain a level or standard of control of the
hazardous substances, pollutants, and contaminants, which at
least attains ARARs under federal and state laws, unless a waiver
can be justified pursuant to CERCLA §121(d)(4), 42 U.S.C.
§9621(d)(4).

This ROD evaluates, in detail,  two remedial alternatives for
addressing contaminated sediments and soils associated with the
Goldisc Recordings Superfund site.  The time to implement a
remedial alternative reflects only the time required to construct
or implement the remedy and does not include the time required to
design the remedy, negotiate with the responsible parties, or
procure contracts for design and construction, or conduct
operation and maintenance at the site.

The remedial alternatives are:

Alternative SR-I: No Action

Capital Cost:       $ 0
0 & M/yr Cost:      $ 0
Present Worth:      $ 0
Time to Implement: N/A

The Superfund program requires that the No Action alternative be
considered as a baseline for comparison with other soil
alternatives.  Under this alternative, the contaminated sediments
and soils would be left in place without treatment.  Since this
alternative would not allow for unlimited use and unrestricted
exposure, CERCLA requires that the Site be reviewed every five
years.  If justified by the review, remedial actions may be
implemented.

Alternative SR-II: Limited Action

Capital Cost:       $ 250,322
0 & M/yr Cost:      $   2,020
Present Worth:      $ 277,062
Time to Implement: 2 months


                                12

-------
This alternative includes measures which would reduce the
leaching of contaminants, particularly nickel, to the
groundwater.  The specific measures include:  removal of
contaminated soils/sediments in the six drywells in AEC 2 and
drywell DW-2 in AEC 14, and removal of surface soils within
AEC 8, a reported discharge area which has shown TPHCs and metals
related to Site operations.  In addition, this alternative would
include decommissioning and cleanup of the on-site production
well.  This action would be taken as a conservative measure to
eliminate potential exposure to contaminated groundwater at the
Site.  The areas to be remediated are detailed on Figure 4.

The top three feet of soils/sediments would be removed via a
vacuum truck from the six dry wells in AEC 2 and drywell DW-2 in
AEC 14.  The drywell structures would be left in-place and
backfilled with clean soil.  New drywells would be installed in
an adjacent area for storm water runoff.  The amount of material
to be removed from these structures is estimated to be
approximately 56 cubic yards; this material represents the most
significant source of nickel contamination on the Site.  In
addition, approximately 215 cubic yards of surface soiJs from
specific areas within AEC 8 would be removed.  Also, the
soils/sediments in the on-site production well vault would be
removed via a vacuum truck.  An additional source of nickel would
be removed by this action.  The well borehole would be sealed and
capped, and the well casing and concrete vault would be removed.
All materials removed during these measures would be transported
off-site for treatment (as necessary) and disposal in accordance
with federal and state requirements.  Steps would also be taken
to try to secure the placement of a deed restriction on the
property so that the use of the property would be restricted to
its current commercial/industrial use.  Although this alternative
would result in no contamination remaining on-site above health-
based levels for the current property use, the remedy does not
allow for unlimited use and unrestricted exposure; therefore,
five-year reviews would be required.

SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES

In selecting a remedy, EPA considered the factors set out in
CERCLA §121, 42 U.S.C. §9621, by conducting a detailed analysis
of the viable remedial alternatives pursuant to the NCP, 40 CFR
§300.430(e)(9) and OSWER Directive 9355.3-01.  The detailed
analysis consisted of an assessment of the individual
alternatives against each of nine evaluation criteria and a
comparative analysis focusing upon the relative performance of
each alternative against those criteria.

The following "threshold" criteria must be satisfied by any
alternative in order to be eligible for selection:
                                13

-------
1.   Overall protection of human health and the environment
     addresses whether or not a remedy provides adequate
     protection and describes how risks posed through each
     exposure pathway (based on a reasonable maximum exposure
     scenario) are eliminated, reduced, or controlled through
     treatment, engineering controls, or institutional controls.

2.   Compliance with Applicable, or Relevant and Appropriate
     Requirements (ARARs)  addresses whether or not a remedy would
     meet all of the applicable (legally enforceable), or
     relevant and appropriate (requirements that pertain to
     situations sufficiently similar to those encountered at a
     Superfund site such that their use is well suited to the
     site) requirements of federal and state environmental
     statutes and requirements or provide grounds for invoking a
     waiver.

The following "primary balancing" criteria are used to make
comparisons and to identify the major trade-offs between
alternatives:

3.   Long-term effectiveness and permanence refers to the ability
     of a remedy to maintain reliable protection of human health
     and the environment over time, once cleanup goals have been
     met.  It also addresses the magnitude and effectiveness of
     the measures that may be required to manage the risk posed
     by treatment residuals and/or untreated wastes.

4.   Reduction of toxicity. mobility, or volume via treatment
     refers to a remedial  technology's expected ability to reduce
     the toxicity, mobility, or volume of hazardous substances,
     pollutants or contaminants at the site.

5.   Short-term effectiveness addresses the period of time needed
     to achieve protection and any adverse impacts on human
     health and the environment that may be posed during the
     construction and implementation periods until cleanup goals
     are achieved.

6.   Implementabilitv refers to the technical and administrative
     feasibility of a remedy, including the availability of
     materials and services needed.

7.   Cost includes estimated capital and operation and
     maintenance costs,  and the present-worth costs.

The following "modifying"  criteria are considered fully after the
formal public comment period on the Proposed Plan is complete:

8.   State acceptance indicates whether, based on its review of
     the RI/FS and the Proposed Plan, the State supports,
     opposes, and/or has identified any reservations with the
     preferred alternative.

                                14

-------
9.   Community acceptance refers to the public's general response
     to the alternatives described in the Proposed Plan and the
     RI/FS reports.  Factors of community acceptance to be
     discussed include support, reservation,  and opposition by
     the community.

A comparative analysis of the remedial alternatives based upon
the evaluation criteria noted above follows.

•    Overall Protection of Human Health and the Environment

     Alternative SR-II would meet the remedial objective of
     preventing cross-media impacts to the groundwater from the
     source of contamination.  Alternative SR-I would not prevent
     the continued migration of nickel into the underlying
     groundwater and, therefore, would not be as protective as
     Alternative SR-II.

•    Compliance with ARARs

     Federal and state regulations dealing with the handling and
     transportation of any wastes to an off-site disposal
     facility for Alternative SR-II would be followed.  Wastes
     would be treated using specific technologies or specific
     treatment levels, as appropriate, to comply with land
     disposal restrictions.  Alternative SR-I would not be
     subject to any ARARs, although, potential excursions of
     groundwater/drinking water standards could occur under this
     alternative, due to cross-media impacts resulting from
     contaminants remaining in the soil.

•    Long-Term Effectiveness and Permanence

     Alternative SR-II would remove the principal source of
     nickel to prevent leaching of contamination to the Upper
     Glacial Aquifer.  Alternative SR-I would not reduce the
     potential long-term leaching to groundwater.

•    Reduction in Toxicity. Mobility, or Volume via Treatment

     Treatment may be employed at the off-site facility to reduce
     the toxicity, mobility, and potentially volume of
     contaminants, especially nickel, in soils/sediments under
     Alternative SR-II; otherwise off-site disposal will achieve
     the same reductions without treatment.  Alternative SR-I
     would provide no reduction in contaminant mobility,
     toxicity, or volume.

•    Short-Term Effectiveness

     There is the potential for a temporary increase in risk to
     the community and workers due to dust generation during the

                                15

-------
     soil removal activities of Alternative SR-II.  However,
     health and safety measures, along with the use of a vacuum
     truck for soil collection, would be implemented to mitigate
     the potential for risk.  Workers would also be protected
     through the use of respirators (if needed).   The
     implementation of Alternative SR-I would result in no
     additional risk to the community or workers during
     implementation.

•    Implementability

     Components of Alternative SR-II would utilize relatively
     common construction equipment and materials.  The services
     and technologies needed to implement this work are readily
     available.  Use restrictions via zoning are in place at the
     Site and are not expected to change, however EPA would seek
     to have a deed restriction put on the property so as to
     restrict the property to commercial/industrial uses.
     Because no construction activities are associated with
     Alternative SR-I, this alternative would be easier to
     implement than Alternative SR-II.

•    Cost

     The no action alternative has no associated costs.
     Alternative SR-II is estimated to cost $277,062.

•    State Acceptance

     The State of New York concurs with the selected remedy.

•    Community Acceptance

     The community concurs with the selected remedy.  Specific
     responses to public comments are addressed in the
     Responsiveness Summary section of the ROD.

SELECTED REMEDY

EPA and NYSDEC have determined, after reviewing the alternatives
and public comments,  that Alternative SR-II is the appropriate
remedy for the Site,  because it best satisfies the requirements
of CERCLA §121, 42 U.S.C. §9621, and the NCP's nine evaluation
criteria for remedial alternatives, 40 CFR §300.430(e)(9).

The major components of the selected remedy are as follows:

t    Excavation via a vacuum truck and off-site disposal of
     approximately 56 cubic yards of sediments and soils from the
     six dry wells in AEC 2 and drywell DW-2 in AEC 14;
                                16

-------
•    Excavation and off-site disposal of approximately 215 cubic
     yards of surface soils within AEC 8;

•    Abandonment of the on-site production well including
     excavation and off-site disposal of sediments and soils from
     the well vault; and

•    Taking steps to secure the placement of a deed restriction
     on the property to limit it to a nonresidential use.

STATUTORY DETERMINATIONS

As previously noted, CERCLA §121(b)(l), 42 U.S.C.  §9621(b)(l),
mandates that a remedial action must be protective of human
health and the environment, cost-effective, and utilize permanent
solutions and alternative treatment technologies or resource
recovery technologies to the maximum extent practicable.  Section
121(b)(l) also establishes a preference for remedial actions
which employ treatment to permanently and significantly reduce
the volume, toxicity, or mobility of the hazardous substances,
pollutants, or contaminants at a site.  CERCLA §121(d), 42 U.S.C.
§9621(d), further specifies that a remedial action must attain a
degree of cleanup that satisfies ARARs under federal and state
laws, unless a waiver can be justified pursuant to CERCLA
§121(d)(4), 42 U.S.C. §9621(d)(4).

For the reasons discussed below, EPA has determined that the
selected remedy meets the requirements of CERCLA §121, 42 U.S.C.
§9621:

Protection of Human Health and the Environment

The selected remedy is considered to be fully responsive to this
criterion and to the identified remedial action objective.
Excavation and appropriate off-site treatment and disposal of the
contaminated Site sediments and soils will prevent cross-media
impacts by removal of a continuous source of contaminants to the
underlying groundwater.

Compliance with ARARs

At the completion of the response action, the selected remedy
will have complied with all applicable ARARs, including:

Action-Specific ARARs:

•    40 Code of Federal Regulations  (CFR) Part 61 - National
     Ambient Air Quality Standards for Hazardous Air Pollutants

•    40 CFR Part 254.25 - Excavation and Fugitive Dust Emissions

•    40 CFR Part 262.1 - Standards for Generators of Hazardous
     Waste

                                17

-------
 •    40 CFR Part 263 - Standards Applicable to Transport of
     Hazardous Waste

 •    40 CFR Part 264 - Standards for Owners and Operators of
     Hazardous Waste Treatment, Storage, and Disposal Facilities

 •    40 CFR Part 268 - Land Disposal Restrictions

 •    6 New York Code of Rules and Regulations (NYCRR) Part 200.6 -
     Ambient Air Quality Standards

 •    6 NYCRR Part 372 - Hazardous Waste Manifest System & Related
     Standards for Generators, Transporters and Facilities

 •    6 NYCRR Subpart 373 - Final State Standards for Owners and
     Operators of Hazardous Waste Treatment, Storage and Disposal
     Facilities

 •    12 NYCRR Subpart 753 - New York Industrial Code Rule # 53 for
     Notification Requirements on Buried Pipeline

 •    Occupational Safety and Health Act (OSHA)  - 20 CFR Part 1910 -
     General Industry Standards

 •    OSHA - 20 CFR Part 1926 - Safety and Health Standards

 •    OSHA - 20 CFR Part 1904 - Record-Keeping,  Reporting, and
     Related Regulations

 •    Department of Transportation (DOT) - 49 CFR Parts 107, 171.1 -
     172.5-58 - Rules for Transportation of Hazardous Materials

Chemical-Specific ARARs:

 •    40 CFR Part 268 - RCRA Universal Treatment Standards

Location-Specific ARARs:

 •    None applicable.

To Be Considered:

 •    New York State Technical and Administrative Guidance
     Memorandum (TAGM)  - HWR-94-4046

     USEPA Interim Draft Health Advisory for Nickel

Cost~Effectiveness

The selected remedy is cost-effective in that it provides overall
effectiveness proportional to its cost.  The total cost of the
remedy is $277,062; very little long-term operation and maintenance

                                 18

-------
costs are expected.  With respect to the total cost,  approximately
50% of the cost is attributed to sediments and soils  removal,
backfilling, and regrading activities; the remaining  50% is
attributed to post-excavation sampling,  soil classification,  and
disposal.  A detailed breakdown of the costs associated with this
remedy is provided in Tables 13a and 13b.

Utilization of Permanent Solutions and Alternative Treatment
Technologies to the Maximum Extent Practicable

The selected remedy utilizes permanent solutions and  treatment
technologies to the maximum extent practicable.  The  selected
remedy represents the best balance of trade-offs among the
alternatives with respect to the evaluation criteria.  The State of
New York and the community also support the selected  remedy.

The selected remedy employs removal of the inorganic  and organic
contaminated sediments and soils on the Site through  excavation and
appropriate off-site treatment (as necessary)  and disposal.  The
potential for future releases of contaminants to the  underlying
grourdwater will be eliminated.  Removal and treatment of the
contaminated sediments and soils will, over the long  term, reduce
the toxicity, mobility, and volume of contaminants in the
groundwater underlying the Site and prevent further degradation of
area groundwater.

No short-term adverse impacts and threats to human health and the
environment are foreseen as the result of implementing the selected
remedy.  However, to minimize and/or prevent worker exposure to
contaminants, personal protection equipment will be utilized.

Preference for Treatment as a Principal Element

The selected remedy requires that the prinicipal threats posed by
the Site, nickel-contaminated sediments and soils, be excavated and
transported off-site for treatment  (as necessary) and disposal in
accordance with applicable requirements.  Although the remedy does
not require treatment, it is anticipated that these materials will
require treatment prior to disposal.  If off-site treatment is
required, the remedy will satisfy the preference for treatment as a
principal element.

DOCUMENTATION OF SIGNIFICANT CHANGES

The Proposed Plan for the Site sediments and soils, identifying the
selected remedy as Alternative SR-II, was released to the public on
August 26, 1995.  There are no significant changes from the
preferred alternative as presented  in the Proposed Plan.
                                 19

-------
APPENDIX I




  FIGURES

-------

  *\{M\u$&r^   v	MW^^\IS 1 ^SS~^S|Q'
                                    JT	•TI^VW?
                                    id.    * lx.>$i!£x
                                   GENERAL VICINITY

                                        MAP
  URCE: U.S.G.S. Quadrangle Maps. Patchogue & Sayvllle. NY


sISCALE: T

-------
                                                      Figure 2.
                                       Goldisc Recordings Study Area
                      (Formerly
                     Occupied by
                     Genco Auto
                     Electric, Inc.)
                                                                   Currently Occupied by Consumers
                                                                          Kitchens and Baths
                Currently Occupied
                  by Cheap John's
                                                                              (Formerly
                                                                             Occupied by
                                                                        Goldisc Recordings, Inc.)
                     (Formerly
                    Occupied by
                    Electros ound
                    Group, Inc.)
                                                                                £&«&^**J$?3K&*?k ?>"^«>
                                                                                Ff^^~^ex^^ ??&
              D
            Gas Station
Note: An asterisk ( •) batore a number denotes in araa ol concern
     to be further investigated during the Phase II RI/FS.
                                                        II Asphalt Pavement
	Property Line
Areas of Concern

-------
   FIGURE 3
WELL LOCATIONS

-------
                                          FIGURE A

                                  AREAS TO BE REMEDIATED
                                        AEC 8
                                      SURFACE SOILS
                                        (215 CY)
DRYWELL n (DW-2)
  (A CY)

-------
APPENDIX II




  TABLES

-------
                                      TABLE 1
                 PHASE I ANALYTICAL RESULTS FOR AREA 2 SOIL SAMPLES
                                 FORMER GOLDISC SITE
                                 HOLBROOK, NEW YORK

Date Collected
Aluminum
Barium
Beryllium
Cadmium
Cakium
Chromium
Cobalt
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Nickel
Potassium
Silver
Vanadium
Zinc
Area 2
EC2-1
15-17'
6/29/88
1590
<23.26
<0.58
1.9
<581
47.4 J
<3.49
118
3290
54.7 J
<581
78.8 J
0.19 B
75.1 J
<581
<1.16
9.6
65.3 J
Area 2
EC2-2
15-17'
6/30/88
999
<26.32
<0.66
2.9
<658
195.0
13.7 J
68.7
4120
41.7 J
<658
17.6
0.16
999
<658
<1.32
<6.58
159 J
Area 2
EC2-2
17-19'
6/30/88
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
24.2
NA
NA
NA
NA
Area 2
EC2-3
12-14'
6/30/88
1750
<24.1
<0.6
<1.2
1170
102
<3.61
97.2
6490
73.2 J
1340
64.6
0.10
1120
<602
4.3
17
108 B
Area 2
EC2-3
14-16'
6/30/88
NA
NA
NA
NA
NA
10.7
NA
NA
NA
NA
NA
NA
NA
107
NA
NA
NA
NA
Area 2
EC2-3
16-18'
6/30/88
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
25.6 J
NA
NA
NA
NA

Date Collected
Aluminum
Barium
Beryllium
Cadmium
Calcium
Chromium
Cobalt
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Nickel
Potassium
Silver
Vanadium
Zinc
Area 2
EC2-4
9-11'
6/30/88
1300 J
<25.64
<0.64
<1.28
717
50.5 J
<3.85
24.7 J
2440 J
13.3 J
<64.1
33.2 J
0.08
726.0 J
<641
1.9 J
<6.41
122.0 J
Area 2
EC2-4
11-13'
6/30/88
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
107
NA
NA
NA
NA
Area 2
EC2-4
13-15'
6/30/88
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
70.9 J
NA
NA
NA
NA
Area 2
EC2-5
12-14'
6/30/88
812
<23.53
<0.59
<1.18
<588
30.3
<3.53
45.6
1600
34.7 J
<588
22.7
<0.05
193
<588
3.9
<5.88
34.2 B
Area 2
EC2-5
14-16'
6/30/88
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
70.2
NA
NA
NA
NA
Area 2
EC2-6
15'-17'
6/30/88
1029
<24.1
<0.6
2
<602
41.6 J
<3.16
95.2
1870
64.6 J
<602
14.8 J
0.14 B
41.5 J
<602
<1.2
<6.02
50.5 J
NOTES:
Units are milligrams per kilogram.
       U: Undetected.
   J: Estimated concentration.
      NA;  Not Analyzed
B:  Compound also detected in blank.

-------
                                          TABLE  2
                 PHASE I! ANALYTICAL RESULTS FOR AREA 14 SOIL SAMPLES
                                    FORMER GOLDISC SITE
                                    HOLBROOK, NEW YORK
                                           Page 4 of 4
Semi-volalilcs (cont.)

Date Collected
Pentachlorophcnol
Phenanthrcnc
Anthracene
Carbazolc
Di-n-bulylphthalatc
Fluoranthcne
Pyrcnc
Bulylbcnzlphihalate
3,3'-Dichlorobenzidine
Bcnzo(a)anlhracene
Chrysene
bis(2-Ethvlhexvl)phthal
Di-n-octylphthalate
Benzo(b)fluoranlhene
Benzo(k)fluoranthene
Benzo(a)pvrene
Indeno(l,2,3-cd)pyrene
Dibenz(a,h)anthracene
Benzo(g,h,i)pervlene

DW-l
9-ir
5/2/93
120 J
<500
<500
<500
<500
54 J
190 J
<500
<500
<500
<500
170 J
<500
<500
<500
<500
<500
<500
<500
DW-1
13-15'
5/2/93
<870
<350
<350
<350
<350
<350
96 J
<350
<350
<350
<350
79 J
<350
<350
<350
<350
<350
<350
<350
DVV-1
17-19'
5/2/93
DW-2
15-17'
5/2/93
<870 <1600
<350
<350
<350
<350
<350
<350
<350
<350
<350
<350
42 J
<350
<350
<350
<350
<350
<350
<350 J
<650
450 J
<650
<650
1000
1200
<650
<650
500 J
770
510 J
L50 J
860
510 J
260 J
460 J
290 J
400 J
DW-2
17-19'
5/2/93
<900 J
<360
<360
<360
<360
<360
<360J
<360
<360
<360
<360
<360
<360
<360
<360
<360
<360
<360
<360
DW-2
27-29'
5/2/93
<880 J
<350
<350
<350
<350
<350
<350 J
<350
<350
<350
<350
42 J
<350
<350
<350
<350
<350
<350
<350
DW-3
16-18'
5/2/93
230 J
220 J
<930 J
<930 J
<930 J
500 J
400 J
250 J
DW-3
24-26'
5/2/93
1000
<410
<410
<410
<410
<410
<410
<410
<930 J| <410
170 J
210 J
460 J
<930 J
140 J
110 J
<930 J
<930 J
<930 J
<930 J
<410
<410
<410
<410
<410
<410
<410
<410
<410
<410 J
DW-3
26-30'
5/2/93
<980
<390
<390
<390
<390
<390
<390
<390
<390
<390
<390
<390
<390
<390
<390
<390
<390
<390
<390 J
DW-3
28-30'
5/2/93
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
DW-3
Split
5/2/93
<950 U
<390 U
<390 U
<390 U
43 J
<390 U
<390 U
<390 U
<390 U
<390 U
<390 U
<390 U
<390 U
<390 U
<390 U
<390 U
<390 U
<390 U
<390 U
NOTES:        Units are micrograms per kilogram for volatile organics, semi-volatiles, and PCBs.
               Units are milligrams per kilogram for metals.
               TICs:  Tentatively Identified Compounds.
               D: Concentration determined at a secondary dilution factor.
               U: Undetected.
               J: Estimated concentration.
               NA: Not Analyzed.
               R: Value rejected by data validation review.
               Split - Split sample comparison results

-------
                                          TABLE 3
            PHASE II ANALYTICAL RESULTS FOR 1993 GROUND WATER SAMPLES - METALS
                                    FORMER GOLDISC SITE
                                    HOLBROOK, NEW YORK

Date Collected
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Calcium
Chromium
Cobalt
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Nickel
Potassium
Selenium
Silver
Sodium
Thallium
Vanadium
Zinc
STD.

—
6M
50
2000
1 M
5
...
100
—
—
300
50
—
300
2
.-_
—
10
50
—
L_ 2M _J
	
5000
ivrw-2
4/22/93
NA
NA
NA
NA
NA
NA
NA
<9.7
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
M\V-4R
4/21/93
NA
NA
NA
NA
NA
NA
NA
<9.7
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
MW-8R
4/21/93
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
1.5 J
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
MW-9
4/22/93
NA
NA
NA
NA
NA
NA
NA
<9.7
NA
NA
NA
NA
NA
NA
NA
31.0
NA
NA
NA
NA
NA
NA
NA
ivnv-ioR
4/21/93
NA
NA
NA
NA
NA
NA
NA
<9.7
NA
NA
NA
NA
NA
NA
NA
<13.6
NA
NA
NA
NA
NA
NA
NA
M\v-ns
4/21/93
166
<2.4
2.2 J
12.8 J
<0.8
<3.3
S090
<9.7
<12.6
3.1
186 J
1.6 J
2060
6.5
<0.2
<13.6
1460 J
1.4 J
<0.2J
18,500
<0.4J
5.6
33.8
M\V-17I
4/21/93
187
<2.4
2.6
I7.8J
<0.8
<3.3
10,100
<9.7
<12.6
5.0
65.0
3.0 J
3980
55.6
<0.2
<13.6
2150J
<1.2J
<2.0J
15,900
<0.4 J
7.7
32.4
MW-17D
4/21/93
16.7
<2.4
2.9 J
10.6 J
<0.8
<33
9990
<9.7
<12.6
5.1
101 J
2.9 J
2230
54.1
<0.2
<13.6
872 J
<1.2J
<2.0J
9840
<0.79 J
8.6
30.9
NOTES:    Units are micrograms per liter.                                   U:  Undetected.
           NA: Not Analyzed.                                           J: Estimated concentration.
           STD: New York State drinking water standard, except those followed by M, which are USEPA MCLs.

-------
                                                                       TABLE  4a
                                   PHASE II ANALYTICAL RESULTS FOR 1994 GROUND WATER SAMPLES - METALS
                                                                FORMER GOLDISC SITE
                                                                HOLBROOK, NEW YORK

DATE
Silver
Aluminum
Arsenic
Barium
llcryllium
Calcium
Cadmium
Cobatl
Chromium
Copper
Iron
Mercury
Potassium
Magnesium
Manganese
Sodium
Nickel
Lead
Antimony
Selenium
Thallium
Vanadium
Zinc
SIT).

—
6M
SO
2000
1M
5
—
100
—
—
300
50
—
300
2
100 M
—
10
30
—
2M
—
5000
MW-2
9/7/94
NA
NA
NA
NA
NA
NA
NA
NA
<9.7
NA
28.2 T
NA
NA
NA
2 1
NA
17.6 J E
NA
NA
NA
NA
NA
NA
MW-2
Split
9/7/94
<10 L
<200 I
<10 I
<200 L
<5 I
15
<5 t
<50 L
12
<2S L
<100 L
<0.2 L
<5 L
<5 I
<15 L
30
<40 L
<3 L
<60 L
<$ L
<10 L
<50 L
<20 L
MW-5
9/8/94
NA
NA
NA
NA
NA
NA
NA
NA
<9.7
NA
16 r
NA
NA
NA
1.6 II
NA
<12.3
NA
NA
NA
NA
NA
NA
MW-5
Split
9/8/94
<10 L
22900
12.1
<200 L
<5 L
15
<5 L
<50 L
31
42
35100 L
<0.2 L
<5 L
5
2940
12
127
25.4
<60 L
<5 L
<10 t
51
40
MW-7A
9/7/94
NA
NA
NA
NA
NA
NA
NA
NA
<9.7
NA
97 r
NA
NA
NA
128
NA
<12.3
NA
NA
NA
NA
NA
NA
MW-7A
Split
9/7/94
<10 L
531
<10 L
<200 I
<5 L
13
<5 I
<50 L


-------
                                                                  TABLE  4b
                             PHASE 11 ANALYTICAL RESULTS FOR 1994 GROUND WAFER SAMPLES - METALS
                                                           FORMER GOLDISC SITE
                                                           HOLBROOK, NEW YORK

OATH
Silver
Aluminum
Arsenic
Barium
llcryllium
Calcium
Cadmium
Cobalt
Chromium
Copper
Iron
Mercury
Potassium
Magnesium
Manganese
Sodium
Nickel
l-ead
Aniimony
Selenium
Thallium
Vanadium
Zinc
STD.

50
—
50
2000
1 M
—
5
—
100
—
300
2
—
—
300
—
.. —
50
6M
10
2M
—
5000
W-I1RF
9/8/94
NA
NA
NA
NA
NA
NA
NA
NA
<9.7
NA
185
NA
NA
NA
459
NA
63.1 J
NA
NA
NA
NA
NA
NA
MW-11RF
Split
9/8/94
<10 U
671
<10 LI
<200 I
<5 I
15
<5 I

-------
               TABLE  5


     GOLDISC RECORDINGS SITE

CHEMICALS OF POTENTIAL CONCERN



      Volatile Organic Compounds

          1,1-dichloroethane
          tetrachloroethene
         1,1,1-trichloroethane
             vinyl chloride


    Semi-Volatile Organic Compounds

         benzo(a)anthracene
              chrysene


               Metals

              cadmium
               copper
                lead
               nickel
                zinc

-------
                                         TABLE 6
              Direct Contact with Site Soil by On-Site Commercial/Industrial Employees
                            Calculation of Potential Carcinogenic Risk
Chemicals
1,1-dichloroethane
tetrachloroethene
1 , 1 , 1-trichloroethane
vinyl chloride
benzo(a)anthracene
chrysene
cadmium
copper
lead
nickel
zinc
Average Daily
Intake
Oral
(mg/kg-day)
9.61E-10
2.27E-09
9.61E-10
9.44E-10
1.13E-07
1.13E-07
1.03E-07 '
1.65E-06
4.08E-06
4.43E-06
3.56E-06
Oral
Potency
Factor
(mg/kg-day)- 1
...
5.20E-02
—
1.90E+00
7.30E-01
7.30E-03
—
—
—
—
...
TOTAL
Potential
Cancer
Risk
(-)
na
1.18E-10
na
1.79E-09
8.23E-08
8.24E-10
na
na
na
na
na
8.50E-08
25500263.XLS/lc

-------
                                          TABLE  7
              Direct Contact with Site Soil by Future Short-Term Construction Workers
                            Calculation of Potential Carcinogenic Risk
Chemical
1,1-dichloroethane
tetrachloroethene
1,1,1 -trichloroethane
vinyl chloride
Denzo(a)anthracene
chrysene
cadmium
copper
ead
nickel
zinc
Oral
Average Daily
Intake
(mg/kg-day)
1.43E-10
3.31E-10
1.43E-10
3.31E-10
5.01E-09
6.37E-09
1.29E-07
6.17E-06
2.17E-06
3.56E-06
3.31E-06
Potency
Factor
(mg/kg-day)- 1
—
5.20E-02
—
1.90E+00
7.30E-01
7.30E-03
—
—
—
—
...
TOTAL
Potential
Cancer
Risk
(-)
—
1.72E-11
—
6.30E-10
3.65E-09
4.65E-11
—
—
—
—
—
4.34E-09
25500263.XLS/lc

-------
                                                              TABLE  8
                                                     Domestic Use of Ground Water
                                               Calculation of Potential Carcinogenic Risk
Chemical
1,1-dichloroethane
tetrachloroethene
1,1,1 -trichloroethane
vinyl chloride
benzo(a)anthracene
chrysene
cadmium
copper
lead
nickel
zinc
TOTAL
Oral Risk
Average Daffy
Intake (ADI)
(mg/kg-day)
1.17E-05
9.39E-06
4.23E-05
2.94E-06
8.81E-08
2.70E-08
2.94E-05
1.53E-06
2.81E-05
2.08E-03
1.17E-04

Potency
Factor
(mg/kg-day)-l
~.
5.20E-02
—
1.90E400
7.30E-01
7.30E-03
—
—
—
—
—

Oral
Risk
(~)

4.88E-07

5.59E-06
6.43E-08
1.97E-10






Inhalation Risk
Average Daily
Intake (ADI)
(mg/kg-day)
4.40E-05
3.52E-05
1.59E-04
1.10E-05
3.30E-07
1.01E-07
1.10E-04
5.72E-06
1.06E-04
7.79E-03
4.40E-04

Potency
Factor
(mg/kg-day)- 1
—
2.03E-03
—
3.00E-01
na
na
na
na
na
na
na

Inhalation
Risk
(-)

7.15E-08

3.30E-06








Total
Pathway
Risk
(-)

5.60E-07

8.89E-06
6.43E-08
1.97E-10





9.51E-06
   na=not applicable, inhalation exposure evaluated for volatile organics only
Z5500263.XLS/1C

-------
                                         TABLE 9
                       Dermal Absorption of Chemicals in Soil by Children
                              Calculation of Chronic Hazard Index
                                   (Noncarcinogenic Effects)



Chemical
cadmium
Absorbed
Dose
Dermal
(mg/kg-day)
8.80E-08
Dermal
Reference
Dose
(mg/kg-day)
5.00E-04

Hazard
Index (HI)
(-)
1.76E-04
25500263-XLS/lc

-------
                                                         TABLE  10
                             Direct Contact with Site Soil by On-Site Commercial/Industrial Employees
                                              Calculation of Chronic Hazard Index
                                                   (Noncarcinogenic Effects)
Chemical
1,1-dichloroelhanc
lelrachloroelhene
1',1,1-trichloroethane
vinyl chloride
benzo(a)anlhracene
chrysene
cadmium
copper
lead
nickel
zinc
Oral
Average Daily
Intake
(mg/kg-day)
2.69E-09
6.36E-09
2.69E-09
2.64E-09
3.16E-07
3.16E-07
2.89E-07
4.62E-06
1. HE-OS
1 .24E-05
9.98E-06
Reference
Dose
(mg/kg-day)
l.OOE-01
I.OOE-02
...
...
...
...
5.00E-04
...
...
2.00E-02
3.00E-01
Oral
Hazard
Index (-)
2.69R-08
6.36E-07




5.78E-04


6.20E-04
3.33E-05
Dermal
Absorbed
Dose
(mg/kg-day)






3.30E-07




Reference
Dose
(mg/kg-day)
...
...
—
...
...
...
5.00E-04
...
...
—
—
Dermal
Hazard
Index (-)






6.60E-04




TOTAL
Total Pathway
Hazard
Index (HI)
(-)
2.69E-08
6.36E-07
na
na
na
na
1.24E-03
na
na
6.20E-04
3.33E-05
I.89E-03
25500263.XLS/lc

-------
                                                        TABLE  11
                             Direct Contact with Site Soil by Future Short-Term Construction Workers
                                             Calculation of Chronic Hazard Index
                                                  (Noncarcinogenic Effects)
Chemicals
1,1-dichloroethane
tetrachloroethene
1,1,1-trichloroethane
vinyl chloride
3enzo(a)anthracene
chrysene
cadmium
copper
lead
nickel
zinc
Oral
Average Daily
Intake
(mg/kg-day)
l.OOE-08
2.32E-08
l.OOE-08
2.32E-08
3.50E-07
4.46E-07
9.00E-06
4.32E-04
1.52E-04
2.49E-04
2.32E-04
Reference
Dose
(mg/kg-day)
l.OOE-01
l.OOE-02
...
•
—
—
5.00E-04
—
—
2.00E-02
3.00E-01
Oral
Hazard
Index (-)
l.OOE-07
2.32E-06
•



1.80E-02


1.25E-02
7.73E-04
Dermal
Absorbed
Dose
(mg/kg-day)
—
—
—
'
—
—
1.11E-06
—
—
—
—
Reference
Dose
(mg/kg-day)
—
—
.„
—
—
—
5.00E-04
—
—
—
—
Dermal
Hazard
Index (-)






2.23E-03




TOTAL
Hazard
Index (HI)
l.OOE-07
2.32E-06
—
—
—
—
2.02E-02
—
—
1.24E-02
7.72E-04
3.34E-02
25500263.XLS/1C

-------
                                                           TABLE  12
                                                   Domestic Use of Ground Water
                                                Calculation of Chronic Hazard Index
                                                     (Noncarcinogenic Effects)
Chemical
1,1-dichloroethane
tetrachloroetliene
1,1,1-trichloroethane
vinyl chloride
benzo(a)anthracene
chrysene
cadmium
copper
lead
nickel
zinc
TOTAL
Oral
Average Daily
Intake
(mg/kg-day)
2.74E-05
2.19E-05
9.86E-05
6.85E-06
2.05 E-07
6.30E-08
6.85E-06
3.56E-06
6.58E-05
4.85E-03
2.74E-04

Reference
Dose
(mg/kg-day)
l.OOE-01
l.OOE-02
—
—
...
—
5.00E-04
—
—
2.00E-02
3.00E-01

Oral
Hazard
Index (-)
2.74E-04
2.19E-03
•



1.37E-02


2.43E-01
9.13E-04

Inhalation
Average Daily
Intake (ADI)
(mg/kg-day)
1.03E-04
8.22E-05
3.70E-04
2.57E-05
7. 71 E-07
2.36E-07
2.57E-05
1.34E-05
2.47E-04
1.82E-02
1.03E-03

Reference
Dose
(mg/kg-day)
1.43E-01
—
2.86E-01
—
—
—
na
na
na
na
na

Dermal
Hazard
Index (-)
7.20E-04

1.29E-03









Hazard
Index (HI)
(-)
9.94E-04
2.19E-03
1.29E-03



1.37E-02


2.43E-01
9.13E-04
2.62E-01
              na=not applicable, inhalation exposure evaluated for volatile organics only
25500263.XLS/lc

-------
   Table  I3a
   Cost Estimate
   Former Goldisc Recordings Facility, Holbrook, New York
   Soil Remedial Alternative Limited Action
   Item Description

   Capital Costs
Unit
Quantity   Unit Cost ,   Cost    Total Cost
hr
hr
hr
day
day
day
day
Is
day
160
320
80
16
16
16
8
1
8
65
42
80
105
35
35
2,000
600
2,000
10,400
13,440
6,400
1,680
560
560
16,000
600
16,000
   Soil Removal from All Area 2 Dry Wells and Area 14 Dry Well DW-2
   (soil removal and disposal costs for production well sediment also included in this task cost)
      Soil Removal Labor and Equipment
         Supervisor
         Technicians (2 persons)
         Project Manager
         Field Vehicle
         Hand Tools
         Hard%vare
         Super Sucker
         Super Sucker Mob
         Confined Space Entry
      Dry Well Dewatering Labor and Equipment
         Labor
         Vacuum Truck
         Vacuum Truck Mob
      Soil Classification Sampling
      Soil Disposal
      Dry Well Water Classification Sampling
      Dry Well Water Disposal
   Abandonment of the Production Well

       Abandonment of the Production Well
  Is
                                                                                         S65.640
gal
day
each

Is
cy
sample
Is
13,310
5
3

1
56
3
1
0.50
1,500
600

1,700
225
150
8,886
6,655
7,500
1,800

1,700
12,600
450
8,886



315,955
S 1,700
312,600
3450
38,886
                   Task Subtotal   SI05,231



              4000      4,000'      S4.000

                   Task Subtotal     S4.000
ERM-Northcast
                                                                                  COST2..XLS\Updatcd:8/3/9S

-------
   Table  I3b
   Cost Estimate
  ^Former Goldisc Recordings Facility, Holbrook, New  York
   Soil Remedial Alternative Limited Action
   Item Description

   Excavation of Surface Soil in Area 8

       Clearing and Grubbing
       Excavation
       Backfill and Regrade
       Post-Excavation Sampling
         Senior Project Hydrogeologist
         Project Hydrogeologist
         Expenses
         Analysis for Nickel
       Soil Classification Sampling
       Soil Disposal
   Operating Costs

  . Access and Use Restrictions

       Pavement and Foundation Maintenance
       Site Inspections
Unit
  Is
y,ear
Quantity   Unit Cost „   Cost     Total Cost
day
days
cy
hours
hours
Is
sample
Is
cy
1
2
215
4
10
1
15
1
215
2,500
2500
23
90
55
150
35
1,000
225
2,500
5,000
4,945
360
550
150
525
1,000
48,375
                                                                           Task Subtotal    563,405
                                                          Subtotal of Capital Costs for SR-II   SI 72,636
                                                       Engineering and Contingencies (45%)    577,686

                                                               Total Capital Costs for SR-H   5250,322
  1,760
   260
1,760
260
                                                           Subtotal Annual Costs  52,020

                                                     Present Worth (20yrs, 7%, PWF=10.59)    521,392
                                                                       Contingency (25%)     55,348

                                           Total Present Worth of Remedial Action Annual Costs     526,740

            Total Cost, Soil Remedial Alternative SR-II wo/Contingency Area 2 Soil Study Cost  5277,062
ERM-Northeast
                                     COST2.XLS\Updated:8/3/95

-------
        APPENDIX  III




ADMINISTRATIVE RECORD INDEX

-------
                     GOLDISC RECORDINGS SITE
                   ADMINISTRATIVE RECORD FILE
                        INDEX OF  DOCUMENTS
1.0  SITE INVESTIGATION

1.4  Site Investigation Reports

P.   100001 -  Report:  Engineering Investigations at Inactive
     100304    Hazardous Waste Sites in the State of New
               York. Phase 1 - Preliminary Investigation.
               Final Report. Goldisc Recordings. Inc. Site.
               prepared for Division of Solid Waste, New York
               State Department of Environmental Conservation,
               prepared by Woodward-Clyde Consultants,  Inc.,
               September 20, 1984.

3.0  REMEDIAL INVESTIGATION

3.1  Sampling and Analysis Plans
P.
300001 -
300311
     300312 -
     300320
Report:  Final Field Operations Plan. Phase II
Remedial Investigation. Former Goldisc Recordings
Facility. Holbrook. New York, prepared by ERM-
Northeast, November, 1992.

Report:  Final Field Operations Plan. Phase II
Remedial Investigation. Former Goldisc Recordings
               Facility. Holbrook. New York. Appendix J; October
               28. 1992 Response to EPA Comments, prepared by
               ERM-Northeast, November, 1992.

3.2  Sampling and Analysis Data/Chain of Custody Forms

P.   300321 -  Report:  Split Sample Data Comparison Report.
     300364    Goldisc Recordings Site. Islip. New York. RI/FS
               Compliance Oversight, prepared for U.S. EPA,
               prepared by TRC Environmental Corporation, January
               24, 1994. (Note: This document is CONFIDENTIAL. It
               is located at U.S. EPA Superfund Records Center,
               290 Broadway, 18th floor, N.Y., N.Y. 10007-1866.)

P.   300365 -  Letter to Mr. Robert Finke, ICF Technologies, from
     300379    Mr. John Birri, Chief, Inorganic Chemistry
               Section, Technical Support Branch, 'U.S. EPA,
               Region II, re:  Enclosed results of the Goldisc
               Recording sampling survey conducted by ICF
               Technologies during the week of September 5, 1994,
               November 4, 1994.  (Attached: Sampling data for the
               Goldisc Recording Site, November 4, 1994.)

-------
 3.3  Work  Plans
 P.    300380  -  Report:  Final Phase II Work Plan. Remedial
      300551    Investigation and Feasibility Study. Former
               Goldisc Recordings Facility. Holbrook. New York.
               Volume 1 of 2. prepared for Electrosound Group,
               prepared by ERM Northeast, December, 1991.

 P.    300552  -  Report:  Final Phase II Work Plan. Remedial
      300566    Investigation and Feasibility Study. Former
               Goldisc Recordings Facility. Holbrook. New
               York. Volume 2 of 2. prepared for Electrosound
               Group, prepared by ERM Northeast, December, 1991

 3.4   Remedial Investigation Reports
P.
P.
P.
P.
P.
     300567 -  Report:  Site Analysis. Goldisc Recording. Inc..
     300596    Holbrook. New York, prepared by Ms. Melissa
               Simpson, Imagery Analyst, The Bionetics
               Corporation, December, 1987.

     300597 -  Report:  Final Field Oversight Summary Report.
     300741    RI/FS Compliance Oversight. Goldisc Recordings.
               Islip. New York, prepared for U.S. EPA, prepared
               by TRC Environmental Corporation, April 12, 1994.
               (Note: This document is CONFIDENTIAL. It is
               located at U.S. EPA Super fund Records Center, 290
               Broadway, 18th floor, N.Y., N.Y. 10007-1866.)

     300742 -  Federal Register, Vol. 60, No. 125, Rules and
     300744    Regulations, Thursday, June 29, 1995.
     300745 -
     300839
          Report:  Final Baseline Risk Assessment. Former
          Goldisc Recordings Facility, Holbrook. New York.
          prepared for Electrosound Group, prepared by ERM-
          Northeast, August, 1995.
                        Phase II Remedial
300840 -  Report:
301278    Former Goldisc Recordings Facility
Investigation Report
         Holbrook.
                                                             New
               York, prepared for Electrosound Group, prepared by
               ERM-Northeast, August, 1995.

4.3  FEASIBILITY STUDY

4.3  Feasibility Study Reports

P.   400001 -  Report:  Final Feasibility Study Report.
     400331    Former Goldisc Recordings Facility. Holbrook. New
               York, prepared for Electrosound Group, prepared by
               ERM-Northeast, August 15, 1995.

-------
7.0  ENFORCEMENT

7.3  Administrative Orders

P.   700001 -  Administrative Order on Consent for Remedial
     700042    Investigation/Feasibility Study, in the Matter
               of: The Goldisc Recording Site, First Holbrook
               Company, Electrosound Group, Inc., Respondents,
               Index No. II CERCLA-10218, June 27, 1991.

8.0  HEALTH ASSESSMENT

8.3  Correspondence

P.   800001 -  Memorandum to addressees, from Tudor T. Davies,
     800002    Director, Office of Science and Technology (4301),
               re: Interim Draft Health Advisory for Nickel, July
               10, 1995.

10.0 PUBLIC PARTICIPATION

10.2 Community Relations Plans

P.   1000001-  Plan:  Community Relation Plan. Community
     1000042   Relations Support. Goldisc Recordings. Islip. New
               York, prepared for U.S. EPA, prepared by TRC
               Environmental Corporation, February 9, 1993.

10.9 Proposed Plan

P.   1000043 - Plan:  Superfund Proposed Plan. Goldisc Recordings
     1000052   Site. Town of Islip. Suffolk County. New York.
               prepared by U.S. EPA, Region II, August, 1995.

-------
        APPENDIX IV




STATE LETTER OF CONCURRENCE

-------
NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION
50 Waif Road. Atony, lew Ywh 12233
    Ms. Kathleen Callahan
    Director
    Emergency & Remedial Response Division
    U.S. Environmental Protection Agency
    Region II
    290 Broadway
    New York, NY 10007-1866
                                                      SEP 28 1995
                              Re: Goldisc Recordings Site TD No. 152022
                                 Record of Decision
                                                                                   Mithtel 0. Zagiu
                                                                                   Comnistmntr
    Dear Ms. Callahan:
          The New York State Department of Environmental Conservation has reviewed the record of
   decision for the Goldisc Recordings site. The Department concurs with the selected remedy of
   Alternative SR-IJ, Limited Action, as it is detailed in the above-referenced document
   457-3976.
       CM  UI
       CM  C_>
«-   o
0-   ,,-,

co   r."
Cv!   p

fc   O
CO   (JJ
LO   9:
°~   a
                                            above-referenced document.

    If you have any questions, please contact Mr. Jeffrey McCullough, of my staff, at (S18)
                                     Sincerely,

                                          ae (L
                                         ^ Michael 1. 0'Toole, Jr.
                                           Director
                                           Division of Hazardous Waste Remediation
                    PosWf Fax Note
                               7671
                                                    . 0
                     Co
                                      Co.

-------
      APPENDIX V




RESPONSIVENESS SUMMARY

-------
                     RESPONSIVENESS SUMMARY

                Goldisc Recordings Superfund Site
INTRODUCTION
A responsiveness summary  is  required  by  Superfund  regulation.  It
provides a  summary of  citizens'  comments and  concerns  received
during the public comment period, and the United States Environmen-
tal Protection Agency's (EPA's)  responses to those  comments and
concerns.   All comments  summarized in  this  document have  been
considered  in  EPA's final decision for  selection of  a  remedial
alternative for the Goldisc Recordings Superfund site (Site).

SUMMARY OF COMMUNITY RELATIONS ACTIVITIES

Community involvement at the Site has  been low.   EPA took over as
the lead Agency for community relations and remedial activities at
the Site in  1991.  EPA initiated its community relations activities
on March 10, 1991  with  in-person  interviews with local officials
and residents of Holbrook  and Islip.   Based on  these interviews,
the  key issue  of  concern  centered  around  the possibility  of
contamination  of  the  Suffolk  County  Water  Authority  (SCWA)
Wellfield,   which  is located  only  1200 feet downgradient  of the
Site.

The remedial investigation,  feasibility  study,  and  baseline  risk
assessment reports, as well as the Proposed Plan  for the Site,  were
released to the  public  for  comment on August  26,  1995.   These
documents were made available to the public in the administrative
record file at the EPA Docket Room in Region II, New York and the
information repositories  at  the Islip Town  Hall and  the  Sachem
Public Library.  A press release announcing the proposed action was
issued on August 30, 1995  to local media  outlets.   The notice of
availability for the above-referenced  documents was  published in
the Suffolk County News on September 7, 1995.   The public comment
period  on   these  documents  was held  from  August  26,  1995  to
September 26,  1995.

On September 11,  1995,  EPA conducted a public meeting at the Islip
Town Hall West Auditorium,  to inform local  officials and interested
citizens  about  the  Superfund  process,   to  discuss  remedial
alternatives for  the Site,  to present EPA's preferred  remedial
alternative, and  to provide an opportunity  for the  interested
parties to present oral comments and questions to EPA.

Attached  to   the   Responsiveness  Summary  are  the   following
Appendices:

     Appendix A - Proposed Plan

     Appendix B — Public Notice

-------
     Appendix C - September 11, 1995 Public Meeting Attendance
                  Sheets

     Appendix D - Letters Submitted During the Public Comment
                  Period

SUMMARY OF COMMENTS AND RESPONSES

Comments  expressed  at  the  public  meeting and  written comments
received  during  the public comment period from counsel  and the
consultant  representing ElectroSound Group,  Inc.  and  the First
Holbrook  Company, as well as  counsel  representing  the Red Ground
Corporation, have been categorized as follows:

     A.   Selected Remedy Issues

     B.   Health Effects Issues

     C.   General Enforcement Issues

     D.   Groundwater Issues

A summary of the comments and  EPA's responses to the comments is
provided  below.

A. Selected Remedy

Comment #1:  A resident asked  how  the cubic  volume of soil to be
removed   from  the  Site  was   determined  and  if  that  amount
corresponded to the  amount of wastes known to have been discharged
on the Site.

Response #1:  There are three distinct areas targeted for sediments
and/or soil removal on  the Site.   For sediments  and soils in the
various drywells, the analytical data were used  to determine the
depth  of  removal.   It  was determined  that removal  of  the first
three feet from each of the six drywells in Area of Environmental
Concern (AEC)  2 and  drywell  (DW) 2  in AEC  14 would remove the most
significant contamination.  Post removal  levels of nickel remaining
in AEC 2 would be below 70 parts per million (ppm), which is within
typical background ranges.   Removal of the top two feet from DW-2
in AEC 14 would remove concentrations  of benzo(a)anthracene and
chrysene to below the New York State recommended cleanup levels for
protection of groundwater.  A total of approximately 39 cubic yards
of sediments and/or  soils would be  removed from these features for
off-site  disposal.

Analytical data  collected  from nine separate sampling locations
were used to determine  which surface soil locations within AEC 8
required remediation.  The estimate of soil to be  removed was based
on excavating soils to a depth of two feet, around the first four
sampling locations (approximately 2900 square feet), which detected

-------
the highest levels of nickel and  chromium.   This  would result in
the removal of approximately 215 cubic yards of surface soils which
would  be  transported  off-site  for  disposal.     In  addition,
approximately 17 cubic yards of sediments would be  removed from the
former production well vault, designated as AEC 12.  This estimate
is  based  on   the  presence   of   approximately   three  feet  of
contaminated sediment in a 10 feet by 15 feet vault.

In total,  the  three areas targeted  for removal  would  result in
approximately 271 cubic  yards of sediments/soils requiring removal
for off-site treatment (as necessary) and disposal.

It is  not  possible to  determine  exact quantities  of  illegal or
inappropriate discharges that  were made on  the Site  by previous
operators  15  to  25  years ago.    It is  important to  note  that
sediments/soil   targeted   for   removal  and off-site  disposal
represents the  most significant contamination currently found on
the Site.   It is EPA's intention that removal  of this material will
prevent further  cross-media impacts to the underlying groundwater.

Comment #2:  A resident  asked where the  contaminated sediments and
soils that are to be removed from the Site will  be disposed.

Response #2:  The final disposal facility will be selected during
the remedial design or remedial action phase of  the project.  EPA
and the New  York State Department  of Environmental Conservation
(NYSDEC) will ensure that the selected facility is  fully permitted
to handle the sediments/soils  and  is in full compliance with all
applicable laws governing its operations.

Comment #3:  A resident asked why, if no unacceptable risks exist
with the on-site  sediments and soils,  is EPA proposing to remove
any of the sediments and soils from the Site.

Response |3:  Most of the sediments and  soils targeted for removal
from  the   Site  are  inaccessible.    Because of  this,  the  risk
assessment performed concluded that the sediments  and soils do not
pose any unacceptable additional risks.  However, EPA believes that
contamination detected  in these sediments  and soils continues to
impact the underlying groundwater.   The major contaminant in the
sediments and soils,  nickel,  has been detected at  very high levels
in the  underlying groundwater.   It  is EPA's  intent  to  prevent
further cross-media impacts, i.e.,  continuing degradation of the
underlying groundwater from sources of nickel in the Site sediments
and soils.

Comment #4: A resident asked whether EPA had tested the Sans Souci
Lakes, downgradient of the Site and, if so, what the findings were.

Response  #4:     The  Sans  Souci  Lakes,  a   state  and  federally
designated wetland, is  located  approximately  1/2 mile south of the
Site.  The NYSDEC surface water classification  for Sans Souci is

-------
Class B, which  means  the waters are best suited for recreational
purposes and not  a  source of  drinking water.   The Phase  I RI
involved collection of surface water and sediment samples from four
separate locations. During the Phase II RI,  samples were collected
from five additional locations.  Results of sampling indicated that
the only contaminant detected at levels which could have potential
impacts to  the  wetland was  lead;  the levels  of  lead  found were
typical of  soils collected near major roadways.   Lead is  not a
contaminant  of  concern  at  the  Site.   Therefore, it was concluded
that there  has  been  no impact to  the wetland  from  the  Goldisc
Recordings site.

B.  Health Effects Issues

Comment #1:   A resident asked  what the dangers  are  to  children
playing  in   the wooded  area  to  the  north of  the  two  on-site
buildings.

Response #1:  The  wooded area  north of the two on-site buildings
was sampled  during both Phase  I and Phase  II  of  the RI.   A risk
assessment conducted  during  Phase I  evaluated potential  impacts
resulting from children ingesting soil at the Site, including those
soils north  of  the building;  the  assessment  indicated that the
soils did not pose an unacceptable risk.  A second assessment was
performed during Phase II  to supplement the Phase  I assessment.
This supplemental work assessed the impacts  posed to children from
dermal contact with soil; the assessment indicated that these soils
did not pose an unacceptable risk.

Comment #2:   A  former Goldisc  Recordings employee inquired about
the health risk to those working in the facility at the height of
its operations.

Response #2:  The risk assessment performed  for the Site evaluated
data  collected  during the   Phase   I  and  Phase  II  remedial
investigations  and only addressed  current and  potential  future
risks.   In order to assess risks of past exposure, EPA would need
historical  data  from the time frame of concern.   Because EPA is not
in possession of the  necessary historical  data and  information,
this determination cannot be made.

C. General  Enforcement  Issues

Comment  #1:     A   resident  asked   about  who  would   pay  for
implementation  of the remedy, and if there were any legal actions
EPA could take  against  the former owners of the Site.

Response #1: Both the  Phase I and Phase II remedial investigations
and feasibility studies have  been performed  by  two potentially
responsible  parties  (PRPs),   namely,   ElectroSound  Group,  Inc.
(parent company to Goldisc  Recordings)  and   the  First  Holbrook
Company (past owner of  the property).  These PRPs have cooperated

-------
with both  NYSDEC  and EPA and  have  signed Orders on  Consent  for
performance of these  tasks.   After selection of  the  remedy,  EPA
will notify these  two PRPs,  and  the  other PRPs at the  Site,  of
their liability at the Site, and  request  that the PRPs voluntary
finance or implement the remedy.  If the PRPs fail to voluntarily
agree to finance or implement the remedy, EPA can order the PRPs to
do so.   Alternatively, EPA can utilize the  Superfund to finance the
remedy and subsequently take legal actions to recoup costs incurred
in implementing the remedy.

D.  Groundwater Issues

Although the  Proposed Plan only  addressed  remedy  selection  for
sources  of contamination  at  the Site,  there were  significant
comments   made  by  interested  parties   regarding   the  Site's
contribution to the contamination of the groundwater,  the impacts
of this contamination on the SCWA's  Church Street Wellfield,  and
EPA's decision to  defer the selection  of a  remedy for groundwater.
During  the public meeting EPA was assisted in responding to a
number of these concerns by representatives from the Suffolk County
Department of  Health Services  (SCDHS)  and  the SCWA.   EPA  also
received written comments from the PRPs and the PRP's consultant on
related issues.   The key concerns raised are summarized below.

Comment #1: Residents questioned  whether  any agencies involved in
the site investigation could explain  the  condition  or quality of
the local drinking  water during the height  of Goldisc's operations,
and when the leaching of contaminants,  particularly nickel,  from
the Site into the  groundwater  had begun to pose a problem at the
Church Street Wellfield.

Response #1:   It was noted that a Safe  Drinking Water Act maximum
contaminant level  (MCL)  did not exist  for  nickel until 1992 (note:
this MCL  was  subsequently  remanded  and  replaced with  a Health
Advisory set at the same level) . During the conduct of  the  Phase II
RI, nickel levels  in  Church  Street (CS)  well  number  2 (CS-2), a
well in the Upper Glacial Aquifer, did  exceed the MCL; nickel was
also detected  in CS-1  (also in the Upper Glacial  Aquifer) at levels
well below the MCL; nickel was not  detected in CS-3,  which draws
water from the deeper Magothy Aquifer.   Nickel is  the only Site
contaminant that is known to have impacted the wellfield.  It was
first determined to be a problem in CS-2  in  sampling  conducted in
1993, however,  the well was not in service at that time due to an
organic  contamination problem  associated  with a  nearby Sunoco
gasoline station.   The water from CS-2  has subsequently been used
at times of peak demand; in such instances it is blended with water
from CS-1  or  CS-3 prior  to  distribution.   Sampling of  CS-2 in
August of 1995 indicated that the levels of nickel  had  decreased to
below 100 ppb which is the former MCL and  current Health Advisory
level.

-------
During  the  public meeting, Mr.  Miller from SCWA  noted  that the
authority was not  required  to  test  for nickel  as part  of its
routine monitoring  program prior to 1993.  The  Authority did do
some random sampling  for  nickel  prior  to that  date, and as noted
previously,  first identified nickel levels of concern in 1993.  Mr.
Miller noted  that while  significant  information  is not available
regarding the presence of  nickel prior to 1993,  it is unlikely that
people were exposed to significant levels of nickel  due to the way
in which the water is distributed by SCWA.  He explained that the
wellfield has utilized three wells since the early 1970's, and that
on most  occasions  the water  from  the  wells is  blended  prior to
distribution.  In fact there are  fifteen  wells  located within five
miles of the Church Street Wellfield which are -often blended under
various scenarios prior to distribution.

Mr. Steven  Calobufo,  senior hydrogeologist with SCWA,  indicated
that he did not believe that there was a contamination problem at
the wellfield prior  to  the  detection  of  nickel  in  1993.   He
indicated  that  it   would  take   at   least   15   years  for  the
contamination  to travel  from the Site  to the  intakes  for the
wellfield.

Since the levels found at  CS-2 have been very  close to (and most
recently below) the Health Advisory, it is unlikely that residents
were exposed to levels above the Health Advisory,  and if they were,
the frequency/extent of exposure  was likely to be inconsequential.
This is because MCLs and Health Advisories are developed using very
conservative  assumptions.    It  is  typically  assumed  that  the
population drinks 2 liters of  water each  day for  thirty years over
a seventy-year lifetime  and,  in the case of the  nickel  MCL and
Health Advisory, that the population would obtain no more than 20%
of its daily acceptable nickel consumption from drinking water.

Comment #2:   Counsel for ElectroSound and  First Holbrook, their
consultant ERM,  and Red Ground Co./Red Ground  Corp. (Red Ground)
provided  written comments explaining  their objections  to EPA's
decision to defer  remedy selection for  Site groundwater.   These
parties claim that EPA's decision to bifurcate the remediation is
arbitrary and capricious.  Red Ground further contends that there
is no technical or scientific basis for this bifurcation.

Response #2:   EPA's  decision to defer remedy  selection for Site
groundwater is appropriate,  within our  discretion and supported by
case law.   It is appropriate  for  EPA  to defer  the decision for
several reasons that were  described in the Proposed Plan and at the
public meeting.  These include: the concentration  of .nickel  (deemed
to  be  the  major  contaminant of  concern at  the  Site)   in the
groundwater  increased  dramatically as   evidenced by  the  1994
sampling event (which indicated a maximum nickel concentration in
the groundwater of  approximately 959  ppb);  the  Church Street
Wellfield has and continues to be impacted by nickel contamination;
and the groundwater modeling  as  performed by  the PRPs consultant

-------
(ERM)  indicates that levels  of nickel reaching the wellfield could
potentially triple  in the  future.   It is appropriate  for  EPA to
defer its  decision  until  such time when additional  test results
better define  whether  additional  measures  are warranted.   EPA's
decision arises out of a legitimate concern for the public health,
and is a fair and reasonable approach for ensuring the protection
of  the  Church  Street  Wellfield  given the  need  for  additional
information and the uncertain  accuracy  of  groundwater  modeling
efforts.

Comment #3:   The parties,  identified  in Comment  #2  above,  were
concerned that  EPA  has not  specified  any reasonable  timetable in
which to  gather the additional  information nor  recommended any
alternate remedy which may be implemented within a specified time
frame.  Red Ground also  claimed that  deferring  the  remedy could
impact EPA's  ability to  recover  response cost  from two  of the
bankrupt PRPs, and could also impact Red Ground's ability to sell
the property.

Response  #3:    It  is anticipated  that a groundwater  monitoring
program will be initiated  this fall and continue for approximately
a year.   After such time,  the sampling data will be evaluated and
remedies  explored;   remedial  alternatives  to  be evaluated  are
expected  to  include  at  a minimum,  those  identified  in  the
Feasibility Study (FS).   It is envisioned that the results of the
additional work would be documented in  a brief addendum to the FS;
any new alternatives would  also be documented  in this addendum.
The remedial action for groundwater, if one is authorized by EPA,
will then be implemented as  soon as Site data and  information make
it possible.

It is our position that the further monitoring is necessary given
the factors stated  above  and will  address  the many uncertainties
associated with the site that may be impeding the financing or sale
of the property.   While  cost recovery is an  important issue for
EPA,  it  does  not  take  precedence over  our  duty  to  protect the
health and safety of the public.

Comment #4: The parties identified in Comment #2  believed that EPA
failed to identify any particular  threat  or harm to public health.
They also indicated their belief that EPA was relying on a Health
Advisory  to  make the determination  to defer  groundwater remedy
selection, and objected to the use of the Health Advisory for this
purpose.   Additionally, they allege that EPA's actions in deferring
selection of the remedy are inconsistent with its own regulations
and procedure.

Response  #4:   The  highest level of nickel found at  the site was
found in  the  most  recent  sampling event  (September  1994) .  This
level of   980  ppb  was  confirmed  via a  duplicate  sample  which
indicated 959 ppb.  This level  exceeds  the risk based number of 730
ppb which was  developed  in  accordance  with  EPA guidance for

-------
conducting risk assessments at Superfund sites.

Samples collected from several wells also exceeded the nickel MCL
of  100  ppb  which was in effect  when  the September 1994 sampling
event was  conducted.   As  noted  above,  this MCL  was  remanded in
February 1995  and subsequently  replaced with an interim Health
Advisory set at the same level.  The MCL and Health Advisory were
set  at  more stringent levels  than the Site  specific risk based
number  due  to  more conservative assumptions  utilized during the
development  of  the number.   Concentrations of nickel  have been
detected at two of the Church Street wells,  namely, CS-1 and CS-2.
Levels detected at CS-2 have exceeded  the Health Advisory, causing
the  SCWA to modify  its  water  distribution  operations.    SCWA
continues to modify  its  operations,  based upon  direction being
provided by  the New  York  State  Department of Health,  the State
agency  responsible   for   ensuring that  water  distributed  to
communities  is safe for consumption.

Although the levels of nickel  in both of the  impacted wells were
recently determined to be below the Health Advisory (the levels at
CS-2, 95  ppb and  98 ppb,  were  only  slightly below  the Health
Advisory) there is  still  significant  concern that  the  highest
levels  of contamination  have not yet reached  the wellfield.   In
fact, the PRPs consultant,  ERM, notes  in the FS that the plume has
moved a  considerable distance since 1989 and that "solute transport
groundwater modeling of the nickel plume at the Site, conducted for
the  FS  and  presented in  Section  Dl. 4.1 of  Appendix D  to this
document,   indicates   that   "...   the  maximum   future   nickel
concentration in groundwater at the Church Street Wellfield will
be 325 ug/1." This level is 3 times the Health Advisory and former
MCL and higher than any level yet seen at the wellfield.

While the   Health  Advisory  is  intended  to   serve   as  informal
technical guidance and not a legally enforceable federal standard,
the  Agency  had identified  the  Health  Advisory as  a   "to  be
considered"  (TBC) criterion.   In arriving  at  a decision to defer
the  groundwater  remedy,  EPA has not  only  considered  this Health
Advisory, but has taken several other factors into  account as well,
including  the  Site-specific  risk  assessment,  the  increasing
concentrations of nickel  found in the latest round  of sampling, the
existing impacts and  burden placed upon the  SCWA as  a result of
contamination  reaching  the  wellfield,    and the  uncertainties
related to  modeling the potential future impacts to the wellfield.
Given the  above, EPA believes  it  is prudent, appropriate,  and
consistent  with  its  regulations  and  procedures to defer  the
groundwater  remedy until the  fate  and transport of the nickel in
the groundwater can be better defined.

-------
 APPENDIX A
PROPOSED PLAN

-------
   Superfund Proposed Plan
                                                      Goldisc  Recordings  Site
                  EPA
                  Region 2
                     Town of Islip
               Suffolk County, New York


                            August 1995
PURPOSE OF PROPOSED PLAN

This Proposed Plan describes the remedial
alternatives considered for addressing contamina-
ted sediments and soils at the Goldisc Recordings
Superfund site and identifies the preferred remedial
alternative with the rationale for the preference.
The Proposed Plan was developed by the U.S.
Environmental Protection Agency (EPA), as lead
agency, with support from the New York State
Department of Environmental Conservation (DEC).
EPA is issuing the Proposed Plan as part of Its
public participation responsibilities under Section
117(a) of the Comprehensive Environmental
Response, Compensation, and Liability Act
(CERCLA) of 1980, 42 U.S.C. §§ 9601-9675, and
the National Contingency  Plan (NCP), 40 C.F.R. §
300.430(f). The alternatives summarized here are
described in the feasibility study report which
should be consulted for a more detailed description
of all the alternatives.

This Proposed Plan is being provided as a
supplement to the remedial  investigation and
feasibility study (RI/FS) reports to inform the public
of EPA's and DEC's preferred remedy and to solicit
public comments pertaining to all the remedial
alternatives evaluated, as well as the  preferred
alternative.

The remedy described in this Proposed Plan is the
preferred remedy for the she. Changes to the
preferred remedy or a change from the preferred
remedy to another remedy may be made, if public
comments or additional data indicate that such a
change will result in a more appropriate remedial
action. The final decision regarding the selected
remedy will be made after EPA  has taken into
consideration all public comments. We are
soliciting public comment on all of the alternatives
considered in the detailed analysis of the RI/FS
because such comments  may influence EPA's and
DEC's selection of the final remedy.
COMMUNITY ROLE IN SELECTION PROCESS

EPA and DEC rely on public input to ensure that
the concerns of the community are considered in
selecting an effective remedy for each Superfund
site. To this end. the RI/FS reports, Proposed
Plan, and supporting documentation have been
made available to the public for a  public comment
period which begins on August 26, 1995 and
concludes on September 26,1995.


Copies of the RI/FS reports, Proposed Plan
and supporting documentation are available
at the following locations:

Islip Town Hall
655 Main Street
Islip. New York   11751
Tel. (516) 224-5490
Hours:  Mon-Fri: 8:30 am to 5:00 pm

Sachem Public Library
150 Holbrook Road
Holbrook, New York  11741
(516) 588-5024
Hours:  Mon-Thurs: 9:00 am to 9:00 pm
       Fri & Sat: 9:30 am to 6:00 pm
       Sun: 12:00 pm to 4:00 pm
A public meeting will be held during the public
comment period at the Islip Town Hall West. 401
Main Street, on Monday, September 11,1995 at
7:00 p.m. to present the conclusions of the RI/FS,
to elaborate further on the reasons for
recommending the preferred remedial alternative,
and to receive public comments.

Comments received at the public meeting, as well
as written comments, will be documented in the
Responsiveness Summary section of the Record of
Decision (ROD), the document which formalizes
the selection of the remedy.

-------
    DATES TO REMEMBER

    August 26, 1995 to September 26, 1995
    Public^ comment period on RI/FS report
    and Proposed Plan  :

    September 1i;;i995- 7:00 p.m.
    Public meeting at/the
    Islip town Hall West "Auditorium
    401 Main Street; ?:;^
   !:lslip,'New York.  .;•
                   Figure 1.
     Goldisc Recordings Superfvmd Site
All written comments should be addressed to:

                Janet Cappelli
                Project Manager
      U.S.  Environmental Protection Agency
            290 Broadway. 20th Floor
           New York, New York 10007
                (212) 637-4270

SITE BACKGROUND

The Goldisc Recordings Superfund site (Site) Is
located at the Intersection of Veterans Memorial
Highway and Broadway Avenue in Islip. New York.
The 34-acre Site consists of two one-story
buildings that occupy six acres, three acres of
pavement surrounding the buildings, and twenty-
five acres of undeveloped land. Current zoning at
the Site is retail/commercial. The area surrounding
the Site is primarily residential and mixed  forest,
with some commercial and light industrial
development. The Site is bordered to the north
and east by mixed forest, to the south by Veterans
Memorial Highway, and to the west  by Broadway
Avenue (see Figure 1).

A municipal water supply wellfield, which provides
drinking water for the Suffolk County Water
Authority, is located approximately 1,200 feet south
of the Site on Church Street. The closest
dwellings are located about 700 feet north of the
Site. A New York State regulated wetland is
located approximately one-half mile south of the
Site. A Sunoco gasoline station is located on the
southeast comer of Veterans Memorial Highway
and Broadway Avenue, just south of the Site.  Soil
and groundwater remediation systems are currently
in operation at the station, to address a release of
petroleum product to the groundwater.

From 1968 to 1990, the two buildings were
occupied by several different companies that
generated and  stored hazardous substances on the
Site. These companies included Goldisc
Recordings. Inc. (Goldisc), which produced
phonographic records; ElectroSound Group, Inc.
(Electrosound), a company that manufactured
    uadrangto: Patehoque, New York, 19675
audio visual and optical devices; and Genco Auto
Electric, Inc. (Genco), which rebuilt automotive
engine parts.  The First Holbrook Company (First
Holbrook) owned the property from 1973 to 1985.
In 1985. the Red Ground  Corporation became the
owner of the property.  The two tenants occupying
the  buildings since 1990 are dry goods merchants
and do not  perform any manufacturing.

The substances known to have  been disposed of
on the Site between 1968 and 1990 include
wastewater from the various production processes,
waste oils, metals, solutions containing high
concentrations of xylene  and trichloroethylene, and
other degreasing agents. These substances were
reportedly discharged to  the environment through
dry wells, leaching pools, storm drains, and leaking
storage containers located around the buildings.

Since the late 1970s, the Suffolk County
Department of Health Services (SCDHS),  DEC, and
EPA have conducted various inspections  and

-------
environmental protection enforcement activities at
the Site.  In 1978. a representative from the SCDHS
inspected the Site and noted stains, puddles, and
leaking drums suspected to be related to industrial
wastes.  In the early 1960s, the SCDHS collected
samples from leaching pools, storm drains, and
cesspools located on the Site.  Laboratory analyses
of the samples revealed violations of New York
State Qroundwater Effluent Guidelines. Between
1981 and 1983, laboratory analyses of groundwater
samples  collected from monitoring wells located
on-slte revealed elevated levels of solvents and
metals, including: trichloroethane, trichioroethylene.
tetrachloroethylene, lead, nickel, chromium, and
silver. Analyses of samples obtained from the
Church Street wellfield showed concentrations  of
tetrachloroethylene slightly exceeding the Maximum
Contaminant Level (MCL) of 5 parts per billion
(ppb) for public drinking water.  Based on these
findings,  the Site was added to the EPA National
Priorities List (NPL) In June 1986.

In 1988, DEC entered into an Administrative Order
on Consent (AOC) with two of the potentially
responsible parties (PRPs), namely, First Holbrook
and ElectroSound. The AOC required the two
PRPs to  conduct an Rl at the Site as required
under CERCLA.  The Rl (Phase I Rl) was
conducted In 1988 and included the Investigation of
nineteen areas of potential contamination.
Groundwater and soil samples were collected and
analyzed to determine the nature and extent of
contamination in these areas. Elevated levels of
lead and tetrachloroethylene were found in
groundwater samples.  Soil samples were found to
contain elevated levels of several metals, volatile
organic compounds, and semi-volatile organic
compounds.

Based on a review of the results, EPA and DEC
determined that additional  information was
necessary in order to better define the extent of
contamination at the Site.  In late 1990, DEC
requested that EPA take over as lead agency for
the Site.  EPA notified First Holbrook,
EiectroSound, and Red Ground of their potential
liability at the Site and requested they finance or
undertake the continuing RI/FS.  Red Ground
refused to enter into negotiations with EPA to
conduct additional RI/FS activities. Subsequently,
In 1991,  EPA entered into an AOC with First
Holbrook and ElectroSound.  This AOC specifically
required the  PRPs to conduct a supplemental
RI/FS (or Phase II RI/FS).
SCOPE AND ROLE OF ACTION

It was EPA's original intention to supplement
previous data collected under state and county
investigations In order to address both sediments
and soils contamination and contaminated
groundwater attributable to the Site.  However, due
to circumstances which occurred as the Phase II
RI/FS progressed, EPA and DEC have decided to
defer the decision regarding groundwater
remediation. The MCL for nickel, which Is the
primary contaminant at the Site, was remanded in
February 1995.  In addition, the concentration of
nickel has fluctuated in the groundwater. While the
Church Street wellfield has been Impacted by
nickel contamination, recent data indicate that
nickel concentrations have dropped below the
current Health Advisory level of 100 ppb. As a
result,  EPA and DEC decided to obtain additional
information and data on the nickel contamination in
the groundwater.

The proposed remedy described in this document
addresses the contamination associated with Site
sediments and soils.  The remedial goal Is to
ensure that concentrations of contaminants in the
sediments and soils are at levels which are
protective of human health and the environment.
EPA intends to collect additional information and
data on nickel contamination In the aquifer in order
to identify appropriate remedial measures to
address this contamination.

REMEDIAL INVESTIGATION SUMMARY

Under the direction of EPA, the PRPs1 contractor.
ERM-Northeast, implemented a supplemental Rl to
characterize further the sediments and soils, and
groundwater at the Site.  The intent of the study
was to fill data gaps identified during review of the
DEC Phase I Rl report.  Groundwater data
collected as part of the Phase II RI/FS is provided
below, as Is data for sediments and  soils.

Sediments. Soils. Storm Drains, and Drvwells

The Phase I Rl  identified  19 separate soil Areas of
Environmental Concern (AEC), which included
storm drains, drywells, a  sump, drum storage
areas, sanitary discharge areas, a transfer pad
area, and a former production  well.  Phase I
sampling of AECs 3, 4, 6, 7, 17, and 18 determined
that these areas had not been  significantly
 impacted.  Therefore, no additional Phase II
sampling was performed in these areas. Likewise,
 Phase I sampling adequately defined the impacts
to AECs 2, 9.11, and 12. Therefore, no additional

-------
Pt.ase II sampling was performed in these areas.
and were not detected at lower intervals.
The Phase I data indicated that the highest levels
of contamination were found in AEC 2. AEC 2
consists of an interconnected system of 6 drywells
which allegedly received direct discharges from the
Goldisc building, as well as spillage from  a drum
storage area.  Chromium was detected in
sediments and soils at levels ranging from 30 parts
per million (ppm) to 195 ppm. Nickel was found at
levels ranging from 25 ppm to 1.120 ppm.
Phase II involved the  collection of additional
surface and subsurface soil samples from 9 AECs.
During May 1993. 7 soil borings were drilled. 3 test
trenches were excavated, and 46 surface and
subsurface samples were collected for physical and
chemical analyses. Together with  earlier  data.
Phase II sampling confirmed that AECs 1, 5.  8, 10,
13. and 14 were also  impacted by  Site-related
contamination.  Based on the Phase II data, AECs
la, 15 and 16 were not considered to have been
significantly impacted.

The Phase II results for AEC 1 confirmed  the
presence of total petroleum hydrocarbons (TPHCs)
in the three solid-bottom storm drains and the base
of the receiving drywell.

Previous data for AEC 5 indicated  nickel In
sediments slightly above Site background and
TPHCs at levels up to 93.000 ppm at the  drainage
pipe  outfall.  Phase II involved collection of
samples from the base of 2 drywells and  2 storm
drains to characterize the TPHC content.  The
samples contained TPHCs ranging from 406 ppm
to 5,780 ppm.  In addition, it appeared that the
drainage system had  been impacted  by a
petroleum release emanating from the oil-fired
boilers within the former Goldisc building.
Petroleum releases are not actionable under
CERCLA. Therefore,  this AEC has been referred to
the DEC spills program for evaluation and possible
remediation.

Locations previously  showing high levels  of nickel
and chromium in AEC 8 were resampled.
Maximum detected levels for nickel and chromium
in Phase II sampling were 33 ppm and 80 ppm,
respectively, In surface soils. Phase I and Phase II
results confirm that this reported discharge area
had contamination related to Site operations.

A soil boring was taken and analyzed for TPHCs in
AEC 10.  The highest concentration of TPHCs was
detected in the 10-foot to 12-foot interval at 9,240
ppm. Concentrations decreased significantly with
depth to 84 ppm in the 20-foot to 22-foot interval,
Phase II analyses were performed to complete the
delineation of soils impacted by TPHCs in AEC 13.
In one boring, the TPHCs extended to the water
table. It is believed that oil reached  this area
through the Area 5 drainage system pipe. This
AEC has also been referred to the DEC spills
program.

Phase II sampling for AEC  14 included borings and
analyses from three drywells. The uppermost
sediments contained several metals  at
concentrations slightly above background.  Deeper
samples were within background ranges.  The
highest VOC detected was acetone at 0.44 ppm.
Polychlorlnated biphenyls (PCBs) were detected in
all three drywells, the highest concentration at 0.41
ppm.  Drywell #2 in this area contained levels of
chrysene at a concentration of 0.77  ppm and
benzo(a)anthracene at a concentration of 0.5  ppm
in the 15-foot to 17-foot Interval, above the
recommended New York State cleanup guidelines
of 0.4 ppm and 0.224 ppm, respectively.

Groundwater

The Phase I Rl involved the collection of
groundwater samples from 18 on-site monitoring
wells, 1 on-slte production  well, 1 off-site
upgradient well, and the 3 SCWA Church Street
supply wells.  Of the 18 on-site monitoring wells
sampled. 14 are shallow (less than 50 feet deep), 2
are intermediate (75 to 90 feet deep), and 2 are
deep (over 100 feet deep). All on-slte monitoring
wells are installed in the shallow aquifer, the Upper
Glacial aquifer.  The thickness of the Upper Glacial
underlying the Site is approximately 135 feet.
Depth from the surface to the water table ranged
across the Site from 18 to 32 feet.  Church  Street
wells #1 and #2 (CS-1 and CS-2) are both shallow;
installed in the Upper Glacial aquifer.  Church
Street well #3 (CS-3) is much deeper, screened in
the lower Magothy aquifer. The groundwater flow
direction in the northern portion of the Site  is
generally south to southeast. However, the
southeast portion of the Site shows a shift in flow
direction to the southwest  in response to the  radial
drawdown resulting from to operation of the
Church Street supply wellfield.  The groundwater
flow velocity, ranging between 1.3 to 1.7 feet/day
during nonpumping periods, increases to 2.4 to 2.9
feet/day during Church Street pumping operations.

The initial Phase II groundwater sampling effort,
performed in April 1993,  included collection of
samples from 8 of the on-site monitoring wells.

-------
Two of these monitoring wells required
replacement; they were abandoned and new
monitoring wells installed in their place. The
groundwater samples were analyzed for Target
Analyte List (TAL)  metals and/or Target Compound
List (TCL) volatile organic compounds (VOCs), to
fill data gaps or to confirm  Phase I analytical
results. After review of these results, an additional
round of groundwater samples was collected from
a greater number of on-slte wells in order to
Investigate further the presence of heavy metals.  In
September 1994, ERM-Northeast collected samples
from 15 on-slte monitoring  wells and analyzed
these samples  for nickel, chromium, iron, and
manganese.  All 15 samples were split with ICF
Technology Corp.. EPA's oversight contractor, and
analyzed by EPA for all TAL metals.
Comparison of the Phase II groundwater sampling
results with Phase I indicated that the VOC
concentrations had decreased.  For the Phase II
data, the only VOC detected at a concentration
above its drinking water standard was carbon
disulfide in monitoring well 17D (MW-17D).
Analytical results for the split sample from MW-17D
did not Indicate the presence of carbon disulfide
above its drinking water standard. Carbon disulfide
has been determined to be a laboratory artifact and
not a contaminant of concern.

Results of the Phase II first round of metals
analysis collected from eight monitoring wells did
not indicate the presence of metals above any
drinking water  standards. The Phase II second
round of metals analysis, performed on samples
collected from  15  monitoring wells, detected high
levels of nickel, ranging from 13.3 ppb to 959 ppb.
At the time the sampling was performed, the
federal MCL for nickel, which had become effective
on June 17, 1992, was 100 ppb.  In February 1995,
in response to on-going litigation over its validity,
EPA filed a joint motion to remand the nickel MCL
voluntarily.   On June 29,1995, EPA issued a
Federal Register notice formally removing the
nickel MCL from the Code of Federal Regulations.
Currently, no federal or state drinking water
standard exists for nickel.  However, on July 10,
1995, EPA Issued a Health Advisory of 100 ppb for
nickel, while a  new MCL for nickel is being
reestablished.  This Health Advisory is Intended to
serve as informal technical guidance only and is
not to be construed as setting legally enforceable
federal standards.  Of the fifteen wells sampled
during Phase II, only 3 had levels of nickel above
100 ppb, namely.  MW-11 (140 ppb), MW-12 (959
ppb) and MW-16 (278 ppb).  Since an MCL for
nickel does not exist, a health-based action level
was developed for the Site utilizing Superfund risk
assessment methodologies.  This health-based
action level, detailed further in the risk discussion.
was calculated to be 730 ppb. Only one sample,
collected from MW-12 (959 ppb), exceeded this
level.

In late 1993, routine monitoring performed by
SCWA on the Church Street wellfield detected the
presence of nickel in Church Street well #2 (CS-2)
in excess of the then existing 100 ppb MCL This
prompted SCWA to remove CS-2 from service and
conduct testing to determine a suitable method of
remediation for the well.  Sampling of CS-2 In July
1995 and August 1995 revealed decreasing nickel
concentrations of 98 ppb and 95 ppb, respectively.
Since the remand  of the nickel MCL, SCWA has
put CS-2 back into service, blending it with the
other wells, resulting in drinking water which is still
well below the former MCL and current Health
Advisory level of 100 ppb.

Based on its frequent detection at elevated
concentrations at the Site, its former MCL. and the
impact to the Church Street wellfield. nickel has
been deemed to be the major contaminant of
concern at the Site.

The Phase II second round of metals analysis also
detected the presence of both iron and manganese
above their respective secondary drinking water
standards.  Split samples verified these results.
The secondary federal and state MCLs for iron and
manganese are both based on aesthetic properties
and are intended to prevent potential problems,
such as poor taste, odor, and staining of plumbing
fixtures, and do not specifically present a health
risk. The highest  concentrations were reported for
the unfiltered sample collected from MW-11 R.  For
this sample, iron was detected at a concentration
of 34,900 ppb and manganese at a concentration
of 2,840 ppb.  The federal secondary MCLs for iron
and manganese are 300 ppb and 50 ppb,
respectively.  A filtered sample collected from MW-
11R detected Iron and manganese at  reduced
levels of 189 ppb  and 459 ppb, respectively.  In the
filtered sample, manganese was still in excess of
the drinking water standard. However, manganese
is not a contaminant of concern and does not
present a risk; the levels detected represent
background conditions In the area.

SUMMARY OF SITE RISKS

Using the Rl data, a baseline risk assessment was
conducted to estimate the risks associated with
current and future Site conditions. The baseline
risk assessment estimates the human health and

-------
ecological risk which could result from the
contamination at the Site, if no remedial action
were taken.

Health Assessment

As part of the baseline risk assessment, the
following four-step process Is utilized for assessing
site-related human health risks for a reasonable
maximum exposure scenario: Hazard
/denf///catfon-identlfies the contaminants of
concern at the Site based on several factors such
as toxicity, frequency of occurrence, and
concentration. Exposure Assessment-estimates
the magnitude of actual and/or potential human
exposures, the frequency and duration of these
exposures, and the pathway (e.g. ingesting
contaminated well-water) by which humans are
potentially exposed.  Toxicity Assessment-
determines the types of adverse health effects
associated with chemical exposures, and the
relationship between magnitude of exposure (dose)
and  severity of adverse effects (response).  Risk
C/wacfer/rar/on-summarizes and combines
outputs of the exposure and toxicity assessments
to provide a quantitative (e.g., one-in-a-million
excess cancer risk) assessment of site-related
risks.

The  baseline  risk assessment began with selecting
contaminants of concern which would be
representative of Site risks. These contaminants
included tetrachloroethylene,  1,1-dichloroethane,
1,1,1-trichloroethane, vinyl chloride,
benzo(a)anthracene, chrysene, cadmium, copper.
lead, nickel, and zinc.

Four exposure pathways were evaluated under
possible on-site present and future land  use
conditions. The site was assumed to retain Its
current zoning status of commercial/Industrial.  The
exposure  pathways considered were: dermal
absorption of chemicals in the soil by children
trespassing on the Site, direct contact (including
incidental Ingestion and dermal absorption) with
soils by on-site commercial/  industrial employees,
direct contact with soil by future short-term
construction  workers, and domestic use of
groundwater (including Ingestion and inhalation of
volatiles by nearby residents  using the Church
Street wellfield as the exposure point).

EPA's acceptable cancer risk range Is 10"4 to 10*
which can be Interpreted to mean that an individual
may have a one in ten thousand to a one in a
million increased chance of developing cancer as a
result of a site-related exposure to a carcinogen
over a 70-year lifetime under the specific exposure
conditions at a site.  The results of the baseline risk
assessment indicate that the soils  and groundwater
at the Site pose no unacceptable carcinogenic risk
to human health.  The overall carcinogenic risk for
on-site workers, through direct contact with soils, Is
estimated to be 8.5 x 10'' (risk of 8.5 in 100
million).  The overall carcinogenic  risk for future
construction workers, through direct contact with
soils, is estimated to be 4.3 x 10*  (risk of 4.3 in a
billion).  The overall carcinogenic risk for domestic
use of groundwater, through ingestion and
inhalation, is estimated to be 9.5 x 10* (risk of 9.5
in a million).  Much of this risk is attributable to
vinyl chloride, which was not detected In recent
sampling events at the Church Street supply
wellfield or  on the Site. The preceding risk values
indicate that the Site poses no unacceptable
carcinogenic risk to human health. The dermal
exposure pathway for  children  was not evaluated
for carcinogenic health effects  because there were
no contaminants of concern detected which are
potential carcinogens via dermal exposure.
Therefore, no adverse effects are expected to result
from chronic exposure by these pathways to
chemicals from the Site based on their
carcinogenic properties.

To assess the overall potential  for noncarclnogenlc
effects posed by the contaminants at a site, EPA
has developed the hazard index (Hi). The  HI
measures the assumed simultaneous subthreshold
exposures to several chemicals which could result
in an adverse health effect.  When the HI exceeds
1.0. there may be concern for potential
noncarcinogenic health effects.

The calculated HI values for the dermal absorption
and direct contact pathways were all calculated  to
be less than 1.  Dermal absorption by nearby
children contributed to an HI value of 0.0002, direct
contact by  on-site workers contributed to an HI
value of 0.002 and direct contact by future workers
contributed to an HI value of 0.03. Domestic use
of groundwater contributed to  an  HI value  of 0.26;
nickel was  the major contributor to this HI.  As
noted below, this calculation assumes that there
are no appreciable sources of nickel exposure
outside of groundwater ingestion.

As noted In the Rl Summary section, the MCL for
nickel was  remanded  in February 1995.  Due to the
fact that significant nickel contamination exists In
the Upper Glacial Aquifer,  potential risks related to
this contamination were closely evaluated. An
acceptable health-based action level was
developed  for nickel in groundwater at the Site.

-------
Assuming that the groundwater would be used for
domestic purposes, it was determined that
groundwater concentrations of nickel below 730
ppb would result in an acceptable HI for the Site
(i.e., an HI less than or equal to  1.0); conversely.
levels above 730 ppb could present an
unacceptable noncarcinogenic risk for the Site.
Consistent with EPA guidance for conducting
Superfund risk assessments, this calculated value
assumes that there are no other significant sources
of nickel exposure  from other  environmental media
(e.g.. air, soil, diet). As a point of reference, the
95% Upper Confidence Level (UCL) of the
arithmetic mean, calculated utilizing nickel data
from all of the on-site wells sampled during Phase I
was 480 ppb, well below the 730 ppb action level.
As noted previously, EPA has  issued a Health
Advisory for nickel  of 100 ppb which Is the same
level as the former MCL  The Health Advisory
incorporates additional conservative safety factors
to account for potential nickel exposure from media
other than drinking water; this very conservative
level of safety assumes that drinking water only
contributes 20%  of expected nickel exposure.

Ecological Assessment

The ecological risk assessment considered
potential exposure routes of Site contamination to
terrestrial wildlife.  Much of the Site Is paved or
covered by structures and there is little, if any,
potential for wildlife to be exposed to contaminated
subsurface soils on-site.   The  only potential route
of exposure to wildlife in the Site vicinity is If
contaminants were transported through
groundwater and discharged via groundwater into
surface waters, particularly the state wetland
located one-half mile south of the  Site.  Phase II
sampling shows that the wetland has not been
impacted by Site contaminants.  Therefore, it was
determined that  no significant effect on aquatic
organisms in the wetland in the  vicinity of the Site
could be attributed to groundwater discharge from
the Site.

Actual or threatened releases of hazardous
substances from this Site, if not addressed by the
preferred alternative or one of the other active
measures considered, may present a current or
potential threat to the environment through
leaching of contaminants in the Site's sediments
and soils into the groundwater.

Since significant contamination, specifically nickel,
was detected In the soils at the  Site, there is a high
potential for cross-media impacts as nickel can
migrate into the groundwater  via fluctuations of the
water table and precipitation.  This Is supported by
the detection of high levels nickel in the
groundwater. The maximum concentration of
nickel in one on-site well was detected at 959 ppb.
Furthermore, Site-related nickel contamination has
impacted the nearby Church Street supply wells.

Due  to these circumstances, remedial action
alternatives were developed for the Site sediments
and  soils.

REMEDIAL ACTION OBJECTIVES

Remedial Action objectives are specific goals to
protect human health and the environment.  These
objectives are  based on available information and
standards such as applicable or relevant and
appropriate requirements (ARARs) and risk-based
levels established in the risk assessment.

The  following remedial action objective was
established for Site sediments and soils:

   (1)   prevent leaching of contaminants.
        particularly nickel, in the subsurface soils
        and sediments to the groundwater.

SUMMARY OF REMEDIAL ALTERNATIVES

CERCLA requires that each selected site remedy
be protective of human health and the
environment, be cost-effective, comply with other
statutory laws, and utilize permanent solutions and
alternative technologies and resource  recovery
alternatives to the maximum extent practicable.  In
addition, the statute includes a preference for the
use  of treatment as a principal element for the
reduction of toxicity, mobility, or volume of  the
hazardous substances.

The remedial alternatives discussed below are for
Site sediments and soils. While the FS also
includes preliminary remedial alternatives for
groundwater, as stated previously,  EPA has
decided to defer a decision  oh groundwater
remediation. Therefore, no groundwater remedial
alternatives are presented in this Proposed  Plan.

The remedial alternatives considered in the FS
were screened based on implementability,
effectiveness,  and cost. The screening resulted in
remedial alternatives upon which a detailed
analysis was performed.  The alternatives
considered in detail are discussed  below.  Time to
implement* is  defined as only the period of time
needed to implement the remedy, and does not
Include the time required to design the remedy.

-------
procure contracts for design and construction or to
negotiate with responsible parties for
implementation of the remedy, conduct operation
and maintenance, or conduct long-term monitoring.

Alternative SR-I: No Action

Capital Cost:      $  -0-
O&M/yrCost:    $  -0-
Present Worth:    $  -0-
Time to Implement: N/A

The Superfund program requires that the No Action
alternative be considered  as a baseline for
comparison with other soil alternatives. Under this
alternative, the contaminated soil would be left in
place without treatment. Since this alternative
would involve  no contaminant removal. CERCLA
requires that the Site be reviewed every five years.
If justified by the review, remedial actions may be
implemented to remove or treat  the wastes.

Alternative SR-II: Limited Action

Capital Cost:      $ 250,322
0 & M/yr Cost:    $   2.020
Present Worth.    $ 277,062
Time to Implement: 2 months

This alternative includes measures which would
reduce the leaching of contaminants, particularly
nickel, to the groundwater.  The specific measures
include: removal of contaminated soils/sediments
in the 6 drywells in AEC 2 and drywell DW-2 in
AEC 14, and removal of surface soils within AEC 8,
a reported discharge area which has shown TPHCs
and metals related to Site operations.  In addition,
this alternative would Include decommissioning and
cleanup of the on-slte  production well.  This action
would be taken as a conservative measure to
eliminate potential  exposure to contaminated
groundwater at the Site.

The top three feet of soils/sediments would be
removed via a vacuum truck from the 6 dry wells in
AEC 2 and  drywell DW-2 In AEC 14. The drywell
structures would be left in-piace and backfilled with
clean soil.   New drywells would  be installed in an
adjacent area  for storm water runoff. The amount
of material to be removed Is estimated to be
approximately 56 cubic yards; this material
represents the most significant source of nickel
contamination on the Site.  In addition, surface
soils would be removed from the top 2 feet of
locations within AEC 8. The amount of material
here to be removed is estimated to be
approximately 215 cubic yards.  Also, the soils/
sediments in the on-site production well vault
would be removed via a vacuum truck.  The well
borehole would be sealed and capped, and the
well casing and concrete vault would be removed.
All materials removed during these measures would
be transported off-site for treatment (as necessary)
and disposal in accordance with federal and state
requirements.  It would also be recommended that
the use of the property be restricted to its current
commercial/industrial use.  Although this
alternative would result in no contamination
remaining  on-site above health-based levels for the
current property use, since the remedy does not
allow for unlimited use and unrestricted exposure,
five-year reviews would be  required.

EVALUATION  OF ALTERNATIVES

During the detailed evaluation  of remedial
alternatives, each alternative is assessed against
nine evaluation criteria, namely overall protection of
human health and the environment; compliance
with applicable or relevant and appropriate
requirements (ARARs): short-term effectiveness;
long-term  effectiveness and permanence; reduction
of toxicity, mobility, or volume; implementabllity;
cost; community and state acceptance.

* Overall  protection of human health and the
  environment addresses whether or not a remedy
  provides adequate protection  and  describes how
  risks are eliminated, reduced,  or controlled
  through treatment, engineering controls, or
  institutional  controls.

* Compliance with ARARs addresses whether or
  not a remedy will  meet all of the applicable or
   relevant and appropriate requirements and/or
  provide grounds for invoking a waiver.

»  Long-term effectiveness and permanence refers
  to the ability of a  remedy to maintain reliable
   protection of human health  and the environment
  over time, once cleanup goals have been met. It
  also addresses the magnitude and effectiveness
   of the measures that may be required to
   manage the risk posed by treatment residuals
   and/or untreated  wastes.

*  Reduction of toxlcitv. mobility, or volume
   through treatment is the anticipated performance
   of the treatment technologies a remedy may
   employ.

-------
*  Short-term effectiveness addresses the period of
   time needed to achieve protection from any
   adverse impacts on human health and the
   environment that may be posed during the
   construction and implementation period until
   cleanup goals are achieved.

»  Implementabilitv Is the technical and
   administrative feasibility of a remedy, including
   the availability of materials and services needed
   to implement a particular option.

*  Cost includes both estimated capital and
   operation and maintenance costs, and  net
   present worth costs.

*  State acceptance indicates whether, based on
   its review of the RI/FS reports and Proposed
   Plan, the State concurs with, opposes,  or has
   no comment on the preferred alternative.

»  Community acceptance will be assessed In the
   ROD and refers to the public's  general response
   to the alternatives described In the RI/FS report
   and the Proposed Plan.

Comparison of Alternatives

The following discussion compares the relative
performance of each alternative using the  specific
evaluation criteria listed previously.

*  Overall Protection of Human Health and the
   Environment

   Alternative SR-ll would meet the remedial
   objective of preventing cross-media impacts to
   the groundwater from the source of
   contamination.  Alternative SR-I would  not
   prevent the continued migration of  nickel into
   the underlying groundwater and,  therefore,
   would not be as protective as Alternative SR-ll.

«  Compliance with ARARs

   Federal and state regulations dealing with the
   handling and transportation of any wastes to an
   off-site disposal facility for SR-ll would be
   followed. Wastes would be treated using
   specific technologies or specific treatment
   levels,  as appropriate, to comply with land
   disposal restrictions.  Alternative  SR-I would not
   be subject to any ARARs, although, potential
   excursions of groundwater/drinklng water
   standards could occur under SR-I,  due to cross-
   media  impacts resulting from contaminants
   remaining in the soil.
» Long-Term Effectiveness and Permanence

  Alternative SR-ll would remove the principal
  source of nickel to prevent leaching of
  contamination to the Upper Glacial aquifer.
  Alternative SR-I would not reduce the potential
  long-term leaching to groundwater.
  Reduction In Toxlcitv. Mobility, or Volume
  Through Treatment

  Through removal and off-site disposal, SR-ll
  would reduce the toxiclty, mobility, and volume
  of contaminants, especially nickel,
  soils/sediments located at the Site.  Alternative
  SR-I would provide no reduction in contaminant
  mobility, toxlcity, or volume.

  Short-term Effectiveness

  The potential for a temporary Increase of risk to
  the community and workers due to dust
  generation during the soil removal activities of
  SR-ll would be mitigated by the use of a vacuum
  truck for soil collection.  Workers would also be
  protected through the use of respirators (if
  needed).  The implementation of Alternative SR-I
  would result in no additional risk to the
  community or workers during implementation.

  Implementabilitv

  Components of Alternative  SR-ll would  utilize
  relatively common construction equipment and
  materials.  The services and technologies
  needed to implement this work are readily
  available.  Use restrictions via zoning are in
  place at the Site and are not expected to
  change, however EPA will recommend  to the
  current property owner to amend the deed
   restricting residential use.   Because no
  construction activities are associated with
  Alternative SR-I, this alternative would be easier
  to implement than Alternative SR-ll.

   Cost

  The no action alternative has no associated
   costs.  Alternative SR-ll is estimated to cost
   $277,062.

   Community Acceptance

   Community acceptance of the preferred soil
   alternative will be assessed in the ROD following
   a review of the public comments received on the
   RI/FS report and the Proposed Plan.

-------
» State Acceptance

  DEC concurs with the preferred alternative.

PREFERRED REMEDY

Based upon an evaluation of the various
alternatives, EPA and DEC recommend Alternative
SR-II (Limited Action) as the preferred alternative
for contaminated sediments and soils. Alternative
SR-ll is designed to be protective by removing
sediments/soils containing the principal source of
nickel contamination.

The preferred alternative will provide the best
balance of trade-offs among alternatives with
respect to the evaluating criteria. Based on the
information available at this time, EPA and DEC
believe that the preferred alternative will be
protective of human health and the environment,
comply with ARARs, be cost-effective, and utilize
permanent solutions and alternative treatment
technologies or resource recovery technologies to
the maximum extent practicable.
In addition, EPA will conduct a monitoring program
of the groundwater. Sampling results from both
on-site wells and those at the Church Street
wellfield will be evaluated to better define the
vertical extent of the nickel plume, to identify any
trends in the concentration of nickel at the Site and
at the wellfield. and to determine whether the
proposed removal  of nickel contaminated
sediments and soils has  an impact on nickel
concentrations in the groundwater. Additional
modelling will be conducted to ensure that the
contaminant plume emanating from the Site does
not result in the contravention of appropriate health
based levels of nickel in  water distributed for
consumption at the Church Street wellfield.  It
should be noted that the NYSDOH is currently
using the federal Health  Advisory level of 100 ppb
for nickel in its supervision of public drinking water
supplies in  New York state. Subsequent to the
completion of this monitoring effort,  EPA and DEC
will propose a preferred  remedial alternative for
addressing the groundwater contamination In a
second Proposed Plan.
                                                   10

-------
  APPENDIX B
PUBLIC NOTICES

-------
                    APPENDIX C
SEPTEMBER 11, 1995 PUBLIC MEETING ATTENDANCE SHEETS

-------
    UNITED  STATES ENVIRONMENTAL PROTECTION AGENCY
                      REGION II
                    PUBLIC MEETING
                         FOR
           Goldisc Recordings Superfund Site
                   Islip, New York

              Monday,  September 11, 1995
                      ATTENDEES
                (Please Print Clearly)


STREET          CITY        ZIP       PHONE      REPRESENTING

-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                  REGION II
                PUBLIC MEETING
                     FOR
       Goldisc Recordings Super fund site
               Islip, New York

          Monday, September 11,  1995
                  ATTENDEES
            (Please Print Clearly)
NAME
STREET
CITY
ZIP
PHONE
                                              REPRESENTING

-------
                    APPENDIX D
LETTERS SUBMITTED DURING THE PUBLIC COMMENT PERIOD

-------
                              PERICONI & ROTHBERG. P.C.

                                      ATTORNEYS AT LAW
DEBRA L. K01HBERO-                                                                    SUITE. 6L3
                                                                          NEW YORK. MEW YORK ,0169
•AlSO MEMBER OF KJ CAR                                                              FAX (Sl2) 49O-SOO6
-AlSO MEMBER OP MASS- BAR


                                                  September 26, 1995

     BY TELECOPIER & FEDERAL EXPRESS

     Ms. Janet Cappelli
     New York/Caribbean Superfund Branch I
     Emergency and Remedial Response Division
     U.S. Environmental Protection Agency
     Region n
     290 Broadway - 17th floor
     New York, NY  10007-1866

                  Re:    Comments on TJSEPA Superfund Proposed Plan
                         for Fonder Q<

     Dear Ms. Cappelli:

                  These comments to the Superfund Proposed Plan for the Goldisc Site (the
     "Proposed Plan"), issued by the United States Environmental Protection Agency ("USEPA")
     are submitted on behalf of Red Ground Co., the current owner of the Goldisc Recordings
     Superfund Site ("Goldisc Site") and Red Ground Corporation, a former owner (collectively,
     "Red Ground").  Red Ground requests that these comments be docketed and made a part of the
     administrative record in this matter.

     1.     Introduction

                  The USEPA states that the Proposed Plan is being provided as a supplement to
     the remedial investigation and  feasibility study ("RI/FS") reports, to inform the public of the
     preferred remedy for the Site and solicit public comments.  Proposed Plan, p. 1.  However,
     while the RI/FS addresses both Site sediments and soils, and Site groundwater, the Proposed
     Plan addresses only the contamination associated with sediments and soil. Moreover, data
     collection for Site groundwater, as  well as for sediments and soils, was completed under the
     RI, and remedial alternatives were  identified for both in the FS.  Nevertheless, the USEPA
     and the New York State  Department of Environmental Conservation ("NYSDEC") have
     decided to defer the decision regarding groundwater contamination for the indefinite future.
     Proposed Plan, p. 3.  As described below, Red Ground objects to this decision, and finds  it to
     be arbitrary and capricious, because:   1) there is no technical or scientific basis for deferring

-------
.fERJCON1 Cc
       ATTORKEYS XT LAW

    Ms. Janet Cappelli
    September 26, 1995
    Page 2

    remedy selection for groundwater; 2) the USEPA's actions are inconsistent with its own
    regulations and procedures and with the RJ/FS; and 3) deferring the remedy creates
    uncertainty and delay for affected parties and the public.

                 Further, the Proposed Plan contains an inaccurate reference to Red Ground's
    participation in this matter.  Red Ground wishes to correct the record with regard to its own
    support, cooperation and participation in the Rl/FS.

    2.     The USEPA Lacks Anv Technical or Scientific Basis to Peter Its Selection of a
          Remedy for Groundwater

                 Red Ground has reviewed the comments prepared by ERM-Northeast ("ERM"),
    dated September 26,1995 and submitted in this matter on behalf of the ElectroSound Group,
    Inc. ("ESG"), former operator of the Goldisc Site, and agrees with ERM's evaluation of the
    Proposed Plan. Without relinquishing any rights Red Ground may have with regard to claims
    or causes of action against ESG and the First Holbrook Company ("First Holbrook"), Red
    Ground concurs with the following points made by ERM in response to the USEPA's
    explanation of its flawed decision to postpone the selection of a groundwater remedy for the
    Site.

          a.      The USEPA has stated that additional monitoring is needed to explain trends in
    nickel concentrations in She groundwater. However, the Site groundwater has been fully
    characterized by groundwater sampling and analysis performed over a 13-year period, from
    1981 through September 1994.  As part of that process, changes in nickel concentrations have
    been sufficiently characterized through sampling and modeling of groundwater flow and
    chemical fate and transport.

          b.     The USEPA has also stated that additional monitoring is needed to define the
    vertical extent of the groundwater  contamination.  Yet during the review by the USEPA and
    the NYSDEC of the work plans for the Phase I and Phase H remedial investigations, neither
    the USEPA nor the NYSDEC raised this concern. Moreover, if the USEPA or the NYSDEC
    now  conclude thai this additional monitoring is necessary, this concern is fully addressed
    within the context of one of the remedial alternatives described and recommended in the FS,
    the "No Action with Monitoring" alternative.

          c.     The USEPA refers repeatedly to an interim draft Health Advisory issued on
    July  10. 1995, which establishes a Health Advisory for nickel of 100 micrograms per liter
    ("ug/L"), and on which the New York State Department of Health ("NYSDOH") evidently
    relies in supervising public drinking water supplies.  These references imply that the 100 ug/L
    level is applicable or relevant and appropriate to the USEPA's evaluation of groundwater
    remedies at the Site. However, the interim draft Health Advisory is an informal standard that
    is not legally enforceable. Thus, the Health Advisory level  for nickel should not be a factor in

-------
PEHICONI  & ROTHBEHG. P.C
       ATTORNEYS AT LAW

    Ms. Janet Cappelli
    September 26,  1995
    Page 3

    the assessment  of a groundwater remedy.  The federal Maximum Contaminant Level ("MCL")
    for nickel, also 100 ug/L, was remanded to the Agency in February, 1995, and therefore is
    also not relevant to the remedy selection process.  The appropriate target clean-up level is the
    site-specific health-based level developed during the RI/FS in accordance with USEPA
    regulations and guidance for performing risk assessments.

                 The preceding points demonstrate that there is no rational basis for the USEPA
    to defer remedy selection because of the need for additional monitoring. Moreover, the
    USEPA may not consider or rely upon the informal draft Health Advisory, and its references
    to the Health Advisory 100 ug/L level are therefore inappropriate. This is particularly true
    because  the 100 ug/L level is precisely that of the remanded, and therefore null and void,
    MCL.

    3.     The USEPA's Actions in Deferring the Selection of a Remedy Are Inconsistent With
          Jts Own Regulations and Procedures  and With the RI/FS Results

                 As described above, there is no technical basis for the USEPA's proposed
    course of action with respect to groundwater.  Further, the Agency's actions in deferring the
    selection of a remedy are also inconsistent with its own regulations and procedures, and with
    the results reached in the RI/FS. This decision by the USEPA is arbitrary and capricious, and
    undermines the RI/FS process and the USEPA's own authority.

                 In support of deferring its decision on a remedy for groundwater, the USEPA
    points to the fact that there  is currently no MCL for nickel, which is a contaminant of concern
    at the Site and has been detected in the groundwater at the Church Street water supply well
    downgradient from the Site. Yet MCLs have not been established for numerous chemicals
    commonly found at Superfund Sites.  In such cases, the USEPA relies on the risk assessment
    procedures outlined in the National Contingency Plan ("NCP") and in USEPA guidance
    documents to establish clean up levels.  ERM properly followed these risk assessment
    procedures in selecting the nickel clean up standards employed in the FS to arrive at the
    groundwater remedial alternatives.  To now reject the results of ERM's extensive site specific
    risk assessment, which the USEPA approved, because of the absence of a generic standard is
    without  support or authority.

                 The USEPA's unusual action in deferring proposal of a groundwater remedy is
    evidently based on objections raised by the NYSDOH relating to its reliance on the draft
    interim Health Advisory for nickel of 100 ug/L in supervising drinking water supplies.  Since
    the USEPA cannot legally apply this informal 100 ug/L standard, it is inappropriate to delay
    the remedy selection on this basis, Le.. simply because the NYSDOH is not satisfied with the
    site-specific health-based levels developed during the RI/FS. According to USEPA Guidance
    for preparing the Proposed Plan, any dispute arising during  the remedial process between the
    lead  and support agencies should be resolved in a timely manner, and,  "(rjegardless of the

-------
PEEICONI & ROTHBERG. P.C
       ATTORNEYS AT LAW

   Ms. Janet Cappelli
   September 26, 1995
   Page 4

   process utilized, the result should be an equitable resolution of the outstanding issues."
   "Guidance on Preparing Superfund Decision Documents," OSWER Directive #9355.3-02 (July
   1989) at 3-7.  Where final resolution cannot be reached, however, "the Region should use its
   discretion as to whether to proceed with publication of the Proposed Plan." LL at 3-8.
   Where,  as in this case, the State's concerns are unsupported by science or law, the USEPA
   should exercise its discretion and proceed with publication of a proposed remedy for
   ground water in addition to Site sediments and soils.

                Instead, the USEPA's purported resolution to the absence of an MCL for nickel
   is its proposal to monitor groundwater at the Site and perform additional modeling, and, at
   some unspecified future point, propose a remedial alternative for groundwater. Ironically, this
   course of action is essentially the No Action With Monitoring alternative proposed and
   recommended by ERM, but without the critical components of an effective monitoring plan as
   set forth in ERM's proposal. If the USEPA supports the alternative of no current active
   remediation but ongoing monitoring, it should have proposed the No Action With Monitoring
   alternative, so the remedy could proceed in proper form.  The USEPA has the authority to
   address the possible need for future response actions relating to Site groundwater pursuant to
   the terms of a reopener provision.

                The purpose of the Proposed Plan is to supplement the RI/FS and provide the
   public with an opportunity to comment on the preferred alternative for a remedial action as
   well as the other alternatives considered. 40 C.F.R. § 300.430(f)(2). The Proposed Plan
   should direct the public to the RI/FS report as the primary source of detailed information on
   the remedial alternatives analyzed, as well as other site-specific information.  OSWER
   Directive #9355.3-02 at 2-1. In this instance, instead of supplementing the Goldisc RI/FS, the
   Proposed Plan contradicts and conflicts with the RI/FS.  While the Plan describes in detail the
   groundwater investigation and the baseline risk assessment for human health risks related to
   groundwater contamination, it then completely omits any discussion of the groundwater
   alternatives.  This is likely to confuse members of the public, and, even worse, deprives the
   public of an opportunity to understand the options available to the USEPA and thus, to
   comment upon the wisdom of the deferral of groundwater remedy selection.  The USEPA's
   statement in the Proposed Plan that changes may be made in the selected remedy based on
   public comment is an empty offer with respect to groundwater remediation, as the public has
   not been fully informed regarding the remedial alternatives.

                As explained in the NCP at 40 C.F.R. § 300.430(a), the purpose of the remedy
   selection process is to implement remedies that eliminate, reduce or control risks to human
   health and the environment. Thus, "[r]emedial actions are to be implemented as soon as site
   da^a apd ^formation make it possible to do so."  LL (emphasis added). At the Goldisc Site,
   extensive data has in fact been gathered under the close direction of the USEPA during the
   performance of comprehensive Phase I and Phase II remedial investigations at the Site. The
   data and information are currently available,  and  it is incumbent upon the USEPA to propose

-------
Jr'EBICONI  & ROTHBEEG. P.C
       ATTORNEYS AT  I_*w

    Ms. Janet Cappelli
    September 26, 1995
    Page 5

    and select the appropriate remedy for groundwater, which is the No Action With Monitoring
    alternative.

    4.     EPA's Failure to Propose a Remedy for Groundwater Creates Uncertainty and Does
          Not Benefit Public Health or the Environment

                 The ongoing bankruptcy proceedings of ESG, former Site operator and
    signatory, along with First Holbrook, to an Administrative Order on Consent ("AOC")
    governing the performance of the RI/FS, presents further reason for the USEPA to proceed
    with selection of a remedy at the Site.  In failing to do so, the Agency is creating an
    unnecessary degree of uncertainly, prejudicing its own ability to recover funds necessary to
    perform the clean-up, as well as the rights of other parties to the bankruptcy proceeding,
    particularly Red Ground.

                 On or about May 9, 1994, ESG and two of its subsidiaries filed petitions under
    Chapter  11 of the United States Bankruptcy Code, 11 U.S.C. § 101 etse^, in the United
    States Bankruptcy Court for the Eastern District of New York.

                 In December, 1994, the United States Department of Justice filed a proof of
    claim with respect to the bankruptcy proceedings of ESG ("Proof of Claim").  The Proof of
    Claim stated that the debtor, ESG,  is liable to reimburse the United States for all past and
    future response costs for actions taken and to be taken at the Site by the USEPA. Proof of
    Claim, t15, 9.  The Proof of Claim further stated that the USEPA "anticipates that
    remediation of the contaminated soil and groundwater may be required," and that the agency
    "presently estimates that the future costs for cleanup of the soil and groundwater at the site
    may range between $4 million and $6 million." Proof of Claim,  19.

                 While the USEPA has delayed to date quantifying  its claim, the Government
    should now make every effort to assert its rights in ESG's bankruptcy proceedings so as to
    secure the maximum amount of funds possible from the bankrupt estate to fund the clean up of
    the She. It should not be necessary to point out that the refusal of the USEPA to select a
    remedy for groundwater, and thus be able to quantify its claim in the ESG bankruptcy may
    complicate the Government's ability to obtain those funds.  Red Ground recognizes that First
    Holbrook, which is not  in bankrutcy, is also a potentially responsible party for the Goldisc
    Site.  Nevertheless, without  the ESG monies,  the public health and the environment may
    suffer. In this time of financial cutbacks for the USEPA, it is fiscally irresponsible for the
    Agency to delay its decision. This is particularly true since, as noted by ERM, the USEPA
    has identified the Goldisc Site as one at which because of the recent reduction in the USEPA's
    budget, no funds will be available for clean up oversight, which makes it highly unlikely that
    any monies will be available for the proposed additional monitoring and modeling.

                 Moreover, the deferral of Site groundwater remedy selection has a direct

-------
PEBICONI & ROTHBEEG. P.C
       ATTORNEYS AT LAW

    Ms. Janet Cappelli
    September 26, 1995
    Page 6

    detrimental impact on Red Ground Company, as the owner of the Site.  The Site was listed by
    the USEPA on the National Priorities List ("NPL") in June 1986. Almost ten years later, Red
    Ground Co. continues to face delays in Site remediation. The encumbrance placed upon the
    property by the NPL listing and the uncertainty surrounding the clean up have given rise to
    difficulties in financing or selling the property, and evidently  will continue to do so for the
    indefinite 'future.  As discussed below, Red Ground Co. has filed for bankruptcy, due in large
    part to the condition of the Site and the slow progress of the remediation. Further delays
    exacerbate the inequitable impact upon Red Ground Co. of. this exceptionally drawn-out
    process.

    5.     Red Ground Has Appropriately Cooperated with the USEPA in the RI/FS Process

                In the Site Background section of me Proposed Plan, the USEPA asserts that it
    notified First Holbrook, ESG and Red Ground of their potential liability at the Site and
    requested that they finance the RI/FS. It continues: "Red Ground refused to enter into
    negotiations with EPA to conduct additional RI/FS activities.  Subsequently, in 1991, EPA
    entered into an AOC  with First Holbrook and ElectroSound." Proposed Plan, p. 3. This
    characterization of the events that transpired in 1991 is totally incorrect.

                In fact, in early May 1991, the USEPA transmitted to Red Ground a draft
    AOC, with an attached draft Statement of Work in connection with  the Goldisc Site.  Shortly
    thereafter, counsel for ESG advocated to the USEPA that Red Ground  Corporation be included
    as a party to the AOC.  In response, by letter dated May 28, 1991,  Red Ground explained to
    the USEPA that pursuant to the Contract of Sale between Red Ground and First Holbrook for
    the Goldisc property, First Holbrook and ESG were legally obligated to undertake all
    necessary measures to remediate the Goldisc property, and Red Ground would rely on that
    Contract.  The May 28, 1991 letter further noted that ESG and First Holbrook had already
    submitted to the Agency a good faith offer to conduct the supplemental RI/FS activities.
    Finally, while not stated in the letter. Red Ground would have been in breach of this Contract
    of Sale if it signed the AOC, and  thus would have risked losing the benefits of the Contract.

                In response to this  letter, the USEPA continued negotiations with ESG and First
    Holbrook, eventually reaching final agreement in an AOC that became effective on July 3,
    1991.  Red Ground, as appropriate, is not a party to that AOC.

                However, as owner of the property and pursuant to the contract of sale with
    First Holbrook, Red Ground has fully cooperated with the USEPA  and has participated
    through its counsel in the  remedial investigation process.  As  the USEPA is  aware, Red
    Ground has taken every step possible to persuade ESG and First Holbrook to fulfill their
    commitments to Red  Ground, including  the commencement of a civil action against ESG and
    First Holbrook in the Supreme Court, Suffolk County.  Red Ground has also made every
    effort to cooperate with the Agency to implement the remedial program, and in fact has

-------
PEHICONI & ROTHBEHG. P.C.
       ATTORNEYS AT LAW
    Ms. Janet Cappelli
    September 26, 1995
    Page?

    assisted the USEPA in obtaining the cooperation and performance of ESG and First Holbrook.
    Given the continued responsibility of First Holbrook and ESG, and the fact that ESG caused
    the contamination at the Site, Red Ground's actions have been appropriate and Red Ground
    has acted in good faith.

    6.     Red Ground Co. ffanjcyuptcy and Reservation of Rights

                 On March 11, 1993, Red Ground Co., the current owner of the Site, filed a
    voluntary petition pursuant to Chapter 11  of the United Slates Bankruptcy Code, 11 U.S.C.
    § 101 £1 seq.  The NPL listing of the Site and the slow progress  of the remediation has made it
    difficult for Red Gound to obtain financing or sell the property.  Now, after an extended RJ/FS
    process, the results of which were approved by the USEPA, the  Agency proposes to extend
    the uncertain status of the Site indefinitely. This inequitable course of action promises to
    continue the harm to the Site owner and keep the property out of productive use for further,
    unknown years of delay.

                 Red Ground Co. hereby reserves all its  rights in this matter.

    7.     Conclusion

                 Red Ground objects to the decision of the USEPA, made in consultation with
    the NYSDEC, to defer selection of a remedy for groundwarer contamination at the Goldisc
    Site.  This decision is arbitrary  and capricious because it is without any technical or scientific
    basis,  is inconsistent with the USEPA's regulations and procedures, and creates uncertainty
    and delay for  affected parties and the public. The results of the  RI/FS show that the No
    Action With Monitoring alternative is the appropriate remedy for Site groundwater. The
    USEPA should revise the Proposed Plan to propose this alternative, so that the public may
    comment on this  alternative and the remedy can proceed in a timely manner.

                                                  Sincerely,

                                                  Periconi & Rothberg, P.C.
                                                  Attorneys for Red Ground Corporation
                                                   and Red Ground Company
                                                      Debra L. Bthberg,

-------
                 REISMAN, PEIREZ, REISMAN & CALICA, L.L.P.
                             COUNSELORS AT LAW
                             I3OI FRANKLIN AVENUE
SEYMOUR J. REISMAN                 GARDEN ClTY, NI.Y. II53O
DAVID H.
JEROME REISMAN                        (SI6) 746-7799

ROBERT M CALICA                       <2 I E) 897-1 37 7

MICHAEL J. ANGELO                         -                           COUNSEL

   _                           FACSIMILE                        MARK S. CHARWAT

JOSEPH OAPOBIANCO                      (5 I 6) 7 4S-4946

ANN P. ZYQERT

SUSAN T. KlUEWER

COWARD M. ROSS°

ANTHONY C. ACAMPORA

LYDIA A. MILONE"


" MEMBER NT AND ft BAH
0 MEMBCR NY AND CT OAR
                                  September 25, 1995

    VIA FEDERAL EXPRESS
    Ms.  Janet Cappelli
    Project Manager
    U.S.  Environmental Protection Agency
    290  Broadway, 20th Floor
    New  York, New York 10007

              Re:  EPA Superfund Proposed Plan - Goldisc Recordings
                   Site,  August 1995  ("Plan")

    To The EPA,  Region II:

    This firm has acted as special legal counsel to ElectroSound  and
    First Holbrook,  two of the potentially responsible parties
    (PRPs),  signatories to the Administrative Order on Consent
    ("AOC").   In fact, the undersigned negotiated the AOC with  the
    EPA  in 1991, and has provided special legal advice to the PRPs
    with regard to all environmental legal issues from time  to  time.

    The  Plan's proposed remedial action with regard to the preferred
    alternative for contaminated sediments and soils is acceptable,
    but  the decision of the EPA to conduct a monitoring program of
    the  groundwater in order to better define the vertical extent of
    the  nickel plume, to identify any trends in the concentration of
    nickel and,  thus, to defer decisions regarding groundwater
    remediation is legally indefensible and constitutes'an arbitrary
    and  capricious action by the EPA.

                       SUMMARY OF LEGAL CONCLUSION

    The  arbitrary and capricious characteristics of the Plan are:

                   1.  The lack of any reasonable timetable  or
    schedule in which to gather information;

-------
REISMAN, PEIREZ, REISMAN & CALICA, L.L.P.

    Ms.  Janet Cappelli
    September 25, 1995
    Page 2


                    2.  A  failure to recommend any alternate remedy
    which may be implemented within a specified  time frame;

                    3.  A  failure to identify any reasonable proposal
    in  the  light of  currently existing technology;

                    4.  A  failure to identify any particular threat  or
    harm to the public health;

                    5.  The  EPA's decision to effectively ignore  the
    recent  judicial  decision rejecting the Federal standard for
    nickel  levels in groundwater ("MCL"), thus circumventing the U.S.
    Circuit Court by, in  effect, adopting and relying upon a Health
    Advisory which is not legally binding, which reliance directly
    violates the NCP (the governing Federal body of regulations).

                                  DISCUSSION

    First,  we note the written comments just submitted by ERM
    Northeast  ("ERM") to  the Plan,  on behalf of  ElectroSound.  ERM
    correctly points out  that the nickel, detected in groundwater at
    the  Church Street well,  is even below the current level of the
    Health  Advisory,  and  that the Site groundwater has been fully and
    properly characterized.

    The  Health Advisory is  neither applicable nor relevant and
    appropriate, is  "not  legally enforceable" by its own terms,  and,
    clearly is inconsistent with the NCP,  (see 40 CFR 300.5).  As ERM
    particularizes,  health  advisories are no more than "informal
    guidance", and cannot be construed to be legally enforceable
    Federal standards or  regulations.

    It  is arbitrary  and capricious for the EPA to "bootstrap" the
    failed  (and judicially  rejected) MCL by deferring a decision on
    groundwater at this Site, after 15 years of  EPA/DEC supervised
    Site investigation1,  simply because the EPA  and DEC are now
          The arbitrary and endless nature of governmental activity can be seen in
          the fact that the Site has been subjected to nearly  15 years, i.e.,  from
          1961 to date, of testing, sampling and reporting. Comprehensive
          remedial investigations were performed according to  a number of plans
          submitted to and approved by the EPA and the NYSDEC.  These agencies
          have had,  as noted by ERM in its comments,  " ... more than adequate
          opportunity to request and receive additional groundwater data if they
          decided it was necessary to properly characterize groundwater conditions
          at the Site."

          Neither agency made such a request because such a request was totally
          unnecessary.  The now-proposed further required monitoring for the
          purposes of determining whether additional remedial  activities are
          needed for groundwater on the Site is, after IS years, "cruel and
          unusual",  which the courts will clearly see as arbitrary and capricious.

-------
REISMAN, PEIREZ, REISMAN & CALICA, L.L.P.

    Ms.  Janet Cappelli
    September 25,  1995
    Page 3


    going to proceed to develop a new MCL for nickel.  The
    bootstrapping is exacerbated by the fact that  it  leaves the PRP's
    "hanging" in mid-air without any time frame or scientific
    parameters to apply or use in determining whether,  or to what
    extent,  a groundwater remedy may be necessary  or  selected for the
    Site.

    In all evaluations of the appropriateness of an EPA promulgated
    remedial action,  whether by a proposed plan or in a Record of
    Decision ("ROD"),  the essential factor is whether or not the
    action to be taken arises out of a legitimate  concern,  which must
    be rational,  and where the public health may be endangered.  A
    ROD,  is not to be an academic exercise or a theoretical approach
    for  general scientific investigation.   This is precisely what the
    EPA  has done here by deferring a decision on groundwater remedy.
    It is dead wrong.   It is by legal standards and previous court
    decisions "arbitrary and capricious".

    US v.  Cannons En'q Corp.. 720 F.  Supp. 1027 (District of Mass.
    1989),  aff'd 899 F.2d 79 (1st Cir.  1990)  and US v.  Akzo Coatings
    of America. Inc..  949 F.2d 1409 (6th Cir. 1991) are two
    informative decisions which discuss when a remedial action plan
    is rational and whether the remedies fashioned are fair,
    reasonable and adequate, and, consistent with  CERCLA.  Among the
    criteria the courts have announced are:   i)  the nature and extent
    of the hazards at a site; ii) the degree to which the remedy will
    address the hazards at a site;  iii)  the degree to which the
    public interest is served.   In this case, the  hazard at issue is
    simply whether or not and to what degree there is nickel in the
    groundwater.   Nickel is neither a priority pollutant nor is there
    a  validly existing MCL.  The previous MCL was  recently rejected,
    scientifically and procedurally,  by the U.S. Federal Circuit
    Court.   The so-called "remand"  was hardly voluntary on the part
    of the EPA, see,  .1995 WL 118042 [B.C.  Cir.,  per curiam decision] .

    One  of the earliest cases examining the legality  of an open-ended
    remedy,  such as the proposed Plan,  was U.S.  v. Hooker Chemicals,
    540  F.  Supp.  1067 (WDNY 1982).   There the court did approve the
    open ended remedy proposal.  However,  that case dealt with very
    substantial toxic wastes with a grave potential danger to the
    public welfare because of the likelihood of enormous amounts of
    toxic chemicals migrating from a landfill into the Niagara River
    and  Lake Ontario.   Nothing like that is present here.  Indeed, in
    this case,  the possible presence of nickel,  and the migration
    factor,  limited to a single public well is refuted by the fact
    that the well is in service and water is being drawn for the
    public use.  Thus, the Hooker case is inapposite.

    The  open-ended Plan in this case utterly fails to establish a
    reasonable timetable or schedule for information  gathering, has
    no specified time frame whatsoever,  and in light  of currently

-------
REISMAN, PEIREZ, REISMAN & CALICA, L.L.P.

    Ms.  Janet Cappelli
    September 25,  1995
    Page 4


    existing technology,  the proposal is unreasonable.   The latter is
    so because the EPA wrongfully relies upon a Health Advisory only,
    which is no more than a recirculated version of the judicially
    rejected MCL for nickel.

    Simply put, there are no sound justifications for leaving open
    the remedy for groundwater treatment.   The EPA currently
    possesses adequate toxicological information and the requisite
    knowledge to prepare a final Plan with regard to groundwater.
    When viewed in conjunction with the absence of a currently valid
    Federal standard  (i.e., an MCL), and the recent judicial
    rejection of the former Federal standard, it is clear that the
    EPA proposal to defer decision on groundwater remediation until
    after additional monitoring and modeling is unjustified and based
    on insubstantial evidence.  In short,  the Plan, as proposed, is
    an exercise in academia which the PRPs will be subjected to,
    after nearly 15 years of government-supervised Site
    investigation.

    Since the EPA has, i) failed to define any parameters; ii) set no
    time frame for its proposed testing program; and iii) been
    provided with sufficient data to render a final decision now,  the
    Plan leaves the matter in limbo, and stalls a final
    implementation simply to allow the government to satisfy an urge
    to develop a new standard for nickel groundwater.  This
    contravenes sound stated judicial policy as set forth in U.S.  v.
    Cannons En'q.  Corp..  899 F.2d at 88, supra.

    The bottom line is that the Church Street well was returned to
    service, and water is being provided to the public with nickel
    levels well below even the Health Advisory of 100 mgl.  Thus,  the
    EPA has itself demonstrated that there is no adverse condition at
    the public well.  There is simply no health-based threat to the
    public, the Health Advisory is unenforceable, and the nickel at
    the Site is both contained and in decline.  With the removal of
    the soil, that fact will be further strengthened and is self-
    confirming.

                                CONCLUSION

    For all of the above reasons, there appears to be no basis to
    support the EPA's groundwater proposal, which we suspect is the
    result of unjustified pressure from the State DEC and Dept. of
    Health.  It is wrong, wrong scientifically, and wrong legally.
    We have recommended that unless the EPA reverses its present
    proposed decision to defer a remedy on groundwater treatment, and
    use this Site as the "guinea pig" to develop a new Federal MCL
    standard for nickel,  the PRPs seek relief in the Federal Court
    upon the basis that the ROD is arbitrary and capricious.

-------
REISMAN, PEIREZ, REISMAN & CALICA, L.L.P.

    Ms.  Janet Cappelli
    September 25, 1995
    Page 5


    We ask that your written response to this comment, submitted on
    behalf of the PRPs,  ElectroSound Group and First Holbrook, be
    addressed and mailed to the undersigned in our capacity as
    special environmental legal counsel, and that our comment be
    included in the Administrative Record to preserve the PRPs rights
    to a judicial review.

                                  Very truly yours,

                                  REISMAN, PEIREZ, REISMAN & CALICA, LLP
    DHP:lk36972
    CC - ElectroSound Group
         First Holbrook Company
                                         DAVl-D" tf .  PEIREZ

-------
                          ROD FACT SHEET
SITE
Name:
Location/State:
EPA Region:
HRS Score/date:
Site ID #:

ROD .	
Date Signed:
Remedy/ies:
Operating Unit:
Capital cost:
Construction
Completion:
0 & M/year:
Present worth:

LEAD	

Enforcement:
Primary contact:
Secondary contact
Main PRP(s):
PRP Contact:
Goldisc Recordings
Holbrook, Suffolk County, New York
2
33.39  (6/1/86)
NYD980768717
09/29/95
soil & sediment excavation and offsite
disposal (by containment, bioremediation,
etc.), restrict deed to non-residential
OU-1
$250,322 (in '95 $)

9/96
$2,020 (in '95 $)
$271,722 (assumes 20 yrs, 7%, PWF=10.594)
EPA oversight/PRP
Damian Duda  (212) 637-4269
Doug Garbarini (212) 637-4263
ElectroSound Group, Inc.
First Holbrook Co.
Red Ground Corp
Robert Barone/David Peirez  (516) 746-7799
WASTE
Type:
Medium:
Origin:
Est. quantity:
nickel, chromium, semi-VOCs
soils/sediments
plating-type wastes
270 cu yds soil/sediments

-------