United States
             Environmental Protection
             Agency
             Office of
             Emergency and
             Remedial Response
EPAJROD/R02-84/009
September 1984
SEPA
Superfund
Record of Decision:
             Pijak Farm Site, NJ

-------
TECHNICAL REPORT DATA
(Please read Instructions on the reverse before completing)
1. REPORT NO. 2.
EPA/ROD/R02 -84/009
4. TITLE AND SUBTITLE
SUPERFUND RECORD OF DECISION:
Pijak Farm Site, NJ
7. AUTHOR(S)
9. PERFORMING ORGANIZATION NAME AND ADDRESS
. SPONSORING AGENCY NAME AND ADDRESS
. S. Environmental Protection Agency
01 "M" Street, S. W.
ashington, D. C. 20460
3. RECIPIENT'S ACCESSION NO.
5. REPORT DATE
09/30/84
6. PERFORMING ORGANIZATION
8. PERFORMING ORGANIZATION

4
CODE ^H
REPORT NO.
10. PROGRAM ELEMENT NO.
11. CONTRACT/GRANT NO.
13. TYPE OF REPORT AND PERIOD COVERED
Final ROD Report
14. SPONSORING AGENCY CODE
800/00
SUPPLEMENTARY NOTES
  ABSTRACT
       The Pijak Farm is located approximately two miles northeast of the Town of New
   ypt in Plumsted Township, Ocean County, New Jersey.  The site  is approximately 87
   res and is relatively flat with portions that drop off into a  marshy, wooded  flood
   ain.  Between 1963 and 1970, drums and free-flowing liquids from a facility dis-
   sing of specialty and research chemicals were dumped into a natural ditch which
   aversed the site and were later covered with soil.  The deteriorated remains  of
   ams are visible along the edge of the flood plain.  Contaminants found at the sit*
   .Tlude:  halogenated hydrocarbons, PCBs., phenolic compounds and oil sludges.   The
   inciple contaminants found onsite are not priority pollutants.

       The cost-effective remedial alternative selected for this  site includes:
   moval and off-site disposal of all drums and lab packs to a RCRA facility; excavation
   d off-site disposal of visibly contaminated soil to a RCRA facility; pumping  and
  :moval of contaminated ground water, as necessary, during excavation; monitoring on-
   te wells, annually, for a five year period and sediment control during excavation
   d sampling efforts.  The capital cost for the selected alternative is estimated to
  , $1,962,750 and the five-year O&M ground water monitoring costs are estimated to be
  33,600.
rKev Words on Attached Sheet)
KEY WORDS AND DOCUMENT ANALYSIS
DESCRIPTORS
Record of Decision
,-jite Name:- Pijak Farm Site, NJ
Contaminated Media: GW, SW, Soil, Stream
Sediments
Key Contaminants: PCBs, Phenols, Oils,
Halogenated hydrocarbons , VOCS , pesticides,
metals
18. DISTRIBUTION STATEMENT
b.lDENTIFIERS/OPEN ENDED TERMS

19. SECURITY CLASS .(This Report/
Nonp
20. SECURITY CLASS (This page/
None
c. COSATI Field/Group

21. NO. OF PAGES
•7C ^
22. PRICE ^^H
EPA Form 2220-1 (R«v. 4-77)   PREVIOUS EDITION is OBSOLETE

-------
16.  ABSTRACT (Continued)




Key Words:  Direct Contact,  Excavation,  Ground Water  Contamination,  NDD,  ROD

-------
                         ROD  ISSUES  ABSTRACT
Site;  Pijak Farm, New Jersey

Region:  II

AA, OSWER
Briefing;  September 27, 1984


                          SITE DESCRIPTION

    The Pijak Farm is located approximately two miles northeast of
the Town of New Egypt in Plumsted Township, Ocean County, New
Jersey.  The site is approximately 87 acres and is relatively flat
with portions that drop off into a marshy, wooded flood plain.
Between 1963 and 1970, drums and free-flowing liquids from a
facility disposing of specialty and research chemicals were dumped
into a natural ditch which traversed the site and were later covered
with soil.  The deteriorated remains of drums are visible along the
edge of the flood plain.  Contaminants found at the site include:
halogenated hydrocarbons, PCBs, phenolic compounds and oil sludges.
The principle contaminants found onsite are not priority pollutants.

                        SELECTED ALTERNATIVE

    The cost-effective remedial alternative selected for this site
includes: removal and off-site disposal of all drums and lab packs
to a RCRA facility; excavation and off-site disposal of visibly
contaminated soil to a RCRA facility; pumping and removal of con-
taminated ground water, as necessary, during excavation; monitoring
on-site wells, annually, for a five year period and sediment control
during excavation and sampling efforts.  The capital cost for the
selected alternative is estimated to be $1/962,750 and the five-year
O&M ground water monitoring costs are estimated to be S53,600.

        ISSUES AND RESOLUTIONS                    KEY WORDS

1.  This ROD authorizes the Phase I remedy of     .  Direct Contact
    limited excavation to eliminate the threat    .  Excavation
    of direct contact from the site.  The extent  .  Ground Water
    of contamination and the potential for ground    Contamination
    water contamination will be determined dur-
    ing the Phase I remedial action.  A supple-
    mental ROD for site closure and additional
    remedial actions, if necessary, will be
    initiated upon the completion of Phase I.
                                -1-

-------
Pijak Farm, New Jersey
September 27, 1984
Continued
        ISSUES AND RESOLUTIONS                      KEY WORDS

    A decision was made to approve a ROD for this   .   NDD
    site instead of an NDD because there were no    .   ROD
    substantive areas for negotiation and the cost
    of the remedy is relatively low.
                                 -2-

-------
                       Record of Decision
                 Remedial Alternative Selection
 S ite
 Pijak Farm, Plumsted Township, New Jersey

 Documents Reviewed

      I am basing my decision primarily on the following documents
 which describes the analysis of cost-effectiveness of remedial
 alternatives for the Pijak Farm site.

      -  Remedial Investigation and Feasibility Study for the
         Pijak Farm site,  Elson T.  Killam Associates, Inc.,
         August 1984
      -  Staff Summaries and Recommendations
      -  Responsiveness Summary, September 1984

 Description of Selected Remedy

      -  Removal and off-site disposal  of all  drums
         and lab packs at  a RCRA 264 facility
      -  Excavation and off-site disposal of visibly contaminated
         soil at a RCRA 264 facility
         Pump and remove contaminated ground water,  as necessary,
         during excavation
         Monitor on site wells,  annually,  for  a five year
         period
         Sediment control  during excavation and sampling efforts

 Declarations

      Consistent with the  Comprehensive Environmental Response,
 Compensation and Liability Act of  1980 (CERCLA),  and the National
 Contingency Plan (40 CFR  Part  300),  I  have determined that  the
 excavation and offsite disposal of visibly contaminated soil and
 waste,  pumping and removal of  contaminated groundwater during
 excavation,  and monitoring onsite  wells is the cost-effective
 remedy and provides adequate protection of public health, welfare
 and  the environment.   The State has been consulted  and agrees
 with  the proposed  remedy.

      I  have  also determined that the action being taken is
 appropriate  when balanced against  the  availability  ot Trust Fund
jnonies  for use at  other sites.   In addition,  the  removal of
 contaminated waste,  soil  and groundwater  to a secure hazardous
 waste  facility is  more cost-effective  than other  remedial actions,
 and  is  necessary to protect public health,  welfare,  or the
 environment.   The  State and EPA will include  additional .sampling  to

-------
                               -2-
determine the potential contact of contamination with the ground
water.  A Supplemental Record of Decision will be prepared for
approval of the future Remedial Actions.
                                                       ?-•
                                                        •v.
Date                           Lee M. Thomas, Assistant Administrator
                               Office of Solid Waste and
                                 Emergency Response

-------
            Summary of Remedial Alternative Selection

                         Pijak Farm site
                      Plumsted. New Jersey

 Site Location and Description

      The Pijak Farm site is located approximately  2.0  miles
 northeast of the Town of New Egypt in Plumsted  Township,  Ocean
 County,  New Jersey.  The site is  approximately  1,000 feet south
 of New Egypt-Lakewood Road (County of Route 528) and approximately
 1.000 feet west of Fischer Road.   It occupies a portion of Lot
 22,  Block 15 in Plumsted Township.   Waste  disposal occurred  at
 several  locations along  the edge  of an open field  and  in  an
 adjacent low-lying wooded area which drains ultimately to
 Crosswicks Creek.  A vicinity map and site location map are
 presented in Figures 1 and 2.

      The area consists of gently  rolling farmlands which  range
 in elevation from 115 to 145 feet above mean sea level.   The
 fields are cut by forested and heavily overgrown stream valleys
 which form a dendritic pattern and  range in elevation  from 100
 to 140 feet above mean sea level.   The total area  investigated is
 approximately 87 acres of which approximately 40 acres are woods,
 stream valleys or swamp  lands.

      The drainage area for the stream system crossing  the site
 is approximately 0.88 square miles  and is  situated within the
 Delaware River Basin.  Downstream from the site the stream joins
 another  small stream which flows  west into Crosswicks  Creek  in
 New  Egypt.   Several homes are  located within one-quarter  mile ot
 the  site.

      The Pijak  Farm site  is  located  in the Atlantic Coastal Plain
 which covers  portions of  eastern  and  central New Jersey.   This
 unconsolidated  geological  formation overlies bedrock comprised
 of early Paleozoic  to Precambrian metamorphic gneiss and  schist.
 The  unconsolidated  beds generally strike northeast/southwest,
 although shallower  units  strike in  a  more  easterly direction.
 The  units  dip and thicken  toward  the  southeast  at  dip  angles
 varying  from  about  10 feet per mile at  the  top  to  approximately
 120  feet per  mile at  the  bottom of  the  unconsolidated  sequence.
 Many of  the units vary in  composition from where they  outcrop to
 downdip  locations.

_ '   The Pijak  Farm  site  is  in the outcrop  area of  the
 Kirkwood Formation,  one of the major  aquifers in the Coastal
 Plain sequence.   Two  lithologic members make up the  Kirkwood•,
 an upper unit consisting  of  light gray  to  yellow-brown, fine
 quartz sand and  a lower unit consisting of  dark brown,  fine to
 very  fine  sand  and  silt containing some glauconite.  Muscovite,
 ilmentite  and lignite are common minerals  to both members.  The

-------
 Kirkwood Formation,  which ranges in thickness from 40 to 100
 feet iYi the outcrop area, has an average dip of 22 feet per mile
 in the southeastern direction and strikes N 60°E.   Downdip, this
 formation thickens to over 500 feet at the coast.   The Kirkwood
 aquifers are the most heavily developed of the Coastal Plain
 aquifers in Ocean County.

      A gradual formational contact exists between  the finer sands
 of the Kirkwood Formation and the coarser sands of the underlying
 Manasquan Formation,  the target depth for termination of monitor
 wells in the remedial investigation.   Even though  both formations
 have geologic similarities,  noticeable differences,  such as the
 larger grain size, increased glauconite content and  the fossil-
 iferous and calcareous nature of the  sediments, distinquishes
 the Manasquan from the Kirkwood.  Additionally, the  Manasquan  is
 generally considered  an aquitard even though in localized areas
 the upper unit of the Manasquan may be more permeable than the
 Kirkwood.

      Beneath the Manasquan Formation  are the Vincentown Formation,
 Hornerstown Sand, Red Bank Sand, Navashink Formation and
 Mt. Laurel-Wenonah Formation.   The Vincentown and  Mount Laurel-
 Wenonah formations are major aquifers in the area.

 Site History

      Portions of the  Pijak Farm site  are currently in use as
 cultivated  farmland.   The site is relatively flat, however,
 portions drop off into a marshy, wooded floodplain.   It is alleged
 that between 1963 and 1970,  drums and free-flowing liquids were
 dumped into a natural ditch  which traversed the site and were
 later covered with soil.  The  deteriorated remains of drums are
 visible along the bank of the  floodplain.

      Presently,  there are no containment or diversion systems
 for the waste or for  contaminants emanating from the site.   The
 location of this site in the bank of  and possibly  within an
 active floodplain makes the  hazardous waste particularly suscep-
 table to erosion by  flood waters and  surface runoff.

      The New Jersey Department of Environmental Protection Agency
 (NJDEP)  has performed a limited site  investigation of the Pijak
 Farm site prior  to the initiation of  a comprehensive Remedial
 Investigation and Feasibility  Study (RI/FS).

 Contaminants found at the site include;  halogenated  hydrocarbons,
~~PCBs,  phenolic compounds, and  oil sludges.

      A stream sample  taken adjacent to the site showed a high
 COD.   Ground water samples from the site indicate  the presence
 of  a number of contaminants  including zinc,  2-chlorophenol,
 2,4 dichlorophenol, 4-nitrophenol,  di-n-butyl phthalate,
 fluorine, pyrene,  anthracene,  and Arochlor 1254.

-------
     To  date,  the  Pijak  Farm site has had no known documented
 effects  upon  the local human population.  However, ground
 water  is used  as the major source of potable water throughout
 the  area.   Leachate breakouts  from the ground surface  into the
 adjacent marshy floodplain have been reported.

     A Remedial Action Master  Plan (RAMP) was completed for
 the  Pijak  Farm site in 1982.  Subsequently the NJDEP filed a
 Cooperative Agreement Application with the USEPA to cover the
 costs  to complete  a detailed RI/FS for the site.  In September
 1982,  $292,500 of  Federal Funds were approved for the  Pijak
 Farm RI/FS .

     The State of  New Jersey proceeded to procure a consultant
 to undertake the work necessary to complete the RI/FS.  Elson
 T.  Killam Associates was selected as the State's consultant.
 Work on  the RI/FS  was initiated in November 1983.  A draft
RI/FS  report was completed in August 1984.

 Current Site Status

     The  investigation program undertaken as part of the remedial
 investigation  phase included the following activities:

 1.  An electromagnetic induction terrain conductivity  survey
    of the site
 2.  An emanation flux detection survey
 3.  Construction and sampling of eleven monitoring wells
 4.  Excavation of  seven test pits and bbtainment of four soil
    and  six waste  samples
 5.  Collection of  one sediment and three surface-water samples.

     The results of these remedial investigation activities
 indicate that:

     0  Wastes were disposed of at the site by surface dumping
        and burial.

     0  Most waste containers were opened intentionally or have
         rusted and their contents dispersed;

     0  Principal contamination on site found in waste
        containers, underlying soils, a small area containing
        buried waste and the ground water at monitoring well 2-S ;

     0  Most organic pollutants detected were not priority
        pollutants; and

     0 Review of available data on toxicity for these non-
        priority organic pollutants indicated that the greatest
        potential for adverse health and environmental effects
        were found  in soil rather than in water.

-------
     A more detailed discussion  of  remedial  investigative results
 is noted below;

 Ground Water Samping and Results

     All eleven  newly constructed monitoring wells were sampled
 as part of the investigative program.  There were no volatile
 organics, acid extractable  organics, pesticides or PCB's detected
 in any of the ground-water  samples.  Only two wells, MW-2S and
 MW-5D, yielded ground water that contained base extractable
 organics: the latter having just 13 ug/1 of  3,7,11-Trilmethyl-
 (Z,E)-2,6,10 dodecatrien-1-OL, which was identified through the
 library search.  The sample from MW-2S contained 14 base extract-
 able compounds ranging in concentrations from 220 ug/1 to 3600
 ug/1, and averaging about 1000 ug/1.  Included are four priority
 pollutants: ethylbenzene, 1,2-dichlorobenzene, di-n-butyl phthalate
 and bis (2-ethylhexyl)-phthalate in concentrations of 940 ug/1,
 220 ug/1, 310 ug/1 and 320  ug/1, respectively.

     The only inorganic compounds found were very low concentrations
 of mercury (approximately 0.0004 mg/1) and zinc (approximately
 0.11 mg/1).  These contaminants were detected in all ground water
 samples.

Surface Water Sampling and Results

     The flows of streams on the Pijak Farm site are primarily
maintained by the discharge of ground water at the stream channels.
As such, surface water throughout the site is the recipient of
water first entering the cycle as recharge.  Thus, the three
surface-water samples are important for defining the water quality
at the end-point of its underground migration including the
point where the surface water eventually leaves the study area.

     The results of the chemical analyses indicate that the surface
water at two of the three locations are virtually free of priority
pollutants, both organic and inorganic.  Sample SW-3, centrally
 located on the site, contained no priority pollutants and contained
only one organic compound 13 ug/1 of 1-(1 Methylpropoxy)-2 propaool.
The surface water sample at the downstream boundary of the study
area, SW-5, also contained  only one organic compound, 15 ug/1 of
toluene which was detected  through the base-extraction procedure.
The third sample SW-1 which is representative of surface water
entering the study area, contained the largest number and
concentrations of organic compounds.  Again, only base extractable
compounds were detected, and these all were identified through
the library search including the priority pollutant toluene.
Five compounds were identified and ranged in concentrations
from 18 ug/1 to 56 ug/1.  All .three samples contained mercury
and zinc at concentrations  well below drinking water standards.

-------
 Test Pit Soil Sampling _and__Resuits

      Aside from actual waste samples, the four samples obtained
 at Test Pits 2, 2A, 2B, and 3 contained the highest concentrations
 of contaminants found on the Pijak Farm site.  These samples are
 considered to be adjacent to the source as they were collected at
 depths not exceeding 3 feet below grade.  Contamination by
 individual organic compounds ranged from a low of 4 ug/kg to a
 high of 36,000 ug/kg and generally averaged about 6500 ug/kg.
 Similarly, individual inorganic compounds ranged from 0.02 ug/g
 to 280 ug/g with an average of about 9 ug/g.  The pesticides
 4,4' DDE and 4,4'  ODD were detected in Test Pit 2B in concen-
 trations of 7.2 ug/kg and 9.0 ug/kg, respectively.  No other
 pesticides were found in this or the other test pits.  Soil from
 Test Pit 2 was found to contain 2300 ug/kg of PCB-1254; the
 only detection of  a PCB compound in the investigation.

      Two important observations are made from the test pit results.
 First, Test Pit 2  is the only location which showed a variety of
 volatile organics, two of which are priority pollutants (toluene
 and ethyl-benzene).  Of the three remaining samples, Test Pit 2B
 was free of volatile organics.   Methyloxirane,  found at Test
 Pit 3, an 1,3-oxathiolane, found at Test Pit 2A, were identified
 through the library search.   The second observation is the rela-
 tively small number and concentrations of organic compounds on
 the priority pollutant list, toluene, ethylbenzene, di-m-butyl
 phthalate and bis  (2-ethylhexyl) phthalate were the only compounds
 detected.  With the exception of bis (2-ethylhexyl) phthalate,
 which was found at Test Pit 3,  organic priority pollutants were
 found only at Test Pit 2.

      In summary, Test Pit 2  revealed the most heavily contaminated
 soil.  There is a  relatively small number of priority pollutants
 and volatile organics in the test pit soil samples.  Those organics
 which have been detected and identified with the library search
 are rarely found at more than one test-pit location.  Pesticides
 and PCB have been  detected in shallow soils in  the area of Test
 Pit 2.

 Split Spoon Soil Sampling  and Results

      The soil zone sampled by split-spoon is adjacent to the
 initial contaminant sources  from the shallow soils of the test
 pits.  Shortly after the start  of dumping at Pijak Farm, the
 saturated soils likely retained or adsorbed a portion of the
-contaminants being carried by the ground water.   However, recent
 sampling indicates that ground  water presently  has signficantly
 lower contaminant  concentrations than the soil.   Therefore,
 these soils may be acting  as secondary sources  of contamination
 of  the ground water by the leaching process.            *

      Because of an oversight in the laboratory  procedures, the
 split spoon soil samples from Sites MW-4 and MW-5 were not
 subjected to preliminary OVA scanning and,  as a  result,  they
 were not considered for the  complete chemical analyses.   The

-------
 fact that there is low contamination in the ground water sample
 at these locations does not imply the absence of soil contamination.
 Ground water and soil samples from MW-1 and MW-2D support this
 notion.  Similarily, low near-background readings from OVA scanning
 are also not conclusive evidence that no contamination is present.
 This possibility is illustrated by the sampling results of MW-1.
 Therefore, since existing data makes extrapolation inconclusive
 the existence of contaminated soils at Site MW-4 and MW-5 is
 uncertain.  However, because of the proximity of Site MW-4 to a
 suspected dumping location, the detection of volatile organics
 by EFD's just downgradient of this area, and the contamination
 detected in a soil sample from nearby Test Pit 3, the soils at
 Site MW-4 should be considered as contaminated for the purposes
 of evaluation of remedial alternatives.  There is no visual
 evidence of waste disposal at MW-5 and nearby EFD's were not
 considered anomalous.  Therefore, the soils at MW-5 were probably
 not subject to direct contamination but could be affected by
 mobile contaminants migrating with the ground water.

      The split spoon samples were similar to the test pit samples
 in that of the 8 organic compounds identified, only 1 was a
 priority pollutant.  Methylene chloride was detected in three of
 four split-spoon samples which were subjected to complete chemical
 analysis.  Also, the highest levels of contamination were found
 at Site MW-2 near Test Pit 2 and the main buried waste disposal
 area identified by the EM survey.  In general, individual organic
 compounds were detected in concentrations of from 10 ug/kg to
 24,000 ug/kg while the average was on the order of 2,400 ug/kg.
 Inorganic compounds included on the priroity pollutant list were
 again found at all locations.   These concentrations ranged from
 0.011 ug/g to 61 ug/g.   None of the split spoon samples contained
 pesticides or PCB's.

      When compared to test pit sampling results the split spoon
 samples have a larger portion of volatile organics and virtually
 no acid extractable organics.   Also of note is the 400 ug/1 of
 methylene chloride, 1.1 ug/g of chromium and 310 ug/kg to 700
 ug/kg of 1-chlorodecane found  in a soil sample from MW-1.  Not
 only is this the upgradient well, but the sample was obtained
 at a depth of 40-42 feet below grade.

 Stream Sediment Sampling and Results

      One stream sediment sample was obtained where the main
 stream flows out of the study  area.   The chemical analysis
^showed this sample to be similar to the test pit samples but
 with fewer contaminant  species and smaller concentrations.
 Ethylbenzene was the  only organic priority pollutant detected
 in the sample.   Also,  the types and proportions of acid and base
 extractable organic compounds  were about the same.   Thesmain
 differences are the generally  lower concentration of organics,
 averaging about 5,500  ug/kg,  though the range of values is larger

-------
 (15  ug/kg  to 52,000  ug/kg).  The  inorganics  are  lower,  averaging
 about  2.8  ug/g.   Three pesticides on  the priority  pollutant  list
 were also  identified; 4 ,4'-DDT, 4,4'-DDE and 4,4'-ODD  in  concn-
 trations of  8.1  ug/kg, 10  ug/kg and 15  ug/kg,  respectively.

 Discussion of Remedial Investigation  Results

     The remedial investigation activity results at  the Pijak
 Farm site  indicate that  random dumping  occurred over the  entire
 wooded area  of the site.   A major disposal area was  found
 approximately 100 feet south of th stream traversing the  site
 and  approximately 700 feet west of Fischer Road.

     Of the  many compounds which have been identified  few are
 found  in more than one sample of a particular  sample type, while
 fewer  still  are  in different types of samples.  Though  it is
 expected that some degree  of breakdown  has occurred  in  the organic
 compound found in the shallow soils of  the test pits,  different
 compounds  were detected  in the ground water.

     Few of  the  organics found on-site  are in  the  volatile
 classification.   This implies that either these compounds were
 not  disposed  of  or that  the dumping practices  terminated  some
 time ago and  most of the volatiles have had  time to  dissipate.

     The majority of the numerous organic compounds  detected at
 the  site were identified through the acid or base  extraction
 process.   The fact that  these processes are  required to move
 the  compounds from the soil matrix indicates that, under  natural
 conditions, moving ground  water will leach out only  minor amounts
 Df these tightly  held compounds.  The stability of these  organic
 compounds  in  the  sediments is borne out by the relatively large
 number and concentration of compounds detected in  the soil samples
 while the  ground  water samples in general contained  few organics
 in relatively low concentrations.  However, at MW-2S concentrations
 of organics  in the shallow ground water were greater than concen-
 trations detected in split spoon samples obtained at the  same
 lepth intervals.   The detection of relatively stable organics in
 the saturated  soils over the site indicates that at  some  previous**
 time these compounds were  transported by ground water.  This
would be due  to  the sporadic nature of dumping and slow rusting
of drums which would tend  to result in low concentrations of
contamination  small distances from the source.  Over time the
soils accumulated contaminants by adsorption from moving  ground
water.

     Of the organic compounds found on-site,  it should  be noted
that few are  priority pollutants.  This means that most of the
compounds  used in this evaluation were identified through a
library search.

-------
      Inorganic  compounds were  the only contaminants that were
common  to the various  types of samples.  The results indicate
a general decline  in inorganic compounds as water moves further
from  source contamination areas.  These elements might be expected
in on-site or downgradient samples considering the concentrations
found in soils  on-site.  However, on-site sources at Pijak Farm
cannot  be the source of mercury and zinc in the upgradient monitor
well, the upstream surface water sample, and the potable wells
sampled as part of the Spence Farm study.  These concentrations
are within the  background levels for this area, which tend to be
unusually high.

     After assessing the priority pollutant and non-priority
pollutant data  generated during the remedial investigation
activities, it  can be  seen that no surface water or ground water
quality criteria are violated as a result of waste disposal at
the Pijak site.  The principal priority and non-priority organic
pollutants are  bound in the soil and released from the site as
sediment.  Therefore,  the control objectives are first to limit
or eliminate sediment  loss and second, to limit or eliminate
direct contact.  Because of the exotic nature of the non-priority
organic contaminants a numerical control objective could not be
developed.  However, given the relatively low level and low
toxicity of the contaminants present, dredging of these sediments
is not recommended.

     The focus of soil removal is on those species which are
priority pollutants or which are listed in Subpart D, Section
3001 of the Resource Conservation and Recovery Act (RCRA).
Potential criteria for removal include:

     0  An order of magnitude above detection limit for
        individual species using EPA Methods 624 and 625
        (detected limit approximately 10 ppb)

     0  A level of 500 ppb in soil of any single volatile
        species, based on ten times the NJDEP water quality
        criteria

     0  A level of 1 ppm in soil of total priority pollutants
        and RCRA Section 3001 pollutants ppb level permitted by
        the NJDEP.  The source of contamination appears to be
        the buried material found in Test Pit 2.

     Initial estimates of -the extent of soil removal to each
eriterion can be based on results of remedial investigation soil
analyses.  The most stringent criterion (ten times detection
limit or approximately 100 ppb for individual pollutants)  would
require excavation and reburial of material at depths ranging
from 26 feet (Well No. 9) to 30 feet (Well No. 2) to 3 ffeet.  It
is estimated that the resulting volume of excavation would be
approximately 98,000 cubic (Test Pit 3) yards, with 10,970 cubic
yard for disposal.

-------
      For the second approach,  based on 500 ppb of any pollutant
 (ten times the NJDEP criteria),  the levels of excavation would
 be similar, that is, 98,000 CY excavated and 10,970 removed
 for disposal.

      For the third possible criterion, i.e., 1 mg/kg of  total
 RCRA Section 3001 pollutants,  the extent of removal would be
 much reduced based on data resulting from the remedial investi-
 gation.   Only the monitoring Well No.  2 soil sample (301  depth)
 showed total RCRA pollutants in  excess of this criterion.
 Therefore, approximately 5,500 cubic yards would  require  excavation
 and 370  cubic yards would require removal under this criterion.

      The results of a ground water sample taken at MW-2S  show  the
 well to  be contaminated with volatile  organic priority pollutants
 greater  than 100 ppb.  Nor can on-site sources account for the
 organics found in the upstream surface-water sample or the presence
 of methylene chloride and chromium in  a deep split-spoon  sample
 of the upgradient monitor well.   Possible explanations might
 include  off-site dumping areas,  a flaw in sampling and/or anlaysis,
 or,  in the case of mercury and zinc,  their natural occurrences
 or the application of agricultural substances containing  these
 elements.

 Alternatives Evaluation

      After assessing the all data generated during the remedial
 investigation activities,  it can be seen that surface water
 quality  is not violated as a results of waste disposal at the
 Pijak Farm site.    However,  a  violation of ground water quality
 criteria has occurred.   The  ground water contamination found in
 MW-S2 exceed ground water quality standards.

      The principal priority  and  non-priority organic pollutants
 are  bound  in soil and released from the site as sediment  or found
 in one area of burned,  buried  waste.   Therefore,  the control
 objectives are first,  to limit or eliminate sediment loss,  second,
 to limit or eliminate direct contact,  and third,  to remove  the
 buried material and contaminated ground water.  Because of  the
 exotic nature of  the non-priority organic contamination,  no
 numerical  control objective  could be developed.   However,  given
 the  relatively low level  and low toxicity of  the  species  present,
 dredging of these sediments  should not be necessary.

      The initial  screening of  alternatives can  be done based on
-cast,  effectiveness,  and  acceptable engineering practice.   The
 most  significant  pathways  with the potential  for  adverse  impacts
 on public  health  and the  environment are to limit or eliminate
 pollutant  migration and  direct contact.   The  candidate remedial
 actions  identified  in  the  National Contingency  Plan are presented
 in Table 2.

-------
                               10
     The screening of remedial alternatives indicates that remedial
action will be necessary to mitigate the threat to public health,
welfare and the environment.  Source control action which would
lessen the migration of stream sediment and measures to eliminate
direct contact will also be required.  For this reason the "No
Action" alternative was not considered in the detailed Evaluation
of Alternatives.
                    SEE INSERT A.
     The following remedial action alterantives were developed
for a more detailed analysis of effectiveness and cost measure.

Alter nati ye 1 - Waste, soil and groundwater removal, dam and pond
for sediment control, groundwater removal, fencing and direct
access control and groundwater monitoring.

Alternative 2 - Waste, soil and groundwater removal, berms along
stream for sediment control, groundwater removal, fencing and
groundwater monitoring.

Al ter ria t i ve 3 - Waste, soil and groundwater removal, berms along
stream and site perimeter, groundwater removal, fencing and
ground water monitoring.

Alternative 4 - Waste, soil and groundwater removal, site regrading
and surface restoration, groundwater removal, berm along site
perimeter, and ground water monitoring.

A11 e r na t i ye 5 - Removal of all waste and contaminated soil,
ground water removal and site restoration.
       t
A11e rna t rye 6 - Construction of on-site landfill to RCRA and
NJDEP landfill specifications, ground water removal,  site
restoration, and ground water monitoring.

     The cost-effective alternative is defined as the lowest cost
alternative that is technologically feasible and reliable and
which effectively mitigates damage to and provides adequate
protection to public health, welfare and the environment.

     The following evaluation of the six remedial action alter-
natives will consider their present worth cost as well as their
effectiveness in controlling direct contact and sediment migration.

-------
                               lOa
   INSERT AT A.

     The alternative of closing the site in accordance with RCRA,
without the removal of any waste off-site for disposal, was
eliminated during the initial screening of alternatives.  This
alternative did not significantly lessen the migration of
contamination through ground water already in contact with source
materials.  In addition, the scattered disposal of drums and lab
packs would require the extensive capping of the site.  However,
the discrete removal of the drums, lab packs, and visibly
contaminated soils would be significantly lower in cost, as well
as more environmentally secure, and will facilitate capping the
remaining contaminated soils.
                                                     - - m   f.
                                                       L iK I INITIALS


-------
                                11


Alternative  *1

     This alternative would  include  removal of contaminated waste,
soil and ground water from the  site  and  the construction of a
dam across the stream flowing through  the site.  The proposed
dam would be  located below the  perimeter of the site approximately
200 feet upstream of the confluence  of the stream flowing through
the site and  the Stony Ford  Brook, as  shown in Figure  3.

     The total drainage area of this stream is approximately 190
acres.  Designing the basins to contain a 100 year storm event
would require the construction  of a  dam 175 feet wide  and approx-
imately 8 feet high.  The pond  created during a 100 year storm
event would have a volume of approximately 517,000 ft3 and
depth of approximately 6 feet at the dam.  The basin will have
an emergency overflow riser pipe and will be dewatered by the
use of subsurface drains.

     The effects of this dam will only be realized during storm
events when a pond will be created as a result of the  excess of
inflow entering the basin over  the capacity of the subsurface
drain.  The area behind the dam will be a relatively calm area
where the sediment transported by the stream will slowly drain.
Preliminary calculations indicate volume of approximately
38,000 ft3 of soil will be removed annually.  Therefore, the
periodic excavation of this sediment will be required.  The
sediment yield of 38,000 ft3 will not all be delivered to the
dam.  For sandy soils, approximately 19 percent of the sediment
yeild will occur at the dam, with the remainder being  deposited
upstream of the pond area.  Therefore, the annual sediment yield
will be approximately 7,200 ft3, or  270 CY.  The area  behind
the dam is over eight (8) acres, so  the sediment yield will
require approximately 50 years to fill one foot.  Removal of
sediment is recommended every 15 years.

Alternative »2

     This alternative includes the removal of contaminated waste,
soil and groundwater from the site as well as the construction
of berms along the banks of the stream flowing through the site.
These berms would prevent the surface runoff passing through the
site from carrying contaminated soil into the stream.  The area
upgradient of the berm will be so graded that the surface runoff
will be directed towards a sediment basin where the contaminated
soil will settle out.
  „•
     Approximately 3800 linear feet of berms would be  required
to isolate the stream as it flows through the site as  shown in
Figure 4.  The total drainage area tributary to and including
the site is aproximately 55 acres.  The berm on the soutrh bank
would have tributary to it a drainage area of approximately
15 acres while the berm on the north bank would have approximately
40 tributary acres.  Designing the respective basins (north and

-------
                                12


 south side) to withhold a 100 year storm event would require
 basins with volumes of approximately 90,000 ft3 and 22,000 ft-*
 respectively.  Each basin would be designed with an emergency
 overflow riser pipe and will be dewatered by the use of subsurface
 drains.

      The effects of the berms will be to prevent the contaminated
 soil from entering the stream and leaving the site.  Preliminary
 calculations indicate that the basins on the north side of the
 stream will remove annually approximately 1,900 ft3 of soil.  The
 south side basin will annually remove approximately 25 ft3 of
 soil.  Excavation of this sediment every 15 years is recommended.

 Alternative »3

      This alternative includes the removal of contaminated waste,
 soil and ground water from the site as well as the construction
 of berms along the backs of the stream and along the upland
 perimeter of the site shown in Figure 5.

      The addition of the perimeter berm would prevent upland
 runoff from flowing over the site, by directing it to a point
 further downstream.  This alternative would require approximately
 2200 feet of smaller sized berms to isolate the site.  This is
 in addition to the approximately 3800 linear feet of berms required
 to isolate the stream as it flows through the site.  Therefore,
 the total drainage area tributary to the site would be greatly
 reduced.  The north side berm would have a drainage area of
 approximately 10 acres.  The south berm would have a drainage
 area of approximately 15 acres.   The respective basins required
 to withhold a 100 year storm event would have volumes of approxi-
 mately 21,000 ft3 and 22,000 ft3.   Each basin would be designed
 with an emergency overflow riser and will be dewatered by the
 use of subsurface drains.   With  the construction of a perimeter
 berm, there is a reduction in size required for the sediment
 basins.   Similarly, the amount of sediment removed prior to
 entering the stream is also reduced.   Preliminary calculations
 indicate that the basin on the north side of the stream will
 remove annually approximately 15 ft3 of soil.   The south side
 basin will remove approximately  25 ft3 of soil annually.  With
 this small quantity,  removal of  sediment should not be required
 over the thirty year planning period.

 Alternative #4

T '    This alternative involves the removal of contaminated waste,
 soil and ground water from the site as well as construction of a
 temporary dam,  regrading of  areas  of  high slope and covering with
 native material,  construction of a site perimeter berm for runoff
 control  and the restoration  of vegetation.              *

-------
                                 13


      The  greatest source  of  contaminated  soil  is  the  embankment
 area  marking  the transition  from upland to  wetland  areas.   The
 slope of  this embankment  area  ranges  from approximately  1.5 to
 1  to  approximately 3  to  1.   To regrade the  slope  to 4  to 1  and
 cover with  one foot of contaminated material will require
 approximately 6  cubic yards  of excavation per  linear  foot of
 slope.   In  addition,  the  slopes will  require clearing  and
 grubbing  (approximately 3.4  acres) before regrading and  will
 require  surface  restoration  after regrading for the area shown
 in Figure 6.   To further minimize erosion,  the site perimeter
 berm  described in Alternative  13 will be  incorporated.   The
 final stage of construction  will be the removal of  the temporary
 sediment  control dam.

 Alternative #5

      This alternative would  involve removal of contaminated
 waste, soil and  groundwater  from the  site.  Removal of the  top
 two feet  of soil with proper regrading and  revegetation  would
 remove the  potential  for direct contact and potential  for soil
 loss  and  consequent sediment migration.

      This alternative would  require the construction of  a temporary
 dam for the control of sediment loss  during construction.   The
 area  affected  by removal and restoration  is estimated  to be 3.4
 acres with  the volume of soil  to be removed being 10,970 cubic
 yards.

 Alternative t6

      This alternative involves  the removal  of  contaminated  ground
 water from  the site.  Contaminated waste  and soil will be excavated
 and placed  in  an on-site RCRA  quality controlled  landfill.  This
 landfill  will  be constructed in an upland area.

      In addition to RCRA criteria, NJDEP  landfill criteria  for
 new construction were used in  development of the  design.  These
 additional  criteria include  double, rather  than single,  lining
 and specifications  for surface  cover  and  drainage layers.   The
 RCRA  landfill  configuration  is  shown  in Figure 7  with  the disturbed
 area  and  tentative  landfill  locations shown in Figure 8.  The
 landfill  design  includes site  regrading,  a  double bottom layer
 for leachate control, surface  sealing using a  clay  cap and  new
monitoring  wells.

~. '   Excavation  and removal  of  contaminated surface and  subsurface
 soils will  require  excavating  approximately 75,600  CY of soil,
of which  8,890 CY would be placed in  the  landfill in addition
 to the 4000 CY to be removed.   This excavation will require well
pointing  to lower the groundwater sufficiently for  removal  of
contaminated materials at an average  depth  of  15  feet below
grade.  For sediment control the  temporary  dam would also be
 required.

-------
                                 14


 Community  Relations

      A public meeting was  held  by the NJDEP  on  February 7.  1984.
 to  discuss the  initiation  of  a  Remedial  Investigation/Feasibility
 Study (RI/FS) for  the Pijak Farm site.   Notification  of the
 meeting was  accomplished through press releases sent  to all
 newspapers listed  in the Pijak  Farm Community Relations Plan and
 mailings to  all parties listed  in the "Contacts" section  of the
 plan.   An  information package,  including an  agenda, fact  sheet.
 overview of  the Community  Relations Program  at  Superfund  sites.
 and  the steps involved in  a major hazardous  waste  site cleanup.
 was  given  to all attendees at the beginning  of  the meeting.  The
 meeting was  attended by approximately 30 people in addition to
 local  Township officials and  NJDEP representatives.   After  the
 initial presentation by the contractor,  Elson T.  Killanir the
 meeting was  opened for public discussion.  There were four  questions-
 asked  by citizens with regard to testing of  the ground water.  'The
 state  officials responded  to  these inquiries.

      A second public meeting was held by NJDEP  on August  16, 1984.
 to discuss the results of  the RI/FS.  An information  package
 including  the agenda and fact sheet were provided to  the 'approxi-
 mately 30  people who attended.   The contractor  outlined the
 objectives,  scope of work, results and conclusion of  the  RI/FS.
 Six  alternatives were discussed.  The contractor's recommended
 alternative  included: removal of drums,  lab  packs and contaminated
 soil,  site regrading and surface restoration and berming  the
 perimeter  of the site.  Numerous questions were asked by  the
 public  regarding the proposed remedial alternative.   The  State
 officials  were able to respond adquately to  all concerns  raised
 by the  public.

     The Remedial Investigation/Feasibility Study was available
 for  public review and comment, beginning on August 17r at three
 locations  the Ocean County Library in Toms River, the Plumsted
Township Municipal Building, and the NJDEP1s Hazardous Site
Mitigation Administration in Trenton.   There was one  letter
 received prior to the conclusion of the twenty one day comment
period.

     A  letter was received from Mr.  Edward C. Larid.  Esq.  ,
attorney for Morton-Thiokol.  This letter included comments
concerning the technical feasibility and detailed implementation
of the  various facets of the recommended alternative.   The
comments, that are directly related to the first phase of the
recommended remedial alternative, have been considered in this
Record  of Decision document and the NJDEP's response  is included
 in the  responsiveness summary.

Consistency With Other Environmental Laws

     The final recommended remedial  alternative for Pijak Farm
will require the removal of containerized waste and visibly
contaminated soil.   These  materials  will be manifested for

-------
                                15


 transport  from  the site  to a secure facility in accordance with
 RCPA and TSCA requirements.

     .The benefits of reducing direct contact ot the residual
 contaminants and the migration  of these contaminants into the
 stream  for outweigh the  minimal  impacts on the floodplain.  The
 NJDFP Bureau of Floodplain Management will require the incorpor-
 ation of specific environmental  specifications into the cleanup
 plan to minimize the impacts on  the floodplain.  The cleanup
 contractor will be required to  obtain a Stream Encroachment
 Permit  from the NJDEP prior to  the initiation of any work in
 the floodplain area.  The floodplain management assessment is
 inclused as Attachment I.

 Enforcem enjt

     The State of New Jersey and EPA have identified Morton-
 Thiokol. Inc., and Dayton Hopkins (former property owner) as
 potential  responsible parties (PRP's).  Notice letters were sent
 by the State to Thiokol  on March 18, 1982.  This resulted in a
 meeting with Thiokol of  July 7,  1982. to discuss its role in
 undertaking the site cleanup.

     Further correspondence resulted in Thiokol submitting two
 proposals  for conducting a modified RI/FS.  These proposals were
 rejected by EPA on January 16,  1983.  A second Notice Letter was
 sent to Thiokol on March IP, 1983 indicating the State would be
 responsible to perform the RI/FS.

     The State of New Jersey and EPA Region II have designated
 this site  a State enforcement lead.   Currently, the State of New
 Jersey is  negotiating an Administrative Consent Order with Morton-
 Thiokol, Inc.  for the clean up of this site.  There will be a
 negotiation period of no greater than sixty (60)  days from the
 signing of the ROD.  The recommended remedial actions included
 in this Record of Decision will be incorporated by the State
 into the Administrative Consent Order.  If New Jersey is not
 successful in these negotiations EPA will likely issue a §1U6
Order for  the selected remedy and later pursue a Cost Recovery
Action against Morton-Thiokol.

Recommended Alternative

     According to 40CFR Part 300.68  (j), cost-effectiveness is
described  as the lowest cost alternative that is technically
 feasible and reliable and which effectively mitigates and
minimizes  damages to and provides adequate protection of public
health,  welfare and the environment.   A cost comparison of remedial
alternatives is presented in Table 3.   The evaluation of the six
 remedial alternatives leads to the conclusion that Alternative 1*4
 is the most cost-effective.

-------
                                 16
      Of the remaining alternatives,  the initial  three were  all
 found to have slightly higher present  worth cost.   In addition.
 operation and maintenance costs were significantly greater  for
 all three alternatives.   The permanent loss of  forest and wetlana;
 areas are common to all  these activities.   Furthermore,  contami-
 nation would remain on site in the surface water sediment for
 these alternatives.

      Alternatives 5 and  6 would result in  the permanent  loss of
 forest and wetland areas.  These two alternative were also  far
 more costly than the recommended alternative.

      The components of Alternative #4  are  technically feasible
 and reliable and when combined,  provide adequate protection of
 public health,  welfare and the environment.   The removal of
 containerized wastes and contaminated  ground water and visibly
 contaminated soils to a  secure hazardous waste management facility
 is  a reliable remedial measure.   The regrading of  the site  in
 conjunction with placing clean fill  will effectively  control
 direct contact  with residual contaminants.   The  construction of
 a temporary dam during excavation activities will  eliminate the
 off-site migration of contaminants.  The monitoring of existing
 on-site wells for a period of five years after the completion of
 the remedial action will evaluate for  the  possible migration of
 contaminants from the site,  thereby, ensuring the  effectiveness
 of  the remedial action.

      The Agency and the  State of  New Jersey  have decided to
 proceed with the recommended alternative as  a multiphase remedial
 action.   Phase  I will consist of  :   The excavation of surface
 waste material  and visibly contaminated soil;  the  transportation
 and off-site disposal of the excavated material; dewatering
 during excavation and disposal of contaminated aqueous materials
 generated;  the  monitoring of ground  water  for a  five-year period;
 and further sampling and analysis of soil,  stream  sediment  and
 ground water in the areas of the  excavation.  The.additional
 sampling will be conducted to establish the  design criteria £05,
 the next phase  of the remedial action.   Sediment control measures
 will  be taken during excavation  and  sampling efforts.  Based on
 the results of  the sampling  and  analysis effort, Phase II will
 consist  of?   site regrading  and  closure; ground  water monitoring;
 and if necessary,  additional excavation of  contaminated  soils
 and/or sediments and off-site disposal  of  the excavated  materials.
-and,  the off-site removal,  treatment and disposal  of  contaminated
 ground water.

      The following listed  figures respresent a cost estimate for
 the proposed  actions.  Cost  sharing  for project  implementation
 is  90%  Federal  and 10% State on  capital costs and  the first
 year  of  O&M monitoring costs.  The remaining  four  years  of
 monitoring  costs will be borne by the  State  of New Jersey.

-------
                                17
       Cost Summary for Recommended Remedial Alternative #4
Remedial Measure
   Component

Waste Removal & Disposal

Ground water Monitoring

Sampling and Analysis

TOTAL COST
Capital
  Cost

$1,737,750
   225,000
$1,962,750
Present Worth
   of O&M
                 53,600
     __
Present Worth

 $1,737,750

     53,600

    225,000
    $53,600
 $2,016,133
Operation and Maintenance

     Upon completion of all remedial actions, monitoring of the
site will be necessary to evaluate the migration of any contami-
nants into the local groundwater.
Future Actions

        Schedule

    Final Record of Decision
    Continue negotiation with
      Morton-Thiokol
    Amend Cooperative Agreement
      (if necessary)
    Initiate Design
      (if necessary)
    Complete Design
      (if necessary)
                     Date

                September 1984

                October-November 1984

                December 1984

                February 1985

                August 1985

-------
        PENNSYLVANIA
                              PIJAK FARM - VICINITY.MAP




                                       \FIGURE 1
                                 STATE
                                                               NEW    YORK
                                                    NEWARK
OF
                                   .TRENTON
                                                 /  MONMOUTH CO. // '
DELA*
              SITE
               .^
                   -*\
ss*T^^V
t \
~-*s \
I

x-'

NEW JERSEY



-------
                    FIGURE 2
               PIJAK FARM
           NEW EGYPT. NEW JERSEY
         REGIONAL SITE LOCATION MAP
                       Qr >!
                       _  '»s^/T»
> -
• f <-
PIJAK FARM SITE
2000 FOOT RADIUS
                                   SCALE IN FEET ;2
                                     0   1000 2000
                                         /
                          LEOOETTE. BRA3HEAR3 A GRAHAM. INC.

-------
                                                        APPROX!
                                                             T!O
                                                            POSED DAM
FIGURE 3  - Illustration  of  Alternative.#1


  SCAI.K:   I"  =  l.JOU'i
  -SOL'RCE: .U.S.C.S.  TOPO MAPS
           PIJAK FARM
  PLUMSTED TOWNSHIP, NEW JERSEY
DAMMING WITH  STREAM  PONDING
   El»on T. Klltom At>oc»»t«», Inc.
                                                          .               ,   .
                                                    tnvironm«nt»i tno Hydrauic Engineers
                                                    tr •....„ I,,..,  „,„„„,„ „.. W>MT  0,04,

-------
FIGURE 4 - Illustration of  Alternative #2




   SCAI.K:   1" = I ,Jl)U'±-

   SOURCK:  I .S.C.S. TOPO  MAPS
          ?:JAK  FARM

PLUMSTED TO'.-.-JSHlP,  NEW JERSEY


     BERMS ALONG  STREAM

El«on T. KllUm At.ocKt.s. Inc

Environmental
                                                               and Hydraulic Engineers
                                                           »"««i  u.iie,,,. H.. rt,,,f  0,o4,
Oi

-------
                                 PPROXIMATE LOCATION
\ v  '  :; n  •'' -i
 \  >i  *u  ;:    \
FIGURE 5 - Illustration of Alternative #3



    SCALE:   I"  = l,J(JO'±

    SOl'RCK: U.S.ti.S. TOPO  >L\PS
                                                          PIJAK FARM

                                                PLUMSTED  TOWNSHIP, NEW JERSEY


                                                      PERIMETER BERMS
                                               Elton T. Kllfrm At»ocl«tt». Inc.'

                                               Environmental and HydrauK Enoineers"
                                               J7 ....... Si...,  M.,,D.,. „,. rt,,.Y 0,04,

-------
FIGURE 6 -  Illustration of Alternative #4

  SCALE:   1"  =  l,200'±
  SOURCE:   U.S.G.S.  TOPO MAP
         PIJAK FARM
PLUMSTED TOWNSHIP, NEW JERSEY
      SITE  REGRADING
        & RESTORATION
Eicon T. Klltom Asaoclatci, Inc.
Environmental and Hydraulic Engineers
>' «!••••• ItrMt

-------
                                            FIGURE 7 - Sketch of RCRA Landfill
NEW SURFACE
ELEVATION
        ORIGINAL
        SURfACE
        ELEVATION
  ?.' CLAY CAP
                                             MINIMUM 5"  SLOPE  TO DRAIN-
-  TO LFACHATE
   HOLDING TANK
                                                      UNDERDRA1N (TYP.)
                                                                                  I t
   NOT TO  SCALE
                                                          PIJAK
                                                 PLUMSTED TOWNSHIP. NEW JERSEY
                                                           ON-SITE
                                                       SECURE LANDFILL
                                                  f (sen T. KMtam Associates, Inc.

-------

                                   .
.^'l^:.	__.  •_-.•   JT-—.  4\/£NU'  .4-—.-..-»• \.
       »•--••     r""w' —-•*"  '     '!
                                   pH   :AV..  •/•-•••?#
                                             N
         A              -*-f
         V- •-  :   -.V^-l
FIGURE 8 - Illustration of Alternative #6




 SCALE:  1" = l,200'±

 SOURCE: U.S.U.S. TOPO MAP
       P'JAK FARM

PLUMSTED TOWNSHIP, .\EW JERSEY

   EXCAVATION  AND ON

     SITE  LANDFILL

El»on T. Klllam A««OC|«t«t. inc.
                                        Environment and Hydraulic Eng,n««rs"
                                        IT in.... s>'..i M.,,B|,,« w,. j.,M, 07041

-------
                           Table  1
              Summary of On-Site Waste Material


Estimate of Drummed Material

Site                        |Drums                 Drums Intact

TP 2A                         50                        20
TP 4B                          10                         5
TP 5                          4                          2
Scattered                     50                         0
                             114                        TT

Labortary Packs;

Site                         Number

TP 2                          400

Buried Material

Site                         Quantity

TP 2                          4000 CY

-------
Eicon T. Klllsm Associates, Inc.
0
                                       TABLE 2
                             Screening of Altetnatives
                                                   Acceptabl  e

  Remedial                     Need For                 Effective-    Engineering
  Action                       Action?        Cost?       ness?         Practice?


  I.  Emissions Control
    A.  Air Emissions Control
      1.  Pipe Vents              N
      2.  Trench Vents            N
      3.  Gas Barriers            N
      4.  Gas Collection          N
      5.  Overpacking             N

    B. Surface Water Controls

      1.  Surface Seals           Y            N            Y               Y
      2.  Diversion/Collection
        a.  Dikes & Berns         Y            Y            Y               Y
        b.  Ditching              Y            Y            Y               Y
        c.  Chutes                Y            Y            Y               Y
        d.  Levees                Y            Y            Y               Y
        e.  Seepage Basins        Y            Y            Y               Y
        f.  Sediment Basins       Y            Y            Y               Y
        g.  Terracing             Y            Y            Y               Y

    C.  Groundwater Controls
      1.  Impermeable Barriers    N
      2.  Permeable Treatment     N
      3.  GW Pumping              Y            Y            Y               Y
      4.  Leachate Control        N

    D.  Contaminated
          Sewer Lines             N
                                         -9-

-------
Elton T. Klllsm Associates, hie.
TABLE 2
PIJAK FARM
Acceptab
Remedial Need For Effective-
Action Action? Cost? ness?
II. On Site Treatment
A. Direct Treatment
1. Biological N
2. Chemical N
3. Physical N
B. Contain. Soil /Sediment
1. Incineration Y NY
2. Wet Air Oxidation Y NY
3. Solidification N
4. Encapsulation Y Y Y
5. In-Situ Treatment N
III. Other Control Technology
A. Removal for Off-Site
Treatment or Disposal Y Y Y
B. Provision of Alternative
Water Supply N
C. Relocation N
D. Other
1. Securing Site Y Y Y
2. Monitoring
a. Groundwater Y Y Y
b. Surface Water Y Y Y
C. Air N
~ Uc^.

1 e
Engineering
Practice






Y
Y

Y



Y




Y

Y
Y

                                           -10-

-------
                                                                               TABLE  3
               Alternative

               1.  Permanent Dam
               2.  Berm along
                    Stream
     Present Worth Costs
Capital        O&M      Total
COMPARISON OF ALTERNATIVES

        PIJAK FARM

  Control             Effectiveness  for
  Objective   Sediment   Groundxater   Access
  -Soils     Control    Control       Control
SI.942.140   S167.390  S?. 109.530     1  ppm      LT  lOOt    LT  1001      LT 1001
S2.045.7PO   $130.620  S2.176,340     1 ppm      IT  100X     LT  100*      LT 1001
          Adverse  Environmental
                Effects	

         Permanent Loss  of Forest
         & Wetland,  Contaminated Sed-
         iment  On-Site
                                                  Permanent Loss of Forest
                                                  I Wetland. Contaminated Sed-
                                                  iment On-Site
ro
CD
               3.  berni along
                    Stream & Peii-
                    mete.      -       S2.IVP.S70    SIOH.MQO.  S2.I31.460    1 ppm      LT 100X     IT 100%      LT  1001
                4;  Kegrading &  • '
                    Restoralion      Sl.976.5hd   S  f,4,730  S2.041,290    1 ppm
               5.  Complete Removal
                    I Restoration    S7.29l.S7n
                       $7.291.570    loo ppb
                                                                                       100S
                             100S
                                                                                     Permanent Loss of Forest
                                                                                     & Wetland, Contaminated Sed-
                                                                                     iment On-Site
                                                   lUOt      LT  1001      LT- 100X     Temporary Loss of Wetland
1001     Permanent  Loss  of  Forest
         & Wetland, Groundwater
         Movement
               6.  On-Site land-
                    fill
S2.1.VJ.HJU   SJH). I'jO  S2.970.180    100 ppb
                100X         1001         1001     Permanent Loss of Forest
                                                  Wetland, firm Lands. Ground-
                                                  water Movement

-------
                           ATTACHMENT 1

                         Pijak Farm Site
                            New Jersey

                FLOOD PLAIN MANAGEMENT ASSESSMENT
  I.  Purpose

      The purpose of this addendum is to:

      1.  Review Executive Order No. 11988, May 24, 1977, 42 F.R.
          26951 entitled Floodplain Management•

      2.  Review applicable statute referred to in the Executive
          Order as required?

      3.  Review the proposed Remedial Alternative as it relates
          to the floodplain;

      4.  Summarize the review and describe any technical
          requirements necessary to comply with (1) and (2)
          above.

II.    Introduction

          A Remedial Investigation/Fresibility Study (RI/FS) was
      prepared by Elson T. Killam Associates,  for the New Jersey
      Department of Environmental Protection (NJDEP), to determine
      the extent of contamination on-site and  to evaluate remedial
      alternatives.  The Pijak Farm site is located in Plumsted
      Township, south of Route 528 and approximately 1000 feet
      west of Fischer Road.   Waste disposal occurred at several
      locations along the edge of an open field  and in an adjacent
      low-lying wooded area  which drains to a  small stream,  and
      ultimately to Crosswicks Creek.

          The random dumping of hazardous wastes via drums and
      lab packs has resulted in numerous areas of contamination.
      Investigative activities indicated a majority of the drums
      dumped at the site were intentionally opened or rusted
      through and their content dispersed.   This has resulted in
      many areas of contaminated surface soils,  along the stream
      banks.

          At all times the stream flow is below  the areas of soil
      contamination.   However, during  times of high flow scouring
      of the stream bank can result in the  migration of contaminants
      into the waterway.   Also,  precipitation  runoff can carry
      the contaminants from  the low-lying areas  into the stream.
      Figure 1 shows  the general location of the remedial activity.
      Currently the slope in this area of the  stream ranges  from
      1.5* 1 to 3^   1.

-------
                          ATTACHMENT 1

                        PIJAK FARM SITE
                           NEW JERSEY
               FLOOD PLAIN MANAGEMENT ASSESSMENT

 I.  Purpose

     The purpose of this addendum is to:

     1.  Review Executive Order No. 11988, May 1977, 42 F.R.
         26951 entitled Floodplain Management;

     2.  Review applicable status referred to in the Executive
         Order as required;

     3.  Review the proposed remnant site contaminant option
         as it relates to the floodplain  of the Hudson River;

     4.  Summarize the review and describe any technical require-
         ments necessary to comply with ( 1) and (2) above.

II.  Introduction

          A Remedial Investigation/Feasibility Study (RI/FS) was
     prepared by Elson T. Killam Associates, for the New Jersey
     Department of Environmental Protection (NJDr,P), to determine
     the extent of contamination on-site  and to evaluate remedial
     alternatives.  The Pijak Farm site is located in Plumsted
     Township, south of Route 528 and approximately 1000 feet
     west of Fischer Road.  Waste disposal occurred at several
     locations along the edge of an open  field and in an adjacent
     low-lying wooded area which drains to a small stream, and
     ultimately to Crosswicks Creek.

          The random dumping of hazardous wastes via drums and
     lab packs has resulted in numerous areas of contamination.
     Investigative activities indicated a majority of the drums
     dumped at the site were intentionally opened or rusted
     through and their contents dispersed.  This has resulted in
     many areas of contamination surface  soil along the stream
     banks.

          Virtually all of the time the stream flow is below
     the areas of soil contamination.  However, during times of
     high flow scouring of the stream bank can result in the
     migration of contaminants into the waterway.  Also,
     precipitation runoff can carry the contaminants from the
     low-lying areas into the stream.  Figure  1 shows the general
     location of the remedial activity.  Currently the slope in
     this area of the stream ranges from  1.5 to  1 to 3 to  1.

-------
                                -2-
           A Flood Insurance Study for Plumsted Township was
      completed in March 1981, and the Flood Insurance Rate Maps
      were published in March 1982.   Based on this study it appears
      that the low-lying areas of the Pijak Farm site are within
      the 100 year flopdplain.  However,  it should be noted that
      the actual location of the 100 year flood was not determined
      from the flood insurance study.

 III.  Proposed Site Remedial Action

           The selected remedial action for the Pijak Farm site
      includes the removal of drummed material and lab packs and
      adjacent contaminated soil. After  additional samples are
      taken to determine the extent  of soil contamination, clean
      fill material will be placed in area where removals have
      occurred.  The clean soil will be graded to its original
      condition prior to the removal action.

 IV.   Flood _P_I_ai_n_ jtegu1 atory Reguirements

           In accordance with Executive Order 11988, Floodplain
      Management,  an applicable executive agency shall provide
      leadership and shall take action to reduce the risk of
      flood loss,  to minimize the impact  of floods on human
      safety, health and welfare, and to  restore and preserve the
      natural and  beneficial values  served by floodplains.  In
      addition, it is necessary to evaluate the potential effects
      of  any action that may be taken in  a floodplain and to
      assure that  potential harm is  minimized.

      The following agencies would be involved in any floodplain
      management efforts:

      0   United States Environmental Protection Agency
      0   U.S. Army Corps of Engineers
      0   Federal Emergency Management Agency
      0   New Jersey Department of Environmental Protection

      As  a responsibility  under the  cooperative agreement between
 the USEPA and the NYSDEC  the appropriate agencies and concerned
 groups will be kept abreast of proposed  design and construction
 activities.

      The EPA in conjunction with the NJDEP has determined that
-the proposed activities for the site are the most practical
 options  available in light of current funding  limitations and
 technical constraints.   It is not expected that working in the
 low-lying area will have  any major  or long-term detrimental impacts
 on the floodplain, since  the majority of the work will bfe temporary
 sediment control  measures.

-------
                             =3-


Flood Hazard Assessment

     Part of the future recommended remedial action for the Pijak
Farm site includes the removal of contaminated soil along the
stream channel and thus involved working in the floodplain.  The
benefits of reducing direct contact of the residual contaminants
and the migration of these contaminants into the stream far
outweigh the minimal impacts on the floodplain.  The NJDEP Bureau
of Floodplain Management will require the incorporation of specific
environmental specifications into the cleanup plan to minimize
the impacts on the floodplain.  In addition, the cleanup contractor
will be required to obtain a Stream Encroachment Permit from the
NJDEP prior to the initiation of any work in the floodplain area.

-------
                                       APPROXIMATE   *
                                       LIMITS OF SITE
SC:AI.I::   r  =  1,^00'±
SOCRCK: -U.S.C.S.  TOPO M\1JS
            FIGURE 1
          PIJAK FARM
PLUMSTED  TOWNSHIP, NEW JERSEY

 APPROXIMATE SITE  LIMITS
El«on T. KHlam At»ocl«t««. Inc.' P|r"T
*       I and Hydraulic Engineers I 1*^.
        1  tMtvra. Nra MfMr  07041 h^MBM
                                                                                 .®

-------
                                                \  __ _.__ ';
                                                *    	

                                                 ArrrMrv
                           .»f t » + * x» •»
                            SEP 28
                                                      : t A^'IJ fc •
MEMORANDUM
SUBJECT
FROM:
TO:
Authorization to Proceed with Remedial Action for the
Pijak Farm Site, New Jersey - Record of Decision
William N. Hedeman, Jr., Director.
Office of Emergency and Remedial

Lee M. Thomas
Assistant Administrator
                                                  J
     The attached Record of Decision  (ROD)  is presented  for your
authorization of remedial action at the subject site.  We are
asking your approval for the excavation and off-site disposal of
drums, lab packs, and adjacent soils  in accordance with  RCRA.
We are also recommending the sampling and analysis for possible
soil and ground water contamination,  in order to determine the
extent of contamination and the possible need for further excava-
tion.  A supplemental ROD will be developed for site regrading
and closure, as well as excavation if additional action  is
determined to be necessary.

    Funding is included in the FY-85  SCAP for the remedial design
of the above cited remedial activities.
Attachment

-------

I   =.,.          UN I TED'STATES ENVIRONMENTAL PROTECTION AGENCY

\ ^il'l/ / ""•   t=r:- .•—------  . WASHINGTON. D.C. 20460
    '
                                                    2 r i. i D W AST E A N D E I.1: ! i C L :
     MEMORANDUM
     SUBJECT:  Record of Decision for Approval of Remedial  Action
                   the Pijak Farm 8*1 te, New Jersey
     FROM:     /Francis J. Biros, Director
                CERCLA Enforcement Division,
                Office of Waste Programs Enforcement  (WH-527)

     TO:        William N. Hedeman, Jr., Director
                Office of Emergency and Remedial Response  (WH-548E)
          The Record  of Decision for the Pijak Farm Site,

     New Jersey  has been reviewed by my staff.


                               I Concur                	*

                               I Do Not Concur
                               I Concur With the
                                Attached Conditions
                                              Date
     Comments:

-------
  DATE:
SUBJECT:
  FROM
    TO:
                  UNITED STATES ENVIRONMENTAL PROTECTJON.AGENCY-
Record of Decision
Pijak Farm

Christopher J. DagqefetA +s^,
Regional AdministratwV>^^^

Lee M. Thomas
Assistant Administrator
 Office of Solid Waste & Emergency Reponse (WH-562A)
         This is to provide you with the draft Record of Decision (ROD)
         prepared by my staff for the Pijak Farm site in the State of
         New Jersey.

         The ROD document reflects Region II's recommendations for remedial
         action at the Pijak Farm site.  Our recommendations were developed
         based on the results of a remedial investigation and feasibility
         study performed by Elson T. Killam, Associates, Inc. for the New
         Jersey Department of Environmental Protection (NJDEP).

         Specifically, we agree with the recommendations presented by the
         NJDEP.  They recommend the removal of all drums and lab packs and
         the discolored soil surrounding these surface wastes as well as
         the buried waste found during the excavation of Test Pit 2.
         These hazardous wastes will be removed to a secure hazardous
         waste disposal facility.  Following this phase of the cleanup,
         further testing of soil will be performed to determine whether
         additional soil should be removed.  The NJDEP has agreed to
         monitor the groundwater by sampling the existing on-site wells,
         annually, for a five year period.

         The proposed action, I feel, is consistent with the goals and
         objectives of the Comprehensive Environmental Response, Compen-
         sation and Liability Act and the National Contingency Plan to
         provide adequate protection of public health and environment.
         Also, the recommended action has been discussed with the NJDEP,
         and they concur with the proposed remedy.

         If you have any questions regarding the attached Record of Decision,
         do not hesitate to contact me.

         Attachment
EFA Form 1320-6 (Rev. 3-76)

-------