United States        Office of
Environmental Protection   Emergency and
Agency           Remedial Response
                                       EPA/ROD/R02-91/U2
                                       March 1991
EPA   Superfund
        Record of Decision
        Genzale Plating, NY

-------
50272-101
REPORT DOCUMENTATION i. REPORT HO. 2.
PAGE EPA/ROD/R02-91/142
4. TIMindSubM*
SUPERFUND RECORD OF DECISION
^Mzale Plating, NY
^•Bst Remedial Action
7. AuRor(*)

""V.
12. Oponeoftnu OrqerinBon Mane end «i*»««e
U.S. Environmental Protection Agency
401 M Street, S.W.
Washington, D.C. 20460
3. Redctanr* Acenetan Mo.
5. Report 0*t*
03/29/91
s.
•» PeWTOnHinQ QrQWriXBflMfl HAflC No.
10. ProlectfTeak/Work Unit No.
11. ComradlC) or Gnnlper, silver, zinc,  cadmium,  nickel, and chromium compounds,  as well as acids and
    Peaners, were used  during plating processes.  Wastewaters  generated from the
   electroplating operations were discharged to four subsurface leaching pits.  Following
   a  1981 county inspection, the  owner was required to discontinue onsite contaminant
   discharge to the leaching pits.   Testing of the wastewater  samples from the pits
   indicated heavy metal  concentrations in excess of State discharge standards.  In 1982,
   36  cubic yards of contaminated material were excavated; but  the entire excavation was
   never completed.  In April 1983,  a State investigation determined that onsite
   contaminants presented a  potential public health threat because the site is in close
   proximity to public  water supply wells.  The primary contaminants of concern affecting

   (See Attached Page)
 17. Do
          ejyeto *. OMcrtplora
                                          NY
Record of Decision  - Genzale Plating,
First Remedial.Action
Contaminated Media:   soil,  gw
Key Contaminants: VOCs  (PCE,  TCE),  other organics  (PAHs),  metals (arsenic, chromium,
                  lead)
   c. COSAT1 RcWGroup
la^^^UbUty Stauciwfit
^^^
1C. Security C1*M (Th!» Report)
None
TO. Security CUM (TTil* Ptge)
None
21. No. of Pig**
76
22. Me*
(S*» ANSI-Z39.18)
                                    SM Intavcuon* on R»v»n»
                                                                            (Formerly HT1S-35)
                                                                                nt ofl Conwiwrcv

-------
EPA/ROD/R02-91/142
Genzale Plating, NY
First Remedial Action
   .tract  (Continued)
tire soil and ground water are VOCs including PCE and ICE; other organics including PAHs;
and metals including arsenic, chromium, and lead.

The-^selected interim remedial action for this site includes treating soil using in-situ
vacuum extraction and vapor phase carbon .adsorption to control emissions, followed by
excavating 1, 600 cubic yards of the treated soil and 480 cubic yards of topsoil and
material from the leaching pits, followed by offsite treatment and disposal; backfilling
the excavated areas with clean soil; pumping and treatment of ground water using
precipitation to remove metals, followed by air stripping, with reiajection onsite and
offsite disposal of treatment residuals.  The estimated present worth cost for this
remedial action is $6,358,700, which includes an annual OSM cost of $223,800.

PERFORMANCE STANDARDS OR GOALS:  Chemical-specific soil clean-up goals include TCE
1 mg/kg.  Ground water treatment will be designed to reduce the metals concentrations in
the treated ground water below the Federal and State ground water standards.

-------
                          ROD FACT SHEET
Name: Genzale Plating Company
Location/State: Franklin Square, Nassau County, New York
EPA Region: II
HRS Score  (date): 33.79  (May 1986)
NPL Rank  (date): # 789  (July 1987)

ROD

Date Signed: March 29,  1991

Selected Remedy

     Soils - In-Situ Vacuum Extraction/Surface Excavation/
             Leaching Pit Excavation/Off-Site Treatment and
             Disposal/Fill With Clean Soil

Capital Cost:  $  1,89.1,200
0 & M/Year:    $     32,700
Present Worth: $  2,449,500

 Groundwater - Pumping/Metals Precipitation/Air Stripping/
               Reinjection

Capital Cost:  $    971,500
O & M/Year:    $    191,100
Present Worth: $  3,909,200

LEAD

Remedial, EPA
Primary Contact (phone): Janet Cappelli (212-264-8679)
Secondary Contact (phone): Douglas Garbarini (212-264-0109)

WASTE

Type: inorganic (e.g. cadmium, chromium, lead, nickel) and
organic (1,1,1-trichloroethane; trichloroethylene; 1,2-
dichloroethane)
Medium: ground water and soil
Origin: Pollution originated during the operation of the
        Genzale Plating Company.  The processes used
        resulted in the generation, storage and disposal of waste
        water into four unlined leaching pits.

-------
             DECLARATION FOR THE RECORD OF DECISION
SITE NAME AND LOCATION '

Genzale Plating Company,  FranJclin Square,  Nassau County, New York

STATEMENT OF BASIS AND PURPOSE

This decision document presents the selected remedial action for
the Genzale Plating Company site, located in Nassau County, New
York, which was chosen in accordance with the Comprehensive
Environmental Response, Compensation, and Liability Act, as
amended, 42 U.S.C. § 9601, et seq.. and,  to the extent
practicable, the National Oil and Hazardous Substances Pollution
Contingency Plan, 40 C.F.R. Part 300.  The attached index
(Appendix V) identifies the items that comprise the
administrative record upon which the selection of the remedial
action is based.

The State of New York concurs with the selected remedy.

ASSESSMENT OF THE SITE

Actual or threatened releases of hazardous substances from this
site, if .not addressed by implementing the response action.
selected in this Record of Decision, may present an imminent and
substantial endangerment to public health, welfare, or the
environment.

DESCRIPTION OF SELECTED REMEDY

This operable unit represents the first of two planned for the
site.  It addresses the treatment of both groundwater in the
immediate vicinity of the property and those soils contaminated
primarily with heavy metals and volatile organics.  The selected
groundwater remedy is an interim action and does not constitute
the final action for groundwater.  The second operable unit will
involve the study and possible remediation of a plume of
groundwater contamination downgradient of the property.

The major components of the selected remedy include:

Groundwater

     A Containment of the most highly contaminated portion of
       contaminant plume;

     * Treatment, via metal precipitation and air stripping, of
       contaminated groundwater in the Upper Glacial Aquifer to
       drinking water standards prior to reinjection; and,

-------
       Disposal of treatment residuals at a RCRA Subtitle C
       facility.

       Collection of data on aquifer and contaminant response to
       remediation measures.
Soils
     A In-situ vacuum extraction for volatile organics followed
       by surface excavation over the entire property, and deeper
       excavation of leaching pit "hot spots";

     A Off-site treatment and disposal of excavated material at a
       RCRA subtitle C facility; and,

     A Backfill with clean soil.

STATUTORY DETERMINATIONS

The selected remedy is protective of human health and the
environment, complies with Federal and State requirements that
are legally applicable or relevant and appropriate to the
remedial action, and is cost-effective.  The selected remedy
utilizes permanent solutions and alternative treatment
technologies to the maximum extent practicable and satisfies the
statutory preference for remedies that employ treatment that
reduces toxicity, mobility, or volume as a principal element for
the on-site soils.

The selected groundwater remedy is an interim action and it does
not ^ constitute the final remedy for the groundwater portion of
the site.  Therefore, the statutory preference for remedies that
employ treatment that reduces toxicity, mobility, or volume as a
principal element will be addressed at the time of the final
response action.  Subsequent actions are planned to address fully
the potential threats posed by a plume of groundwater
contamination.

The need for conducting a five-year review will be evaluated upon
completion of the second operable unit.
            Sidamon-Eristoff  /           Date7    /
Regional Administrator      /                <

-------
               DECISION SUMMARY




           GENZALE PLATING COMPANY




          FRANKLIN SQUARE, NEW YORK
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY




                  REGION II




                   NEW YORK

-------
     ATTACHMENTS

     Appendix   I - Figures
     Appendix  II - Tables
     Appendix III - NYSDEC Letter of Concurrence
     Appendix  IV - Responsiveness Summary
     Appendix   V - Administrative Record Index
                        TABLE OF CONTENTS



SECTION


Site Name, Location and Description	           1

Site History and Enforcement Activities	           2

Highlights of Community Participation	           3

Scope and Role of Response Action	           4

Summary of Site Characteristics	           4

Summary of .Site Risks	           6

Description of Alternatives	           9

Summary of the Comparative Analysis
  of Alternatives	          15

The Selected Remedy... ...	 •         25

Statutory Determinations	          27

Documentation of Significant Changes	          31

-------
SITE NAME. LOCATION AND DESCRIPTION

The Genzale Plating Company site (the "Site")  includes the
property located at 288 New Hyde Park Road in the Town of
Franklin Square, Nassau County,  New York.   The Genzale Plating
Company facility ("Facility")  lies immediately adjacent to New
Hyde Park Road, Kalb Avenue, and Cathedral Road on the west,
east, and north, respectively (see Figure  1).   The properties
immediately adjacent to and surrounding the Genzale Plating
facility are primarily residential.

The Facility occupies an area of approximately 24,000 square
feet.  The western portion of the Facility property is occupied
by a two story building which houses the company office, plating
facility, and chemical storage area.  The  eastern portion of the
Facility is undeveloped and serves as an outdoor storage yard and
parking lot.  Subsurface structures located in the yard include
sanitary and industrial sewer lines, and four abandoned
wastewater leaching pits.

Census data indicate that the population density in the vicinity
of the Facility is estimated to be on the  order of 3,000 to 6,000
persons per square mile.  The properties immediately adjacent to
and surrounding the Facility are predominantly residential.
Although small businesses do exist, they are generally restricted
to New Hyde Park Road both north and south of the Facili-y.
Agricultural land use is not practiced in  the area surrounding
the Site.

Regionally, the naturally-occurring surface soils are a sandy
loam which generally promote rapid infiltration of precipitation
to the groundwater.  Site specific soils and these of the
surrounding area are, however, classified  as urban soils.
Greater surface runoff of precipitation is characteristic of
developed areas (i.e., buildings and pavement).  The ground
surface at the Facility is entirely unpaved and therefore
exposed.

Directly underlying the Site is the Upper  Glacial Aquifer, which
is designated with the federal classification II for a drinking
water source.  Although not generally used as a potable vater
s-pply, it is tapped by three Jamaica Water Supply Company wells
within 1-1.5 miles of the Site.   Most water supply wells in the
vicinity of the Site are screened within the deeper Magcthy
Aquifer.  The Magothy aquifer, underlying  the glacial sediaents,
is the thickest hydrogeological unit on Long Island.  In the
vicinity of the Site, it is estimated to be approximately 350 -
400 feet thick.  Although this aquifer is  confined in southern
Long Island, it is believed to be unconfined or under semi-
confined conditions in the vicinity of the Site.  In the Site
area, groundwater flow is in a south-southwesterly direction.

The .nearest downgradient surface water bodies to the Sita are
located approximately 3.2 miles southwest  and 3.0 miles

-------
SITE NAME. LOCATION AND DESCRIPTION

The Genzale Plating Company site (the "Site") includes the
property located at 283 New Hyde Park Road in the Town of
FranJclin Square, Nassau County, New York.  The Genzale Plating
Company facility ("Facility") lies immediately adjacent to New
Hyde Park Road, Kalb Avenue, and Cathedral Road on the west,
east, and north, respectively (see Figure 1).  The properties
immediately adjacent to and surrounding the Genzale Plating
facility are primarily residential.

The Facility occupies an area of approximately 24,000 square
feet.  The western portion of the Facility property is occupied
by a two story building which houses the company office, plating
facility, and chemical storage area.  The eastern portion of the
Facility is undeveloped and serves as an outdoor storage yaxd and
parking lot.  Subsurface structures located  in th.e yard include
sanitary and industrial sewer lines, and four abandoned
wastewater leaching pits.

Census data indicate that the population density in the vicinity
of the Facility is estimated to be on the order of 3,000 to 6,000
persons per square mile.  The properties immediately adjacent to
and surrounding the Facility are predominantly residential.
Although small businesses do exist, they are generally restricted
to New Hyde Park Road both north and south of the Facili-y.
Agricultural land use is not practiced in the area surrounding
the Site.

Regionally, the naturally-occurring surface  soils are a sandy
loam which generally promote rapid infiltration of precipitation
to the groundvater.  Site specific soils and these of the
surrounding area are, however, classified as urban soils.
Greater surface runoff of precipitation is characteristic of
developed areas (i.e., buildings and pavement).  The ground
surface at the Facility is entirely unpaved  and therefore
exposed.

Directly underlying the Site is the Upper Glacial Aquifer, which
is designated with the federal classification II for a drinking
water source.  Although not generally used as a potable vater
s-pply, it is tapped by three Jamaica Water  Supply Company wells
within 1-1.5 miles of the Site.  Most water  supply wells in the
vicinity of the Site are screened within the deeper Magcthy
Aquifer.  The Magothy aquifer, underlying the glacial sediaents,
is the thickest hydrogeological unit on Long Island.  In the
vicinity of the Site, it is estimated .to be  approximately 350 -
400 feet thick.  Although this aquifer is confined in southern
Long Island, it is believed to be unconfined .or under semi-
confined conditions in the vicinity of the Site.  In the Site
area, gro.undwater flow is in a south-southwesterly direction.

The nearest downgradient surface water bodies to the Site are
located approximately 3.2 miles southwest and 3.0 miles

-------
 southeast,  at  Valley Stream  State  Park and Hempstead Lake State
 Park,  respectively.  The  slope  of  the ground surface between the
 Site  and  these surface water bodies  is less than  1 percent.  The
 nearest wetland area is located approximately 3.0 miles to the
 southeast of the Site in  Hempstead Lake State Park.  There is no
 designated New York State significant habitat,  agricultural land,
 nor historic or landmark  site directly or potentially affected by
 conditions at  the Site.   There  are no endangered  species or
 critical  habitats within  close  proximity of the Site.

 SITE  HISTORY AND ENTORCEMENT ACTIVITIES

 The Genzale Plating Company,  Inc.  (the "Company") is an
 electroplating facility that has been in operation at this Site
 since 1915.  Over tiae, the  production activities and chemicals
 used  in the electroplating process have changed.  The earliest
 record of operations at the  Genzale  facility dates back to 1952.
 At that tine,  processing  was reported to have involved anodizing
 and cadmium, zinc, and brass plating.  In 1954  electroplating  .
 operations are on record  as  utilizing the following chemical
 .compounds:  copper, cyanide,  silver cyanide, zinc  cyanide, cadmium
 oxide, chromic acid, nickel  sulfate, sulfuric acid, nitric acid,
 and alkali cleaners.  The relative quantities of  chemicals used
 at the Site during this period  of  time are unknown.

 At present, the Company electroplates such products as automobile
_antennas  and_.component .parts;, tops and bottoms, of ball point
 pens;  and housewares such as can and bottle openers.  The
 electroplating process performed at  the Site since 1959 involved
 a number  of different steps  which  included the  use of a variety
 of chemicals.   The electroplating  process is carried out by
 dipping and advancing the materials  to be plated  through a series
 of processing  tanks or vats.  Rinsing the metal parts between
 each  processing tank generates  wastewater which is discharged to
 the municipal  sewer system for  disposal.  Previously, wastewater
 was discharged to tie subsurface leaching pits  located in the
 rear  yard area of tie Site.   It should be noted,  that wastewater
 was detected in three of  the four  leaching pits as recently as
 1981.  Distillation of spent solvent (1,1,1-trichloroethane) is
 presently in operation on the Site to condense  out clean product
 for re-use.  The sludge remaining  from the distillation process
 is stored on-site for eventual  removal.

 In April  1981,  the Kassau County Department of  Health  ("NCDH")
 conducted an inspection of the  Genzale facility.  During this
 inspection, NCDH noted that  industrial wastewater from the
 plating facility was being discharged to at least three of four
 on-site leaching pits.  NCDH representatives instructed Company
 personnel to discontinue  discharge to the leaching pits at that
 time.  In addition, wastewater  samples were obtained from the
 "leaching  pits  by NCDH and submitted  for laboratory analysis of
 inorganic compounds only.  The  results indicated  that the

-------
wastewater samples exhibited heavy metal concentrations in excess
of New York State Department of Environmental Conservation
("NYSDEC") discharge standards.

In March 1982, the Company's owners contracted Gamma TEC
Consulting Engineers to excavate potentially contaminated
materials from the leaching pits.  An estimated total of 36 cubic
yards of material was removed from three of the leaching pits at
the Facility.  Due to a lack of financial resources available to
the Company, leaching pit excavation was not completed.

Woodvard-Clyde Consultants, Inc. ("WCCI") performed a site survey.
in April 1983, under contract to the NYSDEC.  WCCI concluded that
contaminant transport from the Site presented a "relatively
low", yet potential public health threat due to the Site's
proximity to a number of public water supply wells.  The. nearest
supply well is approximately 1300 feet east of the Site.  In June
1986, the Site was added to the EPA National Priorities List of
Superfund sites.

A special notice letter was issued to the Company on December 31,
1937 by the EPA.  Based upon the Company's response it was
determined that it was financially unable to conduct the investi-
gative activities at the Site.  Accordingly, EPA proceeded with
the Remedial Investigation and Feasibility Study ("RI/FS").  A
work plan for the RI/FS was completed in October 1988, however
field work could not be initiated due to problems obtaining  • -••--- -
access.  In August 1989, EPA issued an Access Order to the
Genzale Plating Company so that field work could commence.  As a
result of the Company's failure to comply, EPA sought and was
granted a court ruling in October 1989 which enforced the terms
of the Order.  Field work for the RI/FS began in November 1989
and was completed in February 1990.

HIGHLIGHTS OF COMMUNITY PARTICIPATION

A Coimunity Relations Plan for the Site was finalized in November
1988.  This document lists contacts and interested parties
throughout government and the local community.  It also estab-
lished communication pathways to ensure timely dissemination of
pertinent information.  Subsequently, a factsheet outlining the
RI sampling program was distributed6 in November 1989 and a public
availability session was held on November 21, 1989 to answer
questions.

The RI/FS reports and the Proposed Plan for the Site were
released to the public on February 22, 1991.  These documents
were made available to the public in both the administrative
record file and the information repositories maintained at the
EPA Record Center room in Region 2 and at the Franklin Square
Library.  A press release concerning the availability of the
RI/FS reports, the Proposed Plan, and the initiation of the

-------
public comment period was issued on February 22,  1991.   A public
notice was published in a local newspaper which provided a 30-day
public comment period, ending on March 23, 1991.   In addition,  a
public meeting was held on March 13, 1991 at which
representatives froa EPA and NYSDEC answered questions  about the
problems at the Site and remedial alternatives under
consideration.  All comments which were received by EPA prior to
the end of the public comment period,  including those expressed
verbally at the public meeting, are addressed in the
Responsiveness Summary which is attached, as Appendix E, to this
Record of Decision.

This decision document presents the selected remedial action for
the Genzale Plating Company site, in FranJclin Square, New York,
chosen in accordance with the Comprehensive Environmental
Response, Compensation, and Liability Act ("CERCLA"), as amended,
and to the extent practicable, the National Contingency Plan.
The decision for this Site is based on the administrative record.

SCOPE AND ROTE OF RZSPONSE ACT

The areas of concern addressed by this response action include
soils and groundwater in the vicinity of the Facility.   These
_reas of the Site pose the principal threat to human health and
the environment because of risk from possible ingestion,
inhalation, or dermal contact with the soils and/or groundwater.
Although the_results of the.RI/FS indicate the need for an
interim groundwater remedial action, EPA was unable to delineate
the extent of the groundwater plume beyond the Facility property.
An additional investigation of the nature and extent of the plume
will be initiated under a second operable unit.  The purpose of
this interia groundvater remedy is to work toward the overall
goal of aquifer restoration,  but it does not constitute the final
action for groundwater.

The overall objective of this response action is to reduce the
concentrations of contaminants in the on-site soils to levels
which are protective of human health and the environment, to
reduce the concentrations of contaminated groundwater underlying
the Facility in order to reduce the risk associated with the
contaminants,  and to prevent further deterioration of the area
groundwater.

SUMKARY OF SITS CHARACTERISTICS

Previous investigations and the RI  (Ebasco, 1991) have shown that
there were discharges of untreated process wastewater to leaching
pits located in the rear yard area of the Site.  Media sampled
during the remedial investigation included surface soils,
subsurface soils,  and groundwater.

-------
Groundvater

Two rounds of unfiltered groundwater samples were collected from
eight monitoring veils, six installed at the Facility and two
installed downgradient of the Facility, four water supply wells,
one County monitoring veil, and one private irrigation well.  The
locations of the monitoring wells at the Facility and the
dovngradient wells are shown on Figures 2 and 3, respectively.
The wells at the Facility were installed and screened in both
shallow (30 - 40 ft below surface) and deep (60 - 70 feet below
surface) portions of the Upper Glacial Aquifer.  Groundwater
level measurements obtained from the newly installed wells
indicated that groundwater generally occurred 32-36 feet below
the surface.   Exceedingly high contaminant values were
consistently detected in shallow wells located at the Facility.
The four volatile organic compounds which were most abundant from
both a concentration and frequency of occurrence basis include:
trichloroethene (TCZ), 1,1,1-trichloroethane (TCA), 1,1-
dichloroethene (DCE), and tetrachloroethene (PCE).  TCA and TCE
were present at the greatest concentrations in the groundwater
underlying the Facility (1,100 and 500 parts per billion,
respectively).  Inorganics such as chromium, nickel, copper,
"=iiaium, manganese, and iron were also detected.  Maximum
--ncentratipn levels of primary contaminants of concern in the
groundwater can be found in Table 1.

Surface/Subsurface Soils

The soil sampling program involved the determination of lateral
and vertical extents of contamination by obtaining samples from
seven surface soil locations, six soil borings, two leaching pit
borings, and three conitoring well borings.  All soil sampling
locations are depicted on Figure 4.  Many of the contaminants
found in the soils were the same as those found in the
groundwater.  Table 2 lists the overall maximum, average, and
minimum concentrations of contaminants detected in the on-site
soils.

The surface soils were sanpled between a depth"of 0-2 feet
below grade.  Inorganic compound concentrations exceeding
regional background levels were detected at almost all surface
soil locations sampled.  Typical background concentration levels
of inorganic compounds are shown on Table 3.  Inorganic compounds
consistently detected at elevated levels include: chromium,
copper, lead, nickel, and zinc.  The highest concentration of
most, if not all, inorganic compounds at the surface were
detected at boring location SB-06.  This boring was advanced
directly through a former leaching pit.  Maximum surface
concentrations at S3-06 include chromium at 14,800 mg/kg
(background (bg)  10 - 80 ag/kg), nickel at 46,400 mg/kg (bg 4 -30
mg/kg), lead at 1,440 mg/kg (bg 3-30 mg/kg),  and copper at
11,200 mg/kg (bg 2 - 100 mg/kg).  The highest values of volatile

-------
organics in surface soils vere also detected in samples located
at SB-06.  The maximum concentration of TCE detected at 0 - 2
feet is reported at 120 ug/kg.

Inorganic compounds consistently detected at elevated values in
subsurface soils include: chromium, nickel, lead, and to a lesser
extent, copper and cadmium.  The highest concentrations of these
compounds are generally detected in subsurface soils of sampling
locations SB-06, SB-04, SB-OS, and SB-02.  In general, inorganic
compound concentrations decrease with depth from maximum values
exhibited at (0 - 2 feet) or near  (approximately 5 feet below
grade)  the surface.  The maximum chromium value detected at the
Site was 27,300 mg/kg in S3-06 at a depth of 2 - 4 feet.  High
levels of chromium, nickel, and lead were detected in locations
SB-05 and SB-02 occurring at depths of 10 and 30 feet,
respectively.  The distribution of organic contaminants and the
concentrations at vhich they occur in subsurface soil vary
greatly upon location.  Volatile organics detected most
frequently include TCZ and TCA (maximum concentrations of 53 and
7 mg/kg, respectively).

The volume of soil contaminated by organic compounds is estimated
to be 3,150 cubic yards.  The areas of organic contamination,
approximately 2500 square feet, are depicted on Figure 5.  Most
of the inorganic contamination was detected in the top 4-5 feet
oi the Site, resulting in approximately 1,600 cubic yards of
contaminated soil, with the exception of inorganic contamination
as deep as 40 feet below grade related to the former leaching
pits.  The estimated amount of this deeper inorganic
contamination is 480 cubic yards.  This amount is based upon the
leaching pits being between 12 - 18 feet in depth and 12 feet in
width and assumes that soils within roughly 2 feet of these
parameters would also require excavation.

SUWARY OF SITE RISKS

A baseline risk assessment was developed as part of the remedial
investigation for the Site.  The risk assessment evaluates the
potential impacts on human health and the environment if the
contamination at the Site is not remediated.  The assessment also
anticipates potential future uses for the Site.  This information
is used by EPA to naJce a determination as to whether remediation
of the Site is required.

Two scenarios were developed based on current (industrial) and
possible future (residential)  land use at the Facility.  Under
both scenarios, several pathways (direct contact, inhalation and
ingestion)  were evaluated for exposure to surface and subsurface
soils,  air, and grouncwater used for drinking and domestic
purposes.  The populations evaluated included nearby residents,
current and future on-site workers, future on-site development
workers, and future on-site adult and child residents.  An
exposure assessment was conducted to estimate the magnitude,
frequency,  and duration of actual and/or potential exposures to
the chemicals of potential concern via all pathways by which
humans are potentiaTly""exposed.  Exposures were based on

-------
 reasonable maximum concentrations, calculated as the 95th
 percentile upper confidence  limit of the geometric mean.  This
 reasonable maximum exposure  is defined as the highest exposure
 that is reasonably expected  to. occur at the Site for individual
 and combined pathways.

 Based on the evaluations performed during the risk assessment,
 the contaminants which are likely to pose the most significant
 risks to human health and the environment  (i.e., chemicals of
 concern) were identified for the soil and groundwater.  The
 chemicals concern in. the soil are cadmium, chromium, nickel,
 barium, lead, copper, arsenic, trichloroethene, bis  (2-ethyl-
 hexyl) phthalate, and chrysene.  The chemicals of concern in the
 groundwater are trichloroethene, 1,1,1-trichloroethane,
 1,1-dichlorcethene,  tetrachloroethene, cadmium, chromium, copper,
 lead, and nickel.  The maximum concentrations of these
 contaminants are provided in Table 1.  All levels of primary
 contaminants detected in the groundwater exceeded federal and/or
 state drinking water standards.

 Under current EPA guidelines, the likelihood of carcinogenic
 (cancer causing) and noncarcinogenic (non-cancer) effects due to
 exposure to site chemicals are considered separately.  EPA
.considers carcinogenic risk  in the range of 10"4 to  10"6 to be
 acceptable.  This risk range can be interpreted to mean that an
 individual may have  a one-in-teh-thousand to a one-in-a-million
 increased chance of  developing cancer as a result of site-related"
 exposure to a carcinogen over a 70-year lifetime under the
 specific exposure conditions at the Site.

 Potential carcinogenic risks were evaluated using the cancer
 potency factors developed by the EPA for the chemicals of
 concern.  Cancer potency factors ("CPF"s) have been developed by
 EPA's Carcinogenic Risk Assessment Verification Endeavor for
 estimating excess lifetime cancer risks associated with exposure
 to potentially carcinogenic  chemicals.  CPFs, which are expressed
 in units of (mg/kg-day) "1, are multiplied by the estimated  intake
 of a potential carcinogen, in mg/kg-day, to generate an upper-
 bound estimate of the excess lifetime cancer risk associated with
 exposure to the compound at  the intake level.  The term "upper
 tcur.d" reflects the  conservative estimate of the risks calculated
 from the CPF.  Use of this approach makes the underestimation of
 the risk highly unlikely.  CPFs for chemicals of potential
 concern can be found on Table 4.

 EPA's baseline risk  assessment indicates that the most
 significant public health risk results from the ingestion of
 groundwater, inhalation of groundwater volatiles (i.e., while
 showering), and direct contact and ingestion of soils.  Table 5
 summarizes the baseline risk assessment results.  Under the
 future-use scenario, ingestion of groundwater in the vicinity of
 the Facility by off-Facility adult residents would present an

-------
excess cancer risk of 2.56 x 10"3; ingestion of groundwater by
on-Facility adult residents would present an excess cancer risk
of 2.55 x 10'3 and for on-Facility child residents an excess
cancer risk of 1.7 x 10"3.  This indicates that future off-
Facility and on-Facility adults have approximately a three-in-
one-thousand additional chance of developing cancer, and on-
Facility children have a two-in-one-thousand additional chance of
developing cancer, as a result of drinking this groundwater.
Under the future-use scenario for on-Facility development
workers, inhalation of the Site soils during construction
activity would present an excess cancer risk of 9.96 x 10"4.
This indicates that an on-Facility worker involved in
construction and excavation activities would have approximately a
one-in-one-thousand additional chance of developing cancer.

The non-cancer risk associated with different pathways was
assessed using a hazard index ("HI") approach, based on
comparison of expected contaminant intakes and safe levels of
intake  (reference doses).  Reference doses (RfDs) have been
developed by EPA for indicating the potential for adverse health
effects.  The chronic and subchronic RfDs for chemicals of
potential concern can be found on Table 4.  RfDs, which are
expressed in units of milligram per kilogram per day (mg/kg-day),
are estimates of daily exposure levels for humans which are
thought to be safe over a lifetime (including sensitive
individuals).  Estimated intakes of chemicals from environmental
media (e.g., the amount of a chemical ingested from contaminated
soil), are .compared with the RfD to derive the hazard quotient for
the contaminant in the particular aedia.  The Hi is obtained by
adding the hazard quotients for all compounds across all media.
An HI value greater than 1.0 is considered to pose an
unacceptable non-cancer risk.  Under the current-use worker
scenario, inhalation and ingestion of Site soils contributes to
an HI of 2.2.  Under the future-use scenario, ingestion of
groundwater for off-Facility adult residents presents an HI value
of 86.2; ingestion of groundwater for on-Facility adult residents
presents and HI value of 86.2 and for on-Facility child residents
an HI of 114; ingestion and dermal contact with soils for on-
Facility adult residents contributes to an HI value of 2.56 and
for on-Facility child residents an HI of 15.4; ingestion and
dermal contact with Site soils by future on-Facility workers
presents and HI of 2.2 and for future Site development workers an
HI of 23.9.  For soil pathways, the chemicals of concern which
contribute the most to the HI values are chromium and nickel.
For groundwater pathways, the largest chemical contributors are
antimony, chromium,  and nickel.

The risk assessment contains the conclusion that inhalation of
Site soils by current off-Facility residents does not present a
non-cancer risk nor an excess cancer risk.

-------
 In summary,  it is evident that the contaminants in soils at the
 Facility and underlying grbuhdwater warrant remediation in order
 to prevent the continued degradation of groundwater quality in
 the area and to reduce their associated risks.

 Uncertainties

 The procedures used to assess potential human health risks in
 this evaluation are subject to wide uncertainties.  In general,
 the main sources of uncertainty in this assessment include:

     * environmental chemistry sampling and analysis;

     A exposure models and assumptions; and

     A- toxicological models and parameters.

 Uncertainty  in environmental sampling arises in part from the
 potentially  uneven distribution of chemicals in the media
 sampled.  Consequently, there is significant uncertainty as to
 the actual levels present.  Environmental chemistry analysis
 error can stem from several sources including the errors inherent
 in the analytical methods and characteristics of the matrix being
 sampled.  Uncertainties in the exposure assessment are related to
 estimates of how often an individual would actually come into
 contact with the chemicals of concern, the period of time over
 which such exposure would occur, and in the models used to
.estimate the concentrations of the chemical so concern at the
 point of exposure.  Uncertainties in toxicological data occur in
 extrapolating both from animals to humans and from high to low
 doses of exposure, as well as from the difficulties in assessing
 the toxicity of a mixture of chemicals.  These uncertainties are
 addressed by making very conservative assumptions concerning risk
 and exposure parameters throughout the assessment.  As a result,
 the risk assessment provides upper bound estimates of the risks
 to populations near the Site, and is highly unlikely to
 underestimate actual risks related to the Site.

 Actual or threatened releases of hazardous substances from this
 Site, if not addressed by the preferred alternative or one of the
 other active measures considered, may present a current or
 potential threat to the environment through the groundwater
 pathway.

 DESCRIPTION  OF ALTERNATIVES

 Following a  screening of remedial technologies in accordance with
 the NCP, five remedial alternatives were developed for
 contaminated groundwater and six for contaminated soil.  The
 alternatives were further screened based on technical
 considerations such as effectiveness, implementability, and cost.
 The present  worth costs listed below for all soil and groundwater

-------
alternatives are based on a 30-year period and a 5% discount
rate.

Remedial Alternatives for Contaminated Soils (SC)

     A SC-1: No-Action

     A SC-2: Surface Excavation/Off-Site Treatment and
       Disposal/Capping

     A SC-3: In-Situ Vacuum Extraction/In-Situ Stabilization
       (Solidification)/Soil Cover

     A SC-4: In-Situ Vacuum Extraction/Excavation/Off-Site
       Treatment and Disposal/Fill with Clean Off-Site Soil

     A SC-5: In-Situ Vacuum Extraction/Surface Excavation/
       Excavation of Leaching Pits/Off-Site Treatment and
       Disposal/Fill with Clean Off-Site Soil

Alternative SC-1; No-Action

Capital Cost: $ 65,600
Annual Operation & Maintenance (0 & M) Cost: $34,400
Present Worth Cost: $650,000
Time to Implement: 6 months

CERCLA requires that the No-Action alternative be considered as a
baseline:"-:for-compar-isorv "with other-soil alternatives.  Under this
alternative, the contaminated soil would be left in place without
treatment.  A long-term monitoring program would be implemented
to- track the migration of contaminants from the soil into the
groundwater utilizing existing monitoring well clusters as well
as a total of 10 newly installed cluster wells.  This alternative
also includes the development and maintenance of a public
awareness and education program for the residents and workers in
the area surrounding the Facility.  Since this alternative would
involve no contaminant removal, CERCLA requires that a Site
subject to such a selected remedy be reviewed every five years.
If justified by the review, remedial actions may be implemented ,
to remove or treat the wastes.

Alternative SC-2; Surface Excavation/Off-Site Treatment and
                  Disposal/Capping

Capital cost: $1,257,100
0 & M Cost: $32,700
Present Worth: $1,815,400
Time to Implement: 30 months

This alternative would involve the removal of the top 4-5 feet
of contaminated soil from approximately 10,280 ft2  of the  open

                             .   1Q

-------
area (entire open area is 16,000 ft2)  of the Site.   The  total
volume of excavated material is estimated to be 1,600 cubic
yards.   The excavated soil would be transported to an off-site
permitted Resource Conservation and Recovery Act (RCRA)  facility
for treatment and disposal.  For purposes of estimating cost for
this alternative, as well as Alternatives SC-4 and SC-5, it is
assumed that these soils would be treated via stabilization/
solidification.  Off-site transport would comply with all federal
and state transportation requirements.  The excavated area would
be filled with clean soil.  The entire open area (16,000 ft2)
would then be graded and capped with a 6-inch asphalt cap, to
prevent leaching of subsurface contaminants into the ground-
water through infiltration.  Since this alternative would result
in contamination remaining on-site, five year reviews and long-
term monitoring would be required.

Alternative SC-3; In-Situ Vacuum Extraction/In-Situ Stabilization
                  fSolidification)/Soil Cover

Capital Cost: $1,965,600
O 4 M Cost: $27,200
Present Worth: $2,439,300
Time to Implement: 36 months

Under this alternative, the contaminated soil would be left in
place,  undisturbed; no excavation would be required.  An in-situ
vacuum extraction process would be employed over portions of the
volatile organic contaminated area (2,500 ft2)  to remove the_
contaminants, mainly TCE, from the soil to 1 mg/kg.  This process
would involve the installation of approximately 5 vacuum
extraction wells, each with a maximum depth of 30 feet.   The
vacuum wells would be connected via a piping system*to a skid-
mounted, high volume vacuum pump.  The vacuum pump would pull air
through the contaminated soils, within a radius of 20 feet from
the wells, depending on soil composition and volatility of the
contaminants.  The air containing the stripped volatile organics
would be fed through a condenser to remove moisture and then
through an emissions control system,  i.e., a vapor phase carbon
adsorption system to remove volatilized organics.

While in-situ vacuum extraction is being applied to applicable
portions of the Site, an in-situ stabilization process would
begin in another portion of the Site and continue until the
entire inorganic contamination has been immobilized.  The
approximate area of inorganic contamination varies from 10,280
ft2  at  the surface to 8,850 ft2 at. a 34-ft depth.  The process
would incorporate mechanical mixing and injection of reagents to
immobilize both organic and inorganic contaminants.  The
stabilizing additives polymerize with the soils producing a
cement-like mass.  For each type of contaminated soil, the
additives used varies and would have to be optimized.  An on-site
batch mixing tank supplies the proprietary chemical additives.

                                11

-------
Once both processes are complete,  a 6-inch cover of clean soil
would then be placed over the entire yard area (16,000 ft2).
Since this alternative would result in contamination remaining
on-site, five year reviews and long-term monitoring would be
required.

Alternative SC-4:  In-Situ Vacuum Extraction/Excavation/Off-Site
                  Treatment and Disposal/Fill with Clean Off-
                  Site Soil

Capital Cost: $8,974,600
0 & M Cost: none
Present Worth: $8,974,600
Time to Implement: 42 months

This alternative is identical to Alternative SC-3 except that the
contaminated soil  in areas ranging rora 10,280 ft2 at the  surface
to 8,850 ft2  at  a  34-ft  depth  of the  contaminated yard area  of
the Site would be  excavated and transported off-site for treat-
ment and disposal.  In-situ vacuum extraction would be conducted
first in order to  prevent exposure of workers and residents to
volatile organics  and to reduce organic contaminant levels such
that only inorganics would require treatment off-site prior to
disposal.  Approximately 11',700 cubic yards of contaminated soil
would be transported to an off-site RCRA permitted treatment and
disposal facility.  This total excavation amount is based on the
assumption that all elevated levels of contaminants scattered
throughout the Site would need to be excavated .  The excavated
area would, be filled, with, clean soil, compacted, and graded.

Alternative SC-5;  In-Situ Vacuum Extraction/Surface Excavation/
                  Excavation of Leaching Pits/Off-Site Treatment
                  and Disposal/Fill with Clean Off-Site Soil

Capital Cost: $1,777,410
0 & H Cost: none
Present Worth: $1,777,410
Time to Implement: 36 months

This alternative is the same as Alternative SC-4 except that the
amount of soil to  be excavated would be different.  After the in-
situ vacuum extraction is conducted,  the top 4-5 feet of the
contaminated yard  area of the Site would be exca%'at~d, resulting
in approximately 1,600 cubic yards of material to be transported
for off-site treatment and disposal.   During the course of the
initial excavation when the leaching pits or "hot spots" can be
further delineated through additional borings and sampling,  the
excavation would continue until all contaminated soils were
removed.  The estimated amount of soil that would be excavated
from the leaching  pits is 480 cubic yards.  This amount is based
upon the leaching  pits being between 12 - 18 feet in depth and 12
feet wide and assumes that soils within 2 feet of these

                               12

-------
parameters would also need to be excavated.  The excavated areas
would be backfilled with clean soil and the entire open area
(16,000 ft2)  would then be graded.

Remedial Alternatives for Contaminated Groundwater (GW)

     A GW-l:  No-Action

     A GW-2:  Limited Action

     A GW-3:  Pumping/Metals Precipitation/Air Stripping/
              Reinjection

     * GW-4:  Pumping/Metals Precipitation/Carbon Adsorption/
              Reinjection

     * GW-5:  Pumping/Metals Precipitation/UV-Chemical Oxidation/
              Reinjection

     * GVT-7:  Pumping/Pretreatment/Discharge to Local Publically
              Owned Treatment Works (POTW)

Alternative GW-l: No-Action

Capital Cost: $65,500
0 & M Cost: $26,900
Present Worth: $534,600
Time to Implement: 6 months

The No-Action alternative would only include a long-term
monitoring program to sample the migration of contaminants of .
concern in the aquifer.  The contaminants in the groundwater
would be left to attenuate without any treatment.  A total of
twelve monitoring wells, including existing upgradient, Facility,
and downgradient wells would be utilized in order to sample the
groundwater from the shallow and deeper portions of the aquifer
and to track contaminant migration.  Regular five-year reviews
would be performed to assess the need for additional remedial
actions.

Alternative GW-2: Limited Action

Capital Cost:  $99,300
0 & M Cost:  $29,700
Present Worth:  $611,500
Time to Implement: 36 months

This alternative would include a long-term monitoring program, as
described in Alternative GW-l, and also an institutional control
program to restrict the use of the aquifer.  The contaminants in
the groundwater would be left to attenuate without any treatment.
Institutional controls, such as well permit restrictions, would
be implemented to limit the use of the aquifer downgradient of

                               11

-------
 the Facility for both potable and municipal  purposes.   As with
 Alternative GW-l,  regular five year reviews  would be  necessary to
 assess the need for further response actions.

 Alternative GW-3;  Pumping/Metals Precipitation/Air Stripping/
                   Reinfection                       •        '  .

 Capitol Cost:   $971,500
 0 & M Cost:  $191,100
 Present Worth:   $3,909,200
 Time to Implement: 36 Months

 The major features of this alternative would include  groundwater
 collection, treatment, and reinjection of the treated groundwater
 and a performance monitoring program.

 The collection  system would consist of one extraction well  to  be
 installed at the southwestern corner of the  Facility  into the
 Upper Glacial Aquifer to a depth of approximately 70  feet  in
 order to extract 28,800 gallons per day (gpd)  of groundwater from
 the Site contaminant plume.  The groundwater would then be  piped
 to an on-site treatment facility consisting  of two major
•process: treatment to remove metals by chemical precipitation,
 flocculation, clarification and filtration;  and,  air  stripping
 followed by carbon .adsorption to remove volatile organic
 contaminants.   The treatment system would be designed to
 effectively reduce the metal concentrations  in the treated
 groundwater below the federal and New York State groundwater
 standards.-  Any sludge generated during the  metal removal process
 would be disposed of in a RCRA Subtitle C landfill.   The spent
 carbon would be transported off-site for disposal or  regeneration
-and reuse.  The treated groundwater would then be reinjected into
 the aquifer through a reinjecticn well.   The siting of the
 extraction and  reinjection wells would be completed during  the
 design phase based on technical criteria.

 Alternative GW-4;  Pumping/Metals Precipitation/Carbon Adsorption/
                   Reinjeciton

 Capital Cost:   $1,062,900
 0 & M Cost:  $201,600
 Present Worth:   $4,162,000
 Time to Implement:  36 Months

 The major features of this alternative would be the same as that
 of Alternative  GW-3.  The unit processes used in this alternative
 are similar to  those of Alternative GW-3 with the exception that
 the unit operation for organic removal would be achieved by a
 liquid phase carbon adsorption'system rather than the air
 stripping system.
                                14

-------
Alternative GW-5; Pumping/Metals Precipitation/UV-Chemical
                  Oxidation/Reiniection

Capital Cost: $1,011,200
0 & M Cost: $274,100
Present Worth: $5,224,800
Time to Implement: 36 months

The major features of this alternative would be the same as that
of Alternative GW-3.  The unit processes used in this alternative
are similar to those of Alternative GW-3 with the exception that
the unit operation for organic removal would be achieved by a UV-
chemical oxidation system rather than the air stripping system  .
used in Alternative GW-3 or the liquid phase carbon adsorption
system used in Alternative GW-4.  With a UV-chemical oxidation
system, the groundwater would be mixed with a 50% hydrogen
peroxide solution and then pumped to a 20 gpm UV-chemical
oxidation reactor.  The organic contaminants are converted to
carbon dioxide (C02) ,  water,  and chlorides.

Alternative GW-7; Puinpina/Pretreatrent/Discharge to Local POTW

Capital Cost:  $760,100
0 & M Cost:  $180,700
Present Worth:  $3,537,900
Time to Implement:  42 months

The major features of this alternative would include groundwater
collection, pretreatment, "and discharge of the treated
grcundwater into the sewer line adjacent to the Site on Kalb
Avenue which leads to the Bay Park Sewage Treatment Plant located
10 miles south of the Site.  The unit process used in this
alternative for the removal of heavy metals would be the same as
that used in Alternative GW-3.  The organic removal in this case
is achieved by the activated sludge system (secondary wastewater
treatment system) at the Bay Park Sewage Treatment Plant.

SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES

All remedial alternatives were evaluated in detail utilizing nine
criteria as set forth in the OSWER Directive 9355.3-01. " These
criteria were developed to address the requirements of Section
121 of CERCLA to ensure all important considerations are factored
into remedy selection decisions.

The following "threshold" criteria are the most important'and
must be satisfied by any alternative in order to be eligible for
selection:

-------
Threshold Criteria  A overall protection of human health and the
                      environment; and
                    A Compliance with applicable or relevant and
                      appropriate requirements to the extent
                      practicable.

The following "primary balancing" criteria are used to make
comparisons and to identify the major trade-offs between
alternatives:

Primary Balancing   A Long-term effectiveness and permanence;
   Criteria         A Reduction in toxicity, mobility, or volume
                      through treatment;
                    A Short-term effectiveness;
                    A Implementability; and
                    A Cost.

The following "modifying" criteria is considered fully after the
formal public comment period on the Proposed Plan is complete:

Modifying Criteria  A state/support agency acceptance; and
                    * Community acceptance.

The nine criteria are summarized below:

1. Overall Protection of Human Health and the Environment

This criterion addresses whether or not a remedy provides
adequate protection and describes how risks are eliminated,
reduced or controlled through treatment, engineering controls, or
institutional controls.

Protection of human health is the central mandate of CERCLA.
Protection is achieved primarily by taking appropriate action to
ensure -that there will be no unacceptable risks to human health
or the environment through any exposure pathways.

2. Compliance with ARARs

This criterion addresses whether or not a remedy will meet all
applicable or relevant and appropriate requirements (ARARS1)
and/ or provide grounds for invoking waiver.  ARARS can be
chemical-specific, location-specific, or action-specific.

3. Long-term Effectiveness and Permanence

This criterion refers to the ability of a remedy to maintain
reliable protection of human health and the environment over
time,  once clean-up levels have been met.  It also addresses the
magnitude and effectiveness of the measures that may be required
to manage the risk posed by treatment residuals and/or untreated
wastes.

-------
4. Reduction of Toxicity.  Mobility,  or Volume

This evaluation criterion relates to the anticipated performance
of a remedial technology,  with respect of these parameters,  that
a remedy may employ.

5. Short-term Effectiveness

This criterion involves the period of time each alternative needs
to achieve protection and any adverse impacts on human health and
the environment that may be posed during construction and
implementation of the alternative.

6. Impleaentability

This criterion involves the technical and administrative
feasibility of a remedy, including the availability of materials
and services needed to implement the chosen solution.

7. Cost

This criterion includes both estimated capital and operation and
maintenance (O&M) costs.  The present worth costs are based on a
30-year period and a 5% discount rate.

8. State/Support Agency Acceptance

This criterion assesses the technical and administrative issues
and concerns the state may have regarding each of the
alternatives.  The factors to be evaluated includes features of
the alternatives that the state supports, opposes, and any
reservations the state may identify.

9. Community Acceptance

This criterion provides an assessment of any public concerns
regarding any of the alternatives.  Factors of community
acceptance to be discussed include support, reservation, and
opposition by the community.

Analysis

The.discussion which follows provides a sussary of the relative
performance of each soil and groundwater alternative with respect
to the nine criteria.

SOIL ALTERNATIVES

A Overall Protection of Human Health and the Environment

Alternative SC-1 does not meet the remedial objectives, thus it
would not be protective of human health and the environment due

                                II

-------
to the continued migration of volatile organics and inorganics
into the groundwater.  Alternatives SC-2, SC-3, SC-4, and SC-5
would meet the remedial objective of protecting the groundwater
from the source.  However, Alternatives SC-3 through SC-5 would
provide a more permanent solution to the problem since the
protectiveness of Alternative SC-2 relies on the effectiveness of
the asphalt cap.  Alternative SC-2 would not meet -the cleanup
levels for prevention of cross-media impacts on the groundwater
since only surface soil would be removed.  Alternatives SC-3,
SC-4, and SC-5 have the potential to meet the cleanup level for
volatile organics.  Alternative SC-3 can effectively immobilize
the remaining contaminants.  Alternative SC-5 would meet all
cleanup levels once the leaching pits or "hot spots" of
contaminated are further delineated.  Alternative SC-4 can meet
all the cleanup levels in the unsaturated soil since all of the
contaminated soil would be remove from the Site.  Alternatives
SC-2, SC-3, SC-4 and SC-5 would protect nearby residents and
workers by eliminating inhalation and direct contact pathways.

A Compliance with ARARS

All technologies proposed for use in Alternatives SC-2, SC-3,
SC-4, and SC-5 would ne designed and implemented to satisfy all
ARARs.  However, Alternative SC-2 could result in cross-media
contamination impacts on the groundwater through leaching of
contaminants.  Federal and state regulations dealing with the
handling and transportation of hazardous wastes to an off-site
treatment facility would be followed.  Contaminated soil, debris,
and sediments from the-Site would be treated using specific
technologies or specific treatment levels, as appropriate, to
comply with RCRA Land Disposal Restrictions (LDRs).  The
residuals from the treatment processes (i.e., spent carbon) would
also be treated and disposed of to comply with LDRs.  This
alternative will comply with LDRs through a treatability variance
for the contaminated soil, debris, sediments, and residuals.
(More detail can be found under the "Statutory Determinations"
section).

* Long-term Effectiveness

Alternative SC-1 would only monitor the migration of the
contaminants and would not provide treatment or containment.
Therefore,  it would not provide effective or permanent long-term
protection of groundwater or human exposure to soils at the Site.

Alternatives SC-2, SC-3,  SC-4, and SC-5 would mitigate the
significant risks by partial or total removal and/or
immobilization of Site contaminants.  Alternatives SC-4 and SC-5
would provide the highest degree of effectiveness since all
identified contaminated soils would be treated as well as removed
from the Site.  Alternatives SC-3 can effectively remove TCE from
the soil through in-situ vacuum extraction and can effectively

                                18

-------
southeast, at Valley Stream State Park and Hempstead Lake State
Park, respectively.  The slope of the ground surface between the
Site and these surface vater bodies is less than 1 percent.  The
nearest wetland area is located approximately 3.0 miles to the
southeast of the Site in Hempstead Lake State Park.  There is no
designated New York State significant habitat, agricultural land,
nor historic or landmark site directly or potentially affected by
conditions at the Site.  There are no endangered species or
critical habitats within close proximity of the Site.

SITE HISTORY AND ENFORCEMENT ACTIVITIES

The Genzale Plating Company, Inc. (the "Company") is an
electroplating facility that has been in operation at this Site
since 1915.  Over time, the production activities and chemicals
used in the electroplating process have changed.  The earliest
record of operations at the Genzale facility dates back to 1952.
At that tine, processing was reported to have involved anodizing
and cadmium, zinc, and brass plating.  In 1954 electroplating
operations are on record as utilizing the following chemical
compounds: copper, cyanide, silver cyanide, zinc cyanide, cadmium
oxide, chromic acid, nickel sulfate, sulfuric acid, nitric acid,
and alkali cleaners.  The relative quantities of chemicals used
at the Site during this period of time are unknown.

At present, the Company electroplates such products as automobile
antennas and component parts; tops and bottoms of ball point
pens; and housewares such as can and bottle openers.  The
electroplating process performed at the Site since 1959 involved
a number of different steps which included the use of a variety
of chemicals.  The electroplating process is carried out by
dipping and advancing the materials to be plated through a series
of processing tanks or vats.  Rinsing the metal parts, between
each processing tank generates wastewater which is discharged to
the municipal sewer system for disposal.  Previously, wastewater
was discharged to the subsurface leaching pits located in the
rear yard area of the Site.  It should be noted, that wastewater
was detected in three of the four leaching pits as recently as
1981.  Distillation of spent solvent (1,1,1-trichloroethane) is
presently in operation on the Site to condense out clean product
for re-use.  The sludge remaining from the distillation process
is stored on-site for eventual removal.

In April 1981, the Nassau County Department of Health ("NCDH11)
conducted an inspection of the Genzale facility.  During this
inspection, NCDH noted that industrial wastewater from the
plating facility was being discharged to at least three of four
on-site leaching pits.  NCDH representatives instructed Company
personnel to discontinue discharge to the leaching pits at that
time.  In addition, wastewater samples were obtained from the
"leaching pits by NCDH and submitted for laboratory analysis of
inorganic compounds only.  The results indicated that the

-------
wastewater samples exhibited heavy metal concentrations in excess
of New York State Department of Environmental Conservation
("NYSDEC") discharge standards.

In March 1982, the Company's owners contracted Gamma TEC
Consulting Engineers to excavate potentially contaminated
materials from the leaching pits.  An estimated total of 36 cubic
yards of material was removed from three of the leaching pits at
the Facility.  Due to a lack of financial resources available to
the Company/ leaching pit excavation was not completed.

Woodvard-Clyde Consultants, Inc. ("WCCI") performed a site survey
in April 1983, under contract to the NYSDEC.  WCCI concluded that
contaminant transport from the Site presented a "relatively
low", yet potential public health threat du6 to the Site's
proximity to a number of public water supply wells.  The. nearest
supply well is approxinately 1300 feet east of the Site.  In June
1986, the Site was added to the EPA National Priorities List of
Superfund sites.

A special notice letter was issued to the Company on December 31,
1987 by the EPA.  Based upon the Company's response it was
determined that it was financially unable to conduct the investi-
gative activities at the Site.  Accordingly, EPA proceeded with
the Remedial Investigation and Feasibility Study ("RI/FS").  A
work plan for the RI/FS was completed in October 1988, however
field work could not be initiated due to problems obtaining
access.  In August 1989, EPA issued an Access Order to the
Genzale Plating Company so that field work could commence.  As a
result of the Company's failure to comply, EPA sought and was
granted a court ruling in October 1989 which enforced the terms
of the Order.  Field work for the RI/FS began in November 1989
and was completed in February 1990.

HIC-HXIGHTS OF COMMUNITY PARTICIPATION

A Community Relations Plan for the Site was finalized in November
1988.  This document lists contacts and interested parties
throughout government and the local community.  It also estab-
lished communication pathways to ensure timely dissemination of
pertinent information.  Subsfeguently, a factsheet outlining the
RI sampling program was distributed in November 1989 and a public
availability session was held on November 21, 1989 to answer
questions.

The RI/FS reports and the Proposed Plan for the Site were
released to the public on February 22, 1991.  These documents
were made available to the public in both the administrative
record file and the information repositories maintained at the
EPA Record Center room in Region 2 and at the Franklin Square
Library.  A press release concerning the availability of the
RI/FS reports, the Proposed Plan, and the initiation of the

-------
 public  comment  period was  issued on February 22, 1991.  A public
 notice  was  published in  a  local newspaper which provided a 30-day
 public  comment  period, ending on March 23, 1991.  In addition, a
 public  meeting  was held  on March 13, 1991 at which
 representatives froa EPA and NYSDEC answered questions about the
 problems  at the Site and remedial alternatives under
 consideration.   All comments which were received by EPA prior to
 the end of  the  public comment period, including those expressed
 verbally  at the public meeting, are addressed in the
 Responsiveness  Summary which is attached, as Appendix E, to this
 Record  of Decision.

 This decision document presents the selected remedial action for
 the Genzale Plating Company site, in Franklin Square, New York,
 chosen  in accordance with  the Comprehensive Environmental
 Response, Compensation,  and Liability Act ("CERCLA"), as amended,
 and to  the  extent practicable, the National Contingency Plan.
 The decision for this Site is based on the administrative record.

 SCOPE AND ROT"?  OF RZSPONSE ACTION

 The areas of concern addressed by this response action include
 soils and groundwater in the vicinity of the Facility.  These
 _reas of  the Site pose the principal threat to human health and
 the environment because  of risk from possible ingestion,
 inhalation,  or  dermal contact with the soils and/or groundwater.
 Although  the results of  the RI/FS indicate the need for an
 interim groundwater remedial action, EPA was unable to delineate
 the extent  of the groundwater plume beyond the Facility property.
 An additional investigation of the nature and extent of the plume
 will be initiated under  a  second operable unit.  The purpose of
 this interim groundvater remedy is to work toward the overall
 goal of aquifer restoration, but it does not constitute the final
 action  for  groundwater.

 The overall objective of this response action is to reduce the
 concentrations  of contaminants in the on-site soils to levels
 which are protective of  human health and the environment, to
 reduce  the  concentrations  of contaminated groundwater underlying
 the Facility in order to reduce the risk associated with the
 contaminants, and to prevent further deterioration of the area
.groundwater.

 SUKJ-tARY OF  SITS CHARACTERISTICS

 Previous  investigations  and the RI (Ebasco, 1991) have shown that
 there were  discharges of untreated process wastewater to leaching
 pits located in the rear yard area of the Site.  Media sampled
 during  the  remedial Investigation included surface soils,
 subsurface  soils, and groundwater.

-------
Groundvater

Two rounds of unfiltered groundwater samples were collected from
eight monitoring wells, six installed at the Facility and two
installed downgradient of the Facility, four water supply wells,
one County monitoring veil, and one private irrigation well.  The
locations of the monitoring wells at the Facility and the
dovngradient wells are shown on Figures 2 and 3, respectively.
The wells at the Facility were installed and screened in both
shallow (30 - 40 ft below surface)- and deep (60 - 70 feet-below
surface) portions of the Upper Glacial Aquifer.  Groundwater
level measurements obtained from the newly installed wells
indicated that groundvater generally occurred 32 - 36 feet below
the surface.   Exceedingly high contaminant values were
consistently detected in shallow wells located at the Facility.
The four volatile organic compounds which were most abundant from
both a concentration and frequency of occurrence basis include:
trichloroethene (TCE), 1,1,1-trichloroethane (TCA), 1,1-
dichloroethene (DCE), and tetrachloroethene (PCE).  TCA and TCE
were present at the greatest concentrations in the groundwater
underlying the Facility  (1,100 and 500 parts per billion,
respectively).  Inorganics such as chromium, nickel, copper,
~ = iiaium, manganese, and iron were also detected.  Maximum
--ncentration levels of primary contaminants of concern in the
groundwater can be found in Table 1.

Surface/Subsurface Soils   .-      :.-               ;     -   •  -  	

The soil sampling program involved the determination of lateral
and vertical extents of contamination by obtaining samples from
seven surface soil locations, six soil borings, two leaching pit
borings, and three conitoring well borings.  All soil sampling
locations are depicted on Figure 4.  Many of the contaminants
found in the soils were the same as those found in the
groundwater.  Table 2 lists the overall maximum, average, and
minimum concentrations of contaminants detected in the on-site
soils.

The surface soils were sampled between a depth"of 0-2 feet
below grade.  Inorganic compound concentrations exceeding
regional background levels vere detected at almost all surface
soil locations sampled.  Typical background concentration levels
of inorganic compounds are shown on Table 3.  Inorganic compounds
consistently detected at elevated levels include: chromium,
copper, lead, nickel, and zinc.  The highest concentration of
most, if not all,  inorganic compounds at the surface were
detected at boring location SB-06.  This boring was advanced
directly through a former, leaching pit.  Maximum surface
concentrations at S3-06 include chromium at 14,800 mg/kg
(background (bg)  10 - 80 sg/kg), nickel at 46,400 mg/kg (bg 4 -30
mg/kg), lead at 1,440 mg/kg (bg 3 - 30 mg/kg),  and copper at
11,200 mg/kg (bg 2 - 100 mg/kg).  The highest values of volatile

-------
organics  in surface soils were also detected in samples located
at SB-06.  The maxiaun concentration of TCE detected at 0 - 2
feet is reported at 120 ug/kg.

Inorganic compounds consistently detected at elevated values in
subsurface soils include: chromium, nickel, lead, and to a lesser
extent, copper and cadmium.  The highest concentrations of these
compounds are generally detected in subsurface soils of sampling
locations SB-06, SB-04, SB-OS, and SB-02.  In general, inorganic
compound  concentrations decrease with depth from maximum values
exhibited at  (0 - 2 feet) or near  (approximately 5 feet below
grade) the surface.  The maximum chromium value detected at the
Site was  27,300 mg/kg in SB-06 at a depth of 2 - 4 feet.  High
levels of chromium, nickel, and lead were detected in locations
SB-05 and SB-02 occurring at depths of 10 and 30 feet,
respectively.  The distribution of organic contaminants and the
concentrations at which they occur in subsurface soil vary
greatly upon location.  Volatile organics detected most
frequently include TCZ and TCA (maximum concentrations of 53 and
7 mg/kg,  respectively).

The volume of soil contaminated by organic compounds is estimated
to be 3,150 cubic yards.  The areas of organic contamination,
approximately 2500 square feet, are depicted on Figure 5.  Most
of the inorganic contamination was detected in the top 4-5 feet
or the Site, resulting in approximately 1,600 cubic yards of
contaminated soil, with the exception of inorganic contamination
as deep as 40 feet below grade related to the former leaching
pits.  The estimated amount of this deeper inorganic
contamination is 480 cubic yards.  This amount is based upon the
leaching  pits being between 12 - 18 feet in depth and 12 feet in
width and assumes that soils within roughly 2 feet of these
parameters would also require excavation.

SUMMARY OF SITE RISKS '

A baseline risk assessment was developed as part of the remedial
investigation for the Site.  The risk assessment evaluates the
potential impacts on human health and the environment if the
contamination at the Site is not remediated.  The assessment also
anticipates potential future uses for the Site.  This information
is used by EPA to nake a determination as to whether remediation
of the Site is required.

Two scenarios were developed based on current (industrial) and
possible  future (residential) land use at the Facility.  Under
both scenarios, several pathways (direct contact, inhalation and
ingestion) were evaluated for exposure to surface and subsurface
soils, air, and groundvater used for drinking and domestic
.purposes.  The populations evaluated included nearby residents,
current and future on-site workers, future on-site development
workers,  and future on-site adult and child residents.  An
exposure  assessment was conducted to estimate the magnitude,
frequency, and duration of actual and/or potential exposures to
the chemicals of potential concern via all pathways by which
humans are potentially exposed.  Exposures were based on

-------
reasonable maximum concentrations, calculated as the 95th
percentile upper confidence limit of the geometric mean.  This
reasonable maximum exposure is defined as the highest exposure
that is reasonably expected to occur at the Site for individual
and combined pathways.

Based on the evaluations performed during the risk assessment,
the contaainants which are likely to pose the most significant
risks to human health and the environment (i.e., chemicals of
concern) were identified for the soil and groundwater.  The
chemicals concern in the soil are cadmium, chromium, nickel,
barium, lead, copper, arsenic, trichloroethene, bis (2-ethyl-
hexyl) phthalate, and chrysene.  The chemicals of concern in the
groundwater are trichloroethene, 1,1,1-trichloroethane,
1,1-dichlorcethene,  tetrachloroethene, cadmium, chromium, copper,
lead, and nickel.  The maximum concentrations of. these
contaminants are provided in Table 1.  All levels of primary
contaminants detected in the groundwater exceeded federal and/or
state drinking water standards.

Under current EPA guidelines, the likelihood of carcinogenic
(cancer causing) and noncarcinogenic (non-cancer) effects due to
exposure to site chemicals are considered separately.  EPA
considers carcinogenic risk in the range of 10"4 to  10"6 to be
acceptable.  This risk range can be interpreted to mean that an
individual may have a one-in-ten-thousand to a one-in-a-million
increased chance of"developing cancer as a result of site-related
exposure to a carcinogen over a 70-year lifetime under the
specific exposure conditions at the Site.

Potential carcinogenic risks were evaluated using the cancer
potency factors developed by the EPA for the chemicals of
concern.  Cancer potency factors ("CPF"s) have been developed by
EPA's Carcinogenic Risk Assessment Verification Endeavor for
estimating excess lifetime cancer risks associated with exposure
to potentially carcinogenic chemicals.  CPFs, which are expressed
in units of (mg/kg-day)"', are multiplied by the estimated intake
of a potential carcinogen, in mg/kg-day, to generate an upper-
bound estimate of the excess lifetime cancer risk associated with
exposure to the compound at the intake level.  The term "upper
bcur.d" reflects the conservative esti-ate of the risks calculated
from the CPF.  Use of this approach makes the underestimation of
the risk highly unlikely.  CPFs for chemicals of potential
concern can be found on Table 4.

EPA's baseline risk assessment indicates that the most
significant public health risk results from the ingestion of
groundwater, inhalation of groundwater volatiles (i.e., while
showering), and direct contact and ingestion of soils.  Table 5
summarizes the baseline risk assessment results.  Under the.
future-use scenario, ingestion of groundwater in the vicinity of
the Facility by off-Facility adult residents would present an

-------
excess cancer .risk of 2.56 x 10*3; ingestion of groundwater by
on-Facility adult residents would present an excess cancer risk
of 2.55 x 10"3 and for on-Facility child residents an excess
cancer risk of 1.7 x 10*3.  This indicates that future off-
Facility and on-Facility adults have approximately a three-in-
one-thousand additional chance of developing cancer, and on-
Facility children have a two-in-one-thousand additional chance of
developing cancer, as a result of drinking this groundwater.
Under the future-use scenario for on-Facility development
workers, inhalation of the Site soils during construction
activity would present an excess cancer risk of 9.96 x 10~4.
This indicates that an on-Facility worker involved in
construction and excavation activities would have approximately a
one-in-one-thousand additional chance of developing cancer.

The non-cancer risk associated with different pathways was
assessed using a hazard index ("HI") approach, based on
comparison of expected contaminant intakes and safe levels of
intake  (reference doses).  Reference doses (RfDs) have been
developed by EPA for indicating the potential for adverse health
effects.  The chronic and subchronic RfDs for chemicals of
potential concern can be found on Table 4.  RfDs, which are
expressed in units of milligram per kilogram per day (mg/kg-day),
are estimates of daily exposure levels for humans which are
thought to be safe over a lifetime (including sensitive
individuals).  Estimated intakes of chemicals from environmental
media (e.g., the amount of a chemical ingested from contaminated
soil) are compared with the RfD to derive the hazard quotient for
the contaminant in the particular aedia.  The HI is obtained by
adding the hazard quotients for all compounds across all media.
An HI value greater than 1.0 is considered to pose an
unacceptable non-cancer risk.  Under the current-use worker
scenario, inhalation and ingestion of Site soils contributes to
an HI of 2.2.  Under the future-use scenario, ingestion of
groundwater for off-Facility adult residents presents an HI value
of 86.2; ingestion of groundwater for on-Facility adult residents
presents and HI value of 86.2 and for on-Facility child residents
an HI of 114; ingestion and dermal contact with soils for on-
Facility adult residents contributes to an HI value of 2.56 and
for on-Facility child residents an HI of 15.4; ingestion and
dermal contact with Site soils by future on-Facility workers
presents and HI of 2.2 and for future Site development workers an
HI of 23.9.  For soil pathways,  the chemicals of concern which
contribute the most to the HI values are chromium and nickel.
For groundwater pathways, the.largest chemical contributors are
antimony, chromium,  and nickel.

The risk assessment contains the conclusion that inhalation of
Site soils by current off-Facility residents does not present a
non-cancer risk nor an excess cancer risk.

-------
In summary, it is evident that the contaminants in soils at the
Facility and underlying groundwater warrant remediation in order
to prevent the continued degradation of groundwater quality in
the area and to reduce their associated risks.

Uncertainties

The procedures used to assess potential human health risks in
this evaluation are subject to wide uncertainties.  In general,
the main sources of uncertainty in this assessment include:

     A environmental chemistry sampling and analysis;

     * exposure models and assumptions; and

     * toxicological models and parameters.

Uncertainty in environmental sampling arises in part from the
potentially uneven distribution of chemicals in the media
sampled.  Consequently, there is significant uncertainty as to
the actual levels present.  Environmental chemistry analysis
error can stem from several sources including the errors inherent
in the analytical methods and characteristics of the matrix being
sampled.  Uncertainties in the exposure assessment are related to
estimates of how often an individual would actually come into
contact with the chemicals of concern, the period of time over
which such exposure would occur, and in the models used to
estimate the concentrations of the chemical so concern at the
point of exposure.  Uncertainties in toxicological data occur in
extrapolating both from animals to humans and from high to low
doses of exposure, as well as from the difficulties in assessing
the toxicity of a mixture of chemicals.  These uncertainties are
addressed by making very conservative assumptions concerning risk
and exposure parameters throughout the assessment.  As a result,
the risk assessment provides upper bound estimates of the risks
to populations near the Site, and is highly unlikely to
underestimate actual risks related to the Site.

Actual or threatened releases of hazardous substances from this
Site, if not addressed by the preferred alternative or one of the
other active measures considered, may present a current or
potential threat to the environment through the groundwater
pathway.

DESCRIPTION OF ALTERNATIVES

Following a screening of remedial technologies in accordance with
the NCP, five remedial alternatives were developed for
contaminated groundwater and six for contaminated soil.  The
alternatives were further screened based on technical
considerations such as effectiveness, implementability, and cost.
The present worth costs listed below for all soil and groundwater

-------
alternatives are based on a 30-year period and a 5% discount
rate.

Remedial Alternatives for Contaminated Soils (SC)

     A SC-1: No-Action

     A SC-2: Surface Excavation/Off-Site Treatment and
       Disposal/Capping

     A SC-3: In-Situ Vacuum Extraction/In-Situ Stabilization
       (Solidification)/Soil Cover

     A SC-4: In-Situ Vacuum Extraction/Excavation/Off-Site
       Treatment and Disposal/Fill with Clean Off-Site Soil

     A SC-5: In-Situ Vacuum Extraction/Surface Excavation/
       Excavation of Leaching Pits/Off-Site Treatment and
       Disposal/Fill with Clean Off-Site Soil

Alternative SC-1; No-Action

Capital Cost: $ 65,600
Annual Operation & Maintenance (0 & M) Cost: $34,400
Present Worth Cost: $650,000
Time to Implement: 6 months

CERCLA requires .that the No-Action alternative be considered as a
baseline for comparison with other soil alternatives.  Under this
alternative, the contaminated soil would be left in place without
treatment.  A long-term monitoring program would be implemented
to track the migration of contaminants from the soil into the
groundwater utilizing existing monitoring well clusters as well
as a total of 10 newly installed cluster wells.  This alternative
also includes the development and maintenance of a public
awareness and education program for the residents and workers in
the area surrounding the Facility.  Since this alternative would
involve no contaminant removal, CERCLA requires that a Site
subject to such a selected remedy be reviewed every five years.
If justified by the review, remedial actions may be implemented
to remove or treat the wastes.

Alternative SC-2; Surface Excavation/Off-Site Treatment and
                  Disposal/Capping

Capital cost: $1,257,100
0 & M Cost: $32,700
Present Worth: $1,815,400
Time to Implement: 30 months

This alternative would involve the removal of the top 4-5 feet
of contaminated soil from approximately 10,280 ft2  of the  open

                               10

-------
area (entire open area is 16,000 ft2)  of  the  Site.   The  total
volume of excavated material is estimated to be 1,600 cubic
yards.   The excavated soil would be transported to an off-site
permitted Resource Conservation and Recovery Act (RCRA)  facility
for treatment and 'disposal.  For purposes of estimating cost for
this alternative, as well as Alternatives SC-4 and SC-5, it is
assumed that these soils would be treated via stabilization/
solidification.  Off-site transport would comply with all federal
and state transportation requirements.  The excavated area would
be filled with clean soil.  The entire open area (16,000 ft2)
would then be graded and capped with a 6-inch asphalt cap, to
prevent leaching of subsurface contaminants into the ground-
water through infiltration.  Since this alternative would result
in contamination remaining on-site, five year reviews and long-
term monitoring would be required.

Alternative SC-3; In-Situ Vacuum Extraction/In-Situ Stabilization
                  (Solidificationy/Soil Cover

Capital Cost: $1,965,600
0 & M Cost: $27,200
Present Worth: $2,439,300
Time to Implement: 36 months
                                       »>
Under this alternative, the contaminated soil would be left in
place,  undisturbed; no excavation would be required.  An in-situ
vacuum extraction process would be employed over portions of the
volatile organic contaminated area (2,500 ft2)  to remove the
contaminants, mainly TCE, from the soil to 1 mg/kg.  This process
would involve the installation of approximately 5 vacuum
extraction wells, each with a maximum depth of 30 feet.   The
vacuum wells would be connected via a piping system" to a skid-
mounted, high volume vacuum pump.  The vacuum pump would pull air
through the contaminated soils, within a radius of 20 feet from
the wells, depending on soil composition and volatility of the
contaminants.  The air containing the stripped volatile organics
would be fed through a condenser to remove moisture and then
through an emissions control system,  i.e., a vapor phase carbon
adsorption system to remove volatilized organics.

While in-situ vacuum extraction is being applied to applicable
portions of the Site, an in-situ stabilization process would
begin in another portion of the Site and continue until the
entire inorganic contamination has been immobilized.  The
approximate area of inorganic contamination varies from 10,280
ft2  at  the surface to 8,850  ft2 at. a 34-ft depth.  The process
would incorporate mechanical mixing and injection of reagents to .
immobilize both organic and inorganic contaminants.  The
stabilizing additives polymerize with the soils producing a
cement-like mass.  For each type of contaminated soil, the
additives used varies and would have to be optimized.  An on-site
batch mixing tank supplies the proprietary chemical additives.

                               11

-------
Once both processes are complete,  a 6-inch cover of clean soil
would then be placed over the entire yard area (16,000 ft2).
Since this alternative would result in contamination remaining
on-site, five year reviews and long-term monitoring would be
required.

Alternative SC-4; In-Situ Vacuum Extraction/Excavation/Off-Site
                  Treatment and Disposal/Fill with Clean Off-
                  Site Soil

Capital Cost: $8,974,600
0 & M Cost: none
Present Worth: $8,974,600
Time to Implement: 42 months

This alternative is identical to Alternative SC-3 except that the
contaminated soil in areas ranging rom 10,280 ft2 at  the surface
to 8,850 ft2  at  a 34-ft  depth  of the  contaminated yard area  of
the Site would be excavated and transported off-site for treat-
ment and disposal.  In-situ vacuum extraction would be conducted
first in order to prevent exposure of workers and residents to
volatile organics and to reduce organic contaminant levels such
that only inorganics would require treatment off-site prior to
disposal.  Approximately 11,700 cubic yards of contaminated soil
would be transported to an off-site RCRA permitted treatment and
disposal facility.  This total excavation amount is based on the
assumption that all elevated levels of contaminants scattered
throughout the Site would need to be excavated .  The excavated
area,,.would, be filled, with : clean soil,, compacted and graded.

Alternative SC-5: In-Situ Vacuum Extraction/Surface Excavation/
                  Excavation of Leaching Pits/Off-Site Treatment
                  and Disposal/Fill with Clean Off-Site Soil

Capital Cost: $1,777,410
0 & M Cost: none
Present Worth: $1,777,410
Time to Implement: 36 months

This alternative is the same as Alternative SC-4 except that the
amount of soil to be excavated would be different.  After the in-
situ vacuum extraction is conducted,  the top 4-5 feet of the
contaminated yard area of the Site would be excavated, resulting
in approximately 1,600 cubic yards of. material to be transported
for off-site treatment and disposal.   During the course of the
initial excavation when the leaching pits or "hot spots" can be
further delineated through additional borings and sampling,  the
excavation would continue until all contaminated soils were
removed.  The estimated amount of soil that would be excavated --
from the leaching pits is 480 cubic yards.  This amount is based
upon the leaching pits being between 12 - 18 feet in depth and 12
feet wide and assumes that soils within 2 feet of these

                               12

-------
parameters would also need to be excavated.  The excavated areas
would be backfilled with clean soil and the entire open area
(16,000 ft2)  would then be graded.

Remedial Alternatives for Contaminated Groundwater (GW)

     A GW-l:  No-Action

     A GW-2:  Limited Action

     * GW-3:  Pumping/Metals Precipitation/Air Stripping/
              Reinjection

     A'GW-4:  Pumping/Metals Precipitation/Carbon Adsorption/
              Reinjection

     * GW-5:  Puziping/Metals Precipitation/UV-Chemical Oxidation/
              Reinjection

     A GW-7:  Pusping/Pretreatiaent/Discharge to Local Publically
              Owned Treatment Works (POTW)

Alternative GW-1; No-Action

Capital Cost: $65,500
O & M Cost: $26,900
Present Worth: $534,600
Time to Implement: 6 months

The No-Action alternative would only include a long-term
monitoring program to sample the migration of contaminants of
concern in the aquifer.  The contaminants in the groundwater
would be left to attenuate without any treatment.  A total of
twelve monitoring wells, including existing upgradient, Facility,
and downgradient wells would be utilized in order to sample the
groundwater from the shallow and deeper portions of the aquifer
and to track contaminant migration.  Regular five-year reviews
would be performed to assess the need for additional remedial
actions.

Alternative GW-2; Limited Action

Capital Cost:  $99,300
O & M Cost:  $29,700
Present Worth:  $611,500
Time to Implement: 36 months

This alternative would include a long-term monitoring program, as
described in Alternative GW-l,  and also an institutional control
program to restrict the use of the aquifer.  The contaminants in
the groundwater would be left to attenuate without any treatment.
Institutional controls,  such as well permit restrictions,  would
be implemented to limit the use of the aquifer downgradient of

                               13

-------
 the  Facility  for both potable and municipal purposes.  As with
 Alternative GW-l,  regular  five year reviews would be necessary to
 assess  the need for  further response actions.

 Alternative GW-3;  Pumping/Metals Precipitation/Air Stripping/
                   Reiniection

 Capitol Cost:  $971,500
 0  &  M Cost:   $191,100
 Present Worth:  $3,909,200
 Time to Implement: 36 Months

 The  major features of this alternative would include groundwater
 collection, treatment, and reinjection of the treated groundwater
 and  a performance  monitoring program.

 The  collection system would consist of one extraction well  to be
 installed at  the southwestern corner of the Facility into the
 Upper Glacial Aquifer to a depth of approximately 70 feet in
 order to extract 28,800 gallons per day  (gpd) of groundwater from
 the  Site contaminant plume.  The groundwater would then be  piped
 to an on-site treatment facility consisting of two major
•process: treatment to remove metals by chemical precipitation,
 flocculation, clarification and filtration; and, air stripping
 followed by carbon .adsorption to remove volatile organic
 contaminants.  The treatment system would be designed to •
 effectively reduce the metal concentrations .in the treated
 groundwater below  the federal and New York State groundwater
 standards.  Any sludge generated during the metal removal process
 would be disposed  of in a  RCRA Subtitle C landfill.  The spent
 carbon  would  be transported off-site for disposal or regeneration
 and  reuse.  The treated groundwater would then be reinjected into
 the  aquifer through  a reinjecticn well.  The siting of the
 extraction and reinjection wells would be completed during  the
 design  phase  based on technical criteria.

 Alternative GW-4;  Pumping/Metals Precipitation/Carbon Adsorption/
                   Reinieciton

 Capital Cost:  $1,062,900
 0  &  M Cost:   $201,600
 Present Worth:  $4,162,000
 Time to Implement:   36 Months

 The  major features of this alternative would be the same as that
 of Alternative GW-3.  The  unit processes used in this alternative
 are  similar to those of Alternative GW-3 with the exception that
 the  unit operation for organic removal would be achieved.by a
 liquid  phase  carbon  adsorption 'system rather than the air
 stripping system.
                                14

-------
Alternative GW-5; Pumping/Metals Precipitation/UV-Chemical
                  Oxidation/Reini action

Capital Cost: $1,011,200
0 & M Cost: $274,100
Present Worth: $5,224,800
Time .to Implement: 36 months

The major features of this alternative would be the same as that
of Alternative GW-3.  The unit processes used in this alternative
are similar to those of Alternative GW-3 with the exception that
the unit operation for organic removal would be achieved by a UV-
chemical oxidation system rather than the air stripping system
used in Alternative GW-3 or the liquid phase carbon adsorption
system used in Alternative GW-4.  With a UV-chemical oxidation
system, the groundwater would be mixed with a 50% hydrogen
peroxide solution and then pumped to a 20 gpm UV-chemical
oxidation reactor.  The organic contaminants are converted to
carbon dioxide (C02) ,  water,  and chlorides.

Alternative GW-7; Puinpina/Pretreat~ent/Discharae to Local POTW

Capital Cost:  $760,100
0 & M Cost:  $180,700
Present Worth:  $3,537,900
Time to Implement:  42 months

The major features of this alternative would include groundwater
collection, pretreatment, and"discharge of the treated -
grcundwater into the sewer line adjacent to the Site on Kalb
Avenue which leads to the Bay Park Sewage Treatment Plant located
1.0 miles south of the Site.  The unit process used in this
alternative for the removal of heavy metals would be the same as
that used in Alternative GW-3.  The organic removal in this case
is achieved by the activated sludge system (secondary wastewater
treatment system) at the Bay Park Sewage Treatment Plant.

SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES

All remedial alternatives were evaluated in detail utilizing nine
criteria as set forth in the OSWER Directive 9355.3-01. ' These
criteria were developed to address the requirements of Section
121 of CERCLA to ensure all important considerations are factored
into remedy selection decisions.

The following "threshold" criteria are the most important and
must be satisfied by any alternative in order to be eligible for
selection:
                                15

-------
Threshold Criteria  * Overall protection of humam health and the
                      environment; and
                    A Compliance with applicable or relevant and
                      appropriate requirements to the extent
                      practicable.

The following "primary balancing" criteria are used to make
comparisons and to identify the major trade-offs between
alternatives:

Primary Balancing   A Long-term effectiveness and permanence;
   Criteria         * Reduction in toxicity, mobility, or volume
                      through treatment;
                    A Short-term effectiveness;
                    * Implementability; and
                    A cost.

The following "modifying" criteria is considered fully after the
formal public comment period on the Proposed Plan is complete:

Modifying Criteria  * State/support agency acceptance; and
                    A Community acceptance.

The nine criteria are summarized below:

1. Overall Protection of Human Health and the Environment

This criterion addresses whether or not a remedy provides
adequate protection and describes how risks are eliminated,
reduced or controlled through treatment, engineering controls,"or
institutional controls.

Protection of human health is the central mandate of CERCLA.
Protection is achieved primarily by taking appropriate action to
ensure -that there will be no unacceptable risks to human health
or the environment through any exposure pathways.

2. Compliance with ARARs

This criterion addresses whether or not a remedy will meet all
applicable or relevant and appropriate requirements (ARARS')
and/ or provide grounds for invoking waiver.  ARARS can be
chemical-specific, location-specific, or action-specific.

3. Long-term Effectiveness and Permanence

This criterion refers to the ability of a remedy to maintain
reliable protection of human health and the environment over
time,  once clean-up levels have been met.  It also addresses the
magnitude and effectiveness of the measures that may be required
to manage the risk posed by treatment residuals and/or untreated
wastes.

                                16

-------
4. Reduction of Toxici"ty. Mobility, or Vnimne

This evaluation criterion relates to the anticipated performance
of a remedial technology, with respect of these parameters, that
a remedy may employ.

5. Short-term Effectiveness

This criterion involves the period of time each alternative needs
to achieve protection and any adverse impacts on human health and
the environment that may be posed during construction and
implementation of the alternative.

6. Implementabilitv

This criterion involves the technical and administrative
feasibility of a remedy, including the availability of materials
and services needed to implement the chosen solution.
This criterion includes both estimated capital and operation and
naintenance .(O&M) costs.  The present worth costs are based on a
30-year period and a 5% discount rate.

8. State/Support Agency Acceptance

This criterion assesses the technical and administrative issues
and concerns the state may have regarding each of the
alternatives.  The factors to be evaluated includes features of
the alternatives that the state supports, opposes, and any
reservations the state may identify.

9. Community Acceptance

This criterion provides an assessment of any public concerns
regarding any of the alternatives.  Factors of community
acceptance to"be discussed include support, reservation, and
opposition by the community.

Analysis

The.discussion which follows provides a sursary of the relative
performance of each soil and groundwater alternative with respect
to the nine criteria.

SOIL ALTERNATIVES

A Overall Protection of Human Health and the Environment

Alternative SC-1 does not meet the remedial objectives, thus it
would not be protective of human health and the environment due

                                II

-------
to the continued migration of volatile organics and inorganics
into the groundwater.  Alternatives SC-2, SC-3, SC-4, and SC-5
would meet the remedial objective of protecting the groundwater
crom the source.  However, Alternatives SC-3 through SC-5 would
provide a more permanent solution to the problem since the
protectiveness of Alternative SC-2 relies on the effectiveness of
the asphalt cap.  Alternative SC-2 would not meet the cleanup
levels for prevention of cross-media impacts on the groundwater
since only surface soil would be removed.  Alternatives SC-3,
SC-4, and SC-5 have the potential to meet the cleanup level for
volatile organics.  Alternative SC-3 can effectively immobilize
the remaining contaminants.  Alternative SC-5 would meet all
cleanup levels once the leaching pits or "hot spots" of
contaminated are further delineated.  Alternative SC-4 can meet
all the cleanup levels in the unsaturated soil since all of the
contaminated soil would be remove from the Site.  Alternatives
SC-2, SC-3, SC-4 and SC-5 would protect nearby residents and
workers by eliminating inhalation and direct contact pathways.

* Compliance with ARARS

All technologies proposed for use in Alternatives SC-2, SC-3;
SC-4, and SC-5 would ne designed and implemented to satisfy all
ARARs.  However, Alternative SC-2 could result in cross-media
contamination impacts on the groundwater through leaching of
contaminants.  Federal and state regulations dealing with the
handling and transportation of hazardous wastes to an- off-site
treatment facility would be followed.  Contaminated soil, debris,
and sediments from the Site would be treated using specific
technologies or specific treatment levels, as appropriate, to
comply with RCRA Land Disposal Restrictions (LDRs).  The
residuals from the treatment processes (i.e.,  spent carbon) would
also be treated and disposed of to comply with LDRs.  This
alternative will comply with LDRs through .a treatability variance
for the contaminated soil, debris, sediments,  and residuals.
(More detail can be found under the "Statutory Determinations"
section).

A Loner-term Effectiveness

Alternative SC-1 would only monitor the migration of the
contaminants and would not provide treatment or containment.
Therefore,  it would not provide effective or permanent long-tera
protection of groundwater or human exposure to soils at the Site.

Alternatives SC-2, SC-3,  SC-4, and SC-5 would mitigate the
significant risks by partial or total removal and/or
immobilization of Site contaminants.  Alternatives SC-4 and SC-5
would provide the highest 'degree of effectiveness since all
identified contaminated soils would be treated as well as removed
from the Site..  Alternatives SC-3 can effectively remove TCE from
the soil through in-situ vacuum extraction and can effectively

                               18.

-------
immobilize the remaining contaminants:  although the long-term
integrity of the stabilized soil matrix is unJcnown, maintenance
of the soil cover over the stabilized soil would help ensure that
future leaching does not occur.  Alternative SC-2 may not be as
effective as Alternatives SC-3, SC-4, and SC-5 because it would
leave contaminants in-place without treatment and relies on the
integrity of the asphalt cap to prevent further migration and
cross-media impacts on the groundwater.

A Reduction in Toxicity. Mobility,  or Volume

Alternative SC-1 would provide a very slow and gradual reduction
in toxicity through natural attenuation.   It would provide no
reduction in contaminant mobility.   Alternative SC-2 would
provide a reduction in mobility of surface soil contaminants via
removal and off-site stabilization and in subsurface contaminants
by Site capping, but does not reduce the toxicity of the
subsurface soils. •

Alternatives SC-3, SC-4, and SC-5 again are similar, in that each
would result in significant reductions in the toxicity, mobility,
and volume of the treated material.  Material toxicity would be
reduced by removal and in-situ vacuum extraction of TCE and other
volatile organics under Alternatives SC-3, SC-4, and SC-5.
Contaminant mobility would be reduced in Alternative SC-3 by in-
situ stabilization and a soil cover over the treated soil.
Alternatives SC-4 and SC-5 would provide for reduction in
toxicity, mobility, and volume.through removal of all
contaminated soil.  Volume increases resulting' from stabilization
of metal contaminated soil would be minimal in SC-3.

* Short-terra Effectiveness

The implementation of Alternative SC-1 would result in"no
additional risk to the community or workers during
implementation, since subsurface soil would not be disturbed.
Alternatives SC-2, SC-4, and SC-5 would include activities such
as contaminated soil excavation and off-site transport or on-
site treatment that could result in potential exposure of
residents and workers to volatilized contaminants and
contaminated dust.  Engineering controls and other measures
(e.g., restricting access to the sit* t-.o authorized personnel
only)  would effectively eliminate an> impact these activities
would have on nearby residents.  Alternatives SC-3 would include
in-situ treatment of contaminated soils,  so exposure risk to
workers and residents from excavation would be minimal.  Under
Alternatives SC-3, SC-4, and SC-5,  proper air emission control
units would be installed to minimize the potential for public
health exposures because of low-level emissions from on-site
treatment units.

-------
Alternative SC-1 would be implemented in approximately 30 months.
Alternatives SC-2, SC-3, SC-4, and SC-5..would be designed and
constructed in roughly 2 years with actual remediation to follow,
resulting in full implementation time frames of approximately 6,
12, 18, and 12 months, respectively.

A Implementability

Components of all alternatives would utilize relatively common
construction equipment and materials.  Although implementable,
some construction difficulty would be encountered with
Alternatives SC-2, SC-3, SC-4, and SC-5 because of the limited
Facility space available for equipment staging and material
handling.  Alternative SC-3 would not have a space problem since
no excavation and stockpiling would be required.  Alternative SC-
4 would involve maximum excavation and would require the largest
work area.  Alternative SC-1 would be the easiest to implement.

A degree of uncertainty exists with the in-situ processes called
for in Alternatives SC-3, SC-4, and SC-5, since these
technologies have only been performed.on a limited full-scale
basis at similar contaminant concentration levels.  However, the
physical nature of the soils at the Site appear to be optimum for
the in-situ vacuum extraction process.
According to the present worth cost estimates for all
alternatives evaluated", Alternative SC-4 ($8t974,600) would be
the most costly alternative to implement, followed by
Alternatives SC-3, SC-2, and SC-5.  Alternative SC-1, no action,
would be the least costly to implement.  Present worth considers
a 5% discount rate, and a 30-year operational period for
Alternatives SC-1, SC-2, SC-3, and SC-5.  Since Alternatives
SC-4 and SC-5 do not require any 0 & M cost, their present worth
costs are equivalent to their capital costs.  The present worth
cost estimates for the alternatives evaluated are as follows:

     SC-1: $   650,000
     SC-2:   1,815,400
   -  SC-3:   2,439,300
     SC-4:   8,974,600
     SC-5:   1,777,410

Alternative SC-5 is protective and permanently treats the
principal threats posed by the Site at a cost of $1,777,410,
which is much less than Alternative SC-4.

A CoTTununity Acceptance

No objections from the community were raised regarding the
selected soil remedy.  A responsiveness summary which addresses

                                20

-------
all comments received during the public comment period, including
the March 13, 1991 public meeting, is attached as Appendix IV.

A State Acceptance

The State of New York, through the NYSDEC,  has concurred with
EPA's selected remedy.  The NYSDEC letter of concurrence is
attached as Appendix III.

GROUNDWATER ALTERNATIVES

A Overall Protection of Human Health and the Environment

Alternatives GW-l and GW-2 would not provide protection of human
health and the environment.  Existing groundwater contamination
would continue to degrade the aquifer and downgradient
groundwater.

Alternatives GW-3, GW-4, GW-5 and GW-7 would be much more
protective of human health and the environment than Alternatives
GW-l and GW-2 since they would be directed at reducing the
toxicity, mobility, and volume of contaminants in the aquifer and
protecting downgradient groundwater from further contamination.

A Compliance with APARs

Alternatives GW-l and GW-2 would not comply with federal or state
drinking water standards or criteria or those ARARs required for
protection of the groundwater resources.' -Neither alternative
would achieve ARARs.

The design of Alternatives GW-3, GW-4, and GW-5 would be
performed to permit achievement of chemical-specific ARARs for
drinking water and those required for groundwater protection in
the treated water stream.  Alternative GW-7 would be in
compliance with a discharge permit to a POTW.  Each of these
alternatives would be capable of providing the required
contaminant removal levels.  Because UV-chemical oxidation
(Alternative GW-5) experience is limited,  its effectiveness is
slightly less certain but considered achievable.  Groundwater
protection criteria would not be met at all points of the aquifer
immediately upon implementation of any of the alternatives.  A
second operable unit groundwater invesciga*.icn would be required
to determine the need for potential remediation of the
downgradient portion of the plume.

The residuals from the treatment processes (i.e., spent carbon)
would also be treated and disposed of to comply with LDRs.  This
alternative will comply with LDRs through a treatability variance
for the spent carbon.
                               21

-------
 A  Long-tern Effectiveness and Permanence

 Alternatives GW-l and GW-2 would not provide treatment, but
 Alternative GW-2 would restrict the use of the contaminated
 aquifer for private and municipal purposes.  Neither alternative
 would restore the contaminated aquifer for future use.

 Alternatives GW-3, GW-4, GW-5, and GW-7 would all function to
 reduce the potential risk associated with groundwater ingestion
 by extracting and treating the groundwater to remove contaminants
 from the aquifer.  The time to achieve these risk reductions
 would be limited by the-effective extraction rates from the
 aquifer.  The long-term effectiveness of any of the systems would
 be dependent upon a well planned monitoring program and proper
 operation and maintenance of the treatment system.  None of the
 alternatives would be able to remediate the groundwater to
 federal and state standards in a reasonable period, but the
 treatment alternatives would protect downgradient groundwater
 from further contamination while further Investigation of the
 downgradient groundwater is conducted.  The reinjection process
 called for in Alternatives GW-3, GW-4, and GW-5 would result in
 conservation of groundwater resources.  Alternative GW-7 extracts
 groundwater from the aquifer and discharges it to a POTW, thereby
 failing to replenish the aquifer.

 Alternative GW-4 would require the disposal of more process
 residuals than Alternatives GW-3, GW-5, and GW-7, since liquid
 phase carbon adsorption would be used.  The estimated annual
"carbon usage would be approximately 6,000 Ibs for the liquid
 phase activated carbon unit called for in Alternative GW-4 as
 opposed to an estimated 2,000 Ibs for the vapor phase carbon unit
 called for in Alternative GW-3. .

 A  Reduction in Toxicitv, Mobility, or Volume

 Alternatives GW-l and GW-2 would not involve any removal,
 treatment, or disposal of the contaminants in the aquifer and
 therefore would not be effective in reducing the toxicity,
 mobility, or volume.

 Alternatives GW-3, GW-4, GW-5, and GW-7 would effectively reduce
 the toxicity, mobility, and volur-j of contaminants in the aquifer
 to a larger extent than Alternatives wW-1 and GW-2, since
 removal, treatment and disposal would be provided.  These four
 alternatives would be similarly effective in their reduction of
 the toxicity, mobility, and volume of contaminants.

 A  Short-term Effectiveness

 The implementation of Alternatives GW-l and GW-2 would result in
 no additional risk to the community or on-site workers during
 remedial activities since no major- construction activities would

                                22,

-------
 be  conducted.

 Alternatives GW-3, GW-4, GW-5, and GW-7 include excavation
 activities, installation of the collection and reinjection/
 discharge  systems, and construction of the treatment plant that
 could  result in  potential exposure of residents and workers to
 volatilized contaminants and contaminated dust.  The treatment
 plant  would be constructed on-site.  Proper handling procedures
 of  the treatment reagents must be followed for all treatment
 alternatives.  All alternatives, except Alternatives GW-1 and
 GW-2,  would generate process residuals requiring proper handling
 and disposal.

 Alternatives GW-1 and GW-2 would take less than 1 year to
 implement.  Alternatives GW-3, GW-4, GW-5, and GW-7 would all
 require approximately 2 years to complete their construction
 prior  to operation.

 *• Implementability

 All components of Alternatives GW-1 and GW-2 would be easily
 implemented.  Alternative GW-2 would require that state or local
 authorities implement institutional controls to restrict the use
 of  the aquifer for private and municipal purposes.  These
 controls would have to be implemented by the state or local
 authorities.  Alternatives GW-3, GW-4, GW-5, and GW-7 would
 utilize relatively common construction equipment and materials.
 Site space available for treatment plant construction is limited.
'In  Tight of"this, Alternative GW-7 would be the easiest treatment
 alternative to implement -since only a pretreatment system would
 be  required on-site.  However, Alternative GW-7 would require
 that a discharge permit be granted by local authorities.  There
 is  a degree of uncertainty as to whether this permit could be
 obtained.

 The metals precipitation technology common to all treatment
 alternatives is  proven and reliable in achieving the specified
 process efficiency and performance goals.  The air stripper and  .
 vapor  phase carbon unit called for in Alternative GW-3 is a
 proven and efficient method of removing organic contaminants from
 groundwater, as  is the liquid phase carbon adsorption technology
 proposed for use in Alternative GW-4.  UV-chenical oxidation (for
 destruction of organic contaminants) called for in Alternative
 GW-5 has not been used extensively, but has been used
 successfully in  several groundwater treatment facilities.  An
 additional process may need to be added onto Alternative GW-5 if
 the resulting chlorides from the UV-chemical oxidation process
 exceed the maximum limits allowable for reinjection.  The use of
 the activated sludge process of the Bay Park Sewage Treatment
 Plant  proposed for use in Alternative GW-7, to remove the organic
 contaminants from the pretreated groundwater, is a conventional
 municipal  wastewater treatment system designed to aerobically

-------
biodegrade organic contaminants.

All proposed treatment technologies are readily available from a
number of sources with the exception of UV-chemical oxidation.
It is expected that additional equipment manufactures will be
available once the UV-chemical technology becomes more mature.

Alternatives GW-3, GW-4,  and GW-5 would require institutional
management of the operation and maintenance of the treated
groundwater reinjection system.  Alternative GW-7 would require
coordination with the Bay Park Sewage Treatment Plant for the
discharge and treatment of the pretreated groundwater.

Off-site disposal facilities are available for the disposal of
the pretreatment sludge generated from Alternatives GW-3, GW-4,
GW-5 and GW-7.  Disposal facilities for the spent carbon
generated from Alternatives GW-3 and GW-4 are also available.
The estimated annual carbon usage would be approximately 6,000
Ibs for the liquid phase activated carbon unit called for in
Alternative GW-4 as opposed to an estimated 2,000 Ibs for the
vapor phase carbon unit called for in Alternative GW-3.  The
spent carbon would be transported off-site for disposal or
regeneration and reuse.  Any process residual generated from the
activated sludge system during the treatment of the contaminated
groundwater in Alternative GW-7 would be properly handled by the
Bay Park Sewage Treatment -facility.

  Cost

According to the present worth cost estimates for all
alternatives evaluated, Alternative GW-5 ($5,224,800) would be
the most costly alternative to implement followed by Alternatives
GW-4, GW-3, GW-7, GW-2, and GW-1.  Alternative GW-7 would be the
least expensive treatment alternative.  Present worth is based on
a 5% discount rate, and a 30-year operational period.  The
present worth cost estimates for the alternatives evaluated are
as follows:
GW-1
GW-2
GW-3
GW-4
GW-5
GW-7
$ 534,600
611,400
3,909,600
4,162,000
5,224,800
3,537,900
  Community Acceptance

No objections from the community were raised regarding the
selected groundwater remedy.  A responsiveness summary which
addresses all comments received during the public comment period,
including the March 13, 1991 public meeting, is attached as
Appendix IV.

                                24

-------
 A State Acceptance

 The State of New York, through the NYSDEC, has concurred with
 EPA's selected remedy.  The NYSDEC letter of concurrence is
 attached as Appendix III.

 SELECTED REMEDY

 Based upon an evaluation of the various alternatives, EPA and
 NYSDEC recommend Alternative SC-5 (In-Situ Vacuum Extraction/
 Surface Excavation/Excavation of Leaching Pits/Off-Site Treatment
 and Disposal/Backfill with Clean Off-Site Soil) and active  -
.restoration of the groundwater utilizing Alternative GW-3
 (Pumping/ Metals Precipitation/Air Stripping/Reinjection) as the
 preferred alternative for remediation of contaminated soils and
 groundwater at the Facility.  Prior to implementation, an
 extensive design effort will be performed to elaborate on
 specific details of the preferred alternative.

 The preferred alternative will involve the following actions: '

 Soil

 First, an in-situ vacuum extraction process will be employed over
 portions of the contaminated area (2,500 ft2)  to reduce the
 volatile organic contaminants, mainly trichloroethene, to 1 mg/kg
 or one part per million.  This process will involve the
 installation of approximately 5 vacuum extraction wells, each
 with a maximum depth of- 30 feet.  The vacuum wells will be
 connected via a piping system to a skid-mounted, high volume
 vacuum pump.  The vacuum pump will pull air through the
 contaminated "soils, within a radius of 20 feet from the wells,
 depending on soil composition and volatility of the contaminants.
 The air containing the stripped volatile organics will be fed
 through a condenser to remove moisture and then through an
 emissions control system, i.e., a vapor phase carbon adsorption
 system to remove volatilized organics.

 After the vacuum extraction process,  the top 4-5 feet of soils
 at the Facility will be excavated, resulting in approximately
 1,600 cubic yards of material to be transported for off-site
 treatment and disposal in compliance with land disposal
 restrictions.  Excavation to this depth addresses all
 contamination found with the exception of the deeper
 contamination in the leaching pit areas.  This will eliminate the
 risk posed by direct contact with soils.  During the course of
 this initial excavation when the leaching pits or "hot spots" of
 contamination can be further delineated, the excavation will
 continue until all contaminated soils are removed.  It is
 estimated that the leaching pit excavation will result in 480
 cubic yards of material transported off-site for treatment and
 disposal.   This amount is based upon the leaching pits being
 between 12 - 18 feet in depth and 12  feet wide and assumes that

                             ..... 25

-------
soils within 2 feet of these parameters would also need to be
excavated.  Exact areas and depths of contamination will be
determined during the design phase.   Additional sampling during
design to delineate "hot spots" will ensure that all contaminated
areas are removed and, at the same time, that excessive and
unnecessary excavation will not occur as with Alternative SC-4.
The excavated areas will be backfilled with clean soil and the
entire open area (16,000 ft2)  will then be  graded.

Alternative SC-5 will treat the principal threat posed by Site
soils and significantly reduce cross-media impacts on the
underlying groundwater.

During the design phase, further evaluation of the potential for
inorganic contaminants to leach from the soil to the groundwater
will be conducted to determine the specific soil quantities
required to be removed in order to protect the groundwater from.
significant inorganic contamination resulting from leaching of
the inorganic contamination in the soils.  The cleanup levels
derived from this effort will 'represent average contaminant
concentrations of the inorganic chemicals in the soil which will
theoretically produce contaminant groundwater concentrations in
the Site vicinity which will meet potable water standards.  Also,
the design phase will involve sampling of areas adjacent to the
Sice to determine immediate background levels and to ensure that
soils off-site do not pose a risk.

The present worth of Alternative SC-5 is $1,777,410.

Grouadvater

Approximately 28,800 gallons per day of contaminated groundwater
will be extracted through one extraction well to be installed at
the southwestern corner of the Site into the Upper Glacial
Aquifer to a depth.of approximately 70 feet, in order to remove
heavy metals and chlorinated organics which are currently present
above szate and/or federal drinking water standards.  The treated
groundwater will then be reinjected into the aquifer through two
reinjection wells.   The siting of the extraction and reinjection
wells will be completed during the design phase based on
technical criteria.   The treatment residuals will be disposed of
in a RCRA subtitle C facility.  The major components of the
grcuTivivater remedy,  Alternative GW-3, are depicted in Figure 4.
All contaminant concentrations will be reduced until they are
equal to or less than their respective federal or state standards
prior to reinjection.  The treated effluent will be tested to
ensure that the treatment system is operating efficiently.  Any
waste residuals generated by the treatment processes will be
disposed of in accordance with applicable disposal standards.

The purpose of the interim groundwater response action is to
control risks posed by the ingestion of contaminated groundwater
and to limit further migration of contaminants by addressing the

                               21

-------
following issues:

     A Containment of the most highly contaminated portion of the
       contaminant plume;

     A The metal concentrations (chromium, nickel, copper,
       cadmium, manganese, and iron)  will be reduced through a
       metals precipitation process involving a clarification/
       filtration unit.

     A The chlorinated organic concentrations (1,1,1-tri-
       chloroethane, trichloroethene, 1,1-dichloroethene, and
       tetrachloroethene) will be reduced using air stripping.

     A Collection of data on aquifer and contaminant.response to
       remediation measures.

The ultimate goal of groundvater remediation will be determined
in a final remedial action for this Site.  This interim  ground-
water remedial action will be monitored carefully to determine
the feasibility of achieving this goal with this method and to
ensure that hydraulic control of the contaminated plume is
maintained.  After the period of time necessary, in EPA's
judgement, to arrive at a final decision for the Site, a final
ROD for groundwater, which specifies the ultimate goal, remedy
and anticipated remediation timeframe, will be prepared.  Upon
completion of the second operable unit RI/FS, this interim system
may be ..incorporated into the design of the Site remedy specified
in the final action groundwater ROD.

The present worth of Alternative GW-3 is $3,.909,600.

STATUTORY DETERMINATIONS

EPA believes that the selected interim remedy will satisfy the
statutory requirements of providing protection of human health
and the environment, being cost-effective, utilizing permanent
solutions and alternative treatment technologies or resource
recovery technologies to the maximum extent practicable, and
satisfying the preference for treatment as a principal element.

Protection cf KuT^ar..Health and the Envirorjent

Alternative SC-5 is considered to be fully responsive to this
criterion and to the identified remedial response objectives.
Treatment, excavation, and disposal of the contaminated Site
soils will prevent the release of contaminants to the environment
and will constitute excellent protection of both human health and
the environment.  The carcinogenic and non-carcinogenic risks
associated with the contaminated soil will be reduced to
acceptable levels for current and future uses (i.e. 10"4 to 10"6
and HI < 1.0).  Treatment of the groundwater through

                               22

-------
implementation of Alternative GW-3 will reduce the toxicity,
mobility, or volume of contaminants in the groundwater and^result'
in overall protection of human health and the environment.  Prior
to reinjection, the groundwater will meet all state and/or
federal drinking water standards.  A second operable unit will be
initiated to address potential future risks.

Compliance with ARARs

The selected remedy for source control (SC-5: in-situ vacuum
extraction/surface excavation/excavation of leaching pits/off-
site treatment and disposal/backfill with clean off-site soil)
will comply with all related ARARs.  The off-site facility will
be fully RCRA permitted and will be in compliance with the terms
of the permit.  Contaminated soil, debris, and sediments from the
Site will be treated using specific technologies or specific
treatment levels, as appropriate, to comply with LDRs.  The
residuals from the treatment processes (i.e., spent carbon)  will
be treated and disposed of to comply with LDRs.  This alternative
will co'mply with LDRs through a treatability variance for the
contaminated soil, debris, sediments, and residuals.  Based on
concentrations determined by the Toxicity Characteristic Leaching
Procedure (TCLP) test, the appropriate concentration range or
percent reduction.will be determined during design.

At the completion of the response action for contaminated soil,
the selected remedy will have complied with the following ARARs:

Action-specific ARARs:._.._._ 	     v      ._.-,

The selected remedy calls for the transport of contaminated soil
and treatment residuals to a RCRA facility for treatment and
disposal and will comply with the following ARARs:


 A RCRA 40 CFR Part 263 - Standards Applicable to Transport of
   Hazardous Waste

 A RCRA 40 CFR Part 264 - Standards for Owners and Operators of
   Hazardous Waste Treatment, Storage, and Disposal Facilities

 * RCRA 40 CFR Part 268 - Spent carbon from the in-situ vacuum
   extraction treatment systsm aj well as any other•treatnent
   residuals will be disposed of cff-site, consistent with
   applicable land disposal restrictions.

 A 6 NYCRR Part 372 - Hazardous Waste Manifest System & Related
   Standards for Generators, Transporters and Facilities.

 A 6 NYCRR Subpart 373-2 Final State Standards for Owners and
   Operators of Hazardous Waste Treatment, Storage and Disposal
   Facilities.

                                28

-------
 A During implementation of the in-situ vacuum extraction,  all
   resulting air emissions will be in compliance with 6 NYCRR
   Parts 200, 201, 212, and 231.

Chemical-specific ARARs:

 A None applicable.

Location-specific ARARs:

 A None applicable.

The selected groundwater remedy, GW-3:  pumping/metals
precipitation/air stripping/reinjection, is expected to comply
with the associated ARARs over time.  The primary purpose for
this interim groundwater remediation is to contain and treat the
most highly contaminated portion of the plume.  A second operable
unit, resulting in the final groundwater remedial action for the
Site, will address achievement of chemical-specific ARARs in
groundwater.

The residuals from the treatment processes (i.e., spent carbon)'
will be treated and disposed of to comply with LDRs.  This
alternative will comply with LDRs through a treatability variance
for the spent carbon.

The associated ARARs include:

Action-specific ARARs:

 A RCRA 40 CFR Parts 141.11-141.16 (SDWA Maximum Contaminant
   Levels (MCLs))  (See Table 1 in Appendix II),  provide standards
   and goals for toxic compounds for public drinking water
   systems.  The reinjection process for the treated groundwater
   will meet underground reinjection well regulations by its
   status as a Superfund remedial action under 40 CFR 147.   The
   extracted groundwater will be treated to meet all standards
   prior to reinjection.

 A 6 NYCRR Part 703 and 10 NYCRR Part 5 - provide groundwater
   quality standards and drinking water standards.

 A RCRA 43 CFR Parts 263, 264, 263; and NYCPJi Fart 3"2 (described
   above under action-specific ARARs for soil) - spent carbon, as
   well as any treatment residuals, from the groundwater
   treatment system for removal of organics and inorganics will
   be transported, treated (as necessary), and disposed of off-
   site.
                               29

-------
Chemical-specific ARARs:

  A Since  the groundwater at the Site is classified as lib,
   drinking water standards are relevant and appropriate.  Again,
   these  include SDWA MCLs, 6 NYCRR Groundwater Quality
   Regulations  and/or limitations of discharges to Class GA
   waters, and  10 NYCRR Part 5 standards.

Location-specific ARARs:

  * None applicable.

Cost Effectiveness

The selected remedy provides overall effectiveness proportional
to its cost.  The total capital and present worth costs for the
soil and  groundwater alternatives are estimated to be $1,777,410
and $3,909,200, respectively.  The selected soil alternative,
SC-5, is  the least expensive treatment alternative.  The selected
groundwater alternative, GW-3, is the second least expensive
treatment alternative.  Alternative GW-7, involving discharge to
the POTW,  would be slightly less costly to implement, however,
.GW-7 would not  conserve groundwater resources.

Detailed  cost estimates of the selected groundwater and soil
alternatives are depicted on Tables 6 and 7, respectively.

Utilization of  Permanent Solutions and Alternative Treatment
Technologies to the Maximum Extent Practicable           ...

The selected remedy utilizes permanent solutions.and treatment
technologies to the maximum extent practicable.  The selected
remedy represents the best balance of trade-offs among the
alternatives with respect to the evaluation criteria.  The State
and community also support the selected remedy.

The selected remedy employs permanent treatment of the organic
contaminated soil on the Site through the implementation of in-
situ vacuum extraction and through excavation and off-site
treatment and disposal.  The potential for future releases of
organic contaminants to the environment as well as the direct
contact risk to the soils will be eliminated.  The indirect and
direct risks posed by the soils as a continued source of
groundwater contamination will be removed.  Extraction and
treatment of.contaminated groundwater will reduce the toxicity,
mobility,  and volume of contaminants in the groundwater
underlying the  Site and prevent further degradation of area
groundwater.

No short-term adverse impacts and threats to human health and the
environment are foreseen as the result of implementing the
selected  remedy.  However, to minimize and/or prevent worker

                                10

-------
exposure to contaminants, personal protection equipment will be
utilized.

The selected remedy will require construction of on-site soil and
groundwater treatment facilities.  No technological problems are
anticipated since the treatment technologies are well established
and readily available.

Preference for Treatment as the Principal Element

The selected remedy fully satisfies this criterion for the
treatment of the soil and groundwater contamination which are
considered, the principal threats at the Site.  There the
statutory preference for remedies that employ treatment as a
principal element is satisfied.

EXPLANATION OF SIGNIFICANT DIFFERENCES

The Proposed Plan for the Genzale Plating Company site was
released to the public on February 22, 1991.  The Proposed Plan
identifies the selected remedy as including Alternatives SC-5 and
Alternative GW-3.  Upon further review, EPA determined that a
minor modification to the selected soil remedy (SC-5), as it was
originally identified in the Proposed Plan, was necessary.
Because the principal threat posed by the contaminated soil at
the Site will be eliminated through removal or treatment of the
soils, EPA determined that an asphalt cap over the entire
Facility is not required.  In the alternative, EPA proposed that
the entire Facility be backfilled with clean off-site soil, and
this proposed difference was presented and explained at the  /
public meeting to provide the public with an opportunity to
comment on the change.  EPA has reviewed all verbal comments
expressed during the public meeting, and no written comments were
received.  No objections to the proposed plan or the modification
were raised.
                                31

-------
APPENDIX I




  FIGURES

-------
GENZALE  PLATING PLANT
                                                                           SlIC SuRfACE  AND SutiSuRf ACC
                                                                                  SIRUCIURCS

-------
                                                                                          "	l»        II       |4
08
                                    GENZALE  PLATING  PLANT
7~is
(ys)
                                                                                                                                              "       it
                                                                                                                                                       11_






                                                                                                                                                  lECEND


                                                                                                                                                 ' M«-»
                                                                                                                                                            MU 10 H
                                                                                                                                                       yntMAf A
                                                                                                                                                       ^ff"^^»*


                                                                                                                                                       «• WMIOBNC MU
                                                                                               HUtl

                                                                                               (i) IOCADON ANO sn or
                                                                                                  SIONACf 1UU} AM
                                                                                                                                                  ) iu IUMC >-} ran
                                                                                                                                                   ACIUM idCAiot or
                                                                                                                                                   UQMIOKMC Mlli
                                                                                                                                               CRAl'MIC SCALE

                                                                                                                                                    =fe
                                                                                                                                                    i nn )
                                                                                                                                        U a CNVUOMNCNTAL ftOItCIIOII AC CMC!
                                                                                                                                              U«|At( PlAkiC CO. VB .
                                                                                                                                             IIAMUM MIA*. «• lOU

                                                                                                                                        MONITORING WCU LOCAllONS
                                                                                                                                           UtSCO JC«nCCJ

-------
JWSC-5155 A
                                                                                                                       _NFWLJY INSTALLED MONITORING WILLS
                                                                                                                        if>  MW-4S
                                                                                                                        ^  UW-SS
                                                                                                                        PUIILIC SUPPLY  WtLLS
                                                                                                                        A   JOIH mANKLIN  SQUARE WAlfR  DIS1HICI
                                                                                                                        A   '117 FRANKLIN SQUARE WAUR OIS1HICT
                                                                                                                        A   4298 JAMAICA WAItH SUPPLY COUP ANY
                                                                                                                        A   i'iS JAMAICA WAItH SUPPLY COMPANY
                                                                                                                       PIUVAIC
                                                                                                                                         MCU
                                                                                                                        A   7744 PLAIlOeUlSQIC REI1REUENI HOME

                                                                                                                       COUtm MONITORING WELL
                                                                                                                            9984 NASSAU COUNIY OEPI. PUBLIC WORKS
                                                                                                                                                                  I MJL£
                              HIS INMMMC IXISIS ON * C*\*> IUC.  t»> Will III M.'J II UAHIIMI f
                                 OA*
                                                             DAH
                                                                                     EBASCO SERVICfS INCORPORAICD
I   ««0    «•£!"
   	 CM_
   AS MOID)
                   J	L
                                    U.3. ENVIRONUXNTAL PROTECTION
                                               AGENCY
                                                                                                                             CENI ALE PLAHNC CO. SITE
                                                                                                                                  crr-siir MILS
                                                                                                                            OIOIMOWA4UI
                                                                                                                                                             CPA
                                                                                                                                                             4236.374
                                                                                                                                                            ncutt i-5

-------
'I   i>wir • +



I
     HUM • -J-
0-8
                                                        •       •    .   I*
                                                                                      II       II

                               GENZALE  PLATING PLANT
                                                                                                                             >'       n      II
                                                                                                                               jj irc
                                                                                                                                 uc-oi
                                                                                                                                           M
                                                                                                                                     HUHlCwiC nil IUKMC
                                                                                                                                IIOII

                                                                                                                                (I) iOC*Un
                                                                                                                                (1) Ul l»J*l 1 i ICM
                                                                                                                                   «£|UM lULOIdH IK Ul-illl
                                                                                                                                           il DOMMCi
                                                                                                                                           SCALC
                                                                                                                                      I » nn i

-------
*
c
c
1
r
o
i
j
t










                                                  II       II       11       l<
                                                                                           I*       I'       I*       II
GENZALE PLATING  PLANT
M0il_
(I) IOCHIKJM AM) S« Of

  MTMUUU
                                                                                                      CHAI'HIC SCALE

                                                                                                          • nn i
                                                                                               U 1  CHViaOHKCKTU. ftOfOTIlOM
                                                                                                  CIAJCO j£
                                                                                                                   'iCUBt

-------
                                                                         to Aiuur>riiiur
                       UONI l( WING
                          W1 IL
                                                                        MOIS1URE
                                                                        RECOVERY
                                                                          1ANK
                                                                                                                 WAICR IRfAICD
                                                                                                                     AND/OR
                                                                                                                    OlSI'OSfO
08
3233
oo
PHOOUCIION
   Will


in"; j*Mtt*tfi; f *ftf.\ * _

*^r«u«»
II

mi KNVIHONU»:NIAL I'IIDTICIIOH
AII»:NI V
CfH/AlC f'lAllHIi C0. Slif
MIIWWIM «l 1 1
rmnli% utm IIMOHOM MNI
H vlu vmtnw IHIMIIIIIN
ir*
•3IO.CII
r—


-------
OLHIMOwt)  Mill

-------
           PKETHCAIMENf
                UUCT
                 DLIIUMIDII il.R
   VAPOR PHASE
      OARHON
     AOSUKIH.R
1O A1MOSPHERE
                                AIR
                             SHOPPING
                               IOWI:R
§§
SI RIPPED
 WAII U
 SUMP
IO REINJECIION
-<




1




IS W/U




me




in





-------
APPENDIX II




   TA3LZS

-------
                                                                                 I
                                 COWAMINAWS or CONCERN  IN GROUNUWATER ANO  IIIEIR COMPARISON wini ARAR BASED CLEANUP LEVELS
                                          Averay?*
                                          Conccn-
                                          trat ion
             Conceo-
             trat ton
             lug/UJ-
          Hiniiraia
          Concen-
          trat ion
          SWUA MIL'i
          J.UU/JJ	
             NY
            HCl's
            luy/11
                   NYS GROUNUWAIER
                   SIANOARUS  CLASS GA
                NYS TECHNICAL
                OPERATIONAL G
                SERIES (TOGS)
                       (uu/Ll
YOLAlILLJM&AmCS.

1 . l-Uichloroethane
1 , l-0ich)oroethene
let rachl ornellif ne
1,1. 1-Triclrloroclhane
1 , 1 ,2-Trichlo roe thane
Irichloroethime
Vinyl Chloride

Semuol 4l U e JJuaai ti

Uen;o( a) anthracene
Beruo(b) f luoranthene
(lenio(a)pyrene
Qls(2-etliylhexyl )Phthalate
Chrysene
Antimony
Arsenic
Barium
Deryll iuM
Cadmium
Chromium VI
Copper
Iron
Lead
Hanijanese
Nickel
Vanadiun
Zinc
1.43
25.13
41.5
299
1.45
121.90
0.411
1.75
1.75
2.0
9.5
1.75
421.43
5.68
260.13
2.43
23
3523.06
832.78
54042.5
96.27
053
4726.03
90.97
419.1
3
94
96
1100
2
500
0.6
2
2
2
36
2
1116
11.3
314
2.9
37
14400
32^0
120.000
105
IU'100
21900
731
1620
Nl)
W)
Nil
NU
Nil
NU
NU
Nl)
NU
Nl)
Nt)
NU
Nl)
NO
51
NU
NU
73.7
16
1560
17.6
10
44
NU
22
7
5
200
50


10



50
  5
  5
  5
  5
  5
  5
  2
               50
               50
               10
               50
               50
  50
1000

  10
  50
1000
 300-
  50
 300"
                5"
                                         10
                                         5.0
  25
1000

  10
  50
IOUO
 300
  25
 300
                                       5000
                    50
                    0.07
                    0.07
                    50
                    0.6
0.002


0.002



30

1000

3
                                             5000
*   Average of on-ilte wells.  Duplicate  sani|iliis  are  avnraycil  to represent  *t well.
••  If iron and manganese ire present,  the  total  concentration of  both should not exceed 0.5 ng/l.   Illyher levels «viy ba allowed whtn Justified by  I
    supplier of water.
**• Secondary Standard
349 IK

-------
Tri chloroelliene
Benio( a) anthracene
Benzo(a)pyrene
Oenzo{b)fluoranthene
Bis(2-ethylhexyl)uhlhalate
Clirysene
Indeno( 1 , 2.3-c,d)pyrene
Arsenic
Barium
Chromium (VI)
Nickel
PCBs (Arochlor  1260)
                                                                  IAOLE  2

                             CONIAHINANIS Of  CONCEKN OETECIEO IN SOIL ANU IIIEIH COMPAHISOM W1III At HUN LEVELS
                  HinioHim
               Concontr.it ion
               	ID'J/-KU	
ND
NO
NO
NO
NO
NO.
NO
NO
NO
2.1
NO
NO
                            Conccnlrjt ion
                            	my/.Ku	
2.;o
0.105
0.440
0.5'JO
4.569
0.463
0.339
2.72
604.65
141)6. M
1901.16
0.462
                     H.I* i
                  Content rat ion
                  	my/Ku	
53
 2.2
 I.a
 1.0
24.0
 2.2
 1.0
14.8
36400
3/300
5UUOO
 1.213
 * - Based on excess  lifetime  cancer  ri'.k  of  I«IO~"
NO - Not detected or  below method  of  detection limit
NR - No risk identified
BG - Action level based on background concentration
33/6K

-------
                INORGANIC COMPOUND CONCENTRATIONS
               TYPICALLY FOUND IN LONG ISLAND  SOIL
ANALYTES
BACKGROUND(1)  CONCENTRATION
	RANGE (ma/ka)	
Aluminum
Antimony
Arsenic
Barium
Beryl liur?.
Cadmium
Calcium
Chromium
Cobalt
Copper
Iron
Lead
Magnesium
Mercury
Nickel
Potassium
Selenium
SiIver
Sodium
Thai liurn
Vanadium
Zinc
Cyanide
     10000 - 300000
     <1 - 500(2)
     5 - 15<2>
     100 - 3500
     <1 - 7<2>
     0.01 - 7
     100 - 400000
            (2)
     10 - 80
     <3 - 70
     2 - 100
(2)
     7000 - 550000
     3 - 30(2>
     100 - 4000
     0.2 - 0.6(2)
     * - 30(2>
     400 - 30000
     0.1 - 2.0
     0.1 - 5.0
     750 - 7500
     1 - 2(3)
     20 - 500
     10 - 300
     Not Available
SOURCE:  (1)  Dragun, J., 1938
         (2)  Conner, J.J. and H.T. Shacklette, 1=75
         (3)  USIPA, 1982

-------
1AIILE  /,  -  IOXIOIIY I'AMAMEIEMS USED IN  I HI: IIISK ASM SSMI Nl (8lin.il I nl 2

Chemical ol
Potential Concern
aculone
horuone
tiromodlchloromnthanu
2-bulanonu(MEK)
carbon lelrachlorldo
chlorobunzono
cliluiuloim
chloromolhana
dlbromochlorornolhana
.t-dlchloroelhana
,2-dlchloroelhane
,1-dlchloroelhona
,2-dlchloroelheno(lfans)
,2-dlchlo(opropane
olhylbonzono
inelhylene chlorldo
slyiona
lelrachloioelhuno
loluuna
t.t.t-lilchloroulhana
t.1.2-lrlchloroulhana
lilchloroelherie(d)
Irlchlofollouromelhane
vinyl chloilda
lylones
anlhracena
benzole acid
bls(2-elhylhexyl) phlhalalc
butyl banzyl phlhalale
dl-n-bulyl plilhalala
llouranthane
llourena
naphthalene
phenol
pyiono
carcinogenic PAIIs
Chronic Moloroncu Doso(Mfl))
(m<)/hi)/«lay)
Inhalalion
NA (c)
NA (b)
NA
9. 001: -02
NA
5.00C-03
NU
NA
NA
I.OOE-OI
NA
NA
NA
NA
NO
NA
NA
NA
200E.OO
3.00E-OI
NA
NA
2.00E-01
NA
4 OOE-01
NA
NA
ND
NA
ND
NA
NA
NU
NA
NA
NA
Source (a)



HEA

ML- A



HEA








IIL:A
• It A


HEA

II (IS











Oral
1 OOE-01
NA
20tll;-()2
5.00E-02
7.00E-04
2. 001: -02
I.OOE-02
NA
2.00IZ-02
I.OOE-OI
NA
900E-03
2CXIL-02
NA
t.OOL-01
C.OOE-02
2.00i:-0t
1. 001: -02
3.00L-OI
90011-02
400E-03
NA
30011-0)
NA
2 001:. 00
300E-01
4.00E.OO
200E-02
2.00E-01
i.oon-oi
4.00E-02
4.00E-02
4.00E-03
G.OOE-OI
3.00E-02
NA
Souicit (a)
IMIS

II IIS
IMIS
IMIS
IMIS
IMIS

IMIS
MLA

IMIS
IMIS

IMIS
IMIS
IMIS
IMIS
IMIS
IMIS
IMIS

HEA

IMIS
IIC A
IMIS
IMIS
IMIS
IMIS
MEA
HEA
HEA
IMIS
HEA

Siibchiuiuc Mnluiuncu Dose (HID:,)
(ni||/k(|/.l.ly)
Inhal.Ulun
Ml)
NA
NA
9 001; -01
NA
S. 001: -02
NA
NA
NA
5.CKH .00
NA
NA
NA
NA
NA
NA
NA
NA
2 .OOi: .00
rM
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA.
NA
NA
IIA
NA
SouiLu(a)



HEA

HEA



HEA








HEA
















•
Oral
NA
NA
2.00E-02
S.OOE-OI
/OOE-03
2.00E-OI
l.0()l:-02
NA
2.00E-OI
1.00E«00
NA
9 OOE-03
200E-OI
NA
t.OOL.OO
NA
200E.OO
1.00E-OI
4.00E-OI
9.00E-01
4.00E-02
NA
7.00E-01
NA ,
400E.OO
300E.OO
4.00E«00
2.00E-02
2.00E«00
t.OOE.OO
4.00E-01
4.00E-01
4 OOE-03
G.OOE-OI
3.00E-01
NA
Source (a)


HI:A
HliA
III A
III A
HEA

HEA
HEA

HEA
HEA

HEA

HEA
Ml A
HEA
HEA
HEA

HEA

HEA
HEA
HEA
HEA
HEA
HEA
HEA
HEA
HEA
HEA
HEA

Cancur Potency Facloi
(m(|/ku/day)*-t
Inhalalion
NA
2 'JOE -02
NA .
NA
1.30E-OI
NA
O.I 01: -02
6.30E-03
NA
NO
9 10E-02
1.20E»00
NA
NA
NA
1.4UE-02
2. OOE-03
NA
•NA
I.60E-05
S.70E-02
1.70E-02
NA
2.95E-OI
NA
NA
NA
NO
NA
NO
NA
NA
NA
NA
NA
G.I
Source (a)

IMIS


IMIS

IMIS
HEA


IMIS
IMIS



IMIS
HEA


HEA
IMIS
HEA

HEA











(o)
Ural
NA
290E-02
NA
NA
I.30E-01
NA
6 IOE-03
I.30E-02
B.40E-02
9.IOE-02
9.IOE-02
6 OOE-OI
NA
680E-02
NA
7.50E-03
300E-02
NA
NA
5.70E-02
S.70E-02
t.lOE-02
NA
2.30E.OO
NA
NA
NA
1.40E-02
NO
NO
NA
NA
NA
NA
NA
11.5
Source (a)

IMIS


IMIS

IMIS
HEA
HEA
HEA
IMIS
IMIS

HEA

IMIS
HEA


HEA
IMIS
HEA

HEA



IRIS







(o)
Wl. ol Ev.
D
A
02
O
02
O
02
C
C
C
02
C

02
0
02
02



C
02

A



02
C




O



-------
TAUIE
ICIIY I'AMAMEIEMSUSI DIN I ML MISK ASSLSSMLNI (Miuol 2 nl

Chomiral ol
Polontlal Cuncotn
chlordane
4.4 DOT
dloldrln
hoplachloi epoitlde
PCils (arochlor 1200)
anllmony
aisunlc
barium
beryllium
cadmium; lood (MID)
cadmium; water (HID)
chromium; hexavalanl
chromium; Irlvalunl
copper
manyanasa
mercury
nickel
sllvor
solenlurn
lhalllum
vanadium
zinc
cyanide
Mulomni o Uuso (MIU)
(niii/Mi/day)
Inhalation
Nl)(b)
NA(c)
NA
NA
NA
NA
NA
I.OUE-04
NO
NO
-
NO
NO
NO
30011-04
NO
NO
NA
NA
NA
NA
NO
NA
Sourcu (a)







MEA






ML A








Oial
600E-OS
50011-04
S.OOE-0'j
1.30E-0'j
NA
4 01)1: -04
1 OOE-03
700E-02
5 OOE-03
1.0OE-03
500E-04
500E-03
1 OOt.OO
3./OE-02
I.OOE-OI
300E-04
2.00E-02
300E-03
3.00U-03
7.00E-OS
/OOE-03
2.00E-01
200E-02
Suurco(a)
II IIS
IMIS
IMIS
IMIS

IMIS
MEA
IMIS
IMIS
IMIS
IMIS
IMIS
IMIS
MEA
IMIS
MEA
IMIS
IMIS
HE A
MEA
MEA
MEA
IMIS
Subclnumc Moltmince Oose(MIOs)
(ni\(/K.)/ilay)
Inhalallun
NA
NA
NA
NA
NA
NA
NA
1 OOE-03
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
Source (a)







MEA















Oral
GOOt-OS
S.OOE-04
b.OOE-Uli
NA
NA
4.00U-04
1. OOE-03
/.OOE-02
5. OOE-03
NA
NA
2. OOE-02
1 OOL.OI
3./OE-02
NA
300E-04
200C-02
3 OOE-03
NA
7OOE-04
7. OOE-03
2.00E-OI
200E-02
Source (a)
MEA
MEA
MEA


MEA
MEA
MEA
MEA


MEA
MEA
MEA

MEA
MEA
MEA

MEA
MEA
MEA
MEA
Cancur Potency Facloi
(inu/kcjAlayr-l
Inhalation
1 30E.OO
3 4011-01
1 GUI:. 01
9 10E.OO
NO
NA
SOOE.OI
NA
840E.OO
C tOE.OO
-
4.IOE.OI

NA
NA
NA
840E-OI
NA
NA
NA
NA
NA
NA
Source (a)
IMIS
IMIS
IMIS
IMIS


IMIS

IMIS
IMIS

IMIS




IMIS






Oral
I.30E.OO
340E-OI
1 GOE.OI
9 10E.OO
7.70E«OO
NA
t.80E*oo
NA
4.3015*00
NO
-
NO

NA
NA
NA
NO
NA
NA
NA
NA
NA
NA
Source (a)
mis
IMIS
IMIS
IMIS
IMIS



IMIS










~



ol Ewlde
(12
U2
112
U2
112

A

U2
Ul

A




A






                    (a)  IMIS
                        MEA
                    (b)  NO
                    (C)  NA
                    (d)
                            Ml&k Inlorrnallon System (USEI'A)
                   HOAM > • Moots As6us&iniM)l Summary loUlos
                   Nol boionnlned
                   Not Aooiicable or Nol Available
        Cancer Potency ^ tutors (of Trlchloroelhene have boon withdrawn Irom IRIS as ol 6/90.
    (e)  Cancel Poloncy Fa :lors lor PAMs have been removed Irom IMIS and MEA. Ihusu are Interim
        (actors rocommoiidod by U.S. EPA's ECAO.
    (I)  Holerenca Oosc lor load estimated Irom the SOWA MCL by assuming an adull (7!>kij) drinking
        2 liters ol water pur day.

-------
i ABLE r»  : SUMMARY OF BASELINE RISK ASSESSMENT RESULTS FOR THE GENZALE PLATING COMPANY SITE

Ma/Hid
llllln«

Cull will
Pll-Sllll llclllllullll
•' IIIHII
', All I'alliiway*
B04U-04
Cimenl
GPC
Wolknl
f.£OE»OO
Fuluio
Oll-Slla Mnd.lunU
IIIHII Ah I'olhwiiy* and
(iMIIIIldvVAllll UHO
(071 lOI
riilmn On- Gilo
!>ull Pnlh«%lly|
2 Ml 100
A, lull H.iililiinl
(liiiiinilN*!*! I'alliway*
• 02EtOI
1 uluia On-Glla Child llmldanl
tioll I'clliMayt
1 64E«OI
Uiouiiilnnliii rallmiiy*
I.14E«02
fului*
QPG
Wwk.l
2.2t)E«M
Fuluia
Sll* 0*vulopm*nl
Wo)k*r
2.3UEHM
it CiMililliulliMi |ty |>i»lliwny:
Inhalnllun
Ingaillon
donnal
IOOH
-
-
- .
42 4H
67 OH
O.IH
Dtf »^ (uiiHindmnlni)
-
-
42 4H
67 flH
0 IH
00 0H
-
-
32 *H
07 2H
0 2H
0U «H
-
-
42 4H
67 OH
IU3H
• 3H
24H
rt C
-------
1.
2.
3.
4 .
5.
6.
7.
8 .
9.
10
11
12
13

14
15
15
                           TABLE 6

    SUMMARY  OF  COST  ESTIMATES FOR ALTERNATIVE GW-3:  PUMPING/
             PRETREATMENT/AIR STRIPPING/REINJECTION
     ITEM
Support Facilities
Groundwater Extraction
Collection
Pretreatment
Air Stripping
Treated Water Reinjection
Electricals
Instrumentation & Controls
Process Water Supply
Foundation and Pads
Miscellaneous
Contingency-
             Legal
             e
Engineering,
Administrati
Labor
Maintenance
Monitoring Wells
      Total

     TOTAL PRESENT WORTH"
and
                                 COST (1991 DOLLARS)

22
37
18
228
80
40
82
. 85
17
50
10
.143
108


43
ITAL
,100
,200
,300
,600
,900
,100
,000
, 000
,000
,000
,000
,900
,000
_
-
,400

.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00


.00
ANNUAL

700
—
11,500
4,300
200
-
—
-
-
-
9,100.
-
87,600.
77,700.
—
ow

.00

.00
.00
.00





00

00
00

                              971,500.00      191,100.00

                                      3,909,200
•Present worth analysis based on a 30-year period and 5 percent
 discount rate.
                              4-56
3467K

-------
                            Table 7

     SUMMARY  OF  COST ESTIMATES  FOR  ALTERNATIVE  SC-5:   IN-SITU
       VACUUM EXTRACTION/SURFACE EXCAVATION/EXCAVATION OF
      LEACHING PITS/OFF-SITE TREATMENT AND  DISPOSAL/BACKFILL
                     WITH CLEAN OFF-SITE  SOIL

          ITEM                             COST (1991 DOLLARS^
                                           CAPITAL    ANNUAL OSra

1.  Warning Signs .                         100.00
2.  Site Preparation                     3,000.00        - .
3.  Support Facility                    13,600.00
4.  In-Situ Vacruua Extraction          157,500.00 •
5.  Surface Soil Excavation   •          30,400.00
6.  Excavation of Leaching Pits          9,600.00
7.  Off-Site Treatnent               1,020.000.00
    (Stabilization)  and Disposal
8.  Treatability Study                  50,000.00
9.  Clean Fill                          32,400.00
10. Contingency                        263,320.00
11. Engineering, Legal and             197,490.00
    Administrative                   	     	
     TOTAL             .              1,777,410.00


    * First year.QSM cost included in the capital cost.

-------
        APPENDIX III




NYSDEC LETTER OF CONCURRENCE

-------
New York State Department of Environmental Conservation
50 Wolf Road, Albany, New Yortt 12233 -7010
                                                                         Thomas C. Jorilng
                                                                         Commlsalonar
                                                      '«*  2 - ;S9i
           Mr.. Kathleen C. Callahan
           Director
           uv.orgency & Remedial Response Division
           U.S. Environmental Protection Agency
           Region II
           25 Federal Plaza
           New York. NY   10278
                                 Re:  Urufl KccoiM of Doci?.ion
                                      Geruale Plating Site -  10 No.
           Dear M-i. Cal Kilian:
           The New York Stale Deyar-UiienL uf tnviromnontal Conservation
           approves the Record of Decision for the Genzale  Plating  Site #130018
           with the following conditions:

           1.    Duriny deuiyn:

                 a)   Surface soil sampling will be  initiated  to  better delineate
                      the area and the total volume  of  soil  to be excavated.

                 b)   The so-i 1 cleanup levels for inorganic  compounds will  be
                      determined subject to NYSDEC approval, and  will be used
                      to delineate the extent of excavation.

           2.    During remediation:

                 a;   Al' 'euc:;-nb- ^, w will be "ocated  and  e'-av-ited.   Vhere  avo
                      four known  leaching pits; however, more  arc suspected.

                 b)   Tho nifltallic anomalies detected during the  RI  will  be
                      proporly characterized and handled appropriately.

           3.    Off-site residential surface soils  adjacent to the site will  be
                 sampled either during the design or during  the second  operable
                 unit.

           <1.    Warning signs will be posted outside the sito as soon  as possible.

-------
Ms. Kathleen C. Callahan                                          Pago 2

Please contact Mr. Michael J. O'Toolo, Jr. if you have any questions or
       •j regarding this matter.

                               Sincerely,
                               FdwardjO. Sullivan
                               Deputy Convnissioner

-------
      APPENDIX IV




•RESPONSIVENESS SUMMARY

-------
               RESPONSIVENESS SUMMARY
               GENZALE PLATING COMPANY
             FRANKLIN SQUARE , NEW YORK
The U.S. Environmental  Protection Agency ("EPA")  held a
public comment period from  February 22, 1991 through March'
23, 1991 to receive comments  from interested parties on the
final Remedial Investigation  and Feasibility Study ("RI/FS")
reports and Proposed Plan for the Genzale Plating Company
Superfund site ("Site").

A public participation  meeting was conducted by EPA on March
13, 1991 at the Franklin Square Public Library, Franklin
Square, New York to discuss remedial alternatives, to present
EPA's preferred remedial alternative, and to provide an
opportunity for the interested parties to present oral
comments and questions  to EPA.

This responsiveness summary provides a synopsis of citizen's
comments and concerns about the Site as raised during the
public comment period,  and  EPA's responses "to- those comments.
All comments summarized in  this document were considered in
EPA.'s final decision for selection of the remedial activities
for cleanup of the Genzale  Plating Company site.

This responsiveness summary is divided into the following
sections:

   I. Responsiveness Surunary  Overview •- This section briefly
      describes the background  of the Genzale  Plating Company
      site and summarises  the proposed and selected
      alternatives.
  II. EacV.crc u~d r-n Cor-?.ur.itv Involvement, gnd Cor^c^rr.s - This
      section provides a orief history of  conxmnity interests
      and concerns regarding the Genzale  Plating Company
      site.

 III. SuTTunary of Public Comments and  EPA's Responses - This
      section summarizes comments expressed verbally at the
      public meeting and provides EPA's responses to these
      comments.

  IV. Appendices - This section includes  a copy of the agenda
      for the public meeting (Appendix A)  and the public
      meeting sign-in sheet (Appendix B) .

-------
I. RESPONSIVENESS SUMMARY OVERVIEW

Site Background

The Site includes the property located at 288 New Hyde Park
Road in the Town of Franklin Square, Nassau County, New York.
The Genzale Plating Company ("Company") facility is located
in a primarily residential area.

The Company has operated an electroplating facility on the
property since 1915.  The property occupies an area of
approximately 24,000 square feet.  The western portion of the
property is occupied by a two story building which houses the
company office, plating facility, and chemical storage area.
The eastern portion of the property is undeveloped and serves
as an outdoor storage yard and parking lot. .

Subsurface structures located in the yard include sanitary
and industrial sewer lines, and four abandoned wastewater
leaching pits, approximately 12 to 18 feet in depth.

Presently, the operation consists of electroplating
automobile and houseware products using nickel and chrome.
Past operations included anodizing and cadmium, zinc, and
brass plating.  The electroplating processes utilize several
degreasing and cleaning agents, including organic solvents.
Distillation, of spent 1,1,1-trichloroethane is currently
performed by the Company to recycle the product for re-use.
Wastewater, which is currently treated and discharged to the
municipal sewer system, was discharged in the past to the
underground leaching pits.

In 1981, the Nassau County Department of Health ("NCDH")
conducted an inspection of the Company which indicated that
wastewater being discharged to the leaching pits exhibited
heavy metal concentrations in excess of NYSDEC discharge
standards.  In June 1986, the Site was added to the EPA
National Priorities List of Superfund sites.

A special notice letter was issued to the Company on December
21, 198".  Based upon the Cor^any's response it was
atitfemii(,-:cl -i.at. it vds tir.ancially unable to conduct the
investigative activities at the Site.  Accordingly, EPA
proceeded with the RI/FS.  In August 1989, EPA issued an
Access Order to the Company so that field work could
commence.  As a result of the Company's failure to comply,
EPA sought and was granted a court ruling in October 1989
which enforced the terms of the Order.  Field work for the
RI/FS began in November 1989 and was completed in February
1990.

-------
Summary of Proposed and Selected Remedial Alternatives

The remedial alternatives considered for the Site are
described in the RI/FS and Proposed Plan for this operable
unit (referred to as operable unit one).  All alternatives
considered are listed below:

Remedial Alternatives for Contaminated Soils (SO)

   A SC-1: No-Action
   A SC-2: Surface Excavation/Off-Site Treatment and
     Disposal/Capping
   A SC-3: In-Situ Vacuum Extraction/In-Situ stabilization
     (Solidification)/Soil  Cover
   A SC-4: In-Situ Vacuum Extraction/Excavation/Off-Site
     Treatment and Disposal/Fill with Clean Off-Site Soil
   A SC-5: In-Situ Vacuum Extraction/Surface Excavation/
     Excavation of Leaching Pits/Off-Site Treatment and
     Disposal/Fill wich Clean Off-Site Soil

Remedial Alternatives for Contaminated Groundwater (G¥)

   A GW-l: No-Action
   A GW-2: Limited Action
   A GW-3: Pumping/Metals Precipitation/Air
     Stripping/Reinjection
   A GW-4: Puaping/Metals Precipitation/Carbon Adsorption/
     Reinjection                                       •
   A GW-5: Pumping/Metals Precipitation/UV-Cheinical
     Oxidation/Reinjection
   A GW-7: Pumping/Pretreatment/Discharge to Local Publically
     Owned Treatment Works  (POTW)

EPA,  with concurrence from the New York State Department of
Environmental Conservation,  chose a remedy which addresses
the principal threats posed by the Site through a combination
of a soil remedial alternative (SC-5) with active restoration
of the groundwater (GW-3) .  Based on current information,
these alternatives provide the best protection of human
health and the environment.

II. BACKGROUND OP COMMUNITY INVOLVEMENT

Community interest in the Site has been high throughout the
RI/FS process.  The community has been kept aware of
activities at the Site through local newspaper articles, fact
sheets, press releases, public notices,  and public
information meetings.

The major concern expressed by the community is the migration
of contaminants into the local public water supply wells and
the close proximity of the Site to residences.

                              «*	

-------
III.  SUMMARY O? PUBLIC COMMENTS 6 BPA'S RESPONSES

Comments expressed at the public meeting held on March 13,
1991 are summarized below.  No written, comments were received
during the public comment period.

Specific Questions Regarding the RI/FS and Proposed Alternative

COMMENT: A representative from the FranJclin Square Water
District inquired about the sampling results of two water
district supply wells.

RESPONSE: All of the water supply wells sampled, those
belonging to the Franklin Square Water District ("FSWD") and
the Jamaica Water Supply Company ("JWSC"),  had either very
minimal or no contamination.  A sample taken from FSWD well #
7117 detected trichloroethylene at 5 parts per billion
("ppb"), which is the maximum contaminant level allowable.  A
sample taken from JWSC well f 4298 detected trichloroethylene
at an estimated quantity of 16 ppb.  Samples from FSWD well #
3604 ar.d JWSC well # 5155 detected no volatile organic
compounds above allowable limits.  No heavy metals, in excess
of allowable limits, were detected in any of the above four
Welter supply wells.

COMMENT: A resident asked whose responsibility it is to
operate and maintain the treatment system during its use.

RESPONSE: The EPA would fund the first.ten years of the
remedial action.  Thereafter, the State of New York would be
responsible for the long-term maintenance of the treatment
system.

COMMENT: A resident wanted assurance that EPA would be
working closely with the local water districts.

RESPONSE: EPA has worked with both the Franklin Square Water
District ("FSWD")  and the Jamaica Water Supply Company
("JWSC") during the remedial investigation.  Both FSWD and
JWSC will be involved with EPA during the design of the
treitr.r-r.t s^r-'tcz for this first oc«.rabl-? unit of the Site and
will also be involved in developing the sampling plan for the
second operable unit, which will investigate a downgradient
plume of contamination.  It is possible that FSWD and/or JWSC
wells will be sampled during the second operable unit.

COMMENT: A resident wanted to know why it took so long for
the sampling results to become available.

RESPONSE: After the soil and groundwater samples were
collected  between November 1989 through February 1990,  they

-------
were all analyzed by a certified laboratory and then
validated to ensure the quality of the results.  This process
took about 4-5 months.  Once all the data was compiled,  EPA
evaluated the data to determine whether the results pose a
risk.  All the data results and the risk results have been
summarized and explained in the RI report.

COMMENT: A resident asked whether the same type of treatment
proposed for the Genzale Plating site is currently in
operation at any other sites on Long Island.

RESPONSE: At present, similar technologies have been proposed
for use at other sites on Long Island.  A similar groundwater
pump and treat system involving metals precipitation is
currently being-designed for the Preferred Plating site,
located in Farmingdale, Suffolk County.  The design is
scheduled to be completed in September 1991.  Vacuum
extraction has been selected for other sites, but is
currently still in the design stage.

COMMENT: A resident asked if the treatment system would be
continuously operating and how loud the vacuum extraction
process would be.                                .

RESPONSE: The groundwater pump and treat system should
operate oh a continuous basis, 24 hours a day.  The vacuum
extraction process, will take place during normal working
hours, approximately 9 a.m. through 5 p.m.  Without special
housing, the vacuum extraction process reaches approximately
80 decibels.  The system can be designed with a special
housing encasing it, so the noise level will be greatly
reduced.  The entire vacuum extraction process, from
mobilization and implementation through completion, should
require six months.

COMMENT: A resident asked how long it would be before the  .
treatment systems are designed and constructed and EPA was
back on the property.

RESPONSE: The design for both the groundwater treatment
sy-te~ and tht? :=oll ^r^c.'.m'jnt an'4 excavation system will
Legia i.i OctwOtr  9*1 ar.u wii^. require 13 to 24 months for
completion.  EPA expects to be constructing the treatment
systems on the property by October 1993.  Construction of
both the vacuum extraction process and the groundwater
treatment system will not be extensive. . Construction of the
vacuum extraction process must first  involve the installation
of the extraction wells.  The groundwater treatment units are
readily available and can be brought  to the property q-uickly.
Extraction and reinjection wells will need to be installed
first.

-------
COMMENT: A resident asked when the drums on the property
would be removed.

RESPONSE: The 65 drums currently on the property resulted
from the remedial investigation field work.  They contain
discarded protective clothing, drill cuttings,  and
decontamination and development water.  Normally/ the drums
would remain on a site until EPA is constructing the
treatment system.  It is EPA's responsibility to ensure the
integrity of the drums.  Presently, all 65 drums are in good
shape and do not pose any danger.  If the drums show signs of
decay or deterioration, they will either be overpacked or
removed promptly from the property.

COMMENT:  A resident asked whether the treated groundwater
that is to be reinjected into the aquifer will be sampled.

RESPONSE: The groundwater treatment system will be designed
to include continuous monitoring and sampling of the treated
water to ensure the efficiency of the system and to ensure
that federal and/or state drinking water standards are being
met prior to reinjection.

COMMENT: A resident asked how many gallons per day will be
pumped through the treatment system.

RESPONSE: The current pump rate estimate is 28,800 gallons.
per day.  This estimate will be further refined during the
design phase.

COMMENT: A resident asked what would happen to the property
if the Genzale Plating Company were to go out of business.

RESPONSE: No matter if the Genzale Plating Company or anyone
else is on the property, EPA's treatment system will remain
on the property until the groundwater is remediated.

COMMENT: A resident asked how long the treatment system would
remain on the property.

r.1^-^ .:*,:*: Tv.e so.'Is tr^tment should be completed in six
-cn'uhs.  Tha current estimate for the length of time required
for remediation of the groundwater is 30 years.  Since the
source of contamination in the soils will be removed prior to
the full implementation of the groundwater treatment system,
the estimated time for remediation may decrease.  The
treatment system will be continuously monitored and the
remediation time frame will be adjusted accordingly.

COMMENT: A resident asked if the treatment system would be
enclosed to ensure its safety from children.

-------
RESPONSE: A temporary structure will be placed over the most
of the groundwater treatment system to limit access and to
protect the treatment units from the elements.  The exact
details and dimensions of the housing structure will be
determined during the design phase. .

COMMENT: A resident asked if the treatment system would be
visible from the curb side of the property.

RESPONSE: The only part of the treatment system which may be
visible from outside of the property will be the air
stripper.  This unit will be approximately 16 feet high.  The
fence surrounding the property is about 10 - 12 feet in
height.  Presently, it appears that the treatment system will
be located in a corner of the property.  The air stripper
will most likely be situated behind one of the tall trees
bordering the property,  making it a bit less noticeable from
the curb.

COMMENT: A resident asked if any types.of signs would be
placed on the property and if EPA provides for guards or
security.

RESPONSE: Signs which inform the public of the presence of a
Superfund site and the name of the site are commonly placed
on the site during remedial action.  EPA recognizes that the
community is sensitive over having a Superfund site in this
very residential area.  EPA is willing to discuss the use of
signs with the community.  One approach would be to install
warning an "no trespassing" signs only.

COMMENT: A resident asked where EPA would be sending the
excavated soils and sludges from the treatment system and why
it would be acceptable to place contaminated material in
another location.

RESPONSE: Any excavated soils, sediments, or sludges
resulting from the treatment system will be transported off-
site to an EPA-permitted facility.  This facility, or
landfill, must be in compliance with EPA's Resource
Conservation and Recovery Act.  These  facilities are strictly
'c-.x'--'---' £^^ co;,V..-. .iid -o ens'-rt. u. .*• r.o contaminants can
migrate from the landfills into the surrounding environment.
Any excavated soils and sludges will first be treated or
stabilized prior to their disposal in the landfill to ensure
that contaminants will not leach out.  The exact location of
this facility has not been determined as yet.

-------
Questions Regarding the Present Status of the Genzale Plating
Company

COMMENT: A resident asked if the Genzale Plating Company is
currently in operation on the property.

RESPONSE: Yes, the company still operates on the property.
The leaching pits are no longer used for discharge of waste
water.  The company now treats their waste water prior to
discharge"to the municipal sewer system.

COMMENT: A resident asked whether the Genzale Plating Company
could continue operating on the property during the remedial
action.

RESPONSE: The plating company can continue to operate on the
property as long as their operations do not interfere with
EPA's actions and they are no longer contributing to the
contamination problem.  The company must continue to comply
with the terms of their operating license.

General Superfund Questions

COMMENT: A resident asked how many ongoing Superfund sites
are located on Long Island and how many of those represent
emergency situations.

RESPONSE: EPA has assessed sites on the National Priorities
List to determine which sites pose imminent threats that
warrant emergency action.  These actions may be temporary or
permanent in nature and can range from relocation of
residents to provision of alternative water supplies or
physical removal, treatment, or containment of wastes.   These
actions are taken to reduce imminent danger without delay.

At present, there are approximately 20 - 25 Superfund sites
listed on the National Priorities List in Nassau and Suffolk
Counties.  Very few of these sites currently have ongoing
e-errrercv removal actions.  One removal action is currently
*.•«•. .1.1.^° ..ofiCii''' ^~.:-l >':'! til..; .*... >'.'.aC3 S^'t-ti iii G.! .1". CoVts , N =t J i 3'•.
County, to repair a collapsed .retaining wall at the site.
Removal actions have been completed at other Long Island
sites such as at the Rowe Industries site located in Sag
Harbor, Suffolk County (provision of an alternative water
supply) and at the Claremont Polychemical site located in Old
Bethpage, Nassau County and the Circuitron site located  in
Farmingdale,  Suffolk County (removal of contaminated
materials stored in drums, tanks, etc.)

-------
 COMMENT: A resident asked if EPA has any policy allowing
   Krms in the vicinity of a site to bid on the work being
   nducted at the site, in order for federal monies being
 spent to go back into the community.

 RESPONSE: EPA retains several contractors under its
 Alternative Remedial Contracting Strategy ("ARCS") and
 Technical Enforcement Support ("TES") programs.  Both ARCS
 and TES contracts were competitively bid to ensure equality
 and fairness and several contracting firms were selected into
 each program,, providing EPA with a fast method of procuring a
 contractor to repond guickly to a given site situation.  EPA
 does not have a set policy to use local contracting firms.
 The U.S. Army Corps of Engineers ("COE") will, at times,
 oversee remedial actions for EPA and will open bids to all
 interested parties.  Local firms may possibly have the
 opportunity to responsd to a bid invitation from the COE or
 through subcontract to a, prime EPA contractor.

 Questions Regarding Enforcement  Issues

 COMMENT: A resident asked if EPA has any indication as to
 whether the Company could contribute financially to the
 project.

 RESPONSE: Based on the information gathered at this time, the
^potentially responsible party, Genzale Plating, is not
^financially viable to" fund a remedial action of this
 magnitude.  Initially, the Company expressed an interest in
 .conducting the remedial investigation, but determined it was
 impossible upon realizing the scope of the work involved.
 The federal government is in the process of issuing a notice
 of lien on the property,.which would enable EPA to recover
 monies, paid for the property up to the amount expended at the
 Site.

-------
     APPENDIX A




PUBLIC MEETING AGENDA

-------
      I  UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

      r"                        REGOHI
                            K. JAVTTS FSCRAL BXDING
                          »«W YO«K, >€W YORK 10278
                                  AGENDA
                            Information  Meeting
                      Genzale Plating Superfund site
                        PranXlin  Square,  New York

                        Wednesday.  March  13.  1991
                                7:00  P.M.
    I. Welcome & Introduction
    II. Overview of Superfund
    III.  Site History
    IV.  Remedial Investigation
        Results
    V.  Risk Assastr.ent
    VT   r -;s- ibil;'-
    VII.  Proposed Alternative
Cecilia Echols
Conununity Relations
 Coordinator
U.S. EPA, Region  2   '

Douglas Garbarini
Chief, Eastern  New  York/
Caribbean Superfund
 Section
U.S. EPA, Region  2

Janet Cappelli
Remedial Project  Manager
U.S. EPA, Region  2

Tom Fowler
Field Work Supervisor
EBASCO Services,  Inc.
 (Consultant  to EPA)

Marina Stefanidis
U.S. EPA, Region  2

i:-pl : o K-.*-..>• -:'
Feaiibiiit'^ Study Leader
EBASCO Services,  Inc.
 (Consultant  to EPA)

Janet Cappelli
    VIII.  Questions and Answers
    IX.  Closing
PRKTc" ON RECYCLED PAP£R

-------
           APPENDIX B '




PUBLIC MEETING SIGN-IN SHEETS

-------
                             UK I TED STATES  ENVIRONMENTAL PROTECTION AGENCY
                                                RE
-------
                         UNITED STATES ENVIRONMENTAL  PROTECTION AGENCY
                                           REGION II
                                         PUBLIC MEETING
                                              FOR
                                 Genzale  Plating fluperfund Site
                                   Franklin Square, New York

                                         March 13, 1991
                                       MEETING ATTENDEES
».
(A
     NAME
     QJ
       O
_/>v^-W
^LA
   -n>
      STREET
/<>
                              /O
                      rritfifi /
                        if
                                         (Pleaae Print)
                                      CITY
                /A
                       ii          i>
                                                // o
                                                   PHONE
                                                        77V-
                                                                 Yo
REPRESENTING
MAILING
LIST

-------
         APPENDIX  V




ADMINISTRATIVE RECORD INDEX

-------
                       GEN2ALE  PLATING COMPANY
                     ADMINISTRATIVE RECORD  FILE
                         INDEX  OF DOCUMENTS

 REMEDIAL INVESTIGATION

 WORK PLANS  .


 P.  1 - 108     Report: Engineering Investigation at Inactive
                Hazardous Waste Sites in the State of Nev York -
                Phase 1- Preliminary Investigation.  prepared by
                Woodward-Clyde consultants, Inc. September 30,
                1983.

 P.  109 - 216   Report: Final Work  Plan  for RI/FS - Genzale
                Platinc CoTr.cany Site, Franklin Scruare.  N.Y..
                prepared by  E3ASCO,  October, 1988.

 P.  217 - 360   Report: Final Field Operations Plan (TOP] for
                RI/7S - Genzale Platir.e  Cor.oar.v Site,  Franklin
                Scuare. N.Y..  prepared by E3ASCO, October, 1588.

 REMEDIAL INVESTIGATION REPORTS

 P.  361 - 556   Report: Final Remedial Investigation Report,
                prepared by  EBASCO,  Volume  I of  III,  February,
  	  -•--•-.•    1991.   -•••••

 P.  557 - 569   Report: Final Remedial Investigation Report,
                prepared by  EBASCO,  Volume  II of III,  February,
                1991.

 P.  570 - 765   Report:  Final  Remedial Investigation Report,
                prepared by  EBASCO,  Volume  III  of III,  February,
                1991.

 FEASIBILITY  STUDY

 FEASIBILITY  STUDY REPORTS

P. 766 - 968    Report:  Draft  Final  Feasibility  Study Report,
               'prepared by  EBASCO,  February,  1991.

ENFORCEMENT

ADMINISTRATIVE  DECREES          '           •            .

P. 969 -  992A   Memorandum of Decision -  U.S.A.  against  M.  Genzale
                Plating,  Inc.,  Michael Genzale and Pasquale
                Genzale,  October 13,  1989.

-------
 CORRESPONDENCE

 P. 393 - 995   Letter to Mr. Pasquale Genzale,  Genzale Plating
                Corporation,  from Mr. Stephen  Luftig,  U.S.  EPA,
                Re:  Special Notice Letter Pursuant to  Section
                122 (e) - Genzale Plating Site,  Franklin Square.,
                New  York, December 31, 1987.


 PUBLIC PARTICIPATION

 COMMUNITY RELATIONS PLANS

 P. 996 - 1020  Report: Final Ccrjnunitv Relations  Plan For  the
                Genzale Plating Site, Town of  Franklin 5c"uare,  New
                York, prepared by E3ASCO, November,  1SSS.

 FACT SHEETS AND PRESS RELEASES

•'P. 1021 - 1C22' Fact sheet: Genzale Platine Site.  Tovn of
                Hemcstead.  Nassau Cour.tv. NY.  November,  1S89.

 P. 1G23 - 1024 Press Release: U.S. EPA TO HOLD  PUBLIC
                AVAILABILITY SESSION ON G'ENZALE  PLATING  CO.
                SUPERFUND SITE IN FRANKLIN SQUARE. NEW YORK.
                Prepared by, U.S. EPA, November  14,  1589.

 REQUEST FOP. FOIA

 P. 1025 - 1030 Letter to Honorable Raymond J. McGrath,  U.S.
                Congressman, from Mr. William Muszynski, U.S. EPA,
                Re: Request for information,  January 9,  1S89.

 PROPOSED  FLAN
      •
 P.  1031 - 1043 Proposed plan: Genzale Plating Co-canv Site. U.S.
                EPA. Region  II, February,  1991.

-------