United States         Office of
           Environmental Protection    Emergency and
           Agency            Remedial Response
                                EPA/ROD/R02-91/147
                                October 1991
f/EPA
Superfund
Record of Decision
           Global Landfill,  NJ

-------
50272-101
1 REPORT DOCUMENTATION 1. REPORT NO. 2.
I PAGE EPA/ROD/R02-91/147
^ TIBe and Subtitle
^SUPERFUND RECORD OF DECISION
^Global Landfill, NJ
First Remedial Action
7. Au*or(s)
t. Performing Organization Name and Address
12. Sponsoring Organization Nun* and Adckms
U.S. Environmental Protection Agency
401 M Street, S.W.
Washington, D.C. 20460
3. Recipient* Accession No.
5. Report Date .
09/11/91
6.
a Performing Organization Rept No.
10. Pro|ect/Ta«k/Work Unit No.
11. Contract(C) or Grant(G) No.
(C)
(G)
IX Type of Report t Period Covered
800/000
14.
15. Supplementary Note*
16. Abstract (Limit: 200 words)
The 57.5-acre Global Landfill is an inactive solid waste disposal facility in Old
Bridge Township, Middlesex County, New Jersey. The facility is bordered by wetlands
to the northeast, southeast, and southwest, and a former sand borrow pit and wooded
area to the northwest. Land use in the area is primarily residential. Onsite
^   features  include a 51-acre  landfill, a 6.5-acre  northwest landfill  extension, and  an
   inactive  1.7-acre leachate  collection pond.  Municipal water supply wells are located
   approximately 1 mile north  of  the landfill.  From 1968 until its  closure in 1984,  the
   Global Landfill site was used  for non-hazardous  solid waste disposal.   As a result of
   a slope failure in 1984, landfill wastes were exposed, the dyke was breached, and  the
   wastes spilled into an adjacent  wetlands area.   Subsequently, the State ordered all
   onsite disposal operations  to  cease.  From 1988  to 1991, EPA and  State site
   investigations identified 63 buried 55-gallon drums containing hazardous wastes
   including VOCs, organics, and  metals within both the waste mound  and northwest
   extension.   This Record of  Decision (ROD) addresses Operable Unit 1 (OU1), the
   landfill  wastes.  A second  ROD will address possible offsite ground water and surface
   water contamination, and wetland areas, as OU2.   The primary contaminants of concern

   (See Attached Page)
                                           NJ
17. Document Analysis a. Descriptors
  Record of Decision - Global  Landfill,
  First Remedial Action
  Contaminated Media:   soil, sediment
  Key Contaminants: VOCs  (benzene,  PCE, TCE, toluene,  xylenes), other organics, metals
                     (arsenic,  chromium, lead)
  b. tdentifiere/Open-EndedTerm*
   c. COSATI Held/Group
   AvalloblDty Statement
                                                     19. Security das* (This Report)
                                                           None
                                                    20. Security Class (This Page)
                                                    	None	
                                                                             21. No. of Pages
                                                                               168
                                                                              22. Price
(See ANSI-Z39.18)
                                    See bwtructfon* on Rtnnt
OPTIONAL FORM 272 (4-7T)
(Formerly NTIS-35)
Department of Commerce

-------
 EPA/ROD/R02-91/147
 Global Landfill, NJ
  irst Remedial Action
I
 Abstract (Continued)

 affecting the soil and sediment are VOCs including benzene,  PCE,  TCE,  toluene,  and
 xylenes; other organics; and metals including arsenic,  chromium,  and lead.

 The selected remedial action for this site includes capping the landfill with a
 synthetic and clay cap; constructing a soil stabilization berm; constructing and
 operating a gas management system, and stormwater and leachate collection
 systems; pumping leachate and condensate from the gas collection system to a holding
 tank,  and subsequently transporting the waste offsite for treatment and disposal (this
 constitutes an interim remedy for the leachate);  disposing of sludge offsite at a RCRA
 facility; implementing a monitoring program to ensure the effectiveness of the  remedy;
 mitigating any affected wetlands; and implementing site access restrictions such as
 fencing.  Onsite leachate treatment that would replace the offsite leachate treatment
 and disposal provided for in this ROD, may be initiated as part of the ground water
 remedy in the next ROD, which addresses OU2,  as part of the preferred leachate
 management alternative.  This may include treatment using powdered activated carbon,
 nitrification and denitrification, and UV disinfection, followed by discharging the
 treated effluent onsite to the Cheesequake Creek.  The estimated present worth  cost of
 this remedial action is $30,353,200, which includes an annual O&M cost of $865,100 based
 on onsite treatment of leachate.

 PERFORMANCE STANDARDS OR GOALS:  A waiver of the New Jersey Hazardous Waste Landfill
 Closure Regulations will be required on the basis of technical impracticality due to the
^.arge  volume of waste to be removed.  The remedy will meet the appropriate Federal and
•tate  guidelines and requirements for subsurface gas and leachate management systems and
Surface water systems.  No chemical-specific standards were provided.

-------
                          ROD FACT SHEET
 SITE

 Name:
 Location/State:
 EPA Region:
 HRS Score  (date):
 NPL Rank (date):

 ROD

 Date Signed:

 Selected Remedy

 Soils:
Groundwater:
Capital Cost:
O & M:
Present Worth:

LEAD
Global Landfill
Old Bridge Twp., Middlesex Co., New Jersey
II
45.92  (March  '89)
297 (February 91)
September 11, 1991
Restore Landfill Source Control and Stability
through the Construction of a Modified NJDEP
Hazardous Waste Cap.

Leachate Collection from OU-1 will Likely be
Integrated with Off-site Groundwater
Collection and Treatment under OU-2.
$
$
$
21,464,200
   865,100
30,353,200
Remedial, EPA
Primary Contact  (phone):
Secondary Contact  (phone):
        Remedial, State Lead
        Peter Latimer (609-633-1328)
        Edward J. Finnerty (212-264-3555)
WASTE

Type:




Medium:

Origin:
Soil - VOC's, naphthalene, phthalates,
     heavy metals and buried drums.
Groundwater - Elevated levels of BOD, COD,
      and TDS found in the upper aquifer.

Soil, groundwater and wetlands.

Pollution originated as a result of both
deliberate and indirect disposal of hazardous
wastes at the landfill.  Drums and liquid
wastes were also deposited there.

-------
  SEP   6 1991

Record  of Decision for the
Global  Landfill Site

Kathleen C. Callahan, Director
Emergency and Remedial Response Division  (2ERRD)

Constantino Sidamon-Eristoff
Regional Administrator (2RA)


Attached for your approval is the Record of Decision  (ROD) for
the Global Landfill site, Middlesex County, New Jersey.

The selected remedial action represents the first of two planned
operable units for the site, and is a response action to
institute on-site controls for the landfill.  NJDEP has initiated
an RI/FS at Global Landfill for the second operable unit, to
determine the nature and extent of migration of contaminants from
the site into the groundwater, surface water, and wetland areas,
and to  evaluate remedial alternatives.

Both EPA and the New Jersey Department of Environmental
Protection (NJDEP) have determined that a modified NJDEP
hazardous waste cap is the most appropriate remedy for addressing
source  control at the Global Landfill site.  The remedy involves
capping of the landfill in accordance with State and Federal
requirements, slope stability enhancement through construction of
a soil  stabilization berm, construction and operation of a gas
management system, construction and operation of stormwater and
leachate management systems, installation of a perimeter security
fence to restrict access to the site, and implementation of a
monitoring program to ensure the effectiveness of the remedy.
The preferred leachate treatment option is on-site treatment with
discharge to surface water, however disposal of the leachate at
an industrial waste treatment plant will be employed until the
RI/FS for the second operable unit is completed.

The estimated present worth for all tasks associated with the
selected remedy (with Leachate Option 3) is $30,353,200.

The results of the FS and the Proposed Plan for the site were
released to the public on February 19, 1991.  The public comment
period  extended from this date until May 6, 1991.  NJDEP
conducted a public meeting on March 12, 1991, and a public
information session on March 13, 1991.  A few written comments on
the FS  and Proposed Plan were received from the community; they
were generally supportive of the proposed remedial actions.  In

-------
addition, the potentially responsible parties submitted extensive
comments questioning the proposed remedial actions.

The attached ROD was developed by EPA, and has been reviewed by
NJDEP and the appropriate program offices within Region II.
Their input and comments are reflected in this document.

If you have any questions concerning this ROD, I will be happy to
discuss them at your convenience.

Attachment

-------
                        _.		      OF
9. 10.  91


                                            STATE OF NEW JERSEY
                                      DEPARTMENT OF ENVIRONMENTAL PROTECTION
                                           •OOrr A. WBNEft, COMMISSIONER
                                                  CN402
                                             TRENTON, NJ. M825-0402
                                                (609) 292-2185        "_-
                                               PM: (609) 914.3962
    Mr. Constantine sidamon-Eristoff                    june 27, 1991
    Regional Administrator
    USEPA - Region XI
    Jacob K. Javits Federal Building
    New York, KY  10276

    RE;  Global Landfill Project,  Operable Unit 1
         Record of Decision Concurrence Letter


    The  Department  of  Environmental  Protection has  evaluated  and
    concurs with  the  selected remedy  for operable  Unit fl for  the
    Global Landfill superfund Site outlined belowt

         The  selected  remedy  represents the first  of  two planned
         operable units  for  the  site.   It  involves  cappping  the
         landfill in accordance with State and Federal requirements.
         A subsequent  decision document will  address the remediation
         of groundvater, surface waters and wetland areas surrounding
         the site.

         The  major  components of the  selected  remedy  include  the
         following:

         " capping the  landfill with a  modified hazardous waste cap;
         - Slope  stability enhancement  through construction  of  a soil
           stabilization barm;
         - construction and operation of a gas management system;
         - Construction and operation of stormwater and leachate
           management systems;
         - Installation of a perimeter  security fence to restrict
           access to the eite;  and
         - Implementation  of a  monitoring program to ensure  the
           effectiveness of the remedy.

    The Department  reserves its final comments en the complete  Record
    of  Decision  pending  an  opportunity  to  review  the   completed
    documents, including the document's Responsiveness Summary.


                                           Sincerely,
                                           Scott A. Weiner
                                           Commissioner
                        Ntw Jirtty it an Equal Opportunity Empioytr

-------
                      DECLARATION STATEMENT

                        RECORD OF DECISION

                         GLOBAL LANDFILL
SITE NAME AND LOCATION

Global Landfill
Township of Old Bridge, Middlesex County, New Jersey


STATEMENT OF BASIS AND PURPOSE

This Record of Decision presents the selected remedial action for
the Global Landfill Superfund site, chosen in accordance with the
requirements of the Comprehensive Environmental Response,
Compensation, and Liability Act of 1980, as amended by the
Superfund Amendments and Reauthorization Act of 1986 and, to the
extent applicable, the National Oil and Hazardous Substances
Pollution Contingency Plan of 1990.  This decision document
serves to explain the factual and legal basis for selecting the
remedy for the site.

The State of New Jersey concurs with the selected remedy.
Information which supports the remedy can be found within the
administrative record for the site.
ASSESSMENT OF THE SITE

Actual or threatened releases of hazardous substances from this
site, if not addressed by implementing the response action
selected in this Record of Decision, may present an imminent and
substantial endangerment to public health, welfare, or the
environment.
DESCRIPTION OF THE REMEDY

The remedial action described in this document represents the
first of two planned operable units for the site.  It involves
capping of the landfill in accordance with State and Federal
requirements.  A subsequent decision document will address the
remediation of groundwater, surface waters and wetland areas
surrounding the site.

-------
   The major components  of the  selected remedy include the
   following:

             Capping  of  the  landfill with a modified hazardous waste
             cap;

        •     Slope  stability enhancement through construction of a
             soil stabilization berm;

        •     Construction and operation of a gas management system;

        •     Construction and operation of stormwater and leachate
             management  systems;

             Installation of a  perimeter security fence to restrict
             access to the site; and

        •     Implementation  of  a monitoring program to ensure the
             effectiveness of the remedy.


   STATUTORY DETERMINATIONS

   The selected remedy is protective of human health and the
   environment, and is cost-effective.  With the exception of cap
   construction, the  selected remedy complies with Federal and State
   requirements that  are legally applicable or relevant and
   appropriate to the remedial  action.  The remedy utilizes
   permanent solutions and alternative treatment technologies to the
   maximum extent practicable for this site.  However, because
   treatment of the entire contents of the wastefill was not found
   to  be practicable, the statutory preference for treatment as a
   principal element  of the  remedy will not be completely satisfied.
   This action does not constitute the final remedy for the site.
   Subsequent actions are planned to fully address the remaining
   principle threats  posed by the site.

   Because the remedy will result in low levels of .hazardous
   substances remaining on the  site above health-based levels, a
   review will be conducted  within five years after commencement of
   the remedial action to ensure that the remedy continues to
   provide adequate protection  of human health and the environment.
^Constantine Sidamon-Erls^bff                 Date I
  Regional Administrator/
  EPA Region II      ' c  '

-------
         RECORD OF DECISION




          DECISION SUMMARY




    GLOBAL LANDFILL SUPERFUND SITE




OLD BRIDGE TOWNSHIP,  MIDDLESEX COUNTY




             NEW JERSEY

-------
                        TABLE OF CONTENTS

SECTIONS                                                     PAGE

Site Location and Description                                   1
Site History and Enforcement Activities                         2
Highlights of Community Participation                           3
Scope and Role of the First Operable Unit                       4
Summary of Site Characteristics                                 4
Summary of Site Risks                                           9
Description of Alternatives                                    12
Summary of Comparative Analysis of Alternatives                18
Selected Remedy                                                25
Statutory Determinations                                       26
Documentation of Significant Changes                           28

Appendices
Appendix A.    Figures
Appendix B.    Tables

-------
                         DECISION SUMMARY

                        RECORD OF DECISION

                         GLOBAL LANDFILL


SITE NAME. LOCATION. AND DESCRIPTION

The Global Landfill site is a landfill located on Lots 10, 25.12
and 26, Block 4185, in Old Bridge Township, Middlesex County, New
Jersey  (Figure 1).  The northeastern property line is also the
municipal boundary between Old Bridge Township and the Borough of
Sayreville.  The site is bordered by wetlands to the northeast,
southeast, and southwest, in the drainage basin of Cheeseguake
Creek.  The creek is located approximately 900 feet southeast of
the landfill, drains to the northeast, and enters the Raritan Bay
approximately 9,000 feet northeast of the site. On the opposite
side of the creek is Cheeseguake State Park.  The Garden State
Parkway is located 2,700 feet east-northeast of the landfill.
Immediately to the northwest, the site is bordered by a former
sand borrow pit.  An active 42-inch gas pipeline is located
approximately four feet beneath the original ground level, at the
base of the landfill's northwestern toe of slope.  This pipeline
is owned by the Transcontinental Gas Pipe Line Company (Transco).

Residential areas of Old Bridge Township and the Borough of
Sayreville are north and west-northwest of the site,
respectively, and include several apartment complexes, as well as
single-family homes, located off of Westminster Boulevard and
Ernston Road.  The apartments are approximately 900 to 2400 feet
from the site, with the intervening area consisting of either the
previously mentioned borrow pit or a wooded area.  The nearest
single-family homes are located in Sayreville, approximately 500
feet north of the site.  The nearest municipal water supply wells
are located approximately one mile north of the landfill.  They
are located upgradient from groundwater flow, and are not
believed to be impacted by the site.

The Global Landfill site is approximately 57.5 acres in size, and
consists of two areas, a 51-acre main section and a 6.5-acre
northwest extension (Figure 2).  The main section of the landfill
consists of a mound ranging from 5 to 15 feet above mean sea
level (MSL) at its base, to approximately 90 to 108 feet at the
top.  The top of the mound area (above elevation 90) is
approximately 11-12 acres,  with the remaining area of the mound
consisting of sideslope.  The top of the mound slopes generally
to the southeast, however,  localized variations in grade occur,
resulting in flat areas or depressions that periodically contain
standing water.  The mound has a volume of approximately
2,400,000 cubic yards.  The northwest extension of the landfill
begins at the northwestern toe of slope of the mound area, and
extends across the Transco pipeline right-of-way to the northwest

-------
property line of lot 25.12.  Elevations in the northwest
extension range from 8 to 32 feet above MSL.  The volume of waste
material in the northwest extension is estimated to be 160,000
cubic yards.

Elevations in the adjacent wetlands area are between 3 to 6 feet
above MSL.  Mean high tide in the wetlands and Cheeseguake Creek
is approximately elevation 4 feet above MSL.  The 100-year and  .
the 500-year tidal floods in Cheeseguake Creek are approximately
elevation 12 feet and 15.5 feet above MSL, respectively.


SITE HIBTORY AND ENFORCEMENT ACTIVITIES

The Global Landfill site was used for solid waste disposal from
approximately 1968 to 1984.  The landfill was operated by Global
Landfill Reclaiming Corporation (GLRC), and was permitted to
accept waste classified by the State of New Jersey as ID-10
(municipal waste), ID-13 (bulky waste), ID-23 (vegetative waste),
and ID-27 (non-hazardous industrial waste).

In April 1984, a slope failure occurred on the southeast side of
the landfill, opening a fissure approximately 60 feet wide, 600
feet long and 40 feet deep.  Rapid filling of the eastern portion
of the landfill followed by a period of heavy rainfall, and
excessive high tides in the surrounding wetlands, were reported
to be the principal factors contributing to the failure.  The
failure exposed landfill wastes, breached the perimeter dike, and
filled a large portion of the adjacent wetlands with waste.
Subsequently, the failure area was filled, regraded and topped
with a thin soil cover.  NJDEP ordered the GLRC to cease disposal
operations at the landfill on April 27, 1984, in an order to show
cause filed in the Superior Court of New Jersey, Middlesex
County.  Since that time, the landfill has been inactive.

GLRC was ordered to establish an escrow account for closure of
the landfill, and on April 23, 1986, the Superior Court of New
Jersey, Middlesex County, appointed an Administrator to oversee
the closure fund.  Later in 1986,  the Administrator of the
closure fund authorized the consulting firm of E.T. Killam
Associates of Millburn, New Jersey, to conduct "an investigation
at the site.  A slope stability study was performed which showed
that the sideslopes adjacent to the wetlands generally do not
meet acceptable safety levels.

Witnesses have alleged that large numbers of drums containing
hazardous waste were also disposed of at the landfill, both in
the 51-acre mound area and the 6.5-acre northwest extension.
These allegations led to an exploratory excavation of the 6.5-
acre northeast tract by Killam Associates in March 1988.  Drums
of hazardous waste were encountered during the excavation.

-------
The site was placed on the Environmental Protection Agency's
National Priorities List  (NPL) in March 1989 and became eligible
for action under the Comprehensive Environmental Response,
Compensation and Liability Act (CERCLA).  Killam Associates was
authorized by NJDEP and the Administrator of the closure fund to
prepare a Feasibility Study (FS)  to evaluate alternatives for on-
site controls at the site, prior to completion of a remedial
investigation and feasibility study (RI/FS).

A search for Potential Responsible Parties (PRPs) has also been
conducted.  New Jersey Spill Act Directives were issued by NJDEP
on August 18, 1989 and March 21,  1991, to a total of 52
respondents.  The Directives ordered the respondents to pay for
the ongoing RI/FS, and all future remedial actions required at
the site.  In addition, the Environmental Protection Agency (EPA)
has issued General Notice letters to 24 respondents, notifying
them of their potential liability with respect to the site.

In June 1991, NJDEP negotiations with a group of respondents
known as the Global Landfill PRP Group, resulted in the funding
of the RI/FS for operable unit two (OU-2), in accordance with the
Spill Act Directives.  In addition, several suits were filed by
residents in the vicinity of the Global Landfill, and have been
consolidated under Bernard Lamb,  et al. vs. Global Landfill
Reclaiming, Inc., et al.) in the Superior Court of New Jersey,
Middlesex County (Docket No. w-15349-88).


HIGHLIGHTS OF COMMUNITY PARTICIPATION

The FS report and a Proposed Plan for the Global Landfill site
were released for public comment on February 19, 1991 by NJDEP.
These two documents were made available to the public in the
administrative record information repositories maintained at
NJDEP in Trenton, EPA Region II Docket Room in New York City, and
at the Old Bridge Public Library.  A notice of availability for
these two documents was published in the Central New Jersey Home
News,  on February 19, 1991.  A public comment period on the
Proposed Plan was held from February 20, 1991 to May 6, 1991.

A public meeting was held on March 12, 1991.  At this meeting,
representatives from EPA and NJDEP answered questions about
problems at the site and the remedial alternatives under
consideration.  Following the public meeting, a public
information session was held on March 23, 1991.  A response to
the comments received during the public comment period is
included in the Responsiveness Summary, which is part of this
Record of Decision (ROD).  This decision document presents the
selected remedial action for the Global Landfill Superfund site
under CERCLA, as amended by the Superfund Amendments and
Reauthorization Act (SARA) and, to the extent practicable, the
National Oil and Hazardous Substances Pollution Contingency Plan

-------
 (NCP).  The decision for this site is based on information
 contained within the administrative record.
SCOPE AND ROLE OF THE FIRST OPERABLE UNIT

The NJDEP in consultation with EPA, has organized the remedial
work into two planned actions/ which are referred to as operable
units.  This ROD addresses the first operable unit (OU-1) for the
site, which is a response action to institute on-site controls
for the landfill.  The principal threats associated with the site
relate to the buried drums of hazardous waste in the landfill. In
addition, there is an unacceptable factor of safety related to
the stability of the southeast sideslope of the landfill which
threatens the adjacent wetlands.  The overall objective of this
action is to contain contaminants at the site, and limit exposure
to levels protective of human health and the environment.

The NJDEP has also initiated a comprehensive RI/FS at Global
Landfill (OU-2).  This RI/FS will determine the nature and extent
of the migration of contaminants from the site into nearby
surface water and groundwater, and will evaluate alternatives to
address this contamination.  Selection of a remedial alternative
for the OU-2 action will take place at a later date.


SUMMARY OF SITE CHARACTERISTICS

When the landfill ceased operations in 1984, it was closed with
only a thin soil cover.  Vegetative cover over most of the site
is sparse to non-existent.  As a result, the soil cover is
eroding, forming gullies in the sideslopes, and exposing waste
materials across the surface of the site.  The height of the
landfill, the steepness of the sideslopes, the characteristics of
the underlying soils, and the nature of the fill, indicate that
the landfill is marginally stable.  Slope movement (creep) of the
southeast sideslope will continue until engineering controls are
implemented.

Solid Wastes and Buried Drums

A total of 63 drums were discovered during the drum excavation in
March 1988, 18 of which were removed for sampling and analysis.
The drums,  all of 55-gallon capacity, contained wastes of varied
color and consistency.  The drums were generally in poor
condition,  having been previously crushed or corroded.  Their
contents included solids and sludges; one drum contained liquids.
Table 1-A presents the results of Priority Pollutant analyses
performed on the contents of the drums.  The table lists only the
compounds which were detected in the samples.

-------
Volatile organic compounds present in the samples ranged in
concentration from 49.2 milligrams per kilogram (mg/kg) (1,3
dichlorobenzene) to 4,890 mg/kg (carbon tetrachloride).  The
predominant volatile organic compounds present included xylene,
toluene, and ethylbenzene.  Base-neutral extractable organic
compounds in the samples ranged in concentration from 126 mg/kg
to 70,900 mg/kg.  Bis  (2-ethylhexyl) phthalate, naphthalene and
di-n-butylphthaiate were the principal base-neutral extractable
organic compounds present.  The predominant metals present
included arsenic, chromium, copper, lead, nickel and zinc.  Of
the 18 drums sampled, 11 contained hazardous waste based on EPA
limits.  An additional three drums contained hazardous waste
based on NJDEP limits.  Table 1-B contains a summary of the drum
wastes which fail Resource Conservation and Recovery Act (RCRA)
characteristics and, therefore, are considered hazardous waste.

The feasibility of additional drum removal in the northwest
extension of the landfill will be determined as part of the
remedial design activities.

Groundwater

Groundwater in the vicinity of Global Landfill is classified as
Class GW-2 under New Jersey Administrative Code (NJAC 7.9-6.5).
There are 15 active groundwater monitoring wells at the site.
The boring logs indicate that at the southeast limit of the
landfill, the site is generally underlain by two to ten feet of
meadow mat (an organic-rich horizon comprised of clays, silts,
sands, and decomposed vegetation that is generally representative
of. a water saturated environment,  such as a swamp or marsh), and
25 to 35 feet of dark gray silty clay, identified as the Amboy
Stoneware Clay member of the Raritan Formation.  Beneath the clay
is the old Bridge Sand member of the Raritan Formation, a
municipal water supply source for Old Bridge Township and several
other communities.

The meadow mat layer decreases in thickness in a northwesterly
direction, and is absent upland of the landfill.  The Amboy
Stoneware Clay also thins in a northwesterly direction.  In the
vicinity of the Transco gas pipeline, it is either replaced by,
or grades into, one to two feet of light tan to gray clay layer.
The Amboy Stoneware Clay serves as a confining layer between the
landfill and the Old Bridge Sand,  however, in the northwestern
section of the landfill, it may be locally absent.  The absence
of this confining layer between the Old Bridge Sand and water
table aquifer may provide a pollutant pathway to the potable
water aquifer.  A hydraulic conductivity of 125 feet per day in
the Old Bridge Sand aquifer has been reported by the United
States Geological Survey.

Eight of the fifteen groundwater monitoring wells at the site are
screened in the water table aquifer in sands above the clay

-------
layer.  Seven of the wells are screened in the Old Bridge Sand
beneath the clay.  The direction of groundwater flow at the site
is generally to the southeast, both in the water table aquifer
and in the Old Bridge Sand.  The shallow groundwater flow
direction may be influenced by mounding of groundwater within the
landfill.  Infiltration of precipitation may contribute to
mounding of groundwater below the landfill surface, and thereby
contribute to leaching and off-site migration of hazardous
substances.  Mounding effects will continue to occur until a
proper cap and stormwater runoff controls are implemented to
prevent precipitation from entering the site in the future.
Water level measurements indicate that the Old Bridge Sand is
under confined or artesian conditions.  An upward vertical
gradient is greatest in the southeastern section of the landfill,
where the clay layer is thickest, and less in the northwestern
part of the site, where the clay layer thins or disappears.

Groundwater data presented in the FS was obtained from monitoring
wells which have been sampled quarterly since October 1987, as
required under a New Jersey Pollution Discharge Elimination
System (NJPDES) permit issued to Global Landfill.

Data shown in Tables 2-A, 2-B, 2-C indicates that the landfill
has adversely impacted groundwater in the area.  Many
contaminants identified in the landfill leachate and in the drums
excavated from the landfill, have been detected above maximum
contaminant levels (MCLs) in the downgradient groundwater.  MCLs
are generally "at the tap" or "point of use" standards.

Typical leachate indicator parameters such as Biological Oxygen
Demand (BOD), Chemical Oxygen Demand (COD), iron, chlorides,
total dissolved solids (TDS), and ammonia nitrogen are at
elevated levels in the shallow groundwater aquifer.  Several of
the shallow monitoring wells have shown a general trend of
increasing concentration for these leachate parameters from
October 1987 to April 1990.

Table 2-A presents a comparison of downgradient and upgradient
groundwater quality in the shallow aquifer.  Groundwater quality
criteria are based on State and Federal MCLs, and New Jersey GW-2
groundwater quality standards.  These data demonstrate the
landfill's impact on groundwater quality in this aquifer.
Contaminants not detected in upgradient wells were found at
levels above their MCLs in the downgradient wells.  For example,
in the downgradient wells, benzene and chlorobenzene were
detected above MCLs in 39 of 45, and 42 of 45 samples,
respectively, and were not detected in upgradient wells.
Similarly,  acenaphthene,  1,2 dichlorobenzene, heptachlor,
cadmium,  hexavalent and total chromium were detected above MCLs
in the downgradient wells.

-------
Table 2-B, a comparison of groundwater quality in the deep wells
 (Old Bridge Sand aquifer), indicates that the landfill also has
impacted groundwater in the Old Bridge Sand aquifer.  For
example, cadmium, total chromrom, lead, benzene, chlorobenzene,
trichloroethene, and vinyl chloride exceed MCLs in the
downgradient wells, and were not detected in the upgradient
wells.

During the March 1988 drum investigation, two samples of
groundwater, pumped from the trenches during dewatering
operations, were sampled and analyzed for Priority Pollutant
organics and metals.  The data, summarized in Table 2-C, reveal a
similar spectrum of compounds to those encountered in the shallow
groundwater.

Leachate

Leachate seeps and ponded leachate have been frequently observed
at the landfill.  These surface exposures of leachate are most
often observed at the toe of slope, but have also been noted at
higher elevations on the landfill sideslopes.  At the present
time, there are no measures in place for leachate collection and
disposal.  A 1.75-acre leachate collection pond was previously
constructed at the southern corner of the landfill, and a
leachate collection well was installed through the top of the
landfill in July 1985.  However, neither of these facilities is
currently in operation.

As part of a NJPDES quarterly monitoring program, leachate
samples from exposed seeps have been collected for analysis from
October 1987 to April 1990.  The average flow rates for
individual seeps ranged from 0.08 gallons per minute (gpm) to 3.5
gpm, while the total average leachate seepage flow from the site
is 5.5 gpm (8000 gallons per day).  This flow represents only
surface leachate seeps that are exposed at the toe of the slope
or on sideslope areas.

Since 1987, concentrations of leachate indicator parameters (BOD,
COD, ammonia, chlorides, TDS, hardness and iron) were found to be
elevated.  Certain heavy metal compounds (including lead and
cadmium) have been detected in the leachate above MCLs.  Volatile
organics detected in the leachate consisted primarily of benzene-
related compounds, with chlorobenzene concentrations up to 4,600
micrograms per liter (ug/1).  Benzene, chlorobenzene, and xylene
exceeded MCLs, respectively, in 24, 28, and 14 of the 50 samples
analyzed.  Table 3 compares leachate data with groundwater
quality standards and illustrates the potential impact the
leachate is having on the groundwater and wetlands.

-------
 Surface Water and Wetlands

 Cheesequake Creek has been classified as a saline SE-1 surface
 water under the NJAC Surface Water Quality Standards.  Surface
 waters within Cheesequake State Park are classified as Category
 One waters, which are considered non-degradable.  In addition,
 Global Landfill is bordered on three sides by wetlands.  Surface
 drainage on the northeast, southeast, and southwest sides of the
 mound area of the landfill is into the adjoining wetlands.  On
 the northwest side, surface drainage from the landfill mound is
 into the northwest extension, and then southwest into the
 wetlands.  Currently, the wetlands are subject to several
 discharges from the landfill, including stormwater runoff,
 surface leachate seeps, and contaminated shallow groundwater.

 In October 1986, NJDEP sampled surface water at two locations
 adjacent to the landfill (one sample in Kelvin's Creek, and one
 at an unspecified location on the southwest side of the
 landfill), and analyzed them for Priority Pollutants.  These data
 are presented in Table 4-A.  In October 1987, additional surface
 water sampling was performed at ten locations in the vicinity of
 the landfill (Table 4-B).

 Table 4-C summarizes the data from the two sampling events, and
 compares them'to NJDEP Surface Water Quality standards for
 estuarine waters (NJAC 7:9-4.14(c)), and with NJPDES Criteria for
 Protection of Salt Water Aquatic Life (NJAC 7:14A-appendix F).
 Concentrations of cadmium, copper, nickel, silver, and zinc
 exceeded the NJPDES Criteria for Protection of Salt Water Aquatic
 Life.  With regard to surface water quality, standards for the
 pesticides, lindane and DDT, were exceeded.

 These data are insufficient to establish background water quality
 in the wetland areas, and to determine what impact the landfill
 is having on those areas.  However, the compounds detected above
 NJPDES standards are present in both the leachate and groundwater
 that discharges into the wetlands.  These discharges provide a
 potential threat to the wetlands.  The nature and extent of
 contaminants in the wetland areas will be characterized during
 the RI/FS for OU-2.

Air

 Limited air monitoring data are available, and therefore cannot
be compared with State or Federal air quality standards.
Monitoring of ambient air for organic vapors suggests that the
 organic gasses emitted from the landfill consist primarily of
methane.   No gas analyses for specific organic compounds have
been performed.

 Subsurface methane migration has occurred beyond the northwest
property line.   However, methane was not detected at a distance

-------
 of  500  feet  from the toe of slope, and did not extend to the
 adjacent residential areas at the time of the field
 investigation.  Odor generation has been a significant nuisance
 problem in the vicinity of the landfill, vith odors being
 detected in  the residential areas and as far away as the Garden
 State Parkway, 2700 feet to the east-northeast.

 Although no  specific toxic compounds have been identified in the
 air emissions from the landfill, there exists the potential of a
 public  health risk via the air pathway.  Air and gas quality
 monitoring will be performed during the RI/FS for OU-2, and will
 be  incorporated into the design of the gas management system
 (OU-1).

 Transcontinental Gas Pipeline

 Transco owns a 42-inch natural gas pipeline that lies between the
 northwest extension and the main portion of the landfill.  The
 pipeline is  located approximately four feet beneath the original
 ground  level, within a 75-foot easement that runs through the
 landfill proper.  Approximately five to fifteen feet of refuse
 have been deposited on the Transco easement.  Discussions are
 currently underway between representatives of Transco and NJDEP
 regarding the feasibility of relocating the pipeline to an area
 beyond  the extent of the proposed cap.  This would have the
 desired effect of isolating the pipeline from the possible
 corrosive effects of contaminated groundwater and leachate
 beneath the  landfill.  This action would also prevent post-
 construction damage to the cap, should repairs to the pipeline
 become  necessary.


 SUMMARY OF SITE RISKS

 Human Health Assessment

 When Global Landfill ceased operations in 1984, it was improperly
 closed with only a six-inch soil cover.  The lack of a proper
 cover at the landfill creates a number of potential pathways for
 exposure.   The failure of the southeast east sideslope also
 created on- and off-site potential pathways for exposure through
 direct  contact with, or ingestion of, contaminants present in the
 exposed refuse.   Potential hazards also exist through the
 inhalation of contaminated airborne particulates migrating from
the exposed refuse.  Also, the migration of landfill gas
 emissions can act as carrier gasses for volatile and semi-
volatile organic compounds present in the refuse.

The discovery of drums in the northwest area of the landfill,
 containing hazardous waste, support allegations that drums were
 also disposed of in the main landfill area.  A possibility exists
that these drums have and may continue to release hazardous waste

-------
                                10

into the environment.  Leachate generated from the infiltration
of rainwater significantly increases the mobility of contaminants
present in the landfill.  Additionally, the potential frr direct
contact with the leachate seeps present on the surface of the
landfill also exists.

Sixteen potential exposure pathways were evaluated in the FS, ten
of which were determined to be complete pathways, as defined by
the following exposure pathway elements:

          A source and mechanism of chemical release in the
          environment,
     •    A transport medium,
          A point of potential environmental or human exposure,
     •    An exposure route at the point of contact.


The ten complete pathways for the Global Landfill site are:

           1.  Inhalation of contaminated ambient outdoor air,
                    off-site;
           2.  Inhalation of contaminated ambient outdoor air,
                    on-site;
           3.  Inhalation of contaminated ambient indoor air;
           4.  Ingestion of garden produce contaminated by
               ambient outdoor air;
           5.  Ingestion of contaminated windblown particles
               deposited onto back yard soils;
           6.  Ingestion of contaminated windblown particles
               deposited onto indoor surfaces;
           7.  Ingestion of contaminated particles and liquids
               on-site;
           8.  Dermal contact with contaminated windblown
               particles deposited onto back yard soils;
           9.  Dermal contact with contaminated windblown
               particles deposited onto indoor surfaces; and
          10.  Dermal contact with contaminated particles and
               liquids on-site.

Exposures to site-related contaminants through the above pathways
were not quantified.  However, in accordance with CERCLA guidance
on municipal landfills (Conducting Remedial Investigations/
Feasibility Studies for CERCLA Municipal Landfill Sites, February
1991,  OSWER Directive 9355.3-11), where established standards for
one or more contaminants in a given medium are clearly exceeded,
the basis for taking remedial action is warranted.  Many
contaminants in the Old Bridge aquifer, a source of public water
supply, were detected at levels in excess of MCLs.  Metals
(cadmium,  chromium, and lead), and volatile organic compounds
(chlorobenzene, benzene, and vinyl chloride), were all detected
in excess of MCLs.  The presence of these hazardous substances at
levels above MCLs poses a potential future threat to public

-------
                                11

health, and may prevent groundwater near the site from being used
as a potable water supply.

In an effort to qualitatively assess public health issues, the
mean landfill-associated concentration of each substance in
shallow groundwater was compared with State and Federal
groundwater protection standards.  In addition, the estimated
overall concentrations of each substance, including groundwater,
leachate, and drummed waste, were also compared with State and
Federal groundwater standards.

Substances of concern identified through this analysis are
presented in Table 5.  The data shown in this table has been
revised to update and correct the MCL standards presented in the
FS.  Nine substances are of concern based upon comparison of mean
groundwater concentrations with State and Federal standards.
They are ammonia nitrogen (641 x MCL), iron (56.7 x MCL),
chlorobenzene (41.0 x MCL), sodium (36.8 x MCL), benzene  (21.0 x
MCL), chloride (37.7 x MCL), heptachlor  (4.08 x MCL), aldrin
(2.22 x MCL) and total chromium (1.45 x MCL).  However, it is
likely that the concentrations of chloride and sodium are
influenced by background tidal conditions.  Based on the
comparison of leachate and drummed waste with State and Federal
MCLs, 30 pollutants are of concern, including eleven metals, five
substituted alkane and alkene hydrocarbons, and five
miscellaneous substances.

The environmental data collected at and near Global Landfill lead
to a number of conclusions which support the need for remedial
action at the site.  As previously stated, groundwater data
collected to date reveals that groundwater quality beneath this
site exceeds MCLs for numerous hazardous substances, pollutants
and contaminants.  Many of these hazardous substances were
detected in drums buried at the landfill, and in leachate flowing
out of the fill material.  The migration of these substances from
the landfill into the underlying aquifers, and possibly into the
nearby surface waterways will continue unless remedial actions
are implemented.

Actual or threatened releases of hazardous substances from this
site, if not addressed by the preferred alternative or one of the
other active remedial measures considered, may present a current
or potential threat to the public health, welfare, and the
environment through the continued leaching of contaminants from
the landfill.

Environmental Assessment

As previously mentioned/ the wetlands are subject to several
discharges from the landfill, including stormwater runoff,
surface leachate seeps, and contaminated shallow groundwater.  In
September 1990,  Killam Associates conducted a wetland delineation

-------
                                12

study which evaluated potential wetland losses and mitigation
requirements associated with the capping alternatives.  The
result of the study, presented in Appendix L of the FS report,
concludes that the proposed remedial activities will disturb the
wetland fringe along the base of the landfill.  The study also
concludes that mitigation of impacted wetlands will be required.
A wetland mitigation report will be prepared in conjunction with
the design of the selected remedial alternative.

In addition to the delineation, a Wetland Evaluation Technique
(WET) 2.0 analysis was conducted, and provides preliminary
information regarding the functions and values of the wetland
habitat in, and adjacent to, the Global Landfill site.  The WET
was prepared as a supplement to the OU-1 FS report.  The WET
identifies areas in which further data collection is required,
and provides a basis for evaluating potential wetland losses and
mitigation requirements associated with remedial activities at
the site.  The WET recommends sampling parameters utilizing
quantitative data collection techniques, in order to gain a
useful and workable inventory of existing wildlife resources.
Also, a quantitative wildlife survey should be performed prior to
the design of on-site controls, or specification of mitigation
requirements for the site.


DESCRIPTION OF ALTERNATIVES

The goals of the remedial action are to prevent, reduce, or
control the migration of contaminants from the landfill.
Treatment or removal alternatives that reduce toxicity, mobility,
or volume are preferred.  However,  it has been estimated that
removal of waste in the main portion of the landfill would
require bulk excavation of approximately 2,500,000 cubic yards of
landfill material.  Removal of waste in the northwest extension
area would require excavation of approximately 160,000 cubic
yards.  Because of the variability and volume of wastes
encountered at the landfill, excavation and/or treatment is
economically and technically infeasible, and was not considered
further.  Containment of potentially contaminated soil and waste
at the landfill involves the placement of an impermeable cover
over the existing fill material.  Containment technologies are
proven to be an effective and reliable means of protecting human
health and the environment against direct contact and migration
of contaminants from landfills.

In preparing the FS, a wide range of remedial technologies were
identified and initially screened for effectiveness,
implementability, and cost.  Those alternatives which passed this
screening process were further evaluated for incorporation into
the on-site containment alternatives discussed below.  Each
capping alternative, with the exception of the "No Action"
alternative,  would include the following technologies:

-------
                         -;'.      13   : i

          construction of a clay-based or composite cap;
          slope stability enhancement by construction of a
          stabilization berm;
          construction of a gas collection/treatment system;
          construction of a stormwater management system;
          construction of site access controls; and
          implementation of a program to monitor movement of the
          landfill sideslopes.

Each alternative assumes .operation and maintenance (O&M) over a
thirty-year period of time.  The estimated annual O&M costs, and
the estimated capital construction costs, are presented along
with the calculated estimated present worth cost.

The conceptual gas collection and treatment system consists of an
interior and perimeter active gas collection system", and
treatment of the gasses by flare or thermal oxidation.  Future
sampling will be conducted at the site to analyze the gas
emissions.  This information will be used during the design of
OU-1 to determine the proper choice of gas treatment.

While each of the five capping alternatives propose a specific
berm configuration, the final design of the berm will be
determined during the design of OU-1, and will take into account
all specific design parameters necessary to achieve an adequate
short and long-term factor of safety.  The extent of the berm
will also be determined during the design.

In addition to the above components, there are three options for
leachate collection and treatment.  These options will be
discussed under the section entitled "Leachate Treatment
Options".  The costs for the leachate system options are listed
separately, and are not included in the cost estimates for the
individual capping alternatives.

Alternative 1:  No Action

Estimated Capital Cost:            $0
Estimated Annual O&M Cost:         $210,000
Estimated Present Worth:           $3,228,000 .

CERCLA requires that the evaluation of a "No Action" alternative
be considered at each site, to serve as a point of comparison
with other remedial action alternatives.  Under this alternative,
the landfill would remain in its current condition.  No
remediation measures would be implemented.  However, NJPDES
groundwater monitoring program would be continued for 30 years.
The expense for this monitoring is shown as the annual O&M cost.
This program would consist of quarterly sampling of the 15 wells
which surround the site, in order to monitor contaminant
migration.  The samples would be analyzed for EPA priority
pollutants plus selected indicator parameters.  Also, the

-------
                                14

 condition of the wells would be inspected on a weekly basis.  No
 other action is proposed under this alternative.  Because this
 alternative does not entail contaminant removal, CERCLA requires
 that a review of site conditions be conducted every five years.

 Alternative 2:  NJDEP solid Waste Cap

 Estimated Capital Cost:            $16,915,000
 Estimated Annual O&M Cost:         $489,000
 Estimated Present Worth:           $23,722,000
 Estimated Construction Periods     l*j years

 This alternative would incorporate requirements for capping a
 solid waste landfill, in accordance with the NJAC 7:26-2.9.
 Using these guidelines, the following cap was developed:

          12" vegetative topsoil
          12" sand drainage
          12" clay (with permeability of 1 x 10'7 cm/sec)

 This cap would have an overall thickness of three feet, and a
 unit weight of 450 pounds per square foot (psf).  The
 construction of this cap would require a stabilization berm in
 Zone 1 (Figure 2) in order to achieve an acceptable factor of
 safety for sideslope stability.  The Zone 1 stabilization berm
 would consist of a soil embankment that would be constructed
 along the toe of slope of the landfill for a length of
 approximately 1000 feet.  The berm would be placed along the
 entire southeast sideslope in the former sideslope failure area,
 and would have 3:1 to 3.5:1 sideslopes.  The top width would be
 approximately 50 feet, with a top elevation of about 20 feet
 above MSL, or 15 feet above the adjacent wetlands.

 Alternative 3:  NJDEP Hazardous Waste Cap

 Estimated Capital Cost:            $30,190,000
 Estimated Annual O&M Cost:         $581,900
Estimated Present Worth:           $38,420,000
Estimated Construction Period:     2\ years

This alternative would incorporate capping requirements in
 compliance with New Jersey State Hazardous Waste Regulation (NJAC
 7:26-10.8(i)).  Using these guidelines, the following cap was
developed:

          12" vegetative topsoil
          12" clean fill
          12" sand drainage
          30  mil textured synthetic material layer
          36" clay (with permeability of 1 x 10'7 cm/sec)

-------
                                15

This alternative would have a unit weight of 800 pounds psf, an
overall thickness of six feet, and would employ a textured
synthetic material layer.  NJDEP guidelines restrict the use of
smooth synthetic material layers on landfills with sideslopes
greater than 7 percent.  The sideslopes at Global Landfill range
from 5:1  (20 percent) to 3:1 (33 percent) slopes.  Smooth
synthetic material layers have insufficient friction angles
between overlying soil layers to maintain long-term slope
stability.  Recently, synthetic material manufacturers have
developed textured synthetic material layers that provide
increased friction angles with soil material together with other
engineering controls, such as geogrids and geonets, that provide
support, and render sufficient slope stability on sideslopes
greater than 7 percent.

This cap would require a stabilization berm in Zones 1 and 2 in
order to achieve an acceptable factor of safety for sideslope
stability.  The Zone 1 and 2 stabilization berm would consist of
soil embankments constructed along the toe of slope of the
landfill for lengths of approximately 1000 and 600 feet
respectively.  They would range in height from approximately ten
to twenty feet above the adjacent wetlands, with 3:1 to 3.5:1
sideslopes.  The top width of the southeast berm (Zone 1) would
be approximately 50 feet, with a top elevation of about 25 feet
above MSL.  The top of the southwest berm (Zone 2)  would be about
20 feet wide, with a top elevation of 15 to 18 feet.

Alternative 4:  RCRA Cap

Estimated Capital Cost:            $26,739,000
Estimated Annual O&M Cost:         $554,000
Estimated Present Worth:           $34,548,000
Estimated Construction Period:      2\ years

This alternative would employ the capping requirements set forth
in RCRA (40 C.F.R. 264.310)  guidelines.  Using these guidelines,
the following was developed:

          12" vegetated topsoil
          12" clean fill
          12" sand drainage
          30  mil textured synthetic material layer
          24" clay (with a permeability of 1 x 10'7  cm/sec)

This alternative would have an overall thickness of five feet and
a unit weight of 650 pounds psf.  As is the case with Alternative
3, this cap would require the construction of a stabilization
berm in Zones 1 and 2 in order to achieve an acceptable factor of
safety for sideslope stability.

-------
                                16

Alternative 5:  Bentonite Clay Cap

Estimated Capital Cost:            $18,909,000
Estimated Annual O&M Cost:         $504,000
Estimated Present Worth:           $25,945,000
Estimated Construction Period:     1% years

Bentonite is a clay material which is typically mixed with soil,
or used alone, to form an impervious layer.  This capping
alternative uses a bentonite barrier layer in order to minimize
the load placed on the landfill from capping.  The bentonite cap
would include:

          12" vegetated topsoil
           8" sand fill
        ±0.5" synthetic drainage
           4" bentonite clay (with permeability of
              1 x 10'9 cm/sec,  after hydration)

The barrier layer in this alternative would be a pre-fabricated
material consisting of a dry bentonite clay layer (approximately
0.5-inch), sandwiched between two geotextile layers.  Upon
contact with moisture, the bentonite layer swells to a thickness
of approximately two inches.  A fifty percent overlap of the
barrier would be provided, resulting in an effective bentonite
thickness of four inches.  This cap has a unit weight of 300
pounds psf.  Also, as is the case with Alternative 2, this cap
would require a stabilization berm in Zone 1 in order to achieve
an acceptable factor of safety against sideslope failure.

Alternative 6:  Modified NJDEP Hazardous Waste Cap

Estimated Capital Cost:            $19,938,000
Estimated Annual O&M Cost:         $512,000
Estimated Present Worth:           $27,101,000
Estimated Construction Period:     2 years

This alternative -was developed to provide a light weight capping
system for the Global Landfill site.  It would.incorporate the
composite cap features of NJDEP Hazardous Waste and RCRA capping
alternatives in that it would also contain a textured synthetic
material layer that would increase friction along the landfill
sideslopes, and provide sufficient stability along the
sideslopes.  However, this alternative would have a reduced unit
weight and thickness, in consideration of the slope stability
problems of the landfill.  The Modified Hazardous Waste Cap
alternative would include:

          12" vegetated topsoil
          12" sand drainage
          30  mil textured synthetic material layer
          12" clay (with permeability of 1 x 10'7 cm/sec)

-------
                                17

This cap would have a total thickness of three feet, and a unit
weight of 450 pounds psf.  Also, as is the case with Alternatives
2 and 5, this alternative would require a stabilization berm in
Zone 1 in order to assure an acceptable factor of safety against
sideslope failure.

Leachate System Options

The landfill is partially saturated with leachate due to the lack
of an adequate cap.  The leachate finds its way to the surface of
the landfill in the form of leachate seeps, and needs to be
collected.  Collection of exposed leachate surface seeps would
prevent their migration from the landfill and discharge to the
adjacent wetlands.  In addition, collection of the leachate would
assist in maintaining cap integrity by preventing a buildup of
leachate at the toe of slope of the landfill.  Once collected,
the leachate would be treated, using one of the treatment options
described below.  Condensate generated by the landfill gas
management system would also be collected and treated along with
the leachate.  Reinfiltration of groundwater was not considered
because recharge at the site would be limited by the shallow
depth to groundwater characteristic of the surrounding wetlands.

The leachate treatment system would treat a flow rate that
diminishes annually from approximately 20,000 gallons per day
(gpd) to approximately 400 gpd after 15 years.  Below are three
options for leachate collection and treatment:

Option 1; Off-Site Disposal at an Industrial Waste
          Treatment Facility

Under this option, a leachate surface seep collection system
would be constructed along the toe of slope around the perimeter
of the landfill.  Leachate, along with condensate from the gas
collection system, would then be pumped to a holding tank, and
transferred by truck to a RCRA permitted hazardous waste
treatment, storage and disposal (TSD) facility.  No pretreatment
would be required under this option.

Option 2; On-Site Pretreatment With Discharge to a Publicly
          Owned Treatment Works fPOTW)

This option requires the construction of a wastewater
pretreatment plant on site.  Collection of the leachate seeps for
this option is similar to that described for Option 1.  The
collected leachate and gas condensate would be pumped to the
treatment facility.  The pretreatment process proposed under this
option would consist of flow equalization followed by a
one-stage, batch-operated biological treatment with the addition
of powdered activated carbon.  Metals removal may be necessary to
meet Federal and state regulations.  Following pretreatment, the
collected wastewater would be retained on-site in storage tanks,

-------
                                18

then transported by truck to a municipal waste water treatment
facility  (otherwise known as a publicly owned treatment works, or
POTW).  Sludge generated during pre-treatment would be
transported by truck to a RCRA permitted TSD facility for
treatment and disposal.


Option 3; On-Site Treatment With Discharge to Surface Water

This option requires the construction of a complete waste water
treatment plant oh-site.  The leachate seep collection system for
this option is also similar to that described in Option 1.  The
collected leachate and gas condensate would be pumped to the on-
site treatment plant.  The treatment process proposed under this
option would consist of flow equalization followed by a
two-stage, batch-operated biological treatment system, with the
addition of powdered activated carbon for residual organics
removal.  The system provides for nitrification and
denitrification as part of the process.  Ultraviolet disinfection
of the treated effluent would be the final step, prior to
discharge to the Cheesequake Creek.  Metals removal may be
necessary to meet Federal and State regulations.  As in Option 2,
sludge generated from the treatment process would be transported,
by truck, to a RCRA permitted TSD facility.  The treatment unit
would be designed to produce an effluent that would meet NJPDES
requirements for discharge to surface water.

     Estimated  Costs  and Required Construction  Time  (Years)

                         Option 1       Option 2       Option 3

Capital Cost             $483,600       $1,051,700     $1,526,200
Annual O&M Cost          $1,394,700     $275,500       $253,100
Present Worth            $4,485,800     $2,797,700     $3,252,200
Construction period*     1 to 1%        2 to 2\        2 to 2k

*    Construction would take place concurrently with cap
     construction
SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES

In accordance with the NCP, a detailed analysis of each remedial
alternative was conducted with respect to each of the nine
criteria.  This section discusses and compares the performance of
the remedial alternatives under consideration against these
criteria.  The nine criteria are described below.  All selected
alternatives must at least attain the Threshold Criteria.  The
selected alternative should provide the best trade-offs among the
Primary. Balancing Criteria.  The Modifying Criteria were
evaluated following the public comment period.

-------
                                19

THRESHOLD CRITERIA

•  Overall Protection of Humpj Health and Environment addresses
   whether or not a remedy provides adequate protection and
   describes how risks posed through each pathway are eliminated,
   reduced, or controlled through treatment, engineering
   controls, or institutional controls.

•  Compliance with ARARs addresses whether or not a remedy will
   meet all of the applicable or relevant and appropriate
   requirements (ARARs) of other Federal and State environmental
   statutes and/or provide grounds for invoking a waiver.

PRIMARY BALANCING CRITERIA

•  Long-term Effectiveness and Permanence refers to the magnitude
   of residual risk and the ability of a remedy to maintain
   reliable protection of human health and the environment over
   time once remedial objectives have been met.

•  Reduction of Toxicity, Mobility, or Volume Through Treatment
   is the anticipated performance of the disposal or treatment
   technologies that may be employed in a remedy.

   Short-term Effectiveness refers to the speed with which the
   remedy achieves protection, as well as the remedy's potential
   to create adverse impacts on human health and the environment
   that may result during the construction and implementation
   period.

   Implementability is the technical and administrative
   feasibility of a remedy, including the availability of
   materials and services needed to implement the chosen
   solution.

•   Cost refers to estimates used to compare costs among various
   alternatives.

MODIFYING CRITERIA

   State Acceptance indicates whether, based on its review of the
   FS and Proposed Plan, NJDEP concurs with, opposes, or has no
   comment on the preferred alternative.

•   community Acceptance summarizes the public's general response
   to the alternatives described in the Proposed Plan and the FS
   report.  Responses to public comments are addressed in the
   Responsiveness Summary of this ROD.

-------
                                20

ANALYSIS

The  following  is a summary of the comparison of each
alternative's  strengths and weaknesses with respect to the nine
evaluation criteria:

Overall Protection of Human Health and the Environment

All  of the containment alternatives, with the exception of the No
Action alternative, address the on-site remedial action
objectives identified for the Global Landfill site.  Wastes would
be contained on-site and residuals would be controlled through
the  implementation of gas and leachate surface seep controls.
The  alternatives would offer protection from windblown
contaminants,  and from direct contact with contaminated soil or
leachate seeps.  All of the alternatives are protective of a 100-
year flood, however, they would not offer protection from a 500-
year flood without additional reinforcement of sideslopes and/or
increasing the size of the berm.

Alternative 3  (NJDEP Hazardous Waste Cap), Alternative 4 (EPA
RCRA Cap), Alternative 5 (Bentonite Clay Cap), and Alternative 6
(Modified NJDEP Hazardous Waste Cap) would reduce the
infiltration of rainwater through the landfill's surface by over
99 percent, thereby reducing the current rate of leachate
generation.  Alternative 2 (NJDEP Solid Waste Cap) reduces
infiltration of rainwater by an estimated 94 percent.

Alternatives 2, 5, and 6 would impact the least wetlands acreage
because they are lighter in weight (450, 300, and 450 pounds psf,
respectively), and therefore would only require Zone 1
stabilization  berms.  These alternatives would impact
approximately  2.6 acres of wetlands.  Alternatives 3 and 4,
however, would require stabilization berms in Zones 1 and 2 to
support their unit weights (800 and 650 pounds psf,
respectively).  These alternatives would impact approximately a
total of 4.0 and 4.2 acres of wetlands, respectively.

Alternatives 3, 4, and 6 would provide greater control of gas
migration (in conjunction with the gas collection system) than
Alternatives 2 and 5, due to the incorporation of an synthetic
material layer into the cap.

The No Action alternative offers little protection of human
health and the environment.  The risks would be increased over
time due to continual deterioration of the minimal on-site cover.
This alternative will not be considered further in this document.

Alternative 6 offers the greatest overall protection of human
health and the environment.  This Modified NJDEP Hazardous Waste
Cap alternative effectively reduces the infiltration of
rainwater,  thereby reducing the rate of leachate generation and

-------
                                21

provide protection from exposure to contaminants.  It is lighter
in weight and would provide a greater factor of safety for the
sideslopes of the landfill.  In addition, this alternative would
require a smaller berm, thereby impacting less wetland acreage.

Compliance With ARARs

Location-specific ARARs

The Coastal Zone Development requirements (NJAC 7:7E-3.27),
Freshwater Wetlands Protection Act Rules (NJAC 7:7A-1.1 et seq.),
and Section 404 of the Clean Water Act (33 U.S.C.A. §1344) are
ARARs for this site.  Therefore, wetlands destroyed as a result
of non-compliance with past permitting requirements, the
sideslope failure in 1984, and any encroachment due to remedial
construction activities, would require mitigation in compliance
with these ARARs.  The type of wetland mitigation will be
determined during the design of the selected remedy.  Also, in
order to comply with the provisions of the National Historic
Preservation Act, a cultural resource study will be preformed
during the design of the selected remedy.  If cultural resources
are found, a cultural resources mitigation plan will be developed
to reduce the impact to these resources as much as possible.

All the containment alternatives would comply with the Coastal
Zone Management Act (15 C.F.R. 930), Waterfront Development Law
(New Jersey Statutes Annotated (NJSA 12:5-3) and the Wetlands Act
of 1970 (NJSA 13:9A-1 et seq.)  Because this project would impact
freshwater wetlands, the requirements of the Freshwater Wetlands
Statewide General Permit #4, under the Freshwater Wetlands
Protection Act Rules (NJAC 7:7A-1.1 et seq.) are also applicable.

Activity-specific ARARs

The presence of hazardous waste in the landfill was confirmed, by
excavation, in 1988.  Therefore, requirements set forth in
Subtitle C of RCRA, and the New Jersey Hazardous Waste Landfill
Closure Regulations (NJAC 7:26-10.8(i)), as well as the
appropriate Federal and State requirements for subsurface gas and
leachate management systems, are relevant and appropriate for
capping of Global Landfill.

The NJDEP Solid Waste Cap (Alternative 2), NJDEP Hazardous Waste
Cap (Alternative 3), and the RCRA Cap (Alternative 4) have been
developed using Federal and State capping guidelines.  The
Bentonite Clay Cap (Alternative 5)  and Modified Hazardous Waste
Cap (Alternative 6) are specialized modifications of those
guidelines, that were developed as lightweight containment
alternatives to address the slope stability concerns specific to
Global Landfill; therefore, for either of these alternatives to
be implemented, a waiver of New Jersey Hazardous Waste Landfill

-------
                                22

Closure Regulations  (NJAC 7:26-10.8(1)2) would be required based
upon technical impracticability from an engineering perspective.

All leachate collection and treatment system options would be in
compliance with requirements set forth in Sections 402 and 404 of
the Clean Water Act  (33 U.S.C.A. §§1342, 1344), the New Jersey
Pollution Discharge Elimination System (NJAC-7:14 et seq.)/ the
New Jersey Safe Drinking Water Act (NJAC 7:10 et seq.), New
Jersey Water Supply Management Act rules (NJAC 7:19 et seq.), and
Surface Water Quality Standards (NJAC 7:9-4 et seq.)  Also,
Option 3 (on-site treatment with discharge to surface water),
would comply with Federal and State regulations concerning
discharges to surface waters.

Under the NJAC Surface Water Quality standards, Cheesequake Creek
is classified as a saline SE-1 surface water.  The discharge to a
POTW option would be subject to discharge limitations set by the
agency receiving the pretreated wastewater.  The construction
efforts at the site will also be subject to the Noise Control Act
of 1971 (NJAC 7:29-4 et seq.)  In addition, trucking of the
leachate would be subject to Department of Transportation
regulations for hazardous wastes.

Air emissions of specific contaminants from Global Landfill can
not be quantified based on data collected to date.  Therefore, a
comparison of ambient air quality at the landfill after capping,
with applicable air quality standards, cannot be made at this
time.  Additional air and gas quality monitoring will be
performed during the OU-1 design, and will be incorporated into
the design of the gas management system.

Long-Term Effectiveness and Permanence

All five containment alternatives address this criteria by
eliminating the potential risks associated with direct (on-site)
contact with hazardous wastes, and with the off-site migration of
contaminated dust or landfill wastes.  The bentonite clay cap
proposed in Alternative 5, and the textured synthetic material
layer in the clay composite caps (Alternatives 3, 4, and 6) are
relatively new technologies; their long-term performance as
landfill capping materials are not well documented  (as is the
more conventional clay cap in Alternative 2).

All the capping alternatives address other existing site
conditions that require attention.   These include improvement of
slope stability,  leachate and gas management controls, and site
access controls.   After the construction of the slope
stabilization berm and cap, the long-term factor of safety would
be greater for all the alternatives.   However, Alternatives 2, 5,
and 6 are lighter, and would provide higher initial factors of
safety,  which would improve further as a result of construction.

-------
                                23

Wetlands would be impacted during construction of the slope
stabilization berms.  The impact would be greatest with capping
Alternatives 3 and 4 because of the larger sizes of the berms
required to support the weight of those caps.

All the capping alternatives are expected to adequately control
and manage wastes remaining on-site, and residuals generated
after capping.  The key to effective long-term performance is
post-capping operation, maintenance, inspection, and monitoring.
Factors that could effect long-term performance include the
effects of differential settlement and sideslope creep.
Differential settlement could damage the wells and piping systems
of the gas collection and leachate collection systems, as well as
the low permeability layer of the cap.  Buildup of solids and
biological growth on well screens and piping systems could also
effect long-term operation.  The appropriate O&M programs would
be implemented to minimize these potential performance problems.

Reduction of Toxicity, Mobility or Volume

None of the containment alternatives reduce the overall toxicity,
mobility or volume of wastes present at Global Landfill.  The
alternatives will not address contamination caused by waste
materials in direct contact with shallow groundwater within the
landfill.  However, all containment alternatives provide for on-
site containment of wastes, reduction in leachate generation, and
collection and treatment of leachate surface seeps generated by
the landfill.  They would also eliminate the potential for direct
human contact with hazardous waste, and assist in controlling
erosion and sediment loss.  In addition, the collection and
treatment of gasses would reduce the toxicity, mobility, and
volume of gaseous contaminants released through the surface of
the landfill.

Alternative 2 (NJDEP Solid Waste Cap) reduces infiltration of
rainwater by an estimated 94 percent.  Alternative 3  (NJDEP
Hazardous Waste Cap), Alternative 4 (EPA RCRA Cap), Alternative 5
(Bentonite Clay Cap) and Alternative 6 (Modified NJDEP Hazardous
Waste Cap)  would reduce the infiltration of rainwater through the
landfill's surface by over 99 percent, diminishing the current
rate of leachate generation, and therefore reducing the mobility
and volume of contaminants migrating into the groundwater.  All
leachate collection and treatment options would be designed to
collect all of the leachate seeps and gas condensate.

Short-Term Effectiveness

All five containment alternatives may cause potential short-term
health and environmental impacts.  These impacts are generally
related to potential exposure to waste materials on-site, air
emissions (on- or off-site), typical construction related safety
hazards, increased truck traffic, noise, and potential soil

-------
                                24

erosion.  The short-term impacts, however, can be mitigated
through appropriate design considerations and construction
practices.  In addition, health and safety plans including on-
and off-site air monitoring, would be developed for protection of
local residents and on-site workers.

Short-term health effects may be a concern during well drilling
for the gas collection system.  Protection of local residents and
on-site workers can be achieved through air monitoring,
minimizing the aerial extent of waste disturbance, and by
employing standard dust control measures.  Construction of the
leachate collection system would also require similar measures.

The time required to construct Alternatives 2, 5, and 6 ranges
from 1*5 to 2 years, while Alternatives 3 and 4 would require
approximately 2h years to construct.

Implementability

Alternatives 3 and 4 would be difficult to implement due to the
instability of the landfill sideslopes, and the potential for
another slope failure to occur.  The weight of the caps proposed
in these alternatives, due to the amount of clay required, would
result in an unacceptable factor of safety for sideslope
stability.  Alternatives 2, 5, and 6 are the most technically
feasible for Global Landfill to assure the greatest factor of
safety against sideslope failure.  They are lighter in weight,
and would minimize the additional load placed on the landfill
during capping.

The Bentonite clay proposed in Alternative 5, and the textured
geomembranes in the composite clay cap alternatives (3, 4 and 6),
are presently available from a limited number of manufacturers,
while natural clay is available from a number of sources.
Alternatives 2, 3, and 4 employ technologies that are based on
conventional construction procedures.  The materials and
techniques required to construct these alternatives have been
used at other landfills and should be implementable.  The
construction of the cap, berm, leachate collection system, and
gas treatment system will be performed in a manner which will
minimize the impact to the wetlands.

No implementation difficulties are anticipated for the gas .
collection and treatment system.  Implementation of all leachate
collection and treatment options is also technically and
administratively feasible.

COSt

Capital, costs, first year O&M costs, and the total present worth
of all the remedial alternatives are summarized in Table 6.
Present worth costs are based on a 30-year period and a discount

-------
                                25

rate of five percent.  Alternative 2 is the least expensive in
terms of total present worth  ($23,722,000), while Alternative 3
($',8,420,000) is the most expensive.  Alternative 2 also has the
lowest capital ($16,915,000) and first year O&M cost ($489,000).
The highest capital cost ($30,190,000) and first year O&M cost
($581,000) are for Alternative 3.

State Acceptance

The New Jersey Department of Environmental Protection concurs
with the preferred alternative.

Community Acceptance

Community acceptance of the preferred alternative was evaluated
after the public comment period.  Local residents had no
opposition to the preferred alternative, nor did they prefer any
other alternative.  Comments raised at the public meeting and
during the public comment period are summarized in the attached
Responsiveness Summary.


SELECTED REMEDY

Based upon considerations of CERCLA, the detailed analysis of the
alternatives, a detailed evaluation of all comments submitted by
interested parties during the public comment period, both EPA and
NJDEP have determined that Alternative 6 (Modified NJDEP
Hazardous Waste Cap) is the most appropriate remedy for
addressing source control at the Global Landfill site.  This
alternative involves:
                                                          *
   • Capping of the landfill with a modified hazardous waste cap
     which includes:                              .
                    •12" vegetated topsoil
                    •12" sand drainage
                    •30  mil textured synthetic.material layer
                    •12" clay (with permeability
                         of 1 x 10'7 cm/sec)

   • Slope stability enhancement through construction of a soil
     stabilization berm;

   • Construction and operation of a gas collection and treatment
     system;

   • Construction and operation of stormwater and leachate
     management systems;

-------
                                26

    •  Installation of a perimeter security fence to restrict
      access to the site; and

    •  Implementation of a monitoring program to ensure the
      effectiveness of the remedy.

The estimated present worth for all tasks associated with the
.selected remedy  (with Leachate Option 3) is $30,353,200.  The
capital cost is  estimated to be $21,464,200, with an annual O&M
cost  of approximately $765,100.

The preferred leachate collection and treatment system is
Option 3 (on-site treatment with discharge to surface water).
However, Leachate Option 1 (Disposal at an Industrial Waste
Treatment Plant) will be employed until the RI/FS for OU-2 is
completed.  At that time, the design and installation of a
combined leachate and groundwater system can be considered.  The
leachate seep treatment option chosen here would be designed to
be considerate of possible future expansion to accommodate
additional treatment capacity.

The leachate collection and treatment system, and other
associated remedial activities, will be designed to avoid further
impacts to wetlands.


STATUTORY DETERMINATIONS

The selected remedy is protective of human health and the
environment, and is cost-effective.  With the exception of cap
construction, the selected remedy complies with Federal and State
requirements that are legally applicable or relevant and
appropriate to the remedial action.  The remedy utilizes
permanent solutions and alternative treatment technologies to the
maximum extent practicable for this site.  However, because
treatment of the entire contents of the wastefill was not found
to be practicable, the statutory preference for treatment as a
principal element of the remedy will not be completely satisfied.
This action does not constitute the final remedy for the site.
Subsequent actions are planned to fully address 'the remaining
principle threats posed by the site.   A brief, site-specific
description of how the selected remedy complies with the
statutory requirements is presented below.

Overall Protection of Human Health and the Environment

The selected remedy is protective of human health and the
environment by preventing direct contact with contaminated wastes
or leachate seeps, while effectively reducing leachate generation
and serving as an effective barrier to the release of landfill
gasses to the atmosphere.  The remedy includes a composite cap
which, when constructed in combination with the stabilization

-------
                                27

benn  (Zone 1), would provide an acceptable factor of safety for
sideslope stability on all the landfill sideslopes.  In addition,
the selected remedy requires a smaller stabilization berm and,
therefore, would encroach upon fewer wetland acres.

The combination of the Modified Hazardous Waste Cap with a Zone 1
stabilization berm, gas and leachate management systems, and
perimeter security fence would eliminate site risks by limiting
the off-site migration of contaminants and restricting access to
the site.  In addition, wetlands and surface waters would be
protected from the discharge of leachate by reducing infiltration
into the landfill, and by collecting the leachate for treatment.
Furthermore, the spread of contamination in the water table
aquifer, which affects the wetlands and possibly the Old Bridge
Sand aquifer, would be greatly reduced.

Compliance with ARARs

The selected remedy will meet the appropriate RCRA Subtitle C
regulations set forth in 40 C.F.R. §264.310(A).  Pursuant to 40
C.F.R. §300.430(f)(ii)(C) a waiver of New Jersey Hazardous Waste
Landfill Closure Regulations (NJAC 7:26-10.8(i)2) is invoked
under this ROD.  The basis upon which this waiver is invoked is
technical impracticability; the specific engineering design
criteria for the cap set forth in NJAC 7:26-10.8(i)2 cannot be
implemented due to slope instability concerns and the additional
impact to wetlands at the site.  However, the selected remedy
will attain a standard of performance that is equivalent to that
required under the New Jersey Hazardous Waste Landfill Closure
Regulations.  The remedy will meet the appropriate Federal and
State guidelines and requirements for subsurface gas management
systems.

The selected leachate management system (Leachate Option 3) will
be in compliance with the appropriate Federal and State
regulations concerning discharges to surface waters.  The interim
leachate management system (Leachate Option 1) will also comply
with appropriate Federal and State regulations concerning
leachate disposal at a TSD facility.

Wetlands impacted as a result of non-compliance with past
permitting requirements, the sideslope failure in 1984, and any
encroachment due to remedial construction activities, will be
mitigated in accordance with the appropriate State and Federal
regulations.  Also, in order to comply with the provisions of the
National Historic Preservation Act, a cultural resource study
will be undertaken.

Cost-Effectiveness

Of the alternatives which most effectively address the principal
threats posed by the site, the selected remedy affords the

-------
                                28

highest level of overall effectiveness proportional to its cost.
Based on the information generated during the FS, the estimated
total project cost, with Leachate Option 3, is $30,353,200.

Utilization of Permanent Solutions and Alternative Treatment
Technologies to the Maximum Extent Practicable and Preference for
Treatment as a Principal Element

The selected remedy utilizes permanent solutions and alternate
treatment (or resource recovery) technologies to the maximum
extent practicable by providing the best balance among the nine
evaluation criteria.  The remedy employs a textured synthetic
material layer.  This is a new technology developed for use on
landfills with sideslopes greater than 7 percent.  The sideslopes
at Global Landfill range from 5:1 (20 percent) to 3:1 (33
percent) slopes.  Smooth synthetic material layers have
insufficient friction angles between overlying soil layers to
maintain long term slope stability.  The textured synthetic
material layer will provide increased friction on the angles with
soil material to render sufficient slope stability sideslopes.

The selected remedy does not satisfy the statutory preference for
treatment.  The landfill would require excavation and removal in
order to effectively treat the on-site waste.  Excavation of such
a large volume of waste is technically impractical and not cost-
effective.  The principal threats to groundwater will be
addressed under a separate ROD.


DOCUMENTATION OF SIGNIFICANT CHANGES

The Proposed Plan for the Global Landfill site was released to
the public in February 1991.  The Proposed Plan identified the
preferred alternative for containment of the landfill.  EPA
reviewed all written and verbal comments submitted during the
public comment period.  Upon review of these comments, it was
determined that no significant changes to the selected remedy, as
originally identified in the Proposed Plan, were necessary.

-------
Appendix A: Figures

-------
SOURCE:  SOUTH AMBOY U.S.G.S
         7.5 MIN.  QUADRANGLE
         PHOTO REVISED 1981

SCALE:    1"  •  2000'
                                                    FIGURE 1

                                                   GLOBAL LANDFILL
                                             OLD BRIDGE TOWNSHIP, N.J.
       LOCATION MAP

Elton T KflUm A»»oel«U«, Inc.
Envrorvntniil and Hyortui« Enginetri
fT Mtl "   •••"   '      	
D!
                                                            POORQ
                                                               ORIGINAL


-------
  -o
08
 3
00
IP
                                               .-•V. .-- *  r"'
                                              	^"'  1-,     /-N
                                              ««• •«• •   - - s.

                                                                      bd
                                                                        I
                                                                        I
                                                                      iiSI
M
111

-------
Appendix B: Tables

-------
                                          TABLE 1-A
                  Summary of Results of Priority Pollutant  Analysis
                                       of Drum Contents
                          DRUMS WITH  SOLIDS  AND SLUDGES CONTENT


                                            CONCENTRATION                     NUMBER OF TIMES
                                            RANGE fmo/kcrt                           FOUND

VOLATILE ORGANICS
Carbon Tetrachloride                               72-4.940                               3
Chlorobenzene                                   135-204                                2
1,3 Dichlorobenzene                                  49.2                                1
Ethylbenzene                                    105-1,250                               5
Methylene Chloride                                  207                                   1
Tetrachloroethytene                                126-343                                3
Trichloroethylene                                 309-510                                2
Toluene                                        142-552                                8
Xylene                                         112-4,890                               6

BASE/NEUTRALS
Bis (2-Ethylhexyl) Phthalate                          133-70,900                              8
Dimethylphthalate                                 134 - 251                                2
Di-rvButylpnthalate                                126-3,830                               3
Naphthalene                                     800-1440                               3
METALS
Arsenic
Cadmium
Chromium
Copper
Lead
Nickel
Mercury
Thallium
Zinc
0.32 - 146
0.23 - 7.47
0.28 - 7,530
0.92-21.70
1.57 - 42,600
0.22-154
0.26 - 14.8
1.18-6.21
1.11 -11,600
18
4
18
18
18
14
3
3
19
                                  DRUM WITH  LIQUID CONTENT
BASE/NEUTRALS
Naphthalene                                      80.00 mg/l                              1

METALS
Arsenic                                          0.32 mg/l                              1
Chromium                                       0.28 mg/l                              1
Copper                                          0.92 mg/l                              1
Lead                                           1.57 mg/l                              1
Nickel                                           0.22 mg/l                              1
Zinc                                            7.45 mg/l                              1

-------
                        Table 1-B

      Drum Waste Which Failed RCRA Characteristics
     Resulting in Classificationas  a  Hazardous  Waste
  DRUM
  WASTE
  SAMPLE
VOLATILE ORGANIC
COMPOUNDS (VOC8)
     (ag/kg)
 LEAD

(mg/kg)
TR5-D3
TR4-D5
TR4-D2
TR5-D5
TR5-D4
TR4-D3
TR4-D4
TR4-D7
P9-D1
P9-D2
TR4A-D1
113
2,005
552
6,112
1,160
112
559
142
7,027
105
182
BDL
BDL
2.09
29.8
BDL
0.12
0.45
2.71
4.25
BDL
BDL
VOC characteristic level      100 mg/kg

Lead characteristic level     5 mg/kg

-------
             Table 2-A

 Comparison of Groundwater Quality
in Shallow Wells with Water Quality
   Criteria for Heavy Metals and
    Priority Pollutant Organics
PARAMETER
STANDARD
mJcfoQwns
. per liter (ug/l)
NUMBER
OF
SAMPLES
EXCEEDING
TOTAL
NUMBER
OF
SAMPLES
REPORTED
RANGE OF
CONCENTRATION

-------
                          Table  2-A,  Continued

                 Comparison of Groundvater  Quality
                in Shallow  Wells  with Water Quality
                    Criteria for Heavy Metals and
                     Priority Pollutant Organics
PARAMETER
Xylene
Arodor - 1260 (PCB)
Heptachlor
Heptachlor Expoxide
Aldrin

STANDARD
nilcrog rents
pw M*r (ug/l)
44"
0.5"
0.4e
0-2°
0.003*

NUMBER
OF
SAMPLES
EXCEEDING
16
1
1
2
2

TOTAL
NUMBER
OF
SAMPLES
45
45
45
45
45

REPORTED
RANGE OF
CONCENTRATION
(ug/0
ND-140
ND-1.2
ND - 71
ND-2
ND • 0.33

ND     Not Detected
 *      Elevated Concentrations are believed to be attributed to positive matrix interference during analysis
**      Methylene chloride concentrations are subject to blank contamination, and are not believed to accurately
       reflect actual concentrations in groundwater

 a      NJDEP Water Quality Standards for GW-2 Groundwater
 b      NJDEP MCL (NJ A-280 Amendments)
 c      EPA Safe Drinking Water Act • MCL, Promulgated January 30. 1991
 d      EPA Safe Drinking Water Act - Action Level for Drinking Water, Promulgated May 7,1991

-------
                                  Table  2-B

                  Comparison  of Groundwater Quality
                   in  Deep Wells with  Water  Quality
                    Criteria  for  Heavy  Metals and
                      Priority Pollutant Organics
PARAMETER
STANDARD
rntCTOQTBfTtS
p«f in* (ug/i)
NUMBER
OF
SAMPLES
EXCEEDING
Upgradient Wells MW-7D
Methytene Chloride
Tetrachloroethene
4.4-DDT

2"
1b
0.001*

7"
5
1

TOTAL
NUMBER
OF
SAMPLES
REPORTED
RANGE OF
CONCENTRATION
(ug/i)

8
9
9

ND-120
ND • 4.1
ND • 0.043

Downgradient Wells
MW-2A, 3A, 4A, 5A, 6D, 8D
Cadmium
Chromium (Hexavalent)
Chromium (Total)
Lead
Benzene
Chlorobenzene
Methytene Chloride
Tetrachloroethene
Trichloroethene
Vinyl Chloride
4,4-DDT

5e
50*
50*
15"
1b
4b
2*
1b
1b
2"
0.001'

3
2'
1
4
4
3
42"
3
2
3
4

54
54
54
54
54
54
54
54
54
"54
54

ND-15
ND-110
ND-70
ND-280
ND-3
ND-43
ND-110
ND-5
ND - 10
ND-7
ND • 0.06

ND     Not Detected
 *      Elevated Concentrations are believed to be attributed to positive matrix interference during analysis
•*      Methytene chloride concentrations are subject to blank contamination, and are not believed to accurately
       reflect actual concentrations in groundwater

 a      NJDEP Water Quality Standards for GW-2 Groundwater
 b      NJDEP MCL (NJ A-280 Amendments)
 c      EPA Safe Drinking Water Act • MCL, Promulgated January 30,1991
 d      EPA Safe Drinking Water Act • Action Level for Drinking Water, Promulgated May 7,1991

-------
                                  Table 3

                  Comparison of Leachate Data  with
                       Groundwater Quality  Data
PARAMETER
•
STANDARD
nticroQrwns
p«r w«r (ug/0
NUMBER OF
SAMPLES
EXCEEDING
STANDARD
(Total & so lamptos)
RANGE OF
CONCENTRATIONS
EXCEEDING STANDARD
(ufl/0

Arsenic
Barium
Cadmium
Chromium (Hexavalent)
Cyanide
Lead
Benzene
Chlorobenzene
Methylene Chloride*
Tetrachloroethene
Xytenes (Total)
50"
1000*
5s
50*
200"
15"
1"
«b
2"
1b
44b
1
6
13
1
3
27.
24
28
22
5
14
110
1082-2019
5-27
200
200-26,000
15-5530
1-69
4-4600
2-720
1-12
68-990
      Methylene Chloride concentrations are subject to blank contamination"
a     NJDEP Water Quality Standards for GW-2 Groundwater
b     NJDEP MCL (NJ A-280 Amendments)
c     EPA Safe Drinking Water Act - MCL, Promulgated January 30,1991
d     EPA Safe Drinking Water Act - Action Level for Drinking Water, Promulgated May 7,1991

-------
                                   TABLE 4-A

                 SUMMARY  OF NJDEP SURFACE WATER SAMPLING PROGRAM
                                 OCTOBER 1986
                                                               Southwest Side
          (ug/1)                  Kelvin's Creek                 of Landfill
Phenols                              10 '                           10
Cyanide                             <25                          . <25
•Antimony                            4.3                           4.3
Arsenic                             5.4                            ND
Beryllium                           0.7                           0.5
Cai-iu-s                             1.2                           0.9
Chrc--u-                             ND                           5.6
Copper                            .  4.6                           0.8
Lead                                2.2                           7.8
Mercury                              ND                            ND
Nickel                              4.3                            18
Sele-. •:•„••:.                            2.4                           0.8
Silver                      •        2.5                           0.8
ThaViiu-                             ND                            ND
Zinc                                 16                            20
Sa-.:les analyzed for Priority Pollutant organics and metals.
Orcs-ic fractions for both samples were non-detectable except for
"pehicic'es/PCE's for Kelvin's Creek sample.  This sample was  reported  lost due
t: t::.l ever on a hot plate during laboratory preparation.

ND - indicates parameter  not  detected in analysis.
                                                             POOR Q'JWJ
                                                                ORIGINAL

-------
                                                       TABLE 4-B

                                           SUMMARY OF RESUITS OF SURFACE WATER SAMPLING
ADJACfNT TO GLOBAL LANOFILL
, ocTonrR
1907



Sample l.ncat (on
Parameter
BOOc
Cl
COO
Hardness
Hllj-N
NOj-N
pll (units)
Total Phenols
Na
50-
TO?
10X
F. Coll (HPN/IOOmls)
T. Coll (MPN/lOOmls)
00
PHC
Fe
Cd
Pb
Cr
N1
7n
PCB'S (ug/1)
Aldrln/Oleldrln (ug/1)
flenildene (ug/1)
DOT (ug/1)
tndrln (ug/1)
Toxaphene (ug/1)
Other PP Pesticides (ug/1)
Beta BMC (ug/1)
Gamna BMC (Llndane) (ug/1)
Color (CPU)
,
O.O
34
34
103
7.0
<0.5
6.4
0.075
74
18
1740
0.047
740
2
4.3
47
30
68
7.0
1.18
6.5
0.015
26
58
740
0.046
4600
460 >?4000
9.1
ND(<1.0)
18.6
0.0034
<0.005
0.0045
<0.010
0.031
NO
NO
N0(<50)
NO
NO
NO
NO
NO
NO
70
7.1
NO
7.03
<0.003
'<0.005
0.017
0.015
0.116
NO
NO
NO
0.1?
NO
NO
NO
0.77
NO
30
3
3.3
till
n;
4R.7
 24000
>?4000
4.0
NO
4.71
<0.003
<0.005
<0.004
?4000
8.9
NO
7.06
<0.003
<0.005
<0.004
<0.010
0.063
NO
NO
NO
NO
NO
NO
NO
0.70
0.13
15
6
0.0
4977
194
7371
15.0
<0.5
6.8
0.005
4350
754
3410
7
0.0
7379
72
7579
?4000
>?4000
8.7
NO
7.65
<0.003
<0.005
<0.004
<0.010
0.033
NO
NO
NO
NO
NO
NO
NO
NO
NO
70
8
O.O
6004
110
7007

-------
                                   TABLE A-
                      COMPARISON OF SURFACE WATER QUALITY
WITH NJDEP WATER DUALITY CRITERIA
Parameter
Fecal Colifonr.
Bacteria
Lindane
DDT
Cadmium
N.' - 1. - i
. ».K.C I
Zinc
Copper
Silver
Chrorriiun;
Standard
or
Criteria
200 per 100ml *
0.004 ug/la
0.001 ug/l*«b
4.5 ug/lb
7.1 ug/lb
58 ug/lb
4.0 ug/lb
2.3 ug/lb
50 ug/1*
No. of
Samples
Exceeding
10
1
1
1
3
6
1
1
1
AND STANDARDS
Total
No. of
Samples
10
11
11
12
12
12
2
2
12
Max 1 num
Reported
Concentrat1onc
24,000
0.130
0.120
5.3
61
255
4.6
2.5
289
Monitoring wes conducted In October 1986 by NJDEP and
October 1987 by Killam Associates.
a - NJD:P Surface Water Quality Standards
b - NJPDES Criteria for Protection  of Salt Water Aquatic Life.
c - Units are the same as for the appropriate standard or criteria.

-------
                  Table 5

Substances of concern in the Global Landfill
       Based Upon Concern Index Values
Action Mean
Levels 1n Cone, in
Groundwater Shallow
Groundwater
Substance (mg/1) (mg/1)
Metals
lead
iron
chromium (total)
mercury
copper
arsenic
cadmium
zinc
barium
Substituted Alkane and Alkene
carbon tetrachloride
trichlorethylene
tetrachl oroethyl ene
methyl ene chloride
1,2-trans-dichl oroethyl ene

0.015d 0.035
0.30s 1.70
0.05s 0.0723
0.002s 0
1.0s 0.016
0.05s 0.0035
0.005s 0.0068
5.0s 0.134
1.0s 0.467
Hydrocarbons
0.002b 0
0.001b 0
0.0016 0
0.002b 0
0.010b 0
Overall
Cone.
in
Landfill
(mg/kg)

97.5
87.2
11.1
0.0468
20.2
0.461
0.0396
15.4
1.10

15.4
3.12
2.12
1.87
0.0343
Lowest
Concern
Index

2.30
56.7
1.45
0.00
0.02
0.07
1.36
0.03
0.47

0.00
0.00
0.00
0.00
0.00
Highest
Concern
Index

6,500
291
221
23.4
20.2
9.22
7.92
3.07
1.10

WL5
2,115
937
3.43
Aromatic and Substituted Aromatic Hydrocarbons
chlorobenzene
xylenes, total
benzene
DDT/metabolites
ethyl benzene
aldrin
heptachlor
toluene
Miscellaneous
ammonia (as nitrogen)
sodium
chloride
cyanide
nitrate (as nitrogen)
0.004b 0.164
0.0446 0.0345
0.001b 0.0210
0.000001" 0
0.7° 0.0139
0.000003' 0.000007
0.0004C 0.0016
1.0C 0.00067

0.5s 320
50" 1840
250s 3420
0.2s 0.00052
10s 5.55
2.17
17.3
0.0263
0.00001
5.39
0.00002
0.0016
2.85

791
3480
5920
0.66
20.9
41.0
0.78
26.3
0.00
0.02
2.22
4.08
0.00

641
36.8
13.7
0.00
0.56
543
394
26.3
10.3
7.70
7.00
4.14
2.85

1,581
69.6
23.7
3.30
2.09
a NJDEP Water Quality Standards for 6V- 2 GrounoVater
b NJDEP HCL (NJ A-280 Amendments)
c EPA Safe Drinking Water
d EPA Safe Drinking Water
Act - HCL, Promulgated January 30, 1991
Act - Action Level for Drinking Water,

Promulgated May

7. 1991



-------
                                 Table  6

                  Summary of Remedial Alternative  Costs
                        CONTAINMENT ALTERNATIVES
Alternative 1:
No Action

Estimated Capital Cost:
Estimated Annual O&M Cost:
Estimated Present Worth:
                                                  $ 0
                                                  $  210,000
                                                  $3,228,000
Alternative 2:
NJDEP Solid Waste Cap

Estimated Capital Cost:       $16,915,000
Estimated Annual O&M Cost:    $   489,000
Estimated Present Worth:      $23,722,000
Estimated Construction Period:   m years
Alternative 3:.
NJDEP Hazardous Waste Cap

Estimated Capital Cost:
Estimated Annual O&M Cost:
Estimated Present Worth:
                                                  $30,190,000
                                                  $   581,900
                                                  $38,420,000
                    Estimated Construction Period:   2\ years
Alternative 4:
RCRA Cap

Estimated Capital Cost:
Estimated Annual O&M Cost:
Estimated Present Worth:
Estimated Construction Period:
                                                  $26,739,000
                                                  $   554,000
                                                  $34,548,000
                                                     2\ years
Alternative 5;
Bentonite Clay cap

Estimated Capital Cost:       $18,909,000
Estimated Annual O&M Cost:    $   504,000
Estimated Present Worth:      $25,945,000
Estimated Construction Period:   I3* years
Alternative 6:
Modified NJDEP Hazardous Waste Cap

Estimated Capital Cost:       $19,938,000
Estimated Annual O&M Cost:    $   512,000
Estimated Present Worth:      $27,101,000
Estimated Construction Period:    2 years

-------
                           TABLE  6  (Continued)

                  Summary of Remedial Alternative Costs
                         LEACHATB  SYSTEM OPTIONS
Option l:
          Off-Site Disposal at an Industrial Waste Treatment
          Facility
               Estimated Capital Cost:
               Estimated Annual O&M Cost:
               Estimated Present Worth:
               Estimated Construction Period:
                                             $  483,600
                                             $1,394,700
                                             $4,485,800
                                             1 to l^i years
Option 2:
          On-Site Pretreatment With Discharge to a Publicly Owned
          Treatment Works (POTW)
               Estimated Capital Cost:
               Estimated Annual O&M Cost:
               Estimated Present Worth:
               Estimated Construction Period:
                                             $1,051,700
                                             $  275,500
                                             $2,797,700
                                             2 to 2S ye
years
Option 3:
          On-Site Treatment With Discharge to
          Surface Water

          Estimated Capital Cost:
          Estimated Annual O&M Cost:
          Estimated Present Worth:
          Estimated Construction Period:
                                                  $1,526,200
                                                  $  253,100
                                                  $3,252,200
                                                  2 to 2^ years
Notes;

 1,
The cap alternative costs (Alt. 1 through 5) include costs for the
cap and slope stabilization berm (from Table 4-1), gas management
(from Table 4-2), and groundwater monitoring plus and allowance
for wetlands mitigation but exclude leachate management costs.

Leachate management costs are presented separately as Options IA,
2A, 3A and Options IB, 2B, 3B and are derived from Table 4-3.

All capital costs include a 30% allowance for indirect capital
costs.
     Construction of Leachate Systems would take place concurrently
     with cap construction.

-------
                      RESPONSIVENESS SUMMARY

                        RECORD OF DECISION

                         GLOBAL LANDFILL

I.   OVERVIEW

From February 19, 1991 through May 6, 1991, the New Jersey
Department of Environmental Protection (NJDEP) held a public
comment period to obtain verbal and written comments from
citizens, elected officials, and other interested parties for the
preferred remedy proposed by NJDEP and the United States
Environmental Protection Agency  (EPA) for Operable Unit I (OU-1)
at the Global Landfill Superfund Site located in Old Bridge
Township, Middlesex County.  This Responsiveness Summary provides
highlights of community involvement and NJDEP community relation
activities at the site during the Feasibility Study (FS) and
public comment period.  In particular, the document summarizes
community relations, legal questions and technical concerns
pertaining to the FS and the Proposed Plan expressed by
residents, local officials, and other interested parties.

At the public meeting held on March 12, 1991, NJDEP formally
presented its preferred alternative, addressing the on-site
controls for the Global Landfill site.  The preferred alternative
involves the construction of a modified NJDEP hazardous waste
cap, which was detailed in the February 1991 Proposed Plan in
Alternative 6.  The components of this alternative include the
following:

          Capping of the landfill with a modified hazardous waste
          cap;

          Slope stability enhancement through construction of a
          soil stabilization berm;

          Construction and operation of a gas management system;

          Construction and operation of stormwater and leachate
          management systems;

          Installation of a perimeter security fence to restrict
          access to the site; and

          Implementation of a monitoring program to ensure the
          effectiveness of the remedy.

Comments received during the public comment period focused on
concerns with the actual design, the impact of costs on Old
Bridge Township, relocation of the gas pipeline, traffic impacts
from construction, and planting trees as a buffer.  The Global
Landfill Potentially Responsible Parties  (PRP) Group requested an

-------
 extension of the comment period; the comment period was extended
 to May  6, 1991.  Detailed answers-to the Global Landfill PRP
 Group's technical comments are presented in this document.

 Some of the community relations activities for the Global
 landfill include the following:

     •    NJDEP prepared a Community Relations Plan (February
          1989).  Copies of this plan are located in the public
          repositories for the site.
     •    Since January 1988, the Global Landfill/Sommers
          Brothers Property Site Task Group (Task Group) have met
          almost monthly.  The Task Group consists of
          representatives from Citizens Helping Environmental
          Cleanup (CHEC), the Old Bridge Environmental
          Commission, the Old Bridge Health Department, NJDEP,
          and New Jersey Department of Health (NJDOH).  This
          group is actively involved in overseeing the NJDOH
          health study on residents living near the sites.
          NJDEP held a briefing on February 13, 1991 with the
          Task Group to discuss on-site controls and the project
          schedule for Global.
          NJDEP held a public meeting on March 12, 1991 to
          discuss the preferred option for on-site controls on
          the landfill, and to respond to citizens' comments and
          questions.  A transcript of the meeting is available at
          the public repository locations.  NJDEP also held a
          public information session to answer citizens'
          questions on March 13, 1991.
          The public comment period on the Proposed Plan
          continued until May 6, 1991.


 II.  BACKGROUND ON COMMUNITY INVOLVEMENT

 Global  Landfill,  located in Old Bridge Township, Middlesex
 County, was in operation from 1968 until 1984.  The site was
 closed  in April 1984 by the NJDEP, after the southeast sideslope
 of the  landfill failed and slid into the adjacent wetlands.  A
 New Jersey court appointed an administrator to oversee the proper
 closure of the landfill on April 23, 1986.

The administrator authorized the consulting firm of E.T. Killam
Associates of Millburn, New Jersey, to conduct an on-site
 investigation.  The landfill was reported to contain municipal
 solid,  bulky, vegetative, and industrial wastes.  Drums
containing hazardous waste were discovered during an exploratory
excavation in March 1988.

The site was placed on EPA's National Priorities List (NPL) in
March 1989.   Killam Associates was authorized by NJDEP and the
administrator to prepare a Feasibility Study (FS) for on-site

-------
controls at the site.  The FS provides" only limited data on the
nature and extent of contamination of groundwater, surface water,
and air at the landfill.  An investigation of the groundwater and
other natural resources at the site, will be conducted during the
ongoing Remedial Investigation/Feasibility Study (RI/FS) for
Operable Unit 2 (OU-2).

The combination of high population density and high visibility of
hazardous waste problems has resulted in significant community
interest.  In March 1986, residents of the London Terrace
Apartments collected soil samples from the landfill for analysis.
The test results indicated the presence of volatile organic
compounds.  Many of the local residents feel that the tests prove
that the site is the cause of unexplained medical conditions and
illnesses in surrounding communities.  These residents formed
CHEC in March 1986.

Two toxic tort action suits were filed in 1988 against numerous
parties involved with operations at Global Landfill by plaintiffs
seeking damages for health and economic distress caused by
hazardous wastes.  Continued community health concerns led to the
passage of PL 1987, C.358, which appropriated $75,000 for a NJDOH
study of local residents.  NJDOH set up the Task Group to
implement the legislation.  The Task Group's main
responsibilities included:

     •    Conducting a community cancer evaluation;
     •    Conducting a health risk assessment
          Implementing a soil monitoring program to confirm the
          absences or presence of a third landfill under the
          housing complexes;
     •    Establishing a pediatric health care service to monitor
          health of Old Bridge and Sayreville children;
     •    Conducting a community demographic profile; and
          Continuing community outreach and education.

The work performed under the grant to the NJDOH should be
completed in the near future and presented to the Task Group.


III. SUMMARY OF PUBLIC COMMENTS AND LEAD AGENCY RESPONSES

Verbal comments made during the March 12, 1991 public meeting are
summarized below, followed by responses from the lead agency
(NJDEP).  Responses to written comments submitted by the Old
Bridge Township Environmental Commission (OBEC), the
Transcontinental Gas Pipe Line Corporation (Transco), and the
Global Landfill Potentially Responsible Party Group are in a
separate section of the Responsiveness Summary.  Copies of the
written comments received are attached as an Appendix of this
document.

-------
COMMENTS MADE AT THE PUBLIC MEETING ON MARCH 12. 1991

A Task Group member requested an explanation of a synthetic
geomembrane.

Response;  The synthetic geomembrane is about a quarter inch
thick and composed of rubber and plastic.  It is designed as an
impermeable landfill liner.  The geomembrane will be placed on
the top of the landfill over the clay layer, to form a composite
cap.

A question was raised by a Task Group member regarding the
shrinking and settling of the landfill over time and how this
will affect the cap's integrity.

Response;  Organic decomposition of waste in any landfill will
continue as long as moisture is present.  This decomposition
produces gas and causes shrinkage and landfill settling.  As part
of the operation and maintenance (O&M) phase, regular inspections
will be made to assure the cap's integrity and, when necessary,
the cap will be repaired.  Geogrids are plastic lattices that
provide strength and integrity to the cap to protect against     :
damage due to settling of the landfill.

Questions from a Task Group member concerning whether the
landfill will .be disturbed during the OU-1 construction, and if
air monitoring will be conducted during the construction to
protect the area residents.

Response;  Any intrusive work on Global will be controlled by
disturbing only small areas at one time.  As part of the Health
and Safety Plan for the OU-1 construction, dust suppression and
continuous air monitoring will be required.  The NJDEP, in
consultation with the community, will establish a program of
perimeter air monitoring during the construction.  The only
proposed regrading of Global would occur on the top seven acres
to provide proper drainage of precipitation.

A Task Group member asked what other sites in New Jersey have the
same type of NJDEP hazardous waste cap/ and how has it performed.

Response;  This will be the first site in NJ to "have this
specific type of cap.  A similar cap with a lighter weight
geomembrane material was used at Kin-Buc Landfill in 1981.  The
Hackensack Meadowlands Development Commission is using the
textured geomembrane with native soil as a cap on two landfills.

A Task Group member requested information on how to obtain a
Technical Assistance Grant.

Response;  The Task Group received a Technical Assistant Grant as
requested.

-------
A question was raised by the OBEC about whether the proposed
alternative for OU-l has a foundation sand layer under the cap.

Response;  For the proposed capping alternative, the regraded
landfill surface will be covered with new sand, a geogrid
material (to stabilize the clay layer), and then the clay layer.
A detailed description of Alternative 6 can be found in the
Feasibility Study  (FS) located in the listed repositories.

Another inquiry from the OBEC concerned assurance that the
engineering specifications for OU-l will be fulfilled during
construction.

Response;  The engineering specifications and plans will be
public documents upon their completion.  The NJDEP will hold a
public meeting at the end of the design phase, and prior to the
actual construction, to present the final design.  Every item
used in the construction for OU-l will have detailed specifics in
the final design.  The NJDEP and the design engineering firm will
have staff on-site during the construction phase to ensure that
the required materials are used.

The OBEC inquired about who is responsible for the post-closure
funding.

Response;  Under the Superfund program, the state is responsible
for the operation and maintenance phase.  The NJDEP will
establish funds to perform the O&M phase of the remediation.  The
Department has established a specific group to oversee this
phase, although the O&M could be delegated to the county, the
municipality, or responsible parties with NJDEP oversight.  The
O&M plan will be placed in the repositories with the other
documents for Global.

A question was raised by a Task Group member whether the leachate
and gas treatment facilities will be located in wetlands.

Response;  During the design phase, the precise size, type and
location of both facilities will be determined.  Additional
impacts on wetlands will be a consideration on where to locate
these facilities.

The OBEC inquired about what permits would be necessary for the
leachate treatment on-site with discharge to Cheesequake Creek;
who would be responsible for obtaining such permits; will the
RI/F8  process define the nature and type of permits required;
and how, if any, will the stormwater Runoff Regulations impact
the treatment facility.

Response;  In the design phase for OU-l, statutory and technical
requirements will determine the discharge limitations.  Under the
Superfund program, these discharge limitations must still meet

-------
 all normal permit requirements for any landfill, storm run-off,
 and surface water discharge to the Cheesequake, even though a
 permit  is not  issued.  The monitoring and discharge requirements
 are the same as would be required for a permit.  The NJDEP would
 make all monitoring data available to the public.

 A question was raised by a Task Group member regarding the
 "burning11 of landfill gas for treatment and how clean the
 emissions would be.

 Response;  The NJDEP will collect data during the design phase
 which will be  used to develop a state-of-the-art gas treatment
 facility that  must meet New Jersey State air quality standards.

 Two members of the Task Group stated that trees should be planted
 behind  the London Terrace Apartments.

 Response;   Whether or not tree planting can be funded by
 Superfund as a part of OU-1 will be evaluated during the design.

 An inquiry was made by a Task Group member concerning the access
 route for trucks during the construction phase of Global.  A
 resident questioned the interaction between the Global
 construction phase traffic and the road construction at Ernston
 Road and Route 9.

 Response;  As  part of the design phase of OU-1, a transportation
 plan will be developed.  The only route to Global is through that
 intersection.  Depending on the schedule for road construction
 and the construction at Global for OU-1, there may be traffic
 problems.  NJDEP will work closely with local officials to limit
 traffic impacts as much as possible.

 The OBEC requested copies of all reports concerning Global
 Landfill from  NJDEP in addition to any placed in the site's
 repositories listed in the February 1991 Proposed Plan.

 Response;  As  a member Task Group, OBEC has had direct access to
 all reports concerning Global Landfill.  In the future NJDEP will
 provide documents regrading the Global Landfill Site to the Old
 Bridge Environmental Commission, the Task Group-, as well as to
 all the repositories listed in the February 1991 Proposed Plan.

 Comments from  a Task Group member and the OBEC concerned the gas
pipeline that  runs through the Global Landfill/ and whether it
will be relocated, by whom, and who will pay for the relocation.

Response;  The Transcontinental Gas Pipe Line Corporation
 (Transco) has  a 42-inch high pressure natural gas pipeline that
transects the  site, and is covered by 12 to 15 feet of waste, in
the northwest  section of the landfill area.  The NJDEP is
discussing the relocation of the pipeline with Transco.  The

-------
question of responsibility for the movement of the pipeline is a
legal issue.  The New Jersey Attorney General's Office is
reviewing this issue.

A resident inquired about time schedules/ and the OBEC requested
that a detailed explanation of the OD-1 design and construction
processes, with estimated timetables - schedule of goals or
milestones, be included in this document.

Response;  The following schedules are NJDEP's best estimates for
each of the operable units:
OU-1      Record of Decision
          Design Phase - Start
          Design Phase - Completion
          Construction Contractor Proposal Request
          Construction Contract Award
          Construction - Start
          Construction - Completion

OU-2      Phase I Field Investigation
          Phase I Remedial Investigation
            Report Completion
          Phase 2 Field Investigation
          Phase 2 Remedial Investigation
            Report Completion
          Record of Decision
          *Design Phase - Start
          *Design Phase - Completion
          Construction - Start
          Construction - Completion
Summer
Winter
Winter
Winter
Summer
  Fall
  Fall
1991
1992
1993
1993
1993
1993
1995
    Ongoing

Winter 1993
Spring l?93

Winter 1994
Spring 1994
Spring 1994
  Fall 1995
Winter 1995
Winter 1997
     * If required, based on Record of Decision for OU-2.

-------
WRITTEN COMMENTS FROM THE GLOBAL LANDFILL PRP GROUP -
Submitted Mav 6. 1991

The following Comments and Responses are presented in the format
of the written comments from the Global Landfill PRP Group.

I. Introduction
          The NJDEP was arbitrary in classifying Global Landfill
as a hazardous waste site.

Response:  While Global Landfill was not permitted as a hazardous
waste landfill, evidence indicates that significant amounts of
hazardous waste and hazardous substances were improperly disposed
of a*: the site.

Former landfill employees, who were personally involved in the
disposal of tens of thousands of drums of hazardous wastes and
hazardous substances at the landfill, provided this information
to NJDEP.  Their information was corroborated in 1987, when test
pits uncovered metal drums of hazardous wastes in areas
designated by these former employees as containing buried drums.

Landfill facility reports, which summarize information regarding
volume and types of waste disposed in landfills, indicate that
tons of waste, including both hazardous waste and hazardous
substances, were disposed of in the Global Landfill.  These
include the following:  furnace flue dust, a source specific
hazardous waste (K-061) under RCRA and New Jersey Hazardous Waste
Regulations; paint waste; filter residuals containing the
hazardous substances toluene, acetone, phenol, and formaldehyde;
asbestos; heavy metals; organics; and polychlorinated biphenyls.

Based upon the evidence that hazardous wastes were disposed at
Global Landfill, and the resultant documented potential threats
to human health and the environment, New Jersey's Hazardous Waste
Regulations are relevant and appropriate for the capping of
Global Landfill.

II.  NJDEP has not complied with the NCP's data collection and
     analysis requirements and/ as a result, has selected a
     preferred remedial alternative that is not cost-effective
     and is beset with serious technical deficiencies

          NO Remedial Investigation was performed.
Response:  EPA Guidance entitled "Conducting Remedial
Investigations/Feasibility Studies for CERCLA Municipal Landfill
Sites" (OSWER Directive 9355.3-11, February 1991) (RI/FS
Guidance) , states that since most CERCLA municipal landfill sites
are similar, the RI/FS process, including the Site
Characterization (Remedial Investigation Report) , Risk

                                8

-------
Assessment, and the Development of Remedial Alternatives, nay be
streamlined.  With respect to the Global Landfill site, NJDEP
believes that the groundwater, leachate, and drum excavation data
collected throughout the five year involvement of Killam
Associates, provides the basis for an adequate site
characterization of the site.  As a result of this data and
analysis it has .been determined, pursuant to EPA guidance
Directive:9355.3-11FS and the National Contingency Plan (NCP)
Section 300.430(a)(1)(iii)(B), that a containment technology is
appropriate at Global Landfill.

Commentt  No Quantitative Risk Assessment was performed..

Response;  The data presented in the FS clearly indicates that
the leachate .seeps and the shallow aquifer (which is in hydraulic
contact with the lower potable aquifer) are contaminated with
hazardous substances.  Both aquifers discharge to the wetlands
and surface waters at levels which exceed State and Federal
standards.  The release and migration of hazardous substances
from the landfill pose a potential risk to human health and the
environment.  As stated in the RI/FS guidance on municipal
landfills, a qualitative risk assessment that describes the
exposure pathways, and qualitatively describes the risk to
receptors, is sufficient to establish risk.  While a Quantitative
Risk Assessment is not required for OU-1, one Will be performed
during the RI/FS for OU-2.

Comment;  NJDEP did not account for interdependence between the
two operable units.

Response;  NJDEP is well aware of the potential interrelationship
of the remedy selected in this Record of Decision and the
selected remedy for the second operable unit.  For this reason, a
decision has been made to implement off-site treatment as an
interim remedy for leachate disposal, pending the selection of
the remedy for the second operable unit.

The cap will employ collection systems for leachate seeps,
landfill gasses, and stormwater management.  The possible future
collection systems for groundwater collection and treatment would
be no less implementable or effective as a result of
implementation of OU-1.

Comment;  Insufficient geotechnical study was performed.

Response;  The degree of geotechnical study performed at the site
has been extensive and reiterative in nature.  The study
performed by French and Parello Associates (F&P) originated in
1989 and was based on soil boring data which was reviewed by
NJDEP.  This report was subsequently refined in 1991, based on
additional soil borings.  The U.S. Army Corps of Engineers
reviewed the F&P report and concurred with the assumptions made

                                9

-------
 regarding  site conditions, the method of calculation used, and
 the  level  of confidence attributable to the results.  The
 allegation that an inadequate amount of geotechnical study was
 performed  is inaccurate.  The assumptions made in the development
 of vemedial alternatives for the cap and berm were conservative
 due  to the previous slope failure, which suggests the danger of a
 subsequent slope failure at the site.  Due to the heterogeneous
 nature of  the waste disposed of at the site, there is no
 practical  way to gain a high level of confidence in certain
 geotechnical parameters such as shear strength of the refuse.

 Comment;   No treatability studies were performed on the leachate
 seep stream.

 Response;  Treatability studies may be performed in design.

 qommftTifc'   There was inadequate data on landfill refuse
 characteristics to choose a gas collection and treatment system.

 Response;  The effects of settlement on subsurface structures
 (i.e. gas  collection wells or associated piping), preferential
 flow paths and chemical characteristics of the refuse can be
 either predicted or estimated for the purposes of developing a
 gas  collection and treatment alternative.

 Comment;   No Field Sampling Plan, Quality Assurance Plan or
 clearly defined data quality objectives.

 Response;  Although no Field Sampling Plan or Quality Assurance
 Plan were  supplied for the Killam Feasibility Study, the data was
 collected  in accordance with New Jersey Pollution Discharge
 Elimination System permit requirements and deemed by EPA and
 NJDEP to meet data quality objectives.

 Comment;   The refuse strength parameters used by F&P in their
 1991 study were inappropriate.  Although the 1984 Woodward Clyde
 Consultants report, the 1989 F&P report, and 1991 F&P report
 include the results of stability analyses for the landfill
 against sliding, all base the analyses on waste strength
parameters that are neither site-specific nor appropriate.
 Inexplicably,  the fieldwork ignored the strength of the refuse as
a data needed.   As a result of this omission, the Proposed Plan
 erroneously assumes that the Global Landfill is unstable.

Response;  The analyses used by F&P to assess the stability of
the  landfill under present and proposed loading conditions placed
a major emphasis on the geotechnical parameters.  These
parameters included the unit weights and strengths of the refuse
materials  and the underlying organic foundation soils.

F&P's evaluation assessed the merits of performing field
measurements of the refuse parameters.  Landfill materials are

                                10

-------
extremely variable; if a field evaluation was performed, the
question of representativeness would arise.  Due to the
heterogenous nature of the landfill, testing of particular
sections may result in parameters which are not representative of
the entire landfill, and would not provide any additional level
of confidence in the parameters selected than what could be
obtained from empirical published data.  F&P chose data that are
consistent with recently published parameters.

In order to back calculate the refuse strength, the following
parameters have to be determined:  geometry of failure surface,
unit weight and strength of the organic soils, and the unit
weight of the refuse.  The unit weight of the refuse value is
significant since it is the driving force producing instability.
In the 1990 F&P study, a unit weight of 50 pounds per cubic foot
(pcf), and a saturated unit weight of refuse below the water
table of 70 pcf were used.  This is within the range of typical
values appearing in recent publications.  The Global Landfill PRP
Group selected a unit weight of 76.4 pcf, which is above the
typical range of unit weights in any of the references F&P have
seen.  In order to establish equilibrium, the resisting strength
must be increased if the driving force is increased.  Therefore,
by starting a back analyses with an unrealistically high unit
weight or driving force, the refuse strength parameter required
for equilibrium is also unrealistically high.  The Global
Landfill PRP Group's assessment of the refuse strengths is
significant because they used the errant higher strength in their
stability analyses, concluding that the factors of safety for the
slopes under proposed loading conditions do not warrant
construction of the berm.

Comment;  The Proposed Plan is based on the premise that
substantial movement of the southeast sideslope is now occurring,
but NJDEP has not performed any monitoring for slope stability as
called for in the NCP and EPA guidance.

Response;  Sensitivity evaluation of the underlying soils
indicates that the southeast sideslopes are subject to creep
movement.  Sensitivity is defined as the ratio of undisturbed
strength to remolded (or disturbed) strength.  Materials that are
highly sensitive are susceptible to both acute slope stability
failure, and long-term creep movement.  In addition, there is
some evidence of slope movement of the southeast sideslope as
indicated by the hummocky ground surface.  The U.S. Army Corps of
Engineers concurs with this observation.

Commentt  Since the drum excavation was outside the main
landfill, and due to a lack of analysis of the leachate, the true
characterization of the landfill waste is in doubt.

Response;  RI/FS Guidance states that "Characterization of a
landfill's contents is generally not necessary because

                                11

-------
 containment  of the  landfill contents, which is often the most
 practicable  technology, does not require such information."
 Notwithstanding the fact that RI/FS Guidance requires minimal, if
 any waste characterization, characterization of the landfill
 contents was performed, and included:  landfill facility reports,
 statements from former landfill employees, magnetometer studies,
 drum excavations, and leachate sampling and analyses.

 Landfill facility reports, which summarize information regarding
 volume and types of waste disposed in landfills, indicate that
 tons of waste, including both hazardous waste and hazardous
 substances,  were disposed of in the Global Landfill.  These
 include the  following:  furnace flue dust, a source specific
 hazardous waste (K-061) under RCRA and New Jersey Hazardous Waste
 Regulations; paint  waste; filter residuals containing the
 hazardous substances toluene, acetone, phenol, and formaldehyde;
 asbestos; heavy metals; organics; and polychlorinated biphenyls.

 Former landfill employees stated that they were personally
 involved in  the disposal of tens of thousands of drums of
 hazardous wastes and hazardous substances in both sections of the
 landfill.  These allegations led to an exploratory excavation of
 the northwest extension.  A total of 63 drums were discovered, 18
 of which were removed for sampling and analysis; 11 contained
 hazardous waste based on EPA limits and an additional three drums
 contained hazardous waste based on NJDEP limits.  The drums
 contained numerous  hazardous substances including:  xylenes,
 toluene, ethylbenzene, chlorobenzene, trichloroethylene,
 tetrachloroethylene, arsenic, chromium, copper, lead, nickel,
 zinc, and some base neutral compounds.

 As part of a NJPDES quarterly monitoring program, leachate
 samples from exposed seeps have been collected for analysis from
 October 1987 to April 1990.  Since 1987, concentrations of
 leachate indicator  parameters (BOD, COD, ammonia, chlorides, TDS,
 hardness, and iron) were found to be elevated.  Volatile organics
 detected in the leachate consisted primarily of benzene-related
 compounds.  Chlorobenzene was found at concentrations up to 4,400
micrograms per liter (ug/1), which far exceeds the groundwater
 quality standard of 4 ug/1.  This further illustrates the
potential impact the leachate is having on the groundwater and
wetlands.

These waste characterization efforts clearly comply with the
 requirements of the NCP and the RI/FS Guidance referred to above.

Comment;  Insufficient air quality monitoring has been conducted
at the site.

Response;  NJDEP acknowledges that little air analysis was
performed at the site.  However, this analysis was not necessary


                                12

-------
 for the  selection  of the cap or the gas collection system.  The
 selection of  either a  flare or a thermal oxidation unit will
 depend upon additional air characterization to be performed
 during design of OU-1.  Based upon this information, the decision
 to  employ either a flare or a inore advanced gas treatment system
 will be  made.

 poHnnenti   in  view  of the data gaps, and the resulting safety
 factors  applied to protect against a future slide, a temporary
 cap is warranted until the settlement rate has stabilized.

 Response;   An analysis of temporary or interim cap alternatives
 was performed for  Global Landfill.  The alternatives ranged from
 a soil cover  (no impermeable cap), exposed synthetic caps, to
 variations  of conventional solid waste and hazardous waste caps.
 The less  expensive alternatives (soil cover and exposed
 synthetic)  were rejected due to either non-responsiveness to site
 concerns,  or  construction/maintenance difficulties.  The
 remaining alternatives complied with NJDEP requirements, however,
 their costs were close to those for standard NJDEP cap designs.
 The decision  was made  to implement a final cap, rather than
 install an  interim cap and upgrade or modify it in the future.

 III.  The  Proposed  Plan alternative is not justified by the
 purported risks alleged to exist at the site.

 Comment;  The  Qualitative Risk Assessment is inadequate for the
 purposes  of the study, and does not comply with the requirements
 of  the NCP.

 Response;   This claim  by the PRPs is erroneous.  The RI/FS
 guidance  states:   "Because options for remedial actions at
 municipal landfill sites are limited, it may be possible to
 streamline  or  limit the scope of the baseline risk assessment by
 (1)  using a conceptual model ... to perform a qualitative risk
 assessment  ..."  The Guidance goes on to state that
 "...Quantitative assessments ... are not necessary to initiate
 remedial  action."  Use of qualitative instead of quantitative
 risk  assessments for municipal landfills is clearly an acceptable
 procedure under the RI/FS Guidance, and complies with the
 requirements of the NCP.  One purpose for this option is to
 streamline  remedial action decisions, and allow rapid
 implementation of  protective measures for the major problems at
municipal landfills.   The need for "rapid implementation" of the
 remedy at this site is clearly warranted given the fact that:
hazardous substances have been disposed of, and are present in
the Global  Landfill; contamination has been detected in both the
 leachate seeps and groundwater above State and Federal maximum
contamination levels (MCLs); the landfill is marginally stable,
having previously  experienced a sideslope failure; and the
landfill routinely receives infiltration which may flush
                                13

-------
hazardous substances from the fill material into the groundwater
and adjoining wetlands..

Comment;  The Concern Index Approach is flawed.

Response;  A Hazard Index is calculated by dividing the
quantified dose of a toxic compound to a reference dose for that
compound.  In the absence of data necessary to derive Hazard
Indices, the purpose of the Concern Index approach was to obtain
a frame of reference to qualitatively evaluate the relative
levels of source concentrations and their potential impacts on
the public health and the environment.  With respect to the
applicability of the Concern Indices, they are put forward as a
means of comparison of landfill concentrations to State and
Federal MCLs.

Comment:  Methane migration does not reach the residential areas
and conclusions that air transport is a complete pathway is
invalid.

Response;  This PRP claim is invalid.  The Superfund Public
Health Evaluation Manual (1986) requires four elements to
comprise a "complete" exposure pathway.  These are a) a source
and mechanism for chemical release in the environment; b) a
transport medium; c) a point of potential environmental or human
exposure; and d) an exposure route at the contact point.

The PRP's comment incorrectly implies a chemical from the site
must be detected in the residential area before a "complete"
pathway can be found to exist under EPA risk assessment protocol.
The fact air samples were not taken in the residential zone for
some specific site related chemicals does not support the PRPs
conclusion that those chemicals have not or will not in the
future reach the residential zone and come in contact with
individuals in that zone.  Only a potential point of exposure
need exist; an actual exposure event or actual detection of a
specific chemical in the residential area is not required for a
determination that a "complete" pathway exists under risk
assessment protocol.


IV.  The agency has failed to integrate the first Operable Unit
     with any later groundwater remediation operable unit.

Comment;  The remedy proposed for OU-1 will be constructed
entirely within the property boundaries.

Response;  The remedy proposed for OU-1 will extend beyond the
property boundaries if it becomes necessary for engineering
implementation, as determined during the design phase.
                                14

-------
With respect to the integration of the two operable units, the
implementation of OU-1 will not result in an increase in the
amount of wetlands disrupted as a part of OU-2.

Comment;  No evaluation vas made of the wetlands to be disrupted
during implementation of OU-1.

Response;  An evaluation of the wetlands in the area immediately
surrounding the landfill which may be impacted by the
implementation of OU-1 was performed.  This evaluation was
finalized in the April 1991 report entitled "Final Supplemental
Report on Wetland Evaluation Technique (WET 2.0) Analysis", and
is in the Administrative Record.

Comment;   The construction of the berm may preclude the
effective use of a slurry wall as a component of OU-2.

Response;  It is the opinion of NJDEP that the proposed berm will
not interfere with construction of a slurry wall, if a slurry
wall is called for in OU-2.  The slurry in the trench should
maintain the trench stability until a cement-bentonite slurry is
placed.  If trench stability becomes a concern, then various
construction methods, such as construction of the trench in
sections, can be employed.  Furthermore, a berm will actually
facilitate slurry wall construction by providing a working pad
from which equipment can operate.

Comment;  OU-2 will in all probability extend beyond the property
limit of the landfill, therefore, it is more logical to integrate
OU-2 into OU-1, so that wetland impacts are reduced.

Response;  NJDEP intends to minimize adverse impacts on wetlands
in both OU-1 and OU-2, consistent with the need to take
appropriate and timely actions to protect public health and the
environment.

Comment;  If NJDEP follows the preference for on-site treatment
and discharge as part of OU-1, a treatment system for leachate
could be designed and built prior to leachate characteristic and
volume changes, and before the groundwater treatment system, if
any, is analyzed and determined.  This could lead to duplicate
treatment systems, and therefore, is not cost-effective.

Response;  The preferred leachate collection and treatment system
is Option 3 (on-site treatment with discharge to surface water).
In the interim, Leachate Option 1 (disposal at an Industrial
Waste Treatment Plant) will be employed until the RI/FS for OU-2
is completed.  At that time, the design and installation of a
combined leachate and groundwater system can be considered.  The
leachate seep treatment option chosen here would be designed to
be considerate of possible future expansion to accommodate
additional treatment capacity.

                                15

-------
V.   The agency has failed to include any interim action
     alternatives which account for data gaps and which are
     commensurate with the low level of risk at the site.

Response;  Various interim capping alternatives were evaluated in
the FS.  The alternatives ranged from a soil cover (no
impermeable cap), exposed synthetic caps, to variations of
conventional solid waste and hazardous waste caps.  The less
expensive alternatives (soil cover and exposed synthetic) were
rejected due to either non-responsiveness to site concerns, or
construction/maintenance difficulties.  The remaining
alternatives complied with NJDEP requirements, however, their
costs were close to standard NJDEP cap designs.  The decision was
made to implement a final cap, rather than install an interim cap
and upgrade or modify it in the future.


VI.  The geogrids, sand, berm, leachate treatment plant, and cap
     contained in the Proposed Plan alternative are neither
     necessary nor properly designed.

Comment;  Slope stability analyses with appropriate soil and
refuse parameters indicate that the landfill slopes are stable,
and therefore, geogrids are unnecessary.  In addition, the need
for geogrids is unjustified since the landfill has been closed
for more than -.seven years, and it is far more justified to assume
that the major part of final settlement has already occurred.

Response; Based on consolidation analyses of the organic soils,
which vary in thickness around the landfill, some differential
settlement will occur as these soils continue to consolidate
under their existing loads.  Since the nature of the landfill
material is heterogeneous, the amount of settlement due to
decomposition and possible structural collapse of buried objects
is unpredictable, and can be very localized.  This makes it
difficult to assess the stresses and strains associated with the
cap without destroying its integrity.

Geogrids are that component of the cap which provides the
strength to mitigate differential settlement.  It is important
that the geogrids relieve the georoembrane of the stresses,
because if the geomembrane tears, the integrity-of the cap is
compromised and costs for repair will be great.

NJOEP believes that geogrids are necessary and can be
successfully installed.  In the design phase, it will be
determined if one or two layers of geogrid are required for the
purposes of cap sliding stability and differential settlement
concerns.

Comment;  In order to repair the geogrids, bodkin connectors
would have to be "needled" into the existing grids, an operation

                                16

-------
which may not be successful in restoring the grid's strength and
other properties.

Response:  NJDEP is of the opinion that cutting and repairing the
geogrids will not significantly reduce their effectiveness.  It
is common practice to use bodkin joint connections.

Comment;  A geonet could be used instead of the sand drainage
material immediately above the liner.

Response;  This could be considered during design.  However,
NJDEP believes that replacement of the 12 inch sand, or sand and
gravel layer, with a geonet does not represent a significant cost
savings.

Commenti  other landfills under the jurisdiction of NJDEP, such
as GEMS or Helen Kramer, do not include geogrids.  This indicates
an inconsistency on the part of NJDEP.

Response;  Site characteristics are markedly different at each
site.  Geogrids have been determined to be necessary at the
Global Landfill because of slope stability and surrounding
wetlands.

Comment;  A berm is unnecessary based upon back analyses.

Response;  F&P stability analyses indicate that marginal factors
of safety exist, and a berm is required at the toe of the east
slope for construction of the proposed cap.

Comment;  Monitoring may be necessary during construction of the
berm.  In addition, soils underlying the berm may contain waste
that would permanently be trapped under the berm and outside the
cap.

Response;  During design, a monitoring program for berm
construction will be established, along with the design of the
berm.  Also, the area under the proposed berm may be explored for
possible refuse.  At the present time, NJDEP does not intend to
allow refuse to be left under the berm.

Comment;  The leachate treatment plant is not cost-effective for
two reasons.  First, the Proposed Plan alternative does not take
into account the sharp drop in flows after the first year.
Second, it does not take into account the efficiencies associated
with a comprehensive treatment program in OU-2.  It would be more
sensible and cost-effective to address any leachate treatment
along with the groundwater treatment at the time of OU-2.

Response;  The preferred leachate collection and treatment system
is Option 3 (on-site treatment with discharge to surface water).
However,  a contingency system, Leachate Option 1 (disposal at an

                                17

-------
Industrial Waste Treatment Plant), will be employed until the
RI/FS  for OU-2 is completed.  At that time, the design and
installation of a combined leachate and groundwater system can be
considered.  The leachate seep treatment option chosen here would
be designed to be considerate of possible future expansion to
accommodate additional treatment capacity.

Comment;  The flexible membrane liner to be placed over clay
material is accompanied by risks associated with moisture
collecting under the liner during construction.  Moisture may
originate from condensation, or consolidation of the clay from
the weight of the materials above, as was the case in the
Kettleman Hills Waste Landfill slope failure.  The wetted clay
may lead to a stability problem.

Response;  The referenced landfill experienced a failure in its
liner  system, not the cap, and a contributing factor was a
buildup of moisture under the geomembrane overlying the clay.
The moisture buildup was attributed to several possibilities that
are not applicable here, since a cap system is being utilized at
Global.  In addition, the stability of the cap components will be
evaluated during design.

Comment;  Until its closure in 1984, the landfill, like other
municipal landfills, was authorized to receive up to 100, and for
a period of time, 1000 kilograms per month of hazardous waste
from small quantity generators.  Yet, the Proposed Plan would
treat  the site differently from a municipal site.  This site
should be closed as an ordinary municipal landfill.  In addition,
RCRA Subtitle C is not an ARAR.  RCRA Subtitle C does not require
a composite cap.  A solid waste cap, or its equivalent, should be
selected in the ROD.

Response;  The environmental data collected at and near Global
Landfill lead to a number of conclusions which support the need
for the selected remedial action at the site.  Hazardous
substances have been disposed of, and are now present in the
Global Landfill.  Groundwater data collected to date reveals that
groundwater quality in both the shallow aquifer and the Old
Bridge Sand aquifer (a source of public water supply) exceeds
MCLs for numerous hazardous substances, pollutants, and
contaminants.  Many of these substances were detected in drums
buried at the landfill, and in leachate flowing out of the fill
material.  For these reasons, it would not be appropriate to cap
this site as an ordinary municipal landfill.

Both New Jersey Hazardous Waste Landfill Closure Regulations,
subchapter 10, and Resource Conservation Recovery Act (RCRA)
Subtitle C have been identified as being relevant and appropriate
(NCP,  Section 300.400 (g)(2)) to the circumstances of the release
at Global Landfill as iterated above.  Both regulations address
closure of hazardous waste landfills to provide long-term

                                18

-------
minimization of migration of hazardous substances through the
closed  landfill.  Also, many of the hazardous substances
identified at Global Landfill are also listed as RCRA hazardous
substances.  The NCP states that EPA will often find RCRA
requirements are relevant and appropriate at a site, and that
these requirements may be relevant and appropriate where waste is
just similar in composition, even where it is not identifiable as
a RCRA  listed waste, and even for waste disposed of prior to 1980
(55 Fed. Reg. 8763).  In the case of Global Landfill the selected
remedy  would incorporate the composite cap features of NJDEP
Hazardous Waste cap.  The NJDEP Hazardous Waste Landfill Closure
Regulations (NJAC 7:26-10.8(i)) require specific cap features
that must be attained.  The selected remedy includes a modified
NJDEP Hazardous Waste cap that will attain a standard of
performance that is equivalent to that required under the New
Jersey  Hazardous Waste Landfill Closure Regulations.  Since the
New Jersey Hazardous Waste Landfill Closure Regulations require
specific cap features, such as a composite cap, then use of a
NJDEP Hazardous Waste cap for remediation of a site such as
Global  is clearly consistent with the RI/FS Guidance and the NCP.
The RI/FS Guidance states:  "A composite-barrier cap is to be
used when the landfill contains RCRA listed wastes, waste
sufficiently similar to RCRA listed waste, or RCRA characteristic
waste."  A composite-barrier cap may also be used at landfills
which contain much lower concentrations of hazardous contaminants
than that of RCRA listed or characteristic wastes, depending upon
site specific characteristics (RI/FS Guidance, p. 4-11).
Composite-barrier caps minimize infiltration into the fill
material, and provide greater protection against migration of
contaminants out of the fill material than single barrier caps or
closures with just soil cover.

RI/FS Guidance recognizes that where "... a groundwater
contaminant problem exists, a RCRA cap would serve to "... limit
infiltration of precipitation (RI/FS Guidance, p. 5-9).  The NCP
also recognizes that "... the mobility of the waste ... may be a
key concern in evaluating" the need for a highly impermeable cap
(55 Fed. Reg.  8763).

The purposes of closure under Subtitle C and the objectives of
CERCLA  remediation at Global are clearly the same (control of
release of hazardous waste and other contaminants into the
environment),  thereby reflecting accord with 40 C.F.R.
§  300.400(g)(2)(i).  The media regulated by Subtitle C under 40
C.F.R.   Part 264 include, inter alia, landfills, the same type of
media to be affected by this remedial action, thereby meeting the
intent  of 40 C.F.R. § 300.400(g)(2)(ii).  The substances
"regulated by" Subtitle C (i.e. hazardous waste) were not only
found at the site but also fall within the legal definition of
those same substances affected by CERCLA (i.e. hazardous
substances),  thereby meeting the intent of 40 C.F.R.
§  300.400(g)(2)(iii).  Finally, the actions regulated by

                               19

-------
Subtitle C  (e.g. closure of landfills), are similar to this
remedial action.

Therefore, the cap requirements of both New Jersey Hazardous
Waste Landfill Closure Regulations and RCRA Subtitle C are
relevant and appropriate for the capping of Global Landfill.

Comment:  The risk assessment does not justify using a hazardous
waste cap at the Global Landfill.

Response;  This PRP claim misconstrues the relationship between
remediation goals and risk assessments.  Risk assessments and
ARARs serve different functions.  The baseline assessment is
intended to be essentially an evaluation of the no-action
alternative (55 Fed. Reg. 8711).  The determination of whether
particular requirements are ARARs for a site is to be made
independently from the risk assessment (55 Fed. Reg. 8711).

VII. Group's proposed alternative

Comment;  The group's proposed alternative is presented in their
attached comments on the Proposed Plan, on pages 60 to 72.

Response;  It is NJDEP's opinion that the Global Landfill PRP
Group's proposed alternative is not cost effective from a
geotechnical viewpoint.  Based upon F&P's analyses, construction
of the stabilization berm is necessary.  The total amount spent
at the beginning of this project to preclude failure will be much
less than the amount which will be required should a failure
occur.  Given the sensitivity of the underlying organic soils,
and the fact that the east slopes are in a remolded state of
stress, NJDEP believes that slope failure will occur without a
berm.  The resultant effort to re-stabilize a slope after a
failure would most likely include the construction of a berm much
larger than presently proposed, impacting more wetlands than what
are presently anticipated.

The NJDEP recognizes that there are alternate ways of achieving
some of these intended functions.  The preferred alternative
achieves these objectives and minimizes disruption of the
wetlands.

VIII.  ROD Flexibility

Comment;  Flexibility should be extended to the design of the cap
and the determination of the necessity of the berm.

Response;  Due to the unique slope stability problems, and the
surrounding wetlands at Global Landfill,  it has been determined
that a berm is necessary.
                                20

-------
 Comment;  The Global ROD should have as much flexibility with
 regard to cap design as the Sharkey Landfill ROD.

 Responset  Site characteristics are markedly different at each
 site.  The selected remedy addresses the unique characteristics
 at the Global Landfill site.

 IZ.  Miscellaneous

 Comment;  OU-1, as a phased remedy addressing only source
 control, is only governed by certain action-specific ARARs, and
 not contaminant-specific ARARs.

 Response;  OU-1 is governed by action-specific and location-
 specific ARARs.

 Comment;  Under Section 121 of CERCIA, permits are not required
 for any proposed treatment plant.

 Response;  Under the Superfund program, discharge limitations
 must still meet all substantive permit requirements even though
 permits are not issued.  The discharge requirements are the same
 as would be required for a permit.

 Comment;  Without a requirement-by-requirement determination as
 mandated by CERCLA, no standard has an independent application to
 a cleanup under CERCLA.  The FS assumes the application of, and
 includes standards wholesale without the type of ARARs analysis
 required.  One example of this is that MCLs are not ARARs for
 either OU-1 or OU-2.  MCLs may be "relevant and appropriate" only
 for "ground and surface water that is a current or potential
 source of drinking water."  The water table aquifer is not a
 potable water source, and the nearest Old Bridge aquifer well is
 downgradient one mile from the landfill.  In addition,
 groundwater quality data in the Old Bridge aquifer reflects
 "background levels" of contaminants.

 Response;  This claim is erroneous.  The legislative history of
 the Superfund Amendments and Reauthorization Act of 1986 (SARA)
 indicates that aquifers which have any potential future use
 should be cleaned up to achieve MCLs.  Furthermore, MCLs must be
 applied not only at the tap, but whenever contaminated [ground]
 waters are found (Senate Congressional Record, October 3, 1986,
 p. S14915).

 Some of the hazardous substances present in the landfill and in
 the shallow aquifer may be migrating downward into the Old Bridge
 Sand aquifer, a source of public water supply.  Under the NCP,
MCLs and non-zero maximum contaminant level goals (MCLGs) are
potential ARARs, and may appropriately be used as cleanup goals
 in groundwater where it is or may be directly used for drinking
water.

                               21

-------
Groundwater data collected to date reveals that groundwater
quality in both the shallow and the Old Bridge Sand aquifers
exceeds MCLs for numerous hazardous substances, pollutants, and
contaminants, downgradient from the landfill.  For example,
cadmium, total chromium, benzene, chlorobenzene, and vinyl
chloride were not detected in upgradient wells in the Old Bridge
formation.  However, they were detected above MCLs in
downgradient samples, indicating that the landfill may have
affected this public water supply.  These downgradient
contaminant levels clearly are not "background levels" as the
PRPs assert.  Many of these hazardous substances were detected in
drums buried at the landfill, and in leachate flowing out of the
fill material.  The migration of these substances from the
landfill into the underlying aquifers, and possibly into the
nearby surface waterways will continue unless remedial actions
are implemented.  The selected remedy will limit and control
infiltration and surface runoff of precipitation, thereby
reducing leachate generation and migration into the groundwater
and surface waters.  The NCP states that operable units should
not be inconsistent with nor preclude implementation of the
expected final remedy.  OU-1 is a response action to contain
hazardous substances at the site which are impacting the
groundwater.  Therefore it is appropriate to examine MCLs as
ARARs in this ROD.

Comment:  Any -drum removal at this site must be limited to the
already excavated drums.

Response;  The decision whether or not additional excavation of
drums is necessary will be determined in design.

X.  Conclusion

Comment;  The Proposal suggested by the PRPs compares favorably
with remedial alternatives implemented at other New Jersey
landfills, and accepted by NJDEP as appropriate at those sites.

Response;  Site characteristics are markedly different at each
site.   The selected remedy addresses the unique characteristics
at the Global Landfill site.
                                22

-------
WRITTEN COMMENTS FROM THE OLD BRIDGE ENVIRONMENTAL COMMISSION-
Subndtted on March 12. 1991. and May 6. 1991

^fltnniATifrf  please provide a detailed explanation of remedial
processes to be done at the Global Landfill, and provide an
estimated timetable for completion of goals or milestones in the
process.

Response;  The components of this remedial action (OU-1) include
the following:

          Capping of the landfill with a modified hazardous waste
          cap;

          Slope stability enhancement through construction of a
          soil stabilization berm;

     •    Construction and operation of a gas management system;

          Construction and operation of stormwater and leachate
          management systems;

     •    Installation of a perimeter security fence to restrict
          access to the site; and

     •    Implementation of a monitoring program to ensure the
          effectiveness of the remedy.

OU-2 will address groundwater contamination from the site.
Selection of a remedial alternative for the OU-2 action will take
place at a later date.

The following schedules are NJDEP's best estimates for each of
the operable units:

OU-1      Record of Decision                          Summer 1991
          Design Phase - Start                        Winter 1992
          Design Phase - Completion                   Winter 1993
          Construction Contractor Proposal Request    Winter 1993
          Construction Contract Award                 Summer 1993
          Construction - Start                          Fall 1993
          Construction - Completion                     Fall 1995

OU-2      Phase I Field Investigation                     Ongoing
          Phase I Remedial Investigation
            Report Completion                         Winter 1993
          Phase 2 Field Investigation                 Spring 1993
                                23

-------
           Phase 2 Remedial Investigation
            Report Completion                         Winter 1994
           Record of Decision                          Spring 1994
           *Design Phase - Start                       Spring 1994
           *Design Ph?.*se - Completion                    Fall 1995
           Construction - Start                       Winter 1995
           Construction - Completion                  Winter 1997

      * If  required, based on Record of Decision for OU-2.

     int;   Will a protective sand bed be incorporated into the
engineering design.

Response;  For the proposed capping alternative, the regraded
landfill surface will be covered with new sand, a geogrid
material (to stabilize the clay layer), and then the clay layer.
A detailed description of Alternative 6 can be found in the
Feasibility Study (FS) located in the listed repositories.

Comment;   How will the specifications be written to ensure
compliance with engineering design, and what safeguards will be
incorporated?

Response:  The engineering specifications and plans will be
public documents upon their completion.  NJDEP will hold a public
meeting at the end of the design phase, and prior to the actual
construction, to present the final design.  Every item used in
the construction for OU-1 will have detailed specifics in the
final design.  NJDEP and the design engineering firm will have
staff on-site during the construction phase to ensure that the
required materials are used.

Comment;   Who is responsible for the post-closure funding?

Response;  Under the Superfund program, the state is responsible
for the operation and maintenance phase (O&M).  The NJDEP will
establish  funds to perform the O&M phase of the remediation.  The
Department has established a specific group to oversee this
phase, although the O&M could be delegated to the county, the
municipality, or responsible parties with NJDEP oversight.  The
O&M plan will be placed in the repositories with the other
documents  for Global.

Comment;   What permits are necessary for the leachate treatment
on-site with discharge to Cheesequake Creek; who would be
responsible for obtaining such permits; will the RI/FS process
define the nature and type of permits required; and how, if any,
will the Stormwater Runoff Regulations impact the treatment
facility.

Response;  In the design phase for OU-1, statutory and technical
requirements will determine the discharge limitations.  Under the

                               24

-------
Superfund program, these discharge limitations must still meet
all permit requirements for any landfill, storm run-off,  and
surface water discharge to the Cheesequake, even though a permit
is not issued.  The discharge requirements are the same as would
be required for a permit.  Th« NJDEP would make all monitoring
data available to the public.

qonmianfc'  should relocation of the pipeline be necessary,, who
will pay for its relocation?

Response;  The question of responsibility for the movement of the
pipeline is a legal issue.  The New Jersey Attorney General's
Office is looking into the matter.

Comment;  The OBEC requested copies of all reports concerning
Global Landfill from NJDEP in addition to any placed in the
site's repositories listed in the February 1991 Proposed Plan.

Response;  As a member Task Group, OBEC has had direct access to
all reports concerning Global Landfill.  In the future NJDEP will
provide documents regrading the Global Landfill site to the Old
Bridge Environmental Commission, the Task Group, as well as to
all the repositories listed in the February 1991 Proposed Plan.

Comment;  The OBEC is concerned that the construction and the
operation of the proposed on-site treatment plant and the
associated costs, operation, and liability will someday fall
under the jurisdiction of the Township.  Unless the Township
could be indemnified against any courses of action that may
transpire as a result of any violations to any regulation, be it
air or water should the Township take over operation of the
plant, they would be exceedingly reluctant to agree with this
course of action.

Response;  Any on-site treatment plant will be constructed,
operated and maintained for the life of the plant, and eventually
dismantled by the agency or party funding the site remediation.
It is not foreseeable how the construction, operation, and
maintenance of an on-site treatment plant would fall under the
jurisdiction of the Township of Old Bridge.
                                25

-------
WRITTEN COMMENTS FROM TRANSCONTINENTAL GAS PIPE LINE CORPORATION-j
Submitted March 20. 1991

Comment;  Transco is willing to relocate its existing facilities
and loop around the site, however, Transco is unwilling to
undertake the relocation from both a regulatory and an economic
standpoint unless it is on a fully reimbursable basis.

Response?  The question of responsibility for the movement of the
pipeline is a legal issue.  The New Jersey Attorney General's
Office is reviewing this issue.
                               26

-------
     ENVIRONMENTAL COMMISSION               Ye ' -."SN-> */                   MIDDLESEX COUNTY. NJ.
            (201) 721-5600
                              TOWNSHIP OP OLD BRIDGE
          Blanche D. Hoffman, Chairwoman
          Joyce Caldon
          Susan E. Knauf
          George R. Koehler
          William Schnitzerling
          Robert Sommers
          Gary Szelc
                                                      March 12, 1991
          Ms. Grace L. Singer, Chief
i,         Bureau of Community Relations
          Division of Hazardous Site  Mitigation
-          New Jersey Department of Environmental Protection
J         CN 413
t         401 East State St., 6th Floor
|         Trenton, NJ 08625
          RE:   Feasibility Study for Capping of the Global Landfill Superfund Site
          Dear Ms. Singer:

          On behalf of the Old Bridge Environmental Commission, we offer the following comments and
          questions regarding the proposed plan for the remedial alternative for the proper closure of the
          Global Landfill. We recognize that the. capping alternative and the subsequent engineering
          design for the gas venting system and the leachate collection system as well as the remediation
          of contaminated groundwater will be incorporated into the Complete Feasibility Study for the
          closure of Global as a Superfund Site. We ask for a detailed explanation of the process, as well
          as an estimated time table for completion of goals or milestones in the process.  It is assumed
          that these requirements will then be set  forth in the Record of Decision (ROD).  We also
          request an explanation of the steps  in  the remedial action,  including the time frame of the
          remedial design, the subsequent  remedial action and the plan both technical and financial for
          the operation and maintenance of the post closure monitoring.
                                                                    
-------
 Ms. Grace Singer
 March 12,  1991
 Page 2 of 2
The selection of  Alternative 6, a modified  NJDEP  Hazardous  Waste  Cap, as  the  most
technically feasible for Global,  as presented  did not include the incorporation of what  is
commonly referred to as a foundation layer. This layer generally consists of a protective sand
bed and is laid first. Is this to be incorporated into the engineering design, and if not, was its
incorporation considered and rejected as either not necessary or infeasible?

As in  the capping of any landfill, the engineering specifications are critical.  How will the
specifications be written to ensure compliance with the engineering design?  What safeguards
will be incorporated and who will maintain supervision of the process? Who will be responsible
for the post closure financial plan?

The proposed  option for the treatment of the leachate raises many questions. Who  would be
responsible for the design, operation and maintenance of this facility and be responsible for the
associated permits? Will the RI/FS process define the nature and type of the permits  required?
What will be the nature of the NJPDES permits required?  How, if any, will the Stormwater|
Runoff Regulations impact this  facility?   Our concern here is deterioration of CheesequaW|
Creek, should it be determined to be the receiving body.

Our last question regards the Transcontinental Pipeline.  Should relocation of the pipeline be
necessary,  who will pay for its relocation?

Regardless of alternatives chosen  either for the capping of the landfill or  final remediation
design for Global as a Superfund site, the  Environmental Commission respectfully requests  to
receive copies of all reports conducted in relation to the Landfill.  This copy  would be  in
addition to any sent to the Health Department or the  Library.

We appreciate the  opportunity to comment on this proposal.

                                               Very Truly Yours,
                                               Blanche D. Hoffman
:sek

-------
         FRI
                                                            COUNTY. *.•
                  TOWNSHIP OF OI-D BRI3X5E


                                   Kay 6, 1991

 Ms. Grace L. Singer, Chief
 Bureau of Community Relations
 Division of Hazardous Site Mitigation
 Nev Jersey Department of Environment Protection
 401 East State St., CN 413
 Trenton, NJ 08625-0413

 RI: Global Landfill Super fund Site, Township of Old Bridge

 Dear Ms. Singer:

 As a follow up to our comments  and letter read during the Public
 Meeting  on March 12,  1991 to discuss  the  completion of  the
 Feasibility Study for the Global Landfill Super fund,  the Old Bridge
 Environmental Commission wishes  to augment our remarks as follows:

     l)   We are concerned that the construction and the operation
     of the proposed  on site treatment plant  and  the associated
     costs, operation, and  liability will someday  fall  under the
     jurisdiction of the Township.  Unless  the Township could b«
     indemnified against any courses of action that may transpire
     as a result of any  violations to any  regulation, be it air or
     water should the Township  take over  operation  of the plant,
     we would be  exceedingly reluctant tc agree  with this course
     of action.

     2)   We recommend that the planting of trees along the buffer
     zone near London Terrace be  given  strong consideration from
     the Department for inclusion in the remedial design.

we appreciate the opportunity to consent on the Proposed Plan.

                                   Very truly yours,
                                   Blanche D. Hoffman
                                   Chair, Old Bridge Environmental
                                   Commission
copy: Scott Weiner, Commissioner, NJD£P
      Peter La timer, NJDEP, Site Manager
      Barbara Cannon, Council President, Township of Old Bridge
      Arthur Haney, Mayor, Township of Old Bridge
      Thomas SiXorsXi, Health Officer, Township of Old Bridcr

-------
                                                                        MAR 2 IBM
 Transcontinental Gas
 Pipe Line Corporation
 Al	£._.,~V^

 2800 Pen Oak •outovird
 P. 0  Bo. 1396
 Houston. Tt»tl 77251-1396
 713-439-2000


 Ms.  Grace Singer,  Chief
 Bureau of Community Relations
 New Jersey Department of Environmental Protection
 CN413, 401 East State Street, 6th Floor
 Trenton, New Jersey 08825-0413


 RE:   The Global  Landfill Superfund  Site ("Site") in Old  Bridge Township,  Middlesex
      County, New Jersey

 Dear Ms. Singer:

      Transcontinental Gas  Pipe Line Corporation  ("TGPL") would like to  take this
opportunity to  thank both the United States Environmental Protection Agency ("EPA")
and  the New Jersey Department of Environmental Protection ("NJDEP")  for allowing it
to review and comment on the Proposed Plan ("Plan") forwarded under cover of Ronald J.
Borsellino's letter.

     TGPL is a major interstate natural gas pipeline operating a 12,000 mile system and
transporting natural gas  from Gulf Coast production areas to Northeast market areas.
Upon review of the Plan, it  appears a portion of TGPL's system lies within an easement
which runs  beneath  the above-referenced Site.   The easement was granted prior  to
commencement of activities at the  Site and reserved specific rights, outside the control
of TGPL, to the surface owner.

     As previously discussed with NJDEP, regarding that portion of TGPL's system lying
beneath the Site, TGPL is willing, if feasible, to relocate its existing facilities and loop
around the  Site to alleviate any potential future problems associated  with NJDEP's
maintenance and oversite of the Site.  However, TGPL is unwilling to  undertake the
relocation from both  a  regulatory  and an economic standpoint unless it is on a  fully
reimbursable basis (i.e., TGPL bears no cost of any type or nature).

     TGPL again thanks both the EPA and the NJDEP for soliciting its comments.
                                         R. TJ. Graves
                                         Senior Vice President
                                         Transmission Operations
                                         Vice President
                                         Environment*! and Safety Affairs

-------
                   EDWARDS Ac ANGELL
Counsellors at Law
Lrofljrd R Cli»i
Citergt A. Rodentuuim
Irim M Frnhrh
Alfred R. pjluni
Ltnit «'rifhi
•ofein F. PrKi
Sine* 6. Rohn
Supkm *: O'Conntll
Afldm H. Dononn
tr« P. Mixlkr
Rcliiu A. Mneiki
Kf»m M. V«nan
                                                     Gateway One, Suite 702
                                                     Newark, NJ 07101
                                                     (TJI)613-1616
                                                     Telecopier: (101) 613-7717
                               May 6, 1991
           VIA BAND DELIVERY
           Grace  Singer, Chief
           Bureau of Community  Relations
           New Jersey Department  of Environmental  Protection
           CN 413
           401 East State Street,  6th Floor
           Trenton,  New Jersey  08625-0413
           Dear Ms.  Singer:

                     Enclosed  herewith are  the Comments  of the Global Land-
           fill  PRP Group  Concerning  the February 1991  New Jersey  Depart-
           ment  of Environmental  Protection  Proposed Remedial Action Plan
           for Global Landfill,  Old Bridge Township,  Middlesex County, New
           Jersey  ("Comments"),   with appendices.   Also  enclosed  herewith
           is  a  copy of  the  transcript  of  the deposition of  Richard  J.
           Sullivan,  which was conducted on November  13,  1990 in  a  litiga-
           tion  caption  Lamb,  et  al.  v.   Global  Landfill  Reclaiming,  'et
           3.ij-,  Superior  Court  of New  Jersey,  Middlesex  County Law Divi-
           sion, Docket No. W-15349-88.
                     The  membership   of  the  PRP  group   is   set  forth  in
           Appendix E  to the  Comments.   Please  be  advised,  however,  that
           the  membership  may change;  if  so,  an  amended  Appendix will be
           submitted promptly.

                     The  Comments are  submitted  pursuant  to  the  provisions
           of  CERCLA   and  the  regulations  promulgated   pursuant  thereto.
           The  Comments  do  not  constitute the waiver   of  any  rights or
           positions on  the  part  of the  Global  Landfill  PRP Group  or any
           of  its  members;  additionally,  the  Comments  do  not  constitute
           any  admission of  liability on  the  part  of the Global  Landfill
           PRP  Group or  any of  its members.  Finally, the  members  of the
           Global  Landfill PRP Group do not purport  to represent  the views
           of any  other person or  entity.

                     By copy  of  this letter,  three  copies of the  Comments
           and  appendices, along with  one  copy  of the Sullivan  deposition
           transcript,   are  being delivered  to  John  MacDonald,  Esq.  and
           Frank  Cardiello,  Esq., deputy attorneys  general,  for  their use
           and  information.
3700 Hospital Trust Tower
Providence, Rl 0190.1
(401) 174-9100
•to Lexington Avenue
New York, NY. 10011
(nil ,308-4411
150 Royal Palm Way
Palm Bach, FL Jj4«o
(407)ljj-7-oo
i jo Bellevue Avenue
Newport, RI 01840
wot) 4*9-7800
joo Union Street
New Bedford, MA 01740

-------
Grace Singer, Chief
May 6, 1991
Page 2
         Any   inquiries   concerning   the   enclosed,   and   any
response  thereto,  may  be  directed  to  this  office  or to  the
following:

         Richard F. Ricci, Esq.
         Lowenstein, Sandier, Kohl, Fisher & Boylan
         65 Livingston Avenue
         Roseland, NJ  07068

         Mark G. Weisshaar, Esq.
         Hunton & Williams
         2000 Pennsylvania Avenue, N.W.
         Ninth Floor
         Washington, D.C.  20006

         Thank you for your consideration.

                                  Very truly yours,
                                  Nancy B.-^Rohn

NBRiswx

Enclosures

cc: John MacDonald, Esq. (w/enc.)
    Frank Cardiello, Esq. (w/enc.)
    Global Landfill PRP Group (w/enc.)

-------
     COMMENTS OF THE GLOBAL LANDFILL PRP CROUP
            CONCERNING TEE FEBRUARY 1991
NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION
           PROPOSED REMEDIAL ACTION PLAN
        GLOBAL LANDFILL, OLD BRIDGE TOWNSHIP
            MIDDLESEX COUNTY, NEW JERSEY
     Submitted by the Members oftfu Global LemdfiH PRP Group

                   do Edwards & Angell
                  Gateway One, Suite 702
                 Newark, New Jersey 07102

                    Hunion & Williams
                2000 Pennsylvania Ave., N.W.
                       Ninth Floor
                  Washington, D.C. 20006

           Lowenstein, Sandier, Kohl, Fisher & Boy Ian
                   65 Livingston Avenue
                    Roseland, NJ 07068
                      May 6,1991

-------
                        TABUS OF CONTENTS
                                                             lift

I.    INTRODUCTION	     I
II.   THE NJDEP HAS NOT COMPLIED WITH THE NCP'S DATA
     COLLECTION AND ANAL?SIS REQUIREMENTS AND, AS
     A RESULT, HAS SELECTED A PREFERRED REMEDIAL
     ALTERNATIVE THAT IS NOT COST-EFFECTIVE AND
     THA T IS BESET WITH SERIOUS TECHNICAL
     DEFICIENCIES	,,,	     5

     A,  The Proposed Plan It Not Baud On m
         Remedial Investigation audit tiif
         Product of Inadequate Data Collection
         and Site Characterization	     7

            *  StrtHgtti of Refuse, Settlement,
              and Slope Stab&tj	    10

              Nature oftiu Wafts	    17

              Ambient Air and Landfill Gas Qvatity	    18

     B.  The Omission ofNeeetsary Data Ltd to A
         Flawed PRAP Alternative	    19
111.   THE PRA P ALTERNA TTVE IS NOT JUSTIFIED
     B Y THE PURPORTED RISKS ALLEGED TO EXIST
     AT TELE SITE ....... ...................... ................. . ____    21

IV.   THE AGENCY HAS FAILED TO INTEGRATE TMK
                               VA &*<*£•*
                               OPERABLE UNIT ................    31
V.   THE AGENCY HAS FAILED TO INCLUDE ANT
     INTERIM ACTION ALTERNATIVES WHICH ACCOUNT
     FOR DATA CAPS AND WHICH ARE COMMENSURATE
     WfTHTBE LOW LEVEL OF RISK AT TOE SITE ---- .......... . .....    34

-------
                         TAB_L£ OF CDNTENJS
                              (continued)
                                                                 Page

VI.    TUE GEOCRWS, SAND, BERM, LEACHATE
      TREATMENT PLANT, AND CAP CONTAINED
      IN THE PRAP ALTERNA TJVE ARE NEITHER
      NECESSARY NOR PROPERLY DESIGNED	    35

      A.   CeogriJt	    35

      B.   Sand	    3*

      T.   Bfrm	    38

      D.   Leachate Treatment Plant	    40

      E.   Composite Cmp	    43

               Technical Itrues	    43

               Legal lames	   44

               I.    A Hazardous Waste Cap It Nat
                     Justified By The Risk Aueament	    46

               2.    RCRA Subtitle C Is Not An ARAR	    47

                     a. Nature of the Waste	    48

                     b. Nature of the Site	    54

               3.    RCRA Doe* Not Require m Composite Cap	    56

               4.    Summary	    5*


VII.   CROUP'S PROPOSED ALTERNATIVE	   60

      A*   Description	   60

      B.   Remedy Selection AMafytu	   65

               1.    Analjrit of NCP Criteria	   65

               2.    AppKcatioit of the NCP Factor*
                     to Remedy Selection AnaJjru	   70


Vlll.  ROD FLEXIBILITY	>	   72
                                  il

-------
                         TABLE OF C0J&EJOS
                             (contixtuJ)
17..   MISCELLANEOUS	


     A.  ARARi	


     B.  Excavation and Removal ofDnuns,
Page


  75


  75


  79
     CONCLUSION	  80
                                •HI-

-------
/.        INTRODUCTION
         Global  Landfill,   located   in   Old  Bridge  Township,
Middlesex  County,  New  Jersey,  was  a municipal  landfill  which
operated  from 1968  until April  1984.   At  that  time,  a  side
slope  failure  prompted  administrative   action:  in  connection
with an  Order  to Show Cause with  Temporary  Restraints obtained
by the  State  of New Jersey  Department of Environmental  Protec-
tion ("NJDEP") and entered by  the  Honorable  Richard S. Cohen on
April 17,  1964,  Global  was ordered to cease  operations.   Global
was  further  ordered to  "...immediately  retain the  services  of
an engineering  firm, approved  ^.   iNJDEP],  to prepare  a  final
closure  plan  as  required by  the  "Sanitary  Landfill  Facility
Closure  and  Contingency Fund  Act,*  N..J.S.A..  13:1E-100  fit  seq.
and   [NJDEP]'s   rules   and   regulation   promulgated,  pursuant
thereto!.],.."
         In January  1986,  a consent  order was entered  in  con-
nection  with  the  litigation commenced  by  NJDEP in  1984.   In
pertinent part, the consent order provided that Global
         ...shall  forthwith  retain  the  services  of  Richard  J.
         Sullivan  for  the  purpose  of  overseeing   the  expedi-
         tious,  and  cost effective  closure  of  the  landfill
         which is  the subject  matter  of  this litigation  as  soon
         as practicable  and  in accordance with  the appropriate
         environmental  requirements  and  law.   More  specifi-
         cally,  Mr.  Sullivan  shall  hire an  engineering  firm,
         from  a  list   agreed  to  by  the parties,  to  prepare
         closure plans  in accordance with the appropriate  rules
         and  regulations  of  the  [NJDEP]  and  further, retain  a
         contractor(s)  to implement  said plans  provided  they

-------
         are approved  beforehand by  DEP.   Mr. Sullivan's f
         as well as the fees of  the  engineering  firm  he  reta
         to prepare the closure  plans for Global shall be pa
         for  from tl>e  escrow  accounts established  by  Global
         pursuant  to   the  Sanitary  Landfill  Facility Closure
         Contingency Fund  Act,  M.J..5.&.  13:1E-100 t
Consent Order entered by the Honorable John E. Keefe  on  January

M   l9Bf,  K  1.   Clearly,  the  objective of  NJDEP since April
     (if  not  earlier
i  was  the complete,  quick,  final and cost
elective  closure  of  Global  Landfill,  in  keeping  with  the

*r
-------
shortcut procedure,  had not been  shown  by the  data  presented.
Sullivan Deposition at T112-5 to T118-11.
         On  or  about August  22,  1969,  NJDEP issued  Directive
and Notice  to Insurers  Number  1  pursuant  to the  Spill  Compen-
sation  and  Control  Act,  M.J.S.A-  58:10-23.11  fti  fififl-   This
Directive,   which  named  approximately  twenty-one  (21)  Poten-
tially  Responsible Parties  ("PRPsT),  demanded  the  payment  of
$1,500,000 to fund a Remedial  Investigation  ("RI") plus another
$225,000 in   the .cost  of  NJDEP's  administrative  oversight  of
that  activity.   During  the _course  of  discussions between  the
PRPs  and  NJDEP,  it  became apparent  that  the scope  of  the  RI
pertained  to groundwater  issues,  and  not  to  closure of  the
site,   per  s_£.   In  February  1991,  NJDEP  issued  the  Proposed
Remedial Action Plan, which  specified its  preferred  alternative
for capping  the site, ini«_r_  a_l_Lft.   In March  1991,  Directive and
Notice  to  Insurers Number Two  was issued, which  added several
PRPs  and  called for  the   payment  of a  reduced  figure  for  the
RI/FS  (the same demand  covered  in  Directive  Number One), and to
pay $500,000 for  the Remedial  Design,  and $30,353,200  for  the
costs of Operable  Unit  Number  One  (which mirrored  the preferred
alternative  identified  in  the  PRAP)  plus $4,652,980  in adminis-
trative oversight.
         As  NJDEP  acknowledges, Global Landfill  was  a municipal
landfill authorized to  accept  a variety  of wastes  for disposal;
among  the  authorized wastes was  "ID 27* which  is described  as
"dry  industrial  waste."   Encompassed within that category  is,
                              -  3  -

-------
Inter  ilia,   "asbestos  and   asbestos-containing   waste....
K.J.A.C.   7:26-2.13(g)(vi).   There is  no dispute  that much  or
most of the waste allegedly generated  and/or  transported  by  the
PKPs named in both the  First and  Second Directives  was properly
disposed  of at  Global Landfill;  insulation material containing
asbestos  is  an  excellent illustration.   There  is no  dispute
that   NJDEP   rules   and   regulations   governing   closure   of
municipal, or solid waste, landfills contemplate  and anticipate
the  presence  of  such properly disposed of  materials at  such
sites.    ,    .     .  _    .._	 -   —	  -  - -
          In  the  Proposed   Remedial   Action  Plan  issued   on
February  19,  1991,  NJDEP maintains that the discovery of  some
drums in  a discrete portion  of the landfill, some  of  which  are
alleged  to have  contained  hazardous  materials,   is enough  t
warrant  the  treatment  of Global  Landfill  as  something  othe
than a municipal  landfill.  However, that  conclusion is  largely
the  result  of assumption, extrapolation,  and inadequate  foun-
dation.   When  all  of  the  legal  and  technical  deficiencies
reflected  in NJDEP's  conclusions  are  considered,  it is  readily
apparent  that the preferred alternative  promulgated by NJDEP is
inappropriate.   In  fact,  it is highly  probable  that if  NJDEP
had not interfered vi«-h fh*» *•£"-?* ?*:riti!ity 5tudy, the  proper
municipal  landfill  closure  design, and the  landfill  construc-
tion  process,   no additional   closure  or  remediation  efforts
would have been required at  Global Landfill.

-------
         In the  discussion  which follows,  the  Global Landfill
PRP Group  ("PRPs"  or  "Group"),  the membership of  which  is set'
forth in Appendix E, will address the inadequacies in the NJDEP
preferred  alternative  (and  the materials  upon  which  it  re-
lies).  Importantly, the Group also presents an alternative for
closure of  Global  Landfill which  complies with  technical and
legal requirements  and addresses the  alleged  problems posed by
this  site  —   in  fact,   the   Group's  alternative  achieves
everything expected in the  NJDEP alternative,  at  a significant
cost savings.	    	      .      	
         The  Global Landfill  PRP  Group  urges NJDEP to  give
meaningful  consideration  to  the  comments  and  suggestions set
forth herein.  At  the  very least,   the  Group  stresses that any
Record of  Decision entered in  connection  with  Global Landfill
should be  sufficiently  flexible to meet  site-specific  circum-
stances and needs as they arise.

//.       TEE NJDEP HAS NOT COMPLIED WITH THE NCP'S DATA COL-
         LECTION AND ANALYSIS REQUIREMENTS AND, AS A RESULT, HAS
         SELECTED A PREFERRED REMEDIAL ALTERNATIVE THAT IS NOT
         COST-EFFECTIVE AND THAT IS BESET WITH SERIOUS TECHNICAL
         DEFICIENCIES
         There can be  no  doubt  that  the  actipn  intended  at
Global Landfill is  "remedial" -- final, complete,  and thorough,
not temporary or  "stop-gap" — indeed,  that intent is reflected
in  the  very label  imposed by NJDEP.   In  its  Proposed Remedial
Action  Plan  for   the  Global Landfill  (emphasis added)   (herei-
nafter "Proposed  Plan" or  "PRAP"),  the NJDEP  plans two  actions
                             - 5 -

-------
to  remedy  this  landfill.   The  first,  known  as Operable  Unit
Number 1 (OU4F1), is a phased  response action  that  addresses *9
closure of the landfill.   The Proposed Plan's  preferred alterna-
tive for OU#1  (PRAP  alternative) calls  for the  construction of
a modified  hazardous  waste  cap  over the  entire landfill,  and
the installation of a  gas collection and active treatment  sys-
tem,  and   collection  and  treatment   for   surface   leachate.
NJDEP's    estimated    cost   of    the    PRAP    alternative   is
$30,353,200.  A  second remedial  action,  known as Operable  Unit
Vjrber 2  (OU*2), may  be  needed to  address  groundwater.   OU#2
will include an RI/FS  to  focus on OU*2 issues.
         The selection process  for the  OU#1  remedy  was  flawed
from the outset because NJDEP failed to  complete a  remedial in-
vestigation  (RI),  both oi  the  overall   site  conditions  and of
the conditions  specifically related to  OU'fll, prior  to issuij
its  Proposed  Plan.  This   is  inconsistent  with  the  NationaT
Contingency  Plan  (NCP),  which establishes  a  systematic  method
of data collection  and analysis  as  the basis for  selecting reme-
dial actions.  The absence of the data  that  an RI is designed
to provide  has  led to a misunderstanding  by  NJOEP of  the  site
risks  to  human  health  and  the environment posed  by  Global
Landfill,  a  faulty Feasibility  Study  (FS),  and  a  failure  by
NJDEP to  realize and plan  for  the  interdependence of the  two
Operable Units  in  achieving  the overall  effectiveness of  the
final remedy for this  landfill,  as  required  by the  NCP.   Most
importantly, the lack of  an RI has led to  a failure by NJDEP to
                             •- 6 -

-------
develop  the  data  on the  landfill's soil  .strength, settlement
rate, waste characteristics,  and  hydrogeology,  all of which  are
essential  to  an  evaluation of  the alternatives  considered  in
the  Proposed  Plan for  capping  the  landfill  and  installing  gas
and leachate treatment systems for it.
         With a  thorough RI and  an  accurate FS,  cost-effective
and  integrated  remedies could have  been selected  on the basis
of  adequate  data.   Without  these  essential elements,  NJDEP's
premature  and  incorrect selection  of  the  PRAP alternative  for
OU#1 makes  it more  likely that  any decision  relating  to OU#2
will not be well  integrated with  OU#1.   In summary,  the NJDEP's
failure  to  collect necessary technical  data in  an RI, NJDEP's
defective FS,  and  its  failure to  consider the overall site rem-
edy, has resulted  in the premature  selection of a  PRAP alterna-
tive that  is  not  cost-effective and  is inconsistent  with  the
NCF.
         A.   Tht Proposed Plan It Not Based On a Remedial Investigation and It
              the Product of Inadequate Data Collection and Site ChancUrization
         The  NJDEP did  not follow  the  methodology  established
by the NCP for characterizing the nature and extent of the con-
tamination present  at  Global Landfill.  Pursuant  to the NCP,  a
lead agency must develop a sampling  and analysis  plan that pro-
vides data of sufficient quality to support the analysis and  de-
sign of  potential  response actions for a Superfund site.   40
C.F.R.  §§  300.430(b)(8),  (d)(2)  (1990).   The NCP specifies that
                              - 7 -

-------
     sampling  and  analysis  plan shall consist of  a field s

ling plan,  a quality assurance  project  plan  (QAPP),  and often

one or  more  treatability studies.  40 C.F.R.  §§  300.430(b) (8)

(li),   (d)(l)  (1990).   As part  of the field  investigation, the

RI  must obtain  data on the  physical  characteristics   of the

-:'te,   including  soils/  geology,  and  hydrogeology;  characteris-

nrs of  the air,  surface water, and  groundwater;  characteris-

«••«-« Cf  the  waste;, the extent  to which  the source  c*n  be ade-

~.-.8f«»iy  characterized;   and  actual  and   potential  exposure

.'_tes.  40 C.F.R.  §§ 300.430(d)(i)-(vi)  (1990).

         For   municipal  waste   landfills,   EPA,   which  is

responsible  for  implementing  the NCP,  has  identified   certain

types  of data that  at the minimum must be considered when evalu-

ating   specific  elements of  the potential  remedial  alterna-

i. jvc-5.    Data  on  settlement  rate,  availability and  adequacy ^

rover  materials, and  soil and waste  characteristics are neces-

sary to  evaluate capping alternatives for  these  landfills.I7
*'     "Conducting  Remedial  Investigations/Feasibility  Studies
frr CERCLA  Municipal  Landfill Sites," OSWER  Dir.  No. 9355.3-11
at  pp.   3-11,   4-8  (Feb.  1991)   ("Municipal  Guidance").   The
development  of  capping  alternatives  relies  on  an  analysis  of
i*nofill  contents.  For  landfill contents,  the  objectives  of
	-.  collection   are   to  determine   "total   and  differential
—». • i f,->-, =>"- n    ota.-..   *><; «c-»• 4 ^»i»s-4r**>i    <*•?>£    "rt*i'<5ntration    of
.junlaminotion in surficial soils,s  *th@  latsgsifcy of any buried
    3,"  and "the  degree of  contaminiation  of  any unsaturated
--n."   Id.  at  3-16  to 3-17.   To  "document  settlement  over
--,-e. a series of  settlement  markers  should  be established  on a
-rid  pattern of   approximately  100  feet  (more  in  areas  with
kncwn settlement   problem)."  Ifl.  at  3-17.   The  importance  of
JcLermining  settlement, particularly differential  settlement,
• c  difficult to   overstate.    It  may be  necessary  to  monitor
settlement  throughout  the Rl/FS  and the  design stage.  Id.  at
3-18.

                              -  8  -

                                             POOR QUALITY

                                                 ORIGINAL

-------
Data  on hydrogeology  and the  chemical  characteristics of  the
leachate,  often  coupled with  a treatability study,  are  funda-
mental   to  an  evaluation   of  leachate   treatment   options.
Municipal  Guidance  at  4-22,  4-23.^/   Finally/ data  on settle-
ment  rate,  nature  of  the  wastes,  preferential flow  paths,  and
chemical characteristics of the gas  emanating from the  landfill
are  required  to  evaluate gas collection  and treatment  alterna-
tives. Id. at 4-28, 4-30.ix
         The  Proposed  Plan for Global Landfill is  not  based on
er.  adequate  field  investigation and NJDEP  has  therefore  failed
to  consider  in the Proposed Plan the specific  data that  is  re-
quired by  the NCP  and  that is  necessary  for evaluation  of reme-
dial  actions  for   municipal   landfills.   The  Administrative
27    For  leachate,  the  objectives  of  data  collection are  to
provide    information    that    determines    its    "chemical
characteristics,"  and  its  "impact   on   groundwater."   Id.  at
3-10.   Leachate  wells  or  collection drains  should be used  to
define  "soil"  characteristics  including  permeability,   grain
size   distribution,    and    moisture   content"   . and   "waste
characteristics."  Id. at 3-13.
2X    Landfill gas  characterization  has  as -its  objectives  "an
assessment  of   human   health  risks  due  to  air  toxics  and
explosive  hazards,"  and "the feasibility of  gas  collection and
treatment."   Id.  at  3-26  .to  3-27.   Data  should  therefore
include  "contour  maps,"  "geologic,  hydrogeologic,   and  soil
characteristics...to    determine    gas    migration   patterns,"
landfill gas  "composition,  moisture  content,  quality,  and heat
and  methane  content,"  and  "types of  microorganisms  present."
Id. at 3-29.
                              - 9  -

-------
Record does not include  a  field  sampling plan and a quality
surance  project  plan,  the two  essential elements  in  any  NCP
field investigation.  40 C.F.R.  §  300.430(b) (8) .   The field ef-
fort for Global Landfill did  not define data quality objectives
and  therefore  failed  to obtain essential  categories  of  data.
In  particular,  the Proposed  Plan  is  not  supported by  an  ade-
quate  field  investigation  of the  nature and  strength of  the
waste,  the  soil characteristics,  or  the  landfill's settlement
rate,  all  of which  are necessary  to  evaluate capping  and  gas
treatment alternatives.  Furthermore,  the Proposed  Plan is not
based upon treatability  studies  which  are necessary to evaluate
leachate treatment  alternatives, or an investigation of prefer-
ential  flow  paths  and  characteristics  of  the  gases  from  the
landfill which are  required for  the evaluation of gas treatment
alternatives.    This   is   inconsistent   with   40  C.F.R.
300 .430(d) (1) and  the basic  principles  governing evaluation of
municipal landfills.  As a result, NJDEP could not  and did not
develop  and  effectively  evaluate  remedial  alternatives  for
Global Landfill in its Proposed Plan.
         NJDEP 's failure to conduct an adequate RI for the land-
fill has  caused it to  erroneously assume that the landfill is
unstable.  thr, Ts^n^st ^?!r*"-^~  r-r-5 discussed below.
         Strength ofRtfust, SettUmtnl, and Slept Stability
         The Proposed  Plan is based  on three investigations of
soil conditions at the site:

                             - 10 -

-------
              An  investigation  including  fifteen  test  borings
              and  five  cone  penetration  tests  in   1964   by
              Woodward  Clyde  Consultants  following   a   major
              slope failure in April 1984.*x

              An investigation by French and Parello Associates
              including  four  test  borings and  in  situ  field
              vane tests in January 1989.^'

              An investigation by French and Parello consisting
              of eight  borings and  fifteen in-situ  field  vane
              shear tests in February 1990.£'
         Although these  reports  include the results of stabil-
ity  analyses  for  the landfill  against sliding,  all   base  the
analyses on waste strength parameters that are  neither  site-spe-
cific nor appropriate.   Inexplicably,  the  fieldwork  ignored the
strength of  the refuse  as a  data  need.   As  a  result  of  this
V    Geotechnical Investigation, Global Sanitary  Landfill,  Old
Bridge Township, New Jersey, Woodward Clyde Consultants.
^    Report of  Geotechnical  Exploration for the  Closure  Plan,
Global  Sanitary  Landfill,  Old Bridge  Township,  New  Jersey,
French and Parello Associates, April 1989.
£'    Report of Supplementary  Geotechnical  Evaluation for  the
Feasibility  Study,   Global   Sanitary   Landfill,   Old   Bridge
Township,  New  Jersey, French  and  Parello Associates,  February
14, 1991.
                             - 11 -

-------
omission,  the Proposed  Plan  erroneously  assumes  that  Global
Landfill is unstable.
         The  1984  Woodward Clyde investigation  used  rotational
slide  analysis to  back  analyze the  strength  of  the  refuse.
Notably, the  actual  failed  slope profile  followed a block slide
failure; it  did not  represent  the  rotational  slide  mechanism.
Several calculations of slope stability were performed with dif-
ferent  refuse strengths,  but  with  inappropriate  slide  mechan-
;-rs,  until  the  calculated  factor  of  safety  reached  unity.
This back  analysis  led to Woodward Clyde's  assumption that, the
correct refuse strength was a cohesion  of 780  psf,  using an un-
drsined strength analysis.  A back  analysis had been performed,
but  led to  an  over-conservative result  owing to  the improper
slide mechanism adopted.
         In 1989 French and Parello  Associates used the same inv
proper  rotational  analysis  approach,  but  with refuse strengths
that were assumed from limited desk studies of available litera-
ture.   The analysis  assumed undrained  strength parameters  of
750 psf (similar to Woodward Clyde).  No back analyses were per-
formed  on  the landfill slopes  prior  to  failure  to justify the
refuse  strengths.   The studies  led French and Parello  to con-
clude that  the  a»*3£i3.5 was r*.^«-.;i:««..>?«  *^MAB  si^d back analy-
sis  been used with a  more appropriate  block slide, it  could
have been  realized that  the  refuse strengths were  higher,  and
consequently  the  actual  calculated factors of  safety  for  the
landfill were better than predicted.

                             - 12 -

-------
         In 1991,  French  and  Parello  reanalyzed  the  landfill
stability using  a  block analysis, and  found that the  existing
fa-.tor of  safety was 1.34 for the North and South slopes, but
that the East  slope presented a  factor  of  safety of 1.1.  The
refuse parameters  used were drained  values of  22 degrees for
friction and 200 psf cohesion, as a  result  of a published  lit-
erature review.  Although  an  appropriate analytical method was
now being used, the tefuse strengths were still not based  on ap-
propriate site  specific back analysis,  in   the  absence of any
field testing  to determine refuse strengths.  While the  report
did examine soils strengths in detail,  less  attention was  appar-
ently given to  refuse strengths  which are nonetheless  of  equal
importance.  The 1991 French and Parello analysis, therefore,
used the  appropriate slide mechanism,  but  the  refuse  strength
parameters were again inappropriate.
         In the  case of  the  analysis  of the  North East  slope
existing  stability  evaluation,   French  and  Parello   did not
lecognize that measured vane soil strengths  did  not support the
fact that  the slope was  stable.  (If  measured  vane  strengths
are  used,  the  calculated  factor of  safety for  the  existing
slopes is  less  than or near unity.)   This would have  indicated
to them that  the vane strengths  underestimated  soil strengths.
They used  vane strength data to  evaluate the stability of the
East slope,  leading  to their  conclusion that it  is  unstable,
when site  observations indicate  it   is also  stable.   The low
soil  strengths  based on  vane  tests  were   later  used  in the

                             - 13 -

-------
analysis  of the  East  slope with  a  cap,  which  contributed
their misconception that a bertn is necessary.
         By  implementing  the correct methodology,  the  analysis
by  the  PRP group clearly demonstrates  by back  analysis  with a
uioc*  slide approach,   that  the refuse  strengths  are  signifi-
:~r.tly  higher  than those  stated by  French  and  Parello.   Back
0,,0-Ljsis has shown that parameters of a friction angle of 34 de-
    , and  a  cohesion of 334  psf  are appropriate for the refuse,
oecause with a  block  analysis,  the calculated  factor  of safety
TCI  the landfill profile  before failure  was  near  unity,—that •
is, it  was at  an incipient failure condition.   Analysis of the
Proposed Plan's  preferred alternative with these parameters and
n.ethc'J  of  anc;yris show that there is no  D_e.ejl  for,  a, stabi Hza-
'..::r. -:rr..  See Appendix A.
         There  has  been only  one  incident  of  slope  stabilitlj
'•:'!i:re  at Global which  was . then corrected  by regrading  the
l_..::ill.   Given that  stability  failure  event,  an experienced
engineer would  have  known that  ground movement  monitoring  in-
formation  would be essential.   It is  difficult to understand
why NJDEP  did not subsequently install a  series of  vertical and
  r:rental  movement monitors to follow  the landfill  behavior.
-jch an installation would  have  enabled NJDEP  to better under-
r:=na the  stability of the  landfill,  and this would have  pro-
vided critical data to the Feasibility Study in proposing real-
:rt£c cap designs.
                                                 POOR QU-v.
                                                   ORIGINAL

-------
         The Proposed Plan is based on the premise that substan-
tial movement  of  the southeast sideslope  is  now occurring  but,
contrary  to  the NCP  and  ZPA guidance,  the  KJDEP has  not  per-
formed  any monitoring for  slope  stability or  landfill settle-
ment even  though NJDEP, through the  site Administrator for  clo-
sure, has  been in  control of the site for over  five years.   An
inspection  of  Global's  existent   cap by  the  PRPs   in January
1991, accompanied  by representatives of  the  NJDEP consultants,
showed  no  evidence  of  ongoing instability or  movement  to  the
southeast.  During the visit,  there  were no  signs of settlement
or creep monitoring  points  from which a  firm conclusion  on  in-
stability  could be  drawn  through regular survey measurements.
If NJDEP had  conducted  an adequate RI that  (1)  included  survey
points to  measure  the landfill's  vertical and lateral movements
soon after  the original  slide  or (2) included  routine settle-
ment monitoring attendant to  a  landfill closure/ the Proposed
Plan could be  based  on  actual  data  and not general observations
or overly conservative assumptions.^/
         Based  on  information  that NJDEP has.made available,  it
appears that  the  only survey  source of data to quantitatively
1'    The DEP's approach  is  based largely on  the  1984  incident
of  slope failure.   This  type  of  failure  is  not expected  to
recur in the future.  First,  the  1984  slope  failure occurred on
the east  slope  where a large volume  of refuse had  been  placed
rapidly  during  the  previous four  to  five  months.  Second,  a
heavy   rainfall  and   extremely   high  tide  were   recorded
immediately prior  to the slope failure.
                             - 15 -

-------
estimate movement is contours on  successive  aerial  surveys.   It
is widely recognized that  such  surveys are  not  accurate  enougV
for proper settlement monitoring, as  the  margin  of  error  gener-
ally associated with such  aerial  surveys is one  contour  inter*
val, which equates  to  two feet for  the site drawings.   From  a
comparison of  two  available  topographical  surveys dated  June
1986 and  March  1989,  the  landfill  exhibited generally four  to
six feet  of  settlement.   The 1986  topography  is on the  Feasi-
bility Study  drawing  "Feasibility  Study  for On-Site  Controls,
Site Plan" by Killam Associates,  and  the  1989   topography was
provided to the PRPs by Killam Associates in January 1991.  The
contour changes were consistent with  normal  landfill consolida-
tion,  were not isolated,  but  were  general  around  the whole land-
fill.   This is not  a  sign  of landfill  slope instability  or  in-
cipient failure,  but of the normal  aging  of  the  landfill.
                                                               ^
also supports slope stability analyses performed by the PRPs.
         Settlement  measurements,  in  order  to be  meaningful,
should generally be  made  to  levels of accuracy of one  tenth  of
a foot (or less),  as  they  are  when settlement monuments are  in-
stalled.   At  a minimum, therefore,  periodic monitoring with sur-
vey instruments  is needed to  determine  the  rate  of  settlement
and degree of  slope  stability.  Municipal Guidance at  p.  3-17.
                             - 16 -

-------
The Proposed Plan has been issued, therefore, without the essen-
tial site-specific data needed  for  a decision concerning a tem-
porary or  final  response  action and  for  development  and analy-
sis  of  capping  and  gas  collection  alternatives.  Municipal
Guidance at pp. 4-7,  4-8,  4-11, 4-12, 4-30.
         In the absence of  the  required site-specific data,  the
NJDEP adopted very conservative values  in the assessment of  al-
ternative cap.  designs.  The final analysis  assumed  an angle of
friction of 22 degrees and a cohesion of 200 psf.   A more appro-
priate back analysis^of the  1984  slope  failure would have indi-
cated that the strength of  the  waste is actually  at  an angle of
friction of 34 degrees  and has a cohesion  of 334 psf.^'  Thus,
NJDEP has seriously underestimated  the  current stability of  the
landfill, overestimated  the urgency  to  improve  stability,  and
overdesigned various  elements of the PRAP alternative.

         Naturt oftht Waste
         Only one investigation to determine the general charac-
teristics of the waste  was conducted on  a  portion of the smal-
ler 6.5 acre section of the  landfill.  The much larger and dis-
tinct 51  acre area  was  not  investigated,  even  though  it  ob-
viously contains most of the waste and will cost the most to  re-
mediate.   This  omission  is  inconsistent  with  40  C.F.R.  §
          Appendix A.
                             - 17 -

-------
300.430(d)(2)(iii)/  which  requires  general  characteristics^^
the  waste  to be  investigated.   Moreover,  although  boreholes
through  the refuse were drilled  by Woodward Clyde Consultants,
ihe  information  from the boreholes was not used by NJDEP to as-
sess  the general characteristics of  the  waste.   Again, this is
inconsistent  with  40  C.F.P.  $  300.«30(b) (1),   requiring  the
evaluation  of existing data at  the  site.
         One  important  indicator of  the  nature  of the waste in
&  landfill  is the leachate.   Through a Bite monitoring program,
v.TDEP has  been  collecting annual  and some  quarterly leachate
data  from  the landfill  since October 1986.  NJDEP, however, has
not   performed  any  treatability  studies  on  the  leachate  or
groundwater,  nor has NJDEP reviewed  the  leachate data and com-
pared leachate   chemistry with   the  Toxicity   Characteristics
Leaching Procedure   (TCLP)   to  determine the   nature  of  t
waste.   The failure to perform these analyses  on the nature of
the  waste  has  prevented  NJDEP from  determining the viability
and  effectiveness of treatment and from  adequately characteri-
sing  the nature  of this  landfill.
         Ambient ASr otuf LandJUl Gas Quality
         NJDEP  also failed  to  perform a  baseline  study of the
types  and amounts  of  gssss  ^sssti^  tx&& Global  Landfill and
Lhe  effect these gases have on ambient air.  This is difficult
to understand because  the  Proposed Plan claims that OUI1 is nec-
essary  to mitigate odor complaints  from  surrounding residents.

                             -  18 -

-------
Furthermore,  the  baseline  risk assessment  included in  the FS
identified ambient  air  or windblown particles as complete expo-
sure pathways.
         The data  available on air quality  and  landfill  gas is
very limited.  It  does  not  include an analysis of the constitu-
ents of representative  gas  samples,  an analysis of preferential
gas  flow  paths,  or  off-site  ambient air monitoring  data.   The
Feasibility  Study  indicates only  that air  monitoring  was  per-
formed in 1986 in  a fissure on the existing cap, in 1988 during
the drum investigation, and in 1988 during  a subsurface methane
gas survey,  which  found continuous methane  concentrations to be
zero at a distance  of  500 feet from the landfill toe.  The data
relied on  is largely  data  from other  landfills.   The Proposed
Flan has  thus not.  -.oii^iiecl wit:': 40  C.F.R.  § 300.430(d) (2) (ii).
requiring  an  investigation  of  air,  nor  with  40  C.F.R.  §
300.430(d)(2)(iii)   requiring   investigation  of  landfill  gas
which  is  a  waste  product.   £&£ a_l_s_c Municipal Guidance  at p.
4-30.

         B.   The Omission ofNecestorj Data Led to A Flawed PHAP Alternative
         NJDEP's failure to obtain the necessary data discussed
above  has  adversely  affected the  selection of  several  compo-
nents  of  the PRAP  alternative.  These adverse consequences are
most evident  in  the type of  cap selected,  the requirement that
a toe  berm  be used for the cap, and the  Proposed Plan's appar-
ent preference for  on-site  leachate treatment.


                             - 19 -

-------
         The  failure  to  provide accurate  strength
for the  calculation of  cap  stability led to an  underest:
of the  factors of safety  against sliding failure of the  exist-
'•••0 landfill.*''   The failure  to determine the  settlement  rate
of the  waste  has resulted in  the  inclusion of unnecessary  and
ineffective geogrids.   Moreover, the  inadequate evaluation  of
-.::? nature of the waste led  to the unfounded assumption  that  a
-opposite cap is necessary for this  site.   Together, these  data
	.iencies and the consequent reliance on overconservative as-
enr--<«-ir>ns directly led to  an  overdesign of  the  cap.
         In spite of the lack  of essential  geotechnical  studies
on the  strength  of  the  waste,  the  PRAP alternative recommends
the construction of  a perimeter berm to enhance landfill  stabil-
ity.   The  analyses  in  the  Feasibility  Study  indicate  minimum
lectors  of  safety of  1.13 increasing  to 1.37  with a toe berntf
An  analysis  by  the  PRP Group with  more   realistic   refuse
 '.:en;ths indicates  a minimum factor of safety of  1.57 assuming
M.< sell  strength increases  from aging  and without a toe berm.
The factor of safety of  the  East slope may be as high  as  3.13
without  a  berm,  if significant aging  has  occurred. ^/   The
landfill, under  current  conditions, does  not  pose a stability
      In fact,  if  the  landfill is  a*  unstable as indicated  in
    . ioposed Plan, a temporary cap would be warranted until  the
    lenient rate has stabilized.  Municipal Guidance at pp. 4-8,
      4-12.
          Appendix A.
                                              POOR GUAi-V1
                                                 ORIGINAL

-------
risk.  Because of the  lack  of proper data, the NJDEP  overesti-
mated the  risk  of stability  failure,  and consequently the  al-
ternatives with a bernt are overdesigned.
         The lack of  adequate data  on  the groundwater quality
and  volumes,  owing  to  the  limited investigations  that  have
taken place, represent a failure to  adequately address the  date
needs for  leachate  treatment.   Equally  important, even if  lea-
chate treatment is to be performed in OUK1, the failure to  ana-
lyze representative leachate  has  prevented an adequate consid-
eration  of treatment -options.   Significantly,  the  investiga-
tions have not included any treatability  studies.   Such studies
can  only be representative  if they include water typical  of
that to  be treated.   Without the  benefit of such  studies,  the
Proposed Plan has indicated  a preference foi on-site  treatment
-- which may not  be practicable,  administratively  feasible,  or
cost-effective for leachate  at this site.

///.       THE PRAP ALTERNATIVE IS NOT JUSTIFIED BY THE
         PURPORTED RISKS ALLEGED TO EXIST AT THE SITE
         It is fundamental that a  remedial action is  driven,  at
least in  large  measure,  by  the risks determined  to exist  at  a
site.  In  that regard, it is  imperative that the  risks be quan-
tified.   The risk assessment  incorporated into the  FS  is  admit-
tedly a  qualitative assessment, and not quantitative.   Conse-
quently, it is  fatally flawed.
         The National  Contingency  Plan   provides  in  pertinent
part:

                             - 21  -

-------
         (d)  Remedial  Investigation.   (1)  The purpose of  t!
         remedial investigation  (RI)  is to  collect  data  nec<
         sary to adequately characterize the site for  the pul
         pose of  developing  and  evaluating effective  remedial
         alternatives.    To characterize  the  site/  the  lead
         agency shall,  as  appropriate,  conduct  field investiga-
         tions,   including  treatability studies,  and conduct  a
         baseline risk assessment.  The RI  provides  information
         to assess  the  risks  to  human health  and the  environ-
         ment and  to support the development, evaluation,  and
         selection of appropriate response alternatives. .  .or

              (2)  The  lead  agency  shall characterize the  na-
         ture of  and threat  posed  by  the  hazardous substances
         and hazardous  materials and  gather data necessary  to
         assess the  extent to which the release  poses  a  threat
         to human  health or  the  environment or  to  support  the
         analysis and design  of  potential  response  actions  by
         conducting, as  appropriate, field .investigations.  ...  . ...

              (4)   Using the data  developed   under  paragraphs
         (d)(l)  and  (2)  of this section, the  lead  agency shall
         conduct  a   site-specific  baseline  risk  assessment  to
         characterize  the current  and  potential  threats  to
         human health and  the environment that may  be  posed  by
         cpntair.ir.a.'jt^  migrating  to  ground  water  or  surface
         water,  releasing to  air, leaching through soil, remain-
         ing  in  the soil,  and  bioaccumulating in  the  fooi
         chain.   The results  of  the  baseline  risk  assessment
         will help establish  acceptable exposure  levels for  us^
         in developing  remedial  alternatives in the FS.  .   . .

300  C.F.R.  § 430(d)(l),  (2)  and  (4)   (emphasis  added).   There

can be no doubt  that data is  required for the conduct of a quan-

titative assessment; absent that d_a_Lfl,  only a qualitative,  judg-

mental,  and  subjective   assessment  is   possible.  A  qualitative

assessment  cannot,  and   does  not,  satisfy  the requirements  of

the NCP.

         Risk assessments are required  as part  of the Superfund

process  to do  that which the   name  implies:  assess the  risk

posed  by  a given site.    In this instance,  the risk assessment

incorporated in  the Feasibility  Study  fails to  accomplish  the
                             - 22 -

-------
obvious goal;  this  deficiency  is  admitted by the  company  per-
forming the  work.   In  summarizing  the  potential  health  risks
rosed  by  Global  Landfill,   Ram Trac  Corporation,  the  subcon-
tractor to  Killam which  prepared the  risk assessment  (see  FS
Appendix E) states,  "[ijnasmuch  as routes  and  pathways of  expo-
sure to substances of potential  concern were not quantified,  it
is impossible  to  determine  to what degree public health in the
vicinity of the Global Landfill  may  be threatened.* Feasibility
Study,  App.  E, at p.  188.
         This  deficiency  is  recognized  repeatedly _throughout
the FS. For example,  the  FS includes  a detailed executive  sum-
mary which sets forth the conclusions  of  the component parts  of
the FS.  Kith  regard to  the requisite risk assessment,  the ex-
ecutive summary states:
         Due  to  the  limited  data  base  for  the  site,  only  a
         qualitative  health  assessment could  be performed  for
         Global Landfill.   Ten complete potential exposure path-
         ways  were   identified  but  health  risks  could not  be
         quantified based  on available data. .  .  .
Id., at ES-5.   Recognizing the  deficiencies  in  a  qualitative as-
sessment,  the executive  summary concludes:
         Inasmuch as routes  and pathways  of  exposure  to  sub-
         stances  of  potential  concern were not quantified  as
         part  of  this study,  it  is  impossible .to  determine  to
         what  degree public  health  in  the  vicinity  of  the
         Global Landfill may be threatened. .  . .
         Based on presently  available  data, it is impossible  to
         determine whether  the facility poses non-cancer  risks
         because  such risks  are  typically associated  with  a
         threshold of  toxic  action  below which  they will  not
         occur.   Having  not  quanitified  [sic]  exposure,  this
         risk  assessment  cannot  determine whether  or  not levels
                             - 23 -

-------
         of  exposure  via  exposure  pathways  deemed  to be  co
         plete are above or below applicable thresholds....
Id., at  ES-8.   By its own  terms,  therefore,  the risk assessment
incorporated  into the  FS,  which gives  rise  to the  Proposed
Plan's  preferred   alternative,  does not  assess "... to  what
degree  public health  in  the  vicinity  of the Global Landfill may
be threatened. .  . ."
         The risk assessment then admits that:
         Health  risk  can be quantified only  when exposures can
         be quantified through  identification of  a complete ex-
         posure pathway.  .  .  .  [T]en  complete exposure pathways
         were identified  but quantification  of the level  of ex-
         posure was not possible.   -    —- —   —-~ —  	—
1£. at  1-22.  Once again,  the  absence of quantitative data ren-
ders  the interpretation  of "complete"  exposure  pathways  sus-
pect.    F-£T T:3c  ackrrw'Jedcei1 tMr fata]  deficiency.   In its ex-
ecutive  summary  included  in   the  risk  assessment,  Ram  Tra,
states:
         .   .  .Although  ten pathways were deemed  complete based
         upon  qualitative  evidence,   no  conclusions  could  be
         drawn  about  the  significance of  these  routes.   Such
         conclusions require quantitative analysis of data....
Id. Appendix E, at p. 1 (emphasis added).  Surely, if no conclu-
sion can be  drawn about  the significance of  the  route  of expo-
sure,  no conclusion  can  be drawn about the  actual or potential
risk to public  health.   Without any real ability to reach  such
a  conclusion,  the risk  assessment  is  seriously  deficient,  and
rr.ost certainly cannot form the  basis  upon which to propose, let
alone select, a site-specific remedy.

-------
         Ram Trac states that because  a  quantitative  assessment

cannot be  performed,  a  qualitative  one must  suffice.   Ifl. at

pp.  71-72.   However,  the basis  upon which Ram  Trac  forms its

qualitative judgment of  a complete exposure pathway is the ob-

servation  of  "odors."  Id.  at  pp.  74-82.   Odors  are  clearly  a

matter of  subjective  judgment;  nevertheless,  the constituent

parts of a discerned odor can  and  should be a natter of  objec-

tive  quantification.   The  risk  assessment  herein does nothing

to consider  the  objectively  determinable constituents.   Impor-

tantly,  Ram Trac  specified the  problem as follows:

              In  the  analysis  of  the  completeness of  exposure
         pathways,  it  is important to emphasize that  complete-
         ness was  judged based  upon  the reliability  of  avail-
         able evidence documenting each  pathway, but  not  neces-
         sarily  quantifying  it.   Thus,   some  of  the  complete
         pathways  Hi:.:' ebi. c  ••..-':••>:,:.  te  r&liauly  quantifies.
         based upon presently available  data.  Whether  or  not  a
         pathway  can  be reliably  quantified  based upon  avail-
         able data,  it  is  important to  note  that no  quantita-
         tive or qualitative  judgment is being  made  about the
         fnsonitude  of exposure  or of  potential  health  risk asso-
         ciated with the pathway.  The bottom  line is  that, al-
         though  the  exposure pathways  listed above  have  been
         deemed  complete,  the  risk  assessment  is essentially
         non-quantitative,  and does  not permit  differentiating
         complete  pathways  of  exposure  which  are significant
         from those which are insignificant.

Id. at p. 187 (emphasis added).
                   i
         Apart from  the obvious  doubts  about the validity of

deeming .an exposure pathway  "complete," the  rationale for so

concluding, even on  a  qualitative basis,  is seriously flawed.

For  example,  seven  of  the  ten purportedly  complete  exposure

pathways  are  derived  from  alleged  transport of contaminants by
                                                POOR QUALITY
                                                   ORIGINAL

-------
oil.  £££  Feasibility  Study at 1-20 for list of  sixteen  poter
rial exposure pathways, and  1-21  for  list  of  ten  exposure path-
wf»vs deemed "complete."  Notably, the air monitoring data  is re-
markable in  its  lack of significance: air  monitoring  conducted
during  the March 1988  drum investigation  revealed  readings  in
1ve residential  area which  were  basically  non-detectable; read-
mos taken at the excavation site specifically,  and at the land-
f-in penerally, were hardly different.  Ifl. at 1-16.  To the ex-
»r,nf any readings were possible, there was no  consideration of
.r? actual  source!__	      	       	    ..      . .    	
         Similarly,   a  December  1986  methane  survey  focused  on
the area between the northwest  side  slope of  the  landfill and
the residential area.  According to the results, ". . .at a dis-
tance of 500 feet from  the  toe of  the slope,  both peak and con-
i i-vj^us  methane  concentrations  were  zero.   Methane  migratio™
?w?y .from  the site  is  therefore  taking place  in a northwesterly
direction.   However  at  the  time  of  the survey the migration was
i imilej	&H3	did  not	extend  tQ  the	residential   area  located
north and  northwest  of  the  landfill.  ,  .  ." Id. at 1-17 (empha-
sis added).  This  conclusion  therefore  casts  significant doubt
     the basis for  the determination of seven  of  the ten "com-
     " pathways:
         Seven  of   [the]   pathways   are  associated  with  the
         off-site   airborne  transport  of   contaminants  from
         Global Landfill.   Although air  monitoring  data are un-
         available  for  quantifying  the exposure,  these  pathways
         were determined to  be complete  on a  qualitative  basis,
         due to  the high  vapor  pressure  of many  of  the  sub-
         stances known to exist at Global and the documented de-
         tection of off-site  odors.   Although  the  identity  of

                             - 26 -

-------
         the gases  has not been  established,  the detection  of
         landfill-associated odors is sufficient  to  confirm  the
         presence of an effective  transport medium.
Id. at 1-21.  If  th«: detection of ortors  is the  prime justifica-
tion for concluding that air transport of contaminants is an  ef-
fective, or  complete,  exposure  pathway,  yet the  only quantita-
tive analyses of  the  transport of  landfill gases reveals that
it  is  no_t reaching the  residential  areas, it  is clear  that  a
qualitative conclusion that air transport  is a  complete pathway
  »
is invalid.
         The deficiencies  in  the  Ram Trac  report are magnified
when the  other  presumptions  employed by  that  company  are  ex-
amined.  For example,  Ram  Trac  seeks to reach  a  source assess-
ment based upon  a multiplication  of the estimated waste volume
by the concentration of the substances of concern ".   . .as meas-
ured  in  the environmental  media  for  which   data   are  avail-
able..." FS,  Appendix  E,  p.  57.   However, the media  truly  at
issue  is air; virtually no  data exists  for the  concentration of
substances of concern in air.   Ram Trac then looks to data aris-
ing from  media  which  are  nai purportedly  complete  pathways  in
this health  risk assessment: groundwater, leachate,  and exca-
vated  drums.  This  reliance upon  data from media which  are  ad-
mittedly not part of the exposure pathways under  review results
in insupportable conclusions.
         Moreover, the Ram  Trac assumption that buried drums ".
.   .are of 55-gallon volume,  and  that  they are  distributed  at
this same  density throughout the  landfill.  .   .• is completely

                             - 27  -

-------
without foundation.  FS,  App.  E, p.  57.   Drums were  excavate;
in the 6.5 acre portion of the site which  is  separated from th<
main  landfill  mound  by the Transcontinental  Gas Company  pipe-
line.  No  investigation,  excavation or analysis  has  been  per-
formed in  the  main landfill mound.   Consequently,  there  is  no
support for a  conclusion  that  drums,  of any  particular  content
or  density,   are   present  in  that  portion  of  the  landfill.
Inasmuch as that  mound portion of  the landfill represents  the
overwhelming  majority  of  the  total  acreage  and  volume of  the
landfill,  the  lack of  any specific  information _tp_ support  the
view  that  drums  are  present therein  is  a  major, and  obviously
fatal, defect  in the  source assessment developed by  Ram Trac.
         The  deficiencies  in the calculation  of  the source term
are  acknowledged  by  Ram Trac.   ifl.  at p.  58  ("[tjhese  values
are  set  forth with  the caveat  that  significant uncertaintiefl
are  associated  with  them*).   Therefore,  the source  assessment
upon which the risk assessment relies is gravely dubious  — any
and  all  of the  conclusions  which  flow from  it are  similarly
doubtful.
         The  risk assessment  is totally incapable of demonstrat-
ing  a  true exposure  pathway  that is based on quantifiable,  ob-
jective information^ *n*  th«  calculation  contained in  the risk
assessment of  the contaminants which  are  travelling  that  pur-
ported  exposure   pathway  is  similarly   unsupported.    Unfor-
tunately,  the failings of  the  risk  assessment do not  end  there
                             - 28  -

-------
—  also  insupportable is  the determination  of concern  index
which depends upon groundwater action levels.
         There is no  dispute that groundwater does  not  present
an  exposure  pathway  in  connection with  Global Landfill.   £££
id.  at  1-21.  There  is  also  no argument  that  the Old  Bridge
Sand aguifer reflects ".  .  .leachate indicator parameters gener-
ally close to  background  levels," and that any  remedial  action
relating to  the  groundwater will be  the  subject of OU#2.   Id.
at  ES-4.   Groundwater at  or near Global  Landfill  is not  a  po-
table water  source  for the  surrounding residents;  indeed,  the
nearest  well  is  both  some  distance  away,  and  upgradient.
Adoption of  drinking water  standards  in  connection with  this
site is therefore inappropriate and unreasonable.
         Significantly,  NJDEP  similarly  rejected  Ram  Tree's
interpretation of  "concern  indices."   In a memorandum  dated
November 13,  1990,  which  followed  review  of the October  1990
"final  draff  of   the  FS  risk  assessment  section,  an  NJDEP
research scientist wrote the following:
         1)   The concept  of  using  hazard  index  values  [the
         label  used  for   "concern  index*  in  the  predecessor
         document]  as  described  on page  178  [the same  page in
         the February 1991 FS,  Appendix  E]  is  unorthodox.   As
         stated  on  page 176  "In particular,  the hazard  index
         value  corresponding  to a   pollutant  'present  in  the
         Global  Landfill is  calculated as  the  concentration at
         which it was detected divided by  the  applicable NJDEP
         action  level.  Thus,  with  respect to any  substance,  a
         hazard  index value equal to  or exceeding  unity  denotes
         that  the substance  is present at  levels of concern to
         NJDEP,  and  that   remediation is  appropriate."   This
         approach is  basically comparing  site related  levels to
         ARARs  and  determining   if   the  ratio  exceeds   unity.
         This  is not  consistent with the EPA approach  which

                             - 29 -

-------
         compares a  site related  exposure level for  any  tox^
         cant to  a  reference dose  (based on a  daily  exposu^B
         for that  toxicant  and  then  sums the  hazard  quotient
         for the  same exposure  period.   When the  hazard  index
         exceeds  unity,   there   may  be  concern  for  potential
         health effects.  It  should  be  noted that seme of  tJie
         NJ  action  levels  are  not health based aqd  therefore
         exceedance of these values does not accurately portray
         the  potential  for any  site   related  adverse,  health
         effect.  It  is  also incorrect  to  state that  remedia-
         tion is appropriate if  there has  been  an  exceedanee of
         a  NJ  action level.   Action  levels can  be  exceeded
         without remediation.

&££ Appendix D, p. 1  (emphasis  added).   Insofar  as  the Ram Trac

analysis depends  upon the  determination of  "concern  indices,"

which determination is questioned by NJDEP  itself/  the conclu-

sions of the risk assessment are indisputably unfounded.

         when the FS  risk assessment  is  viewed  in  totality,  the

following  can  be gleaned:   The   landfill  most  likely  emits

odors, as  all  landfills  do.  The  landfill most  likely presents

a leachate problem,  as any landfill which was not properly

tained or  covered by  the operator would.  These  qualities  or

characteristics can be addressed readily  by the implementation

of  gas  (methane) 'controls  and  the  addition  of  a  simple,

straightforward cover  which will  interfere  with the  rainwater

infiltration thus significantly  reducing,  and ultimately elimi-

nating,   leachate  creation  and   movement.   No  risks  have  been

chown to exist  at or near  Global  Landfill which call  for  more

extreme measures.
                             - 30 -

-------
IV.       THE AGENCY HAS FAILED TO INTEGRATE THE FIRST OPERABLE
         UNIT WITH ANY LATER GROUNDWATER REMEDIATION OPERABLE
         UNIT
         The  Proposed Plan  artificially separates  groundwater
treatment from those  elements of OU#1.   Although the concept of
dividing remedial  actions  into  operable units is  recognized in
the  provisions  of the NCP,  40  C.F.R. Part  300,  a lead  agency
may utilize operable  units only if  they  are  consistent with  the
expected final remedy and meet the  basic statutory criterion of
cost-effectiveness.   40   C.F.R.   §  300.430(a)(1)(ii)(B);  42
U.S.C. § 9621(a).                           "	""
         The initial  phase of the RI/FS  process consists  of  the
scoping  of  the  project.   The scoping  process includes  assem-
bling and evaluating  exi-:tir;T £.•;-.* for a site,  developing  a con-
ceptual  understanding of  the  site,  and  identifying  operable
units that tr.ay  address  site problems.   40 C.F.R.  § 300.430(b).
Yet,  in developing the operable units described in the Proposed
Plan, NJDEP has  not  properly scoped  the nature  of the site or
the potential conflicts between OU#1  and OU#2.  Thus, NJDEP has
developed a final  remedial  action recommendation  for OUJfl that
may  be  inconsistent  with  the remedy  for OU#2, that  bears  no
relationship to  the low short-term  risks presented by the site,
and  that will   result  in  an overall   response  which is  not
cost-effective.
         The  potential  for  inconsistency  is manifest  in  a
number of ways.   First,  the  PRAP's  alternative  for OU#1  calls
for the  construction  of  a berm at  the  foot  of the landfill  in

                             - 31  -

-------
-rSer to provide  the  support  that NJDEP claims is necessary
«-h«? weight  of  the cap.  Yet, the presence  of  the term may
elude as a  component  of  OU#2,  the construction of a slurry wall
.0  arrest  migration of groundwater  (due  to high pore pressures
leading to  slurry trench instability),  even though slurry walls
have been  accepted as efficient and effective means of address-
•-7  groundwater  conditions  beneath municipal  landfills.   See.
».«., Record of Decision for Helen Kramer Landfill.
         Second,  OUfll has  been developed to  close the landfill
    .. ..-ilructing a cap,  a  gas collection and  treatment system,
_.;: e leachate  collection  and treatment system, entirely within
the property limits of the landfill.  In so doing, the PRAP al-
ternative  significantly restricts  placement  of  various  struc-
tures required  to  be  implemented as  psrt of OU#1.  Yet, the rem-
Ox<.  fnr  ou#2   will,   in  all   probability,  extend  beyond  trfl
property limit  of the landfill.   In order to reduce the overall
fci,6ce requirements  around  the  landfill  to a minimum,  it is more
logical to  wait  for  OU#2  and  integrate  it into  OU#1,  so that
 .l.ler.ds impacts  are  reduced.
         Third,  the  Proposed  Plan  acknowledges  that  the  pre-
ferred  leachate collection and  treatment system  should  not  be
constructed until  NJDEP  can  evaluate whether  a single treatment
-i = r.f can  be  designed  to address  both  landfill  leachate  and
....ndwater.  The  Proposed Plan addresses this problem by allow-
_::g, while  this evaluation takes place,  for  a contingency sys-
tem that  requires collection of  leachate in  on-site  tanks  for

                             - 32 -

-------
ultimate  trucking  off-site  for  disposal.   Confusingly,   the
Proposed  Plan  nevertheless expresses  a preference for  ori-^ite
treatment and discharge  as  part  of  OU#1.   If  NJDEP follows  this
stated preference, a  treatment system  for  leachate could be de-
signed and built  prior  to  a period  of  dramatic leachate  charac-
teristic  and  volume  change,  and before the  groundwater treat-
ment  system,  if  any, is analyzed  and determined.  This could
lead  to  potentially  duplicative treatment systems  —  one  for
leachate  and  one  for groundwater  —   and  an overall  response
which  is not  cost-effective. _Had the  project  been  properly
scoped,  NJDEP could  have avoided this  inefficiency and  lack of
cost-effectiveness by providing  for the design  of the leachate
and  groundwater  treatment  systems  concurrently  (once the  lea-
chate  generation,  volume,  and characteristics stabilize  follow-
ing construction of the cap).
         Fourth,  the  Proposed Plan  states  that  OU#2 will  focus
on  the natural   resources  at the  site.  In  spite of this  ex-
pressed  intent,  OU#1  calls  for the construction of a  berrr,  that
will  substantially impact  the most obvious natural  resource at
the   site,  the  wetlands,  without  making  any  evaluation  of
whether  the need for the berm outweighs the  destruction of the
wetlands..     •     	
         These   numerous   possibilities   for   inconsistency,
coupled with the  fact that  the site, even  in  its present state,
presents  extremely low  risks,  compel  the  conclusion  that  the
                             - 33 -

-------
operable  units  developed  by the  department  are inconsiste
with the NCP.
V.       THE AGENCY HAS FAILED TO INCLUDE ANT INTERIM ACTION
         ALTERNATIVES WHICH ACCOUNT FOR DATA CAPS AND WHICH
         ARE COMMENSURATE WITB THE LOW LEVEL OF RISK AT THE SITE
         As described  in  the  risk  assessment,  current  site
conditions  present  a  low  level  of  potential  risk  to public
health and  the  environment.   The only pathways for even these
potential risks  are  direct contact and the  air,  both of which
can  be   -addressed  -by  site—controls/  -gas  collection . and
treatment,  and  an interim  cover.   Moreover,  based on  NJDEP's
understanding  of  the  site  conditions, the  settlement rate for
the  landfill  has not  stabilized.   If these  analyses are cor-
rect, then  NJOEP  should have  considered  and adopted  an  interind
action for  the site.  An  interim action would have  addressed
the perceived risks at the site while developing an  integrated
and consistent  approach to final  remediation of the  site.  See
55 Fed.  Reg.  8705,  col.  1 (March  8,  1990).   It is well-under-
stood that  "a  temporary  cap  as an interim  action  may be war-
ranted in situations where  the  settlement  rate of  the  landfill
contents  has  not stabilized.*  Municipal Guidance  at pp. 4-8.
Given the low  ivv.i  »,» wU*i"^i-rt  :vis»R  sad WJDEPVs understanding
of the site, NJDEP's  failure  to  consider an  interim  action oper-
able unit to deal with the site on a  temporary  basis  was incon-
sistent with the NCP.
                             -  34  -

-------
VI.       TEE GEOGRIDS, SAND, BERM, LEACHATE TREATHENT PLANT, AND
         CAP CONTAINED IN THE FRAF ALTERNATIVE  ARE NEITHER
         NECESSARY NOR PROPERLY DESIGNED
         A.   Geogridi
         The PRAP alternative cap calls for two layers of rein-
forced geogrid to prevent  settlement of the  landfill  from af-
fecting the performance of the cap  and to  prevent  the cap from
"sliding."  However,  as  noted previously, a quantitative assess-
ment of future  long  term settlement  of  the cap has not been per-
formed and  no numerical justification  for  the geogrids is pre-
sented in  the  PRAP.  And, with  regard to slope  stability,  zr.
analysis   which   uses  the  appropriate parameters  for  refuse
strength  and which  takes  account of soil  aging  indicates that
the slope of the landfill has stabilized.  There  is,  in short,
no justification for  the assumption that  the layers of geogrid
are needed.  Slope stability analyses with appropriate soil and
refuse parameters indicate that the  landfill  slopes  are stable.
         In fact, the geogrids are  unnecessary.  The cap's soil
cover  materials  would  be  of sufficient  strength   so  that re-
inforcement will not  be required.   There  is  no need to provide
geogrids  in order to  reduce the tensile stresses in the cap ma-
terials that are due to a tendency  for them to  slide down the
slope.   The interface  friction  between  the materials  of the
PRAP  alternative cap is   sufficient  for  slopes  as   steep  as
2.5H:1V.   The  slopes at Global  Landfill  are much  less  steep,
                             -  35  -

-------
generally ranging from  5H:1V to  3.5H:1V.   Furthermore,  the tei
tured FMC that would  be part  of the PRAP  alternative cap  has
roughened surface, which increases available friction.
         There is no need to require geogrids to address the ef-
fects of depressions  and crevices in the  landfill  surface that
are  due  to  large local  absolute or differential settlement  of
refuse.  There  is  no indication that  such large  deformations
have formed or will form.  Because  the  landfill  has been closed
for  seven years,  it  is  far  more justified  to assume  that the
major part of final settlement  has already occurred.  _    	.._
         The landfill shows no evidence to suggest  it  will pre-
sent greater future settlements  than other sanitary waste  land-
fills.   It  is  not general practice  to  include geogrids in the
cover designs of  sanitary waste landfills,  and  their  inclusion
at  Global Landfill  is  unjustified.  Other  landfills under
jurisdiction of NJDEP, such as GEMS or Helen Kramer, do not in-
clude geogrids, even  though  they are Superfund  sites  and  exhi-
bit  in certain cases  slopes  much steeper  than  Global  Landfill.
This indicates an  inconsistency  on  the  part of NJDEP  in  impos-
ing  geogrids at the Global Landfill site, where  the  settlement
potential is  no  greater  than  other, similar  sites where  geo-
grids have not bean 3mc?3Jnenta!?L
         Furthermore,  even  if  the  geogrid layers  were  needed,
they would  not  be  effective  if implemented in  the manner  set
forth in the  Proposed Plan.   First, the PRAP  alternative  would
place the upper layer only twelve inches   below the surface. At

                             -  36 -

-------
that depth, there would be inadequate  load on  the  upper  grid  to
generate enough shear resistance for the upper grid to be effec-
tive.  Second,  the  Feasibility Study  assumes  a minimum factor
of safety of 1.13 with a berm,  which would  produce disturbances
for which the  lower  geogrid  would,  in any event,  not  be effec-
tive.  The geogrids, therefore, do  not  add to  the  long-term ef-
fectiveness of the cap.
         Moreover, the geogrids can create  substantial  implem-
entability concerns.  There  are significant  problems  associated
with their  installation, which is  an  operation of some diffi-
culty.   Unlike geonets,  which  are uniaxially unrolled, geogrids
are difficult to  install when  installed  biaxially. When double
grids have  to  be installed  to provide  biaxial  strength  as  is
the case for covers,  the  geogrids  tend  to roll up in two perpen-
dicular  directions.   The contractor installing them on  a slope
lias to provide  additional  labor to  unroll the grids  in  two di-
rections to  hold  them down  as soil is  placed above  them.   in
addition,  repairs to the gas header  pipes of the gas  extraction
system,  buried  under  the cover, will  require cutting the  geo-
grids,   thereby  losing any  contribution  they  may make   in the
strengthening of the cap.   In order  to  repair the geogrids,  bod-
kin  connectors  would have  to  be  'needled*  into  the  existing
grids,  an  operation which  may not   be  successful  in  restoring
the grid's  strength  and  other  properties.   The need  to repair
gas header pipes raises  the possibility that, however  little ef-
fectiveness  the  geogrids would  have contributed  in   the  first

                             -  37  -

-------
     ,  even  that  level  of effectiveness would be undermined
tne repairs.
         B.   Soul
         The  placement  of  the  sand  drainage  material  immedi-
-'ely above the liner is less implementable than would  be a geo-
ncr ,  which  is  easier  to control from a QA/QC aspect.  The geo-
-•««•  rould  be  more  rapidly installed with a superior perform-
s-r-e   Ease  of installation is much  enhanced  by the  fact that
 ?« oecnet may simply be unrolled.   The superior performance  re-
sults because  the  geonet,  with its crisscrossed plastic grids,
is  much  more  permeable  than  sand,  producing  better  surface
water drainage laterally.

         C.   Berm
         The PRAP alternative would include  a toe berm in order
to increase  slope  stability.   A berm is unnecessary.    Even  as
proposed,  the  berm would  not  be  effective.   The  inclusion  of
tne  berm also would  have  a significant  adverse impact  on  the
surrounding wetlands.
         As  discussed  above,  the   landfill  stability analyses
I.o.-c, used  erroneous  strength parameters  for the refuse, which
 . =  critical parameter  in determining  slope  stability.   The
rrrner use  of back  analyses  would have  demonstrated  that   the
rtrength is nearer to a friction angle of 34  degrees  and  a cohe-
sion of  334  psf,  rather than the  values  of  22 degrees  and  200
                                             POOR QUALITY
                             - 38 -             ORIGINAL

-------
psf  that  were  used   in   the   Feasibility  Study  for  refuse
strengths.^/   Similar  refuse  strengths have been used  in  the
design  of  caps for other  solid fasce  landfills  without  berms,
and  with  successful  results.   Thus, given  the  appropriate  cal-
culation of  refuse strength and  the data  from  the  performance
of similar  landfills,  the  berm is  unnecessary to achieve slope
stability.
         Moreover,  construction  of the  berm would be  a  diffi-
cult operation, as it  would involve substantial  loading  of  the
underlying soils.   The  increase  in pore pressures in the  under-..
lying  soils  would  have to  be monitored  carefully, to  ensure
that pure  water  could  drain fast  enough for the  soil  to with-
stand the  loading.  Any  overloading could  lead  to a  slide,  with
waste  being  pushed  into  the  wetland.   If wick drains  were
added,   an  additional  10,000 gpd of leachate  would  have to  be
treated.
         In addition,  construction of the berm could be accompa-
nied by significant  settlement  of the  underlying soils,  which
might also contain waste.  This might lead to waste being  perma-
nently  trapped under  the  berm outside  the cap,  and must  pre-
clude  any subsequent  attempts  to address  this  trapped  waste
without removing portions of the berm.   Because of the difficul-
ties of the  construction  of the  cap,   and  the  risk that  some
      £fi£ Appendix A.
                             - 39 -

-------
waste might  be  trapped  by the  berm,  the  implementability,
well  as  the  long-term effectiveness, of  the  PRAP  alternative
would be reduced by the inclusion of a berm.
         Not  only  is  the  berm unnecessary and  ineffective,  it
would harm the environment.  Construction  of  the berm would re-
quire the destruction  of  approximately 2.4 acres of  wetland.  As
construction  of the  berm will  affect  an area  significantly
greater than  the berm  footprint,  the Feasibility Report has se-
riously underestimated the  extent  of wetlands  impact.   Thus,
the  proposed  berm  is  not protective-of the-environment.  - Nor
have  practicable alternatives  been  explored  to avoid  the  pos-
sible wetlands  impacts,  thus violating  applicable wetlands re-
quirements.          •

         D.    Leaf hate Trtatment Plant
         Although leaving the final choice of treatment alterna-
tive  to remedial design,  the Proposed Plan  expresses a prefer-
ence  for  leachate  collection  and  on-site  treatment   as  part  of
the  preferred  alternative.    The  proposed  leachate  treatment
plant is  not  cost-effective for  two reasons.   First,  the  PRAP
alternative does not  take into account  the  sharp drop  in flows
after the  first year.   Second,  it  does not take into  account
                             - 40 -

-------
the efficiencies associated with  a  comprehensive  treatment  pro-

gram  in  OU#2,  if  any is  needed.1*'  The  leachate  treatment

plant  was sized on  the basis of  10,000  gpd  of  liquids to  be

treated.  The  expected generation rate of leachate  provided  in

the  Feasibility  Study  is   10,000   gpd  for  only   the  first

££££ H/  Tne  expected leachate flows are  1,000  gpd  from  year

six onwards.14 '    Consequently,  there is every  reason  to  con-

clude  that it  would  be more sensible  and  cost-effective to  add-

ress  any  leachate treatment  along  with  the groundwater treat-

ment  at  the time of .any OUH.2, and provide an -alternative  and
      The  proper  approach  is represented in EPA's  selection of
a  leachate  treatment  remedy at the Helen Kramer  Landfill  site.
See  Record  of Decision for  Helen  Kramer Landfill at  32  (Sept.
21,  1585).   There,  EPA  rejected  the  separation  of  groundwater
from  leachate into separate  operable  units.   Id.  at 34.   The
decision  as  to whether and to what extent  on-site  treatment of
the  leachate  and groundwater  was needed  was  reserved  until
treatability  studies  were  completed,  on which  the  decision was
"dependent."   Id. at  24  and  32.  The results of the study  would
assist  the  determination of whether complete  on-site treatment
or   pre-treatment  with  off-site  discharge   were   the   most
cost-effective.    Id.    EPA   noted   that   because   of    the
"substantial  flow decrease with time,*  alternatives  to building
a  plant on  the  site  might  be  preferable because  they  "should
lower  the capital cost." Ifl.   "Thus,  the Kramer ROD concluded
that  it  would   be  possible  'to  rent  a   number   of  package
treatment  plants instead  of building  a plant  on  site.'    Id.
The  Kramer  ROD retained  sufficient  flexibility  to adapt  to both
the  results  of  the  Treatability  Studies  and   substantial  flow
decreases."
      Feasibility Study, App. K,  table 2.  The  levels  for years
2, 3 and 4 are 4,700, 3,200 and 2,100 gpd respectively.  Id-
                             - 41 -

-------
 temporary  solution for  leachate  until OU*2 is  implemented.-^^
 wore  important, there  is no  reason  to conclude  that  the pro-
.posed  treatment plant would be effective.   One of the most se-
 ricus  flaws in  the  technical  work done to  date is the absence
 of  treatability  studies.  Leachate  constituent  concentrations
 will  vary  as  the  installation of  any cap decreases precipita-
 tion  infiltration and.  as the landfill  continues  to decompose.
 It  is  simply  not possible  to be  confident that the proposed
 treatment  p:ant will  be effective  or reliable because  of the
 tremendous  uncertainties relating to  the landfill  leachate.	
         Furthermore,  there  are  implementability  concerns.  The
 leachate  treatment plant  study  in the  Feasibility Study  indi-
 cates  that  priority  pollutants  are present in the influent in
 "trace  amounts" and no  difficulties  are anticipated in meetin
 the  discharge   limits.   The  discharge limits have not  yet b
 established but could be quite low.   In the absence of treata-
 bility  studies, it has  to be  demonstrated that such low  levels
 can  be met.  £fi£  40  C.F.R.  §  300.430(e)(9)(iii)(F)(1) (imple-
 mentability includes  "[tjechnical feasibility").  Moreover, the
 NJDEP  discharge limits  are as  yet unknown, which  also  seriously
 places  in  doubt the  administrative feasibility of the  discharge
 to  surface  str~=^.  £~>  40  C.2V?..  |  3C-2. «3D<2) <9) (iii) (F) (2)
 (implementability  includes "Mdministrative feasibility").
      The   Feasibility   Study   identified  a   Chemical  Waste
Management  facility only 25 miles  from the  landfill  that  was
prepared to  accept  untreated leachate  and gas condensate.
                             - 42 -

-------
         E.   Composite Cap
                          Technical btuet
         The  Proposed  Plan's  preferred alternative  includes  a
synthetic  geomembrane  using   a  geoteztile  made from  recycled
plastic bonded  to Hypalon.  The  availability and long-term per-
formance of  such materials  are unproven,  particularly given the
size  of  the cover and  its  behavior when  the  landfill  settles.
Hypalon has  an inherent weakness  in that the  scrim reinforce-
ment  from  which it  derives its initial  strength can  act  as  a
wick, and  the water  in  the wick can lead to  separation  of the
multiple layers of  polyethylene.   This liner  is  therefore not
as  reliable  as  alternative  synthetic   liners,  reducing  its
long-term effectiveness.
         The  construction of  a composite  cap,  where a  flexible
membrane liner  is to be placed over a clay material, is accompa-
nied  by risks  associated  with  moisture  collecting under  the
liner during construction.  The moisture may originate from con-
densation,  or  consolidation of the clay from  the weight  of the
materials  above.•^/    The wetted  clay  may lead  to  a stability
problem of  the cover  sliding,  unless  a  great  deal of care  is
      Mitchell,  Seed  and Seed,  Kettleman Hills  Waste  Landfill
Slope  Failure;  Liner  System  Properties,  116  J.  Geotechnical
Eng. (April 1990).

-------
taken during  the construction of  the  cap.12/   The liner  cl
would have  to be carefully protected from  rainfall  and  thermal
effects  during and  after  placement.  This  renders the  actual
emplacement of the PRAP alternative  cap difficult.  There  ex-
ist,  therefore,  serious   questions  as  to  its  implementabil-
        an
-------
100, end, for a period of time,  1000 kilograms per month  of  har-
crdous  waste from  small  quantity generators.^•/   And,  as  de-
scribed  in  the leachate monitoring  data,  the contamination  at
Global  Landfill  is  similar  to  that  found  at  other  municipal
waste landfills.
         Yet,  the  Proposed Plan  would treat  the site  differ-
ently  from  a  municipal  site.   The PRAP  alternative would  in-
clude a modified hazardous waste composite cap that  consists  of
a 12  inch clay layer,  a synthetic layer of  a non-woven  geotex-
'. ile  spun  from recycled plastic  and  bonded  to a  Hypalon-based
containment  membrane,  a  drainage   layer,   and   a   vegetative
layer.   Proposed  Plan  at  6,  9.   In  these  circumstances,  the
Proposed Plan must  be supported  by  independent reasons  for  this
substantial   departure  from requirements and practice for  clo-
sure of a municipal  landfill.  Such reasons  are not  to be found
in  the  Proposed Plan  or  accompanying materials.   On the  con-
trary,  the  analyses contained  in the Proposed Plan  support  the
conclusion that this site is, and should be  closed as,  an ordi-
nary municipal landfill.
      Under  RCRA until  19B4,  a  small  quantity  generator  was
allowed  to  dispose  of  up   to   1000   kilograms/month   at   an
authorized  municipal  landfill.    40  C.F.R.  §  261.5(g)(3)(iv)
(1984).  In  1981,  New Jersey  authorized  disposal  of up  to  100
kilograms/month  by   small  quantity  generators   at   municipal
landfills,  a requirement that  is currently  in  force  in both  New.
Jersey and RCRA  regulations.  Sfifi fi.J.&.C. 7:26-8.3(f )(3)(iv);
40 C.F.R. § 261(f)(3)(iv)(1990).

-------
              1.   A Bazanfomj Waste Cap It Not Juti/itt By Tht JUcft AuaxmeM
         The baseline public health  assessment  does  not  support
the use  of  a  hazardous  waste cap.  The  assessment  indicates  nc
immediate danger to human health or  the  environment.   No drink-
ing water  wells  are located downgradient  of the landfill.   No
studies  have   identified  significant  exposures or  threats  to
human  health  from gas emissions from  the landfill.   Odor pro-
blems  have  been  identified,  but they  have not been  quantified
in the  Feasibilty Study as being  different  from any  other  mu-
nicipal landfill.
         The  baseline  public health  assessment identified  ten
potential  pathways  which,  upon further  investigation,   may  be
found  to be complete.   Most  concerned ambient  air  or  windborne.
particles,  which  a  noncomposite cover would prevent.^'   Th
other two pathways refer to on-site contact,  which could be pre
vented by erection of a fence or a  noncomposite cover.  None  of
the identified pathways  requires  a very high performance cover
I
2-Q'   Although the public  health assessment in  the  Feasibility
Report has  identified  airborne  pathways as the  majority  of all
potential  pathways,  no  ambient air  quality investigation  has
been  performed.   Air quality data  which  is  available has  not
been used in the choice of cover section.

-------
to prevent escape of gas front the site.   The choice of  a  compos-
ite cap is neither necessary nor a cost-effective  means  to  edd-
'•oss the  identified  pathways  of  direct  contact in the risk  as-
sessment.   Thus, the choice  of  a composite .cover  is simply  not
justified by the risk assessment.

              2.   KCRA StMdf C h Not Am AXAK
         The  Proposed  Plan,   with  no analysis,  states  conclu-
-~'My that  " [h] azardous  waste  landfill requirements  are  rele-
v:.-.t  and   appropriate   for  closure  of _the  Global Landfill.^
Frcposed  Plan  at 8.   EPA describes  "relevance"   as addressing
"similar situations or  problems," and "appropriate"  as address-
ing "whether  the requirement is well-suited to the particular
site." 55 Fed. Reg.  8743,  col.  2 (Mar.  8,*  1990).  As  EPA  noted
3 r. trie preamble to its  proposed  NCP, even  the. basic requirement
to cap  landfills  upon  closure is "an  example of  a  requirement
that may be  relevant but  not  appropriate  in certain situations.
..."  53  Fed.  Reg.  51437,  col. 1  (Dec.  21,  1988).ii/    Thus,
"la]lthough  capping  may  be  appropriate for  smaller  areas,  it
may not  be  appropriate in  some circumstances for  large  dis-
~ersed  areas of  low-level  soil contamination such as  may  be
:*,-,.3'  at  many large solid  waste landfill  facilities."  Ifl.   A
*-*''   Unless directly  contradicted or superseded  in the  final
NCP,  "the  preamble  to  the  proposed  rule reflects  the  EPA's
intent  in  promulgating  [the]  revisions  to the  NCP."  55  Fed.
neg. 8666,  col. 3 (March 6,  1990).
                             - 47 -
                                             ORIGINAL

-------
hazardous waste cap  is  even  less  "relevant and appropriate* fM
Global Landfill.
         The NCP  requires that  a  determination of whether a re-
quirement is an ARAR must be  the  product  of an analysis of sev-
eral  factors.   An  analysis  of these  relevant  factors  estab-
lished by the  NCP does  not  direct the use of  a hazardous waste
cap at Global  Landfill; rather, the factors  reinforce  the con-
clusion that use  of  the proposed hazardous waste cap would not
be justified at this landfill.

                        a. Katurt of the West*
         The  NCP  ARAR  determination  analysis  requires,  inter
alia.  a comparison of the "substances  regulated by the require-
ment and the substances found at  the CERCLA  site."  40  C.F.R.  §
300 .400(g) (2) (iii).  In order to find that RCRA closure
ments are "relevant  and appropriate,"  there should be a showing
that either  RCRA hazardous  wastes,  or wastes similar  to RCRA
hazardous wastes, are present at  the facility  subject  to these
requirements,  fififi 55 Fed. Reg. 8763,  cols. 1-2 (Mar. 8, 1990);
53 Fed. Reg. 51447,  col.  1.   However,  even if  waste  similar to
RCRA hazardous wastes or containing  RCRA  hazardous constituents
are present, there is no presumption t.hat a *?»A requirement is
relevant  and appropriate.   Preamble  to Final NCP, 55 Fed.  Reg.
8763,  col.  2 (Mar.  8,  1990).   To the contrary,  EPA  states that
"low concentrations  of  a  hazardous  constituent, dispersed  in
soil over a  wide  area,  would generally not trigger  Subtitle  C

                             - 48  -

-------
as  relevant and  appropriate.-  "CERCLA  Compliance With  Other
Laws  Manual,"  at  p.  2- 6  -  2-7  (Aug.  1988)  (Interim  Final).
Thus, it is important to determine if a waste similar to hazard-
ous  waste  is present and whether  that waste  is  representative
of the Global Landfill's contents.
         Global  Landfill  consists  of  two  distinct  landfill
areas.  Proposed Plan at 2.  The only investigation for  hazard-
ous  wastes  was  performed at the sraller, 6.5  acre  tract.   That
investigation claims to  have revealed the presence  of hazardous
wastes in  fourteen drums.   However, the  fourteen drums  of haz-
ardous waste constitute  an  isolated  instance'and  are not repre-
sentative of  the  contents  of  either  the  6.5 acre  tract or the
51 acre area.  The drum  investigation spanned  a two week period
and  a  few  drums  were  encountered  on   ei-ght  different  days.
Excavations were performed  at  locations which  had  been  identi-
fied by positive magnetometer readings. .Although there were nu-
merous  areas of   very  high magnetic concentrations,  most  of
these proved  to  represent  buried metal representative  of  solid
waste  (such as  stoves  and  refrigerators),  rather   than  buried
drums.  Feasibility Study,  at pp.  1-9, 1-11.
         The drum  excavation went to  a depth of 15  feet  through
municipal waste  and only.discovered 63 drums  —  relatively few
for  an  area that  size but  consistent with the contents at  mu-
nicipal  landfills,  which   would  typically  include  relatively

-------
small  amounts  of  hazardous  waste  from  small quantity  gener

tors.  The Feasibility  Study  determined  that  "no organized  pa
i
tern of  drum disposal could  be  established" and that  "no  spe-

cific hot spots or areas of elevated contamination have been de-

fined  at Global  Landfill.-   Feasibility  Study at  pp.  1-11,

2-13.  Rather,  the  results of  the drum excavation were  summa-

rized as follows:
         At  Global Landfill,  specific  locations  of  hazardous
         wastes  have  not  been  identified.   Instead,  as  indi-
         cated by  the  results of the  drum  investigation,  drums
         containing hazardous  waste were found  randomly" inter-
         mixed with municipal refuse, construction  and  demoli-
         tion  debris  and other  bulky wastes.  During the  drum
         investigation,  a  total of   approximately  1900  cubic
         yards  of  waste  material  was excavated  and  63  drums
         were  encountered.   Assuming  all 63  drums were  55  gal-
         lons  in  capacity  r-.rd  originally  contained  hazardous
         waste,  the  volume of  hazardous waste  encountered  was
         approximately one  percent  of  the total  volume of  was^
         excavated.


Feasibility  Study   at  pp.  2-21,  2-22  (emphasis  added).    The

calculation of even this 1\ value  is  based on overconservative

assumptions.^'    Moreover,  because the excavation  was  already

targetted toward the  areas that  registered positive during  the
      Feasibility Study at  p.  2-22.   The assumption that  all  63
drums were  "full" of  hazardous  waste is, of  course,  incorrect
even unaer the saets  is dsv^ioped  H-'«in.9 the drum survey.   Some
of  the  drums were  corroded or  crushed,  so  there  is  no  infor-
mation on what they contained.  In fact, only 18 out  of  the  63
drums were actually sampled; of  those,  4 were determined  not  to
contain hazardous waste.  Thus,  even  to reach the "1%" estimate
required unwarranted and overly conservative assumptions.
                             - 50 -

-------
magnetometer survey, it is obvious that  far  less  that  1\  of  the
waste is likely  to  be  hazardous.  Under  these circumstances,  it
ir clear that the contents of the 6.5  acre  tract  are not  repre-
sentative of a hazardous waste landfill.
         At  least equally important,  no such  investigation  was
initiated for the 51  acre landfill  tract.   Ifl.   In the  absence
of evidence  establishing  that hazardous  waste is  representative
of the  contents  in  that  portion  of  the landfill, the documen-
tary evidence  supporting  the Proposed Plan states that  the  51
acre tract   contains .only "municipal  solid,  bulky, vegetative
end  non-chemical industrial  waste."   Ifl.   Those  are  precisely
the types of wastes which a  solid waste  landfill  is  licensed to
accept   and  for  which  the solid waste  closure requirements  were
designed.^/  To extrapolate from the conditions  found  in  iso-
lated instances  in  a  much  smaller  tract to a much larger  and
distinct  area,   and conclude that  the  entire site   should  be
closed  using  a  modified  hazardous  waste  cap,  is   unjusti-
fied.^/    The  only evidence in the Feasibility  Study supports
      Moreover, given  the  authorized  disposal  of small quantity
generator  hazardous waste,  the  presense  of  isolated drums  of
hazardous  waste  is consistent  with  the  site's operation  and
closure as a municipal landfill.
      The Feasibility  Study merely  states  in one sentence,  that
 hazardous  waste  landfill  closure  regulations  are  relevant  and
appropriate  due to  the  known presense  of hazardous wastes  at
the  landfill."  Feasibility  Study on-Sitc  Controls at  Global
Landfill,   Vol.  I,  p.   2-12  (Feb.   1991)   (emphasis   added).
                             - 51 -

-------
the  conclusion that  the  51  acre  tract should  be  closed as
solid waste landfill.
         A  further  indication of the nati-re  of the waste at  a
landfill can  be gleaned by comparing leachate  data  with RCRA's
toxicity  characteristic  threshold  levels.    Under  RCRA,  waste
can  be  characterized  by  its  toxicity  as  hazardous  waste.
Toxicity is  measured by  the  TCLP>  a test designed  to  simulate
leaching of the waste,  and  to measure the concentrations of  me-
tals, volatiles,  semivolatiles and pesticides  in the  leachate.
Examination  of the  leachate  quality results -contained  in  the
Feasibility Study support the conclusion that  this  is  a typical
municipal  landfill.^^   Monitoring  of  leachate  has  occurred
at ten  locations  at  least annually and often quarterly for  the
last three  and one-half  (3%)  years.  These  sampling results,  ij
                                                              i
general, show  a  low level of  toxicity.  The  average concentri
tions for  the hazardous  constituents  found at  Global  Landfill
which were  evaluated by  the  TC procedure  are  between  100  and
1,000 times  less  than the  leachate  concentration  levels estab-
lished  to  designate  a  hazardous waste.^'   There  is  only  one
value that  barely exceeded  the TC  threshold,  and  the average
                                                   in. the  drums
from  the   6.3   acre  landt'ili  cannot  be  compared   with   TC
thresholds.   TC  thresholds   take   account  of   leaching   from
hazardous  waste,  and  consequently  the  thresholds  are   less
concentrated than "pure" waste.
          Appendix C.
                             - 52 -

-------
value  for  that  constituent   is  far  below  the  TC  threshold

vpi'je.*^'    Thus,  these  low  leachate  readings  confirm  that,

w'red on  the nature of the waste,  Global should  ke  classified
      £e_e. Appendix C (the values for lead).
      The  leachate  sample  from  leachate  seep  L4,  taken  in
  -j;:y 1988, measured 5.53 mg/1 of  lead, which  compares  to the
re:;.?  threshold  of  5 mg/1.  See  FS,  Appendix D.   That value  is
J—rctrably an outlier.  All other  leachate  samples taken from
*-*<=> same  seep  ranged from .025  mg/1  to .41 mg/1 of  lead,  less
 '--  1/10 of  this  single value.   Id.  The leachate  samples
       from  the   -other   locations  had  a   range   from   below
  '—••able limits  to .576 mg/1  of  lead  and averaged 1/100  of
n-s-  Dingle  value.   For  a  variety of  reasons,  this  single
_»...i.ie 'does not overcome the overwhelming  contrary data.    	
      In  the  first  place,   the  Feasibility  Study  does  not
-isclcse  the methods used to collect and analyze  this  sample.
i*ur is  theie  any  evidence  that  a  challenge was  made   to  the
laboratory analysis  that  produced this anomolous value.   Thus,
this  value may well result  from poor quality assurance.   Seco
thp  value  for  th«-  single  sarrple  and   *.he  TCLP  threshold.
?cir,.-jm-.  a«:  ". ofchalt see? L3,  only  250  feet awty,  during  the
same  sampling  event, produced  a value of  '.465  mg/1, which  is
less  than 1/10 of  the value  at  L4.  The other locations  yielded
ivc:£ce values of  less thanl/200 of  the L4  value.   These  facts,
and the fact that  lead is  not consistently  the  highest value  in
the   readings  of  the  other   seeps,   suggest   that  the  most
  -.-:r,cble explanation is  that  the value  reflects  a small lead
particle,   rather  than   the  concentrations   from   progressive
icscning.    In  any  event,  in   light  of  the  consistent  and
f'verwhelrr.ingly contrary leachate data and the other  facts that
«
-------
and closed  as a  municipal  landfill and  not  a hazardous
landfill.
                         *. Natxrt oftfu Stir
         In order to determine when a  closure requirement  is  ap-
propriate, the NCP  also  requires a  comparison  between  the "type
and size  of  structure or  facility*  regulated by the  potential
closure  requirement and  that found  at  the  CERCLA  site.   40
C.F.R.  §  300.400(g)(2)(vi),  (vii).   The  nature  of  Global
Landfill  is  very different. from the  usual. RCRA unit,  which  is
typically a  discrete waste management unit that is  the product
of uniform  construction  and   operating  standards and  that  con-
tains  only  listed  or  characteristic  hazardous  waste.   Such
unit  precludes the  type  of unregulated  landfill  growth that  r<
suits  in  widely  dispersed waste  as  is  the  case  with  Globe
Landfill.
         In  fact,  EPA  has   explicitly  recognized  that  RCRA
Subtitle C caps  may not  be "appropriate  under certain circums-
tances for large municipal landfills. .  .if  the  waste  is  gener-
ally  of low  toxicity  and the contamination  is dispersed  over  a
large  area that  bears  little resemblance to the discrete units
regulated under  SCRA*-  53  res.  Keg.  5i«4/,  col,  2;   see  also
"CERCLA Compliance  with  Other Laws Manual,"  at p.  2-21  ("RCRA
covers are generally  not appropriate  for large  municipal land-
fills"  that."bearlJ little  resemblance  to  the discrete  units
regulated under  RCRA   Subtitle C").   The conditions  identified

                             - 54 -

-------
by EPA which  militate  against the use of  Subtitle  C covers  are

met  in this  case.  The Global  Landfill  leachate data  shows

consistently  low  levels  of  contamination,  thereby  indicating

the waste is  generally of  low toxicity.   Moreover,  the landfill

is  unquestionably a  large  site,  consisting  of  two  distinct

areas totaling approximately  57  acres,  and the waste  is  widely

dispersed over the 57 acre area.  Based on the size and type of

facility,  therefore,  it is clear  that Global Landfill  is  appro-

priately capped as a  solid waste landfill.2A'

         Moreover, the general principles  Q_overning_the closure

of municipal  landfills in the  Superfund program  reaffirm  that a

noncomposite  cap  typically  used  for municipal landfills  should

also be used  for this site.  As explained  by EPA,  such a  cap is

appropriate where  groundwater is  not being  used  for  drinking
      EPA has  underscored this  principle  in its  September  30,
1?P8 Record of Decision for  the  Oak Grove  Landfill in Oak Grove
Township, Anoka County,  Minnesota.  EPA has stated that:

      The  USEPA  does   not   believe  it  appropriate  to  use  a
      Subtitle  C  cap/cover  to   remediate   a   large  sanitary
      landfill where we have  such small  documented  quantities
      of hazardous waste known to have been disposed.

With respect to the important factor  concerning  the size of  the
facility, the  EPA  applied the WCP  requirements  described above
end concluded:

      In  view of  the   small  documented quantity of  hazardous
      waste and the potential wide  distribution  of the  waste in
      a  45-acre  sanitary  landfill,  there  does  not  seem to  be
      sufficient similarity between the OGSLF site and  the type
      of circumstances  Subtitle  C requirements  are intended  to
      address.
                             - 55 -

-------
water.  Municipal Guidance  pp.  4-7, fig. 4-1.  As  confirmed  in
the  Proposed  Plan,  groundwater  in  the upper  aquifer,  whi
exhibits elevated levels of  some  contaminants,  is not  a present
or potential  source  of drinking  water.   In the groundwater  of
the  Old  Bridge Sand,  the Feasibility  Study has detected  only
occasional  and low  levels   of  contamination.   The  Feasibility
Study has determined that there is  upward pressure  from the Old
Bridge Sand  which  confines  contamination in the upper aquifer,
thus  indicating  that the low  levels of contamination detected
may  well  be  attributable  to areawide contamination  rather  then
Global Landfill.  In any  event,  this portion of the Old Bridge
Sand  does  not provide  any  drinking water  supply.   The nearest
drinking water  intake  is  upgradient and approximately one  mile
away,  end  as  a  result  of  gravity and .attenuation,  is  not
affected  or   threatened  by   Global  Landfill.   Thus,  given  t
lack  of use of  groundwater  as a drinking water  supply, there  fs
even  greater  reason  to support  a  noncomposite cap,  consistent
with  solid waste closure requirements.   Id.

              3.   RCRA Dcxt Hex Ktfutrt A Compcrte Cap
         In  any  event,  even  if   it   is   assumed that   RCRA
requirements  should be  utilized  for the cover  on the  landfill,
these requirements do  not justify or mandate the cap  described
in the Proposed Plan's preferred alternative.   Under  RCRA,  the
primary requirement  applicable to  the  cover  is that the  top
liner must  be  more  impermeable  than  any  bottom liner or  any

                             - 56 -

-------
natural  subsoils.   40  C.F.R.  §  264.228(a)(2) (iii)(E)  (1990).
At Global, the bottom of  the  landfill  does not have a liner and
rests on  entirely  natural materials.   Under such circumstances,
a  noncomposite   top  cover   will  easily  satisfy   the   RCRA
requirement.                          ^__
         The  idea  of  a  composite  cap  derives not  from  the
regulations   of    RCRA    but   from   certain  guidance   issued
tnereunder.  At best, this guidance  is simply  information to be
-~r!sidered (TBC),  not an  applicable  or relevant and appropriate
requirement for the cap.   As stated  in  the Municipal Guidance,
"RCRA  provides technical guidance  that  defines  the types  of
layers EPA  considers  to  be  appropriate  for a cap  for  new RCRA
landfill  cells.   This  Guidance  is a TBC  (to  be considered)."
Municipal  Guidance at p.  4-11. Unlike  an -ARAR,  a TBC  is not
rar.datory  and  need not be followed  in  developing  alternatives
v.-hich comply  with RCRA.   55  Fed.  Reg.  8745,  col.  3  (March 8,
1990).   Moreover,  unlike  ARARs,   the  underlying validity  of  a
TBC  is  at issue  in the remedy selection  process and  a  TBC can
only be used if it  is cost effective.  Id.
         Current  experience  with  composite caps  indicates the
difficulty of  their installation  and  the  loss  of  their effec-
tiveness  if  the  clay becomes wet,  thereby  undermining  the
original  rationale  of the   cap  guidance.   At least  equally
important,  as  demonstrated  below, a  composite cap  is  clearly
not  cost-effective when  compared  to a  noncomposite  cap.   When
                             - 57 -

-------
use of  a  TBC  would produce a result that is not cost-effectiv
it should not be used.
         The  proper  application of  this  principle is  illur-
trated  in the ROD for Sharkey  Landfill  in Morris  County,  New
Jersey.   At  the Sharkey  Landfill,  substantial  hazardous waste
disposal  led  to the  consideration of  RCRA Subtitle C closure
requirements  as ARARs.  Record  of Decision for Sharkey Landfill
at 35  (Sapt.  29,  1986).   However, the  ROD  pointed out  that the
remedy  would  not  meet the "compositional criteria  of  the RCRA
'model' cap."  Id..   Instead, the ROD considered the "-jnodel" to
be  "unwarranted  for  this  site," and  selected  a noncomposite
cap.  id.   The reason provided  was  that the  extra  layer would
not have  increased effectiveness  but:  would have  increased the
cost  significantly --  the  same situation 'that  obtains  here
Id.   at 8, .35.  Thus,  in  light  of  past practice at  other New
Jersey  sites,  it  is   apparent  that a  non-composite cap meets
Subtitle C requirements and  is well-suited to Global.

              4.   Summary
         In conclusion,  a  solid  waste  cap, or  its  equivalent,
should  be  selected in the  ROD.   Global Landfill was authorized
to  and  received   various  forms  of   solid  waste,  including
residential waste, bulky  waste,  and   non-hazardous  industrial
waste.   Until  its closure  in  1964,  Global  was  authorized,
consistent with RCRA  and  New Jersey law, to  receive  hazardous
waste from small  quantity generators —  a  situation applicable

                             - 58 -

-------
tu  most  municipal   landfills.   As  demonstrated  by  the  drum
investigation, far in excess  of  99% of the landfill's contents
is solid waste.
         Unquestionably,   solid  waste   is  representative  of
Global's  contents.   Moreover,  Global  is  an  extremely   large
i»-£fill (100  feet in height  and  57.5 acres in lateral extent)
wmrh  is characterized  by widely  dispersed  contamination  of
^-orally i0w  tuxicity.  The  solid  waste capping  requirements,
'=fher than the hazardous waste requirements, were designed  for
/•ecisely  these   situations   --_ large  volumes  of  essentially
solid waste  giving  rise to  widely  dispersed  and  low toxicity
contamination.  As stated by  the NCP, RCRA  hazardous waste caps
are not  appropriate  for  such  municipal landfills;  instead,  the
specifically  tailored  requirements  governing  solid  waste caps
±'—u:u form the basis of  the  selected  alternative.
         Even  if  hazardous waste  requirements are  chosen  for
the  Global   cap,  however,  those  requirements  can  be  easily
satisfied by  a noncomposite  cap.   The composite  cap  found  in
tne  Proposed  Plan's  preferred  alternative  is  based  on  a
guidance document, not a regulation.   It  should not  be used at
Global because experience  in  the  field has  not  confirmed  its
i: pis.T.entability  or  effectiveness   and   because   it   is   not
  . z-effective.   Moreover,  at  Sharkey  Landfill,  EPA reached
rr.'.s  same  conclusion  and  determined  that a  noncomposite  cap
fully  satisfies  RCRA's  hazardous  waste  capping  requirements.
                             ' 59 "         POOR QUALITY
                                              ORIGINAL

-------
It would  be  unjustified  and  unreasonable  to  allow a
posite cap at Sharkey Landfill  and not at Global.
V/7.      CROUP'S PROPOSED ALTERNATIVE
         A.   Description
         The  alternative  recommended  by  the PRP  group  would
begin by an  investigation to fill  identified  site-specific data
gaps.  The investigation would  include  the following:
              a field investigation of  sampling  the  soils, with
              in -situ -vane tests and CPT -tests  to confirm shear
              strength and  aging  effects, and  a field  test  to
              determine the refuse  strength  parameters,  through
              t-pcV analyses  of  an  excavated refuse fence;
              bench   scale   treatability  'tests  to   evalug
              proposed leachate treatability;
              ambient  air  monitoring   including  gas  migration
              studies and quarterly monitoring of landfill  gas
              constituents;
              settlement and  horizontal  surface monitoring  of
              the  existing  .landfill,   with   survey  points  and
              inclinometers,  and  a current  topography  from  an
              aerial survey with  ground control  to establish a
              base map; and
              regular monitoring of leachate  for flow  rate  and
            .  quality, using recognized protocols.
                             - 60 -

-------
         Based  on  the  existing  data  and  depending  on  the
outcome of further testing, the  Global  Landfill  PRP Group  ("the
Group") believer that the problems  identified with  the Proposed
Plan can be solved by  a  different  alternative.   The alternative
suggested by the Group ("Recommended Alternative*)  is  comprised
of the following: 1) a fence around the site; 2) a  noncomposite
cap with  installation  of a geonet  and without  geogrid  layers;
3; grading of  the  cap  to provide surface water  controls;  4)  an
active gas  extraction system;  and 5)  a  temporary storage  of
leachate  on-site  with  transportation  to  •n____p_ff-site  water
treatment plant. The  Recommended Alternative would  not  include
construction of a toe faerm.^'                              .     .
         The  Recommended Alternative   will  include  a  compre-
hensive monitoring scheme of settlement  markers  on  the existing
cover  on grids  ranging   from  500  to  100  feet,  depending  on
location.  This  will  enable landfill  movements  to  be  followed
      The Group's Alternative  is  based on provision of  a  cover
to meet the PRAP Remedial Action Objectives,  which are  to:
           prevent direct contact with exposed waste  materials
           or  leachate  surface  seeps  that  could  result  in
           exposure to substances of concern;
           prevent  airborne  transport  of  landfill  gases  or
           waste  particles  that  would  result in  exposure  to
           substances of concern; and
           develop  controls  and measures  for  stormwater  and
           soil  erosion management,  establishing a vegetative
           cover,  landfill   gas   and  leachate  surface   seep
           management,  correction of  slope  stability  problems
           and site security.
                             . 61 -

-------
as early  as  possible,  including the design  and bidding
The monitoring will indicate  if  there  are  signs of instability;
and  also  enable  landfill  behavior  to be  followed during  cap
construction.   In  the  unlikely event  that   the  landfill  is
unstable,  measures  such as  regrading  or  even  stabilization in
some form could be implemented.
         The proposed cap consists of  a top  layer of stabilized
vegetation.    Below  that mat  would  be  a  12  inch  layer  of
topsoil,  a  12   inch   layer   of common   borrow  soil,  and  a
geocomposite drain  (geonet  with non-woven geotextile  bonded to
both sides)  which will together provide frost  protection.   The
next lower  layer  would  consist  of  a  60  mil textured  VLDPE or
HDPE geomembrane.   The  landfill surface would  be regraded with
6 to 12 inches  of clean backfill.  The cover would no_i include
the two geogrid layers proposed in the PRAP alternative.
         The  cover would  be  graded  to   include  channels  for
surface   water    collection   so  that  water   velocities   are
controlled to prevent  erosion.   Surface water  would be led via
channels  to  sedimentation  ponds  before  discharge.    Surface
seeps of  leachate would  be collected  and  stored in tanks before
transportation and  treatment off-site.  An  active  landfill gas
ezi: rarh i r-»r>  *vsf«>m-  ^onctfhar  **i vh *•*»«*•* <-»m^»nt  from the  liner,
would  lead  to  inward gradients  to  collect  landfill gas,  which
would  be   flared  in   accordance with  applicable  air  quality
standards.
                             - 62 -

-------
         There  are  four  principal   differences   between   the
Recommended Alternative and the PRAP  alternative:  these  concern
the cap, the berm and leachate treatment.
         The  first  two  differences  between  the  Recommended
Alternative  and  that  presented  in  the  PRAP  address the  cap.
First, the Group's cover would delete  the  two  geogrid layers  in
the PRAP  alternative.   For  the reasons noted  previously,  those
layers  are  unnecessary, ineffective  as  designed,   and  decrease
the implementability of the  cap.   Second,  the Group  proposes  a
noncomposite cap.  The  proposed  noncomposite  cap  would  provide.
an  essentially  equivalent  barrier  to  infiltration.  Analyses
with the current version  of  EPA's  HELP software have been  made
of    the    Recommended   Alternative.^'      These    analyses
demonstrate that the Recommended Alternative  compares favorably
with  that  in  the  Proposed  Plan:  it  would  yield a  reduction
efficiency of  99.95  percent  as compared  with an  efficiency  of
99.97 percent  for  the  PRAP  alternative.   The noncomposite  cap
is   less    costly    than   the   composite   cap,   and   avoids
implementability problems  associated  with a composite cap.
         The   third    difference    between    the    Recommended
Alternative and that included the PRAP is  that the Group's  plan
would not  require  the construction of a  berm (in  part  because
the  Feasibility  Study  underestimated  the   strength   of   the
      See Appendix B.
                             - 63 -

-------
waste).   The Recommended Alternative  would provide  factors
safety  against  sliding that exceed those  in  the  Proposed Plan,
based  on  an evaluation of  refuse strengths that have  been  the
subject   of  back  analysis, ^-l'    The  Recommended  Alternative
also  includes  a  limited program of  investigation  that  would
confirm the  refuse and soil strength  parameters used and set up
points  to monitor landfill  movements,  at an estimated  cost  of
$120,000.    Monitoring would  be  an  integral  part   of  the
Recommended   Alternative;   such   monitoring   would   provide
sufficient  notice so  that   any  necessary  measures  to  enhance
slope stability can be performed  in a timely manner.
          Finally,  the Recommended   Alternative  provides  for
transportation  of  leachate  to an off-site  treatment plant.   As
noted previously, corstruction  of an  on-site plant would either
duplicate  or prejudice the  selection  of  a  treatment plant,
any,  for  groundwater  in OU#2.   Treatment at a larger  facility
off-site  would  also   solve  two  lurking  problems  in the  PRAP
alternative:  (1)  it  ensures  that  the  leachate is  brought to  a
facility  designed  to  effectively  treat  the leachate,  a result
that  is much less  certain at the on-site  plant in  light of  the
omission  of  treatability studies;  and  (2) the  inefficiencies
produced  by  the dramatic  reduction of leashats flows over time
would  be  effectively  addressed at a  larger off-site  facility
      gee Appendix A.
                             - 64 -

-------
*nere the capacity  is much less affected by the volume produced
try the Global Landfill  leachate.
         B.    Remeffy Selection Analyxit
              I.   Ajulyat oftiCP Criteria
         An  analysis  of the criteria set  forth  in  the NCP, see
" C.F.R. §  300.430(e)(9),  shows that the PRAP alternative does
-~t  reflect  the best balance  of  these  criteria.   Both the
	Bended  Alternative and the PRAP alternative  would protect
  ._,„   health.    Sfifi  Proposed  Plan   at  7.    However,   the
. ice—ended  Alternative  would  better  protect  the  .environment
•-ecr'jse  it  would not  include  the construction of  a  berm and
on-site  leachate  treatment  facility,  and thus would not destroy
the surrounding wetlands.
         Both   the    Recommended  Alternative   and   the   PRAP
riternative   would    comply    with   all   pertinent   closure
AP.AP.s.-^7     However,   the  PRAP   alternative,  which    would
construct  a  berm and  expresses  a   preference  for an  on-site
Jeschate  treatment   facility,  would  not  comply with  wetlands
AKARS.   while response  actions  under  the NCP may  be eligible
for a nationwide  permit,  £££  33  C.F.R.  $ 330.5(a)(20), they are
subject  to  certain  conditions.  Sfi£  33 C.F.R.  §  330.6(a).  In
KO. Licular,   "to  the  maximum  extent  practicable,"  "IdHscharges
-'-4/   The  Group's  proposed Alternative  meets  the New  Jersey
~-]id Waste  Regulations,  £.£.&.£. 7:26-2A.9  for  closure  with a
cover of a solid waste landfill.
                             - 65 -

-------
.   .  .  shall  be  avoided or minimized  through the use  of  other/
practical  alternatives*;  and  *[d]ischarges  in wetlands  areas
shall be  avoided.* 33 C.F.R,  §  330.6(a)(1),(5).   See Executive
Order 11990,  Sec.  2(a)  (new construction  located in wetlands is
permitted  only  if there is "no  practicable  alternative"  to the
construction).  &££  alsp 40 C.F.R. §  230.10(a).   Because there
exists a  practical alternative  that  fully protects human health
and the  environment  — the Recommended Alternetive • --  the PRAP
alternative  does  not satisfy  wetlands  ARARs.    See  Municipal
Guidance at 5-5,  fig. 5-3._ _             	 	
         The  Proposed  Plan does  not  suggest  that the  solid
waste  and  hazardous waste cap  alternatives  reviewed in  the
Feasibility Study are distinguishable based  on  the criteria of
"long-term effectiveness  and permanence."  Sfifi Proposed Plan at
8.   In  reality,  though,  the   PRAP   alternative  suffers  from)
several    deficiencies    which    will    undermine     long-term
effectiveness.    In   the   first  place,   there  are  significant
questions  about  the  short-term  effectiveness of a composite cap
in  light  of  the  problems associated with  moistening of  the
clay,  which  may  undermine stability.   Second,  the  PRAP  and
accompanying  materials  do  not  provide any  data  to demonstrate
the  reliability  >??  •*. n-^ri—»*rtv*«  «<*«:><»«>•! la  %?>un  from  recycled
plastic  beverage  bottles,  whereas the cap  in  the Recommended
Alternative  consists  of  a  thick HDPE   —  a demonstrated  and
reliable  technology.  The Recommended Alternative  also  offers
essentially equivalent  impermeability to that provided  by  the

                             - 66 -

-------
PRAP     alternative    but     without     these     significant
deficiencies. ^2-/   Thus,  the   Recommended   Alternative   offers
greater "long-term effectiveness.*                        -
         The  PRAP  alternative  is  presumed  "implementable"  but
this presumption is questionable.   First, the  PRAP alternative
cap creates  several  problems associated with the  combination of
clay and  synthetic  liner.   Measures must be  taken to  prevent
wetting of  the clay in order  to avoid stability  problems.   It
is difficult  to  reach satisfactory  compaction  and permeability
with   clay.   -As   .a  result, _ placement—of ...-clay  -increases.
construction   difficulty   and   time.     A   second   set   of
implementability problems  arises  due to  the  presence   of  the
geogrids.    As settlement  occurs,   the  gas  headers and  piping
will  need  repairs,  thus  necessitating  the  cutting   of  the
geogrids.    Attempting  to   repair  the  geogrids  will   be  a
difficult  and perhaps  ineffective  operation  because  it  will
require bodkin connectors  when  backfilling  trenches.   Finally,
in the  absence of  treatability  studies,  the  implementability of
a  leachate  treatment  plant  is  questionable.  The  Recommended
Alternative,  in  contrast,  does  not contain   these  components
with the  associated implementability concerns.   Consequently,
the  Recommended  Alternative  will  be considerably quicker  to
construct and more "implementable."
      See Appendix B.
                             - 67 -

-------
         •Reduction of  toxicity, mobility,  or volume" is not
relevant factor as far  as the choice of caps  is  concerned.
Proposed  Plan at  8.    To  the  .extent  that  it  is  .relevant  to
leachate or  groundwater,  in light  of  the uncertainty  produced
by  the  omission  of   treatability  studies,  the   Recommended
Alternative  proposal  of  off-site  treatment  offers  a  greater
likelihood  that  toxicity will  be  reduced.   Sec 40 C.F.R.   §
300.430(e)(9)(iii)(D)(2),  (3)  (factors include  the  -amount  of
hazardous substances.  .  .that  will  be treated,* and  "degree  of
expected reduction -in  toxicity").   In addition,  there  would  be
no  outfalls  into  the  wetlands,  and  thus  no  residuals  left
on-site.   &££  40  C.F.R.  §  300.430(e)(9)(iii)(D)(5)  (factors
include  -"the  type   and   quantity   of   residuals").    Thus,
"reduction  of toxicity"  is  more  nearly  achieved  by  off-site
treatment.
         "Short-term   effectiveness,"    which   addresses   the
effects  of  the  alternative  during  both  its  construction  and
implementation  phases,  would  be  somewhat  less  for  the  PRAP
alternative.  This  is  because  the  construction of  a berm  and
any leachate  treatment  would require measures  that  would result
in greater  impacts  on wetlands.  Moreover, the.construction  of
the  extra  clay  layer  in. the  composite  cap would  result  in

-------
greater  potential  disturbance to  the public due  to the  extra
truck traffic associated with the transport of the  clay.^4/
         The  capital  costs  would  be  greater  for  the   PRAP
alternative because that proposal  contemplates a composite cap,
an  unnecessary  berm,  unnecessary   geogrid   layers,   and  the
additional  costs  of mitigating  the  impacts  to  wetlands.   The
estimated  capital  cost  of  the  cap described in  the  Proposed
Plan is $19.9 million.  On the other  hand,  a  rough estimate for
the  capital  cost  of  the   Recommended  Alternative  is  $14.8
million, a  savings  of over  25%.   Moreover,  it.can  be  expected.
that  the   Recommended  Alternative   would  result   in   lower
operation  and  maintenance  expenses  because  repair  would  be
simpler  due  to  the  absence  of  geogrids  and  the  unnecessary
extra composite layer.
         As   the   preceding   discussion   demonstrates,    the
Recommended  Alternative offers  a  far  better  balance  of  the
relevant  criteria  than  the  PRAP   alternative..   Under   such
circumstances,  the  PRAP alternative should  not   be  selected
because  it   is   inconsistent   with  the  MCP.    40  C.F.R.   §
300.43.0(f)(I)(i)(B) (1990).
      See FS  at 3-10 -  3-11 (berms  under  review would  affect
from 2.4 to 3.8 acres of  wetlands and encroach on  £loodplains).
                             - 69 -

-------
              2.   Application oftht NCF F acton to Remedy Selection Analysis
         The NCP requires  that the  selected alternative protect
human  health  and  the  environment,  comply with ARARs,  offer
"permanent solutions" to the maximum  extent practicable, and be
cost-effective.   40  C.F.R.  §  300.430(£ )(i) , (ii)  (1990).   The
Recommended Alternative meets  all of  these  requirements.  It is
doubtful whether the PRAP  alternative satisfies the first three
requirements and it is clear that it violates the fourth.
         Each  alternative  would be  protective  of human health,
but   the   Recommended   Alternative   would    provide  greater
protection   of    the   environment.     S&£.   40    C.F.R.    §
300.430'f)(I)(ii)(A)..  The PRAP alternative,  which includes the
construction of  a berm,  would  violate1 wetlands  ARAR;^'  the
Recommended   Alternative   would   not.     See    40    C.F.R.
300.430(f ) (1)  (ii)(B).   With  regard  to  whether  an alternative
offers  "permanent  solutions,"  it is  uncertain  whether the PRAP
alternative's  use  of  the recycled plastic  liner  will offer the
equivalent  "permanence"   as   the   Group's   demonstrated  liner
technology.  &££ 40  C.F.R.  S  300.430(f ) (I)  (ii)(E).   Moreoever,
as described  above,  the Proposed  Plan's preferred alternative
doer  r.ct  off?"   *•**  h***»r   balsr-.-vs  »?   the  five  relevant
criteria, particularly long-term effectiveness.
      id. at 4-18
                             - 70 -

-------
         Finally  and  crucially,  the NCP's  requirement  that  the
remedy be  "cost-effective" would not  be met by the selection of
wiie  PRAP  alternative.   fi££ 40  C.F.R.  §  300.430(f )(l)(ii)(D).
In  order  to  determine  "cost-effectiveness,"  the  NCP  first
requires the  determination  of "overall  effectiveness"  --  which
.-eludes   (1)   long-term  effectiveness  and   permanence;   (2)
 -'.ction  of  toxicity, mobility,  or volume  through  treatment;
     .'3)  short-term  effectiveness.  Id.   As  noted  previously,
	   Recommended  Alternative   and   PRAP  alternative   offer
                                         ->.
equivalent performance-with regard  to -impermeability  but., _for.
.ther  reasons,  the PRAP  alternative provides  less  "short-term
effectiveness"  and "long-term  effectiveness."   Because it  is
uncertain  how successful  an on-site  leachate  treatment  plant
would  be  in   light  of the absence of  treatability studies,  it
ksouid  offer   less  "reduction of  toxicity"  than the  much  more
certain treatment  at  a facility with  the full  range  of treat-
~onf  methods.   On  balance,  therefore,  the  PRAP  alternative
offers less "overall effectiveness."
         The  next  step  in  the  NCP  requires  that  "overall
effectiveness" be compared to  "cost."  The  NCP states that  «
•Tprnedy shall  be cost-effective if  its costs  are proportional
tc  its  overall  effectiveness."   40  C.F.R.  §  300.430(f)(1)
,.:;(D).    As  EPA states  in the  preamble  to  the  final  NCP,
 r:oportional" is used to  show that  the  determination is  one
that "compare[s]  the  cost and effectiveness of  alternatives  in
relation to one another."  55 Fed.  Reg. 8728 (Mar. 8,  1990}.

                             - 71 -

-------
         In  this  situation,  no  "proportionality*  could  be s
to  exist.   The  capital  costs  associated  with  the  capping
portion of  the PRAP alternative  are  approximately $5.1  million
higher   than   the   Recommended   Alternative;   the   overall
effectiveness  of  the  PRAP alternative  is the  same  or  lower.
This  is  therefore  not  a  situation  where  the  more  costly
alternative  offers  a significantly more  effective remedy.  The
decision to  select  the more costly alternative  — with similar
or   less   overall   effectiveness  —   would   be,    therefore,
inconsistent with the NCP._. _  	  _,    	

VW. ROD FleabiKtj
         In  general,  any  alternative selected  in a  record of
decision (ROD)  should  be flexible and should  not  constrain the
ultimate  design of  a  cap  or  other  elements  of  the remedia
alternative.   If  NJDEP decides to proceed  based on the current
inadequate  information,  it  is even more  important to provide a
flexible ROD  in order  that the  remedy can  be  adapted as essen-
tial  data   gaps  are  filled.   The  general  requirement  of  ROD
flexibility  has been  made explicit by EPA  in  its  discussion of
the development of remedial alternatives:
                          :«••:•  -;"M."Ji.-J   2 2   i-Z-Cted,   if
         possible,  so*  saeh technology  type to  simplify
         the  subsequent  development   and  evaluation  of
         alternatives without  limiting  flexibility  during
         remedial   design.    The   representative   process
         provides   a   basis  for   developing  performance
         specifications    during    preliminary    design;
         however,  the specified  process actually used  to
         implement  the  remedial action  at a site may not
         be selected until remedial design.
                             - 72 -

-------
Guidance for Conducting  Remedial  Investigations  and Feasibility
Studies under CERCLA  (Interim  Final),  4-16 (October 1988).   The
ROD selects an  alternative which  has  been developed pursuant to
this process.   The  ROD sets  forth the  conceptual  remedy,  which
is  provided  to  inform  the  public about  the basic  elements  of
the remedy  and to  establish  relative cost estimates  among  the
possible  remedial  alternatives.   The  actual  remedial  design
takes  place  after  the  adoption of the ROD.  See 40 C.F.R.  §
300.435.  The  performance  of  the ultimate design  must meet  the
performance objectives  set  forth "in the  POD," such  as "remedial
action  objectives  and   ARARs.it/    &&£  40  C.F.R.    §  300.435
(b)(l),  (2)  (1990).  However,  so  long as these  objectives  are
met, the  ultimate  c3e?iar. nay  ce?s>rt  frorr, the  remedy described
in  the ROD with  no further  action  required unless  the  remedy
design  "differs  significantly"  from  the ROD  with  respect  to
scope,  performance, or cost.   Sfifi 40 C.F.R. § 300.435(c)(2)
         In some respects,  the  Proposed   Plan  already reflects
this   understanding  of  the   relationship  between   the   ROD
alternative and the Remedial  Design  stage.   Thus,  the Proposed
Plan proposes  an "active gas  collection  and treatment  system"
as  its preferred alternative,  leaving  to the design  stage  the
details  of   how   this  component   will  be constructed   and
      For  the  first  operable  unit,  most  of  the  ARARs  will
consist of action-specific ARARs.
                             - 73 -

-------
operated.   Sfifi Proposed  Plan at  9.   In  addition,  though  t^f
Proposed Plan  expresses a  preference for *on-site treatment" as
the  preferred  leachate  treatment  alternative,  it  appears  to
preserve  needed  flexibility:  "The  final  option  for  leachate
collection and  treatment,  however, would be selected during the
design of this operable unit."  Id. at 6.^'
         This  flexibility  should be  extended to the design of
the  cap  and  the  determination  of  the  necessity of  the berm.
with respect to the type  of  cap  implemented at Global Landfill,
the  ROD  could  select _a. general  type  of .cap or  one. achieving
"equivalent  performance."   With  respect to  the berm,  the ROD
could  select   monitoring  and   an  engineering  evaluation  to
de-rnstrate slope stability  during  the post-closure  period.  In
the  event  the  required  slope  stability  is  not  achieved,  the
installation of a berm to  achieve the required stability may
made at  that  time.   That decision  would  not  be  prejudiced by
the  implementation of the other components of OUK1.
         This  approach was   used at  the  Sharkey  Landfill  in
Morris County,  New Jersey, described in the ROD for  the site as
a  "hazardous  waste  site."   Record  of Decision   for  Sharkey
—-i--'   in  *>viu* v *t*-«9f  fctn-i  «• »-*j» «*».»'«*«  * £.&ti  $> 4. ^> v <* tie 5  the following:
"However,  a contingency  system,  which  would  include  off-site
disposal,  may  be  used  during   this  phase  of  the  remedial
action.  This would provide  sufficient  time to evaluate whether
a  single  treatment  plant could be designed  and  constructed to
address    both    the    landfill   leachate    and   underlying
groundwater."  Proposed Plan at 9.
                             - 74 -

-------
Landfill,  at  35  (Sept.  29,  1986).   Although  the  Sharkey  ROD
concluded  that  RCRA  Subtitle  C closure requirements were  to be
utilized  at  the site,  the  cap  selected  did  'not  meet  the
compositional criteria of the RCRA  'model' cap," because  it  did
not  include  a  synthetic liner.   Id.  Instead,  the  preferred
alternative was a noncomposite cap  which met "the  performance
requirements  of the relevant RCRA regulations.*  16.   Because
of  the  site  characteristics  of   Global  Landfill   discussed
previously,   the  ROD  should  be  similarly   written  to  allow
flexible   remedial  and  cap "design   so  long   as   performance
criteria are  met.   In  fact, given the circumstances  at  Global,
it  would  be  unreasonable   for  the Global ROD  not  to have  at
least  as  much  flexibility  with  regard  to  cap design  as  the
Sharkey ROD.
IX.       MISCELLANEOUS
         A.   AAARi
         The  Feasibility Study was   designed  for  a  specific
purpose  --   the  analysis   of  alternatives   that   address  the
en-site  source   control  of  contamination at  Global  Landfill.
However,  the Feasibility   Study  also  purports  to  identify  a
universe  of  ARARs  in  order  to  assist  the  determination  of
remedial objectives at the  site.   &££ Feasibility Study  at 2-1;
App. F.   That  limited use  should  not be confused with  whether
OU#1  must  comply  with  these  contaminant-specific,   ambient
standards  as  ARARs.   OUfll,  as  a  phased  remedy  addressing only
source  control,  is  only  governed  by certain  action-specific

                             - 75 -

-------
           and  not  contaminant-specific  ARARs.   See  55  F
Reg. 8755, col. 3 (March 8, 1990).
         Indeed, the  Feasibility  Study recognites that none of
the  caps  under  consideration would produce compliance with the
chemical-specific   groundwater   or   surface   water   standards
identified  in Appendix  F  of  the  Feasibility  Study.   id-  at
4-18.   Nor  is  there  any  present  method of  comparison of  air
ambient quality  in  relation to the gas management  options that
were  analyzed.   Id-  at  4-6.  Similarly,  none  of the  leachate
options   under   consideration    would    necessarily   produce
compliance  with  chemical-specific  ARARs  or  groundwater  and
surface water.  Id. at 4-38.
         The  reason  is  straightforward:  ambient standards  are
not  relevant  at  this  stage  for   air,   surface   water,  and
groundwater because  the  Proposed  Plan  only covers  OU#1.   Ev^
were  they  arguably relevant,  they would  be  the subject  of  a
waiver under  CERCLA  § 121(d)(4)(A),  because OU#1 is  "only part
of  a  total   remedial  action that  will  attain  such level  or
standard  of   control  when   completed.*  The Proposed Plan  also
treats  the  standards identified in Appendix   F  as  not  yet
relevant  beyond  assisting  in   the   formulation  of  remedial
                                saSsr.   iss .  the   Proposed-  Plan
      These  action-specific   ARARs  will   be  different   for
distinct remedial alternatives.  As EPA has  stated,  "ARARs  will
differ  depending  upon the  specific actions  and objectives  of
each alternative being considered.  .  .  ."53 Fed.  Reg.  51438,
col. 3 (Dec.  21 1988).
                             - 76 -

-------
identifies  only  ope  ARAR  as  potentially  relevant:  closure
requirements.  Proposed Plan at 8.
         Nonetheless,  though  the universe  of ARAT^s  identified
in  Appendix   F  does  not   apply   to  OU*1,32/   the  general
formulation in  Appendix  F of what  constitutes an ARAR  at this
 •te  is  noteworthy.   First,   the  Proposed  Plan  apparently
<•-r-j~.es  that  permits  would  be  required  for  any  proposed
•---••Tent plant.  Proposed Plan  a 6'("effluent.  .  .  .would meet
.-.-i^nrg requirements  for  discharge to surface  water").   This is
.-correct.  Section  121(e) of  CERCLA  states  that permits_ ^re_
~ct required for "the  portion of any removal or remedial action
conducted entirely  onsite."  fififi also  H.J.A.-C  7:14A-3. l(b) (3)
(exception  to  NPDE5  permit  requirements for  CERCLA  and  Spill
Act  activities).    The   proposed  treatment  plant   would  be
•cr.site."  Proposed Plan at 6.
         Second, the  justification  for  what constitutes  an ARAR
is  not  in  accordance  with law.  The Feasibility  Study states
*"•''   Further support  for  the proposition that  the  state ARARs
identified in  the Feasibility  Study  were identified  solely to
assist in  determining  remedial objectives can be found  in the
feet that  there  was  no effort  to  specifically explain why each
standard was either  "applicable" or  "relevant and appropriate."
_.,.  has   stated   that  "(i)t  is  not  sufficient  to  provide  a
Mu,.c;;5l  'laundry'  list  for statutes and  regulations  that might
jje ARARs  for  a particular site.   The  state  .  .  .  must instead
 ...ide  a  list of requirements with specific  citations  to the
•ration  of law  identified as  a  potential  ARAR,  and a  brief
°*-ianation  of  why  that  requirement   is   considered  to  be
applicable or  relevant and  appropriate to.  lh£ fiitfi." 55 Fed.
F.eg. 8746 col. 2  (Mar.  8,  1990) (emphasis added).
                             - 77 -

-------
 that  "[fjor purposes of  this FS, ARARs  constitute Federal antf
 State  promulgated  regulations,  standards  and  criteria  whose
 legality  is not overridden by any clause of  [CERCLA or SARA]."
 Feasibility Study at 2-2.  This  is  a misreading of CERCLA, and
 reverses  the proper  burden for  determining  ARARs.  The entire
 point  of  the   ARARs  process  —  i.ft.,  to determine  whether  a
 requirement is  "applicable" or "relevant and appropriate* — is
 that   CERCLA  alone  determines  those  requiiements  that  are
 subsequently applied to  cleanups on a  case-by-case basis.  As
-noted -in the preamble  -to  the J4CP,  -."the  position that, on-site
 CERCLA  response actions are  not  independently subject to other
 federal  or  state  environmental   laws  is  a  longstanding  one,
 based  on a  theory  of  implied repeal or  preemption."   55 Fed.
 Reg.  £742,  col.  1  (March  8,  1990).  '  In  short, without  a
 requirement-by-requirement  determination as mandated by CERCLA
 no  standard has  an  independent  application  to a  cleanup under
 CERCLA.    The   result  of   this  misconception   is  that  the
 Feasibility Study  assumes  the  application  of,  and  includes,
 standards wholesale without the type of ARARs  analysis required.
         One example should  suffice to make  this point clear.
 The MCLs  are not ARARs,  for  either OU*1 o_r  OU«2.  MCLs may be
 "relevir-w  sni   ;??^;jrists- sr.Iy  f=r =i»s=r,d  and surface water
 that  is  a  current  or potential  source  of  drinking water."  55
 Fed.  Reg.  8750,  col.  2   (Mar.   8,  1990).   However,  the  upper
 water  table aquifer  is not  a potable water  source.   Proposed
 Plan  at  4.  It  therefore  could  not  serve   as  a current  or

                              - 78 -

-------
potential  source of drinking  water.  And  the Old  Bridge  Sand
aquifer  beneath  Global Landfill  is  downgradient; one mile  from
the nearest  drinking water well.  Id.  It,  therefore,  does  not
serve as  a  current  drinking water source.  Nor  can  it  serve as
a  potential  drinking  water  source  inasmuch  as  there  is  no
significant  likelihood of  development or the  installation of  a
drinking  water   intake downgradient   from  the site  due to  the
proximity  of the  surrounding  wetlands   and  Cheeseguake  State
Park.   See id., at 2."
         B.   Excavation and Removal of Drums
         The   Proposed    Plan   states   that    "also    under
consideration is  the possible  removal  of  the drums  during  the
exploratory drum  investigation  in  the 6.5  acre tract  of  land."
Proposed  Plan  at  3.   The number  of drums  discovered in  that
investigation was  63,  and these were  randomly  intermixed  with
the  surrounding  solid waste.   From the face  of the  Proposed
Plan,  it  appears  that  the contemplated  removal is  limited  to
these 63 drums and does not extend to a  search for and ultimate
removal  of any  other  drums  or the  landfill's  contents.   The
Feasibility  Study   considered  an  alternative   of   full-scale
excavation  and  off-site  disposal  for  the 6.5  acre  tract  and
properly  rejected  this   option during  screening  due  to  the
increased  risks  to  the  workers  and the  public, the lack  of
                             - 79 -

-------
available  disposal   capacity,      and  the  prohibitive   cos
Feasibility  Study   at   2-22,   2-23.    The  rejection   of   this'
alternative  is  consistent  with  the  NCP  and  EPA's  governing
principles  because  the  few,  random  drums  are  clearly  not  a
principal  threat at  this  site and  because the  alternative  is
completely  impracticable for  an  area  as  extensive  as the  6.5
acre tract.  55  Fed.  Reg. 8703, col.  1 (March 8,  1990); 53 Fed,
Reg.  51427,   col.   2 (Dec.  21,  1998); Municipal  Guidance  at
4-12.  Thus,  any drum removal  at  this site must be  limited  to
the already excavatedjJrums.	      _  _ 	   _	

X.       CONCLUSION
         The  foregoing  discussion  amply demonstrates  that  the
preferred  alternative  suggested  by   NJDEP  in  the  PRAP  is
result  of  inadequate  data  and  overconservative  assumptions
which  are  not  warranted by the site  or the evidence.  On  the
other  hand,  the proposal  advanced by the Global Landfill  PRP
Group  is   in  complete  keeping with   the  site  conditions,  the
regulatory requirements,  and the potential  risks posed by  the
site.  Importantly,  the proposal suggested  by  the PRPs is  one
which  compares  favorably  with   remedial  alternatives   being
implemented  at  other Rsv;  Jsrssy  landfills,   and  accepted by
NJDEP as appropriate  at those other sites.
      The  lack  of  available disposal  capacity  renders  this
alternative unimplementable.
                             - 80 -

-------