**-.'
United States
Environmental Protection
Agency
                          Off ice of ~
                          Emergency and
                          Remedial Response
EPA/ROD/R02-91/162
September 1991
&EPA   Superfund
           Record of Decision
           NL  Industries, NJ

-------
50272-101
REPORT DOCUMENTATION i. REPORT NO. s-
PAGE EPA/ROD/R02-91/162
4. TM**nd8ubM*
SUPERFUND RECORD OF DECISION
NL Industries, NJ
First Remedial Action
7. Autx*.)
9* HirtOnMRQ QTQMnBMMfl NMW MO A0QM09

U.S. Environmental Protection Agency
401 M Street, S.W.
Washington, D.C. 20460
XBK*hnr.*«^)nN(,
5. Report (M*
09/27/91
8.
•» RirfoffnilnQ QTQMMXRwofl HtpL No.
10. Pro|ecVTMk/WorklMtNo.
11. Con«imet :«2p«t-ErNM Twins                            *
   c. COSATI Held/Group
18. AveiUbiity Statement
18. Security CUM (TN* Report)
None
20. Security Ctau (Thto P»ge)
None
21. NaefPcgm
140
22. Price
(SMANSU39.18)
                                    See Instruction* en flc
OPTIONAL FORM 272 (4-77)
(Formerly KT1S-35)
Dopvtnwnt of Comnwrcc

-------
EPA/ROD/R02-91/162
NL Industries, NJ
First Remedial Action

Abstract (Continued)

over 40,000 pounds of toxic and reactive materials; incinerating 2,200 empty drums
offsite; and constructing a chain-link fence to enclose the site.  In addition, EPA
conducted a Focused Feasibility Study (FFS) to address the remediation of slag and lead
oxide piles, debris and contaminated building surfaces, standing water, and sediment.
The FFS resulted in the issuance of this Early Remedial Action Record of Decision
(ROD), designated as Operable Unit (OU2).  The nature and extent of remaining
contamination on the site and areas adjacent to the site in various environmental
media, such as soil, sediment, ground water, surface water, and air,  are currently
being evaluated and will be addressed as OU1 in a subsequent ROD.  The primary
contaminants of concern affecting the slag and lead oxide piles, sediment, debris, and
standing surface water are metals including arsenic, chromium, and lead.

The selected remedial action for this site includes treating onsite the slag and lead
oxide piles using solidification/stabilization and placing the residual material
onsite; decontaminating debris and contaminated building surfaces, with offsite
treatment and disposal of debris that cannot be decontaminated; treating and disposing
of standing water, wash water from the decontamination process, and sediment offsite;
conducting environmental monitoring;  and implementing institutional controls including
land use restrictions.  The estimated present worth cost for this remedial action is
$4,987,000, which includes an annual O&M cost of $17,000.

PERFORMANCE STANDARDS OR GOALS:  The selected remedy will attain all Federal and State
ARARs.  Chemical-specific clean-up goals were not provided.

-------
                          ROD FACT SHEET
SITE
Name:
Location/State:
EPA Region:
HRS Score  (date):
NPL Rank (date):

ROD
                    NL Industries, Inc.
                    Pedricktown, Salem County, New Jersey
                    II
                    52.96 (March 1991)
                    145 (March 1991)
                    September 27, 1991
Date Signed:
Selected Remedy
The selected remedy for the second operable unit includes the
following components:
     o    Solidification/stabilization and on-site placement of
          the slag and lead oxide piles;
          Capital Cost:                                $2,014,000
          Annual O&M Costs:                               $17,000
          Present Worth Cost:                          $2,303,100
     o    Decontamination and off-site treatment and disposal of
          debris and contaminated surfaces;
          Capital Cost:                                $1,691,100
          Annual O&M Costs:                                    $0
          Present Worth Cost:                          $1,691,100
     o    Off-site treatment and disposal of standing water and
          sediments; and
          Capital Cost:                                  $993,200
          Annual O&M Costs:                                    $0
          Present Worth Cost:                            $993,200
     o    Appropriate environmental monitoring to ensure the
          effectiveness of the remedy.
TOTAL
          Capital Cost:
          O&M:
          Present Worth:
                              $
                              $
                              $
4,698,300
   17,000
4,987,000
LEAD
Enforcement, EPA
EPA Project Manager  (phone):
NJDEPE Case Manager  (phone):
                              Michael H. Gilbert (212-264-6418)
                              Paul Harvey (609-633-1455)
WASTE

Type:
Media:
Origin:
                    Metals contamination, particularly lead
                    Soil, wetlands, groundwater, surface water,
                    standing water, sediments, and dust covered
                    surfaces.
                    Pollution originated as a result of secondary
                    smelting of lead bearing materials and poor
                    management and handling of these materials.

-------
                      DECLARATION STATEMENT


                        RECORD OF DECISION

                       HL INDUSTRIES, INC.
SITE NAME AND LOCATION

NL Industries, Inc.
Pedricktovn, Salem County, New Jersey

STATEMENT OF BASIS AND PURPOSE

This decision document presents the selected remedial action for
the NL Industries, Inc. site, which was chosen in accordance with
the requirements of the Comprehensive Environmental Response,
Compensation and Liability Act of 1980, as amended by the
Superfund Amendments and Reauthorization Act of 1986, and to the
extent practicable, the National Oil and Hazardous Substances
Pollution Contingency Plan.  This decision document summarizes
the factual and legal bases for selecting the remedy for the
site.  The attached index identifies the items that comprise the
administrative record for the site, upon which this decision is
based.

The New Jersey Department of Environmental Protection and Energy
concurs with the selected remedy.

ASSESSMENT OP THE SITE

Actual or threatened releases of hazardous substances from the
site, if not addressed by implementing the response action
selected in this Record of Decision, may present an imminent and
substantial endangerment to public health, welfare or the
environment.

DESCRIPTION Or THE SELECTED REMEDY

The remedial alternative described in this document represents
the second operable unit for the NL Industries, Inc. site.  It
will address slag and lead oxide piles, debris and contaminated
surfaces, and standing water and sediments.  A comprehensive
study is underway to determine the full nature and extent of
contamination on the site and areas adjacent to the site in
various environmental media such as air, soils, groundwater,
surface water and stream sediments.  Remedial actions to address
these other contaminant sources will be the subject of a
subsequent Record of Decision for the site.

-------
The selected remedy for the second"operable unit includes the
following components:

     o    Solidification/stabilization and on-site placement of
          the slag and lead oxide piles;

     o    Decontamination and off-site treatment and disposal of
          debris and contaminated surfaces;

     o    Off-site treatment and disposal of standing water and
          sediments; and

     o    Appropriate environmental monitoring to ensure the
          effectiveness of the remedy.


STATUTORY DETERMINATIONS

The selected remedy is protective of. human health and the
environment, complies with Federal and State requirements that
are legally applicable or relevant and appropriate to the
remedial action, and is cost-effective.

This remedy utilizes permanent solutions and alternative
treatment or resource recovery technologies to the maximum extent
practicable, and it satisfies the statutory preference for
remedies that employ treatment that reduce toxicity, mobility, or
volume as their principal element.  The remedy, when completed,
will achieve the applicable or relevant and appropriate
requirements for the site.

Because the selected remedy will not allow for unrestricted use
of the site and, further, will result in hazardous substances
remaining on the site, a review will be conducted within five
years after commencement of the remedial action to ensure that it
will continue to provide adequate protection of human health and
the environment.
Constant ine Sidamon-Eristoff   /            Dat^e
Regional Administrator

-------
Sep 2V,9i it.: 24  N.J. DEFT.  OF WASTE
                                      State of New Jersey
                        Department of Environmental Protection *nti Energy
                                    Office of the Commissioner
                                           CN 402
                                     Trencon, NJ 08625-0402
                                      Tel. * 609-292-2885
Scort A v.einer                           FAX # 609-984-3967.
     ssioner

                                                 October 2,  19*1

      Mr. Conscantlne Sldsaor-Eriecoff
      Regional Administrator
      USEPA Region II
      26 Federal Plata
      New York, NV 10278

      Dear Mr. Sidsoon-Eiristoff:

      Re:  Record of Decision, r.L.  Industries, Pedrickcowr.
           Sales County* K*v  Jersey

           This  la  to  formally notify  the  United States  Environmental Protection
      Afccnr.y  that tha New Jersey Department  of Environmental Protection and  Energy
      hae evaluated  the a€l«et*J  plan  fox the  Interim rdtcedlal action AC  the  N.L.
      Industrie^ Supsrfund  Site and concurs with  the  reaedy as stated  In  the final
      Record Of Decision.

           This  Record  of  Decision Is  for the  contaminated slag  piles,  building
      surfaces  and  debris,  and standing  surface water.   It is  understood  that  a
      slte-virie  Pl/FS  is  being conducted to  deal  with all  contamination related
      to the Bite.

           The eo&ponent? of  the Record of Decision include:

           »    Solidification/Stabilisation of the elag and on-site disposal;
           *    p«cor,r.amlnatlon  «ud  off-site disposal  for surfaces and  debris;
           «    Off-site  trestaent and  disposal for the standing water.

           New  Jersey  fully  appreciates the Importance of the  Record of  Decision
      in  the  cleanup process and will Continue  to tfike  all  reasonable steps  to
      ensure  that the Stale's cOKIitwenta  in this area are net.
                                               Sincerely,
                                               jcott A.
                                               Conmiaaloner
      SAVi:PH/kJ
                                 .'9>v/c/ie/ .'k Jit Ufuti Opportunity tinpluycr

-------
                         DECISION SUMMARY

                     NL INDUSTRIES,  INC.  SITE
              FBDRICKTOWN, SALEM COUNTY, NEW JERSEY


SITE NAME. LOCATION AND DESCRIPTION


The NL Industries, Inc.  (NL) site is an abandoned, secondary lead
smelting  facility situated on 44 acres  of land  on  Penns Grove-
Pedricktown Road,  in  Pedricktown, Salem  County,  New  Jersey.   The
site  is  bisected  by  a railroad  and  includes a  closed 5.6-acre
landfill.  The  southern  28 acres contain the  industrial area and
landfill  access road  (Figure  1).  NL  maintains the landfill area
and operates the  landfill's leachate collection system.

The site overlies the Cape  May aquifer.  The West and East Streams,
which are intermittent tributaries  to the Delaware River, border
and receive surface discharges from  the site.  The nearest home is
less than 1000 feet from the site and B.F. Goodrich and the Tomah
Division  of Exxon, inactive facilities, are neighboring industrial
facilities.

Demography and Land Use

The  1980  U.S> .Census reported the total- population  of. Oldmans
Township,  in which Pedricktown is located, at 1,847.

The site  is part  of an area that is  zoned for development as an
industrial park.   This area includes  operations  of the following
major  corporations:  Airco  (inactive .facility);  B.F.  Goodrich
(inactive  facility);   Browning-Ferris   Industries   (inactive
facility); and Exxon, Tomah Division  (inactive facility).  To the
north of  the  industrial  area, between the site  and  the Delaware
River, is a military base and an Army Corps  of  Engineers Dredge
Spoil area.  The industrial park area  is bordered  by a combination
of open,  residential  and agricultural lands.   The residences are
one-  or   two-story,  single-  family homes.   Agricultural  lands
produce a variety of crops, including tomatoes, corn, soybean and
asparagus.

Hydrogeologio Characteristics

The  local aquifer system  can be separated  into  three aquifers
(unconfined, first confined and  second confined)  on  the basis of
groundwater elevations and lithology  around the  site.   The site
geology consists  of  thick and interfingering strata  of clay and
sand.  The clay members function as  aquitards  in some sections.
The discontinuity of the Upper Clay member provides the potential
for the unconfined aquifer  to leak into the first confined aquifer.
The observed  thickness of the Middle Clay Member appears  to be

-------
greater  than  20 feet,  and  its  reported  presence on  adjacent
industrial properties  suggests  that this aquitard extends across
the site.

Groundwater  flow in  the  unconfined  aquifer is predominantly in a
northwest direction,  however, discontinuous layers of  sands and
clays cause localized variations in flow direction. Groundwater in
the first confined aquifer appears to flow in a westerly direction.
Groundwater flow in the second confined aquifer appears to be in a
easterly direction.   This suggests that the industrial supply wells
neighboring  the  site may  be  controlling the   second  confined
groundwater flow under the site.

Climate

The climate of the site is largely continental, chiefly as a result
of the predominance  of winds  from the interior of North America.
Climatologic data for Salem County are collected by the New Jersey
Department of Agriculture.    The  1987 Annual Report states that
Salem County  receives an average  of 42.81 inches  of rainfall per
year.  The  region experiences an average temperature of 55.2° F,
with a monthly average  low of  33°  F occurring in January  and a
monthly average high of 77° F occurring in July.  The wind rose for
Philadelphia, PA airport indicates that more than 50 percent of the
wind over three miles/hour is  from the  west  (north northwest to
south southwest).

Soil

The soils under the  NL site are characterized by a thin  (1 to 2
inches) layer of top soil containing little plant material over a
tannish-brown sandy soil.  In  adjacent wooded areas, a thick humus
layer is overlaying the soil.  This humus layer is  generally six to
eight inches thick.   The soil under the humus layer is tannish to
reddish brown.  Soils on adjacent agricultural  lands have twelve to
fourteen inches of rich,  blackish-brown topsoil with an underlying
tannish-brown, sandy soil.

Drainage and Surface Water

An unnamed tributary to the Delaware River is  located  along the
western  property boundary, henceforth referred  to  as the West
Stream in this document.   A second stream, referred to as the East
Stream, runs  approximately  1000 feet  east of  and  parallel to the
site's eastern  property  boundary.    Both streams merge  north of
Route 130 and ultimately discharge to the Delaware River, which is
approximately 1.5 miles from the site.

-------
BITE HISTORY AMD ENFORCEMENT ACTIVITIES

Sit* History

In 1972, the  facility began the operation of recycling lead from
spent automotive batteries.  The batteries were drained of sulfuric
acid, crushed, and  then  put through the lead recovery process at
the on-site smelting facility.   Plastic  and rubber waste materials
were buried in an on-site landfill.

Between 1973 and 1980, the New Jersey Department of Environmental
Protection  (NJDEP)   cited  NL  with  46  violations  of State  air
regulations and issued several notices and memoranda with respect
to unregulated  discharges of  contaminated water from ths site.
Water pollution violations were directed toward the battery storage
area, the on-site landfill, and the septic system.  NJDEP conducted
an  air-monitoring  program  in  1980  that  identified  airborne
quantities of lead,  cadmium, antimony, and ferrous sulfate produced
by  the  smelting process,  at  levels  exceeding  the facility's
operating permits.

When NL operated the facility,  emissions from the plant discolored
or stained  aluminum siding of homes  and automobiles, and etched
concrete.  High concentrations of lead, iron,  cadmium,  and antimony
were detected in airborne dust samples collected by NJDEP in 1980
when the plant was operational.

NL ceased  smelting  operations  in May 1982.   In October  1982, NL
entered into an Administrative  Consent  Order (AGO)  with NJDEP to
conduct a  remedial  program to address  contamination  of  the site
soils,  paved  areas,   surface   water  runoff,   landfill,   and
groundwater.  In  December 1982, the site was placed on  the National
Priorities List (NPL).

In February 1983, the plant  was  sold to National  Smelting of New
Jersey  (NSNJ) and smelting  operations recommenced.   NSNJ entered
into an amended AGO with National Smelting and Refining Company,
Inc., (NSR), NSNJ's parent company, NL and NJDEP,  which clarified
environmental  responsibilities  of  NSNJ and  NL.     NSNJ  ceased
operation in January 1984,  and  filed for bankruptcy in March 1984.
In June 1984, NL voluntarily entered the site to pump and dispose
of leachate from the  landfill.

In 1986, NL  signed  a consent order  with EPA,  whereby NL assumed
responsibility for  conducting  a  site-wide Remedial Investigation
	5 Feasibility Study (RI/FS) with EPA oversight.  Versions of the
 *  Report  were  submitted to EPA  &n April and  October  1990,  and
April 1991.  EPA amended the report and approved it in July 1991.

As discussed  in more detail . in the  following section of  this
document, EPA began a Removal Action at the site in March 1989 to
address site conditions which presented an imminent and substantial

-------
risk or threat  to public health and the environment.   Due to the
magnitude and complexity of the surface contamination at the site
and the constraints on EPA's regional removal program budget> EPA
decided to  address the  most imminent  or  threatening conditions
under  the Removal program, and to  conduct  a Focused Feasibility
Study  (FFS)  to  address the remaining components.   The FFS which
provides the technical  information  which supports this Record of
Decision, identified  and evaluated remedial  alternatives  for an
Early  Remedial  Action which will continue the site-stabilization
and remediation efforts initiated under the Removal Action.

Removal Action Activities

EPA conducted a multi-phased Removal Action  at the site to address
several conditions that presented serious risk to public health and
the environment.   EPA conducted Phase I of the  Removal Action in
March  and April 1989, which consisted of construction of a chain-
link .fence  to  enclose the former smelting  plant  and spraying or
encapsulation of  the on-site slag  piles.    Encapsulation  of the
piles provided temporary protection  from wind and rain erosion and
contaminant migration.

In July and August 1989,  EPA sampled private potable wells located
along U.S.  Route 130,  just  north of the site, with the closest well
being  approximately 1000 feet from the landfill. The samples were
analyzed for pH and heavy  metals contaminants and indicated that
the water was within applicable drinking water standards.

As part of the-RI  Phase I Sampling Program,  an inventory of raw and
waste materials was conducted at the site. The inventory indicated
that  various hazardous  chemicals,  notably  red  phosphorus  and
metallic sodium, were  stored in a locked  concrete building adjacent
to the plant warehouse.

In November 1989, EPA began Phase II of the Removal Action.  This
phase  consisted of additional  encapsulation of the  slag  piles,
securing the entrances of the contaminated buildings, and removal
of over 40,000  pounds of the most  toxic and reactive materials.
The bulk of  these  materials was recycled  and the remainder was sent
for disposal to a permitted landfill.   These materials included
arsenic, metallic sodium, red phosphorus and waste oil.

Chain-link  fence  gates were  installed  at  all  entrances  of the
contaminated buildings to deter trespassing.  Moreover, the leaky
roof of the lead  oxide storage building was repaired to prevent
rainwater from entering the building.

Berms  composed of sand  and  straw were  installed  around  the
perimeters of the  four slag piles to aid  in containing the slag and
to filter participates in order to prevent their entry into surface
runoff.  In addition,  the slag piles were  treated  with a second
coating of the previously used encapsulant to help reduce further

-------
slag migration.  In April 1990, the concrete retaining walls around
the slag piles were reenforced to prevent collapse and release of
slag to the environment.

During February and March 1991, the slag piles, lead oxide pile and
surface water at the site's former smelting facility were sampled
as  part of  the Focused Feasibility Study  (FFS)  effort.   This
additional information was to be used to help  evaluate appropriate
remedial measures  for treatment or disposal of these contaminated
media.

During  March  1991,  EPA  performed  Phase III  of  its  removal
activities at  the site.   During this phase,  the  damages  to the
perimeter  fence  were  repaired  and  a  new  entrance  gate  was
installed.

Approximately 2200 empty, rusted and deteriorated 55-gallon steel
drums  were  removed  from  the  site  for  incineration and  steel
recycling.

All on-site  containers,  stored  in the open, containing materials
threatening release were emptied of their contents and piled under
the existing covered area at the rear of the facility.  Berms of a
sand/gravel mix  were  installed  at the base of the piles.   These
measures were taken to reduce the discharge of these  substances as
leachate or particulates.
 .'T  •  ..-...,•   .  •       •" •'   "•••'••..,-'•.••   ;  ;• •    .  • ;     •
Forty-four 55-gallon  open  head drums  containing copper  wire and
cable were removed from the facility and  have been shipped to an
EPA warehouse in Edison, New Jersey.  This material  and other items
of value have been the  main target of trespassers  into the site.
It was EPA's aim that this action would reduce or eliminate site
break-ins, and  subsequent  exposure  of individuals  to  hazardous
materials.

Current Conditions

The site is presently inactive.   NL  maintains the landfill area
and its leachate collection system.   The landfill operator and the
New Jersey State Police continue to monitor  the site.   EPA has
posted signs indicating  that the site is hazardous and entry to the
property  is  restricted.    Figure 2  shows the  location of  the
remaining  on-site contaminant   sources  and  debris.   Table  1,
provides an estimated quantitative inventory of these materials.


Enforcement Activities

Initial enforcement  investigations  identified  the  previous  and
current  site owners  and  operators  as  Potentially Responsible
Parties (PRPs)  for the site.  These were NL, NSNJ, NSR and Standard
Metals Corp.  Under an  AGO,  NL  is currently performing the site-

-------
vide RI/FS (referred to as the first operable unit or OU-1).  EPA's
records  indicate that  NSNJ and  NSR  are bankrupt,  and standard
Metals Corp. reformed after bankruptcy.

EPA has recently identified additional PRPs, primarily generators,
to whom General Notice Letters, along with a demand for past costs,
were  sent  pursuant  to  Section  107  (a)   of the  Comprehensive
Environmental Response, Compensation,  and Liability Act of 1980, as
amended  (CERCLA).  These  PRPs are believed to have sent hazardous
substances including, but not limited to, lead to  the site.

HIGHLIGHTS OP COMMUNITY PARTICIPATION

The Proposed Plan, FFS and other information related  to the second
operable unit  (OU-2)  remedy (addressing the  slag and  lead oxide
piles, debris  and contaminated surfaces, and standing water and
sediments) were released  to the public  on  July  17,  1991.  These
documents were  made available to the public in the Administrative
Record file at  the following locations:

Penns Grove Public Library
South Broad Street
Penns Grove, NJ 08069

Pedricktown Municipal Building
Box 98 Mill Street   .
Pedricktown, NJ 08067

U.S. Environmental Protection Agency
Emergency & Remedial Response Division
Division File Room, 29th  Floor
26 Federal Plaza
New York, NY 10278

The notice of availability  of these document  was published in The
Gloster County Times and Today's Sunbeam on  July 17, 1991.  A public comment
period was held from July 17 to  September 6, 1991.  In addition, a
public meeting  was  held  on August  6,  1991.   At this meeting,
representatives from  EPA  presented  and answered questions on the
results of the  site-wide  RI, the results of the FFS  for OU-2, and
EPA's preferred remedy for OU-2.

Responses to all comments  pertaining to remedy selection which were
received by EPA in  writing  during the public comments period are
included in the Responsiveness Summary, which is an  attachment to
this document.    The  Responsiveness  Summary  also includes EPA's
responses to  questions and concerns regarding  remedy selection
which were stated during  the August 6 public meeting.

-------
SCOPE AKD ROLE OF OPERABLE UNIT WITHIN BITE STRATEGY

Due to the size and complexity of the site, EPA is addressing its
remediation in phases, or operable units.  This Record of Decision
addresses the  remediation of several areas  of  hazardous surface
contamination which EPA has designated as Operable Unit Two (OU-2).
These areas, which  include slag  and lead oxide  piles,  debris and
contaminated  surfaces,   and  contaminated  standing  water  and
sediments, were found to be  significant and continual  sources of
contaminant migration from the site.

In 1989,  EPA  began a Removal Action at  the  site which addressed
conditions that presented an  imminent risk and/or threat to public
health  and  the  environment.    Recognizing  the  magnitude  of
activities that qualified for action under its removal authority,
EPA  prioritized its  efforts  to  address the  most serious  and
threatening conditions first.  EPA conducted a FFS to address the
slag and  lead oxide piles, debris and  contaminated surfaces, and
contaminated standing water  and sediments on an  expedited basis
that would be consistent with  the long-term remedy for the site.
The FFS identified and evaluated remedial alternatives for an Early
Remedial  Action which would continue the site-stabilization and
remediation efforts which were initiated under the Removal Action
activities.

The  Early  Remedial  Action  will  prevent   further  releases  of
contaminants from areas of hazardous surface  contamination and can
be implemented while  the site-wide RI/FS proceeds.

Removal Action Activities

EPA conducted a multi-phased  Removal Action at the site to address
several conditions that presented a risk to public health and the
environment.  The Removal Action activities are described  in detail
under the Site History and Enforcement Activities section of this
document.

Operable Unit One

A site-wide RI/FS, which EPA has designated as  Operable Unit One
(OU-1), is  currently  being  performed  for NL by O'Brien  &  Gere
Engineers, Inc.   This RI is  a  comprehensive  study designed to
determine the nature  and extent  of contamination  on the site and
areas adjacent to the site in various environmental media such as
air,  soils, groundwater, surface water and stream sediments.   The
FS will  identify and evaluate  remedial action alternatives to
address contaminated  media sources and  eliminate  potential long-
term health and environmental risks.

-------
Operable Unit Two

The basis for expediting response actions  at the site is supported
by the criteria for performing a Removal Action.

Section  300.415 of  the  National Oil  and Hazardous  Substances
Contingency Plan (NCP) describes the following factors to be used
in determining whether a Removal Action is appropriate.

    [i]   Actual or potential exposure to hazardous substances or
          pollutants or contaminants by nearby human populations,
          animals, or the food chain

   [ii]   Actual  or potential  contamination  of  drinking  water
          supplies or sensitive ecosystems

  [iii]   Hazardous substances  or pollutants  or  contaminants in
          drums, barrels, tanks, or other bulk storage containers
          that may pose a threat of release

   [iv]   High  levels  of hazardous  substances or  pollutants or
          contaminants in soils  largely at or near  the surface that
          may migrate

    [v]   Weather conditions that may cause hazardous substances or
          pollutants or contaminants to migrate or be released

   [vi]   Threat of fire or explosion

  [vii]   Other appropriate  Federal or State response mechanisms to
          respond to the release are not available

 [viii]   Other situations  or factors  that  may  pose  threats to
          public health or welfare or the environment


An assessment of the conditions  at the NL  site with respect to the
criteria described in Section 300.415 of  the NCP  and above yield
the following conclusions:

   •  The presence  of  bulked  storage piles containing hazardous
     substances satisfies criteria (i)  and (iii).

   •  The presence of contaminated standing water on surfaces and in
     basements that may migrate  off  site  satisfies  criteria  (i),
     (ii) and (iv).

   •  The  presence  of  dust  contaminated  surfaces  and  debris
     satisfies criteria (i)  and (v).

   •  The presence of  a  lead oxide pile and slag  piles satisfies
     criteria (i),  (iv)  and (v).

                                8

-------
    • The presence of lead on the paved surfaces satisfies criteria
     (iv) and  (v).

In  addition, the need  for a Removal Action is a direct result of
the unique  circumstances  associated with thefts and vandalism at
the site, which satisfies criterion  (viii).

The response actions taken pursuant to this Record of Decision are
consistent  with Section  104  of CERCLA,  as  amended.    The Early
Remedial Action will continue the site-stabilization effort begun
under the Removal Action activities and will be consistent with the
long-term site-wide remedial action.


SUMMARY OP BITE CHARACTERISTICS

Sources of Contamination

The NL Industries site was used during the approximate period from
1972 through 1984  for  the production of lead from used batteries
and other lead-bearing materials.  As a result, the site contains
many  potential  sources  of  chemical   contamination.    Numerous
mechanisms for chemical migration, and many exposure pathways for
both human and ecological receptors exist.

The three  areas of hazardous  surface  contamination at the site
which were  identified  by EPA during previous investigations and
addressed within  this operable  unit include, the  slag and lead
oxide piles, debris and contaminated surfaces, and standing water
and sediments.

Four separate piles contain an estimated volume of 9800 cubic yards
of kiln slag from the smelting process,  which are a source of heavy
metal and  metal oxides  contamination.    Approximately  200 cubic
yards of lead oxide and similar materials, which are also sources
of lead and dust emissions, are stored in enclosed areas.

Drums and debris  were scattered throughout the  site,  within and
outside of buildings and on the paved areas. Some of this material
is  lead  feed  stock with high  lead content.   As part  of EPA's
Removal Action activities, much  of the  reactive materials were
removed from the site, and  contaminated debris and drums of lead-
bearing material, located throughout the site and buildings, were
consolidated into piles in semi-protected areas of the site.  Wipe
samples indicated that equipment surfaces and  the process building
•'^ or and walls were contaminated.  Elevated levels of inorganics
c -Si as  lead,  cadmium  and nickel* were  detected.   Lead-bearing
materials are also present on contaminated surfaces throughout the
facility,  specifically  in  piping,  piles,   conveyer  and  dust
collection systems, and the process and ventilation equipment.

-------
The buildings on the site contain many physical and environmental
hazards, including water filled basements, areas filled with ponded
water, hidden pits, and sumps containing contaminated liquids and
sludges.   Contaminated water was estimated  at approximately one
million gallons.   Approximately  200  cubic yards of sediment were
estimated to have  accumulated in the standing water.   Drains are
blocked and contaminated liquid continues to accumulate and run off
from the ponded areas.

Concentrations  of  contaminants  of  concern,  which  were detected
during  sampling of  the slag and lead  oxide piles, debris and
contaminated surfaces and standing water, are listed in Tables 2,
3 and 4.

In addition to the numerous contamination sources described above,
the  contaminants  are  believed  to have  migrated into  the  soil,
groundwater, surface waters and sediments, and air,  since the plant
began  operation in 1972.   Sampling of  these media  has  been
undertaken by NL in connection with the site-wide RI/FS and was not
addressed in the FFS.
SUMMARY OP BITE RISKS / NATURE AND EXTENT OP THE PROBLEM

EPA  conducted  a  qualitative  Risk  Assessment to  evaluate  the
potential risks to human health and the environment associated with
the NL site in its current state.  The Risk Assessment focused on
CECRLA hazardous  substances in  the slag  and lead oxide piles,
standing water and dust which are likely to pose significant risk
to human health and the environment.

Toxicity Information

High concentrations of lead, cadmium, nickel and other inorganics
have been detected on site  in  the slag,  standing  water and dust.
Lead is considered a probable human carcinogen and exposure to lead
is also associated with  human  noncarcinogenic effects, including
alterations in the hematopoietic and nervous system.   Currently,
however,  there are no EPA-verified toxicity values  available for
lead and hence, the risks associated with lead exposure cannot be
quantitated in a risk assessment.  EPA thus relies solely on risk
management, rather than risk assessment, to base decisions  on lead.


Exposure  to   cadmium   and  nickel  has   been associated  with
noncarcinogenic effects via ingest ion.  Cadmium is a probable human
carcinogen by  inhalation based on evidence from human and animal
studies.   Nickel dust has an A classification and is carcinogenic
by inhalation.
                                10

-------
Contamination Exposure Pathways

An  exposure pathway consists of  the following elements:   (1)  a
source and mechanism of chemical release to the environment;  (2) an
environmental transport  medium for  the  released  chemical  (e.g.,
air, surface runoff); (3) a point of potential human contact with
the contaminated medium  (referred to as an exposure point); and (4)
a  route  of exposure at the  exposure  point  (e.g.,  ingestion,
inhalation or dermal contact).

The  plant-area  sources  of  contamination  have  previously been
identified as airborne contamination and surface runoff resulting
from the slag piles,  other hazardous waste areas and standing water
at  the  site.   With these contaminant  sources (i.e.,  slag piles,
standing  water  and dust),  there  are  many  potential  exposure
scenarios.   The following paragraphs  address release mechanism,
transport mechanism, potentially exposed populations and exposure
routes relative  to  each  of  the potential exposure media, namely,
slag and lead oxide piles, debris and contaminated  surfaces, and
contaminated standing water.   Only  the current land-use exposure
pathways were evaluated.

Slag Piles and Lead Oxide Piles

Four slag piles totaling approximately  9800 cubic  yards are stored
on site in open deteriorating bins,  and on paved ground surfaces.
Consequently, the  potential for  the creation of dust  via wind
erosion  is  high.   In addition,  approximately 200 yards of lead
oxide and similar materials are stored in enclosed areas.  The slag
materials were sprayed with an encapsulant as a temporary measure
to  mitigate releases of hazardous  constituents  and  contaminant
migration that would occur from wind and rain erosion.

High concentrations  of metals were  detected in the slag and lead
oxide piles.   Concentrations  of  lead detected were  as  high as
130,000 parts per million (ppm)  and 480,000  ppm  in the slag and
lead oxide piles, respectively.  These concentrations exceeded the
lead  cleanup range  of   500  to 1000 ppm  specified under  OSWER
Directive 19355.4-02.   In addition, the Toxicity Characteristic
reachability Procedure (TCLP) results presented in Table 5 indicate
that  the  majority  of  piles  tested  are  hazardous  based  on
leachability of lead and/or cadmium.

Based on the level of contamination detected in the slag and lead
oxide piles,  a  qualitative  risk assessment indicates  that the
potential  for  inhalation  of  contaminated  dust is  considered
significant for on-site workers and nearby receptors.   Runoff via
rain erosion is a mechanism for potential release of contaminants
into the environment.  In addition,  exposure to contaminants via
accidental ingestion, inhalation or  through dermal  contact is of
potential concern for site workers and trespassers on the site.


                               11

-------
Debris and Contaminated Surfaces

The process  building walls,  ceiling,  floors, structural members,
piping, and  equipment are covered with dust.  The results of wipe
tests taken by EPA's Technical Assistance Team  (TAT) contractor in
Table  2  indicate high  concentrations  of  lead,  iron,  cadmium,
nickel, and copper throughout the building.   Concentrations of lead
ranged  from  0.88  to  552   micrograms/kg/quarter  square  meter.
Approximately 2500 cubic yards of contaminated debris consisting of
lead dross and  contaminated  wooden pallets, baghouse bags,  scrap
metal and other materials are present throughout the site.  Much of
these materials were consolidated in temporarily protected areas,
as part of the most recent removal activity.

Releases  of  contaminants  to  air may occur  from the  migration of
dust  due  to  wind  or  activities  at  the  site.    The  metal
concentrations  in the dust are significant  and may pose a health
risk, if inhaled by on-site workers or  individuals downwind of the
site.  The potential  also exists  for site  workers or trespassers
and  animals  to be exposed  to  contaminated dust  through  dermal
contact or ingestion,  although the potential risk from this pathway
is  expected  to  be much  lower when compared  to  the  inhalation
pathway.

Standing Water

It is suspected that the drains are blocked  in areas where standing
water is ponded.   It was estimated that approximately one million
gallons   of   contaminated   standing   water  (i.e.,   accumulated
rainwater) is  present at the site.   Samples   of  standing  water
collected by EPA's TAT  contractor  in November  1989 (Table 2)  and
March 1991  (Table 4),  were  found to have high concentrations of
lead  and  other  metals.    Lead and cadmium concentrations  were
detected  as  high  as  5500  parts per billion (ppb) and  560  ppb,
respectively.   The contamination  is  due,  in  part, to  airborne
particulates, and rainwater  runoff from the slag  and  lead oxide
piles and other waste materials.   In addition, approximately 200
cubic  yards  of contaminated  sediments  were  estimated to  have
accumulated  in the standing water.

Given site conditions, accidental ingestion,  inhalation and dermal
contact are potentially the most likely on-site exposure pathways.
The potential  receptors would  likely be  site workers  and  area
trespassers.

Off-site  contaminant  migration  is  potentially  a  significant
exposure  pathway  from the NL site.   During heavy  rainfall,  the
standing water  eventually overflows the site in the area  of the
West Stream.  Concentrations  of lead in the stream were measured as
high as 206 ppb in surface water samples and 26,800 ppm in stream
sediment samples  taken  in  1990.  The  lead  concentrations  in the


                                12

-------
stream exceed  the  EPA recommended surface water criterion of 1.3
ppb  for protection of aquatic life due to chronic toxicity.

Conclusion

In summary,  the Risk Assessment determined that  current on- and
off-site exposures to CERCLA hazardous substances, including lead,
present in the slag and lead oxide piles,  contaminated surfaces and
debris, and  standing water and  sediments pose sufficient risk to
human health and the environment to warrant the response actions
chosen in this Record of Decision.
DESCRIPTION OP REMEDIAL ALTERNATIVES

The feasibility study process involves,  as a first step, selecting
technologies that are appropriate for addressing the public health
and environmental concerns associated with a particular site.

In  the case  of  the  NL  site, the  remedial  objectives  focus on
preventing future release and migration  of hazardous materials and
eliminating  the  areas  addressed in  OU-2 as  sources  of future
contamination and exposure on and off site.  The remedial measures
evaluated were designed to  alleviate the potential public health
risks  and  environmental  impacts  associated  with  three  areas
addressed in the  FFS,  namely,  the slag and lead  oxide piles, debris
and contaminated surfaces, and standing water and sediments present
at the NL site.

The alternatives that are presented in this document are those that
passed the  initial screening as  presented in the  Evaluation of
Alternatives  section  of the  FFS  Report.  Further  evaluation of
these alternatives is presented in the next section.

CERCLA,  as  amended,  requires each  selected  site  remedy to be
protective of human health and the environment,  cost-effective, and
in accordance with statutory requirements. Permanent solutions to
hazardous waste contamination problems are to be achieved wherever
possible while treating wastes on site, and applying alternative or
innovative technologies are preferred.

The FFS presents remedial alternatives  to address three areas of
hazardous surface contamination at the site:   slag and lead oxide
piles, debris  and  contaminated surfaces,  and  standing water and
sediments.  A wide range of  technologies was considered to address
the  remedial  objectives   for   each of  these   areas.    These
technologies  were  screened  on the  basis   of  effectiveness,
implementability and  cost.   Those that  were not  eliminated from
consideration during  screening  were assembled into  the remedial
alternatives presented below.  The term "Months  to Achieve Remedial
Action Objectives" refers to  the  amount of time  it would take to
design, construct and complete the action, but does not include the

                                13

-------
time that  may be involved for negotiations between EPA and PRPs,
for private-party funding or implementation of the  work.   "N/A"
denotes that the "Months to Achieve Remedial Action Objectives" is
not applicable for the alternative.


fllacr and Lead Oxide Piles

Alternative 8P-1: Ho Action

Capital Cost:                                                  $0
Annual O&M Costs:                                         $25,000
Present Worth Cost:                                      $439,000

Months to  Achieve Remedial Action Objectives:                 N/A

Superfund  regulations require  that  a  No Action  alternative be
evaluated  at  every site to establish a baseline  for comparison.
The No Action alternative for the slag and lead oxide piles would
include annual sampling and analysis of groundwater, surface waters
and soils  on  and around the  site .to  monitor the  migration of
contaminants,  in addition,  assessments would be performed every
five years to determine the need for further actions.

Alternative 8P-3: off-Site Flame Reactor

Capital Cost:                                          $4,215,100
Annual O&M Costs:                                              $0
Present Worth Cost:                                    $4,215,100

Months to  Achieve Remedial Action Objectives:            Eighteen

This alternative would include removing and treating the slag and
lead oxide off site in a flame reactor.   This innovative technology
would involve  subjecting  the wastes  to  very hot gas which reacts
rapidly to produce a nonhazardous slag and a  recyclable metal-
enriched oxide.  The volume of material .would be reduced 10 to 20
percent.   The slag could possibly be recycled as fill material or
road aggregate and the metal-enriched oxide could be recycled by a
secondary smelting facility, although at this time,  no markets have
been identified for these materials.

Alternative 8P-4:  On-Sit« Hydro-Metallurgical Leaching/on-Site
                   Disposal

 ^pital Cost:                                          $2,980,400
'. nual O&M Costs:                •                         $17,000
Lresent Worth Cost:                                    $3,269,500

Months to Achieve Remedial Action Objectives:             Sixteen
                                14

-------
This  alternative  would treat  the existing  waste  by a  hydro-
netallurgical leaching process on site.  Bench-scale testing would
be  required to define  design criteria.   The process, which is
widely used in  the metallurgical industry, selectively dissolves
lead and other  heavy  metals  present in  the waste materials.   The
leaching step would be followed by filtration, residue collection,
and precipitation.   The precipitate is a lead-rich, potentially
marketable  product.    The  caustic  leaching solution would be
recycled through the process.  The resulting treated material would
require testing according to the TCLP to confirm that the material
is nonhazardous.  There  would be no significant reduction in volume
of the material.  The  treated material would be redeposited on site
in accordance with Resource  Conservation  and Recovery Act (RCRA)
treatment standards.  For conservative cost-estimating purposes, it
was assumed that  on-site  placement would meet RCRA  Subtitle D
landfill requirements.  Any material from  which contaminants would
leach above acceptable  RCRA regulatory levels,  as determined by
TCLP testing, would be disposed of off site at an appropriate RCRA-
permitted  facility.  However,  it  is  expected  that all  of  the
material would meet RCRA regulatory levels after treatment.

Alternative 8P-5z On-Site Solidification/Stabilisation/
                  On-site Disposal

Capital Cost:                                          $2,014,000
Annual O&M Costs:                                         $17,000
Present Worth Cost:     -_ . ...   :.                .      $2,303,100

Months to Achieve Remedial Action Objectives:             Fifteen

This alternative , would . stabilize  the  existing  waste  on  site by
using  a  mobile  treatment  system.   This  technology immobilizes
contaminants by binding  them into an insoluble matrix.  Stabilizing
agents such as  cement, pozzolan,  silicates and/or proprietary
polymers would be mixed with the feed material.   The equipment is
similar to that used  for cement mixing and handling.  Bench-scale
tests  would  be  required  to  select  the  proper  quantity  of
stabilizing agents, feed material, and water.  It is possible that
contaminated  standing  water  may  be utilized  in this  process.
Depending on the specific treatment process, the stabilized volume
may increase up  to  40 percent  of the  original  volume.   The
stabilized material would require testing  according to the TCLP to
confirm that the material is nonhazardous.   Disposal of the treated
material would  occur on site  in accordance  with  RCRA treatment
standards.   For  conservative  cost-estimating  purposes,   it  was
assumed that on-site placement would meet  RCRA Subtitle D landfill
requirements.   Any material  from  which contaminants would leach
above acceptable  RCRA  regulatory  levels, as determined  by  TCLP
testing,  would  be disposed of  off site  at an  appropriate RCRA-
permitted  facility.  However,  it  is  expected  that all  of  the
material would meet RCRA regulatory levels after treatment.


                                15

-------
Debris and Cont^*" i pfted Surfaces

Alternative CS-J.: Ho Action

Capital Cost.                                             $17,700
Annual O&M Costs:                                          $6,800
Present Worth Cost:                                      $136,000

Months to Achieve Remedial Action Objectives:                 N/A

The  No  Action alternative  for contaminated  surfaces  and debris
provides  a  baseline  against  which  other  alternatives may  be
compared.   Contaminated debris, equipment and  surfaces would be
left  in  their current condition.  Roofs  would  be repaired where
necessary and a long-term maintenance program would be implemented
to ensure  that the buildings  are not accessible.   In addition,
assessments would be  performed every five years to determine the
need  for further actions.

Alternative C8-2: Debris and Contaminated Surfaces
                  Decontamination/Off-Site Treatment and Disposal

Capital Cost:                                          $1,691,100
Annual O&M Costs:                                              $0
Present Worth Cost:                                    $1,691,100

Months to Achieve Remedial, Action Objectives:    •>...-......      Twelve

This  alternative  would involve  decontaminating the contaminated
building surfaces, debris  (i.e.,  scrap metal, pallets, etc.) and
equipment using dusting, vacuuming and wiping procedures. Parts of
the  buildings  and  surfaces  which  could withstand high  water
prassure would  be  cleaned by hydroblasting.  Materials would be
recycled where possible.  Debris that could not  be decontaminated,
such  as  contaminated  baghouse  bags,  along  with  collected dust,
would be  transported to an appropriate off-site, RCRA-permitted
facility.  Contaminated wash water would be  treated with the on-
site standing water.

Standing Water and Sediments

Alternative 8W-1: Mo Action

Capital Cost:                                                  $0
Annual O&M:                                               $10,700
Present Worth Cost:                                      $220,100

Months to Achieve Remedial Action Objectives:                 N/A

The No Action alternative for  standing water provides a baseline
against which other alternatives may be compared. This alternative
would rely on natural attenuation of contaminated standing (rain)

                                16

-------
 water without any  treatment.    Drains would remain  plugged and
 contaminated.    Contaminated  standing water  would be  likely to
 continue to  overflow  the site  into the  West  Stream.    This
 alternative would include annual monitoring of groundwater, surface
'waters  and soils  in and around  the  site to  track contaminant
 migration.  In addition, assessments would be performed  every five
 years to determine  the  need for further actions.


 Alternative 8W-2: On-Site Treatment  and Groundvater Recharge

 Capital  Cost:                                           $1,335,000
 Annual O&M  Costs:                                              $0
 Present  Worth Cost:                                     $1,335,000

 Months to Achieve Remedial Action  Objectives:            Fourteen

 This  alternative   would  consist  of  collecting  and treating
 approximately one million gallons of standing water on site.  Wash
 water, which was generated from the decontamination of  contaminated
 surfaces and debris, would also  be treated with the standing water.
 The  treatment   process  would    consist   of   precipitation,
 clarification,  filtration and,  if necessary, ion exchange or ion
 replacement.    The  treated  water  would  be  recharged to the
 groundwater via injection wells or infiltration basins.   Sediments
 and sludges generated during the treatment process would  be treated
 and disposed of at ah appropriate off-site, RCRA-permitted facility
 capable  of  accepting these materials.  The treatment  system  would
 be designed to  reduce  metal  concentrations  to meet  Federal and
 State discharge standards.  Treatability studies would be required
 to define the .design and operating criteria to meet  the required
 standards for groundwater recharge.  As part  of this  alternative,
 drains would be unplugged and cleaned, which in conjunction with
 the decontamination  of buildings and paved surfaces, would prevent
 contaminated runoff from leaving the site  in  the future.

 Alternative 8W-3: Off-Site Treatment and Disposal

 Capital  Cost:                                            $993,200
 Annual O&M  Costs:                                              $0
 Present  Worth Cost:                                      $993,200

 Months to Achieve Remedial Action  Objectives:                 Six

 This  alternative would  consist of  collecting  approximately one
 million  gallons of standing water  in approximately 200  tanker
 trucks and transporting it to an off-site,  RCRA-permitted treatment
 facility, which would be  capable  of accepting  the water with no
 pretreatment at the site.  Wash water,  which would be  generated
 from the decontamination of contaminated surfaces and debris,  would
 also  be  transported with the  standing water.  Sediments would be
 transported to  an  appropriate  off-site,  RCRA-permitted facility

                                17

-------
that would be capable of accepting this material.  Samples of the
contaminated water  and  sediments would be sent  to  the treatment
facilities  to  ensure  waste  acceptance.     As part  of  this
alternative,  drains would  be unplugged  and  cleaned, which  in
conjunction  with  the  decontamination of  buildings  and  paved
surfaces, would prevent contaminated runoff from leaving the site
in the future.
SUMMARY OP COMPARATIVE ANALYSIS OF ALTERNATIVES

In accordance with the NCP, a  detailed  analysis  of each remedial
alternative was conducted with respect to each of nine evaluation
criteria.  This section discusses and compares the performance of
the  remedial  alternatives  under  consideration  against  these
criteria.  The nine criteria are described below, and all selected
alternatives must  at least attain  the  Threshold Criteria.   The
selected alternative should provide the best trade-offs among the
Primary Balancing Criteria.  The Modifying Criteria were evaluated
following the public comment period.

     Threshold criteria

     o    Overall Protection of Human Health and the Environment;
          This criterion addresses whether or not  a remedy provides
          adequate protection and describes how risks posed through
          each  pathway are  eliminated,  reduced  or  controlled
          through treatment, engineering controls or institutional
          controls.

     o    Compliance with  ARARs;  This criterion addresses whether
          or not  a  remedy  will meet  all of  the applicable  or
          relevant and appropriate requirements (ARARs) of Federal
          and  State  environmental  statutes  (other than  CERCLA)
          and/or provide grounds for invoking a waiver.  There are
          several  types  of  ARARs:    action-specific,  chemical-
          specific, and location-specific.   Action-specific ARARs
          are  technology  or   activity-specific  requirements  or
          limitations related to various activities.  Chemical- or
          contaminant-specific ARARs are usually, numerical values
          which establish the amount or concentration of a chemical
          that may be found  in,  or discharged  to,  the  ambient
          environment.     Location-specific  requirements   are
          restrictions placed  on the concentrations  of hazardous
          substances  or the conduct  of  activities  solely because
          they occur in  a special  location.   Summaries  of  the
          contaminant-specific,  action-specific   and   location-
          specific ARARs  are   presented  in Tables 6,  7,  and  8,
          respectively.  In addition, Table  9  contains numerical
          values  for  contaminant-specific  ARARs  relevant  for
          groundwater and  surface water discharges.
                               18

-------
     Primary Balancing criteria

     o    Long-term Effectiveness and Permanence;  This criterion
          refr.rs to the magnitude of residual risk and the ability
          of a remedy to  maintain reliable protection  of human
          health and the environment over time, once cleanup goals
          have been met.

     o    Reduction  of  Toxicity.  Mobility  or  Vfl"^?  Through
          Treatment;  This criterion addresses the degree to which
          a  remedy utilizes  treatment  to  reduce the  toxicity,
          mobility or volume of contaminants at the site.

     o    Short-term Effectiveness;  This criterion refers to the
          time in which the remedy achieves protection, as well as
          the remedy's potential to create adverse impacts on human
          health and  the environment that may result  during the
          construction and implementation period.

     o    Implementability;  Implementability is the technical and
          administrative feasibility of a remedy,  including the
          availability  of  materials   and  services  needed  to
          implement the selected alternative.

     o    Cost;     Cost  includes  capital  and   operation  and
          maintenance (0 & M)  costs.  Cost comparisons are made on
       '   the basis of the present worth value of the entire cost
          of the alternative.

     Modifying Criteria

     o    State  Acceptance;    This criterion indicates  whether,
          based on its review of the FFS, the Proposed Plan and the
          Record of Decision, the State concurs with, opposes, or
          has  no comment  on  the preferred  alternative.    This
          criterion is satisfied since the State concurs with the
          preferred alternative.

     o    Community  Acceptance;    This  criterion  addresses  the
          public's general response to the alternatives described
          in the Proposed  Plan  and  the FFS  report.    Comments
          received  during  the public comment  period and  EPA's
          responses  to  these  comments  are  addressed  in  the
          Responsiveness Summary attached to this document.


The comparison of remedial alternatives using the nine evaluation
criteria  for each  area of hazardous  surface  contamination  is
presented below.
                                19

-------
Comarison of   *<  ffd Lead Oxide Piles  (BP) Remedial Alternatives
This subsection compares the relative performance of each slag and
lead  oxide  remedial  alternative  using the  specific evaluation
criteria listed above.  A summary  of this comparative analysis is
presented in Table 10.

Overall Protection of  u     ealth and the Environment
Alternative  SP-1,  the No  Action alternative,  does not  meet the
remedial objectives; thus it is not protective of human health and
the environment.  Surface water and groundwater and soils would be
further contaminated due to migration of contaminants from slag and
lead oxide piles.  Alternative SP-3 would meet remedial objectives
by removing  the  hazardous  slag and lead oxide materials from the
site.  Alternative SP-4 would meet remedial objectives by leaching
contaminants from the slag and lead oxide piles.  Alternative SP-5
would  meet remedial objectives  by binding contamination  into a
insoluble  matrix.    Alternatives SP-4 and  SP-5  would place the
treated  material  on  site  in  accordance  with  RCRA  treatment
standards.   For conservative cost-estimating  purposes,  it was
assumed  that the  on-site  placement would  meet  RCRA Subtitle D
requirements, although  the actual disposal  requirements would be
defined  during   the  design  phase  of  the   project,   pending
treatability studies.  Long-term monitoring would be required for
Alternatives SP-4 and SP-5.

Compliance with  ARARs    .         .....                    .

Occupational Safety and Health  Administration  (OSHA)  Standards,
RCRA Land Disposal Restrictions (LDR) , RCRA Subtitle D Nonhazardous
Waste  Management Standards and RCRA  Identification of  Hazardous
Waste, which defines the  TCLP  to characterize a waste  as being
hazardous,  are  ARARS  which apply to,  and would be  met  by,
Alternatives SP-3,  SP-4 and SP-5.   Department  of Transportation
(DOT) Rules for Hazardous Materials Transport and RCRA Requirements
for Transporting Waste for  Off-Site Disposal would apply and be met
by Alternative SP-3.  Alternative SP-5 would comply with  40 CFR
264, Subpart X, which provides standards that are applicable to the
on-site  solidification/stabilization of contaminated  waste.   A
complete listing of ARARs for the site is contained in Tables 6, 7,
8, and 9.

Alternative  SP-1 would  fail to  comply  with  all the  associated
contaminant-specific   ARARs  but   would    comply  with   the
action-specific ARARs.

*  .1  removal  and/or  treatment technologies proposed  for  use  in
Alternatives SP-3, SP-4 and SP-5  would be designed and implemented
to   satisfy   all   contaminant-specific,  location-specific   and
action-specific  ARARs.    Alternatives SP-3,  SP-4  and  SP-5  are
designed to render treated  materials nonhazardous according to the

                                20

-------
 TCLP.   Some uncertainty exists  for Alternative SP-4 to meet all
 contaminant-specific  ARARs  due  to  the  presence   of  multiple
 contaminants.

• Long-Verm Effectiveness and Permanence

 Alternative  SP-1  would  only  monitor  the  migration  of  the
 contaminants  and does  not  provide  removal  and/ or treatment.
 Therefore,  it is not effective for  the  long-term protection  of
 human  health and the environment.                             •

 Alternatives SP-3,  SP-4 and SP-5 would  mitigate  the hazards  by
 total  removal  and/or treatment and disposal of slag and lead oxide
 materials.

 Some uncertainty exists with respect to  the effectiveness and
 implement ability of  Alternative SP-4, since it has not been applied
 to  similar CERCLA   waste  material.   Although  some long-term
 uncertainties regarding the integrity of  the stabilized mass have
 been raised,  Alternative  SP-5  is highly  effective in treating
 inorganic contamination and will inhibit leaching of  contaminants.

 Alternatives SP-4 and SP-5 would place treated materials on site  in
 accordance  with  RCRA treatment standards.   For  cost-estimating
 purposes, it was assumed that the on-site placement would meet RCRA
 Subtitle D  requirements, although the actual disposal requirements
 would  be defined in design,  pending treat ability studies.  Although
 treated material may be considered nonhazardous, it  would require
 long-term monitoring.   Alternative  SP-3 would be  considered  a
 permanent remedy and would  not require long-term monitoring.

 Reduction of Toxicitv.  Mobilit   or  Qfe Throuh  Treatment
 Alternative SP-1, the No Action alternative, would not provide any
 immediate  reduction   in   toxicity,  mobility   and  volume   of
 contaminants.  It may provide some reduction in toxicity and volume
 by natural attenuation, but it would be insignificant.   It would
 not provide any long-term reduction in mobility  of  contaminants.
 Alternatives SP-3 and  SP-4 would result in significant reductions
 in toxicity, mobility and volume of contaminants.  Alternative SP-3
 would reduce  the toxicity,  mobility and  volume by removal  of
 contaminated slag  and lead  oxide  materials  from  the  site  and
 off-site treatment and disposal  or  recycling.   Alternative  SP-4
 would reduce toxicity, mobility and volume by on-site treatment.
 Alternative SP-5 would reduce the  mobility and  toxicity  of  the
 contaminants in that they would be immobilized in the stabilized
 mass and no longer  present a direct  contact threat.   Alternatives
 SP-4 and SP-5 would  leave some  contaminants on  site, but their
 mobility would be significantly reduced.  Alternative SP-5 would
 result in some volume  increase after treatment.
                                21

-------
Short-Term Effectiveness

The implementation of Alternative SP-1, the No Action alternative,
should not  result in any additional risk to the  workers and the
community.   Alternatives SP-3, SP-4 and SP-5  include activities
such  as  contaminated  slag  and  lead oxide  removal,  handling,
treatment   and/or transportation that could result  in potential
exposure of  workers  and residents to contaminated dust generated
from  remedial activities.   Alternatives SP-4  and  SP-5 involve
on-site treatment that reduces the chances of spillage of hazardous
waste  in  transit,  but  could  result  in  worker  exposure  to
contaminants during treatment.  However,  Alternative SP-5 employs
a less complex treatment process than  Alternative SP-4,  and does
not involve the handling of such hazardous chemicals.  Dust control
measures  and closed  loop treatment systems would significantly
reduce these possibilities.  For costing purposes, it was assumed
that it would take a period of  30 years for natural attenuation to
achieve protection under Alternative SP-1.  Implementation periods
of 18, 16 and 15 months were estimated  for Alternatives SP-3, SP-4
and  SP-5,  respectively.   These  estimates include design  and
testing, selection of a contractor, mobilization,  demobilization,
and actual remediation period.

Implementability

Alternative SP-1 does not involve any major site activities except
monitoring, which can be easily implemented.   Alternatives SP-3,
SP-4 and SP-5 involve removal and/or treatment of contaminated slag
and  lead oxide  materials from  the site.   Implementability  of
Alternative SP-3, which involves a flame reactor,  is considered an
innovative technology and implementability  on  a  commercial scale
has not been  proven,  nor has it been used  at  any Superfund site.
Markets  have  not been  identified  for  .the  process  byproducts
associated with this  alternative, which may further increase costs.
Regulatory permits must be approved and  obtained and implementation
depends on the availability of  an operating flame reactor facility
at the time of remediation.   Alternative SP-4 could be implemented
because   the  technology is   available   and   proven   in  the
hydro-metallurgical  industry.  However, the process  has not been
used  for  similar applications or  waste  materials.  It  may also
require a series of steps to  leach multiple contaminants and would
also  produce a slag  and lead  oxide residue which would require
disposal, in addition to  large amounts of liquid wastes generated
during the process.

Solidification/stabilization  would  be   relatively   simple  to
implement, since a one-step mixing and placement process is used.
This alternative would treat these wastes  to  be nonhazardous, which
would be ensured by testing according to the TCLP.  The technology
is  proven for  CERCLA  waste  contaminated  with  metals.    Mobile
treatment  units  are  also available.   Any material  from  which
contaminants would leach  above acceptable RCRA regulatory levels,

                                22

-------
as determined by TCLP testing, would be disposed of off site at an
appropriate RCRA-permitted facility.  However,  it is expected that
all  of  the  material  would  meet RCRA  regulatory levels  after
treatment.

Cost

The total  capital,  annual  operation and maintenance,  and present
worth costs for all slag and  lead oxide material alternatives are
presented in Table 10.  The present worth cost,  based on a discount
rate  of  five  percent  and  a  30-year  operation  period,  for
Alternatives SP-1,  SP-3, SP-4 and SP-5 are $439,000,  $4,215,100,
$3,269,000 and $2,303,100, respectively.  Alternatives SP-1, SP-4
and SP-5 would require  annual operation and  maintenance costs.
Alternative  SP-3   does  not   require  long-term  operation  and
maintenance.  Alternative SP-1 is the le;st expensive alternative.
However, its primary constituent  is moni. ,>ring and does not involve
any  treatment  and disposal.   Alternative  SP-5  is  the  least
expensive treatment and disposal alternative while alternative SP-3
is the most expensive.


Comparison of Debris and P**aB|**a*d surfaces (C8) Alternatives
This subsection compares  the relative performance of each debris
and contaminated surfaces remedial alternative using the specific
evaluation  criteria  listed  previously.    A  summary  of  this
Comparative analysis is presented in Table 11.


Overall Protection of Human Health and the Environment

Alternative CS-1,  the No Action alternative, would leave debris and
surfaces, which are primarily contaminated with lead dust, in their
current condition.   This  alternative  would not meet the remedial
objectives and would not  allow safe entry  in  the future.   Human
health would be protected from direct  exposure  as  long as the site
and building security can be effectively maintained. However, risk
due to  exposure of  down-wind receptors and  environmental risks
would  not  change.    In  comparison,  Alternative  CS-2  would
decontaminate debris and  remove it from site for  disposal  in a
Subtitle  D landfill.   This alternative  would also  recycle any
appropriate  materials.    Alternative  CS-2  would  also  remove
contaminated  dust from  the  buildings  and equipment  surfaces.
Therefore, it would  be fully protective of human health and the
environment.  In addition, Alternative CS-2 achieves the remedial
objectives and allows safe entry into the buildings.

Compliance with ARARs

Alternative  CS-1  would not achieve  contaminant-specific  ARARs.
However, it would comply with action-specific and location-specific

                                23

-------
ARARs.  ARARS which apply to,  and would be met by Alternative CS-2
are OSHA Standards,  DOT  Rules for  Hazardous Materials Transport,
and RCRA Requirements for Transporting Waste for Off-site Disposal.
A complete listing of ARARs for the site is contained in Tables 6,
7, 8 and 9.

Long-Term Effectiveness and Permanence

Alternative  CS-1  would only  maintain the  site and  buildings in
their present conditions.  Therefore, debris and contaminated dust
on surfaces would  remain, although roof repairs would prevent water
leakage and transport of  contaminants.  Protection of human health
and the environment would rely solely on maintaining the site and
building security.   Alternative CS-2 would remove  all hazardous
debris and  dust for off-site treatment and disposal.   Materials
would  be  recycled  wherever  possible.   Any contaminated  water
generated  from decontamination operations  would  be  removed and
treated  and/or  disposed  of  with the  standing  water.    This
alternative would eliminate long-term exposure risks from the site
and the buildings to on-site workers and downwind receptors.  The
buildings could be safely entered after decontamination without
presenting a risk to human health.

Reduction of Toxicity.  Mobility or Volume Through Treatment

Alternative  CS-1  would not provide any reduction in toxicity or
volume.   Mobility  of contaminants  in  the buildings would  be
somewhat reduced by repairing  the leaky roof. However, mobility of
contaminants from debris staged outdoors would  remain unaltered.
Alternative  CS-2  would  provide complete  reduction  in mobility,
toxicity and volume, since all contaminants would be removed from
the site.

Short-Tenn Effectiveness

Alternative  CS-1  would not result  in any  additional  risk to the
workers, community or the environment as long as building security
and integrity could be maintained.  Roof repair would not introduce
additional  risk.    Alternative CS-2  would. involve  removal  and
transport of contaminants from the site.  Therefore, there would be
some  potential public exposure risks as  well as  environmental
impacts associated with possible accidents involving transportation
of waste materials  to  approved facilities.   Worker  exposure risk
would increase  during  decontamination activities  associated with
Alternative  CS-2.   These risks would be mitigated  by protective
equipment and  strict adherence to the  site-specific  Health and
Safety Plan. Alternative CS-1 would require long-term maintenance.
Alternative CS-2 would be considered a permanent remedy and would
not require  any maintenance.   Roof  repair for Alternative CS-1
could take approximately  one month.  Building decontamination could
be accomplished in approximately three months for Alternative CS-2.
However, a period of one year was  estimated for design, bidding,

                                24

-------
•election of a contractor, mobilization, demobilization, and actual
decontamination time.

Impleroentability

Alternative CS-1 could be easily implemented as it does not involve
any major activities.  This alternative would require monitoring,
roof repair, and maintaining site security. Alternative CS-2 would
require extensive decontamination.  Multiple technologies such as
dusting, vacuuming,  wiping and  hydroblasting would be  utilized
depending  on  the  area  of   the building  and  surfaces  to  be
decontaminated.  Some parts of the buildings, such as walkways and
stairs, are structurally weak and would require proper assessment
before   using  high  pressure   washing  techniques   such   as
hydroblasting.  Although some  of the areas, such as the kiln burner
building, feed building and decasing building,  have walls and roofs
containing  asbestos,  it  is   not in  a friable  state.    Friable
asbestos was removed  during  the Removal Action activities,  and
proper care would be  taken during the buildings' decontamination to
ensure  that friable asbestos would not be exposed  during these
activities.   Areas containing asbestos would  not be subjected to
hydroblasting.  All  technologies associated with Alternative CS-2
are  commercially  available and  commonly used for  cleaning  and
decontamination applications.  Collected dust,  and wipe cloths used
for  decontamination,  could  be  treated  and  disposed of at  an
appropriate RCRA permitted facility,  while  decontaminated debris
would be either, recycled or disposed of appropriately.

Cost

The total capital, annual  operation and maintenance, and present
worth costs for both alternatives are presented in Table 11.  The
present worth cost of  $136,000 for Alternative CS-1 is based on a
five percent  discount rate and  30-year period and  is  primarily
associated with maintenance costs. Alternative CS-2, which has an
estimated present worth cost of $1,691,000, would not incur annual
operation and maintenance cost.   Although  Alternative CS-1 is less
expensive than Alternative CS-2, it would not involve any treatment
or be as protective  as Alternative CS-2.


Comparison   of   Standing  Water   and  Sediment   (SW)   Remedial
Alternatives

This subsection compares the relative performance of each standing
water  and  sediment  remedial  alternative  using  the  specific
evaluation criteria  listed above.   A  summary  of  this comparative
analysis is presented  in Table 12.
                                25

-------
Overall Protection of       Health and the Environment
Alternative  SW-1,  the No  Action alternative, would  not provide
protection  of human  health and  the environment.   Contaminated
standing  water  and  sediments  on  the  site would continue  to
contaminate surface water and groundwater.  Alternatives SW-2 and
SW-3 would be protective of human health and the environment and
achieve  the  remedial  objectives  because contaminated  water and
sediments  would be removed  from  the  site  and treated  and/or
disposed.   These alternatives would result in  the reduction of
toxicity, mobility  and volume of contaminants.   Alternative SW-2
would  involve on-site treatment and disposal, and  treated water
would  meet groundwater discharge  requirements.   Secondary wastes
generated from treatment  along with sediments removed from the site
would  be disposed of  off  site  at  an  appropriate RCRA-permitted
facility.  Alternative SW-3 would remove contaminated surface water
and sediments for disposal at an  off -site, RCRA-permitted facility.

Compliance with ARARs

Alternative SW-1 would not  comply with contaminant-specific ARARs.
It  would,  however,  comply with  associated  action-specific  and
location-specific ARARs.  A complete list of ARARs for the site may
be found in Tables 6,  7,  8 and 9.

OSHA Standards are  ARARs that would be met by  both Alternatives
SW-2 and SW-3.  All  Federal  and State standards applicable for
recharge of  treated wastewater  to groundwater,  including Maximum
Concentration Levels (MCLs) , would apply and be met by Alternative
SW-2.   Alternative SW-3,  which involves off-site  treatment and
disposal, would meet  DOT Rules  for Hazardous Materials Transport
and RCRA Requirements  for Transporting Waste for Off-Site Disposal.
The   shipment  of   contaminated   water,   containing   ha z ardour?
constituents to an off-site treatment and disposal facility would
be consistent with  EPA's policy  to ensure that  the  facility is
authorized  to  accept such material   in   compliance  with  RCRA
operating standards.

Alternative SW-2 would be designed to achieve contaminant-specific
ARARS  for groundwater  recharge.   Alternatives SW-2 and SW-3 would
meet contaminant-specific,  action-specific  and  location-specific
ARARs.

Lona-Term Effectiveness and Permanence

Alternative SW-1 would not provide removal or treatment but would
provide  site access  restrictions.   However, this  would  not be
effective in the long term in preventing further contamination of
surface water and groundwater.

Alternatives  SW-2  and SW-3 would be  effective in  eliminating
potential risks  associated with on-site exposure through direct

                                26

-------
 contact and ingestion of contaminated standing water and sediments.
 This  alternative  would  also  prevent  further  contamination  of
 surface water and groundwater and off-site contaminant migration.
. Both alternatives would be permanent and  effective  in protecting
 the human health and the environment.

 Reduction of Toxicitv.  Mobility or Y9lMPc  Through Treatment

 Alternative SW-1,  the No Action alternative, would not involve any
 removal, treatment or disposal of the contaminated standing water
 and sediments and, therefore, would not be  effective  in reducing
 the toxicity, mobility or volume of the contamination.

 Alternatives SW-2  and SW-3 would effectively reduce the toxicity,
 mobility and volume of the contamination because these alternatives
 would  completely  remove  contaminated   standing   water  ponded
 throughout the site and in the basement of the refining building.
 These  alternatives would also  include  disposal  of  sediments
 underlying the standing  water in an appropriate,  RCRA-permitted
 facility.

 Short-Term Effectiveness

 The  implementation of Alternative  SW-1  would  not  result  in
 additional risk to the workers and the community,  since no major
 remedial activities would be conducted.  Alternatives SW-2 and SW-3
 involve  collection,  treatment,  and/or disposal of  contaminated
 standing water  and sediments.   Alternative  SW-2  would  involve
 on-site treatment and disposal and require  handling of chemicals
 and process byproducts, such as contaminated sludges,  which would
 require  appropriate  disposal.   The activities associated  with
 Alternatives SW-2  and SW-3 would involve  short-term risk to site
 workers.  However,  these   risks   could  be  minimised  through
 implementation of  the  site-specific health and safety plan.

 Off-site disposal  of secondary wastes  generated during treatment
 and  sediments  in  Alternative  SW-2 and  transportation   of
 contaminated water and sediments in Alternative SW-3 would pose a
 potential risk  to the  community from possible spillage  during
 transit.   Coordination with local  traffic  authorities would  be
 required for these alternatives.  Alternative SW-1 could take more
 than 30 years to achieve protection through natural attenuation of
 contaminated water.  However, a period of 30 years was used  for
 cost-estimating purposes.    A  period  of  fourteen  months  was
 estimated for Alternative SW-2.  This estimate includes design and
 testing,    bidding,     contractor   selection,    mobilization,
 demobilization,  and actual  remediation time.   Alternative  SW-3
 would require six  months to achieve complete protection.
                                27

-------
Implementability

All components  of Alternative SW-1 would be  easily implemented.
This  alternative  simply  requires  access  restrictions  and  a
monitoring program.   Alternative  SW-2 would utilize  relatively
common treatment technologies and materials and is available from
a number of vendors.  However, it would require time to conduct a
treatability study to define the design and operating parameters of
the treatment process, and design and set up an on-site treatment
facility  to  meet the  stringent  treatment  levels required  for
groundwater recharge. Alternative SW-3 utilizes off-site treatment
and disposal and  would  require less time and money to implement
compared  to  alternative  SW-2.   There are only  a  few  off-site
treatment  and  disposal  facilities available  for  aqueous  waste
treatment,  but inquiries made  by  EPA indicate that  adequate
treatment and disposal capacity would be available.


Cost

The total  capital,  annual operation and maintenance  and present
worth  costs  for all   standing   water  and  sediment  remedial
alternatives are presented in Table 12.  The present worth costs,
based on a discount rate of five percent and a 30-year period, for
Alternatives SW-1,  SW-2  and  SW-3  are $220,000,   $1,335,000  and
$993,200,  respectively.   Only Alternative SW-1 would  require an
annual operation and maintenance cost.   Alternatives SW-2 and SW-3
would not  involve operation  and maintenance costs.   Alternative
SW-l would be the least expensive, but it would  not involve any
treatment.  Alternative SW-2  would be the most expensive standing
water remedial  alternative.    Alternative SW-3 would be a less
expensive alternative involving treatment and disposal.


THE SELECTED REMEDY

The  evaluation  of  the  alternatives   in  the  previous  section
discussed each of  the alternatives relative to criteria established
under the Superfund law and regulations.  The intent of the Early
Remedial  Action is  to  remediate  those areas of the site that
require an expedited response, and to implement remedial activities
that will be consistent with the final remedy at the site.

Based on the  results  of the FFS, and after careful  consideration of
all reasonable alternatives,  EPA and the New Jersey Department of
Environmental Protection and Energy (NJDEPE) proposed utilizing the
following alternatives for the Early Remedial Action at the NL site
at the public meeting held on August 6, 1991:

SP-5:     Solidif ication/Stabilization/On-Site Disposal of the Slag
          and Lead Oxide Piles
                                28

-------
CS-2:     Decontamination/Off-Site Treatment  and  Disposal of the
          Contaminated Surfaces and Debris

SW-3:     Off-Site Treatment and Disposal of the standing Water and
          Sediments

After considering public comments,  the selected alternatives are
the implementation of Alternatives SP-5, CS-2 and SW-3.   Site risks
have  been  identified as being  primarily  due  to exposure  to
contaminated  media  and   releases to  the  environment from  the
contaminated  media.    These  risks  would  be  eliminated  through
implementation of the selected remedy.

The selected alternatives represent  the best balance of trade-offs
among the criteria used to evaluate remedial actions. The selected
alternatives  meet the statutory  requirements  in  CERCLA Section
121(b):   l)  to protect  human-health and the  environment;  2)  to
comply  with  ARARs;  and  3)  to  be cost-effective.   The selected
alternatives   utilize   permanent   solutions  and  alternative
technologies  to  the maximum  extent practicable and  satisfy the
statutory preference for treatment as a principal element.

EPA and NJDEPE  believe  that the  selected remedy  will reduce the
threat  to public health and the environment through the following
sequence  of  actions.  First,  the slag and lead  oxide piles,  in
addition  to  similar  materials,  would  be  treated  using  the
solidification/ stabilization technology. Concurrently, buildings,
paved  surfaces,  equipment' and debris  would  be  decontaminated.
Subsequently, the contaminated standing water and water used for
decontamination  of  buildings,  etc.,  would  be  collected  and
transported for off-site treatment and disposal.  Finally, drains
would be decontaminated and unplugged.  Through this sequence, the
sources of contaminated runoff would be eliminated and water from
future  rain  events  would  drain through  these   areas  without
transporting contamination off site.

In addition,  materials  for  which markets  can be  found  will  be
recycled.  Recycling will allow recovery of contaminant resources
in the  waste materials  and  will  result in permanent  removal  of
these  materials  from the  site.    Materials  will be  recycled,
providing that it can be done in a manner  that is protective of
human health  and the environment,  is cost-effective and  can  be
accomplished  in  approximately  the   same  time   frame  as  the
alternatives identified in the selected remedy.

The total present worth cost of the selected remedy is estimated to
be $4,987,000 which includes treatment and on-site disposal of the
slag  and lead  oxide materials,  decontamination  of debris  and
contaminated surfaces with off-site treatment  and disposal,  and
off-site treatment and disposal of contaminated standing water and
sediments.    All  off-site   disposal  will  be  at  appropriate
facilities.   The  capital cost  is  estimated  to  be  $4,698,300.

                                29

-------
Annual operation and maintenance costs are estimated to be $17,000.

The actual cost may vary due to a number of factors including the
uncertainty in the precise amount of material that is amenable to
the solidification/stabilization technology, the increase in volume
after  solidification/stabilization,  and  the  exact  amount  of
standing water and  sediments  present which will require off-site
transportation and disposal.


STATUTORY DETERMINATIONS

Under  its  legal  authorities,  EPA's  primary responsibility  at
Superfund  sites  is  to undertake  remedial actions that  achieve
adequate  protection of  human health  and the  environment.   In
addition, Section 121 of the Comprehensive Environmental Response,
Compensation, and Liability Act,  as amended,  establishes several
other statutory requirements and preferences.  These specify that,
when complete, the selected remedial action for a site must comply
with applicable or relevant and appropriate environmental standards
established  for  Federal  and  State . environmental  laws unless  a
statutory waiver is  justified.  The selected  remedy  must also be
cost-effective and  utilize permanent solutions and  alternative
treatment technologies to the maximum extent practicable.  Finally,
the  statute  includes  a  preference  for remedies  that  employ
treatment that permanently and significantly reduce the toxicity,
mobility  or volume  of hazardous  substances  as their  principal
element.  The  following  sections  discuss  how  the selected remedy
meets these statutory requirements.


Protection of Human Health and the Environment

The three components of the selected remedy provide for protection
of human health and the environment by removing the immediate and
future  risks  posed  by  these   hazardous materials  on  site.
Contaminated slag and lead oxide materials will be treated on site
using   solidification/stabilization  processes.     The  treated
materials  will then  be placed on site  in a protective  manner
pursuant to RCRA standards. Contaminated  debris and surfaces will
be decontaminated.   Debris that could not be decontaminated will be
transported to an appropriate off-site,  RCRA-permitted facility.
Any recyclable materials for  which markets can be found  will be
recycled.     Contaminated  standing water  and sediments will  be
transported off  site for  treatment and disposal.    The selected
remedy  will  significantly reduce  the  mobility  and  available
toxicity of contaminants and will  directly result in the reduction
of risks posed by the presence of  contaminants at the site.  There
will be no unacceptable short-term risks caused by implementation
of this remedy.
                                30

-------
Compliance with Applicable or Relevant and Appropriate Requirements

The three components of the selected remedy, SP-5, CS-2 and SW-3,
will  comply with  all  Federal and  State requirements  which are
applicable or relevant and appropriate to its implementation.

Alternative  SP-5  would be  implemented  to conform with all OSHA
Standards,  RCRA Land  Disposal Restrictions  (LDRs),  RCRA Haste
Management  Standards,  procedures  for  RCRA  Identification  of
Hazardous  Waste,   and 40 CFR  264,  Subpart X,  which provides
standards  that are applicable  to  the on-site  solidification/
stabilization of contaminated waste.

ARARS vhich apply to, and  would be.met by Alternatives CS-2  and SW-
3, are OSHA Standards, DOT Rules for Hazardous Materials Transport,
and RCRA Requirements for Transporting Waste for Off-Site Disposal.

Cost-E f feet iveness

After evaluating  all  of the alternatives which  most effectively
address  the  principal  threats posed by  the contamination at the
site and the statutory preference  for treatment, EPA has concluded
that the three components  of the selected remedy afford the highest
level of overall  effectiveness proportional to their cost.   The
selected remedial action components are cost-effective because they
provide the highest degree of protectiveness for human health and
the environment in the both the long term and short term, compared
to  the  alternatives evaluated, while representing a  reasonable
value for the cost.

Utilization of  Permanent  Solutions  and  Alternative Treatment for
Resource Recovery! Technologies to the Maximum Extent Practicable

The  three components  of  the  selected  remedy  provide  the  best
balance  among the  alternatives  with respect  to  the  evaluation
criteria.  In particular,  the selected remedy is able to maintain
permanent protection of human health and the environment over the
long term, once the remedy is completed.  This remedy will reduce
the mobility  and  available toxicity of  the  contaminants without
adverse  impacts on human health  and the environment during the
construction and implementation period.

In  addition,  materials for which markets can  be found  will  be
recycled.  These materials may include,  but would not  be limited
to, lead feedstock materials, scrap metal and equipment.  Recycling
s  .3.1 allow recovery of contaminant resources in the waste materials
  ,a will result in  permanent rexer'al of these materials from the
site.

Services  and  materials   needed  for  the implementation  of  the
selected alternative  are  readily available  and no technical  or


                               31

-------
administrative difficulties are foreseen with the implementation of
the remedy.

The State  and community concur with the remedy,  which meets the
statutory requirements to utilize permanent solutions and treatment
technologies to the maximum extent practicable.

Preference for Treatment as a Principal Element

The statutory preference for treatment is satisfied by the selected
remedy, since principal  threats posed  by the slag and lead oxide
piles, debris  and contaminated surfaces,  and  standing water and
sediments will be addressed through treatment and disposal of these
contaminated materials. These treatment methods effectively reduce
the mobility and toxicity of contaminants.

DOCUMENTATION OF SIGNIFICANT CHANGES

The Proposed  Plan for the NL site was  released to  the public in
July 1991.  The Proposed Plan identified the preferred alternative
for  addressing  the  slag  and  lead  oxide  piles,  debris  and
contaminated  surfaces,   and  contaminated  standing   water  and
sediments.  EPA reviewed all written and verbal comments submitted
during the public comment period.  Upon review of these comments,
it was determined that  no significant  changes to the  selected
remedy,  as  originally  identified  in  the  Proposed   Plan,  were
necessary.        .

EPA has received a number of comments relative to the recycling of
waste materials.  As  indicated in  this document and discussed in
the attached Responsiveness Summary, recycling will allow recovery
of  resources  in the  waste materials and  will  result  in  the
permanent removal of these materials from the site.  Consequently,
EPA intends  to pursue recycling of  such  materials and/or  would
allow PRPs to do so, if it could be  implemented in  a manner that is
protective of human health and the environment and within a time
frame comparable to the selected remedy.
                                32

-------
TO DELAWARE
   RIVER
                                 //•       V-^i            /
                                 /CLOSED    \        B. F. COODMC
                                   LANDFILL  X     I          ./
                            LANDFJLL-/
                            ACCESS
                            ROAD
                          >.NL
                            ' INDU
                             SITE
REDUCTION AREA
AND) BUILDINGS

» —'
 LEGEND  :

   SLAG  PILE  '

   STANDING WATER
                           NOT TO SCALE
                              FIGURE 1

-------
                           x—x *
           DL  —J  "—"
        	txumafss*.	i
         ' «.NnM*cc!   .-'
PENNS   GROVE   PfDRICKTOWN    ROAD
                                        NLINDUSTRIES
                                     PEDRICKTOWN, NEW JERSEY
                                           MM NOT TO SCALE

-------
                            TABLE 1
                          NATIONAL LEAD
                    RELOCATED WASTE INVENTORY
Sample

     1
     2
     2A
     3
     4
     5
     6
     7
     8
     9
     10
     11
     12
     13
     14
     15
     16
     17
     18
     19
     20
     21
     22
     23
     24
     A,B,C,D
Material

Litharge
Baghouse Socks
Baghouse Socks
Paper Bags
Fiber Drum Parts
Battery Casing £ Debris
Lead Bearing Slag
Slag & Debris
White Powder (Lead Sulfate)
Lead Hard Head Material
Lead Debris
Red Dross
Soft Lead Dross
Black Dross
Orange/Yellow Dross
Empty Metal Drums
Wood Pallets
Drum .Covers/Parts
Plastic Debris
Rubber Conveyor Belts
Lead Oxide
Oily Sludge

Liquids
White Powder
Standing Water
Slag Piles
Estimated Volume

31 drums
120 drums
160 CY
50 CY
200
250 CY
4 CY
170 CY
110 CY
40 CY
400 CY
40 CY
105 CY
10 CY
4 CY
80
350
60
60 CY
60 CY
40 CY
(3) 55-Gal. Drums
(4) 5-Gal. Pails
(7) 55-Gal. Drums
(300) Bottles
1 Million Gals.
9,800 CY
     CY«Cubic Yards

-------
                                                                 TAni.R  2



                                              SUMMARY  OF rlirHICAI. CONSTITIirNTS IN IMfrfRENT UASTE STRtAMS


                                                     Iff. litifuttriff*.  tr<1r Irhtown. N«w
08
2 30

OO
, 	
Mt
...; 	 . 	
: 	 I 	
JMt*-M-l|AI«BllM
»*M-M-*|AHtlMHT
|M«*-M-t|«r»*f>le
|MM-lt-l|*a*l«
|Mt*-tl-t|*«tylltw
M4*-tl-t|c*4Bl«B
MM-?*-i|cai«iM
| MM-* r- 1 |cfc*wl«i
|M**-M-*|c*t*lt
Mlt-M-«|l«M
Mlt-tl-l|l«»4
MM-M-t|*»>i»«»i»»
f • M-M- 1 |MM*M*M
Mlt-tr-«|n*rc*rr
M4*-*t-*|ftlcfc*l
Ut*-*t-f (?•«••• !«••
|rMt-*t-f|S«l«MOT
1 1
|»4t*-i*-*|n»tiiM
| Mt*-«t-t|*MM*lM
|f«**-M-«|tlM
• onits - -•»•
•• WltS - ••Illtav

A
Hill - KM
	 	 	
tIM - MM*
•t.t - MM
IM - IIM
It.* - IIM
1.9 - •••
9*. 9 • IM
IM« - MM
91 • ««•
II. 1 • tM
•M - MM
•MM -MMM
IIM* -MMM
'•If* TIM*
It* - MM
•.Ml - •.»!
•*.* - MM
MM - M«M
•.•I - t.«
f - 9.9
tlM - 4fM»
•.M - l.t



SLAC
•
HIM - mi
	 . 	

Itl - IMM
It* - MI
II - *M
t.l - t.t
II. « - tM
tlM - IMM
IM • IIM
11.9 - IM
IIM - MM
•MM -tlMM
• m -• MM
•.M* . «.M
lit • • •!!
9IM - «I*M
*.M • I.I
9 • It
*.• - I.I
t*9 • *M
IIM - ••!•


rn.i •
c
MM - MA*
}M* - *tM
9M - IIM
• M - IIM
Mt - IIM
«.« , 1*
Mt - MM
•*M - **M
1*1* - «*M
It MM -M*M*
MM* -IIMM
Ml -* tlM
911 - MM
*.*• - *.M
11* - IIM
IIM* • MM*
I.I • 1.1
••• - II
IffM - MM*
I.I - t.t
M* - MM
IIM - MM



•
HIM - WAX
	
MM - MM
*».t - tIM
IM - Itl*
Ml - Itt*
l.t - *.l
41. «- 14*
tir* - i«i**
tl* - »!••
• .1 - IM
•M - MM
IMM -I14M*
•*M -I1IM*
• 14 • I*IM
tit • M4«
•.•II • •.!•
lit - MM
MM . «1»M
•.•1 - 1.9
t.« • 19
MM - CMM
*.*! - 1.9
lit - 11*
•M • MM


i.rjM» mune •
' 9tt W
r II.C
HIM • HAX
IM - III*
MM - !M*
Ml - 414
1* - II*
*.ll - *.M
1*1 - •!•
Ill* - 111*
M* - 111
t.l - • •
lit - «M
IMM - M1M
l*t*M -*IIM*
111 - MM
M.I - tM
1 - l.«
IM - 1»I
MM* - **M*
•.tl - *.*•
t.t - •.*
IIM* - 4MM
*.* - *.M
*.« - II. 1
t*» - MM


nmra n«stx •

MM - MM
11. • • MM*
1.1 - 9«*M*
*.* - IMM
*.ll - IIM*
• .•II - M.*
• .t» • IIM*
11 - IMM*
• .tl - IMM
•.•f - • 1*1
t.l - MM*
III - ttMM
111 - MMM
1.1 - IIM*
• .«• - IIM
•.•It • •«
l.t - IIM
Ml - MM*
*.MI - tl. 9
•.II - M
• .Ml . I.*
• ••1 - Ml
11 - «MM


|nrc«MTAMiiMtiaii •
VtfC SAMPLES
HIM - MAX
•.•It . It. I
• .•M* - M.t
*.M«* - It.*
•••It - l.t
».M*f - •.•!•
•.Mlt - l.t
• .Ml - »l.t
• .Mt* - *.•
•.MM . «.ll
• - It
*.t« . «tt
• .M . 911
*.«'-" *.*
• - 9.9
*.M*I - *.*!•
*.M*t - 9.1
*.*tl - I*
*.M*t - «.Mt
• .Mt* - *.lt
• .» - M.t
*.M*t - «.MI
«.M*f - •.!!
• .•M - M*


	 -1
stm>twB ••
SAMPI.es
MIM - MM
M.t - •!!.•
11.* - t*M.«
• • • M.«
If. 9 - *•.•
9.9 - 99
II.* - •!!.•
IM*.* - tlM*.*
•.• - It.l
*.* - tit.*
II. t - »»».*
M.* - ttM.*
IM.* - *1M.*
IIM.« - 1IM.B
It.t - IM.«
•.t • ».l
It.* - 141. •
MM.* - IMM.*
9.9 - M.*
ItM - «MM*
*.* • •.*
• !.• - M.t
It.* - IIM..*



-------
                                TABLE 3

                        ••tutts of tht Nttitt Antlyvlt


                         SLAG AND LEAL OXIDE PILES (1991)

                        Conctntratitn rtpertttf in «Q/kg
Clitnt •
leeitien:

X Sslidt
f»f»i»w.
AiJ-'nj-
»-.:i!W»y
»-»t-ie
ii-rx
C«r-:j-
C--S--IT
:::9*-
Jrs-
.*«:
»«»•*$ iiT
••i-;i-.tn
•*-c.-r
».-:«*.
St.e-.-iiT
S-;ve-
2 '.-.:
•08794
Ittd
Oxid* A
•8.0

1400
970
403
770
1000
100
• 430
'12000
483333
783
333
2.10
383
MS
8
1123
•0879S
lt»d
toidt •
97.1

•00
2530
490
40
•00
110
2400
15000
350030
•63
SO
2.40
43D
«0
11
4000
•08794
A Hit

99.3

•4000
12000
1000
•30
soo
169
31030
130000
133300
19900
480
0.02
MO
1
4
40000
•08797
• Hit

•8.4
•
•700
1100
1400
450
SO
200
27SO
100000
120000
2000
*40
0.10
•90
S
*
ssoo
•08798
e Hit

93.2

11000
400
1400
1400
350
ISO
2500
110000
130099
1500
1100
0.02
470
1
4
3050
•08799
t Hit

74.4

12000
SOO
1200
1300
260
130
3060
130000
110000
2040
1100
10
•99
2
*
' 5570



.omen*
. tlHIT
SO
1
1
2.5
2.5
5
5
10
s:
5
5
0.02
5
0.5
2.5
2.5
             n:: ot:«:t»ti
POOR QUALITY
   ORIGINAL

-------
        Appendix c
List of PRP« Who W«r« 8«nt
  Central Votio* i*tt«rs

-------
                      List of Potentially Responsible Parties
                   To Whom EPA Sent a General Notice Letter
                       Dated June 20,1991 Concerning_
                      The NL Industries Inc. Superfund Site
                          Predericktown, New Jersey
Aaron Ferer & Sons Company
Ace Battery Company
Acme Alloys
American Freight Warehousing
  Company
Amlon Metals
Amspec Chemical
Ansam Metals Corporation
Anzon Inc./Associated Lead
Ashland Metals
AT&T Nassau Metals (Nassau Recyling
  Company)
Balmet Recycling
Belmont Metals, Inc.
Bonus Metal Canada, Inc.
C & D Battery Company
C. Tennants & Sons & Co./Carghill,
  Inc.
Canada Metals
City Metal Company
Delco-Remy Division, GMC
Douglas Battery
Elizabeth Herb & Metal
Exide Corporation
Freeway Scrap Battery, Inc.
Fundamental Minerals & Metals
Gale Industrial Scrap Iron & Metal
  Co.
General Metals & Smelting Co., Inc.
Gibson Metals
Gibson, Dunn & Crutcher, Trustee,
  NSNJ
Globe-Union/Johnson Controls
Golf Cars, Inc.
Gould, Inc.   .
Grant Manufacturing & Alloying, Inc.
Hammond Lead Products, Inc.
Kasmar Metals, Inc., c/o Paul A.
  Kasmar
Louis Mack Co., Inc.
Master Metals, Inc.
Mayer Alloys Corporation
McKinney Scrap Metal
Metal Bank of America
Minkin  Industries, c/o Trustee
N. Bantivoglio's Sons, Inc.
NL Industries, Inc.
Reserve Trading Company
Resource Alloys & Metals
Riverside Metals Company
Robert L Puckett, Director & President,
  NSNJ
Robert L Puckett, Director & President,
  NSR
Sampson Tank Service
Seitzinger/Taracorp
Standard Metals, Inc.
Steven L Zimmerman, PC, Trustee,
  NSR
Tennessee Chemical Company (Corp.
  HQ)
Thermal Reduction Corporation
Tonolli  Trading Co.
U.S.S.  Lead Refinery
USARCO
Wharton Enterprises

-------
     J .
          710
£«

                    /JL

                     O                 •
                     r£bAtt,k7?>u)i)j  Afe«J O&gfgti




       J
of TW-


      /QCWSrtL U'A/£t> 4*T *
                     .i*A6tr  totai c*vf*titjr OH A*H tint*.


                            save  *t  * Af*nie&  cf A/L
        or SfiijU   UAH*, ff A  S^r^MfJ ytiu J?>arn   /

            ***   IT /s *

-------
                                    **  ?   *
                        v
r**tt«r»*», fcueb nsn At <**\ OF
                 **tt«r»*»,
       ft) otft*. to

                                         . J
                                   C
                          : A). J.
                                         71

                  J of
                      S£7~ A
THE

        V
           A/,

-------
     Comments on the Proposed Flan and Focused Feasibility Study (FFS)
                for Operable Unit Two, NL Industries, Inc. Site,
                             Pedricktown, New Jersey
 Remedial Alternative for Contaminated Surfaces and Debris
     EPA has proposed decontamination of contaminated surfaces and debris with off-site
 treatment and disposal as pan of Operable Unit (OU) Two.  At the threshold, we note mat
. building contamination has also been considered in OU One, and recommend mat EPA
 clarify which OU will address decontamination. The contaminated debris consists of lead
 dross, wooden pallets, baghouse bags, scrap metal and other materials present throughout the
 site.  It is not clear that the debris and contaminated surfaces present similar risks, that
 similar cleanup criteria should be applied, or that  similar remedial alternatives are available.
 Further the need for expedited cleanup of wooden pallets, scrap metal and other debris is
 unclear.  NL Industries, therefore, recommends that the debris and building surfaces be
 evaluated separately.
     The primary justification for including the buildings in an  expedited remedial action,
 appears to be exposures from inhalation, ingestion and dermal contact with dust.  It is
 recognized in  the FFS (p. 1-4 and 1-5) that the limited  access to the site, the securing of
 entrances to the contaminated buildings, and removal of valuable material from the site would
 effectively deter trespassers from the site and would reduce the dermal and ingestion
 exposure. The potential risks from these pathways were thus considered to be much lower
 compared to inhalation exposure (FFS p. 1-9).
     However, it is not evident that any dust in the buildings, which has remained seven
 years after the cessation of operations, would be suspended in air and present a health threat
 via inhalation.  The small layer of dust that may still adhere to  the surfaces of the buildings
 presents  an extremely limited source for wind erosion, and would not be readily susceptible
 to suspension.  FPA has not provided any data to  support the assumption that the inhalation
 pathway presents a potential health risk.
     It should be noted that the preferred remedy  does not provide any guidance on the
 acceptable cleanup level  for the building surfaces.  The cleanup objective should be
 established in  consideration of future use scenarios.  While decontamination and potential
 reuse of buildings may be feasible for the laboratory/office complex, the warehouse, and
 potentially the refining buildings, clearly the decaying operations, buffer storage and kilns
 have little value to non-smelting operations.  NL asserts that demolition of some or of all the
 structures should be considered as a remedial option by EPA if it is a safer and/or more cost-
 effective .remedial alternative. In addition, cleanup should take into account whether or not
 RCRA standards for off-site disposal apply.

                                         -1-

-------
Remedial Alternatives for Slag and Ltsad Oxide Materials
     NL Industries agrees that solidification/stabilization of waste using a mobile treatment
system, followed by on-site disposal is a reasonable alternative for management of slag and
oxide materials. Several issues, howevtr, are raised by the FFS and Proposed Plan which
require clarification. First, there is some question of the ultimate quantity of material to be
treated. Table 1-2 from the FFS suggests approximately 9,800 cubic yards (cy) of slag and
200 cy of lead oxide in piles on the paved area.  Hie 1988 inventory, presented as Table 1 in
the Remedial Investigation, indicated approximately 7,500 cy of slag and other lead bearing
materials in the manufacturing area.  The EPA is using a value approximately 30% higher
than the 1988 inventory.  The EPA stated in Section 5.2.4.1 of the FFS mat the stabilization
process might result in a volume change of as much as 40%, which seems high for mis type
of material. The EPA estimates 14,000 cy of stabilized materials to be disposed in an on-site
RCRA Subtitle D landfill.
     EPA should provide an analysis of appropriate sites for on-site disposal of the material,
especially in the context of  future use scenarios for the site. Examination of the attached
Figure W-l of the Remedial Investigation Repent Volume IV suggests that wetlands and
property boundaries preclude the use of unpaved areas of the property for the construction of
the on-site landfill.  •
     The construction  cost presented in  the FFS and Proposed Plan apparently includes no
cost for construction of an on-site landfill.  The cost estimate presented as Table B-4 of the
FFS provides a cost of $4.34/cy for  disposal on-site. This value may pay for the transfer of
material from the curing location to a disposal location, however, it does not cover the
construction cost of a landfill  on-site.
     Consideration should be  given to the feasibility of placement of Jie stabilized material in
the paved  area at the site.  For example, the basement of the refining building could contain
approximately 1,500 cy of stabilized material. Placement of the remaining  stabilized  material
at the north end of the paved manufacturing area (86,000 square feet) would require further
analysis, and would likely involve dismantlement of all structures north of the refining
building.
Remedial Alternative for Standing Water and  Sediments
     EPA's decision to remove the standing water from the property for off-site treatment is
premature in that it neglects other contaminated water present at the site that will be
addressed in the FS for OU One.  OU One's FS will be completed'by December 1991, prior
to the completion time for implementation of this alternative. Therefore, it is logical  that
EPA consider the appropriateness of treating this waste stream with other OU One waste
streams (e.g., contaminated ground water) in a common remedy.

G:\vfj\wp\oM784ftcm2

                                         -2-

-------
     If sand blasting is being conducted ve. can process the lead contaminated
sand at $.10 per pound delivered in bulk containers.  We feel Master Metals
can be cocpetitive in any disposal area where lead contamination is concerned
by us,ing proper recycling techniques and environmentally  sound technology.
I vill be in touch after you review the above.
Sincerely,
      X K. Mickey
President
Master Metals Inc.
cc: Dillip Kothari Ebasco
    WM Bradford

-------
                                                            €  N  V  I   RO  N
   August 16, 1991
   Michael H. Gilbert
   Project Manager
   USEPA, Emergency & Remedial Investigation
    Response Division
   26 Federal Plaza
   Room 720
   New York, NY  10278

   Re:    NL Industries Superfund Site-Proposed Plan

   Dear Mr. Gilbert:

   Enclosed please find comments prepared on the Proposed Plan and Focused Feasibility Study
   (FSS) for Operable Unit Two, NL Industries, Inc. Site, Pedricktown, New Jersey by
   ENVIRON Corporation oh behalf of NL Industries.  NL Industries is providing additional
   comments under separate cover.

   If you have any questions please call me at (703) 516-2340.

   Sincerely,
  Joyce S. Schlesinger, P.
  Principal

  JSS:vfj
  G:\vfj\n\1784cmts.cvr

  Enclosure

  cc:   Janet Smith, Esq.
        Steve Holt
        Dillip Kothari
CNVIRON Corporation • Counsel in Health and Environmental Science
4350 North Fairfax Drive. Arlington. Virginia 22203 • (701) 516-2)00 • (800) CNVIRON • FAX (705) SI6-214S

-------
MASTER METALS, INC., *BSO w. THIRD ST.. CLEVELAND. OHIO 44113 > (216) 621-2361 FAX 621-7475
                                        Smthtr mi


   August 13, 1991
   Mr. Michael Gilbert
   Project Manager
   U.S. EPA
   Energency and Remedial Response Division
   26 Federal Plaza Room 720
   ftw York, New York  10278


   Dear Mr. Gilbert:

   I -would like to respond to the Superfund Proposed Plan K.I. Industries Inc.,
   Pedricktoun, New Jersey. In particular the slag and lead oxide piles and your
   method of action.

   Background:
        lister Petals is a TSD facility with approval to accept K069 and D008
   wastes. He process-lead residues through rotary furnaces and recylce the lead
   back to the end users. We have environmental improvement insurance and permits
   to operate the rotary furnaces. Our slag passes the TOLP leachate test and is
   diposed of at a sanitary land fill.

   You are proposing Alternative SP-5: On'site Solidification and Stabilization/
   On site disposal for $2,303,100.00 .  We would be willing to process the material
   at our facility in Cleveland. I feel we would accomplish this for approximately
   the sane amount of money excluding transportation cost. We are already receiving
   material from your area and would arrange economical transportation. I am including
   a brochure on our company. I would hope that this idea would be of mutual interest
   that ye could further discuss the possibility. I will call in a few days to see
   how we should proceed.
     , glasK.
   President  /-

-------
MASTER METALS, INC., ZBSO w. THIRD ST.. CLEVELAND. OHIO 44-1:3 • (?ie)-62i-236i FAX 621-7475
                                        Smelter ad Refiner

   September 5, 1991


   Mr. Michael Gilbert
   Project Manager
   U.S. EPA Region 2
   Jacob K. Javits Federal Building
   New York, New York 10278

   Subject: Focused Feasibility Study Report
            N.J. Industries Superfund Site
            Operable Unit Two

   Dear Mr. Gilbert:

        Master Metals Inc. would like to respond to the sunnary of Remedial
   Alternatives for slag and lead oxide materials.   As noted in previous
   correspondence, Master Metals Inc. is an approved and insured TSD facility
   for C008 and K069.  We have several years experience in treating these
   waste streams and the characteristics of these two streams are indentical
   to materials we are currently processing.  We have examined the characteristics
   and we are capable of handling the material at our facility.

        I would like to briefly address the key components as they compare to
   alternative £P-1 SP-3 SP-4 SP-5.   Criteria 1,2,  4 and 5 would be stated as in
   your executive sunxnary.  In criteria 3,  Master  Metals would have a definite
   advantage as this is proven technology and the operation is reliable.  All
   the factors mentioned under 6 inplementability for Master Metals facility  are
   positive.  The  factors are as follows.

             a) proven technology
             b) no monitoring required after remediation
             c) Lacy's Express Inc.  has agreed to provide
                transportation, They are experienced and licensed
                in these matters.
             d) history of proven experience
             e) can complete remediation within 11  months

   The cost we propose including freight is $2,690,000.  This cost is 107. higher
   than your recommendation, however the material will no longer remain on site.

        We would also be interested in materials from building, demolition, sand
   blasting or sediments.  The building components  would have to be estimated
   depending on the scope of the demolition.

-------
Mr. Michael Gilbertson
Page Two
September 5, 1991


Also,  the Proposed  Plan  requires  the  placement of  stabilized
naterials in a  RCRA  Subtitle  D landfill.   We are concerned about
the consistency of this requirement with any remedy prescribed for
Operable Unit I at a later date.  If other materials at the site
aust be placed  in a  landfill,  it  may be  uneconomical to design a
separate landfill at a later time.  Consequently, we request that
U.S. EPA include in its Record of Decision provisions which allow
the party conducting the remedial  action the option of storing the
stabilized material  in the interim or designing a landfill which
will accommodate all site materials.   Since the Record of Decision
on Operable Unit I is expected next year, well before the remedial
design for Operable Unit XI is completed, allowing either interim
storage or proper sizing of the landfill as alternatives will help
to assure that  the remedy is  cost-effective  without creating any
long-term problems.

with.respect to the ponded stormwater, we have obtained estimates
which indicate that one million gallons of water could be treated
on-site in a rental unit for less  than $100,000.  Also, while off-
site  disposal  costs may be  considerably  less that  U.S.  EPA
estimated, they are expected to be significantly greater than the
rental unit cost.  U.S. EPA determined that both remedies satisfy
NCP criteria,  but hypothesized that off-site disposal  would be
cheaper  (a  questionable conclusion).  We propose that  U.S.  EPA
permit whoever  performs the remedial  action to choose  the more
cost-effective alternative.

Also,  we request that U.S.- EPA permit  whoever performs the remedial
action to  use  ponded stormwater in the  stabilization  process.
There is no point in using clean water.  Furthermore, in the event
on-site treatment of the ponded stormwater  is utilized, we request
that  U.S.  EPA  permit  the use of  treated  water  for  building
decontamination and cleaning to lessen the  amount of treated watez
which must be discharged.

Thank you for the opportunity to submit these comments.

Very truly yours,

JOHNSON CONTROLS, INC.
Jean M. Beaudoin
Manager, Environmental Relations

-------
ce:  AT&T
     Allied-Signal
     C&D Charter Power Systems
     Exide Corp.
     Could Inc.

-------
Mr. Michael H. Gilbert                                   Page Five

          feas consideration been given to the potential future need
          to reclean the facility if subsequent remedial activities
          at the cite result in recontamination of surfaces?  Has
          adequate consideration been given to possible recycling
          of dust,  lead dross, scrap metal,  and  other materials
          which nay be generated from these activities?

     2.   Alternative CS-2  notes  that "debris that  could  not be
          decontaminated, such as contaminated baghouse bags, along
          with  collected   dust,  would   be  transported  to  an
          appropriate off-site RCRA hazardous waste treatment and
          disposal  facility".   Exide  Corporation believes  that
          baghouse dusts, as well as baghouse bags  from a secondary
          lead  smelter,  are  classified  as  K069 listed  wastes
          pursuant   to   EPA   regulations  under  the   Resource
          Conservation  and  Recovery Act.  The EPA land disposal
          restrictions prohibit the disposal of these types of
          materials and mandate thermal recovery  (i.e., secondary
          lead smelting).  EPA's proposed plan with respect to the
          disposal of baghouse dusts and baghouse bags,  therefore,
          is a violation of RCRA.


     Exide  Corporation   appreciates  the  opportunity to  provide
comments on EPA's proposed early remedial action plan and also on
your letters which had  previously been  submitted  to this office.
In addition, Exide Corporation  looks forward  to the reopening of
discussions with EPA personnel regarding the potential recycling of
materials from the site at  the Exide/General  Battery Corporation
facility in Reading,  Pennsylvania or at other authorized secondary
lead recycling facilities.


     Should additional information or clarification be required or
should you wish to discuss  this matter  in further detail,  please
contact this office at  (215) 378-0852.

                              Very truly yours,

                              EXIDE CORPORATION
                              teffrly A. Leed
                              Director - Environmental Resources
JALrsb

-------
                                      Johnson Controls. Inc.
                                      Batttry Group
                                      5757 N. Grten Bay Avenue
                                      Post Office Box 591
                                      Milwaukee. Wl 53201-0591
                                      Tel. 414/228 1200

                             VIA P1DBRAL BXPBZ8S


                             Michael H. Gilbert, Project Manager
  • X-M  IN'I/-N^NK i             United States Environmental
JOHNSON             .  Protection Agency
                             Region
^V\\ rrriMi O                    Region 11
CJL/N I KS'LO                    Jacob K. Javits Federal Building
                                     New York, New York 10278

                                     September 5, 1991

       Re:  NL Industrie* Superfund Site
            Pedricktovn, New Jersey

    •  Dear Mr. Gilbert:

       We are corresponding on behalf of AT&T, Allied-Signal, CtD Charter
       Power Systems, Exide Corp.,  Gould Inc., and Johnson Controls, with
       comments regarding the Proposed Plan for Operable Unit ZZ at the  NL
       Zndustries/NSNJ  Superfund Site  in  Pedricktown,  New Jersey.   By
       submitting these comments, the parties sake no admission regarding
       liability  for response  actions and  specifically deny all such
       liability.  The remedy proposed by the United States Environmental
       Protection Agency ("U.S. EPA") for Operable Unit ZZ includes three
       major  components:   stabilization  of slag  and  oxide,  building
       .cleaning, and treatment of ponded stormwater.

       We  are  concerned  with  sequencing  of   the  remedy  components.
       Sequencing should assure that any further stormwater which falls  at
       the site  remains clean.   The slag and oxide  should be  addressed
       first so that handling of these materials does not result in any
       hazardous substances which may be present at the site migrating  to
       already cleaned  areas.  The buildings should  be addressed next,
       with water treatment beginning for each building as any  wash water
       is generated and in turn for the ponded water around each building,
       with  immediate  cleaning  of  the  underlying  areas   so  future
       stormwater remains clean.

       Our next concern is the choice of remedy for the slag and/or oxide.
       U.S. EPA apparently agrees that recycling is an appropriate remedy,
       but elected stabilization and on-site disposal in its Proposed Plan
       because  it could  not  find a  recycling  vendor.   However, our
       conversations  with  recyclers  indicate  that  U.S.  EPA  may   be
       incorrect in dispensing with the recyling  option.  Also,  U.S. EPA
       did not explore  the  possibility that recyclers could be  paid for
       their  efforts   at   a   rate  considerably  less  than  that for
       stabilization and disposal. Accordingly,  we request that U.S. EPA
       identify alternate remedies (recycling and the remedy set forth  in
       the Proposed  Plan)  in its Record  of Decision so .that  whoever
       undertakes the remedial action can choose  between them  during the
       remedial design phase according  to relative cost-effectiveness.

-------
Mr. Michael H. Gilbert                                  Pase Three
     3.   ^s you nay also know, Exide Corporation  and  the Center
          for  Hazardous Materials  Research (CHMR) , Pittsburgh,
          Pennsylvania,  have  recently  received  authorization,
          through the  EPA SITE Emerging Technology Program,  to
          investigate the potential for  utilizing  secondary lead
          smelters for the recovery of lead from materials removed
          from Superfund sites.  As part of the effort  with CHMR,
          it   is  anticipated   that  the  Exide/GBC   Reading,
          Pennsylvania facility will be utilized to investigate the
          recovery of lead from a diverse variety of materials.

          Exide  Corporation  has recently  received authorization
          from EFA Region III for the removal of five  loads of
          battery case materials  from  the Tonolli Corporation
          Superfund cite in Nesguehoning,  Pennsylvania, an activity
          which has been scheduled to begin on September 5, 1991.
          The test of the Tonolli materials represents the first
          actual test  which  Exide/GBC will conduct  of materials
          from an NPL site, despite the fact that the processing of
          materials from the Brown's Battery site and the Hebelka
          site, both in Pennsylvania,  have already been discussed
          with Region III  personnel.  Exide Corporation is willing
          to initiate  further activities  with EPA Region  XI to
          determine the feasibility of recycling materials from the
          NL Pedricktown site.


     With respect to the  information  in your  letter of  July 16,
1991 regarding  the  proposed plan for  early remedial  action for
operable unit two at  the NL Pedricktown  site,  Exide Corporation
provides the following comments:


     STANDING WATER AND SEDIMENTS

     1.   If treatability studies have not been conducted as noted
          in the discussion of alternative SW-2, Exide Corporation
          questions whether EPA has considered all available and
          appropriate  options for  treatment  and  management  of
          standing  water  and  wastewater.    Have,  options  for
          treatment  of  water  been  considered  with  possible
         —discharge into the  sanitary sewer in lieu of groundwater
          recharge?  (Table €-1 of the June 8,  1990 Final Removal
          Action/Feasibility  Study  Report prepared  by  Roy  F.
          West on,  Inc.  suggests  the   option  of  local  sewer
          discharge) .    Have  potential options for recycling of
          contaminated sludges and sediments been considered?

-------
Mr. Michael B. Gilbert                                  Page Four

     SIAC'AND LEAD OXIDE PILES


    . 1.   Exide Corporation does not  understand EPA's basis far
          comparing lead levels in  slag to EPA's Interim Guidance
          on Establishing Soil Lead Clean-up Levels in residential
          soils at Superfund Sites.

     2. .-'While EPA has  considered treatment options such as flame
          reaction,    hydrometallurgical     leaching,    and
          solidification/stabilization (options SP-3, SP-4, and SP-
          5, respectively) for the  slag and lead oxide, recycling
          through a secondary lead smelter has  not been fully
          considered.   As noted in the discussion above, Exide
          Corporation believes that, because of the lead content  in
          these materials,  some of them may  be recyclable and
          further consideration of  this option  is warranted.

     3.   As  noted  in  the  EPA  third-third  land  disposal
          restrictions published in the Federal Register on June. 1,
          1990,  the U.S.  EPA has acknowledged that inorganic solid
          debris  which  exhibits   a  toxicity   characteristic
          represents a unique treatability group of materials due
          to the inherent difficulties  in stabilizing these  wastes.
          In fact,  the Agency recognized the inherent difficulties
          associated with stabilization and subsequently issued a
          National  Capacity  Variance  until May 1992. The  EPA
          statements  and alternative  SP-5 which  indicate  that
          "bench-scale tests would be required"  to  evaluate  this
          option,  suggest  that  EPA may  not have considered the
          potential   need  to   process   the    slag   prior    to
          stabilization,  to  control  dust from this  operation,
          and/or to properly collect and treat wastewater which may
          be generated.   In addition,  the  agency appears  to  have
          selected this  option without bench-scale tests and  thus
          with  little,  if any,  knowledge  about the amount  of
          solidification agents which would be needed to stabilize
          these materials.    Given the  potential  uncertainties
          associated with the feasibility and costs associated  with
          this option, it is suggested that bench-scale tests  be
          conducted to evaluate this option against the potential
          recycling alternative.  Indeed, it may also be necessary
          to perform independent evaluations on the slag and  lead
          oxide as the results of the evaluations may be different.


     DEBRIS AND CONTAMINATED  SURFACES
                                        •
     1.   Exide Corporation questions whether  the EPA has fully
          evaluated  all  options  associated  with   debris  and
          contaminated surfaces and whether all of this  work  is
          required at this time.

-------
         •EXIDE CORPORATION
AIRBORNE-EXPRESS- RETURN RECEIPT REQUESTED
                              September 5,  1991


Mr. Michael H. Gilbert
Project Manager
Southern New Jersey Compliance Section
U.S. Environmental Protection Agency
Region XI
Jacob K. Javits Federal Building
New York, NY  10278

     RE:  NL Industries, Inc. Site
          Pedricktown, New Jersey

Dear Mr. Gilbert:

     Exide  Corporation  is  in receipt  of  your  letters  dated
September 24, 1990 and  January 24,  1991 which  provide  analytical
information  regarding  materials  which  are  stored  at  the NL
Industries, Inc.  site in Pedricktown,  New Jersey.  In addition,
Exide Corporation has also received your letter of July 16,  1991
which summarizes  the  options which  EPA has considered  for  early
remedial action at the site and which also documents EPA's proposed
plan for addressing several areas of surface contamination.

     At  the  outset  of  our  response  to  your  letters,  Exide
Corporation  wishes   to  advise  your  office  that   Exide  is
participating  with  a number  of  other companies who are  also
intending to provide additional comments -to your office about EPA's
proposed early remedial  plan.  Exide  Corporation's comments in this
letter,  therefore,  should., be  viewed  as   a  supplement  to the
information in  that  letter.    In  this letter,  Exide Corporation
intends  to  focus specifically on several  portions of  the  early
remedial plan  and the  potential  for  secondary lead smelters to
reclaim  materials from  the NL site.   Exide Corporation  has not
responded to your earlier  letters due to the previous  litigation
with NL  regarding the Pedricktown site and  due to other on-going
efforts at other former NL facilities throughout the United States.

     Exide submits these comments, and is participating with other
parties  in  the submission of joint comments,  because it has  a
general interest in seeing that all  proposed response actions, as
identified by EPA at this and other sites,  are protective of human
health and the environment while remaining  cost affective.  Exide
also has a direct interest in the remedy for this site because EPA
may consider  using  Exide  secondary  lead  smelter facilities for
managing the  waste  material  at the site.    Exide has  also  been
identified  by EPA as  a  potentially  responsible  party.    Exide
specifically denies any and all liability for response actions at
                       §45>tnn Strttt  Rodin* »A 19601
                      P.O. Box1420S  RudiniPA 1M124205
               216/37*0500 TWX 810/651-S2M Ttlwopfer 216/37*0616

-------
Mr. Michael H. Gilbert                                   Page Two

the cite and reserves all available rights and privileges that nay
be asserted in defense of any allegations of such liability.


     with respect to the information contained in your letters  of
September 24, 1990 and January 24,  1991,  Exide Corporation wishes
to provide the following comments:

     1.   The lead concentrations in some of the on-site materials
          are sufficiently high to allow for  consideration to  be
          given to  the recycling  of some  of these aaterials  at
          secondary lead smelters.   A listing of secondary lead
          smelters in the United States is attached.

     2.   The  Exide/General  Battery  Corporation  facility   in
          Reading, Pennsylvania is  a RCRA permitted treatment and
          storage   facility,   permitted  under   U.S.  EPA  ID#
          PAD990753089 by the U.S. Environmental Protection Agency
          and  the   Pennsylvania   Department  of  Environmental
          Resources in November 1988.   In addition, the Exide/GBC
          Reading   facility   also   operates  under   appropriate
          authorizations  and  permits  for   air  emissions  and
          discharge of treated wastewater.   Additional analytical
          information would be needed for Exide/GBC to evaluate the
          feasibility of recycling these materials and to evaluate
          the costs associated with this activity.  Other details
          related to packaging  of  the  materials at the  NL site,
          loading, and transportation would also need  to be known
          before the costs could be assessed.

          Exide understood  that the  previous  EPA  requests for
          "utilization" of the NL materials were based on the need
          for Exide to load and transport the materials, to pay the
          costs for.recycling the materials, and to pay the costs
          for  disposal of  byproducts  generated  from  recycling
          operations.  Under this scenario, this office  does not
          believe  that recycling  would have been economically
          viable  to Exide Corporation.    It  EPA is  willing  to
          reimburse Exide to help defray our  recycling expenses,
          Exide Corporation  is  willing to  discuss  this  matter.
          Exide believes that recycling is an option which will  be
          more environmentally  acceptable and  less  costly than
          stabilization with long term  storage or disposal.

          Page 1-5 of the EPA Focused Feasibility Study indicates
          that EPA made several  inquiries to parties that nay have
          been interested in removing the slag for recycling and
          that "...no positive responses were  received, primarily
          due to the low lead content of the  slag and lead oxide
          piles."   In Exide Corporation's  case,  this is  not  an
          accurate statement.

-------
                 UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                             JACOB K. JAVITS rcoEKAu BUILDING

                               NEW YORK. NEW VOMK 1O270
       EPA EXTENDS PUBLIC COMMENT PERIOD FOR THE NL INDUSTRIES SUPERFUND
       SITE IN PEDRICKTOWN  . NEW JERSEY

       The U.S. Environmental Protection Agency (EPA) has extended the
       public comment period for the NL Industries Superfund Site in
       Pedricktown, New Jersey to Friday , September 6, 1991. Copies of
       the Proposed Plan, which discusses the preferred  remedial
       alternative, as well as copies of the Focused Feasibility Study
       can be reviewed at :

       Penns Grove Public Library
       South Broad Street
       Penns Grove, New Jersey 08069

       All written comments on Proposed Plan nay be cent to Michael
       Gilbert, Remedial Project Manager, U.S. Environmental Protection
       Agency , Emergency & Remedial Response Division, 26 Federal
       Plaza, Room 720 , New York, New York 10278

       For additional information please contact Yvette Harris,
       Community Relations Coordinator at 212 264-9368
MtlMTID ON MCCrCUCD PAPI*

-------
                    Appendix B
       VL Industries, Inc. Written Consents
on the Proposed Plan and Focused Feasibility Study

-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                  REGION ZI
               PUBLIC MEETING
                     POR
        NL INDUSTRIES  CUERFUND SITE
               PEDRICXTOTO, HEW JERSEY

               AUGUST «, lt*l
              MEETING ATTENDEES
                (Please Print)
NAME
STREET
CITY
ZIP
                           PHONE    REPRESENTING

-------
                        UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                                        REGION ZI
                                      PUBLIC MEETING
                                           TOR
                                NL INDUSTRIES  SUERPUND SITE
                                      PEDRICKTOWN, «W JERSEY

                                      AUGUST «,  1ftI
                                     MEETING ATTENDEES
                                      (Plus* Print)
                               CITY
SIP
PHONE     REPRESENTING
^~.££faftfi*z^-(fa^ &J .  ..*Safcr... zts-n&^zr^tf'*'
    '       f     .. _     .        •'                               C

-------
                                       14
SLAG & LEAD OXIDE PILES
SP-5:Solidification/Stabllizatlon/On-
Site Disposal

SURFACES AND DEBRIS
CS-2:Decon tarn I nation/Off-Site
Treatment and Disposal

STANDING WATER
SW-3:Off-Site Treatment and Disposal

The  preferred   alternatives  represent
the  best balance  of  trade-offs among
the  criteria   used  to evaluate  remedial
actions.    Based   on  the  information
available  at  this   time,  the  preferred
alternatives  would  be  more  protective
than   competing   alternatives,  attain
ARARs, be cost-effective  and would use
permanent   and   complete  treatment
technologies  to  the   maximum  extent
possible.
                     First, the slag and  toad  oxide piles, in
                     addition to similar  materials,  would  be
                     treated  using  the  solidification/
                     stabilization   technology.
                     Concurrently,  buildings,  paved
                     surfaces, equipment  and debris would be
                     decontaminated.    Subsequently,  the
                     contaminated  standing  water  and water
                     used for decontamination of  buildings,
                     etc.,  would   be  collected   and
                     transported  for  off-site  treatment  and
                     disposal.     Finally,   drains  would   be
                     decontaminated and  unplugged. Through
                     this sequence,  the  sources   of
                     contaminated   runoff would  be
                     eliminated  and  water  from  future  rain
                     events  would  drain through these areas
                     without   transporting  contamination   off
                     she.
                  SUMMARY OF THE PREFERRED ALTERNATIVES
Remedial
Alternative
Present Worth   Months to Achieve
Cost ($1000)    Remedial Objectives
Comments
SLAG & LEAD CKJDE PILES     f 2£03
(SM:SoWificalion/
Stabilization/OrvSite
Disposal)

SURFACES AND DEBRIS       $ 1,691
(CS-2:Decontamination/
Off-Site Treatment and
Disposal)

STANDING WATER            $ 8632
(SVW:Off-Slte Treatment
and Disposal)
               FlftMn
               Twelve
               (can be concurrent
               w/ARemative SP«)
              Six
Protective, reduces
mobility and exposure to
todofr readily Implemented.
cost^ffective

Picitecilve, reduces
toxioty mobility,
and volume, readBy
implemented, permanent

Protective, reduces
toxic** mobfflty and
                                                              permanent
ESTIMATED TOUL
  $4,987

-------
f
V
I      UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

*                          REGIONII

                   JACOB K. JAVITS rtOEMAL BUILDING               ,"i

                     NEW YORK. NEW YORK 1O278
                                       From Th»

                 U.S. ZnvironjMAtal Protection Mgmney

                        • lovitm You To Attend

                           A Public Mmmtlny
Purpose:  To discuss the activities at the KL Industries Supertund
          Site

Date:  Tuesday,  August 6, 1991

Tine:  7pa      ;

Place: Oldsman Middle School, Freed Road, Pedricktovn,  NJ  .

For further information please contact Yvette Sarris, Commmity
Delations Coordinator at (212) 264-9368.
   «IC»C.t: »*»t»

-------
                                       12
placed   in   accordance  with  RCRA
treatment  standards  to  alleviate   this
concern.    The  technology  Is  widely
available,   proven   affective   for
inorganics,  cost-effective  and  readily
implemerrtable.

Alternatives  SP-3 and  SP-4  would be
effective in the long and  short term in
protecting   human  health   and   the
environment   and  would  result   In a
reduction   of  toxicity,  mobility   and
volume of the slag and lead  oxide piles.
However,   these  alternatives   have  not
been  utilized  at Superfund  sites   and
are more  expensive than Alternative  SP-
5.     Furthermore,  Alternative   SP-3,
which  involves  a   flame  reactor,  Is
considered  an  innovative  technology
and  implementability on  a  commercial
scale has not been proven. Markets have
not  been   identified  for  the  process
byproducts   associated  with  this
alternative;  this  may  further Increase
costs.   Alternative  SP-4, which uses a
hydro-metallurgical   leaching  process,
may require  a series of steps to leach
multiple   contaminants.     This
alternative  would  also  produce  a  slag
and  lead  oxide  residue  which  would
require  disposal,  in addition  to large
amounts   of   liquid  wastes  generated
during the process.

Given  the  site  conditions,
solidification/stabilization  offers
the greatest  certainty  for treating  the
slag  and  lead  oxide  piles.
Accordingly,  RCRA  treatment standards
should  be   readily  achievable  after
treatment  has  immobilized  the  waste
materials.

Occupational   Safety  and  Health
Administration (OSHA) Standards, RCRA
Land Disposal Restrictions  (LDR), RCRA
Subtitle  D  Nonhazardous   Waste
Management  Standards  and  RCRA
Identification  of   Hazardous   Waste,
which defines  the  TCLP to  characterize
a waste as being hazardous, are  ARARS
which apply to,  and would  be  met by,
Alternative*  SP-3,   SP-4    and   SP-5.
Department  of   Transportation   POT)
Rules  for   Hazardous  Materials
Transport  and  RCRA Requirements for
Transporting   Waste  for  Off-site
Disposal  would  apply and  be  met by
Alternative   SP-3.     Alternative   SP-5
would comply with 40 CFR 264, Subpart X,
which  provides  standards  that  are
applicable  to  the   on-site
solidification/stabilization  of
contaminated waste.
CONTAMINATED  SURFACES  AND
DEBRIS

Alternative  CS-2,   decontamination   of
contaminated  surfaces  and debris with
off-site treatment  and  disposal  is  the
only  alternative   which  would  satisfy
the criteria.  It would be permanent and
effective  in  protecting  human   health
and  the  environment, completely reduce
mobility,  toxicity  and  volume  of  the
contamination  at  the  site,   and  be
readily implementable.    ARARS  which
apply to, and  would be  met  by, this
alternative are  OSHA  Standards,  DOT
Rules  for  Hazardous Materials
Transport, and  RCRA Requirements for
Transporting  Waste   for   Off-site
Disposal.

Short-term  risks  associated  with  dust
emissions and  accidents  would  exist,
but  could  be  mitigated  by  protective
equipment  and  adherence  to  the site-
specific health and  safety  plan.   Long-
term  reliable  protection would  be
achieved  by removing the  material  from
the site.   There would  be no operation
and   maintenance  costs  for  this
alternative.

-------
                                        13
 STANDING WATER

 Alternative  SW-3,   which  Involve  off-
 site ' treatment   and   disposal   of
 contaminated   standing  water ' and
 sediments, would   eliminate  the  future
 threat  of  orvsite exposure  and  off-site
 contaminant  migration.    It  would  be
 permanent ' and affective In  protecting
 human  health  and  the  anvironment,
 comply with  ARARs,  completely  reduce
 mobility,  toxicty  and  volume  of  the
 contaminated   water  and  be   readily
 Implementable.   For  the  estimated one
 million  gallons  of  standing  water,  tt
 would  be  the  more  cost-effective than
 Alternative  SW-2.   There would  be  no
 operation   and  maintenance  costs  for
 this alternative.

 Alternative  SW-2,   which  Involves  on-
 slte  treatment  followed  by  groundwater
 recharge,  would also be affective and
 permanent in  protecting  human  health
 and  the  environment   It would  reduce
 the  toxicity,  mobility  and  volume   of
 contamination  through   treatment   to
 required  Federal  and  State  discharge
 standards.

 Short-term  risks    associated  with
 operation  of the treatment system could
 be  mitigated  by  protective  equipment
 and   adherence  to  the  site-specific
 health  and  safety  plan.    Long-term
 reliable  protection   would be  achieved
 by removing the contaminated water from
the site.

Alternative  SW-2,  would  require  more
time  to implement than  Alternative SW-3
and be more  costly,  while being  no more
effective  In  meeting   remedial
objectives.     Alternative  SW-2  would
require time  to conduct a treatabil'rty
study  to   define   the  design and
operating  parameters  of  the  treatment
process, and  design and set  up an on-
alte   treatment  facility   to  meet   the
atringent  treatment  (avals   rac   red
for groundwater recharpa.

OSHA Standards are ARARs that would be
mat  by both Alternatives SW-2 and SW-3.
All  Fadaral  and   State  atandards
applicable  for   recharge  of  treated
wastewater to groundwater would apply
and   be   met  by   Alternative  SW-2.
Alternative  SW-3,  which  Involves   off-
alte  treatment  and disposal, would meet
DOT  Rules   for  Hazardous  .Materials
Transport  and  RCRA  Requirements  tor
Transporting  Waste  for   Off-site
Disposal.  The shipment of contaminated
water  containing   hazardous
constituents  to   an  off-site   treatment
and  disposal  facility   would   be
consistent  with  EFAfc policy to  ensure
that   the  facility   Is   authorized  to
accept such material  in compliance with
RCRA operating standards.
SUMMARY  OF  THE   PREFERRED
ALTERNATIVE

The  evaluation  of  the  alternatives  In
the previous  section discussed each  of
the  alternatives  relative   to.  criteria
established under the Superfund law and
regulations.   The  Intent  of  the  Early
Remedial  Action  Is  to remediate  those
areas  of  the  alte  that   require  an
expedited response,  and  to  implement
remedial  actions  that  will  be
consistent with  the final  remedy at the
aita.

After  careful   consideration  of  all
reasonable alternatives,   EFA  proposes
utilizing   the  following   alternatives
for the Early  Remedial Action at the  NL
alte:

-------
                                       10
 Alternative SW4: Off-Site Treatment and
 Disposal
 Capital Cost
 Annual O&M Costs:
 Present Worth Cost
$993,200
      $0
 Months  to  Achieve   Remedial  Action
 Objectives:                        Six

 This   alternative   would  consist  of
 collecting  approximately   one  million
 gallons  of  standing  water  in
 approximately  200  tanker  trucks  and
 transporting tt  to  an  off-site, RCRA-
 permitted   treatment  facility, which
 would  be capable of accepting the  water
 with no  pretreatment at the site.   Wash
 water,  which would be generated  from
 the  decontamination   of   contaminated
 surfaces   and   debris,  would   also  be
 transported  with  'the  standing  water.
 Sediments  would  be  transported to  an
 off-site   treatment  and  disposal
 facility  that  would  be   capable  of
 accepting  this  material.    Samples  of
 the contaminated water and sediments
 would   be sent   to  the  treatment
 facilities  to ensu.v  waste  acceptance.
 As  part   of  this   alternative, drains
 would  be unplugged and cleaned, which
 in  conjunction   with   the
 decontamination of  buildings and  paved
 surfaces,   would  prevent   contaminated
 runoff  from  leaving  the   site  in  the
 future.

 EVALUATION OF ALTERNATIVES

 The  nine  criteria used  to  evaluate  all
 remedial   alternatives  fall into  four
 categories:  environmental/public
 health  protectiveness,   compliance  with
 required  cleanup  standards,   technical
 performance and cost   In addition, the
 selected,  remedy  should  result  in
 permanent  solutions  and  should   use
treatment  to   the  maximum  extent
 practicable.     This   section  discusses
 and compares the performance of the
 remedial   alternatives  under
 consideration  for  each  source  against
 these  criteria.    The  nine  criteria are
 summarized below:

 Overall Protection of Human Health and
 Environment addresses whether or  not a
 remedy  provides  adequate  protection
 and describes how risks posed through
 each pathway  are  eliminated,  reduced,
 or  controlled  through  treatment,
 engineering  controls,  or  institutional
 controls.

 Compliance with Applicable or Relevant
 and Appropriate Requirements (ARARs)
 addresses whether or not a remedy will
 meet all  of the applicable or relevant
 and   appropriate  requirements  of
 Federal  and  State   environmental
 statutes  and/or  provide  grounds  for
 invoking a waiver.

 Long-term Effectiveness and Permanence
 refers  to  the  magnitude  of residual
 risk and  the ability  of  a  remedy to
 maintain  reliable  protection  of  human
 health  and  the  environment over  time
 once remedial objectives have  been met

.Reduction of Toxlclty, Mobility, or volume
 Through  Treatment  is  the anticipated
 performance  of  tha   disposal  or
 treatment  technologies   that  may  be
 employed in a remedy.

 Short-term  Effectiveness refers  to the
 speed  with  which the remedy  achieves
 protection,  as wen   as  the  remedy*
 potential to  create adverse  impacts  on
 human  health and the environment that
 may result during  the construction and
 implementation period.

 Implementablllty  Is the  technical   and
 administrative  feasibility  of   a

-------
                                       11
 remedy,   including  the   availability  of
 materials   and   services  needed  to
 Implement the chosen solution.

 Cost  refers  to  estimates   used  to
 compare  costs  among  various
 alternatives.     Costs  include  both
 capital and operation  and maintenance
 costs.  Cost comparisons are made on the
 basis of  the  present worth value, of the
 entire  cost of  the  alternative,  at the
 beginning of construction.

 State Acceptance will be assessed in the
 Record  of Decision  following a review
 of the States comments received on the
 FFS report and the Proposed  Plan.  The
 NJDEP concurs with the proposed remedy.

 Community Acceptance will be assessed
 In the Record of Decision following  a
 review  of  the  public  comments received
 on the FFS report and the Proposed Plan.

 NO ACTION

 The  No  Action  alternatives SP-1, CS-1,
 and  SW-1  would not  provide  protection
 of public  health or the environment or
 any  effective  remediation   in  the  long
 or  short  term.    Contaminants  would
 remain  in  their  present state,  with
 little  or   no  reduction  in  toxidty,
 mobility  or  volume.     Potential  risks
 due  to exposure  to  and migration  of
 contaminants  would  remain.   The No
 Action  alternatives  are the simplest  to
 implement  from  a technical  standpoint,
 since  they  only  involve actions  to
 inspect   and   sample  the  site
 periodically,   ensure  restricted  site
 access,   and  continue   to  provide
 information  about  the   site  to  the
surrounding community.

Since the  No Action  alternatives SP-1,
CS-1 and SW-1 would not be protective of
human health and  the environment  or
comply wtth ARARs, they  are eliminated
from   further  consideration  for  the
preferred alternatives.

SLAG AND LEAD CDQDE PILES

Alternative  SP-5,  which  involves
solidification/stabilization  of  the
slag and  toad  oxide  plies, would  be
effective  and  permanent  In reducing
risks   to  human  health  and  the
environment      Materials  of   similar
composition to  the slag and lead oxide,
such  as certain toad feedstocks, would
be  treated   with  these   materials.
Solidification/stabilization  would  be
relatively simple, to  implement,  since
a one-step  mixing and placement  process
is  used.   This  alternative  would treat
these wastes  to be nonhazardous, which
would  be  ensured by  testing according
totheTCLP.

The treated material would be placed on
site in accordance with RCRA treatment
standards.     For  cost-estimating
purposes,  It was  assumed that  the on-
site placement would meet RCRA  Subtitle
D  requirements,   although  the   actual
disposal requirements would be  defined
in  design,   pending  treatability
studies.    Toxicity  of  the  hazardous
constituents of  the materials would  be
reduced   in   that  they   would   be
immobilized in  the  stabilized mass  and
no  longer  present  a  direct   contact
threat   Mobility would  also  be  reduced
and volume  may increase  up   to  40
percent  depending  upon  the   specific
treatment process.  Although some long-
term   uncertainties  regarding  the
integrity of the  stabilized  mass  have
been   raised,  solidification/
stabilization  is  preferable  for
treating   inorganic  contamination   and
will inhibit  teaching  of  contaminants.
Furthermore,  efficacy  testing  will   be
conducted  and the  material will   be

-------
                                       8
lead-rich,   potentially   marketable
product   The  caustic leaching solution
woulrf  be recycled through the process.
The  resulting  treated  material  would
require  testing  according  to the TCLP
to   confirm  that  the   material  is
nonhazardous.    There would be  no
significant reduction  In volume  of the
material.    The  treated material  would
be  redeposited  on  site  In accordance
with   Resource  Conservation  and
Recovery  Act   (RCRA)  treatment
standards.    For  costing   purposes,  ft
was assumed  that   on-site  placement
would  meet RCRA  Subtitle D  landfill
requirements.

Alternative  SP-5:On-Slte
Solidification/Stabilization/
On-site Disposal
Capital Cost
Annual O&M Costs:
Present Worth Cost
$2,014,000
  $17,000
$2,303,100
Months  to  Achieve   Remedial   Action
Objectives:                      Fifteen

This  alternative  would   stabilize  the
existing waste on site  by  using a mobile
treatment   system.     This  technology
immobilizes  contaminants  by  binding
them   Into  an  insoluble   matrix.
Stabilizing  agents  such   as   cement,
pozzolan,   silicates  and/or  proprietary
polymers would be mixed with the feed
material.   The  equipment is similar to
that   used  for  cement   mixing   and
handling.   Bench-scale tests would  be
required  to select the  proper  quantity
of  stabilizing   agents,  feed  material,
and  water.   Depending on the specific
treatment  process,   the  stabilized
volume may increase up to 40 percent of
the  original  volume.     The  stabilized
material  would  require  testing
according  to  the TCLP to confirm  that
the material is  nonhazardous.  Disposal
               of the treated material would  occur  on
               site in accordance with  RCRA treatment
               standards.    For costing  purposes,  It
               was   assumed  that  on-slte  placement
               would  meet  RCRA  Subtitle   D  landfill
               requirements.
Debris and Contaminated Surfaces

Alternative CS-1: No Action

Capital Cost                   $17,700
Annual O&M Costs:              $6,800
Present Worth Cost            $136,000

Months  to  Achieve  Remedial  Action
Objectives:                        N/A

The   No  Action  alternative   for
contaminated   surfaces  and   debris
provides  a  baseline against which other
alternatives   may  be   compared.
Contaminated  debris,  equipment  and
surfaces  would be  left  in  their  current
condition.   Roofs  would  be  repaired
where   necessary  and   a  long-term
maintenance  program   would  be
implemented   to  ensure   that   the
buildings  are  not  accessible.     In
addition,  assessments   would  be
performed every  five  years to determine
the need for further actions.

Alternative CS-2:Debrls and Contaminated
Surfaces  Decontamlnatlon/Off-Slte
Treatment and  Disposal
               Capital Cost
               Annual O&M Costs:
               Present Worth Cost
                            $1,691,100
                                  $0
                            $1,691,100
               Months  to  Achieve  Remedial  Action
               Objectives:                      Twelve

               This   alternative   would  Involve
               decontaminating  the   contaminated
               building  surfaces,   debris  (i.e.,  scrap

-------
                                         9
 metal,   pallets,  etc.)  and  equipment
 using  dusting, vacuuming and  wiping
 procedures.   Parts of the buildings and
 surfaces  which  could  withstand high
 water  pressure would be cleaned  by
 hydroblasting.    Materials  would  be
 recycled  where possible.   Debris  that
 could not be decontaminated,  such as
 contaminated baghouse bags,  along with
 collected dust, would be  transported to
 an  appropriate off-site  RCRA  hazardous
 waste  treatinent  and  disposal  facility.
 Contaminated  wash   water  would  be
 treated   with  the  on-site   standing
 water.

 Standing Vteter and Sediments

 Alternative SW-1: No Action

 Capital Cost                        $0
 Annual O&M:                  $10,700
 Present Worth Cost             $220,100
: :••)- •   '• - ,
 Months   to   Achieve   Remedial  Action
 Objectives:                        N/A

 The  No  Action alternative  for .standing
 water provides a baseline  against which
 other alternatives   may  be compared.
 This  alternative would  rely  on natural
 attenuation   of  contaminated   standing
 (rain)  water  without  any  treatment
 Drains   would  remain  plugged  and
 contaminated.   Contaminated   standing
 water would  be  likely to continue  to
 overflow the  site into the  West Stream.
 This  alternative would  Include  annual
 monitoring   of  groundwater,   surface
 waters and soils In and around the site
 to   track contaminant  migration.    In
 addition,  assessments  would  be
 performed every five  years to determine
 the need for further actions.
Alternative SW-2: Ort-SKe Treatment and
Groundwater Recharge
Capital Cost
Annual O&M Costs:
Present Worth Cost
$1.335.000
       $0
$1,335,000
Months  to  Achieve   Remedial  Action
Objectives:                     Fourteen

This   alternative  would  consist  of
collecting   and  treating  approximately
one million gallons  of  standing  water
on   site.     Wash  water,   which  was
generated from  the  decontamination of
contaminated  surfaces  and  debris,
would  also be treated  wtth the standing
water.    The  treatment  process  would
consist  of  precipitation,
clarification,  filtration   and   If
necessary,  Ion  exchange   or  ion
replacement   The  treated water would
be  recharged to  the  groundwater  via
injection  wells   or  Infiltration
basins.     Sediments  and   sludges
generated during the  treatment  process
would  be treated  and  disposed  of  off
site  at a  facility capable of  accepting
these materials.   The  treatment syitem
would  be  designed  to  reduce   metal
concentrations   to   meet  Federal  and
State  discharge   standards.
Treatabiltty  studies  would  be  required
to  define  the  design  and  operating
criteria to  meet the required  standards
for  groundwater  recharge.   As  part of
this  alternative,  drains   would   be
unplugged   and   cleaned,  which  In
conjunction  wtth  the  decontamination
of buildings and paved surfaces, would
prevent  contaminated   runoff   from
leaving the site in the future.

-------
                                         6
 or  through   dermal  contact  it  of
 potential  concern for site  workers  and
 trespassers on the site.

 Debris and Contaminated Surfaces

 The   process   building   walls,   ceiling,
 floors,  structural   members,   piping,
 and equipment are  covered  wtth dust
 The  results   of wipe  tests  indicated
 high   concentrations  of  lead,  iron,
 cadmium, nickel and copper  throughout
 the  building.    Concentrations  of  lead
 ranged  from   0.88   to  552
 micrograms/kg/quarter   meter*.
 Approximately   2500   cubic  yards   of
 contaminated  debris  consisting  of  toad
 dross  and contaminated wooden pallets,
 baghouse bags, scrap  metal  and other
 materials  are   present  throughout  the
 site.    Many   of these  materials  were
 consolidated   In . temporarily   protected
 areas  as part of the most recent  removal
 activity.

 Releases  of  contaminants  to air  may
 occur  from the  migration  of dust due to
 wind   or  activities  at  the  site.   The
 metal  concentrations  in  the  dust  are
 significant and  may  pose a health  risk,
 if  inhaled    by  site  workers   or
 individuals downwind  of the site.  The
 potential  also  exists  for  site  workers,
 trespassers and animals to  be exposed
 to  contaminated dust  through  dermal
 contact or Ingestion.

 Standing Water and Sediments

 It  is   suspected that  the drains   are
 blocked in areas where  standing water
 is  ponded.      It  was  estimated  that
 approximately   one   million  gallons   of
contaminated   standing   water  (i.e.,
accumulated  rainwater)  are present  at
the site.   This water  was tested  and
found  to  have high  concentrations  of
lead and other metals.  Lead and cadmium
concentrations were detected as high as
5,500  ppb  and  560  ppb,  respectively.
The contamination  is  due,  in  part, to
airborne  particulates,   and   rain   that
has contacted  the  slag  and toad oxide
piles  and  other waste  materials.    In
addition,  approximately  200 cubic
yards of  sediments were  estimated to
have accumulated In the standing water.

Given   site  conditions,   accidental
Ingestion  and  dermal   contact   are
potentially  the  most  likely   on-slte
exposure   pathways.     The  potential
receptors  would  likely be  site workers
and area trespassers.

Off-site  contaminant   migration  Is
potentially   a   significant   exposure
pathway from the NL site.  During heavy
rainfall,  the  standing  water
eventually  overflows  the  site  in   the
area   of   the  West   Stream.
Concentrations  of  toad  in  the  stream
were measured as  high  as 206  ppb In
surface  water samples and 26,800 ppm in
stream  sediment samples  taken  in 1990.
The toad concentrations  In  the stream
exceed  the Efft recommended criterion of
1.3 ppb for  protection  of  aquatic life
based on chronic toddty

In  summary,  current  on-  and  off-site
exposures   resulting   from  hazardous
materials present in the  slag and  toad
oxide  piles,  contaminated  surfaces   and
debris   and   standing  water  pose  an
imminent  and   substantial  threat  to
public health and the environment   The
proposed  remedy  will  address these
source   areas  on  an expedited  basis
white the  site-wide RI/FS  continues to
address the  full  nature  and extent of
contaminant migration from the site.

-------
SUMMARY OF ALTERNATIVES
Alternative SP-3: Off-Site Flamt Reactor
The  FFS presents  remedial  aftamathws
to  address  three areas  of **ft?fi'^wf
surface  contamination  at  the  site:
slag and lead oxide piles, debris  and
contaminated  surfaces,  and  standing
water and sediments.  A wide  range of
technologies  were  considered  to
address  the  remedial  objectives   for
each   of   these   areas.     These
technologies were screened on the basis
of  effectiveness,   implementabiUty  and
costs.   Those that were not eliminated
from   consideration   during  screening
were   assembled  into  the   remedial
alternatives  presented below.  The term
•Months  to  Achieve  Remedial  Action
Objectives*   refers 'to  the  amount  of
time it  would  take  to  design, construct
and  complete  the action.   *N/# Implies
that  the 'Months to Achieve Remedial
Action   Objectives*   Is  not  applicable
for the this alternative.

Slag and Lead Oxide Piles

Alternative SP-1: No Action

Capital Cost                        SO
Annual O&M Costs:             $25,000
Present Worth Cost            $439,000

Morths  to   Achieve   Remedial  Action
Objectives:                        N/A

Superfund regulations require that a  No
Action   alternative   be  evaluated  at
every site  to  establish a  baseline  for
comparison.   The No  Action alternative
for the slag and  toad oxide piles would
include annual sampling and  analysis of
groundwater, surface  waters  and  soils'
on and around the site to monitor the
migration   of   contaminants.     In
addition,  assessments   would   be
performed every  five years  to determine
the need for further actions.
Capital Cost
Annual O&M Costs:
Present Worth Cost
$4,215,100
       $0
$4,215,100
Months  to  Achieve   Remedial   Action
Objectives:                    Eighteen

This  alternative   would  include
removing and treating  the slag and  toad
oxide off site  In a flame reactor.   This
Innovative  technology  would  Involve
subjecting the wastes  to very hot  gas
which  reacts   rapidly   to   produce  a
nonhazardous  slag  and  a  recyclable
metal-enriched oxide.    The  volume of
material  would be reduced  10   to 20
percent   The  slag  could   possibly be
recycled  as  fill   material  or  road
aggregate and the metal-enriched oxide
could  be  recycled   by  a  secondary
smelting  facility,   although  at   this
time,  no  markets  have been identified
for these materials.

Alternative  SP-4:On-Slte  Hydro-
Metallurgical Leaching/ On-Slte Disposal
Capital Cost
Annual O&M Costs:
Present Worth Cost
$2,980,400
   $17,000
$3,269,500
Months   to   Achieve   Remedial  Action
Objectives:                      Sixteen

This  alternative  would  treat  the
existing  waste  by  a   hydro-
metallurgical   leaching   process   on
site.    Bench-scale  testing  would  be
required  to  define   design  criteria.
The process, which is widely used In the
metallurgical  industry,  selectively
dissolves toad  and  other heavy  metals
present  in  .the waste  materials.    The
leaching  step  would  be  followed  by
filtration,   residue   collection,  and
precipitation.    The  precipitate  Is  a

-------
 In 1986, NL signed a consent order wtth
 EPA,  whereby NL  assumed  responsibility
 for  conducting   a   Remedial
 Investigation   and   Feasibility  Study
 (RI/FS)   for   the  site  with   EPA
 oversight.   Versions  of  the  Rl report
 were  submitted to  EPA in  April  and
 October 1990, and April 1991.
£COPE AND ROLE OF THE OPERABLE
UNIT

Recognizing the size  and complexity of
the   site,  EPA  is  addressing  its
remediation   in   phases,   or  operable
units.   This  Proposed Plan  addresses
the  remediation  of  several  areas  of
hazardous  surface  contamination  which
EPA has  designated  as  Operable Unit
Two.   These  areas, which include slag
and   lead  oxide  piles,   contaminated
surfaces  and  debris,  and  contaminated
standing   water,  were   found  to  be
significant  and   continual   sources  of
contaminant  migration  from  the  site.
As  a  result,  ERA,  decided  to  address
these areas on an .expedited  basis that
would  be consistent with the long-term
remedy for  the site.    To achieve this
objective,  EFA conducted  a  FFS that
identified   and  evaluated  remedial
alternatives   for  an   .Early  Remedial
Action  which  would continue the  site-
stabilization   and  remediation   efforts
which  were  initiated  under  a Removal
Action.   The  Early  Remedial Action will
prevent   further  releases  of
contaminants from  areas  of  hazardous
surface  contamination   and  can  be
implemented  while  the  site-wide RI/FS
proceeds.

Removal Action Activities

EPA  conducted a multi-phased Removal
Action  at the  site  to  address   several
conditions  that   presented  a  risk to
 public hearth and the environment  EPA
 conducted Phase I of the Removal Action
 In March  and April 19P3 which  consisted
 of  construction  of  «  chain-link  fence
 to  endow the  former  smelting  plant
 and  spraying  or  encapsulation of  the
 on-stte  slag piles.    Encapsulation  of
 the  piles  provided  temporary
 protection  from  wind  and rain erosion
 and contaminant migration.

 In November 1989, EPA began Phase Two of
 the   Removal  Action.     This  phase
 consisted   of  additional   encapsulation
 of  the  slag  piles,  securing   the
 entrances  of  the  contaminated
 buildings,  and  removal of over 40,000
 pounds of the most toxic and reactive
 materials.

 During  March of 1991,  ERA performed
 Phase  III  of  Its  removal activities  at
 the site when damages to  the  perimeter
 fence were repaired and a  new entrance
 gate   was  installed.     In   addition,
 approximately  2,200  empty, rusted  and
 deteriorated   55-gallon   steel  drums
 were  removed  from the site.  All on-slte
 containers, stored in  open  areas  and
 containing  materials   threatening
 release, were emptied and  staged under
 an  existing  covered area at the rear of
 the facility.    Sand/gravel  berms  were
 installed   around  these   materials   to
 deter  the  release  of  hazardous
 substances  from  this  area.    Finally,
 forty-four  55-gallon   drums  containing
 copper wire and cable were  removed from
the  facility and  were  shipped  to  EPA*
 facility In   Edison, New  Jersey.   Theft
 of this  material  has  been the primary
 target of trespassers at the site.

 Operable Unit Ons

 A   site-wide  RI/FS,  which  ERA  has
 designated as  Operable  Unit  One,  Is
 currently   being  performed for  NL   by

-------
 O'Brien &  Gere Engineers, Inc.  This Rl
 is  a comprehensive  study  designed to
 determine  the  nature   and  extent  of
 contamination  on  the  site  and  areas
 adjacent  to  the  aite   in  various
 environmental media  such as  air, soils,
 groundwater,  surface  water  and  stream
 sediments.   The  FS wfll  Identify  and
 evaluate  remedial  action   alternatives
 to  address  contaminant sources  and
 eliminate   potential  long-term   health
 risks.
 SUMMARY OF AREAS OF CONCERN AND
 SITE RISKS

 EPA   conducted   a  baseline  risk
 assessment  to   evaluate   the  potential
 risks  associated  with  conditions  at  the
 site.    The  baseline  risk assessment
 qualitatively   addressed   risks  which
 could  result  from contamination  at  the
 site, If no remedial action were taken.

 Numerous   contamination   sources  of
 hazardous wastes were identified  at the
 site  during  previous   investigations
 conducted by EPA.   High concentrations
 of  lead,  cadmium,  nickel  and  other
 metals have been detected  on site in the
 slag,  standing  water and  dust   Lead
 exposure   causes  noncarci.nogenic
 effects on  the central nervous  system.
 In  addition,  lead  is  considered  a
 probable human carcinogen. Exposure to
 cadmium and nickel has been associated
 with   noncarcinogehlc   effects   via
 ingestion. Cadmium is a probable human
 carcinogen   by   inhalation  based  on
 evidence from human and animal studies.
 Nickel   has  an  'A'   classification,
 denoting a  human  carcinogen,  and is
 carcinogenic by inhalation.

The  exposure   assessment  addressed
three  exposure media  •  the  slag piles,
dust  and  standing  water.    A  brief
description   of   these  areas  follows.
Potentially   exposed   populations,  fate
and transport mechanisms and exposure
routes were identified for each.

Slag and Lead Oxide Piles

Four slag  piles totaling approximately
9300 cubic yards are stored  on site tn
open,  deteriorating  bins  and  on  paved
ground   surfaces.     In   addition,
approximately 200 cubic  yards  of lead
oxide and  similar  materials are  stored
In enclosed  areas.   The slag materials
were sprayed with  an  encapsulant  to
mitigate  releases  of   hazardous
constituents  and contaminant  migration
which would occur from wind and rain
erosion.

High concentrations   of  metals   were
detected   In  the slag and  toad  oxide
piles.  Concentrations of toad detected
were as   high  as 130,000  mg/kg and
480,000 mg/kg in the slag and  toad oxide
piles,   respectively.     These
concentrations   exceeded   the   lead
cleanup range of 500 to 1000 ppm listed
in   EPA's  'Interim  Guidance  on
Establishing  Soil Lead Cleanup  Levels
at   Superfund   Sites.'     In.  addition,
results  of  the  Tcoddty  Characteristic
teachability   Procedure  (TCLP)  indicate
that  the  majority of  piles  tested  are
hazardous based on teachability of toad
and/or cadmium.

Based on  the  level  of contamination
detected   In  the slag and  toad  oxide
piles,  a   qualitative   risk  assessment
Indicates  that  the  potential for
inhalation  of  contaminated   dust  is
considered  significant for  on-slte
workers  and nearby receptors.   Runoff
via  rain  erosion is a mechanism  for
potential  release of  contaminants  into
the environment   In  addition, exposure
via  accidental   ingestion,    inhalation

-------
on new Information or public comments.
Therefore, the  public is encouraged  to
review and  comment  on  all  of  the
alternatives identified herein.
DATES TO REMEMBER

July 17,1991-August 16,1991
Public comment period for Operable Unit
Two Preferred Remedy

Tuesday, August 6,1991
7:00pm-9:00pm
Public Meeting at

Oldmans Middle School
Freed Road
Pedricktown, New Jersey 08067

ER4 solicits  input from  the  community
on the cleanup methods proposed at each
Superfund site.   EPA has  set  a public
comment  period  from  July  17,  1991
through  August  16,  1991 to encourage
public   participation   in  the   selection
process. The comment period includes a
public   meeting  at  which   EPA   will
discuss  the  FFS  and  Proposed  Plan,
answer  questions and  accept  both oral
and written comments.

The   public   meeting for  the  site  is
scheduled from 7:00 pm until 9:00 pm, on
Tuesday, August  6,  1991,  and  will  be
held  at the  Oldmans  Middle  School,
which  is  located on  Freed  Road  in
Pedricktown, New Jersey.

Comments on the  Proposed Plan will be
summarized  and responses provided  in
the Responsiveness Summary section  of
the Record of Decision.   The Record  of
Decision is the  document  that presents
ERA'S   final   selection   for   response
actions.     Written  comments  on  this
Proposed Plan should be sent by dose of
business, August 16,1991, to:
Michael Gilbert, Project Manager
U.S. Environmental Protection Agency
Emergency & Remedial Response Division
26 Federal Plaza, Room 720
New \brk, New Mxk 10278

SITE BACKGROUND
The NL site is an abandoned, secondary
toad  smelting  facility,  situated  on  44
acres  of   land  on  Pennsgrove-
Pedricktown   Road,   in   Pedricktown,
Salem County,  New Jersey.  The site Is
bisected   by  •  railroad,  with
approximately  16  acres  north  of  the
tracks  which  Includes a closed  5.6-acre
landfill.    The  southern  28   acres
contain   the  industrial   area   and
landfill  access  road   (refer  to  site
location  map).     NL  maintains  the
landfill   area  and  operates  the
landfills leachate collection system.

The  West  and East Streams,  parts  of
which  are   intermittent  tributaries   of
the Delaware  River, border  and receive
surface runoff from   the  site..    The
nearest home is less than 1000 feet from
the site and B.F. Goodrich and the Tomah
Division  of  Exxon   are   active
neighboring industrial facilities.

In  1972,   the  facility   began  the
operation  of  recycling  toad from  spent
automotive   batteries.     The   batteries
were  drained  of  sulfuric add,   crushed
and then processed for toad recovery at
the smelting  facility.   The plastic and
rubber waste  materials  resulting  from
the   battery-crushing   operation  were
buried in  the  on-slte  landfill,  along
with slag from the smelting process.

-------
  NL Industries, Inc. Site Location Map .  (Not Drawn  to Scale)
Between 1973 and 1980, NJDEP dted NL
with  46 violations of the State  air and
water  regulations.    Water  pollution
violations  were   directed   toward  the
battery  storage  area  and  the  on-slte
landfill.    NJDEP   conducted   an  air-
monitoring  program   in  1980  that
detected   airborne   quantities of  toad,
cadmium,  antimony  and  ferrous  sulfate
produced  by the smelting  process,  at
levels  exceeding  the  facility's
operating permits.

NL  ceased smelting operations  in  May
1982.  In October 1982, NL entered into
an Administrative  Consent Order (/CO)
with   NJDEP to  conduct  a  remedial
program  to  address   the   site  soils,
paved   areas,  surface  water  runoff,
landfill  and groundwater.   In  December
1982,  the  site  was  placed  on  the
National Priorities Ust

In February 1983, the plant was sold to
National Smelting of  New Jersey (NSNJ)
and  smelting  operations  recommenced.
NSNJ entered into an amended ACO with
NJDEP,  National  Smelting  and  Refining
Company, Inc., which was NSNJfc parent
company, and  NL   The amended ACO
clarified   the   environmental
responsibilities  of NSNJ and NL   NSNJ
ceased  operation in  January  1984, and
filed for bankruptcy in March 1984.

-------
            lpp«adix A

           Proposed Plan
           Public Votie*
  Public M*«ting &tt«adano« 8h««t
Votie* of Public CoBB«nt Bzt«B«ien

-------
 Superfund Propottd Plan
                       NL Industries, Inc.  Site
                            Padricktown, New Jarsay
 Region 2
                        July 1991
 EPA ANNOUNCES PROPOSED PLAN

 This   Proposed  Plan  identifies  the
 preferred   options  for   addressing
 several   areas  of  hazardous   aurfaoe
 contamination   at   the  NL  Industries,
 Inc.  (NL)   site.     In  addition,  the
 Proposed Plan includes  summaries  of
 other  alternatives   evaluated  for  this
 Early   Remedial  Action, designated  as
 Operable Unit Two  for the  t^.z.   This
 document   is  issued  by   she  U.S.
 Environmental  Protection Agency  (EFA),
 the  lead  agency  for alte  activities,
 and The New  Jersey  Department  of
 Environmental  Protection  (NJDEP),  the
 support agency for this project   EPA,
 in  consultation with NJDEP,  will  select
 a  remedy  for  the  site only  after  the
 public comment period has ended and the
 information   submitted  during this  time
 has been reviewed and considered.
THE  COMMUNITY'S   ROLE   IN  THE
SELECTION PROCESS

EPA is  issuing this  Proposed Plan as
part  of   its  public  participation
responsibilities   under  Section  117(a)
of  the   Comprehensive   Environmental
Response,  Compensation,  and Liability
Act of 1980, as amended by the Superfund
Amendments and  Reauthorization  Act of
1986.   This Proposed  Plan summarizes
information  that   can  be   found In
greater   detail   In'  the   Pocused
Feasibility  Study  (FFS)  and   other.
documents  contained   In  the
administrative  record  for  this  site.
EM encourages  the  public  to  review
these  documents  to  gain   a  more
comprehensive  understanding   of  the
alte  and Superfund activities  that  have
bean  conducted  to   data.     The
administrative  record   file   contains
the  information  upon  which   the
selection of  the  response  action  will
be  based.   The  file Is  available at the
following locations:

Panns Grove Public Library
South Broad Street
Panns Grove, New Jersey 08069
(609) 299-9255
Hours:M,W:


      Th,F:


      Sa:
10:00anv1:00pm
 3:00pm-8:00pm

10:00anv1:00pm
 3:00pm-6:00pm

10:00anv1:00pm
            and
U.S. Environmental Protection Agency
Emergency & Remedial Response Division
Division Rle Room
26 Federal Plaza, 29th Floor
New York, New Vbrk 10276
HoursrM-F:
 9:00am-5:00pm
EFA, in consultation  wtth  NJDEP,  may
modify  the  preferred  alternative  or
select  another  response  action
presented  in this  Proposed Plan based

-------
                           20
      /
cost-effective recycling is available, would be recycled.  EPA
also believes that recycling nay be cost competitive for sone
on-site material*, fcincc some facilities with the capability
of recycling these materials are also PRPs for the site.


EXXDEs   "Has  adequate consideration been given  to possible
recycling  of  dust,  lead  dross/  scrap  metal,  and  other
materials which may be generated from these [decontamination]
activities?"

IPX  RESPONSEt    As mentioned previous?y,  any untreated or
treated waste material  for which  protective,  cost-effective
recycling is available  would  be recycled.  Also,  see EPA's
previous discussion and responses concerning recycling.


EXIDE:  "Altentative C8-2 notes that • debris that eould not be
decontaminated such as contaminated baghouse bags, along with
collected dust,  would be  transported  to  an appropriate off-
site RCRA hazardous waste treatment and disposal facility.*

Ezide  Corporation believes that baghouse  dust,  as well mm
baghouse bags from a secondary lead smelter, are classified as
X069  listed wastes pursuant  to EPA  regulations  under the
Resource Conservation and Recovery Act. The EPA land disposal
restrictions prohibit the disposal of these types of materials
and mandate thermal recovery (i.e., secondary lead smelting).
EPA's proposed plan with respect to the disposal of baghouse
dusts and baghouse bags, therefore,  is a violation of RCRA.**

EPA  RESPONSE!    The  commentor  is correct  in stating that
baghouse dusts  and baghouse bags are listed waste (K069).
These materials would be treated in accordance with RCRA Land
Disposal Restrictions and treatment standards and disposed of
accordingly at an appropriate RCRA-permitted facility, using
Best Demonstrated Available Technology (BDAT).  SDAT for K069
waste is thermal recovery of lead in secondary lead smelters.


JOEK80N CONTROLS*  "U.S. EPA apparently agrees that recycling
is  an  appropriate remedy, but elected  stabilization  and
on-site disposal in its Proposed Plan because it  could not
find a recycling vendor.  However, conversations with recycles
indicate that D.8. EPA may be incorrect in dispensing with the
recycling  option.    Also,  U.S.  EPA  did not  explore  the
possibility that recyclers could be paid for their efforts at
a  rate considerably  less  than that  for  stabilisation and
disposal.   Accordingly, we request  that U.S. EPA identify
alternate remedies (recycling  and the  remedy set forth in the
Proposed Plan)  in  its  Record of Decision so that whoever
undertakes the remedial  action can choose between them during

-------
                                21

     the   'remedial    design   phase   according   to   relative
     COSt-effectiveneSS.**

     •PA  RESPONSES    Refer  to  EPA1* previous  discussion  and
     responses concerning recycling.


V.   SEQUENCE OF CONODCTZNO REMEDIAL ACTIVITIES

     JOHNSON CONTROLSs   •me  are concerned vith sequencing of the
     remedy components.  Sequencing should assure that any further
     stormvater vhioh  falls  at the site remains clean.   The slag
     and oxide should be addressed first so that handling of these
     materials does  not result in any hasardous substances which
     may be present at  the site migrating to already cleaned areas.
     The buildings should be addressed next, vith water treatment
     beginning for each building as any wash water is generated and
     in  turn for  the  ponded  water  around  each building,  with
     immediate  cleaning of  the  underlying  areas  so  future
     stormvater remains  clean.**

     EPA RESPONSE:   EPA, as stated in  the Proposed Plan, agrees
     vith  the  sequence  of  the  first  tvo  components.    Dust
     suppression vould be provided during remediation of slag and
     lead  oxide  materials.     Decontamination  of  the  building
: .• 
-------
                           18

the  flag.   Ac a  result, EPA  did not  conduct a  detailed
•valuation  of  potential  options  involving recycling,  and
proceeded with  the evaluation  of  more viable  and  cost-
effective alternatives for the slag material.

Following issuance of the Proposed Plan, however, EPA received
comments  from several companies indicating that they believed
that recycling may be a viable and cost-effective alternative
for  many  of the  materials at the  site.   Two  of  these
companies, which EPA has  named as  PRPs,  indicated that they
are permitted RCRA facilities and have offered to discuss the
feasibility  of  treating materials  from the  NL site at their
facilities.   One of them,  as  discussed below, submitted a
preliminary proposal to treat the slag material.

In  light of  the  comments that  EPA has received  regarding
recycling of site materials, EPA is willing to discuss such
options  further during  design  and implementation  of  the
selected remedy. As recycling would result  in the recovery of
contaminant  resources in  the waste  material, and in  the
permanent removal of materials from the site, EPA would allow
materials to be recycled,  provided  that it could be done in a
protective   and  cost-effective .  manner,    and  could   be
accomplished  in approximately the same time  frame as  the
selected  remedy.


EZZDEt    "Page  1-5  of the  EPA Focused Feasibility  Study
indicates that EPA made several inquiries to parties that may
have been interested in removing the slag  for recycling and
that '...no positive responses were received, primarily due to
the lor lead content of the  slag and lead  oxide piles.•   ia
Exide Corporation's ease,  this is not an accurate statement.1*

EPA RESPONSE!   In a letter to Exide Corp,  dated January 24,
1991, and contained in the Administrative Record, EPA sent an
analysis  and a description of  the  slag  material.    This
followed  a  preliminary slag analysis sent  to Exide  Corp on
September 24, 1990, and a conversation with Mr. Jeff Leed of
Exide Corp,  on  January 23, 1991.  As stated in the  FFS, no
positive responses were received which indicated a willingness
to remove the slag for recycling, prior to the completion of
the FFS and  issuance of the Proposed Plan.


MASTER METALS i  "Master Metals Zne. would like to respond to
the summary  of  Remedial  Alternatives for the slag and lead
oxide material. As  noted  in  previous correspondence,  Master
Metals Inc. is an approved and insured TSD facility for DOOS
and XO69.  We have  several  years  experience  ia treating these
waste streams and the characteristics of these two streams are
identical to material ve  are currently processing.   We have

-------
                           19

examined the characteristics and are capable of handling the
material at our facility.

Z veuld  like  to briefly address the k«y  components  as they
compare to alternative IP-1 8P-J 8P-4 SP-5.  Criteria 1, 2, 4
and  5 would be  stated ae  in your executive summary.   Xn
criteria 3, Master Metals would have a definite advantage as
this is proven technology and  the operation is reliable.  Ill
the  factors  mentioned under  < implementability  for Master
Metals facility are positive.   The factors are as followss

     a) proven technology
     b) no monitoring would .be required after remediation
     c) Laey's Express has agreed to provide transportation.
        They are experienced and licensed in these matters.
     d) history of proven experience
     e) can complete remediation within 11 months.

The  cost we propose including freight is $2,C90.000.   This
cost  is  10% higher than  your recommendation, however  the
material will no longer remain on site.

We would also  be interested in materials from the building
demolition and sand blasting or sediments."

EPA  RESPONSE:  As discussed "above,  EPA would be  willing to
discuss this  or other recycling proposals,  if it could be
demonstrated  that  the  work  would  be  implemented  in  a
protective and cost-effective  manner  and  in a  comparable
period of time as the preferred remedy.


EXIDE:   "The  lead  concentration  in  some  of the  on-site
materials are sufficiently high to allow for consideration to
be given to the recycling of some of  these materials at
secondary lead smelters."

EPA  RESPONSES    Refer  to EPA's  response to the  previous
comment.
EZIDEs "Recycling  through a secondary lead smelter  has not
been fully considered... because of the lead content of these
materials,  some  of  them  may  be  recyclable  and.  further
consideration of this option is warranted.**

EPA RESPONSE! As stated above and on page 1-5 of the TTS, EPA
has made  several  inquiries to parties  that  may have  been
interested in removing  the  slag for  recycling.   No positive
responses were received, primarily due to the low lead content
of the slag  and  lead  oxide  piles.  As mentioned previously,
any untreated or treated waste material for which protective,

-------
                           16

bellaves that sufficient area exists for deposition of these
notarial*.  EPA agrees that placement of treated material in
this area (existing slag pile A, truck cut area and pond area;
see  Figure 1-2  of the  FFS)  may  involve  dismantling  some
structures such as  the  dilapidated  slag  bins.   Actual space
availability and disposal area vould be determined during the
design phase.  On-site disposal vould limit the use of paved
areas but  not eliminate future use of the buildings.   The
basement may be considered for treated material disposal, but
the space is limited and it would preclude future use of the
basement.
JOHNSON CONTROLS!  "The Proposed Plan requires the placement
of stabilised materials in a RCRA Subtitle D landfill.  We are
concerned about the consistency of this requirement with any
remedy prescribed  for  Operable Unit Z at a later  date.   Zf
other materials at the site must be placed in a landfill, it
may be uneconomical to design a separate landfill at a later
time.  Consequently, we request that U.S. BPA include in its
Record of Decision provisions which allow the party conducting
the  remedial action the  option of storing the  stabilised
material  in  the  interim or designing a  landfill  which will
accommodate all site materials. Since the Record of Decision
on Operable  Unit Z is  expected next year, well  before the
remedial  design  for Operable Unit  ZZ is completed, allowing
either interim storage or  proper siting of the  landfill as
alternatives  will  help  to   assure  that the   remedy  is
cost-effective without creating any long-term problems.

EPA RESPONSES An important point requires clarification.  The
Proposed Plan does not specify that the stabilized materials
must  be  placed  in  a  RCRA  Subtitle  D  facility.  -  For
conservative  cost-estimating purposes,  it was assumed that
Subtitle  D   requirements  would   be  met.     However,  the
requirement for the placement of stabilized material is that
it  be done   in  a protective  manner.   EPA  believes  that
depending on the remedial activities that will be required by
the Operable  Unit  1  action, consolidation  of  the stabilized
material with other materials in the future may be possible.

PUBLIC COMMENTS  n[A]s much of the  lead wastes  as possible
should be removed from  the site.  This removal would not only
include the slag piles, but also all buildings, unsalvageable
process equipment  or any other debris or structures which
would  serve  as  a  reminder of ML Zndustries and National
Smelting.  Since  the site lies in an outcrop and recharge tone
of  the  Raritan-Magothy aquifer  (an  important  source  of
drinking water for  southern New Jersey)  it would be prudent to
further reduce the  potential for groundwater contamination by
removing  the  wastes rather than stabilising for  disposal on
site."

-------
                                17


     1PA RESPONSEi  Removal and off-lit*  disposal of stabilised/
     •olidified slag and  lead  oxide material* and decontaminated
     buildings and equipment from the  site would not achieve any
     significant additional protection, while incurring substantial
     additional cost for transportation and disposal.  Stabilised
     material would pass the TCLP test  and would be placed on site
     in a protective manner.  A long-term monitoring program would
     be instituted to monitor potential migration of contaminants
     from treated material and ensure protectiveness of the remedy.
     Similarly,  once  the  buildings  and  equipment  have  been
     decontaminated, they would no longer pose a threat to public
     health and the environment. Demolition of structurally sound
     buildings  and disposition of equipment  which  have  been
     decontaminated is beyond the remedial response objectives and
     responsibilities under Superfund.


     PUBLIC COMMENT:   The cleanup should be  expanded  to include
     contaminated stream sediments or any other highly contaminated
     soils on adjacent properties.

     EPA RESPONSE:  Cleanup of contaminated stream sediments and
     soils will be  addressed as part of the Operable Unit 1 remedy.

                                '••'.*.,",      " -      •/
S.   RECYCLING

     Since a number of comments received on  the proposed remedy
     concerned the recycling of site materials,  EPA provides the
     following to clarify its position on this issue.

     It has always been EPA's intention to allow for recycling and
     recovery  for  reuse  of as many  of  the  site materials  as
     possible.    This  is evidenced  by  the statement made  in the
     Proposed Plan  that as part  of the remediation which would
     address debris and contaminated surfaces, materials would be
     recycled where possible.

     While conducting  the FFS,  EPA investigated recycling for off-
     site treatment, disposal and recovery of waste materials from
     the site.  Specifically, EPA was interested in identifying the
     recycling potential of the slag piles, which at an estimated
     volume of  9800 cy, represent the major portion of waste being
     addressed.
 s
     Based upon information  obtained during EPA's  preliminary
     evaluation of recycling options,  due to the relatively low
     lead content (approximately 12  percent) of the slag material,
     no markets  were  identified which indicated an interest  in
     utilizing this material.   Consequently,  EPA concluded that
     recycling was not a viable or cost-effective alternative for

-------
                           14

and  surface  water contamination, since it  overflows during
precipitation   events  into   surface   streams,  and   also
infiltrates into groundwater.  Therefore, expedited removal of
contaminated standing water and cleaning of the drains,  is
necessary  to   eliminate   it   as  a continuing source  of
contaminant exposure and migration.


JOHNSON CONTROLS i  "With respect to the ponded stormwater, ve
have  obtained  estimates  vhieh  indicate that  one  million
gallons of water eould be treated on-site in  a rental unit for
less than $100,000.  Also, vhile off-site disposal  costs may
be considerably less than BPA  estimated, they are expected to
be  significantly greater  than the rental  unit cost.   BPA
determined  that  both remedies  satisfy »CP  criteria,  but
hypothesised  that  off-site disposal  would be cheaper  (a
questionable eonclusioa).  We  propose that BPA permit whoever
performs the remedial action to ehoose the more cost-effective
alternative.**

EPA RESPONSE:   Injection  of standing water  into the aquifer
would  require  on-site treatment to achieve the EPA action
level  for  lead  of  15 micrograms per  liter (ug/1).   For a
surface water discharge, the treated water would need to meet
a site-specific discharge criterion estimated to be 1.3 ug/1,
which is based on EPA's recommended criterion for freshwater
aquatic life protection for chronic toxicity.   EPA believes
that a number of unit processes in series would be required to
achieve these  levels.   An estimate of $100,000 seems  to be
unrealistically  low  to  achieve these stringent  discharge
requirements.  If, however, it could be demonstrated that on-
site  discharge could  be  conducted in accordance   with the
appropriate discharge  criteria,  and would be  less  expensive
than off-site  treatment and disposal,  EPA  would permit the
more cost-effective alternative.
JOHNSON  CONTROLS s    **[W]e  request that  BPA permit  whoever
performs the remedial action to use ponded stormwater in the
stabilisation  process.   There  is mo  point in using  clean
water,   furthermore, in the event on-site  treatment of the
ponded stormwater is utilised, we  request that BPA permit the
use of treated water  for building decontamination and cleaning
to  lessen  the  amount  of  treated  water  which  must  be
discharged.**

BPA RESPONSES  It is mentioned  on page 5-21 of the FFS that
standing water on site may be used as  a  source of water for
the stabilization/solidification process.  In addition, if it
can be demonstrated that ponded water can be  treated to levels
determined by  EPA to be  acceptable  for decontamination, EPA
would allow using such water  for this purpose.  EPA, however,

-------
                               15

     does not believe that it would be cost-effective to do so.


     BXlDEs  **Eave options for treatment of vater been eoneidered
     with possible discharge  into  the sanitary sewer in  lieu of
     groundwater recharge?... .Have potential options for recycling
     of contaminated sludges and sediments been considered?**

     EPA RESPONSE*  Yes.  Based on inquiries with town officials,
     there are no sewer lines or sewage treatment plant (POTH) in
     Pedricktown.  The nearest POTW is in Carney's Point, which is
     approximately five miles  from the NL site.  In addition, this
     facility indicated that it would not accept water originating
     from a Superfund site.

     EPA has indicated on page 4-45 of the FFS that any untreated
     or  treated material  for which  protective,  cost-effective
     recycling is available would be recycled.


D.   ON-8ITE PLACEMENT

     ENVIRON:  "EPA should provide an analysis of appropriate sites
     for  on-site disposal  of the  material,  especially in  the
     context of future use scenarios for the site.  Examination of
     the attached Figure W-l of the Remedial Investigation Report
     Volume  IV suggests ' that wetlands n'and property  boundaries
     preclude  the  use of unpaved areas  of the property  for the
     construction of the on-site landfill.... Consideration should
     be given  to  the feasibility of placement of  the stabilised
     material  in  the paved area at the  site.  For  example,  the
     basement of the refining building could contain approximately
     1,500 ey of stabiliied material.   Placement of the remaining
     stabilised  material   at  the  north  end  of  the  paved
     manufacturing area (86,000 square feet) would require further
     analysis,  and  would  likely  involve dismantlement  of  all
     structures north of the refining building.**

     EPA RESPONSES   EPA has considered a potential  site  for the
     on-site  disposal of  stabilized/solidified  material in  the
     context of future use scenarios for the site.   Treated waste
     would potentially  be  disposed  on paved areas which include
     sufficient  space  for  deposition of  such materials.    For
     conservative cost-estimating purposes,  it was  assumed that
     disposal would meet RCRA Subtitle D requirements. Figure 2 of
     the Remedial Investigation Report -  Volume I and Figure W-l
     of Remedial  Investigation Report - Volume  IV were  used to
     determine space availability for FFS purposes.  The total area
     required for the on-site  deposition of the  treated material
     was estimated to be between 40,000 and 50,000 square feet. As
     the open paved area in the northern portion-of the industrial
     area was estimated to be approximately 63,000 square feet, EPA

-------
                           12


ENVIRON:  **[I]t is net evident that any duet in .the building*,
which  has  remained  seven years after  the  cessation  of
operations, would be suspended in air and present  a health
threat via inhalation.  The small layer of dust that may still
adhere to the surfaces of the buildings presents an extremely
limited  source for wind  erosion,  and would not  be readily
susceptible to suspension.  EPA has not provided any data to
support the assumption that the inhalation pathway presents a
potential health risk.**

SPA RESPONSEt   Chemical  analyses  for wipe samples and other
waste areas presented  in Table 3-1 of the FFS indicate high
metal concentrations (e.g., lead and cadmium) on contaminated
surfaces and debris.   Although currently not in suspension,
the dust represents  a  potential source of air contamination
within and  outside  of the buildings  and a threat  to human
health and the environment due to potential exposure to, and
migration   of,   these    contaminants.       In  --addition,
decontamination  of  the  buildings  is  consistent with  the
overall site remedy.


ENVIRON:  "It should be noted that the preferred remedy does
not provide any guidance on the acceptable cleanup level for
the  building  surfaces.    The  cleanup  objective should  be
established in consideration of future use scenarios.  While
decontamination  and potential reuse  of buildings may  be
feasible for the laboratory/office complex, the warehouse, and
potentially  the  refining buildings,  clearly the rdecaying
operations, buffer  storage and kilns have little  value  to
non-smelting operations.  NL asserts that demolition of some
or of all the  structures should be considered as a remedial
option by  EPA if it  is  a safer  and/or  more cost-effective
remedial alternative.  In addition, cleanup should take into
account whether or not RCRA standards for off-site disposal
apply.*'                                             .
                                                   »
EPA RESPONSE:  Although the preferred  remedy does not provide
specific  cleanup levels,  the  objective of  the  expedited
response action is to  remove known sources  of contamination
which present  potential  risks  to human health,  in.terms  of
inhalation and  direct  contact.  Health-based cleanup levels
for building surfaces will determined during remedial design.

Demolition and disposal  of some  of  the  structures  such  as
large buildings would involve additional cost and be no more
protective of human health, and the environment.  For some of
the structures, EPA agrees that if it were safer and/or more
cost-effective, remedial activities would  include demolition.
However, decontamination would still be required,  because
demolition without decontamination could involve releases of

-------
                                13

     contaminated  dust and  result  in risks  to the  neighboring
     community and the environment.  In addition, cleanup would be
     conducted in  accordance with RCRA regulations.   Disposal of
     contaminated  demolition  debris would require treatment and
     disposal at a RCRA  facility and  be  subject to Land?Disposal
     Restrictions due to  the potential presence of lead dust, which
     is a  listed waste  (K069).   Haste materials  resulting fro*
     decontamination would be treated  in accordance with RCRA Land
     Disposal Restrictions and disposed  at an appropriate RCRA*
     permitted facility.                                 t * - ''-«
     EXlDEs  "Has consideration been given to the potential future
     need to reelean the facility if subsequent remedial activities'
     at the site result in recontamination of surfaces?*'  ••>'>*-   -'
                                                        •• -.*Jy  ,.*
     EPA RESPONSE:  Subsequent remedial actions will be conducted'
     utilizing standard  dust control measures  at a  minimum;  to
     control  fugitive  dust  emissions,  and  therefore  minimise
     reeontamination of clean surfaces.
C.   STANDING WATER AMD SEDIMENTS                    -     f, r; - :.

     ENVIRONS,  "EPA*• decision  to  remove,the standing water Xros*
     the property for off-site  treatment  is premature la £h*t it-
     neglects other contaminated water present at  the site that
     will be addressed  in the 78 for Operable Unit 1.  Operable
     Unit I's 78 willjbe completed by December 1991, prior to the
     completion  time* for  implementation   of  this-^ Alternative^
     Therefore, it is logical that EPA consider the appropriateness*
     of treating this waste stream with other Operable Unit 1 waste-*
     streams (e.g., contaminated ground water) in a common remedy.-***

     EPA RESPONSES  The Draft Feasibility Study for Operable-Unit*
     1  is  scheduled to be completed  in March 1992,  and  it* is:
     expected to take  several  additional months until the document**
     is finalized and EPA has selected a remedy.  Although a remedy*
     may be  selected  by mid  to late  1992  for Operable  Unit !,•
     implementation of  the remedy  may  not begin .for  another
     eighteen months or so.  Recognizing this, along with the size*
     and complexity of the site, EPA is addressing site remediation*-
     in phases, or operable units.                          &  .
                                                            *   .  j
     EPA has designated that Operable Unit 2, which  is the subject*
     of this document,  would  address areas of  hazardous surface7
     contamination within  the paved area of the  site.   EPA* hasT
     determined that these areas will be remediated on an expedited
     basis which  would continue the activities begun undetf the
     Removal Action and be consistent with the total site remedy.
     Contaminated standing water is one of the  continuing sources
     of off-site contaminant migration contributing to groundwater

-------
                               10

     in Table 3-3, TCLP results indicate that the majority of piles
     tested qualify as hazardous waste purnuant to RCRA,  based on
     leachability of lead and/or cadmium.


     EXIDE:    "The  EPA  statements  and Alternative  SF-5  which
     indicate  that  (bench-scale  tests veuld  be  required*  to
     evaluate this option, suggest that EPA may not have considered
     the potential need to process the slag prior to stabilisation,
     to  control dust  from this operation,  and/or to  properly
     collect  and  treat wastevater  vhieh  may be  generated.   Zn
     addition,  the  agency appears  to  have  selected this  option
     without  bench-scale  tests  and thus with little,  if  any,
     knowledge  about  the amount  of solidification agents  which
     would be needed to  stabilise these materials.   Given  the
     potential uncertainties associated with the  feasibility and
     costs  associated with  this  option,  it  is  suggested  that
     bench-scale tests be conducted to evaluate this option against
     the potential recycling alternative.  Indeed, it may also be
     necessary to perform independent evaluations  on the slag and
     lead  oxide  as  the  results  of  the   evaluations  may  be
     different."

     EPA RESPONSE:  As stated on page  5-25 of  the FFS  and in the
     Record of  Decision,  bench-scale tests  will be  required for
     stabilization/solidification to  select  the proper  type  and
     quantity  of  stabilizing agents,  feed material and  water.
     These  tests would  be  performed  during  Remedial  Design.
     Literature and vendor information  is sufficient  to indicate
     that the widely used and proven stabilization/solidification
     technology would achieve  remedial  objectives  for  metals-
     contaminated  materials  for  the  approximate  cost  of  the
     remedial action, which was estimated  at  $2.3  million.
B.   DEBRIS AND CONTAMINATED SURFACES

     ENVIRON:  "EPA has proposed  decontamination  of contaminated
     surfaces and debris with off-site treatment  and disposal as
     part of Operable Unit  (OU)  Two.  At the threshold,  we note
     that building contamination  has also been considered  in OU
     One, and  recommend  that EPA  clarify which OU  will  address
     decontamination.   The  contaminated  debris consists  of lead
     dross, wooden pallets, baghouse bags, scrap  metal  and  other
     materials present throughout the site.   It is not clear that
     the debris and contaminated  surfaces present similar risks,
     that  similar  cleanup  criteria  should be  applied,  or that
     similar remedial alternatives are available. Further the need
     for expedited cleanup of wooden pallets, scrap metal and other
     debris is unclear.  NL  Industries, therefore,  recommends that
     the debris and building surfaces be  evaluated separately."

-------
                           11

•PA  RESPONSE:   EPA  has  decided  that decontamination  of
contaminated surfaces and debris with off-site treatment and
disposal will be conducted as part of Operable 3nit 2.  Lead
dross, a lead-bearing byproduct of the smelting process, has
been considered as  similar to lead oxide material and would be
treated with lead oxide material,  or recycled if possible and
cost-effective.   Other contaminated  debris such  as wooden
pallets, bag  house bags,  scrap metal, plastic,  rubber and
other materials present similar risks as contaminated surfaces
(buildings and equipment) because these materials are covered
with  dust  similar to contaminated  surfaces.    The  metal
concentrations  in  the dust  are significant and may  pose a
health  risk,   if  Inhaled  by potential  on-site workers  or
individuals downwind  of the site.  This dust  is  subject to
migration by wind,  and possibly rain, due to the deteriorating
roof condition.  Decontamination of contaminated surfaces is
consistent with the overall site remedy and  eliminates the
need to maintain the  buildings1 integrity  until some future
date, while at the same time,  permanently  eliminates these
contaminated  areas as  sources of  contaminant exposure  or
migration.

EPA  agrees  that  all  materials may  not  be  amenable  to
decontamination.    Any  materials  which   could   be  cost-
effectively recycled would be recycled.  Debris that could not
be decontaminated,  such as  contaminated bag house bags, would
be transported to  an appropriate off-site,  RCRA permitted
treatment and/or disposal facility.


ENVIRON:    "The primary   justification for  including  the
buildings  in  aa expedited remedial  action,  appears  to  be
exposures from inhalation,  ingestioa and dermal contact with
dust.   Zt is  recognized ia the  7F8  (p.  1-4 and  1-5)  that
limited access to the site, the securing of entrances to the
contaminated buildings, and removal  of valuable material from
the site would effectively deter trespassers from the site and
would reduce the dermal and ingestion exposure.  Tha potential
risk from these pathways were thus considered to  be much lower
compared to inhalation exposure (FFS p.1-9)."

EPA RESPONSES   Although limiting access to the site, securing
entrances to the contaminated buildings and removing valuable
material from the  site would deter  trespassers, it will not
completely eliminate curious trespassers, children or vandals
from entering  the site.  These individuals would  be subject to
inhalation, dermal  and ingestion risks to contaminants at the
site, while possibly exposing others by bringing contaminants
off-site on their  shoes and clothing.  Furthermore,  because
they do not address the problem on a  permanent basis, EPA does
not consider  institutional  controls  such  as fencing,  when
evaluating potential exposure pathways.

-------
                                8

     EPA RESPONSES  EPA has no legal authority or decision-making
     role relative to the  fate of  the  on-site buildings once the
     site remediation haa been completed, and therefore, does not
     plan to take further actions to address the buildings.  Since
     the current owner of the site,  National Smelting of New Jersey
     (NSNJ),  is  bankrupt  and  a  trustee  was  appointed,  any
     disposition of the site buildings and equipment must be done
     in accordance with applicable bankruptcy lavs. EPA also notes
     that  the  trustee  for  NSNJ  has  been   notified  of  NSNJ's
     liability as a PRP for the site.



     Responses

This section  contains a summary of the questions and  comments,
which pertain to the selection of  the  remedy, received  by EPA in
writing during the public comment period.  Copies of the original
letters stating the  comments may  be found in Appendix B.   Comments
were received from one citizen and  from representatives of some of
the PRPs for the site.  These PRPs are Exide Corp,  AT&T, Allied-
Signal, C&D Charter Power Systems, Gould Inc.,  Johnson Controls and
Master Metals,  Inc.    In addition, questions and comments were
received from ENVIRON,  a technical consultant to NL Industries,
Inc., a PRP for the site.  Comments presented in this section are
organized into the following categories:

     A.   Slag aad Lead Oxide Piles

     B.   Debris and Contaminated Surfaces

     C.   standing Water and Sediments

     D.   On-site Placement

     B.   Recycling

     r.   Sequence of Conducting Remedial Activities


     A. SLAG AND LEAD OXIDE PILES

     ENVIRON: "Table 1-2 from the FF8 suggests approximately 9,800
     cubic yards (cy)  of slag and 200 cy of lead oxide in piles on
     the paved area.   The 1988 inventory, presented as Table l in
     the Remedial Investigation,  indicated approximately 7,500 cy
     of slag and other lead bearing materials  in the manufacturing
     area.   The  EPA is using a value approximately 30% higher than
     the 1988 inventory.**

     EPA RESPONSE:  A March 1991 inventory taken by EPA  estimated
     approximately 9,800  cy of  slag  and  200 cy of lead  oxide

-------
materials on the paved area.  Both the 1988 and 1991 estimates
represent approximations.  EPA is relying on its own estimate
for cost-estimating purposes.   Although the  actual quantity
may vary somewhat from this estimate,  it would not affect the
selection of remedial alternative.
ENVIRONS  "The IPX stated la Section 5.2.4.1 of the 778 that
the stabilisation process might result in a volume change of
as much as  40%, vhieb  seems  high for this type of material.
The EPA  estimates 14,000 cy of stabilised materials  to be
disposed in an en-site RCRA Subtitle D landfill.**

EPA  RESPONSES    Volume  increase  by  the  stabilization/
solidification  process  depends  on the  material  treated,
reagents used and quantity of reagents added.  Literature and
vendor information range from a volume decrease to a 100 per
cent volume increase.  Most widely reported volume increases
for metal-contaminated waste  stabilization/solidification are
from 30 to 50 per cent.  For the purposes of the FFS, EPA used
a value of  40 percent  to provide a conservative estimate of
the amount  of stabilized material to be place on  site in a
protective  manner.     The  actual  volume  increase will  be
determined by a treatability study.


ENVIRON:   "The  construction  cost presented in the  778 and
Proposed Plan apparently includes no cost for construction of
an on-site landfill.  The cost estimate presented as Table B-4
of the 778 provides a cost of $4.34/oy for disposal on-site.
This value  may pay  for the  transfer  of material  from the
curing location to a disposal location, however, it does not
covar the construction cost of a landfill on-site.*1

EPA RESPONSES  Cost  estimates presented in Table  B-4 of the
FFS include the construction  cost of an on-site RCRA Subtitle
D landfill.   EPA recognizes that although this cost  ($4.34/cy>
may be on the low end of the cost range,  even if the cost were
tripled, it would only increase the total estimated cost by
$122,000, which would not affect the selection of the remedial
alternative.
EZlDEs "Exide Corporation does not understand BPA*s basis for
comparing lead  levels  in slag to EPA's  Interim Guidance on
Establishing Soil Lead Clean-up Levels in residential soils at
Superfund sites.**

EPA RESPONSES   Lead  levels  in slag  and lead oxide materials
were compared to EPA's Interim Guidance on establishing soil
cleanup levels for lead to show the relative concentration of
lead in these materials.  As stated in the FFS on page 1-8 and

-------
EPA RESPONSE:  Arsenic was  detected during FFS sampling and
analysis activities and is a contaminant of concern at the NL
sive.    EPA  has  identified  lead  and cadmium  as  primary
contaminants at the site because the results of the Toxicity
Characteristic Leaching Procedure (TCLP) conducted on samples
of the slag and lead oxide piles, indicated that, of all the
metals  analyzed,  these  two  leached  from  the  piles  at
concentrations which exceeded the criteria which characterize
the piles  as hazardous.   Remediation of  lead  and  cadmium
contamination at the site will also  result  in the remediation
of other heavy-metal contamination.


COMMENT:   A  resident  commented that  EPA*s public  Meeting
presentation  and  associated documentation appeared  to sbov
levels of contamination  which decreased abruptly beyond the
site property line  and sought clarification  regarding this
abrupt change.

EPA RESPONSE:  The illustrations  presented  by EPA showed
ranges  of  contaminant  concentrations and depicted  higher
concentrations within the fenced  industrial area and the site
property boundary.  Contaminant concentrations were found to
decrease in areas removed from contaminant  sources, including
off-site areas.  Extensive sampling  has been conducted on and
off the  former NL  property.  The  levels of  contamination
decrease significantly beyond  the  property  boundary*  and
particularly, beyond the industrial area of the property.


COMMENT:  A resident asked  how EPA  determined the range and
scope of its PP8 sampling activities.

EPA RESPONSE:  EPA1s Removal Action activities addressed the
worst areas  of hazardous surface contamination at the site.
As a result of the information and data collected during these
activities,  EPA determined  that  certain areas  of hazardous
surface contamination could be addressed on  an expedited basis
through an Early Remedial Action, which would be consistent
with the long-term, site-wide remedy.  Sampling was  done to
provide information needed to choose a remedy for these areas
of hazardous surface contamination,  namely, the slag and lead
oxide piles,  debris and  contaminated surfaces,  and standing
water and sediments.
COMMENT:  A  resident asked if EPA vas proposing on-site or
off-site disposal of the slag pile material.

EPA RESPONSE: Under EPA's Preferred Alternative for slag pile
and lead oxide pile contamination (Alternative SP-5), the slag
pile material will be solidified, stabilized and disposed on

-------
     site in a manner which is protective of human health and the
     environment.  As a temporary measure, the slag material may be
     encapsulated by a spraying technique to prevent releases of
     fugitive dusts and particulates, while the permanent remedial
     alternative is being implemented.


     COMMENTS  A resident asked why Alternative SP-3, the off-site
     flame   reactor,   was  not   selected  as  IPX's   preferred
     alternative.

     EPA RESPONSE t  Treatment of contaminated material with a flame
     reactor   is   considered   an  innovative  technology   whose
     implementability on  a commercial scale is not yet proven.  The
     only flame reactor currently operating is in Pennsylvania, and
     is operating on a pilot scale.   In addition,  this technology
     was estimated to be  more  expensive  to  implement compared to
     the solidification/stabilization technology.  Markets for the
     process byproducts associated with the flame reactor have not
     been  identified,  which  may further increase  its cost  to
     implement.   There  are also some  state  permitting  issues
     regarding  flame reactor  treatment  which have yet  to  be
     resolved.  These involve emissions permits and permitting to
     accept hazardous waste from out-of-state sources.
     " ' • '. e- .  ' , }•   - -.   .   .     ,\t ,   •  •*"


C.   COMMUNITY ISSUES

     COMMENT:  A loeal official suggested that the HL Industries
     site be cleared of structures following completion of remedial
     actions, so that it  would  c%  suitable for SOLS future use and
     consequently provide the community with needed tax revenue.

     EPA RESPONSE:   Under Superfund,  EPA is authorized to spend
     money   to  remediate  sites  contaminated  with  hazardous
     materials.  Once the buildings are decontaminated, EPA is not
     authorized to spend money solely for demolition purposes.

     COMMENT:  A resident asked if the site  would  remain unusable
     once the Operable Unit 2 remediation is completed.

     EPA RESPONSE:   The NL site will be suitable for certain uses
     following  the   remediation.     However,   some   land   use
     restrictions  will  be  placed on  the  site to  ensure  that
     stabilized material  is not disturbed,  so that  the remedial
     action continues to  be  protective of public health and the
     environment.
     COMMENT: A resident asked what would become of the industrial
     area buildings after they have been decontaminated.

-------
Ill* Summary of Pii^>llo Ccpwypts and EPA Responses

This section contains a  summary  of verbal  questions and comments
which pertain  to the selection  of the remedy received  from the
community  during the August  6,  1991  public meeting.   Comments
presented  in  this  section  are  organized  into  the  following
categories.

     A.   Cleanup Funding and Schedule

     B.   Technical Concerns

     C.   Community Issues


A.   CLEANUP FUNDING AND SCHEDULE

     COMMENT!   A resident  asked who would  pay  for the  eost of
     implementing the remedial alternative.

     EPA RESPONSE:  EPA has  identified approximately fifty parties
     as  potentially  responsible  for  contamination  at  the  NL
     Industries site.  EPA  has requested payment  of  $700,000 of
     past response cost from the PRPs.  EPA will continue to pursue
     all liability and enforcement provisions available to it under
     the Superfund  legislation to have past and  future response
     actions funded by PRPs.


     COMMENT:  A resident asked how EPA expects to recover cleanup
     costs from  those PRPs  which have been  delinquent  in paying
     local property taxes and other taxes.

     EPA RESPONSE:  Most of the PRPs which have been identified for
     the NL  site  do not own the  site property  but have  sent
     hazardous substances and/or hazardous wastes to the site.  EPA
     believes that many of these PRPs are solvent entities with the
     financial ability to pay cleanup  costs for which  they are
     liable.    As discussed in EPA's  response  to  the  preceding
     comment, EPA has  the  authority to request payment  of  past
     costs.  If a PRP were to  refuse to reimburse EPA voluntarily,
     EPA can also initiate legal proceedings for cost recovery.


     COMMENT:   A resident  expressed  concern that  the  estimated
     schedule  for  completing the  remediation  of  the  areas  of
     hazardous surface contamination was too long.

     EPA RESPONSE:   The estimated time  for implementing  EPA's
     preferred alternatives  for remediating the slag and lead oxide
     piles,   surfaces   and   debris,   and   standing  water  is
     approximately  three years.   EPA  believes  that this  is  a

-------
     realistic tine frame for such work.

     The  time  frame  is  based  upon  the  following sequence  of
     remedial activities.   First, the slag and  lead oxide piles
     would be treated.   Concurrently,  buildings, paved surfaces,
     equipment and debris would be decontaminated.  Subsequently,
     the   contaminated   standing  water   and  water   used  for
     decontamination  of buildings,  etc.,  would  be  collected and
     transported  for  off-site treatment and  disposal.   Finally,
     drains would be  decontaminated and unplugged.   Through this
     sequence,   the  sources   of  airborne   contamination  and
     contaminated runoff would be eliminated and water from future
     rain  events  would  drain  through   these  areas  without
     transporting contamination off site.


     COMMENT:   A resident asked if bids had  been solicited from
     area waste management companies regarding removal and disposal
     of contaminated oa-site materials  and  suggested that this may
     be a more cost-effective way to perform the cleanup.

     EPA RESPONSE t  EPA's cost estimate for  this off-site treatment
     and disposal alternative was included under Alternative SP-6
     in Chapter  4 of  the FFS.  The cost of this alternative was
     estimated  to  be  $6,159,100.   Identification of  specific
     .contractors  would  occur during the  Remedial  Design  phase.
     However, based upon experience and inquiries made during the
     FFS,  EPA believes that the  cost of  off-site disposal  is
     significantly more expensive, and no more protective, than the
     selected remedy.


     COMMENT t  A resident asked if National  Lead  (NL) and National
     Smelting of  New Jersey  (purchaser of the plant site in 1983)
     are both identified as PRPs for contamination at the site.

     EPA RESPONSES  Both companies have been identified as PRPs for
     the site.


     COMMENT:   A resident  asked for a listing  of  all  the VRPs
     identified for the site.

     EPA RESPONSES  A list of companies notified that they may be
     PRPs for the site  is presented in Appendix C.


B.   TECHNICAL CONCERNS

     COMMENTS  A resident asked if EPA had detected arsenic during
     sampling activities conducted as part of the 7F8.

-------
•xpressed  by the  public at  the public  nesting concerning  the
proposed remedy. Section IV presents a summary of written comments
on the Proposed Plan and  FFS.  Each question or comment is followed
by EPA's  response.   Written comments  received during  the public
comment period are  attached in the appendices  described below.  All
comments expressed to EPA were considered in EPA's final decision
for   selecting  the  remedial   alternatives   for   addressing
contamination at the site.

Attached   to  the   Responsiveness  Summary   are  the   following
appendices:

     • Appendix A - Proposed Plan and Public Comment

           • Attachment A.I - Proposed Plan
                             NL Industries, Inc.  Site
                             Pedricktown, New Jersey
                             July 1990

           • Attachment A.2 - Public Notice

           • Attachment A.3 - August 6, 1990 Public Meeting
                             Attendance Sheet

           • Attachment A.4 - Notice of Public Comment Period
                             Extension

     • Appendix B - Written Comments on the Proposed Plan
                    and Focused Feasibility Study

     • Appendix c - PRPs Who Were Sent a General  Notice Letter


II* Background on CoiwuBitv Involvement and Concerns

Pedricktown residents first became aware of potential environmental
and public health impacts associated with operations  at the NL site
in 1975,  when the Salem County  Department of Health  sampled 15
private drinking-water wells in the site  vicinity.   One well was
found to have elevated lead levels.  Several months later, private
homes along Benjamin Green Road west of the site were connected to
the public water supply.   Other early  investigative  activities
performed  to assess  off-site impacts  included an air  monitoring
program initiated  by the New Jersey  Department  of  Environmental
Protection  (NJDEP)   which  detected  elevated levels  of  several
airborne contaminants, including lead.

EPA's involvement with the  NL Industries site began in December
1982 with the site's inclusion on the National Priorities List of
Superfund sites. Since that time, EPA has implemented a community
relations  program  in the site area  designed to both  inform the
public of  site activities and solicit input from  the community

-------
regarding its site-related concerns and questions.  These efforts
have included disseminating  printed public information materials
and conducting public meetings and information sessions to coincide
with technical milestones at  the site.  Recently,  on July 17, 1991,
EPA  conducted  community  interviews with local  officials  and
residents to identify community issues and concerns regarding the
site.   EPA received additional  input from the  community  at the
August 6, 1991 public meeting,  during which EPA provided an update
of the Superfund activities at  the site and presented the Proposed
Plan.

Based on comments received during the July  17 community interviews
and August  6  public meeting, the three major issues  or concerns
expressed by local residents and officials were:

o    Desire to have remedial  activities proceed and be completed as
     soon as possible

o    After decontamination, demolition of the large buildings and
     structures in the industrial area of  the plant,  so that the
     property may be returned to the tax roll

o    More frequent  communications by EPA  to  local officials and
     residents updating  them on the status and  progress  of site
     activities

Additional  concerns  and  issues which  were expressed  by  the
community include the following:

o    Liability  of  the  PRPs  for  conducting and funding  site
     investigations and cleanup .            .

o    Plans to monitor area drinking-water supplies periodically

o    Impact of site activities on area property values

o    Potential future uses of the site

o    Anticipated schedule for completion of the .site cleanup

o    Turnover of EPA and other personnel assigned to the site

o    Loss of local tax revenue from the site property

o    Site security

Based on the attendance at public meetings and  the overall feedback
EPA has received from the public, the level of community interest
in the NL site can be characterized as moderately high.

-------
18/81/91                             Index Docuient Nuiber Order                                              Page: 4
                                     NL INDUSTRIES OPERABLE UNIT 12 DocuMftts
Oocuient Nuiber: (0-881-8263 To 1263    .                                           Date? 11/15/91

Title {Letter regarding applicable or relevint requirnents for tilting it the site)

     Type: CORRESPONDENCE
   Author: Holitroi, Christina:  HJ Dept of  Environiental Protection
Recipient: Gilbert, Hichael H:  US EPA


Oocuient Nuiber: NLD-881-B264 To 1277                                               Date: 11/27/98

Title: (Referral fon fornarding attached turface Mter ARARi for the lite)

     Type: CORRESPONDENCE
   Author: Holstroi, Chriitina:  NJ Dipt of  Environmental Protection
Recipient: Gilbert, Hichael N:  US EPA
Docuient Nuiber: NLD-II1-I27B To 1291                                                Date: 17/11/91

Title: (EPA announcement regarding Proposed  Plan  for NL  Industries site)

     Type: CORRESPONDENCE
   Author: none:  US EPA
Recipient: none: . none
Docuient Nuiber: NLD-881-8292 To 1528                                               Date: 17/11/91

Title: Draft Focused Feasibility Study •  NL  Industries Superfund Site. Operable Unit 2

     Type: REPORT
Condition: DRAFT
   Author: none:  US EPA
Recipient: none:  none

-------
                      RESPONSIVENESS  SUMMARY

                        RECORD OF DECISION

                NX, INDUSTRIES, INC. 8UPER7UND  SITE

I. Introduction

The NL Industries, Inc.  (NL)  site,  located  in  Pedricktovn,  New
Jersey, consists of an abandoned, secondary lead smelting facility.
Past treatment,  handling and disposal practices at  the facility
have resulted  in  extensive  inorganic contamination of  the air,
soil,  ground water,  surface  water   and  stream sediments.   In
addition,  when  the   site  was  abandoned, significant  areas  of
hazardous surface contamination were left in the industrial area of
the  plant.   EPA has  designated remediation of these  areas  of
hazardous surface  contamination  as Operable Unit 2,  which is the
subject of this document.  EPA has conducted a Focused Feasibility
Study  (FFS)  to  identify and  evaluate remedial alternatives  to
address these areas which  include the slag and  lead oxide piles,
debris and contaminated surfaces, and standing  water and sediments.
In addition,  a comprehensive, site-wide Remedial Investigation (RI)
was  completed  in  July  1991  and a  site-wide Feasibility  Study
addressing other areas of contamination, which EPA has designated
as Operable Unit 1, is currently underway.

In  accordance  with  the U.S.  Environmental   Protection  Agency's
(EPA's) community relations  policy  and guidance  and the public
participation  requirements  of  the   Comprehensive  Environmental
Response,  Compensation,   and  Liability  Act,  EPA  originally
established  a  public comment  period  from July  17,  1991 through
August 16, 1991  to obtain  comments on the Proposed Plan for this
site.  At the request of a  potentially responsible party (PRP) for
the site,  the public comment period was extended until September 6,
1991.

EPA held a public meeting on August 6, 1991 at the Oldmans Middle
School located in  Pedricktown, New Jersey.  At  this meeting, EPA
provided  a  general overview  of  the  Superfund process,  the site
history, the results  of the  site-wide RI, the results of the FFS
for Operable Unit 2,  and discussed the Proposed Plan for Operable
Unit  2.    Subsequent  to  this  presentation, EPA responded  to
questions and comments of interested parties.  A  summary of the
questions received during the public meeting and during the public
comment period are contained  in this Responsiveness Summary.

The Responsiveness Summary,  required as  part  of the  Superfund
process,  provides  a  summary of  citizens'  comments and  concerns.
Section II  of  this document  provides a brief background  of the
community involvement and concerns regarding the  site.  Section III
presents  a  summary  of  the   significant  questions and  comments

-------
IB/11/91                             Index Docuient Nuiber Order                                             Page: 2
                                     NL INDUSTRIES OPERABLE .UNIT 12 DocuMnts
Docuient Nuflber: NLD-M1-I83S To IB35                  Parent:  UD-IB1-H34          Cite: 19/24/91

Title: (Letter regarding the proposed utilization of the flag piles  at  the lite, and fornarding requested
       analysis)

     Type: CORRESPONDENCE
Condition: HISSING ATTACHMENT
   Author: Gilbert, Hichael H:  US EPA
Recipient: Leed, Jeff:  Exide Corporation
Docueent Nuiber: NLD-B81-BB34 To I83i                                        •       Date: 16/15/91

Title: (Letter regarding the proposed utilization of slag  piles  at  the  site, and forwarding requested
       analysis)

     Type: CORRESPONDENCE
Condition: HISSING ATTACHMENT
   Author: Gilbert, Hichael H:  US EPA
Recipient: Roberts, Jill.:  Sunapee ChMicals Inc
Docuient Nuiber: NLD-BB1-BB37 To BB37                                               Date: 15/21/98

Title: (Letter regarding the proposed utilization of slag  piles  at  the  site, and forwarding requested
       analysis)

     Type: CORRESPONDENCE
Condition: HISSING ATTACHMENT
   Author: Gilbert, Hichael H:  US EPA
Recipient: Rosenberg, Henry:  Coietals Inc
Docuient Nuiber: NLD-I81-IB36 To I83B                                               Date: 15/21/91

Title: (Letter regarding the proposed utilization of slag  piles  at  the  site, and forwarding requested
       analysis)

     Type: CORRESPONDENCE
Condition: MISSING ATTACHMENT'
   Author: Gilbert, Michael H:  US EPA
Recipient: Sawhney, Ripp:  Kesteniore Metals

-------
•e/urn
Inde.' Docuient Nuiber Order
NL INDUSTRIES OPERABLE UKtT 12 DccuienU
Hszssssnssssssnnusssssssrscs:
                                                                               KSSBZSSSBSSSSSI
Docuient Nuiber:. NLDHB1-BB39  To 1157
                                               fiece: 16/18/91
Title: Final Reioval  Action/Feasibility Study Report for the National Lead Industry Site, Pedricktom
       NJ

     Type: REPORT                   .                                       ,        •   '
   Author: none:   Roy F Neston  Inc
Recipient: none:   US  EPA
Page: 3
Docuient Nuiber:  NLD-I81-I158  To 1158

Title: (Letter requesting  State Mater Quality Standards)

     Type: CORRESPONDENCE
Condition: HARE I NAM A
   Author: Gilbert,  Michael  H;  US EPA
Recipient: Holstroi,  Christina:  NJ Dept of Environmental Protection
Docucent Nuiber:  NLD-8B1-B159  To  1199

Title: (Soil) Analytical  Report - National Lead Industries

     Type: PLAN
   Author: Hunter,  J:   Roy  F Heston  Inc
Recipient: Zcwnir,  A:   US EPA
Docuient Nuiber:  NLD-CM-I2N  To  1256

Title: (Hater)  Analytical  Report  - National Lead Industries

     Type: PLAN
   Author: Hunter,  J:   Roy F Neston  Inc
Recipient: Zovnir,  A:   US  EPA
                                               Date: 15/11/91
                                               Date: 15/22/91
                                               Date: 14/11/91
Docuient Nuiber:  NLO-BB1-B257  To  1242                                                Date:  14/17/89

Title: (Neao fornarding attached  Preliminary Health Assessient for NL Industries)

     Type: CORRESPONDENCE
   Author: Nelson,  Nilliu:  Agency  for  Toxic Substances t Disease Registry (ATSOR)
Recipient: Donate,  Kenuns   US EPA

-------
18/11/91                             Indei  Author Nate Order.                                                 Page:  4
                                     NL INDUSTRIES OPERABLE UNIT 12 Documents
Docunent Number: NLD-MH812 To 1818                                               Datt: 12/14/91

Title: NL Industries Standing liter Sup ling Plan

     Type: PLAN
   Author: lei ley, Carl:  Roy F Niston  Inc
Recipient: Doiinich, Eugene:   US EPA
Docutent Nuaber: 10-881-8824 To 1133                                               Date: 17/11/91

Title: Slag Pile TAL Sampling Plan  - NL  Industries, Pedricktown, Sain NJ

     Type: PLAN
   Author: Hentzel,  Hichael:   Heston Spill  Prevention i Emergency Response Div (SPER)
Recipient: Doiinich, Eugene:   US EPA
Docuaent Nuiber: NLD-8B1-8257 To 1262                                               Date: 14/17/89

Title: (Heio for«irding attached Preliiinary Health Assessment for NL Industries)

     Type: CORRESPONDENCE
   Author: Nelson, Hilliai:   Agency for  Toxic Substances I Disease Registry (ATSDR)
Recipient: Donate, Kemin:  US EPA
Docuient Nuiber: NLD-BB1-8B82 To Mil                                                Date:   /  /

Title: Potential Hazardous Hast* Site  Site  Inspection Report - NL Industries Inc.

     Type: PLAN
   Author: Zervas, David:   NJ Dept of  Environmental Protection
Recipient: none:  none

-------
ie/ll/91                             Index Docuient Nuiber Order                                             Page: 1
                                     NL  INDUSTRIE OPERABLE UNIT 12 Docuunts
Docuient Huiber: NLD-8B1-IBB2  To IB11                                                Bite:    /   /

Title: Potentiil Hizirdous Hiite Site Site Inspection Report - NL Industrie! Inc.

     Type: PLAN
   Author: Zervis,  David:   NJ  Dept of Environmental Protection
Recipient: none:  none


Do alien t Nuiber: NLD-IB1-IB12  To NIB                    .                            Date:  12/14/91

Title: NL Industries Standing  Niter Supling Plin

     Type: PLAN
   Author: Kelley,  Ctrl:   Roy  F Neston  Inc                                           •
Recipient: Ooiinich, Eugene:   US EPA
Docuient Nuiber: NLD-8B1-IB19  To 1823                                                Dite:  IS/19/91

Title: (Neio regirding NL  Industries Disposal Status Report; inventory lilts attached)

     Type: CORRESPONDENCE
   Author: Butfroe, Thoiis:   none                     ••              '      '  '
Recipient: Doiinach,  Eugene:  US EPA
Docuient Nuiber:  NLD-IB1-BB24  To  1833                                                Dite: 12/11/91

Title: Sug Pile  TAL Supling  Plin - NL  Industries, Pedricktonn, Salei NJ

     Type: PLAN
   Author: Hentzel,  Dichiel:   Neston Spill Prevention I Emergency Response Div (SPER)
Recipient: Doiinich, Eugene:   US  EPA
Docuient Nuiber: NLD-881-1834  To  1834                                                Date: 11/24/91

Title: (Letter regirding  the proposed utilization of excess NL literals by Exide Corpontion,  ind
       foritrding inilytical inforntion)

     Type: CORRESPONDENCE
Condition: HISSING ATTACHNENT
   Author: Bilbert, Hichiel H: US  EPA
Recipient: Leed, Jeff:  Exide  Corpontion
 Attached: NLD-8B1-BB35

-------
. 18/11/91                             Indei Author Nut Order                                                  Page:  2
                                      HI  INDUSTRIES OPERABLE UNIT 12 Dociuents
 Docuient Nuiber: NLD-«l-t835 To 8835                  Pinnt: KLD-M1HB34          Diti:  19/24/98

 Title: (Letter regarding the propoied  utilization of the flag piles it the lite, and forwarding requested
        analysis)

      Type: CORRESPONDENCE
 Condition: HISSING ATTACHMENT
    Author: Gilbert, Hichael  N:   US EPA
 Recipient: Leed, Jeff:   Elide Corporation
 Docuient Nuiber:  NLD-8B1-I83A To  IB36                                                Date: 16/15/91

 Title: (Letter regarding  the  proposed utilization of dag piles it the site, and fonarding requested
        analysis)

      Type: CORRESPONDENCE
 Condition: HISSING ATTACHMENT
    Author: Gilbert, Michael H: US  EPA
 Recipient: Roberts, Jill:  Sunapee  Cheiicals  Inc
 Docuient Nuiber: NLD-8B1-8837 To 1137                                                Date: IS/21/91

 Title: (Letter regarding  the proposed  utilization of slag piles at the site, and forwarding requested
        analysis)

      Type: CORRESPONDENCE
 Condition: NISSIN6 ATTACHMENT
    Author: Gilbert, Hichael  H:   US  EPA
 Recipient: Rosenberg,  Henry:  Coietals Inc
 Docuient Nuiber: NLD-BB1-IB3B To IB38                                               Date: 15/21/91

 Title: (Letter regarding  the proposed utilization of slag piles at the site, and forwarding requested
        analysis)

      Type: CORRESPONDENCE
 Condition: MISSING ATTACHMENT
    Author: Gilbert, Hichael  H:  US  EPA
 Recipient: Sanhney, Ripp:  Nisteniore Metals

-------
16/11/91                             Indix Author Nut  Order                                                  Page:  3
                                     NL INDUSTRIES OPERABLE WIT 12 Docuicnts
Document Number: NLD-M1-I158 To 1158                                               Date: 15/11/91

Title: (Letter requesting State Nater Quality Stindirds)

     Type: CORRESPONDENCE
Condition: DARSINALIA
   Author: Gilbert, Hichae! H:  US EPA
Recipient: Holstrom, Christina:  NJ Dept of Environmental Protection
Document Nuiber: NLD-II1-I263 To 1263                                               Datet 11/15/91

Title: (Letter regarding applicable or relevant  requirements for testing at the site)

     Type: CORRESPONDENCE
   Author: Holstroa, Christina:   NJ Dept of  Environmental Protection
Recipient: Gilbert, Michael H:  US EPA
Docuaent Number: NLD-N1-B264 To 1277                                               Date: 11/27/91

Title: (Referral form fomarding attached  surface «ater ARARs for the site)

     Type: CORRESPONDENCE
 'Author: Nolstrom, Christina:   NJDept of  Environmental Protection
Recipient: Gilbert, Hichael H:  US EPA
Document Number: NLD-BB1-I159 To 1199                                               Date: 15/22/91

Title: (Scil) Analytical Report • National  Lead  Industries

     Type: PLAN
   Author: Hunter, J:  Roy F Neiton Inc
Recipient: Zo*nir, A:  US EPA
Document Number: NLD-IB1-I28B To 1256                                               Date: 14/11/91

Title: (Nater) Analytical Report - National  Lead  Industries

     Type: PLAN
   Author: Hunter, J:  Roy F Neston Inc
Recipient: Zonnir, A:  US EPA

-------
tr •!:."?!                             Index Chronological  Orter                                               Page: 4
                                     ML INDUSTRIES OPERABLE UNIT 12 Docments
Docuient. Nuibtr: NLD-Ul-NH To 1123                                               Ditti 15/19/91

Title (HeiD regarding NL Industries Disposal Status Report;  inventory  liiti ittiched)

     Type: CORRESPONDENCE
   Author: Budroe, Tnoias:  none
Recipient: Doiinach, Eugene:  US EPA
Oocutent Nuiber: NLD-IB1-I1S8 To 1158                                               Oitet 15/11/91

Title: (Letter requesting State Mater Quality Standards)

     Type: CORRESPONDENCE
Ccnjiticn: HAP.81NW.IA
   Author: Gilbert, Hi chid H:  US EPA
Recipient: Holstroi, Christina:  NJ Dept of Environtentil  Protection
Oocuient Nuiter: NID-BB1-B159 To 1199                                               Date: 15/22/91

7;lit. :;ui;; Analytical Report • National Lead Industries

     Type: PLAN
   Author- Hunter, J:  Roy F Heston Inc
Recipient: Zonnir, A:  US EPA
Docuient Nuiber: NLD-BB1-B278 To 1291                                .               Date: 17/11/91

Title; (EFA announceient regarding Proposed Plan for NL Industries  site)

     Type: CORRESPONDENCE
   Author: none:  US EPA
Recipient: none:  none
Dccuient Nuiber: NLO-BB1-I292 To 1528                                               Date: 17/11/91

T>t)»: Drift Focused Feasibility Study - NL Industries Superfund Sit* Operable Unit 2

     Type: REPORT
Condition: DRAFT
   .I:-*.!:::: none:  US EPA
Recipient: none:  none

-------
 18/11/91                             Index Author Nut Ordir                                                 P«ge: 1
                                     NL INDUSTRIES OPERABLE UNIT 12 DocuMittf
Docuient Nuiber: NLD-BB1-IB39 To 1157                                                D*tt:  16/18/91

Titlt: Final Retovjl Action/Fusibility Study Report for the National Lead Induitry Site, Pedricktonn
       NJ
                           »
     Type: REPORT
   Author: none:  Roy F Helton Inc
Recipient: none:  US EPA
Docuient Nuiber: NLD-8B1-I278 To 1291                                                Diti:  17/11/91

Title:  (EPA announceeent regarding Propoied Plan for NL Industries site)

     Type: CORRESPONDENCE
   Author: none:  US EPA
Recipient: none:  none
Docuient Nuiber: NLD-B81-I292 To «528                             .         .          Date:  17/11/91

Title: Drift Focused Feasibility Study • NL Industries Superfund Site Operable Unit  2

     Type: REPORT
Condition: DRAFT
   Author: none:  US EPA
Recipient: none:  none                      ..     ,     .  •                  -
Docuient Nuiber: NLD-B81-IB19 To 1823                                                Date:  IS/19/91

Title: (Heio regarding NL Industries Disposal Status Report;  inventory lists attached)

     Type: CORRESPONDENCE
   Author; Budroe, Thoiis:  none
Recipient: Doiinich, Eugene:  US EPA
Docuient Nuiber: NLD-ltl-1134 To 1834                                                Diti:  11/24/91

Title: (Letter regarding the proposed utilization of eicess NL uterials by Elide Corporation,  and
       forwarding analytical information)

     Type: CORRESPONDENCE
Condition: HISSING ATTACHHENT
   Author: Gilbert, Michael H:  US EPA
Recipient: Leed, Jeff:  Exide Corporation
 Attached: NLD-BB1-IB35

-------
IB/B1/91                             indu Ctironologicil Ordir                                                Pigi:  2
                                     NL INDUSTRIES  OPERABLE UNIT 12 Docuatnts
         Nuaber: NLD-J81-IB39 To 1157                                               Ditu lft/18/91

Title: Final Reioval Action/Feasibility Study Report  for the National Ltad Industry Site, PtdricktMtt
       NJ

     Type: REPORT
   ftut!;er: none:  Roy F Neston Inc
Recipient: none:  US EPA
Docuient Nuiber: NLD-I81-II36 To 1136                                        .       Bite: 14/15/91

Title: (Letter regarding the proposed utilization of slag piles at the site, and fomarding requested
       analysis)

     Type: CORRESPONDENCE
::r.i;tion: KISSING ATTACHMENT
   Author: Gilbert, flichael H:  US EPA
Recipient: Roberts, Jill:  Sunapee Cheiicals Inc
Docuaent Nuaber: NLD-K1-K35 To 1835                 Parent: NLMI1-M34          Date: 19/24/91

Title: (Letter regarding the proposed utilization of  the slag piles at the site, and forwarding requested
       analysis)

     Type: CORRESPONDENCE
Condition: HISSING AT1ACHKENT
   Author: Gilbert, Hichael  H:  US EPA
R?:ipient: Leed, Jeff:  Eude Corporation
Docuaent Nuaber: NLD-eei-I2i3 To 1263                                               Date: 11/15/91

Title: (Letter regarding applicable or relevant requirements for testing it the site)

     Type: CORRESPONDENCE
   • ••'^r: Hclstroi, Christina:   NJ Dept of  Environiental Protection
Recipient: Gilbert, Hichael H:  US EPA

-------
*s/8i/91                             Indei Chronological Order                                               Page: 3
                                     ML  INDUSTRIES OPERABLE UNIT 12 Oocuintl
Docuient Njiber: NlD-H 1-1264  To 1277                        '                       Dates 11/27/91

Title: (Referral for* forwarding attached surface liter ARARt for the site)

     Type: CORRESPONDENCE
   Author: Holstros,  Christina:   NJ Dept of Environiental Protection
Recipient: Gilbert, Michael H:   US EPA
Pocuient Nuiber:  NLD-M1-IB34  To 1134                    •                            Date: 11/24/91

Title: (Letter regarding  the proposed utilmtion of excess ML uterials by Elide Corporation, and
       forwarding analytical infonation)

     Type: CORRESPONDENCE
Condition: HISSIN6 ATTACHMENT
   Author: Gilbert, flichael H:  US EPA
Recipient: Leed,  Jeff:  Eside  Corporation
 Attacheo: NLl»tei-K35
Oocuient Nuiber: N1D-M1-N24  To 1B33                                                Date:  12/11/91

Title: Slag Pile TAL Saepling  Plan - NL Industries, Pedricktom, Salee NJ

     Type: PLAN
   Author: Her.trel,  flichiel:   Neston Spill Prevention 4 Ecergency Response Div (SPER)
Recipient: Doiinich, Eugene:   US EPA
Docutent Nuttier:  NLD-8ei-IB12 To 1116                                 '               Date:  12/14/91

Title: NL Industries Standing Mater Sampling Plan

     Type: PLAN
   Author: kelley, Carl:   Roy F Neston  Inc
Recipient: Donrurh, Eugene:  US EPA
r::uisrt Nuiber: NLD-eei-I2H  To I2S6                                                Dati:  14/11/91

Title: (Niter)  Analytical  Report - National Lead Industries

     Type: PLAN
   f:'thor: Hunter,  J:   Roy F Neston  Inc
Recipient: 2o»nir,  A:   US  EPA

-------
ADMINISTRATIVE RECORD INDEX
       Chronological
        Author Mam*
   Index Document Number

-------
8S/»;/»l                             Index Ch,-«nological  Order                                               Page: 1
                                   '  NL INDUSTRIES OPERABLE UNIT  12 Contents
Docuitiit Nuiber: NLMB1-8BB2 To Nil                                               Diti:   /  /

Title Potential Hazardous Haiti Siti Siti Inspection Report - ML Industries  Inc.

     Type: PLAN
   Author: Zervis, Divid:  NJ Dept of Environmental  Protection
Recipient: none:  none
Docuicnt Nuiber: NLD-lfll-1257 To 1242                                               Date: 14/17/89

Title: (Heio forwrding attached Preliiinary Health Assesstent for  NL  Industries)

     Type: CORRESPONDENCE
   Author: Nelson, Milliae:  Agency for Toxic Substances I Disease  Registry  (ATSDR)
Recipient: Donate, Kervin:  US EPA
Docuient Nutber: NLD-BB1-BB37 To 1137                                               Dlti: IS/21/91

Title: (Letter regarding the proposed utilization of slag piles at the site,  and  forwarding requested
       •niiysil)

     Type: CORRESPONDENCE
Conditisn: KiSSlNS ATTACHMENT
   Attr.sr: Gilbert, Richael N:  US EPA
Recipient: Rosenberg, -Henry:  Coietals Inc
Docucent Nutter: KLD-eei-BHS To IB3B                                                Date: IS/21/91

Title: (Letter regarding the proposed utilization of slag piles at the site,  and forwarding requested
       analysis)

     Type: CORRESPONDENCE
Condition: K1SSINE ATTACHMENT
   Author: Gilbert, Hichael H:  US EPA
Recipient: Sanhney, Ripp:  Nesteneore Metals

-------
                                                                          TABLE 12

                                              SUMMARY OF  REMEDIAL  ALTERNATIVES FOR STANDING WATER AND  SEDIMENTS
                                                                                                                                            Sheet 4 of 5
Criteria
      Alternative SW-1
         No Action
Alternative SW-2
On-Site Treatment and
Groundxater Recharge
    Alternative SW-3
    Off-Site Treatment
    and Disposal	
6.  Implementability

    Technical feasibility

    o  Ability to construct and
       operate technology



    o  Reliability of technology
No construction involved.
Monitoring program can be
easily implemented.
No treatment technology
involved.  Monitoring is
reliable.
Easy to construct and
operate all aspects of
this technology.


All aspects of this
technology are very
reliable.
Availability of off-site treat-
ment facilities may be potential
problem).
Saw as Alternative SW-2.
    o  Ease of undertaking
       additional remedial
       action, if necessary.
    o  Monitoring Considerations
    Administrative Feasibility

    •  Coordination with other
       agencies
    Availability of Services
    and Materials

    e  Availability of treat-
       ment, storage capacity
       and disposal services.
If monitoring Indicates that
future action is necessary, must
go through the FS/ROO process
again.

Long-term) monitoring required.
Hi grat i on/exposure
pathways can bo monitored.
Coordination required with
appropriate agencies for long
time period for monitoring
and reviewing site conditions.
No treatment, storage or
disposal facilities required.
If found necessary.
additional water could
be treated using this
facility.

No monitoring required
after completion of
remedial actions.
Coodination required
with EPA. DOT and
State agencies during
remedial actions.
All of these tech-
nologies are proven
and readily available.
Same as Alternative SW-2
assuming facility can handle
additional volume of water.
Same as Alternative SW-2.
Same as Alternative SW-2.  In
addition coordination required
with local traffic authorities.
All these technologies are
proven, however facility
availability may be limited.
4874K

-------
                                                                         TABLE  12

                                              SUMMARY OF REMEDIAL ALTERNATIVES FOR STANDING WATER AND SEDIMENTS
                                                                                                                                            Sheet  5 of 5
Criteria
      Alternative SW-I
         No Action	
Alternative SW-2
On-Site Treatment and
Croundwater Recharge
    Alternative SW-3
    Off-Site Treatment
    and Disposal	
6.  JMyleMentability (Cont'd)

    •  Availability of necessary
       equipment, specialists
       and Materials.
7.
    •  Availability of
       technologies
    •  Total Capital Cost ($)

    •  Annual operation and
       Maintenance (OCN1 cost
       l$/yr)

    •  Present worth* ($ based
       on S.OX discount rate
       and 30 year period)
Equipment and specialists
for Monitoring and inplew
ting public awareness program
are readily available locally.

None required.
        I

   10.700



  220.100
Several vendors can
provide all necessary
equipment, specialists
and Materials.

Technologies are coMMerctatty
available fro* several vendors.
1.335.000

        0



1.335.000
Facility availability May be
tiMited.
Technologies are readily
available.  Facilities May be
liMited.
993.200
993.200
•   Present worth cost includes approMiMtely $241.000 for Alternative SM-1 for each five-year review and site assessment.
4874K

-------
                                                                         TABLE  12

                                              SUMHARY OF REMEDIAL ALTERNATIVES FOR STANDING WATER AND SEDIMENTS
                                                                                                                                            Sheet 2 of 5
Criteria
      Alternative SW-1
         No Action	
Alternative SW-2
On-Site Treatment and
Craundwater Recharoe
                                                                                         Alternative SW-3
                                                                                         Off-Site Treatment
                                                                                         and Disposal	
3.  Long-Term Effectiveness

    o  Magnitude of residual
       risks
Standing water and sediments would not
be treated or removed.  Enisling risk
will essentially regain.
Natural attenuation is a very
slow process.
No residual risks to
public health or the
environment regain
after remedial action
is completed.
                                                                                     SaM as ATtemative SU-2.
    o  Adequacy of controls
No remedial actions and
therefore potential exposures
remain the same.
                                                   These technologies are
                                                   proven Methods for
                                                   handling these types
                                                   of contaminants.
                                       •s Alternative SW-2.
    o  Reliability of Control
4.  Reduction of Toxicity.
    Mobility and Volume
    Through treatment

    •  Treatment process and
       remedy
       Amount of hazardous
       material destroyed or
       treated.
    O  Reduction of  toxicity,
     •  mobility and  volume
       UMV).
Monitoring program is reliable
to assess contaminant
migration.
No treatment employed.
conditions Itoxicity. mobility
and volume of contaminants)
remain the same.  Volume of
contaminated standing water
and sediments may increase.

None by treatment.
None by treatment.
4874K
These operations arc
reliable processes
for handling the
contaminated standing
water and sediments.
Significant overall
reduction in toxicity.
mobility and volume of
contaminants of concern
in standing water
and sediments.

All standing water
containing contaminants
in excess of cleanup
levels and approximately 200 cy
of sediments underlying the
standing water.

Toxicity. mobility and
volume of contaminated
standing water signi-
ficantly reduced.
                                                                                     SaM  as Alternative  SW-2.
                                                                                     Totally eliminates the toxlcity.
                                                                                     mobility and volume of all  con-
                                                                                     taminants of concern In standing
                                                                                     water and sediments at the site.
                                                                                     Same as Alternative SW-2.
                                                                                     Toxicity. mobility and volume of
                                                                                     contaminated standing water at
                                                                                     the site would be eliminated.

-------
                                                                         TABLE  12

                                             SUMMARY OF REMEDIAL ALTERNATIVES FOR STANDING WATER AND SEDIMENTS
                                                                                                                                            Sheet 3 of S
Criteria
      Alternative SW-I
         No Action
Alternative SW-2
On-Site Treatment and
Groundwater Recharoe
    Alternative SW-3
    Off-Site Treatment
    and Disposal	'
«.  Reduction of Toxiclty.
    Mobility and Volume
    Through Treatment (Cont'd)

    o  Irreversibility of
       treatment

    o  Type and quantity of
       treatment residues
No treatment involved.
No treatment Involve*1.
Treatment It
irreversible.

Sludge would be gene
rated and disposed of
off-site.  Total quantity
of sludge and sediment is
estimated to be 358 tons.
     as Alternative SW-2.
No treatment residue regains
site.
5.  Short-Term Effectiveness

    o  Protection.of community
       during remedial actions

    o  Protection of workers
       during remedial actions
    o  Environmental Impacts
    o  Tio» until remedial
       response objectives are
       achieved
No short-term risks to
community.

No significant short-ten risk.
Personnel protection
would be used during
sampling activities.
No snort-term risks during
implementation of this
alternative.
Natural attenuation takes
long period of time, over
30 years.  It would take 3
•withs to Impl event tne
•onitoring and institutional
program.
Minimal short-teni
risks

Applicable OSHA regula-
tions, would be fol-
lowed.  Personnel
protective equipment
would be provided for
workers.

No Major environmental
{•pacts during imple-
mentation of this
remedial alternative.
Overall remediation
period is approximately
14 Months.  Actual re-
Mediation period Is
approximately 3 Months.
Same as Alternative SW-2.
No significant short-teni risk.
Personnel protective equipment
would be provided to prevent
direct contact with contaminated
water and sediments.
Increased traffic and noise
pollution resulting from hauling
of contaminated water and
sediments to off-site treatment
facilty.
Possibility of spillage along
the transport route.

Overall remediation period Is
approximately 6 months.  Actual
remediation period is
approximately 3 months.

-------
                                                                         TABLE  11

                                            SUMMARY OF REMEDIAL ALTERNATIVES FOR DEBRIS AND CONTAMINATED SURFACES
                                                                                                                                            Sheet 3 of  3
Criteria
   Alternative CS-1
      Mo Action
                      Alternative CS-2
         Contaminated Surfaces Decontamination/
            Off-Site treatment and Disposal
6.  Implementability

    Technical Feasibility (Cont'd)

    o  Case of undertaking
       additional remedial
     '  action. If necessary.

    0  Monitoring Considerations

    Administrative Feasibility

    o  Coordination with other
       agencies
    Availability nf Services
    and Materials
If Monitoring Indicates that future action is necessary.  If additional  contaminated surfaces are  found during
    o  Availability of treat-
       •eat. storage capacity
       and disposal services.
    6  Availability of necessary
       equipment, specialists
       and Materials.
oust go through the FS/ROO process again.
Monitoring and 5-year reviews are required because
contaminants remain on site.
Coordination required with appropriate agencies for
long time period for monitoring and reviewing site
conditions.
No treatment, storage or disposal facilities are
required.
Equipment and specialists for sealing building
and for monitoring are readily available.
    e  Availability of               None required.
       technologies

7.  toil*

    o  Total Capital Cost ($)         17,700

    o  Annual Operation and            6,800
       Maintenance (OIM) Cost ()/yr)

    0  Present Worth" ($ based on    136.100
       5.Of discount rate and
       30-year period)
remedial action, they can be decontaminated at that time.


No monitoring required after remedial actions are completed.
Coordination required with DOT and local  traffic authorities
for transporting the contaminated dust to the off-site treat-
ment and disposal facility.
All of these services are available from several.vendors.
Equipment and specialists for performing 'he decontamination
are readily available.  Several RCRA-permitted facilities can
accept the contaminated dust and water for off-site treatment
and disposal.

All technologies are proven and readily available from
several sources.
                                                          I.691.100

                                                                  0


                                                          1.691.100
•   Present worth cost includes approximately $5,000 for Alternative CS-1 for each five-year review and site assessemnt.


4874K

-------
                                                                         TABLE 12

                                              SUMMARY  OF REMEDIAL ALTERNATIVES FOR  STANDING WATER  AND  SEDIMENTS
                                                                                                                                            ShMt I of S
Criteria
      Alternative SW-1
         No Action	
 Alternative SW-2
 On-Site Treatment and
 Groundwater Recharoe
                                       Alternative SW-3
                                       Off-Site Treatment
                                       and Disposal	
    Key Components
 1.  Overall Protection of Human
    Health ami the Environment
2.  Compliance with ARARs

    o  Contaminant-specific
       ARARs
    o  Action-specific ARARs


    •  Location-specific ARARs
long-ten* monitoring and
5-year reviews.
Public awareness and education
program.
Essentially no reduc-
tion in tOMicity. mobility or
volume of hazardous con-
taminants in the standing
water.  Risk from contaminant
migration is monitored but not
reduced.
Does not meet the remedial
objectives for the site and
therefore does not provide
protection to human health
•r the environment.
Would not comply.  Would leave
contaminated water and sediments
on site.
Would comply.


Would not comply.
Standing water and sediments
would be collected and treated
for metals removal via chemical
precipitation, flocculation,
and filtration. Ion exchange
would be used, if necessary.
The treated water would then
be recharged to groundwater
via injection wells or infil-
tration basins.  Drains would be
decontaminated and unplugged.

This alternative would
remove and treat the
contaminated water
thereby eliminating
all human health, and
environmental risks
associated with the
standing water.
resulting in overall
permanent protection
to human health and
the environment.
Would comply because
removes contaminated
water and sediments
and treats to discharge
standards.

Would comply with action-
specific ARARs.

Would comply with all
locatln-spectfic ARARs.
                                   Collection of standing water an
                                   sediments, and transport to a
                                   RCRA permitted treatment and
                                   disposal facility.  Drains woul
                                   bo decontaminated and unplugged
                                   Same as Alternative SW-2
                                   Would comply by removing
                                   contaminated water  from the
                                   site.
                                    Same as Alternative SW-2.
                                    Same as  Alternative SW-2.

-------
                                                                         TABLE  IL

                                           SUHHARY OF REMEDIAL ALTERNATIVES FOR DEBRIS AND CONTAMINATED SURFACES
                                                                                                                                            Sheet I  of 3
                                        Alternative CS-I
                                           No Action
                                                                                Alternative CS-2
                                                                   Contaminated Surfaces Decontamination/
                                                                      Off-Site Treatment and Disposal   ^
    Key Components
Restrict building access and use of buildings
and equipment.  Roof repairs to prevent leakage.
Long-term inspection and Maintenance program including
five-year reviews to assess site conditions.
Decontaminate buildings and equipment via dusting, vacuuming
and wiping and send dust for off-site treatment and disposal.
Hydroblasting would be used to clean par's of buildirj and
this water would then be treated and disposed of with the
standing water.  Recyclable materials would be recycled.
1.  Overall Protection of Human
    Health and the Environment
2.  Compliance with ARARi

    e  Contaminant-specific
       ARARs

    •  Action-specific ARARs

    o  Location-specific ARARs

3.  Long-Term Effectiveness

    •  Magnitude of residual
       risks


    e  Ademuacy of controls
    •  Reliability of Control
4.  Reduction of Tojicity.
    Mobility and Volume
    Through Treatment

    o  Treatment process and
       remedy
Provides protection to human health and the environment
as long as the building is locked and its use is
prohibited and there is no further significant
deterioration.
Would not comply.


Would comply.

Would comply.
Source would not bo removed or treated, therefore
residual risk remains.  However, access would be
restricted so that risks would be reduced.

The long-term maintenance program is designed to
maintain the security of the building and is effective
In minimi ting trespassing.

Building access control and security are reliable at
minimizing access, although susceptible to vandalism.
Locking building and roof repair would reduce mobility
of contaminants.  Toxicity and volume of contaminants
remain unchanged.
Provides overall permanent protection to
environment.
health and
Would comply by removing and decontaminating contaminated
surfaces and debris.

Would comply wi'.b all  action-specific ARARs.

Would comply with all  location-specific ARARs.



No remaining risks after completion of remedial action.
The building decontamination and off-site treatment and
disposal procedures are proven technologies.
All technologies are very rollable.
Decontamination, off-site treatment and disposal are very
effective at reducing toicicity. mobility and volume of
contaminants in the buildings.
4874X

-------
                                                                         TABLE  I 1

                                            SUMMARY OF REMEDIAL ALTERNATIVES FOR DEBRIS AND CONTAMINATED SURFACES
                                                                                                                                           Sheet 2 of 3
Criteria
                             Alternative CS-1
                                No Action
                                                                               Alternative CS-2
                                                                  Contaminated Surfaces  Decontamination/
                                                                     Off-Site Treatment  and Disposal  .
4.  Reduction of Toxicity..
    Mobility and Volume
    Through Treatment (Con'td)

    o  Amount of hazardous
      . Material destroyed or
       treated.

    •  Reduction of toKicity.
       mobility and voluM
       ITMV).

    o  Irreversibllity of
       treatment

    o  Type and quantity of
       treatment residues

5.  Miort-Term Effectiveness

    0  Protection of community
       daring remedial actions

    e  Protection of workers
       during remedial actions
    •  Environmental Impacts

    o  Time until remedial
       response objectives are
       achieved
f.  lOBll
utabilltv
    technical Feasibility

    o  Ability to construct and
       operate technology
    o  Reliability of technology
                          None by treatment.
                          Mobility is reduced by containing contaminants
                          within building.  Toxicity and volume of contaminants
                          remains unchanged.

                          No treatment.   If building security Is breached  .
                          exposure risks increase to current levels.

                          No treatment involved.
                          No protection required.
                          Applicable OSHA regulations would be observed  to
                          prevent Markers from normal construction hazards
                          during roof repair.
                                       tal  Impacts  from remedial actions.
No envi
                          This alternative would not achieve  the  response
                          objectives.  It would take approximately I month
                          to secure the buildings.
                          Sealing of building is  easily  implemented.
                          Building access control  and  security
                          techniques are reliable  technologies.
                          they could be breached by vandalism.
                                                                            However.
                                                          All  of  the  contaminated dost (approximately 70 ey) and debris
                                                          (approximately 2,5000 cy)  would be  removed, treated and
                                                          disposed  of.

                                                          Toxicity. mobility and volume of building contaminants would
                                                          be reduced.
                                                          Treatment  is  irreversible.
                                                          No treatment residues  remain.
Ninimal risks duo to Increase In dust during remedial action.
Safeguards would bo implemented to minimi 10 these risks.

Applicable OSHA regulations and personnel protective
equipment would be used to protect workers during
implementation of remedial actions.

No environmental Impacts from remedial actions.

Time required to achieve response objectives Is approximately
12 months.  Actual remediation period Is estimated to be 3
months.
                                                          Ousting,  vacuuming,  wiping and hydroblasting technologies are
                                                          easily implemented.   Several  off-site treatment and disposal
                                                          facilities can handle the contaminated materials.

                                                          All technologies employed In this alternative ire  reliable.

-------
                                                                          TABLE 10

                                             SUMMARY OF REMEDIAL ALTERNATIVES FOR SLAG AND LEAD OXIDE MATERIALS
                                                                                                                                            Sheet 9 of It
Criteria
                                          Alternative SP-5
                               On-Slte Stabilization (Solidification)/
                              	On-Site Disposal	
6.  iMplenentability

    Technical feasibility

    o  Ability U construct
       and operate technology
                                Easily iapleoentable on site
                                using Mobile treatMent units.
                                Sufficient land is available
                                on site for operation of Mobile
                                units and disposal of treated
                                Materials.
       Reliability of
       technology
    •  Ease of undertaking
       additional reMediaf
       action, if necessary.

    •  Monitoring
       Considerations
Administrative Feasibility

•  Coordination with
   other agencies

Availability of Services
and Materials•

•  Availability of treat-
  *Ment, storage capacity
   and disposal services.
                                Stabilization/solidification
                                technology is reliable for Metal-
                                contaMinated waste.  This technology
                                Is widely used for CERCLA waste.

                                Saw as Alternative SP-3.
                                Monitoring is required because
                                treated Material is disposed of
                                on site.
                                         as Alternative SP-4.
                                    SaMe as Alternative SP-4.
    o  Availability of
       necessary equipment,
       specialists and
       Materials.
                                Sane as Alternative SP-4.
4874K

-------
                                                                         TABLE  10

                                             SUMMARY OF REMEDIAL ALTERNATIVES FOR  SLAG AND LEAD  OXIDE  MATERIALS
                                                                                                                                            Sheet  10  of  10
Criteria
           Alternative SP-5
On-Sitt Stabilization (Solidification)/
           On-S Lle_ Disposal	
    Availability of Service?
    and Materials (Cont'd)

    e  Availability of
       technologies
 Saw as Alternative SP-4.
7.  Costs

    o  Total Capital Cost (()       2.014,000

    o  Annual operation and         17,000
       Maintenance (OIK) cost
       <$/yr)

    e  Present worth* ($ based      2.303.100
       on 5.OX discount rate
       and 30-year period)



    Present worth cost includes approximately $10.000 for Alternative SP-5 for each five-year review and site assessment.
487*

-------
                                                                          TABLE  10

                                              SUMMARY Or REMEDIAL ALTERNATIVES  FOR  SLAG AND LEAD OXIDE MATERIALS
                                                                                                                                             Sheet  7  of  10
Criteria
    Key Components
I.  Overall Protection of
    Human Health and the
    Environment
2.  Compliance with ARARi

    o  Contaminant-specific
       ARMs

    o  Action-Specific ARARs
    o  Location-Specific
        ARARs

3.  Long-Term Effectiveness

    •  Magnitude of residual
       risks
            Alternative SP-5
 On-Site Stabilitation (Solidification)/
	On-Site Disposal	_^
  On-site stabitiiation/solidification
  of 9.800 and 200 cy of slag
  material and lead oxide material
  respectively, using mobile
  treatment system.  TCLP testing
  of treated material.
  On-site disposal in a protective
  manner in accordance with RCRA
  treatment standards.

  Achieves overall protection of human
  health and the environment by
  reducing the mobility of the
  contaminants.  Toxicity of cont-
  aminants would be reduced due to
  immobiIllation in stabiliied mass.
  Hilt comply with contaminant-
  specific ARARs.

  Will comply with action-specific
  ARARs

  Will comply
  Same as Alternative SP-4
    o  Adequacy of controls
    o  Reliability of Control
  These technologies are proven
  methods for handling these
  types of contaminants.

  These operations are reliable
  processes for handling the slag
  and lead oxide materials.
4874K

-------
                                                                         TABLE  10

                                             SUNMARV OF REMEDIAL ALTERNATIVES FOR SLAG AND LEAD OXIDE MATERIALS
                                                                                                                                            Sheet 8 of 10
Criteria
            Alternative SP-S
 Oiv-Site Stabiliiation (Solidification)/
	On-Site Disposal	
4.  Deduction of Toxicity,
    Mobility and Volume
    Through Treatment

    •  Treatment process
       remedy
  Reduction In Mobility of
  inorganic contmainants by
  stabilization/solidification
  process.
    o  Amount of hazardous
       Material destroyed or
       treated.
    o  Reduction of toxicity
       •obility and voliMW
       (TMV).
    o  Irreversibility of
       treatment
    o  Type and quantity of
       treatment residues
S.  Short-Term Effectiveness

    o  Protection of community
       during remedial actions
    o  Protection of Moriers
       during remedial actions

    o  Environmental impacts

    0  Tl«e until rmedial
       response objectives
       are achieved
  Approximately 9.800 and 200 cy
  of slag and lead oxide Material
  respectively would be removed and
  treated en-site.

  Nobility of contaminants would be
  reduced.  Reduction of toxicity of
  contaminants due to immobilisation
  in stabilized Mass.  Volume of
  solidified Material may increase up
  to 40 percent depending on additives
  used.

  Treatment oroces is essentially
  irreversible over short-term).
  Long-term, irreversibility is
  not known. '

  Treatment Immobilizes contaminants
  although immobile contaminants remain
  in treated material.
  Same as Alternative SP-3.  In
  addition, increased dust emissions
  due to on-site treatment.

  Same as Alterative SP-4.
  Same as Alternative SP-4.

  Overall remediation period is
  approximately IS months.  Actual
  remediation time is estimated to
  be 3 months.

-------
                                                                          TABLE  10

                                             SUMMARY OF REMEDIAL ALTERNATIVES FOR SLAG AND LEAD OXIDE MATERIALS
                                                                                                                                            Sheet 5 of 10
Criteria
                                Alternative SP-I
                                   No Action	
  Alternative SP-3
  Off-Site Flame
  Reactor	
      Alternative SP-4
 On-Site Hydro-Metallurgical
 Leachino/On-Site Disposal
                     (Confd)
    o  Reliability of technology  No treatment technology
                                  involved.  Monitoring is
                                  reliable.
       Ease of undertaking
       additional remedial
       action, if necessary.
    o  Monitoring Considerations
    Administrative feasibility

    o  Coordination with other
       agencies
                           If Monitoring  indicates that
                           future action  is necessary, wist
                           go through  the FS/ROO process
                           again.
                           Long-term monitor ing required.
                           Mi grat i on/exposure
                           pathways  can be Monitored.  .
                          Coordination required with
                          appropriate agencies for long
                          time period for Monitoring
                          and reviewing site conditions.
                                                                  Treatment technology
                                                                  to date is not yet
                                                                  proven for CERCLA waste
                                                                  on a full-scale basis.
                                                                  However, proven for elec-
                                                                  tric arc furnace dust.
If additional slag and
lead OHide Material
requires treatment, it
can be easily removed
during remedial
activities.

No MonitorIng required
after remediation is
completed.
Coordination with State
and local agencies re-.
quired.  Transportation
of the waste to an off-
site facility requires
coordination with DOT
and local traffic
department.
Treatment technology is pro-
••en and reliable for extracting
metals fro* ores, however,
bench- or pilot-scale
treatability study required to
develop design criteria for
slag and lead oxide Materials.
Treatment technology is not yet
proven for CERCLA waste.

Saw as Alternative SP-3.
In addition if treatment
objectives are not being Met,
design criteria could be re-
evaluated.
Long-term Monitoring Is required
due to disposal of treated
Materials on site.
Coordination with State and
local agencies required.
    in*
liability a
 Materials
       Availability of treat-
       ment, storage capacity
       and disposal services.
                          No  treatment, storage or
                          disposal  facilities required.
Commercial facility not
currently available,
although It is expected
to be available in a
year.
Several vendors can provide
mobile treatment units.  Suf-
ficient space is available
on site for treatment and
disposal of treated material.
4874K

-------
                                                                         TABLE  10

                                             SUMMARY Of REMEDIAL  ALTERNATIVES  FOR SLAG AND LEAD OXIDE MATERIALS
                                                                                                                                           Sheet 6 of 13
Criteria
Alternative SP-I
   MB Action
                                                                           Alternative SP-3
                                                                           Off-Site MJ
                                                                          _Reacloc	
     Alternative SP-4
Oil-Site Hydro-Metallurgical
Leathino/On-Site Disposal
       Availability of necessary  Equipment and specialists
       equipment,  specialists     for Monitoring and i•piemen-
       ami Materials.              ting public  awareness  program
                                  are readily  available  locally.
    e  Availability of            None required.
       technologies
7.  CfllU

    •  Total Capital Cost ($)           0

    •  Annual operation and        25.000
       Maintenance (MM) cost
       ($/yr)

    •  Present worth* ($ based    439.900
       on 5.OX discount rate
       and 30-year period)
                                                                         Only one vendor is
                                                                         available for this tech-
                                                                         nology  (at this tie*).
                                                                         therefore competitive
                                                                         bids May not be
                                                                         available.
                                                                         Treatment technology
                                                                         May not be available
                                                                         on full-scale basis
                                                                         at the time of remediation.
                                                                         4.215.100"

                                                                                 0"



                                                                         4.215.100"
                                                                      All necessary equipment.
                                                                      specialists  and materials aro
                                                                      readily available from
                                                                      several vendors.  However.
                                                                      modified  design May be •
                                                                      required  for Materials
                                                                      in question.-

                                                                      TreatMent technology  is proven
                                                                      and readily  available.
                                                                       2.9M.400

                                                                       17.000



                                                                       3.269.500
    Present worth cost includes approximately $70.000 for Alternative SP-I  and $10.000 for Alternatives SP-4 for each five-year review and site assessment.
    This cost estimate is based on the assumption that treated materials would be recycled.
    Cost may increase if Markets are not available and treated material would have to be disposed of.
4B74K

-------
                                                                         TABLE  10

                                             SUMMARY OF REMEDIAL ALTERNATIVES FOR SLAG AND LEAD OXIDE MATERIALS
                                                                                                                                            Sheet 3 of 10
Criteria
      Alternative SP-l
         Mo Action	
                                                                            Alternative SP-3
                                                                            Off-Site Flaw
                                           Alternative SP-4
                                      On-Site Hydro-Metallurgical
                                      LeachinpyOn-Site Disposal
4.  Reduction of Toxicity.
    Mobility and Volume
    Through Treatment (Cont'd)

    o  Irreversibility of
       treatment
No treatment Involved.
Treatment process is
irreversible.
                                                                             Treatment process is
                                                                             irreversible.
    o  Type and quantity of
       treatment residues
5.  Short-Term Effectiveness
                         »
    o  Protection of comw^ilty
       during remedial actions
All the contaminants remain
on site.
Short-term risk to community
is not applicable since no
remedial action involved.
No treatment residues
on site.  Treated slag
and lead oxide could
possibly be recycled.
Temporary increase in
direct contact risks and
inhalation of fugitive
dust to community.
Oust control measures
would be provided.
                                                                             Minimal  contaminated  residues
                                                                             remain in treated residues.
                                                                             Treated  residue is expected
                                                                             to pass  TCLP.
                                                                             Same as Alternative SP-3.
                                                                             In addition,  increased  risk
                                                                             due to use of chemicals in
                                                                             on-site treatment.
    o  Protection of workers
       during remedial actions
No significant short-term risk.
                                        Increased risk of dermal
                                        contact and inhalation
                                        of dust to workers.
                                        However personal
                                        protective equipment
                                        would be provided.
                                     Same as Alternative SP-3.  only
                                     slightly increased risk due
                                     to performance of treatment
                                     on site.
4874K

-------
                                                                         TABLE 10

                                             SUMMARY OF REMEDIAL ALTERNATIVES FOR SLAG AND LEAD OXIDE MATERIALS
                                                                                                                                            Sheet  4 of  10
Criteria:
      Alternative SP-I
     	No Action
  Alternative SP-3
  Off-Site Flaw
  Reactor	
      Alternative SP-4
 On-Site Hydro-Metallurgical
 Leachino/On-Site Disposal
    o  Environmental impacts
Continued contamination of
surface water, groyndwater, soils
and air fro* existing conditions.
    o  lime until remedial
       response objectives are
       achieved
6.  Implementability

    Technical feasibility

    o  Ability to construct and
       operate technology
Natural attenuation takes
long period of tine, over
30 years.  It would take 3
months to implement the
•onitoring and institutional
program.
No construction involved.
Monitoring wells are already
installed.
Increase in traffic.
noise and dust due to
remedial activities.
Erosion and sediment
control Measures would
be provided to minimize
contaminant Migration
during remedial
activities.  In addit-
ion.1 potential accidents
and spillage would
exist during off-site
transport of contam-
inated Material.

Overall remediation
period is approximately
18 Months.  Actual reme-
diation period is esti-
mated to be approxi-
mately 6 months.
Technology is being-
tested under EPA's SITE
Program currently.
The vendor envisions a
full-scale unit for
treating CERCLA waste to
be operational in one
year.  Contaminated slag
and lead oxide material would
have to undergo a series
of analyses prior to
acceptance for treatment
at an off-site facility.
Same as Alternative SP-3.
however, slightly less traffic.
Overall remediation period is
approximately 16 months.
Actual remediation period is
estimated to be 4 months.
Easy to implement on-site.
Sufficient land is available
on site for operation of
mobile system.  Bench or pilot-
scale treatability study would
be needed to develop design
criteria.
4874K

-------
                                                                         TABLE 10

                                             SUMMARY OF REMEDIAL  ALTERNATIVES  FOR SLAG AND  LEAD OXIDE MATERIALS
                                                                                                                                            Sheei I  of  10
Criteria
      Alternative SP-1
         No Action
  Alternative SP-3
  Off-Site Flaw
  Reactor	
      Alternative SP-4
 On-Site Hydro-Metallurgical
 Leachino/On-Site Disposal
    Key Components
1.  Overall Protection of Human
    Health and the Environment
2.  Compliance with ARARs

    o  Contaminant-specific
       ARARs
    o  Action-specific ARARs


    o  Location-specific ARARs
Long-ten* Monitoring
5-year reviews.
Public awareness and education
program.
There Is essentially no reduc-
tion in toxicity. Mobility or
volume of contaminants.
Contaminant migration Is
monitored but risk is not reduced.
Migration of contaminants from
the slag and lead oxide mater-
ials to the surface water.
groundwater. soil and air would
continue.  This alternative does
not meet any of the remedial
objectives and therefore is not
protective of human health  .
and the environment.
Mould not comply
Contaminants remain on-site.
Would comply with ARARs
associated with monitoring.

Would not comply
Off-site treatment of 9.800
and 200 cy of slag material
and lead oxide material,
respectively, at a RCRA per-
mitted flame reactor
facility.  Possibly
recycle treated matrial
as fill material or road
aggregate.

The removal and treat-
ment of the slag and
lead oxide materials
would reduce the
toxicity. mobility and
volume of hazardous
contaminants in the
materials, thereby        , .
significantly reducing
the potential risks to
human health and
the environment.
Results in overall,
permanent protection
of human health and
the environment.
Would comply.  Removes
slag and lead oxide
materials from the site.

Would comply with all
action-specific ARARs.

Would comply
On-site treatment of 9,800 and
200 cy of slag material and lead
oxide material, respectively.
using a hydrometallurgical
leaching process.  TCLP testing of
treated material, followed by
on-site disposal in protective
manner in accordance with
RCRA treatment standards.

May reduce the public health
and environmental risks
associated with concerned
exposure pathways, and may
result in overall protection
of human health and the
environment.  The uncertainty
associated with this alterna-
tive exists due to the pre-
sence of multiple metals.
Technology never used on these
types of materials.
Treatability studies would be
performed to determine if
treatment objectives can be
achieved..
May comply.  Some uncertainty
exists due to multiple
contaminants.

Would comply with all action-
specific ARARs

Would comply
4874K

-------
                                                                          TABLE   10

                                             SUMMARY OF REMEDIAL ALTERNATIVES FOR SLAG AND LEAD OXIDE MATERIALS
                                                                                                                                            Sheet 2 of 10
Criteria
      Alternative SP-1
         Ma Action
  Alternative SP-3
  Off-Site Flaw
  Reactor	
      Alternative SP-4
 On-Site Hydro-Metallurgical
 Leachino/On-Site Disposal
3.  Long-Term Effectiveness

    o  Magnitude of residual
       risks
    o  Adequacy of controls
Source Mould not be removed or
treated.  Existing risk would
essentially remain.  Natural
attenuation is very slot* process
for type of contaminants involved
and would lead to surface and
groundwater contamination.

Potential exposures
remain the same. '
    o  Reliability of Control
Monitoring program is reliable
to assess contaminant
migration.
4.  Reduction of Tout city.
    Mobility and Volume
    Through Treatment

    •  Treatment process and
       remedy
     o  Amount of hazardous
        material destroyed or
        treated.
No treatment employed,
conditions  (toxicity, mobility
and volume  of contaminant)
remain  the  sa
 48:
     o   Reduction  of  toxicity.
        mobility and  volume
        (TMV).
None by  treatment.  Natural
attenuation continues to take
place.
None by  treatment.
Slag and lead oxide
materials would be
removed and treated
off-site, therefore, no
residual risk remains.
Flame reactor technology
is proven for electric
furnace dust, but
being tested for
CERCLA waste.
These operations are
considered reliable
for handling metal
wastes.
Slag and lead oxide
materials would be eliminated
as a source of
contamination.

Approximately 9,800
and 200 cy of slag and
lead oxide material.
respectively removed
and treated off site.
Complete reduction of
toxicity. mobility and
volume of contaminants
   «l«o and IIMM! oxH* ««teri»1.
After remediation is completed
there are minimal remaining
risks.
 Treatability studies would be
 performed to test if treatment
 objectives can be achieved.
 Assuming these objectives can
 be met. then these technologies
 would adequately handle these
.types of contaminants.  .

 Assuming treatability studies
 show that treatment objectives
 could be met. then these
 technologies would be reliable
 processes for handling the
 slag and lead oxide materials.
 Some uncertainty associated
 with multiple contaminants.
 Same  as  Alternative SP-3,
 assuming treatability studies
 show  that treatment objectives
 would be met.

 Approximately  9.800 and 200  cy
 of  slag  and lead oxide materials
 removed  and treated assuming
 treatability studies demon-
 strate that treatment objec-
 tives could be met.

 Same  as  Alternative SP-1
 assuming treatability studies
 demonstrate that treatment
 «M»ctiv»« could to «*t.

-------
                                                                         TABLE  8 -

                                                                  LOCATION-SPECIFIC ARARS
REGULATORY LEVEL
Federal
Federal
New Jersey
ARARS
Fish and Wildlife Coordination
Act 16 USC 661 '
National Historic Preservation
Act
New Jersey Rules on Coastal
STATUS
Relevant and
Appropriae
Relevant and
Appropriate .
To be considered
REQUIREMENT SYNOPSIS
Details requirements with regard to the protection of
fish and wildlife.
Sets forth requirements for the preservation of items
of cultural or historic value.
Regulates the development of coastal areas in certain
     New Jersey
Resources and Development
(7:7E-1.1 et seq)

Delaware River Basins Compact
NJSA SB:IB-IB
To Be Considered
                                                                                                  counties in the State of New Jersey.
Regulates all projects significantly affecting water
resources  within  the jurisdiction  of  the  Delaware
River Basin Commission.
      1)  Applies to alternatives including discharge to surface waters.
      4878K
i,

-------
         TABLE  9

     CONTAMINANT - SPECIFIC ARARs
(ug/l unless otherwise noted)
COMPOUND
Arsenic
Barium
Cadmium
Chromium
Copper
Lead
Mercury
Nickel
Selenium
Silver
Zinc
Cyanide
PH
TOS
BOO (5 day)
FEDERAL CWA
woe
(FISH ft WATER)
-
.
10
50
1000
SO
-
13.4
'
SO
5000
200
.
-
-
FEDERAL
SOWA
' MCLs*
SO
'1000
10
50
1000
156
2
-
10
50
-
- •
-
-
-
FEDERAL
SOWA NJ
MCLGs3 WQ
-
5000
5
1.2
1300
20
-
-
•
-
-
-
-
-
,
SURFACE
STANDARDS4
50
1000
10
50
-
50
2
-
10
50
-
-
6.5-8.5
-
-
1 Federal Clean Water Act Water Quality Criteria.
2 Federal Safe Drinking Water Act. Maximum Contaminant levels.
3 Federal Safe Drinking Water Act. Maximum Contaminant Level Goals.
4 New Jersey Surface Water Quality Standards.
5 New Jersey Ground Water Quality Standards.
6 EPA Action Level for Lead - Hay 7. 1991.
7 EPA recommended criterion for the protection of human health from consumption of aquatic organisms
8 EPA recommended criterion for the protection of aquatic life due to chronic toxicity.
9 EPA recommended criterion for the protection of aquatic life due to acute toxicity.
SITE-SPECIFIC
NJ GROUND EPA CRITERIA FOR
WQ STANDARDS5 SURFACE DISCHARGE
. SO 0.147
1000
10 0.668
50 II8
2.o"
50 1.38
2 0.0128
.
10 58
50 1.29
S98
200
5-9
500.000 NA
3.000
at a 10-* risk level.

-------
                                                                      TABLE  7

                                                                ACTION-SPECIFIC ARARS
                                                                                                                                        Page 1 of 2
REGULATORY LEVEL
ARABS
STATUS
REGULATORY SYNPOS15^
A.  Common to all Alternatives
OSHA - General Industries Standards       Applicable
(29 CFR 1910)
                                    OSHA - Safety and Health Standards        Applicable
                                    (29 CFR 1926)
                                    OSHA - Recordkeeping. Reporting and       Applicable
                                    Related Regulations
                                    (29 CFR 1904)

                                    RCRA TSOF Regulation                      Relevant and
                                    (40 CFR 264 and 265 subparts A. 8. C.     Appropriate
                                    D. E. F. fi. L. and N)
                                    RCRA Requirements                         Relevant and
                                    for transporting waste for                Appropriate
                                    Off-Sito Disposal (40 CFR 263)3

                                    RCRA Standards for Generators of          Applicable
                                    Hazardous Waste (40 CFR 262)
                                                                              V -'.
                                    RCRA Nonhaiardous Waste Management        Applicable
                                    Standards (40 CFR 257)z

                                    RCRA Groundwater Nonitaring Requirements  Applicable
                                    (40 CFR 264 Subpart F)4

                                    National Emission Standards for           Relevant and
                                    Hazardous Air Pollutants (NESHAPS)        Appropriate
                                    (40 CFR 61)
                                    DOT Rules for Hazardous         ,         Applicable
                                    Materials Transport (49 CFR 171)3

                                    New Jersey Standards for the              Relevant and
                                    Design and Operation of Hazardous         Appropriate
                                    Waste Treatment Facilities (MAC 7:26)
                  These standards regulate the 8-hour time weighted
                  average concentration for  worker exposure  to  various
                  compounds.    Timing   requirements   for  workers   at
                  hazardous wastes operations are also specified.

                  This regulation specifies the typo of safety
                  equipment and  procedures to  be followed during site
                  remediation.

                  This regulation outlines the recordkeeping and
                  reporting requirements for an employer under OSHA.
                                                            Provides standards for hazardous waste treatment
                                                            facilities with regard to design and operation of
                                                            treatment and  disposal  systems  (ie.  general  facility
                                                            standards, landfills,  incinerators, containers, etc.)

                                                            Provides manifest and  record keeping require-
                                                            ments for generators of hazardous waste.
                                                            General standards for generators of
                                                            hazardous waste.

                                                            Provides standards for the management of non-
                                                            hazardous waste under RCRA Subpart 0.

                                                            This regulation details requirements for
                                                            groundwater monitoring programs.

                                                            Provides standards for acceptable limits for
                                                            specific chemicals in air emissions.  Requirements
                                                            address  operational,  record   keeping,   and  general
                                                            emission  standards   that  apply   to  air  pollution
                                                            control equipment.

                                                            Provides requirements for the transportation
                                                            of hazardous waste.

                                                            This regulation outlines general waste facility
                                                            requirements with regard to waste analysis,
                                                            security    measures.    inspection    and    training
                                                            requirements.
4878K

-------
                                                                 TABLE  7   (Cont'd)

                                                                ACTION-SPECIFIC ARABS
                                                                                                                                        Page 2 of 2
REGULATORY LEVEL
                                    ARAKS
                                                                          STATUS
                                                            REGULATORY SYNPOSIS
B.
    Standing Water and Sediment
    Treatment
C.
Slag and Lead Oxide Materials.
Debris and Contaminated
Surfaces
New Jersey Noise Pollution                Applicable
Regulations (NJAC 7:29)

NPOES Regulations                         Applicable
(40 CFR 122)
New Jersey Pollution Discharge            Applicable
Elimination System Regulations
NJAC (7:14A)

RCRA Closure and Post-Closure           .  Relevant and
Standards (40 CFR 264. Subpart G)         Appropriate
                                RCRA Subtitle D Nonhazardous              Applicable
                                Waste Management Standards              ''
                                (40 CFR 257)*

                                RCRA Land Disposal Restrictions         "• Applicable
                                (LORs) (40 CFR 268)
                                    New Jersey RCRA Closure and Post-         Relevant and
                                    Closure Standards (NJAC 7:26)             Appropriate
                                    New Jersey Standards for Generators       Applicable
                                    of Hazardous Waste (NJAC 7:26)

                                    New Jersey Air Pollution Control          Applicable
                                    Requirements (NJAC 7:27)

                                    New Jersey Soil Erosion and Sediment      Applicable
                                    Control Act Requirements'
                                                                                            Provides standards for the control  of noise
                                                                                            pollution.

                                                                                            Provides regulations for discharge  of the treatment
                                                                                            system effluent.   Refers to effluent  limitations  for
                                                                                            discharge to surface water.

                                                                                            Provides regulations for discharge  of pollutants
                                                                                            to surface water of the State.
                                                                                                This regulation details specific requirements for
                                                                                                closure and post-closure of hazardous waste
                                                                                                facilities.

                                                                                                Provides regulations for the management of non-
                                                                                                hazardous waste.
                                                                                                Regulates land disposal of hazardous »iste.  Provides
                                                                                                treatment  levels  which  must   be  met  before  land
                                                                                                disposal of hazardous waste may occur.

                                                                                                This regulation details specific requirements for
                                                                                                closure   and   post-closure    of    hazardous   waste
                                                                                                facilities.

                                                                                                General Standards for generators of hazardous waste.
                                                                                                Provides guidelines for the control of Air
                                                                                                contaminants.

                                                                                                Provides guidelines for soil erosion and sediment
                                                                                                control plans.
     1) Applies to alternatives remediating slag and lead oxide materials only.

     2) Applies to alternative which involve en-site disposal.

     3) Applies to alternatives which Involve off-site transportation

     4) Applies to monitoring of ground and surface waters.
4878K

-------
                                                                       TABLE 6

                                                   CONTAMINANT-SPECIFIC ARABS.  CRITERIA AND GUIDANCE
                                                                                                                                            Pag*  1 of 2
REGULATORY LEVEL
ARAR IDENTIFICATION
STATUS
REGULATORY SYNOPSIS
FS CONSIDERATION
federal
Federal
CWA Water Quality Criteria      Relevant and
(WQC) for protection of      ,  Appropriate
Human Health and Aquatic Lift2
federal
Federal
RCRA Maximum Contaminant1
Levels (HCLs)
SDWA Maximum Contaminant1
Levels (NCLs)


SOWA MCL Goals1
To be Considered
To be Considered
To Be Considered
Federal
Federal
Federal
Federal
RCRA Identification of
Hazardous Waste (40 CFR 261)
Applicable
h:BA Land Disposal Restriction  Applicable
(LDR) (40 CFR 268)
National Ambient Air Quality    Applicable
Standards (MAAQS) (40 CFR 50)
EPA Risk Reference Doses
(RfOs)
To Be Considered
Contaminant levels regulated by
WQC are provided to protect human
health in relation to exposure from
drinking water and from consuming
aquatic organisms (primarily fish).

Provides standards for 14 toxic com-
pounds and pesticides for protection
of groundwater.  These standards are
equal to the NCLs established by
SDWA.
Provides standards for toxic
compounds for public drinking
water.

EPA has promulgated contaminants 1eve's
and has proposed others for public
water system.  The MCLGs art health
goals and are set at levels that
Mould result In no known or anticipated
adverse health effects with an adequate
margin of safety.

Provides regulations concerning
identification and classification of
RCRA Hazardous Waste.
                                                              WQC  are relevant and appropriate to
                                                              evaluation of surface .water discharge
                                                              acceptability.
The promulgated values are included
in the SOWA NCLs:  The combined
standards are compared with the
maximum contaminant levels at the NL
site to determine the level of
contamination.

The promulgated values are used as
standards to determine the level of
treatment for groundwater discharge.

NCLGs art used as reference values to
indicate contaminant levels for the
NL site.
Will bt used to determine RCRA listed
and characteristic waste present at
the NL site.
                    Limits land disposal options and provides Treatment standards or BOAT require-
                    treatment standards for contaminants      ments must be met prior  to land dis-
                    prior to disposal.                        posal.  Effective for CERCLA soil
                                                              and debris as of November 1990.
These standards provide acceptable
limits for particulate matter, sulfur
dioxide, nitrogen dioxide, carbon
monoxide, ozone, and lead that must
not be exceeded in ambient air.

RfD's are considered to be the levels
unlikely to cause significant adverse
health effects associated with a
threshold mechanism of action in
human exposure for a lifetime.
                                                              Remediation technologies that could
                                                              release contaminants into the air
                                                              will  be designed to meet these
                                                              standards.
EPA Reference Doses are used to
characterize risk associated with
non-carcinogens in various media.
487BK

-------
                                                                  TABLE  f>  (Cont'd)

                                                   CONTAMINANT-SPECIFIC ARABS. CRITERIA AND GUIDANCE
                                                                                                                                            Page 2 of 2
REGULATORY LEVEL
ARAR IDENTIFICATION
STATUS
REGULATORY SYNOPSIS
FS CONSIDERATION
New Jersey



Mew Jersey



New Jersey




New Jersey



New Jersey
New Jersey Regulations
for the Identification of
Hazardous Waste (NJAC 7:26-6)

New Jersey Groundwater '
Quality Standards


New Jersey Safe OHnking '
Mater Act Max I MM Contaminant
Levels (NCL's) (NJAC 7:10-16)


New Jersey State Water2
Standards (NJAC 7:9-4)
New Jersey Ambient Air
Quality Standards
Applicable
To Be Considered
To Be Considered
Relevant and
Appropriate


Applicable
Provides regulations concerning the
identification and classification of
Hazardous Waste

Provides quality standards for
groundwater based on aquifer
characteristics and use.

Provides quality standards for
drinking water.
Provides quality standards for
surface water.
Provides guidance regarding
air Missions.
Will be used to determine listed and
characteristic hazardous waste at the
HL site.

The levels will be compared to levels
at the NL site to determine
contaminant Migration.

These levels will be compared to
contaminant levels at the NL site
to determine contaminant
migration.

These standards will be used to
determine appropriate levels for
discharge to surface water.

Remedial activities which cause
air emissions will conform to
these standards.
1)  Applies to alternatives including groundwater monitoring

2)  Applies to standing water treatment alternatives
4878K

-------
                       TABLE 4
              »t»utt» ef th» Nmli Arwlytit

                    of TCl> extract*


            •LAG AND LEAD OXIDE PILES  (1991)

              Cenetntrctlen rtpertws in «8/l
cinr.t •          C8794   urn   ear»6   e*797   ewe   0*799
loeitie-.:          it«d   ind   A rut  • nu  C rut  6 nu  Otttction  Regulatory
              Oxidt A 0<<0t I                               limit

8«--:--
:»s-- j-
:--9--.j-
iti:
••*•:.-•
Se.e- j-
s ..«•
ND
N:
24.1
ND
. ; -620
ND
N:
fc'S
0.262
0.199
26.3
ND
2750
ND
ND
NS

ND
1.4
ND
1.0
ND
ND
ND
ND
ND
1.6
ND
4.9
ND
ND
ND
ND
ND
5.3
ND
5.1
ND
ND
ND
ND
ND
0.69
ND
4.5
ND
ND
ND
0.10 5.0
O.io 100.0
o.io 1.0
0.10 5.0
0.10 5.0
0.10 0.2
o.io 1-0
0.10 5.0
     ct:t:T*s
OOR QUALITY
          IAL
                                                           ORIGIN

-------
                           TABLE 5

                    •t»utt»'»f tht HtUlt

             STANDING WATER SAMPLES (1991)
Clif.t*
tOCItion:
Unit:
A,,^r

»•§»••: e
IfyllihT
C»S- IT
f'tr-
-------