EPA-R2-73-281
July 1973                     Environmental Protection Technology Series
Electrical Power Consumption  For
Municipal  Wastewater Treatment
                                    National Environmental Research Center

                                    Office Of Rearch And Development

                                    U.S. Environmental Protection Agency

                                    Cincinnati, Ohio 45268

-------
            RESEARCH REPORTING SERIES
Research reports of the  Office  of  Research  and
Monitoring,  Environmental Protection Agency, have
been grouped into five series.  These  five  broad
categories  were established to facilitate further
development  and  application   of   environmental
technology.   Elimination  of traditional grouping
was  consciously  planned  to  foster   technology
transfer   and  a  maximum  interface  in  related
fields.  The five series are:

   1.  Environmental Health Effects Research
   2.  Environmental Protection Technology
   3.  Ecological Research
   U.  Environmental Monitoring
   5.  Socioeconomic Environmental Studies

This report has been assigned to the ENVIRONMENTAL
PROTECTION   TECHNOLOGY   series.    This   series
describes   research   performed  to  develop  and
demonstrate   instrumentation,    equipment    and
methodology  to  repair  or  prevent environmental
degradation from point and  non-point  sources  of
pollution.  This work provides the new or improved
technology  required for the control and treatment
of pollution sources to meet environmental quality
standards.

-------
                                                        EPA-R2-73-281
                                                        July 1973
             ELECTRICAL  POWE.R CONSUMPTION FOR MUNICIPAL

                         WASTEWATER TREATMENT
                                  By

                             Robert Smith
            Advanced Waste Treatment Research Laboratory
               National Environmental  Research Center
                        Cincinnati, Ohio  45268
                        Program Element  1B2043
               NATIONAL ENVIRONMENTAL  RESEARCH CENTER
                  OFFICE QF RESEARCH AND MONITORING
                U.S.  ENVIRONMENTAL PROTECTION AGENCY
                        CINCINNATI, OHIO 45268
For sale by the Superintendent of Documents, U.S. Government Printing Office, Washington, D.C. 20402 - Price $1.25

-------
                            ABSTRACT
Electrical power consumption by most conventional and advanced
processes for treating municipal wastewater has been estimated
on a unit process basis.  Electrical power for complete plants
has been estimated by adding power consumption for individual
processes and plant utilities.  Electrical power consumption
for wastewater treatment has been compared to other consumptive
uses of electrical power.
                               111

-------
                       TABLE OF  CONTENTS

                                                            Page
INTRODUCTION                                                  3
PRELIMINARY TREATMENT                                         7
INFLUENT PUMPING                                              9
SEDIMENTATION                                                11
TRICKLING FILTERS                                            14
ACTIVATED SLUDGE PROCESS                                     15
SLUDGE HANDLING AND DISPOSAL                                 17
CHLORINATION                                                 35
LIGHTS AND MISCELLANEOUS  POWER                              37
PRODUCTION OF  POWER BY UTILIZATION OF SLUDGE GAS            41
TOTAL ELECTRICAL POWER CONSUMPTION FOR CONVENTIONAL PLANTS  43
EXPENDITURE FOR ELECTRICAL POWER IN CONVENTIONAL PLANTS     51
ELECTRICAL POWER REQUIREMENTS  FOR ADVANCED PROCESSES        61
ELECTRICAL POWER REQUIREMENTS  FOR ADVANCED PROCESS TRAINS   71
COMPARISON WITH OTHER  CONSUMPTIVE USES                      77
APPENDIX                                                     85
                                 v

-------
                             FIGURES



Number                                                    Page

   1.  Sludge Handling Schemes                              5

   2.  Installed Electrical Horsepower for Settlers
       versus Length of Settler
                                                           12
   3.  Installed Electrical Horsepower for Settlers
       versus Design Capacity                              13

   4.  Number of Anaerobic Digesters per Installation
       versus Total Volume of Di'gester Installation        22

   5.  Installed Horsepower for Anaerobic Sludge Digester
       Heater and Heat Exchanger                           24

   6.  Total Installed Electrical Horsepower for Vatcuum
       Filters                                             29

   7.  Electrical Energy Requirements for Multiple           ,
       Hearth Furnaces                                     33

   8.  Estimated Floor Area for Wastewater Treatment
       Plants                                              38

   9.  Electrical Energy Requirements for Lighting and
       Miscellaneous Power                                 39

  10.  Electrical Energy Consumption by Municipal Wa'ste^
       water Treatment Plants versus Plant Size            49

  1].  Annual Expenditure for Electrical Power in
       Conventional Plants versus Plant Size               57

  12.  Cost of Electrical Power versus Daily Usage         59

  13.  Electrical Energy Requirements for Microstireens     62

  14.  Electrical Energy Consumption for Tertiary Waste*
       water Trains versus Plant Size                      75
                               VI

-------
                             TABLES
Number                                                     Page

    I    Electrical Energy Requirments for Wastewater
         Treatment Plants - Primary - Scheme  I               44

   II    Electrical Energy Requirements for Wastewater
         Treatment Plants - Primary - Scheme  II              45

  III    Electrical Energy Requirements for Wastewater
         Treatment Plants - Activated Sludge  - Scheme  II     46

   IV    Electrical Energy Requirements for Wastewater  i
         Treatment Plants - Activated Sludge  - Scheme  III    47

    V    Electrical Energy Requirements for Wastewater
         Treatment Plants - High Rate Trickling Filter  -
         Scheme  II               ,                            48

   VI    Cost of Electrical Power  - Primary - Scheme I       52

  VII    Cost of Electrical Power  - Primary - Scheme II      53

 VIII    Cost of Electrical Power  - Activated Sludge -
         Scheme  II                                           54

   IX    Cost of Electrical Power  - Activated Sludge -
         Scheme  III                                          ^5

    X    Cost, of Electrical Power  i- Trickling Filter -
         Scheme  II                                           56

   XI    Estimated Electrical  Power Corlsumption for
         Alternative Tertiary  Treatment Trains after
         Secondary Treatment Plant Size 1 mgd               72

  XII    Estimated Electrical  Power Consumption for
         Alternative Tertiary  Treatment Trains after
         Secondary Treatment Plant Size 10 mgd               73

 XIII    Estimated Electrical  Power Consumption fo'r
         Alternative Tertiary  Treatment Trains after
         Secondary Treatment Plant Size 100 mgd              74

  XIV    Percentage Distribution of Mining and Manu-
         facturing KWHRS by Major  Groups of SIC for
         Investor-Owned Electric Utilities in U.S.           78

   XV    Consumption of Electrical Energy Based on the
         1968 Inventory of Municipal Waste Facilities        79
                                vii

-------
                           CONCLUSIONS
Electrical power consumed in municipal wastewater treatment is
about 1% of the average residential consumption of electrical
power when the distribution of treatment schemes given in the
1968 Inventory of Municipal Waste Facilities is used as a basis,
If all communities were served by activated sludge plants, the
electrical power used will be about twice this amount.  This is
equivalent to about 15 watts per household.  Thus, for complete
secondary treatment, the power consumed is about equivalent to
24 hour operation of one desk lamp per household.  The power
consumed by tertiary treatment depends on the processes used,
but for the Lake Tahoe system of tertiary treatment, the power
consumed is about 40-50% greater than the power consumed in
conventional activated sludge treatment.

-------
                          INTRODUCTION
This report contains estimates of electrical power consumption
for most of the conventional and advanced processes used  to  treat
municipal wastewater.   Much of the  inforKbtion  was taken  from
literature available from equipment manufacturers and some in-
formation was available from reports on EPA-sponsored research
projects.  The assistance of applications engineers representing
the equipment manufacturers has been invaluable  in clarifying
important points  and in the contribution of technical information
not available in  the open literature.  This report could  not have
been completed without  their generous contributions.  The detailed
cost estimates reported from the South Lake Tahoe Public  Utility
District in California  have been most useful.
The first part of the report is devoted to detailed calculations
of electrical power consumption for individual  conventional
processes.  These estimates are then summed for  primary,  trickling
filter, activated sludge plants and the sludge  handling schemes
selected are shown in Figure 1.  Estimates of mechanical  and
electrical energy available from the use of anaerobic digester
off-gas are made  and these are compared to the  energy expended
in operation of the plant.  The cost of electrical power  was taken
from the report "Typical Electric Bills 1970" by the Federal Power
           2
Commission.  A detailed rate schedule currently  used by the  Cincin-
nati Gas and Electric Company was used to convert the estimated
power consumption values to expenditure for electrical power.
The second part of the  report presents detailed  computations of
electrical power  consumption for the advanced or tertiary processes
to be used downstream of secondary processes.   Estimates  of  electrical
power usage made  at Lake Tahoe were the principal source  of  this
information.  Electrical power consumption estimates were then
summed for various alternative tertiary treatment trains.

-------
Finally, the electrical power used in treatment plants is related
to other consumptive uses such as the typical residental, use of
electrical power.  In this way the use of electrical power in
treatment of wastewater is put into perspective with the national
scene.

-------
1


Primary
Settler:

<
i
2
4

Aerator

X"~X 3
/Final ^
Uet
<

tier/
> 5
I 6
                                                    Anaerobic  Digester
                     Sludge  Drying Beds
                         SLUDGE  HANDLING  SCHEME I

• _
Primary
Settler

<
•
	 	
4
Aerator

(FinaA „
\Sett ler/
<
Thickener '
> 5
i 6
Incinerator
                         Vacuum
                         Filter
Sludge
Holding
Tank
                          10

                         SLUDGE HANDLING SCHEME  II

                                      5
Anaerobic
Digester
                             Figure 1

-------
             SLUDGE HANDLING  SCHEME IH
Thickener

                                Air Flotation
                                Thickener
                            Sludge Holding Tank
                      Vacuum  Filter
                                                   Incinerator
                                                      10
                                             Figure 1  (Cont'd.

-------
PRELIMINARY TREATMENT
Preliminary treatment  is  a  generic  term which  includes  processes
such as bar screens, comminutors, grit removal,  and flow  measure-
ment.  The electrical  power consumption for  these processes  is
comparatively small.
Bar screens are  recommended for  installation upstream of  the in-
fluent pumps to  remove debris which would  interfere with  the oper-
ation of the pumps.  An average  of  about 5 cu. ft. of debris per
million gallons  is  removed.  The bar  screen  is cleaned  of  debris
by a rake which  travels about 7.5 ft/sec and operates for  a  maximum
of about 6 minutes  an  hour.  The channel which serves the  bar screen
is sized for a velocity of  about 2  ft/sec  at average flow.   Ac-
cording to manufacturer's literature   the  minimum size  motor to
drive the rakes  is  \ horsepower  and a bar  screen with sufficient
capacity to serve a 15 mgd plant can  be powered  by either  a  5§ or
3/4 horsepower electric motor.   It  will be assumed here that all
bar screens up to 15 mgd  will be powered by  a  3/4 hp motor and
for each additional 15 mgd  increment  an additional 3/4  hp  motor
will be required.
The electrical efficiency of electrical motors will be  taken as
0.877 as recommended by one of the  principal suppliers  of  elec-
trical motors.   The electrical power  in kilowatts is then  ex-
pressed as follows;
                 Kilowatts  = 0.85 x Horsepower                  (1)
Bar screen power consumption for all  plants  up to 15 mgd  is,
therefore 1.53 kwh/day.   This estimate will apply to the  1  and
10 mgd plants.   The corresponding power consumption for the  100
mgd plant will be 10.7 kwh/day,
                          3
Manufacturers'  literature  for comminutors which are used to grind
and shred floating  debris gives  the size of  the  installed  motor

-------
on each size comminutor.  Several typical sizes are shown below:  ' ;
       Average Flow Range
          .25 - 1.82 mgd          0.75 horsepower motor
          .97 - 5.10 mgd          1.50 horsepower motor
         1.0  - 9.40 mgd          1.5  horsepower motor
         1.30 - 20.  mgd          2.0  horsepower motor
Thus, for the 1 mgd plant size the smallest size unit would be
sufficient.   The electrical power consumption, since the communitor
will operate 24 hr/day,  will be 15.3 kwh/day.  At the 10 mgd size
a conservative estimate  would be two of the 1.5 horsepower sizes
and the electrical power consumption would be 61 kwh/day.  At the
100 mgd size five of the larger size should handle the flow and
the power consumed would be 204 kwh/day.
Equipment for grit removal, according to one manufacturer ,  comes
in sizes capable of handling 5 mgd.   The installed electric motor
is % horsepower.  Thus,  one horsepower per 10 mgd will be assumed.
The grit is  removed usually during the high flow period in the
morning hours between 8-12 a.m.  Therefore, at the 1 mgd size
electrical power consumption is estimated as 1.7  kwh/day.
At the 10 mgd size the power consumption can be estimated as 3.4
kwh/day  and at the 100  mgd size as  34 kwh/day.
Flow measurement is accomplished by a Parshall flume in the smaller
plants and by a Venturi  or magnetic flow meter in the larger sizes.
The power consumption for these flow sensing devices is negligible.

-------
 INFLUENT PUMPING
 A major part of  the electrical power consumption at  a waste-
 water treatment  plant is  attributable to pumping the main stream
 from one level to a higher level.   The total pumping head to  bring
 the wastewater from the interceptor to the plant level varies some-
 what with the plant,  but  about 30  ft. is commonly observed.   The
 horsepower consumed in pumping water is given by the following
 relationship:
      Pumping Horsepower = ^D * X°  X H                         (2)
                   ^       1440 x 3960 x e^                      v '
                                          h

      M3D = volume of  water pumped, millions of gallons per day
        H = total dynamic  head, ft. of water
       e,  - hydraulic  efficiency

 This relationship can be  simplified as follows:
      Pumping Horsepower = MGD x 0.1754 x H/e                    (3)

 The hydraulic efficiency  of water  pumps depends  on the volume of
 water pumped as  well  as the total  dynamic head delivered.  Since
 most water pumps are  driven by induction motors,  the speed of the
 pump is  almost fixed.   If the duty cycle for a pump  is known,  the
 hydraulic efficiency  can  be accurately determined from the pump
 map.   For estimates of the kind made here,  this  is not possible.
 Therefore,  rough averages for hydraulic efficiency will be used.
 One principal supplier of water pumps recommended the following
 values  which will be  used in this  report:
          up to 1000 gpm     70% hydraulic efficiency
          1000 -  7000  gpm     74% hydraulic efficiency
          over 7000 gpm      83% hydraulic efficiency
 Assuming  a  total dynamic  head of 30 ft.  for influent pumping,  the
power consumption  at the  1  mgd plant  is  computed  as  133 ;ewh/day.
For the 10 mgd the  corresponding value  is  1451 kwh/day.  For  the
100 mgd size  the value  is  12,933 kwh/day.

-------
In this report, other pumping requirements such as recirculation
pumping for activated sludge process or trickling filters or
pumping of the main stream through such processes as carbon ad-
sorption,  filtration, reverse osmosis, etc. will be handled in
a similar way.
                             10

-------
SEDIMENTATION
Settlers for  removal  of  suspended  solids from  raw wastewater and
secondary settlers, used with  the  activated  sludge process, can
be constructed  in  either a  circular  or  a rectangular  shape.  In
this report only rectangular settlers will be  considered.  Rec-
tangular settlers  are normally constructed with common walls and
the number of individual settlers  needed, assuming an overflow
rate of 800 gpd/sq ft, as a function of plant  size is given below;
    MGD     Number of Individual Settlers      Length, feet
      13                       37
      24                       50
      35                       56
      46                       60
      56                       74
     10                     8                      106
     20                   11                      149
     30                   14                      172
     40                   16                      198
     5O                   17                      232
     6O                   19                      248
     70                   20                      274
     80                   22                      283
     90                   23                      304
    1OO                   24                      323
                                      3
According to  manufacturer's literature  , the installed electrical
horsepower to drive the  flights depends primarily on  the length
of the settler  as  shown  in  Figure  2.  The installed horsepower,
as a function of average flow, can,  therefore  be determined as
shown in Figure 3.  Since settlers normally operate 24 hr/day,
we can compute  the power consumption at !:he  1  mgd size as 30.6 kwh/day.
The corresponding  values for 10 mgd  and 100 mgd sizes are 122 kwh/day
and 734 kwh/day.
                                11

-------
--H-  INSTALLED ELECTRICAL HORSEPOWER FOR SETTLERS
                         versus
                    LENGTH OF  SETTLER
            Length of Settler,  ft.
                                                                     FIGURE 2

-------
                                                  FPr
                                                   rr 11 j 111111
                                                    \ r TTTI
                                                                    ±r
TI !


                                                                        rfl

         -flfl
                                                           i!


            :hr!:
INSTALLED  ELECTRICAL HORSEPOWER FOR SETTLERS

                    versus


                DESIGN  CAPACITY
                                                                             4   5  6789 10
                            10
                              Design Capacity,  mgd
                                                                             FIGURE 3
                                        13

-------
TRICKLING FILTERS
Trickling filters can be designed in many configurations and the
pumping power consumed will depend on the configuration.  The
loading in mgd/acre roughly divides filters into standard and
high rate.  Filters with loadings in the range of 1.1-4.4 mgd/
acre are called standard filters while filters with loadings in
the range 8.7-44 mgd/acre are known as high rate.  Recycle of the
main stream is commonly employed with high rate filters while
standard rate filters usually have no provision for recycle.
The depth of rock media in all filters is about 6 feet.  The dis-
tributor is normally about 1 foot above the top of the rock media
and a head loss of about 2 feet occurs in the underdrains.  The
head loss across the distributor is about 3 feet.  Thus, the head
loss through a one stage trickling filter is about 12 feet.  The
electrical power consumed in driving the main stream through the
filters is therefore, 61 kwh/day for the 1 mgd size, 580 kwh/day
for the 10 mgd size, and 5173 kwh/day for the 100 mgd size.
The recirculation ratio (volume of recycled stream/volume of main
stream) varies from 0.5 to 3 in most cases.  A recycle ratio of
2.0 will be assumed here.  When recycle is used, the power con-
sumption can be estimated by multiplying the estimates given above
by the recirculation ratio plus one.
For trickling filters without recycle, the power consumption is
only about one-tenth that required for supplying air to the acti-
vated sludge process.
Sludge production in high-rate trickling filters has been found
to be 35-50% of the BOD plus suspended solids load entering the
filter.  If the primary settler removes 50% of the suspended solids
and 35% of the BOD, the sludge production is about 700-900 Ib/mg,
which is approximately the same as the conventional activated sludge
process.
                                15

-------
ACTIVATED SLUDGE PROCESS
Supplying oxygen to the activated sludge process is one of the
principal needs for electrical energy-  The diffused air system
is most commonly used and the amount of air needed depends on the
strength of the primary effluent, the detention time in the aerator,
the concentration of mixed liquor suspended solids used, and whether
or not nitrification occurs.  For normal conditions, such as 130
mg/1 5-day BOD into the aerator and a mixed liquor suspended solids
concentration of 2000 mg/1, the oxygen requirement is about 728
Ib. 0  per million gallons treated.  If we take the aeration ef-
     £
ficiency (oxygen dissolved/oxygen supplied) as a nominal 5%, the
amount of air required is about 0.92 scf/gal.  To supply this air,
positive displacement or centrifugal compressors can be used.  The
pressure to be supplied by the compressor is about 8.1 psig.  The
power needed to compress the air, assuming isentropic compression,
is given by the following relationship:
                                                                (4)
     Work of Compression, BTU/lb = c T    (P /P )   n  _
                                    p J.     21

        c  = specific heat of air at constant pressure =
         P   .24 BTU/lb/°F
        T  = temperature of inlet air = 70° F = 530°R
        P  = outlet pressure, psia
        P  = inlet pressure, psia
        n  = ratio of specific heats = 1.40

Substituting into equation 4, the work required to compress atmos-
pheric air to 8.1 psig is 17 BTU/lb.  Using the assumed value of
1 scf/gal and an air density of 0.075, 3125 Ib. of air per hour
must be delivered at the 1 mgd plant site.  Since 2545 BTU/hr
is equivalent to one horsepower, the adiabatic horsepower associated
                               17

-------
 with  the  air  delivered is  20.87 at the 1 mgd plant size.  If we
 take  the  adiabatic  efficiency  of the blower as O.8,  the horse-
 power needed  to  drive  the  blower is 26.1 horsepower for the 1
 mgd size.   Since the blower  operates 24 hr/day, the power consump-
 tion  at the 1 mgd size will  be 532 kwh/day.
 Literature  from  suppliers  of mechanical aerators quote a transfer
 efficiency  of 3.5 Ib.  0 per bhp-hr in clean water and ideal con-
 ditions.  After  the various  correction factors are applied, the
 effective transfer  efficiency  is  about 2.17 Ib. C>2/bhp-hr.  Since
 we had assumed 1 scf/gallon  for the diffused air system which is
 equivalent  to about 791 Ib.  0  /mg,  the amount of power needed to
 transfer  this amount of oxygen,  using mechanical aerators, is 365
 bhp-hr/mg or  15.2 HP at the  1  mgd size.
 Thus,  based on this analysis,  it  would appear that mechanical
 aeration  is significantly  less  expensive than diffused air.  The
 five  percent  efficiency assumed for diffused air is  conservative
 and in tests  made at the Milwaukee Wastewater Treatment Plant}
 efficiencies  as  high as 15-17% have been observed for the ridge
 and furrow  type  of  diffused  air system.
 Recirculation of activated sludge  requires  electrical power.  The
 installed pump capacity recommended is  100% of the main stream,
 but on the  average, only about  50% of  the main stream is returned.
 From  discussions  with  consulting  engineers  and pump  manufacturers,
 the pumping head  for recirculation was  estimated to  be 15-20 ft. of
 water.  Thus,  the electrical power consumption is 45 kwh/day at the
 1  mgd  size, 423 kwh/day at the  10  mgd  size  and 3131  kwh/day for the
 100 mgd size.
 Power  requirements for  final sedimentation  will be taken as equal
 to  those already  estimated for primary  sedimentation.
The Linde Division of Union Carbide  Corporation4 has  estimated  the
power requirements for generation  of pure oxygen and  dissolving it
in the aerator water at 25 hp for  the  1  mgd size,  142  hp  for the
6 mgd size,  700 hp for  the 30 mgd  size  and  1960 hp for the  1OO  mgd
size.   An  aerator with  2 hours detention time was  assumed  in making
these  estimates.
                               18

-------
SLUDGE HANDLING AND DISPOSAL
Energy for pumping  sludges from  the  primary settler and  the  acti-
vated sludge process  is difficult  to estimate, but the head  to be
pumped against will be at  least  the  25-35 ft.  required to pump the
sludge into the digester.  Under average conditions, the  sludge
volume in the primary plant will be  about 0.00125 mgd/mgd of  in-
fluent wastewater.  For the activated sludge process,  this ratio is
0.0052 mgd/mgd of plant influent.  If we take  the total  head  to be
100 ft., the power  consumed in the 1 mgd primary plant is only
0.64 kwh/day.  The  power consumed  for the 10 mgd and  100 mgd  pri-
mary plants would be  multiples of  this value.  For the 1 mgd  acti-
vated sludge plant  the power  consumed for sludge pumping would be
2.66 kwh/day and for  10 mgd and  100  mgd the values would be 26.6
and 266 kwh/day-
The electrical power  for operating gravity thickeners is based on
the drag forces on  the sludge scraper. These  are in  the range of
8-12 Ib/ft of radius.  The torque  on the scraper and  pickets, if
they are provided,  equals  the load in pounds per foot times the
radius in feet squared.  The  tip speed of the  scraper is set  at
1 ft. per minute.   Horsepower is computed as torque (ft-lb) times
2 71 times the turning speed in rpm divided by  33,000.  This  relation-
ship can be reduced to the loading in Ib/ft times the radius  in feet
divided by 33,000.  This is clearly  a negligible amount  of power.
Since it is policy  to install at least % horsepower motors,  the
power can be estimated as \ horsepower per gravity thickener.
Primary plants are  sometimes  not equipped with gravity sludge thick-
eners.  However, if a thickener  is used, the normal loading  rate is
16 Ib/day/sq ft.  Since a  1 mgd  primary plant  will produce about
833 Ib/day of organic sludge, one  8  ft. dia. thickener should be
sufficient.  At the 10 mgd size, two 18 ft. dia. thickeners  should
be adequate.  At the  100 mgd  size, three 48 ft. dia.  thickeners are
needed.  Thus, the power consumed  can be estimated as 10.2 kwh/day
at 1 mgd, 20.4 kwh/day at  10  mgd and 30.6 kwh/day at  100 mgd.
                                19

-------
The recommended loading rate for activated sludge plants is 8
Ib/day/sq ft.   Since  the activated sludge plant produces about
1726 Ib.  of combined  primary and waste activated sludge per million
gallons,  the area needed at  the 1 mgd size is 216 sq. ft.  Thus,
one 18 ft. dia. thickener will be sufficient for the 1 mgd size.
For the 10 mgd size,  two 38  ft. dia.  thickeners will be adequate.
At the 100 mgd size,  four 82 ft. dia. thickeners will be sufficient.
The installed horsepower is, therefore,  0.5 at the 1 mgd size, 1.0
at the 10 mgd size and 2.0 at the 100 mgd size.  This is equivalent
to 10.2 kwh/day for 1 mgd, 20.4 kwh/day  at 10 mgd and 40.8 kwh/day
at the 100 mgd size.
Installed horsepower  for flotation thickening of waste activated
sludge is a log-log function of the surface area of the thickener.
For example, at 100 sq. ft.  the installed horsepower is 14.5, at
1000 sq.  ft. the installed horsepower is 115 and at 6000 sq. ft.
the installed horsepower is  570.  The recommended loading rate
with chemical addition is 2  Ib/hr/sq ft.  The loading rate, when
no chemicals are used, is about 0.5 Ib/hr/sq ft.  The amount of
waste activated sludge produced is about 900 Ib/mg.  Thus, at a
1 mgd plant where the flotation thickener is operated 40 hr/week
and chemicals are used, about 80 sq.  ft. of surface area would be
required.  The next largest  standard size is 100 sq. ft.  This
unit requires about 14.5 horsepower.   The consumption of electrical
power will be 70 kwh/day. Similarly, at the 10 mgd size (assumed
to operate 100 hr/wk) the unit selected would be 400 sq. ft. and
the installed horsepower is  50 horsepower.  Operating an average
of 14.3 hr/day the power consumption will be 608 kwh/day.  At the
100 mgd size which operates  24 hr/day, the size of installation
will be two 1000 sq.  ft. units having 115 horsepower each for a
total of 230 hp.  The power  consumption will be 4692 kwh/day.  If
no chemicals are used the power consumption at 1 mgd will be 242
kwh/day,  at 10 mgd 1800 kwh/day, and at  100 mgd 18,800 kwh/day.
The use of flotation  thickeners for thickening of activated sludge
can be expensive in terms of electrical power consumption.
                               20

-------
Electrical energy is consumed in the anaerobic digestion process
for two principal reasons; first, for mixing the contents of the
primary digester (gas recirculation) and second, for heating the
incoming sludge and holding the contents of the digester at the
optimum temperature, usually about 95°F.
Anaerobic digesters range in size from 25 ft. in diameter to a
maximum of about 110 ft.  The depth is generally about 20 ft. at
the 25 ft. size and about 35 ft. at the maximum size.  The points
on Figure 4 show the number of anaerobic digesters in installations
with various total volumes.
The solid lines on the right and left of the data points represent
limits corresponding to 25 ft. diameter and 20 ft. deep digesters
on the left bound and 110 ft. diameter and 35 ft. deep on the
right bound.
An interesting and important problem is to find the number of
digesters which will minimize the cost of the installation when
one extra digester is provided (over and above the minimum re-
quirements) for cleaning and maintenance.  This problem can be
solved in a crude way by assuming that the cost of the digester
is directly proportional to the volume of concrete involved.
Clearly, if no duplication of digesters were needed, the minimum
cost would be represented by building one large digester in every
case up to the maximum size of 110 feet.  Thus, the optimum sizes
would be represented by a horizontal line at N = 1 terminating in
the right hand bound and then following the right hand bound.
Clearly, this principal is not always followed.
The results of the simplified analysis of optimum number of digesters
to provide one extra is shown by the squared points.  The dashed
stepped line is only an approximation because the number of digesters
must be an integer.  It appears from this analysis that at the larger
sizes, say about 500,000 cu. ft., practice is not significantly
different from the optimum number of digesters.  At the smaller sizes,
                                21

-------
21- -
 _LO.Q_.
       T3 -:-
       Vl
       0)
       0) -"•
       •H
       Q
       •O
       •H
      - >
       •H
       T3
      _ C
M-l
0 .
                   NUMBER OF ANAEROBIC DIGESTERS PER INSTALLATION
                                     versus
                       TOTAL VOLUME OF DIGESTER INSTALLATION
                                  -. -.I-:.
                J+LL
                             ±
                                         ~rr;
                                               Jl"
                                                                   in
                                                                   ^
                                                                   itt
                                                                        -ffft
                                                                             tlfl
                                                                                £S
                                                                                   ±TE
                                                                                           I
                         a-
                                                                -, - -,._:-_i_
                    Li- I
                                                                                      iH-t

               3   4  5678
                              ! 10
                               100
                                        3    4   5678910
                                                       1000
                                                                              3   4  &  6789 10
                Total  Digester Volume, thousands  of cubic feet
                                                                                  FIGURE  4
                                             22

-------
however, there seems to be a  tendency  to not provide for dupli-
cation of digester facilities.  Where  duplication is shown, it
appears that three digesters  might have been more cost-effective
than two digesters.
Electrical power is consumed  in heating incoming sludge and over-
coming the heat loss to the environment.  The usual practice is to
operate a hot water boiler and pump the sludge from the digester
through the hot water heat exchanger to maintain the temperature
in the digester at the 95°F level.  The installed electrical horse-
power for units with heating  capacities in BTU/hr is shown in
Figure 5.  These motors do not all operate continuously, but the
manufacturer estimates that power consumption would, on the average,
be equivalent.to operation of all motors 75% of the day.  By es-
timating the number and size  of digesters for primary and activated
sludge plants of various sizes, the heat requirements can be found
and from this the consumption of electrical power.
Primary plants produce about  833 Ib/mg and activated sludge plants
about 1726 Ib/mg.  In terms of volatile solids, these estimates
are 650 Ib/mg for the primary plant and 1275 Ib/mg for the activated
sludge plant.
For completely mixed digesters the recommended loading is 1000 cu.
ft. of digester volume for each 8O Ib. volatile solids per day-
Thus, a primary completely mixed digester for a primary plant would
be sized on 8,125 cu ft/mg.   Similarly, for the activated sludge
plant the sizing parameter would be 15,400 cu ft/mg.
If we take conventional practice as a  guide, (see figure 4 ) we can
assume that up to about 60,000 cu. ft. a single digester will be
provided.  Two digesters might be provided up to a volume of about
400,000 cu. ft.  Three digesters might be provided up to about
850,000 cu. ft.  Four digesters will be provided up to 1,350,000
cu. ft. and above this the maximum size digester with 338,000 cu.
ft. might be used.
                               23

-------
                                                   _l	_l.
                                         	r
                                                                            41-r-
                                                                                •ITr
                                                                                       4-
'0
9
                      INSTALLED  HORSEPOWER  FOR ANAEROBIC SLUDGE'—,.
                           DIGESTER HEATER AND HEAT EXCHANGER
 10
                                                            1,000

                                          .-pac.'-xv -  tfion/sands  of BTU/hr
•'   6  6  7 8 9 10

       10,000
                                                                             ICURE  5

-------
The number and volume of primary digesters  in primary and acti-
vated sludge plants can, therefore, be estimated as follows:

      Primary Plants          Plant Size     Activated Sludge Plants
1 digester @ 8,125 cu ft         1 mgd      1 digester @ 15,400 cu ft
2 digesters @ 40,625 cu ft      10 mgd      2 digesters @ 77,OOO cu ft
3 digesters @ 270,833 cu ft     100 mgd      5 digesters @ 308,000 cu ft

For primary plants, the heat load in BTU/hr can be computed as
9000 times the design population in thousands.  The factor for
activated sludge plants is 15,OOO.  Loss of heat through the walls
of the digester can also be estimated in an approximate way.  For
digesters with gas recirculation and exposed outside walls, the
heat load can be approximated by multiplying the digester capacity
in thousands of cubic feet times a factor.  This factor is 4800
for a moderate climate such as  that for Cincinnati, Ohio.  Heat
requirements for primary and activated sludge digesters can be
computed as follows :

   Primary Plants :
      BTU/hr = 90,000 x mgd + 4800 x I^ster volume cu. ft.
                                             ^

   Activated Sludge Plants :
          /,     , ^  ~~~      •,    *r>^^   Digester volume cu. ft.
      BTU/hr = 150,000 x mgd +  4800 x - —
                                             1000

The capacity of sludge heating units for each size of plant can
now be computed as follows;

      Primary Plants          Plant Size     Activated Sludge Plants
   1 @ 129,000 BTU/hr            1 mgd        1 @ 223,920 BTU/hr
   2 @ 645,000 BTU/hr           10 mgd        2 @ 1,119,600 BTU/hr
   3 @ 4,300,000 BTU/hr        100 mgd        5 @ 4,478,400 BTU/hr
                              25

-------
The installed horsepower can be taken from Figure 5 to give the
following estimates:

      Primary Plant           Plant Size     Activated Sludge Plant
1 unit @ 1.1 hp                  1 mgd       1 unit @ 1.15 hp
2 units @ 3.1 hp = 6.2 hp       10 mgd       2 units (§ 4 hp = 8 hp
3 units @ 10.3 hp = 30.9 hp    100 mgd       5 units @ 10.3 hp = 51.5 hp

Assuming that these installed electric motors operate about 75%
of the time, the following estimates for electrical power con-
sumption can be computed:

      Primary Plant           Plant Size     Activated Sludge Plant
        16.8 kwh/day              1 mgd           17.6 kwh/day
        95.  kwh/day             10 mgd          122.4 kwh/day
       473.  kwh/day            100 mgd          788   kwh/day

These are the electrical energy requirements for the primary digester
which is always heated.  If the secondary digester is to be heated
these values should be multiplied by two.  Secondary digesters are
usually not heated.
Electric motors are also used to drive the gas recirculation equip-
ment for mixing the contents of the primary digester.
From specifications   of  manufacturers' of  gas  recirculation systems
for mixing of anaerobic digesters, the following operating horse-
powers  are shown as a function of the diameter of the digester;

                25-30 ft. dia.       4.09 HP
                31-40 ft. dia.       5.20 HP
                41-50 ft. dia.       5.20 HP
                51-80 ft. dia.       8.18 HP
                81-110 ft. dia.     11.0  HP

Since  the mixers normally operate 24 hr/day, the electrical power
consumption can be estimated directly from the installed horsepower
shown above.
                               26

-------
Since the depth of sludge  in  the digester is known to vary from
20 ft. at the 25 ft. dia.  size  to 35 ft. at the  110 ft. dia. size,
the diameter of the digesters required  can be computed as follows:
   Primary Plants        Plant Size      Activated Sludge Plants
   1 @ 23 ft. dia.          1  mgd          1 @ 31 ft. dia.
   2 @ 47 ft. dia.         10  mgd          2 @ 62 ft. dia.
   3 @ 102 ft. dia.       100  mgd          5 @ 108 ft. dia.
The installed electrical horsepower for mixing is given below:
   Primary Plants        Plant Size     Activated Sludge Plants
   1 @ 4.09 hp              1  mgd          1 @ 5.2 hp
   2 <§ 5.2 hp = 10.4 hp    10  mgd          2 @ 8.18 hp = 16.36 hp
   3 @ 11 hp = 33 hp      100  mgd          5 @ 11 hp = 55 hp
Power consumption in kwh/day  are given below;
   Primary Plants        Plant Size.     Activated Sludge Plants
      84 kwh/day            1  mgd            106  kwh/day
     212 kwh/day           10  mgd            334  kwh/day
     673 kwh/day          100  mgd           1122  kwh/day
Aerobic digestion is sometimes  used to destroy suspended solids in
waste activated sludge and  to improve the dewatering characteristics
of the remaining solids.  The aerobic digester is similar to an
aerator used in the activated sludge process except that settling
and recycle of thickened sludge is not provided.  The digester is
supplied with diffused air, except during the periods when the con-
tents of the digester are allowed to settle in order to draw off
the thickened digested sludge.  The detention time needed, when
waste activated sludge alone  is digested, is in  the range 15-20 days
Since the volume of the waste activated sludge stream is about
0.018 mg/mg, a 1 mgd plant  would produce about 18,000 gallons of
waste activated sludge per  day, requiring about  36,000 cu. ft. of
digester capacity.  About 25-30 cfm per 1000 cu. ft. of digester
capacity is recommended  to  keep the sludge in suspension and supply
                               27

-------
the oxygen demand of the microorganisms.  Since about  90O  scf  is

needed in diffused air system, the air requirements for  the  1  mgd

aerobic digestion process exceeds the requirements for the con-

ventional activated sludge process by a factor of 1.3.   Thus,

aerobic digestion increases the electrical power consumption of

activated sludge plants significantly-

The installed electrical horsepower for vacuum filters is  shown

in Figure 6 .  The estimated amounts of sludge to be vacuum  fil-

tered, using sludge handling scheme II for primary plants  and
sludge handling schemes II and III for activated sludge  plants.
is shown below together with the size of filter likely to  be in-

stalled and the operating times:
PRIMARY PLANTS
       SCHEME II
  1 mgd
 10 mgd
100 mgd
    508 Ib/day
  5,080 Ib/day
 50,800 Ib/day
  60 sq. ft.
 125 sq. ft.
 250 sq. ft.
 0.94 hr/day
 5.   hr/day
24.   hr/day
ACTIVATED SLUDGE PLANTS
  1 mgd
 10 rngd
100 mgd
  1,046 Ib/day
 10,886 Ib/day
108,860 Ib/day
SCHEME II

  60 sq. ft.
 575 sq. ft.
 2 x 575 = 1150 sq. ft.
 4.36 hr/day
 5.   h r/day
24.   hr/day
ACTIVATED SLUDGE PLANTS   SCHEME III
  1 mgd
 10 mgd
100 mgd
  1,661 Ib/day
 17,261 Ib/day
172,610 Ib/day
  60 sq. ft.
 575 sq. ft.
 3 x 430 = 1290 sq. ft.
 4.6  hr/day
 5.   h r/day
24.   hr/day
Using these estimates and the installed electrical horsepower

shown in Figure  6,  the following electrical power requirements
can be calculated;
PRIMARY PLANTS   SCHEME II

   1 mgd      10.4 kw-hr/day
  10 mgd     108   kwh/day
 100 mgd     847   kwh/day
                     ACTIVATED SLUDGE PLANTS   SCHEME  II
                             1 mgd
                            10 mgd
                           100 mgd
                         57 kwh/day
                        346 kwh/day
                       3325 kwh/day
                               28

-------
TOTAL INSTALLED ELECTRICAL HORSEPOWER  FOR VACUUM FILTERS
               Vacuum Filter  Area,  sq. it.

-------
ACTIVATED  SLUDGE PLANTS   SCHEME III
       1  mgd       60 kwh/day
      10  mgd      346 kwh/day
     100  mgd     3947 kwh/day
Electrical power consumption by centrifuges  used for  dewatering
digested organic sludge can be estimated accurately by  the  manu-
facturers  of  the equipment, but the computations are  complex and
depend on  the specific application intended.   The type  of centri-
fuge considered here is the solid bowl centrifuge for dewatering
digested organic sludge.   Estimates of power  consumed  are  shown
below for  four different  centrifuge sizes:
                 1.   0.73  - 1.6  horsepower/gpm
                 2.   0.8  - 1.48 horsepower/gpm
                 3.   0.43  - 0.81 horsepower/gpm
                 4.   0.41  - 0.74 horsepower/gpm
The  limits  of power  consumption shown above  correspond  to 1000 g's
and  20OO g' s.   The  lower  value is typical of  operation  where the
sludge is  to  be disposed  of by land spreading.   The higher  value
is characteristic of a dryer sludge which might  be incinerated.
The  range  of  volume  handled per centrifuge is 10 gpm  for the
smaller  size  and 140 gpm  for the larger size. When waste sludge
is to be incinerated,  it  is common practice  to provide  a gravity
thickener  upstream of  the centrifuge.   The concentration of the
thickened  sludge would be about 5% solids.   If we take  the  amounts
of sludge  given in the discussion on vacuum filters and convert
these  amounts  to gpm,  assuming a solids concentration of 5%,  the
volume of  the  stream to the centrifuge in the primary plants  is
0.85  gpm at 1  mgd, 84.7 gpm at 10 mgd and 847. gpm at the 100 mgd
size  if  the centrifuge is  operated 24 hr/day.  Thus,  the power
consumed in the primary plants would be 28 kwh/day at 1 mgd,  256
kwh/day  at  10  mgd and  1400 kwh/day at  100 mgd.   For activated
sludge plants  using  sludge handling scheme II, the power consumed
at 1 mgd would  be 57 kwh/day,  at  10 mgd 368 kwh/day and at  100 mgd
                               31

-------
2740 kwh/day.  For activated sludge plants using sludge handling
scheme III, the corresponding values would be 90 kwh/day at 1 mgd,
435 kwh/day at 10 mgd and 4348 kwh/day at 100 mgd.  Thus, the
electrical power consumption for centrifugation of digested sludge
is somewhat higher than that required for vacuum filters.

The amounts of sludge to be incinerated will equal the amounts
                                                                  7
vacuum filtered.  Figure 7 shows the electrical power consumption
as a function of hearth area in terms of kwh per ton of sludge in-
cinerated.  The recommended loading is 2 Ib. of sludge per hour
per sq. ft. of hearth area.  The size of incinerator likely to be
used is shown below together with the electrical power consumption:
PRIMARY PLANTS

      1 mgd
     10 mgd
    100 mgd
  SCHEME II

   85 sq. ft.
  510 sq. ft.
  2 x 575 = 1150 sq.  ft.
  28.4 kwh/day
 152.4 kwh/day
1148.  kwh/day
ACTIVATED SLUDGE PLANTS   SCHEME II
      1 mgd
     10 mgd
    100 mgd
  112 sq.  ft.
1,117 sq.  ft.
2,275 sq.  ft.
ACTIVATED SLUDGE PLANTS
            SCHEME III
      1 mgd      166 sq.  ft.
     10 mgd    1,752 sq.  ft.
    100 mgd    2 x 1849 = 3698  sq.  ft
  54
 245
1905
                                75
                               328
                              3280
kwh/day
kwh/day
kwh/day
       kwh/day
       kwh/day
       kwh/day
                              32

-------
ELECTRICAL ENERGY REQUIREMENTS FOR MULTIPLE HEARTH  FURNACES

                                                                     6  7 8 9 10
                 Hearth Area per  MHF,  sq.  ft,
                                                                FIGURE 7
                                33

-------
CHLORINATION

The dose of chlorine  for  disinfection of primary  effluent  is
20-25 mg/1.  For  activated sludge  effluents  the corresponding
dose is 8 mg/1.   Thus,  the average useage of chlorine  is  187
Ib/mg for primary plants  and 67  Ib/mg for activated  sludge plants.
The three standard sizes  of chlorinators are 400  Ib/day,  2000
Ib/day and 8000 Ib/day.   When the  chlorine is removed  from the
storage pressure  vessel as a gas,  the power  requirements  for these
chlorinators are  negligible;  30  watts for the 400 and  2000 Ib/day
units and 75 watts for  the 8000  Ib/day unit.
If a large amount of  chlorine is used at a plant,  it is often ad-
vantageous  (reduced storage)  to  remove the chlorine  as a  liquid
and then evaporate the  chlorine  to a  gas before use  in the chlor-
inator.  The kilowatt rating of  a  standard evaporator  is  18 kilo-
watts.  The manufacturer  recommends the  use  of an evaporator if
chlorine useage exceeds 2000 Ib/day.
The actual dissipation  of electrical  energy  can be computed from
the heat of vaporization  of chlorine  (123.7  BTU/lb)  and the heat
required to raise the temperature  of  the gas to ambient temperature.
The specific heat of  chlorine is 0.115 BTU/lb and since the boiling
point is -30 F, about 11.5 BTU/lb  is  needed  to bring the  gas to
room temperature.   The  total to  evaporate chlorine is  135  BTU/lb.
One kilowatt-hr is  equivalent to 3412 BTU.
The 2000 Ib/day point is  equivalent to about 10 mgd  for a primary
plant and 30 mgd  for  an activated  sludge plant.   The 1 mgd plait
would, therefore,  consume only 30  watts  or 0.72 kwh/day.   The 10
mgd primary plant  would consume  3C watts plus 135 BTU/lb  or a total
of 82.4 kwh/day.   The 10  mgd activated sludge plant  would consume
only 3O watts.  The 100 mgd primary plant would consuma 20,825 Ib
Cl  per day.  The  chlorinators would  corsume 225  watts and the heat
to vaporize the chlorinS  would amount to 824 kwh/day for  a total of
829 kwh/day.  The  corresponding  value for the 100 mgd  activatec
sludge plant is 226 kwh/day.
                               35

-------
LIGHTS AND MISCELLANEOUS  POWER
Additional electrical  power  is  used in plants  for indoor and out-
door lighting,  operation  of  hand tools and office equipment, and
other miscellaneous  uses.  The  annual  reports  of the  larger plants
often give an estimate of  this  consumptive use,  but  in the  smaller
plants, an estimate  must  be  made.   The circled points  in Figure  9
show values  taken from the annual  reports  of ;four large plants.
Building electrical  usage  for  lights and outlets is  often estimated
as 2-4 watts per square foot of floor  area.   In  estimating  the
building power  consumption for  plants  in the  1-10 mgd  range, a
working day  of  10 hours was  assumed.  The  floor  area assumed as
a function of plant  size  is  shown in Figure 8  .
                                                                  8
From a recent study  made  by  Black and  Veatch Consulting Engineers ,
the estimated number of outdoor lights was found to be four lights
at a 1 mgd plant, 8  lights at  a 5 mgd  plant and  12 lights at a
10 mgd plant.   The average expenditure per outdoor light was
estimated as $25 per year.  If  we take the average cost of  elec-
trical power as 2 cents/kwh, one light would consume 342 watts,
which is a good average between the conventional 400 watt street
light and the 250 watt pole  light  often used  in  plants around
aerators and settlers. If we  assume that  the  outdoor  lights are
turned on for an average  of  10  hr/day, the curve shown in Figure 9
can be constructed.
                               37

-------
             ESTIMATED FLOOR AREA FOR WASTEWAIER TREATMENT PLANTS
                                                                                   EEE
            HI
                  ±1-
                                          1
                                                     =F-t
                                                            -FI-FF
                                                                     -fi+4
                                                                                       -. H-
                       •I
                         -47.
                           :f
                                                   i-lt
                           ±
       -h-
                                                 +H
                                                             ffil
                                                                           ffi


                                            c±tti
-Li-J-l-
                                          I
                              l+tr^fF^
                              —h~H- ^f\ ' ,e,
                                                              ±t
                                                                  TTi
                                                 s
                                                                      I

                                                                             t;±
                                                                           +irt
if*
                                                                         it
- -p
--S-I -"-
            •ff
                     ±fl±
                                   ill
                                                                    -FT-
                                                                                      3EE
                                   1
                                   itri
                                          I
                                                :Ef

                                          :Tf
                                                                                        :±
  rt
  Q) '
=! n-
                                                                         1
         m
                     •ffi

                                                                               I

          turn
                                     ttt
              2   4  5678910

                             10
                                            3    4   5  678910

                                                          100
                               Plant Size,  mgd
                                          38
                                                                              FIGURE 8

-------
          ELECTRICAL  ENERGY REQUIREMENTS FOR LIGHTING AND MISCELLANEOUS  POWER
               3  4 567691
                                 2   3  45678SI
                                                          3  4  567091
                                                                                   4  567891
                                                                                                        4 567891
>>

-3
     Thin-)
                                                                                   	i	
                                                                                      T"

                                                                                            •~:p::
                                                                                           f"T
                                                                                                   	i _.
                                        Tffi-
1

 O
i— I
•H
      •H-i-i
      Ite
                                                             1
                                                                                     -4-4.
                                                                                           __|	.
                                                                                                  	i_
                                                       iti:
                              ii
                                                                                         tt
                                                                                         il
B
                                               10
                                                                    100
                                 Plant Size,  mgd
                                                                                                     FIGURE 9

-------
PRODUCTION OF POWER BY UTILIZATION OF SLUDGE GAS


Gas produced as a  result of anaerobic digestion of organic sludge
can be used to supply internal combustion engines.  These 1C engines
can be direct coupled to air blowers or water pumps or can be used
to drive electric  generators.  Digester gas can also be used to
heat the digesters or to support combustion in the incinerator.
Digester gas is normally about 65-7O% methane by volume.  The
volume of gas produced per pound of volatile solids destroyed is
reported as 17-18  scf/lb at the larger and better instrumented
plants.  Smaller plants report lesser values, sometimes as low as
6 scf/lb VSS destroyed, but these lower values are probably due to
poor measurement techniques.  The fuel value of methane is about
963 BTU/scf and since digester gas is about 67% methane, the fuel
value of digester  gas is about 645 BTU/scf.
Average values for volatile solids fed to the digesters is 650
Ib/mg for primary plants and 1275 Ib/mg for activated sludge
plants.  if we assume that about 50% of these volatile solids
will be destroyed  in the digester and a yield of 17.5 scf/lb
destroyed, the amount of digester gas available will be 5688 scf/mg
for the primary plant and 11,156 scf/mg for the activated sludge
plant.
The BTU's available for power generation will be 3.669 x 10
                                          fi
BTU/mg for the primary plant and 7.20 x 10  BTU/mg for the acti-
vated sludge plant.  If we use this gas in an internal combustion
engine, the power produced, using 7000 BTU/bhp-hr, will be 524
bhp-hr/mg for the primary plant and 1029 bhp-hr/mg for the activated
sludge plant.  Assuming 24 hr. operation of the blowers, a direct
coupled 1C engine would develop about 43 horsepower per million
gallons in the activated sludge plant.  Thus, sufficient gas is
produced to drive the blowers.
At the Cincinnati Mill Creek Primary Plant where digester gas is used
                               41

-------
to generate electrical power, it has been reported that  17.5  scf
of digester gas is used to produce one kilowatt-hour.  Therefore,
if all of the gas was utilized, about 325 kwh/mg could be  produced
in the primary plant and 627 kwh/mg could be produced in the  acti-
vated sludge plant.  Since primary plants use about 235  kwh/mg, it
should be possible to supply all of the electrical energy  require-
ments for primary plants by using an 1C engine to drive  a  generator.
This is, in fact, what is done at the Mill Creek Plant and a  neg-
ligible amount of power is purchased.  The activated sludge plants
consume an average of 942 kwh/mg; this exceeds the amount  of  power
which might be generated by utilization of digester gas.   Even in
activated sludge plants a.maximum of 2/3 of the power needed  could
be generated by using sludge gas.
Since sludge gas is not produced continuously, a storage sphere
is normally provided and some power is consumed in storing  the gas
at about 40 psig.  Sludge gas is also often used for heating  the
digester or for operating the incinerator.   Thus,  the total amounts
estimated above might not be available for power generation.
                              42

-------
TOTAL ELECTRICAL POWER CONSUMPTION FOR CONVENTIONAL PLANTS


Since estimates of power  consumption have been made for all of
the conventional processes shown  in Figure 1, these can now be
summed to find the total  power  consumption for complete plants.
These totals are shown in Tables  I and II for primary plants using
sludge handling schemes I and II.  In Tables III and IV the totals
for activated sludge plants using sludge handling schemes II and
III are shown.  Table V gives the totals for trickling filter
plants using sludge handling scheme  II.  Since no electrical power
is used by sand drying beds, the  totals for activated sludge plants
using sludge handling scheme I  can be found by subtracting the con-
sumption for vacuum filtration  and incineration from totals for
sludge handling scheme II.  These totals are 1004 kwh/day at 1 mgd,
8218 kwh/day for 10 mgd and 75,864 kwh/day for the 100 mgd size.
Similarly, the totals for trickling  filter plants using drying
beds would be 610 kwh/day at 1  mgd,  4215 kwh/day at 10 mgd, and
35,052 kwh/day at 10O mgd.
Total electrical power consumption for plants taken from Tables
I-V are shown plotted versus plant size in Figure 10.  Power con-
sumption for activated sludge plants is almost linear with plant
size because influent pumping and diffused air consumption are
the major uses and these  are linear with the volume of the main
stream.  The curves for primary and  trickling filter plants show
significant economy of scale.
                               43

-------
                              TABLE I




ELECTRICAL ENERGY  REQUIREMENTS FOR WASTEWATER TREATMENT PLANTS
TYPE OF PLANT Primary
SLUDGE HANDLING SCHEME I
Killowatt -hours/day
PLANT SIZE
PRELIMINARY TREAT mNT
Bar Screens
Comrainutors
Grit Removal
INFLUENT PUMPING (30 ft TDH)
PRIMARY SEDIMENTATION
(800 gpd/sq ft)
TRICKLING FILTERS
Recirculation Pumping
Final Sedimentation
ACTIVATED SLUDGE PROCESS
Diffused Air
Recirculation Pumping (50%,
17.5 ft)
Final Settlers (800 gpd/sq ft)
CHLORINATION
SLUDGE HANDLING AND DISPOSAL
Sludge Pumping
Gravity Thickeners
Air Flotation Thickeners
Anaerobic Digesters
Mixing
Heating
Vacuum Filtration
Multiple Hearth Incineration
LIGHTS AND MISCELLANEOUS POWER
TOTAL Kilowatt-hours/day
1 mgd

1.53
15.3
1.7
153
30.6





0.72

'0.64
10.2
84.
17.6

57.
372
10 mgd

1.53
61.
'3.4
1,451
122.





82.4

6.4
20.4
212.
122.4

210.
•2293
100 mgd

10.7
204.
34.
12,933
734.





829.

64.
30.6
673.
788.

2400.
18,700
                               44

-------
                              TABLE II




ELECTRICAL  ENERGY REQUIREMENTS FOR WASTEWATER TREATMENT PLANTS
TYPE OF PLANT Primary
SLUDGE HANDLING SCHEME II
Killowatt -hours /day
PLANT SIZE
PRELIMINARY TREATMENT
Bar Screens
Comminutors
Grit Removal
INFLUENT PUMPING (30 ft TDH)
PRIMARY SEDIMENTATION
(300 gpd/sq ft)
TRICKLING FILTERS
Recirculation Pumping
Final Sedimentation
ACTIVATED SLUDGE PROCESS
Diffused Air
Recirculation Pumping (50%,
17.5 ft)
Final Settlers (800 gpd/sq ft)
CHLORINATION
SLUDGE HANDLING AND DISPOSAL
Sludge Pumping
Gravity Thickeners
Air Flotation Thickeners
Anaerobic Digesters
Mixing
Heating
Vacuum Filtration
Multiple Hearth Incineration
LIGHTS AND MISCELLANEOUS POWER
TOTAL Kilowatt-hours/day
1 mgd

1.53
15.3
1.7
153

30.6







0 . 72

.64
10.2


84.
17.6
10.4
28.4
57
411
10 mgd

1.53
61.
'3.4
1451.

122.







62.4

6.4
20.4


212.
122.4
108
152.4
210
2,343
100 mgd

1'''. 7
204.
-J4
12,,,,

7J4.







82-.

64.
30.6


673.
788.
847.
,'1448.
2 , 400
21,000
                             45

-------
                             TABLE III





ELECTRICAL ENERGY  REQUIREMENTS FOR WASTEWATER TREATMENT PLANTS
TYPE OF PLANT Activated Sludge
SLUDGE HANDLING SCHEME II
Killowatt -hours/day
PLANT SIZE
PRELIMINARY TREAT NE NT
Bar Screens
Comminutors
Grit Removal
INFLUENT PUMPING (30 ft TDH)
PRIMARY SEDIMENTATION
(300 gpd/sq ft)
TRICKLING FILTERS
Recirculation Pumping
Final Sedimentation
ACTIVATED SLUDGE PROCESS
Diffused Air
Recirculation Pumping (50%,
17.5 ft)
Final Settlers (800 gpd/sq ft)
CHLORINATION
SLUDGE HANDLING AND DISPOSAL
Sludge Pumping
Gravity Thickeners
Air Flotation Thickeners
Anaerobic Digesters
Mixing
Heating
Vacuum Filtration
Multiple Hearth Incineration
LIGHTS AND MISCELLANEOUS POWER
TOTAL Kilowatt-hours/day
1 mgd

1.53
15.3
1.7
153
30.6



532
45
30.6
.72

'2.65
10.2

106.
17.6
57.
54.
57
1,115
10 mgd

1.53
61.
3.4
1 , 451
122.



5,320
423
122.
.72

26.6
20.4

334.
122.4
346.
245.
210
8,809
100 mgd

10.7
2O4.
34.
12,933
734.



53,200
3,131
734
266

266
40.8

1,122.
788.
3,325.
,'1,905.
2,400
81,094
                           46

-------
                              TABLE IV




ELECTRICAL ENERGY REQUIREMENTS FOR WASTEWATER TREATMENT PLANTS
TYPE OF PLANT Activated Sludge SLUDGE HANDLING SCHEME III
Killowatt -hours /day
PLANT SIZE
PRELIMINARY TREATMENT
Bar Screens
Comminutors
Grit Removal
INFLUENT PUMPING (30 ft TDK)
PRIMARY SEDIMENTATION
(800 gpd/sq ft)
TRICKLING FILTERS
Recirculation Pumping
Final Sedimentation
ACTIVATED SLUDGE PROCESS
Diffused Air
Recirculation Pumping (50%,
17.5 ft)
Final Settlers (800 gpd/sq ft)
CHLORINATION
SLUDGE HANDLING AND DISPOSAL
Sludge Pumping
Gravity Thickeners
Air Flotation Thickeners
Anaerobic Digesters
Mixing
Heating
Vacuum Filtration
Multiple Hearth Incineration
LIGHTS AND MISCELLANEOUS POWER
TOTAL Kilowatt-hours/day
1 mgd

1.53
15.3
1.7
153

30.6




532
45

30.6
.72

2.65
10.2
70.



60.
75.
57.
1,085
1O mgd

1.53
61.
'3.4
1,451

122.




5,320
423

122.
.72

26.6
20.4
608.



346.
328.
210.
9,044
100 myd

10.7
204.
34.
12,933

734.




53 , 200
3,131

734
266.

266.
30.6
4,692.



3,947.
3,280
2,400.
85,862
                            47

-------
                             TABLE V




ELECTRICAL ENERGY REQUIREMENTS FOR WASTEWATER TREATMENT PLANTS
High Rate
TYPE OF PLANT THrklinq Filter SLUDGE HANDLING SCHEME II
Killowatt -hours/day
PLANT SIZE
PRELIMINARY TREATMENT
Bar Screens
Comrainutors
Grit Removal
INFLUENT PUMPING (30 ft TDH)
PRIMARY SEDI1\ENTATION
(800 gpd/sq ft)
TRICKLING FILTERS
Recirculation Pumping
Final Sedimentation
ACTIVATED SLUDGE PROCESS
Diffused Air
Recirculation Pumping (50%,
17.5 ft)
Final Settlers (800 gpd/sq ft)
CHLORINATION
SLUDGE HANDLING AND DISPOSAL
Sludge Pumping
Gravity Thickeners
Air Flotation Thickeners
Anaerobic Digesters
Mixing
Heating
Vacuum Filtration
Multiple Hearth Incineration
LIGHTS AND MISCELLANEOUS POWER
TOTAL Kilowatt-hours/day
1 mgd

1.53
15.3
1.7
153

30.6

183
30.6





.72

'2.6t
10.2


106
17.6
57
54
57
721
10 mgd

1.53
61.
3.4
1,451

122.

1740
122





.72

26.6
20.4


344
122.4
346
245
210
4,806
100 mgd

10.7
204.
34.
12,933

734.

15,519
734





266.

266.
40.8


1,122
788
3,325
1,905
2,400
40,282
                             48

-------
    ELECTRICAL ENERGY CONSUMPTION BY MUNICIPAL WASTEWATER  TREATMENT  PLANTS
                                   versus
                                 PLANT SIZE
 100,000
fi)
     100
                         3   4   5678910
                                       10
                                                     3   4   5678910
                         Plant Design Capacity, mgd

                                      49
  100
FIGURE 10

-------
EXPENDITURE FOR ELECTRICAL  POWER  IN CONVENTIONAL PLANTS
The cost of electrical power  depends  on  the  peak  demand for  power
as well as the amount of  kilowatt-hours  used.   A  schedule  of charges
for electrical power used by  the  Cincinnati  Gas and  Electric Co.
is shown in the Appendix.  The  average cost  of  power in the  United
States is published yearly by the Federal  Power Commission and  the
latest available nationwide averages  are shown  in the Appendix.
The cost of power, based  on the Cincinnati Gas  and Electric  schedule
for the power categories  used by  the  Federal Power Commission,  is
also shown in the Appendix.   Notice  that these  exceed the  1970
national average in the 150 kw, 30,000 kwh/mo category by  8%, in
the 300 kw, 60,000 kwh/mo category by 9% and the  1000 kw,  2000,000
kwh/mo category by 14%.   The  Cincinnati  Gas  and Electric schedule
has been used to compute  the  monthly  expenditure  for electrical
power in the five plant types shown  in Tables I-V.   These  dollar
amounts are given in Tables VI-X.  These values have been  con-
verted to dollars per year and  plotted in  Figure  11.
                          9
In a paper by R. L. Michel  of EPA, published in the  Water  Pollution
Control Federation for November 1970, the  electrical power con-
sumption in plants was reported in terms of  annual dollar  expen-
diture for electrical power.  This data  was  gathered over  the
1965-68 period.  The relationships reported  by  Michel cover  the
range 0.1-10 mgd and his  data for primary, high rate trickling
filter, and activated sludge  plants  are  shown as  dashed lines in
Figure 11.  A multiplier  of 1.12  was  applied to Michel's data to
make it consistent with the cost  of  electrical  power, using  the
CG&E schedule shown in the Appendix.
The agreement between Michel's  data  and  the  estimates produced  in
this report is good for conventional  primary plants.  The  agree-
ment for activated sludge plants  is  not  as good and  this could
be due to the use of sludge gas or natural gas  in 1C engines to
power the blowers.  The agreement  between  Michel's data on high

                               51

-------
TABLE VI
                                COST OF  ELECTRICAL POWER - PRIMARY  -  SCHEME I
TYPE OF PLANT: Primary
SLUDGE HANDLING SCHEME: I

KW Demand
k'.vh/day
kv,'b/.T;o
Tirst 6000 kwh
60 x KW Demand x 1 . 42^/kwh
120 x KW Demand x 1.14^/kwh
120 x KW Demand x 0.82^/kwh
Additional kwh x 0.7 Iff /kwh
KW Demand minus 15
First 35 KW x $2 = $70
-Second 50 KW x $1.95 = $97.50
Third 900 KW x $1.50 = $1350
Additional KW Demand x $1.35
t
Total Monthly Bill, dollars
Cents /kwh
; - 	 	
i
Cents/1000 gallons treated

1 mgd
kwh
31
372
11,160
5,160
3,300
0


16







$/mo



157. 60
26.41




32.



216.01
1.936
.72
10 ngd
kwh
153
2,293
68,790
62,790
53,610
35,250
16,890

138
103
53





$/mo



157.60
130.36
100 mgd
kwh
1,013
18,700
561,000
555,000
494,220
209.30 !372'66°
150.55
11 Q . 97

70.
97.50
79.50

1,015.08
1.476
.338
251,100

998
963
913
13

$/mo



157.60
863. O8
1,385.78
996.79
1,782.81

70.
97.50
1,350.
17.55
|6,721.11

1.198
1 .224

-------
TABLE VII
                                 COST OF ELECTRICAL POWER - PRIMARY  -  SCHEME II
TYPE OF PLANT; Primary
SLUDGE HANDLING SCHEME: II


KW Demand
kwh/day
kwh /mo
first 6000 kwh
60 x KW Demand x 1.42^/kwh
120 x KW Demand x 1.14pf/kwh
120 x KW Demand x 0,82(zf/kwh
Additional kwh x 0.71^/kwh
KW Demand minus 15
First 35 KW x $2 = $70
Second 50 KW x $1.95 = $97.50
Third 900 KW x $1.50 = $1350
Additional KW Demand x $1.35
1
Total Monthly Bill, dollars
Cents /kwh
Cents/1000 gallons treated

1 n
kwh
34
411
12.330
6,330
4,290
210


19








gd
$/mo



157.60
28.97
2.39



38.



226.96
1.84
.756

10
kwh
156
2,343
70 .,290
64,290
54,930
36,210
17,490

141
106
56






mgd
$/mo



157.60
132.91
213.41
153.50
124.18

70.
97.50
84.00

1 , 033 . 10
1.47
.344

100
kwh
1,138
21,000
630,000
624,000
555,720
419.160
282,600

1,123
1,088
1.038
138
'


i
	 i

mgd
$/mo



157.60 :
969.58
Ie 556,78
1,119.79
2 , 006 . 46

70.
97.50
1,350.
186.30
!
7,514.01 !
1.193
.250 1

-------
TABLE VIII
                           COST OF  ELECTRICAL POWER - ACTIVATED SLUDGE - SCHEME  II
TYPE OF PLANT: Activated Sludge
SLUDGE HANDLING SCHEME: II

KW Demand
kwh/aay
ku-h/mo
first 6000 kwh
60 x KW Demand x 1 . 42jZ?/kwh
120 x KW Demand x 1.14^/kwh
120 x KW Demand x 0.82^/kwh
1
Additional kwh x 0.71^/kwh
KW Demand minus 15
First 35 KW x $2 = $70
Second 50 KW x $1.95 = $97.50
Third 900 KW x $1.50 = $1350
Additional KW Demand x $1.35
Total Monthly Bill, dollars
Cents /kwh
Cents/1000 gallons treated

1 mgd
kwh
95.4
1,145
34,350
28,350
22,626
11,178


80.4
45.4






$/mo



157.60
81.28
130.51
91.67


70.
88.53


619.59
1.80
2.07
10 mgd
kwh
612
9,179
275,370
269,370
232,650
159,210
85,770

596
562
512





$/mo



157.60
521.42
837.22
602.21
608.97

70.
97.5
768.

3,662.92
. 1.33
1.22
100 mgd
kwh
4,566
84,288
2,528,640
2,522,640
2,248,680
1,700,760
1,152,840

4,551
4,516
4,466
3.566




$/mo



157.60
3,890.23
6,246.29
4,492.94
8,185.16
I
70.
97.50
1,350.
4,814.10
29, 303 . 82 i
~i
1.16
.977

-------
TABLE IX
                          COST OF  ELECTRICAL POWER - ACTIVATED SLUDGE - SCHEME III
TYPE OF PLANT: Activated Sludge
SLUDGE HANDLING SCHEME: m


KW Demand
kwh/day
ku'h/mo
first 6000 kwh
60 x KW Demand x 1.42^/kwh
120 x KW Demand x 1.14^/kwh
120 x KW Demand x 0.32c?/kwh
Additional kwh x 0.71^/kwh
KW Demand minus 15
First 35 KW x $2 = $70
-Second 50 KW x $1.95 = $97.50
Third 900 KW x $1.50 = $1350
Additional KW Demand x $1.35
Total Monthly Bill, dollars
Cents/kwh
Cents/1000 gallons treated

1 m
kwh
93
1,115
33,450
27,450
21,870
10,710


78
43







gd
$/mo



157.60
79.24
127.22
87,82


70.
83.85


605.73
1.81
2.01

10
kwh
628
9,414
282,420
276,420
238,740
163,380
88,020

613
578
528




!
1

mgd
$/mo



157.60
535.06
859.10
617.95
624.94

70.
97.50
792.

3,754.15
1.33
1.25

100 mgd
kwh 1 $/mo
1 !
4824 1 [
89,056
2,671,680
2,665,680 157.60
2,376,240 4,110.05
1,797,360 6,599.23
1,218,480 4,746.82
8,651.21
4809
4774 70.
I
4724 j 97.50
3824 |l,350.
i
15, 162.40
,'30, 944.81
i
i 1.15
* 1 . 03

-------
TABLE X
COST OF ELECTRICAL POWER - TRICKLING FILTER  -  SCHEME II
TYPE OF PLANT: Trickling Filter
SLUDGE HANDLING SCHEME: II

KW Demand
kv,'h/day
kwh /mo
first 6000 kvvh
60 x KW Demand x 1 . 42^/kwh
120 x KW Demand x 1.14^/kwh
120 x KW Demand x 0.82<^/kwh
Additional kwh x 0.71ef/kwh
KW Demand minus 15
First 35 KW x $2 = $70
Second 50 KW x $1.95 = $97. 5O
Third 900 KW x $1.5O = $135O
Additional KW Demand x $1.35
Total Monthly Bill, dollars
Cents /kwh
Cents/lOOO gallons treated

1 mgd
kwh
6O
721
21,630
15,630
12,030
4,830


45
1O






$/mo



157.60
51.12
82. 08
39.61


70.
19.50


419.91
1.94
1.40
10 mgd
kwh
320
4,806
144,180
138,180
118,980
SO, 580
42 , ISO

3O5
270
220





$/mo



157.60
272.64
100 mgd
kvjh
2,182
$/mo
i
4O,282
1,208,460
1,202,460
1.071.540
809,700
314.88
547,860
299.48

7O.
97.50
330.

1,979.86
1 _^7
.66
2,167
2,132
2,O82
1.182



157.60
1.859.O6
2,984.98
2,147.09
3,889.81

70.
97.50
1,35O.
1,595.70
;
14^151.74 \
1.17
1
| .472

-------
H
O
-0
O
Cu

r-l
rf
O
•H
M
•p
O
0)
0

-------
rate trickling filters and the estimates made here  is  not  good.
Michel's estimates for trickling filters is only slightly  above
his estimates for conventional primary.  The explanation for
this discrepancy is not known at this time.  The cost  of elec-
trical power versus the amount of power used, taken from Tables
is shown plotted in Figure 12.
                              58

-------
COST OF ELECTRICAL  POWER
                                 5  678910
                                       1O,000
         Daily  Power Usage,  kilowatt-hours/day

                        59
   5  6 7  8 9 10
     100,000
FIGURE 12

-------
ELECTRICAL POWER  REQUIREMENTS  FOR  ADVANCED PROCESSES


The first process which  might  be considered for use downstream
of the activated  sludge  process  is microscreening to  remove sus-
pended solids which  escape  over  the weirs  of the final  clarifier.
Installed electrical horsepower  and average electrical  power con-
sumption for microscreening equipment  is shown in Figure  13.   The
principal source  of  this  information is a  paper presented at  the
41st Annual Meeting  of  the  Ohio  Water  Pollution Control Conference
by E. W. J. Diaper of Glenfield  and Kenned;- Inc.   The triangular
points are from a recent  EPA report 17090  EEM 12/71.  Thus,  the
power actually consumed  is  about 115 kwh/day for 1 mgd, 375 kwh/day
at 10 mgd and 1200 kwh/day  at  100  mgd.  The economy of  scale  is
apparently very significant.
Liquid alum can be added  to the  aerator to remove phosphorus  with
the waste activated  sludge.   The usual dose of aluminum is  1.5
moles of aluminum per mole  of phosphorus in the main  stream.   If
we take the influent phosphorus  concentration as  10 mg/1,  the
aluminum dose would  be  13.05 mg/1  or 144 mg/1 of  dry  alum.   Since
one gallon of liquid alum contains 5.4 Ib.  of dry alum, the amount
of liquid alum used  would be 222 gallons/mg treated.  This  is
equivalent to 9.25 gph/mgd.   It  is customary to install a one-third
horsepower motor  on  all  feeders  up to  60 gph.  A second pump  might
be needed to deliver the  liquid  alum to a  head tank and a one-third
horsepower motor  would  also be adequate for this  purpose.   The ac-
tual horsepower consumed  in raising the liquid 50 ft. would only be
0.3 horsepower at the 100 mgd size.  The total power  consumption
for feeding liquid alum will,  therefore, be taken as  10 kwh/day
at the 1 mgd size, 15 kwh/day  at the 10 mgd size, and 110 kwh/day
at the 100 mgd size.
The addition of alum to  the  aerator will result in extra  sludge
production and extra electrical power consumption.  Addition  of
                               61

-------
                                    EL-RCTRICAL ENERGY REQUIREMENTS FOR MICROSCREENS
               3  4  567891
                                2   3   4567691
                                                         3  4 557891
                                                                          2    3  4567891
                                                                                                   3  4  567891
                                                                                                               1000
                                                                                                                100
0.1
                         10
   .01
                                                                  10
100
                                                                                                            1000
                                                   Design Capacity, mgd
                                                                                                 FIGURE 13

-------
alum to the  aerator  will  result  in an increase  of about  40% in
sludge production.   The increased power consumption for  mixing
and heating  of  anaerobic  digesters will be  about  25 kwh/day at
1 mgd, 90 kwh/day  at 1O mgd,  and 400 kwh/day at the 100  mgd level.
Increased power for  vacuum filtration will  be 42  kwh/day at 1  mgd,
87 kwh/day at 10 mgd,  and 964 kwh/day at 100 mgd.  Additional  power
for incineration of  the extra sludge will amount  to 24 kwh/day at
1 mgd, 141 kwh/day at  10  mgd,  and 1044 kwh/day  at 100 mgd.   Thus,
if we select sludge  handling  scheme II for  use  with alum addition
to the aerator,  the  total additional power  consumption will be
101 kwh/day  at  1 mgd,  333 kwh/day at 10 mgd,  and  2518 kwh/day  at
100 mgd.
For lime clarification, Lake  Tahoe estimates  power consumption as
431 kwh/day  for clarification,  637 kwh/day  for  dewatering of lime
mud, and 55O kwh/day for  recalcining of lime  sludge for  a total of
1618 kwh/day at the  7.5 mgd size.   Lake Tahoe uses two stage lime
clarification with the ammonia stripping tower  built over the
second clarifier.  The EPA report on lime clarification, TWRC-14   ,
gives the installed  horsepower per densator as  14/11 times  the flow in
mgd for sizes of 11  mgd and less and 14 + 0.06  (mgd - 11) for  sizes
greater than 11 mgd.   Thus, the  installed horsepower for a  two stage
lime clarification at  the 7.5  mgd size would be estimated as 10
horsepower per  clarifier  which  would consume  an average  of  408
kwh/day which is close to the  Lake Tahoe value.   Using the  estimates
from TWRC-14 we can  estimate  the power consumption for lime clari-
fication at  the 1 mgd  size as  52 kwh/day, at  the  10 mgd  as  611
kwh/day and  at  the 100 mgd size  as 2958 kwh/day.   The largest
densator will handle 20 mgd so the power requirements for this size
was multiplied  by five to find the estimated power requirements for
the 100 mgd  size.
At the Lake Tahoe plant,  the  lime sludge with a solids concentration
of about 1%  solids is  first gravity thickened to  about 4.9% solids
and then dewatered with centrifuges  before  disposal.   The estimated

-------
lime sludge produced by the 7.5 mgd plants is 17 tons per day of
dry solids.  A fraction of this must be wasted to prevent build-
up of phosphates in the system.  The estimated amount to be re-
calcined is 9 tons per day at the 7.5 mgd plant.  Thus, roughly
one-half of the lime sludge would be combined with the organic
sludges and disposed of by incineration or land fill.
The underflow stream from the lime sludge thickener at Lake Tahoe'
was estimated as 36 gpm with a solids concentration of 4.9%.  The
amount of electrical power used in the dewatering process was given
as 637 kwh/day at the 7.5 mgd size and this would correspond to
31.2 horsepower for 24 hr/day or 0.324 hp/gpm.  Estimates from
the manufacturer for the 24" x 60" centrifuge, used at Lake Tahoe,
was 0.43 - 0.81 hp/gpm.  These values were for digested primary
sludges and, therefore, the 0.324 hp/gpm value seems reasonable.
Therefore, for lime sludge dewatering, the estimates are 84.9 kwh/
day at the 1 mgd size, 849 kwh/day for the 10 mgd size and 8490
kwh/day for the 100 mgd size.
In the Lake Tahoe estimate for recalcination, only the cost of the
recalcined sludge was included and the cost of burning the waste
lime sludge with the organic waste sludge was included in the cost
of the conventional processes.  The policy used here will be to
charge the cost of burning the waste lime sludge to the lime recal-
cination process.  A loading rate of 2 Ib/hr/sq. ft. will be assumed
for the waste lime sludge.  Since about 8 tons/day of waste lime
sludge are burned at the 7.5 mgd size, the estimate of power con-
sumption will be 100 kwh/day at 1 mgd, 450 kwh/day at 10 mgd, and
3500 kwh/day at 100 mgd for burning of the waste lime sludge.
The 14.25 ft. diameter, 6 hearth recalcination furnace used at
Lake Tahoe has a hearth area of 575 sq. ft.  The maximum capacity
of this furnace is given as 20 tons/day or about 3 Ib/hr/sq. ft.
It was found at Lake Tahoe that the optimum feed rate was 1.13
Ib/hr/sq. ft. to maximize the activity of the recalcined lime.
This value will be used here.  Using a recalcination rate of 1.29
                               64

-------
tons/day/mgd, the size of the recalcination furnace at the I mgd
size should be 457 sq. ft. if the furnace is operated an average
of 5 hours per day.
From the electrical power consumption estimates shown in Figure 7
for incineration of organic sludge and the fact that the loading
rate is 2 Ib/hr/sq. ft., we can derive the following relationship
for power consumption in terms of kilowatts/sq. ft.

   kilowatts/sq. ft. = 0.636  (hearth area, sq. ft.)~°'37712

Using this relationship, we find the power consumption for the re-
calcination furnace used at Lake Tahoe to be 33.3 kw.  The 550 kwh/
day estimated at Lake Tahoe would correspond to a loading of about
1.3 Ib/hr/sq. ft.
Using the optimized loading of 1.13 Ib/hr/sq. ft., the 10 mgd plant
would require a hearth area of 951 sq. ft., if operation is 24 hr/day.
The next standard size furnace is 988 sq. ft.  The power consumption
would be 46.7 kw or 1120 kwh/day.  At the 100 mgd size, a hearth
area of 9513 would be required.  Three recalcination furnaces with
hearth area of 3120 sq. ft. would be sufficient.  The power consump-
tion would be 95.5 kw per furnace or 6874 kwh/day total.  Electrical
power consumption for the 1 mgd plant would be 30.8 kw or 154 kwh/day,
Thus, the total power consumption, including burning of waste lime
sludge, would be 254 kwh/day at 1 mgd, 1570 kwh/day at 10 mgd,  and
10,374 kwh/day at 100 mgd.
For recarbonation, Lake Tahoe estimates 702 kwh/day.  It will be
assumed here that power for recarbonation is proportional to flow.
Therefore, the power consumption at 1 mgd would be 93.6 kwh/day,
for 10 mgd, 936 kwh/day, and for the 100 mgd size, 9355 kwh/day.
Ammonia stripping requires a significant amount of power because
the water must be pumped to the top of the tower and the volume
of air required to strip the ammonia from the water is large.  At
Lake Tahoe the estimate was 672 kwh/day/mgd for each day the ammonia
                               65

-------
stripping tower is in operation.  In the colder climates,  the
ammonia stripping tower is likely to freeze in the winter  months
and provision must be made for this if a yearly average is com-
puted.  At Lake Tahoe it was estimated that the tower could  operate
about 65% of the year.
The principal consumptive use of electrical power, associated  with
multi-media filtration, is the energy required to pump the main
stream through the filters.  Additional power is required  for  back-
washing, surface spray, and feeding of chemicals.  The estimates
for electrical power from Lake Tahoe are not generally applicable
because of the filters and the carbon adsorption vessels are in
series, and because of the peculiarities of the site.  For example,
          •«
the total dynamic head for the filters was given as  1OO ft.  of
water.  Actually, the filters which were sized for 5 gpm/sq. ft.
were backwashed when the head across the two filters in series
reached 16 ft. of water.  Horsepower for pumping the main  stream
is given by the following relationship:
             Horsepower = mgd x 0.17546 x TDH/eff

               mgd = millions of gallons per day
               TDH = total dynamic head, ft.
               eff = hydraulic efficiency

Backwash pumps must deliver about 5% of the main stream against a
head of about 75 ft.  Surface wash pumps operate for about 15
minutes per day and are sized for about 1.42 gpm/sq. ft. at  a  head
of about 300 ft.  If we use a hydraulic efficiency of 70% for  the
1 mgd size and an average pumping head of 15 ft., the power  consumed
by the main stream would be 77 kwh/day.  For backwashing,  the  power
consumption would be 19.2 kwh/day.  For surface spray, the power
consumption would be 3.3 kwh/day and the total would be 99.5 kwh/day.
Since the power consumption will be proportional to  flow,  except for
the hydraulic efficiency, the estimate for 10 mgd would be 953 kwh/
day and 8743 kwh/day at the 100 mgd size.
                               66

-------
The pressure drop  through  a  column of  granular  carbon varies  with
the application  rate and with  the length  of  the column.   When the
design contact time and the  hydraulic  surface loading is  known,
the length of the  column can be  computed  with the  following re-
lationship :
     Column Length,  ft.  =  gpm/sg.  ft.  x contact  time,  min.
                                         7.48
If we assume a design contact  time of  40 minutes  and a hydraulic
surface loading of  7 gpm/sq. ft.,  the  length of  the column  re-
quired is 38 ft.  The pressure  drop  through 38 ft. of  clean granular
carbon will be about 8.23  psig  or  19 ft.  of water.  It is common
practice to design  the pressure contactors for a  maximum working
pressure of 50 psi  or 116  ft.  of water.   The average of these two
is about 68 ft. of  water.  Therefore,  the electrical power used in
pumping the main  stream  through the  granular carbon will be about
348 kwh/day at the  1 mgd size.  If variable speed pumping is used
rather than a flow  equalization tank,  this value  might be increased
by about 25%.  The  corresponding values  for 10 mgd and 100 mgd are
3287 kwh/day and  29,308  kwh/day.   About  5% of the main stream will
be used for backwash and the pumping head will be about 75 ft. of
water.  The electrical power consumed  will be 19.2 kwh/day for 1
mgd, 192 kwh/day  for 1O  mgd and 1916 kwh/day for  100 mgd.
The surface spray will operate for about  15 minutes per day and
will be sized for 1.42 gpm/sq. ft.   Thus, the power consumed for
surface spray will  be 3.24 kwh/day at  1  mgd, 32.4 kwh/day at 10
mgd, and 324 kwh/day at  100 mgd.   The  total power consumption for
the carbon columns  will, therefore,  be 371 kwh/day at  1 mgd, 3511
kwh/day at 10 mgd,  and 31,548 kwh/day  at  100 mgd.
The amount of granular carbon to be  regenerated  is about 350 lb/
million gallons treated.   The  recommended loading rate for the
regeneration furnace is  100 Ib/day/sq.  ft. of hearth area or 4.17
Ib/hr/sq. ft.  At the 1  mgd size the smallest standard size re-
generation furnace  (85 sq. ft.) will be  capable  of regenerating

                               67

-------
the spent carbon, operating an average of one hour per day.   At
the 10 mgd size, a furnace with 168 sq. ft. of hearth area will
be capable of regenerating the carbon, operating 5 hours per  day.
At the 100 mgd size, a furnace with 351 sq. ft. will be able  to
regenerate the carbon if it operates 24 hours per day.
At the Lake Tahoe plant a regeneration furnace with about 62  sq.
ft. of hearth area was used.  The maximum capacity of this furnace
was 6000 Ib/day or about 100 Ib/day/sq. ft.  The amount of power
expended for carbon regeneration was 169 kwh/day.  If we estimate
the amount of carbon to be regenerated as 35O Ib/mg, the furnace
would be operated for about 10 hours per day.  Using the relation-
ship for power consumption for a multiple hearth incinerator,  the
power consumption for the regeneration furnace alone would be  about
83 kwh/day.  Thus, the total power used, which would include  trans-
port of the carbon, is about twice that used by the regeneration
furnace alone.  Using this information, we can estimate the power
requirements for the 1 mgd plant as 20 kwh/day at the 1 mgd size,
155 kwh/day at the 10 mgd size, and 1175 kwh/day for the 1OO mgd
size.
The principal consumptive use of electrical power for biological
nitrification is the additional air required.  The amount of oxygen
required to convert ammonia nitrogen to nitrate can be computed
from the following chemical relationship;

         2NH*  + 40  	»~ 2NO"  +  2H O  +  4H+
            ^t      £-*•             J       £
The ratio of oxygen required per pound of nitrogen converted  to
nitrate is, therefore, 64/14 or 4.57.  If we take the concentration
of ammonia nitrogen as 20 mg/1, we can compute that 761 pounds of
oxygen is required per million gallons treated.  If diffused  air
is used to supply the oxygen, the amount of air needed can be  cal-
culated as follows;
      scf/day = (Ib 0 /day)/.075/.21/aeration efficiency
                               68

-------
If we take the aeration efficiency  as  a  nominal  5%,  the  amount
of air needed for nitrification  is  0.967 scf/gallon  treated.  This
is essentially the same as  the amount  of air assumed for the  acti-
vated sludge process.  An additional expenditure of  electrical
energy will be required to  supply about  50% recycle  and  for final
settling.
The denitrification process will require power to keep the floe
in suspension and for  recycle.   The power needed for mixing is
about one-half horsepower per mgd.  Thus,  the power  consumed  will
be about 10.2 kwh/day  at the 1 mgd  size,  102 kwh/day at  the 10
mgd size and 1O20 kwh/day at the 100 mgd size.   Recycle  will  be
taken as 50% of the main stream.
Where demineralization of the water is required,  electrodialysis
or reverse osmosis can be used.  From  EPA report WP-20-AWTR-18
the cost of supplying  DC power to the  electrodialysis process was
given as 0.85 kwh/1000 gallons.  The cost  of pumping the main stream
through the electrodialysis stacks  was estimated as  0.491 kwh per
1000 gallons.  Thus, the total for  reducing the  TDS  of the water
from 850 mg/1 to 500 mg/1 is 1.341  kwh/1000 gallons.
For the reverse osmosis process  the principal consumptive use of
electrical power is for pumping  the main stream  through  the mem-
brane.  The pressure drop through the  reverse osmosis process is
about 500 psig.  About 10%  of the feed stream is  wasted  with  the
rejected salts and a small  amount of power could be  recovered by
using this stream to drive  a turbine.  This  scheme,  however,  has
not been shown to be cost/effective and  it will  not  be considered
here.  At the 1 mgd size, the power consumed will be 5903 kwh/day.
At the 10 mgd size, the corresponding  value is 55,836 kwh/day and
at the 100 mgd size, the power consumption would be  497,811 kwh/day.
                               69

-------
ELECTRICAL POWER REQUIREMENTS FOR ADVANCED  PROCESS  TRAINS


Estimates of electrical power consumption for various alternative
tertiary treatment trains are shown  in Tables XI-XIII.  Train VIII
represents the set of processes used at  Lake Tahoe.  For the
ammonia stripping process, it was assumed that  the  process will
operate 65% of the year.  Trains III and IV represent the sets
of processes which are most  likely to be used in  the near future
for control of nutrients such as nitrogen and phosphorus.  Values
for electrical power consumption shown in Tables  XI-XIII for
trains without demineralization are  shown in graphical form in
Figure 14.
The power requirements for treatment train  III  are  roughly 20%
less than the activated sludge plant using  sludge handling
scheme II.  The Lake Tahoe system shown  as  train  VII is 2O-40%
more expensive in terms of electrical power than  the activated
sludge plant.
                               71

-------
                                                      TABLE XI




ESTIMATED ELECTRICAL POWER  COrlSU?'iTTIO.\'  FOR ALTERNATIVE TERTIARY TREATMENT  TRAINS AFTER SECONDARY TREAT f>Ei\T




                                                Plant Size -
1
ADVANCED PROCESSES USED
•" i i.c ror. c ra«n i rivi
Alum At: 
-------
                                                     TABLE XII




ESTIMATED  ELECTRICAL,  POWER CONSUMPTION FOR ALTERNATIVE TERTIARY TREATMENT  TRAINS AFTER SECOMDARY  TREAT MEi\T




                                               Plant Sirze -  10 mgd
ADVANCED PROCESSES USED
> 1:. c r o L~. c x & -2 n i n .1
Alu.;, Ace it ion and
Ext ra S lud -R I I:\ndl incj
LiKft Clarification
Lime Sludrje Dswataring
Lina R^calcination
Rcca rbonati on
A'Ui^-onia Stripping
,'\ i 1 r :". :J i c s. t i o n
Donf-'crii ication
Mwl'ci- Madia Filtration
i
Granular Carbon Adsorption
Carbon Regeneration
j
Electrooialysis
Reverse Osmosis
Total Power Consumption, kwh/cay
I
375













375
II

333





III

333





6235 6235
102





6670
1O2
953




7623
IV


611
637
1570
-



953




3771
V


VI


611 [ 611
637
157O




953
3511
155


7437
637
157O




953
3511
'155

13,410
20,847
VII









953



55,836
57,239
VIII

1
i
]
611
:
637
157O
:
936
4368


953
3511
155


12,741

-------
                                                   TABLE XIII




ESTTMAfED  ELECTRICAL TOWER CONSUMPTION! FOR ALTERNATIVE TERTIARY TREATMENT TRAINS  AFTER SECONDARY TREATISE NT




                                              Plant Size -  100 mgd







-~J
.p-








ADVAwCED PROCESSES USED
|
" ':'. c r or o r-.-:s : i :_ -MI
Alu:n A'K.ltJ.ori ix'id
Extra SliKi.>~ !r-'.ndliaq
L J. m 2 C 1 a r i J I c ;A t i o n
• Li ~.e Sludge D;:vtering
Li'.n> Racalci nation
R ; _• c a r b o 1 1 a t i o n
A--;MO ni a S r, ri ppi nq
;\lY.ri..'ica iiou
D c- n i -critic a t i o n
fCal'ci-.'.^dir,. Fil trj.tion
Granular Carbon Adsorption
Carbon Regeneration
Electrodialysis
Ra v ••• rse Osmo;; is
Total Power Consumption, kwh/day
I
1,200













1,200
II

2,518





60,255
1,020





63 , 797
_L J. JL

2,518





60,25&
1,020
8 , 743




72,540
I, .


.
2,958
6,370
10,374




8,743




28,445
*


2,958
6,370
10,374




8,743
31,548
1,175


61,168
VI


2,958
6,370
10,374




8,743
31,548
1,175

134,100
195,268
vn:







.

> 8 , 743



497,811
506,554
VII I
i
(

(
2,958
6,370
10,374
9,355
43,680
i

8,743
31,548
1,175
:•-,'

114,203

-------
     ELECTRICAL ENERGY CONSUMPTION FOR TERTIARY WASTEWATER TREATMENT TRAINS
                                     versus

                                   PLANT SIZE
     1OO,OOO
I
c
0
•H
en
C
VI


1
rt
o
•H
M
^
0
01
      10,000 ;io
1,000
         100
10
9
8
7

6
b
4
3
2


10
<)




6
5

4



3
2






10
9
8
7
6
6
4
3
Z




pq




-




~1










-.
=


/




^
^

^
~"
~
~|

4?

1
q





















F

/




^
/

£
• — •
r-,

H






^


















^






^

^
=
-




,,
	 —
	

HffiBffi
^ 	 ::::::::::! — :



H-— :-r;:::::::I:;::
-rS-^^iil:!::!
i 1 ;
^ --. i I....IL---:
_l_ __tf 	
^

1 	 	 j2--



~t 'T
r~ ~W~
fflii^i^ii:E??
|jE|~;;i!! ?~
	 L_-?«..,! 	

< ?' 	 " ?
,? ^ Ix
s s 	 v -
/ S ;;n
/ <' T
i^r n" irati1 I
rz:i:jffi:-:i^::
i-L--?--4ff-5|— -

^_. -. 	 - -.
p==t±:-::::::::::.=C = i
S^^^ffiUtt
	 _. 	 ^^
**
	 Js___ 	 	 _ 1 _
a.'* :::::::::::::: -i


2 3
1 1 1 Hum1! |-| 1 1 1 1 1 1~
— ± 	


:::-:-:::::-=----"-


t
/
	 ;j _ ^ ;;
	 Sz 	 3
L
,' ~ > >
	 ,?.. ,<4'
..../. 	 _.,^Z_H
iSi'^^li-
:::EE;;;iig?EEEft-
:::::;! :;!---Hv4.,^
- - ,i!.( . N <
^i /
. ' i ^
e . jt 	 -. — 1 	 0-1 — 1 —
t 	 	 — ? 	 3
: :±::::::: ^ 	 ~±~
:;?^::::::. — -:::::q





— 	 	 1 	


.,---. _^
*e. - - -
* 	 	 	 — 	



4 5 678910
10




-SS::::JWi
StM i «
^wH^t
Pf^-^|:|4yffi
f- i'-)''
_,£ j? 	
? /r
:^^v.-.::::::;^
-•£--/ \ 	 j'fT
zz x — •'' "

t'
?
^ r
_ — ^ 	 	 —
_^ 	 1 	
>




— — j|E:EE:"i":==









	 1 	 "~ 	 ~7*
E=,EEJ\J:,|:E,:
t 	 j,''- 	 t- ---
t 	 1 	 —
	 	 	 	


2 3
/
1 1 1 1 1 1 II 1 1 1 1 1 1 I |>gL.(

2 T
- 	 ; "if1
-•£±---trt-A — =p£f •
>'- 	 r-;i'3Z-- + i
— 	 	 • j ^-[- ^ — — 	 1 	 1-
----/-/i 	
ij^pjfjf i;^^!
— ;'' 	 	
f ~[~ T


::::::: :::i— :::::,





EE:EEEi:|E:-EEEEEEE





-:"g±|^r:|=E
fflw^ffl
-{-- 	
_.. 	 I __ _.



0 *
£--|l±-5»''!--t:--
T 	 ;|l 	 if
— ,.:! 	 	
.•'-..... -L -
;! 	 _±_.

HfflSlS
f 	 i 	 1 	
	


4 5 678910
1OO
                             Plant Design  Capacity,  mgd


              Note;  I, II, in, iv,  & VIII  refer  to specific treatment
                     trains

                                        75
                                                                  FIGURE  14

-------
COMPARISON WITH OTHER  CONSUMPTIVE USES
The total production of  electrical  power  in the United States
in 1969 has been estimated  by  the Department of Commerce  as
1,522,229 million kwh.   The total for  1971  was  1,717,520  million
kwh.  Residential sales  of  electrical  power totaled 407,922
million kwh in 1969.   In 1969  the average residential  consumption
of electrical power was  5,943  kwh per  year  and  the  average  popu-
lation per household was 3.2 persons.   Thus,  the per capita resi-
dential use of power was about 5.09 kwh/day.
                                          2
According to the Federal Power Commission ,  the average consumption
of electrical power varied  significantly  with the area of the
country from a high of 19,636  kwh/yr/household  in Eugene, Oregon
to a low of 2,275 kwh/yr/household  in  Bronx,  New York.
Commercial and industrial power were combined and divided into
small light and power  and large light  and power.  Power usage for
small light and power  was estimated by the  Department  of Commerce
as 286,686 million kwh in 1969 and  557,222  million  kwh for  large
light and power for a  total of 843,908 kwh/yr for industrial and
commercial.  Thus, commercial  and industrial  power  represented
about 55% of the total power generated while  residential power
represented only 27%.
The Edison Electric Institute   conducted a survey  of  127 companies  to
determine the percentage usage of electrical  power  among various
industries.  The results of the survey is shown in  Table  IX.  The
principal users of electrical  power are primary metals  and  chemicals
and allied products.   The aluminum  industry alone used 51,894
million kwh in 1970.
The estimated power consumption for  plants,  included  in  the  1968
                                        12
Inventory of Municipal Waste Facilities    is  shown in Table  X.
The average usage was 0.0573 kwh/day/capita.   This amount  of power
                                77

-------
                                      TABLE  XIV
      PF.RCF.;:T-\GE DISTRIBUTION- o? MINING A:JD MAMLTACTI-RINC i-;;~HR3 FA- MAJOR CROUPS  
-------
                                              TABLE XV

CONSUMPTION OF ELECTRICAL ENERGY BASED  ON THE 1968 INVENTORY OF MUNICIPAL WASTE FACILITIES
Minor Treatment
Primary Treatment
Intermediate Treatment
Activated Sludge
Trickling Filters
Ponds
Other and Unknown
Tertiary Treatment

   Totals
Population Served

    1,360,870
   36,947,397
    5,857,690
   41,264,036
   29,617,136
    6,123,078
    8,636,514
      325,530
                                                 gpd/capita
122
122
122
123
 89
 89
 89
123
kwh/day/capita

    .0185
    .0286
    .0286
    .113
    .043
    .O135
    .0135
    .226
  130,132,251
 kwh/day

   25,176
1,056,696
  167,530
4,662,836
1,273,537
   82,662
  116,593
   73,570

7,458,600
   Average kwh/day/capita  =  0.0573

-------
consumed in wastewater treatment is about 1% of the average resi-
dential consumption of electrical power.  This amount of power
is about equivalent to one 8 watt bulb in each household, burning
24 hours per day.  If all of the population was served by activated
sludge plants, the power consumption would be about 0.113 kwh/day/
capita which is equivalent to a 15 watt light bulb, burning in each
household 24 hours per day.  A desk lamp is normally equipped with
two 15 watt fluorescent lamps.
Power consumption for tertiary treatment is highly dependent on
the train of processes selected.  For train V the power consumption
is roughly equivalent to the activated sludge process.  For the
Lake Tahoe system, shown as train VIII, the power consumption is
roughly 40-50% greater than activated sludge.  Thus, if we assume
train III or train V, the consumption of power per household would
be roughly equivalent to a 30 watt desk lamp burning for 24 hr/day.
In terms of cost per capita for activated sludge plants, the usage
would be about 0.54 cents/day/household, taking the cost of elec-
trical power as 1.5 cents/kwh.  If tertiary trains III or V are
provided, an additional cost of about 0.44 cents per household day
would be incurred, making a total of roughly 1 cent/household per
day.
                              80

-------
                         ACKNOWLEDGMENTS
This study was made possible through  the help  and  support of
various equipment manufacturers  such  as Westinghouse Electric
Corp., Pacific Flush Tank Division of Rex  Chainbelt, Inc., Dorr-
Oliver, Inc., Bird Machine Co.,  Wallace and Tiernan, Environmental
Control Group, Rex Chainbelt,  Inc., Allis  Chalmers  and others.
The Rex Chainbelt and PFT Engineering Manuals  were  particularly
valuable.  Valuable information  on plant utilities  was supplied
by Black and Veatch Engineers  of Kansas City and by the Cincinnati
Gas and Electric Co.
                                81

-------
                            REFERENCES
 1.  Evans, David R. and Wilson, Jerry  C.,  "Capital  and  Operating
     Costs-AWT," Jour. WPCF, Vol.  44, No. 1, pp.  1-13

 2.  "Typical Electric Bills,"  1970, Federal Power Commission,
     Washington, D. C.

 3.  "Process Equipment - Sewage,  Water,  Industrial  Waste Treat-
     ment," Rex Chainbelt,  Inc., Milwaukee, Wisconsin, Binder
     No. 315, Vol. I and II

 4.  Albertson, J. G., et al, "Investigation of the  Use  of High
     Purity Oxygen Aeration  in  the Conventional Activated Sludge
     Process," EPA Water Pollution Control  Research  Series,
     No. 17050 DNW 05/70

 5.  "Waste Treatment Equipment,"  Pacific Flush Tank Division,
     Rex Chainbelt, Inc., Chicago,  Illinois

 6.  Personal Communication  from Mr. Eugene Guidi of Bird Machine Co.

 7.  Unterberg, W. , Sherwood, R. J. and Schneider, G. R.,
     "Computerized Design and Cost Estimation for Multiple-
     Hearth Sludge Incineration,"  EPA Water Pollution Control
     Research Series, No. 17070 EBP 07/71

 8.  Personal Communication  from Mr. Don  Parkhurst of Black and
     Veatch Consulting Engineers,  Kansas City, Kansas

 9.  Michel, Robert L., "Costs and Manpower for Municipal Waste-
     water Treatment Plant Operation and  Maintenance 1965-1968,"
     Jour. WPCF, Vol. 42, No. 11,  pp. 1883-1910

10.  Seiden, L. and Patel, K., "Mathematical Model of Tertiary
     Treatment by Lime Addition,"  Robert A. Taft Water Research
     Center, Report No. TWRC-14, September  1969

11.  Edison Electric Institute Publication, July 21, 1972,
     "Tabulations of Industrial KWHR Sales by Investor-Owned
     Companies for 1971"

12.  "Municipal Waste Facilities in the United States," Statistical
     Summary, 1968 Inventory, U. S. Dept. of Interior, FWQA
                                83

-------
APPENDIX
   85

-------
  Cincinnati  Oas k Elactrlc Company
    Fourth  and  Main Streets
        Cincinnati, Ohio
P.U.C.O.  Bo.  11
                                      Original  Sheat  Ho.  16-F
                                                Sheet 1  of 2
                                    OSH3BAL S23VTC3 - LAR05

AVAILABILITY
     Available in localities  indicated  on Shasta Ho. 2, S-A of thin schedul*, whsr« facilities  of
     suitable volttg* and adequate  capacity are adjacent to tha prsmiaai to b« sarvsfi.

APPLICABILITY
     Applicable to electric service required for any purpose by an individual customer on  ona
     premiae,  whan supplied at ona point of delivery, except breakdown, standby  or supplemental
     earvico, or rea'als Bervlca not in  conformity  with Ccnpany's service regulations.  When both
     alngl* and thrae phase Harvice Is  required by a customer tho monthly  usage shall be the
     arithmetical sun for three phaae and for  single ph»a« aarvlce.

     Th» account shall never be billed  as one  single phaaa account and  ona three  phaae account  on
     this rst*.  alien cu»tomer'a demand for alngla phaae service has  not exceeded 5 kilowatts  In
     evsry nonth of twelva conaecutlve  months, customers will bo billed for single phaae sarvico
     on R&ta General Service   Small, If available.

TYPS OF 32HVICS - Alternating current 60 Hz, slngla or threa phaae at Company's itand&rd voltoga.

fTST MONTHLY BILL   Computed In accordance with the following chargos: .

A.  Secondary voltage service:  where Company  furnishes  standard rating primary voltage  transferees-*
    and appurtenances and supplies service from  Its overhead or underground ayBtama at standard
    secondary voltage.  Company may meter at primary  or  secondary voltage  aa  circumstances warrant.
    Demand Chargei

    First 15 kilowatt* of Demand or less
    Noxt 35 Kilowatts of Demand
    Haxt 50 kilowatts of Demand
    Noxt 900 kilowatts of Demand
    Additional kilowatts of Demand

    Ensrgy Ch&rget

    First 500 kilowatt hours
    Naxt 1,500 kilowatt hours
    Next It ,000 kilowatt hours
    Haxt 60 kilowatt hours par kilowatt of Damind
    ?/sjct 120 kilowatt hours per kilowatt of Demand
    Next 120 kilowatt hours par kilowatt of Demand
    Additional kilowatt hours
                      40.00
                   at 32.00 p«r kilowatt
                   at SI.95 P«r kilowatt
                   at 31-50 per kilowatt
                   at $1.35 per kilowatt
                    at  5-12^ par  kilowatt  hour
                    at  3.12«! per  kilowatt  hour
                    at  2.13(( per  kilowatt  hour
                    at  l.U2# par  kilowatt  hour
                    at  I.l4jl per  kilowatt  hour
                    at   .82^ per  kilowatt  hour
                    at   .?!<* per  kilowatt  hour
     Plus  or  minus  an  adjustment par kilowatt hour determined in accordance with "Tax Adjustment"
     forth In Sheet Ho.  60 of this tariff.
                                                                                                 set
     Plus  or minus  0.0055^ per kilowatt hour for each 0.5# par million Btu by which the average cost
     of fual burned during the next preceding month  is above or below 20.5^ per million Btu.  Th«
     average cost of fuel burned  shall be  that recorded on Company's books,excluolve of charge* for
     unloading from the  shipping  medium.

     A thrsa phaae  euatoaer  whose demand does not exceed 15 KH all! be charged an additional  surcharge
     of $lt.OO per month  for  the three ph&sa service.

     Minimumi  Tha  Damand Charge  for the Billing Demand but not le»» than $5-00.

     Primary voltage aervlco:  whera customer furnlshss prlnary voltaga  transformers and  appurtenances
     and takes service from  Company's ovarhead or underground By»t«m at  standard primary  nominal
     voltage of 13  KV or higher.   Billing  at yats in paragraph A  above subjact to th»  folloaing
     additional provisional
     Monthly discount par kW billing deamnd
         13
                                                                            66  XV
                                                  10.15
                                                                                              kV
     Undar this paragraph B,  If Company elects to metor at primary voltage tha Xlloaratt hours
     rsglttered on Company's  m*tar will ba reduced 1-1/255 for billing purposes.

     Minimum!  - The Damand Charg» for the billing Damand but for not loss th&A 300 kW.
                                 Isousd by B. John Toigar, Prsald»"t
                                          Cincinnati, Ohio
                                                                             Sffactlv® October 30, 1970
                                             86

-------
The Cincinnati Qaa & Electric Company
       Fourth and Main Streets
          Cincinnati, Ohio
P.U.C.O. No. 11
                                    ORIGINAL SHEET NO.  16-P
                                             SHEET 2 of 2
                                      GENERAL SERVICE - LARQE
 DEMAND
     1.  The Demand shall be the kilowatts derived from the Company's demand meter for the fifteen
     ntinut* period of customer's greatest use during the month adjusted for power factor, as provided
     herein.  At Company's option a demand meter may not be Installed if tha nature of the load clearly
     indicates the load will have a constant demand. In which case the demand will be the calculated
     demand.  The Company may Install a demand meter when the consumption exceeds 2500 kilowatt houra
     for two consecutive months or when the Company has reason to beliave the demand exceeds 15
     kilowatts.

     2.  Wh»n b,oth thra» phase service and single phaae service are supplied each ehall be metered
     a«parat«ly, and the Demand for billing shall be tha arithmetical sum of the demand for thra*
     ph»i» servlc* and for single phaoo service,

     In no tvant will the billing Demand be taken as lass than the higher of tha followingi

       A.  70$ of the highest kllowstta similarly established during the preceding 11 month*.
       b.  300 kilowatts for prlnary voltage service.

     Pow«r factor Adjustment!

     This rat« is based on a maintained power faotor of not less than 90$ lagging and If the Company
     determine Customer's power factor to be less than 9056, tha billing demand will be th« number of
     kilowatts equal to the kilovolt atnparea multiplied by 0.90.

     Power Factor nay be determined by contlnous measurement or'by tests at Company's option;  if by
     continuous measurement, power factor determined during tha Interval in which tha kilowatt asuinui*
     iSsaiand ia established, will be used for billing purposes) If by testa, power faotor dategtmlned
     during a period in which Customer's KW demand as measured la not lesa than 90# of the measured
     kilowatt maximum demand in tha next preceding billing period, will bs-uaed for billing purposes
     until superseded by a poser factor determined by subsequent teat mada at tha direction of Company
     or raquest of Customer.

 PAYMENT
     The H«t Monthly Bill is payable within fourteen (14) days from date.  When not so paid, tha
     Gross Monthly Bill, which is the Hat Montrtly Bill plus 5$, IB due and payable.

 T2HM 0? 8ZHVICB - One (l) year for Secondary voltage service, and three (3) years for Primary volt»s«
     eervloe.

 SEHVIC2 REGULATIONS
     Tha supplying of, and billing for, service and all conditions applying thereto, are aubjaot to
     the Jurisdiction of The Public Utilities Commission of Ohio, and to Company's Sarvloe Regulation*
     currently •ffaotive, as filed with Tha Public Utilities Commission of Ohio, as provided bj law.
                                                                           effective October 30,  1<«70
                                Issued by B. John Yeagar, President
                                         Cincinnati, Ohio
                                              87

-------
               TABLE 8.—NATIONAL WEIGHTED
AVERAGK BILLS FOR INDUSTRIAL SERVICE,
 1935-1070
                                                  cities ouly3
05
00
Average bill

Ja
3t\
Ja.
Ja
Ja.
,I» i
.1 HI
Jai
JKI
.1 a I
Ja;
Ja.
Jill
Jai
Jar
Jai
Jar
Jai
Jnn
Jan
Jai
Jan
J.in
J:.n

i. 3,
i. 3.
i. 3,
i. 3,
i. 3,
. 3,
'• 3,
. 1.
• 3,
. 3,
' l!
• 3,
. 3i
- 3,
• 1,
. 1.
. 3,
. 3,
. 3,
. 1.
- 1,

1!)70
39CS
1 M',!
HH;.-',
3 Oh 4
3 9 r,:i
3 nr>2
liiho
1915
3010
Date 350 I W
"kWli
? G-l S
c::<>

c:;3
r,",i
' (I'M
fj''4
.^

G'>7
(••»o
G''l
010
012
GOG

	 COl
5 S3

5SO
. 	 	 _. f,C5
	 	 	 Gli5
C12

300 }CW
Go.utjy
kV.'ti
*l|li>3
1 ! 1 r!o
i.i nt
3 , 1 CO
3JC7
1.1 -i()
3,1 ::R
1.33-1
3.12-t
1.1211
1,111
1 , 1 03
3,093
1 OsO
l.OSC
3.0-10
3 ,03i5
1.043
1.002
l,b;>5
3.000 kW
2IHI.IKK)
Si-lL'.S
3.-VJ2
3.-I07
.1.423
3,-n-t
3.442
•X2S.1
3.279
3.204
31302
3,154
3,042
3'.024
O >^(>O
2!S28
3,081
Avernpre cliarfre per k\Vh Index of avcrapc hill (1007=100)
3T.O KW
:;o.oi)0
2. 1C
2.12
2.11
2.33
2.10
2.11
2.11
2.1.-1
2.09
2. OS
2 09
2.07
2.07
2.05
2.04
2.02
2 02
2.'00
1.04
1.93
1.03
l.SS
1.88
2.04
300 kW
G<>. (nil)
k\Vli
1.97
1 .04
3.93
3.93
3.02
1.93
1.03
1.95
3 .90
l.SO
l!,S7
1.S7
1.K5
3.P4
3..S2
1.S2
1.R1
1.74
1.73
1.74
1.C7
l.CC
1.81
1.000 kW
200.000
k\\'h
1.75
1.72
3.71
1.71
1.70
1.71
1.71
3.72
3. OS
1.07
1.05
1.0-1
1.G4
l.r.2
l.f.O
1.5S
1.58
1.5S
i.r,2
1.51
1.51
1.43
1.41
1.54
ir.o i;W
"k\Vli
102.4
100.5
300.2
100.0
00.7
100 2
100.2
100.K
99.2
OS G
09.1
OS. 3
OS.l
97.3
90.7
05.7
05. C
94.9
92.1
91.3
91. G
89 3
R9.3
8C.7
300 IcW
<;o ooo
k\Vli
302.1
300.3
100.1
300.0
!.9.C
300.1
300.0
100.7
9S.4
OS.O
97.8
07.0
00.0
ij'i'.l
04.0
93.7
00.3
89.4
90.0
SG.5
85.8
93.G
1.0(10 V-W
200 (M)0
k\Vli
102.0
300.4
300 2
300.0
lob'.o
99.S
lOu.G
07.9
97.5
on!o
05.8
91.5
o:>.G
92. G
02.4
92.2
PR. 9
RS.O
gK.4
83.7
S2.G
90.0
            Source:  Federal"Power Commission Report FPC  R-76  "Typical Electric
                     Bills  197O"  Federal Power Commission, Washington, D. C.

-------
Comparison Between Federal Power
Commission Power Categories and
CG&E Schedule


KW Demand
kwh/day
kwh /mo
first 6000 kwh
60 x KW Demand x 1 . 42gf/kwh
120 x KW Demand x 1.14^/kwh
120 x KW Demand x 0.82^/kwh
Additional kwh x 0.71jZ?/kwh
KW Demand minus 15
First 35 KW x $2 = $70
Second 50 KW x $1.95 = $97.50
Third 9OO KW x $1.50 = $1350
Additional KW Demand x $1.35
Total Monthly Bill, dollars
Cents /kwh
Ccnts/lOOO gallons treated

1 m
kwh
ISO

3O,OOO
24,000
15,OOO



135
10O
50






gd
$/mo



157.60
127. 8O
171.



7O.
97.50
75.

698.90
2.33


10
kwh
3OO

6O , OOO
54,OOO
36, OOO
O


285
25O
2OO






mgd
$/mo



157.60
255. 6O
410 . 4O



7O.
97. 5O
300.

•
1,291.1
2.15
!

100
kwh
1,OOO

200 , OOO
194,OOO
134,OOO
14,000


985
95O
900




;

mod
$/rno
i
j

!
t
1
157.60
1
852.
i
1,368.
114. 8O
;
I
i

70.
i
i
Qv.sn i
1,35O. |

4,OO9.9O !
2.OO j
1

-------
   SELECTED WATER
   RESOURCES ABSTRACTS
   INPUT TRANSACTION FORM
                     1. Report No.
                       3.  Accession No.
   4. Title
           ELECTRICAL POWER CONSUMPTION FOR  MUNICIPAL
           WASTEWATER TREATMENT
   7. Author(s)
             Robert Smith
   9. Organization      .         . _   ,   , .     .
                Envxronmental Protection Agency
                National  Environmental  Research Center
                Advanced  Waste Treatment  Research Laboratory
                Cincinnati, Ohio   45268
  12. Sponsoring Organization

  IS. Supplementary Notes

             Environmental  Protection Agency report number,
 	EPA-R2-73-281, July 1973.
                                         5. Report Date  Aug.  1972
                                         6.
                                         8. Performing Organization
                                           Report No.

                                        10. Project No.
                                        11. Contract I Grant No.
                                        13. Type of Re port and
                                           Period Covered
  16. Abstract

     Electrical power consumption by most  conventional and advanced processes
     for  treating municipal wastewater has been estimated on a unit process
     basis.   Electrical power  for complete plants has  been estimated by adding
     power consumption for individual processes and plant utilities.  Electrical
     power consumption for wastewater treatment has been compared to other
     consumptive uses of electrical power.
  17a. Descriptors
     *Waste water Treatment,  ^Electrical  Power Demand,  *Electric  Power Costs,
     Sewage Treatment Plants,  Sewage Works
  17b. Identifiers

     Wastevmter Treatment Processes, Electrical Power Consumption
  17c. COWRK Field & Group
  18. Availability
19. Security Class.
   (Report)
                         20. Security Class.
                            (Page)
  Abstractor    Robert  Smith
21. No. of
   Pages

22. Price
                                                      Send To:
                            WATER RESOURCES SCIENTIFIC INFORMATION CENTER
                            U.S. DEPARTMENT OF THE INTERIOR
                            WASHINGTON, D. C. 20240
                                      Institution
                        EPA
WRSIC 102 (REV. JUNE 1971 )
                                                                               GP 0 9 13.26 ?

-------