EPA-670/2-73-067
September 1973
                        Environmental Protection Technology Series
   Hypochlorination of Polluted Stormwater

   Pumpage at New  Orleans
X
\.
                                              £o
                                                LU
                                                CD
                                 Office of Research and Development

                                 U.S. Environmental Protection Agency

                                 Washington, D.C. 20460

-------
            RESEARCH REPORTING SERIES
Research reports of the  Office  of  Research  and
Monitoring,  Environmental Protection Agency, have
been grouped into five series.  These  five  broad
categories  were established to facilitate further
development  and  application   of   environmental
technology.   Elimination  of traditional grouping
was  consciously  planned  to  foster   technology
transfer   and  a  maximum  interface  in  related
fields.  The five series are:

   1.  Environmental Health Effects Research
   2.  Environmental Protection Technology
   3.  Ecological Research
   1.  Environmental Monitoring
   5.  Socioeconomic Environmental Studies

This report has been assigned to the ENVIRONMENTAL
PROTECTION   TECHNOLOGY   series.    This   series
describes   research   performed  to  develop  and
demonstrate   instrumentation,    equipment    and
methodology  to  repair  or  prevent environmental
degradation from point and  non-point  sources  of
pollution.  This work provides the new or improved
technology  required for the control and treatment
of pollution sources to meet environmental quality
standards.

-------
                                             EPA-670/2-73-067
                                              September 1973
HYPOCHLORINATION OF POLLUTED STORMWATER PUMPAGE AT NEW ORLEANS
                                by

                          Uwe R. Pontius

                       Edgar H. Pavia, P.E.

                         Donald G. Crowder



                        Project #11023 FAS
                         Project Officer
                         Robert L. Killer
             Research and Development Representative
         Region VI, U.S. Environmental Protection Agency
                       Dallas, Texas 75201
                           Prepared for
                Office of Research and Development
               U.S. ENVIRONMENTAL PROTECTION AGENCY
                     Washington, D.C. 20460

-------
                EPA Review Notice
This report has been reviewed by the Environmental
Protection Agency and approved for publication.
Approval does not signify that the contents nec-
essarily reflect the views and policies of the
Environmental Protection Agency, nor does mention
of trade names or commercial products constitute
endorsement or recommendation for use.

-------
                        ABSTRACT
Storm water from the streets of New Orleans flows to large
drainage pumping stations where it is discharged into Lake
Pontchartrain by means of long outfall canals.   To reduce
the coliform density, storm water was disinfected with
sodium hypochlorite (NaOCl).  Project facilities included
manufacture, transportation, storage and feeding of 100 gram/1
NaOCl.  Residual chlorine analyzers were used to monitor NaOCl
dosage levels.  Sixteen high volume storms totaling 109 gal.  of
storm water were treated with more than 35,000  gal, of NaOCl.

Total and fecal coliform in untreated storm water exceeded
103 org/100 ml, 99% of the time.  Coliform densities in
treated water were significantly reduced, with  chlorine
residuals (total available) of greater than 0.5 mg/1 resulting
in 99.99% or greater removal.  However, rapid recovery of
coliform levels occurred within 2k hours.  Total coliform
recovered to pre-disinfection levels, but fecals did not.
The recovery did not appear to be the result of tidal influ-
ences.  Long term fecal coliform levels were reduced by one
order of magnitude in each outfall canal.

The amortized cost of NaOCl manufacturing, transporting,
feeding and control facilities was $53,600/yr.   NaOCl costs
for treating ~6xlO-L  gal. of storm water yearly were
$200,300.  This resulted in a treatment cost of $.000051/gal.

This report was submitted in fulfillment of Project # 11023
FAS under the sponsorship of the U.S. Environmental Protection
Agency.

-------
                        CONTENTS
Section No.

      I

     II

    III

     IV
     VI

    VII


   VIII

     IX

      X


     XI

    XII

   XIII

    XIV

     XV

    XVI
      Title                     Page No

Conclusions                         ^

Recommendations                     *
                                    £
Introduction                        D

Description 3 History, and          11
Development of the New Orleans
Drainage System

Design and Construction of         is
Disinfectant Facilities

Transportation Equipment           37

Sodium Hypochlorite Storage        39
Facilities

NaOCl Disinfection Facilities      42

Evaluation Program                 59

Microbiological Aspects of Storm  122
Water and Disinfectants
Economics

Acknowledgments

References
                                  130

                                  135

                                  136
Project Patents and Publications  139

Glossary and Abbreviations        140

Appendices                        143
                               IV

-------
                           FIGURES

Figure No.                                          Page No,,

     1              Map of New Orleans and              7
                    Lake Pontchartrain

     2              Cross Section of  New             12
                    Orleans

     3              Map of Present Day Drainage       15
                    System

     4              DPS #3  Exterior View of          16
                    Discharge Side

     5              DPS #3  Interior View             16

     6              Pumping, Rainfall, and            21
                    Coliform Record - DPS #7  1963

     7              Averaging Tank and Reactor        23

     8              NaOCl Manufacturing Plant         25

     9              Flow Sheet - NaOCl Manufacturing  27
                    Plant

    10              Control Panel at NaOCl            28
                    Manufacturing Plant

    11              NaOCl Reactor                     31

    12              NaOCl Transport Trucks            37

    13              NaOCl Storage and Pumping         44
                    Facilities DPS #3

    14              NaOCl Supply Header and           44
                    Discharge Nozzles

    15              DPS #3 and #4 - Flow Sheet        45
                    NaOCl Feeding Facilities

    16              NaOCl Feedline   DPS #4           46

    17              DPS #7  Flow Sheet  NaOCl         48
                    Feeding Facilities

-------
Figure                                                 gggg.

  18                St.  Charles DPS - Flow Sheet        50
                    NaOCl Feeding Facilities

  19                Cross Section of St.  Charles        51
                    Reaction Basin

  20                St.  Charles DPS - Reaction Basin    52

  21                DPS  #7 - Residual Chlorine          53
                    Analyzer

  22                St.  Charles DPS - NaOCl Control     55
                    Panel

  23                Automatic Water Sampler - Interior  57
                    View

  24                Exterior View of Metal Building     58

  25                DPS  £7 Bacterial and  Physical       61
                    Parameters  5 Year Base Period
                    Evaluation

  26                Schematic Diagram of  Drainage       66
                    System Involved in Project

  27                Pre-Construction Evaluation         69
                    Project Sampling Points

  28                DPS  £7 - Pre-Construction           70
                    Evaluation Program -  Bacterial,
                    Rainfall, and Ivater Pumped Data

  29                Orleans Ave. Canal (DPS #7) -       72
                    Pre-Construction Evaluation
                    Program-Total Coliform Histogram

  30                Orleans Ave. Canal (DPS #7) -       73
                    Pre-Construction Evaluation
                    Program-Suspended Solids Histogram

  31                Orleans Ave. Canal (DPS #7) -       74
                    Pre-Construction Evaluation
                    Program-Dissolved Oxygen
                    Histogram
                               VI

-------
Figure                                                Page

  32             Orleans Ave.  Canal (DPS #7) -          75
                 Pre-Construction Evaluation
                 Program Temperature Histogram

  33             Pre-Construction Evaluation            78
                 Program - Total Coliform -
                 Arithmetic Mean vs Time
                 DPS #3, 4, and 7 Discharge

  34-             Pre-Construction Evaluation            79
                 Program - Suspended Solids -
                 Arithmetic Mean vs Time
                 DPS #3, 4, and 7 Discharge

  35             Pre-Construction Evaluation            80
                 Program - Dissolved Oxygen -
                 Arithmetic Mean vs Time
                 DPS #3, 4, and 7 Discharge

  36             Pre-Construction Evaluation            81
                 Program - Temperature -
                 DPS #3, 4, and 7 Discharge
                 Arithmetic Mean vs Time

  37             DPS #7  Pre-Construction               82
                 Evalution Program - Parameter
                 Levels - % vs Day

  38             Post-Construction Evaluation           91
                 Program - Storm Water Sampling
                 Points

  39             London Ave. Canal (DPS #3 S 4)         96
                 Total Coliform Levels  5 Year
                 Base Period, Pre-Construction and
                 Post-Construction Evaluation Program

  40             London Ave. Canal (DPS #384)         97
                 Fecal Coliform Levels  5 Year Base
                 Period, Pre-Construction and Post-
                 Construction Evaluation Program

  ill             Orleans Ave. Canal (DPS #7)            d8
                 Total Coliform Levels 5 Year Base
                 Period, Pre-Construction and Post-
                 Construction Evaluation Program
                              Vll

-------
Figure                                                Page_

  H2             Orleans Ave.  Canal (DPS #7)            99
                 Fecal Coliform Levels  5 Year Base
                 Period, Pre-Construction and Post-
                 Construction  Evaluation Program

  43             St.  Charles Reaction Basin (St.       1,00
                 Charles DPS)  Total Coliform Levels
                 5  Year Base Period,  Pre-Construction
                 and  Post-Construction Evaluation
                 Program

  44             St.  Charles Reaction Basin (St.       101
                 Charles DPS)  Fecal Coliform Levels
                 5  Year Base Period,  Pre-Construction
                 and  Post-Construction Evaluation
                 Program

  45             DPS  #3 Storm  Aftergrowth Study        106

  46             DPS  #7 Orleans Ave.  Outfall Canal     107

  47             DPS  #7 Storm  Profile Physical         111
                 Results Nov.  13,  1972

  48             Storm Profile Chemical Results
                 Nov.  13, 1972

  49             DPS  #7 Storm  Profile Bacterial        113
                 Results Nov.  13,  1972

  50             DPS  #7 Post-Construction Evaluation   116
                 Program Average Total Suspended
                 Matter Initial and Final Samples

  51             Point A - Sampler Inlet at DPS #7     118

  52             DPS  #7 - Post-Construction Evaluation 1-20
                 Program Storm Profile Aftergrowth
                 Study

  53             Bacterial Growth  Curve                123
                             Vlll

-------
                           TABLES

Table No.                                          Page No.

    1            Average Rainfall: 1967-              13
                 Aug. 1972

    2            Capacities of Drainage Pumping       17
                 Stations

    3            NaOCl Plant Equipment and            33
                 Material List

    4            Aging Characteristics of Stored      35
                 NaOCl

    5            Bacterial Percentile Levels:         63
                 5 Year Base Period

    6            Rainfall and Water Pumped            65
                 Frequencies

    7            Bacterial Percentage Levels:         77
                 5 Year Base Period vs Pre-
                 Construction Evaluation

    8            Means and Standard Deviations        85
                 Pre-Construction Data 22
                 Month Analysis

    9            Coliform Correlation Coefficients    87

   10            Post Construction Storm Water        93
                 Treatment Episodes

   11            DPS #7 - Pre and Post-Construction   95
                 Evaluation Program:  Means and
                 Standard Deviations of Chemical
                 and Physical Parameters

   12            DPS #3 - Pre and Post-Construction  102
                 Evaluation Program:  Means and
                 Standard Deviations of Chemical
                 and Physical Parameters

   13            DPS #4 - Pre and Post-Construction  103
                 Evaluation Program:  Means and
                 Standard Deviations of Chemical
                 and Physical Parameters
                             IX

-------
Table Uo.                                           Page Mo.

   14            St.  Charles - Pre and Post-         104
                 Construction Evaluation Program
                 Means and Standard Deviations of
                 Chemical and Physical Parameters

   15            DPS  §3 Storm Sampling,  Bacterial,   105
                 Chemical, and Physical  Results

   16            DPS  #7 - Storm Sampling,  Bacterial,  108
                 Chemical, and Physica'l  Results

   17            DPS  #7:  Volumetric Time Delays      HO

   13            DPS  #7 - Maximum Coliform Reduction  117
                 for  Sixteen Storm Profiles

   19            Fixed Costs:   NaOCl Manufacturing   131
                 Plant

   20            Average  Cost of Manufacturing       132
                 NaOCl

   21            Fixed Costs:   NaOCl Feeding         132
                 Facilities

   22            Fixed Costs:   Chemical  Feed         133
                 Systems

   23            Total Fixed Costs                   133

-------
                        SECTION I

                       CONCLUSIONS
1.  Demonstration of the feasibility of reducing total coliform
and fecal coliform levels in large volumes of storm water
by chemical disinfection and of the effectiveness of
utilizing open channels in populated areas as treatment
facilities met with unqualified success.  It was also possible
to reduce the coliform levels of storm water discharged into
the outfall canals.  However, recovery of coliform levels
after 24 hrs obscured the goal of coliform reduction in water
ultimately discharged to the lake since treated water could
remain in the outfall canal for days or weeks after treatment.

2.  NaOCl was added to storm water during 16 high volume
storm and more than 20 low volume storms.  During the 16
high volume storms, 1.0UxlO9 gals, of storm water were
treated with more than 3.5x10^ gals, of NaOCl.   The largest
single treatment episode was 6.8x107 gals, of storm water
with 8.1x103 gals, of NaOCl.  Sampling programs both before
and during hypochlorination were extensive with more than
2600 water samples taken for analysis.  The resulting data
set exceeded 26,000 items.

3.  Pre-Construction Sampling Programs indicated that 99% of
the total coliform densities in the storm water reaching the
pumping stations were greater than the 1,000 org/100 ml
recommended for body contact recreation areas by the Louisiana
State Board of Health.  Fecal coliform densities were also
high with 99% greater than 100 org/100 ml.

4.  From a consideration of the 16 high volume storms, chlorine
residuals greater than 0.5 mg/1 resulted in 99.99% or greater
reduction of bacterial densities.  For several storms minimum
bacterial densities after disinfection were 100 org/100 ml for
total coliform, and <10 org/100 ml for fecal coliform.

5.  Upon cessation of disinfection, coliform bacterial levels
in the outfall canals recovered within 24 to 30 hours.  Total
coliform recovery levels of 106 org/100 ml were comparable to
those normally found in the outfall canals.  Fecal coliform
recovery levels of 10  org/100 ml were approximately two
orders of magnitude less than normal endogenous levels.  Tidal
influences did not appear to be a factor.

6.  The coliform bacteria surviving disinfection are on the
logarithmic growth phase and the declining growth phase for
the first 24 to 30 hours.  This can result in rapid recovery

-------
of the bacterial population to that level normally found in
the outfall canal.  This rapid recovery changes significance
of the coliform levels.  Their use as indicators of possible
pathogenicity of the storm water is obscured once disinfection
has occurred.

7.  Since there are over lOxlO5 cu ft of water and associated
benthos in most of the outfall canals, it is not economically
possible or ecologically desirable to keep a chlorine
residual in the outfall canal at all times tc prevent coliform
level recovery.  Also, pathogens are not likely to reproduce
in the harsh environment encountered in the outfall canals.

8.  With recovery of indicator bacteria after disinfection,
the environmental conditions in the outfall canals dictate
the levels and viability of pathogens in the disinfected
storm water.  The important environmental considerations are:
(1) temperature, (2) interference of growth due to competing
microorganisms, (3) time since introduction of microorganisms,
(4) the initial and subsequent effects of substances such as
NaOCl or other inhabiting chemicals either from natural or
manmade sources, and (5) the presence of solid materials in
the water which can shelter the microorganisms from attack.

9.  BOD, COD and suspended solids levels in the outfall
canals indicated that 99.5% of the BOD values <50 mg/1,
97.7% of the COD values <175 mg/1, and 95.1% of the suspended
solids levels <100 mg/1.  The majority of values which
exceeded these levels occurred just after initiation of pumping.

10.  Long term levels of fecal coliform in the outfall canals
were reduced by one or more orders of magnitude at each
pumping station where NaOCl was added.  Long term total
coliform levels were approximately the same as pre-disinfection
values, except for a one order of magnitude reduction at
one pumping station where all storm water was disinfected.

11.  The automatic, continuous, sodium hypochlorite (NaOCl)
manufacturing plant, utilizing a patented process, is
capable of producing 1,000 gal./hr of 120 gram/liter NaOCl
under atmospheric conditions.  This method of manufacture
proved to be extremely safe and reliable during the project.

12.  The two, 3,000 gal., lined steel transport trucks were
able to maintain NaOCl stores at the pumping stations with
no difficulty.  Both trucks were fully operational at the
termination of the project and appear suitable for transport
of high strength NaOCl,

-------
13.  High strength NaOCl was stored in 20,000 gal., cylindrical,
lined steel storage tanks.  The tanks were lined with white
natural rubber, flexible hard rubber, and polyethylene.   The
storage tanks were in operation for four years under ambient
temperature and high NaOCl concentration conditions.  During
this period no failures of any tanks have occurred.  Thus,
these linings seem suitable for containment of high strength
NaOCl.

11.  The field half life of the stored NaOCl, with an initial
concentration of greater than 90 grams/liter, exposed to
ambient conditions (March through August), averaged 133  days.
Thus, the use of 20,000 gals., cylindrical- linpd steel
tanks appears to be a quite satisfactory storage'method  for
high strength NaOCl.

15.  The intermittent pumpage of high strength NaOCl with
long term contact between pumpage results in the rapid
failure of polypropylene lined NaCCl pump  and ORP cell
mountings.

16.  Chlorine residual (C^R) analyzers used to indicate
treatment levels performed adequately after a continuous water
supply was installed for operation between storm pumpages.
This modification resulted in an inordinate use of buffer
chemicals for the operation of the analyzer-  At present,
there do not exist any residual chlorine analyzers which
can be used intermittently on storm water without major
modification.

17.  The automatic discrete water sampler designed and con-
structed for the project operated satisfactorily.  However,
sampling intake heads, located in the storm water streams
with high velocities, were ineffective as the sample head
would tilt and break prime on the sample pump.

18.  The addition of NaOCl at a point prior to the pumping
of storm water resulted in excellent mixing of the NaOCl
with the storm water.  One location where a constriction
of flow in the outfall canal was to provide for complete
mixing was not effective as channeling of the water took
place.  This resulted in inadequate mixing of the storm
water and disinfectant.

19.  The addition of NaOCl to polluted storm water involves
eight major cost elements: (1) land, (2) manufacturing
facilities, (3) transportation facilities, (4) storage
facilities, (5) chemical feed systems, (6) chemicals, (7)
operation and maintenance, and (8) amortization cost.

-------
20.  The total cost of facilities was $53,600/yp.   The cost
of manufacturing NaOCl to treat 5x10^-° gals,  of storm water
]5er year, with a chlorine demand of 3.5 mg/1, at a level of
1.0 mg/1 residual,  is $200,300.  On this basis, the average
treatment cost is $.000051/gal. of storm water.

-------
                         SECTION II

                       RECOMMENDATIONS
1.  Disinfection should be continued in order to decrease
levels of possible pathogens even if coliform levels recover
since the environmental conditions are not favorable for
pathogen regrowth.

2.  Controlled microbiological studies of the recovery
phenomenon, in situ, are indicated.  Specific tests for
pathogens should be included as well as the standard coliform
procedures in order to ascertain the proper use of coliform
levels in controlling storm water discharge after disinfection
and to study the various parameters affecting pathogen removal
in treated storm water.

3.  Chlorine residuals of 0.5 mg/1 should be maintained since
contact time is sufficiently long to decrease the levels of
coliform to less than the 1000 org/100 ml suggested for
body contact recreation areas by the Louisiana State Board
of Health.

4-.  The point of disinfectant addition should be prior to
storm water pumpage whenever possible so that adequate mixing
will take place.  This is expecially desirable from the
standpoint of rupturing large clumps of material and allowing
maximum NaOCl contact.

5.  Since shut down of residual chlorine analyzers between
periods of storm water disinfection resulted in rapid failure
of the analyzers, a constant water supply should be provided
whenever this equipment is used intermittently.  In addition,
the excessive cost of buffer chemicals for the machines should
be circumvented by mixing the necessary chemicals in bulk
on site, rather than using commercially available mixtures.

6.  In order to decrease the adverse effects of long term
contact with high strength NaOCl, all equipment should be
flushed with water between usages, when possible.  This would
be a much less expensive procedure in the long term when
considering the disparity (10:1) in the initial cost of
the polyethylene versus all titanium equipment.

7.  The possibility of using ORP readings in a feedforward
loop to control disinfectant feed should be studied.  Residual
chlorine feedback signals could be used as an overriding
parameter.

-------
                          SECTION  III

                         INTRODUCTION


The project,  "Hypochlorination of  Polluted Storm Water Pumpage
at New Orleans"",  consisted of demonstrating the use of sodium
hypochlorite (NaOCl) for disinfecting  storm water pumped from
the east bank of the city of New Orleans into Lake Pontchartrain
(Figure 1).  Initiated in December, 1966, the project_also
included the construction of NaOCl manufacturing, delivery, and
monitoring systems.  Two extensive data acquisition and analysis
programs were carried out to evaluate  the short and long term
effects of disinfection on the quality of the water subsequently
discharged to Lake Pontchartrain.   The project was completed
in September of 1972.

The project had three basic purposes:
     1.  To demonstrate the feasibility of reducing
         the total and fecal coliform  count in large
         volumes of storm water by chemical disinfection.
     2.  To demonstrate the effectiveness of utilizing
         open channels in populated areas as treatment
         facilities.
     3.  To reduce the coliform ba.cteria levels of storm
         water discharged into Lake Pontchartrain, a
         recreational body of water.

The feasibility of reducing the total  and fecal coliform counts
in large volumes of storm water by chemical disinfection and
the demonstration of the effectiveness of utilizing open
channels in populated areas as treatment facilities met with
unqualified success.  Coliform levels  were reduced in the
outfall canals after treatment with no apparent deleterious
effects on surrounding, residential areas from hypochlorination.
However, the determination of bacterial levels in the sur-
rounding waters of Lake Pontchartrain  with respect to the
treated water was not possible since several days to several
weeks could pass before treated water  would leave the 10,000
ft long outfall canals.  Since coliform levels recovered
during this time, the concept of coliform control became
obscured.  In addition, the number of  samples taken in the
lake were insufficient to determine the causative source of
either increase or decrease of coliform levels.  This is due
to the large size of the lake, and numerous points of discharge
other than the treated water from the  outfall canals.  However,
levels of coliform at points of immediate discharge into the
lake were lowered,   (32)

-------
FIGURE 1   MAP OF NEW  ORLEANS  8  LAKE  PONTCHARTRAIN

-------
FACILITIES

The project was initiated after data taken between 1961 and
1966 (Five Year Base Period) indicated that storm drainage
water being pumped from the east bank of New Orleans into
Lake Pontchartrain was grossly polluted vrith indicator
bacteria.  Since an elevated level of indicator bacteria was
the only form of gross pollution demonstrated by the base
period data, it was felt that disinfection on a large scale
would be adequate to restore the .quality of the water to an
acceptable level.  To accomplish this, it was decided to add
disinfectant to the storm water pumped by four drainage pump-
ing stations (DPS), DPS #3, DPS #4, DPS.#7, and St. Charles",
which are located on three outfall canals on the east bank
of New Orleans.  The four DPS have a combined pumping capac-
ity of 11,050 cfs and each normally pumps in excess of
20,000,000 cfd of storm water on rainy days.

Due to the large amount of polluted water being pumped and
the concomitant requirement for large quantities of disin-
fectant, the project included the design and construction of
a NaOCl manufacturing plant to prepare the disinfectant used
during the demonstration phase.  Disinfectant prepared at
the NaOCl manufacturing plant was stored at feeding facilities
located adjacent to each pumping station in the project.  In
order to evaluate the effects of feeding NaOCl to the polluted
storm water, sampling facilities were installed at each
pumping station.  Analytic equipment at the sampling facilities
consisted of water samplers, amperometric residual chlorine
analyzers, temperature probes, and dissolved oxygen (DO) meters,
EVALUATION PROGRAM

The first data acquisition program consisted of a 22 month
Pre-Construction Evaluation Program whose purpose was to
provide base line bacterial, chemical, and physical levels
for each canal, from which changes produced by the addition
of NaOCl could be determined.  The 22 month Pre-Construction
Evaluation Program consisted of obtaining grab samples of
water in the suction bays and outfall canals at regular
intervals and analyzing these samples for applicable sanitary
parameters, i.e., total coliform, fecal coliform, chemical
oxygen demand (COD), biochemical oxygen demand (BOD), chlorine
demand (C1D), and solids.  The data acquired from these grab
samples as well as that from the Five Year Base Period was
then used to generate statistics which characterized the
quality of the drainage water normally found in the system.

Upon completion of construction, a Post-Construction Evaluation

-------
Program continued the routine sampling of the open outfall
canals between periods of disinfectant feeding so that the
long term effects of disinfection could be determined.
Additionally, low volume storm and high volume storm profile
samples were taken.  Storm sampling provided composite
samples of untreated storm water in the suction bays of the
pumping station and chlorinated samples from the discharge
side after disinfection during low volume pumping episodes.
The composite samples were evaluated immediately.  When
possible, portions were then stored and sampled again at
24 hour intervals for three days in a bacterial aftergrowth
study.  A storm profile consisted of numerous samples taken
prior to and after the addition of the disinfectant during
periods of high rates of storm water pumpage.  One storm
profile aftergrowth study was performed by operating a
sampler at the outfall canal for 30 hours, at two hour
intervals following disinfection.  Additionally, samples
were taken in Lake Pontchartrain weekly during the
Pre-Construction Evaluation Program and after storms during
the Post-Construction Evaluation Program.
RESULTS
Weekly sampling during the post-construction period indicated
that few changes had taken place in the outfall canals and
suction bays of the various pumping stations in the project
since the Pre-Construction Evaluation Program.  There were
minor changes of the chemical and physical parameter levels,
but these were within the range of the pre-construction base
lines.  Total coliform levels at DPS #3, #4, and St. Charles
remained high and other parameters were of comparable values.
However, fecal coliform values in the outfall canals at all
stations between episodes of NaOCl addition showed significant
decreases from those of the Pre-Construction Evaluation Program,
Additionally, the long term total coliform level at DPS #7 has
been lowered.  This trend was obvious even though rapid
recovery of indicator coliform levels in the outfall canals
occurs after residual chlorine levels disappear.  However,
fecal coliform levels do not recover to pre-treatment levels.
Thus, as discussed later, the indicator significance of the
coliform group is obscured once NaOCl has been added to the
water.  Pathogens are not likely to reproduce in the outfall
canals, but regrowth of non-pathogenic bacteria is a natural
and expected phenomenon.  During storm profiles, bacterial
densities were greatly reduced in the storm water which had
NaOCl added to it.  Removals of greater than 1014 org/100 ml
(99.99%) were demonstrated with residual chlorine levels
>0.5 mg/1.  No substantial results could be gleaned from the

-------
lake samples since an insufficient number were taken to account
for the many factors which influence the coliform levels in
the lake.
                           10

-------
                        SECTION IV

           DESCRIPTION, HISTORY AND DEVELOPMENT
            OF THE NEW ORLEANS DRAINAGE SYSTEM
BACKGROUND
New Orleans was founded in 1718 on the banks of the Missis-
sippi River 100 miles from its mouth.  Originally the land
area was an impenetrable swamp bounded by streams and lakes.
The city lay between the Mississippi River and Lake Pontchar-
train, both of which were subject to flooding during certain
periods of the year.  In fact, the river overflowed its
banks and flooded the small community consisting of 66 square
blocks within the first year.

TOPOGRAPHY
The topography of New Orleans is shown in a typical cross
section through the city (Fig. 2).  It can be seen that the
elevation of the city ranges from +12 ft to -8 ft msl, with
the vast majority of the land area being below +2 ft msl.
For this reason, it has been necessary to construct levees
along both the Mississippi River and Lake Pontchartrain to
Protect the city from floods.  The levees along the Missis-
sippi River have a crown elevation of +25 ft msl.  The levees
along Lake Pontchartrain are being raised to a level of +13
ft msl to protect the city from hurricane tides of +11 ft
msl.

RAINFALL
The erratic nature and quantity of rainfall is an additional
complication in providing adequate drainage for New Orleans.
Since 1893  when rainfall records were initiated, the average
annual rainfall for the city has been 57.54 in./yr.  The
mean annual rainfall average has varied from 33.5 in. in
1917 to 79.21 in, in 1929.  The average monthly rainfall
varies from 3.21 in. to 6.60 in. although monthly rainfalls
of .06 in, in April, 1915 and 24.62 in. in October, 1937
have been recorded.  The months of July and August are
usually the wettest months of the year, and October and
November the dryest.  During the period of this program. New
Orleans has experienced a relatively dry period.  It can be
seen in Table 1 that the rainfall of 60.94 in, during 1967
and 58.34 in. in 1970 were the only annual rainfalls which
                             11

-------
        CROSS SECTION OF NEW ORLEANS
FIGURE  2.
CROSS  SECTION OF  NEW ORLEANS

-------
exceeded the 78 year average during the last five years.

                          TABLE 1

           AVERAGE RAINFALL:  1967 - AUGUST, 1972

               78 YEAR AVERAGE = 57.54 in./yr

                                              % .EXCESS OF 78
YEAR                   RAINFALL (in.)          YEAR AVERAGE

1967                      60.94                  + 5.71

1968                      50.70                  -13.33

1969                      52.11                  -10.26

1970                      58.34                  + 1.50

1971                      55.57                  - 3,23

1972                      37.12 (R^0 = 40.73)      - 8.89
                                  / o

For the eight month period, January through August 1972, the
average rainfall was 8.9% below normal.

EARLY DRAINAGE SYSTEM
The development of the present drainage system began in 1893
when a group known as the Engineering Committee was organized
to develop a general plan for storm drainage of the city-
The original master drainage plan included construction of
tributary canals, pumping stations, and outfall canals to the
lakes.  The main outfall canal was located at the lowest
depression between the river and the ridges, and ran across
the city from west to east before discharging into Bayou
Bienvenue and thereby to Lake Borgne.  This outfall canal was
designed to carry dry weather flow and light rain drainage
water directly to Lake Borgne.  It would also be used as a
header for three relief outfall canals capable of discharging
water from the main canal directly to Lake Pontchartrain.
Four pumping stations were located along the main canal:
DPS #1, #2, #3, and #5.  DPS #6, and #7 were constructed along
two of the outfall canals and discharged water directly into
Lake Pontchartrain.  DPS #3 has the capability to discharge
water either into the main canal (Lake Borgne) or into the
London Avenue Canal (Lake Pontchartrain).  The route of
drainage water is dependent on the available capacity of the
main canal.  Priority was given to the main canal for drain-
age as originally this canal required less lift.  Storm water
not handled by the main canal was routed to the outfall
canals.  The main canal remains in use today as the Broad
                             13

-------
Street - Florida Avenue system.  DPS #3, #6, and #7 remain
in operation as three of the largest pumping stations in the
system with capacities of 4,100 cfs, 6,000 cfs , and 3,150^cfs
respectively.  With this plan prepared, the Louisiana legis-
lature created a Drainage Commission in New Orleans in 1896
to finance and construct the permanent drainage system.
MODERN DRAINAGE SYSTEM
Drainage Criteria


The present storm drainage system provides for removal of
rainfall at the rate of two inches for the first hour, plus
0.5 in./hr thereafter.   A storm of this intensity is normally
experienced only once each year.   The present drainage system
is designed to remove this rainfall with a runoff coefficient
of 85%.

Present Drainage System


The present drainage system for the East Bank of New Orleans ,
a map of which is shown in Figure 3, is essentially a mod-
ernized version of the drainage system originally conceived
in 1896.  The drainage system includes over 1,400 miles of
subsurface drainage, 225 miles of canals, and 16 pumping
stations which have a combined capacity in excess of 30,000
cfs (13,465,000 gpm).  The 213 miles of canals vary in
cross section with the largest being 28 ft wide by 14 ft deep,
The majority of uncovered canals  are outfall canals carrying
water from the pumping stations to Lake Pontchartrain.  These
outfall canals are up to 250 ft wide and 10 ft deep.  Of the
16 pumping stations, 13 are located on the East Bank of the
city.  These 13 pumping stations  have the capacity to pump
in excess of 18,000 cfs into five outfall canals draining
into Lake Pontchartrain.  Three of these outfall canals, the
Metairie Relief Canal,  the Orleans Avenue Canal, and the
London Avenue Canal lie west of the Industrial Canal.  Each
individual pumping station has its own set of pumps having
different capacities.  The capacities of the individual pumps
range up to 1,100 cfs and several stations have total
capacities of 6,000 cfs.  The tabulation of the pumps and
pumping capacity at the pumping stations in the project
is shown in Table 2.
                           14

-------
en
                                                                                                            LEGEND
                                                                                                           MAJOR STREETS
                                                                                                           WATER SHED BOUNDARY
                                                                                                           OPEN CANALS
                                                                                                           CLOSED CANALS
                                                                                                           (MANAGE PUMPING STA.
                                                                                                           CUBIC FEET
                                     FIGURE 3,     MAP  OF  PRESENT  DAY DRAINAGE  SYSTEM

-------
FIGURE
        DPS #3 - EXTERIOR VIEW OF
        DISCHARGE SIDE.
FIGURE 5.   DPS #3 - INTERIOR VIEW

                16

-------
                          TABLE 2
          CAPACITIES OF DRAINAGE PUMPING STATIONS
                                                   TOTAL
  STATION                 NO. PUMPS            CAPACITY (cfs)
     #3                       5                    4,100
     #4                       5                    3,900
     #7                       6                    3,150
St. Charles                   4                    1,000

The pumps at the pumping stations can move the rated flow
against a pool to pool head of 14 ft.  This head represents
the difference in water level between the suction bay at the
pumping station and the tidal elevation in the outfall canal.
The pumping stations of the original drainage plan are still
in use.  They have been updated and modernized but amazingly
still utilize some of the original pumps.  An exterior and
interior view of DPS #3, located on the London Avenue Canal,
is shown in Figures 4 and 5.  This station was originally
constructed in 1899 by the New Orleans Drainage Commission
and was subsequently remanded to the Sewerage and Water Board
in 1903.  Today, it serves as one of the major stations in
the New Orleans drainage system.  The Sewerage and Water
Board has recently placed in operation its first fully
automatic major pumping station, the St. Charles station.
This pumping station is located in the eastern part of the
city.  Pumping stations crucial to the drainage system are
continuously manned.  Other pumping stations are manned only
when rain is forecast or falling.
                           17

-------
                         SECTION V

    DESIGN AND CONSTRUCTION OF DISINFECTANT FACILITIES
GENERAL
The design and construction of the facilities for this project
required much work not anticipated in the original planning
stages.  Additionally, most of the equipment had to be designed
specifically for the application, e.g., the automatic samplers
located at the feeding facilities.  Also, the use of high
strength NaOCl required an in depth investigation of the
performance of materials under the stringent conditions of
long periods of NaOCl contact.  The construction phase
consisted of six separate programs:

     1.  Sodium hypochlorite manufacturing plant.

     2.  Chemical storage facilities at the manu-
         facturing plant.

     3.  Sodium hypochlorite transportation equipment.

     4.  Sodium hypochlorite storage and feeding facil-
         ities at the points of application.

     5.  Automatic samplers to provide refrigerated,
         discrete water samples for analytical work.

     6.  Data acquisition and residual chlorine analyzer
         installations which monitor and control disin-
         fectant feed.

The NaOCl manufacturing plant designed and constructed for
this project is of a novel design which has been patented (1).
The design has resulted in a process to continuously manu-
facture high strength sodium hypochlorite under atmospheric
conditions.  This method of manufacture is much safer than
those methods that have been available heretofore.  The
patents on this process have been licensed to the United
States government and Sewerage and Water Board of New Orleans
for use in all pollution control work.

Each of the facilities will be discussed separately.  Where
trade names of commercial products are used, their use does
not imply endorsement either by the engineer> the Sewerage
and Water Board of New Orleans or the Environmental Protec-
tion Agency.
                             18

-------
SODIUM HYPOCHLORITE PLANT
General
The decision to use high strength NaOCl as a disinfectant for
bacterially polluted storm drainage water had been made prior
to applying for federal participation.  The Sewerage and
Water Board of New Orleans had by its own volition decided to
feed disinfectant to storm water being pumped by the new
St. Charles Station for the purpose of determining its
effectiveness in reducing total and fecal coliform levels.
Under the provisions of the Federal Water Pollution Control
Act of 1965, as amended, the original plan of the Sewerage
and Water Board was extended to include DPS #3, #4, and #7
which lie on the London Avenue and Orleans Avenue Canals.

Quantity and Strength of NaOCl


With the decision to utilize NaOCl as a chemical disinfectant,
investigations were started to determine the required quantity
and strength of this material in treating the storm water
pumped to the outfall canals.  Provisions were made for feeding
up to 10 mg/1 of available chlorine to the storm water based
on a possible requirement for superchlorination dosages.  It
was decided that water pumped during tropical storms and
hurricanes would not be treated.  With this exception,
however, the capability to treat 99% of normal pumping periods
was required since swimming beaches at the lake are used
year round.  Evaluation of the available space and operating
characteristics of each pumping station involved in the
demonstration program resulted in a decision to use NaOCl
in a concentration of approximately 96 gpl.  Consumption
was determined by analyzing quantities of water pumped
during a five year base period, July 1, 1961 to June 30,  1966.
Pumping, rainfall, and coliform records for DPS #7 on the
Orleans Avenue Canal for 1963 are shown in Figure 6.  Based
on the Five Year Base Period data, a maximum of 20,000
gallons per pumping day of 96 gpl NaOCl would have been used
at each of the pumping stations in the program.  An analysis
of the wettest five day period indicated that each of the
three pumping stations originally slated to use NaOCl would
have required a total of 40,000 gallons of NaOCl.  Due to
the relatively short life of commercially available NaOCl,
the disinfectant would have to be available on a very rapid
replacement basis or disinfectant of a higher strength
would be required.  An evaluation of the NaOCl deterioration
curve indicated that if the disinfectant were supplied at a
                            19

-------
concentration of 120 gpl, it would normally be used before it
had deteriorated below 96 gpl.  The regular suppliers of
NaOCl in the New Orleans area were contacted and their
interest in furnishing disinfectant for the project was
determined.  None were interested in a short term contract
for the quantities and concentration required and the
construction of an NaOCl manufacturing plant was required.

Design of NaOCl Manufacturing Plant


The NaOCl manufacturing plant was located at the water
purification plant of the Sewerage and Water Board of New
Orleans due to the availability of personnel experienced in
handling large quantities of chlorine.  Since the water
purification plant is located in a residential and semi-
commercial area, the utmost degree of safety had to be
designed into the NaOCl manufacturing plant.  The final
design was for a continuous, automatically controlled manu-
facturing plant with a capacity to manufacture 1,000 gal./hr
of 120 gpl NaOCl with a storage of 40,000 gal. of finished
NaOCl at the manufacturing plant.  The design criteria met
the maximum demand for NaOCl and the plant was operated
as required during the periods of lower demand to keep the
feeding facilities at the pumping stations supplied with
suitable strength NaOCl.

Process Design


NaOCl is commonly manufactured by reacting sodium hydroxide,
chlorine, and water.  The reaction is exothermic and is very
sensitive to the temperature of reaction.  If the temperature
of reaction exceeds a value of 86° F to 90°F, sodium chlorate,
an inert material, which is of no value for disinfection,
is formed.  For this reason, high strength NaOCl is commonly
manufactured in a batch type operation with manual control
of the addition of chlorine.  The reaction takes place
either in concrete or rubber lined vats with cakes of ice
or refrigerant coils being used to absorb the heat of reaction.
When ice is used, it provides part of the water required
for the manufacture of the finished product.  The batch
operation is wholly dependent on the operator for the control
of chlorine addition and for the quality of the finished
product.  Due to the intermittent high level demand for the
disinfectant, the process-was designed to provide for the
manufacture of NaOCl on an automatic, continuous basis.

Investigations of the commonly available reactors for con-
tinuously manufacturing high strength NaOCl revealed that
                          20

-------
FIGURE 6.   PUMPING, RAINFALL,  g  COLIFORM RECORD - DPS #7 1963

-------
these reactors generally operated under pressure.   Due to the
location of the plant, it was felt that this would be an
undesirable feature from the standpoint of safety  and should
be avoided if possible.  Thus, it was felt that the process
design should have the following features:

    1.  It would operate at atmospheric pressure.

    2.  It would control the temperature of the
        reaction so that it would never exceed 86°F.

    3.  It would be constructed of materials resistant
        to water, sodium hydroxide, liquid and gaseous
        chlorine, and sodium hypochlorite.

The requirement that the reactor operate at atmospheric
pressure implies that the chlorine must react completely
prior to reaching a free surface.  In batch type operations,
chlorine is usually introduced into the reaction tank approxi-
mately 8 feet below the surface.  Pilot studies were
carried out and indicated that a horizontal reactor providing
an equivalent retention time would suffice.  However, an
averaging tank was placed at the end of the reactor to
provide additional mixing time.  (Fig. 7)

Liquid chlorine is used directly from tank cars, without
vaporization to gaseous chlorine, and blended with a pre-
viously diluted 14% NaOH solution.  This procedure results
in a reduction of the heat of reaction of approximately 16%.
The heat generated by chlorine when combined with  NaOH is
526 BTU per pound of liquid chlorine.  Production  of 120 gpl
NaOCl, at a rate of 1,000 gal./hr results in the generation
of 527,052 BTU which is equivalent to 44 tons of refrigeration,
Since the reaction to form 120 gpl NaOCl requires  chlorine
to be added to a 14% solution of NaOH, the possibility of
using precoo'led 14% NaOH as the heat sink was considered.
It was calculated that 14% NaOH would have to be cooled
to 14°F to provide a sufficient heat sink to absorb the heat
of reaction.  However, 14% NaOH has a crystallization
temperature of 11°F, and it was deemed that the three degree
difference between the two temperatures did not provide an
adequate safety margin.  Thus, another heat sink had to be
found.  It had been previously determined that the finished
NaOCl would be cooled to 60°F in order to improve  its life
span.  Thus, adding a sufficient amount of manufactured and
cooled NaOCl to the reacting mixture served as the second
heat sink.  Using a recirculation of 2.23 volumes  of
finished NaOCl at 60°F, it was found that the 14%  NaOH
solution would only have to be cooled to 60°F for the
combination to provide a sufficient heat sink.  This design
                             22

-------
Co
                                FIGURE 7.   AVERAGING  TANK  8  REACTOR

-------
has eliminated the requirement for either ice or refrigeration
coils to be present inside the reactor.  By utilizing reacted
NaOCl and 14% NaOH as heat sinks at a relatively high tem-
perature of 60°F, it was possible to use commercial air
conditioning chillers rather than heavy duty industrial type
refrigeration machines.  This achieved a considerable saving
in cost, both in equipment and installation.  A second
benefit of the relatively high temperatures of the heat sinks
is that it will not be necessary to operate the chillers for
approximately six months out of the year.  During the winter
months, a favorable temperature differential between the
reacted material and the potable water distribution system
will provide the needed refrigeration capacity.  Thus, during
that portion of the year when the temperature of the water
in distribution mains is below 60°f, the cost of cooling will
only be the cost of pumping and filtering water from the
distribution mains.  Utilizing water from the distribution
system, the NaOCl plant can operate with a total connected
load of 39 hp and demand load of 24 hp.  These levels are
approximately 25% of the total connected and demand load
when the refrigeration chillers are in operation.

The NaOCl plant was designed to be completely outdoors with
the exception of a small control house containing the control
cabinet, a small laboratory for quality control and a desk
for the chemist-operator.  The NaOCl plant is located on
one concrete slab 55 ft by 24 ft which contains all the
equipment of the plant with the exception of the storage
and unloading facilities.  The NaOCl manufacturing plant is
shown in Figure 8.  To provide for receipt of the 50% NaOH
and chlorine, an existing railroad siding was extended to the
NaOCl manufacturing plant.  The 50% NaOH unloading facilities
are designed to unload a 10,000 gal. tank car of 50% NaOH in
50 min.  The loading facility for the finished NaOCl has the
capacity to load a 3,000 gal. tank truck in 15 min.  These
features are necessary to provide for quick loading and
unloading during periods of high NaOCl usage.

With the entire plant outdoors, .the requirement for ventil-
ation to remove any escaping chlorine gas was eliminated.
The outdoor location is considered adequate for plants in
areas where the temperature rarely drops below freezing.
However, if a plant of this type were to be constructed in
the freezing zone, protection against freezing would have
to be provided for the pneumatic control system.

-------
NJ
Cn
   FIGURE 8.   NaOCl MANUFACTURING PLANT - This view shows the entire NaOCl manufacturing
               plant.  The C12 supply car is in place on the railroad siding.  The un-
               loading facilities can be seen adjacent to the railroad track in front
               of the Cl~ car.  The NaOH storage tanks can be seen in the background.
               The finished NaOCl storage tanks are in the lower right of the picture.

-------
Control System


The control system finally selected for this plant is shown
on the process flow sheet in Figure 9.  The control system
basically consists of locally mounted sensing devices,
electrical to pneumatic converters and pneumatically con-
trolled actuators.  The converters send signals to the
control panel which is shown in Figure 10.  From the control
panel, transmitters send pneumatic signals to the control
elements, such as valve positioners, to complete the loop.
All flow meters are magnetic.  Required information is
recorded on four inch strip chart recorders mounted on the
control panel.  To provide sufficient resolution of the
parameters during the manufacturing process, the speed of
the strip chart recorder was selected at two in. per hour.

The main problem in designing the control system was finding
equipment constructed from materials capable of withstanding
the attack of the chemicals.  As a general rule the control
components, both valves and sensing devices, are constructed
of the same material as that in which they are mounted.
However, ORP cells are constructed of epoxy or PVC with
silver and platinum electrodes.  The temperature sensing
probe in the NaOCl reactor is constructed of titanium.
Level sensing devices of the bubble type were used through-
out and utilized PVC piping for the bubble tube.

Operation


The NaOCl manufacturing plant is designed to be completely
automatic and operated by a single chemist-operator.  From
the control panel, the chemist-operator can proportion the
blending of 50% NaOH and water for reaction to the required
NaOCl concentration.  This proportion can be set from the
control panel and is maintained by a ratio controller.  In
addition to the ratio controller, oxidation reduction
potential (ORP) cells were originally used to compensate for
variation in raw materials and/or finished product.  The
ORP was determined by the strength of the finished product
and the excess alkalinity desired.

Normal practice in NaOCl manufacturing plants has been to
control the chlorine feed and the excess alkalinity by
measuring the ORP of the finished product.  In batch type
operations, an ORP sensing device is placed in the reaction
tank to continuously measure the ORP of the reacting solution.
Using this value of ORP, the plant operator varies the
chlorine feed until the desired ORP value is attained.  In
                            26

-------
CO
                      FIGURE 9.   FLOW SHEET - NaOCl MANUFACTURING PLANT

-------

  , i ;•
FIGURE  10.    CONTROL PANEL AT NaOCl MANUFACTURING PLANT

-------
continuous manufacturing plants, the ORP of the finished
product is monitored and the volume of chlorine feed is
determined from this reading.  This feedback use of ORP
makes it possible to correct for over or under chlorination
by changing the input chlorine feed.  However, it does not
indicate the presence of chlorate formation which is accom-
panied by an excessive temperature rise.  Due to this
important effect, reactor temperature was used to provide
an overriding control for the ORP parameter.  Also, rather
than using ORP information only in a feedback loop, the
possibility existed of using feedforward ORP information.
This was. accomplished by providing an ORP sensing device
in the line carrying the mixture of cooled, recirculated
NaOCl and 14% NaOH to sense the chlorine requirement of the
incoming mixture.  Thus, three systems of chlorine feed
control by ORP were available.

    1.  The ORP of the finished product.  (Feedback)

    2.  The ORP of the solution entering the reactor.
        (Feedforward)

    3.  The ORP of the solution entering the reactor
        in combination with the ORP of the finished
        product.  (Feedforward control with feedback
        monitor and override).

A fourth method of chlorine control was also provided and
is referred to as the ratio system.  The ratio system
controls the rate of chlorine addition by monitoring the
flow rate of unreacted 14% NaOH.

In all four systems, the temperature of the reacted product
is continuously monitored in the mixing tank.  If the tem-
perature in the reactor pipe exceeds a preset value of 86°FS
both the chlorine valve and the 14% NaOH valve are immediately
shut.  This allows only cooled, recirculated NaOCl to enter
the reactor and act as a heat sink until the temperature
drops to 78°F.  At this point, control will be returned to
the chlorine control system set by the operator.  A flow
sheet of the final NaOCl manufacturing design is shown in
Figure 9.

Shortly after exposure to high strength NaOCl, the ORP cell
experienced rapid failure of the resin bonding the electrical
ce'lls to the body of the assembly.  After several replacements,
it was decided to abandon the ORP cells and to rely entirely
on the ratio control system.  This has presented no problem
in the manufacture of high quality NaOCl.  The temperature
override was retained and provides adequate over chlorination
                            29

-------
 and  chlorate formation protection for the system.

 MATERIAL SELECTION

 Because of the chemical activity of NaOCl, the construction
 design was greatly affected by the process design.  Many  of
 the  features of the process and construction design were
 dictated by the availability of materials which could_withstand
 the  highly corrosive products while being reasonable in cost.
 Many materials were studied for use in the reactor, NaOCl
 piping, and NaOCl storage facilities.  Since the reactor
 was  the most critical of the three components, materials  for
 its  construction were investigated first.  The material
 finally selected would have to withstand the attack of both
 dry  and wet forms of liquid and gaseous chlorine as well  as
 NaOCl.

 The  only metals found to be resistant to the finished NaOCl
 were duriron, titanium, tantalum and platinum.  Since the
 plant was designed to be operated outdoors, it would be
 subjected to the full range of normal ambient temperatures
 in New Orleans, 14°F to 95°F.  Thus, the use of duriron was
 discarded because of its brittleness and sensitivity to
 temperature changes.  Titanium, the least expensive of the
 remaining metals, was investigated thoroughly.  However,
 tests showed that if the titanium oxide film which forms  on
 the  surface of the metal is removed and subsequently exposed
 to dry chlorine gas, the metal will flash, causing a fire.
 For  this reason, titanium was discarded as a material for the
 reactor.  Tantalum and platinum were eliminated from con-
 sideration due to their cost.

 Several plastics, both of the pure and "fibrous" glass
 varieties, were investigated.  It was found that the fibrous
 varieties were dependant on the quality of the resin binding
 the  glass for resistance to chemical attack.  It is also
 difficult to manufacture this material with reasonable
 assurance of quality.  The first pure plastic investigated
 was  polyvinlychloride (PVC) which is commonly used to contain
 and  transport NaOCl.  However, this material is very brittle
 and  has low beam strength.  Thus, PVC was not deemed a
 suitable material for the reactor-  After futher investigation,
 polyvinyllidene fluoride' (kynar) lined steel pipe was selected
 for  use^as the reactor.  The reactor is shown  in Figure  11.
 It consists of a polyvinlyidene fluoride sparger tube carrying
 the  liquid chlorine into a polyvinylidene fluoride lined  pipe
where the chlorine is discharged into the mixture of preceded
NaOCl and 14%  NaOH.  At the design rates of flow, complete
mixing should be achieved in the reactor almost immediately.
However,  to provide additional mixing and to insure against*
                           30

-------
                                                      r OUTLET
   SODIUM  HYPOCHLORITE REACTOR
FIGURE  11.
NaOCl  REACTOR

-------
any gaseous chlorine  passing through without reacting, a
perforated baffle was placed at the midpoint of the reactor
tube.   At a flow of 51 gal./min, retention time in the
reactor tube is  64 sec.   The reacted material then passes
into an averaging tank which provides a liquid head of 8 ft
to insure against any unreacted chlorine reaching the surface
and discharging  into the atmosphere.  Polyvinylidene fluoride
lined pipe was used for all NaOCl lines and 14% NaOH lines.
Ordinary steel pipe was used to carry water from the water
distribution system to the NaOCl plant.  The materials used
for construction of the major plant components are listed in
Table  3.

CONSTRUCTION OF NaOCl MANUFACTURING PLANT


The construction of the NaOCl manufacturing plant took
approximately 10 months.  From a mechanical standpoint, the
NaOCl manufacturing facility was a relatively simple plant
to construct.  Once the contractor gained experience in
making up the lined pipe joints, piping erection was speeded
up considerably.  The other phases of the construction
proceeded smoothly.

Preliminary testing of the NaOCl manufacturing plant began
on April 1, 1969 in accordance with the startup schedule.
The NaOCl plant was first operated utilizing only water
throughout the plant to check for leaks and test all pumps,
control valves,  and control functions.  During this period
all automatic controllers were placed on their set points
and tested.  This initial procedure was accomplished during
the first two weeks of April, 1969.  After the NaOCl plant
was completely tested by the utilization of water, the first
tank of 50% NaOH was ordered and received.  The startup
procedures called for utilizing only 50% NaOH in the plant
until all control functions pertaining to this material were
operating perfectly.   During this period the NaOCl plant
was operated to dilute 50% NaOH to 14% NaOH.  The 14% NaOH
passed through the reactor to a storage tank.  During this
time approximately 12,000 gal. of 14% NaOH were prepared.
When all control functions were operating properly, the
plant was shut down and thoroughly cleaned.  On May 21, 1969,
the NaOCl plant  first utilized chlorine and 14% NaOH to
prepare finished NaOCl.  Preliminary testing continued during
the summer of 1969.  During the period of the project, the
NaOCl plant has  operated satisfactorily and was able to
produce its design quality of high strength NaOCl.  NaOCl of
strengths as low as 100 gpl and as high as 150 gpl were
prepared to test the flexibility of plant design.
                           32

-------
                         TABLE 3
         NaOCl PLANT EQUIPMENT AND MATERIAL LIST
           ITEM
50% NaOH Storage Tanks

50% NaOH Pumps
50% NaOH Piping
50% NaOH Valves
H^O Pumps
H20 Piping
H20 Valves
11% NaOH Piping

14% NaOH Heat Exchangers
11% NaOH Valves
C12 Piping
Cl  Valves
NaOCl Pumps
NaOCl Piping

NaOCl Reactor

NaOCl Heat Exchanger
NaOCl Valves
NaOCl Tanks
Control Valves
    H20
    NaOH
    NaOCl

Electric Motors
Electric panels, motor
controllers, push buttons,
pilot lights, etc.
Refrigeration Equipment
  MATERIAL £ CONSTRUCTION
Welded Carbon Steel with epoxy
interior lining.
All iron, centrifugal
Seamless Carbon Steel, Sch.  10
SS ball valves
All iron, centrifugal
Seamless Carbon Steel, Sch.  10
SS ball valves
Polyvinylidene fluoride lined
carbon steel.
Plate Type - 301 S.S.
SS ball Valves
Seamless Carbon Steel, Sch.  80
SS Ball Valves
Polypropylene lined Steel, centri-
fugal
Polyvinylidene fluoride lined
carbon steel.
Polyvinylidene fluoride lined
steel, polyvinylidene - solid
PVC lined fibrous glass
Plate Type - Titanium
Teflon lined, SS ball valves
Welded Carbon Steel, rubber lined

Cast Steel, ported
Cast Steel, ported
Polyvinylidene fluoride lined
Saunders Diaphragm
Epoxy encapsulated
Standard NEMA construction in Cu.
free, cast Al housings.

Standard Air Conditioning Type
Packaged Chilled Water Systems
                           33

-------
Evaluation of NaOCl Manufacturing Plant


The NaOCl plant has demonstrated its capability to manufac-
ture a consistant product of high quality without discharging
gaseous chlorine to the atmosphere.  With the unpressurized
reactor, even over chlorination has proven to be more of an
annoyance rather than a major accident.  On July 19, 1969,
over chlorination occurred while setting the ORP control
system.  However, rather than the usual sudden release of
chlorine to the atmosphere, only a slight bubbling on the
surface of the averaging tank was noted.  Over chlorination
was not confirmed until a sample of NaOCl had been titrated.
As the temperature in the reactor increased, the temperature
override shut down the process and prevented further chlorine
from entering the reactor-  It is felt that this malfunction
justified the design of the reactor to operate at atmospheric
pressure.

Some difficulty has been observed in obtaining proper mixing
in the averaging tank located at the end of the reactor.  In
subsequent designs, this tank should be enlarged so that an
adequate head of finished material is maintained and complete
mixing in the averaging tank is achieved.

Several problems were encountered with the handling of the
finished NaOCl.  The ORP cells that measure the strength of
the chemicals failed due to the action of NaOH and NaOCl on
the epoxy lining of the cell.  Due to this failure, the plant
has been run by the chemist-operator using the ratio control
system.  There have been several failures of the lining in
the reactor averaging tank and two failures of the reactor
pipe.  These problems were traced to stresses caused by
vibrations generated in the mixing of the chemicals.  The
averaging tank was replaced with a polyethylene tank designed
by Sewerage and Water Board personnel.  The replacement tank
has performed  satisfactorily.   The kynar lined reactor
pipe was replaced free of charge by Resistoflex.

One problem that remained intractable was the continuing
failure of the polypropylene lined NaOCl pumps manufactured
by the Saran Lined Pipe Company.  With intermittent operation,
the NaOCl ramaining in the system deteriorates and crystals
form on the pump seal faces.  On subsequent operation, the
seals are damaged and NaOCl reaches unlined sections of the
pump shaft.   Rapid failure of the pump follows.  Tests were
conducted using a teflon seal in place of the carbon seal
and_operating life was increased from two to six months.
Additionally, the polypropylene lining covering the impeller
and casing of the pump has failed.  It is possible that the

-------
CO
tn
                                          TABLE  4

                           AGING  CHARACTERISTICS OF STORED NaOCl

                     PART A   Average  Daily  Decrement in NaOCl Strength [gram/I/day]

Concentration
[gram/1]
90 - 100
80 - 90
70 - 80
60 - 70
50 - 60
40 - 50
20 - 40

Storage Period
Mar 13 - Aug 2
Mar 13 - Aug 2
Apr 17 - Aug 2

Jan - Mar Apr - June July - Sept Oct - Dec Avg.
.2 .57 1.1 .56 .61
.36 .32 .84 .76 .59
.11 .33 .33 .64 .35
.3 .43 .84 .21 .44
.3 .43 .34 .41 ..37
.47 .31 .26 .35
.1 .1 -- .10
PART B Approximate Half-Life of Stored NaOCl

Initial Cone. Final Cone. Days stored Approx. Half Life
[gram/1] [gram/1]
92.9 52.5 133 149
94.3 41.1 133 130
96.5 53.2 107 120

-------
NaOCl attacks the lining along mechanical and thermal stress
lines.  Previous  experience  with polypropylene lined pumps
indicates that they can be maintained for long periods of
time during continuous  operation in low strength NaOCl
environments.  The difficulties encountered with the poly-
propylene lined pumps  are due to the highly intermittent
usage pattern and high  strength of the NaOCl.  The use of all
titanium pumps had been contemplated at the initiation of
the project,  but  the cost was prohibitive ($6,000/pump
compared to $500/pump).   At  present, it appears that flushing
of the entire system, piping and pumps, between periods
of use or replacement of the pumps as they fail are the
only solutions.

The aging characteristics of the manufactured NaOCl in the
field are given in Table 4.   Table 4, Part A gives the
average daily decrease  in strength as a function of NaOCl
concentration. These figures are based on weekly sampling
of stored NaOCl at the  pumping stations.   Table M-, Part B,
is the field  half life  (i.e.  time for the concentration to
reach one half its initial value) of the  NaOCl as stored in
the tanks and exposed to ambient conditions.   The approximate
half life was calculated by  using the average daily decrement.
The values seem comparable to NaOCl aging properties reported
in the literature (33)  when  the range of  ambient
temperatures  in New Orleans  is considered during the
storage period. (60°F - 98°F air temperature)
                             36

-------
                       SECTION VI

                TRANSPORTATION EQUIPMENT
The design of the treansportation equipment was based on the
necessity to replace NaOCl as it was utilized during the
worst five day period at each pumping station.  From a con-
sideration of the pumping characteristics of the pumping
stations and chlorine demand of the storm water, the original
requirement was one of being able to transport 40,000 gals.
of NaOCl to each of three pumping stations during a five
day period.  DPS #7, originally slated to feed 40,000 gals.
of chlorine, was Ir.ter redesigned to feed NaOCl.
            FIGURE  12.   NaOCl TRANSPORT TRUCKS
Louisiana has  a  legal  limit  of  50,000  Ibs  for any over the
road vehicle.  A study of  available trucks indicated that
approximately  3,000  gals,  of finished  NaOCl would result in
a gross  vehicle  weight approaching 50,000  Ibs.  A survey of
the routes  that  can  be taken to the pumping stations indi-
cated  that,  at most, three trips  per eight hour shift could
be made  by  one truck.   Assuming 100% availability,  a
                           37

-------
capacity to deliver 22,000 gals, per 24 hrs would be needed.
Based on the requirement for replenishment at_the feeding
facilities, one truck would have sufficed.  Since 100%
availability of automotive equipment cannot be assumed, two
rubber lined steel tank trucks were purchased.   The trucks
were standard heavy duty trucks with reinforced chassis
to carry the heavy loads.  The storage tank on each truck
if 5 ft 10 in. in diameter and 16 ft 8 in. long with a
capacity of 3,000 gals.  The tank is made of steel lined
with a three-ply, semi-hard, rubber lining.  The tank is
designed for compressed air unloading.  The air compressors
have sufficient capacity to unload a truck in approximately
30 minutes.  The tank is equipped with ladders, walkways
and a manhole and meets the requirements of the Interstate
Commerce Commission cargo tank specification #M-312 MS.  The
trucks are tandem trucks (International Harvester) utilizing
a single chassis for both power unit and the tank.  The
trucks are shown in Figure 12.  Both trucks have been used
extensively during the period of the program.   The trucks
have shown signs of external deterioration in the form of
rust and peeling paint due to the harsh environment.
However, the lining on the interior of the truck tanks is
sound and both trucks were in operation at the  end of the
project.
                          38

-------
                       SECTION VII

         SODIUM HYPOCHLORITE STORAGE FACILITIES
STORAGE TANK DESIGN
The major problem of the project was presented by the storage
and handling of 160,000 gals, of 120 gpl NaOCl both at the
NaOCl manufacturing plant and at the pumping stations.  While
there are many materials listed as being capable of containing
120 gpl NaOCl, it was discovered that very few had been used
for long term storage of NaOCl at this concentration.  In
addition, many materials were not recommended for outdoor
use.  Since NaOCl was to be stored in residential or semi-
commercial areas, the safety of adjacent properties and
residences had to be given the highest priority.  In
analyzing the linings of NaOCl storage tanks then currently
in use, it was found that previous experience had been with
low strength NaOCl solutions for extended periods of time or
high strength NaOCl solutions for short periods of time.
Also, thorough flushing of the storage facility between
periods of use was the rule.

MATERIAL SELECTION
General


Since the above conditions could not be met, the investigation
was widened to include all materials capable of withstanding
NaOCl attack.  Among the materials and types of construction
available were the following:

    1.  Rubber lined steel.

    2.  Solid plastics.

    3.  Concrete tanks with collapsible liners.

    4.  Fibrous glass reinforced polyester materials.

    5.  Polyethylene lined steel.

Each material and construction method was investigated with
respect to three main considerations:  (1) a tank construction
design which would prove resistant to the highly corrosive
NaOCl for long periods of time, (2) because of the limited
                           39

-------
 space  available at several of the pumping stations,  a
 multitude of small storage tanks could not be tolerated,
 and  (3)  it was not  desirable to have NaOCl storage  tanks
 which  would exceed the height of any surrounding residences.
 These  limitations were met by using two, 20,000 gal. hori-
 zontal,  cylindrical, steel storage tanks at each^pumping
 station  and at the NaOCl manufacturing plant.  Since tanks
 of this  size were almost unheard of for NaOCl storage, each
 of the available construction methods and materials was
 studied  to determine their adaptability to constructing
 NaOCl  storage tanks of this size.

 Rubber Lined Steel


 While, there was more experience in the use of rubber lined
 steel  tanks for storage of high strength NaOCl, it was found
 that their performance had been very erratic.  Indeed, the
 suppliers of rubber lined steel tanks readily admitted that
 the integrity of the tank was dependent on the workmanship
 used in  the application of the rubber liner to the steel.
 Tanks  storing 80 gpl NaOCl, used as bleach in pulp mills,
 indicated some tanks had useful lives of 15 to 17 years.
 Other  tanks lined with the same material, applied by the
 same personnel, lasted only six months to two years.  The
 manufacturers also admitted that the 15,000 volt spark test
 was no guarantee of a proper bond between the rubber lining
 and the  steel.   Since tanks holding 20,000 gals, of NaOCl
 must be  lined with several sheets of rubber, each containing
 several  joints, the possibility of having an incompletely
 sealed tank is  high.   However, NaOcl storage tanks lined with
 rubber had performed very capably in many cases.

 Solid Plastic
Tanks made of solid plastic such as PVC or polyester resins
were also investigated.   However, the low beam strength of
these materials made their construction in these sizes
impractical.

Lined Concrete Tanks


The use of concrete tanks with collapsible liners was also
investigated  because concrete is known to be fairly resistant
to high strengTh NaOCl.   However, the tanks were very diffi-
cult to repair if failure occurred and this type of construc-
tion was deemed unsuitable.

-------
Fibrous Glass Reinforced Polyester


Another material which had been used with some success to
store high strength NaOCl was fibrous glass reinforced poly-
ester.  Investigations again brought out the importance of
good workmanship in the proper fabrication of these tanks.
The basic method is to construct a fibrous glass tank of
sufficient thickness to provide structural integrity and
then applying a NaOCl resistant resin to the interior.
However, it was found that due to the unequal thermal
coefficient of expansion between the pure resin liner and
the fibrous glass outer shell, a crazing of the inner liner
occurred.  This resulted in rapid failure of the tank.  Since
rather wide temperature fluctuations were expected, this
method of construction was deemed unsuitable.

Polyethylene Lined Steel


The final method of construction considered was a steel tank
lined with polyethylene sheets.  This material has been used
with some success in containing high strength NaOCl as well
as other very corrosive materials.  The only drawback of
this particular method of lining appeared to be an uneven
distribution of thermal stress between the steel tank and the
polyethylene lining.  This uneven matching- of thermal coef-
ficients of expansion causes "bubbles" to appear in the
lining.  However, no difficulties are encountered as long
as the "bubble" does not destroy the continuity of the welds
at the edge of the individual sheaths of lining.

Final Selection and Evaluation


Based on this data, the final selection resulted in four
tanks lined with white natural rubber (DPS #14 and St. Charles),
four tanks lined with flexible hard rubber (DPS #3 and plant),
and two tanks lined with polyethylene (DPS #7).  The storage
tanks were in operation for approximately four years under
extreme temperature and NaOCl concentration conditions.
During this period no failures of any tanks have occurred.
Additionally, the linings of all tanks appear to be sound
as of the time of the final report.

-------
                       SECTION  VIII

              NaOCl  DISINFECTION  FACILITIES
GENERAL
Once the NaOCl  has  been manufactured  at  the  plant  and stored
at the pumping  stations,  a  system was needed to deliver the
NaOCl to the storm  water  on a  demand  basis.   The basic con-
cept of feeding NaOCl  to  bacterially  polluted storm drainage
water is the same at all  four  pumping stations involved in
the program.

However, there  are  slight differences in  the manner in which
the storm water reaches,  is disinfected, and leaves each
pumping station.  The  points of  application  at each station
and the physical differences are as follows:

     1.  DPS #3 - NaOCl is  fed to the storm  water  in the
         discharge  bay.   This  occurs  prior to a constric-
         tion in the outfall canal.   The constriction is
         used to provide  mixing  of the disinfectant and
         storm  water.

     2.  DPS #H - NaOCl is  added to the  storm water in
         the suction bay  and depends  on  the  pumps  of the
         station to provide mixing of the  disinfectant
         and storm  water.

     3.  DPS #7 - NaOCl is  added in the  suction bay
         just prior to the  pumping station.   The pumps
         at  the station provide  complete mixing of the
         disinfectant  and storm  water.

     4.  St. Charles DPS  -  NaOCl is added  to the storm
         water  through a  submerged, perforated pipe at
         the^entrance  of  a  large, concrete lined,  re-
         action basin  which has  a retention  time of
         22  to  86 minutes.   The  reaction basin is  on the
         suction side  of  the pumps and provides a  chamber
         for mixing of the  NaOCl and  storm water.

-------
DPS #3
DPS #3 is located on the London Avenue Canal 3.03 miles from
Lake Pontchartrain.  The canal is covered to the station and
open from the station to the lake.  The station is equipped
with five pumps having capacities from 550 cfs to 1,000 cfs
with a total capacity of 4,100 cfs.  Low volume pumpages
arriving at the station are pumped into the Florida Avenue
Canal - Bayou Bienvenue system while high volume pumpage is
directed to Lake Pontchartrain.

Disinfectant storage at the station consists of two, 20,000
gal. rubber lined steel tanks.  The NaOCl feeding system
employs two polypropylene lined centrifugal pumps, each
having a capacity of 160 gal./min against a 90 ft TDH.  The
installation at DPS #3 is shown in Figure 13.  The disinfec-
tant feed pumps empty into a common discharge header which is
carried underground to the outfall canal.  At the outfall
canal, the disinfectant line comes above ground and is
carried on a timber trestle across the outfall canal.  Once
the feed line reaches the trestle, it is equipped with
nozzles which discharge NaOCl into the water across the full
width of the outfall canal.  The disinfectant feed line
installation is shown in Figure 14.  At the point of dis-
charge, the London Avenue Canal-'is 160 ft side.  At a point
220 ft downstream, the canal narrows to 95 ft and remains at
this width for 17,050 ft before widening again to 130 ft.
Thus, a constriction in flow occurs which might have provided
sufficient turbulence for  complete mixing of the disinfectant
and storm water.  This assumption was not proven during the
program as channeling of the water took place rather than
turbulent mixing.  The channeling resulted in inadequate
mixing of the storm water and disinfectant.  Very high levels
of chlorine residual (Cl^R) occurred in parts of the canal,
while in other portions no residual was found.  This is in
contrast to the excellent mixing provided by the pumps at
those stations where the disinfectant is added prior to pumping.
If possible, the feed point should be moved at this and sub-
sequent installations to a point prior to pumping.  A flow
sheet of the feeding and sampling facilities at DPS #3  and
#4 is shown in Figure IS.

DPS #4


DPS #4 is located on the east side of the London Avenue
Canal at Prentiss Avenue, 1.09 mi from Lake Pontchartrain.  All
                            43

-------
FIGURE 13.   NaOCl STORAGE  AND PUMPING
            FACILITIES,  DPS  #3
 FIGURE  14.  NaOCl  SUPPLY  HEADER  AND
            DISCHARGE  NOZZLES

-------
                                                                               SODIUM HYPOCitt-OHITE FEEDING FACILITl
                                                                                  TREATMENT a SAMPIH3 FLOW
                                                                                   DIAGRAM - LOMDON AVE. CANAL
FIGURE 15.    DPS  #3  g  #4 -  FLOW  SHEET  NaOCI  FEEDING  FACILITIES

-------
 influent lines to the canal are covered.  The station is
 equipped with five pumps having capacities from 300 ere to
 1,100 cfs, with a total capacity of 3,900 cfs.^ A unique
 feature is the pumping of low volume storm drainage to
 DPS #3 and thereby into the Florida Avenue Canal - Bayou
 Bienvenue System which ultimately discharges into Lake
 Borgne, a large body of water east of New Orleans.
At DPS #4, two covered canals enter the suction bay.  ^
canal has an invert 4 ft lower than the other.  The disin-
fectant feeding facilities at DPS #4 are similar to those
at DPS #3 except that application of the NaOCl is on the
suction side of DPS #4, and thus, prior to pumping of the
storm water.  The disinfectant storage and feeding system
consists to two, 20,000 gal., rubber lined steel tanks and
two polypropylene lined centrifugal pumps.  The disinfectant
is fed to the storm water from a pipe located on the divider
wall of the two incoming feeder canals (Fig. 16).  A flow
sheet of the feeding and sampling facilities at DPS #4 is
shown in Figure 15.
             FIGURE 15.    DPS #4 NaOCl FEEDLINE

-------
DPS #7
DPS #7 is located on the Orleans Avenue Canal, 2.43 miles
from Lake Pontchartrain.  Canals on the inlet side are
covered while the outfall canal is entirely open.  The
Orleans Avenue Canal is leveed to protect the adjacent land
areas from flooding.  DPS #7 is located in City Park and is
one of the oldest stations in the system.  It was originally
constructed in 1895.  Originally, it had been intended to
feed chlorine at DPS #7 rather than NaOCl in order to pro-
vide an evaluation of the two disinfection methods.  However,
the feeding and storage of chlorine at DPS #1 was abandoned
due to safety considerations.  Once the decision had been
made, storage and feeding facilities for NaOCl similar to
those at DPS #3, #4, and St. Charles were installed.  The
NaOCl storage and feeding facility consists of two, 20,000
gal., polyethylene lined steel tanks for NaOCl storage and
two polypropylene lined disinfectant feed pumps.  A flow
sheet of the sampling and feeding facilities is shown in
Figure 17.

ST. CHARLES PUMPING STATION
The NaOCl feeding facilities at the St. Charles pumping
station are unique.  The discharge of this station is
located approximately 1,600 ft from Lake Pontchartrain.
The usual pattern of closed canals on the suction side of
the pumping station with open outfall canals on the discharge
canal has been reversed.  Since this pumping station drains
an area which is presently being developed, drainage canals
leading to it have been designed as storage facilities for
storm water runoff prior to its being pumped.  Since addi-
tional time was available to pump the storm water, the
station was built with less capacity than the pumping
stations in the older parts of town.  Thus, a relatively
long period of time is available for contact between the
point of entry of the reaction basin.  NaOCl is fed to
the storm water entering a reaction basin approximately
1,600 ft prior to pumping.  This eliminates the problem in-
volved with chlorinated water being discharged to the lake
and its possible influence on the biota in the vicinity of
the discharge.  To provide sufficient retention time for
complete reaction of NaOCl and storm water at different
rates of pumpage, it was necessary to provide a reaction
basin, measuring 1,673 ft by 98.5 ft by 11 ft, at the
station.  A reaction basin of this size provided between
                            47

-------
                                                    7
                           1LJL
                                                                      Tritcx
                       SODIUM HYPOCHLORITE  Fg£f>W$  FACIUTY
                                TREATMENT ft SAMPLING FLOW
                               DIAGRAM - ORLEANS AV£. CANAL
FIGURE 17
DPS #7 FLOW  SHEET NaOCl FEEDING  FACILITIES

-------
22 and 86 minutes retention time based on the pumping rate
of the station.  Soil conditions and the size of the
reaction basin required that it be completely lined with
concrete.  NaOCl is fed under water at the inlet of the
reaction^basin as shown on the treatment and sampling flow
sheet (Fig. 18).  For safety purposes, NaOCl storage and
feeding facilities are located at the station with NaOCl
being pumped to the point of application.  One interesting
aspect of the reaction basin design was the inclusion of
relief holes in the bottom to equalize water pressure.
The relief holes eliminated the need for support and anchor
piling which would have been necessary to prevent the
reaction basin from rising out of the ground during drought
periods.  A cross section of the reaction basin is shown in
Figure 19 along with a general plan view of the area.  A
view from the St. Charles pumping station to the point of
disinfectant feed is shown in Figure 20.

The St. Charles DPS is equipped with four, 250 cfs pumps.
The NaOCl feeding facilities are similar to those at the
other pumping stations.  Two, 20,000 gal. rubber lined
steel tanks store the NaOCl and two polypropylene lined
pumps are utilized to pump the disinfectant.  Each poly-
propylene lined pump has a capacity of HO gal./min against
a 50 ft TDK.

RESIDUAL CHLORINE ANALYZERS
Each pumping station involved in the program utilizes a
residual chlorine analyzer (total available) to indicate
C12R levels for the purpose of controlling NaOCl feed
rate.  The C1~R analyzers are amperometric analyzers
manufactured By Wallace and Tiernan.  The C12R analyzers
sample water from the outfall canal just downstream from
the point of addition of NaOCl.  The lag time to the point
of sampling by the C12R analyzer varies with the pumping
rate at the station.  Therefore, it is not feasible to
attempt correlations with respect to retention time as had
been hoped.  Contact time varied from two to 20 minutes.
The C12R is displayed on a four inch strip chart recorder
located on a control panel in the pumping station.

The C12R analyzers specifications stipulated that they
should be capable of continuous operation during the
treatment periods, which could last for days or weeks.
However, operation in this manner caused rapid failure
of the C12R analyzers and a continuous water supply from

-------
en
O

i.
^-v
1

i
/-^
f*
~x
I
I
                             ^
                                                                  SODIUM HYPOCHUORITE FEEOWO FACILITY
                                                                     TREATMENT ft  SAMPLING FLOW

                                                                       DIAGRAM   ST. CHARLES CANAL
               FIGURE  18.   ST.  CHARLES DPS  - FLOW  SHEET  NaOCl  FEEDING  FACILITIES

-------
                                                                        t.
                                                                       iLZ
                                                                                    A/ADC/
                                                                                yov £?AS/A/
«i  I
5  I
tn
                                                            "- /0O'
                                           . a'
                                                                                  s-£i./a.y
                                                                                        ST. CHARLES REACTION BASIN
                                                                                            PLAN a SECTION
                           FIGURE  IB.    CROSS  SECTION  OF  ST.  CHARLES  REACTION BASIN

-------
JLJI  "  "A*
••Sc^*-~3'   ^****^r*<«-"***\''*=-~"
                       FIGURE  20.     ST.   CHARLES  DPS  -  REACTION  BASIN

-------
the main distribution system of the city to keep the cells
moist had to be provided at all times.  This required the
use of inordinate amounts of reagent and buffer solutions.
It has been found that the solutions could be produced less
expensively by buying the basic ingredients in bulk and
producing the solutions on site.  There also was plugging
of the buffer and potassium iodine pump and filters had to
be installed on the wastewater influent lines.  On several
occasions, the feed lines for the buffer and potassium iodine
have split.  There has also been corrosion on the solenoid
activated valve which controls the city water supply and
leaking of the gasket on the constant head device which
measures cell flow.  However, when the Cl^R analyzers were
operational, good results were obtained.  At present, there
does not seem to be any equipment in the C1~R analyzer field
which can be used intermittently on wastewater without major
modification.  A picture of the Cl-R analyzers at DPS #7 is
shown in Figure 21.
     FIGURE 21.   DPS #7 - RESIDUAL CHLORINE ANALYZER
NaOCl FEED CONTROL SYSTEMS


Once the C12R is displayed at the control panel, the operator
can vary the NaOCl feed rate to regulate the dosage level
through the NaOCl feed control system.  A NaOCl feed control
                         53

-------
facility consists  of  two pumps  discharging  NaOCl through a
common header,  an  electrically  positioned control valve and
a magnetic flowmeter-   The  entire  feeding facility is
operated from the  control panel in the  pumping station.  The
control panel at St.  Charles  is shown in Figure 22.   Each
control panel is equipped with  three strip  chart recorders,
a Salve positioner and switches for the pumps.  The recorders
are four inch,  electrically operated, strip chart recorders
manufactured by Fisher and  Porter  which continuously indicate
storm water temperature, rate of NaOCl  feed and C12R.  The
control valves are teflon lined butterfly valves equipped ^
with Ramcon electric  valve  actuators.   The  actuator is posi-
tioned by a signal set by the operator  at the control panel.
The rate of disinfectant feed is adjusted manually by the
operator who attempts to maintain  a pre-determined Cl.R
level in the treated  water  in the  discharge bay of th§ station
during the period  of  pumping.

Flow of NaOCl is measured by  a  magnetic flowmeter.  The
temperature sensing system  consists of  a temperature bulb,
capiliary tube, and signal  transmitter. The Cl^R analyzer
is equipped with a signal  converter and transmitter.  The
output of each sensing instrument  is  converted to a 10 to
50 ma signal, transmitted  to  the control panel and recorded
on four inch strip chart recorders.

Little difficulty  has been  encountered  with the piping at
the storage sites.  One small pipe failure  at St. Charles
was replaced by the manufacturer free  of charge.  The
polypropylene lined NaOCl  pumps have  been  a continuing
source of difficulty.  Due  to the  intermittent nature of
disinfection, NaOCl is allowed  to  remain in the pumps for
a protracted period of time.  Thus, the problems encountered
with the NaOCl pumps  at the feeding facilities are exactly
the same as those  at  the NaOCl  manufacturing plant.

Little difficulty  has been  encountered with the Fisher £
Porter temperature units  or Beckman DO probes.  The  Fisher
and Porter four inch  strip  chart recorders on the control
panels at DPS #3,  #4, and  St. Charles were a considerable
source of difficulty  until  surge resistors were installed.

EVALUATION PHASE SAMPLING  FACILITIES
After the NaOCl had been fed to the storm water on a demand
basis, a means for evaluating the efficacy of the disinfec-
tant in reducing bacterial levels in the water had to be

-------
FIGURE 22.   ST. CHARLES DPS - NaOCl CONTROL PANEL



                        55

-------
provided.  It was not economically feasible to keep
personnel continuously on duty to take samples, and recourse
was made to automatic sampling techniques.  Initially,
automatic analyzers were investigated.  Howeyer, since the
primary purpose of the program was to investigate the effect
of the disinfectant on coliform bacteria levels, laboratory
work was required and a holding sampler was essential to the
project.  The requirements of sampling were to take a pre-
determined number of discrete samples, at fixed intervals,
and keep them refrigerated until they could be analyzed.
The water samplers had to have the capacity to take a
representative sample of the storm water in the canals,
both before and after treatment with disinfectant.  They
would also need to operate without attention during a
storm.  Many commercial automatic samplers were investi-
gated, but none could meet the requirements of the project.
The sampler designed and built for this project is shown
in Figure 23.  The samplers have the capacity to take 38
discrete samples and keep them refrigerated.

The sampler is activated by the station operator when storm
water is being treated with disinfectant.  Once activated,
the sampler operates by opening and closing solenoid valves
at pre-determined intervals.  On each opening, one sample
bottle is filled.  Storm water is taken from the canal by
a positive displacement pump.  The sampler pump operates
continuously during the sampling period.  Thus, the water
being discharged into the sample bottle is representative
of the canal water and does not represent a mixture of
dead water which has been stored in the influent line, and
fresh water from the canal.  The sample bottles are filled
to overflow with excess water going to waste.  The sampler
pump and all parts were selected so that they would be
capable of passing the 0.25 inch solids which may be
present in the storm water although sampler inlet lines
were provided with screens to remove such particles.

The first automatic sampler was constructed and placed in
operation at DPS #3 in 1968,  The prototype sampler used
copper tubing and fittings for all internal parts and
bronze solenoid valves.  After several weeks of operation,
corrosion was noticed on the valve seats and the copper
tubing had discolored.  After this experience, it was
decided to construct the automatic samplers utilizing PVC
or aluminum fittings.  Thus, a redesign of the prototype
automatic sampler was required and the second and subsequent
samplers were constructed utilizing PVC pipe and fittings.
The configuration of the sampler remained basically the
                          56

-------
en
                                                                                         AltfOMATC **TEH
                                                                                          1WTERDR ARRAMCH0T
                     FIGURE  2-3.    AUTOMATIC WATER  SAMPLER  -  INTERIOR VIEW

-------
same.

The automatic samplers are located in the pumping stations
at DPS #3, and #4 and in portable metal buildings at DPS rr
and St. Charles Station.  The metal buildings are the
knock down type, bolted construction and are skid mounted
to allow the location of sampling facilities to^be moved
(Fig. 24).  This feature became very useful during the
post-construction evaluation when the downstream samplers
had to be moved from DPS #3 and #4 to DPS #7.
  FIGURE 24.    EXTERIOR VIEW OF METAL SAMPLER BUILDING


The samplers  have worked as designed.  There has been some
difficulty in keeping prime with the sampler pumps, but
this has been traced to air leaks or siphons in the suction
lines.  The main difficulty at the sampling sites is
vandalism.  The control wires from the pumping stations to
the sampler sheds, and the suction lines from the outfall
canals to the sampler sheds have been repeatedly cut and
damaged.  The sample pump and electric controller from the
pre-treatment locations at St. Charles were stolen and
had to be replaced.  Several bullet holes have also been
found in the sampler buildings at the St. Charles Station.
                           58

-------
                           SECTION IX

                       EVALUATION PROGRAM
GENERAL


To demonstrate the feasibility of reducing the coliform density
in polluted storm water pumpage by hypochlorination, three
distinct water sampling and evaluation programs were formulated.
The three programs were:

     1.  A five year base period evaluation which analyzed
         data available from a five year period before the
         program began.

     2.  A pre-construction evaluation program, lasting
         22 months, during which the outfall canals
         were sampled and analyzed for bacterial and
         chemical pollution prior to the use of NaOCl.

     3.  A.post-construction evaluation program which
         analyzed the effects of disinfection on the
         storm water and the outfall canals.

The five year base period data extended from July 1, 1961 to
June 30, 1966.  An analysis of this data provided the pre-
liminary design criteria for the NaOCl manufacturing and
feeding facilities' and gave an indication of the magnitude
of the bacterial pollution.  The Pre-Construction Evaluation
Program, essentially a sanitary analysis, was begun March 1,
1967 and continued through December 30, 1968.

Chemical, physical and bacterial tests were run and the data
analyzed to determine the nature and magnitude of the pollution
present in the storm water, and to establish base line parameter
levels for the outfall canals.  Upon completion of the dis-
infectant feeding facilities, a post-construction evaluation
program was carried out.  This program demonstrated the
feasibility of reducing, by several orders of magnitude, the
indicator coliform density in bacterially polluted storm water
using large outfall canals in populated areas as disinfection
facilities.
                          59

-------
FIVE YEAR BASE  PERIOD  EVALUATION


GENERAL


The Five Year Base Period  Evaluation x-?as  carried out utilizing
data which had  been gathered by the Sewerage and Water Board
of New Orleans, New Orleans  Board of Health, and the Louisiana
State Board of  Health  from July 1, 1961 to June 30, 1966.  This
data was used to:

     1.  Estimate  the  level  of bacterial  pollution in the
         drainage  canals.

     2.  To determine  the  quantity and frequency of storm
         water pumpage.

     3.  Estimate  the  amount of NaOCl which would be
         required  to disinfect the water.

Sampling


Data records consisted of  water samples taken from three out-
fall canals; Orleans,  London, and Citrus, and from Lake Pont-
chartrain.  The samples from the  canals were analyzed for
total and fecal coliform densities.  Bacterial densities were
derived by the Sewerage and  Water Board using the membrane
filter technique,  while both multiple tube and membrane filter
techniques were used by the  New Orleans, and Louisiana Boards
of  Health on Lake  Pontchartrain samples.   Bacterial densities
that were valid for more than one dilution for the membrane
filter technique were averaged on the basis of total volume
sampled.  Storm water quantity and pumping rate data were
obtained from the  log books  of the pumping stations.  Quantity
was determined by  multiplying the capacity rating of the
pump by the time the pump held suction.  Rainfall data were
taken from the rain gauges at the pumping stations.

Five Year Base Period Results


Data gathered during the five year sampling program were
plotted for visual inspection.  The bacterial and physical
parameters from DPS #7 are shown  in Figure  25.  NO visual
correlations were evident.  To further analyze the data,
coliform, water pumped, and rainfall values were punched on
                            60

-------
^ -
    FIGURE  25.   DPS #7  BACTERIAL  8  PHYSICAL PARAMETERS   5  YEAR BASE
                                                                             l!
                                                                            Ill'
                                                                           fill
                                                                              i
£
?i
it
Bl
                                                                               15
                                                                               ?«
                                                                               f!
                 EVALUATION PROGRAM

-------
computer cards.   Computer programs were developed to generate
intensity-frequency data for the anticipated use of NaOCl at
the drainage pumping stations.   Design data for the planned
St. Charles station were developed from information available
from the Citrus  station, which  drains the same area.  Inten-
sity-frequency data for water pumped on a one day and a five
day basis were developed.  These data provided the basis for
estimating the quantities of NaOCl required during the project.

The rainfall pattern is essentially the same for_each station.
However, since each station has a different pumping capacity
and serves a different drainage area there are slight dif-
ferences in the water pumped data.  The Orleans Avenue and
the London Avenue canal serve combined residential and indus-
trial areas with high runoff coefficients.  The St. Charles
station serves a relatively undeveloped rural area with a
low runoff coefficient.  The factor of different drainage
areas is also brought out in the total and fecal coliform
levels in the Orleans, London,  and Citrus canals (Table 5).
The total coliform level in the Citrus canal is relatively
high, while the fecal coliform  level is approximately the
same as the London canal.  The  Orleans Avenue canal was
higher in both types of bacteria.

The high total coliform level in the Citrus canal is partly
due to the almost constant pumping situation.  If the canal
is allowed to remain fallow after a pumping sequence, there
is a tendency for the coliform levels to gradually drop as
the nutrients in the canals are used up and/or settle to the
bottom.  The low fecal coliform levels in the Citrus canal
were probably due to the undeveloped nature of the area and
th« attendant low runoff coefficient ••  Since there were few
hu;; an residents most fecal coliform pollution must have come
from the warm-blooded animal population (2),  This population
includes domesticated animals as well as an abundance of
wildlife.  In fact, this area was often frequented by hunters.

It should be noted that the Citrus station which served the
eastern portion of the city was replaced by the St. Charles
station in 1967.  Thus, the data for the Five Year Base
Period are from the Citrus canal, while the Pre and Post-
Construction Evaluation data are from the St. Charles reaction
basin.  It was felt that no substantial errors would be
introduced in the drainage water characteristics by this
change and the data from the two different stations are
considered to be characteristic of this drainage area.

The London Avenue canal has the lowest pumping frequency  and
coliform level.  This  is due to the fact that'within limitations
                           62

-------
                                      TABLE 5

                 BACTERIAL PERCENTILE LEVELS:  5 YR. BASE PERIOD

                              Total Coliform             Fecal Coliform
                          25%     50%      75%       25%    50%     75%
London Avenue Canal      2,000   10,000   65,000     300   1,000   5,000
  (DPS #3, 4)

Orleans Ave. Canal       4,000   18,000  130,000     400   1,000   7,000
  (DPS #7)

Citrus Canal             1,000    5,000  110,000     400   2,000   5,200
  (Citrus)

-------
governed by the  capacity  of the drainage system and the
location and intensity  of the  rainfall,  DPS #3 pumps into
the Florida Avenue  canal.  Water from the Florida Avenue
canal is then repumped  to Bayou Bienvenue or under extremely
light loading to the Mississippi River.   Thus,  the heavy
bacterial and chemical  loading of the outfall canal during
the initial "flushing"  of the  system does not enter the
London Avenue canal. Since there are many routes drainage
water can take,  a schematic of the possible flows^to and
from the pumping station  in the project  is shown in Figure 27.

The Orleans canal,  which  has the highest bacterial levels,
receives all storm water  reaching DPS #7.  However, this data
is influenced by the location  of the sampling point which is
closer to the pumping station  than on the London Avenue
canal.  Thus storm water, with its high  bacterial densities,
reaches the sampling point even at low pumpage rates and
before die off can occur.  Also, the higher salinity levels
in the lake don't exert the same influence here.  However, all
the canals were highly  polluted bacteriologically as 90% of
all total coliform readings were above the limit of 1,000/100
ml recommended for body contact recreation waters by the
Louisiana State Board of  Health.

Lake Pontchartrain data supplied by the  Louisiana State
Board of Health indicated that the lake  is more polluted
after pumping periods.  However, the lack of a systematic
testing program to eliminate other sources of pollution pre-
clude assigning the increased  bacterial  levels entirely to
storm water pumpage.

The intensity-frequency data developed for rainfall and water
pumped at DPS #7 (Table 6) demonstrate the quantities of water
involved.  From the data, it is evident  that some rainfall
can be expected on approximately one day out of every three,
and that one inch or greater rainfall can be expected approxi-
mately fifteen days per year.   However,  even though most
pumping  stations are equipped with an automatic rain gauge,
the operating characteristics  of the drainage system prevent
obtaining any valid correlation between quantity of rainfall
and quantity of water pumped into the outfall canals.  In
developing intensity-frequency data for  water pumped at DPS
#3, and #4, only that water pumped into  the London Avenue
canal was considered.

The data indicated that water was pumped on approximately
20% of the days which is  somewhat less than the rainfall
frequency since not every rainfall results in pumpage.  Also,
when pumpage occurred,  it exceeded 20,000,OOOcfd on"30%
of the days.  When data  from hurricane periods and other

-------
CD
cn
                                             TABLE 6
                               RAINFALL £ WATER PUMPED FREQUENCIES
                                           % of Days
                           RAINFALL
RAINFALL >1.0 in.

DPS 7
DPS 3
DPS 4
Citrus
Base
DPS 7
DPS 3
DPS 4
Citrus
DPS
Base Period
27,0
27.5
30.0
DPS 31.5
WATER PUMPED
Pre-Const
27.0
32.0
29.0
29.0
WATER
Period Pre-Const Base
45.0
14.0
11.5
87.5
39.0 6
53.0 7
9.5 3
69.5 ' 22





PUMPED
Period
.0
.5
.5
.5
Base




>5xl06cfd
Pre-Const
11.0
8.5
2.5
12.5
                                                                5.0
                                                                5.0
                                                                5.0
                                                                6.5
    id     Pre-Const
             4.0
             3.5
             4.0
             3.5

 WATER PUMPED >10xlQ6cfd
 Base Period  Pre-Const
                                                                      4.0
                                                                      3.5
                                                                      2.0

                                                                     11.5
                 6.5
                 4.5
                 1.5

                 5.0

-------
                                LAKE  PONTCHARTRAIN
en

ORLEANS AVE. CANAL >.
V /
_i
<
<
o
ui
£
O
Q
_J
\
x-
V
VHV
DPS/7 DPS^3
/
\ /
^

«. _. x* " •*%,
/' N\ c
nno Jfjt 	 1 NFW RF4? 1
DPS#4 1 INLW Kt-0. j
v y
VLV /
/ NE
< ' r n '
1 FLORIDA AVE. 1 V a
LV ^ ^ 1 CANAL TO 1 \
•> ' 1 BAYOU 1 V
j BIENVINUE J

/\
ST.
HARLES
REACTION
J__|BASIN
iW RES. \
UNDEV. 1
	 /

              OLD RES
               SEMI-
A
               \^c.mi -    .
               COMM-  /
 OLD RES. \
   a     )
DOWNTOWN J
      X
  HV= HIGH VOLUME PUMPAGES
  LV= LOW VOLUME PUMPAGES
  DPS= DISCHARGE PUMPING STATION
  RES= RESIDENTIAL
UNDEV= UNDEVELOPED
              FIGURE 26.  SCHEMATIC  DIAGRAM OF DRAINAGE SYSTEM INVOLVED IN PROJECT

-------
extraordinary rainfalls were removed from consideration, it
was found that treatment facilities for average water pump-
ages of 79,277,000 cfd or 529,990,000 gpd would be needed"
for three pumping stations originally scheduled to use
NaOCl, and 27,600,000 cfd or 204,210,000 gpd at DPS #7,
originally scheduled to use Cl .  The total quantity of
storm water requiring treatment was 106,877,000 cfd or
734,230,000 gpd.  DPS #7 was subsequently converted to NaOCl
in the interest of safety.

Five day periods were considered in planning disinfectant and
transportation requirements.  The data indicated that NaOCl
treatment facilities would be required for 277,258,000 cf
(2,193,890,000 gal.) of storm water in five days which was
slightly more than five average day pumpages.
PRE-CONSTRUCTION EVALUATION PROGRAM
General
The 22 month Pre-Construction Evaluation Program which fol-
lowed the Five Year Base Period Evaluation was basically a
sanitary water analysis program.  The objectives of this
program were:

     1.  To establish a baseline of total and fecal
         coliform levels in  storm water discharged to
         the outfall canals.

     2.  To determine the overall quality of the storm
         water discharged and the quality of the water
         in the outfall canals between pumping periods.

     3.  To determine an empirical relationship between
         coliform levels and one or more easily deter-
         minable parameters.
 Sampling Program


 The Pre-Construction Evaluation  Program  consisted of recording
 rainfall data  from  gauges  at  the pumping stations, water pump-
 age data from  the pumping  station log  books,  and taking grab
 samples from the pumping station suction bays  and outfall
 canals for bacteriological and chemical  analysis.  _The grab
 samples were taken  every Monday, Wednesday,  and Friday from
 pre-selected points on  the Orleans,  London  and Citrus canals,

                              67

-------
the suction bays  of DPS  #4,  and  #7,  and once a week,  weather
permitting, in Lake Pontchartrain.   The water samples were
all taken at a depth of  approximately 24 in.  The sampling
locations in the  canals  were approximately the same for the
pre-construction  program as  for  the  five year base period
to provide continuity-   The  sampling points are shown in
Figure 27.

The grab samples  from the stations and outfall canals were
analyzed for the  following parameters:

              Total coliform          BOD
              Fecal coliform          Suspended solids
              Enterococci             pH
              COD                     Chlorine demand
              DO                       Temperature


All samples were  analyzed in accordance with the procedures
found in Standard Methods for the Examination of Water and
Wastewater, l2th  Edition. ~      ~    "   '               ~

As in the Five Year Base Period  Evaluation, extensive data
were collected.   The weekly  sampling and pumping data combined
to give over 25,000 items of data.   In order to manipulate
such a mass of data, a computer  again had to be utilized.
The computer facilities  used during  the Five Year Base Period
Evaluation were not available during the pre-construction
program and a time-sharing computer  facility was utilized.

The initial step  taken in the analysis was to compile, tabulate
and plot the data.   The  data was plotted by sampling location
and representative curves for coliform and physical parameters
at DPS #7 are shown in Figure 28.  Three curves were required
for each sampling location to provide sufficient resolution
of the parameters.   Water pumped was plotted on each of the
curves because it is the parameter which indicates the
existence of a new set of initial conditions.

The data curves indicate the overall quality and quantity of
the water to be treated.  The parameters were statistically
analyzed to provide quantitative measures of the water quality.
Also, an effort was made to  obtain a correlation between one
or more of the parameters susceptible to continuous monitoring
and the total coliform density.  Thus, a method which would
give a quick indication  of the coliform level would be avail-
able.  Four parameters were  chosen for extensive study; total
coliform, suspended solids,  temperature, and dissolved oxygen.
Total coliform was chosen because the reduction of this para-
meter was the prime concern  of this  project.  The other three


                            68

-------
ov
to
                                                                                          & LAKE SAMPLING POINTS (100 Fl. Offthort)


                                                                                          O PUMPING STATIONS


                                                                                          A CANAL SAMPLING POINTS
                      FIGURE  27..   PRE-CONSTRUCTION  EVALUATION PROJECT  SAMPLING  POINTS

-------
FIGURE 28.   DPS #7 - PRE-CONSTRUCTION EVALUATION PROGRAM -
            BACTERIAL, RAINFALL & WATER PUMPED DATA

-------
parameters were chosen because they could all be quickly
measured and continuously monitored by automatic analyzers.
If a correlation was found, the incoming bacterial density
could then be calculated using the correlation equation.
The bacterial density desired in the effluent would then be
used to calculate the degree of reduction required.  Once
the degree of reduction was known, the dosage of NaOCl above
that required to satisfy the chlorine demand would be known.

The values for these parameters were placed on punch cards
and statistical tests were performed.  Typical frequency
histograms for the four parameters were all skewed to the
right as can be seen in Figures 29 through 32.  Dissolved
oxygen, suspended solids, and temperature distributions were
fairly continuous but did not appear to have a gaussian
distribution.  The total coliform data tended to be very dis-
crete and no conclusion could be made as to the distribution.
When total coliform readings were grouped to include only
values on days water was pumped, they were found to be nor-
mally distributed.  However, this was revealed to be more a
function of the sampling procedure than a property of the
data.  The samples that were recorded on pumping days could
have been taken before, during, or after a pumping period.
Since the coliform levels depend on the time the sample was
taken, it is not surprising that the data were normally
distributed.  No log transformation or chi square tests were
performed, but when the data were plotted on a log basis,
it did plot normally.  Since the other parameters did not
appear to display any of the standard distributions, further
statistical distribution tests were abandoned.

Several curves were drawn using the four parameters as in-
dependent and dependent variables.  At first, it seemed that
some periodic relations existed between total coliform, dis-
solved oxygen, and suspended solids when temperature was
held constant.  Upon further analysis this was not found to
be the case.

A second approach would have separated the data into various
concentration levels for each parameter.  Then using one
parameter as the dependent variable, the levels of two other
parameters are chosen as independent variables and used in
composing factorial arrangements.  These factorial arrange-
ments could then be subjected to an analysis of variance.
Those main effects and interactions between constituents
which tested as significant in the analysis of variance would
be included in a multiple, non-linear regression analysis
utilizing all the data for the significant parameters.  It
was felt that this procedure would provide either one or a
series of equations from which the necessary quantity of
                          71

-------
o
Z
Ul

o
UJ
                                                        (M   [O
2   8
                         TOTAL COLIFORM   xlO6 org/IOOml.
                                                                             HISTOGRAM

                                                                       TOWL COLIFORM-0-Z5,OOO,000

                                                                          ORLEANS AVE. CAMAL
 FIGURE  29.    ORLEANS  AVENUE CANAL (DPS #7)  PRE-CONSTRUCTION  EVALUATION

                 PROGRAM  ,- TOTAL COLIFORM HISTOGRAM

-------
                      s    8    2   8  - B

                               V
                     SUSPENDED  SOLIDS   Mg/L
a   i   §   s
                                                                         HISTOGRAM
                                                                       SUSPENDED SOUOS
                                                                      ORLEANS AVE. CANAL
FIGURE  30. ORLEANS   AVE.  CANAL  (DPS  #7t-FRE-CONSTRUCT10N EVALUATION  PROGRAM
            SUSPENDED  SOLIDS HISTOGRAM

-------
                                                                      i    s
                       DISSOLVED OXYGEN   Mg/L.
                                                                              HISTOGRAM
                                                                            DISSOLVED OXYGEN
                                                                           ORLEANS AVE, CANAL
FIGURE  31.   ORLEANS AVE.   CANAL  (DPS #  7)   PRE-CONSTRUCTION  EVALUATION  PROGRAM

              DISSOLVED  OXYGEN  HISTOGRAM

-------
   io r
                 !    I
§
   7 _
   5  —
                                                    cvj   04
                                "X"

                          TEMPERATURE
                                                                        n
                                                                        oi
  HISTOGRAM

 TEMPERATURE «C

ORLEANS AVE. CANAL
  FIGURE 32.   ORLEANS  AVE. CANAL (DPS #7)   PRE-CONSTRUCTION  EVALUATION PROGRAM


                TEMPERATURE HISTOGRAM

-------
NaOCl required to obtain specific residual chlorine levels
on the discharge side of the pumping station could be deter-
mined.
Analysis of Variance


The general, linear, analysis of variance model (co- variance
if more than one independent variable is involved) has the
form ( 3 )
where Y is the dependent variable,  x and z are independent
variables, a and g are effect coefficients of the indepen-
dent variables, and e is the experimental error.  Invariance
of the effect coefficients of the independent variables, one
of the prime assumptions of this  model cannot be met when
considering data taken during the Pre-Construction Evaluation
Program because the drainage system has time, temperature,
spatial and concentration dependencies.

Time dependency is found on Several levels and contains both
trends and stochastic series.  First, the characteristics of
the entire drainage area are changing with time.  This can
be seen in Table 7 where the total coliform and fecal coliform
levels for the five year base period are compared with data
from the Pre-Construction Evaluation Program.  This increase
of levels with time is self-evident.  Also, the means of the
various parameters vary with months as shown in Figures 33
through 36 and, thereby, display  a seasonal effect.  Third,
the length of time between pumping periods also effects the
data and, by virtue of its dependency on rainfall, is
stochastic.

The effects of the diurnal cycle, temperature, space, and
concentration are well documented in the literature.  No
attempt will be made to review this aspect of the changing
character of the drainage system.

In an effort to remove several of the time and temperature
effects, a program to structure the data by day after pumping
was written and run.  The results were then subgrouped by
level as shown in Figure 37 for DPS #7.  As expected, tem-
perature and season were related.  The phenomenon of total
and fecal coliform die off with time was also noted.  This
die off arises from their exposure to the relatively harsh
biological environment.  BOD and COD values did show a
                            76

-------
                                         TABLE  7

    BACTERIAL PERCENTAGE LEVELS:  5 YR BASE PERIOD vs PRE-CONSTRUCTION EVALUATION

                                      TOTAL COLIFORM
London Ave Canal
    (DPS #3, 4)

Orleans Ave Canal
     (DPS #7)


Citrus - St Chas.  1000
London Ave Canal
    (DPS #3, 4)

Orleans Ave Canal
     (DPS #7)


Citrus - St Chas.

25%
000
000
000


25%
300
400
400
5 YR
50%
10,000
18,000
5,000

5 YR
50%
1,000
1,000
2,000
PRE-CONSTRUCTION
75%
65,000
130,000
110,000
FECAL COLIFORM

75%
5,000
7,000
5,200
25%
16,000
105,000
19,000


25%
650
5,500
900
50%
80,000
1,050,000 6,
3,000

PRE-CONSTRUCTION
50%
4,900
75%
470,00
000,00
250, oa


75%
2i,ooa
40,000 250,000
5,000
20 ,000

-------
  E
  o
  o

  f
 (E
 o
 o
 o
 o
                                             DATf
      LEGEND

    MABCH 67 TO NOV. 68

  A STATION  3


  A STATION  4

  O STATION  7
   TOTAL  COLIFORM


ARITHMETIC MEAN VS. TIME


D.P.S. NO. 3,4,7 DISCHARGE
FIGURE  33.   PRE-CONSTRUCTION EVALUATION  PROGRAM -  TOTAL COLIFORM -

               ARITHMETIC MEAN vs  TIME  DPS  #3,  U, 7 DISCHARGE

-------
                                          D&TE
    LEGEND
  MARCH'67 TO NOV. 68
4 STATION  3
A STATION  4
O STATI ON  7
                                                                               SUSPENDED SOLIDS
                                                                            ARITHMETIC MEAN VS. TIMC
                                                                             0-R3. NO. 3,4,7 DISC HARSE
FIGURE  34.   p RE-CONSTRUCTION

                                             PROGRAM   SUS-PENBE-g-'
            ARITHMETIC MEAN vs   TIME  DPS  #3,  4, 7  DISCHARGE

-------
                                         DATE
     LEGEND
    MARCH 67 TO NOV. 66
  A STATION  S
  A STATION  4
  O STATION  7
  DISSOLVED OXYGEN
ARITHMETIC MEAN VS. TIME
D.P.S. NO 3,4,7 DISCHARGE
FIGURE 35.   PRE-CONSTRUCTION EVALUATION"PROGRAM  - DISSOLVED OXYGEN - ARITHMETIC

              MEAN vs.  TIME    DPS  #3,  4,  7    DISCHARGE

-------
CO
                                                    DATE
               LEGEND
             MARCH 67 TO
           A STATION 3
           A STA..TJON 4
           O STATION 7
NOV. 68
                                                                              TEMPERTURE C*
                                                                          ARITHMETIC MEAN VS. TIME
                                                                          P.P.S. NO. 2,4,7 DISCHARGE
FIGURE 36.
                    EVALUATION  PROGRAM
                                                                -  TEMPERATURE  -  ARITHMETIC
                      vs.  TIME  DPS  #3, 4,  7  DISCHARGE

-------
% TC FC E R
K>0
H 5°

U 50

M so
U 50




I
1

1 .
1 ill I
1
II II, 1 .1, . ll
I i 1 JLl J 1 1 L _^\ I
. . . 1 1 1 . I 1 1 III III
P 2 3 3T P I 2 3 3" P I 2 3 3* PiZ
0
H X°6
U io5-io6
M »4-io5
4
L W5 (55) >*} (1) >OO (28) >3«K>7 (5) >27 (67) >6.0 (13) >90 (II) >7.5 (32) >30 (9) >4X) 69) >K» (6)
(42) lo'-IO1 (45) IO4-I05 (12) JO-CO (108) C7-3»I07 (35) 23-27 (53) 7.6-aO (33) 30-50 (38) 5.0-75 (36) 2O-30 (17) 3.3-4.0 (25) 60-100(21)
(21) I03-!0' (24) B'-O" (18) .05-JO (16) lcf-C7 (147) 19-23 (22) 7.2-7.6 (49) O-3O (103) 2.5-5.0(56) »-20 (43) 2.0-33 (97) 30-60 (14)
(17) <»" (19) 6 (77) 
-------
reduction in time, if values were followed in days after
pumping, due to the normal satisfaction of these damands,
There were no other correlations evident.

After all groupings had been made, no analysis of variance
could be run because none of the groupings of data had a
sufficient number of readings to fill" a factorial arrangement.
This was evident during the attempt to correlate total coli-
form with dissolved oxygen, suspended solids, and temperature.
when two time factors, diurnal and seasonal,-variation*, are
included in a four level factorial design 4  or 1024 data
sets would be required if a controlled experiment is to be
r^n.  Even a simple two level factorial design would require
2  or 64 data sets.  A sorting program provided approximately
60 data sets per pumping station which included at least
three of the variables.  Unfortunately, even with these sets
there were many replications and omissions due to the random
nature of the pumping and the variables.  Thus, even a two-
level factorial arrangement cannot be carried out for the
four parameters involved.  After consideration of the data
by day and level it was decided not to run the variables as
simple factors since no correlation other than those already
noted would be found.

The lack of ordered values was caused by the stochastic nature
of the initial conditions of the parameters in the suction
bay of the pumping station.  The initial conditions are
stochastic due to the dependency on rainfall and to the
continually changing characteristics of the drainage area.
Besides causing the lack of data points in the subgroups,
this means that the system being sampled is itself in con-
stant change.  Hence, it was felt that an analysis of
variance was not indicated for finding relationships between
and among the parameters of the Pre-Construction Evaluation
Program.

Ultimately, the main obstacle encountered in all attempts of
analysis of the data was the stochastic nature of the drain-
age system.  The fact that this was not recognized when the
initial data sampling programs were formulated resulted in
the collection of a great deal of data which had limited
value and was useful only to provide base line level of
parameters for the Post-Construction Program.
Pre-Construction Evaluation Results
The object of the Pre-Constructioh Evaluation Program was to
provide a characterization of the quality of the pumped storm
                           83

-------
water, outfall canal water,  and lake water.  This was accom-
plished.  However,  attempts  to deterministically establish
relationships between total  coliform and other parameters
that could be used in controlling the application of disin-
fectant in the Post-Construction Program were not successful..

The analysis of the data was begun by compiling, tabulating,
and plotting the data.  From the plots of the data, several
immediate observations were  possible.  The coliform levels
were very high in each outfall canal with a large percentage
of the total coliform readings above 1000 org/100 ml.  Even
more polluted, bacterially,  were the suction bays at the
pumping stations.  Also, the fecal coliform readings seemed
to stay in constant proportion to the total coliform readings.
Concurrently, other parameters traditionally used in indica-
ting pollution were at very  low values.  However, the values
represent standing as well as pumped water and thus were
expected to be lower.

To give a more quantitative  measure to these observations,
computer programs to calculate intensity-frequency data,
means, and standard deviations were written and run.  The
means and standard deviations of the chemical and physical
parameters are given in Table 8.

It was found that the bacteriological pollution was great
with 99% of the total coliform readings on the suction side
of the pumping stations and  92.8% of the total coliform
readings in the outfall canals exceeding a level of 1000 org/
100 ml.  The water in the suction bays was more bacterially
polluted than in the corresponding outfall canal where
dilution by lake water takes place.  The magnitude of the
bacterial pollution is also  indicated in Table 7. (pg. 76)

The relationship between total coliform and fecal coliform
levels was of interest since the five year base period data
had demonstrated the possibility of a ten to one relation-
ship between the two parameters.  A program to calculate the
ratio of total and fecal coliform produced a mean value with
a standard deviation of 47,2.  However, after re-evaluating
the curves, a correlation was sought between the character-
istics of the^log10 transformation of the total and fecal
coliform readings.   This was successful with correlations for
each station being in the 99% or better confidence band.
These correlation coefficients are given in Table 9.  This
fact was useful in planning  the laboratory analysis since it
indicated that the fecal coliform levels were one order of
magnitude less than the total coliform levels.  Also, the
Five Year Base Period Evaluation had indicated that the nature

-------
                                                               TABLE  8

                                                     MEANS 6 STANDARD DEVIATIONS

                                                   PRE-CONSTRUCTION EVALUATION DATA

                                                          22 MONTH ANALYSIS
                                             3D
                                                        4S
                                                                        4D
                                                                                    7S
CD
Cn
WATER PUMPED - cfd
   Weight~~~
   Mean [ft: ]
   Std. Dev.

RAINFALL - in.
   Mean
   Std. Dev.

BOD - mg/1
   Mean
   Std. Dev.

COD - mg/1
    Mean
    Std. Dev.

DO - mg/1
   Mean
   Std. Dev.

Cl  DEMAND-mg/1
   Hean
   Std. Dev.
         •"IB
            lean
           Std. Dev.

         SUSPENDED SOLIDS - mg/1
              Hean
              Std. Dev.

         TEMPERATURE - °C
              Mean
              Std. Dev.
                                    82,953,592,799
                                         3,682,505
                                         7,154,522


                                             8:81
8.3
6.6
72.9
62.9
4.3
2.4
3.3
1.4
7.3
0.4
25.6
23.7
25.1
4.9
6.7
4.9
56.3
37.9
4.3
4.0
3.4
0.9
7.7
0.4
27.4
22.8
26.6
5.1
18,456,172,800
     5,377,672
     6,122,526
         0.53
         0.67
                                                                         7.9
                                                                         6.8
        81.3
        60.1
                                                                         5.4
                                                                         2.0
                                                                         3.5
                                                                         1.4
                                                                7.6
                                                                0.4
                                                               27.1
                                                               37.0
                                                               24.9
                                                                5.2
                   15.2
                   11.3
76.3
48.9
                    2.8
                    1.8
                    3.3
                    1.1
                    7.6
                    0.3
                   35.5
                   36.6
                   24.8
                    5.0
                     7D


           83,754,444,694
                5,084,161
                7,785,217
                    0.52
                    0.70
                   11.7
                    8.7
68.3
44.8
                    4.5
                    3.1
                    3.5
                    2.4
                   25.8
                   26.4
                   25.6
                    4.6
                    IPS


              87,380,336,158
                   3,111,835
                   3,579,620
                      0.50
                      0.71
                      9.6
                      6.5
80.0
44.4
                      5.2
                      2.1
                      3.6
                      1.5
                                         7.6
                                         0.3
                     51.3
                     32-.2
                     24.3
                      5.8

-------
of the bacterial pollution was different in the Citrus canal.
However, as the area changed from-a rural to a developed
region, the coliform levels increased and the ratio, total
to fecal, approximated that in older developed regions.

The visual observation of very low  levels for non-bacterial
parameters were corroborated.   As an example, the suction^
bay at DPS #7 has the highest  level of bacterial and chemical
pollution of any pumping station.  However, BOD, COD, and
suspended solids levels were all seen to be relatively low.
Only one BOD reading in 171 samples was > 50 mg/1, one COD
reading in 43 samples was > 175 mg/1, and nine suspended
solids readings in 185 samples were > 100 mg/1.  The levels
varied from station to station, but all were very low.

Several other parameters were also  studied.  pH levels varied
with 90% of the readings between 7.2 and 8.0.  Dissolved
oxygen data indicated that 93% of the readings were above
2 mg/1.  From the temperature intensity-frequency curves, it
was noted that approximately 75% of the readings were taken
when the temperature was above 25%C.
POST-CONSTRUCTION EVALUATION PROGRAM
General
Following completion of construction, a sampling program was
carried out to study the effectiveness and determine the
cost of coliform reduction by hypochlorination.  The post-
construction evaluation phase continued the weekly canal
sampling program of the pre-construction program.  Lake
samples were only taken after storms.  Additionally, numerous
water samples were taken during low and high volume pumping
operations while NaOCl was being added to the water.  These
programs were known as, Routine (canal and lake), Storm and
Storm Profile Sampling, respectively.

The methodology and sampling points to be used in these three
programs were chosen at the beginning of the project.  However^
from an analysis of the pre-construction data and the method
of operation of the pumps at the pumping stations, it became
apparent that the sampling programs originally contemplated
for the Post-Construction Evaluation Program could not be used
to accomplish the goals of the project.  In particular, the
post-treatment samplers located at DPS #3, #H, and #1 were
up to 10,000 ft from the point of discharge of treated storm
water into the outfall canals.  Thus, they were too far removed
                           86

-------
                         TABLE 9



            COLIFORM CORRELATION COEFFICIENTS
r CTCrFD]
D.F.
r*
r [TC:E]
D.F.
r*
DPS
3S
.856
161
.200
.695
79
.284
DPS
4S
.612
158
.208
.419
88
.269
DPS
4D
.742
159
.208
.625
83
.278
DPS
7S
,635
157
.208
.508
82
.280
DPS
7D
.821
142
.210
.594
76
.291
Citrus
DPS-S
.659
147
.209
.279
86
.273
Characteristic Clog10 FC] = a Characteristic [log,Q TC] + 8



Characteristic Clog10 E] = a Characteristic [log1Q TC] + 6
              r  = Correlation coefficient



              r* = Correlation coefficient required



                    for 99% confidence



            D.F. = Degrees of Freedom





               S - Suction Bay



               D - Discharge Bay
                           87

-------
from the site of treatment.   Due to transport delay, diffusion,
and dispersion,  treated water from the pumping station would
pass the downstream sampler  at an unknown time.  Also, during
low and moderate pumping rate operations, no treated water
would ever arrive at the downstream sampler at an unknown time.
Also, during low and moderate pumping rate operations, no
treated water would ever arrive at the downstream sampler
during the period of disinfection.  To alleviate this problem,
the downstream samplers from DPS #3 and #4 were moved to DPS
#7 and located so that any mode of operation at the pumping
station would cause water to be sampled at least once at a
downstream sampler location.  The result of these changes
was the location of a complete storm profile facility at
DPS #7 with a secondary site at the St. Charles pumping sta-
tion.  Only storm operation  and routine data were taken at
DPS #3 and DPS #4.

The results of the routine sampling program demonstrated that
the overall chemical and physical characteristics of the
water in the outfall canals  had not substantially changed
since the 22 month Pre-Construction Evaluation Program.  How-
ever, the long term fecal coliform levels at the pumping
stations had decreased due to the feeding of NaOCl.  The
storm profiles run at DPS #7 showed conclusively that it was
possible to reduce the total and fecal coliform densities
to extremely low levels, less than 10 org/100 ml, for short
periods of time  in the outfall canals.  However, once treat-
ment had ceased, total coliform densities quickly recovered
to those levels  present in the outfall canals prior to pump-
ing and disinfection.  Fecal coliform densities also recov-
ered but to a lesser degree.  Basic microbiological theory  ''
indicated that the subsequent regrowth of indicator coliform
is an expected phenomenon.  However, it should be noted
that the important effect of decreasing the total number of
human specific pathogens in  the water should have been pro-
vided by disinfection.  If this is the case, the human
specific pathogen levels in  the treated raw storm water
would have been  greatly reduced and it could be assumed that
the relatively harsh environmental conditions in the outfall
canals preclude  regrowth of  the pathogens to a dangerous
level.  This is  a point that requires further study even
though it appears to be the  reason for diminished fecal
coliform regrowth in aftergrowth studies and lower long term
coliform levels  in the outfall canals.  Also, it is important
to note that the significance of the indicator coliform group
levels is radically altered  once disinfection has occurred.
After disinfection their presence no longer provides the
same measure of  possible pathogenicity of the treated storm
water.
                            88

-------
Sampling Programs
Routine Sampling

Routine sampling took place in the outfall canals on Monday,
Wednesday, and Friday morning of each week. , Samplers in the
outfall canals at DPS #7 and St. Charles were operated and
took five samples.  The samples were composited and bacterial
and chemical values were derived.  Grab samples were taken
at DPS #3 and #U.  Values were found for the following
parameters :

     Total coliform              Chlorine demand
     Fecal coliform              Nitrogen (ammonia)
     DO                          Salinity
     Total suspended matter      Chemical oxygen demand
     pH

Data taken during routine sampling was analyzed and compared
with the results of the 22 month Pre-Construction Evaluation
Program.  Specific areas of interest were changes in para-
meter levels which could be attributed to disinfection as
well as changes in the characteristics of the drainage area.


Storm Sampling

Storm sampling during NaOCl feed and low pumpage rates was
carried out at DPS #3, #4 and #7 and St* Charles.  A low level
pumpage period was defined as any storm pumping which con-
sisted of a pumpage rate less than 500 cfs for a period of
thirty minutes.  The purpose of the storm sampling program
was to characterize the storm water during the initial phases
of storm water pumpage.  By characterizing the storm water
during the period of treatment, the storm profile results
from DPS #7 could be utilized at DPS #3 and #<4 in order to
treat the water in an optimum manner-  During storm operations,
samples were taken at each rate of pumping and composited
to provide samples for analysis.  Samples were analyzed for:

     Total coliform              Chlorine demand
     Fecal coliform              pH
     Salinity                    Total suspended matter
     Temperature                 Total solids
     Nitrogen (ammonia)          Volatile suspended matter
     COD                         BOD
     Enterococci
                          89

-------
Once the immediate bacterial,  chemical,  and physical para-
meters were determined,  a 100  ml sample  was stored at 20°C
to determine aftergrowth of coliform and enterococci.  Lake
samples were taken from  the shore as soon as possible after
cessation of the storm.

Data from the storm sampling program was compared with the
influent characteristics of storm profiles at DPS HI as well
as the data available from the Pre-Construction Evaluation
Program,
Storm Profile Sampling

A storm profile consisted of numerous samples taken during
the period of NaOCl feed and high volume pumpage operation.
A high volume pumpage operation was defined as greater than
500 cfs for one-half hour at the pumping station.

Sixteen storm profile samples were taken at DPS #7.  It was
also hoped that storm profiles could be taken at the St.
Charles pumping station.  However, the unmanned operation of
the station, extensive equipment failure, and vandalism at
the St. Charles station (pg58) resulted in a complete lack
of storm profile data from the St. Charles station.  One
preliminary profile had been taken in 1970, but the data
collected was not in the format of the storm profiles taken
during the Post-Construction Evaluation Program.

Four sampJers, A, B, C, and D were in operation during the
disinfection and pumping operation at DPS #7.  Samples were
taken (1) at four minute intervals at A in the suction bay
and at B in the discharge bay immediately downstream of the
station; (2) at 15 minute intervals at C, 0.25 miles down-
stream; and (3) at 30 minute intervals at Ds 1.50 miles
downstream.  The location of the sampling points is shown
in Figure 38.  As previously noted, no storm profiles were
taken at DPS #3, #4, or St. Charles.

Storm profile samples were analyzed for the following para-
meters :

     Total coliform              Nitrogen (ammonia)
     Fecal coliform              Salinity
     pH                          Total suspended matter
     Temperature

The bacterial and chemical results for A and B were derived
by compositing samples while C and D results are discreet
values.  The compositing at A and B was carried out in the
                         90

-------
(6
                                                                                       , LAKE SAMPLING POINTS (ON SHORE)




                                                                                       PUMPING STATIC'-S




                                                                                       , CANAL SAMPLING POINTS
         FIGURE 38.   POST-CONSTRUCTION EVALUATION PROGRAM -  STORM  WATER  SAMPLING POINTS

-------
following manner.   For the first 32  minutes,  samples were
composited with a maximum of two samples per  composite sample
so that the rapidly changing characteristics  of the water
during the initial stages of disinfection would not be
obscured.  Thereafter, a maximum of  seven samples were used
per composite.   The composite  value was plotted at a
mean time determined by averaging the sampling times of the
individual samples.  As an example,  samples 1 and 2 at A
would be composited and plotted at t = 6 min, samples 9
ghrough 16 would be composited and plotted at t = 45 min,
Chlorine residual and NaOCl feed rate values  were taken
from the four inch strip chart recordings on  the control panel.
Water pumpage data were taken from the pumping records at the
pumping station.  Values for total suspended  matter were derived
for initial and final samples only.

The magnitude of the amount of water treated  and representa-
tive results for the sixteen storm profiles are given in
Table 10.  As can be seen, <10m.32xl06 gallons of water
were treated with greater than 35x103 gallons of NaOCl.  The
operating characteristics of the pumping station prevented
all water from being treated on certain occasions.  Since
the top priority of the stations is  to prevent flooding,
the operation would begin pumping prior to notifying the
treatment and sampling personnel. Thus, large quantities of
water would be pumoed before treatment began.  Because of
this fact, the largest single treatment episode was not on
May 12, 1972, but July 20, when 68.19xl06 gal. of storm
water was treated with 8143 gal. of  NaOCl.  Excellent maximum
coliform removals were attained with average  chlorine
residuals of 0.19 mg/1 to 0.82 mg/1.  Average chlorine
residuals were calculated by taking  the time  average of the
chart recording.  The maximum removal rates were calculated
by using the average input coliform  reading at sampler A
and the minimum coliform value at either sampler B or C,
whichever was lower.  When samples from A were not available
due to sampler intake heads breaking, prime point B was
used as the input parameter.  Coliform removal rates improved
at the end of the project due to two factors.  One was the
apparent familiarity of operators with the response of
the system, especially with respect  to the time lags
inherent in the feedback loops.  Secondly, it was found
that a period of prechlorination prior to initiation of pumping
alleviated the original "slug" of high coliform levels (pg.114).
                            92.

-------
                                                           TABLE 10
                                       POST CONSTRUCTION STORM WATER TREATMENT EPISODES
Storm Water
Treated
Date [galxlO6]
Dec. 7, 1971
Feb. 7, 1972
Mar. 2, 1972
Mar. 9, 1972
Mar. 19, 1972
May 11, 1972
May 12, 1972
June 9, 1972
July 5, 1972
July 12, 1972
to July 13, 1972
40 July 20, 1972
Sept. 30, 1972
Oct. 22, 1972
Nov. 4, 1972
49.4
17.07
67.96
36.15
59.81
58.23
312. 651
17.29
146. 711
39.30
61.98
68.19
If. 82
76.72
15.04
NaOCl
Used [gal]
__
I'.Sl
—
—
644
1327
3919
1197
3727
2592
2681
8143
2346
6788
854
NaOCl Strength
[gram/1]
86.5
64.3
76.6
75.2
76.6
62.4
62.4
57.4
60.9
49.6
49.6
47.5
58.9
53.2
51.8
Avg. C1R
[mg/1]
__
.55
—
—
—
.23
.31
.19
.32
.27
.82
.78
.49
.42
Max. Total
Co li form Removal
Rate [%]
__
99.96
99.84
99.99
99.99
99.65
*
*
99.98
99.9
99.99
99.9998
99.9998
99.997
99.99999
Max. Fecal
Coliform Removal
Rate [t]
__
99.9
99.99
99.8
99.99
99.95
*
*
99.9
99.9
99.99
99.998
—
99.998
99.999
Total
1041.32
                               >35,699.
               *  MINIMUM VALUE NOT AVAILABLE
               1  ALL STORM WATER NOT TREATED

-------
The data taken at DPS #7 showed that it was possible to reduce
the total colifor level in the outfall canal below 1000 org/
100 ml as required by the Louisiana State Board of Health.
Decreases in fecal coliform levels were commensurate with total
coliform level changes.  However recovery of both groups of
indicator organisms occurred within 24 to 30 hours.

Post-Construction Evaluation Results

Routine Sampling

Routine samples were taken three times a week in the outfall
canals at the four pumping stations involved in the project.
Values attained were placed on punch cards and statistically
analyzed.  The chemical and physical results for the Orleans
Ave. canal (DPS #7) are shown in Table 11.  As can be seen, the
average values for the chemical and physical parameters during
the Post-Construction Evaluation Program were comparable to
those found during the Pre-Construction Evaluation Program.
Salinity and nitrogen  (ammonia) values were not taken during the
pre-construction program.  However, it can be seen that the
water is predominately fresh water although there are some
dissolved minerals present.  The average temperature in the
outfall canals for the two programs was almost the same with
no significant difference.  Nitrogen (ammonia) is seen to be
present at a very low  level.  COD levels did not vary aopreciably
between the two sampling programs, and neither have Cl^D, pH,
DO, or total suspended matter levels.  This indicates 4hat the
basic chemical and physical nature of the storm water in the
Orleans Avenue Canal (DPS #7) did not change.

The only parameters which have changed during the Post-Construction
Evaluation Program are the levels of total and fecal coliforms
(Figures 39 to 44-).  As can be seen, the level of fecal
coliform has dropped to less than that present during the
Five Year Base Period  in each outfall canal.  This is to be
expected from the treatment of the polluted storm water as
fecal coliform organisms do not regrow to the same extent as
total coliform.  Also, total coliform levels in the Orleans
Avenue Canal (DPS #7) have been lowered considerably, while
remaining the same in the London Avenue Canal (DPS #3 and #4)
and risino- slightly at St. Charles.  The decreased level in the
Orleans Avenue Canal (DPS #7) is due to the fact that all water
pumped by DPS #7 was treated with NaOCl while only a portion of
the storm water pumpage at the other stations was disinfected.
Evidently this increased level of treatment at DPS #7 and
served to lower the long term total coliform levels.  The
total coliform increase at St. Charles was probably due to the
development of the area, with the attendant higher runoff
coefficient.  The statistical chemical and physical results
of the routine sampling program for DPS #3, #4, and St. Charles
                          94

-------
CO
                                              TABLE 11



                       DPS #7 - PRE AND POST-CONSTRUCTION EVALUATION PROGRAM:



                MEANS AND STANDARD DEVIATIONS OF CHEMICAL AND PHYSICAL PARAMETERS
                    PRE-CONSTRUCTION



                Mean (A)           SD
      POST-CONSTRUCTION



Mean (A)       SD      Mean (G)
SAL
TEMP
NH3
COD
C12D
pH
DO
TSM

25.

68.
3.
7.
4.
25.

6

3
5
6
5
8

4.

44.
2.
0.
3.
26.

6

8
4
4
1
4
1853.
24.
0.
77.
3.
7.
5.
28.
1
2
6
0
5
2
7
0
2943
6
0
39
0
0
2
16
.6
.1
.8
.4
.9
.5
.3
.3
827.
21.
0.
67.
3.
7.
5.
23.
7
3
2
7
3
2
1
6

-------
to
01
    w
    >
    M
    H

    3
    2;
    W
    CJ
    «
    W
    a,
                                                        5 Yr«  Base  Period ©—
                                                        Pre-Construction
                                                        Post-Construction
                                    /o'          /o

                               Total Coliforra


FIGURE 39.  LONDON AVE.  CANAL  (DPS #3 £ 4) TOTAL COLIFORM LEVELS

            FIVE YEAR  BASE  PERIOD, PRE-CONSTRUCTION EVALUATION £

            POST-CONSTRUCTION  EVALUATION
                                                                                       /O

-------
/oo
 90
        London Avenue Canal
                     B/    /
                                                 5 Yr. Ease Period O
                                                 Pre-Construction  A
                                                 Post-Construction D
  O
           FIGURE  HO.
                                         /O           /O
                                       Fecal Coliform
LONDON AVE. CANAL (DPS #3 S U) FECAL COLIFORM LEVELS
FIVE YEAR BASE PERIOD, PRE-CONSTRUCTION EVALUATION £
POST-CONSTRUCTION EVALUATION

-------
UD
00
 /oo

 90

 80

 TO

' 6O
     O
     w
     o
     cu
       O
              Orleans Avenue Canal
                                                     5 Yr. Base Period •	
                                                     Pre-Construction  A	
                                                     Post-Construction B	
                                              /O
                                         Total Coliform
                                                     /O
/O
                                                                                      s
             FIGURE HI.
                                ORLEANS AVE. CANAL (DPS #7) TOTAL COLIFORM LEVELS
                                FIVE YEAR BASE PERIOD, PRE-CONSTRUCTION EVALUATION
                                & POST-CONSTRUCTION EVALUATION

-------
ID
(£>
                                                       5 Yr. Base Period O-
                                                       Pre-Construction  £>-
                                                       Post-Construction D-
                                                /O           /O

                                             Fecal  Coliform
                                                    /O
/O
FIGURE  42
                                  ORLEANS AVE. CANAL  (DPS  #7)  FECAL  COLIFORM LEVELS

                                  FIVE YEAR BASE PERIOD, PRE-CONSTRUCTION  EVALUATION

                                  £ POST-CONSTRUCTION EVALUATION

-------
o
o
                St. Charles Avenue
                                                        5 Yr.  Base Period  ® —
                                                        Pre-Construction
                                                        Post-Construction
                                               /O

                                           Total Coliform
JO
          FIGURE  43.   ST. CHARLES REACTION  BASIN  (ST. .CHARLES  DPS)  TOTAL COLIFORM LEVELS

                       FIVE YEAR BASE PERIOD, PRE-CONSTRUCTION  EVALUATION 8  POST-
                       CONSTRUCTION EVALUATION

-------
 /oo



  90



  60



  70
w
>
H
o


H
2;
M
O


W
eu
St. Charles Avenue
                                                  5 Yr. Rase Period O—

                                                  Pre-Construction  A-

                                                  Post-Construction D -
     /O
                                 /O


                             Fecal  Coliform
/O
  FIGURE
      ST.  CHARLES REACTION BASIN (ST. CHARLES DPS) FECAL COLIFORM LEVELS


      FIVE YEAR BASE PERIOD, PRE-CONSTRUCTION EVALUATION g POST-


      CONSTRUCTION EVALUATION

-------
o
to
                                             TABLE  12


                      DPS #3  - PRE AND POST-CONSTRUCTION EVALUATION  PROGRAM:


                MEANS AND STANDARD DEVIATIONS  OF  CHEMICAL  AND  PHYSICAL PARAMETERS
                   PRE-CONSTRUCTION


               Mean (A)           SD
      POST-CONSTRUCTION


Mean (A)       SD      Mean  (G)
SAL
TEMP
NH3
COD
C12D
pH
DO
TSM

25.1
—
72.9
3.3
7.3
4.3
25.6

4.9
—
62.9
1.4
0.4
2.4
23.7
1553.0
24.0
0.4
71.5
3.2
7.1
5.1
28V4
2550.2
6.5
0.5
35.6
0.9
0.8
2.8
20.4
636.4
23.1
0.1
64.4
3.0
6.6
3.0
22.9

-------
o
CO
                                             TABLE  13

                      DPS #4 -PRE AND POST-CONSTRUCTION EVALUATION  PROGRAM:

               MEANS AND STANDARD DEVIATIONS OF CHEMICAL AND PHYSICAL  PARAMETERS
                   PRE-CONSTRUCTION

               Mearv (A)           SD
      POST-CONSTRUCTION

Mean (A)       SD       Mean (G)
SAL
TEMP
NH3
COD
C12D
PH
DO
TSM

24.
—
81.
3.
7.
5.
27.

9

3
5
6
4
1

5.
—
60.
1.
0.
2.
37.

2

1
4
4
0
0
1596.
24.
0.
75.
3.
7.
5.
27.
3
3
3
5
2
2
6
9
2470.
5.
0.
37.
0.
0.
2.
18.
5
6
3
4
8
5
8
3
777.
23.
0.
67.
3.
7.
3.
21.
2
9
1
6
1
1
6
6

-------
o
-p
                                              TABLE 14


                   ST CHARLES - PRE AND POST-CONSTRUCTION EVALUATION PROGRAM:


                MEANS AND STANDARD DEVIATIONS OF CHEMICAL AND PHYSICAL PARAMETERS
                    PRE-CONSTRUCTION


                Mean (A)            SD
       POST-CONSTRUCTION


Mean  (A)       SD      Mean (G)
SAL
TEMP
NH3
COD
C12D
pH
DO
TSM

24.
—
80.
3.
7.
5.
51.

3

0
6
6
2
3

5.

44.
1.
0.
2.
32.

8

4
5
3
1
2
1389.
24.
2.
114.
2.
7.
3.
37.
8
6
6
3
8
2
3
8
2269.
5.
1.
36.
0.
0.
2.
21.
9
0
1
4
8
*
I
3
703.
24.
2.
107.
2.
7.
2.
32.
7
3
3
1
7
2
6
7

-------
are listed in Tables 12 through 14 and show the same properties
as the data for DPS #7.  Thus, with the exception of lower
fecal coliform levels in each outfall canal, lower total coliform
levels in the Orleans Avenue Canal (DPS #7), and slightly
higher total coliform values at St. Charles, there appear to
be no significant long term changes in the parameters due to
NaOCl addition.  However, the time base for this data is only
17 months and it is possible that long term effects might be
demonstrated after years of treatment.  Only continued treat-
ment and sampling can provide the answer-


Storm Operation

Operational data was gathered at DPS #3 and #7 during low
volume pumpage operations.  Data was available from St. Charles
and DPS #4, but the amount was not sufficient to provide
statistical parameters which would be valid.

Samples were taken in the suction bay of DPS #3 and #7 at four
minute intervals during low volume pumpage rates and composited.
Samples were then analyzed for standard sanitary parameters
Cpg 88).  The results for 11 storm sampling episodes from A
at DPS #3 are given in Table 15.
                          TABLE 15
           DPS #3 - STORM SAMPLING, BACTERIAL,
              CHEMICAL, AND PHYSICAL RESULTS

   PARAMETER      MEAN        PARAMETER        MEAN
TOTAL COLIFORM   1.2xl07         pH             7.4
   org/lOOml           r
FECAL COLIFORM   3.7x10       TSM - mg/1        228
   org/lOOml
ENTEROCOCCI      5.6xl04      VSM - mg/1         22
   org/lOOml
SAL - mg/1       739.0        TOTAL SOLIDS     2453
                                 mg/1
COD - mg/1       140.0        NH3 - mg/1         10
C10D - mg/1        2.4        TEMP - °C        24.4
   1                           BOD              16

As can be seen, there were no significant  differences in the
parameter levels between the pre and post  construction suction
bay data.  There were slightly elevated COD and TSM values,
but these are expected during the initial  "flushing" of the
drainage system.  Results for DPS #7 are comparable as can be
seen in Table 16.
                           105

-------
TOTAL
COLIFORM
org/lOOml
FECAL
COLIFORM
org/100ml
ENT,
org/lOOml
           10
10 -•
10
           10'
           10 "
           10°--
                                                         0     144
                                    Time

                    POST-CONSTRUCTION AFTER GROWTH  STUDY
                         DPS  #3           2-2-72


                  FIGURE  45.    DPS  #3  STORM AFTERGROWTH STUDY
                              106

-------
o
-o
                      FIGURE 46.  DPS #7 - ORLEANS AVE.  OUTFALL CANAL

-------
                          TABLE 16

            DPS #7 - STORM SAMPLING,  BACTERIAL,

               CHEMICAL,  AND PHYSICAL RESULTS
  PARAMETER

TOTAL COLIFORM
  org/lOOml
FECAL COLIFORM
  org/lOOml
ENTEROCOCCI
  org/lOOml
SAL - mg/1

COD - mg/1

C12D - mg/1
  MEAN

3.5x10

2.5xlO!
1.3x10

 643

  71

 2.5
PARAMETER

pH

TSM - mg/1

VSM - mg/1

TOTAL SOLIDS
   mg/1
NH3 - mg/1

TEMP - °C

BOD
                                 185
                                  .3

                                23.3

                                 18
It should be noted that the levels  of those parameters
normally indicating pollution of water are much lower than
in sewage.

After bacterial,  chemical,  and physcial tests were performed
on samples taken  during the storm operation, aftergrowth
samples were stored at 20°C in an incubator.  A typical set
of results for DPS #3  is shown in Figure 45.  The aftergrowth
data demonstrated the  characteristics of bacterial growth
available in the  literature as discussed in Section 9.
Logarithmic growth for the  total coliform values is seen
followed by the decreasing  growth phase and eventual dieoff.
Significantly, the fecal coliform densities did not increase
during the laboratory  aftergrowth study.  The enteroccoci
levels also appeared to demonstrate the classical growth and
dieoff characteristics.
Storm Profiles

Detailed records of 16 high volume pumping operations were
taken at DPS #7 (see Table 10, pg. 91).  A high volume
pumping operation was defined as storm water pumpage in excess
of 500 cfs for more than 30 minutes.  During the period of
pumping and disinfection, four water samplers vrere in operation.
Sampler A, located at the entrance of the feeder canal into
the suction bay, took samples at four minute intervals.  Sampler
B, in the  discharge bay, also took samples at four minute
intervals.  Further downstream Sampler C, 0.25 miles from the
                           108

-------
station, took samples at fifteen minute intervals while
Sampler D, 1.50 miles from the station, sampled at 30 minute
intervals.  The location of the samplers can be seen in
Figure 17 (pglOO).  The results of the storm profiles can
be explained by the physical characteristics of the drainage
system, the empirical disinfection equation, the effects of
diffusion and dispersion, and microbiological growth patterns,

NaOCl is fed to the water entering the suction bay at DPS #7
just after passing the intake for Sampler A.  The suction bay
is relatively large and can act as a storage reservoir.  This
introduces the first of several time delays, T ,.  This delay
is the effective time for treated water from Aato reach B.
Since there are several different pumps which can operate
singly or in combination, T .  can vary from approximately
five to twenty minutes.  This first delay factor is extremely
important from the standpoint of NaOCl addition since it
represents the closed loop delay time for the operator in
controlling the residual level.  A delay of this magnitude
normally causes unstable behavior in a feedback loop.

Once the disinfected water leaves the discharge bay at DPS
#7, it flows into the Orleans Avenue outfall canal (Fig. 46).
Sampler C, is located 0.25 miles downstream and the volume
of water between B, the discharge bay, and C introduces a
second delay time, T,  .  The factors influencing T,   are the
rate of storm water pumpage, tidal levels and flow in the
outfall canal, channeling of the storm water flow, and
diffusive and dispersive effects.  The channeling occurs
since the discharge bay is divided by partitions which act
as short flow nozzles.  The delay Tbc can be calculated by
comparing the corresponding peaks in the bacterial levels
at B and C after correcting for decreased coliform levels
at C due to increased NaOCl contact time.  A third delay
time, T  ,, is introduced by the volume of water between C
and D.   The delay, T  ,, is influenced by the same factors
as T,  , but tidal,     diffusion and dispersion effects are
much more important than channeling.  Additionally, if the
quantity of storm pumpage is not sufficient to displace the
water between C and D, then diffusive effects with a time
scale of days or weeks predominate.  Assuming a constant
pumping rate of 550 cfs, and neglecting the other complex^
factors, the time delays on a volumetric displacement basis
at DPS #7 are given in Table 17.
                             109

-------
                          TABLE 17

                DPS #7 :  VOLUMETRIC TIME DELAYS

                       SAMPLING POINTS

             A - B       B - C       C - D       B - D
T   T(min)   "8-20        36          180        216

The actual decrease of bacterial levels by NaOCl is governed
by the emperical relationship.  n
                        E =
Where E is the kill efficiency, t is the contact time during
which a residual is present, c  is the concentration of
available disinfectant, and n is the constant of the reaction.
It should be noted that this equation holds only after the
chlorine demands of all other reducing compounds are satisified
and a residual is present.

When NaOCl is added to the  storm water it is immediately
hydrolyzed,

                  NaOCl + K20 ? NaOH + HOC1
The HOC1 ion then equilibrates  with its dissociated  charged
ions.
                     HOC1 ^ H+  + OC1~

It is generally accepted that the neutral HOC1 particle dis-
rupts the cell to a greater extent than the OC1" ion.  The
HOC1 molecule is thought to interfere with cell respiration
by reacting with enzymes and this destroys the cell.  The
dissociation constant for HOC1  is dependent on temperature,
pH and levels of nitrogenous reducing compounds.  Elevated
temperatures shift the equilibrium to the right as do
alkaline pK levels.  Nitrogenous compounds convert KOC1 to
chloramines which are much less effective as disinfectants.
This effect is also dependent on pH with the maximum conver-
sion occurring at pH = 8.4.

The results of a storm profile  taken at DPS #7 on November 13,
1972 are given in Figures 47 to 49.  This storm profile was
selected because most of the various facets of a treatment
episode are demonstrated.  The  remaining storm profiles are
included in the Appendix.

The most difficult aspect of the disinfection operation is
the maintenance of a pre-determined residual level.  The
fluctuations in the C12R curve are typical (Figure 47),


                            110
The

-------
          3000
 H20

PUMP

RATE
cfs
mg/1
NAOCL

FEED
gpm
2000..






1000-




   o


 2.0



 1.6--



 1.2--



  .8"



  .4--


   0


  60
  50--


  40..


  30-.
     ifdii

  20--


  10"


   o L
               0
            50
100
                                              200
250
                                "Time (Win.)

                   Sampler A  •                  Sampler C

                   Sampler B  O                  Sampler D

                          PHYSICAL PARAMETERS  DPS #7

                          STORM PROFILE      11-13-72
300
                                                  A


                                                  D
      Figure  47.   DPS #7 - STORM PROFILE PHYSICAL RESULTS

                   NOV.  13, 1972
                                111

-------



SAL,
mg/l
C.O.D,
mg/l
CL2D
mg/l
pH

10000
8000-

6000-
HQOO-
2000 -
0
300
200"
100 •
0
4.0-
3.0-
2.0.
1.0.
0
9.0
8.0 -
7.0.
6,0
I" \
9 \
"I \
. \
. * \
i \
•1 \
f 1 \
[1 \
r ^ \
0 ^
T \
k \


---_


;<^^-« .



/v- ' "^^~*"-"~ZLyv— -f^~~&~~ ~Q A n n T
- rf* -''"^ " ^"^ 	 A—
& °^





'

]

50 ' 100 ' 150 '200 ' 250 ' 300



Time (Min.)
Sampler A ® Sampler C A
Sampler B O Sampler D D
                       CHEMICAL PARAMETERS  DPS #7
                       STORM PROFILE      11-13-72
FIGURE 48.    STORM PROFILE  CHEMICAL  RESULTS NOV.  13,  1972

                            112

-------
J.U
10 7-

t io6-
O
O
r-H
CO i A5.
E 10
CO
•H
c
§> 104'
o
10 3-




5.
10

io4-
i
l~l
s
o „
o , A3
H 10 -
\
CO
s
w
•H 9
C 10 -
fO
bO

O
101-

^ ^ * 	 v 	 — — — —
9
"1 —
i ^^CK
'( ^
i\ x
\ N
1 \i---A \
1 V ^
i \ N
•* \
\ >
\ V
(S &-•-£» — ^ — ^ — " 	 ^
\
\
\
\
\J U
9^^^^.
i
i
i
i
L A
9 ^^^n/ ^
i \
\
V
1 X.
^ "\
x N.
>^ — A— A »•
\
\
\
\
- 6--O— O- 	 £©--A-^!sr-£ 	 £k
	 1 	 1 	 1 	 1 	 1 	 1 	 1 	 1 	 1 	 1 	 ! 	



TOTAL
COLIFORM


]



Sampler A •
Sampler B O
o-i_*t^n _ „. /*i A
bampler o tj
Sampler D O







FECAL

COLIFORM
i
j






              50  100  150  200  250  300
                   Time  (Min.)

              BACTERIAL RESULTS   DPS#7
              STORM  PROFILE     11-13-72
FIGURE 49.  DPS #7 STORM PROFILE BACTERIAL RESULTS NOV.  13, 1972

                           113

-------
attempts of the operator to maintain the residual between
0.5 and 2.0 mg/1 are evident.   The initial NaOCl feed rate
was 22 - 25 gpm.  This feed rate is usually sufficient to
maintain this residual level with storm water pumping at
550 cfs if the chlorine demand approximates 3.5 mg/1.  How-
ever, the initial feed rate required depends on the instan-
taneous strength of the NaOCl stored at the station.  During
this storm the initial NaOCl feed rate was not adequate,
but since there is approximately a 20 min transport delay,
T b = 20 min, the operator is  not aware of this initially.
The doubling of the^NaOCl feed rate to 44 gpm at the 20 min
mark was due to an increase in the pumping rate.  Finally
at t = 24 min, the operator has the first indication that
he is not in the desired residual range.  The operator then
increases the NaOCl feed rate to 53 gpm and maintains it
until t = 60 min.  At this time the residual rises above
the 2.0 mg/1 range of the chart.  The NaOCl feed rate is
then decreased to 22 gpm.  It  can be noted that the residual
does not begin to drop until t = 80 min._  The man-residual
feedback loop is obviously very unstable.  The operator main-
tains the NaOCl feed rate at 22 gpm but the pumpage rate is
decreased to 550 cfs at t = 95 min.  The residual again
rises and the operator decreases the feed rate 18 gpm which
is maintained until the cessation of disinfection.  The
fluctuation of chlorine residual due to changes in demand
during the latter stages, and pumpage rate throughout the
storm profile is clearly seen.  From Figure 48 it can be seen
that the chlorine demand is higher initially and thus requires
a greater NaOCl feed level to  effect a residual.  At t = 75
min the demand drops and the composite average remains constant
at 1.9 mg/1.  Compositing of the samples obscures the minor
fluctuations in the demand seen at the end of the treatment
period.

The bacterial results of the treatment are plotted in Figure
49.  As expected, influent coliform levels at A are very
high with total coliforms exceeding 107 org/lOOml while
fecal coliforms exceed 105 org/lOOml.  At B, the initial
levels are comparable.  A note of explanation is usefull here.
The initial coliform levels at B, C, D in the outfall canals
should be nearly equal and approximately two orders of
magnitude lower then the suction bay levels.  However, the
location of B, in the discharge bay, causes the initial B
samples to approximate the conditions in the suction bay
almost immediately when pumping starts.  In fact, due to
stirring up of the benthos, initial conditions at B are
sometimes worse than at A6  Occasionally, the samplers are
turned on prior to initiation of pumping and then the B, C,
and L values are comparable (App3-2).  Once treated water
                            114

-------
reaches B, we see a rapid decline in the coliform levels to
less than 10^ org/lOOml.  The uncertainty  arises since the
plate counts were zero for this and higher dilutions.  Moving
to C, we see that the initial total coliform value is "105
org/100 ml which holds until t = 45 min.  The values then drop
to 104 org/lOOml as the first treated water reaches C.  A second
drop to 
-------
      300-
  6   200f
  21
  u>
  H-
      10 0--
             Initial




             Sampler A ®


             Sampler B O
Time
Final




 Sampler C A


 Sampler D D
FIGURE 50.   DPS #7 - POST-CONSTRUCTION EVALUATION  PROGRAM

            AVERAGE TOTAL SUSPENDED MATTER  INITIAL 8 FINAL

            SAMPLES
                        116

-------
                                                       TABLE  18
                         DPS #7 - MAXIMUM COLIFORM  REDUCTION FOR SIXTEEN STORM PROFILES
Date
12/7/71
2/7/72
3/2/72
3/9/72
3/19/72
5/11/72
5/12/72
6/9/72
7/5/72
7/12/72
7/13/72
7/20/72
9/30/72
10/22/72
11/4/72
11/13/72
C1R - B min.
mg/1
ft*
ft*
ft*
ft*
ft*
.35
.52
.22
.45
.56
.28
1.4-0
1.26
.45
.35
2.00
A
IO7
IO7
IO7
IO7
IO7
IO6
__
IO7
io6
IO7
io6
IO7
IO7
IO7
IO7
io7
TC Values
B min.
IO5
io4
IO5
IO4
IO4
io4
10 3
io5
IO3
IO3
IO3
IO2
IO3
IO3
IO2
IO1
C min.
__
3
5
IO4
IO3
IO3
IO3
io4
IO3
io3
IO3
2
IO2
IO3
IO3
io2
Mag.
B/A
2
IO3
IO2
IO3
IO3
IO2
__
IO2
IO3
IO4
IO3
IO5
io4
IO4
IO5
io6
Red
C/A
__
io4
io2
io3
io4
io3
__
io3
IO3
io4
io3
IO5
IO5
io4
If
io5
                                                                              C/B
                                                                              10J
                                                                              10J
                                                                              10J
                                                                              10J
                                                                              10J
                                                                                     10
10
                                                                                     10
                                                                                       L
                                                                                     10
10'
10
10'
                                                                                     10C
                                                                                     10"
                                                                                     10
                                                                                     10'
                                                                                     10'
                                                                                     105
                                                                                     10'
     FC Values
       B min.
        102
        10'
                                                                                             10J
        10'
        10'
        10'
                                                                                             10
                                                                                             101
        10J
        10J
                                                                                             10J
C min.
 10J
                  10J
                  10'
 10J
 10J
                                                                                                       10J
 10'
                  10
                  101
 10J
 10J
 10'
                  10J
                                                                                                                Mag.  Red. - PC
 B//
 10'
                                                                                                                     C/A  C/B
 10"   10'
10'  10'
IO2  IO2
IO3  IO4
          10J
           10J
102   103   101
102   103   101
10S   105   —
103   103   -
103   103   —
104   104   -
io4  io4
104  IO3
IO4  IO4
**  Not Available

-------
result in higher levels of coliform reduction.  The effect of
the increased contact time is also seen occasionally.  The
occurrence is not uniform since little effect will be demon-
strated at high dosage levels.   At the lower residual levels
mixing with untreated water may occur between B and C when
channeling is present and result in higher bacterial levels
at C.  However, the effect of contact time can be used to
advantage by treating the water at lower residual levels,
i.e., 0.5 mg/1.

The chlorine residual analyzers utilized during this project
measured total available chlorine.  Thus, free and combined
chlorine could not be separated.  However, increased levels
of kill were found with increased residuals.  From a considera-
tion of the strom profiles, chlorine residua.ls greater than
0.5 mg/1 resulted in 99.99% or  greater reduction of bacterial
densities.  The effects of contact time could be seen when
bacterial levels at C were consistently lower than comparable
levels at B.  Unfortunately,  it was not possible to ascertain
statistically the relative importance of each factor in the
treatment process due to a lack of point A samples.  The
sampler inlet at A (Figure 51)  was located at the entrance
of the feeder canal into the  suction bav.
         Figure  51 - Point A -  Sampler  Inlet  at  DPS  #7
 No  problems were encountered at  low  flow  rates, but during
 high  flow  rates the sample head  would  tilt breaking primeJ
                           118

-------
on the sample pump and no further samples could be taken.
During one very high flow rate the sampler head was dislodged
entirely.  An attempt was made to move the sampler inlet to
a protected area to the side of the feeder canal, but this
was unsatisfactory since the samples taken no longer repre-
sented the influent conditions.  A complete redesign of this
sampler inlet would be required if further studies are to be
performed.  However, on the basis of storms where A values
were available, it could be seen that only a slight decline
in initial coliform levels occurred (App. 1-3).

The main objective of the project was to decrease the total
and fecal coliform levels in the storm water which subsequently
reached Lake Pontchartrain by means of the outfall canals.
By analyzing the results of individual storm profiles, this
goal appeared to be well in hand.  Except for a pre-residual
period at the initiation of pumping, coliform levels for most
of the storm water pumped were decreased by four or more
orders of magnitude (>99.99%) to levels below 1000 org/lOOml.
However, when storm profiles were taken on May 11 and 12,
1972 and July 12 and 13, 1972 (App. 6, 7, 10 & 11) it was
noticed that total and fecal coliform levels which had been
reduced to 103 org/lOOml and 101 org/lOOml, respectively,
had recovered to levels normally present in the canals
(106 org/lOOml, 105 org/lOOml).  At first it was thought that
the levels at B and C were being increased by lake water
entering the outfall canals.  However, salinity levels at
B and C on the second day had not recovered to their normal
levels and were at the same level as when pumping had ceased
on the previous day.  This is shown by comparing App. 6-2 and
7-2 where salinity" levels for May 11, 1972 and May 12, 1972
are plotted.

On May 11, 1972, the normal increase in salinity levels as
one proceeds downstream toward the lake is present.  Once
pumping begins, the salinity levels drop as the treated, low
salinity water from A reaches B and C.  As can be seen, no
treated water reaches D.  On May 12, the original salinity
levels at B, C, and D are all very low.  Evidently, the
treated water diffused to D in the twenty-four hour period
between pumping episodes.  Thus, the coliforms appeared to
regrow rather than being imported from the lake by tidal
action.

To explore this behavior further, an aftergrowth study was
initiated at C.  So that the course of bacterial regrowth in
the natural environment of the outfall canal could be deter-
mined, sampler C was utilized to take samples at two hour
intervals for thirty hours after cessation of pumping^and
disinfection.  The samples were then analyzed and coliform, pH,
                             119

-------
TOTAL
COLIFQRM
org/100ml
            10 -•
FECAL
COLIFORM
org/lOOml
io -•
103-

io:

10
                                   o—o-	ex'
o	or
SAL,
mg/l
pH
                  POST CONSTRUCTION AFTER  GROWTH  STUDY DPS #7
                           SAMPLING POINT  C   10-22-72
     FIGURE  52.  DPS  #7  - POST-CONSTRUCTION EVALUATION  PROGRAM
                 STORM PROFILE AFTERGROWTH STUDY
                                 120

-------
and salinity levels were determined.  The results are shown in
Figure 52.  The original dip in the curve is probably due to
dieoff of organisms which began after contact with NaOCl.  This
effect ceases after six hours and there is a uniform, possibly
logarithmic, regrowth of total and fecal coliform organisms.
It is believed that the reading at T = 12 hr is an analytical
error since no concurrent increase in fecal coliform is noted.
Total coliforms increased to 10^ org/lOOml which approximates
the normal level in the Orleans Avenue canal.  Significantly,
the fecal coliforms only recovered to 10^ org/lOOml,  This
level is approximately two orders of magnitude less than was
ordinarily present in the Orleans Avenue canal.  This could
explain the long term decrease in the fecal coliform levels
observed in the routine data.

Although additional aftergrowth studies with better controls
would have to be carried out to substantiate these observa-
tions, the regrowth phenomenon is a well known microbiological
event.  In order to clarify the implications of coliform
regrowth with respect to the goals of the projects the micro-
biological aspects of disinfecting bacterially polluted storm
water had to be considered.
                         ,121

-------
                         SECTION X

   MICROBIOLOGICAL ASPECTS  OF STORM WATER AND DISINFECTION
GROWTH


In order to explain certain observations made during the Pre-
Construction and Post-Construction Evaluation Programs, it is
necessary to refer to the microbiological aspects of disin-
fection of storm water (7, 8).   If storm water is disinfected
through use of NaOCl (or any disinfectant) the number of
coliforms, pathogens, etc, in the storm water is reduced to a
very low level.  If this small  number of microorganisms is
considered analogous to a mass  of organisms in a bacteri-
ological culture medium, the growth curve9 under favorable
conditions, would look like Figure 53.         ~~ ~~~~~~~~"~~

The growth of the microorganisms has several phases.  Loga-
rithmic growth starts a short time after the residual chlorine
level falls to zero and the remaining microorganisms come
into contact with the nutrients in the storm water.  In the
logarithmic growth phase there  is always an excess of food
around the microorganisms«  The rate of metabolism and growth
is limited, in this case, only  by their ability to process
the nutrients in the polluted storm water.  At the end of the
logarithmic phase the microorganisms are growing at the
maximum rate.  At the same time they are removing organic
matter from the water at their  maximum rate-  Needless to say
the limitations of food causes  the rate of growth to decrease
in the declining growth phase.   As the microorganisms lower
the nutrient concentration, the rate of growth decreases.
When growth ceases, the nutrient concentration for the species
is at a minimum and the organic matter still in the waste
water is in equilibrium with the number of microorganisms.
For coliform bacteria the time  base for the log growth and
the^declining growth phases is  approximately 24 hours.  Fol-
lowing the declining growth phase, the number of micro-
organisms remains constant during the stationary phase.  Once
the nutrient levels are  lowered below the critical level die
off begins.

The growth pattern of microbial organisms can explain several
observations of the Pre and Post-Construction Evaluation Pro-
grams.  During the pre-construction program, a gradual die
off of bacteria in the outfall canals was noted with time
after pumping.  It can be seen that the bacteria originally
                          122

-------
CO
       0)
       -P
       O
       M-i
       O

       tfl
       fc
       0)
       M
       O
                                                        D
                                                             A.   Lag Phase
                                                             B.   Accelerated - growth phase
                                                             C.   Exponential phase
                                                             D.   Stationary phase
                                                             E.   Decline phase
                                              Time (Hour)

                                       BACTERIAL GROWTH CURVE
                                  FIGU; r. -S3.   BACTERIAL GROWTH CURVE

-------
present in the water rapidly enter the stationary and die
off phase of growth with its gradual decrease in the number
of microorganisms.   This accounts for the decrease in bac-
terial levels noted during the Pre-Construction Evaluation
Program,   In the Post-Construction Evaluation Program, dis-
infection with NaOCl decreased the total number of organisms
in the water to very low levels while having only a negli-
gible effect, from the microbial view, on the amount of
organic material present as nutrient substrate.  Thus, the
coliform bacteria surviving disinfection are in the logarithmic
growth phase and the declining growth phase for the first 24
to 30 hours.  This  results in a rapid recovery of the bacterial
population to that  level normally found in the outfall canal.
This rapid recovery, once the residual chlorine level has
dropped to zero3 casts serious doubt on the ability of the
project to attain its goal of reducing the coliform bacteria
count in the water discharged into the surrounding recre-
ational areas.  It  was apparent that unless a residual
chlorine level is kept in the water in the outfall canal at
all times, a. rapid recovery of indicator bacteria takes place.
Since there are over 1U,000,000 cu ft of water and associated
benthos in most of the outfall canals, it is not economically
possible or ecologically desirable to keep a chlorine residual
in the outfall canal at all times.  This led to a  reevaluation
of the goals of the project.

Origin of Pathogens


The primary reason  for treating water is to remove human spe-
cific pathogens from it.  Thus, disease will not be caused
in humans when polluted water subsequently comes into contact
either with the skin or enteric system.  Human specific
pathogens are normally transmitted to water by pollution of
fecal origin.  The  access of fecal pollution to water may
add a variety of intestinal pathogens.  The most common
pathogens include strains of Salmonella, Shigella, Leptospira,
enteropathogenic Eseherichia aoli , Pasteurella, Vibrio,
Myccbacterium., human enteric viruses, cysts of Endamoeb a
histolytica, and hookworm larvae.

These pathogens may be found in sewage, streams, irrigation
waters, wells, and tidal waters.  However, the isolation of
pathogens from the  water environment has been infrequently
performed because laboratory methods of isolation and iden-
tification remain too cumbersome for routine use.  For this
reason, the presence of total and fecal coliform has been
used as an indication that other pathogenic organisms may
be_ present.  The rational behind this method is that total
and fecal coliforms are present in the alimentary tract of
                           124

-------
humans, as are pathogens when the host is infected.

Originally indicator bacterial tests included the coliform
group as a whole.  However, Eiijkman (9) introduced a modifi-
cation which distinguished between soil based coliform and
enteric coliforms.  In this modification, those coliform
which are found in the alimentary tract of warm blooded
animals and capable of growth at the normally inhabiting tem-
perature of 44.5°C are operationally defined as fecal coli-
forms.  Since both soil based and enteric coliforms could
multiply at 37°C this combination was designated as the total
coliform group.  The monitoring of sewage for pathogens using
total and fecal coliform indicators has been demonstrated to
be an excellent epidemiological tool for monitoring water
borne diseases that may be prevalent in the community at
the moment.  However, it must be remembered that this observation
has its greatest utility when the fecal material is_ known
tp_ be of human origin.

While the microbial discharge of warm blooded animals is
usually not harmful to humans, pathogens may be found in the
intestinal tract of warm blooded animals..  The~s~e sources
include animal pets (10), livestock (1J), poultry (12),, and
the wild animal community (13).  The animals come into contact
with human specific pathogens through contaminated food and
water sources (14-) and may themselves come infected or serve
as carriers.  Among the cold blooded animals, fresh water
fish and turtles may harbor human pathogens after exposure to
contaminated water or food sources and carry these organisms
to recreational areas (15),  This occurrence of pathogens in
domestic animals and wildlife illustrates the concern about
fecal pollution from all warm blooded animals and not just
from man.  However, it must be remembered that the human spe-
cific pathogen may loose _its pathogenicity when passing through
any link of the chain;Infected host, fecal pollution, non-
human or water host, exposed humans.

In the present project, the effect of environment once the
human specific pathogen leaves its host is of the utmost im-
portance.  In most cases the path traveled by a hypothetical
pathogen will be a cross connection between the sanitary and
storm sewerage systems for human pathogen sources and storm
water runoff for animal borne pathogens.  The possibly con-
taminated storm water is collected by the drainage system and
pumped into the outfall canals.  Once in the outfall canals,
the storm water can subsequently reach recreational areas
where humans may be exposed if_ any pathogens are present.
Thus, it is necessary to investigate the survivabiTity of
pathogens in the storm water once they leave the host organism.
                           125

-------
Effect of Environment on Pathogen Survival


The survival of Salmonellae  in the aquatic environment is
influenced by the same factors that control the persistence
of fecal pollution indicators.  Nutrient rich waste, lower
stream temperatures,  cold blooded host,  and a source of_
Salmonellae can produce an impact downstream.  However in
several studies (16), Salmonellae were added to individual
storm runoff samples  and .stored either at 10°C or 20°C to
approximate the water temperature in the environment.   Results
showed a 99% attrition of Salmonellae in the storm water
samples held ten days at 20°C while 5% of the bacteria
persisted beyond 14 days in  runoff water stored at 10°C.^
However, in no instance did  Salmonellae  levels increase iH
the storm water samples.

Another water borne pathogen causes leptospirosis,  This
disease is due to a group of coil-shaped, actively motile
bacteria, Leptospirae.  These pathogens  gain access to the
blood stream through skin abrasions or mucous membranes and
cause lesions involving the  kidneys, liver, and central
nervous system.  Although leptospires from infected reservoir
hosts may be present throughout the year, infections in the
United States are most frequent during the recreational
season (21).  Again several variables:/.affect the survival of
leptospires in the storm water environment.  At low temperatures
multiplication of these organisms is retarded, but persistence
is increased over that for summer temperature levels.

A commonly identified cause  of intestinal disease in the
United States is exposure to Shigella.  This may occur from
person to person contact and contaminated drinking water or
food.  The survival of shigella strains  once they enter the
water environment is limited by many ecological factors.  As
observed with Leptoapira and enteric viruses, persistence of
Shigella in water is much better when the total bacterial
population is low (17, 18).   Most interesting is the negative
reaction to formic and acetic acids produced by coliform
organisms.  The coliform group acid production apparently has
a bacteriostatic to bacteriocidal effect on the Shigella
strain (19).  A second important factor is water pH.  Experiments
on survival and recovery of S. flexmevi in the intestinal
tract of carp and bluegill indicated regrowth when incubated
at 20°C in a 1% fecal suspension which was free of coliform
and had a pH of 7.6 to 8.3.   However, several experiments in
1% fecal suspensions and an initial pH of  7.2 showed a rapid
die off of Shigella within several days (20).  Water temperature
also influences the levels of Shigella.   That is, it survives
longer at lower temperatures as do all other bacteria.
                           126

-------
The salinity level of the environment also influences the
survival^of leptospires.  The organisms can survive more than
10 days in lake water of low salinity.  In lake and river
waters with moderate salinity levels (70 - 7000 mg/1 chloride),
leptospires survived for less than one week.  In sea water
with a salinity of 13,000 to 17,000 mg/1 chloride, survival
time was reduced to less than one day (22).  Another factor
that influences leptospire persistence in the water environ-
ment is the density and composition of the microbial population.
Leptospires are inhibited rapidly when mixed with fecal
material at either 5°C or 37°C (23).  Also, raw sewage with
its varied microbial population shortens survival to 12 to
11 hours (2«O.

Serious intestinal disease in young children is often due to
infection by enteropathogenic E. ooli.  E. ooli generates an
enteric disease characterized by profuse watery diarrhea,
nausea, and dehydration with a general absence of fever.
A causal'relationship of E. ooli in humans due to exposure
to animals has yet to be established.  When E. ooli is
found in fresh or brackish water,,its occurrence indicates a
recent introduction of fecal contamination.  Multiplication of
E. ooli is observed in untreated cannery waste, poultry
processing waste, and raw domestic sewage.  These discharges
can all be characterized as having warm temperatures and
large quantities of bacterial nutrients.  After dilution by
better quality water downstream or exposure to waters with
high salinity levels, multiplication of E. ooli is
suppressed (25, 26).  Thus, environmental forces can produce
a sharp die off of E. ooli purification with only 10% viable
organisms present after two to five days has been found (27).

One other important observation has been the persistence of
Vibrio choleras in some polluted aquatic environments, although
the organisms should persist only a short time.  This
contradictory behavior was noticed in persistence of V. oholerae
from the Hoogly River in Calcutta, India (28).  Even after
chlorination (2.0 to 3.0 mg/1, ten minute contact time)
cholerae, vibrios, and salmonella are found (29).  It is
probable that pathogenic bacteria present in the poor quality
water are protected in clumps of particles from exposure to
the chlorine during the disinfection period.  Thus, there is
a persistence of pathogenic bacteria in very turbid waters.
                           127

-------
Application to Outfall Canals


In the urban community,  fecal contamination in separate storm
water runoff is derived from the fecal material deposited on
soil by dogs, cats, and rodents or sewage cross connection.
Survival of human specific pathogens in the water environment
is influenced by many of the ecological forces previously
discussed.   These factors need to be taken into consideration
in elucidating the fate of pathogenic organisms in the aquatic
environment.  The main factors are:

     1.  Temperature.

     2.  Interference of growth due  to competing
         microorganisms in the water.

     3.  Time since introduction of  microorganisms
         into water.

     4.  The effect of substances such as NaOCl or
         other inhibitory chemicals  either from natural
         or a man-made source.

     5.  The presence of solid material in the water
         which can shelter the microorganisms from
         attack.

For the particular treatment situation in the outfall canals,
the conditions are such that it is very unlikely that pathogens
could survive in any great number once disinfection has oc-
curred.  Temperature in the outfall  canals ranges from 60°F
to 85°F and thus, does not greatly enhance the survivability
of the organisms.  Additionally, the solids level of the storm
water is low so that the number of enclosed organisms should
also be low.  Also, the receiving stream has a moderate level
of salinity and thus organisms affected by increased osmotic
pressures should not fare well.  Bacteriological studies are
indicated to confirm these conclusions for pathogens in storm
water.  However, the fact that the environment in the dis-
charged storm water is not conducive to regrowth of fecal
organisms was demonstrated by the results of the long term
routine sampling, storm operation aftergrowth studies and the
storm profile aftergrowth study-  Also, it should be noted
that the levels of indicator bacteria in the outfall canals
after disinfection and regrowth no longer provide the same
measure of possible pathogenicity of the storm water unless
new sources of pollution are present.
                          128

-------
Effluent Criteria
There is no doubt that the use of coliform groups as indicators
of contamination has been an extremely useful epidemiological
tool.  However, once storm water has been disinfected, the
significance of the coliform group should be reevaluated since
the alternatives of continued chemical treatment or solids
removal are extremly costly.  In addition, there are only three
possible spheres of disposal which can ultimately be used;
air, water, and land.  The transfer of the problem from one
sphere to another occurs only at the cost of additional
expenditures of energy and, thus, more pollution.  For the
particular case of large volumes of bacterially polluted storm
drainage water, it might be best to allow natural processes to
remove the nutrients if the original treatment with disinfectant
is adequate from health standpoints and the subsequent envi-
ronmental factors are not conducive to pathogen regrowth even
if coliform levels recover.  Additional study is needed to
provide simple tests for pathogen detection and to determine
the effects of disinfection and subsequent environmental
factors on pathogens.
                          129

-------
                          SECTION XI

                          ECONOMICS

GENERAL

The addition of NaOCl to polluted storm water involves eight
major cost elements;  amortization, land, manufacturing
facilities, transportation facilities, storage facilities,
chemical feed systems, chemicals, and operation and mainten-
ance.  The first six  are fixed investment costs while the
last two are dependent on the amount of storm water pumped
and the degree of treatment required.  Sales taxes on
eauipment and freight charges were not included in the
calculations since they vary substantially with location
of the facilities. The cost of construction of the reaction
basin at St Charles was also neglected.

MANUFACTURING FACILITIES

The NaOCl manufacturing plant developed for this project was
of a novel design, subsequently patented, which can continu-
ously manufacture high strength NaOCl under atmospheric con-
ditions.  As is usual in process development, the design and
construction costs were higher than one would normally expect
for a facility with which a great deal of experience had
been available.  For  this reason, design costs are not included
in the cost of construction of the plant.  The fixed costs
of the various facilities at the manufacturing plant are
shown in Table 19. Table 20 shows the cost of manufacturing
1,000 gal. of 120 gpl NaOCl from the basic chemicals which
are delivered to and  stored at the plant.  The sums shown are
the average costs encountered during the project for producing
the NaOCl,  As can be seen,the price $78/52/1,000 gal. of
120 gpl NaOCl is comparable with' commercially available NaOCl
at a much lower solution strength.  It should be noted that
the water used for manufacturing and cooling of NaOCl is
provided at wholesale by the Sewerage and Water Board of New
Orleans.  The cost for the water is only $.035/1,000 gal., and
was neglected.

FEEDING FACILITIES

The fixed costs of the feeding facilities at each pumping station
is shown in Table 21.  The differences in the price of the
storage tanks at the  various stations is due to differences in
                           130

-------
                          TABLE 19

           FIXED COSTS :  NaOCl MANUFACTURING PLANT



A.  Equipment        Item                   Cost

               H20 Pumps                $  2,100.00

               Refrigeration
                  Equipment               13,931.00

               2 NaOCl Pumps               2,994.75

               Heat Exchanger              2,975.00

               NaOH Storage Tank          19,290.00

               2 NaOCl Storage
                  Tanks                   19,208.00

               NaOCl Averaging
                  Tanks                      201.96

               Chilled Water
                  Pumps                      950.25

               Miscellaneous              11,496.73
                                        $  73,147.69
 B.  Construction                         181,733.70
 C.  Supervision                           27,516.75
                                TOTAL    $282.398.14
                            131

-------
                        TABLE  20

           AVERAGE  COST  OF MANUFACTURING NaOCl
              (1,000  gals,  of  120  gpl NaOCD

             ITEM                        COST

          Electricity                  $  2.09

          Labor                          11«66

          Chlorine                        16.30

          Sodium Hydroxide               47.47

          Maintenance                     1.00
                           TOTAL         "78.52
                        TABLE  21

         FIXED COSTS:   NaOCl FEEDING FACILITIES

     ITEM          DPS  #3       DPS #*»     DPS #7      ST CHARLES

(2) NaOCl Storage
    Tanks         $19,208.00  $20,075.00 $24,453.00 $20,075.00

(2) NaOCl Pumps     1,593.83    1,593.83   1,593.00   1,593.83

Misc. Equip.
and Construction   47,279.04   45,353.00  57,186.00  33,700.48

Supervision         6,879.18    6,879.18   6,879.18   6,879.18
   Sub Total      $74,960.05  $73,901.01 $90,112.01 $62,248.49
                  TOTAL COST:   $301,221.56
                            132

-------
                         TABLE 22
             FIXED COSTS:  CHEMICAL FEED SYSTEMS
      ITEM
C12R Analyzers
Electronic Equ:
'water Samplers
DO Analyzers
Construction

$
nt



DPS #3
1968.75
4904.33
	 	
1166.25
7511.89
DPS #4
$ 1968.75
4904.33
2724.88
1166.25
7511.89
DPS #7
$ 1968.75
5121.00
10899.52
1166.25
7511.89
ST CHARLES
$ 1968.75
4904.33
5449.76
1166.25
7511.89
      Sub Total   $15,551.22   $18,551.22 $26,667.41  $21,000.98
                  TOTAL COST:   $ 81,495.71
                         TABLE 23
                    TOTAL FIXED COSTS
NaOCl Manufacturing Facilities
Transportation Costs
NaOCl Feeding Facilities
Chemical Control Facilities

                    TOTAL COST
$ 282,398.14
   35,960.04
  301,221.56
   86,945.47

$ 706,525.21
                              133

-------
the linings.  The different physical characteristics of
pumping stations altered the construction costs.  The increased
cost of the electronic equipment at DPS #7 is due to the fact
that it was ordered one year after the .other electronic
equipment.  The prototype sampler used at DPS #3 was built by
the Sewerage and Water Board machine shop at the initiation
of the project and its cost was not included,

TRANSPORTATION FACILITIES


The cost of the two NaOCl transport trucks was $35,960.04.
The operation and maintenance cost of the trucks will vary
with the frequency and degree of treatment required, and
is neglected.

CHEMICAL FEED SYSTEMS
The cost of NaOCl feed and control systems at the various
stations is shown in Table 22.   The figures here might in-
crease somewhat in subsequent facilities since a change in
the type of feed pumps or regular replacement of pumps is
indicated (pg   ).  However,  if provision is made to completely
flush the pumps during the periods between operation, these
pumps might be used for the life of the manufacturing plant.

SUMMARY
The total fixed costs of hypochlorination are given in Table
23.  Assuming a total life of 10 years for the facilities, and
an  interest rate of 6%, the fixed costs are $53,600/yr.

The calculation of disinfection cost will be based on treating
storm water with a chlorine demand of 3.5 mg/1 so as to main-
tain a 1.0 mg/1 residual at all times.  This requires a dosage
rate of 4.5 mg/1 (4.5 g/264,2 gal.).  A conservative estimate
of the average decrease in.strength of the NaOCl in the field
was 4 g/l/wk.  Assuming eight weeks storage before ultimate
use, 1,000 gal. of 120 gpl NaOCl manufactured at the plant
can ultimately treat 19,600,000 gal. of storm drainage water.

The average yearly pumpage of the ..four pumping stations in
the project is approximately 5x10   gal. if all pumpages are
considered.  The yearly fixed costs are $53,600 and the
manufacturing cost of the NaOCl required to disinfect 5x10
gal. of storm water is $200,300.  On this basis, the average
yearly cost of treatment would be $.000051/gal. of storm water.
                             134

-------
                        SECTION XII

                      ACKNOWLEDGEMENTS


          Sewerage and Water Board of 'New Orleans

The support of Mr. E.F. Hughes, General Superintendent (Ret.),
Mr.^G. Joseph_Sullivan, General Superintendent, and Mr. D.D.
Modianos, Assistant General Superintendent, is acknowledged
with sincere thanks.

Mr. Crawford J. Powell, Assistant General Superintendent (Ret.)
made the original suggestion for the project and gave counsel
and support through the construction and early operational
phases.

Mr. Ray A. Beaman, Clark L. Fox, and Anthony H. Carver
gathered water samples, ran chemical analyses, and maintained
the storm water sampling equipment.

Mr. George Hopkins, Water Treatment Superintendent, and Mr.
William F. Wells, Water Chemist, directed and supervised
the sodium hypochlorite manufacturing facilities.

Mr. Louis Meridier and Mr. E.H. Arnold provided mechanical
and electrical maintenance support for the project.

           Pavia-Byrne Engineering Corporation

Mr. Gerard S. Pabst, Jr. consulted on the microbiological
aspects of the project.

Sincere thanks are extended to Mrs. Joan Herzog, Miss Susan
Luttmann, and Miss Linda Herzog for their patience and
diligence in typing the final report.

             Environmental Protection Agency

The help and support of Mr. Robert Killer, Project Officer,
is acknowledged with sincere thanks.

The guidance and encouragement of Mr. Frank Condon, Head-
queirters Staff Office of Research and Monitoring, Washington,
D.C., and Mr. George Putnicki, Director of Surveillance and
Analysis Division, Region 6, was greatly appreciated.
                           135

-------
                       SECTION XIII

                        REFERENCES
 1.   Pavia, E. H., and  C. J. Powell, "Storm Water  Disinfection
     at  New Orleans", JWPCF, 41:1,  591  (1969).

 2.   Geldrich, E. E., L.  C. Best, B. A. Kenner,  and  D. J.  Van
     Donsel,  "The Bacterial Aspects of  Storm Water Pollution",
     JWPCF, 40:1  1861 (1968).

 3.   Kendall, M.  C., and  A. Stuart, The Advanced Theory  of
     Statistics,  Griffen, London, 1966.

 4.   Biguria, G., R. C. Ahlert, and M.  Schlanger,  "Distributed
     Parameter Model of Thermal Effects in Rivers",  1969
     Stream Pollution Abatement Conference, Rutgers  University,
     1969.

 5.   Dresnick, R., and  W. E. Dubbins, "Numberical  Analysis of
     BOD and  DO Profiles", J. Sanit. Engr. Div.  :  Proc.  ASCE,
     94;SA5,  789  (1968).

 6.   Verhoff, F. H., W. F. Echelberger, Jr., M.  W. Tenney, and
     P.  C. Singer, "Lake  Water Quality  Predictions Through
     Systems  Modeling", 1971 Summer Computer Simulation
     Conference,  Boston,  1971.

 7.   Geldreich, E. E.,  "Water Borne Pathogens",  Water Pollution
     Microbiology, edited by Ralph  Mitchell, John  Wiley  and
     Sons, Inc.;  237 (1972).

 8.   Pelczar, Jr., M. J., and R. D. Reid, Microbiology,  McGraw-
     Hill Book Company, New York, 1958.

 9.   Eiijkman, C., "Die Garungsprobe bei 46°C  als  Hilfsmittel
     bei der  Trinkwasseruntersuchung",  Centr.  Bakt. , 37,742
     (1904).

10.   Galton,  M. M., J.  E. Seatherday, and A. V.  Hardy,
     "Salmonellosis in  Dogs", J. Infec. Dis.,  91,  1(1952).

11.   Salle, A. J., Fundamental Principles of Bacteriology,
     McGraw-Hill  Book Company, Inc., New York,  1961.'

12.   Quist, K. D., "Salmonella in Poultry as Related to  Human
     Health", U.S. Dept.  of Agric., Report of  National Plans
     Conference,  24-30, November, 1962.
                           136

-------
13.  Lafton, C. B., S. M. Morrison, and P. D. Leiby, "The
     Enterd> aoteriaeeae of Some Colorado Small Mammals and
     Birds, and Their Possible Role in Gastroenteritis in
     Man and Domestic Animals", Zoonoses Res., 1, 277 (1962).

14.  Summers, J. L., "The Sanitary Significance of Pollution
     of Waters by Domestic and' Wild Animals  : A Literature
     Review", U. S. Dept. of Health, Education and Welfare,
     P. H. S., Shellfish Sanitation Technical Report, 1967.

15.  Janssen, W. A., and C. p. Meyers, "Fish : Serological
     Evidence of Infection with Human Pathogens", Science,
     159, 547 (1968).                             	L

16.  Andre, D. A., H. H. Weiser, and G. W. Maloney,  J. Amer.
     Water Works Assoc.,  59, 503 (1967).

17.  Wang, W. L. L., S. G. Dunlop, and P. S. Munson, "Factors
     Influencing the Survival of Shigella in Wastewater and
     Irrigation Water", JWPCF, 38, 1775 (1966).

18.  Babbitt, H. E., J. J. Doland, and J. L. Cleasby, Water
     Supply Engineering, McGraw-Hill Book Company, Inc., 1962.

19.  Hentges, D. J., "Inhibition of Shigella flexmeri by the
     Normal Intestinal Flora", J. Bacteriology, 97,  513 (1969).

20.  Geldreich, E. E., and N. A. Clarke, "Bacterial  Pollution
     Indicators in the Intestinal Tract of Freshwater Fish",
     Applied Microbiology, 14, 429 (1966).

21.  Howell, D., "Leptospirosis in Dairy Cows", Vet. Rec., 84,
     122 (1969).

22.  Schuffner, W., "Recent Work on Leptospirosis",  Trans._
     Royal Soc. Trop. Mec. Hyg., 28, 7 (1939).

23.  Clark, L., J. I. Kresse, R. R. Marshak, and^C.  J.
     Hallister, "Leptospira grippotyphosa Infections in Cattle
     and Wildlife in Pennsylvania", J. Amer. Vet. Med. Assoc.,
     141, 710 (1962).

24.  Chang, S. L., M. B. Buckingham, and M. P.  Taylor, "Studies
     on Leptospiva iaterohaemorrhagiae", J._ Infect.  Diseases,
     82, 256 (1948).

25.  Kittrell, F. W., and S.  A. Furfari, "Observations of
     Coliform Bacteria in Streams", JWPCF, 35, [36]  (1963).
                         137

-------
26.   Hanes,  N.  B.,  and  R.  Fragala,  "Effect  of  Seawater Concen-
     tration on Survival  of  Indicator  Bacteria",  JWPCF,  39,
     97 (1967).

27.   Mitchell,  R.,  "Factors  Affecting  the Decline of  Non-Marine
     Micro-Organisms  in Seawater",  Water Research,  2, 535
     (1968).

28.   Gareeb, A.  H.  A.,  "The  Detection  of Cholera  vibrios in
     Calcutta Waters  :  The River Hoogly and Canals",  J. Hygiene,
     58,  2,  (1960).

29.   Sen.,  R. ,  and  B. Jacobs,  "Pathogenic Intestinal  Organisms
     in the  Unfiltered  Water Supply and the Effect  of Chlori-
     nation", Indian  J. Med. Res.,  57, 1220 (1969).

30.   Fair,  Gordon M., John C.  Geyer, Daniel A.  Okun,  "Water
     and Wastewater Engineering", Volume 2, Water Purification
     and Wastewater Treatment  and Disposal, John  Wiley £ Sons,
     Inc.,  New  York,  1968.

31.   Eliassen,  Rolf,  "Coliform Aftergrowths in  Chlorinated
     Storm  Overflows",  J. of the Sanitary Engineering Division,
     Proc.  ASCE, 94:  SAl,  371  (1968).

32.   New Orleans Board  of Health, Personal  Communication.

33.   Chlorine Bleach  Solutions, Bulletin No. 14,  Solvay Technical
     and Engineering  Service,  Allied Chemical Corporation, 1965.
                          138

-------
                        SECTION XIV

              PROJECT PATENTS AND PUBLICATIONS
1.   Patent 3,702,234 - A method for forming sodium hypochlorite
    at atmospheric conditions from sodium hydroxide and
    chlorine in proper proportions and under controlled
    conditions to prevent the escape of unreacted chlorine  to
    the atmosphere; and to avoid the formation of sodium
    chlorate.

2.   Pavia, E. H., "Chlorination and Hypochlorination of Pol-
    luted Storm Water at New Orleans", presented at the 31st
    Annual Short Course for Water, Sewerage and Industrial
    Waste Disposal, Louisiana State University, March 14, 1968.

3.   Pavia, E. H. and C. J. Powell, "Stormwater Disinfection
    at New Orleans", presented at 41st Annual Conference
    of Water Pollution Control Federation, Chicago, 111.,
    Sept. 22-27, 1968, also, JWPCF, 41:4, 591 (1969) 41:4.

4.   Pavia, E. H. and C. J. Powell, "Hypochlorination of Storm
    Water Run Off at New Orleans", presented at Annual Meeting
    of American Shore £ Beach Preservation Association, New
    Orleans, La., Nov. 14-16, 1968, Shore and Beach, 37:1,
    (1969).

5.   Brown, L. R.,E. H. Pavia, "Lake Pontchartrain Storm Water
    Pollution Control Project", presented at American Society
    of Civil Engineers Meeting on Water Resources Engineering,
    New Orleans, La., Feb. 3-7, 1969.
                           139

-------
                        SECTION XV

                 GLOSSARY & ABBREVIATIONS
DEFINITIONS


Analysis of Variance - A statistical technique which analyzes
the variance which can be attributed to each of several
factors which were varied singly or combination.

Benthic Deposits - Deposits of living,  bottom dwelling organ-
isms in a stream.

Cells - In Analysis of Variance a cell contains all the
replicate values for one position in a factorial arrangement.

Chlorine Demand -  The demand for chlorine in a volume of water
caused by organic  and inorganic reductants.  This quantity is
defined as the difference between an initial chlorine concen-
tration in a specific volume of water and the total available
chlorine remaining at the end of a contact period.

Coliform, Coliform Bacteria - All the aerobic and facultative
anaerobic, Gram -  negative, nonspore - forming rod shaped
bacteria which ferment lactose with gas formation within 48
hours at 35°C.  Used as an indicator of bacterial pollution.

Crazing - Fine or  small cracks in a surface.

Diffussion - The transport in a given direction at a point
in a flow due to the difference between the true convection
in that direction  and the time average of the convection in
that direction.

Dispersion - The transport in a given direction at a point in
a flow due to the  difference between the true convection
in that direction  and the spatial average of the convection
in that direction.

Enterococci - A group of bacteria consisting of anaerobic
spore-forming rods which indicate recent fecal pollution,
sometimes referred to as fecal streprococci.

Factorial Arrangement - A method for apportioning the number
of tests required  for an    Analysis of Variance.  Given the
formula N=X  where X is the number of independent variables
and k is the number of levels (factors).
                          140

-------
Fecal Coliform - Coliforms derived from the gut of warm blooded
animals, test results expressed in terms of density in a given
volume of water.

Fibrous Glass Plastic - A laminar material having glass fibers
embedded in a plastic region to provide structural strength.

Membrane Filter Technique - A direct plating technique to
determine the density of coliform bacteria in a given volume
of water.

Multiple Tube Technique - A technique to determine the density
of"coliform bacteria in a given volume of water carried out by
dividing the sample into multiple portions and testing each
portion individually.

Nitrogen (Ammonia) - A product of microbiologic activity some-
times accepted as evidence of sanitary pollution in surface
waters.

ORP - Oxidation Reduction Potential - Oxidation Reduction
Potential (a precise measurement for the determination and
control of minute concentration of oxidant and reductants in
solution).


Pathogen - A microorganism capable of causing disease.
Sodium Hypochlorite - A salt of hypochlorous acid formed by
reacting chlorine with sodium hydroxide, which exhibits greater
stability than the acid.  It is used for disinfection and
bleach in place of the acid.

Solids Series - A series of tests to determine the solids con-
tent of wastewater.  They consists of the residue on
evaporation, total volatile and fixed residue, total volatile
and fixed suspended matter, dissolved matter, and settleable
matter.

Spectral Analysis - Statistical techniques which utilize the
Fourier or Laplace transforms of functions rather than the
functions themselves.

Stochastic - The property of being random with respect to
time.

Suspended Solids - The filterable residue in water.
                         141

-------
Thermal Coefficient of Expansion - A number of expressing
unit change in volume of a material due to a unit change in
temperature.

Ton Of Refrigeration - A unit of refrigeration equivalent to
288,000 BTU per day.

cfd - Cubic Feet per day

cfs - Cubic Feet per second

Cl~ - Chlorine

COD - Chemical Oxygen Demand - A measure of the oxygen equivalent
of that portion of the organic matter in a sample that is sub-
ject to oxidation by a strong chemical,oxidant.

DO - Dissolved Oxygen - The density of oxygen in solution in a
given sample of water.

DPS - Drainage Pumping Station

 °F - Degrees Fahrenheit

gals. - Gallons

gpd - Gallons per day

gpl - Grams per liter

mg/1 - Milligrams per liter

ml - Milliliter

NaOCl - Sodium Hypochlorite

NaOH - Sodium Hydroxide
                           142

-------
                        SECTION  XVI




                         APPENDICES






No.                        Title                      Page  No.




 1           Storm Profile,  DPS  #7,  Dec.  7,  1971       144-146



 2                "            "    Feb.  7,  1972       147-149



 3                "            "    Mar.  2,  1972       150-152



 4                "            "    Mar.  9,  1972       153-155



 5                "            "  Mar.  19,  1972       156-158



 6                "            "    May  11,  1972       159-161



 7                "            "    May  12,  1972       162-164



 8                "            "    June  9,  1972       165-167



 9                "            "    July  5,  1972       168-170




10                "            "    July  12,  1972      171-173



11                "            "    July  13,  1972      174-176



12                "            "    July  20,  1972      177-179



13                "            "    Sep.  30,  1972      180-182



!4                "            "    Oct.  22,  1972      183-185



15                "            "     Nov. 4,  1972      186-188
                            143

-------
 H20
RATE
cfs
Ci2R
mg/l
NAOCL
FEED
gpra
          3000
          2000 ..
1000 --
             0
           2.0
1.6f

1.2

 .8
 .4
   0
  60
  50
  40
  30
  20
  10
   0
                 Not Available
                 Not Available
                      70
80       120
  Time (Min.)
160
                                           200
                                                    240
                  Sampler A  O                  Sampler C   A
                  Sampler B  O                  Sampler D   D
                         PHYSICAL PARAMETERS  DPS#7
                         STORM PROFILE       12-7-71
             Appendix 1-1 Storm Profile, DPS #7, Dec. 7, 1971

-------
 SAL,
 iag /I
C.OJD.
mg/1
CL2D

mg/1
  pH
10000




 8000--




 6000--




 4000--




 2000--
          30
  9.0


  8.0"

  7.O..

  6.0
                                             -h
-i	i	1	1—

 80       120      160

    Time (Min.)
                                                     200
                                                     240
                   Sampler A   •               Sampler  C   A

                   Sampler B   O               Sampler  D   D

                         CHEMICAL PARAMETERS   DPS #7

                         STORM PROFILE   12-7-71
            Appendix 1-2 Storm Profile, DPS #7, Dec. 7, 1971

-------
 &
o
o
H
 w
•H
•fc
O
    10
    io7r
       1-
    io
           00
10
    10'
      4-
                                    TOTAL

                                    COLIFORM
                                        Sampler A  •

                                        Sampler B  O

                                                   A

                                                   a
1
io5-
io4-
*
6
0
3 io3J
A A • 	 A
^ ^ • •
9°

•H 2
c 10 -
re
O
io1-
VD— - '
	 1 	 ! 	 1 	 > 	 1 	 ! 	 1 	 1 	 1 	 1 	 1 	
Sampler I

FECAL
COLIFORM


            40   80   120 160  200  240
                 Time  (Min.)


            BACTERIAL RESULTS  DPS#7

            STORM  PROFILE      12-7-71



    Appendix 1-3 Storm Profile Results, DPS

    Dec, 7, 1971

-------
          3000
 H20
PUMP
RATE
cfs
CL2R
mg/l
NAOCt
FEED
gpm
2000 ..


1000--

   o
 2.0

 1.6--

 1.2--
  .4--

   0

  60
  50--

  40--

  30-.

  20--

  10-
                                Not Available
                                Not Available
               0       24

                   Sampler  A  •
                   Sampler  B  O
                              -i   i     i  —t
                               48      72
                                 Time (Min.)
                                     96       120

                                       Sampler C   A
                                       Sampler D   O
                          PHYSICAL PARAMETERS
                                               2-7-72
                  Appendix 2-1 Storm Profile, DPS #7, Feb 7,1972
                                  147

-------
 SAL,
 Hlg/l
C.O.D.
mg/l
mg/1
  pH
          9.0
          6,0
                                                    i=^cm n
~i-—*—.*—.*.
     72      96
Time  (Min.)
                                                   120
                   Sampler A   •              Sampler C  A
                   Sampler B   O              Sampler D  D
                        CHEMICAL PARAMETERS  DPS#7
                              PROFILE        2-7-72
              Appendix 2-2 Storm Profile,  DPS  #7,  Feb.  7,  1972
                               148

-------
    10'
    10'--
6
o
o
O
O
10
g
W
•H
C
ffl
txO
    10
      6..
j§   105
JO
•H
C
113
M     4
S   10
    10 3t
^    /
    10
    10
     10
I    /
I    /
\   I
\   I
I  /
I /
6
        0    24
   48   72   96
    Time  (Min.)
                           TOTAL
                           COLIFORM
                                         Sampler A

                                         Sampler B

                                         Sampler C

                                         Sampler D
                            FECAL
                            COLIFORM
                                120  144
            BACTERIAL RESULTS  DPS#7
            STORM PROFILE       2-7-72

      Appendix 2-3 Storm Profile, DPS #7, Feb. 7, 1972
                          149

-------
 H20
PUMP
RATE
cfs
Ci2R
mg/l
NAOCt
FEED
gpm
3000


2000..



1000--


   0

 2.0

 1.6

 1.2--

  .8"

  .4-'
Not Available
60
50-
40-
30.
20-
10-
0



Not Available



                     40       80     120     160      200      240
                                Time (Min.)
                  Sampler A  •                  Sampler C   A
                  Sampler B  O                  Sampler D   D
                         PHYSICAL PARAMETERS  DPS #7
                         STORM PROFILE        3-2-72
            Appendix 3-1 Storm Profile, DPS #7,  Mar. 2, 1972
                               150

-------
 SAL,
 mg/l
C.O.Di
mg/l
mg/l
  pH
        10000
         8000--
         6000--
         4000--
         2000--
4.0-


3.0-


2.O..1


1.0..


  0
                             80      120      160

                                Time (Min.)
                                          200
                   Sampler A   •              Sampler C  A

                   Sampler B   O              Sampler D  D

                         CHEMICAL PARAMETERS  DPS #7

                         STORM PROFILE        3-2-72
            Appendix 3-2  Storm Profile,  DPS #7,  Mar.  2,  1972


                               151

-------
E
o
o
H

CO
t—'
£Z
CO
•H
c
re!
bO
rH
s
o
o
to
g
(0
•H
c
(ti
W)
P!
O
    10
      5-
        O0
    10 -•
    10 +
    10 t
f
      \
                          TOTAL
                          COLIFORM
                                         Sampler A  •

                                         Sampler B  O

                                         Sampler C  A

                                         Sampler D  D
                          FECAL
                          COLIFORM
            40   80  120   160   200   240
                 Time  (Min.)

            BACTERIAL RESULTS  DPS #7
            STORM PROFILE       3-2- 72
   Appendix 3-3 Storm  Profile  Results, DPS #7, Mar.2,  1972
                         152

-------
 H20

PUMP

RATE
cfs
Ci2R

mg/l
NAOCL

FEED
gpm
3000






2000 ..







1000-





   0


 2.0




 1.6--




 1.2--




  .8"



  .4



   0



  60
  50--


  HO--


  30-.



  20-


  10--


   0 -
Not Available
 Not Available
                      20
                            60

                      Time (Min.)
               80
100
                  Sampler A  ®                   Sampler  C   A

                  Sampler B  O                   Sampler  D   P

                         PHYSICAL PARAMETERS  DPS #7

                         STORM PROFILE        3-9-72


           Appendix U-l Storm Profile, DPS #7, Mar. 9, 1972
                                153

-------
 SAL,
 aig/l
mg/l
CL2D
mg/l
  PH
        10000
         8000-
         eoool
   }
         4000

         2000

            0
          300
     8^
200

100 +

  0
          9.0
8.0 ••
7.O.-
6.0
               D-
                           -~- --- o
                      I   1-
20
                                   •4——4-
                                                     100
                   40       60       80
                      Time (Min.)
         Sampler A   •              Sampler  C   A
         Sampler B   O              Sampler  D   D
               CHEMICAL PARAMETERS  DPS#7
               STORM PROFILE        3-9-72
120
             Appendix  H-2  Storm Profile,  DPS #7,  Mar.  9, 1972
                                  154

-------
  10
G ±U 1
o JD
5 .--
1 io5-
Cfl
•rH i
c
1 "*•
r^x" X -
- o-d V
i1
iu-


io5-
L)._
r-l
6
| 10 3-
w
•H 2
C 10 -
bd
0
lo1-





'•^A*-'""*
.
•O--CX ^-Qr 	 "
"^i \ -
^•^ \ /^-
Vx


— i — i — i__i — i — i — i — i — i — i — i —
TOTAL
COLIFORM



Sampler A •
Sampler B O
Sampler C A
Sampler D D



FECAL
COLIFORM




       10   30    50    70    90    110
                Time (Min.)

          BACTERIAL RESULTS  DPS #7
          STORM PROFILE       3-9-72
Appendix 4-3 Storm Prpfile Results, DPS #7, Mar. 9, 1972
                         1'55

-------
 H20
PUMP
RATE
cfs
CL2R
mg/1
NAOCL
FEED
gpm
          3000
          2000 ..
1000--
   0

 2.0


 1.6


 1.2


  ,8


  .4

   0

  60

  50

  40

  30

  20

  10

   0
             Note:  Pumped 2 hrs prior to
                    initation of disinfectant
                                      Note:  C1?R analyzer
                                           ceased  functioning
                                           at t = 60 min
40      60
  Time  (Min.)
                                              80
                                            110
                  Sampler A  •                  Sampler C
                  Sampler B  O                  Sampler D

                         PHYSICAL PARAMETERS  DPS#7
                         STORM PROFILE        3-19-72


        Appendix 5-1 Storm Profile, DPS #7, Mar.  19,  1972
120
                                  156,

-------
 SAL,
 mg/l
C.O.Di
mg/l
Ci2D
mg/l
  pH
10000
 9000
 8000
 7000
 6000
 5000
 4000
 3000
 2000
 1000
    0
  300

  200
  100
    0
  5.0
  4.0
  3.0
  2.0
  1.0
    0
                     20
                             60
                        Time (Min.)
100
120
                   Sampler A   •              Sampler C
                   Sampler B   O              Sampler D
                         CHEMICAL PARAMETERS  DPS #7
                         STORM PROFILE       3-19-72
                                                 A
                                                 D
     Appendix 5-2 Storm Profile,  DPS  #7,  Mar.  19,  1972
                               157

-------
10

10 7-



i~i n Q
s
o
o
H
^^^
n 1Q5-
•H
c
£ lO4'
o
10 3-
^ w



10 5"


10 4-
^
,— {
s
o
M 10 -
^s,^
to
6
to
•2 10 2-
rd
bO
fn
0
10 X
•-^r^ — ^ — ^-*____— -*
\ \
V
\D 	 V 	 D 	 	 	 	 	 r
\ \
\ \
V
\ V
\
\ \
\ \
b — °-V,
\








• V-*. ., . — ^
r*C ''^v^r^ 	 •___JL~" ^^
^\n — A-" ^---c
\ \
\ \
\ \
\ \
\ \
\ \
\ \
\ \ ^-°-^

Jr ~





^
	 1 	 ! 	 1 	 1 	 1 	 1— 1 	 1 	 1 	 1 1 , .



]


TOTAL
COLIFORM







Sampler A •
Sampler B O
Sampler C A
Sampler D D








FECAL

COLIFORM







          20   40   60   80  120
               Time  (Min.)

         BACTERIAL RESULTS  DPS#7
         STORM  PROFILE     3-19-72
Appendix 5-3 Storm Profile Results, DPS #7, Mair. 19, 1972
                        158

-------
 H20

PUMP

RATE
cfs
Ci2R

mg/1
NAOCt

FEED
gpm
3000





2000 ..






1000-




   0


 2.0




 1.6--




 1.2--




  .8"
                     WIA
                      1*0       80     120     160
                                Time (Min.)

                  Sampler A  •                  Sampler C   A

                  Sampler B  O                  Sampler D   Q

                         PHYSICAL PARAMETERS  DPS #7

                         STORM PROFILE       5-11-72




         Appendix 6-1  Storm  Profile, DPS #7, May 11, 1972
                                159

-------
 SAL,
 Elg/l
C.O.Di
mg/l
Ci2D
mg/l
  pH
10000
8000-
6000-
4000-
2000 -
0
300
200"
100 •
0
4.0-
3.0-
2.0.
1.0.
0
9.0
8.0 -
7.0 -
6.0
-
-
-
- 4 """---n 	 n
' \
[oo^X^ ^-^j*



«

!
•
|

1 	 — 1 	 1 	 1 	 — I 	 1 	 1 	 1 	 1 	 1 	 1 	 1 	
  UO       80      120       160     200
             Time (Min.)
Sampler A   •              Sampler C   A
Sampler B   O              Sampler D   D
      CHEMICAL PARAMETERS  DPS #1
      STORM PROFILE        5-11-72
                                                             240
      Appendix  6-2  Storm  Profile,  DPS  #7,  May  11,  1972
                              160

-------
->-u r
10 7--
H 106-
f~i
O
H
1 io5-
CO
•H
C
rti
w , ~ 4-
f-. 10
0
10 3-





10 5-
10 4-
•
rH
£
0
3 10 3-

"**>•*
to
rt
^
K)
•H 2
C 10 ^
tfl
bO
r
H
O
10 1

^ \
*v, »
• ^ \ -^
V \^ 0
\ \x^ D
v\ /
,'A \ /
X V ^ /
" ^ ^--V
\
V.
ti
^\
\.
v
^




\
\
\
\
°^-*\
Tr \
. \ v^
\\ ^a
\\
\\
\ \
\\
\ \
iV
bA-o----°
A
\
_A
"ti
! I 	 1 	 1 	 1 	 1 	 1 	 1 	 1 	 1 	 r—

TOTAL

COLIFORM







Sampler A •
Sampler B O
Sampler C A
Sampler D d







FECAL

COLIFORM






80   120 160
 Time  (Min.)
                              200 -240
          BACTERIAL RESULTS  DPS #7
          STORM PROFILE      5-11-72
Appendix 6^3 Storm Profile Results, DPS #7, May 11, 1972
 vv                   161

-------
 H20
PUMP
RATE
cfs
Ci_2R
mg/l
FEED
gpm
3000


2000..



1000--


   0
 2.0

 1.6

 1.2
  .4

   0

  60
  50

  40

  30

  20

  10

   0
                      80
                    160      240      380     400     480
                      Time  (Min.)
                  Sampler A  •                   Sampler C
                  Sampler B  O                   Sampler D
                         PHYSICAL PARAMETERS  DPS#7
                         STORM PROFILE        5-12-72
        Appendix 7-1 Storm Profile, DPS #7, May  12,  1972
                             162

-------
 SAL,
 ag/l
CL2D
mg/l
  PH
J-U U UU
8000-
6000-
4000-
2000-
_
0
300
200'
100-
0
3.0-
2.0.
1.0.
0
9.0
8.0-
7.0 -
6.0
-
i
r
'.
!


-


i
'
!




80 120 240 320 400 48
                                Time  (Min.)
                   Sampler A   •              Sampler C
                   Sampler B   O              Sampler D
                         CHEMICAL PARAMETERS  DPS#7
                         STORM PROFILE        5-12-72
      Appendix 7-2  Storm Profile,  DPS  #7,  May  12,  1972
                             163

-------
10
10 7-

H 10 &\
0
o
H.
| 10 5-
co
•H
C
1 10*
o

S
A
V ^ — \
V>A \ ^
V o ^
"•^cf &
I v^^ '
O-^-/ ) ^^^^ '
\ "^& X
i T /
\ \ 1
\ \ i
^ y

10 4
T



10 ^
0
s
o
3 io3-
w
6
w
•H o
c 102-
d
o
1
10 -



. .
s
^\ ^^^v
\



VI K
fV / '^
\ ^^ I
\ ^ a
\ ^\AX*
-o
	 1 	 ! 	 1 	 1 	 1 	 A 	 ! 	 1 	 1 	 1 	 1 	



TOTAL
COL i FORM








Sampler A €J
Sampler B O
Sampler C A
Sampler D E




FECAL
COLIFORM






          80    160   240   320  400   480
               Time  (Min,)

          BACTERIAL  RESULTS   DPS  #7
          STORM  PROFILE       5-12-72
Appendix 7-3 Storm Profile Results, DPS #7, May 12, 1972

                     164

-------
 H20
PUMP
RATE
cfs
Ci_2R
mg/l
NAOCL
FEED
gpm
3000

2000..

1000--

   0
 2.0

 1.6

 X.2

  .8'-
             0
            60
  50-
  40--
  30-.
                       20
                    40      60
                      Time  (Min.)
                                                      100
120
                   Sampler  A  •                  Sampler C  A
                   Sampler  B  O                  Sampler D  O
                         PHYSICAL PARAMETERS  DPS #7
                         STORM PROFILE        6-9-72
         Appendix 8-1 Storm Profile, DPS #7, June 9, 1972
                                165

-------
 SAL,
 mg/l
C.O.D.
mg/l
mg/1
  pH
10000
8000-
6000-
4000-
2000-
0'
300
200'
100 •
0
4.0-
3.0-
2.0.
1.0.
0
9.0
8.0 -
7.0.
6.0

' V
; \
:^t^^

^^~-—+
^^


^^^~*-&-"(* — •

20 40 60 80
Time (Min.)
Sampler A • Sampler C A
Sampler B O Sampler D D
                         CHEMICAL PARAMETERS  DPS #7

                         STORM PROFILE        6-9-72
           Appendix  8-2 Storm Profile, DPS #7, June 9, 1972


                            166

-------
       10
   o
   o
   •H
    c
    rt
    fc
   o
6
o
o
rH
   6
   CO
   •H
   fi

   bO
      4..
    10
       103T
                   V
                   /\
          -   J
       10
       10
         5..
       io
         3..
    10-
       10
         1..
               20    40    60    80
                    Time (Min.)

               BACTERIAL  RESULTS   DPS  #7
               STORM PROFILE       6-9-72
                                        TOTAL
                                        COLIFORM
                                            Sampler A  •

                                            Sampler B  O

                                            Sampler C  A

                                            Sampler D  O
FECAL
COLIFORM
Appendix 8-3 Storm Profile Results, DPS #7, June 9, 1972

                          167

-------
 H20
PUMP
RATE
cfs
Ci_2R
mg/l
FEED
gpm
          3000
          2000 ..
          1000--
                             100     150
                                Time (Min.)
                                             200
250
300
                  Sampler A  •                  Sampler  C   A
                  Sampler B  O                  Sampler  D   P
                         PHYSICAL PARAMETERS  DPS#7
                         STORM PROFILE         7-5-72
            Appendix 9-1  Storm Profile,  DPS #7,  July 5, 1972
                               168

-------


SAL,
mg/l
C.O.D.
mg/l
CL2D
mg/l
pH
.LUUUU
8000-
6000-
4000-
2000-
0
300
200'
100-
0
4.0-
3.0-
2.0.
1.0.
0
9.0
8.0-
7.0 -
6.0


,
\
\
\
\
iSrt!)*- .d-vA /^A T™1 "^A f\_/\ nv*v -j\' i/h n — W

N


•s.


	 1 	 ^ 	 — 4 	 1 	 1 	 1 1 	 1 1 	 1^ 	 H- 	 —
          50    '   100      150      200     250
                     Time (Min.)
        Sampler A  «               Sampler C   A
        Sampler B  O               Sampler D   D
               CHEMICAL  PARAMETERS   DPS#7
               STORM PROFILE         7-5-72
300
Appendix 9-2 Storm Profile, DPS #7, July 5, 1972
                  169

-------
ID
io7-
H io6-
o
o
Organisms/
M I-1
0 0
-P en
io3-



1C5'
r-ganisms/lOOml.
(_. (_i !_•
0 0 O
ro co -P
*H
0
101
9
i
_ i
60 ^^D^ "$^Q
- V-" ]\
"A\ / x
v /
^"4
-


0
•>• .
?\ NSXD^"'~R / \
!.'\^-^ ;x \ \
*n ^ \/ \
^'\/\ ^
\/ > \
» WJ ^
——) 	 1 	 ^ 	 1- 	 1 	 1 	 1 	 1 	 1— — 1 	 _!___


TOTAL
COLIFORM

Sampler A •
Sampler B O
O ^ rm-\ T ^v^ C^ ^\
bampxer o o
Sampler D E

FECAL
COLIFORM

     50   100  150  200  250  300
           Time (Min.)

     BACTERIAL RESULTS  DPS#7
     STORM PROFILE        7-5-72
Appendix 9-3 Storm Profile Results, DPS #7, July 5, 1972
                  •170

-------
3000

H20
PUMP
RATE
cfs



CL2R
mg/1





NAOCL
FEED
gpm



2000.


1000-

0






9.n
1.6-
1.2-

.8'
.4-
0
60
50-
40-
30-

20-
10-
0



i
1 / 	 VS/S*1 fsAAAV^J
' \ r u 	 ' M^^x
\/






fa
•r^^
	 1 1 	 1 	 1 	 1 	 1 	 1 ' — 1 	 H- 	 — f 	 -+- 	
                    80       120
                      Time (Min.)
                           160
Sampler A  •                  Sampler C
Sampler B  O                  Sampler D
       PHYSICAL PARAMETERS  DPS #7
       STORM PROFILE       7-12-72
                                                 D
  Appendix 10-1 Storm Profile, DPS #7, July 12, 1972
                     171

-------

SAL.
mg/l
C.O.D,
mg/l
CL2D
mg/l

pH

10000
8000-
_,
6000-
4000-
2000-
0
300
200'
100-
0
4.0-
3.0-
2.0.
1.0.
0
9.0
8.0 "
7.0 .
6.0
-
[
; D— •- D
\ - |

1

.




' ^^tfe^.-^._^-..-^A---A
•gj* --o--'Qo----
-------
J.U
10 '•
6
e 10 "
o
o
rH
CO
•ri
c
Tj
bO L|,
O
3
10 '




5
10
10 ^
•
i— i
E
o
o -3
rH 10 -
W
CO
•H 2
C 10 -
bO
J_J
0

10 X-

'
1
• \\
_ V\:^-'^~'-0
\ \
\ \
\ \ .

b-'^^--^'
X3







^fi
TS Q
• \ , \ D
\ ^ .s^
1 , \ \ /
1 \ \ \
A\if \ 	 a/'
\ \ ND 	
'. \
\ \
V ^
\o
\ \
\ \
\ \
\ \
K--^b--OA-Q^ 	 ^
— 1 — 1 — 1 — 1 — 1 — i — 1 — 1 — 1 — II -


TOTAL
COLIFORM







Sampler A •
Sampler B O
Sampler C A
Sampler D O







FECAL
COLIFORM









                       Time  (Min.)

                 BACTERIAL RESULTS  DPS #7
                 STORM  PROFILE       7-12-72
Appendix 10-3 Storm Profile Results, DPS #7, July 12,  1972


-------
 H20
PUMP
RATE
cfs
Ci2R
mg/l
NAOCL
FEED
gpm
          3000
          2000
1000 -•
  50

  40

  30

  20

  10

   0
                             80      120
                                Time (Min.)
                                    160
200
240
                  Sampler A  •                  Sampler C  A
                  Sampler B  O                  Sampler D  D
                         PHYSICAL PARAMETERS  DPS#7
                         STORM PROFILE        7-13-72

  Appendix 11-1 Storm Profile, DPS #7 July 13, 1972
                               174

-------
 SAL,
 mg/l
CL2D
mg/l
  pH
10000

 8000

 6000

 4000


 2000--
            0

          300
C.O.D,    20°
          100 +
            0
  4.04-

  3.0
  2.0

  1.0
    0
  9.0
  8.0
  7.0
  6.0
                                      i
                    80      120     160
                        Time (Min.)
200
                                                            240
                   Sampler A   •              Sampler C
                   Sampler B   O              Sampler D
                         CHEMICAL  PARAMETERS  DPS#7
                         STORM PROFILE        7-13-72

    Appendix  11-2  Storm Profi.le,  DPS  #7,  July  13,  1972
                            175
                                                 A
                                                 D

-------
1U

7
10 -

i 10 6-
o
0
H
u 10 5-
w
••H
c
rd
W3 „ 4.
fc 10
o
io3-



10 5-
4
10 -
•
r— 1
0
O , „ Q
rH 10 3-
co
w
•H ?
c 10 -
bO
O
10 x-
( ^- "" *"* **
\ r~[f^f ^ij
®(
"K
i Y
-1 \
1 i
1 \
' \
" 6--O. \
X \
\ ,
sl ,O
p-' \
r \
\ v
\ \
^rJO^







| '
1 /
1 /
"^c> ^~^d
\ V
\\
\A
\,
\
\
- 1 1 	 -4 	 4- 	 \r~ 	 1 	 J 	 -1 	 ( 	 1 1





TOTAL
COLIFORM








Sampler A •
Sampler B O
Sampler C A
Sampler D D





FECAL
COLIFORM






40   80   120  160
      Time (Min.)
                                 200   240
            BACTERIAL RESULTS  DPS  #1
            STORM  PROFILE     7-13-72
Appendix 11-3 Storm Profile Results,  DPS #7, July 13, 1972
                        176

-------
          3000
 H20

PUMP

RATE
cfs
Ci_2R

mg/l
NAOCL

FEED
gpm
2000..





1000-




   o


 2.0



 1.6



 1.2



  .8



  .4
   0


  60


  50


  40


  30



  20


  10


   0
50     100      150

          Time (Min.)
                                              200
                                            250
                   Sampler A   •                  Sampler C

                   Sampler B   O                  Sampler D

                         PHYSICAL PARAMETERS  DPS #7

                         STORM PROFILE        7-20-72
                                                 A


                                                 D
       Appendix 12-1  Storm Profile,  DPS  #7,  July  20,  1972
                                177

-------


SAL,
mg/l

C.O.D,
mg/l
CL2D
mg/l

pH

1UUUU
8000-
6000-
.•
4000-

2000-
0
300
200'
100-
0
4.0-
3.0-
2.0.
1.0.
0
9.0
8.0-
7.0.
6.0

. ^"-^D
\
\
\
X,
\
0 ^^r~^^-^t--^ "^^

•






^o^-:-^^^ 	 o
	 	 •• — h 	 1 	 — 
-------
1U
io7-
* c
H 10 -
O
o
iH
1 io5-
10
•H
C
(d
u.n 1 1
dU H.
& 10
o
io3-


5
10
4
10 '
inisms/lOOml
j_i |_.
O O
ro so
*u
bS
k
O
1
10"
«
7^ X
; \ /\
\\ ' \
* \\ / ^
i \\ / \
1 >\ / \
4 L/ ^
D— "\\
\
' \
\\
' ^
V \J
\
\A

9-9 •
i \
. l \
A 4 n
V\ A
' \ i \
v / \
* \ i \
-r \
\\ \
\k \
\x \
\ \ V
k-d>A--^ a
ra_4_^_^__^_™-H"~4-^r--4-^^


TOTAL
COLIFORM


Sampler A •
Sampler B O
C-aTnt-iT a~f\ P A.
oa.inpxer' u w
Sampler D D

FECAL
COLIFORM


           To    100   150   200   250
                  Time (Min.)

            BACTERIAL RESULTS   DPS#7
            STORM PROFILE      7-20-72

Appendix 12-3 Storm Profile Results, DPS #7,  July 20,  1972
                         179

-------
 H20
PUMP
RATE
cf s
Ci2R
mg/l
FEED
          3000
          2000 ..
1000--
                              MO       60
                                Time (Min.)
                                    80
100
120
                  Sampler A  ®                  Sampler C  A
                  Sampler B  O                  Sampler D  Q
                         PHYSICAL PARAMETERS  DPS#7
                         STORM PROFILE       9-30-72
       Appendix 13-1 Storm Profile, DPS #7, Sept. 30 , 1972
                                180

-------



SAL,
mg/l
C.O.D,
mg/l
CL2D
mg/l

pH



xuuuu
8000-
6000-
4000-
2000-
0
300
200'
100-
0
4.0-
3.0-
2.0.
1.0.
0
9.0
8.0-
7.0 .
6.0
LJ ' U
11,000 11,800



- ^^a^^^-^---^— -»• 	 A

-— _-

/\
•^N/ ^^
^^—•^



Ct. J3~ ~~ O— 	 O

20 40 60 80 100 12
Time (Min.)
Sampler A * Sampler C A
Sampler B O Sampler D D
                   CHEMICAL PARAMETERS  DPS #7
                   STORM PROFILE       9-30-72
Appendix 13-2 Storm Profile, DPS #7,  Sept.  30,  1972
                        181

-------
10
7
10 -
g
H 10-
O
o
H
co 1Q5.
M
•H
C
£T u
h 10
o

3
10 •



10 "
H
6
o
S io3-
6
w
•H o
S 10-
rd
bO
fn
O
1
10 •
*V\
V -, A
\
- i \
\^ .
' » X
' \ x
-d \ V
\ \

\ 'V P
\ V /
\ \ /
\ N /
\ ^ /
\ N '
\
\
V















' 1 1 	 \- — 1 	 1 1 1 1 1 II



TOTAL
COLIFORM










Sampler A •
Sampler B O
Sampler C A
Sampler D Q



FECAL
COLIFORM









           20   40   60   80   100  120
                Time (Min.)


           BACTERIAL RESULTS  DPS #7

           STORM  PROFILE      9-30-72



Appendix 13-3  Storm Profile Results,  DPS  #7,  Sept.  30,  1972

                       182

-------
 H20

PUMP

RATE
cfs
CL2R

mg/l
NAOCL

FEED
gpm
          3000
          2000..
1000-




   0


 2.0 _



 1.6-



 1.2-.



  .8"



  .«*"


   o L


  60 -


  50-


  UO.-


  30..


  20-"


  10"


   0 .
                               -t-
                      50     100      150

                                Time  (Min.)
                                    200
250
300
                  Sampler A   •                  Sampler C   A

                  Sampler B   O                  Sampler D   Q

                         PHYSICAL  PARAMETERS   DPS#7

                         STORM PROFILE       10-22-72
       Appendix 14-1 Storm Profile,  DPS #7,  Oct.  22,  1972
                                183

-------



SAL,
mg/l
C.O.D,
mg/l
CL2D
mg/l

pH




10000
8000-
6000-
4000-
2000-
0
300
200'
100-
0
4.0-
3.0-
2.0.
l.Oj
0
9.0
8.0 -
7.0 -
6.0
- s,
V.
"\
• \
\
- \
\
t^WV^-^A <*~* 	 *— ^-^

^


^~*



^V_ ^^\
&•'' ~ ,-^^ s& 	 A
00^*









50 100 150 200 250 300
Time (Min.)
Sampler A • Sampler C A
Sampler B O Sampler D D
                   CHEMICAL PARAMETERS  DPS#7
                   STORM PROFILE       10-22-72
Appendix 14-2 Storm Profile,  DPS #7,  Oct.  22,  1972

-------
J-U
io7-



6
H 10 -
O
o
rH
1 io5-
CO
•H
C
nj
P? 10 '
0

io3-




•,«5-
10
rH
6
o
3 io3-
CO
6
CO
•H n
C 102-
WJ
0
10 -1-

-t". '-^^
7^ \/
/\f \ f\
\ / \
\ / V
$ \

/ » v^
. / \ \
1 \
\ 1
I \
V

i>-"° H
\
^




[^ A,
I / V
Cf"^ A /
\ * "^ri
^1 \
\ \
\ 1
\ 1
\ i
\ •
\ 1
^ \
> 1
' i
xl
^ L
h--^.^-^
	 1 	 ; 	 \-—* 	 1 . .1 •! 	 1 	 ! 	 \ — -4—





TOTAL

COLIFORM









Sampler A •
Sampler B O
Sampler C A
Sampler D O





FECAL
COLIFORM






           50   ' 100  ' 150200  250  300
                 Time (Min.)

           BACTERIAL RESULTS   DPS#7
           STORM  PROFILE     10-22-72
Appendix 14-3 Storm Profile Results, DPS #7, Oct.  22,  1972
                       185

-------
 U 0
 r,2G
PUMP
RATE
cfs
mg/l
FEED
          3000
          2000*
1000-f
  60
  50'
  40.
  301

  20|

  10-1

   0
                      H	h
            12       24    '36
                      Time (Min.)
        Sampler A  •
        Sampler B  O
               PHYSICAL PARAMETERS  DPS
               STORM PROFILE        11-472
     60

Sampler C
Sampler D
                                                              72
                                                            Q
       Appendix 15-1 Storm Profile, DPS #7, Nov. 4, 1972
                             186

-------
SAL,
rag/I
       10000
        80004-


        600d|
        4000
        2000
                    12
24      36       48
    Time  (Min.)
60


C.O.Di
mg/l'

CL2D
mg/l

_ ( !
Pn


0
Q n fi
200'
100 i
0

4.0-
3.0-
2.0.
1.0.
0
9n
. U
3.0-

7 n
6.0
s V 	 ^^^ 	 '-'= 	 ~— • --O- • —-.~-. — —— ^ 	 V
! .

*"
•

-


SJ—'j-Ji 	 ^. J-v^ -fi

w
	 1 	 ! 	 1 	 1 	 1 	 ! 	 !- — — i 	 ( 	 — 1— — H 	 —
72
                  Sampler A   •              Sampler C  A
                  Sampler B   O              Sampler D  D
                        CHEMICAL PARAMETERS  DPS #7
                        STORM PROFILE       11-4-72
         Appendix 15-2 Storm Profile, DPS #7,  Nov.  1,  1972
                            187

-------
•*•
7
10 j

H IQ6-
s
0
o
H

, 	 V


6 D
\N
O \
\ xv
^- \ \
2 KPT x \
S \ \
w \ x.
•H \ a
C ! \
re! \




TOTAL
COLIFORM








bo 4J. h
fc 10
o



io3-





, .5-
10 1
H
H
e
0
S 10 3-
"^^
w
S
w
S lo1
bJD
fn
O
10 ^
^
\
\
\
\ ^Q
V"'" \
\
\
\
\
\
n

•^ 	 	 	 *


P



- ^
\ s.
\ X.
\ Vs
\ V
\ N^
^\
^
\
"o 	 o
	 1 	 1 	 1 	 1 	 1 	 1 — 1 	 1 	 1 	 1 	 1 —





Sampler A , •

Sampler B O

Sampler C A
Sampler D O






FECAL

COLIFORM






                      12    24   36    48   60    72
                            Time  (Min.)

                      BACTERIAL RESULTS  DPS #7
                      STORM  PROFILE      11-4-72
       Appendix  15-3 Storm  Profile Results, DPS  #7,  Nov. 4,  1972
                                  188
*U.S GOVERNMENT PRINTING OFFICE:1973 546-312/158 1-3

-------
 SELECTED WATER                   i. Rfi*r»f
 RESOURCES ABSTRACTS                              ...

 INPUT TRANSACTION FORM                              *•
 4  Title  HYPOCHLORINATION OF POLLUTED STORM WATER       5  *.perf/;.,e

        PUMPAGE AT NEW ORLEANS,                         *
                                                        S.  i  form,  , Org.; ..attoo
                                                       I   Sepo: Nu.
 f.  Au<:hor(f.)

 Pontius,  U.R., Pavia, E.H.,  and Crowder, D.G.
                                                          11023  FAS
  .
        Pavia-Byrne Engineering Corporation
        431 Gravier St.
        New Orleans, La.    70130                      '/  Typ, i Repu . and
                                                          Pfioa Co ered
  12. Si  nsorin Organ ition
     Environmental Protection Agency report number,
     EPA-670/2-73-067, September 1973.
        ct storm water from  the streets of New Orleans  flows  to large
drainage pumping stations where it is discharged into  Lake Pontchartrain
by means of long outfall canals.   To reduce the coliform density, storm
water was disinfected with  sodium hypochlorite (NaOCl).   Project facili-
ties included manufacture,  transportation, storage and feeding of 100
 ?am/l NaOCl.  Residual chlorine analyzers were used to monitor NaOCl
dosage levels.  Sixteen high  volume storms totaling 10  to the 9th power
gal. of storm water were treated with more than 35,000  gal.  of NaOCl.
"otal and fecal coliform in untreated storm water exceeded 1000 org/100 ml
99% of the time.  Coliform  densities in treated water  were significantly
reduced, with chlorine residuals (total available) of  greater than 0.5
mg/1 resulting in 99.99% or greater removal.  However,  rapid recovery of
coliform levels occurred within 24 hours.  Total coliform recovered to
pre-disinfection levels, but  fecals did not.  The recovery did not appear
to be the result of tidal influences.  Long term fecal coliform levels
were reduced by one order of  magnitude in each outfall canal.  The
amortized cost of NaOCl manufacturing, transporting, feeding and control
facilities was $53,600/yr.  NaOCl costs for treating 5 times 10 to the
10th power gal. of storm water yearly were $200,300.   This resulted in a
treatment cost of $.000051/gal.	
  i?a. Descriptors *Disinfection,  *Chlorination, *Water  Pollution Treatment,
treatment Facilities,  *Storm Runoff, Coliforms,  Operation and Maintenance
Plastic Pipes, Oxidation-Reduction Potentials,  Centrifugal Pumps,
Concrete Lined Canals,  Protective Coatings, Sodium Compounds, Storage
Tanks

  17b. Identifiers
*Hypochlorination, *Sodium Hypochlorite Manufacturing Facilities, *Lined
Steel Storage Tanks,  *New Orleans, Hypochlorite Feeding Facilities,
Residual Chlorine Analyzers
    COWRR Field & Groun   Q5F
    /• vi'-ibilitv          • 19. Security Class.
                        "Repot }

                      •a S*. 'ityC' s.
                        (Piee)
ZL  No. of
   Pages

 ».  Pi. •!
Send To:


WATER RESOURCES SCIENTIFIC INFORMATION CENTER
US. DEPARTMENT OF THE INTERIOR
WASHINGTON. D. C. 2O24O

-------