United States
                             Environmental Protection
                             Agency
Office of
Solid Waste and
Emergency Response
Publication:  9200.2-15FS
March 1993
        v>EPA      An Overview of the  Outyear
                           Liability Model  (OLM)
Office of Emergency and Remedial Response
Office of Program Management 5201G
                           Quick Reference Fact Sheet
      In 1980, Congress passed a law called the Comprehensive Environmental Response, Compensation, and Liability Act
      (CERCLA), commonly called Superfund. The Superfund Amendments and Reauthorization Act (SARA) was passed
      by Congress in 1986 to update and improve the Superfund law. In 1991, Congress extended Superfund's authority
      through 1994. The law authorizes the Federal government to respond directly to releases, or threatened releases, of
      hazardous substances that may endanger public health, welfare or the environment. Legal actions can be taken to force
      parties responsible for causing the contamination to clean up those sites or reimburse the Superfund Program for the costs
      of cleanup. If those responsible for site contamination cannot be found or are unwilling to clean up a site, EPA can use
      monies from the Superfund Program for clean-up activity.

      The name "Superfund" refers to the trust fund that was set up under CERCLA to finance these clean up actions. CERCLA
      established a $1.6 billion fund which would be collected from taxes on crude oil and commercial chemicals. When
      Superfund was reauthorized by Congress in 1986, the fund was increasedby $8.5 billion throughFY 1991. These monies
      are made available  to the Superfund directly from excise taxes on petroleum and feedstock chemicals, a tax on certain
      imported chemical  derivatives, an environmental tax on corporations, appropriations made by Congress from general
      tax revenues, and any monies recovered or collected from parties responsible for site contamination. Reauthorization
      of the Superfund was incorporated into the 1991 Budget legislation passed by Congress and signed by the President on
      November 5,1990. This authority continues funding under the existing Program structure through September 30,1994.

      EPA has placed 1,275 sites on the National Priority List (NPL). These NPL sites are targeted for cleanup under the
      Superfund. However, this is not a complete list. Site discoveries continue, and EPA estimates that, while some sites will
      be deleted after lengthy cleanups, the NPL will continue to grow. The average Remedial Action (RA) cost is $ 13.2 million
      per operable unit and the average number of operable units per site is 1.8. The lead distribution for non-federal facility
      Remedial Investigation/Feasibility Studies (RI/FSs) is 65% for Responsible Party (RP) leads and 35% for Fund-leads.
      The lead distribution for non-federal facility RAs is 70% for RP-leads and 30% for Fund-leads. The average  cost for
      adding a Fund-lead site to the NPL is $27 million.
      INTRODUCTION

      The Outyear Liability Model (OLM) was developed to
      assist the Environmental Protection Agency (EPA) Office
      of Emergency and Remedial Response (OERR) in
      projecting activity levels, costs, and resource needs
      associated with the Superfund Program. Developed for
      an IBM PC or PC-compatible computer using Lotus 1-2-
      3, Version 3.1, the model is a sophisticated management
      tool which interfaces with other EPA planning systems to
      project these costs and resources. Designed with a high
      degree of flexibility, the OLM permits the user to vary
      assumptions and assess the impact of policy changes on
      total Program obligations and resource needs.
 The OLM combines historical trends and Program activity
 levels with expected Program conditions to develop a
 comprehensive analysis of Superfund Program resource
 and funding needs. Superfund events currently planned
 are incorporated into the model through its interface with
 the  Comprehensive  Environmental  Response,
 Compensation, and Liability Information System
 (CERCLIS), the planning and tracking system for the
 Superfund Program.  Other events not yet planned are
 projected, using planning assumptions about the NPL size
 and the rate at which RI/FS projects will be initiated.

 The OLM incorporates the major factors affecting site-
 level NPL response costs, based on modeled sequences of
 events related to NPL sites  and  assumptions for
                                                                           Printed on Recycled Paper

-------
approximately 100 variables (e.g., activity costs, activity
durations, etc.) for which default values are supplied. The
model allows users to modify these assumptions, either
individually or in combination, to see how such changes
may affect NPL costs and accomplishments. Thus, while
the OLM does not estimate all costs automatically, the
many variables give the user considerable flexibility to
explore a number of possible funding scenarios.

Using the model's default variables produces a "baseline"
liability estimate. In general, this baseline estimate reflects
the estimated  cost  of  implementing  Superfund
Comprehensive Accomplishment Plan (SCAP) planning
guidelines and past RA cost behavior. After creating this
baseline estimate, the user can modify selected variables
to approximate general programmatic changes to see how
they may affect outyear liabilities. For example, the user
can use the OLM to change:

     •   Overall planned Superfund budget amounts;
     •   The number of planned activities;
     •   Program policies (e.g., more treatment,  more
        enforcement, etc.).

On the other hand, the OLM cannot estimate directly or
adjust for NPL site-level activities or changes in public
attitudes or concerns.  To approximate factors  such as
these within the realm of the model, the user must modify
related variables that are contained within the model.

The OLM system concept is illustrated in Exhibit 1. As
can be seen  in the exhibit, the concept discusses three
components:   inputs to the Model, the Model's
computational logic, and outputs from the Model. These
components are briefly discussed below.

INPUTS TO THE MODEL

The inputs that provide the basic foundation of the Model
are: CERCLIS, Superfund Budget Projections, SCAP,
and user input variables.

    •   CERCLIS: CERCLIS is a major source of data
        for  the OLM. It provides information about
        planned and actual  activities at hazardous
        substance release sites, including lead for each
        activity and planned starts, completions, and
        obligations forRI/FSs, Remedial Designs (RDs),
        and RAs.

    •   Superfund Budget Projections: As part of the
        annual EPA budgetprocess, the Agency estimates
        its  overall expected costs and  Full-Time
        Equivalents (FTEs) for the Superfund Program
        for  the budget year.  The  OLM uses certain
        planning assumptions from the budget process,
        including expected activity outputs (e.g., number
        of RA starts), pricing factors, and FTE pricing
        factors. The Superfund budget projections also
        include planned funding for other EPA offices
        (such  as the  Office  for Research  and
        Development) and other Federal agencies and
        departments  (such  as  the  Coast Guard) that
        provide assistance to the Superfund Program.

        SCAP:  The Superfund Comprehensive
        Accomplishments Plan (SCAP) contains the basic
        planning  assumptions  for coming fiscal year
        activities, including project durations and costs.
        It is a central planning tool used by EPA's
        Headquarters and Regional  offices to schedule
        and estimate NPL site events. Given that these
        factors represent EPA's best  estimates for
        Superfund events, they  also  have been
        incorporated into the OLM to provide a baseline
        estimate for the Program.

        User Inputs:  These site condition  variables
        provide the flexibility in the OLM that allows the
        user to model possible Program scenarios. These
        variables include:

        -   Activity Durations  and Pricing Factors
            (Exhibit 2);
        -   NPL Additions and Activity Start Ceilings;
        -   Distribution of Activity (Exhibit 3).

MODEL LOGIC

Using these data inputs, the  OLM reflects  the chain of
events that occur during the course of a site's evaluation
                     and cleanup under the Superfund
                     Program. To accomplish this, the
                     Model was designed with two
                     primary  components:  activity
                     flows and unit activity  costs.
                     Working with these components,
                     the user can apply different cost,
                     FTE,  and policy assumptions to
                     see how such changes  affect
                     Superfund costs.   The activity
                     flows and unit activity costs are
                     outlined  below.
        Activity Flows: Superfund activities have been
        broken down into basic chronologies  called
        "activity flows," which track all remedial,
        enforcement, and removal  activities  that can
        occur at a site. The distribution of these activity
        flows is  dependent  on the lead  distribution
        variables. The Model assumes, at the beginning
        of the Superfund pipeline, that  RI/FSs are
        conducted with a 35% Fund and 65% PRP lead
        division; meanwhile, at the end of the pipeline,
        RAs are conducted with a 30% Fund  and 70%
        PRP  lead distribution.  These flows result in
        project counts for each quarter tracked by the
        Model.

-------
                                               EXHIBIT 1
                              Outyear Liability Model System Concept
         MODEL INPUTS
          ACTIVITY STARTS
        ACTIVITY   FY90 FY91
        NPL ADD.
      VFUNDRI/FS
           25
           78
Q.
3
 L  _
           SITE PROFILES
 ACTIVITY DURATIONS
 LEAD DISTRUBITION
 SUBSEQUENT OU %
  BUDGET PRICING
     FACTORS
EVENT
       RI/FS    FTE  $$$
      VRD      	
             BUDGET
           PROJECTIONS
         OTHER FEDERAL
         AGENCIES &
         EPA OFFICES
                                                                   SCENARIO AND LIABILITY REPORTS
       LIABILITY
        MODEL
                                                                              LIABILITY TO
                                                                              COMPLETE
                                                                             EXISTING SITES
                                                                              SCENARIO(S)
    SYSTEM LOGIC
COMPUTE OBLIGATIONS BY
YEAR TO COMPLETE CURRENT
SITES
COMPUTE OBLIGATIONS BY
YEAR TO COMPLETE
ADDITIONAL SITES (VARYING
BUDGET PRICING FACTORS
POSSIBLE)
COMPUTE ADDITIONAL
OBLIGATIONS (Removal,
preremedlal, enforcement, other
Federal agencies, etc.)
COMPUTE FTE AND
INTRAMURAL RESOURCE
NEEDS
COMPUTE TOTAL OBLIGATION
NEEDS BY FISCAL YEAR
                                                                         WHAT IF
                                                                        ANALYSES
                                    ADDITIONAL SITES
                                    INCREASE RP LEADS j
                                  V REDUCE RA COST
     ACTIVITY
    SUMMARY
     REPORTS
                                                                          BUDGET REPORTS
       BUD1
ACTIVITY  FY94 FY95
PERSONNEL $   $
                                                                         SPECIAL REPORTS
                                                                    ANNUAL REPORT TO
                                                                       CONGRESS
NOTE: The numbers in this exhibit are for illustrative purposes only. They may vary according to user input.

-------
     •   Unit Activity Costs: The Model calculates total
        costestimates by apply ing pricing andFTE factors
        to all removal, pre-remedial, remedial, and
        enforcement project counts that stem from the
        activity flows.  The only exception is for RAs,
        where pricing factors are applied separately.

The sources of the pricing and FTE factors include empirical
analyses of cost data and SCAP guidelines outlined in the
current Program Management Manual. These factors are
applied to each project quarterly and by stage (i.e., start,
on-going, or complete).
MODEL OUTPUTS
                         The Model's output reports
                         consist   of  Liability,
                         Budgetary and  Scenario
                         Reports.  These reports are
                         generated in both graphical
                         and tabular forms.
    •   Liability Reports:  These reports contain the
        OLM's estimates of the Superfund Program's
        costs (e.g., annual costs, total costs to complete
        existing NPL), duration (e.g., how long to
        complete existing NPL), and number of site
        activities (e.g., site cleanups by year or funding
        level).

    •   Budgetary Reports: These reports contain the
        OLM's estimates of costs in the format of the
        annual Superfund  budget (e.g., BUD reports)
        and provide support for development of OERR's
        "Annual Report to Congress on Implementation
        of the Superfund Program."

    •   Scenario Reports: These reports contain the
        OLM's analyses of "What If?" alternative budget,
        liability, and policy scenarios, such as estimating
        the Superfund costs if additional sites are added
        to the NPL, or if the Program benefits from more
        effective enforcement measures.

ONGOING ACTIVITIES
        reflecting the Program over the short term.  In
        addition, while the model allows for user-inputs
        on almost all Program conditions, Model users
        often rely  on default values for these inputs.
        These default values, such as the value for RA
        costs,  are continuously analyzed  and updated
        where  necessary to  improve  the  Model's
        predictive capabilities.

        System Logic Enhancements:   Changes  in
        Model user's needs can sometimes result in needed
        enhancements  in system logic.  Recent
        enhancements have included variable activity
        durations and more  extensive activity  level
        capping capabilities. Future enhancements might
        include customized reporting  capabilities,
        increased graphical user interface capabilities,
        and other enhancements that continue to increase
        Model flexibility and user-friendliness.

This overview of the Outyear Liability Model (OLM) is
provided by the Office of Program Management (OPM).
If you have any questions on  the enclosed information,
please feel free to contact the  Program Development &
Budget Staff at (703) 603-8750.
of these steps include:
                         Maintaining the OLM as a
                         reliable  and  consistent
                         estimating tool requires  a
                         continuous program of
                         updating and documenting
                         the system to respond to the
                         dynamic  and  changing
                         Superfund Program. Some
        Model Data Analyses:  As activity levels in
        CERCLIS change, these changes are reflected
        periodically in the OLM.  These updates are
        necessary to ensure that the model is accurately

-------
                              EXHIBIT 2
             Activity Durations & Pricing Factors Default Values
         ACTIVITY
DURATION (quarters)    COST ($000)
PA
SI
ESI
NPL Proposed
NPL Final
REMOVAL
RI/FS
RD
RA

REMOVAL PRP SEARCH
REMOVAL NEGOTIATIONS
REMOVAL OVERSIGHT

PRP SEARCH (NPL) - start
PRP SEARCH (NPL) - ongoing
RI/FS NEGOTIATION
RP RI/FS OVERSIGHT - start
RP RI/FS OVERSIGHT - ongoing
RD/RA NEGOTIATIONS
RP RD OVERSIGHT
RP RA OVERSIGHT
                           100
                           600
                           750
                           700
                          13200
NOTE: The numbers in this exhibit are for illustrative purposes only. They may vary according to
user input.

-------
                                                                              EXHIBIT 3
                                                                      Distribution of Activity
                            BAND1
                                                           BAND 2
                                                                                                                  BAND 3
                                                                                                        BAND 4
                                     I RJNDPA   |  10
                                     RJNDRD      10
                                       _L
                 ORPHAN SITE I  10  [—| FIND Rlf S |   10
a\
NONORPWNSITES    90
             KEY
                                   »OFSITES
                                                                    SEC.106REFERALS     50
                                                           RJNDRUFS    25
*\S          I  FPflA

                                                                   FD/RANB30T.  90
                                                           PRPRI/FS     65
                                                                    NOSEC.106REFERALS  40
                                                                                                      NO SEC.106 SETTLEMENT      5

-------