United States
          Environmental Protection
          Agency
            Office of Emergency and
            Remedial Response
            Washington DC 20460
&EPA
          Superfund
                        OSWER Directive 9355.0-4A
Superfund Remedial
Design and Remedial
Action Guidance

-------
         UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

                     WASHINGTON. D.C. 20460
                                                      OFFICE OF
                                            SOLID WASTE AND EMERGENCY flESPONSE
                                                       9355.0-4A
      SUPERFUND REMEDIAL DESIGN AND REMEDIAL ACTION GUIDANCE
     The Superfund Remedial Design and Remedial Action Guidance
was first issued in February 1985, by the Environmental Protection
Agency's (EPA) Office of Emergency and Remedial Response  (Directive
9335.0-4).  This document provides assistance to EPA, States, U.S.
Army Corps of Engineers, and private parties who plan, administer
and manage remedial design (RD) and remedial action  (RA)  projects
to assure RD and RA projects are performed consistently and
expeditiously.

     This revised June 1986 version of the Superfund RD and RA
Guidance (Directive 9335.04-A) is being issued to reflect program
changes that have occurred since the document was first issued.
Sections of this document that have significant changes are listed
below:

     Section 2.4.5   Major Design Changes.

     Section 3.3.3   Contingency Funds for Change Orders  and
                     Claims-State Lead Remedial Action.

     Section 3.4.2   Prefinal Inspection.

     Section 3.4.3   Final Inspection and Certification.

     Section 3.5.2   Operational and Maintenance.

     Appendix B.1.6  Selection of RCRA Facilities.

     References

     The February 1985 version of this document (9355.0-4) is
superseded by the June 1986 version (9335.0-4A).  This document
will be updated as necessary.

-------
                                OSWER Directive 9355.0-4A
      SUPERFOND  REMEDIAL DESIGN AND






         REMEDIAL ACTION GUIDANCE
                June  1986
Office of Emergency and  Remedial  Response



   U.S. Environmental  Protection  Agency



         Washington, D.C.   20460

-------
                                                          OSWER Directive 9355.0-4A
                      TABLE   OF   CONTENTS
1.   INTRODUCTION
                                                                      Page
                                                                     Number
     1.1   Purpose of the Guidance Document
     1.2   Overview of the Guidance Document
1-1
1-1
2.   REMEDIAL DESIGN
2-1
     2.1   Architect/Engineer Selection Activities                    2-1

           2.1.1  Federal Lead Remedial Design                        2-1
           2.1.2  State Lead Remedial Design                          2-4

     2.2   Design Initiation                                          2-5

           2.2.1  Remedial Planning  Information                       2-5
                  Provided to Lead Design Party

                  2.2.1.1  Record of Decision/Enforcement             2-6
                           Decision  Document  and Final Remedial
                           Investigation/Feasibility Study Report

                  2.2.1.2  Pre-Design Report                          2-6

                  2.2.1.3  Technical Transfer Briefing                2-6
                                   iii

-------
OSWER Directive 9355.0-4A
           2.2.2  Type of Agreement                                   2-6

                  2.2.2.1  Federal Lead Remedial Design               2-9
                  2.2.2.2  State Lead Remedial Design                 2-9
                  2.2.2.3  Responsible Party Remedial Design          2-9

           2.2.3  Architect/Engineer Conflict of Interest           2-11

     2.3   Elements To Be included in Statement of Work (SOW)       2-11

           2.3.1  Plans and Specifications                          2-13
           2.3.2  Additional Studies                                2-15
           2.3.3  Operations and Maintenance Plan                   2-15
           2.3.4  Quality Assurance Project Plan                    2-15
           2.3.5  Site Safety Plan                                  2-16
           2.3.6  Architect/Engineer Services During Construction   2-16

     2.4   Design Reviews and Approvals                             2-17

           2.4.1  Preliminary Design                                2-17

                  2.4.1.1  Environmental Review                     2-18
                  2.4.1.2  Technical Review                         2-18

           2.4.2  Intermediate Design                               2-18

           2.4.3  Prefinal Design                                   2-18

                  2.4.3.1  Environmental Review                     2-19
                  2.4.3.2  Technical Review                         2-19

           2.4.4  Final Design                                      2-20

                  2.4.4.1  Extent of Review                         2-20
                  2.4.4.2  Final Approval                           2-20
                  2.4.4.3  Plan-In-Hand Review          •           2-20

                                      iv

-------
                                                      OSWER Directive 9355.0-4A
      2.4.5  Major Design Changes                              2-21
      2.4.6  Value Engineering                                 2-22

2.5   Permits, Approvals and Site Access                       2-22

      2.5.1  Permits and Approvals                             2-22

             2.5.1.1  Requirements                             2-23
             2.5,1.2  Responsibilities                         2-23

      2.5.2  Site Access                                       2-23

             2.5.2.1  Requirements                             2-24
             2.5.2.2  Responsibilities                         2-25

2.6   Community Relations Activities                           2-25

      2.6.1  Objectives                                        2-25
      2.6.2  Implementation Activities and Techniques          2-26
      2.6.3  Responsibilities                                  2-27

2.7   Cost Estimates for Construction                          2-27

      2.7.1  Estimated Cost of Project                         2-27

      2.7.2  Supervision and Administration (S&A) and.         2-28
             Engineering and Design (E&D) During Construction

      2.7.3  Contingency Limits                                2-28

             2.7.3.1  Bid Contingency                          2-28
             2.7.3.2  Changes Orders and Claims                2-29

      2.7.4  Total Cost Estimate for Remedial Action           2-29
             Agreements

-------
OSWER Directive 9355.0-4A
  3.   REMEDIAL ACTION                                                 3-1

       3.1   Remedial Action Initiation                                3-1

             3.1.1  Federal Lead Remedial Action                       3-1
             3.1.2  State Lead Remedial Action                         3-1
             3.1.3  Responsible Party Remedial Action                  3-3
             3.1.4  Conflict of Interest                               3-3

       3.2   Procurement Activities                                    3-3

             3.2.1  Advertise for Bids                                 3-6
             3.2.2  Site Inspection                                    3-6
             3.2.3  Review of Bid Documents                            3-6
             3.2.4  Bid Protests                                       3-7

       3.3   Monitoring and Oversight                                  3-7

             3.3.1  Inspections                                        3-7

                    3.3.1.1  Full Time Inspector                       3-8

                    3.3.1.2  Compliance with Environmental             3-8
                             Requirements

                    3.3.1.3  Compliance with Other Contract            3-8
                             Requirements

                    3.3.1.4  Review of Contractor Reports              3-9

             3.3.2  Progress Reports to EPA                            3-9

             3.3.3  Contingency Fund for Change Orders and Claims     3-10

                    3.3.3.1  Federal Lead Remedial Action             3-10
                    3.3.3.2  State Lead Remedial Action               3-11

                                      vi

-------
                                                        OSWER Directive 9355.0-4A
3.4   Remedial Action Completion and Acceptance                3-11

      3.4.1  Prefinal Construction Conference                  3-11

             3.4.1.1  Participating Parties                    3-12
             3.4.1.2  Suggested Agenda Items                   3-12

      3.4.2  Prefinal Inspection                               3-13

             3.4.2.1  Inspecting Parties                       3-13
             3.4.2.2  Extent of Inspection                     3-13
             3.4.2.3  Prefinal Inspection Report               3-13

      3.4.3  Final Inspection and Certification                3-14

             3.4.3.1  Inspecting Parties                       3^14
             3.4.3.2  Extent of Inspection                     3-14
             3.4.3.3  Remedial Action Report                   3-15
                                                                     v's

      3.4.4  Acceptance of Completed Project                   3-15

3.5   Site Closeout                                            3-16

      3.5.1  Deletion of Site from NPL                         3-16

      3.5.2  Operation and Maintenance                         3-16

             3.5.2.1  Operation and Maintenance Assumption     3-17
             3.5.2.2  Operation and Maintenance Report         3-17
                                 vn

-------
OSWER Directive 9355.0-4A
  Appendix A - Sample  USACE  Work  Assignments and Interagency            A-l
               Agreements

  Appendix B - Elements  to be Included in the Remedial Design           B-l
               Statement of  Work

  Appendix C - List  of Acronyms                                         C-l

  Appendix D - Glossary  of Terms                                         D-l

  REFERENCES
                                    vm

-------
                                                          OSWER Directive 9355.0-4A
                      INDEX   OF   EXHIBITS
                                                                      Page
                                                                     Number
EXHIBIT
NUMBER                     TITLE

 1-1       Remedial Process for Fund Lead Sites                       1-2

 2-1       Federal Lead Remedial Design Process                       2-2

 2-2       USACE Regional Assignments for Superfund Projects          2-3

 2-3       Suggested Outline for Pre-Design Report                    2-7

 2-4       State Lead Remedial Design Process                        2-10

 2-5       Responsible Party Lead Remedial Design Process            2-12

 3-1       Federal Lead Remedial Action Process                       3-2

 3-2       State Lead Remedial Action Process                         3-4

 3-3       Responsible Party Lead Remedial Action Process             3-5

 B-l       Basic Elements of Operation and Maintenance Plan           B-7
                                    IX

-------
                                                           OSWER Directive 9355.0-4A
                              1.  INTRODUCTION
1.1  Purpose of the Guidance Document

     This guidance document has been developed to assist agencies and
parties who plan, administer, and manage remedial design (RD) and remedial
action (RA) at Superfund sites.  The guidance document pertains to
Fund-financed RD/RA (i.e., Federal lead and State lead) and responsible
party RD/RA, and provides procedural guidance to be followed in order to
ensure that RD/RA is performed properly, consistently, and expeditiously.

     The guidance document has been developed primarily for use by:

           Environmental Protection Agency Remedial Project Managers (EPA
           RPM)

           State Project Officers

           U.S. Army Corps of Engineers (USAGE) personnel

           Responsible parties.

Exhibit 1-1 highlights the focus of the document within the context and
sequence of activities required to complete an entire remedial response.

1.2  Overview of the Guidance Document

     This guidance document has been organized to reflect the general
sequence of events that occurs prior to, during, and after remedial design
and remedial action at a Superfund site.  Remedial design activities are
presented in Chapter 2, and remedial action activities are presented in
                                     1-1

-------
OSWER Directive 9355.0-4A
    EXHIBIT 11
REMEDIAL PROCESS
               DISCOVERY
                 AND
             INVESTIGATION
                                                                    SUBJECT OF
                                                                  RDIRA GUIDANCE
                                                                        COST
                                                                       RICOVHY
                                                                        1CTIOI
                                             1-2

-------
                                                          OSWER Directive 9355.0-4A
Chapter 3.  The majority of both chapters pertains to Fund-financed and
responsible party projects, however, some sections apply only to
Fund-financed projects and are noted accordingly.  Common information is
consolidated for discussion, and where necessary separate subsections are
provided for Federal lead, State lead, and responsible party RD/RA.
Additional guidance on oversight of responsible party RD/RA activities will
be provided by EPA in the future.

     The discussion on responsible party RD/RA pertains only to those
Superfund sites where EPA has entered into a settlement agreement with the
responsible party(ies), and no trust fund monies are involved in the RD/RA.
If trust fund monies are involved, different procedures to be followed will
be  provided in the future by EPA.

     RD/RA conducted by other Federal agencies is not addressed directly in
this document.  The forthcoming Federal Facilities Program Manual will
tailor the information in this document to address Federal Agency RD/RA
activities.
                                     1-3

-------
                                                           OSWER Directive 9355.0-4A
                             2.  REMEDIAL DESIGN
2.1   Architect/Engineer Selection Activities

       Activities involved in selecting an architect/engineer (A/E) firm for
remedial design will be dependent on the lead party.  A/E selection
activities pertaining to Fund-financed remedial design are discussed below.

2.1.1  Federal Lead Remedial Design

       Exhibit 2-1 diagrams the Federal lead remedial design process.  In
order to expedite the design phase, A/E selection activities may be
initiated prior to Record-of-Decision (ROD) approval if deemed appropriate
by the EPA RPM and EPA headquarters (HQ).  The EPA Regional office will
issue a work assignment consistent with the standing Interagency Agreement
(IAGJ to USAGE Missouri River Division (MRD) to initiate Phase I design
activities based on the draft feasibility study (FS).  The EPA RPM will
forward copies of the executed work assignment to EPA HQ and USACE HQ.

       The map in Exhibit 2-2 shows the USACE Regional  assignments for
Superfund Projects.  Under MRD supervision, the appropriate USACE Design
District (i.e. Kansas City or Omaha) will perform the following Phase I
design activities to retain an A/E firm for the engineering design:

             Synopsize requirements in Commerce Business Daily (CBD)

             Develop A/E pre-selection list

             Contact A/E firms on the pre-selection list to ascertain
             interest in project
                                    2-1

-------
OSWER Directive 9355.0-4A
                                                            EXHIBIT 21
                                          FEDERAL  LEAD REMEDIAL  DESIGN PROCESS
                          COPIES TO
                           EPA HO
                          USAGE HO
  t
ACTIVITIES PRIOR TO
  ROD APPROVAL
  ARE OPTIONAL IN
ORDER TO EXPEDITE
 DESIGN INITIATION
                                             EPA REGION ISSUES
                                             WA FOR INITIATING
                                               PHASE I DESIGN
                                                ACTIVITIES TO
                                                 USACEMRD
                                                    EPA RPM & STATE
                                                 PROCESS STATE LETTER
                                                     OF REQUEST OR
                                                  AMEND  EXISTING MOU
 EPA REGION PREPARES
  DRAFT SITE SPECIFIC
DESIGN IAG CONCURRENT
   WITH EPA REGION
 SUBMITTING FINAL ROD
 PACKAGE FOR APPROVAL
                                     USACE-MRD
                                   DESIGN DISTRICT
                                                                                     -SYNOPSI2EREQMTS. INCBO
                                                                                     -DEVELOP AIE PRESELECTION LIST
                                                                                     -CONTACT AIE FIRMS TO ASCERTAIN INTEREST
                                                                                     -DEVELOP AIE SELECTION LIST WIN. 3 FIRMS)
                                                                                     "-SELECT AIE FIRM (TENTATIVELY)
                                              SELECTION OF REMEDY BY EPA
                                                     ROD APPROVAL
                                                                   REMEDIAL PLANNING
                                                                      INFORMATION
                                                                      PROVIDED TO
                                                                     USACE MRD BY
                                                                        EPA RPM
      ACRONYMS KEY

      RPM       REMEDIAL PROJECT MANAGER
      USAGE-MOD   U.S. ARMY CORPS OF ENGINEERS -
                 MISSOURI RIVER DIVISION
      IAG        INTERAGUCV AGREEMENT
     . ROD       RECORD OF DECISION
      SOW       STATEMENT OF WORK
      WA        WORK ASSIGNMENT
      CBD       COMMERCE BUSINESS DAILY
      •PI        NATIONAL PRIORITIES LIST
      MOU       MEMORANDUM OF AGREEMENT
                                                    DESIGN DISTRICT
                                                    ISSUES SOW FOR
                                                   DESIGN TO A|E FIRM
                                              AIE FIRM DEVELOPS
                                               DESIGN PACKAGE
                                               BASED ON SOW
                                          DESIGN REVIEWS SCHEDULED
                                              AT PRE DETERMINED
                                          INTERVALS (I.E.. PRELIMINARY.
                                         INTERMEDIATE. PREFINAL. FINAL!
                          OVERSIGHT BY EPA RPM
                                                USACE MRD APPROVES AND
                                                  ACCEPTS DESIGN WITH
                                                 CONCURRENCE FROM EPA
                                                   REGION AND STATE
                                                            2-2

-------
                                                              EXHIBIT 22

                                           USAGE REGIONAL ASSIGNMENTS FOR SUPERFUND PROJECTS
ro

CO
ESJ8%I Omaha District
                     Kansas City

                     District
                                                                                                                       o
                                                                                                                       CO

                                                                                                                       m
                                                                                                                       3J

                                                                                                                       O

                                                                                                                       3
                                                                                                                       a
                                                                                                          to
                                                                                                          u
                                                                                                          01
                                                                                                          01

-------
OSWER Directive 9355.0-4A
             Develop A/E selection list (at least 3 firms)

             Select A/E firm (internal tentative selection only).

These activities will take approximately 10 weeks to complete.  Results and
progress will be coordinated by the USACE-MRD Design District with the EPA
RPM.

       The tentative A/E selection will not be finalized by EPA, and no
further action will be taken by USAGE, .until the ROD is approved and USACE
has determined that the A/E is qualified to design the approved remedy.  A
sample standing IAG and Phase I design work assignment are included in
Appendix A (Sample No. 1)'.

       The EPA Region, with concurrence from EPA HQ, may request the USACE
to use one of the EPA remedial planning contractors as the A/E firm for RD
in limited situations.  These situations could include:

             Projects with a low RD cost ($50,000 - $100,000)

             Projects where it is necessary to expedite the design phase and
             RA initiation.

2.1.2  State Lead Remedial Design

       In order to expedite the design phase,  EPA encourages States to
retain the same A/E firm for RD and subsequent RA support activities that
provided services for the RI/FS.  To accomplish this, EPA recommends that
the subagreement with the A/E firm contain an option for RD and RA support
activities.  A class deviation from limited requirements of 40 CFR 33 has
been approved by EPA Grants Administration Division to allow States to
retain the same A/E firm for subsequent activities if the option approach
was not used.  In most cases the State will have an A/E firm available for
design activities, and no special  A/E selection activities will  be
                                    2-4

-------
                                                            OSWER Directive 9355.0-4A
required.  The State officials and the RPM should refer to the following EPA
guidance documents for specific information and procedures:

             State Participation in the Superfund Program, Volume I,
             February 1984 as amended (hereafter referred to as the State
             Manual, Volume I)

             State Participation in the Superfund Program, Volume II:  State
             Procurement Under Superfund Remedial Cooperative Agreements,
             March 1986 (hereafter refered to as the State Manual,
             Volume II).

To be consistent with EPA policy, attention should be given to the
utilization of minority business enterprises and women's business
                                                          *
enterprises.

2.2  Design Initiation

       Following selection of a remedy and Record of Decision
(ROD)/Enforcement Decision Document (EDO) approval by the designated EPA
official, action must be taken to initiate design activities.  The lead
design party shall ensure the design package is developed consistent with
the approved ROD/EDO and applicable CERCLA policy and procedures.  Remedial
planning information to be provided to the lead design party and the type of
agreement used to initiate design are discussed below.

2.2.1  Remedial Planning Information Provided to Lead
       Design Party

       When the lead design party is different than the lead RI/FS party,
the EPA RPM must provide remedial planning information to the appropriate
design party (i.e. USACE, State, responsible party) in order to initiate
design.  If the lead party does not change from RI/FS to RD, this is not
required since the lead party should already have the information.
                                    2-5

-------
OSWER Directive 9355.0-4A
2.2.1.1  Record of Decision/Enforcement Decision Document
         and Final Remedial Investigation/Feasibility Study
         (RI/FS) Report

       Mandatory information to be provided to the lead design party
includes a copy of the approved ROD/EDO and the final RI/FS report(s).  This
information should be forwarded as soon as possible after ROD/EDO approval
in order to facilitate initial design activities.

2.2.1.2  Pre-Design Report

       A Pre-Design Report shall be prepared by the lead RI/FS party and
provided to the lead design party.  The objective of the Pre-Design Report
is to describe the engineering parameters and institutional concerns of the
selected remedy,*and package all pertinent project information for
effectively transferring the project to the lead design party.  The
Pre-Design Report replaces the conceptual design task of the FS.  The
Pre-Design Report should be completed within 2 weeks following remedy
selection, and the cost should be limited to approximately 5 percent of the
cost of the feasibilty study.  A suggested outline for the Pre-Design Report
is presented in Exhibit 2-3.

2.2.1.3  Technical Transfer Briefing

       The EPA RPM should schedule a technical transfer briefing between
lead design party and the lead RI/FS party.  The purpose of this briefing
would be to facilitate project transfer and resolve any outstanding issues
or questions.

2.2.2  Type of Agreement

       The type of agreement used to initiate design is dependent on the
party that is responsible for design.  For Federal lead remedial design,
action is initiated through an Interagency Agreement (IAG) with the USACE.
For State lead remedial design, action is initiated through a cooperative
                                    2-6

-------
                                                       OSWER Directive 9355.0-4A
                                  EXHIBIT 2-3
                    SUGGESTED OUTLINE FOR PRE DESIGN REPORT
1.  Site Description

2.  Summary of Selected Remedy

         Description of remedy & rationale  for  selection
         Performance Expectations
         Site topographic map & preliminary layouts
         Preliminary design criteria &  rationale
         Preliminary process diagrams
         General operation and maintenance  requirements
         Long-term monitoring requirements

3.  Summary of Remedial Investigation and Impact  on  Selected  Remedy

         Field studies
         (Air, surface water, ground water,  geology)

         Laboratory studies
         (Bench scale, Pilot scale)

4.  Design/Implementation Precautions

         Special technical problems
         Additional engineering data required
         Permits & regulatory requirements
         Access, easements, rights-of-way
         Health & safety requirements
         Community relations activities
                                2-7

-------
OSWER Directive 9355.0-4A
                             EXHIBIT 2-3 (CONTINUED)
                     SUGGESTED OUTLINE FOR PRE DESIGN REPORT
  5.   Cost Estimates & Schedules


           Implementation cost estimate  (Order of  Magnitude, + 50%/- 30%)


           Preliminary annual O&M cost estimate and duration


           Project schedule  (design,  construction,  permits & access)


  6.   Appendices


           Reports, data summaries, etc.
                                     2-8

-------
                                                           OSWER Directive 9355.0-4A
agreement (CA) with the State.  For responsible party remedial design,
action is initiated  through a document of settlement with the responsible
party(ies) (i.e. judicial consent decree or administrative order on consent).

2.2.2.1  Federal Lead Remedial Design

       To initiate design at a Federal lead site, the EPA RPM works with the
State to process a new State Letter of Request or amends the existing MOD to
include the remedial design if remedial design was not covered in the
original MOU.  The RPM and the State officials should refer to the State
Manual, Volume I, for specific information.

       Once the State Letter or MOU is processed, the RPM shall coordinate
with USACE-MRD and establish necessary funding for design.  The EPA Region
should prepare a draft site-specific design IAG with USACE-MRD, concurrent
with submitting the final ROD package for approval.  After ROD approval, the
EPA Region should finalize the design IAG with USACE-MRD.  The RPM should
forward copies of the executed design IAG to EPA HQ and USACE-HQ (DAEN
ECE-B).  USACE-MRD will initiate design activities through the appropriate
Design District.  The RPM will monitor all design activities.  The design
process is outlined in Exhibit 2-1.  A sample (sample No. 2) site-specific
design IAG is included in Appendix A.

2.2.2.2  State Lead Remedial Design

       To initiate design at a State lead site, the RPM works with the State
either to amend the existing CA or to develop a new CA for RD, or for both
RD and RA.  The RPM and State should refer to the State Manual, Volumes I
and II, for specific information and procedures.  Exhibit 2-4 graphically
depicts the State lead remedial design process.

2.2.2.3  Responsible Party Remedial Design

       To initiate design for a responsible party clean-up, EPA enters into
a settlement agreement (consent decree or administrative order on consent)
with the responsible party(ies).  The responsible parties will then proceed
                                    2-9

-------
OSWER Directive 9355.0-4A
                                            EXHIBIT 2-4
                              STATE LEAD REMEDIAL  DESIGN PROCESS
                                          STATE AND EPA RPM
                                           PREPARE/AMEND
                                         DRAFT CA CONCURRENT
                                           WITH SUBMITTING
                                          FINAL ROD PACKAGE
                                              TO EPA HQ
                                         SELECTION OF REMEDY
                                            ROD APPROVAL
                        STATE AND
                         EPA RPM
                        FINALIZE CA
                        REMEDIAL PLANNING
                       INFORMATION PROVIDED
                          TO STATE(ONLY
                       REQUIRED IF STATE WAS
                       NOT LEAD RI/FS PARTY)
                                          STATE ISSUES SOW
                                        FOR DESIGN TO A/E FIRM
ACRONYMS KEY

CA    COOPERATIVE AGREEMENT
RPM   REMEDIAL PROJECT MANAGER
ROD   RECORD OF DECISION
RI/FS   REMEDIAL INVESTIGATION)
        FEASIBILITY STUDY
SOW   STATEMENT OF WORK
WA   WORK ASSIGNMENT
                                                 I
                                          A/E FIRM DEVELOPS
                                           DESIGN PACKAGE
                                            BASED ON SOW
DESIGN REVIEWS SCHEDULED
AT INTERVALS (PRELIMINARY,
  INTEMEDIATE. PREFINAL.
         FINAL)
OVERSIGHT BY EPA RPM
                                           STATE APPROVES
                                       AND ACCEPTS DESIGN WITH
                                        CONCURRENCE FROM EPA
                                                 2-10

-------
                                                          OSWER Directive 9355.0-4A
ahead with the selection of a support contractor as needed to complete the
design, according to the schedule and conditions set forth in the document
of settlement.  The process for responsible party lead is shown in Exhibit
2-5.  This discussion pertains only to settlement agreements where no trust
fund monies are involved.  EPA will provide additional guidance on
responsible party oversight in the future.

2.2.3  Architect/Engineer Conflict of Interest

       In the process of selecting an A/E firm'for Fund-financed remedial
design, the State or EPA shall evaluate whether the prospective A/E has a
potential conflict of interest based on any potentially responsible party
(PRP) involvement at the site.  This could include the situation where a
current client may be a PRP at the site.  The EPA-Region should include a
provision in all CAs and lAGs regarding contracts with PRPs.  Appendix F of
the State Manual, Volume I, suggests specific language to be included in a
CA provision and suggests specific clauses to be included by the State in
any contract for services or construction.  lAGs should contain a provision
consistent with Appendix F, stating the USAGE will require interested
contractors to provide information and EPA will evaluate potential
conflicts.  The USAGE should include a provision equivalent to Appendix F in
the contract for RD.

2.3  Elements To Be Included In Statement Of Work (SOU)

       It is essential that the A/E firm retained to accomplish the design
for a specific remedial action have a clear understanding of the project
scope and subsequent required design documents.  The following elements of a
statement of work are intended as guidance in preparing site-specific A/E
instructions and apply to Fund-financed and responsible party remedial
design (RD).  The design Project Officer (PO) shall ensure that the
appropriate elements are addressed.  Further requirements for preparing the
A/E statement of work are presented in Appendix B.
                                    2-11

-------
OSWER Directive 9355.0-4A
                                    EXHIBIT 25
                RESPONSIBLE PARTY LEAD REMEDIAL DESIGN PROCESS
                                                SELECTION OF
                                                  REMEDY
                                               .EDO APPROVAL
                                               EPA ENTERS INTO
                                            SETTLEMENT AGREEMENT
                                              WITH RESPONSIBLE
                                                   PARTY
                                              REMEDIAL PLANNING
                                            INFORMATION PROVIDED
                                               TO RESPONSIBLE
                                                   PARTY
                                                     I
                                              RESPONSIBLE PARTY
                                               ISSUES SOW FOR
                                              DESIGN TO AIE FIRM
                         OVERSIGHT BY EPA RPM
                                              AfE FIRM DEVELOPS
                                               DESIGN PACKAGE
                                                BASED ON SOW
                                                     I
                                           DESIGN REVIEWS SCHEDULED
                                           AT INTERVALS (PRELIMINARY,
                                            INTERMEDIATE. PREFINAL,
                                                    FINAL)
      ACRONYMS KEY

      EDO   ENFORCEMENT DECISION DOCUMENT
      SOW   STATEMENT OF WORK
                                                     1
                         OVERSIGHT BY EPA RPM
   RESPONSIBLE PARTY
       APPROVES
AND ACCEPTS DESIGN WITH
 CONCURRENCE FROM EPA
                                           2-12

-------
                                                           OSWER Directive 9355.0-4A
2.3.1  Plans and Specifications

       The SOW for remedial design should require the A/E to prepare the
final construction plans and specifications to accomplish the remedial
action alternative as defined in the Record of Decision/Enforcement Decision
Document (ROD/EDO).  The specifications should include quality  assurance
provisions in all proposed work.  It should also state that the A/E shall
conduct the analysis and perform all work as required to prepare the
document package required for the remedial action.  (For further detail see
Appendix B).  In general, the plans and specifications portion  of the SOW
should include the following phases:

            Preliminary Design - The Scope of the preliminary design should
            address not less than 30% of the total design and shall be based
            on data furnished for the project.

            Intermediate Design - Complex project designs may necessitate
            review of the design documents between the preliminary and
            prefinal/final design phases.  At the discretion of the design
            PO a design review may be required at 60% completion of the
            design.

            Prefinal/Final Design - Prefinal/final design documents shall be
            submitted in- two parts.  The first submission shall  be at 90%
            completion of design (i.e., prefinal).  After approval of the
            prefinal submission, the A/E shall execute the required
            revisions and submit the final documents 100% complete with the
            reproducible drawings and specifications ready for bid
            advertisement.  This portion of the document package as
            submitted for prefinal/final design shall include, but not be
            limited to the design analysis, final construction drawings and
            specifications and cost estimate.
                                    2-13

-------
OSWER Directive 9355.0-4A
            Correlating Plans and Specifications  - The coordination between
            drawings and technical  specifications  is a principal  requirement
            of the A/E contract.   The coordination shall  be consistent with
            the submission requirements of the drawings and specifications
            through prefinal/final  design.

            Selection of Offsite  Resource Conservation and Recovery Act
            (RCRA) Facilities - The A/E shall  ensure compliance with CERCLA
            procedures for selecting an offsite RCRA facility and the
            requirements specified  in the ROD/EDO.  Refer to Procedures for
            Planning and Implementing Off-Site Response Actions,  memorandum
            from Jack McGraw, May 6, 1985 (reference 3),  for specific
            requirements.

            Compliance with the Requirements of other Environmental Laws -
            The A/E shall ensure  that the design  package submitted is in
            accordance with CERCLA  procedures on  compliance with  other
            environmental laws.  Refer to "CERCLA Compliance with Other
            Environmental Statutes," Appendix to  Preamble of the  National
            Oil and Hazardous Substances Pollution Contingency Plan; Final
            Rule,  (50 FR 2892.6), November 20, 1985 (reference 4), for
            additional information.  All applicable or relevant and
            appropriate requirements identified in the ROD/EDO shall be
            analyzed and incorporated into the design by the A/E.  The A/E
            shall  identify the controlling parameters as  required by such
            standards.

            Equipment startup and Operator Training - The AE shall prepare,
            and include in the technical specifications governing treatment
            systems, contractor requirements for  providing:   appropriate
            service visits by experienced personnel to supervise  the
            installation, adjustment, startup  and  operation of the treatment
            systems, and appropriate operational  procedures training once
            the startup has been  successfully accomplished.
                                   2-14

-------
                                                           OSWER Directive 9355.0-4A
2.3.2  Additional Studies

       Remedial actions involving the on-site treatment or disposal of
contaminated wastes (i.e., groundwater, lagoon wastes, etc.) may require
additional studies to supplement the technical data available from the RI/FS
activities so that the optimum treatment or disposal methods may be
determined.  Additional studies could include field work and/or bench and
pilot scale studies.  For futher detail see Appendix B.  The quality
assurance project plan and site safety plan from the RI/FS should be
tailored for any studies, as required.

       The fact that such studies will be performed should be explicitly
addressed in the ROD, and if necessary, the ROD should authorize the Region
to make any necessary choice among treatment or disposal options.

2.3.3  Operation and Maintenance Plan

       In most instances, remedial activities will result  in the requirement
of a varying degree of operational and maintenance (O&M) activity associated
with the completion of a project.  The RI/FS and ROD will  indicate the types
of O&M activities required and provide a cost estimate.  The RD will provide
more detail on the specifics and degree of O&M activities  required, and
provide a more accurate cost estimate.  To ensure correlation of the
separate but related phases of design and O&M, the A/E shall submit an
initial draft O&M plan simultaneously with the prefinal design document
submission and the final draft O&M plan with the final design documents.
For guidance on developing a comprehensive O&M plan see Appendix B.  The O&M
plan will be finalized and submitted by the A/E or construction contractor
at the prefinal construction conference.

2.3.4  Quality Assurance Project Plan

       A site-specific Quality Assurance Project Plan (QAPP) shall be
prepared by the A/E, if the project will involve any sampling or monitoring
activities.  The plan will provide guidelines for project  organization which
                                    2-15

-------
 OSWER Directive 9355.0-4A
 shall  outline and  identify  quality-control  (QC)  and quality  assurance  (QA)
 responsibilities of the construction contractor,  lead  design party,  or other
 applicable  agencies during  construction.  The QAPP should  be consistent with
 EPA QA/QC Procedures.  The  A/E  shall submit  a draft QAPP simultaneously with
 the prefinal design documents and the final  QAPP  with  the  final  design
 documents submission.  For  guidance on the  development and applicability of
 the QAPP see Appendix  B.

 2.3.5   Site Safety Plan

        An important aspect  of a remedial  action  project, during  both design
 and construction,  is the  health and safety  of the individuals who  will  be on
 site  and that of the surrounding communities.  The A/E shall  develop,  in
 response to site specific data,  specifications to be used  by the
 Construction Contractor in  developing a Site Safety Plan (SSP) that  is
 sufficient  to protect  on-site personnel and  surrounding communities  from the
 physical, chemical, and/or  biological hazards of  the site.   The  A/E  shall
 submit draft specifications with the prefinal design document submission and
 the final specifications  with the final design documents.  For guidance on
 development and compliance  requirements of  the SSP see Appendix  B.

 2.3.6   Architect/Engineer Services During Construction

        The  party responsible for accomplishing a  remedial  action may deem it
 desirable or mandatory that the A/E preparing the final design package
 assume an active role  in  the on-site remedial action (construction)  work.
"The use of  A/E services during  construction  is encouraged  in the following
 areas:

             Review construction contractor  submittals

             Attend conferences and visit project site

             Provide field  representative.
                                    2-16

-------
                                                           OSWER Directive 9355.0-4A
For further information and guidance on possible services  provided by the
A/E within these areas see Appendix B.

2.4  Design Reviews and Approvals

       The concept for a Superfund remedial project is determined when EPA
selects a cleanup alternative based upon the feasibility study  and
supporting documents, and as specified in the ROD or EDO.  Once an A/E firm
is contracted to perform the design work necessary to implement the selected
remedy, the Government reviewing agencies are responsible  for the review,
approval and acceptance of the final plans and specifications.  Interim
outputs as well as the final product of the A/E must be reviewed to ensure
that the design is progressing in a manner consistent with the  ROD/EDO and
existing environmental and construction standards.  The Government design
review and approval responsibilities for all reviews are dependent on the
lead design party and are listed below.  For responsible party RD, the
responsible party has the primary responsibility for design review and for
submitting the design documents to EPA for government review.
     RD Lead
Federal
State
Government Review
  Responsibility
  USAC.E
  State
Responsible Party    EPA
2.4.1  Preliminary Design
Environmental
   Review
 Assistance
EPA and State
EPA


State
Technical
  Review
Assistance
USAGE or EPA
Contractors upon
request
USAGE or EPA
Contractors upon
request
       The preliminary design shall be submitted by the A/E when the design
effort is approximately 30% complete.  The submittal should consist of the
plans and specifications previously described in Section 2.3.1.  If bench
and pilot studies were required, the interim report should be included with
                                    2-17

-------
OSWER Directive 9355.0-4A
the submittal.  For responsible party RD, the preliminary cost estimate will
be submitted at the discretion of the responsible party.  The preliminary
review is important to correct or modify any problems areas before extensive
design is completed.

2.4.1.1  Environmental Review

       The preliminary design submittal shall be reviewed from an
environmental quality standpoint for Fund-financed and responsible party RD,
to ensure that all the necessary elements are included in the specifications
to address full compliance with the applicable or relevant and appropriate
Federal environmental and public health requirements which are identified in
the ROD/EDO (refer to reference 4).

2.4.1.2  Technical Review

       The preliminary design shall be reviewed from a technical standpoint
for compliance with the SOW (refer to Section B.I.I), constructability, and
accuracy of the cost estimate.

2.4.2  Intermediate Design

       At the discretion of the design PO, the intermediate design shall be
submitted for review when the design is approximately 60% complete. The
submittal shall consist of the plans and specifications described in Section
2.3.1.

2.4.3  Prefinal Design

       The prefinal design submittal shall occur when the design is
approximately 9Q% complete and shall consist of the plans and
specifications, O&M plan, QAPP, and specifications for SSP previously
described in Sections 2.3.1 and, 2.3.3 - 2.3.5.  The Government agencies'
major review should occur at this time.  For responsible party RD, the cost
estimate will be submitted at the design PO's discretion.
                                    2-18

-------
                                                           OSWER Directive 9355.0-4A
2.4.3.1  Environmental Review

       The prefinal design submittal shall be reviewed for:

             Compliance with all applicable or relevant  and  appropriate
             environmental and public health requirements  identified in the
             ROD/EDO

             Utilization of currently accepted environmental control
             measures and technology

             The adequacy of the O&M plan, QAPP, and SSP specifications

             Consistency with ROD/EDO, and environmental and public impacts.

2.4.3.2  Technical Review

       The prefinal design submittal shall be reviewed to  ensure:

             The bidability and constructability of the  design

             The accuracy of the construction cost estimate

             Utilization of currently accepted construction  practices  and
             techniques

             The ability of a construction contractor to submit  a fair and
             reasonable bid based upon the bid schedule  included in the
             specifications

             The accuracy of any estimated quantities of materials specified
             in the design
                                    2-19

-------
 OSWER Directive 9355.0-4A
             That the responsibilities and liabilities of the construction
             contractor and the government are clearly defined and detailed
             in the design documents (fund financed only).

2.4.4  Final Design

       The final design submittal shall consist of the final design plans
and specifications (100% complete), the A/E firm's final construction cost
estimate, the final draft O&M Plan, final QAPP and SSP specifications.  The
quality of the design documents should be such that the government or
responsible party is able to include them in a bid package and invite
contractors to submit bids for the construction project.

2.4.4.1  Extent of Review

       The appropriate agencies from Secton 2.4 shall review this submittal,
to ensure that the A/E has adequately addressed all concerns and comments
generated during the prefinal design review process.  If further revisions
to the design are required, the A/E firm shall be so directed.

2.4.4.2  Final Approval

       The agency or party to whom the A/E is under contract shall have the
authority to approve and accept the design, with concurrence from the EPA
and the State on Federal-lead and responsible party projects, and from EPA
alone on State-lead projects.

2.4.4.3  Plan-In-Hand Review

       Plan-In-Hand Review of the final design shall be made by the A/E and
coordinated with the design PO just before the advertisement for
construction of the project.
                                    2-20

-------
                                                           OSWER Directive 9355.0-4A
2.4.5  Major Design Changes

       It is the EPA RPM's responsibility during design reviews and
approvals to ensure that the design package being developed by the USACE,
State, or responsible party is consistent with the approved ROD/EDO.  If it
appears that major design changes are occurring that would significantly
alter the remedy approved in the ROD/EDO, the RPM should notify the design
PO in writing to temporarily halt design activities and immediately notify
the EPA official delegated ROD responsibility of the situation.  That EPA
official  will determine if the design changes warrant a ROD/EDO amendment
and an additional public comment period.  Minor design changes can be
approved by the design PO, with concurrence from the EPA RPM, consistent
with the approved ROD/EDO.

       Technical scope changes and/or cost changes in the project could
constitute a major design change.  Examples of changes which would
constitute a major change include:

             Change from treatment remedy to disposal remedy or vice versa

             Proposed remedy will not work due to field conditions

             Significant increase in implementation cost results in another
             alternative being potentially less costly.

Examples of changes which would not constitute a major change include:

             Change from one treatment process to another with equivalent
             performance

             Cost savings achieved through value engineering review.
                                    2-21

-------
OSWER Directive 9355.0-4A
2.4.6  Value Engineering

       For Fund-financed projects, EPA recommends that the USACE and State
include value engineering screening during the design phase for all remedial
action projects where a potential for substantial cost savings exists.
Value engineering screening shall be limited to project refinements which
would not significantly change or alter the approved remedy, unless
otherwise approved by EPA.  Value engineering screening will consist of
listing high cost items that have a potential for cost savings.

       Those RA projects which, as a result of the value engineering
screening, show a reasonable promise for significant cost savings will be
recommended to EPA for approval of formal value engineering study by the
USAGE or State.  Potential impacts on the RA project schedule and EPA
funding requirements for a formal value engineering study will be identified
by the USACE or State.

2.5   Permits, Approvals and Site Access

       It is important to identify early in the design process all permits,
approvals and site access agreements, if any, required for the project.
Prompt action should be taken to obtain the required permits, approvals, and
site access agreements in order to avoid delays in implementing the remedial
action.  The following discussion pertains to Fund-financed and responsible
party remedial design.

2.5.1  Permits and Approvals

       The permits and approvals which may be required for a project and the
responsibility of obtaining them is dependent on the particular project and
the lead design party.  Refer to reference 2 for additional information.
                                    2-22

-------
                                                          OSWER Directive 9355.0-4A
2.5.1.1  Requirements

       EPA has set forth a policy (Reference 4) addressing compliance with
other environmental statutes.  On-site and off-site remedial actions shall
comply with the substantive requirements of applicable or relevant and
appropriate Federal laws identified in the ROD/EDO.  For on-site remedial
actions, environmental permits are not required.  However, if material is to
be taken off site, the receiving facility must possess all appropriate
environmental permits identified in the ROD/EDO.  In general, the
construction contractor shall be responsible for obtaining any necessary
non-environmental construction permits and approvals (i.e., building permit,
electrical permit, etc.).

2.5.1.2  Responsibilities

       The responsibility for obtaining the required permits and approvals
is dependent on the lead design party and is summarized below.

                                       Environmental Permits
              RD Lead                  (Off-site RA only)
              Federal                  State
              State                    State
              Responsible Party        Responsible Party
The design PO can request the A/E to provide assistance in obtaining
necessary permits and approvals.

2.5.2  Site Access

       At many uncontrolled sites, cleanup actions may have to be taken
which could require short or long term use of adjoining property or property
within the site boundaries owned by parties other than the site owner.  In
addition, the recommended remedial alternative at the site could include
actions which might restrict access to or use of both property within the
site boundaries and adjoining property.  In these situations, it may be
necessary to obtain access to affected property prior to the initiation of
remedial actions.

                                    2-23

-------
OSWER Directive 9355.0-4A
2.5.2.1  Requirements

       At a site where property access is needed, it is first desirable to
obtain voluntary access agreements or rights-of-way from the involved
property owners.  These access agreements should be obtained prior to the
completion of design of the cleanup alternative.  By obtaining these
agreements at this time, there will be assurance that the remedial
construction will not be delayed due to disputes with property owners.

       In some instances, it may be appropriate to acquire easements or
other interests in property.  Guidance on aquisition will be forthcoming.
Any purchase of property or easements would be RA activities, requiring
State cost share for Fund-financed projects.

       For Fund financed RA, if voluntary access cannot be achieved and
resistance from property owners is encountered, the State should make all
efforts to the extent of its legal authority to secure site access.  If
State efforts fail to secure access, the State should notify EPA in writing,
and EPA may have to exercise its statutory authority under Section 104 of
CERCLA and an appropriate access order for entry may have to be secured from
a court having jurisdiction over the matter.

       For responsible party RA, EPA or the State should assure that
responsible parties take all actions needed to obtain access in a timely
manner, and should step in and take legal action if necessary to secure
access.

       Once again, access agreements, acquisition of interest in property,
or court orders for access should occur during the design phase of cleanup,
prior to the initiation of remedial construction, so that possible costly
delays will not be encountered.  Property access should extend for the
duration of the cleanup and associated operation and maintenance, as
necessary.
                                    2-24

-------
                                                           OSWER Directive 9355.0-4A
2.5.2.2  Responsibilities

       The responsibility for obtaining  access to  the  site  and  adjacent
properties, as well  as for all rights-of-way  and easements  necessary to
implement the remedial action is dependent  on the  lead  design party and  is
summarized below.  For Federal lead RD,  the state  or EPA must assure the
USAGE that site access has been obtained prior to  the  USAGE  initiating
procurement activities for RA.

              RD Lead                  Responsibility
              Federal                  State
              State                    State
              Responsible Party        Responsible Party

2.6    Community Relations Activities

       A Community Relations Plan (CRP)  should be  revised to include any
changes in the level of concern or information needs of the community during
design and construction activities.  Community relations activities during
design and construction are discussed below, and pertain to Fund-financed
and private party projects.

2:6.1  Objectives

       The basic objectives of the Superfund community relations program
from remedial  investigation through construction are as follows:

             To gather information about the community in which a site or
             incident is located;

             To inform the public of planned or ongoing actions;

             To give the public the opportunity to be involved in decision
             making; and

             To focus and resolve controversy.

                                    2-25

-------
OSWER Directive 9355.0-4A
                   •
2.6.2  Implementation Activities and Techniques

       The implementation of an active community relations program as
outlined in Community Relations in Superfund:  A Handbook, requires
utilization of two-way communication.  Community relations techniques are
selected to fit the specific needs of the site community as determined by
conducting on-site discussions.  Small public meetings, fact sheets, press
releases, contact lists, door-to-door visits, local information repositories
and comment periods are some of the most effective techniques, especially
during the design process, to ensure that the public is involved in the
decision-making process.

       Specific activities which must be conducted during the design stage
are the following:

             Revise the site community relations plan at the start of design
             to reflect knowledge of citizen concerns and involvement at
             this stage of the process; and

             Prepare and distribute a public notice and an updated fact
             sheet at the completion of engineering design.

       Specific activities to be conducted during the construction stage
could be the following:

             Depending on citizen interest at a site at this point in the
             remedial process, community relations activities could range
             from small group meetings to site visits to fact sheets on the
             technical status.
                                    2-26

-------
                                                           OSWER Directive 9355.0-4A
2.6.3  Responsibilities

       Responsibility for amending the CRP and implementing community
relation activities is dependent on the lead party for the RD/RA and is
outlined below.

       RD/RA Lead    Amend CRP     Implement CRP   Provide Assistance
       Federal       EPA           EPA             State or USACE
       State         State         State           EPA
       Responsible   EPA           EPA             State and/or Responsible
         Party                                       Party
2.7   Cost Estimates For Construction

       The importance of accurately estimating the costs for accomplishing
site-specific construction (i.e., remedial action) can not be over
emphasized.  The development of an accurate total cost estimate is essential
in order to provide adequate funding for a remedial action SSC/IAG or CA,
and to determine State cost share.  The following section discusses the
elements included in the total cost estimate for a remedial action, and
pertains only to Fund-financed remedial actions.

2.7.1  Estimated Cost of Project

       The preparation of a high quality set of plans and specifications is
inadequate unless the project cost estimate is prepared to the same
standards.  The process for developing an accurate project cost estimate is
discussed in Appendix B.  The project cost estimate becomes more refined as
the design progresses from the ROD to the preliminary design to the
prefinal/final design.  For most projects, the final project cost estimate
should be within +15% to -10% of the actual cost.  The importance of the
accuracy of the final project cost estimate is magnified since estimates of
additional costs discussed in Sections 2.7.2 and 2.7.3 are based on the
project cost estimate.
                                    2-27

-------
OSWER Directive 9355.0-4A
2.7.2  Supervision and Administration (S&A) and Engineering
       and Design (E&D) During Construction

       Supervision and Administration (S&A) and Engineering and Design  (E&D)
costs during construction must be established for each remedial action.
These costs are best represented as percentages of the project cost.  The
following are percentages recommended to be used in estimating costs.

       8% S&A for contracts up to $2,000,000"
       6% S&A for contracts over $2,000,000
       1.5% E&D for contracts up to $2,000,000
       1.0% E&D for contracts over $2,000,000

The percentage used may vary even more for very small or very large projects.

2.7.3  Contingency Limits

       A contingency fund should be established for each site-specific
remedial action project to cover unforeseen cost variances which may occur
before construction commences or during construction.

2.7.3.1  Bid Contingency

       The lowest responsive bid submitted during the procurement process
may exceed the project cost estimate due to complexity of the project,
changes in the bidding climate, etc.  Bid contingencies are best represented
as a percentage of the project cost.  The recommended amount for a bid
contingency is 15% of the project cost.
                                    2-28

-------
                                                           OSWER Directive 9355.0-4A
2.7.3.2  Change Orders and Claims

       During construction, unforeseen site conditions, changes in estimated
quantities, project delays and other problems associated with the project
are likely to develop and lead to change orders and claims.  A  contingency
for change orders and claims is best expressed as a percentage  of the
project cost.  The following percentages are recommended.

       10% contingencies for contracts up to $2,000,000
        8% contingencies for contracts over $2,000,000

2.7.4  Total Cost Estimate for Remedial Action Agreements

       The total cost estimate to be .used in developing SSCs should include
all costs discussed in Sections 2.7.1 - 2.7.3.  The total cost estimate to
be used in obligating funds for CAs and lAGs should be the total cost less
the contingency for change orders and claims.

       Any amount of the bid contingency not needed would be applied towards
the contingency for change orders/claims up to the recommended amount in
section 2.7.3.2.  Any additional  amount left in the contingency would be
deobligated or any amount still needed for change orders/claims will be
available from the Region's SCAP.

       Example calculations for estimating the total cost for RA are
presented on the following page.
                                    2-29

-------
OSWER Directive 9355.0-4A
               Total  Cost Estimate for IAG or CA

     Estimated  cost  of  project                              $3,500,000
     S&A  during construction (.06 x $3,500,000)                210,000
     E&D  during construction (.01 x $3,500,000)                 35,000
     Bid  contingency or contingency for change
     orders/claims  (.15 x $3,500,00)                           525,000
                                            Total            $4,270,000

               Total  Cost Estimate for SSC

     Total  cost estimate for IAG                            $4,270,000
     Contingency for change orders/claims
     (.08 x $3,500,000)                                        280.000
                                            Total            $4,550,000
                                     2-30

-------
                                                           OSWER Directive 9355.0-4A
                             3.   REMEDIAL ACTION
3.1   Remedial Action Initiation

        Following completion and approval of the RD package, action must be
taken to initiate remedial action (RA) activities.  The type of agreement
used to initiate RA is dependent on the party that will implement the RA and
is discussed below.

3.1.1  Federal Lead Remedial Action

        To initiate RA at a Federal lead site, the RPM works with the State
to prepare and execute a Superfund State Contract (SSC).  The RPM and the
State should refer to the State Manual, Volume I, for specific information.
Preparation of the SSC should commence during the RD phase of the project
with SSC execution occurring at the completion of RD.

        Once the SSC is executed, the EPA Region should prepare and execute
a site-specific RA IAG with USACE-MRD.  The RPM should forward copies of the
executed RA IAG to EPA HQ and USACE-HQ.  Upon completion of procurement
activities (Section 3.2), USACE-MRD will initiate RA activities through the
appropriate USACE Construction District.  The RPM will maintain oversight of
all RA activities.  The process is outlined in Exhibit 3-1.  A sample
site-specific RA IAG is included in Appendix A (Sample No. 3).

3.1.2  State Lead Remedial Action

        If the existing CA covers RA, no special action is required.  If
this is not the case, the RPM should work with the State to amend the
existing CA for RA in order to initiate RA at a State lead site.  The RPM
                                    3-1

-------
OSWER Directive 9355.0-4A
                                                 EXHIBIT  3-1
                              FEDERAL LEAD REMEDIAL  ACTION PROCESS
                     COPIES TO
                      EPA HO
                     USAGE HO
      ACRONYMS KEY

      RPM       REMEDIAL PROJECT MANAGER
      SSC       SUPERFUND STATE CONTRACT
      USACE MRD  U.S. ARMY CORPS OF ENGINEERS •
                MISSOURI RIVER DIVISION
      RA        REMEDIAL ACTION
      IAG       INTERAGENCY AGREEMENT
      NPl       NATIONAL PRIORITIES LIST
      O&M       OPERATION & MAINTENANCE
                                                  EPA RPM & STATE
                                                    PREPARE SSC
                                                        _L
                                                    SSC EXECUTED
                                                   AT COMPLETION
                                                    OF REMEDIAL
                                                       DESIGN
EPA RPM & USACE MRD
 PREPARE & EXECUTE
 SITE SPECIFIC RA IAG
                                                USACE DESIGN DISTRICT
                                               CONDUCTS PROCUREMENT
                                                ACTIVITIES (FIRM FIXED
                                                  PRICE CONTRACT)
                                                 USACE MRD INITIATES
                                                    RA ACTIVITIES
                                                  THRU APPROPRIATE
                                               CONSTRUCTION DISTRICT
                                                        _L
                                                 USACE CONSTRUCTION
                                                 DISTRICT OVERSIGHT
                                                  AND MONITORING
                                                  CONSTRUCTION TO
                                                 ENSURE COMPLIANCE
                                                 WITH ENVIRON. AND
                                               CONTRACTURAL REQMTS.
                                                    CONTRACTOR
                                                     COMPLETES
                                                   CONSTRUCTION
                       OVERSIGHT BY EPA RPM
                          ADDITIONAL OVERSIGHT
                              BY EPA RPM
                                                   PREFINAL CONST.
                                                  CONFERENCE WITH
                                                    CONTRACTOR
                        PARTICIPANTS
                                                      PREFINAL
                                                     INSPECTION
                        PARTICIPANTS
                                                 USACE CONSTRUCTION
                                                  DISTRICT PREPARES
                                                 PREFINAL INSPECTION
                                               REPORT FOR SUBMISSION
                                              TO EPA.  REGION AND STATE
                                                  FINAL INSPECTION
                                                        AND
                                                   CERTIFICATION
 USACE CONSTRUCTION
  DISTRICT PREPARES
   RA REPORT FOR
 SUBMISSION TO EPA
  REGION AND STATE
        _L
         EPA
    ACCEPTANCE  OF
  COMPLETED PROJECT
USACE CONSTRUCTION DISTRICT
EPA REGION
STATE
CONTRACTOR
USACE CONSTRUCTION DISTRICT
EPA REGION
STATE
CONTRACTOR
                        PARTICIPANTS
USACE CONSTRUCTION DISTRICT
EPA REGION
STATE
CONTRACTOR
   DELETION OF SITE
      FROM NPL
                              STATE ASSUMES
                           O&M RESPONSIBILITY
                                                    O&M REPORT
                                                  PREPARED BY STATE
                                                       3-2

-------
                                                           OSWER Directive 9355.0-4A
and State should refer to the State Manual,  Volume  I, for  specific
information and procedures.  Exhibit- 3-2 graphically depicts the State  lead
remedial action process.

3.1.3  Responsible Party Remedial Action

        The document of settlement issued by EPA where no  trust fund monies
are involved will have covered RD and RA, and no special action is required
to initiate RA at a responsible party site.  The process for responsible
party lead remedial action is shown in Exhibit 3-3.

3.1.4  Conflict of Interest

        In the process of'selecting a contractor for Fund-financed RA,  the
State or EPA shall evaluate whether there is a potential conflict of
interest based on any PRP involvement at the site.  The EPA Region should
include a provision in all CAs and lAGs regarding contracts with PRPs.
Appendix F of the State Manual suggests specific language  to be included in
a CA provision and suggests specific clauses to be  included by the State in
any contract for services or construction.   lAGs should contain a provision
consistent with Appendix F, stating the USACE'will  require interested
contractors to provide information and EPA will evaluate potential
conflicts.  The USAGE should include a provision equivalent to Appendix F in
the contract for construction.

3.2  Procurement Activities

        The responsibility for procurement activities for  Fund-financed
remedial action is dependent on the lead party for  the remedial action
(RA).  For Federal lead RA, the USACE will  conduct procurement activities in
accordance with USACE procurement procedures.  For  State lead RA, the State
will  conduct procurement activities in accordance with 40 CFR Part 33,
Subpart E and the State Manual, Volume II.
                                    3-3

-------
OSWER Directive 9355.0-4A
                                             EXHIBIT 32
                              STATE LEAD REMEDIAL ACTION  PROCESS
                                             EPA RPM AMD STATE
                                                 AMEND CA
                                                IF NECESSARV
                                               STATE CONDUCTS
                                           PROCUREMENT ACTIVITIES
                                            (FIXED PRICE CONTRACT)
           ACRONYMS KEY

           CA   COOPERATIVE AGREEMENT
           RPM  REMEDIAL PROJECT MANAGER
           NPl  NATIONAL PRIORITIES LIST
           O&M  OPERATION & MAINTENANCE
STATE OVERSIGHT
AND MONITORING OF
CONSTRUCTION TO
ENSURE COMPLIANCE
WITH ENVIRON. AND
CONTRACTURAL REOMTS.
1
CONTRACTOR 1
COMPLETES
CONSTRUCTION 1
|
PREFINAL CONST. 1
CONFERENCE WITH
CONTRACTOR

|
PREFINAL 1
INSPECTION

ADDITIONAL OVERSIGHT 1
ANDIOR DESIGNEE |
PARTICIPANTS SES™0"
1 CONTRACTOR
[PARTICIPANTS EPA REGION

™T"^^™"
STATE PREPARES
PREFINAL INSPECTION
REPORT FOR
SUBMISSION TO
EPA
1
FINAL INSPECTION
AND
UUNIHAUlUn
| PARTICIPANTS 1™?™°*
__ 	 1™™^!,°",,,, J rnHTD.rTnp

STATE PREPARES
RA REPORT
FOR SUBMISSION
TO EPA
1
EPA ACCEPTANCE
OF COMPLETED
PROJECT
1 	
DELETION OF SITE
FROM NPL

1
' STATE ASSUMES O&M
RESPONSIBILITY

                                                 O&M REPORT
                                              PREPARED BY STATE
                                                3-4

-------
                                                                    OSWER Directive 9355.0-4A
                                     EXHIBIT 3-3
                RESPONSIBLE PARTY LEAD REMEDIAL ACTION PROCESS
                                RESPONSIBLE PARTY
                                  OVERSIGHT AND
                                  MONITORING OF
                                 CONSTRUCTION TO
                                ENSURE COMPLIANCE
                                WITH ENVIRON. AND
                              CONTRACTURAL REQMTS.
                       ADDITIONAL OVERSIGHT BY
                       EPA-RPM OR DESIGNEE
                                   CONTRACTOR
                                    COMPLETES
                                  CONSTRUCTION
                                 PREFINAL CONST.
                                 CONFERENCE WITH
                                   CONTRACTOR
                   PARTICIPANTS
                                                     PARTICIPANTS
ACRONYMS KEY

NPL   NATIONAL PRIORITIES LIST

O&M  OPERATION & MAINTENANCE
                                RESPONSIBLE PARTY
                                PREPARES PREFINAL
                                INSPECTION REPORT
                                FOR SUBMISSION TO
                                       EPA
                                 FINAL INSPECTION
                                      AND
                                  CERTIFICATION
                                RESPONSIBLE PARTY
                                     PREPARES
                                    RA REPORT
                                  FOR SUBMISSION
                                      TO EPA
                                 EPA ACCEPTANCE
                                  OF COMPLETED
                                     PROJECT
DELETION OF SITE
   FROM NPL
                                       X
                                    O&M REPORT
                                    PREPARED BY
                                 RESPONSIBLE PARTY
EPA REGION
STATE
CONTRACTOR
RESPONSIBLE  PARTY
EPA REGION
STATE
CONTRACTOR
RESPONSIBLE  PARTY
                   PARTICIPANTS
EPA REGION
STATE
CONTRACTOR
RESPONSIBLE PARTY
                          RESPONSIBLE PARTY
                            ASSUMES O&M
                           RESPONSIBILITY
                                         3-5

-------
 OSWER Directive 9355.0-4A
 3.2.1   Advertise for Bids

       Procurement for remedial  action  should  be  through  a fixed-price
 contract  (lump sum,  unit price,  or  a combination of  two), and should be by
 formal  advertising to assure  full and  free  competition.   Procurement by any
 means  other  than formal advertising must  be approved by  the  award official.
 The  specifications are rigid  and require  absolute conformance.   Sealed bids
 are  required at a certain  place, date,  and  time  and  are  publicly opened,
 read,  and  recorded.   The bidder  whose  price is  low and who is otherwise
 responsive and responsible is awarded  a contract.  The solicitation ..should
 require all  proposals to explain how the  prime contractor would utilize
 minority  business enterprises and women's business enterprises.

 3.2.2   Site  Inspection

       The  USAGE or State may  deem it desirable,  or mandatory in some cases,
 to conduct a site visit with  the bidders  in order to answer  questions
 regarding  the design or implementation.   Copies  of the RI/FS and the design
 document will be made available  for review  during the procurement phase,
 either in  the USAGE  Design District Office  or in a local  public library.

 3.2.3   Review of Bid Documents

       This review shall be limited  to  determining whether or not the bidders
 are  both  responsive  to the requirements of  the bid solicitation, (i.e. are
 the  bid bonds there  in the proper form and  amount, is the required insurance
'binder provided, etc.); and responsible (i.e. does each  bidder  possess the
 capability and experience  as  required  in  the  solicitation to perform the
 remedial  action in a safe  and timely manner at the price  bid,  is there any
 potential  conflict of interest,  if  RA  involves off-site  disposal does the
 off-site facility have RCRA compliance  inspection, etc.)

       The  government bid review  responsibility is dependent  on  the lead
 design party and is  summarized below.   For  responsible party RA, the
 responsible  party has the  primary responsibility for bid  review and for
 submitting the bid documents  for government review.
                                    3-6

-------
                                                           OSWER Directive 9355.0-4A
                        Government Review
      RD Lead             Responsibility         Assistance
      Federal             USAGE                EPA and State
      State               State                EPA (USAGE or EPA Contractors)
                                               upon request)
      Responsible Party   EPA                  State  (USAGE or EPA
                                               Contractors upon  request)
3.2.4  Bid Protests
      Bid protests have the potential to significantly delay the RA.
Procedures for avoiding bid protests, and lodging and dealing with protests,
should be consistent with 40 CFR Part 33 and the State Manual, Volume II,
for State lead projects and with USAGE procedures for Federal lead
projects.  The key is often a complete and well documented bid specification
which clearly describes the work to be performed and the
responsi ve/responsi ble requi rements.

3.3   Monitoring and Oversight

      Records and reports maintained during these activities must be
adequately documented since they will be used in the final certification of
a remedial action.  Monitoring and oversight of construction activities are
discussed below, and pertain to Fund-financed and responsible party RA
except where noted.

3.3.1  Inspections

      The responsibility for construction inspection is dependent on the
lead' party for the RA and is summarized below.

     RA Lead               Inspection            Oversight
     Federal               USAGE                 EPA
     State                 State                 EPA (USAGE or EPA
                                                 Contractors upon request)
     Responsible Party     Responsible Party     EPA (State, USAGE, or EPA
                                                 Contractors upon request)
                                    3-7

-------
OSWER Directive 9355.0-4A
3.3.1.1  Full Time Inspector

        During all on-site construction activities the party responsible for
inspection will provide a full time on-site inspector with expertise in
federal construction projects and proceedings.  The on-site inspector shall
be authorized to stop all activities not in compliance with 3.3.1.2 and
3.3.1.3 below, or which endanger the health and welfare of on-site personnel
and surrounding residents.  For large sites or complex projects, additional
on-site inspectors may be required.

        For Fund lead RA, construction oversight will occur at intervals
determined by the complexity of the project, by the EPA RPM on Federal lead
RA and the EPA RPM or USAGE on State lead RA.

        For responsible party RA, construction oversight will be provided by
the EPA RPM or his designee (i.e. State or USACE) on an ongoing basis.  The
document of settlement will specify the authority of the oversight personnel
in regards to construction activities.

3.3.1.2  Compliance with Environmental Requirements

        Inspections should verify compliance with all environmental
requirements identified in the contract.  These inspections shall include,
but not be limited to air quality and emissions monitoring records, waste
disposal records (e.g., RCRA transportation manifests), etc.  The inspector
also should ensure compliance with all health and safety procedures.

3.3.1.3  Compliance with other Contract Requirements

        The inspector shall review all daily reports and construction
activities to verify that all work is in compliance with all contract
requirements and shall note and resolve all discrepancies immediately.  The
EPA RPM can assist in resolving discrepancies upon request.
                                    3-8

-------
                                                           OSWER Directive 9355.0-4A
3.3.1.4  Review of Contractor Reports

        The on-site inspector shall review all reports  (daily, weekly, and
monthly, etc.) and initial each.  All comments on these reports should be
noted in the inspector's daily log.

3.3.2  Progress Reports to EPA

        Detailed progress reports will be required throughout the duration
of the project.  The progress reports will be prepared and submitted to EPA
Regions and HQ in accordance with the following:

        RA Lead                Preparer                Frequency of Report

        Federal     '           USAGE                        Monthly
        State                  State                        Quarterly
        Responsible Party      Responsible Party            Monthly

        The progress reports will be used by EPA to monitor the remedial
construction activities.  The content of these reports will be sufficient to
develop a chronological record of all site activities and should include the
following elements:

             Estimate of the percentage of project completed and the total
             project cost to date

             Summaries of the following items for the reporting period:

                  Work performed on the site
                  Community relations activities including community
                  contacts, citizen concerns, and efforts to resolve any
                  concerns
                  Change orders and claims made on the contract
                  Problems or potential problems encountered
                                    3-9

-------
OSWER Directive 9355.0-4A
             Status of contingency fund to date (Fund-financed RA only)

             Projected work for the next reporting period

             Copies of contractor daily reports, change orders, RCRA
             manifests, and laboratory/monitoring data.

3.3.3  Contingency Fund for Change Orders and Claims

        This fund is available for unforseen site conditions and other
problems with cleanup, containment, need for alternate disposal sites,
additional sampling or monitoring which develop and lead to change orders,
claims, etc.  Problems which would alter ROD decisions are not subject to
use of the contingency fund and require HQ and/or Region approval.  A site-
specific list of items not applicable to contingency fund use may need to be
developed as the project progresses.  This section pertains only to
Fund-financed RA.

3.3.3.1  Federal Lead Remedial Action

        The USACE is reponsible for processing change orders and'claims in
accordance with USACE procurement procedures.

        The USAGE'S project manager will be delegated authority to approve
any change order up to 20% of the project contingency fund.  Any change
order exceeding 20% of the contingency fund will require approval of the EPA
RPM.  If 75% of the total contingency is spent, the USACE's project manager
will formally notify the RPM in writing and state whether additional funding
may be necessary.  The USAGE'S project manager must receive written approval
from the EPA RPM in order to exceed 75% of the project contingency fund.  At
no time will the USACE exceed 100% of the contingency fund.
                                    3-10

-------
                                                           OSWER Directive 9355.0-4A
3.3.3.2  State Lead Remedial Action

        The state  is responsible for  processing  change  orders  and  claims
with assistance and guidance from  EPA,  and  in  accordance with  40 CFR 33.

        The State  Project Officer  (SPO) may be delegated the authority  to
approve any change order which totals up to 20 percent  of the  project
contingency fund.  Any change order that exceeds this 20 percent limit
requires RPM approval.  The SPO may continue to  approve such change orders
until 75 percent of the total contingency fund has been depleted.
Thereafter, the State should request  a  CA amendment for additional funds,
unless the project is near completion and no other change orders are
anticipated.  The  State must receive written approval from EPA  to  exceed 75%
of the project contingency fund.

        Before any change order may be  approved, the State must conduct a
cost or price analysis (see 40 CFR 33).  Superfund program procedures also
require the State to perform a technical and administrative analysis (see
the State Manual, Volume II, for more detail).

        EPA will consider funding claims management costs and claims
allowable to the project via an amendment of the existing CA (see  the State
Manual, Volume II for details).

3.4  Remedial  Action Completion and Acceptance

        As the project nears completion, roles and responsibilities of EPA,
the State, and where appropriate the USACE  and responsible parties, must be
clearly defined to ensure proper project completion, approval,   and
closeout.  Final inspection and closeout activities are discussed  below.

3.4.1  Prefinal Construction Conference

        Upon preliminary project completion, a prefinal construction
conference with the contractor is required for Federal  lead remedial  action
                                    3-11

-------
OSWER Directive 9355.0-4A
(RA) and recommended for State lead and responsible party RA.  The objective
of the conference is to discuss procedures and requirements for project
completion and closeout.  The conference will be scheduled and chaired by
the agency that has primary responsibility for construction inspection.

3.4.1.1  Participating Parties

        The parties that participate in the prefinal construction conference
will vary depending on the lead party for the RA.  In general, participants
should include the following:

         Party                RA Lead

         EPA-Region           all leads
         State                all leads
         Contractor           all leads
         USAQE                Federal lead (State and responsible party when
                              requested)
         Responsible Party    Responsible party lead
         Design A/E           when requested

3.4.1.2  Suggested Agenda Items

        A list of suggested items to be covered at the conference includes
but is not limited to:

             Final O&M plan submission
             Cleanup responsibilities
             Demobilization activities
             Security requirements for project transfer
             Prefinal inspection schedule
             Facility startup and testing
             Operator training
                                    3-12

-------
                                                          OSWER Directive 9355.0-4A
3.4.2  Preflnal Inspection

        A prefinal inspection will be conducted upon preliminary project
completion for Federal lead, State lead, and responsible party RA.

3.4.2.1  Inspecting Parties

        The prefinal inspection will be led by the agency that has primary
responsibility for construction inspection.  The other parties involved in
the inspection will vary depending upon, the lead party for the RA.  In
general, participants should include all parties from the prefinal
construction conference.

3.4.2.2  Extent of Inspection

        The prefinal inspection will consist of a walk-through inspection of
the entire project site.  The RPM and State should inspect the completed
site work to determine whether the project is complete and consistent with
the contract documents and the EPA approved remedy.  Any outstanding
construction items discovered doing the inspection should be identified and
noted by the RPM and State.

        When the RA includes construction of a treatment system, the
facility start-up and shakedown shall have been completed as part of the
RA.  The Contractor shall have certified that the equipment has performed to
meet the purpose and intent of the contract specifications.  Retesting shall
have been successfully completed where deficiencies were revealed.
Shakedown may have taken several months.  Determination of remedy
effectiveness for other types of remedial actions will be addressed on a
case-by-case basis.

3.4.2.3  Prefinal Inspection Report

        Upon completion of the prefinal inspection, a prefinal inspection
report will be prepared and processed in accordance with the following:
                                    3-13

-------
 OSWER Directive 9355.0-4A
       RA Lead              Preparer              Submitted  to
       Federal              USAGE                 EPA,  State
       State                State                 EPA
       Responsible  Party    Responsible  Party     EPA,  State
         The  prefinal  inspection  report should  outline  the outstanding
 construction items,  actions  required to resolve items,  completion date for
 these items, and date for  final  inspection.

 3.4.3  Final Inspection  and  Certification

         Upon completion  of any outstanding construction items,  a final
 inspection will be conducted for Federal Lead,  State lead,  and  responsible
 party RA.

 3.4.3.1   Inspecting  Parties

         The  final  inspection will be led by  the agency that has primary
 responsibility for construction  inspection.  The other parties  will  vary
 depending on the lead party  for  the RA. In  general, participants should
 include  all  parties  form the prefinal  inspection.

 3.4.3.2   Extent of Inspection

         The  final  inspection will consist of a walk-through inspection of
 the project  site.  The prefinal  inspection report  will  be used  as a
 checklist by the RPM and the State, with the inspection focusing on  the
^outstanding  construction items identified in the prefinal inspection.  The
 contractor's demobilization  activities should  be completed, except for
 equipment and  materials  required to complete outstanding  construction items,
 at the time  of inspection.  The  RPM and State  will confirm that all
 outstanding  items  have been  resolved.   If any  items  are still unresolved,
 the inspection shall  be  considered a prefinal  inspection  requiring another
 prefinal inspection  report.
                                    3-14

-------
                                                           OSWER Directive 9355.0-4A
3.4.3.3  Remedial Action  Report

        Upon satisfactory completion  of  the  final  inspection,  a
remedial action report will  be prepared-and  processed  in  accordance  with
Section 3.4.2.3 and  submitted within  60  days after final  inspection.   The  RA
report will include  the following elements:

             Brief description of outstanding construction  items  from the
             prefinal inspection and  an  indication that the  items were
             resolved

             Synopsis of  the work defined  in the SOW and  certification  that
             this work was performed

             Explanation  of  any modifications  to work  in  the SOW  and  why
             these were necessary for the  project

             Certification that the remedy is  operational and  functional

             Documentation necessary to  support deletion  of the site  from
             the NPL.

        For a responsible party RA, the  document of settlement may specify
different final inspection/certification conditions.

3.4.4   Acceptance of Completed Project

        The remedial action report will  be reviewed by the RPM for State
lead- RA and by the RPM and State for Federal  lead  and responsible party RA.
If the RPM or RPM/State are satisfied that the remedy is  complete and
performing adequately, the Regional Administrator  shall provide written
notice to the appropriate party of EPA's acceptance of the completed  project.
                                    3-15

-------
OSWER Directive 9355.0-4A
3.5    Site Closeout

        After acceptance of the completed RA by EPA, site closeout
activities need to be conducted for Fund-financed and responsible party
projects.

3.5.1   Deletion of Site from NPL

        The EPA Region can recommend deletion of a site from the NPL after
completion of a RA, if one of the following deletion criteria has been met:

             EPA, in consultation with the State, has determined that
             responsible parties have completed all appropriate response
             actions

             EPA, in consultation with the State, has determined that all
             appropriate Fund-financed response actions have been completed
             and that no further cleanup by responsible parties is
             appropriate.

        For detailed information on the criteria and mechanism used to
delete sites from the NPL, the RPM should refer to the EPA memorandum
entitled "Interim Procedures for Deleting Sites from National Priorities
List."  Final procedures for NPL deletion are under development.

3.5.2  Operation and Maintenance

        In most instances, there is a requirement for some degree of regular
operation and maintenance activity associated with the completed remedial
action.
                                    3-16

-------
                                                           OSWER Directive 9355.0-4A
3.5.2.1  Operation and Maintenance Assumption

        The date certified in the remedial action report that the project is
complete and the remedy is operational and functional, is  the date when O&M
commences.

        For Fund lead projects, this is the date the State assumes
operational responsibility for O&M.  If necessary, the RPM and State must
either amend the existing CA or develop a new CA covering O&M cost sharing.
This CA should be processed as soon as reliable cost estimates for O&M are
available, and need not wait until final project completion.  For
responsible party projects, this is the date the responsible party assumes
O&M responsibility.

3.5.2.2  Operation and Maintenance Report

        At the completion of Fund financed O&M activities, the State shall
prepare and submit to EPA an O&M report.  This report will include the
following elements:

             Description of O&M activities performed

             Results of site monitoring, indicating that the remedy meets
             the performance criteria

             Explanation of additional operation and maintenance (including
             monitoring) to be undertaken at the site.

        For responsible party O&M, the document of settlement may specify
different O&M conditions.
                                    3-17

-------
                                   OSWER Directive 9355.0-4A
          APPENDIX A

SAMPLE USAGE WORK ASSIGNMENTS
 AND  INTERAGENCY AGREEMENTS
        SAMPLE NO. 1
           IAG FOR
  FIRST  PHASE DESIGN WORK
            A-l

-------
OSWER Directive 9355.0-4A
US ENVIRONMENTAL PROTECTION AGENCY 1
WASHINGTON. OC 20460
INTERAGENCY AGREEMENT/AMENDMENT 3
Part 1 — GENERAL INFORMATION
5. Name and Address of EPA Organization
*
6
I
I
I
C
IAG Identification Number
. Type of Action
New Agreement
2. Funding Location by Region
4. Program Abbreviation
*
. Name and Address of Other Agency
(e'partment of Defense
J.S. Army Corps of Engineers (USAGE)
:ngineering Division, Missouri River
)maha, Nebraska 68101-0103
7. Project Title
First Phase Design Work - FY 1985
8. EPA Project Officer (Name. Address. Telephone Number! S
*
10. Project Period
10/01/84 - 09/30/85
i
1 2. Scope of Work (Attach additional sheets, as needed/
This agreement obligates no more than $ *
. Other Agency Project Officer (Name. Address. Telephone Numoerl
William Mulligan FTS/864-7227
USAGE, Engineering Division, Missouri River
P. 0. Box 103, Downtown Station
Omaha, Nebraska 68101-0103
1 . Budget Period
10/01/84 - 09/30/85
and generally no more
project to the USAGE to Initiate the selection of Architectural/Engin<
the engineering design phase of Federal lead remedial action projects
perform all action necessary to retain an A/E firm for engineering de
the following:
Phase I -

than $7,000 per
jering firms for
The USAGE will
sign, including
Synopslze requirement in Commerce Business Daily
Designate A/E pre-selection and selection boards
Develop A/E pre-selection list
Contact A/E firms to ascertain interest in project
Approve A/E selection list
Tentatively select A/E firm
13. Statutory Authority for both Transfer of Funds and Proiect Activities
CERCLA. E.G. 12316 & the Economy Act of 1932, as amended (31USC1535)
FUNDS
IS. EPA Amount
16. EPA In-Kind Amount
17 C'her Agency Amount
1 8. Other Agency In-Kind Amount
19 Total Proiect Cost

PREVIOUS AMOUN1





AMOUNT THIS ACTION
*



*
20 Fiscal nformaiion
Program Element FY
TFAY9A 85
Appropriation Doc. Control No.
68/20X8145 *
Account Number Obiect Cl
* 25.76
14 Other Agency Type
Federal
AMENDED TOTAL






ass Obligation/Oeobngj: cr. Ami
*
  EPA ' orm 1610-1 (Rev. 8-84) Previous editions are obsolete.
                                                                                                            Page 1 of 5
                                                      A-2

-------
                                                                                             OSWER Directive 9355.0-4A
                     PART II - APPROVED BUDGET
                                                                                   IAG IDENTIFICATION NO
                              21. Budget Categories
                                                                                             Total Itemizition of
                                                                                           Estimated Coat to Date
   (•) Personnel
   (b) Fringe Benefits
   'el Travel
   Idl Equipment
  (t) Supplies
  HI Procurement/Assistance
  (a) Construction
  |h) Other
  |i) Tot«l Direct Charges
                                                                                  $  Breakdown  not  available.
  lil Indirect Costs:  Rate
                             a Base
                                                                                   Will  be  provided  as  part  of
(k) Total
  (EPA Share   100 %|
                           (Other Agency Share   0
    request  for reimbursement.
$                  *
22. Is equipment authorized to be furnished by EPA or acquired with EPA funds?    [J ym    R] No
  (Idfntiff til tquipm»at costing 11.0OO or mortl
23. Are any of these funds being used on extramural agreements?    fj Yes    J3 No (S»* him 21ft

  LJ Grant.    LJ Cooperative Agreement, or    l_l Procurement
  Contactor/Recipient Name (H knowni
                                      Total Extramural Amount Under This Project     Percent Funded by EPA dl know
                                 PART III — PAYMENT METHODS AND BILLING INSTRUCTIONS
24. Gal Disbursement Agreement:

        OS Reimbursement
        D Advance




        LJ Allocation Transfer
                                Request for reimbursement of actual costs will be itemized on SF 1081 or SF 1080 and
                                submitted to the Financial Management Office. Environmental Protection Agency. 26 West St.
                                Clair. Cincinnati. OH 4S268:

                                   to] Monthly    LJ Quarterly    LJ Upon Completion of Work

                                Only available for use by Federal agencies on working caonal fund or with appropriate justifica-
                                tion of need for this type of payment method. Unexpended funds at completion of worn win oe
                                '•turned to EPA Quarterly cost reports will be forwarded to the Financial Management Office.
                                Environmental Protection Agency, 26 West St. Clair. Cincmati. OH 45268

                                Used to transfer obligation*! authority or transfer of function between Federal agencies  Must
                                receive prior approval by the Office of the Comptroller. Budget Division. Budget Formulation and
                                Control Branch. EPA Headquarters	
25. LJ Reimbursement Agreement
Other Agency's IAG Identification Number
Billing Address
                                                          Silling Instructions and Frequency
EPA Form 1610-1 (Rev. 8-84)
                                                                                                             Page 2 ot 5
                                                        A-3

-------
OSWER Directive 9355.0-4A
               PART IV - ACCEPTANCE CONDITIONS
                                                                     LAG IDENTIFICATION NO.
 26. General Conditions:
    The other agency covenants and agrees that it will expeditiously initiate and complete the project work for
    which funds have been awarded under this agreement.	
 27. Special Condition!:
 Work assignments for A/E  selection  will be  initiated via  a letter  signed by  the
                           «	 or his designee.  The letter will
 identify the  particular site, provide the necessary account numbers, and describe any
 adjustments,  including  increases  in the site  dollar ceiling ($7,000) and/or  changes
 to the scope  of work.

 The USAGE will initiate Phase I actions upon  receipt of EPA authorization.   Phase II
 actions will  not begin  until EPA  has notified the USAGE of the selection and approval
 of a remedy and EPA approval of an  Interagency Agreement  for Phase II actions.

 EPA acting  as manager of  the Hazardous Substance Response Trust Fund, requires current
 information on CERCLA response actions and  related obligations of  CERCLA funds for
  these actions.  In addition, CERCLA authorizes EPA to  recover from responsible parties
 all government costs incurred during a response action.

                                          (See Attachment A)
                                    PaftV- OFFER AND ACCEPTANCE
 NOTE:  1)   For disbursement actions, the agreement/amendment must be signed in duplicate and one original
             returned to the Grants Administration Division for Headquarters agreements and to the appropriate
             EPA IAG administration office for Regional agreements within 3 calendar weeks after receipt or within
             any extension of time as may be granted by EPA. The agreement/amendment must be forwarded to
             the address cited in Item 28 after acceptance signature.

             Receipt of a written refusal or failure to return the properly executed document within the prescribed
             time may result in the withdrawal of the offer by the Agency. Any change to the agreement by the other
             agency subsequent to the document being signed by the EPA Action Official which the Action Official
             determines  to  materially alter the agreement/amendment  shall  void  the  agreement/
             amendment.

         2)   For reimbursement actions, the other  agency  will  initiate  the action  and forward two original
             agreements/amendments to the appropriate EPA program office for signature. ~he> agreements/
             amendments will then be forwarded to the appropriate EPA TAG administration office for acceptance
             signature on behalf of the Environmental Protection Agency. One original copy will be returned to the
             other agency after acceptance.
  EPA IAG Administration OH ice /tor Kjminntritift/mtntgtmem ttsituncfl
                     EPA Program Office Hot tnhnietl tssistancti
 28. Organization/Address
          29. Organization/Address
                    Decision Official on Behalf of the Environmental Protection Agency Program Office
 30. Signature
Typed Namt and Title
                                                                                 Date
                          Action Official on Behelf of the Environment*! Protection Agency
3V Signature
Authorizing
32. Signature
Typed Name and Title
*
Official on Behelf of the Other Agency
Typed Name and Title
Oete

Date
 EPA Form 1610-1 (Rev. 8-84)
                                                                                             Page 3 of S
                                                A-4

-------
                                                           OSWER Directive 9355.0-4A
                                ATTACHMENT A

27. SPECIAL PROVISIONS (continued)

    In order to help assure successful recovery of CERCLA funds, the USACE
shall maintain site-specific accounts and documentation of the following:

         Employee hours and salary (timesheets)

         Employee travel and per diem expenses (travel authorizations, paid
         vouchers, and treasury schedules)

         Receipts for materials, equipment, and supplies

         Any other costs not included in the above categories

    In order to assist in the development and prosecution of a cost recovery
action, within three weeks from the date of a request from EPA or the
Department of Justice (DOJ), the USACE will provide to EPA or DOJ
site-specific costs and copies of the back-up documentation which supports
those costs.  EPA and DOJ may periodically request updates of the costs and
documentation after the initial request.  The USACE will provide EPA with a
contact for obtaining such site-specific accounting information and
documentation.  This cost information and documentation must also be
available for audit or verification on request of the Inspector General.

    USACE will provide access to its files concerning the project on an
on-going basis for EPA and DOJ examination to assist in cost recovery.  As
original documents may be requested for cost recovery actions, USAGE will
provide EPA and DOJ access to the original documentation when requested.
USACE will notify EPA in advance of placing any project files in storage or
archives.

    Reimbursement is contingent upon receipt and approval by EPA of monthly
progress and financial reports by site, containing an accounting of funds
and status of activities.

    The USACE will provide a letter report summarizing each A/E selection to
the Regional Technical Project Officer.
                                     A-5

-------
OSWER Directive 9355.0-4A
Mr. William Mulligan
U.S. Array Corps of Engineers
Engineering Division, Missouri River
P. 0. Box 103, Downtown Station
Omaha, Nebraska  68101-0103

Dear Mr. Mulligan:

     This letter serves to initiate a work assignment for the U. S. Army Corps
of Engineers (USAGE) to select an architectural/engineering firm to design the
remedial action at the following superfund site:
     The selected activities must be consistent with the Interagency Agreement
No. DW96******-01-0 between the USAGE and the Environmental Protection Agency
(EPA).  Funding for costs incurred while providing these services to EPA,
authorized under the authority of the Comprehensive Environmental Response,
Compensation and Liability Act of 1980 (CERCLA), is not expected to exceed:
     Enclosed is the Phase I Design Authorization Form.  This document contains
the necessary account numbers that apply specifically to this work assignment.
These numbers must be used on all financial and management reports.
                                                                      i
                                      Sincerely yours,
                                      (Title)

Enclosure

cc;  Richard Ruhe
     Noel Urban
     Paul Nadeau
     Ivery Jacobs
                                    A-6

-------
                                                                       OSWER Directive 9355.0-4A
                            AUTHORIZATION FORM FOR PHASE  I  DESIGN

             AUTHORIZATION IS HEREBY GIVEN TO INITIATE THE  FIRST PHASE  OF  DESIGN
             WORK AS DESCRIBED IN IAG # DW96930***-01-0.  THE  FOLLOWING INFORMATION
             IS PROVIDED FOR COST TRACKING PURPOSES:
             SITE NAME

             REGION

             EPA SITE I.D. #

             HQ TECHNICAL PROJECT OFFICER

             REGIONAL SITE MANAGER

             PERIOD OF PERFORMANCE
PHONE
PHONE
                                           FROM
                                                                 TO
ACCOUNTING INFORMATION

DEOBLIGATE FROM:
OBLIGATE TO:
DOCUMENT
CONTROL NO.
*l<
*!'
1*1*1*1*
'1*1*1*1*
1
1
1
I IAG NO .
|D|W|9|6|*|*|*|*
|D|W|9|6|*|*|*|*
1
1
1
1
*I*|0|1|0|
*l*|0|l|0|
SUPERFUND
ACCOUNT NO.
5|T|F|A|*|*
5|T|F|A|*|*
1*
1*
1 1
I OBJECT |
I CLASS |
I CODE |
|N|0|0|2|5|7|6
|N|*
l*|2|5|7|6
Isl
ISl
NOT TO
EXCEED
AMOUNT
'1*1*1*1
*l*l*l*l
I
1
1
|


                 (Title)
                                                           DATE
              EPA PROJECT OFFICER
                                                           DATE
              (individual who certifies funds)
                                                           DATE
Original to:  Richard Ruhe, EPA
              Cincinnati, OH

cc:           William Mulligan, USAGE

              Noel Urban, USAGE

              Paul Nadeau, EPA
              Ivery Jacobs, EPA, Room 3623M
              Financial Reports and Analysis  Branch
                                           A-7

-------
OSWER Directive 9355.0-4A
                                      SAMPLE NO.  2
                                         IAG FOR
                               DESIGN OF  REMEDIAL ACTION
                                       A-8

-------
                                                                             OSWER Directive 9355.0-4A
       US ENVIRONMENTAL PROTECTION AGENCY
             WASHINGTON. DC 20460
 INTERAGENCY AGREEMENT/AMENDMENT
       Part I — GENERAL INFORMATION
                                                1. IAG Identification Number
                                 3. Type of Action
                                      New Agreement
                                                                   2. Funding Location by Region
                                                           4. Program Abbreviation
5. Name and Address of EPA Organization

                *
                                 6. Name and Address of Other Agency
                                   •  Department  of Defense
                                     U.S.  Army Corps of  Engineers  (USACE)
                                     Engineering Division,  Missouri River
                                     Omaha, Nebraska  68101-0103
7. Project Title
     Remedial action at
8. EPA Project Officer (Name. Address. Telephone Number)

               *
                                 9. Other Agency Project'Officer (Name. Address, leleohoge Number)
                                      William Mulligan        FTS/86%-7227
                                      USACE, Engineering  Division,  Missouri  River
                                      P.  0. Box  103, Downtown Station
                                      Omaha, Nebraska   68101-0103
10. Project Period
          *
                                 11. Budget Period
                                          * (same as project period)
11. Scope of Work {Attach additional sheets, as needed)
    This agreement obligates a total of $     *     to the U.S. Army Corps of  Engineers
    (USACE) for  implementation of the remedial action at 	*	
                   *                    (EPA  ID0      *	).
    divided as  follows:
         1. $
          for implementation  of the  remedial  action.
         2. $             for supervision and execution of  the contract awarded based  on
            the  Invitation for  Bid (IFB).   Specific USACE responsibilities  are detailed
            in the appended Scope of Work  (Attachment A).
13 Statutory Authority for both Transfer nf Funds and Project Activities
	CERCLA,  E.O.  12316 & Economy Act  of 1932,  as amended (31USC1535)
                                                                   14. Other Agency Type
                                                                           Federal
            FUNDS
                                  PREVIOUS AMOUNT
                                                         AMOUNT THIS ACTION
                                                                                   AMENDED TOTAL
  IS. EPA Amount
  16. EPA In-Kind Amount
  17 C'her Agency Amount
  18. Other Agency In-Kind Amount
  19 Total Proiect Cost
20 Fiscal Information
 Program Element
 TFAY9A
FY
85
Appropriation
68/20X8145
                                     Doc Control No
                                                      Account Number
Object Class
 25.76
                                                                    Obligation/ Oeobhganon Ami
EPA Form 1610-1 (Rev. 8-84) Previous editions are obsolete.
                                                                                              Page 1 of 5
                                                A-9

-------
OSWER Directive 9355.0-4A
                       PART II — APPROVED BUDGET
                                                                                     IAG IDENTIFICATION NO
                                21  Budget Categories
                                                                                              Total Itemuation of
                                                                                             Estimated Cost to Date
    a> P»f»onnel
    (bl Fringe Benefits
    1C) Trt
    (dl Equipment
    (el Supplies
    ifl Procurement/Assistance
    (o) Construction
    (Ml Other
    III Toial Direct Charges
                                                                                   $     (Breakdown  not available.
    (il Indirect Costs   Rate
                               »8ase
                                                                                         Will  be  provided  prior  to
    (k) Total
      (EPASha**   100  %)
                          (Other Agency Share  0    %)
                                                                                        reimbursement.)
                                                                                                      *
22. Is equipment authorized to be furnished by EPA or acquired with EPA funds?
  Wenfi/V •// Kjuipmem east my S1.0OO or monl
                                                                            Y(a
                                                                                     \ No
  23 Are any of these funds being used on extramural agreements?    ££1 Yes   D No ISn Item 21 fl

    LJ Grant.    LJ Cooperative Agreement, or    2SI Procurement
    Contactor/Recipient Name /if known)

             Unknown
                                        Total Extramural Amount Under This Project

                                              *       (estimate)
Percent Funded by EPA i'it known)

       100*
                                   PART III — PAYMENT METHODS ANO BILLING INSTRUCTIONS
  24
     I Disbursement Agreement

        £3 Reimbursement
          D
             Advance
            I Allocation Transfer
                                  Request for reimbursement of actual costs will be itemized on SF 1081  or SF 1080 and
                                  submitted to the Financial Management Office. Environmental Protection Agency. 26 West Si
                                  Clair. Cincinnati. OH 4S268:

                                     £5J Monthly    LJ Quarterly    LJ Upon Completion of Work

                                  Only available for use by Federal agencies on working cao'tal fund or with appropriate tustifica-
                                  tion of need for this type of payment method. Unexoenoed iunu> oi lonitiietion of v.c.-l; ...:: be
                                  returned to EPA Quarterly cost reports will be forwarded to the Financial Management Office.
                                  Environmental Protection Agency. 26 West St Clair. dncmati. OH 45268

                                  Used to transfer obligational authority or transfer of function between Federal agencies Must
                                  receive prior approval by the Office of the Comptroller. Budget Division. Budget Formulation and
                                  Control Branch. EPA Headquarters.	
  25
     n
        Reimbursement Agreement
  Other Agency s IAG Identification Number
  Billing Address
                                                            Billing Instructions and Frequency
  EPA Form 1610-1 (Rev. 8-84)
                                                                                                                      2 of 5
                                                         A-10

-------
                                                                             OSWER Directive 9355.0-4A
              PART IV - ACCEPTANCE CONDITIONS
                                                                     IAC IDENTIFICATION NO.
 26. General Condition*:
   The other agency covenants and agrees that it will expeditiously initiate and complete the project work for
   which funds have been awarded under this agreement.	
27. Special Condition!:
Reimbursement  is contingent upon  receipt  and approval  by EPA  of the monthly progress
reports from USAGE described below and any other reports described in  the appended  scope
of work.  The  monthly  progress reports will be submitted to   (Regional P.O.)	 in EPA
                                          (Hq  P.O.)
Region
                                  and
in EPA,  Washington,  O.C.
EPA acting as  manager  of the Hazardous  Substance Response Trust  Fund, requires current
information  on CERCLA  response  actions  and related  obligations of CERCLA funds for
these actions.  In addition, CERCLA authorizes EPA  to recover  from responsible parties
all government costs Incurred during a  response action.

                                      (See  Attachment A)
                                    Pert V - OFFER AND ACCEPTANCE
 NOTE: 1)   For disbursement actions, the agreement/amendment must be signed in duplicate and one original
            returned to the Grants Administration Division for Headquarters agreements and to the appropriate
            EPA IAG administration office for Regional agreements within 3 calendar weeks after receipt or within
            any extension of time as may be granted by EPA. The agreement/amendment must be forwarded to
            the address cited in Item 28 after acceptance signature.

            Receipt of a written refusal or failure to return the properly executed document within the prescribed
            time may result in the withdrawal of the offer by the Agency. Any change to the agreement by the other
            agency subsequent to the document being signed by the EPA Action Official which the Action Official
            determines  to materially  alter  the  agreement/amendment  shall  void  the  agreement/
            amendment.

        2)   For reimbursement actions, the other  agency  will  initiate  the action and forward two original
            agreements/amendments to the appropriate  EPA program office for signature  ~he agreements/
            amendments will then be forwarded to the appropriate EPA TAG administration office for acceptance
            signature on behalf of the Environmental Protection Agency. One original copy will be returned to the
            other agency after acceptance.
 EPA IAG Administration Office Hoi taministniitt/minigemem luiginctl
                                                             EPA Program Office Ifor iKhmcil Htisttncei
28. Organization/Addrai*
                                                  29. Organization/ Address
                   Decision Official on Behalf of tha Environmental Protection Agency Program Office
30. Signature
                                        Typed Name and Title
                                                                                 Oat*
                          Action Official on BeheH of the Environmental Protection Agency
31. Signature
Authorizing
32. Signature
Typed Name and Title ft
Date
Official on Behalf of the Other Agency
Typed Name and Title
Date
EPA Form 1610-1 (Rev. 8 841
                                                                                             Page 3 of 5
                                               A-ll

-------
OSWER Directive 9355.0-4A
                         REMEDIAL DESIGN
                          Scope of Work


SITE   [Name, City, State]

PURPOSE

     The purpose of this assignment is to obtain assistance  from
the U.S. Army Corps of Engineers  (USAGE) for the design  of a
remedial action at the [site name].
BACKGROUND

     [Briefly summarize the site in 1 or 2 paragraphs  to include]

     o  [Location of site]
     o  [Brief history of operations, releases, response  actions,
        etc.]
     o  [Quantity, types, and concentrations of hazardous substances]
     o  [Extent of contamination]

     A Record of Decision (ROD) was signed by the  [AA-OSWER  or
RA] on  [date] selecting  [description of remedy] as  the cost
effective remedy for the [site name].

REMEDY

     The remedy selected by EPA and the State of  [state  name]
includes the following components:

     [List major components in bullet form]
WORK STATEMENT

     The USACE will be responsible for:

     1.   Developing the technical statement of work and awarding
          and managing a contract to a private firm for  the
          design of [description of remedy].  The design package
          will consist of the plans and specifications along with
          [include as necessary -O&M Plan, QAPP, Site  Safety
          Plan, etc.).

     2.   Review of the design package in coordination with  the
          EPA-RPM   at approximately 30%, 60%  (if necessary),
          95%, and 100% completion.  Approval and acceptance of
          final design, with concurrence from EPA.

     3.   Providing other support to include  [permit assistance,
          community relations assistance, etc.].

     4.   Reproducing design documents.

     Specific USACE responsibilities are detailed in the
Superfund Remedial Design and Remedial Action Guidance.
                              A-12

-------
                                                           OSWER Directive 9355.0-4A
27. SPECIAL PROVISIONS  (continued)

    In order to help assure successful  recovery  of  CERCLA  funds,  the  USAGE
shall maintain site-specific accounts and  documentation  of the following:

         Employee hours and salary  (timesheets)

         Employee travel and per diem .expenses (travel authorizations,  paid
         vouchers, and treasury schedules)

         Receipts for materials, equipment, and  supplies

         Contract costs (paid  invoices, treasury schedules and copy of  the
         contract)

         Any other costs not included in the above  categories

    In order to assist in the  development  and prosecution  of a cost recovery
action, within three weeks from the date of a request from EPA or the
Department of Justice (DOJ), the USACE will provide to EPA or DOJ
site-specific costs and copies of the back-up documentation which supports
those costs.  EPA and DOJ may  periodically request  updates of the costs and
documentation after the initial request.   The USACE will provide  EPA with a
contact for obtaining such site specific accounting information and
documentation.  This cost information and  documentation must also be
available for audit or verification on request of the Inspector General.

    USACE will provide access  to its files concerning the  project on an
on-going basis for EPA and DOJ examination to assist in cost recovery.  As
original documents may be requested for cost recovery actions, USACE will
provide EPA and DOJ access to  the original documentation when requested.
USACE will notify EPA in advance of placing any  project files in  storage or
archives.

    Reporting requirments are  as follows:

    The USACE will provide the EPA with a  completed signed SF 1080 and
monthly reports containing:

         a.   USACE estimate of the percentage of project  completed.

         b.   USACE estimate of dollars expended on the project to date.

         c.   Summaries of all change orders and claims made on the contract
              during the reporting period.   Attach copies of all change
              orders as appendix.

         d.   Summaries of all contracts with representatives of  the local
              community, public interest groups  or  State government during
              the reporting period.

         e.   Summaries of all problems or potential problems encountered
              during the reporting period.

         f.   Projected work for the next  reporting period.

                                   A-13

-------
OSWER Directive 9355.0-4A
                                     SAMPLE NO.  3
                                        IAG FOR
                          IMPLEMENTATION OF REMEDIAL  ACTION
                                       A-14

-------
                                                                              OSWER Directive 9355.0-4A
       US ENVIRONMENTAL PROTECTION AGENCY
              WASHINGTON. DC 20460

 INTERAGENCY AGREEMENT/AMENDMENT
       Part I — GENERAL INFORMATION
                                                 1. IAG Identification Number
                                   3. Type of Action
                                        New  Agreement
                                                                     2. Funding Location by Regioi
                                                                           *
                                                             4. Program Abbreviation
5. Nome and Address of EPA Organization
         *
                                   6. Name and Address of Other Agency
                                       Department of  Defense
                                       U.S. Army Corps of Engineers  (USAGE)
                                       Engineering Division,  Missouri  River
                                       Omaha,  Nebraska 68101-0103
7. Project Title
     Design of  remedial action at
8. EPA Project Officer (Name. Address. Telephone Numtierl

          *
                                   9. Other Agency Protect Officer /Name. Address. Telephone Number)
                                        William Mulligan        FTS/864-7227
                                        USAGE,  Engineering Division,  Missouri  River
                                        P. 0.  Box 103,  Downtown Station
                                        Omaha,  Nebraska 68101-0103
10. Protect Period
            *
                                   11. Budget Period
                                           *  (same as  project  period)
12. Scope of Work (Attach additional sheets, as needed)
   This Interagency  Agreement  obligates a total of  $     *    to the  U.S. Army Corps of
   Engineers  (USAGE)  for the  design of remedial action at                *
                                           (ID*
                                                ).  These funds are  divided as
   follows:

      1.   $    *
       for  a contract to  design  the remedial action.
      2.   $    *      for supervision  and execution of the contract.   Specific  USAGE
          responsibilities are detailed in  the appended Scope of Work (Attachment A).
13 Statutory Authority for both Transfer nf Funds and Project Activities
	  CERCLA, E.O.  12316  &  Economy Act of  1932,  as amended (31USC1535)
                                                                     14. Other Agency Type
                                                                             Federal
            FUNDS
                                   PREVIOUS AMOUNT
                                                          AMOUNT THIS ACTION
                                                                                    AMENDED TOTAL
  15. EPA Amount
  16. EPA In-Kind Amount
  17. C'her Agency Amount
  18. Other Agency In-Kind Amount
  19 Total Project Cost
20 Fiscal Information
 Program Element
   TFAY9A
 FY
85
 Appropriation
68/20X8145
Doc. Control No.
    *  .
Account Number
    *
Object Class
  25.76
Obligation/Deo&iiga: on Ami
           *
EPA Form 1610-1 (Rev. B-S4) Previous editions are obsolete.
                                                                                               Page I of 5
                                             A-15

-------
OSWER Directive 9355.0-4A
                      PART II - APPROVED BUDGET
                               21. Budget Categories
                                                                                              Total Itemizanon of
                                                                                            Estimated Cott to Oate
    la) Personnel
    Ibl Fringe Benefits
   jcl Travel
    (dl Equipment
    (el Supplier
   (f) Procurement/Assitta nee
   (ol Construction
    IhlOth>
                                                                                   $   (Breakdown  not  available.
    Ill Total Direct Charges
   (il Indirect Costs  Rate
                              «Ba»e
                                                                                       Will be  provided  prior  to
   (k) Tout
     (EPA Shirt 100
%) 	(Other Agency Share
                                                                 reimbursement.)
                                                                              *
 22. Is equipment authorized to oe furnished by EPA or acquired with EPA funds?    fj Yes
   l/dtnlify til tQUtpmtnt costing 3I.OOO or mart)
                                                              I No
 23. Are any of these funds being used on exlramural agreements?    ffl Yes    C NofSt* Htm 21II

   LJ Grant.    LJ Cooperative Agreement, or   £&1 Procurement
    Contactor/ Recipient N*m* lit tnownl
   Unknown
                   Total Extramural Amount Under This Protect
                          *  (Estimate)
Percent Funded by EPA lit known/
      100
                                  PART III — PAYMENT METHODS AND BILLING INSTRUCTIONS
 24  \Ol Disbursement Agreement

          23 Reimbursement
          D
          D
             Advance
             Allocation Transfer
             Request for reimbursement of actual costs will be itemized on SF 1081 or SF 1080 end
             submitted to the Financial Management Office. Environmental Protection Agency. 26 West Si.
             Clair. Cincinnati. OH 45268:

                2fl Monthly    LJ Quarterly    LJ Upon Completion of Work

             Only available for use by Federal agencies on working capital fund or with appropriate justifica-
             tion of need lor this type of peymeni method. Unexoenued iunu« ai u»nuletiori ofwart: v. ;1!:;
             returned to EPA Quarterly cost reports will be forwarded to the Financial Management Office.
             Environmental Protection Agency. 26 West St Clair. Cmcmati. OH 4S268.

             Used to transfer obligational authority or transfer of function between Federal agencies. Must
             receive prior approval by the Office of the Comptroller. Budget Division. Budget Formulation and
             Control Branch. EPA Headquarters	
 25. LJ Reimbursement Agreement
 Other Agency s IAG Identification Number
 Billing Address
                                        Billing Instructions and Frequency
  EPA Form 1610-1 (Rev. 8-84)
                                                                                           Page 2 of 5
                                                           A-16

-------
                                                                             OSWER Directive 9355.0-4A
              PART IV - ACCEPTANCE CONDITIONS
                                                                     IAC lOINTIf ICATION NO.
 26. General Conditions:
   The other agency covenants and agrees that it will expeditiously initiate and complete the project work for
   which funds have been awarded under this agreement.	
 Reimbursement is contingent upon receipt  and approval by EPA  of the monthly progress
 and financial reports from  the  USAGE described below and any  other reports described
 in the appended scope of work.   The monthly progress reports  will be  submitted  to
 (Regional  P.O.)       In EPA Region    .(city)   .  (state) ^  and    (Hq P.O.)        In
 EPA, Washington, D. C.

 EPA acting as manager of the  Hazardous  Substance  Response Trust Fund, reouires  current
 Information on CERCLA response  actions  and related obligations of CERCLA funds  for
 these actions.  In  addition,  CERCLA authorizes EPA to recover from responsible  parties
 all government costs Incurred during a  response action.

                                      (See  Attachment B)
                                    Pert V - OFFER ANO ACCEPTANCE
 NOTE:  1)   For disbursement actions, the agreement/amendment must be signed in duplicate and one original
            returned to the Grants Administration Division for Headquarters agreements and to the appropriate
            EPA IAG administration office for Regional agreements within 3 calendar weeks after receipt or within
            any extension of time as may be granted by EPA. The agreement/amendment must be forwarded to
            the address cited in Item 28 after acceptance signature.

            Receipt of a written refusal or failure to return the properly executed document within the prescribed
            time may result in the withdrawal of the offer by the Agency. Any change to the agreement by the other
            agency subsequent to the document being signed by the EPA Action Official which the Action Official
            determines to materially  alter the  agreement/amendment shall  void the  agreement/
            amendment.

        2)   For reimbursement actions, the  other agency will initiate the action and forward two original
            agreements/amendments  to the  appropriate EPA  program office for signature The agreements/
            amendments will then be forwarded to the appropriate EPA TAG administration office for acceptance
            signature on behalf of the Environmental Protection Agency. One original copy will be returned to the
            other agency after acceptance.
 EPA IAG Adminiitrmon Qfliet Hot Klminiaritni/n<»n»gtintm laitttntil
                     EP* Program Office Her tectimctl tssisttncn
28. Organization/Addrm
          29. Organization/Addrea
                   Decision Official on BeheM of the Environment*) Protection Agency Program Office
30. Signnura
Typed Hunt *nd Title
                                                                                Out
                          Action Official on B«h«H of the Environmental Protection Agency
31 . Signature
Authorizing
32. Signature
Typed Name and Till*
*
Official on BeheH of the Other Agency
Typed Name and Title
Date

Date
EPA form 1610-1 (Rev. 8-84)
                                                                                                3 of 5
                                             A-17

-------
OSWER Directive 9355.0-4A           REMEDIAL  ACTION

                           Scope  of Work


S_IT_E   [Name, City, State]

PURPOSE

     The purpose of  this  assignment  is to obtain assistance from
the U.S. Army Corps  of  Engineers (USAGE)  for  the implementation
of a remedial action at -the  [site  name].

BACKGROUND

     [Briefly summarize the  site in  1 or  2  paragraphs to include]

     o  [Location of  site]
     o  [Brief history o'f  operations, releases,  response actions,
        etc. ]
     o  [Quantity, types,  and concentrations of  hazardous substances]
     o  [Extent of contamination]

     A Record of Decision (ROD)  was  signed  by the [AA-OSWER or
RA] on  [date] selecting  [description of remedy]  as the cost
effective remedy for the  [site name].

     The remedial design  (RD)  for  the remedy  was performed by the
[USAGE or other party].

REMEDY

     The remedy selected  by  EPA  and  the State of [state name],
and detailed in the  IFB includes the following  components:

     [List major components  in bullet form]

WORK STATEMENT

     The USAGE will  be responsible for:

     1.   Conducting procurement activities for  remedial action.

     2.   Managing the contract  for  remedial  action.

     3.   Providing  oversight and  monitoring  of  construction in
          coordination with  the  EPA-RPM, to ensure compliance
          with all contract  requirements.

     4.   Conducting final inspection and certification of
          completed  remedial action  in coordination with the
          EPA-RPM.

     Specific USAGE  responsibilities are detailed in the
Superfund Remedial Design and Remedial Action Guidance.
                             A-18

-------
                                                          OSWER Directive 9355.0-4A

27. SPECIAL PROVISIONS (continued)

    In order to help assure successful recovery of CERCLA funds, the USAGE
shall maintain site-specific accounts and documentation of the following:

         Employee hours and salary  (timesheets)

         Employee travel and per diem expenses (travel authorizations, paid
         vouchers, and treasury schedules)

         Receipts for materials, equipment, and supplies

         Contract costs (paid invoices, treasury schedules and copy of the
         contract)

         Any other costs not included in the above categories

    In order to assist in the development and prosecution of a cost recovery
action, within three weeks from the date of a request from EPA or the
Department of Justice (DOJ), the USACE will provide to EPA or DOJ
site-specific costs and copies of the back-up documentation which supports
those costs.  EPA and DOJ may periodically request updates of the costs and
documentation after the initial request.  The USACE will provide EPA with a
contact for obtaining such site specific accounting information and
documentation.  This cost information and documentation must also be
available for audit or verification on request of the Inspector General.

    USACE will provide access to its files concerning the project on an
on-going basis for EPA and DOJ examination to assist in cost recovery.  As
original documents may be requested for cost recovery actions, USACE will
provide EPA and DOJ access to the original documentation when requested.
USACE will notify EPA in advance of placing any project files in storage or
archives.

    Reporting requirments are as follows:

    The USACE will provide the EPA with the following reports:

    1.   A completed signed SF 1080.

    2.   A monthly progress report containing:

         a.   USACE estimate of the percentage of project completed.

         b.   USACE estimate of dollars expended on the project to date.

         c.   Summaries of all change orders and claims made on the contract
              during the reporting period.  Attach copies of all change
              orders as appendix.
                                   A-19

-------
OSWER Directive 9355.0-4A
        d.    Summaries of all  contacts with representatives of the  local
             community, public interest groups of State government  during
             the  reporting period.

        e.    Summaries of all  problems or potential problems encountered
             during  the reporting period.

        f.    Projected work for the next reporting period.

        Weekly  telecon construction status update(s) to *	,
        EPA,  Region   * .
                                    A-20

-------
                                                           OSWER Directive 9355.0-4A

                                 APPENDIX B
                           ELEMENTS TO BE INCLUDED
                  IN THE REMEDIAL DESIGN STATEMENT OF WORK
The objective of this Appendix is to provide guidance and clarification of
submission requirements for the Architect/Engineer  (A/E) retained to provide
the final document package, which shall include all the required plans and
specifications, in response to the statement of work (SOW)  issued for a
remedial design project.

B.I  Plans and Specifications

    The final construction plans and specifications prepared by the A/E to
accomplish the remedial action proposed in the SOW  shall be required to
comply to certain standards and submissions as outlined herein.

B.I.I  Preliminary Design

    Submission of the preliminary construction plans and specifications
shall reflect the A/E design effort at 30% completion.  At this stage the
A/E shall have field verified the existing conditions of the site.  The
preliminary design shall reflect a level of effort  such that the technical
requirements of the project have been addressed and outlined so that they
may be reviewed to determine if the final design will provide an operable
and usable remedial project.  Supporting data and documentation shall be
provided with the design documents defining the functional aspects of the
project.  The initiation of construction drawings by the A/E shall reflect
organization and clarity.  The scope of the technical specifications shall
be outlined in a manner reflecting the final specifications.  The A/E shall
include with the preliminary submission design calculations reflecting the
same percentage of completion as the designs they support.
                                     B-l

-------
OSWER Directive 9355.0-4A
 B.I.2   Intermediate  Design

     Complex  project  design  may  necessitate  review  of  the  design  documents
 between  the  preliminary  and the prefinal/final design.  At  the discretion of
 the  design PO,  a  design  review  may  be  required at  60% completion of  the
 project.   The  intermediate  design submittal  should include  the same  elements
 as the  prefinal design.

 B.I.3   Prefinal/Final  Design

     The  prefinal/final construction plans and specification submission  shall
 reflect  90%  and 100% completion as  outlined  herein.

     At  90% completion  of design and after all checking  and  coordinating have
 been completed  by the  A/E,  prints shall  be  furnished  to the design PO for
 review  purposes.   Marked prints and/or written comments will  be  returned to
 the  A/E  for  correction of tracings. After  corrections  have been
 incorporated,  the A/E  shall  furnish new  prints of  the corrected  sheets  and
 the  original tracings.   The A/E shall  also  return  all the marked-up  prints
 as evidence  that  the plans  have been completely  checked.

     Final  specifications shall  be submitted  by the A/E  for  review when  the
 overall  project is approximately 90% complete.   After making any necessary
 corrections, the  typed original speciifications  shall be  sent to the design
 PO with  the  complete design.

     The  design  analysis  and design  calculations  will  be furnished for reyiew
 of prefinal  design.  After  making any  corrections  required, reproducible
 sheets  shall be submitted.

 B.I.4   Estimated  Cost  of Project

     An  estimate and  estimate summary sheet  will  be required with prefinal
 design  submittal  ( 90 percent) and the  final  bid  estimate.  One copy  of  the
 quantity take  off sheets, including the  appropriate items,  i.e., treatment
 equipment, linear feet of piping, linear feet of wells, quantity of

                                     B-2

-------
                                                          OSWER Directive 9355.0-4A

hazardous waste to be removed, etc., will be included with each estimate
submitted.  All work items (mobilization, excavating, transportation of
hazardous waste, disposal costs, site containment/rehabilitation, etc.) will
be broken down into labor, material and plant.  The A/E shall provide basis
for development of all unit prices used in the estimate.  Unit prices,
overhead, and profit, and other such categories shall be shown as separate
items.  The final (bid) estimate will be based on the advertised plans and
specifications including amendments.  It will include any changes made by
the design PO during final design review, and should reflect current prices
for labor, material, and equipment.  The final estimate must fit the
specifications bid form and be submitted to arrive not later than 15 days
prior to the scheduled opening of bids.

B.I.5  Correlating Plans and Specifications

    General correlation between drawings and technical specifications, is a
basic requirement of any set of working construction plans and
specifications.  Before submitting the project specifications, the A/E
shall: (1) Coordinate and cross-check the bid form, specifications and
drawings; (2) Complete the proofing of the edited specifications and
required cross-checking of all drawings and specifications.  These
activities shall be completed prior to the 95% prefinal submittal to the
design PO.

B.I.6  Selection of Resource Conservation and Recovery Act (RCRA) Facilities

    The A/E working in conjunction with the lead design party and the
EPA-Region should include a provision in the plans and specifications to
solicit information from bidders on proposed off-site disposal facilities in
order to evaluate acceptability of proposed facilities.  EPA's current
policy on "Procedures for Planning and Implementing Off-site Response
Actions," dated May 6, 1985, requires the following basic procedures be
followed in using off-site facilities:
                                     B-3

-------
OSWER Directive 9355.0-4A
         Facility must have applicable RCRA permit or interim  status,  or
         other applicable permit.

         A RCRA compliance inspection must be conducted at candidate TSD
         facilities within 6 months of the actual receipt of wastes.

         The TSD facilities must meet the minimum technical requirements  of
         the 1984 RCRA reauthorization,  including double liners,  as
         applicable.

         Interim status  land disposal facilities must have adequate
         groundwater monitoring data to  assess whether the facility poses a
         threat to groundwater.

         CERCLA-derived  wastes are prohibited from going to an offsite TSD
         that has significant RCRA violations (Class I or other),  or other
         environmental conditions that affect the satisfactory operation  of
         the facility unless the following conditions are met:

              Owner or operator has committed through an enforcement
              agreement  to correct the problem prior to contract  award and

              Disposal only occurs at a  unit not contributing  to  the adverse
              conditions at the facility.

 B.I.7  Compliance With the Requirements  of Other Environmental Laws

     All  applicable or relevant and appropriate requirements identified in
 the  ROD/EDD shall be analyzed and incorporated into the design by the  A/E.
 Specific A/E responsibility shall include identifing the following: (1) The
 permitting authority(ies); (2) Construction/operating permits  required; (3)
 Time required by the permitting agency(ies) to process the applications(s);
 (4)  Fee  schedule  including filing/application fees, emissions  fees,
 certification testing, etc; (5) Monitoring and/or compliance testing
 requirements; and (6) Actual agency regulations governing applications,
 exemptions, variances, etc.

                                     B-4

-------
                                                          OSWER Directive 9355.0-4A
    At the design PO's discretion the A/E may obtain all required
applications forms, complete all technical sections, and provide the
partially completed forms to the design PO.  The A/E shall notify the design
PO of any major discrepancies existing between the A/E SOW and the pollution
abatement criteria.  Copies of all correspondence from permitting agencies
which either details permit requirements or indicates that no permits are
necessary, shall be furnished to the design PO by the A/E.

B.I.8  Equipment Start-up and Operator Training

    The A/E shall prepare, and include in the technical specifications
governing treatment systems, contractor requirements for providing:
appropriate service visits by experienced personnel to supervise the
installation, adjustment, startup and operation of the treatment systems,
and appropriate operational procedures training once the startup has been
successfully accomplished.

B.2  Additional Studies

    Remedial actions may require additional studies to supplement the
available technical data.  At the direction of the PO for any such studies
required, the A/E shall furnish all services, including field work as
required, materials, supplies, plant, labor, equipment, investigations,
studies and superintendence.  Sufficient sampling, testing and analyses
shall be performed to optimize the required treatment and/or disposal
operations and systems.  There shall be an initial meeting of all principal
personnel involved in the development of the project.  The purpose will be
to discuss objectives, resources, communication channels, role of personnel
involved and orientation of the site, etc.  The Contractor shall submit an
interim report for the purposes of review when he is approximately 90%
complete with the testing.  The interim report shall present the results of
the testing with the recommended treatment or disposal system (including
options).  The report shall include economic analyses of the various
alternatives.  A review conference shall be scheduled after the interim
report has been reviewed by all interested parties.  The final report of the
                                     B-5

-------
OSWER Directive 9355.0-4A
testing shall include all data taken during the testing, a recommendation
for a facility to most efficiently provide the treatment or disposal system
and a cost estimate of such a facility.

B.3  Operation & Maintenance Plan

    Remedial actions vary greatly in scope.  However, in most instances,
there is a requirement for some degree of regular operation and maintenance
activity associated with the completed project.  Appropriate elements are
listed in Exhibit B-l and should be used by the A/E as a guide in preparing
the site-specific O&M plan.  An initial draft O&M Plan shall be submitted by
the A/E to the design PO for review and approval with the prefinal design
documents.  After making necessary corrections, the A/E shall submit the
final draft O&M plan with the final design documents.  The O&M plan will be
finalized and submitted by the Construction contractor at the prefinal
construction conference.

B.4  Quality Assurance Project Plan

    The A/E shall prepare a site-specific Quality Assurance Project Plan
(QAPP).  The plan will include a precise description of the project and
scope of work.  The QAPP must provide guidelines for project organization
and responsiblity including identification of quality control and quality
assurance responsibilities for the construction contractor, lead design
party, and other appropriate agencies during remedial construction.  In
addition, the QAPP will define quality assurance objectives and other
appropriate elements to be included in the plan based on information
provided by the design PO.  The plan shall later be used as a guide by the
contractor to develop a Contractor Quality Control Plan (CQCP) which must be
approved by the design PO before Notice to Proceed is given.  More specific
guidance will be given to the A/E if more specific information or detailed
testing procedures are known by the design PO and are considered necessary.
A detailed "discussion of elements to be included in a State lead QAPP are
discussed in Appendix L of the State Manual, Volume I.  QAPPs for federal
                                     B-6

-------
                                                          OSWER Directive 9355.0-4A
                                 EXHIBIT B-l


Basic Elements of Operation and Maintenance Plan

         A.   Description of Normal Operation and Maintenance

              1.   Description of tasks for operation

              2.   Description of tasks for maintenance

              3.   Description of prescribed treatment or operating
                   conditions

              4.   Schedule showing frequency of each O&M task

         B.   Description of Potential Operating Problems

              1.   Description and analysis of potential operating problems

              2.   Sources of information regarding problems

              3.   Common remedies

         C.   Description of Routine Monitoring and Laboratory Testing

              1.   Description of monitoring tasks

              2.   Description of required laboratory tests and their
                   interpretation

              3.   Required QA/QC

              4.   Schedule of monitoring frequency and when, if so
                   provided, to discontinue.


                                     B-7

-------
OSWER Directive 9355.0-4A
                           EXHIBIT B-l  (Cont'd)

        D.   Description of Alternate O&M

             1.   Should systems fail,  alternate procedures  to  prevent
                  undue hazard

             2.   Analysis of vulnerability  and additional resource
                  requirements should a failure occur

        E.   Safety Plan

             1.   Description of precautions,  of necessary equipment,  etc.,
                  for site personnel

             2.   Safety tasks required in event of  systems  failure (May be
                  linked to site safety plan developed  during remedial
                  responses)

        F.   Description of Equipment

             1.   Equipment Necessary to plan

             2.   Installation of monitoring components

             3.   Maintenance of site equipment

             4.   Replacement schedule  for equipment and  installed
                  components

        G.   A/E  also shall prepare  an  O&M annual  budget  which  should
             include but not be limited to the following:

             1.   Cost of personnel
                                    B-8

-------
                                                      OSWER Directive 9355.0-4A
                   EXHIBIT B-l  (Cont'd)

     2.   Costs of preventive and corrective maintenance

     3.   Costs of equipment, supplies, etc.

     4.   Costs of any contractual obligation  (e.g.,  lab expenses)

     5.   Costs of operation (e.g., energy costs, etc.)

H.   Records and Reporting Mechanisms Required

     1.   Daily Operating Logs

     2.   Laboratory Records

     3.   Records for Operating Costs

     4.   Mechanism for reporting emergencies

     5.   Personnel and maintenance records

     6.   Monthly/Annual Reports to State agencies
                               B-9

-------
OSWER Directive 9355.0-4A
lead and responsible party projects should be consistent with the guidelines
of Appendix L.  A draft QAPP shall be submitted by the A/E to the design PO
with the prefinal design documents.  After making necessary corrections the
A/E shall submit the final QAPP with the final design documents.

B.5  Site Safety Plan

    An important aspect of this project, both during design and
construction, is the health and safety of the individuals who will be on
site.  The A/E responsible for the design of this project shall review the
project information provided and develop specifications for a Site Safety
Plan (SSP) that are sufficient to protect on-site personnel from the
physical, chemical, and/or biological hazards particular to the site.  The
specifications will describe the minimum health, safety and emergency
response requirements for which the construction contractor will be made
responsible, and which must be included in the SSP developed by the
contractor.  Site Safety Plan guidance, along with sample SSPs, is included
in the State Manual, Volume I, and should be used as a guide by the A/E in
developing specifications for the SSP.  Draft SSP specifications shall be
submitted by the A/E to the design PO with the prefinal design documents.
After making necessary corrections, the A/E shall submit the final SSP
specifications with the final design document.

    To ensure consistency with appropriate EPA, OSHA and State health and
safety requirements, the following reference list can be used as guidance in
developing the SSP.

         CERCLA sections 104(f) and lll(c)(6)

         EPA Order 1440.2 - Health and Safety Requirements for Employees
         Engaged in Field Activities

         EPA Order 1440.1 - Respiratiory Protection
                                    B-10

-------
                                                           OSWER Directive 9355.0-4A
         EPA Occupational Health and Safety Manual

         EPA Interim Standard Operating Safety Guide
         (September 1982)

         Part 1910 of 29 CFR revised 1 July 1982, QSHA Standards for  General
         Industry

         NIOSH, (National Institute of Occupational Safety and Health)
         Manual of Analytical Methods, Volumes I-VII

         Threshold Limit Values (TVL) for Chemical Substances and Physical
         Agents in the Work Environment with Intented Changes Adopted by
         ACGIH (American Conference of Governmental Industrial Hygienists),
         latest edition

         ANSI Z 88.2 - 1980, American National Standard, Practices for
         Respiratory Protection

         Air Sampling Instruments for Evaluation of Atmospheric
         Contaminants, 6th edition, 1983, American Conference of
         Governmental Industrial Hygienists.

         Appropriate State health and safety statutes

B.6  Architect/Engineer Services During Construction

    The agency responsible for accomplishing a remedial action may deem it
desirable or perhaps even necessary that the A/E preparing the plans  and
specifications take an active role in the on-site remedial action
(construction) work.  Following are guidelines for consideration in
utilizing A/E services during construction.
                                    B-ll

-------
OSWER Directive 9355.0-4A
B.6.1  Review Construction Contractor Submittals

    The A/E shall check all shop drawings and calculations submitted by the
Construction Contractor.  The A/E is responsible for complete review and
check of the construction shop drawings submitted by the Construction
contractor for compliance with the requirements of the contract plans and
specifications.  The preparation of all shop drawings is the responsibility
of the Construction Contractor.  If submittals are incomplete or are
insufficient to perform review, the construction PO shall be notified
immediately for instructions.  If deficiencies or errors in the plans and
specifications become evident in the process of review and checking of the
submittals, the A/E shall notify the construction PO who will determine the
course of action to be taken.

B.6.2  Attend Conferences and Visit Project Site

    The A/E as and when requested in writing by the construction PO, shall
furnish technically qualified Architects and/or Engineers to attend
conferences and/or visit the project site before or during construction.
These services will include writing of reports and/or preparation of
required cost estimates upon return to the A/E office.

B.6.3  Provide Field Representative

    The A/E shall provide a Field Representative to perform in general the
following:

         Advise the contruction PO on engineering interpretation of the
         Facility plans and specificiations

         Assist the construction PO in interpreting impact on the design of
         proposed changes and preparing sketches and/or revised drawings in
         a timely manner to aid in the preparation of construction contract
         modifications.
                                    B-12

-------
                                                  OSWER Directive 9355.0-4A
Assist the construction PO  and  A/E's  main  office staff in resolving
design problems associated  with interpretation of contract plans
and specifications.

Document design field changes tht  occur  during construction.

Facility start-up testing shake-down

Operator training
                           B-13

-------
                                                           OSWER Directive 9355.0-4A
                                 APPENDIX C

                              LIST OF ACRONYMS
AA                 Assistant Administrator
A/E                Architect/Engineer
CA                 Cooperative Agreement
CQCP               Contractor Quality Control Plan
CRP                Community Relations Plan
E&D                Engineering and Design
EDO                Enforcement'Decision Document
EPA                Environmental Protection Agency
EPA-HQ             EPA Headquarters
FS                 Feasibility Study
IAG                Interagency Agreement
MOD                Memorandum of Understanding
NPL                National Priorities List
O&M                Operation and Maintenance
OSHA               Occupational Safety and Health Administration
OSWER              Office of Solid Waste and Emergency Response
PO                 Project Officer
PRP                Potentially Responsible Party
QAPP               Quality Assurance Project Plan
RA                 Remedial Action
RCRA               Resource Conservation and Recovery Act of  1976  (PL-94-580)
RD                 Remedial Design
RD/RA              Remedial Design/Remedial Action
RI                 Remedial Investigation
RI/FS              Remedial Investigation/Feasibility Study
RPM                Regional Project Manager (EPA)
ROD                Record of Decision
S&A                Supervision and Administration
SCAP               Superfund Comprehensive Accomplishments Plan
SSC                Superfund State Contract
SSP                Site Safety Plan
                                    C-l

-------
OSWER Directive 9355.0-4A
SOW                 Statement of Work
SPO                 State Project Officer
TLV                 Threshold Limit Value
TSD                 Treatment, Storage and Disposal  Facility
USACE               U.S. Army Corps of Engineers
USACE-MRD          USACE-Missouri River Division
                                     C-2

-------
                                                           OSWER Directive 9355.0-4A
                                 APPENDIX D
                              GLOSSARY OF TERMS
    This appendix provides definitions of selected terms used throughout the
text.  It is not intended to be comprehensive in nature; rather, it attempts
to highlight some of the terms commonly used in the Superfund remedial
program.  Statutory definitions have been quoted for those terms defined in
CERCLA, while other definitions have been taken from appropriate EPA
regulations, guidance, and publications.

Bidability;  Refers to the inclusion of all necessary elements and
specifications of a design package to enable solicitation and procurement of
a construction contractor.

Change Orders;  A change order is a written order issued by the State or
USAGE to its contractor authorizing an addition, deletion, or revision.
Change orders are appropriate when the terms of the contract between the
recipient and one of its contractors must be altered to make a change in the
work within the general scope of the contract as a result of changes in
specifications, time, method or manner of performance of the work, services,
site or recipient-furnished facilities, equipment or materials.

Such changes must be within the general scope of the contract.  The goal of
a change order is to leave the contractor in the same relative profit/loss
situation it would have encountered under the original contract award.
Cardinal changes or changes which substantially alter the scope of the work
under the contract may not be appropriate for change order but may require
readvertising for new bids or proposals.
                                     D-l

-------
OSWER Directive 9355.0-4A
Claims:  A claim is a request by a contractor for additional time and/or
fees that has been rejected by the State or USAGE.  Rejection of a change
order may lead to a contractor claim in which the contractor asserts that,
by either action or inaction on the part of the recipient, a change was made
in the contract requirements which affected the contract time and/or price
and caused the contractor to perform in a manner different form that
required by the existing contract.  Significant changes which may alter the
remedy approved in the ROD require EPA headquarters approval.

Community Relations Plan (CRP): A plan for addressing local citizens' and
officials' concerns about a hazardous waste site and for integrating
community relations activities into the technical response at a site.  The
CRP should help prevent disruptions and delays in response actions and
partially fulfill the NEPA requirement for public notification and
participation.  Each CRP should include a description of the background and
history of the site and community concerns about the site; objectives of the
site-specific community relations program; specific techniques to be used to
achieve those objectives; and a work plan, schedule, budget, and designation
of staff who will be responsible for the program.

Constructability:  Refers to the technical feasibility of a design from an
engineering perspective.

Cooperative Agreement (C/A);  An assistance agreement whereby EPA transfers
money,  property, services, or anything of value to a State for the
accomplishment of certain remedial activities, subactivities, or tasks, as
authorized by CERCLA.  It assumes a significant Federal involvement in the
State's performance of these activities.  The remedial Cooperative Agreement
provides general information about the project, such as the approved budget,
and any specific conditions applicable to the project.  It also documents
any required CERCLA section 104(c)(3) assurances.

Deviation Request;  An official written request to allow a deviation from
EPA's General Regulation for Assistance Programs (40 CFR 30).  One example
of a situation requiring a deviation request would be the need to incur
costs at a site prior to the execution of a Cooperative Agreement.

                                     D-2

-------
                                                           OSWER Directive 9355.0-4A
Enforcement Decision Document  (EDD);  Refers to the documentation of the
Agency's decison-making process for approving remedial actions  to be
implemented by responsible parties, showing consistency with CERCLA and the
NCR and supplementing the feasibility study if necessary.

Engineering and Design (E&D) after Contract Award:  E&D after contract award
is engineering and design support during the construction/cleanup phase of
the project.  This support is  provided by the design Architect-Engineering
or in-Jiouse USAGE or State personnel and can consist of the following:

         Preparation of design modifications due to design deficiencies,
         unforeseen site conditions, client request, or changed criteria.

         Site visits and attendance at meetings or conferences.

Federal Lead:  Means that the  EPA has primary responsibility for planning
and conducting either part of  or an entire removal or remedial  action.

Feasibility Study;  A study intended to 1) evaluate alternative remedial
actions from a technical, environmental, and cost-effectiveness perspective,
2) recommend the cost-effective remedial action, 3) prepare a cost estimate
for budgetary purposes, and a  preliminary construction schedule.

Interagency Agreement (IAG);  A written agreement, enforceable by law,
between EPA and another agency (Federal, State, or local) where goods and/or
services are provided, whether or not in exchange for monetary
reimbursement, or where policy agreements are delineated.  lAGs for CERCLA
activities may function both as obligating documents and as reporting
documents necessary for EPA financial and program management.

Memorandum of Understanding (MOU);  An agreement between EPA and another
agency (Federal, State, or local) that sets forth basic policies and
procedures governing their relationship on matters of mutual interest and
responsibility.  There is no exchange of funds under this type of
agreement.  In the context of  this document, an MOU usually refers to one
                                     D-3

-------
OSWER Directive 9355.0-4A
type of agreement which may be negotiated between EPA and  a  State  to
undertake EPA-lead remedial planning subactivities.

National Contingency Plan  (NCP) 40 CFR Part 300:  Officially known  as  the
National Oil and Hazardous Substances Pollution Contingency  Plan,  outlines
the responsibilities and authorities for responding to releases  into the
environment of hazardous substances and other pollutants and contaminants
under the statutory authority of CERCLA and section 311 of the Clean Water
Act (CWA).

National Priority List;  A list of the highest priority releases or
potential releases of hazardous substances, based upon State and EPA
regional submissions of candidate sites and the criteria and methodology
contained in the Hazard Ranking System (HRS), in order to  allocate  funds for
remedial and planned removal actions.

Operation and Maintenance  (O&M);  Refers to the requirement  for continued
performance of activities, as necessary, at a site after the completion of
remedial action or construction to ensure the sustained effectiveness  of the
applied remedy.

Project Officer (PO):  The official designated by the lead party for RD or
RA who coordinates, monitors and manages RD or RA activities for the site.

Record of Decision (ROD);  Refers to the documentation of the Agency's
decision-making process for approving Fund-financed remedial actions,
showing consistency with CERCLA and the NCP and supplementing the
feasibility study if necessary.  The ROD supports future cost recovery
actions at the site.

Remedial Action (RA);  A subactivity in remedial response  involving actual
implementation, following design, of the selected source control and/or
off-site remedial measure.
                                     D-4

-------
                                                          OSWER Directive 9355.0-4A
Remedial Design (RD):  A subactivity in remedial response where the selected
remedy is clearly defined and/or specified in accordance with engineering
criteria (i.e., a site action plan, a relocation plan, or engineering
drawings and specifications) in a bid package, enabling immediate
implementation of the remedy.

Remedial Investigation (RI):  The portion of a subactivity in remedial
response involving an investigation to gather the data necessary to:  (a)
determine the nature and extent of problems at the site; (b) establish
remedial response criteria for the site; (c) identify preliminary
alternative remedial actions; and (d) support the technical and cost
analyses of the alternatives.  (The entire subactivity is known as "remedial
investigation/ feasibility study.")

Remedial Project Manager (RPM):  The designated EPA Regional official who
coordinates, manages, and monitors site activities covered in both EPA and
State-lead remedial response agreements.

Remedial Response:  A series of activities and subactivities intended to
provide permanent resolution of a release or potential release of a
hazardous substance from a site.  Remedial response generally includes the
following sequence of subactivities:  remedial investigation/feasibility
study, remedial design, remedial" action, and operation and maintenance.

Remedy (statutory definition):  [An action] consistent with permanent remedy
taken ... in the event of a release or threatened release of a hazardous
substance into the environment, to prevent or minimize the release of
hazardous substances so that they do not migrate to cause substantial danger
to present or future public health or welfare or the environment.  The term
includes, but is not limited to, such actions ... as storage, confinement,
perimeter protection using dikes, trenches, or ditches, clay cover,
neutralization, cleanup of released hazardous substances or contaminated
materials, recycling or reuse, diversion, destruction, segregation of
reactive wastes, dredging or excavations, repair or replacement of leaking
                                     D-5

-------
OSWER Directive 9355.0-4A
containers, collection of leachate and runoff, on-site treatment or
incineration, provision of alternative water supplies, and any monitoring
reasonably required to assure that such actions protect the public health
and welfare and the environment.

Responsible Party (statutory definition):  [Includes] (1) the owner or
operator of a vessel (otherwise subject to the jurisdiction of the United
States) or a facility, (2) any person who-at the time of disposal of any
hazardous substance owned or operated any facility at which such hazardous
substances were disposed of, (3) any person who by contract, agreement, or
otherwise arranged for disposal or treatment, or arranged with a transporter
for transport for disposal or treatment, of hazardous substances owned or
possessed by such person, by any other party or entity, at any facility
owned or operated by another party or entity and containing such hazardous
substances, and (4) any person who accepts or accepted any hazardous
substance for transport to disposal or treatment facilities or sites
selected by such person, from which there is a release, or a threatened
release which causes the incurrence of response costs, of a hazardous
substance, [the responsible party] shall be liable for -- (A) all costs of
removal or remedial action incurred by the United States Government or a
State not inconsistent with the National Contingency Plan; (B) any other
necessary costs of response incurred by any other person consistent with the
National Contingency Plan; and (C) damages for injury to, destruction of, or
loss of natural resources, including the reasonable costs of assessing such
injury, destruction, or loss resulting from such a release.

Responsible Party Lead:  Means a private party (owner, operator) has primary
responsibility for planning and conducting a remedial action.

Scope of Work;  The element of a Federal lead remedial planning agreement
which generally outlines the subactivities, tasks, and subtasks to be
undertaken at the site.  The scope of work also provides general information
on the objectives of the project.
                                     D-6

-------
                                                           OSWER Directive 9355.0-4A
 Site  (also  refers  to  a  hazardous  substance site or a hazardous  waste site):
 An  area or  a  location at  which  hazardous  substances have been stored,
 treated, disposed,  placed,  or otherwise came  to be located.  This  includes
 all contiguous  land,  structures,  other appurtenances,  and improvements  on
 the land used for  treatment, storage, or  disposal  of hazardous  substances.
 A site may  consist  of several treatment,  storage,  or disposal facilities
 (e.g., impoundments,  containers,  buildings, or  equipment).

 State Lead:  Means  the  State has  primary  responsibility  for  planning an
 conducting  a remedial action.

 State Letter of Request:  The letter, sent from the administrator  of the
 State pollution control agency  to an EPA  Regional  Administrator, requesting
 EPA action  at a waste site.  A  letter of  request can  initiate only EPA  lead
 remedial  planning activities.   The letter must  refer  to  and  generically
 approve the required  remedial subactivities,  agree to  participate  in
 implementing the Community Relations Plan, designate  a State Project Officer
 for the project, and  state that State officials will meet with  EPA personnel
 to exchange site and  project information.

 State Project Officer (SPO):  The designated  State official  responsible for
 direct management of the activities covered in  a Cooperative Agreement or
 for ensuring that the State carries out responsibilities defined in  an EPA
 lead remedial response agreement.

 Statement of Work (SOW):  The element of  a remedial response agreement that
specifies in detail the subactivities, tasks, subtasks, and  objectives to be
 performed pursuant to that agreement.  The SOW  should  contain salient points
regarding the background of the release or potential release, problem
definition, purpose of the work, and a description  of  the services to be
performed.

Stop Work Order:  A form prepared by an Ordering Officer, OSC, or
Contracting Officer requiring the contractor to stop all, or any part, of
the work  called for in a Delivery Order.
                                     D-7

-------
OSWER Directive 9355.0-4A
Superfund State Contract (SSC):  A bilateral contract between EPA and  a
State that is legally binding on both parties.  The SSC is not  a procurement
contract, but is used to document EPA and State responsibilities and to
obtain any necessary State assurances for EPA-managed remedial  responses.
An SSC is appropriate for any EPA lead remedial implementation  subactivities
which require State cost-sharing.

Supervision and Administration (S&A);  S&A consists of supervision and
administration of the construction/clean up contract.  This is  primarily
accomplished by USAGE or State in-house personnel, but assistance from the
design Architect/Engineer may be required.  Specifically S&A includes the
following:

         Contract Administration

         Site inspection and construction management performed  by on-site
         personnel

         Shop drawing review

         Preparation of as-built drawings reflecting final completed project
         conditions.
                                     D-8

-------
                                                            OSWER Directive 9355.0-4A
                                  REFERENCES
1.  U.S. EPA, State Participation  in  Superfund Program, Volume 1, February
    1984 as amended.

2.  U.S. EPA, State Participation  in  the Superfund Program, Volume II:  State
    Procurement Under Superfund  Remedial Cooperative Agreements, March 1986.

3.  McGraw, Jack W., "Procedures for  Planning and Implementing Off-site
    Response Actions," U.S.  EPA  Memorandum,  May 6, 1985.

4.  "CERCLA Compliance with  Other  Environmental Statutes,"  Appendix to
    Preamble of National Oil  and Hazardous Substances Pollution Contingency
    Plan; Final Rule, (50  FR 2892.6),  November 20, 1985.

5.  U.S. EPA, Community Relations  in  Superfund:  A Handbook, September 1983.

6.  Thomas, Lee M., "Interim Procedures  for  Deleting Sites from the National
    Priorities List," U.S. EPA Memorandum, March 27, 1984.
                                     R-l             OU.S. GOVERNMENT PWNT1NO OFFICE: 1880 -646-116/20842

-------