NATIONAL PROFILE
                 OF SECTION 208
         AREAWIDE MANAGEMENT
             PLANNING  AGENCIES

                      JULY 1975
ENVIRONMENTAL PROTECTION AGENCY

    Washington,D.C. 20460

-------
                 NATIONAL PROFILE
                    OF SECTION 208
           AREAWIDE  MANAGEMENT
               PLANNING AGENCIES

                           JULY 1975
               PROJECT DIRECTOR - MICHAEL L. FRANKEL

               PROJECT STAFF   - CONSTANCE L. CASTLE
                           CHERYL J. DINNEEN
                           PATRICIA C. HIGGINS
                           CAROLYN M. HOCK
                           JEAN A. LYNCH
                           DAVID H. MECKLER
                           JANE M. NOWAK
                           ADAM POE
                           STEPHEN G. PRESSMAN
PREPARED UNDER CONTRACT NO. 68-01-3195
  ENVIRONMENTAL PROTECTION AGENCY

-------
                              PREFACE
        This report summarizes a national profile of local planning
agencies designated under Section 208 of the Federal Water Pollu-
tion Control Act Amendments of 1972.  The project was conducted by
Centaur Management Consultants, Inc. during July and August of 1975
under an EPA contract (No. 68-01-3195) to the Areawide Management
Branch.

        The nine-member project staff was recruited from the urban
and regional planning schools of George Washington University,
Georgia Institute of Technology, Harvard University, Johns Hopkins
University, Stanford University and the University of North Carolina
at Chapel Hill.

        The national profile prepared by this staff represents a
literature review of grant applications and designation packages
from all 149 designated planning agencies and personal interviews
with 136 local planning agencies.  However, the project was not a
research effort.  The facts and figures gathered through the inter-
views were not verified.  Information in the designation packages
and grant applications was not always complete, and often supple-
mented with an "estimate" by the interviewee.  Consequently, the
data is most useful as a general profile of 208 agencies and their
activities.  It should be viewed as the local 208 staffs' best ap-
proximation of information at this time.

        The project staff appreciates the guidance and support pro-
vided by the Water Planning Division of EPA and the time and advice
given by the EPA Regional 208 coordinators.  The staff also thanks
the local 208 agency staffs who gave their time for the interviews.
Finally, the staff extends its gratitude to Ken Regelson for his
tireless efforts in seeing to the technical and administrative day-
to-day needs of the project staff.
                                 Michael L. Frankel
                                 Project Director
 Second Printing

-------
                          TABLE OF CONTENTS


                                                                Page


INTRODUCTION 	   vi i

     Project Methodology 	   vi i
     Major Issues 	    ix

CHAPTER I - AGENCY PROFILE

     Findings 	     1
     Physical Characteristics of 208 Areas	     2
     Type of Agencies Designated 	     3
     Experience of Agencies 	     4
     Staffing of Agencies 	     5

CHAPTER II - ENVIRONMENTAL ASPECTS

     Findings 	     7
     Current Water Qua!1ty Problems 	     7
     Lack of Water Qua!i ty Data 	     9
     The Impact of 208 on Achieving the 1983 Goals  	    11

CHAPTER III - LAND USE ASPECTS

     Findings 	    13
     Land Use Consideration 1n the 208 Planning Process 	    13
     Relationship of Nonpoint Source Pollution and  Land Use...    16

CHAPTER IV - MANAGEMENT/INSTITUTIONAL ASPECTS

     Findings	    17
     Designated Agencies' Capabilities in Management
          Planning ...»	    18
     Major Issues 	    19

CHAPTER V - PUBLIC PARTICIPATION

     Findings 	    25
     Who is the Public?	    25
     A Shift in Approach 	    26
     Experience with Public Participation Programs  	    26
     Budget and Staff  	    27
     Commi ttees 	    28
     Public Education  	    29
     Public Input and Feedback 	    31
     Problem Areas 	    32

-------
                     TABLE OF CONTENTS (CONT'D)

                                                                Page
CHAPTER VI - BUDGET
     Findings 	   35
     Grant Awards 	   35
     Work Plan Budget 	   37
     Contracts 		   41
     Contract Activities	   42
     Type of Contracts	   43

CHAPTER VII - TIMING AND FINANCIAL PROBLEMS

     Findings 	   45
     Timing and the Two-Year Planning Period 	   46
     Financially Self-Sustaining Planning Process 	   49

CHAPTER VIII - DESIGNATION AND GRANT APPLICATION

     Findings	   51
     Why Enter 208 Planning?	   51
     The Designation Process 	   51
     Preparation of Designation Package and Grant Application.   52
     Problems in the Designation and Grant Application
          Process	   52
     Resolutions of Intent	   54
     Cost of Grant Application 	   55
     Assistance and Coordination 	   56

CHAPTER IX - COORDINATION

     Findings 	   57
     Coordination Between 208 and 303(e) Basin Planning 	   57
     Coordination Between 208 and the NPDES 	   58
     Coordination Between 208 and 201 Municipal Facilities
          Planning 	   58
     Coordination with Other Environmental Programs and
          Other Areawide Planning Programs 	   59
     Coordination Between 208 and State 	   59
     Means of Coordination 	   59
                                 11

-------
                     TABLE OF CONTENTS (CONT'D)

                                                                Page
CHAPTER X - EVALUATION AND GUIDANCE

     Conclusions and Findings 	   63
     208 Draft Guidelines 	   63
     Designation and Work Plan Handbooks 	   63
     Workshops 	   64
     OBERS Projections 	   65
     Technical Guidance  	   65
     Management/Legal/Institutional Seminars 	   67
     Other Suggestions 	   69
APPENDIX A - STATISTICAL DATA

APPENDIX B - PLANNING AGENCY DIRECTORY

APPENDIX C - REGIONAL 208 MAPS
                                  m

-------
                               LIST OF TABLES
Table                               Title                            Page

   1      Partial  and Total  SMSA's within 208 Boundaries 	    2

   2     Type of Agency Designated 	    3

   3     208 Agencies'  Experience in Planning 	    4

   4     Other Planning Functions Performed by 208 Agencies 	    5

   5     Factors Responsible for Designation 	    8

   6     Problem Parameters in 208 Areas 	   10

   7     Achievement of the 1983 Goals 	   12

   8     Reasons for not Meeti ng the 1983 Goal s 	   12

   9     Percent of the Budget Allocated for the Land Use
             El ement Under 208 	   15

  10     Substantial Nonpoint Sources 	   16

  11     Who Will Do Legal/Management/Institutional Work
             Element of 208 Plan? 	   18

  12     When Will Management Alternatives Analysis Begin? 	   19

  13     Experience in Public Participation Programs 	   26

  14     Percent of Budget Allocated for Public Participation 	   27

  15     Responsibility for Public Participation Programs  	   28

  16     Requests for Briefing on 208 Program 	   29

  17     Discrepancies Between Requested and Awarded Grant
             Amounts 	^	   36

  18     Summary Table:  Sample Budget Allocations  	   40
                         (Regional Averages)

  19     Anticipated Problems During the 2-Year Planning Period  ...   47

  20     Response on Ability to Attain Legal Powers for Manage-
             ment Agency Prior to 2-Year Deadline  	   48
                                     IV

-------
                          LIST OF TABLES (CON'TO)

Table                               Title                          Page
 21      Total Time of Designation Process 	    52
 22      Major Problems in the Designation and Grant
             Application Processes 	    53
 23      Cost of Grant Applications 	    56
 24      Number of Agencies Which Mentioned the Methods of
             Coordination Used in Relation to the  Organiza-
             tions Listed 	    61
 25      Workshop Attendance by Agency 	    64

-------

-------
                            INTRODUCTION
        At the end of FY 1975, a total of 149 local planning agencies
had been designated and awarded planning grants under Section 208 of
the Federal Water Pollution Control Act Amendments of 1972.  A nation-
al profile of these local planning agencies was conducted during the
first two months of FY 1976 in order to characterize the 208 agencies
and their preliminary activities towards areawide management planning.
The purpose of this report is to summarize this national profile.  It
must be emphasized that this report is based on available information
at this point in time in the first month of the planning process.  The
data is a reflection of the local perspective of 208 planning, and
does not address the state or federal viewpoint.
Project Methodology

        The project staff met in Washington, D.C., the first two weeks
of June to review the 208 program and develop a set of questions and
issues for the interviews.  During this time they met with staff from
EPA Headquarters, private consultants, and pre-tested the profile on a
local 208 agency.  Over the next 8 weeks staff members were then as-
signed to a Regional office, where they met with the EPA Regional
Coordinators to review tiie office 208 files.  They subsequently inter-
viewed the designated agencies within the Region.  When the interviews
were completed, the staff returned to Washington to analyze the data
and prepare this report.

        The review of designation packages, grant applications and work
plans was conducted along the lines of a structured profile.  This in-
formation was then reviewed with the local 208 planning agency staff to
corroborate the information and to supply additional information not
covered in the available documentation.  The structured profile con-
sisted of approximately 175 items of information under the following
headings:

                  Area Description
                  Designated Agency Description
                  Coordination Activities
                  Designation Process
                  Grant Application Process
                  Work Plan
                  Public Participation
                  Land Use
                  Legal/Institutional/Management Issues
                  Financially Self-Sustained Planning
                  Evaluation of Technical Aids
                                VI 1

-------
        136 of a possible 149 interviews were completed.   Of the 13
agencies not interviewed, 9 were in Region IX.   In some cases,  how-
ever, information was unavailable, or agencies  were unable to answer
the questions as asked.  Thus, the total responses to each question
does not always add up to 136.  Whenever possible available docu-
ments were studied to try to answer some of the profile questions
when no interview was done, thus, in some cases the number will  be
14y— the total  number of 208 agencies.

        Whenever a dash (-) is used in a table, it means that the
question was asked and the response was  negative, or that it was not
a factor.  Whenever a blank appears, it  means that there was no re-
sponse.  This is due to any of three factors, the net result being
no information.  The factors are:

        1)    The interviewee did not have the  background to
              answer the question.

        2)    The question was not asked due to lack of time.

        3)    The information was not available at that time.

The number of agencies for which there was no information for that
particular question is totaled by region in the "no answer" column.

        For some questions, agencies were asked to check several
items when more than one answer applied.  In these cases, total  re-
sponses will add to more than 136.

        Interviews generally took 3-4 hours.  They were made with
one person ("lead interview"), although  other staff were often in-
volved  in answering some of the questions.  Of  the 136 agencies
interviewed, 81 of the "lead interviews" were with the 208 project
directors.  When a 208 project director  was either not yet hired or
was not available, lead interviews were  conducted with directors of
the parent agency (27), with staff who wrote the original applica-
tions  (16), with acting directors (4), and with other program direc-
tors of the parent agencies (5).  Many interviews involved more than
one person and over 86 other people were involved in part, including
water quality engineers, planners, public participation specialists,
citizens groups, and representatives of  Indian  organizations.
Section 208 of the Federal Water Pollution Control  Act Amendments of
T977

        Section 208 areawide planning and management is a comprehen-
sive program established to bring about environmental quality on the
nation's waterways by 1983.  The program is designed for areas with
substantial water quality control problems due to urban-industrial
concentrations or other factors.
                               VI 1 1

-------
        This program ties together the various federal water pollution
abatement requirements including municipal, industrial, residual waste,
runoff, and groundwater pollution abatement.  The responsibility for
planning and implementing these provisions rests with regional and
local agencies.
Major Issues

        Several key issues were consistently expressed in the review
of local planning agency documents and in the interviews with local
208 project staffs.  These issues, discussed in more detail in the
following chapters, are summarized below.
              Two-Year Planning Period — Evan though the agencies
              understood 24 months was the allotted planning period,
              they consistently asked for relief.  Those interviewed
              claimed that two years was too short to accomplish
              all the analysis, planning, evaluation and approval
              required for the 208 plan.  Staff recruitment, adminis-
              trative organization, and the need for detailed work
              plans cut into the beginning of the 24-month period.
              Requirements for public participation and local review
              and approval were consistently reported to be very
              time-consuming and cut significantly into the planning
              period.
        •     Management/Institutional -- There is a strong commit-
              ment on the part of the designated agencies to develop
              and implement a management system, but at this time in
              the planning process, it was unclear what that system
              will look like, how it will be created and what powers
              it should exercise.  Most agencies, however, did fore-
              see a single planning agency and several management
              agencies as the probable framework.  The majority will
              opt for modifications of existing arrangements rather
              than major institutional changes.  The general insist-
              ence on "local autonomy" by jurisdictions within the
              208 areas will be a serious constraint on innovative
              regional management alternatives.
              Financially Self-Sustaining Planning Process -- Most
              208 agencies expressed serious doubts about their
              ability to continue planning on a financially self-
              sustaining basis after the 24-month period expires.
              Local governments will not be able to raise enough
              money on their own.  Furthermore, they don't consider
              themselves bound by their resolutions-of-intent to pay
              for 208 planning after the termination of the grant,
              and presently are not showing financial commitment to
                                 IX

-------
the continuing planning process.  Federal  and state
financial assistance is therefore essential  if 208
is to be the ongoing program it was intended to be.
State Water Quality Information -- A major deficiency
exists in the State 303(e) Basin Plans.  Generally,
303's, in particular waste load allocations were
either incomplete at this time, or inadequate because
they were based on insufficient data (e.g. based only
on dissolved oxygen content or incorrect sampling
methods.) This places an extreme burden on 208 agen-
cies which necessarily rely on the availability and
quality of such data in the early stages of the plan-
ning process.  It additionally places economic hard-
ship and time delays on those agencies which must
undertake the monitoring, modeling, and analysis ef-
forts themselves.
Budgets -- Budgets were generally inconsistent in
format and incomplete in preparation at the time of
interview.  This was due to a lack of budgetary
guidance (or its late delivery), and a lack of staff
and expertise in price and cost analysis.  If EPA
should choose to assemble this data nationally, it
will be very difficult to either analyze the direc-
tion (foresight), or evaluate the progress (hind-
sight) of the 208 program.
Public Participation -- 208 Agency expenditures for
public participation generally concentrate on a one-
way flow of information to the public.  This is
necessary as a first step, but is certainly not
sufficient.  Mechanisms for feedback resulting from
such efforts are necessary.  If the general public
is not accounted for except in the committee struc-
ture, it may create potential  problems with plan
acceptance.  Furthermore, a major benefit in terms of
public awareness will  be lost  to 208.
Technical Guidance — There is a serious delivery
problem with EPA guidance between the Federal levels
and local 208 planning agencies.  A significant num-
ber of agencies never received the Handbooks, while
over half of the agencies received them too late to
be useful.  The needs for technical guidance are
similar throughout the country.  The greatest demand
was consistently for nonpoint source analysis, moni-
toring (point and nonpoint), urban storm water, and
combined sewer analysis.   The most requested manage-
ment/legal/institutional  seminar is for state speci-
fic legislation to enable alternative management
structure.

-------
                           AGENCY PROFILE



Findings

        An examination of the characteristics of designated 208 plan-
ning shows several interesting and potentially significant aspects.
Although each agency must respond to unique environmental conditions
and a unique political institutional setting, there are many similar-
ities which make comparisons beneficial.  Furthermore, it is useful
to identify unusual circumstances and approaches that may suggest
improvements for the program as a whole.  Some of the most significant
findings are:

        •     Most 208 agencies are under the auspices of a
              parent agency' that has been in existence for
              several years and that conducts a variety of
              planning functions.  A small number of agencies
              have been newly created and should be given
              high priority for additional guidance in their
              208 effort.  The starting point of these agen-
              cies is considerably behind that of established
              agencies.  Those agencies with no water quality
              experiences should also be a high priority for
              special guidance and assistance.
              When in full operation, over 800 persons will
              be working full time on 208 staffs and another
              800 "borrowed" from other agencies on a tempor-
              ary basis.  In addition, somewhere between 400
              and 1,000 man-years of consultant time will be
              spent on 208 planning through contracts.
Physical Characteristics of 208 Areas

        The 208 area boundaries cover 390,562 square miles, or over
one-tenth of the country.2  In population, the program serves
95,403,219 people, or just under one-half of the country.3  In re-
sponse to the initial legislative intent to address urban/industrial
water quality problems, 90 SMSA's are totally included in 208
1
 Parent agency refers to the larger organization of which 208 planning
 is only one function.  It is generally the RPA, COG or EDO, and the
 official recipient of the grant.
2
 Total area including Alaska, Hawaii and territories is 3,628,066.
3
 Total population of the U.S. in 1970 was 203,235,298.

-------
 boundaries and  49 more SMSA's are  partially  Included.4  The follow-
 ing  table Indicates the number of SMSA's  that are either partially
 or totally Included 1n 208 areas.   (Table 1)

         208  1s also Institutionally complex because  1t Involves so
 many levels  of governmental units,  making coordination a key Issue.
 Only eight states (Hawaii, Alaska,  Vermont, Connecticut, Minnesota,
 Louisiana, Nebraska and New Mexico) have  no 208's.   Three states are
 Included only through Interstate 208 areas, and have no ongoing 1ntra-
 state 208 planning.  385 counties are fully Included within 208
 boundaries and 111 more are partially Included.
                              Table 1

          PARTIAL AND TOTAL SMSA'S WITHIN 208 BOUNDARIES
No. of
SMSA'S

  0

  1

  2

  3

> 3


No answer
Total        17   11   12   28   25    9    5   22   10   10    149
REGION
1
5
10
2
—
2
2
7
2
—
3
3
8
1
—
4
3
21
2
—
5 6
1
12 7
9 -
3 1

789
2 13 2
3 8 4
3
_ _ —

10
3
7
-
_
 4
  On April 5, 1974 there were 269 SMSA's in the country.  The number
  of partially included SMSA's is overstated due to the double count-
  ing resulting from one SMSA being in more than one 208 area.

-------
Type Agencies Designated

        The following table  indicates the type of agencies designated
to do 208  planning.

                              Table 2

                     TYPE OF AGENCY DESIGNATED
      ~~Water Quality
                      Agencies or
COG, RPA    County    Sanitation    Inter!oca!          Not
 or EDO  Government   Districts    Agreement  Other Available  Total


   113          9          5           778       149
        In the majority of cases (113 or 84%) this meant a regional
government, usually called a Regional Planning Agency (RPA) or a
Council of Government (COG) or an Economic Development District.
There is not a meaningful distinction between these three; the differ-
ences in name were generally explained by choice of wording 1n state-
enabling legislation.

        In some cases the traditional regional planning agency was
not the designated 208 agency.  The 16% non-COG type agencies repre-
sent a range of governmental units with varying powers.  Nine desig-
nations were to county governments or county planning boards and five
are to water quality agencies or sanitation districts.  These agencies
may have considerably more implementing powers and therefore may be
able to provide a smoother transition to the management phase and on-
going planning process than the typical COG.

        In a few instances, non-regional agencies were designated.
Rhode Island State Office of Planning is a case of statewide 208 plan-
ning.  Special arrangements were made to conduct 208 planning in Guam
and in Puerto Rico.   In New York City, the Environmental  Division is
the designated agency, while the Delaware River Basin Commission is
doing planning for three 208 agencies.

        Seven 208 designations were made to two agencies jointly
through a consortium or an interlocal agreement.  In most of these
cases, both agencies had originally applied for 208 designation in
the same or in adjoining areas.  The  nature of the water quality  prob-
lem was such, however, that a  joint approach made more sense.   In
these instances a lead agency was chosen and a Joint Working Task
Force formed.  Formal working agreements and work outlines were re-
quired as a condition of ,designation  either by the Governor or  by EPA.
                                  3

-------
Experience of Agencies

        208 agencies'  experience 1n planning 1s presented below.


                              Table 3

               208 AGENCIES'  EXPERIENCE IN PLANNING
New
Agency
Less than
2 Years
2-5
Years
5-10
Years
Over
10 Years
Not
Available
Total
  17
14
16
55
34
13
149
        Only 17 agencies were newly created to do 208 planning.  About
half of these were in Region VIII.   All  other designated 208 agencies
already existed, nearly 65% within  an agency that has been 1n exist-
ence for five years or more.  This  previous agency experience will be
a valuable asset to 208 planning, particularly in light of the short
time 208 has to begin producing outputs.  Such agencies cannot only
offer familiarity and Informal contacts  within the designated areas,
but also have data, offices and staff that can be shared.   98 of the
208 agencies are physically located in the same place as the parent
agency.

        Coordination is another advantage to this parent-208 relation-
ship.  Only fifteen of the agencies conducted just 208 or one other
kind of planning.  80 of the parent agencies conduct at least five
other kinds of planning functions.   The  most common were HUD 701,
noted as a prime function of at least 109 agencies and areawlde trans-
portation planning which was a responsibility for 92 agencies.  This
situation provides an excellent opportunity for coordination and for
joint efforts.  84 programs are A-95 review agencies.  This fact will
become more important during the implementation phase of 208.

        As for other environmental  planning responsibilities, 62
parent agencies conduct solid waste planning, 29 do air quality plan-
ning, and 32 do Coastal Zone Management  work.  Thus, there is a high
potential for inter-media coordination.

        The following table presents the breakdown of the various
other planning functions performed  by 208 agencies.

-------
                              Table 4

        OTHER PLANNING FUNCTIONS PERFORMED  BY  208 AGENCIES
          Planning Program
Number of Agencies
DOT

Coastal Zone Management

HUD 701

Air Quality Maintenance Area

Solid Waste

Areawide Transportation

Corps of Engineers

Forest Service

Soil Conservation Service

A-95 Review
       32

      119

       29

       62

       92

       21

       14

       22

       84
        As for water-related planning experience, only 30 agencies  had
no previous experience.  28 had direct experience, many having  com-
pleted a 3-C plan.  69 had related experience either in-house or
through consultants.  Thus, nearly three-quarters are at least  partially
familiar with the water quality and their related institutional  problems.
Staffing

        By the time of the interviews (July 1975) 325 professionals and
97 non-professionals were working in 208.  Anticipated nationwide totals
are for 653 professionals and 184 non-professionals.   In addition 208
agencies expect to "borrow" from parent agencies and  other agencies an
additional 834 persons.  These would most often be legal, financial,
public participation, land use planners, executive directors and secre-
taries, who will spend most of their time on other projects, but will be
available to 208.  Thus,-in 136 agencies nearly 1,700 staff people will be
involved in 208 in some way, once 208 is in full operation.  These 1,700,
however, will not necessarily be newly hired.  Many,  perhaps the
majority, will be switched either from the parent agency or an agency

-------
dealing with water quality planning.  Consultants form another signi-
ficant manpower resource for the 208 planning effort.  Based on the
percentage of grants for outside contracts (see Budget), it 1s esti-
mated that between 400 and 1,000 consultant man-years will be employed
during the two year planning period.  This estimate is based on the
average value of contracts and average consulting man-year costs.

        75 agencies indicated that staffs were only being hired for
the two year planning period due to the uncertainty of future funding.
This may have unfortunate consequences to 208 during the ongoing
period following the Initial two years.  The earlier 1974 programs
experienced some problems in staff hiring because 208 was still unheard
of.  More recent programs have had no trouble hiring planners, but some
problem hiring experienced people.  This was mentioned in connection
with the unattractiveness of a limited two year job for upper level
engineers.

        Given the dual technical/management nature of 208 it is inter-
esting to look at the backgrounds of those who will  be chiefly respon-
sible for the final end-products.  98 of the 208 Project Directors had
been hired by the time of the interviews.  65 are planners by disci-
pline, 18 are public administrators, and 34 are sanitary or civil
engineers.  The rest all have backgrounds in various disciplines.
Thus, the disciplines of the directors would seem to reflect a recogni-
tion of the planning/management aspects of 208.

-------
                        EWIROflOTAL ASPECTS


Findings

        A review of the environmental problems facing 208's around the
country uncovered the following major issues:
              The water quality factors most often cited as
              critical to designation as a 208 agency were water
              quality limited segments, substantial  industrial
              pollution,  and urban storm drainage.
              The water quality parameters considered critical
              to meeting1 the 1983 goals were coliform bacteria,
              dissolved oxygen and nutrients - these turn out to
              be the most often and easily measured.
              Water quality data essential to 208 plans was
              often incomplete or unavailable because the states
              are not producing the required 303(e) outputs.
              Many agencies are therefore placing great emphasis
              on their own monitoring efforts.
              The two major problems in monitoring and analysis
              are   1) regional differences in the administration
              of EPA monitoring/modeling policy,  2) scheduling
              monitoring activities within the 24-month period.
              The  primary reasons for not achieving the 1983
              "fishable, swimmable" goal are  1) lack of tech-
              nology for nonpoint source control and  2) lack
              of public funds for structures to control urban
              storm water.
Current Hater Quality Problems

        The following table  lists those water quality factors mentioned
as reasons for areawide designation.

-------
                                       Table 5

                        FACTORS  RESPONSIBLE FOR DESIGNATION
FACTORS

Water quality limited segments
Preservation/Protection of high
quality waters involving --
unique resource impaired by
growth
complex institutional setting
complex sources of pollution
state preservation statement
(non-degradation)
Municipal waste management by
two or more local governments
Substantial industrial pollution
problems
Substantial urban storm drainage
Substantial nonpoint sources
agriculture
silviculture
mining
construction
septic fields
benthic (sludge)
combined sewer overflow
urban storm water
fecdlots
other
Groundwatcr Pollution
contaminated groundwater of
major water source
groundwater pollution con-
tributes to surface \Mter
problem
complex groundKuter problem
state or area grcundwater goal
saltwater intrusion
other

1
15



14
11
15

15

16

13
13

13
6
5
13
IS
13
11
13
6
2


13


11
11
12
2
2

2
M



5
4
5

3

8

9
9

4
-
2
8
7
6
5
8
3
-


5


5
5
3
4
-

3
9



5
6
6

3

8

8
6

9
5
3
9
8
5
5
8
5
1


4


3
4
2
4
-
R
4
22



7
5
6

5

20

20
20

20
6
4
19
19
3
6
18
9
-


6


7
7
3
6
-
E G 1
5
21



10
11
7

7

11

20
15

17
3
3
8
11
7
21
15
5
7


12


2
2
1
1
1
0 N
6
5



1
3
2

-

5

5
2

2
-
1
2
2
-
-
3
2
-


-


-
1
-
-
-

7
4



4
5
5

1

5

4
4

3
-
2
2
4
2
3
4
1
1


2 '


1
1
-
-
.

8
15



9
8
5

6

9

11
12

7
6
14
13
7
_
3
10
9
1


11


4
4
-
-
_

T
3



3
-
2

3

1

3
2

1
1
4
4
.
1
5
2
1
4


-


1
1
-
-
_

~TO~
9



7
5
6

4

2

5
-

9
7
4
9
6
4
3
8
2



-


-
-
-
-%
_

Total
103



65
58
59

47

85

98
83

76
26
38
74
74
45
59
79
40
16


40


34
35
18
16
3
Discharge fror v:astewatcr treat-
ment plants
                                                                                         11

-------
Lack of Uater Quality Data

       An essential ingredient for a successful 208 program is the
availability of water quality data which accurately defines problems
in such a way that control strategies and alternatives can be devel-
oped.  Incomplete and often unavailable water quality information
was causing considerable problems for 208 agencies.  Many agencies
expressed concern that this would delay the completion of their plan.
The agencies reported that the 303(e) Basin Study outputs are not
sufficiently developed, and sometimes not readily available to satisfy
the needs of the 208 agencies (see Chapter on Coordination).

       About one-half of the agencies have waste!oad allocation infor-
mation available.  However, many of those agencies feel  that the allo-
cations will need revaluation.  The most often cited reasons for re-
evaluation were insufficient data, faulty modeling, and a lack of
confidence in the results.  The other half of the 208 agencies did not
mention having wasteload allocation information.  This is due to one
of three reasons:  The states have not developed wasteload allocations
yet, the programs have not contacted the states for the wasteload
allocation information, or the fact that some areas do not have water
quality limited segments and, therefore, wasteload allocations are not
applicable.  Regardless of the source of the problem, the lack of
availability of useable data will  delay the program.

       The lack of available information has generated great concern
about monitoring and analysis.  83 agencies stated that monitoring
will definitely be conducted in their areas; 10 stated that they might
do it.  The most often cited reasons for doing monitoring were ranked
as follows:  to determine the spatial and temporal extent of the prob-
lem, to determine whether certain problems exist, to measure the magni-
tude of nonpoint source loads, and to collect, calibrate or verify
data for nonpoint source analysis.  The interviewees stated that the
credibility and acceptance of 208 pollution control strategies would
depend upon sufficient data to demonstrate the cause/effect relation-
ship between land use and water quality in their particular areas.
They feared that incomplete information might result in delay of plan
approval and court action by impacted localities and industries.

       The 208 agencies anticipated two major problems in monitoring
and analysis.  One problem occurred in getting monitoring activities
approved by the Regional EPA office.  Some Regions interpreted the
Program Guidance Memorandum, AM-8 to mean little or no monitoring and
modeling should take place, while other Regions assessed the monitor-
ing and modeling requests on a case-by-case basis.  Those agencies
that are not monitoring anticipate problems establishing control
strategies.  In several instances, monitoring was not permitted in
water supply areas despite the fact that they were prime areas for
residential growth.

-------
       The presence of water quality limited segments was the major
reason for areawlde designation in 103 areas.  Industrial pollution
(98 mentions), municipal  waste by two or more local governments (85
mentions), and substantial  urban storm drainage (83 mentions) are
other nationally significant water quality problems.

       In the area of nonpoint sources, the predominant problem is
urban storm water in 79 areas.  76 agencies stated both construction
and septic fields as nonpoint source pollution problems.

       Where groundwater pollution was a problem, it was considered
a major and difficult task 1n water quality management.  The most
important groundwater problem mentioned was the contamination of
major groundwater drinking supplies (40 mentions).  35 agencies
stated they had a groundwater problem, and 34 said their groundwater
problem contributed to surface water pollution problems.

       Important water quality parameters (and the number of agencies
that mentioned them) are presented in the following Table 6.  The table
totals the number of responses for each parameter by Region.  The ex-
tent of these problems Is not really known, particularly with regard
to groundwater
                               Table 6

                   PROBLEM PARAMETERS IN 208 AREAS

                                      REGION

Dissolved Oxygen(D.O.)
Nutrients
Col i form bacteria
Suspended Solids
Pesticides/Herbicides
PH
Heavy metals (specify)
Toxics (specify)
Temperature
Total dissolved
solids (TDS)
Benthic deposits
1
1
1
1
1
1


1


1
1

3
3
6
5
1
4
9
0
5

0
2
2
8
8
7
7
3
1
4
3
6

2
6
3
10
9
9
8
5
3
7
4
5

5
5
4
17
17
18
9
10
5
6
5
2

3
3
5
22
16
18
17
15
6
14
4
10

9
4
6
5
4
4
3
1
1
1
-
-

2
—
7
5
4
4
3
3
1
2
3
2

3
1
8 9
8
7
12
14
2
2
12
12
3

14
1
10
8
7
10
7
3
2
2
3
8

4
4
Total
96
85
98
83
53
25
57
44
41

52
36
                                  10

-------
       Another problem in monitoring and analysis involves the time
it takes to collect data.  In many cases, other tasks are dependent
on the availability of that data.  Moreover, there are only two sum-
mers in which to collect low flow data for 208; this means that scopes
of work must be prepared and contracts let very quickly.  Most agen-
cies will have only one summer to do sampling, as the low flow period
has passed for the first year of the planning period.  Laboratory over-
loads, and in some places their distance from sampling stations, are
also anticipated as problems in a monitoring program.  The two year
planning period therefore puts severe constraints on the development of
pollution control strategies where data is not available.

       In addition to a lack of stream monitoring data, there is also
a lack of point source discharge information.  Agencies have reported
that the data from the NPDES permits does not provide the type of in-
formation necessary for modeling purposes; others have said they had
difficulty getting the data that was available.  Some agencies had to
pay for the permit information while others were invited to search
state files to obtain it.  Industrial and domestic point source data
was occasionally nonexistent.  At the time of interviews, only 53% of
208 agencies interviewed had obtained list of point source discharges.
The Impact of 208 on 1983 Goals

       208 agencies were asked to indicate whether the 1983 goals
could be met as a result of implementing the plan.  The results are
presented in Table 7.

       61 of the agencies said part of their area could meet the goals;
24 said all  of their area; 12 said none of their area; 31  did not know;
5 said their whole area already met the goals.

       Reasons for not achieving the 1983 goal  are listed  in Table 8.
The most often cited reasons for not achieving  the T983 goals were: lack
of technology for nonpoint source control; lack of public  funds for
structures to control urban storm water, and irreversible  or slowly
reversible water quality problems.  Some agencies, in responding to the
question, said that "fishable and swimmable" had not been  sufficiently
defined.   Others felt that the delay in getting the 208 plan approved
would result in a delay in achieving the '83 goals.  Finally, a few
agencies  stated that the 1983 goals will be met, but that  the water
quality level would not be sustained due to increases in population and
the limits of present abatement technology.
                                  11

-------
                                          Table  7



                               ACHIEVEMENT OF THE  1983 GOALS





1 2 3
REGION
456789

10

Total
Will the 1983 goal be met everywhere or anywhere in the
planning area as a result of implementing the study?
Everywhere
Some places
Nowhere
Don't know
Already meets 1983 goals
No
TOTAL

REASONS
REASONS








Table 8
FOR NOT MEETING


3 - 1
4 10 3
6 -
8
4 1 -
_
17 11 , 12

THE GOALS

1 2 3
3 3 2 - 71
18 12 3 - 6 -
31- 2 -
57226-
______
3 -
26 25 8 5 21 1


REGION
456789
4
5
-
1
-
-
10



10
24
61
12
31
5
3
136



Total
Irreversible or slowly reversible water quality
problems
Lack of best available technology for
control
Lack of technology for nonpoint source
Lack of public funds for structures to
urban storm water

point source

control
control

8 -

3 1 2
622

9 1 1
5711-

28211
7 12 - 32

8 1C 2 4 2
4

1
6

3
26

21
40

40
Difficulty of the required analysis and probable
lack of confidence in results

Inability to show cost-effective control alternatives
4 - - 1
3 - 1
513-
5311-
3
3
17
17
*Total  is greater than 136 due to multiple responses.

-------
                          LAND USE ASPECTS


Findings

       The information gathered on land use revealed the following
issues:
            The EPA time limit for Interim Outputs places a severe
            burden on some agencies whose land use elements are
            less advanced and will require significant data collec-
            tion and updating.  Some agencies stated that not meet-
            ing the 9-month deadline would not necessarily hinder
            other 208 planning activities.
            Where available, most HUD 7Q.1 data was out-dated
            and incomplete, although there were some cases where
            it provided an adequate base for 208 planning.
            Agencies are often unable to identify, quantify and re-
            late nonpoint source pollution to land use and water
            quality.
Land Use Considerations in the 208 Planning Process

       Land Use Projections

       It was originally envisioned that most designated agencies would
be able to use HUD 701 or local data for their land use plans and pro-
jections.  Unfortunately, many areas have not found this feasible.   Even
where there was a great quantity of information, many 208's felt that
existing 701 data was less than complete and often outdated.  28 of the
responding agencies with existing land use plans available indicated
that existing 701 would require extensive development or updating for
their 208 project.  Therefore many agencies felt that they would have
to undertake additional land use tasks that were not originally en-
visioned under 208 planning.  While 93% of the 208 agencies have 701
planning ongoing in their respective areas, only 78% were actually doing
this planning themselves.  42 agencies plan to contract out either all
or part of their land use element.

       The need to do additional land use work should not be construed
as an insurmountable roadblock in the 208 planning process.  Many parent
agencies were already engaged in updating their land use plans or work-
ing in conjunction with their 208 divisions to revise the existing in-
formation.  The data developed through these efforts will help lighten
the burden on the 208 program.


                                 13

-------
        EPA - HUD Agreement

        The agreement between EPA and HUD, clarified in AM-9, has not
reached many 208 agencies.  Those agencies that were familiar with
AM-9 were rarely able to directly follow the specified funding pro-
cedure.  This is not to imply that there is a complete absence of
coordination.  In areas where a strong 701 program is under way,
an equitable division of costs is usually reached under locally de-
signed arrangements.  In a number of areas where 701 funds are dry-
ing up, 208 is assuming the major cost of land use elements.  In no
case was the work of one program being repeated in another.

        In short, the agreement has fostered locally tailored
coordination between the 701 and the 208 programs.  Although not
directly in line with the AM-9 Memo, this has been a step toward
elimination of duplication of Federal efforts in local  areas.  It
has additionally evolved a process of dividing costs, an important
aspect of improving coordination among Federal grants for local
jurisdictions.

       Budgets

       The following table depicts the percentage  of their  grant to be
spent on land use.   (See Table 9)

       44 of the agencies Interviewed plan  to spend  from 8-15% of
their total  budgets on collecting and analyzing  their land  use data.
19 will spend over 16% on land use, while 49  did not have their  land
use budgets developed yet.  Since there was  no standardized budget
guidance from EPA,  and subsequently no clear  definition  of  land  use for
all the agencies to follow, land use expenditures  were often hidden 1n
nonpolnt source analysis budgets.  In addition,  there was often  no
breakdown 1n the budgets between point and  nonpoint  sources of pollu-
tion, thus making it difficult to determine  the  total amount of  money
spent on land use.
       Interim Outputs

       87% of the agencies interviewed  Indicated that they would be
able to meet the nine-month Interim Output deadline.   29% have computer-
ized data banks that Include land use information,  while another 43%
have non-computerized land use data available 1n a  variety of forms.
The remainder feel  they will be able to gather the  Information required.
However, 13% Indicated they will  not be able to gather the needed Infor-
mation on time.  This problem was primarily attributed to a lack of land
use plans within their jurisdictions.

       By establishing time limits for  Interim Outputs, EPA has put
these agencies at an early disadvantage.   Those agencies that must de-
vote a large amount of time to the development of land use information

                                 14

-------
often have less time to devote to other key planning issues, such as
management and analysis, during the initial stages of the project.
                               Table 9

   PERCENT OF BUDGET ALLOCATED FOR THE LAND USE ELEMENT UNDER  208
                       NUMBER OF 208 AGENCIES
"/
lo
of grant
to be spent
on land use 1
0- 3%
4- 7%
8-10% '6
11-15% 7
16-20% 3
> 20% 1
No
Answer
REGION
2 3 a.
1
1 2 4
1 2 7
3
1 2
2

968
567
4 - 1
2 - 1
3 - 1
1 1 1
1
-1

14 7 -
8 9
-
3 -
2 -
6 -
3 -
5 -

2 1
10
2
3
2
1
-
-

2
Total
8
16
24
20
10
9

49
  Total
17   11    12   26   25
21
1    10   136
                                 15

-------
Nonpoint Source Pollution and Land Use
      Nonpoint source pollution is a major reason for areawlde waste
treatment management planning.  However, many agencies expressed con-
cern over their present inability to identify and quantify nonpoint
source pollution and their subsequent difficulty in relating land use
to nonpoint sources and water quality.
      The following table indicates nonpoint source pollution prob-
lems in 208 areas.
                             Table 10
                  SUBSTANTIAL NONPOINT SOURCES

    Nonpoint Source                      Mentions by 208 Agencies
    Agriculture                                     76
    Benthic  (sludge)                                45
    Combined Sewer Overflow                         59
    Construction                                    74
    Feedlots                                        40
    Mining                                          38
    Silviculture                                    26
    Septic Fields                                   74
    Urban Storm Water                               79
    Other                                           16
      One means of determining nonpoint source pollution is the develop-
ment of conversion factors that would relate land use to water quality.
While few agencies have actually undertaken this endeavor, almost half
the agencies interviewed said they will develop these figures at the ap-
propriate time.  Although not asked in the interview, five agencies indi-
cated they plan to use published conversion factors and would like some
guidance from EPA concerning this matter.
                                 16

-------
                 MANAGBefT/ir^STITUTIONAL ASPECTS
Findings
      Management is the structure and process by which a 208 plan
will be implemented.  It is a system of actions and institutional
arrangements necessary to achieve and maintain water quality goals.
The major findings related to the management and implementation of
208 plans are as follows:
           The majority of 208 agencies do not feel they have
           the in-house capability to deal with the management/
           institutional issues and are contracting for this
           work.  Fully a third of the agencies have yet to de-
           cide whether they or consultants will  complete this
           element of the plan.  This may be a problem in view
           of the time it takes to let out contracts and the
           importance of considering management from the outset
           of 208 planning.
           There is a strong commitment on the part of the
           designated agencies to develop and implement a man-
           agement system, but considerable uncertainty at this
           point in the process, as to what that system will
           look like, how it will be created and what powers  it
           will exercise.
           Local 208 personnel are uneasy and uncertain about
           EPA's enforcement powers; if the Agency is consider-
           ing real sanctions, it should make them known.
           A single planning agency and several management
           agencies is the institutional arrangement for 208
           management foreseen by most of the interviewed agen-
           cies.  There will be very few "super agencies."
           Most 208's will opt for modifications of existing
           arrangements.  Rather than major institutional
           changes, the general insistence on "local autonomy"
           will be a serious constraint on management alterna-
           tives.
           The concept of a lead management agency and the
           relationship of the planning agency to the manage-
           ment agency are not understood.
                                17

-------
Designated Agencies Capabilities in Management Planning

      There are few generalizations that can be made about the exist-
ing institutional  arrangements in 208 designated areas.  One charac-
teristic shared by most 208 areas was municipal waste management by
two or more local  agencies.  This kind of fragmented approach to
treating waste is  the reason for 208's areawide approach, and 69% of
the agencies interviewed said it was a factor in their designation.

      More than half the agencies responding said the protection or
preservation of high quality waters was made difficult by a complex
Institutional setting.  208's mission is to create order from chaos
through one integrated waste management system, (though that may be
composed of several different management agencies and many plants).

      Table 11 describes who will be undertaking the management work
element in each of the agencies interviewed.
                             Table 11

         WHO WILL DO THE LEGAL/MANAGEMENT/INSTITUTIONAL
                  WORK ELEMENT OF THE 208 PLAN?
                               REGION

Consultant
In-house
No answer
Total
1
6
2
9
17
2
6
5
-
11
3
7
2
3
12
4
18
4
4
?6
5
0
4
21
?5
6
6
-
2
8
7
3
-
2
5
8
15
-
6
21
9 10
1 9
-
1
1 10
Total
71
17
48
136
       The majority of 208 planning agencies did not feel they had the
 in-house capability to deal with the management/institutional issues
 alone.  Only 17 are doing it all in-house; many more will share this
 responsibility with consultants,  71 are contracting for at least a
 part of this planning and analysis.  48 agencies have yet to decide
 whether they or consultants will do the work.  This is a potential
 problem area considering the time it takes to let out contracts and
 the importance of considering management from the outset of 208 plan-
 ning.  When asked when they planned to undertake the analysis of man-
 agement alternatives, agencies responded with the range of day-one to
 as late as the 18th month in the planning process.  Table 12 presents
 the results.
                                  18

-------
                             Table 12

        WHEN WILL MANAGEMENT ALTERNATIVES ANALYSIS BEGIN?


                                REGION

0 - 1 month
2 - 6
7-12
13-18
19-24
Don't know
No answer
Total
1234
6 - 2
10 2 - 5
7
3
_
6
1 9 12 3
17 11 12 26
5
6
6
6
1
-
6
-
25
6
1
5
1
-
-
1
-
8
789
3 1
1 8 -
1 3 -
2 -
_
2 -
33-
5 21 1
lo
4
2
4
-
-
-
-
10
Total
23
39
22
6
-
15
31
136
      The notion of a statewide model for a management system has been
considered in several states.  Most of the 208 agencies in Texas will
let a joint request-for-proposals for their management/institutional
planning.  In Maine, the designated agencies have agreed to jointly
finance either one consultant or one selected agency which will  re-
search some of the common management institutional questions facing all
of them.
Major Issues
      Commitment

      There 1s clearly a strong commitment on the part of the designa-
ted agencies to develop a management plan that will be both effective
and capable of implementation, though that commitment is hard to quan-
tify.  The most obvious evidence of such a commitment is that 12% of
their grants is the average amount agencies will spend on their legal/
management/ institutional work elements.  15 of the agencies have, or
will soon have., lawyers on their staffs to deal with implementation
issues and any other legal problems; 46 will have public administra-
tion or management specialists.
                                19

-------
      One particular situation should be-carefully watched.   One of
the earliest funded 208 agencies does not Intend to tell  Us  consti-
tuent jurisdictions what is the best Institutional arrangement for
208 implementation.  This agency sees its role as going no further
than the presentation to Its local  governments of alternative manage-
ment systems - the decision as to which alternative to implement
being left to the locals.  This will be a problem 1f locals do not
feel compelled to choose an alternative, and the management system
becomes shelved with other planning programs.  This situation should
be carefully watched to insure that Implementation is an integral
aspect of the plan.

      Regarding those agencies that are_ commi tted to selecting one
management arrangement, it is not clear to them how to achieve a
system that is both effective and can be implemented.  Certainly,
some compromises will have to be made by all agencies to ensure local,
state and federal approval.


      Agencies' Knowledge/Understanding of Management/Institutional
      Aspects

      Most agencies are aware of the particular emphasis of 208 on
management and implementation.  They know that only the most  appro-
priate and innovative management systems will be effective and that
EPA will not accept the designation of a management agency if it does
not have the authority to carry out the plan.

      208 personnel are confused, however, about EPA's enforcement
powers.  For example, it is unclear whether permits or construction
grants will be denied in order to encourage completion or approval
of a plan.  Many agencies voiced the fear that EPA was a "paper
tiger"; if the Agency is considering real  sanctions, it should make
them known.  This would spur 208 agencies  to make the kind of commit-
ment to management and Implementation that will  be necessary  to develop
a worthwhile system.

      Although aware of the need for an areawide management system that
will "meet the requirements of the  Act", the agencies are unsure what
that system will look like, how it  will be created and what powers it
will exercise.  For example, 89% of the agencies Interviewed  said they
would find management/legal/lnstltutional  seminars useful. Their com-
ments in response to this question  demonstrate a great desire for
state-specific guidance as to legislation  needed and how to go about
getting it; and for innovative institutional and financial arrangements.
22% of the agencies could not make  an educated guess as to who the
management agency would be and as mentioned above, several agencies said
it was not their responsibility to  select  a management agency.  About
one-third of the responding agencies were  not familiar with the required
authority of a management system set forth in Section 208(c), and many react
with Incredulity to the suggestion  that their management agency be able
to do such things as Incur indebtedness and refuse wastes from publics
not complying with the plan, both of which are required by Section 208(c)(2)


                                 20

-------
       Optional Management Systems
                    *
       Section 208 allows states and localities great flexibility in
 designing areawide waste management systems, and EPA encourages 208
 agencies to find the best institutional arrangement to deal with its
 own water quality and financial needs.  Possible 208 management sys-
 tems can be placed in 3 categories: single agency for both planning
 and management; single planning agency and a single management agency;
 and single planning agency and plural management agencies.

         "In some situations, when a single governmental jurisdiction
already  exists and encompasses the entire 208 area, it may be assigned
both the planning and management responsibilities."1  Of the 136 agencies
interviewed, however, less than 20 have any management capability at all,
i.e., are something other than COG's with virtually no implementation
authority.  Furthermore, most of these agencies only have limited
implementation capability, and could not serve as the sole management
agency.  Only  3 of the agencies interviewed thought that they would
be  the 208 management agency.

      Another option is to designate one management agency, separate
from the planning agency.  This arrangement will  not appear very often,
judging  by the'present thinking of the designated planning agencies.
Only 11  of those interviewed expected there to be a single management
agency.

      The third option, single planning agency and plural  management
agencies, was definitely preferred by designated planning agencies.
"This option would allow those management agencies already providing
waste treatment service to continue doing so with a minimum effect
upon their internal administration."!  Coordination between planning
and management will suffer in this type of arrangement, but individual
local governments will "retain their own waste treatment agencies and
other authority,"1 a consideration uppermost in the minds of those
agencies searching for a plan that will win local approval.  68 agen-
cies, or just over half of those interviewed, felt there would be
several management agencies in their areas.  There was an even split
among the 68 agencies between those expecting there to be several
management agencies with a high degree of  regional authority and
those expecting several management agencies with much local autonomy.
8 other  interviewees volunteered that management would be solely by
local governments.  There are only 19 agencies that predicted the
creation of a new agency to manage and implement 208.  32 would not
make a prediction as to the structure of their management system.
1
 Draft Guidelines,  May,1974.
                                 21

-------
      In discussing expected management organizations with 208 person-
nel , it became clear that most had done little thinking about the sub-
ject.  Those that had seriously considered it were rather confused
about the relationship of the planning agency to the management agency.
Almost all of them expected to do the ongoing 208 planning themselves,
but were not clear on just what that would entail and how it would
relate to the implementation or management of the program.

      An equally confusing concept is that of a lead management agency.
EPA's Draft Guidelines state that "whatever approach is taken, the
essential consideration is that coordinative authority capable of
facilitating the resolution of conflicts and implementation of the plan
be a central component of the management system."  This has done little
to clarify the situation 1n the minds of 208 project directors.  They
don't know whether they must have a lead agency or what authority the
lead agency should have.

      Compounding the difficulty in selecting a management agency are
the political situations 1n which 208 planning proceeds and which it
cannot Ignore.  More than a third of the agencies experienced delays
1n obtaining resolutions of intent from local governments and 22
said there was public disinterest or hostility toward 208 planning.
55 agencies expect local review and approval  to be a problem.

      Whatever management systems are chosen  will  undoubtedly leave a
great deal of management authority 1n the  hands of local  governments.
Most responses to questions about 208 implementation centered on the
fear    local jurisdiction of losing autonomy and control.   Many inter-
viewees spoke of the "ramifications" of management.   One  agency took 9
months convincing its local  jurisdictions  to  participate  in  208 because
of their fears regarding the prospective management  structure.
      Methods of Organization

      If a plan does nothing  to change  existing Institutional  arrange-
ments and leaves the bulk of  authority  with  local  governments  it will
be considerably simpler and easier to  Implement.   Even  where local
ordinances or contracts are the only  legal arrangements to be  made,

plans to obtain them.   Many of the agencies  responding  said that a
contract would have to be negotiated  between the designated management
agency and local governments  or that  some  kind  of  joint establishment
between the management agency and  the  local  governments would  be likely.
Most interviewees believed that new state  enabling legislation or
changes in State law would be required.
                                 22

-------
      Required Authority and Regulatory Controls

      Section 208(c) (2) states that an areawlde management system
must be able to:

      t    design, construct and operate waste treatment works

      •    accept and utilize grants

      t    raise revenues and assess waste treatment charges

      •    Incur Indebtedness

      t    require participating communities to pay proportionate
           share of treatment costs

      t    refuse wastes from publics not complying with the plan

      t    accept industrial wastes and set pretreatment standards


      Many 208 agencies are not yet aware of the Act's requirement
of these powers.  They are not thinking of one management system
that will have all these capabilities.  This may be attributed to the
early stage of the program in most areas.

      When asked what regulatory controls would be used, many agen-
cies were unable to answer, again because they had not begun to con-
sider the subject.  The most oft-cited method was metering of waste-
water flow, then building and housing codes and subdivision regula-
tions, discharge permits, zoning, planned unit developments, and
finally differential tax assessments.  Discharge permits will be more
heavily relied upon than this rank-order shows, since most agencies
will be relying on the state and Federal governments to administer
the permit program.

        The responses to the potential regulatory methods naturally
vary considerably from state to state.  In a few areas, the notion of
land use control is feared by the locals, and 208 agencies are strug-
gling with ways to get around local practices and beliefs.  There is
a rule for the states to play in this area, where legislation could
mandate a change in local unwillingness to accept any form of land
use controls.
                                 23

-------
                        PUBLIC PARTICIPATION


 Findings
 ono    Jt thls tjme,  1t 1s too early to judge the effectiveness  of
 208  public participation efforts.   Most agencies are  in  the  early
 stages of their projects and only  a few have begun  any significant
 public participation work.

       The profile study did, however,  reveal  a  number of patterns
 and  issues which appear to  be developing across the country:


       •    The majority of  agencies are designing public
            participation programs  in compliance with EPA
            minimum guidelines (40  CFR  105).'


       •    Agencies  generally recognize the  importance of
            securing  public  approval  of 208 if the plans
            are to be accepted and  implemented.


       •    208 agencies  expect to  experience various forms
            of opposition from citizen  groups and individuals.
           208 agencies' public participation expenditures
           are generally used to develop a one-way flow of
           information to the public.  This is a necessary
           first step, but mechanisms for feedback are
           essential.  Plan acceptance will be jeopardized
           if the general public is only included in 208
           planning through committees; furthermore, an
           excellent opportunity to involve the public in
           pollution control will be lost.
Who is the Public?

      "Publics" potentially affected by the 208 program can be broken
into three levels to facilitate differentiating among the various
groups that are part of the planning process.
1
 Public Participation in Water Pollution Control
                                 25

-------
           Level  I  1s composed of governmental agencies linked
           to environmental  management, and private businesses
           which  depend directly on the use of environmental
           resources.
           Level  II Includes special  Interest groups and organ-
           Nation? concerned about environmental management.


           Level  III 1s the general public whose attention 1s
           unlikely to be focused on  environmental  planning
           unless a crisis has alerted them to their dependence
           on sound environmental  policies.
A Shift in Approach

      Most 208 agencies recognized the need to include the public
throughout plan development.   Past experience with other water
quality programs has convinced them that waiting to "sell" the
public a completed plan usually fails.  This was particularly true
with regard to state 303(e)  plans  where the public felt left out
of the planning process.   In  fact, many agencies said it was neces-
sary to disassociate themselves from 303(e) plans because of the
hostilities created during  that process.
Experience with Public Participation  Programs

      Table 13 indicates  the  experience  of the 208 agencies with
public participation  programs.
                             Table  13

           EXPERIENCE  IN  PUBLIC  PARTICIPATION  PROGRAMS

 Experience
  in Public   	           REGION
Participation

    Yes

    No


    Total       17   11   12   26   25    8    5   21     1    10     136
1
17
-
2
9
2
3
12
-
4
24
2
5
23
2
6
7
1
7 8 9
5 13 1
8 -
10
10
-
Total
121
15
                               26

-------
       121 agencies had previous experience with public participation
programs.  Some of these agencies had developed environmentally con-
cerned constituencies, which would be rallied again for the 208 pro-
gram.

       15 agencies had no previous experience with public involvement.
Over half of these are located in the more remote areas of the West
where planning itself is a relatively new activity.  A number of inex-
perienced agencies voiced some concern over their ability to get an
effective program working early enough in the planning process.


Budget and Staff

       The following table depicts regional allocation for public
participation programs.
                              Table 14

     RANGE OF THE % OF BUDGET ALLOCATED  FOR  PUBLIC  PARTICIPATION


                                  REGION
Allocation
Low (%)
High (%)
Average(%)
1
5
20
9.4
2
3.5
10
7.5
3
3
20
9
4
2
14
6.8
5
2
20
10
6
3
10
5.3
7

17
9

2
.3
.1
8
1.5
9
4
9
10
10
10
10
1
13
4.1
        Budget allocations  for  public  participation  ranged from  1%  to
 20%  of total  grant awards  with an  average  allotment of 8%.  This wide
 range  was  experienced  because  some regions advised  their 208 agencies
 to allocate  a uniform  dollar amount for  public  participation rather
 than a percentage  of their budget.  This statistic  also does not reveal
 all  monies that will be  spent  on public  participation.  For example,
 funds  to be  spent  on committees, plan approval,  and other coordination
 activities are often included  in other budget categories.

        Table 15 indicates  how  the  agency will delegate responsibility
 for  the public participation programs.
                                27

-------
                              Table 15

              RESPONSIBILITY FOR PUBLIC PARTICIPATION
                              PROGRAMS*
   Public       ___	REGION	
Participation    123456789   TD~  Total

   Public
Participation
Coordinator
Other
Consul
* Does
Staff
tant
not equal
8
13
3
136,
1
7
1
as
5
5
2
some
12 19
11 3
2 -
agencies
52713
1 3
2 -
Indicated
13 - 8
7 -
joint work
63
64
17
144
       Part of the public participation money will be used directly to
hire In-house staff and consultants.  63 agencies Indicated they would
hire a staff member specifically for the purpose of coordinating the
public participation program.  17 agencies Intended to hire a public
participation consultant to help design and implement a public involve-
ment strategy.  In 64 agencies, various staff members will conduct the
public participation activities.  In a few cases, project directors
will be directly in charge.

       The majority of agencies had not yet formalized an internal
communications system to insure proper transmission of input gathered
through the public participation.
Committees

       All of the 208 agencies have or will  be setting up committees
with representatives from all  levels of the  public to assist with the
development of the 208 plan.   Some of the more established 208 agencies
have extensive networks of committees in operation, while many new or
single purpose agencies only  have an agency  governing board at the
present time.

       For the purposes of 208 planning and  implementation there seems
to be three basic types of committees which  will  be in operation in most
208 areas.  These are the general planning advisory committees, techni-
cal committees and sub-committees, and citizen advisory committees.  The
planning advisory committees  (also called policy advisory committees,
water quality task forces) are quite consistent across the nation.  They
usually constitute the formal  link between the program and the parent
organization, reporting to the parent organization's governing body on
the progress of the program.   These committees will revise the work plans
and review results of data collection, and management analysis.

                                 28

-------
       Membership on these committees primarily includes government
and business representatives (Level I) with additional representation
of interest groups (Level II) and private individuals (Level III).

       At the time of the interviews there were 65 planning advisory
committees in operation, with the balance yet to be established.
Eight of these committees are joint task forces composed of repre-
sentatives from two agencies in dually designated 208 areas.  The
average size of these committees is about 25, although there was a
range of 3 to 90 members.

       The technical  advisory committees (1n some cases, sub-committees
to the areawide 208 planning committees) assist in the development and
review of technical elements in the program.  Although representatives
from all levels of the public exist, government staffs and business
representatives predominate.  Most members are sewer district managers,
city managers, and representatives from various water and sewer authori-
ties, as well as State and Federal agencies.  There are currently 59
technical committees in operation throughout the country.  Most have a
membership of approximately 20, although the numbers range from,7 to 64.

       The citizen advisory committees are the principal avenues for the
Level II and III publics' input into the planning and decision making
process.  45 of these committees were already formed at the time of
interviews.  Their average membership 1s 35 with a range of 5 to 250
members.

       The majority of the 208 areas have opened committee membership
to any Interested individuals.   Some agencies qualified this condition,
however, by specifying that only approved members could vote.  In one
state, for example, the Governor issued an executive order specifying
that he would have final approval over the planning advisory committee
membership.  This situation has restricted public accessibility to the
program, and has delayed some 208 program start-ups.
Public Education

       Table 16 indicates whether 208 agencies have received requests
for briefing on the 208 program.
                              Table 16

              PUBLIC REQUESTS  FOR BRIEFING ON  208 PROGRAM
 Total
                                REGION
Requests
Yes
No
1

1



0
7
2

5
6
3

4
8
4

12
14
5

17
8
6

5
3
7

4
1
8 9

7 1
14
10

7
3
Total

72
64
                17    11    12   26
21
1   10
                                  29
135

-------
       At the time of the Interviews, 72 agencies had already received
requests from various groups for briefings about the program.   Among
the aspects agencies Indicated the public would find difficult to grasp
were:


       0    the nature of the 208 program Itself;

       •    the concept of nonpolnt sources of pollution;

       •    the relationship between land use and water quality;

       •    technical terminology;

       •    the management aspects of the program;

       •    coordination with other water programs such as Sections
            106, 201, 208, 209,  303, and 402;

       •    the need for another planning program.


       In response to this need, agencies were generally setting up
public Information programs similar to the one that appears 1n the
Interim Output Handbook.  At the time of the  Interviews 1t was Impossi-
ble to obtain any meaningful  data on how these techniques would be
received by the public.


       t    Mailing Lists - Of the agencies  Interviewed, 121  have
            already begun to establish mailing lists of interested
            Individuals  and groups 1n their  regions.  In some
            cases, these lists are nothing more than the parent
            agencies normal  mailing lists with a few additions.
            In other areas separate mailing  lists for those people,
            groups, and  agencies concerned with the 208 program are
            being established.  The remaining agencies will  be com-
            piling mailing lists as soon as  they get underway.
              Newsletters - 60 agencies at the present time have
              newsletters which are carrying articles about the
              208 program.  Several of these newsletters will  be
              solely for 208, while the majority of the 208 agen-
              cies will  utilize the parent agency's newsletter.
              The agencies that have not already prepared articles
              for newsletters intend to do so.
              Planning Brochures - 25 agencies currently have a
              planning brochure describing the 208 program, and
              another 77 agencies intend to publish one at a
              future date.
                                  30

-------
       •    Briefings for the Public - Public meetings and hearings
            will be used extensively throughout the 2-year process.
            Each agency was required to hold a public hearing on the
            designation of the area, and since that time, 70 agen-
            cies have already held public meetings to discuss other
            aspects of the program.  53 project directors or other
            senior staff members have already given speeches before
            a wide variety of public and private organizations.  To
            assist at these briefings, 19 agencies have developed
            slide-show, movies, and multi-media presentations, and
            an additional 92 agencies have indicated that they in-
            tend to utilize some form of audio-visual aids in making
            presentations about 208.  15 exhibits have been devel-
            oped thus far, while an additional 61 agencies said that
            they would be developing them in the future.  A few agen-
            cies have also recognized the advantage of having contact
            with citizens in an informal atmosphere as well.  For
            example, one agency currently has brown bag lunches week-
            ly to which any interested person is invited to come and
            have lunch with the 208 staff.
       •    Media^Relations - Certainly one of the primary mechanisms
            by which the Level III public and others will be kept
            abreast of the development of the 208 program will  be
            through the mass media (newspapers, radio and television).
            87 of the agencies have already received some newspaper
            coverage, 51 agencies have been covered on the radio, and
            35 agencies have had exposure on television.  One COG uses
            its own weekly radio show;  several television stations
            have expressed interest in preparing documentaries on
            local 208 programs.


       t    Documentation and Depositories - Presently, 18 agencies
            have established 208 depositories for public use.  61
            additional agencies said that they intended to establish
            such a system in their areas.


       •    Miscellaneous - Several areas are currently offering tours
            of their regions for the public, while others have formed
            speaker bureaus.


Public Input and Feedback

       Some agencies indicated their intentions to create public input
and feedback systems.  However, only a limited number of them were
underway at the time of the interviews.  This can be understood in light
of program start-up delays being encountered across the country.  De-
spite this fact, however, there was a noticeable lack of commitment


                                  31

-------
directed toward planning and decision-making feedback when compared
with the information dissemination systems.  Without including
effective mechanisms for obtaining feedback, some public participa-
tion efforts will be noticeably weak.  This would result in diffi-
culties with plan implementation, as well as the loss of an oppor-
tunity to increase public awareness of water quality problems.

       The techniques most often cited for obtaining public input
and feedback are:
       •    committees

       •    liaison with citizen groups

       •    public meetings and hearings

       •    surveys

       •    seminars

       t    workshops
       Initial feedback from the public has uncovered several issues
which will have to be dealt with by the 208 agencies.  These are:
       t    the role of the citizen in decision-making process

       t    the extent to which economic interests will  be considered
            (I.e.  agricultural  interests, logging, etc.)

       t    the potential loss  of local autonomy by local  governments

       •    the nature and extent of land use controls (i.e.
            regulation v. private property rights)

       •    the relationship between 208 and 201

       •    who is going to pay  for cleaning up existing  nonpoint
            sources

       •    what is public acceptance of the plan


Problem Areas

       A program of the nature  and extent of 208 will  not  go unattacked
by all  elements of society.   208 programs will  be opposed  in a number


                                  32

-------
of areas* by ultra-conservative groups, home-rule advocates and
economic interests that feel threatened by the implications of the
program.

       A large portion of the initial opposition can probably be
attributed to a lack of understanding about the program.  This was
true in the case of several states who initially opposed the program.
Hopefully, many of the groups that are now in opposition to the pro-
gram will become aware that they can have a role in the process and
input into the final plan system.  Other groups will undoubtedly
remain in opposition to the program, throwing up obstacles before
the 208 agency at every available opportunity.

       In addition to vocal opposition to the 208 program, there are
a few major problems which will have to be dealt with.  First, public
participation will be a very time-consuming activity.  Second, travel-
ling distance will be a problem in some areas.  In a few remote 208
areas, committee members might have to miss two working days in order
to attend a routine advisory committee meeting.

       Finally, devising effective techniques for combatting public
apathy is sure to present problems for many of the 208 agencies.
This chapter has described many public participation techniques, but
their mere use does not insure effective public participation.
*The question of the role of environmental groups in 208 clanning was
 not addressed, and did not arise in the discussion of potential opposi-
 tion to 208 planning.  Whether this is because there is not opposition
 at this time by environmental groups or that it was not considered in
 the context of the "opposition" question is not clear.


                                  33

-------
                              BUDGET
Findings
      Information on 208 agency budgets was difficult to obtain at
the time of interviews because most projects were in early stages
of planning at that time and because EPA had not stipulated or dis-
seminated guidance for standardized budget preparation.  However,
several important issues did emerge during the course of the study:


      •    EPA Regional guidance on funding adjustments resulted
           1n indiscriminate cutbacks across agency budgets in
           some areas.  Such action was a source of conflict be-
           tween several 208 agencies and their respective EPA
           Regional offices.
           Misinterpretation of EPA Headquarters directives on
           funding eligibility sometimes resulted in bans on
           particular work tasks, particularly modeling and moni-
           toring.
           On a national average, 208 agencies Intend to contract
           out below the 75% ceiling suggested by EPA.
           Should EPA need to perform a nationwide study of 208
           budgets, it will have difficulty in doing so due to the
           Inconsistent format of individual agency budgets.
Grant Awards

      EPA was authorized by Congress to obligate a total of $250
million for 208 planning in FY 1974 and FY 1975.  Headquarters
succeeded in committing$163 million within the given deadline, but
not always according to 208 agency requests.  Table 17  indicates
the number of agencies with discrepancies between grant amount re-
quested and awarded.
                                 35

-------
                             Table 1 7

    DISCREPANCIES.BETWEEN REQUESTED AND AWARDED GRANT AMOUNTS


                         Number of Agencies Registering Discrepancies
                             IncreasesDecreases
Amount Over Request rrom Kequesi
$ 0- 1,999
2- 9,999
10- 49,999
50- 99,999
100-999,999
> 1 million
1
6
5
1
5
-
1
7
15
9
35
7
    Total                        18                         74
      Over 60% of funded agencies  received less than their original
grant requests while 15% were awarded sums in excess of their requests.
Increases were generally small,  clustering within a median range of
$10,000 to $50,000.   Decreases were generally far more substantial,
with 35 agencies registering cutbacks of $100,000 to $900,000 and 7
agencies with reductions in excess of $1  million.  57 agencies received
the amount of grant  requested.

      Reasons for discrepancies  between requested and awarded grants
seem to follow two general  patterns.   The first reflects a Regional
policy decision to fund a number of smaller planning efforts rather
than concentrate money in a few  major programs.  This can be seen as
an attempt on the part of the Regional  office to achieve an equitable
distribution of funds.  The second is that Regional staffs made adjust-
ments to original grant estimates  after reviewing work plans and
budgets.

      Three out of the ten  Regions tended to resolve funding Issues
through general cutbacks across  the board.  In the majority of cases,
however, line items  were either  reduced or eliminated to comply with
regional policy stands.  Among those line items most frequently af-
fected were water quality and land use data collection and municipal
facilities related work.  Resolution of discrepancies reflect regional
office interpretations of EPA Headquarters directives.
                                 36

-------
      Most local agencies were able to adjust to funding changes
without difficulty.  In a few isolated cases, however, reductions
generated feelings of animosity toward Regional EPA offices.  This
occurred when local agencies felt EPA misled them to believe that
their original grant request would be forthcoming, only to find
that line items or grants were later cut back to a point where the
208 agencies felt they could no longer undertake an effective plan-
ning program.

      More EPA sensitivity to local problems and/or a better expla-
nation of federal policy are needed to alleviate misunderstandings
in the future.
Work Plan Budget

      Of the 136 agencies interviewed, 121 agencies had budgets
available for review and discussion.  They were generally prepared
by 208 staff with EPA and/or state guidance.  The 15 remaining
agencies did not have budgets available at the time of the profile
study; some were revising due to budget cuts.  Half of these 15
were clustered in one region with the remainder spread out among
three other regions.

      The available budget information was nationally inconsistent
in format due to the absence of standardized budgetary guidance
from EPA.  In a few areas where states took it upon themselves to
circulate model budgets, there was a noticeable increase in budget
format consistency.  Uniform budget format would make comparisons
among agencies and across regional lines much more feasible with-
out restricting the 208 agencies' choice of goals, etc.  This may
be a valuable asset to EPA for overall program evaluation, both at
the beginning and end of 208 and similar planning programs in the
future.

      A much more serious problem that arose in 208 budgets can be
traced back to the procedure by which a number of designated agen-
cies determined their grant requests.

      In order to promote equitable national distribution of auth-
orized funds, EPA Headquarters established a grant guidance formula
based on the applicant agency's area population.  This system was
intended to be used as an estimate of total national funding - not
as a formula for individual agency budgets.  Some agencies, however,
misunderstood EPA program guidance and relied on the population
formula to determine their grant request, rather than making a con-
certed effort to identify program goals by task and dollar amounts.
This situation suggests that some agencies did not have a clear
                                 37

-------
understanding of their local water quality goals at the' time of grant
award - a condition which has contributed to delays 1n program start-
ups and could possibly jeopardize chances of reaching highest program
goals.

      Having recognized these possible trouble spots, EPA has Issued
a request for project control plans (PCP's) which will tie Itemized
workplans to specific tasks by dollar amounts.  Regional offices
generally expressed the hope that PCP's will check most potential
problem situations before they get out of hand.

      More detailed guidance from EPA Headquarters, stricter policy
enforcement by EPA Regional offices and an advance on grant awards
or a retroactive allotment of funds for budget preparation during
the grant application period would help eliminate these budgetary
problems in future EPA programs.

      Almost all local agencies indicated that their budgets were
either scheduled for 1ntra-agency revision and/or possible modifica-
tion through PCP's.  Among the reasons cited for the tentative or
incomplete status of budgets was  first, insufficient time between
designation and grant award 1n which the 208 agencies were to prepare
detailed work plans itemized by tasks  and cost.  Another reason was
the uncertainty of designation approval which caused some agencies to
delay budget preparation until such time when they could be assured
of funding and a return on their  investment of  staff time and agency
funds.  Funding the preparation of the budget was also a problem for
many 208's since this expense had to be covered with general  agency
funds.  Many agencies suffered from lack of available staff and the
absence of agency expertise in cost and price analysis.   Finally, con-
fusion on funding eligibility of  such  line Hems as infiltration/
inflow analysis and water supply  studies, delayed budget decisions
1n some agencies.

      In an attempt to compare budgetary allotments across the nation
where standard budgetary categories do not exist, the study group
delineated eight broad categories into which agencies were asked to
translate their budgets.   The categories were as follows:


           Program management

           Point and nonpolnt source monitoring and sampling

           Waste load allocations modeling

           Technical  sub-plan formulation and review

           Municipal  facilities related functions

           Analysis of alternative management systems

           Land  use

           Public participation
                                38

-------
Interpretation of the categories listed was left to the discretion of
the interviewee.  Results, therefore, are not consistent.

      Only 46 of the 121 agencies with available budgets were able to
translate those budgets into the categories presented in the inter-
view schedule.  Seven agencies were able to make a partial transition
by combining point and nonpoint source monitoring, modeling and tech-
nical sub-plan formulation and review into one aggregated item which
they termed "water quality analysis and review."

      Regional and weighted national averages for the available data
are presented in Table Is.

      Program management, monitoring, municipal facilities planning
and land use seemed to receive equal weight in our partial survey,
each averaging between 11 and 14% of total agency budgets.

      Elsewhere in the interview schedule, agencies were asked for
budget information OP individual line items.  These questions met
with a higher response rate.  Results showed an average of 12% of
total budgets would be spent on management/institutional studies, 14%
on land use and 8% on public participation.

      Once again, the reader must be warned that the agencies inter-
preted the budget categories for themselves.  The information gathered,
therefore, may be inconsistent, with some extraneous expenditures hid-
den within major budget categories listed in the interview schedule.
With these caveats in mind, the discrepancies between these figures and
the standardized category tally can be explained by the broader sample
represented in the itemized tallies.  A number of agencies who were
unable to use the standardized categories were able to quote figures on
these particular budget items.  The range of variation between the two
sets of figures is minor, however, this suggests that either set dives
a reasonable estimate of average budget allocations.

      A few regional and/or state policies are revealed through patterns
of budget allocations.  The strongest patterns emerge in regards to
monitoring and modeling, where it appears that a number of regions took
Headquarter funding guidance too literally.  Rather than temper efforts
in these areas, some  regional EPA offices tended to disallow them al-
together.

      In one area where Regional or state guidance was given on "reason-
able" budget allocations by item, a consistent dollar amount was set
aside for public participation programs.  This later situation suggests
that 208 agencies were willing if not eager to follow reasonable,
locally sensitive guidance, particularly in non-controversial areas.
The same sentiment was expressed with regard to items requiring famil-
iarity with cost and price analysis.
                                39

-------
                                                      Table 18

                                      SUMMARY TABLE:  SAMPLE BUDGET ALLOCATIONS
                                                 (Regional Averages)
o


Number of agencies with
budget
Program management
Monitoring
Modeling
Sub-plan formulation/review
[Water Quality]
Management analysis/
selection
Municipal facilities
Land use
Public participation

1

15
13
-
15
-
37

11
15
13
11

2

1
10
8
24
15
47

18
-
3
2

3

1
5
10
15
17
42

19
10
19
5

4

8
13
14
17
15
46

17
11
10
6
R E
5

6
13
15
7
24
46

11
12
6
9
G I 0
6

1
9
9
5
37
51

20
2
11
7
N
7

5
16
-
6
-
41

13
10
10
9

8

8
17
-
5
-
38

12
9
19
5

9

1
20
8
-
23
31

29
-
7
7

"TO

9
11
8
3
34
45

15
9
7
7
Weighted
National
Average


13
12.5
8
22.5
[42]

14
11
11
8
      Regional and National Averages are average percentages of individual agency budgets.
      Water Quality is an aggregated category.

-------
       The study team's general impression on budgets was that products
would have been much more satisfactory, in terms of status and content,
if better guidance and more funds had been available to the 208 agencies
early in the grant application period.  Well-formulated budgets at the
time of grant award would have eliminated start-up delays and perhaps
contributed to a better understanding of goals and scope of work at the
project's initial stages.


Contracts

       A 1975 Headquarters directive suggested a 75% total budget ceil-
ing on contract work to be carried on outside the 208 agencies.  This
celling excludes services contracted between or among 208 agencies.  At
the time of interviews, an intended national contract average of 58%
was identified by 208 agencies - a figure well within the suggested
limit set by EPA.  There were, however, a significant number of agen-
cies with contracts in excess of this mark.

       Only 1/3 of the 136 agencies interviewed had detailed contract
lists.  Most of these were still subject to change contingent upon
possible workplan revisions.  10% of the 136 agencies had not begun out-
lining a contract list.  Reasons given for the preliminary status of
contract lists include the status of  workplans, and difficulty in cost/
price analysis.  In at least one case, there was a sensitive political
situation wherein member jurisdictions perceived a threat to their self-
determination in the face of a strengthened regional planning agency.

       Only 2% of intended contracts had been let at the time of inter-
views.  These contracts generally involved minor program tasks with a
scattering of contracts for workplan revisions.  Regional EPA offices
were generally delaying finalization of contract agreements until PCP's
were completed; agencies were clear on their goals and the scope of
work before they begin spending their money.

       In most instances, decisions on whether to do work in-house or
by contracts were made by the 208 agencies themselves.  Outcomes gener-
ally reflect technical expertise within the agency itself.  Some guid-
ance on contracting was usually provided by EPA or the state, especially
in the case of new or small agencies with little or no past experience
in water quality planning and analysis.  Guidance was also provided in
instances where agencies had difficulty in cost and price analysis on
contract arrangements.  In some cases, states encouraged joint contracts
among 208 agencies with common problems.

        15 agencies indicated that they would be contracting out
over 75% of their total budget; with 2 agencies planning for more than
90% contract work.   Size did not seem to be a controlling factor in
contract decisions.  Two agencies with similar large grant awards, for
example, chose directly opposite approaches.  One committed 90% of its
budget to contract work; the other only 10% of its total.
                                 41

-------
       The decision on whether to contract out appeared to depend on
the 208 agency's expertise In the type of work 1t chose to undertake
rather than its size.   Faced with highly technical, water-related
tasks, local  208's tended to go outside their agency since experienced
personnel were difficult to find and equipment was often prohibitively
expensive to acquire.   Land use on the other hand was usually left In-
house since most regional planning agencies, COG's, etc., have had
prior experience in this  field.


Contract Activities

       53 agencies indicated that they would contract for facilities-
related work.  No differentiation was made between direct municipal
facilities planning and 201/208 coordinating activities.  The general
trend, however, was to contract out for technical/engineering Infor-
mation and then coordinate policy planning in-house.

       58 agencies indicated that they would issue contracts for
monitoring and sampling.  Although many regional  planning agencies
and COG's do water resource planning, water quality planning is
traditionally within the realm of state agencies  or consultants.  For
many 208's, therefore, contracting out for monitoring and sampling
was the most reasonable approach since staffing and equipping 208's
would be both expensive and would not necessarily insure more accurate
results.

       50 agencies indicated they would contract  for modeling-related
work, with state water quality boards and the USGS cited as the most
likely choices.  Preliminary budget information indicated that only
a small amount of individual agency budgets would be spent on modeling
in most cases.  This suggests that most efforts are being concentrated
on the use of existing models - generally from the state with some use
of university systems.  There were a few cases where strong disagree-
ment between local 208 agencies and their respective EPA regional
offices arose when EPA refused to fund extensive  modeling efforts.
Some of these remained unresolved at the time of  interviews.

       22 agencies indicated that they would contract for at least
part of their public participation program.  Options mentioned ranged
from major contracts (11) which entailed total program management to
small contracts for individual tasks such as public opinion surveys.
Although some agencies had not yet decided on the nature of their
public participation program, the general trend was to undertake as
much public participation work as possible in-house.  This decision
was prompted by the agencies' familiarity with their member juris-
dictions.

       42 agencies intended to contract for land  use work.  The
nature of contracts ranged from major areawide plan formulation to
supplementary data collection, graphics and aerial photography.
Many 208 agencies indicated their intention to contact local or county
governments since land use data was already available there or 1n the
process of being collected.
                                 42

-------
        70  agencies were  seeking outside assistance in management and/or
 institutional  literature searches, plan development and analysis.  In
 several  states,  208  agencies were either directly entering joint con-
 tracts  for such  services or were contributing to the state management
 and  coordination funds to carry out such projects.

        At  least  18 agencies noted that they intended to hire lead con-
 tractors who would have  responsibility for subcontracting elements of
 major program  tasks.  This is not to imply that all 18 were relinquish-
 ing  total  program management to a consultant.

        Some did  issue substantial lead contracts which represented a
 transfer of program  management, particularly in technical areas, to a
 contractor.  In  a few cases, lead contracts were issued for workplan
 and  budget revisions, a  most influential task-affecting total program
 scope and  direction.  However, most lead contracts involved only 3-4
 subcontracts.  In such cases, agencies simply found it more convenient
 to rely on a major contractor rather than worry about complicated and
 cumbersome minor contract arrangements.


 Type of Contracts

        Among over 300 tentative contracts mentioned, a total of 137
 were intended  for engineering type firms.  Of these, 79 were specifi-
 cally slated for architectural and engineering companies and primarily
 involved facilities  planning, storm water and combined sewer studies;
 22 were intended for engineer/planning firms and 36 were labeled
 environmental  engineering contracts.  The latter usually involved
 broader water  quality studies.

        Planning  firms were only mentioned in 37 contract proposals.
 These were primarily related to population projections and land use.

        Management consultants were noted in reference to 62 intended
 contracts.  Most of  these involved management/institutional/financial
 studies  rather than  program management.  The latter contracts were
 usually  delegated to engineering firms since so much of 208 planning
 involves highly  technical work.

        Seventeen  individual lawyers and/or legal firms were cited as
were 11   public opinion-type contractors.  About 29 undefined water
quality  consultants  - usually biologists, testing labs or environ-
mental   research  groups - were also listed as potential consultants or
contractors, including 6 contracts to universities.

       A total  of 82 contracts were intended for government agencies
or jurisdictions.  Twenty state contracts - primarily for water qual-
ity monitoring and analyses, facility studies and management arrange-
ments - were to  be arranged with water quality offices, labs, etc.
Nineteen contractual  arrangements were outlined for 201/208 coordina-
tion, assistance, land use data and sub-plan formulation and capital
improvements planning.  Thirty county contracts were also noted

                                 43

-------
primarily In the West and South.   These contracts were geared toward
tasks similar to those intended for local agencies, with the notable
exception of a higher preponderance of legal/management/Institutional
work.  An explanation may come from the fact that many of these same
areas were considering regional management solutions, a subject area
in which county governments may have the most knowledge and under-
standing.  Finally, at least 13 federal agency contracts may be
issued under 208 with the U.S.6.S., Soil Conservation Service, the
Army Corps of Engineers,  and the  Department of Agriculture Forestry
Service cited for water quality-related tasks.

       In general, it appears that 208 agencies are being prudent 1n
their contract decisions.   They recognize the need to strengthen
agency staffs in those areas which are essential  for program conti-
nuity and plan updates.   Yet with the forewarning of EPA regional
staff, they have generally recognized the advantage of limiting con-
tract work so as to retain control  over program direction and work
scope.  Outside consultants may be less interested in seeing a
program through, less able to view the program as an integrated
whole and less committed  to plan  implementation.   This same situa-
tion exists with agencies  that have hired staff for only 2 years.
For these reasons, EPA should continue to counsel 208's against
inordinate reliance on contractors,  except in those cases where
contracting is more reliable and  economical.   In  the latter case,
agencies must be particularly aware of that fine  line at which
they are apt to lose control  of the program and jeopardize its
success.
                                44

-------
                    TIMING AND FINANCIAL PROBLEMS
 Findings
       Most agencies thought that two years was too short a time to
adequately accomplish the tasks in their work plan.  The most common
problems mentioned were:
            Due to start-up time and the need to prepare a Project
            Control Program, 3-6 months is lost at the beginning
            of the 24-month planning period.
            Evaluation and approval at all levels takes an addi-
            tional 3-6 months at the end of the period.
            When water quality or land use data must be newly
            developed, agencies will have difficulty completing
            other tasks that depend on that information.
            There is confusion as to what outputs are due after
            2 years and what tasks can be carried over into on-
            going planning.
            Few agencies have seriously begun to consider manage-
            ment and implementation.
            When management was seen to require establishment of
            a new authority, lengthy delays to obtain legislative
            authority were anticipated.
       Furthermore, most agencies expressed serious doubts that they
could continue 208 planning on a totally financially self-sustaining
basis.  Recurring comments were:
            The local governments do not see a way to raise
            enough money on their own to sustain 208 planning.
            The local governments do not consider themselves bound
            by their resolutions-of-intent to pay for 208 planning
            after the grant runs out.
                                  45

-------
       t    Federal and State financial assistance is essential
            if 208 is to continue beyond two years.


Timing and the Two-Year Planning Period

       All programs were asked "Is the two-year planning period
realistic?"  The answer was a resounding "No."  Programs were then
given a list of 30 work task elements and asked which ones were not
realistic within the two years, and how much more time would be
needed.  The list and results are presented in Table 19.  One addi-
tional response was added to the list because it continually arose.
Called the "Synergistic Effect", it refers to the situation that
any one work task taken alone could be completed, but not all of
therrTtaken together within the given time period.  The total is
somewhat low given it was tabulated from isolated comments, and not
a direct question.

       The most common complaint was that programs do not really
have two years.  Over 2/3 of the programs mentioned that "start up"
has seriously cut into their two-year period, on the average of
about six months.  This included such problems as hiring staff and
administrative organization as well as getting contracts approved.
All programs noted that the need for a detailed work plan and the
Project Control Program (PCP) takes a minimum of 3 months from the
24-month period.  It is useful to note that some of those agencies
designated in FY '74 are no further ahead in this regard than the
FY '75 designations.  Many programs appear resentful  of the need to
prepare the PCP because they feel they already have an adequate work-
plan that cost them considerable time and money to develop at their
own expense.

       Another common complaint about timing involves the building
block nature of the program.  Data analysis depends on data acquisi-
tion.  Developing point and nonpoint source control plans depends on
knowing the extent and sources of problems.  Developing institutional
and management plans depends on defining water quality plans.  Thus,
if one step does not meet schedule, all the others also fall behind.
Over 35% of the agencies answered that data acquisition and analysis
would be a problem, either because it is not available or 1t is not
useful.  Because most of the grant awards were made at the end of the
fiscal year, agencies have lost badly needed data for summer low flow
conditions and this data cannot be available again for 12 months.
Such agencies therefore will have special problems in meeting the two-
year deadline.

       13% of the programs anticipated problems in meeting interim
output deadlines both because data was not available and because of
the lengthy process involved in seeking public approval.
                                 46

-------
                                     Table 19

                     NUMBER OF AGENCIES  ANTICIPATING PROBLEMS
                        DURING THE 2-YEAR PLANNING PERIOD
                                                REGION
TASK
Analysis of water quality factors
Review of appropriate Institutions
Data acquisition
Data analysis
Review alternative controls
Alternative management agency
Selection of appropriate Institutions
Selection of appropriate management plans
Development of point source sub-plans
Development of nonpolnt source sub-plans
Plan evaluation
Plan review and adoption:
Local
Advisory corrrolttee
Certification by state
EPA approval
Municipal facilities
Identification of urban stormwater
controls
Construction priorities
Staffing
Administrative
Regulatory program
Identification of construction, operation,
and maintenance agencies
Control of residual wastes
Implementation of schedule
Selection of management agency
Synergistlc effects
1
4
-
3
2
1
2
3
3
-
2
4

7
2
2
1
1

1
-
2
3
4

1
3
4
3
-
2
2
-
9
5
-
-
-
-
-
1
1

2
-
2
2
-

1
-
4
3
2

1
1
2
1
2
3 4
2 5
-
3 10
2 3
1 7
5
2
1 10
1
8
15

2 13
1 5
6
5
2

1 5
4
5 8
3 7
5

5
-
8
1 12
1
5
3
3
11
6
4
6
3
5
2
8
7

13
5
3
2
3

5
1
1
5
4

3
3
3
4
3
6
_
-
3
2
1
-
1
2
1
2
-

3
3
3
2
-

-
1
5
2
-

-
1
1
1
2
7
-
-
1
-
1
-
-
-
-
1
1

2
1
2
-
-

-
-
2
1
1

-
-
2
1
-
8
3
1
6
3
2
2
3
2
1
6
3

5
1
3
1
1

1
2
10
6
1

-
1
2
2
-
9 10
1 3
-
1 3
1 4
2
2
4
- , 5
1
4
1 3

1 7
1
1 l
2
2

3
1
1 5
1 5
2

1
2
-
2
-
Total
23
4
50
28
19
17
16
28
6
32
35

55
19
23
15
9

17
9
43
36
19

11
11
22
27
8
Total
                                58   41   24  150   116
36
                                                         16   6B
                                                                     65
                      582
                                       47

-------
       It is generally unclear what planning must be completed within
the initial  two years and what planning elements can take place after
the two years.   Most agencies believe that all  outputs and plans will
be due at the end of two years and believe they will have considerable
difficulty achieving that goal.   The local agencies seek EPA guidance
on minimum acceptable plans and on the content  of the continuing plan-
ning process.

       There are serious barriers to meeting the two-year deadline for
completion and approval  of most plans even if the planning and analy-
sis proceed according to schedule.  55 agencies felt that local review
and approval of the plan would jeopardize meeting the 24-month dead-
line.

       The development of a satisfactory management system will take
much time, thought and discussion.  Ideally, the 208 planning process
should be producing interim management outputs  throughout the two-
year planning period prior to the final  selection of a system.  How-
ever, most 208 programs  are not generating these outputs yet.  Few
agencies had seriously begun to consider management and implementation
when the interviews were conducted, although most interviewees said
they would begin management alternative analysis within the first year
of their planning effort.  It should be noted that 10 of the 23 agen-
cies saying they would begin management analysis at day one were in
one particular region where the (fegional  EPA office stressed the im-
portance of addressing this problem early in the process.   15 others
said they did not know when management analysis would start.  Related
to this is the fact that agencies did not yet know whether this work
would be done in-house or by consultants.

       Agencies were asked if the legal  powers  required of a manage-
ment agency could be acquired prior to the two-year deadline.  Table
20 presents the results.


                              Table 20

             RESPONSE ON ABILITY TO ATTAIN LEGAL POWERS
           FOR MANAGEMENT AGENCY PRIOR TO 2-YEAR DEADLINE
Yes

No

Don't know

No answer

Total

1
1
12
-
4
17

2
4
3
-
4
11

3
1
3
-
8
12
R !
4
4
14
3
5
26
I G I
b
n
-
12
2
25
0 N
6 7
3 2
2 -
1 3
2 -
8 5

8 9 TO
9 1 7
2 - 1
-
10 - 2
21 1 10

Total
— MB^BUMHI-
43
37
19
37
136
                                48

-------
        44% of the  agencies  responding  answered yes~;  39%  answered  no;
 and  17% did not  know.   Acquisition  of  legal  authority was  felt  to
 depend  on  the controversiality of the  plan  and whether management
 would be primarily by  the  local  governments,  in which case little
 additional  authority would  be  necessary.   If the  management system
 foreseen would include any  kind of  institutional  rearrangement, and
 if,  therefore, special  state legislation would have  to be  passed,
 delays  of  up to  two years were predicted.

        Most agencies felt  they would be well  into year two before a
 management plan  was devised and that at least two sessions of their
 state legislatures would be required to secure legislation or consti-
 tutional amendments.   Many  legislatures meet  only once every two
 years,  and many  were characterized  as  conservative by the  208 agen-
 cies.   There did not seem  to be any distinction between  agencies  that
 were COG's or RPA's and those  that  were other types  of planning bod-
 ies, such  as county planning departments or  economic development  dis-
 tricts. Even the  one  state planning agency  designated felt that  the
 necessary  legislation  could not be  obtained  in two years.


 Financially Self-Sustaining Planning Process

         Section  208 provides funding for a two-year planning
 period.  It authorizes  the  Administrator to make  grants  to  desig-
 nated agencies for the  costs of  developing and maintaining  an on-
 going areawide waste treatment management planning process.  How-
 ever, since no funds have been allocated for  the  continuing  process
 as of this  time, 208 agencies  must  find a way to  totally finance
 their own  programs after the two-year  period  expires.

       When the agencies were  asked  if  they expected  problems in
establishing a financially  self-sustaining  planning  process, 92
responded affirmatively, and only 27 negatively.   There were no  mean-
ingful  distinctions among the  different types of  208  agencies in how
this question was answered.

       The designated agencies  were  then asked which  of the following
methods they were expected to  use to fund  a continuing 208 program:
contributions  from participating agencies  on local governments,  gener-
al revenue fund allocations, user charges  and general obligation
bonds.

       Most did not expect success in obtaining increased funding
contributions  from participating agencies  or governmental units  suffi-
cient to support continued planning.  The other three methods suggested
were seen as only  slightly more  feasible for financing 208  planning.

       Resolutions of intent were mentioned by several agencies  as
signs of commitment on  the part  of their governments to  an  ongoing plan-
ning process.  The locals do not view the resolutions as binding them
                                  49

-------
to pay for 208 planning after the Initial two-year period expires.
In light of the budget crisis cited by many designated agencies, and
the fact that 107 of  the 136 agencies Interviewed said they would
not have participated 1n 208 had there been only 75* funding, finan-
cially self-sustaining 208 planning may be totally unrealistic.

       Federal contributions are felt by the designated agencies to
be absolutely essential  if 208 1s to be the ongoing process it was
Intended to be.   Some financial  assistance from the states  is hoped
for and at least one state has already agreed to provide it.   If
financial aid 1s not forthcoming, the 208 agencies  will  be  forced to
drastically lower their  water quality goals  or drop  the program
altogether.
                                50

-------
                  DESIGNATION AND GRANT APPLICATION
Findings
       The data gathered on the designation and grant application
processes provides an insight into some of the problems forthcoming
in the planning process.  Additionally, it highlights problems to
avoid with next year's applications.  Briefly stated:
            Agencies have been either unwilling or unable to
            produce detailed workplans before grant award.
            Allocating a portion of the grant for workplan
            development would greatly expedite the presently
            overloaded planning process.
            The requirement of obtaining resolutions of in-
            tent has been administered inconsistently by the
            Federal Regions.  Many local governments are un-
            willing to bind themselves to plan implementation
            at this time.
Why Enter 208 Planning?

       The desire to enter 208 planning can be attributed to several
factors.  Local agencies were understandably enticed by a program
offering 100% Federal funding.  Most saw this as an opportunity to
undertake planning efforts which they could not otherwise afford.
This was clear from the fact that the majority (79%) would not have
applied for the grant on the basis of a 75% Federal share.

       An equally important factor was the desire to prevent the
state from undertaking such planning.  Most localities, seeing this
as a possible alternative, chose to keep the planning locally based.
An additional incentive was the belief that future Federal grants,
in particular 201, would hinge on 208 planning.


The Designation Process

        145 of 149 agencies were designated by governors.   Four  agencies
were self-designated.  These are Charleston, West  Virginia; Washington
Metro; Lakes Region, New Hampshire; and Salern-Rockingham, New Hampshire.
Self-designation has not proven an impediment thus far.   There is  a wide
range in total time taken for designation.  The results are presented
in Table XXIV.
                                   51

-------
                              Table  21

                TOTAL  TIME  OF DESIGNATION  PROCESS*


                                 R E  G  ION
Time
< 1
1- 4
4- 8
9-12
12-15
7-15
No
month
months
months
months
months
months
answer
1
-
1
8
4
3
1
-
2 3
1
8 3
3
1 1
1 -
1 1
3
4
1
7
6
3
6
2
1
b
-
7
10
2
1
5
-
6 7 8 $
- - - -
4 - 8 -
2191
122-
1 -
2 -
1 - 1 -
TO
-
1
1
3
3
2
-
Total
2
39
41
19
15
14
6
   Total         17   11    12    26    25     8     5    21     1    10    136

*In some cases could not be separated from grant  application  process.
Two agencies completed the process  1n  less  than  one month,  while 29
agencies took over one year.   The majority  of  agencies  (80) were desig-
nated in the range of 2 to 8  months.   Although this is  a  reasonable
amount of time 1n the majority of cases,  1t 1s in  part  due  to  adminis-
trative expediency at the end of FY 1975.   The 21 % which  took  over one
year were for the most part those who  applied  for  designation  early in
the process.  They were generally held up either by lack  of guidance at
the local level  or by Indecision at the Federal  level.


Preparation of the Designation Package and  Grant Application

       The designation materials were  prepared by  the agency staff 1n
120 cases.  The remaining 16  were prepared  either  with  or solely by
consultants.  This breakdown  is generally the  same for  the  grant appli-
cation process.   101  agencies prepared the  grant application in-house.   Ten
were written by consultants,  and twenty-five were  developed jointly.


Problems in the Designation and Grant  Application  Processes

       Designation and grant  application requirements were  often ful-
filled simultaneously, or in  overlapping time  periods.   The following
figures represent difficulties encountered  during  both  procedures.
Results are presented in Table 22.

                                 52

-------
on
co
                                                    Table 22


                  AGENCIES  WITH MAJOR PROBLEMS IN THE DESIGNATION AND GRANT APPLICATION PROCESS
R E G I
PROBLEM
Lack of local agency desiring to do 208 planning
Lack of interest or cooperation from the State
Lack of interest or cooperation from the
Regional office
Dispute over appropriate boundaries for 208 area
Absence of legal authority to do all or part of
208 planning
Delays in eliciting other local agencies to
cooperate with 208 planning
Delays in organizing interstate cooperation
(where applicable)
Delays in obtaining resolutions-of-intent from
local governments
Lack of technical knowledge about local water
quality problems
Lack of staff
Lack of funds
Confusion regarding the designation requirements
and/or estimated cost of the 208 study
Public disinterest in or hostility toward 208
planning
Others?
1
-
3

-
5

1

2

4

10

3
6
11

9

4
-
2
3
5

1
1

1

1

-

1

2
3
2

5

2
-
3 4
2
3 4

2 1
1 10

1

7

4

2 11

1 7
1 12
4 10

2 14

2 6
1 1
5
-
9

2
5

2

6

3

7

3
7
7

6

3
-
0 N
6 7
1 1
1 2

3
3 -

-

1 2

1 1

2 1

2
2 1
1 3

1 4

2
-

8 9
4 -
4 1

1 -
3 -

4 -

5 -

-

10 -

7 -
8 -
8 -

5 1

1
2 1

10
-
4

-
7

1

3

-

3

4
7
7

5

2
_

Total
11
36

10
35

10

27

13

47

29
47
53

52

22
5

         *Total is  greater than 136 due to multiple responses.

-------
       The major problems resulted from the framework of the processes
themselves in addition to difficulties which general y accompany the
inception of a large Federal grant program.  Diff culties resulting
from the framework are the development of a detailed workpan before
grant award and the legal aspects of the resolutions of intent.

        The cost of developing a detailed work program was apparent
with TOO agencies,reporting difficulties resulting from lack of staff
or  lack of funds.'  Over one-half of these agencies (52) said they
were confused about requirements and/or estimated cost of the 208
study.  The result of this has been a request for revisions of work
plans throughout the country.

       It is  understandable,  even with  adequate  funds  to  prepare the
application,  that an  agency would be  wary  of a large  investment  with
no guarantee  of a grant.   At least 17 agencies applied  for  FY  1975.
funds and were not awarded grants.

       An alternative policy of letting  out a %of  the  grant  after
designation (or retroactive payment)  for thorough  workplan develop-
ment would eliminate  much duplication and  wasted effort.  This year's
experience has enabled  EPA to^clear up  the guidelines/requirements of
designation and grant application.  These  procedural improvements
should insure  the planning process  begins  on  receipt grant award.
Resolutions of Intent

       The requirement of resolutions of intent from jurisdictions 1n
208 areas was met in varying degrees across the nation.  The original
requirement of "all participating jurisdictions" was loosened to
"workable" for planning and implementation; a consensus on the defini-
tion did not emerge.  In some cases, the resolution requirement was
filled by a letter from the governor guaranteeing the use of the police
power to implement the 208 plan.

       29 agencies plan to acquire a total of 80 additional resolutions
not obtained prior to grant award.  This figure veils a number of agen-
cies who feel that the grant award completes designation process and
therefore they need not pursue additional resolutions.
 1
 This figure may be slightly inflated due to dual responses.
                                 54

-------
       There was a significant difference in the administration of
this requirement by the Federal regions.  Some Regions remained
stringent from 90 to 100% requirements.  Interpretations include all
jurisdictions with population over 5,000, the major jurisdictions
and "anyone who would give them."  In some cases, no resolutions were
obtained prior to designation, and had yet to be pursued at the time
of the interview.  These cases were covered by letters from
the governor.  Given the need for local approval of a 208 plan, this
approach seems to circumvent the purpose of obtaining resolutions.

       EPA's attempt to get assurances that the local jurisdictions
are aware of 208 planning, and that local circumstances are favorable
to 208 planning and implementation of 2081 often was not fulfilled by
the requirement for resolutions.  A common local reaction to requests
for resolutions was fear of giving blanket approval to a plan yet to
be made - a reasonable deduction from the resolutions' use of the word
implementation.  Refusal in other cases was the reflection of local
political jealousies and problems that in the end had no direct bear-
ing on the planning and implementation of the 208 program.  It is also
somewhat inequitable that some agencies were made to go to great
lengths to obtain the majority of resolutions,  while in a few instances
the issue of resolutions was simply passed over.
 Cost  of Grant  Application

        The range of costs  incurred  by 208 planning agencies in prepa-
 ration  of grant  application  reflects the problems resulting from re-
 quiring considerable expenditure  prior  to grant award.  The results
 are presented  in Table  23.   The cost2 ranged from less than $500 to
 $75,000.   The  cost  to the  majority  (56) of agencies was between
 $1,000  and $10,000, although a significant number (34) spent over
 $10,000 but less than $50,000.  Once again, the difference of invest-
 ment  is apparent, and would  be remedied by a % of the grant allocation
 for workplan development.  Aside  from costs, however, 90 agencies
 replied that grant  applications requirements were reasonable in light
 of their local situations.
1
 AM-4, April 3, 1975
2
 Designation costs could not be separated in some cases.

                                  55

-------
                              Table  23

                     COST OF  GRANT APPLICATIONS
Cost
<$ 500
500- 999
1,000- 4,999
5,000- 9,999
10,000-14,999
15,000-24,999
25,000-49,999
50,000-74,999
> 75,000
No answer

1 2
1 -
9 1
4 -
2 2
1 2
1
1
4

3
1
4
1
1
1
1
3
R E
4
2
12
5
1
-
6
G I
5
1
2
4
4
4
6
1
-
3
0 N
6 7
1
2
1 -
1 1
1
-
6 -

9 id
1 -
2 - 1
4 - 5
3 - 2
1 1 1
1
_
10 -
Total
1
5
28
28
14
10
12
4
2
32
Total
17   11    12   26   25
8
21
1   10   136
NOTE:These often would not be separated  from designation  preparation
       costs.
       It is interesting to note how some  of the  grant  applications  were
paid for*.  In 8 regions, HUD 701 assumed at least part  of the cost of
grant applications.   In other cases, cost  was assumed by private founda-
tions, states, consultants, or individuals devoting  their own time.   In
many cases, the funds were from contributing local jurisdictions.
Assistance and Coordination

       In the designation process, 36 agencies  reported a lack of inter-
est and/or cooperation from the state; while only ten had difficulties
with the Regional office.  In the grant application process, 24 agencies
reported difficulties with the EPA Regions.   Often this was the result
of disputes over level of funding.  Only 26  agencies had difficulties
with the state.  One problem was continual  requests for revision of
documents—often the fault of unclear guidance  on allowable tasks; for
example, infiltration and inflow analysis and modeling.  Another was
simply the slow process of establishing effective administrative rela-
tionships on the part of both the States and EPA regional.  Apparently,
some Regions were inconsistent iii designation due dates which added
to the problems of designated agencies.  Aside  from administrative prob-
lems, actual assistance in the preparation of the applications was forth-
coming from both the states and the regions.  This varied from minimal
assistance to actual  development of applications.   113 agencies reported
assistance from the Federal Regions, while 81 agencies received help from
their states.
*This was not an interview question,  but was  continually referred to.
 therefore, cannot be developed as  a  national  statistic.

                                 56
                                                    It,

-------
                            COORDINATION
Findings
      Looking at the different planning programs and mechanisms of
coordination provides a brief overview of existing and potential
coordination between the 208 agency and other institutions or plan-
ning programs.  Several key Issues surfaced:
            The local 208 agencies need clear guidance on the
            substance and timing of 208/201 coordination.
            The role of state planning and the mechanisms for
            state/local coordination need to. be clarified.
      •     Those 208 agencies located within multi-functional
            planning agencies have the greatest potential for
            programmatic coordination.


Coordination Between 208 and 303(e)   Basin Planning

      The State 303(e) water management plans are an essential input
to the 208 planning process:
      •     Water quality goals and standards

      •     Definitions of critical water quality conditions

      •     Waste load allocations


These inputs to the 208 planning process are to provide a sound base
upon which the 208 programs will be built, yet as of March, 1975, only
50 of the 500 303(e) plans were complete.  It was apparent, however,
that those 208 agencies in areas where 303 plans were of poor quality,
behind schedule or non-existent, were at a disadvantage.

      For example, some states viewed 208 planning as an alternative
method for developing the 303(e) information, and were waiting for
outputs from the 208 process for their 303(e) plans.
 1
 Complete  information on the 303(e)  Plans  could  not  be  obtained  as
 in many cases  the  agencies  had not  obtained  or  analyzed  them.
 Answers reflect  general  discussions on  the status of 303(e)  Plans
 and  could not  be statistically tabulated.

                                 57

-------
      Another example of difficulties  obtaining state water quality
information occurred in areas  where 303(e)  plans were non-existent
and agencies had to rely on 3C  plans where  available.  To what extent
information generated under the 3C  program  could be substituted for
the 303(e) inputs was a question agencies in  the State had only begun
to consider.  Determining what information  can  be used and what new
information must be generated  will  slow down  the 208 planning process.
Coordination Between 208 and the  NPDES

      Approximately 80% of the agencies  interviewed  had made at least
preliminary contact with the State NPDES agency.   53% of the agencies
had actually obtained lists but only 30% of the agencies had actually
reviewed the permits to see if they meet their 208 planning needs.

      Specific plans for coordination between  the  208 and 402 programs
were difficult to obtain, in part because of the variety of ways by
which the 402 program is administered.   In some cases, 208 agencies
could deal directly with their respective states to  obtain permit
information.  In other instances, permits are  administered by EPA
through the states.  In such cases, agencies were  uncertain whom to
contact.  This is critical because the  National Pollutant Discharge
Elimination System permit program will  provide an  essential tool for
the implementation of the 208 plans. Permits  issued are to be in con-
cert with approved 208 plans.
Coordination Between 208 and 201  Municipal  Facilities  Planning

      Agencies have indicated their intention  to  allocate an average
of 14 to 15% of their total  budgets to carry on municipal facilities
planning and review to the best of their ability.   Approximately 95%
of the agencies said that 201 municipal  facilities  planning and/or
construction was ongoing in their 208 area.  Just under 80% stated
that they felt existing 201  plans were in concert with their antici-
pated 208 planning effort, but this finding  must  be interpreted with
caution.  The response often appeared to be  based on incomplete
knowledge of existing 201 planning efforts.

      Most agencies interviewed were not sure  of  the programmatic and
timing relation between 208 and 201 municipal  facilities planning and,
consequently  were hesitant to make specific plans  for coordination
until more guidance was available.  Two observations seem to charac-
terize the situation of the locals.  First,  the original draft guide-
line did not detail the programmatic relationship between 208 and 201.
Secondly, more recent guidance cautioned the 208  agencies not to slow'
down the 201 construction process.  Most agencies recognize the need
to avoid delaying the 201 process but more specific guidance on estab-
lishing coordination between the programs appears warranted.
                                 58

-------
Coordination With Other Environmental Programs and Other Areawide
planning Programs


        Various  environmental  programs  in  regional planning agencies
are  provided with  an  excellent opportunity  for coordination.  Most
interviewed felt that the  ease of  in-house  coordination would be
mutually  beneficial to their  ongoing programs.

      29 of the 208 agencies interviewed stated that they either were
air quality maintenance areas or overlapped with them to some extent.
62 agencies have either completed or are currently working on solid
waste plans as providing them with background and experience to  enter
the 208 planning process.
Coordination Between 208 Agency and the State

      Nearly all the agencies said they had made contact with their
state's water quality office, yet only half of them indicated that
some sort of coordination plans were established.  These were most
often in the form of a state coordinator or participation in the tech-
nical advisory committee.  Some state personnel were to be supplied
to 208 agencies through coordination and technical assistance con-
tracts.  Between 4 and 8% of the planning grant was available for this
type of contracting with the state.  The content of the contract was
usually described in a general nature but ranged from extensive tech-
nical services, involving more contract money, to providing data format
specifications to standardize the input to the state planning program.


Means of Coordination with Other Governmental and Other Planning
Programs

      Most agencies did not have well developed mechanisms for coordi-
nation with other agencies and related programs.  At the time of the
interview, most established coordination focused around information
exchange.  Coordination involving more specific work task elements was
usually in the planning stage.

      The committee structure was the most commonly mentioned means
for achieving coordination.  It serves a vital function by providing a
form of umbrella coordination, allowing direct communication among
representatives of many groups.  Representatives of related programs
and interest groups hold seats on 208 advisory committees and in turn
208 staff occasionally hold seats on advisory committees of other pro-
grams.  A parent agency often provided its 208 agency with a skeleton
of a citizen advisory or technical advisory  committee,  or at least
provided the channels for assembling them.   Sometimes regional  sub-
committees were formed in the larger 208 areas where long, difficult
drives might discourage regular attendance.
                                  59

-------
      Frequently mentioned mechanisms through which information was
exchanged with the 208 agencies are inter-program staff meetings,
newsletter exchanges, A-95 Clearinghouse review and comment proce-
dures, and accessibility of the in-house planning expertise in a
multiple function parent agency.  The availability of a common data
base or common population and land use projections from other plan-
ning organizations was mentioned as a good opportunity for planning
coordination.

      Contracts for specific tasks were often mentioned as providing
coordination between the contracting parties.  For example, the Soil
Conservation Service has several contracts to provide 208 agencies
with soil analysis and will thereby become involved with the planning
process.  In cases where studies are done over an area larger than the
208 area (e.g. aerial photography), the 208 agency contracts for only
that portion of the study relevant to the planning area.  A benefit
seen is the potential for coordination with areas outside the 208 area.
Some 208 agencies are contracting with municipal  facilities management
agencies and engineering firms in the facilities  business to aid coor-
dination between the 208 and 201 programs.

      Contracting was often said to be part of the coordination with
other 208 areas.  208 agencies in at least two states are joining with
the other 208 agencies 1n the state to hire a single consultant for
specific work tasks.  In another instance, several 208 agencies have
contracts with a single 208 agency to provide them all with results of
a study on a common problem.

      The following table is interesting because  it shows the broad
range of programs and agencies that must coordinate 1n some manner
with the 208 program.  All  208 agencies were asked to complete a table
listing agencies that had been contacted and methods of coordination.
Figures are understated for two reasons.  First,  the methods column
contained no cues, thus the answers were all volunteered and often
general.  Second, no consistent distinction was made between methods
in existence and anticipated methods.   Some respondents chose not to
answer 1f they were either uncertain or if no formal  means of coordi-
nation had been established.

      Although the figures  are incomplete, the table is useful  because
it shows both the large number of programs that must be coordinated
and it shows the relative frequency of methods of coordinating that
will be used.
                                  60

-------
                                                            Table 24


                               NUMBER OF 208 AGENCIES WHICH MENTIONED THE  METHODS OF COORDINATION
                                           USED  IN  RELATION TO THE ORGANIZATIONS  LISTED
                                                                            T  H
en
ORGANIZATION
Air Quality
Solid Waste
Transportation
Coastal Zone Management
Corps of Engineers
U.S. Forest Service
Soil Conservation Service
U.S. Geological Survey
Housing, Urban Development
National Park Service
EPA
Other Federal
State
Local
Regional
Contacted
but not
Specified
30
27
29
15
21
16
16
3
1
-
1
15
10
9
1
Cormri ttee
23
29
21
13
26
51
47
8
-
8
6
14
62
43
-
Contract Contract
from 208 to 208
2
4 1
2
3 1
4
2
2
5
1
-
1
3
3
4
_
Merros ,
Information Joint Agreement, Staff
Exchange Studies Correspondence Sharing
7
8
7
2
5
8
9
3
-
1
1
3
7
2
-
1
4
2
2
3
2
1
2
-
-
1
6
2
1
-
4
4
5
1
9
9
6
4
-
-
-
3
6
n
-
8
10
13
3
4
10
5
3
T
i
-
1
4
5
5
-
In-
A-95 House
8
- 21
1 21
6
1
1
2
\
-
_
.
2
3 1
1
-
       Note:  Methods are not mutually exclusive.

-------
                       EVALUATION AND GUIDANCE



Findings

       The major findings on evaluation and guidance are listed below.


       t    There is a serious delivery problem with EPA guidance
            to date.  A significant number of agencies never re-
            ceived handbooks  while a fair proportion received
            them too late to be useful.


       •    Technical guidance needs are similar throughout the
            country.  The top four were consistently:  nonpoint
            source analysis, monitoring (point and nonpoint),
            urban storm water, and combined sewer analysis.


       •    The most requested management/legal/institutional
            seminar is state-enabling legislation outlining alter-
            natives for a successful management agency.  Ideally,
            this would be given by the states with proper guidance
            from EPA.


Section 208 Draft Guidelines

       The Guidelines were the only consistently available guidance for
those agencies seeking a 208 designation.  They were considered useful
by 101 agencies.  The value of the Guidelines was primarily for back-
ground information on the 208 process (educational), rather than effec-
tive program guidance.


Designation and Work Plan Handbooks

       The need for timely guidance is evidenced by the variety of
problems previously discussed in both the designation and grant appli-
cation processes.  It appears that the problem rests with the delivery
as opposed to the substance of such guidance.  Thirteen agencies never
received the Designation Handbook while seven never received the Work
Plan Handbook.
                                  63

-------
       61 agencies received the Designation Handbook too late for it
to be useful in the process.  45 agencies received the Work Plan
Handbook equally lateJ  This reflects a serious delivery problem
occurring at certain Federal Regions, as well as a wasted effort in
developing guidance for the majority of agencies able to make headway
on their own.  Some agencies received the handbooks through informal
channels.  Examples include "given by consultants", "copying another
agency's copy", and "picking it up on a trip to Washington, D.C."
An improved regional distribution system or a policy of direct mailings
should prove a useful  step toward improving the delivery of guidance.
Workshops2

       The EPA workshops were  received  with  mixed  reactions.   The
figures available indicate the number of workshops  attended by each
agency.

                              Table 25

                  WORKSHOP ATTENDANCE BY AGENCY

                                             Number  of Conferences
       Number of Agencies                    	Attended	

               19                                      0
               52                                      1
               43                                      2
                9                                      3
               11                                     N/A
              	2                                  Don't know
              T3F


        Unfortunately,  the majority  found the conferences only marginally
 useful.   Some stated that the information was  not  up-to-date  or  general-
 ly not helpful.   Others were  further along  in  the  process than the  sub-
 ject discussed.   Reasons for  not attending  were that they were unaware
 of workshops, or that  the workshops were too far away.  An indirect
 1           '    ~~~
  Does not include FY  '74  agencies, as handbooks were not  published.
 2
 All  meetings on  208  will  be discussed together, as most  agencies
  could not distinguish  sponsors, or particular subject matter.
 Therefore, the most  that could be obtained was general impressions.
                                64

-------
benefit of the conferences which frequently emerged was the informal
contact with other 208 agencies.  Exchange of information on that
level proved very beneficial.
OBERS "Series E"

       As the use of OBERS was a directive from EPA Headquarters, it
will be discussed under the guidance section.  101 agencies reported
that they were not using OBERS projections, although frequently it
was consulted as a base for individualized projections.  Persons
interviewed at thirteen agencies were not familiar with OBERS Pro-
jections.

       The major reason stated for not using OBERS was that the agen-
cies believe they were too low.  The political sensitivity to low
projections can be understood in light of potential future grants and
allocation among jurisdictions who have received a grant.  Addition-
ally, areas subject to high seasonal influxes (tourism) did not feel
that element received adequate treatment in OBERS.  208 areas often
did not coincide with the boundaries of OBERS projections.  As the
county is the smallest jurisdictional unit of OBERS, partial counties
in 208 areas of which there are 111 could not be properly estimated.
Nor do OBERS account for the secondary effects in energy, recreation,
mining, and other areas of expected population increases.

       Certain states are developing and in some cases requiring the
use of their own population projections.  The State of Utah has been
exempt from using OBERS.  Some agencies are not willing to accept
state projections either.
Technical  Guidance

        The need  for  technical  guidance was a major concern of the 208
agencies.   EPA was most  often  chosen  to  provide this guidance.  The
prioritized needs for  such  seminars was  amazingly consistent through-
out  the country.  The  following  list  ranks by significant number of
requests those seminars  which  are most wanted by those interviewed.
The  most prevalent need  is  in  the area of nonpoint source guidance.
Given  regional variations,  combined sewer analysis, point and non-
point  source monitoring,  and urban storm water seminars are consist-
ently  a top priority throughout  the country.  Regional prioritized
requests with a  significant number of mentions are listed below.
                                  65

-------
Prioritized Regional  Requests for Technical  Workshops
Region 1

  Nonpoint source analysis
  Monitoring (point and nonpoint)
  Urban storm water
  Combined sewer analysis

Region 2

  Nonpoint source analysis
  Monitoring (point and nonpoint)
  Urban storm water

Region 3

  Urban storm water
  Nonpoint source analysis
  Monitoring (point and nonpoint)

Region 4

  Urban storm water analysis
  Nonpoint source analysis
  Monitoring (point and nonpoint)

Region 5

  Nonpoint source analysis/agriculture
  Urban storm water
  Combined sewer analysis
  Monitoring 'point and nonpoint)
  Simplified stream modeling
Region 6

  Urban storm water analysis
  Nonpoint source analysis

Region 7

  Combined sewer analysis
  Nonpoint source analysis
  Monitoring (point and
    nonpoint)

Region 8

  Nonpoint source analysis
  Monitoring (point and
    nonpoint)
  Urban storm water

Region 9

  Nonpoint source

Region 10

  Nonpoint source analysis
  Urban storm water
  Combined sewer analysis
  Monitoring (point and
    nonpoint)
                         66

-------
       In the area of nonpolnt sources guidance, requests also show
the regional variation.  These figures should be used as general
indicators, as often, those interviewed were not the technical water
quality staff.  Additionally, 1t was somewhat early in the planning
process to have Identified major needs.  Requests are listed below:
                        agriculture
                        construction
                        erosion
                        feedlots
                        mining
                        petroleum related
                        runoff modelings
                        sedimentation
                        septic tank analysis
Seminars on nonpoint sources should be carefully directed to remain
useful to the particularized need of 208 areas.
Management/Legal/Institutional Seminars

       There are 110 agencies which expressed interest 1n attending
management/legal and institutional seminars.  Only 10 agencies re-
ported they are not in need of guidance 1n this area, while four
indicated they were not sure they wanted to attend seminars.

       The greatest demand for seminars across the country was for
state-specific legislative backgrounds.  This would include authority
for institutional rearrangement, such as in the case of a new manage-
ment agency, as well as nonpoint source controls (land use).  Most
Interviewed felt these would have to be given by the states, but
could be sponsored by and given direction from EPA.

       The following list is based on regional summaries, with an
attempt to pull phrases from the interviews.  It is useful not only
to pinpoint essential seminars, but also as a general indicator of
level of competence.  For example, the fact that certain agencies
were not able to respond with specific needs usually Indicated a lack
of knowledge or understanding of the potential magnitude of 208.  In
the same vein, the listing of the responses provides background as
well as direction in this area.  Therefore, the following list merely
categorizes by subject those seminars which were most consistently
desired or were particularly necessary.
                                  67

-------
            The legal  implications for interstate arrangements
            Legal  responsibilities in the consolidation of sewer
               districts—outstanding bonds and user fees
            Legal  implications of groundwater management
            Land use enforcement (controls)
            Water rights and law
Management
            Management alternatives for small  rural  areas
            Institutional  arrangements  for storm water control
            Alternative management agency structures and systems
Nonpoint Source
       •    Evaluation of nonpoint source  controls
       t    Nonstructural management of nonpoint  sources
Financial
       •    Financing a management agency structure
       •    Methods for funding the continuing  planning  process
       •    Grant management
Political
       •    Political  aspects  of 208—how  to work with  political
               conflicts
       •    Political  aspects  of creating  a management  agency
Procedural
            Evaluating technical  and  management  proposals
            Evaluating existing management  agencies
            Techniques in  conflict  resolution
            Growth  management techniques
                                68

-------
General 208
       t    Elaboration of the 201—208—303 relationship
       •    Long range Federal involvement in 208
       •    Coordination between the State and EPA
Other Suggestions

       A variety of ideas emerged on how to expedite the 208 program.
One interviewee pointed out that it is essential  to gear these semi-
nars to 208's agencies in the various stages of the planning process.
A major weakness of seminars to date is that they have been geared to
one point in time in the planning process.

       An additional aid would be the preparation of a series of semi-
nars or packages geared to the local elected officials.   The need for
education at this level was continually stressed, and would be a valu-
able aid to facilitate plan adoption.

       In order to prevent the expensive and time-consuming effort
required in the development of individual 208 films, it  was suggested
that the present 208 film from headquarters be modified  and distrib-
uted.  The study team suggests the development of a series of films
highlighting different aspects of the 208 process.  This would range
from education on the 208 process itself to elements such as nonpoint
sources.  It would also be necessary to highlight elements specific
to different parts of the country in order to remain relevant.

       Another problem to date has been the lack  of a central and com-
plete source of technical information.  It was suggested that a hot
line providing expert guidance in tune with EPA policy would greatly
expedite the 208 process.  The central 208 library being developed by
EPA Headquarters would certainly serve as such a  base.  Its success
would necessarily depend on the communications network set up to dis-
seminate this information.  Although this may not be the best approach,
the need for strong technical guidance is paramount at this time.

       There is a definite interest in the case study approach.  Sug-
gestions include:

       1)   Nonpoint source research by other 208 agencies

       2)   A history of approaches in other areas

       3)   Case studies on constraints during plan implementation

       It is felt that this approach would keep guidance less theoret-
ical , and more in line with the problems actually experienced in 208
planning.  This could be easily handled by EPA Headquarters in the
"Newsletter" to ensure national coverage.

                                  69

-------
                           APPENDIX  A

                        STATISTICAL  DATA
       The following tables provide data to supplement statistics in
the text.  136 of a possible 149 interviews were completed.   Of the 13
agencies not interviewed, 9 were in Region IX.  In some cases, however,
information was unavailable, or agencies were unable to answer the
questions as asked.  Thus, the total responses to each question does
not always add up to 136.  Whenever possible, available documents were
studied to try to answer some of the profile questions when  no inter-
view was done; thus, in some cases the number will  be 149--  the total
number of 208 agencies.  For some questions, agencies were asked to check
several items when more than one answer applied.   In these cases, total
responses will add to more than 136.

       Whenever a dash (-) is used in a table, it means that question
was asked and the response was negative, or that it was not  a factor.
Whenever a blank appears, it means that there was no response.  This is
due to any of three factors, the net result being no information.  These
factors are:

       1)  The interviewee did not have the background to answer
           the question.

       2)  The question was not asked due to lack of time.

       3)  The information was not available at that time.

       The number of agencies for which there was no information for
that particular question is totaled by region in the "no answer" column.
                                A-l

-------
Number of 208
  Agencies

Number of
  Interviews
                                TABLE  I

                 208  AGENCIES  — DESIGNATED AND  INTERVIEWED

                                   REGION
                                                T
                                    8
17   11    12   28   25
22   10
17   11    12   26    25     8    5    21
           TO"
10
           10
      Tota"
                                                                       149
       136
                                 TABLE  II

                             LEAD INTERVIEW

                                    REGION
1
208 Director 15
Parent Agency
Director
Application 2
Writer
Acting Director
Environmental
Director or
208 Supervisor
2 3 4
8 8 20

2
. w —

2
342


• 5
15

7
_

1
_


6
3

1
4

-
_


789
5 15 1

_
3

1
2


10
5

1
1

3
_


. Total
95

11
10

7
11


     Tota;
17   11    12   26   25
21
10
136
                                    A-2

-------
                                              TABLE  III
                                          OTHERS  INTERVIEWED
                                                         REGION
Parent Agency Director
Engineers
Public Participation
  Coordinator
Application Writer
Environmental Director or
  208's Supervisor
Planning Director
Other Planners
State Water Quality
Land Use
Assistant Director
Acting Director
Consultant
Citizen Group
Indian Representative
1
3
4
1
2
-
-
-
-
-
-
-
-
-
_
23456789
31-1132-
6
131-3-
_______
3 	
________
1 - 6 - - - 5 1
2 - 4 - - 1 -
4
10 - - 1
1
1 - 3
	 1
	 1
10 Total
2 16
10
9
1 3
3
1 1
1 14
3 10
4
11
1
4
1
1

-------
                                TABLE IV



                         POPULATION OF 203 AREAS
Region 1
Region 2
Region 3
Region 4
Region 5
Region 6
Region 7
Region 8
Region 9
Region 10
1970
Census
6,004,220
16,671,827
10,424,972
11,437,670
26,597,479
6,721,865
3,578,296
3,359,544
7.453,980
3,153,366
Most
Recent
Estimates
(based on
diff. yrs.)
6,436,600
17,059,242
10,758,461
12,817,820
29,552,067
7,151,068
3,612,338
3,927,835
8,432,731
3,389,600
Projections*
(to 1985, 1990
or 1995)
6,534,200*
18,726,482
11,605,578
18,744,780*
37,530,416
9,275,428
4,784,687
4,089,028*
10,950,749
4,762,933
Total
95,403,219
103,137,762
127,004,281*
*Means not all  programs answered
                                   A-4

-------
en
                                                      TABLE  V

                                     COUNTIES  IN 208 AREAS — TOTAL AND  PARTIAL

                                                                 REGION
Number of Counties
Totally included
Partially included

NUMBER OF
SMSA's Relation to 208 Area
Totally included
Partially included*



1 2
Square Miles 7406 9883
1 2
27 24
10 2

3 4
66 51
29
TABLE VI
SMSA'S IN 208 AREAS — TOTAL

1 2
7 8
7 3

SQUARE

3 4
12,915 51,572
R
3 4
9 18
10
TABLE VII
MILES OF 208
R E G I 0
5
73,218 19,
5678
97 15 17 69
19 21 4 1

AND PARTIAL
E G I 0 N
5678
23 8 1 9
15 2 2 -

AREAS
N
6789
765 9669 151,911 29,299
9 10 Total
6 13 385
17 8 111



9 10 Total
5 2 90
5 5 49



10 Total
18,103 390,562
      *Th1s number 1s overstated due to the double counting resulting  from one  SMSA being
       In  more than one 208 area.

-------
3>
I
                                                     TABLE VIII


                                 OTHER PLANNING FUNCTIONS PERFORMED BY SAME AGENCY


                                                             REGION
Planning Function
DOT - Transportation
CZM - Coastal Zone
HUD 701
AQMA - Air Quality
Solid Waste
Areawide Transportation
Corps of Engineers
Forest Service
Soil Conservation Service
A-95 Review
Other Federal
Other State
Other Local
1
15
9
17
3
16
17
2
-
12
16
17
16
17
2
7
6
10
3
4
6
1
-
-
9
-
-
-
3
6
3
9
3
5
4
-
-
-
9
-
-
-
4
21
9
26
4
12
25
4
5
1
20
8
5
1
5
18
5
25
4
13
17
6
5
5
6
11
11
5
6
1
-
8
-
3
7
1
-
1
-
5
5
_
7
3
-
4
2
4
3
3
-
-
3
5
1
4
8 9
11
-
13
8
2
5
1
3
-
13
8
13
11
16
6
-
7
2
3
8
3
1
3
2
10
10
10
Total
88
32
119
29
62
92
21
14
22
84
126
61
48

-------
                              TABLE IX



         NUMBER OF PLANNING FUNCTIONS PERFORMED BY AGENCY



                                 REGION
Function
Only 208
1 Other
2-5 Other
More than 5
No Answer
1 2
1
-
1
17 9
-
3
3
-
8
-
1
4
-
-
14
9
3
567
_
2
7
16 8 5
.
8 9
8
-
3
9
1 1
10
-
-
3
7
-
Total
12
2
36
80
6
Total
17   11    12   26   25
21
10
136
Total
                               TABLE X



                AMOUNT OF WATER RELATED EXPERIENCE



                                 REGION
Experience
Extensive
Some
None
No Answer
1
3
13
1
-
2
5
2
4
—
3
6
-
5
1
4
4
18
1
3
5
1
17
7
-
6
1
6
-
1
7
4
1
-
-
8 9
1
7
10
3 1
10
3
5
2
-
Total
28
69
30
9
17   11   12   26   25    8
21
 10
  136
                                 A-7

-------
I
00
Staffing

Full and Part-time
  professionals presently
  employed

Number non-professionals
  now on board (full and
  part-time)

Anticipated total
  professionals

Anticipated total
  non-professi ona1s

Borrowed - part-time
  or temporary
                                                       TABLE  XI

                                                   AGENCY  STAFFING

                                                           REGION
1 2
46 45
7
112 96
34
3
23
8
32
12
4
49
19
69
45
5
93
34
244
60
6
19
9
20
5
7
11
4
26
11
8 9
26 2
12
24
6
10
11
4
30
11
Total
325
97
653
184
                                  78
32     62     41    413     22
53     64
69
834

-------
       TABLE XII



DISCIPLINES OF DIRECTORS



            REGION
Disciplines
Planner
Sanitary Engineer
Public Administration
Biologist
Geologist
Water Planner
Environmental Planner
Public Relations
Civil Engineer
City Manager
Geographer
Legal
Economist
Chemical Engineer
1 2
9 1
3 6
3 1
1
1
1
1
-
-
-
-
-
-
-
34 5 6 7 8 9
5 11 11 - 44
4 4 - - - 3
331-4
1
------
11-8
1 2
1 - - - - 1
344--
1
1
1
1
1
10
1
3
3
-
-
2
1
-
-
-
-
-
-
-
Total
46
23
18
2
1
14
5
2
11
1
1
1
1
1

-------
          TABLE XIII
DIRECTORS HIRED IN 208 AGENCIES
No. of Directors Hired
No. of Directors to be
Hired
No Answer
Total

LENGTH OF STAFF
Was Staff Hired for
More than 2 Years?
Yes
No
No Answer
Total

12345
17 9 4 21 24
2851
-----
17 11 12 26 25
TABLE XIV
EMPLOYMENT DURING AND

12345

3 1 - 12 11
14 9 12 5 4
1 - 9 10
17 11 12 26 25
REGION
6
5
3
-
8

BEYOND
REGION
6

-
4
4
8

7 8 9 10
4916
18-4
4
5 21 1 10

PLANNING PERIOD

7 8 9 10

11-5
39-5
1 11 1 -
5 21 1 10

Total
100
32
4
136



Total

34
65
37
136
              A-10

-------
               TABLE XV
PHYSICAL LAY-OUT OF 208 AGENCY OFFICES
AGENCY
In One Office
Split Up in Different
Offices
No Answer
Total

LOCATION OF
With Parent Agency
Separate From
Parent Agency
No Answer
Total

1234
17 8 12 24
3-2
_
17 11 12 26
TABLE XVI
REGION
56789
25 7 4 17 1
........
114-
25 8 5 21 1


10 Total
9 124
1 6
6
10 136

208 AGENCIES IN RELATION TO PARENT AGENCY

1234
15 11 9 14
2-38
4
17 11 12 26
REGION
56789
25 8 4 14 1
7
1
25 8 5 21 1

10 Total
7 108
3 23
5
10 136
                  A-ll

-------
                                                TABLE XVII
                                 ANTICIPATED 208 MANAGEMENT AGENCIES
  New Agency

  208 Planning Agency

  Single Management Agency

  Several Management with
    Regional Authority

  Several Management with
    Local Autonomy

  No Answer
Will a constitutional amendment
  be necessary to create a new
  agency?

  Yes

  No

  No Answer
REGION
1 2 3
lent agency:
4
1
:y 111
i
1 4 4
i
855
7 1 1
TABLE
MANAGEMENT SYSTEMS REQUIRING
(ndment
a DPW
1 2 3
1
12 - 1
5 11 10
4

9
-
4
5
7
8
XVIII
567

2
_
- - -
1132
10 1
253

8
*
3
1
4
2
8
5

9 10 Total

1 19
1 1 4
11
6 38
4 48
9 - 41

A CONSTITUTIONAL AMENDMENT

4
2
6
18
REGION
567
2 1
13 - 1
10 7 4

8
-
1
20

9 10 Total
1 - 7
34
10 95

-------
                               TABLE XIX
          REGULATORY  METHODS  DESIRED IN A MANAGEMENT AGENCY*
                                        REGIONS
METHODS
Metering Waste
Water Flow
Differential Tax
Assessment
Zoning
Building, Housing
1 2
4

7

7
7
3
9

7

7
6
4
14

4

3
9
5
16

8

9
9
6
6

5

7
8
7
1

1

1

8
13

3

12
15
9
-

-

1
1
10
5

3

6
8
Total
68

38

53
63
  Codes & Subdivision
  Regulations
P.U.D.  and Density        43877-6-    5    40
  Bonuses
Transfer of               2-3   -3-2    --10
  Development Rights
Discharge Permits         2   21213    8   115    1    3    57
Don't Know           17       2   3   8    2   6   2    -    1    41
TOTAL                17  33  36  56  70   46  10  68    3    31    370
*Answers will not total 136 due to multiple responses to  question.
                                   A-13

-------
            TABLE XX
TECHNIQUES FOR PUBLIC PARTICIPATION


Publ ic Meeti ngs

Newsletters

Planning Brochure

Speeches

TV Coverage

Newspaper Coverage

Radio Coverage

SI ide Shows

Exhibits

Depositories



in-use
intended
i n-use
intended
in-use
intended
in-use
intended
in-use
intended
in-use
intended
in-use
intended
in-use
intended
in-use
intended
in-use
intended

1
9
17
3
15
5
16
8
17
2
15
12
17
5
14

12

9
_
14

2
6
7
2
7
2
4
6
8
4
6
5
9
4
8
1
7
.
6
2
7

3
4
4
5
3
2
5
4
4
3
3
5
4
4
4
1
3
.
3
1
2

4
10
21
14
17
2
8
9
19
9
18
17
19
10
15
2
15
1
14
2
8
Region
5
16
13
19
11
9
14
12
16
7
16
17
14
12
16
5
17
6
13
8
15

6
4
4
3
5
.
6
1
5
1
4
1
6
„_
2

7

2
.
2

7
2
5

5
_
4
1
5
2
3
2
5
2
4
1
4

4
.
3

8
8
11
4
7
2
5
6
6
2
9
9
10
6
9
2
8
2
6
2
6

9
1
3

1
.
2
1
2
—
1
1
2
1
1
1
1

1

1

10
9
7
7
6
3
6
8
6
5
6
9
8
7
7
6
8
6
3
3
3

Total
70
92
60
77
25
70
53
88
35
81
87
93
51
80
19
92
15
61
18
61

-------
                                              TABLE XXI

                           PERCENTAGE OF GRANT AWARD TO BE CONTRACTED OUT

                                                       REGION
Contractors

Architectural and
  Engineering

Environmental

Engi neeri ng/Planni ng

Planning

Legal

Management Program

Insti tuti onal/management/
  financial

Public participation

Water Quality Research
  and Analysis

University (non-profit)

     Total
1
48%

2 3
55%

4 5
59% 55%
TABLE XXII
TYPE OF CONTRACTORS: FOR 208

1
28
10
8
9
2
2
5
5
1
2
72
^^*— x
2 3
4
9
-
8
3
4
7
1
10
1
47
REG
4 5
6 8
10
5
4
-
3
14
2
11
2
54 11
6
62%

PLANNING
I 0 N
6
2
2
-
-
2
-
3
-
2
—
11
7
57%



7
6
1
2
2
2
1
2
-
3
_
19
8 9
67%



8 9
18
3
2
10
5
1
6
2
-
1
48
10
56%



10
7
1
5
4
3
1
9
1
2
1
34
Total
58%
National
Average



Total
79
36
22
37
17
12
46
11
29
7
296

-------
I
cn
      Federal Agencies
      State Agencies
      Counties
      Local Agencies
           Total
      Designated by Governor
      Designated by Self
           Total
                                                    TABLE XXIII
                                      NUMBER OF INTENDED GOVERNMENT CONTRACTS
                                                            REGION
1
6
5
-
3
14
234
1
3 1
3
_ _
7 1
5
-
-
5
8
13
6 7
1
1
1
6
9
8 9
1
6
13
1
21
10
4
4
8
1
17
Total
13
20
30
19
82
TABLE XXIV


1
15
2
17
METHOD OF DESIGNATION

234
10 10 28
2
10 12 28
OF 208
R E G I
5
25
-
25
AGENCIES
0 N
6 7
9 5
-
9 5


8 9
22 10
-
22 10


10
10
-
10


Total
144
4
148

-------
           TABLE XXV



PREPARATION OF GRANT APPLICATION



                REGION
PREPARATION BY:
Staff
Consultant
Joint
Other
Don't Know
Total

1
8
2
7
-
-
17

2
10
1
-
-
-
11

3
7
-
2
3
-
12

GRANT
4 5
21 19
1 1
4 5
-
-
26 25
TABLE
6
6
-
1
-
1
8
7
3
-
2
-
-
5
8 9 10
13 - 10
5 -
2 1
1
_
21 1 10
Total
97
10
24
4
1
136
XXVI
AGENCY PERCEPTION OF
APPLICATION REQUIREMENTS
REGION

Reasonable
Not Reasonable
Don't Know
Total
1
15
2
-
17
2
3
4
4
11
3
4
5
3
12
4 5
22 18
4 2
- 5
26 25
6
8
-
-
8
7
4
1
-
5
8 9 10
15 -
4 -
2 1 10
21 1 10
Total
89
22
25
136
                A-17

-------
             TABLE XXVII



AGENCIES THAT DID NOT RECEIVE HANDBOOKS



                          REGIONS
Designation Handbook: 1
Did Not Receive Handbook -
No answer
Work Plan Handbook
Did Not Receive Handbook -
No answer

2345678910 Total
- - - 1 4 1 6 - - 12
- 7 - 1 	 8
- - - 1 - 1 4 - - 6
- 7 - 1 - - - - 10 18
TABLE XXVI 1 1






AGENCIES THAT RECEIVED HANDBOOKS TOO LATE TO BE USEFUL

1 2
Designation Handbook 11 3
Work Plan Handbook 7 3

AGENCIES

1 2
Designation Handbook 11
Work Plan Handbook 10 -
REGIONS
3456789 10
- 14 13 8 - 6 1 5
- 10 13 4 1 5 1 1
TABLE XXIX
THAT DID NOT USE HANDBOOKS
REGIONS
3456789 10
- 14 8 4 1 5 1 4
- 10 11 1 2 3 1 2

Total
61
45



Total
48
40
                  A-18

-------
                    TABLE. XXX

AGENCIES THAT WERE AWARE OF THE 208 BULLETIN
        DURING DESIGNATION PROCESS
REGION
1 2
Yes 15 4
No 24
No answer - 3
Total 17 11


Useful
Not Useful
Insufficient Detail
Too Detailed
Sufficient Detail
Sensitive to Local
Situation
Insensitive to
Local Situation
Neutral
No answer
345678
5 12 8 2 33
2 12 16 5 2 16
5211-2
12 26 25 8 5 21
TABLE XXXI
AGENCY EVALUATION OF HANDBOOKS
208 Draft Designation
Guidelines Handbook
101 62
4 1
24 6
12 1
22 14
20 " 14

20 11

10 4
6 10
9 10 Total
6 58
4 63
1 - 15
1 10 136


Work Plan
Handbook
66
7
16
4
15
16

12

3
7
                         A-19

-------
                                     APPENDIX B
                             PLANNING AGENCY DIRECTORY
As of July 1, 1975 the following one hundred and forty nine  (149) areas
and aqency designations have been approved by  the Administrator,
Environmental Protection Agency
Region and Area
Designation Date
 (Grant Amount)   Agency
                              Contact
Region I
Portland, Me.
Southern Maine
Northern  Maine
  6-25-74
 (770,000)
  7-26-74
 (488,000)
  8-5-74
 (207,900)
 Lewiston-Auburn,  Me. 12-19-74
                     (339,100)
 Augusta-Cobbosse,
   Maine
 Berkshire County
 Pittsfield, Mass.
 Cape Cod, Mass.
  12-19-74
  (380,000)
  2-19-75
  (374,000)
  2-27-75
  (350,000)
Greater Portland
Council of Governments
169A Ocean Street
Portland, Maine 04106

Southern Waine Regional
Planning Commission
York County Courthouse
Alfred, Maine  04002

Northern Maine Regional
Planning Commission
McElwaine House
2 Maine Street
Caribou, Maine 04736

Androscoggin Valley
Regional Planning Comm.
34 Court Street
Auburn, Maine 04210

Southern Kennebec Regional
Planning Commission
154  State Street
Augusta, Maine 04330

Berkshire County Regional
Planning Commission
10 Fern"Street
Pittsfield,  Mass.  01201

Cape Cod Planning  &
Economic Development  Comm.
First District Courthouse
Barnstable,  Mass.  02630
Mr. Frederick Sheenan,
(207) 799-8523
 Mr. Brian Chernack
(207) 324-2952
 Mr. James Barresi
(207) 498-87J6
                                            Mr. Craig Ten Broeck
                                            (207) 784-0151
 Mr. John Forster
 (207)  622-7146
 Mr. Gaylord Burke
 (413)  442-1521
 Dr. William Stanburg
 (617)  362-2511
  Ext 477
                                      B-l

-------
Region and Area
Designation Date
 fGrant Amount)  Agency
                                                               Contact
Martha's Vineyard,  2-27-75
Massachusetts      (216,000)
Lowell, Mass.
Brockton, Mass.
Boston, Mass.
Salem, N.H.
  3-4-75
 (456,840)
  3-6-75
 (650,000)
  4-18-75
(2,292,000)
  4-1-75
 (270,300)
Worcester, Mass.    4-11-75
                  (1,035,000)
Fitchburg, Mass.    4-17-75
                   (377,000)
Southeastern, Mass. 5-20-75
                   (1,132,000)
Lakes Region, N.H.  6-3-75
                   (533,000)
 Martha's Vineyard Land  &
 Water Commission
 Box 1447
 Oak Bluffs, Mass. 02557

 Northern Middlesex
 Area Commission
 144 Merrimac Street
 Lowell, Mass. 01852

 Old Colony Planning Council
 232 Main Street
 Brockton, Mass. 02401

 Metropolitan Area
 Planning Council
 44 School Street
 Boston, Mass. 02108

 Southern-Rock inahajn
 Regional Planning
 District Commission
 19 Main Street
 Salem, NH  03709

 Central Massachusetts
 Regional Planning Comm.
 70 Elm Street
 Worcester, Mass. 01609

 Montachusett Reaional
 Planning Commission
 150 Main Street
 Fitchburg, Mass. 01420

Southeastern Regional
Planning and Economic
Development District
7 Barnadas Road
Marion, Mass  02738

Lakes Region Planning
Commission
Humiston Building
Box 302
Meredith, New Hampshire
03253
                                            Bill Wiocox
                                            (617) 693-3453
Mr. Michael diGiano
(617) 454-8021
Mr. Robert MacMahan
(617) 583-1833
Mr. John Harrington
'617) 523-2454
Mr. John Gilmore
(603) 893-8233
                                            Mr. James M. Arnold
                                            (617) 756-7717
                                            Mr. David Weir
                                            (617) 345-7376
                                            Mr. Alex Zaleski
                                            (617) 748-2100
                                            Mr. David G. Scott
                                            (603) 279-6550
                                    B-2

-------
Region and Area
Designation Date
  (Grant Amount)	Agency
                                Contact
Providence, RI      6-23-75
                  (2,300,000)
Region II

Puerto Rico
  4-17-75
(1,396,000)
Nassau-Suffolk      4-24-75
Counties, Long    (5,207,000)
Island, N.Y.
Mercer Co., N.J.    5-12-75
                   (974,145)
Camden, N.J.
  5-14-75
(1,264,800)
 .-Wlesex Co., N.J.5-14-75
                  (1,420,000)
Westchester, N.Y.  6-3-75
                  (1,080,000)
   .e-Niagara, N.Y. 6-3-75
                  (1,825,000)
               Rhode Island Statewide
               Planning Program
               265 Melrose Street
               Providence, RI 02907
 Commission for the Devel-
 opment and Administration of
 of Areawide Waste Treatment
 Plans for the North Metro-
 politan Area.-Puerto Rico
 Environmental Quality Board
 P.O. Box 11488
 Santurce, Puerto Rico 00910

 Nassau-Suffolk Regional
 Planning Board
 Planning Building
 Suffolk County Center
 Veterans Memorial Highway
 Hauppauge, Long Island, NY

Delaware Valley Regional
Planning Commission
Perm Towers Building
1819 John F. Kennedy Blvd.
Philadelphia, Penn. 19103

Delaware Valley Regional
Planning Commission
Penn Towers Building
1819 John F. Kennedy Blvd.
Philadelphia, Penn.  19103

Board of Chosen Freeholders
of Middlesex County
Kennedy Square
40 Livingston Avenue
New Brunswick, N.J. 08901

Westchester County Government
Environmental Coordinating
Agency-Environmental Advisory
Council
c/o Westchester County
Planning Department
910 County Office Building
White Plains, New York 10601

Erie-Niagara Regional
Planning Board
2085 Baseline Road
Grand Island, N.Y.  14072
                               Patrick J. Fingliss
                               (401) 277-2656
Mr. Carlos M. Jiemenez
      Barber
(809) 725-5140
                                             Dr. Lee E. Koppleman
                                             (516) 979-2922
                                           11787

                                             Mr. John Coscia
                                             (215) 567-3000
Mr. John Coscia
(215) 567-3000
                                             Mr. Douglas S. Powell
                                             (201) 246-6062
                                             Mr. Peter Q. Eschweiler,
                                             (914) 682-2498
                                             Mr. Leo J. Nowak, Jr.
                                             (716) 773-7611
                                       B-3

-------
Region and Area
Designation Date
 (Grant Amount)     Agency
                                                                Contact
Ocean Co. N.J.
    6-3-75
    (503,200)
New York City, N.Y.    6-5-75
                     (8,111,533)
Southern Tier Central  6-5-75
(Corning) N.Y.        (808,000)
Central New York       G-5-75
(Syracuse) N.Y.      (1,271,000)
 Ocean County Board  of
 Chosen Freeholders
 Court House Square
 Toms River, N.J.  08753

 New York City Environ-
 mental Protection
 Administration
 Municipal Bldg.,  Rm 2455
 New York, New York  10007

 Southern Tier Central
 Regional Planning and
 Development Board
 53 1/2 Bridge Street
 Corning, New York 14830

 Central New York  Regional
 Planning and Development
 Board
 321 East Water Street
 Syracuse, N.Y. 13202
Region III

New Castle County,     6-12-74
Delaware             (1,200,000)
Hampton Roads, Va.     6-25-74
                     (1,600,000)
Roanoke, Va.
Richmond, Va.
    6-25-74
    (843,050)
    6-25-74
   (1,300,000)
New Castle County
Areawide Waste Treatment
Management Planning Agency
1 Peddler's Village
Newark, Delaware 19711

Hampton Roads Water
Quality Agency
Pembroke 3 Office Building
Suite 131
Virginia Beach, Va. 23462

5th Planning District
Commission
P.O. Box 2527
145 West Campbell Ave.
Roanoke, Va. 24010

Crater Planning District
Commission
2825 Crater Road South
P.O. Box 1808
Petersburg, VA  23803
Mr. Thomas A. Thomas
(201) 244-2121
                                            Mr. Norman  Nash
                                             (212)  556-3641
                                            Mr. William  D.  Hess
                                            (607)  962-5092
                                            Mr. Robert C. Morris
                                            (315) 422-8276
                                            Mrs. Merna Hurd
                                            (302) 731-7670
                                            Mr. Paul Fisher
                                            (804) 499-5531
                                                              Mr. F.  Ray  Bailey
                                                               (703)  343-4417
                                                              Mr. Jerry  Simmonoff
                                                              (804)  861-1666
                                       B-4

-------
Region and Area
Designation Date
 (Grant Amount)     Agency
                               Contact
Fredericksburg, Va.
Sussex County, Del.
Southwest Virginia
Washington, D.C.
Baltimore, MD
Charlestown, WV
Pittsburgh, PA
Philadelphia,  PA
   1-7-75    Rappahannock Area Develop-
  (350,000)   ment Commission (RADCO)
             913 Charles Street
             P.O. Box 863
             Fredericksburg, Va. 22401

   1-30-75   Sussex County Council
  (633,089)   P.O. Box 507
             Georgetown, Del. 19947

   1-30-75   Cumberland Plateau-
  (649,920)   Lenowisco 208 Planning
             Agency-Southwest Virginia
             U.S. Highway 58-421W
             Duffield, Va. 24244

   3-27-75   Metropolitan Washington
 (3,550,000)  Council of Governments
             1225 Connecticut Ave., NW
             Washington, D.C. 20036

   6-6-75    Regional Planning Council
 (1,187,527)  701 St. Paul Street
             Baltimore, Maryland 21202

   6-6-75    B-C-K-P Regional Inter-
  (801,000)   Governmental Council
             410 Kanawha Blvd. East
             Charlestown, W.V. 25301

   6-23-75   Southwestern Penn. Regional
 (1,511,432)  Planning Commission
             564 Forbes Avenue
             Pittsburgh, PA 15219

  .fi-18-75   Delaware Valley R.P.C.
 (3,852,032)  Penn Towers Bldg.
             1819 J.F. Kennedy Blvd.
             Philadelphia, PA  19103
                              Mr. Ronald Rebman
                              (703) 373-2690
                              Mr. Roger Truitt
                              (302) 856-7701 x216
                              Mr. Paul E. Trammel
                              (703) 431-2206
                              Mr.  Charles Spooner
                              (202) 223-6800
                              Mr. Tom Smith
                              (301) 383- 5840
                              Mr. Mike Russel
                              (304) 348-7190
                              Mr. James DeAanelis
                              (412) 391-4120
                              Mr. John Cpscia
                              (215) 567-3000
Region IV

Raleigh-Durham,
North Carolina
   4-9-74
  (947,500)
Triangle J. Council of
Governments
P.O. Box 12276
Research Triangle Park,
North Carolina 27709
Mr. Frank Chamberlain
(919) 549-0551
                                        B-5

-------
Region and Area
Designation Date
 (Grant Amount)     Agency
                                                               Contact
Memphis, Tenn.
Knoxville, Tenn.
Chattanooga, Tenn.
Nashville, Tenn.
  6-25-74    Miss-Tenn-Ark COG
 (1,187,000)  Memphis Delta Development
             District Commission
             125 North Main Street
             Room 518
             Memphis, Tenn. 38103

  6-28-74    Knoxville-Knox County
  (670,000)   Metro Planning Commission
             301 Locust Street
             Knoxville, Tenn. 37902

  10-10-74   Chattanooga Area Regional
  (949,000)   Council of Governments
             413 James Building
             735 Broad Street
             Chattanooga, Tenn. 37402

  11-11-74   Mid-Cumberland Council of
  (868,700)   Gov'ts/Development District
             Suite 801
             226 Capitol Boulevard
             Nashville, Tenn. 37219
Mr. Hugh Teaford
(901) 362-1883
Birmingham, Ala.     3-25-75
                   (1,250,000)
             Birmingham Regional
             Planning Commission
             21 Office Plaza South
             2112 llth Ave., South
             Birmingham, Ala.  35205
Tuscaloosa, Ala.
Columbia, S.C.
Louisville, Ky.
  3-25-75    West Alabama Planning &
 (601,000)    Development Council
             P.O. Box 86
             Tuscaloosa, Ala.  35401

  3-25-75    Central Midland Regional
 (736,250)    Planning Council
             Dutch Plaza, Suite 55
             800 Dutch Square  Blvd.
             Columbia, S.C. 29210

  4-2-75     Kentuckiana Regional
 (837,000)    Planning & Development
             Agency
             208 South Fifth Street
             Louisville, Kentucky 40202
Mr. Don Parnell
(615) 637-4663
Mr. Gordon Mellancamp
(615) 266-5781
Mr. Phil Armor
(615) 244-1212
Mr. Doug Haddock
(205) 325-3897
                                                              Ms. Nancy Landgraf
                                                               (205)  345-5545
                                                              Mr. Mike McAnnelly
                                                               (803)  798-1243
Mr. Larry Cox
(502) 581-6096
                                       B-6

-------
Region and Area
                 Designation Date
                   (Grant Amount)
        Agency
                                            Contact
Orlando, Pla.
Volusia, Fla.
Breyard County,
Florida
Bay County
(Panama City), Fla.
Palm Beach, Fla.
Greenville, S.C.
Pensacola, FL
Sarasota-Ft. Myers
Florida
Mobile, Alabama
 3-27-75
 (909,400)
 4-22-75
 (730,000)
 4-24-75
 (736,000)
  4-30-75
 (538,000)
  1-10-75
 (984,000)
  5-9-75
(1,139,520)
  5-14-75
 (848,000)
  s-ifi-75
 (949,000)
                    (1,143,000)
East Central Florida
Regional Planning Council
1011 Wymore Road, Suite 105
Winter Park, Fla. 32789

Volusia County Planning and
Development Department
125 E. Orange Avenue
County Courthouse Annex
Daytona Beach, Fla. 32014

Brevard County Planning
& Zoning Department
2575 N. Courtenay Parkway
Merritt Island, Fla. 32952

Northwest Florida Planning
& Development Council
5321 'B1 W. Highway 98
Panama City, Fla. 32401

Area Planning Board of
Palm Beach County
P.O. Box 3643
West Palm Beach, Fla. 33402

South Carolina Appalachian
Council of Governments
211 Century Drive
Greenville, S.C. 29606
     Florida Regional
Planning Council
P.O. Box 486
Pensacola, Florida 32593

Southwest Florida Regional
Planning Council
2121 West First Street
Ft. Myers, Florida 33901

South Alabama Regional
Planning Commission
250 N. Water Street
P.O. Box 1665
Mobile, Alabama 36601
Mr. Arron Dowling
 (305)  645-3339
Mr. Don Sikorski
(904)  255-0111
Mr. John W. Hannah
(305)  452-9480
Mr. Charles Shih
 (904) 785-9581
Mr. Richard Stalker
(305) 683-9450
Mr. F.J. Forbes
(803) 242-9733
Mr. Dwaine Raynor
 (904) 434-1026
Mr. Larry Pearson
 (813)  334-7382
                                           Mr.  Don Pruitt
                                           (205) 433-6541
                                       B-7

-------
Region and Area
Designation Date
 (Grant Amount)	Agency
                                                               Contact
Broward Co. FL
Tanpa Bay, FL
                                             Mr.  Walter Keller
                                             (305)  765-5535
 5-23-75     Broward County Area
(863,000)    Planning Board
            1600 S.E. 10th Terrace
            Fort Lauderdale, Fla.
            33316
    5-27-75    Tampa Bay Regional  Planning   Mr.  Ron Armstronq
  (1,500,000)   Council                       (813)  821-2811
               3151 Third Avenue North
               Suite 540
               St. Petersburg, Fla.  33713
Dade Co., FL
Tallahassee, FL
Beaufort, S.C.
Polk Co.
Charleston, S.C.
Waccamaw, S.C.
    5-30-75
  (1,077,000)
    5-30-75
   (510,000)
    6-3-75
   (680,000)
Kingsoort-Bristol,    6-5-75
TN                   (903,000)
                      6-6-75
                     (759,000)
    6-6-75
  (1,000,000)
                      6-6-75
                     (650,000)
            Dade Cou ty
            Planning Department
            909 S.E. 1st Avenue
            Miami, Florida 33131

            Tallahassee-Leon County
            Planning Department
            P.O. Box 533
            Tallahassee, Florida 32302
Mr. Ed Cahill
(305) 358-1400
Mr. -Tom Pierce
(904) 488-6133
            Lowcountry Reqional Planning Mr. Charles Baggs
            Council                       (803) 589-2751
            P.O.  Box 98
            Yemassee, South Carolina
            29945
            First Tennessee-Virginia
            Development District
            1110 Seminole Drive
            P.O. Box 2779
            E.T.S.U.
            Johnson City, TN 37601

            Central Florida Reqional
            Planning Council
            P.O. Box 2089
            Bartow, Florida 33830

            Berkeley, Charleston,
            Dorchester Regional
            Planning Council
            No. 2 Courthouse So.
            County Office Bldg.
            Charleston, S.C. 29401

            Waccamaw Regional Planning
            Council
            P.O. Box 419
            Georgetown, S.C. 29440
                                             Mr.  Bob Purcell
                                             (615)  928-0224
                                             Mr.  Barry Chefer
                                             (813)  533-4146
                                                              Mr. Ken  Fujishiro
                                                              (803)  577-7800
                                             Mr.  Bob Barker
                                             (803)  546-8502
                                        B-8

-------
 Region and Area
Designation Date
 (Grant Amount)    Agency
Contact
 Asheville, N.C.
Region V

Cincinnati, Ohio




Toledo, Ohio
Dayton, Ohio
Youngstown, Ohio
Southeastern
Wisconsin
Detroit, Michigan
East St. Louis, II
Lake & Porter
Counties, IN
   6-23-75   Land-of-the-Sky-Reqional
  (481,000)   Council
             755 Merriman Avenue
             P.O.  Box  2175
             Asheville,  N.C.  28802
   6-12-74    Ohio-Kentucky-Indiana
 (1,913,000)  Regional  Council of Gov'ts
              426  East  4th  Street
              Cincinnati, Ohio   45202

   6-25-74      oledo Metropolitan Area
 (1,175,000)  Council of Governments
              420  Madison Avenue
              Suite 725
              Toledo, Ohio   43604

   6-25-74    Miami Valley  Regional
 (1,500,000)  Planning  Commission
              33 West First Street
              Dayton, Ohio   45402

   6-28-74    Eastgate  Development &
  (950,000)   Transportation Agency
              1616 Covington Street
              Youngstown, Ohio   44510

   12-26-74   Southeastern  Wisconsin
  (2,607,000) Planning  Comm.  (SEWRPC)
              916  S.E.  Avenue
              Waukesha, Wisconsin  53186

   5-20-75    Southeast Michigan Council
 (5,056,000)  of Governments
              1249 Washington, Blvd.
              Detroit,  Michigan  48226

   5-20-75    Southeastern  Illinois
 (1,105,000)  Metropolitan  and Regional
              Planning  Commission
              203  West  Main Street
              Collinsville, II 62234

   5-20-75    Northwestern  Indiana
  (985,000)   Regional  Planning  Comm.
              8149 Kennedy  Avenue
              Highland, Indiana   46322
Mr. Dennie Martin
(704) .254-8131
   Mr. Dory Montazemi
    513-621-7060
   Mr. Hintz Russelman
    419-241-9155
   Mr. Roger Riga
    513-223-6323
   Mr. Bill Fergus
    216-746-4665
   Mr. Bill McElwee
    414-547-6721
   Mr. Don Lamb
    313-961-4266
   Mr. Bill Ellman
    618-344-4250
   Mr. Ken Cypte
    219-923-1060
                                       B-9

-------
Region and Area
Designation Date
 (Grant Amount)	Agency
                                                                  Contact
Dane County.  WI
South Bend,  IN
Canton-Akron,  OH
Kalamazoo,  MI
Cleveland,  OH
Flint, MI
Muncie, IN
Jackson,  MI
    5-22-75    Dane County Regional
   (598,000)    Planning Commission
               Room 312
               City-County Building
               Madison, Wisconsin 53709

    5-23-75    Michiana Area Council
   (862,000)    of Governments
               llth Floor
               City-County Building
               South Bend, Indiana 46601

    5-23-75    Northeast Ohio Four County
   (973,000)    Planning and Development
               Organization
               19 North High Street
               Akron, Ohio 44308

    5-27-75    South Central Michigan
   (810,000)    Planning & Development Comm.
               Conference Center,
               Connors Hall
               Nazareth College
               Nazareth, Michigan 49074

    5-27-75    Northeast Ohio Areawide
  (3,209,000)   Coordinating Agency
               439 The Arcade
               Cleveland, Ohio 44114

    5-27-75    Gennessee, Lapeer, and
   (848,000)    Shiwwassee Counties
               Region V Planning and
               Development Commission
               801 South Saginaw
               Flint, Michigan 48502

    5-27-75    Region 6 Planning and
   (669,000)    Development Commission
               207 North Talley
               Muncie, Indiana 47303

   5-27-75     Region II Planning Comm.
   (566,000)    Jackson County Building
               312 S. Jackson Street
               Jackson, Michigan 49201
 Mr. Charles Montemayor
 608-266-4137
Mr. George L. Kruse, Jr.
 219-287-1829
Mr. Robert Strantton
 216-535-2644
Mr. Walt Forbes
 616-343-1676
Mr. Tony Ma
 216-241-2414
Mr. Thomas Haga,
 313-766-8865
                                                               Mr.  Dave Schoen

                                                                317-285-6252
                                                               Mr.  Charles Mancherian
                                                                517-787-3800
                                                                ext.  256
                                       B-10

-------
Region and Area
Designation Date
 (Grant Amount)    Agency
                                  Contact
Indianapolis, IN
Chicago, IL
Bay City, MI
Muskegon, MI
Grand Rapids, MI
Tri-County, MI
Green Bay, WI
Terre Haute, IN
Southern Illinois
   5-30-75
 (1,301,000)
   5-30-75
 (7,343,000)
   6-3-75
 (1,040,000)
   6-6-75
  (620,000)
   6-6-75
 (1,012,000)
   6-6-75
  (704,000)
   6-6-75
  (772,000)
   6-6-75
  (477,000)
   6-23-75
 (1,200,000)
Indiana Heartland Coordi-
nating Commission
Suite 217
7202 N. Shadeland Avenue
Indianapolis, IN 46250

Northeastern Illinois
Planning Commission (NIPC)
10 South Riverside Plaza
Chicago, Illinois 60606

East Central Michigan
Regional Planning and
Development Commission
1003 Woodside Avenue
Essexville, Michigan 48732

West Michigan Shoreline
Regional Development Comm.
Torrent House
315 W. Webster Avenue
Muskegon, Michigan 49440

West Michigan Regional
Planning Commission
1204 People's Building
60 Monroe at lona
Grand Rapids, MI 49502

Tri-County Regional
Planning Commission
2722 E. Michigan Avenue
P.O. Box 2066
Lansing, Michigan 48912

Fox Valley Water Quality
Planning Agency
1919 North Lake Street
Neenah, Wisconsin 54956
Mr. Michael Robling
 317-849-4629
Mr. Robert DuCharme
 312-454-0400
Mr. David Gay
 517-893-5561
Mr. Pat Tyson
 616-722-7878
Mr. Robert Stockman
 616-454-9375
Mr. Michael Scieszka
 517-487-9424
Mr. Nathiel Malcoze
 414-739-6156
West Central Indiana          Mr. Charles Staats
Economic Development District  812-238-1561
P.O. Box 627
700 Wabash Avenue
Terre Haute, IN  47808
Greater Egypt Regional
Planning & Development Comm.
P.O. Box 3160
608 East College
Carbondale,  Illinois 62901
Mr. Franklin Moreno
 618-549-3306
                                       B-ll

-------
 Region and Area
Designation Date
 (Grant Amount)	Agency
                              Contact
 Region VI

 Tulsa, Oklahoma
Oklahoma City, OK
 Dallas/Ft. Worth,
 Texas
Beaumont-Port
Arthur, Texas
Houston, Texas
San Antonio, TX
Corpus Christi, TX
Lower Pio Grande,
Texas
Texarkana,  TX
  9-18-74
(1,210,000)
  10-25-74
(1,500,000)
  4-17-75
(2,321,620)
  4-18-75
 (843,000)
  4-22-75
(1,798,300)
  5-16-75
(1,162,112)
  6-6-75
 (643,500)
  6-6-75
 (775,000)
                      fi-23-75
                     (350,000)
 Indian  Nations Council
 of  Governments
 630 West Seventh Street
 Tulsa,  Oklahoma 74127
 Mr.  Umesh Mathur
 (918)  587-3178
Association  of Central       Mr. Bob Fritz
Oklahoma  Governments         (405)  848-8961
4801 Classen Blvd,  Suite 200
Oklahoma  City,  OK  73118
 North Central  Texas
 Council  of  Governments
 P.O. Box 5888
 Arlinaton,  Texas  76011

 Southeast Texas Regional
 Planning Commission
 3800 Hiqhway 365
 Port Arthur, Texas   77640

 Houston-Ga]veston Area
 Council
 3701 West Alabama
 Houston, Texas 77027

 Alamo Area  Council of
 Governments
 400 Three America's Bldq.
 San Antonio, Texas 78205

 Coastal  Bend Council
 of Governments
 International Airport
 Corpus Christi, TX 78410

 Lower Rio Grande Valley
 Development Council
 First National Bank Bldg.
 Suite 207
McAHen, Texas 78501

Ark-Tex Council of Govts.
 P.O. Box 5307
Texarkana, TX 75501
 Mr.  Herman Veselka
 (817) 261-3331
Mr. Don Kelly
(713) 727-2384
                                                               Mr. Nick Aschliman
                                                               (713)  627-3200
                                                              Mr. Al  Notzon
                                                              (512) 255-5201
                                                              Mr. Robert  Weaver
                                                              (512)  884-3911
Mr. Richard Montedeoca
(512)  682-348]
                                          Mr.  Frank Goerke
                                          (214)  794-3481
                                       B-12

-------
                  Designation Date
Region and Area     fGrnnt »mnimt)	Agency
                                               Contact
Region VII

Des Moinee, Iowa     6-10-74
                    (1,385,000)
St. Louis, MO
Centerville, Iowa
Joplin, MO
  5-23-75
(2,243,000)
  5-23-75
 (325,000)
  6-6-75
 (429,500)
Kansas City, KS      6-13-75
                    (1,400,000)
Central Iowa Regional
Association of Governments
P.O. Box 3326
Des Moines, Iowa 50316

East-West Gateway
Coordinating Council
720 Olive Street
Suite 2110
St. Louis, MO 63101

Chariton Valley Regional
Services Agency
P.O. Box 591
Centerville, Iowa 52544

Ozark Gateway Regional
Planning Commission
303 E. Third Street
P.O. Box 1355
Joplin, MO 64801

Mid-America Regional
Council, Third Floor
20 West 9th Street
Kansas City, MO 64105
                                             Dale Harrington
                                             515-244-3257
                                                               Mr. Larry Zensinger
                                                               314-421-4220
                                                                Mr. Charles McCarty
                                                                515-856-2114
Mr. Peter Smith
417-781-3220
                                             Mr.  Tom Neal
                                             816-221-0993
                                        B-13

-------
Reaion and Area
Designation Date
 (Grant Amount)	Agency
                                                              Contact
Region VIII

Colorado Springs
     6-26-74  Pikes  Peak Area Council
    (955,000)  of Governments
              27 East Vermigo
              Colorado Springs, Col.
              80903
Mr. Roland Gow
(303) 471-7030
Pueblo County, Col.
Denver, Col.
Provo, Utah
Uintah, Utah
Salt Lake County,
Utah
Middle Yellowstone,
Montana
Flathead & Lake
Counties, Montana
     9  18-74  Pueblo Area Council  of
    (485,000)  Governments
              1 City Hall Place
              Pueblo, Col. 81003

     10-8-74  Denver Regional Council
   (1,290,000) of Governments
              1776 S. Jackson Street
              Denver, Col. 80210

     1-1-75    Mountain Association
    (670,000)  of Governments
              160 East Center Street
              Provo, Utah 84601

     1-10-75  Uintah Basin Association
    (380,000)  of Governments
              P.O. Box 867
              26 W. 200 North
              Roosevelt, Utah 84066

     3-6-75    Salt Lake County
   (1,046,000) Council of Cover men ts
              2500 S. State Street
              Salt Lake City, Utah S4115

     4-1-75    Middle Yellowstone Areawide
    (735,000)  Planning Oroanization
              3300 2nd Avenue North
              Suite 200
              Billings, Montana

     4-2-75    Flathead Drainage
    (495,000)  208 Project
              P.O. Box 100
              Kalispell, Montana 59901
Mr. Gene Fisher
(303)543-6006
Mr. Michael Smith
(303) 758-5166
Mr. George Scott
(301) 373-5510
Mr. Clinton Harrison
(301) 722-4518
Dr. David Eckhoff
(801) 328-7461
Mr. Allen Bond
(406) 245-6619
Mr. Dave Nunnallee
(406)  755-5521
                                        B-14

-------
Region and Area
Designation Date
 fQrant Amount)	Agency
                                                               Contact
Region VIII

Ogden, Utah             4-2-75   Weber  River Water
(Weber-Davis Counties) (827,000) Quality Planning Council
                                 714  Municipal  Building
                                 Ogden,  Utah 84401
Powder River, WX
Southeast, Utah
Yellowstone-Tongue
Montana
Rifle, Colorado
(Mesa/Rio Blanco)
     4-4-75    Powder  River  Areawide
    (415,000)  Planning Organization
               Box 204
               Buffalo, WY 82834

     4-17-75   Southeastern  Utah
    (380,000)  Association of Govts.
               143 So.  Main  Street
               Helper,  Utah

     4-8-75    Yellowstone-Tongue
    (540,000)  Areawide Planning
               Organization
               Powder  River  County
               Courthouse
               Breadus, Montana 59317

     4-24-75   Colorado West Area
    (362,000)  P.O. Box 351
               Rifle,  Col. 81650
                                            Mr.  Mike Minor
                                            (801)  399-8401
Mr. Rich Douglass
(307) 684-7648
Dr. Courtney Brewer
(801) 472-3403
Mr. Floyd Irion
(406) 436-2483
 Mr. Joel Webster
 (303) 625-1723
Green River, WY
Five Counties, Utah
Northwest, Col.
Larimer-WeId, Col.
     5-14-75   Southwestern Wyoming
     (450,000)  Water Quality Planning
               Association
               Lincoln County Courthouse
               Kemmerer,  WY.

     5-14-75   Five County Association
     (380,000)  of Governments
               P.O. Box 261
               Cedar City, Utah 84720

     5-14-75   Northwest Colorado
     (530,000)  Council of Govts.
               P.O. Box 737
               Frisco, Col. 80443

     5-14-75   Larimer-Weld Council
     (590,000)  of Governments
               201 East 4th Street
               Room 201
               Loveland, Col. 80537
 Mr. Glenn Payne
(307) 789-3897
Mr. Neal Christensen
(801) 586-4842
Mr. Lee Woolsey
(303) 468-5445
Mr. Dick MacRavey
(303) 667-3288
                                         B-15

-------
Region and Area
Designation Date
 (Grant Amount)	Agency
 Contact
Black Hills, SD
Lewis & Clark, ND
Sioux Falls, SD
Jackson Hole, WY
Gallatin,  MT
  5-16-75   Sixth District Council
 (375,000)   of Local Governments
            P.O. Box 1568
            Paoid City, SD 57701

  5-22-75   Lewis & Clark Resource
 (400,000)   Planning & Development
            Council
            Box 236
            Mandan, ND 58554

  5-27-75   South Eastern Council
 (375,000)   of Governments
            ™8 E. 13th Street
            .sioux Falls, SD 57105

  6-4-75    Teton County-Section 208
 (370,000)   Planning Agency
            P.O. Box 1727
            Jackson, WY 83001

  6-5-75    Gallatin County Commission
 '475,000)   Gallatin County Courthouse
            Bozeman, MT 59715
 Mr. Larry Finnerty
 (605)  342-8241
 Mr.  Robert O'Shea
 (701)  663-6587
Mr. John Norton
 (605)  336-1297
Mr. William Ashley
 (307)  733-4430
Mr. Walter Sales
(406)  587-7316
                                         B-16

-------
Reqion and Area
Designation Date
 (Grant Amount-)	Agency
                                        Contact
Reqion IX

Lake Tahoe
Interstate
Reno, NV
Carson City, NV
Tucson, AR
Ventura, CA
 8-5-74
(702,000)
 6-6-75
(372,530)
 6-6-75
(140,510)
 6-6-75
(962,230)
 6-13-75
(928,000)
Clark Co., NV
Monterey,  CA
San Diego,  CA
              Tahoe Regional Planning
              Agency
              P.O. Box 8896
              So. Lake Tahoe
              California 94705

              Washoe Council of Govts.
              417 Forest Street
              Reno, Nevada 89502

              Carson River Basin
              Council of Governments
              P.O. Box 1927
              Carson City, NV 89701

              Pima Association of
              Governments
              405 Transamerica Bldg.
              Tucson, Arizona 85701

              Ventura Regional County
              Sanitation District
              P.O. Box AB
              181 So. Ash Street
              Ventura, CA 93001

              Clark County Soard of
              County Commissioners
              Clark County Courthouse
              200 East Carson Avenue
              Las Vegas, Nevada  89101

              Association of Monterey
              Bay Area Governments
              AMBAG
              1011 Cass Street
              P.O. Box 190
              Monterey, CA 93940
    fi_lp_75   Coirprehensive Planning
   (1,339,280) Organization of San Diego
              County
              Suite  524
              Security Pacific Plaza
              1200  3rd Avenue
              San Diego,  CA 92101
                       (773,880)
 6-18-75
(829,500)
Mr.  James Jordan
(916) 541-0246
Mr. Frank Freeman
(702) 329-6314
Mr. Robert Sullivan
(702) 885-4680
Mr. Paul Mackey
(602) 792-1093*
Mr. John A. Lambie
(805) 648-2717
                                        Mr. Jack Petitti
                                        (702) 451-1066
Mr. William Hood, Jr.
(408)  373-8477
                                        Mr. Richard J. Huff
                                         (714) 233-5211
                                       B-17

-------
 Reaion  and Area
                   Designation Date
                  Agency
 Contact
 San  Francisco, CA




 Guam




 Region  X

 Portland, Oregon




 Salem,  Oreqon
Eugene, Springfield,
Oregon
  6-18-75   Association of  Bay  Area
(4,302,890)  Governments
            Claremont Hotel
            Berkeley, CA  94705

  6-18-75   Guam Environmental
 (286,180)   Protection Agency
            P.O. Box 2999
            Agana, Guam 96910
  11-18-74   Columbia Region Assoc.
(1,110,000)  of Governments
            527 S.W. Hall
            Portland, Oregon 97221

  11-18-74   Mid-Willamette Valley
 (446,400)   Council of Governments
            Civic Center, Rm 305
            Salem, Oregon 97301

  11-18-74   Lane Council of Govts.
 (670,400)   135 6th Avenue East
            Eugene, Oregon 97401
Pocatello, Idaho       3-25-75
(Bannock/Cariboo County)
                      (425,000)
            Southeast Idaho
            Council of Governments
            209 E.  Louis
            Box 4169
            Pocatello, Idaho 83201
Ada/Canyon County,
Idaho
Clark County,
Washington
Seattle,  Washinaton
  4-2-75     Ada/Canyon Waste
 (414,300)   Treatment Management
            Committee
            525 W.  Jefferson
            Boise,  Idaho  83702

  4-9-75     Regional  Planning Council
 (521,000)   of  Clark  County
            2400 T  Street
            Vancouver, Washington 98661

  4-22-75    Municipality of
 (850,000)   Metrooolitan Seattle
            Pioneer Building
            600 1st Avenue
            Seattle,  WA 98104
 Mr. Revan A.F. Tranter
 (415) 841-9730
 Dr.  O.V. Natarajan
 (Overseas Operator)
 Mr.  Tom Lucas
 (503)  221-1646
                                                               Mr.  Larry Frazier
                                                               (503)  588-6177
Mr. L.  Douglas  Halley
(503)  687-4283
Mr. Scott McDonald
(208) 232-4311
Mr. Georae J. Pattis
(208) 345-9510
Mr. Richard Hines
(206) 699-2361
                                                              Mr. Donald J. Benson
                                                              (206) 447-6666
                                       B-18

-------
Region and Area
Designation Date
 (Grant Amount)	Agency
                                                              Contact
Panhandle District,   5-27-75
Idaho                 (485,000)
Medford, OR
Snohomish,
  6-3-75
 (318,000)
  6-3-75
  (950,000)
Panhandle Planning &
Development Council
P.O. Box 1154
Coeur d1 Alene, ID 83814

Rogue Valley Council of
Governments
33 N. Central, Suite 211
Medford, Oregon 97501

Snohomish County Metro-
politan Municipal Corp.
Snohomish County Admin.
Bldg.
Everett, Washington 98201
                                          Mr. Bruce Thompson
                                          (208) 667-4619
Mr. Jeff Gibbs
 (503) 779-7555
George F. Sherwin
       or
Hayden Street
(206) 259-9357
                                        B-19

-------
o
I
LAKES  REGIO


    FITCHBURG


BERKSHIRE
                                                REGION  1
                                 MARTHA S VINEYARD
                                                            NORTHERN MAINE
                                                            LEWISTON - AUEURN
                                                           AUGUSTA - COBBOSSE
                                                           PORTLAND
                                                           SOUTHERN MAINE
                                               CAPE COD
                                                                                       70
                                                                                       m
                                                                                       CD

-------
o
I
ro
            REGION  2
              ERIE-NIAGARA
                SOUTHERN TIER CENTRAL
                   CORNING
                                NEW YORK CITY


                                       MERCER  CO,

                                  CAMDEN  AREA
                                                                    CENTRAL NEW YORK
                                                                      SYRACUSE
WESTCHFSTER

       LONG ISLAND
     MIDDLESEX CO,
                                                                  BAN CO,
                                                                          (PUERTO RICO)


-------
                                   PHILADELPHIA
                                                            REGION   3
               PITTSBURGH
o
I
CO
       CHARLESTON
              SOUTHWEST
                                                    RICHMOND
                                                                    BALTIMORE

                                                                    WASHINGTON^,C, - METRO



                                                                    NEW CASTLE CO,
                                                                       SUSSEX CO,
FREDRICKSBURG
                                                                     HAMPTON ROADS
                              ROANOKE
                                                UGH

-------
                     LOU ISVI LI
                             KNOXVILLE
                                 NGSPORT BRISTOL
                                      GREENVILLE
 REGION   4
    NASHVILLE
     MEMPHI
 CHATTANOOGA
BIRMINGHAM
   TUSCALOOSA
             MOBILE
      TALLAHASSE
               TAMPA BAY
                             11181
                   SARASOTA

                      HEW
                                                                                LEIGH-
                                                                              DURHAM
                                                                         -WACCAMAW
PENSACOLA
    BAY COUNTY
      ASHVILLE

     CHARLESTON



       COLUMBIA

       BEAUFORT,  SC

LUSIA CO,
      BREVARD CO,

    POLK CO,

       PALM BEACH

    BROWARD CO,
    DADE CO,

-------
           GREEN BAY
                   \  V
KALAMAZOO
o
I
en
                                           MUSKEAGON
                                                            REGION  5
                                                                        BAY CITY

                                                                        FLINT
                                                                      DETROIT


                                                                        TOLEDO
                                                                      CLEVELAND



                                                                       yOUNGSTOWN


                                                                       CANTON-AKRON




                                                                        JACKSON, MI

                                                                    DAYTON
                                                                   MUNCIE

                                                                  CINCINNATI
                                          SOUTHERN, IL\ INDIANAPOLIS

-------
o
I
en
        REGION  6
                                                        BEAUMONT - PORT ARTHUR
                                                     HOUSTON


                                                CORPUS CHRISTI
                                             LOWER RIO GRANDE

-------
REGION 7
                                           DBS MOINES
                                             ST, LOUIS, MO
                   KANSAS CITY
                Hill ISSlffi

-------
                                \MIDDLE-YELLOWSTONE
                                                       .YELLOWSTONE - TONGUE
                                                                         REGION   8
FLATHEAD & LAKE
 COUNTIES
                     LEWIS   CIJ\R
                                                                                 BLACK
                                                                                  HILLS
             JACKSON HOLE

              GREEN RIVER
                          SOU IX
                           FALLS
                                                                        LARIMER-WELD CO
 WEBER  - DAVIS     COLORADO
        (OGDEN)     WEST
POWDER RIVER
                                                     NORTJHWEST
                                                         CO
 SALT LAKE CO,
                                                                        COLORADO
                                                                           SPRINGS
                        'SOUTHEASTERN

                      FIVE COUNTIES, UT

-------
                         RENO
      LAKE TAHOE
o
I
    SAN FRANCISCO
           MONTEREY
       (GUAM)
                             \
                                   CARSON CITY
                  VENTURA CO,
                           SAN DIEGO


                          BEfWIlE
                                                     REGION  9
                                                       TUCSON

-------
                       REGION  10
             SEATTLE
                                             PANHANDLE, ID
       CLARK CO,
SALEM    PORTLAND
                                    /W^Xc"
                                             EUGENE

-------