WATER POLLUTION CONTROL RESEARCH SERIES
12060EHV12/70
   Aerobic Secondary Treatment
                 of
      Potato Processing Wastes
ENVIRONMENTAL PROTECTION AGENCY • WATER QUALITY OFFICE

-------
          WATER POLLUTION CONTROL RESEARCH SERIES

The Water Pollution Control Research Series describes the
results and progress in the control and abatement of pollu-
tion of our Nation's waters.  They provide a central source
of information on the research, development, and demon-
stration activities of the Water Quality Office, Environ-
mental Protection Agency, through inhouse research and grants
and contracts with Federal, State, and local agencies, re-
search institutions, and industrial organizations.

Inquiries pertaining to the Water Pollution Control Research
Reports should be directed to the Head, Project Reports
System, Office of Research and Development, Water Quality
Office, Environmental Protection Agency, Washington, B.C. 20242.

-------
  Aerobic  Secondary  Treatment
                  of
     Potato Processing Wastes
                   by
        The  R. T.  French  Company
              Shelley, Idaho
                 for the

 ENVIRONMENTAL PROTECTION AGENCY
        WATER  QUALITY OFFICE
           Program  12060  EHV
             WPRD  15-01-68

             December 1970
For sale by the Superintendent of Documents, U.S. Government Printing Office
           Washington, B.C., 20402 - Price $1.50

-------
                 EPA Review Notice
This report has been reviewed by the Water Quality Office,
EPA, and approved for publication.  Approval does not signi-
fy that the contents necessarily reflect the- views and poli-
cies of the Environmental Protection Agency, nor does mention
of trade names or commercial products constitute endorsement
or recommendation for use.

-------
                                    ABSTRACT
A  new  secondary  treatment  facility at the R. T. French Company, Shelley, Idaho, has
demonstrated  the  feasibility  of a  complete mix activated  sludge system  for secondary
treatment of potato  processing wastes. The secondary treatment facility was designed for
an  average daily flow of  1.25  million gallons per day  and  a BOD loading of 14,100
pounds  per day. Frequent aerator shutdowns following mechanical problems have limited
oxygen  transfer  and  biological activity in the aeration basins; however, BOD removals of
over 90 percent have been obtained for extended periods of time, demonstrating the
applicability of the activated sludge process for treating the wastes. These removals have
been obtained with:  (1) MLSS concentrations between 2,000 mg/1 and  8,000 mg/1, (2)
aeration basin D. O.  concentrations between 0.3  mg/1 and 5.2 mg/1, (3)  aeration basin
temperatures between 45 degrees F and 67 degrees F, (4) aeration basin  pH between 7.1
and 8.4, (5) organic loadings between 10 and 120 Ib BOD/1,000 cu ft/day, (6) hydraulic
detention times of 0.9 to 8.7 days, and (7) BOD/MLVSS ratios of 0.15 to 0.47.

This report was  submitted  in fulfillment of Grant No. WPRD 15-01-68, Program 12060
EHV, between the Environmental Protection Agency and R. T. French Company.

Key Words:      Potato  processing  wastes,  food  processing  wastes, activated  sludge,
                secondary treatment, treatment costs.

-------
                          TABLE  OF CONTENTS

 SECTION
                                                                   PAGE
                 ABSTRACT                                            '
 I               SUMMARY                                            '
 II               RECOMMENDATIONS                                   3
 ill              INTRODUCTION                                       4
 IV              TREATMENT METHODS
                     Activated Sludge Process                              6
                     Solids Treatment and Disposal                          6

 V               THEORETICAL CONSIDERATIONS                        8

 VI              PLANT DESCRIPTION
                     Design Criteria                                     ' 1
                     Flow Pattern                                      12
                     Design Factors                                     15
                     Demonstration Procedures                            19

 VII             PLANT INFLUENT CHARACTERISTICS                    23

 VIII            PLANT PERFORMANCE
                    Activated Sludge System                              25
                    Solids Treatment and Handling                         65

 IX              OPERATING PROBLEMS
                    Mechanical Problems                                 70
                    Process Problems                                    71

 X               FINANCIAL CONSIDERATIONS
                    Constmction Costs                                   73
                    Operation and Maintenance Costs                       73
                    Total Annual Costs                                  74

XI              DISCUSSION
                    Activated Sludge  System                             76
                    Solids Treatment  and Disposal                        105

Xll              ACKNOWLEDGMENT                                 108
XIII             REFERENCES                                        109

-------
                    TABLE  OF  CONTENTS  -  CONTINUED

SECTION                                                                PAGE

XIV             APPENDIXES                                            111
                      A.  Glossary
                      B.  Photographs of Major Components
                      C.  Supplemental Operating Data
                      D.  Sampling Points, Sampling Schedule, and Testing
                         Equipment
                      E.  Outside Laboratory Testing Reports
                      F.  Construction, Operation, and Maintenance Costs
                      G.  Supplemental Velocity Profiles, Dissolved Oxygen
                         Profiles, and Oxygen Uptake Data
                      H.  Heat Loss Relationships
                                      in

-------
                              LIST  OF FIGURES

FIGURE                                                                  PAGE

 1                Aerial View Secondary Waste Treatment Facility                13
 2                Flow Diagram Secondary Waste Treatment Facility              I4
 i                                                                          ~> "*
 j                Aeration Basin Operation
 4                Average BOD Loading vs. Time
 5                Probability of Influent BOD                                  26
                                                                            ") H
 6                Aeration Basin Dissolved Oxygen
                                                                            ^ Q
 7                Dissolved Oxygen, Basin 1
                                                                            OQ
 8                Dissolved Oxygen, Basin 2
 9                Basin Temp vs. Time
                                                                            O 1
10                Temperature, Basin 1
11                Temperature, Basin 2                                        32
12                Basin pH vs. Time                                           34
13                pH, Basin 1                                                35
14                pH, Basin 2                                                36
15                Plant Influent and Effluent pH                                37
16                SVI vs. Time                                               38
17                Influent and Effluent BOD                                   39
18                Average Organic Removals vs. Time                           40
19                Average BOD Removal                                       41
20                Average BOD Removal vs. Average BOD Loadings               42
21                Average Effluent BOD vs.  Average  BOD Loading                43
22                Substrate Removal vs. BOD Loading                           44
23                Effluent Soluble BOD                                       45
24                Average BOD Removal vs. Average BOD Loading                47
25                Basin Temperature vs. Coliform Removal                       48
26                Average MLSS vs. Average Effluent TSS                       49
27                Average Clarifier Loading vs. Average Effluent TSS              50
28                Average Effluent BOD vs.  Average  Effluent TSS                51
29                Average SVI vs. Average Effluent TSS                         52
30                Total Phosphate Removal  vs. Time                            53
31                Total Nitrogen Removal vs. Time                              54
32                Substrate and BOD Removal vs. BOD Loading                  55
33                Substrate and BOD Removal vs. BOD Loading                  56
34                Velocity Profile, Basin 1, 3 Aerators                           58
35                Velocity Profile, Basin 1, 3 Aerators                           59
36                Dissolved Oxygen Profile, Basin 2, 6 Aerators                    60
                                   IV

-------
                       LIST OF  FIGURES  -  CONTINUED

FIGURE                                                                  PAGE

37                Dissolved Oxygen Profile, Basin  1, 3 Aerators                   61
38                Dissolved Oxygen Profile, Basin  1, 9 Aerators                   62
39                Dissolved Oxygen Profile, Basin  1, 9 Aerators                   63
40                Dissolved Oxygen Profile, Basin  1, 9 Aerators                   64
41                Average TSS Removal vs. Time,  Clarifier-Thickener              66
42                Average BOD Removal vs. Time, Clarifier-Thickener              67
43                Solids Concentration and Dewatering                           68
44                Photomicrographs of Activated Sludge                          77
45                Effluent Soluble BOD vs. Substrate Removal                    78
46                Effluent Soluble BOD vs. Substrate Removal                    79
47                Effluent Soluble BOD vs. Substrate Removal                    80
48                Substrate Removal Rate vs.  Temperature                       81
49                Substrate Removal vs. Sludge Production                       83
50                Substrate Removal vs. Sludge Production                       84
51                Endogenous Respiration Rate vs. Temperature                   85
52                Sludge Age vs. Sludge Production                              87
53                Oxygen Uptake Rate vs. Substrate Removal Rate                88
54                Average BOD Removal vs. Average Basin D. O,                  89
55                Average BOD Removal vs. Average Basin Temp                  91
56                Average BOD Removal vs. Average Basin pH                    92
57                Average BOD Removal vs. Average PO4/BOD                   93
58                Average BOD Removal vs. Average N/BOD                      94
59                Average Substrate Removal  vs. Average D. O.                    95
60                Average Substrate Removal  vs. Average Basin Temp              96
61                Average Substrate Removal  vs. Average pH                      97
62                Substrate Removal vs. PO4/BOD                              98
63                Substrate Removal vs. N/BOD                                 99
64                Plant Influent and Effluent  Temperatures                     100
65                Aeration Basin Heat Loss Relationship, 2 to 3.5 Days
                    Detention Time                                          102
66                Aeration Basin Heat Loss Relationship, 3.5 to 6.5  Days
                    Detention Time                                          103
67                Aeration Basin Heat Loss Coefficient vs. Detention Time       104
68                Secondary Clarifier Loading Factor vs. MLSS                  106

-------
                               LIST OF  TABLES

TABLE                                                                    PAGE

1                 Secondary Treatment Facility Design Criteria                   11
2                 Secondary Treatment Facility Design Factors                   15
3                 Major Equipment Manufacturer                               18
4                 Activated Sludge System Operation Schedule                   20
5                 Secondary Treatment Costs                                   74

-------
                                    SECTION I
                                    SUMMARY
During  the  1969-70  potato processing  season, aerobic secondary treatment of potato
processing wastewater at R. T. French Company was studied. These studies were partially
supported by an Environmental Protection Agency demonstration grant.

On the  basis of the results  presented in  this report, the following conclusions have been
reached:

 1.  Treatment  of potato  processing wastewater by  a fully  aerobic  aeration process,
     specifically by the  activated sludge process, is feasible.

 2.  BOD removals of over 90 percent have been obtained for sustained periods of time
     while operating the plant as an activated sludge system.

 3.  BOD removals of between 70 and 80 percent have been obtained while operating as
     a flow-through aeration system, without secondary clarification.

 4.  Coliform removals in excess  of 96 percent were obtained  in the activated sludge
     system.

 5.  High pH values of influent process  wastewater were buffered in the aeration basins
     and were not detrimental to treatment efficiencies.

 6.  Low air temperatures have not caused failure of  the activated sludge process.  Data
     obtained do, however, demonstrate  the need to consider temperature loss in system
     design.

 7.  The quantity of excess biological sludge,  AXy, was found to be a function of  the
     BOD removal rate, Sf, and  the  average MLVSS (mixed  liquor volatile  suspended
     solids), X^.

 8.  The  substrate  removal  rate coefficient,  k, was  found  to  be  a  function   of
     temperature, as follows:

          k  = 0.016 x 1.

 9.  System  oxygen requirements  are a  function of the BOD removal rate, Sr, and  the
     average MLVSS, X^, in accordance with the following equation:

          02 =  0.48 Sr + 0.03 Xd

-------
10.  Total annual activated sludge treatment costs are estimated to be $0.038 per pound
    of BOD  applied  and  $0.021  per pound  of COD  applied. These  costs  are  for
    secondary treatment only and do not include waste activated sludge disposal.

11.  The  clarifier-thickener  approached 100 percent suspended  solids removal  when
    operated  as a straight silt removal system.

12.  Operation of the clarifier-thickener for dewatering secondary sludge in combination
    with silt was not successful.

13.  Operation of the clarifier-thickener, vacuum filter, and solids  conveying system  has
    demonstrated the need for special  designs for handling silt removed from potatoes.

-------
                                    SECTION II
                               RECOMMENDATIONS
It  is  recommended  that  future  studies be initiated  to determine feasible methods to
concentrate, dewater, and dispose of the large quantities of waste activated sludge from a
potato  processing waste  treatment facility. These  studies  should be  concentrated  on
methods which could produce an end product palatable for use as cattle  feed.

Development of a system to mix and dewater silt and waste activated sludge effectively
would be  beneficial  to use as  a  standby for a cattle feed disposal system.  Chemical
additions would probably  be required to meet this objective.

Additional studies in the area of  sludge bulking control are needed. Development of a
feasible  control system would enhance the value of the highly  efficient activated sludge
process in treating potato  process wastewater and other similar industrial  wastes.

-------
                                    SECTION III
                                  INTRODUCTION
SCOPE

Aerobic  secondary treatment systems  were  studied  at  the  R. T.  French  Company  in
Shelley,  Idaho, during the 1969-70 potato processing season  to  ascertain their efficiency
in  treatment  of  potato  processing  wastes.  These  studies  were  conducted  as  an
Environmental Protection Agency demonstration grant project.

The objectives of the  grant were to:

1.   Demonstrate  the feasibility of secondary treatment  of potato processing wastewater
     by a fully aerobic aeration process; specifically by the activated sludge system.

2.   Determine the BOD removal  efficiency  and effluent characteristics when the system
     is operated as:

     a.    An  activated  sludge  system with biological  sludge  being returned  to the
          aeration basins to maintain a specific MLSS (mixed  liquor suspended solids)
          concentration.

     b.   A  flow-through aeration  system  with biological  sludge  carry-over into the
          effluent.

     c.    An  intermittent  aeration  system   with  the  clarified  upper portion  of the
          aeration basin  contents being discharged directly to  the river.

3.   Determine  the quantity and  characteristics  of the excess biological  sludge which
     must be disposed of.

4.   Demonstrate  the effectiveness of  solids  removal through the clarifier-thickener and
     disc filter handling system when  operated:

     a.    As straight  silt removal system.
     b.   With dewatering of secondary sludge in combination with silt.
     c.    With dewatering of secondary sludge alone.

5.   Demonstrate  and  establish operating parameters for  the systems constructed and
     studied, which will include:
'This objective was to be pursued only if time permitted and it  could  be   worked   in
 conveniently.

-------
     a.    Initial and construction costs.
     b.    Operating costs (power, chemicals, etc.).
     c.    Operation problems.
     d.    Treatment efficiency.
     e.    Maintenance problems and costs.
     f.    Silt and waste secondary sludge disposal problems and cost.

6.    Determine  the effect of this  treatment on MPN and chlorine requirements of the
     final effluent.

7.    Establish  the influence  of:   foaming, ice,  climatic temperatures, pH,  nitrogen,
     phosphorus, and  periodic flow interruptions  and processing plant  shutdowns upon
     the treatment system.

Operation and cost data included in this report are for the secondary treatment  facility
only. Primary treatment of the process wastewater is provided at the processing plant and
has not been evaluated in this study.

The R. T. French Company retained  the firm of Cornell,  Rowland, Hayes & Merryfield,
Consulting Engineers, to design the facility and to exercise technical supervision over the
research and development program.

-------
                                   SECTION  IV
                             TREATMENT  METHODS
ACTIVATED SLUDGE PROCESS

The activated sludge process is a biological treatment process in which biologically active
growths (activated sludge) are  continuously mixed in a basin with the wastewater in the
presence  of oxygen. The combination of wastewater and activated sludge is called mixed
liquor. The oxygen is supplied to the mixed liquor from compressed air injected into the
liquid mass in  the  form of fine bubbles  under turbulent  conditions, or by mechanical
aeration.  The   activated  sludge is  subsequently  separated  from  the mixed liquor by
sedimentation  in  a clarifier and is  then wasted  or returned  to the aeration  basin  as
needed. The overflow  from the clarifier (treated wastewater) is chlorinated and discharged
to a receiving stream.

There are many variations of  the activated sludge  process; however,  all operate  basically
the same. The variations are the result of unit arrangement  and methods of introducing
air and wastewater into the aeration basin.

The  most  recent  advances  in the  activated  sludge  process utilize  a  "complete  mix"
approach when combining the activated sludge and wastewater. Biological stability and
the subsequent  efficiency of the aeration basin is enhanced by the design which maintains
the entire  content  of the aeration  chamber in a "completely  mixed" and essentially
homogeneous state  during the aeration cycle.  Wastewater introduced into the  aeration
basin  is dispersed rapidly throughout the  mass and is  subjected to immediate attack by
fully-developed  organisms throughout the aeration basin.

Complete-mix  activated  sludge  treatment may or  may  not be  preceded  by  primary
treatment.  In general, large treatment facilities use  primary treatment in conjunction with
the activated sludge process, while smaller  treatment plants do not.

The  R. T.  French treatment  facility is  a complete-mix  system, preceded  by  primary
treatment.

SOLIDS TREATMENT AND DISPOSAL

Unit processes currently employed in treatment and disposal of solids can be  divided into
four categories:   concentration, stabilization, dewatering, and dehydration disposal. The
R. T.  French   facility employs  concentration, dewatering, and disposal  methods  as
described below:

-------
GRAVITY THICKENING-Gravity thickening is a concentration process in which solids
are gently stirred  in  a  sedimentation  tank  to release entrapped water and gas, allowing
thickened solids to settle to a bottom hopper from which they are later removed.

VACUUM FILTRATION—Vacuum filtration is a  dewatering process in which cylindrical
drums or discs, covered  with filter media and  partially  submerged in a  container of
sludge,  rotate while  a  vacuum is pulled through the drum or  disc surfaces and  filter
media. Water is extracted while solids are retained on the filter media to form a cake.

LANDFILL—Landfill  is  an ultimate process  for  disposing of  dehydrated  solids.  It is,
however, generally limited to reclaiming waste land.

-------
                                   SECTION V
                       THEORETICAL  CONSIDERATIONS
BIOLOGICAL CHARACTERISTICS OF ACTIVATED SLUDGE

MICROBIOLOGY-The living organisms of activated sludge can be classified as plants and
animals. The  plants consist of bacteria and fungi, while the animals consist primarily of
protozoa, rotifers, and nematodes.

Hawkes [1]  stated  that bacteria  are normally dominant as primary feeders on organic
wastes,  with  different holozoic  protozoa being secondary  feeders,  and  rotifers  and
nematodes  being at the higher levels in the food chain. Fungi cannot  normally compete
with bacteria, but they may predominate as primary feeders  if certain conditions exist,
such as:  low  pH, nitrogen deficiency, or low dissolved oxygen [2]. High-carbohydrate
wastes  are also reported to stimulate fungi growth.

The composition of the organic waste determines which bacterial genera will predominate
[1,2]. Protein wastes favor Alcaligenes, Flavobacterium, and Bacillus, while carbohydrate
wastes  favors  Pseudomonas. A high population of free swimming bacteria will sustain  free
swimming ciliata as the predominate protozoa; however, if the free swimming bacterial
population  is  reduced, stalked ciliJates take over from the free swimming cililates because
the lower food level cannot provide the amount of energy required by the free swimmers
Rotifers thrive in very  stable  systems and are better indicators of stable conditions than
are the nematodc worms.

Ml TABOLlSM-The  metabolic  reactions which  occur within activated  sludge  can  be
divided  into three phases: (1) oxidation, (2) synthesis, and (3) endogenous respiration.
These three  phase reactions can be illustrated with the  following general equations, which
have been simplified from those formulated by Weston  and Eckenfelder [3]:

     (1)  Organic Matter Oxidation

         CxHyOz + a02	*xC02 + bH2O + Energy

     (2)  Cell Material Synthesis

         CxHyOz + NH3 + cO2 + Energy	^CjH-yNO-, +  dCO2 + eH->O

-------
     (3)  Cell Material Oxidation

         C5H7NO2 + 5O2	*• 5CO2 + 2H2O + NH3 + Energy

In the presence of enzymes, produced by living microorganisms, about  one-third of the
organic matter  removed  is oxidized to carbon dioxide  and  water  to provide energy for
synthesis of the other two-thirds of the organic matter removed to cell material [4]. The
cell material  is also oxidized  to carbon dioxide, water, etc., by endogenous respiration
(auto-oxidation).

KINETICS—Several authors  [5,6,7] have formulated  mathematical equations  for design
and operation of  complete-mix activated sludge plants. Some of these  formulations are
more  easily used  for evaluation of full-sized  plant operation  than others. Eckenfelder's
equations [6] are  of this nature and have been used to evaluate the operation of the new
R. T.  French Company waste treatment facility. The basic equations are presented below:

SUBSTRATE UTILIZATION-The  Michaelis-Menton relationship was used to define the
microbial growth rate and steady state substrate removal in  a  completely mixed system,
and a simplified equation for substrate removal was developed:
              Sa - Sf   Sr
          6     Xat     Xat

where Sr   =   BOD removed, Ibs per day
       Sa   =   influent BOD, Ibs per day
       Sf   =   soluble effluent BOD, Ibs per day
       Se   =   soluble effluent BOD, mg/1
       Xa  =   average mixed liquor volatile suspended solids, Ib
       t    =   aeration time, days
       k    =   removal rate coefficient, Ib BOD/day-lb MLVSS-mg/1 BOD

The equation shows  that the substrate  removal is proportional to the product of the
MLVSS and the aeration time.

SLUDGE  YIELD—Excess solids  in the  activated  sludge  system  will result  from the
non-biodegradable  suspended  solids  in the influent and the biological cells synthesized  in
the system  during BOD removal less the  quantity of  cell mass synthesized which  is
broken down by endogenous respiration. This excess  sludge can be expressed with the
following  equation,  when  influent  non-volatile suspended  solids  do  not exist or are
ignored:

-------
        AXN    =      fS0 + aSr  bXd

where   A\v    =      net accumulation of volatile suspended solids, Ibs per day

       f        =      fraction  of volatile suspended  solids  present  in  the influent
                       which are not degradable

       S0       =      influent volatile suspended solids, Ibs per day

       a        =      sludge synthesis yield coefficient

       Sr       =      BOD removed, Ibs per day

       b        =      rate of sludge endogenous respiration, per day

       X^       =      average   mixed  liquor   volatile  suspended  solids  which  are
                       degradable, Ib

Where  non-volatile suspended  solids exist in the system  influent, this quantity can be
added directly to the foregoing excess solids yield, AXy.

OXYGEN  REQUIREMENTS-O.xygen  is   used  to  provide  energy  for synthesis of
biological cells  and for endogenous respiration  of the biological mass.  The total oxygen
requirements can be expressed with the following equation:

       02       =      a' Sr + b' Xd

where  O->       =      oxygen requirements, Ibs per day

       a1        =      fraction of BOD removed  that is oxidized for energy

       Sr       =      BOD removed, Ibs per day
       b        -      oxygen used for endogenous respiration of the biological mass, per
                       day

       Xd       =      average mixed liquor volatile suspended solids that are degradable,
                       Ib
                                       10

-------
                                 SECTION VI
                             PLANT  DESCRIPTION
Potato processing plant wastewater can be divided into two major streams: (1) silt water
and (2) process water. The silt  water  originates from raw potato washing and fluming
operations.  It contains large  amounts of soil removed from  the raw  potatoes. Process
water flows  from  potato  processing  operations, where raw potatoes are processed into
packaged, partially  cooked food products. It contains caustic potato  peeler  and  barrel
washer discharges,  as  well as all other liquid wasted from  the processing operations,
including cleanup water.

DESIGN CRITERIA

The  criteria  used for  the final design of the secondary treatment facilities at the R. T.
French Company are listed in Table 1.

                                   TABLE 1
           SECONDARY  TREATMENT FACILITY  DESIGN CRITERIA
AVERAGE DAILY FLOW
     Waste Process Water
     Waste Silt Water
                                                  TOTAL
     1.0
     0.25
     1.25mgd
PEAK HOUR FLOW RATE
     Waste Process Water
     Waste Silt Water
                                                  TOTAL
  836
  400
 1,236 gpm
BOD LOAD
    Waste Process Water
    Waste Silt Water
                                                  TOTAL
13,700
  400
14,100 Ib/day
SUSPENDED SOLIDS LOAD
     Waste Process Water
     Waste Silt Water
                                                  TOTAL
 5,680
   940
 6,620 Ib/day
                                      11

-------
FLOW PATTERN

An aerial photo of the secondary waste treatment facility is shown on Figure  1, and the
treatment facility flow diagram is shown  on Figure 2. A general description of the flow
patterns of the plant is given in the following paragraphs.

Primary clarified potato process  wastewater flows by gravity to the influent pump pit
where it  is combined with clarified silt water. This total plant influent is then pumped to
the aeration basin inlet-outlet structure,  where  the  flow can  be divided,  as  desired,
between  the two aeration basins. The incoming wastewater is dispersed throughout each
of the aeration basins by floating  mechanical aerators.

Effluent  from  the  aeration basins flows  by gravity  back  through the aeration basin
inlet-outlet structure  to  the clarifier bypass structure. The flow is  normally directed to
the secondary  clarifier,  but in an emergency may be bypassed at the  clarifier bypass
structure for discharge to the Snake River.

Effluent from  the secondary clarifier flows to the Snake River.

Lightweight settled sludge  flows by gravity from the bottom of the clarifier to  the sludge
collection  launder. It then flows by  gravity from the sludge launder to  the sludge
recirculation pump  pit. The sludge is then pumped to the recirculated sludge splitter box,
where  it can  be divided  into two portions of  desired size and  returned to the two
aeration basins.

Dense settled  sludge is pumped from the sludge hopper  in  the bottom of the clarifier to
either  the  vacuum filter or to  the clarifier-thickener.  This waste sludge  may also be
pumped to the clarifier bypass structure for discharge to the river.

The waste  sludge, pumped to the clarifier-thickener,  is concentrated along with silt water.
Clarifier-thickener overflow is transferred  by gravity  to  the influent pump  pit. The
thickened sludge is pumped from the  bottom of the clarifier-thickener to the vacuum
filter, where it is dewatered along with any waste sludge pumped directly to  the filter.

Solids discharge from the vacuum filter is conveyed to  the silt  bunker in  a  cake form.
This cake is then hauled away  by  trucks for ultimate disposal as landfill.
                                        12

-------
                                                                 FIGURE 1
                                                               AERIAL VIEW
                                                             SECONDARY WASTE
                                                            TREATMENT FACILITY
CLARIFIER-
THICKENER

-------
   FLOW DIAGRAM
 SECONDARY WASTE
TREATMENT FACILITY

-------
DESIGN FACTORS

The design factors used for major equipment selection are shown in Table 2. Photographs
of the major components are located in Appendix B and the major treatment units are
described below. Selected equipment manufacturers are listed in Table 3.

Aeration Basin 1 holds 1.25 million  gallons  and normally contains three  50-hp foating
mechanical aerators. Aeration Basin 2 holds 2.5 million gallons and normally utilizes six
50-hp floating mechanical aerators. Both basins have a water depth of 16 feet. The design
BOD  loading  is 28  lb/1,000 cu ft/day when the two aeration  basins are operated  in
parallel. The aeration  basins are  constructed of earth  and were lined with PVC (polyvinyl
chloride). The bottom  of the  basins  were  sloped  to  prevent  forming  pockets  for
entrapment of water or gas. A sun-resistant Hypalon  plastic sheet was placed around the
perimeter of the basins to  protect the PVC from exposure to sunlight. The Hypalon was
bonded to the PVC to provide a  watertight field weld.

The  secondary clarifier  is  70 feet in diameter and has a 12-foot side  water depth. The
clarifier  has a rapid  sludge withdrawal mechanism. The hydraulic overflow rate is 325
gal/sq ft/day at the design flow of 1.25 mgd.

The  treatment facility control building houses the vacuum  filter, sampling and  testing
laboratory, and various sludge handling equipment. The vacuum filter is  a  disc type and
has a surface area of 300 square  feet.

The  clarifier-thickener is 30 feet in diameter  and has a side  water depth of 8  feet. The
hydraulic overflow rate at design flow is 860 gal/sq ft/day.

                                    TABLE  2
            SECONDARY TREATMENT FACILITY DESIGN  FACTORS

INFLUENT PUMPS
       Number                                                                   2
       Type                                                             Centrifugal
       Capacity
          Each                                                          1,300 gpm
          Total                                                         2,600 gpm
       Total Head                                                          27 feet
       Constant Speed                                                     870 rpm
                                       15

-------
                           TABLE 2   CONTINUED
SLUDGE RECIRCULATION PUMPS
      Number
      Type
      Capacity
         Each
         Total
      Total  Head
      Constant  Speed

WASTE  SLUDGE PUMP
      Number
      Type
      Capacity
      Total  Head
      Speed
      Drive
                     Centrifugal

                       435 gpm
                       870 gpm
                        18 feet
                       870 rpm
                             1
            Positive displacement
                       100 gpm
                        46 feet
                       550 rpm
                 Variable - speed
AERATION BASINS
       Number
       Type
       Volume of Basin  1
       Volume of Basin  2
       Basin Water Depths
       Basin Side Slopes
       Basin Freeboard
       Basin Lining

       Number of Aerators, Basin 1
       Number of Aerators, Basin 2
       Design Organic loading

AERATION EQUIPMENT
       Number Aerators in Aeration Basins
       Type
                             2
                        Earthen
              1.25 million gallons
               2.5 million gallons
                         16 feet
                           2:1
                         2 feet
       PVC with Hypalon cover in
                sun-exposed area
                             3
                             6
         28 Ib BOD/1,000 cu ft/d
   Floating pump type mechanical
     surface aerators with variable
oxygen transfer-power draw feature
                                     16

-------
                           TABLE 2 -  CONTINUED
AERATION EQUIPMENT - Continued
       Oxygen Transfer Capacity
SECONDARY CLARIFIER
       Number
       Diameter
       Side Water Depth
       Mechanism Type
       Design Flow
       Overflow Rate at Design Flow
       Detention Time at Design Flow

CLARIFIER-THICKENER
       Number
       Diameter
       Side Water Depth
       Design Flow
       Overflow Rate at Design Flow

VACUUM FILTER STATION
       Vacuum Filter
           Number
           Type
           Diameter
           Number  of Discs
           Filter Area
           Tank Volume
           Hydraulic Capacity - Filtrate
       Vacuum Pump
           Number
           Capacity
           Speed
           Vacuum
             75 pounds per hour each in
        aeration basins with mixed liquor
          suspended solids = 4,000 mg/1,
operating elevation = 4,627 ft. above MSL,
            temperature at 20 degrees C.,
          Alpha = 0.85, Beta = 0.90, and
    operating dissolved oxygen =1.5 mg/1
                                    1
                               70 feet
                               12 feet
          Multiple port hydraulic suction
                1.25 million gallons/day
                      325 gal/sq ft/day
                             7.2 hours
                                    1
                               30 feet
                                8 feet
                             425 gpm
                      860 gal/sq ft/day
                                    1
                                 Disc
                                6 feet
                                    6
                        300 square feet
                           750 gallons
                              150 gpm

                                    1
                              900 cfm
                            2,100 rpm
                          20 inches  Hg
                                     17

-------
                           TABLE  2  CONTINUED

VACUUM FILTER STATION - Continued
      Filtrate Pump
           Number                                                            1
           Capacity                                                    150 gpm
           Speed                                                      l,750rpm
           Allowable Head                                               55 feet
      Blower
           Number                                                            *
           Capacity                                                     199 cfm
           Speed                                                      l,750rpm
           Discharge Pressure                                               5 psi
      Screw Conveying System
           Size of Screw                                                 9 inches
           Length                                                      27 feet
           Capacity                                         200 pounds per hour
      Clarifier-Thickener Underflow Pump
           Number                                                            1
           Type                                                      Diaphram
           Capacity                                                     50 gpm
           Total Head                                                   30 feet
           Power Unit                                              Variable drive
                                  TABLE 3
                    MAJOR  EQUIPMENT  MANUFACTURER

       EQUIPMENT ITEM                                 MANUFACTURER

 Influent pumps                                          Cornell Manufacturing Co.
 Sludge recirculation pumps                                       Chicago Pump Co.
 Waste sludge pumps                                                Moyno Pumps
  sample pumps                                           Robbins & Meyers, Inc.
 Clarifier-thickener underflow pump                                   Marlow Pumps
 Flowmeters                                             Hersey-Sparling Meter Co.
 Aerators                                                   Welles Products Corp.
 Disc filter                                                    Eimco Corporation
  clarifier-thickener mechanism
 Secondary clarifier mechanism                                      Dorr-Oliver, Inc.
                                     18

-------
DEMONSTRATION PROCEDURES

During  the  test period,  the secondary treatment facility received wastewater flow on  a
schedule  parallel  with  the operating schedule  of the potato  processing  plant.  The
processing plant operated  almost  continuously, except  for a  two-day  shutdown  on
weekends for cleanup and repairs.  Cleaning water flow during processing shutdowns was
directed to the treatment facility.

Primary clarified process wastewater was directed to the secondary treatment facility by
adjusting  slide gates in Manhole 1 (see Figure  2). The amount of process water discharged
to the facility was determined by  the aeration basin operation. All process water entered
the  facility  during  normal  operation.  Screened  silt  water  was  directed   to  the
clarifier-thickener by silt water pumps  in the storage cellars.

Potato processing seasons are about nine to ten months long in Idaho.

OPERATION SCHEDULE—The secondary waste treatment facility was operated from 3
September  1969  through 6  June  1970.  The activated  sludge system was operated as
shown in  Table  4.

AERATION  BASIN  STARTUP-Initial   startup   of   the  activated  sludge  system
included:  (1) filling aeration basin  2  with  wastewater,  (2)  aerating  the wastewater
without additional influent until  the  D. O. rose above 0.5 mg/1, (3) directing increased
portions  of  the total plant influent to the aeration basin  while maintaining the D. O.
above 0.5 mg/1, and (4)  returning all of the secondary clarifier solids to the  aeration basin
until the  desired MLSS concentration was reached.

After initial plant startup, aeration basins have been restarted by transferring some or all
of the contents  of the basin in operation into  the basin being started. Influent wastewater
was then  directed to the newly started basin  in increasing proportions of the total plant
influent while  maintaining a residual D. O.  concentration  over  0.5  mg/1.  All of the
secondary clarifier  solids  were returned  until  the  desired MLSS  concentration  was
attained.

The startup  method  used successfully during  the latter part  of the demonstration period
and during the current processing season includes the following steps:

1.   Fill the basin with  clean water.

2.   Position and start aerators.
                                        19

-------
                                                             TABLE 4
                                                   ACTIVATED SLUDGE SYSTEM
                                                      OPERATION SCHEDULE
OPERATION
PERIOD
SEPT. 3
TO
OCT. 22
OCT. 22
TO
NOV. 10
NOV. 10
TO
DEC. 18
DEC. 18
TO
JAN. 12
JAN. 12
TO
FEB. 12
FEB. 12
TO
APR. 13
APR. 13
TO
MAY 27
MAY 27
1 U
JUNE 6
BASIN
NO.
2
1
2
1
2
1
2
2
1
2
1
2
METHOD
OF
OPERATION
R.S.<2>
R.S.
R.S.
R.S.
R.S.
R.S.
FT. <3>
R.S.
R.S.
R.S.
F.T.
R.S.
% OF
INFLOW
100
20
80
33
67
20
80
100
100
100
22.5
77.5
AVERAGE
FLOW
(MGD)
0.530
0.241
0.967
0.341
0.694
0.207
0.829
0.717
1.144
1.071
0.197
0.681
AVERAGE
DETENTION
TIME (DAYS)
4.71
5.18
2.58
3.66
3.60
6.03
3.01
3.48
1.09
2.33
6.34
3.67
LENGTH
OF
OPERATION
(DAYS)
50
19
36
25
31
60
45
9
MLSS<1>
OPERATING
RANGE (MG/L)
930-3600
66-6280
1830-6130
2350-5140
1830-6450
1430-3360
1350-4050
245-3270
455-9400
1450-7100
450-2750
1100-3600
BASIN TEMP.
OPERATING
RANGE
(°F)
46-67
50-68
55-67
45-63
45-61
42-50
49-58
43-60
45-65
50-70
50-60
60-68
to
O
          NOTES:
            (11   MIXED LIQUOR SUSPENDED SOLIDS
            (2)   RETURN SLUDGE AERATION
            (3)   FLOW THROUGH AERATION

-------
3.   Build up a D. O. of about 5 mg/1 in the basin.

4.   Start  feeding  wastewater  to the basin  at  increasing flow  rates  as  the MLSS
     concentration increases.  Keep the F:M ratio (pounds of BOD per day to  the pounds
     of mixed  liquor  volatile suspended  solids in the basin)  between 0.1  and 0.5  in
     accordance with Figure 3.

5.   Keep the D. O. level above 1.0 mg/1  at all times, preferably in the range of 1.5  to
     3.0 mg/1.

6.   Return all secondary  clarifier solids  to  the  aeration basin until the desired MLSS
     level is reached.

Future  processing plant annual startups will  be by stages,  permitting treatment of the
entire wastewater flow by the secondary treatment facility.

SAMPLING SCHEDULE AND PROCEDURE-Sample points are shown on Figure 2 and
are described in detail in Appendix D. Waste  activated sludge and vacuum filter  filtrate
analyses were made on grab samples.  Samples  were collected at all other sample points
with  sample  pumps  and  automatically  controlled  stock  samplers  to  give 24-hour
composite samples, proportional to flow.

The sampling and testing schedule used during the demonstration operation is located  in
Appendix D.

ANALYTICAL TECHNIQUES-Analytical tests were  performed in accordance with the
twelfth edition  (1965)  of  Standard  Methods for   the Examination  of  Water  and
Wastewater of the American Public Health  Association,  with the  following exception:

Suspended  Solids—Suspended solids tests were performed using GF/C glass-fiber filter
discs instead of asbestos mats. A list  of the laboratory equipment used in the analytical
testing is included in Appendix D.
                                       21

-------
I J
I J
                                          4.000
                                 INFLUENT BOD LOAD TO AERATION BASIN 1  (LBS./DAY)

                                    8,000          12,000         16,000           20.000
                        5.000
                     o  4,000 .
                     CO
                     Q
o
CO
a
LLJ
Q
                     O_
                     co
                     CO
<
_l
o
cr
O
O
                        3,000 .
   2.000
                        1,000 .
                              OPERATION NOT
                              RECOMMENDED
                              IN THIS RANGE
                                       RECOMMENDED;
                                       OPERATING    i
                                       RANGE
                                          8,000
                                                                                        OPERATION NOT
                                                                                        RECOMMENDED
                                                                                        IN THIS RANGE
   16,000          24,000          32000          40,000
INFLUENT  BOD LOAD  TO AERATION BASIN  2  (LBS./DAY)

                 FIGURE  3
                                                                                             24,000
                                                                                                                                 28.000
                                                                                              48,000
                                                                                                             56,000
                                                           AERATION BASIN  OPERATION

-------
                                 SECTION VII
                     PLANT  INFLUENT CHARACTERISTICS
Total secondary treatment  plant influent contains primary clarified process  water  and
clarified silt water. Characteristics of the total plant influent are described below,  and
daily variations and probability plots of the characteristics are located in Appendix C.

ALKALINITY, pH, AND TEMPERATURE-Total plant influent alkalinity varied from 70
mg/1 to 5,740 mg/1, with an average of 1,640 mg/1, as CaCC^. The pH varied from 6.8 to
11.5, and  averaged 9.3. The influent temperature varied from 12 degrees C to  24 degrees
C. The average temperature was 20 degrees C.

BOD AND COD-The BOD of  the total plant influent varied from 780 mg/1 to  3,210
mg/1. The average  BOD was 1,680 mg/1. Sixty-five to 70 percent  of the total influent
BOD was  in a soluble form. The total BOD loading varied from 385 Ibs/day to 33,000
Ibs/day, with an average of 14,500 Ibs/day. Figure 4 shows the average weekly BOD load
variation and the general tread  of increased load (first order curve, least squares fit) as
the processing season progressed. The COD (chemical  oxygen demand)  of the influent
varied  from  1,330 mg/1  to 7,100  mg/1, with an  average of 3,050 mg/1. The average
influent BOD:COD ratio was 0.55.

SUSPENDED SOLIDS-The TSS (total suspended solids) concentration  in the  total plant
influent varied  from 320 mg/1 to 6,460 mg/1. The average TSS was  1,480  rng/1. VSS
(volatile suspended solids) averaged 70 percent of the TSS.

NUTRIENTS-The BOD:nitrogen:phosphate  ratio  of  the  plant influent  varied from
100:4.4:0.6 to 100:10.1:2.4 and averaged 100:6.2:1.1.

FLOW—The total plant influent flow varied  from  0.03 mgd to 1.64 mgd  and averaged
0.95 mgd.
                                      23

-------
cc
o
CD
cr
o
CD


UJ
cr
a:
erg
  ID
  SEPT. 1
               OCT. 1
                            NOV. 1
                                         DEC. 1
                                                      JAN. 1
                                                                    FEB. 1
                                                                               MAR. 1
                      1969
                                                             TIME
	1	1	
 APRIL 1        MAY 1

        1970
  I

JUNE 1
                                                                                                                                    JULY 1
                                                               FIGURE 4
                                                   AVERAGE BOD LOADING VS. TIME

                                                              (ALL  DATA)

-------
                                  SECTION  VIH
                             PLANT  PERFORMANCE

ACTIVATED SLUDGE SYSTEM

SYSTEM  OPERATION—Numerous mechanical  problems hindered  plant  performance;
however, four months of effective operation  has been achieved. The operating data from
these four months  of experience have been analyzed in greater detail than the data for
the other five months of demonstration operation.

Figure 5 is a computer  plot of the best fit curve of the frequency distribution of BOD
loading to the activated sludge  system on arithmetic-probability  paper. The  probability
shown on this and  following similar figures is the percentage of measurements equal to,
or less  than, the stated  class mean of the measured item, with all available data being
used. Figure 5 shows that about 45 percent of the time the BOD loading to the activated
sludge system was equal to, or less than, the  plant design load of 14,100 Ibs BOD/day or
55 percent of the time,  the BOD  loading was equal to, or greater than, the design load.
Actual loadings exceed the design criteria because of a delay in the construction  of the
facility and an expansion of the processing plant. However, design safety factors  permit
the present treatment plant to handle the existing volume of processing wastes; although
further expansion of the processing plant capacity could require expansion of treatment
facilities.

Aeration basin dissolved  oxygen levels are shown on Figure 6. Figure 7 shows that about
40  percent  of the time the D. O.  (dissolved  oxygen) in Basin 1 was less than 1.0 mg/1,
which is often thought  to be  a minimum level to avoid limiting biological activity. Basin
2 operated at a  similar  level for over 25 percent of the time (Figure 8). Low basin D. O.
levels were associated with mechanical aerator  problems. At the top of Figure  6  and
subsequent plots with  time functions, R. S. means return sludge operation  and F. T.
means flow-through  operation. The percentages represent the portion of influent to each
basin.

The  temperature  variations in the aeration basins are shown on Figure 9, while Figure  10
shows  that about 20 percent of the time, Basin 1 temperature was equal to, or below,  50
degrees F (10 degrees C), which is reported to be low enough for  filamentous bacteria to
become competitive. Basin 2 had similar low temperatures 10 percent of the time (Figure
11).  Low basin  temperatures  occurred at long aeration times and low air  temperatures.
Basin temperatures  also  dropped  during weekend shutdowns when warm process water
discharges to the treatment facility were decreased or discontinued.
                                       25

-------
PROBABILITY (% EQUAL TO OR LESS THAN)
                                                                       CD
                                                                       CD

00
f~i
o
OS9S3
csets
SSR83
i.esoe
J CD
-3 . ^pou)*-cno)-ja)(DCD CD • 
-------
BASIN 2
R.S. *~
BASIN 1
20%
BASIN 2
80%
3OTH R.S.
BASIN 1-33%
BASIN 2-67%
BOTH R.S.
BASIN 1
20% R.S.
BASIN 2
80% R.S.
BASIN 1
DOWN
* BASIN 2 *"
R.S,
BASIN 1 R.S.
* BASIN 2 DOWN *~
BASIN 1 DOWN
|" BASIN 2 R.S. *~


BASIN 1
F.T.
BASIN 2
DOWN
                       SYSTEM UPSET
                       BULKING DUE
                       TO LOW D.O.
                                                            SYSTEM UPSET
                   BULKING DUE
                   TO LOW D.O.
                                                                                                           SYSTEM
                                                                                                            UPSET
                BULKING
                DUE TO
                LOW D.O.
X
o
o

•5'
o
(O
(O
               KEY
            BASIN 1  »
            BABIH 2  X
  S^PT.
              OCT. 1         NOV. 1
                      1969
DEC. 1
             JAN. 1         FEB. 1
                    TIME
                                     MAR. 1
APRIL 1        MAY 1
       1970
JUNE 1
             JULY 1
                                                               FIGURE 6
                                                AERATION  BASIN DISSOLVED OXYGEN
                                                              (ALL DATA)

-------
  99.99
  99.9
to
to
ui
DC
o

o
O
LU
m
O
a:
o.
    99
    95
   O.I
  0.01
                           DISSOLVED OXYGEN-BASIN 1 (MG/L)
                                 FIGURE 7
               PROBABILITY OF DISSOLVED OXYGEN - BASIN 1

-------
ay .yy
QQ Q
AA
QQ
< on
i
1-
W
_J
DC
O7n
o
H so
3 50
O
m 40
£
x_ qn
> 30
_i
mon
<
CO
0
DC
Q. in




C
¥
ht,










Jt
s




) C
a
i •-









4
X





> •-
? E










X





* »•
• *
i a








4
r
i
/






• i-
- a
•a o







<
I
/







• *.
» •-
i>






^
t X
^"







J ^
Q
J •-






)
X








» ^
i a
Q





>
i
( ^









3 (j
0 i-
n ci
















i) C
a
9 (1





^^^i










t t
i a
a -




^^











a <
S J




X)











>. «
i 0
- Cl



x
S )











>• •»
n a
n a



^












0
So
0


X
^^ <












1 Cl
i :


X
q












*'
n a
3 2


X
*












i!
1 0
y iv
c


X













D a
3 Q
n o

x
^













l> Ol
1 U
3 OJ
         DISSOLVED OXYGEN - BASIN 2 (MG/L)
                  FIGURE 8
PROBABILITY OF DISSOLVED OXYGEN - BASIN 2
                     29

-------
BASIN 2
R.S. "~
BASIN 1
20%
BASIN 2
80%
BOTH R.S.
BASIN 1-33%
BASIN 2-67%
BOTH R.S.
BASIN 1
20% BS.
"* BASIN 2
80% R.S.
BASIN 1
DOWN
~" BASIN 2
R.S,
BASIN 1 R.S.
J BASIN 2 DOWN *
BASIN 1 DOWN
* BASIN 2 R.S.


BASIN 1
FT.
BASIN 2
DOWN
                         SYSTEM UPSET
                         BULKING DUE
                         TO LOW D.O.
                                                               SYSTEM UPSET
       BULKING DUE
       TO LOW D.O.
                                                                                                                 SYSTEM
                                                                                                                  UPSET
BULKING
DUE TO
LOW D.O.
o_
z:
LJ
03
                KCT
             BASIN 1   »
             MtBIN 8   X
 S?PT.
               OCT. 1
                             NOV. 1
                                          DEC. 1
                       1969
JAN. 1           FEB. 1
       TIME
                                                                                   MAR. 1
                                                                                                APRIL 1        MAY 1
                                                                                                        1970
                                                                                                                             JUNE 1
                                                                                                                                          JULY 1
                                                                   FIGURE 9
                                                            BASIN TEMP. VS. TIME
                                                                  (ALL DATA)

-------
yy
In
QO

on


Cfl

A. n
an
on

1U
2

• 1
rti
fv
a













X


> it
> C.













^


) Cl
? r»












xl



i a
> v* o











• jt.
'



» -
n a











s,




1 0
9 »•










jt
/,




3 C
»










^ i





3 J
h V









x
r \
t
t
\





n c
o
J C








/
r ^
\





n a
a i
3 C







S
r «
4
r






n c
^ 0
a c






^
/
; 3







n c
n c
i> t






/
3
r







I I
3 ft





r )










n c.
o c
3 «




J
X^










3 S
n a




X











s ?
a >•



t
, X
Sr











n c
9 (1
- 4


i
*
X












s ?
1. V


^
^
y













! 8
4 e


X













? *
3 U
           TEMPERATURE BASIN 1 (°F)
              FIGURE 10
PROBABILITY OF TEMPERATURE - BASIN 1
                 31

-------
»•»»
QQ a

99
96
yu

Cn

A ft
^fi
on
i n

i •
0. I
0.01
0
















i r













X



















» V












/
/


j a











^
/



> c











X




n o
3 >-











''




! ?










X





1 0
) *









X






1 '








/
'






u °
fl •-







/
J







1 ) T
> U



^












) 1
> a


,>
^1












•> a
i a


X













1 -J
) a

•
X













> a
> (c
                                 O)
                                           
-------
Aeration basin pH variations  are shown on  Figure  12.  Figure  13  shows that about 35
percent of the time, the  pH of Basin 1 was equal to, or above, 8.0, which is normally
considered the top of the normal  operating range for an activated sludge  system. This
occurred in Basin  2 about 25  percent of the time (Figure 14), but neither basin appeared
to be directly affected by  the high pH.
CC>2 production in the aeration basins during organic material breakdown buffered the
high alkalinity in the influent and resulted in a pH drop. This is illustrated on Figure 15.
The average influent pH was 9.3 and the average effluent pH was 7.8. Many of the high
basin pH levels were associated with low values of organic removal, which were caused by
mechanical aerator problems.

The aeration basin SVI  (sludge volume  index) variations are shown on Figure 16. SVI
levels  above 200  correspond to sludge  bulking  and  corresponding  reduced process
efficiencies.

Influent and effluent BOD  variations are shown on Figure  17. Figure  18  shows that
weekly average  BOD and  COD reductions decreased during periods of sludge bulking.
Sludge  bulking  was  associated with  mechanical  aerator  failures,  which lowered  the
available D. O. in the  aeration basins below desirable levels.

Figure  19  shows that the BOD removal  was 82 percent, or greater, 50  percent of the
time. The average BOD removal for the entire demonstration period was 80 percent, even
though numerous mechanical problems limited operating efficiency much of the time.

Analysis of three periods of effective operation, two about one month long each, and one
about  two months long,  with  the plant  operating  as  a return sludge activated sludge
system,  has provided  several operating  relationships.  These relationships are described
hereinafter and  are based on weekly average data unless  noted otherwise. The three
periods of optimum operation,  analyzed  in detail, were: 14  September - 4 October, 23
November - 20  December, and 1  March 22 April.  The   referenced figures  include
least-square curves fitted to the plotted data  by computer. Figures  without average data
reference are plotted from available daily  data.

The effect of average BOD  loading  (Ib  BOD/lb  MLVSS/day)  on  percentage of BOD
removal is shown on  Figure 20. Figure 21 shows the effect of this same BOD loading on
effluent  BOD  concentration. As the BOD loading  increased,  the effluent  BOD  appeared
to  increase, while  the BOD removal  remained  above 94  percent.  Figure 22 shows
substrate removal [(influent  BOD-effluent  soluble BOD)/influent  BOD] versus BOD
loading  for all  data.  Substrate removal was above   90   percent  during  the entire
demonstration  period,  including sludge  bulking  periods,  and  effluent soluble BOD
remained below 125 mg/1 (Figure 23).
                                       33

-------
BASIN 2
US. *~
BASIN 1
20%
BASIN 2
80%
JOTH H.S.
BASIN 1-33%
BASIN 2-67%
BOTH R.S.
BASIN 1
20% ns.
* BASIN 2
80% R.S.
BASIN 1
DOWN
* BASIN 2 *
RS.
BASIN 1 R.S.
* BASIN 2 DOWN *
BASIN 1 DOWN
"* BASIN 2 R.S. *~


BASIN 1
F.T.
BASIN 2
DOWN
                    SYSTEM UPSET
                    BULKING DUE
                    TO LOW D.O.
                                                           SYSTEM UPSET
       BULKING DUE
       TO LOW D.O.
                                                                                                             SYSTEM
                                                                                                              UPSET
BULKING
DUE TO
LOW D.O.
           KEY
        BASIN 1   *
        M81N 8   X
. i
          OCT. 1
                        NOV. 1
                                      DEC. 1
                  1969
JAN. 1          FEB. 1        MAR. 1
       TIME
                                                                                            APRIL 1        MAY 1
                                                                                                    1970
            JUNE 1
                          JULY 1
                                                            FIGURE 12
                                                        BASIN pH VS. TIME
                                                            (ALL DATA)

-------
  99.9
    99
    95
^  90
ui
DC   *^0
O
O   60
v  >
5S
    30
_J  20
m
CQ
g  10
CL
   O.t
  O.D:
      •    at   6>   o    c»   to
                <7>   -J   ~J    Ut    CO   25   <3    a   Q   •-    "'!O   IV}    Ctf   CO   «»    *-   VI
      en   en
                                                PH BASIN 1
                                              FIGURE  13
                                   PROBABILITY  OF pH  BASIN  1
                                                  35

-------
QO -WW

99
9o
90
OU
>-
*"" sn
i— • Oil
_l
•— • i «=n
m 50
mvn
o
a: 30
Q_ 3°
on
% n

>
)
O.i
0.01
C














^
t

r> G














? *
/

i>













y
^

j













^
X


4













S


J
•












^



J












^^^ ^
^ 4



J











^r \




4










I/





J









y






4








j
/






4







/>
/







4






^
^ ^








4





/










4 0
•





X










1) 0




>/)











8 0
•

•


'











0 0


1
X












a a
•
—
1
i>
h ^













a a
       pH - BASIN 2
        FIGURE 14
PROBABILITY OF pH BASIN 2
           36

-------
BASIN 2
R.S.
BASIN 1
20%
BASIN 2
80%
3OTH R.S.
BASIN 1-33%
BASIN 2-67%
BOTH R.S.
BASIN 1
20% R.S.
BASIN 1
80% R.S.
BASIN 1
DOWN
^ BASIN 2 *"
R.S,
BASIN 1 R.S.
BASIN 2 DOWN *"
BASIN 1 DOWN
BASIN 2 R.S.


BASIN 1
F.T.
BASIN 2
DOWN
                      SYSTEM UPSET
                      BULKING DUE
                      TO LOW D.O.
                                                          SYSTEM UPSET
                                             BULKING DUE
                                             TO LOW D.O.
                                                                                                          SYSTEM
                                                                                                           UPSET
                                                      BULKING
                                                      DUE TO
                                                      LOW D.O.
              KEY
           INFLUENT +
           EFFLUENT X
SJEPT. 1
OCT. 1         NOV. 1
       1969
                          DEC. 1
JAN. 1          FEB. 1
       TIME
                                                                MAR. 1
                                                                                          APRIL 1        MAY 1
                                                                                                 1970
JUNE 1
             JULY 1
                                                            FIGURE  15
                                               PLANT INFLUENT AND EFFLUENT PH
                                                              (ALL DATA)

-------
BASIN 2
R.S. *"

BASIN 1
20%
BASIN 2
80%
BASIN 1-33%
BASIN 2-67%

BASIN 1
20% R.S.
BASIN 2
80% RS.
BOTH R.S. BOTH R.S.





SYSTEM UPSET
BULKING DUE
TO LOW D.O.




BASIN 1
DOWN
"" BASIN 2 *"
R.S.
BASIN 1 R.S.
* BASIN 2 DOWN *

BASIN 1 DOWN
* BASIN 2 R.S.






SYSTEM UPSET
BULKING DUE
TO LOW D.O.
SYSTEM
UPSET
BULKING
DUE TO
BASIN 1
F.T.
BASIN 2
DOWN





LOW D.O.
                     KEY
                  M8IN 1  »
                  BASIN 8  X
ui
oo
     >o
     (Of-
       §.
       sBr. i
                   OCT. i
                                 NOV. 1
                                             DEC. 1
                           1969
JAN. 1          FEB. 1       MAR. 1        APRIL 1        MAY 1         JUNE 1        JULY 1
       TIME                                   1970
                                                                     FIGURE 16
                                                                    SVI VS TIME
                                                                    (ALL DATA)

-------
BASIN 2
R.S. *
BASIN 1
20%
BASIN 2
80%
3OTH R.S.
BASIN 1-33%
BASIN 2-67%
BOTH R.S.
BASIN 1
20% R.S.
BASIN 2
80% R.S.
BASIN 1
DOWN
~" BASIN 2 *~
R.S,
BASIN 1 R.S.
* BASIN 2 DOWN *
BASIN 1 DOWN
* BASIN 2 R.S. *~


BASIN 1
F.T.
BASIN 2
DOWN
                            SYSTEM UPSET
                            BULKING DUE
                            TO LOW D.O.
                                                                 SYSTEM UPSET
                                BULKING DUE
                                TO LOW D.O.
                                                                                                                SYSTEM
                                                                                                                 UPSET
BULKING
DUE TO
LOW D.O.
vo
       HPT. 1
                    OCT. 1
NOV. 1
             DEC. 1
                         JAN. 1
                                       FEB. 1
                                                  MAR. 1
                           1969
                                                                 TIME
                                                               APRIL 1        MAY 1
                                                                      1970
                                                                                                                           JUNE 1
                                                                                                                                       JULY 1
                                                                    FIGURE 17
                                                          INFLUENT AND EFFLUENT BOD
                                                                   (ALL DATA)

-------
BASIN 2
" R.S. *

BASIN 1
n, *>* ^
BASIN 2
80%
BASIN 1-33%
BASIN 2-67%

BASIN 1
20% R.S.
* BASIN 2
80% R.S.
BASIN 1
DOWN
* BASIN 2 *~
R5,
BASIN 1 R.S.
BASIN 2 DOWN

BASIN 1 DOWN
" BASIN 2 R.S.




BOTH R.S. BOTH R.S.





SYSTEM UPSET
BULKING DUE
TO LOW D.O.





SYSTEM UPSET
BULKING DUE
TO LOW D.O.
SYSTEM
UPSET
BULKING
DUE TO
BASIN 1
FT.
BASIN 2
DOWN





LOW D.O.
CO
_i
0.
UJ


o
UJ
o
cc
QC
UJ
  S?PT. 1
              OCT. 1
                           NOV. 1
                                        DEC. 1
                     1969
JAN. 1          FEB. 1

       TIME
                         MAR. 1
                                                                                          APRIL 1       MAY 1

                                                                                                 1970
                                                                                                                    JUNE 1
                                                                                                                                JULY 1
                                                               FIGURE 18


                                                 AVERAGE ORGANIC REMOVALS VS TIME

                                                               (ALL DATA)

-------
99.9
99
95
90
80
70
60
50
40
30
20
10
S
1
0.1
3 01













X






























_x*
^"














X^















X^














X
p














x^






























jXl















x^














x3
1













X
t
X














\^^^^














4















^














»<*
9^














X)














^
J
X













*

x^










"*"** f* * 01 (II C/l 05  0) -3 ^J -J 00 CD CD O> (0 CD U
        AVERAGE BOD REMOVAL (%)
             FIGURE 19
PROBABILITY OF AVERAGE BOD REMOVAL
                41

-------
K)
cr

o
z:
UJ
cc

o
o
m

UJ

cr
O£
           3
            0.0
                  °'flVERflGE BOD LOflDINO (LB BOO/LB MLVSS/OflY)
                                                                                        0.8
                                         FIGURE 20
                        AVERAGE BOD REMOVAL VS. AVERAGE BOD LOADINGS

                                       SELECTED DATA

-------
 a
 a _
 w
a
o
to'

I—
z
UJ
23
_l
u.
u.«
UJc




-------
  o
  o
/•^ 10
^^


_J
cr

o
UJ
t—
GC
ce
t—

-------
BASIN 2
* R.S. *

BASIN 1
^ 20% f
BASIN 2
80%
BASIN 1-33%
BASIN 2-67%

BASIN 1
20% R.S.
BASIN 2
80% R.S.
BASIN 1
DOWN
** BASIN' 2 *
R.S,
BASIN 1 R.S.
* BASIN 2 DOWN *

BASIN 1 DOWN
BASIN 2 R.S.




BASIN 1
FT.
BASIN 2
DOWN
BOTH R.S. BOTH R.S,





SYSTEM UPSET
BULKING DUE
TO LOW D.O.





SYSTEM UPSET
BULKING DUE
TO LOW D.O.
SYSTEM
UPSET
BULKING
DUE TO




LOW D.O.
  o
  8
00

UJ
_I
00
tn-
 S?PT. 1
OCT. 1         NOV. 1

       1969
                         DEC. 1
JAN. 1         FEB. 1

       TIME
                                                            MAR. 1
APRIL 1       MAY 1
       1970
                                                                                                               JUNE 1
                                                                                                                           JULY 1
                                                          FIGURE 23
                                                    EFFLUENT SOLUBLE BOD
                                                          (ALL DATA)

-------
Figure 24 shows the effect of BOD loading as Ib BOD/1,000 cu ft/day on BOD removal.
As  the BOD loading increased, the  BOD removal appeared to decrease slightly. MLVSS
concentrations are  not considered in  this  relationship.

Increased  coliform bacteria  reduction  was achieved through the  activated sludge system
with  increased  basin liquor  temperature (Figure  25). Results show  that the  system is
capable of significant coliform count reduction. Effluent coliform  concentrations averaged
3.9 x 107 per ml.

Figures 26 and 27 are  related to secondary  clarifier operation.  Increased  MLSS levels,
with  corresponding higher solids  loading to the secondary clarifier, normally resulted in
increased effluent suspended solids levels. Both figures have second-order curves.

Figure 28 shows  that  better secondary  clarification would  have reduced  the effluent
BOD. During periods of effective operation, SVI variations between 100 and 200 did not
affect the effluent  suspended solids (Figure 29).

Total phosphate and total nitrogen removal variations with time are shown on Figures 30
and 31. Decreased  removal efficiencies coincide with periods of sludge bulking and loss of
bacterial cells in the secondary clarifier effluent.

Figures 32 and 33 show BOD removal and substrate removal (soluable BOD) versus BOD
loadings while Basin  1  was operated as a flow-through aeration basin without secondary
clarification. The difference  in the two removal curves on  each figure represents the BOD
of the suspended solids in the basin effluent.

Limited  chlorine  breakpoint testing of the plant effluent provided a breakpoint  range
from  14 to 18 mg/1 and an average of 15  mg/1.

The average effluent characteristics during effective activated  sludge treatment are  listed
below:

          pH = 8.0
          Temperature = 16.4 degrees C.
          Suspended Solids = 160 mg/1
          COD = 380 mg/1
          BOD = 85  mg/1
          Soluble BOD = 40 mg/1
          Chlorine Breakpoint = 15 mg/1

Additional effluent relationships are located in Appendix C.
                                       46

-------
2=
LU
o
o
CD

LU
o
a:
a:
  S
               20           40           60           80

                     flVERfl&E BOD LORDING  (LB/1000 CF/DflY)
too
120
                                      FIGURE 24


                   AVERAGE &UU REMOVAL VS AVERAGE BOD LOADING

                                   SELECTED DATA

-------
  o
  o
  to
  to
—'10
CC w
cc


n
oc
  CM
  a
            x     x
   64
56
59
60         62         64

BflSIH  TEflPERflTURE  (F)
66
                                          FIGURE 25
                          BASIN TEMPERATURE VS COLIFORM REMOVAL

                                         (ALL DATA)

-------
  o
  p.,
O
r:
UJ
Ci>
C£
o:
UJ
  CM
               50
                           100          150          200
                               RVERfl&E EFFLUENT TSS
250
            300
                        350
                                    400
                                              FIGURE 26
                               AVERAGE MLSS VS AVERAGE EFFLUENT TSS
                                           SELECTED DATA

-------
T
50
100          150          200
AVERAGE EFFLUENT TSS I1&/L)
250
                                               300
                                                           360
                            FIGURE 27
       AVERAGE CLARIFIER LOADING VS. AVERAGE EFFLUENT TSS
                         (SELECTED DATA)

-------
  o
  o
  CM
  O
  «D

CD
Z
UJ
UJ
o
a:
a:
UJ
               50
100          150         200          250

     flVERfl&E  EFFLUENT TS3  (M&/U
300
                                                                                     350
                                                                                                 400
                                               FIGURE 28
                            AVERAGE EFFLUENT BOD VS. AVERAGE EFFLUENT TSS
                                            (SELECTED DATA)

-------
  o
  o
  o
  u>
  CM
  O
  a

  CM
CO
a:
oz.

HJ
>
CL
  o
  o
  o
  in
               —i—

               50
—i	1	1	1	

 100          150          200          250

         HVERH&E EFFLUENT  TSS  IM&/LJ
300
            350
                        400
                                              FIGURE 29
                               AVERAGE SVI VS. AVERAGE EFFLUENT TSS

                                           (SELECTED DATA)

-------
BASIN 2
R.S. *"

BASIN 1
20%
B

ASIN 2
80%
BASIN 1-33%
BASIN 2-67%

BASIN 1
20% R.S.
BASIN 2
80% R.S.
BASIN 1
DOWN
"" BASIN 2 *"
R.S,
BASIN 1 R.S.
* BASIN 2 DOWN *~

BASIN 1 DOWN
BASIN 2 R.S.




BASIN 1
FT.
BASIN 2
DOWN
BOTH R.S. BOTH R.S.




SYSTEM
SYSTEM UPSET
BULKING DUE
TO LOW D.O.




SYSTEM UPSET
BULKING DUE
TO LOW D.O.
UPSET
BULKING
DUE TO




LOW D.O.
<

O
  S?PT. 1
OCT. 1         NOV. 1
       1969
                         DEC. 1
JAN. 1         FEB. 1
       TIME
                                                                            MAR. 1
APRIL 1        MAY 1
       1970
                                                                                                                   JUNE 1
                                                                                                                                JULY 1
                                                              FIGURE 30
                                               TOTAL PHOSPHATE  REMOVAL VS. TIME
                                                             (ALL DATA)

-------
BASIN 2
R.S

BASIN 1
-. 20% .
BASIN 2
80%
BASIN 1-33%
BASIN 2-67%

BASIN 1
20% R.S.
BASIN 2
80% R.S.
BOTH R.S. BOTH R.S.





SYSTEM UPSET
BULKING DUE
TO LOW D.O.




BASIN 1
DOWN
"* BASIN 2 ""*
R.S,
BASIN 1 R.S.
"* BASIN 2 DOWN *



SYSTEM UPSET
BULKING DUE
TO LOW D.O.
BASIN 1 DOWN
BASIN 2 R.S.





SYSTEM
UPSET
BULKING
DUE TO
BASIN 1
F T
BASIN 2
DOWN





LOW D.O.
o
IE
LLJ_

OS
o
oc
o
•-s
                     NO DATA COLLECTED DURING THIS PERIOD OF TIME
 S?PT.
             OCT. 1         NOV. 1

                    1969
DEC. 1
            JAN. 1         FEB. 1

                  TIME
                                                                         MAR. 1
APRIL 1
            MAY 1
                         JUNE 1
                                    JULY 1
                                                                                            1970
                                                     FIGURE 31
                                           NITROGEN REMOVAL VS. TIME
                                                    (ALL  DATA)

-------
                                     SUBSTRATE
  g-
Oo,
Q
O
CO
cc

CO
CO
Z>
CO
                                     BOD
  o
  10
   3.000
0.090       3.150        0.240       0.920       0.400
    BOO LOflDINO  (LB  BOO/LB  MLVSS/OflY)
0.480
                                FIGURE 32
                SUBSTRATE AND BOD REMOVAL VS. BOD LOADING
                           FLOW-THROUGH DATA

-------
  o _
  o
  at
Q
O
CO
Q
2
< ?
LU
CO
D
CO o
  to
  a
  10
                                                SUBSTRATE
                                                                •BOD
              49          12          16         20
                 BOO LOflOINO  (LB  BOO/1000  C.F./OflY)
                                                                   24
                               FIGURE 33
              SUBSTRATE AND BOD REMOVAL VS. BOD LOADING
                        (FLOW - THROUGH DATA)

-------
VELOCITY PROFILES-Velocity measurements were  made  in the aeration  basins with
three different aerator arrangements. An example of velocity profiles obtained is shown
in plan  view  on Figure  34 and in section on Figure 35. Additional velocity profile plots
are located in Appendix G.

Measurements were made from a raft with a propeller type current  meter and counter
made by A.  Ott. The velocity profile is meaningful for evaluating possible minimum or
maximum  velocities in the given areas of the basins during operation.  Each  of the
aerators has  a nameplate  horsepower of 50  and an  impeller  pumping rate  of  23,500
gallons  per minute at a power draw of 67 amperes. The aerator power use during the
testing is provided on the figures. Some  minor scour was noted in the high velocity and
turbulence  areas at the ends  and sides of Aeration Basin 1  after about two months of
operation  without a  plastic liner. The scour was  6 to 8  inches deep  and was located
primarily in the wave  action zone.

DISSOLVED OXYGEN PROFILES-Dissolved  oxygen measurements  were taken in the
aeration basins at  various  depths with four different aerator location configurations. The
dissolved oxygen readings were obtained with a YSI field  probe and  meter from a raft.
Figures  36 through 39 show dissolved oxygen profiles  for the basins with power loadings
from about 90 to 245 hp per million gallons of aeration basin mixed  liquor. Dissolved
oxygen  profiles, at 2-foot and  6-foot  depths  of Basin 1  with 9  aerators, are shown  on
Figures  38 and 39, respectively. A  section profile taken  through these plan profiles is
included as Figure 40.  Other dissolved  oxygen profiles are located  in Appendix G. The
power use for each aerator is given on the figures.

The dissolved oxygen distribution shown on Figures 38 through  40 was fairly uniform.
Having  one  of nine  aerators  out of  operation does  not appear to have affected the
dissolved oxygen distribution in the basin at the time of the measurements.  If the  aerator
out  of  operation  had been at the  end of the basin,  the effect  might have been more
noticeable.

OXYGEN UPTAKE RATES—Oxygen uptake studies were conducted  on grab samples of
aeration basin  mixed liquor.  The  oxygen  uptake  tests were conducted by  placing the
sample  in a  BOD bottle, mixing with a magnetic  stirrer, and using  a  YSI BOD bottle
probe. Dissolved oxygen values obtained during  the first 60 seconds and below 1.0 mg/1
were  discounted in determing  the slope of the oxygen uptake plot. Plots of dissolved
oxygen  depletion with time are included in Appendix G. The oxygen  uptake  rates varied
from 0.06  to 0.26 mg ©2 per day per mg MLVSS with corresponding temperatures of
11.3 and 15.5  degrees C.  These uptake rates are described in more detail in  Section  11.
                                       57

-------
4 JUNE 1970
    x    VELOCITY READINGS
         IN FEET PER SECOND
         AERATOR NOT IN OPERATION
                                                 PROFILE AT 3 FOOT DEPTH
                                                                         POWER = 66 HP/MILLION GALLONS
         AERATOR WITH OPERATING
         HORSEPOWER DURING TEST
                                                                                               FIGURE 34
                                                                                       THE R. T. FRENCH COMPANY
                                                                                           SHELLEY,IDAHO

                                                                                          VELOCITY PROFILE
                                                                                                BASIN 1
                                                                                            3  AERATORS

-------
4 JUNE 1970
                                                     SECTION A-A
    VELOCITY READINGS IN
 x   FEET PER SECOND
                                                                                         FIGURE 35

                                                                                   THE R. T. FRENCH COMPANY
                                                                                      SHELLEY, IDAHO

                                                                                     VELOCITY PROFILE
                                                                                          BASIN 1
                                                                                        3 AERATORS

-------
30 MAY 1970

POWER -  94 HP/MILLION GALLONS
25
           SCALE IN FEET
                   s~*\
                    50
25          50
  I

   AERATOR WITH OPERATING
   HORSEPOWER DURING TEST
                                                   PROFILE AT 2 FOOT DEPTH
X  DISSOLVED OXYGEN
   READINGS IN MG/L
                                                                                                      FIGURE 36
  THE R. T. F-HtNI-n UWrrrrrMM T
      SHELLEY,IDAHO

DISSOLVED OXYGEN PROFILE
          BASIN 2
        6 AERATORS

-------
30 MAY 1970
                                                   PROFILE AT 2 FOOT DEPTH
           AERATOR WITH OPERATING
           HORSEPOWER DURING TEST
           DISSOLVED OXYGEN
           READINGS IN MG/L

        =  91 HP/MILLION GALLONS
            FIGURE 37

  THE R. T. FRENCH COMPANY
      SHELLEY, IDAHO

DISSOLVED OXYGEN PROFILE
          BASIN 1
         3 AERATORS

-------
30 MARCH 1970
   X   DISSOLVED OXYGEN READINGS
      IN MG/L
      AERATOR NOT IN OPERATION
OXYGEN UPTAKE = 0.06 MG 02/DAY-MG MLVSS
                                                                            POWER
                                                                                           243 HP/MILLION GALLONS
  50 )  AERATOR WITH OPERATING
      HORSEPOWER DURING TEST
                                                                                                 FIGURE 38

                                                                                          THE R. T. FRENCH COMPANY
                                                                                               SHELLEY,IDAHO

                                                                                       DISSOLVED OXYGEN PROFILE
                                                                                                  BASIN  1
                                                                                               9 AERATORS

-------
30 MARCH 1970
  X   DISSOLVED OXYGEN READINGS
      IN MG/L
      AERATOR NOT IN OPERATION
      AERATOR WITH OPERATING
      HORSEPOWER DURING TEST
PROFILE AT 6 FOOT DEPTH
                                                                                                FIGURE 39
 25
                      25
                                50
           SCALE IN FEET
                                       THE R. T. FRENCH COMPANY
                                            SHELLEY, IDAHO

                                     DISSOLVED OXYGEN PROFILE
                                                BASIN 1
                                            9  AERATORS

-------
30 MARCH 1970
                                                    SECTION B-B
    DISSOLVED OXYGEN
  X READINGS IN MG/L
FIGURE 40
                                                                                 THE R. T. FRENCH COMPANY
                                                                                    SHELLEY,IDAHO

                                                                               DISSOLVED OXYGEN PROFILE
                                                                                        BASIN 1
                                                                                      9 AERATORS

-------
SOLIDS TREATMENT AND HANDLING

CLARIFIER-THICKENER-The clarifier-thickener  was used to clarify silt water and a
mixture  of  silt  water  and  waste  activated  sludge.  The  primary  function  of  the
clarifier-thickener is  to remove most  of the abrasive silt from the silt water. Influent silt
water suspended solids varied from 1,050 mg/1 to 72,640 mg/1 and  averaged 13,240 mg/1.
Suspended solids removal from the silt water is shown on Figure 41. Influent silt water
BOD  varied from 75 mg/1 to 2,730 mg/1 and averaged 770 mg/1. BOD removal is a side
benefit and is shown on Figure 42.

Total suspended solids  removals  have approached 100 percent with silt water  alone
flowing through  the clarifier-thickener.  The  average  suspended solids removal was  72
percent.  COD and  BOD  removals approached 80  percent. The  noticeable variations in
suspended  solids removal and BOD  removal  are primarily the result  of poor underflow
pump performance which prevented  frequent solids  withdrawal. Waste activated sludge
discharge   to  the  clarifier-thickener  also hindered  silt settling  and reduced removal
efficiencies. Preliminary coagulation studies were conducted on clarification of silt water
alone, and on a combination of silt water and waste activated sludge. Anionic polymers
improved  clarification   of  silt  water  alone,  and   cationic  polymers   improved  the
settleability of  a  mixture of silt water  and  waste activated sludge during  bench scale
testing;  however, limited full-scale testing has not  been very successful to date. Further
testing is  presently being conducted to optimize waste activated sludge-silt water mixing
and polymer dispersion. Waste activated sludge was  normally bypassed  to the river.

The  thickening capability of the clarifier-thickener is shown on Figure 43. The underflow
solids level reached  about 48 percent before being transferred to  the vacuum  filter for
dewatering. Polymer additions increased the thickened solids concentrations.

VACUUM  FILTRATION-The solids concentration of  the clarifier-thickener underflow
averaged about 48 percent and the vacuum filter cake averaged 62 percent solids without
coagulants (Figure 43). When an anionic polymer was added to the silt water entering the
clarifier-thickener, the underflow solids increased to about 53 percent and the filter cake
solids increased  to about 72  percent. The addition of waste activated sludge  directly to
the vacuum filter, while attempting to use the silt as a  filter precoat, was not successful
because the waste activated sludge only tended to wash off part of  the silt cake, resulting
in overall thinner sludge cakes. Spraying  waste activated sludge on a preformed silt cake
also resulted in thinner cakes.

The dewatered solids cake became more concentrated with more dilute clarifier-thickener
underflow  solids  concentrations;  however, the dewatered cake  was thinner, resulting in
lower filter loading rates.
                                        65

-------
  o
  o _
> s

O


LU
DC
OC

LLJ
  O .
  «
  SEPT. 1
               OCT. 1
                            NOV. 1
                                         DEC. 1
                                                      JAN. 1
                                                                    FEB. 1
                                                                               MAR. 1
                                                                                           	1	

                                                                                            APRIL 1
                                                                                                         MAY 1
                                                                                                                       JUNE 1
                                                                                                                                   JULY 1
                      1969
                                                             TIME
                                                                                                   1970
                                                                FIGURE 41
                                                      AVERAGE  TSS REMOVAL VS. TIME

                                                          (CLARIFIER - THICKNER)

-------
                                                                            WASTE ACTIVATED SLUDGE ADDED •
      §
o\
-a
     DC


     Q

     O
     CO



     3°
    LU
      O
      CM
       EPT. 1
                  OCT. 1
                               NOV. 1
                                           DEC. 1
                                                       JAN. 1
                                                                    FEB. 1
                                                                               MAR. 1
                         1969
                                                                                           APRIL 1
                                                              TIME
                                                                                                  1970
                                                                                                        MAY 1
                                                                                                                     JUNE 1
                                                                                                                                 JULY 1
                                                           FIGURE 42
                                                AVERAGE BOD  REMOVAL VS. TIME

                                                    (CLARIFIER - THICKNER)

-------
       g
ON
00
     z
     UJ
     CD
     o
     og-
     o
     
-------
DEWATERED  SOLIDS HANDLING-The dewatered  silt solids  were very acceptable as
landfill. During the 1969-70 processing season,  most of the waste silt solids were used to
fill  in  low areas  around the plant  site.  Excess waste  silt solids  were hauled to a local
sanitary landfill. This practice has been  continued  during the 1970-71 processing season.
                                       69

-------
                                   SECTION  IX
                             OPERATING PROBLEMS
MECHANICAL PROBLEMS

Numerous  mechanical  problems  were encountered  at  the  secondary waste  treatment
facility, and as a result, problems developed within the biological and physical treatment
processes.  Some  of the major  mechanical  problems are discussed below, along with
attempted solutions to these problems.

AERATION BASINS-The  following listed problems were encountered with equipment
and materials used with the aeration basin:

1.   The  Hypalon  basin-top Lining would not  stay  below the water surface  and, as a
     result, it  caught in the wind and tore in several places. Pieces of the lining caught in
     the aerators. The problem was solved by removing the remaining lining and replacing
     it with a  rock surface.

2.   The  PVC basin linings failed and pieces of the linings caught in  the aerators. The
     linings were replaced  and  covered with rock on the  basin bottom and on the side
     slopes in  the wave action area.  Basin 1 lining failed again near the beginning of the
     1970-71  processing  season, but the  extent of the failure will not be assessed until
     the processing plant shuts down in June.

3.   The  floating  mechanical aerators frequently:  (1) overdrew amperage and shut off,
     (2)  had   bearing   failures,   and (3)  developed  loose  hardware.   The  aerator
     manufacturer determined that these  problems were the result  of high velocity axial
     flow entering the  aerator intake. The manufacturer recently installed an intake cone
     with a baffle plate in  the  center of  the intake  on each of the aerators, which
     appears to have solved the problems.

SECONDARY CLARIFIER   WASTE SOLIDS PUMP-The sludge withdrawal mechanism
rotation  was jerky until the seals were adjusted  and additional structural  bracing was
installed.

The waste  sludge pump  became inoperable when the waste sludge line had become filled
with sand from grout  on the clarifier bottom.  The problem  was solved by  replacing  the
pump stator and cleaning the waste sludge line.
                                       70

-------
CLARIFIER-THICKENER-Frequent  clarifier-thickener  underflow  pump  breakdowns
resulted in excessive silt concentration in the bottom  cone, and hardened silt prevented
rotation of the rake mechanism.  A silt recycle system  was installed to allow frequent silt
removal and rubber scrapers were installed on  the rakes to limit the reoccurrence of this
problem. The underflow pump manufacturer provided air chambers for  the suction and
discharge sides of the pump to relieve excessive pump strain; however, breakdowns still
occur, and additional analysis is planned to eliminate this problem.

VACUUM FILTER—Several problems encountered with the vacuum disc  filter are listed
below:

1.   The rubber scrapers did not remove the solids  cake from the cloth media. Stainless
     steel media  with plastic  scrapers were  installed to remedy this problem. This has
     proven successful.

2.   Limited funds required housing  the vacuum filter in the control building. This has
     resulted in  a  noisy  control building and laboratory.  Placing the exhaust muffler
     underground relieved the external noise and resident complaints. Internal noise will
     be reduced to an acceptable level with insulation.

3.   Dewatered silt and sludge conveying was hampered by excessive wear of the screw
     conveyor  hanger bearing  and stub  shaft. A  new  belt  conveyor  was installed to
     replace the screw conveyor.

PROCESS PROBLEMS

Problems encountered in the activated sludge process have been primarily  associated with
sludge bulking. This has occurred several  times and appears  to be related to frequent
aerator problems, with accompanying large fluctuations in D. O. levels. Recycling of
waste  activated sludge  through  the  clarifier-thickener, where removal  efficiencies  were
poor, resulted in increased aeration basin suspended solids levels and reduced D. O. levels.
Increased  D. O. levels  and  reduced  influent BOD  to basin  MLVSS  ratios have  been
successfully  used to  eliminate the bulking sludge when  it  appeared; however,  the last
occurrence  of bulking sludge (last part of April) was  not controlled by these methods. At
the close of the processing season, a  sludge sample was sent to nearby Ricks College and
was  reported  to  contain  a filamentous fungus (Appendix E). Subsequent pilot plant
studies indicated  that the fungus can be controlled with  a fungicide, potassium  sorbate,
and  that it  can be eliminated by starvation (continuous aeration without food) in less
than two weeks.
                                       71

-------
Foaming has occurred  on the aeration  basins  at low MLSS  levels, but  has not  been a
problem at MLSS levels above 2,000 mg/1 and a D. O. above 1.5 mg/1.

Addition of  an  anionic polymer  to  the  silt  water,  ahead of the clarifier-tlu'ckener, has
improved  the  silt   removal efficiency.  Polymers have not  been  found  effective  on
full-scale,  combined waste activated  sludge-silt  water clarification and  thickening in the
clarifier-thickener.  Preliminary  laboratory testing with  cationic polymers has,  however,
looked promising. Additional coagulation testing is  being conducted at this time under
the sponsorship of the Potato Processors of Idaho Association.
                                        12

-------
                                   SECTION  X
                          FINANCIAL  CONSIDERATIONS
CONSTRUCTION COSTS

The  total capital  cost for construction of the secondary wastewater treatment facility was
$598,105. A detailed cost breakdown is presented in Appendix F. About 28 percent, or
$167,000,  of this  cost is estimated  to be attributable  to providing additional facility
capabilities to carry out the demonstration project.

OPERATION AND  MAINTENANCE COSTS

The  first  season's   operation  and  maintenance  costs  for  the secondary wastewater
treatment facility were  $93,212. A detailed cost  breakdown is provided in Appendix  F.
Approximately 22  percent ($20,950) of the  total operation  and maintenance costs are
estimated to  be the  result of  the  first-year  demonstration project, which required
additional sampling, testing, supervision, and data  analysis.

Reported solids disposal costs  were low during  the  1969-70 processing season because
most of the waste silt solids were used to fill in low areas around the plant site and waste
activated sludge was discharged to the river. Waste silt solids are being hauled to a local
sanitary landfill this year  for a cost of  $1,000 per month or about $3.30 per cubic yard.
Disposing of the waste activated sludge and  all  of the  silt  by this method during the
1969-70  season would have cost about $14,000 more than the reported costs. This would
have resulted in a total operating and maintenance cost of about $86,300, excluding the
first-year demonstration costs.

Michael [8] reported annual  operation  and maintenance  costs for activated sludge plants
(secondary treatment only)  sized for a population equivalent of 85,300  people (14,500
pounds of BOD per day) to range from  $80,000 to $400,000 per year. The average
reported  cost was $180,000 per year. On the basis of a season lasting about 9 months,
these reported  figures  would  range  from  $60,000  to  $300,000,  with  an  average  of
$135,000. These  costs were reported  for 1965-67 and should  be increased by at least  15
percent to arrive at comparable  1969-70 costs. The updated  cost range  would be  from
$69,000  to  $345,000, with an  average  of  $155,000  per season.  The  operation and
maintenance  costs at R. T. French during  the 1969-70 processing season, excluding the
demonstration expenses, were  about $72,300  (Appendix  F), which  is on the low end of
the range reported for municipal activated sludge plants.
                                       73

-------
TOTAL ANNUAL COSTS

Total  annual treatment  costs can be shown to be equal to the sum of:  (1) annual capital
amortization  costs  (7   percent  interest  for  20 years),  (2)  annual  operation  and
maintenance costs, and  (3) equipment replacement and depreciation costs (5 percent  ot
equipment capital cost). Table 5 contains treatment cost estimates for the demonstration
year (1969-70  season) with  and without the demonstration  costs. On the basis of these
elements, the  unit treatment costs of the  demonstration year were about  $0.049 per
pound of BOD  applied, or  $0.027  per  pound of COD applied.  The estimated  costs,
excluding demonstration costs, are  $0.038  per pound  of BOD  applied, or  $0.021 per
pound of COD applied. Both season's unit  cost estimates are based on the waste load
during the 1969-70 season, or 3,335,000 pounds of BOD and 6,064,000 pounds of COD.

                                   TABLE  5
                       SECONDARY TREATMENT  COSTS

                                                              ESTIMATED
                                        TOTAL                 1969-70
                                        1969-70            SEASON WITHOUT
              ITEM                    SEASON            DEMONSTRATION
Construction Cost                        $598,105                $431,379

Amortized Capital Cost
(7% - 20 years)                             56,500                  40,700

Annual Operation & Maintenance Cost         93,200                  72,300

Estimated Equipment Replacement &
Depreciation (5% of Equipment Cost)          15,000                  15,000
Total Annual Cost                        $164,700                $128,000

Estimated Cost of Treatment

   (3,335,000 Ib BOD/year)        $0.049/lb BOD Applied    $0.038/lb BOD Applied
   (6,064,000 lb COD/year)        $0.027/lb COD Applied    $0.021/lb COD Applied


These total annual  cost estimates are lower than  costs reported  for activated sludge
treatment of fruit processing wastes [9].  Activated sludge treatment of fruit wastes were
estimated to  be $0.061 per pound  of BOD removed  or  $0.048  per pound of COD
removal. Assuming 95 percent BOD removal and 90 percent COD removal, the reported
costs would be  S0.058 per pound of BOD applied or $0.043 per pound of COD applied.
                                     74

-------
The  lower unit cost at  R. T. French is probably due to the greater annual  organic load
experienced.  Lower unit treatment  costs are frequently associated with systems receiving
larger waste loads.

Adding   extra sludge disposal  costs  ($14,000) to the estimated 1969-70  total annual
costs at R. T. French, without demonstration  costs,  would result in unit treatment costs
of $0.043 per pound of BOD applied and $0.023 per pound of COD  applied.
                                       75

-------
                                   SECTION  XI
                                   DISCUSSION
ACTIVATED SLUDGE SYSTEM

MICROBIOLOGY—Treatment system operation was the most efficient when the activated
sludge  contained  a high population of  stalked ciliates  and a moderate  population  of
free-swimming ciliates.  Some  filamentous growth  was  usually present in the sludge;
however, during periods of efficient operation, it was present only in limited quantities.
These findings are in agreement with the findings of many other researchers  [1,2,10,11].
Photomicrographs of the activated sludge  during normal operation and during  periods of
sludge bulking are shown on Figure 44.

Ciliates  which were  identified  in the activated sludge include  Vorticella  microstoma,
Vorticella campanula,  Lionotus species, and Paramecium. The best effluent was produced
when Vorticella campanula was the predominant  Vorticella.

During extended periods of low dissolved oxygen, filamentous growth, either bacteria or
fungi,   seemed  to  dominate   the  activated  sludge  as   shown   in   the   left-hand
photomicrograph of Figure 44.

SUBSTRATE  REMOVAL-The  substrate  utilization equation presented in Section V is
shown below:
If the total weight of BOD removed per day per unit weight of MLVSS is plotted against
the effluent soluble BOD, the slope of the first order curve  passing through (0,0) will be
equal to the BOD removal rate coefficient, k. Figures 45, 46, and 47 are plots of BOD
removal versus effluent soluble  BOD at the three temperature ranges in which the system
operated when  working efficiently. The  lines were passed through (0,0)  and the  mean
coordinates. Figure 46 has considerable scatter, which is not unusual  for field data.

Figure 48 is  a  semi-logarithmic plot of the BOD removal rate coefficient, k, versus the
average  basin temperatures obtained from  the  figures described  above. The equation of
the straight line  can be  used  to determine BOD removal rate coefficients at various
temperatures. The equation is:

          k - 0.016 x 1.1
                                       76

-------
                     \*t*£?t''Z&i£*ftt
                   W.>$$^   1
                   fc-^>*-.-^.-        '-2
                                      ir
                  *-*,'         •  ^•
                  &('    •-••. •.;.?:•
             FILAMENTOUS ACTIVATED SLUDGE

                       (100X)
IB4435.3
                                                                        t-f ~~-
                                                                        i*   •-
                                                                              .
                                                                        H  '

                                                                       ^   &^:


                                                                                 A^cy*!*  \;«.
NORMAL ACTIVATED SLUDGE

        (100X)
                                                                                 FIGURE 44



                                                                   PHOTOMICROGRAPHS OF ACTIVATED SLUDGE

-------
                 o
                 o
               «•—» •
               CO-
               CO
               CD
               Q
               \
               UJ
oo
CO"?
ODO


CO

CD
_J



ujS
               cc.
               >
               o
               Zio
               UjW
               0:0

               UJ
               I—
               cc
               a:
               >—
               co_
               QQ§

               S-.
                                                                0.0048
                                        40          60          80          100
                                         EFFLUENT SOLUBLE BOD  WG/L)
                                                                     120
140
                                                   FIGURE 45
                                  EFFLUENT SOLUBLE BOD VS. SUBSTRATE REMOVAL
                                        TEMPERATURE  EQUALS 50 TO 56 °F
                                                (SELECTED DATA)

-------
                 co
                 <0
                 DO
                 o
                 \
                 IU
                 I—
                 oc
                 ce
                 CQO

                 ID
                 CO


                 03
-o
                 ceo

                 UJ
                 t—
                 a:
                 cc
0.0082
                                         40         eo          so          too
                                           EFFLUENT SOLUBLE B3D  (flQ/LJ
                ISO
                           140
                                                   FIGURE 46
                                  EFFLUENT SOLUBLE BOD VS. SUBSTRATE REMOVAL
                                        TEMPERATURE EQUALS 58 TO 60 °F
                                                (SELECTED DATA)

-------
OC
o
                 co
                                         40         50         80         100
                                          EFFLUENT SOLUBLE  BOD  (fIG/L)
120
                                                    FIGURE 47
                                    EFFLUENT SOLUBLE BOD VS. SUBSTRATE REMOVAL
                                          TEMPERATURE EQUALS 61 TO 63 °F
                                                  (SELECTED DATA)

-------
     0.020
UJ
a:
     0.010


     0.009

     0.008


     0.007



     0.006



     0.005




     0.004
DC
I-

£    0.003
D
C/3
     0.001
                  ky =  0.016 x 1.17 (T'20>
                                                         0.016
                                        LOG "  0.0189 = 1.17
                       5            10            15

                          BASIN TEMPERATURE (°C)
                                                              20
                                FIGURE 48
             SUBSTRATE REMOVAL RATE VS. TEMPERATURE
                                      81

-------
SLUDGE  YIELD-An  equation expressing net  sludge  yield  in  a  completely  mixed
activated sludge system was presented in Section V and is repeated below:

          AXV = fSQ + aSr  bXd

This equation shows  that  the  net  change in average MLVSS concentrations  should be
equal to the sum of the non-biodegradable volatile suspended solids in  the influent plus
the volatile  fraction of biological cells  produced while removing  BOD from  the waste
material, minus the volatile fraction of the biological cells used in endogenous respiration.

The fraction of volatile suspended  solids in plant influent, which  is not degradable, has
been assumed to be negligible, resulting in the following equation:

          AXv = aSr  bXd

A  plot of  net volatile suspended solids produced per  day,  AXy, per unit  weight of
MLVSS versus the quantity of BOD removed per day, Sp per unit weight of MLVSS was
made for each of two temperature ranges with enough data to plot a first-order curve
(Figures 49  and 50).  Even then, the field data included sufficient scatter to require prior
knowledge  of  the  direction  that  the  straight  line  should be  plotted. Both  sets of
temperature  data represented about the same sludge age range, and as  a result, straight
lines with the same slope,  a, seemed  to fit both sets of data. The sludge synthesis yield
coefficient,  a, is shown as 0.88. The Y-axis intercept,  which is equal to net sludge growth
at zero BOD removal or the rate of endogenous respiration (auto-oxidation) per day, b,
was different in each case.

Figure 51 is a semi-logarithmic  plot of the endogenous respiration rate, b, versus average
basin temperature. The data for the two points  shown on Figures 49  and 50, and the
semi-logarithmic plot was  chosen because  of the tendency of the  BOD  removal  rate
coefficient versus temperature  plot to  vary  in a semi-logarithmic order, and because of
other reported  experience  [9]  in evaluating  b. The equation  of the straight line plot can
be  used  to determine the  endogenous respiration  rate,  b, at  various temperatures;
however, it  should be  understood that  the variability of field data and  the narrow range
of aeration  basin operating temperatures did not allow verification of this equation over a
wide range of temperatures. The equation is:

          bT = 0.19 x 1.3l(T-2°)

The sludge synthesis yield coefficient, a, presented above is slightly  above other published
data [6,9,11], which indicates the presence of non-biodegradable volatile suspended solids
in the influent.  The  rate  of endogenous respiration,  b,  corresponds  to other published
                                        82

-------
                o
                ID
              to.
              d
              O
oo
OJ
              0°
              CC
              Q_

              UJ
              O
              O
             0.05 —
0.88
                  .00
0.10        0.20        0.30        0.40       0.50        O.SO
     SUBSTRRTE  REflOVRL  RRTE  (LB  SUBSTRRTE/DRY/LB MLV5S)
                                                    FIGURE 49
               0.10
                                                                                                      0.80
                                    SUBSTRATE REMOVAL VS. SLUDGE PRODUCTION
                                          TEMPERATURE EQUALS 58 TO 60 F
                                                 SELECTED DATA

-------
oo
             o
             11}
           CO
           CO
           to
           CO
           >

           CO
           CJ
           ZJ
           o
           o
           cc:
           o
           :D
           _i
           CO
             o
             o
          0.09-
               .00
                                                              0.88
r0.lO        0.20        0.^0        0.40        O.SO        0.60
     SUBSTRflTE REflOVflL RRTE  (LB  SUBSTRRTE/DRY/LB  fILVSS)


                           FIGURE 50
                                   SUBSTRATE  REMOVAL VS. SLUDGE PRODUCTION
                                        TEMPERATURE EQUALS 61 TO 65 F
                                                 SELECTED DATA
                                                                                           0.70
0.80

-------
    Q.3  -
-Q

LU
I-

cc

z
o

I-

cc

ol
CO
LJJ
QC

CO


o
o
Q
    0.2  -
0.1


0.09


0.08



0.07



0.06




0.05





0.04







0.03 -
    0.02 -
    0.01
                                                      0.19
                    bT = 0.19x1.31 (T'20)
                                              LOG "1 0.116= 1.31
                     5            10           15

                        BASIN TEMPERATURE  (°C)
                                                       20
                             FIGURE 51
        ENDOGENOUS RESPIRATION RATE VS. TEMPERATURE
                                85

-------
data [6,9.11]. but the correlation between b and basin temperature appears high. This is
probably because  the  narrow aeration  basin temperature  range  limited the number of
points  for Figure 51.

Figure  52 shows that net sludge production decreases with sludge age; therefore, systems
operating with a  longer  sludge age will  have  less waste sludge for  disposal.  This  is a
general plot and  does  not include the  temperature variations described above. The net
sludge  production  rates include influent volatile suspended solids and are in agreement
with other data published [6,9,11]  on treatment  of  wastewaters with influent  volatile
suspended solids.

OXYGEN  REQUIREMENTS-The  equation  presented  in   Section V  for  oxygen
requirements is:
          O2 = a1  Sr + b  Xd

System  oxygen uptake rate  data is  included in Appendix G. Plotting the oxygen uptake
rate  (weight of O2 used per day per unit weight of MLVSS) versus the BOD removal rate
(weight of BOD removal per  day per  unit  weight  of MLVSS) provided a first-order
least-square curve (Figure 53). The equation of the curve is equal to the total oxygen use,
the slope of the line is  equal  to a' and the  Y-axis intercept is equal to b , the oxygen
utilization rate when  BOD removal is equal to zero. The coefficient  a1 is  equal to 0.48
and  the coefficient b'  is  equal  to 0.03.  This  plot is for temperatures  between 52 and 60
degrees  F.

The  oxygen requirement equation, with the determined coefficient values, becomes:

          O2 = 0.48 Sr + 0.03 Xd

The  determined  value   of  a1  compares favorably  with  published  data  [9,11].  The
determined value of b  is slightly below the same published data because of the low basin
temperature range.

BOD AND SUBSTRATE REMOVAL RELATIONSHIPS-Data obtained during periods of
efficient operation have  been  analyzed  to determine the effect that certain operating
parameters had on BOD  and substrate removal. The curves are least-square  fits of weekly
average  data  by  computer. Each of  the curves takes  into  consideration only the
referenced variables.

Figure  54 shows that  BOD removal increased  slightly with higher average aeration  basin
dissolved oxygen levels, while operating  between the  range  of  0.6 to  2.8 mg/1 dissolved
oxygen.
                                       86

-------
CO
         Q


         00
         Q


         Q
         UJ

         cc.
         QQ
o




is
oc°
Q.

CO
CO


I-
UJ_
                                                           nit
                                                      AERATION BASIN TEMPERATURE RANGE = 52-65°F
                                                   SLUDGE ROE  (DRY3)
                                                       FIGURE 52
                                           SLUDGE AGE VS. SLUDGE PRODUCTION

                                                    (SELECTED DATA)

-------
     o
     10
   10
   GO
00
CO
_l


UJ
t—o

OCQ

UJ

en
i—
a.
   x
   o
                                                                                          0.48
                                                                           AERATION BASIN TEMPERATURE RANGE = 52-6Q°F
                 0.03
      0.00
                 0-05
                          0.10        0.15        O.£0        0.15         0.33        0.95
                               SUBSTRflTE REflOVRL  RfiTE  (LB SUBSTRflTE/OflY/LB  HLVS3)
Q.40
           0.45
0.50
                                                        FIGURE 53
                                         OXYGEN UPTAKE RATE VS. BOD REMOVAL

-------
oo
(X

ISM

LU
o:

o
o
CD
                      0.00
                                       X  X
              0.40
0.90        1.20         1.60

        BflSIN 0.0.  (HG/L)
2.00
2.40
2.80
                                                        FIGURE 54
                                     AVERAGE BOD REMOVAL VS. AVERAGE BASIN D.O.

                                                    (SELECTED DATA)

-------
The  average  aeration basin temperature did not appear to affect BOD removal  between
52 and 66 degrees F. (Figure 55).

The  BOD removal seemed  to  increase with higher  pH levels while operating within the
range of 7.4 and 8.2 as shown on Figure 56. This may have been a coincidence.

Figures  57 and 58 show that BOD removal increased only a slight amount with increases
in influent  total  phosphate to BOD and  total Kjeldahl nitrogen to  BOD ratios. This
indicates that the treatment system was not significantly deficient in nutrients.

The  average substrate removal did not appear to be affected by dissolved oxygen over a
wide  range  of  0.7 to 5.1  mg/1  (Figure 59). Higher  BOD removals with higher dissolved
oxygen  levels (Figure 54),  while  substrate  removal stayed about the  same, suggest the
formation of a better settling sludge at  higher dissolved oxygen levels  and subsequent
better final clarification.

Average  basin temperature did not measurably affect  the substrate removal (Figure 60);
however, substrate removal did increase  slightly with  pH (Figure 61) as did the BOD
removal shown  on Figure 56.

The  influent total phosphate to BOD ratio  and total Kjeldahl nitrogen to BOD ratio did
not affect the substrate removal (Figures 62 and 63), indicating  that sufficient  nitrogen
and phosphates were available. These two  plots are based on available daily data.

The  average BOD:N:PO4  ratio of  the  plant  influent was  100:6.2:1.1.  This  ratio  is
generally considered adequate.

HEAT   LOSS   RELATIONSHIPS-Figure   64   shows   plant   influent  and   effluent
temperatures. The difference in  the two plots is the heat loss throughout the plant. This
net heat  loss can be analyzed by plotting the heat lost  from the aeration basins versus the
heat added to the aeration  basins. The heat lost from the basins has been reported [13]
to be  related to  the  surface  area of the  basins  and  to the  temperature  differential
between  the basin  contents and the surrounding air. This relationship can be expressed by
the following equation:

         HL -    hL(TW-TA)A

where:   H^ =    heat lost from aeration basins
         !IL -    heat loss coefficient
         Tyy =    temperature  of aeration basin liquor, degrees F
         TA =    air temperature, degrees F
         A   =    aeration basin surface area, square feet
                                        90

-------
 a
 a _
  to
  at
  s
CO
  IA

  CD
                             X      X



                             X
X   X



               X



                  X
     	1	1	1	1	1—

   50          53          56          59          62          65

                             BRSIN  TEMP  (F)
                               FIGURE 55




           AVERAGE BOD REMOVAL VS. AVERAGE BASIN TEMP.

                          (SELECTED DATA)

-------
  g
  U> .
  a>
cn

l§

LU
Ct

O
o
CO
  o .
  CD
   7.3
              7.4
                          7.5
                                      7.6
                                                 7.7          7.8

                                                   BflSIN  PH
7.iJ
           S-0
                       R.I
                                                   FIGURE 56
                                 AVERAGE BOD REMOVAL VS. AVERAGE BASIN pH

-------
UJ
cc

o
o
oo
  «0
   0.000       0.100        0.200       0.900       0.400       0.500        0.600        0.700       0.800        0.900

                                               P/BOO   *lCr




                                                FIGURE 57



                             AVERAGE BOD REMOVAL VS. AVERAGE POd/BOD

                                           (SELECTED DATA)

-------
  0 _
LU
o:

a
o
CD
   0.04
O.OS
O.OB
  0.07

N/BOO
                                              0.08
0.08
                                                      0.10
                                FIGURE 58
                 AVERAGE BOD REMOVAL VS. AVERAGE N/BOD

                             (SELECTED DATA)

-------
  o
  o
tug
a:

tu
K-
cr
oc:
to
cc
a:
UJ
          XXX  XX
                                         XX
                                                       XX
               flVERROE RERfiTION  BflSIN 0. 0.  (J1G/L)
                               FIGURE 59
              AVERAGE SUBSTRATE REMOVAL VS. AVERAGE D.O.

                              (ALL DATA)

-------
                         O
                         O
o\
CL

O
z:

ce

LU(
i—
cc

t—

CD
23

  t
IU

cn
a:
LU
                         to
                         «o
                           50
                                               flVERfl&E BflSIN  TEMP (F)'
                                                       FIGURE 60
                                   AVERAGE SUBSTRATE REMOVAL VS. AVERAGE BASIN TEMP.
                                                       (ALL DATA)

-------
UJ
I—

  A
   7.3
7.4
7.6
7.6         7.7         7.8
  RVERflGE  BflSIN  PH
7.9
9.0
8.1
                                           FIGURE 61
                          AVERAGE SUBSTRATE REMOVAL VS. AVERAGE pH
                                           (ALL DATA)

-------
          g
00
        o
        z:
        UJ
        a:
        GC
        te.
        i—
        (O
        CD
        23
        (O
         8
                           X  X X
          •0.000
o.oso
                                    0.100
                                                 0.150
                                      0.200
                                    P04/BOD



                                    FIGURE 62
                                                                           .250
                                                                                       0.900
                                                                                                   0.360
                                                                                                                0.400
                                                                                                                            0.450
                                             SUBSTRATE  REMOVAL VS. PO4/BOD

-------
  o _
O
z:
LU
cc
ct:
OO
3
to
  1C
   0.00
0.02
0.04
  0.06
N/BOD
0.08
0.10
0.12
                                  FIGURE 63
                        SUBSTRATE REMOVAL VS. N/BOD
                                  (ALL DATA)

-------
o
o
     CL
     a:
     UJ
                                      INFLUENT
                                             EFFLUENT
                                                                                                                 JUNE 1
          . 1
                  OCT. 1
                              NOV. 1
                                          DEC. 1
                         1969
JAN. 1         FEB. 1
      TIME
                                                                             MAR. 1
                                                                                         APRIL 1
                                                                                                     MAY 1
                                                                                                                             JULY 1
                                                                                                1970
                                                              FIGURE 64
                                           PLANT INFLUENT AND EFFLUENT TEMPERATURES
                                                             (ALL DATA)

-------
The heat added to  the  aeration  basins has been reported [13]  to  be related  to  the
influent flow volume and to the temperature differential between the influent flow and
the basin contents. This relationship can be  expressed with the equation:
where:    Hj  =    heat added to aeration basins
          hj  =    heat addition coefficient
          Tj  =    temperature of aeration basin influent, degrees F
          T^- =    temperature of aeration basin liquor, degrees F
          Q   =    aeration basin influent flow, mgd

Assuming that the heat lost from  the  basins is  equal  to  the heat added to them,  the
following equations result:
              hL   (TrTw)Q
          h=~h7 = (Tw-TA)  A

The heat loss coefficient, h, is  directly related to  the heat added to the  aeration basins
and inversely related to the heat lost from the basins. Therefore, as the heat loss increases
(with other variables remaining the same), the heat loss coefficient decreases.
Plotting (T-yy - TA) A versus (Tj - T^y) Q will provide a straight line with a slope equal to
h. Figures 65  and 66 are similar plots in accordance with the above discussion for two
detention times at one hp per million gallon ratio. The lines were passed  through (0,0)
and  the  mean coordinates of daily data. The effect of detention time is shown by the
lower heat loss coefficient, h, and higher aeration basin heat loss with a longer detention
time. Similar plots at higher hp per million gallon ratios are located in Appendix H. The
water surface  areas of Basin  1 and Basin 2 are 17,850 square  feet and 30,370 square feet,
respectively,  at design  water level.  The  air  temperatures used  are  averages  of the
maximum and minimum  daily temperatures and the influent and basin temperatures are
actual average temperatures.

The  slopes of the  straight lines shown  on the figures mentioned above are plotted versus
average aeration basin detention  times  on Figure 67. The hp per million gallon ratios are
shown for each point.  A general curve is shown passing  through the data points and is
assumed  to be  asymptotic at each axis, h  is shown to  decrease with longer detention
                                        101

-------
O
K)
                   cv
                 Q
                 O
                                                                     2.32 X 10"'
                                                            44 TO 84 HP/MILLION GALLONS


                                                            AVERAGE AIR TEMP. RANGE = 24 TO 62°F
                                         fl(TH-Tfi)
(100.000 SO  FT-FJ
                                                                                        18
                                                     FIGURE 65
                                       AERATION BASIN HEAT LOSS RELATIONSHIP
                                           2 TO 3.5 DAYS DETENTION TIME

-------
                Q

                (D
o
(Jj
                                                                                       1.64 X 10"'
                                                               44 TO 84 HP/MILLION GALLONS


                                                               AVERAGE AIR TEMP. RANGE = 15 TO 57°F
                                         R(TW-Tfl)
(100,000 SO  FT-F)
                                                                                        18
                                                     FIGURE 66
                                       AERATION BASIN HEAT LOSS RELATIONSHIP

                                           3.5 TO 6.5 DAYS DETENTION TIME

-------
  10 •
 . 8-
O
CO


8
O

o"
O


Q
  6-
          103-185 HP/MG  X
O 4-
      211-243 HP/MG  x
                                      X103-185 HP/MG
UJ

O
O

CO
CO

O
  2-
uu
I
                           44-84 HP/MG  *
                                                                   44_84 HP/MG
                                         3            4

                                    DETENTION TIME (DAYS)




                                          FIGURE 67
                AERATION BASIN HEAT LOSS COEFFICIENT VS. DETENTION TIME

-------
times. The temperature differential between the basin liquor and the air appears to have a
stronger  effect on h  than the hp per million  gallon ratio. This is  shown by the  lower
values of h at 44 to  84  hp per million gallons (with high temperature differentials) than
at 103 to 185 hp per  million gallons with low  temperature differentials.

Figure 67  can be used for design purposes to determine approximate h values for design
detention times. The  equation  for h,  which was presented above, can then be solved for
the basin  liquor temperature,  T^. Additional work  should be performed  to obtain  a
clearer understanding  of  the effects of hp per million gallon ratios and other variables not
considered during  this project,  including  the  effect of heat loss through the sides  and
bottom of a basin, the effect of wind  velocity, and the effect of solar radiation.

SECONDARY   CLARIFIER   LOAD ING-Section  VII  includes   secondary  clarifier
operational data,  which show  that effluent suspended solids and BOD  values  are
somewhat  related  to  clarifier loading, which,  in turn, is dependent upon the MLSS  and
the flow rate  to the  clarifier. The ability  of the clarifier to settle and compact the solids
applied  to it  is a function of the SVI of the MLSS, as  well as the solids loading. The
higher the SVI  value is, the lower the settleability of  the mixed liquor. When the SVI
increases  to   a  point of  clarifier  overload,  the  MLSS load must be  decreased  in
compensation, by increasing the rate of sludge  wasting.

Figure 68  is a plot of MLSS versus (Q + ROJSVI,  using different symbols for good  and
poor operation. Q represents total plant influent and R is the quantity of return sludge as
a  fraction  of  total plant influent.  A straight line  is drawn between the good data  and
poor data. Good secondary clarification can be predicted by operating the system so that
the coordinates  of (Q + ROJSVI and  MLSS  fall below  the line.  Acceptable operation
allows lower (Q  + ROJSVI values for increased MLSS levels.

SOLIDS TREATMENT AND DISPOSAL

WASTE  ACTIVATED   SLUDGE  CHARACTERISTICS-A sample of waste activated
sludge was concentrated, analyzed, and found to contain  and exhibit the following listed
materials and characteristics:

       pH                                                               6.6
       Moisture                                                       94.5%
       Protein                                                          1.9%
       Fat                                                           0.02%
       Fiber                                                          0.16%
       Ash                                                            1-64%
       NFE (Nitrogen Free  Extract)                                     1.78%
       TON (Total Digestible Nutrients)                                 2.7%
                                        105

-------
  o
  o
C3o
-2
                                                           * OBOO 8PCBATIOM
                                                           + POOH OPtRATtOM
                         A *
              10
                         20
40          50         SO
 MLSS  (M&/L)    »10*
80
                                                                                                        90
                      100
                                                    FIGURE 68
                                  SECONDARY CLARIFIER  LOADING FACTOR VS. MLSS
                                                    (ALL DATA)

-------
       Calcium                                                       0.25%
       Phosphorus                                                   0.051%
       Iron                                                        0.0028%
       Sodium                                                      0.099%
       Pesticides                                              None Detected

A laboratory report on this analysis is located in Appendix F.

The protein content of the waste activated sludge amounted to 34.5 percent of the total
solids, indicating that it may have a nutrition value high enough to allow use in animal
feed.

The heat  value, or calorific value, of the waste activated sludge was found to be 5,200
Btu per pound of  total  solids or 9,020 Btu per pound of volatile solids. The volatile
solids value is about 10 percent below values reported for dairy waste  sludge, pulp and
paper waste sludge, and domestic sewage activated sludge [12].

TREATMENT SYSTEM SOLIDS-The variation of the average VSS to TSS ratio through
the treatment  system is listed below:

       Location                                                    VSS/TSS
       Plant Influent                                                   0.70
       Aeration Basins                                                  0.70
       Final Effluent                                                   0.52
       Return Sludge                                                   0.74
       Waste Sludge                                                    0.74

The BOD to VSS ratio of the plant influent solids was 0.49, while the same ratio for the
plant effluent solids was 0.55 and did not appear to be dependent on sludge age.
                                       107

-------
                                SECTION XII
                            ACKNOWLEDGMENT
This project was supported in part by Research and Development Grant WPRD 15-01-68,
Program 12060 EHV, from the Environmental Protection Agency.
                                    108

-------
                                 SECTION  XIII
                                 REFERENCES
 1.  Hawkes, H. A., Ecology  of Waste Water Treatment, Pergamon Press, New York,
    N. Y. (1963).

 2.  McKinney, R. E., Microbiology for Sanitary Engineers, McGraw-Hill Book Co., New
    York, N. Y. (1962).

 3.  Weston,  R. F.,  and Eckenfelder, W.  W.,  "Application of Biological  Treatment to
    Industrial Wastes,  I. Kinetics  and Equilibria  of Oxidative Treatment." Sewage and
    Industrial Wastes, 27, 802 (1955).

 4.  McKinney,  R.  E., "Biological Design of Waste  Treatment Plants."  Presented at
    Kansas City Section of ASCE Seminar, Kansas City, Mo. (1961).

 5.  McKinney, R. E.,  "Mathematics of Complete Mixing Activated Sludge." Jour. San.
    Engr. Div., Proc. Amer. Soc. Civil Engr., 88, SA3,  87 (May 1962).

 6.  Eckenfelder, W. W., "Comparative  Biological Waste Treatment Design." Jour. San.
    Engr. Div., Proc. Amer. Soc. Civil Engr., 93, SA6,  157  (December 1967).

 7.  Lawrence,  A. W.,  and McCarty,  P.  L.,  "Unified Basis  for Biological  Treatment
    Design and Operation." Jour. San. Engr. Div.,  Proc. Amer. Soc.  Civil Engr., 96, SA3,
    757 (June  1970).

 8.  Michel, R.  L.,  "Costs and Manpower  for Municipal Wastewater Treatment  Plant
    Operation  and Maintenance,  1965-68." Jour. Water Poll. Control Fed., 42,  1883
    (1970).

 9.  Snowkist Growers, Inc.,  "Aerobic Treatment of  Fruit Processing Wastes." Report
    No. DAST-8, U. S. Dept.  Interior, Fed. Water  Quality Admin. (1969).

10.  Sawyer, C. N., "Bulking  of Activated Sludge  and Related Problems." Proceedings of
    Seminar at the University of Michigan, 185 (February 1966).

11.  Eckenfelder, W. W., "A Theory of Activated Sludge Design for Sewage." Proceedings
    of Seminar at the University of Michigan, 72 (February 1966).
                                       109

-------
12.   Eckenfelder.  W. W._.  and  O'Connor, D. J., Biological  Waste  Treatment,  Pergamon
     Press, New York. N. Y. (1961).

13.   Eckenfelder,  W. W.,  "Design  and Performance  of  Aerated  Lagoons for Pulp and
     Paper Waste Treatment." Proc.  16th  Ind. Waste  Conf., Purdue Univ., Ext. Ser. 109,
     115  (1962).
                                      110

-------
SECTION XIV
APPENDIXES
       111

-------
APPENDIX A

-------
                                 APPENDIX  A
                                  GLOSSARY
Some of the various terms frequently used in conjunction with wastewater systems and
referred to throughout this report are defined  as follows:

ACCLIMATION—Period  during which the microorganisms become  accustomed to  then-
new environment and substrate.

ACTIVATED SLUDGE—A biological mass produced in  wastewater  by the  growth of
bacteria and other microorganisms in the presence  of dissolved oxygen, and accumulated
in sufficient concentration by returning floe previously formed.

ACTIVATED SLUDGE  PROCESS-A method of secondary  wastewater treatment in
which a mixture of wastewater and activated sludge is agitated and aerated. The activated
sludge   is subsequently  separated from  the treated  wastewater  (mixed  liquor) by
sedimentation, and wasted or returned to the process as needed.

AERATION—The bringing about of intimate  contact between air and liquid  by one of
the following methods: spraying the liquid in the air, bubbling air through the liquid, or
agitation of the  liquid to promote surface absorption of air.

AERATOR—A device which agitates the liquid and brings fresh surfaces of liquid into
contact with the atmosphere,  thereby introducing atmospheric oxygen into the liquid by
mechanical means.

AEROBIC  TREATMENT—A  biological treatment  process in which  bacteria  stabilize
organic matter in the presence of dissolved oxygen.

ANAEROBIC TREATMENT-A biological treatment process in which bacteria stabilize
organic matter in the absence of dissolved oxygen.

AVERAGE DAILY FLOW-The average quantity of wastewater reaching a given point in
a 24-hour period.

BIOCHEMICAL OXYGEN DEMAND  (BOD)-A measure of the oxygen necessary to
satisfy  the requirements  for  the  aerobic decomposition  of the decomposable  organic
matter in a liquid  by bacteria.  The standard (BOD 5) is five days at 20 degrees C.
                                      A-l

-------
BIOLOGICAL SEED-Sludge  that  has  undergone decomposition which is mixed with
undecomposed wastewater for the  purpose  of introducing favorable organisms, thereby
accelerating the initial stages of decomposition.

BUFFER—The action of certain solutions in  opposing a change of composition, especially
of pH.

CHEMICAL  OXYGEN DEMAND (COD)-A  measure of the oxygen required to approach
total oxidation of the organic matter in the waste.

CLARIFIER-A tank or basin, in which wastewater is retained for a sufficient time, and
in which  the  velocity of flow is sufficiently low to remove by gravity a part of the
suspended matter.

COAGULANT—A chemical, which, when  added to water  or  wastewater, furnishes ionic
charges opposite  to  those of the  colloidal turbidity particles in the water or wastewater,
allowing the colloidal particles  to come together in the form  of a flocculant precipitate.

COAGULATION-The agglomeration of colloidal or finely divided suspended matter in
water or wastewater by the addition of an  appropriate coagulant.

COMPLETELY  MIXED  ACTIVATED   SLUDGE-Treatment  system  in  which  the
untreated wastewater is instantly mixed throughout the entire aeration basin.

COMPOSITE SAMPLE—Integrated sample collected by taking a portion at regular time
intervals, with sample size  varying  with  flow;  or taking  uniform  portions on  a time
schedule varying with the total flow.

DETENTION TIME—Period  of time  required for a liquid to flow through a tank or unit.

DISSOLVED OXYGEN (DO)-Free or uncombined oxygen  in a liquid.

EFFLUENT—Liquid flowing out of a basin or treatment plant.

FLOC—Small gelatinous masses,  formed  in water or wastewater by  the addition  of
coagulants, through biochemcial processes,  or by agglomeration.

FLOCCULATION—The  bringing  together of  flocculating  particles  by  hydraulic  or
mechanical means.
                                      A-2

-------
INDUSTRIAL WASTEWATER—Flow of waste liquids from industries using large volumes
of water from processing industrial products, such as food processing plants.

INFLUENT—Liquid flowing into a basin or treatment plant.

MILLIGRAMS PER LITER (mg/l)-The weight of material in one liter of liquid.

MIXED LIQUOR (ML)-A mixture of sludge and wastewater in a biological reaction tank
undergoing biological degradation in an activated sludge system.

NITRIFICATION—A biological  process in which certain  groups of bacteria, when in the
presence of dissolved  oxygen,  convert ammonia  nitrogen  first to nitrites and then to
nitrates.

NUTRIENT—Any  substance absorbed  by  organisms  which promotes  growth   and
replacement of cellular parts.

OXYGEN UPTAKE RATE—Oxygen utilization rate or rate at which oxygen is used by
bacteria in the decomposition of organic matter.

PEAK FLOW—The highest average daily flow occurring throughout a period of time.

pH—The logarithm  of the reciprocal  of the  hydrogen ion  concentration.  It is used to
express the intensity of the acid or alkaline condition of a solution.

POLYELECTROLYTES-High  molecular weight  water  soluble  polymers that contain
groups  capable  of undergoing  electrolytic dissociation  to give highly charged,  large
molecular weight ions. Polymers whose functional  groups in  water solution give  positively
charged ions are cationic,  while polymers that dissociate  to form negatively charged ions
are called anionic. Polymers which  dissociate to  yield both  large positive and  large
negative ions are referred to as nonionic.

PRIMARY TREATMENT—A wastewater treatment  process that utilizes sedimentation
and/or flotation  to  remove a substantial portion of the settleable or flotable solids and
accompanying BOD of untreated wastewater.

RETURN SLUDGE—Sludge  which has settled in the final clarifier and is returned to the
biological reaction tank in  an activated sludge system.

SECONDARY   TREATMENT-A   wastewater    treatment   process   that   utilizes
microorganisms to reduce the  oxygen demand and pollutional load of primary treated
wastewater and to remove  the solids resulting from the process.
                                       A-3

-------
SETTLEABLE  SOLIDS-Suspended  solids which  will settle in  sedimentation basins
(clarifiers) in normal detention times.

SLUDGE—The accumulated settled solids separated from  wastewater in clarifiers, and
containing more or less water to form a semi-liquid mass.

SLUDGE AGE-The average  total  time of detention of a suspended solids particle in  a
system. It is defined as the total weight of suspended solids in the aeration basin divided
by the total weight of suspended solids in  the effluent and otherwise wasted per day.

SLUDGE  DENSITY INDEX (SDI)-The  reciprocal  of the sludge  volume index  (SVI)
multiplied by 100.

SLUDGE  VOLUME INDEX  (SVI)-The  volume of sludge occupied by one gram of
activated  sludge after 30 minutes of quiescent settling  in a 1,000 ml graduated cylinder.

SUBSTRATE—Raw waste feed on  which  a microorganism  grows  or  is placed  to grow by
decomposing the waste material.

SUBSTRATE REMOVAL-The total BOD in plant influent, minus the soluble  BOD in
plant effluent, divided by the  total  influent BOD.

SUPERNATANT LIQUOR-The liquid overlying settled  solids.

SUSPENDED SOLIDS  (SS or TSS)-The quantity of material deposited when a quantity
of wastewater is filtered  through an asbestos mat in a  Gooch crucible, or equal method.

TOTAL SOLIDS (TS)—The solids in the wastewater, both suspended  and dissolved.

VOLATILE  SUSPENDED  SOLIDS  (VSS)-The  quantity  of  suspended  solids  in
wastewater that are lost on ignition of the total suspended solids.

WASTE   SLUDGE—Sludge  which  is no  longer  needed  in the  treatment  system and
therefore  is disposed of.

-------
APPENDIX B

-------
     FIGURE B-1
THE R.T. FRENCH COMPANY
    SHELLY, IDAHO

  AERATION BASIN 1

-------
      FIGURE B-2

THE R.T. FRENCH COMPANY
    SHELLEY, IDAHO

  AERATION BASIN 2

-------
     FIGURE B-3
THE R.T. FRENCH COMPANY
    SHELLEY, IDAHO

SECONDARY CLARIFIER

-------
      FIGURE B-4

THE R.T. FRENCH COMPANY
    SHELLEY, IDAHO

  CONTROL BUILDING

-------


      FIGURE B-5

 THE R.T. FRENCH COMPANY
     SHELLEY, IDAHO

CLARIFIER - THICKENER

-------
APPENDIX C

-------
o
o
Si
    1        OCT. 1        NOV. 1
                   1969
                                    DEC. 1
JAN. 1         FEB. 1      MAR. 1
       TIME
APRIL 1       MAY 1
       1970
JUNE 1
            JULY 1
                                                          FIGURE C-1
                                                INFLUENT ALKALINITY VS. TIME

-------
99.09
 99.9
  99
   95

   90

   80

   70
   60
   50
   40
   30

   20

   10
  0.1
 0.01
                              INFLUENT ALKALINITY (MG/L CaCo3)

                                 FIGURE C-2

                    PROBABILITY OF INFLUENT ALKALINITY
                                     02

-------
   99. £
    99.9
2

<
I
W
(/)
oc
o
<


O
01
99










98





90






80








60







40



30




20






10
     0-1
     0.01
        
                                      CO
                                          03(0<0(£{O'"'''p-IH-*-H->-'
0)
to
o   o»   «n
(a   (d   O)
J»   O

Q   O)
en
o
                                                           vj
                                                               CD
                                                                     o   w   —   u>
                                                                     o>   •-   en   o>
                                          INFLUENT pH
                                          FIGURE C-3
                               PROBABILITY OF  INFLUENT pH
                                            C-3

-------
98.99
 99.9
   99
   95





   90






   80




   70



   SO



   50



   40



   30




   20






   10





   5
                                                     >:
                                               /
  o.i
 0.01
        •\>
u)   *-


o   o
en


o
                                                  CO
en   o   *o  *j   QB   oo
>••••«
C0   C/1   •*"  ^   O)   CQ
a   o   a  o   o   a



  INFLUENT TEMPERATURE (°C)
                                                      8
                                              •o
                                              a
                                                  c/i  •-
                                                  o  o
r   ?   ?

a   a   a
O)


a
                                 FIGURE C-4
                  PROBABILITY OF INFLUENT TEMPERATURE


                                    C-4

-------
99.99
99.3
go
95
on
fin
7n
en
^n
A n
Ofl


1U
5'


• 1
Oni
a
4
*














,


D C
». c
•• ^













/
t


tf c
3 <












x
' '
1


3 N
! I












X




§ a
n *










^
X





! 1









t
j ^^^
X





>• c
k >.
D <








^
t
/
/






n c
J U
3 •-







«
t
V
^







s s
. c





4
/










3 ^
3 "
1 -
n




)
X











3 C
f
* t
4 6




J












3 0
3 4
0 <<
0 C



5
/












2 £
3 4
3 A.



X













3 I1
n c
>. c
3 C



X













3 (N
n
n <
o c

















3 £
5 £


x
«













3 £
ii S


i














S S
3 *
D (C
       INFLUENT BOD (MG/L)
         FIGURE C-5
PROBABILITY OF INFLUENT BOD
            C-5

-------
iw.wa
99.9
99
95
90
80
70
60
SO
40
30
20
10
5
1
I3
0.1
0.01











X

t
\













/
\














X
i













X














x1













)
/
^












>
t
V













>
f
t
x













>
/













>
t
/














t
'













\
x






























X















X






























X















X
1 <






























8
                                          2
       INFLUENT COD (MG/L)
         FIGURE C-6
PROBABILITY OF INFLUENT COD
            C-6

-------
99.99
 99.9
 0-01
  0.1
     w
vi   en    o   en
                         INFLUENT SUSPENDED SOLIDS (MG/L)
                               FIGURE C-7





               PROBABILITY OF INFLUENT SUSPENDED SOLIDS



                                   C-7

-------
3
_J
U-
  o
  SEPT. 1
              OCT. 1        NOV. 1
                      1969
DEC. 1
             JAN. 1         FEB. 1       MAR. 1
                   TIME
APRIL 1        MAY 1
       1970
JUNE 1
            JULY 1
                                                             FIGURE C-8
                                                      INFLUENT FLOW VS. TIME

-------
99.99
 99.9
  99
  95

  90

  33

  70

  SO
  50
  43
  30

  20

  10
                      X
                          X
       );
;;
  O.I
 0.01
    o   —
                            TOTAL INFLUENT FLOW
                                FIGURE C-9
                  PROBABILITY OF TOTAL  INFLUENT FLOW
                                   C-9

-------
  g
  g
a
o
o
  S
  S
  a

  g
               400
800
            1200
1600         2000

       BOD IMO/L)
2400
2800
                                                                                                  3200
9600
                                                                                                                         4000
                                                        FIGURE C-10
                                                    INFLUENT BOD VS. COD

                                                         (ALL DATA)

-------
n
a
o
to

UJ
-Jo
03 g
=3*
_J
«D
(O
         g
                      400
                          800
1200        1600        2000
        TOTflL BOO  U1G/U
                                                                              2400
2800
3200
                                                                                                                 3600
                                                        FIGURE C-11
                                            INFLUENT TOTAL BOD VS. SOLUBLE BOD
                                                         (ALL DATA)

-------
    U3
2
io
      §
                   •00
1200
                                           1800
2400         9000

        S3  (MO/L)
9600
4200
                        4800
5400
6000
                                                              FIGURE C-12
                                                         INFLUENT  SS VS. VSS

                                                               (ALL  DATA)

-------
     o
     a
     Si
   ta
   CO
n
                            20
                                       30
40          50          60

   S3  (M&/L)    »10*
                                                                                   70
80
           90
                      100
                                                         FIGURE C-13
                                                       BASIN  SS VS. VSS

                                                         (ALL DATA)

-------
  99.(
   99.9
    99
    96

    90

    80

    70
    60
    50
    40
    30

^   20

    10
      J
     5
                                                                  x
                                                                      X
   0.1
   o.oi
      oo
                                EFFLUENT BOD (MG/L)
                                   FIGURE C-14

                          PROBABILITY OF EFFLUENT BOD
                                     C-14

-------
99.99
 99.9
  0.1
 0.01
                          EFFLUENT SOLUBLE BOD (MG/L)






                                FIGURE C-15





                  PROBABILITY OF EFFLUENT SOLUBLE BOD




                                  C-15

-------
Sj
10 H
§
a
o ,
             100
230
1.00
403         533         600

       BOD K1&/L)
                                                        700
                                                        930
                                                                                                      000
                                                                                          1000
                                                    FIGURE C-16
                                              EFFLUENT BOD VS. COD

                                                    (ALL DATA)

-------
12
           18
24          30          36
    SS (MO/L)   »10*
                                                         42
                                                                    48
                                                                               54
                                                                                           £-0
                          FIGURE C-17
                     EFFLUENT  SS VS. VSS
                          (ALL DATA)

-------
APPENDIX D

-------
                                APPENDIX  D
   SAMPLING  POINTS,  SAMPLING SCHEDULE,  AND TESTING EQUIPMENT
SAMPLING POINTS

 1.  TOTAL  PLANT  INFLUENT-The sample  was taken from  the  influent  pump
    discharge line, downstream  from the influent pump pit, and pumped to the stock
    samplers in the control building. The sample point is shown as S-l on Figure 2.  The
    pump is located in the control building.

 2.  SILT  WATER—The  sample  was  taken   from  the  silt water  line  to  the
    clarifier-thickener,  just  inside   the   control   building   wall  adjacent  to  the
    clarifier-thickener. It flows by pressure to the stock  sampler adjacent to the sample
    point.  The  sample point is shown as S-2 on Figure 2. No pump was used to collect
    this sample.

 3.  CLARIFIED  SILT  WATER-The sample was  taken from  the  bottom  of  the
    clarifier-thickener  effluent launder and pumped to the stock samplers located in the
    control building. The sample point is shown as S-3 on Figure 2.  The sample pump is
    located in the control building.

 4.  AERATION BASIN NO. 2 EFFLUENT-The sample was taken from the aeration
    basin  inlet-outlet structure, near the bottom of  the box just upstream from
    discharge Weir W-3,  and pumped to the stock samplers in the control building.  The
    sample  point is shown  as  S-4  on  Figure 2. The sample pump is located in  the
    control building.

 5.  RETURN  SLUDGE—The sample was taken from  the  recirculation  sludge line,
    downstream from  the valve  and  meter pit, and pumped to the stock samplers in the
    control building. The sample point is shown as S-5 on Figure 2.  The sample pump is
    located in the control building.

 6.  WASTE SLUDGE—A grab sample was taken  from the waste sludge line by opening
    Valve V-13, shown on Figure 2. The sample point is  shown as S-6 on Figure 2.

 7.  FINAL PLANT EFFLUENT-The sample  was taken from the secondary clarifier
    effluent line, just downstream  from  the secondary clarifier, and pumped to  the
    stock samplers in  the control building.  The sample point is shown as S-7 on Figure
    2. The sample pump is located in the control  building.
                                     D-l

-------
 8.  PRIMARY TREATED PROCESS WATER-The sample was taken from the treated
    process water line at the meter manhole just upstream from the  influent pump pit,
    and  pumped  to  the stock samplers in the  control building. The sample point is
    shown as S-8  on  Figure 2, and  the sample pump is located in the control building.

 9.  AERATION BASIN NO. 1 EFFLUENT-The sample was taken  from the aeration
    basin inlet-outlet  structure, near the bottom of the box upstream from discharge
    Weir W-2, and pumped to  the  stock samplers in the control building. The sample
    point is  shown as S-9  on Figure 2. The sample pump is located in the control
    building.

10.  FILTRATE—A grab sample was taken from the filtrate discharge line by opening
    Valve V-19, shown on Figure 2. The sample point is shown as S-10 on  Figure 2.
                                    D-2

-------
           TABLE D-1
SAMPLING AND  TESTING SCHEDULE
     NUMBER OF  TESTS PER WEEK
SAMPLE
POINT
1
9
»
5
7
2
3
10
8
6
TOTAL
PLANT
INFLUENT
AERATION POND
NO. 1
EFFLUENT
AERATION POND
NO. 2
EFFLUENT
RETURN
SLUDGE
FINAL PLANT
EFFLUENT
SILT
WATER
CLARIFIED
SILT
WATER
FILTRATE
PRIMARY
TREATED
PROCESS WATER
WASTE
SLUDGE
o
o
5
5
5
1
5
2
5
1
5
-

CJ
o
CO
2
2
2
-
2
1
2
1
2
-
SUSPENDED SOLIDS
o
5
5
OR
MORE
5
OR
MORE
5
5
3
3
5
5
5
UJ
K
_l
o
1
2
2
5
1
1
1
1
1
-
SETTLEABLE
5
5
5
-
5
3
1
1
5
-
TEMPERATURE
5
CONT.
CONT.
1
5
1
1
1
5
-
o.
CONT.
5
5
1
1
1
1
1
5
-
DISSOLVED
OXYGEN
-
10
10
-
5
-
-
-
-
-
CO
O£.
O
u.
o
o
1
-
-
-
1
1
1
-
1
-
NITROGEN
i—
o
1
1
-
-
1
-
1
-
1
-
CO
0
1
1
-
-
1
-
1
-
1
-
PHOSPHOROUS
1
1
-
-
1
-
1
-
1
-
UJ UJ
o :E x
0 =» LU
=> _l 0
— 1 O Z
CO =*• —
-
5
5
-
-
-
-
-
-
-
i—
0.
CM UJ
O OQ
1
-
1
-
1
-
-
-
1
-
1
en >-
gt
UJ OQ
0 -t
-
-
-
1
-
1
-
-
-
-
MICROSCOPIC
EXAMINATION
-
1
1
-
-
-
-
-
-
-
I
1
1
1
-
-
-
1
-
1
-
Z UJ
UJ *£
O < UJ
X O- 
-------
                                         TABLE D-2
                                    TESTING  EQUIPMENT
          ITEM
1.    INCUBATOR
       CABINET
       TEMPERATURE
         CONTROL
MANUFACTURER


GENERAL ELECTRIC

N-CON, INC.
 MODEL
OPERATING
  RANGE       ACCURACY
                                                                     20° C
                              ±1°C
2.    REFRIGERATOR


3.    pH METER


4.    ANALYTICAL
     BALANCE
GENERAL ELECTRIC


SARGANT


METTLER
   54


H 10TW
                                                                    35° C
   0-14


   0-160g
                                                       ±2°C
±0.05


± 0.0001 g
5.    MUFFLE
     FURNANCE
THERMOLYNE
                                                      F-D1525M
                                                                    550° C
                                                      ±10° C
6    DRYING OVEN
                             NATIONAL
                             APPLIANCE CO.
                                                        420
                                                                    103°C
                                                      ±1°C
7.    VACUUM PUMP
8.    ION EXCHANGE
     COLUMN
GELMAN


BARNSTEAD
                                                       13400
                                                                    20" HG
                                                                                    ± 0.5 "HG
9.    DISSOLVED OXYGEN
     PROBE
       FIELD PROBE
       BOD BOTTLE PROBE
YELLOW SPRINGS
INSTRUMENT CO.
                                                        54
              0-10
              MG/L
                                                                                    ±0.1 MG/L
10.   SPECTROPHOTOMETER
                             BAUSCH & LOMB
                                                      SPEC.-20
11.   PHOTO BINOCULAR
     MICROSCOPE
BAUSCH & LOMB
 PG252
12.   CURRENT METER
A. OFF
                           C1
                                              D-4

-------
APPENDIX E

-------
  .icks  Coll
Ricks   College
   REXBURG.  IDAHO 83440
                                                         >.   Q.UJ
                                                             JOHN I. CLARKE,
BIOLOGICAL SCIENCES
                                               June 13,  1970
   Mr. lynne Sirrins
   The R.T.French Company
   P.O.Box Drawer AA
   Shelley, Idaho

   Dear

   This is a report on our findings of the waste disposal sample which we re-
   ceived from you the week of June 8th.  Our examination of the organism
   you designated has been, a preliminary examination only.

   Our results show that the orgaism is not a bacterium; it is likely a fungus.
   ¥e do not have a ugrcologist on our staff, for this reason we;1 were unable
   to identify the organism for you»

   The bacteria found, which were long filamentous rods, belonged to the genus
   Bacillus. No other long filamentous bacteria were observed.
                                      Kindest personal regards,

                                      Lyle J. Lovder
                                     E-Ji

-------

           *3ta*^t-
f^4-sO*K~'C<^T^
                                                          FROM
THE  R.  T. FRENCH CO.

                SHELLEY, IDAHO
       0
       fi/^
                                 *x_^>'   AS  ,  it -70
MEUACE:
          ^



           ^__.CL<
-------
                               LABORATORY REPORT
LAB. NUMBER     5513                   July 21,  1970
DATE RECEIVED     July 2 ,  1970
            Sample, potato waste:  as received basis
                    pH                           6.6
                    Moisture                     94.5 $
                    Protein                      1.9 ^
                    Pat                          .02 £
                    Fiber                        .16 f
                    Ash                          1.64 %
                    NPE                          1.78 %
                    TISS                          2.7 i°
                    Calcium                      0.25 %
                    Phosphorous                  0.051
                    Iron                         0.0028
                    Sodium                       0.099
            Pesticide residue report will follow.
    r                                          n
                                                                   PHONE 343-783O
           R.  T.  French Co.                         U
           p.  0.  Drawer AA                         ijIBaS
           Shelley,  Idaho    83274                 JABORATORKS
    |_                      ATTN: Mr. K. L.  Sirrjne"'  2808 CASSIA     BOISE'IDAHO e3705
                                         E-3

-------
                               LABORATORY REPORT
LAB. NUMBER   5513                    Feb. 7, 1971
DATE RECEIVED    Sept. 23, 1970
           Waste: Activated  sludge sample from R.I.French,  Shelley,  Idaho:

           Pesticide residue by G.L.C. electron-capture.
           Results: nil
           Pesticides:                      Detection limit
           Standards used                       ppm
           Lindane                              .005
           Aldrin                               .01
           Heptachlor epoxide                   .01
           Dieldrin                             .05
           Endrin                               .05
           DDE                                  .05
           DDD                                  .1
           DDT                                  -1
           Me thoxychlor.                        .2
     r                                          n
           Cornell Howaand Hayes & Merryfield       ij           PHONE 343-7MO
           1600 Western Bird.                       til BBS
           Corrallis,  Oregon                       JABORATOiHCS
     I              ATTH: HZ*. Glen RiChter.      i   Af  aaoe CASSIA     BOISE. IDAHO M706
                                         &4

-------
APPENDIX F

-------
                                 TABLE F-l

                        THE R. T.  FRENCH COMPANY
                                 Shelley, Idaho

                 SECONDARY WASTE TREATMENT FACILITY
                            CONSTRUCTION COSTS
                                       TOTAL
             ITEM                     COSTS

Control Building
  Building, Complete                   $ 33,884.56
  Influent Pumps                        12,768.40
  Influent Pump Wet Well                  8,163.61
  Sludge Pumps                          9,788.25
  Sample Pumps and Samples              17,470.80
  Continuous Temperature Recording       4,705.72
  Laboratory Equipment and Supplies       6,389.19
Flow Metering Equipment                 11,842.85
Aeration Equipment                     87,123.85
Secondary Clarifier and Sludge
Recirculation Station                    51,811.94
Aeration Basin and Miscellaneous
Earthwork
  Earthwork                           18,809.93
  Plastic Sheet Liner                     18,825.00
  Influent Splitter Boxes                  2,322.10
  Outlet Boxes                           3,953.11
  Inlet Header Piping                     6,808.50
  Outlet Piping to Clarifier                 6,146.55
Miscellaneous Outside Piping and
Plumbing
  Sample Lines, Washwater Lines,
  and Hydrants                          5,167.02
  Water Source                           2,312.46
  Sludge Piping                          6,731.04
  Pipe from Waste Solids System              650.00
Gravity Influent from Processing Plant      14,628.45
Gravity Outfall to Existing Storm Sewer
in Fir Street                             13,418.71
      ESTIMATED
  TOTAL COSTS LESS
DEMONSTRATION COSTS
        $ 20,000
          12,768
           8,164
           9,788
          11,843
          50,000

          40,000
          12,000
           8,000
           6,500
           6,000
           2,312
           6,000
             650
          14,628

          13,419
                                       F-l

-------
                           TABLE F-l - CONTINUED
Waste Solids System
  Filter                               $ 30,810.68
  Intercept Silt Water, Screen, Pump,
  and Pipe to Waste Solids System          54,971.38
  Clarifier-Thickener                      29,254.66
  Solids Pump                             1,823.85
  Solids Bunker                            3,419.26
Electrical
  Primary Transformer and Meter            6,499.78
  In-Plant Electrical                      28,693.72
  Electrical Building                        2,464.00
Painting                                    830.70
Gravel Roadway and Parking                 2,491.02
Fence                                     4,404.00
Cleanup and Miscellaneous                   650.00
Move-in and Temporary Facilities             2,300.00
Bond and Insurance                        2,530.00
Design, Engineering, Inspection and
Supervision                              78,135.69
Legal and Administrative                    4,987.60

                  TOTAL             $598,104.94
$ 30,811

  54,971
  29,255
    1,824
    3,419

    6,500
  28,500
    2,464
     500
    2,491
    4,404
     650
    2,000
    2,530

  34,000
    4,988

$431,379
                                         F-2

-------
                                 TABLE F-2

                       THE R. T. FRENCH COMPANY
                                Shelley, Idaho

                 SECONDARY  WASTE TREATMENT FACILITY
                  OPERATION AND MAINTENANCE COSTS
            ITEM
Operating Staff
  Laboratory Technician
  Clerk-Typist
  Chemist-Operator
Professional Staff
Power
Maintenance
  Labor
  Parts
Improvements and Spreading on Site
Solids Disposal
Laboratory Supplies
Operating Supplies
Outside Laboratory Testing
Preparation of Project Reports
Transportation
On-Site Living Expense
Telephone

                   TOTAL
 TOTAL
 COSTS
$ 4,685.14
  3,702.51
  9,718.83
 19,441.53
 23,498.90

  7,647.65
  5,824.17
  6,973.64
  1,,777.69
  5,391.73
  2,227.82
     82.90
   751.59
   556.35
   150.40
   781.61

$93,212.46
      ESTIMATED
  TOTAL COSTS  LESS
DEMONSTRATION COSTS
        $ 4,685.14
         3,702.51
         9,718.83

        23,498.90

         7,647.65
         5,824.17
         6,973.64
          1,777.69
         5,391.73
         2,227.82
            82.90
           730.60
        $72,261.58
                                      F-3

-------
APPENDIX G

-------
     3 JUNE 1970

     POWER = 167 HP PER
            MILLION GALLONS
o
                                                              ^^—	0,5O

                                                          /^   ^	0.46
                            ,0.80
                                                           PROFILE AT 3 FOOT DEPTH
SCALE IN FEET
       AERATOR WITH OPERATING
       HORSEPOWER DURING TEST
                                                X  VELOCITY READINGS
                                                   IN FT. PER SECOND
                                                                                                            FIGURE G-1
THE R. T. FRENCH COMPANY
    SHELLEY,IDAHO

   VELOCITY  PROFILE
         BASIN 2
      9  AERATORS

-------
     3 JUNE 1970
9
to
                                                           SECTION C-C
          VELOCITY READINGS
          IN FT. PER SECOND
        20
                             20
                                       40
                  SCALE IN FEET
        FIGURE G-2

THE R. T. FRENCH COMPANY
     SHELLEY, IDAHO

   VELOCITY PROFILE
        BASIN 2
     9 AERATORS

-------
4 MAY 1970

POWER = 167 HP PER
       MILLION GALLONS
                                                   PROFILE AT 1 FOOT DEPTH
                         AERATOR WITH OPERATING
                         HORSEPOWER DURING TEST
X DISSOLVED OXYGEN
  READINGS IN MG/L
                                                                                                      FIGURE G-3
  THE R. T. FRENCH COMPANY
      SHELLEY,IDAHO

DISSOLVED OXYGEN PROFILE
          BASIN 2
        9 AERATORS

-------
4 MAY 1970
    DISSOLVED OXYGEN
    READINGS IN MG/L
                                               PROFILE AT 6 FOOT DEPTH
                        AERATOR WITH OPERATING
                       HORSEPOWER DURING TEST
                                                                                               IGURE G-4
  THE R. T. FRENCH COMPANY
      SHELLEY, IDAHO

DISSOLVED OXYGEN PROFILE
          BASIN 2
        9 AERATORS

-------
4 MAY 1970
                                                     SECTION D-D
           10      o      10
             EEC
                SCALE IN FEET
           X  DISSOLVED OXYGEN
              READINGS IN MG/L
                              20
           FIGURE G-5


  THE R. T. FRENCH COMPANY
      SHELLEY, IDAHO

DISSOLVED OXYGEN PROFILE
          BASIN 2
        9 AERATORS

-------
O


_J
o
2
z
LU
X
o
Q
LU
_J
O
CO
CO
Q





_
_l
O
5
Z
LU
O
X
o
Q
LU
_l
s
5




-
-
3 -
-
-
~
7 '.
_
-
_
_
1 -

"
-
-
0 "
C


-
-
3 -
-
-
—
2 -



1 -
-
_
0

(

MAR 4 - BASIN NO. 1
ao
0 — — = 64.0 MG/L/HR.
dt
° VSS = 6,470 MG/L

0 02 UPTAKE = 0.24 MG O2/DAY/MG ML VSS
« TEMP = 15.7° C
>Q
^W
^^^
>w
e 0

o
e o

) 100 200
TIME (SEC.)
MAR 9 - BASIN NO. 1
e do
-ft- - 24 MG/UHR.
0 VSS = 2,325 MG/L
° 0_ UPTAKE = 0.25 MG O0/DAY/MG ML VSS
0 4 z
0 TEMP. = 15.0° C
e
0
a>v^
^^"^>te^
0*^5^^^
^^0
o



) 100 200
TIME (SEC.)


J
a
5
Z
LU
0
X
o
Q
LU
_J
O
co
CO
Q





~


Z
LU
CO

X
o
Q
LU

_J
0
8
Q




-
-
3-
-
-
~
2 -
_
-
_
_
1 -

"
-
-
0
C


-
-
3 -
-
-
—
2 .
-


1 -
-
-
0~



MAR 6 - BASIN NO. 1
e do
	 = 48 MG/L/HR.
e dt
0 VSS= 5,100 MG/L

0 0, UPTAKE - 0.23 MG 02/DAY/MG ML VSS
X' - 15.8° C




O
O
o


100 200
TIME (SEC.)
0 MAR 11 - BASIN NO. 1
do
0 -ft- = 36 MG/L/HR.
VSS = 5,950 MG/L
0 02 UPTAKE = 0.15 MG 02/DAY/MG ML VSS
0 TEMP. = 15.0° C
O

N^
^TQL^
^N^k
^^*O
0


'1'IIIITIIII
3 100 200
TIME (SEC.)
                                           OXYGEN UPTAKE DATA
                                                FIGURE G-6

-------
                            MAR 16 - BASIN NO. 1
MAR 18 - BASIN NO. 1
O
-
-
3 3-

2 •
Z
LU
C3 2-
X "
o -
Q "
LU
j 1 -
O -
(/)
Q -
0_
do
a — = 17 MG/L/HR.
& Qt

VSS = 4,950 MG/L
° 02 UPTAKE = 0.08 MG 02/DAY/MG ML VSS
° TEMP. = 12.4° C
e
*"S^Jk
^'•••^^^^
° ^^*^^&"^*^
^9**^*^,,..
^^^""•"•••P




0 100 20
TIME (SEC.)
MAR 19 - BASIN NO. 1
—
—

3 3-
5 -
•
LU •
O 2™
>-
x •
o -
Q •
LU .
_l 1-
O -
c/? —
Q -
o

e do
, = 30.8 MG/L/HR.
dt
0 VSS = 6,300 MG/L
0- UPTAKE = 0.12 MG 0-/DAY/MQ ML VSS
e
e TEMP. = 14.2 C
e
'S^
^^^xc_
^^•^et
^^ 0
o
o

Mlllllllll'l
0 100 20
TIME (SEC.)


^
a
2
Z
LU

X
O
o
LU
^
0
t/5
Q



_
-
3-
-
-
-
2-
-
™
-
—
1-
-
-
-
0_
do
lit"

0 VSS =

38.4 MG/L/HR.

6,450 MG/L
0 02 UPTAKE = 0.14 MG 02/DAY/MG ML VSS
e TEMP.
e
e^
^^^.
^^i^W
o^»
^V^




0 100
TIME (SEC.)
= 13.2° C






&•
&
6 e

i i i i i
200

_, ° MAR 28 - BASIN NO. 1


<«K.
O
2

UJ
O
X.
0
Q
LU
>
o
V)
V)
Q




—
^

3-
-
•
-
2—
:
-
-
_
.
-
0_
do
© — — =
QT
o
o vss =

25.0 MG/L/HR.

4,600 MG/L
0 Q2 UPTAKE = 0.13 MG 02/DAY/MG ML VSS
^a>^
^^>,^ TEMP. =
^">X^
^°^






• 1 1 1 I 1 1 1
0 100
TIME (SEC.)
ft
= 14.9° C

"^^
^^^
^0




1 1 1 1 1
200

                                               OXYGEN UPTAKE DATA
                                                   FIGURE G-7

-------
O
do
                  3 -
LU
O
>•  2^
X
O
Q
LU


I  n
                                 dt
                                      MAR 30 - BASIN NO. 1
                                      =  14.0 MG/L/HR.
                                 VSS  - 5,600 MG/L
                                 02 UPTAKE
0.06 MG 02/DAY/MG ML VSS
                                      100
                                      TIME (SEC.)
                                                        200
                                                                                 z
                                                                                 LU
                                                                                 O
                                                                                 >-
                                                                                 X
                                                                                 O
                                                                                 O
                                                                                 co
                                                                                 CO
                                                                                    3-
                                       2-
                                                                                     1-
                                                                                        APRIL  1 - BASIN NO. 1


                                                                                   do
                                                                                   -fa   =  30.0 MG/L/HR.

                                                                                   VSS  = 5,180 MG/L

                                                                                   02 UPTAKE = 0.14 MG 02/DAY/MG ML VSS

                                                                                   TEMP. *  14.3° C
                                                           100
                                                          TIME (SEC.)
                                                                                                                          200
               5

               Z
                  3H
                  2-
X
O
O
LU
>
=f   1-
                       APRIL 8 - BASIN NO. 1

                       — "  38.4 MG/L/HR.
                       dt

                       VSS -  3,560 MG/L

                       02 UPTAKE « 0.26 MG 02/DAY/MG ML VSS
                                       [EMP.
                                               15.5° C
                                      100
                                      TIME (SEC.)
                                                        200
                                        3-
                                    >   2-|
                                    X
                                                                                 a
                                                                                 LU
                                                                                 O
                                                                                 to
                                                                                 to
                                                                                     1-
                                                                                                       APRIL 20 - BASIN NO. 2
                                                     do

                                                     dt

                                                     VSS
                                                                                                        =  28.8 MG/L/HR.
                                                                                                          2,840 MG/L
                                                     02  UPTAKE = 0.24 MG 02/DAY/MG ML VSS


                                                     TEMP. =  15.0° C
                                                           100
                                                           TIME (SEC.)
                                                                              200
                                                             OXYGEN  UPTAKE DATA
                                                                FIGURE G-8

-------
                                      APRIL 27 - BASIN NO. 2
                                                                                          APRIL 28 - BASIN NO. 2
o
vb
              _l
              c5
                  6.O-
                  5:0-
                  4-°
LU
a


X   3.0


Q
LU
               O
               %  2.0

               Q
                  1.0-
                  0.0
                    do
                    IT
                                         19.0 MG/L/HR.
                                                                                                    do
                                  VSS =  2,650 MG/L

                                  02 UPTAKE  = 0.17 MG 02/DAY/MG ML VSS
                                  TEMP.
                             15°  C
                      i    i   \   i
                         too
                         TIME (SEC.)
                                                         200
                                                                                     6.0
                                                                                     5.0 < ^
                                                                                     4.0-
LU
o

X  3.0-1


Q
LU
                                                                   |  2'«H

                                                                   Q
                                                                                     1.6-
                                                                                    0.0
                          26.4 MG/L/HR.


                          2,800 MG/L
                                                                                      VSS

                                                                                      02 UPTAKE = 0.23 MG 02/DAY/MG VSS
                                                                                                    TEMP.
                           15.0° C
                         100

                         TIME (SEC.)
                                                                                                                            200
                                                              OXYGEN UPTAKE  DATA
                                                                    FIGURE G-9

-------
APPENDIX H

-------
u_
 I
Q
(D
                                              6.75 X 10"'
                                                      103 TO 185 HP/MILLION GALLONS

                                                      AVERAGE AIR TEMP. RANGE = 37 TO 57°F
                        R(TU-TR)
(100.000 SO FT-F)
                                     FIGURE H-1
                       AERATION BASIN HEAT LOSS RELATIONSHIP
                            1.0 - 2.0 DAYS DETENTION TIME
                                     (ALL DATA)

                                         H-1

-------
                                5.16 X 10"'
                           103 TO 185 HP/MILLION GALLONS

                           AVERAGE AIR TEMP. RANGE = 42 TO 60° F
fl(TW-Tfl)
(100.000 SO FT-F)
               FIGURE H-2
AERATION BASIN HEAT LOSS RELATIONSHIP
     2.0 - 3.5 DAYS DETENTION TIME
              (ALL DATA)
                 H-2

-------
                                                                    4.07 X 1
-------
1

5
Accession Number
n Subject Field &, Group
05D
SELECTED WATER RESOURCES ABSTRACTS
INPUT TRANSACTION FORM
Organization
         French Co., The R. T., Shelley, Idaho
     Title
         AEROBIC SECONDARY TREATMENT OF POTATO PROCESSING WASTES
     Authors)
          French Co., The R. T.
                                         16
                                        Project Designation
                                         ftVPRD  15-01-68) 12060 EHV
                                         21
                                             Note
 22
     Citation
 23
 Descriptors (Starred First)
     *Waste treatment, *Secondary treatment, *Industrial wastes, Activated sludge,
     Aeration, Treatment facilities
 25
 Identifiers (Starred First)

     *Potato processing wastes, Food processing wastes, Waste treatment costs
 27
Abstract
A new secondary treatment facility at the R. T. French Company, Shelley, Idaho, has demonstrated the
feasibility of  a complete mix activated sludge system for secondary treatment of potato processing
wastes. The secondary treatment  facility was designed  for an average daily flow of 1.25 million gallons
per  day and  a  BOD  loading of 14,100  pounds  per day. Frequent aerator shutdowns  following
mechanical problems have limited oxygen transfer and biological activity in the aeration basins; however,
BOD removals  of over 90 percent have been obtained  for extended  periods of time, demonstrating the
applicability of the activated sludge process for treating the wastes. These removals have been obtained
with:  (1)  MLSS  concentrations  between  2,000  mg/1 and 8,000 mg/1,  (2)  aeration basin D. O.
concentrations  between 0.3 mg/1  and  5.2 mg/1, (3)  aeration basin temperatures between 45 degrees F
and  67  degrees F, (4) aeration basin pH between 7.1 and 8.4, (5) organic loadings between 10 and 120
Ib BOD/1,000 cu ft/day, (6) hydraulic detention times of 0.9 to 8.7 days, and (7) BOD/MLVSS ratios
of 0.15  to 0.47.

This report was submitted in fulfillment of Grant No.  WPRD 15-01-68, Program 12060 EHV, between
the Environmental Protection Agency and R. T. French  Company.
Abstractor   Glenn Richter
                             institution Cornell, Rowland, Hayes & Merryfield, Corvallis, Oregon
  WR:<02  (REV. JULY 1969)
  WRSIC
                                               SEND TO: WATER RESOURCES SCIENTIFIC INFORMATION CENTER
                                                       U.S. DEPARTMENT OF THE INTERIOR
                                                       WASHINGTON. D. C. 20240
                                                                                        * GPO: 1969-359-339

-------