SEWER SYSTEM EVALUATION
    ^^^   FOR
    INFILTRATION/INFLOW
              Prepared for
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
      TECHNOLOGY TRANSFER PROGRAM
              Prepared By
              "mill'
      AMERICAN CONSULTING SERVICES, INC.
             Minneapolis, Minnesota

-------
           SEWER SYSTEM EVALUATION

                    FOR

             INFILTRATION/INFLOW
                PREPARED FOR

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

          TECHNOLOGY TRANSFER PROGRAM
               PRESENTED BY

          LELAND E. GOTTSTEIN, P.E.

                 PRESIDENT

      AMERICAN CONSULTING SERVICES, INC.
           MINNEAPOLIS, MINNESOTA

-------
                   TABLE OF CONTENTS



INTRODUCTION                                           1

THE NEW FEDERAL LAW                                    5

SEWER SYSTEM EVALUATION ... WHAT IT IS                 6

FEDERAL STUDY AND MANUAL OF PRACTICE                   6

THE METHODOLOGY OF SEWER SYSTEM EVALUATION             8

PHASE I - INFILTRATION/INFLOW ANALYSIS                 8

     a.  Patterned Interviews                          9
     b.  Sanitary and Storm Sewer Map Study           10
     c.  System Flow Diagrams                         11
     d.  Dry vs Wet Weather Flow Determinations       12
     e.  Preliminary Field Survey and Selective
           Flow Tests                                 13
     f.  Determination of Excessive or Non-
           Excessive Infiltration/Inflow              15
     g.  Establish a Plan of Action, Budget
           and Timetable for Execution                16

PHASE II - FIELD INVESTIGATION AND SURVEY             17

     a.  Physical Survey and Groundwater Analysis     18
     b.  Rainfall Simulation                          19
     c.  Prepare Engineering Report and Analysis      22
     d.  Preparatory Sewer Cleaning                   24
     e.  Television Inspection of Preselected
           Sewers                                     28
     f.  Preparation of the Evaluation Survey Report
           and Analysis                               34
     g.  Preparation of the Proposed Rehabilitation
           Program                                    37

THE NEED FOR PUBLIC RELATIONS                         38

PHASE III - REHABILITATION                            40

     a.  Sewer Repair                                 40
     b.  Pipe Relining                                44
     c.  Sewer Replacement                            45
     d.  Finalization of Treatment Plant Design       46

SUMMARY                                               47

APPENDIX                                              48

     Figures 1, 2, 3, 4                               49
     Figure 5                                         50
     Excerpt of Law                                   51

-------
                   SEWER SYSTEM EVALUATION
                             FOR
                    INFILTRATION/INFLOW

                             BY

                  LELAND E. GOTTSTEIN, P. E.
                          PRESIDENT

              AMERICAN CONSULTING SERVICES, INC.
                    MINNEAPOLIS, MINNESOTA
INTRODUCTION

In past years, infiltration and inflow of extraneous waters

into sewer systems were not of much concern to the engineer or

municipal official.  Some of the major reasons which trigger

desperate corrective measures to solve the extraneous water intru-

sion problem are:


(1)  Flooded basements during period of intensive rainfall

(2)  Excessive power costs for pumping

(3)  Overtaxing of lift station facilities often resulting in

     frequent electric motor replacements

(4)  Overloading of treatment plant facilities

(5)  Excessive costs of sewage treatment including meter charges

     levied by sanitary districts or other jurisdictional

     authorities

(6)  Obnoxious odors and health hazards caused with by-passing

     of raw sewage

-------
                              -2-
 (7)  A pumping-up action of downstream sewers when excessive



     heads and surcharging of manholes occur.  When the sur-



     charging stops and the head over the pipe is relieved



     through defective joints, a fine sugar sand enters the



     pipe with the water.  A loss of pipe overburden occurs



     and the street eventually settles or collapses.








In addition to the above motivators for correction, there are



many other sewer system inadequacies which concern the engineer



and the municipal official.  Problems of infiltration/inflow



are often relieved by the construction of relief sewers, larger



lift stations and treatment plants, and the use of sewage by-



passes throughout the system.  Unfortunately, however, this



approach results in untreated sewage flows being discharged into



rivers, streams, lakes and open ditches.  In past years the



engineer concerned himself with the best economical design choice



of a system which would serve the needs of the community 90 to



95 per cent of the time.  On those rare occasions where the flows



were excessive, relief facilities and by-passes provided a con-



venient solution to the problem.








What were acceptable standards of sewage treatment in the past are



not sufficient to meet the sophisticated requirements of treat-



ment today.  The upgrading of federal and state standards for the

-------
                               -3-
type and degree of sewage treatment, has resulted in new problems



that the engineer must now face.  "Zero discharge" is a new term



in the environmental lexicon of today.      *








New federal legislation proposes a zero discharge standard as a



national goal.  The objective is to eliminate all pollutant dis-



charge to open ditches, lakes, streams, rivers and navigable



waters.







The engineer is now faced with the problem of handling all of



the wastewater.  The problems connected with infiltration/inflow



and overloaded sewer systems must be faced. There is no choice.



Past practices of constructing relief sewers and by-pass facilities



will not solve the problem.  Therefore, we must go to the source



of the infiltration/inflow problem ... the sewer system itself.







Unfortunately, we have to live with our existing collection systems,



We cannot trade them in on new ones.  We have huge sums of money



invested in our underground sewers and the street surfaces above



them.   The replacement cost of the existing sewers would far



exceed what we paid to install them.  Complete sewer replacement



would not only be too costly but in most cases would not solve



the infiltration/inflow problem.







Intrusion of ground water or storm water into the sewer system

-------
                               -4-
via house laterals and other service connections compound the



problem.  Often the major contributions to the clear water



problem are faulty service connections and direct connections



of footing drain tile to the sanitary sewer.  Any sewer system



evaluation must differentiate between the extraneous water



contribution from service connections and those extraneous flows



contributed through irregularities or deficiencies in the muni-



cipal sewer system.  Correction of service connection problems



are political in nature and must be handled judiciously.  The



technology for correcting these problems is also different from



that used to correct infiltration/inflow problems in the larger



sewer mains.  Replacement of municipal sewer mains or grouting



sewer joints in the main will not solve the service connection



problem.








What can we do with our existing sewer systems?  We must evaluate



these systems and formulate programs to solve the infiltration/



inflow problems.  One may ask, where do we start?  How do we do



it?  Who is going to do it?  How much will it cost?  How long will



it take?  How are we going to finance it?  What assurance do we



have that any program will solve the infiltration/inflow problems?



What are the alternatives?  These and other questions can boggle



the mind.  The burden is on the engineer and public official to



provide answers and solve the problem.  This is the real subject



of this presentation ... SEWER SYSTEM EVALUATION.

-------
                               -5-
THE NEW FEDERAL LAW




ON OCTOBER 18, 1972 THE 92ND CONGRESS OF THE UNITED STATES




OVERWHELMINGLY PASSED PUBLIC LAW 92-500 WHICH IS CITED AS THE




"FEDERAL WATER POLLUTION CONTROL ACT AMENDMENTS OF 1972."  IT




IS SUGGESTED THAT ANY ENGINEER OR PUBLIC OFFICIAL CONCERNED WITH




THE DESIGN, IMPROVEMENT OR OPERATION OF SEWAGE TREATMENT PLANTS




AND/OR SEWAGE COLLECTION SYSTEMS SECURE A COPY OF THE NEW LAW.




MANY CHANGES IN REQUIREMENTS AND ELIGIBILITIES FOR FEDERAL GRANT




ASSISTANCE HAVE BEEN MADE.








The new act recognizes that sewer problems can relate to the




sewage treatment needs.  AMONG THE MANY NEW PROVISIONS IS ONE




WHICH PROVIDES FOR FEDERAL FINANCIAL ASSISTANCE TO SPECIFICALLY




DEAL WITH INFILTRATION/INFLOW IN EXISTING SEWER SYSTEMS.  Excerpts




from Title II of the federal Water Pollution Control Act Amend-




ments of 1972 are included in the Appendix of this presentation.








If you read the excerpts, you will note that it is now mandatory




to identify the extraneous water problems and to determine whether




the sewer system is subject to excessive infiltration/inflow.




Federal grant assistance is available to study the problem and,




in turn, to correct or accommodate it provided that all such work




is performed in "accordance with rules and regulations promulgated




by the Administrator", (EPA).  Copies of the EPA rules and regu-




lations are available from each regional EPA office.

-------
                               -6-
SEWER SYSTEM EVALUATION ... WHAT IT IS



For the purpose of this discussion/ we will define sewer system



evaluation or system analysis as a systematic approach to



evaluating a sewer system which will enable the engineer to:





(1)  Identify the scope and nature of the infiltration/inflow



     problem.



(2)  Establish an end objective.   (The amount of infiltration/



     inflow that can be economically eliminated)



(3)  Isolate those general sections of the sewer system where



     infiltration/inflow is occurring.



(4)  Formulate a plan which can be economically justified for



     investigating and locating specific areas from which the



     major infiltration/inflow emanates.



(5)  Formulate a plan which will assure correction of the



     infiltration/inflow problem along with alternatives for



     rehabilitation and a prediction of the end results that can



     be expected.



(6)  Establish hydraulic parameters for sewage treatment plant



     design.








FEDERAL STUDY AND MANUAL OF PRACTICE



What are the causes, effects and means of correcting excessive



extraneous water entering public sewer systems, as a result of



infiltration and inflow?  A very detailed and exhaustive national



study examining these factors and their economic impact in the

-------
                              -7-
United States has been conducted by the Research Foundation




of the American Public Works Association, under contract and




in concert with the water quality office of the Environmental




Protection Agency.   The study involved many public agencies,




the American Public Works Association, the American Society of




Civil Engineers, the Water Pollution Control Federation, an



Industrial Advisory Panel, the Associated General Contractors




of America and consulting engineering firms.








AS A RESULT OF THIS JOINT EFFORT, TWO DOCUMENTS WERE PUBLISHED.




THE FIRST DOCUMENT IS ENTITLED, CONTROL OF INFILTRATION AND INFLOW




INTO SEWER SYSTEMS (NO. 11022 EFF 12/70).  THIS REPORT IS A




TABULATION AND ANALYSIS OF INTENSIVE FIELD INVESTIGATIONS CARRIED




OUT BY THE FULL TIME STAFF OF APWA.








THE SECOND DOCUMENT IS ENTITLED, PREVENTION AND CORRECTION OF




EXCESSIVE INFILTRATION AND INFLOW INTO SEWER SYSTEMS ... A MANUAL




OF PRACTICE (NO. 11022 EFF 01/71).  THIS REPORT CONTAINS THE




SUGGESTED METHODS, GUIDELINES AND PRACTICES PERTAINING TO THE




CONSTRUCTION,  TESTING AND ACCEPTANCE OF NEW SEWER FACILITIES AS




WELL AS DEALING WITH THE PROBLEMS OF INFILTRATION/INFLOW INTO




EXISTING SEWER SYSTEMS.  BOTH PUBLICATIONS ARE AVAILABLE FROM THE




SUPERINTENDENT OF DOCUMENTS, U.S. GOVERNMENT PRINTING OFFICE,




WASHINGTON D.C. 20402 AT A COST OF $1.25 EACH.

-------
                               -8-
THE REPORTS ARE PART OF THE WATER POLLUTION CONTROL RESEARCH




SERIES OF THE WATER QUALITY OFFICE OF THE ENVIRONMENTAL PRO-




TECTION AGENCY.  ANYONE WHO IS DIRECTLY RESPONSIBLE FOR THE




DESIGN,INSTALLATION OR MAINTENANCE OF SEWER SYSTEMS IS ENCOURAGED




TO PURCHASE THESE TIMELY EPA DOCUMENTS AND TO READ THEM THOROUGHLY,




THE INFORMATION WILL PROVIDE YOU WITH SOME NEW IDEAS FOR DEALING




WITH YOUR OWN SEWER PROBLEMS.








THE METHODOLOGY OF SEWER SYSTEM EVALUATION




Figure 1 shows the general considerations of an orderly pro-




grammed approach to evaluating a sewer system.  Each phase of the




program will be discussed separately.  The following presentation




should facilitate the understanding of the federal Guidelines for



Control of Infiltration/Inflow in Sewer Systems.  Phase I deals




with the work involved under the Infiltration/Inflow Analysis




section of the Federal EPA Guidelines.  Phases II and III refer




to the work involved under the Sewer System Evaluation Survey




section.








PHASE I - INFILTRATION/INFLOW ANALYSIS




Figure 2 shows the essential considerations.under this phase of




the program.  The first problem is to find the problem.  Without




identifying how much extraneous water one has to conquer, any




program of search and correct would be a shotgun approach without




direction.  Without a definite objective, no one would know what

-------
                              -9-
portion of the total problem is being solved at any one time



nor would one know how much money would have to be spent for



correction.





     a.  Patterned Interviews



         The Patterned Interview involves the first look at



         the extraneous water problem in the community.  An



         experienced professional in the area of infiltration/



         inflow should interview everyone who is,  or has been,



         connected with the sewer system.  Subsequent analysis



         of the data will answer questions and give the analyst



         a feel of the overall problem.







         The general objective of the patterned interview is



         to focus the problem.  The questions should cover a



         broad spectrum of subjects ranging from technological



         and geological matters to municipal performance capa-



         bilities to the socio-economic profile of the city.  A



         well planned interview also helps the municipality



         to think about its problems in an orderly fashion



         and to recognize alternate methods for solution.  The



         interviews reveal what the municipality knows and,



         more important, what it does not know about its sewer



         system.   It tells both the engineer and municipality



         what yet remains to be answered before the evaluation

-------
                         -10-
    program can continue.  This is the key to the evaluation



    process.  If you cannot identify the problem you must



    solve, the system evaluation program should stop.








    The next step is the collection of all available data



    such as the treatment plant records, maps, etc. pertain-



    ing to the infiltration/inflow problem.  Many communi-



    ties have no maps of their sewer system.  It is often



    necessary to gather whatever data is available, however



    sketchy.  Once all this information is gathered, it



    must be assimilated, and here is where analytical as



    well as practical experience in sanitary engineering



    and sewer system maintenance is necessary.







    Questions and Comments:
b.  Sanitary and Storm Sewer Map Study



    The next step is to study the plot maps of the sanitary



    and storm sewer systems.  If the maps are not available



    in reasonably accurate form, system evaluation is diffi-



    cult if not impossible and efforts must be made to



    garner whatever piece-meal information is available.



    A map should be developed for those areas which need

-------
                         -11-
    evaluation since the patterned interviews may dictate



    that the entire sewer system need not be evaluated.








    The study of the plot maps generally reveals relation-



    ship of storm sewers to sanitary sewers, location of



    pumping stations, key manhole juncture points, and



    a host of other valuable data.  Without accurate plot



    maps and flow charts, further study is impossible.







    Questions and Comments:
c.  System Flow Diagrams



    When the appropriate sewer plot maps are developed,



    it is then possible to divide the system into mini-



    systems which can be studied independently.   The



    Vector Flow diagrams can be prepared which will relate



    the theoretical sewer capacities to the actual flow



    conditions.







    Information from the vector flow diagrams coupled with



    the study of the sewer plot maps and analysis of the



    data collected during the patterned interviews gives

-------
                         -12-
    the experienced analyst the sense of direction he



    needs to solve the infiltration/inflow problems in



    the sewer system.








    Questions and Comments:
d.  Dry vs Wet Weather Flow Determinations



    Analysis begins with a very careful comparison of



    the flow records obtained from the municipality.



    Correlations are drawn between times of high sewage



    flow and periods of heavy rainfall and/or runoff.







    The difference between the peak industrial and



    domestic flow rates and peak wet weather flow rate



    determines what we call "Delta Q" flow rate, or



    the magnitude of the extraneous water problem.







    The nature of the infiltration/inflow problem, the



    sewage treatment requirements, the industrial sewage



    contribution, the climatological and seasonal vari-



    ations, must be considered in determining the scope



    of the study and the time of performance.  The Delta

-------
                         -13-
    Q should be reduced to its contributing components



    by district to facilitate the investigation in the



    major problem areas.








    Questions and Comments:
e.  Preliminary Field Survey and Selective Flow Tests



    Flow surveys and other tests can be conducted at



    selective locations to more accurately determine



    the scope of the infiltration/inflow problem.  The



    engineer should familiarize himself with the subject



    of instrumentation relating to appropriate sewer flow



    measurement techniques.  It is safe to say that there



   / has been much time wasted gathering flow data by "V"



    notch or other types of weirs on a 24 hour surveillance



    basis.   The results have either been useless or



    inconclusive.








    Flow tests conducted at the wrong time and under the



    wrong conditions will lead to fallacious conclusions,



    and random weiring at key locations in the system may



    not yield meaningful results.  Ineffectual tests can

-------
                     -14-
result in costly corrective measures and provide no



solution for the flooded basement conditions, raw



sewage by-passing, or other infiltration/inflow



connected problems.








The author has found that one of the most practical



methods of flow measurement is simply to measure the depth



of flow in pre-determined key manholes with a ruler.



Knowing the hydraulic characteristics of the sewers in



these manholes (slope, pipe size, etc.)  a computation



will determine the flow rate.  It is important•that



these depth measurements are taken at the proper times,



such as dry weather, high groundwater and rainfall



situations, so that the relationships between the flows



at these times can be compared.  These measurements,



coupled with allowances for peak domestic and industrial



flow rates, will be the determinant as to whether flows



are possibly excessive or non-excessive at these key



points.







Questions and Comments;

-------
                         -15-
f.   Determination of Excessive or Non-Excessive Infiltration/



    Inflow



    Information to be obtained and evaluated in making a



    determination as to whether flows are excessive or



    non-excessive includes:





    1.   Flow data for all flows in the sewer system



        including overflows  and bypassed flows



    2.   Location, frequency  and cause of overflow conditions



        in the collection/treatment system caused by



        infiltration/inflow



    3.   Relationships of existing population and industrial



        contribution to flows in the sewer system



    4.   Geographical and geological conditions which may



        affect the present and future quantities or



        correction costs of  the infiltration/inflow



    5.   A general discussion of age, length, type,  materials



        of construction and  known physical condition of the



        sewer systems





    From this information preliminary estimates can be



    developed for the relative costs (for the design life



    of  the treatment works)  both for correcting the infiltration/



    inflow conditions,  and increasing the treatment works



    capacity to provide the  required degree of wastewater



    treatment for the quantities of infiltration/inflow.

-------
                         -16-
    Excessive infiltration/inflow would be present in



    the sewer system if the cost estimate for its treatment



    would be greater than the cost estimates for its



    correction.







    Questions and Comments:
g.  Establish a Plan of Action, Budget and Timetable



    for Execution



    Having determined in the earlier phases of the



    infiltration/inflow analysis that the infiltration/



    inflow problem is excessive, the engineer must now



    recommend a program that will culminate in the solution



    of the problem.   A proposed detailed plan for a systematic



    sewer system evaluation survey would normally be divided



    into five phases:





    1.  Physical Survey



    2.  Rainfall Simulation



    3.  Preparatory Cleaning



    4.  Television Inspection



    5.  Analysis

-------
                               -17-
         An explanation of the plan would include the tasks



         to be performed, the method of task accomplishment,



         data to be obtained and recorded, information and data



         to be reported and a cost estimate for each phase of



         the survey which is recommended.  An approximate



         estimate of starting dates and duration of execution



         of each phase is necessary taking into account the



         climatological restrictions for performance.







         Questions and Comments:
PHASE II - FIELD INVESTIGATION AND SURVEY



The infiltration/inflow problem has now been identified, areas



of study established, budget estimates set and expected results



determined.  Phase II can now be considered.  Figure 3 generally



outlines the work entailed in this phase of the system investi-



gation.  It should be pointed out that the physical survey,



ground water analysis and rainfall simulation work must be com-



pleted before it is possible to prepare an engineering report,



analysis and timetable for the performance of the preparatory sewer



cleaning and selected television inspection studies.

-------
                         -18-
a.  Physical Survey and Groundwater Analysis



    The physical survey of the sewer system involves



    the descent into every manhole that is within the



    study area of the sewer system.  It should be



    emphasized that the mere observation of sewer flows



    from on the top of the ground does not constitute



    a physical survey.  Accurate assessments of actual



    manhole and sewer conditions can only be made from



    inside the manhole.  The physical survey is con-



    ducted by descending every manhole in the area of



    study and actually observing the degree and nature



    of the deposition in all lines into and out of the



    manhole.







    Unless each manhole is descended and each pipe



    lamped, it is unlikely that the engineer can



    accurately judge the impact of infiltration on the



    system as a whole.  By actual observation the engineer



    may be able to eliminate large portions of the system



    from further study.








    Inspection by a trained observer during the physical



    survey generally reveals sources of inflow that



    might otherwise go undetected, such as manhole covers

-------
                         -19-
    with large holes, obvious deficiencies in the manhole



    structures, manholes located in natural ponding areas



    and other such deficiencies.  These sources of inflow



    are usually the least costly to eliminate.  The



    physical survey provides valuable information for



    refining the cost effective rehabilitation estimates.








    Questions and Comments:
b.  Rainfall Simulation



    If the infiltration/inflow analysis demonstrates that



    major inflow problems occur during periods of intense



    rainfall, a controlled systematic check of all storm



    sewers that parallel or cross the sanitary sewer system



    and/or house services should be initiated.  In performing



    this phase, the percolative capacity of the soil should



    be taken into account.  A Rainfall Simulation study is



    not simply the flooding of storm sewers with dyed water,



    but is a geologic and hydrologic study of the assimilative



    capacity of soil surrounding the storm sewer, coupled



    with the susceptability of the sanitary sewers to accept

-------
                     -20-
the exfiltration/infiltration phenomenon.  In addition,



before and after flow rate comparisons are essential



to the success of this phase of the work.  Unless these



flow rates are compared, it is impossible to determine



the impact of rainfall on the system as related to the



exfiltration/infiltration phenomenon.








Without the appropriate engineering considerations,



i.e. flow rate comparisons, time of flooding, time



lapse for dye transfer, etc., the results of an impro-



perly conducted storm sewer flooding program will yield



fallacious results upon which equally fallacious con-



clusions and recommendations will be made.







Again the reader is cautioned that great care and



professional judgement should be exercised in conduct-



ing these simulation tests.  They should not be con-



ducted by the inexperienced or lay person.







Diverse field conditions dictate the extent of this



phase.  The number of open ditches and closed storm sewer



conduits to be tested and the availability of water



supplies are a few of the major considerations that



must be taken into account during this phase of the



program.

-------
                     -21-
It should be pointed out that rainfall simulation



is not always required in every system evaluation



study.  Here again whether or not storm sewers are



to be tested is dependent upon the pre-determination



by the engineer.  He must decide whether or not the



impact of rainfall on the sanitary sewer system



creates excessive inflow conditions.  Furthermore, it



should be brought to the engineer's attention that this



work does not include the cleaning and/or televising



of the storm sewers being tested.  Only in very rare



and unusual cases, will storm sewers need to be



cleaned and televised as part' of a sewer system



evaluation study.  Hydraulic testing of storm sewers



to determine whether exfiltration and cross connections



affect the adjacent sanitary sewers should not be con-



fused with the procedure of televising sewers.







Questions and Comments:

-------
                         -22-
c.  Prepare Engineering Report and Analysis



    The engineering report which summarizes and evaluates



    all of the findings of the physical survey, groundwater



    analysis and rainfall simulation studies,  provides



    the basis for the culmination of this phase of the



    program.  The engineer must be able to economically



    justify his recommendations for future work.  His



    conclusions must assure the municipality that, if the



    work is carried out as recommended, the infiltration/



    inflow problem will be brought under control.   The



    report should further itemize the infiltration/inflow



    findings by sewer district which then is correlated



    to the total Delta Q.  Television inspection and



    cleaning schedules are established and the next phases



    of the study are determined.







    Based on the recommendations and analyses from the



    physical survey and rainfall simulation, meaningful



    engineering reports can be prepared and budget adjust-



    ments made.  At this juncture in the program,  precise



    locations for televising can be determined and the



    exact cost of these TV inspections established.  Com-



    pletion dates and^end results can be predicted.  The



    engineer can plan the necessary preparatory sewer



    cleaning and television inspection.  Sewer cleaning

-------
                     -23-
costs can also be accurately predicted.







Because time is usually a critical factor, it should



be pointed out that the television inspection generally



can be accomplished much more rapidly than the preparatory



sewer cleaning.  Many municipalities are not sufficiently



staffed to perform the preparatory sewer cleaning prior



to the deadline stipulated by federal and state govern-



ments.  Generally they do not possess the cleaning



equipment which will minimize the time required for



proper preparatory cleaning.







It is the engineer's responsibility to advise the



municipality on the latest sewer cleaning techniques,



the time required to perform the work and the anticipated



costs.  After a thorough discussion of all of the findings



and recommendations as a result of the field investiga-



tions, the municipality is now ready to proceed with



selective preparatory cleaning and television inspection.








Questions and Comments;

-------
                          -24-
d.  Preparatory Sewer Cleaning



    At this point a reiteration and further clarification



    of the preparatory sewer cleaning program is necessary.



    The importance of identifying the physical condition



    of the sewer system was previously discussed.   The



    findings of the physical survey indicate not only the



    apparent deficiencies in the system,  but also the nature



    and degree of the deposition within the sewers.








    In many smaller communities, routine maintenance



    may mean rodding of sewers on an as needed basis with



    occasional flushing of the rest of the system once or



    twice a year.  In other communities,  routine main-



    tenance may mean actual cleaning of each section of



    sewer once every two to three years.   The important



    point to stress is that full gauge instruments must



    be used in any sewer cleaning preparatory to TV



    inspection.  Full gauge instruments may mean rubber



    squeegees with the use of the conventional bucket



    machines or they may mean an extra pass or two with



    the high velocity hydraulic jet machine.







    Particular attention should be paid to root removal.



    Up to now, the successful removal of roots with the use

-------
                      -25-
of a jet machine and hydraulic root cutter has not



proven successful enough to be considered as sufficient



preparation for TV viewing.  It is recommended that



conventional bucket machines be used with root scarifiers,



brushes and squeegees where ever heavy root infestations



are in evidence.  These areas are located during the



physical survey.







The preparation of a routine sewer maintenance program



is included as part of the physical survey report



since future costs for sewer maintenance are projected



in the report.  Intelligent budgeting is now possible



rather than basing the sewer maintenance budget on last



year's figures plus 10 per cent which were based on the



previous year's figures plus 10 per cent, etc., all of



which were really not based on cleanliness, or lack



thereof.







In analyzing this data, the scope of the sewer cleaning



program can be established in terms of crew hours and



dollars.  Sewer cleaning is a necessary prerequisite



for any subsequent television inspection that may be



required.  Many engineers are not aware of the tremendous



time involved in properly preparing sewers for television

-------
                     -26-
inspection.  They assume that this is a routine function



that any municipality is capable of performing.  Thorough



cleaning of sewers which will permit optimum viewing



with television cameras is not routine work in most



municipalities.  In addition, municipal governments



generally do not provide adequate funds to do the "first



time around cleaning" needed to restore full capacity



to sewers.  Therefore, it is the duty of the engineer



to not only describe the general condition of the sewer



system, including all of the physical deficiencies that



can be visually observed, but also to point out the



scope of the cleaning program required.  Special



emphasis should be placed on those locations where



infiltration/inflow is known to exist.  The data from



the physical survey will dictate the most practical



scheduling of municipal sewer cleaning crews, and for



the first time will permit municipal officials to



set realistic budgets for these activities.







There are various, ways to clean a sewer. With the advent



of the new hydraulic cleaning machines, more efficient



sewer cleaning can be accomplished in a fraction of the



time required by older methods.  Facing up to the cleaning



problems has forced many municipalities to reconsider not

-------
                     -27-
only their budgets, but the methods they employ for



sewer maintenance.








Cleaning costs, however, are a function of the nature



of the deposition, volume of debris to be removed



and the distance between manholes.  It is the engineer's



responsibility to accurately justify these cleaning



costs as part of his estimated budget for system evalu-



ation and restoration.








Normally more sewers will have to be cleaned than are



televised.  Depending on the findings of the physical



survey, there are times when extra cleaning is necessary



to avoid the reclogging of sewers prior to televising.



This will assure that the sewers to be internally



studied will remain clean long enough for television



inspection work.  The cleaning process is generally far



more time consuming than the actual television inspection



work.  It is not reasonable to have a television camera



available on site at all times while the cleaning crews



are working in attempts to televise right behind the



cleaning crews.  This method will result in much higher



costs for TV inspection.








The preparatory sewer cleaning will be an allowable



Federal cost only where it is necessary prior to any

-------
                         -28-
    television inspection.  WHOLESALE,  INDISCRIMINATE AND




    ECONOMICALLY UNJUSTIFIABLE SEWER CLEANING AND TELE-




    VISING WILL NOT BE ELIGIBLE FOR FUNDING ASSISTANCE.








    Questions and Comments:
e.  Television Inspection of Preselected Sewers



    Under the previous phases of the work,  the infiltration/



    inflow problem was localized.   It was identified in



    terms of approximate quantities and the general areas



    where the sources originate.  The municipality now



    knows that the sewers in these areas are leaking, but



    it does not know whether or not such leaks emanate from



    house services, joints,  broken pipe, cross connections,



    etc.   It also does not know the general condition of the



    pipe, the number of contributing sources, nor their



    quantitative contribution of extraneous water.  The



    ONLY way to pinpoint the problem is by use of the



    television camera.  The sophisticated use of this inspec-



    tion tool will produce valuable data which can be con-



    structively used for analytical purposes.  Since viewing

-------
                     -29-
the monitors also requires field interpretations, the



same tool in the hands of the inexperienced, with little



or no analytical capabilities can prove to be a great



waste of time and money.








Television provides the only means by which moving water



can be instantly observed.  This, of course, is the object



of a system evaluation.







If the infiltration/inflow analysis indicates that ground



water is the major factor contributing to the infiltration/



inflow problem, televising sewers in the middle of the



driest months will not yield the expected results.  TV



inspection must be conducted during those periods when



the ground water is at its highest level.







Groundwater studies are usually encompassed as part of



the physical survey of the sewer system.  Groundwater



gages  should be installed in key selected manholes as



a means of correlating the impact of static heads on



sewage flows. This procedure will be necessary in order



to determine the relative significance of infiltration to



the total infiltration/inflow problem.  Figure 5 shows



a typical static groundwater gage  installation.

-------
                     -30-
If it has been pre-determined that inflow is a signifi-
cant part of the problem, selected storm sewers should
be reflooded so that television inspection can be
accomplished under simulated rainfall conditions.
Those sections of storm sewers that must be reflooded
during the TV inspection are determined during the
Rainfall Simulation Study.

Experience to date has shown that the use of still
photography is neither practical nor advisable for
a sewer system evaluation survey.  The objective in any
study is to identify all of the sources of infiltration/
inflow ... therefore, one must include the extraneous
water contributions from service connections.

If, for example, a house service is flowing during a
TV inspection, the camera travel must be stopped and
the possibility of domestic contribution to the observed
flow determined.  If no flows are being generated within
the house, then it can be assumed that the observed flow
is infiltration or inflow.  Basement footing drain tile,
yard drains and other extraneous water sources entering
the house service are further indications that the flows
observed on the TV screen are not domestic contributions.

-------
                     -31-
Still photography may indicate (after the film is



developed) that a house service was flowing, raising



the question, "Were those people using their facilities



at three o'clock yesterday afternoon?"  No one will ever



know.  To date, the author's attempts to conduct



infiltration studies using still photography or movie



cameras have met with little success.







Still photography or the use of movie cameras may have



merit if the intent of the sewer inspection is merely



for structural purposes.  Experience, however, has



shown that TV cameras are preferable for infiltration/



inflow studies since deficiencies are more discernable



and can be evaluated instantly as compared to waiting



for film development.  It is important that any TV



inspection for infiltration/inflow identification include



the location and rate of contribution of each leak.



Without such quantitative   evaluations, extensive repairs



based on sealing big leaks, little leaks, drippers, etc.



are strictly arbitrary.  Without predetermining the



relative contribution of sewer main leaks, house service



leaks and manhole leaks, one cannot be assured of an



accurate and meaningful analysis upon which decisions for



correction can be made.

-------
                     -32-
Polaroid or 35MM pictures taken from the TV monitor



as permanent records will not always reveal the



necessary information required for an infiltration



analysis.  The use of video tape recordings during



the TV viewing process enables the engineering analyst



to review the important findings.  Based on his own



independent observations along with those of the



trained TV technician, he will be able to make an



unbiased and a more accurate evaluation of the



extraneous water findings.







Television inspection performed as part of any infiltration/



inflow study usually cannot be successfully accomplished



on a bid basis.  If such a practice is followed, the



successful bidder is interested only in how fast he can



go through the sewer at a fixed price.  Each time the TV



camera travel must be stopped in order to determine



whether the visible source of water flow into the sewer



is extraneous water or domestic waste water (i.e. house



service flow, etc.), the TV operator becomes nervous



because he is wasting time.  He cannot afford to spend



the time to study the flow.  The experienced professional



can accurately determine a fair and reasonable fee for



such infiltration/inflow study work.  The engineer is

-------
                     -33-
cautioned not to confuse volume bid type sewer



televising with utilizing the same tool as an aid to



engineering evaluation work.  Costs of televising



sewers for infiltration/inflow studies are generally



higher than those for volume viewing for such purposes



as TV inspection of new sewer construction, before



paving, etc.







As was pointed out previously,during infiltration/inflow



study viewing, camera travel must often be stopped so



that extraneous water from house services, roof drains,



footing tile, yard drains and other possible infiltration/



inflow sources can be accurately identified and quantified,



It is essential that these types of extraneous water



entry be differentiated from those emanating from sewer



joints in the main sewers.







Viewing sewers above 24" and below 8" diameter may be



higher in cost.  Televising pipe smaller than 8" presents



a higher degree of risk since protruding service



connections, horizontal or vertical misalignment, offset



joints, etc. could easily prohibit passage of the TV



camera.  Conversely, attempting to televise large diameter



sewers which handle heavy flows often requires special



setups and rigging to float the camera through the line.

-------
                         -34-
    Depending upon the distance between manhole stations,
    the setup and rigging costs could substantially
    increase the costs .

    Questions and Comments:
f.   Preparation of the Evaluation Survey Report and
    Analysis
    All TV engineering reports should include the engineering
    analysis and recommendations, final map preparation and
    cost estimates for rehabilitation.   The sewer system
    evaluation report is the basis for formulating the
    rehabilitation program.   It represents the culmination
    of all the investigative procedures.  At this stage of
    the program definite decisions can be made based on
    positive recommendations for replacement and/or repair.
    It is now possible to compare the extraneous water
    findings of the TV investigation to the original
    estimated Delta Q determinations that were made during
    the infiltration/inflow analysis.  It is also possible

-------
                     -35-
to accurately predict the end results that the



municipality can expect in the way of extraneous



water reduction if the recommended rehabilitation



program is carried out.








It is important to stress the difference between a



TV report and an analytical evaluation.  A TV report



contains log sheets showing field data along with



Polaroid pictures of obvious physical deficiencies



and apparent leaks. A conventional TV report generally



describes leaks as big leaks, little leaks, drippers,



house service flowing or apparent break, etc.



These reports often include comments at the bottom



of the page indicating leaks should be sealed without



any quantitative explanation.








In other words, a TV report still leaves the evaluation



of the data to the municipality or its engineer who may



or may not be experienced in the interpretation of the



data.  Without an accompanying video tape showing move-



ment of water such evaluation would be valueless especially



if the engineer did not have the opportunity to be in



the field during the viewing operations.  Attempts to



evaluate a video tape in a remote office by an engineer

-------
                      -36-
with no first hand knowledge of field operations could



lead to interpretations of data that result in erroneous



evaluations and marginal rehabilitation results.  It is



not possible to achieve meaningful interpretive results



by having a TV inspection firm video tape every foot of



sewer.  This does not constitute a sewer system evaluation



survey.  It is also a waste of time to have to view video



tapes which depict foot after foot of good sound sewer



pipe.  Recording all of the good pipe on video tape is



very expensive and is not worth the cost.








A useful engineering report (analytical evaluations)



will not only include standard log sheet data,P olaroid



pictures, house service locations,etc., but also a



quantitative analysis of each leak in terms of gallons



per minute.  These quantitative judgements are based on



laboratory simulations, the combined judgements of a



competent TV technician and an experienced reviewing



engineering specialist.  With this flow data, the engineer



is able to make a sound judgement as to whether the



infiltration/inflow sources should be rehabilitated.








Summary tables should be prepared which indicate the



rehabilitation needed, differentiating between those



repairs which will reduce the infiltration/inflow



and those that should be made from a structural point

-------
                        -37-
    of view.  The engineer should be able to point out



    the difference between excessive and non-excessive



    infiltration/inflow conditions.  Therefore, based on the



    recommendations, interpretations and evaluations of



    the engineering report, an intelligent rehabilitation



    program can be prepared which will serve as a basis



    for funding requirements.







    Questions and Comments:
g.  Preparation of the Proposed Rehabilitation Program



    TV reports can be voluminous.  A municipality is not



    usually interested in all of the details.  It is the



    job of the evaluating engineer to summarize the findings



    of the TV inspection, and to present the findings,



    recommendations and a rehabilitation program.







    Questions and Comments:

-------
                              -38-
THE NEED FOR PUBLIC RELATIONS



The municipality now knows its entire problem.  It is able to



witness the problem on video tape.  It now has a budget, it



feels comfortable in what it has to do ... but not so comfortable



in raising the necessary money or seeking the support of the



taxpayers.  Here again, the engineer must take an active part



in presenting the repair and rehabilitation program to the public.



No matter how justified the project may be, the public must feel



the urgent need for the work and must feel that the projects, as



recommended, are worthwhile.  It has been found that most municipal



councils are more than willing to hold a public meeting on this



matter.  Announcing these meetings in the news media and inviting



any and all interested parties to hear and see the results of the



TV inspection are excellent civic public relations gestures.







It is becoming more and more apparent that the consulting engineer



must become cognizant of the importance of public relations in his



work.  A well conducted presentation of an infiltration/inflow



study using video tape equipment, large color-coded overlay maps



and layman oriented engineering reports can serve as valuable



tools at any public meeting.  Showing selected portions of the video



tapes which depict significant infiltration/inflow, structural



deficiencies and as well as sound sections of pipe gives the



interested citizen an opportunity to witness first hand the need



for a rehabilitation program.  Such meetings can be held in a

-------
                              -39-
council chamber, school auditorium or some other appropriate



place where a large group of people can gather. The engineer



can explain to the public the findings of his report and the



recommendations for rehabilitation.







In the case of new treatment works, the design consultant can



explain his phase of the work and how it correlates to the



collection system evaluations.  The mayor or some other municipal



official can explain the position of the council and the course



of action they plan to take.  An appropriate question and answer



period stimulates further interest.  In this way, the general



public can recognize the need for money to be expended in correcting



the infiltration/inflow problem.  The pictorial, graphic and docu-



mented evidence is available for all to see.







Questions and Comments:

-------
                              -40-
PHASE III - REHABILITATION



Figure 4 refers to Phase III of the program.  A decision has now



been made, based on the findings of the engineers'  reports, as to



which sewers will not need any work, which sewers can be successfully



grouted, relined or replaced to eliminate the sources of infiltration/



inflow, the amount of street repair that will be required,  and a



total program whereby the engineer will be able to prepare  plans



and specifications for each class of work.  It should be the



responsibility of the engineer to give serious consideration to



all methods of rehabilitation.  These considerations are a  part of



the analytical work encompassed in the engineering report for



television inspection.






     a.  Sewer Repair



         Sewer repair is defined as the partial physical replace-



         ment, internal or external grouting, or relining of the



         sewer pipe.  The cost of rehabilitation varies over a



         wide range.  Engineers should take into account local



         construction costs, availability of  local contractors,



         etc. to determine meaningful costs for rehabilitation



         of the sewer pipe.



             Grouting



             In those cases where sewer grouting is recommended,



             a word of caution is in order.  Not all soils  will



             accept grout.  The engineer should familiarize



             himself with the limitation of all available

-------
                 -41-
grouting technology.  If he is not acquainted
with the latest techniques available, he should
make it his professional duty to learn.  There
are limitations as to the types of soil that will
readily accept grout and remain permanent.
There are some grouting materials that are definitely
not recommended for sewer rehabilitation.

A recent innovation in sewer sealing technology,
involving the use of elastomeric polymer grouts
has been developed.  This technique involves internal
in-place application of a new gasket to the pipe
structure itself as compared to the common accepted
procedure of grouting the soil surrounding the
sewer pipe.  However, at this date the methods
involving elastomeric polymer compounds are new
and untested in the field as to permanence, wearing
quality, permeability factors, adhering quality,
resistant to root penetration, etc.  The new method
does show promise in time but should not be confused
with the proven soil grouting techniques in common
use today.

The engineer should be forwarned that basic unit
grouting costs quoted generally do not reflect the
cost of the chemical grout needed which could inflate

-------
                 -42-
unit costs by 100% to 150% or more, depending



upon the geological characteristics of the soil



such as percolation rates, void ratios, etc.  The



engineer must include the cost of the chemical



grout in his rehabilitation estimates.  Grouting



should be accomplished by only experienced and




qualified personnel.  Attempts to restrict the



bidders as to the maximum amount of grout to be



pumped per joint can result in future joint failure.




On the other hand, excessive use of grout can be a



gross waste of money.  It is possible to pre-



determine the reasonable amount of grout expected



to be pumped per joint that will still assure a



permanent repair job.  Proven technology and time-



tested materials are the standards by which the



engineer must judge this work.  CAUTION; SEWERS TO



BE GROUTED SHOULD NOT BE DONE ON A"TEST AND/OR SEAL"



EVERY JOINT BASIS WITHOUT THE BENEFIT OF SYSTEM



EVALUATION.  SEALING EVERY JOINT IN ANY ONE MANHOLE



REACH CAN RESULT IN COSTS THAT COME CLOSE TO, OR



EXCEED, COMPLETE SEWER REPLACEMENT.








The engineer must also include in his estimate the



cost for correcting the sources of excessive inflow.



These types of corrections would include, but not

-------
                 -43-
be limited to, such items as disconnecting roof



drains that are directly connected to sanitary



sewers, replacement of manhole covers that contain



holes, raising manhole covers above the flood plain,



plugging off yard and driveway drains that are



connected to sanitary sewers, changing grades to



eliminate ponding situations, etc.








IN CONSIDERING ANY REHABILITATION WORK, THE ENGINEER



SHOULD ALWAYS KEEP IN MIND THE QUESTION, "HOW MUCH



INFILTRATION/INFLOW, IN TERMS OF G.P.M., WILL BE



ELIMINATED FOR THE DOLLARS OF REHABILITATION MONEY



SPENT AND ... WHAT PER CENT OF THE TOTAL INFILTRATION/



INFLOW PROBLEM IS BEING SOLVED BY SUCH WORK?"








It would require a separate presentation and lengthy



discussion to adequately cover the technology and



methodology of sewer grouting.  At this point it is



safe to emphasize that there are many responsible



sewer grouting firms throughout the country with



expertise from whom the consulting engineers can obtain



reliable information.  The consultant must obtain



this information and seek the advice of such firms



in preparing the rehabilitation costs for the proposed



rehabilitation program.  It is the responsibility of



the engineer to accurately determine the costs of the

-------
                         -44-
        rehabilitation work he proposes,
    Questions and Comments:
b.  Pipe Relining



    Another alternative for the rehabilitation of existing



    sewer systems is the recently developed technology



    of pipe relining.   The location,  type and condition of



    sewer to be rehabilitated will determine the feasibility



    of this method.








    To date, relining  technology has  not progressed to the



    point where unit costing procedures can be standardized.



    Complications arising from the reconnection of house



    services or the  backfilling of the void between the lines



    and the existing pipe can result  in added costs not



    anticipated in the'rehabilitation estimate.  Relining is a



    method for achieving the rehabilitation objective and



    should be compared with other alternatives on a cost



    effective basis.

-------
                         -45-
    Questions and Comments:
c.   Sewer Replacement



    The latest standards for new sewer construction need not



    be explained here.  Modern methods of acceptance of new



    sewer work, such as low pressure air testing,  have been



    well publicized.








    In those cases where complete sewer replacement is



    recommended, consideration must be given to dealing with



    the reconnection of existing house services,  the proximity



    of other utilities, the traffic disruption, and a host



    of other factors that normally become involved in this



    sort of rehabilitation.  Again, the costs for  this work



    will depend on local experiences.








    Questions and Comments:

-------
                         -46-
d.  Finalization of Treatment Plant Design



    Once the quantity of excessive infiltration/inflow has



    been identified, the consultant can begin to seriously



    consider finalizing the hydraulic design parameters



    for the wastewater treatment works.  He can be



    comfortable that he has a handle on the infiltration/



    inflow problem and that it will be brought under



    control.








    The engineer can now prepare plans and specifications



    for the sewer system rehabilitation work along with



    those for the construction or expansion of the



    treatment works.,  There is assurance that the new



    treatment works will accept all of the waste water.



    Intensive rainfalls will not cause basement flooding



    raw sewage by-passing,   lift stations will not be



    overloaded and the groundwater infiltration will be



    controlled.  The wastewater treatment works will



    function and serve the  needs of the community.







    Questions and Comments:

-------
                              -47-
SUMMARY



Infiltration/inflow of extraneous waters in sewer systems cause



many problems including raw sewage by-passing.  The "Zero Dis-



charge" federal goal for pollution control has created new



considerations that the engineer must now face in dealing with the



design of wastewater treatment works.  The recent advent of



television inspection cameras, sewer relining, plus external



and internal grouting equipment, has provided the engineer with



useful and valuable tools for implementation of sewer system



rehabilitation.  However, the use of such equipment to solve the



infiltration/inflow problem without the benefit of a logical



and systematic approach can prove to be costly and ineffective.

-------
  -48-
APPENDIX

-------
                                                    FIGURE 1
                                  A "PHASED" PROGRAM FOR SEWER SYSTEM EVALUATION
                                  AND REHABILITATION INFILTRATION/INFLOW STUDIES

                                    PHASE I      INFILTRATION/INFLOW ANALYSIS

                                    PHASE II     FIELD INVESTIGATION AND SURVEY

                                    PHASE III    REHABILITATION
                 FIGURE 2
                 PHASE I

        INFILTRATION/INFLOW ANALYSIS

a. Patterned Interviews

b. Sanitary and Storm Sewer Map Study

c. System Flow Diagrams

d. Dry vs Wet Weather Flow Determinations

e. Preliminary Field Survey and Selective Flow Tests

f. Determination of Excessive or Non-Excessive
   Infiltration/Inflow

g. Establish a Plan of Action, Budget and
   Timetable for Execution
                                                                                 FIGURE 3
                 PHASE II

     FIELD INVESTIGATION AND SURVEY

a. Physical Survey and Groundwater Analysis

b. Rainfall Simulation                     <•

c. Prepare Engineering Report and Analysis

d. Preparatory Sewer Cleaning

e. Television Inspection of Preselected Sewers

f. Preparation of the Evaluation Survey Report
   and Analysis

g. Preparation of the Proposed Rehabilitation
   Program
vo
I
                                                    FIGURE  4
                                                    PHASE  III

                                                  REHABILITATION

                                    a.  Sewer Repair

                                    b.  Pipe Relining

                                    c.  Sewer Replacement

                                    d.  Finalization of Treatment Plant Design

-------
                     -50-
                    FIGURE 5
     STATIC   GROUNDWATER  GAGE
             INSTALLATION
(L



(5W/



^

\
Yi



y x xxxxxxxxxxk
^7 — ^





^

s
/^






^^^



                   SECURE  TUBE
                     TO STEPS
                               MEASURE  FROM  THE  TOP
                               OF EACH PIPE  TO  THE
                               WATER  LEVEL  IN THE TUBE
                                 INSTALL GAGE AS
                                 NEAR AS POSSIBLE TO
                                 THE  TOP OF THE
                                 LOWEST PIPE IN THE
                                 MANHOLE.
                    GROUNDWATER
                        GAGE
                           •'.: •: :*.' •. -s.*
                           ' • -v' '•'.*•/.'•
        INVERT

-------
   Public Law 92-500
92nd Congress, S. 2770
    October  18, 1972
                                               86 STAT. 816
                                               trol Aot Amend-
                                                     °f
            To amend the Federal Water Pollution Control Act.

  Be it enacted by the Senate and House of Representatives of  the
United States of America in Congress assembled, That this Act may be  Federal Water
cited as the "Federal Water  Pollution Control Act Amendments of  Pollution Con-
1972".
  SEC. 2. The Federal Water Pollution Control Act is amended to read
as follows:                                                        84 stat. 91.
                                                                  33 USC 1151
   "TITLE I—RESEARCH AND RELATED PROGRAMS     note.

                ''DECLARATION OF GOALS AND POLICY

  "SEC. 101. (a) The objective of this Act is to restore and maintain
the chemical, physicalj and biological integrity of the Nation's waters.
In order to achieve this objective it is hereby declared that, consistent
with the provisions of this Act—
      " (1) it is the national goal that the discharge of pollutants into
    the navigable waters be eliminated by 1985;
      " (2)  it is the national goal that wherever attainable, an interim
    goal of water quality which provides for the protection and
    propagation of fish, shellfish, and wildlife and provides for recrea-
    tion in and on the water be achieved by July 1,1983;
      " (3)  it is the national policy that the discharge of toxic pollut-
    ants in toxic amounts be prohibited;
      "(4)  it is the national policy that Federal financial assistance
    be provided to construct  publicly owned waste treatment works;
      "(5)  it is the national policy that areawide waste treatment
    management planning processes be developed and implemented
    to assure adequate control of sources of pollutants in each State;
    and
      " (6)  it is the national policy that a major research and demon-
    stration effort be made to develop technology necessary to elimi-
    nate the discharge of pollutants into the navigable waters, waters
    of the contiguous zone, and the oceans.
  •'(b) It is the policy of the  Congress to  recognize, preserve, and
protect the primary responsibilities and rights of States to prevent.
reduce, and eliminate pollution, to plan  the development and use (in-
cluding restoration, preservation, and  enhancement) of land and
water resources, and to consult with the  Administrator in the exercise
of his authority under this Act. It is further the policy of the Congress
to support and aid research relating to the prevention, reduction, and
elimination of pollution, and to provide Federal technical services and
financial aid to State and interstate agencies and municipalities in con-
nection with the prevention,  reduction,  and elimination of pollution.
  "(c) It is further the policy of Congress that the  President, act-
ing through the Secretary of State and such national and international
organizations as he determines appropriate, shall take such action as
may be necessary to insure that to the fullest extent possible all for-
eign countries shall take meaningful action for the prevention, reduc-
tion, and elimination of pollution in their waters and in international
waters and for the achievement of goals regarding the elimination of
discharge of pollutants  and the improvement of water quality to at
least the same extent as the United States does under its  laws.
  "(d) Except as otherwise expressly provided in this Act, the Ad-  Administration.
ministrator of the Environmental Protection Agency (hereinafter in
this  Act called  'Administrator') shall administer this Act.

-------
          October 18, 1972        -19-        Pub. Law  92-500 86 STAT> 834

               ;'(1) the recycling of potential sewage pollutants through the
              production of agriculture, silviculture, or aquaculture products, or
              any combination thereof;
               "(2) the confined and  contained  disposal of pollutants not
              recycled;
               ''(3) the reclamation of wastewater; and
               "(4) the ultimate disposal of sludge in a manner that will not
              result in environmental hazards.
            "(e) The Administrator shall encourage waste treatment manage-
          ment which results in integrating facilities for sewage treatment and
          recycling -\yith facilities to treat, dispose of, or utilize other industrial
          and municipal wastes, including but not limited to solid waste and
          waste heat and thermal discharges. Such integrated facilities shall be
          designed and operated to produce revenues in excess of capital and
          operation  and maintenance costs and such revenues shall be used by
          the designated regional management agency to aid in financing other
          environmental improvement programs.
            il(f) The Administrator shall encourage waste treatment  manage-
          ment which combines 'open space' and recreational considerations with
          such management.
            "({?)(!) The Administrator is authorized to make grants to any
          State, municipality,  or intermunicipal or interstate agency for the
          construction of pub'licly owned treatment works.
            "(2) The Administrator shall not make grants from funds author- Condi-tions.
          ized for any fiscal year beginning after June 30, 1974, to any State,
          municipality, or intermunicipal or interstate agency for the erection,
          building, acquisition, alteration, remodeling, improvement, or exten-
          sion of treatment works unless the grant applicant has satisfactorily
          demonstrated to the Administrator that—
               " (A) alternative waste management techniques have been stud-
              ied and  evaluated and the works proposed for grant assistance
              will provide for the application of  the best practicable waste
              treatment technology over the life of the works consistent with the
              purposes of this title; and
               "(B) as appropriate, the works proposed for grant assistance
              will take into account and allow to the extent practicable the
              application of technology at a later date which will provide for
              the reclaiming or recycling of water or otherwise eliminate the
              discharge of pollutants.

   "(3)  The Administrator  shall not  approve any grant after July 1,
1973, for treatment  works under this section unless the applicant shows
to the satisfaction  of the  Administrator  that each sewer collection
system discharging  into such treatment Avorks is not subject to excessive
infiltration.
   "(4)  The Administrator is authorized to make grants to applicants
for treatment works grants under this section for- such  sewer system
evaluation studies  as may be  necessary to  carry out the requirements
of paragraph (3)  of  this  subsection. Such grants shall be  made in
accordance with  rules and regulations promulgated by the Adminis-
trator. Initial rules and  regulations  shall be promulgated under  this   Rules and
paragraph not later than 120 days after the date of enactment of the   regulations,
Federal "Water Pollution Control Act  Amendments of 1972.


                             "FEDERAL SHARE

   "SEC. 202. (a)  The amount of any grant for treatment works made
under this Act from  funds authorized for any  fiscal year beginning
after June 30,1971, shall be 75 per centum of the cost of construction

-------
             66 STAT. 835  Pub- Law 92-500        -20-        October 18, 1972

                         thereof (as approved by the Administrator). Any grant (other than
                         for reimbursement) made prior to the date of enactment of the Federal
                         Water Pollution Control Act Amendments of 1972 from any funds
                         authorized for any fiscal year beginning after June 30, 1971, shall,
                         upon the request of the applicant, be increased to the applicable per-
                         centage under this section.
                           "(b) The amount  of the  grant  for any project approved by the
                         Administrator after January 1,1971, and before July 1,1971, for the
                         construction of treatment works,  the actual erection, building  or
                         acquisition of which  was not commenced prior to July 1, 1971, snail,
                         upon the request of the applicant, be increased to the applicable per-
                         centage under subsection (a) of this section for grants for treatment
                         works from funds for fiscal years beginning after June 30, 1971, with
                         respect to the cost of such actual erection, building, or acquisition. Such
                         increased amount shall be paid from any funds allocated to the State
                         in which the treatment works is located without regard to the fiscal
                         year for which  such funds were authorized. Such  increased amount
                         shall be paid for such project only if—
                               "(1) a sewage collection system that is a part of the same total
                             waste treatment system  as the treatment works for which such
                             grant was approved is under construction or is to be constructed
                             for use in conjunction with such treatment works, and if the cost
                             of such sewage collection system exceeds the cost of such treatment
                             works, and
                               "(2) the  State water pollution control agency or other appro-
                             priate State authority  certifies that  the quantity of available
                             ground water will be insufficient, inadequate,  or unsuitable for
                             public use, including the ecological preservation and recreational
                             use of surface water bodies, unless effluents from publicly-owned
                             treatment works after adequate treatment  are returned to the
                             ground water consistent with acceptable technological standards.


                           "PLANS. SPECIFICATIONS, ESTIMATES, AND PAYMENTS

                  "SEC. 203.  (a)  Each  applicant  for a  grant  shall  submit to  the
                Administrator for his approval, plans, specifications, and estimates for
                each  proposed project for the construction of  treatment  works  for
                which a grant is applied  for  under section  201(g)(l). from funds
                allotted to the State under section 205 and which otherwise meets the
                requirements of this Act.  The Administrator shall act upon such plans,
                specifications, and estimates as  soon as practicable after the same have
                been submitted, and his approval of any such plans, specifications, and
                estimates  shall be  deemed a  contractual obligation of the  United
                States for the payment of its proportional contribution to such project.
                  "(b)  The Administrator shall, from .time to time as the  work pro-
                gresses, make payments to the recipient  of  a grant for costs  of con-
Limitation,     struction incurred on a project. These payments shall at no time exceed
                the Federal share of the cost of construction incurred to the date of the
                voucher covering such payment plus the Federal share of the value of
                the materials which have been stockpiled in the vicinity of such con-
                struction in conformity to plans and specifications for the project.
                  " (c) After completion of a project and approval of the final voucher
                by the Administrator, he shall pay out of the appropriate sums  the
                unpaid  balance  of the Federal share payable  on account of such
                project.
                           "SEC. 204. (a)  Before approving grants for anv project for any
                         treatment works  under section 201(g)(l) the Administrator shall
                         determine—

-------
  86 STAT. B43
              Pub. Law 92-500
                             -28-
October 18,  1972
Appropriation.
Teohnioal
assistance.
Appropriation.
79 Stat. 244.
42 USC 1962
note.
Annual report
to Congress.
Appropriation.
  "(3) Each applicant for a grant under this subsection shall submit
to the Administrator for his approval each proposal for which a grant
is applied for under  this subsection. The Administrator shall act
upon such proposal as soon as practicable after it has been submitted.
and his approval of  that proposal shall be deemed a contractual
obligation of the United  States for the payment of  its contribu-
tion to such proposal. There is authorizd to be appropriated to carry
out this subsection not to exceed $50,000,000 for the fiscal year ending
June 30,  1973, not to exceed $100.000,000 for the  fiscal year ending
June 30, 1974, and not to exceed  $150,000,000 for the, fiscal yenr
ending June 30,1975.
  " (g) The Administrator is authorized, upon request of the Governor
or the designated planning agency, and without reimbursement, to con-
sult with, and provide technical assistance to, any  agency designated
under subsection (a)  of this section in the development of areavide
waste  treatment management plans  under subsection (b) of this
section.
  "(h)(l) The Secretary of the Army, acting  through the Chief of
Engineers, in cooperation with the Administrator is authorized and
directed, upon request of the  Governor or the designated planning
organization, to consult with, and provide technical assistance to, any
agency designed under subsection  (a) of this  section  in developing
Mnd operating a continuing areavide. waste treatment management
planning process under subsection (b) of this section.
  " (2) There is authorized to be appropriated to the Secretary of the
Army, to carry out this subsection, not to exceed $50.000.000 per fiscal
year for the fiscal years ending June 30, 1973, and  June 30, 1974.

                       "BASIN  PLANNINO

  "SEC. 209 (a) The President, acting through the Water Resources
Council, shall, as soon as practicable, prepare a Level B plan under tho
Water Resources Planning Act for all basins in the  United States. All
such plans shall be completed not later than January 1, 1980, except
that priority in the preparation of such plans shall be given to those
basins and portions thereof which are within those areas designated
under paragraphs (2), (3), and  (4) of subsection  (a)  of section 208
of this Act.
  "(b) The President, acting through the Water Resources Council.
shall report annually to Congress on progress being made in carrying
out this section. The first such report shall be submitted not later than
January 31,1973.
  " (c)  There is authorized to be appropriated to carry out this section
not to exceed $200,000,000.

                       "ANNUAL SURVEY

  "SBC. 210. The Administrator shall annually make a survey to deter-
mine the efficiency of the operation and maintenance  of treatment works
constructed with grants made under this Act. as compared to the effi-
ciency  planned at the time the grant  was made. The results of such
iinnual survey shall be included in'the report, required under section
.-)lfi(a)ofthisAcf.
                           •'
                            SEWAGE  COLLECTION  SYSTEMS
      "SEC. 211.  No grant  shall be made for a sewage  collection system
   under this title unless such grant (1) is for replacement or major reha-
   bilitation of an existing collection system and is necessary to the total
   integrity and performance of the waste treatment works servicing such

-------
        October 18, 1972
                               -29-
Pub. Law 92-500
                                                           86 STAT. 844
        community, or (2) is for a new collection system in an existing com-
        munity with sufficient existing or planned capacity adequately to treat
        such collected sewage and is consistent with section 201 of this Act.

                           "DEFINITIONS

  "SEC. 212. As used in this title—
  "(1)  The term 'construction' means any one or more of the follow-
ing: preliminary planning to determine the feasibility  of treatment
works, engineering, architectural, legal, fiscal, or economic investiga-
tions or studies, surveys, designs, plans, working drawings, specifica-
tions,  procedures, or  other  necessary  actions, erection,  building,
acquisition, alteration, remodeling, improvement,  or extension  of
treatment works,  or the inspection or supervision of any of  the
foregoing items.
  " (2) (A) The term 'treatment works' means any devices and systems
used in the storage, treatment, recycling, and reclamation of municipal
sewage  or industrial  wastes of a liquid  nature to implement section
201 of this Act, or  necessary to recycle or reuse water at the most eco-
nomical cost over the estimated life of the Avorks, including intercept-
ing sewers, outfall sewers, seAvage collection systems, pumping, pOAver,
and other equipment, and their appurtenances; extensions, improve-
ments, remodeling, additions, and alterations thereof; elements essen-
tial to provide a reliable recycled supply such as standby treatment
units and clear Avell facilities; and any Avorks, including site acquisition
of the land that Avill be an integral part of the treatment process or is
used for ultimate disposal of residues resulting from such treatment.
  "(B)  In addition to the definition contained in subparagraph (A)
of this paragraph,  'treatment  AA-orks' means any other method or sys-
tem for preventing, abating, reducing, storing, treating, separating,
or disposing of  municipal Avaste, including storm  Avater  runoff,  or
industrial .waste, including waste in combined storm Avater  and sani-
tary seAver systems. Any application for construction grants  Avhich
includes wholly or in part such methods or systems shall, in accordance
Avith guidelines published by the Administrator pursuant to subpara-
graph (C)  of this paragraph, contain  adequate data and analysis
demonstrating such proposal  to be, OA-er the  life of such Avorks, the
most cost efficient alternative  to comply Avith sections 301 or 302  of
this Act,  or the requirements of section 201 of this Act.
  "(C)  For the purposes of subparagraph (B) of this paragraph, the
Administrator shall,  Avithin one hundred and eighty days  after the
date of enactment  of this title, publish and thereafter revise no less
often than annually,  guidelines  for the  evaluation  of  methods,
including cost-effective analysis, described in subparagraph (B)  of
this paragraph.
  "(3)  The term  'replacement' as  used in  this title  means  those
expenditures for obtaining and installing equipment, accessories, or
appurtenances during the useful life of the treatment Avorks necessary
to maintain the capacity  and performance for Avhich such Avorks are
designed and constructed.

            "TITLE III—STANDARDS AND ENFORCEMENT

                         "EFFLUENT LIMITATIONS

          "SEC. 301. (a) Except as in compliance with this section and sec-
        tions 302, 306, 307, 318, 402, and 404 of this Act, the discharge of any
        pollutant by any person shall be unlawful.
          "(b) In order to carry out the objective of this Act there shall be
        achieved—
                                                                    Methods,
                                                                    evaluation
                                                                    guidelines,
                                                                    publication.

-------