EPA-AA-TEB-82-7
         The Portland Study
                 by


          H. Anthony Ashby
              June  1982
     Test and Evaluation Branch
Emission Control Technology Division
      Office of Mobile Sources
U.S. Environmental Protection Agency

-------
Summary

The  Portland  Study encompassed  a  series of  test  programs  conducted  for
EPA by a contractor in Portland, Oregon  from  September 1977  through April
1982.  The objectives of the major  programs were to  study the correlation
between short  inspection tests and  the  Federal Test  Procedure,  to study
the emission-reduction effectiveness of  an operating  vehicle inspection-
maintenance  (I/M)  program, and  to  study  post-I/M  deterioration.   Other
important  tasks completed  in the   Portland  Study  included an  Emission
Factors  test  program,  an  evaluation of  the  effectiveness of  mechanic
training,  a  study  of   the effect  of  I/M  on  light-duty  trucks,  and
evaluations  of  the  in-use  performance  of   three-way catalyst  emission
control systems.

A  total  of 8,465  emission test  sequences  were conducted  (all of  which
included at least the FTP and various short t«;sts),  at a  cost for the  two
contracts of $5,258,328.

Data  are  on magnetic  tape in Ann  Arbor under the  cognizance of  either
Test  and  Evaluation Branch  (TEB)  or I/M  Staff personnel.   Included  are
mass  emissions  and  tailpipe  concentration  data,  vehicle  descriptions,
maintenance  information,  vehicle   owner  questionnaires,  diagnostic  and
repair information,  and  so on.  Portland  Study data  have been discussed
in I/M Staff reports, TEB  reports,  and papers presented to  the Society of
Automotive Engineers and the Air Pollution Control  Association.

-------
Introduction

    This  report  describes  the  two   phases  of  the  Portland  Study,  a
contractor-operated vehicle  emission  test program  that  was  conducted in
Portland, Oregon,  over  a  five-year period beginning in  1977.   The  report
includes information on the  history of  the program,  the  objectives  of the
various  tasks  that  were  completed,  program  design,   and   some  of  the
problems encountered.  It does  not include any  test  results,  which  may be
found  in contractor  test reports  available  from the  library at the  EPA
Motor  Vehicle Emission  Laboratory in Ann Arbor, Michigan.  Test  data and
other  information  are  also  stored on magnetic  tape under  the  cognizance
of I/M Staff and Test and Evaluation Branch personnel in Ann Arbor.

    Motor vehicle  emission inspection  and maintenance has  been  recognized
for  years  by  EPA  as   an  integral  part  of  the  total  approach  toward
reducing  exhaust  emissions  from  motor vehicles.   In  late 1975, a  study
was conceived by Characterization and  Applications Branch  (CAB)  personnel
for examining two  major  areas,  of interest with respect to  I/M programs.
These  areas,  on which  very  little  data were  available,   were:   1)  the
emission  data  correlation  between the  offical  EPA  test  for  measuring
exhaust emissions  (the cold  start Federal Test  Procedure)  and the various
simple, short inspection tests  that would be used in I/M programs;  and 2)
the  effectiveness  of  an   operating   inspection  program  in   terms  of
identifying  high-emission  cars,  emission  reductions  due  to  repairs,
costs, and the emission histories of cars subject  to I/M programs.

    At the time the study was being designed, I/M programs were operating
in  the state of  New Jersey and in  the metropolitan  area  of  Portland,
Oregon.   Both  were  considered  to be  acceptable  sites  for the  study.
Portland  was chosen  because   of  slightly lower  costs,  and  because  a
question had arisen  as  to whether the  New Jersey Inspection program was
going to continue.

-------
I.  Short Test Correlation and Effectiveness Study

Contract Information

    Title:  Short Test Correlation and Effectiveness Study
    Contract No.:  68-03-2513
    Contractor:  Hamilton Test Systems, Inc.
    Cost:  $3,135,983
    Number of Tests:  5,874
    Period of Performance:  February 3, 1977 through July 9,  1979
                            (except for Final Report)

Objectives

    The  Portland  Study as  originally planned consisted  of  two parts  or
elements.  The  objective of  Element  I was  t:o  determine the  correlation
between   the   Federal   Test   Procedure,    conducted   under   laboratory
conditions,  and  various  short  tests  that might  be  used   in  actual
inspection  programs.    Such   correlation   was   necessary  in   order   to
implement  the  emission  performance warranty  provisions  of  the  Clean  Air
Act (Section 207(b)).

    The  objective of  Element  II was  to  evaluate the effectiveness of  an
operating I/M program (that run  by  the Oregon Department of  Environmental
Quality) (DEQ).  The  evaluation was in terms of the idle test's  ability
to identify  gross  emitters,  the effectiveness  of the repair  industry  in
reducing emissions,  and the  deterioration  ol: emissions  over  a  one-year
period.

    Well into  the  program a  third  element   was  added.   The  objective  of
Element  III, the post-I/M deterioration study, was  to collect  information
on deterioration of emissions  over  short periods  of  time after passing  an
inspection test.

-------
Chronology

     12-08-75
     06-11-76



     06-24-76

     07-26-76
     08-23-76

     09-23-76

     10-22-76



     11-24-76

     12-08-76



     12-15/16-76


     01-15-77


     02-03-77

     04-11-77


     04 and 05-77
CAB personnel  initiated Procurement
Request for  "Short  Test Correlation
and Effectiveness  Study."  Estimated
cost:  $2.8 million.

Request for  Proposal  No.  CI 76-0070
issued   by   Negotiated   Contracts
Branch

Bidders' Conference held in Portland

Amendment  to  RFP  issued;  Contract
type  changed  from  Cost Plus  Fixed
Fee to Firm Fixed Price

Proposal  submittal  date moved  back
two weeks, from 08-09-76 to 08-23-76

Minor  Scope   of  Work  changes  in
response  to   questions   raised  in
Bidders' Conference

Proposal received (one offerer only)

CAB Technical Evaluation completed

Received   HTS    clarification    of
questions    raised    in   Technical
Evaluation

Cost Advisor's Report receiived

Meeting   with  HTS   and   NCB   in
Cincinnati   to  discuss   source  of
Element II control fleet

Negotiations in Ann Arbor  on  Scope
of Work

Agreement  achieved  on  Firm  Fixed
Price:  $2,730,000

Contract signed

EPA  personnel  arrived  in  Portland
to set up Project  Office

Modification   of    test   facility,
installation   of   test   equipment,
training of personnel

-------
05-11/12-77


08-26-77


09-20-77


09-01-78


01-22-79

01-24-79


04-02-79


07-06-79
Meeting  in  Ann  Arbor  to  resolve
data handling problems

HTS  terminated  contract  with  OLI
(testing subcontractor)

First  emission   test   successfully
completed

Short   tests  by   DEQ   inspectors
halted.

Element III testing began

Element   I   testing   halted   (1950
tests)

Element  II  testing completed  (3220
tests)

Element  III  testing completed  (704
tests)

-------
Program Design

     Element I

     For the Element I correlation  study,  59  t:est  vehicle groups or cells
were  chosen  to  represent  the  national   fleet   of  1975-77  model  year
passenger  cars.   The  cells  were defined  by model  year,  manufacturer,
engine,   transmission   and   vehicle   weight.   Considering   statistical
validity for the  intended short test-FTP correlation, the  minimum sample
size  for  each  cell was  set  at  40  vehicles.   The criteria by  which the
cells were defined included:  the  widest  possible coverage of  vehicles and
engines,  quantities  produced,  technological  significance, likelihood  of
future  production,  and  availability  in  the Portland   area.   The  test
sequence  included  idle   and  other   short  tests conducted   at  a  DEQ
inspection station, the same  tests at the HTS  facility,  and the FTP.

     Originally,  there  were  to be  2400 cars tested for  Element I,  of
which 220 would  also  be involved in the Element  II  effectiveness study.
As  the  program developed, it  was necessary to recruit  many  replacements
for  participants  who  dropped out  of  the  Element  II  program.   Also,
Element  I testing  was  halted  ahead  of  schedule when  I/M  Staff  data
analysis indicated that sufficient data  on FTP-short  test correlation had
been  collected.   This  resulted in  a  total of 2207  tests for Element  I.
Of  these, 1950 cars  were tested  exclusively  for Element I, and  257  were
involved in both Element I and Element II.

     Element II

     For  the  Element   II  effectiveness  study,   a   fleet  of  cars  from
Portland (subject to I/M)  and a  similar fleet from  Eugene, Oregon (non-
I/M area, to serve as  the experimental  control)  were tested  initially  in
as-received condition and  then at three month, i.e., quarterly  intervals
for  one  year.   An  additional  test  was  conducted  on  Portland  cars
initially  failing the  DEQ   inspection,  following repair sufficient  to
enable the car to pass the inspection.   Thus,  Element II testing produced
emission  histories  of  cars  subject  to   I/M  for  comparison  with  the
histories of cars not  subject to I/M.   In  addition,  the  effectiveness  of
repairs to  failed cars,  done  in the repair  Industry at the  car owner's
expense, was  clearly  shown.   The test  sequence included the FTP,  HFET,
hot start FTP,  and various short tests.

     The  test  fleet  of  660  cars  was  divided  into model  year  groups
1972-74 and  1975-1977,  the composition  of  each  group reflecting  Oregon
registration figures.  Within each model  year group, about 110 Portland
cars  passed  the  DEQ  inspection,  110  Portland cars  failed,  and  110  were
from Eugene.  Element II attrition was significant:   7%  to 9%  of the  cars
remaining in the  program dropped  out  each  quarter.  As  a  result,  over  50
cars had to be recruited to replace those  whos?e owners dropped out of the
program.  A  total of  715  cars were  initially  tested   and  506,  or  71%,
received  the   fourth  quarterly  re test.   By  contractual  requirement  the
total number of Element II tests was 3220.

-------
     Early in the  follow-on  contract,  second,  third,  and fourth quarterly
retests were conducted on  1975-77 Portland  cars  to  improve the Element II
data base.  This brought the completion total to 527 cars, or 74%.

     Element III

     The element III  post-I/M deterioration jitudy was  a negotiated-price
modification  to  the   original  contract.    The  Element  III  test  fleet
consisted  of  292 privately  owned  cars of  1975-77 model years  in  rough
proportion to the  Oregon registered population of those  model years,  but
with  sample  sizes  of  five  minimum and  nine  maximum.   The  recruiting
objective was to  start the test program on each car  at  the  beginning of
its biennial registration cycle  rather than at an unknown point  as in the
case  of  Element II.   Owners were  contacted at the  time  their  vehicles
were  due  to  be  reregistered  and   therefore  due   for  a  "real"  DEQ
inspection.  This was  accomplished  by recruiting on  the  basis of vehicle
model year and the first letter  on  the license  plate, which indicates the
month in which the car was registered.

     The initial test  was  in as-received condition.   Retests  were at one,
two,  or  three  month  intervals  for  each  third  of  the  test  fleet,
respectively.  Cars were entered in  the  program without  regard  to  their
DEQ pass/fail  status,  and it  turned  out  thai: 113  (39%) were DEQ fails.
The owners of those cars were  asked  to have the  cars  repaired to pass the
DEQ inspection (108 did so) and the cars  were retested after the repair.

     If  a  vehicle showed  significant deterioration  of  emissions on  the
one,  two,  or three month  retest,  the owner was interviewed  to  possibly
establish the reason.  With the owner's permission the car was  tuned by
the  contractor to  manufacturer's  specifications,  tested,  and  retested
after one  month.   There were  fourteen  such cars.   A total of  704  tests
were run in Element III.

DEQ Support

     An  important  phase  of  the  Element  I  correlation  study was  to have
short inspection tests conducted by  state employees at  a state inspection
station.  To this end  the  Oregon DEQ was awarded a contract,  "Support to
Correlation and I/M Study,"  to provide space at  an  inspection station for
test  equipment  installed by  HTS,  and to  provide the  services  of  state
inspectors  to conduct inspection  tests  on Element   I  cars  using  that
equipment.

     Because of changes  in EPA policy on the need  for correlation between
the FTP and loaded inspection  tests,  the contract with  the Oregon DEQ was
terminated by EPA on September 1, 1978.   By l:hat time 1182 cars  had been
tested by the DEQ personnel.  The total cost of the contract was £100,500.

Problems

     As  might  be  expected with  a  project  of  the  size  and  scope of  the
original  Portland  Study,   there   were   numerous  problems.    The   most
important ones will be discussed here, roughly in chronological order.

-------
     Element I Vehicle List

     The original vehicle  list  that  appeared in the RFP  and  the contract
consisted of 2400 cars of  1975-76  model  years.   They represented the four
major U.S. manufacturers plus 20  foreign marques including Alfa Romeo,  MG
and  Triumph.   Sample sizes  for various  vehicles  ranged  from  5  to  100.
Shortly  after  the  contract  was  signed  the  CAB Branch  Chief  determined
that  testing  1977 models  would be  desirable.   Further,  for  statistical
validity of  the desired FTP-short test  correlation,  the  minimum sample
size for a given  vehicle  type (defined as a  combination of manufacturer,
engine, transmission, and weight class) had to be 40.

     The Element  I  test fleet  was completely redesigned,  using criteria
including:  the   widest   possible   coverage   of  vehicle  and   engines,
quantities  produced,  technological  significance,  likelihood  of  future
production, and availability in the  Portland area.  Because  the contract
was  for a Firm Fixed  Price,  this  change  had  to  be  accomplished by  a
contract modification.

     Data Formatting and Handling

     Early on, a major problem  developed over EPA's  requirements for data
collecting and  formatting  as revealed in the EPA proposed data formats.
These  had  the  effect  of  increasing  the  contractor's  equipment  and
personnel  requirements  beyond  its  contractual  responsibilities.   After
considerable discussion  and negotiation,  the data  collecting,  handling,
and  formatting  requirements  were  agreed to.  The  main elements  of  the
agreement were that HTS would collect  the additional data required by EPA
and  rearrange all data  into EPA's formats,  using an EPA-paid  account  on
the   Michigan   Terminal   System.    HTS   would   supply   terminals   and
teleprinters both for itself and  the  EPA Portland  Study  project office.
The  agreement  was  documented as  contract  modification  number  3.   This
data handling system worked well for as long ,is it was used.

     Program Delays

     The  contractor's original  plan  of  performance was  that  equipment
would  be  installed  in  May 1977,  with testing beginning  in  June  at  the
rate  of 20  tests  per  day.   The  actual program startup  was  much  more
time-consuming, and  the testing  reached 20  per day only by July 1978.
Problems were numerous.  Calibration gases  and  chassis  dynamometers  were
delivered  on  schedule,  but other  test equipment  was   a  month  late.
Installation  and  checkout  were  complicated   by   wiring and  plumbing
mistakes  in  the  analyzers.   These  problems  were  aggravated  by  the
inability  of  the  testing  subcontractor  (Olson Laboratories,   Inc.)  to
organize and  manage  the  work  it  had to do.   In  late  August  1977  HTS
terminated  its  contract  with  OLI  and   assumed the  responsibility  for
vehicle  testing operations.   A  new  plan  of  performance was  submitted
showing  a  gradual  buildup  of  the  testing   rate  as equipment   was  made
operational and  new  test  technicians  were  trained.   The  first  official
test,  which  became  part  of  EPA's data  basu,  was  run  on September  20,
1977.  These delays  caused  the  program to slip  several  months  behind  the

-------
                                    10
original schedule.  EPA  thus  had to spend additional money  on its office
space in Portland and on its  contract  for  support  from the DEQ.   To cover
EPA's  extra expenses,  a downward  adjustment  in  the  price  of  a  later
modification to the HTS contract was negotiated.

     Vehicle Recruiting

     Vehicle recruiting  went  very well in terms of  the  public's response
to  the  HTS recruiting  letter.   Problems  did  occur with  respect  to  the
makeup of  the  fleet in  both Element I  and  Element II.   In Element  I,  HTS
recruited  off  the  top  of  the   registration  lists for  each  cell,  which
resulted in a  lot of  vanity plates and  letter-A license plates  getting
into the program.  HTS also  recruited  makes  in  bunches,  in violation of a
contractual  requirement.   At one  point  19  cars  had  been tested  in  one
cell and none,  or only a few,  in several  other cells.  The ideal  was to
have the Element  I cells be  filled  evenly,  with cars of  various  license
plate first-letters,  over  the  entire  10  months of  Element  I testing so
that climatic  effects in the  short test  to FTP correlation  could  be seen
for  all the  cells.  Technical directions  and a contract  modification
finally  got  HTS   squared   away  but  not  before  much  distortion  had
occurred.   At  the  end of Element  I  testing,  sample sizes ranged  from 32
to 45, where the ideal would have been 37.

     The same  vanity  plate and  A-plate  problems occurred in  Element  II.
A bigger problem had  to  do with the Element II  program  design.   Vehicles
were  recruited for  Element  II at  any  point:  in  their  two-year  Oregon
registration cycle;  the ideal  would  have be:en to recruit  them  at  the
beginning  of  that  cycle.   (An  EPA  remark  in the  Bidders'  Conference
indicates  that  such  was   EPA's  intent.)   Unfortunately  it  was  never
clearly stated in the RFP or  the contract.   The  result was that  cars were
recruited  off  registration lists  without  regard  to  when they  were last
inspected  by DEQ.   Therefore, the emissions  history  of  a car in  Element
II could be interrupted  by  maintenance sometime  during  the one-year study
if the  car needed  it  to pass the  DEQ  inspection.   Thanks to  Element  III
and its continuation  in  the  follow-on  contract,  data  did become  available
on cars in the first  year  after they passed i:he DEQ inspection.   Also to
help with  Element  II  data  analysis the Oregon Motor Vehicle  Division was
engaged to look up registration dates on Elemesnt II cars.

     Data  Packet Error Rate

     The   contractor's   original   proposal   stated   that   the   same
Hewlett-Packard computer used  to  present   driving cycles and  to  switch
valves  for CVS bag filling  would also select  gas analyzer ranges,  zero
and  span  the analyzers,  read sample  bag  concentrations and  CVS  inputs,
and  calculate  mass  emissions.    This  capability  was never  achieved  in
spite  of   attempts  by both OLI  and HTS.    The idea  of  hiring the  H-P
programming  service was rejected  by HTS  on  the  grounds  of  cost.   As  a
result the HTS data flow system included a large number  of manual  entries
and  interfacing,  and  manual  checking.  The HTS data  review  process  was
insufficient to ensure delivery to EPA of error-free data.

-------
                                     11
     The  error  rate was  very  high  for  several  months  -  from September
1977  through  April  1978  over  one  third  of the  data  packets submitted
contained error, and there  was no trend of  improvement.   After EPA began
simply   returning   erroneous  packets,  instead   of  also   including  a
description of  the  error, HTS  finally seemed  to  attend  to  the problem.
By June the error rate was down to an acceptable 10%.

     Contract Modifications

     Because this was  a Firm  Fixed  Price contract,  it  was  difficult to
change the  Scope  of Work, as EPA found  it necessary to do  several times
during the course of the  program.  For each  change the entire procurement
cycle  was involved:   preparation of  procurerient  package,  evaluation of
HTS response, price negotiation and  so on.   "his  often  led  to delays in
the implementation of the desired changes.

II.  Testing Support for Evaluation of I/M Issues

Contract Information

     Title:  Testing Support for Evaluation of I/M Issues
     Contract No.:  68-03-2829
     Contractor:  Hamilton Test Systems, Inc.
     Cost:  $2,122,345
     No. of Tests:  2591
     Period of  Performance:  June 10, 1979  through  April 14,  1982  (for
     testing operations)

Objective

     The  objective  of  the program was  primarily  to provide  EPA with the
capability  of  quickly obtaining  emission  data and  other  information to
answer questions and resolve issues  that might  arise  as  I/M programs  were
planned and implemented around  the country.   In general the  data were to
come  from  in-use,   privately   owned  light   duty  vehicles  recruited  in
Portland,  where an  I/M program  had been in operation  since  1975.   In
addition,   the   contract   would  provide   a   site   for   other  testing
requirements which could not be handled  by the  EPA Motor Vehicle Emission
Laboratory at Ann Arbor,  Michigan.   A total  of 1951  tests were conducted
for I/M support purposes.

     As  the  program developed  and  testing  requirements  were  defined  by
IMS and  TEB  personnel,  a significant  number of tests were  conducted for
which  I/M was  not  the rationale.   These included  tests  to  study  fuel
economy discrepancies between in-use and EPA values,  tests on cars from a
non-I/M area (Vancouver,  Washington)  for the: Emission Factors  data base,
and evaluation  of a  fuel  economy  retrofit  device.   Additional tests under
the  Project Officer's  direction  were  also run to  evaluate  alternate
fuels,   retrofits   and  other .  systems,   primarily  at  the   request  of
government  agencies  in  the  Portland  area.   A  total   of  640  non-I/M
oriented tests were conducted.

-------
                                       12
Chronology

     12-19-78      TEB   personnel   initiate   Procurement   Request   for
                   "Testing Support for Evaluation of I/M Issues"
     03-28-78      RFP No. CI 79-0118 issued (Sole Source Procurement)
     04-16-79      HTS proposal received
     05-04-79      TEB Technical Evaluation completed
     06-10-79      Work begun under Anticipatory Cost Letter
     07-26-79      Effective date of contract
     04-15-82      End of testing operations

Program Design

     The contract type - Cost Plus Fixed Fee -• made  it  relatively  easy to
give technical direction to HTS,  within  the  general  specifications of  the
contract.  The  assigned tasks,  called Test  Groups in  the  contract,  were
described  in Technical  Directions  which included  instructions in  these
areas:

         Vehicles to be recruited
         Recruiting methods
         Sequence of tests to be run
         Data to be collected
         Criteria for performing maintenance and retest

     Seventeen Test  Groups were  specified.   All  except  No.  15  required
the two-speed idle test conducted by the Oregon  DEQ,  the  FTP,  the  Highway
Fuel  Economy Test,  two  to  five chassis  dynamometer  short  tests,  and
underhood and diagnostic inspections.  In some  sequences  in Test Group 8,
the FTP was replaced with the hot start FTP.

     On  Test  Groups  14,   16,  and  17,  test  data  including  emissions
concentrations were  entered on EPA-specifiec!  forms  and  sent  to  Systex,
Inc., EPA's  data reduction  contractor.   On all  other  Test Groups,  test
information  including   mass   emissions  and.   fuel   economy  data   were
transmitted via telephone to MTS, reformatted,  and made  available  to EPA.

     Test Group Descriptions

     Following  are   brief  descriptions  of   the   tasks  completed  in  the
     program.

     Test Group 1 - Restorative Maintenance en Three-Way Catalyst Vehicles

     Three-way catalyst  cars of  1978-79  model  years tested  as  received
     and after restorative maintenance. 51 cars,  74 tests.

     Test Group 2 - Element II Continuation Tests.

     Quarterly  retests  were  continued  on  1975-77  Portland   cars  from
     Element  II  to  increase  the  number  of  cars  completing  the  full
     one-year series of tests.  22 cars,  50 l:ests.

-------
                                  13
Test Groups 3 and 4 - Element III Retests

 Element  III  cars  were re tested at intervals  of  6,  9 and  12  months
after  the initial  test.    Cars  failing  the  DEQ  inspection at  the
12-month point were given restorative maintenance  and  retested.   258
cars, 743 tests.

Test Group 5 - Effectiveness of EGR Repairs

Element II cars  with  defective EGR systems were  tested  as  received,
after  EGR repairs,  and after  six more  months  of  service in  the
owner's hands.  28 cars, 80 tests.

Test Group 6 - Heated Air Intake Disablement

Cars from the contractor's loaner  fleet  (1979-80 model years)  were
tested to  study the effect of  disabling  heated air intake systems.
10 cars,  20 tests.

Test Group 7 - Mechanic Training Evaluation Program

The objective of this  program was  to  evaluate  the effect of mechanic
training  on  emission  reductions  achieved  in  an  I/M  program.   The
training consisted  of  the  Colorado State University emission  repair
course.

Cars  failing  the   DEQ inspection were  tested  as-received,   after
repair  by   the  participating  mechanics,  and   after   restorative
maintenance  by  the contractor.   Matched  sets of cars  were  tested
this way before  and after  the  training  course was given, in a blind
study.  98 cars, 307 tests.

Test Group 8 - Evaluation of Potential Catalyst Diagnostic Tests

Cars from  the  contractor's  loaner fleet were  tested to  evaluate the
usefulness  of  various  short  tests   in  identifying   lead-poisoned
catalytic converters.   3 cars, 43 tests.

Test Group 9 - Vancouver Versus Portland Vehicle Emissions

Matching cars  (1976 and 1978 model years)  from the  two  cities  were
tested as-received  to  compare  emissions from I/M  and  non-I/M  areas.
212 cars, 212 tests.

Test Group 10 - Effect of Specific Maintenance Tasks  on Emission
                Repairs on I/M Failed  Vehicles

Test  Group   9   Vancouver   cars  that  failed  the  DEQ  inspection
as-received were repaired  in specified steps  by  the  contractor  and
retested.  35 cars, 41 tests.

-------
                                  14
Test Group 11 - Fuel Economy Shortfall Tests

Twenty  types  of 1978-80  model year  vehicles  (including four  light
duty  truck  models)  were  tested  to  provide  information  on  the
discrepancies between  in-use  fuel economy and the EPA  Buyer's  Guide
values.   The  sample  size  for  each  type  was  between  5  and  7
vehicles.   The  vehicles  were  tested  as-received;  those failing  to
meet Federal  emission standards  were  aliio tested after restorative
maintenance.  129 vehicles, 219 tests.

Test Group 12 - Effect of I/M on Light Duty Trucks

 Light duty trucks of  1976, 1978  and  1980 model  years  were  tested in
as-received  condition.   Those failing   the  state  inspection  were
repaired  commercially and  retested.   Selected   vehicles  were  also
given  restorative maintenance  by  the  contractor and  retested.   105
vehicles, 148 tests

Test Group 13 - Evaluation of 1981 Ford Open-Loop Three-Way  Catalyst
                Cars

Open-loop 1981  Ford  products  were  tested in  as-received  condition.
Those  exceeding  specified levels on  the  FTP  or  certain short  tests
were  given restorative  maintenance  and  retested.   Four  cars  were
given a series  of tests  using various fuels and  with  disablement of
emission control systems.  112 cars, 179 tests.

Test Group 14 - A Study of Emissions Froia Light-Duty  Vehicles in
                Vancouver, Washington.

Vehicles  of  1978-82  model  years  from  Vancouver  were  tested  in
as-received   condition  as   part   of   l:he  Emission   Factors   data
collection program.  Those failing  to  rae.et certain emission criteria
were retested following  restorative maintenance.  300  vehicles,  340
tests.

Test Group 15 - Evaluation of "Super-Mag Fuel Extender".

This device evaluation was  conducted pursuant to Section 511  of  the
Motor Vehicle Information and Cost Savings Act.  3 cars, 34  tests.

Test Group 16 - Problem Closed-Loop 3-way Catalyst Cars

As-received   and   after-maintenance   tests    were    performed   on
closed-loop 3-way catalyst  cars  with known or suspected problems in
those systems.  6 cars, 10 tests.

Test Group 17 - Disablement Testing of Closed-Loop Systems

Closed-loop cars  were  tested to  evaluate  the   effects of  various
disablements on FTP and short test emissions.   22 cars,  80 tests.

-------
                                       15
     In addition to  the  tasks described above, a  total  of 47  tests  were
conducted by  technical direction of  the EPA Project Officer.   Almost  all
of these were in response to  requests  from  two  government  agencies  in the
area.   For  the  Bonneville  Power  Administration,   tests  were  run  to
evaluate alcohol-gasoline blends,  a methanol-fueled car,  and  an  exhaust
system heat  shield  for  a vehicle  that  travels off-road.  For  the  Oregon
Department  of Environmental  Quality  Vehicle   Inspection  Program,  tests
were run on  aftermarket  turbochargers,  a retrofit  device,  a  gasohol fuel,
and a noncomplying  imported car.  A total  of about  6  tests  were  run  on:
a  liquefied  natural  gas  fueled  pickup  truck,  an  experimental  safety
vehicle, an energy storage system, and a methanol-fueled  car.

Program Conclusions

     The  last  of   several  modifications   to  the  contract   for  Testing
Support  for Evaluation  of  I/M  issues covered  testing  until  April  15,
1982.  The  final  test  sequence in the  program  was conducted,  as part  of
the Test Group 17 task,  on April 14.

     No   final   laboratory   qualification  procedure   was   conducted.
Calibration  and  calibration   checks  on  chassis  dynamometers,  constant
volume  samplers,  and  gas  analyzers  had  been  conducted  on  a  regularly
scheduled basis all  through the life  of  the program,  with EPA personnel
on  site.    The   EPA  Project  Officer  felt   that  a   final  laboratory
qualification, therefore, was unnecessary.

     All test equipment  was removed  by the  contractor and shipped  to  its
corporate  headquarters   in  Arizona,   and   the  facility  was  vacated  on
May/15, 1982.

Test Results
    Subject                          Contact

    Contractor's Test Reports on     MVEL Library
    Element I, Element II,
    Element III, and Test
    Groups 1 through 17

    I/M Staff Reports                Phil Lorang, Chief
    (See "Abstracts of I/M Tech-     I/M Staff
    nical Reports and Policy")

    Emission Factors Data Base       Lois Platte, TEB

-------