&EPA
               United States
               Environmental Protection
               Agency
                   Office of Mobile Source Air Pollution Control
                   Emission Control Technology Division
                   2565 Plymouth Road
                   Ann Arbor, Michigan 48105
               Air
EPA 460/3-84-012
April 1986
Costs To Convert  Coal To
Methanol

-------
                                           EPA 460/3-84-012
Costs  To Convert  Coal To  Methanol
                              by

                  David S. Moulton and Norman R. Sefer

                     Southwest Research Institute
                        6220 Culebra Road
                      San Antonio, Texas 78284

                       Contract No. 68-03-3162
                       Work Assignment No. 9

           EPA Project Officers: Robert J. Garbe and Craig A. Harvey
            EPA Branch Technical Representative: Thomas M. Baines


                           Prepared for

                ENVIRONMENTAL PROTECTION AGENCY
                Office of Mobile Source Air Pollution Control
                   Emission Control Technology Division
                        2565 Plymouth Road
                      Ann Arbor,  Michigan 48105
                           April 1986

-------
This report is issued by the Environmental Protection Agency to report technical data
of interest to a limited number of readers.  Copies are available free of charge to
Federal employees, current contractors and grantees, and nonprofit organizations - in
limited quantities -  from the  Library  Services  Office,  Environmental Protection
Agency, 2565 Plymouth Road, Ann Arbor, Michigan 4.8105.
This report was  furnished  to  the  Environmental Protection Agency by  Southwest
Research  Institute, 6220 Culebra Road, San Antonio, Texas, in  fulfillment  of  Work
Assignment 9 of Contract No. 68-03-3162.  The contents of this report are reproduced
herein as  received from Southwest Research Institute.   The opinions, findings, and
conclusions expressed are  those of  the author and not necessarily  those of the
Environmental Protection  Agency.  Mention of company or product names is not to be
considered as an endorsement by the Environmental Protection Agency.
                                       n

-------
                                 FOREWORD

     This  Work  Assignment  was initiated  by  the  Emission  Control  Technology
Division, Environmental Protection Agency, 2565 Plymouth Road, Ann Arbor, Michigan
48105. The effort on which this report is based was accomplished by the Department
of Emissions  Research  and  the  Department  of Energy Conversion and Combustion
Technology of Southwest Research Institute, 6220 Culebra Road, San Antonio,  Texas
78284.   This program, authorized by Work Assignment 9 under Contract 68-03-3162,
was initiated  August 18, 1983 and was completed September 28, 1984.   The program
was identified within Southwest Research Institute as Project 03-7338-000.

     This  Work  Assignment  was  conducted  by  Mr. David S. Moulton,  Research
Engineer and Mr. Norman R. Sefer, Senior Research Engineer.  Mr. Chares Hare was
Project Manager and was involved in the initial technical and fiscal negotiations and
subsequent major program decisions.  The EPA Project Officers  were Messrs. Robert
1. Garbe  and  Craig A. Harvey  of  the  Technical  Support  Staff,  Environmental
Protection Agency.
                                      in

-------
                                  ABSTRACT

     This report provides estimated costs of producing methanol transportation fuei
from  coal.    Estimates were made for  mine-mouth  plants  in  five different coal
producing regions, and uniform methods were used so the estimated sales prices could
be compared for market analysis.   In addition to plant-gate prices, delivered  prices
were  estimated  for  three  major  market  areas.      With  presently  available
transportation, the lowest delivered prices were for methanol production based  in the
southern  lignite  coal  region.   If  new  methanol-compatible  pipelines  were  to  be
constructed, the  lowest delivered prices would be for production based in the western
subbituminous  coal  region.   In  the western subbituminous  region, limited  water
resources would make  extensive planning and careful site selection necessary, but they
would not prevent the development of a  coal-to-methanol  industry.    By-product
carbon dioxide sales for enhanced  oil recovery could reduce the required plant-gate
methanol price in some areas near oil  fields amenable to  carbon dioxide  injection
techniques.
                                     IV

-------
                           TABLE OF CONTENTS
                                                                       Page
FOREWORD	   iii
ABSTRACT	   iv
LIST OF ILLUSTRATIONS	   vi
LIST OF TABLES 	  vii
I.    SUMMARY	    1
II.   INTRODUCTION	    4
III.   PROCESS DESCRIPTION 	    7
     Gasification	    7
     Gas Preparation 	   10
     Methanol Synthesis	   11
     Coal Properties and Material Balances	   12
IV.   PLANT-GATE COSTS 	   21
     Capital Expenditures	   21
     Operating Costs 	   29
     Credit for  By-Products	   36
     Economic Assumptions	   38
     Siting Limitations	   42
     Eastern Low-Sulfur  Coal	   45
     Methanol Cost  Distribution	   46
V.   TRANSPORTATION COSTS AND DELIVERED PRICES	   49
     Existing Product Pipelines	   49
     Water and  Rail Transportation	   50
     New Pipeline Construction	   51
     Delivered Prices	   53
     Future Prices	   59
VI.   CONCLUSIONS	   61
REFERENCES      	   63
APPENDICES
     A.   Program  for Calculating Sales Price and Return on Investment
     B.   Example  Computer Output for one Complete Price Calculation
     C.   Telephone Quotes for Costs of Water and Rail Transportation
     D.   Report on Pipeline Economic Factors
                                    v

-------
                             LIST OF FIGURES

                                                                         Page

1.   Flow Chart of Coal-to-Methanol Process Scheme	   8

2.   Coal-to-Methanol Plant Organization Chart  	   34

3.   Cost Distribution for Methanol Production in the Midwestern
    High-Sulfur Region	   47

4.   Cost Distribution for Methanol Production in the Western Subbituminous
    Coal Region	   48

5.   Cost Distribution for Methanol Production in the Western Subbituminous
    Coal Region, Assuming No Credit for Carbon Dioxide Sales	   48

6.   Map Showing Projected Methanol Producing Regions and
    Representative Consuming Locations With Their Associated Areas	   54
                                     VI

-------
                               LIST OF TABLES
Table
 1.  Characteristics of Some Commercial and Near Commercial
     Coal Gasifiers	    9
 2.  Characteristics of Some Methanol Synthesis Processes	   13
 3.  Properties of Coals	   14
 4.  Material Balances for Gasifier	   15
 5.  Material Balances for Shift Reactor and COS Hydrolyzer,
     Feed Streams	   16
 6.  Material Balances for Shift Reactor and COS Hydrolyzer,
     Product Streams	   17
 7.  Material Balances for Acid Gas Removal and Guard Bed Gas
     Conditioning Processes, Feed Streams  	   18
 8.  Material Balances for Acid Gas Removal and Guard Bed Gas
      Conditioning Processes, Product Streams	   19
 9.  Material Balances for Methanol Synthesis Reactor, All Coals	   20
10.  Factors in Cost Estimation Relationship	   22
11.  Capital Expenditures for Major Process Modules	• • •   23
12.  Capital Expenditures for Offsites 	   25
13.  Initial Catalyst and Chemical Inventory Cost  	   26
14.  Capital Expenditures for Royalties	   27
15.  Factors for Estimating Effects of State Use Tax  	   27
16.  Capital Cost Summaries 	   28
17.  Coal Cost Forecasts	   30
18.  Total Coal Consumption 	   31
19.  Water Costs	   31
20.  Water Consumption 	   32
21.  Annual Catalyst and Chemical Costs	   32
22.  Estimated Labor Rates 	   33
23.  Annual Operating Labor Costs	   35
24.  Annual Maintenance Costs 	   35
25.  Annual Insurance and Local Tax  Costs  	   36
26.  Estimated Prices for Crude Bright Sulfur	• • • •   36
27.  Total Carbon Dioxide Demand	   37
28.  Carbon Dioxide Prices and Expected Sales	   38
29.  Plant-Gate Methanol Prices	   41
                                     vii

-------
                            LIST OF TABLES (Cont'd)

Table                                                                       Page

30.  Effect of Variables on Price of Methanol in the Western
     Subbituminous Region  ...............................................  44

31.  Effect of Carbon Dioxide Sales Credits on the Methanol Price
     in the Southern Lignite Region ........................................  44

32.  Estimated Costs of Methanol Transportation Using Readily Available Means •  50

33.  Estimated Costs of Methanol Transportation in Newly Constructed
     Pipelines, Dollars per Thousand Barrel Miles .............................  52

34.  Estimated Costs of Methanol Transportation in Newly Constructed
     Pipelines [[[  52

35.  Delivered Methanol Prices Using Readily Available Means of
     Transportation [[[  55

36.  Delivered Methanol Prices Using Newly Constructed Pipeline
     Transportation [[[  56

37.  Delivered Methanol Prices Using Newly Constructed Pipeline Transportation
     Western Development Restricted by Water Availability ..................  57

38.  Delivered Methanol Prices Using Best Estimate of Water Availability
     Readily Available Transportation, and No CO2 Sales Credit,
          $/Gallon [[[  58
39.  Delivered Methanol Prices Using Best Estimate of Water Availability,
     Newly Constructed Pipeline Transportation, and No CO2 Sales Credit

-------
                                 I.  SUMMARY

     Methanol has received considerable attention as a possible future transportation
fuel because it can be used in properly designed vehicles, and large amounts could be
produced from domestic coal reserves.  Coal is mined in many different locations, and
the properties of the coal differ from place to place. Mining costs, water availability,
climate, and taxes also vary, and as a result, the cost of producing methanol from coal
should  differ significantly from place to place.  In addition, the availability and cost
of transportation could make  a significant impact on delivered methanol prices.  The
objective of this study was  to use uniform methods to estimate the cost of producing
methanol at different coal fields  so the estimated sales prices could be compared  for
market analysis.   A rapidly growing market for methanol as a transportation fuel was
assumed.

     The   production  of  methanol  fronn  coal  requires three  major  steps: coal
gasification, gas conditioning, and methanol synthesis.   Several individual processes
are involved in each step and an overall processing scheme was developed for this
study by putting together individual processes.  Process selections included the Texaco
gasification process, the selective SELEXOL® process for acid-gas removal, and  the
Imperial  Chemical Industries (ICI)  process for methanol synthesis.   The following
criteria were used for process selection.

     o    Commercially available or very close
     o    Usable on a wide variety of feedstocks
     o    Economic
     o    Environmentally sound
     o    Reliable, low anticipated down time

     Methanol  prices were estimated  for production based on five types of coal,
representing five different coal-producing  regions.   They were  eastern  high-sulfur
bituminous,  midwestern  high-sulfur  bituminous,  western  subbituminous,  southern
lignite, and northern lignite coals.   Material balances were  developed for  the major
processes based on each coal's characteristics and the  process requirements.   Then
groups of processing equipment,  termed 'process modules', were sized based on their
throughput. Capital and operating costs were estimated for mine-mouth plants in each
of the  five producing regions,  and credits were taken  for by-products where  feasible.

-------
Required  plant-gate  selling prices were calculated for each plant assuming  four
different discounted-cash-flow rates of return on investment ranging from  10 to 25%.

     The lowest plant-gate methanol  prices were for production based in  the western
subbituminous region and in the southern lignite region.   In those regions, the price
was about $0.52 to $0.58 per  gallon, depending on coal prices, for 15% rate of return
on investment.  Prices in the northern  lignite region were about $0.69 to $0.73 per
gallon.  Prices for the plants using the high-sulfur coal in the eastern and midwestern
regions were $0.79 and $0.86 per gallon,  respectively.  By-product credits for sales of
carbon dioxide for use in enhanced oil  recovery were found to have a significant effect
on the methanol price.   For example,  without by-product sales the methanol price for
production based in  the southern lignite region would be $0.71 per gallon, rather than
$0.55 per gallon with by-product sales credits.  Both prices were calculated assuming
a 15% rate of return on investment.  The prices are based on 1984 dollars.  Prices
based on 1990  dollars can be obtained by using a 1.328  multiplier on the 1984 dollar
prices.

      Transportation  costs were  estimated  for   moving  the methanol  from  the
producing regions to major market areas.  Chicago, New York City, and Atlanta  were
studied as typical market locations.  Transportation  costs were estimated using two
different assumptions:    transportation  by the least-cost method or combination of
methods available  in 1984,  and  transportation  by hypothetical,  newly-constructed
pipelines.     The  right  of eminent domain  was assumed  for  the  new pipeline
construction.    Transportation  costs  were  estimated  for the  presently available
methods based on  telephone  quotes, and  were  calculated  for  newly  constructed
pipelines  using capital and operating  cost figures  supplied by a pipeline engineering
company.

      Plant-gate  prices  and transportation  costs  were used  to determine delivered
prices.  With presently available transportation, the lowest delivered prices were for
production based in  the southern lignite  region.  With newly constructed pipelines, the
lowest delivered prices were for production based in the western subbituminous  region.
Three locations would  gain a major  benefit from  newly constructed pipelines:  the
western  subbituminous and northern lignite producing regions, and  the Atlanta market
area.

-------
     Water availability could be a major restriction on industrial development in arid
western regions.  An analysis of water  costs and availability in this study indicated
that with adequate  planning and careful site selection, water availability would not
prevent the development of  a coal-to-methanol industry in  the western subbituminous
region.  Also, a large increase in water  cost would  make  only  a slight difference in
methanol  price.     Neither water  availability  nor  other  siting  limitations were
significant problems in any of the other producing regions.

     Some  of the issues which  would  affect the  delivered methanol prices merit
further study.  These  include the effects of water  availability and credits for CO2
sales which are  presented as case studies toward the end of the report. These issues
are very site and time-specific.  For a particular plant location, a thorough analysis of
water availability will be required, particularly in the west,  as part of the construction
planning and permitting procedures.  This will involve the acquistion of additional data
and  extensive review of  federal, state, and local planning  activities.  Similarly, prior
to construction of a plant,  a thorough market analysis for CO2 sales including CO2
transportation,  and technical and economic analyses for its use in  individual  oil fields
should be made. These issues were studied in this report from a general viewpoint and
the sensitivity factors are indicative of potential rather than specific results.

-------
                              II.  INTRODUCTION

     Methanol may become a major transportation fuel.  It can be made from any of
several concentrated sources of carbon including conventional hydrocarbon fuels, coal,
peat and biomass.  The technical problems associated with  the use of rnethanol as a
transportation fuel are being widely investigated and it may become  a practical fuel
for properly designed vehicles.  The problems do not appear to be insoluble; no major
breakthroughs are required.    Because rnethanol can be made  from coal,  it  could
become an attractive domestic alternative to petroleum-derived  vehicle fuels.   The
energy content  of our  domestic coal reserve  is about 100  times as great as our
petroleum reserves.   The use of our  coal reserves to provide methanol vehicle fuel
could significantly increase our energy security.

     The huge deposits of coal in this country contain several  different types of coal.
A  number of factors which affect methanol production costs are known to vary widely
among these coal deposits. These  include  compositional  factors  such  as sulfur,
moisture, and ash contents, and geological factors relating to ease and costs of mining.
The availability of water for  industrial use is a major issue in  arid regions, and markets
for by-products differ  from place to place.    Less important variables include the
effects of climate on building costs and differences in state and local taxes.

     The delivered costs of  methanol  are further affected by transportation variables.
Some areas with  factors favoring low production costs, such  as the western low-sulfur
coal fields, have  no access to inexpensive water  transportation and only a very limited
local market because of  the  low  population density.   Other  areas are served by
extensive networks of  existing product pipelines, but they  may  not be  available for
methanol shipment because of high demand for shipping other  products, and questions
of materials compatability.    Newly constructed pipelines built specifically  to  allow
methanol shipments  need to  be considered  for the  development of a large-scale
methanol fuel industry.

     A number of previous  studies have been  made to determine coal-to-methanol
production costs.  These have generally been made for specific sites using particular
processes and financial assumptions.   Each study has had a somewhat different  basis,
thus it has been difficult to  compare the effects on delivered  price that would  result
from locating plants in different parts of the country  utilizing  locally obtained coal in

-------
each plant.  The objective of this study is to use uniform methods to estimate the cost
of producing methanol at different coal fields.  Making estimates on the  same basis
provides sales prices which can be compared among the different regions  for market
analysis.

     Factored estimate  methods based  on publicly  available studies were used  to
obtain capital and operating costs.  Particular  attention was paid  to items which were
variable by  region.   The capital and operating costs  were used to calculate required
selling price for several  rates of return on investment.    Resources did not  allow
detailed engineering design and optimization, or construction specifications. However,
the methods employed do allow reasonable estimates for delivered methanol costs, and
the variations can be assigned to differences among producing regions. Transportation
costs were estimated and the delivered prices  were  used to project development  of
the coal-to-methanol industry in various coal producing regions, assuming the industry
would grow  rapidly.

     Five types of coal were considered in  this study.  These were eastern high-sulfur
bituminous,  midwestern  high-sulfur  bituminous,  western low-sulfur subbituminous,
northern lignite  and southern lignite.    A  composition was  chosen  for  each coal
generally representative of actual coal samples of the  type and locality.   The eastern
and  midwestern coal compositions were  intended to represent high-sulfur resources
with little chance for utilization  in direct combustion, due to increasingly stringent
controls on sulfur emissions.

     The coal compositions were used  to develop material balances for major process
modules which were then sized  by throughput.    Cost estimates were made  using
literature values for similar process modules, adjusted for inflation and throughput.
Off sites, which include land, utilities, administrative buildings, piping, roads, and other
improvements which are  not a direct part  of the production process,  were estimated
based on process requirements and projected plant employment.   Building costs were
estimated on a  square  foot basis  utilizing  the experience of  Southwest Research
Institute architects.    Operating costs were based on literature  values, publicly
available statistics, and raw material price forecasts made by SwRI.

     Costs  of  product  transportation  were  estimated  using  similar  procedures.
Transportation costs for existing transportation methods were derived from  quotes
obtained by telephone from several carriers.   Costs  for  newly constructed pipelines

-------
were calculated from capital and operating cost estimates for several rates of return
on investment.  Raw data were supplied by a major pipeline engineering  firm which
provided consultant services  for  this  part  of  the project.    Both  the plant-gate
methanol prices and the new pipeline transportation costs were calculated to obtain
the required rates of return using the discounted cash flow method.

     Siting limitations  and by-product  sales credits  were  studied  from a  general
viewpoint.  Water availability  in the western  subbituminous region was the only major
siting limitation found.  Credits for  CO2 sales for use in enhanced oil recovery were
found to have a major effect on the required  methanol sales price.  Both factors were
very site and time-specific and would merit much further study for an individual plant.
In addition, the technology  for using CC>2 in enhanced oil recovery was developing
rapidly  and some changes  in  the  potential  market were expected.   The potential
effects  that  water availability and CC>2 credits could  have on the required methanol
sales price were presented as case studies.

     Plant locations were projected based on lowest  delivered cost.   Three cities,
New York City, Chicago, and Atlanta, representing three major regions of the country,
were used  for delivery locations.  It was assumed that production would rise rapidly to
100 x 10^ gal/day and that this total would be apportioned among the three regions in
the same ratio as recent gasoline sales.

-------
                          III.  PROCESS DESCRIPTION

     The overall processing scheme is shown in Figure 1.   The main unit operations,
and flow directions for the principal materials and utilities are included.    Several
criteria were used to select the individual processes:
     o     Commercially available or very close
     o     Usable on a wide variety of feed  stocks
     o     Economic
     o     Environmentally sound
     o     Reliable, low anticipated down time
Gasification
     Table  1  lists characteristics of  six gasifiers which  appear to be applicable to
methanol  production  and  which  meet  the requirements of  this  study.   All are
commercial now or could become  commercial  within  five years.   The Lurgi and
BGC/Lurgi products are high in  methane and  are  advantageous where  methane is a
desired  product.   The Shell and Texaco processes are more attractive because of their
product distributions and high energy efficiencies.

     There are some possible  disadvantages of the Texaco process.  In the reactor,
molten  slag contacts the  refractory  which could lead to early  refractory failure.
However,  this problem  was apparently solved  during process development.   Another
possible problem concerns  preparation of the lignite feedstocks.   The  high  moisture
content of lignites makes  grinding difficult and the slurry feed to the  gasifier could
have too  much water.    The alternative  would  be to  dry  the  lignite, but most
competing  processes  require drying anyway so this is not a  big disadvantage  to the
Texaco  process.    Overall,  lignite  feeding seems  to  require special engineering and
design   work,   but problems that might occur were  judged  to be  solvable.    The
successful  start-up of  the Texaco  gasifiers in  the  Cool Water Plant has  provided
additional confidence in this selection.

     The  Texaco entrained  flow  process was  selected for the coal gasification.   It
includes the gasification,  cooling,  ash  dewatering, and  slag  dewatering blocks  in
Figure  1.   Advantages over competing processes include the following:
     o     Drying is not required for bituminous or subbituminous coals
     o     The high pressure reactor reduces downstream compression costs
     o     Steam feed is not required

-------
H,S
                                                                                     MAIN PROCESS
                                                                            	BOILER FEEDWATER
                                                                            	 STEAMSYSTEM
                                                                                     OTHER PROCESS AND UTILITY
                                                                                           FIGURE  1
                                                                                FLOW  CHART  OF COAL TO METHANOL
                                                                                        PROCESS SCHEME

-------
                                                                         TABLE 1.
                     CHARACTERISTICS OF SOME COMMERCIAL AND NEAR COMMERCIAL COAL GASIFIERS (1-7)*
vo
                                                Lurgi

                                             Commercial

                                              Fixed Bed

                                                 Dry
                                                2 x K
                                                   fines)
                                               Top Lock
                                               Hoppers
    Casifier

Commercial Status

Type of Contact

Coal Preparation



Coal Feed Method


Solid Recycle                    No

Temperature, °F              1000-2000

Pressure, psig                  350-450

Relative, O2 feed                n/a

Relative steam feed              high

Slag/refractory contact         No slag
                 Energy Efficiency
                   Cold gas only                   80
                   Cold gas + hydrocarbons          89
                   Including steam                 89

                 Product Composition, Volume, %
                   Hydrogen                      39     45
                   Carbon monoxide                17     16
                   Carbon dioxide                       31
                   Methane                        9     8.5
                 Other Hydrocarbons,
                   Ib per Ib of CO2 free gas               3.9

                 Information Source, Reference No.    7      5
BGC Lurgi
ear Commerical

Fixed Bed
Dry
2 x (4
(- 35% fines)
Top Lock
Hoppers
Optional
1300-3300
350-450
low
low
Flux
(lowers M.P.)

88
90
90
29
59
3.3
8.7
1.7
5
Koppers-Totzek
Commercial

Entrained Flow
Dry - 2% H2O
70%- 200 M

Screw
Conveyors
No
2700
0
high
n/a
L.P. steam
outside
refractory
67
67
85
36
52

0
0
7
Shell
Late 1980's

Entrained Flow
Dry < 5% H2O
Grind

Pressurized
Pneumatic
Yes
2500
392
high
None
H.P. steam
in wall

80
80
94
30
60
2
0
0
3
Texaco
Cool Water
Mid 1984
Entrained Flow
No Drying
Grind
H2O slurry
Slurry
Pump
No
2300
690
high
None
Slag contacts
the
refractory
77
77
95
39 35
38 48
17
0.5 0.5
0 0
7 5
Westinghousi
Keystone in
SFC Negotiatii
Fluidized Be
Dry
X xO

Pneumatic

Yes
1900
230
low
n/a
No Slag


81
81
90
n/a
n/a
n/a
n/a
n/a
6
                 *    lumbers in parentheses designate references at the end of this report.
                 n/a   Not available

-------
     o     Energy efficiency and product gas composition compare favorably
     o     There are no size requirements for the coal particles
     o     It accepts both caking and non-caking coals

Gas Preparation
     Before  the  synthesis  gas  can be  used in a methanol reactor two major changes
must be made in its composition.    These  are adjustment of the hydrogen to carbon
monoxide  ratio, and the removal of sulfur  compounds.  The ratio is adjusted through
use of the water gas shift reaction:
                           CO +  H2O J5r=fe H2 + CO2

Most methanol synthesis reactors require a  small amount of CC>2 in the feed, but when
coal is used as the feedstock, a large  amount of excess CC>2 is produced in the shift
reactor and it must be removed to  obtain the required synthesis gas composition.   Two
types of catalysts are available for the water-gas shift reaction; one requires some
sulfur in the  feed, the other requires a sulfur-free feed.   The sulfur-tolerant process
was selected because it appears to have less stringent operating requirements.  This
selection  requires  placement  of   the  shift reactor  ahead of  the  sulfur  removal
processes.

     While most of the sulfur  from the gasifier is  in the form of hydrogen sulfide
(H2$), which can be readily removed from the gas stream, some  is present as carbonyl
sulfide (COS) which is difficult to  remove.   In the shift reactor COS reacts with water
to form hydrogen sulfide:
                           COS + H2O =£5= H2$ + CO2
However, the final hydrogen to carbon monoxide ratio is controlled by by-passing part
of the gas stream  around the shift reactor.   To remove COS from the by-pass stream,
a reactor is used which contains a catalyst selective to the COS-water reaction and
does not promote  the water gas shift reaction.  With this arrangement, nearly all the
sulfur in the feed to the acid-gas removal section is in the form of
      There are two types of acid-gas removal processes:  selective and non-selective.
In non-selective processes, several acid gases, in this case H2$ and CO2, are removed
in a mixture, but in selective processes, relatively concentrated streams of each acid
gas are produced.   A high H^S concentration in the stream from the acid gas removal
                                       10

-------
section is  advantageous for  the  later production of elemental  sulfur.    Also, the
growing importance of carbon dioxide in enhanced oil recovery processes makes it a
valuable  by-product in some areas.  The selective SELEXOL  process was chosen for
this step.

     Elemental sulfur is the desired final form of the sulfur impurities because it  is
easily  handled  and is a valuable  by-product.    Of  the available  sulfur production
processes, the Claus process was selected because of reliability.  In the Glaus process,
part of the H2S stream is oxidized  to form sulfur dioxide (SO2).    The two sulfur
compounds react first in a thermal reactor, then in a series of catalytic reactors to
form elemental sulfur:
                           2H2S  + SO2—*• 35 + 2H20

The Claus reaction does not proceed to completion; there are still some sulfur gases
left over in the  tail-gas.  The SCOT process, which uses hydrogen to convert the left-
over SO2 back to H2S, was selected to treat the tail-gas.  The H2S is then separated
from the rest of the tail-gas and sent back to the Claus feed.

     The available acid gas removal processes do not get the H2S concentration low
enough to prevent damage  to the methanol synthesis catalyst. A zinc-oxide absorption
bed, or guard-bed, is used to remove  the last traces of sulfur before the synthesis gas
enters the methanol reactor.

Methanol Synthesis
     Several very competitive  processes are available  for methanol  synthesis. The
reaction  is favored by high pressure;  the higher the temperature, the more pressure  is
required.  At  low temperatures the  reaction rates are too slow.   Historically, more
active catalysts have been sought to provide  an acceptable reaction rate  at lower
temperatures than used in  the previous generation of  reactors.   This  allowed the use
of lower pressures with savings in  reactor capital cost and in  compression energy
requirements.  For this reason, high pressure processes such as Vulcan  Cincinnati were
not considered.    The Wentworth process  is a recent variation of  the high  pressure
processes and several advantages are claimed, but whether these advantages offset the
higher compression  cost  was  difficult  to  determine  without  using  proprietary,
commercial scale data and experience. (8-9)  Chem System's new liquid phase process
                                       11

-------
was not close enough to commercial demonstration for these purposes.  Mitsubishi Gas
Chemicals' process is similar to the Imperial Chemical Industries' (ICI) process, but the
catalyst may have a  shorter lifetime.

     Other major process licensors include Lurgi and Haldor Topsoe.   Brief process
summaries for their  methanol processes were  recently published based on information
provided by the licensors. (10)    Table 2  is a comparison based on these summaries.
Both Fluor and  Synthetic Fuels  Associates (SFA) have compared the ICI and Lurgi
process.   Fluor(ll)  found  their costs  comparable when considering  both capital and
operating costs.  Catalyst life is  3-5 years for each.  SFA  (12) points out that there
are differences  in the kinds of  utilities  required and that they favor ICI's process
where  utilities are based on coal or gas  combustion, but they favor Lurgi's process
where  utilities are  based  on steam generation from waste heat boilers.  The large
number of operating ICI  plants,  utilities based on coal, and  the fact  that costs are
believed to be comparable were  the bases for choosing the ICI process for methanol
synthesis.

     The ICI process  is  based on a quench  type, catalytic  reactor.   The  reaction
between hydrogen and carbon monoxide  to  produce methanol  is highly  exothermic
causing the temperature  to rise out of limits before  a very high conversion of the
feedstock has been achieved.  In ICI's reactor, the feed contacts a series of catalyst
beds, and between the beds additional cooled feed is mixed in to bring the temperature
back into the proper  range.  The catalyst is based on copper  oxide, but the exact
composition and  methods of formulation are  proprietary.   It may contain zinc oxide
and alumina or chromia, which are  believed to prevent copper oxide crystal growth,
because crystal growth reduces the catalyst's useful lifetime.   Other  processes use
different catalysts and have different methods of controlling the temperature.

Coal Properties and  Material Balances
     Coal properties  selected for this study are given in  Table 3.   The references
contain descriptions  of coal with  similar properties.   Calculated material balances for
the gasifier and other major process modules are shown in Tables * through 9.
                                       12

-------
     TABLE 2. CHARACTERISTICS OF SOME METHANOL SYNTHESIS
                          PROCESSES
Haldor Topsoe
Reactor Type Fixed bed
Radial flow
ICI
Fixed bed
down flow
Heat Removal Heat exchange cold feed
between stages gas, between
cat. beds
Pressure, psig 700-1000
Temperature, °F
No. Plants Operating
Plants in Des. or Const.
Size of Plants, Bbl^/d
Feed and Fuel, 10* Btu(2)/Bbl(D
Natural Gas Feed 29.0
Heavy Oil Feed
Coal Feed
Electric Power, kWh/Bbl*1)
Natural Gas Feed 1.9
Heavy Oil Feed
Coal Feed
Cooling Water Requirements, 103 Gal/BblO)
Natural Gas Feed 4.32
Heavy Oil Feed
Water Consumption, Gal/Bbl^)
Natural Gas Feed 26.3
Heavy Oil Feed
Coal Feed
Catalysts <3c Chemicals, $/BblO)
Natural Gas Feed
Heavy Oil Feed
Coal Feed
750-1500
400-570
28
12
400-20,000
29.0
31.0
4.4
11.0
2.32
2.93
38.2
24.9
0.188
0.226
Lurgi
Tubular
water jacket
for steam
1000-1500
460-520
14
7
1200-20,000
28.2
36.3
38.7
-
-
103
83
126
0.126
0.063
0.075
 -    Not available
(1)   Bbl = barrel or 42 gallons of methanol product
(2)   Based on higher heating value
                              13

-------
                     TABLE 3.  PROPERTIES OF COALS
Coal Type Eastern
High-Sulfur
Bituminous
Coal Moisture
Content, % 2.1
Proximate Analysis (dry basis)
Vol. matter, % 42.3
Fixed carbon, % 49.0
Ash, % 8.6
Ultimate Analysis, (MAP)
Carbon, % 79.3
Hydrogen, % 5.7
Sulfur, % 4.0
Nitrogen, % 1.2
Oxygen, % 9.8
Higher Heating Value,
BTU/lb (AF) 14,170
Ash Fusibility (Reducing)
Initial
Deformation,°F
Softening
Temp., °F 2,080
Fluid Temp., °F
Midwestern
High-Sulfur
Bituminous

12.4

39.5
46.2
14.2

79.03
5.61
5.49
1.32
8.54
12,757

1,975
2,140
Western
Sub-
bituminous

6.39

46.48
46.48
7.04

72.95
5.35
0.65
0.86
20.19
11,558

2,230
2,250
                                                          Southern   Northern
                                                           Lignite    Lignite
                                                           32.0
                                                           42.1
                                                           39.4
                                                           15.6
                                                           73.70
                                                            5.61
                                                            2.33
                                                            1.47
                                                           16.89
                                                          8,500
                                                          2,280
                                         36.0
                                         45.9
                                         42.3
                                         11.8
                                         70.2
                                          5.3
                                          1.3
                                          0.8
                                         22.4
                                        7,100
                                        2,185

                                        2,210
                                        2,265
Information Source,
Reference No.     13, 14
15, 16
13, 17
18,19
18, 19
   Not available
                                     14

-------
               TABLE it.  MATERIAL BALANCES FOR GASIFIER
Coal Type
  Eastern     Midwestern     Western
High-Sulfur   High-Sulfur       Sub-
Bituminous   Bituminous    bituminous
                                                          Southern
                                                           Lignite
Stream and Components, 1000 Ib mols/day except as noted:
Slurry Gasifier Feed:
  Coal, raw,
  ton/day        9097

  Coal, moisture free
  ton/day        8909
  Water         1239

Oxygen Gasifier Feed:
  O2            561.4
  N2               1.78
  Ar               9.68
                               10850
                               9551
                               1243
                                566.5
                                  1.79
                                  9.77
                           10052
                            9409
                            1225
                            498.4
                              1.58
                              8.59
                           15172
                           10314
                            1231
                            529.0
                              1.67
                              9.12
                                      Northern
                                       Lignite
                          16161
                          10340
                           1229
                           491.9
                             1.56
                             8.48
Raw Gas Product
CO
H2
CO2
H2O
H2S
COS
NH3
CH^
N2
Ar

774
561
294
1098
19.06
1.26
6.66
5.79
5.42
9.68
                                776
                                555
                                295
                               1096
                                 26.32
                                  1.740
                                  6.68

                                  5.80
                                  6.17
                                  9.77
                            766
                            570
                            291
                           1094
                              3.33
                              0.220
                              6.58

                              5.72
                              3.66
                              8.59
                            769
                            565
                            292
                           1118
                             11.87
                              0.784
                              6.62

                              5.75
                              7.50
                              9.12
                           768
                           567
                           292
                          1116
                             4.27
                             0.282
                             6.60

                             5.74
                             6.72
                             8.48
Total Raw Gas   2775
Ash, Slag
   Tons/day
 766
              2779
1356
             2749
662
             2786
                                                          1609
                                                                       2775
1220
                                     15

-------
TABLE 5.  MATERIAL BALANCES FOR SHIFT REACTOR AND
           COS HYDROLYZER, FEED STREAMS
Coal Type
Eastern
High-Sulfur
Bituminous
Stream and Components, 1000 Ib
Midwestern
High-Sulfur
Bituminous
mols/day except
Western
Sub-
bituminous
as noted:
Shift Reactor Feed
CO
H2
C02
H2O
H2S
COS
Cfy
N2
Ar
Total Shift Feed
COS Hydrolyzer
CO
H2
C02
H2O
H2S
COS
CH^
N2
Ar
Total COS
Hyd. Feed
569
412
216
982
14.01
0.927
4.26
3.99
7.12
2210
Feed
205
149
77.9
147
5.05
0.333
1.53
1.44
2.57

590
573
410
218
990
19.43
1.28
4.28
4.56
7.21
2228
203
145
77.3
154
6.89
0.455
1.52
1.62
2.56

592
558
415
212
961
2.43
0.161
4.17
2.66
6.26
2162
208
154
78.9
148
0.901
0.060
1.55
0.99
2.33

595
                                               Southern   Northern
                                                Lignite     Lignite
                                               563          562
                                               414          415
                                               214          214
                                               974          967

                                                 8.69         3.12
                                                 0.573        0.206

                                                 4.21         4.20
                                                 5.49         4.91
                                                 6.68         6.20

                                              2191         2175
                                               206          207
                                               151          152
                                                78.3         78.5
                                               156          155

                                                 3.18         1.148
                                                 0.210        0.076

                                                 1.54         1.54
                                                 2.01         1.81
                                                 2.44         2.28
                                                600          600
                           16

-------
         TABLE 6. MATERIAL BALANCES FOR SHIFT REACTOR AND
                  COS HYDROLYZER, PRODUCT STREAMS
Coal Type
Stream and
Eastern
High-Sulfur
Bituminous
Components, 1000 Ib
Midwestern
High-Sulfur
Bituminous
mols/day except
Western
Sub-
bituminous
as noted:
Shift Product
CO
H2
C02
H2O
H2S
COS
CH^
N2
Ar
Total Shift
Product
Hydrolyzer
CO
H2
C02
H2O
H2S
COS
CHif
N2
Ar
171
811
615
584
14.75
0.185
4.26
3.99
7.12

2210
Product
205
149
78.3
147
5.369
0.0125
1.53
1.44
2.57
172
811
620
588
20.46
0.257
4.28
4.56
7.21

2228
203
145
77.6
153
7.326
0.0183
1.52
1.62
2.56
167
806
603
570
2.55
0.0321
4.17
2.66
6.26

2162
208
155
79.0
148
0.958
0.0024
1.55
0.99
2.33
                                                        Southern   Northern
                                                        Lignite     Lignite
                                                        169          168
                                                        808          808
                                                        609          607
                                                        579          574

                                                          9.15         3.29
                                                          0.115        0.042

                                                          4.21         4.20
                                                          5.49         4.91
                                                          6.68         6.20
                                                       2191         2175
                                                        206          207
                                                        151          152

                                                         78.5         78.6
                                                        156          155

                                                          3.379        1.220
                                                          0.0084       0.0031

                                                          1.54         1.54
                                                          2.01         1.81
                                                          2.44         2.28

Total Hydrolyzer
  Product        590           592          595           600          600
                                     17

-------
 TABLE 7. MATERIAL BALANCES FOR ACID GAS REMOVAL AND GUARD BED
              GAS CONDITIONING PROCESSES, FEED STREAMS


Coal Type        Eastern      Midwestern    Western
              High-Sulfur    High-Sulfur      Sub-         Southern     Northern
              Bituminous    Bituminous   bituminous      Lignite       Lignite

Stream and Components, 1000 Ib mols/day except as noted:

Feed (Combined Shift and Hydrolyzer product, dry)
CO
H2
C02
H2O
H2S
COS
Inerts
Total Feed
376
959
694
1.09
20.12
0.198
20.9
2071
375
957
698
1.09
27.8
0.275
21.7
2080
375
960
682
1.07
3.51
0.035
18.0
2040
375
959
688
1.08
12.5
0.123
22.4
2058
375
960
685
1.08
4.51
0.044
20.9
2045
                                   18

-------
 TABLE 8. MATERIAL BALANCES FOR ACID GAS REMOVAL AND GUARD BED
           GAS CONDITIONING PROCESSES, PRODUCT STREAMS
Coal Type Eastern
High-Sulfur
Bituminous
Midwestern
High-Sulfur
Bituminous
Western
Sub-
bituminous
Stream and Components, 1000 Ib mols/day except as noted:
H2S Rich Product
CO 0.187 0.187 0.188
H2
CO2
H2O
H2S
COS
Inerts
Total H2S
Rich Product
CO2 Rich Product
CO
H2
C02
H2O
H2S
COS
Inerts
Total CO2
Rich Product
Methanol Synthesis
CO
H2
CO2
H20
H2S
COS
Inerts

50.30
0.011
20.12
0.148
-
70.76
0.563
0.289
573
0.011
0.050
-
574
Feed Gas
375
959
70.3
1.06
0
0
20.9

69.47
0.011
27.79
0.206
-
97.66
0.561
0.287
558
0.011
0.069
-
559
374
956
70.4
1.07
0
0
21.7

8.78
0.011
3.51
0.026
-
12.52
0.563
0.288
603
0.011
0.009
-
604
374
960
70.3
1.05
0
0
18.0
Southern
Lignite
0.187

31.3
0.010
12.53
0.092
-
44.13
0.563
0.289
586
0.011
0.031
-
587
374
959
70.3
1.05
0
0
22.4
Northern
Lignite
0.188
.
11.27
0.011
4.51
0.033
-
16.01
0.563
0.288
604
0.011
0.011
-
605
375
960
70.3
1.05
0
0
20.9
Total Methanol
  Feed         1426         1424         1424         1427        1427
                                 19

-------
    TABLE 9.  MATERIAL BALANCE FOR METHANOL SYNTHESIS REACTOR,
                              ALL COALS*
Components
  CO
  H2
  CO2
  H2O
  Methanol
  Light Ends
  Higher Alcohols
  Crty
  N2
  Ar
TOTAL                       1424     62.76      503.8
Streams, 1000 Ib
Feed
374
960
70.3
1.05
-
-
-
5.72
3.66
8.59
mols/day
Raw
Purge Gas Methanol
3.30
32.18
8.58
0.017
0.931
-
-
5.58
3.62
8.56
0.073
0.137
1.97
71.36
429.6
0.24
0.24
0.141
0.040
0.034
*  Stream compositions for the methanol synthesis reactors were the same for each
   coal type.  This material balance is for one of them.
                                   20

-------
                            IV.   PLANT-GATE COSTS

Capital Expenditures
     The sizes of the streams calculated in the material balances provide a basis for
estimating the  process module costs.     Capital expenditures  are estimated for
equipment of differing sizes by using the following  general  relationship, called the
power law (20):

     Cost = A (Capacity)17

The term F is typically 0.6 where increases in  capacity are achieved by increasing the
size of the processing units,  and between 0.9 and 1.0  where increases in capacity are
achieved  by  increasing the  number of processing units.   Values for A and F  were
obtained by a least squares regression of published costs for processing  modules.  In
some  cases only  one published cost was obtained for  a processing module adequately
representative of the module planned  in this study.  In each of these cases, the size is
in the  range where  increased  capacity is  achieved by  increasing  the size  of the
processing units and the value 0.6 was  assigned for F.   Table 10 gives the values for A
and F,  the units to be used for the capacity, and the capacity  range for which the
equation is considered valid.   The results are in 1980 dollars.  The  cost of flue gas
desulfurization units  for  the  boiler  was based on  a  model by Rubin, Bloyd,  and
Molberg (21).   The estimated  capital expenditures for  the major process units are
given  in Table 11.   Most of the raw  data used for the capital expenditure estimates
were given in 1980 dollars.  Those which were not  were adjusted  for inclusion in the
tables.  In the last part of this section, the summaries are given in 198^ dollars.
                                        21

-------
                              TABLE 10.  FACTORS IN COST ESTIMATION RELATIONSHIP
N>
   Process Module
Coal Preparation
Oxygen Plant
Gasification
Gas Conditioning

Acid Gas Removal
   H2S
   C02
Sulfur Plant
Methanol Synthesis
Methanol Distillation
Steam  and Power
                                 Capacity Units
                                    tons/day
                                 Ib mols O2/hr
                                 tons coal/day
                              Ib mols shift feed/hr
 Ib mols H2S/hr
 Ib mols CO2/hr
 Ib mols H2S/hr
Ib mols MeOH/hr
 Ib mols feed/hr
   kilowatts
Capacity Range
1,000 -
2,000 -
5,000 -
70,000 -
100 -
5,000 -
100-
10,000 -
15,000 -
40,000 -
20,000
50,000
20,000
150,000
2,000
50,000
2,000
50,000
30,000
100,000
F
0.497
0.905
0.745
0.674
0.600
0.600
0.709
0.854
0.600
0.600
A,$106 -1980
161,170
15,400
194,200
14,680
1,218,000
77,283
197,900
22,097
32,728
68,800
References
(51,58,61)
(51,52,54,55,58-60)
(51,58,61)
(51,52,54)
(54,58)
(54,58)
(51,55,58,60,61)
(51,52,54,60)
(53,59)
(51,52,54)
         Includes initial charge of methanol synthesis catalyst.

-------
    TABLE 11.  CAPITAL EXPENDITURES FOR MAJOR PROCESS MODULES
                               (1000$, 1980)


Process Module
Coal Preparation
Oxygen Plant
Gasification
Gas Conditioning
Acid Gas Removal
Sulfur Plant
Methanol Synthesis*
Methanol Distillation
Steam and Power
Flue Gas Desulfurization

Eastern
High-
Sulfur
17,114
152,385
182,275
34,948
108,510
25,211
103,600
13,665
48,850
16,340
Mid-
Western
High-
Sulfur
18,914
153,630
213,188
35,140
123,690
31,698
103,600
13,665
49,654
18,526

Western
Sub-
bituminous
17,814
136,820
199,190
34,435
61,771
7,310
103,600
13,665
49,667
0


Southern
Lignite
22,648
144,400
287,219
34,745
90,757
18,020
103,600
13,665
51,711
19,735


Northern
Lignite
23,118
135,205
303,804
34,574
66,252
8,732
103,600
13,665
52,528
17,475
TOTAL
702,898
761,705
624,272     786,500     758,953
    Includes initial charge of methanol synthesis catalyst.
                                     23

-------
     The utilities constitute a major  portion  of  the  offsite costs.    Estimates of
utilities  consumption and  production were  made  for  each  process  module in the
following categories:

     o     Electric Power
     o     Water
           -   Cooling
           -   Raw
           -   Demineralized
              Boiler feed
              Condensate
     o     Steam
           -   1500 psig
               100 psig
                50 psig
     o     Fuel Gas

The  estimates  were made  by  analogy with published  utility summaries for similar
processes.  (22,23,24,25,26).    Estimates in each category  were summarized and the
equivalent  heat requirement or credit was calculated for  the electric power, fuel gas,
boiler feed water loss, and each category of steam.   The heat requirement was used to
calculate the non-process coal requirement for  each plant.  The capital expenditures
for utilities were based on the total electric power requirement.

     Other offsite expenditures were  estimated by various  methods.   Condensate
treatment, piping, methanol storage, and sulfur handling  were estimated using the
same mathematical relationship used for estimating most of the process module costs.
The required acreage was estimated based on the total coal use, anticipated  number of
employees, the approximate sizes  of the  process units, and the size  of land parcels
available in the different coal producing regions.  Land  costs were estimated based on
phone conversations with  local taxing authorities.    Building sizes were  estimated
based on function  and anticipated  occupancy.   Building costs per  square  foot  were
based on recent contracts  and adjusted using experience  factors for rural locations in
the different  parts  of  the country  supplied by  the  Southwest Research Institute
architects. The capital expenditures for offsites are summarized in Table 12.

-------
                  TABLE 12.   CAPITAL EXPENDITURES FOR OFFSITES
                                    ($1,000 - 1980)
Function
Utilities
Condensate Treatment
Piperack and Yard piping
Methanol Storage
Sulfur Handling
Land Acquistion
Site work, roads,
  parking, & landscape
Admin. Offices
Cafeteria
Shops Building
Warehouse
Garage
Chem. Laboratory
Chem. & Mat'l. Storage
Change Room
Fire Station
Eastern
High-
Sulfur
Bituminous
54718
1427
14572
9556
15345
659
3393
322
457
934
467
208
249
415
156
75
Midwestern
High
Sulfur
Bituminous
55626
1480
14572
9556
21197
606
3393
322
457
934
467
208
249
415
156
75
Western
Sub-
bituminous
55531
1266
14010
9188
2572
242
3131
297
422
862
431
192
230
383
144
69
Southern
Lignite
57809
1379
13730
9004
8452
747
3001
285
404
826
414
184
220
367
138
66
Northern
Lignite
58658
1292
14291
9372
3308
455
3262
309
440
898
449
200
240
399
150
72
Total Offsites
102953
109713
88970
97026
93795
                                     25

-------
     People experienced in permitting  indicate that  costs do not vary significantly
from region to region.  Permitting  costs were estimated at two million dollars (1980)
in any of the coal producing locations.

     Costs of catalysts and  chemicals  were estimated based on information in the
Fluor and Oak Ridge reports (11,22,27,28), a report by Badger Plants Inc. (29), and
phone conversation with a methanol manufacturer.  The results are shown in Table 13.
      TABLE 13.  INITIAL CATALYST AND CHEMICAL INVENTORY COST,
                                 $1,000 (1980)
                          Eastern    Midwestern     Western
                        High-Sulfur   High-Sulfur      Sub-     Southern  Northern
                        Bituminous   Bituminous   bituminous  Lignite   Lignite
Gas Conditioning
   Shift reaction
   COS hydrolysis
1602
 110
 1615
  111
1567
 111
1588
 111
1577
 111
Acid Gas Removal
   Selexol for CO2
   Selexol for H2$
   ZnO guard bed
1*01
4874
145
1364
6732
144
1474
850
144
1433
3035
145
1477
1093
145
Sulfur Plant
   Claus catalyst
   SCOT hydrogenation
   SCOT solvent
105
82
54
145
113
75
18
14
9
65
51
34
24
18
12
Utilities
   Water treatment
  29
   29
  29
  29
  29
(Methanol synthesis catalysts included in process module estimates).
TOTAL
8402
10327
4216
6491     4341
                                       26

-------
     Royalty cost estimates were made with the aid of  guidelines supplied  by phone
from  the  process  licensors.    Actual  royalties  are  often  subject to  extensive
negotiation, and the licensors requested that the individual process royalties not  be
published.   A summary is given in Table 14.   All the royalties are capital charges
rather  than operating charge royalties except for those charged by Texaco, which has
both a  capital charge and a small operating royalty.  Texaco provides some  technical
services in return for the operating royalty and process data.
             TABLE 1*.  CAPITAL EXPENDITURES FOR ROYALTIES
                                  ($106, 1980)
Eastern
High-Sulfur
Bituminous
Midwestern
High-Sulfur
Bituminous
Western
Sub-
bituminous
Southern
Lignite
Northern
Lignite
Cost          6.50            6.53             6.26            6.39        6.30
     The start-up costs and working capital estimates are based on  other estimates.
The  start-up  costs  for  each plant were  estimated at  8.0% of the total process
investment which  includes the process modules,  the initial charge  of catalysts  and
chemicals, and  the  royalties.   The working  capital was taken as total operating
expenditures  for one month, plus  one extra month's coal cost, plus two extra months
labor cost, plus one year's catalyst and chemical make-up costs.

     Some adjustments  were made to the capital  costs  before they were used in
calculating the sales price.  Factors were applied to the depreciable assets to adjust
their cost to  an effective cost which included the payment of state use taxes.  Table
15 shows the  states and the use tax factors.

     TABLE  15.  FACTORS FOR ESTIMATING EFFECT OF STATE USE TAXES
                                                  State                 Factor
Eastern High-Sulfur Bituminous                Ohio                     1.000
Midwestern High-Sulfur Bituminous             Illinois                   1.009375
Western Subbituminous                        Wyoming                 1.040
Southern Lignite                              Texas                    1.040
Northern Lignite                              North Dakota            1.040
                                         27

-------
     Installed process plants cost more in cold climates than in mild climates.  Extra
insulation,  heat  tracing, and heavy duty construction add to costs in cold climates.
Engineers with experience in process plant economics estimate the cost differential to
be 15% between the Gulf Coast and the Canadian border.  The locations used  in the
studies which formed the basis for this estimate  were in the north central part  of the
country.  Two of the selected  coal producing regions were in  areas with climates
significantly  different;  these were the northern  lignite area  and  the  southern  lignite
area.  The factor 1.05 was applied to the northern lignite case and 0.95 was applied to
the southern  lignite case to account for climatic effects.
      All of the costs were adjusted for  inflation to  1984  dollars.  The Nelson Cost
Indexes for refinery construction are published periodically  in the Oil and Gas 3ournal,
and they were  used to adjust  the capital  costs to 1983 dollars.  Adjustment to 1984
dollars was  made  with a projected  10% inflation rate.   Table  16 gives the adjusted
capital costs.

                     TABLE 16.  CAPITAL COST SUMMARIES
                                  ($106 - 198*)
Process Modules
Offsites
Initial Chemicals
Royalties
Permitting
Start-up
Working Capital
TOTAL
Eastern
High-Sulfur
Bituminous
968.6
141.9
11.6
9.0
2.8
78.7
39.6
Midwestern
High-Sulfur
Bituminous
1059.5
152.6
14.4
9.0
2.8
86.6
47.2
Western
Sub-
bituminous
894.7
127.5
5.8
8.6
2.8
72.7
25.2

Southern
Lignite
1070.8
132.1
9.3
8.8
2.8
87.1
28.7

Northern
Lignite
1142.1
141.1
6.2
8.7
2.8
92.6
29.5
1252.1
1372.0
1137.3
1339.7
1422.9
                                        28

-------
Operating Costs
     Operating  cost estimates were  developed from several sources.  Coal costs are
one of the largest expenses and forecasts of coal price involve a considerable amount
of uncertainty.   Published forecasts in industry journals typically extend prices for
only one or two years  in  advance.    The Energy  Information  Agency has compiled
statistics  on steam coal  prices  since 1972, and  they project prices out to 1995,
apparently based on a constant rate of price  increase. (30)  Coal price forecasts used
in design of coal gasification systems have  typically been higher.   (31,32)  Several
coal producers  and utility coal  consumers  contacted by phone  expect coal price
increases to eventually exceed the inflation rate.

     The  published information  and  the phone  conversations generally  concerned
contract prices,  that  is,  the prices paid when demand can  be  met  from current
operations.  If production must  be  expanded,  typically  by opening new mines, the
prices paid would have to be somewhat higher.  This marginal price is  typically about
20 percent above average contract prices.

     High  sulfur  coal  costs were  expected  to  show no major  long-term change.
Although the sulfur content  of the high-sulfur  coals studied  here  is above  the high-
sulfur  coal average,  in  making  SwRI's coal price forecast,  further  downward
adjustments in price were not made because  of two conflicting pressures. The current
oil glut is expected to be temporary, and overall coal prices are expected to increase
faster than inflation because of the long term energy shortage.  However, demand for
coal with  the high sulfur content  considered here is expected to  decline relative to the
total demand  because  of controls  on  gaseous  sulfur  emissions.     With  these
considerations, high-sulfur coal prices were forecast  to  remain  steady, in constant
dollars, throughout the plant life.

     The  low-sulfur coal prices seem to be more  subject to increases because  fuel-
switching  may increase  in the future.  However, this will be  somewhat dependent on
governmental decisions and legal  interpretations which make it difficult to forecast
                                        29

-------
the extent of fuel switching.    To  see  how coal price increases  might affect the
product price, calculations were made based on  four different, twenty year, constant
dollar forecasts:
     1.     Coal cost low, remaining near 1984 levels.
     2.    Coal cost rises slowly, increasing about 45%.
     3.    Coal cost rises rapidly, increasing about 90%.
     4.    Coal cost high and constant, well above 1984 levels.
The coal cost forecasts are summarized in Table  17.

                  TABLE 17.  COAL COST FORECASTS, $/Ton
                                (Constant 198* $)
Years From 1990 Plant Startup     1-5            6-10          11-15         16-20
Eastern High-Sulfur Bituminous   31.70          31.70         31.70         31.70
Midwestern High-Sulfur
   Bituminous                   34.30          34.30         34.30         34.30
Western Subbituminous
   Coal Cost Low                11.00          11.00         11.00         11.00
   Coal Cost Rises Slowly        11.00          12.67         14.33         16.00
   Coal Cost Rises Rapidly       11.00          14.00         17.00         20.00
   Coal Cost High                15.00          15.00         15.00         15.00
Southern Lignite
   Coal Cost Low                 9.50           9.50          9.50          9.50
   Coal Cost Rises Slowly         9.50          11.00         12.50         14.00
   Coal Cost Rises Rapidly        9.50          12.50         15.50         18.50
   Coal Cost High                13.50          13.50         13.50         13.50
Northern Lignite
   Coal Cost Low                 9.50           9.50          9.50          9.50
   Coal Cost Rises Slowly         9.50          11.00         12.50         14.00
   Coal Cost Rises Rapidly        9.50          12.50         15.50         18.50
   Coal Cost High                13.50          13.50         13.50         13.50

     The  total  coal consumption is given for  each plant  in  Table  18.     Coal
consumption is the total  required for the process material balances, plus the utility
boiler requirements.
                                       30

-------
                   TABLE 18.  TOTAL COAL CONSUMPTION
          Coal Type                                 Coal, 1Q6 ton/year
          Eastern High-Sulfur Bituminous                   3.93
          Midwestern High-Sulfur Bituminous               4.81
          Western Subbituminous                          4.26
          Southern Lignite                                6.91
          Northern Lignite                                7.20

     The cost of water is a much lower fraction of the total operating costs than the
cost of coal.    Water  costs  do  not respond to  supply in the same way that other
resources do because prices are  regulated and because it  is usually  impractical to
transport it  over  long distances.  Elements of the water cost include the facilities to
acquire the water and do preliminary treatment, and the operating costs.  For surface
water, facilities costs would  include pumps  and  the construction of reservoirs  and
treatment plants to remove  both  suspended and dissolved impurities.    For deep
groundwater, facilities costs would include well drilling, pumps, and treatment plants
to remove dissolved impurities.   Pump operation for lifting water from  a deep well
requires a  large  amount  of energy and can be  quite  expensive  compared  to pump
operation for moving water on the surface.

     Reliable information on water costs in areas where surface water is plentiful was
published by Ebasco Services, (33) which was based on information supplied by the
Illinois  Water Resources  Board.   Fluor (25)  estimated water  costs in  the  northern
lignite fields and Pritchard  (34) provided information applicable to deep groundwater
in an arid, western subbituminous coal region.  Water cost forecasts are given in Table
19 and  the  water consumption for the principal in-plant uses is  given  in  Table 20.
Other utilities were produced in plant and costs were included elsewhere.

                           TABLE 19. WATER COSTS

          Coal Type                                 1984, $/1000 Gallons
          Eastern  High-Sulfur Bituminous                   0.072
          Midwestern High-Sulfur Bituminous               0.072
          Western Subbituminous                          1.155
          Southern Lignite                                0.150
          Northern Lignite                                0.115

                                      31

-------
                      TABLE 20.  WATER CONSUMPTION
                                (109 Gal/year)
Coal Type                   Process
Eastern High-Sulfur
   Bituminous                  0.98

Midwestern High-Sulfur
   Bituminous                  0.98

Western Subbituminous         0.97

Southern Lignite               0.97

Northern Lignite               0.97
Cooling
10.36
11.90
6.50
8.50
6.60
Other
3.12
3.12
3.12
3.12
3.12
Total
1M.
16.00
10.59
12.59
10.69
     The high cooling-water requirement for the plants using high-sulfur coal is due to
consumption in the large acid gas removal sections required for those plants.
     The annual costs of catalysts and chemicals were estimated based on information
in the Fluor and Oak Ridge reports (11,22,27,28), the report by Badger Plants (29) and
a phone conversation with a  methanol manufacturer.     The results are shown  in
Table  21.
           TABLE 21.  ANNUAL CATALYST AND CHEMICAL COSTS,
                                 $1,000 (1980)

Eastern
Process High-Sulfur
Module Bituminous
Gas conditioning
Shift reaction
COS hydrolysis
Acid Gas Removal
Selexol for CO2
Selexol for H2S
ZnO guard bed
Sulfur Plant
Claus catalyst
Hydrogenation
SCOT solvent
321
37

177
616
145

20
24
162
Midwestern
High-Sulfur
Bituminous
323
37

172
851
144

27
33
224
Western
Sub-
bituminous
314
37

186
107
144

3
4
28

Southern
Lignite
318
37

181
383
145

12
15
101

Northern
Lignite
315
37

187
116
145

5
5
36
Utilities
   Water
   treatment

Methanol
synthesis

TOTAL
 431


4411

6344
 431


4411

6653
 431


4411

5665
 431


4411

6034
 431


4411

5688
                                     32

-------
     Operating labor costs were estimated from the numbers of employees projected
in several labor categories.  The number of employees required for various sections of
the plant were  estimated based on  published sources (11,32) and  experience  with
similar units.  The numbers are indicated on  the organization chart shown in Figure 2.
Operating labor  rates shown in Table 22 were estimated with the aid of information
supplied by the Bureau of Labor Statistics and industry sources.

            TABLE 22.  ESTIMATED LABOR RATES, 198* Dollars/Hour

Eastern
Labor High-Sulfur
Category Bituminous
Process Engineer
Sr. Plant Operators
Plant Operators
Drivers
Chemist
Sr. Lab Technician
Lab. Technician
Purchasing
Ins. & Personnel
Acctg. & Payroll
Sales
Secretaries
Nurse
20.13
18.26
14.55
13.39
15.56
17.89
13.95
15.39
14.54
10.56
13.04
10.00
13.13
Midwestern
High-Sulfur
Bituminous
20.13
18.26
14.55
13.39
15.86
18.19
13.95
15.39
13.81
10.03
12.38
9.50
12.47
Western
Sub-
bituminous
19.23
18.08
14.29
14.37
15.16
17.48
13.80
16.85
14.53
10.41
12.85
9.86
12.95

Southern
Lignite
21.12
16.52
13.08
11.81
16.64
18.65
12.03
14.65
13.85
10.06
12.42
9.53
12.51

Northern
Lignite
19.23
17.52
13.91
13.47
15.16
17.41
13.52
16.85
13.85
10.06
12.42
9.86
12.95
     Supervision, benefits (labor burden), and overhead were estimated using the same
factors,  applied  to  the operating labor cost,  for  each  plant.    Supervision was
estimated at 20% of the operating labor, burden at  35% of the operating labor plus
supervision, and the overhead  at  35%  of  the  operating labor  plus supervision plus
burden.  The total amounts of annual labor cost are shown in Table 23.
                                       33

-------
                                   Plant Manager
  Operations
Superintendent
     7 Unit
     Supervisors
                                         I
                      Plant
                  Superintendent
Safety
Engineer
     18 Sr. Operators
     52 Operators
     2-8 Drivers
     7 Process
     Engineers
     2 Plant
     Inspectors
                         1 Chem &
                         5 Technicians
                         Feedstock
                         Department
Maintenance
Superintendent


	 8 Ma
Crew

int.
Chiefs

142 Maint.
Personnel

__ 6 Maint.
Engineers
                                                       7 Sr. Operators
                                                       34 Operators
                         Utility
                         Department
                                                      6 Sr. Operators
                                                      39 Operators
     FIGURE 2.  METHANOL-FROM-COAL PLANT ORGANIZATION CHART

-------
                TABLE 23.  ANNUAL OPERATING LABOR COST
                                  ($106, 198*)
           Coal Type                                    Cost
           Eastern High-Sulfur Bituminous                   12.55
           Midwestern High-Sulfur Bituminous               13.10
           Western Subbituminous                           12.93
           Southern Lignite                                 11.69
           Northern Lignite                                 12.2*

     Annual maintenance costs were estimated at 4.0% of the process module costs;
annual totals are shown in Table 24.  Two-thirds of the maintenance cost is estimated
for materials and one-third is estimated for maintenance labor.

                  TABLE 2*. ANNUAL MAINTENANCE COSTS
                                  ($106, 198*)
           Coal Type                                    Cost
           Eastern High-Sulfur Bituminous                   38.74
           Midwestern High-Sulfur Bituminous               42.38
           Western Subbituminous                           35.79
           Southern Lignite                                 42.83
           Northern Lignite                                 45.68

     Insurance and local tax cost estimates were made.  Annual insurance costs were
estimated at 1.0%  of the cost of the process modules, plus the off sites, plus the initial
chemical inventory.  Local taxes were estimated based on  phone information provided
by representative local taxing authorities in each region.   Local taxes generally make
only  a very small contribution to the overall product price in industries of this type,
and would  normally be  included only in much more detailed cost  studies.  However,
they do vary among different regions of the country, and they  were included  here
because in this study an evaluation of the regional differences was an  important
objective.  They were grouped with the insurance for calculation purposes. Totals are
shown in Table 25.
                                       35

-------
           TABLE 25.   ANNUAL INSURANCE AND LOCAL TAX COSTS
                                  ($106, 198*)
           Coal Type                                    Cost
           Eastern High-Sulfur Bituminous                   25.24*
           Midwestern High-Sulfur Bituminous               14.81
           Western Subbituminous                          11.02
           Southern Lignite                                 13.18
           Northern Lignite                                 12.97
*  First year only, costs decline slightly in succeeding years.

     State taxes were estimated based on  the main  provisions of the state tax laws,
utilizing credits  for local taxes where applicable.  The states used for these estimates
were the same as given in Table  15 for the  use taxes.  Federal tax was estimated at
46% of the income less state taxes and depreciation.

Credit for By-Products
     Two  by-products make  contributions  to  the  plant  economics, and both show
considerable variation by region.  These are sulfur and carbon dioxide.   Sulfur prices
were estimated from listings in recent issues of the Chemical Marketing Reporter and
are given in  Table 26.    Northern  and western prices  were lower because of their
distance  from  major  markets  in  fertilizer manufacture, and  their  proximity  to
inexpensive Canadian  supplies.  Prices in the southern  lignite region were estimated
slightly  lower because those producers would compete  with Houston area  oil refiners
who have ready access to water transportation.

          TABLE 26.  ESTIMATED PRICES  FOR CRUDE BRIGHT SULFUR
                               (1984 $/Long Ton)

           Eastern High-Sulfur Bituminous                  110
           Midwestern High-Sulfur Bituminous              110
           Western Subbituminous                          75
           Southern Lignite                                 90
           Northern Lignite                                 80
                                       36

-------
      Most studies of methanol plant economics have not taken any credit for carbon
dioxide.  However, its use in enhanced oil recovery has increased in recent years and
its potential sale has become a significant factor.  Literature pertaining to possible
markets and competing sources  was  examined for guidance in estimating CO2 sales.
Science Applications Inc. (35)  studied  demand  in  four basins  for  a 15 year CO2
injection life with results given in Table 27:

               TABLE 27. TOTAL CARBON DIOXIDE DEMAND (35)
                                                     Carbon Dioxide Demand
Oil Producing Basin
Permian Basin and Texas Gulf Coast
Williston Basin (North Dakota, Montana)
Appalachian Basin (Ohio, West Virginia)
Los Angeles Basin

*   Million standard cubic feet per day
** Tons per day
MMSCFD*
8228
194
68
309
TPD**
478,000
11,300
3,900
17,900
     Industry sources have indicated that there are major markets near the western
subbituminous and the  northern lignite  coal  regions.   Although  CO2 injection for
enhanced oil recovery has  been demonstrated in Appalachian fields (36), the oil fields
in that region are small, shallow, and the potential market is very small. (37) Also, the
procedure would be economic only if CO2 could be obtained at a low price.  The same
is true  of  the  Illinois basin  fields where  the potential market appears to be  even
lower.  (35)  No projects are underway or planned in Illinois, but CO2 use is increasing
in the other basins of interest. (38-40)

     The principal competing source of CO2 was natural deposits obtained from wells.
Some was  available  as  a by-product in natural gas, but other  wells  produced nearly
pure CO2-   Natural CO2 was available  for oil fields near the  western subbituminous
coal region, the southern lignite region, and the eastern high-sulfur region.  However,
CO2 pipelines  several  hundred miles long would be required  in  each case.    One
pipeline has recently gone into service bringing CO2 from southern  Colorado to the
Permian Basin.
                                       37

-------
         The pattern of CC>2 use in an individual project results in reduced sales over a
   period of time.  Typically, CC>2 use remains nearly constant for about 5 years until
   CC>2  content in the product oil  gets high enough  to make recovery and recycle
   profitable.  New CO2 use then declines for several years until it is used only  to
   replace losses.   To maintain constant sales, new projects would need to be found
   during the plant life.

         With this background, decisions were made about the prospects  for CO2 sales.
   They were necessarily somewhat arbitrary.    Since  the technology is relatively
   young, new developments could significantly alter the sales pattern from that given
   in Table 28.   The decisions include the percent of production expected to be sold,
   the period of sales,  the maximum number of plants expected to sell CO2, and the
   price.  The sales  patterns in  Table  28 were  used  in  calculating  the plant-gate
   annual credits for CO2 sales.
         TABLE 28.  CARBON DIOXIDE PRICES AND EXPECTED SALES
Coal Type
Eastern High-Sulfur
   Bituminous
Midwestern High-Sulfur
   Bituminous
   C02
Produced,
   TPD
  12600
  12300
Percent of
Production
   Sold
    10%
           Sales
          Period
        Plant Life
                                                                  Max.
                                                                  No.
                                                                 Plants
Price,
$/Ton
                                                                            20
Western Subbituminous
  13300
     60
          decline
                                                                            30
Southern Lignite

Northern Lignite
                             12900
                             13300
100     Plant life
                 60
             decline
                                        10
                                    25
                                35
Economic Assumptions
     Several economic  assumptions were  used  with the information given  in  the
preceding sections for calculating the plant-gate price of methanol.  Four different
discounted-cash-flow  rates  of  return  were used to show the effect  on  sales price.
Different rates of return would be expected  with  different  financing arrangements.
Plants built with  equity  financing  typically  expect  20-25%  rate of  return  on
                                       38

-------
investment, while those built with some sort of government participation are willing to
accept a lower rate of return. The  government participation could take the form of a
subsidy, a loan guarantee, or a price support. Price supports seem likely in view of the
successful negotiation of price support agreements by Union Oil Shale and Cool Water
Coal Gasification. Actual  rates  of  return differ from industry  to industry  and  vary
with market conditions, but 18% is typical for  manufacturing  industries.    Energy
companies  are very competitive and generally  receive lower rates of return, typically
about 12%, although  investment funds are not generally available for new projects
unless economic studies indicate about 20 to 25% rate of return. For a plant built with
governmental participation,  a selling  price equivalent to  about 12% rate of return
could probably be negotiated.    For a plant built with equity financing, 20% would
seem a  reasonable rate of  return if the technology and markets are  well established.
If an equity-financed  plant were seen as a pioneering venture, investors would expect a
higher  rate of return, 25%  or greater.    Other economic  assumptions used in the
calculations included the following:

     o     Project life was 20 years
     o     Construction schedule -
                           Year            Percent Spent
                            1                    12
                            2                   23
                            3                   30
                            t                   23
                            5                   12
     o     Depreciation using the accelerated cost recovery system -
                           Year            Percent Depreciated
                            1                      15
                            2                     22
                            3                     21
                            t                     21
                            5                     21
     o     A  10%  federal investment tax credit was taken, but no energy investment
           credits were taken.
                                         39

-------
     o     Income was assumed to be  continuous for determining the present worth
           factors used in the discounted-cash-flow method (41).
     o     Four discounted-cash-flow rates of return on investment were used:  10,
           15,  20,  and 25%.    The  method  of calculation  was based  on  income
           distributed evenly throughout each year.

     A   computer  program  was written which uses  an  iterative  procedure  for
calculating the required sales price.   It has provision for running a series of cases with
minor variations,  without requiring  re-input  of the  data which remain constant
between cases.  Options allowed year by year changes in any operating costs or credits
which were expected to vary  over the project life, cash outlays  and recoveries, and the
incorporation of site  specific items, such as the coal severance tax or license report
fees, not covered in the general operating cost categories.  Temporary modifications
were made on  a case-by-case basis  to accommodate unusual items such as state tax
credits for local taxes, or a state net worth tax.  The program was written to meet the
needs of this project, and  as  these needs were developed the program was expanded by
putting additional subroutines at  the end, so program elements  are not all  arranged in
the same sequence as calculations occur.  A complete listing of the program is given in
Appendix A.

     The computer program  was used to calculate plant-gate  methanol prices for all
five coal types.  The results, shown in Table  29, indicate  that coal-derived methanol
can be produced for the lowest cost in  the western subbituminous region, if sufficient
water is available.  Costs in the southern lignite region are only slightly higher.  Costs
in the northern lignite region are about  midway between the lower cost regions and the
high cost eastern and  midwestern regions using high-sulfur coal. The prices indicate
that the rate of return on investment has much more influence on the methanol price
than the coal cost in the ranges studied.  Coal cost projections  were given in Table 17.

     The computer output for each calculated price includes a year-by-year listing of
the cash outlays, sales, earnings, taxes, cash flow, and present values.   It also includes
the payout period and tables showing each operating expense, both in annual dollars
and as a percent of the total operating  expenses.  An example printout is included in
Appendix B.
                                        40

-------
        TABLE 29.  PLANT-GATE METHANOL PRICES, 198* $/GALLON
Return on Investment, %
Eastern High-Sulfur
Midwestern High-Sulfur
Western Subbituminous
   Coal Cost Low
   Coal Cost Rises Slowly
   Coal Cost Rises Rapidly
   Coal Cost High
Southern Lignite
   Coal Cost Low
   Coal Cost Rises Slowly
   Coal Cost Rises Rapidly
   Coal Cost High
Northern Lignite
   Coal Cost Low
   Coal Cost Rises Slowly
   Coal Cost Rises Rapidly
   Coal Cost High
     In 1984, by comparison, conventionally produced methanol prices were low.
Most methanol  was made from natural gas and some U.S. plants were closed or
operating below capacity.  In world markets, there was an oversupply of methanol,
yet some new plants had recently come on stream, or were nearing completion in
areas of the world with sources of inexpensive natural gas feedstocks.  No major
new market areas were expected, except the automotive fuel market just beginning
to develop.  The potential  automotive fuel market was much  larger  than  the
available,  conventional supply  both in the U.S.A.  and worldwide. (42) However,
without rapid growth of the fuel market, the low methanol prices were expected to
continue  with  little  change for several years.  Spot prices  for U.S. Gulf coast
delivery were frequently between $0.40 and $0.45  per gallon  and contract prices
for rail-car or truck shipment were generally below $0.50 per gallon.  The plant-
gate costs  for coal-derived methanol would be significantly higher except  for  the
western subbituminous and the lignite regions at 10% return on  investment.
10
0.608
0.651
0.363
0.372
0.379
0.388
0.353
0.364
0.376
0.390
0.470
0.482
0.495
0.509
15
0.790
0.862
0.520
0.527
0.533
0.546
0.544
0.553
0.563
0.582
0.688
0.699
0.709
0.729
20
1.037
1.144
0.732
0.738
0.743
0.759
0.800
0.808
0.816
0.840
0.983
0.991
0.999
1.025
25
1.345
1.496
1.000
1.004
1.008
1.027
1.121
1.127
1.133
1.162
1.356
1.362
1.368
1.399
                                    41

-------
Siting Limitations
     Despite the low price of methanol produced in the western subbituminous region,
plant siting  would  present some difficulties.    In  some  localities, the  coal  is  at
excessive depth, and there are significant hazards associated with underground mining.
Aquifer disruption and acid mine drainage can cause problems  there, just as in  other
coal fields.   However,  the western subbituminous coal deposits are very large, and
most of these problems can be avoided by careful selection of the mine location.   The
principal  constraint on  siting is  the water supply,  and it has been the  subject  of
extensive controversy, but it also seems to be a solvable problem.

     A review by  the  U.S.  Office  of Technology  Assessment (43)  discusses the
restraints on water  use  in  the western  subbituminous  mining region.  Surface water
allocations  are based on average  streamflows  rather  than on expected minimum
streamflows, the basis used in most of  the eastern U.S.   Furthermore, the western
streamflows show large  season-to-season variations and large year-to-year variations.
(43,44)   If  water allocation could be obtained,  large reservoirs would be required  to
avoid water shortages.    However, reservoir construction in  highly scenic western
areas has usually  been  controversial and  strong local opposition has  prevented,
delayed, or forced alteration of many reservoir construction plans.

     Ground water resources in the western  subbituminous  region have not  been
extensively  developed.   There  are  some shallow groundwater  aquifers, but they are
generally  believed to be insufficient for industrial needs. (43,45)    The Madison and
related formations  appear  to contain a significant groundwater resource at greater
depth.  (46)  The safe yield has been  estimated at 75,500 acre feet (24.6  x 109 gallons)
per year,  but drilling depths range from 4000 to 20,000 feet. (43)   The water will  be
expensive and the estimated safe yield would support only  a little  more than two  of
the  coal-to-methanol  plants  in  this study.    Actual  plants will  most likely use a
combination of water sources, supplementing whatever  surface  water can be obtained
with wells.

     Water conservation can  significantly reduce the  water consumption  relative  to
the normal water requirements.  Cooling consumes the  largest fraction  of water used
in a coal-to-methanol plant,  and dry cooling towers are available, but seldom used
because of  cost.   It  is  significant that  one of  the  very few dry cooling towers
constructed in  the U.S. is on a small power plant located in the  western  subbituminous
                                        42

-------
region.     Larinoff  (47)  has  written a  critical  review of  dry  cooling  tower cost
estimates, and it appears that dry cooling towers cost about 4 times as much as wet
cooling  towers to build.  They also require more electric power, which for the coal-to-
methanol plants considered here means  a larger boiler and electric  generator and
higher coal consumption.  Larinoff's data were used to estimate the cost of producing
methanol from  western subbituminous coal using both dry  cooling towers and other
water conservation measures  to reduce the total water consumption to  about 20% of
the normal requirement.

     The  Yellowstone River in  southern Montana  contains  sufficient  water for
extensive synfuels development; its' average stream flow is  about 2000 x  10^ gallons
per year, large compared to the methanol plant requirement of  11  x 10^  gallons per
year. It goes close to the northern edge of a large subbituminous coal field, but many
acceptable mine locations would be  located 40-70 miles away.  Transportation could
raise the water cost to about $4.00 per 1,000 gallons and estimates were  made based
on this figure with and without credit taken for CO2 sales.  These can be compared to
the base case which has normal water usage, water cost at $1.15 per 1000 gallons, and
allows credit for CO2 sales. For these estimates, the coal price forecast termed "price
rises slowly1 was used.

     The results,  shown  in Table  30, indicate that  a  large increase  in  water cost
causes only a slight increase  in product price. For  plants with normal water usage,
cases A and D, using high cost water  increases the product price by less than 4 cents
per gallon. For plants with low water usage, the use of high cost water increases the
product price only about  one  cent per gallon, cases C and E.  The cost attributed  to
low water  use ranges from 2 to 10 cents  per gallon of product when water costs are
normal, cases A and B.   Loss of CC>2 credits would increase costs about 9 cents per
gallon, cases B and C.

     The effect that loss of credits for  CO2 sales would have on the required selling
price was  also calculated for production in  the  pertinent  producing  areas.   The
calculations were made for 15% return on investment and for coal price  projections
termed  'coal prices  rises slowly'.   The greatest effect was in the  southern lignite
region for which some additional calculations  were  made  using the other  rates  of
return.  The  results  are shown in Table 31, and they again indicate the major effect
CO2 sales credits should have on methanol plant economics.
                                       43

-------
     TABLE 30.  EFFECT OF VARIABLES ON PRICE OF METHANOL IN THE
             WESTERN SUBBITUMINOUS REGION, 1984 $/GALLON
                                                   Return on Investment,  %
Case   	Case Description	       10         15       20      25
 A     Base case, normal water cost 2 credit

          TABLE 31. EFFECT OF CARBON DIOXIDE SALES CREDITS
           ON THE PLANT GATE METHANOL PRICE, 1984 $/GALLON
Case                                  CO2 Credits               No Co2 Credits
Eastern High Sulfur                         0.790                      0.806
Midwestern High Sulfur*                     0.862                      0.862
Western Subbituminous                      0.527                      0.615
Southern Lignite
  Return on Investment, %
     10                                   0.364                      0.518
     15                                   0.553                      0.707
     20                                   0.808                      0.961
     25                                   1.127                      1.280
Nothern Lignite                            0.699                      0.801
*  Credits for CO2 sales were not expected in the midwestern high-sulfur region, see
   Tables 27 and 28.

     Water supply is important for development in the western subbituminous region,
but it is not an impediment to development in  any of the other regions.   Reports by
the U.S.  Water Resources  Council (48) and by  Scott, Pfeiffer and Gronhovd of North
Dakota State University (45) indicate adequate surface  water  supply for  synfuel
development in  most of the northern lignite mining region.  Similarly, Smoller (49),
and Mathewson and  Cason (50) report that both surface water supplies and shallow
                                      44

-------
ground water  supplies are adequate for extensive development in Eastern Texas and
Louisiana where the largest and highest quality portion of the southern lignite resource
is concentrated.

Eastern Low-Sulfur Coal
     There are deposits of low-sulfur  coal in the eastern part of the country which
could be used for methanol production.   Many low-sulfur coal  mines in  the  central
Appalachian mining region produce low-ash, high heating-value material.  It tends to
be agglomerating in character, favorable for coke production.  These properties make
the eastern low-sulfur coal very expensive, but also favorable for methanol  production.

     For coal gasification, coke  is an undesirable  product and agglomerating coals
cannot be used in some types of coal gasifiers.  However, the entrained beds used for
the Texaco coal gasifiers can handle  agglomerating coal.    The  low sulfur content
should  allow reductions in the cost of  acid gas removal equipment and eliminate the
need for  flue-gas desulfurizers on  the boiler.    The  low ash content would allow
operation with  about 10% lower coal consumption for  process  feedstock  than the
corresponding  high-sulfur  case.   Similarly, the high heating value would allow about
25% lower  consumption  for  utilities  production, resulting in about  13% less coal
purchased than for the high-sulfur case.

     Capital  expenditures would  be  lower with low-sulfur  coal.     Based  on
approximate material balances (not shown) about 10% savings were inferred  for the
gasifier and coal preparation plant.  Savings for acid gas removal would be about 35%
and for the sulfur plant about 75%.    Flue gas desulfurization for the utility boiler
should  not be required.  There would be a very small savings, about 5%, for the oxygen
plant, but for  other process modules costs would be  about the same.   Offsite  savings
were  estimated at  10%,  mostly for   reduced  sulfur  handling facilities.     Capital
expenditures for the process modules and offsites together were estimated to cost \b%
less  than for  the eastern high-sulfur case.    Capital expenditures for royalties,
chemicals and plant startup would be slightly  less.   The  only  area requiring a higher
capital expenditure was working capital which was  higher because of the coal price.
For coal at $50 per ton, the working capital requirement was about 12% higher.

     Coal was the dominating feature of the operating costs.   Because  of its high
value for both steam and coking  purposes the price was estimated at $50 per ton.

                                         45

-------
Water consumption and the cost of maintenance were each estimated to be about 10%
lower than  for the high-sulfur case.   It seemed unlikely  that any  income could  be
obtained from carbon dioxide sales, and sulfur production was lower.

     A plant-gate price for 15% return on investment was calculated for the eastern
low-sulfur case using the estimates discussed above.   A plant  location in Virginia was
assumed for state tax  calculations.  A coal price  at $50 per ton is believed  to  be
reasonable,  but to see the effect of coal price changes, an additional calculation was
made for coal at $70 per  ton.   The required  methanol sales prices were $0.78 and
$0.87 per gallon respectively.

     The price was not significantly different  from the high  sulfur case at $0.79 per
gallon.   The high cost  of  coal tends to offset the  benefits gained elsewhere in the
plant.   If low-sulfur coal could be obtained for about $30  to $35 per ton, perhaps by a
plant-owned reserve  which was easily  mined, the  methanol price would probably  be
reduced  to  about $0.70  per gallon.   However, eastern low-sulfur coal prices in that
range for 1990 and beyond should be regarded as fortuitous.

Methanol Cost Distribution
     It  is  of interest  to  consider  the contribution which  different parts of the
methanol production  process  make  to  the  plant-gate price.   The  coal-to-methanol
process can be divided into four major cost areas:   coal  purchase, coal gasification,
gas preparation, and methanol synthesis.  The contribution to  the plant-gate cost was
estimated for each  area except for coal purchase by dividing the plant capital and
operating costs  among  the areas and  calculating a product  price  for each.    The
contribution of coal cost was  estimated from the cases where  calculations were made
for two different coal prices, with adjustments for differences in coal use  and price
where needed.

     Each  of the  plant cost areas included  several process  modules and  related
operations.  The coal gasification area included  coal preparation, gasification, cooling,
ash and  slag handling, and  the oxygen  plant.   The gas preparation area included the
shift reaction, COS  hydrolysis,  acid  gas removal,  sulfur production,  synthesis gas
purification in the  guard bed, and flue-gas  desulfurization at the boiler.   Methanol
synthesis included gas recovery, methanol distillation and storage.
                                       46

-------
     Utilities and some operating costs were assigned  in proportion to the  process
module costs.  Other operating costs which could be readily identified with plant areas
were assigned based on use as determined for the overall plant-gate price estimation.
For example, 67% of the chemical use was assigned to the methanol  synthesis area.
All by-product credits were arbitrarily assigned to the gas preparation area.

     Three cases were  examined.    The  first  case, shown in Figure  3,  was  for
midwestern high-sulfur coal feedstock.  The second and  third cases, Figures 4 and 5,
were  for  western low-sulfur  coal feedstock with and  without credit allowed  for
carbon-dioxide  sales.    In  all three cases, coal gasification was the major price
contributor, accounting for about half of the plant-gate price.  For the western low-
sulfur coal, gas preparation was  the least  contributor to the price if carbon dioxide
sales  credits  were  allowed,  otherwise  coal  purchase  was  the  least contributor.
Methanol synthesis was the least contributor in the midwestern high-sulfur coal case.
The fact that coal gasification is such a large contributor  to the price indicates that
improvements in gasification  economy would have a major effect on the plant-gate
methanol price.
           COAL PURCHASE
                                                            COAL GASIFICATION
  METHANOL  SYNTHESIS
                                     GAS PREPARATION
          FIGURE 3.  COST DISTRIBUTION FOR METHANOL PRODUCTION
                IN THE MIDWESTERN HIGH-SULFUR COAL REGION
                                        47

-------
  COAL PURCHASE
METHANOL SYNTHESIS
COAL GASIFICATION
                              GAS PREPARATION
   FIGURE 4. COST DISTRIBUTION FOR METHANOL PRODUCTION
         IN THE WESTERN SUBBITUMINOUS COAL REGION
   COAL PURCHASE
METHANOL SYNTHESIS
                                             COAL GASIFICATION
                                  GAS  PREPARATION
FIGURE 5. COST DISTRIBUTION FOR METHANOL PRODUCTION IN THE
  WESTERN SUBBITUMINOUS COAL REGION, ASSUMING NO CREDIT
                 FOR CARBON DIOXIDE SALES
                             48

-------
            V.  TRANSPORTATION COSTS AND DELIVERED PRICES

      Transportation costs for bringing coal-derived methanol from mine-mouth plants
to the  three  representative delivery  locations were estimated for readily available
means of  transportation and for newly constructed pipelines.   Three readily available
means of transportation were investigated:
      o    Existing product pipelines
      o    Barge  service operating  in  the  Great  Lakes area,  inland  rivers  and
           tributaries, and surrounding coastal waters
      o    Unit train/railroad tanker

Existing Product Pipelines
      There appears to be very little  precedence in the industry in moving methanol
via existing product pipelines.   Reasons for this condition, expressed by personnel at
the different pipeline  companies  contacted,  are the  effects  that  methanol would
produce on pipeline  seals and valves due to its corrosive nature and the presence of
water in the pipelines.  No one, however, ruled out the possibility of moving methanol
via pipeline in the future  should demand and production increase.  For the purpose of
this study, assuming that  methanol were treated as other products moved via pipeline,
the present cost would average between $0.60 and $0.80 per thousand barrel miles.

      While existing product pipelines are  inexpensive means of transportation,  they
have  limited  availability.   The only line  into  the  northern  lignite region carries
liquefied petroleum  gases, but the operating requirements for this type  of line differ
significantly from lines carrying  other  liquid products,  and  it  would be difficult to
adapt it  for  carrying  methanol.    There  are  no product  lines  in  the   western
subbituminous region, and very few between the southern lignite region  and  Chicago.
Most  products  from  gulf  coast  refineries  going  to the Chicago  area  use water
transportation.  Extensive, large product pipelines are in place from the gulf coast to
Atlanta and on to New York City, but these are very highly utilized.   Since methanol
can replace gasoline only  on about a 2 to 1 basis, pipeline transportation for only about
50%  of the  fuel  methanol could be  gained by assuming an equivalent quantity of
gasoline to be backed  out  of  the market.   With high  pipeline  utilization, questions
about methanol incompatibility, and  lack  of  service to  some of the less expensive
producing areas, the existing network of product pipelines at  the time of  this report
was assumed to be not readily  available.   The problems did not  seem insurmountable,
and pipeline transportation was expected to become available in the future.

                                        49

-------
Water and Rail Transportation
     For water transportation of methanol, points of pick-up and delivery are limited.
For this study, the gulf coast area, the Chicago area, the eastern Ohio River, and New
York City could be used.  There are no navigable water-ways near the northern lignite
or the western subbituminous regions.  The southern  lignite  region is near, but not
adjacent to water transportation and rail  transportation would be required for about
150 miles.  Only the midwestern and eastern producing  locations are adjacent to water
transportation. Telephone quotes obtained from  several marine barge companies and
several railroads are summarized in Appendix C.  The  information was used as  a basis
for estimating the transportation costs given in Table 32.

    TABLE 32. ESTIMATED COSTS OF METHANOL TRANSPORTATION USING
                 READILY AVAILABLE MEANS, 1984 $/GALLON
                                       Chicago         New York City   Atlanta
Eastern High-Sulfur Bituminous          0.113b              0.189a»b      0.142a
Midwestern High-Sulfur Bituminous      0.020b              0.085b        0.186a
Western subbituminous                  0.396a              0.452         0.431a
Southern Lignite                        0.125               0.125         0.208
Northern Lignite                        0.353a              0.423         0.421a
a -   rail transportation only
b -   water transportation only
     The routes used for making the estimates in Table 32 were those which appeared
to result in the lowest cost.  Rail transportation is very expensive for short distances,
but  the cost per mile goes down on very long routes.  For example, rail costs from the
western subbituminous or northern  lignite producing  regions to the  Mississippi  River
are  almost as high as rail costs direct to Atlanta.   Only in  the case of the southern
lignite could  savings be realized by utilizing water transportation over part of a  route
to Atlanta.    New York City would receive  all its  supply by water transportation,
except for that produced in the eastern high-sulfur bituminous region, from  where the
rail cost is  about the same  as the cost of barging it down  the  Ohio and Mississippi
Rivers and on around Florida.   Production from the western  subbituminous region
would  go by  rail to St. Louis, then utilize water  transportation.    It is possible to
transport by water from St. Louis to New York City via the Great Lakes, but the cost
is slightly more than twice the gulf coast route; however, in  an actual case it may be
                                       50

-------
the best route for  destinations between eastern Michigan and western Pennsylvania.
Production from the northern lignite area would also travel by rail to the Mississippi
River, but the  junction  would vary  with the season.    Most of  the time, water
transportation would begin  in Minneapolis, but during the winter, rail  transportation
could be required  to as  far south as St.  Louis.   Chicago could receive methanol by
water transportation from both the eastern and the  midwestern high-sulfur regions.
For methanol produced in the western and the northern lignite regions, the rail cost
differential between the  Mississippi River and Chicago is so  small  that  it would be
impractical to make the transfer.

     Transportation cost estimates show  that three areas would have critical needs
for lower cost transportation.   Costs are very high for western subbituminous and
northern lignite producing regions, and for  the Atlanta consuming region.

New Pipeline Construction
     New  means of transportation could  be  very important to the development of a
coal-derived   methanol  industry.      Newly  constructed  pipelines  could  provide
inexpensive transportation  for  regions where existing transportation  methods were
lacking, or prohibitively  expensive, and could affect the geographic distribution  of a
future coal-to-methanol industry.   To obtain  an estimate of transportation costs using
a newly constructed pipeline, consultant services were purchased from the Williams
Brothers Engineering Company.  They were asked to provide estimated capital costs,
operating and maintenance  costs,  and  other economic  data for  two  methanol-
compatible, pipeline systems.   The northern pipeline system had two origin points, one
in the northern lignite region,  and the other in the  western subbituminous region.
Lines from each origin point  met in South Dakota and continued as a single line to
terminals in Chicago and New York City.  The southern pipeline system originated in
the southern  lignite region and proceeded  to terminals in Atlanta and New York City.
The Williams Brothers report is included in Appendix D.

     The transportation costs were calculated using the computer program discussed
previously. A 20-year project lifetime was assumed, a cash outlay was taken the  first
year for filling the  line, and a cash recovery was taken the last year for recovering 90
percent of the line  fill.   Results are shown in Table 33, assuming 90% utilization,  in
terms of barrel miles shipped.
                                        51

-------
      TABLE 33.  ESTIMATED COSTS OF METHANOL TRANSPORTATION IN
         NEWLY CONSTRUCTED PIPELINES, 1984 $/1000 BARREL MILES
Return on Investment, %
N.L.* - Junction
W.S.* - Junction
Junction  -  New York City
S.L.* -  New York City
10
1.450
1.352
1.143
1.320
15
1.907
1.797
1.533
1.744
            20      25
          2.481   3.156
          2.357   3.015
          2.022   2.594
          2.278   2.905
*  Producing regions,  N.L. = northern lignite,  W.S.  =  western subbituminous, and
   S.L.  =  southern lignite

     The transportation costs calculated for 20% return on investment were used as
guidelines in estimating the transportation costs on a gallon basis given in Table 34.
They  should  be regarded  as  fairly low  estimates  because of  the assumed  90%
utilization.   While this is achieved in present products  lines, it may be optimistic to
assume such a high utilization for pipelines dependent on a future industry.  However,
even if the  costs were to be 20 or 30% higher than in the above estimates, the savings
over the presently available means would be, in most cases, quite large.
      TABLE 3*.  ESTIMATED COSTS OF METHANOL TRANSPORTATION IN
              NEWLY CONSTRUCTED PIPELINES, 198* $/GALLON
Producing Region                      Chicago
Eastern High-Sulfur Bituminous          0.020
Midwestern High-Sulfur Bituminous      0.015
Western Subbituminous                 0.045
Southern Lignite                       0.052
Northern Lignite                       0.044
New York City   Atlanta
0.022
0.048
0.081
0.082
0.079
0.031
0.023
0.080
0.040
0.075
     It should be emphasized that the estimated costs in Table 34 are based on the
assumption that the pipeline would acquire the right of eminent domain.  This allows
the pipeline owner to acquire pipeline right-of-way via condemnation proceedings if a
landowner  refuses compensation for his property.   Without  the right of eminent
domain, the transportation costs would be higher than estimated  and it is very possible
that difficulties in obtaining right-of-way could prevent pipeline construction entirely.
                                       52

-------
     Some other options are locally available which are attractive, but no attempt has
been made to estimate costs based on them.  For example, a short pipeline connecting
a methanol producer in the southern lignite  region to the nearest navigable waterway
should  facilitate transportation to  New York City at attractive rates.  Similarly, a
pipeline from  the Ohio River in western Pennsylvania may be able to follow existing
corridors to Cleveland and reduce transportation costs between the eastern high-sulfur
coal region and  consumers near the Great Lakes.  An existing crude oil pipeline was
built from  North Dakota and adjacent parts of Canada to a refinery near Duluth when
expectations  of  crude  oil  production  were greater than  later realized.   This line
probably has a low utilization, and it may become attractive to revamp it for methanol
carriage.   Short additions to the line could bring it within easy reach of the northern
lignite region and some of the western subbituminous region.

Delivered Prices
     The  plant-gate costs, the transportation  costs, the  effects  of  plant  designs
allowing reduced  water consumption in the western subbituminous  region,  and the
effects of by-product credits were used to estimate delivered prices. The geographic
distribution of plant locations was  modeled based on delivered price and an arbitrary
demand limit for each  of  the consuming locations.   The total demand limit was set at
100 x 106 gallons per day proportioned among  the three consuming locations relative
to the  regional  gasoline sales during 1982 and 1983.   Figure 6 shows the producing
locations, the representative consuming locations and the states used for each of the
regional sales compilations.  This procedure yielded the following regional demand
limits in millions of gallons per day:

                                           Demand Limit, Million Gallons Per Day
                Chicago                                    36.7
                New York City                             36.3
                Atlanta                                    27.0

     The  lowest delivered  prices provided  the basis for  plant location.   The lowest
price to any location was  found first, then the next lowest, until the demand limit had
been reached in  each region.  The plant-gate costs for 15%  return on investment and
the coal cost  forecast  labeled 'coal cost rises slowly' were used  in determining the
delivered prices.

-------
                                                                  Producing Location

                                                                  Consuming Location
                 ;        /      W  !          !
           ^'7;r—j        / Western     !          i
            , **DA    Tfi-~..j Subbituminous  KwZir	—-J
FIGURE 6.  MAP SHOWING PROJECTED METHANOL PRODUCING REGIONS AND
 REPRESENTATIVE CONSUMING LOCATIONS WITH THEIR ASSOCIATED AREAS
                                    54

-------
     The number of plants producing at the lowest price in each location was limited
by the expected  sales of carbon dioxide shown in Table  28, and  by  water supply
limitations in  siting plants in the western subbiluminous  region.   Delivered prices
differing by less than five cents per gallon were regarded as equivalent and the amount
of methanol was divided equally.

     Results for  the readily available means of transportation are shown in Table 35.
The geographic distribution of methanol plants shows production concentrated heavily
in the southern lignite region with 34 plants and 72% of the total production.  There
were no plants in the northern lignite region because the plant-gate costs were higher
than other  western production and transportation costs were too high to compete with
eastern and midwestern production.

  TABLE 35. DELIVERED METHANOL PRICES USING BEST ESTIMATE OF WATER
 AVAILABILITY,  AND READILY AVAILABLE TRANSPORTATION, 198* $/GALLON
Producing Region
Southern Lignite

Southern Lignite

Midwestern Bituminous
Southern Lignite
Eastern Bituminous
Eastern Bituminous
Western Subbituminous
No.
of
Plants
10

18

6
6
4
1
2
Plant-Gate
Cost,*
$/Gal.
0.553

0.707
0.707
0.862
0.707
0.790
0.806**
0.527
Sales,
106 Gal./
Day
10.5
10.5
25.2
12.6
12.6
12.6
8.4
2.1
4.2
Chicago
Cost
$/Gal.

0.695
—
0.849
0.882
-
-
-
_
N.Y.C.
Cost
$/Gal.
0.678
-
0.832
-
-
-
-
—
_
Atlanta
Cost
$/Gal.
-
—
-
-
0.915
0.932
0.948
0.958
*  Assumes 15% return on investment and coal costs that rise slowly.
** The higher cost on this line is due to loss of credits for CO2 sales.

      For newly-constructed pipelines, two development models  were considered  for
the  western subbituminous region  based  on water  limitations.   The  first  model
represented the best estimate  of water availability, and two plants were allowed with
normal water use,  four  plants with low water use but normal  water price, and an
                                       55

-------
unrestricted number with both low water use and high water price. The results, shown

in Table 36,  indicate production concentrated in the western subbituminous  region.
Plants are also located in the southern and northern lignite region, but their numbers

were nearly limited to the number of plants with a CO2 market.


 TABLE 36. DELIVERED METHANOL PRICES USING  BEST ESTIMATE OF WATER
   AVAILABILITY, AND NEWLY CONSTRUCTED PIPELINE TRANSPORTATION,
                               198* $/GALLON
Producing Region

Western Subbituminous



Southern Lignite



Western Subbituminous



Western Subbituminous



Western Subbituminous



Southern Lignite

Northern Lignite
 No.
  of
Plants
                                  Plant-Gate     Sales,    Chicago N.Y.C.  Atlanta
                                    Cost,*     106 Gal./    Cost   Cost    Cost
10
  23



   4

   5
$/Gal.

0.527



0.553



0.567



0.655**



0.662



0.707

0.699
                      Day
 1.4

 1.4

 7.0
 7.0
 7.0

 0.7
 0.7
 0.7

 2.1
 2.1
 2.1

21.3
 5.1
21.9

 8.4

 3.5
 3.5
 3.5
$/Gal.  $/Gal.  $/Gal.

0.572
                                0.605
                                0.612
                                0.700
                                0.707
                                       0.608
                                       0.635
                                       0.648
                                       0.736
                                       0.743
                                               0.607
                                                 0.593
                                0.743
                0.647



                0.735



                0.742


                0.747


                0.774
                                                                 0.778
*  Assumes 15% return on investment and coal costs that rise slowly.

** The higher cost on this line is due to loss of credits for CO2 sales.


     The second development model  for the western subbituminous region  assumed

more stringent restrictions on development.    No plants  were allowed with normal
water use, three plants were allowed with low water use but normal water prices, and
only seven additional plants were allowed with low water use and high water prices.
As shown in Table 37, these restrictions caused two concentrated areas of production;
besides the 10 plants in the western subbituminous region, 21  plants would be located
                                       56

-------
in the  southern lignite region.   Only eight  plants would be located in the northern

lignite  region and  four  in  the eastern bituminous  region.   With either of  the
development  models  for  the  western subbituminous  region,  the  existence  of

inexpensive  pipeline  transportation  would  prevent  midwestern  production  from

competing effectively and would severely limit eastern production.


   TABLE 37. DELIVERED METHANOL PRICES USING NEWLY CONSTRUCTED
     PIPELINE TRANSPORTATION, WESTERN DEVELOPMENT RESTRICTED
                  BY WATER AVAILABILITY, 1984 $/GALLON
Producing Region

Southern Lignite



Western Subbituminous



Western Subbituminous



Northern Lignite



Southern Lignite



Eastern Bituminous


Northern Lignite
 No.
  of
Plants

  10
                                 Plant-Gate     Sales,   Chicago N.Y.C. Atlanta
  11
Cost,
$/Gal.

0.553
0.567



0.662



0.699



0.707



0.790


0.764
106 Gal./    Cost   Cost    Cost
  Day     $/Gal.  $/Gal.  $/Gal.
   7.0
   7.0
   7.0

   2.1
   2.1
   2.1
   4.9
   4.9

   3.5
   3.5
   3.5

   9.9
   6.5
   6.5

   4.2
   4.2

   8.4
   8.4
0.593
                                 0.605
                                 0.612
                                 0.707
                                 0.743
                                 0.759
                                 0.810
                                 0.808
                                         0.635
                                         0.648
                                         0.743
                                         0.778
                                         0.789
                                         0.812
                                                                 0.843
                                                0.647
                                                0.742
                                                0.774
0.747
     Credit for CO2  sales, as shown  in Table 31,  made a  significant effect  on  the

plant-gate methanol price.  The effect was greatest in the regions where most of the

plants were located as portrayed in the above tables.  The loss of credit for CO2 sales
was  examined to see  how plant siting would be affected.   The results are shown in

Tables 38 through 40.
                                       57

-------
     There were few changes in the pattern of plant siting and delivered costs for the
case using readily available transportation.   There were  33  plants with 70% of the
total  production in  the  southern lignite  region,  and  no  plants  in the  western
subbituminous region. A comparison of Tables 38 and 35 shows that three plants lost
in those regions were gained by the eastern and midwestern bituminous regions.  The
lowest delivered prices  were higher without  the CO2 credits, but the highest prices
were about the same because of the expected market limitations for  the CO2 where
credit was taken.

  TABLE 38.  DELIVERED  METHANOL PRICES USING BEST ESTIMATE OF WATER
  AVAILABILITY, READILY AVAILABLE TRANSPORTATION, AND NO CO2 SALES
                            CREDIT, 1984 $/GALLON
Producing Region
Southern Lignite

Midwestern Bituminous
Southern Lignite
Eastern Bituminous
     For the case of newly constructed pipeline transportation and best estimate of
water availability there was a shift in plant siting from both lignite regions toward the
western  subbituminous region.   With credit for CO2 sales, Table 36, the combined
lignite regions had 19 plants and 40% of the total production. Without credit for CO2
sales, Table 39, there were only eight plants with 17% of the  total production, all
located  in the  southern  lignite region.   The  remaining  83%  was in  the western
subbituminous region.

     When western development was restricted by water availability, the plant siting
was  shifted back  toward the  southern lignite  region.  With  western development
restricted, Table 40,  the southern lignite  region had  31 plants and 65% of the total
production.  The loss of credits for CO2 sales resulted in the loss of all 13 plants shown
in the northern lignite region in Table 37.  The southern lignite region gained 10 plants
and the eastern bituminous region gained three plants.
                                      58
No.
of
Plants
26
8
7
6
Plant-Gate
Cost
$/Gal
0.707
0.862
0.707
0.806
Sales
106 Gal./
Day
36.3
18.9
16.8
14.7
12.6
Chicago N.Y.C.
Cost Cost
$/Gal $/Gal
0.832
0.832
0.882
-
— —
Atlanta
Cost
$/Gal
-
0.915
0.948

-------
 TABLE 39.  DELIVERED METHANOL PRICES USING BEST ESTIMATE OF WATER
 AVAILABILITY, NEWLY CONSTRUCTED PIPELINE TRANSPORTATION, AND NO
                    CO2 SALES CREDIT, 1984 $/GALLON
Producing Region

Western Subbituminous



Western Subbituminous



Western Subbituminous



Southern Lignite
 No.
  of
Plants
  34
Plant-Gate
   Cost
  $/Gal

  0.615
           0.655
0.662
           0.707
           Sales   Chicago N.Y.C. Atlanta
          106 Gal./    Cost   Cost   Cost
            Day      $/Gal  $/Gal   $/Gal
                        I A
                        I A
 2.8
 2.8
 2.8

32.5
22.8
16.1

16.8
                     0.660
                     0.700
                       0.707
0.696



0.736



0.743

0.789
                                   0.695
                                              0.735
                                              0.742
   TABLE *0. DELIVERED METHANOL PRICES USING NEWLY CONSTRUCTED
    PIPELINE TRANSPORTATION, WESTERN DEVELOPMENT RESTRICTED BY
      WATER AVAILABILITY, AND NO C&2 SALES CREDIT, 198* $/GALLON
Producing Region

Western Subbituminous



Western Subbituminous



Southern Lignite



Eastern Bituminous

Future Prices
     Early  in 1984 it was necessary to estimate the inflation rate between 1983 and

1984 to express plant-gate costs in 1984 dollars.  At that time the inflation rate was

expected to be about  10%.  Toward the end of the project, that figure appeared to be

high, and the real inflation rate was probably closer to 4%.  If the  4% figure is proven

correct, the correction factor 0.945 should be applied to prices reported here in 1984
dollars.
No.
of
Plants
3
7
31
7
Plant-Gate
Cost
$/Gal
0.655
0.662
0.707
0.806
Sales
106 Gal./
Day
2.1
2.1
2.1
4.9
4.9
4.9
20.0
29.7
14.6
14.7
Chicago
Cost
$/Gal
0.700
0.707
0.759
_
N.Y.C.
Cost
$/Gal
0.736
0.743
0.789
0.828
Atlanta
Cost
$/Gal
0.735
0.742
0.747
_
                                     59

-------
     Several factors,  such as  the high federal budget deficit, which were related to
high inflation  rates were still  present in 1984.   The inflation rate was expected to
increase, but because  of changes in monetary policy by the Federal Reserve  Board, it
was  not  expected to return to the high rates experienced in the late 1970's.   An
inflation rate at 5% was projected for 1985 and 6% for the years 1986-1990.

     The inflation rate was expected to be quite uniform.  No reasons were found to
expect differences in the inflation rate among the different coal producing regions. In
1984, crude oil prices appeared to be quite stable, which would imply a slightly lower
inflation rate  for transportation than for production, but not enough to alter the
conclusions reached in this study.  However, for  the past few years,  long term crude
oil  price forecasts had gone awry,  and events in the  Middle East were still seen as
capable of  causing big changes  in both  price  and supply.   Such changes would, of
course, affect the transportation costs much more than the methanol production costs.
Assuming stability in crude-oil prices, the factor  1.328 should be used to convert 1984
dollar prices as reported here to 1990 dollar prices.
                                         60

-------
                         VI.  CONCLUSIONS

1.   Based on the assumptions made in this study, methanol can be produced
     from coal in  the southern lignite and  western subbituminous  regions at
     lower cost  than in  the eastern and midwestern bituminous coal regions.
     Costs in the northern lignite region would be about midway  between the
     others.

2.   Without pipelines, the  presently available transportation to major market
     areas is more expensive for production in the western subbituminous and in
     the  northern  lignite   regions  than  for other  producing regions.   The
     presently available transportation is also more expensive for delivery in the
     Atlanta market area than for the Chicago or New York City market areas.

3.   For  the production  and transportation costs projected in this  study, and
     using presently-available, non-pipeline transportation,  the  delivered prices
     of methanol  would  favor industry  development  in  the  southern  lignite
     region.

4.   With  presently-available,  non-pipeline  transportation,  utilization  of
     methanol fuel would be favored in the New York  City and Chicago areas
     over the Atlanta area.  This  result occurs because Atlanta, unlike most
     major cities in  the other regions, is not adjacent to water transportation,
     however  several  other cities  in  the  area  such  as  Mobile, Miami, and
     Charleston  are  adjacent to water, so this result does not apply over the
     whole area.

5.   This  study indicates that new pipeline  construction, requiring the right of
     eminent domain,  could provide a  significant reduction  in the delivered
     methanol price. New  pipelines would  be particularly useful  to serve the
     western subbituminous and  northern lignite producing  regions,  and the
     Atlanta market area.  If these pipelines were constructed, delivered prices
     would favor industry development  in the western subbituminous producing
     region  and  utilization  of the  methanol fuel would not be favored in any
     market area over other areas.
                                   61

-------
6.    The analyses  of water  resources presented  here indicates  that water
      availability will not prevent development of a coal-to-methanol industry in
      the western subbituminous region, but it will make siting more  difficult. A
      detailed  water  plan  must  be  given  high  priority  in  western siting
      considerations, and  it may  still be necessary to pay high prices for water,
      or to transport it a  considerable distance.   However, if water were much
      more expensive the cost of methanol would only be slightly higher.   The
      use of dry  cooling towers and  other similar measures to  conserve water
      would also  make the methanol  slighty more expensive.  However, neither
      high-cost water nor water conservation were expected to cause a methanol
      price  high  enough  to change  the western regions'  favorable  economic
      position relative to other producing regions.

7.    No major siting limitations were found for any producing region except the
      water supply in  the western subbituminous region.

8.    Carbon dioxide  has  potential as an important by-product in areas where it
      could be used for enhanced oil recovery.  Credits for its sale could have a
      major effect on the required methanol selling price in the southern lignite,
      the western subbituminous, and  the northern lignite regions.  The loss of all
      credits for  CO2 was found to have little or no impact on plant  siting if the
      industry relies on presently  available transportation without pipelines.  If
      new pipelines were extensively available, the loss of  CO2  credits would
      result  in  delivered   methanol   prices  which should   favor  industry
      development in  the western bituminous region. If western development
      were  restricted,  the  southern lignite region  would  be  favored.    For
      individual plants, the  possibility of CC>2 sales merits serious consideration
      and careful study.
                                   62

-------
                                REFERENCES


 1.   BDM Corp.  "Coal  Gasification  Systems Engineering  and Analysis," Volume 2,
     Final Report, 1980, Report No. NASA-CR-16165*.

 2.   Simbeck, D.R.,  Dickenson, R.L.,  Oliver, E.O, (Synthetic  Fuels Associates) "Coal
     Gasification Systems:  A Guide to Status, Applications, and Economics," Electric
     Power Research Institute, Palo Alto, CA, 1983,  (Report No. AP-3109).

 3.   Hartmann,  3.3., Matchak,  T.A., Sipe,  H.E., Wu M. (Fluor Engineers Inc.) "Shell
     Based Gasification-Combined Cycle Power Plant  Evaluations," Electric Power
     Research Institute, Palo Alto, CA, 1983, (Report No. AP-3129).

 *.   BDM Corp.  "Coal Gasification Systems Engineering and Analysis.  Appendix A:
     Coal Gasification  Catalogue,"  Final Report, 1980,  Report No. NASA-CR-161655.

 5.   BDM Corp.  "Coal Gasification Systems Engineering and Analysis.  Appendix G:
     Commercial Design and Technology Evaluation," Final  Report,  1980, Report No.
     NASA-CR-161661.

 6.   Schwartz, C.W., Rath, L.K., Freier, M.D., (Westinghouse Electric  Corp.) "The
     Westinghouse Gasification Process," Chemical Engineering Progress, April  1982,
     p.55.

 7.   Sun Tech Inc.   "Assessment of Ether  and Alcohol Fuels from  Coal," Volume 2,
     1983, U.S. Department of Energy Report No. DOE/CS/54045-2.

 8.   Wentworth,  T.O.  and  Othmer, D.F., "Producing Methanol for  Fuels," Chemical
     Engineering Progress,  p 29, (August 1982).

 9.   Wham,  R.M.  and  Forrester, R.C.  Ill,  "Available  Technology  for  Indirect
     Conversion of Coal to Methanol and  Gasoline:   A Technology and Economics
     Assessment," presented  at  the  Third Miami  International  Conference  on
     Alternative Energy Sources, Dec. 15-18, 1980.

10.   "Petrochemical Handbook," Hydrocarbon Processing  62  (11), 111-113,  (Nov.
     1983).

11.   Wham, R.M. et al, "Liquefaction Technology  Assessment,  Phase  1:  Indirect
     Liquefaction of Coal to Methanol and Gasoline Using Available Technology," Oak
     Ridge National  Laboratory, Report  No. ORNL-566*, Feb. 1981, p 1*3.

12.   Simbeck, D.R.  and Dickenson, R.L.,  "Methanol from Coal:   Making the Best
     Choice," Proceedings  Fifth International Alcohol  Fuel Technology  Symposium,
     Vol. 1, Auckland, New Zealand, 1982, pp 1-261 through  1-268.

13.   Nielsen,  G.F.  (Ed.)  U.S.  Coal  Mine Production by  Seam  - 1976,   Mining
     Informational Services, Keystone Coal  Industry  Manual, McGraw-Hill, NY, 1977.

1*.   Retcofsky, H.L.  and  Hough,  M.R., "Nature  of  the  Free Radicals  in Coals,
     Pyrolyzed  Coals,  and  Liquefaction  Products,"  American  Chemical  Society,
     Division of Fuel Chemistry Preprints, 2*, (1), 83 (1979).
                                      63

-------
15.   Nielsen, G.F. (Ed.)  1981  Keystone Coal Industry Manual,  Mining Informational
     Services, Keystone Coal Industry Manual, McGraw-Hill, NY, 1982.

16.   HNG Synfuels Co. and Texaco Inc.  "Convert Synfuels Project Feasibility Study
     Coal to Methanol,"  DOE Report No. DE-FG-1-80RA-50337, 31 December  1980,
     p. 5.

17.   3ohanson,E.,  (Hydrocarbon Research Inc.) "Solvent Refining of Wyodak, Illinois
     No. 6 (Monterrey Mine) and Black Mesa Coals," Volume 2.  EPRI Report No. 389,
     Electric Power Research Institute, Palo Alto, CA, 1976, pp 12, 198.

18.   Boley,  C.C., Fegley, M.M.,  "Design and  Operation  of Two Refractory-Lined
     Internally   Heated,    Entrained-Bed  Carbonizers,"    DOE    Report   No.
     GFERC/RI77/1,   Grand  Forks Energy Research Center, Grand Forks, ND,  1977,
     p9.

19.   Bouchillon,  C.W., et	al, "Evaluation of the  Micropulverization,  Drying and
     Beneficiation  of Lignite,"  Conference  Proceedings, 6th  International  Coal
     Utilization Exhibition and Conference, Houston,  TX, Nov. 1983, Vol. VI, Lignite
     Development and Utilization, p. 295.

20.   Rudd,  D.F., and Watson, C.C., Strategy  of Process Engineering,  Wiley, New
     York, 1968, pp 115-124.

21.   Rubin,  E.S., Bloyd, C.N., and Molburg, 3.C.,  "Models of  Air Pollution Control
     Costs  for Coal-to-Electricity  Systems,"  Fifth  International  Coal  Utilization
     Exhibition and Conference, Houston, TX  7-9 Dec.,  1982, Proceedings Volume 3,
     pp 189-208.

22.   Buckingham, P.A., Cobb, D.D., Leavitt, A.A., Snyder, W.G., (Fluor Engineers and
     Constructors,  Inc.)   "Coal to Methanol, An Engineering  Evaluation of Texaco
     Gasification and ICI  Methanol-Synthesis Route," EPRI Report No.  AP-1962,
     Electric Power Research Institute, Palo Alto, CA, 1981, p 6-13 through A-15.

23.   Fluor  Engineers and  Constructors Inc.,    "Crow  Tribe  of  Indians  Synfuels
     Feasibility  Study,"   Vol. II,  Book  III,  Department  of  Energy   Report  No.
     DOE/RA/50351-1300, pp 6-910 through 6-920.

24.   New York State  Energy Research and Development Authority, "Low/Medium BTU
     Coal Gasification Assessment  Program for Specific  Sites of  Two New  York
     Utilities," Albany, 1980.  Department of Energy Report No. DOE/FE/20223-2.

25.   Fluor Engineers  and Constructors "Dunn-Nokota Methanol  Project, Dunn County,
     North Dakota, Volume II, Preliminary Plant  Design and  Cost Estimate," Irvine,
     CA, 1982, Department of Energy Report No. DOE/RA/50362-1395-Vol. 2-Pt. 2.

26.   Hyder, D.A. (Burns and ROE), Ku, W.S.,  Piascik, T.M., (Public Service Electric &
     Gas  Co),  District  Gasification  in New  3ersey,"  Fourth  International  Coal
     Utilization  Exhibition  and  Conference,  Houston,  TX,  17-19,   Nov.   1981,
     Proceedings Volume 4, 329-352.

27.   Fluor  Engineers L  Constructors  "Coal Liquefaction Technology  Assessment
     Phase 1,"  Department of Energy Report No. ORNL/SUB-80-/24707, pp 315-331.
                                        64

-------
28.   Ulrich,  W.C.,  Edwards, M.S. and Salmon, R.,  "Evaluation  of  an  In-Situ  Coal
     Gasification Facility for Producing  M-Gasoline via Methanol,"  Department of
     Energy Report No. ORNL/5439, pp 85-98.

29.   Badger  Plants Inc.,  "Conceptual  Design  of a  Coal-to-Methanol-to-Gasoline
     Commercial Plant, Volume 1, Technical,"  Second Interim Final Report, Aug. 31,
     1977 - Mar. 1, 1979. Department of Energy Report No. FE-2416-43 (Vol.  1), pp
     173-179.

30.   Energy  Information  Agency,  DOE, "1981  Annual Report  to Congress,"  EIA,
     Volume 3, May 1982, pp 27-28. See also recent issues of Monthly Energy Review,
     DOE/EIA-0035, Energy Information Agency, Washington, DC.

31.   BDM Corp., "Coal Gasification Systems Engineering and Analysis.  Appendix E:
     Cost Estimation  and Economic  Evaluation Methodology," Final Report, 1980,
     Report No. NASA-CR-161659.

32.   Burns  and Roe  Industrial  Services,  "Low/Medium  BTU Coal  Gasification  -
     Assessment Program For  Potential Users in  New  Jersey,"  Burns and  Roe,
     Parancus, N3  1981.  Department of Energy Report No. DOE/FE/20216-2.

33.   Ebasco  Services, Inc., "Feasibility  Study Gasoline From Coal  in the  State of
     Illinois, Volume  II Cost-Site-Environmental-Planning,"   Department  of Energy
     Report No.  DOE/RA/50326-1145, Vol. 2.

34.   Pritchard, Corporation, "Underground Coal Gasification (UCG) Gas to Methanol
     and MTG-Gasoline: An Economic and Sensitivity Study," Pritchard  Corporation,
     Kansas City, 1982. Department of Energy Report No. UCLR-15510.


35.   Anada, H., King,  D., Seskus, A., Fraser,  M. (Science Applications Inc.) and Sears,
     3.,  (West Virginia University), "Feasibility  and Economics of By-Product  CC>2
     Supply  for Enhanced  Oil  Recovery," Volume  1,  Technical Report,  U.S.
     Department of Energy Report No. DOE/MC/08333-3 (Vol. 1), 1982.

36.   Watts, R.3., Gehr, 3.B., Wasson, 3.A., Evans,  D.M., and  Locke, C.D.,  "A Single
     CO2 Injection Well Minitest in a  Low  Permeability  Carbonate  Reservoir,"
     3ournal of Petroleum Technology, 34(8),  1781 (Aug. 1982).

37.   Kuuskraa, V.A.,  Hammershaimb, E.G.,  Morra, F.,  and Wicks, D.  (Lewin and
     Assciates Inc.), "Technical and Economic Potential of Enhanced  Oil Recovery in
     Appalachia,"  Presented  at  the  Eastern Regional Meeting  of  the Society of
     Petroleum Engineers, 4-6 Nov.  1981, Columbus OH.    Paper No.  SPE 10373,
     Society of Petroleum Engineers of AIME, Dallas, 1981.

38.   Leonard,  3.,   "EOR  Set to Make Significant  Contribution," Oil and Gas 3ournal
     82(14), 83 (April 2, 1984).

39.   Matheny, S.L. 3r., "EOR Methods Help Ultimate Recovery,"  Oil and Gas 3ournal
     78(13), 79 (Mar. 31, 1980).

40.   McRee,  B.C., "CO2:  How It Works,  Where It Works,"  Petroleum  Engineer,
     49(11), 52 (Nov.  1977).
                                        65

-------
41.  Congelline,  R.H.,  "Correcting  Economic  Analyses," Chemical Engineering 77
     (23), 109 (Nov. 16,  1970).

42.  Anderson, E.V., "Large Volume Fuel Market Still Eludes Methane!," Chemical and
     Engineering News,  July 16, 1984, pp 9-16.

43.  U.S. Office of Technology Assessment "Increased Automobile Fuel  Efficiency
     and  Synthetic  Fuels:  Alternatives for Reducing  Oil  Imports.   Background
     Paper 5.  Water Availability  for Synthetic Fuels:   An  Assessment of Current
     Studies," NTIS No.  PB83-152645, 1981.

44.  Hickcox, D.H.  "The Impact of  Energy  Development in the Tongue River Basin,
     Southeastern Montana," Water Resources Bulletin, _18(6), 941 (Dec. 1982).

45.  Scott,  D.F. Pfeiffer, G.H., and Gronhovd, D.E.,  "Water  as  a Parameter for
     Development of Energy Resources in the Upper Great Plains - Effects on Land
     and  Water  Resources   of   Alternative  Patterns  of   Coal-Based  Energy
     Development,"  North Dakota  Agricultural Experiment Station  Research  Report
     No. 70,  North Dakota State University, Fargo, ND 1978.

46.  Ricker,   D.A.,  Ulman,   W.3.,   Hampton,  E.R.,  (Eds),  "Synthetic   Fuels
     Development -  Earth   Science   Considerations,"  U.S.   Department  of  the
     Interior/Geological Survey, Washington, D.C.,  1979.

47.  Larinoff, M.W. "Performance and  Capital Costs of Wet/Dry Cooling Towers in
     Power  Plant Service," in Waste Heat  Management and Utilization Vol. 2 Ed:
     Samuel  S. Lee and Subrata Sengupta, Hemisphere, Washington, Proc. Conf. 9-11
     May 1977, Miami Beach, FL, 1977, pp 687-714.

48.  U.S. Water  Resources  Council "Synthetic Fuel Development for the  Upper
     Missouri River  Basin, Section   13(a)  Water  Assessment  Report," U.S.  Water
     Resources Council, Washington,  1981.

49.  Smoller, R.K.,   "Gasification of Gulf Coast Lignites," Sixth International Coal
     Utilization  Exhibition  and  Conference,  Houston,  TX,  15-17  November 1983,
     Proceedings Volume 5, pp 117-124.

50.  Mathewson, C.C.,  and Cason, C.L., "Evaluation of the Impact of  Texas  Lignite
     Development on Texas Water  Resources," Technical Report   No.  108,  Texas
     Water Resources Institute, Texas A&M University, 1980.
                                        66

-------
                      APPENDIX A
Program for Calculating Sales Price and Return on Investment

-------
                                APPENDIX A
     PROGRAM FOR CALCULATING  SALES  PRICE AND RETURN ON INVESTMENT

     LANGUAGE;  BASIC/1. 00 DC
10

20
25
30
35
40
0041
0042
45
50
55
60
65
7(1
*7r-"
no
101
1.02

1.1.0
115

1.25
130
135
140
1.45
1.50
155
160
165
170
175
180
185
190
199
200
205
210
214
21.5
216
220
225
230
 DIM A*[701,Cf(60),Co<60),DfT(50),Dp<60),Ccf(60)
 DIM Ebt(60>,Ex(60),FiT<60>,Dcp<60>,DcT(2Q,100>
 DIM Pv(60), Pvf(60>, Ro.t(60),  Rrpv (60 ) , Fp ( 60 )
 DIM Sit(60),Sp(60)?Tpw(60),Ti(60),Up(60),Bpis(60),Bp2s(60)
 DIM Rcsti(60),Rcst2(AO),RcsT3(60),RMtc(60),Rn2c(60>,RM3r(60)
 DIM RMia(60> ,Rh2a<60) , RM,3a(60> ,Ut<60) , l..a(60> ,Ma(60),Ilt(60>
 DIM Otc(60),Bpip(60>,Bpta(60),Bp2p(60), Bp2a(60>,Rpi(60)
 DIM Rp2(60),Rp3(60),Utp(60),L.ap(60),Map(60),Htp(60),Otp(60)
 DIM Bppl(60),Bpp2(60),0pp(13>,Sitp(60),Fitp(60)
 PRINT "THIS PROGRAM CALCULATES  EITHER RETURN ON  INVESTMENT  OR
 PRINT "REQUIRED SALES PRICE    THE  FIRST  PART OF  THE
 PRINT "REQUESTS INPUTS   AFTER  THEY  ARE  ENTERED  YOU
 "PINT "A CHANCE TO REVIEW  AND  CORRECT THEM
                                               PROGRAM "
                                               WILL HAVE
 PRINT
 r.:n<"-im
 GO SUP

 nrjSi.j^

 COS! IP
 TF K'l;
360
380
710
BOS
935
< 5  " r
4 5 0 0
 TF E* = "C" THEN
 C,GSUF( 1090
 1 = 1.
 GOSUB 1115
 GO SUB 1.205
 IF I>i THEN .1.55
        !   NAME INPUT
        !   PROJECT COST AND  TIME  INPUTS
TAX JNF'O  INPUTS
ROI INFO  INPUTS
Oi'F-RAIING EXPENSE INPUTS
 EDIT Al. I. INPUTS
               r x EB . vALLIi-! FuC " i'.iR •!>

               (FIRST SALES PRICK EST.)
               (EARN, TAX, CASH  FLOW)  +  (SUM  RETURN)


                (NFU SALES ESTIMATE)
 GOSUB 1530
 GOTO 130
 IF APS (Up ( I) --UoCI '--I i >< Spa*Up(I)   THEN   346
 IF I>3 THEN :i.:iu
 1 = 1 + 1
 GOSUB 1530        i   (NEW SALES ESTIMATE)
 GOTO 130
 Ds3=ABS(Up(I~3)-Up(I-2> )
 Ds2 = ABS(Up(I-2)-Up(I-l> )
 Dsl = ABS(Up Ds2 OR Ds3  >  Dsi THEN 1.40
 PRINT " SUCCESSIVE CALCULATIONS DO NOT  IMPROVE  "
 PRINT " THE SOLUTION.  THESE PRICES  WERE  TRIED:  "
 FOR L = i TO I
FIXED 6
 PRINT " SALES PRICE TRIAL ";!...;" WAS  ";  Up(L)    ;  "PER" jG*
FIXED 0
 NEXT I...
 PRINT " DO YOU WISH TO PRINT THE OUTPUT  (Y)  "
 PRINT " OR QUIT WITH NO OUTPUT (N)?   CHOICE  Y EVENTUALLY ALLOWS A RERUN.
                                     A-2

-------
235
240
245
             THEN BOOO
255
260
265
270
275
280
285
290
295
300
305
310
315
320
325
330
335
340
345
346
347
350
360
365
370
375
380
385
390
395
400
405
41.0
415
420
425
430
435
440
445
450
455
460
465
470
47S
480
4H5
490
49S
500
505
507
510
515
520
525
535
538
540
545
550
                      !  EARNINGS,  TAX •»• CASH FLOU
                      (INITIAL EST.  RATE OF RETURN
                         CALC.  PRESENT VALUE FACTORS
                         PRESENT VALUES AND SUMS
                                  THEN 330
                       Roid)
                                   i
                                   !  CALC.
INPUT F$
IF F$ = "N
GOTO 346
GOSUB 1205
GOSUB 1475
1 = 0
Roid) = Roip
GOSUB 1090
GOSUB 1445
RrpM(I) = Tpw(Pl)
IF I<2 THEN 300
Dv = ABS(Rrpvd)-Rrpvd-i))
IF Dw > ABS(Rrpvd) + Rrpvd-D)
1 = 1 + 1
IF Rrpwd-1) > 0 THEN 320
Roip = R o i(I-i)-i
GOTO 265
Ro.ip = Roid-1) + 1
GOTO 265
Roip = (Rrpvd)/Dv>
GOSUB 1090
GOSUB 1445
GOSUB HIS
IF K* <> "
GOSUB 4400
GOSUB 2040
PRINT
PRINT
INPUT A*
RETURN
PRINT " ENTER THE TOTAL PROJECT COSTS "
INPUT PC
PRINT " ENTER TOTAL YEARS FOR PROJECT LIFE,
PRINT " INCLUDING CONSTRUCTION YEARS "
INPUT PI
PRINT " ENTER TOTAL YEARS FOR CONSTRUCTION "
INPUT Cy
Ydl = Cy + i
GOSUB 595           .!   DEPRECIATION  INPUTS
RETURN
PRINT
PRINT
PRINT
PRINT
PRINT
PRINT
FOR Y
PRINT
FINAL ROI INTERPOLATION
CALC. PRESENT VALUE FACTORS
      PRESENT VALUES AND SUMS
                       !  FOR ONLY THE PRESENT VALUE OF CASH OUTLAYS
              THEN 350
                        !  FOR OPERATING EXPENSE Y. BY CATEGORY
                       !  PRINT OUTPUTS   (END OF MAIN PROGRAM).
       " ENTER NAME OF PROJECT AND/OR CASE NUMBER "
       11 70 CHARACTERS MAX "
         CONSTRUCTION SCHEDULE ENTRIES "

         ENTER PERCENT SPENT IN EACH CONSTRUCTION YEAR-
         i TO Cy
         PERCENT SPENT IN YEAR
 INPUT Cp(Y)
 Co(Y) = (Pc*Cp(Y) >/100
 NEXT Y
 PRINT " FOR HOU MANY OTHER YEARS WILL THERE "
 PRINT " BE. CASH OUTLAYS OR RECOVERIES ? (MAXIMUM = 20)  "
 INPUT Yco
 FOR Z = i TO Yco
 PRINT " ENTER A YEAR NO.,  IT'S NET CASH OUTLAYS, "
PRINT " AND IF NOT DEPRECIABLE, THE LETTER N."
 PRINT " (FOR EXAMPLE 17,12900,N).   USE A - SIGN FOR CASH
 PRINT " RECOVERIES, (FOR EXAMPLE 35,-52500, ) "
 INPUT Y,C,Dep*
 Co(Y)  = C
 IF C<0 OR Dep*="N"  THEN 560
 Ya = Y + Tdy
 FOR Yy = Y TO Ya
 Aa = Yy - Y + Yd!
 Dct(Z.Yv) = C*(Dp(Aa>/100)
                                      A-3

-------
555
SAO
565
570
575
580
585
590
595
600
605
610
615
620
625
630
635
640
645
650
655
660
665
670
675
680
685
690
695
700
705
710
715
725
730
735
740
745
755
760
765
770
775
781
784
785
790
795
800
805
810
815
820
825
830
835
840
845
850
855
860
865
870
875
880
NEXT Yy
NEXT Z
FOR Y = Yd I TO PI
FOR DC = 1 TO Yc:o
Dft(Y) = Dft(Y) -f Dct(Dc,Y)
NEXT DC
NEXT Y
RETURN
PRINT " ENTER COST OF DEPRECIABLE ASSETS "
INPUT Da
PRINT " ENTER NUMBER OF YEARS FOR TAX DEPRECIATION "
PRINT " AFTER END OF CONSTRUCTION "
INPUT Tdy
PRINT " IS TAX DEPRECIATION STRAIGHT LINE ? Y OR N "
INPUT D*
Yde = Cy -f Tdy
IF D* = "N" THEN 665
FOR Y = Yd! TO Yde
Dft(Y) = Da/Tdy
Dp(Y) = 100/Tdy
NEXT Y
GOTO 700
PRINT " ENTER PERCENT DEPRECIATED EACH YEAR "
PRINT " STARTING WITH THE YEAR AFTER CONSTRUCTION ENDS '
FOR Y = Ydl TO Yde
PRINT " PERCENT DEPRECIATED IN YEAR  ">Y>" = "
INPUT Dp(Y)
Dft(Y) =  = 0 THEN  755
Ftr = (VAL(C*>)/100
Str = 0
PRINT " ENTER PERCENT STATE CORPORATE OR FRANCHISE "
PRINT " TAX RATE (DEFAULT IS OX).  IN THIS PROGRAM "
PRINT " FEDERAL TAX IS NOT A STATE TAX DEDUCTION "
INPUT Strp
Str = Strp/ 1.00
PRINT
PRINT " ENTER THE PERCENT INVESTMENT TAX CREDIT "
PRINT " APPLICABLE (FEDERAL) - NOT APPLIED TO CASH OUTLAYS FOLLOWING
PRINT " THE INITIAL CONSTRUCTION"
INPUT Itcp
RETURN
PRINT " IS RETURN ON INVESTMENT TO BE CALCULATED   100 THEN Spap =100
Soa = Snao/100
                                      A-4

-------
885  PRINT " ENTER ANNUAL SALES VOLUME,UNITS. FOR EXAMPLE—  185,TON"
890  INPUT Sv, G*
89S  IF E* = "S" THEN 980
900  PRINT " IF SALES PRICE WILL BE CONSTANT OVER PROJECT LIFE, "
905  PRINT " ENTER SALES PRICE PER  ";G$;"   IF YOU WISH TO  SUPPLY"
910  PRINT " FORECAST PRICES, ENTER F "
915  INPUT J*
920  IF J* = "F" THEN 955
925  JM = VAL
940  Sp(Y) = JM
945  NEXT Y
950  GOTO 980
955  FOR Y = Ydl. TO PI.
960  PRINT " ENTER FORECAST PRICE FOR YEAR   ";Y
965  INPUT Fp
1035 Expt = Expt + Ex(Y)
1040 NEXT Y
1045 GOTO 1085
1050 FOR Y = Ydl TO PI
1055 PRINT "  ENTER FORECAST NET OPERATING EXPENSE FOR YEAR   ";Y
1060 INPUT Ex(Y)
1065 Expt = Expt •*• Ex(Y)
1070 NEXT Y
1075 GOTO 1085
1080 GOSUB 2500
1085 RETURN
1090 Rf = l/(i + (Roip/100))
1095 FOR Y = i TO PI
1100 Pvf(Y) = <(RfAY)-(RfA(Y-1)))/LOG(Rf)
1105 NEXT Y
1110 RETURN
1115 Bf'-=Q
1120 Tvco = 0
1125 IF E$ = "C" THEN 1150
1130 FOR Y = Ydl TO PI
1135 Sf = Sf •«• Pvf(Y)
1140 NEXT Y
1145 Sfa = SfX(Pl-Cy)
1150 FOR Y = i TO PI
1155 Tuco = Tyco + Pvf(Y)*Co
1160 NEXT Y
1165 IF E* = "C" THEN 1.200
11.70 Sfr = Str +  - 
-------
1205
1206
1.21.0
1.215
1220
1.225
1230
 1240
 1245
 1250
 1255
 1.260
 1265
 1.270
 1275
 1200
 1285
 1290
 1295
1305
1310
1.315
1320
1325
1330
1335
1340
1345
1350
1355.
1360
1365
1370
1375
1380
1305
1395
1400
1.402
1405
1410
1.41.5
1435
1440
1441
1442
1443
1445
1450
1455
1460
1465
1470
1.475
1480
1485
1490
1495
1500
1505
1510
1515
1520
1525
!  FEDERAL INCOME TAX
Ccfc = 0
FOR Y = Ydl TO PI
EbT(Y) =  Sp*Str   ! STATE INC./FRANCHISE  TAX
Ti = 2500() THEN 1.290
IF Itc <= Fitl THEN 1275
Fit(Y) = 0
Itc = Itc - Fit!
GOTO 1355
Fit(Y) = FiTl-lTc
ITC = 0
GOTO 1355
IF Itc < 25000 THEN 1330
FT! = FiTl - 25000
ITC = ITC - 25000
Trie = 0.85*FTi
IF Tric<=Itc THEN 1345
FiT(Y) = FT! - ITC
ITC = 0
GOTO 1355
Fit(Y) = Fitl - Itc
Itc = 0
GOTO 1355
Itc = Itc - Trie
Fit(Y) = Ftl - Trie
Fitl = Ftr*Ti(Y-f.l)
IF Y - Yd! > 15 THEN Itc = 0
NEXT Y
CcfCO)
Tp v(0 )
 FOR Y
Cf(Y) =
Ccf(Y)
!  FEDERAL INCOME TAX
iit(Y) - Fit(Y)
CASH FLOW
CUMULATIVE
                               CASH FLOW
 THEN 1405
      PRESENT VALUES OF CASH FLOWS
      CUMULATIVE PRES. VALUES OF CASH FLOWS
              -Ccf  - i
        ' Ccf(Y-l) •»• Cf(Y)
IF Ccfc. > 0 OR Cc:f(Y) < 0
GOSUB 1441
IF E* = "C" THEN 1435
Pv(Y) = Cf(Y)*Pvf(Y)
Tpu(Y) = Tpu(Y-i) + Pv(Y>
NEXT Y
RETURN
Pop = Y - 1 + < <-l)*/-
Ccfc = 1
RETURN
Tpv(O) = 0
FOR Y = i TO PI
Pv(Y) = Cf(Y)*Pvf
Tpv(Y) = Tpw(Y-l) + Py(Y)
NEXT Y
RETURN
Tci = 0
Tco = 0
Fh = INT((P1 - Cy)/2 ) + Cy   ! YR. NO. TO END FIRST HALF CASH INTAKES
FOR Y ~ Ydl TO Fh
Tci = Tci + Cf(Y)
NEXT Y
FOR Y = i TO PI
Tco = Tco + Co
-------
1530 Tcf = 0
1535 FOR Y = Ydl TO PI
1540 Tcf = Tcf + Cf(Y)
1545 NEXT Y
1550 Sa = Sa*(i-« l + (Ro:ip/4> >*(Tpv(PD/Tcf )) )   !  NEW ANNUAL. SALES ESTIMATE
1555 FOR Y = Ydl TO PI
1560 Sp(Y) = Sa               !  FOR OUTPUT LISTING OF ANNUAL SALES
1565 NEXT Y
1570 Up(I) = Sa/Sv            !  NEW UNIT PRICE ESTIMATE
1575 RETURN
1580 IF «Y-i>/5-INT«Y-l>/5» = 0 THEN PRINT  !  SPACE TOP AND AFTER 5
1585 RETURN
1590 PRINT
1.595 PRINT
1600 PRINT " INPUTS WILL BE SHOWN IN SECTIONS FOR CHECKING.
1605 PRINT
1610 PRINT " A. PROGRAM NAME:  "
1615 PRINT
1620 PRINT A*
1625 GOSUB 2005
1630 IF 7* 0 "N" THEN 1640
1635 GOSUB 360
1640 PRINT " B.  PROJECT DATA "
1645 PRINT "     TOTAL PROJECT COST =   "-,  PC
1650 PRINT "     PROJECT LIFE INCLUDING CONSTRUCTION =   ";  PI
1655 PRINT "     CONSTRUCTION PERIOD IS TO BE   "; Cy j "  YEARS"
1660 GOSUB 2005
1665 IF 7* <> "N" THEN 1675
1670 GOSUB 380
1675 PRINT " C.  DEPRECIATION: "
1680 PRINT "     DEPRECIABLE ASSETS^  "> Da
1685 PRINT
1690 FOR Y = Yd! TO Yde
1695 PRINT "     7. DEPRECIATION  FOR YEAR  ">  Y >" = "jDp(Y)
1700 NEXT Y
1705 GOSUB 2005
1710 IF 7$ <> "N" THEN 1720
1715 GOSUB 595
1720 PRINT " D.  CONSTRUCTION AND OTHER OUTLAYS:
1725 FOR Y = 1 TO Cy
1730 PRINT "     PERCENT SPENT IN YEAR  " >  Y  ; "FOR CONSTRUCTION =  ";Cp(Y>
1735 NEXT Y
1738 PRINT
1740 FOR Y = Ydl TO PI
1745 IF Co = 0 THEN 1755
1750 PRINT "     CASH OUTLAYS FOR YEAR  ";Y >"= ">Co(Y)
1755 NEXT Y
1.760 GOSUB 2005
1765 IF 7$ <> "N" THEN 1775
1770 GOSUB 430
1775 PRINT
1780 PRINT " E.  TAX INFORMATION: "
1785 PRINT "     FEDERAL TAX RATE. IS "; 100*Ftr ; "PERCENT,  AND THE STATE "
1790 PRINT "     INCOME OR FRANCHISE TAX RATE IS  ">Strp>" PERCENT"
1795 PRINT
1800 PRINT "     THE INVESTMENT  TAX CREDIT  IS "iltcpj" PERCENT "
1805 PRINT "     OF THE DEPRECIABLE ASSETS NOT INCLUDING  CASH OUTLAYS"
1810 GOSUB 2005
1815 IF 7* <> "N" THEN 1825
1820 GOSUB 710
1825 PRINT "F.    RETURN ON INVESTMENT (ROD:  "
1.830 PRINT "     ROI IS TO BE
1835 IF E* = "C" THEN PRINT "      CALCULATED  FROM SALES YOU  SUPPLY"  ELSE.  1845
                                       A-7

-------
 1840 GOTO  1.950
 1845 PRINT  "     SUPPLIED BY YOU FOR CALCULATION OF REQUIRED SELLING PRICE."
 1R50 TF E$  =  "C" THEN  1870
 1RS5 PRINT  "     ROI IS  "iRoipi"  PERCENT AND THE SELLING PRICE"
 I860 PRINT  "     ACCURACY IS ";Sp*p> " PERCENT OF THE  SELLING  PRICE."
 1865 PRINT
 1870 PRINT  "     ANNUAL  SALES VOLUME IS  ";Su> G*
 1875 IF E*  =  "S" THEN  1.920
 1880 PRINT  "     ANNUAL  CASH INTAKES FROM SALES WILL BE BASED  ON  "
 1885 PRINT  "     THESE PRICES:"
 1890 PRINT
 189S PRINT  "YEAR   ", "FORECAST PRICE"
 1.900 FOR Y  =  Yd! TO PI
 1.905 GOSUB  1580
 1.910 PRINT  Y, Fp(Y)
 191.5 NEXT Y
 1920 GOSUB  3005
 1925 IF Z*  0 "N"  THEN 1935
 1.930 GOSUB  SOS
 1935 PRINT  "  G.  NET OPERATING EXPENSES:  "
 1.936 IF K*  =  "C" THEN  1967
 1.940 PRINT
 1945 PRINT  "  YEAR  ", "OPER.   EXPENSES"
 1950 FOR Y  =  Yd! TO PI
 1955 GOSUB  1580
 1.960 PRINT  Y, Ex(Y)
 1.965 NEXT Y
 1966 GOTO  1970
 1967 GOSUB  3500
 1.970 GOSUB  3005
 1975 IF Z*  0 "N"  THEN 1995
 1.980 GOSUB  985
 1985 PRINT  "  INPUT REVIEW COMPLETED - BUT THERE IS ALWAYS ANOTHER CHANCE.  "
 1.990 PRINT  "  WOULD YOU LIKE TO REVIEW THE INPUTS AGAIN 7  Y OR N   "
 1995 INPUT  Z*
 2000 IF Z$  -  "Y" THEN 1590 ELSE 2035
 3005 PRINT
 201.0 Z* =  ""
 2015 PRINT  "  IS THIS SECTION CORRECT ?  ENTER N TO RESUBMIT THE SECTION,  "
 2020 PRINT  "  OR CARRIAGE RETURN TO CHECK THE NEXT SECTION.  ALSO, USE  THE"
 3025 PRINT  "  CARRIAGE RETURN FOR VALUES WHICH ARE ALREADY CORRECT."
 2030 INPUT  Z$
 2035 RETURN
 2040 PRINT  "  DO YOU WANT A PAUSE (P) BETWEEN PAGES FOR CUSTOM  PRINTOUT,"
 2041 PRINT  "  OR DO YOU WANT CONTINUOUS "P" AND A1*O"C" THEN 2040
 3044 PRINT  A$
 2045 PRINT
 2046 Pr = 1
 2050 PRINT  " PAGE  1 -••- CASH OUTLAYS AND DEPRECIATION "
 2055 PRINT
 2060 PRINT  " YR. "; "CASH OUTLAYS","SALES","EARNINGS", "TAX"
 2065 PRINT  "     ">"   ","   ", "BEFORE TAX","DEPRECIATION"
 2070 PRINT
 2075 FIXED  0
 2080 FOR Y= 1 TO PI
 2085 GOSUB  1580
 2090 PRINT USING 2445; Y > Co(Y),Sp(Y>,Eht(Y),DfT(Y)
 2095 NEXT Y
 2100 GOSUB 2455
 2105 PRINT  A*
2110 PRINT
2115 PRINT  "PAGE 2 — TAXES AND CASH FLOW "
 2130 PRINT
                                      A-8

-------
2125 PRINT "YR. "; "STATE","TAXABLE"/'FEDERAL","CASH"
2130 PRINT "    ";" TAX","INCOME  (FED.)","TAX","FLOW"
2135 PRINT
2140 FOR Y =  1  TO PI
2145 GOSUB 1580
2150 PRINT USING 2445; Y  ;Sit(Y) ,Ti(Y),F11(Y),Cf(Y)
2155 NEXT Y
2160 GOSUB 2455
2165 PRINT A*
2170 PRINT
2175 FIXED 3
2180 PRINT "PAGE 3 —- CUMULATIVE CASH FLOWS AND PRESENT VALUES  "
2185 PRINT "          FOR "; Roip ;  " PERCENT  RETURN ON INVESTMENT"
21,Pvf(Y),Pv
2230 NEXT Y
2235 GOSUB 2455
2240 PRINT A*
2245 PRINT
2250 PRINT "APPENDIX A — PRICE, RETURN AND OTHER INFORMATION"
2255 PRINT
2260 IF ,T* =  "F" THEN 2300
2265 IF E* =  "C" THEN 2300
2270 FIXED 6
2275 PRINT "     THE PRICE IS "; Up(I)       /'PER "; G*
2280 FIXED 0
2285 .PRINT "     VALUE OF AVERAGE ANNUAL BALES: ";Sa
2290 FIXED 4
2295 PRINT "     REQUIRED ACCURACY:     ",Spap;"X"
2300 PRINT
2305 FIXED 1
2310 PRINT "     THE RETURN ON INVESTMENT  IS  "; Roip ; "PERCENT"
2315 FIXED 2
2320 PRINT
2325 PRINT "     THE PAYOUT PERIOD  IS ";  Pop  ; "YEARS."
2330 PRINT
2335 FIXED 0
2340 PRINT
2345 PRINT "     THE TOTAL PRESENT  VALUES OF ALL CASH OUTLAYS-.   ";Twc.o
2350 IF E* :=  "S" THEN 2365
2355 PRINT "     TOTAL CASH OUTLAYS:       ";Tco
2356 PRINT
2360 IF E* -  "C" THEN 2405
2365 PRINT "     THIS SOLUTION REQUIRED ";I  /'ITERATIONS"
2370 PRINT "     THE FOLLOWING SALES WERE TRIED: "
2375 FIXED 4
2380 PRINT
2385 PRINT "ITERATION" , "PR ICE. /  ";G$
2390 FOR W =  1 TO I
2395 PRINT W  , Up(W)
2400 NEXT W
2401 IF K$ 0 "C" THEN 2405
2402 GOSUB 4600
2405 GOSUB 2455
2410 PRINT
2411 IF K* <> "C" THEN 2415
2412 GOSUB 3500
2413 Pr = 0
2414 GOSUB 4900
2415 PRINT " IF YOU WISH TO RE-EDIT THE INPUTS, AND RERUN THE PROGRAM, "
2420 PRINT " ENTER  RR "
2425 INPUT Rr*
                                        A-9

-------
 2430
 2435
 2440
 2445
 2446
 2447
 2448
 2450
 2455
 2456
 2460
 2465
 2470
 2475
 2480
 2485
 2490
 2491
 2492
 2493
 2494
 2495
 2500
 2505
 2510
 2515
 2520
 2525
 2530
 2535
 2540
 2541
 2542
 2543
 2544
 2545
 2546
 2547
 2548
 2550
 2551
 2555
 2560
2565
 2570
 2575
2580
2590
 2595
2596
 2600
2605
 2610
2615
2625
 2630
2635
2636
 2640
2645
 2646
2650
 26S5
2660
2665
 2670
2675
STANDARD
If Rr$ = "RR» THEN 5000 ELSE 7980
RETURN
IMAGE DD,ilD,i6D,200,201)
IMAGE I)D,10D.DD,, 17D,15D.DD,1 OX,DD . 3D
IMAGE DD,13D. 21) ,2X, 12D . 3D , 14D . DD, 2X , 1 ID .3D
I MAGE DD, 3X, K , !3X , K , 20I), 12X, 2D . 3D
IMAGE DD,13D,6X,Z.6D,17D,2X,20D
PRINT
IF Al* = "C" AND Pr = 1 THEN 2492
PRINT
PRINT " THE PROGRAM HAS PAUSED.  THE TERMINAL MAY BE PUT IN LOCAL MODE1
PRINT " TO PRINT OUT OR MANIPULATE THE DISPLAY.   WHEN READY FOR THE "
        NEXT PAGE, ENSURE THE TERMINAL IS IN REMOTE MODE AND TYPE"
        CONT.  IF YOU WISH TO QUIT, TYPE STOP.  CAUTION!!!!
        STOP CAUSES LOSS OF ALL DATA!!! "
PRINT
PRINT
PRINT
PAUSE
GOTO 2495
FOR P5 = 1
PRINT
NEXT P5
 RETURN
PRINT
PRINT
PRINT
PRINT
PRINT
PRINT
PRINT
PRINT
PRINT
PRINT
PRINT
PRINT
PRINT
PRINT
PRINT
PRINT
           TO 10
        INPUTS CAN BE MADE IN THESE OPERATING COST CATEGORIES:"
            3 RAW MATERIALS (UNIT COST, ANNUAL CONSUMPTION EACH)"
            UTILITIES"
            TOTAL OPERATING LABOR"
            TOTAL MAINTENANCE "
            INSURANCE PLUS LOCAL TAXES"
            ONE OTHER COST ITEM, YOU NAME IT"
            2 BY-PRODUCT CREDITS (UNIT PRICE, ANNUAL SALES EACH)"
      "in
             CAUTION
        IN THE NEXT SECTION, A ZERO INPUT IS NOT RECOGNIZED - THE"
        COMPUTER WILL ASSIGN THE PREVIOUS YEAR'S VALUE TO THE"
        CURRENT YEAR.  IF ZERO IS DESIRED, IT CAN BE APPROXIMATED"
        BY A VERY SMALL NUMBER "
GOSUB 7945
IF Sk$ = "S" THEN 2635
Bi = i
PRINT "      ENTER THE NAME OF THE FIRST RAW MATERIAL:"
INPUT Rwi$
FOR Y = Yd! TO PI
PRINT " ENTER UNIT COST FOR YEAR ";Y;"   IF SAME AS PREVIOUS "
PRINT " YEAR, MAKE NO ENTRY "
INPUT RMlc(Y)
IF Rnlc(Y) = 0 THEN Rwlc"
PRINT " YEAR, MAKE NO ENTRY."
INPUT RMla(Y)
IF RMia(Y) = 0 THEN RMla(Y) = RMia(Y-l)
NEXT Y
PRINT
PRINT " THE NEXT CATEGORY IS THE SECOND RAW MATERIAL,"
GOSUB 7945
IF Sk* = "S" THEN 2727
B2=l
PRINT "ENTER THE NAME OE THE SECOND RAW MATERIAL:"
INPUT Rd2*
FOR Y = Yd! TO PI
PRINT " ENTER UNIT COST FOR YEAR ";Y;"
PRINT " YEAR, MAKE NO ENTRY."
INPUT R«2c(Y)
                                          IF  SAME AS  PREVIOUS
                                         IF  SAME  AS  PREVIOUS
                                       A-10

-------
2685 IF RM2c(Y) = 0 THEN R«2c = RM2c = 0 THEN Rfi2a = RM2a
2775 IF R«3r(Y) = 0 THEN Rp\3c
2890 NEXT Y
2895 GOTO 2931
2900 FOR Y = Ydi TO PI •
2905 PRINT " ENTER ANNUAL UTILITY COST  FOR YEAR ">Y;" IF SAME. AS "
291.0 PRINT " PREVIOUS YEAR , MAKE NO ENTRY."
2915 INPUT Ut
-------
2980 FOR Y = Ydl TO PI
2985 PRINT " ENTER ANNUAL. LABOR COST FOR YEAR  ";Y;" IF SAME AS  "
2990 PRINT " PREVIOUS YEAR  , MAKE NO ENTRY."
2995 INPUT La(Y>
3005 IF La(Y) = 0 THEN l..a(Y) = La(Y-i)
3010 NEXT Y
3011 PRINT
3012 PRINT " THE NEXT CATEGORY IS THE TOTAL MAINTENANCE,"
3013 GOSUB 7945
3014 IF Sk* = "S" THEN 3092
3015 PRINT " IF MAINTENANCE COST WILL BE CONSTANT OVER THE"
3020 PRINT " PROJECT LIFE, ENTER THE AMOUNT.   IF YOU WISH  "
3025 PRINT " TO SUPPLY FORECAST COSTS, ENTER F."
3030 INPUT Ma*
3031 B6=l
3035 IF Ma* = "F" THEN 3060
3040 FOR Y = Ydl TO PI.
3045 Ma(Y) = VAL(MaS)
3050 NEXT Y
3055 GOTO 3092
3060 FOR Y = Ydl TO PI
3065 PRINT " ENTER ANNUAL. MAINTENANCE COST FOR YEAR ";Y>"  IF SAME AS '
3070 PRINT " PREVIOUS YEAR , MAKE NO ENTRY."
3075 INPUT Ma
3085 IF Ma(Y) = 0 THEN Ma(Y> = Ma(Y-i)
3090 NEXT Y
3092 PRINT
3093 PRINT " THE NEXT CATEGORY IS INSURANCE PLUS LOCAL TAXES,"
3095 GOSUB 7945
3098 IF Sk* = "S" THEN 3176
3099 B7=l
3100 PRINT " IF INSURANCE AND LOCAL TAXES WILL BE CONSTANT OVER THE"
3105 PRINT " PROJECT LIFE, ENTER THE AMOUNT.   IF YOU WISH  "
3110 PRINT " TO SUPPLY FORECAST COSTS, ENTER F."
3115 INPUT lit*
3120 IF lit* = "F" THEN 3145
3125 FOR Y = Ydl TO PI
3130 ITt(Y) = VALdlt*)
3135 NEXT Y
3140 GOTO 3176
3145 FOR Y = Ydl TO PI
31.50 PRINT " ENTER INSURANCE AND LOCAL TAX COST FOR YEAR ">Y
31.55 PRINT " IF SAME AS THE PREVIOUS YEAR , MAKE NO ENTRY."
3160 INPUT IJ. t(Y)
3170 IF I1t(Y) = 0 THEN Ilt(Y) = H.t(Y~l)
3175 NEXT Y
3176 PRINT
3177 PRINT " THE NEXT CATEGORY IS GENERAL; A NAME WILL BE REQUESTED."
3180 GOSUB 7945
3182 IF Sk* = "S" THEN 3272
3183 B8=l
3185 PRINT " ENTER THE NAME OF ANOTHER COST CATEGORY;"
3190 INPUT Ot*
3195 PRINT " IF ";0t$;" COST WILL BE"
3200 PRINT " CONSTANT OVER THE PROJECT LIFE, ENTER THE AMOUNT."
3205 PRINT " IF YOU WISH TO SUPPLY FORECAST COSTS, ENTER F."
3210 INPUT Otr*
3215 IF Otc* = "F" THEN 3240
3220 FOR Y = Ydl TO PI
3225 Otc(Y) = VAL(Otc$)
3230 NEXT Y
3235 GOTO 3272
3240 FOR Y = Yd! TO PI
3245 PRINT " ENTER ">0t*;" COST FOR  YEAR ">Y
3250 PRINT " IF SAME AS THE PREVIOUS YEAR ,,  MAKE NO ENTRY."
3255 INPUT Otc(Y)
3265 IF Otc(Y) = 0 THEN Otc(Y) = Otc(Y-l)
3270 NEXT Y


                                        A-12

-------
 3272 PRINT
 33.73 PRINT " THE NEXT CATEGORY IS THE FIRST BY-PRODUCT  CREDIT."
 3275 GOB LIB 7945
 3277 IF Sk$="S"THEN 3350
 3370 B9=l
 320(1 PRINT "ENTER THE NAME 01" THE FIRST BY-PRODUCT:"
 3285 INPUT Bplt>
 3290 FOR Y = Ydi TO PI
 3295 PRINT " ENTER UNIT PRICE FOR YEAR "-.Y;".  IF SAME  AS  PREVIOUS  "
 3300 PRINT " YEAR, MAKE NO ENTRY."
 3305 INPUT Bplp(Y)
 3310 IF Bplp = Bplp(Y-i)
 331.5 NEXT Y
 3316 GOSUB 4(300
 3320 FOR Y = Ydl TO PI
 332S PRINT " ENTER ANNUAL SALES •VOLUME: FOR YEAR ";Y;"  .  IF SAME AS"
 3330 PRINT " PREVIOUS YEAR, MAKE NO ENTRY."
 3335 INPUT Bpla(Y)
 3340 IF Bpia = 0 THEN Bpia(Y) = Bpia(Y-l)
 3345 NEXT Y
 3350 PRINT
 3355 PRINT " THE LAST CATEGORY IS THE SECOND BY-PRODUCT CREDIT."
 3360 GOSUB 7945
 3362 IF SI<*-"S"THETN 3435
 3363 B 1.0 = 1
 3365 PRINT "ENTER THE NAME OF THE SECOND BY-PRODUCT:"
 3370 INPUT Bp2*
 3375 FOR Y = Ydi TO PI
 3300 PRINT " ENTER UNIT PRICE-: FOR YEAR ";Y;".  IF SAME  AS  PREVIOUS  "
 3385 PRINT " YEAR, MAKE MO ENTRY."
 3390 INPUT Bp2p(Y)
 3395 IF Bp2p(Y) = 0 THEN Bp2p = Bp2.p "  .  IF SAME. AS"
 3415 PRINT " PREVIOUS YEAR, MAKE NO ENTRY."
 3420 INPUT Bn2a
-------
36053 PRINT "APPENDIX B	-OPERATING COST DETAIL,  ";RM2*;" PAGE 2"
3609 PRINT
3610 IF Pr = 1 THEN 3614
3611 GOSUB 7945
361.3 IF Sk* = "S" THEN 3690
3614 PRINT "YR   " ;RM2*,RM2$,R«2*,"PERCENT OF"
361.5 PRINT "     "."UNIT COST" , "ANNUAL CONS.","COST","EXPENSES *"
36,30 PRINT
3635 FOR Y- 1. TO PI.
3630 GOSUB 1580
3635 PRINT USING 2446; Y >Rii2c ( Y ) , R«2a < Y ) ,Rcst2< Y) ,Rp2< Y)
3645 NEXT Y
3650 GOSUB 2455
3655 GOTO 3670
3660 PRINT " NO ENTRIES FOR SECOND RAW MATERIAL, PAGE 2 SKIPPED."
3665 GOTO 3690
3670 PRINT A*
3685 PRINT
3690 IF B3 = 0 THEN 3745
369,? PRINT
3693 PRINT "APPENDIX B—OPERATING COST DETAIL,  ";RM3*>" PAGE 3"
3694 PRINT
3695 IF Pr = 1 THEN 3699
3696 GOSUB 7945
3697 IF Sk* = "S" THEN 3775
3699 PRINT "YR .   "> Rn3* ,, R«3'6, RM3*, "PERCENT OF"
3700 PRINT "     "i"UNIT COST","ANNUAL CONS.","COST","EXPENSES *"
3705 PRINT
3710 FOR Y= 1 TO PI
3715 GOSUB 1580
371B PRINT USING 2446; Y >Rw3c: ( Y > ,Rfi3a (Y) ,Rcst3< Y) ,Rp3< Y)
3730 NEXT Y
3735 GOSUB 2455
3740 GOTO 3755
3745 PRINT " NO ENTRIES FOR THE THIRD RAW MATERIAL, PAGE 3 SKIPPED."
3750 GOTO 3775
3755 PRINT A*
3770 PRINT
3775 IF B4 = 0 AND P5 = 0 THEN 3045
3777 PRINT
377R PRINT "APPENDIX B—OPERATING COST DETAIL,  UTILITIES AND LABOR, PAGE 4"
3779 PRINT
3780 IF Pr = 1 THEN 3784
3781 GOSUB 7945
378? IF Sk* = "S" THEN 3875
3784 PRINT "YR   'V'UTU. ITIES","UTILITIES X","LABOR","LABOR %"
1785 PRINT "     "."COST","OF EXPENSES *", "COST ","OF EXPENSES *"
3790 PRINT
3800 FOR Y= 1 TO PI
3805 GOSUB 1580
3810 IF Ut$ = "P" THEN 3825
3815 PRINT USING 2447j Y ; 1.11 < Y ) ,l!tp ( Y) ,l...a < Y ) , Lap < Y)
3820 GOTO 3830
3B,?5 PRINT USING 2448: Y;"  < IN-PI... ANT) ", " 0 0 00 " , La (Y ) , Lap (Y )
3830 NEXT Y
3835 GOSUB ,?455
3840 GOTO 3855
3845 PRINT " NO ENTRIES FOR UTILITIES OR LABOR, PAGE 4 SKIPPED"
3850 GOTO 3875
3BS5 PRINT A*
3870 PRINT
3875 IF B6 = 0 AND B7 = 0 THEN 3930
3877 PRINT
3878 PRINT "APPENDIX B—OPERATING COST DETAIL, MAINT., INS. & LCI. TAX PAGE 5"
3879 PRINT
                                       A-14

-------
3880  IF Pr =  1 THEN 3884
3881  GOSUB 7945
388;?  IF Sl<* =  "S" THEN 3960
3884  PRINT "YR   "; "MAINTENANCE ", "MAINTENANCE  X" ," INSURANCE" , "INS t> LCI... TAX X"
3885  PRINT "     "i"COST","OF  EXPENSES  *  ","\  LOCAL.  TAX","OF  EXPENSES *"
3890  PRINT
3895  FOR  Y= 1  TO PI
3905  GOSUB 1.580
3910  PRINT USING 2447; Y;Ma(Y),Map(Y),111(Y),Iltp(Y)
3915  NEXT Y
3930  GOSUB 2455
3925  GOTO 3940
3930  PRINT " NO  ENTRIES FOR EITHER MAINTENANCE OR FOR  INSURANCE  "
3931  PRINT "  PLUS LOCAL TAXES,  PAGE  5  SKIPPED"
3935  GOTO 3960
3940  PRINT A*
3955  PRINT
3960  IF B8 =  0   THEN 4010
3961  PRINT
396?  PRINT "APPENDIX B—OPERATING COST DETAIL, OTHER COSTS, PAGE. 6"
3963  PRINT
3965  IF Pr = 1. THEN 3969
3966  GOSUB 7945
3967  IF 8k* =  "S" THEN 4040
3969  PRINT "YR.  "; Ot*,0t*
3970  PRINT "     "'; "COST","X OF EXPENSES *"
3975  PRINT
3980  FOR  Y= 1 TO PI
3985  GOSUB 1.580
3990  PRINT USING 2447 ; Y , 01c(V),01p(Y)
3995  NEXT Y
4000  GOSUB 2455
4005  GOTO 4020
4010  PRINT " NO ENTRIES FOR 'OTHER'  COSTS, PAGE 6 SKIPPED"
4015  GOTO 4040
4020  PRINT A*
4035  PRINT
4040  IF B9 = 0 THEN 4085
4042  PRINT
4043  PRINT "APPENDIX B—OPERATING COST DETAIL, ";Bpi*;" PAGE 7"
4044  PRINT
4045  IF Pr = 1 THEN 4049
4046  GOSUB 7945
4047  IF Sk* =  "S" THEN 41.15
4049  PRINT "YR   "; Bp It, Bp 1.*, Bp It, "PERCENT OF"
4050  PRINT "     "."UNIT PRICE","ANNUAL SALES" ,"CREDIT","EXPENSES *"
4055  PRINT
4060  FOR  Y= 1 TO PI
4065  GOSUB 1580
4070  PRINT USING 2446;  Y ;Bpip ,Bpia(Y),Bpis,Bppl(Y)
4075  NEXT Y
4080  GOSUB 2455
4082  GOTO 4095
4085  PRINT " NO ENTRIES FOR THE FIRST BY-PRODUCT, PAGE 7 SKIPPED"
4090  GOTO 411.0
4095  PRINT A*
4110  PRINT
4115  IF B10 = 0 THEN 4165
41.1.7  PRINT
4118  PRINT "APPENDIX B—OPERATING COST DETAIL, ">Bp2*;" PAGE 8 "
411.9  PRINT
41.20  IF Pr " 1 THEM 4124
4121  GOSUB 7945
41.22  IF Sk* = "S" THEN 41.8?
4124  PRINT "YR.  "> Bp?>* - Bp2* , Bp2t, "PERCENT OF"
4125  PRINT "      'V'UNIT PRICE","ANNUAL SALES","CREDIT","EXPENSES #"
4130  PRINT
41.35  FOR  Y= 1  TO PI
                                       A-15

-------
 4140  GOSUB  1580
 41.45  PRINT  USING  2446;  Y >Bp2p ( Y ) , Bp2a ( Y ) ,Bp2s< Y ) ,Bpp2( Y )
 4150  NEXT Y
 4160  GOTO 41.70
 4165  PRINT  "  NO ENTRIES FOR  SECOND BY-PRODUCT, PAGE '8 SKIPPED"
 4170  PRINT
 4175  PRINT  "* EXPENSES  INCLUDE OPERATING  EXPENSES (NO CREDITS), PLUS1
 41.80  PRINT  "  STATE  AND  FEDERAL TAXES"
 4101  GOSUB  2455
 4182  PRINT
 4185  RETURN

 4305  FOR Y = Ydl TO PI.
 4306  Rcstl(Y) = RMic(Y)*RMla*R
 4325  Tut ™  Tut +  Ut(Y)
 4330  Tla =  Tla +  L.a(Y)
 4335  Twa •-  Tna +  Ma(Y)
 4340  Tilt =•• Tilt  +  II. t(Y)
 4345  Totr = Tote  +  Otc(Y)
 4350  Tbpl -- Tbpl  •»•  Kpis(Y)
 4355  Thp2 = Thp2  •*•  Bp;:.'s(Y)
 4360  Fx(Y)-=Rcsti( Y) +Rcst2( Y )+Rcst3( Y) -HJt < Y)+L.a< Y)+Ma < Y > + Ilt < Y)+Otc (Y )
 4361.  Ex(Y)  •=  Ex(Y)  -  Bpis.= <100*Tr«l)/Txp
 4480  Opp<2> = <100*TrM2>/Txp
4485  Opp(3> = (100*TrM3)/Txp
 4490  Opp(4) = (100*Tut)/Txp
4495 Opp(5) = (100*Tla)/Txp
 4500 Opp(6) = (iOO*Tna)/Txp
4505 Opp(7) = <100*Ti1.t)/Txp
 4510 Opp(8) = (100*Totc)/Txp
451.5 Opp(9) = <100*Tsit)/Txp
 4520 Opp(lO) = (100*Tfit)/Txp
4525 Opp(il) ™ (100*rbpi)/Txp
 4530 Opp(12) = <100*Tbp2)/Txp
4535 RETURN
 4600 PRINT
                                        A-16

-------
PROJECT LIFE FRACTIONAL EXPENSE SUMMARY"

          	PERCENT OF TOTAL EXPENSES *"
4605 PRINT
461.0 PRINT "
461.1. PRINT
461.2 PRINT
4615 PRINT "EXPENSE CATEGORY
4619 Cr$ = "  (CREDIT)  "
4620 FIXED 3
4621. IMAGE 30X,DD.3D
4622 IMAGE 10X,DD.3D
4623 IMAGE 10X,K , 1. OX ,DD . 3D
4625 PRINT
4630 PRINT Rfil*;" . ",
4631. PRINT USING 4621 > Opp
4645 PRINT "UTILITIES",
4646 PRINT USING 4621; Opp(4)
4650 PRINT "OPERATING  LABOR",
4651 PRINT USING 4621> Opp<5>
4652 PRINT
4655 PRINT "MAINTENANCE",
4656 PRINT USING 4621; Opp(6>
4660 PRINT "INSURANCE  PLUS LOCAL TAXES",
4661. PRINT USING 4622; Opp(7)
4670 PRINT Ot*; " .",
4671 PRINT USING 4621, Opp<8)
4675 PRINT "STATE TAX",
4676 PRINT USING 4621; Qpp<9)
4680 PRINT "FEDERAL TAX",
4681 PRINT USING 4621; QppdO)
4605 PRINT
4690 PRINT Bpi*}".",
4691 PRINT USING 4623;Cr$,Opp<11)
4695 PRINT Bp2*>".",
4696 PRINT USING 4623 ;(>*, Opp ( 1.2 >
4700 PRINT
4705 PRINT
4710 PRINT "  * EXPENSES INCLUDE OPERATING EXPENSES  (NO CREDITS),PLUS"
4715 PRINT "  STATE AND FEDERAL TAXES."
4720 RETURN
4800 PRINT
4805 PRINT
4810 PRINT "  COST/PRICE SECTION COMPLETED.  NEXT, ENTER THE ANNUAL"
4815 PRINT "  VOLUME  IN CONSISTENT UNITS."
4820 PRINT
4825 PRINT
4830 RETURN
4900 PRINT A*
4905 PRINT
4910 PRINT "APPENDIX C—TAXES AS A PERCENT OF TOTAL EXPENSES *"
4915 PRINT
4920 PRINT "YR.  ";"STATE TAX","STATE TAX","FEDERAL TAX","FEDERAL. TAX"
4925 PRINT "     "; "AMOUNT", "% OF- EXPENSES *", "AMOUNT" , "7. OF EXPENSES *"
4930 PRINT
4935 FOR Y «  t  TO PI
4940 GOSUP 1580
4945 PRINT USING 2447; Y ;S:i. t ( Y> ,Si tp (Y) ,Fi t ( Y ) ,Fi tp ( Y )
4950 NEXT Y
4955 PRINT
4960 PRINT "* EXPENSES INCLUDE OPERATING EXPENSES (NO CREDITS), PLUS"
4965 PRINT "  STATE .AND FEDERAL TAXES"
4970 RETURN
5000 PRINT "  DO YOU WISH TO READ THE RE-RUN EDIT SUGGESTIONS ? (Y OR N>"
5001 INPUT Re*
5010 IF Re* = "N" THEN 1.00
5015 PRINT "   THE FIRST STEP IN A RERUN  IS TO EDIT ALL INPUTS.   INPUT VARIABLES'
                 A-17

-------
 50,?(1 PRINT  " WILL REMAIN THE SAME UNLESS CHANGED.  WHEN CARRIAGE RETURN IS"
5025 PRINT
5030 PRINT
5035 PRINT
5040 PRINT
5045 PRINT
        KEYED IN RESPONSE TO A ,  THE VARIABLE REMAINS UNCHANGED FROM"
        THE PREVIOUS RUN."

         IF OPERATING EXPENSES WERE  ENTERED BY CATEGORY, SECTIONS MAY"
        BE SKIPPED WITHOUT ALTERING  THE INPUT VARIABLES.  ALSO, KEYING"
5050 PRINT " CARRIAGE RETURN IN THIS SECTION DOES NOT GIVE THE PREVIOUS YEAR'S"
5055
•5060
5065
5070
5075
5080
5085
5090
5095
6000
7945
7946
7950
7965
7970
7980
7981
7983
7984
8000
8010
PRINT " VALUE AS IT DID IN THE FIRST RUN,  INSTEAD IT CAUSES THE VALUE"
PRINT " USED IN THE PREVIOUS RUN TO BE RETAINED.   HOWEVER,  THE YEAR TO"
        YEAR REPEAT FEATURE CAN BE UTILIZED BY KEYING IN A  (0).  FOR"
        EXAMPLE, IN A RERUN  YOU MAY WISH  TO CHANGE LABOR COSTS TO"
        13.682E6 FOR YEARS 1.4 THROUGH 31.   IT MAY BE ENTERED FOR YEAR"
        NUMBER 14 THEN REPEATED FOR YEARS  IS - 31 BY KEYING 0 CARRIAGE"
        RETURN.  DURING INPUT CHECKING,  CALCULATED VARIABLES WILL BE"
        SHOWN AS LEFT OVER FROM THE PREVIOUS RUN, BUT THEY  WILL BE "
        CHANGED DURING CALCULATION."
PRINT "
PRINT "
PRINT "
PRINT "
PRINT "
PRINT "
PRINT "
GOTO 100
Sk* = ""
PRINT " IF YOU WISH TO SKIP THE NEXT CATEGORY,  ENTER S "
INPUT Sk'f
PRINT
RETURN
PRINT " DO YOU REALLY WANT TO QUIT AND LOSE ALL YOUR INPUT DATA ?"
PRINT " (Y OR N)"
INPUT Rq*
IF Rq$ = "Y" THEN 8000 ELSE 5000
STOP
END
                                       A-18

-------
    Some program modifications were required to handle the state tax for the eastern high-sulfur
case.   The state chosen  for this case,  Ohio, has  a  net worth tax and it  was convenient to
temporarily modify the program to handle it.   For  broader  applications it could be desirable to
write this feature into the program as a regular option.   The  following printout shows the lines
which were modified; changes are circled.
      DIM Ebt(60> jExCbO) - F ':> t (60 ) ,I>cp(60> ,Dct(20 ,1.00)
                                                        _
 2 0    D I M P M ( 6 0 ) ,  P v f ( 6 0 > ,  R o :i. ( 6 0 ) ,  R r p v ( 6 0 ) , F p ( 6 0 )|>(3c(26)
      Sit(Y)=  Si-NY)  THEN Sit(Y)  =  Nwt
 1.21 R S:it(Y)  ==  Si. t(Y)  •«  Qc)))  I
          I
 1220  T:i(Y) -~  Eht(Y> ••••  Dft(Y) - Sit(Y)  ! FEDERAL TAXABLE INCOME


 32SO  PBTMT  "  IF SAHF AS THE PREVIOUS YEAR  ,  MAKE NO  ENTRY  "
      INPUT DC (Y)|
 3995 NEXT  V
3996 PRINT
3997 PRINT  "  *** STATE  TAX CREDITS FOR LOCAL TAXES WERE USED  TO  CALCULATE"
3998 PRINT  "  THE STATE  TAX AND  ARE NOT INCLUDED HERE."    	    	
 4000 GOSUB  2455


 471.5 PRINT  "  STATE AND  FEDERAL TAXES. "
 4716 PRINT
 471.7 PRINT  "  *** STATE  TAX CREDITS FOR LOCAL TAXES WERE USED TO  CALCULATE"
 471R PRINT  "  THE STATE  TAX AND  ARE NOT INCLUDED HERE."
4720  RETURN
                                     A-19

-------
                     APPENDIX B
Example Computer Output for One Complete Price Calculation

-------
                                          Example Computer Output
WESTERN LOU-SULFUR	CASE 7

 PAGE 1 —• CASH OUTLAYS AND DEPRECIATION
 YR .  CASH OUTLAYS
SALES
                    EARNINGS
                    BEFORE TAX
TAX
DEPRECIATION
i
2
3
4
5
6
7
8
9
10
ii
12
13
14
15
16
17
18
19
SO
21
22
23
24
25
131555160
252147390
328887900
252147390
131555160
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
        0
        0
        0
        0
        0

553683020
553683020
553683020
553683020
553683020

553683020
553683020
553683020
553683020
553683020

553683020
553683020
553683020
553683020
553683020

553683020
553683020
553683020
553683020
553683020
                                                0
                                                0
                                                0
                                                0
                                                0

                                        499568987
                                        499573940
                                        499578893
                                        499583846
                                        499588799

                                        487953752
                                        476318705
                                        464713658
                                        453078611
                                        441452564

                                        441457517
                                        441462470
                                        441467423
                                        441472376
                                        441477329

                                        441482282
                                        441487235
                                        441492188
                                        441497141
                                        441502094
                                                0
                                                0
                                                0
                                                0
                                                0

                                        146387850
                                        214702.180
                                        204942990
                                        204942990
                                        204942990

                                                0
                                                0
                                                0
                                                0
                                                0

                                                0
                                                0
                                                0
                                                0
                                                0

                                                0
                                                0
                                                0
                                                0
                                                0
                               B-2

-------
UFSTERN LOU-SULFUR	CASE 7

PAGE 2 --•• TAXES AND CASH FLOW
YR.  STATE
    TAX
TAXABLE
INCOME (FED.)
FEDERAL
TAX
CASH
FLOW
 i
 2
 3
 4
 5

 6
 7
 8
 9
10

11
12
13
14
15

16
17
18
19
20

21
22
23
24
25
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
353181137
284871760
294635903
294640856
294645809
487953752
476318705
464713658
453078611
441452564
441457517
441462470
441467423
441472376
441477329
441482282
441487235
441492188
441497141
441502094
                            0
                            0
                            0
                            0
                            0

                     64871423
                    131041009
                    135532515
                    135534794
                    135537072

                    224458726
                    219106604
                    213768282
                    208416161
                    203068179

                    203070458
                    203072736
                    203075014
                    203077293
                    203079571

                    203031850
                    203084128
                    203086406
                    203088685
                    203090963
                   -131555160
                   -252147390
                   -328887900
                   -252147390
                   -131555160

                    434697564
                    368532930
                    364046377
                    364049052
                    364051727

                    263495026
                    257212100
                    250945375
                    244662450
                    238384384

                    238387059
                    238389734
                    238392408
                    238395083
                    238397757

                    238400432
                    238403107
                    238405781
                    238408456
                    238411131
                               B-3

-------
WESTERN LOU-SULFUR	CASE 7
PAGE 3— CUMULATIVE CASH FLOWS AND PRESENT VALUES
          FOR  20.000  PERCENT RETURN ON INVESTMENT
YR.

i
2
3
4
5
6
7
8
9
10
ii
12
13
14
15
16
17
1G
19
20
21
22
23
24
25
CUMULATIVE
CASH FLOW
-131555160
-383702550
-712590450
-964737840
-1096293000
-661595436
-293062506
70983871
435032923
799084650
1062579676
1319791776
1570737151
1815399601
2053783985
2292171044
2530560778
2768953186
3007348269
3245746026
3484146458
3722549565
3960955346
4199363802
4437774933
                    PRESENT
                    VALUE FACTOR
                     0.914136
                     0 761780
                     0.634817
                     0.529014
                     0.440845

                     0.367371
                     0.306142
                     0.255119
                     0.212599
                     0.177166

                     0.147638
                     0.123032
                     0.102526
                     0.085439
                     0.071199

                     0.059332
                     0 . 049444
                     0.041203
                     0.034336
                     0.028613

                     0.023844
                     0.019870
                     0.016559
                     0.013799
                     0.011499
    PRESENT
    VALUES
-120259285
-192080802
-208783480
•133389446
 -57995411

 159695142
 112823496
 92874977
 77396383
 64497460

 38901889
 31645242
 25728530
 20903637
 16972706

 14144080
 11786866
  9822498
  8185507
  6821333

  5684508
  4737143
  3947663
  3289756
  2741494
  CUMULATIVE
  PRES. VALUES
-120259285
-312340087
-521123567
-654513013
-712508424

-552813282
-439989786
-347114808
-269718425
•205220966

-166319077
-134673835
-108945305
 -88041668
 -71068962

 -56924882
 -45138016
 -35315518
 -27130011
 -20308678

 -14624171
  -9887028
  -5939365
  -2649608
     91886
                               B-ft

-------
WESTERN LOW-SULFUR-—CASE 7

APPENDIX A — PRICE. RETURN AND OTHER INFORMATION

     THE PRICE IS   .722352 PER GALLON
     AVERAGE ANNUAL SALES:  553683020
     REQUIRED ACCURACY:       .0100 7.

     THE RETURN ON  INVESTMENT IS  20.0 PERCENT

     THE PAYOUT PERIOD IS  7.81 YEARS.
     THE TOTAL PRESENT VALUES OF ALL CASH OUTLAYS
     THIS SOLUTION REQUIRED  18 ITERATIONS
     THE FOLLOWING SALES WERE TRIED:
                                  712508424
ITERATION
 1.0000
 2.0000
   0000
   0000
   0000
   0000
   0000
 8.0000
 9. 0000
 10 .0000
 11.0000
 12.0000
 13.0000
 14.0000
 15.0000
 16.0000
 17.0000
 IB.0000
PRICE /
 .8675
 .8176
 .7848
 .7631
 .7490
 .7397
 .7336
 .7297
 .7271
 .7254
 .7243
 .7236
 .7231
 .7228
 .7226
 .7225
 .7224
 .7224
GALLON
          PROJECT LIFE FRACTIONAL EXPENSE SUMMARY
 EXPENSE  CATEGORY 	

 COAL.
 WATER.
 CHEMICALS.
 UTILITIES
 OPERATING  LABOR

 MAINTENANCE
 INSURANCE  PLUS LOCAL TAXES
 CORP.  LICENSE.
 STATE  TAX
 FEDERAL.  TAX

 SULFUR.
 CARBON DIOXIDE.
             -PERCENT OF TOTAL EXPENSES *

                              19.492
                               3.970
                               2.381
                                . 000
                               3.943

                              10.497
                               3.234
                                . 016
                                .000
                              56.467
           (CREDIT)
           (CREDIT)
                        .428
                      15.080
  *  EXPENSES  INCLUDE OPERATING EXPENSES  (NO CREDITS),PLUS
  STATE  AND FEDERAL TAXES.
                                  B-5

-------
WESTERN LOW-SULFUR	CASE 7

APPENDIX B--OPERATING COST DETAIL, PAGE i
YR. COAL
    UNIT COST
          COAL
          ANNUAL CONS,
               COAL
               COST
                     PERCENT OF
                     EXPENSES *
 i
 2
 3
 4
 5

 6
 7
 8
 9
10

ii
12
13
14
15

16
17
18
19
20

21
22
23
24
25
  .00
  .00
  .OD
  .00
  . 00

15. 00
15.00
15.00
15.00
15.00

15.00
15.00
15.00
15.00
15.00

15. 00
15.00
15.00
15.00
15.00

15.00
15.00
15.00
15.00
15.00
      0
      0
      0
      0
      0

4259900
4259900
4259900
4259900
4259900

4259900
4259900
4259900
4259900
4259900

4259900
4259900
4259900
4259900
4259900

4259900
4259900
4259900
4259900
4259900
        .00
        . 00
        .00
        .00
        .00

63898500.00
63898500.00
63898500.00
63898500.00
63898500.00

63898500.00
63898500.00
63898500.00
63898500.00
63898500.00

63898500.00
63898500.00
63898500.00
63898500.00
63898500.00

63898500.00
63898500.00
63898500.00
63898500.00
63898500.00
  .000
  .000
  .000
  .000
  .000

30.776
23.338
22.962
22.962
22.963

17.402
17.660
17.924
18.198
18.480

18.480
18.480
18.480
18.480
18.480

18.480
18.481
18.481
18.481
18.481
                               B-6

-------
WESTERN LOU-SULFUR	CASE 7
APPENDIX B—OPERATING COST DETAIL, PAGE 2
YR.  UATER
    UNIT COST
         WATER
         ANNUAL CONS.
UATER
COST
PERCENT OF
EXPENSES *
 i
 2
 3
 4
 5

 6
 7
 8
 9
10

ii
12
13
14
15

16
17
18
19
20

21
22
23
24
25
 .00
 .00
 .00
 .00
 .00

i. 16
1.16
1.16
1.16
1.16

i . 16
1 .16
1.16
1.16
1.16

1. 16
1.16
1.16
1.16
1.16

i . 16
i .16
1.16
1 .16
1.16
0
0
0
0
0
11266600
11266600
11266600
11266600
11266600
11266600
11266600
11266600
11266600
11266600
11266600
11266600
11266600
11266600
11266600
11266600
11266600
11266600
11266600
11266600
,




13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
13012923.
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
                      .000
                      . 000
                      .000
                      . 000
                      .000

                     6.267
                     4.753
                     4.676
                     4.676
                     4.676
                     3.544
                     3.596
                     3.650
                     3.706
                     3.763
                     3.763
                     3.763
                     3.763
                     3.763
                     3.764
                     3.764
                     3.764
                       .764
                       764
 3
 3.
                     3.764
                              B-7

-------
WESTERN LOU-SULFUR	CASE 7
APPENDIX B—OPERATING COST DETAIL, PAGE 3
YR .  CHEMICALS
    UNIT COST
CHEMICALS
ANNUAL CONS.
CHEMICALS
COST
PERCENT OF
EXPENSES *
i
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25





7805000
7805000
7805000
7805000
7805000
7805000
7805000
7805000
7805000
7805000
7805000
7805000
7805000
7805000
7805000
7805000
7805000
7805000
7805000
7805000
.00
.00
.00
.00
.00
.00
.00
.00
.00
. 00
. 00
. 00
. 00
. 00
. 00
. 00
.00
. 00
. 00
. 00
. 00
.00
.00
. 00
. 00
                               0
                               0
                               0
                               0
                               0

                               1
                               i
                               1
                               1
                               i

                               1
                               i
                               1
                               i
                               i

                               1
                               1
                               1
                               i
                               1

                               1
                               1
                               i
                               1
                               i
                           .00
                           .00
                           .00
                           . 00
                           .00

                    7805000.00
                    7805000.00
                    7805000.00
                    7805000.00
                    7805000.00

                    7805000.00
                    7805000.00
                    7805000.00
                    7805000.00
                    7805000.00

                    7805000.00
                    7805000.00
                    7805000.00
                    7805000.00
                    7805000.00

                    7805000.00
                    7805000.00
                    7805000.00
                    7805000.00
                    7805000.00
                      .000
                      . 000
                      .000
                      .000
                      .000

                     3.759
                     2.851
                     2.805
                     2.805
                     2.805

                     2.126
                     2.157
                     2.189
                     2.223
                     2.257

                     2.257
                     2.257
                     2.257
                     2.257
                     2.257

                     2.257
                     2.257
                     2.257
                     2.257
                     2 257
                                 B-8

-------
WESTERN LOW-SULFUR	CASE 7
APPENDIX B--OPERATING COST DETAIL, PAGE 4
YR.  UTILITIES
    COST
UTILITIES %
OF EXPENSES *
LABOR
COST
LABOR 7.
OF EXPENSES *
i
2
3
4
5
6
7
8
9
10
ii
12
13
14
15
16
17
18
19
20
21
22
23
24
25
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
(IN
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
PLANT)
                         0.000
                         0. 000
                         0 .000
                         0.000
                         0.000

                         0 . 000
                         0 . 000
                         0. 000
                         0.000
                         0.000

                         0 . 000
                         0.000
                         0.000
                         0.000
                         0.000

                         0.000
                         0. 000
                         0.000
                         0 .000
                         0. 000

                         0 .000
                         0. 000
                         0 . 000
                         0 .000
                         0.000
                             0
                             0
                             0
                             0
                             0

                      12927000
                      12927000
                      12927000
                      12927000
                      12927000

                      12927000
                      12927000
                      12927000
                      12927000
                      12927000

                      12927000
                      12927000
                      12927000
                      12927000
                      12927000

                      12927000
                      12927000
                      12927000
                      12927000
                      12927000
                        .000
                        .000
                        .000
                        .000
                        .000

                       6.226
                       4.721
                       4.645
                       4.645
                       4.645

                       3.521
                       3.573
                       3.626
                       3.682
                       3.739

                       3.739
                       3.739
                       3.739
                       3.739
                       3.739

                       3.739
                       3.739
                       3.739
                       3.739
                       3.739
                                 B-9

-------
WESTERN LOW-SULFUR	CASE 7
APPENDIX B—OPERATING COST DETAIL, PAGE 5
YR.  MAINTENANCE
    COST
MAINTENANCE %
OF EXPENSES *
INSURANCE
& LOCAL TAX
INS & LCL TAX X
OF EXPENSES *
1
2
3
4
5
6
7
8
9
10
it
12
13
14
15
16
17
18
19
20
21
22
23
24
25





34410000
34410000
34410000
34410000
34410000
34410000
34410000
34410000
34410000
34410000
34410000
34410000
34410000
34410000
34410000
34410000
34410000
34410000
34410000
34410000
.00
. 00
.00
. 00
.00
.00
.00
. 00
.00
. 00
.00
.00
.00
. 00
.00
.00
.00
.00
.00
. 00
.00
. 00
.00
. 00
.00
                                .000
                                .000
                                .000
                                . 000
                                .000

                              16.573
                              12.568
                              12.365
                              12.365
                              12.366
                               9.371
                               9.510
                               9.652
                               9.800
                               9.951
                               9.952
                               9.952
                               9.952
                               9.952
                               9.952
                              .00
                              .00
                              .00
                              .00
                              .00

                      10603000.00
                      10603000.00
                      10603000.00
                      10603000.00
                      10603000.00

                      10603000.00
                      10603000 .00
                      10603000.00
                      10603000.00
                      10603000.00
9.952
9.952
9.952
9.952
9.952
10603000.00
10603000.00
10603000.00
10603000.00
10603000.00
                      10603000.00
                      10603000.00
                      10603000.00
                      10603000.00
                      10603000.00
                          .000
                          . 000
                          .000
                          .000
                          .000

                         5.107
                         3.873
                         3.810
                         3.810
                         3.810

                         2.888
                         2.930
                         2.974
                         3.020
                         3.066
                                                                 3
                                                                 3.
                                                                 3.
                                                                 3.
                                                                 3.
                                               066
                                               066
                                               066
                                               067
                                               067
                         3.067
                         3.067
                         3.067
                         3.067
                         3.067
                             B-10

-------
UESTERN LOU-SULFUR	CASE 7
APPENDIX B—OPERATING COST DETAIL, PAGE 6
YR .  CORP. LICENSE
    COST
          CORP. LICENSE
          '/. OF EXPENSES *
 i
 2
 3
 4
 5

 6
 7
 8
 9
10

11
12
13
14
15

16
17
18
19
20

21
22
23
24
     . 00
     .00
     .00
     .00
     .00

99060.00
94107.00
89154.00
84201.00
79248.00

74295.00
69342.00
64389.00
59436.00
54483.00

49530.00
44577.00
39624.00
34671.00
29718.00

24765.00
19812.00
14859.00
 9906.00
 4953.00
000
000
000
000
000

048
034
032
030
028

020
019
018
017
016

014
013
Oil
010
009

007
006
004
003
001
                                B-ll

-------
WESTERN LOU-SULFUR—CASE 7
APPENDIX  B--OPERATING  COST  DETAIL,  PAGE  7
YR. SULFUR
    UNIT  PRICE
          SULFUR
          ANNUAL SALES
SULFUR
CREDIT
PERCENT OF
EXPENSES *
1
2
3
4
5
6
7
8
9
10
11.
12
13
14
15
16
17
18
19
20





75.
75.
75.
75.
75.
75.
75.
75.
75.
75.
75.
75.
75.
75.
75.
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
00
21
22
23
24
75.00
75.00
75.00
75.00
75.00
                                0
                                0
                                0
                                0
                                0
                                      .00
                                      . 00
                                      .00
                                      .00
                                      .00
18686
18686
18686
18686
18686
18686
18686
18686
18686
18686
18686
18686
18686
18686
18686
18686
18686
18686
18686
18686
1401450
1401450
1401450
1401450
1401450
1401450
1401450
1401450
1401450
1401450
1401450
1401450
1401450
1401450
1401450
1401450
1401450
1401450
1401450
1401450
.00
.00
.00
.00
.00
.00
. 00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
                      .000
                      . 000
                      .000
                      . 000
                      .000

                      .675
                      .512
                      .504
                      .504
                      .504

                       382
                      .387
                      .393
                      .399
                      .405

                      .405
                      .405
                      .405
                      .405
                      .405

                      .405
                      .405
                      .405
                      .405
                      405
                                B-12

-------
WESTERN LOU-SULFUR	CASE 7
APPENDIX B—OPERATING COST DETAIL, PAGE 8
YR.  CARBON DIOXIDE  CARBON DIOXIDE
    UNIT PRICE      ANNUAL SALES
 CARBON DIOXIDE
 CREDIT
            PERCENT OF
            EXPENSES *
1
2
3
4
5
6
7
8
9
10
ii
12
13
14
15
16
17
18
19
20
21
22
23
24
25





30
30.
30
30
30
30.
30
30
30
30
30
30.
30
30.
30
30.
30
30 ,
30
30
.00
. 00
00
.00
00
. 00
00
. 00
00
.00
00
.00
. 00
.00
.00
.00
00
.00
00
.00
00
.00
.00
.00
.00
                               0
                               0
                               0
                               0
                               0

                         2908000
                         2908000
                         2908000
                         2908000
                         2908000

                         2520000
                         2132000
                         1745000
                         1357000
                          969300

                          969300
                          969300
                          969300
                          969300
                          969300

                          969300
                          969300
                          969300
                          969300
                          969300
        .00
        . 00
        .00
        .00
        .00

87240000.00
87240000.00
87240000.00
87240000.00
87240000.00

75600000.00
63960000.00
5235aOOO.00
40710000.00
29079000.00

29079000.00
29079000.00
29079000.00
29079000.00
29079000.00
29079000
29079000
29079000
29079000
00
00
00
00
29079000.00
  .000
  .000
  .000
  . 000
  .000

42.018
31.864
31.350
31.350
31.351

20.589
17.677
14.685
11.594
 8.410

 8.410
 8.410
 8.410
 8.410
 8.410

 8.410
 8.410
 8.410
 8.410
 8.410
* EXPENSES INCLUDE OPERATING EXPENSES (NO CREDITS), PLUS
 STATE AND FEDERAL TAXES
                                B-13

-------
WESTERN LOU-SULFUR	CASE 7

APPENDIX C—TAXES AS A PERCENT OF TOTAL EXPENSES  *
YR. STATE TAX
    AMOUNT
     STATE  TAX
     '/. OF EXPENSES *
        FEDERAL  TAX
        AMOUNT
FEDERAL TAX
7. OF EXPENSES *
 1
 2
 3
 4
 5

 6
 7
 8
 9
10

ii
12
13
14
15

16
17
18
19
20

21
22
23
24
25
.00
.00
.00
. 00
.00

. 00
.00
. 00
.0.0
.00

.00
. 00
.00
. 00
.00

.00
.00
.00
 00
. 00

.00
.00
 00
.00
.00
.000               .00
.000               .00
. 000               .00
.000               .00
.000               .00

.000       64871422.82
 000      131041009.40
.000      135532515.18
 000      135534793.56
.000      135537071.94

.000      224458725.72
.000      219106604.10
.000      213768282.48
.000      208416160.86
.000      203068179.24

.000      203070457.62
 000      203072736.00
,000      203075014.38
 000      203077292.76
,000      203079571.14

 000      203081849.52
 000      203084127.90
 000      203086406.28
 000      203088684.66
 000      203090963.04
      .000
      . 000
      .000
      .000
      .000

    31.244
    47.862
    48.704
    48.705
    48.707

    61.129
    60.555
    59.965
    59.355
    58.728

    58.729
    58.730
    58.731
    58.732
    58.733

    58.734
    58.736
    58.737
    58.738
    58.739
* EXPENSES INCLUDE OPERATING EXPENSES  (NO CREDITS), PLUS
 STATE AND FEDERAL TAXES
                                  B-14

-------
                     APPENDIX C
Telephone Quotes for Costs of Water and Rail Transportation

-------
                                 APPENDIX C
           Telephone Quotes for Costs of Water and Rail Transportation

     Water
1.    For  shipment size at 80,000  barrels,  the cost is $2.00 per barrel from  the
     Houston, TX port  up the Mississippi and Illinois Rivers to Lamont, IL (20 miles
     south of Chicago). Due to  low bridge restriction, local tug boats to tow barges
     into Chicago proper must be subcontracted at an additional cost of $6,500.00 per
     shipment.

2.    For 70,000 barrels minimum 90,000 barrels maximum shipment, the cost is $16.00
     per ton or $2.21 per barrel from the Houston, TX port to Jo lie t, IL (30 miles SW
     of Chicago on the Illinois River). Subcontracting of local tug boats into Chicago
     proper is also necessary.

3.    For 10,000  barrel barge shipments,  the cost is $15.00 per ton or $2.07 per barrel
     from  the Houston, TX port up the Mississippi and Illinois Rivers into Chicago
     proper. No bridge restrictions.

*.    For  50,000  barrels minimum the cost is $2.15 per barrel from Galveston, TX
     around the east coast to New York City, New York.

5.    For  50,000 barrel minimum per  shipment the  cost  is  $2.46 per  barrel from
     Chicago to Buffalo, New York via  the Great Lakes.  Can also move up  the St.
     Lawrence River around  the Northeast coast  into  New York City at a cost of
     $8.10 per barrel.

     Costs for loading and unloading of the methanol were not addressed in any of the
     above estimates.

     Rail
     The  feasibility of  moving methanol by unit train - a series of specially designed
     and  built railroad cars  interconnected  to  form a single unit for  loading  and
     unloading - was investigated.  It appears that some of the  railroad companies
     that were contacted can provide this service at a lower cost than the standard
                                       C-2

-------
     individual tanker car.  However,  in order to formulate a price quote, amount,
     duration and frequency of shipments must be known. Therefore, the price quotes
     that were obtained are based on the standard individual tanker cars ranging from
     52,800 to 19,000 Ib capacity.  The capacity size of the cars  vary depending on
     availability,  weight restrictions, etc.   The larger the capacity size,  the lower
     than the cost. Rail prices are usually stated in dollars per hundred pounds.

The following are price quotes for rail transportation of methanol from locations near
the five regions locations to Chicago, Atlanta, and New York City.

1.   From Wheeling, W. VA  to Chicago, IL, 180,000 Ib capacity car at $2.04 per 100
     wt or $5.65 per barrel.

     From Wheeling  W. VA to Atlanta, GA: 190,000 Ib capacity car at $2.16 per 100
     wt or $5.98 per barrel.

     From Wheeling W. VA to New York City, NY 180,000 Ib capacity car at $2.36 per
     100 wt or $6.90 per barrel.

2.   From Palastine, TX to Chicago, IL; 180,000 Ib capacity car at $1.67 per 100 wt
     or $4.62 per barrel.

     From Palastine, TX to Atlanta, GA; 180,000 Ib capacity car at $3.44 per 100 wt
     or $9.52 per barrel.

     From Palestine, TX to New York  City, NY; 130,000 Ib capacity car at $2.44 per
     100 wt or $6.75  per barrel.

3.   From St. Louis, MO to  Chicago, IL; 130,000 Ib capacity car at $1.80 per 100 wt
     or $4.98 per barrel.

     From St. Louis, MO to Atlanta, GA; 130,000 Ib capacity car at $2.83 per 100 wt
     or $7.83 per barrel.

     From St. Louis, MO to  New York City, NY  64,000 Ib capacity car at $5.04 per
     100 wt or $13.96 per barrel.
                                         C-3

-------
4.    From BeuJah, ND to Chicago, IL; 52,800 lb capacity car at $5.33 per 100 wt or
     $14,81 Per barrel.

     From Beulah, ND to Atlanta, GA; 52,800 lb capacity car at $6.36 per 100 wt or
     $17.67 per barrel.

     From Beulah, ND to New York City, NY; 52,800 capacity car at $7.40 per 100 wt
     or $20.56 per barrel.

     From Gillette, WY  to Chicago, IL; 52,800 lb capacity car at $5.99 per 100 wt or
     $16.64 per barrel.

     From Gillette, WY  to Atlanta, GA; 52,800 lb capacity car at $6.52 per 100 wt or
     $18.12 per barrel.

     From Gillette, WY  to New York City, NY; 52,800 capacity car at $8.42 per 100
     wt or $23.40 per barrel.

5.    From Palestine, TX to  Houston and Galveston,  TX for further movement via
     waterway; 52,800 lb capacity car at $1.46 per 100 wt or $4.06 per barrel.
                                       C-4

-------
          APPENDIX D
Report on Pipeline Economic Factors

-------
Williams Brothers
  Engineering Company

 Resource Sciences Park
 MOO Souih Yale Avenue
 rulu, Oklahoma 74136
 Phone: (918) 496-5020
 Tele« 497493 WBEC TUl
 facvmile (918) 49«-50J4
        September 6,  1984
        Southwest Research Institute
        Post Office Drawer 28510
        6220 Culebra Road
        San Antonio, Texas  78284

        Attention:  Mr. David S. Moulton

        Subject:   Methanol Pipeline Transportation

        Dear Mr.  Moulton:

        In response to  the  Statement of  Work issued  by Southwest
        Research  Institute  dated  July 24, 1984,  Williams  Brothers
        Engineering Company  has prepared  preliminary design and cost
        data for potential pipeline systems transporting methanol from
        the North-Central  and  South-Central regions of the  United
        States to New  York City.   Data was developed for two  methanol
        pipeline systems:  one to  transport 400,000 barrels  per day
        from sources in Wyoming and North  Dakota to  markets  in Chicago,
        Illinois and New York City;  the  second to  transport  300,000
        barrels per day  from a source in  Texas to markets in  Atlanta,
        Georgia and New York City.  This data will be used by  Southwest
        Research  to calculate  pipeline  transportation  costs  for
        comparison to other potential modes of methanol transportation.

        It must be emphasized that much of the data  presented  herein  is
        definitely  conceptual  in nature.   Attempts  at optimizing the
        pipeline design, a normal  part of the pipeline transportation
        cost analysis  process, have been minimal  due  to the time
        constraints placed on  the  assignment.   The data presented does
        constitute a reasonable set of pipeline system design and cost
        characteristics which should be suitable for your purposes at
        this time.

        Routes and Capacities

        For the  northern pipeline  system,  origin points in Campbell
        County,  Wyoming  and  Mercer County, North Dakota were specified
        by the Statement of Work.   Brule County,  South Dakota  was
        selected  as a convenient  junction location for the  origin
        pipeline segments, being  approximately 320 miles from Campbell
                                       D-2

-------
Williams Brothers
       Southwest Research Institute
       Mr. David S. Moulton
       September 6, 1984
       Page 2

       County  and  280 miles from Mercer  County.   From the junction
       point,  the  selected route proceeds  across  northern Iowa and
       Illinois to  Chicago,  then continuing across northern  Indiana
       and Ohio, central  Pennsylvania,  and northern New Jersey  into
       New York City.   The  estimated distance  from the junction  point
       in South Dakota  to New  York  City is  1,300 miles.  The  selected
       route  is basically straight  line  from point to point, with
       slight  adjustment  to  minimize  major  river   crossings.
       Elevations  are estimated at  4,500  feet above  sea  level  in
       Campbell County,  2,000  feet  in  Mercer  County,  1,500 feet in
       Brule County,  600 feet at Chicago, and 0 feet at New York City.
       Design capacities for the pipeline segments are 200,000 barrels
       (8.4 million gallons)  per day for both  the Wyoming to South
       Dakota  and North Dakota to South Dakota segments and  400,000
       barrels (16.8  million gallons) per day  for  the  South Dakota  to
       New York segment.

       The origin point of  the southern pipeline  system is in Milam
       County, Texas,  from  where the selected route proceeds  across
       southern Louisiana and  Mississippi  and central  Alabama to
       Atlanta, then continuing across  western South Carolina  and
       North  Carolina,  central Virginia  and  Maryland, southeastern
       Pennsylvania,  and  north central  New  Jersey  into New York  City.
       The estimated length of  the  pipeline  is 1,520 miles.   The
       selected route is  basically  straight line  from its  origin to
       Baton  Rouge,  Louisiana, at which  point  it  joins an existing
       pipeline corridor  occupied by Colonial  Pipeline.   The route
       follows the  Colonial corridor into Pennsylvania and continues
       on a  straight line into New  York.  Elevations are estimated  at
       500  feet  above  sea  level in Milam County, 1,000  feet at
       Atlanta, and 0 feet  at  New York  City.   Design capacity for the
       pipeline is  300,000 barrels (12.6 million gallons) per day.

       Pipeline Design

       Applicable parts of the Department of Transportation regulation
       for transportation of hazardous  liguids  by  pipeline (Part 195,
       Title  49,   Code  of  Federal  Regulations) and   incorporated
       references,   plus principles  of fluid flow in pipe were  used  in
       preparing the  design, construction,  operations  and  maintenance
       data  presented  herein.   Pipeline  sizing  and  pumping
       requirements are based on transporting methanol with a specific
       gravity of 0.795 and a kinematic viscosity of 0.74 centistokes.
                                       D-:

-------
Williams Brothers
        Southwest Research  Institute
        Mr. David S. Moulton
        September 6, 1984
        Page 3

        Initial  pipe and  pump station  selection was based  on  the
        following factors:

        •    Internal design  pressure of 1,440 psig  and design  factor
            of  0.72

        •    Pipe material  to be API 5L Grade X-60 priced at $800 per
            ton

        •    Pipe wall thickness to be standard API wall thickness

        •    Pipe sized  to produce a friction head loss of between 25
            and 50  feet per  mile

        •    75  percent pumping unit  efficiency

        •    Pump station costs of $1,200 per installed horsepower

        Using  these factors,  various combinations of pipe  size and
        pumping  capacity for  each flowrate were evaluated on  an  initial
        investment  cost  basis,  with the lowest cost  combination being
        selected for development of  more detailed construction and
        operating data.  The  selected pipeline systems are described in
        Table 1.

        Capital  Requirements

        Capital  requirements  for constructing each of the four pipeline
        segments described in Table  1  have been estimated  and are
        displayed in Table  2.  All costs are based on estimated  current
        material prices  and labor rates and no escalation to year of
        construction has  been included.   Total costs, in millions  of
        1984 dollars, for the four pipeline segments  are:

            Wyoming to South Dakota            $106.3
            North Dakota to  South Dakota          95.7
            South Dakota to  New York            742.1
            Texas to New York                    721.2
                                      D-4

-------
Williams Brothers
 Inynrering Company
        Southwest  Research  Institute
        Mr. David  S. Moulton
        September  6, 1984
        Page 4

        Economic Factors

        The  Statement of Work issued by Southwest Research requested
        information  on typical or reasonable values  for  certain  items
        considered in evaluating  pipeline  economics.  The  following
        discussion addresses  these points:

        *    Project Life

            Although  the  useful  life  of  a pipeline  facility can
            sometimes extend to 50 years or longer, a project life of
            20  to 25 years  is typically assumed  when evaluating the
            potential revenues from a  proposed pipeline investment.
            This  is  due to  the risks  involved in  forecasting  the
            business  aspects of pipeline operation  such as growth or
            decline of product  supply or demand,  competition,  etc.

        *    Number  of Years  Required for Construction

            The  duration  of physical  construction activity  on a
            pipeline   system is  determined  by  the  number  of
            construction spreads  used,  their rate of progress, and the
            success of pre-construction planning.   It  is  estimated
            that  approximately  1.5 years would be required to  complete
            construction  on  the  methanol pipelines studied.    The
            duration  of  pre-construction activity is  much  more
            difficult to predict and  probably will be  considerably
            longer  than  that  for  construction.   Pre-construction
            activities would include engineering,  environmental  study,
            survey,   acquisition  of agreements  and  permits  from
            landowners  and  responsible governmental and  regulatory
            agencies,  materials procurement,  and contracting.   It is
            recommended  that a minimum of 3  years  be  allowed  for
            completion of  pre-construction activity.

        *    Approximate Percent of Construction Funds  Spent Each Year
            of Construction

            Assuming  a project duration of 5  years  from commencement
            of  pre-construction  to  completion of  construction  and
            demobilization,  reasonable estimates of  percentage of
            capital requirements  spent  per year would be:
                                       D-5

-------
Williams Brothers
        Southwest Research  Institute
        Mr. David S. Moulton
        September 6, 1984
        Page  5

                           Year            %

                              1              1
                              2              2
                              3             22
                              4             50
                              5             25

        *     Percent of  the Capital Outlay Which  is Depreciable

             One  hundred percent of the monies considered as initial
             investment  are depreciable.

        *     Amount and  Timing of Other Capital Outlays  during the
             Project Life

             Once the  pipeline is ready for service  it  must  be  filled
             with methanol  before normal operation begins.  The  cost  of
             line fill is  the product of the volume  required and its
             unit value to the owner.   For the two pipeline systems
             studied,  line  fill  volumes would be 5.14 million barrels
             for  the  northern system and 3.52 million barrels for the
             southern  system.  No  other capital  outlays should be
             required,  outside of  normal operating  and maintenance
             costs, unless  operating conditions change at some time in
             the  future.   Examples of  such  change would be  a
             significant increase in volume  to be transported,  the
             addition  of new  methanol  source  or delivery points, or
             investment  in  new technology advances which might decrease
             operating costs.  At this point,  estimating the amount of
             capital  expenditures for  these purposes  will  require
             additional  input  from Southwest Research.

        Operating Expenses

        An  estimate  of the annual operating and  maintenance  expenses
        for each of the  four pipeline segments described in Table 1 are
        summarized  in Table  3.   All  costs are  presented in 1984
        dollars.   These costs would  not  be  expected  to change
        substantially  during  the  project life  if adjustments  for
        inflation are  taken into account.

        Some  of  the   criteria used  in  estimating  operating and
        maintenance expenses were:
                                       D-6

-------
Williams Brothers
       Southwest Research  Institute
       Mr. David S. Moulton
       September 6, 1984
       Page 6

       •    Intermediate pump stations  are  unmanned.   Initial pump
            stations and delivery terminals  are manned continuously.

       •    Power  costs  are  based on an average charge of 6 cents per
            kwh  of power consumed by mainline pumping  units.   Power
            cost is the  largest single  item of expense  in operating
            the  pipeline systems and  is a significant factor to be
            considered when  optimizing pipeline design.

       •    Insurance  and ad valorem  taxes are  calculated at 1.5
            percent of initial  investment.

       Taxes and Depreciation

       In  response to  the Southwest Research request for  guidance on
       certain  tax and depreciation matters, we  offer  the following
       comments:

       *    State   income  tax   levies   are  usually  considered
            insignificant  at this stage of  a cost of transportation
            study  and  are  ignored.   Also, there  is little uniformity
            from state  to  state on methods  of calculating state tax.
            However,  if provision is  to be made for state income
            taxes,  2 percent of pretax  income would be  a reasonable
            annual  average to use.

       *    Southwest Research  Institute assumptions of a ten percent
            investment tax credit, five  year accelerated cost  recovery
            system for  depreciation  and  no energy investment tax
            credits appear to be appropriate.

       *    Regarding  areas   unique  to  pipelines which may affect
            project economics,  Southwest Research Institute should be
            aware  of the necessity of the  pipeline owner to obtain the
            right  of eminent domain.  This allows the owner to acquire
            pipeline right-of-way via condemnation proceedings  if a
            landowner  refuses   reasonable  compensation   for  his
            property.   Without this  privilege,  acquisition  of
            right-of-way is  likely to be much more costly  than we have
            estimated, if not virtually  impossible.
                                    D-7

-------
Wffiams Brothers
       Southwest Research  Institute
       Mr. David S. Moulton
       September 6, 1984
       Page 7

       We  appreciate  the  opportunity  you have  given  us  for
       participating  in this  project and  sincerely  hope that the
       information presented herein  fully satisfies your  requirements
       If  we  can be  of further service, please do not hesitate  to
       call.

       Very truly yours,

       WILLIAMS BROTHERS ENGINEERING COMPANY
       Michael M. Friese
       Project Manager

       MMF:slm/5803-001
       Attachments
                                       D-8

-------
      •^Williams Brothers
       f nginetnng Company
                                                                    5803
                                    TABLE  1

                      METHANOL PIPELINE  SYSTEM  FACILITIES
Line Length, Miles

Flow Rate, MBPD

Pipe Diameter and Wall
Thickness, Inches

No. of Pump Stations

Installed Brake
Horsepower per Station

No. Delivery Terminals
                            Wyoming
                               to
             North Dakota   South Dakota
                  to
                         South Dakota    South Dakota
    320

    200

18 x 0.312


      3

  7,000
    280

    200

18 x 0.312


      3

  7,000


      0
   to
New York

  1,300

    400

26 x 0.438


      9

 13,000
 Texas
   to
New York

  1,520

    300

22 x 0.375


     14

 10,000
                                      D-9
                                                                       5803-002

-------
5803
• ' rvY/VT|lll<||l|3 umiiicii 	
\AA/ tnginecring Company
TABLE 2
CAPITAL REQUIREMENTS FOR CONSTRUCTING
Wyoming North Dakota
to to
South Dakota South Dakota
ROW and Land 4.8 4.2
Line Pipe 39.9 34.9
Coating 2.1 1.8
Scraper Traps, Valves, 3.7 3.6
and Other Materials
Pipeline Construction 29.6 26.3
Pump Stations and 12.8 12.8
Terminals
Engineering, 8.3 7.5
Construction
Management and
Inspection
Subtotal 101.2 91.1
Contingency @ 5% 5.1 4.6
Total 106.3 95.7
Notes: (1) Costs are in millions of 1984 dollars.
(2) Costs for project financing, initial line
studies and permitting are not included.
D-10
PIPELINES
South Dakota Texas
to to
New York New York
27.3 35.8
323.5 271.5
12.3 12.1
18.3 21.4
179.5 187.8
87.7 101.7
58.2 56.6

706.8 686.9
35.3 34.3
742.1 721.2
fill, and environmental

   5803-002

-------
NoA/ tngioeering Company
TABLE 3
ANNUAL OPERATING AND MAINTENANCE
Wyoming North Dakota
to to
South Dakota South Dakota
Operations Payroll 0.36 0.34
Supervisory Payroll 0.20 0.19
Communications 0.04 0.04
Automotive 0.03 0.03
Power 6.65 7.09
Pipeline Maintenance 0.10 0.08
Station Maintenance 0.11 0.11
Contract Services 0.03 0.02
Insurance and 1.59 1.44
Ad Valorem Tax
Miscellaneous .05 .05
TOTAL 9.16 9.39
Note: Costs are in millions of 1984 dollars.
D-ll


COSTS
South Dakota
to
New York
1.45
0.61
0.17
0.09
40.78
0.39
0.59
0.10
11.13

2.77
58.08




Texas
to
New York
1.95
0.90
0.20
0.13
48.38
0.46
0.70
0.12
10.82

3.18
66.84


5803-002

-------
                                   TECHNICAL REPORT DATA
                            (Please read Instructions on the reverse before completing)
 1. REPORT NO.
  EPA 460/3-84-012
                              2.
                                                           3. RECIPIENT'S ACCESSION-NO.
 4. TITLE AND SUBTITLE

  Costs  to Convert Coal to Methanol
                                  5. REPORT DATE
                                    April 1986
                                  6. PERFORMING ORGANIZATION CODE
 7. AUTHOR(S)
  David  S.  Moulton and Norman R. Sefer
                                                           8. PERFORMING ORGANIZATION REPORT NO
9. PERFORMING ORGANIZATION NAME AND ADDRESS
  Southwest Research Institute
  6220  Culebra Road
  San Antonio,  Texas  78284
                                  10. PROGRAM ELEMENT NO.

                                    Work Assignment  9
                                  11. CONTRACT/GRANT NO.

                                    68-03-3162
 12. SPONSORING AGENCY NAME AND ADDRESS
  Environmental Protection Agency
  2565  Plymouth Road
  Ann Arbor,  MI  48105
                                  13. TYPE OF REPORT AND PERIOD COVERED
                                    Final  (8/15/83  - 9/30/84)
                                  14. SPONSORING AGENCY CODE
 15. SUPPLEMENTARY NOTES
 16. ABSTRACT

  This  report provides estimated  costs  of producing methanol  transportation fuel
  from  coal.   Estimates were made for mine-mouth plants in  five  different coal
  producing regions, and uniform  methods were used so the estimated sales prices could
  be  compared for market analysis.   In  addition to plant-gate prices,  delivered prices
  were  estimated for three major  market areas.  With presently available transportation
  the lowest  delivered prices were  for  methanol production  based in the southern
  lignite coal region.  If new methanol-compatible pipelines  were to be constructed,
  the lowest  delivered prices would be  for production based in the western
  subbituminous coal region.  In  the western subbituminous  region,  limited water
  resources would make extensive  planning and careful site  selection necessary, but
  they  would  not prevent the development of a coal-to-methanol industry.  By-product
  carbon dioxide sales for enhanced oil recovery could reduce the required plant-gate
  methanol price in some areas near oil fields amenable to  carbon dioxide injection
  techniques.  Contains a literature review with 50 references.
17.
                                KEY WORDS AND DOCUMENT ANALYSIS
                  DESCRIPTORS
                     b.IDENTIFIERS/OPEN ENDED TERMS  C.  COSATI Ffold/GrOUp
  Coal
  Bituminous Coal
  Subbituminous Coal
  Lignite
  Cost  Estimates
  Conversion
Manufacturing
Coal gasification
Carbinols
Desulfurization
Prices
Transportat ion
Coal rank
Methanol
 8. DISTRIBUTION STATEMENT

  Unlimited
                     19. SECURITY CLASS (ThisReport)
                      Unclassified	
                         217NO. OF PAGES
                             122
                                              20. SECURITY CLASS (Thtspagt)
                                               Unclassified
                                                                        22. PRICE
EPA Form 2220-1 (9-73)

-------