United States      Office of Air Quality        EPA-340/1-85-014a
              Environmental Protection  Planning and Standards       October 1984
              Agency         Washington, D.C. 20460
              Stationary Source Compliance Series
              Utility  FGD Survey
              October  1983-
              September 1984

              Volume 1:
              Categorical
              Summaries of
              FGD Systems        Property0f
                                      EPA Lfcrr..--,
                                     RTPNC 27, 11
EPA LIBRARY SERVICES RTP NC
TECHNICAL DOCUMENT COLLECTION

-------
                                 EPA-340/1-85-014a

           Utility FGD Survey
  October 1983 - September 1984

Volume 1: Categorical Summaries of
               FGD Systems
                M. T. Melia, R. S. McKibben,
                   and B. W. Pelsor
                 PEDCo Environmental, Inc.
                   11499 Chester Road
                  Cincinnati, Ohio 45246
                EPA Contract No. 68-02-3963
                 Work Assignment No. 46
               EPA Project Manager: John Busik
         EPA Work Assignment Manager: Sonya M. Stelmack
           U.S. ENVIRONMENTAL PROTECTION AGENCY
             Stationary Source Compliance Division
            Office of Air Quality Planning and Standards
                 Washington, D.C. 20460

                    October 1984

-------
                         ACKNOWLEDGMENT


     The EPA-SSCD Project Officer and authors of this report
appreciate the assistance provided by Norman Kaplan, the Project
Officer for the U.S. Environmental Protection Agency (Industrial
Environmental Research Laboratory, Research Triangle Park, North
Carolina)  for the Flue Gas Desulfurization Information System
(FGDIS), in updating and maintaining the data base and his sug-
gestions on the content and format of the survey report  (and
project summary) and on other project activities.
                           DISCLAIMER
     This report was prepared for the U.S. Environmental Protec-
tion Agency by PEI Associates, Inc., Cincinnati, Ohio, under Con-
tract No. 68-02-3963, Work Assignment No. 46.  The contents of
this report are reproduced herein as received from PEI Associates,
Inc.  The opinions, findings, and conclusions expressed are those
of the authors and not necessarily those of the U.S. Environmental
Protection Agency.  Mention of trade names or commercial products
is not intended to constitute endorsement or recommendation for
use.  Copies of this report are available from the National
Technical Information Services, 5285 Port Royal Road, Springfield,
Virginia 22161.
                               11

-------
                             NOTICE
     The data in this information transfer document are supplied
voluntarily by utility representatives, flue gas desulfurization
 (FGD) system suppliers and designers, regulatory agencies, and
others.  The accuracy or completeness of the information con-
tained herein is not warranted by the Stationary Source Control
Division of EPA or the designated contractor.  Portions of the
work upon which this publication is based were performed pursuant
to Contract Nos. RP982-32  (Electric Power Research Institute) and
68-02-3173  (Environmental Protection Agency).

     A project summary will be distributed to organizations and
individuals indicating a specific interest in the field of FGD
technology.  Interested parties can be added to the Project
Summary mailing list by contacting Carolyn Fowler at the Indus-
trial Environmental Research Laboratory (919/541-2915) or the
secretary of the Emission and Effluent Technology Branch of the
EPA  (919/541-2578) .  Copies of preceding issues of this report
through December 1981 can be purchased from the National Tech-
nical Information Service, Springfield, Virginia  22161,  (703)
487-4650.  Succeeding issues of this report can be purchased from
the Electric Power Research Institute Research Reports Center,
P.O. Box 50490, Palo Alto, California 94303, (415) 965-4081.

     This report summarizes the FGD system design and performance
data contained in a computerized data base known as the Flue Gas
Desulfurization Information System  (FGDIS).  Access to the FGDIS
is available through the National Technical Information Service
 (NTIS) for a nonprofit user's fee.  Users also have access to
additional design and performance data stored within the data
base that cannot conveniently be printed in this report.  Direct
access to the data base affords analyses of the data  (e.g.,
averages, maxima, minima, and standard deviations of various
parameters), the use of simple mathematical functions, the capa-
bility of virtually unlimited data cross-referencing, and data
tabulation to fit the user's individual information needs.  An
FGDIS users manual is available from NTIS (NTIS No. PB 83 146
209) .

     Requests for further information concerning the FGDIS and
periodic FGDIS training seminars should be directed to Michael
Melia or Skip Jones, PEI Associates, Inc. (513/782-4700).  In-
formation concerning access to the FGDIS can be obtained  from
Walter Finch, NTIS, 5285 Port Royal Road, Springfield, Virginia
22161 (703/487-4808).

                               iii

-------
                       USE OF THIS REPORT


     This report is the first fully compiled edition since the
July 1982-March 1983 issue released in April 1984, which contains
more complete design and performance data since the FGS system
startup dates.  This report supersedes all previous issues.
Volume 1 includes several categorical summaries of key data and
the appendix sections.  Volume 2, Parts 1 and 2 contain all
available design and performance data for operational FGD systems
(Section 13).

     The Executive Summary contains the number and capacity of
FGD systems as of the end of December 1984, future (December 1993)
projections of controlled and uncontrolled generating capacity,
and unit-by-unit summaries of status changes (e.g., contract
awarded, under construction, or operational) and performance and
status highlights for the period.

     Appendix sections incl-ude definitions, a table of unit
notation and simplified process flow diagrams,  as well as data
on terminated FGD systems, particle scrubbers and Japanese FGD
systems.
                               IV

-------
                            ABSTRACT
     The Utility FGD Survey report, which is generated by a
computerized data base system, represents a survey of operational
and planned domestic utility flue gas desulfurization (FGD)
systems.  The three volume set summarizes information contributed
by the utility industry, system and equipment suppliers, system
designers, research organizations, and regulatory agencies.   The
data cover system design, fuel characteristics, operating
history, and actual system performance.  Also included is a
unit-by-unit discussion of problems and solutions associated with
the boilers, scrubbers, and FGD systems.

     The development status (operational, under construction, or
in the planning stages), system supplier, process, waste disposal
practice, and regulatory class are tabulated alphabetically by
utility company.  Simplified process flow diagrams of FGD systems,
definitions, and a glossary of terms are attached to the report.
Current data for domestic FGD systems show 124 systems in opera-
tion, 25 systems under construction, and 68 systems planned.  The
current FGD-controlled capacity in the United States is 47,255 MW.
                                v

-------
                            CONTENTS
Acknowledgment
Notice
Use of This Report
Abstract
Tables and Figures
Executive Summary
Highlights
Section 1

Section 2

Section 3

Section 4

Section 5

Section 6


Section 7


Section 8

Section 9

Section 10

Section 11

Section 12


Appendix A

Appendix B

Appendix C

(Continued)
Summary List of FGD Systems

Status of FGD Systems

Summary of FGD Systems by Company

Summary of FGD Systems by System Supplier

Summary of FGD Systems by Process

Summary of Operational FGD Systems by
 Process and Unit

Summary of End-Product Disposal
 Practices for Operational FGD Systems

Summary of FGD Systems in Operation

Summary of FGD Systems Under Construction

Summary of Contract-Awarded FGD Systems

Summary of Planned FGD Systems

Total FGD Units and Capacity (MW)
 Installed, by Year

Definitions

Table of Unit Notation

FGD Process Flow Diagram
                               VI
                                                            Page
  11
 iii
  iv
   v
viii
  ix
  xx

 1-1

 2-1

 3-1

 4-1

 5-1


 6-1


 7-1

 8-1

 9-1

10-1

11-1

12-1


 A-l

 B-l

 C-l

-------
                      APPENDIX (continued)
Appendix D     Design and Performance Data for Operational
                Particle Scrubber
                  Commonwealth Edison
                    Will County 1                           D~l
                  Minnesota Power & Light
                    Clay Boswell 3                          D-27
                    Syl Laskin 1                            D-30
                    Syl Laskin 2                            D-34
                  Montana-Dakota Utilities
                    Lewis & Clark 1                         D-38
                  Pacific Power & Light
                    Dave Johnston 4                         D-42
                  Potomac Electric Power
                    Dickerson 1                             D-45
                    Dickerson 2                             D-48
                    Dickerson 3                             D-51
                  Public Service of Colorado
                    Arapahoe 4                              D-58
                    Cherokee 1                              D-62
                    Cherokee 4                              D-65
                    Valmont 5                               D-68
                  Southwestern Public Service
                    Harrington 1                            D-75

Appendix E     Design and Performance Data for Operational
                Foreign FGD Systems                         E-l

Appendix F     Design and Performance Data for Terminated
                FGD Systems                                 F-l
                               vn

-------
                             TABLES
Number                                                      Page

  1       Number and Total Capacity of FGD Systems            ix

  2       Summary of Status Changes, October 1983 -
            September 1984                                    xi

  3       Power Generation Sources:  Present and Future     xiii

  4       Power Production by Source                        xiii

  5       FGD-Controlled Generating Capacity:  Present
            and Future                                       xvi

  6       Summary of FGD Systems by Process                 xvii

  7       Categorical Results of the Reported and Adjusted
            Capital and Annual Costs for Operational FGD
            Systems                                        xviii
                            FIGURES
Number

  1

  2
Computerized Data Base Structure Diagram

History of Utility Projections for Operational,
  Under Construction, and Planned FGD Capacity
  December 1970 through September 1984

Actual and Projected Coal-Fired Generating
  Capacity and FGD Capacity, 1984
Page

   x



 xiv


  XV
                               Vlll

-------
                         EXECUTIVE SUMMARY
     This  report is prepared  by PEI Associates,  Inc.,  under
contract to  the Stationary Source Control Division  of  the U.S.
Environmental Protection Agency in conjunction with the Indus-
trial Environmental Research  Laboratory/Research Triangle Park of
the U.S. Environmental Protection Agency.  It is generated by a
computerized data base system,  the structure of which  is il-
lustrated  in Figure 1.

     Table 1 summarizes the status of flue gas desulfurization
(FGD) systems in the United States as of the end of September
1984.  Table 2 lists the units  on which the status  has changed
during the October 1983-September 1984 period.  The units includ-
ed in the  figures presented in  Table 1 are identified  in Table 3.

              TABLE 1.  NUMBER AND TOTAL CAPACITY OF FGD SYSTEMS
Status
Operational
Under construction
Planned:
Contract awarded
Letter of intent
Requesting/evaluating bids
Considering only FGD
systems for S02 control
TOTAL
No. of
units
124
25
15
3
4
46
217
Total
controlled
capacity, MW
50,870
14,656
9,248
2,500
1,926
27,512
106,712
Equivalent
scrubbed
capacity, MW
47,255
14,335
9,190
2,500
1,926
26,869
102,075
 Summation of the gross unit  capacities (MW)  brought  into compliance by the
 use of FGD systems,  regardless of the percentage of  the flue gas scrubbed
 by the FGD system(s).

 Summation of the effective scrubbed  flue gas capacities in equivalent MW,
 based on the percentage of flue gas  scrubbed by the  FGD system(s).
                                 IX

-------
                                                      FLUE GAS DESULFUR1ZATION INFORMATION SVS1EM
X
                                    Figure 1.  Computerized  data base  structure  diagram.

-------
TABLE 2.  SUMMARY OF FGD SYSTEM STATUS  CHANGES, OCTOBER 1983-SEPTEMBER 1984
FGD status report
September 30. 1983
Arizona Public Service
Choi la 5
Big Rivers Electric
D.B. Wilson 1
Boston Edison
New Boston 1
New Boston 2
Central Illinois light
Duck Creek 2
Cincinnati Gas & Electric
Zinroer 1
Colorado Ute Electric
Craig 3
Deseret Generating I Transmission
Bonanza 1
General Public Utilities
Coal 1
Jersey Central Power ft Light
N/D 1
Los Angeles Dept. of Hater ft Power
Intel-mountain 2
Lower Colorado River Authority
Fayette Power Project 3
Fayette Power Project 4
Middle South Utilities
Arkansas Lignite 5
Arkansas Lignite 6
Unassigned 1
Unassigned Z
Montana Power
Colstrip 3
Operational
No.
116

+ 1



+ 1
*1





+ 1
MWa .
43,206°

440



447
410





778
Under
construction
No.
?6

-1



-1
-1


+ 1
+1

-1
HW »
14,609°

440



447
410


820
451

778
Contract
awarded
No.
21









-1
-1


MM8
12,635









820
451


letter
of intent
No.
7











-1
-1
-1
-1

«w8
6,060











890
890
890
890

Requesting/
eval. bids
No.
3


+1
+ 1




-1





MW\
l,840b


388
388




690





Considering
FGD
No.
41
»1


-]
+ 1


+ 1
-1

+ 1


rw «
23,549b
126


450
1,386


690
625

451


Total
No.
214
+1

+ 1
+ 1
-1
+ 1



-1

+ 1
-1
-1
-1
-1

MW*
101 ,899°
126

388
388
450
1,386



625

451
890
890
890
890


-------
             TABLE  2  (continued)
x
(-••
K-
FGD status report
September 30, 1983
New York State Electricity i Gas
Somerset
Orlando Utilities Commission
C. H. Stanton 1
Pacific Power & Light
Jim Bridger 2
Wyodak 1
Platte River Power Authority
Rawhide 1
Public Service Company of Colorado
Pawnee 2
San Antonio Public Service
N/D 3
N/D 1
Seminole Electric
Seminole 2
South Carolina Public Service
Cross 2
Southern Indiana Gas * Electric
A.B. Brown 2
Southwestern Electric Power
Oolet Hills 1
Southwestern Public Service
South Plains 1
West Texas Utilities
Oklaunlon 1
Total
Operational
No.
1!6
+ 1


+ 1


+ 1
+ 1




124
MWS .
43.2066
625


279


620
450




47,255
Under
construction
No.
26
-1
+ 1
+ 1
-1


-1
-1
+1
+ 1

+ 1
25
MW8 .
14,609
625
465
550
279


620
450
265
720

504
14,335
Contract
awarded
No.
21

-1
-1
+ 1





-1
-1

-1
15
MWa
1?,635

465
550
330





265
720

504
9,190
Letter
of intent
No.
7












3
MW3
6,060












2,500
Requesting/
eval. bids
No.
3












4
MWa .
1 ,840b












1,926
Considering
FGO
No.
41


-1

+ 1
+1
+ 1




+ 1

46
MWa ,
23, Wb


330

500
500
500




572

26,869
Total
No.
214




+ 1
+ 1
+ 1




+ 1

217
MWa .
101,899°




500
500
500




572

102,075
            8  Equivalent  scrubbed capacity.

            b  This value  was modified slightly to reflect a MW correction.

-------
     Figure 2 presents a historic breakdown of utility  status
reports for operational, under-construction, and planned  FGD
capacity.  The operating FGD capacity has grown significantly
each year since 1972.  Since 1977 the capacity under construction
has been fairly stable.  The planned capacity reported  by the
utilities has increased each year in the past until 1980,  when  it
reached its peak, and has dropped sharply since that time.

     Figure 3 presents a comparison of actual coal-fired  generat-
ing capacity and FGD capacity  from 1975 through 1984 and  projec-
tions thereafter through 1992.  Although the retirement of older
units is taken into account in these plots, such retirements
affect only the overall coal-fired capacity rate because  FGD-
controlled capacity represents primarily new power generating
capacity.  This accounts for the slightly greater slope of the
lower line, which depicts FGD-controlled capacity.

     Current projections estimate the total power-generating ca-
pacity of the U.S. electric utility industry will be 791  GW by
the end of 1992.6   (This value reflects the loss resulting from
the retirement of older units, which is considered to be  approx-
imately 3.24 GW by the end of  1992.7)  Approximately 345  GW, or
44 percent of the 1992 total,  is estimated to be produced by
coal-fired units.  Table 3 presents a distribution of present
(December 1983) and future  (December 1992) power generation
sources.
          TABLE 3.  POWER GENERATION SOURCES:  PRESENT AND FUTURE
                                                        ,6,7

Coal
December 1983 43%
December 1992 44%

Nuclear
11%
16%

Oil
20%
17%

Hydro
12%
11%

Gas
13%
11%

Other
1%
1%
Total generating
capacity, GW
671
791
     It is interesting to note that the breakdown  for  the  actual
power produced by these sources during the past year  (Table  4)
differs appreciably, especially for coal- and  oil-fired  sources,
from the power generating capacity shown in Table  3.   This is  due
to the effect of the changing economy on the operation of  various
types of powerplants.

                  TABLE 4.  POWER PRODUCTION BY SOURCE8
Coal
January-December 1983 55%
Nuclear
13%
Oil
6%
Hydro
14%
Gas
12%
Other
0
Total energy
generated, GWh
2,308,746
                               Xlll

-------
no
100
90
i 80
o
0
170
t—

-------
   450
   400  -
   350  -
   300  -
   250  -
i  200
   150
   100  «
    50
               i    i   i    i   i    i    i
                   COAL-FIRED CAPACITY
    FGD-CONTROLLED CAPACITY
                  ACTUAL CAPACITY
    PROJECTED CAPACITY
              ;:*;&&^
       75  76
77  78  79  80 81  82  83  84  85  86  87
                       YEAR*
89  90 91  92
         YEAR-END TOTALS
       Figure 3.  Actual and projected coal-fired qeneratinq
                  capacity and FGD capacity, 1984.1~7
                                  xv

-------
     Based  on known commitments of utilities  to FGD (as presented
in Table  1)  and other coal-fired generating capacity expected  to
be required to incorporate  FGD (Figure 3), current and projected
percentages of electrical generating capacity controlled by  FGD
are shown in Table 5.
    TABLE 5.  FGD-CONTROLLED GENERATING CAPACITY:  PRESENT AND FUTURE
                                                             1,6

September 1984a
December 1992
Coal -fired generating capac-
ity controlled by FGD, %
17.2
31.0
Total generating capaci
controlled by FGD, %
ty
7.4
13.6
 The September 1984  FGD capacity figures are based on reports by utilities.
 The figures used for the total generating capacity and the December 1992
 coal-fired generating capacity are  based on December 1982 DOE projected
 figures.


     Table 6  shows both the current (September 1984)  and project-
ed (December  1999)  breakdown of  throwaway-product FGD  systems
versus  salable-product FGD systems as  a percentage of  the total
known commitments to FGD.

     Table 7  presents categorical  FGD  system cost data in common
1981 dollars.
                                 xvi

-------
                  TABLE  6.   SUMMARY  OF  FGD  SYSTEMS BY PROCESS
                           (percentage  of total MW)


Process
Throwaway-product process
Wet systems
Lime
Limestone
Lime/alkaline flyash
Limestone/alkaline flyash
Dual alkali
Sodium carbonate
NAD
Dry systems
Lime
Sodium carbonate
NAD
Dry injection
Trona/dry injection
Saleable-product process
Aqueous carbonate/
spray drying
Limestone
Magnesium oxide
Wellman Lord
Process undecided

TOTAL


Byproduct
















Elemental sulfur

Gypsum
Sulfuric acid
Sulfuric acid




September
1984


23.9
46.7
7.7
3.2
3.3
3.2
-

4.8
0.9
-

-


0.2
0.4
1.5
4.2
_

100.0

December
1999


13.2
43.1
4.3
1.5
2.2
3.1
1.8

6.2
0.4
2.2

0.5


0.1
1.4
0.7
1.9
17.4

100.0
December
1999
(Normalized)3


16.0
52.2
5.2
1.8
2.7
3.7
2.1

7.5
0.5
2.7

0.6

.
0.1
1.7
0.9
2.3
_

100.0
 The  effect of those  systems  listed  as  "Process  undecided"  is  removed.

3NA - Not available (These systems are  committed to  a  throwaway-product
 process; however,  the actual  process is  unknown at  this  time.)
                                   xvn

-------
                                  TABLE 7.   CATEGORICAL RESULTS OF THE REPORTED AND
                           ADJUSTED CAPITAL AND ANNUAL COSTS FOR OPERATIONAL FGD SYSTEMS

All
New
Retrofit
Saleable
Throwaway
Alkaline
flyash/llme
Alkaline flyash/
limestone
Dual alkali
line
Limestone
Sod 1 un carbonate
Hellman Lord
Reported
Capital
Range. $/kW
23.7-213.6
23.7-213.6
29.4-157.4
132.8-185.0
23.7-213.6
43.4-173.8
49.3- 49.3
47.2-174.8
29.4-213.6
23.7-170.4
42.9-100.8
132.8-18S.O
Average,
$/W
80.2
80.4
79.7
153.1
75.8
93.9
49.3
97.8
81.8
67.9
69.2
153.1
o
44.3
46.1
39.4
20.6
41.5
44.0
0.0
55.3
43.7
37.2
26.6
20.6
Annual
Range,
mllls/kUh
0.1-13.0
0.1- 5.5
0.5-13.0
13.0-13.0
0.1-11.3
0.4- 5.4
0.8- 0.8
1.3- 1.3
0.3-11.3
0.1- 7.8
0.2- 0.5
13.0-13.0
Average,
mflls/kWn
2.3
1.7
4.5
13.0
2.1
2.1
0.8
1.3
3.2
1.6
0.4
13.0
0
2.8
1.8
4.4
0.0
2.4
1.9
0.0
0.0
2.7
2.2
0.1
0.0
Adjusted
Capital
Range, $/kW
38.3-282.2
38.3-263.9
60.4-282.2
254.6-282.2
38.3-263.9
52.5-184.4
102.6-102.6
87.8-263.9
60.4-210.0
38.3-194.3
87.1-150.9
254.6-262.2
Average,
$/kW
118.8
110.8
139.3
271.6
110.9
122.8
102.6
146.7
116.5
98.9
110.9
271.6
0
58.1
48.4
73.8
12.1
47.6
51.4
0.0
82.9
44.2
44.0
26.4
12.1
Annual
Range,
mllH/kWh
1.6-20.8
1.6-14.6
4.3-20.8
16.7-20.8
1.6-17.6
3.0-14.1
5.4- 5.4
5.0-13.9
4.0-17.6
1.6-14.6
5.8- 7.4
16.7-20.8
Average,
mills/kWh
7.6
6.8
9.7
18.1
7.0
7.2
5.4
8.7
8.1
6.1
6.4
18.1
a
4.1
3.Z
5.3
1.9
3.4
3.8
0.0
3.6
3.6
3.1
0.7
1.9
X
<
K-
H-
H-

-------
             HIGHLIGHTS:  OCTOBER 1983-SEPTEMBER 1984


     The following paragraphs highlight FGD system developments
during the period of October 1983 through September 1984.

     Arizona Electric Power reported that the Apache 2 and 3
     limestone FGD systems demonstrated high dependabilities
     during the months of October 1983 through July 1984.   No
     major FGD-related problems were encountered.

     Arizona Public Service announced plans to construct a new
     unit, Cholla 5, in Joseph City, Arizona.  The 375-MW (gross)
     pulverized-coal-fired boiler (supplied by Combustion Engineer-
     ing) will have an FGD system for the control of S02 emissions.
     The unit is scheduled to start up in 1997.

     Atlantic City Electric announced that they have postponed
     indefinitely their plans to install Cumberland 1 in Milville,
     New Jersey, because power demand has not met projections.

     Basin Electric Power reported that the limestone FGD systems
     on Laramie River 1 and 2 achieved high dependabilities
     during most of the period.  Minor FGD-related problems
     encountered included maintenance on welds in the quencher
     section on Unit 2 and repairs to the absorber recycle and
     feed tank mixers on both units.

     Big Rivers Electric reported that initial operation of the
     FGD system on D. B. Wilson 1 in Centertown, Kentucky, began
     in September 1984.  This 440-MW  (gross) unit fires coal with
     an average sulfur content of 3.75 percent.  The emission
     control system consists of an ESP followed by an M. W.
     Kellogg wet-lime FGD system.

     New Boston 1 and 2 of Boston Edison in Boston, Massachusetts,
     are being converted from oil- to coal-fired units.  The
     388-MW (gross) Babcock and Wilcox units will fire  subbitumin-
     ous coal with an average sulfur content of 2.3 percent and
     heat content of 12,600 Btu/lb.  Bids are currently being
     requested/evaluated for a wet-limestone FGD system with
     salable gypsum byproduct recovery.  Particulate control will
     be provided by ESP's, and the flue gas will exit via a
     359-ft acid-brick-lined stack.  Forced oxidation will be
                               xix

-------
utilized for sludge treatment.  New Boston 1 and 2 are
scheduled to start up in October 1987 and June 1988 respec-
tively -

Cajun Electric Power announced that their plans to install
Oxbox 1  in De Soto Parish, Louisiana, have been postponed
indefinitely because power demand has not met projections.

Central Illinois Light reported that the Duck Creek 1 lime-
stone FGD system demonstrated high dependabilities during
the period of October 1983 through July 1984, except during
May, when the FGD system was down for general inspection and
maintenance.  The utility also announced that they had
cancelled plans for the construction of a second unit at the
Duck Creek Station in Canton, Illinois, because of a reduction
in projected power demand.

Central Illinois Public Service reported that the Newton 1
dual-alkali FGD system demonstrated high dependabilities
during the period of October 1983 through August 1984,
except for June, when the FGD system was down because of
repairs to the absorber tower lining.

Cincinnati Gas and Electric announced plans to convert the
Zimmer 1 nuclear facility in Moscow, Ohio, to coal.  The
retrofit 1386-MW (gross) coal-fired boiler will have an FGD
system for control of S02 emissions.  The unit is scheduled.
to start up in 1991.

Colorado Ute Electric indicated that initial operation of
the FGD system on Craig 3 in Craig, Colorado, commenced in
June 1984.  This 447-MW (gross) unit fires coal with an
average sulfur content of 0.45 percent.  Babcock and Wilcox
supplied this lime/spray drying process.  A fabric filter is
used for particulate removal.

Cooperative Power, not Buckeye Power as previously reported,
plans to construct a 750-MW  (gross) unit in Ohio.  The
facility has not yet been named, nor has a site been finalized.
This unit is expected to fire Ohio coal.  A wet-limestone
FGD system will control S0? emissions, and ESP's will control
particulate emissions.  Initial startup is tentatively
scheduled for 1994.

Deseret Generating and Transmission reported that initial
operation of the FGD system on Bonanza 1 in Vernal, Utah,
began in September 1984.  This 410-MW  (gross) unit fires
coal with an average sulfur content of 0.5 percent.  Combus-
tion Engineering supplied the wet-limestone FGD system.  A
fabric filter supplied by Ecolaire is used to control particu-
late emissions.  The unit operates in a closed-water-loop
mode and the sludge is disposed of in an onsite landfill.

                           xx

-------
General Public Utilities, not Jersey Central Power & Light
as previously reported, will be the operating utility of the
690-MW (gross) Coal 1 unit (reported earlier as 625 MW).
The unit and FGD system are still in the planning stage.
The coal-fired (3.5 percent sulfur) unit is scheduled to
start up sometime in 1993.

Iowa Electric Light and Power announced that they are post-
poning indefinitely their plans to install Guthrie County 1
in Panora, Iowa, because power demand has not met
projections.

Kentucky Utilities announced that they have postponed indefin-
itely their plans to install a second unit at the Hancock
station in Hawesville, Kentucky, because of a reduction in
projected power demand.

The Los Angeles Department of Water and Power reported that
the FGD system on Intermountain 2 in Delta, Utah, is now
under construction.  Fabric filters will control particulate
emissions from this 820-MW (gross) unit.  The wet limestone
FGD system will control S02 in the flue gas downstream from
the particulate collection equipment.  Flue gas reheat will
be provided by in-line heat exchangers prior to the 710-foot
stack.  The fly ash-stabilized sludge will be disposed of on
site at this closed-loop facility.  The unit is expected to
begin operations in July 1987.

The Lower Colorado River Authority reported that the Fayette
Power Project 3 in La Grange, Texas, is now under construction.
This lignite-fired 451-MW  (gross) unit will be equipped with
a wet-limestone FGD system designed to remove 90 percent of
the S02.  An ESP supplied by Flakt will control particulate
emissions, and the cleaned flue gas will exit through a
535-ft acid-brick-lined stack.  Sludge will be disposed of
in an onsite landfill.  The unit is expected to begin opera-
tions in November 1987.  The utility also announced plans to
construct a fourth unit at the Fayette Power Project Station
in La Grange, Texas.  This lignite-fired  (1.7 percent sulfur,
4300 Btu/lb) boiler will also use a wet-limestone FGD system
for S02 control and ESP's for particulate removal.  Initial
startup is scheduled for June 1990.

Middle South Utilities announced the cancellation of their
plans to install Arkansas Lignite 5 and 6 and two other
plants (name undecided), which were to be located in Louisiana,
The utility has also announced that they have postponed
indefinitely their plans to install Wilton 1 and 2 in Convent,
Louisiana, because of a reduction in projected power demand.

Minnesota Power and Light reported that the Clay Boswell 4
lime/alkaline fly ash FGD system demonstrated high dependa-
bilities during the months of October 1983 through June
1984.  No major FGD-related problems were encountered.
                           xxi

-------
Minnkota Power reported that the Milton R. Young 2 lime/al-
kaline fly ash FGD system demonstrated high dependability
during the period of October 1983 through June 1984, except
during December and January, when the system was shut down
for repairs on the absorber spray recycle system.

Montana Power reported that initial operation of the FGD
system on Colstrip 3 in Colstrip, Montana, began in October
1983.  This 778-MW (gross) unit fires low^sulfur coal (0.7
percent sulfur, 8500 Btu/lb).  The lime/alkaline fly ash FGD
system was supplied by Bechtel/Montana Power.  Particle
scrubbers are used to control particulate emissions, and the
system operates in a closed-water-loop mode.  Flue gas exits
via a 692-ft stack.

New York State Electric and Gas indicated that initial oper-
ation of the FGD system on Somerset 1 in Somerset, New York,
began in September 1984.  This 625-MW (gross) unit fires
coal with an average sulfur content of 2.2 percent.  A
cold-side ESP with a design efficiency of 99.7 percent is
used for particulate control.  The wet-limestone FGD system
was supplied by Peabody Process Systems.  The system operates
in a closed-water-loop mode, and the flue gas exits via a
450-ft stack.  The sludge is dewatered and stabilized before
being landfilled.

Nevada Power reported that the Reid Gardner 1, 2, 3, and 4
sodium carbonate FGD systems demonstrated high dependabili-
ties during the months of October 1983 through August 1984.
Only minor FGD-related problems were encountered.

Northern Indiana Public Service reported that the Schahfer
17 dual-alkali FGD system demonstrated high dependabilities
during the months of October 1983 through July 1984.  No
major FGD-related problems were encountered.

Orlando Utilities Commission announced that the Combustion
Engineering wet-limestone FGD system on C. H. Stanton 1 in
Orlando, Florida, is now under construction.  The utility
will control particulate emissions with an ESP.  Initial
startup is scheduled for 1987.

Pacific Power and Light announced that construction of the
retrofit wet sodium carbonate FGD system on Jim Bridger 2
began during the first quarter of 1984.  The retrofit system
will treat 2,700,000 acfm of flue gas from a 550-MW  (gross)
bituminous coal-fired boiler located in Rock Springs, Wyoming.
A cold-side ESP is currently in operation for primary particu-
late control.  The FGD system will operate in a  closed-water-
loop mode and flue gas will exit via a 500-ft stack.  The
FGD system is scheduled to  start up in 1986.  The utility
also announced that a contract has been awarded  to Joy

                          xxii

-------
Manufacturing/Niro Atomizer for a retrofit lime/spray-drying
system to control particulate matter and S02 emissions from
Wyodak 1.  This 330-MW  (gross) mine mouth plant is located
in Joliet, Wyoming, and has been operational since 1978.
The FGD system is scheduled to start up in 1986.

The Platte River Power Authority reported that initial
operation of the FGD system on Rawhide 1 in Wellington,
Colorado, began in December 1983.  The 279-MW (gross) unit
supplied by Combustion Engineering fires low-sulfur coal
(0.34 percent sulfur, 8500 Btu/lb).  Joy Manufacturing/Niro
Atomizer supplied the dry-lime FGD system for S02 control
and the fabric filters for particulate removal.   The system
operates in a closed-water-loop mode, and sludge is disposed
of in a landfill.  Flue gas exits via a 505-ft stack.

Public Service Company of Colorado has plans for a new unit,
Pawnee 2, to be located near Rush, Colorado.  The 500-MW
(gross) Babcock & Wilcox boiler will fire subbituminous coal
(0.35 percent sulfur, 8290 Btu/lb).  Fabric filters will be
utilized for particulate removal and S02 emissions will be
controlled through injection of dry trona.  The trona will
be pulverized and blown into the ductwork upstream of the
fabric filter system for contact with flue gas on the duct
and fabric filter surfaces.  Flue gas will exit via a 500-ft
stack.  Initial startup of the unit is scheduled for 1990.

Public Service of New Mexico reported that the San Juan 1,
2, and 3 Wellman Lord FGD systems achieved high dependabili-
ties for most of the period.  Minor FGD-related problems
encountered included replacing the absorber lining, repairing
absorber trays, and replacing broken mist eliminator pads.

San Antonio Public Service reported plans to construct  four
new units (name and location undecided) instead of two, as
previously reported.  The lignite-fired (1 to 2 percent
sulfur, 5600 Btu/lb) units will have a gross megawatt rating
of 500 each and each will have a wet-limestone FGD system.
The four units are scheduled to commence operations in  1993,
1995, 1999, and 2001, respectively.

Seminole Electric reported that initial operation of the  FGD
system on Seminole 2 in Palatka, Florida, began in September
1984.  This 620-MW  (gross) unit fires coal with an average
sulfur content of 2.75 percent.  The Peabody Process Systems
wet-limestone FGD system is downstream of an ESP used  for
particulate control.  The cleaned flue gas exits via a
675-ft stack.  The utility also announced they have  indefin-
itely postponed their plans to install Taylor 1 and  2  in
Perry, Florida, because power demand has not met projections.
                           XXlll

-------
South Carolina Public Service reported that initial opera-
tion of the FGD system on Cross 2 in Cross, South Carolina,
began in October 1983.  This 450-MW (gross) unit fires coal
with an average sulfur content of 1.8 percent.  The wet-lime-
stone scrubbing system, supplied by Peabody Process Systems,
controls S02 emissions, and a cold-side ESP controls
particulate emissions.  The system operates in a closed-water-
loop mode, and the cleaned flue gas exits via a 600-ft
stack.  The utility also announced that the Winyah 2 limestone
FGD system achieved high dependabilities during the months
of October 1983 through March 1984.  Minor FGD-related
problems encountered included cleaning the mist eliminators
and repairing frozen slurry and water pipe lines.

South Mississippi Electric Power reported that the R. D.
Morrow, Sr. 1 and 2 limestone FGD systems demonstrated high
dependabilities during the period of October 1983 through
July 1984 except for October.  The R. D. Morrow, Sr. 1 FGD
system was off line most of October for absorber ductwork
repairs and the other FGD system was also unavailable that
month because of scheduled maintenance.

Southern Indiana Gas and Electric announced that the FMC
dual-alkali FGD system on A. B. Brown 2 in West Franklin,
Indiana, is now under construction.  The 265-MW  (gross) unit
will fire bituminous coal (3.35 percent sulfur, 11,100
Btu/lb).  A cold-side ESP will provide primary particulate
matter control.  The cleaned flue gas will" exit via a 498-ft
stack.  The system will operate in a closed-water-loop mode,
and the sludge will be disposed of in an onsite landfill.
Operation of the FGD is scheduled to start up in January
1985.

Southwestern Public Service reported that the wet-limestone
FGD system on Dolet Hills 1 in Mansfield, Louisiana, is now
under construction.  Flue gas from this 720-MW  (gross)
lignite-fired unit will exit via a 525-ft stack, and the
system will operate in a closed-water-loop mode.  Initial
startup is scheduled for December 1985.

Southwestern Public Service announced plans to construct a
new unit, South Plains 1, to be located near Idalou, Texas.
The 572-MW  (gross) unit will burn low-sulfur Western coal
and will be equipped with an FGD system to control SO
emissions.  Initial startup is scheduled for 1990.

United Power Association reported that the Stanton 1A lime/
spray drying FGD system demonstrated high dependabilities
during the months of October 1983 through June 1984.  No
major FGD-related problems were encountered.
                          xxiv

-------
West Texas Utilities reported that the GEESI wet-limestone
FGD system on Oklaunion 1 in Oklaunion, Texas, is now under
construction.  The 720-MW (gross) coal-fired unit will also
be equipped with a Lodge-Cottrell rigid-frame, cold-side ESP
for particulate control.  The system will operate in a
closed-loop mode, and the cleaned flue gas will exit via a
453-ft acid-brick-lined stack.  Initial operations are
scheduled for September 1986.
                           XXV

-------
                           REFERENCES


1.    U.S.  Environmental Protection Agency-   Flue Gas Desulfuri-
     zation Information System (FGDIS).   Computerized Data Base.
     Industrial Environmental Research  Laboratory,  Research
     Triangle Park,  N.C.   (Access to FGDIS  can be obtained through
     Walter Finch,  NTIS,  5285 Port Royal Road, Springfield,
     Virginia 22161).

2.    U.S.  Department of Energy.   Inventory  of Power Plants in the
     United States.   Office of Utility  Project Operations.
     DOE/RA-0001,  December 1977.

3.    U.S.  Department of Energy.   Inventory  of Power Plants in the
     United States - December 1979.  Energy Information Administra-
     tion.  DOE/EIA-0095(79), June 1980.

4.    U.S.  Department of Energy.   Inventory  of Power Plants in the
     United States - 1980 Annual.  Energy Information Administra-
     tion.  DOE/EIA-0095(80), June 1981.

5.    U.S.  Department of Energy.   Inventory  of Power Plants in the
     United States - 1981 Annual.  Energy Information Administra-
     tion Office of Coal, Nuclear, Electric, and Alternate Fuels.
     DOE/EIA-0095(81),  September  1982.

6.    U.S.  Department of Energy.   Inventory  of Power Plants in the
     United States - 1982 Annual.  Energy Information Administra-
     tion Office of Coal, Nuclear, Electric, and Alternate Fuels.
     DOE/EIA-0095(82),  June 1983.

7.    Personal communication from  Mr. Skeer, Office of Policy
     Planning and  Analysis, U.S.  Department of Energy, August
     1983.

8.    U.S.  Department of Energy.   Energy Information Administra-
     tion.  Office of Coal, Nuclear, Electric, and Alternate
     Fuels.  Electric Power Monthly, DOE/EIA-0226 (83/01), January
     1983.                                                      *
                               XXVI

-------
                                               UTILITY FGO SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                          SECTION 1
                                  SUMMARY  LIST OF FGD SYSTEMS
COMPANY NAME/
UNIT NAME
ALABAMA ELECTRIC
TOMBIGBEE
TOMBIGBEE
ARIZONA ELECTRIC POWER
APACHE
APACHE
ARIZONA PUBLIC SERVICE
CHOLLA
CHOLLA
CHOLLA
CHOLLA
FOUR CORNERS
FOUR CORNERS
FOUR CORNERS
FOUR CORNERS
FOUR CORNERS
UNIT NO.

2
3

2
3

1
2
4
5
1
2
3
4
5
UNIT LOCATION

LEROY
LEROY

COCHISE
COCHISE

JOSEPH CITY
JOSEPH CITY
JOSEPH CITY
JOSEPH CITY
FRUITLAND
FRUITLAND
FRUITLAND
FARMINGTON
FARMINGTON


ALABAMA
ALABAMA

ARIZONA
ARIZONA

ARIZONA
ARIZONA
ARIZONA
ARIZONA
NEW MEXICO
NEW MEXICO
NEW MEXICO
NEW MEXICO
NEW MEXICO
START-UP
DATE

9/78
6/79

8/78
6/79

10/73
4/78
3/81
0/97
11/79
11/79
11/79
10/84
10/84
STATUS

1
1

1
1

1
1
1
6
1
1
1
Z
2
REG
CLASS

D
D

C
c

C
c
A
A
C
C
C
A
A
ASSOCIATED ELECTRIC
   THOMAS HILL

ATLANTIC CITY ELECTRIC
   CUMBERLAND

BASIN ELECTRIC POWER
   ANTELOPE VALLEY
   ANTELOPE VALLEY
   ANTELOPE VALLEY
   LARAMIE RIVER
   LARAMIE RIVER
   LARAMIE RIVER

BIG RIVERS ELECTRIC
   D.B. WILSON
   GREEN
   GREEN

BOSTON EDISON
   NEW BOSTON
   NEW BOSTON

CAJUN ELECTRIC POWER
   OXBOW

CENTRAL ILLINOIS LIGHT
   DUCK CREEK

CENTRAL ILLINOIS PUBLIC SERV
   NEWTON

CENTRAL MAINE POWER
   SEARS ISLAND
        MOBERLY
        MILLVILLE
MISSOURI
NEW JERSEY
                                       10/62
                                       99/99
BEULAH
BEULAH
BEULAH
WHEAT LAND
WHEATLAND
WHEATLAND
CENTERTOWN
SEBREE
SEBREE
BOSTON
BOSTON
DE SOTO PARISH
CANTON
NEWTON
PENOBSCOT BAY
NORTH DAKOTA
NORTH DAKOTA
NORTH DAKOTA
WYOMING
WYOMING
WYOMING
KENTUCKY
KENTUCKY
KENTUCKY
MASSACHUSETTS
MASSACHUSETTS
LOUISIANA
ILLINOIS
ILLINOIS
MAINE
5/83
11/85
0/92
7/80
7/81
11/62
9/84
12/79
11/80
10/87
6/88
99/99
7/76
9/79
11/95
                                                  5
                                                  5
                                                  3


                                                  1
                                   B


                                   D


                                   D


                                   A
1.  OPERATIONAL UNITS
2.  UNITS UNDER CONSTRUCTION
3.  PLANNED - CONTRACT AWARDED
4.  PLANNED - LETTER OF INTENT SIGNED
5.  PLANNED - REQUESTING/EVALUATING BIDS
6.  PLANNED - CONSIDERING ONLY FGD SYSTEMS FOR S02  CONTROL
7.  PLANNED - CONSIDERING FGD SYSTEMS!  ALSO ALTERNATIVE METHODS
A.  STANDARD!S) MORE STRINGENT THAN NSPS (6/79)
B.  FEDERAL NSPS (6/79)
C.  STAK'DARD(S) MORE STRINGENT THAN NSPS (12/71) BUT NOT MORE STRINGENT THAN NSPS (6/79)
D.  FEDERAL NSPS (12/71)
E.  STANDARD(S) EQUAL TO OR LESS STRINGENT THAN NSPS (12/71)
                                           1-1

-------
UTILITY FGD SUPVEY: OCTOBER 1983 - SEPTEMBER
                                             SECTION 1
                                    SUMMARY LIST OF FGD SYSTEMS
  COMPANY NAME/
     UNIT NAME
UNIT NO. UNIT LOCATION
                                   START-UP
                                     DATE    STATUS CLASS
  CENTRAL POWER & LIGHT
     COLETO CREEK                2

  CINCINNATI GAS 4 ELECTRIC
     EAST BEND                   1
     EAST BEND                   Z
     ZIMMER                      1

  COLORADO UTE ELECTRIC
     CRAIG                       1
     CRAIG                       Z
     CRAIG                       3

  COLUMBUS t SOUTHERN OHIO ELEC
     COHESVILLE                  5
     CONESVILLE                  6

  COOPERATIVE  POWER
     N/D                         1

  COOPERATIVE  POWER ASSOCIATION
     COAL CREEK                  1
     COAL CREEK                  2

  DELMARVA POWER &  LIGHT
     DELAWARE  CITY               1
     DELAWARE  CITY               2
     DELAWARE  CITY               3
     VIENNA                      9

  DESERET GEN  t TRANS
     BONANZA                     1
     BONANZA                     2

  DUQUESNE  LIGHT
     ELRAMA                      1-4
     PHILLIPS                    1-6

  EAST KENTUCKY POWER
     J.K. SMITH                  1
     SPUR LOCK                    2

  FLORIDA POWER &  LIGHT
     MARTIN                      3
     MARTIN                      *

  GENERAL PUBLIC UTILITIES
     COAL                        1
     COAL                        2

  GRAND HAVEN  BRD  OF  LIGHT  & PWR
     J.B. SIMS                  3

  GRAND RIVER  DAM  AUTHORITY
     GRDA                        2
         FANNIN
         RABBIT HASH
         RABBIT HASH
         MOSCOW
         CRAIG
         CRAIG
         CRAIG
         CONESVILLE
         CONESVILLE
         UNDECIDED
         UNDERWOOD
         UNDERWOOD
                        TEXAS
                   KENTUCKY
                   KENTUCKY
                   OHIO
                   COLORADO
                   COLORADO
                   COLORADO
                   OHIO
                   OHIO
                   OHIO
                   NORTH DAKOTA
                   NORTH DAKOTA
                                         10/93
         DELAWARE CITY  DELAWARE
         DELAWARE CITY  DELAWARE
         DELAWARE CITY  DELAWARE
         VIENNA         MARYLAND
         VERNAL
         VERNAL
                   UTAH
                   UTAH
         ELRAMA         PENNSYLVANIA
         SOUTH HEIGHTS  PENNSYLVANIA
         WINCHESTER     KENTUCKY
         MAYSVILLE      KENTUCKY
         MARTIN COUNTY  FLORIDA
         MARTIN COUNTY  FLORIDA
         FORKED RIVER   NEW JERSEY
         UNDECIDED      UNDECIDED
         GRAND HAVEN    MICHIGAN
0/89
3/81
0/91
10/80
12/79
6/8*
1/77
6/78
0/9*
7/79
7/80
5/80
5/80
5/80
0/95
9/8*
0/92
10/75
7/73
6
1
6
1
1
1
1
1
6
1
1
1
1
1
6
1
6
1
1
A
C

C
C
C
D
D
B
D
D
E
E
E
B
A
A
C
C
                                           PRYOR
                                                         OKLAHOMA
                                     0/92
                                    12/82
                                     0/9*
                                     0/95
                                     0/93
                                     0/97
                                          5/83


                                          3/85
A
C
B
B
B
B
                                                                                             B
   1.   OPERATIONAL UNITS
   2.   UNITS UNDER CONSTRUCTION
   3.   PLANNED  -  CONTRACT  AWARDED
 *.
 5.
 6.
 7.
PLANNED - LETTER OF INTENT SIGNED
PLANNED - REQUESTING/EVALUATING BIDS
PLANNED - CONSIDERING ONLY FGD SYSTEMS FOR S02 CONTROL
PLANNED - CONSIDERING FGD SYSTEMS;  ALSO ALTERNATIVE METHODS
   A.   STANDARD(S)  MORE  STRINGENT THAN NSPS  (6/79)
   B.   FEDERAL  NSPS (6/79)
   C.   STANDARD(S)  MORE  STRINGENT THAN NSPS  (12/71) BUT NOT MORE STRINGENT THAN NSPS
   D.   FEDERAL  NSPS (12/71)
   E.   STANDARD!S)  EQUAL TO  OR  LESS STRINGENT THAN NSPS (12/71)
                                              1-2

-------
                                                UTILITY FGO SURVEY:  OCTOBER  1983  - SEPTEMBER 1984
                                           SECTION 1
                                  SUMMARY LIST OF FGD SYSTEMS
COMPANY NAME/
UNIT NAME
HOOSIER ENERGY
MEROM
MEROM
HOUSTON LIGHTING * POWER
LIMESTONE
LIMESTONE
MALAKOFF
MALAKOFF
W.A. PARISH
INDIANAPOLIS POWER t LIGHT
PATRIOT
PATRIOT
PATRIOT
PETERSBURG
PETERSBURG
UNIT NO.

1
Z

I
Z
1
2
8

1
2
3
3
4
UNIT LOCATION

MEROM
MEROM

JEWITT
JEWITT
MALAKOFF
MALAKOFF
THOMPSONS

PATRIOT
PATRIOT
PATRIOT
PETERSBURG
PETERSBURG


INDIANA
INDIANA

TEXAS
TEXAS
TEXAS
TEXAS
TEXAS

INDIANA
INDIANA
INDIANA
INDIANA
INDIANA
START-UP
DATE

8/82
12/81

12/85
12/86
12/89
12/90
10/82

0/93
O/ 0
O/ 0
12/77
3/86
STATUS

1
1

Z
Z
3
3
1

6
6
6
1
Z
REG
CLASS

D
D

B
B
B
B
B

A
A
A
D
D
IOWA ELECTRIC LIGHT ft
   GUTHRIE CO.
PWR
JACKSONVILLE ELEC AUTHORITY
   ST.JOHNS RVR PWR PRK
   ST.JOHNS RVR PWR PRK

KANSAS CITY POWER « LIGHT
   LA CYGNE

KANSAS POWER t LIGHT
   JEFFREY
   JEFFREY
   JEFFREY
   LAWRENCE
   LAWRENCE

KENTUCKY UTILITIES
   GREEN RIVER
   HANCOCK
   HANCOCK

LAKELAND UTILITIES
   MCINTOSH

LOS ANGELES DEPT OF WTR t PWR
   INTERMOUNTAIN
   INTERHOUNTAIN

LOUISVILLE GAS & ELECTRIC
   CANE RUN
   CANE RUN
   CANE RUN
   MILL CREEK
   MILL CREEK
   MILL CREEK
   MILL CREEK
   PADDY'S RUN
1.  OPERATIONAL UNITS           4.
2.  UNITS UNDER CONSTRUCTION    5.
3.  PLANNED - CONTRACT AWARDED  6.
                                7.
                                        PANORA
                  JACKSONVILLE
                  JACKSONVILLE
                  LA CYGNE
                                                       IOWA
               FLORIDA
               FLORIDA
                                 KANSAS
1
2
3
4
5
UAMEGO
WAMEGO
WAMEGO
LAWRENCE
LAWRENCE
KANSAS
KANSAS
KANSAS
KANSAS
KANSAS
         1-3
         1
         2
CENTRAL CITY
HAWESVILLE
HAWESVILLE
                  LAKELAND
                  DELTA
                  DELTA
KENTUCKY
KENTUCKY
KENTUCKY
               FLORIDA
               UTAH
               UTAH
4
5
6
1
2
3
4
6
LOUISVILLE
LOUISVILLE
LOUISVILLE
LOUISVILLE
LOUISVILLE
LOUISVILLE
LOUISVILLE
LOUISVILLE
KENTUCKY
KENTUCKY
KENTUCKY
KENTUCKY
KENTUCKY
KENTUCKY
KENTUCKY
KENTUCKY
                                                                        99/99
                  4/87
                 10/88
                                                 12/72
                                                  8/78
                                                  1/80
                                                  5/83
                                                  1/77
                                                  4/78
 9/75
10/93
99/99
                  7/82
                  7/86
                  7/87
1
3
6
                  A
                  A
                                                 C
                                                 c
                                                 C
                                                 c
                                                 c
c
A
A
8/76
12/77
4/79
12/80
12/81
8/78
7/82
4/73
1
1
1
1
1
1
1
1
E
E
E
E
E
D
D
E
              PLANNED - LETTER OF INTENT SIGNED
              PLANNED - REQUESTING/EVALUATING BIDS
              PLANNED - CONSIDERING ONLY FGD SYSTEMS FOR  S02  CONTROL
              PLANNED - CONSIDERING FGD SYSTEMS;  ALSO ALTERNATIVE  METHODS
A.  STANDARD(S) MORE STRINGENT THAN NSPS (6/79)
B.  FEDERAL NSPS (6/79)
C.  STANDARD(S) MORE STRINGENT THAN NSPS (12/71) BUT NOT MORE STRINGENT THAN NSPS (6/79)
D.  FEDERAL NSPS (12/71)
E.  STANDARD(S) EQUAL TO OR LESS STRINGENT THAN NSPS (12/71)
                                           1-3

-------
UTIUITt FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 1
                                    SUMMARY LIST OF FGD SYSTEMS
COMPANY NAME/
UNIT NAME
LOUISVILLE GAS & ELECTRIC
TRIMBLE COUNTY
TRIMBLE COUNTY
LOWER COLORADO RIVER AUTH
FAYETTE POWER PROJECT
FAYETTE POWER PROJECT
MARQUETTE BOARD OF LIGHT & PWR
SHIRAS
MICHIGAN SO CENTRAL PWR AGENCY
PROJECT
MIDDLE SOUTH UTILITIES
WILTON
WILTON
MINNESOTA POWER * LIGHT
CLAY BOSWELL
MINNKOTA POWER
MILTON R. YOUNG
MONONGAHELA POWER
PLEAS ANTS
PLEASANTS
MONTANA POWER
COLSTRIP
COLSTRIP
COLSTRIP
COLSTRIP
UNIT NO.

1
2

3
4

3

1

1
Z

4

2

1
2

1
2
3
4
UNIT LOCATION

BEDFORD
BEDFORD

LA GRANGE
LA GRANGE

MARQUETTE

LITCHFIELD

CONVENT
CONVENT

COHASSET

CENTER

WILLOW ISLAND
WILLOW ISLAND

COLSTRIP
COLSTRIP
COLSTRIP
COLSTRIP


KENTUCKY
KENTUCKY

TEXAS
TEXAS

MICHIGAN

MICHIGAN

LOUISIANA
LOUISIANA

MINNESOTA

NORTH DAKOTA

WEST VIRGINIA
WEST VIRGINIA

MONTANA
MONTANA
MONTANA
MONTANA
START-UP
DATE

7/87
7/90

11/87
6/90

3/83

5/83

99/99
99/99

2/80

9/77

12/78
10/80

9/75
5/76
10/83
10/85
STATUS

5
5

2
6

1

1

4
4

1

1

1
1

1
1
1
2
REG
CLASS

A
A

B
B

B

B

B
B

D

D

D
D

D
D
A
A
   MONTANA-DAKOTA UTILITIES
      COYOTE                      1

   MUSCATINE  POWER  t WATER
      MUSCATINE                   9

   NEBRASKA PUBLIC  POWER DISTRICT
      FOSSIL  III                  1
   NEVADA  POWER
      HARRY  ALLEN
      HARRY  ALLEN
      HARRY  ALLEN
      HARRY  ALLEN
      REID GARDNER
      REID GARDNER
      REID GARDNER
      REID GARDNER

   NEW YORK  STATE ELEC  t
      SOMERSET
         1
         2
         3
         4
         1
         2
         3
         4
GAS
                  BEULAH
                  MUSCATINE
                                          SARGENT
    LAS VEGAS
    LAS VEGAS
    LAS VEGAS
    LAS VEGAS
    MOAPA
    MOAPA
    MOAPA
    MOAPA
                                          SOMERSET
                                 NORTH DAKOTA
                                 IOWA
                                                         NEBRASKA
NEVADA
NEVADA
NEVADA
NEVADA
NEVADA
NEVADA
NEVADA
NEVADA
                                                         NEW YORK
                                                   4/81
                                                   4/83
                                                                           3/96
0/94
0/95
0/96
0/97
3/74
4/74
6/76
6/83
6
6
6
6
1
1
1
1
B
B
B
B
D
D
D
B
                                                                           7/84
   1.  OPERATIONAL UNITS
   2.  UNITS  UNDER CONSTRUCTION
   3.  PLANNED  - CONTRACT AWARDED
          4.
          5.
          6.
          7.
PLANNED - LETTER OF INTENT SIGNED
PLANNED - REQUESTING/EVALUATING BIDS
PLANNED - CONSIDERING ONLY FGD SYSTEMS FOR S02 CONTROL
PLANNED - CONSIDERING FGD SYSTEMS; ALSO ALTERNATIVE METHODS
  A.  STANDARD(S) MORE STRINGENT THAN NSPS (6/79)
  B.  FEDERAL NSPS  (6/79)
  C.  STANDARD(S) MORE STRINGENT THAN NSPS (12/71) BUT NOT MORE STRINGENT THAN N«?P<;
  D.  FEDERAL NSPS  (12/71)                                                       3  s
  E.  STANDARD!S) EQUAL TO OR  LESS STRINGENT THAN NSPS (12/71)
                                             1-4

-------
                                                UTILITY FGD SURVEY:  OCTOBER  1983 -  SEPTEMBER  1984
                                           SECTION 1
                                  SUMMARY LIST OF FGD SYSTEMS
COMPANY NAME/
   UNIT NAME
                               UNIT NO. UNIT LOCATION
                                      START-UP          REG
                                        DATE    STATUS CLASS
NIAGARA MOHAMK POWER
   CHARLES R. HUNTLEY          66

NORTHERN INDIANA PUB SERVICE
   SCHAHFER                    17
   SCHAHFER                    18

NORTHERN STATES POWER
   RIVERSIDE                   6-7
   SHERBURNE                   1
   SHERBURNE                   2
   SHERBURNE                   3

ORLANDO UTILITIES COMMISSION
   C.H. STANTON                1

PACIFIC POWER & LIGHT
   JIM BRIDGER                 1
   JIM BRIDGER                 2
   JIM BRIDGER                 3
   JIM BRIDGER                 4
   WYODAK                      1

PENNSYLVANIA POWER
   BRUCE MANSFIELD             1
   BRUCE MANSFIELD             2
   BRUCE MANSFIELD             3

PHILADELPHIA ELECTRIC
   CROMBY                      1
   EDDYSTONE                   1
   EDDYSTONE                   2

PLAINS ELECTRIC G & T
   PLAINS ESCALANTE            1

PLATTE RIVER POWER AUTHORITY
   RAWHIDE                     1

PUBLIC SERVICE INDIANA
   GIBSON                      5
 PUBLIC SERVICE OF NEW MEXICO
   NEW MEXICO
   SAN JUAN
   SAN JUAN
   SAN JUAN
   SAN JUAN

 PUB. SER. CO. OF COLORADO
   PAWNEE
SALT RIVER  PROJECT
   COROHADO                    1
   CORONADO                    2
   CORONADO                    3

1.  OPERATIONAL UNITS
2.  UNITS UNDER CONSTRUCTION
3.  PLANNED - CONTRACT AWARDED
        BUFFALO
                      NEW YORK
4.
5.
6.
7.
WHEATFIELD
WHEATFIELD
MINNEAPOLIS
BECKER
BECKER
BECKER
INDIANA
INDIANA
MINNESOTA
MINNESOTA
MINNESOTA
MINNESOTA
        ORLANDO
        ROCK SPRINGS
        ROCK SPRINGS
        ROCK SPRINGS
        ROCK SPRINGS
        JOLIET
        SHIPPINGPORT
        SHIPPINGPORT
        SHIPPINGPORT
        PHOENIXVILLE
        EDDYSTONE
        EDDYSTONE
        PREWITT
        WELLINGTON
        PRINCETON
                       FLORIDA
                  WYOMING
                  WYOMING
                  WYOMING
                  WYOMING
                  WYOMING
                   PENNSYLVANIA
                   PENNSYLVANIA
                   PENNSYLVANIA
                   NEW MEXICO
                       COLORADO
                   INDIANA
                                        4/82
                                        4/83
                                        6/86
                                       11/80
                                        3/76
                                        3/77
                                        0/88
                                        0/87
 0/90
 0/86
 0/88
 9/79
 0/86
12/75
 7/77
 6/80
                   PENNSYLVANIA     10/82
                   PENNSYLVANIA      9/82
                   PENNSYLVANIA     11/82
10/84
                                    12/83
                                    10/82
        RUSH
        ST. JOHNS
        ST. JOHNS
        ST. JOHNS
                       COLORADO
                   ARIZONA
                   ARIZONA
                   ARIZONA
                                     0/90
11/79
 7/80
 0/92
3
2
3
1
3
1
1
6
                                                     B
                                                     B
                                                     E
                                                     C
                                                     c
                                                     A
C
C
c
c
A
       C
       C
       c
                  c
                  c
                  c
1
1
2
3
4
BISTI
WATERFLOW
MATERFLOW
WATERFLOW
WATERFLOW
NEW MEXICO
NEW MEXICO
NEW MEXICO
NEW MEXICO
NEW MEXICO
0/95
4/78
8/78
12/79
5/82
6
1
1
1
1
A
A
A
A
A
C
c
B
PLANNED - LETTER OF INTENT SIGNED
PLANNED - REQUESTING/EVALUATING BIDS
PLANNED - CONSIDERING ONLY FGD SYSTEMS FOR S02 CONTROL
PLANNED - CONSIDERING FGD SYSTEMS;  ALSO ALTERNATIVE METHODS
A.  STANDARD(S) MORE STRINGENT THAN NSPS  (6/79)
B.  FEDERAL NSPS  (6/79)
C.  STANDARD(S) MORE STRINGENT THAN NSPS  (12/71) BUT NOT MORE STRINGENT THAN NSPS (6/79)
D.  FEDERAL NSPS  (12/71)
E.  STANDARD(S) EQUAL TO OR  LESS STRINGENT THAN NSPS (12/71)
                                            1-5

-------
UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER
                                             SECTION 1
                                    SUMMARY LIST OF FGD SYSTEMS
COMPANY NAME/
UNIT NAME
SAN ANTONIO PUBLIC SERVICE
N/D
N/D
N/D
N/D

UNIT NO.

1
2
3
4

UNIT LOCATION

UNDECIDED
UNDECIDED
UNDECIDED
UNDECIDED



TEXAS
TEXAS
TEXAS
TEXAS
START-UP
DATE

0/93
0/95
0/99
99/99
REG
STATUS CLASS

6 B
6 B
6 B
6 B
  SAN MIGUEL ELECTRIC
     SAN MIGUEL

  SEMINOLE ELECTRIC
     SEMINOLE
     SEMINOLE
     TAYLOR
     TAYLOR

  SIERRA PACIFIC POWER
     THOUSAND SPRINGS
     THOUSAND SPRINGS
     THOUSAND SPRINGS
     VALMY
  SIKESTON BRD OF MUNICIPAL UTIL
     SIKESTON                    1
  SOUTH CAROLINA PUBLIC SERVICE
     CROSS
     CROSS
     WINYAH
     WINYAH
     WINYAH

  SOUTH MISSISSIPPI ELEC PWR
     R.D. MORROW, SR.
     R.D. MORROW, SR.

  SOUTHERN ILLINOIS POWER
     MARION

  SOUTHERN INDIANA GAS i. ELEC
     A.B. BROWN
     A.B. BROWN

  SOUTHWESTERN ELECTRIC POWER
     DOLET HILLS
     HENRY W. PIRKEY
     WALKER  CO.
     WALKER  CO.

  SOUTHWESTERN PUBLIC SERVICE
     SOUTH PLAINS

  SPRINGFIELD CITY UTILITIES
     SOUTHWEST
        SAN  MIGUEL
        PALATKA
        PALATKA
        PERRY
        PERRY
        WELLS
        HELLS
        WELLS
        VALMY
        SIKESTON
                       TEXAS
                   FLORIDA
                   FLORIDA
                   FLORIDA
                   FLORIDA
                   NEVADA
                   NEVADA
                   NEVADA
                   NEVADA
                       MISSOURI
                                         8/81
 5/83
 9/84
99/99
99/99
 0/90
 0/95
 0/99
 6/85
                                         6/81
        MARION
                       ILLINOIS
        WEST FRANKLIN  INDIANA
        WEST FRANKLIN  INDIANA
                                         4/79
                                     3/79
                                     1/85
        IDALOO
                                          SPRINGFIELD
                       TEXAS
                                                         MISSOURI
                                         0/90
                                                                           4/77
1
1
6
6
       B
       B
       B
       B
1
2
2
3
4
1
2
CROSS
CROSS
GEORGETOWN
GEORGETOWN
GEORGETOWN
PURVIS
PURVIS
SOUTH CAROLINA
SOUTH CAROLINA
SOUTH CAROLINA
SOUTH CAROLINA
SOUTH CAROLINA
MISSISSIPPI
MISSISSIPPI
5/91
10/83
7/77
7/80
7/81
8/78
6/79
3
1
1
1
1
1
1
A
A
C
C
A
D
D
                  D
                  B
1
1
1
2
MANSFIELD
HALLSVILLE
HUNTSVILLE
HUNTSVILLE
LOUISIANA
TEXAS
TEXAS
TEXAS
12/85
12/84
12/93
12/93
2
2
6
6
B
D
B
B
   1.   OPERATIONAL UNITS
   2.   UNITS UNDER CONSTRUCTION
   3.   PLANNED  -  CONTRACT  AWARDED
4.
5.
6.
7.
PLANNED - LETTER OF INTENT SIGNED
PLANNED - REQUESTING/EVALUATING BIDS
PLANNED - CONSIDERING ONLY FGO SYSTEMS FOR S02 CONTROL
PLANNED - CONSIDERING FGD SYSTEMS; ALSO ALTERNATIVE METHODS
   A.   STANDARD(S)  MORE STRINGENT THAN NSPS  (6/79)
   B.   FEDERAL  NSPS (6/79)
   C.   STANDARD(S)  MORE STRINGENT THAN NSPS  (12/71) BUT NOT MORE STRINGENT  THAN  NSPS (6/79)
   D.   FEDERAL  NSPS (12/71)
   E.   STANDARD(S)  EQUAL TO OR  LESS STRINGENT THAN NSPS (12/71)
                                             1-6

-------
                                                UTILITY F6D SURVEY:  OCTOBER 1983 - SEPTEMBER
                                           SECTION 1
                                  SUMMARY LIST OF FGD SYSTEMS
COMPANY NAME/
   UNIT NAME
                               UNIT NO. UNIT LOCATION
                                                                      START-UP          REG
                                                                        DATE    STATUS CLASS
SPRINGFIELD WATER, LIGHT t PWR
   DALLMAN                     3

SUNFLOWER ELECTRIC
   HOLCOMB                     1

TAMPA ELECTRIC
   BIG BEND                    4

TENNESSEE VALLEY AUTHORITY
   PARADISE                    1
   PARADISE                    2
   WIDOWS CREEK                7
   WIDOWS CREEK                8

TEXAS MUNICIPAL POWER AGENCY
   GIBBONS CREEK               1

TEXAS POWER S LIGHT
   SANDOW                      4
   TWIN OAKS                   1
   TWIN OAKS                   2

TEXAS UTILITIES
   FOREST GROVE                1
   MARTIN LAKE                 1
   MARTIN LAKE                 2
   MARTIN LAKE                 3
   MARTIN LAKE                 <»
   MONTICELLO                  3

TUCSON ELECTRIC POWER
   SPRINGERVILLE               1
   SPRINGERVILLE               2
   SPRINGERVILLE               3

UNITED POWER ASSOCIATION
   STANTON                     1A
                                        SPRINGFIELD    ILLINOIS
                                        HOLCOMB
                                        TAMPA
                                        PARADISE
                                        PARADISE
                                        BRIDGEPORT
                                        STEVENSON
                                        CARLOS
                                                       KANSAS
                                                       FLORIDA
KENTUCKY
KENTUCKY
ALABAMA
ALABAMA
                                                       TEXAS
ROCKDALE
BREMOND
BREMOND
ATHENS
TATUM
TATUM
TATUM
TATUM
MT. PLEASANT
TEXAS
TEXAS
TEXAS
TEXAS
TEXAS
TEXAS
TEXAS
TEXAS
TEXAS
                                        SPRINGERVILLE  ARIZONA
                                        SPRINGERVILLE  ARIZONA
                                        SPRINGERVILLE  ARIZONA
                                        STANTON
                                                       NORTH DAKOTA
                 10/80
                  7/83
                  1/85
5/83
7/83
3/61
5/77
                 11/82
                                                                        12/80
                                                                         8/89
                                                                         8/91
                                                                         0/88
                                                                         4/77
                                                                         5/78
                                                                         2/79
                                                                         0/89
                                                                         5/76
                  2/65
                  2/89
                  0/91
                                                                         7/82
                            3
                            1
                            1
                            1
                            3
                            1
          2
          3
          6
C
c
C
c
                                   D
                                   B
                                   B
                 B
                 D
                 D
                 D
                 B
                 D
D
D
A
UTAH  POWER  &  LIGHT
   HUNTER
   HUNTER
   HUNTER
   HUNTINGTON
   NAUGHTON

WASHINGTON  WATER  POWER
   CRESTON  COAL
   CRESTON  COAL
   CRESTON  COAL
   CRESTON  COAL
1
2
3
1
3
1
2
3
4
CASTLE DALE
CASTLE DALE
CASTLE DALE
HUNTINGTON
KEMMERER
CRESTON
CRESTON
CRESTON
CRESTON
UTAH
UTAH
UTAH
UTAH
WYOMING
WASHINGTON
WASHINGTON
WASHINGTON
WASHINGTON
3/79
6/80
4/83
5/78
9/81
0/95
0/97
0/98
0/99
1
1
1
1
1
6
6
6
6
C
C
B
C
A
A
A
A
A
WEST  PENN  POWER
   MITCHELL                     33
                                        COURTNEY
                                                       PENNSYLVANIA
                                                                         8/82
1.  OPERATIONAL UNITS
2.  UNITS UNDER CONSTRUCTION
3.  PLANNED - CONTRACT AWARDED
                                <».  PLANNED - LETTER OF INTENT SIGNED
                                5.  PLANNED - REQUESTING/EVALUATING BIDS
                                6.  PLANNED - CONSIDERING ONLY FGD SYSTEMS FOR S02 CONTROL
                                7.  PLANNED - CONSIDERING FGD SYSTEMS; ALSO ALTERNATIVE METHODS
    STANDARD(S) MORE  STRINGENT THAN NSPS  (6/79)
    FEDERAL NSPS  (6/79)
    STANDARD(S) MORE  STRINGENT THAN NSPS  (12/71) BUT NOT MORE STRINGENT THAN NSPS (6/79)
    FEDERAL NSPS  (12/71)
A.
B.
C.
D.
E.  STANDARD(S) EQUAL TO OR LESS STRINGENT THAN NSPS (12/71)
                                           1-7

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER
                                             SECTION 1
                                    SUMMARY LIST OF F6D SYSTEMS
  COMPANY NAME/
     UNIT NAME
                           UNIT NO.  UNIT LOCATION
                                                                   START-UP
                                                                     DATE
                                                     REG
                                             STATUS CLASS
  WEST TEXAS UTILITIES
     OKLAUNION
     OKLAUNION

  WHITE PINE COUNTY
     WHITE PINE PWR PROJ.
     WHITE PINE PWR PROJ.
                                    OKLAUNION
                                    OKLAUNION
                                    ELY
                                    ELY
                   TEXAS
                   TEXAS
                   NEVADA
                   NEVADA
9/86
0/96
3/91
3/92
2
6
B
B
       B
       B
   1.   OPERATIONAL UNITS
   2.   UNITS UNDER CONSTRUCTION
   3.   PLANNED - CONTRACT AWARDED
                            5.
                            6.
                            7.
PLANNED - LETTER OF INTENT SIGNED
PLANNED - REQUESTING/EVALUATING BIDS
PLANNED - CONSIDERING ONLY FGD SYSTEMS FOR S02 CONTROL
PLANNED - CONSIDERING FGD SYSTEMS; ALSO ALTERNATIVE METHODS
  A.
  B.
  C.
  D.
  E.
STAW)ARD(S) MORE STRINGENT THAN NSPS (6/79)
FEDERAL NSPS (6/79)
STANDARD(S) MORE STRINGENT THAN NSPS (12/71)  BUT NOT MORE STRINGENT THAN NSPS (6/79)
rCutRAL N5P5 (12//1)
STANDARD(S) EQUAL TO OR LESS STRINGENT THAN NSPS (12/71)
                                             1-8

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF F6D SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
ALABAMA ELECTRIC
TOMBI6BEE
Z
NEW       ZS5 MM (GROSS)
          179 MW (ESC)
COAL
 1.61 XS  BITUMINOUS
LIMESTONE
PEABODY PROCESS SYSTEMS
ENERGY CONSUMPTION:  3.IX
STATUS 1     STARTUP  9/76
TOMBIGBEE Z OF ALABAMA ELECTRIC COOP IS A PULVERIZED COAL BOILER LOCATED
IN LEROY, ALABAMA. THE BOILER GENERATES A MAXIMUM FLUE GAS FLOW OF 953,000
ACFM AND BURNS BITUMINOUS COAL WITH AN AVERAGE SULFUR CONTENT OF 1.61X AND
AN AVERAGE HEAT CONTENT OF 11,42* BTU/LB. THE UNIT S02 EMMISSION LIMITA-
TION VALUE IS 1.2 LB/MMBTU. PRIMARY PARTICULATE MATTER CONTROL IS PROVID-
ED BY A HOT SIDE ESP. THE S02 REMOVAL EQUIPMENT CONSISTS OF TWO SPRAY
TOWERS SUPPLIED BY PEABODY PROCESS SYSTEMS WHICH UTILIZE A LIMESTONE REA-
GENT. A CHEVRON MIST ELIMINATOR IS INCLUDED FOR EACH TOHER AND THE FLUE
GAS IS REHEATED WITH BYPASSED GAS BEFORE BEING VENTED TO A 400 FOOT ACID-
BRICK LINED STACK. THE SYSTEM OPERATES IN A CLOSED WATER LOOP MODE AND
SPENT ABSORBENT IS DISPOSED OF IN AN ON-SITE LINED POND.
ALABAMA ELECTRIC
TOMBIGBEE
3
NEW       255 MW (GROSS)
          179 MW (ESC)
COAL
 1.61 XS  BITUMINOUS
LIMESTONE
PEABODY PROCESS SYSTEMS
ENERGY CONSUMPTION:  3.IX
STATUS 1     STARTUP  6/79
TOMBIGBEE 3 OF ALABAMA ELECTRIC COOP IS A PULVERIZED COAL BOILER LOCATED
IN LEROY, ALABAMA. THE BOILER GENERATES A MAXIMUM FLUE GAS FLOW OF 953,000
ACFM AND BURNS BITUMINOUS COAL WITH AN AVERAGE SULFUR CONTENT OF 1.61 AND
AN AVERAGE HEAT CONTENT OF 11,424 BTU/LB. THE UNIT S02 EMISSION LIMITATION
VALUE IS 1.2 LB/MMBTU. PRIMARY PARTICULATE CONTROL IS PROVIDED BY A HOT
SIDE ESP. THE S02 REMOVAL EQUIPMENT CONSISTS OF TWO SPRAY TOWERS SUPPLIED
BY PEABODY PROCESS SYSTEMS WHICH UTILIZE A LIMESTONE REAGENT. A CHEVRON
MIST ELIMINATOR IS INCLUDED IN EACH TOWER, AND THE FLUE GAS IS REHEATED
WITH BYPASSED GAS BEFORE BEING VENTED TO A 400 FOOT ACID BRICK LINED
STACK. THE SYSTEM OPERATES IN A CLOSED WATER LOOP MODE, AND SPENT ABSORB-
ENT IS DISPOSED IN AN ON-SITE LINED POND.
ARIZONA ELECTRIC POWER
APACHE
2
NEW       195 MW (GROSS)
            98 MW (ESC)
COAL
   .70 XS  SUBBITUMINOUS
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION:   4.IX
STATUS 1     STARTUP 8/78
APACHE 2 OF ARIZONA ELECTRIC POWER COOP IS LOCATED IN COCHISE,  ARIZONA AND
IS A DRY BOTTOM PULVERIZED COAL FIRED UNIT WITH A FLUE GAS FLOW OF 735,000
ACFM. SUBBITUMINOUS COAL WITH A HEATING VALUE OF 10,000 BTU/LB, A SULFUR
CONTENT OF 0.70X AND AN ASH CONTENT OF 15X IS THE FUEL USED FOR THIS UNIT.
PARTICULATE MATTER IS CONTROLLED BY A HOT SIDE ESP.  HALF THE FLUE GAS
PASSES THROUGH TWO RESEARCH-COTTRELL PACKED TOWERS EMPLOYING LIMESTONE
ABSORBENT AND HAVING A DESIGN S02 REMOVAL OF 85X.  ENTRAINED DROPLETS ARE
REMOVED BY CHEVRON TYPE MIST ELIMINATORS.  NO REHEAT IS EMPLOYED.  A 400
FT COLE BRAND CXL2000 LINED STACK IS IN USE. THE SYSTEM OPERATES IN AN
OPEN WATER LOOP MODE AND WASTE MATERIAL IS DISPOSED OF IN OFF-SITE
SLUDGE PONDS. OPERATIONS COMMENCED IN AUGUST 1978.
ARIZONA  ELECTRIC  POWER
APACHE
3
NEW        195  MW  (GROSS)
            98  MW  (ESC)
COAL
   .70 XS  SUBBITUMINOUS
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION:   4.IX
STATUS 1    STARTUP 6/79
APACHE 3 OF ARIZONA ELECTRIC POWER COOP IS A DRY BOTTOM, PULVERIZED COAL
FIRED UNIT IN COCHISE, ARIZONA. LOW (0.70X) SULFUR SUBBITUMINOUS COAL WITH
AN AVERAGE HEATING VALUE OF 10,000 BTU/LB PRODUCES A MAXItflJM FLUE GAS FLOW
OF 735,000 ACFM. HALF OF THE FLUE GAS PASSES THROUGH A HOT SIDE ESP TO TWO
RESEARCH COTTRELL PACKED TOWERS, WHERE LIMESTONE IS USED TO REMOVE 85X OF
THE S02. THE GAS EXITS A HORIZONTAL CHEVRON MIST ELIMINATOR INTO ITS OUN
CEILCOTE LINED FLUE IN THE 400 FOOT STACK IT SHARES WITH UNIT 2. THE FGD
SYSTEM WHICH HAS BEEN OPERATIONAL SINCE JUNE OF 1979, USES NO REHEAT. THE
SYSTEM OPERATES IN AN OPEN WATER LOOP AND SLUDGE IS DISPOSED OF IN TWO OFF
SITE LINED PONDS WITH 20 YEARS EXPECTED LIFESPAN. TWO ADDITIONAL PONDS ARE
PLANNED, WHICH WOULD ADD ANOTHER 20 YEARS OF DISPOSAL CAPACITY.
ARIZONA  PUBLIC  SERVICE
CHOLLA
1
RETROFIT  119 MW (GROSS)
           119 MW (ESC)
COAL
   .50 XS  BITUMINOUS
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION:   3.4X
STATUS 1     STARTUP 10/73
ARIZONA PUBLIC SERVICE'S CHOLLA 1 IS LOCATED IN JOSEPH CITY, ARIZONA AND
IS A TANGENTIALLY FIRED, WET BOTTOM PULVERIZED COAL UNIT. IT IS FUELED BY
BITUMINOUS COAL THAT HAS A SULFUR CONTENT OF 0.5X AND A HEATING VALUE OF
10,150 BTU/LB. PARTICULATE MATTER IS CONTROLLED BY TWO FLOODED DISC SCRUB-
BERS. THE FGD SYSTEM STARTED UP IN OCTOBER, 1973 AND IS NOW OPERATIONAL.
S02 IS CONTROLLED BY ONE TOWER WITH HUNTERS PACKING EMPLOYING A LIMESTONE
ABSORBENT.  THE UNIT, SUPPLIED BY RESEARCH COTTRELL, HAS A DESIGN S02 RE-
REMOVAL EFFICIENCY OF 92X.  CHEVRON MIST ELIMINATORS ARE LOCATED PRIOR TO
AN IN-LINE STEAM REHEAT SYSTEM. THE TREATED FLUE GAS IS VENTED TO A 250 FT
ACID BRICK LINED STACK.  THE SYSTEM OPERATES IN AN OPEN WATER LOOP MODE
AND THE UNTREATED WASTE IS DISPOSED OF IN AN ON-SITE UNLINED POND.
ARIZONA  PUBLIC  SERVICE
CHOLLA
2
NEW        285 MW  (GROSS)
           285 MW  (ESC)
COAL
   .50 XS  BITUMINOUS
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION:   5.3X
STATUS 1    STARTUP  4/78
CHOLLA 2 OF ARIZONA PUBLIC SERVICE IS  LOCATED IN JOSEPH CITY, ARIZONA. THE
BOILER BURNS PULVERIZED BITUMINOUS COAL  (0.5X S, 10,150 BTU/LB). MECHANI-
CAL COLLECTORS PROVIDE INITIAL PARTICULATE CONTROL.  FOUR PARALLEL
FLOODED DISC AND PACKED TOWER S02 ABSORBER TRAINS  (THREE ARE REQUIRED FOR
FULL  LOAD) PROVIDE PRIMARY PARTICULATE AND S02 CONTROL.  THE DESIGN S02
REMOVAL FOR THE SYSTEM, WHICH BEGAN OPERATIONS IN  APRIL, 1978, IS 75X.
THE CLEANED GAS PASSES THROUGH AN IN-LINE STEAM REHEATER INTO A 550 FOOT
ACID  BRICK LINED STACK.  SLUDGE FROM THE OPEN WATER  LOOP SYSTEM IS
DEPOSITED IN A FLY ASH POND.
                                              2-1

-------
UTILITY FGD SURVEY'- OCTOBER 1983 - SEPTEMBER
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
ARIZONA PUBLIC SERVICE
CHOLLA
4
NEW       375 MW (GROSS)
          126 MW (ESC)
COAL
   .50 XS
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION: ****X
STATUS 1     STARTUP  3/81
CHOLLA 4 OF ARIZONA PUBLIC SERVICE IS LOCATED IN JOSEPH  CITY,  ARIZONA.
THE PULVERIZED COAL (0.5X S, 10150 BTU/LB) FIRED BOILER  EXHAUSTS FLUE
GAS THROUGH AN ESP TO A DOUBLE LOOP COMBINATION TOWER  (RESEARCH-COTTRELL
DESIGN) WHICH TREATS 36X OF THE GAS WITH LIMESTONE.  OPERATIONS COMMENCED
IN MARCH, 1981.
ARIZONA PUBLIC SERVICE
CHOLLA
5
NEW        375 MW  (GROSS)
           126 MW  (ESC)
COAL
   .50 XS
PROCESS NOT  SELECTED
VENDOR NOT SELECTED
ENERGY CONSUMPTION: «**«X
STATUS 6     STARTUP   0/97
ARIZONA PUBLIC SERVICE HAS PLANS FOR A NEW UNIT, CHOLLA  5,  TO  BE  LOCATED
IN JOSEPH CITY, ARIZONA.  THE 375 MW (GROSS) PULVERIZED  COAL (10150 BTU/LB
13.5X S) FIRED BOILER SUPPLIED BY COMBUSTION ENGINEERING WILL  EMPLOY AN
FGD SYSTEM FOR CONTROL OF 502 EMISSIONS.  START-UP  IS  SCHEDULED  FOR 1997.
 ARIZONA PUBLIC SERVICE
 FOUR CORNERS
 1
 RETROFIT  195 MW (GROSS)
           195 MW (ESC)
 COAL
   .75 XS  SUBBITUMINOUS
 LIME/ALKALINE FLYASH
 GE ENVIRONMENTAL SERVICES
 ENERGY CONSUMPTION:   2.6X
 STATUS 1     STARTUP 11/79
ARIZONA PUBLIC SERVICE HAS UPGRADED THE OPERATIONAL  PARTICULATE  SCRUBBERS
AT FOUR CORNERS 1, 2, AND 3 IN FRUITLAND, NEW MEXICO TO HANDLE ADDITIONAL
S02 REMOVAL. THE  FRONT FIRED, DRY BOTTOM, PULVERIZED COAL (SUB-
BITUMINOUS, 0.75X S, 8600 BTU/LB) UNITS 1 AND 2  SUPPLY  814,000 ACFM  EACH
INTO 2 GEESI VENTURI SCRUBBERS PER UNIT FOR  PRIMARY  PARTICLE  CONTROL
AND APPROXIMATELY 30X S02 REMOVAL USING ALKALINE FLY ASH.  THE DESIGN 502
REMOVAL EFFICIENCY SINCE THE CONVERSION TO LIME  AND  ALKALINE  FLY ASH
SCRUBBING IS 67;5X.  THE SYSTEM OPERATES IN AN OPEN WATER LOOP MODE AND
FLUE GAS EXITS A  250 FOOT STACK.  OPERATIONS COMMENCED  IN NOVEMBER 1979.
 ARIZONA PUBLIC SERVICE
 FOUR CORNERS
 2
 RETROFIT  195 MW (GROSS)
           195 MW (ESC)
 COAL
   .75 XS  SUBBITUMINOUS
 LIME/ALKALINE FLYASH
 GE ENVIRONMENTAL SERVICES
 ENERGY CONSUMPTION:  2.6X
 STATUS 1     STARTUP 11/79
ARIZONA  PUBLIC SERVICE HAS UPGRADED THE OPERATIONAL  PARTICULATE SCRUBBERS
AT  FOUR  CORNERS 1,2, AND  3 IN FRUITLAND, NEW  MEXICO  TO HANDLE ADDITIONAL
502 REMOVAL.  THE  FRONT FIRED, DRY BOTTOM,  PULVERIZED COAL (SUB-
BITUMINOUS,  0.75X S, 8600 BTU/LB) UNITS 1  AND 2  SUPPLY 614,000 ACFM EACH
INTO  2 GEESI  VENTURI SCRUBBERS  PER UNIT FOR PRIMARY  PARTICLE CONTROL
AND APPROXIMATELY 30X S02 REMOVAL USING ALKALINE FLY ASH. THE DESIGN SOS
REMOVAL  EFFICIENCY SINCE  THE CONVERSION TO LIME  AND  ALKALINE FLY ASH
SCRUBBING  IS  67.5X. THE SYSTEM  OPERATES IN AN OPEN WATER LOOP MODE AND
FLUE  GAS EXITS A  250 FOOT STACK.  OPERATIONS  COMMENCED IN NOVEMBER 1979.
 ARIZONA PUBLIC SERVICE
 FOUR CORNERS
 3
 RETROFIT  225 MW (GROSS)
           225 MW (ESC)
 COAL
   .75 XS  SUBBITUMINOUS
 LIME/ALKALINE FLYASH
 GE ENVIRONMENTAL SERVICES
 ENERGY CONSUMPTION: ****X
 STATUS 1     STARTUP 11/79
 ARIZONA  PUBLIC  SERVICE  HAS  UPGRADED  THE  OPERATIONAL PARTICULATE SCRUBBERS
 AT  FOUR  CORNERS 1,2,  AND  3  IN FRUITLAND, NEW MEXICO TO HANDLE ADDITIONAL
 S02 REMOVAL.  THE FRONT  FIRED, DRY BOTTOM,  PULVERIZED COAL (SUBBITUMINOUS,
 0.75X S, 8600 BTU/LB) UNIT  3 SUPPLIES 1,030,000 ACFM INTO 2 GEESI VENTUPI
 SCRUBBERS PER UNIT FOR  PRIMARY PARTICLE  CONTROL AND APPROXIMATELY 30X S02
 REMOVAL  USING ALKALINE  FLY  ASH.  THE  DESIGN 502 REMOVAL EFFICIENCY SINCE
 THE CONVERSION  TO LIME  AND  ALKALINE  FLY  ASH SCRUBBING IS 67 5X  THE SYSTEH
 OPERATES IN AN  OPEN WATER LOOP MODE  AND  FLUE GAS EXITS A 250 FOOT STACK.
 OPERATIONS COMMENCED IN NOVEMBER 1979.
 ARIZONA PUBLIC SERVICE
 FOUR CORNERS
 4
 RETROFIT  745 MW (GROSS)
           745 MW (ESC)
 COAL
   .75 XS  SUBBITUMINOUS
 LIME
 BABCOCK t WILCOX
 ENERGY CONSUMPTION: ##**X
 STATUS 2     STARTUP 10/64
 ARIZONA PUBLIC SERVICE'S FOUR CORNERS 4 AND 5 RETROFIT FGD SYSTEMS ARE
 UNDER CONSTRUCTION IN FARMINGTON,  NEW MEXICO.  THE 745 MW (GROSS) UNITS
 WILL BURN SUBBITUMINOUS COAL (0.75X S, 8650 BTU/LB) AND WILL EACH EMPLOY
 A BABCOCK t WILCOX WET LIME FGD SYSTEM FOR S02 CONTROL   FABRIcVlLTERS
 WILL BE USED FOR CONTROL OF PARTICULATE MATTER.  THE UNIT WILL SUPPLY
 560,000 ACFM TO EACH OF 10 ABSORBER MODULES WITH AN OVERALL DESIGN S02
 REMOVAL EFFICIENCY OF 90X.  INITIAL START-UP IS SCHEDULED FOR OCTOBER
 1984.
                                              2-2

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
ARIZONA PUBLIC SERVICE
FOUR CORNERS
5
RETROFIT  745 MW (GROSS)
          745 MW (ESC)
COAL
  .75 XS  SUBBITUMINOUS
LIME
BABCOCK & MILCOX
ENERGY CONSUMPTION: ****X
STATUS 2     STARTUP 10/84
ARIZONA PUBLIC SERVICE'S FOUR CORNERS 4 AND 5 RETROFIT FGD SYSTEMS ARE
UNDER CONSTRUCTION IN FARMINGTON, NEW MEXICO.  THE 745 MW (GROSS)  UNITS
WILL BURN SUBBITUMINOUS COAL (0.75X S, 8650 BTU/LB) AND WILL EACH  EMPLOY
A BABCOCK t WILCOX WET LIME FGD SYSTEM FOR S02 CONTROL.  FABRIC FILTERS
WILL BE USED FOR CONTROL OF PARTICULATE MATTER.  THE UNIT WILL SUPPLY
560,000 ACFM TO EACH OF 10 ABSORBER MODULES WITH AN OVERALL DESIGN 502
REMOVAL EFFICIENCY OF 90X.  INITIAL START-UP IS SCHEDULED FOR OCTOBER
1984.
ASSOCIATED ELECTRIC
THOMAS HILL
3
NEW       730 MW (GROSS)
          670 MW (ESC)
COAL
 4.80 XS
LIMESTONE
M.W. KELLOGG
ENERGY CONSUMPTION: *#*»X
STATUS 1     STARTUP 10/82
THOMAS HILL 3 OF ASSOCIATED ELECTRIC COOP IS A PULVERIZED  COAL (4.8X S,
10,500 BTU/LB) FIRED UNIT LOCATED IN MOBERLY, MISSOURI.  TWO COLD  SIDE
ESP'S PRECEDE THE FOUR 91.5X EFFICIENT M. W. KELLOGG HORIZONTAL
WEIR FGD MODULES USING MAG-PROMOTED LIMESTONE AS THE ABSORBENT. THE
CLEANED GAS PASSES THROUGH A VERTICAL CHEVRON MIST ELIMINATOR  TO  A 650
FOOT BRICK LINED STACK. REHEAT IS ACCOMPLISHED BY FLUE GAS BYPASS.  THE
FIXATED SLUDGE IS TRUCKED TO AN ACTIVE STRIP MINE. THE SYSTEM  OPERATES
IN A CLOSED WATER LOOP. THE FGD SYSTEM HAS BEEN OPERATIONAL SINCE OCTOBER
1982.
ATLANTIC CITY ELECTRIC
CUMBERLAND
1
NEW       330 MW  (GROSS)
          330 MW  (ESC)
COAL
 3.25 XS  BITUMINOUS
LIMESTONE
VENDOR NOT SELECTED
ENERGY CONSUMPTION: ****X
STATUS 6     STARTUP  99/99
CUMBERLAND 1 IS A PULVERIZED COAL (3.25X S) FIRED BOILER TO BE LOCATED  IN
MILVILLE, NEW JERSEY.  THE UTILITY IS CONSIDERING A LIMESTONE
FGD SYSTEM WITH NO BYPRODUCT RECOVERY FOR S02 CONTROL.  START-UP FOR  THE
UNIT HAS BEEN DEFERRED INDEFINITELY.
BASIN  ELECTRIC  POWER
ANTELOPE VALLEY
1
NEW       440 MW  (GROSS)
          440 MW  (ESC)
COAL
   .68  XS  LIGNITE
LIME/SPRAY  DRYING
JOY MFG/NIRO ATOMIZER
ENERGY CONSUMPTION: «K**X
STATUS 1     STARTUP  5/83
ANTELOPE VALLEY 1 OF BASIN ELECTRIC POWER IS A PULVERIZED COAL (0.68X S,
6600 BTU/LB LIGNITE) FIRED UNIT LOCATED IN BEULAH, NORTH DAKOTA.  THE
BOILER FEEDS 2,055,000 ACFM OF FLUE GAS TO A LIME/SPRAY DRYING SYSTEM
SUPPLIED BY JOY MFG/NIRO ATOMIZER.  THE 62X EFFICIENT SYSTEM CONSISTS OF
FIVE NIRO ATOMIZER SPRAY DRYERS FOLLOWED BY TWO JOY MFG BAGHOUSES.  THE
CLEANED GAS, ALONG WITH A 4X BYPASS REHEAT, EXIT A 600 FOOT PVC LINED
STACK.  THE SYSTEM OPERATES IN AN OPEN WATER LOOP AND THE SLUDGE IS USED
FOR LANDFILL IN A COAL MINE.  INITIAL OPERATIONS COMMENCED IN
MAY, 1983.
BASIN  ELECTRIC  POWER
ANTELOPE  VALLEY
2
NEW        440 MW (GROSS)
           440 MW (ESC)
COAL
   .68  XS   LIGNITE
LIME/SPRAY DRYING
JOY MFG/NIRO ATOMIZER
ENERGY CONSUMPTION: ****X
STATUS 2     STARTUP 11/85
ANTELOPE VALLEY 2 OF BASIN ELECTRIC POWER COOP IS UNDER CONSTRUCTION IN
BEULAH, NORTH DAKOTA. JOY/NIRO WAS AWARDED A CONTRACT FOR THIS LIGNITE
(0.68Z S, 6600 BTU/LB) FIRED UNIT.  A LIME/SPRAY DRYING FGD SYSTEM ANT)
FABRIC FILTERS WILL BE EMPLOYED FOR S02 AND PARTICULATE CONTROL.
THE SYSTEM WILL OPERATE IN AN OPEN WATER LOOP MODE AND BE REQUIRED
TO COMPLY WITH STATE EMISSIONS STANDARDS VIA BEST AVAILABLE CONTROL TECH-
NOLOGY.  START-UP IS SCHEDULED FOR NOVEMBER, 1985.
BASIN  ELECTRIC  POWER
ANTELOPE VALLEY
3
NEW        560 MW (GROSS)
           560 MW (ESC)
LIGNITE
   .68  XS
LIME/SPRAY DRYING
VENDOR NOT SELECTED
ENERGY CONSUMPTION: *«**X
STATUS 6     STARTUP  0/92
ANTELOPE VALLEY 3 OF BASIN ELECTRIC POWER IS A PLANNED 560 MW (GROSS)
LIGNITE FIRED BOILER TO BE LOCATED IN BEULAH, NORTH DAKOTA.  THE UTILITY
IS PRESENTLY INVESTIGATING LIME/SPRAY DRYING AS THE POSSIBLE EMISSION
CONTROL STRATEGY.  START-UP IS EXPECTED IN 1992.
                                              2-3

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
BASIN ELECTRIC POWER
LARAMIE RIVER
1
NEW       570 MW (GROSS)
          570 MW (ESC)
COAL
  .54 XS  SUBBITUMINOUS
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION:   .9X
STATUS 1     STARTUP  7/80
BASIN ELECTRIC POWER COOP'S LARAMIE RIVER 1 IS A PULVERIZED COAL
(0.54X S, 8400 BTU/LB) FIRED UNIT LOCATED IN WHEATLAND, WYOMING.
THE BOILER FEEDS 2,300,000 ACFM OF FLUE GAS THROUGH A COLD SIDE
ESP TO FIVE RESEARCH COTTRELL LIMESTONE PACKED TOWER MODULES, WHICH
REMOVE 90X OF THE S02. THE CLEANED GAS EXITS FROM A VERTICAL CHEVRON
MIST ELIMINATOR INTO A 600 FOOT ACID BRICK LINED STACK.  NO REHEAT IS
USED.  THE FLYASH STABLIIZED SLUDGE IS DEWATERED TO 83X SOLIDS BEFORE
BEING LANDFILLED, AND THE SYSTEM EMPLOYS A CLOSED WATER LOOP. OPERATIONS
BEGAN ON JULY 1, 1980.
BASIN ELECTRIC POWER
LARAMIE RIVER
Z
NEW       570 MW (GROSS)
          570 MW (ESC)
COAL
   .54 XS  SUBBITUMINOUS
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION: ****X
STATUS 1     STARTUP  7/81
BASIN ELECTRIC POWER COOP'S LARAMIE RIVER 2 IS A NEW UNIT LOCATED
IN WHEATLAND, WYOMING. THE PULVERIZED SUBBITUMINOUS COAL (0.54X S, 8400
BTU/LB) FIRED BOILER FEEDS 2,300,000 ACFM OF FLUE GAS THROUGH A COLD SIDE
ESP TO FIVE RESEARCH-COTTRELL LIMESTONE PACKED TOWER MODULES, WHICH
REMOVE 90X OF THE S02. THE CLEANED GAS EXITS FROM A VERTICAL CHEVRON
MIST ELIMINATOR INTO A 600 FOOT ACID BRICK LINED STACK.  NO REHEAT IS
USED.  THE FLYASH FIXATED SLUDGE IS DEWATERED TO 83X SOLIDS BEFORE
BEING LANDFILLED IN THIS CLOSED WATER LOOP SYSTEM. START-UP TOOK PLACE
IN JULY 1981.
BASIN ELECTRIC POWER
LARAMIE RIVER
3
NEW       570 MW (GROSS)
          570 MW (ESC)
COAL
   .54 XS  SUBBITUMINOUS
LIME/SPRAY DRYING
BABCOCK t WILCOX
ENERGY CONSUMPTION: ****X
STATUS 1     STARTUP 11/82
LARAMIE RIVER 3 OF BASIN ELECTRIC POWER COOP IS A NEW UNIT LOCATED IN
WHEATLAND, WYOMING.  IT UTILIZES FOUR BABCOCK & WILCOX LIME SPRAY DRIERS
AND A COLD SIDE ESP. THE BOILER FIRES PULVERIZED COAL (0.54X S,
8400 BTU/LB) AND SUPPLYS 2,800,000 ACFM OF FLUE GAS TO THE FGD
SYSTEM, WHICH REMOVES 85X OF THE S02 BEFORE THE GAS EXITS THROUGH
A 600 FOOT FIBER-REINFORCED POLYESTER LINED STACK.  A 3X BYPASS IS USED
FOR REHEAT. THE SYSTEM OPERATES IN AN OPEN WATER LOOP, AND THE DRY POWDER
WASTE IS LANDFILLED.
BIG RIVERS ELECTRIC
D.B. WILSON
1
NEW       440 MW  (GROSS)
          440 MW  (ESC)
COAL
 3.75 XS  BITUMINOUS
LIME
M.W. KELLOGG
ENERGY CONSUMPTION: ****X
STATUS 1     STARTUP  9/64
BIG RIVERS ELECTRIC'S D.B. WILSON 1 IS A NEW UNIT LOCATED IN CENTERTOWN,
KENTUCKY.  THE PULVERIZED BITUMINOUS COAL (3.75X S) FIRED FOSTER WHEEL-
ER BOILER HAS A GROSS MW RATING OF 440.  A COLD SIDE ESP IS EMPLOYED FOR
PARTICULATE CONTROL AND SLUDGE IS TREATED VIA FORCED OXIDATION.  THE M. W.
KELLOG WET LIME FGD SYSTEM AT UNIT 1 BEGAN INITIAL OPERATIONS IN SEPTEMBER
1984.
BIG RIVERS ELECTRIC
GREEN
1
NEW       242 MW  (GROSS)
          242 MW  (ESC)
COAL
 3.91 XS  BITUMINOUS
LIME
AMERICAN AIR FILTER
ENERGY CONSUMPTION'- ****X
STATUS 1     STARTUP 12/79
UNIT 1 OF BIG RIVERS ELECTRIC'S GREEN STATION IS LOCATED IN
SEBREE,KENTUCKY. THE DRY BOTTOM PULVERIZED COAL (3.91X S,  9600 BTU/LB)
FIRED BOILER SUPPLIES 1,000,000 ACFM TO A COLD SIDE ESP FOLLOWED BY
TWO AMERICAN AIR FILTER LIME SPRAY TOWERS WHICH REMOVE 90X OF THE
S02. THE CLEANED GAS PASSES THROUGH A CHEVRON MIST ELIMINATOR AND
EXITS A 350 FT SAUERISEN 72 LINED STACK AFTER IT IS HEATED BY A STEAM COIL
REHEATER. THE SLUDGE FROM THE CLOSED WATER LOOP SYSTEM IS  POZ-0-TEC
STABILIZED. OPERATIONS COMMENCED IN DECEMBER 1979
BIG  RIVERS  ELECTRIC
GREEN
2
NEW       242 MW  (GROSS)
          242 MW  (ESC)
COAL
 3.91 XS  BITUMINOUS
LIME
AMERICAN AIR FILTER
ENERGY CONSUMPTION: #*#*X
STATUS 1     STARTUP 11/80
UNIT 2 OF BIG RIVERS ELECTRIC'S GREEN STATION IS  LOCATED  IN SEBREE,
KENTUCKY. THE DRY BOTTOM PULVERIZED COAL  (3.91X S,  9800 BTU/LB)
FIRED BOILER SUPPLIES 1,000,000 ACFM TO A COLD SIDE ESP FOLLOWED BY
TWO AMERICAN AIR FILTER LIME SPRAY TOWERS WHICH REMOVE 90X OF THE
S02. THE CLEANED GAS PASSES THROUGH A CHEVRON MIST  ELIMINATOR AND
EXITS A 350 FT SAUERISEN 72 LINED STACK AFTER IT  IS HEATED BY A  STEAM COIL
REHEATER. THE SLUDGE FROM THE CLOSED WATER  LOOP SYSTEM IS POZ-0-TEC
STABILIZED. OPERATIONS COMMENCED IN NOVEMBER 1980
                                             2-4

-------
                                                  UTILITY FED SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
BOSTON EDISON
NEW BOSTON
1
NEW       388 MM (GROSS)
          388 MM (ESC)
COAL
 2.30 XS  SUBBITUMINOUS
LIMESTONE
VENDOR NOT SELECTED
ENERGY CONSUMPTION: *«*«X
STATUS 5     STARTUP 10/87
NEW BOSTON 1 AND 2 OF BOSTON EDISON ARE TWO OIL TO COAL CONVERSION UNITS
LOCATED IN BOSTON MASSACHUSETTS.   THE 388 MW (GROSS)  BABCOCK AND  WILCOX
UNITS WILL FIRE SUBBITUMINOUS COAL (12,600 BTU/LB, 2.3X S).   BIDS ARE
CURRENTLY BEING REQUESTED/EVALUATED FOR A WET LIMESTONE FGD  SYSTEM WITH
GYPSUM GENERATED AS A SALEABLE BYPRODUCT.  ESP'S WILL PROVIDE PARTICULATE
CONTROL AND FLUE GAS WILL EXIT A  359 FT ACID BRICK LINED STACK.   FORCED
OXIDATION WILL BE UTILIZED FOR SLUDGE TREATMENT.  UNIT 1 IS  SCHEDULED
TO START UP IN OCTOBER, 1987 AND  UNIT 2 IN JUNE, 1988.
BOSTON EDISON
NEW BOSTON
2
NEW       388 MW (GROSS)
          388 MW (ESC)
COAL
 2.30 XS  SUBBITUMINOUS
LIMESTONE
VENDOR NOT SELECTED
ENERGY CONSUMPTION: «**«X
STATUS 5     STARTUP  6/88
NEW BOSTON 1 AND 2 OF BOSTON EDISON ARE TWO OIL TO COAL CONVERSION  UNITS
LOCATED IN BOSTON MASSACHUSETTS.   THE 388 MW (GROSS)  BABCOCK  AND  WILCOX
UNITS WILL FIRE SUBBITUMINOUS COAL (12,600 BTU/LB, 2.3X S).   BIDS ARE
CURRENTLY BEING REQUESTED/EVALUATED FOR A WET LIMESTONE FGD SYSTEM  WITH
GYPSUM GENERATED AS A SALEABLE BY PRODUCT.  ESP'S WILL PROVIDE  PARTICULATE
CONTROL AND FLUE GAS WILL EXIT A 359 FT ACID BRICK LINED STACK.   FORCED
OXIDATION WILL BE UTILIZED FOR SLUDGE TREATMENT.  UNIT 1 IS SCHEDULED
TO START UP IN OCTOBER, 1987 AND UNIT 2 IN JUNE, 1988.
CAJUN ELECTRIC POWER
OXBOW
1
NEW       540 MW (GROSS)
          540 MW (ESC)
COAL
   .60 XS  LIGNITE
LIME/SPRAY DRYING
JOY MFG/NIRO ATOMIZER
ENERGY CONSUMPTION: ****x
STATUS 3     STARTUP 99/99
CAJUN ELECTRIC HAS PLANS TO CONSTRUCT A 540 MW UNIT,  OXBOW 1,  TO BE  LOCAT-
ED IN DE SOTO PARISH, LOUISIANA.  THE UTILITY HAS AWARDED A CONTRACT TO
JOY MANUFACTURING/NIRO ATOMIZER FOR A LIME/SPRAY DRYING FGD SYSTEM TO
CONTROL S02 EMISSIONS FROM THE PULVERIZED COAL (.6X S,  6750 BTU/LB)  FIRED
BOILER.  THE UNIT HAS BEEN DEFERRED INDEFINITELY.
CENTRAL ILLINOIS  LIGHT
DUCK CREEK
1
NEW       416 MW  (GROSS)
          416 MW  (ESC)
COAL
 3.40 XS  BITUMINOUS
LIMESTONE
ENVIRONEERING, RILEY STOKER
ENERGY CONSUMPTION:  2.9X
STATUS 1     STARTUP  7/76
DUCK CREEK 1 OF CENTRAL ILLINOIS LIGHT IS LOCATED IN CANTON,  ILLINOIS.  THE
BALANCED DRAFT, FRONT FIRED, DRY BOTTOM UNIT BURNS PULVERIZED BITUMINOUS
COAL (3.40X S, 10,396 BTU/LB) AND SUPPLIES 2,415,000 ACFM OF  FLUE GAS TO
TWO COLD SIDE ESP'S FOLLOWED BY FOUR RILEY STOKER/ENVIRONEERING ROD DECK
SPRAY TOWER MODULES. THE LIMESTONE FGD SYSTEM HAS BEEN OPERATIONAL (AT
LEAST ONE MODULE) SINCE JULY, 1976. IT IS DESIGNED TO REMOVE  65X OF THE
S02.  HORIZONTAL CHEVRON MIST ELIMINATORS FOLLOW THE ABSORBERS, AND THE
CLEANED GAS EXITS TO A 500 FOOT CEILCOTE LINED STACK WITHOUT  REHEAT.
SLUDGE FROM THE CLOSED WATER LOOP SYSTEM IS DIPOSED OF IN AN  ON-SITE CLAY
LINED POND.
CENTRAL  ILLINOIS  PUBLIC SERV
NEWTON
1
NEW       617 MW  (GROSS)
          617 MW  (ESC)
COAL
 3.00 XS BITUMINOUS
DUAL ALKALI
GE ENVIRONMENTAL  SERVICES
ENERGY CONSUMPTION:   2.4X
STATUS 1    STARTUP  9/79
NEWTON 1 OF CENTRAL ILLINOIS PUBLIC SERVICE IS A TANGENTIALLY FIRED, DRY
BOTTOM, PULVERIZED BITUMINOUS COAL (3.00X S, 10,900 BTU/LB) FIRED UNIT
LOCATED IN NEWTON, ILLINOIS. A COLD SIDE ESP RECEIVES 2,163,480 ACFM
OF FLUE GAS AND FEEDS IT TO FOUR GEESI POLYSPHERE PACKED TRAY TOWER
ABSORBERS FOLLOWED BY TWO VERTICAL MIST ELIMINATORS PER MODULE. THE
CLEANED GAS IS BOOSTED 25 DEG F BY A COMBINATION OF TWO DIFFERENT TYPES
OF IN-LINE REHEATERS PLUS BYPASS REHEAT, AND THEN EXITS A 530 FOOT
PRECRETE-LINED STACK. THE WATER LOOP IS CLOSED, AND THE SLUDGE IS
POZ-0-TEC TREATED.  OPERATIONS COMMENCED IN SEPTEMBER, 1979.
CENTRAL MAINE  POWER
SEARS ISLAND
1
NEW       600  MW  (GROSS)
          600  MW  (ESC)
COAL
 2.23 XS  BITUMINOUS
PROCESS NOT SELECTED
VENDOR NOT SELECTED
ENERGY CONSUMPTION: ****X
STATUS 6     STARTUP  11/95
SEARS ISLAND 1 IS A PLANNED UNIT TO BE BUILT ON PENOBSCOT BAY BY CENTRAL
MAINE POWER. BECAUSE OF THE DISCOVERY OF A GEOLOGICAL FAULT ON SEARS
ISLAND, PLANS FOR A 1150 MW NUCLEAR POWER PLANT HAVE BEEN REPLACED WITH
PLANS FOR A 600 MW COAL (2.23X S, 12,500 BTU/LB) FIRED PLANT. LIME AND
LIMESTONE SCRUBBING ARE THE PRIMARY METHODS BEING CONSIDERED FOR COMPLI-
ANCE WITH THE NSPS.  IT WILL BE TWO YEARS BEFORE ALL PERMITS REQUIRED HAVE
BEEN RECEIVED.  START UP IS SCHEDULED FOR NOVEMBER 1995.
                                              2-5

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                       ABSTRACT
CENTRAL POWER 4 LIGHT
COLETO CREEK
2
NEW       720 MW  (GROSS)
          720 MW  (ESC)
COAL
   .39 7.5  SUBBITUMINOUS
LIME/SPRAY DRYING
JOY MFG/NIRO ATOMIZER
ENERGY CONSUMPTION: ****X
STATUS 3     STARTUP 10/93
                     COLETO  CREEK  2  OF  CENTRAL POWER  AND  LIGHT  IS A COAL SUBBITUMINOUS (.39-
                     .60X  S) FIRED UNIT PLANNED FOR CONSTRUCTION IN FANNIN,  TEXAS.   A CONTRACT
                     HAS BEEN AWARDED TO JOY  MFG/NIRO ATOMIZER  FOR A LIME/SPRAY DRYING FGD  SYS-
                     TEM ON  THIS UNIT.   PARTICULATE MATTER  WILL BE CONTROLLED VIA A RIGID FRAME
                     COLD  SIDE ESP.  THE BOILER WILL  BE SUPPLIED BY COMBUSTION ENGINEERING  AW
                     FLUE  GAS WILL EXIT THROUGH A 450 FOOT  STACK.  SLUDGE WILL BE DISPOSED  OF
                     IN A  LANDFILL.  THE UNIT WILL BY CENTRAL AND SOUTHWEST SERVICES, BUT WILL
                     BUT WILL BE OPERATED BY  CENTRAL  POWER  & LIGHT.  START UP IS TENTATIVELY
                     SCHEDULED FOR OCTOBER 1993..1993.
 CINCINNATI  GAS  &  ELECTRIC
 EAST  BEND
 1
 NEW      650 MW  (GROSS)
          650 MW  (ESC)
 COAL
 4.00 XS
 PROCESS NOT SELECTED
 VENDOR NOT  SELECTED
 ENERGY CONSUMPTION:   2.9/C
 STATUS 6     STARTUP   0/89
                     CINCINNATI  GAS  AND  ELECTRIC  HAS PLANS FOR A NEW UNIT,  EAST BEND 1,  TO BE
                     LOCATED  ADJACENT TO EAST  BEND  2 AT THE RABBIT HASH,  KENTUCKY SITE.   THE
                     COAL (4.00X S)  FIRED BOILER  WILL HAVE A GENERATING CAPACITY OF 650  MW AND
                     FLUE GAS WILL EXIT  THROUGH A 650 FT STACK.  THE SYSTEM WILL OPERATE IN A
                     CLOSED WATER LOOP MODE.   START-UP IS SCHEDULED FOR 1989.
 CINCINNATI GAS
 EAST BEND
 2
 NEW
                4 ELECTRIC
650 MW (GROSS)
650 MW (ESC)

BITUMINOUS
 COAL
  2.60 XS
 LIME
 BAECOCK i WILCOX
 ENERGY CONSUMPTION:   2.9X
 STATUS 1     STARTUP  3/81
EAST BEND 2 OF CINCINNATI GAS AND ELECTRIC IS A PULVERIZED COAL (2.60X S,
11,000 BTU/LB) FIRED BOILER LOCATED IN RABBIT HASH, KENTUCKY.  THE EMIS-
SION CONTROL SYSTEM CONSISTS OF A HOT-SIDE ESP FOLLOWED BY THREE BABCOCK
& WILCOX LIME FGD MODULES [67X S02 REMOVAL EFFICIENCY).  THE CLEANED GAS
PASSES THROUGH A CHEVRON MIST ELIMINATOR BEFORE BEING HEATED BY AN IN-
DIRECT AIR REHEATER AND EXITS THROUGH A BRICK LINED 650 FOOT STACK.  THE
SLUDGE FROM THIS CLOSED WATER LOOP IS POZ-0-TEC STABILIZED BEFORE DISPOSAL
IN AN ON-SITE LANDFILL. OPERATIONS COMMENCED IN MARCH 1981.
 CINCINNATI GAS & ELECTRIC
 ZIMMER
 1
 NEW      1386 MW (GROSS)
          1386 MW (ESC)
 COAL
  3.50 XS  SUBBITUMINOUS
 PROCESS NOT SELECTED
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION: «**«X
 STATUS 6     STARTUP  0/91
                     CINCINNATI GAS AND ELECTRIC HAS PLANS FOR A NUCLEAR TO COAL CONVERSION
                     UNIT LOCATED IN MOSCOW,  OHIO.   S02 EMISSIONS FROM THE 1386 MW (GROSS) COAL
                     FIRED BALANCED DRAFT BOILER WILL BE CONTROLLED WITH FGD.  INITIAL START-UP
                     IS TENTATIVELY SCHEDULED FOR 1991.
 COLORADO UTE ELECTRIC
 CRAIG
 1
 NEW       455 MW (GROSS)
           455 MW (ESC)
 COAL
   .45 XS  SUBBITUMINOUS
 LIMESTONE
 PEABODY PROCESS SYSTEMS
 ENERGY CONSUMPTION:  1.3X
 STATUS 1     STARTUP 10/80
                     THE COLORADO UTE ELECTRIC ASSN HAS CONSTRUCTED A NEW UNIT, CRAIG 1, LOCAT-
                     ED IN CRAIG, COLORADO.  CRAIG 1 FIRES PULVERIZED SUBBITUMINOUS COAL
                     (0.45X S, 10,000 BTU/LB).  THE EMISSION CONTROL SYSTEM FOR THIS UNIT CON-
                     SISTS OF A HOT SIDE ESP AND FOUR LIMESTONE SPRAY TOWERS (PEABODY PROCESS
                     SYSTEMS) FOR REMOVAL OF PARTICULATE MATTER AND 85X OF THE S02.  THE
                     SCRUBBER EXHAUST IS REHEATED BYPASS GAS AND PASSES THROUGH A 600 FOOT
                     ACID LINED STACK.  THE SYSTEM OPERATES IN A CLOSED MATER LOOP ANT) THE
                     STABILIZED SLUDGE IS DISPOSED OF IN AN OFF-SITE MINEFILL.  UNIT 1 HAS
                     BEEN OPERATING SINCE OCTOBER 1980.
 COLORADO UTE ELECTRIC
 CRAIG
 2
 NEW       455 MM (GROSS)
           455 MW (ESC)
 COAL
   .45 XS  SUBBITUMINOUS
 LIMESTONE
 PEABODY PROCESS SYSTEMS
 ENERGY CONSUMPTION:   1.3X
 STATUS 1     STARTUP 12/79
                     THE CRAIG 2 UNIT OF THE COLORADO UTE ELECTRIC ASSN IS LOCATED IN CRAIG,
                     COLORADO AND FIRES PULVERIZED SUBBITUMINOUS COAL (0.45XS, 10,000 BTU/LB).
                     THE EMISSION CONTROL SYSTEM FOR THIS UNIT CONSISTS OF A HOT SIDE ESP AND
                     FOUR PEABODY PROCESS SYSEMS LIMESTONE SPRAY TOWERS FOR REMOVAL OF PARTIC-
                     ULATE AND 85X OF THE S02.  THE SCRUBBER EXHAUST IS HEATED BY A BYPASS
                     REHEATER AND PASSES THROUGH A 600 FOOT ACID BRICK LINED STACK.  THE SYSTEM
                     OPERATES IN A CLOSED LOOP. AND THE STABILIZED SLUDGE IS DISPOSED OF IN AN
                     OFF-SITE MINEFILL.  START-UP OF UNIT 2 WAS IN DECEMBER 1979.
                                              2-6

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
COLORADO UTE ELECTRIC
CRAIG
3
NEW       447 MM (GROSS)
          447 MW (ESC)
COAL
  .45 XS  SUBBITUMINOUS
LIME/SPRAY DRYING
BABCOCK & MILCOX
ENERGY CONSUMPTION: »***X
STATUS 1     STARTUP  6/84
CRAIG 3 OF COLORADO UTE ELECTRIC ASSN.  IS LOCATED IN CRAIG,  COLORADO.
THE UNIT, SUPPLIED BY BABCOCK & MILCOX FIRES PULVERIZED SUBBITUUMINOUS
COAL (0.45X S, 10,000 BTU/LB). THE DRY SCRUBBING SYSTEM UTILIZING
LIME/SPRAY DRYING WITH A DESIGN REMOVAL EFFICIENCY OF 85X IS SUPPLIED  BY
BABCOCK AND WILCOX.  THE UNIT HAS A FABRIC FILTER FOR PARTICULATE MATTER B
CONTROL AND FLUE GAS EXITS A 600 FT STACK.  OPERATION OF THE FGD SYSTEM
COMMENCED IN JUNE 1984.
COLUMBUS S SOUTHERN OHIO ELEC
CONESVILLE
5
NEW       405 MM (GROSS)
          350 MM (ESC)
COAL
 4.50 XS  BITUMINOUS
LIME
AIR CORRECTION DIVISION, UOP
ENERGY CONSUMPTION:  1.7X
STATUS 1     STARTUP  1/77
CONESVILLE 5 OF COLUMBUS AND SOUTHERN OHIO ELECTRIC IS A DRY BOTTOM,
PULVERIZED BITUMINOUS COAL (4.SOX S, 10,850 BTU/LB) FIRED UNIT LOCATED
IN CONESVILLE, OHIO. A COLD SIDE ESP RECEIVES 1,393,893 ACFM OF  FLUE
GAS AND PASSES IT TO TWO THIOSORBIC LIME TCA MODULES SUPPLIED BY UOP.
THE S02 REMOVAL EFFICIENCY OF THE TWO MODULES, WHICH BEGAN INITIAL
OPERATION IN JANUARY 1977, IS 89.5X (DESIGN). EACH MODULE HAS ONE
BULK ENTRAINMENT SEPARATOR AND TWO CHEVRON MIST ELIMINATORS. THE
CLEANED GAS EXITS THROUGH AN 600 FOOT ACID BRICK LINED STACK. THE
POZ-0-TEC STABILIZED SLUDGE IS PUMPED INTO AN ON-SITE DIKED LAND-
FILL. THE SYSTEM OPERATES IN A CLOSED WATER LOOP.
COLUMBUS & SOUTHERN OHIO ELEC
CONESVILLE
6
NEW       405 MW  (GROSS)
          350 MW  (ESC)
COAL
 4.50 XS  BITUMINOUS
LIME
AIR CORRECTION DIVISION, UOP
ENERGY CONSUMPTION:   1.7X
STATUS 1     STARTUP  6/78
CONESVILLE 6 OF COLUMBUS AND SOUTHERN OHIO ELECTRIC IS A DRY BOTTOM,
PULVERIZED BITUMINOUS COAL (4.SOX S, 10,850 BTU/LB) FIRED UNIT LOCATED
IN CONESVILLE, OHIO. A COLD SIDE ESP RECEIVES 1,393,893 ACFM OF FLUE
GAS AND PASSES IT TO TWO THIOSORBIC LIME TCA MODULES SUPPLIED BY UOP.
THE SOS REMOVAL EFFICIENCY OF THE TWO MODULES, WHICH BEGAN INITIAL
OPERATION IN JUNE 1978, IS 89.5X (DESIGN). EACH MODULE HAS ONE
BULK ENTRAINMENT SEPARATOR AND TWO CHEVRON MIST ELIMINATORS. THE
CLEANED GAS EXITS THROUGH AN 800 FOOT ACID BRICK LINED STACK. THE
POZ-0-TEC STABILIZED SLUDGE IS PUMPED INTO AN ON-SITE DIKED LAND-
FILL. THE SYSTEM OPERATES IN A CLOSED WATER LOOP.
COOPERATIVE  POWER
N/D
1
NEW        750 MW (GROSS)
           750 MW (ESC)
COAL
***** XS
LIMESTONE
VENDOR NOT SELECTED
ENERGY CONSUMPTION: ****X
STATUS 6     STARTUP  0/94
COOPERATIVE POWER HAS PLANS TO CONSTRUCT A 750 MW (GROSS) UNIT IN OHIO.
THE FACILITY NAME HAS NOT YET BEEN DECIDED NOR HAS THE SITE LOCATION BEEN
FINALIZED.  THE UNIT IS EXPECTED TO FIRE OHIO COAL.  A WET LIMESTONE
FGD SYSTEM WILL BE EMPLOYED TO CONTROL S02 EMISSIONS AND PARTICLE MATTER
WILL BE CONTROLLED BY ESP'S.  INITIAL START-UP IS TENTATIVELY SCHEDULED
FOR 1994.
COOPERATIVE  POWER ASSOCIATION
COAL CREEK
1
NEW       550 MM (GROSS)
          327 MW (ESC)
COAL
   .63 XS  LIGNITE
LIME/ALKALINE FLYASH
COMBUSTION ENGINEERING
ENERGY CONSUMPTION:    ,2X
STATUS 1     STARTUP  7/79
COAL CREEK 1 AND 2, LOCATED IN UNDERWOOD, NORTH DAKOTA ARE TWO PULVERIZED
LIGNITE (0.63X S, 6258 BTU/LB) FIRED UNITS OWNED BY THE COOPERATIVE POWER
ASSN AND UNITED POWER.  A COLD SIDE ESP RECEIVES 2,200,000 ACFM OF FLUE
GAS AND EXHAUSTS IT TO FOUR COUNTERCURRENT SPRAY TOWERS SUPPLIED BY COM-
BUSTION ENGINEERING.  MIST ELIMINATION IS PROVIDED BY A BULK ENTRAINMENT
SEPARATOR AND TWO CHEVRON MIST ELIMINATORS.  A MINIMUM OF 40X BYPASS RE-
HEAT IS PROVIDED BEFORE THE CLEANED GAS EXITS A 658 FT ACID BRICK LINED
STACK.  THE LIME/ALKALINE FLYASH SYSTEM DESIGN S02 REMOVAL EFFICIENCY IS
90X.  IT OPERATES IN AN OPEN WATER LOOP, AND THE FLYASH FIXATED SLUDGE IS
DISPOSED OF IN A CLAY LINED POND.  UNIT 1 OPERATIONS BEGAN IN JULY 1979.
COOPERATIVE  POWER ASSOCIATION
COAL CREEK
2
NEW       550 MW (GROSS)
          327 MM (ESC)
COAL
   .63 XS  LIGNITE
LIME/ALKALINE FLYASH
COMBUSTION ENGINEERING
ENERGY CONSUMPTION:    .2X
STATUS 1     STARTUP  7/80
COAL CREEK 1 AND 2,  LOCATED IN UNDERWOOD, NORTH DAKOTA ARE TWO PULVERIZED
LIGNITE  (0.63X S, 6258 BTU/LB) FIRED UNITS OWNED BY THE COOPERATIVE POWER
ASSN AND UNITED POWER.  A COLD SIDE ESP RECEIVES 2,200,000 ACFM OF FLUE
GAS AND  EXHAUSTS IT  TO FOUR COUNTERCURRENT SPRAY TOWERS SUPPLIED BY COM-
BUSTION  ENGINEERING.  MIST ELININATION IS PROVIDED BY A BULK  ENTRAINMENT
SEPARATOR AND TWO CHEVRON MIST ELIMINATORS.  A MINIMUM OF 40X BYPASS RE-
HEAT IS  PROVIDED BEFORE THE CLEANED GAS EXITS A 658 FT ACID BRICK LINED
STACK.  THE LIME/ALKALINE FLYASH SYSTEM DESIGN S02 REMOVAL EFFICIENCY IS
90X.  IT OPERATES IN AN OPEN WATER LOOP, AND THE FLYASH STABILIZED SLUDGE
IS DISPOSED OF IN A  CLAY LINED POND.  UNIT 2 COMMENCED OPERATIONS IN JULY,
1980.
                                              2-7

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION  2
                                       STATUS OF  FGD  SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
DELMARVA POWER & LIGHT
DELAWARE CITY
1
RETROFIT   60 MW (GROSS)
           60 MW (ESC)
COKE
 7.00 XS  BITUMINOUS
WELLMAN LORD
DAVY MCKEE
ENERGY CONSUMPTION: ****x
STATUS 1     STARTUP  5/80
DELAWARE CITY 1, 2, AND 3 OF DELMARVA POWER AND LIGHT ARE THREE RETRO-
FITTED COKE (7.OX Si 14,000 BTU/LB) FIRED BOILERS WHICH HAVE A STEAM CAP-
ACITY OF 500K LB/HR EACH.  THE BOILERS GENERATE STEAM AS WELL AS ELECTRI-
CITY FOR GETTY REFINING AND MARKETING.  EACH BOILER SUPPLIES 295,000 ACFM
OF FLUE GAS TO A MECHANICAL COLLECTOR THEN TO A VENTURI PARTICLE SCRUBBER
FOR PARTICULATE CONTROL.  THE FLUE GAS THEN PASSES THROUGH A CHEVRON TYPE
MIST ELIMINATOR TO A WET ESP FOR BOTH PARTICULATE AND ACID MIST REMOVAL. A
FOUR STAGE WELLMAN-LORD SYSTEM, WHICH IS DESIGNED FOR 90X REMOVAL, IS USED
FOR S02 CONTROL.  HOT AIR INJECTION REHEAT IS USED BEFORE THE GAS EXITS
OUT A 500 FT STACK. THE EMISSION CONTROL SYSTEM IS SUPPLIED BY DAVY MCKEE.
IT IS A CLOSED LOOP WATER SYSTEM.  THE SYSEM BEGAN OPERATING IN MAY 1980.
DELMARVA  POWER  *  LIGHT
DELAWARE  CITY
2
RETROFIT    60 MW  (GROSS)
            60 MW  (ESC)
COKE
  7.00  XS   BITUMINOUS
WELLMAN LORD
DAVY MCKEE
ENERGY CONSUMPTION: *»**•/
STATUS 1     STARTUP  5/80
DELAWARE CITY 1, 2, AND 3 OF DELMARVA POWER AND LIGHT ARE THREE RETRO-
FITTED COKE (7.OX S) FIRED BOILERS WHICH HAVE A STEAM CAPACITY OF BOOK
LB/HR EACH.  THE BOILERS GENERATE STEAM AS WELL AS ELECTRICITY FOR GETTY
REFINING AND MARKETING.  EACH BOILER SUPPLIES 295,000 ACFM OF FLUE GAS TO
A MECHANICAL COLLECTOR THEN TO A VENTURI PARTICLE SCRUBBER FOR PARTICULATE
CONTROL.  THE FLUE GAS THEN PASSES THROUGH A CHEVRON TYPE MIST ELIMINATOR
TO A WET ESP FOR BOTH PARTICULATE AND ACID MIST REMOVAL.  A FOUR STAGE
WELLMAN-LORD SYSTEM DESIGNED FOR 90X REMOVAL, IS USED FOR S02 CON-
TROL.  HOT AIR INJECTION REHEAT IS USED BEFORE THE GAS EXITS OUT A 500 FT.
STACK.  THE EMISSION CONTROL SYSTEM IS SUPPLIED BY DAVY MCKEE.  IT IS A
CLOSED LOOP WATER SYSTEM.  THE SYSTEM BECAME OPERATIONAL IN MAY 1980.
 DELMARVA POWER  &  LIGHT
 DELAWARE CITY
 3
 RETROFIT   60 MW  (GROSS)
            60 MW  (ESC)
 COKE
  7.00 XS  BITUMINOUS
 WELLMAN LORD
 DAVY MCKEE
 ENERGY CONSUMPTION:  ****X
 STATUS 1     STARTUP  5/80
DELAWARE CITY 1, 2, AND 3 OF DELMARVA POWER AND  LIGHT ARE THREE RETRO-
FITTED COKE (7.OX S) FIRED BOILERS WHICH HAVE A  STEAM CAPACITY OF 500K
LB/HR EACH.  THE BOILERS GENERATE STEAM AS WELL  AS ELECTRICITY FOR GETTY
REFINING AND MARKETING.  EACH BOILER SUPPLIES 295,000 ACFM OF FLUE GAS TO
A MECHANICAL COLLECTOR THEN TO A VENTURI PARTICLE SCRUBBER FOR PARTICULATE
CONTROL.  THE FLUE GAS THEN PASSES THROUGH A CHEVRON TYPE MIST ELIMINATOR
TO A WET ESP FOR BOTH PARTICULATE AND ACID MIST  REMOVAL.  A  FOUR STAGE
WELLMAN-LORD SYSTEM DESIGNED FOR 90X REMOVAL, IS USED FOR S02 CON-
TROL.  HOT AIR INJECTION REHEAT IS USED BEFORE THE GAS  EXITS OUT A 500 FT.
STACK.  THE EMISSION CONTROL SYSTEM IS SUPPLIED  BY DAVY MCKEE.  IT IS A
CLOSED LOOP WATER SYSTEM.  THE SYSTEM BECAME OPERATIONAL IN  MAY 19SO.
 DELMARVA POWER 8 LIGHT
 VIENNA
 9
 NEW       550 MW (GROSS)
           550 MW (ESC)
 COAL
  2.50 XS  BITUMINOUS
 PROCESS NOT SELECTED
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION:  2.7X
 STATUS 6     STARTUP  0/95
DELMARVA POWER AND LIGHT IS PLANNING A NEW 550 MW  (GROSS) UNIT, VIENNA 9,
TO BE CONSTRUCTED IN VIENNA, MARYLAND.  THE UTILITY  IS  PRESENTLY  CONSIDER-
ING A LIMESTONE FGD UNIT FOR S02 CONTROL AND AN ESP  FOR  PARTICULATE REMOV-
AL.  THE PULVERIED COAL (2.5X S, 12,200 BTU/LB) FIRED UNIT  IS  EXPECTED TO
COMMENCE OPERATIONS IN MAY 1995.
 DESERET GEN 4 TRANS
 BONANZA
 1
 NEW       410 MM (GROSS)
           410 MW (ESC)
 COAL
   .50 XS  BITUMINOUS
 LIMESTONE
 COMBUSTION ENGINEERING
 ENERGY CONSUMPTION:  2.9X
 STATUS 1     STARTUP  9/84
BONANZA 1, OF DESERET GEN. & TRANS. IS A 410 MW  (GROSS)  UNIT  LOCATED  IN
VERNAL UTAH.  THE PULVERIZED COAL  (10,500 BTU/LB,  .5X  S) FIRED BOILER
SUPPLIES FLUE GAS TO A COMBUSTION  ENGINERING WET LIMESTONE  FGD SYSTEM
WITH A DESIGN S02 REMOVAL EFFICIENCY OF 95X.   PARTICULATE MATTER IS CON-
TROLLED WITH AN ECOLAIRE FABRIC  FILTER AT 99.6X  DESIGN REMOVBAL EFFICIEN-
CY.  THE SYSTEM OPERATES IN A CLOSED WATER  LOOP  MODE AND SLUDGE IS DIS-
POSED AT AN ON-SITE LANDFILL.  OPERATIONS COMMENCED IN SEPTEMBER 1984.
 DESERET GEN t TRANS
 BONANZA
 2
 NEW       410 MW (GROSS)
           410 MW (ESC)
 COAL
   .50 XS  BITUMINOUS
 LIMESTONE
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION:  2.9X
 STATUS 6     STARTUP  0/92
BONANZA  (FORMERLY MOON  LAKE)  2  IS  A  PULVERIZED  COAL ( .5X S, 10,500 BTU/LB)
FIRED UNIT  PLANNED BY DESERET GENERATION &  TRANS.  COOP TO BE LOCATED IN
VERNAL,  UTAH.   A WET LIMESTONE  SCRUBBING SYSTEM WITH AN S02 REMOVAL EF-
FICIENCY OF 95X WILL BE EMPLOYED FOR S02 CONTROL.   THE SYSTEM
WILL FEATURE A  BAGHOUSE DESIGNED TO  REMOVE  99.6X OF THE PARTICULATE.  THE
UNIT WILL OPERATE IN A  CLOSED WATER  LOOP WITH SLUDGE DISPOSAL ON-SITE
IN A LANDFILL.  OPERATIONS  ARE  SCHEDULED TO COMMENCE IN 1992.
                                              2-8

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
DUQUESNE LIGHT
ELRAMA
1-4
RETROFIT  510 MW (GROSS)
          510 MM (ESC)
COAL
 2.05 XS  BITUMINOUS
LIME
GE ENVIRONMENTAL SERVICES
ENERGY CONSUMPTION:  1.4X
STATUS 1     STARTUP 10/75
                               ELRAMA 1-4 OF  DUQUESNE  LIGHT CONSISTS OF  FOUR  PULVERIZED  COAL  (2.05X  S,
                               11,568 BTU/LB) FIRED UNITS LOCATED  IN ELRAMA,  PENNSYLVANIA. THE RETROFIT
                               EMISSION CONTROL SYSTEM FOR EACH  UNIT CONSISTS OF  MECHANICAL COLLECTORS
                               FOLLOWED BY ESP'S AND FIVE VARIABLE THROAT  VENTURI LIME ABSORBER MODULES
                               SUPPLIED BY GEESI, WHICH ARE DESIGNED TO  REMOVE 83X OF THE S02 FROM THE
                               FLUE GAS.   THE CLEANED  GAS EXITS  VIA A 398  FOOT ACID BRICK LINED STAf.K.
                               THE SYSTEM OPERATES IN  AN OPEN WATER LOOP AND  THE  POZ-0-TEC STABILIZED
                               SLUDGE IS HAULED TO AN  OFF-SITE LANDFILL.   THE SYSTEM HAS BEEN
                               OPERATIONAL SINCE OCTOBER 1975.
DUQUESNE LIGHT
PHILLIPS
1-6
RETROFIT  408 MW (GROSS)
          408 MW (ESC)
COAL
 2.05 XS  BITUMINOUS
LIME
GE ENVIRONMENTAL SERVICES
ENERGY CONSUMPTION:  3.4X
STATUS 1     STARTUP  7/73
                               THE PHILLIPS POWER STATION OF  DUQUESNE  LIGHT CONSISTS OF SIX DRY BOTTOM
                               PULVERIZED COAL (2.05X S,  11568 BTU/LB)  FIRED UNITS  LOCATED IN SOUTH
                               HEIGHTS, PENNSYLVANIA. PARTICULATE  CONTROL  IS ACCOMPLISHED BY SIX MECHAN-
                               ICAL COLLECTORS FOLLOWED BY SIX ESP'S (ONE/BOILER).  ONE TWO STAGE AND
                               THREE SINGLE STAGE VARIABLE THROAT  VENTURI  LIME  FGD  MODULES SUPPLIED BY
                               GEESI ARE DESIGNED TO REMOVE 83X OF THE  S02 FROM THE FLUE GAS. THE CLEANED
                               FLUE GAS PASSES THROUGH TWO CHEVRON MIST ELIMINATORS (EACH MODULE) AND
                               EXITS VIA A 340 FT ACID BRICK  LINED STACK.  THE  RETROFIT SYSTEM OPERATES
                               IN AN OPEN WATER LOOP, AND THE POZ-0-TEC STABILIZED  SLUDGE IS TRUCKED TO
                               AN OFF-SITE LANDFILL. THE  SYSTEM HAS BEEN OPERATIONAL SINCE JULY
                               1973.
EAST KENTUCKY POWER
J.K. SMITH
1
NEW
          650 MW  (GROSS)
          650 MW  (ESC)

          BITUMINOUS
                               THE EAST KENTUCKY POWER COOP HAS PLANS TO  BUILD  A  NEW  UNIT,  J.K. SMITH  1,
                               IN WINCHESER, KENTUCKY.  A CONTRACT WAS AWARDED  TO BABCOCK & WILCOX FOR A
                               WET LIME PROCESS TO CONTROL S02 EMISSIONS.   AN ESP WILL BE EMPLOYED FOR
                               PARTICULATE REMOVAL AND THE SYSTEM WILL OPERATE  IN A CLOSED  WATER  LOOP.
                               INITIAL START-UP IS EXPECTED IN 1992.
COAL
 1.50 XS
LIME
BABCOCK S WILCOX
ENERGY CONSUMPTION: «***X
STATUS 3     STARTUP  0/92
EAST KENTUCKY  POWER
SPURLOCK
2
NEW       500  MW  (GROSS)
          500  MM  (ESC)
COAL
 3.50 XS
LIME
THYSSEN/CEA
ENERGY CONSUMPTION: *»*«x
STATUS 1     STARTUP 12/82
                               SPURLOCK 2 OF EAST KENTUCKY POWER COOPERATIVE  IS A BALANCED  DRAFT  PULVER-
                               IZED COAL (3.5X S, 11,000 BTU/LB) FIRED  UNIT LOCATED  IN MAYSVILLE,  KY.  THE
                               EMISSION CONTROL SYSTEM CONSISTS OF AN ESP FOLLOWED BY  A THYSSEN/CEA  LIME
                               FGD SYSTEM (90X DESIGN S02 REMOVAL EFFICIENCY).   FLUE GAS FROM UNIT 1 IS
                               USED TO REHEAT THE CLEANED GAS WHICH EXITS THROUGH AN 802 FT STACK.  THE
                               CLOSED WATER LOOP SYSTEM EMPLOYS A POZ-0-TEC SLUDGE STABILIZATION
                               FACILITY.  UNIT 2 OPERATIONS COMMENCED IN DECEMBER 1982.
FLORIDA POWER  &  LIGHT
MARTIN
3
NEW       800  MW (GROSS)
          800  MW (ESC)
COAL
***** XS
PROCESS NOT SELECTED
VENDOR NOT SELECTED
ENERGY CONSUMPTION: ****•/.
STATUS 6     STARTUP  0/94
                               FLORIDA POWER AND LIGHT HAS PLANS FOR TWO NEW UNITS, MARTIN 3 AND 4 TO BE
                               LOCATED IN MARTIN COUNTY, FLORIDA.  THE PULVERIZED COAL FIRED BOILERS
                               WILL HAVE A MW RATING OF 800 EACH.  THE UTILITY IS PRESENTLY CONSIDERING
                               ONLY FGD AS THE EMISSION CONTROL STRATEGY.  THE START-UP FOR UNIT 3 IS
                               PROJECTED FOR 1994.
FLORIDA POWER *  LIGHT
MARTIN
4
NEW       800 MW (GROSS)
          800 MW (ESC)
COAL
***** xs
PROCESS NOT SELECTED
VENDOR NOT SELECTED
ENERGY CONSUMPTION: **»*X
STATUS 6     STARTUP  0/95
                               FLORIDA POWER AND LIGHT HAS PLANS FOR TWO NEW UNITS, MARTIN 3 AND 4 TO BE
                               LOCATED IN MARTIN COUNTY, FLORIDA.  THE PULVERIZED COAL FIRED BOILERS
                               WILL HAVE A MW RATING OF 800 EACH.  THE UTILITY IS PRESENTLY CONSIDERING
                               ONLY FGD AS THE EMISSION CONTROL STRATEGY.  THE START-UP FOR UNIT 4 IS
                               PROJECTED FOR 1995.
                                              2-9

-------
UTILITY FGD SURVEY'- OCTOBER 1983 - SEPTEMBER
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                       ABSTRACT
GENERAL PUBLIC UTILITIES
COAL
1
NEW       690 MW  (GROSS)
          690 MW  (ESC)
COAL
 2.00 XS
LIMESTONE
VENDOR NOT SELECTED
ENERGY CONSUMPTION: *****
STATUS 6     STARTUP  0/93
                    GENERAL  PUBLIC UTILITIES HAS PLANS FOR  A  625  MW  UNIT,  COAL 1,  TO BE  LO-
                    CATED  IN FORKED  RIVER  NEW JERSEY.   THE  PULVERIZED  COAL (2.OX S,  13,800
                    BTU/LB)  FIRED BABCOCK  k  WILCOX UNIT WILL  HAVE A  GROSS  RATING OF  625  MW AND
                    WILL UTILIZE A WET  LIMESTONE FGD SYSTEM FOR CONTROL OF S02 EMISSIONS.
                    PARTICULATE MATTER  WILL  BE CONTROLLED WITH AN ESP.  THE SYSTEM WILL
                    OPERATE  IN A CLOSED WATER LOOP MODE AND FLUE  GAS WILL  EXIT A 650 FT  STACK.
                    START-UP IS SCHEDULED  FOR 1993.
 GENERAL  PUBLIC  UTILITIES
 COAL
 2
 NEW       690 MW  (GROSS)
           690 MW  (ESC)
 COAL
  3.50 XS
 LIMESTONE
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION:  ****X
 STATUS 6    STARTUP  0/97
                     GENERAL PUBLIC  UTILITIES IS PLANNING TO CONSTRUCT A 690 MW UNIT,  COAL 2,
                     IN THE  WESTERN  U.S.   THE UTILITY IS PRESENTLY CONSIDERING A WET LIMESTONE
                     FGD SYSTEM AS THE  EMISSION CONTROL STRATEGY.  THE COAL FIRED (3.5X S) UNIT
                     IS SCHEDULED  TO COMMENCE OPERATIONS IN 1997.
 GRAND HAVEN BRD OF
 J.B.  SIMS
 3
 NEW
 COAL
  2.75 XS
 LIME
 BABCOCK t
 65 MW (GROSS)
 65 MW (ESC)

BITUMINOUS
LIGHT 4 PWR J.B.  SIMS 3 OF GRAND  HAVEN BOARD  OF LIGHT AND POWER IS A BITUMINOUS COAL
            (2.75X S, 11,000 BTU/LB)  FIRED UNIT LOCATED IN GRAND HAVEN, MICHIGAN.  THE
            BABCOCK & WILCOX EMISSION CONTROL SYSTEM CONSISTS OF TWO LIME SPRAY TOWERS
            WITH  AN S02 REMOVAL EFFICIENCY OF 90-95X.  EACH TOWER IS EQUIPPED WITH A
            CHEVRON MIST ELIMINATOR FOLLOWED  BY AN IN-LINE REHEATER.  AN ESP IS EM-
            PLOYED FOR PARTICULATE CONTROL AND FLUE GAS EXITS A 360 FT STACK.  IT
            OPERATES IN A CLOSED  WATER LOOP MODE AND THE SLUDGE IS DISPOSED OF IN AN
            OFF-SITE LANDFILL.  INITIAL OPERATIONS OF THE FGD SYSTEM BEGAN IN MAY 1983.
           WILCOX
 ENERGY CONSUMPTION:  ****X
 STATUS 1     STARTUP  5/83
 GRAND RIVER DAM AUTHORITY
 GRDA
 2
 NEW       575 MW (GROSS)
           520 MW (ESC)
 COAL
   .95 XS  SUBBITUMINOUS
 LIME/SPRAY DRYING
 FLAKT
 ENERGY CONSUMPTION:  ****X
 STATUS 2     STARTUP  3/85
                     GRDA 2 OF GRAND RIVER DAM AUTHORITY IS A 575 MW (GROSS) UNIT UNDER CON-
                     STRUCTION IN PRYOR,  OKLAHOMA.   FLAKT IS SUPPLYING A TURNKEY LIME/SPRAY
                     DRYING FGD SYSTEM CONSISTING OF FOUR SPRAY DRYERS WITH THREE ROTARY ATOM-
                     IZERS EACH FOLLOWED  BY TWO ESP'S FOR PARTICULATE (FLY ASH AND REACTOR
                     PRODUCT) REMOVAL.  INITIAL START-UP IS SCHEDULED FOR MARCH 1985.
 HOOSIER ENERGY
 MEROM
 1
 NEW       490 MW (GROSS)
           441 MW (ESC)
 COAL
  3.50 XS  BITUMINOUS
 LIMESTONE
 MITSUBISHI HEAVY INDUSTRIES
 ENERGY CONSUMPTION:  1.2X
 STATUS 1     STARTUP  8/82
                     MEROM 1, OF HOOSIER ENERGY IS LOCATED IN MEROM, INDIANA.  THIS
                     PULVERIZED COAL (3.5X S) FIRED UNIT PRODUCES 866,000 ACFM OF FLUE GAS
                     WHICH IS BEING CLEANED BY A COLD SIDE ESP UPSTREAM OF A MITSUBISHI
                     LIMESTONE GRID TOWER ABSORBER (90X DESIGN S02 REMOVAL).  THE SYSTEM
                     UTILIZES BYPASS REHEAT AND A 702 FOOT STACK.  THE SLUDGE IS BEING
                     FORCIBLY OXIDIZED AND LANDFILLED, AND THE SYSTEM OPERATES IN A CLOSED
                     WATER LOOP MODE.  UNIT 1 COMMENCED OPERATIONS IN AUGUST 1982.
 HOOSIER ENERGY
 MEROM
 2
 NEW       490 MW (GROSS)
           441 MW (ESC)
 COAL
  3.50 XS  BITUMINOUS
 LIMESTONE
 MITSUBISHI HEAVY INDUSTRIES
 ENERGY CONSUMPTION:  1.2X
 STATUS 1     STARTUP 12/81
                     MEROM 2, OF HOOSIER ENERGY IS LOCATED IN MEROM, INDIANA.  THIS
                     PULVERIZED COAL (3.5X S) FIRED UNIT PRODUCES 666,000 ACFM OF FLUE GAS
                     WHICH IS BEING CLEANED BY A COLD SIDE ESP UPSTREAM OF A MITSUBISHI
                     LIMESTONE GRID TOWER ABSORBER (90X DESIGN S02 REMOVAL). THE SYSTEM
                     UTILIZES BYPASS REHEAT AND A 702 FOOT STACK. THE SLUDGE IS BEING
                     FORCIBLY OXIDIZED AND LANDFILLED, AND THE SYSTEM OPERATES IN A CLOSED
                     WATER LOOP MODE. UNIT 2 COMMENCED OPERATIONS IN DECEMBER 1961.
                                              2-10

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
HOUSTON LIGHTING & POWER
LIMESTONE
1
NEW       750 MM (GROSS)
          750 MW (ESC)
COAL
 1.08 XS  LIGNITE
LIMESTONE
COMBUSTION ENGINEERING
ENERGY CONSUMPTION: ****X
STATUS 2     STARTUP 12/85
HOUSTON LIGHTING AND POWER CO HAS PLANS FOR TWO NEW UNITS,  LIMESTONE 1
AND 2, UNDER CONSTRUCTION IN JEWITT TEXAS.   THE PULVERIZED  COAL (1.08X S,
6177 BTU/LB) FIRED BOILER WILL UTILIZE A WET LIMESTONE SCRUBBING PROCESS
FOR PRIMARY S02 COLLECTION.  A COLD SIDE ESP WILL ALSO BE USED FOR PRIMARY
PARTICLE CONTROL.  THE SYSTEM WILL OPERATE  IN A CLOSED WATER LOOP MODE AND
FLUE GAS WILL EXIT THROUGH A 563 FT STACK.   THE UILITY AWARDED A CONTRACT
TO COMBUSTION ENGINEERING FOR THE INSTALLATION OF THIS SYSTEM.  UNIT 1 IS
SCHEDULED TO COMMENCE OPERATIONS IN DECEMBER 1985.
HOUSTON LIGHTING & POWER
LIMESTONE
2
NEW       750 MW (GROSS)
          750 MW (ESC)
COAL
 1.08 XS
LIMESTONE
COMBUSTION ENGINEERING
ENERGY CONSUMPTION: ***«X
STATUS 2     STARTUP 12/86
HOUSTON LIGHTING AND POWER CO HAS PLANS FOR TWO NEW UNITS,  LIMESTONE  1
AND 2, UNDER CONSTRUCTION IN JEWITT,  TEXAS.  THE PULVERIZED COAL (1.08X S,
6177 BTU/LB) FIRED BOILER WILL UTILIZE A WET LIMESTONE SCRUBBING PROCESS
FOR PRIMARY S02 COLLECTION.  A COLD SIDE ESP WILL BE USED  FOR  PRIMARY
PARTICLE CONTROL.  THE SYSTEM WILL OPERATE IN A CLOSED WATER LOOP MODE  AND
FLUE GAS WILL EXIT THROUGH A 563 FT STACK.  THE UTILITY AWARDED A CONTRACT
TO COMBUSTION ENGINEERING FOR THE INSTALLATION OF THIS SYSTEM.  UNIT  2  IS
SCHEDULED TO COMMENCE OPERATIONS IN DECEMBER 1986.
HOUSTON LIGHTING 8 POWER
MALAKOFF
1
NEW       690 MW (GROSS)
          690 MW (ESC)
COAL
 1.10 XS  LIGNITE
LIMESTONE
GE ENVIRONMENTAL SERVICES
ENERGY CONSUMPTION: ****X
STATUS 3     STARTUP 12/89
HOUSTON LIGHTING AND POWER HAS PLANS FOR TWO NEW UNITS,  MALAKOFF 1 AND  2,
TO BE LOCATED IN MALAKOFF, TEXAS.  EACH PULVERIZED COAL  (1.1X S, 6112
BTU/LB LIGNITE) FIRED BABCOCK & WILCOX BOILER WILL UTILIZE A WET LIMESTONE
SCRUBBING PROCESS FOR S02 CONTROL.  A COLD SIDE ESP SUPPLIED BY WHEELABRA-
TOR FRYE WILL CONTROL PARTICULATE MATTER.  THE CLEANED FLUE GAS WILL EXIT
THROUGH A 625 FOOT ACID RESISTANT BRICK LINED STACK.  THE UTILITY HAS
AWARDED A CONTRACT TO GE ENVIRONMENTAL SERVICES FOR INSTALLATION OF THE
FGD SYSTEMS.  UNIT 1 IS SCHEDULED TO COMMENCE OPERATIONS IN DECEMBER 1989.
HOUSTON LIGHTING & POWER
MALAKOFF
2
NEW       690 MW (GROSS)
          690 MW (ESC)
COAL
 1.10 XS  LIGNITE
LIMESTONE
GE ENVIRONMENTAL SERVICES
ENERGY CONSUMPTION: **»«*
STATUS 3     STARTUP 12/90
HOUSTON LIGHTING AND POWER HAS PLANS FOR TWO NEW UNITS,  MALAKOFF 1 AND 2,
TO BE LOCATED IN MALAKOFF, TEXAS.  EACH PULVERIZED COAL  (1.1X S, 6112
BTU/LB LIGNITE) FIRED BABCOCK & WILCOX BOILER WILL UTILIZE A WET LIMESTONE
SCRUBBING PROCESS FOR S02 CONTROL.  A COLD SIDE ESP SUPPLIED BY WHEELABRA-
TOR FRYE WILL CONTROL PARTICULATE MATTER.  THE CLEANED FLUE GAS WILL EXIT
THROUGH A 625 FOOT ACID RESISTANT BRICK LINED STACK.  THE UTILITY HAS
AWARDED A CONTRACT TO GE ENVIRONMENTAL SERVICES FOR INSTALLATION OF THE
FGD SYSTEMS.  UNIT 2 IS SCHEDULED TO COMMENCE OPERATIONS IN DECEMBER 1990.
HOUSTON LIGHTING & POWER
W.A. PARISH
8
NEW       600 MW (GROSS)
          492 MW (ESC)
COAL
  .41 XS  SUBBITUMINOUS
LIMESTONE
GE ENVIRONMENTAL SERVICES
ENERGY CONSUMPTION:  l.OX
STATUS 1     STARTUP 10/82
W.A. PARISH 8 OF HOUSTON LIGHTING t POWER IS A PULVERIZED COAL (0.41X S,
8942 BTU/LB) FIRED UNIT LOCATED IN BOOTH, TEXAS.  GEESI HAS SUPPLIED A
LIMESTONE FGD SYSTEM THAT REMOVES 82X OF THE FLUE GAS S02. FABRIC FILTERS
ARE EMPLOYED FOR PARTICULATE CONTROL AND REHEAT IS PROVIDED BY BYPASSING
18X OF THE CLEANED FLUE GAS. SLUDGE IS DEWATERED, BLENDED WITH FLYASH, AND
DISPOSED OF IN AN ON-SITE LANDFILL. THE SYSTEM OPERATES IN A CLOSED WATER
LOOP MODE AND FLUE GAS EXITS THROUGH A 500 FT STACK.  THE UNIT HAS BEEN
OPERATINAL SINCE OCTOBER 1982.
INDIANAPOLIS POWER & LIGHT
PATRIOT
1
NEW       650 MW (GROSS)
          650 MW (ESC)
COAL
 3.50 XS
LIMESTONE
VENDOR NOT SELECTED
ENERGY CONSUMPTION: ****X
STATUS 6     STARTUP  0/93
INDIANAPOLIS POWER AND LIGHT HAS PLANS FOR THREE NEW UNITS, PATRIOT 1, 2,
AND 3, TO BE LOCATED IN PATRIOT, INDIANA.  THE UTILITY PLANS ON UTILIZING
A LIMESTONE FGD PROCESS FOR EMISSION CONTROL AND A LOCAL COAL WITH A
SULFUR CONTENT OF 3.5X.
                                             2-11

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
INDIANAPOLIS POWER &  LIGHT
PATRIOT
2
NEW       650 MM  (GROSS)
          650 MM  (ESC)
COAL
 3.50 XS
LIMESTONE
VENDOR NOT  SELECTED
ENERGY CONSUMPTION: ****X
STATUS 6     STARTUP   O/ 0
INDIANAPOLIS POWER AND LIGHT HAS PLANS FOR THREE NEW UNITS, PATRIOT 1, 2,
AND 3, TO BE LOCATED IN PATRIOT, INDIANA.  THE UTILITY PLANS TO UTILIZE
A LIMESTONE FGD PROCESS FOR EMISSION CONTROL AND A LOCAL COAL WITH A
SULFUR CONTENT OF 3.5X.
 INDIANAPOLIS POWER  S  LIGHT
 PATRIOT
 3
 NEW       650 MW (GROSS)
           650 MM (ESC)
 COAL
  3.50 XS
 LIMESTONE
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION; »»**x
 STATUS 6     STARTUP  O/  0
INDIANAPOLIS POWER AND LIGHT HAS PLANS FOR THREE NEW UNITS, PATRIOT 1, 2,
AND 3, TO BE LOCATED IN PATRIOT, INDIANA.  THE UTILITY PLANS ON UTILIZING
A LIMESTONE FGD PROCESS FOR EMISSION CONTROL AND A LOCAL COAL WITH A
SULFUR CONTENT OF 3.5X.
 INDIANAPOLIS POWER & LIGHT
 PETERSBURG
 3
 NEW       532 MM (GROSS)
           532 MW (ESC)
 COAL
  3.25 XS  BITUMINOUS
 LIMESTONE
 AIR CORRECTION DIVISION, UOP
 ENERGY CONSUMPTION:  2.4X
 STATUS 1     STARTUP 12/77
PETERSBURG 3 OF INDIANAPOLIS POWER AND LIGHT IS LOCATED IN PETERSBURG,
INDIANA, AND BURNS BITUMINOUS COAL (3.25X S, 10,750 BTU/LB).  TWO COLD
SIDE ESP'S ARE LOCATED UPSTREAM OF FOUR 85X EFFICIENT UOP LIMESTONE TCA
MODULES. A HORIZONTAL MIST ELIMINATOR PRECEDES AN INDIRECT HOT AIR REHEAT-
ER THAT BOOSTS THE GAS TEMPERATURE BY 30 DEC F BEFORE IT EXITS THE 616
FOOT RIGIFLAKE 4850 LINED STACK. STABILIZED SLUDGE IS DISPOSED OF IN AN
ON-SITE POND, AND THE SYSTEM OPERATES IN A CLOSED WATER LOOP MODE.
THE UNIT HAS BEEN OPERATIONAL SINCE DECEMBER 1977.
 INDIANAPOLIS POWER « LIGHT
 PETERSBURG
 4
 NEW       530 MM (GROSS)
           530 MW (ESC)
 COAL
  3.50 XS  BITUMINOUS
 LIMESTONE
 RESEARCH-COTTRELL
 ENERGY CONSUMPTION:  2.IX
 STATUS 2     STARTUP  3/86
 PETERSBURG 4 OF INDIANAPOLIS POWER AND LIGHT IS A BITUMINOUS COAL  (3.SOX S
 11,000 BTU/LB) FIRED UNIT UNDER CONSTRUCTION IN PETERSBURG, INDIANA. THE
 BOILER WILL BE SUPPLIED BY COMBUSTION ENGINEERING AND THE LIMESTONE FGD
 SYSTEM FOR THIS UNIT WILL BE SUPPLIED BY RESEARCH-COTTRELL AND AN  ESP WILL
 BE  EMPLOYED FOR PARTICULATE CONTROL.  THE SYSTEM WILL OPERATE IN A CLOSED_
 WATER LOOP AND SLUDGE WILL BE POZ-0-TEC STABILIZED BEFORE PONDING.  START-
 UP  IS SLATED FOR MARCH 1986.
 IOWA ELECTRIC LIGHT & PWR
 GUTHRIE CO.
 1
 NEW       720 MW (GROSS)
           720 MW (ESC)
 COAL
   .40 XS  SUBBITUMINOUS
 LIMESTONE
 COMBUSTION ENGINEERING
 ENERGY CONSUMPTION: *«**X
 STATUS 4     STARTUP 99/99
 IOWA  ELECTRIC  LIGHT AND POWER HAS PLANS TO CONSTRUCT A 720 MW UNIT,
 GUTHRIE  COUNTY 1, SUPPLIED BY COMBUSTION ENGINEERING IS TO BE LOCATED  IN
 PANORA,  IOWA.   A  LETTER OF INTENT WAS SIGNED WITH COMBUSTION ENGINEERING
 TO  PROVIDE  A WET  LIMESTONE FGD SYSTEM TO CONTROL S02 EMISSIONS  FROM  THE
 PULVERIZED  COAL (0.4X S, 8180 BTU/LB) FIRED BOILER.  AN ESP IS  TO  BE USED
 FOR PARTICULATE MATTER REMOVAL.  THE SYSTEM WILL OPERATE  IN A CLOSED WATER
 LOOP  MODE AND  FLUE GAS WILL EXIT A 650 FOOT STACK.  START UP HAS BEEN
 DEFERRED INDEFINITELY.
 JACKSONVILLE ELEC AUTHORITY
 ST.JOHNS RVR PWR PRK
 1
 NEW       612 MW (GROSS)
           612 MW (ESC)
 COAL
  2.50 XS  BITUMINOUS
 LIMESTONE
 RESEARCH-COTTRELL
 ENERGY CONSUMPTION: ****•/.
 STATUS 2     STARTUP  4/87
 THE  JACKSONVILLE  ELECTRIC AUTHORITY HAS STARTED CONSTRUCTION  ON TWO NEW
 UNITS,  ST.  JOHNS  RIVER  POWER  PARK  1 AND 2,  LOCATED  IN  EAST  PORT, FLORIDA.
 EACH UNIT WILL BURN  PULVERIZED COAL (2-4X S) AND  SUPPLY  2,500,000 ACFM TO
 A  MET LIMESTONE FGD  PROCESS AND AN ESP FOR  EMISSION CONTROL.   THE CLEANED
 FLUE GAS WILL  EXIT THROUGH A  640 FOOT DOUBLE LINED  SINGLE STACK.  THE
 UTILITY HAS AWARDED  A CONTRACT TO  RESEARCH-COTTRELL FOR  INSTALLATION OF
 THE  CONTROL SYSTEMS.  START-UP IS  SCHEDULED FOR APRIL  1987.
                                              2-12

-------
                                                  UTILITY F6D SURVEY:  OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF F6D SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
JACKSONVILLE ELEC AUTHORITY
ST.JOHNS RVR PWR PRK
Z
NEW       612 MM (GROSS)
          612 MW (ESC)
COAL
 2.50 XS  BITUMINOUS
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION: *«*«X
STATUS 2     STARTUP 10/68
                               THE JACKSONVILLE ELECTRIC AUTHORITY  HAS  STARTED  CONSTRUCTION ON  TWO NEW
                               UNITS,  ST.  JOHNS RIVER POWER  PARK 1  AND  2,  LOCATED  IN EAST  PORT,  FLORIDA.
                               EACH UNIT WILL BURN PULVERIZED COAL  (2-4X S)  AND SUPPLY  2,500,000 ACFM TO
                               A WET LIMESTONE FGD PROCESS AND AN ESP FOR  EMISSION CONTROL.  THE CLEANED
                               FLUE GAS WILL EXIT THROUGH A  640 FOOT DOUBLE  LINED  SINGLE STACK.   THE
                               UTILITY HAS AWARDED A CONTRACT TO RESEARCH-COTTRELL FOR  INSTALLATION OF
                               THE CONTROL SYSTEMS.  START-UP IS SCHEDULED FOR  OCTOBER  1988.
KANSAS CITY POWER & LIGHT
LA CYGNE
1
NEW       874 MW (GROSS)
          874 MW (ESC)
COAL
 5.39 XS  SUBBITUMINOUS
LIMESTONE
BABCOCK & WILCOX
ENERGY CONSUMPTION:  3.2X
STATUS 1     STARTUP 12/72
                               LA CYGNE 1 IS A WET BOTTOM,  CYCLONE-FIRED  UNIT LOCATED  IN  LA  CYGNE,
                               KANSAS.  THE UNIT BURNS SUBBITUMINOUS COAL (5.39X S,  9400  BTU/LB).
                               THE EMISSION CONTROL SYSTEM  CONSISTS OF EIGHT VARIABLE  THROAT
                               VENTURI/LIMESTONE SIEVE TRAY TOWER TRAINS  SUPPLIED BY BABCOCK AND WILCOX.
                               EACH 80X (S02 REMOVAL,  DESIGN)  EFFICIENT TRAIN IS FOLLOWED BY A
                               COMBINATION SIEVE TRAY  AND CHEVRON MIST ELIMINATOR, AND BOTH  A DIRECT AND
                               INDIRECT REHEATER. THE  CLEANED  GAS EXITS THROUGH  A 700  FOOT STEEL LINED
                               STACK.  THE SYSTEM OPERATES  IN  AN OPEN WATER  LOOP, AND  THE SLUDGE IS
                               DISPOSED IN AN UNLINED  POND. OPERATIONS COMMENCED IN DECEMBER 1972.
KANSAS POWER
JEFFREY
1
NEW
             & LIGHT
          720 MW  (GROSS)
          540 MW  (ESC)
COAL
   .32 XS  SUBBITUMINOUS
LIMESTONE
COMBUSTION ENGINEERING
ENERGY CONSUMPTION: »***X
STATUS 1     STARTUP  8/78
KANSAS POWER & LIGHT'S JEFFREY 1 IS A TANGENTIAL FIRED  PULVERIZED
COAL (0.32X S, 8125 BTU/LB) UNIT IN WAMEGO,  KANSAS.  THE EMISSION CONTROL
SYSTEM FOR THIS UNIT CONSISTS OF A COLD SIDE ESP FOLLOWED  BY  SIX (ONE
SPARE) LIMESTONE SPRAY TOWER MODULES SUPPLIED BY COMBUSTION ENGINEERING.
THE DESIGN S02 REMOVAL EFFICIENCY IS SOX (INCLUDING  A 30X  BYPASS REHEAT).
THE SYSTEM OPERATES IN A CLOSED WATER LOOP MODE AND  FLUE GAS  EXITS  A 600
FOOT STACK.  THE UNIT HAS BEEN OPERATIONAL SINCE AUGUST 1978.
KANSAS POWER
JEFFREY
2
NEW
             &  LIGHT
          720 MW (GROSS)
          540 MW (ESC)
COAL
  .32 XS  SUBBITUMINOUS
LIMESTONE
COMBUSTION ENGINEERING
ENERGY CONSUMPTION: *#**X
STATUS 1     STARTUP  1/80
UNIT 2, PRESENTLY OPERATING AT KANSAS POWER AND LIGHT'S JEFFREY ENERGY
CENTER IN WAMEGO, KANSAS, BURNS 0.32X S PULVERIZED COAL (8125 BTU/LB).
THIS UNIT'S EMISSION CONTROL SYSTEM CONSISTS OF A COLD SIDE ESP
AND COMBUSTION ENGINEERING LIMESTONE SPRAY TOWERS. A 30X FLUE GAS
BYPASS PROVIDES REHEAT OF THE CLEANED GAS BEFORE IT EXITS THROUGH A
600 FOOT STACK. THE SYSTEM OPERATES IN A CLOSED WATER LOOP MODE, AND
THE SLUDGE IS STABILIZED WITH BOTTOM ASH AND PIPED TO AN ON-SITE CLAY
LINED POND. INITIAL OPERATIONS COMMENCED IN JANUARY 1980.
KANSAS POWER  *  LIGHT
JEFFREY
3
NEW        730 MW  (GROSS)
           540 MW  (ESC)
COAL
   .32 XS   SUBBITUMINOUS
LIMESTONE
COMBUSTION ENGINEERING
ENERGY CONSUMPTION: ***«X
STATUS 1      STARTUP  5/83
                               JEFFREY 3 OF KANSAS POWER & LIGHT IS A TANGENTIAL FIRED PULVERIZED COAL
                               (.32X S, 8125 BTU/LB) UNIT LOCATED IN WAMEGO, KANSAS.  EMISSIONS
                               ARE CONTROLLED VIA A COLD SIDE ESP AND FOUR COMBUSTION ENGINEERING
                               LIMESTONE SPRAY TOWERS.  THE ABSORBERS OUTLET INTO A COMMON BYPASS DUCT
                               (FOR CONTINUOUS REHEAT) THAT FEEDS THE 600 FOOT STACK.  THE SYSTEM OPER-
                               ATES IN A CLOSED WATER LOOP MODE AND SLUDGE IS STABILIZED WITH
                               BOTTOM ASH BEFORE BEING PIPED TO AN ON-SITE CLAY LINED POND.  INITIAL
                               OPERATIONS COMMENCED IN MAY 1983.
KANSAS POWER
LAWRENCE
4
RETROFIT
             I LIGHT
          125 MW (GROSS)
          125 MW (ESC)
COAL
  .55 XS
LIMESTONE
COMBUSTION ENGINEERING
ENERGY CONSUMPTION: **»*X
STATUS 1     STARTUP  1/77
LAWRENCE 4 OF KANSAS POWER AND LIGHT IS A BALANCED DRAFT, TANGENTIAL FIRED
PULVERIZED COAL (0.55X S, 10,000 BTU/LB) UNIT LOCATED IN LAWRENCE, KANSAS.
A NEW COMBUSTION ENGINEERING LIMESTONE ROD DECK/SPRAY TOWER SYSTEM
REPLACED THE EXISTING MARBLE BED TAIL END SCRUBBER IN JANUARY 1977. THE
SYSTEM TREATS 403,000 ACFM OF FLUE GAS, WITH A DESIGN SOS REMOVAL OF
73X. MIST ELIMINATION IS ACCOMPLISHED BY TWO CHEVRONS AND ONE BULK
ENTRAINMENT SEPARATOR FOLLOWING EACH OF THE TWO MODULES. A FINNED TUBE
REHEATER BOOSTS THE TEMPERATURE OF THE CLEANED GAS BY 20 DEG F BEFORE
IT IS EXHAUSTED THROUGH A 200 FOOT STACK. THE SLUDGE IS DISPOSED IN AN
UNLINED INTERIM POND, WHICH OVERFLOWS INTO A FINAL DISPOSAL POND. THE
SYSTEM OPERATES IN A CLOSED WATER LOOP.
                                             2-13

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
KANSAS POWER t LIGHT
LAWRENCE
5
RETROFIT  420 MW (GROSS)
          420 MW (ESC)
COAL
   .55 XS  SUBBITUMINOUS
LIMESTONE
COMBUSTION  ENGINEERING
ENERGY CONSUMPTION: ****X
STATUS 1     STARTUP  4/78
LAWRENCE 5 OF KANSAS POWER AND LIGHT IS A BALANCED DRAFT, TANGENTIAL FIRED
PULVERIZED COAL (0.55X S, 10,000 BTU/LB) UNIT LOCATED IN LAWRENCE, KANSAS.
A NEW COMBUSTION ENGINEERING LIMESTONE ROD DECK/SPRAY TOWER SYSTEM
REPLACED THE EXISTING MARBLE BED TAIL END SCRUBBER IN APRIL 1978. THE
SYSTEM TREATS 403,000 ACFM OF FLUE GAS, WITH A DESIGN S02 REMOVAL OF
73X. MIST ELIMINATION IS ACCOMPLISHED BY TWO CHEVRONS AND ONE BULK
ENTRAINMENT SEPARATOR FOLLOWING EACH OF THE TWO MODULES. A FINNED TUBE
REHEATER BOOSTS THE TEMPERATURE OF THE CLEANED GAS BY 20 DEG F BEFORE
IT IS EXHAUSTED THROUGH A 350 FOOT STACK. THE SLUDGE IS DISPOSED OF IN AN
UNLINED INTERIM POND, WHICH OVERFLOWS INTO A FINAL DISPOSAL POND. THE
SYSTEM OPERATES IN A CLOSED WATER LOOP.
 KENTUCKY  UTILITIES
 GREEN  RIVER
 1-3
 RETROFIT   65  MW (GROSS)
           65  MW (ESC)
 COAL
  2.23  XS   BITUMINOUS
 LIME
 AMERICAN  AIR FILTER
 ENERGY CONSUMPTION:   4.6X
 STATUS 1      STARTUP   9/75
GREEN RIVER 1-3 OF KENTUCKY UTILITIES ARE THREE DRY BOTTOM PULVERIZED
BITUMINOUS COAL (2.23X S, 11,250 BTU/LB) FIRED UNITS LOCATED IN CENTRAL
CITY, KENTUCKY. THE BOILER SUPPLIES A TOTAL OF 360,000 ACFM OF FLUE GAS TO
A VARIABLE THROAT VENTURI FOLLOWED BY AN AMERICAN AIR FILTER LIME MOBILE
BED CONTACTOR (BOX DESIGN S02 REMOVAL EFFICIENCY). A RADIAL VANE MIST
ELIMINATOR IS FOLLOWED BY A STEAM TUBE REHEATER AND A 165 FOOT STACK.
SLUDGE IS DISPOSED IN AN ON-SITE UNLINED POND, AND THE SYSTEM OPERATES
IN A CLOSED WATER LOOP. THIS RETROFIT SYSTEM HAS BEN OPERATIONAL SINCE
SEPTEMBER 1975.
 KENTUCKY UTILITIES
 HANCOCK
 1
 NEW       708 MW (GROSS)
           650 MW (ESC)
 COAL
  3.50 XS  BITUMINOUS
 LIMESTONE
 BABCOCK & WILCOX
 ENERGY CONSUMPTION:  «*«*X
 STATUS 3     STARTUP 10/93
KENTUCKY UTILITIES HAS PLANS TO CONSTRUCT TWO NEW 650 MW (NET) PULVERIZED
BITUMINOUS COAL (3.5X S, 10,500 BTU/LB) FIRED BOILERS, SUPPLIED BY
COMBUSTION ENGINEERING.  THE UNITS, HANCOCK 1 AND 2, ARE TO BE LOCATED IN
HAWESVILLE, KENTUCKY.  THE UTILITY HAS AWARDED A CONTRACT TO B & W FOR A
WET LIMESTONE SCRUBBING SYSTEM WHICH WILL OPERATE IN A CLOSED WATER LOOP
MODE TO CONTROL EMISSIONS AT A DESIGN REMOVAL EFFICIENCY OF 91.8X.  AN ESP
WILL BE EMPLOYED FOR PARTICULATE CONTROL AND FLUE GAS WILL BE REHEATED BY
ZZZZ
PLOYED  FOR SLUDGE TREATMENT.  HANCOCK 1 IS SCHEDULED TO COMMENCE IN
OCTOBER 1993.
 KENTUCKY UTILITIES
 HANCOCK
 2
 NEW       708 MW (GROSS)
           650 MW (ESC)
 COAL
  3.50 XS  BITUMINOUS
 LIMESTONE
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION: *#**X
 STATUS 6     STARTUP 99/99
KENTUCKY UTILITIES HAS PLANS TO CONSTRUCT TWO NEW 650 MW (NET) PULVERIZED
BITUMINOUS COAL (3.5X S, 10,500 BTU/LB) FIRED BOILERS, SUPPLIED BY
COMBUSTION ENGINEERING.  THE UNITS, HANCOCK 1 AND 2, ARE TO BE LOCATED IN
HAWESVILLE, KENTUCKY.  THE UTILITY IS PRESNTLY INVESTIGATING A WET LIME-
STONE SCRUBBING SYSTEM WHICH WILL OPERATE IN A CLOSED WATER LOOP MODE TO
CONTROL EMISSIONS AT A DESIGN REMOVAL EFFICIENCY OF 91.8X.  AN ESP WILL BE
EMPLOYED FOR PARTICULATE CONTROL AND FLUE GAS WILL BE REHEATED BY INDIRECT
HOT AIR BEFORE EXITING A 600 FT STACK.  FORCED OXIDATION IS EMPLOYED FOR
SLUDGE TREATMENT.  HANCOCK 2 HAS BEEN DEFERRED INDEFINITELY.
 LAKELAND UTILITIES
 MCINTOSH
 3
 NEW       364 MW (GROSS)
           364 MW (ESC)
 COAL
  2.56 XS  BITUMINOUS
 LIMESTONE
 BABCOCK * WILCOX
 ENERGY CONSUMPTION: *«*#X
 STATUS 1     STARTUP  7/82
MCINTOSH 3 OF LAKELAND UTILITIES IS A PULVERIZED BITUMINOUS COAL FIRED
BOILER  LOCATED IN LAKELAND, FLORIDA.  BABCOCK AND WILCOX WAS AWARDED A
CONTRACT TO SUPPLY AN 85X EFFICIENT (S02) LIMESTONE FGD SYSTEM FOR THIS
UNIT.   THE EMISSION CONTROL SYSTEM CONSISTS OF A COLD SIDE ESP FOLLOWED
BY  TWO  PARALLEL FGD MODULES AND A 250 FOOT ACID BRICK LINED STACK.  THE
SYSTEM  OPERATES IN A CLOSED WATER LOOP WITH POZ-0-TEC BEING USED TO STAB-
ILIZE THE SLUDGE.
 LOS ANGELES DEPT OF WTR t PWR
 INTERMOUNTAIN
 1
 NEW       820 MM (GROSS)
           820 MW (ESC)
 COAL
   .79 XS  SUBBITUMINOUS
 LIMESTONE
 GE ENVIRONMENTAL SERVICES
 ENERGY CONSUMPTION:   .OX
 STATUS 2     STARTUP  7/86
 THE  LOS ANGELES DEPARTMENT OF WATER AND POWER HAS STARTED CONSTRUCTION ON
 TWO  NEW BOILERS, INTERMOUNTAIN 1 AND 2 TO BE LOCATED IN DELTA, UTAH
 EACH 820 MW BOILER WILL FIRE PULVERIZED SUBBITUMINOUS COAL  (0.79X si
 10,200 BTU/LB) AND WIIL SUPPLY 5,400,000 ACFM OF FLUE GAS TO A GEESI WET
 LIMESTONE SCRUBBING SYSTEM.  HOT SIDE ESP'S WILL BE USED FOR PARTICLUATE
 CONTROL.  THE FLUE GAS WILL PASS THROUGH A CHEVRON-TYPE MIST ELIMINATOR
 DESIGNED FOR 90X S02 REMOVAL EFFICIENCY AND WILL BE REHEATED BY IN-LINE
 HEAT EXCHANGERS BEFORE EXITING A 710 FT STACK.  THE SYSTEM  WILL OPERATE IN
 A  CLOSED WATER LOOP MODE AND THE SLUDGE WILL BE FLYASH STABILIZED BEFORE
 BEING DISPOSED ON-SITE.  UNIT 1 IS SCHEDULED TO COMMENCE OPERATIONS IN
 JULY 1986.
                                              2-14

-------
                                                  UTILITY F6D SURVEY:  OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
LOS ANGELES DEPT OF WTR S PUR
INTERMOUNTAIN
Z
NEW       820 MM (GROSS)
          620 MM (ESC)
COAL
   .79 XS  SUBBITUMINOUS
LIMESTONE
6E ENVIRONMENTAL SERVICES
ENERGY CONSUMPTION:    .OX
STATUS 2     STARTUP   7/67
THE LOS ANGELES DEPARTMENT OF WATER AND POMER HAS STARTED CONSTRUCTION ON
TWO NEW BOILERS, INTERMOUNTAIN 1 AND 2 TO BE LOCATED IN DELTA,  UTAH.
EACH 820 MM BOILER WILL FIRE PULVERIZED SUBBITUMINOUS COAL (0.79X S,
10,200 BTU/LB) AND Will SUPPLY 5,400,000 ACFM OF FLUE GAS TO A  GEESI  WET
LIMESTONE SCRUBBING SYSTEM.  HOT SIDE ESP'S WILL BE USED FOR PARTICLUATE
CONTROL.  THE FLUE GAS WILL PASS THROUGH A CHEVRON-TYPE MIST ELIMINATOR
DESIGNED FOR 90X S02 REMOVAL EFFICIENCY AND WILL BE REHEATED BY IN-LINE
HEAT EXCHANGERS BEFORE EXITING A 710 FT STACK. THE SYSTEM WILL  OPERATE IN
A CLOSED WATER LOOP MODE AND THE SLUDGE WILL BE FLYASH STABILIZED BEFORE
BEING DISPOSED ON-SITE.  UNIT 1 IS SCHEDULED TO COMMENCE OPERATIONS IN
JULY 1987.
LOUISVILLE GAS & ELECTRIC
CANE RUN
4
RETROFIT  186 MW (GROSS)
          168 MW (ESC)
COAL
 3.87 XS  BITUMINOUS
LIME
AMERICAN AIR FILTER
ENERGY CONSUMPTION:  1.6X
STATUS 1     STARTUP  8/76
UNIT 4 AT LOUISVILLE GAS AND ELECTRIC'S CANE RUN STATION IS A PULVERIZED
BITUMINOUS COAL (3.87X S, 11,300 BTU/LB) FIRED UNIT IN LOUISVILLE,  KEN-
TUCKY. AN ESP AND TWO AMERICAN AIR FILTER CARBIDE LIME MOBILE BED ABSORBER
MODULES (85X DESIGN S02 REMOVAL) TREAT 734,000 ACFM OF FLUE GAS FROM THE
BOILER. TWO CHEVRON MIST ELIMINATORS/MODULE ARE FOLLOWED BY A DIRECT
COMBUSTION REHEATER AND A 250 FOOT STACK. THE WATER LOOP IS OPEN, AND
THE POZ-0-TEC FIXATED SLUDGE IS DISPOSED IN AN ON-SITE LANDFILL.   THIS
RETROFIT SYSTEM HAS BEEN OPERATIONAL SINCE AUGUST 1976.
LOUISVILLE GAS * ELECTRIC
CANE RUN
5
RETROFIT  200 MW (GROSS)
          200 MM (ESC)
COAL
 3.80 XS  BITUMINOUS
LIME
COMBUSTION ENGINEERING
ENERGY CONSUMPTION:   1.5X
STATUS 1     STARTUP  12/77
CANE RUN 5 OF LOUISVILLE GAS AND ELECTRIC IS A PULVERIZED BITUMINOUS COAL
(3.8X S, 11,0000 BTU/LB) FIRED UNIT LOCATED IN LOUISVILLE, KENTUCKY. THE
BOILER SUPPLIES 700,000 ACFM OF FLUE GAS TO AN EMISSION CONTROL SYSTEM
CONSISTING OF AN ESP FOLLOWED BY TWO COMBUSTION ENGINEERING 85X EFFICIENT
(DESIGN) CARBIDE LIME SPRAY TOMERS. A STEAM TUBE REHEATER RAISES THE GAS
TEMPERATURE 40 DEC F. THE SYSTEM OPERATES IN AN OPEN WATER LOOP MODE, AND
THE SLUDGE IS POZ-0-TEC STABILIZED.  THE CLEANED FLUE GAS EXITS A"250 FT
STACK.  OPERATION OF THIS RETROFIT SYSTEM BEGAN IN DECEMBER 1977.
 LOUISVILLE GAS  4  ELECTRIC
 CANE RUN
 6
 RETROFIT  299 MW  (GROSS)
          299 MM  (ESC)
 COAL
 4.80 XS  BITUMINOUS
 DUAL ALKALI
 THYSSEN/CEA
 ENERGY CONSUMPTION:  l.OX
 STATUS 1     STARTUP  4/79
 LOUISVILLE GAS AND ELECTRIC'S CANE RUN 6 IS A 299-MW (GROSS) BITUMINOUS
 COAL (4.80X S, 11,000 BTU/LB) FIRED UNIT LOCATED IN LOUISVILLE,
 KENTUCKY.  THYSSEN/CEA SUPPLIED A RETROFIT DUAL ALKALI DEMONSTRATION
 FGD SYSTEM FOR THIS UNIT. THE EMISSION CONTROL SYSTEM, DESIGNED TO REMOVE
 95X OF THE FLUE GAS S02, CONSISTS OF A COLD SIDE ESP AND TWO TRAY TOWER
 MODULES. THE CLEANED GAS PASSES THROUGH A CHEVRON MIST ELIMINATOR AND TWO
 DIRECT COMBUSTION REHEATERS BEFORE EXITING A 518 FOOT STACK. THE WATER
 LOOP IS CLOSED, AND THE SLUDGE IS DISPOSED IN AN ON-SITE LANDFILL.
 LOUISVILLE GAS  t  ELECTRIC
 MILL CREEK
 1
 RETROFIT  358 MW  (GROSS)
          358 MM  (ESC)
 COAL
 3.75 XS  BITUMINOUS
 LIME
 COMBUSTION ENGINEERING
 ENERGY CONSUMPTION:  1.4X
 STATUS 1     STARTUP 12/80
MILL CREEK 1 OF LOUISVILLE GAS AND ELECTRIC IS LOCATED IN LOUISVILLE, KEN-
TUCKY. A RETROFIT LIME FGD SYSTEM IS PRESENTLY OPERATING ON THIS PULVER-
IZED COAL (3.75X S, 11,500 BTU/LB) FIRED UNIT SUPPLIED BY COMBUSTION EN-
GINEERING.  AN ESP IS EMPLOYED FOR PARTICULATE CONTROL AND THE CLEANED
FLUE GAS EXITS A 600 FT STACK.  THE SYSTEM CAN OPERATE IN AN OPEN OR
CLOSED WATER LOOP MODE.  OPERATIONS BEGAN IN DECEMBER I960.
LOUISVILLE GAS t ELECTRIC
MILL CREEK
2
RETROFIT  350 MW (GROSS)
          350 MW (ESC)
COAL
 3.75 XS  BITUMINOUS
LIME
COMBUSTION ENGINEERING
ENERGY CONSUMPTION:  1.4X
STATUS 1     STARTUP 12/81
MILL CREEK 2 OF LOUISVILLE GAS AND ELECTRIC IS LOCATED IN LOUISVILLE, KEN-
TUCKY. A RETROFIT LIME FGD SYSTEM IS PRESENTLY OPERATING ON THIS PULVER-
IZED COAL (3.75X S, 11,500 BTU/LB) FIRED UNIT SUPPLIED BY COMBUSTION EN-
GINEERING.  AN ESP IS EMPLOYED FOR PARTICULATE CONTROL AND THE CLEANED
FLUE GAS EXITS A 600 FT STACK.  THE SYSTEM OPERATES IN A CLOSED WATER LOOP
MODE.  INITIAL START-UP TOOK PLACE IN DECEMBER 1981.
                                              2-15

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                  ABSTRACT
LOUISVILLE GAS i ELECTRIC
MILL CREEK
3
NEW       427 MW (GROSS)
          427 MW (ESC)
COAL
 3.87 XS  BITUMINOUS
LIME
AMERICAN AIR FILTER
ENERGY CONSUMPTION: *»**x
STATUS 1     STARTUP  8/78
LOUISVILLE GAS AND ELECTRIC'S MILL CREEK 3 IS A 3.87X S COAL (11,300 BTU/
LB) FIRED UNIT LOCATED IN LOUISVILLE, KENTUCKY. AMERICAN AIR FILTER SUP-
PLIED A CARBIDE LIME FGD SYSTEM FOR THIS UNIT WHICH WAS DESIGNED TO REMOVE
857. OF THE S02 FROM THE FLUE GAS. AN ESP IS FOLLOWED BY FOUR MOBILE BED
CONTACTORS AND A STEAM TUBE REHEATER. CLEANED FLUE GAS EXITS A 600 FT
STACK.  THE WATER LOOP IS OPEN AND THE LIME/FLYASH STABILIZED SLUDGE IS  -
PONDED.  THIS UNIT HAS BEEN OPERATIONAL SINCE AUGUST 1978.
 LOUISVILLE  GAS  t  ELECTRIC
 MILL CREEK
 4
 NEW      495 MW  (GROSS)
          495 MW  (ESC)
 COAL
  3.75 XS BITUMINOUS
 LIME
 AMERICAN AIR FILTER
 ENERGY CONSUMPTION: **«*X
 STATUS 1    STARTUP   7/82
MILL CREEK 4 OF LOUISVILLE GAS AND ELECTRIC IS A PULVERIZED BITUMINOUS
COAL (3.75X S, 11,500 BTU/LB) FIRED UNIT LOCATED IN LOUISVILLE, KENTUCKY.
THE EMISSION CONTROL SYSTEM CONSISTS OF AN ESP AND FOUR MOBILE BED CON-
TACTORS.  THE LIME FGD SYSTEM FOR THIS UNIT WAS SUPPLIED BY AMERICAN AIR
FILTER.  THE SYSTEM'S WATER LOOP IS CLOSED AND THE SLUDGE IS STABILIZED
WITH LIME AND FLYASH.  STEAM TUBES PROVIDE REHEAT OF THE CLEANED GASES
WHICH EXIT A 600 FT STACK.  INITIAL START-UP WAS IN JULY 1982.
 LOUISVILLE  GAS £ ELECTRIC
 PADDY'S RUN
 6
 RETROFIT   72  MW (GROSS)
            72  MW (ESC)
 COAL
  3.70 XS BITUMINOUS
 LIME
 COMBUSTION  ENGINEERING
 ENERGY CONSUMPTION:   E.8X
 STATUS 1     STARTUP 4/73
UNIT 6 AT LOUISVILLE GAS AND ELECTRIC'S PADDY'S RUN STATION IS A DRY BOT-
TOM PULVERIZED COAL (3.8X S, 11,300 BTU/LB) FIRED UNIT IN LOUISVILLE, KEN-
TUCKY. A RETROFIT CARBIDE LIME FGD SYSTEM BY COMBUSTION ENGINEERING TREATS
400,000 ACFM OF FLUE GAS FROM THE BOILER. AN ESP IS FOLLOWED BY TWO MARBLE
BED ABSORBERS, A DIRECT COMBUSTION REHEATER, AND A 250 FOOT STACK. MIST
ELIMINATION IS PROVIDED BY ONE CHEVRON/MODULE. THE LIME FIXATED SLUDGE IS
TRUCKED TO AN UNLINED POHD, AND THE WATER LOOP IS CLOSED. THE FGD SYSTEM
BEGAN INITIAL OPERATIONS IN APRIL 1973.
 LOUISVILLE GAS * ELECTRIC
 TRIMBLE COUNTY
 1
 NEW       575 MW (GROSS)
           575 MW (ESC)
 COAL
  4.00 XS  BITUMINOUS
 PROCESS NOT SELECTED
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION: ****X
 STATUS 5     STARTUP  7/87
 LOUISVILLE GAS AND ELECTRIC WILL BE INSTALLING FGD SYSTEMS ON TWO OF THE
 FOUR BOILERS AT THE UTILITY'S PLANNED TRIMBLE COUNTY STATION IN BEDFORD,
 KENTUCKY. THE PULVERIZED 4X S (IF NO COAL WASH IS INCLUDED) COAL FIRED
 UNITS' FLUE GAS WILL BE CLEANED BY ESP'S AND WET SCRUBBING ( 90X REMOVAL
 EFFICIENCY). SLUDGE DISPOSAL STRATEGY IS UNDECIDED. UNIT 1 IS SCHEDULED
 FOR START-UP IN JULY 1987.
 LOUISVILLE GAS & ELECTRIC
 TRIMBLE COUNTY
 2
 NEW       575 MW (GROSS)
           575 MW (ESC)
 COAL
  4.00 XS  BITUMINOUS
 PROCESS NOT SELECTED
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION: ****X
 STATUS 5     STARTUP  7/90
 LOUISVILLE GAS AND ELECTRIC WILL BE INSTALLING FGD SYSTEMS ON TWO OF THE
 FOUR BOILERS AT THE UTILITY'S PLANNED TRIMBLE COUNTY STATION IN BEDFORD,
 KENTUCKY. THE PULVERIZED 4X S (IF NO COAL WASH IS INCLUDED) COAL FIRED
 UNITS'  FLUE GAS WILL BE CLEANED BY ESP'S AND WET SCRUBBING (90X REMOVAL
 EFFICIENCY). SLUDGE DISPOSAL STRATEGY IS UNDECIDED. UNIT 2 IS SCHEDULED
 FOR START-UP IN 1990.
 LOWER COLORADO RIVER AUTH
 FAYETTE POWER PROJECT
 3
 NEW       451 MW (GROSS)
           451 MW (ESC)
 LIGNITE
  1.70 XS
 LIMESTONE
 COMBUSTION ENGINEERING
 ENERGY CONSUMPTION:  -.7X
 STATUS 2     STARTUP 11/87
 LOWER  COLORADO RIVER AUTHORITY HAS STARTED CONSTRUCTION ON  A  451  MW  UNIT,
 FAYETTE  POWER PROJECT  3, IN  LA GRANGE, TEXAS.  THE  LIGNITE  (1.7X  S,  4300
 BTU/LB)  FIRED BOILER WILL UTILIZE A WET  LIMESTONE SCRUBBING SYSTEM
 DESIGNED TO  REMOVE  90X 502.  AN ESP SUPPLIED BY FLAKT WILL  CONTROL
 PARTICLE EMISSIONS  AND THE CLEANED FLUE  GAS WILL EXIT THROUGH A 535  FOOT
 ACID BRICK LINED STACK.  SLUDGE WILL BE  FORCIBLY OXIDIZED BEFORE  BEING
 DISPOSED IN  AN ON-SITE LANDFILL.  OPERATIONS ARE SCHEDULED  TO COMMENCE  IN
 1988.
                                              2-16

-------
                                                  UTILITY F6D SURVEY:  OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
LOWER COLORADO RIVER AUTH
FAYETTE POWER PROJECT
4
NEW       451 MM (GROSS)
          451 MW (ESC)
LIGNITE
 1.70 XS
LIMESTONE
VENDOR NOT SELECTED
ENERGY CONSUMPTION: «***X
STATUS 6     STARTUP  6/90
            LOWER  COLORADO RIVER  AUTHORITY HAS  PLANS  FOR A 451 MW UNIT, FAYETTE
            POWER  PROJECT 4,  TO BE  LOCATED IN LA GRANGE TEXAS.  THE  LIGNITE  (1.7X S,
            4300 BTU/LB)  FIRED  BOILER  WILL UTILIZE  A  WET LIMESTONE SCRUBBING SYSTEM
            DESIGNED TO REMOVE  90X  302.   AN  EDP WILL  CONTROL  PARTICLE EMISSIONS AND
            THE  CLEANED FLUE  GAS  WILL  EXIT THROUGH  A  535 FOOT ACID BRICK  LINED STACK.
            SLUDGE WILL BE FORCE  OXIDIZED BEFORE BEING DISPOSED IN AN ON-SITE LAND-
            FILL.   INITIAL START-UP IS SCHEDULED FOR  JUNE 1990.
MARQUETTE BOARD OF
SHIRAS
3
NEW
           44 MW (GROSS)
           44 MW (ESC)
COAL
   .30 XS  SUBBITUMINOUS
LIME/SPRAY DRYING
GE ENVIRONMENTAL SERVICES
ENERGY CONSUMPTION: *«**X
STATUS 1     STARTUP  3/83
LIGHT t PWR SHIRAS 3 OF THE MARQUETTE  BOARD  OF  LIGHT AND  POWER  IS A PULVERIZED SUBBI-
            TUMINOUS COAL (.3X S,  8654 BTU/LB)  FIRED BOILER  LOCATED IN MARQUETTE,
            MICHIGAN.  GE ENVIRONMENTAL SERVICES  HAS SUPPLIED A LIME/SPRAY DRYING PRO-
            CESS TO CONTROL EMISSIONS.  FABRIC  FILTERS WITH  99.8X REMOVAL EFFICIENCY
            CONTROL PARTICULATE MATTER AND THE  CLEANED FLUE  GAS EXITS A 350 FT STACK.
            THE FGD WASTE IS DISPOSED  AT AN  OFF-SITE LANDFILL.   OPERATIONS COMMENCED
            IN MARCH 1983.
MICHIGAN SO CENTRAL PWR AGENCY
PROJECT
1
NEW        55 MW  (GROSS)
           55 MW  (ESC)
COAL
 3.25 XS  BITUMINOUS
LIMESTONE
BAECOCK & WILCOX
ENERGY CONSUMPTION:   1.8X
STATUS 1     STARTUP  5/83
            THE PROJECT 1 UNIT OF MICHIGAN SOUTH CENTRAL  POWER  AGENCY  IS  A  PULVERIZED
            COAL FIRED BOILER LOCATED IN LICHTFIELD,  MICHIGAN.   THE  EMISSION CONTROL
            SYSTEM CONSISTS OF A HOT SIDE ESP AND A BABCOCK  t WILCOX LIMESTONE SPRAY
            TOWER.  THE SPRAY TOWER MIST ELIMINATOR IS  FOLLOWED BY AN  IN-LINE REHEAT-
            ER AND A 250 FOOT STACK.  THE SYSTEM OPERATES IN A  CLOSED  WATER LOOP AND
            SLUDGE IS DISPOSED AT AN OFF-SITE LANDFILL.   OPERATIONS  COMMENCED IN MAY
            1983.
MIDDLE SOUTH UTILITIES
WILTON
1
NEW       890 MW  (GROSS)
          890 MW  (ESC)
COAL
   .50 XS
LIMESTONE
COMBUSTION  ENGINEERING
ENERGY CONSUMPTION:  ****X
STATUS 4     STARTUP 99/99
            WILTON 1 IS A COAL (.50X S) FIRED BOILER TO BE  LOCATED  IN CONVENT,  LOUI-
            SIANA.  MIDDLE SOUTH  UTILITIES HAS SIGNED A LETTER  OF INTENT WITH COMBUS-
            TION ENGINEERING FOR  A WET LIMESTONE SCRUBBING  SYSTEM FOR EMISSION
            CONTROL.  START-UP HAS BEEN DEFERRED INDEFINITELY.
MIDDLE SOUTH UTILITIES
WILTON
2
NEW       890 MW  (GROSS)
          890 MW  (ESC)
COAL
   .50 XS
LIMESTONE
COMBUSTION ENGINEERING
ENERGY CONSUMPTION: ****X
STATUS 4     STARTUP 99/99
            WILTON 2 IS A COAL (.50X S) FIRED BOILER TO BE LOCATED IN CONVENT,  LOUI-
            SIANA.  MIDDLE SOUTH UTILITIES HAS SIGNED A LETTER OF INTENT WITH COMBUS-
            TION ENGINEERING FOR A WET LIMESTONE SCRUBBING SYSTEM FOR EMISSION
            CONTROL.  START-UP HAS BEEN DEFERRED INDEFINITELY.
MINNESOTA POWER & LIGHT
CLAY BOSWELL
4
NEW       554 MW (GROSS)
          475 MW (ESC)
COAL
   .94 XS  SUBBITUMINOUS
LIME/ALKALINE FLYASH
PEABODY PROCESS SYSTEMS
ENERGY CONSUMPTION:  1.3X
STATUS 1     STARTUP  2/80
            CLAY BOSWELL 4 OF MINNESOTA POWER AND LIGHT IS A SUBBITUMINOUS COAL (0.94X
            S, 8287 BTU/LB) FIRED UNIT LOCATED IN COHASSET, MINNESOTA.  PEABODY PRO-
            CESS SYSTEMS HAS SUPPLIED A LIME/ALKALINE FLYASH SYSTEM WHICH IS DESIGNED
            TO REMOVE 64.6X OF THE S02 IN THE FLUE GAS. PARTICULATE MATTER AND ADD-
            ITIONAL S02 CONTROL IS ACHIEVED WITH VENTURI SCRUBBERS (ONE HOT SIDE ESP
            CONTROLS PARTICULATE MATTER IN THE BYPASS FLUE GAS STREAM).  MIST ELIMINA-
            TION IS PROVIDED BY A SIEVE TRAY FOLLOWED BY A SPIN VANE CHEVRON, AND RE-
            HEAT IS SUPPLIED BY BYPASSING 5X OF THE FLUE GAS.  THE SYSTEM OPERATES IN
            A CLOSED WATER LOOP MODE, SLUDGE IS DISPOSED IN A LINED POND AND FLUE GAS
            EXITS A 600 FT STACK.  OPERATIONS COMMENCED IN FEBRUARY 1980.
                                              2-17

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS Of FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
MINNKOTA POWER
MILTON R. YOUNG
Z
NEW       440 MW (GROSS)
          374 MW (ESC)
COAL
   .60 XS  LIGNITE
LIME/ALKALINE FLYASH
THYSSEN/CEA
ENERGY CONSUMPTION:  1.6X
STATUS 1     STARTUP  9/77
                               MINNKOTA  POWER  COOPERATIVE'S  MILTON  R.  YOUNG  2  IS A CYCLONE  FIRED  LIGNITE
                               (0.60XS,  6500 BTU/LB)  BOILER  LOCATED IN CENTER,  NORTH  DAKOTA.  THE  BOILER
                               PRODUCES  2,021,400  ACFM OF  FLUE  GAS, HALF  OF  WHICH IS  CLEANED  BY TWO ESP'S
                               AND  TWO THYSSEN/CEA LIME/ALKALINE  FYLASH SPRAY  TOWERS  (75X DESIGN
                               S02  REMOVAL EFFICIENCY).  THE CLEANED GAS  PASSES THROUGH  A CHEVRON
                               MIST ELIMINATOR BEFORE IT JOINS  A  15X BYPASS  REHEAT  (HOT  UNSCRUEBED
                               GAS),  AND EXITS A 550  FOOT  STACK.  THE WATER LOOP IS CLOSED,  AND THE
                               SLUDGE IS TRUCKED TO AN OFF-SITE MINEFILL.  OPERATIONS BEGAN IN 1977.
 MONONGAHELA  POWER
 PLEASANTS
 1
 NEW
           626  MW  (GROSS)
           626  MW  (ESC)

           BITUMINOUS
COAL
 3.00 XS
LIME
BABCOCK t WILCOX
ENERGY CONSUMPTION:  2.4X
STATUS 1     STARTUP 12/78
MONONGAHELA POWER PLEASANTS 1 IS A BITUMINOUS COAL (3.00X S, 12,500
BTU/LB) FIRED BOILER IN WILLOW ISLAND, WEST VIRGINIA.  BABCOCK AMD WIL-
COX SUPPLIED A LIME FGD SYSTEM DESIGNED TO REMOVE 90X OF THE FLUE GAS S02
FROM THIS UNIT. THE EMISSION CONTROL SYSTEM INCLUDES AN ESP UPSTREAM OF
FOUR SPRAY TOWER ABSORBERS.  A FLUE GAS BYPASS SYSTEM PROVIDES REHEAT OF
THE CLEANED GAS BEFORE IT IS DISCHARGED THROUGH A 1000 FOOT PLACITE LINED
STACK. THE SYSTEM OPERATES IN A CLOSED WATER LOOP.  THE FGD SYSTEM ON THIS
UNIT HAS BEEN OPERATIONAL SINCE DECEMBER 1978.
 MONONGAHELA POWER
 PLEASANTS
 2
 NEW       626 MW (GROSS)
           626 MW (ESC)
 COAL
  3.00 XS  BITUMINOUS
 LIME
 BAECOCK & WILCOX
 ENERGY CONSUMPTION:   2.4X
 STATUS 1     STARTUP 10/80
                               MONONGAHELA POWER PLEASANTS 2 IS A BITUMINOUS COAL (3.00 XS,  12,500 BTU/
                               LB) FIRED BOILER LOCATED IN WILLOW ISLAND,  WEST VIRGINIA.   BABCOCK AND
                               WILCOX SUPPLIED A LIME FGD SYSTEM DESIGNED  TO REMOVE 90X OF THE BOILER
                               FLUE GAS SOS.   THE EMISSION CONTROL SYSTEM  ON THIS UNIT INCLUDES AN ESP
                               UPSTREAM OF FOUR SPRAY TOWER ABSORBERS.   A  FLUE GAS BYPASS SYSTEM PROVIDES
                               REHEAT OF THE  CLEANED GAS BEFORE IT IS DISCHARGED THROUGH A 1000 FOOT
                               ACID BRICK STACK.  THE SYSTEM OPERATES IN A CLOSED WATER LOOP.   THE FGD
                               SYSTEM OPERATION COMMENCED IN OCTOBER 1980.
 MONTANA POWER
 COLSTRIP
 1
 NEW       360 MW (GROSS)
           360 MW (ESC)
 COAL
   .78 XS  SUBBITUMINOUS
 LIME/ALKALINE FLYASH
 THYSSEN/CEA
 ENERGY CONSUMPTION:  3.3X
 STATUS 1     STARTUP  9/75
                               COLSTRIP 1 OF MONTANA POWER IS A 360-MW (GROSS) SUBBITUMINOUS COAL
                               (0.78X S, 8843 BTU/LB) FIRED UNIT LOCATED IN COLSTRIP,  MONTANA.  THYSSEN/
                               CEA SUPPLIED A LIME/ALKALINE FLYASH FGD SYSTEM CONSISTING OF THREE
                               VENTURI SCRUBBER/SPRAY TOWER ABSORBER MODULES. THE TOWERS ARE FOLLOWED
                               BY HORIZONTAL CHEVRON MIST ELIMINATORS, A STEAM TUBE REHEATER, AND A 503
                               FOOT STACK. THE UNSTABILIZED SLUDGE IS DISPOSED IN AN ON-SITE LINED POND.
                               THE WATER LOOP IS CLOSED. OPERATIONS INITIALLY BEGAN IN SEPTEMBER 1975.
 MONTANA POWER
 COLSTRIP
 2
 NEW       360 MM (GROSS)
           360 MW (ESC)
 COAL
   .78 XS  SUBBITUMINOUS
 LIME/ALKALINE FLYASH
 THYSSEN/CEA
 ENERGY CONSUMPTION:  3.3X
 STATUS 1     STARTUP  5/76
                               COLSTRIP 2 OF MONTANA POWER IS A 360-MW (GROSS) SUBBITUMINOUS COAL
                               (0.78X S, 8843 BTU/LB) FIRED UNIT LOCATED IN COLSTRIP, MONTANA.  THYSSEN/
                               CEA SUPPLIED A LIME/ALKALINE FLYASH FGD SYSTEM CONSISTING OF THREE
                               VENTURI SCRUBBER/SPRAY TOWER ABSORBER TRAINS. THE ABSORBERS ARE FOLLOWED
                               BY HORIZONTAL CHEVRON MIST ELIMINATORS, A STEAM TUBE REHEATER, AND A 503
                               FOOT STACK. THE UHSTABILIZED SLUDGE IS DISPOSED IN AN ON-SITE LINED POND.
                               THE WATER LOOP IS CLOSED. OPERATIONS INITIALLY BEGAN IN MAY 1976.
 MONTANA POWER
 COLSTRIP
 3
 NEW       778 MW (GROSS)
           778 MW (ESC)
 COAL
   .70 XS
 LIME/ALKALINE FLYASH
 BECHTEL/MONTANA POWER
 ENERGY CONSUMPTION: **»*X
 STATUS 1     STARTUP 10/83
                               MONTANA POWER'S COLSTRIP 3 IS A LOW SULFUR COAL (0.7X S, 8500 BTU/LB)
                               FIRED UNIT LOCATED IN COLSTRIP, MONTANA. A LIME/ALKALINE FLY-
                               ASH FGD SYSTEM SUPPLIED BY BECHTEL/MONTANA POWER CONTROLS S02 EMISSIONS
                               AT THIS UNIT.  PARTICLE SCRUBBERS ARE EMPLOYED FOR THE CONTROL OF PART-
                               TICULATE MATTER AND THE SYSTEM OPERATES IN A CLOSED WATER LOOP MODE
                               FLUE GAS EXITS A 692 FT STACK.  START-UP COMMENCED IN OCTOBER 1983
                                              2-18

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1963 - SEPTEMBER 1984
                                             SECTION Z
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
MONTANA POWER
COLSTRIP
4
NEW       778 MW (GROSS)
          778 MW (ESC)
COAL
  .70 XS
LIME/ALKALINE FLYASH
BECHTEL/MONTANA POWER
ENERGY CONSUMPTION: ****X
STATUS Z     STARTUP 10/85
                     MONTANA  POWER'S  COLSTRIP  4  IS  A  LOW SULFUR COAL  (0.7X S, 8800 BTU/LB)
                     FIRED  UNIT  UNDER CONSTRUCTION  IN COLSTRIP, MONTANA. A LIME/ALKALINE FLY-
                     ASH FGD  SYSTEM IS BEING BUILT  BY BECHTEL/MONTANA POWER FOR 95X S02 REMOVAL
                     EFFICIENCY  AT THIS UNIT.  PARTICLE SCRUBBERS WILL BE EMPLOYED FOR THE
                     CONTROL  OF  PARTICULATE  MATTER  WITH REHEAT FROM IN-LINE STEAM AND THE SYS-
                     TEM WILL OPERATE IN A CLOSED WATER LOOP MODE.  SLUDGE WILL BE FORCE
                     OXIDIZED BEFORE  BEING DISPOSED IN AN ON-SITE POND.  START-UP IS SCHEDULED
                     FOR OCTOBER 1985.
MONTANA-DAKOTA UTILITIES
COYOTE
1
NEW       440 MW (GROSS)
          440 MW (ESC)
COAL
   .87 XS  LIGNITE
SODIUM CARBONATE/SPRAY DRYING
WHEE LA3RATOR-FRYE/R.I.
ENERGY CONSUMPTION:  1.1X
STATUS 1     STARTUP  4/81
                     COYOTE 1 IS A CYCLONE  FIRED  PULVERIZED  LIGNITE  (0.87X S, 7050 BTU/LB)
                     BOILER OPERATING IN BEULAH,  NORTH DAKOTA.  THIS UNIT IS JOINTLY OWNED
                     BY FIVE UTILITIES,  WITH MONTANA-DAKOTA  UTILITIES BEING THE MAJOR
                     OWNER AND CONSTRUCTOR.   A  SODIUM CARBONATE DRY  FGD SYSTEM DESIGNED TO
                     REMOVE 70X OF THE S02  WAS  SUPPLIED BY WHEELABRATOR-FRYE AND ROCKWELL
                     INTERNATIONAL. THE SPRAY DRYER/BAGHOUSE SYSTEM  COMMENCED OPERATION IN
                     APRIL 1981.
MUSCATINE
MUSCATINE
9
NEW
POWER & WATER
          166 MW  (GROSS)
          166 MW  (ESC)
COAL
 3.21 XS  BITUMINOUS
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION:  4.8X
STATUS 1     STARTUP  4/83
                     MUSCATINE 9 IS A PULVERIZED  BITUMINOUS  COAL  (3.21X S, 11,220 BTU/LB) FIRED
                     UNIT LOCATED IN MUSCATINE, IOWA.   RESEARCH-COTTRELL SUPPLIED A LIMESTONE
                     SCRUBBING SYSTEM FOR  EMISSION CONTROL.  THE FGD SYSTEM FEATURES AN ESP,
                     TWO 100X CAPACITY ABSORBER TOWERS,  STEAM COIL REHEAT, A CLOSED WATER LOOP,
                     FORCED OXIDATION OF THE SLUDGE BEFORE LANDFILL AND A 300 FOOT STACK.  THE
                     DESIGN S02 REMOVAL EFFICIENCY IS  94X.   OPERATIONS INITIALLY BEGAN IN
                     APRIL 1983.
NEBRASKA  PUBLIC  POWER DISTRICT FOSSIL III 1 IS A PULVERIZED SUBBITUMINOUS COAL (0.36X S, 8000 BTU/LB)
FOSSIL III
1
NEW       650 MW  (GROSS)
          650 MW  (ESC)
COAL
   .36 XS  SUBBITUMINOUS
PROCESS NOT SELECTED
VENDOR NOT SELECTED
ENERGY CONSUMPTION: ****x
STATUS 6     STARTUP  3/96
                     FIRED UNIT PLANNED BY THE NEBRASKA PUBLIC POWER  DISTRICT  TO  BE  LOCATED
                     NEAR SARGENT, NEBRASKA.   THE UTILITY IS CONSIDERING  A  DRY SCRUBBING
                     FGD PROCESS TO CONTROL EMISSIONS FROM THE 650  MW BOILER.   START-UP FOR
                     THE UNIT IS TENTATIVELY  SCHEDULED FOR MARCH  1996.
NEVADA POWER
HARRY ALLEN
1
NEW       500 MW  (GROSS)
          500 MW  (ESC)
COAL
***** XS
PROCESS NOT SELECTED
VENDOR NOT SELECTED
ENERGY CONSUMPTION: ****X
STATUS 6     STARTUP  0/94
                     NEVADA POWER'S HARRY ALLEN 1 IS A PLANNED COAL FIRED UNIT TO BE  LOCATED IN
                     LAS VEGAS, NEVADA. THE UTILITY IS CONSIDERING A HOT SIDE ESP IN  CONJUNC-
                     TION WITH AN FGD SYSTEM.  SPECIFICATIONS HAVE NOT YET BEtN PREPARED.  START-
                     UP IS SCHEDULED FOR 1994.
NEVADA POWER
HARRY ALLEN
2
NEW       500 MM (GROSS)
          500 MW (ESC)
COAL
***** XS
PROCESS NOT SELECTED
VENDOR NOT SELECTED
ENERGY CONSUMPTION: ****X
STATUS 6     STARTUP  0/95
                     NEVADA POWER'S HARRY ALLEN 2 IS A PLANNED COAL FIRED UNIT TO BE LOCATED IN
                     LAS VEGAS, NEVADA. THE UTILITY IS CONSIDERING A HOT SIDE ESP IN CONJUNC-
                     TION WITH AN FGD SYSTEM. SPECIFICATIONS HAVE NOT YET BEEN PREPARED. START-
                     UP IS SCHEDULED FOR 1995.
                                             2-19

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                  ABSTRACT
NEVADA POKER
HARRY ALLEN
3
NEW       500 MW (GROSS)
          500 MW (ESC)
COAL
***** xs
PROCESS NOT SELECTED
VENDOR NOT SELECTED
ENERGY CONSUMPTION: ****X
STATUS 6     STARTUP  0/96
NEVADA POWER'S HARRY ALLEN 3 IS A PLANNED COAL FIRED UNIT TO BE LOCATED IN
LAS VEGAS, NEVADA. THE UTILITY IS CONSIDERING A HOT SIDE ESP IN CONJUNC-
TION WITH AN FGD SYSTEM. SPECIFICATIONS HAVE NOT YET BEEN PREPARED. START-
UP IS SCHEDULED FOR 1996.
 NEVADA  POWER
 HARRY ALLEN
 4
 NEW        500  MW  (GROSS)
           500  MW  (ESC)
 COAL
 ***** xs
 PROCESS NOT SELECTED
 VENDOR  NOT SELECTED
 ENERGY  CONSUMPTION: ****X
 STATUS  6      STARTUP   0/97
NEVADA POWER'S HARRY ALLEN 4 IS A PLANNED COAL FIRED UNIT TO BE LOCATED IN
LAS VEGAS, NEVADA. THE UTILITY IS CONSIDERING A HOT SIDE ESP IN CONJUNC-
TION WITH AN FGD SYSTEM. SPECIFICATIONS HAVE NOT YET BEEN PREPARED. START-
UP IS SCHEDULED FOR 1997.
 NEVADA POWER
 REID GARDNER
 1
 RETROFIT  125 MW (GROSS)
           125 MW (ESC)
 COAL
   .50 XS  BITUMINOUS
 SODIUM CARBONATE
 THYSSEN/CEA
 ENERGY CONSUMPTION:  ****x
 STATUS 1     STARTUP  3/74
REID GARDNER 1 IS A 125-MW (GROSS) WET BOTTOM LOW SULFUR COAL (0.5X S,
12,450 BTU/LB) FIRED UNIT OWNED BY NEVADA POWER, LOCATED IN MOAPA, NEVADA.
THE THYSSEN/CEA SODIUM CARBONATE-BASED (TRONA) SCRUBBING SYSTEM
CONSISTS OF ONE MODULE CONTAINING TWIN VARIABLE THROAT VENTURIS FOL-
LOWED BY A SEPARATOR IN SERIES WITH A SINGLE STAGE PEFORATED PLATE WASH
TOWER. PRIMARY PARTICULATE CONTROL IS PROVIDED BY UPSTREAM MULTICLOK'ES.
A RADIAL VANE MIST ELIMINATOR PRECEDES AN INDIRECT STEAM COIL REHEATER
AND A 200 FOOT STACK. THE SYSTEM OPERATES IN A CLOSED WATER LOOP, AND THE
SLUDGE IS DISPOSED IN AN ON-SITE CLAY LINED SOLAR EVAPORATION POND. THE
DESIGN S02 REMOVAL EFFICIENCY IS 90X. THE SYSTEM HAS BEEN OPERATIONAL
SINCE MARCH 1974.
 NEVADA POWER
 REID GARDNER
 2
 RETROFIT  125 MW (GROSS)
           125 MW (ESC)
 COAL
   .50 XS  BITUMINOUS
 SODIUM CARBONATE
 THYSSEN/CEA
 ENERGY CONSUMPTION: ****X
 STATUS 1     STARTUP  4/74
REID GARDNER 2 IS A 125-MW (GROSS) WET BOTTOM LOW SULFUR COAL (0.5X S,
12,450 BTU/LB) FIRED UNIT OWNED BY NEVADA POWER, LOCATED IN MOAPA, NEVADA.
THE THYSSEN/CEA SODIUM CARBONATE-BASED (TRONA) SCRUBBING SYSTEM
CONSISTS OF ONE MODULE CONTAINING TWIN VARIABLE THROAT VENTURIS FOL-
LOWED BY A SEPARATOR IN SERIES WITH A SINGLE STAGE PEFORATED PLATE WASH
TOWER. PRIMARY PARTICULATE CONTROL IS PROVIDED BY UPSTREAM MULTICLONES.
A  RADIAL VANE MIST ELIMINATOR PRECEDES AN INDIRECT STEAM COIL REHEATER
AND A 200 FOOT STACK. THE SYSTEM OPERATES IN A CLOSED WATER LOOP, AND THE
SLUDGE IS DISPOSED IN AN ON-SITE CLAY LINED SOLAR EVAPORATION POND. THE
DESIGN S02 REMOVAL EFFICIENCY IS 90X. THE SYSTEM HAS BEEN OPERATIONAL
SINCE APRIL 1974.
 NEVADA POWER
 REID GARDNER
 3
 NEW       125 MW (GROSS)
           125 MW (ESC)
 COAL
   .50 XS  BITUMINOUS
 SODIUM CARBONATE
 THYSSEN/CEA
 ENERGY CONSUMPTION: ****x
 STATUS 1     STARTUP  6/76
 REID  GARDNER  3  IS  A 125-MW  (GROSS) WET BOTTOM LOW SULFUR BITUMINOUS  COAL
 (0.5X S,  12,450 BTU/LB) FIRED FOSTER WHEELER UNIT LOCATED  IN MOAPA,
 NEVADA.   THE  THYSSEN/CEA SODIUM CARBONATE-BASED (TRONA) SCRUBBING  SYSTEM
 CONSISTS  OF ONE MODULE CONTAINING TWIN VARIABLE THROAT VENTURIS  FOL-
 LOWED BY  A SEPARATOR  IN SERIES WITH A SINGLE STAGE PERFORATED  PLATE  WASH
 TOWER.  PRIMARY  PARTICULATE  CONTROL IS PROVIDED BY UPSTREAM MULTICLONES.
 A RADIAL  VANE MIST ELIMINATOR PRECEDES AN INDIRECT STEAM COIL  REHEATER
 AND A 200 FOOT  STACK. THE SYSTEM OPERATES IN A CLOSED WATER  LOOP,  AND THE
 SLUDGE IS DISPOSED IN AN ON-SITE CLAY LINED SOLAR EVAPORATION  POND.  THE
 DESIGN S02 REMOVAL EFFICIENCY IS 90X. THE SYSTEM HAS BEEN  OPERATIONAL
 SINCE JUNE 1976.
 NEVADA POWER
 REID GARDNER
 4
 NEW       295 MW (GROSS)
           250 MW (ESC)
 COAL
   .75 XS
 SODIUM CARBONATE
 THYSSEN/CEA
 ENERGY CONSUMPTION: **#*x
 STATUS 1     STARTUP  6/83
 REID GARDNER  4  IS  A  295 MW  (GROSS)  LOW SULFUR COAL  (0.75X  S,  11,500  BTU/
 LB)  FIRED  UNIT  LOCATED IN MOAPA, NEVADA.  THE EMISSION CONTROL  SYSTEM CON-
 SISTS OF A THYSSEN/CEA SODIUM  CARBONATE FGD  SYSTEM  FOR S02 CONTROL.   A
 BAGHOUSE PRECEDES  THE FGD SYSTEM FOR  PARTICULATE  MATTER  CONTROL.   THE SYS-
 TEM  OPERATES  IN AN OPEN WATER  LOOP  MODE AND  FLUE  GAS EXITS A  500  FT  STACK
 OPERATIONS COMMENCED IN JUNE 1983.
                                              2-20

-------
                                                  UTILITY F6D SURVEY:  OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
NEW YORK STATE ELEC t GAS
SOMERSET
1
NEW       625 MM (GROSS)
          625 MM (ESC)
COAL
 2.70 XS  BITUMINOUS
LIMESTONE
PEABODY PROCESS SYSTEMS
ENERGY CONSUMPTION: »***X
STATUS 1     STARTUP  7/84
THE NEW YORK STATE ELECTRIC & GAS CORP.  IS OPERATING A PULVERIZED BITUMI-
NOUS COAL (2.2X S, 13,000 BTU/LB) FIRED  BOILER SUPPLIED BY BABCOCK ft
WILCOX, IN SOMERSET, NEW YORK WHICH GENERATES A FLUE GAS FLOW OF 2,862,000
ACFM.  A COLD SIDE ESP WITH A DESIGN EFFICIENCY OF 99.7X PROVIDES THE  PRI-
MARY PARTICULATE REMOVAL.  PEABODY PROCESS SYSTEMS SUPPLIED A LIMESTONE
FGD SYSTEM WITH A DESIGN REMOVAL EFFICIENCY OF 90X FOR S02 CONTROL.  THE
SYSTEM OPERATES IN A CLOSED WATER LOOP MODE AND FLUE GAS PASSES THROUGH AN
IN-LINE STEAM REHEATER INTO A 450 FT STACK.  THE SLUDGE IS DEWATERED AND
STABILIZED BEFORE ON-SITE LANDFILLED. OPERATIONS COMMENCED IN JULY  1984.
NIAGARA MOHAWK POWER
CHARLES R. HUNTLEY
66
RETROFIT  100 MW (GROSS)
          100 MM (ESC)
COAL
 1.80 XS
AQUEOUS CARBONATE/SPRAY DRYING
ROCKWELL INTERNATIONAL
ENERGY CONSUMPTION: **»*X
STATUS 1     STARTUP  4/82
CHARLES R. HUNTLEY 66 OF NIAGARA POWER COOP IS A PULVERIZED  COAL (1.8X  S,
12,500 BTU/LB) FIRED UNIT LOCATED IN BUFFALO,  NEW YORK.   ROCKWELL INTER-
NATIONAL DESIGNED AND INSTALLED A 90X EFFICIENT AQUEOUS  CARBONATE
FGD SYSTEM WHICH PRODUCES ELEMENTAL SULFUR AS  AN END PRODUCT.   FUNDS
WERE PROVIDED BY THE U.S. EPA AND THE EMPIRE STATE ELECTRIC  ENERGY
RESEARCH CORP. A SPRAY DRYER IS FOLLOHED BY TMO BANKS OF 8 CYCLONES,  AN
ESP, AND A LINED 200 FOOT CARBON STEEL STACK.   THE WATER LOOP  IS OPEN.
START-UP OF THE FGD SYSTEM WAS IN APRIL, 1982.
NORTHERN INDIANA PUB SERVICE
SCHAHFER
17
NEW       391 MW (GROSS)
          391 MW (ESC)
COAL
 3.20 XS  BITUMINOUS
DUAL ALKALI
FMC
ENERGY CONSUMPTION: ****•/.
STATUS 1     STARTUP  4/83
SCHAHFER 17 OF NORTHERN INDIANA PUBLIC SERVICE IS A 391 MW (GROSS)  COAL
(3.2X S, 10,900 BTU/LB) FIRED UNIT LOCATED IN WHEATFIELD, INDIANA.   THE
FMC EMISSION CONTROL SYSTEM CONSISTS OF AN ESP FOLLOWED BY FOUR DUAL
ALKALI WET ABSORBERS.  THE CLEANED FLUE GAS IS REHEATED AND EXITS VIA A
500 FOOT STACK.  INITIAL OPERATIONS COMMENCED IN APRIL 1983.
NORTHERN INDIANA  PUB SERVICE
SCHAHFER
16
NEW       391 MM  (GROSS)
          391 MW  (ESC)
COAL
 3.20 XS  BITUMINOUS
DUAL ALKALI
FMC
ENERGY CONSUMPTION: ««**X
STATUS 2     STARTUP  6/86
SCHAHFER 18 OF NORTHERN INDIANA PUBLIC SERVICE IS A COAL (3.2X S, 11,085
BTU/LB) FIRED UNIT UNDER CONSTRUCTION IN WHEATFIELD, INDIANA. THE UTILITY
AWARDED A CONTRACT TO FMC FOR THE INSTALLATION OF A DUAL ALKALI
FGD SYSTEM AT THIS UNIT. PARTICULATE MATTER WILL BE COLLECTED BY AN ESP
AND THE SYSTEM WILL INCLUDE A REHEATER.  START-UP OF THIS UNIT IS
SCHEDULED FOR JUNE 1986.
NORTHERN STATES POWER
RIVERSIDE
6-7
RETROFIT  110 MW  (GROSS)
          110 MW  (ESC)
COAL
 1.20 XS  SUBBITUMINOUS
LIME/SPRAY DRYING
JOY MFG/NIRO ATOMIZER
ENERGY CONSUMPTION: *«**X
STATUS 1     STARTUP 11/80
RIVERSIDE 6 AND 7 ARE TWO COAL FIRED BOILERS OWNED BY NORTHERN STATES
POWER AND LOCATED IN MINNEAPOLIS, MINNESOTA.  EACH BOILER GENERATES A FLUE
GAS FLOW OF 340,000 ACFM AT 350 F. CURRENTLY, A DEMONSTRATION LIME/SPRAY
DRYING FGD SYSTEM THAT IS CAPABLE OF TREATING THE FLUE GAS FROM BOTH
BOILERS IS BEING TESTED AT THIS UNIT. THE SYSTEM WAS SUPPLIED BY NIRO
ATOMIZER/JOY MANUFACTURING AND CONSISTS OF A SPRAY DRYER FOLLOWED BY
A BAGHOUSE.  THE CLEAN FLUE GAS IS VENTED TO TWO 275 FT CONCRETE STACKS
WITH FIRE BRICK LINERS.  SPENT ABSORBENT IS BEING DISPOSED OF IN AN
OFF-SITE LANDFILL.  OPERATIONS COMMENCED IN NOVEMBER 1980.
NORTHERN STATES POWER
SHERBURNE
1
NEW       750 MM (GROSS)
          750 MW (ESC)
COAL
   .80 XS  SUBBITUMINOUS
LIMESTONE/ALKALINE FLYASH
COMBUSTION ENGINEERING
ENERGY CONSUMPTION:  4.OX
STATUS 1     STARTUP  3/76
NORTHERN STATES POWER'S SHERBURNE 1 IS A BALANCED DRAFT PULVERIZED SUBBI-
TUMINOUS COAL (0.80X S, 8400 BTU/LB) FIRED BOILER IN BECKER, MINNESOTA. A
SOX EFFICIENT (DESIGN) LIMESTONE/ALKALINE FLYASH FGD SYSTEM SUPPLIED BY
COMBUSTION ENGINEERING HAS BEEN OPERATIONAL ON THIS UNIT SINCE MARCH
1976. TWELVE VARIABLE THROAT ROD DECK VENTURI/MARBLE BED ABSORBER TRAINS
ARE FOLLOWED BY ONE CHEVRON MIST ELIMINATOR/TRAIN, AN IN-LINE HOT WATER
REHEATER, AND A 650 FOOT COR-TEN LINED STACK. THE SLUDGE IS FORCIBLY OXI-
DIZED AND DISPOSED IN A CLAY LINED SETTLING POND. THE WATER LOOP IS OPEN.
                                              2-21

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS Of FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
NORTHERN STATES POWER
SHERBURNE
2
NEW       750 MW (GROSS)
          750 MW (ESC)
COAL
   .80 XS  SUBBITUMINOUS
LIMESTONE/ALKALINE FLYASH
COMBUSTION  ENGINEERING
ENERGY  CONSUMPTION:  4.OX
STATUS  1     STARTUP  3/77
NORTHERN STATES POWER'S SHERBURNE 2 IS A BALANCED DRAFT PULVERIZED SUBBI-
TUMINOUS COAL (0.80X S, 8400 BTU/LB) FIRED BOILER IN BECKER, MINNESOTA. A
SOX EFFICIENT (DESIGN) LIMESTONE/ALKALINE FLYASH FGD SYSTEM SUPPLIED BY
COMBUSTION ENGINEERING HAS BEEN OPERATIONAL ON THIS UNIT SINCE MARCH
1977. TWELVE VARIABLE THROAT ROD DECK VENTURI/MARBLE BED ABSORBER TRAINS
ARE FOLLOWED BY ONE CHEVRON MIST ELIMINATOR/TRAIN, AN IN-LINE HOT WATER
REHEATER, AND A 650 FOOT COR-TEN LINED STACK. THE SLUDGE IS FORCIBLY OXI-
DIZED AND DISPOSED IN A CLAY LINED SETTLING POND. THE WATER LOOP IS OPEN.
 NORTHERN STATES  POWER
 SHERBURNE
 3
 NEW       860  MW (GROSS)
           810  MW (ESC)
 COAL
  1.00  XS  SUBBITUMINOUS
 LIME/SPRAY DRYING
 JOY MFG/NIRO ATOMIZER
 ENERGY CONSUMPTION:  ****X
 STATUS Z    STARTUP  0/88
NORTHERN STATES POWER, SHERBURNE 3 IS A 800 MW (NET) PULVERIZED COAL
(l.OX S, 8700 BTU/LB) FIRED BOILER UNDER CONSTRUCTION AND ADJACENT TO
THE SHERBURNE 1 AND 2 UNITS IN BECKER, MINNESOTA. THE UTILITY AWARDED A
CONTRACT TO JOY MFG/NIRO ATOMIZER FOR A LIME SPRAY DRYING SYSTEM TO CON-
TROL SOS EMISSIONS.  FABRIC FILTERS WILL BE EMPLOYED FOR PARTICULATE CON-
TROL.  THE SYSTEM WILL OPERATE IN A CLOSED MATER LOOP MODE.  INITIAL START
UP IS SCHEDULED FOR JANUARY 1988.
 ORLANDO UTILITIES COMMISSION
 C.H.  STANTON
 1
 NEW       465 MW (GROSS)
           465 MW (ESC)
 COAL
 ***** XS
 LIMESTONE
 COMBUSTION ENGINEERING
 ENERGY CONSUMPTION:  ****X
 STATUS 2     STARTUP  0/87
ORLANDO UTILITIES COMMISSION IS CONSTRUCTING  A 465 MW (GROSS), COAL FIRED
UNIT, C.H. STANTON 1, NEAR ORLANDO, FLORIDA.  THE UTILITY WILL CONTROL
PARTICLE MATTER VIA ESP.  S02 EMISSIONS WILL BE CONTROLLED WITH A WET
LIMESTONE FGD SYSTEM WITH A REMOVAL EFFICIENCY OF 90X, SUPPLIED BY
COMBUSTION ENGINEERING.  INITIAL START-UP IS SET FOR THE FALL OF 1987.
 PACIFIC POWER & LIGHT
 JIM BRIDGER
 1
 RETROFIT  550 MW (GROSS)
           550 MW (ESC)
 COAL
   .56 XS  SUBBITUMINOUS
 SODIUM CARBONATE
 BABCOCK & WILCOX
 ENERGY CONSUMPTION:   .2X
 STATUS 3     STARTUP  0/90
 PACIFIC POWER AND  LIGHT'S JIM BRIDGER 1 IS A DRY BOTTOM  PULVERIZED SUB-
 BITUMINOUS COAL  (0.56XS, 9300 BTU/LB) FIRED BOILER SUPPLIED BY  COMBUSTION
 ENGINEERING AND  LOCATED IN ROCK SPRINGS, WYOMING.  THE UTILITY  HAS AWARD-
 ED A CONTRACT TO BABCOCK & WILCOX FOR A RETROFIT WET SODIUM CARBONATE  FGD
 SYSTEM, WHICH TREATS 2,700,000 ACFM OF FLUE GAS.  A COLD-SIDE ESP IS CUR-
 RENTLY IN OPERATION FOR PRIMARY PARTICULATE CONTROL.  THE  FGD SYSTEM WILL
 OPERATE IN A CLOSED WATER LOOP MODE AND FLUE GAS WILL EXIT A 500  FT STACK.
 START-UP IS SCHEDULED  FOR 1990.
 PACIFIC POWER t LIGHT
 JIM BRIDGER
 2
 RETROFIT  550 MW (GROSS)
           550 MW (ESC)
 COAL
   .56 XS  SUBBITUMINOUS
 SODIUM CARBONATE
 BABCOCK & WILCOX
 ENERGY CONSUMPTION:   ,2X
 STATUS 2     STARTUP  0/86
 PACIFIC  POWER  AND  LIGHT'S JIM BRIDGER  2  IS  A  DRY  BOTTOM PULVERIZED SUB-
 BITUMINOUS  COAL (0.56X  S, 9300  BTU/LB) FIRED  BOILER  SUPPLIED BY COMBUSTION
 ENGINEERING AND LOCATED IN  ROCK SPRINGS,  WYOMING.  BABCOCK & WILCOX IS
 CONSTRUCTING A RETROFIT WET SODIUM  CARBONATE  FGD  SYSTEM, WHICH WILL TREAT
 2,700,000 ACFM OF  FLUE  GAS.  A  COLD-SIDE  ESP  IS CURRENLY IN OPERATION FOR
 PRIMARY  PARTICULATE  CONTROL.  THE FGD  SYSTEM  WILL OPERATE IN A CLOSED
 WATER  LOOP  AND FLUE  GAS WILL EXIT A 500  FT  STACK.  INITIAL START-UP IS
 SCHEDULED FOR  1986.
 PACIFIC POWER & LIGHT
 JIM BRIDGER
 3
 RETROFIT  550 MW (GROSS)
           550 MW (ESC)
 COAL
   .56 XS  SUBBITUMINOUS
 SODIUM CARBONATE
 BABCOCK * WILCOX
 ENERGY CONSUMPTION:   .2X
 STATUS 3     STARTUP  0/88
 PACIFIC POWER AND  LIGHT'S JIM BRIDGER  3 IS A DRY BOTTOM PULVERIZED SUB-
 BITUMINOUS COAL (0.56XS,  9300 BTU/LB.) FIRED BOILER SUPPLIED BY COMBUSTION
 ENGINEERING AND LOCATED IN ROCK SPRINGS,  WYOMING.  THE UTILITY HAS Ats'AnnFP
 A CONTRACT TO BABCOCK 4 WILCOX FOR A RETROFIT WET SODIUM CARBONATE FGD
 SYSTEM, WHICH TREATS 2,700,000 ACFM OF FLUE GAS.  A COLD-SIDE ESP IS CUR-
 RENTLY IN OPERATION FOR PRIMARY PARTICULATE CONTROL.   THE FGD SYSTEM WILL
 OPERATE IN A CLOSED WATER LOOP MODE AND FLUE GAS WILL EXIT A 500 FT STACK.
 INITIAL START-UP IS SCHEDULED FOR 1988.
                                              2-22

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION Z
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
PACIFIC POWER & LIGHT
JIM BRIDGER
4
NEW       550 MW (GROSS)
          550 MM (ESC)
COAL
  .56 XS  SUBBITUMINOUS
SODIUM CARBONATE
AIR CORRECTION DIVISION, UOP
ENERGY CONSUMPTION;   .ax
STATUS 1     STARTUP  9/79
PACIFIC POWER AND LIGHT'S JIM BRIDGER 4 IS A DRY BOTTOM PULVERIZED
SUBBITUMINOUS COAL (0.56X Si 9300 BTU/LB) FIRED BOILER LOCATED IN
ROCK SPRINGS, WYOMING. A 91X EFFICIENT SODIUM CARBONATE FGD SYSTEM FOR
THIS UNIT WAS SUPPLIED BY THE AIR CORRECTION DIVISION OF UOP.  A COLD
SIDE ESP TREATS 2,720,000 ACFM OF FLUE GAS, FOLLOWED BY THREE  SIEVE
TRAY ABSORBERS. THE SYSTEM OPERATES IN A CLOSED WATER LOOP MODE AND FLUE
GAS EXITS A 500 FT STACK.  A SYSTEM CHECK OUT WAS CONDUCTED IN JULY 1979
AND OPERATIONS BEGAN IN SEPTEMBER 1979.
PACIFIC POWER « LIGHT
WYODAK
1
RETROFIT  330 MW (GROSS)
          330 MW (ESC)
COAL
***** XS  SUBBITUMINOUS
LIME/SPRAY DRYING
JOY/NIRO
ENERGY CONSUMPTION: ****X
STATUS 3     STARTUP  0/86
PACIFIC POWER AND LIGHT HAS AWARDED A CONTRACT TO JOY/NIRO TO RETROFIT A
LIME SPRAY DRYING FGD SYSTEM WITH RECYCLE ASH ON WYODAK 1, A 330 MW( GROSS)
SUBBITUMINOUS COAL FIRED UNIT.  THE UNIT IS LOCATED IN JOLIET, WYOMING AND
IS A MINE MOUTH PLANT.  THE UNIT STARTED IN 1978 AND THE FGD SYSTEM IS
SCHEDULED TO START-UP IN 1986.
PENNSYLVANIA POWER
BRUCE MANSFIELD
1
NEW       917 MW (GROSS)
          917 MW (ESC)
COAL
 3.50 XS  BITUMINOUS
LIME
GE ENVIRONMENTAL SERVICES
ENERGY CONSUMPTION:  4.IX
STATUS 1     STARTUP IE/75
BRUCE MANSFIELD 1 OF PENNSYLVANIA POWER IS A SUPERCRITICAL,  BALANCED DRAFT
BOILER FIRING PULVERIZED COAL (3.5X S, 12,000 BTU/LB) IN SHIPPINGPORT,
PENNSYLVANIA. A GEESI THIOSORBIC LIME FGD SYSTEM WAS DESIGNED TO REMOVE
FLYASH AND S02 (92.IX) FROM 3,350,000 ACFM OF FLUE GAS.  THE  FGD SYSTEM
CONSISTS OF SIX VARIABLE THROAT VENTURI SCRUBBERS FOLLOWED BY SIX FIXED
THROAT VENTURI ABSORBERS, HORIZONTAL MIST ELIMINATORS, TWO DIRECT COMBUS-
TION REHEATERS (INCLUDED IN ORIGINAL DESIGN BUT LATER REMOVED FROM
SERVICE) AND A 950 FOOT FLAKEGLASS STACK SHARED BY UNITS 1 AND Z.  THE   .
WATER LOOP IS OPEN, AND THE CALCILOX FIXED SLUDGE IS DISPOSED IN
AN OFF-SITE POND.  THIS SYSTEM HAS BEEN OPERATIONAL SINCE DECEMBER 1975.
PENNSYLVANIA POWER
BRUCE MANSFIELD
2
NEW       917 MW  (GROSS)
          917 MW  (ESC)
COAL
 3.50 XS  BITUMINOUS
LIME
GE ENVIRONMENTAL  SERVICES
ENERGY CONSUMPTION:  4. IX
STATUS 1     STARTUP  7/77
BRUCE MANSFIELD 2 OF PENNSYLVANIA POWER IS A SUPERCRITICAL, BALANCED DRAFT
BOILER FIRING PULVERIZED COAL (3.5X S, 12,000 BTU/LB) IN SHIPPINGPORT,
PENNSYLVANIA. A GEESI THIOSORBIC LIME FGD SYSTEM WAS DESIGNED TO REMOVE
FLYASH AND S02 (92.IX) FROM 3,350,000 ACFM OF FLUE GAS. THE FGD SYSTEM
CONSISTS OF SIX VARIABLE THROAT VENTURI SCRUBBERS FOLLOWED BY SIX FIXED
THROAT VENTURI ABSORBERS, HORIZONTAL MIST ELIMINATORS, TWO DIRECT COMBUS-
TION REHEATERS (INCLUDED IN ORIGINAL DESIGN BUT LATER REMOVED FROM
SERVICE) AND A 950 FOOT FLAKEGLASS STACK SHARED BY UNITS 1 AND 2. THE
WATER LOOP IS OPEN, AND THE CALCILOX FIXED SLUDGE IS DISPOSED IN
AN OFF-SITE POND. THIS SYSTEM HAS BEEN OPERATIONAL SINCE JULY 1977.
 PENNSYLVANIA POWER
 BRUCE MANSFIELD
 3
 NEW       917 MW  (GROSS)
          917 MW  (ESC)
 COAL
 4.30 XS  BITUMINOUS
 LIME
 M.W. KELLOGG
 ENERGY CONSUMPTION:  3.IX
 STATUS 1     STARTUP  6/80
BRUCE MANSFIELD 3 OF PENNSYLVANIA POWER IS A SUPERCRITICAL PULVERIZED
COAL (4.3X S, 12,000 BTU/LB) FIRED BOILER LOCATED IN SHIPPINSPORT,
PENNSYLVANIA. FOUR ESP'S TREAT 3,308,000 ACFM OF FLUE GAS, FOLLOWED
BY FIVE  (ONE SPARE) M. W. KELLOGG THIOSORBIC LIME ABSORBERS WHICH
REMOVE 92.2X OF THE S02. THE CLEANED GAS PASSES THROUGH
CHEVRON  MIST ELIMINATORS AND DIRECT COMBUSTION REHEATERS BEFORE
DISCHARGE THROUGH A 600 FOOT INCONEL 625 STACK FLUE. THE SYSTEM OPER-
ATES IN  AN OPEN WATER LOOP MODE AND FLYASH STABILIZED SLUDGE IS PIPED TO
AN OFF-SITE LANDFILL.  OPERATIONS COMMENCED IN JUNE 1980.
PHILADELPHIA ELECTRIC
CROMBY
1
RETROFIT  160 MW  (GROSS)
          150 MW  (ESC)
COAL
 2.00 XS
MAGNESIUM OXIDE
UNITED ENGINEERS
ENERGY CONSUMPTION: «**«X
STATUS 1     STARTUP 10/82
PHILADELPHIA ELECTRIC HAS RETROFITTED AN FGD SYSTEM ON ONE OF THE
TWO 2.OX SULFUR COAL FIRED BOILERS AT CROMBY STATION IN PHOENIXVILLE,
PENNSYLVANIA.  THE MAGNESIUM OXIDE SYSTEM WAS SUPPLIED BY UNITED
ENGINEERS.  FABRIC FILTERS AND PARTICLE SCRUBBERS ARE EMPLOYED FOR
PARTTICULATE CONTROL.  THE SYSTEM BECAME OPERATIONAL IN OCTOBER 1982.
                                              2-23

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
PHILADELPHIA ELECTRIC
EDDYSTONE
1
RETROFIT  240 MW (GROSS)
          240 MW (ESC)
COAL
 2.00 XS
MAGNESIUM OXIDE
UNITED  ENGINEERS
ENERGY  CONSUMPTION: ****X
STATUS  1     STARTUP  9/82
UNIT 1 OF PHILADELPHIA ELECTRIC'S EDDYSTONE, PENNSYLVANIA STATION IS A
BITUMINOUS COAL (2.OX S, 13,600 BTU/LB) FIRED UNIT WHICH USES ESP'S,
MECHANICAL COLLECTORS, AND THREE PARTICLE SCRUBBERS (TWO ROD DECK SPRAY
TOWERS AND ONE VENTURI) FOR PRIMARY PARTICLE CONTROL.  THE UNIT 1 FGD
SYSTEM FOLLOWS THE TWO ROD DECK SPRAY TOWERS.  UNITED ENGINEERS
SUPPLIED A MAGNESIUM OXIDE FGD SYSTEM FOR S02 EMISSION CONTROL SIMILAR
TO THE MAGNESIUM OXIDE PROTOTYPE SYSTEM THAT WAS PREVIOUSLY OPERATED
AT THIS UNIT.  THE SYSTEM OPERATES IN AN OPEN WATER LOOP MODE.
OPERATIN OF THE FGD SYSTEM COMMENCED IN SEPTEMBER 19S2.
 PHILADELPHIA  ELECTRIC
 EDDYSTONE
 2
 RETROFIT   334 MW  (GROSS)
           334 MW  (ESC)
 COAL
  2.00  XS
 MAGNESIUM  OXIDE
 UNITED ENGINEERS
 ENERGY CONSUMPTION:  «**«X
 STATUS 1      STARTUP 11/82
EDDYSTONE 2 OF PHILADELPHIA ELECTRIC IS A 2.OX SULFUR COAL FIRED BOILER
LOCATED IN EDDYSTONE, PENNSYLVANIA.  THE PLANT'S GENERATING
CAPACITY IS 334 MW.  UNITED ENGINEERS HAS SUPPLIED A MAGNESIUM OXIDE
FGD SYSTEM FOR EMISSION CONTROL AND PARTICLE SCRUBBERS ARE EMPLOYED FOR
PARTICULATE REMOVAL.  OPERATIONS COMMENCED IN NOVEMBER 1982.
 PLAINS ELECTRIC  G  4  T
 PLAINS ESCALANTE
 1
 NEW       233 MW (GROSS)
           233 MW (ESC)
 COAL
   .80 XS  SUBBITUMINOUS
 LIMESTONE
 COMBUSTION ENGINEERING
 ENERGY CONSUMPTION:  *«**X
 STATUS 2     STARTUP 10/84
PLAINS ESCALANTE 1 OF PLAINS ELECTRIC G t T IS A PULVERIZED SUBBITUMINOUS
COAL (.80X S) FIRED UNIT UNDER CONSTRUCTION IN PREWITT, NEW MEXICO.  THE
233 MW UNIT SUPPLIED BY COMBUSTION ENGINEERING WILL UTILIZE A WET LIME-
STONE SCRUBBING PROCESS WITH A S02 REMOVAL EFFICIENCY OF 75X.  A FABRIC
FILTER SUPPLIED BY GE ENVIRONMENTAL SERVICES WILL PROVIDE PRIMARY PARTICLE
CONTROL.  SLUDGE WILL BE MIXED WITH FLYASH AND DISPOSED AT AN ON-SITE
LANDFILL.  A CONTRACT WAS AWARDED TO COMBUSTION ENGINEERING FOR THE WET
LIMESTONE SYSTEM.  INITIAL START-UP IS SCHEDULED FOR OCTOBER 1984.
 PLATTE RIVER POWER AUTHORITY
 RAWHIDE
 1
 NEW       279 MW (GROSS)
           279 MW (ESC)
 COAL
   .34 XS  BITUMINOUS
 LIME/SPRAY DRYING
 JOY MFG/NIRO ATOMIZER
 ENERGY CONSUMPTION: **«*X
 STATUS 1     STARTUP 12/83
RAWHIDE 1, OF THE PLATTE RIVER POWER AUTHORITY, IS LOCATED IN
WELLINGTON, COLORADO.  THE 279 MW PULVERIZED COAL (0.34X S, 8500 BTU/LB)
FIRED BOILER WAS SUPPLIED BY COMBUSTION ENGINEERING.  JOY MANUFACT-
URING/NIRO ATOMIZER SUPPLYED A DRY LIME SCRUBBING SYSTEM FOR S02
CONTROL AND FABRIC FILTERS ARE EMPLOYED FOR PARTICULATE REMOVAL.  THE
SYSTEM OPERATES IN A CLOSED WATER LOOP MODE AND SLUDGE IS DIS-
POSED OF  IN A LANDFILL.  FLUE GAS EXITS A 505 FT STACK.  THE UNIT
COMMENCED INITIAL OPERATIONS IN DECEMBER 1983.
 PUBLIC SERVICE INDIANA
 GIBSON
 5
 NEW       670 MW (GROSS)
           670 MW (ESC)
 COAL
  3.30 XS
 LIMESTONE
 M.W. KELLOGG
 ENERGY CONSUMPTION: *»**X
 STATUS 1     STARTUP 10/62
 GIBSON  5  OF  PUBLIC SERVICE OF INDIANA IS A 3.3X SULFUR COAL  FIRED UNIT
 LOCATED IN PRINCETON, INDIANA.  THE SYSTEM SUPPLIER, M.W. KELLOG,
 HAS  INSTALLED  A  LIMESTONE FGD SYSTEM CONSISTING OF  FOUR KELLOGG-
 WEIR ABSORBER-REACTOR MODULES.  THE SYSTEM USES KELLOGG'S PROPRIETARY
 MAGNESIUM-PROMOTED LIMESTONE.  ESP'S ARE EMPLOYED FOR PARTICULATE CONTROL
 AND  FLUE  GAS EXITS A 500 FT STACK.  THE SYSTEM OPERATES IN A CLOSED  WATER
 LOOP MODE.   OPERATINS COMMENCED IN OCTOBER 1982.
 PUBLIC SERVICE OF NEW MEXICO
 NEW MEXICO
 1
 NEW       500 MW (GROSS)
           500 MW (ESC)
 COAL
 *»*** XS  SUBBITUMINOUS
 PROCESS NOT SELECTED
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION: »***x
 STATUS 6     STARTUP  0/95
 PUBLIC SERVICE  OF  NEW MEXICO HAS  PLANS  FOR A NEW UNIT,  NEW  MEXICO 1,  TO BE
 LOCATED IN  BISTI,  NEW MEXICO.  THE  PULVERIZED  SUBBITUMINOUS COAL (9000
 BTU/LB) FIRED UNIT WILL HAVE A GROSS MEGAWATT  RATING  OF 500.   THE UTILITY
 IS CONSIDERING  WET LIMESTONE OR LIME/SPRAY DRYING  FGD SYSTEMS FOR S02
 CONTROL AND FABRIC FILTER  FOR PARTICULATE CONTROL.  THE SYSTEM WILL OPER-
 ATE IN A CLOSED WATER LOOP MODE.  INITIAL START-UP IS SCHEDULED FOR 1995.
                                              2-24

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
PUBLIC SERVICE OF NEW MEXICO
SAN JUAN
1
RETROFIT  361 MW (GROSS)
          361 MW (ESC)
COAL
  .80 XS  SUBBITUMINOUS
WELLMAN LORD
DAVY MCKEE
ENERGY CONSUMPTION:  4.4X
STATUS 1     STARTUP  4/78
SAN JUAN 1 OF PUBLIC SERVICE OF NEW MEXICO IN WATERFLOW,  NEW MEXICO IS A
COAL (0.8X S, 9000 BTU/LB) FIRED BOILER WHICH SUPPLIES 1,319,000 ACFM OF
FLUE GAS TO A RETROFIT WELLMAN LORD FGD SYSTEM BY DAVY MCKEE. THE EMIS-
SION CONTROL SYSTEM, OPERATIONAL SINCE APRIL 1978, CONSISTS OF A HOT
SIDE ESP FOLLOWED BY FOUR (ONE SPARE) VENTURI SCRUBBER/SPRAY TOWER ABSOR-
BER TRAINS WHICH WERE DESIGNED TO REMOVE 85X OF THE FLUE  GAS S02. AN IN-
DIRECT HOT AIR REHEATER PRECEDES A 400 FT BRICK LINED STACK.  ACCORDING
TO THE ORIGINAL DESIGN, THE SYSTEM EMPLOYED THE ALLIED CHEMICAL PROCESS
FOR ELEMENTAL SULFUR RECOVERY.  THE SYSTEM HAS SINCE BEEN MODIFIED TO
PRODUCE SULFURIC ACID.  THE WATER LOOP IS CLOSED.
PUBLIC SERVICE OF NEW MEXICO
SAN JUAN
2
RETROFIT  350 MW (GROSS)
          350 MW (ESC)
COAL
   .80 XS  SUBBITUMINOUS
WELLMAN LORD
DAVY MCKEE
ENERGY CONSUMPTION:  4.6X
STATUS 1     STARTUP  8/78
SAN JUAN Z OF PUBLIC SERVICE OF NEW MEXICO IN WATERFLOW,  NEW MEXICO IS A
COAL (0.8X S, 9000 BTU/LB) FIRED BOILER WHICH SUPPLIES 1,319,000  ACFM OF
FLUE GAS TO A RETROFIT WELLMAN LORD FGD SYSTEM BY DAVY MCKEE.  THE EMIS-
SION CONTROL SYSTEM, OPERATIONAL SINCE AUGUST 1978,  CONSISTS OF A HOT
SIDE ESP FOLLOWED BY FOUR (ONE SPARE) VENTURI SCRUBBER/SPRAY TOWER ABSOR-
BER TRAINS WHICH MERE DESIGNED TO REMOVE 85X OF THE  FLUE  GAS S02. AN IN-
DIRECT HOT AIR REHEATER PRECEDES A 400 FT BRICK LINED STACK.  ACCORDING
TO THE ORIGINAL DESIGN, THE SYSTEM EMPLOYED THE ALLIED CHEMICAL PROCESS
FOR ELEMENTAL SULFUR RECOVERY.  THE SYSTEM HAS SINCE BEEN MODIFIED TO
PRODUCE SULFURIC ACID.  THE WATER LOOP IS CLOSED.
PUBLIC SERVICE OF NEW MEXICO
SAN JUAN
3
NEW       534 MW (GROSS)
          534 MW (ESC)
COAL
   .80 XS  SUBBITUMINOUS
WELLMAN LORD
DAVY MCKEE
ENERGY CONSUMPTION:  3.6X
STATUS 1     STARTUP 12/79
SAN JUAN 3 IS A COAL (0.8X S, 9000 BTU/LB) FIRED UNIT OF THE PUBLIC
SERVICE OF NEW MEXICO AND IS LOCATED IN WATERFLOW,  NEW MEXICO.  THE FGD
SYSTEM, SUPPLIED BY DAVY MCKEE UTILIZES THE WELLMAN LORD S02 RECOVERY
RECOVERY PROCESS AND SULFURIC ACID IS PRODUCED AS THE END PRODUCT.  FIVE
(ONE SPARE) VENTURI SCRUBBER/SPRAY TOWER ABSORBER (90X OESIGN S02 REMOVAL)
TRAINS FOLLOW A HOT SIDE ESP AND FLUE GAS EXITS A 400 FT STACK.  AN INDI-
RECT HOT AIR REHEATER BOOSTS THE GAS TEMPERATURE 50 DEG F. THE SYSTEM
OPERATES IN A CLOSED WATER LOOP MODE.  OPERATIONS COMMENCED IN DECEMBER
1979.
PUBLIC SERVICE OF NEW MEXICO
SAN JUAN
4
NEW       534 MW (GROSS)
          534 MW (ESC)
COAL
   .80 XS  SUBBITUMINOUS
WELLMAN LORD
DAVY MCKEE
ENERGY CONSUMPTION:  3.6X
STATUS 1     STARTUP  5/82
SAN JUAN 4 IS A COAL (0.8X S, 8100 BTU/LB) FIRED UNIT OF THE PUBLIC SER-
VICE OF NEW MEXICO LOCATED IN WATERFLOW, NEW MEXICO. THE FGD SYSTEM,
WHICH WAS SUPPLIED BY DAVY MCKEE, UTILIZES THE WELLMAN LORD S02 RECOVERY
PROCESS AND SULFURIC ACID IS PRODUCED AS THE END PRODUCT.  FIVE (ONE
SPARE) VENTURI SCRUBBER/SPRAY TOWER ABSORBER (90X DESIGN S02 REMOVAL)
TRAINS FOLLOW A HOT SIDE ESP AND FLUE GAS EXITS A 400 FT STACK.  AN INDI-
RECT HOT AIR REHEATER BOOSTS THE GAS TEMPERATURE 50 DEG F.  THE SYSTEM
OPERAES WATER LOOP MODE. THE SYSTEM COMMENCED OPERATIONS IN MAY
1982.
PUB. SER. CO. OF COLORADO
PAWNEE
2
NEW       500 MW (GROSS)
          500 MW (ESC)

   .35 XS
TRONA/DRY INJECTION
VENDOR NOT SELECTED
ENERGY CONSUMPTION: »***X
STATUS 6     STARTUP  0/90
PUBLIC SERVICE COMPANY OF COLORADO HAS PLANS FOR A NEW UNIT, PAWNEE 2, TO
BE LOCATED NEAR RUSH, COLORADO.  THE 500 MW (GROSS) BABCOCK & WILCOX
BOILER WILL FIRE SUBBITUMINOUS COAL (8290 BTU/LB, .35X S).  FABRIC FILTERS
WILL BE UTILIZED FOR PARTICULATE REMOVAL AND S02 EMISSIONS HILL BE CON-
TROLLED THROUGH INJECTION OF DRY TRONA.  THE TRONA WILL BE PULVERIZED AND
BLOWN INTO THE DUCTWORK UPSTREAM OF THE BAGHOUSE FOR CONTACT WITH FLUE GAS
ON THE DUCT AND BAGHOUSE SURFACES.  FLUE GAS WILL EXIT A 450 FOOT STACK.
INITIAL START UP IS SCHEDULED FOR 1990.
SALT RIVER PROJECT
CORONADO
1
NEW       400 MW (GROSS)
          320 MW (ESC)
COAL
  .55 XS  SUBBITUMINOUS
LIMESTONE
M.W. KELLOGG
ENERGY CONSUMPTION:  1.3X
STATUS 1     STARTUP 11/79
SALT RIVER PROJECT'S CORONADO 1 IS A DRY BOTTOM PULVERIZED SUBBITUMINOUS
COAL (0.55X S, 10,600 BTU/LB) FIRED BOILER LOCATED IN ST. JOHNS, ARIZONA.
M. W. KELLOGG SUPPLIED THE TWO LIMESTONE HORIZONTAL WEIR SPRAY TOWERS
WHICH REMOVE 82.5X OF THE S02 FROM THE FLUE GAS PASSED THROUGH THEM.
PARTICLE SCRUBBERS AND ESP'S ARE EMPLOYED FOR PARTICULATE REMOVAL AND VER-
TICAL HEIL MIST ELIMINATORS PRECEDE A 500 FT STACK.  A MINIMUM OF 20X BY-
PASS PROVIDES REHEAT.  THE WATER LOOP IS OPEN, AND THE UNSTABILIZED SLUDGE
IS DISPOSED OF IN AN UNLINED POND.  START-UP WAS IN NOVEMBER 1979.
                                             2-25

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
SALT RIVER PROJECT
CORONADO
Z
NEW       400 MW (GROSS)
          320 MW (ESC)
COAL
   .55 7.5  SUBBITUMINOUS
LIMESTONE
M.W. KELLOGG
ENERGY CONSUMPTION:   1.3X
STATUS 1     STARTUP  7/80
SALT RIVER PROJECT'S CORONADO 2 IS A DRY BOTTOM PULVERIZED SUBBITUMINOUS
COAL (0.55X S, 10,800 BTU/LB) FIRED BOILER LOCATED IN ST. JOHNS, ARIZONA.
M. W. KELLOGG SUPPLIED TWO LIMESTONE HORIZONTAL WEIR SPRAY TOWERS WHICH
REMOVE 82.5X OF THE S02 FROM THE FLUE GAS PASSED THROUGH THEM.  PARTICLE
SCRUBBERS AND ESP'S ARE EMPLOYED FOR PARTICULATE REMOVAL AND VERTICAL HEIL
MIST ELIMINATORS PRECEDE A 500 FT STACK.  A MINIMUM OF 20X BYPASS PROVIDES
REHEAT.  THE WATER LOOP IS OPEN, AND THE UNSTABILIZED SLUDGE IS DISPOSED
OF IN AN UNLINED POND.  START-UP WAS IN JULY 1980.
SALT RIVER  PROJECT
CORONADO
3
NEW       400 MW  (GROSS)
          280 MW  (ESC)
COAL
   .60  XS  SUBBITUMINOUS
LIMESTONE
VENDOR NOT  SELECTED
ENERGY CONSUMPTION:   3.ex
STATUS 6     STARTUP   0/92
CORONADO 3 IS A DRY BOTTOM PULVERIZED SUBBITUMINOUS COAL (.60X S, 8300 BTU
/LB) FIRED UNIT PLANNED BY SALT RIVER PROJECT TO BE LOCATED IN ST. JOHN'S,
ARIZONA. THE UTILITY IS PRESENTLY CONSIDERING THE INSTALLATION OF TWO HOR-
IZONTAL LIMESTONE SPRAY TOWERS FOR S02 CONTROL AND FABRIC FILTERS FOR PAR-
TICULATE REMOVAL.  THE SYSTEM WILL HAVE A 20X BYPASS REHEAT, AN OPEN WATER
LOOP, A 200 FT STACK AND THE SLUDGE WILL BE PONDED.  SCHEDULED OPERATIONS
ARE PLANNED TO BEGIN IN 1992.
 SAN ANTONIO PUBLIC  SERVICE
 N/D
 1
 NEW       500  MW (GROSS)
           500  MW (ESC)
 LIGNITE
  1.50 XS
 LIMESTONE
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION: ****•/
 STATUS 6     STARTUP  0/93
SAN ANTONIO PUBLIC SERVICE HAS PLANS FOR FOUR NEW UNITS (NAME AND LOCATION
UNDECIDED).  THE LIGNITE (5600 BTU/LB, 1-2X S) FIRED UNITS WILL HAVE A
GROSS MEGAWATT RATING OF 500 EACH AND WILL UTILIZE A LIMESTONE FGD SYSTEM.
THE FOUR UNITS ARE SCHEDULED TO COMMENCE OPERATIONS IN 1993, 1995, 1999,
AND 2001 RESPECTIVELY. ND 2001 RESPECTIVELY.
 SAN ANTONIO PUBLIC SERVICE
 N/D
 2
 NEW       500 MW (GROSS)
           500 MW (ESC)
 LIGNITE
  1.50 XS
 LIMESTONE
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION: «***X
 STATUS 6     STARTUP  0/95
SAN ANTONIO PUBLIC SERVICE HAS PLANS FOR FOUR NEW UNITS (NAME AND  LOCATION
UNDECIDED).  THE LIGNITE (5600 BTU/LB, 1-2X S) FIRED UNITS WILL HAVE A
GROSS MEGAWATT RATING OF 500 EACH AND WILL UTILIZE A LIMESTONE FGD SYSTEM.
THE FOUR UNITS ARE SCHEDULED TO COMMENCE OPERATION IN 1993, 1995,  1999,
AND 2001 RESPECTIVELY.
 SAN ANTONIO PUBLIC SERVICE
 N/D
 3
 NEW       500 MW (GROSS)
           500 MW (ESC)
 LIGNITE
  1.50 XS
 LIMESTONE
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION: ****X
 STATUS 6     STARTUP  0/99
 SAN  ANTONIO  PUBLIC SERVICE HAS PLANS FOR FOUR NEW UNITS  (NAME  AND  LOCATION
 UNDECIDED).  THE  LIGNITE  (5600 BTU/LB, 1-2X S) FIRED UNITS WILL  HAVE  A
 GROSS  MEGAWATT RATING OF  500 EACH AND WILL UTILIZE  A LIMESTONE FGD SYSTEM.
 THE  FOUR  UNITS ARE SCHEDULED TO COMMENCE OPERATIONS IN 1993,  1995, 1999,
 AND  2001  RESPECTIVELY.
 SAN ANTONIO PUBLIC SERVICE
 N/D
 4
 NEW       500 MW (GROSS)
           500 MW (ESC)
 LIGNITE
  1.50 XS
 LIMESTONE
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION: ****X
 STATUS 6     STARTUP 99/99
 SAN ANTONIO  PUBLIC  SERVICE  HAS  PLANS  FOR  FOUR  NEW  UNITS (NAME  AND LOCATION
 UNDECIDED).   THE  LIGNITE  (5600  BTU/LB,  1-2X  S) FIRED  UNITS WILL HAVE A
 GROSS MEGAWATT RATING  OF  500  EACH  AND WILL UTILIZE A  LIMESTONE FGD SYSTEM.
 THE FOUR  UNITS ARE  SCHEDULED  TO COMMENCE  OPERATIONS IN 1993,  1995, 1999,
 AND 2001  RESPECTIVELY.
                                              2-26

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
SAN MIGUEL ELECTRIC
SAN MIGUEL
1
NEW       400 MW (GROSS)
          400 MM (ESC)
COAL
 3.39 XS  LIGNITE
LIMESTONE
BABCOCK & WILCOX
ENERGY CONSUMPTION:  5.OX
STATUS 1     STARTUP  8/81
SAN MIGUEL 1 OF THE SAN MIGUEL ELECTRIC COOP IS A LIGNITE (2.39X S,  5000
BTU/LB) FIRED RADIANT BOILER LOCATED IN SAN MIGUEL, TEXAS.   THE
EMISSION CONTROL SYSTEM ON THIS UNIT CONSISTS OF A COLD SIDE ESP FOL-
LOWED BY FOUR BABCOCK AND WILCOX 86X EFFICIENT LIMESTONE TRAY TOWERS.
CHEVRON MIST ELIMINATORS PRECEDE AN IN-LINE REHEATER AND A  450 FT ACID
BRICK LINED STACK. THE SYSTEM OPERATES IN A CLOSED WATER LOOP MODE.
WASTE SLUURY IS DEWATERED, MIXED WITH FLYASH AND DISPOSED OF IN AN OFF-
SITE LANDFILL. OPERATIONS COMMENCED IN AUGUST 1981.
SEMINOLE ELECTRIC
SEMINOLE
1
NEW       620 MW (GROSS)
          620 MW (ESC)
COAL
 2.75 XS  BITUMINOUS
LIMESTONE
PEABODY PROCESS SYSTEMS
ENERGY CONSUMPTION: ****X
STATUS 1     STARTUP  5/83
SEMINOLE 1 OF SEMINOLE ELECTRIC IS A PULVERIZED COAL (2.75X S,  11,700
BTU/LB) UNIT LOCATED IN PALATKA, FLORIDA.  THE EMISSION CONTROL  SYSTEM
CONSISTS OF RESEARCH-COTTRELL ESP'S WITH 99.6X REMOVAL EFFICIENCY AND A
PEABODY PROCESS LIMESTONE FGD SYSTEM DESIGNED TO REMOVE 86X OF  THE S02.
AN ADDITIONAL 4X S02 REMOVAL IS ACHIEVED THROUGH COAL WASHING.   THE
CLEANED FLUE GAS EXITS THROUGH A 675 FOOT ACID BRICK LINED STACK AND
SLUDGE DISPOSAL IS HANDLED VIA THE POZ-0-TEC CONVERSION SYSTEM.  START-
UP COMMENCED IN MAY 1983.
SEMINOLE ELECTRIC
SEMINOLE
2
NEW       620 MM (GROSS)
          620 MW (ESC)
COAL
 2.75 XS  SUBBITUMINOUS
LIMESTONE
PEABODY PROCESS SYSTEMS
ENERGY CONSUMPTION: *****
STATUS 1     STARTUP  9/84
SEMINOLE 2 OF SEMINOLE ELECTRIC IS A PULVERIZED COAL (2.75X S,  11,700
BTU/LB) UNIT LOCATED IN PALATKA, FLORIDA. THE EMISSION CONTROL  SYSTEM
CONSISTS OF RESEARCH-COTTRELL ESP'S WITH 99.6X REMOVAL EFFICIENCY AND A
PEABODY PROCESS LIMESTONE FGD SYSTEM DESIGNED TO REMOVE 86X OF  THE S02.
AN ADDITIONAL 4X SOa REMOVAL IS ACHIEVED THROUGH COAL WASHING.   THE
CLEANED FLUE GAS EXITS THROUGH A 675 FOOT ACID BRICK LINED STACK AND
SLUDGE DISPOSAL IS HANDLED VIA THE POZ-0-TEC CONVERSION SYSTEM.  START-
UP COMMENCED IN SEPTEMBER 1984.
SEMINOLE ELECTRIC
TAYLOR
1
NEW       620 MW (GROSS)
          620 MM (ESC)
COAL
***** xs
PROCESS NOT SELECTED
VENDOR NOT SELECTED
ENERGY CONSUMPTION: ****X
STATUS 6     STARTUP 99/99
SEMINOLE ELECTRIC HAS PLANS TO CONSTRUCT A 620 MW (GROSS) UNIT, TAYLOR 1,
TO BE LOCATED IN PERRY, FLORIDA.  THE UTILITY IS PRESENTLY CONSID-
ERING ONLY FGD SYSTEMS AS THE CONTROL STRATEGY.  START-UP HAS BEEN
DEFERRED INDEFINITELY.
SEMINOLE ELECTRIC
TAYLOR
2
NEW       620 MW (GROSS)
          620 MW (ESC)
COAL
***** XS
PROCESS NOT SELECTED
VENDOR NOT SELECTED
ENERGY CONSUMPTION: ****X
STATUS 6     STARTUP 99/99
SEMINOLE ELECTRIC HAS PLANS TO CONSTRUCT A 620 MW (GROSS) UNIT, TAYLOR 2,
TO BE  LOCATED IN PERRY, FLORIDA.  THE UTILITY IS PRESENTLY CONSID-
ERING  ONLY FGD SYSTEMS AS THE CONTROL STRATEGY.  START-UP HAS BEEN
DEFERRED INDEFINITELY.
SIERRA PACIFIC POWER
THOUSAND SPRINGS
1
NEW       500 MW  (GROSS)
          500 MM  (ESC)
COAL
***** XS
PROCESS NOT SELECTED
VENDOR NOT SELECTED
ENERGY CONSUMPTION: ****X
STATUS 6     STARTUP  0/90
SIERRA PACIFIC POWER HAS PLANS FOR THREE NEW UNITS, THOUSAND SPRINGS 1,2
AND 3 TO BE  LOCATED IN WELLS, NEVADA. THE UNITS WILL HAVE A GROSS MEGAWATT
RATING OF 500 EACH AND WILL UTILIZE AN FGD SYSTEM FOR CONTROL OF S02
EMISSIONS.   UNITS 1,2 AND 3 ARE SCHEDULED TO START UP IN 1990, 1995 AND
1999 RESPECTIVELY.
                                              2-27

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
SIERRA PACIFIC POWER
THOUSAND SPRINGS
2
NEW       500 MW (GROSS)
          500 MW (ESC)
COAL
***** xs
PROCESS NOT SELECTED
VENDOR NOT SELECTED
ENERGY CONSUMPTION: ****X
STATUS 6     STARTUP  0/95
SIERRA PACIFIC POWER HAS PLANS FOR THREE NEW UNITS, THOUSAND SPRINGS 1,2
AND 3 TO BE LOCATED IN WELLS, NEVADA. THE UNITS MILL HAVE A GROSS MEGAWATT
RATING OF 500 EACH AND WILL UTILIZE AN FGD SYSTEM FOR CONTROL OF S02
EMISSIONS.  UNITS 1,2 AND 3 ARE SCHEDULED TO START UP IN 1990, 1995 AND
1999 RESPECTIVELY.
 SIERRA  PACIFIC  POWER
 THOUSAND  SPRINGS
 3
 NEW        500 MW  (GROSS)
           500 MW  (ESC)
 COAL
 ***** xs
 PROCESS NOT  SELECTED
 VENDOR  NOT SELECTED
 ENERGY  CONSUMPTION: *»**X
 STATUS  6     STARTUP   0/99
SIERRA PACIFIC POWER HAS PLANS FOR THREE NEW UNITS, THOUSAND SPRINGS 1,2
AND 3 TO BE LOCATED IN WELLS, NEVADA. THE UNITS WILL HAVE A GROSS MEGAWATT
RATING OF 500 EACH AND WILL UTILIZE AN FGO SYSTEM FOR CONTROL OF S02
EMISSIONS.  UNITS 1,2 AND 3 ARE SCHEDULED TO START UP IN 1990, 1995 AND
1999 RESPECTIVELY.
 SIERRA PACIFIC POWER
 VALMY
 2
 NEW       276 MW (GROSS)
           276 MW (ESC)
 COAL
   .50 XS
 LIME/SPRAY DRYING
 ROCKWELL INTERNATIONAL
 ENERGY CONSUMPTION:    .OX
 STATUS 2     STARTUP  6/85
SIERRA PACIFIC POWER IS CONSTRUCTING A 276 MW UNIT LOCATED IN VALMY,
NEVADA.  THE FOSTER WHEELER PULVERIZED COAL (.5X S) FIRED BOILER AT THE
VALMY 2 STATION WILL UTILIZE A LIME/SPRAY DRYING FGD SYSTEM SUPPLIED BY
ROCKWELL INTERNATIONAL.  A FABRIC FILTER WILL CONTROL PARTICLE EMISSIONS
AND FLUE GAS WILL EXIT A 500 FT STACK.  THE UNIT IS SCHEDULED TO COMMENCE
OPERATIONS IN JUNE 1985.
 SIKESTON BRD OF MUNICIPAL UTIL
 SIKESTON
 1
 NEW       235 MW (GROSS)
           235 MW (ESC)
 COAL
  2.80 XS  BITUMINOUS
 LIMESTONE
 BABCOCK 4 WILCOX
 ENERGY CONSUMPTION:   1.7X
 STATUS 1     STARTUP  6/81
THE SIKESTON BOARD OF MUNICIPAL UTILITIES' SIKESTON 1 IS A PULVERIZED COAL
(2.8X S, 11,340 BTU/LB) FIRED BOILER LOCATED IN SIKESTON, MISSOURI.
BABCOCK AND WILCOX SUPPLIED THE EMISSION CONTROL SYSTEM CONSIST-
ING OF TWO ESP'S AND THREE SOX CAPACITY LIMESTONE VENTURI FGD MODULES. THE
CLEANED GAS PASSES THROUGH CHEVRON MIST ELIMINATORS BEFORE EXITING A
450 FOOT FRP LINED FLUE (A SECOND CARBON STEEL LINED FLUE, USED FOR EMER-
GENCY BYPASS, IS ALSO IN THE STACK). THE WATER LOOP MODE IS OPEN, AND THE
SLUDGE IS PONDED.  THE SYSTEM STARTED OPERATIONS IN JUNE 1981.
 SOUTH CAROLINA PUBLIC SERVICE
 CROSS
 1
 NEW       450 MW (GROSS)
           450 MW (ESC)
 COAL
  1.60 XS  BITUMINOUS
 LIMESTONE
 PEABODY PROCESS SYSTEMS
 ENERGY CONSUMPTION: ****X
 STATUS 3     STARTUP  5/91
 SOUTH  CAROLINA  PUBLIC SERVICE HAS PLANS TO CONSTRUCT A NEW UNIT,
 CROSS  1  TO BE LOCATED IN CROSS, SOUTH CAROLINA.  THE 450 MW
 BOILER WILL  FIRE COAL (1.8X S, 11,200 BTU/LB).  THE UTILITY HAS SIGNED A
 CONTRACT WITH PEABODY PROCESS SYSTEMS FOR THE INSTALLATION OF A WET  LIME-
 STONE  SCRUBBING SYSTEM TO CONTROL S02 EMISSIONS.  A COLD SIDE ESP  WILL
 CONTROL  PARTICLE EMISSIONS AND THE CLEANED FLUE GAS WILL EXIT A 600  FOOT
 STACK.  THE  SYSTEM WILL OPERATE IN A CLOSED WATER LOOP MODE.  UNIT 1 IS
 SCHEDULED TO COMMENCE OPERATIONS IN MAY 1991.
 SOUTH CAROLINA PUBLIC SERVICE
 CROSS
 2
 NEW       450 MW (GROSS)
           450 MW (ESC)
 COAL
  1.80 XS  BITUMINOUS
 LIMESTONE
 PEABODY PROCESS SYSTEMS
 ENERGY CONSUMPTION: ****X
 STATUS 1     STARTUP 10/83
 SOUTH  CAROLINA  PUBLIC  SERVICE HAS ANNOUNCED THE  INITIAL  START-UP OF
 CROSS  2,  LOCATED  IN  CROSS,  SOUTH CAROLINA.  THE  450  MW BOILER  FIRES
 1.8X S,  11,200  BTU/LB  COAL.  A  WET  LIMESTONE  SCRUBBING SYSTEM  SUPPLIED
 BY PEABODY PROCESS SYSTEMS  CONTROLS S02  EMISSIONS  AND  PARTICULATE MATTER
 IS CONTROLLED VIA A  COLD  SIDE ESP.   THE  CLEANED  FLUE GAS EXITS A 600 FT
 STACK  AND THE SYSTEM OPERATES IN A  CLOSED WATER  LOOP MODE.   INITIAL
 START-UP COMMENCED IN  OCTOBER 1983.
                                              2-28

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
SOUTH CAROLINA PUBLIC SERVICE
WINYAH
Z
NEW       280 MM (GROSS)
          140 MM (ESC)
COAL
 1.00 XS  BITUMINOUS
LIMESTONE
BABCOCK & WILCOX
ENERGY CONSUMPTION:  1.1X
STATUS 1     STARTUP  7/77
WINYAH Z OF SOUTH CAROLINA PUBLIC SERVICE IS A PULVERIZED BITUMINOUS COAL
(l.OOX S, 11,500 BTU/LB) FIRED UNIT LOCATED IN GEORGETOWN, SOUTH CAROLINA.
A COLD SIDE ESP AND A BABCOCK AND WILCOX VENTURI SCRUBBER/LIMESTONE TRAY
TOWER ABSORBER TRAIN DESIGNED TO REMOVE 45X OF THE S02 FROM THE BOILER
FLUE GAS (BOX GAS BYPASSES SCRUBBER) MAKE UP THE EMISSION CONTROL SYSTEM
ON THIS UNIT.  THE SYSTEM OPERATES IN AN OPEN WATER LOOP, THE SLUDGE
IS DISPOSED IN AN UNLINED POND AND FLUE GAS EXITS A 400 FT STACK.  OPERA-
TIONS COMMENCED IN JULY 1977.
SOUTH CAROLINA PUBLIC SERVICE  WINYAH 3 OF SOUTH CAROLINA PUBLIC SERVICE IS A DRY BOTTOM BOILER  WHICH
WINYAH
3
NEW       280 MM (GROSS)
          280 MM (ESC)
COAL
 1.00 XS  BITUMINOUS
LIMESTONE
BABCOCK & WILCOX
ENERGY CONSUMPTION:  2.IX
STATUS 1     STARTUP  7/80
FIRES l.OX SULFUR COAL (11,500 BTU/LB) AND IS LOCATED IN GEORGETOWN,
SOUTH CAROLINA. AN ESP PRECEDES A BABCOCK AND WILCOX LIMESTONE  FGD
SYSTEM AND AN INDIRECT STEAM REHEATER. THE SYSTEM OPERATES IN A CLOSED
WATER LOOP MODE AND FLUE GAS EXITS A 400 FT STACK.  OPERATIONS  COMMENCED
IN MAY 1980.
SOUTH CAROLINA PUBLIC SERVICE
WINYAH
4
NEW       280 MM (GROSS)
          280 MW (ESC)
COAL
 1.70 XS  BITUMINOUS
LIMESTONE
AMERICAN AIR FILTER
ENERGY CONSUMPTION:  2.IX
STATUS 1     STARTUP  7/81
SOUTH CAROLINA PUBLIC SERVICE'S WINYAH 4 IS A BITUMINOUS COAL (1.70X S,
11,500 BTU/LB) FIRED UNIT LOCATED IN GEORGETOWN,  SOUTH CAROLINA.
TWO AMERICAN AIR FILTER LIMESTONE SLURRY SPRAY TOWERS FOLLOW AN ESP.
THE TEMPERATURE OF THE CLEANED GAS IS RAISED BY AN INDIRECT STEAM
REHEATER. THE SYSTEM OPERATES IN A CLOSED WATER LOOP MODE.   INITIAL
OPERATIONS COMMENCED IN JULY 1981.
SOUTH MISSISSIPPI ELEC PWR
R.D. MORROW, SR.
1
NEW       200 MW (GROSS)
          124 MW (ESC)
COAL
 1.64 XS  BITUMINOUS
LIMESTONE
ENVIRONEERIHG, RILEY STOKER
ENERGY CONSUMPTION:  2.5X
STATUS 1     STARTUP  8/78
R.D. MORROW 1 OF SOUTHERN MISSISSIPPI ELEC. IS A PULVERIZED COAL (1.64X
S, 12,250 BTU/LB) FIRED UNIT IN PURVIS, MISSISSIPPI. THE EMISSION CON-
TROL SYSTEM FOR THIS UNIT CONSISTS OF A HOT SIDE ESP FOLLOWED BY A LIME-
STONE VENTRI-ROD ABSORBER SUPPLIED BY RILEY STOKER/ENVIRONEERING. AFTER
THE CLEANED GAS PASSES THROUGH A VERTICAL CHEVRON MIST ELIMINATOR, IT IS
JOINED BY A 36X BYPASS REHEAT BEFORE IT IS DISCHARGED THROUGH A 400 FOOT
STACK SHARED BY UNITS 1 AND 2 (EACH UNIT HAS ITS OWN ACID BRICK LINED
FLUE). THE WATER LOOP IS CLOSED, AND THE FLYASH STABILIZED SLUDGE IS
HAULED BY TRUCK TO AN OFF-SITE LANDFILL. THE SYSTEM HAS BEEN OPERATIONAL
SINCE AUGUST 1978.
SOUTH MISSISSIPPI ELEC PWR
R.D. MORROW, SR.
2
NEW       200 MM (GROSS)
          124 MW (ESC)
COAL
 1.64 XS  BITUMINOUS
LIMESTONE
ENVIRONEERING, RILEY STOKER
ENERGY CONSUMPTION:  2.5X
STATUS 1     STARTUP  6/79
R.D. MORROW 2 OF SOUTHERN MISSISSIPPI ELEC. IS A PULVERIZED COAL (1.64X
S, 12,250 BTU/LB) FIRED UNIT IN PURVIS, MISSISSIPPI. THE EMISSION CON-
TROL SYSTEM FOR THIS UNIT CONSISTS OF A HOT SIDE ESP FOLLOWED BY A LIME-
STONE VENTRI-ROD ABSORBER SUPPLIED BY RILEY STOKER/ENVIRONEERING. AFTER
THE CLEANED GAS PASSES THROUGH A VERTICAL CHEVRON MIST ELIMINATOR, IT IS
JOINED BY A 38X BYPASS REHEAT BEFORE IT IS DISCHARGED THROUGH A 400 FOOT
STACK SHARED BY UNITS 1 AND 2 (EACH UNIT HAS ITS OWN ACID BRICK LINED
FLUE). THE WATER LOOP IS CLOSED, AND THE FLYASH STABILIZED SLUDGE IS
HAULED BY TRUCK TO AN OFF-SITE LANDFILL. THE SYSTEM HAS BEEN OPERATIONAL
SINCE JUNE 1979.
SOUTHERN ILLINOIS POWER
MARION
4
NEW       184 MW (GROSS)
          184 MW (ESC)
COAL/REFUS
 3.75 XS  BITUMINOUS
LIMESTONE
BABCOCK t WILCOX
ENERGY CONSUMPTION:  2.2X
STATUS 1     STARTUP  4/79
UNIT 4 AT SOUTHERN ILLINOIS POWER COOP'S MARION STATION IN MARION, ILLI-
NOIS IS A CYCLONE FIRED COAL (3.75X S, 11000 BTU/LB) UNIT WHICH IS SERVED
BY A 89.4X EFFICIENT (DESIGN) LIMESTONE FGD SYSTEM SUPPLIED BY BABCOCK AMD
WILCOX. TWO SPRAY TOWERS AND A 400 FT BRICK LINED STACK ARE DOWNSTREAM OF
AN ESP IN THIS SYSTEM. THE WATER LOOP IS CLOSED, AND THE FLYASH STABIL-
IZED SLUDGE IS DEWATERED AND LANDFILLED.  THE SYSTEM BECAME OPERATIONAL
DURING APRIL 1979.
                                              2-29

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
SOUTHERN INDIANA GAS & ELEC
A.B. BROWN
1
NEW       265 MW (GROSS)
          265 MW (ESC)
COAL
 3.35 XS  BITUMINOUS
DUAL ALKALI
FMC
ENERGY CONSUMPTION:    .ex
STATUS 1     STARTUP   3/79
SOUTHERN INDIANA GAS AND ELECTRIC'S A.B.BROWN 1 IS A DRY BOTTOM PULVERIZED
COAL (3.35X S, 11,100 BTU/LB) FIRED UNIT IN WEST FRANKLIN, INDIANA. FMC
SUPPLIED A DUAL ALKALI FGD SYSTEM DESIGNED TO REMOVE 85X OF THE FLUE GAS
S02. THE UNIT CONSISTS OF TWO THREE STAGE DISC CONTACTORS. A COLD SIDE ESP
PROVIDES PRIMARY PARTICULATE CONTROL, AND ONE CHEVRON MIST ELIMINATOR/MOD-
ULE PRECEDES A 498 FOOT ACID BRICK LINED STACK. THE SYSTEM PRODUCES A
FILTER CAKE WASTE PRODUCT WHICH IS DISPOSED IN AN ON-SITE LANDFILL. THE
WATER LOOP CAN BE EITHER OPEN OR CLOSED. THE SYSTEM HAS BEEN OPERATIONAL
SINCE MARCH 1979.
 SOUTHERN  INDIANA GAS  t  ELEC
 A.B.  BROWN
 2
 NEW       265  MW (GROSS)
          265  MW (ESC)
 COAL
  3.35 XS  BITUMINOUS
 DUAL  ALKALI
 FMC
 ENERGY CONSUMPTION:    .ex
 STATUS 2     STARTUP   1/85
SOUTHERN INDIANA GAS AND ELECTRIC HAS A NEW UNIT, A.B. BROWN 2, UNTDER CON-
STRUCTION IN WEST FRANKLIN, INDIANA.  THE 265-MW (GROSS) UNIT SUPPLIED BY
BABCOCK & WILCOX WILL FIRE BITUMINOUS COAL (3.35X S, 11,100 BTU/LB).  A
COLD SIDE ESP WILL PROVIDE PRIMARY PARTICULATE MATTER CONTROL AND A DUAL
ALKALI FGD SYSTEM WITH A S02 REMOVAL EFFICIENCY OF 90X WILL BE SUPPLIED BY
FMC TO CONTROL EMISSIONS.  THE FLUE GAS WILL EXIT THROUGH A 498-FOOT
STACK.  THE SYSTEM WILL OPERATE IN A CLOSED WATER LOOP MODE AND THE SLUDGE
WILL BE DISPOSED IN AN ON-SITE LANDFILL.  OPERATIONS ARE SCHEDULED TO COM-
MENCE IN JANUARY 1985.
 SOUTHWESTERN ELECTRIC  POWER
 DOLET HILLS
 1
 NEW       720 MW (GROSS)
           720 MW (ESC)
 COAL
   .70 XS  LIGNITE
 LIMESTONE
 AIR CORRECTION DIVISION,  UOP
 ENERGY CONSUMPTION:  *#**X
 STATUS 2     STARTUP 12/85
DOLET HILLS 1 OF SOUTHWESTERN ELECTRIC POWER IS A 720 MW LIGNITE (0.7X S,
7100 BTU/LB) FIRED BOILER UNDER CONSTRUCTION IN MANSFIELD, LOUISIANA.
THE EMISSION CONTROL SYSTEM WILL CONSIST OF AN ESP FOR PARTICULATE CONTROL
AND A WET LIMESTONE FGD SYSTEM FOR S02 CONTROL.  THE FLUE GAS WILL EXIT
THROUGH A 525 FOOT STACK AND THE SYSTEM WILL OPERRATE IN A CLOSED WATER
LOOP MODE.  INITIAL START-UP IS SCHEDULED FOR DECEMBER 1985 AND
COMMERCIAL OPERATIONS ARE SCHEDULED FOR MARCH 1986.
 SOUTHWESTERN ELECTRIC POWER
 HENRY W.  PIRKEY
 1
 NEW       720 MW (GROSS)
           720 MW (ESC)
 COAL
   .80 XS  LIGNITE
 LIMESTONE
 AIR CORRECTION DIVISION,  UOP
 ENERGY CONSUMPTION:  »***X
 STATUS 2     STARTUP 12/64
HENRY W. PIRKEY 1 OF SOUTHWESTERN ELECTRIC POWER IS A WET BOTTOM LIGNITE
(0.8X S, 6300 BTU/LB) FIRED UNIT UNDER CONSTRUCTION IN HALLSVILLE, TEXAS.
A CONTRACT WAS AWARDED TO THE AIR CORRECTION DIVISION OF UOP FOR FOUR
LIMESTONE SPRAY TOWERS (99+X EFFICIENCY) AND PARTICULATE WILL BE CON-
TROLLED WITH ESP'S.  MIST ELIMINATION WILL BE PROVIDED BY TWO STAGE CHEV-
RONS AND THE 525 FT STACK WILL BE ACID BRICK LINED.  NO REHEAT IS PLANNED.
THE WATER LOOP WILL BE CLOSED AND THE SLUDGE WILL BE POZ-0-TEC FIXATED.
START-UP IS EXPECTED BY DECEMBER 1984.
 SOUTHWESTERN ELECTRIC POWER
 WALKER CO.
 1
 NEW       720 MW (GROSS)
           720 MW (ESC)
 COAL
  1.49 XS  LIGNITE
 PROCESS NOT SELECTED
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION: ****X
 STATUS 6     STARTUP 12/93
WALKER COUNTY 1 OF SOUTHWESTERN ELECTRIC POWER IS A PLANNED 720 MW  (GROSS)
LIGNITE  (1.49X S) FIRED BOILER TO BE LOCATED IN HUNTSVILLE, TEXAS.  THE
UTILITY  IS PRESENTLY CONSIDERING BOTH WET LIMESTONE AND DRY SCRUBBING AS
THE  POSSIBLE EMISSION CONTROL STRATEGY WITH A DESIGN S02 REMOVAL EFFICIENC
OF 90X.  COMMERCIAL START-UP IS SCHEDULED FOR DECEMBER 1993.
 SOUTHWESTERN ELECTRIC POWER
 WALKER CO.
 2
 NEW       720 MW (GROSS)
           720 MW (ESC)
 COAL
  1.49 XS  LIGNITE
 PROCESS NOT SELECTED
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION-' *»*«X
 STATUS 6     STARTUP 12/93
 WALKER  COUNTY  2 OF SOUTHWESTERN ELECTRIC POWER  IS A  PLANNED  720  MW (GROSS)
 LIGNITE (1.49X S) FIRED BOILER TO BE  LOCATED  IN HUNTSVILLE,  TEXAS.  THE
 UTILITY IS  PRESENTLY CONSIDERING BOTH WET  LIMESTONE  AND DRY  SCRUBBING  AS
 THE  POSSIBLE EMISSION CONTROL STRATEGY WITH A DESIGN S02  REMOVAL EFFICIENC
 OF 90X.  COMMERCIAL START-UP IS SCHEDULED  FOR DECEMBER 1993.
                                              2-30

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                  ABSTRACT
SOUTHWESTERN PUBLIC SERVICE
SOUTH PLAINS
1
NEW       572 MM (GROSS)
          572 MW (ESC)
COAL
***»* XS
PROCESS NOT SELECTED
VENDOR NOT SELECTED
ENERGY CONSUMPTION: *««*X
STATUS 6     STARTUP  0/90
SOUTHWESTERN PUBLIC SERVICE HAS PLANS FOR A 572 MW (GROSS) UNIT,  SOUTH
PLAINS 1 TO BE LOCATED NEAR IDALOO TEXAS IN LUBOCK COUNTY.  THE UNIT WILL
BURN LOW SULFUR WESTERN COAL AND WILL UTILIZE AN FGD SYSTEM FOR CONTROL OF
S02 EMISSIONS.  INITIAL START-UP IS SCHEDULED FOR 1990.
SPRINGFIELD CITY UTILITIES
SOUTHWEST
1
NEW       194 MW (GROSS)
          194 MW (ESC)
COAL
 3.50 XS  BITUMINOUS
LIMESTONE
AIR CORRECTION DIVISION, UOP
ENERGY CONSUMPTION:  4.6X
STATUS 1     STARTUP  4/77
SPRINGFIELD CITY UTILITIES'  SOUTHWEST 1 IS A PULVERIZED BITUMINOUS COAL
(3.5X S, 11,000 BTU/LB) FIRED BOILER LOCATED IN SPRINGFIELD,  MISSOURI.  THE
EMISSION CONTROL SYSTEM FOR  THIS UNIT CONSISTS OF A COLD SIDE ESP FOLLOWED
BY TWO UOP LIMESTONE TCA MODULES WHICH WERE DESIGNED TO REMOVE BOX OF  THE
FLUE GAS S02. ONE CHEVRON/MODULE LEADS TO A 385 FOOT CEILCOTE LINED STACK.
THE DRY FLYASH STABILIZED SLUDGE IS DEWATERED BY A ROTARY DRUM VACUUM  FIL-
TER AND TRUCKED TO A LANDFILL.  THE SYSTEM OPERATES IN A CLOSED WATER  LOOP
MODE.  OPERATIONS COMMENCED  IN APRIL 1977.
SPRINGFIELD WATER, LIGHT t PUR
DALLMAN
3
NEW       205 MW (GROSS)
          205 MW (ESC)
COAL 1 ISO
 3.05 xs  BITUMINOUS; BITUMINO
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION:  4.9X
STATUS 1     STARTUP 10/80
DALLMAN 3 OF SPRINGFIELD WATER, LIGHT, AND POWER IS A PULVERIZED COAL
(3.05X S, 11,369 BTU/LB) FIRED BOILER LOCATED IN SPRINGFIELD,  ILLINOIS.
RESEARCH COTTRELL SUPPLIED A LIMESTONE FGD SYSTEM DESIGNED TO  REMOVE
95X OF THE S02 FROM 650,000 ACFM OF BOILER FLUE GAS.  A HOT SIDE ESP
PRECEDES TWO PACKED TOWER ABSORBERS, ONE HORIZONTAL CHEVRON PER MODULE,
AND A 500 FOOT ACID BRICK LINED STACK.  NO REHEAT IS PROVIDED.   THE SYS-
TEM OPERATES IN A CLOSED WATER LOOP MODE AND SLUDGE IS DISPOSED OF IN A
LANDFILL.  FGD OPERATIONS COMMENCED IN OCTOBER 1980.
SUNFLOWER ELECTRIC
HOLCOMB
1
NEW       347 MW  (GROSS)
          347 MU  (ESC)
COAL
   .34 XS  SUBBITUMINOUS
LIME/SPRAY DRYING
JOY MFG/NIRO ATOMIZER
ENERGY CONSUMPTION:    .OX
STATUS 1     STARTUP   7/83
SUNFLOWER ELECTRIC COOP'S HOLCOMB 1 STATION IS A 347 MW UNIT LOCATED IN
HOLCOMB, KANSAS.  THE PULVERIZED COAL (0.47X S, 8065 BTU/LB) FIRED BAB-
COCK AND WILCOX BOILER UTILIZES A JOY MANUFACTURING/NIRO ATOMIZER LIME/
SPRAY DRYING PROCESS FOR S02 CONTROL.  A FABRIC FILTER IS UTILIZED FOR
PRIMARY PARTICULATE CONTROL AND THE FLUE GAS EXITS A 475 FT STACK.
INITIAL START-UP OF THE FGD SYSTEM COMMENCED IN JULY 1983.
TAMPA ELECTRIC
BIG BEND
4
NEW       458 MW (GROSS)
          458 MW (ESC)
COAL
 3.50 XS
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION:  3.5X
STATUS 2     STARTUP  1/85
UNIT 4 AT TAMPA ELECTRIC'S BIG BEND STATION, LOCATED IN TAMPA, FLORIDA,
IS A DRY BOTTOM PULVERIZED COAL (3.50X S, 10,495 BTU/LB) FIRED UNIT.
RESEARCH-COTTRELL WILL SUPPLY A LIMESTONE SCRUBBING PROCESS.  A COLD SIDE
ESP AND MECHANICAL COLLECTORS MILL PROVIDE PARTICULATE CONTROL.  THE FGD
SYSTEM, PRESENTLY UNDER CONSTRUCTION, WILL REMOVE 90X OF THE FLUE GAS S02,
AND WILL INCLUDE AN INDIRECT HOT AIR REHEATER LEADING TO A 490 FOOT CON-
CRETE LINED STACK.  THE SYSTEM WILL OPERATE IN AN OPEN WATER LOOP MODE
AND WILL PRODUCE GYPSUM AS A SALEABLE PRODUCT.  INITIAL START-UP IS
SCHEDULED FOR JANUARY 1985.
TENNESSEE VALLEY AUTHORITY
PARADISE
1
RETROFIT  704 MW (GROSS)
          704 MW (ESC)
COAL
 3.20 XS  BITUMINOUS
LIMESTONE
GE ENVIRONMENTAL SERVICES
ENERGY CONSUMPTION:  2.6X
STATUS 1     STARTUP  5/83
PARADISE 1 OF TVA IS A 3.2X SULFUR COAL FIRED UNIT LOCATED IN PARADISE,
KENTUCKY. A CONTRACT WAS AWARDED TO GEESI FOR AN 84.2X EFFICIENT LIMESTONE
FGD SYSTEM TO BE RETROFITTED ON THIS BOILER. THE FGD SYSTEM CONSISTS OF
SIX VENTURI SCRUBBERS AND VENTURI ABSORBER TRAINS PRECEDED BY AN ESP.
INLET FLUE GAS IS USED TO HEAT GLYCOL, WHICH IN TURN IS USED TO REHEAT
THE OUTLET FLUE GAS.  UNTREATED SLUDGE IS PUMPED DIRECTLY TO A POND FOR
DISPOSAL.  THE SYSTEM OPERATES IN A CLOSED WATER LOOP MODE AND FLUE GAS
EXITS A 600 FT STACK.  OPERATIONS COMMENCED IN MAY 1983.
                                             2-31

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER
                                             SECTION Z
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
TENNESSEE VALLEY AUTHORITY
PARADISE
Z
RETROFIT  70* MW (GROSS)
          704 MW (ESC)
COAL
 3.20 XS  BITUMINOUS
LIMESTONE
GE ENVIRONMENTAL SERVICES
ENERGY CONSUMPTION:   2.6X
STATUS 1     STARTUP  7/83
PARADISE 2 OF TVA IS A 3.2X S COAL FIRED LOCATED UNIT IN PARADISE,
KENTUCKY. A CONTRACT WAS AWARDED TO GEESI FOR AN 8*.Z'/. EFFICIENT
LIMESTONE FGD SYSTEM RETROFITTED ON THIS BOILER. SIX VENTURI SCRUB-
BERS AND VENTURI ABSORBER TRAINS FOLLOW AN ESP. INLET FLUE GAS IS
USED TO HEAT GLYCOL, WHICH IN TURN IS USED TO REHEAT THE OUTLET
FLUE GAS.  UNTREATED SLUDGE IS PUMPED DIRECTLY TO A POND FOR DISPOSAL. THE
SYSTEM OPERATES IN A CLOSED WATER LOOP MODE AND FLUE GAS EXITS A 600 FOOT
STACK.  OPERATIONS COMMENCED IN JULY 1983.
 TENNESSEE  VALLEY AUTHORITY
 WIDOWS  CREEK
 7
 RETROFIT   575  MW (GROSS)
           575  MW (ESC)
 COAL
 3.70 XS   BITUMINOUS
 LIMESTONE
 COMBUSTION ENGINEERING
 ENERGY  CONSUMPTION: ****X
 STATUS  1     STARTUP  3/81
WIDOWS CREEK 7 IS A PULVERIZED BITUMINOUS COAL (3.7X S, 11,100 BTU/LB)
FIRED BOILER OF TVA LOCATED IN BRIDGEPORT, ALABAMA. COMBUSTION ENGINEERING
SUPPLIED A LIMESTONE VENTRI ROD SCRUBBER/SPRAY TOWER ABSORBER FGD SYSTEM
ON THIS UNIT.  AN ESP PRECEDES THE SCRUBBING TRAIN, AND A COMBINATION OF
A BULK ENTRAINMENT SEPERATOR, TWO CHEVRON MIST ELIMINATORS AND A FINNED
TUBE REHEATER FOLLOW THE SYSTEM.  A FORCED OXIDATION SYSTEM IS EMPLOYED
FOR SLUDGE TREATMENT.  OPERATIONS COMMENCED IN MARCH 1981.
 TENNESSEE  VALLEY  AUTHORITY
 WIDOWS CREEK
 8
 RETROFIT  550  MW  (GROSS)
           550  MW  (ESC)
 COAL
  3.30  XS  BITUMINOUS
 LIMESTONE
 TENNESSEE  VALLEY  AUTHORITY
 ENERGY CONSUMPTION:   4.7X
 STATUS 1    STARTUP 5/77
WIDOWS CREEK 8 OF TVA IS A BALANCED DRAFT, TANGENTIALLY FIRED COAL (3.30X
S, 11,810 BTU/LB) BOILER IN STEVENSON, ALABAMA. TVA RETROFITTED THIS UNIT
WITH A LIMESTONE FGD SYSTEM (SOX DESIGN S02 REMOVAL EFFICIENCY) WHICH BE-
GAN OPERATIONS IN MAY 1977. AN ESP PRECEDES FOUR VARIABLE THROAT VENTURI
SCRUBBER/MULTIGRID TOWER ABSORBER TRAINS (ONE OF THE TOWERS IS PACKED).
ONE VERTICAL CHEVRON/TRAIN AND AN INDIRECT HOT AIR REHEATER ARE INCLUDED
IN THE SYSTEM. THE SYSTEM OPERATES IN A CLOSED WATER LOOP AND FLUE GAS
EXITS A 500 FT STACK.  A FORCED OXIDATION SYSTEM IS EMPLOYED FOR SLUDGE
TREATMENT.
 TEXAS MUNICIPAL POWER AGENCY
 GIBBONS CREEK
 1
 NEW       443 MW (GROSS)
           400 MW (ESC)
 COAL
  1.06 XS  LIGNITE
 LIMESTONE
 COMBUSTION ENGINEERING
 ENERGY CONSUMPTION:   1.4X
 STATUS 1     STARTUP 11/82
GIBBONS CREEK 1 OF THE TEXAS MUNICIPAL POWER AGENCY IS A DRY BOTTOM PUL-
VERIZED LIGNITE (1.06X S, 4860 BTU/LB) FIRED UNIT LOCATED IN
CARLOS, TEXAS. THE EMISSION CONTROL SYSTEM CONSISTS OF A COLD SIDE ESP
FOLLOWED BY THREE SOX CAPACITY LIMESTONE SPRAY TOWERS. THE COMBUSTION EN-
GINEERING FGD SYSTEM INCLUDES A CHEVRON MIST ELIMINATOR AND A STEAM COIL
REHEATER.  CLEANED FLUE GAS IS DISCHARGED THROUGH A 465 FT ACID BRICK
LINED STACK. THE WATER LOOP IS OPEN AND THE POZ-0-TTEC STABILIZED SLUDGE
IS USED AS STRIP MINE LANDFILL.  OPERATIONS COMMENCED IN NOVEMBER
1982.
 TEXAS POWER & LIGHT
 SANDOW
 4
 NEW       545 MW (GROSS)
           382 MW (ESC)
 COAL
  1.60 XS  LIGNITE
 LIMESTONE
 COMBUSTION ENGINEERING
 ENERGY CONSUMPTION: ****X
 STATUS 1     STARTUP 12/80
SANDOW 4 IS A PULVERIZED 1.6X SULFUR LIGNITE FIRED BOIL'R OF TEXAS POWER
AND  LIGHT  LOCATED IN ROCKDALE, TEXAS.  COMBUSTION ENGINEERING SUPPLIED
THREE LIMESTONE SPRAY TOWERS FOR THIS UNIT.  A COLD SIDE ESP PROVIDES
PRIMARY PARTICULATE CONTROL.  A 30X BYPASS IS EMPLOYED TO PROVIDE REHEAT,
AND  THE OVERALL S02 REMOVAL EFFICIENCY IS 75X.  THE SYSTEM OPERATES  IN A
CLOSED WATER LOOP, AND THE SLUDGE IS PONDED.  OPERATIONS COMMENCED IN
DECEMBER 1980.
 TEXAS POWER & LIGHT
 TWIN OAKS
 1
 NEW       750 MW (GROSS)
           750 MW (ESC)
 COAL
   .70 XS  LIGNITE
 LIMESTONE
 GE ENVIRONMENTAL SERVICES
 ENERGY CONSUMPTION: **#*X
 STATUS 3     STARTUP  8/89
TWIN OAKS  1 IS A 750 MW  (GROSS) LIGNITE  (.7X S) FIRED BOILER  PLANNED  BY
TEXAS  POWER AND LIGHT AND ALCOA FOR LOCATION IN BREMOND,  TEXAS.   A CON-
TRACT  HAS  BEEN AWARDED TO GE ENVIRONMENTAL SERVICES  FOR A LIMESTONE FGD
SYSTEM WITH A DESIGN S02 REMOVAL  EFFICIENCY OF 70X.  ESP'S WILL  CONTROL
PARTICULATE MATTER AND THE SYSTEM WILL OPERATE IN A  CLOSED WATER LOOP
MODE.   START-UP IS SCHEDULED FOR  AUGUST  1989.
                                              2-32

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
TEXAS POWER & LIGHT
TWIN OAKS
Z
NEW       750 MM (GROSS)
          750 MW (ESC)
COAL
  .70 XS  LIGNITE
LIMESTONE
GE ENVIRONMENTAL SERVICES
ENERGY CONSUMPTION: «*««x
STATUS 3     STARTUP  8/91
                  TWIN OAKS 1 IS A 750 MW (GROSS)  LIGNITE  (.7X S)  FIRED  BOILER  PLANNED  BY
                  TEXAS POWER AND LIGHT AND ALCOA  FOR  LOCATION IN  BREMOND,  TEXAS.   A  CON-
                  TRACT HAS BEEN AWARDED TO GE ENVIRONMENTAL SERVICES FOR A LIMESTONE FGD
                  SYSTEM WITH A DESIGN S02 REMOVAL EFFICIENCY OF 70X.  ESP'S WILL  CONTROL
                  PARTICULATE MATTER AND THE SYSTEM WILL OPERATE IN A CLOSED WATER LOOP
                  MODE.  START-UP IS SCHEDULED FOR AUGUST  1991.
TEXAS UTILITIES
FOREST GROVE
1
NEW       750 MW (GROSS)
          750 MW (ESC)
COAL
   .80 XS  LIGNITE
LIMESTONE
WHEELABRATOR AIR POLTN. CNTRL.
ENERGY CONSUMPTION: «*««X
STATUS 3     STARTUP  0/88
                  TEXAS UTILITIES IS PLANNING A LIGNITE  (0.8X  S,  7000  BTU/LB)  FIRED BOILER,
                  FOREST GROVE 1, WHICH WILL BE LOCATED  IN ATHENS,  TEXAS.   A CONTRACT HAS
                  BEEN AWARDED TO WHEELABRATOR AIR POLLUTION CONTROL FOR A  WET LIMESTONE FGD
                  SYSTEM AT THIS UNIT.  TWO ESP'S WILL PROVIDE PRIMARY PARTICULATE CONTROL
                  AND NO STACK GAS REHEAT IS PLANNED.   START-UP IS  SCHEDULED FOR  1988.
TEXAS UTILITIES
MARTIN LAKE
1
NEW       793 MW (GROSS)
          595 MW (ESC)
COAL
   .90 XS  LIGNITE
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION:  1.3X
STATUS 1     STARTUP  4/77
                  TEXAS UTILITIES' MARTIN LAKE 1 IS A LIGNITE (0.9X S,  7380  BTU/LB)  FIRED
                  BOILER IN TATUM, TEXAS. THIS UNIT IS EQUIPPED WITH AN EMISSION CONTROL
                  SYSTEM WHICH INCLUDES A COLD SIDE ESP AND A LIMESTONE FGD  SYSTEM,  BOTH
                  SUPPLIED BY RESEARCH COTTRELL. THE FGD SYSTEM CONSISTS OF  SIX PACKED  SPRAY
                  TOWER ABSORBERS WHICH TREAT 75X OF THE TOTAL BOILER FLUE GAS.  THE  REMAIN-
                  ING FLUE GAS IS BYPASSED FOR REHEAT. THE TOTAL DESIGN S02  REMOVAL  EFFICI-
                  ENCY IS 70.5X. TWO CHEVRONS/MODULE PROVIDE MIST ELIMINATION.  THE FLUE GAS
                  CLEANING WASTES ARE FLYASH STABILIZED AND DISPOSED IN AN ON-SITE LANDFILL.
                  THE SYSTEM OPERATES IN A CLOSED WATER LOOP MODE AND FLUE GAS  EXITS A  450
                  FT STACK.  INITIAL OPERATIONS COMMENCED IN APRIL 1977.
TEXAS UTILITIES
MARTIN LAKE
Z
NEW       793 MW (GROSS)
          595 MW (ESC)
COAL
   .90 XS  LIGNITE
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION
STATUS 1
        1.3X
STARTUP  5/78
                  TEXAS UTILITIES' MARTIN LAKE 2 IS A LIGNITE (0.9X S,  7380  BTU/LB)  FIRED
                  BOILER IN TATUM, TEXAS. THIS UNIT IS EQUIPPED WITH AN EMISSION CONTROL
                  SYSTEM WHICH INCLUDES A COLD SIDE ESP AND A LIMESTONE FGD  SYSTEM,  BOTH
                  SUPPLIED BY RESEARCH COTTRELL. THE FGD SYSTEM CONSISTS OF  SIX PACKED  SPRAY
                  TOWER ABSORBERS WHICH TREAT 75X OF THE TOTAL BOILER FLUE GAS. THE  REMAIN-
                  ING FLUE GAS IS BYPASSED FOR REHEAT. THE TOTAL DESIGN S02  REMOVAL  EFFICI-
                  ENCY IS 70.5X. TWO CHEVRONS/MODULE PROVIDE MIST ELIMINATION.  THE FLUE GAS
                  CLEANING WASTES ARE FLYASH STABILIZED AND DISPOSED IN AN ON-SITE LANDFILL.
                  THE SYSTEM OPERATES IN A CLOSED WATER LOOP MODE AND FLUE GAS  EXITS A  450
                  FT STACK.  INITIAL OPERATIONS COMMENCED IN MAY 1978.
TEXAS UTILITIES
MARTIN LAKE
3
NEW       793 MW (GROSS)
          595 MW (ESC)
COAL
   .90 XS  LIGNITE
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION:
STATUS 1
        1.3X
STARTUP  2/79
TEXAS UTILITIES' MARTIN LAKE 3 IS A LIGNITE (0.9X S,  7380 BTU/LB) FIRED
BOILER IN TATUM, TEXAS. THIS UNIT IS EQUIPPED WITH AN EMISSION CONTROL
SYSTEM WHICH INCLUDES A COLD SIDE ESP AND A LIMESTONE FGD SYSTEM, BOTH
SUPPLIED BY RESEARCH COTTRELL. THE FGD SYSTEM CONSISTS OF SIX PACKED SPRAY
TOWER ABSORBERS WHICH TREAT 75X OF THE TOTAL BOILER FLUE GAS. THE REMAIN-
ING FLUE GAS IS BYPASSED FOR REHEAT. THE TOTAL DESIGN S02 REMOVAL EFFICI-
ENCY IS 70.5X. TWO CHEVRONS/MODULE PROVIDE MIST ELIMINATION. THE FLUE GAS
CLEANING WASTES ARE FLYASH STABILIZED AND DISPOSED IN AN ON-SITE LANDFILL.
THE SYSTEM OPERATES IN A CLOSED WATER LOOP MODE AND FLUE GAS EXITS A 450
FT STACK.  INITIAL OPERATIONS COMMENCED IN FEBRUARY 1979.
TEXAS UTILITIES
MARTIN LAKE
4
NEW       750 MW (GROSS)
          750 MW (ESC)
COAL
  .90 XS  LIGNITE
LIMESTONE
RESEARCH-COTTRELL
ENERGY CONSUMPTION: «***X
STATUS 3     STARTUP  0/89
                  MARTIN LAKE 4 OF TEXAS UTILITIES IS A LIGNITE (0.9X S, 7380 BTU/LB) FIRED
                  BOILER UNDER CONSTRUCTION IN TATUM, TEXAS. A CONTRACT FOR A LIMESTONE FGD
                  SYSTEM FOR THIS UNIT HAS BEEN AWARDED TO RESEARCH COTTRELL. ESP'S WILL BE
                  EMPLOYED FOR PARTICULATE CONTROL.  FGD START-UP IS EXPECTED IN
                  1989.
                                              2-33

-------
UTILITY FGO SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
TEXAS UTILITIES
MONTICELLO
3
NEW       800 MW (GROSS)
          800 MW (ESC)
COAL
   .50 XS  LIGNITE
LIMESTONE
GE ENVIRONMENTAL SERVICES
ENERGY  CONSUMPTION: ****X
STATUS  1     STARTUP  5/78
MONTICELLO 3 OF TEXAS UTILITIES IS A LIGNITE ( .5X S, 7000 BTU/LB) FIRED
UNIT IN MT. PLEASANT, TEXAS. THIS UNIT'S EMISSION CONTROL SYSTEM CONSISTS
OF TWO COLD SIDE ESP'S FOLLOWED BY THREE GEESI LIMESTONE SPRAY TOWERS
(74X DESIGN S02 REMOVAL EFFICIENCY), ONE HORIZONTAL CHEVRON MIST ELIMINA-
TOR/MODULE, AND AN INDIRECT HOT AIR REHEATER. THE WATER LOOP IS CLOSED,
AND THE FLYASH STABILIZED SLUDGE IS DISPOSED IN AN ON-SITE LANDFILL.  THE
CLEANED FLUE GAS FROM THIS UNIT EXITS A 600 FT STACK.  INITIAL START-UP
OCCURRED IN MAY 1978.
 TUCSON  ELECTRIC  POWER
 SPRINGERVILLE
 1
 NEW       370  MW (GROSS)
           370  MW (ESC)
 COAL
   .61 XS  SUEBITUMINOUS
 LIME/SPRAY DRYING
 JOY MFG/NIRO ATOMIZER
 ENERGY  CONSUMPTION:  ****•/.
 STATUS  2    STARTUP  2/85
TUCSON ELECTRIC POWER WILL BE BUILDING TWO NEW UNITS IN SPRINGERVILLE,
ARIZONA, SPRINGERVILLE 1 AND 2.  THE UNITS WILL FIRE PULVERIZED SUBBITU-
MINOUS COAL (0.53-0.69X S AND 8500-8900 BTU/LB).  A CONTRACT WAS
AWARDED TO JOY MANUFACTURING/NIRO ATOMIZER FOR A LIME/SPRAY DRYING FGD
SYSTEM TO CONTROL PARTICULATE MATTER AND S02 EMISSIONS.  THE SYSTEM WILL
BE DESIGNED TO ACCOMODATE A REHEATER (SHOULD ONE BE REQUIRED) AND WILL
OPERATE IN A CLOSED WATER LOOP.  CLEANED FLUE GAS WILL EXIT THE SYSTEM
VIA A 500 FOOT CONCRETE STACK.  START-UP IS SCHEDULED FOR FEBRUARY 1985.
 TUCSON ELECTRIC  POWER
 SPRINGERVILLE
 2
 NEW       370  MW (GROSS)
           370  MW (ESC)
 COAL
   .61 XS  SUBBITUMINOUS
 LIME/SPRAY DRYING
 JOY MFG/NIRO ATOMIZER
 ENERGY CONSUMPTION:  ****X
 STATUS 3    STARTUP  2/89
TUCSON GAS AND ELECTRIC WILL BE BUILDING TWO NEW UNITS IN SPRINGERVILLE,
ARIZONA, SPRINGERVILLE 1 AND 2.  THE UNITS WILL FIRE PULVERIZED SUBBITU-
MINOUS COAL (0.53-0.69X S AND 8500-8900 BTU/LB).  A CONTRACT HAS BEEN
AWARDED TO JOY MANUFACTURING/NIRO ATOMIZER FOR A LIME/SPRAY DRYING FGD
SYSTEM TO CONTROL PARTICULATE MATTER AND S02 EMISSIONS.  THE SYSTEM WILL
BE DESIGNED TO ACCOMODATE A REHEATER (SHOULD ONE BE REQUIRED) AST) WILL
OPERATE IN A CLOSED WATER LOOP.  CLEANED FLUE GAS WILL EXIT THE SYSTEM
VIA A 500 FOOT CONCRETE STACK.  START-UP IS SCHEDULED FOR FEBRUARY 1989.
 TUCSON ELECTRIC POWER
 SPRINGERVILLE
 3
 NEW       370 MW (GROSS)
           370 MW (ESC)
 COAL
   .61 XS  SUBBITUMINOUS
 PROCESS NOT SELECTED
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION: *#**X
 STATUS 6     STARTUP  0/91
TUCSON ELECTRIC POWER HAS PLANS FOR A NEW UNIT, SPRINGERVILLE 3, TO BE
LOCATED IN SPRINGERVILLE, ARIZONA.  THE PULVERIZED COAL (.53-.69X S, 8500-
8900 BTU/LB) FIRED UNIT WILL HAVE A GROSS MEGAWATT RATING OF 370 AND WILL
UTILIZE A FGD SYSTEM FOR CONTROL OF S02 EMISSIONS.  INITIAL START-UP IS
SCHEDULED FOR 1991.
 UNITED POWER ASSOCIATION
 STANTON
 1A
 NEW        60 MW (GROSS)
            50 MW (ESC)
 COAL
   .77 XS  LIGNITE
 LIME/SPRAY DRYING
 RESEARCH-COTTRELL
 ENERGY CONSUMPTION: ****X
STANTON 1A OF THE UNITED POWER ASSOCIATION IS A PULVERIZED COAL  (0.77X S,
7000 BTU/LB) FIRED UNIT LOCATED IN STANTON, NORTH DAKOTA.  THE LIME/SPRAY
DRYING SYSTEM, SUPPLIED BY RESEARCH-COTTRELL, CONSISTS OF A SPRAY DRYER
FOLLOWED BY A FABRIC FILTER FOR S02 I PARTICULATE REMOVAL.  KOMLINE AND
SANDERSON, THE SUBCONTRACTOR TO RESEARCH-COTTRELL, SUPPLIED THE  ROTARY
ATOMIZER AND ASSOCIATED EQUIPMENT FOR THE REACTOR VESSEL.  THE SYSTEM OP-
ERATES IN AN OPEN LOOP MODE WITH SLUDGE DISPOSED IN A CLAY LINED SETTLING
POND.  THE CLEANED FLUE GAS EXITS A 25* FT STACK.  OPERATIONS COMMENCED
IN  JULY 1982.
 STATUS 1
              STARTUP  7/82
 UTAH POWER & LIGHT
 HUNTER
 1
 NEW       420 MW (GROSS)
           360 MW (ESC)
 COAL
   .52 XS  BITUMINOUS
 LIME
 GE ENVIRONMENTAL SERVICES
 ENERGY CONSUMPTION:   1.7X
 STATUS 1     STARTUP  3/79
 HUNTER  1  OF UTAH  POWER AND  LIGHT IS A COAL  (0.52X S,  11,500  BTU/LB)  FIRED
 UNIT  IN CASTLEDALE, UTAH. GEESI SUPPLIED A  PEBBLE LIME WET SCRUBBING
 SYSTEM  WHICH  BECAME OPERATIONAL IN MARCH 1979.  THE SYSTEM IS DE-
 SIGNED  TO OPERATE IN AN OPEN WATER LOOP WITH AN S02 REMOVAL  EFFICIENCY OF
 SOX.  PRIMARY  PARTICULATE CONTROL IS PROVIDED BY AN UPSTREAM  ESP,  AND STACK
 GAS REHEAT IS PROVIDED BY BYPASS.  THE CLEANED  FLUE GAS  EXITS A 600  FT
 STACK.  THE SLUDGE IS FLYASH STABILIZED AND DISPOSED  ON-SITE.
                                              2-34

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 198*
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
UTAH POWER * LIGHT
HUNTER
2
NEW       420 MM (GROSS)
          360 MM (ESC)
COAL
  .52 XS  BITUMINOUS
LIME
GE ENVIRONMENTAL SERVICES
ENERGY CONSUMPTION:  1.7X
STATUS 1     STARTUP  6/80
                     UTAH POWER AND LIGHT'S HUNTER 2 IS A COAL (0.52X S,  11,500  BTU/LB)  FIRED
                     UNIT LOCATED IN CASTLEDALE,  UTAH.  FOR EMISSION CONTROL,  GEESI  SUPPLIED
                     A PEBBLE LIME MET SCRUBBING  SYSTEM DESIGNED  TO OPERATE  IN AN OPEN MATER
                     LOOP MITH AN S02 REMOVAL EFFICIENCY OF 80X.  AN UPSTREAM ESP PROVIDES
                     PRIMARY PARTICLE CONTROL, AND A BYPASS SYSTEM PROVIDES  STACK GAS REHEAT.
                     THE SLUDGE IS FLYASH STABILIZED AND DISPOSED OF ON-SITE. START-UP OF BOTH
                     THE BOILER AND FGD SYSTEM TOOK PLACE IN JUNE 1980.
UTAH POWER & LIGHT
HUNTER
3
NEM       400 MM (GROSS)
          400 MM (ESC)
COAL
   .55 XS  BITUMINOUS
LIMESTONE
GE ENVIRONMENTAL SERVICES
ENERGY CONSUMPTION: «***X
STATUS 1     STARTUP  4/83
                     HUNTER 3 OF UTAH POWER AND LIGHT IS A PULVERIZED COAL (0.55X S,  12500
                     BTU/LB) FIRED UNIT LOCATED IN CASTLE DALE,  UTAH.  A LIMESTONE NONREGENER-
                     ABLE FGD UNIT WAS SUPPLIED BY GEESI FOR 502 CONTROL AND  ESP'S ARE  EM-
                     PLOYED FOR PARTICULATE REMOVAL.   THE SYSTEM OPERATES IN  A  CLOSED HATER
                     LOOP MODE AND FLUE GAS EXITS A 600 FT STACK.  INITIAL OPERATIONS COM-
                     MENCED IN APRIL 1983.
UTAH POWER S LIGHT
HUNTINGTON
1
NEW       432 MM (GROSS)
          366 MM (ESC)
COAL
   .43 XS  BITUMINOUS
LIME
GE ENVIRONMENTAL SERVICES
ENERGY CONSUMPTION:  1.6X
STATUS 1     STARTUP  5/78
                     HUNTINGTON 1 OF UTAH POWER IS A TANGENTIALLY FIRED PULVERIZED  COAL (0.43X
                     S, 11,650 BTU/LB) BOILER IN HUNTINGTON,  UTAH.   A COLD  SIDE  ESP TREATS
                     1,742,000 ACFM OF FLUE GAS AND IS FOLLOMED BY A GEESI  LIME  FGD SYSTEM
                     CONSISTING OF FOUR SPRAY TOMERS (SOX DESIGN EFFICIENCY).  ONE  FOUR PASS
                     CHEVRON/MODULE PROVIDES MIST ELIMINATION,  AND A COMBINATION OF A STEAM
                     TUBE AND 10-20X BYPASS REHEATERS BOOST THE GAS TEMPERATURE  45-50 DEC F.
                     THE SYSTEM OPERATES IN A CLOSED MATER LOOP, AND THE FLYASH  STABILIZED
                     SLUDGE IS TRUCKED TO AN ON-SITE LANDFILL.  THE SYSTEM INCLUDES  A 600 FOOT
                     ACID BRICK LINED STACK, AND HAS BEEN OPERATIONAL SINCE MAY  1978.
UTAH POWER *  LIGHT
NAUGHTON
3
RETROFIT  330 MW  (GROSS)
          330 MW  (ESC)
COAL
   .55 XS  SUBBITUMINOUS
SODIUM CARBONATE
AIR CORRECTION DIVISION, UOP
ENERGY CONSUMPTION:  1.5X
STATUS 1     STARTUP  9/81
                     NAUGHTON 3 OF UTAH POWER AND LIGHT IS A PULVERIZED COAL (.55X S,  9500
                     BTU/LB) FIRED BOILER LOCATED IN KEMMERER, WYOMING.  THE BOILER SUPPLIES
                     1,500,000 ACFM OF FLUE GAS TO AN ESP FOR PARTICULATE MATTER CONTROL.   THE
                     UNIT WAS RETROFITTED WITH A UOP WET SODA ASH FGD SYSTEM FOR S02
                     CONTROL.  THE FGD SYSTEM IS DESIGNED TO REMOVE 70X OF THE  S02 BEFORE  THE
                     FLUE GAS EXITS OUT A 475 FOOT STACK.  INITIAL START-UP TOOK PLACE IN
                     SEPTEMBER 1981.
WASHINGTON WATER POWER
CRESTON COAL
1
NEW       570 MM (6ROSS)
     '     570 MW (ESC)
COAL
***** XS  UNKNOWN
LIMESTONE
VENDOR NOT SELECTED
ENERGY CONSUMPTION: **«*X
STATUS 6     STARTUP  0/95
                     MASHINGTON MATER POMER HAS PLANS FOR A NEM UNIT, CRESTON COAL 1, TO BE
                     LOCATED IN CRESTON, WASHINGTON.  THE COAL FIRED BOILER WILL HAVE A GROSS
                     GENERATING CAPACITY OF 570 MW AND MILL UTILIZE A MET LIMESTONE FGD SYSTEM
                     FOR CONTROL OF S02 EMISSIONS.  FGD OPERATIONS ARE SCHEDULED TO COMMENCE
                     IN 1995.
MASHINGTON HATER POMER
CRESTON COAL
2
570 MM (GROSS)
570 MM (ESC)
NEM

COAL
***** XS  UNKNOWN
LIMESTONE
VENDOR NOT SELECTED
ENERGY CONSUMPTION: ****X
STATUS 6     STARTUP  0/97
HASHINGTON WATER POWER HAS PLANS FOR A NEW UNIT, CRESTON 2, TO BE LOCATED
IN CRESTON, WASHINGTON.  THE COAL FIRED BOILER HILL HAVE A GROSS GENERAT-
ING CAPACITY OF 570 MM AND HILL USE A MET LIMESTONE FGD SYSTEM FOR CONTROL
OF S02 EMISSIONS.  FGD OPERATIONS ARE SCHEDULED TO COMMENCE IN 1997.
                                             2-35

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION 2
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                  ABSTRACT
WASHINGTON WATER POWER
CRESTON COAL
3
NEW       570 MW (GROSS)
          570 MW (ESC)
COAL
*»*** XS  UNKNOWN
LIMESTONE
VENDOR NOT SELECTED
ENERGY CONSUMPTION: 12.37.
STATUS 6     STARTUP  0/98
WASHINGTON WATER POWER HAS PLANS FOR A NEW UNIT, CRESTON 3, TO BE LOCATED
IN CRESTON, WASHINGTON.  THE COAL FIRED BOILER WILL HAVE A GROSS GENERAT-
ING CAPACITY OF 570 MW AND WILL USE A WET LIMESTONE FGD SYSTEM FOR CONTROL
OF S02 EMISSIONS.  FGD OPERATIONS ARE SCHEDULED TO COMMENCE IN 1998.
 WASHINGTON  WATER  POWER
 CRESTON  COAL
 4
 NEW       570 MW  (GROSS)
          570 MW  (ESC)
 COAL
 *****  XS UNKNOWN
 LIMESTONE
 VENDOR NOT  SELECTED
 ENERGY CONSUMPTION:  12.3X
 STATUS 6    STARTUP 0/99
WASHINGTON WATER POWER HAS PLANS FOR A NEW UNIT, CRESTON 4, TO BE LOCATED
IN CRESTON, WASHINGTON.  THE COAL FIRED BOILER WILL HAVE A GROSS GENERAT-
ING CAPACITY OF 570 MW AND WILL USE A WET LIMESTONE FGD SYSTEM FOR CONTROL
OF S02 EMISSIONS.  FGD OPERATIONS ARE SCHEDULED TO COMMENCE IN 1999.
 WEST PENN POWER
 MITCHELL
 33
 RETROFIT  300  MW (GROSS)
           300  MW (ESC)
 COAL
  2.80 XS  BITUMINOUS
 LIME
 GE ENVIRONMENTAL SERVICES
 ENERGY CONSUMPTION:   l.OX
 STATUS 1     STARTUP 8/82
UNIT 33 AT ALLEGHENY POWER SYSTEM'S MITCHELL POWER STATION IN COURTNEY,
PENNSYLVANIA IS A COAL (2.8X S, 12,520 BTU/LB) FIRED BOILER.  GEESI HAS
INSTALLED A LIME SCRUBBING PROCESS WITH AN S02 REMOVAL EFFICIENCY OF 95X.
PARTICULATE MATTER IS CONTROLLED WITH ESP'S.  OPERATIONS COMMENCED IN
AUGUST 1982.
 WEST TEXAS UTILITIES
 OKLAUNION
 1
 NEW       720 MW (GROSS)
           504 MW (ESC)
 COAL
   .34 XS  SUBBITUMINOUS
 LIMESTONE
 GE ENVIRONMENTAL SERVICES
 ENERGY CONSUMPTION:    .OX
 STATUS 2     STARTUP  9/86
WEST TEXAS UTILITIES HAS STARTED CONSTRUCTION ON A PULVERIZED SUBBITUMI-
NOUS COAL (.34X S, 8227 BTU/LB) FIRED BOILER LOCATED NEAR OKLAUNIOH,
TEXAS.  THE FOSTER WHEELER BOILER WILL SUPPLY 2,382,679 ACFM OF FLUE GAS
TO A WET LIMESTONE FGD SYSTEM SUPPLIED BY GE ENVIRONMENTAL SYSTEMS FOR
CONTROL OF S02 EMISSIONS (70X DESIGN REMOVAL EFFICIENCY).  LODGE-COTTRELL
WILL SUPPLY A RIGID FRAME COLD SIDE ESP FOR PARTICULATE CONTROL.  THE SYS-
TEM WILL OPERATE IN A CLOSED WATER LOOP MODE AND FLUE GAS WILL EXIT
THROUGH A 453 FT ACID BRICK LINED STACK.  INITIAL OPERATIONS ARE SCHEDULED
FOR SEPTEMBER 1986.
 WEST TEXAS UTILITIES
 OKLAUNION
 2
 NEW       720 MW (GROSS)
           504 MW (ESC)
 COAL
   .34 XS  SUEBITUMINOUS
 PROCESS NOT SELECTED
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION:   .OX
 STATUS 6     STARTUP  0/96
WEST TEXAS UTILITIES HAS PLANS TO BUILD A SECOND COAL (.34X S, 8227
BTU/LB)  FIRED BOILER TO BE LOCATED NEAR OKLAUNION, TEXAS.  THE UTILITY
WILL INCLUDE AN FGD SYSTEM FOR S02 CONTROL FROM THE 720 MW UNIT.   LODGE-
COTTRELL WILL SUPPLY A RIGID FRAME COLD SIDE ESP FOR CONTROL OF PARTICU-
LATE MATTER.  THE SYSTEM WILL OPERATE IN A CLOSED WATER LOOP MODE.  UNIT
2  IS SCHEDULED TO COMMENCE OPERATIONS IN 1996.
 WHITE PINE COUNTY
 WHITE PINE PWR PROJ.
 1
 NEW       820 MW (GROSS)
           820 MW (ESC)
 COAL
   .60 XS
 PROCESS NOT SELECTED
 VENDOR NOT SELECTED
 ENERGY CONSUMPTION: ****X
 STATUS 6     STARTUP  3/91
WHITE  PINE COUNTY HAS PLANS FOR TWO NEW UNITS, WHITE PINE  POWER  PROJECT
1  AND  2, TO BE  LOCATED NEAR ELY NEVADA.  THE PULVERIZED COAL  (10,530  BTU/
LB,  0.6X S) FIRED UNITS WILL HAVE A GROSS MEGAWATT RATING  OF  820 EACH AND
WILL UTILIZE A  SPRAY DRYING FGD SYSTEM FOR CONTROL OF S02  EMISSIONS.   FAB-
RIC  FILTERS WILL BE EMPLOYED FOR PARTICULATE CONTROL.  UNITS  1 ANT)  2  ARE
SCHEDULED TO COMMENCE OPERATIONS IN 1991 AND 1992 RESPECTIVELY.
                                              2-36

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                             SECTION Z
                                       STATUS OF FGD SYSTEMS
UNIT IDENTIFICATION
                                                                 ABSTRACT
WHITE PINE COUNTY
WHITE PINE PWR PROJ.
Z
NEW       820 MM (GROSS)
          820 MM (ESC)
COAL
  .60 XS
PROCESS NOT SELECTED
VENDOR NOT SELECTED
ENERGY CONSUMPTION: »»»*X
STATUS 6     STARTUP  3/92
WHITE PINE COUNTY HAS PLANS FOR TWO NEW UNITS, WHITE PINE POWER PROJECT
1 AND 2 TO BE LOCATED NEAR ELY NEVADA.  THE PULVERIZED COAL (10,530 BTU/
LB, 0.6X S) FIRED UNITS WILL HAVE A GROSS MEGAWATT RATING OF 820 EACH AND
WILL UTILIZE A SPRAY DRYING FGD SYSTEM FOR CONTROL OF S02 EMISSIONS.  FAB-
RIC FILTERS WILL BE EMPLOYED FOR PARTICULATE CONTROL.  UNITS 1 AND 2 ARE
SCHEDULED TO COMMENCE OPERATIONS IN 1991 AND 1992 RESPECTIVELY.
                                              2-37

-------
                                           UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER
                                      SECTION 3
                          SUMMARY OF FGD SYSTEMS BY COMPANY
                              TOTAL
	STATUS	
OPERATIONAL  CONSTRUCTION     CONTRACT
                              AWARDED
PLANNED
COMPANY NAME
ALABAMA ELECTRIC
ARIZONA ELECTRIC POWER
ARIZONA PUBLIC SERVICE
ASSOCIATED ELECTRIC
ATLANTIC CITY ELECTRIC
BASIN ELECTRIC POWER
BIG RIVERS ELECTRIC
BOSTON EDISON
CAJUN ELECTRIC POWER
CENTRAL ILLINOIS LIGHT
CENTRAL ILLINOIS PUBLIC SERV
CENTRAL MAINE POWER
CENTRAL POWER t LIGHT
CINCINNATI GAS & ELECTRIC
COLORADO UTE ELECTRIC
COLUMBUS * SOUTHERN OHIO ELEC
COOPERATIVE POWER
COOPERATIVE POWER ASSOCIATION
DELMARVA POWER t LIGHT
DESERET GEN & TRANS
DUQUESNE LIGHT
EAST KENTUCKY POWER
FLORIDA POWER i LIGHT
GENERAL PUBLIC UTILITIES
GRAND HAVEN BRD OF LIGHT & PWR
GRAND RIVER DAM AUTHORITY
HOOSIER ENERGY
HOUSTON LIGHTING £ POWER
INDIANAPOLIS POWER & LIGHT
IOWA ELECTRIC LIGHT t PHR
JACKSONVILLE ELEC AUTHORITY
KANSAS CITY POWER « LIGHT
KANSAS POWER i LIGHT
KENTUCKY UTILITIES
LAKELAND UTILITIES
LOS ANGELES DEPT OF WTR t PWR
LOUISVILLE GAS t ELECTRIC
LOWER COLORADO RIVER AUTH
MARG'JETTE BOARD OF LIGHT t PWR
MICHIGAN SO CENTRAL PWR AGENCY
MIDDLE SOUTH UTILITIES
MINNESOTA POWER t LIGHT
MINNKOTA POWER
MONONGAHELA POWER
MONTANA POWER
MONTANA-DAKOTA UTILITIES
MUSCATINE POWER t WATER
NEBRASKA PUBLIC POWER DISTRICT
NEVADA POWER
NEW YORK STATE ELEC t GAS
NIAGARA MOHAWK POWER
NORTHERN INDIANA PUB SERVICE
NORTHERN STATES POWER
ORLANDO UTILITIES COMMISSION
PACIFIC POWER & LIGHT
PENNSYLVANIA POWER
PHILADELPHIA ELECTRIC
PLAINS ELECTRIC G & T
PLATTE RIVER POWER AUTHORITY
PUBLIC SERVICE INDIANA
NO.
Z
2
9
1
1
6
3
2
1
1
1
1
1
3
3
2
1
2
4
2
2
2
2
2
1
1
2
5
5
1
2
1
5
3
1
2
10
2
1
1
2
1
1
2
4
1
1
1
8
1
1
2
4
1
S
3
3
1
1
1
MW
358.
196.
2761.
670.
330.
3150.
924.
776.
540.
416.
617.
600.
720.
2686.
1357.
700.
750.
654.
730.
820.
918.
1150.
1600.
1380.
65.
520.
882.
3372.
3012.
720.
1224.
874.
2165.
1365.
364.
1640.
3539.
902.
44.
55.
1780.
475.
374.
1252.
2276.
440.
166.
650.
2625.
625.
100.
782.
2420.
465.
2530.
2751.
724.
233.
279.
670.
NO.
2
2
6
1
0
4
3
0
0
1
1
0
0
1
3
2
0
2
3
1
2
1
0
0
1
0
2
1
1
0
0
1
5
1
1
0
6
0
1
1
0
1
1
2
3
1
1
0
4
1
1
1
3
0
1
3
3
0
1
1
MM
358.
196.
1145.
670.
0.
2150.
924.
0.
0.
416.
617.
0.
0.
650.
1357.
700.
0.
654.
180.
410.
918.
500.
0.
0.
65.
0.
882.
492.
532.
0.
0.
874.
2165.
65.
364.
0.
2389.
0.
44.
55.
0.
475.
374.
1252.
1498.
440.
166.
0.
625.
625.
100.
391.
1610.
0.
550.
2751.
724.
0.
279.
670.
NO.
0
0
2
0
0
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
0
2
1
0
2
0
0
0
0
2
0
1
0
0
0
0
0
0
1
0
0
0
0
0
0
1
1
1
1
0
0
1
0
0
MM
0.
0.
1490.
0.
0.
440.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
520.
0.
1500.
530.
0.
1224.
0.
0.
0.
0.
1640.
0.
451.
0.
0.
0.
0.
0.
0.
778.
0.
0.
0.
0.
0.
0.
391.
810.
465.
550.
0.
0.
233.
0.
0.
NO.
0
0
0
0
0
0
0
0
1
0
0
0
1
0
0
0
0
0
0
0
0
1
0
0
0
0
0
2
0
0
0
0
0
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
3
0
0
0
0
0
MM
0.
0.
0.
0.
0.
0.
0.
0.
540.
0.
0.
0.
720.
0.
0.
0.
0.
0.
0.
0.
0.
650.
0.
0.
0.
0.
0.
1380.
0.
0.
0.
0.
0.
650.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
1430.
0.
0.
0.
0.
0.
NO.
0
0
1
0
1
1
0
2
0
0
0
1
0
2
0
0
1
0
1
1
0
0
2
2
0
0
0
0
3
1
0
0
0
1
0
0
2
1
0
0
2
0
0
0
0
0
0
1
4
0
0
0
0
0
0
0
0
0
0
0
MW
0.
0.
126.
0.
330.
560.
0.
776.
0.
0.
0.
600.
0.
2036.
0.
0.
750.
0.
550.
410.
0.
0.
1600.
1380.
0.
0.
0.
0.
1950.
720.
0.
0.
0.
650.
0.
0.
1150.
451.
0.
0.
1760.
0.
0.
0.
0.
0.
0.
650.
2000.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
NOTE - PLANNED STATUS INCLUDES LETTER OF INTENT SIGNED,
       AND CONSIDERING ONLY FGD SYSTEMS
               REQUESTING/EVALUATING BIDS,
                                      3-1

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER
                                             SECTION 3
                                 SUMMARY OF FGD SYSTEMS BY COMPANY

TOTAL
COMPANY NAME
PUBLIC SERVICE OF NEW MEXICO
PUB. SER. CO. OF COLORADO
SALT RIVER PROJECT
SAN ANTONIO PUBLIC SERVICE
SAN MIGUEL ELECTRIC
SEMINOLE ELECTRIC
SIERRA PACIFIC POWER
SIKESTON BRD OF MUNICIPAL UTIL
SOUTH CAROLINA PUBLIC SERVICE
SOUTH MISSISSIPPI ELEC PWR
SOUTHERN ILLINOIS POWER
SOUTHERN INDIANA GAS & ELEC
SOUTHWESTERN ELECTRIC POWER
SOUTHWESTERN PUBLIC SERVICE
SPRINGFIELD CITY UTILITIES
SPRINGFIELD WATER, LIGHT & PWR
SUNFLOWER ELECTRIC
TAMPA ELECTRIC
TENNESSEE VALLEY AUTHORITY
TEXAS MUNICIPAL POWER AGENCY
TEXAS POWER & LIGHT
TEXAS UTILITIES
TUCSON ELECTRIC POWER
UNITED POWER ASSOCIATION
UTAH POWER t LIGHT
WASHINGTON WATER POWER
WEST PENH POWER
WEST TEXAS UTILITIES
WHITE PINE COUNTY
NO.
5
1
3
4
1
4
4
1
5
2
1
Z
4
1
1
1
1
1
4
1
3
6
3
1
5
(t
1
2
z
MW
2279.
500.
920.
2000.
400.
2480.
1776.
235.
1600.
248.
184.
530.
2880.
572.
194.
205.
347.
458.
2533.
400.
1882.
4085.
1110.
50.
1816.
2280.
300.
1008.
1640.
OPERATIONAL
NO.
4
0
2
0
1
2
0
1
4
2
1
1
0
0
1
1
1
0
4
1
1
4
0
1
5
0
1
0
0
MM
1779.
0.
640.
0.
400.
1240.
0.
235.
1150.
248.
184.
265.
0.
0.
194.
205.
347.
0.
2533.
400.
382.
2585.
0.
50.
1816.
0.
300.
0.
0.
CONSTRUCTION CONTRACT
AWARDED
NO.
0
0
0
0
0
0
1
0
0
0
0
1
2
0
0
0
0
1
0
0
0
0
1
0
0
0
0
1
0
MW
0.
0.
0.
0.
0.
0.
276.
0.
0.
0.
0.
265.
1440.
0.
0.
0.
0.
458.
0.
0.
0.
0.
370.
0.
0.
0.
0.
504.
0.
NO.
0
0
0
0
0
0
0
0
1
0
0
0
0
0
0
0
0
0
0
0
2
2
1
0
0
0
0
0
0
MW
0.
0.
0.
0.
0.
0.
0.
0.
450.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
1500.
1500.
370.
0.
0.
0.
0.
0.
0.
PLANNED
NO.
1
1
1
4
0
2
3
0
0
0
0
0
2
1
0
0
0
0
0
0
0
0
1
0
0
4
0
1
2
MW
500.
500.
280.
2000.
0.
1240.
1500.
0.
0.
0.
0.
0.
1440.
572.
0.
0.
0.
0.
0.
0.
0.
0.
370.
0.
0.
2280 .
0.
504.
1640.
    TOTALS
                                   217 102075.
                                                 124   47255.
                                                                25   14335.
                                                                              15    9190.
                                                                                            53   31295.
        NOTE - PLANNED STATUS INCLUDES LETTER OF INTENT SIGNED,  REQUESTING/EVALUATING BIDS,
               AND CONSIDERING ONLY FGD SYSTEMS
                                              3-2

-------
                     UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
               SECTION 4
SUMMARY OF FGD SYSTEMS BY SYSTEM SUPPLIER
                        	STATUS	
               TOTAL    OPERATIONAL  CONSTRUCTION   CONTRACT
                                                    AWARDED
SYSTEM SUPPLIER/PROCESS
AIR CORRECTION DIVISION, UOP
LIME
LIMESTONE
SODIUM CARBONATE
TOTAL -
AMERICAN AIR FILTER
LIME
LIMESTONE
TOTAL -
BABCOCK * WILCOX
LIME
LIMESTONE
LIME/SPRAY DRYING
SODIUM CARBONATE
TOTAL -
BECHTEL/MONTANA POWER
LIME/ALKALINE FLY ASH
TOTAL -
COMBUSTION ENGINEERING
LIME
LIMESTONE
LIMESTONE/ALKALINE FLY ASH
LIME/ALKALINE FLY ASH
TOTAL -
DAVY MCKEE
WELLMAN LORD
TOTAL -
ENVIRONEERING, RILEY STOKER
LIMESTONE
TOTAL -
FLAKT
LIME/SPRAY DRYING
TOTAL -
FMC
DUAL ALKALI
TOTAL -
GE ENVIRONMENTAL SERVICES
DUAL ALKALI
LIME
LIMESTONE
LIME/ALKALINE FLYASH
LIME/SPRAY DRYING
TOTAL -
JOY MFG/NIRO ATOMIZER
LIME/SPRAY DRYING
TOTAL -
NO.

2
4
2
8

6
1
7

7
9
2
3
21

2
2

4
14
2
2
22

7
7

3
3

1
1

4
4

1
8
12
3
1
25

10
10
MM

700.
2166.
880.
3746.

1659.
280.
1939.

4107.
3182.
1017.
1650.
9956.

1556.
1556.

980.
6581.
1500.
654.
9715.

1959.
1959.

664.
664.

520.
520.

1312.
1312.

617.
4138.
8124.
615.
44.
13538.

4426.
4426.
NO.

2
2
2
6

6
1
7-

4
8
2
0
14

1
1

4
9
2
2
17

7
7

3
3

0
0

2
2

1
8
5
3
1
18

4
4
MM

700.
726.
680.
2306.

1659.
280.
1939.

1967.
2532.
1017.
0.
5516.

778.
778.

980.
3932.
1500.
654.
7066.

1959.
1959.

664.
664.

0.
0.

656.
656.

617.
4138.
3100.
615.
44.
8514.

1176.
1176.
NO.

0
2
0
2

0
0
0

2
0
0
1
3

1
1

0
5
0
0
5

0
0

0
0

1
1

2
2

0
0
3
0
0
3

3
3
MM

0.
1440.
0.
1440.

0.
0.
0.

1490.
0.
0.
550.
2040.

778.
778.

0.
2649.
0.
0.
2649.

0.
0.

0.
0.

520.
520.

656.
656.

0.
0.
2144.
0.
0.
2144.

1620.
1620.
NO.

0
0
0
0

0
0
0

1
1
0
2
4

0
0

0
0
0
0
0

0
0

0
0

0
0

0
0

0
0
4
0
0
4

3
3
MM

0.
0.
0.
0.

0.
0.
0.

650.
650.
0.
1100.
2400.

0.
0.

0.
0.
0.
0.
0.

0.
0.

0.
0.

0.
0.

0.
0.

0.
0.
2-veo.
0.
0.
2880.

1630.
1630.
                 4-1

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                            SECTION ^
                             SUMMARY OF FGD SYSTEMS BY SYSTEM SUPPLIER

TOTAL
SYSTEM SUPPLIER/PROCESS
JOY/NIRO
LIME/SPRAY DRYING
TOTAL -
MITSUBISHI HEAVY INDUSTRIES
LIMESTONE
TOTAL -
M.W. KELLOGG
LIME
LIMESTONE
TOTAL -
PEABODY PROCESS SYSTEMS
LIMESTONE
LIME/ALKALINE FLYASH
TOTAL -
RESEARCH-COTTRELL
LIMESTONE
LIME/SPRAY DRYING
TOTAL -
ROCKWELL INTERNATIONAL
AQUEOUS CARBONATE/SPRAY DRYING
LIME/SPRAY DRYING
TOTAL -
TENNESSEE VALLEY AUTHORITY
LIMESTONE
TOTAL -
THYSSEN/CEA
DUAL ALKALI
LIME
LIME/ALKALINE FLYASH
SODIUM CARBONATE
TOTAL -
UNITED ENGINEERS
MAGNESIUM OXIDE
TOTAL -
KHEELABRATOR AIR POLTN. CNTRL.
LIMESTONE
TOTAL -
WHEELABRATOR-FRYE/R.I.
SODIUM CARBONATE/SPRAY DRYING
TOTAL -
NO.

1
1

2
Z

2
4
6

9
1
10

17
1
18

1
1
2

1
1

1
1
3
4
9

3
3

1
1

1
1
MM

330.
330.

882.
882.

1357.
1980.
3337.

4033.
475.
4508.

6984.
50.
7034.

100.
276.
376.

550.
550.

299.
500.
1094.
625.
2518.

724.
724.

750.
750.

440.
440.
OPERATIONAL
NO.

0
0

2
2

2
4
6

8
1
9

12
1
13

1
0
1

1
1

1
1
3
4
9

3
3

0
0

1
1
MW

0.
0.

882.
882.

1357.
1980.
3337.

3583.
475.
4058.

4022.
50.
4072.

100.
0.
100.

550.
550.

299.
500.
1094.
625.
2518.

724.
724.

0.
0.

440.
440.
CONSTRUCTION
NO.

0
0

0
0

0
0
0

0
0
0

4
0
4

0
1
1

0
0

0
0
0
0
0

0
0

0
0

0
0
MM

0.
0.

0.
0.

0.
0.
0.

0.
0.
0.

2212.
0.
2212.

0.
276.
276.

0.
0.

0.
0.
0.
0.
0.

0.
0.

0.
0.

0.
0.
CONTRACT
AWARDED
NO.

1
1

0
0

0
0
0

1
0
1

1
0
1

0
0
0

0
0

0
0
0
0
0

0
0

1
1

0
0
MM

330.
330.

0.
0.

0.
0.
0.

450.
0.
450.

750.
0.
750.

0.
0.
0.

0.
0.

0.
0.
0.
0.
0.

0.
0.

750.
750.

0.
0.
         TOTAL -
                                          164 70780.
                                                       124 47255.
                                                                     25 14335.
                                                                                  15  9190.
                                              4-2

-------
                                               UTILITY F6D SURVEY:  OCTOBER 1983 - SEPTEMBER 1984
                                         SECTION 5
                              SUMMARY OF FGD SYSTEMS BY PROCESS
                                 TOTAL
	STATUS	
OPERATIONAL  CONSTRUCTION   CONTRACT
                            AWARDED
PROCESS
                               NO.   MM
                                            NO.
                                                         NO.
                                                                      NO.
                                                                            MW
  SUBTOTAL - SALEABLE  PRODUCT  15  4183.    12  2949.
DUAL ALKALI
LIME
LIMESTONE
LIMESTONE/ALKALINE FLYASH
LIME/ALKALINE FLYASH
LIME/SPRAY DRYING
PROCESS NOT SELECTED
SODIUM CARBONATE
SODIUM CARBONATE/SPRAY DRYING
TRONA/DRY INJECTION
  SUBTOTAL - THROWAWAY PRODUCT 172 80089.   112 44306.
                    458.
               23 13412.
14  8860.
                                                                                    PLANNED
                                                                                   NO.
                                                                                         MW
AQUEOUS CARBONATE/SPRAY DRYING
LIMESTONE
MAGNESIUM OXIDE
WELLMAN LORD
1
4
3
7
100.
1400.
724.
1959.
1
1
3
7
100.
166.
724.
1959.
0
1
0
0
0.
458.
0.
0.
0
0
0
0
0.
0.
0.
0.
0
2
0
0
0.
776.
0.
0.
                                              776.
6
30
90
2
11
16
6
9
1
1
2228.
13441.
44008.
1500.
4394.
6333.
4090.
3155.
440.
500.
4
27
54
2
10
8
0
6
1
0
1572.
11301.
22085.
1500.
3616.
2287.
0.
1505.
440.
0.
2
2
12
0
1
5
0
1
0
0
656.
1490.
7522.
0.
778.
2416.
0.
550.
0.
0.
0
1
8
0
0
3
0
2
0
0
0.
650.
5480.
0.
0.
1630.
0.
1100.
0.
0.
0
0
16
0
0
0
6
0
0
1
0.
0.
8921.
0.
0.
0.
4090.
0.
0.
500.
                                         23 13511.
TOTALS                         187 84272.   124 47255.    24 13870.    14  8860.    25 14287.

  SALEABLE PRODUCT PROCESS
  Y. OF TOTAL MW                        56305

NOTE:  30 UNITS ARE UNDECIDED (WITH RESPECT TO SALEABLE/THROWAWAY PRODUCT) AND ARE NOT INCLUDED
       IN THIS TABLE.  THE   6 UNITS LISTED AS PROCESS NOT SELECTED ABOVE ARE PLANNED THROWAWAY
       PRODUCT FGD SYSTEMS;  HOWEVER A SPECIFIC PROCESS HAS NOT YET BEEN CHOSEN.
                                             5-1

-------
                                    UTILITY F6D  SURVEY:  OCTOBER  1983 - SEPTEMBER
                              SECTION 6
        SUMMARY OF OPERATIONAL F6D SYSTEMS BY PROCESS AND  UNIT
PROCESS/
  UNIT NAME
                          UNIT NO.
            CAPACITY
               MM
        INITIAL
        STARTUP
        COMMERCIAL
         STARTUP
AQUEOUS CARBONATE/SPRAY DRYING
  CHARLES R. HUNTLEY      66
DUAL ALKALI
  A.B. BROWN
  CANE RUN
  NEWTON
  SCHAHFER
LIME
  BRUCE MANSFIELD
  BRUCE MANSFIELD
  BRUCE MANSFIELD
  CANE RUN
  CANE RUN
  CONESVILLE-
  CONESVILLE
  D.B. WILSON
  EAST BEND
  ELRAMA
  GREEN
  GREEN
  GREEN RIVER
  HUNTER
  HUNTER
  HUNTINGTON
  J.B. SIMS
  MILL CREEK
  MILL CREEK
  MILL CREEK
  MILL CREEK
  MITCHELL
  PADDY'S RUN
  PHILLIPS
  PLEASANTS
  PLEASANTS
  SPURLOCK
 LIMESTONE
  APACHE
  APACHE
  BONANZA
  CHOLLA
  CHOLLA
  CHOLLA
  CORONADO
  CORONADO
  CRAIG
  CRAIG
  CROSS
  DALLMAN
  DUCK CREEK
  GIBBOUS CREEK
  GIBSON
  HUNTER
1
6
1
17
3
2
1
5
4
6
5
1
2
1-4
1
2
1-3
1
2
1
3
4
3
2
1
33
6
1-6
1
2
2
                                         100.

                                         100.
265.
299.
617.
391.
                                        1572.
                                       11301.
                98.
                98.
               410.
               126.
               285.
               119.
               320.
               320.
               455.
               455.
               450.
               205.
               416.
               400.
               670.
               400.
                                                   4/82
3/79
4/79
9/79
4/83
          6/79
          8/78
          9/84
          3/81
          4/78
         10/73
          7/80
         11/79
         12/79
         10/60
         10/83
         10/80
          7/76
         11/82
         10/82
          4/83
                                    8/82
 4/79
 4/79
12/79
 6/83
917.
917.
917.
200.
188.
350.
350.
440.
650.
510.
242.
242.
65.
360.
360.
366.
65.
495.
427.
350.
358.
300.
72.
408.
626.
626.
500.
6/80
7/77
12/75
12/77
8/76
6/78
1/77
9/84
3/81
10/75
12/79
11/80
9/75
3/79
6/80
5/78
5/83
7/82
8/78
12/81
12/60
8/82
4/73
7/73
12/78
10/80
12/82
10/80
10/77
6/76
7/78
8/77
7/78
2/77
9/84
3/81
10/75
12/79
12/80
6/76
5/79
6/80
5/76
8/83
10/82
3/79
4/82
4/81
9/82
4/73
6/74
12/80
12/80
4/83
           6/79
           1/79
          12/84
           6/81
           6/78
          12/73
          10/81
          12/79
           5/80
          12/80
           5/84
           1/81
           8/78
          10/83
           3/83
           6/83
THIS TABLE IDENTIFIES UNITS IN ALPHABETICAL ORDER.
RESPECTIVE COMPANIES CAN BE FOUND IN SECTION 1.
                               6-1

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                            SECTION 6
                      SUMMARY OF OPERATIONAL FGD SYSTEMS BY PROCESS AND UNIT
PROCESS/
UNIT NAME
JEFFREY
JEFFREY
JEFFREY
LA CYGNE
LARAMIE RIVER
LARAMIE RIVER
LAWRENCE
LAWRENCE
MARION
MARTIN LAKE
MARTIN LAKE
MARTIN LAKE
MCINTOSH
MEROM
MEROM
MONTICELLO
MUSCATINE
PARADISE
PARADISE
PETERSBURG
PROJECT
R.D. MORROW, SR.
R.D. MORROW, SR.
SAN MIGUEL
SANDOW
SEMINOLE
SEMINOLE
SIKESTON
SOMERSET
SOUTHWEST
THOMAS HILL
TOMBIGBEE
TOMBIGSEE
WIDOUS CREEK
WIDOWS CREEK
WINYAH
WINYAH
WINYAH
W.A. PARISH
UNIT NO.
3
Z
1
1
Z
1
5
*
*
1
3
2
3
Z
1
3
9
1
Z
3
1
Z
1
1
*
Z
1
1
1
1
3
3
Z
8
7
Z
ft
3
8
CAPACITY
MM
5*0.
5*0.
5*0.
87*.
570.
570.
*20.
125.
18*.
595.
595.
595.
36*.
**1.
**1.
800.
166.
70*.
70*.
532.
55.
12*.
12*.
*00.
382.
620.
620.
235.
625.
19*.
670.
179.
179.
550.
575.
1*0.
280.
280.
*92.
INITIAL
STARTUP
5/83
1/60
8/78
12/72
7/81
7/80
*/78
1/77
*/79
*/77
2/79
5/78
7/82
12/81
8/82
5/78
*/83
5/83
7/83
12/77
5/83
6/79
8/78
8/81
12/80
9/8*
5/83
6/81
7/8*
*/77
10/82
6/79
9/78
5/77
3/81
7/77
7/81
7/80
10/82
COMMERCIAL
STARTUP
5/83
5/80
8/78
6/73
7/86
7/80
*/78
1/77
6/79
10/77
2/79
5/78
9/82
2/62
8/82
10/78
8/83
7/83
12/83
12/77
5/83
6/79
8/78
10/81
1/81
1/85
2/8*
9/81
8/8*
9/77
12/82
6/79
9/78
1/78
9/81
7/77
9/81
7/80
12/82
               LIMESTONE/ALKALINE  FLYASH
                 SHERBURNE                2
                 SHERBURHE                1
               LIME/ALKALINE  FLYASH
                 CLAY BOSWELL           *
                 COAL CREEK             1
                 COAL CREEK             2
                 COLSTRIP               1
                 COLSTRIP               3
                 COLSTRIP               2
                 FOUR CORNERS           3
                 FOUR CORNERS           2
                 FOUR CORNERS           1
                 MILTON R.  YOUNG        2
                                                     22251.
 750.
 750.

1500.
 *75.
 327.
 327.
 360.
 778.
 360.
 225.
 195.
 195.
 37*.

3616.
 3/77
 3/76
 2/60
 7/79
 7/80
 9/75
10/83
 5/76
11/79
11/79
11/79
 9/77
 */77
 5/76
 */80
 8/79
 9/80
11/75
 1/8*
10/76
11/79
11/79
11/79
 6/78
               THIS TABLE IDENTIFIES UNITS IN ALPHABETICAL ORDER.
               RESPECTIVE COMPANIES CAN BE FOUND  IN  SECTION  1.
                                              6-2

-------
                                   UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                             SECTION 6
       SUMMARY  OF OPERATIONAL  FGO SYSTEMS BY PROCESS AND UNIT
PROCESS/
UNIT NAME
LIME/SPRAY DRYING
ANTELOPE VALLEY
CRAIG
HOLCOMB
LARAMIE RIVER
RAWHIDE
RIVERSIDE
SHIRAS
STANTON

MAGNESIUM OXIDE
CROMBY
EDDYSTONE
EDDYSTONE

SODIUM CARBONATE
JIM BRIDGER
NAUGHTON
REID GARDNER
REID GARDNER
REID GARDNER
REID GARDNER

SODIUM CARBONATE/SPRAY
COYOTE

WELLMAN LORD
DELAWARE CITY
DELAWARE CITY
DELAWARE CITY
SAN JUAN
SAN JUAN
SAN JUAN
SAN JUAN

UNIT NO.

1
3
1
3
1
6-7
3
1A


1
2
1


4
3
4
3
Z
1

DRYING
1


3
Z
1
1
3
2
4

CAPACITY
MW

440.
447.
347.
570.
279.
110.
44.
50.
2287.

150.
334.
240.
724.

550.
330.
250.
125.
125.
125.
1505.

440.
440.

60.
60.
60.
361.
534.
350.
534.
1959.
INITIAL
STARTUP

5/83
6/84
7/83
11/62
12/83
11/80
3/83
7/82


10/82
11/82
9/82


9/79
9/81
6/83
6/76
4/74
3/74


4/81


5/80
5/80
5/80
4/78
12/79
8/78
5/82

COMMERCIAL
STARTUP

7/84
2/85
8/83
11/82
4/84
12/80
4/83
11/82


1/63
12/82
12/82


2/80
12/81
7/83
7/76
4/74
4/74


5/81


5/80
5/80
5/80
4/78
12/79
8/78
7/82

TOTAL
                                       47255.
                               6-3

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                            SECTION 7
              SUMMARY OF END-PRODUCT DISPOSAL PRACTICES FOR OPERATIONAL FGD SYSTEMS

PROCESS/
UNIT NAME
                               	THROWAWAY	
                       UNIT NO   LANDFILL        POND
                                                                  	BYPRODUCT	
                                                                   TYPE             DISPOSITION
AQUEOUS CARBONATE/SPRAY DRYING

CHARLES R. HUNTLEY     66

DUAL ALKALI

A.B. BROWN             1
CANE RUN               6
NEWTON                 1
SCHAHFER               17

LIME
BRUCE MANSFIELD
BRUCE MANSFIELD
BRUCE MANSFIELD
CANE RUM
CANE RUN
CONESVILLE
CONESVILLE
D.B. WILSON
EAST BEND
ELRAMA
GREEN
GREEN
GREEN RIVER
HUNTER
HUNTER
HUNTINGTON
J.B. SIMS
MILL CREEK
MILL CREEK
MILL CREEK
MILL CREEK
MITCHELL
PADDY'S RUN
PHILLIPS
PLEASANTS
PLEASANTS
SPUR LOCK
3
2
1
5
4
6
5
1
2
1-4
1
2
1-3
1
2
1
3
4
3
2
1
33
6
1-6
1
2
2
LIMESTONE

APACHE
APACHE
BONANZA
CHOLLA
CHOLLA
CHOLLA
CORONADO
COROHADO
CRAIG
CRAIG
CROSS
DALLMAN
DUCK CREEK
GIBBONS CREEK
GIBSON
HUNTER
JEFFREY
JEFFREY
JEFFREY
LA CYGNE
LARAMIE RIVER
LARAMIE RIVER
LAWRENCE
                        3
                        2
                        1
                        4
                        2
                        1
                        2
                        1
                        2
                        1
                        2
                        3
                        1
                        1
                        S
                        3
                        3
                        2
                        1
                        1
                        2
                        1
                        5
                                                           ELEMENTAL SULFUR
                                                                                MARKETED
                               UNSTABILIZED
                               FIXATION
                               FIXATION
                               UNSTABILIZED
                                             FIXATION
                                             FIXATION
                                             FIXATION
                               FIXATION
                               FIXATION
                               FIXATION
                               FIXATION

                               FIXATION
                               FIXATION
                               STABILIZATION
                               STABILIZATION

                               STABILIZATION
                               STABILIZATION
                               STABILIZATION
                               FIXATION

                               FIXATION
                               FIXATION
                               FIXATION

                               FIXATION
                               FIXATION
                                             UNSTABILIZED
                                             FIXATION
                                             FIXATION
                                             FIXATION
                               UNSTABILIZED
                                FORCED-OX
                                FORCED-OX
                                                           NONE
                                                           NONE
                                                           NONE
                                                           NONE
                                                           NONE
                                                           NONE
                                                           NONE
                                                           NONE
                                             STABILIZATION
                                             UNSTABILIZED
                                             UNSTABILIZED
                                             UNSTABILIZED
                               STABILIZATION
                               FORCED-OX

                               FIXATION

                               STABILIZATION
              NONE
UNSTABILIZED
                                              FORCED-OX
                                              FORCED-OX
                                              FORCED-OX
                                              UNSTABILIZED
                                              FORCED-OX
                                              7-1

-------
UTILITY FGD SURVEY'- OCTOBER 1983 - SEPTEMBER 1984

                                            SECTION 7
              SUMMARY OF END-PRODUCT DISPOSAL PRACTICES FOR OPERATIONAL FGD SYSTEMS
PROCESS/
UNIT NAME
LAWRENCE
MARION
MARTIN LAKE
MARTIN LAKE
MARTIN LAKE
MCINTOSH
MEROM
MEROM
MONTICELLO
MUSCATINE
PARADISE
PARADISE
PETERSBURG
PROJECT
R.D. MORROW, SR.
R.D. MORROW, SR.
SAN MIGUEL
SANDOW
SEMINOLE
SEMINOLE
SIKESTON
SOMERSET
SOUTHWEST
THOMAS HILL
TOMBIGBEE
TOMBIG3EE
WIDOWS CREEK
WIDOWS CREEK
WINYAH
WINYAH
WINYAH
W.A. PARISH

UNIT
4
4
1
3
2
3
2
1
3
9
1
2
3
1
2
1
1
<+
2
1
1
1
1
3
3
2
8
7
2
4
3
8
NO LANDFILL POND TYPE DISPOSITION
FORCED-OX
STABILIZATION
STABILIZATION
STABILIZATION
STABILIZATION
FIXATION
FORCED-OX
FORCED-OX
STABILIZATION
FORCED-OX GYPSUM
FORCED-OX
FORCED-OX
FIXATION
FORCED-OX
FIXATION
FIXATION
STABILIZATION
FORCED-OX
FIXATION
FORCED-OX
UNSTABILIZED
STABILIZATION
STABILIZATION
FORCED-OX
UNSTABILIZED
UNSTABILIZED
FORCED-OX
FORCED-OX


UNSTABILIZED
STABILIZATION









MARKETED






















LIMESTONE/ALKALINE FLYASH
SHERBURNE
SHERBURNE
LIME/ALKALINE FLYASH
CLAY BOSWELL
COAL CREEK
COAL CREEK
COLSTRIP
COLSTRIP
COLSTRIP
FOUR CORNERS
FOUR CORNERS
FOUR CORNERS
MILTON R. YOUNG
LIME/SPRAY DRYING
ANTELOPE VALLEY
CRAIG
HOLCOMB
LARAMIE RIVER
RAWHIDE
RIVERSIDE
SHIRAS
STANTON
MAGNESIUM OXIDE
CROMBY
EDDYSTONE
EDDYSTONE
2
1

4
1
2
1
3
2
3
Z
I
Z

1
3
1
3
1
6-7
3
1A

1
2
1
FORCED-OX
FORCED-OX

UNSTABILIZED


UNSTABILIZED
FORCED-OX
UNSTABILIZED



UNSTABILIZED










SULFURIC ACID
SULFURIC ACID
SULFURIC ACID























MARKETED
MARKETED
MARKETED
                                              7-2

-------
                                                  UTILITY FGD SURVEY: OCTOBER 19S3 - SEPTEMBER 1984

                                            SECTION 7
              SUMMARY OF END-PRODUCT DISPOSAL PRACTICES FOR OPERATIONAL FGD SYSTEMS

PROCESS/
UNIT NAME
        	THROWAWAY	
UNIT NO   LANDFILL        POND
	BYPRODUCT	
 TYPE             DISPOSITION
SODIUM CARBONATE

JIM BRIDGER
NAUGHTON
REID GARDNER
REID GARDNER
REID GARDNER
REID GARDNER
                      UNSTABILIZED
                      UNSTABILIZED
                      UNSTABILIZED
                      UNSTABILIZED
SODIUM CARBONATE/SPRAY DRYING

COYOTE                 1

WELLMAN LORD
DELAWARE CITY
DELAWARE CITY
DELAWARE CITY
SAN JUAN
SAN JUAN
SAN JUAN
SAN JUAN
                                    SULFURIC
                                    SULFUR1C
                                    SULFURIC
                                    SULFURIC
                                    SULFURIC
                                    SULFURIC
                                    SULFURIC
  ACID
  ACID
  ACID
  ACID
  ACID
  ACID
  ACID
MARKETED
MARKETED
MARKETED
MARKETED
MARKETED
MARKETED
                                              7-3

-------
                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
            SECTION 8
SUMMARY OF FGO SYSTEMS IN OPERATION
COMPANY NAME/
UNIT NAME UNIT NO.
ALABAMA ELECTRIC
TOMBIGBEE 2
ALABAMA ELECTRIC
TOMBIGBEE 3
ARIZONA ELECTRIC POWER
APACHE 2
ARIZONA ELECTRIC POWER
APACHE 3
ARIZONA PUBLIC SERVICE
CHOLLA 1
ARIZONA PUBLIC SERVICE
CHOLLA Z
ARIZONA PUBLIC SERVICE
CHOLLA 4
ARIZONA PUBLIC SERVICE
FOUR CORNERS 1
ARIZONA PUBLIC SERVICE
FOUR CORNERS 2
ARIZONA PUBLIC SERVICE
FOUR CORNERS 3
ASSOCIATED ELECTRIC
THOMAS HILL t
BASIN ELECTRIC POWER
ANTELOPE VALLEY 1
BASIN ELECTRIC POWER
URAMIE RIVER 1
BASIN ELECTRIC POWER
LARAMIE RIVER 2
BASIN ELECTRIC POWER
LARAMIE RIVER 3
BIG RIVERS ELECTRIC
D.B. WILSON 1
BIG RIVERS ELECTRIC
GREEN 1
BIG RIVERS ELECTRIC
GREEN 2
CENTRAL ILLINOIS LIGHT
DUCK CREEK 1
CENTRAL ILLINOIS PUBLIC SERV
NEWTON 1
CINCINNATI GAS 8 ELECTRIC
EAST BEND 2
COLORADO UTE ELECTRIC
CRAIG 1
COLORADO UTE ELECTRIC
NEW OR C
RETROFIT
NEW
NEW
NEW
NEW
RETROFIT
NEW
NEW
RETROFIT
RETROFIT
RETROFIT
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
:APACITY
MW
179.
179.
98.
98.
119.
285.
126.
195.
195.
225.
670.
440.
570.
570.
570.
440.
242.
242.
416.
617.
650.
455.
455.
PROCESS/
SYSTEM SUPPLIER
LIMESTONE
PEABODY PROCESS SYSTEMS
LIMESTONE
PEABODY PROCESS SYSTEMS
LIMESTONE
RESEARCH-COTTRELL
LIMESTONE
RESEARCH-COTTRELL
LIMESTONE
RESEARCH-COTTRELL
LIMESTONE
RESEARCH-COTTRELL
LIMESTONE
RESEARCH-COTTRELL
LIME/ALKALINE FLYASH
GE ENVIRONMENTAL SERVICES
LIME/ALKALINE FLYASH
GE ENVIRONMENTAL SERVICES
LIME/ALKALINE FLYASH
GE ENVIRONMENTAL SERVICES
LIMESTONE
M.W. KELLOGG
LIME/SPRAY DRYING
JOY MFG/NIRO ATOMIZER
LIMESTONE
RESEARCH-COTTRELL
LIMESTONE
RESEARCH-COTTRELL
LIME/SPRAY DRYING
BABCOCK t WILCOX
LIME
M.W. KELLOGG
LIME
AMERICAN AIR FILTER
LIME
AMERICAN AIR FILTER
LIMESTONE
ENVIRONEERING, RILEY STOKER
DUAL ALKALI
GE ENVIRONMENTAL SERVICES
LIME
BABCOCK t WILCOX
LIMESTONE
PEABODY PROCESS SYSTEMS
LIMESTONE
START-UP
DATE
9/78
6/79
8/78
6/79
10/73
4/78
3/81
11/79
11/79
11/79
10/82
5/83
7/80
7/81
11/82
9/84
12/79
11/80
7/76
9/79
3/81
10/80
12/79
                        PEABODY PROCESS SYSTEMS
             8-1

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                            SECTION 8
                                SUMMARY OF FGD SYSTEMS IN OPERATION
COMPANY NAME/
UNIT NAME UNIT NO.
COLORADO UTE ELECTRIC
CRAIG 3
COLUMBUS 8 SOUTHERN OHIO ELEC
CONESVILLE 5
COLUMBUS & SOUTHERN OHIO ELEC
CONESVILLE 6
COOPERATIVE POWER ASSOCIATION
COAL CREEK 1
COOPERATIVE POWER ASSOCIATION
COAL CREEK 2
DELMARVA POWER t LIGHT
DELAWARE CITY 1
DELMARVA POWER t LIGHT
DELAWARE CITY 2
DELMARVA POWER ft LIGHT
DELAWARE CITY 3
DESERET GEN & TRANS
BONANZA 1
DUQUESNE LIGHT
ELRAMA 1-4
DUQUESNE LIGHT
PHILLIPS 1-6
EAST KENTUCKY POWER
SPUR LOCK 2
GRAND HAVEN BRD OF LIGHT ft PWR
J.B. SIMS 3
HOOSIER ENERGY
MEROM 1
HOOSIER ENERGY
MEROM 2
HOUSTON LIGHTING t POWER
W.A. PARISH 8
INDIANAPOLIS POWER & LIGHT
PETERSBURG 3
KANSAS CITY POWER ft LIGHT
LA CYGNE 1
KANSAS POWER ft LIGHT
JEFFREY 1
KANSAS POWER ft LIGHT
JEFFREY 2
KANSAS POWER ft LIGHT
JEFFREY 3
KANSAS POWER ft LIGHT
LAWRENCE 4
KANSAS POWER ft LIGHT
LAWRENCE 5
NEW OR CAPACITY
RETROFIT MW
NEW
NEW
NEW
NEW
NEW
RETROFIT
RETROFIT
RETROFIT
NEW
RETROFIT
RETROFIT
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
RETROFIT
RETROFIT
447.
350.
350.
327.
327.
60.
60.
60.
410.
510.
408.
500.
65.
441.
441.
492.
532.
874.
540.
540.
540.
125.
420.
PROCESS/
SYSTEM SUPPLIER
LIME/SPRAY DRYING
BABCOCK ft WILCOX
LIME
AIR CORRECTION DIVISION, UOP
LIME
AIR CORRECTION DIVISION, UOP
LIME/ALKALINE FLYASH
COMBUSTION ENGINEERING
LIME/ALKALINE FLYASH
COMBUSTION ENGINEERING
MELLMAN LORD
DAVY MCKEE
WELLMAN LORD
DAVY MCKEE
WELLMAN LORD
DAVY MCKEE
LIMESTONE
COMBUSTION ENGINEERING
LIME
GE ENVIRONMENTAL SERVICES
LIME
GE ENVIRONMENTAL SERVICES
LIME
THYSSEN/CEA
LIME
BABCOCK ft WILCOX
LIMESTONE
MITSUBISHI HEAVY INDUSTRIES
LIMESTONE
MITSUBISHI HEAVY INDUSTRIES
LIMESTONE
GE ENVIRONMENTAL SERVICES
LIMESTONE
AIR CORRECTION DIVISION, UOP
LIMESTONE
BABCOCK ft WILCOX
LIMESTONE
COMBUSTION ENGINEERING
LIMESTONE
COMBUSTION ENGINEERING
LIMESTONE
COMBUSTION ENGINEERING
LIMESTONE
COMBUSTION ENGINEERING
LIMESTONE
COMBUSTION ENGINEERING
START-UP
DATE
6/84
1/77
6/78
7/79
7/80
5/80
5/80
5/80
9/84
10/75
7/73
12/82
5/83
8/82
12/81
10/82
12/77
12/72
8/78
1/80
5/83
1/77
4/78
                                              8-2

-------
                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
            SECTION 8
SUMMARY OF FGD SYSTEMS IN OPERATION
COMPANY NAME/
UNIT NAME UNIT NO.
KENTUCKY UTILITIES
GREEN RIVER 1-3
LAKELAND UTILITIES
MCINTOSH 3
LOUISVILLE GAS * ELECTRIC
CANE RUN 4
LOUISVILLE GAS & ELECTRIC
CANE RUN 5
LOUISVILLE GAS 4 ELECTRIC
CANE RUN 6
LOUISVILLE GAS 4 ELECTRIC
MILL CREEK 1
LOUISVILLE GAS 8 ELECTRIC
MILL CREEK 2
LOUISVILLE GAS & ELECTRIC
MILL CREEK 3
LOUISVILLE GAS & ELECTRIC
MILL CREEK 4
LOUISVILLE GAS & ELECTRIC
PADDY'S RUN 6
MARQUETTE BOARD OF LIGHT 4 PMR
SHIRAS 3
MICHIGAN SO CENTRAL PWR AGENCY
PROJECT 1
MINNESOTA POWER & LIGHT
CLAY BOSWELL 4
MINNKOTA POWER
MILTON R. YOUNG Z
MONONGAHELA POWER
PLEASANTS 1
MONOHGAHEU POWER
PLEASANTS 2
MONTANA POWER
COLSTRIP 1
MONTANA POWER
COLSTRIP 2
MONTANA POWER
COLSTRIP 3
MONTANA-DAKOTA UTILITIES
COYOTE 1
MUSCATINE POWER & WATER
MUSCATINE 9
NEVADA POWER
REID GARDNER 1
NEVADA POWER
REID GARDNER 2
NEW OR CAPACITY
RETROFIT MW
RETROFIT
NEW
RETROFIT
RETROFIT
RETROFIT
RETROFIT
RETROFIT
NEW
NEW
RETROFIT
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
RETROFIT
RETROFIT
65.
364.
188.
200.
299.
358.
350.
427.
495.
72.
44.
55.
475.
374.
626.
626.
360.
360.
778.
440.
166.
125.
125.
PROCESS/
SYSTEM SUPPLIER
LIME
AMERICAN AIR FILTER
LIMESTONE
BABCOCK 4 WILCOX
LIME
AMERICAN AIR FILTER
LIME
COMBUSTION ENGINEERING
DUAL ALKALI
THYSSEN/CEA
LIME
COMBUSTION ENGINEERING
LIME
COMBUSTION ENGINEERING
LIME
AMERICAN AIR FILTER
LIME
AMERICAN AIR FILTER
LIME
COMBUSTION ENGINEERING
LIME/SPRAY DRYING
GE ENVIRONMENTAL SERVICES
LIMESTONE
BABCOCK 4 WILCOX
LIME/ALKALINE FLYASH
PEABODY PROCESS SYSTEMS
LIME/ALKALINE FLYASH
THYSSEN/CEA
LIME
BABCOCK & WILCOX
LIME
BABCOCK 4 WILCOX
LIME/ALKALINE FLYASH
THYSSEN/CEA
LIME/ALKALINE FLYASH
THYSSEN/CEA
LIME/ALKALINE FLYASH
BECHTEL/MONTANA POWER
SODIUM CARBONATE/SPRAY DRYING
WHEELABRATOR-FRYE/R.I.
LIMESTONE
RESEARCH-COTTPELL
SODIUM CARBONATE
THYSSEN/CEA
SODIUM CARBONATE
THYSSEN/CEA
START-UP
DATE
9/75
7/82
8/76
12/77
4/79
12/80
12/81
8/78
7/82
4/73
3/83
5/83
2/80
9/77
12/76
10/80
9/75
5/76
10/83
4/81
4/83
3/74
4/74
              8-3

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                            SECTION 8
                                SUMMARY OF FGD SYSTEMS IN OPERATION
COMPANY NAME/
UNIT NAME UNIT NO.
NEVADA POWER
REID GARDNER 3
NEVADA POWER
REID GARDNER 4
NEW YORK STATE ELEC & GAS
SOMERSET 1
NIAGARA MOHAWK POWER
CHARLES R. HUNTLEY 66
NORTHERN INDIANA PUB SERVICE
SCHAHFER 17
NORTHERN STATES POWER
RIVERSIDE 6-7
NORTHERN STATES POWER
SHERBURNE 1
NORTHERN STATES POWER
SHERBURNE 2
PACIFIC POWER i LIGHT
JIM BRIDGER 4
PENNSYLVANIA POWER
BRUCE MANSFIELD 1
PENNSYLVANIA POWER
BRUCE MANSFIELD 2
PENNSYLVANIA POWER
BRUCE MANSFIELD 3
PHILADELPHIA ELECTRIC
CROMBY 1
PHILADELPHIA ELECTRIC
EDDYSTOHE 1
PHILADELPHIA ELECTRIC
EDDYSTONE 2
PLATTE RIVER POWER AUTHORITY
RAWHIDE 1
PUBLIC SERVICE INDIANA
GIBSON 5
PUBLIC SERVICE OF NEW MEXICO
SAN JUAN 1
PUBLIC SERVICE OF NEW MEXICO
SAN JUAN 2
PUBLIC SERVICE OF NEW MEXICO
SAN JUAN 3
PUBLIC SERVICE OF NEW MEXICO
SAN JUAN 4
SALT RIVER PROJECT
CORONADO 1
SALT RIVER PROJECT
CORONADO 2
NEW OR CAPACITY
RETROFIT MW
NEW
NEW
NEW
RETROFIT
NEW
RETROFIT
NEW
NEW
NEW
NEW
NEW
NEW
RETROFIT
RETROFIT
RETROFIT
NEW
NEW
RETROFIT
RETROFIT
NEW
NEW
NEW
NEW
125.
250.
625.
100.
391.
110.
750.
750.
550.
917.
917.
917.
150.
240.
334.
279.
670.
361.
350.
534.
534.
320.
320.
PROCESS/
SYSTEM SUPPLIER
SODIUM CARBONATE
THYSSEN/CEA
SODIUM CARBONATE
THYSSEN/CEA
LIMESTONE
PEABODY PROCESS SYSTEMS
AQUEOUS CARBONATE/SPRAY DRYING
ROCKWELL INTERNATIONAL
DUAL ALKALI
FMC
LIME/SPRAY DRYING
JOY MFG/NIRO ATOMIZER
LIMESTONE/ALKALINE FLYASH
COMBUSTION ENGINEERING
LIMESTONE/ALKALINE FLYASH
COMBUSTION ENGINEERING
SODIUM CARBONATE
AIR CORRECTION DIVISION, UOP
LIME
GE ENVIRONMENTAL SERVICES
LIME
GE ENVIRONMENTAL SERVICES
LIME
M.W. KELLOGG
MAGNESIUM OXIDE
UNITED ENGINEERS
MAGNESIUM OXIDE
UNITED ENGINEERS
MAGNESIUM OXIDE
UNITED ENGINEERS
LIME/SPRAY DRYING
JOY MFG/NIRO ATOMIZER
LIMESTONE
M.W. KELLOGG
WELLMAN LORD
DAVY MCKEE
WELLMAN LORD
DAVY MCKEE
WELLMAN LORD
DAVY MCKEE
WELLMAN LORD
DAVY MCKEE
LIMESTONE
M.W. KELLOGG
LIMESTONE
M.W. KELLOGG
START-UP
DATE
6/76
6/83
7/84
4/82
4/83
11/80
3/76
3/77
9/79
12/75
7/77
6/80
10/82
9/82
11/82
12/83
10/82
4/78
8/78
12/79
5/82
11/79
7/80
                                              8-4

-------
                                              UTILITY FGD SURVEY:  OCTOBER  1983 -  SEPTEMBER  1984
                                        SECTION 8
                            SUMMARY OF FGD SYSTEMS IN OPERATION
COMPANY NAME/
UNIT NAME UNIT NO.
SAN MIGUEL ELECTRIC
SAN MIGUEL 1
SEMINOLE ELECTRIC
SEMINOLE 1
SEMINOLE ELECTRIC
SEMINOLE 2
SIKESTON BRD OF MUNICIPAL UTIL
SIKESTON 1
SOUTH CAROLINA PUBLIC SERVICE
CROSS 2
SOUTH CAROLINA PUBLIC SERVICE
WINYAH 2
SOUTH CAROLINA PUBLIC SERVICE
WINYAH 3
SOUTH CAROLINA PUBLIC SERVICE
WINYAH 4
SOUTH MISSISSIPPI ELEC PWR
R.D. MORROW, SR. 1
SOUTH MISSISSIPPI ELEC PWR
R.D. MORROW, SR. 2
SOUTHERN ILLINOIS POWER
MARION 4
SOUTHERN INDIANA GAS & ELEC
A.B. BROWN 1
SPRINGFIELD CITY UTILITIES
SOUTHWEST 1
SPRINGFIELD WATER, LIGHT & PWR
DALLMAN 3
SUNFLOWER ELECTRIC
HOLCOMB 1
TENNESSEE VALLEY AUTHORITY
PARADISE 1
TENNESSEE VALLEY AUTHORITY
PARADISE 2
TENNESSEE VALLEY AUTHORITY
WIDOWS CREEK 7
TENNESSEE VALLEY AUTHORITY
WIDOWS CREEK 8
TEXAS MUNICIPAL POWER AGENCY
GIBBONS CREEK 1
TEXAS POWER t LIGHT
SANOOW 4
TEXAS UTILITIES
MARTIN LAKE 1
TEXAS UTILITIES
NEW OR C
RETROFIT
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
RETROFIT
RETROFIT
RETROFIT
RETROFIT
NEW
NEW
NEW
NEW
IAPACITY
MW
400.
620.
620.
235.
450.
140.
280.
280.
124.
124.
184.
265.
194.
205.
347.
704.
704.
575.
550.
400.
382.
595.
595.
PROCESS/
SYSTEM SUPPLIER
LIMESTONE
BABCOCK t WILCOX
LIMESTONE
PEABODY PROCESS SYSTEMS
LIMESTONE
PEABODY PROCESS SYSTEMS
LIMESTONE
BABCOCK t WILCOX
LIMESTONE
PEABODY PROCESS SYSTEMS
LIMESTONE
BABCOCK t WILCOX
LIMESTONE
BABCOCK t WILCOX
LIMESTONE
AMERICAN AIR FILTER
LIMESTONE
ENVIRONEERING, RILEY STOKER
LIMESTONE
ENVIRONEERING. RILEY STOKER
LIMESTONE
BABCOCK t WILCOX
DUAL ALKALI
FMC
LIMESTONE
AIR CORRECTION DIVISION, UOP
LIMESTONE
RESEARCH-COTTRELL
LIME/SPRAY DRYING
JOY MFG/NIRO ATOMIZER
LIMESTONE
GE ENVIRONMENTAL SERVICES
LIMESTONE
GE ENVIRONMENTAL SERVICES
LIMESTONE
COMBUSTION ENGINEERING
LIMESTONE
TENNESSEE VALLEY AUTHORITY
LIMESTONE
COMBUSTION ENGINEERING
LIMESTONE
COMBUSTION ENGINEERING
LIMESTONE
RESEARCH-COTTRELL
LIMESTONE
START-UP
DATE
8/81
5/83
9/84
6/81
10/83
7/77
7/80
7/81
6/78
6/79
4/79
3/79
4/77
10/80
7/83
5/83
7/83
3/81
5/77
11/82
12/80
4/77
5/78
MARTIN LAKE
                                                    RESEARCH-COTTRELL
                                         8-5

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                            SECTION 8
                                SUMMARY OF FGD SYSTEMS IN OPERATION
COMPANY NAME/
UNIT NAME
TEXAS UTILITIES
MARTIN LAKE
TEXAS UTILITIES
MONTICELLO
NEW OR CAPACITY PROCESS/
UNIT NO. RETROFIT MW SYSTEM SUPPLIER
3
3
UNITED POWER ASSOCIATION
STAHTON 1A
UTAH POWER & LIGHT
HUNTER
UTAH POWER S LIGHT
HUNTER
UTAH POWER & LIGHT
HUUTER
UTAH POWER t LIGHT
HUNTINGTON
UTAH POWER & LIGHT
NAUGHTON
WEST PENN POWER
MITCHELL
1
Z
3
1
3
33
NEW 595. LIMESTONE
RESEARCH-COTTRELL
NEW 800. LIMESTONE
GE ENVIRONMENTAL SERVICES
NEW 50. LIME/SPRAY DRYING
RESEARCH-COTTRELL
NEW 360. LIME
GE ENVIRONMENTAL SERVICES
NEW 360 . LIME
GE ENVIRONMENTAL SERVICES
NEW 400. LIMESTONE
GE ENVIRONMENTAL SERVICES
NEW 366. LIME
GE ENVIRONMENTAL SERVICES
RETROFIT 330. SODIUM CARBONATE
AIR CORRECTION DIVISION, UOP
RETROFIT 300. LIME
GE ENVIRONMENTAL SERVICES
START-UP
DATE
2/79
5/78
7/82
3/79
6/80
4/83
5/78
9/81
8/82
     TOTAL
                                               47255.
                                              8-6

-------
                     UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
               SECTION 9
SUMMARY OF FGD SYSTEMS UNDER CONSTRUCTION
COMPANY NAME/
UNIT NAME UNIT NO.
ARIZONA PUBLIC SERVICE
FOUR CORNERS 4
ARIZONA PUBLIC SERVICE
FOUR CORNERS 5
BASIN ELECTRIC POWER
ANTELOPE VALLEY 2
GRAND RIVER DAM AUTHORITY
GRDA Z
HOUSTON LIGHTING & POWER
LIMESTONE 1
HOUSTON LIGHTING ft POWER
LIMESTONE Z
INDIANAPOLIS POWER t LIGHT
PETERSBURG 4
JACKSONVILLE ELEC AUTHORITY
ST. JOHNS RVR PWR PRK 1
JACKSONVILLE ELEC AUTHORITY
ST. JOHNS RVR PWR PRK Z
LOS ANGELES DEPT OF WTR t PWR
INTERMOUNTAIN 1
LOS ANGELES DEPT OF WTR & PWR
INTERMOUNTAIN ^
LOWER COLORADO RIVER AUTH
FAYETTE POWER PROJECT 3
MONTANA POWER
COLSTRIP 4
NORTHERN INDIANA PUB SERVICE
SCHAHFER 18
NORTHERN STATES POWER
SHERBURNE 3
ORLANDO UTILITIES COMMISSION
C.H. STANTON 1
PACIFIC POWER t LIGHT
JIM BRIDGER Z
PLAINS ELECTRIC G 1 T
PLAINS ESCALANTE 1
SIERRA PACIFIC POWER
VALMY 2
SOUTHERN INDIANA GAS & ELEC
A.B. BROWN 2
SOUTHWESTERN ELECTRIC POWER
DOLET HILLS 1
SOUTHWESTERN ELECTRIC POWER
HENRY W. PIRKEY 1
TAMPA ELECTRIC
BIG BEND 4
NEW OR C
RETROFIT
RETROFIT
RETROFIT
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
RETROFIT
NEW
NEW
NEW
NEW
NEW
NEW
:APACITY
MW
745.
745.
440.
520.
750.
750.
530.
612.
612.
820.
820.
451.
778.
391.
610.
465.
550.
233.
276.
265.
720.
720.
458.
PROCESS/
SYSTEM SUPPLIER
LIME
BABCOCK t WILCOX
LIME
BABCOCK I WILCOX
LIME/SPRAY DRYING
JOY MFG/NIRO ATOMIZER
LIME/SPRAY DRYING
FLAKT
LIMESTONE
COMBUSTION ENGINEERING
LIMESTONE
COMBUSTION ENGINEERING
LIMESTONE
RESEARCH-COTTRELL
LIMESTONE
RESEARCH-COTTRELL
LIMESTONE
RESEARCH-COTTRELL
LIMESTONE
GE ENVIRONMENTAL SERVICES
LIMESTONE
GE ENVIRONMENTAL SERVICES
LIMESTONE
COMBUSTION ENGINEERING
LIME/ALKALINE FLYASH
BECHTEL/MONTANA POWER
DUAL ALKALI
FMC
LIME/SPRAY DRYING
JOY MFG/NIRO ATOMIZER
LIMESTONE
COMBUSTION ENGINEERING
SODIUM CARBONATE
BABCOCK t WILCOX
LIMESTONE
COMBUSTION ENGINEERING
LIME/SPRAY DRYING
ROCKWELL INTERNATIONAL
DUAL ALKALI
FMC
LIMESTONE
AIR CORRECTION DIVISION, UOP
LIMESTONE
AIR CORRECTION DIVISION, UOP
LIMESTONE
RESEARCH-COTTRELL
START-UP
DATE
10/64
10/84
11/85
3/85
12/85
12/86
3/86
4/87
10/68
7/86
7/87
11/87
10/85
6/86
0/88
0/87
0/86
10/84
6/85
1/85
12/85
12/84
1/85
                 9-1

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                            SECTION 9
                             SUMMARY OF FGD SYSTEMS UNDER CONSTRUCTION
    COMPANY NAME/
    UNIT NAME
           NEW OR   CAPACITY  PROCESS/
UNIT NO.  RETROFIT     MW     SYSTEM SUPPLIER
                                      START-UP
                                        DATE
    TUCSON ELECTRIC POWER
    SPRINGERVILLE

    WEST TEXAS UTILITIES
    OKLAUNION
                                    NEW
          NEW
370.   LIME/SPRAY DRYING
       JOY MFG/NIRO ATOMIZER

504.   LIMESTONE
       GE ENVIRONMENTAL SERVICES
                                                                                         2/85
                                                               9/86
    TOTAL
                                               14335.
                                              9-2

-------
                                              UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER
                                        SECTION 10
                          SUMMARY OF CONTRACT AWARDED FGD SYSTEMS
COMPANY NAME/
UNIT NAME
CAJUN ELECTRIC POWER
OXBOW
CENTRAL POWER ft LIGHT
COLETO CREEK
EAST KENTUCKY POWER
J.K. SMITH
NEW OR CAPACITY
UNIT NO. RETROFIT MW
NEW
1
NEW
2
NEW
1
HOUSTON LIGHTING ft POWER NEW
MALAKOFF 1
HOUSTON LIGHTING ft POWER NEW
MALAKOFF 2
KENTUCKY UTILITIES
HANCOCK
PACIFIC POWER ft LIGHT
JIM BRIDGER
PACIFIC POWER ft LIGHT
JIM BRIDGER
PACIFIC POWER ft LIGHT
WYODAK
SOUTH CAROLINA PUBLIC
CROSS
TEXAS POWER ft LIGHT
TWIN OAKS
TEXAS POWER ft LIGHT
TWIN OAKS
TEXAS UTILITIES
FOREST GROVE
TEXAS UTILITIES
MARTIN LAKE
TUCSON ELECTRIC POWER
SPRINGERVILLE
NEW
1
RETROFIT
1
RETROFIT
3
RETROFIT
1
SERVICE NEW
1
NEW
1
NEW
2
NEW
1
NEW
4
NEW
2
540.
720.
650.
690.
690.
650.
550.
550.
330.
450.
750.
750.
750.
750.
370.
PROCESS/
SYSTEM SUPPLIER
LIME/SPRAY DRYING
JOY MFG/NIRO ATOMIZER
LIME/SPRAY DRYING
JOY MFG/NIRO ATOMIZER
LIME
BABCOCK ft WILCOX
LIMESTONE
GE ENVIRONMENTAL SERVICES
LIMESTONE
GE ENVIRONMENTAL SERVICES
LIMESTONE
BABCOCK ft WILCOX
SODIUM CARBONATE
BABCOCK ft WILCOX
SODIUM CARBONATE
BABCOCK ft WILCOX
LIME/SPRAY DRYING
JOY/NIRO
LIMESTONE
PEABODY PROCESS SYSTEMS
LIMESTONE
GE ENVIRONMENTAL SERVICES
LIMESTONE
GE ENVIRONMENTAL SERVICES
LIMESTONE
WHEELABRATOR AIR POLTN. CNTRL.
LIMESTONE
RESEARCH-COTTRELL
LIME/SPRAY DRYING
JOY MFG/NIRO ATOMIZER
START-UP
DATE
99/99
10/93
0/92
12/89
12/90
10/93
0/90
0/88
0/86
5/91
8/89
8/91
0/88
0/89
2/89
TOTAL
                                            9190.
                                        10-1

-------
                UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 198*
          SECTION 11
SUMMARY OF PLANNED FGD SYSTEMS
COMPANY NAME/
UNIT NAME UNIT
LETTER OF INTENT
IOWA ELECTRIC LIGHT & PWR
GUTHRIE CO. 1
MIDDLE SOUTH UTILITIES
WILTON 1
MIDDLE SOUTH UTILITIES
WILTON 2
TOTAL
REQUESTING/EVALU
BOSTON EDISON
NEW BOSTON 1
BOSTON EDISON
NEW BOSTON Z
LOUISVILLE GAS & ELECTRIC
TRIMBLE COUNTY 1
LOUISVILLE GAS t ELECTRIC
TRIMBLE COUNTY Z
TOTAL
CONSIDERING FGD
ARIZONA PUBLIC SERVICE
CHOLLA 5
ATLANTIC CITY ELECTRIC
CUMBERLAND 1
BASIN ELECTRIC POWER
ANTELOPE VALLEY 3
CENTRAL MAINE POWER
SEARS ISLAND 1
CINCINNATI GAS ft ELECTRIC
EAST BEND 1
CINCINNATI GAS ft ELECTRIC
ZIMMER 1
COOPERATIVE POWER
N/D 1
DELMARVA POWER ft LIGHT
VIENNA 9
DESERET GEN ft TRANS
BONANZA 2
FLORIDA POWER ft LIGHT
MARTIN 3
FLORIDA POWER t LIGHT
MARTIN 4
GENERAL PUBLIC UTILITIES
NEW OR
NO. RETROFIT
SIGNED
NEW
NEW
NEW

ATING BIDS
NEW
NEW
NEW
NEW

SYSTEMS
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
CAPACITY
MW

720.
890.
890.
2500.

388.
388.
575.
575.
1926.

126.
330.
560.
600.
650.
1386.
750.
550.
410.
800.
800.
690.
PROCESS/
SYSTEM SUPPLIER

LIMESTONE
COMBUSTION ENGINEERING
LIMESTONE
COMBUSTION ENGINEERING
LIMESTONE
COMBUSTION ENGINEERING


LIMESTONE
VENDOR NOT SELECTED
LIMESTONE
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED


PROCESS NOT SELECTED
VENDOR NOT SELECTED
LIMESTONE
VENDOR NOT SELECTED
LIME/SPRAY DRYING
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
LIMESTONE
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
LIMESTONE
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
LIMESTONE
START-UP
DATE

99/99
99/99
99/99


10/87
6/88
7/87
7/90


0/97
99/99
0/92
11/95
0/89
0/91
0/94
0/95
0/92
0/94
0/95
0/93
                      VENDOR  NOT  SELECTED
           11-1

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                            SECTION 11
                                  SUMMARY OF PLANNED FGD SYSTEMS
COMPANY NAME/
UNIT NAME UNIT NO.
GENERAL PUBLIC UTILITIES
COAL Z
INDIANAPOLIS POWER t LIGHT
PATRIOT 1
INDIANAPOLIS POWER & LIGHT
PATRIOT 2
INDIANAPOLIS POWER » LIGHT
PATRIOT 3
KENTUCKY UTILITIES
HANCOCK 2
LOWER COLORADO RIVER AUTH
FAYETTE POWER PROJECT 4
NEBRASKA PUBLIC POWER DISTRICT
FOSSIL III 1
NEVADA POWER
HARRY ALLEN 1
NEVADA POWER
HARRY ALLEN 2
NEVADA POWER
HARRY ALLEN 3
NEVADA POWER
HARRY ALLEN 4
PUBLIC SERVICE OF NEW MEXICO
NEW MEXICO 1
PUB. SER. CO. OF COLORADO
PAWNEE 2
SALT RIVER PROJECT
CORONADO 3
SAN ANTONIO PUBLIC SERVICE
N/D 1
SAN ANTONIO PUBLIC SERVICE
N/D 2
SAN ANTONIO PUBLIC SERVICE
N/D 3
SAN ANTONIO PUBLIC SERVICE
N/D 4
SEMINOLE ELECTRIC
TAYLOR 1
SEMINOLE ELECTRIC
TAYLOR 2
SIERRA PACIFIC POWER
THOUSAND SPRINGS 1
SIERRA PACIFIC POWER
THOUSAND SPRINGS 2
SIERRA PACIFIC POWER
THOUSAND SPRINGS 3
NEW OR
RETROFIT
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
NEW
CAPACITY
MW
690.
650.
650.
650.
650.
451.
650.
500.
500.
500.
500.
500.
500.
280.
500.
500.
500.
500.
620.
620.
500.
500.
500.
PROCESS/
SYSTEM SUPPLIER
LIMESTONE
VENDOR NOT SELECTED
LIMESTONE
VENDOR NOT SELECTED
LIMESTONE
VENDOR NOT SELECTED
LIMESTONE
VENDOR NOT SELECTED
LIMESTONE
VENDOR NOT SELECTED
LIMESTONE
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
TRONA/DRY INJECTION
VENDOR NOT SELECTED
LIMESTONE
VENDOR NOT SELECTED
LIMESTONE
VENDOR NOT SELECTED
LIMESTONE
VENDOR NOT SELECTED
LIMESTONE
VENDOR NOT SELECTED
LIMESTONE
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
PROCESS NOT SELECTED
VENDOR NOT SELECTED
START-UP
DATE
0/97
0/93
O/ 0
O/ 0
99/99
6/90
3/96
0/94
0/95
0/96
0/97
0/95
0/90
0/92
0/93
0/95
0/99
99/99
99/99
99/99
0/90
0/95
0/99
                                             11-2

-------
                                             UTILITY  F6D SURVEY:  OCTOBER  1983  -  SEPTEMBER  1984
                                        SECTION  11
                              SUMMARY  OF PLANNED F6D  SYSTEMS
COMPANY NAME/ NEW OR
UNIT NAME UNIT NO. RETROFIT
SOUTHWESTERN ELECTRIC POWER NEW
WALKER CO. 1
SOUTHWESTERN ELECTRIC POWER NEW
WALKER CO. 2
SOUTHWESTERN PUBLIC SERVICE NEW
SOUTH PLAINS 1
TUCSON ELECTRIC POWER NEW
SPRINGERVILLE 3
WASHINGTON MATER POWER NEW
CRESTON COAL 1
WASHINGTON WATER POWER NEW
CRESTON COAL 2
WASHINGTON WATER POWER NEW
CRESTON COAL 3
WASHINGTON WATER POWER NEW
CRESTON COAL 4
WEST TEXAS UTILITIES NEW
OKLAUNION 2
WHITE PINE COUNTY NEW
WHITE PINE PWR PROJ. 1
WHITE PINE COUNTY NEW
WHITE PINE PWR PROJ. 2
CAPACITY PROCESS/
MW SYSTEM SUPPLIER
720. PROCESS NOT SELECTED
VENDOR NOT SELECTED
720. PROCESS NOT SELECTED
VENDOR NOT SELECTED
572. PROCESS NOT SELECTED
VENDOR NOT SELECTED
370. PROCESS NOT SELECTED
VENDOR NOT SELECTED
570 . LIMESTONE
VENDOR NOT SELECTED
570. LIMESTONE
VENDOR NOT SELECTED
570 . LIMESTONE
VENDOR NOT SELECTED
570. LIMESTONE
VENDOR NOT SELECTED
504. PROCESS NOT SELECTED
VENDOR NOT SELECTED
620. PROCESS NOT SELECTED
VENDOR NOT SELECTED
820. PROCESS NOT SELECTED-
VENDOR NOT SELECTED
START-UP
DATE
12/93
12/93
0/90
0/91
0/95
0/97
0/98
0/99
0/96
3/91
3/92
TOTAL
                                           26869.
                                        11-3

-------
                         UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER 1984
                   SECTION 12
TOTAL FGD UNITS AND CAPACITY (MW) INSTALLED BY YEAR
YEAR
1968
1969
1971
1972
1973
1974
1975
1976
1977
1978
1979
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
UNDEFINED
NEW ON LINE
NO. MW
1
0
1
10
5
4
9
7
11
15
19
20
11
17
16
9
9
7
6
5
5
7
5
5
7
3
8
3
4
1
12
2
140.
0.
80.
1548.
854.
586.
2279.
2709.
4727.
5544.
5824.
6817.
4397.
6410.
6233.
4985.
4577.
3875.
3311.
3110.
3210.
3838.
3776.
2720.
4650.
2050.
4520.
1654.
1886.
570.
7330.
1300.
TERMINATED
NO. MM
0
1
0
0
1
3
5
4
2
0
2
0
1
7
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0.
140.
0.
0.
10.
340.
628.
1014.
215.
0.
143.
0.
20.
825.
100.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.

TOTAL
NO.
1
0
1
11
15
16
20
23
32
47
64
84
94
104
119
128
137
144
150
155
160
167
172
177
184
187
195
198
202
203
215

ON LINE
MW
140.
0.
80.
1628.
2472.
2718.
4369.
6064.
10576.
16120.
21801.
28618.
32995.
38580 .
44713.
49698.
54275.
58150.
61461.
64571.
67781.
71619.
75395.
78115.
82765.
84815.
89335.
90989.
92875.
93445.
100775.

                    12-1

-------
APPENDIX A




DEFINITIONS
    A-:.

-------
                           DEFINITIONS
Boiler Commercial Service Date
Byproduct Nature
Commercial Service Date
   (FGD System)
Company Name
Disposal
Efficiency:
     Total Unit Design Particle
     Removal Efficiency
     Total Unit SC-2 Design
     Removal Efficiency
                               A-2
Date when boiler and auxiliary
equipment (including FGD sys-
tem for new boilers) has met
initial supplier guarantees
and begins to contribute elec-
trical power to the power
grid.

The nature (e.g. elemental
sulfur, sulfuric acid) and
disposition (e.g. stockpile on
site, marketed) of the end
product by systems that gen-
erate a saleable product.
Date when the FGD system suc-
cessfully completes compliance
testing and the utility is
satisfied that the system
meets supplier contractual
guarantees.

Name of corporation as it ap-
pears in Electrical World -
Directory of Electrical Util-
ities, McGraw-Hill - Current
Edition - as space permits.

Disposal method for throwaway
product systems producing
sludge including:  interim and
final disposal sites and
disposal type  (minefill,
landfill, etc.) as well as
disposal location and site
capacity.
The actual percentage of par-
ticulate matter removed by  the
emission control system  (me-
chanical collectors, ESP, or
fabric filter and FGD) from
the untreated flue gas.
The actual percentage  of  S02
removed from  the  flue  gas by
the FGD system.

-------
FGD Viability Indexes
     Availability Index
     Reliability Index
Several parameters have been
developed to quantify the vi-
ability of FGD system technol-
ogy.  Various terms such as
"availability," "reliability,"
"operability," and "utiliza-
tion" are used to accurately
represent the operation of any
FGD system during a given per-
iod.  The above-mentioned pa-
rameters are defined below and
discussed briefly.  The objec-
tives of this discussion are
to make the reader aware that
several different definitions
are being used and to select
appropriate parameters that
can be used for reporting pur-
poses so that reasonably con-
sistent comparisons can be
made.

Hours the FGD system is avail-
able for operation (whether
operated or not)  divided by
hours in period,  expressed as
a percentage.  This parameter
tends to overestimate the vi-
ability of the FGD system be-
cause it does not penalize for
election not to operate the
system when it could have been
operated.  Boiler downtime may
tend to increase the magnitude
of the parameter because FGD
failures generally cannot oc-
cur during such periods.

Hours the FGD system was oper-
ated divided by the hours the
FGD system was called upon to
operate, expressed as a per-
centage.  This parameter has
been developed in order not to
penalize the FGD system for
elected outages, e.g., periods
when the FGD system could have
been run but was not run be-
cause of chemical shortages,
lack of manpower, short dura-
tion boiler operations, etc.
The main problem in using this
                              A-3

-------
     FGD Operability Index
     FGD Utilization Index
End Product
     Sludge
formula is the concise determi-
nation whether or not the sys-
tem was "called upon to oper-
ate" during a given time per-
iod.  In addition, an undefined
value can result when the FGD
system is not called upon to
operate for a given period
(e.g., turbine or boiler out-
age when FGD system is avail-
able) .

Hours the FGD system was oper-
ated divided by boiler operat-
ing hours in period, expressed
as a percentage.  This param-
eter indicates the degree to
which the FGD system is actu-
ally used, relative to boiler
operating time.  The parameter
is penalized when options are
exercised not to use the FGD
system in periods when the
system is operable.  In addi-
tion, an undefined value can
result when neither the boiler
nor the FGD system is operated
for a given period (e.g., tur-
bine or boiler outage when FGD
system is available).

Hours that the FGD system op-
erated divided by total hours
in period.  This parameter is
a relative stress factor for
the FGD system.  It is not a
complete measure of FGD system
viability because the parameter
can be strongly influenced by
conditions that are external
to the FGD system  (e.g., in-
frequent boiler operation will
lower the value of the parame-
ter although the FGD system
may be highly dependable in
its particular application).
The S02 removed  from  the  flue
gas is not recovered  in a us-
able or marketable  form and
resulting sulfur-bearing  waste
                               A-4

-------
     Recoverable Byproduct
Energy Consumption, %
Equivalent Scrubbed Capacity
  (ESC)
FGD Status:
     Category 1
     Category 2
     Category 3
     Cateogry 4
     Category 5
products must be disposed in
an environmentally acceptable
fashion.

The SC-2 removed from the flue
gas is recovered in a usable
or marketable form (e.g., sul-
fur, sulfuric acid, gypsum,
ammonium sulfate, sodium sul-
fate).

The percentage of gross unit
electrical generating capacity
consumed by the FGD system, as
defined by the following equa-
tion:

[Net MW w/o FGD - Net MW w/FGD]/
[Gross unit rating]
The effective scrubbed flue
gas in equivalent MW based on
the percent of flue gas scrubbed
by the FGD system.
Operational - FGD system is in
service removing S02.

Under construction - ground
has been broken for installa-
tion of FGD system, but FGD
system has not become opera-
tional .

Planned, Contract Awarded -
contract has been signed for
purchase of FGD system but
ground has not been broken for
installation.

Planned, Letter of Intent
Signed - letter of intent has
been signed, but legal con-
tract for purchase has not
been awarded.

Planned, Requesting/Evaluating
Bids - bid requests have been
released but no letter of  in-
tent or contract has been  is-
sued.
                               A-5

-------
     Category 6
     Category 7


     Category 8
Fuel Firing Rate - TPH
Initial Start-Up (FGD System)
NA




N/A

NR
New
Plant Name
Process Additives
Considering only FGD Systems -
an FGD system is proposed as a
means to meet an S02 regula-
tion.

Considering an FGD system as
well as alternative methods.

Nonoperational - FGD system
has been operated in the past
but has been shut down perma-
nently or for an extended in-
definite period of time.

Boiler fuel firing rate in
terms of tons per hour at max-
imum continuous load.

Date when flue gas first
passes through any component
of the FGD system (or is
scheduled to do so).

Not available - early status -
information not known at this
time.

Not applicable.

Not reported - the information
is known but for one reason or
another has not been reported
by the utility.

FGD unit and boiler were de-
signed at the same time or
space for addition of an FGD
unit was reserved when boiler
was constructed.

Unit identification as it ap-
pears in Electrical World -
Directory of Electrical Util-
ities, McGraw-Hill - Current
Edition - or as indicated by
utility representative for  in-
stallations in planning stages.

A chemical compound or element
which is added to the process
or normally found with the
main process reagent in small
                               A-6

-------
Process Type
Regulatory Class
Retrofit
S02 Removal Mode
Spare Capacity Index  -  %
quantities (e.g., Mg, adipic
acid) to promote improved
process operation (e.g., scale
reduction, increased S02 re-
moval efficiency).

Company name if process is
patented.  Generic name if
several companies have similar
processes  (e.g., Lime, Lime-
stone, Wellman Lord, Thorough-
bred 121) .

A.   Unit(s) subject to stan-
     dard (s) more stringent
     than  NSPS  (6/79).

B.   Unit(s) subject to Fedei—
     al New Source Performance
     Standards  (NRPS) promul-
     gated in June 1979.

C.   Unit(s) subject to stan-
     dard (s) more stringent
     than  NSPS  (12/71),'but
     not more stringent than
     NSPS  (6/79).

D.   Unit(s) subject to Feder-
     al New Source Performance
     Standards  (NSPS) promul-
     gated in December  1971.

E.   Unit(s) subject to stan-
     dard (s) equal to or  less
     stringent  than NSPP
      (12/71).

FGD  unit will be/was added to
an existing boiler not  specif-
ically designed  to accommodate
FGD  unit.

The  manner in which the SC>2
from the  flue gas is  collected,
e.g., wet  scrubbing,  spray
drying,  dry adsorption.

The  summation of the  individ-
ual  component capacities  (%)
minus 100%.
                                A-7

-------
Spare Component Index
System Supplier
Total Controlled Capacity (TCC)
Unit Rating
     Gross
     Net w/FGD
     Net w/o FGD
The equipment spare capacity
index (%) divided by the indi-
vidual component capacity  (%) .

A firm that fabricates and
supplies flue gas desulfuriza-
tion systems.

The gross rating (MW) of a
unit brought into compliance
with FGD, regardless of the
percent of flue gas treated at
the facility.  In the case of
prototype and demonstration
FGD systems, this figure will
be identical to the Equivalent
Scrubbed Capacity rather than
the gross unit rating if the
system is not meant to bring
the facility into compliance
with S02 emission standards.
Operational - Maximum contin-
uous gross generation capacity
in MW; Preoperational - maxi-
mum continuous design genera-
tion capacity in MW.

Gross unit rating less the
energy required to operate
ancillary station equipment,
inclusive of emission control
systems.

Gross unit rating less the
energy required to operate
ancillary station equipment,
exclusive of emission control
systems.
                               A-3

-------
      APPENDIX B




TABLE OF UNIT NOTATION
           B-l

-------
TABLE OF UNIT NOTATION
Classification
Area

Concentration




Flow


W
1
to
Heat Content

Length


L/G Ratio


Mass/Weight

Pressure
Temperature
Volume

English Unit
Acre
Square foot
Grains per standard
cubic foot
Parts per million
Pounds per million
Btu
Actual cubic feet
per minute
Gallons per minute
Pounds per minute
Ton per day
Ton per hour
Btu per pound

Foot
Inch
Mile
Gallons per
thousand actual
cubic feet
Pound
Ton
Inches of water
Degree Fahrenheit
Cubic feet
Acre-feet
Pymbol
acre
ft?
gr/scf

ppm
lb/10 Btu

ft /m i n
(actual )
gal/min
1 b/mi n
t/day
t/h
Btu/lb

ft
in
mi
gal/1000
ft^
(actual )
Ib
t
in. H20
•F
ft3
Acr
-------
        APPENDIX  C



FGD PROCESS FLOW  DIAGRAMS
           C-l

-------
n
 i
NJ
                                                       "in ntctcit
                                                          HOT T0!«l)
                                                             UNtSTWt 51UHK
                                                                 I mo toi«i)
           \                   /   "*suJ
            » - »B50«B[I WCYClt PUWS - '   ''v™1
IT rwws — '          (siiPKUNii)            „»,„
\
 \
                                                                                                                                    WS TO STUCK

                                                                                                                                    (PCX UKIT ]
                                                                                                                                    ll"tSTO« SIU»«T

                                                                                                                                      10 U«IT 3
                                                                                                                               '010
                                                                     Alabama Electric,

                                                  Simplified  Process Flow  Diagram for Tombigbee  2 and  3

-------
O
                         SINGLE LOUVER
                            DAMPER
                                     DOUBLE LOUVER
                                        DAMPER
                         I.D. FAN
     . TO DISPOSAL POND
    TO PROCESS
    SEAL WATER
   (SERVICE WATER)
                  SLURRY
                 SUMP PIT
SEAL WATER
1 BOOSTER
1  PUMPS
            -— SLURRY
             SUMP PUMPS

            QUENCHER
             PUMPS \
                                        \*~A
                                       ABSORBER
                                         TOWER
                                                                 CYCLONES
                    TIDiUCES
                    nr^'-T-trir
                                                                               STACK
DOUBLE -BLADED
GUILLOTINE
DAMPER
r-


ii *i
YY LIQUID


                                              ABSORBER
                                              FEED TANK
                             '
   TOTAL PROCESS
   HAKE-UP WATER
  (COOLING TOWER
    SLOWDOWN)
-» TO UNIT NO. 3

— FROM UNIT NO. 3
-»• TO UNIT NO. 3
-»• TO UNIT NO. 3
                                                                                                                     MET LIMESTONE
                                                                                                                    GRINDING SYSTEM
                                             -»• TO UNIT NO. 3
                                                                                 ABSORBER REAGENT
                                                                                   FEED PUMPS
                                       Arizona  Electric  Power  Coop, Apache 2  and 3
                                                    Process Flow Diagram

-------
                                                      lOUVCI
n
 i
1—
^






„

STUB
•
/
/
L-^-J



.. I LOUYtK
H
r 	 r^-5U-
a«
IM
                                                                                            PMTICUIMI
                                                                                            KHIUII

DS

|^

1






1
[ iUItU TMK | | UfU




                                                                                                          >-<    HUW1
                                                                                                         HOSUI  CUIUOTM
                                                                                                          ru
                                       Arizona  Public Service,  Cholla  1 :
                                        Simplified  Process  Flow Diagram

-------
 MECNAMICAL
DUST COLLECTOR
II ILOUVEI I ILOUVFI
JJpiwi PDAMMI
n

— •• ».


FLUT CAS
ta


n— '"J
LJ IflOSTf*
IMS
         FLOODED
          DISC
         SCIUME
                    IENEATEI
       rV^=-"
                 <__\ ^
       »«cm*
    TO M«STt
    DISPOSAL
mi
4                                    LIQUID
                                    CTCLONES
NktEUr
                    Do
                     Tl.
                                    ABSOKttS
                                    FEU TAM
                             AiSOKIE"
                             FEED rw
 SCIMI0
 FEED »!»•
                 AISMtEl
                  TOHEI
     LIICSTOMI
     STORA6E
         fEtDO
                                                     o-o
MCRM    'I"""





    ^~4L   TO KHS1
       J^^~" OJS^OSA
                                                           s
                                                           FEED
                                  KT
                                                   REMEKT FEED TAW

ll- 1
MLL HIU
l_

r
"
1| 1
HILL tLM


b1
HILL SLUWT
                          •mi
                     Arizona  Public Service, Choi!a  2:
                      Simplified Process  Flow Diagram
                                      C-5

-------
o
en
                            »ru I '   I   fS
                            '!""'     1/21
                            »«>•, '    '	tV
                                            Central  Illinois  Light,
                                Simplified Process Flow  Diagram of Duck Creek 1
                                    Power Plant and  Emission  Control System

-------
n
 i
            1 BOOSTER FAN
            2 CHLORIDE/FLYASH PRECOOLER
            3 FLYASH THICKENER
            4 ABSORBER
            5 NEUTRALIZE
            6 REACTOR-CLARIFIER
            7 CAUSTICIZERS
            8 THICKENER
            9 HORIZONTAL BELT FILTER
           10 REHEAT FACILITY (EXPERIMENTAL)
STACK
                                             WATER



•
SODA ASH|
(MAKEUP)
SODA ASH


                (MAKEUP)
CaS03/CaS04
SOLIDS


r
v
1 ,
                                           Central  Illinois  Public  Service,  Newton 1:
                                Simplified  Process Flow Diagram  Showing One of  Four  Absorbers

-------
       MKEUP HATER
       (POND MATER)-
                                                                     -»• TO STACK -  FLUE GASES
                                                              y ) ti >i >.
MIST ELIMINATOR
            FROM ESP -
            FLUE GASES
         LINt FROH
         STORAGE
          SERVICE
          HATER
n
 I
00
                                                                                                                              ••TO fUCS
                                 Columbus  and Southern Ohio Electric,  Conesville  5 and
                                   Simplified Process  Flow  Diagram for a Riven Module

-------
                                  To Stack
O
vo
                      From
                   Precipitator
                                                  Mist Eliminator

                                               M.E. Wash       Mal"? Up
               Flyash Silo
                             Lime Silo
                                                                Flyash Wet'G
                                                                    Tank
             Flyash Feeder


                      Make Up
I
--:

-v*i
Lime
^ Bleed Feed Pumps
>-
(

e
(
3
                                                    ] ,_ dtf Li
                                                                                       fH    I
                                                                                       i_  limt
                                   Lim«
                                   Feeder
                            Lime
                            Slaker
Reaction Tank
  In-Tank
  Strainer
                                                                                    Lime
                                                                                 Feed Tank
To Disposal
                                  Cooperative  Power Association, Coal Creek  1 and  2:
                                            Simplified  Process  Flow Diagram

-------
o
i
                      Flue  gas
                     from boilers
        Makeup from
          overflow
           pumps   ~

          Bleed 10
         thickener  -^
        and clorifier
To thickener trough
                                           Adjustable
                                             throat
                                             dampers

                                                Damper
                                               operator
                                                housing
                                                 Sproy
                                                 water  qas
                                             Mist eliminator
                                                                                                   Combustion
                                                                                                   air
                                                  To thickener
                                                              Lime slurry feed line
                             Service water
I » 	
IT""*.

Q. . -+ 	
(o
1
H«k

 Lime
storage
  silo
                                                                                     Vibrator
                                                                                     weigh
                                                                                     feeder
                                                                                       I
                                                                                       t
                                                                                                              I
                                                                                                              T
 Lime
slurry
 lank
                                                          Lime stoker
                                                                                                 Lime slurry
                                                                                                   pump
                              Duquesne  Light, Elrama  1-4:   Simplified Process  Flow Diagram

-------
o
 I
                                               1ST STAGE
                                               ADJUSTABLE VENTURI
                                               FOR FLY ASII/SO,
                                                                 2ND  STAGE
                                                                     ABSORBER SCRUBBER

                                                                   X
                            RECYCLE RETURN SYSTEM
                 CaS03/S04
                 FLY ASH SLURRY
RETURN_TO_P_OND
       Lr_=|.
       'THICKENE
                             ASH POND

                             TO
                       STABILIZATION
                         FACILITIES
                                      Duquesne Light, F. R. Phillips FGD System:
                                                   General Diagram.

-------
                                  FROM DISPOSAL POND
           FLUE GAS
          FROM PLANT


         ISOLATION
         0/WPER
O
 I
                                                               REHEATER
                                                              NO. ? FUEL OIL
              SURGE
              TANK
              (EXISTING
              V-103 I Y-103
              EPRI SYST.
                    FLANGED
                  CONNECTION TO
                  CLIENT'S DUCT
     THICKENER
     HOLD PUMP
  I  I
  I  I
•*-  i    THICKENER
    T--,HOLD TANK
                                                 - SODA ASH
                                                    VIBRATING
                                                    HOPPER
                                            O  SODA ASH
                                            r1 ' - 1 HEIGH
                                            — .    FEEDER
             REACTOR NO.  I
             AND AGITATOR  REACTOR NO. ?
                        AND AGITATOR REACTOR NO. 3
                                   AND AGITATOR
                                                                                                                                          FILTER CAKE
                                                                                                                                          WASH MATER
           ADDITIONAL S0? INJECTION
                                     SODA ASH
                                     TANK 1
                                     AGITATOR
                                                                                                               REACTOR NO. 4
                                                                                                               AND AGITATOR
                                                                                                                         REACTOR NO. 5
                                                                                                                         AND AGITATOR
                                                               Gulf Power,  Scholz  1:
                                         Simplified Process  Flow Diagram  of  the Demonstration
                                                   Soda  Ash/Limestone Dual  Alkali  Process

-------
                        AIR
                       HEATER
        AMBIENT
          AIR   FAN


           MIST
        ELIMINATOR
    MOBILE  PACKING
PRE-SATURATION SPRAY

           FLUE GAS IN
       Tn c;TnRAr,F ARFA
                                           CLEAN  GAS  OUT TO  STACK
MIST ELIMINATOR
     WASH
                                   WASTE
                                SLURRY TANK
                                                 PUMP
             Indianapolis Power and Light, Petersburg 3:
      Simplified Process Flow Diagram for One of Four Absorbers
                                C-13

-------
                                                     STACK
                                                                      D. FAN
              COAL
              SUPPLY
o
i
                                                                                STACK  GAS
                                                                                REHEATER
                                                    AIR HEATER
                                                       .DEMISTER
                                                     STACK GAS
                                                     SCRUBBER
           PULVERIZER
        LIME
        PREPARATION
        TANK
      CLARIFIER
                                                            RECYCLE
                                                            PUMP

                              Kansas City Power and Light, Hawthorn Units 3 and 4:
                         Simplified Process Flow Diagram of the Lime Scrubbing  Process
     MAKE UP
     WATER

TO ASH DISPOSAL
POND

-------
o
 i
M
Ul
                                                                                           ABSORBER
                                                                                          REJCIRCULATION
                                                                                            PUMPS
                                                                                    VENTURI
                                                                                  RECIRCULATION
                                                                                  PUMPS
                                                         LIMESTONE
                                                          SLURRY
                                                          STORAGE'
                    160 ACRE
                  SETTLING POND
                      BOILER
WET BALL
  MILL
                                              Kansas City  Power  and Light,
                                        LaCygne  1  FGD System:   General  Diagram

-------
                                  FURNACE
                                                              DAMPERS
            TWO PRECIPITATORS
o
. i
H
cn
FOUR I.D.  FANS
                                                                            ONE
                                                                           STACK
                                                       WATER RETURN TO
                                                       REACTION TANKS
                                                                          BLEED PUMP
                                             FOUR
                                           REACTION
                                             TANKS
                                                       SLUDGE DISPOSAL
                                                            POND
                                            Kansas Power and Light,
                      Schematic of Jeffrey Steam Generator and Emission Control Equipment

-------
LIMESTONE
•mnnra







CRUSHED
LIMESTONE
BUCKET
[LEVATOR
wrriH

x/









— v
FEEDER \
MAUN (OR
SLURR»ING
1 SCALPING
f^P SCREEN
V
^ADDITUE
TRANSFER
PUMPS



1 BALI L
| Mill ft





MIIER
n /*
1 J/'
c*o







DOITUE SIOMU
INK U SOLIDS
^T[
~~"ADOHIM LJ
                                                OIIUIION UAIIR
                                                (FIOM RECIRCUIMION !•««)

                 SUMP
                     SlURRf PUMPS
STORAGE
PUMPS
  10 OTHER
SCRURICR WOU.I
o

M
-O
                                                                         STACK I POND RETURN
                                                                                (MAKE-UP)
                                                                              I   WATER
                                                                        I    '   T THICKENER |~0\
                                                                        l-^U^i — I
                                                                                                                                               WEIR
                                                                                                                                             OVERFLOW
                                                                                                                                   \^P - »• SETTLING

                                                                                                                                  THINNER    PONO
                                                                                                                               UNDERFLOW PUMPS
                                                                 Kansas Power  and  Light,
                                                           Lawrence 4  Operational  FGD  System:
                                                            Simplified Process Flow Diagram

-------
      LlKSTMt «Tt«
                                          DIIUTIW tt»UI> (HI
                                   STOMGC   KCIHClMtlOl" TUi
                               T»H> (0 SOLIDS
o
 I
I-1
oo
WOITHI
DILUTION
EC. IH.
i ADOIT(JI[
~5*
SCBUBBFC
MODULI
r~ — ~~ 	
T
F
*
ADDITIVE
(FROM HILL)
/
L
0 STACK /
B
LUE GAS t
UR PREHE)


tDOITIVE
FEED
PUMPS(2)
ONE OF TUO NODULES

OUTLET
1.0. FANS (2) J~
. ' L.
rPASS ^ ^

RON
UER
^
t
1
.IN.
'^X
INLET \
DAMPER \
w
	 «
ll
MAKEUP I-.
"" Ji
ROO SCRUBBER [!<•
SPRAY PUMP ,| |
' 	 is


DAMPER
— A J pREHEATER
KN
B-E-S- .,3^ 	 NIST ELIMINATOR
r inn 	 BLOWFR
ABSORBER STRAINER HASHER
/(TYP.)
STRAINER HASH
f LINE (TYP 1 - - „ _
' J n 1
fll 1? I *BSORBE*
It III SPWT Pl**
*» JL;J
lEACTION !.
TANK ll —0
TRAINERS:
u
1 ADDITIVE QCW«INUTO«
STORAGE TANK 1
EFFIUFMTQ
BLEED H
"» J__TOPO«
                                                         Kansas  Power and Light,
                                                   Lawrence 5  Operational FGD  System:
                                                    Simplified  Process  Flow Diagram

-------
o
 I
I-1
vo
                                                                                                 ELECTRICAL

                                                                                                 GENERATING

                                                                                                 UNIT NO. 2
ELECTRICAL

GENERATING

UNIT NO. 1
                                                                                                           MAKEUP HATER




                                                                                                             MAKEUP MATER
                                                                         SPARE
                                                       Kentucky  Utilities,

                                     Green River FGD System:   General Process Diagram

-------
                                                                       QUENCHER
                                                                                   MIST
                                                                                 ELIMINATOR
                                                                                 (CHEVRON)

                                                                                 CONTACTOR
                                                                                 SCRUBBER
                                                                                 ~- MODULE
                           ELECTROSTATIC
                           PRECIPITATOR
            REACTION
             TANK
                 BOILER
                  FLUE
                  GAS
O
 I
N)
O
CONTACTOR
 SCRUBBER
  MODULE
                                                                                                         MIST
                                                                                                       ELIMINATOR
                                                                                                        (CHEVRON)
                                         Louisville Gas and  Electric,  Cane  Run 4
                                       FGO System:   Simplified  Process Flow Diagram

-------
o

to
H
                                   IN LINE REHEATER (STEAM)
              I.D. BOOSTER FANS
                TO STACK
                             BYPASS
ESP'S
                                                   HIST ELIMINATOR



                                                     P MIST ELIMINATOR WASH
                                                   —	—	
                                                    -BULK ENTRAPMENT

                                                        SEPARATOR


                                                   *-SPRAY  TOWER ABSORBERS
                                                      CRUSHER-
                                                    DISINTEGRATOR!
                        SPRAY PUMPS
                OK
                         IN-TANK STRAINER
oUil


-------
                                                 COMBUSTION AIR
EXISTING
  FAN T, I
                     Louisville Gas  and Electric,  Cane Run 6
           Dual  Alkali FGD System:   Simplified  Process Flow Diagram
                                       C-22

-------
IN LINE REHEATER (STEAM)






l.D. BOOSTER FANSi
TO STACK-- 	 1

.
n

w ESP'S
-i


^
fU

BYPASS


I

"-^


i







1



\ •- \

SPRAY PUMPS





~>
~\
<.J




i




3










6
\—

n
•?




m m « jr





**•.
t

-i
IN-TANK STRAINER




• - - -


5 — y^

ii
.'MIST ELIMINATOR
9 MIST ELIMINATOR WASH
tJo '






*^-BULK ENTRA1NMENT
SEPARATOR CRUSHER- (->
FROM LIME
STORAGE TANK

*• SPRAY TOWER ABSORBERS n 1






a

3C3

A



_&
r












LIME O
FEED PUMPS





c:








^







9EFFLUENT BLEED
J REACTION TANK




LIME FEEDTANK






OVERFLOW
1
THICKNER |
— -~_^_ ^ 	 ' orryri i

\JT

MAK
WA
0-








EUP
fER

•
\L^
"fc^* ***•*• HI- rTi
DUMPC "tL'V











M.E.WASH
Lt PUMP
O. •-"' TANK
rn niconcoi- 	 DUNDERFLOW PUMPS
           Louisville Gas and  Electric,
          Mill Creek 1 and 2 FGD System:
          Simplified Process Flow Diagram

-------
                                                                      GAS 10 STACK
o
                       GAS REHEATERS
                    HIST ELIMINATOR



                         WASHERS
                                                                                                                      Ml CA(OM)2

                                                                                                                     ADDITIVE SYSTEM
                GAS INLET
                                                     Louisville  Gas  and  Electric,
                                                       Paddys  Run 6  FGD  System:
                                                    Simplified Process Flow Diagram

-------
TREATED-GAS
    DUCT
SPRAY TOWER
 ABSORBER
                                                              "WET"  VENTURI
                                                                 SCRUBBER
              Minnesota  Power and Light, Clay Boswell 4:
                           General Diagram
                                  C-25

-------
                                       RCMCAT BY-MSS
                          •OOSTM

                           FAN
n
i
to
                                                         CAKC
                                  Minnkota Power  Cooperative, Milton R. Young  2:

                             Simplified Process Flow  Diagram for One of Two Absorbers

-------
o
                 S02 BOOSTER FANS
                 FLUE GAS)
                LIME  FEED
                 SYSTEM
     MIST
  ELIMINATORS
uuumit
IOCLONE

I
—


U
c

' «i

D

yL

                                       RECYCLE TANK
       TO STACK
                                                            WASH TRAY


                                                            -ABSORBER TRAY
RECYCLE
LIQUOR
              *- TO  EMERGENCY
                   DUMP POND
                                                                                   TO DISPOSAL SITE
                                      Monongahela  Power,  Pleasants 1 and 2:
                     Simplified Process Flow Diagram for  One of  Four Modules for Either Unit

-------
n
i
to
CO
        FLUE
         GAS
                               EMERGENCY WATER
            PLENUM




               BLEED
MIST

ELIMINATORS
                                                               STEAM
                                                             5	»-CLEAN FLUE GAS	fc~ >
    CXh-SEAL WATER SUPPLY

JJNDERSPRAY   ^    MAKEUP
                  WATER
                                       FLY ASH POND
                                   Montana Power, Col strip 1 and 2:
                                 Process diagram of a given FGD module.
                                                                                 WASH TRAY POND
                                                                                                     POND
                                                                                                    [RETURN

-------
                                                           TO CHIMffT
O
 I
NJ
                                  MECHANICAL
                                    OUST
                                  COLLECTOR
                                 (NUITICLONES)
                                     Nevada Power, Reid  Gardner  1,2 and  3:
                                     Process diagram of  a given  FGD system.

-------
                                            DISCHARGE
                                            TO STACK
                                               4
                                              I  I TRAY TOWER
                                              I  I ABSORBER
                                                                           CONDENSER
                            PRESCRUBBER

                          (VARIABLE-THROAT
                                 VENTURI)
O

L-J
O
FLUE GAS FROM
    UNIT #11
      FLY ASH PURGE TO POND-*
                                              TREATED
                                           PURGE STREAM
                                                                                              EVAPORATOR/

                                                                                              SCRYSTALLIZER
                                                                              REDUCTION  ~n

                                                                                PLANT~-®coSmssoR
                                                                          CRYSTALLIZER
                                          DRIED
                                         SULFATE
                                         PRODUCT
                                          Northern Indiana Public Service,
                                       D.  H.  Mitchell  11 WeiIman Lord/Allied System:
                                               General Process Diagram.

-------
o


U)
-•:




*J







-
=•


IKWIAI
inn* ••
'•'• it » i .
l**v>J


                                                                                         i emu  \ /\ /\ /

                                                                                         •«.»! 'if V/  \/  \/
                                                                                            .«unJ  H  He
                                                                                              IWKWSf
                                                                                                       COLLKTIK

                                                                                                       comtio
                                                                  Simplified Process Flow Diagram
             Spray Dryer Cutaway  View



                   Northern States  Power, Riverside  6,7:   FGD System  Flow Diagrams

-------
o
 I
OJ
                    FLUE GAS
                      TO
                    SCRUBBER
                                      REHEATER
LIMESTONE —i
                                        MIST
                                     ELIMINATOR
                                    OVERFLOW POTS
                                   AND MARBLE BED
                                                               THICKENER
                                                               UNDERFLOW
                                                                PUMP
                                                                                                           ASH POND
                                                                                                          RETURN PUMP
                               Northern  States  Power,  Sherburne 1  and 2 FGD System:
                                            Simplified  Process  Flow  Diagram

-------
o
I
u>
to
                                 \ 1*11 1101 IMtl t»QI«

                               jiL
                                 sin iftintDiM. i
                             ~   0"
                             « - 	J

                             i««mt
                            r*-«Ki i«*»w«




                            •-"—- r"i5* ~~^^j^ ^ £""5?^_rr^_
                            ._..._ 	 I	 HKII-OISWUl SII1lllll« ««t«««_M»l Ij^J-1          Km If CWITO •'•• I     ~V««
-------
     FLUE GAS FROM
       UPPER ESP
o
i
U)
                                                                           HOT REHEAT GAS
                                    EXHAUST  PLENUM
                                    EXHAUST
                                    ISOLATION
                                    DAMPERS
                                  (4 PER UNIT)
X
     FLUE GAS FROM
       LOWER ESP
    \
      STACK  INLET
      DAMPERS  (2)
      (1  EACH SIDE)
                             STACK
                     ABSORBERS
                    (4 PER UNIT)
       INLET
      PLENUM

           INLET ISOLATION
        DAMPERS (4 PER UNIT)
              BOOSTER FAN FLOW
              CONTROL DAMPERS
                (4 PER UNIT)
                                                                VENTURIS
                                                                (4 PER UNIT)
BOOSTER FANS
(4 PER UNIT)
                             Public Service of New Mexico, San Juan 1, 2, 3, and 4
                                         FGD System Flue Gas Flow Path

-------
                            FLUE
          SCRUBBER-
           OUTLET
          DUCTWORK
            HIST
         ELIMINATOR
              REACTION
              MIX TANK
         FLUE GAS FROM
        .ELECTROSTATIC
       f PRECIPITATORS
           INDUCED-
          DRAFT FANS
        BOOSTER FANS

PRESATURATOR
O

ui
ui
                                                                                    FROM FANS
                                                                                                                  TO STACK
                                                                                                                     »
                                                                                                                   FROM ABSORBER B
                                                              TO SEAL-WATER SYSTEM

                                                              TO FLUSH CONNECTIONS
                                                      TO ALKALI-PREPARATION SYSTEM
 ABSORBER -A
      OSTER
      FAN


ABSORBER-B
BOOSTER FAN
                                                                               LIMESTONE-SLURRY
                                                                                    MAKEUP

                                                                                    FROM ABSORBER B
                                                                                                                     FLOCCULENT
                                                                                                                      ADDITION
                                                                                         TO
                                                                                         ABSORBER B
                                                                               TO SLUDGE
                                                                             STORAGE  TANKS
                              Salt River Project, Coronado  1  and  2 FGD System:
                                       Simplified  Process  Flow  Diagram

-------
o

U)
en
Lll
«ESTONE
SILO
Y

i
\
C FECDC* J


1
•^>


CLASSIFIER
LJ
MILL -i
y PUMP
SI
1
I
d:
• jvmi- i^
f
O

SL
reeo
.URRY STORAGE fc/~
                TANK
                      FRESH
                      MAKEUP
                      WATER
      RECYCLE
      WATER
      TANK
                                                                                                        ESP
                         RECYCLE WATER
                             PUMP
OUCNCMCM
  PUMP
                                                         ABSORBER    QUENCHER
                                                           TANK         TANK
                     TO POND
               South Carolina  Public Service Authority,  Winyah 2:  Simplified Process Flow  Diagram

-------
                                       EXISTING
O
 I
OJ
                                                                                                                        VEHTURI SORBER
                                                                                                                          SCRUBBERTN
                                                                                                                         (ONE IN USE)
                                                                                      MAKEUP HATER
  LIMESTONE
  FEED BIN
(ONE  IN USE
  FOR TWO
                                                                      HIST ELIMINATOR
                                                                        I  PUMP   I
                                                                       (ONE IN USEP-v
                                                                        ONE SPARE)V?
                                                                         MIST
                                                                        L1MINATOR
                                                                        TANK (ONE
                                                                         IN USE)
                                                         I  I
                                                         ELII

                                                        B
MET BALL MILL
 (ONE IN USE)
           MILL SLURRY
              TANK
                                                                                                                                             FROM THICKENER
                                                                                                                                                 TO THICKENER^
                                                                                                                                  Tutr>vmFBi    ^E&'
SLURRY STORAGE
    TANK
                                                            SLURRY
                            IAI1K   Ifmf tM IKF  lrlnlN            PIMP
                        (ONE IN USE) {™[ JJaJI) (ONE IN USE) (0||E ^ USE

                                                          ONE SPARE)
                                                                                                       RECYCLE TANK
                                                                                                       (ONE IN USE)
  RECYCLE
   PUMP
(TWO  IN USE
 ONE  SPARE)
                                                                                                                  THICKENER
                                                                                                                   SUPPLY
                                                                                                                    TANK
                                                                                                                 (ONE IN USE)
                                                                                                                      PUMP
                                                                                                                  [(ONE IN USE
                                                                                                                   ONE SPARE)
                                                  South Mississippi  Electric,  R.D.  Morrow  1  and  2:
                                                        Simplified  Process  Flow  Diagram

-------
                                                       LIMESTONE SLURRY
                                                       STORAGE TANK
o
 I
CO
oo
                                                                      TO OTHER ABSORBER
                                                       LIMESTONE
                                                       TRANSFER
                                                       PUMP
                CYCLONE  l~p*1
                SEPARATOR X/
                                                 MILL PRODUCT PUMP
QUENCHER
REdRCULATING
PUMP
ABSORBER
RECIRC.
PUMP
                        MILL PRODUCT TANK


                                      MAKEUP WATER
                                                                                ^-RECIRCULATING TANK
                                                                                             • DEMISTER
                                                                                             | WASH

                                                                                              -€?
                                                                                            BOTTOM ASH
                                                                                            DE WATERING
                                                                                            BIN
         ',  ••*«*«. »i*l fry**!*****.
         ? /o            PS
               ASH CONVEYOR

               PLUG MILL
                                        SLUDGE
                                    TRANSFER PUMP
                                                                                      SLUDGE CONVEYORS
                      Southern Illinois Power Coop,  Marion  4:  Simplified  Process  Flow  Diagram

-------
n
U)
vo
                     FROM
                      ESP
STACK
 VcO/
BOOSTER
  FAN
                             A
SODA ASH
 STORAGE
                                       LIME
                                      STORAGE
                       USE  ySLAKER Ca(OH)2


                            WATER


                                       THICKENER
   SULFUR DIOXIDE ABSORPTION
'Na2S03 + s°2  +  H2°	"•
       SURGE
=r=*JJ TANK
                                                           vCaS03/CaS04
       2 NaHS0
                                                                                           FILTER
                                                                  SODIUM REGENERATION       CAKE

                                                     Ca(OH)2 - + CaS03 '  1/2 H20 * Na2S03 + 1-1/2 H20
                                Southern  Indiana  Gas  and  Electric, A.B. Brown  1:
                             Dual  Alkali  FGD  System Simplified  Process  Flow Diagram

-------
                                  SCRUBBER  INLET
                                TEST PORT LOCATION
               PREC1PITATOR
                INLET TEST
              PORT LOCATION
n
 I
                                                                                TOP OF STACK
                                                                               ELEVATION 1645'

                                                                                  TEST PORT
                                                                               ELEVATION 1516'
  "B" ABSORBER
     MODULE
                                                                              U-TOP OF OUTLET BREECHING
                                                                                 ELEVATION 1372'-2 3/8"
                                                                                TOP OF BYPASS BREECHING
                                                                                ELEVATION 1307'- 8 1/Z"
BYPASS DUCT  V
                                                                               -GRADE ELEVATION IMP
       A" ABSORBER
         MODULE
                                      SCRUBBER INLET
                                    TEST PORT LOCATION
                                             Springfield  City Utilities,  Southwest  1:
                                                          Simplified  Process  Diagram

-------
o
                                  Springfield Water, Light ft Power,  Dallman  3
                                             Process Flow Diagram

-------
                                        H2S GENERATION
                                           METHANE/
                                        CARBON MONOXIDE
       BOILER
                                                            PREHEATER
     LIME
  NEUTRALIZER
                            CRYSTALLIZER
              SULFUR
              SLURRY   SULFUR
        SULFUR        PRODUCT
       FLOTATION
PRECONDITIONING AND
  S02 ABSORPTION
SULFUR  PRECIPITATION
    AND RECOVERY
                 St. Joe Zinc,  G.F. Weaton 1:
     Citrate  FGD System Simplified Process Flow  Diagram
                                C-42

-------
n
*»
u>
              I   AIR   >---.

              JFUEL  OIL>—»| REHEATER|—
                                                           f
                                       
-------
                                FLUE GAS
      MAKE-UP WATER
o
i
                       SPRAY TOWER EFFLUENT
                             HOLD TANK
                                                                         VENT  AIR
                                                                          A
                                                             OXIDATION
                                                              TANK
                                                                      u
                                                                                  CLARIFIED  LIQUOR
                                                                                       WATER
                                                                                             D
^>
^
tl .*
1
T_
MM—



	 	

1
<-
->

L^_, t ^
	 i
DESUPERSATURATION
TANK
   BLEED  TO
 DEWATERING
-^   SYSTEM
                           Tennessee Valley Authority,  Shawnee  10B Prototype Test Unit:
                         Modified Venturi/Spray Tower System for  2-Stage  Oxidation Testing.

-------
o
I
                 1    AIR
                  FUEL OIL >-*•[ REHEATER }
                                                                          PROCESS
                                                                           WATER
                                                                         HOLD TANK
                              SCRUBBER
                              EFFLUENT
                               HOLD
                               TANK
       I  LIME  >—
         SAMPLE POINTS
         OGAS COMPOSITION
         &PARTICULATE COMPOSITION & LOADING
         ©SLURRY OR SOLIDS COMPOSITION
GAS STREAM
LIQUOR STREAM
                                          SETTLING POND
                            Tennessee Valley Authority, Shawnee 10B  Prototype  Unit:
                                             General Process Diagram.

-------
n
 i
                      ASH
                                              REHEATER

                                             STEAM
                                           ENTRAPMENT
                                            SEPARATOR
                   DISPOSAL  POND
                   TO STACK PLENUM
                O        «-
                  FROM ESP
cz
                     FAN



^ FROM B. C, AND D TRAIN
"VENTURI CIRCULATION TANK^J_
                   TO SETTLING POND _
                 	O-l

\t
^

4 r

|
*
t
«
\
N
•
^
\

TO
B,C
TRAINS
, AND [
ABSORBER
fl
TO 1
o r


SLURRY PUMP
SEAL WATER
. HEADER
t-~\ a
FRAINS
Ann n


ft
— f^RIVER
WATER
~^* PUMPS
FROM POND
WATER ,
                                                                                       RECYCLE  PUMPS


                                                                                 FROM LIMESTONE SLURRY
                                                     VENTURI
                                                   CIRCULATION
                                                    TANK AND
                                                      PUMPS
                                                     ABSORBER
                                                   CIRCULATION
                                                     TANK AND
                                                      PUMPS
TO TRAINS,
B.C. AND  Dl
                                                                                 LIMESTONE SLURRY
                                                                                   STORAGE TANK
                                  EFFLUENT SLURRY
                               SURGE TANK AND PUMPS
                                                                     LIMESTONE SLURRY
                                                                       FEED PUMPS
                               Tennessee Valley Authority, Widows Creek 8  FGD System:
                             Process  Flow  Diagram for One of  the Four Scrubber Trains

-------
                                            FAN OUTLfT DAMPER
                                                                   TnWFR INLET OAMPFR
                                                                              TOHE» OUTLET
                                                                              I  DAMPER
                          FROM BOILER
                         AIR PREHEATERS

—
LOCAT
TUT
REHE
a
»

»
a
ON
JRE
«TE

—
OF
R
a
•

t
T
FO

—
R FUTUV
TOWERS
                                                                                                   -&-
TO OTHER)
MODULES j

      1-&-
                                                                                                A
                                                                                                   r&~
o
 I
                                                                                                      CONTINUOUS
                                                                                                    RECIRCULATIOII


                                                                                                   ^-^
                               HET CYCLONES
                                                                                                          . PUMP SEAL HATER.
                                                                                                           BALL MILL COOLING
                                                                                                           AND HOSE STATIONS
                                                                                                 MAKEUP HATER TO
                                                                                                  LIMESTONE AREA
                                                               SERVICE MATER     ASH POND
                                                               (LAKE HATER)    RETURN HATER
                                                                          (RECYCLE HATER)
              y^U
                                                                 Texas  Utilities,
                                  Simplified  Process Flow Diagram  for One  of  the Three  Identical
                                                           Martin  Lake FGD  Systems

-------
n
 i
ib
00
                                                                       BYPASS

                                                                       TO SPRAY TOWER 301





                                                                       TO SPRAY TOWER 201
                                                                                          BYPASS

                                                                             FROM SPRAY TOWER 301
                 FROM
           LIMESTONE  STORAGE
             o_
                      _D
                                       TO SPRAY TOWER 301

                                       TO SPRAY TOWER 201
           TO SPRAY TOWER 301
           TO SPRAY TOWER 201

           TP SPRAY TOWER 301
           TO SPRAY TOWER 201  -*
(V
                               LIMESTONE
                                STORAGE
                                  BIN
  Sc/
              TO SPRAY  TOWER 301

              TO SPRAY  TOWER
r                                   LIMESTONE GRINDING
                                	SYSTEM
                                         LIMESTONE SLURRY
                                          TANK AGITATOR
                                                                                                       TOTAL PUMP SEALS AMD
                                                                                                       INSTRUMENT PURGE WATER
                                                                                                                                                  TO ASH AREA
                                                 -SERVICE  WATER
FROM ASH WATER
RETENTION POND
                                                                            SO, REMOVAL AREA
                                                                           -   SUMP PUMPS
                                                        LIMESTONE
                                                          SLURRY
                                                           TANK
                                                           S02 REMOVAL AREA SUMP
                                                                      Texas Utilities,
                                              Simplified Process  Flow  Diagram for  Monticello 3

-------
                                    REHEATERFAfL
n
4*
vo
                         FROM
                     ELECTROSTATIC
                     PRECIP1TATORS
                                                                          WATER
                                                                              FROM OTHER
                                                                              ABSORBERS
TO OTHER
ABSORBERS
  t  t  t
                VIBRATING-rf^=^f
                 HOPPER
       Utah Power & Light,  FGD System Simplified Process  Flow Diagram for  Hunter  1, 2 or Huntington 1

-------
                                                 UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 198*
                                          APPENDIX D
                 DESIGN AND PERFORMANCE DATA FOR OPERATIONAL PARTICLE SCRUBBERS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MM
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY M/FGD - MM
NET UNIT GENERATING CAPACITY WO/FGD - MM
EQUIVALENT SCRUBBED CAPACITY - MW
COMMONWEALTH
WILL COUNTY
1
ROMEOVILLE
ILLINOIS
E
86.
77*.
******
11*7
167
137
1**
167
EDISON





( .200 LB/MMBTU)
( 1.800 LB/MMBTU)
(****«* LB/MMBTU)





 ** UNIT DATA  - BOILER  AND  STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW  -  CU.M/S
     BOILER FLUE  GAS TEMPERATURE  -  C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RAN3E HEAT CONTENT - BTU/LB
     AVERAGE ASH  CONTENT -  7.
     RANGE ASH CONTENT  - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RAN3E MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** FABRIC FILTER
     NUMBER
     TYPE

 ** ESP
     NUMBER
     TYPE
     SUPPLIER
     INLET FLUE GAS TEMPERATURE - C
     PARTICLE  REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     NUMBER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC  TYPE
     TRADE NAME/COMMON  NAME
     SUPPLIER
     DIMENSIONS  - FT
     SHELL GENERIC  MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC  MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE  TYPE
BABCOCK » NILCOX
CYCLONE
CYCLING
363.36 (
179.* (
107. (
NR
3.8 (



770000 ACFM)
355 F)
350 FT)

12.* FT)
COAL
******
22260.         (   9570 BTU/LB)
                9100-10500
    7.*0
3.0-16.0
********
******
    1.50
0.3-4.5
********
******
 0
NONE
 0
NONE
COLD SIDE
WESTERN PREC. DIVISION, JOY
  179.*        (  355 F)
   90.0
 2
 */72
VENTURI TOWER
VARIABLE-THROAT/SIDE-MOVABLE BLADES
N/A
BABCOCK & WILCOX
8.0 X 26.0 X 16.0
CARBON STEEL
AISI 1110
ORGANIC; INORGANIC
INERT FLAKE-FILLED VINYL ESTER; HYDRAULICALLY-BO
NONE
                                             D-l

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON: WILL COUNTY 1 (CONT.)

     LIQUID RECIRCULATION RATE - LITER/S          365.4
     L/G RATIO - LITER/CU.M                         2.4
     PH CONTROL ADDITIVE                        LIMESTONE
     PRESSURE DROP - KPA                            2.2
     SUPERFICIAL GAS VELOCITY - M/S                36.6
     INLET GAS FLOW RATE - CU.M/S                 181.7
     INLET GAS TEMPERATURE - C                    179.4
     PARTICLE REMOVAL EFFICIENCY - X               98.0
     ENERGY CONSUMPTION - X                         4.2
                                                        ( 5800 GPM)
                                                        (18.0 6AL/1000ACF)

                                                        ( 9.0 IN-H20)
                                                        (   120.0  FT/S)
                                                        ( 385000  ACFM)
                                                        (   355 F)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR
 2/72  SYSTEM
                                                                             696
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         IN FEBRUARY 1972 THE BABCOCK * WILCOX WET LIMESTONE FGD SYSTEM AT WILL
                         COUNTY COMMENCED OPERATION.  THE LONGEST PERIOD OF CONTINUOUS OPERATION
                         WAS 23 DAYS WITH ONE OF THE TWO MODULES.  THE S02 REMOVAL EFFICIENCY WAS
                         ABOUT 85X AND THE PARTICULATE MATTER REMOVAL EFFICIENCY WAS ABOUT 98X.
                         THE SYSTEM WAS PLAGUED WITH MANY MECHANICAL PROBLEMS.  THE MAIN
                         PROBLEMS ASSOCIATED WITH THE FGD SYSTEM WERE PLUGGING OF THE MIST
                         ELIMINATORS, CORROSION OF THE REHEATER TUBES AND SLUDGE DISPOSAL.  TO
                         SOLVE THE MIST ELIMINATOR AND REHEATER PROBLEMS, A CONSTANT UNDERSPRAY AND
                         INTERMITTENT OVERSPRAY WERE USED TO WASH ALL THE MIST ELIMINATOR COMPART-
                         MENTS.  THE REHEATER UNIT WAS ALSO RETUBED.
                         DURING THE FIRST TWO MONTHS OF 1975 MODULE A WAS OPERATIONAL WHEN NEEDED
                         WHILE MODULE B WAS UNDERGOING MODIFICATIONS.
  3/72
       A
       B
       SYSTEM
                          .0
                        35.0
                                                                             744
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         IN MARCH 1972 MODULE A WAS DOWN FOR REPAIRS AND MODIFICATION OF THE MIST
                         ELIMINATOR WASH PIPING ASSEMBLY.  MODULE B WAS REMOVED EVERY TWO OR THREE
                         DAYS TO HAND WASH THE MIST ELIMINATOR.

                         OTHER PROBLEMS ENCOUNTERED DURING THE MONTH INCLUDED VIBRATION OF THE
                         REHEATER TUBE BUNDLES, RAPID EROSION OF THE SCRUBBER SPRAY NOZZLES, AND
                         PLUGGING OF THE VENTURI NOZZLES.
  4/72
        A
        B
        SYSTEM
                        34.0
                        14.0
                                                                             720
        **  PROBLEMS/SOLUTIONS/COMMENTS
                         MODULE A WAS OUT OF SERVICE FOR SIX DAYS IN APRIL BECAUSE OF A NEAR-
                         RUPTURE OF A VENTURI PIPE EXPANSION JOINT AND HEAVY BUILDUP OF SOLIDS
                         ON THE MIST ELIMINATOR.

                         MODULE B WAS OUT OF SERVICE MOST OF THE TIME FOR SIMILAR REPAIR OF THE
                         VENTURI PIPE EXPANSION JOINT, AND FOR MODIFICATION OF THE REHEATER UNIT
                         AND MIST ELIMINATOR WASH SYSTEM.
  5/72
A
B
SYSTEM
70.0
32.0
                                                                             744
        **  PROBLEMS/SOLUTIONS/COMMENTS
                          MODULE B WAS OUT OF SERVICE FOR TWO WEEKS IN MAY TO REBRACE THE REHEAT,
                          INSTALL UNDERSPRAY NOZZLES ON THE MIST ELIMINATOR, AND TO INSTALL  HEAVIER
                          SCREENS IN THE SUMP.
                                             D-2

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON: MILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR

                         REHEATER PLUGGING DURING THE MONTH CAUSED ADDITIONAL OUTAGES.

 6/72  A                        8.0
       B                       31.0
       SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING JUNE BOTH MODULES WERE OUT OF SERVICE PART OF THE MONTH DUE TO
                         A HIGH DIFFERENTIAL PRESSURE ACROSS THE MIST ELIMINATORS AND PLUGGING
                         OF THE MIST ELIMINATORS DUE TO A LEAKING BYPASS VALVE.

                         THE RUBBER LINER IN MODULE A WAS REPLACED DURING THE MONTH.

 7/72  SYSTEM

 8/72  A                       79.0
       B                       21.0
       SYSTEM

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         A TWO DAY OUTAGE DURING AUGUST WAS NECESSARY TO UNPLUG THE VENTURI NOZZLES
                         AND THE MIST ELIMINATOR OF MODULE A.

                         MODULE B WAS OUT OF SERVICE 22 DAYS FOR CLEANING OF THE MIST ELIMINATOR
                         AND REHEATER. INSTALLATION OF OVERHEAD SPRAY NOZZLES AND REPLACEMENT OF
                         SECTIONS OF THE MIST ELIMINATOR.

                         THE BOILER WAS SHUTDOWN FOR TWO DAYS TO REPAIR THE TURBINE/GENERATOR.

 9/72  A                         . 0
       B                       30.0
       SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER WAS OFF LINE FROM SEPTEMBER 1 TO SEPTEMBER 5 DUE TO A LACK OF
                         DEMAND.

                         AN ID FAN PROBLEM CAUSED UNSTABLE OPERATION DURING THE MONTH.

                         MODULE A WAS OUT OF SERVICE IN SEPTEMBER DUE TO THE NECESSARY MODIFICATION
                         OFTHE REHEATER AND TO REPAIR THE RECYCLE TANK SCREENS.

 10/72  A                         .0
       &                         .0
       SYSTEM                                                                744

       *« PROBLEMS/SOLUTIONS/COMMENTS

                         DURING OCTOBER THE BOILER WAS OUT OF SERVICE THE ENTIRE MONTH.

                         MODULES A AND B WERE OUT OF SERVICE DUE TO THE INSTALLATION OF THE REHEATER
                         BAFFLE PLATES TO DAMPEN VIBRATIONS AND ALSO THE INSTALLATION OF AN EXPERI-
                         MENTAL MIST ELIMINATOR WASH SYSTEM.

 11/72  A                         . 0
       B                         .0
       SYSTEM                                                                720
                                             D-3

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON: WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       *# PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER REMAINED OUT OF SERVICE DURING THE MONTH OF NOVEMBER.

                         MODULES A AND B REMAINED OUT OF SERVICE DUE TO UNSTABLE OPERATIONS OF THE
                         BOILER.
12/72
 1/73
       A
       B
       SYSTEM
22.0
30.0
       »* PROBLEMS/SOLUTIONS/COMMENTS
                         MODULES A AND B OPERATED INTERMITTENTLY DURING DECEMBER DUE TO TESTING OF
                         THE ESP AND MISCELLANEOUS INSTRUMENT PROBLEMS.
       A
       B
       SYSTEM
  .0
  .0
                                              744
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         DURING JANUARY MODULES A AND B WERE OUT OF SERVICE THE ENTIRE MONTH TO
                         PERFORM SOME NECESSARY REPAIRS AND MODIFICATIONS TO THE SYSTEM.
  2/73  A
       B
       SYSTEM
22.0
24.0
                                                                             672
        **  PROBLEMS/SOLUTIONS/COMMENTS
                         DURING FEBRUARY MODULES A AND B REMAINED OUT OF SERVICE DUE TO CRACKS
                         IN THE INLET DUCTWORK OF THE BOOSTER FAN.

                         THE IMPROPER INSTALLATION OF THE MIST ELIMINATOR IN MODULE B CAUSED
                         PLUGGING IN THE REHEATER.
  3/73   A
        B
        SYSTEM
65.0
11.0
                                                                             744
        **  PROBLEMS/SOLUTIONS/COMMENTS
                         MODULE A WAS OUT OF SERVICE FOR FIVE DAYS IN MARCH DUE TO PLUGGING OF THE
                         MIST ELIMINATOR.

                         DURING MARCH THE BOILER WAS OUT OF SERVICE FOR APPROXIMATELY FOUR DAYS
                         DUE TO AN INSPECTION.

                         MODULE B WAS OUT OF SERVICE PART OF THE MONTH DUE TO REHEATER TUBE LEAKS.
  4/73   A
        B
        SYSTEM
 6.0
13.0
                                                                             720
        **  PROBLEMS/SOLUTIONS/COMMENTS
                         DURING APRIL PROBLEMS OCCURRED DUE TO THE DEPOSITS OF CALCIUM SULFATE
                         SCALE ON THE REHEATER TUBES OF MODULE A.

                         PERSISTING PROBLEMS WITH THE MIST ELIMINATOR WERE ENCOUNTERED DURING THE
                         MONTH.
                                             D-4

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984
COMMONWEALTH EDISON:  WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR
 5/73
 6/73
 7/73
 8/73
  9/73
 10/73
 11/73
A
B
SYSTEM
  .0
  .0
       ** PROBLEMS/SOLUTIONS/COMMENTS

                         MODULES A AND B WERE OUT OF SERVICE FOR THE ENTIRE MONTH OF MAY.
A
B
SYSTEM
16.0
  .0
                                                                             720
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         DURING JUNE BOILER-RELATED PROBLEMS WERE RESPONSIBLE FOR MOST OF THE
                         OUTAGE TIME OF MODULE A.  MODULE B WAS TAKEN OUT OF SERVICE TO ALLOW
                         CONCENTRATION ON THE PROBLEMS OF MODULE A.
       A
       B
       SYSTEM
                        51.0
                          .0
                                                                             744
       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING JULY PROBLEMS WERE ENCOUNTERED WITH REHEATER TUBE LEAKS ON MODULE A.

                         HIGH FAN VIBRATIONS CAUSED OUTAGE TIME DURING JULY.
A
B
SYSTEM
19.0
  .0
                                                                             744
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         DURING AUGUST MORE REHEATER TUBE LEAKS ON MODULE A ATTRIBUTED TO CHLORIDE
                         CORROSION ATTACK.
       A
       B
       SYSTEM
                           .0
                           .0
                                                                      720
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         DURING SEPTEMBER MODULES A AND B REMAINED OUT OF SERVICE.  DURING THIS
                         TIME THE CHICAGO FLY ASH CO. FINISHED CLEANING AND TREATING THE NORTHEAST
                         HALF OF THE SLUDGE POND.'
       A
       B
       SYSTEM
                        32.0
                           .0
                                                                      744
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         DURING OCTOBER MODULE A TRIPPED SEVERAL TIMES DUE TO BAD LIMIT SWITCHES
                         IN THE BYPASS AND THE BLOCK DAMPERS.

                         THE BOILER WAS TAKEN OUT OF SERVICE TO BALANCE THE BOOSTER I.D. FAN.
       A
       B
       SYSTEM
                        51.0
                           .0
                                                                      720
                                             0-5

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

COMMONWEALTH EDISON: MILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING NOVEMBER PROBLEMS OCCURRED WITH THE MIST ELIMINATOR DUE TO POOR GAS
                         DISTRIBUTION.

                         MODULE A WAS TAKEN OUT OF SERVICE FOR AN INSPECTION.  CLEANING AND MODI-
                         FICATIONS WERE ALSO DONE DURING NOVEMBER.
13/73  A
       B
       SYSTEM
 1/74
  .0
  .0
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         MODULES A AND B WERE OUT OF SERVICE DURING DECEMBER DUE TO MODIFICA-
                         TIOMS AND MAINTENANCE TO THE ISOLATION VALVES, PUMPS, VENTURI THROATS AND
                         THE MIST ELIMINATOR.
       A
       B
       SYSTEM
  .0
  .0
                                                                             744
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         MODULES A AND B WERE OUT OF SERVICE DUE TO FREEZING IN THE 10-INCH-DIAME-
                         TER, 4400 FT. LINE BETWEEN THE MODULES AND THE POND.

                         DAMAGE OCCURRED TO THE SUMP PUMPS AND ALSO SOME OTHER INSTRUMENTS DUE TO
                         THE FREEZING.
  2/74  A
       B
       SYSTEM
  .0
  .0
                                                                             67Z
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         DURING FEBRUARY THE FROZEN PIPELINES WERE THAWED, REANCHORED AND RETURNED
                         TO SERVICE.  THE INSTRUMENTS DAMAGED BY THE FREEZING WERE REPAIRED.

                         MODULE A REMAINED OUT OF SERVICE UNTIL THE ARRIVAL OF THE SECOND-STAGE
                         MIST ELIMINATOR.
  3/74   A
        B
        SYSTEM
21.0
  .0
                                                                             744
        *»  PROBLEMS/SOLUTIONS/COMMENTS
                         MODULE A WAS OPERABLE MARCH 20, BUT WAS NOT RETURNED TO SERVICE UNTIL
                         MARCH 27 DUE TO THE BOILER BEING OUT OF SERVICE.
 4/74  A
       B
       SYSTEM
72.0
  .0
                                                                             720
        **  PROBLEMS/SOLUTIONS/COMMENTS
                         DURING APRIL MODULE A OPERATED ON LOW-SULFUR COAL FOR 23 CONSECUTIVE DAYS.
                         TWO SHORT INSPECTION OUTAGES OCCURRED DURING THAT TIME.

                         THE SUMP SCREEN FROM MODULE B WAS SUBSTITUTED FOR THE DAMAGED  SCREEN IN
                         MODULE A.
                                             D-6

-------
                                                  UTILITY F6D SURVEY:  OCTOBER 1983 - SEPTEMBER 198*
COMMONWEALTH EDISON:  WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR
 5/74
 6/74
 7/74
 8/74
A
B
SYSTEM
  9/74
10/74
93.0
  .0
                                                                             744
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         DURING MAY MODULE A OPERATED MOST OF THE TIME ON HIGH-SULFUR COAL.  DURING
                         THIS TIME A FEW SHORT OUTAGES OCCURRED FOR INSPECTIONS.
A
B
SYSTEM
55.0
  .0
                                                                             720
       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING JUNE MODULE A OPERATED FOR APPROXIMATELY 300 HOURS.

                         TWO WEEKS OF OUTAGE TIME WAS NECESSARY TO MAKE REPAIRS TO THE VENTURI
                         THROAT DRIVE.
       A
       B
       SYSTEM
                        96.0
                          .0
                                                                             744
       *» PROBLEMS/SOLUTIONS/COMMENTS
                         MODULE B WILL REMAIN OUT OF SERVICE UNTIL SATISFACTORY OPERATION OF MODULE
                         A IS ACHIEVED.
       A
       B
       SYSTEM
                        91.0
                           .0
                                                                      744
       #* PROBLEMS/SOLUTIONS/COMMENTS
                         DURING AUGUST THE BOILER WAS TAKEN OFF LINE THREE TIMES DUE TO LACK OF
                         DEMAND.

                         TWO OUTAGES OCCURRED DUE TO LEAKS IN THE STEAM PIPING.

                         ONE OUTAGE OCCURRED DUE TO THE BALANCING OF A FAN.
       A
       B
       SYSTEM
                        85.0
                           .0
                                                                      720
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         DURING SEPTEMBER MODULE A WAS OUT OF SERVICE ONCE FOR THE REPAIR OF A
                         SUPERHEATER LEAK AND ONCE FOR CLEANING OF DEPOSITS FROM THE VENTURI
                         THROAT.
       A
       B
       SYSTEM
                        94.0
                           .0
                                                                      744
       ** PROBLEMS/SOLUTIONS/COMMEHTS
11/74  A
                  DURING OCTOBER REHEATER  LEAKS CAUSED MODULE A TO BE OUT OF SERVICE TWICE.
                  ADDITIONAL OUTAGE TIME WAS A RESULT OF A BOILER OUTAGE AND A INSPECTION
                  OF THE MODULE.

                        97.0
                                             D-7

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

COMMONWEALTH EDISON: WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR

       B                         .0
       SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         MODULE A WAS SHUT DOWN THREE TIMES DURING NOVEMBER.  TWICE DUE TO LACK OF
                         DEMAND AND ONCE FOR AN INSPECTION.

12/74  A                       99.0
       B                         .0
       SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         MODULE A WAS TAKEN OFF LINE PART OF THE MONTH TO REPAIR THE VALVE IN THE
                         SPENT LIQUOR LINE TO THE POND AND ALSO FOR AN INSPECTION.

 1/75  A                       99.0
       B                         .0
       SYSTEM                                                                7*4

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         MODIFICATIONS OF MODULE B ARE STILL CONTINUING.

                         DURING JANUARY MODULE A WAS OUT OF SERVICE TWICE;  ONCE FOR AN INSPECTION
                         AND ONCE DUE TO LACK OF DEMAND.

 2/75  A                       99.0
       B                         .0
       SYSTEM                                                                672

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         DURING FEBRUARY MODULE A WAS OUT OF SERVICE TWO TIMES DUE TO LACK OF DE-
                         MAND AND ALSO FOR AN INSPECTION.  THE INSPECTION SHOWED THAT CONDITIONS
                         INSIDE THE MODULE WERE THE SAME AS BEFORE.

                         DURING THE MONTH A SMALL REHEATER LEAK IN A STAINLESS STEEL BUNDLE CAUSED
                         THE SYSTEM TO SHUT DOWN.

                         DURING THE INSPECTION OF MODULE A, THE UNDERWASH NOZZLES WERE CLEANED AND
                         A SMALL SECTION FO THE MIST ELIMINATOR WAS REPLACED.

                         CHICAGO FLYASH IS TREATING MATERIAL FROM THE SYSTEM WITH PORTLAND
                         CEMENT AND FLYASH AND DUMPING THE TREATED MATERIAL INTO THE NORTH HALF
                         OF THE HOLDING BASIN.

 3/75  A            94.0        99.2                    81.2
       B              .0          .0                      .0
       SYSTEM                                                                744   609

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         A VENTURI HOSE LEAK FORCED MODULE A OUT ONCE.

                         MODULE B WAS OUT OF SERVICE TWICE FOR NO DEMAND AND ONCE AS A RESULT OF AN
                         ACCIDENTAL 50 MINUTE TRIP.

                         COAL BURNED THIS MONTH AVERAGED LESS THAN ONE  PERCENT SULFUR.

 4/75  A            37.0        39.5                    35.0
       B              .0          .0                      .0
       SYSTEM                                                                720   638
                                              D-8

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON:  WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         CHICAGO FLY ASH IS TREATING MATERIAL FROM THE SCRUBBER WITH LIME AND FLY
                         ASH AND DUMPING IT INTO THE HOLDING BASIN.

                         A BOILER OUTAGE FORCED MODULE A OUT OF SERVICE ONCE THIS MONTH (MODULE B
                         WAS ALREADY OUT OF SERVICE).

                         COAL BURNED THIS MONTH WAS RECLAIM COAL AND VARIED IN SULFUR CONTENT.

 5/75  A           8"*. 5        84.5                    84.5
       B           37.1        37.1                    37.1
       SYSTEM                                                                744   744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         MODULE B WAS IN SERVICE ON MAY 20 FOR THE FIRST TIME SINCE APRIL 13, 1973.

                         RECIRCULATION TANK MIXERS.

                         MODULE A (WHICH WAS THE ONLY ONE OPERATING) WAS FORCED OUT TWICE IN APRIL
                         TO AVOID POND OVERBOARDIHG INTO THE DES PLAINES RIVER. THE SECOND OUTAGE
                         LASTED UNTIL MAY 5. DURING THE PAST SEVERAL MONTHS OF GENERALLY CONTINUOUS
                         OPERATION OF MODULE A. IT HAS BECOME APPARENT THAT THE PRESENT LIQUID
                         CIRCULATING SYSTEM CANNOT BE OPERATED IN A CONTINUOUSLY CLOSED CYCLE.  THE  '
                         WATER IMBALANCE POSES A HIGH RISK OF OVERBOARDING FROM THE SLUDGE POND
                         DURING LONG PERIODS OF SUSTAINED OPERATON. THE FOLLOWING REVISIONS HAVE
                         BEEN MADE TO REDUCE THE WATER IMBALANCE:
                              1. THE PUMP GLAND WATER FLOWS HAVE BEEN CUT FROM 10 GPM TO S GPM.
                              2. THE SCRUBBER HOUSE SERVICE WATER FILTER BACKWASH HAS BEEN ROUTED
                                 OUT OF THE SYSTEM.
                              3. THE CONTINUOUS UNDERSPRAY HAS BEEN CHANGED TO AN INTERMITTENT
                                 SPRAY 5 MINUTES ON, 5 MINUTES OFF.

                         THE THICKENER HAS BEEN DOWN SINCE APRIL 21 DUE TO A BROKEN GEAR AND A  STUCK
                         SWEEP ARM. THE THICKENER HAS BEEN BYPASSED AND THE SLUDGE IS COINS TO  THE
                         POND.

                         DURING MAY, MODULE A WAS OUT FOR 45 MINUTES DUE TO A DAMPER TRIP.

                         MODULE A WAS OUT ONCE FOR SPRAY NOZZLE CLEANING.

                         MODULE B WAS OUT TWICE AFTER START UP, ONCE FOR A VENTURI PUMP TRIP AND
                         ONCE FOR A RECIRCULATION TANK LEVEL TRIP.

                         CHICAGO FLY ASH IS TREATING THE MATERIAL FROM THE SCRUBBER WITH LIME AND
                         FLY ASH AND DUMPING IT INTO THE HOLDING BASIN. A MIXER HAS BEEN INSTALLED
                         AT THE THICKENER, WHICH ENABLES THEM TO SUBSTITUTE SEALED DUMP TRUCKS FOR
                         THE CEMENT TRUCKS WHICH WERE USED IN THE PAST FOR MIXING AND TRANSPORTING
                         THE WASTE MATERIAL TO THE HOLDING BASIN.

                         COAL BURNED THIS MONTH VARIED GREATLY IN SULFUR CONTENT, RANGING FROM LOW
                         SULFUR WESTERN COAL TO HIGH SULFUR ILLINOIS COAL.

 6/75  A           64.1        60.6                    54.1
       B           85.5        84.6                    75.4
       SYSTEM                                                                720   642

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         A REHEATER PLUGGAGE INSPECTION FORCED ONE MODULE A OUTAGE.

                         A LOW LEVEL TRIP CAUSED A 35 MINUTE OUTAGE, AND NO DEMAND ACCOUNTED FOR TWO
                                             D-9

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON: WILL COUMTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR

                         MORE MODULE A OUTAGES.

                         MODULE B WAS OUT FOR 95 HOURS TO CLEAN THE BOOSTER FAN AND OEMISTER.

                         HIGH BOOSTER FAN VIBRATIONS CAUSED MODULE B TO SHUT DOWN ON JUNE 30.

                         DURING THIS MONTH HIGH SULFUR COAL WAS BURNED IN A TWO WEEK TEST, AND LOW
                         SULFUR COAL WAS BURNED THE REST OF THE MONTH.
 7/75  A
       B
       SYSTEM
              .0
            79.2
   .0
 79.4
  .0
73.5
                                                                      744   689
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         CHICAGO FLY ASH IS TREATING THE SCRUBBER WASTE MATERIAL WITH LIME AND FLY
                         ASH AND DUMPING IT INTO THE ON SITE HOLDING BASIN. THE MATERIAL FROM THE
                         HOLDING BASIN IS BEING TRUCKED TO AN OFF SITE DUMP.

                         MODULE B WAS OUT ONCE (30 MINUTES) TO REPAIR A MINOR STEAM HEADER LEAK.

                         MODULE B WAS OUT ONCE DUE TO NO DEMAND.

                         LOW SULFUR COAL WAS BURNED MOST OF THIS MONT, WITH HIGH SULFUR COAL BEING
                         BURNED DURING THE LAST WEEK OF THE MONTH.
 8/75
A
B
SYSTEM
                      .0
                   93.5
   .0
100.0
  .0
76.4
                                                                             744   565
       ** PRCBLEMS/SOLUTIONS/COMMENTS
                         IN JUNE, MODULE A ENCOUNTERED PLUGGAGE IN THE DEMISTER, WHICH REQUIRED ITS
                         REPLACEMENT. THE WORK WAS COMPLETED IN AUGUST.

                         MODULE A WENT OUT OF SERVICE ON JUNE 20 AND REMAINED OUT THROUGH AUGUST DUE
                         TO MASSIVE REHEATER LEAKS. THERE IS PRESENTLY A HOLD ON THE NEW REHEATER
                         ORDER BECAUSE OF MATERIAL FAILURES EXPERIENCED IN MODULE B'S CARBON STEEL
                         REHEATER.

                         MODULE B SUFFERED TWO OUTAGES IN JULY AND ONE IN AUGUST BECAUSE OF REHEATER
                         TUBE LEAKS. THE FAILURES WERE DUE TO VIBRATION FATIGUE. THE REHEATER, WHICH
                         WAS INSTALLED IN MAY, HAS LOST SIX OF ITS TWELVE TUBE BUNDLES SO FAR. THE
                         LENGTH OF TIME THAT THE TUBES HAVE LASTED WOULD SEEM TO INDICATE THAT THERE
                         IS A DIESIGN RELATED MATERIAL DEFICIENCY. THREE OF THE TUBE BUNDLES WERE
                                 REPLACED WITH MARGINAL BUNDLES LEFT OVER FROM MODULE A.

                         A SMALL STEAM HEADER LEAK CAUSED ONE MODULE B OUTAGE.

                         MODULE B WAS OUT FOUR TIMES FOR NO DEMAND AND ONCE FOR A LOW FLOW TRIP.

                         HIGH SULFUR COAL WAS BURNED ALL MONTH, CAUSING AN INCREASE IN SLUDGE
                         PRODUCTION WHICH HAS FORCED A MINIMUM SIX DAY A WEEK, TEN HOUR A DAY
                         SLUDGE DISPOSAL OPERATION. THE SLUDGE IS BEING TREATED WITH LIME AND
                         FLY ASH AND BEING DUMPED INTO THE ON SITE HOLDING POND. STABILIZED
                         MATERIAL IS BEING TRUCKED FROM THE POND TO AN OFF SITE DISPOSAL AREA.
  9/75   A
        B
        SYSTEM

 10/75   A
        B
        SYSTEM
              .0
            32.3
   .0
100.0
  .0
26.6
                                                                      720
                                                                              744    194
                                             0-10

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER
COMMONWEALTH EDISON:  WILL COUNTY 1 (CONT. )
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         MODULE A WAS OFF THE ENTIRE 11 DAYS THE BOILER OPERATED THIS MONTH, WAITING
                         FOR ITS NEW REHEATER, WHICH HAS NOW BEEN RELEASED FOR MANUFACTURING BY
                         SMED.

                         MODULE B HAD TWO OUTAGES, ONE FOR NO DEMAND AND ONE MINOR 15 MINUTE TRIP.

                         HIGH SULFUR COAL WAS BURNED THIS MONTH WHEN THE SCRUBBER WAS IN SERVICE.

                         THE SLUDGE IS BEING TREATED WITH LIME AND FLY ASH AND HAULED TO AN OFF SITE
                         DISPOSAL AREA.
11/75  A
       B
       SYSTEM

12/75  A
       B
       SYSTEM

 1/76  A
       B
       SYSTEM

 2/76  A
       B
       SYSTEM
  3/76
       A
       B
       SYSTEM
  .0
  .0
  .0
  .0
  .0
  .0
  .0
  .0
30.1
 8.8
45.2
20.4
                          .0
                          .0
18.8
 8.5
                                                          720
                                                          744
                                                          744
                                                          696
                                                          744   309
       *« PROBLEMS/SOLUTIONS/COMMENTS
                         UNIT 1 WAS DOWN FROM OCTOBER 11 THROUGH MARCH 19 FOR ITS BOILER TURBINE
                         AND SCRUBBER OVERHAUL. THE MAJOR ITEMS TO BE ACCOMPLISHED DURING THE
                         OUTAGE WERE:
                              1. SIMPLIFICATION OF THE MILLING SYSTEM CONTROL.
                              2. PULLING AND CLEANING OF THE MODULE B REHEATER AND RETURNING IT
                                 REPLACED WITH MARGINAL BUNDLES LEFT OVER FROM MODULE A.
                              3. CLEANING OF THE POND PUMP BAY.
                              4. REMOVAL OF THE VENTURI AND ABSORBER PUMP CHECK VALVES (ONE OF THEM
                                 FAILED LAST SPRING AND DESTROYED A PUMP LINER AND IMPELLER).
                              5. CLEANING AND REPAIR OF THE VENTURI NOZZLES AND SUPPORTS.
                              6. REPAIR OF CORRODED REHEATER SUPPORTS.
                              7. RESETTING AND ADJUSTMENT OF ALL DAMPERS.
                              8. REVISION OF SCRUBBER CONTROLS BY REMOVING THE CONTROLS NO LONGER
                                 USED OR NEEDED.
                              9. INSPECTION AND CLEANING OF THE ENTIRE SCRUBBER AND RELATED
                                 EQUIPMENT.

                         MODULE A WAS PUT INTO THE GAS PATH ON MARCH 22 AND REMAINED AVAILABLE FOR
                         SERVICE THE REST OF THE MONTH.

                         MODULE B HAD TO REMAIN OUT OF SERVICE UNTIL MARCH 29 WHILE ITS REPAIRED
                         REHEATER WAS INSTALLED.
 4/76  A
       B
       SYSTEM
23.0
20.0
49.3
19.2
47.3
                                                          720   691
                                             D-ll

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON: WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  V. REMOVAL   PER  BOILER  FGD   CAP.
                                                                502  PART. HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         UNIT 1 RETURNED TO SERVICE APRIL Z AFTER A SHORT TURBINE CONTROL OUTAGE.
                         BOTH MODULES CAME ON LINE JUST BEFORE THE BOILER.

                         A FIVE DAY OUTAGE OF MODULE B WAS DUE TO REHEATER TUBE BUNDLE LEAKS.

                         SEVERAL MODULE B OUTAGES WERE DUE TO PLUGGED ABSORBER TANK SCREENS CAUSED
                         BY MILL AND CLASSIFIER FAILURES WHICH ALLOWED ROCK TO GET INTO THE SYSTEM.
                         MODULE B WAS THOROUGHLY CLEANED.

                         ONLY ONE ABSORBER PUMP IS BEING USED IN MODULE B, SINCE THE IBZ PUMP LINER
                         FAILED AS A RESULT OF A BROKEN DISCHARGE VALVE. A REPLACEMENT LINER IS
                         BEING INSTALLED.

                         A SCRUBBER TESTING AND EVALUATING PROGRAM WAS STARTED THIS MONTH. MUCH OF
                         THE LATTER TWO WEEKS OF THE MONTH WERE SPENT TRAINING THE TESTING PERSON-
                         NEL. THE PROGRAM WILL PROVIDE CHEMISTRY DATA AND OPERATING CHARACTERISTICS.

 5/76  A              .0          .0                      .0
       SYSTEM                                                                744   665

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         A VENTRUI HOSE LEAK FORCED MODULE B OFF ONCE THIS MONTH.

                         MODULE B WAS TAKEN OUT OF SERVICE ONCE BECAUSE OF A PLUGGED ABSORBER TANK
                         SCREEN.

                         MODULE B WAS OFF ONCE DUE TO A FOULED I.D. FAN.

                         MODULE B WAS OUT OF THE GAS PATH ONCE DUE TO NO DEMAND.

 6/76  A           52.0        44.2                    37.6
       B           66.2        84.5                    71.9
       SYSTEM                                                                720   612

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         MODULE A SUFFERED VENTURI PUMP LINER FAILURES ON APRIL 78 WHEN AN INLET 16
                         INCH BUTTERFLY ISOLATION VALVE BROKE APART AND FELL INTO THE VENTURI PUMP.
                         BOTH THE A AND BACKUP AB VENTURI PUMP LINERS WERE DESTROYED. MODULE A
                         REMAINED OUT SERVICE UNITL JUNE 9, WHEN THE LINERS WERE REPLACED.

                         MODULE A WAS OFF ONCE FOR SHEARED BYPASS DAMPER PINS.

                         I.D. BOOSTER FAN FOULING FORCED MODULE A OFF ONCE THIS MONTH FOR ABOUT
                         164 HOURS.

                         BOTH MODULES WERE OFF TWICE DUE TO NO DEMAND. DURING THESE OUTAGES, THE
                         DEMISTERS WERE WASHED AND ABSORBER TRAY SCALE, IF ANY, WAS KNOCKED OFF.

                         MODULE B WAS OUT OF THE GAS PATH FOR SEVERAL SHORT VENTURI LOW FLOW TRIP
                         OUTAGES DUE TO A PLUGGED, SCALED VENTURI TANK SCREEN. AT THE END OF THE
                         MONTH, THE MODULE WAS TAKEN OUT TO CLEAN THE SCREEN.

                         THE MODULE B I.D. BOOSTER FAN REQUIRED CLEANING DURING THE MONTH.

                         THE REHEATER TUBES ARE SCALING, WHICH RESULTS IN A LOWER HEAT TRANSFER RATE
                         RATE, AND THEREFORE INCREASES I.D. BOOSTER FAN FOULING. THE ONLY WAY TO
                         CLEAN THE REHEATERS EFFECTIVELY IS TO REMOVE THEM, WHICH DEMANDS A SUBSTAN-
                         TIAL OUTAGE.
                                             0-12

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH  EDISON:  WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


 7/76  A           19.9          .0                      .0
       B           86.2        90.0                    72.3
       SYSTEM                                                                744   598

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         MODULE A WAS OFF THE FIRST PART OF THE MONTH DURING REPAIRS TO THE ABSORBER

                         THE LATTER PART OF THE MONTH THE MODULE WAS READY FOR SERVICE BUT WAS NOT
                         OPERATED BECAUSE OF THICKENER-POND SLUDGE OVERLOADING.

                         MODULE B WAS FORCED OFF ONCE TO BALANCE THE I.D. BOOSTER FAN. AND ONCE TO
                         MASH THE FAN.

                         MODULE B WAS OUT OF THE GAS PATH TWICE DUE TO NO DEMAND.

 8/76  A           98.2        57.6                    38.3
       B           65.4        61.4                    40.9
       SYSTEM                                                                744   495

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         MODULE A WAS OUT OF THE GAS PATH THE FIRST HALF OF THE MONTH T AVOID
                         THICKENER-POND OVERLOADING.

                         DURING THE LATTER HALF OF THE MONTH, MODULE A WAS USED WITH THREE MINOR
                         FORCED OUTAGES AND ONE FOUR DAY NO DEMAND OUTAGE.

                         MODULE B WAS OUT OF THE GAS PATH THREE TIMES DUE TO NO DEMAND.

                         LOSS OF CHEMICAL CONTROL CAUSED TWO MODULE A OUTAGES.

                         MODULE B WAS OFF FOR NINE DAYS DUE TO FOULING.

                         SPENT SLURRY VALVE REPAIRS FORCED A MODULE B OUTAGE.

                         ON AUGUST 12 THE OPERATING PH CONTROL SET POINT WAS REDUCED FROM 5.4 TO
                         5.1. IT IS BELIEVED THAT THIS LOWER PH IS THE CAUSE OF THE FOULING OUTAGE
                         OF MODULE B ON AUGUST 21. MODULE A WAS ALSO OPERATED FOR THREE DAYS, AND
                         IT, TOO, EXPERIENCED INCREASED SACLE FOULING. THE PH SET POINT WAS THEN
                         INCREASED BACK TO 5.4.

 9/76  A           42.3        28.7                    22.6
       B           79.4                                59.9
       SYSTEM                                                                720   566

       «* PROBLEMS/SOLUTIONS/COMMENTS

                         MODULE A WENT OFF ONCE DUE TO A LOW FLOW TRIP.

                         MODULE A WAS TAKEN OFF ONCE FOR CLEANING OF THE RECIRCULATION TANK AND
                         PUMPS, AND INSPECTION OF PUMP ISOLATION VALVES.

                         A LINER LEAK IN 1A2 ABOSORBER PUMP ALSO FORCED MODULE A OFF.

                         MODULE A WAS OUT OF TH GAS PATH TWICE DUE TO NO DEMAND.

                         MODULE A WAS TAKEN OFF ONCE TO AVOID THICKENER-POND OVERLOADING.

                         SPENT SLURRY VALVE TROUBLE CAUSED TWO MODULE B OUTAGES.

10/76  A           27.9        28.9                    37.9
                                             D-13

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON: WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR

       B           76.4        56.2                    54.8
       SYSTEM                                                                744   726

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         HIGH SULFUR ILLINOIS COAL WAS BURNED IN THE BOILER FROM MARCH THROUGH
                         OCTOBER.

                         THE SCRUBBER WASTE MATERIAL WAS TREATED WITH LIME AND FLY ASH AND HAULED TO
                         AN OFF SITE DISPOSAL AREA.

                         MODULE A OPERATED ON ONE ABSORBER PUMP, ALLOWING TESTING ON A LOWER
                         ABSORBER FAN.

                         MODULE A WAS OUT OF THE GAS PATH ONCE FOR AN I.D. BOBOOSTER FAN TRIP.

                         WORK ON RECIRCULATION TANK LEVEL CONTROLS CAUSED A MODULE A OUTAGE.

                         MODULE B WAS FORCED OFF ONCE TO REPAIR A REHEATER HEADER LEAK.

                         ONE MODULE B OUTAGE WAS FOR VENTURI NOZZLE CLEANING.

                         MODULE B WENT OFF FOR A VENTURI LOW FLOW TRIP.

                         MODULE B REMAINED OUT OF SERVICE WHILE MODULE A WAS BEING TESTED TO AVOID
                         THICKENER-POND OVERLOADING.

                         A VACUUM FILTER WAS TIED IN AT THE THICKENER.

 11/76  A           20.1        25.6                    20.1
       B           72.2        69.6                     4.7
       SYSTEM                                                                720   566

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         MODULE A OPERATED ON ONE ABSORBER PUMP DURING MODULE B OUTAGE.

                         MODULE B WAS FORCED OUT OF THE GAS PATH ONCE FOR A MILLING SYSTEM FAILURE.

                         MODULE B ENCOUNTERED A VENTURI HEADER LEAK.

                         THE VENTURI NOZZLES REQUIRED CLEANING DURING THE MONTH.

                         REPLACEMENT OF THE SPENT SLURRY VALVE NECESSITATED A MODULE OUTAGE.

                         MODULE B WAS OFF ONCE DUE TO A CHEMICAL SYSTEM UPSET.

                         MODULE B WAS OUT OF THE GAS PATH TWICE DUE TO NO DEMAND (MODULE A WAS NOT
                         IN SERVICE AT THE TIME OF THE OUTAGE).

 12/76  A           44.9        48.3                    44.9
       B           53.4        51.7                    48.0
       SYSTEM                                                                744   692

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THE LAST WEEK OF NOVEMBER, THE 1A2 ABSORBER PUMP WAS TAKEN OUT OF
                         SERVICE FOR OVERHAUL. THE REPAIRS WERE COMPLETED ON DECEMBER 6, WHEN THE
                         MODULE ASSUMED A ONE ABSORBER PUMP STANDBY CAPABILITY UNTIL THE 1A1 ABSOR-
                         BER PUMP CAN BE REPAIRED.

                         DURING THE LAST HALF OF THE MONTH, MODUELE A OPERATED WHILE MODULE B WAS
                         BEING REPAIRED.
                                              D-14

-------
                                                  UTILITY FGO SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON:  MILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR

                         MODULE B PERFORMED SATISFACTORILY DURING THE FIRST HALF OF THE MONTH,
                         EXPERIENCING ONLY ONE NO DEMAND OUTAGE. ON THE 17TH, HOWEVER, THE SPENT
                         SLURRY VALVE FAILED AND THE MODULE HAS REMAINED OUT OF SERVICE.

 1/77  A           98.2        98.7                    95.8
       B           13.5         1.1                     1.1
       SYSTEM                                                                744   722

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE 1A1 ABSORBER PUMP WENT OUT IN LATE SEPTEMBER WITH BURNED OUT BEARINGS
                         AND REMAINED OUT THROUGH JANUARY WAITING FOR PARTS.

                         LOW SULFUR COAL WAS BURNED IN THE BOILER FROM NOVEMBER THROUGH JANUARY.

                         DUE TO THE LOW VOLUME OF SLUDGE PRODUCED WHILE BURNING LOW SULFUR COAL,
                         MUCH OF THE SLUDGE HANDLING TIME WAS SPENT DIGGING OUT THE ACCUMULATED
                         SLUDGE IN THE RECIRCULATION POf.-DS. THIS MATERIAL, ALONG WITH SCRUEBER
                         WASTE MATERIAL, WAS TREATED WITH LIME AND FLYASH AND HAULED TO AN OFF
                         SITE DISPOSAL AREA.

                         MODULE A WAS FORCED OUT ONCE BY A FAILED SPENT SLURRY VALVE.

                         PLUGGED DEMISTER UNDERSPRAYS CAUSED ANOTHER MODULE A OUTAGE.

                         MODULE A WENT OUT ONCE BECAUSE OF NO DEMAND AND ONCE DUE TO A BOILER OUTAGE
                         (MODULE B WAS ALREADY OUT OF SERVICE FOR REPAIRS).

                         MODULE B BECAME AVAILABLE FOR SERVICE ON JANUARY 27, AFTER REPAIRS TO THE
                         SPENT SLURRY VALVE WERE COMPLETED. DUE TO SEVERE WEATHER CONDITIONS, THE
                         MODULE WAS PLACED IN THE GAS PATH JANUARY 31.

 2/77  A           38.8        42.6                    38.8
       B           72.0        45.7                    41.7
       SYSTEM                                                                672   613

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THERE WAS VERY LITTLE DIGGING IN THE RECIRCULATION PONDS. CHICAGO FLYASH
                         SPENT MOST OF THEIR TIME ON CLEANING AND MAINTENANCE.

 3/77  A           96.9        66.7                    64.2
       B           80.9        75.5                    73.9
       SYSTEM                                                                744   728

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         AN ERT S02 ANALYZER WAS INSTALLED ON THE DISCHARGE SIDE OF MODULE B I.D.
                         BOOSTER FAN. THIS IS AN "IN SITU" ON-DISPERSIVE ANALYZER THAT CONTINUALLY
                         MEASURES AND READS OUT CONCENTRATIONS OF S02, CO, C02, AND NO.

                         AN ABSORBER SUCTION HEADER LEAK FORCED MODULE B FROM THE GAS PATH.

                         MODULE B WAS FORCED OUT DUE TO A SLURRY VALVE GASKET LEAK.

                         A PLUGGED FEED SLURRY RECIRCULATION LINE WAS ENCOUNTERED IN MODULE B.

                         HIGH SULFUR COAL WAS BURNED FOR SEVEN DAYS THIS MONTH TO PROVIDE HIGH
                         SULFUR SLUDGE FOR THE UOP SLUDGE TEST.

                         CHICAGO FLYASH SPENT 75X OF THEIR TIME DIGGING IN THE POND. THE REST WAS
                         SPENT ON THE THICKENER AND VACUUM FILTER IPERATION. THE SCRUBBER WASTE
                         MATERIAL WAS TREATED WITH LIME FLYASH AND HAULED OFF SITE.
                         DISPOSAL AREA.
                                             D-15

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON: WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS  FACTOR
ft/77 A
B
SYSTEM
86.1
45.5

67.7
30.2

61.2
27.3



720 650
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         THE PERFORMANCE OF THE ERT S02 ANALYZER TO DATE HAS BEEN, AT BEST, UNRELIA-
                         BLE AND INCONSISTENT. THE ERT TECHNICIANS ARE OUT TO SERVICE THE ANALYZER
                         ALMOST EVERY OTHER DAY. THE PROBLEM, ACCORDING TO ERT TECHNICIANS, IS OF A
                         "THERMAL NATURE". WHEN THE ANALYZER REACHES A CERTAIN TEMPERATURE, A CHIP
                         SHORTS OUT. THEY HAVE NOT BEEN ABLE TO LOCATE THE FAULTY INTEGRATED CIRCUIT
                         YET.

                         A BOILER TUBE LEAK REPAIR FORCED MODULE A OUT OF THE GAS PATH ONCE THIS
                         MONTH (MODULE B WAS ALREADY DOWN FOR REPAIRS).

                         MODULE B WAS FORCED OUT OF THE GAS PATH TWICE FOR AN ABSORBER SUCTION
                         HEADER LEAK REPAIR.

                         MODULE B WAS OUT OF SERVICE ONCE TO WASH THE I. 0. BOOSTER FAN.

                         CHICAGO ADMIXTURES SPENT MOST OF THEIR TIME DIGGING IN THE SMALL POND,
                         GETTING READY FOR THE MGO ADDITION AND FORCED OXIDATION TEST. THE SCRUBBER
                         WASTE MATERIAL WAS TREATED WITH LIME AND FLYASH AND HAULED TO AN OFF SITE
                         DISPOSAL AREA.
  5/77
        A
        B
        SYSTEM
89.4
98.0
 2.2
50.9
 2.0
47.3
                                                                             744   691
        **  PROBLEMS/SOLUTIONS/COMMENTS
                         THE ERT S02 ANALYZER HAS BEEN REMOVED FROM SERVICE DUE TO A POOR PERFORM-
                         ANCE RECORD OVER THE LAST THREE MONTHS. ERT IS IN THE PROCESS OF RE-
                         ENGINEERING THEIR ANALYZER.

                         THE MGO ADDITION TEST WENT WELL. ALTHOUGH THE MGO INCREASED S02 REMOVAL
                         EFFICIENCY ABOUT 10X, IT DID PRACTICALLY NOTHING FOR THE TWO MORE SERIOUS
                         PROBLEMS, SINCE THICKENER AND SLUDGE PRODUCTION AND LIMESTONE CONSUMPTION
                         RATE WERE ABOUT THE SAME.

                         MODULE A WAS FORCED OUT OF THE GAS PATH ONCE THIS MONTH WHEN THE INLET
                         VALVE ON 1A2 ABSORBER PUMP FAILED.

                         MODULE B WAS TAKEN OFF TO CLEAN AND INSPECT THE REHEATER TUBES.

                         BOTH MODULES WERE FORCED OFF FOR THE FIRST FIFTEEN DAYS OF THE MONTH DUE TO
                         A  FAILED 120V CONTROL TRANSFORMER FOR THE POND RETURN PUMPS. THE TRANSFORM-
                         ER HAD TO BE ORDERED FROM WESTINGHOUSE.

                         HIGH SULFUR COAL HAS BURNED FOR ELEVEN DAYS DURING THE MONTH.
  6/77   A
        B
        SYSTEM
31.8
93.2
13.3
93.4
10.5
73.5
                                                                              720   566
        **  PROBLEMS/SOLUTIONS/COMMENTS
                          THE  1A1 ABSORBER PUMP  IS STILL OUT OF SERVICE WAITING  FOR  PARTS  1A2
                          ABSORBER  PUMP'S ISOLATION VALVES FORCED MODULE A OFF FOR MOST  OF T(E  MONTH.

                          MODULE A  HAD ONE NO DEMAND AND ONE BOILER OUTAGE THIS  MONTH.
                                             D-16

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
COMMONWEALTH EDISON:  WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR

                         MODULE B WAS ALSO FORCED OFF TO CLEAN THE I.D. BOOSTER FAN.

                         NO HIGH SULFUR COAL WAS BURNED THIS MONTH.

                   70.3        41.4                    21.0
7/77
 8/77
  9/77
 10/77
 11/77
 12/77
B
SYSTEM
                                                                             744   377
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         HIGH SULFUR COAL HAS BURNED FOR EIGHT DAYS THIS MONTH. LIMESTONE OPERATION
                         WAS NORMAL FOR HIGH SULFUR OPERATION.

                         MODULE B WAS FORCED OUT OF THE GAS PATH ONCE TO REMOVE A PLUGGED DIFFUSER.
                         THE FINAL TEST, FORCED OXIDATION SEEMDD TO BE THE MOST SUCCESSFUL OF ALL.
                         USING LIQUID OXYGEN, UP TO 12,000 CFM OF GASEOUS 02 WAS FED INTO EACH
                         VENTURI DOWNCOMER, OXIDATION OF SULFITE TO SULFATE WAS INCREASED FROM
                         35 TO 90 7.

                         MODULE B WAS ALSO FORCED OFF DUE TO A LOW LEVEL IN THE SLURRY STORAGE TANK.

                         MODULE B WAS ALSO FORCED OFF DUE TO REHEATER TUBE BUNDLE LEAKS.
      A
      B
      SYSTEM
            99.8
             9.7
99.6
12.0
                                                       80.8
                                                        9.7
                                                                             744   604
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         MODULE A WAS AVAILABLE THE ENTIRE MONTH WITH JUST THE VENTURI PUMP OPERAT-
                         ING.
       A
       B
       SYSTEM
                  61.0
                  52.3
                        77.8
                        75.4
                        54.0
                        52.3
                                                                            720   499
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         MODULE B ENCOUNTERED HIGH VIBERATIONS IN ITS BOOSTER FAN DURING THE FIRST
                         WEEK OF THE MONTH. AFTER THE FAN WAS BALANCED, THE MODULE OPERATED INTIL
                         THE UNIT OUTAGE ON SEPTEMBER 21.
      A
      B
      SYSTEM

      A
      B
      SYSTEM
                      .0
                      .0
               .0
             8.8
                               50.1
                                                   .0
                                                   .0
                          .0
                         8.8
                                                                             744
                                                                             720   126

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         UNIT ONE CAME UP ON NOVEMBER 25 AFTER A SIXTY-THREE DAY OUTAGE.

                         MODULE B IS IN THE GAS PATH FATER EXPERIENCING SOME DIFICULTY IN BALANCING
                         ITS BOOSTER FAN.
       A
       B
       SYSTEM
                  42.5
                  84.1
                        42.5
                        84.1
            47.8
            94.6
42.5
84.1
                                                                            744   661
                                             D-17

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

COMMONWEALTH EDISON: WILL COUNTY 1 (CONT. )
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  7. REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         PLUGGAGE WAS ENCOUNTERED IN THE MODULE B REHEATER.  BECAUSE NO SPARE REHEAT
                         COILS WERE AVAILABLE, THE UTILITY TRIED TAKING SOME COILS FROM MODULE A
                         MODULE B APPEARED TO BE MORE ORE SEVERELY PLUGGED THAN ORIGINALLY THOUGHT.

                         MODULE A WAS DOWN HALF THE MONTH BECAUSE OF A MAIN STEAM LEAK WHICH COULD
                         NOT BE ISOLATED.

                         MODULE A OPERATED UNTIL SEPTEMBER 19, WH E A COMBINATION OF MUD AND SCALE
                         BUILD-UP ON THE SUMP FLOOR STRUCTURALLY DAMAGED THE MODULE. REPAIRS PUT
                         THE MODULE OUT OF SERVICE UNTIL MID DECEMBER.

 1/78  A           69.0        89.9                    66.3
       B           22.0        29.8                    22.0
       SYSTEM                                                                744   549

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         ON JANUARY 7, THE MODULE B I.D. BOOSTER FAN DISCHARGE DUCT STARTED VIBRAT-
                         ING WILDLY. THIS FORCED THE BOILER OFF WHILE THE SHOP MADE REPAIRS TO THE
                         DUCTWORK AND BALANCED THE FAN WITH AN I.R.D. MACHINE.

                         WHEN THE UTILITY ATTEMPTED TO PUT MODULE B BACK IN THE GAS PATH, A LEAK IN
                         THE SLURRY LINE FORCED IT BACK OFF.

                         A PLUGGED VENTURI PUMP FORCED MODULE B OFF THE REST OF THE MONTH.

                         DURING THE OUTAGE, THE REHEATER COILS WERE CLEANED WITH A HIGH PRESSURE
                         (5000 LB) SPRAYER.

                         MODULE A WAS FORCED OFF WHEN A STEAM REGULATING VALVE BLEW ITS PACKING.

                         ON THE 23RD, BOTH MODULES WERE TAKEN OFF AND DRAINED TO ALLOW THE SHOP TO
                         INSTALL NEW ISOLATION VALVES IN THE ABSORBER AND VENTURI PUMPS.

                         TOWARD THE END OF THE MONTH, SOME PROBLEMS WERE ENCOUNTERED WITH THE POND
                         RETURN PUMPS FREEZING.

 2/78  A           40.9        56.5                    34.4
       B           69.5        92.9                    56.5
       SYSTEM                                                                672   409

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         MODULE A RAN INTO DIFFICULT OPERATIONG CONDITIONS THIS MONTH DUE TO RAPID
                         PLUGGING OF THE REHEAT COILS.

                         INSPECTION AND SUBSEQUENT CLEANING OF MODULE A UNCOVERED PLUGGED SPRAY
                         NOZZLES AND DEMISTER TRAYS DUE TO NOZZLE INEFFICIENCY.

                         MODULE B OPERATED VERY WELL AND AN INSPECTION SHOWED THE MODULE TO BE VERY
                         CLEAN.

 3/78  A           93.5       100.0        90.6
       B           83.5        84.7        76.0        26.2
       SYSTEM                                                                7^   230

       #* PROBLEMS/SOLUTIONS/COMMENTS

                         THIS MONTH, DUE TO COAL CONSERVATION, UNIT 1 WAS ON THE SYSTEM VERY LITTLE.

                         MODULE B HAD DIFFICULTY FOR SEVERAL DAYS BECAUSE OF A CRACKED SHEAVE ON THE
                                             D-18

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER
COMMONWEALTH EDISON:  MILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY .UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR

                         VENTURI PUMP.

                         HIGH PRESSURE CLEANING ON BOTH MODULES DURING THE COAL CONSERVATION ALONG
                         WITH REMOVING THE VENTURI THROAT RESTRICTOR BLOCKS PROVED BENEFICIAL IN
                         MAINTAINING BETTER CONTROL OF THE DRAFT CONDITIONS IN THE SCRUBBER.
 4/78
A
B
SYSTEM
 99.9
100.0
 99.7
 99.9
                                                       92.0
                                                       92.2
                                                                             720   665
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         THE PRESSURE DIFFERENTIAL ACROSS THE VENTURIS HAS BEEN REDUCED BY APPROXI-
                         MATELY <»OX AT l WHICH IN TURN IS A FUNCTION OF PRESSURE DROP. INCREASED SOLIDS CARRY-
                         OVER COULD POSSIBLY COMPUND REHEATER PLUGGING PROBLEMS. THE UTILITY IS
                         KEEPING A CLOSE WATCH FOR PLUGGING, BUT HAS NOT YET FOUND ANYTHING UNUSUAL.

                         MODULE A WAS FORCED OUT OF THE GAS PATH ONCE THIS MONTH FOR A VENTURI PIPE
                         LEAK.
 5/78
A
B
SYSTEM
  9.5
 89.2
 99.*
100.0
55.2
56.1
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         DURING THE LAST PART OF THE MONTH BOTH MODULES WERE FORCED OUT OF THE GAS
                         PATH DUE TO REHEATER LEAKS. IT REQUIRED A TWO DAY OUTAGE TO REMOVE THE
                         LEAKING REHEATER BUNDLES. ADDITIONAL REHATERS ARE ON ORDER AND ARE EXPECT-
                         ED TO ARRIVE IN JUNE.
 6/78
       A
       B
       SYSTEM
            87.1
            85.6
             9*.5
            100.0
                         23.7
                         25.1
                                                                      720   181
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         DURING A SCRUBBER INSPECTION, 25X DIEMISTER AND 75X ABSORBER SPRAY PLUGGAGE
                         WAS DISCOVERED IN MODULE A. MODULE B WAS NOT AS BAD.

                         HIGH VIBRATION WAS ENCOUNTERED IN THE TURBINE BEARINGS DURING BOILER START
                         UP, CAUSING THE BOILER TO SHUT BACK DOWN.

                         THE PUG MILL FOR CHICAGO ADMIXTURES HAS BEEN APPROVED, AND THE NEW SLUDGE
                         TREATMENT SYSTEM SHOULD BE OPERATING BY FALL.

                         THE SCRUBBER WAS FORCED OUT OF THE GAS PATH ONCE THIS MONTH WHEN THE 1B1
                         ABSORBER DISCHARGE VALVE FAILED TO OPEN.

                         THE BOILER WAS FORCED OFF THE LAST FOUR DAYS OF THE MONTH FOR CYCLONE
                         LEAKS. DURING THIS OUTAGE, THE A AND B MODULE SPENT SLURRY VALVES
                         WERE REPLACED.
 7/78
       A
       B
       SYSTEM
            97.0
            99.2
            100.0
            100.0
                         11.6
                         11.6
                                                                             77
                                             D-19

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

COMMONWEALTH EDISON: WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER WAS PLAGUED ALL MONTH BY CYCLONE CASING LEAKS. BECAUSE OF THE
                         CYCLONE PROBLEMS AND THE COAL CONSERVATION PROGRAM, THE BOILER WAS ONLY
                         OPERATED SEVENTY-SEVEN HOURS FOR THE MONTH.

                         THE BOILER DOWN TIME WAS USED FOR PREVENTATIVE MAINTENANCE ON THE SCRUBBER.
                         SIX NEW REHEATERS WERE INSTALLED AND A DRAIN VALVE ON THE SPENT SLURRY LINE
                         WAS REPAIRED.

                         A VALVE FAILURE ON THE 1A1 ABSORBER PUMP FORCED THE SCRUBBER FROM THE GAS
                         PATH ONCE DURING THE MONTH.

                         MODULE B EXPERIENCED A LEAKING VENTURI HEADER.

 8/78  A           97.8       100.0                    59.1
       B           99.6       100.0                    59.1
       SYSTEM                                                                744   440

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         CHICAGO ADMIXTURES SPENT MOST OF THEIR TIME OPERATING OUT OF THE THICKENER.
                         THE SCRUBBER WASTE MATERIAL WAS TREATED WITH LIME AND FLY ASH AND HAULED
                         OFF TO AN OFF SITE DISPOSAL AREA.

                         REPAIRS TO THE VENTURI EMERGENCY SPRAY VALVE CAUSED ONE BOILER OUTAGE
                         DURING THE MONTH.

                         A REHEATER FLANGE LEAK WAS RESPONSIBLE FOR FORCING THE UNIT OFF.

                         MODULE A WAS FORCED OFF ONCE DUE TO HIGH VIBRATION OF THE I.D. BOOSTER FAN.
                         THE PROBLEM WAS CORRECTED BY REPACKING THE COUPLING ON THE FAN.

 9/78  A           77.7        95.9                    55.4
       B           77.7        96.0                    55.5
       SYSTEM                                                                720   416

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         CHICAGO ADMIXTURES SPENT MOST OF THEIR TIME OPERATING OUT OF THE THICKENER.
                         THE SCRUBBER WASTE MATERIAL WAS TREATED WITH LIME AND FLY ASH AND HAULED TO
                         AN OFF SITE DISPOSAL AREA.

                         REHEATER TUBE LEAKS, ONE IN MODULE A AND FOUR IN MODULE B, CAUSED ONE
                         BOILER OUTAGE AND CAUSED THE FGO SYSTEM TO BE UNAVAILABLE FOR A TOTAL
                         OF NINETY HOURS. SAMPLES OF THE TUBES HAVE BEEN SUBMITTED TO O.A.D. FOR
                         METALLURGICAL EXAMINATION.

                         A RUPTURED AIR LINE ON A VENTURI PUMP ISOLATION VALVE WOULD NOT ALLOW THE  E
                         VALVE TO GO COMPLETELY CLOSED.

                         WHEN THE A VENTURI PUMP WAS STARTED, A VENTURI SPRAY HOSE RUPTURED.

                         IT WAS DISCOVERED THAT THE MODULE A VENTURI TANK LEVEL PRESSURE SWITCH WAS
                         NOT WORKING PROPERLY.

                         THE PUGMILL ORDERED FOR CHICAGO ADMIXTURES HAS ARRIVED ON SITE. IN OCTOBER,
                         THEY WILL FINISH THE CONVERSION, WHICH WILL ALLOW THE MATERIAL SERVICE
                         MIXER TRUCKS TO BE ELIMINATED.

                         IN OCTOBER, THE THICKENER WILL HAVE TO BE BYPASSED WHILE THE UTILITY DOES
                         MAINTENANCE ON THE RAKE AND REPLACES SOME  LEAKING VALVES.
                                              D-20

-------
                                                  UTILITY FGO SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON:  MILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


10/78  A          100.0       100.0                    35.0
       B          100.0       100.0                    35.0
       SYSTEM                                                                744   261

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         LOW BOILER HOURS WERE DUE TO FOUR OUTAGES CAUSED BY HIGH BEARING METAL
                         TEMPERATURES AND EXCESSIVE VIBRATION IN THE 1-B FORCED DRAFT TAN.

                         THE BOILER DOWN TIME WAS UTILIZED FOR CLEANING AND REPAIR OF THE VENTURI
                         THROAT, SUMP AND SUMP SCREENS, AND INLET BLOCK DAMPERS OF MODULE A, AS
                         WELL AS THE VENTURI AND ABSORBER TANKS AND SCREENS AND ALL ABSORBER SPRAY
                         NOZZLES OF BOTH MODULES.

                         ON INSPECTION, IT WAS DISCOVERED THAT THE B MODULE ABSORBER DEPARTMENTAL
                         DAMPER HAD SLIPPED SOX CLOSED. THE DAMPERS WERE JACKED OPEN AND WELDED
                         IN PLACE.

                         TO CORRECT A HIGH PRESSURE DROP ACROSS THE MODULE B REHEATER, A NEW METHOD
                         WAS EMPLOYED WHEREBY ONLY THE MIDDLE TUBES WERE REMOVED, ALLOWING THE TOP
                         AND BOTTOM TUBES TO BE SEEN AND CLEANED, ELIMINATING THE REMOVAL OF ALL THE
                         TUBES. THIS PROCEDURE CUT OUTAGE TIME FROM ONE OR TWO WEEKS TO TWO DAYS.

11/78  A           96.Z       100.0                    48.3
       B           85.2       100.0                    48.3
       SYSTEM                                                                720   348

       «* PROBLEMS/SOLUTIONS/COMMENTS

                         THE UNIT WAS DOWN THREE TIMES THIS MONTH DUE TO A VENTURI PUMP AND TWO
                         BOOSTER FAN OUTAGES.

12/78  A           65.3       100.0                    64.5
       B           64.5       100.0                    64.5
       SYSTEM                                                                744   480

       *# PROBLEMS/SOLUTIONS/COMMENTS

                         REHEATER TUBE LEAKS CAUSED TWO OUTAGES.

                         THE MODULE B SPENT SLURRY DRAIN WAS REPAIRED.

  1/79  A           83.5       100.0                    61.3
       B           62.2        87.1                    53.4
       SYSTEM                                                                744   456

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE S02 PLANT WAS FORCED OFF TWICE THIS MONTH DUE TO REHEATER TUBE LEAKS.
                         TWO TUBES ON MODULE A AND FOUR TUBES ON MODULE B WERE REPLACED.

                         THE I.D. BOOSTER FAN ON MODULE B WAS FOULED AND HAD TO BE REPLACED.

                         TWO SPECIAL SECTIONS OF VENTURI PIPING, A SIXTEEN TO EIGHT INCH  ECCENTRIC
                         REDUCER AND AN OFFSET TEE WERE PREPARED BY LOCKPORT FABRICATING  AUD  INSTAL-
                         LED THIS MONTH. THE ORIGINAL REDUCER AND TEE HAD BEEN PATCHED AND WELDED SO
                         MANY TIMES THAT THEY WERE BEYOND REPAIR.

  2/79  A           93.0        91.3                    54.2
       B           93.0        91.3                    54.2
       SYSTEM                                                                672   399
                                             D-21

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

COMMONWEALTH EDISON: WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE UNIT WAS FORCED OFF ONCE FOR A MAIN STEAM HEADER LEAK.

 3/79  A          100.0       100.0                    46.0
       B           68.6       100.0                    46.0
       SYSTEM                                                                744   343

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE SYSTEM WAS FORCED OUT TWICE IN FEBRUARY AND FOUR TIMES IN MARCH DUE   E
                         TO A VENTURI HEADER LEAK. A TEN FOOT SECTION OF PIPE WILL HAVE TO BE
                         REPLACED DUE TO EXTENSIVE CORROSION.

                         THE SYSTEM WAS DOWN ONCE FOR A SPRAY HEADER LEAK.

                         MODULE B EXPERIENCED A LEAK IN THE VENTURI DOWNCOMER. A FIVE FOOT SECTION
                         OF THE PIPE WILL HAVE TO BE REPLACED.

 4/79  A
       SYSTEM                                                                720

 5/79  A                                                 . 0
       B                                                 .0
       SYSTEM                                                                744     0

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         UNIT 1 WAS OUT OF SERVICE THE ENTIRE MONTH DUE TO A BOILER OVERHAUL.

                         CHICAGO ADMIXTURES WILL STOCKPILE THE FIXED SLUDGE ON STATION PROPERTY.

 6/79  SYSTEM                                                                720     0

 7/79  SYSTEM                                                                744     0

 8/79  SYSTEM                                                                744     0

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         UNIT 1 WAS OUT OF SERVICE TO REPLACE THE AIR HEATER TUBES, TUBE SHEET AND
                         HOPPERS.  DURING THIS OUTAGE, THE WORN VENTURI SPRAY NOZZLES AND DEMISTERS
                         WERE REPLACED.  WELDING LEAKS AND GENERAL CLEANING OF THE S02 INTERNALS
                         WAS ALSO DONE AT THIS TIME.

                         THE BOILER AND THE SCRUBBER ARE SCHEDULED TO RETURN TO SERVICE OCTOBER 1.
                         1979.

                                                                             720     0

                                                                             744     0

                                                       85.4
                                                       85.4
                                                       85.4                  720   336    336

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         ON NOVEMBER 5, UNIT 1 RETURNED TO SERVICE AFTER A SIX MONTH OUTAGE TO
                         REPLACE THE AIR HEATER TUBES, TUBE SHEET AND HOPPERS.

                         DURING THE OUTAGE, SEVERAL LENGTHS OF VENTURI PIPING HAD TO BE REPLACED
                         WITH NEW RUBBER LINED PIPE.
                                             D-22
9/79
10/79
11/79
SYSTEM
SYSTEM
A
B
SYSTEM


53.3
53.3
53.3


100.0
100.0
100.0

-------
                                                  UTILITY F60 SURVEY:  OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH  EDISON:  WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                SOZ  PART.  HOURS HOURS  HOURS FACTOR

                         THE UNIT DID NOT FORCE THE BOILER OFF AT ANY TIME  DURING NOVEMBER.

13/79  A           77.0        99.5                    57.5
       B           84.9       100.0                    57.8
       SYSTEM      77.0        99.5                    57.5                  744   431    428

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         ON DECEMBER 4, UNIT 1 CAME OFF LINE SO THAT THE AIR HEATER HOPPERS  AND
                         PRECIPITATOR HOPPERS COULD BE EMPTIED OF CARBON CARRY-OVER AND DEBRIS.
                         DURING THIS OUTAGE THE SHOP REPAIRED A LEAK IN THE POND RETURN LINE.

                         ON DECEMBER 10, THE A-MODULE DEVELOPED A SERIOUS STEAM LEAK (25,000 MAKE-
                         UP) IN A LOWER REHEAT BUNDLE.  THE LEAKING BUNDLE  HAD TO BE REMOVED AND
                         REPLACED.  THIS RESULTED IN A TWO DAY FORCED OUTAGE.  LATER IN THE  MONTH
                         THE A-MODULE BLEW ANOTHER REHEATER TUBE FORCING THE BOILER OFF FOR  AN
                         ADDITIONAL 25 HOURS AND 12 MINUTES.

                         THE A-MODULE WAS REMOVED FROM THE GAS PATH ON DECEMBER 29, FOR THREE HOURS
                         TO ALLOW THE MAINTENANCE SHOP TO WELD A LEAKING REHEATER FLANGE.

                         THE S02 PLANT FORCED THE BOILER OFF TWICE THIS MONTH.  TOTAL FORCED OUTAGE
                         TIME ATTRIBUTED TO THE SCRUBBER WAS 54 HOURS AND 39 MINUTES.

 1/80  A           91.0        87.5                    63.0
       B           88.6        84.1                    60.6
       SYSTEM      88.6        84.1                    60.6                  744   536    451

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         THE FIRST SIX DAYS OF JANUARY, UNIT 1 BOILER WAS OFF THE SYSTEM BECAUSE
                         OF A SLAG SCREEN TUBE LEAK.  THE UNIT RETURNED TO  SERVICE ON JANUARY 7.

                         ON JANUARY 16, THE UTILITY HAD TO DERATE UNIT 1 TO 50 MW BECAUSE THE RE-
                         HEATER SECTIONS ON A ANT) B MODULES WERE PLUGGING.   ON JANUARY 17, THE
                         MODULES WERE TAKEN OUT OF THE GAS PATH TO BEGIN REMOVING AND CLEANING THE
                         REHEATER SECTIONS WITH A HIGH PRESSURE (4000 PSD  WATER SPRAY.  UNIT 1
                         BOILER WAS LEFT ON TO PROVIDE STABILITY FOR THE 138 KV SYSTEM.

                         IN THE PAST, ALL 42 BUNDLES CONSISTING OF SEVEN TUBES PER BUNDLE,
                         HAD TO BE TAKEN OUTSIDE TO BE CLEANED ON A CONCRETE SLAB.  IN THIS  CASE
                         SINCE TIME WAS THE MOST IMPORTANT FACTOR, A DIFFERENT APPROACH WAS  USED.
                         ONLY THE MIDDLE SIX BUNDLES ON EACH MODULE WERE REMOVED.  THIS PROVIDED  A
                         LARGE ENOUGH SPACE SO THAT A LANCE WITH AN EXTENSION ON IT COULD BE USED
                         TO CLEAN THE BOTTOM OF THE TWO TOP BUNDLES AND THE TOP OF THE TWO BOTTOM
                         BUNDLES.  THERE ARE DOORS THAT ALLOW EASY ACCESS TO THE TOP AND BOTTOM
                         OF THE REHEATER.  USING THIS METHOD, ONLY 12 OR THE 42 BUNDLES WERE
                         REMOVED.  IN THE PAST, THIS JOB HAS TAKEN AS LONG  AS TWO WEEKS TO
                         COMPLETE.  USING THE NEW METHOD, ALL THE REHEATER  BUNDLES WERE CLEANED IN
                         20 HOURS.

                         THE B-MODULE WAS FORCED OFF LINE ON TWO OTHER OCCASIONS IN JANUARY.  BOTH
                         THESE OUTAGES WERE CAUSED BY THE REHEATER (A COIL  LEAK AND A FLANGE LEAK)
                         TOTALING 18 HOURS AND 24 MINUTES.

 2/80  A           79.7        90.5                    79.7
       B           78.6        89.2                    78.6
       SYSTEM      74.1        84.2                    74.1                  696   613    516

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         SGRU5BER PROBLEMS IN FEBRUARY WERE CAUSED FROM LEAKS IN THE VENTURI SPRAY
                         HEADER.  THESE LEAKS DEVELOP WHERE THE RUBBER LINING INSIDE THE VENTURI
                         PIPING HAS WORN AWAY SO THAT THE BARE METAL IS EXPOSED.  THIS EXPOSED METAL
                                             D-23

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 198*

COMMONWEALTH EDISON: WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  F60   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR

                         IS THEN SUBJECT TO ERROSION/CORROSION.  THE LINING IS MOST LIKELY TO WEAR
                         AT THE WELD HEAD OF THE SPRAY NOZZLE TO THE MAIN HEADER.  ALL THE VENTURI
                         SPRAY PIPING IS BEING REPLACED.

                         TUBE LEAKS IN THE STEAM COIL REHEAT SYSTEM CAUSED SCRUBBER PROBLEMS THIS
                         MONTH.  MODULE A WAS FORCED OUT ONCE AND MODULE B WAS FORCED OUT THREE
                         TIMES.  THESE TUBES WILL BE REPLACED DURING THE NEXT OUTAGE.
 3/80
       A
       A
       SYSTEM
 83.9
 83.9
 83.9
                                               744
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         THE BOILER WAS OUT OF SERVICE FOR ALL OF MARCH DUE TO BOILER TUBE LEAKS IN
                         THE REHEAT SECTION OF THE BOILER.
 4/80
       A
       B
       SYSTEM
100.0
 87.7
 93.9
 71.0
 71.0
 71.4
17.3
17.3
17.3
                                                                             720   175
                                                                        125
       »* PROBLEMS/SOLUTIONS/COMMENTS
                         DURING THE FIRST 15 DAYS OF APRIL THE BOILER WAS OUT OF SERVICE DUE TO
                         TUBE LEAKS IN THE AIR PREHEATER.

                         WHEN ATTEMPTS WERE MADE TO BRING THE BOILER ON LINE ON THE 16 THE
                         B-MODULE OF THE S02 SYSTEM DEVELOPED REHEATER TUBE LEAKS.  THIS CAUSED
                         A FORCED OUTAGE OF 53 HOURS AND 40 MINUTES.

                         WHEN ATTEMPTS WERE MADE TO RETURN THE BOILER TO SERVICE AGAIN, THE AUXIL-
                         IARY LOW PRESSURE GOVENOR DEVELOPED AN OIL LEAK CAUSING A FOUR DAY OUTAGE,
                         FOLLOWED BY ANOTHER REHEATER TUBE LEAK OUTAGE ON THE B MODULE.  THIS
                         OUTAGE LASTED 35 HOURS.  THE UNIT RETURNED TO SERVICE ON APRIL 24 AND
                         WAS AVAILABLE FOR THE REST OF APRIL.
  5/80   SYSTEM

        **  PP.OBLEMS/SOLUTIONS/COMMENTS
                                                           744
                         INFORMATION WAS NOT AVAILABLE FOR THE MONTH OF MAY.
  6/80
        A
        B
        SYSTEM
 86.5
 86.5
 86.5
100.0
100.0
100.0
81.2
81.2
81.2
                                                                             720   584
                                                                                          584
        **  PROBLEMS/SOLUTIONS/COMMENTS
                         THE SCRUBBING SYSTEM FORCED THE BOILER OUT OF SERVICE FROM JUIIE 6 TO
                         JUNE  10.  THE OUTAGE WAS CAUSED BY PLUGGED REHEATERS ON BOTH MODULES.
                         THIS  WAS THE ONLY FORCED OUTAGE EXPERIENCED DURING JUNE.
  7/80
        A
        B
        SYSTEM
 87.8
 87.8
 87.8
 78.3
 78.3
 78.3
55.0
55.0
55.0
                                                                              744   522
                                                                                          409
        **  PROBLEMS/SOLUTIONS/COMMENTS
                         DURING THE MONTH OF JULY THERE WERE NO FORCED SCRUBBER OUTAGES.

                         TWO SLAG  LINE OUTAGES, ONE FORCED DRAFT  FAN AND ONE BOILER  SCREEN  WALL
                         TUBE  OUTAGE OCCURRED.  THIS ACCOUNTED FOR  193 HOURS OF BOILER-RELATED
                         OUTAGE TIME DURING THE MONTH.
                                             D-24

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON:  WILL COUNTY 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR

                         ON NINE OCCASIONS IN JULY THE SCRUBBER WAS BY-PASSED SO THAT THE BOILER
                         COULD CARRY MAXIMUM LOAD (163 MW).  THE UNIT WAS LIMITED TO 135 MW AFTER
                         A RECENT STACK EMISSION TEST.

 6/80  SYSTEM                                                                744

 9/80  SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO INFORMATION WAS AVAILABLE FOR THE MONTHS OF AUGUST AND SEPTEMBER.

10/80  A           69.9       100.0                    60.9
       B           69.9       100.0                    60.9
       SYSTEM      69.9       100.0                    60.9                  744   453    453

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING OCTOBER THERE WAS ONE FORCED OUTAGE DUE TO PROBLEMS WITH THE AB-
                         SORBER RECIRCULATION PUMP ON MODULE B.  DURING THIS OUTAGE THE WALL WASH
                         HEADERS WERE REPLACED ON BOTH MODULES.

                         DURING OCTOBER THE BOILER WAS SHUT DOWN TWICE DUE TO A LACK OF DEMAND.
                         THIS ACCOUNTED FOR APPROXIMATELY 51 HOURS OF DOWN TIME.  ADDITIONAL UNIT
                         OUTAGE TIME WAS DUE TO INTERCEPT VALVE AND AIR HEATER PROBLEMS.

11/80  A           92.4       100.0        83.4        33.0
       B           92.4       100.0        83.4        33.0
       SYSTEM      92.4       100.0        83.4        33.0            -      720   238    238

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT NO MAJOR PROBLEMS WITH THE SCRUBBING SYSTEM WERE
                         ENCOUNTERED DURING NOVEMBER.

12/80  A           77.9       100.0        31.5        31.5
       B           77.9       100.0        31.5        31.5
       SYSTEM      77.9       100.0        31.5        31.5                  744   234    234  20.3

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING DECEMBER AVAILABILITY OF THE FGD SYSTEM WAS LOW DUE TO PLUGGED
                         VENTURI NOZZLES AND HEADER, WHICH HAD TO BE HIGH-PRESSURE JETTED.

 1/81  A           82.4       100.0        80.8        80.8
       B           82.4       100.0        80.8        80.8
       SYSTEM      82.4       100.0        80.8        80.8                  744   601    601

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         DURING JANUARY THE MIST ELIMINATOR TRAY WAS REPLACED ON MODULE A.

 2/81  A           75.4       100.0        68.9        68.9
       B           75.4       100.0        68.9        68.9
       SYSTEM      75.4       100.0        68.9        68.9                  672   463    463  59.3

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING FEBRUARY THE BOILER WAS OUT OF SERVICE APPROXIMATELY 209 HOURS DUE
                         TO TUBE LEAKS.

                         THE SCRUBBING SYSTEM WAS OUT OF SERVICE 164 HOURS DUE  TO CLEANING AND A
                         TWO HOUR INSPECTION.
                                             D-25

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON: MILL COUNTY 1 (COKT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR
3/81 A 70.2 100.0 68.2 68.2
B 70.2 100.0 68.2 68.2
SYSTEM 70.2 100.0 68.2 68.2


744 507 507 63.1
 4/81
       «* PROBLEMS/SOLUTIONS/COMMENTS
                         DURING MARCH DOWNTIME OCCURRED DUE TO MISCELLANEOUS CLEANING TO THE BOILER
                         AND THE SCRUBBER.
A
B
SYSTEM
                   32.9
                   32.9
                   32.9
100.0
100.0
100.0
 32.9
 32.9
 32.9
32.9
32.9
32.9
                                                                      720   237
                                                                                          237  30.1
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         DURING MAY THE SCRUBBING MODULES AND THE SCRUBBER PIPING WERE CLEANED.
                         THIS ACCOUNTED FOR THE OUTAGE TIME DURING THE MONTH.
 5/81  A
       B
       SYSTEM
            59.1
            59.1
            59.1
100.0
100.0
100.0
 51.0
 51.0
 51.0
48.1
48.1
48.1
                                                                             744   358    358  42.7

       «* PROBLEMS/SOLUTIONS/COMMENTS

                         DURING MAY THE BOILER WAS DOWN FOR 11 DAYS FOR A SCHEDULED OUTAGE.

                         IN MAY 41 HOURS OF OUTAGE TIME WAS DUE TO A LACK OF DEMAND.

                         LEAKS IN THE CYCLONE TUBES CAUSED THE SYSTEM TO SHUT DOWN FOR 53 HOURS.

                         TOWARD THE END OF MAY, THE SYSTEM WAS SHUTDOWN FOR 30 HOURS TO PREPARE
                         FOR AN EMISSION TEST.
 6/81  A
       B
       SYSTEM
           100.0
           100.0
           100.0
100.0
100.0
100.0
100.0
100.0
100.0
63.7
63.7
63.7
                                                                             720   458
                                                                                          458  49.4
       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING JUNE NO MAJOR PROBLEMS WERE ENCOUNTERED.
                                             D-26

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 198*
                                           APPENDIX D
                  DESIGN AND PERFORMANCE DATA FOR OPERATIONAL PARTICLE SCRUBBERS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE  EMISSION LIMITATION - NG/J
SOS EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MM
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 *» UNIT DATA - BOILER AND STACK
     BOILER  SUPPLIER
     BOILER  TYPE
     BOILER  SERVICE LOAD
     DESIGN  BOILER FLUE GAS FLOW - CU.M/S
     BOILER  FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 »» FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE  HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE  ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - '/.
     RANGE  MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE  SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE  CHLORIDE CONTENT - 7.

**« PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** FABRIC  FILTER
     NUMSER
     TYPE

 »* ESP
     NUMBER
     TYPE

 ** PARTICLE SCRUBBER
     NUMSER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE  NAME/COMMON NAME
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER  GENERIC MATERIAL
     LINER  SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER  OF CONTACTING ZONES
     LIQUID  RECIRCULATION RATE - LITER/S
     L/G RATIO - LITER/CU.M
               (  .600 LB/MMBTU)
               ( 4.000 LB/MMBTU)
               (****** LB/MMBTU)
MINNESOTA POWER & LIGHT
CLAY BOSWELL
3
COHASSET
MINNESOTA
E
  258.
 1720.
******
 1000
  364
  347
  350
  350
COMBUSTION ENGINEERING
PULVERIZED COAL
BASE
  613.47       (1300000 ACFM)
  123.3        (  254 F)
  213.         (  700 FT)
CONCRETE
    7.9        (  26.0 FT)
COAL
SUBBITUMINOUS
19538.

    9.00
4.8-16.0
   26.00
24.0-28.0
      .92
0.5-1.5
      .01
0.00-0.07
 0
NONE
 0
NONE
 0
NONE
 1
 5/73
IMPINGEMENT TOWER
NP
NR
KREBS ENGINEERS
18.0 X 126.0 X 52.0
STAINLESS STEEL
AUSTENITIC
NONE
N/A
NONE
 1
  714.4
    1.1
               (  8400 BTU/LB)
                7500-9900
                (11340 GPM)
                ( 8.3 GAL/1000ACF)
                                             0-27

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

MINNESOTA POWER & LIGHT: CLAY BOSWELL 3 (CONT.)
     PH CONTROL ADDITIVE
     PRESSURE DROP - KPA
     SUPERFICIAL GAS VELOCITY - M/S
     INLET GAS FLOW RATE - CU.M/S
     INLET GAS TEMPERATURE - C
     SOS REMOVAL EFFICENCY - X
     PARTICLE REMOVAL EFFICIENCY - X
     ENERGY CONSUMPTION - X
                  ALKALINE  FLYASH
                      1.0
                      2.4
                    613.5
                    123.3
                     98.7
                       .8
                     (  4.0  IN-H20)
                     (    8.0 FT/S)
                     (1300000 ACFM)
                     (   254 F)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR
 5/73  SYSTEM
       ** PROBLEMS/SOLUTIONS/COMMENTS

                         SINCE STARTUP IN MAY 1973 SCALING AND PLUGGING HAVE OCCURRED IN NOZZLES,
                         NOZZLE TREES, STRAINERS, ON PUNCH PLATE BAFFLES, IN THE WET/DRY ZONE, AND
                         ON THE FAN AND THE MIST ELIMINATOR.  PLUGGING HAS ALSO RESULTED AS DEPOSITS
                         HAVE FALLEN INTO THE DRAINS AT THE BOTTOM OF THE SCRUBBER.  DUE TO THE
                         CALCIUM-RICH ASH, CHARACTERISTIC OF THE WESTERN COAL BURNED, THE SCALING
                         IS AGGRAVATED.  THE UTILITY HAS CONTROLLED SCALE BY SLOWDOWN OF THE
                         SCRUBBING SYSTEM.  THIS HAS MAINTAINED THE PROCESS CHEMISTRY BELOW SATURA-
                         TION WITH RESPECT TO CALCIUM SULFITE.  A VERY HIGH LEVEL OF MAINTENANCE
                         HAS BEEN MAINTAINED ALSO TO MINIMIZE SCALE ACCUMULATION AND PLUGGING, THIS
                         HAS INCLUDED WASHING OF THE WET FAN WHICH HAS RESULTED IN A STACK MIST
                         PROBLEM.  THE USE OF SOOT BLOWERS IN PLACE OF WASHING WAS ATTEMPTED BUT
                         WAS UNSUCCESSFUL.  THE UTILITY HAS REDUCED THE AMOUNT OF WASHING AND HAS
                         CONSIDERED THE INSTALLATION OF REHEAT OR CONSTRUCTION OF A NEW LOW-VELOCITY
                         STACK.

 10/79  SYSTEM                                                                744

 11/79  SYSTEM                                                                720

 12/79  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO INFORMATION WAS AVAILABLE FOR THE FOURTH QUARTER 1979.

  1/80  SYSTEM                                                                744

  2/80  SYSTEM                                                                696

  3/80  SYSTEM                                                                744

       «* PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT THE SCRUBBER EXPERIENCED NO PROBLEMS DURING THE
                         1ST QUARTER OF 1980.
 4/80  SYSTEM

 5/80  SYSTEM

 6/80  SYSTEM

       **  PROBLEMS/SOLUTIONS/COMMENTS
                                               720

                                               744

                                               720
                         THE UTILITY REPORTED THAT NO SCRUBBER-RELATED OUTAGES OCCURRED DURING THE
                         SECOND QUARTER OF 1980.  DOWN TIME FOR MAINTENANCE WAS NOT REQUIRED SINCE
                         GENERAL MAINTENANCE CAN BE PERFORMED ON THE MINNESOTA POWER AND  LIGHT PAR-
                         TICLE SCRUBBERS WHILE THEY ARE IN SERVICE.
 7/80  SYSTEM

 8/80  SYSTEM
100.0

100.0
100.0

100.0
90.3

78.0
720   650    650  60.2

744   580    580  52.3
                                             D-28

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER 1984

MINNESOTA POWER  & LIGHT:  CLAY BOSWELL 3 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


 9/80  SYSTEM                 100.0       100.0        84.0                  744   625    625  54.8

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO OPERATIONAL PROBLEMS WERE REPORTED FOR THE JULY THROUGH SEPTEMBER
                         PERIOD.
10/80
11/80
12/80
SYSTEM
SYSTEM
SYSTEM
100.0
100.0
100.0
100.0
100.0
100.0
100
100
100
.0
.0
.0
85
81
81
.9
.5
.6
744
720
744
639
587
607
639
587
607
62.3
64.6
60.9
«* PROBLEMS/SOLUTIONS/COMMENTS

1/81
2/81
3/81

SYSTEM
SYSTEM
SYSTEM

100.0
100.0
100.0
THE UTILITY
THE FOURTH
100.0
100.0
100.0
REPORTED THAT
QUARTER 1980.
100
100
100
.0
.0
.0
NO SCRUBBER
94
97
79
.3
.0
.0
PROBLEMS WERE ENCOUNTERED
744
672
744
702
651
585
DURING
702
651
585
69.1
73.2
65.1
       »* PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT NO SCRUBBER-RELATED PROBLEMS MERE ENCOUNTERED
                         DURING THE FIRST QUARTER 1981.

                         DURING MARCH THE BOILER WAS OUT OF SERVICE APPROXIMATELY 159 HOURS TO RE-
                         PAIR STEAM LEAKS AND TO PERFORM MAINTENANCE.

                                                                             720   447    447  50.9

                                                                             744   709    709  79.3

                                                                             720   696    696  75.7

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT NO MAJOR PROBLEMS WERE ENCOUNTERED DURING THE
                         SECOND QUARTER 1981.
4/81 SYSTEM
5/81 SYSTEM
6/81 SYSTEM
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
62.1
95.3
96.7
                                             D-29

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                           APPENDIX D
                  DESIGN AND PERFORMANCE DATA FOR OPERATIONAL PARTICLE SCRUBBERS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY M/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RAN3E CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** FABRIC FILTER
     NUMBER
     TYPE

 ** ESP
     NUMBER
     TYPE

 ** PARTICLE SCRUBBER
     NUMBER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - LITER/CU.M
               (  .600 LB/MMBTU)
               ( 4.000 LB/MMBTU)
               (****** LB/MMBTU)
MINNESOTA POWER * LIGHT
SYL LASKIN
1
AURORA
MINNESOTA
E
  258.
 1720.
******
  116
   62
   57
   58
   58
COMBUSTION ENGINEERING
PULVERIZED COAL
INTERMEDIATE
  141.57       (
  171.1        (
   91.         (
CONCRETE
    3.2
                 300000 ACFM)
                 340 F)
                 300 FT)
COAL
SUBBITUMINOUS
20469.

    9.00
4.8-16.0
   26.70
24.0-28.0
    1.00
0.5-1.5
      .01
0.00-0.07
 0
NONE
 0
NONE
 0
NONE
 1
 6/71
IMPINGEMENT TOWER
NR
NR
KREBS ENGINEERS
34.0 X 18.0 X 23.0
STAINLESS STEEL
AUSTENITIC
NOME
N/A
NONE
 1
  151.2
    1.1
               (  10.5 FT)
               (  8800 BTU/LB)
                7509-9923
               ( 2400 GPM)
               ( 8.3 GAL/1000ACF)
                                             D-30

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER
MINNESOTA POWER * LIGHT: SYL LASKIN 1 (CONT.)

     PH CONTROL ADDITIVE
     PRESSURE DROP - KPA
     SUPERFICIAL GAS VELOCITY - M/S
     INLET GAS FLOW RATE - CU.M/S
     INLET GAS TEMPERATURE - C
     S02 REMOVAL EFFICENCY - X
     PARTICLE REMOVAL EFFICIENCY - X
     ENERGY CONSUMPTION - X
ALKALINE FLYASH
     .6
    2.1
  137.4
  171.1
   •  .0
   97.8
    1.6
(  2.5 IN-H20)
(     7.0 FT/S)
(  291160 ACFM)
(   340 F)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


 6/71  SYSTEM

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         SINCE STARTUP IN JUNE 1971 SCALING AND PLUGGING HAVE OCCURRED IN NOZZLES.
                         NOZZLE TREES, STRAINERS, ON PUNCH PLATE BAFFLES, IN THE WET/DRY ZONE, AND
                         ON THE FAN AND THE MIST ELIMINATOR.  PLUGGING HAS ALSO RESULTED AS DEPOSITS
                         HAVE FALLEN INTO THE DRAINS AT THE BOTTOM OF THE SCRUBBER.  DUE TO THE
                         CALCIUM-RICH ASH, CHARACTERISTIC OF THE WESTERN COAL BURNED, THE SCALING
                         IS AGGRAVATED.  THE UTILITY HAS CONTROLLED SCALE BY SLOWDOWN OF THE
                         SCRUBBING SYSTEM.  THIS HAS MAINTAINED THE PROCESS CHEMISTRY BELOW SATURA-
                         TION WITH RESPECT TO CALCIUM SULFITE.  A VERY HIGH LEVEL OF MAINTENANCE
                         HAS BEEN MAINTAINED ALSO TO MINIMIZE SCALE ACCUMULATION AND PLUGGING, THIS
                         HAS INCLUDED WASHING OF THE WET FAN WHICH HAS RESULTED IN A STACK MIST
                         PROBLEM.  THE USE OF SOOT BLOWERS IN PLACE OF WASHING WAS ATTEMPTED BUT
                         WAS UNSUCCESSFUL.  THE UTILITY HAS REDUCED THE AMOUNT OF WASHING AND HAS
                         CONSIDERED THE INSTALLATION OF REHEAT OR CONSTRUCTION OF A NEW LOW-VELOCITY
                         STACK.
                         THE PROBLEMS AT SYL LASKIN ARE NOT AS SEVERE AS THE PROBLEMS AT CLAY
                         BOSWELL DUE TO THE FACT THAT THE RECYCLE LOOP IS NOT CLOSED TO THE SAME
                         EXTENT.  THE MIST CARRYOVER PROBLEM IS LESS SEVERE OWING TO OPERATION OF
                         THE UNIT AT PARTIAL LOAD RESULTING IN A LOWER STACK VELOCITY.
 10/79  SYSTEM

 11/79  SYSTEM

 12/79  SYSTEM
                             744

                             720

                             744
       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO INFORMATION WAS AVAILABLE FOR THE FOURTH QUARTER 1979.

  1/80  SYSTEM                                                                744

  2/80  SYSTEM                                                                696

  3/80  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT THE SCRUBBER EXPERIENCED NO PROBLEMS DURING THE
                         1ST QUARTER OF 1980.
 4/80  SYSTEM

 5/80  SYSTEM

 6/80  SYSTEM

       »* PROBLEMS/SOLUTIONS/COMMENTS
                             720

                             744

                             720
                         THE UTILITY REPORTED THAT NO SCRUBBER-RELATED OUTAGES OCCURRED DURING THE
                         SECOND QUARTER OF 1980.  DOWN TIME FOR MAINTENANCE WAS NOT REQUIRED SINCE
                         GENERAL MAINTENANCE CAN BE PERFORMED ON THE MINNESOTA POWER AND  LIGHT PAR-
                                             D-31

-------
10/80 SYSTEM
11/80 SYSTEM
12/80 SYSTEM
100.0
100.0
100.0

100.0
100.0

100.0
100.0
.0
24.3
64.1
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

MINNESOTA POWER & LIGHT: SYL LASKIN 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER   FGD    CAP.
                                                                S02  PART. HOURS HOURS   HOURS  FACTOR

                         TICLE SCRUBBERS WHILE THEY ARE IN SERVICE.

 7/80  SYSTEM     100.0       100.0       100.0        56.6                  744   421     421   25.2

 8/80  SYSTEM     100.0       100.0       100.0        19.0                  744   140     140   12.0

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT NO BOILER OR FGD-RELATED PROBLEMS WERE  ENCOUNTER-
                         ED DURING JULY AND AUGUST.  LOW UTILIZATION FACTORS WERE DUE TO A LACK
                         OF POWER DEMAND.

 9/80  SYSTEM     100.0       100.0       100.0         4.4                  720    33      33   1.9

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO SCRUBBER OUTAGES OCCURRED DURING SEPTEMBER.  THE LOW UTILIZATION FACTOR
                         WAS AGAIN THE RESULT OF A LACK OF DEMAND FOR POWER.

                                                                             744     0     744     .0

                                                                             720   175     175   10.2

                                                                             744   477     477   23.4

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT NO SCRUBBER-RELATED PROBLEMS OCCURRED DURING
                         THE FOURTH QUARTER 1980.  LOW UTILIZATION FACTORS WERE CAUSED BY  A LACK
                         OF POWER DEMAND.

 1/81  SYSTEM      78.5       100.0       100.0        78.5                  744   524     524   23.8

       *« PROBLEMS/SOLUTIONS/COMMENTS

                         DURING JANUARY THE BOILER WAS OUT OF SERVICE APPROXIMATELY 160  HOURS  DUE
                         TO A TURBINE STEAM LEAK.  THE BOILER WAS OUT OF SERVICE AN ADDITIONAL 60
                         HOURS DUE TO A LACK OF POWER DEMAND.

 2/81  SYSTEM       5.4       100.0       100.0         5.4                  672    36      36   17.4

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         DURING FEBRUARY THE BOILER REMAINED OFF LINE FOR APPROXIMATELY  708 HOURS
                         TO REPAIR A TURBINE STEAM LEAK.

 3/81  SYSTEM      99.1       100.0       100.0        79.0                  744   588     588   44.8

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         DURING MARCH THE BOILER WAS OUT OF SERVICE SEVEN HOURS TO CLEAN THE ID FANS
                         AND 77 HOURS DUE TO A LACK OF DEMAND.

 4/81  SYSTEM     100.0       100.0       100.0       100.0                  720   720     720   46.0

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING APRIL 10 HOURS OF OUTAGE TIME WAS NECESSARY TO WORK ON THE EXCITER.

 5/81  SYSTEM      64.1       100.0       100.0        64.0                  744   476     476   31.3
                                              0-32

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER 1984

MINNESOTA POWER £ LIGHT:  SYL LASKIN 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGO   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING MAY THE UNIT WAS OUT OF SERVICE 209 HOURS FOR AN OVERHAUL.

                         SYSTEM DOWN TIME WAS NEEDED TO REPAIR A STEAM DRIVEN OIL PUMP.

                         FOLLOWING A TEST THE SYSTEM WAS TAKEN OFF-LINE FOR SANDBLASTING ID FANS.

 6/81  SYSTEM     100.0                                  .0                  720     0      0

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         IN JUNE THE UNIT WAS DOWN DUE TO A LACK OF DEMAND.  DURING THIS PERIOD
                         GENERAL MAINTENANCE WAS PERFORMED.
                                             D-33

-------
UTILITY FGO SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                           APPENDIX D
                  DESIGN AND PERFORMANCE DATA FOR OPERATIONAL PARTICLE SCRUBBERS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MM
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MM
NET UNIT GENERATING CAPACITY WO/FGD - MM
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - V.
     RANGE ASH CONTENT - V.
   •  AVERAGE MOISTURE CONTENT - V.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - V.
     RANGE SULFUR CONTENT - Y.
     AVERAGE CHLORIDE CONTENT - V.
     RANGE CHLORIDE CONTENT - Z

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** FABRIC FILTER
     NUMBER
     TYPE

 ** ESP
     NUMBER
     TYPE

 ** PARTICLE SCRUBBER
     NUMBER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATICN RATE - LITER/S
     L/G RATIO - LITER/CU.M
MINNESOTA POMER & LIGHT
SYL LASKIN
2
AURORA
MINNESOTA
E
  258.
 1720.
******
  116
   62
   57
   58
   58
COMBUSTION ENGINEERING
PULVERIZED COAL
INTERMEDIATE
  141.57       (
  171.1        (
   91.         (
CONCRETE
    3.2
(   .600 LB/MMBTU)
(  4.000 LB/MMBTU)
(****** LB/MMBTU)
  300000 ACFM)
  340 F)
  300 FT)

(  10.5 FT)
COAL
SUBBITUMINOUS
20469.

    9.00
4.8-16.0
   26.70
24.0-28.0
    1.00
0.5-1.5
      .01
0.00-0.07
 0
NONE
 0
NONE
 0
NONE
 1
 6/71
IMPINGEMENT TOWER
NR
NR
KREBS ENGINEERS
34.0 X 18.0 X 23.0
STAINLESS STEEL
AUSTENITIC
NONE
N/A
NONE
 1
  151.2        (
    1.1        (
(   8800 BTU/LB)
 7509-9923
  2400 GPM)
  8.3 GAL/1000ACF)
                                             D-34

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984
MINNESOTA  POWER  & LIGHT:  SYL LASKIN 2 (CONT.)

     PH CONTROL  ADDITIVE
     PRESSURE DROP - KPA
     SUPERFICIAL GAS VELOCITY - M/S
     INLET GAS FLOW RATE  - CU.M/S
     INLET GAS TEMPERATURE - C
     S02 REMOVAL EFFICENCY - X
     PARTICLE REMOVAL EFFICIENCY - X
     ENERGY CONSUMPTION - X
                                               ALKALINE FLYASH
                                                     .6
                                                   2.1
                                                 137.4
                                                 171.1
                                                     .0
                                                  97.8
                                                   1.6
(  2.5 IN-H20)
(     7.0 FT/S)
(  291160 ACFM)
(   340 F)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION
                                                               X REMOVAL   PER  BOILER  FGD   CAP.
                                                               S02  PART. HOURS HOURS  HOURS FACTOR
 6/71  SYSTEM

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         SINCE STARTUP IN JUNE 1971 SCALING AND PLUGGING HAVE OCCURRED IN NOZZLES,
                         NOZZLE TREES> STRAINERSi ON PUNCH PLATE BAFFLES, IN THE WET/DRY ZONE AND
                         ON THE FAN AND THE MIST ELIMINATOR.  PLUGGING HAS ALSO RESULTED AS DEPOSITS
                         HAVE FALLEN INTO THE DRAINS AT THE BOTTOM OF THE SCRUBBER.  DUE TO THE
                         CALCIUM-RICH ASH, CHARACTERISTIC OF THE WESTERN COAL BURNED, THE SCALING
                         IS AGGRAVATED.  THE UTILITY HAS CONTROLLED SCALE BY SLOWDOWN OF THE
                         SCRUBBING SYSTEM.  THIS HAS MAINTAINED THE PROCESS CHEMISTRY BELOW SATURA-
                         TION WITH RESPECT TO CALCIUM SULFITE.  A VERY HIGH LEVEL OF MAINTENANCE
                         HAS BEEN MAINTAINED ALSO TO MINIMIZE SCALE ACCUMULATION AND PLUGGING, THIS
                         HAS INCLUDED WASHING OF THE WET FAN WHICH HAS RESULTED IN A STACK MIST
                         PROBLEM.  THE USE OF SOOT BLOWERS IN PLACE OF WASHING WAS ATTEMPTED BUT
                         WAS UNSUCCESSFUL.  THE UTILITY HAS REDUCED THE AMOUNT OF WASHING AHD HAS
                         CONSIDERED THE INSTALLATION OF REHEAT OR CONSTRUCTION OF A NEW LOW-VELOCITY
                         STACK.
                         THE PROBLEMS AT SYL LASKIN ARE NOT AS SEVERE AS THE PROBLEMS AT CLAY
                         BOSWELL DUE TO THE FACT THAT THE RECYCLE LOOP IS NOT CLOSED TO THE SAME
                         EXTENT.  THE MIST CARRYOVER PROBLEM IS LESS SEVERE OWING TO OPERATION
                         OF THE UNIT AT PARTIAL LOAD RESULTING IN A LOWER STACK VELOCITY.

       SYSTEM                                                                744

       SYSTEM                                                                720

       SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO INFORMATION WAS AVAILABLE FOR THE FOURTH QUARTER 1979.

       SYSTEM                                                                744

       SYSTEM                                                                696

       SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT THE SCRUBBER EXPERIENCED NO PROBLEMS DURING THE
                         1ST QUARTER OF 1980.
10/79

11/79

12/79
 1/80

 2/80

 3/80
 4/80

 5/80

 6/80
      SYSTEM

      SYSTEM

      SYSTEM

      ** PROBLEMS/SOLUTIONS/COMMENTS
              720

              744

              720
                         THE UTILITY REPORTED THAT NO SCRUBBER-RELATED OUTAGES OCCURRED DURING THE
                         SECOND QUARTER OF 1980.  DOWN TIME FOR MAINTENANCE WAS NOT REQUIRED SINCE
                         GENERAL MAINTENANCE CAN BE PERFORMED ON THE MINNESOTA POWER AND LIGHT PAR-
                                             D-35

-------
10/80 SYSTEM
11/80 SYSTEM
12/80 SYSTEM
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
26.3
76.0
70.8
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

MINNESOTA POWER & LIGHT: SYL LASKIN 2 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR

                         TICLE SCRUBBERS WHILE THEY ARE IN SERVICE.

 7/80  SYSTEM     100.0       100.0       100.0        24.5                  744   182    182  12.3

       «* PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER DID NOT OPERATE MOST OF JULY DUE TO A BOILER INSPECTION.  NO
                         PROBLEMS WERE ENCOUNTERED WITH THE FGD UNIT.

 8/80  SYSTEM     100.0       100.0       100.0        15.0                  744   115    115   5.0

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER OPERATED ONLY 115 HOURS DURING AUGUST DUE TO A LACK OF DEMAND.

 9/80  SYSTEM     100.0       100.0       100.0         5.2                  720    39     39   2.4

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORT THAT NO SCRUBBER OUTAGES OCCURRED DURING SEPTEMBER.
                         THE LOW UTILIZATION FACTOR RESULTED FROM A LACK OF DEMAND FOR
                         POWER.

                                                                             744   195    195  15.0

                                                                             720   547    547  37.2

                                                                             744   527    527  34.9

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT NO SCRUBBER-RELATED PROBLEMS WERE ENCOUNTERED
                         DURING THE FOURTH QUARTER.

 1/81  SYSTEM     100.0       100.0       100.0        45.3                  744   337    337  23.8

       ** PROBLEMS/SOLUTIOHS/COMMENTS

                         DURING JANUARY THE BOILER WAS OUT OF SERVICE APPROXIMATELY 407 HOURS DUE
                         TO A LACK OF POWER DEMAND.

 2/81  SYSTEM     100.0       100.0       100.0        97.4                  672   653    653  28.5

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING FEBRUARY THE UTILITY REPORTED THAT NO SCRUBBER-RELATED PROBLEMS
                         OCCURRED.

 3/81  SYSTEM     100.0                                  .0                  744     0      0     .0

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING MARCH THE BOILER WAS OUT OF SERVICE TO FIND THE CAUSE OF A TURBINE
                         VIBRATION.

 4/81  SYSTEM      88.2       100.0       100.0        56.4                  720   406    406  26.9

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING APRIL 229 HOURS OF DOWN TIME WAS DUE TO A LACK OF DEMAND.

                         THE UNIT WAS DOWN 109 HOURS FOR A BEARING CHECK AND REPAIR DUE TO HIGH
                         VIBRATION.

 5/81  SYSTEM      94.1       100.0       100.0        55.0                  744   409    409  28.7
                                             D-36

-------
                                                  UTILITY F6D SURVEY:  OCTOBER 1983 - SEPTEMBER 198
-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER
                                           APPENDIX D
                  DESIGN AND PERFORMANCE DATA FOR OPERATIONAL PARTICLE SCRUBBERS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
SOS EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MM
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - V.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANSE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE
     SUPPLIER
     INLET FLUE GAS CAPACITY - CU.M/S
     INLET FLUE GAS TEMPERATURE - C
     PRESSURE DROP - KPA
     PARTICLE REMOVAL EFFICENCY -7.

 ** ESP

 ** PARTICLE SCRUBBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - LITER/CU.M
     PH CONTROL ADDITIVE
     PRESSURE DROP - KPA
     INLET GAS FLOW RATE - CU.M/S
MONTANA-DAKOTA UTILITIES
LEWIS 4 CLARK
1
SIDNEY
MONTANA
E
   86.         (
  430.         (
******
     200 LB/MMBTU)
     000 LB/MMBTU)
               I****** LB/MMBTU)
   50
   55
   50
   52
   55
COMBUSTION ENGINEERING
PULVERIZED COAL
BASE
  153.37
  215.6
   76.
CARBON STEEL
    4.4
 (  325000 ACFM)
 (  420 F)
 (  250 FT)

 (  14.5 FT)
COAL
LIGNITE
15003.

    7.80
7.2-9.3
   36.20
34.3-38.2
     .61
0.3-1.4
     .03
******
MULTICLONE
WESTERN PREC.
  106.2
  176.7
     .4
   85.7
 (  6450 BTU/LB)
  6200-6700
DIVISION, JOY
 ( E25000 ACFM)
 (  350 F)
 (  1. IN-H20)
VENTURI TOWER
VARIABLE-THROAT/BOTTOM-ENTRY LIQUID DISTRIBUTION
FLOODED DISC SCRUBBER
RESEARCH-COTTRELL
10.5 DIA X 27.0
CARBON STEEL
AISI 1110
ORGANIC
GLASS FLAKE-FILLED POLYESTER
NONE
  212.6
    1.7
LIMESTONE
    3.2
  148.0
 ( 3374 GPM)
 (13.0 GAL/1000ACF)

 (13.0 IN-H20)
 ( 313730 ACFM)
                                             D-38

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER

MONTANA-DAKOTA UTILITIES:  LEWIS & CLARK 1 (CONT.)

     INLET  GAS TEMPERATURE - C                    215.6        (   420 F)
     ENERGY CONSUMPTION -  7.                         3.6
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


10/79  SYSTEM                                                                720

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         DURING A SCHEDULED BOILER OUTAGE GENERAL SCRUBBER MAINTENANCE WAS
                         PERFORMED.

11/79  SYSTEM                                                                720

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         DURING NOVEMBER THE SCRUBBER WAS TEMPORARILY BYPASSED TO ALLOW FOR REPAIRS
                         NECESSITATED BY A LEAK IN THE FLOODED DISC SCRUBBER.

12/79  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT NO SCRUBBER PROBLEMS OCCURRED DURING DECEMBER.

 1/80  SYSTEM                                                                744

 2/80  SYSTEM                                                                696

 3/80  SYSTEM                                                                744

       *« PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THE JANUARY THROUGH MARCH PERIOD THE SCRUBBER WAS AVAILABLE MORE
                         THAN 95X OF THE TIME.

                         THE EROSION PROBLEM MENTIONED DURING NOVEMBER CONTINUED.  SECTIONS OF THE
                         EXTERIOR CARBON STEEL LINED COLUMN WALL SUPPORTING THE FLOODED DISC WERE
                         ERODING, FILLING THE INNER CHAMBER WITH SLURRY AND ULTIMATELY RENDERING THE
                         DISC MOVEMENT MECHANISM INOPERATIVE.  THE UTILITY HAS MANAGED TO KEEP THE
                         SCRUBBER OPERATING AS A STOP-GAP MEASURE BETWEEN UNIT SHUTDOWNS BY INSERT-
                         ING A GARDEN HOSE IN THE COLUMN HOLES AND CONTINUALLY FLUSHING THE INNER
                         CHAMBER.  THE UTILITY HAS HAD SOME SUCCESS IN OTHER EROSION AREAS BY
                         MAKING REPAIRS WITH A HASTELLOY MATERIAL.  PLANS ARE BEING MADE TO JACKET
                         THE ENTIRE DISC SUPPORT COLUMN WITH HASTELLOY G.

 4/80  SYSTEM                                                                720

 5/80  SYSTEM                                                                744

 6/80  SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER WAS SHUT DOWN FOR TWO WEEKS IN MAY.

                         CREWS INSPECTING THE SCRUBBING SYSTEM DISCOVERED THAT THE NINE FOOT SCRUB-
                         BER LINER SECTION AT THE BOTTOM OF THE CYCLONIC MIST ELIMINATOR WAS SEVERE-
                         LY ERRODED.  THE LINER HAS LASTED THREE YEARS.  THE UTILITY CONSIDERS THIS
                         A NORMAL MAINTENANCE PROBLEM.  AT ONE TIME LINERS IN THIS SECTION WERE RE-
                         PLACED EVERY SIX MONTHS.  REPLACEMENT WORK ON THE LATEST FAILURE IS EXPECT-
                         ED TO BEGIN BY JULY 21.

                         THE ENTIRE SCRUBBER COLUMN SUPPORTING THE DISC WHICH WAS ERODING AS REPORT-
                         ED DURING THE PREVIOUS TWO QUARTERS HAS BEEN CLAD WITH HASTELLOY G.
                                             D-39

-------
UTILITY FGD SURVEY: OCTOBER 1933 - SEPTEMBER 1984

MONTANA-DAKOTA UTILITIES: LEWIS t CLARK 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR

                         THE UTILITY REPORTED THAT THE SCRUBBER HAS EXPERIENCED PLUGGING AT WET/DRY
                         INTERFACES WITHIN THE STRUCTURE.  IT APPEARS THAT THIS IS RELATED TO COAL
                         SULFUR CONTENT.  WHEN THE SULFUR CONTENT IS RELATIVELY HIGH (0.7 TO l.OX AT
                         LEWIS AND CLARK) THE PLUGGING DOES NOT OCCUR.  LIMESTONE IS ADDED AS RE-
                         QUIRED TO PREVENT THE OCCURRANCE OF LOW PH LEVELS.  WHEN THE SULFUR CONTENT
                         FALLS TO THE 0.3X RANGE THE PH RISES AS A RESULT OF THE ALKALINE CONSTITU-
                         ENTS IN THE FLY ASH UNTIL SOFT SCALE PLUGGING RESULTS.  THE UTILITY HAS
                         CONSIDERED ADDING ACID TO STABILIZE THE PH WHEN THE COAL SULFUR CONTENT
                         DROPS.

 7/80  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING JULY TWO WEEKS OF DOWN TIME WAS NECESSARY TO REPLACE THE MIST
                         ELIMINATOR LINER.

                         THE PROBLEM WITH THE FLOODED DISC BUILDUP MENTIONED EARLIER CONTINUED.
                         THE UTILITY PERFORMS THE NECESSARY REPAIRS IN THREE TO FOUR HOURS WHEN
                         THIS OCCURS.

 fl/80  SYSTEM                                                                744

 9/80  SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT NO MAJOR PROBLEMS WERE ENCOUNTERED WITH SCRUBBING
                         OPERATIONS DURING THE MONTHS OF AUGUST AND SEPTEMBER.

10/80  SYSTEM                                                                744

11/80  SYSTEM                                                                720

12/80  SYSTEM                                                                744

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT NO MAJOR PROBLEMS WERE ENCOUNTERED WITH THE
                         SCRUBBING OPERATIONS DURING THE OCTOBER THROUGH DECEMBER PERIOD.

                         SCRUBBING OPERATIONS WERE SHUTDOWN FOR ONE WEEK DURING THE LAST PART OF
                         OCTOBER FOR A SCHEDULED MAINTENANCE OVERHAUL AND NO PROBLEMS WERE FOUND.

 1/81  SYSTEM                                                                744

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT NO MAJOR SCRUBBER PROBLEMS OCCURRED DURING
                         JANUARY.

 2/81  SYSTEM                                                                672

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         ON FEBRUARY 10 THE SCRUBBER WAS SHUT DOWN FOR FIVE HOURS DUE TO A PLUGGED
                         VENTURI.

                         ON FEBRUARY 23 A LEAK WAS DISCOVERED ON THE OUTER WALL OF THE SCRUBBER,
                         LOCATED BELOW THE VENTURI.  THE LEAK WAS TEMPORARILY REPAIRED FROM THE
                         OUTSIDE WILE THE SCRUBBER REMAINED ON-LINE.  THE UTILITY PUNNED TO REPAIR
                         THE LEAK DURING THE SCHEDULED OUTAGE IN MARCH.

 3/81  SYSTEM                                                                744
                                             D-40

-------
                                                  UTILITY FGD SURVEY:  OCTOBER  1983 -  SEPTEMBER  1984

MONTANA-DAKOTA UTILITIES:  LEWIS t CLARK 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE  AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER   FGD    CAP.
                                                                S02  PART.  HOURS HOURS  HOURS FACTOR


       «* PROBLEMS/SOLUTIONS/COMMENTS

                         THE SCHEDULED OUTAGE PERIOD WAS HELD FROM MARCH 3  TO 15.  DURING THIS TIME
                         THE VENTURI AND SUMP WERE INSPECTED.  THE LEAK DISCOVERED EARLIER IN FEB-
                         RUARY WAS REPAIRED CORRECTLY.
                                              D-41

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                           APPENDIX D
                  DESIGN AND PERFORMANCE DATA FOR OPERATIONAL PARTICLE SCRUBBERS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY H/FGD - MM
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BCILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RAN3E SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RAN3E CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** PARTICLE SCRUBBER
     HUM3ER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - LITER/CU.M
     PH CONTROL ADDITIVE
     PRESSURE DROP - KPA
     INLET GAS FLOW RATE - CU.M/S
     INLET GAS TEMPERATURE - C
     502 REMOVAL EFFICENCY - 7.
     PARTICLE REMOVAL EFFICIENCY - 7.
     ENERGY CONSUMPTION - 7.
PACIFIC POWER & LIGHT
DAVE JOHNSTON
4
GLENROCK
WYOMING
C
   90.         (  .210 LB/MMBTU)
  215.         (  .500 LB/MMBTU)
******         (****** LB/MMBTU)
*****
  330
  327
  330
  330
COMBUSTION ENGINEERING
PULVERIZED COAL
BASE
  707.85       (1500000 ACFM)
  132.2        (  270 F)
   76.         (  250 FT)
NR
*******        (***** FT)
               (   7430 BTU/LB)
                5000-9000
COAL
SUBBITUMINOUS
17282.

   12.00
******
   26.00
******
     .50
******
     .04
******
 3
 4/72
VENTURI TOWER
VARIABLE-THROAT/TOP-ENTRY PLUMB BOB
N/A
GE ENVIRONMENTAL SERVICES
CARBON STEEL
AISI 1110
ORGANIC
POLYESTER
N/A
  409.5
    1.7
               (  6500 6PM)
               (13.0 GAL/1000ACF)
LIME/ALKALINE FLYASH
    2.5
  327.5
  135.0
   40.0
   99.7
     .9
               (10.0 IN-H20)
               (  694000 ACFM)
               (   275 F)

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

PACIFIC  POWER  &  LIGHT:  DAVE JOHNSTON 4 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE  AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


 4/72  SYSTEM

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         SINCE STARTUP IN APRIL 1972, THE SCRUBBING UNIT HAS EXPERIENCED MAJOR
                         SCALING PROBLEMS.  HARD GYPSUM SCALE ACCUMULATES IN THE SCRUBBER VESSELS
                         AND PIPING.  THE USE OF LIME FOR PH CONTROL AND LIGNO SULFONATE TO ALTER
                         THE HARDNESS OF DEPOSITS IMPROVED THE SCALE PROBLEM.  FRESH WATER WASHING
                         HAS BEEN REQUIRED TO FLUSH ASH AND SCALE DEPOSITS FROM THE SCRUBBER
                         VESSELS.
                         SOLIDS BUILDUP HAS OCCURRED AT THE WET-DRY INTERFACE AND IN THE BLEED AND
                         RECYCLE LINES.  THE UTILITY IS USING AN ADDITIVE (HEXAMATA PHOSPHATE) IN
                         WHICH THE EFFECTS HAVE YET TO BE DETERMINED.
                         ADDITIONAL OPERATING PROBLEMS EXPERIENCED SINCE STARTUP INCLUDE ERROSION
                         IN THE RECYCLE PUMP AND "SILTING" DURING SHUTDOWN.
                         THE UTILITY CHARACTERIZED THE AVAILABILITY AS BEING DEPENDENT ON THE
                         AMOUNT OF SLOWDOWN AND FRESH WATER IRRIGATION THAT ARE EMPLOYED.

10/79  SYSTEM                                                                7*4

11/79  SYSTEM                                                                720

12/79  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO INFORMATION MAS AVAILABLE FOR THE FOURTH QUARTER 1979.

 1/80  SYSTEM                                                                744

 2/80  SYSTEM                                                                696

 3/80  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO INFORMATION WAS AVAILABLE FOR THE FIRST QUARTER OF 1980.

 4/80  SYSTEM                                                                720

 5/80  SYSTEM                                                                744

 6/80  SYSTEM                                                                720

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT NO MAJOR PROBLEMS OCCURRED DURING THE SECOND
                         QUARTER OF 1960.

 7/80  SYSTEM                                                                744

 8/80  SYSTEM                                                                744

 9/80  SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO INFORMATION WAS AVAILABLE FOR THE THIRD QUARTER  OF 1980.

10/80  SYSTEM                                                                744

11/80  SYSTEM                                                                720

12/80  SYSTEM                                                                744
                                             D-43

-------
UTILITY FGD SURVEY: OCTOBER 1933 - SEPTEMBER 198*

PACIFIC POWER & LIGHT: DAVE JOHNSTON 4 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                SOS  PART. HOURS HOURS  HOURS FACTOR


       *» PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT NO MAJOR PROBLEMS WERE ENCOUNTERED WITH THE
                         SCRUBBING OPERATIONS DURING THE OCTOBER THROUGH DECEMBER PERIOD.

 1/81  SYSTEM                                                                744

 2/61  SYSTEM                                                                672

 3/81  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO INFORMATION WAS AVAILABLE FOR THE FIRST QUARTER 1981.
                                             D-44

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                           APPENDIX D
                  DESIGN AND PERFORMANCE DATA FOR OPERATIONAL PARTICLE SCRUBBERS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE  EMISSION LIMITATION - NG/J
502 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 »* UNIT DATA - BOILER AND STACK
     BOILER  SUPPLIER
     BOILER  TYPE
     BOILER  SERVICE LOAD
     DESIGN  BOILER FLUE GAS FLOW - CU.M/S
     BOILER  FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 «* FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE  MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE  SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RAN3E  CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 «* ESP
     TYPE

 »* PARTICLE SCRUBBER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE  NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER  GENERIC MATERIAL
     LINER  SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER  OF CONTACTING ZONES
                  POTOMAC ELECTRIC POWER
                  DICKERSON
                  DICKERSON
                  MARYLAND
                  ******
                  ******
                  ******
                  ******
                   1348
                    190
                    183
                  *****
                    190
               («***** LB/MMBTU)
               (****** LB/MMBTU)
               (****»* LB/MMBTU)
                  COMBUSTION ENGINEERING
                  PULVERIZED COAL
                  ******
                  ********       (******* ACFM)
                  *******        (**** F)
                    213.         (  700 FT)
                  CONCRETE
                  *******        (***** FT)
                                 (  11700 BTU/LB)
                                  ******
COAL
******
27214.

   14.00
******
********
6.0-7.0
    2.00
******
********
******
                  COLD SIDE
                   0/78
                  VENTURI TOWER
                  VARIABLE-THROAT/TOP-ENTRY PLUMB BOB
                  N/A
                  CARBON STEEL
                  AISI 1110
                  NR
                  NR
                  NONE
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  7. REMOVAL    PER  BOILER   FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS  FACTOR
10/79  SYSTEM

11/79  SYSTEM

12/79  SYSTEM
100.0

 96.0

100.0
       83.6

       80.1

       87.4
744   622    622

720   601    577

744   650    650
                                             D-45

-------
UTILITY FGD SURVEYS OCTOBER 1983 - SEPTEMBER 1984

POTOMAC ELECTRIC POWER: DICKERSON 1 (CONT. )
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  '/. REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THIS PERIOD ONLY ONE SCRUBBER RELATED OUTAGE OCCURRED.  THE OUTAGE
                         WAS FOR AN ID FAN INSPECTION WHICH LASTED ONE DAY.

 1/80  SYSTEM     100.0       100.0                   100.0                  744   744    744

 2/80  SYSTEM      94.3        95.8                    94.3                  696   685    656

 3/80  SYSTEM     100.0       100.0                   100.0                  744   744    744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THE FIRST QUARTER OF 1980 ONLY ONE SCRUBBER OUTAGE OCCURRED.  IN
                         FEBRUARY OUTAGE TIME WAS NECESSARY TO REPAIR A SLURRY RECYCLE LINE LEAK.

 4/80  SYSTEM                                                                720

 5/80  SYSTEM                                                                744

 6/80  SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DICKERSON 1 SCRUBBER DEPENDABILITY FACTORS WERE UNAVAILABLE FOR THE APRIL-
                         JUNE PERIOD.  THESE FIGURES SHOULD BE AVAILABLE BY THE THIRD QUARTER
                         REPORT.  THE UTILITY REPORTED THAT THE FGD SYSTEM OPERATED THE ENTIRE
                         SECOND QUARTER WITH ESSENTIALLY 100X AVAILABILITY.  NO SCRUBBER-RELATED
                         PROBLEMS WERE REPORTED.

 7/80  SYSTEM                                                                744

 8/80  SYSTEM                                                                744

 9/80  SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED HAVING MINIMAL SCRUBBING SYSTEM PROBLEMS DURING THE
                         JULY-SEPTEMBER PERIOD.

                         THE BOILER CAPACITY WAS REDUCED DURING PART OF THE PERIOD DUE TO A LINING
                         FAILURE IN THE SCRUBBING SYSTEM PIPING.

 10/80  SYSTEM                                                                744

 11/80  SYSTEM                                                                720

 12/80  SYSTEM                                                                744

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THE OCTOBER THROUGH DECEMBER PERIOD THE BOILER WAS OPERATED AT A
                         60X (110 MW) CAPACITY  DUE TO A LINING FAILURE IN THE SCRUBBING SYSTEM
                         PIPING.

 1/81  SYSTEM      97.0        88.1        91.9       82.1                  744   694    611

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING JANUARY APPROXIMATELY 53 HOURS OF OUTAGE TIME WAS CAUSED BY PROBLEMS
                         WITH THE RECYCLE LINE  REDUCER AND THE BLEED LINE SPOOL.

 2/81  SYSTEM         .0                                   .0                  672     0      0
                                              D-46

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 198*

POTOMAC ELECTRIC POWER:  DICKERSON 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


 3/81  SYSTEM        .0                                  .0                  744     0      0

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DICKERSON UNITS 1, 2 AND 3 WERE SHUT DOWN SO THAT THE STACK AND THE COMMON
                         DUCT LEADING TO THE STACK COULD BE RELINED WITH PLASITE.  UNIT 1 WAS SHUT
                         DOWN ON JANUARY 31 AND REMAINED DOWN THROUGHOUT FEBRUARY AND MARCH DUE TO
                         THESE REPAIRS.

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                           APPENDIX D
                  DESIGN AND PERFORMANCE DATA FOR OPERATIONAL PARTICLE SCRUBBERS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGO - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** ESP
     TYPE

 ** PARTICLE SCRUBBER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRACE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
                  POTOMAC ELECTRIC POWER
                  DICKERSON
                  DICKERSON
                  MARYLAND
                  ******
                  ******
                  ******
                  ******
                   1348
                    190
                    183
                  *****
                    190
               (****** LB/MMBTU)
               (****** LB/MMBTU)
               (****** LB/MMBTU)
                  COMBUSTION ENGINEERING
                  PULVERIZED COAL
                  ******
                  ********       (******* ACFM)
                  *******        (**** F )
                    213.          (  700 FT)
                  CONCRETE
                  *******        (***** FT)
                                 (  11700 BTU/LB)
                                  ******
COAL
******
27214.

   14.00
******
********
6.0-7.0
    2.00
******
********
******
                  COLD SIDE
                   0/78
                  VENTURI TOWER
                  VARIABLE-THROAT/TOP-ENTRY PLUMB BOB
                  N/A
                  CARBON STEEL
                  AISI 1110
                  NR
                  NR
                  NONE
                   2
 	PERFORMANCE DATA	
 PERIOD  MODULE  AVAILABILITY  OPERABILITY RELIABILITY UTILIZATION  7. REMOVAL    PER   BOILER   FGD    CAP.
                                                                S02   PART. HOURS  HOURS   HOURS  FACTOR
 10/79   SYSTEM

 11/79   SYSTEM

 12/79   SYSTEM
100.0

 96.4

100.0
       97.0

       88.9

      100.0
744   722    722

720   664    640

744   744    744
                                              0-48

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

POTOMAC ELECTRIC POWER:  DICKERSON 2 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         A ONE DAY OUTAGE OCCURRED, DUE TO A FAN LINING PROBLEM.  NO OTHER
                         SCRUBBER UNIT PROBLEMS MERE ENCOUNTERED DURING THE PERIOD.

 1/80  SYSTEM      95.*        96. 4                    95.4                  744   736    710

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         IN JANUARY THE SCRUBBER WAS DOWN FOR THREE HOURS TO REPAIR A SLURRY
                         RECYCLE LINE LEAK.

                         31 HOURS OF THE OUTAGE TIME IN JANUARY WAS NECESSARY TO REPAIR A RECYCLE
                         PUMP.

 2/80  SYSTEM     100.0       100.0                   100.0                  696   696    696

 3/80  SYSTEM      96.9        96.9                    96.9                  744   7**    721

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         IN MARCH THE SCRUBBER WAS DOWN FOR A SCRUBBER LINING WARRANTY INSPECTION.
                         NO REPAIR WORK WAS NECESSARY.

 4/80  SYSTEM                                                                720

 5/80  SYSTEM                                                                744

 6/80  SYSTEM                                                                720

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         DICKERSON 2 SCRUBBER DEPENDABILITY FACTORS WERE UNAVAILABLE FOR THE APRIL-
                         JUNE PERIOD.  THESE FIGURES SHOULD BE AVAILABLE BY THE THIRD QUARTER
                         REPORT.  THE UTILITY REPORTED THAT THE FGD SYSTEM OPERATED THE ENTIRE
                         SECOND QUARTER WITH ESSENTIALLY 100X AVAILABILITY.  NO SCRUBBER-RELATED
                         PROBLEMS WERE REPORTED.

 7/80  SYSTEM                                                                744

 8/80  SYSTEM                                                                744

 9/80  SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY HAS NOT FIGURED OUT THE DEPENDABILITY FIGURES AS YET.

                         THE UTILITY REPORTED HAVING MINIMAL SCRUBBING SYSTEM PROBLEMS DURING THE
                         JULY-SEPTEMBER PERIOD.

                         THE BOILER CAPACITY WAS REDUCED DURING PART OF THE PERIOD DUE TO A  LINING
                         FAILURE IN THE SCRUBBING SYSTEM PIPING.

 10/80  SYSTEM                                                                744

 11/80  SYSTEM                                                                720

 12/80  SYSTEM                                                                744
                                             D-49

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

POTOMAC ELECTRIC POWER: DICKERSON 2 (CONT. )
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THE OCTOBER THROUGH DECEMBER PERIOD THE BOILER WAS OPERATED AT A
                         60X (110 MW) CAPACITY DUE TO A LINING FAILURE IN THE SCRUBBING SYSTEM
                         PIPING.

 1/81  SYSTEM      96.9        92.8       100.0        81.9                  744   654    607

 2/81  SYSTEM        .0                                  .0                  672     0      0

 3/81  SYSTEM        .0                                  .0                  744     0      0

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         OICKERSON UNITS 1, 2 AND 3 WERE SHUT DOWN SO THAT THE STACK AND THE COMMON
                         DUCT LEADING TO THE STACK COULD BE RELINED WITH PLASITE.  UNIT 2 WAS SHUT
                         DOWN ON JANUARY 31 AND REMAINED DOWN THROUGHOUT FEBRUARY AND MARCH DUE TO
                         THESE REPAIRS.
                                             D-50

-------
                                UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 198*
                         APPENDIX D
DESIGN AND PERFORMANCE DATA FOR OPERATIONAL PARTICLE SCRUBBERS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW
POTOMAC ELECTRIC POWER
DICKERSON
3
DICKERSON
MARYLAND
******
****** (******
668. ( 1.600
****** ( ******
548
190
178
182
95






LB/MMBTU)
LB/MMBTU )
LB/MMBTU)





 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS  FLOW  -  CU.M/S
     BOILER FLUE GAS  TEMPERATURE  -  C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT -  J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT  - 7.
     AVERAGE SULFUR CONTENT  - 7.
     RANGE SULFUR CONTENT -  7.
     AVERAGE CHLORIDE CONTENT - 7.
     RAN3E CHLORIDE CONTENT  - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** FABRIC FILTER
     NUMBER
     TYPE

 ** PARTICLE SCRUBBER
     NUMBER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     L/G RATIO -  LITER/CU.M
     PRESSURE DROP -  KPA
     INLET GAS FLOW RATE - CU.M/S
     INLET GAS TEMPERATURE - C
     PARTICLE REMOVAL EFFICIENCY  -  7.
     ENERGY CONSUMPTION - 7.
                              COMBUSTION ENGINEERING
                              PULVERIZED COAL
                              BASE
                                278.42       ( 590000 ACFM)
                                126.1        ( 259 F)
                                213.         ( 700 FT)
                              CONCRETE
                              *******        (***** FT)
                              COAL
                              BITUMINOUS
                              27214.

                                 14.00
                              ******
                              ********
                              6.0-7.0
                                  2.00
                              ******
                              ********
(  11700 BTU/LB)
 ******
                                0
                              NONE
                                0
                              NONE
                                1
                                9/75
                               VENTURI TOWER
                               VARIABLE-THROAT/TOP-ENTRY  PLUMB BOB
                               N/A
                               GE ENVIRONMENTAL  SERVICES
                               CARBON STEEL
                               AISI 1110
                               ORGANIC
                               FIBER-REINFORCED  POLYESTER
                               NONE
                                  2.7         (20.0  GAL/1000ACF)
                                  2.7         (11.0  IN-H20)
                                139.2         (  295000  ACFM)
                                126.1         (   259 F)
                                 99.0
                                  2.1
                            D-51

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

POTOMAC ELECTRIC POWER: DICKERSON 3 (CONT. )
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER   FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS  FACTOR


 9/73  SYSTEM                                                                720

10/73  SYSTEM                                                                744

11/73  SYSTEM                                                                720

12/73  SYSTEM                                                                744

 1/74  SYSTEM                                                                744

       ** PROSLEMS/SOLUTIONS/COMMENTS

                         PROBLEMS DURING THIS PERIOD RANGED FROM CORROSION LEAKS IN EXPANSION  JOINTS
                         TO PROBLEMS IN MATERIAL HANDLING EQUIPMENT, FEEDING AND SLAKING  OF MGO,
                         PLUGGING IN THE MGO MIX TANK AND SUCTION LINES TO THE MGO MAKE-UP PUMPS.

 2/74  SYSTEM                                                                672

 3/74  SYSTEM                                                                744

 4/74  SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         MAINTENANCE AND MODIFICATIONS WERE PERFORMED ON THE SYSTEM.  THE MAJOR
                         SYSTEM REVISION MADE DURING THIS PERIOD WAS THE ADDITION OF A PRE-MIX TANK
                         IN THE MGO SYSTEM.

 5/74  SYSTEM                                                                744

 6/74  SYSTEM                                                                720

 7/74  SYSTEM                                                                744

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         LIMITED OPERATION OCCURRED BECAUSE THE UTILITY DID NOT HAVE ACCESS TO THE
                         EPA CALCINING FACILITY AT THE ESSEX CHEMICAL COMPANY SULFURIC ACID PLANT.
                         BY THE END OF JUNE 1974, ALL THE MGO AT DICKERSON HAD BEEN USED  AND A SILO
                         PLUS THREE CARS WERE FULL OF MGS03.

 8/74  SYSTEM                                                                744           a7

 9/74  SYSTEM                                                                720

10/74  SYSTEM                                                                744

11/74  SYSTEM                                                                720

12/74  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THIS PERIOD THE SYSTEM GENERALLY OPERATED AT 75 PERCENT OF THE
                         DESIGN GAS FLOW.

 1/75  SYSTEM                                                                7^

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         PROBLEMS DEVELOPED IN THE BUCKET ELEVATOR TRANSPORTING THE MGS03 FROM THE
                         DRYER TO THE STORAGE SILO.

 2/75  SYSTEM                                                                672
                                             D-52

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

POTOMAC  ELECTRIC POWER:  DICKERSON 3 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


 3/75  SYSTEM                                                                744

 4/75  SYSTEM                                                                720

 5/75  SYSTEM                                                                744

 6/75  SYSTEM              .                                                 720

 7/75  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         UNIT NO. 3 WAS TAKEN OUT OF SERVICE FOR AN 8 TO 12 WEEK TURBINE OVERHAUL.
                         THE SCRUBBER WAS INSPECTED, MAINTENANCE AND MODIFICATIONS WERE MADE.

 8/75  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE FGO SYSTEM CONSISTS OF A SINGLE, TWO-STAGE SCRUBBER/ABSORBER, WHICH
                         INCORPORATES AN ADJUSTABLE-THROAT VENTURI SCRUBBER FOR PARTICULATE REMOVAL
                         AND A SECOND STAGE ABSORBER WITH A FIXED VENTURI TO REMOVE S02.  THE LIQUOR
                         STREAMS FOR BOTH STAGES ARE SEPARATE AND OPERATE IN A CLOSED-LOOP MODE.
                         UNTIL MID-1975 THE MAGNESIUM SULFITE GENERATED WAS TRANSFERRED TO AN EPA
                         FINANCED FACILITY AT THE ESSEX CHEMICAL COMPANY SULFURIC ACID MANUFACTURING
                         PLANT IN RUMFORD, RHODE ISLAND WHERE MAGNESIUM OXIDE WAS REGENERATED AND
                         S02 FROM THE REGENERATION PROCESS WAS CONVERTED TO SULFURIC ACID.  THE
                         RUMFORD FACILITY HAS SINCE BEEN CLOSED DOWN.

                         CONSTRUCTION WAS COMPLETED IN AUGUST AND THE SYSTEM STARTED UP IN SEPTEMBER
                         1973.  DURING INTERMITTENT OPERATIONS FOR SHAKEDOWN THROUGH JANUARY 1974,
                         THE SYSTEM'S LONGEST CONTINUOUS RUN WAS 271 HOURS.  THE SYSTEM HAS RE-
                         STARTED FROM JULY THROUGH DECEMBER 1974, AND AGAIN ON AUGUST 11, 1975, FOR
                         APPROXIMATELY 87 HOURS.

                         FGD UNIT OUTAGES WERE CAUSED PRIMARILY BY PIPE AND PUMP CORROSION AND
                         MAJOR TURBINE OVERHAUL OF THE BOILER.  PARTICULATE AND S02 REMOVAL
                         EFFICIENCY GUARANTEES WERE CORROBORATED DURING OPERATIONAL PHASES.

                         THE FGD SYSTEM WAS RESTARTED IN AUGUST.  STEAM WAS LOST TO THE MGO MIX
                         TANK, RESULTING IN A VERY MOIST PRODUCT FROM THE CENTRIFUGE.  CAKING IN THE
                         DRYER OCCURRED.  AT THIS POINT, THE UTILITY DECIDED TO TEST ONLY THE FIRST-
                         STAGE OF THE SCRUBBING SYSTEM, TAKING GAS AHEAD OF THE PRECIPITATOR.  FGD
                         OPERATION AT DICKERSON TERMINATED AT THIS POINT.

                         THE REMAINING SUPPLY OF MAGNESIUM OXIDE, ABOUT 100 TONS (10 DAYS), HAS
                         BEEN DEPLETED, AND THE DICKERSON UNIT HAS BEEN TERMINATED AS A FGD SYSTEM.

 9/75  SYSTEM                                                                720

10/75  SYSTEM                                                                744

11/75  SYSTEM                                                                720

12/75  SYSTEM                                                                744

 1/76  SYSTEM                                                                744

 2/76  SYSTEM                                                                696

 3/76  SYSTEM                                                                744

 4/76  SYSTEM                                                                720
                                             0-53

-------
UTILITY FGO SURVEY: OCTOBER 1933 - SEPTEMBER 1984

POTOMAC ELECTRIC POWER: DICKERSON 3 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


 5/76  SYSTEM                                                                744

 6/76  SYSTEM                                                                720

 7/76  SYSTEM                                                                744

 8/76  SYSTEM                                                                744

 9/76  SYSTEM                                                                720

10/76  SYSTEM                                                                744

11/76  SYSTEM                                                                720

12/76  SYSTEM                                                                744

 1/77  SYSTEM                                                                744

 2/77  SYSTEM                                                                672

 3/77  SYSTEM                                                                744

 4/77  SYSTEM                                                                720

 5/77  SYSTEM                                                                744

 6/77  SYSTEM                                                                720

 7/77  SYSTEM                                                                744

 8/77  SYSTEM                                                                744

 9/77  SYSTEM                                                                720

10/77  SYSTEM                                                                744

11/77  SYSTEM                                                                720

12/77  SYSTEM                                                                744

 1/78  SYSTEM                                                                744

 2/78  SYSTEM       38.0         38.0                    38.0                  672   672     252

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THERE  HAVE BEEN MANY MAINTENANCE PROBLEMS AND PROBLEMS WITH  LINER FAILURES.
                         SINCE  SHIFTING FROM S02 TO PARTICULATE SCRUBBING ONLY, PLUGGING PROBLEMS
                         HAVE NOT OCCURRED.  LOW PH HAS CAUSED CORROSION WHICH WAS AGGRAVATED BY
                         PARTICULATE ERROSION.  THE UTILITY WILL PROBABLY RELINE WITH A FLAKE GLASS
                         TYPE LINER.  NO CHEMICALS (E.G. LIME) ARE ADDED TO THE CIRCULATING LIQUOR
                         FOR FH BALANCE.

                         OUTAGE TIME WAS CAUSED BY LEAK REPAIRS IN SLURRY PIPING.

 3/78  SYSTEM       21.0         22.0                    21.0                  744   717     156

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         OUTAGE TIME WAS DUE TO RUBBER LINING FAILURE  IN THE RECYCLE  PUMP  DISCHARGE
                         LINE.

 4/78  SYSTEM       80.7         79.8                    76.4                  720   689     550
                                              D-54

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

POTOMAC  ELECTRIC POWER:  DICKERSON 3 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  F6D   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         26 HOURS OF OUTAGE TIME MERE DUE TO SMALL LEAKS IN PIPING.

 5/78  SYSTEM      8*.5        82.7                    74.0                  744   666    551

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         A LEAK OCCURRED IN A MIST ELIMINATOR DRAIN.

                         THERE MAS A LEAK IN A BLEED LINE FOR THE SCRUBBER RECYCLE CIRCUIT.

                         OUTAGE TIME MAS REQUIRED FOR BLEED LINE REPLACEMENT.

 6/78  SYSTEM     100.0        90.1                    68.7                  720   549    495

 7/78  SYSTEM     100.0          .0                      .0                  744    16      0

       »» PROBLEMS/SOLUTIONS/COMMENTS

                         THE VENTURI SCRUBBER HAD AN AVAILABILITY OF 100X FOR JUNE AND JULY.  THE
                         ONLY VENTURI OUTAGE TIME WAS IN JUNE.  THE OUTAGE TIME WAS REQUIRED TO
                         TIE IN EQUIPMENT COMMON TO THE NEW UNIT AND UNIT 3.

                         THE BOILER WAS DOWN IN JULY FOR AN OVERHAUL.

                         THE REASON VENTURI HOURS CAN BE LOWER THAN BOILER HOURS WHEN THE VENTURI
                         HAS A 100X AVAILABILITY IS BECAUSE THE VENTURI IS NOT OPERATED UNDER LOW
                         LOAD CONDITIONS.

 8/78  SYSTEM                                                                744

 9/78  SYSTEM                                                                720

10/78  SYSTEM                                                                744

11/78  SYSTEM                                                                720

12/78  SYSTEM                                                                744

 1/79  SYSTEM                                                                744

 2/79  SYSTEM                                                                672

 3/79  SYSTEM                                                                744

 4/79  SYSTEM                                                                720

 5/79  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         SCRUBBER OUTAGE HOURS SINCE SEPTEMBER 1978  (I.E. SEPTEMBER 19V8 THROUGH
                         MAY 30, 1979) TOTAL 140.  THE UTILITY INDICATED THAT IT IS NO LONGER ALLOW-
                         ABLE TO BYPASS THE SCRUBBER WHEN PROBLEMS OCCUR, CLEANING THE PARTICULATE
                         MATTER SOLELY WITH THE ESP.  THE UTILITY MUST DROP THE BOILER LOAD SO THE
                         UNIT REMAINS IN COMPLIANCE.
                         THERE HAVE BEEN HO PROBLEMS REPORTED FOR THE LAST  FEW MOUTHS.  THE UTILITY
                         IS KEEPING AHEAD OF PROBLEMS WITH A CONSCIENTIOUS  INSPECTION AND  MAINTEN-
                         ANCE PROGRAM.

 6/79  SYSTEM                                                                720

 7/79  SYSTEM                                                                744
                                             D-55

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

POTOMAC ELECTRIC POWER: DICKERSON 3 (CONT. )
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER   FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS  FACTOR


 8/79  SYSTEM                                                                744

 9/79  SYSTEM                                                                720

10/79  SYSTEM                  98.6                    95.4                  744   720    710

       #* PROBLEMS/SOLUTIONS/COMMENTS

                         A TEN HOUR OUTAGE OCCURRED FOR REPAIRS OF A LEAD LINE LEAK.

11/79  SYSTEM                  95.2                    88.8                  720   672    640

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         IN NOVEMBER, 8 HOURS OUTAGE TIME WAS REQUIRED TO REPAIR A LEAK IN A
                         RECYCLE LINE.

12/79  SYSTEM                  96.1                    93.5                  744   724    696

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         AN OUTAGE FOR GENERAL INSPECTION TOOK PLACE DURING DECEMBER.

 1/80  SYSTEM      78.7        88.2                    78.7                  744   664    586

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING JANUARY THE SCRUBBER WAS DOWN TO REPAIR THE FLAKEGLASS LINING.

 2/80  SYSTEM      100.0       100.0                   100.0                  696   696    696

 3/80  SYSTEM      100.0       100.0                   100.0                  744   744    744

       «* PROBLEMS/SOLUTIONS/COMMENTS

                         DURING FEBRUARY AND MARCH THE SCRUBBER OPERATED WITH NO MAJOR PROBLEMS.

 4/80  SYSTEM                                                                720

 5/80  SYSTEM                                                                744

 6/80  SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE UNIT 3 SCRUBBER EXPERIENCED SOME DOWN TIME DURING THE APRIL-JUNE  PERIOD
                         AS A RESULT OF THE CONTINUING DETERIORATION OF THE SCRUBBER  FLAKEGLASS
                         LINIIJG.  THE UTILITY REPORTED THAT MAINTENANCE CREWS ARE PATCHING OLD
                         PATCHES.  A STUDY WILL BEGIN IN LATE JULY TO ESTABLISH THE OPTIMUM  LINER
                         MATERIAL AND APPLICATION STRATEGY FOR THE UNIT 3 SCRUBBING SYSTEM.

 7/80  SYSTEM                                                                744

 8/80  SYSTEM                                                                744

 9/80  SYSTEM                                                                720

       ** PR03LEMS/SOLUTIONS/COMMENTS

                         THE UTILITY HAS NOT FIGURED OUT THE DEPENDABILITY FIGURES AS YET.

                         THE UTILITY REPORTED HAVING MINIMAL SCRUBBING SYSTEM PROBLEMS DURING  THE
                         JULY-SEPTEMBER PERIOD.
                                              D-56

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
POTOMAC  ELECTRIC POWER:  DICKERSON 3 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                502  PART. HOURS HOURS  HOURS FACTOR

                         THE BOILER CAPACITY WAS REDUCED TO 1/2 LOAD DURING PART OF THE PERIOD DUE
                         TO THE NECESSARY PATCHING OF THE SCRUBBER LINING.  THE UTILITY IS PRESENTLY
                         STUDYING THE POSSIBILITY OF REPLACING THE FLAKEGUSS LINER WITH A RUBBER
                         LINER.
10/80  SYSTEM

11/80  SYSTEM

12/80  SYSTEM

       ** PROBLEMS/SOLUTIONS/COMMENTS
                                                          744

                                                          720

                                                          744
                         DURING THE OCTOBER THROUGH DECEMBER PERIOD THE BOILER WAS OPERATED AT A
                         60X (110 MW) CAPACITY DUE TO A LINING FAILURE IN THE SCRUBBING SYSTEM
                         PIPING.

                         UNIT 3 WILL BE SHUTDOWN ON FEBRUARY 2, 1981 TO REPLACE THE FLAKEGLASS
                         LINING.
 1/81  SYSTEM

 2/81  SYSTEM

 3/81  SYSTEM
96.8

  .0

  .0
                               96.9
97.5
            94.2

              .0

              .0
744

672

744
723

  0

  0
701

  0

  0
       *« FROBLEMS/SOLUTIONS/COMMENTS
                         DICKERSON UNITS 1, 2 AND 3 WERE SHUT DOWN SO THAT THE STACK AND THE COMMON
                         DUCT LEADING TO THE STACK COULD BE RELINED WITH PLASITE.  UNIT 3 WAS SHUT
                         DOWN ON JANUARY 30 AND REMAINED DOWN THROUGHOUT FEBRUARY AND MARCH DUE TO
                         THESE REPAIRS.
                                             D-57

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                           APPENDIX D
                  DESIGN AND PERFORMANCE DATA FOR OPERATIONAL PARTICLE SCRUBBERS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW
PUBLIC SERVICE OF COLORADO
ARAPAHOE
4
DENVER
COLORADO
D
43.
******
******
*****
112
109
*****
112

( .100
(******
(******






LB/MMBTU)
LB/MMBTU )
LB/MMBTU )





 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - '/.
   .  AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER

 ** FABRIC FILTER
     NUMBER
     TYPE

 ** ESP
     NUMBER

 ** PARTICLE SCRUBBER
     NUMBER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     L/G RATIO - LITER/CU.M
     PH CONTROL ADDITIVE
     PRESSURE DROP - KPA
     SUPERFICIAL GAS VELOCITY - M/S
     INLET GAS FLOW RATE - CU.M/S
******
PULVERIZED COAL
******
  245.39
  148.9
******
NR
*******
(  520000 ACFM)
(300 F)
(**** FT)

(***** FT)
COAL 1 [50X]
SUBBITUNINOUS; BITUMINOU
23609.
               (  10150 BTU/LB)
                ******
   10.90
******
   12.45
******
     .80
0.6-1.0; NR
     .01
******
 0
NONE
 1
 9/73
PACKED TOWER
MOBILE BED PACKING
TURBULENT CONTACT ABSORBER
AIR CORRECTION DIVISION, UOP
CARBON STEEL
AISI 1110
ORGANIC
NATURAL RUBBER
STAINLESS STEEL
 3
    7.5        (56.0 GAL/1000ACF)
ALKALINE FLYASH
    3.0        (12.0 IN-H20)
    3.4        (   11.0 FT/S)
  245.4        ( 520000 ACFM)
                                             D-58

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER

PUBLIC  SERVICE  OF  COLORADO:  ARAPAHOE * (COST.)

     INLET GAS  TEMPERATURE - C                    151.7        (   305  F)
     S02  REMOVAL EFFICENCY - X                     30.0
     PARTICLE REMOVAL EFFICIENCY - X               93.0
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART.  HOURS HOURS  HOURS FACTOR


 9/77  SYSTEM

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         SINCE STARTUP IN SEPTEMBER 1977 SCALING AND PLUGGING AT THE WET/DRY ZONE,
                         ON THE FIRST STAGE GRIDS, AND IN THE REHEATERS HAVE BEEN THE MOST PROMINENT
                         PROBLEM AREAS CHARACTERIZED BY THIS SYSTEM.  VARIOUS CHEMICAL ADDITIVES
                         HAVE BEEN TESTED FOR CONTROL OF SCALING, INCLUDING PHOSPHATED ESTERS,  BUT
                         WITHOUT SIGNIFICANT IMPROVEMENT.  SLOWDOWN IS MAINTAINED AT A HIGH LEVEL
                         TO CHECK THE BUILDUP OF SALTS BUT, OTHER THAN FOR  TESTING PURPOSES, NO
                         CHEMICAL CONTROL METHOD HAS BEEN USED TO CONTROL SCALE ACCUMULATION.
                         OTHER OPERATING EXPERIENCES INCLUDE WEAR AND PERIODIC REPLACEMENT OF THE
                         MOBILE BALLS, EROSION OF LINING AND CORROSIVE FAILURE OF REHEATERS.  THE
                         EROSION AND LINING FAILURE HAVE NOT BEEN A SERIOUS PROBLEM EXCEPT IN THE
                         RECIRCULATING PUMPS.

10/79  SYSTEM                                                                74*

11/79  SYSTEM                                                                720

12/79  SYSTEM                                                                7*4

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         DURING" THE FOURTH QUARTER REHEATER FAILURES OCCURRED.

                         LEAKAGE IN THE INLINE STEAM TUBES HAS BEEN ENCOUNTERED.  CORROSION
                         IS KNOWN TO OCCUR AFTER LEAKS ARE EXPERIENCED.

                         THE PRIMARY PROBLEM WITH THE SYSTEM IS THE INABILITY TO ISOLATE MODULES.
                         IF A PROBLEM OCCURS NO MODULE MAINTENANCE CAN BE PERFORMED UNLESS THE
                         UNIT LOAD IS CUT BACK OR THE UNIT IS SHUT DOWN.

 1/80  SYSTEM                                                                74*

 2/80  SYSTEM                                                                696

 3/80  SYSTEM                                                                7*4

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE MODULE ISOLATION PROBLEMS CONTINUED THROUGH THE FIRST QUARTER OF 1980.
                         USE OF THE CARBON STEEL DAMPERS HAS BEEN ABANDONED.  THE PROGRAM FOR RE-
                         PLACING THE DAMPERS HAS BEEN SUSPENDED INDEFINITELY.  THE UNIT IS SHUTDOWN
                         WHEN MAJOR SCRUBBER PROBLEMS OCCUR.

                         REHEATER STEAM TUBE LEAKS ARE STILL CAUSING PROBLEMS.  THE SIX STEAM COILS
                         ON THIS IN-LINE REHEAT SYSTEM, TWO OF WHICH ARE 316SS AND FOUR OF WHICH
                         ARE CARBON STEEL, ARE EXPERIENCING CORROSION PROBLEMS.  A SOLUTION TO THE
                         PROBLEM HAS NOT YET BEEN DETERMINED.

                         IN FEBRUARY THE UTILITY REPLACED THE SCRUBBER BALLS AND GRIDS.  THE OLD
                         BALLS WERE REPLACED WITH THE NEW HOLLOW HARD PLASTIC-WALLED BALLS WITH
                         NOTCHED SEAMS.  THE GRIDS WERE ORIGINALLY  316L SS, CERAMIC, POLYPROPYLENE,
                         AND RUBBER LINED CARBON STEEL, BUT HAVE BEEN REPLACED WITH 317L SS GRIDS.

                         THE SCRUBBERS OPERATED CONTINUOUSLY THROUGHOUT THE QUARTER EXCEPT  FOR THE
                         BALL AND GRID REPLACEMENT DOWNTIME.

 4/80  SYSTEM                 100.0                   100.0                  720   720    720
                                             D-59

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

PUBLIC SERVICE OF COLORADO: ARAPAHOE 4 ICONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                502  PART. HOURS HOURS  HOURS FACTOR


 5/80  SYSTEM                 100.0                   100.0                  744   744    744

 6/80  SYSTEM                 100.0                   100.0                  720   720    720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         BOTH BOILER AND SCRUBBERS OPERATED THE ENTIRE APRIL-JUNE PERIOD.

                         THE ISOLATION DAMPERS ARE STILL EFFECTIVELY INOPERABLE AND A REPLACEMENT
                         PLAN AS YET HAS NOT BEEN REESTABLISHED.

                         THE UTILITY REPORTED THAT THE REHEATER TUBE LEAK PROBLEM CONTINUED THROUGH
                         THE SECOND QUARTER.  THE TUBES WILL BE ENTIRELY REPLACED WITH NEW 316L SS
                         BUNDLES DURING THE NEXT SCHEDULED OUTAGE IN NOVEMBER AND DECEMBER.  DURING
                         THE SECOND QUARTER MORE TUBES WERE BUNKED OFF AFTER STEAM LEAKS OCCURRED.
                         TO DATE ROUGHLY SOX OF THE TUBES ARE SEALED OFF AND ARE OUT OF SERVICE
                         BECAUSE OF LEAKS THAT OCCURRED OVER THE PAST MONTHS.

 7/80  SYSTEM     100.0       100.0       100.0       100.0                  744   744    744

 8/80  SYSTEM     100.0       100.0       100.0       100.0                  744   744    744

 9/80  SYSTEM     100.0       100.0       100.0       100.0                  720   720    720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER AND SCRUBBERS OPERATED ACCEPTABLY DURING THE JULY-SEPTEMBER PER-
                         IOD.  NO PLANS HAVE BEEN MADE TO REPAIR THE ISOLATION DAMPERS.  THE FAULTY
                         REHEATER TUBES WILL BE REPLACED DURING THE SCHEDULED OUTAGE NOW SET FOR THE
                         FIRST THREE WEEKS OF DECEMBER.

 10/80  SYSTEM                                                                744

 11/80  SYSTEM                                                                720

 12/80  SYSTEM                                                                744

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THE OCTOBER THROUGH DECEMBER PERIOD THE REHEATER TUBES WERE NOT RE-
                         PLACED AND THE UNIT IS OPERATING WITHOUT REHEAT UNTIL THE NEXT SCHEDULED
                         OUTAGE PERIOD IN FEBRUARY 1981.

                         NO MAJOR SCRUBBER RELATED PROBLEMS WERE ENCOUNTERED, EXCEPT THE REPLACE-
                         MENT OF THE DISCHARGE VALVE ON THE RECIRCULATION PUMP.

 1/81  SYSTEM                                                                744

 2/81  SYSTEM                                                                672

 3/81  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THE SCHEDULED FOUR WEEK OUTAGE STARTING JANUARY 30 AND ENDING FEBRU-
                         ARY 24, TWO NEW A-SIDE REHEATER BUNDLES WERE INSTALLED.  THE UNIT WAS THEN
                         RESTARTED.

                         THE UNIT HOWEVER HAD TO BE SHUT DOWN ON FEBRUARY 24 ONLY AFTER OPERATING  3
                         HOURS DUE TO OPERATOR ERROR.  THE BOOSTER FAN WAS RESTARTED WITHOUT ITS OIL
                         BEARING COOLING SYSTEM.  CONSEQUENTLY, THE FAN BEARINGS WERE DAMAGE AND THE
                         BOOSTER FAN HAD TO BE SHUT DOWN.  THE UTILITY HAS SINCE REPAIRED THE FAN
                         SHAFT BUT STILL AWAITS FOR THE REPAIRED FAN BEARINGS BEFORE THE UNIT CAN  BE
                                             D-60

-------
                                                  UTILITY  FGD  SURVEY:  OCTOBER  1983  - SEPTEMBER  1984

PUBLIC  SERVICE  OF  COLORADO:  ARAPAHOE  4 (CONT.)
	PERFORMANCE  DATA	
PERIOD MODULE  AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER   BOILER   FGD    CAP.
                                                                SOS   PART.  HOURS HOURS   HOURS  FACTOR

                         RESTARTED.
                                             D-61

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                           APPENDIX D
                  DESIGN AND PERFORMANCE DATA FOR OPERATIONAL PARTICLE SCRUBBERS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 «* UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M
               (   .100 LB/MMBTU)
               (**#*** LB/MMBTU)
               (****** LB/MMBTU)
PUBLIC SERVICE OF COLORADO
CHEROKEE
1
DENVER
COLORADO
D
   43.
******
******
  710
  115
  100
  105
  102
BABCOCK * WILCOX
PULVERIZED COAL
******
  245.39       ( 520000 ACFM)
  146.1        ( 295 F)
******
NR
*******
               (**** FT)
               (***** FT)
  **  FUEL DATA
      FUEL TYPE
      FUEL GRADE
      AVERAGE HEAT CONTENT - J/G
      RANGE HEAT CONTENT - BTU/LB
      AVERAGE ASH CONTENT - 7.
      RANGE ASH CONTENT - 7.
      AVERAGE MOISTURE CONTENT - V.
      RANGE MOISTURE CONTENT - 7.
      AVERAGE SULFUR CONTENT - 7.
      RANGE SULFUR CONTENT - 7.
      AVERAGE CHLORIDE CONTENT - 7.
      RANGE CHLORIDE CONTENT - 7.

 ***  PARTICLE CONTROL

  **  MECHANICAL COLLECTOR
      NUMBER

  **  FABRIC FILTER
      NUMBER
      TYPE

  **  ESP
      NUMBER

  **  PARTICLE SCRUBBER
      NUMBER
      INITIAL START-UP DATE
      GENERIC TYPE
      SPECIFIC TYPE
      TRADE NAME/COMMON NAME
      SUPPLIER
      SHELL GENERIC MATERIAL
      SHELL SPECIFIC MATERIAL
      LINER GENERIC MATERIAL
      LINER SPECIFIC MATERIAL
      GAS CONTACTING DEVICE TYPE
      NUNcER OF CONTACTING ZONES
      L/G RATIO - LITER/CU.M
      PH CONTROL ADDITIVE
      PRESSURE DROP - KPA
      SUPERFICIAL GAS VELOCITY - M/S
      INLET GAS FLOW RATE - CU.M/S
COAL
BITUMINOUS
23493.

   12.50
9.4-12.5
   11.30
******
     .65
******
     .01
******
               (  10100 BTU/LB)
                ******
 0
NONE
 1
 6/73
PACKED TOWER
MOBILE BED PACKING
TURBULENT CONTACT ABSORBER
AIR CORRECTION DIVISION, UOP
CARBON STEEL
AISI 1110
ORGANIC
NATURAL RUBBER
STAINLESS STEEL
 3
    7.5        (56.0 GAL/1000ACF)
ALKALINE FLYASH
    3.2        (13.0 IN-H20)
    3.4        (
                                                   164.4
                   11.0 FT/S)
               ( 348400 ACFM)
                                             D-62

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER 1984

PUBLIC SERVICE OF COLORADO:  CHEROKEE 1 (CONT.)

     INLET GAS TEMPERATURE - C                    146.1        (   295  F)
     S02 REMOVAL EFFICEHCY - X                     16.0
     PARTICLE REMOVAL EFFICIENCY - X               97.0
     ENERGY CONSUMPTION - X                         4.3
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART.  HOURS HOURS  HOURS FACTOR


 6/73  SYSTEM

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         SINCE STARTUP IN JUNE 1973 SCALING AND PLUGGING AT THE MET/DRY ZONE,
                         ON THE FIRST STAGE GRIDS, AND IN THE REHEATERS HAVE BEEN THE MOST PROMINENT
                         PROBLEM AREAS CHARACTERIZED BY THIS SYSTEM.  VARIOUS CHEMICAL ADDITIVES
                         HAVE BEEN TESTED FOR CONTROL OF SCALING, INCLUDING PHOSPHATED ESTERS,  BUT
                         WITHOUT SIGNIFICANT IMPROVEMENT.  SLOWDOWN IS MAINTAINED AT A HIGH LEVEL
                         TO CHECK THE BUILDUP OF SALTS BUT, OTHER THAN FOR  TESTING PURPOSES NO
                         CHEMICAL CONTROL METHOD HAS BEEN USED TO CONTROL SCALE ACCUMULATION.
                         OTHER OPERATING EXPERIENCES INCLUDE WEAR AND PERIODIC REPLACEMENT OF THE
                         MOBILE BALLS, EROSION OF LINING AND CORROSIVE FAILURE OF REHEATERS.  THE
                         EROSION AND LINING FAILURE HAVE NOT BEEN A SERIOUS PROBLEM EXCEPT IN THE
                         RECIRCULATING PUMPS.

10/79  SYSTEM                                                                744

11/79  SYSTEM                                                                720

12/79  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THE PERIOD ID FAN FAILURES HAVE OCCURRED DUE TO EROSION FROM THE
                         FLYASH.

                         THE ISOLATION DAMPER HAS BEEN A PROBLEM DUE TO FREEZE UPS MAKING IT
                         INOPERATIVE.

                         REHEATER FAILURES HAVE OCCURRED DUE TO PLUGGING OF THE HOT AIR INJECTION
                         STEAM COILS.

                         THE SCRUBBER EXIT DUCTWORK WILL BE REPAIRED TEMPORARILY WITH A SPRAY ON
                         FIBERGLASS-LIKE MATERIAL.

 1/80  SYSTEM                 100.0                   100.0                  744   744    744

 2/80  SYSTEM                 100.0                   100.0                  696   696    696

 3/80  SYSTEM                 100.0                   100.0                  744   744    744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE SCRUBBERS OPERATED CONTINUOUSLY THROUGHOUT THE FIRST QUARTER OF 1980.

                         THE ISOLATION DAMPERS HAVE NOT CAUSED ANY  PROBLEMS BECAUSE MODULE
                         ISOLATION WAS NOT REQUIRED DURING THE PERIOD.

                         THE FANS ARE STILL EXPERIENCING EROSION PROBLEMS.

                         IN MARCH A BOILER/SCRUBBER OVERHAUL BEGAN.  DURING THIS TIME THE CARBON
                         STEEL ISOLATION DAMPERS WILL BE REPLACED WITH 316 SS.  THE NEU FANS
                         WILL BE INSTALLED IN THE OLD HOUSINGS.  THE NEW HIGH STRENGTH CAREON STEEL
                         FANS WILL BE EQUIPPED WITH REPLACABLE CHROMIUM ALLOY WEAR PLATE BLADE
                         TIPS.

 4/80  SYSTEM                                                                720

 5/80  SYSTEM                                                                744
                                             D-63

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 198
-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER
                                           APPENDIX D
                  DESIGN AND PERFORMANCE DATA FOR OPERATIONAL PARTICLE SCRUBBERS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MM
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY M/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MM
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RAN3E CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 *» MECHANICAL COLLECTOR
     NUMBER

 ** FABRIC FILTER
     NUMBER
     TYPE

 ** ESP
     NUMBER

 »* PARTICLE SCRUBBER
     NUMBER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NU113ER OF CONTACTING ZONES
     L/G RATIO - LITER/CU.M
     PH CONTROL ADDITIVE
     PRESSURE DROP - KPA   -
     SUPERFICIAL GAS VELOCITY - M/S
     S02 REMOVAL EFFICENCY - 7.
               (   .100 LB/MMBTU)
               (****** LB/MMBTU)
               («***** LB/MMBTU)
PUBLIC SERVICE OF COLORADO
CHEROKEE
4
DENVER
COLORADO
D
   43.
******
******
  710
  375
  350
  375
  356
COMBUSTION ENGINEERING
PULVERIZED COAL
******
  717.29       (1520000 ACFM)
               ( 275 F)
               (**** FT)
  135.0
******
NR
*******
COAL
BITUMINOUS
23*93.

   12.50
9.4-12.5
   11.30
******
      .65
******
      .01
******
               (***** FT)
               ( 10100 BTU/LB)
                ******
 0
NONE
 4
 7/74
PACKED TOWER
MOBILE BED PACKING
TURBULENT CONTACT ABSORBER
AIR CORRECTION DIVISION, UOP
CARBON STEEL
AISI 1110
ORGANIC
NATURAL RUBBER
STAINLESS STEEL
 3
    7.5        (56.0 GAL/1000ACF)
ALKALINE FLYASH
    3.2        (13.0 IN-H20)
    3.4        (   11.0 FT/S)
   16.0
                                             D-65

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER

PUBLIC SERVICE OF COLORADO: CHEROKEE 4 (CONT.)

     PARTICLE REMOVAL EFFICIENCY - '/.               97.0
     ENERGY CONSUMPTION - X                         6.7
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


 7/7*  SYSTEM

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         SINCE STARTUP IN JULY 197* SCALING AND PLUGGING AT THE WET/DRY ZONE,
                         ON THE FIRST STAGE GRIDS, AND IN THE REHEATERS HAVE BEEN THE MOST PROMINENT
                         PROBLEM AREAS CHARACTERIZED BY THIS SYSTEM.  VARIOUS CHEMICAL ADDITIVES
                         HAVE BEEN TESTED FOR CONTROL OF SCALING, INCLUDING PHOSPHATED ESTERS, BUT
                         WITHOUT SIGNIFICANT IMPROVEMENT.  SLOWDOWN IS MAINTAINED AT A HIGH LEVEL
                         TO CHECK THE BUILDUP OF SALTS BUT, OTHER THAN FOR TESTING PURPOSES NO
                         CHEMICAL CONTROL METHOD HAS BEEN USED TO CONTROL SCALE ACCUMULATION.
                         OTHER OPERATING EXPERIENCES INCLUDE WEAR AND PERIODIC REPLACEMENT OF THE
                         MOBILE BALLS, EROSION OF LINING AND CORROSIVE FAILURE OF REHEATERS.  THE
                         EROSION AND LINING FAILURE HAVE NOT BEEN A SERIOUS PROBLEM EXCEPT IN THE
                         RECIRCULATING PUMPS.

10/79  SYSTEM                                                                7**

11/79  SYSTEM                                                   .             720

12/79  SYSTEM                                                                7**

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THE PERIOD ID FAN FAILURES HAVE OCCURRED DUE TO EROSION FROM THE
                         FLYASH.

                         THE ISOLATION DAMPER HAS BEEN A PROBLEM DUE TO FREEZE UPS MAKING IT
                         INOPERATIVE.

                         REHEATER FAILURES HAVE OCCURRED DUE TO PLUGGING OF THE HOT AIR INJECTION
                         STEAM COILS.

                         THE SCRUBBER EXIT DUCTWORK WILL BE REPAIRED TEMPORARILY WITH A SPRAY ON
                         FIBERGLASS LIKE MATERIAL.

 1/80  SYSTEM                                                                744

 2/80  SYSTEM                                                                696

 3/80  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE OUTLET DUCT WORK IS BEING REBUILT INTERNALLY WITH FIBERGLASS FOR
                         STRUCTURAL SUPPORT AND ACID RESISTANCE.  WITH REGULAR MAINTENANCE THE
                         UTILITY EXPECTS THIS TO PROVE TO BE A PERMANENT SOLUTION TO THE EROSION/
                         CORROSION PROBLEM.

                         THE OLD FANS ARE BEING REPLACED WITH HIGH STRENGTH CARBON STEEL FANS HAVING
                         REPLACABLE CHROMIUM ALLOY WEAR PLATE BLADE TIPS.

 4/80  SYSTEM                                                                720

 5/80  SYSTEM                                                                744

 6/80  SYSTEM                                                                720
                                             D-66

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 198*

PUBLIC SERVICE OF COLORADO: CHEROKEE 4 ICONT.)
------------------------------------------ PERFORMANCE DATA ------------------------------------------
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE NEW FANS DESCRIBED DURING THE LAST REPORT PERIOD WERE INSTALLED IN ONE
                         OF THE FOUR MODULES.  NEW FANS WILL BE INSTALLED IN THE OTHER THREE MODULES
                         DURING A SCHEDULED LATE SEPTEMBER OUTAGE UNLESS THE UTILITY HAS AN OPPOR-
                         TUNITY TO MAKE THE REPLACEMENTS SOONER.

 7/80  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE SCRUBBER RETURNED TO SERVICE IN MID JULY AFTER A TWO WEEK OUTAGE.
                         DURING THIS TIME, THE FIBERGLASS INSIDE THE DUCTWORK WAS REPLACED, AND A
                         VERTICAL GRID WAS INSTALLED ON THE SECOND LEVEL OF THE MOBILE BED TOWER TO
                         IMPROVE SYSTEM PERFORMANCE.
 8/80  SYSTEM

 9/80  SYSTEM                                                                720

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER AND FGD SYSTEM WENT DOWN ON SEPTEMBER 15, 1980 FOR A SCHEDULED
                         OVERHAUL.  DURING THIS TIME, FANS WERE INSTALLED ON MODULES A, C, AND 0.

                         THE UTILITY IS CURRENTLY EVALUATING THE VERTICAL GRID ON THE SECOND LAYER.
                         IF THE GRID IMPROVES SYSTEM PERFORMANCE, THEY MILL INSTALL ANOTHER ONE
                         ON THE THIRD  LEVEL.

 10/80  SYSTEM                                                                744

 11/80  SYSTEM                                                                720

 12/80  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         UNIT 4 EXPERIENCED SOME MINOR REHEATER LEAKAGE PROBLEMS DURING THE PERIOD.

                         DURING THE FOURTH QUARTER OF 1980 THE UTILITY REPORTED THAT PROBLEMS WERE
                         ENCOUNTERED WHEN VERITICAL GRIDS WERE INSTALLED ON THE SCRUBBER BED.  THIS
                         WAS INTENDED  TO SOLVE THE PROBLEM OF KEEPING THE SCRUBBER BALLS FROM MOVING
                         HORIZONTALLY, RESULTING IN PILES OF SCRUBBER BALLS IN LOCALIZED AREAS, BUT
                         CORROSION AND SYSTEM PERFORMANCE DID NOT IMPROVE.

 1/81  SYSTEM                                                                744

 2/81  SYSTEM                                                                672

 3/81  SYSTEM                                                                744

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         THROUGHOUT THE JANUARY-MARCH PERIOD THE UTILITY INTERMITTENTLY SHUT DOWN
                         THE SCRUBBER  MODULES (ONE MODULE AT A TIME) TO REPLACE SCRUBBER BALLS AND
                         REPAIR SCRUBBER BALL PARTITIONS.

                         THE UTILITY REPORTED EXPERIENCING CORROSION PROBLEMS WITH THE FOUR SCRUBBER
                         BOOSTER  FANS.
                                             0-67

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                           APPENDIX D
                  DESIGN AND PERFORMANCE DATA FOR OPERATIONAL PARTICLE SCRUBBERS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
302 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MM
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     INLET FLUE GAS CAPACITY - CU.M/S

 ** FABRIC FILTER
     NUMBER
     TYPE

 ** ESP
     NUMBER
     TYPE
     INLET FLUE GAS CAPACITY - CU.M/S

 ** PARTICLE SCRUBBER
     NUMBER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     L/G RATIO - LITER/CU.M
     PH CONTROL ADDITIVE
PUBLIC SERVICE OF COLORADO
VALMONT
5
VALMONT
COLORADO
E
   43.         (  .100 LB/MMBTU)
******         (****** LB/MMBTU)
******         (****** LB/MMBTU)
  274
  166
  157
  163
  166
COMBUSTION ENGINEERING
PULVERIZED COAL
BASE
  436.93       ( 926000 ACFM)
  126.7        ( 260 F)
******         (**** FT)
NR
*******        (***** FT)
COAL
SUBBITUMINOUS
25121.

    6.00
5.4-7.0
   15.00
12.7-18.3
      .70
0.6-0.7
********
******
  218.5
 0
NONE
COLD SIDE
  218.5
(  10800 BTU/LB)
 ******
               ( 463000 ACFM)
               ( 463000 ACFM)
 2
11/71
PACKED TOWER
MOBILE BED PACKING
TURBULENT CONTACT ABSORBER
AIR CORRECTION DIVISION, UOP
CARBON STEEL
AISI 1110
ORGANIC
NATURAL RUBBER
STAINLESS STEEL
 3
    7.8        (58.3 GAL/1000ACF)
LIMESTONE/ALKALINE FLYASH
                                             0-68

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER 1984
PUBLIC  SERVICE  OF  COLORADO:  VALMONT 5 (CONT.)

     PRESSURE DROP -  KPA                            3.7
     SUPERFICIAL GAS  VELOCITY - M/S                 3.4
     INLET GAS  FLOW RATE - CU.M/S                 109.2
     INLET GAS  TEMPERATURE - C                    132.8
     S02 REMOVAL EFFICEMCY - X                  .45.0
     PARTICLE REMOVAL EFFICIENCY - X               96.0
     ENERGY CONSUMPTION - X                         3.6
(15.0 IN-H20)
(    11.0 FT/S)
(  231500 ACFM)
(   271 F)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART.  HOURS HOURS  HOURS FACTOR
11/71  SYSTEM

       ** PROBLEMS/SOLUTIONS/COMMENTS
              720
                         THE FIRST PARTICLE MATTER SCRUBBER COMMENCED OPERATION IN NOVEMBER  1971.
                         THE SCRUBBER WAS ORIGINALLY INSTALLED FOR PARTICLE MATTER REMOVAL SINCE THE
                         PLANT BURNS LOW SULFUR COAL; HOWEVER, 45X OF THE S02 IS REMOVED  AS  WELL
                         BECAUSE OF THE ALKALINITY OF THE FLYASH.

                         DURING THE FIRST YEAR OF OPERATION PROBLEMS INCLUDED DIFFICULTIES WITH THE
                         MODULE PACKING GRID SUPPORT, GENERAL VESSEL SCALE FORMATION,  FLOW DISTRI-
                         BUTION PROBLEMS, BALL BREAKAGE,  SCALING IN THE MIST ELIMINATOR SECTION,
                         AND PLUGGING OF THE REHEATER.  SCALE FORMATION WAS THE MOST PREDOMINANT
                         CONTINUING MAJOR CAUSE OF DOWNTIME IN THE SCRUBBER.  SCALE ACCUMULATION
                         WAS NOTED ON THE WET-DRY INTERFACE IMMEDIATELY DOWNSTREAM OF  THE PRESATU-
                         RATION NOZZLES.  SCALE ALSO ACCUMULATED HEAVILY ON THE UNDERSIDE OF THE
                         FIRST LAYER OF GRID BARS.
                         SCALE ON THE UPPER GRID BARS WAS LESS PREVALENT AS THE ACTION OF THE "PING
                         PONS" BALLS TENDED TO KEEP THE SCALE OFF OF THESE SECTIONS.  SCALE  ALSO
                         COLLECTED ON THE WALLS OF THE VESSEL AND INTERMITTENTLY SLOUGHED OFF AND
                         FELL INTO THE SUMP IN LARGE PIECES CAUSING BLOCKAGE OF THE RECIRCULATION
                         PUMP SUCTION SCREENS.  SCALING OF THE MIST ELIMINATOR ABATED  SOMEWHAT WITH
                         THE INTRODUCTION OF A CLEAR RINSE WATER WASH.  SCALE FORMATION IN THE RE-
                         HEAT SECTION SOMETIMES REQUIRED SUPPLEMENTAL CLEANING OF THE  REHEATER IN
                         ADDITION TO THE CLEANING OBTAINED BY THE USE OF THE SOOTBLOWERS  WHICH WERE
                         INSTALLED AS A PART OF THE REHEATER EQUIPMENT.  UNDER NORMAL OPERATION,
                         THE SOOTBLOWERS LOCATED IN THIS REHEAT SECTION WERE FAIRLY SUCCESSFUL IN
                         REMOVING THE ACCUMULATION OF THE SCALE IN THE REHEATER.
                         ALTHOUGH MANY OF THE INITIAL START-UP PROBLEMS WERE SOLVED OVER  A PERIOD
                         OF TIME, THE CALCIUM SULFATE-FLYASH SCALING CONTINUED TO BE A SIGNIFICANT
                         OPERATING PROBLEM AT THE VALMONT INSTALLATION.  IN ADDITION TO THESE
                         SCALING RELIABILITY PROBLEMS, A WATER QUALITY CONCERN ALSO SURFACED THAT
                         WAS A DIRECT RESULT OF THE PARTICLE SCRUBBER OPERATION.  THE  RELATIVELY
                         HIGH CAO CONCENTRATION IN THE VALMONT FLYASH RESULTED IN FAIRLY  HIGH S02
                         REMOVAL RATES (45-50 PERCENT) WITHIN THE UNITS.  SINCE NO PH CONTROL CAPA-
                         BILITY FOR EITHER THE RECIRCULATING SLURRY OR THE SYSTEM SLOWDOWN SLURRY
                         WAS DESIGNED INTO THE SYSTEM, AN ACID CONDITION WAS CREATED IN THE  SLURRY
                         AND THE SLOWDOWN STREAM.  PH LEVELS OF THE SLOWDOWN NORMALLY RANGED BETWEEN
                         1.7 AND 2.0.  ALTHOUGH THE STREAM WAS NEUTRALIZED TO A DEGREE BY ALKALINE
                         FLYASH, PSCC FELT THAT IT WAS IMPORTANT TO INVESTIGATE VARIOUS CONTROL
                         MEASURES WHICH COULD BE APPLIED TO THIS STREAM.  THE CALCIUM SULFATE
                         SCALING PROBLEM WAS THOUGHT TO BE THE RESULT OF A SUPER-SATURATED CALCIUM
                         SULFATE CONDITION IN THE RECIRCULATING SLURRY.  BECAUSE OF THIS  IT  WAS  FELT
                         THAT CONTINUOUS PH CONTROL OF THE RECIRCULATING SLURRY, CONVERSION  OF THE
                         SYSTEM TO CLOSED LOOP OPERATION AND ESTABLISHING A HIGHER CONCENTRATION  OF
                         SEEDING SOLIDS IN THE RECIRCULATION SLURRY (THEREBY CONTROLLING  THE SCALING
                         PROBLEMS WITHOUT CHEMICAL ADDITIVES) WOULD BE NECESSARY MEASURES.
                         FOR PH CONTROL, LIMESTONE WAS TESTED INITIALLY, THEN LIME WAS UTILIZED  FOR
                         THE ALKALI REAGENT.  IN THE FIRST TEST, SINCE LIMESTONE UTILIZATION WAS  A
                         MAJOR CONCERN, A SPECIAL EFFORT WAS MADE TO REDUCE THE POTENTIAL FOR THE
                         SH03T CIRCUITING OF THE ADDED LIMESTONE AND TO PROVIDE SUFFICIENT RESIDENCE
                         TIME IN THE REACTOR SECTION OF THE SYSTEM.  BY UTILIZING FOUR REACTION  MIX
                         TANKS IN SERIES, PLUG FLOW WAS EXPECTED TO BE MORE CLOSELY SIMULATED.  TO
                         MAINTAIN A CLOSED LOOP SYSTEM WHERE THE QUANTITY OF WATER REMOVED FROM  THE
                         SYSTEM WAS HELD TO A MINIMUM, FOUR SYSTEM DESIGN FEATURES WERE  UTILIZED.
                              1. UTILIZATION OF A COMBINATION OF POND SUPERNATANT AND MAKE-UP WATER
                                             D-69

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

PUBLIC SERVICE OF COLORADO: VALMONT 5 (CONT.)
	,	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR

                                 FOR RECYCLE WATER.
                              2. PRESATURATION OF THE INCOMING FLUE GAS WITH RECIRCULATIN6 SLURRY.
                              3. INTERMITTENT MIST ELIMINATOR WASH.
                              ft. PROPER SELECTION OF MATERIALS OF CONSTRUCTION TO PROTECT AGAINST
                                 ATTACK CAUSED BY HIGH CHLORIDE CONCENTRATIONS.
                         THE SCRUBBERS R & 0 FACILITY WAS NOT EQUIPPED WITH A MECHANICAL THICKENER
                         FOR CONTROL OF THE SUSPENDED SOLIDS CONCENTRATION OF THE RECIRCULATING
                         SLURRY (ALL PURGED MATERIAL WAS SENT TO THE SLUDGE POND).  WITH A 500 PPM
                         SOS CONCENTRATION IN THE FLUE GAS, IT IS EXPECTED THAT THE RECIRCULATING
                         SLURRY SOLIDS COULD BE REALLY CONTROLLED IN THE 5 TO 7 PERCENT RANGE.  DUE
                         TO THE MIXED FUEL FIRED AT THE UNIT DURING THE TEST PERIOD, HOWEVER, THE
                         S02 CONCENTRATIONS EMITTED FROM THE BOILER AND HENCE PRESENT IN THE FLUE
                         GAS STREAM VARIED SIGNIFICANTLY AND FINALLY FELL TO SUCH LOW LEVELS (OFTEN
                         100-200 PPM) THAT SUSPENDED SOLIDS CONCENTRATIONS IN THE SLURRY COULD NOT
                         BE MAINTAINED.  IT IS ALMOST CERTAIN THAT A THICKENER, WITH THE SUBSE-
                         QUENT RETURN OF SOLIDS TO THE SCRUBBER LIQUOR, COULD HAVE BEEN USED TO
                         GOOD ADVANTAGE DURING THIS TIME PERIOD.  GENERALLY SPEAKING, THE SEVERE
                         SCALING CONDITIONS PLAGUING THE TEST MODULE WERE INTENSIFIED DURING THESE
                         PERIODS OF LOW INLET S02 CONDITION.

11/74  SYSTEM                                                                720

12/74  SYSTEM                                                                744

 1/75  SYSTEM                                                                744

 2/75  SYSTEM                                                                672

 3/75  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE FGD SCRUBBING SYSTEM WAS OPERATED FOR A TOTAL OF FOUR AND ONE-HALF
                         MONTHS, FROM MID-OCTOBER 1974 TO MARCH 1975.  THE OVERALL RELIABILITY OF
                         THE SYSTEM WAS APPROXIMATELY 75X.

 4/75  SYSTEM                                                                720

 5/75  SYSTEM                                                                744

 6/75  SYSTEM                                                                720

 7/75  SYSTEM                                                                744

 8/75  SYSTEM                                                                744

 9/75  SYSTEM                                                                720

10/75  SYSTEM                                                                744

11/75  SYSTEM                                                                720

12/75  SYSTEM                                                                744

 1/76  SYSTEM                                                                744

 2/76  SYSTEM                                                                696

 3/76  SYSTEM                                                                744

 4/76  SYSTEM                                                                720

 5/76  SYSTEM

 6/76  SYSTEM                                                                720
                                             D-70

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

PUBLIC SERVICE  OF COLORADO:  VALMONT 5 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


 7/76  SYSTEM                                                                7*4

 8/76  SYSTEM                                                                744

 9/76  SYSTEM                                                                720

10/76  SYSTEM                                                                74*

11/76  SYSTEM                                                                720

12/76  SYSTEM                                                                744

 1/77  SYSTEM                                                                744

 2/77  SYSTEM                                                                672

 3/77  SYSTEM                                                                744

 4/77  SYSTEM                                                                720

 5/77  SYSTEM                                                                744

 6/77  SYSTEM                                                                720

 7/77  SYSTEM                                                                744

 8/77  SYSTEM                                                                744

 9/77  SYSTEM                                                                720

10/77  SYSTEM                                                                744

11/77  SYSTEM                                                                720

12/77  SYSTEM                                                                744

 1/78  SYSTEM                                                                744

 2/78  SYSTEM                                                                672

 3/78  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THERE HAVE BEEN RECURRING PROBLEMS ASSOCIATED WITH BALL MIGRATION  IN THE
                         BALL COMPARTMENT AS WELL AS RECIRCULATION PUMP MOTOR  BEARING  FAILURE, AND
                         WEAR AND FAILURE IN THE BALL COMPARTMENT LINING.  THERE HAVE  BEEN  CONTINUAL
                         PROBLEMS WITH REHEATER PLUGGING.  THERE ALSO HAVE BEEN EXPANSION JOINT
                         FAILURES AT BOTH THE  INLET AND OUTLET OF THE SCRUBBER.
                         MOPE RECENTLY THERE WAS A PINCH BELT FAILURE.
                         THE SCRUBBING SYSTEM  HAS HAD AN AVAILABILITY RANGE OF 50  TO 78X WITH AN
                         AVERAGE OF 66X.

 4/78  SYSTEM                                                                720

 5/78  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO SIGNIFICANT PROBLEMS WERE ENCOUNTERED.

 6/78  SYSTEM                                                                720

 7/78  SYSTEM                                                                744
                                             D-71

-------
UTILITY FGD SURVEY: OCTOBER 1933 - SEPTEMBER 1984

PUBLIC SERVICE OF COLORADO: VALflONT 5 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


 8/78  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY HAD NO COMMENTS FOR THIS PERIOD.

 9/78  SYSTEM                                                                720

10/78  SYSTEM                                                                744

11/78  SYSTEM                                                                720

12/78  SYSTEM                                                                744

 1/79  SYSTEM                                                                744

 Z/79  SYSTEM                                                                672

 3/79  SYSTEM                                                                744

 4/79  SYSTEM                                                                720

 5/79  SYSTEM                                                                744

 6/79  SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         AVERAGE SCRUBBER AVAILABILITY FROM START UP THROUGH APRIL 1979 WAS 64.42X.
                         AVERAGE SCRUBBER AVAILABILITY FOR 1978 WAS 66.85X.
                         AVERAGE SCRUBBER AVAILABILITY FROM JANUARY 1, 1979 THROUGH MAY, 1979 WAS
                         APPROXIMATELY SOX.

                         BALL MIGRATION, ALTHOUGH NOT SERIOUS, IS A CHRONIC PROBLEM FOR VALMONT 5.

                         EROSION AND CORROSION HAVE OCCURRED ON THE SCRUBBER GRID BAR AREA (PACKING
                         SUPPORT).

                         EROSION/CORROSION IS EVIDENT IN THE MIST ELIMINATOR SECTION.

                         EROSION/CORROSION OCCURRS IN THE REHEATER AREA AND SOOT BLOWER.

                         THE UTILITY HAD TO REPLACE INLET AND OUTLET EXPANSION JOINTS.

                         REHEATER  PLUGGING HAS BEEN A PROBLEM.

                         RECYCLE PUMP BEARING FAILURES OCCURRED.

                         THE JACK  SCREW DRIVE HAS BEEN MALFUNCTIONING ON  INLET AND OUTLET ISOLATION
                         DAMPERS.

 7/79  SYSTEM                                                                744

 8/79  SYSTEM                                                                744

 9/79  SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THE ANNUAL SHUTDOWN IN SEPTEMBER THE OLD  SCRUBBER BALLS WERE
                         REPLACED  WITH A NEW BRAND.  DUE TO BALL MOTION THE RUBBER  LINER  ERODED.

                         IN THE MIST ELIMINATOR  SECTION EROSION AND CORROSION OCCURRED.
                                              D-72

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER
PUBLIC SERVICE  OF COLORADO:  VALMONT 5 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR
10/79  SYSTEM

11/79  SYSTEM

12/79  SYSTEM
           100.0

            92.3

            98.1
                                                          720
 1/80
 2/80
 3/80
 4/80
  5/80
 6/80
          PROBLEMS/SOLUTIONS/COMMENTS
A
B
SYSTEM

A
B
SYSTEM

A
B
SYSTEM
98.5
98.5
98.5

84.4
94.9
89.7

90.8
87.7
89.0
                         ONE OF THE MAJOR SCRUBBING SYSTEM PROBLEMS IS THE SCRUBBER WALL WEAR WHICH
                         HAS TO BE PATCHED DURING THE SPRING AND FALL.

                         REHEATER PLUGGING HAS BEEN A CHRONIC PROBLEM.

                         THE UTILITY HAS REPORTED THE FOLLOWING ANNUAL AVAILABILITIES FOR THE UNIT.
                             1972 - 1978: 64.3X
                             1972 - 1979: 65.9X
                                    1978: 66.8X
                                    1979: 80.5X
                                                                             744
                                                                             696
                                                                             744   615
       *« PROBLEMS/SOLUTIONS/COMMENTS
                         DURING THE FIRST QUARTER OF 1980, NO MAJOR PROBLEMS WERE ENCOUNTERED WITH
                         THE SCRUBBER.
       A
       B
       SYSTEM
            88.1
            88.1
            88.1
                                                          720   716
       *« PROBLEMS/SOLUTIONS/COMMENTS
                         THE SCRUBBER WAS SHUT DOWN ON APRIL 14 FOR A WEEK TO MAKE REPAIRS TO A HOLE
                         IN THE SCRUBBER RUBBER LINING, RECYCLE PUMP LININGS AND A STEAM REGULATOR
                         ON ONE OF THE REHEATERS.
       A
       B
       SYSTEM
            96.8
           100.0
            98.4
                                                          744   744
       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO PROBLEMS WERE REPORTED FOR MAY.
       A
       B
       SYSTEM
             8.0
             8.0
             8.0
                                                          720   720
       ** PROBLEMS/SOLUTIONS/COMMENTS
                         DURING JUNE THE SCRUBBER WAS FORCED OUT OF SERVICE WHEN AN INBOARD FAN
                         PEDISTLE BEARING FAILED.  THE BEARING SECTION WAS REBUILT.
                                             0-73

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

PUBLIC SERVICE OF COLORADO: VALMONT 5 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR

                         WHILE FAN REPAIRS WERE IN PROGRESS EXTENSIVE MAINTENANCE WAS PERFORMED ON
                         THE SCRUBBER.  MAINTENANCE WORK INCLUDED COMPLETE BALL REPLACEMENT, ADDI-
                         TIONAL REPAIR WORK ON THE SCRUBBER LINER, REPAIR OF HOLES IN THE TOWER
                         SHELL AND OF A RUPTURED MIST ELIMINATOR WASH LINE AND THE REHEATER WAS
                         CLEANED.

                         DAMPER JAMMING AT VALMONT HAS OCCURRED PERIODICALLY.  SOMETIMES DAMPERS DO
                         NOT READILY CLOSE.  THE OPERATOR MUST MOVE THE DAMPER UP AND DOWN UNTIL THE
                         GUILLOTINE SEATS.  BECAUSE OF CONTINUOUS FLY ASH ACCUMULATION IT APPEARS
                         THAT THE DAMPERS MUST BE EXERCISED FREQUENTLY TO PREVENT JAMMING.

 7/80  5A                      48.3                    46.6
       SB                      48.3                    46.6
       SYSTEM                  48.3                    46.6                  744   719    347

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE SCRUBBER SYSTEM WAS SHUT DOWN BECAUSE OF SCRUBBER BOOSTER FAN
                         BEARING FAILURE.

 8/80  5A                      87.5                    84.8
       5B                      95.6                    92.6
       SYSTEM                  91.5                    87.7                  744   721    660

       ** FROBLEMS/SOLUTIONS/COMMENTS

                         THE RECIRCULATION PUMP MOTOR BEARING FAILED CAUSING SOME MINOR OUTAGE
                         TIME IN AUGUST.

 9/80  SYSTEM                                            .0                  720     0      0

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER AND SCRUBBER WERE SHUT DOWN DURING SEPTEMBER FOR SCHEDULED
                         MAINTENANCE.

10/80  SYSTEM                                                                744

11/80  SYSTEM                                                                720

12/80  SYSTEM                                                                744

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         THE SCRUBBER REMAINED OUT OF SERVICE THROUGHOUT THE OCTOBER-DECEMBER PERIOD
                         AND IS EXPECTED TO START UP AT THE END OF JANUARY.  LATE START UP OF THE
                         SCRUBBER IS DUE TO A MANPOWER SHORTAGE.  THE BOILER AND TURBINE RETURNED TO
                         SERVICE IN MID-DECEMBER.

 1/81  SYSTEM                                                                744

 2/81  SYSTEM                                                                672

 3/81  SYSTEM

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         SCRUBBER CAME BACK ON-LINE AT THE END OF JANUARY AND OPERATED THROUGHOUT
                         THE MONTHS OF FEBRUARY AND MARCH WITHOUT ANY MAJOR SCRUBBER RELATED PROB-
                         LEMS.
                                             D-74

-------
                                                  UTILITY F60 SURVEY: OCTOBER 1983 - SEPTEMBER
                                           APPENDIX D
                  DESIGN AND PERFORMANCE DATA FOR OPERATIONAL PARTICLE SCRUBBERS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NS/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY M/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFL'R CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

**» PARTICLE CONTROL

 ** ESP
     'NUMBER
     TYPE
     SUPPLIER
     INLET FLUE GAS CAPACITY - CU.M/S
     INLET FLUE GAS TEMPERATURE - C
     PRESSURE DROP - KPA
     PARTICLE REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     NUM3ER
     NUMBER OF SPARES
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE -  LITER/S
     L/G RATIO - LITER/CU.M
     PH CONTROL ADDITIVE
     SUPERFICIAL GAS VELOCITY - M/S
     INLET GAS FLOW RATE - CU.M/S
               (  .100 LB/MMBTU)
               ( 1.200 LB/MMBTU)
               (*»**»* LB/MMBTU)
SOUTHWESTERN PUBLIC SERVICE
HARRINGTON
1
AMARILLO
TEXAS
D
   43.
  516.
******
  350
  350
  320
*****
  350
COMBUSTION ENGINEERING
PULVERIZED COAL
BASE
  778.63       (1650000 ACFM)
  176.7        ( 350 F)
   76.         ( 250 FT)
CONCRETE
    8.2        ( 27.0 FT)
               (  8700 BTU/LB)
                8400-8700
COAL
SUBBITUMINOUS
20236.

    5.00
5.0-5.5
   27.10
25.0-30.0
      .31
0.3-0.5
********
******
COLD SIDE
RESEARCH-COTTRELL
  778.6        (1650000 ACFM)
  168.3        (  335 F)
     .1        (  1. IN-H20)
   95.0
 6
 1
PACKED TOWER
STATIC BED PACKING
MARBLE-BED SCRUBBER
COMBUSTION ENGINEERING
24.0 X 25.0
CARBON STEEL
AISI 1110
ORGANIC
NR
GLASS MARBLES
 1
  444.1
    3.1
                (  7050 GPM)
                (23.0 GAL/1000ACF)
SLUDGE FROM WATER TREATMENT
    2.4         (    8.0  FT/S)
  141.6         (  300000  ACFM)
                                             0-75

-------
UTILITY FGD SURVEY'- OCTOBER 1983 - SEPTEMBER 1984

SOUTHWESTERN PUBLIC SERVICE: HARRINGTON 1 (CONT.)

     INLET GAS TEMPERATURE - C                     60.0        (  140 F)
     PARTICLE REMOVAL EFFICIENCY - X               50.0
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


10/79  SYSTEM                                                                744

11/79  SYSTEM                                                                720

12/79  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING OCTOBER THROUGH DECEMBER, TWO SPRAY PUMP MOTORS FAILED.

                         THE FRP FLUSH PIPING HAS FAILED CAUSING SOME LEAKING.

                         PLUGGING IN ONE MARBLE BED WAS ENCOUNTERED WHEN THE CHEMISTRY CONTROL MAS
                         TEMPORARILY LOST.

                         THE CONE SHAPED EXPANDED METAL (316L SS) SCREENS COVERING THE BED DRAIN
                         PIPES HAVE ERODED AWAY FROM BALL MOVEMENT.  THE MARBLE BALLS HAVE BEEN
                         DROPPING INTO THE RECYCLE TANK.  WHERE THE UTILITY HAS REPLACED THE METAL
                         SCREEN WITH EXPANDED PLASTIC SCREEN, EROSION HAS NOT OCCURRED.

 1/80  SYSTEM                                                                744

 2/80  SYSTEM                                                                696

 3/80  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THE FIRST QUARTER OF 1980 THE MIST ELIMINATOR WASH PIPING RUPTURED
                         CAUSING PLUGGING IN SCRUBBERS 4 AND 5.  THE UTILITY PLANS TO REPLACE
                         ALL FRP PIPING WITH STEEL.  THE RUPTURE ON NO. 5 ALSO DAMAGED THE WATER
                         SUPPLY HEADER.

                         THE MARBLE BED PLUGGING REPORTED DURING THE LAST QUARTER IS NOT YET
                         COMPLETELY CLEARED.  THE SOFT SCALE IS GRADUALLY GOING BACK INTO THE
                         SOLUTION.  THE PLATE AREA IS CLEAN.

                         THE DUCT BENEATH THE REHEATER TUBING ON ONE OF THE MODULES HAS CORRODED TO
                         THE POINT THAT HOLES HAVE FORMED.  SCALE AW MOISTURE WERE FOUND ON THE
                         PLATE WHERE THE CORROSION FORMED.  THE PLATE WAS REMOVED AND A NEW CARBON
                         STEEL PLATE WAS WELDED IN.  NO OTHER REHEATER DUCTS HAVE EXPERIENCED ANY
                         SCALE OR MOISTURE ACCUMULATION.

 4/80  SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         A  PUMP LINER FAILURE OCCURRED IN APRIL.  THE IMPELLER SHAFT LINER WAS RE-
                         PAIRED AND REPLACED.

 5/80  SYSTEM                                                                744

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER WAS SHUT DOWN A FEW DAYS IN LATE APRIL AND 12 TO 14 DAYS IN
                         EARLY MAY FOR AIR PREHEATER REPAIRS.

                         DURING APRIL AND MAY THE SCRUBBING SYSTEM EXPERIENCED AGITATOR PROBLEMS.
                         THE RECENT PROBLEMS HAVE BEEN RELATED TO BEARING FAILURE, HOWEVER, THE
                         SEALS HAVE BEEN  LEAKING AS WELL.  THE AGITATORS AT THIS  FACILITY  ARE  SIDE
                         MOUNTED.  THE AGITATOR SHAFT ENTERS THE TANK AT ROUGHLY  12 FT BELOW THE
                                              D-76

-------
                                                  UTILITY FGD SURVEY:  OCTOBER  1983 - SEPTEMBER  1984

SOUTHWESTERN  PUBLIC  SERVICE:  HARRINGTON 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART.  HOURS HOURS  HOURS FACTOR

                         FLUID SURFACE.  IT APPEARS THAT THE SEAL LEAKING MAY BE ATTRIBUTABLE TO
                         FAULTY INSTALLATION.

 6/80  SYSTEM      92.1                                                      720   696         79.3

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         DURING JUNE THE SCRUBBER EXHIBITED AN AVAILABILITY OF 92.IX.   THERE WAS
                         GREATER SCRUBBER CAPACITY AVAILABLE THAN REQUIRED  BY THE BOILER.   NO
                         PROBLEMS WERE REPORTED FOR JUNE.

                         DAMPER PROBLEMS REPORTED PREVIOUSLY HAVE BEEN ELIMINATED.   THE OLD OPERATOR
                         MECHANISMS WERE REPLACED WITH OPERATORS SUPPLIED BY ANOTHER MANUFACTURER.

                         ONE OF THE MARBLE BEDS IS STILL PARTIALLY PLUGGED.  THE MATERIAL SEEMS TO
                         BE HARD CALCIUM SULFATE SCALE.  THE SCALE WILL PROBABLY NOT CLEAR FURTHER
                         THROUGH DISSOLUTION DURING NORMAL SCRUBBER OPERATIONS AS HAD BEEN HOPED.
                         ALTHOUGH THE MODULE MUST OPERATE AT LOWER THAN DESIGN GAS FLOW SCRUBBER
                         OPERATIONS ARE NOT HAMPERED OVERALL BECAUSE THE SYSTEM HAS SOME DESIGN
                         SPARE CAPACITY.

                         THE REHEATER PROBLEM REPORTED PREVIOUSLY HAS OCCURRED ON THREE REHEATERS
                         NOW.  THE FAILURE OF THE REHEATER DUCT BOTTOM PANELS MAY BE A RESULT OF AN
                         UNDERSIZED DEFLECTION SHIELD BENEATH THE TUBE BANKS.  IT IS ALSO POSSIBLE
                         THAT THE DUCTING WAS IMPROPERLY WELDED.

 7/80  SYSTEM                                                                744

 8/80  SYSTEM                                                                744

 9/80  SYSTEM                                                                720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT NO MAJOR SCRUBBING SYSTEM PROBLEMS OCCURRED
                         DURING THE THIRD QUARTER 1980.

                         THE PROBLEM REPORTED EARLIER WITH THE MIST ELIMINATOR WASH PIPING IS
                         PRESENTLY BEING SOLVED BY REPLACING THE PIPING WITH CARBON STEEL.

10/80  SYSTEM                                                                744

11/80  SYSTEM                                                                720

12/80  SYSTEM                                                                744

      '** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THE OCTOBER THROUGH DECEMBER PERIOD REPLACEMENT OF THE MIST ELIMI-
                         NATOR WASH PIPING WITH CARBON STEEL CONTINUED; AS THE OLD PIPING WEARS OUT
                         AND MAINTENANCE TIME PERMITS.

                         DURING LATE DECEMBER, THE SLURRY SPRAY PUMP HOUSING CRACKED DURING A BACK
                         FLUSH.  THIS WAS THE SECOND TIME IN TWO YEARS THAT THIS PROBLEM HAD
                         OCCURRED.

 1/81  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE UTILITY REPORTED THAT AT THE BEGINNING OF THE YEAR THE SCRUBBER SYSTEM
                         BE-GAN TO SEE VOLUMES OF FLUE GAS GREATER THAN THAT  PRODUCED BY THE BOILER.
                         IT WAS LATER DISCOVERED THAT THE EXPANSION JOINTS LOCATED AT  THE  ESP HAD
                         CRACKED AND WERE ALLOWING AMBIENT AIR TO ENTER THE  SYSTEM.  THE UTILITY
                                             D-77

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

SOUTHWESTERN PUBLIC SERVICE: HARRINGTON 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR

                         REPORTED THEY HAD ORIGINALLY ORDERED VITRON EXPANSION JOINTS BUT INSTEAD
                         RECEIVED CHLOROBUTYL JOINTS WHICH SUBSEQUENTLY FAILED.  DUE TO THE IN-
                         CREASED GAS LOAD THE UTILITY HAS HAD TO RUN MORE MODULES THAN NORMALLY
                         NECESSARY FOR A GIVEN BOILER LOAD.  THE UTILITY PLANS TO REPLACE THE
                         EXPANSION JOINTS DURING THE NEXT SCHEDULED OUTAGE IN MAY.

 2/81  SYSTEM                                                                672

 3/81  SYSTEM                                                           ,     744

       *# PROBLEMS/SOLUTIONS/COMMENTS

                         MODULE 3 WAS SHUT DOWN FOR 24 HOURS TO REPLACE A RUBBER PUMP LINER WHICH
                         HAD BEEN WORN AWAY BY THE PUMP IMPELLERS.

                         EXCEPT FOR THE PUMP LINER AND EXPANSION JOINT FAILURES THE SCRUBBER SYSTEM
                         OPERATED WELL THROUGHOUT THE JANUARY-MARCH PERIOD.
                                             D-78

-------
                                                  UTILITY FGO SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                           APPENDIX E
                DESIGN AND PERFORMANCE DATA FOR OPERATIONAL FOREIGN FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
COUNTRY
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION  LIMITATION - HG/J
NOX EMISSION  LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MM
NET UNIT  GENERATING CAPACITY M/FGD - MW
NET UNIT  GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT  DATA - BOILER ANO STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL  DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE  HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE  ASH CONTENT - '/.
     RANGE ASH CONTENT - V.
     AVERAGE  MOISTURE CONTENT - 7.
     RAN3E MOISTURE CONTENT - 7.
     AVERAGE  SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE  CHLORIDE CONTENT - 7.
     RAN3E CHLORIDE CONTENT - 7.

*** PARTICLE  CONTROL

 »* MECHANICAL COLLECTOR
     TYPE
     SUPPLIER

 ** FABRIC  FILTER
     NUMBER
     TYPE

 ** ESP
     NUMBER
     TYPE
     SUPPLIER
     INLET  FLUE GAS CAPACITY - CU.M/S
     INLET  FLUE GAS TEMPERATURE - C
     PRESSURE DROP - KPA

 ** PARTICLE  SCRUBBER
     NUMBER
     GENERIC  TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS  CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
CHUGOKU ELECTRIC
SHIMONOSEKI
1
SHIMONOSEKI
JAPAN
******
******
  219.
******
  575
  175
*****
*****
  175
MITSUBISHI
PULVERIZED COAL
BASE
  266.27
  130.0
  200.
CONCRETE
    3.0
               <****** LB/MMBTU)
               (   .510 LB/MMBTU)
               <****** LB/MMBTU)
                 564255 ACFM)
                 266 F)
                 656 FT)
               (   9.7 FT)
               ( 10768 BTU/LB)
                ******
COAL
******
25046.

   24.60
******
    2.30
******
      .59
******
      .04
0.01-0.11
MULTICLONE
MITSUBISHI
 0
NONE
COLD SIDE
MITSUBISHI HEAVY INDUSTRIES
  246.1         ( 521589 ACFM)
  140.0         (  284 F)
     .8         (3. IN-H20)
SPRAY TOWER
NR
NR
MITSUBISHI
CARBON STEEL
AISI 1110
ORGANIC
SYNTHETIC RUBBER
NONE
 1
                                             E-l

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

CHUGOKU ELECTRIC: SHIMONOSEKI i (CONT.)

     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - LITER/CU.M
     SUPERFICIAL GAS VELOCITY - M/S
     INLET GAS FLOW RATE - CU.M/S

*** FGO SYSTEM
 «# GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     PROCESS ADDITIVES
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
     NEU/RETROFIT
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     CURRENT STATUS
     COMMERCIAL START-UP
     INITIAL START-UP
     CONTRACT AWARDED

 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     NUMBER
     NUMBER OF SPARES
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     NUMSER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     GAS-SIDE PRESSURE DROP - KPA
     SUPERFICAL GAS VELOCITY - M/SEC
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C
     S02 REMOVAL EFFICIENCY - 7.
     PARTICLE REMOVAL EFFICENCY - X

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     NUMBER OF STAGES
     PRESSURE DROP - KPA
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     WASH WATER SOURCE
     WASH RATE - L/S

 «» REHEATER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     TEMPERATURE INCREASE - C
     INLET FLUE GAS FLOW RATE - CU. M/S
     INLET FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
  544.3
    3.0
   13.1
  203.7
(  8640 GPM)
(22.5 GAL/1000ACF)
(    43.0 FT/S)
(  431725 ACFM)
SALEABLE PRODUCT
WET SCRUBBING
LIMESTONE
NONE
MITSUBISHI HEAVY INDUSTRIES
MITSUBISHI
FULL SCALE
RETROFIT
   85.00
 1
 7/79
 5/79
 5/77
NR
NR
 1
 0
COMBINATION TOWER
NR
N/A
MITSUBISHI
CARBON STEEL
AISI 1110
N/A
ORGANIC
NR
NR
 4
 2722.
    1.0
    3.0
  203.73
   50.0
   89.0
   90.0
(43200 GPM)
(  3.9 IN-H20)
(   9.8 FT/S)
(  431725 ACFM)
(   122 F)
PRIMARY COLLECTOR
IMPINGEMENT
BAFFLE
CLOSED VANE
    2
     .1
NR
NR
FRESH
  200.0
(   .6 IN-H20)
               ( 3170 GAL/MIN)
WASTE HEAT RECOVERY
NR
NR
  157.8        (  284 F)
  203.73       ( 431725 ACFM)
  105.0        (  221 F)
NR
NR
                                             E-2

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER
CHUGOKU ELECTRIC:  SHIMONOSEKI i (CONT.)
 ** FANS
     DESIGN
     SUPPLIER
     FUNCTION
     APPLICATION
     SERVICE
     FLUE GAS  FLOW RATE - CU.M/S
     FLUE GAS  TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC  TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 »» REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

 ** TANKS
     SERVICE
     NR

 ** PUMPS
     SERVICE
     NR
 ** SOLIDS COHCENTRATIHG/DEWATERING
     DEVICE
     NUMBER
     NUMBER OF SPARES
     FEED STREAM CHARACTERISTICS
     OUTLET STREAM CHARACTERISTICS

 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUMBER
     NUMBER OF SPARES
     DIMENSIONS - FT
     FEED STREAM CHARACTERISTICS
     OUTLET STREAM CHARACTERISTICS

 *** SALEABLE BYPRODUCTS
     NATURE
     FULL LOAD QUANTITY - M T/H
     QUALITY - X

 *** SLUDGE

 ** TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 ** DISPOSAL
     NATURE
     TYPE
     SITE TREATMENT
NR
MITSUBISHI HEAVY INDUSTRIES
NR
'NR
NR
  294.04        ( 623108 ACFM)
  140.0         (  284 F)
NR
NR
NR
NR
NR
NR
NR
NR
WET BALL MILL
NR
NR
NUMBER

***«


NUMBER

****
 CENTRIFUGE
  5
 0
 25X SOLIDS
 90X SOLIDS
 THICKENER
  1
 0
 33.0 DIA X 10.0
 5X  SOLIDS
 25X SOLIDS
 GYPSUM
     6.98
    99.0
 NR
 NR
 NR
 NR
 NR
 NR
t   7.70 TPH)
                                              E-3

-------
UTILITY FGO SURVEY: OCTOBER 1983 - SEPTEMBER 1984

CHUGOKU ELECTRIC: SHIMONOSEKI i 
-------
                                                  UTILITY F6D SURVEY:  OCTOBER 1983 - SEPTEMBER  1984
CHUGOKU  ELECTRIC:  SHIMONOSEKI  i CCONT.)
	PERFORMANCE DATA	
PERIOD MODULE  AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART.  HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE F60 SYSTEM OPERATED CONTINOUSLY WITH NO PROBLEMS DURING JUNE.

 7/80  SYSTEM      100.0       100.0       100.0       100.0                  744   744    744  98.9

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         THE FGD SYSTEM OPERATED DURING JULY WITH NO PROBLEMS.

 8/80  SYSTEM       88.7        88.7        88.7        88.7                  744   744    660  99.5

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING AUGUST THE FGD SYSTEM WAS SHUT DOWN FOR 84 HOURS DUE TO SOME PLUG-
                         GING IN THE REHEATER.  DURING THIS TIME THE REHEATER WAS WATER WASHED AND
                         THE SOOT BLOWER SYSTEM WAS IMPROVED.

 9/80  SYSTEM       89.0        89.0        89.0        89.0                  720   720    641  97.3

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING SEPTEMBER PROBLEMS WITH PLUGGING IN THE REHEATER RECURRED.   THE
                         TROUBLE WAS CAUSED BY ESP PROBLEMS, BY WHICH A LARGE AMOUNT OF FLYASH
                         WENT INTO THE REHEATER.

10/80  SYSTEM      100.0        97.4       100.0        88.0                  744   673    655  88.5

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING OCTOBER THE BOILER WAS TAKEN OFF LINE FOR THREE DAYS FOR AN
                         INSPECTION OF THE NOX REMOVAL SYSTEM.

11/80  SYSTEM     100.0       100.0       100.0       100.0                  720   720    720  99.4

12/80  SYSTEM     100.0       100.0       100.0       100.0                  744   744    744  99.6

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO PROBLEMS WERE ENCOUNTERED DURING THE MONTHS OF NOVEMBER AND DECEMBER.

 1/81  SYSTEM                                                                744

 2/81  SYSTEM                                                                672

 3/81  SYSTEM                                                                744

       «* PROBLEMS/SOLUTIONS/COMMENTS

                         THE FIRST QUARTER 1981 DATA IS NOT AVAILABLE AT THIS TIME;  HOWEVER THE
                         DATA WILL BE AVAILABLE IN THE SECOND QUARTER 1981 REPORT.
                                              E-5

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

                                           APPENDIX E
                DESIGN AND PERFORMANCE DATA FOR OPERATIONAL FOREIGN FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
COUNTRY
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - V.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTUPE CONTENT - V.
     AVERAGE SULFUR CONTENT - V.
     RANGE SULFUR CONTENT - V.
     AVERAGE CHLORIDE CONTENT - V.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL
ELECTRIC POWER DEVELOPMENT
ISOGO
YOKOHAMA
JAPAN
******
   20.
   58.
******
  238
  265
  238
*****
  265
(   .046 LB/MMBTU)
(   .135 LB/MMBTU)
<****** LB/MMBTU)
IHI
PULVERIZED COAL
BASE
  405.36
  170.0
  122.
CARBON STEEL
    3.7
  859000 ACFM)
  338 F)
  400 FT)
               (  12.0 FT)
COAL
******
25958.

   16.00
15.0-17.0
    7.00
6.0-8.0
     .60
0.2-0.6
********
******
(  11160 BTU/LB)
 11160-11520
 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** ESP
     NUMBER
     TYPE
     SUPPLIER
     INLET FLUE GAS CAPACITY - CU.M/S
     INLET FLUE GAS TEMPERATURE - C
     PARTICLE REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     NUMBER
     NUMBER OF SPARES
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - LITER/CU.M
 0
NONE
COLD SIDE
TOYO ENGINEERING
  353.2        ( 748362 ACFM)
  150.0        (  302 F)
   98.0
 1
 0
VENTURI TOWER
NR
NR
IHI-CHEMICO
43.6 DIA X 101.4
CARBON STEEL
AISI 1110
ORGANIC
GLASS FLAKE-FILLED POLYESTER
NONE
 1
 2194.1        (34827 GPM)
    9.4        (70.0 GAL/1000ACF)
                                             E-6

-------
                                                  UTILITY FGD SURVEY:  OCTOBER  1983 - SEPTEMBER  198*
ELECTRIC POWER DEVELOPMENT:  IS060 1  (CONT.)

     PRESSURE DROP  -  KPA
     SUPERFICIAL GAS  VELOCITY  - M/S
     INLET  GAS FLOW RATE - CU.M/S
     INLET  GAS TEMPERATURE - C

*»* FGO SYSTEM

 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     DEVELOPMENT  LEVEL
     NEW/RETROFIT
     UNIT  DESIGN  PARTICLE REMOVAL EFFICIENCY
     UNIT  DESIGN  S02  REMOVAL EFFICIENCY - X
     CURRENT STATUS
     COMMERCIAL START-UP
     INITIAL START-UP

 «* DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 «* ABSCP.BER
     NUMBER
     NUMBER OF SPARES
     GENERIC TYPE
     SPECIFIC  TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     DIMENSIONS  - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF  CONTACTING ZONES
     LIQUID PECIRCULATION RATE - LITER/S
     L/G RATIO  -  L/CU.M
     GAS-SIDE  PRESSURE DROP - KPA
     SUPERFICAL  GAS VELOCITY - M/SEC
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C
     PARTICLE  REMOVAL EFFICENCY - X

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     GENERIC TYPE
     SPECIFIC  TYPE
     TRADE NAME/COMMON TYPE
     CONFIGURATION
     NUMBER OF STAGES
     NUMBER OF PASSES PER STAGE
     PRESSURE  DROP - KPA
     SUPEPFICAL GAS VELOCITY - M/S
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     WASH FREQUENCY

 ** REHEATER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     TEMPERATURE INCREASE - C
     INLET FLUE  GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE
     1.5
     3.0
   170.0
               (  5.9  IN-H20)
               (    10.0  FT/S)
               (  899864  ACFM)
               (   338 F)
 SALEABLE PRODUCT
 WET SCRUBBING
 LIMESTONE
 IHI-CHEMICO
 FULL SCALE
 RETROFIT
X   97.00
    95.00
  1
  3/76
 12/75
 NR
 NR
  1
  0
 VENTURI TOWER
 NR
 NR
 IHI/CHEMICO
 43.5 DIA X 76.8
 CARBON STEEL
 NR
 N/A
 ORGANIC
 GLASS FLAKE-FILLED POLYESTER
 NR
 NONE
  1
  2194.
     9.4
     1.5
     3.0
   566.28
    55.0
    96.7
               (34827 GPM)
               (  70.0 GAL/1000 ACF)
               (  5.9 IN-H20)
               (  10.0 FT/S)
               (1200000 ACFM)
               (   131 F)
                ( 2.0 IN-H20)
                (  9.8 FT/S)
PRIMARY COLLECTOR
IMPINGEMENT
BAFFLE
CLOSED VANE
HORIZONTAL
    4
    4
     .5
    3.0
ORGANIC
NR
INTERMITTENT
 DIRECT COMBUSTION
 NR
 OIL
    83.9         (   151  F)
   120.0         (   248  F)
 NR
                                             E-7

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

ELECTRIC POWER DEVELOPMENT: ISOGO 1 (CONT.)
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     NUMBER
     NUMBER OF SPARES
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     FLUE GAS FLOW RATE - CU.M/S
     FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

 ** TANKS
     SERVICE
     WASTE SLURRY BLEED
     ABSORBER RECYCLE
     REAGENT PREP PRODUCT
     THICKENER OVERFLOW
     VACUUM FILTER FILTRATE
     SPARGER/OXIDIZER

 ** PUMPS
     SERVICE
     SLURRY MAKEUP
     ABSORBER RECIRCULATION
     OXIDATION TOWER SUPPLY TRANSFER
     FILTRATE

 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUMBER
     NUMBER OF SPARES
     FEED STREAM CHARACTERISTICS
     OUTLET STREAM CHARACTERISTICS

 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUMBER
     NUMBER OF SPARES
     DIMENSIONS - FT
     FEED STREAM CHARACTERISTICS
     OUTLET STREAM CHARACTERISTICS

*** SALEABLE BYPRODUCTS
     NATURE
     FULL LOAD QUANTITY - M T/H
     DISPOSITION

*** SLUDGE
                                                NR
 2
 0
NR
BOOSTER
NR
NR
  362.14
  170.0
NR
NR
NR
NR
NR
NR
NR
NR
WET BALL MILL
NR
NR
                                                NUMBER
(  767400 ACFM)
(   338 F)
   1
****
   1
   1
   1
   1
NUMBER

   3
   8
   2
   2
CENTRIFUGE
18. 57. SOLIDS
90X SOLIDS
THICKENER
 1
0
20.0 DIA X 10.0
8.5X SOLIDS
18.6X SOLIDS
GYPSUM
    4.53
MARKETED
(   5.00 TPH)
                                             E-8

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

ELECTRIC  POWER  DEVELOPMENT: ISOGO 1 (CONT.)


 ** TREATMENT
     METHOD                                      FORCED OXIDATION
     DEVICE                                      OXIDATION TANK
     PROPRIETARY PROCESS                        N/A

 ** DISPOSAL
     NATURE                                      NR
     TYPE                                       NR
     SITE TREATMENT                             NR

 ** PROCESS  CONTROL AND INSTRUMENTATION
     CHEMICAL PARAMETERS                        PH
     PROCESS CONTROL MANNER                     AUTOMATIC
     PROCESS CHEMISTRY MODE                     FEEDBACK

 «» WATER BALANCE
     WATER LOOP TYPE                            OPEN
     POND SEEPAGE/RUNOFF WATER LOSS - LITERS/S  40
     MAKEUP  WATER ADDITION - LITERS/S              22.3        (  354 GPM)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  7. REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


 4/78  SYSTEM                                                                720

 5/78  SYSTEM                                                                744

 6/78  SYSTEM                                                                720

 7/78  SYSTEM                                                                744

 8/78  SYSTEM                                                                744

 9/78  SYSTEM                                                                720

10/78  SYSTEM                                                                744

11/78  SYSTEM                                                                720

12/78  SYSTEM                                                                744

 1/79  SYSTEM                                                                744

 2/79  SYSTEM                                                                672

 3/79  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         100X AVAILABILITY FOR THE FGD SYSTEM WAS REPORTED DURING THE PERIOD APRIL
                         1978 THROUGH MARCH 1979. THE SYSTEM S02 REMOVAL EFFICIENCY WAS REPORTEDLY
                         AVERAGING 952.

 4/79  SYSTEM                                                                720

 5/79  SYSTEM                                                                744

 6/79  SYSTEM                                                                720

 7/79  SYSTEM                                                                744

 8/79  SYSTEM                                                                744

 9/79  SYSTEM                                                                720

10/79  SYSTEM                                                                744
                                             E-9

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

ELECTRIC POWER DEVELOPMENT: ISOGO 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER   FGO   CAP.
                                                                S02  PART. HOURS HOURS  HOURS  FACTOR


11/79  SYSTEM                                                                720

12/79  SYSTEM                                                                744

 1/80  SYSTEM                                                                744

 2/80  SYSTEM                                                                696

 3/80  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO INFORMATION MAS AVAILABLE FOR THE APRIL 1979 THROUGH MARCH 1980 PERIOD.

 4/80  SYSTEM     100.0       100.0       100.0       100.0                  720   720    720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE FGD SYSTEM OPERATED ALONG WITH THE BOILER FOR THE ENTIRE MONTH OF
                         APRIL.

 5/80  SYSTEM     100.0       100.0       100.0        52.8                  744   393    393

 6/80  SYSTEM     100.0       100.0       100.0        10.0                  720    72     72

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER WAS SHUT DOWN FROM MAY 17 TO JUNE 27 FOR ANNUAL MAINTEN-
                         ANCE.  THE FGD SYSTEM WAS OPERATED DURING ALL OF THE BOILER OPERATION
                         IN MAY AND JUNE.

                                                                             744   744    744  90.9

                                                                             744   744    744  91.9

                                                                             720   718    718  90.4

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING SEPTEMBER THE BOILER WAS OUT OF SERVICE FOR APPROXIMATELY TWO HOURS
                         TO CHANGE THE TAP ON THE MAIN TRANSFORMER.

                                                                             744   680    680  84.5

                                                                             720   720    720  91.7

                                                                             744   744    744  93.2

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING JULY THROUGH DECEMBER THE FGD SYSTEM EXPERIENCED NO OPERATIONAL
                         PROBLEMS.

 1/81  SYSTEM                                                                744

 2/81  SYSTEM                                                                672

 3/81  SYSTEM                                                                744
7/80 SYSTEM
8/80 SYSTEM
9/80 SYSTEM
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
99.8
10/80 SYSTEM
11/80 SYSTEM
12/80 SYSTEM
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
91.4
100.0
100.0
                                             E-10

-------
                                                  UTILITY F6D  SURVEY:  OCTOBER  1983  - SEPTEMBER  1984

ELECTRIC  POWER DEVELOPMENT:  ISOGO 1  (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE  AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER   BOILER   FGD    CAP.
                                                                S02  PART.  HOURS HOURS   HOURS  FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE FIRST QUARTER 1981 DATA IS NOT AVAILABLE AT THIS TIME;   HOWEVER THE
                         DATA WILL BE AVAILABLE IN THE SECOND QUARTER 1981  REPORT.
                                              E-ll

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 198*

                                           APPENDIX E
                DESIGN AND PERFORMANCE DATA FOR OPERATIONAL FOREIGN FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
COUNTRY
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - V.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RAtJGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RAN3E CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** ESP
     NUMBER
     INLET FLUE GAS CAPACITY - CU.M/S
     INLET FLUE GAS TEMPERATURE - C
     PARTICLE REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     NUMBER
     NUMBER OF SPARES
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATICN RATE - LITER/S
     L/G RATIO - LITER/CU.M
     PRESSURE DROP - KPA
     SUPERFICIAL GAS VELOCITY - M/S
{   .046 LB/MMBTU1
(   .135 LB/MMBTU)
(****** LB/MMBTU)
ELECTRIC POWER DEVELOPMENT
ISOGO
2
YOKOHAMA
JAPAN
******
   20.
   58.
******
  238
  265
  238
  246
  265
IHI
PULVERIZED COAL
BASE
  405.36       (
  170.0        (
  140.         (
CARBON STEEL
    3.7        (  12.0 FT)
  859000 ACFM)
  338 F)
  460 FT)
COAL
******
25958.

   16.00
15.0-17.0
    7.00
6.0-8.0
     .60
0.2-0.6
********
******
 0
NONE
  356.6
  150.0
   98.0
(  11160 BTU/LB)
 11160-11520
(  755654 ACFM)
(   302 F)
 1
 0
VENTURI TOWER
NR
NR
IHI-CHEMICO
43.6 DIA X 101.4
CARBON STEEL
AISI 1110
ORGANIC
GLASS FLAKE-FILLED POLYESTER
NONE
 1
 2194.1        (34827 GPM)
    9.4        (70.0 GAL/1000ACF)
    1.5        ( 5.9 IN-H20)
    3.0        (   10.0 FT/S)
                                             E-12

-------
                                                  UTILITY FGD SURVEY:  OCTOBER  1983 -  SEPTEMBER  1984
ELECTRIC POWER DEVELOPMENT:  ISOGO  2  (CONT.)

     INLET GAS FLOW RATE  - CU.M/S
     INLET GAS TEMPERATURE - C

»«* FGD SYSTEM

 »* GENERAL  DATA
     SALEABLE PRODUCT/THROWAUAY PRODUCT
     S02 REMOVAL  MODE
     PROCESS TYPE
     SYSTEM  SUPPLIER
     DEVELOPMENT  LEVEL
     NEW/RETROFIT
     UNIT  DESIGN  PARTICLE REMOVAL EFFICIENCY
     UNIT  DESIGN  S02  REMOVAL EFFICIENCY - X
     ENERGY  CONSUMPTION - X
     CURRENT STATUS
     COMMERCIAL START-UP
     INITIAL START-UP

 »* DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/FRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 »* ABSORBER
     NUMBER
     NUMBER  OF SPARES
     GENERIC TYPE
     SPECIFIC  TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     DIMENSIONS  - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMSER  OF CONTACTING ZONES
     LIQUID  RECIRCULATION RATE - LITER/S
     L/G RATIO -  L/CU.M
     GAS-SIDE  PRESSURE DROP  - KPA
     SUFERFICAL GAS VELOCITY - M/SEC
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C
     PARTICLE  REMOVAL EFFICENCY - X

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     GENERIC TYPE
     SPECIFIC  TYPE
     TRADE NAME/COMMON TYPE
     CONFIGURATION
     NUMBER  OF STAGES
     NUMBER  OF PASSES PER STAGE
     PRESSURE  DROP - KPA
     SUPERFICAL GAS VELOCITY - M/S
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     WASH FREQUENCY

 ** REHEATER
     GENERIC TYPE
     SPECIFIC  TYPE
     TRADE NAME/COMMON TYPE
     TEMPERATURE INCREASE - C
     INLET FLUE GAS FLOW RATE - CU. M/S
     INLET FLUE  GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE
   424.6
   170.0
               (  699864 ACFM)
               (   338 F)
 SALEABLE PRODUCT
 WET SCRUBBING
 LIMESTONE
 IHI-CHEMICO
 FULL SCALE
 RETROFIT
X   97.00
    95.00
     3.0
  1
  5/76
  3/76
 NR
 NR
 1
 0
VENTURI TOWER
NR
NR
IHI/CHEMICO
43.5 DIA X 76.8
CARBON STEEL
NR
N/A
ORGANIC
GLASS FLAKE-FILLED POLYESTER
NR
NONE
 1
 2194.
    9.4
    1.5
    3.0
  566.28
   55.0
   96.7
                (34827 GPM)
                ( 70.0 GAL/1000 ACF)
                (5.9 IN-H20)
                (10.0 FT/S)
                (1200000 ACFM)
                (  131 F)
 PRIMARY COLLECTOR
 IMPINGEMENT
 BAFFLE
 CLOSED VANE
 HORIZONTAL
     4
     4
       .5         (
     3.0         (
 ORGANIC
 NR
 INTERMITTENT
                 2.0 IN-H20)
                  9.8 FT/S)
DIRECT COMBUSTION
NR
OIL
83.9
132.50
120.0
NR


( 151 F)
( 280783 ACFM)
( 248 F)

                                             E-13

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

ELECTRIC POWER DEVELOPMENT: ISOGO 2 (CONT.)
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     NUMBER
     NUMBER OF SPARES
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     FLUE GAS FLOW RATE - CU.M/S
     FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

 ** TANKS
     SERVICE
     WASTE SLUP.PY BLEED
     REAGENT PREP PRODUCT
     THICKENER OVERFLOW
     VACUUM FILTER FILTRATE
     SPARGER/OXIDIZER

 **  PUMPS
     SERVICE
      SLURRY MAKEUP
      ABSORBER RECIRCULATION
      OXIDATION TOWER SUPPLY TRANSFER
      FILTRATE

  **  SOLIDS CONCENTRATING/DEWATERING
      DEVICE
      NUMBER
      NUMBER OF SPARES
      FEED STREAM CHARACTERISTICS
      OUTLET STREAM CHARACTERISTICS

  *»  SOLIDS CONCENTRATING/DEWATERING
      DEVICE
      NUMBER
      NUMBER OF SPARES
      DIMENSIONS - FT
      FEED STREAM CHARACTERISTICS
      OUTLET STREAM CHARACTERISTICS

***  SALEABLE BYPRODUCTS
      NATURE
      FULL LOAD QUANTITY - M T/H
      DISPOSITION

**#  SLUDGE
                                                NR
 Z
 0
NR
BOOSTER
NR
NR
  362.1
  170.0
NR
NR
NR
NR
NR
NR
NR
NR
WET BALL MILL
NR
NR
                                                NUMBER
(  767400 ACFM)
(   338 F)
NUMBER

   2
   8
   2
   2
CENTRIFUGE
 4
0
18.57. SOLIDS
90X SOLIDS
THICKENER
 1
0
20.0 DIA X 10.0
8.SX SOLIDS
18.6X SOLIDS
GYPSUM
    4.53
MARKETED
(   5.00 TPH)
                                             E-14

-------
                                                  UTILITY FSD SURVEY: OCTOBER 1983  -  SEPTEMBER 1984

ELECTRIC POWER  DEVELOPMENT:  ISOGO Z (CONT.)


 ** TREATMENT
     METHOD                                      FORCED OXIDATION
     DEVICE                                      OXIDATION TANK
     PROPRIETARY PROCESS                        N/A

 »* DISPOSAL
     NATURE                                      NR
     TYPE                                        NR
     SITE  TREATMENT                             NR

 ** PROCESS  CONTROL AND INSTRUMENTATION
     CHEMICAL  PARAMETERS                        PH
     PROCESS CONTROL MANNER                     AUTOMATIC
     PROCESS CHEMISTRY MODE                     FEEDBACK

 ** WATER  BALANCE
     MATER LOOP TYPE                            OPEN
     POND  SEEPAGE/RUNOFF WATER LOSS - LITERS/S  40
     MAKEUP  WATER ADDITION - LITERS/S              22.3         (   354 GPM)
 	PERFORMANCE DATA	
 PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION   7.  REMOVAL   PER   BOILER   FGD   CAP.
                                                                 S02   PART.  HOURS HOURS  HOURS FACTOR


 4/78  SYSTEM                                                                 720

 5/78  SYSTEM                                                                 744

 6/78  SYSTEM                                                                 720

 7/78  SYSTEM                                                                 744

 8/78  SYSTEM                                                                 744

 9/78  SYSTEM                                                                 720

 10/78  SYSTEM                                                                 744

 11/78  SYSTEM                                                                 720

 12/78  SYSTEM                                                                 744

 1/79  SYSTEM                                                                 744

 2/79  SYSTEM                                                                 672

 3/79  SYSTEM                                                                 744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         1002 AVAILABILITY  FOR  THE  FGD  SYSTEM WAS REPORTED DURING THE PERIOD APRIL
                         1978 THROUGH MARCH 1979.   THE  FGD  SYSTEM LOGGED A TOTAL OF 1,689 HOURS OF
                         OPERATION.

 4/79  SYSTEM                                                                 720

 5/79  SYSTEM                                                                 744

 6/79  SYSTEM                                                                 720

 7/79  SYSTEM                                                                 744

 8/79  SYSTEM                                                                 744

 9/79  SYSTEM                                                                 720

 10/79  SYSTEM                                                                 744
                                              E-15

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

ELECTRIC POWER DEVELOPMENT: ISOGO 2 (COKT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER   FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS  FACTOR


11/79  SYSTEM                                                                720

12/79  SYSTEM                                                                744

 1/80  SYSTEM                                                                744

 2/80  SYSTEM                                                                696

 3/80  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO INFORMATION WAS AVAILABLE FOR THE APRIL 1979 THROUGH MARCH 1980 PERIOD.

 4/80  SYSTEM     100.0       100.0       100.0        31.3                  720   225    225

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         ON MARCH 30 THE BOILER WAS SHUTDOWN FOR ANNUAL MAINTENANCE.  THE UNIT
                         REMAINED DOWN THROUGH APRIL 20.  WHEN OPERATIONS COMMENCED THE FGD SYSTEM
                         OPERATED WITH THE BOILER FOR THE REST OF THE MONTH.

 5/80  SYSTEM     100.0       100.0       100.0       100.0                  744   744    744

 6/80  SYSTEM     100.0       100.0       100.0       100.0                  720   720    720

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING MAY AND JUNE THE FGD SYSTEM OPERATED WITH NO REPORTED PROBLEMS.

 7/80  SYSTEM     100.0       100.0       100.0        88.2                  744   656    656  82.0

       »» PROBLEMS/SOLUTIONS/COMMENTS

                         DURING JULY THE BOILER WAS OFF LINE APPROXIMATELY 88 HOURS FOR MAINTEN-
                         ANCE.

 8/80  SYSTEM     100.0       100.0       100.0       100.0                  744   744    744  91.9

 9/80  SYSTEM     100.0       100.0       100.0        99.8                  720   718    718  92.1

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         APPROXIMATELY TWO HOURS OF BOILER OUTAGE TIME WAS NECESSARY TO CHANGE
                         THE TAP OF THE MAIN TRANSFORMER.

                                                                             744   744    744  92.2

                                                                             720   720    720  92.7

                                                                             744   744    744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING JULY THROUGH DECEMBER THE FGD SYSTEM OPERATED WITH NO PROBLEMS.

 1/81  SYSTEM                                                                744

 2/81  SYSTEM                                                                672

 3/81  SYSTEM                                                                744
10/80 SYSTEM
11/80 SYSTEM
12/80 SYSTEM
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
                                             E-16

-------
                                                  UTILITY  F6D  SURVEY: OCTOBER  1983 - SEPTEMBER 1984

ELECTRIC  POWER DEVELOPMENT:  ISOGO Z  (CONT.)
	PERFORMANCE  DATA	
PERIOD MODULE  AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL    PER   BOILER   F6D   CAP.
                                                                S02  PART.  HOURS HOURS  HOURS  FACTOR


       »* PROBLEMS/SOLUTIONS/COMMENTS

                         THE FIRST QUARTER 1981 DATA IS NOT AVAILABLE AT THIS TIME;   HOWEVER THE
                         DATA WILL BE AVAILABLE IN THE SECOND QUARTER 1981  REPORT.
                                              E-17

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

                                           APPENDIX E
                DESIGN AND PERFORMANCE DATA FOR OPERATIONAL FOREIGN FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
COUNTRY
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MM
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - '/.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - Y.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** ESP
     NUMBER
     TYPE
     SUPPLIER
     INLET FLUE GAS CAPACITY - CU.M/S
     INLET FLUE GAS TEMPERATURE - C
     PARTICLE REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     NUMBER
     NUMBER OF SPARES
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - LITER/CU.M
ELECTRIC POWER DEVELOPMENT
TAKASAGO
TAKASAGO
JAPAN
******
   37.
  ISO.
******
  230
  250
  230
  238
  250
               (   .086 LB/MMBTU)
               (   .350 LB/MMBTU)
               (****** LB/MMBTU)
                 774000 ACFM)
                 310 F)
               ( 590 FT)
               ( 11.9 FT)
               (  11160 BTU/LB)
                11160-11520
MITSUBISHI
******
BASE
  365.25
  154.4
  180.
CARBON STEEL
    3.6
COAL
******
25958.

   22.00
******
    7.00
******
    1.80
******
********
******
 0
NONE
COLD SIDE
MITSUBISHI HEAVY INDUSTRIES
  344.3        ( 729507 ACFM)
  154.4        (  310 F)
   99.5
 1
 0
VENTURI TOWER
NR
NR
MITSUI-CHEMICO
37.7 DIA X 62.3
CARBON STEEL
AISI 1110
ORGANIC
NR
NONE
 1
 1228.8        (19505 GPM)
    6.5        (48.6 GAL/1000ACF)
                                             E-1C

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER
ELECTRIC  POWER DEVELOPMENT:  TAKASAGO 1  (CONT.)

     PRESSURE DROP  -  KPA
     INLET  GAS FLOW RATE - CU.M/S
     INLET  GAS TEMPERATURE - C
     S02  REMOVAL  EFFICENCY - X
     PARTICLE REMOVAL EFFICIENCY - X

«** FGD SYSTEM

 ** GENERAL DATA
     SALEABLE FRODUCT/THROWAWAY PRODUCT
     S02  REMOVAL  MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     DEVELOPMENT  LEVEL
     NEW/RETROFIT
     UNIT DESIGN  S02  REMOVAL EFFICIENCY - X
     ENERGY CONSUMPTION - X
     CURRENT STATUS
     INITIAL START-UP

 ** DESIGN AND OPERATING PARAMETERS

 »* QUENCHER/FRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 «* ABSORBER
     NUMBER
     NUMBER OF  SPARES
     GENERIC TYPE
     SPECIFIC  TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     DIMENSIONS  - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF  CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO  -  L/CU.M
     GAS-SIDE  PRESSURE DROP - KPA
     INLET GAS TEMPERATURE - C
     50Z REMOVAL EFFICIENCY - X

 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC  TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF  CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C
     S02 REMOVAL  EFFICIENCY - X

 «* ABSORBER
     NUMBER
     GENERIC TYPE
    1.5
  260.5
  154.4
   56.0
   50.0
(5.9 IN-H20)
(  552000 ACFM)
(   310 F)
SALEABLE PRODUCT
MET SCRUBBING
LIMESTONE
MITSUI-CHEMICO
FULL SCALE
RETROFIT
   93.00
    3.2
 1
 2/75
NR
NR
 1
 0
VENTURI TOWER
NR
NR
MITSUI/CHEMICO
45.9 DIA X 78.7
CARBON STEEL
NR
N/A
NR
NR
NR
NONE
 1
 2566.
    6.5
    1.5
   55.0
   85.0
(40727 GPM)
(  48.6 GAL/1000 ACF)
(  5.9 IN-H20)
(   131 F)
VENTURI TOWER
NR
NR
MITSUI/CHEMICO
26.2 DIA X 82.3
CARBON STEEL
NR
N/A
NR
NR
NR
NONE
 1
  610.
   69.37
  154.4
   63.0
SPRAY TOWER
( 9689 GPM)
( 147000 ACFM)
(  310 F)
                                             E-19

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER
ELECTRIC POWER DEVELOPMENT: TAKASAGO 1 (CONT.)

     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     NUMBER OF STAGES
     NUMBER OF PASSES PER STAGE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     WASH WATER SOURCE

 ** REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     INLET FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION  EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

 »* TANKS
     SERVICE
     CENTRIFUGE
     REAGENT PREP PRODUCT
     ABSORBER RECYCLE

 ** PUMPS
     SERVICE
NR
NR
MITSUI/CHEMICO
19.7 DIA X 65.0
CARBON STEEL
NR
N/A
NR
NR
NR
NONE
 1
 9986.
   18.26
               (»**»* 6PM)
               (   38686 ACFM)
               (   310 F)
PRIMARY COLLECTOR
IMPINGEMENT
BAFFLE
CLOSED VANE
    4
    4
NR
NR
BLENDED
DIRECT COMBUSTION
NR
OIL
  120.0        (   248 F)
NR
NR
NR
BOOSTER
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
WET BALL MILL
NR
NR
                                                NUMBER
     CIRCULATION
     PH ADJUSTER CIRCULATION
     REACTOR CIRCULATION
NUMBER

   5
   3
   3
                                             E-20

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

ELECTRIC  POWER  DEVELOPMENT:  TAKASAGO 1 (CONT.)


 «* SOLIDS CONCENTRATING/DEWATERING
     DEVICE                                     CENTRIFUGE
     NUMBER                                      7
     OUTLET STREAM CHARACTERISTICS              90X SOLIDS

 »* SOLIDS CONCENTRATING/DEWATERING
     DEVICE                                     THICKENER
     OUTLET STREAM CHARACTERISTICS              20X SOLIDS

**» SALEABLE BYPRODUCTS
     NATURE                                     GYPSUM
     FULL LOAD  QUANTITY - M T/H                     8.63       (  9.50 TPH)

»»* SLUDGE

 «» TREATMENT
     METHOD                                     FORCED OXIDATION
     DEVICE                                     OXIDATION TANK
     PROPRIETARY PROCESS                        N/A

 ** DISPOSAL
     NATURE                                     NR
     TYPE                                       NR
     SITE TREATMENT                             NR

 »* PROCESS CONTROL AND INSTRUMENTATION
     CHEMICAL PARAMETERS                        FLUE GAS VOLUME t 502 CONCENTRATION

 ** HATER BALANCE
     WATER LOOP TYPE                            OPEN
     POND SEEPAGE/RUNOFF WATER LOSS - LITERS/S  40
     MAKEUP WATER ADDITION - LITERS/S              13.1        (  208 GPM)
 	PERFORMANCE DATA	
 PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


  2/75  SYSTEM                  96.9                    88.8                  672   616    597

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         THE FGD SYSTEM WAS DOWN ONCE DUE TO A  PIPING  FLANGE LEAK.

  3/75  SYSTEM                 100.0                    48.4                  744   360    360

  4/75  SYSTEM                 100.0                    44.1                  720   318    318

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER WAS TAKEN OFF-LINE FOR ANNUAL MAINTENANCE  DURING MARCH  AND
                         APRIL.

  5/75  SYSTEM                 100.0                    96.4                  744   717    717

  6/75  SYSTEM                  97.9                    97.9                  720   720    705

  7/75  SYSTEM                  98.0                    97.8                  744   743    728

  8/75  SYSTEM                  98.0                    98.0                  744   744    729

  9/75  SYSTEM                  95.7                    91.7                  720   690    660
                                              E-21

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

ELECTRIC POWER DEVELOPMENT: TAKASAGO 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER   FGD   CAP.
                                                                SQZ  PART. HOURS HOURS  HOURS  FACTOR


       «* PROBLEMS/SOLUTIONS/COMMENTS

                         SYSTEM DOWN TIME FROM JUNE THROUGH SEPTEMBER WAS DUE TO MIST ELIMINATOR
                         SCALING.

10/75  SYSTEM                  95.2                    95.2                  744   744    708

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         FAN VIBRATIONS CAUSED A SYSTEM OUTAGE DURING THE MONTH.

11/75  SYSTEM                  98.5                    98.5                  720   720    709

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         MIST ELIMINATOR SCALING WAS ENCOUNTERED IN NOVEMBER.

12/75  SYSTEM                  95.9                    92.2                  744   715    686

 1/76  SYSTEM                 100.0                   100.0                  744   744    744

 2/76  SYSTEM                  95.2                    90.8                  696   664    632

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING FEBRUARY, THE SYSTEM AGAIN ENCOUNTERED MIST ELIMINATOR SCALING.

 3/76  SYSTEM                 100.0                    92.3                  744   687    687

 4/76  SYSTEM                 100.0                    30.4                  720   219    219

 5/76  SYSTEM                 100.0                   100.0                  744   744    744

 6/76  SYSTEM                 100.0                   100.0                  720   720    720

 7/76  SYSTEM                 100.0                   100.0                  744   744    744

 8/76  SYSTEM                                                                744   744

 9/76  SYSTEM                 100.0                   100.0                  720   720    720

10/76  SYSTEM                  91.7                    91.7                  744   744    682

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE SYSTEM WAS TAKEN OFF-LINE FOR CLEANING OF THE FIRST STAGE SCRUBBER.

11/76  SYSTEM                  99.3                    99.3                  720   720    715

       #» PROBLEMS/SOLUTIONS/COMMENTS

                         REPAIR OF A DUCT FORCED ONE SYSTEM OUTAGE DURING THE MONTH.

12/76  SYSTEM                  98.9                    98.9                  744   744    736

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         A DECEMBER OUTAGE WAS DUE TO THE REPAIR OF A SPRAY PIPE.

 1/77  SYSTEM                  99.3                    99.3                  744   744    739
                                             E-22

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 198*

ELECTRIC POWER DEVELOPMENT: TAKASAGO 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE SYSTEM WAS TAKEN OFF-LINE ONCE FOR CLEANING OF THE FIRST STAGE
                         SCRUBBER.

 2/77  SYSTEM                 100.0                   100.0                  672   672    672

 3/77  SYSTEM                                            .0                  744     0      0

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE SYSTEM WAS OFF DURING MARCH FOR ANNUAL BOILER MAINTENANCE.

 4/77  SYSTEM                 100.0                    71.3                  720   513    513

 5/77  SYSTEM                  98.7                    98.7                  744   744    734

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         FAN VIBRATIONS CAUSED ONE SYSTEM OUTAGE DURING MAY.

 6/77  SYSTEM                 100.0                   100.0                  720   720    720

 7/77  SYSTEM                 100.0                    96.4                  744   717    717

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE FIRST STAGE ABSORBER WAS CLEANED DURING JULY.

 8/77  SYSTEM                 100.0                   100.0                  744   744    744

 9/77  SYSTEM                 100.0                   100.0                  720   720    720

 10/77  SYSTEM                  94.2                    94.2                  744   744    701

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE SYSTEM WAS OFF  LINE  PART OF THIS MONTH FOR CLEANING  OF  THE  SCRUBBERS
                         AMD REACTORS.

 11/77  SYSTEM                 100.0                   100.0                  720   720    720

 12/77  SYSTEM                 100.0                   100.0                  744   744    744

 1/78  SYSTEM                 100.0                   100.0                  744   744    744

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         THE FIRST REACTOR WAS CLEANED THIS  MONTH.

 4/78  SYSTEM                                                                720

 5/78  SYSTEM                                                                744

 6/78  SYSTEM                                                                 720

 7/78  SYSTEM                                                                744

 8/78  SYSTEM                                                                 744

 9/78  SYSTEM              -                                                   720

 10/78  SYSTEM                                                                 744

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

ELECTRIC POWER DEVELOPMENT: TAKASAGO 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


11/78  SYSTEM                                                                720

12/78  SYSTEM                                                                74*

 1/79  SYSTEM                                                                744

 2/79  SYSTEM                                                                672

 3/79  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING APRIL 1978 THROUGH MARCH 1979 NO FORCED OUTAGES OCCURRED.  THE FGD
                         SYSTEM AVAILABILITY WAS 99.9X, AND LOGGED A TOTAL OF 7823.4 HOURS OF
                         OPERATION WITH 6.1 HOURS OF SCHEDULED OUTAGE TIME.

 4/79  SYSTEM                                                                720

 6/79  SYSTEM                                                                720

 7/79  SYSTEM                                                                744

 8/79  SYSTEM                                                                744

 9/79  SYSTEM                                                                720

10/79  SYSTEM                                                                744

11/79  SYSTEM                                                                720

12/79  SYSTEM                                                                744

 1/80  SYSTEM                                                                744

 2/80  SYSTEM                                                                696

 3/80  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO INFORMATION WAS AVAILABLE FOR THE APRIL 1979 THROUGH MARCH 1980 PERIOD.

 4/80  SYSTEM     100.0       100.0       100.0        31.1                  720   224    224

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER WAS SHUTDOWN ON MARCH 29 FOR ANNUAL MAINTENANCE.  THE UNIT
                         REMAINED OFF LINE THROUGH APRIL 21.  WHEN OPERATIONS COMMENCED THE FGD
                         SYSTEM OPERATED WITH THE BOILER FOR THE REST OF THE MONTH.

 5/80  SYSTEM     100.0       100.0       100.0       100.0                  744   744    744

 6/80  SYSTEM     100.0       100.0       100.0       100.0                  720   720    720

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         THE FGD SYSTEM EXPERIENCED NO PROBLEMS DURING THE MAY-JUNE PERIOD.

 7/80  SYSTEM     100.0       100.0       100.0       100.0                  744   74*    744  33.4

 8/80  SYSTEM     100.0       100.0       100.0       100.0                  744   744    744  83.6

 9/60  SYSTEM     100.0       100.0       100.0       100.0                  720   720    720  83.3
                                             E-24

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER

ELECTRIC POWER DEVELOPMENT: TAKASAGO 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       «* PROBLEMS/SOLUTIONS/COMMENTS

                         NO PROBLEMS WERE ENCOUNTERED DURING THE THIRD QUARTER 1980.

10/80  SYSTEM      99.5        99.5        99.5        99.5                  7**   7**    7*0  85.3

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE FGD SYSTEM UAS SHUT DOWN FOR APPROXIMATELY FOUR HOURS IN OCTOBER FOR
                         AH INSPECTION OF THE SECOND SCRUBBER OUTLET DUCT AND THE MIST ELIMINATOR.
                         THE INSPECTION REVEALED THAT NO PROBLEM EXISTED.

11/80  SYSTEM     100.0       100.0       100.0       100.0                  720   720    720  85.0

12/80  SYSTEM     100.0       100.0       100.0       100.0                  7**   7**    7**  89.9

       »* PROBLEMS/SOLUTIOHS/COMMENTS

                         NO PROBLEMS WERE ENCOUNTERED DURING NOVEMBER AND DECEMBER.

  1/81  SYSTEM                                                                7**

  2/81  SYSTEM                                                                672

  3/81  SYSTEM                                                                7**

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE FIRST QUARTER 1981 DATA IS NOT AVAILABLE AT THIS TIME;  HOWEVER THE
                         DATA WILL BE AVAILABLE IN THE SECOND QUARTER 1981 REPORT.
                                              E-25

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

                                           APPENDIX E
                DESIGN AND PERFORMANCE DATA FOR OPERATIONAL FOREIGN FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
COUNTRY
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RAN3E HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** ESP
     NUMBER
     TYPE
     SUPPLIER
     INLET FLUE GAS CAPACITY - CU.M/S
     INLET FLUE GAS TEMPERATURE - C
     PARTICLE REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     NUMBER
     NUMBER OF SPARES
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - LITER/CU.M
               (   .086 LB/MMBTU)
               (   .350 LB/MMBTU)
               (****** LB/MMBTU)
ELECTRIC POWER DEVELOPMENT
TAKASAGO
2
TAKASAGO
JAPAN
******
   37.
  150.
******
  230
  250

  238
  250
MITSUBISHI
******
BASE
  365.25
  154.4
  180.
CARBON STEEL
    3.6
                 774000 ACFM)
                 310 F)
                 590 FT)
               (  11.9 FT)
               (  11160 BTU/LB)
                11160-11520
COAL
******
25958.

   22.00
******
    7.00
******
    1.80
******
********
******
 0
NONE
COLD SIDE
MITSUBISHI HEAVY INDUSTRIES
  344.3        ( 729507 ACFM)
  154.4        (  310 F)
   99.5
 1
 0
VENTURI TOWER
NR
NR
MITSUI-CHEMICO
37.7 DIA X 62.3
CARBON STEEL
AISI 1110
ORGANIC
NR
NONE
 1
 1542.2        (24480 GPM)
    6.5        (48.6 GAL/1000ACF)
                                             E-26

-------
                                                  UTILITY FGD  SURVEY:  OCTOBER  1983  - SEPTEMBER
ELECTRIC  POWER  DEVELOPMENT:  TAKASAGO 2 (CONT.)

     PRESSURE DROP - KPA
     INLET GAS  FLOW RATE - CU.M/S
     INLET GAS  TEMPERATURE - C
     S02  REMOVAL EFFICENCY - X
     PARTICLE REMOVAL EFFICIENCY - X

«»* FGD SYSTEM

 ** GENERAL DATA
     SALEABLE PRODUCT/THROMAWAY PRODUCT
     S02  REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     ENERGY CONSUMPTION - X
     CURRENT STATUS
     INITIAL START-UP

 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 «* ABSORBER
     NUMBER
     NUMBER OF SPARES
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - L/CU.M
     GAS-SIDE PRESSURE DROP - KPA
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C
     S02 REMOVAL EFFICIENCY - X

 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C
     S02 REMOVAL EFFICIENCY - X
    1.5
  260.5
  154.4
   56.0
   50.0
(5.9 IN-H20)
(  552000 ACFM)
(   310 F)
SALEABLE PRODUCT
WET SCRUBBING
LIMESTONE
MITSUI-CHEMICO
FULL SCALE
RETROFIT
   93.00
    3.2
 1
 3/76
NR
NR
 1
 0
VENTURI TOWER
NR
NR
MITSUI/CHEMICO
45.9 DIA X 78.7
CARBON STEEL
NR
N/A
NR
NR
NR
NONE
 1
 2066.
    6.5
    1.5
  280.24
   55.0
   85.0
(32801 GPM)
( 48.6 GAL/1000 ACF)
( 5.9 IN-H20)
( 593855 ACFM)
(  131 F)
VENTURI TOWER
NR
NR
MITSUI/CHEMICO
26.2 DIA X 82.3
CARBON STEEL
NR
N/A
NR
NR
NR
NONE
 1
  743.
   69.37
  154.4
   63.0
(11799 GPM)
( 147000 ACFM)
(  310 F)
                                             E-27

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER

ELECTRIC POWER DEVELOPMENT: TAKASAGO 2 (CONT.)
 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     NUMBER OF STAGES
     NUMBER OF PASSES PER STAGE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     WASH WATER SOURCE

 ** REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     INLET FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 »* FANS
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 *# DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION  EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

 »* TANKS
     SERVICE
SPRAY TOWER
NR
NR
MITSUI/CHEMICO
CARBON STEEL
NR
N/A
NR
NR
NR
NONE
 1
19639.
   36.51
(»***# GPM)
(   77372 ACFM)
(   310 F)
PRIMARY COLLECTOR
IMPINGEMENT
BAFFLE
CLOSED VANE
    4
    4
NR
NR
BLENDED
DIRECT COMBUSTION
NR
OIL
  120.0        (  248 F)
NR
NR
NR
BOOSTER
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
WET BALL MILL
NR
NR
                                                NUMBER
     CENTRIFUGE
     REAGENT  PREP  PRODUCT
     ABSORBER RECYCLE
                                              E-28

-------
ELECTRIC POWER DEVELOPMENT: TAKASAGO 2 (CONT.)
                                                  UTILITY F60 SURVEY: OCTOBER 1983 - SEPTEMBER 198*
 #* PUMPS
     SERVICE
                                                NUMBER
    CIRCULATION                                    5
    PH ADJUSTER CIRCULATION                       2
    REACTOR CIRCULATION                           1

 »* SOLIDS CONCENTRATING/DEWATERING
    DEVICE                                      CENTRIFUGE
    NUMBER                                       7
    OUTLET STREAM CHARACTERISTICS              90X SOLIDS

 «* SOLIDS CONCENTRATING/DEWATERING
    DEVICE                                      THICKENER
    OUTLET STREAM CHARACTERISTICS              20X SOLIDS

«»» SALEABLE BYPRODUCTS
    NATURE                                      GYPSUM
    FULL LOAD QUANTITY - M T/H                     8.62

*** SLUDGE

 «* TREATMENT
    METHOD
    DEVICE
    PROPRIETARY  PROCESS

 »* DISPOSAL
    NATURE
    TYPE
    SITE TREATMENT

 »* PROCESS CONTROL AND INSTRUMENTATION
    CHEMICAL  PARAMETERS

 *» WATER BALANCE
    WATER  LOOP TYPE
    POND SEEPAGE/RUNOFF WATER LOSS - LITERS/S  40
    MAKEUP WATER ADDITION - LITERS/S              13.1
                                                               (  9.50 TPH)
                                                FORCED OXIDATION
                                                OXIDATION TANK
                                                N/A
                                                NR
                                                NR
                                                NR
                                                FLUE GAS VOLUME ft S02 CONCENTRATION


                                                OPEN

                                                               (  208 GPM)
 	PERFORMANCE DATA	T	
 PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  7. REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS  FACTOR
  3/76  SYSTEM

  4/76  SYSTEM

  5/76  SYSTEM

  6/76  SYSTEM
                              100.0

                              100.0

                              100.0

                              100.0
100.0

100.0

 29.0

 87.8
744   744    720

720   720    720

744   216    216

720   632    632
       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE SYSTEM WAS DOWN  FOR  PART  OF MAY AND JUNE  FOR  ANNUAL  BOILER  MAINTENANCE.

  7/76  SYSTEM                 100.0                    100.0                   744    744    744

  8/76  SYSTEM                 100.0                    100.0                   744    744    744

  9/76  SYSTEM                 100.0                    100.0                   720    720    720

 10/76  SYSTEM                   94.2                     94.2                   744    744    701
                                              E-29

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 198*

ELECTRIC POWER DEVELOPMENT: TAKASAGO 2 (CONT. )




	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       ** PROBLEMS/SOLUTIONS/COMMENTS

                         OUTAGE TIME DURING OCTOBER WAS NECESSARY FOR DUCT CLEANING.

11/76  SYSTEM                 100.0                   100.0                  720   720    720

12/76  SYSTEM                  99.3                    99.3                  744   744    739

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE SYSTEM WAS DOWN BRIEFLY FOR REPAIR OF A GYPSUM CONVEYOR.

 1/77  SYSTEM                 100.0                   100.0                  744   744    744

 2/77  SYSTEM                  88.2                    88.2                  672   672    593

 3/77  SYSTEM                  98.7                    98.7                  744   744    734

       »» PROBLEMS/SOLUTIONS/COMMENTS

                         OUTAGE TIME IN FEBRUARY & MARCH WAS NEEDED FOR CLEANING OF A PH CONTROLLER.

 4/77  SYSTEM                 100.0                   100.0                  720   720    720

 5/77  SYSTEM                 100.0                    51.6                  744   384    384

 6/77  SYSTEM                 100.0                     3.3                  720   240    240

 7/77  SYSTEM                 100.0                   100.0                  744   744    744

 8/77  SYSTEM                 100.0                   100.0                  744   744    744

 9/77  SYSTEM                 100.0                   100.0                  720   720    720

10/77  SYSTEM                 100.0                   100.0                  744   744    744

11/77  SYSTEM                  89.2                    89.2                  720   720    642

       «* PROBLEMS/SOLUTIONS/COMI1ENTS

                         CLEANING OF THE PH CONTROLLER CAUSED ONE OUTAGE DURING NOVEMBER.

                         A REACTOR WAS ALSO CLEANED THIS MONTH.

12/77  SYSTEM                 100.0                   100.0                  744   744    744

 1/78  SYSTEM                                                                744   744

 2/78  SYSTEM                                                                672

 3/78  SYSTEM                                                                720

 4/78  SYSTEM                                                                720

 5/78  SYSTEM                                                                744

 6/78  SYSTEM                                                                720

 7/78  SYSTEM                                                                744

 8/78  SYSTEM                                                                744

 9/78  SYSTEM                                                                720
                                             E-30

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

ELECTRIC POWER DEVELOPMENT: TAKASAGO 2 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


10/78  SYSTEM                                                                744

11/78  SYSTEM                                                                720

12/78  SYSTEM                                                                71*

 1/79  SYSTEM                                                                744

 2/79  SYSTEM                                                                672

 3/79  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING THE PERIOD FROM APRIL 1978 THROUGH MARCH 1979 THE FGD SYSTEM
                         OPERATED WITH 99.SX AVAILABILITY.  THERE WERE NO FORCED OUTAGES DURING THIS
                         TIME.  A TOTAL OF 8147.4 HOURS OF FGO SYSTEM OPERATION WERE LOGGED WITH
                         19.5 HOURS OF SCHEDULED OUTAGE TIME.

 4/79  SYSTEM                                                                720

 5/79  SYSTEM                                                                744

 6/79  SYSTEM                                                                720

 7/79  SYSTEM                                                                744

 B/79  SYSTEM                                                                744

 9/79  SYSTEM                                                                720

10/79  SYSTEM                                                                744

11/79  SYSTEM                                                                720

12/79  SYSTEM                                                                744

 1/80  SYSTEM                                                                744

 2/80  SYSTEM                                                                696

 3/80  SYSTEM                                                                744

       »* PROBLEMS/SOLUTIONS/COMMENTS

                         NO INFORMATION WAS AVAILABLE FOR THE APRIL 1979 THROUGH MARCH  1980 PERIOD.

 4/80  SYSTEM     100.0       100.0       100.0       100.0                  720    720     720

 5/80  SYSTEM     100.0       100.0       100.0       100.0                  744    744     744

       *» PROBLEMS/SOLUTIONS/COMMENTS

                         DURING APRIL AND MAY THE UTILITY EXPERIENCED NO PROBLEMS WITH  THE FGO
                         SYSTEM.

 6/80  SYSTEM     100.0       100.0       100.0        24.6                  720    177     177

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER WAS SHUTDOWN FROM JUNE 3 TO JUNE 24 FOR ANNUAL  MAINTENANCE.
                         THE FGD SYSTEM OPERATED ALONG WITH THE BOILER THE REMAINDER  OF THE TIME.

 7/80  SYSTEM     100.0       100.0       100.0       100.0                  744    744     744   83.0
                                              E-31

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

ELECTRIC POWER DEVELOPMEKT: TAKASAGO 2 (CONT.)
PERIOD
8/80
9/80
10/80
11/80
12/80
MODULE AVAILABILITY
SYSTEM
SYSTEM
SYSTEM
SYSTEM
SYSTEM
100.0
100.0
100.0
100.0
100.0
OPERABILITY
100.0
100.0
100.0
100.0
100.0
	 HtKi-UKnAr
RELIABILITY
100
100
100
100
100
.0
.0
.0
.0
.0
UTILIZATION X REMOVAL PER BOILER
S02 PART. HOURS HOURS
100
100
100
100
87
.0
.0
.0
.0
.3
744
720
744
720
744
744
720
744
720
649
FGD
HOURS
744
720
744
720
649
CAP.
FACTOR
83.3
83.4
85.1
84.8
78.4
       ** PROBLEMS/SOLUTIONS/COMMENTS

                         DURING JULY THROUGH DECEMBER NO FGD-RELATED PROBLEMS WERE EXPERIENCED.

                         IN DECEMBER THE BOILER WAS OUT OF SERVICE APPROXIMATELY FOUR DAYS FOR
                         GENERAL MAINTENANCE.

 1/81  SYSTEM                                                                744

 2/81  SYSTEM                                                                672

 3/81  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE FIRST QUARTER 1981 DATA IS NOT AVAILABLE AT THIS TIME;  HOWEVER THE
                         DATA WILL BE AVAILABLE IN THE SECOND QUARTER 1981 REPORT.
                                             E-32

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                           APPENDIX E
                DESIGN AND PERFORMANCE DATA FOR OPERATIONAL FOREIGN FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
COUNTRY
REGULATORY CLASSIFICATION
PARTICULATE  EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MM
GROSS UNIT GENERATING CAPACITY - MM
NET UNIT GENERATING CAPACITY M/FGD - MM
NET UNIT GENERATING CAPACITY WO/FGD - MM
EQUIVALENT SCRUBBED CAPACITY - MM

 ** UNIT DATA - BOILER AND STACK
     BOILER  SUPPLIER
     BOILER  TYPE
     BOILER  SERVICE LOAD
     DESIGN  BOILER FLUE GAS FLOM - CU.M/S
     BOILER  FLUE GAS TEMPERATURE - C
     STACK  HEIGHT - M
     STACK  SHELL
     STACK  TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE  HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RAN3E  ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE  MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RAN3E SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

«** PARTICLE CONTROL

 *# MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** ESP
     NUMBER
     TYPE
     SUPPLIER
     INLET FLUE GAS CAPACITY - CU.M/S
     INLET FLUE GAS TEMPERATURE - C
     PARTICLE REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER  SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - LITER/CU.M
     PRESSURE DROP - KPA
     INLET GAS FLCM RATE - CU.M/S
               (   .130 LB/MMBTU)
               (   .630 LB/MMBTU)
               (*«**** LB/MMBTU)
ELECTRIC POMER DEVELOPMENT
TAKEHARA
1
MIHARA
JAPAN
******
   56.
  271.
******
  231
  250
  231
  239
  250
BABCOCK-HITACHI
PULVERIZED COAL
BASE
  577.13
  140.0
  201.
CARBON STEEL
    3.6
               (1223000 ACFM)
               ( 284 F)
               ( 660 FT)

               ( 11.9 FT)
               ( 10804 BTU/LB)
                10804-11520
COAL
******
25130.

   23.00
******
    9.05
******
    2.00
******
      .05
******
 0
NONE
COLD SIDE
SUMITOMO HEAVY INDUSTRIES
  333.2        ( 706000 ACFM)
  140.0        (  284 F)
   98.0
VENTURI TOMER
NR
NR
HITACHI
NR
NR
ORGANIC
NR
NONE
  1
  533.7         ( 8471 GPM)
    2.5         (18.7 GAL/1000ACF)
    2.3         ( 9.1 IN-H20)
  168.0         ( 356000 ACFM)
                                              E-33

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

ELECTRIC POWER DEVELOPMENT: TAKEHARA 1 (CONT.)

     INLET GAS TEMPERATURE - C                    140.0

*** FGD SYSTEM
                (   284 F)
 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     PROCESS ADDITIVES
     SYSTEM SUPPLIER
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     ENERGY CONSUMPTION - X
     CURRENT STATUS
     COMMERCIAL START-UP
     INITIAL START-UP

 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - L/CU.M
     GAS-SIDE PRESSURE DROP - KPA
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     NUMBER PER SYSTEM
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONFIGURATION
     PRESSURE DROP - KPA
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     WASH WATER SOURCE
     WASH FREQUENCY
     WASH RATE - L/S

 ** REHEATER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     INLET FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 »* FANS
     NUMBER
     DESIGN
     FUNCTION
     APPLICATION
 SALEABLE PRODUCT
 WET SCRUBBING
 LIMESTONE
 NONE
 BABCOCK-HITACHI
 FULL SCALE
 RETROFIT
X   91.70
    94.20
     3.2
  1
  2/79
  2/77
 NR
 NR
 TRAY TOWER
 NR
 NR
 BABCOCK-HITACHI
 CARBON STEEL
 NR
 N/A
 ORGANIC
 POLYESTER
 NR
  5
   721.         (11448 GPM)
     7.0        (  52.4 GAL/1000 ACF)
     3.8        (15.2 IN-H20)
   164.76       (  349142 ACFM)
    52.2        (   126 F)
 PRIMARY COLLECTOR
  2
 IMPINGEMENT
 TUBE BANK
 VERTICAL PARALLEL TUBES
 HORIZONTAL
      .1
 NR
 NR
 FRESH
 CONTINUOUS
(   .4 IN-H20)
     1.3
                    20 GAL/MIN)
 DIRECT COMBUSTION
 NR
 OIL
   120.0        (  248 F)
 NR
 NR
  2
 NR
 BOOSTER
 INDUCED DRAFT
                                              E-34

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 198*
ELECTRIC  POWER DEVELOPMENT: TAKEHARA 1 (CONT.)

     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 »* REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

 «« TANKS
     SERVICE
     PR E SATURATOR/QUENCHER
     ABSOR3ER RECYCLE
     VACUUM FILTER FILTRATE
     SPARGER/OXIDIZER

 »* PUMPS
     SERVICE
     COOLER RECYCLE
     ABSORBER RECIRCULATION

 «* SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUM5ER
     NUMBER OF SPARES
     CAPACITY
     FEED STREAM CHARACTERISTICS
     OUTLET STREAM CHARACTERISTICS

 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUM3ER
     CONFIGURATION
     DIMENSIONS - FT
     FEED STREAM CHARACTERISTICS
     OUTLET STREAM CHARACTERISTICS

 *** SALEABLE BYPRODUCTS
     NATURE
     FULL LOAD QUANTITY - M T/H
     QUALITY - •/.
     DISPOSITION

 »** SLUDGE

 ** TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 ** DISPOSAL
     NATURE
     TYPE
     SITE TREATMENT
MET
NR
NR
NR
NR
NR
NR
NR
NR
MET BALL MILL
NR
NR
                                                NUMBER
   2
****
****
   2
NUMBER

   Z
   4
CENTRIFUGE
 9
1
4 GPM
20X SOLIDS
88X SOLIDS
THICKENER
  1
HORIZONTAL
45.0 OIA X  10.0
12X SOLIDS
20X SOLIDS
GYPSUM
     9.89
    95.0
MARKETED
(  10.90 TPH)
 FORCED  OXIDATION
 OXIDATION  TANK
 N/A
 NR
 NR
 NR
                                              E-35

-------
UTILITY F60 SURVEY: OCTOBER 1983 - SEPTEMBER 1984

ELECTRIC POWER DEVELOPMENT: TAKEHARA 1 (CONT.>
 ** PROCESS CONTROL AND INSTRUMENTATION
     CHEMICAL PARAMETERS                        PH, GAS FLOW
     CONTROL LEVELS                             PH 5.0-6.0
     PROCESS CONTROL MANNER                     AUTOMATIC

 ** WATER BALANCE
     WATER LOOP TYPE                            OPEN
     POND SEEPAGE/RUNOFF WATER LOSS - LITERS/S  60
     MAKEUP WATER ADDITION - LITERS/S              14.9        (  237 GPM)
 	PERFORMANCE DATA	
 PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILEF!  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


 4/78  SYSTEM                                                                720

 5/78  SYSTEM                                                                744

 6/78  SYSTEM                                                                720

 7/78  SYSTEM                                                                744

 8/78  SYSTEM                                                                744

 9/78  SYSTEM                                                                720

 10/78  SYSTEM                                                                744

 11/78  SYSTEM                                                                720

 12/78  SYSTEM                                                                744

 1/79  SYSTEM                                                                744

 2/79  SYSTEM                                                                672

 3/79  SYSTEM                                                                744

       **  PROBLEMS/SOLUTIONS/COMMENTS

                          99.95X AVAILABILITY WAS REPORTED FOR THE PERIOD FROM APRIL 1978 THROUGH
                          MARCH 1979.

 4/79  SYSTEM                                                                720

 5/79  SYSTEM                                                                744

 6/79  SYSTEM                                                                720

 7/79  SYSTEM                                                                744

 8/79  SYSTEM                                                                744

 9/79  SYSTEM                                                                720

 10/79  SYSTEM                                                                744

 11/79  SYSTEM                                                                720

 12/79  SYSTEM                                                                744

 1/80  SYSTEM                                                                744

 2/80  SYSTEM                                                                696

 3/80  SYSTEM                                                                744
                                              E-36

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

ELECTRIC POWER DEVELOPMENT: TAKEHARA 1 (CONT.)
	PERFORMANCE DATA	
PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  7. REMOVAL   PER  BOILER  FGD   CAP.
                                                                S02  PART. HOURS HOURS  HOURS FACTOR


       *» PROBLEMS/SOLUTIONS/COMMENTS

                         NO INFORMATION WAS AVAILABLE FOR THE APRIL 1979 THROUGH MARCH 1980 PERIOD.

 4/80  SYSTEM     100.0       100.0       100.0       100.0                  720   720    720

 5/80  SYSTEM     100.0       100.0       100.0       100.0                  744   744    744

 6/80  SYSTEM      87.9       100.0       100.0        87.9                  720   633    633  82.4

       «* PROBLEMS/SOLUTIONS/COMMENTS

                         THE FGD SYSTEM WAS OUT OF SERVICE FOR APPROXIMATELY 3 DAYS IN JUNE TO
                         REMOVE THE SCALE ACCUMULATION IN THE FGD OUTLET DUCT.

                                                                             744   744    744  95.5

                                                                             744   744    744  95.3

                                                                             720   720    720  95.3

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         NO PROBLEMS WERE ENCOUNTERED DURING THE THIRD QUARTER 1980.

 10/80  SYSTEM     100.0       100.0       100.0       100.0                  744   744    744  94.5

 11/80  SYSTEM     100.0       100.0       100.0       100.0                  720   720    720  95.2

 12/80  SYSTEM     100.0       100.0       100.0        27.7                  744   206    206  22.4

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE BOILER WAS OUT OF SERVICE FROM DECEMBER 1 THROUGH DECEMBER 25 FOR
                         SCHEDULED MAINTENANCE.

 1/81  SYSTEM                                                                744

 2/81  SYSTEM                                                                672

 3/81  SYSTEM                                                                744

       ** PROBLEMS/SOLUTIONS/COMMENTS

                         THE FIRST QUARTER 1981 DATA  IS  NOT AVAILABLE AT THIS TIME;  HOWEVER THE
                         DATA WILL BE  AVAILABLE IN THE SECOND QUARTER 1981 REPORT.
7/80 SYSTEM
8/80 SYSTEM
9/80 SYSTEM
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
                                              E-37

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

                                           APPENDIX E
                DESIGN AND PERFORMANCE DATA FOR OPERATIONAL FOREIGN FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
COUNTRY
REGULATORY CLASSIFICATION
PARTICIPATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MM
GROSS UNIT GENERATING CAPACITY - MM
NET UNIT GENERATING CAPACITY W/FGD - MM
NET UNIT GENERATING CAPACITY WO/FGD - MM
EQUIVALENT SCRUBBED CAPACITY - MM

  »* UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOM - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

  ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANSE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

  ** ESP
     NUMBER
     TYPE
     SUPPLIER
     INLET FLUE GAS CAPACITY - CU.M/S
     INLET FLUE GAS TEMPERATURE - C
     PRESSURE DROP - KPA
     PARTICLE REMOVAL EFFICENCY - 7.

  ** PARTICLE SCRUBBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     INLET GAS FLOW RATE - CU.M/S
     INLET GAS TEMPERATURE - C

*»» FGD SYSTEM

  «* GENERAL DATA
     SALEABLE PRODUCT/THROMAWAY PRODUCT
     S02 REMOVAL MODE
HOKKAIDO ELECTRIC POWER
TOMATOATSUMA THERMAL POM
1
TOMAKOMAI
JAPAN
******
******
******
  350
  350
  175
  175
  350
BABCOCK-HITACHI
PULVERIZED COAL
BASE
  508.21
  121.1
  170.
CARBON STEEL
    4.5
(****** LB/MMBTU)
(****** LB/MMBTU)
(****** LB/MMBTU)
(1076939 ACFM)
(  250 F)
(  558 FT)

(  14.6 FT)
COAL
BITUMINOUS
25121.

   20.50
******
    7.00
******
     .30
******
********
******
HOT SIDE
HITACHI
  828.8
  363.9
     .2
   99.8
( 10800 BTU/LB)
 ******
(1756252 ACFM)
(   687 F)
(   1. IN-H20)
VENTURI TOMER
NR
NR
BABCOCK-HITACHI
NR
NR
NR
NR
NONE
  198.7
   47.2
(  421036 ACFM)
(   117 F)
SALEABLE PRODUCT
MET SCRUBBING
                                              E-38

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER 1984

HOKKAIDO ELECTRIC POWER: TOMATOATSUMA THERMAL POM 1 (CONT.)
     PROCESS TYPE
     SYSTEM SUPPLIER
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN 302 REMOVAL EFFICIENCY - X
     ENERGY CONSUMPTION - X
     CURRENT STATUS
     COMMERCIAL START-UP
     INITIAL START-UP

 ** DESIGN AND OPERATING PARAMETERS

 «* QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C
     PARTICLE REMOVAL EFFICENCY - X

 »» MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     NUMBER  PER SYSTEM
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONFIGURATION
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 *» REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     PERCENT GAS BYPASSED - AVG
     TEMPERATURE INCREASE - C
     INLET FLUE GAS FLOW RATE - CU. M/S
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     NUMBER
     DESIGN
     SUPPLIER
     FUNCTION
     APPLICATION
     SERVICE
     FLUE GAS FLOW RATE - CU.M/S
     FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
LIMESTONE
BABCOCK-HITACHI
FULL SCALE
RETROFIT
   90.00
     .0
 1
10/80
 7/80
NR
NR
 1
NR
NR
NR
BABCOCK-HITACHI
NR
NR
NR
NR
NR
NR
  198.69
   47. Z
   90.0
(  421036 ACFM)
(   117 F)
PRIMARY COLLECTOR
 1
IMPINGEMENT
BAFFLE
NR
VERTICAL
NR
NR
WASTE HEAT RECOVERY
GAS-GAS
WHEEL TYPE
    14.3
    65.6
   199.17
NR
NR
(  118 F)
( 422057 ACFM)
CENTRIFUGAL
HITACHI,LOT.
BOOSTER
NR
NR
  254.47
  137.2
NR
 NR
 NR
 NR
 NR
 NR
 NR
( 539247 ACFM)
(  279 F)
                                              E-39

-------
 UTILITY  FGD  SURVEY:  OCTOBER  1983 - SEPTEMBER

 HOKKAIDO ELECTRIC POWER:  TOflATOATSUMA THERMAL POW 1 (CONT. )
      LINER SPECIFIC MATERIAL TYPE

  ** REAGENT PREPARATION EQUIPMENT
      FUNCTION
      DEVICE
      DEVICE TYPE
      NUMBER
      PRODUCT QUALITY - X SOLIDS

  ** PUMPS
      SERVICE
      NR
  ** SOLIDS CONCENTRATING/DEWATERING
      DEVICE
      NUMBER

  ** SOLIDS CONCENTRATING/DEWATERING
      DEVICE
      NUMBER
      NUMBER OF SPARES

 *** SALEABLE BYPRODUCTS
      NATURE
      QUALITY - X
      DISPOSITION

 *»* SLUDGE

  ** TREATMENT
      METHOD
      DEVICE
      PROPRIETARY PROCESS

  «* DISPOSAL
      NATURE
      TYPE
      SITE TREATMENT

  ** WATER BALANCE
      WATER LOOP TYPE
      MAKEUP WATER ADDITION - LITERS/S
                                                 NR
WET BALL MILL
NR
NR
 1
   92.0
NUMBER
THICKENER
 Z
CENTRIFUGE
 3
1
GYPSUM
   45.0
MARKETED
NR
NR
NR
NR
NR
NR
CLOSED
    4.0
                                                                    63 GPM)
 	PERFORMANCE DATA	
 PERIOD MODULE AVAILABILITY OPERABILITY RELIABILITY UTILIZATION  X REMOVAL   PER  BOILER  FGD   CAP.
                                                                 SOS  PART. HOURS HOURS  HOURS FACTOR


 10/80  SYSTEM     100.0       100.0       100.0        70.3    94.40         744   523    523  46.0

        ** PROBLEMS/SOLUTIONS/COMMENTS

                          OPERATIONS AT THE TOMATOATSUMA STATION COMMENCED IN OCTOBER 1980.

 11/80  SYSTEM     100.0       100.0       100.0        85.1                  720   613    613  61.1

 12/80  SYSTEM     100.0       100.0       100.0       100.0                  744   744    744  94.7

        ** PROBLEMS/SOLUTIONS/COMMENTS

                          DURING DECEMBER SCALE FORMATION WAS OBSERVED IN THE PIPING AND IN A PUMP OF
                          THE WASTE WATER TREATMENT FACILITY.  A WATER WASH LINE WAS INSTALLED FOR
                          THE PIPING AND A PUMP WAS ADDED TO ELIMINATE SCALE.  THE FGO SYSTEM
                          OPERATION WAS NOT AFFECTED DURING THIS TIME.
                                              E-40
3BRKPT PRINTS

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1963 - SEPTEMBER
                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC F6D SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MM
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY M/FGD - MM
NET UNIT GENERATING CAPACITY MO/FGD - MM
EQUIVALENT SCRUBBED CAPACITY - MM

 «* UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - Y.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RAN3E SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

«** PARTICLE CONTROL

 »* MECHANICAL COLLECTOR
     NUM3ER
     TYPE

 ** ESP

 «* PARTICLE SCRUBBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE

»** FGD SYSTEM

 *» GENERAL DATA
     SALEABLE PRODUCT/THROMAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     CURRENT STATUS
ARIZONA PUBLIC SERVICE
FOUR CORNERS
5A
FARMINGTON
NEM MEXICO
C
   21.
  258.
******
 2089
  755
*****
*****
  755
******
PULVERIZED COAL
BASE
               (   .050 LB/MMBTU)
               (   .600 LB/MMBTU)
               (****** LB/MMBTU)
               (******* ACFM)
               (**** F)
               (**** FT)

               (****» FT)
               (  9700 BTU/LB)
                ******
********
*******
******
NR
*******
COAL
SUBBITUMINOUS
22562.

   24.00
******
   11.00
******
      .81
******
********
******
 0
NONE
  0
NONE
N/A
N/A
N/A
N/A
N/A
N/A
N/A
THROMAWAY  PRODUCT
MET  SCRUBBING
LIME
SOUTHERN CALIFORNIA  EDISON
BECHTEL
EXPERIMENTAL
RETROFIT
  8
                                              F-l

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

ARIZONA PUBLIC SERVICE: FOUR CORNERS 5A (CONT.)
     TERMINATION
     INITIAL START-UP
     CONTRACT AWARDED

 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTIN3 DEVICE TYPE
     NUMBER OF CONTACTING ZONES

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     NUMBER PER SYSTEM
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 »* REHEATER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     NUMBER
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 «« REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE
     NUMBER
12/76
 2/76
 1/74
NR
NR
SPRAY TOWER
OPEN CROSSCURRENT SPRAY
HORIZONTAL SPRAY CHAMBER
60.0 X 28.0 X 17.0
CARBON STEEL
AISI 1110
N/A
ORGANIC
NATURAL RUBBER; GLASS FLAKE-FILLED POLYESTER
BLACK NATURAL RUBBER; NR
NONE
 5
PRIMARY COLLECTOR
 1
IMPINGEMENT
BAFFLE
CLOSED VANE
STAINLESS STEEL; CARBON STEEL
NR
INDIRECT HOT AIR
EXTERNAL HEAT EXCHANGER
STEAM TUBE BUNDLE
NR
NR
CENTRIFUGAL
BOOSTER
FORCED DRAFT
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
SLAKER
DETENTION
N/A
 1
                                             F-2

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER

ARIZONA PUBLIC SERVICE: FOUR CORNERS 5A (CONT.)


 ** PUMPS
     SERVICE                                    NUMBER
     SLURRY RECIRCULATION                         12

 ** SOLIDS CONCENTRATIN6/DEMATERING
     DEVICE                                     THICKENER
     NUMBER                                      1
     DIMENSIONS - FT                            60.0 DIA
     SHELL GENERIC MATERIAL TYPE                CARBON STEEL
     OUTLET STREAM CHARACTERISTICS              30X SOLIDS

 *** SLUDGE

 »« TREATMENT
     METHOD                                     NR
     DEVICE                                     NR
     PROPRIETARY PROCESS                        NR

 ** DISPOSAL
     NATURE                                     NR
     TYPE                                       NR
     SITE TREATMENT                             NR
                                              F-3

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MM
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** FABRIC FILTER
     NUMBER
     TYPE

 ** ESP

 ** PARTICLE SCRUBBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE

*** FGD SYSTEM

 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
BOSTON EDISON
MYSTIC
6
EVERETT
MASSACHUSETTS
******
******
******
******
*****
  150
*****
*****
  150
COMBUSTION ENGINEERING
OIL FIRED
******
  273.70
  148.9
   99.
NR
*******
(****** LB/MMBTU)
(****** LB/MMBTU)
I****** LB/MMBTU)
(  580000 ACFM)
(  300 F)
(  325 FT)

(«**** FT)
OIL
NO. 6
               (****** BTU/LB)
                ******
     .07
******
    1.00
******
    2.00
******
********
******
 0
NONE
 0
NONE
 0
NONE
N/A
N/A
N/A
N/A
N/A
N/A
N/A
SALEABLE PRODUCT
WET SCRUBBING
MAGNESIUM OXIDE
GE ENVIRONMENTAL SERVICES

-------
                                                  UTILITY F6D SURVEY:  OCTOBER 1983 - SEPTEMBER
BOSTON EDISON: MYSTIC 6 (CONT.)

     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP
     CONTRACT AWARDED

 «* DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 »» ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE -  LITER/S
     L/G RATIO - L/CU.M
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     NUMBER PER SYSTEM
     GENERIC  TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     NUMBER OF PASSES PER STAGE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     WASH WATER SOURCE

 »* REHEATER
      GENERIC  TYPE
      SPECIFIC TYPE
      TRADE  NAME/COMMON TYPE
      CONSTRUCTION MATERIAL GENERIC  TYPE
      CONSTRUCTION MATERIAL SPECIFIC TYPE

  ** FANS
      NUMBER
      DESIGN
      FUNCTION
      APPLICATION
      SERVICE
      CONSTRUCTION MATERIAL GENERIC  TYPE

  ** DAMPERS
      FUNCTION
      GENERIC  TYPE
      SPECIFIC TYPE
      CONSTRUCTION MATERIAL GENERIC  TYPE
      CONSTRUCTION MATERIAL SPECIFIC TYPE
      LINER  GENERIC  MATERIAL  TYPE
      LINER  SPECIFIC MATERIAL TYPE
 DEMONSTRATION
 RETROFIT
X   55.00
    90.00
  8
  7/7*
  4/72
  4/72
  0/70
 NR
 NR
 VENTURI TOWER
 VARIABLE-THROAT/TOP-ENTRY PLUMB BOB
 N/A
 CARBON STEEL
 NR
 N/A
 ORGANIC
 EPOXY
 FLAKELINE E
 N/A
  1
   9*5.         (15000 GPM)
     *.*        ( 33.0 GAL/1000 ACF)
   200.56       ( 425000 ACFH)
   1*8.9        (  300 F)
 PRIMARY COLLECTOR
  1
 IMPINGEMENT
 BAFFLE
 CLOSED VANE
     6
 NR
 NR
 FRESH
   0
 NONE
 N/A
 N/A
 NONE
 N/A
   2
  NR
  NR
  INDUCED DRAFT
  NR
  NR
  NR
  NR
  NR
  NR
  NR
  NR
  NR
                                              F-5

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

BOSTON EDISON: MYSTIC 6 (CONT.)


 ** DUCTWORK
      SHELL GENERIC MATERIAL TYPE               NR
      SHELL SPECIFIC MATERIAL TYPE              NR
      LINER GENERIC MATERIAL TYPE               NR
      LINER SPECIFIC MATERIAL TYPE              NR

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION                                   SLAKER
     DEVICE                                     NR
     DEVICE TYPE                                NR

 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE                                     CENTRIFUGE
     NUMBER                                      1
     SHELL GENERIC MATERIAL TYPE                CARBON STEEL
     FEED STREAM CHARACTERISTICS                10X SOLIDS

*** SLUDGE

 «* TREATMENT
     METHOD                                     NR
     DEVICE                                     NR
     PROPRIETARY PROCESS                        NR

 ** DISPOSAL
     NATURE                                     N/A
     TYPE                                       NONE
     SITE TREATMENT                             NR

 ** PROCESS CONTROL AND INSTRUMENTATION
     CHEMICAL PARAMETERS                        PH, FLUE GAS INLET TEMP., SCRUBBER OUTLET TEMP.
     COtlTROL LEVELS                             PH 6.8
     MONITOR LOCATION                           PH - BLEED LINE FROM ABSORBER TO CENTRIFUGE
     PROCESS CONTROL MANNER                     MANUAL
     PROCESS CHEMISTRY MODE                     FEEDBACK

 ** WATER BALANCE
     WATER LOOP TYPE                            CLOSED
                                             F-6

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC F6D SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - N6/J
502 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY M/FGD - MM
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 »* FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RAN3E HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - '/.
     RANGE MOISTUPE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 «* FABRIC FILTER
     NUMBER
     TYPE

 ** ESP
     NUMBER
     TYPE
     SUPPLIER
     INLET FLUE GAS CAPACITY - CU.M/S
     INLET FLUE GAS TEMPERATURE - C
     PARTICLE REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE-TYPE
COMMONWEALTH EDISON
POWERTON
51
PEKIN
ILLINOIS
E
   43.         (
  774.         (
******
 1700
  450
  400
  425
  450
BABCOCK i MILCOX
CYCLONE
BASE
  722.18
  157.2
  137.
CONCRETE
    6.4
                   100  LB/MMBTU)
                   800  LB/MMBTU)
               I******  LB/MKBTU)
               (1530370 ACFM)
               (  315 F)
               (  450 FT)

               (  21.0 FT)
COAL
******
24516.
               ( 10540 BTU/LB)
                ******
    9.16
   16.34
******
    3.53
******
      .20
******
  0
NONE
  0
NONE
COLD SIDE
RESEARCH-COTTRELL
   722.2         (1530370 ACFM)
   157.2         (   315 F)
    98.7
  0
NONE
N/A
N/A
N/A
N/A
N/A
N/A
N/A
                                              F-7

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

COMMONWEALTH EDISON: POWERTON 51 (CONT.)
*** FGD SYSTEM

 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     ENERGY CONSUMPTION - X
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP
     CONTRACT AWARDED

 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 *« ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - L/CU.M
     GAS-SIDE PRESSURE DROP - KPA
     SUPERFICAL GAS VELOCITY - M/SEC
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C
     502 REMOVAL EFFICIENCY - X

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     NUMSER PER SYSTEM
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONFIGURATION
     SUPERFICAL GAS VELOCITY - M/S
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** REKEATER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     TEMPERATURE INCREASE - C
     INLET FLUE GAS FLOW RATE - CU. M/S
     INLET FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
THROWAWAY PRODUCT
WET SCRUBBING
LIMESTONE
AIR CORRECTION DIVISION, UOP
SARGENT & LUNDY
FULL SCALE
RETROFIT
   75.50
    5.6
 8
 5/82
 6/81
 4/80
 5/76
NR
NR
PACKED TOWER
MOBILE BED PACKING
TURBULENT CONTACT ABSORBER
AIR CORRECTION DIVISION, UOP
55.0 X 30.0 X 18.0
CARBON STEEL
AISI 1110
N/A
ORGANIC
SYNTHETIC RUBBER
NEOPRENE LS-576
PLASTIC/RUBBER MOBILE BALLS
 3
 1575.
    6.6
    3.0
    3.8
  240.73
  157.2
   75.5
(25000 GPM)
(  49.0 GAL/1000 ACF)
(12.0 IN-H20)
(  12.5 FT/S)
(  510123 ACFM)
(   315 F)
PRIMARY COLLECTOR
 2
IMPINGEMENT
BAFFLE
CLOSED VANE
HORIZONTAL
    2.7        (9.0 FT/S)
ORGANIC
FIBER-REINFORCED POLYESTER
INDIRECT HOT AIR
EXTERNAL HEAT EXCHANGER
STEAM TUBE BUNDLE
   13.9        (   25 F)
  583.28       (1236021 ACFM)
   54.4        (  130 F)
NR
NR
                                             F-8

-------
COMMONWEALTH EDISON: POWERTON 51 (CONT.)
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
 »* FANS
     DESIGN
     SUPPLIER
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 »* DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTWCPK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LIHER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE
     MANUFACTURER
     NUMBER
     FULL LOAD DRY FEED CAPACITY - M.TONS/HR

 *« TANKS
     SERVICE
     ABSORBER RECYCLE
     REAGENT PREP PRODUCT
     MIST ELIMINATOR WASH
     WASTE SLURRY BLEED
     THICKENER OVERFLOW

  **  PUMPS
     SERVICE
     RECLAIMED WATER TRANSFER
     WASTE SLURRY TRANSFER
     FILTRATE TRANSFER
     COMDEK'SATE RETURN
     SERVICE WATER BOOSTER
     FILTERED WATER BOOSTER
     SURGE PONO RECOVERY
     SLURRY RECIRCULATION
     REACTANT FEED
     DEMISTER WASH
     WASTE SLURRY
     SLURRY TRANSFER

  »« SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUMBER
     NUKSER OF SPARES
     SHELL GENERIC MATERIAL TYPE
     OUTLET STREAM CHARACTERISTICS

  *» SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUMBER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL TYPE
     OUTLET STREAM CHARACTERISTICS
CENTRIFUGAL
GREEN FAN
BOOSTER
FORCED DRAFT
DRY
CARBON STEEL
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
MET BALL MILL
COMPARTMENTED
NR
KOPPERS
 2
   ZO.O        (
NUMBER
22 TPH)
NUMBER

   2
   2
   3
   2
   2
   2
   3
   9
   2
   2
   2
VACUUM FILTER
 3
1
CARBON STEEL
55X SOLIDS
THICKENER
 1
170.0 DIA X 10.0
CARBON STEEL
35X SOLIDS
                                              F-9

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON: POWERTON 51 (CONT.)
*** SLUDGE

 ** TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS
     INLET QUALITY - X

 ** DISPOSAL
     NATURE
     TYPE
     SITE TREATMENT

 ** DISPOSAL
     NATURE
     TYPE
     LOCATION
     SITE TREATMENT
     SITE CAPACITY - CU.M

 ** PROCESS CONTROL AND INSTRUMENTATION
     CHEMICAL PARAMETERS
     PROCESS CONTROL MANNER
     PROCESS CHEMISTRY MODE

 ** WATER BALANCE
     WATER LOOP TYPE
     MAKEUP WATER ADDITION - LITERS/S
FIXATION
PUG MILL
CONVERSION SYSTEMS [POZ-0-TECI
   35.0
FINAL
POND
NONE
INTERIM
PONO
ON-SITE
CLAY LINING
    122300
100.0 ACRE-FT)
S02, GAS FLOW, PH
AUTOMATIC
FEEDBACK/FEED FORWARD
CLOSED
   35.3
                                                               (  560 GPM)
                                             F-10

-------
                                                 UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER
                                          APPENDIX F
              DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC F6D SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW
COMMONWEALTH
WILL COUNTY
1A
ROMEOVILLE
ILLINOIS
E
86.
77*.
******
11*7
167
137
1**
167
EDISON





( .200 LB/MMBTU)
( 1.800 LB/MMBTU)
I****** LB/MMBTU)





 ** UNIT DATA - BOILER AND STACK
    BOILER SUPPLIER
    BOILER TYPE
    BOILER SERVICE LOAD
    DESIGN BOILER FLUE GAS  FLOW - CU.M/S
    BOILER FLUE GAS TEMPERATURE - C
    STACK HEIGHT - M
    STACK SHELL
    STACK TOP DIAMETER - M

 ** FUEL DATA
    FUEL TYPE
    FUEL GRADE
    AVERAGE HEAT CONTENT -  J/G
    RANGE HEAT CONTENT - BTU/LB
    AVERAGE ASH CONTENT - 7.
    RAUSE ASH CONTENT - 7.
    AVERAGE MOISTURE CONTENT - '/.
    RAUSE MOISTURE CONTENT  - 7.
    AVERAGE SULFUR CONTENT  - 7.
    RAH3E SULFUR CONTENT -  7.
    AVERAGE CHLORIDE CONTENT - 7.
    RANGE CHLORIDE CONTENT  - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
    NUMBER
    TYPE

 »* FABRIC FILTER
    NUMBER
    TYPE

 «* ESP
    NUMBER
    TYPE
    SUPPLIER
    INLET FLUE GAS TEMPERATURE  -  C
    PARTICLE REMOVAL EFFICENCY  -  7.

 ** PARTICLE SCRUBBER
    NUM2ER
    INITIAL START-UP DATE
    GENERIC TYPE
    SPECIFIC TYPE
    TRADE NAME/COMMON NAME
    SUPPLIER
    DIMENSIONS - FT
    SHELL GENERIC MATERIAL
    SHELL SPECIFIC MATERIAL
    LINER GENERIC MATERIAL
    LINER SPECIFIC MATERIAL
    GAS CONTACTING DEVICE TYPE
BABCOCK *
CYCLONE
CYCLING
363.36
179.*
107.
NR
3.8
WILCOX


( 770000 ACFM)
( 355 F)
( 350 FT)

( 12.* FT)
COAL
******
22260.         (   9570 BTU/LB)
                9100-10500
    7.*0
3.0-16.0
********
******
    1.50
0.3-*.5
********
******
 0
NONE
 0
NONE
COLD SIDE
WESTERN PREC. DIVISION, JOY
  179.*        (  355 F)
   90.0
 2
 */72
VENTURI TOWER
VARIABLE-THROAT/SIDE-MOVABLE BLADES
N/A
BABCOCK I WILCOX
8.0 X 26.0 X 16.0
CARBON STEEL
AISI 1110
ORGANIC; INORGANIC
INERT FLAKE-FILLED VINYL ESTER; HYDRAULICALLY-BO
NONE
                                             F-ll

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON: WILL COUNTY 1A (CONT.)

     LIQUID RECIRCULATIOH RATE - LITER/S
     L/G RATIO - LITER/CU.M
     PRESSURE DROP - KPA
     SUPERFICIAL GAS VELOCITY - M/S
     INLET. GAS FLOW RATE - CU.M/S
     INLET GAS TEMPERATURE - C
     PARTICLE REMOVAL EFFICIENCY - X

*»* FGD SYSTEM
   365.4
     2.4
     2.2
    36.6
   181.7
   179.4
    98.0
(  5800 GPM)
(18.0 GAL/1000ACF)
(  9.0 IN-H20)
(   120.0 FT/S)
(  385000 ACFM)
(   355 F)
 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     ENERGY CONSUMPTION - X
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP
     CONTRACT AWARDED
 THROWAWAY PRODUCT
 WET SCRUBBING
 LIMESTONE
 BABCOCK t WILCOX
 BECHTEL
 FULL SCALE
 RETROFIT
X   98.00
    76.00
     4.2
  8
  7/77
  2/73
  2/72
  2/71
  *#  DESIGN AND OPERATING PARAMETERS

  *«  QUENCHER/PRESATURATOR
      CONSTRUCTION MATERIAL GENERIC TYPE
      CONSTRUCTION MATERIAL SPECIFIC TYPE

  **  ABSORBER
      NUMBER
      GENERIC  TYPE
      SPECIFIC TYPE
      TRADE NAME/COMMON TYPE
      SUPPLIER
      DIMENSIONS  - FT
      SHELL GENERIC  MATERIAL
      SHELL SPECIFIC MATERIAL
      SHELL MATERIAL TRADE NAME/COMMON TYPE
      LINER GENERIC  MATERIAL
      LINER SPECIFIC MATERIAL
      LINER MATERIAL TRADE NAME/COMMON TYPE
      GAS CONTACTING DEVICE TYPE
      NUMBER OF CONTACTING ZONES
      LIQUID RECIRCULATION RATE - LITER/S
      L/G RATIO - L/CU.M
      GAS-SIDE PRESSURE DROP - KPA
      SUFERFICAL  GAS VELOCITY - M/SEC
      INLET GAS FLOW - CU. M/S
      INLET GAS TEMPERATURE - C
      PARTICLE REMOVAL EFFICENCY - X

  **  MIST ELIMINATOR
      PRE-MIST ELIMINATOR/MIST ELIMINATOR
      NUMBER PER  SYSTEM
      GENERIC  TYPE
      SPECIFIC TYPE
      TRADE NAME/COMMON TYPE
      CONFIGURATION
      NUMBER OF STAGES
      NUMBER OF PASSES PER STAGE
      FREEBOARD DISTANCE - M
      DISTANCE BETWEEN VANES - CM
      VANE ANGLES -  DEGREES
      PRESSURE DROP  - KPA
      CONSTRUCTION MATERIAL GENERIC TYPE
      CONSTRUCTION MATERIAL SPECIFIC TYPE
 NR
 NR
 TRAY TOWER
 SIEVE TRAY
 N/A
 BABCOCK 4 WILCOX
 16.0 X 24.0 X 60.0
 CARBON STEEL
 HIGH STRENGTH LOW ALLOY IHSU1
 COR-TEN
 ORGANIC
 NATURAL RUBBER
 BLACK NATURAL RUBBER
 PERFORATED TRAYS
  2
   693.         (11000 GPM)
     4.7        (35.0 GAL/1000 ACF )
     2.5        (10.0 IN-H20)
     3.0        (  10.0 FT/S)
   181.68       (  385000 ACFM)
   179.4        (   355 F)
    76.0
 PRIMARY COLLECTOR
  2
 IMPINGEMENT
 BAFFLE
 CLOSED VANE
 HORIZONTAL
     2
       05
     3.8
(10.0 FT)
( 1.50 IN)
   45
      .2        (1.0 IN-H20)
 ORGANIC
 FIBER-REINFORCED POLYESTER
                                             F-12

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER
COMMONWEALTH EDISON: WILL COUNTY 1A CCONT.)

     WASH WATER SOURCE
     WASH FREQUENCY
     WASH RATE - L/S

 ** REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     TEMPERATURE INCREASE - C
     INLET FLUE GAS FLOW RATE - CU. M/S
     INLET FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 *« FANS
     NUMBER
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE

 »» DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC  MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 «* DUCTWORK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION  EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE
     NUMBER
     FULL LOAD  DRY  FEED  CAPACITY - M.TONS/HR
     PRODUCT QUALITY - X SOLIDS

 «* TANKS
     SERVICE
      SCRUBBER  RECYCLE

  ** PUMPS
      SERVICE
      VENTURI  RECIRCULATION
      ABSORBER RECIRCULATION

  ** SOLIDS  CONCENTRATING/DEWATERING
      DEVICE
      NUMBER
      CONFIGURATION
      DIMENSIONS  -  FT

  »* SOLIDS  CONCENTRATING/DEWATERING
      DEVICE
      NUM3ER
      CAPACITY
BLENDED
UNDERSPRAY-CONTINUOUS; OVERSPRAY-INTERMITTENT
   71.0        (  1125 GAL/MIN)
 2
IN-LINE
STEAM
NR
   28.9        (    52 F)
  179.32       (  380000 ACFM)
   53.3        (   128 F)
STAINLESS STEEL
AUSTENITIC
CENTRIFUGAL
BOOSTER
INDUCED DRAFT
DRY
   82.2        (  180 F)
CARBON STEEL
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
 WET  BALL MILL
 COMPARTMENTED
 NR
  2
   10.9         (   12 TPH)
   27.5
 NUMBER

    2


 NUMBER
 THICKENER
  1
 CIRCULAR,  SLOPED  BOTTOM
 65.0 OIA X 15.0
 VACUUM FILTER
  1
 90TON/DAY
                                              F-13

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

COMMONWEALTH EDISON: WILL COUNTY 1A (CONT. )
*»» SLUDGE

 «* TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 ** DISPOSAL
     NATURE
     TYPE
     LOCATION
     SITE TREATMENT

 ** DISPOSAL
     NATURE
     TYPE
     LOCATION
     SITE TRANSPORTATION METHOD

 *# PROCESS CONTROL AND INSTRUMENTATION
     CHEMICAL PARAMETERS
     PROCESS CONTROL MANNER

 ** WATER BALANCE
     WATER LOOP TYPE
FIXATION
PUG MILL
CHICAGO ADMIXTURES
INTERIM
POND
ON-SITE
CLAY LINING
FINAL
LANDFILL
OFF-SITE
TRUCK
PRESSURE, LIMESTONE FEED, PH
AUTOMATIC
                                                CLOSED

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 »* UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAC-E HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
   •  RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

 ***  PARTICLE CONTROL

 »*  ESP
     NUMBER

 **  PARTICLE SCRUBBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
      LINER GENERIC MATERIAL
      LINER SPECIFIC MATERIAL
     GAS  CONTACTING DEVICE TYPE

 »**  FGD SYSTEM

 *»  GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02  REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN S02 REMOVAL  EFFICIENCY - 7.
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP
DAIRYLAND POWER
ALMA
5
ALMA
WISCONSIN
******
******
******
******
  210
   80
*****
*****
   80
******
******
******
********
*******
******
NR
*******
(*****« LB/MMBTU)
(****** LB/MMBTU)
(****** LB/MMBTU)
COAL
******
******

********
12.0-20.0
********
3.0-3.S
********
******
********
******
(******* ACFM)
<**** F)
(**** FT)

(***** FT)
(****** BTU/LB)
 10500-11000
  0
NONE
N/A
N/A
N/A
N/A
N/A
N/A
N/A
 THROWAWAY PRODUCT
 WET SCRUBBING
 LIME
 FOSTER  WHEELER
 EXPERIMENTAL
 RETROFIT
    32.50
  8
  8/74
  6/71
  6/71
                                              F-15

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

DAIRYLAND POWER: ALMA 5 (CONT.)
 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE         NR
     CONSTRUCTION MATERIAL SPECIFIC TYPE        NR

 «* ABSORBER
     GENERIC TYPE                               NR
     SPECIFIC TYPE                              NR
     TRADE NAME/COMMON TYPE                     NR
     SHELL GENERIC MATERIAL                     NR
     SHELL SPECIFIC MATERIAL                    NR
     SHELL MATERIAL TRADE NAME/COMMON TYPE      NR
     LINER GENERIC MATERIAL                     NR
     LINER SPECIFIC MATERIAL                    NR
     LINER MATERIAL TRADE NAME/COMMON TYPE      NR

 *« MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR        NR
     GENERIC TYPE                               NR
     SPECIFIC TYPE                              NR
     TRADE NAME/COMMON TYPE                     NR
     CONSTRUCTION MATERIAL GENERIC TYPE         NR
     CONSTRUCTION MATERIAL SPECIFIC TYPE        NR

 ** REHEATER
     GENERIC TYPE                               NR
     SPECIFIC TYPE                              NR
     TRADE NAME/COMMON TYPE                     NR
     CONSTRUCTION MATERIAL GENERIC TYPE         NR
     CONSTRUCTION MATERIAL SPECIFIC TYPE        NR

 *« FANS
     DESIGN                                     NR
     FUNCTION                                   NR
     APPLICATION                                NR
     SERVICE                                    NR
     CONSTRUCTION MATERIAL GENERIC TYPE         NR

 ** DAMPERS
     FUNCTION                                   NR
     GENERIC TYPE                               NR
     SPECIFIC TYPE                              NR
     CONSTRUCTION MATERIAL GENERIC TYPE         NR
     CONSTRUCTION MATERIAL SPECIFIC TYPE        NR
     LINER GENERIC MATERIAL TYPE                NR
     LINER SPECIFIC MATERIAL TYPE               NR

 »* DUCTWORK
       SHELL GENERIC MATERIAL TYPE               NR
       SHELL SPECIFIC MATERIAL TYPE              NR
       LINER GENERIC MATERIAL TYPE               NR
       LINER SPECIFIC MATERIAL TYPE              NR

 ** REAGENT PREPARATION  EQUIPMENT
     FUNCTION                                   SLAKER
     DEVICE                                     NR
     DEVICE TYPE                                NR

 #* TANKS
     SERVICE                                    NUMBER
     NR

 ** PUMPS
     SERVICE

     NR
                                                 ****
NUMBER
                                              F-16

-------
                                                  UTILITY FED SURVEY:  OCTOBER  1983  - SEPTEMBER 1984
OAIRYUND POWER: ALMA 5 (CONT.)
 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE

*«* SLUDGE

 «* TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 *« DISPOSAL
     NATURE
     TYPE
NA
NA
NA
NA
NR
NR
                                              F-17

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC F60 SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MM
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MM
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M
DETROIT EDISON
ST. CLAIR
6A
BELLE RIVER
MICHIGAN
A
   86.
 1376.
******
 1798
  325
(   .200 LB/MMBTU)
(  3.200 LB/MMBTU)
(****** LB/MMBTU)
  163
  163
COMBUSTION ENGINEERING
******
PEAK
  465.77
  132.2
  130.
NR
*******
(  987000 ACFM)
(  270 F)
(  425 FT)

(****« FT)
 **  FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RAN3E HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RAN3E MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

 ***  PARTICLE CONTROL

 **  MECHANICAL COLLECTOR
     NUMBER
     TYPE

 **  FABRIC FILTER
     NUMBER
     TYPE

 **  ESP
     NUMBER
     SUPPLIER
     PARTICLE REMOVAL EFFICENCY - 7.

 **  PARTICLE SCRUBBER
     NUMBER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - LITER/CU.M
     PRESSURE DROP - KPA
COAL
SUBBITUMINOUS
22330.         (   9600 BTU/LB)
                9500-9600
    4.00
3.0-4.0
   22.60
22.0-24.0
     .35
0.3-0.4
********
******
 0
NONE
 0
NONE
WHEELABRATOR-FRYE
   90.0
 2
 9/75
VENTURI TOWER
VARIABLE-THROAT/ADJUSTABLE DRUM
RADIAL FLOW VENTURI
PEABODY-LURGI
STAINLESS STEEL
AUSTENITIC
ORGANIC
NATURAL RUBBER
NONE
  278.5        ( 4420 GPM)
    2.7        (20.0 GAL/1000ACF)
    3.5        (14.0 IN-H20)
                                              F-18

-------
                                                  UTILITY FGD SURVEY:  OCTOBER  1983  -  SEPTEMBER
DETROIT EDISON:  ST. CLAIR 6A (CONT.)

     SUPERFICIAL GAS VELOCITY - M/S
     INLET GAS FLOW RATE - CU.M/S
     INLET GAS TEMPERATURE - C

«** FGD SYSTEM

 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     ENERGY CONSUMPTION - X
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP
     CONTRACT AWARDED

 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     L/G RATIO - L/CU.M
     GAS-SIDE PRESSURE DROP - KPA
     SUPERFICAL GAS VELOCITY - M/SEC
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C
     S02 REMOVAL EFFICIENCY - X

 »« MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     NUMBER  PER SYSTEM
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONFIGURATION
     FREEBOARD DISTANCE  - M
     DISTANCE BETWEEN VANES - CM
     VANE ANGLES - DEGREES
     PRESSURE DROP - KPA
     SUFERFICAL GAS VELOCITY - M/S
     CONSTRUCTION  MATERIAL GENERIC TYPE
     CONSTRUCTION  MATERIAL SPECIFIC TYPE

 *« REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     PERCENT GAS BYPASSED - AVG
     TEMPERATURE INCREASE - C
    28.3
   116.6
   132.2
(    93.0 FT/S)
(  247000 ACFM)
(   270 F)
 THROWAWAY PRODUCT
 WET SCRUBBING
 LIMESTONE
 PEABODY PROCESS SYSTEMS
 BECHTEL
 DEMONSTRATION
 RETROFIT
X   99.70
    90.00
     2.8
  8
 12/76
  9/75
  6/75
  0/71
 NR
 NR
 SPRAY TOWER
 OPEN COUNTERCURRENT SPRAY
 N/A
 PEABODY PROCESS SYSTEMS
 STAINLESS STEEL
 AUSTENITIC
 TYPE 316L
 NOME
 N/A
 N/A
 NONE
    10.7        (80.0 GAL/1000 ACF)
     2.5        (10.0 IN-H20)
     2.9        (  9.5 FT/S)
   101.46       ( 215000 ACFM)
    47.8        (  118 F)
    90.0
 PRIMARY COLLECTOR
  2
 CENTRIFUGAL
 RADIAL VANE
 RADIAL BAFFLE
 HORIZONTAL
     1.37       ( 4.5 FT)
    20.3        ( 8.00 IN)
   45
       .0        (   .2 IN-H20)
     3.0        ( 10.0 FT/S)
 STAINLESS STEEL
 AUSTENITIC
  DIRECT COMBUSTION
  EXTERNAL COMBUSTION CHAMBER
  OIL
       .0
    27.8         (   50  F)
                                              F-19

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

DETROIT EDISON: ST. CLAIR 6A (CONT.)

     INLET FLUE GAS FLOW RATE - CU. M/S
     INLET FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     NUMBER
     SUPPLIER
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 »* DUCTWORK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 «* REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE
     NUMBER
     PRODUCT QUALITY - X SOLIDS

 ** PUMPS
     SERVICE
     VENTURI RECIRCULATION
     SPRAY TOWER RECIRCULATION

 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUM3ER

*** SLUDGE

 ** TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 ** DISPOSAL
     NATURE
     TYPE
     SITE TRANSPORTATION METHOD
     SITE TREATMENT
     SITE SERVICE LIFE - YRS

 ** PROCESS CONTROL AND INSTRUMENTATION
     CHEMICAL PARAMETERS
     CONTROL LEVELS
     MONITOR LOCATION
     PROCESS CONTROL MANNER
     PROCESS CHEMISTRY MODE

 ** WATER BALANCE
     WATER LOOP TYPE
                                                  187.20
                                                   50.0
               (  396700 ACFM)
               (   122 F)
                                                NR
                                                NR
                                                PEABOOY PROCESS SYSTEMS
                                                BOOSTER
                                                INDUCED DRAFT
                                                WET
                                                STAINLESS STEEL
                                                NR
                                                NR
                                                NR
                                                NR
                                                NR
                                                NR
                                                NR
                                                NR
                                                NR
                                                NR
                                                NR
                                                NONE
                                                N/A
                                                N/A
                                                 1
                                                   35.0
                                                NUMBER
   3
   6
NONE
 0
BLEED
N/A
N/A
FINAL
POND
PIPELINE
NONE
  1
PH, SOLIDS
PH 5.8-6.0; SOLIDS 15X
RECYCLE TANK
AUTOMATIC
FEEDBACK
                                                OPEN
                                             F-20

-------
                                                 UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                          APPENDIX F
              DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC F6D SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW
GULF POWER
SCHOL2
1
SNEADS
FLORIDA
E
******
******
******
80
20
*****
*****
20


( ******
( ******
( ******







LB/MMBTU )
LB/MMBTU )
LB/MMBTU )





 ** UNIT  DATA  -  BOILER  AND  STACK
     BOILER  SUPPLIER
     BOILER  TYPE
     BOILER  SERVICE  LOAD
     DESIGN  BOILER FLUE GAS FLOW - CU.M/S
     BOILER  FLUE GAS  TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL  DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT  CONTENT - BTU/LB
     AVERAGE ASH CONTENT -  Y.
     RANGE ASH CONTENT  - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTUPE  CONTENT - 7.
     AVERAGE SULFUR  CONTENT - 7.
     RANGE SULFUR CONTENT  - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE  CONTENT - 7.

*** PARTICLE CONTROL
BABCOCK « WILCOX
PULVERIZED COAL
BASE
   50.02       ( 106000 ACFM)
*******        (**** F)
******         (**** FT)
NR
*******        (***** FT)
COAL
******
30005.

********
******
********
******
    3.25
3.0-3.5
********
******
(  12900 BTU/LB)
 ******
 ** ESP
     NUMBER

 *« PARTICLE SCRUBBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
NR
NR
NR
NR
NR
NR
NR
*** FGD SYSTEM
 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     CURRENT STATUS
     TERMINATION
     INITIAL START-UP
THROWAWAY PRODUCT
WET SCRUBBING
DUAL ALKALI/LIMESTONE
THYSSEN/CEA
A.D. LITTLE
DEMONSTRATION
RETROFIT
 8
 5/81
 8/80
                                             F-21

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

GULF POWER: SCHOLZ 1 (CONT. )
 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 «* ABSORBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** REHEATER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     TEMPERATURE INCREASE - C
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 »* DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTU'CRK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

 ** PUMPS
     SERVICE
     NR
 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUMBER
     SHELL GENERIC MATERIAL TYPE
     SHELL SPECIFIC MATERIAL TYPE
NR
NR
TRAY TOWER
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
INDIRECT HOT AIR
NR
NR
   zz.z
40 F)
NR
NR
CENTRIFUGAL
BOOSTER
INDUCED DRAFT
WET
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
                                                NUMBER

                                                *«**
THICKENER
 1
CARBON STEEL; ORGANIC  ILININGI
AISI 1110; NR
                                              F-22

-------
                                                  UTILITY F6D SURVEY:  OCTOBER  1983 -  SEPTEMBER  1984
GULF POWER:  SCHOLZ 1 (CONT.)
 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUMBER
     SHELL SPECIFIC MATERIAL TYPE
     FEED STREAM CHARACTERISTICS

«** SLUDGE

 »* TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 «* DISPOSAL
     NATURE
     TYPE
     SITE TREATMENT

 ** MATER BALANCE
     WATER LOOP TYPE
VACUUM FILTER
 1
FIBERGLASS
20X SOLIDS
DEWATERED
N/A
N/A
FINAL
POND
CLAY LINING
                                                CLOSED
                                              F-23

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
502 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MM
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 «* FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - Y.
     RAN3E ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** ESP
     NUMBER
     TYPE
     SUPPLIER
     PARTICLE REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     NUM3ER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE

»** FGD SYSTEM

 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     DEVELOPMENT LEVEL
     NEW/RETROFIT
GULF POWER
SCHOLZ
1A
SNEADS
FLORIDA
A
******
  516.
******
   80
   48
   40
*****
   48
BABCOCK £ WILCOX
PULVERIZED COAL
BASE
               (****** LB/MMBTU)
               (  1.200 LB/MMBTU)
               (****** LB/MMBTU)
               (******* ACFM)
               (  295 F)
               (**** FT)

               (***** FT)
               (****** BTU/LB)
                ******
********
  146.1
******
NR
*******
COAL
******
******

********
******
********
******
    5.00
******
********
******
COLD SIDE
BUELL DIVISION, ENVIROTECH
   99.5
 1
 2/75
VENTURI TOWER
VARIABLE-THROAT/TOP-ENTRY PLUMB BOB
N/A
THYSSEN/CEA
CARBON STEEL
AISI 1110
INORGANIC
HYDRAULICALLY-BONDED MORTAR
NONE
THROWAWAY PRODUCT
WET SCRUBBING
DUAL ALKALI
THYSSEN/CEA
PROTOTYPE
RETROFIT
                                             F-24

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
GULF POWER: SCHOL2 1A (CONT.)

     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY - X   99.70
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP

 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 *« ABSORBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST  ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     PERCENT GAS BYPASSED - AVG
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

  ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC  MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
       SHELL GENERIC MATERIAL TYPE
       SHELL SPECIFIC  MATERIAL  TYPE
       LINER GENERIC MATERIAL TYPE
       LINER SPECIFIC  MATERIAL  TYPE

 *» REAGENT PREPARATION  EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE
   95.00
 8
 7/76
 2/75
 Z/75
NR
NR
VENTURI TOWER
NR
NR
THYSSEN/CEA
CARBON STEEL
AISI 1110
N/A
ORGANIC
GLASS FLAKE-FILLED POLYESTER
NR
NONE
NR
NR
NR
NR
NR
NR
 1
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
    5.0
                                              F-25

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

GULF POWER: SCHOLZ 1A (CONT.)
 ** PUMPS
     SERVICE                                    NUMBER
     NR                                         ****

 #* SOLIDS CONCENTRATING/DEWATERING
     DEVICE                                     VACUUM .FILTER
     NUMBER                                      1
     CONFIGURATION                              ROTARY DRUM
     SHELL GENERIC MATERIAL TYPE                INORGANIC
     SHELL SPECIFIC MATERIAL TYPE               NR

*** SLUDGE

 ** TREATMENT
     METHOD                                     DEWATERED
     DEVICE                                     N/A
     PROPRIETARY PROCESS                        N/A

 *# DISPOSAL
     NATURE                                     FINAL
     TYPE                                       POND
     LOCATION                                   ON-SITE
     SITE TREATMENT                             CLAY LINING

 ** WATER BALANCE
     WATER LOOP TYPE                            CLOSED
                                             F-26

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER
                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MM
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - '/.
     RANGE ASH CONTENT - 7.
  .  AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** ESP
     NUMBER
     TYPE
     SUPPLIER
     PARTICLE REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     NUMBER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE

«** FGD SYSTEM

 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     DEVELOPMENT LEVEL
     NEW/RETROFIT
               (****** LB/MMBTU)
               (  1.200 LB/MMBTU)
               (*****« LB/MMBTU)
GULF POWER
SCHOLZ
1B.2B
SNEADS
FLORIDA
A
******
  516.
******
   80
   48
   40
*****
   48
BABCOCK t WILCOX
PULVERIZED COAL
BASE
********       (******* ACFM)
  146.1        ( 295 F)
   23.         (  76 FT)
FIBER-REINFORCED POLYESTER
*******        (***** FT)
               (*»**** BTU/LB)
                ******
COAL
******
*****-*

********
******
********
******
    5.00
******
********
******
COLD SIDE
BUELL DIVISION, ENVIROTECH
   99.5
 1
 2/75
VENTURI TOWER
VARIABLE-THROAT/TOP-ENTRY PLUMB BOB
N/A
CHIYODA INTERNATIONAL
CARBON STEEL
AISI 1110
INORGANIC
HYDRAULICALLY-BONDED MORTAR
NONE
THROWAWAY PRODUCT
WET SCRUBBING
THOROUGHBRED 101
CHIYODA  INTERNATIONAL
PROTOTYPE
RETROFIT
                                              F-27

-------
UTILITY FGO SURVEY: OCTOBER 1983 - SEPTEMBER 1984
GULF POWER: SCHOLZ 1B.2B (CONT.)

     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP

 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 *» ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     NUMBER PER SYSTEM
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** REHEATER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     PERCENT GAS BYPASSED - AVG
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE
X   99.70
    90.00
  8
  3/77
  2/75
  2/75
 NR
 NR
 PACKED TOWER
 NR
 NR
 CHIYODA INTERNATIONAL
 STAINLESS STEEL
 AUSTENITIC
 TYPE 316L
 NONE
 N/A
 N/A
 PRIMARY COLLECTOR
  2
 IMPINGEMENT
 BAFFLE
 CLOSED VANE
 NR
 NR
 NR-
 NR
 NR
     5.0
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 MIX TANK
 N/A
 AGITATED TANK
                                             F-28

-------
                                                  UTILITY F6D SURVEY:  OCTOBER 1983 -  SEPTEMBER  1984
GULF POWER: SCHOLZ 1B.2B (CONT.)
 ** SOLIDS CONCENTRATING/OEWATERING
     DEVICE
     NUMBER
     CONFIGURATION

*** SLUDGE

 ** TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 ** DISPOSAL
     NATURE
     TYPE
     SITE TREATMENT

 »* WATER BALANCE
     WATER LOOP TYPE
CENTRIFUGE
 1
CONTINUOUS SCREW-DECANTER/SOLID BOWL
DEMATERED
N/A
N/A
FINAL
POND
CLAY LINING
OPEN
                                              F-29

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     PAUSE ASH CONTENT - V.
     AVERAGE MOISTURE CONTENT - 7.
     RAN3E MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RAN3E SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** ESP
     NUMBER
     TYPE
     SUPPLIER
     INLET FLUE GAS TEMPERATURE - C
     PARTICLE REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
               (***#** LB/MMBTU)
               (****** LB/MMBTU)
               (*****» LB/MMBTU)
GULF POWER
SCHOLZ
1,2
SNEADS
FLORIDA
A
******
******
******
   80
   23
   23
*****
   23
BABCOCK A WILCOX
PULVERIZED COAL
BASE
********       (**#**** ACFM)
*******        (**** F)
   23.         (  76 FT)
FIBER-REINFORCED POLYESTER
*******        (***** FT)
               (  12500 BTU/LB)
                ******
COAL
BITUMINOUS
29075.

   11.00
******
    5.00
******
    2.50
2.5-5.0
********
******
COLD SIDE
BUELL DIVISION, ENVIROTECH
  151.7        (   305 F)
   99.5
 0
NONE
N/A
N/A
N/A
N/A
N/A
N/A
N/A
 ***  FGD  SYSTEM

 **  GENERAL DATA
     SALEABLE PRCDUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     PROCESS ADDITIVES
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
THROWAWAY PRODUCT
WET SCRUBBING
LIMESTONE/THOROUGHBRED 121
NONE
CHIYODA INTERNATIONAL
CHIYODA CHEMICAL ENG'R & CONSTION
PROTOTYPE
                                             F-30

-------
                                                  UTILITY FGO SURVEY:  OCTOBER  1983 -  SEPTEMBER
GULF POWER:  SCHOLZ l,Z (CONT.)

     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     CURRENT STATUS
     TERMINATION
     INITIAL START-UP

 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 »* ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C
     S02 REMOVAL  EFFICIENCY - 7.

  ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     NUMBER PER SYSTEM
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONFIGURATION
     NUMBER OF STAGES
     NUMBER OF PASSES PER STAGE
     PRESSURE DROP  - KPA
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC  TYPE

  «* REHEATER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC  TYPE

  ** FANS
     NUMBER
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     FLUE GAS FLOW  RATE  - CU.M/S
     FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE

  »* DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC  TYPE
     LINER  GENERIC  MATERIAL TYPE
     LINER  SPECIFIC MATERIAL  TYPE
 RETROFIT
X   99.50
    90.00
  8
  6/79
  8/78
 NR
 NR
 MECHANICALLY-AIDED TOWER
 GAS SPARGER
 JET BUBBLER REACTOR
 CHIYCDA INTERNATIONAL
 34.0 DIA
 STAINLESS STEEL
 AUSTENITIC
 NR
 ORGANIC
 FIBER-REINFORCED POLYESTER
 NR
 N/A
  1
    37.75       (  80000 ACFM)
   148.9        (  300 F)
    95.0
  PRIMARY COLLECTOR
   1
  IMPINGEMENT
  BAFFLE
  CLOSED VANE
  VERTICAL
      Z
      Z
       .2         ( 1.0  IN-H20)
  NR
  NR
  NONE
  N/A
  N/A
  NONE
  N/A
  CENTRIFUGAL
  BOOSTER
  FORCED  DRAFT
  DRY
     25.01
    148.9
  CARBON  STEEL
(   53000 ACFM)
(   300 F)
  NR
  NR
  NR
  NR
  NR
  NR
  NR
                                              F-31

-------
UTILITY FGD SURVEY: OCTOBER 1933 - SEPTEMBER 1984

GULF POWER: SCHOLZ 1,2 (COMT.)
 ** DUCTWORK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

 ** PUMPS
     SERVICE
     NR
 ** SOLIDS CONCENTRATING/DEMATERING
     DEVICE

*** SALEABLE BYPRODUCTS
     NATURE
     DISPOSITION

*** SLUDGE

 ** TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 ** DISPOSAL
     NATURE
     TYPE
     SITE TREATMENT

 ** PROCESS CONTROL AND INSTRUMENTATION
     PROCESS CONTROL MANNER

 ** WATER BALANCE
     WATER LOOP TYPE
NR
NR
NR
NR
WET BALL MILL
COMPARTMENTED
NR
NUMBER

****


NONE
GYPSUM
STACKED IN POND
FORCED OXIDATION
JET BUBBLER
N/A
FINAL
POND
CLAY LINING
MANUAL


CLOSED
                                             F-32

-------
                                                 UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER
                                          APPEMDIX F
              DESIGN ANO PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW
GULF POWER
SCHOLZ
2A
SNEADS
FLORIDA
A
*K****
******
******
80
48
40
*****
48






(****** LB/MMBTU)
(«***** LB/MMBTU)
(****** LB/MMBTU)





 ** UNIT  DATA  -  BOILER  AND  STACK
     BOILER  SUPPLIER
     BOILER  TYPE
     BOILER  SERVICE  LOAD
     DESIGN  BOILER FLUE GAS FLOW  -  CU.M/S
     BOILER  FLUE GAS  TEMPERATURE  -  C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL  DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT  CONTENT - BTU/LB
     AVERAGE ASH CONTENT -  V.
     RANSE ASH CONTENT  - 7.
     AVERAGE MOISTURE CONTENT - '/.
     RANSE MOISTURE  CONTENT - 7.
     AVERAGE SULFUR  CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE  CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** ESP
     NUMBER

 ** PARTICLE SCRUBBER
     NUMBER
     GENERIC TYPE
     SPECIFIC  TYPE
     TRADE NAME/COMMON  NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC  MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC  MATERIAL
     GAS CONTACTING  DEVICE  TYPE

*«* FGD SYSTEM

 «* GENERAL  DATA
     SALEABLE  PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM  SUPPLIER
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY
 BABCOCK  &  WILCOX
 PULVERIZED COAL
 BASE
                (******* ACFM)
                (  295  F)
                (****  FT)

                (***** FT)
                (****** BTU/LB)
                 ******
********
  146.1
******
NR
*******
COAL
BITUMINOUS
******

********
******
********
******
    3.50
******
********
******
  0
 NONE
  0
 NONE
 N/A
 N/A
 N/A
 N/A
 N/A
 N/A
 N/A
 SALEABLE PRODUCT
 SPRAY DRYING
 ACTIVATED CARBON
 FOSTER WHEELER/BERGBAU
 DEMONSTRATION
 RETROFIT
7.   99.70
                                             F-33

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984
GULF POWER: SCHOLZ 2A (CONT.)

     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP
     CONTRACT AWARDED

 ** DESIGN AND OPERATING PARAMETERS

 *« QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 »* REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 «* FANS
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL  TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE
   74.50
 8
 5/76
 2/76
 8/75
 1/73
NR
NR
PACKED TOWER
NR
NR
FOSTER WHEELER/BERGBAU
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
 0
NONE
N/A
N/A
NONE
N/A
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
N/A
N/A
N/A

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 -  SEPTEMBER  1984
GULF POWER: SCHOLZ 2A (CONT.)
 ** PUMPS
     SERVICE
     NR
 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE

»** SLUDGE

 ** TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 »* DISPOSAL
     NATURE
     TYPE
     SITE TREATMENT
NUMBER

****


NONE
N/A
N/A
N/A
FINAL
POND
CLAY LINING
                                              F-35

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 198*

                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER

 ** FABRIC FILTER
     NUMBER
     TYPE

 ** ESP
     NUMBER
     SUPPLIER
     PARTICLE REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE

*** FGD SYSTEM

 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     SOS REMOVAL MODE
ILLINOIS POWER COMPANY
WOOD RIVER
EAST ALTON
ILLINOIS
C
*«*K**
  774.
******
  651
  110
  103
*****
  110
(****** LB/MMBTU)
(  1.800 LB/MMBTU)
(****** LB/MMBTU)
COMBUSTION ENGINEERING
PULVERIZED COAL
BASE
********       (******* ACFM)
  154.4        (  310 F)
   76.         (  250 FT)
NR
*******        (***** FT)
COAL
******
25121.

   10.00
******
    4.30
******
    3.10
******
********
******
(  10800 BTU/LB)
 ******
 0
NONE
RESEARCH-COTTRELL
   99.6
 0
NONE
N/A
N/A
N/A
N/A
N/A
N/A
N/A
SALEABLE PRODUCT
WET SCRUBBING
                                             F-36

-------
    UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
  NR
  NR
   PACKED TOWER
   NR
   NR
   30.0 DIA X 65.0
   CARBON STEEL
   AISI 1110
   N/A
   NR
   NR
   NR
   8
      30,
       1.
     454
    12.0IN)
  4.0  IN-H20)
   850 F)
ILLINOIS POWER COMPANY: WOOD RIVER 4 (CONT.)

     PROCESS TYPE                               CATALYTIC OXIDATION
     SYSTEM SUPPLIER                            MONSANTO ENVIRO CHEM SYSTEMS
     DEVELOPMENT LEVEL                          DEMONSTRATION
     NEW/RETROFIT                               RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY -7,   99.90
     UNIT DESIGN S02 REMOVAL EFFICIENCY - '/.        85.00
     CURRENT STATUS                              8
     TERMINATION                                 0/74
     COMMERCIAL START-UP                        10/72
     INITIAL START-UP                            9/72
     CONTRACT AWARDED                            6/70

 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATCR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     NUMBER OF CONTACTING ZONES
     DISTANCE BETWEEN GAS CONTACTING ZONES - CM
     GAS-SIDE PRESSURE DROP - KPA
     INLET GAS TEMPERATURE - C
     S02 REMOVAL EFFICIENCY - '/.

 »* ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     INLET GAS TEMPERATURE - C

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     NUMBER PER SYSTEM
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     PRESSURE DROP - KPA
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     WASH FREQUENCY

 ** REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     PERCENT GAS BYPASSED - AVG
     TEMPERATURE INCREASE - C
     INLET FLUE GAS TEMPERATURE  - C
     CONSTRUCTION MATERIAL-GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
      85.0
   PACKED  TOWER
   NR
   NR
   CARBON  STEEL
   AISI  1110
   N/A
   INORGANIC
   PREFIRED BRICK/SHAPES
   ACID-RESISTANT  BRICK  [LOW H20 ABSORPTION]
     121.1        (   250  F)
   PRIMARY COLLECTOR
    1
   IMPINGEMENT
   MESH
   KNITTED WIRE MESH
       4.5
   HIGH ALLOY
   NR
   INTERMITTENT
   PAD
(18.0 IN-H20)
   IN-LINE
   NR
   NR
      14.5
     247.8
     176.7
   NR
   NR
   446 F)
   350 F)
F-37

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

ILLINOIS POWER COMPANY: WOOD RIVER 4 (CONT.)
 «* FANS
     NUMBER
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

 ** TANKS
     SERVICE
      SALEABLE BYPRODUCT

  #*  PUMPS
      SERVICE
      ACID RECIRCULATION
      PRODUCT  ACID

  **  SOLIDS  CONCENTRATING/DEWATERING
      DEVICE
      NUMBER

 ***  SLUDGE

  **  TREATMENT
      METHOD
      DEVICE
      PROPRIETARY PROCESS

  «*  DISPOSAL
      NATURE
      TYPE
      SITE TREATMENT

  **  PROCESS CONTROL AND INSTRUMENTATION
      CHEMICAL PARAMETERS
CENTRIFUGAL
NR
INDUCED DRAFT
NR
STAINLESS STEEL
NR
NR
NR
NR
NR
NR
NR
STAINLESS STEEL
NR
NONE
N/A
N/A
N/A
N/A
NUMBER

   2


NUMBER
**#*
***»
NR
 0
N/A
N/A
N/A
N/A
NOME
NR
TEMPERATURE, ASH LOADINGS, ACID CONCENTRATION
                                              F-38

-------
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MM
NET UNIT GENERATING CAPACITY M/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGO - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 *» FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
    • RAN3E MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*»* PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** FABRIC FILTER
     NUMBER
     TYPE

 »* PARTICLE SCRUBBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE

*** FGD SYSTEM

 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY  PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     PROCESS ADDITIVES
     SYSTEM SUPPLIER
     A-E FIRM
KANSAS CITY POWER t LIGHT
HAWTHORN
KANSAS CITY
MISSOURI
E
   64.
«***«*
******
  836
   90
   85
   fl7
   90
(   .150 LB/MMBTU)
(****** LB/MMBTU)
(****** LB/MMBTU)
COMBUSTION ENGINEERING
PULVERIZED COAL
CYCLING
  335.95
  148.9
   61.
CARBON STEEL
    5.5
(  500000 ACFM)
(  300 F)
(  200 FT)

(  18.0 FT)
COAL 1 (25X1
BITUMINOUS; BITUMINOUS
26388.
(  11345 BTU/LB)
 9500-10800; 10500-13000
   11.75
6-15; 9-12
    7.28
9-17; 1.5-12
    2.78
0.2-1.2! 0.6-4.6
      .15
0.01-0.06; 0.01-0.40
 0
NONE
  0
 NONE
  0
 NONE
 N/A
 N/A
 N/A
 N/A
 N/A
 N/A
 N/A
 THROWAWAY PRODUCT
 WET SCRUBBING
 LIME
 NONE
 COMBUSTION ENGINEERING
 BLACK & VEATCH
                                              F-39

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 198*
KANSAS CITY POWER « LIGHT: HAWTHORN 3 (CONT.)

     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY -
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     ENERGY CONSUMPTION - X
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP
     CONTRACT AWARDED

 ** DESIGN AND OPERATING PARAMETERS
     DESIGN COAL SULFER CONTENT - X
     DESIGN COAL HEAT CONTENT - J/G
     DESIGN COAL ASH CONTENT - X
     DESIGN MOISTURE CONTENT - X
     DESIGN CHLORIDE CONTENT - X
     SPACE REQUIREMENTS - SQ M
     OPER. i MAINT. REQUIREMENT - MANHR/DAY

 ** QUENCHER/PRESATURATOR
     NUMBER

 ** ABSORBER
     NUMBER
     NUMBER OF SPARES
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - L/CU.M
     GAS-SIDE PRESSURE DROP - KPA
     SUPERFICAL GAS VELOCITY - M/SEC
     INLET GAS FLOU - CU. M/S
     INLET GAS TEMPERATURE - C
     S02 REMOVAL EFFICIENCY - X
     PARTICLE REMOVAL EFFICENCY - X

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     NUMBER PER SYSTEM
     NUMBER OF SPARES PER SYSTEM
     NUMBER PER MODULE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     MANUFACTURER
     CONFIGURATION
     NUMBER OF STAGES
     NUMBER OF PASSES PER STAGE
     FREEBOARD DISTANCE - M
     DISTANCE BETWEEN STAGES - CM
     DISTANCE BETWEEN VANES - CM
     VANE ANGLES - DEGREES
     PRESSURE DROP - KPA
     SUPERFICAL G4S VELOCITY - M/S
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     WASH WATER SOURCE
     WASH FREQUENCY
     WASH RATE - L/S
 FULL SCALE
 RETROFIT
X   99.00
    70.00
     2.2
  8
 10/82
 11/72
 11/72
  0/71
     2.80
 26400.1
    11.80
     7.30
      .15
   688.4
   136.0
(  11350 BTU/LB)
    7410 SO FT)
  2
  0
 PACKED TOWER
 STATIC BED PACKING
 MARBLE-BED SCRUBBER
 COMBUSTION ENGINEERING
 18.0 X 26.0 X 56.0
 CARBON STEEL
 AISI 1110
 N/A
 STAINLESS STEEL
 AUSTENITIC
 TYPE 316L
 GLASS MARBLES
  1
   321.
     2.7
     2.7
     1.8
   117.97
   148.9
    50.0
    99.5
(  5090 GPM)
(  20.4 GAL/1000 ACF)
(11.0 IN-H20)
(   6.0 FT/S)
(  250000 ACFM)
(   300 F)
 PRIMARY COLLECTOR
  2
  0
  1
 IMPINGEMENT
 BAFFLE
 CLOSED VANE
 COMBUSTION ENGINEERING
 HORIZONTAL
     2
     2
     3.05       (10.0 FT)
    15.24       (  6.0 IN)
     7.6        (  3.00 IN)
   45
      .3        (  1.2 IN-H20)
     1.8        (   6.0 FT/S)
 ORGANIC
 FIBER-REINFORCED POLYESTER
 FRESH
 EVERY 48 HOURS
    63.1        (  1000 GAL/MIN)
                                             F-40

-------
KANSAS CITY POWER & LIGHT: HAWTHORN 3 (CONT.)
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER  1984
 ** REHEATER
     NUMBER
     NUMBER OF SPARES
     NUMBER PER MODULE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     LOCATION
     PERCENT GAS BYPASSED - AVG
     TEMPERATURE INCREASE - C
     INLET FLUE GAS TEMPERATURE - C
     OUTLET FLUE GAS TEMPERATURE - C
     NUMBER OF HEAT EXCHANGER BANKS
     NUMBER OF BUNDLES PER BANK
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     NUMBER
     NUMBER OF SPARES
     DESIGN
     SUPPLIER
     FUNCTION
     APPLICATION
     SERVICE
     FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE

 »* DAMPERS
     NUMBER
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     MANUFACTURER
     MODULATION
     SEAL AIR FLOW - CU. M/S
     SERVICE CONDITIONS
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DAMPERS
     NUMBER
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     MANUFACTURER
     MODULATION
     SEAL AIR FLOW - CU. M/S
     SERVICE CONDITIONS
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DAMPERS
     NUMBER
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     MANUFACTURER
     MODULATION
     SEAL AIR FLOW - CU. M/S
     SERVICE CONDITIONS
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE
 4
 0
 1
IN-LINE
HOT WATER
BARE TUBE
TOP OF ABSORBER VESSEL
     .0
   33.3        (   60 F)
   48.9        (  120 F)
   82.Z        (  180 F)
   6
   1
STAINLESS STEEL
AUSTENITIC
 Z
 0
CENTRIFUGAL
HOUDEN, CANADA
BOOSTER
INDUCED DRAFT
DRY
   79.4        (  175 F)
CARBON STEEL
SHUT-OFF
LOUVER
PARALLEL BLADE MULTILOUVER
COMBUSTION ENGINEERING .
OPEN/CLOSED
      .00       (      0 ACFM)
330
CARBON STEEL
HIGH STRENGTH LOW ALLOY CHSLA1
NONE
N/A
SHUT-OFF
LOUVER
PARALLEL BLADE MULTILOUVER
COMBUSTION ENGINEERING
OPEN/CLOSED
      .00       (      0 ACFM)
330
CARBON STEEL
HIGH  STRENGTH LOW ALLOY (HSLA1
NONE
N/A
SHUT-OFF
GUILLOTINE
TOP-ENTRY GUILLOTINE
SELF-DESIGNED  t  INSTALLED BY KCP  *
OPEN/CLOSED
      .00       (       0 ACFM)
330
CARBON STEEL
HIGH  STRENGTH  LOW  ALLOY  WSLA1
NONE
N/A
                                              F-41

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

KANSAS CITY POWER & LIGHT: HAWTHORN 3 CCONT.)
 »* DUCTWORK
     LOCATION
     CONFIGURATION
     DIMENSIONS
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
     LOCATION
     CONFIGURATION
     DIMENSIONS
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
     LOCATION
     CONFIGURATION
     DIMENSIONS
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE
     MANUFACTURER
     NUMBER
     NUMBER OF SPARES
     FULL  LOAD DRY FEED CAPACITY - M.TOHS/HR
     PRODUCT QUALITY - X SOLIDS

 ** TANKS
     SERVICE
     ABSCPBER RECYCLE
     LIME SLURRY
     CLEARWELL

 «* PUMPS
     SERVICE
     RECYCLE
     CLEAR WATER SUPPLY
     SLUDGE
     BLOUOOWN
     REHEATER FEED
     MIST ELIMINATOR WASH
     LIME SLURRY
     SCRUBSER MAKEUP

 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUrEER
     NUMBER OF SPARES
     DIMENSIONS - FT
     CAPACITY
     SHELL GENERIC MATERIAL TYPE
     SHELL SPECIFIC MATERIAL TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE
     FEED STREAM SOURCE
     FEED STREAM CHARACTERISTICS
     OUTLET STREAM CHARACTERISTICS
     OVERFLOW STREAM CHARACTERISTICS
SCRUBBER INLET
RECTANGULAR
ft.5 FT X 26 FT
CARBON STEEL
HIGH STRENGTH LOW ALLOY tHSLAJ
INORGANIC
HYDRAULICALLY-BONDED MORTAR
SCRUBBER OUTLET
RECTANGULAR
3 FT X 26 FT
CARBON STEEL
HIGH STRENGTH LOW ALLOY tHSLA]
INORGANIC
HYDRAULICALLY-BONDED MORTAR
BYPASS
RECTANGULAR
3 FT X 26 FT
CARBON STEEL
HIGH STRENGTH LOW ALLOY [HSLAJ
NONE
N/A
SLAKER
NR
NR
COFFMAN INDUSTRIES
 1
 0
   51.7        (57 TPH)
   25.0
NUMBER

   2
   1
   1
NUMBER

   2
   2
   2
   2
   4
   4
   1
   2
THICKENER
 1
0
115.0 DIA X 10.0
75000
CARBON STEEL [WALLS); INORGANIC [BOTTOM]
AISI 1110; HYDRAULICALLY-BONDED CONCRETE
ORGANIC
NR
ABSORBER BLEED
12X SOLIDS
30X SOLIDS
13900 GFM
                                             F-42

-------
KANSAS CITY POWER * LIGHT: HAUTHORN 3 (CONT.)

     OUTLET STREAM DISPOSITION
     OVERFLOW STREAM DISPOSITION

*** SLUDGE

 ** TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 ** DISPOSAL
     NATURE
     TYPE
     LOCATION
     SITE TRANSPORTATION METHOD
     SITE TREATMENT
     SITE DIMENSIONS
     SITE CAPACITY - CU.M
     SITE SERVICE LIFE - YRS

 ** PROCESS CONTROL AND INSTRUMENTATION
     PROCESS STREAM
     CHEMICAL PARAMETERS
     PHYSICAL VARIABLES
     CONTROL LEVELS
     MONITOR LOCATION
     PROCESS CONTROL MANNER
     PROCESS CHEMISTRY MODE

 *» MATER BALANCE
     WATER LOOP  TYPE
     RECEIVING WATER STREAM
     SOURCE OF MAKEUP WATER

 ** CHEMICALS AND CONSUMPTION
     FUNCTION
     NAME
     PRINCIPAL CONSTITUENT
     SOURCE/SUPPLIER
     POINT OF ADDITION

 ** FGD  SPARE CAPACITY INDICES
     ASS03BER -  '/.
     MIST ELIMINATOR - X
     REHEATER -  X
     FAN - X
     SLAKER - X
     EFFLUENT HOLD TANK -  X
     RECIRCULATION PUMP -  X
     THICKENER - X

 ** FGO  SPARE COMPONENT INDICES
     ABSORBER
     MIST ELIMINATOR
     REHEATER
     FAN
     SLAKER
     EFFLUENT HOLD TANK
     RECIRCULATION PUMP
     THICKENER
                                                  UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984
TO ASH POND
TO RECYCLE CANAL, ASH SLUICE PUMP
BLEED
N/A
N/A
FINAL
POUD
ON-SITE
PIPELINE
NONE
40 ACRES/15 FT
    733800
  3
(    600.0 ACRE-FT)
RECIRCUUTING SLURRY
PH
X SOLIDS
PH 5.5-6.0, 10X SOLIDS
GRAB SAMPLES TO LABORATORY
MANUAL
FEEDBACK
OPEN
MISSOURI RIVER
MISSOURI RIVER
ABSORBENT
LIME
93X CAO
ASHGROVE
LIME SLAKER
      .0
      .0
      .0
      .0
      .0
      .0
      .0
      .0
      .0
      .0
      .0
      .0
      .0
      .0
      .0
      .0

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
SOS EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MM
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MM
NET UNIT GENERATING CAPACITY MO/FGD - MM
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOM - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - V.
     RANGE ASH CONTENT - '/.
     AVERAGE MOISTURE CONTENT - '/.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - '/.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RAN3E CHLORIDE CONTENT - '/.

*** PARTICLE CONTROL

 *» MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** FABRIC FILTER
     NUMBER
     TYPE

 ** PARTICLE SCRUBBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE

*** FGD SYSTEM

 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     PROCESS ADDITIVES
     SYSTEM SUPPLIER
     A-E FIRM
KANSAS CITY POMER 4 LIGHT
HAWTHORN
4
KANSAS CITY
MISSOURI
E
   64.         (  .150 LB/MMBTU)
******         (****** LB/MMBTU)
******         (****** LB/MMBTU)
  836
   90
   85
   87
   90
COMBUSTION ENGINEERING
PULVERIZED COAL
CYCLING
  235.95
  148.9
   61.
CARBON STEEL
    5.5
(  500000 ACFM)
(  300 F)
(  200 FT)

(  18.0 FT)
COAL 1 125X1
BITUMINOUS; BITUMINOUS
26388.         (  11345 BTU/LB)
                9500-108005 10500-13000
   11.75
6-15; 9-12
    7.28
9-17; 1.5-12
    2.78
0.2-1.2! 0.6-4.6
     .15
0.01-0.06; 0.01-0.40
 0
NONE
 0
NONE
 0
NONE
N/A
N/A
N/A
N/A
N/A
N/A
N/A
THROWAWAY PRODUCT
WET SCRUBBING
LIME
NONE
COMBUSTION ENGINEERING
BLACK & VEATCH
                                             F-44

-------
                                                  UTILITY FGD SURVEY:  OCTOBER  1983 - SEPTEMBER 1984
KANSAS CITY POWER & LIGHT: HAWTHORN 4 (CONT. )

     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY •
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     ENERGY CONSUMPTION - X
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP
     CONTRACT AWARDED

 ** DESIGN AND OPERATING PARAMETERS
     DESIGN COAL SULFER CONTENT - X
     DESIGN COAL HEAT CONTENT - J/G
     DESIGN COAL ASH CONTENT - X
     DESIGN MOISTURE CONTENT - X
     DESIGN CHLORIDE CONTENT - X
     SPACE REQUIREMENTS - SQ M
     OPER. 4 MAINT. REQUIREMENT - MANHR/DAY

 «* QUENCHER/PRESATURATOR
     NUMBER

 ** ABSORBER
     NUMBER
     NUMBEP OF SPARES
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - L/CU.M
     GAS-SIDE PRESSURE DROP - KPA
     SUPERFICAL GAS VELOCITY - M/SEC
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C
     S02 REMOVAL EFFICIENCY - X
     PARTICLE REMOVAL EFFICENCY - X

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     NUMBER PER SYSTEM
     NUMBER OF SPARES PER SYSTEM
     NUMBER PER MODULE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     MANUFACTURER
     CONFIGURATION
     NUMBER OF STAGES
     NUMBER OF PASSES PER STAGE
     FREEBOARD DISTANCE - M
     DISTANCE BETWEEN STAGES - CM
     DISTANCE BETWEEN VANES - CM
     VANE ANGLES - DEGREES
     PRESSURE DROP - KPA
     SUPERFICAL GAS VELOCITY - M/S
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     WASH WATER SOURCE
     WASH FREQUENCY
     WASH RATE - L/S
 FULL SCALE
 RETROFIT
X   99.00
    70.00
     2.2
  8
 10/82
 11/72
  8/72
  0/71
     2.80
 26400.1
    11.80
     7.30
      .15
   688.4
   136.0
(  11350 BTU/LB)
(    7410 SQ FT)
  Z
  0
 PACKED TOWER
 STATIC BED PACKING
 MARBLE-BED SCRUBBER
 COMBUSTION ENGINEERING
 18.0 X 26.0 X 56.0
 CARBON STEEL
 AISI 1110
 N/A
 STAINLESS STEEL
 AUSTENITIC
 TYPE 316L
 GLASS MARBLES
  1
   321.
     2.7
     2.7
     1.8
   117.97
   148.9
    50.0
    99.5
( 5090 GPM)
( 20.4 GAL/1000 ACF)
(11.0 IN-H20)
(  6.0 FT/S)
( 250000 ACFM)
(  300 F)
 PRIMARY COLLECTOR
  2
  0
  1
 IMPINGEMENT
 BAFFLE
 CLOSED VANE
 COMBUSTION ENGINEERING
 HORIZONTAL
     2
     2
     3.05       (10.0 FT)
    15.24       ( 6.0 IN)
     7.6        ( 3.00 IN)
   45
       .3        (1.2 IN-H20)
     1.8        (6.0 FT/S)
 ORGANIC
 FIBER-REINFORCED POLYESTER
 FRESH
 EVERY 48 HOURS
    63.1        ( 1000 GAL/MIN)
                                              F-45

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

KANSAS CITY POWER & LIGHT: HAWTHORN 4 (CONT. )
 ** REHEATER
     NUMBER
     NUMBER OF SPARES
     NUMBER PER MODULE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     LOCATION
     PERCENT GAS BYPASSED - AVG
     TEMPERATURE INCREASE - C
     INLET FLUE GAS TEMPERATURE - C
     OUTLET FLUE GAS TEMPERATURE - C
     NUMBER OF HEAT EXCHANGER BANKS
     NUMBER OF BUNDLES PER BANK
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     NUMBER
     NUMBER OF SPARES
     DESIGN
     SUPPLIER
     FUNCTION
     APPLICATION
     SERVICE
     FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     NUMBER
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     MANUFACTURER
     MODULATICN
     SEAL AIR FLOW - CU. M/S
     SERVICE CONDITIONS
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 »* DAMPERS
     NUMBER
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     MANUFACTURER
     MODULATION
     SEAL AIR FLOW - CU. M/S
     SERVICE CONDITIONS
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DAMPERS
     NUMBER
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     MANUFACTURER
     MODULATION
     SEAL AIR FLOW - CU. M/S
     SERVICE CONDITIONS
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE
 4
 0
 1
IN-LINE
HOT WATER
BARE TUBE
TOP OF ABSORBER VESSEL
     .0
   33.3        (   60 F)
   48.9        (  120 F)
   82.2        (  180 F)
   6
   1
STAINLESS STEEL
AUSTENITIC
 2
 0
CENTRIFUGAL
HOUDEN, CANADA
BOOSTER
INDUCED DRAFT
DRY
   79.4        (   175 F)
CARBON STEEL
SHUT-OFF
LOUVER
PARALLEL BLADE MULTILOUVER
COMBUSTION ENGINEERING
OPEN/CLOSED
     .00       (       0 ACFM)
330
CARBON STEEL
HIGH STRENGTH LOW ALLOY [HSLAJ
NONE
N/A
SHUT-OFF
LOUVER
PARALLEL BLADE MULTILOUVER
COMBUSTION ENGINEERING
OPEN/CLOSED
     .00       (       0 ACFM)
330
CARBON STEEL
HIGH STRENGTH LOW ALLOY IHSLAI
NONE
N/A
SHUT-OFF
GUILLOTINE
TOP-ENTRY GUILLOTINE
SELF-DESIGNED & INSTALLED BY KCP S
OPEN/CLOSED
     .00       (      0 ACFM)
330
CARBON STEEL
HIGH STRENGTH LOW ALLOY IHSLAJ
NONE
N/A
                                             F-46

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER
KANSAS CITY POWER t LIGHT: HAWTHORN 4 (CONT.)
 ** DUCTWORK
     LOCATION
     CONFIGURATION
     DIMENSIONS
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
     LOCATION
     CONFIGURATION
     DIMENSIONS
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 »* DUCTWORK
     LOCATION
     CONFIGURATION
     DIMENSIONS
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE
     MANUFACTURER
     NUMBER
     NUMBER OF SPARES
     FULL  LOAD DRY FEED CAPACITY - M.TONS/HR
     PRODUCT QUALITY - X SOLIDS

 ** TANKS
     SERVICE
     ABSORBER RECYCLE
     LIME SLURRY
     CLEARWELL

  **  PUMPS
     SERVICE
      RECYCLE
      CLEAR  WATER  SUPPLY
      SLUDGE
      SLOWDOWN
      REHEATER  FEED
      MIST ELIMINATOR WASH
      LIME SLURRY
      SCRUBBER  MAKEUP

  **  SOLIDS  CONCENTRATING/DEWATERING
      DEVICE
      NUMBER
      NUMBER OF SPARES
      DIMENSIONS - FT
      CAPACITY
      SHELL  GENERIC MATERIAL  TYPE
      SHELL  SPECIFIC MATERIAL TYPE
      LINER  GENERIC MATERIAL  TYPE
      LINER  SPECIFIC MATERIAL TYPE
      FEED STREAM  SOURCE
      FEED STREAM  CHARACTERISTICS
      OUTLET STREAM CHARACTERISTICS
      OVERFLOW  STREAM CHARACTERISTICS
SCRUBBER INLET
RECTANGULAR
4.5 FT X 26 FT
CARBON STEEL
HIGH STRENGTH LOW ALLOY IHSLA1
INORGANIC
HYDRAULICALLY-BONDED MORTAR
SCRUBBER OUTLET
RECTANGULAR
3 FT X 26 FT
CARBON STEEL
HIGH STRENGTH LOW ALLOY IHSLAJ
INORGANIC
HYDRAULICALLY-BONDED MORTAR
BYPASS
RECTANGULAR
3 FT X 26 FT
CARBON STEEL
HIGH STRENGTH
NONE
N/A
LOW ALLOY IHSLAI
SLAKER
NR
NR
COFFMAN INDUSTRIES
 1
 0
   51.7        (  57 TPH)
   25.0
NUMBER

   2
   1
   1
NUMBER

   2
   2
   2
   2
THICKENER
  1
0
115.0 DIA X 10.0
75000
CARBON STEEL  [WALLS!; INORGANIC  tBOTTOM]
AISI 1110} HYDRAULICALLY-BONDED  CONCRETE
ORGANIC
NR
ABSORBER BLEED
12X SOLIDS
30X SOLIDS
13900 GPM

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

KANSAS CITY POWER & LIGHT: HAWTHORN 4 (CONT.)
     OUTLET STREAM DISPOSITION
     OVERFLOW STREAM DISPOSITION

*** SLUDGE

 ** TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 ** DISPOSAL
     NATURE
     TYPE
     LOCATION
     SITE TRANSPORTATION METHOD
     SITE TREATMENT
     SITE DIMENSIONS
     SITE CAPACITY - CU.M
     SITE SERVICE LIFE - YRS

 *» PROCESS CONTROL AND INSTRUMENTATION
     PROCESS STREAM
     CHEMICAL PARAMETERS
     PHYSICAL VARIABLES
     CONTROL LEVELS
     MONITOR LOCATION
     PROCESS CONTROL MANNER
     PROCESS CHEMISTRY MODE

 ** WATER BALANCE
     WATER LOOP TYPE
     RECEIVING WATER STREAM
     SOURCE OF MAKEUP WATER

 ** CHEMICALS AND CONSUMPTION
     FUNCTION
     NAME
     PRINCIPAL CONSTITUENT
     SOURCE/SUPPLIER
     POINT OF ADDITION

 ** FGD SPARE CAPACITY INDICES
     ABSORBER - X
     MIST ELIMINATOR - X
     REHEATER - X
     FAN - X
     SLAKER - X
     EFFLUENT HOLD TANK - X
     RECIRCULATION PUMP - X
     THICKENER - X

 «« FGD SPARE COMPONENT INDICES
     ABSORBER
     MIST ELIMINATOR
     REHEATER
     FAN
     SLAKER
     EFFLUENT HOLD TANK
     RECIRCULATION PUMP
     THICKENER
TO ASH POND
TO RECYCLE CANAL, ASH SLUICE PUMP
BLEED
N/A
N/A
FINAL
POND
ON-SITE
PIPELINE
NONE
40 ACRES/15 FT
    733800
  3
600.0 ACRE-FT)
RECIRCULATING SLURRY
PH
X SOLIDS
PH 5.5-6.0, 10X SOLIDS
GRAB SAMPLES TO LABORATORY
MANUAL
FEEDBACK
OPEN
MISSOURI RIVER
MISSOURI RIVER
ABSORBENT
LIME
93X CAO
ASHGROVE
LIME SLAKER
                                             F-48

-------
                                                  UTILITY FGD SURVEY:  OCTOBER  1983  -  SEPTEMBER
                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MM
GROSS UNIT GENERATING CAPACITY - MM
NET UNIT GENERATING CAPACITY M/FGD - MM
NET UNIT GENERATING CAPACITY MO/FGD - MM
EQUIVALENT SCRUBBED CAPACITY - MM

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOM - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - '/.
     RANGE ASH CONTENT - Y.
     AVERAGE MOISTUPE CONTENT - 7.
     RAN3E MOISTURE CONTENT - Y.
     AVERAGE SULFUR CONTENT - Y.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - Y.
     RANGE CHLORIDE CONTENT - Y.
KEY MEST UTILITY BOARD
STOCK ISLAND
1
KEY MEST
FLORIDA
E
******
  473.
******
   42
   42
   37
*****
   37
ERIE CITY
OIL FIRED
BASE
********
*******
   34.
NR
*******
OIL
NO. 6
******

     .04
******
********
******
    2.01
2.0-3.0
********
******
               (****** LB/MMBTU)
               (  1.100 LB/MMBTU)
               (****** LB/MMBTU)
               (******* ACFM)
               (**** F)
               (  110 FT)

               (***** FT)
               (****** BTU/LB)
                ******
 ***  PARTICLE  CONTROL

  **  MECHANICAL  COLLECTOR
      NUMBER
      PRESSURE DROP - KPA

  **  FABRIC FILTER
      NUM3ER
      TYPE

  **  ESP
      NUMBER
      TYPE

  **  PARTICLE  SCRUBBER
      NUM3ER
      GENERIC  TYPE
      SPECIFIC TYPE
      TRADE NAME/COMMON  NAME
      SHELL GENERIC MATERIAL
      SHELL SPECIFIC MATERIAL
      LINER GENERIC MATERIAL
      LINER SPECIFIC MATERIAL
      GAS CONTACTING DEVICE TYPE

 ***  FGD SYSTEM

  **  GENERAL DATA
      SALEABLE PRODUCT/THROMAWAY PRODUCT
      S02 REMOVAL MODE
      .6
               (  3. IN-H20)
 0
NONE
 0
NONE
 0
NONE
N/A
N/A
N/A
N/A
N/A
N/A
N/A
 THROHAMAY  PRODUCT
 MET  SCRUBBING
                                              F-49

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER
KEY WEST UTILITY BOARD: STOCK ISLAND 1 (CONT.)

     PROCESS TYPE
     SYSTEM SUPPLIER
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY - X
     UNIT DESIGN S02 REMOVAL EFFICIENCY - 7.
     CURRENT STATUS
     TERMINATION
     INITIAL START-UP
     CONTRACT AWARDED

 «* DESIGN AND OPERATING PARAMETERS

 »* QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     LIQUID RECIRCULATION RATE - LITER/S
     GAS-SIDE PRESSURE DROP - KPA
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 »* REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     NUMBER
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 *» DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 *# DUCTWORK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
LIMESTONE
ZURN AIR SYSTEM
DEMONSTRATION
NEW
   90.00
   85.00
 8
 1/75
10/72
 0/70
NR
NR
VENTURI TOWER
NR
NR
ZURN AIR SYSTEMS
STAINLESS STEEL
AUSTENITIC
TYPE 304L
NONE
N/A
N/A
SCRUBBING TUBE
   25.         (
    1.5        (
   58.04       (
   62.8        (
 400 GPM)
6.0 IN-H20)
123000 ACFM)
 145 F)
PRIMARY COLLECTOR
IMPINGEMENT
CURVED DEFLECTOR PLATE
GULL WING
ORGANIC
FIBER-REINFORCED POLYESTER
 0
NONE
N/A
N/A
NONE
N/A
 1
NR
NR
INDUCED DRAFT
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
                                             F-50

-------
                                                  UTILITY F6D SURVEY:  OCTOBER 1983 - SEPTEMBER  1984

KEY WEST UTILITY BOARD: STOCK ISLAND 1 (CONT.)

      LINER GENERIC MATERIAL TYPE               NR
      LINER SPECIFIC MATERIAL TYPE              NR

 »* REAGENT PREPARATION EQUIPMENT
     FUNCTION                                   WET BALL MILL
     DEVICE                                     NR
     DEVICE TYPE                                NR

 ** PUMPS
     SERVICE                                    NUMBER
     NR                                         «***

 *» SOLIDS CONCENTRATING/DEWATERING
     DEVICE                                     NA

 *** SLUDGE

 »* TREATMENT
     METHOD                                     BLEED
     DEVICE                                     N/A
     PROPRIETARY PROCESS                       N/A

 ** DISPOSAL
     NATURE                                     FINAL
     TYPE                                      POND
     SITE TREATMENT                            NONE

 »* PROCESS  CONTROL AND INSTRUMENTATION
     CHEMICAL PARAMETERS                       TEMPERATURE,  PARTICLE  LOADING, PH

 »* WATER BALANCE
     WATER LOOP TYPE                           OPEN
                                              F-51

-------
UTILITY FSD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC F6D SYSTEMS
COMPANY NAME
PUNT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
502 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 »* UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - V.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** ESP
     NUMBER
     TYPE
     SUPPLIER

 ** PARTICLE SCRUBBER
     NUMBER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     INLET GAS TEMPERATURE - C

*** FGD SYSTEM

 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
               (   .100 LB/MMBTU)
               (  1.200 LB/MMBTU)
               (****** LB/MMBTU)
NORTHERN INDIANA PUB SERVICE
DEAN H. MITCHELL
11
GARY
INDIANA
E
   43.
  516.
******
  505
  116
   9*
  108
  115
BABCOCK & WILCOX
PULVERIZED COAL
BASE
  198.20
  142.2
   51.
FRP
               (  420000 ACFM)
               (  288 F)
               (  168 FT)
               (***** FT)
               (  11000 BTU/LB)
                ******
*******
COAL
******
25586.

********
******
   11.00
******
    3.50
3.2-3.5
********
******
COLD SIDE
AMERICAN STANDARD
 1
 7/76
VENTURI TOWER
VARIABLE-THROAT/BOTTOM-ENTRY PLUMB BOB
N/A
CARBON STEEL
AISI 1110
NR
NR
NONE
 1
  142.2        (   288 F)
SALEABLE PRODUCT
WET SCRUBBING
WELLMAN LORD
DAVY MCKEE
DAVY MCKEE
DEMONSTRATION
                                             F-52

-------
                                                  UTILITY F6D SURVEY:  OCTOBER  1983  -  SEPTEMBER  1984

NORTHERN INDIANA PUB SERVICE: DEAN H. MITCHELL 11 (CONT.)

     NEW/RETROFIT                               RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY - X   98.50
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X        90.00
     ENERGY CONSUMPTION - X
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP
     CONTRACT AWARDED
   IZ.
 8
 3/82
 6/77
 7/76
 6/72
 »* DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 »* ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC  MATERIAL
     SHELL MATERIAL  TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC  MATERIAL
     LINER MATERIAL  TRADE NAME/COMMON TYPE
     GAS  CONTACTING  DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     GAS-SIDE PRESSURE DROP -  KPA
     INLET GAS FLOW  - CU. M/S
     S02  REMOVAL EFFICIENCY -  X

  ** MIST  ELIMINATOR
     PRE-MIST ELIMINATOR/MIST  ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

  ** REHEATER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     TEMPERATURE INCREASE  - C
     INLET FLUE  GAS  TEMPERATURE  - C
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

  ** FANS
     NUMBER
     DESIGN
      FUNCTION
     APPLICATION
     SERVICE
     FLUE GAS FLOW RATE -  CU.M/S
     FLUE GAS TEMPERATURE  - C
     CONSTRUCTION MATERIAL GENERIC TYPE

  ** FANS
     NUMBER
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE
NR
NR
TRAY TOWER
VALVE TRAY
BUBBLE CAP TRAY TOWER
DAVY MCKEE
CARBON STEEL
AISI 1110
N/A
INORGANIC
PREFIRED BRICK/SHAPES
ACID-RESISTANT BRICK [LOW H20 ABSORPTION]
VALVE TRAYS
    3.0
  198.20
   91.0
(12.0 IN-H20)
(  420000 ACFM)
NR
NR
NR
NR
NR
NR
DIRECT COMBUSTION
NR
NATURAL GAS
    27.8
    54.4
NR
NR
 CENTRIFUGAL
 BOOSTER
 FORCED DRAFT
 DRY
   198.20
   142.2
 CARBON STEEL
(    50 F)
(   130 F)
( 420000 ACFM)
(  288 F)
 CENTRIFUGAL
 UNIT
 FORCED  DRAFT
 DRY
 CARBON  STEEL;  HIGH  ALLOY
                                              F-53

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER

NORTHERN INDIANA PUB SERVICE: DEAN H. MITCHELL 11 (CONT.)
 ** DAMPERS
     FUNCTION                                   NR
     GENERIC TYPE                               NR
     SPECIFIC TYPE                              NR
     CONSTRUCTION MATERIAL GENERIC TYPE         NR
     CONSTRUCTION MATERIAL SPECIFIC TYPE        NR
     LINER GENERIC MATERIAL TYPE                NR
     LINER SPECIFIC MATERIAL TYPE               NR

 ** DUCTWOPK
     LOCATION                                   SCRUBBER INLET
      SHELL GENERIC MATERIAL TYPE               CARBON STEEL
      SHELL SPECIFIC MATERIAL TYPE              AISI 1110
      LINER GENERIC MATERIAL TYPE               NONE
      LINER SPECIFIC MATERIAL TYPE              N/A

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION                                   MIX TANK
     DEVICE                                     N/A
     DEVICE TYPE                                AGITATED TANK
     MANUFACTURER                               AGITATED TANK

 ** TANKS
     SERVICE                                    NUMBER
     REAGENT PREP PRODUCT                       ****
     ABSORBER RECYCLE                           ****

 »* PUMPS
     SERVICE                                    NUMBER
     DISSOLVING TANK TO ABSORBER FEED TAN       ***»
     FLYASH PURGE TO POND TRANSFER              «***
     ABSORBER RECIRCULATION                        3
     EVAPORATCR-CRYSTALLIZER FEED               ****
     SLURRY FEED                                ****

  ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE                                     CENTRIFUGE
     NUMBER                                      1

»** SALEABLE BYPRODUCTS
     NATURE                                     ELEMENTAL SULFUR
     QUALITY - 7.                                   99.9

*** SLUDGE

  ** TREATMENT
     METHOD                                     N/A
     DEVICE                                     N/A
     PROPRIETARY PROCESS                        N/A

  ** DISPOSAL
     NATURE                                     N/A
     TYPE                                       NONE

  ** WATER BALANCE
     WATER LOOP TYPE                            CLOSED

  ** FGD SPARE CAPACITY INDICES
     ABSORBER - '/.                                     .0

  ** FGD SPARE COMPONENT INDICES
     ABSORBER                                         .0

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 -  SEPTEMBER
                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MM
NET UNIT GENERATING CAPACITY M/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 *» UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 *» FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANSE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

 *** PARTICLE CONTROL

 ** ESP
     NUMBER

 ** PARTICLE SCRUBBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME

 *** FGD SYSTEM

 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
     NEU/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL  EFFICIENCY
     UNIT DESIGN S02 REMOVAL  EFFICIENCY  -  7.
     CURRENT STATUS
     TERMINATION
     INITIAL START-UP
     CONTRACT AUARDED
               <****** LB/MMBTU)
               (  .300 LB/MMBTU)
               («***** LB/MMBTU)
PACIFIC POWER * LIGHT
JIM BRIDGER
2A
ROCK SPRINGS
WYOMING
B
******
  129.
******
*****
  550
*****
  509
  100
 COMBUSTION ENGINEERING
 PULVERIZED COAL
 BASE
  1283.57       (2720000 ACFM)
 *******        (**** p)
   152.         ( 500 FT)
 ******
 *******        (***** FT)
 COAL
 SU3BITUMINOUS
 22330.

    11.00
 5.0-16.0
    17.00
 12.0-2*.0
      .56
 0.2-0.9
 ********
 ******
               (  9600 BTU/LB)
                ******
  0
 NONE
 N/A
 N/A
 THROWAWAY PRODUCT
 SPRAY DRYING
 LIME/SODIUM CARBONATE
 FLAKT
 FLAKT t PACIFIC POWER t LIGHT
 DEMONSTRATION
 RETROFIT
7.   99.30
    86.00
  8
  1/83
  1/82
 12/80
                                              F-55

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER

PACIFIC POWER & LIGHT: JIM BRIDGER 2A (CONT.)
 ** DESIGN AND OPERATING PARAMETERS

 *» QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 «* ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     INLET GAS TEMPERATURE - C
     SOZ REMOVAL EFFICIENCY - X
     PARTICLE REMOVAL EFFICENCY - X

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 »* REHEATER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 #* DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 *» DUCTWORK
       SHELL GENERIC MATERIAL TYPE
       SHELL SPECIFIC MATERIAL TYPE
       LINER GENERIC MATERIAL TYPE
       LINER SPECIFIC MATERIAL TYPE

 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE

 *** SLUDGE

 »* TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 »* DISPOSAL
     NATURE
     TYPE
NA
NA
SPRAY DRYER
NA
HYDRAULIC PRESSURE NOZZLE
36 FT DIAMETER
NA
NA
NA
NA
NA
NA
  121
   86
(   250 F)
   99.3
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NONE
NA
NA
NA
FINAL
LANDFILL
                                             F-56

-------
                                                  UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER  1984

PACIFIC POWER £ LIGHT: JIM BRIDGER 2A (CONT.)


 ** MATER BALANCE
     WATER LOOP TYPE                            CLOSED
                                              F-57

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 198*

                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY M/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - V.
     AVERAGE MOISTURE CONTENT - V.
     RANGE MOISTURE CONTENT - V.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER

 ** ESP
     NUMBER

 ** PARTICLE SCRUBBER
     NUMBER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     L/G RATIO - LITER/CU.M
     PRESSURE DROP - KPA
     INLET GAS FLOW RATE - CU.M/S
     INLET GAS TEMPERATURE - C

 ** PARTICLE SCRUBBER
     NUMBER
     INITIAL START-UP DATE
PHILADELPHIA ELECTRIC
EDDYSTONE
1A
EDDYSTONE
PENNSYLVANIA
C
******         (****** LB/MMBTU)
******         (****** LB/MMBTU)
******         (****** LB/MMBTU)
 1395
  120
  120
*****
  120
COMBUSTION ENGINEERING
******
BASE
  437.45       (  927000 ACFM)
  157.2        (  315 F)
   76.         (  249 FT)
CONCRETE
    5.6        (  18.5 FT)
COAL
BITUMINOUS
31634.

    9.40
******
    5.90
******
    2.60
******
********
******
               (  13600 BTU/LB)
                ******
 2
 9/75
VENTURI TOWER
VARIABLE-THROAT/VERTICALLY-ADJUSTABLE ROD DECKS
ROD SCRUBBER
ENVIRONEERING
14.0 X 25.0 X 53.0
STAINLESS STEEL
AUSTENITIC
NONE
N/A
NONE
 1
     .6        (
     .0        (
  145.8        (
  157.2        (
                 4.8 GAL/1000ACF)
                  .1 IN-H20)
                 309000 ACFM)
                  315 F)
 1
 9/75
                                             F-58

-------
                                                  UTILITY FGD SURVEY:  OCTOBER  1983  - SEPTEMBER
PHILADELPHIA ELECTRIC: EDDYSTONE 1A CCONT.)

     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     L/G RATIO - LITER/CU.M
     PRESSURE DROP - KPA
     INLET GAS FLOW RATE - CU.M/S
     INLET GAS TEMPERATURE - C

»** FGD SYSTEM

 «* GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     302 REMOVAL MODE
     PROCESS TYPE
     PROCESS ADDITIVES
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
     NEH/RETPOFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY
     UNIT DESIGN 502 REMOVAL EFFICIENCY - X
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP
     CO.MTRACT AWARDED

 ** DESIGN AND OPERATING PARAMETERS

 »* GUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 »* ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     L/G RATIO - L/CU.M
     GAS-SIDE PRESSURE DROP - KPA
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONFIGURATION
     NUMBER OF STAGES
     NUMBER OF PASSES PER STAGE
     FREEBOARD DISTANCE - M
 VENTURI TOWER
 VARIABLE-THROAT/ADJUSTABLE DRUM
 RADIAL FLOW VENTURI
 PEABODY-LURGI
 14.0 X 25.0 X  53.0
 STAINLESS STEEL
 AUSTENITIC
 NONE
 N/A
 NONE
      .6
      .0
   145.8
   157.2
(  4.8 GAL/1000ACF)
(   .1 IN-H20)
(  309000 ACFM)
(   315 F)
 SALEABLE PRODUCT
 WET SCRUBBING
 MAGNESIUM OXIDE
 NONE
 UNITED ENGINEERS
 UNITED ENGINEERS t CONSTRUCTORS
 DEMONSTRATION
 RETROFIT
X   99.00
    90.00
  8
 12/79
  9/75
  9/75
  0/73
 NR
 NR
 PACKED TOWER
 GRID PACKING
 N/A
 ENVIRONEERING, RILEY STOKER
 14.0 X 25.0 53.0
 CARBON STEEL
 HIGH STRENGTH LOW ALLOY tHSLAl
 COR-TEN
 ORGANIC
 EPOXY
 FLAKELINE E
 ROD DECKS
  2
   843.         (13384 GPM)
     6.5        ( 48.5 GAL/1000 ACF)
     2.5        (10.0 IN-H20)
   126.47       ( 266000 ACFM)
    51.7        (  125 F)
 PRIMARY COLLECTOR
 IMPINGEMENT
 BAFFLE
 CLOSED VANE
 VERTICAL
     2
     2
     2.44       t 8.0 FT)
                                              F-59

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984
PHILADELPHIA ELECTRIC: EDDYSTONE 1A (CONT.)

     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     WASH WATER SOURCE
     WASH FREQUENCY

 ** REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     TEMPERATURE INCREASE - C
     INLET FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 #* FANS
     NUMBER
     DESIGN
     SUPPLIER
     FUNCTION
     APPLICATION
     SERVICE
     FLUE GAS FLOW RATE - CU.M/S
     FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE

 *# DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
     LOCATION
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
     LOCATION
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

 ** PUMPS
     SERVICE
     ABSORBER RECIRCULATION

 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUMBER
     DIMENSIONS  - FT
     OUTLET STREAM CHARACTERISTICS

 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUM3ER
ORGANIC
FIBER-REINFORCED POLYESTER
FRESH
INTERMITTENT
DIRECT COMBUSTION
IN-LINE BURNER
OIL
   57.Z        (  103 F)
   51.7        (  125 F)
NR
NR
CENTRIFUGAL
BUFFALO FORGE
UNIT
INDUCED DRAFT
DRY
  126.47       (  268000 ACFM)
  107.2        (   225 F)
NR
NR
NR
NR
NR
NR
NR
NR
SCRUBBER INLET
STAINLESS STEEL
AUSTENITIC
NONE
N/A
SCRUBBER OUTLET
STAINLESS STEEL
AUSTENITIC
NONE
N/A
SLAKER
NR
NR
NUMBER

   2
THICKENER
 1
40.0 DIA
25X SOLIDS
CENTRIFUGE
 1
                                             F-60

-------
                                                  UTILITY F6D SURVEY:  OCTOBER  1983 - SEPTEMBER 1984
PHILADELPHIA ELECTRIC: EDDYSTONE 1A (CONT. )
*** SLUDGE

 ** TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 »* DISPOSAL
     NATURE
     TYPE
     SITE TREATMENT

 ** WATER BALANCE
     MATER LOOP TYPE
     MAKEUP WATER ADDITION - LITERS/S

 »* FGD SPARE CAPACITY INDICES
     ABSORBER - X

 #* FGD SPARE COMPONENT INDICES
     ABSORBER
DEWATERED
N/A
N/A
N/A
NONE
N/A
OPEN
    8.3
      .0
      .0
(   132 GPM)
                                              F-61

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MM
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 »« FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RAN3E CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** FABRIC FILTER
     NUMBER
     TYPE

 ** ESP
     NUMBER
     SUPPLIER
     PARTICLE REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
               (****** LB/MMBTU)
               (  1.600 LB/MMBTU)
               (****** LB/MMBTU)
POTOMAC ELECTRIC POWER
DICKERSON
3A
DICKERSON
MARYLAND
E
******
  688.
******
  548
  190
  178
  182
   95
COMBUSTION ENGINEERING
PULVERIZED COAL
BASE
  278.42       (  590000 ACFM)
  126.1        (  259 F)
  122.         (  400 FT)
CONCRETE
*******        (***** FT )
               (  11700 BTU/LB)
                ******
COAL
BITUMINOUS
27214.

   14.00
******
********
6.0-7.0
    2.00
******
********
******
 0
NONE
 0
NONE
RESEARCH-COTTRELL
   97.5
VENTURI TOWER
VARIABLE-THROAT/TOP-ENTRY PLUMB BOB
N/A
CARBON STEEL
AISI 1110
ORGANIC
FIBER-REINFORCED POLYESTER
NONE
*** FGD SYSTEM
 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
SALEABLE PRODUCT
WET SCRUBBING
                                              F-6£

-------
                                                  UTILITY F60 SURVEY:  OCTOBER  1983 - SEPTEMBER 1984
POTOMAC ELECTRIC POWER: DICKERSON 3A (CONT.)

     PROCESS TYPE
     PROCESS ADDITIVES
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     ENERGY CONSUMPTION - X
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP
     CONTRACT AWARDED

 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     L/G RATIO -  L/CU.M
    " GAS-SIDE PRESSURE DROP -  KPA
     S02 REMOVAL  EFFICIENCY -  X

  »» MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST  ELIMINATOR
     NUMBER  PER SYSTEM
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     NUMBER  OF STAGES
     NUMBER  OF PASSES  PER STAGE
     DISTANCE BETWEEN  VANES -  CM
     VANE ANGLES  - DEGREES
     PRESSURE DROP - KPA
     SUPERFICAL GAS VELOCITY  - M/S
     CONSTRUCTION MATERIAL GENERIC  TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

  *«  REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE  NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC  TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

  **  FANS
     NUMBER
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC  TYPE
 MAGNESIUM OXIDE
 NONE
 GE ENVIRONMENTAL SERVICES
 GE ENVIRONMENTAL SERVICES
 DEMONSTRATION
 RETROFIT
X   99.30
    90.00
     2.1
  8
  8/75
  7/74
  9/73
  7/71
 NR
 NR
 VENTURI TOWER
 VARIABLE-THROAT/TOP-ENTRY PLUMB BOB
 N/A
 GE ENVIRONMENTAL SERVICES
 CARBON STEEL
 AISI 1110
 N/A
 ORGANIC
 GLASS FLAKE-FILLED POLYESTER
 NR
 NONE
     5.3
     2.2
    90.0
(  40.0 GAL/1000  ACF)
(  9.0 IN-H20)
  PRIMARY COLLECTOR
  IMPINGEMENT
  BAFFLE
  CLOSED VANE
      3
      2
      5.1
    45
       .2
      3.0
  ORGANIC
( 2.00 IN)

( 1.0 IN-H20)
(10.0 FT/S)
  FIBER-REINFORCED  POLYESTER
   0
  NONE
  N/A
  N/A
  NONE
  N/A
  CENTRIFUGAL
  UNIT
  INDUCED DRAFT
  WET
  HIGH ALLOY
                                              F-63

-------
UTILITY FGD SURVEY! OCTOBER 1983 - SEPTEMBER

POTOMAC ELECTRIC POWER: DICKERSON 3A (CONT.)
 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 »« DUCTWORK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

 ** TANKS
     SERVICE
     REAGENT PREP PRODUCT

 ** PUMPS
     SERVICE
     NR
 »» SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUMBER

*«* SLUDGE

 *» TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 ** DISPOSAL
     NATURE
     TYPE
     SITE TREATMENT

 *» PROCESS CONTROL AND INSTRUMENTATION
     CHEMICAL  PARAMETERS
     CONTROL LEVELS
     MONITOR LOCATION
     PROCESS CONTROL MANNER
     PROCESS CHEMISTRY MODE
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NUMBER

   1


NUMBER

**##
THICKENER
 2
THICKENED
N/A
N/A
N/A
NONE
N/A
PH, PRESSURE DROP
PH 7
IN SECOND STAGE SYSTEM
AUTOMATIC
FEEDBACK

-------
                                                  UTILITY FGD SURVEY:  OCTOBER  1983 - SEPTEMBER 1984
                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD  SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RAN3E MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RAK3E SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RAN3E CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     INLET FLUE GAS CAPACITY - CU.M/S

 ** FABRIC FILTER
     NUMBER
     TYPE

 ** ESP
     NUMBER
     TYPE
     INLET FLUE GAS CAPACITY - CU.M/S

 ** PARTICLE SCRUBBER
     NUMBER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LIN^R SPECIFIC MATERIAL
     GAS  CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     L/G  RATIO -  LITER/CU.M
     PRESSURE DROP - KPA
               (   .100  LB/MMBTU)
               (******  LB/MMBTU)
               (******  LB/MMBTU)
PUBLIC SERVICE OF COLORADO
VALMONT
5A
VALMONT
COLORADO
D
   43.
******
******
  274
  166
  157
  163
  166
COMBUSTION ENGINEERING
PULVERIZED COAL
BASE
  436.98       (  926000 ACFM)
  126.7        (  260 F)
******         (**** FT)
NR
*******        (***** FT)
COAL
SUBBITUMINOUS
25121.

    6.00
5.4-7.0
   15.00
12.7-18.3
      .70
0.6-0.7
********
******
  218.5
 0
NONE
COLD SIDE
  218.5
               (  10800 BTU/LB)
                ******
               ( 463000 ACFM)
                ( 463000 ACFM)
 1
 11/71
 PACKED TOWER
 MOBILE BED PACKING
 TURBULENT CONTACT ABSORBER
 AIR CORRECTION DIVISION, UOP
 CARBON STEEL
 AISI 1110
 ORGANIC
 NATURAL RUBBER
 STAINLESS STEEL
 3
    7.8        (58.3 GAL/1000ACF)
    3.7        (15.0 IN-H20)
                                              F-65

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

PUBLIC SERVICE OF COLORADO: VALMONT 5A (CONT.)

     SUPERFICIAL GAS VELOCITY - M/S
     INLET GAS FLOW RATE - CU.M/S
     INLET GAS TEMPERATURE - C
     S02 REMOVAL EFFICENCY - X
     PARTICLE REMOVAL EFFICIENCY - X

*** FGD SYSTEM
 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     PROCESS ADDITIVES
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY
     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     ENERGY CONSUMPTION - X
     CURRENT STATUS
     TERMINATION
     INITIAL START-UP
     CONTRACT AWARDED

 ** DESIGN AND OPERATING PARAMETERS

 »* QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     NUMBER
     NUMBER OF SPARES
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     S02 REMOVAL EFFICIENCY - X

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONFIGURATION
     NUMBER OF STAGES
     NUMBER OF PASSES PER STAGE
     PRESSURE DROP - KPA
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     WASH WATER SOURCE

 ** REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     TEMPERATURE INCREASE - C
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 »* FANS
     DESIGN
     FUNCTION
     3.4
   109.2
   132.8
    45.0
    96.0
(    11.0 FT/S)
(  231500 ACFM)
(   271 F)
 THROWAMAY PRODUCT
 WET SCRUBBING
 LIMESTONE/ALKALINE FLYASH
 NONE
 UOP/PUBLIC SERVICE OF COLORADO
 STEARNS-ROGER
 EXPERIMENTAL
 RETROFIT
X   95.00
    85.00
     3.6
  8
  3/75
 10/74
  0/72
 NR
 NR
  1
  0
 PACKED TOWER
 MOBILE BED PACKING
 TURBULENT CONTACT ABSORBER
 AIR CORRECTION DIVISION, UOP
 CARBON STEEL
 AISI 1110
 N/A
 ORGANIC
 SYNTHETIC RUBBER
 NEOPRENE LS-576
    77.5
 PRIMARY COLLECTOR
 IMPINGEMENT
 BAFFLE
 CLOSED VANE
 HORIZONTAL
     2
     7
      .1        (   .5 IN-H20)
 STAINLESS STEEL
 NR
 SUPERNATANT
  1
 IN-LINE
 STEAM
 NR
    36.1        (   65 F)
 NR
 NR
 CENTRIFUGAL
 BOOSTER
                                             F-66

-------
                                                  UTILITY F6D SURVEY:  OCTOBER  1983  - SEPTEMBER 1984
PUBLIC SERVICE OF COLORADO'- VALMONT 5A (CONT.)

     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
     LOCATION
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 »» REAGENT PREPARATION  EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

 «* TANKS
     SERVICE
      THICKENER  OVERFLOW

  *» PUMPS
      SERVICE
      NR
  ** SOLIDS CONCENTRATING/DEWATERING
      DEVICE

 *** SLUDGE

  ** TREATMENT
      METHOD
      DEVICE
      PROPRIETARY PROCESS

  ** DISPOSAL
      NATUSE
      TYPE
      SITE TREATMENT

  ** WATER BALANCE
      WATER LOOP TYPE
      EVAPORATION WATER LOSS - LITER/S
FORCED DRAFT
DRY
CARBON STEEL
NR
NR
NR
NR
NR
NR
NR
OUTLET
CARBON STEEL
AISI 1110
NONE
N/A
WET BALL MILL
NR
NR
NUMBER

    1


NUMBER

***«


THICKENER
 BLEED
 N/A
 N/A
 FINAL
 POND
 NONE
 CLOSED
     5.5
(    88 GPM)
                                              F-67

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - V.
     RANGE ASH CONTENT - V.
     AVERAGE MOISTURE CONTENT - '/.
     RANGE MOISTURE CONTENT - V.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - V.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** FABRIC FILTER
     NUMBER
     TYPE

 ** ESP
     NUMBER
     SUPPLIER
     PARTICLE REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     NUttSER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE

*#» FGD SYSTEM
               (  .064 LB/MMBTU)
               (  .150 LB/MMBTU)
               (****** LB/MMBTU)
SOUTHERN CALIFORNIA EDISON
MOHAVE
1A
LAUGHLIN
NEVADA
D
   28.
   64.
******
 1560
  790
  790
  790
  170
COMBUSTION ENGINEERING
PULVERIZED COAL
BASE
********       (******* ACFM)
  132.2        (  270 F)
  152.         (  500 FT)
NR
*******        (***** FT)
COAL
******
26749.

   10.00
******
********
******
     .40
******
********
******
 0
NONE
 0
NONE
RESEARCH-COTTRELL
   97.2
 0
NONE
N/A
N/A
N/A
N/A
N/A
N/A
N/A
               (  11500 BTU/LB)
                11000-12000
                                             F-68

-------
                                                  UTILITY F6D SURVEY:  OCTOBER  1983  -  SEPTEMBER
SOUTHERN CALIFORNIA EDISON: MOHAVE 1A (CONT.)
 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY
     ENERGY CONSUMPTION - X
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP

 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     L/G RATIO - L/CU.M
     SUPERFICAL GAS VELOCITY  - M/SEC
     INLET GAS FLOU - CU. M/S
     S02 REMOVAL EFFICIENCY - X
     PARTICLE REMOVAL EFFICENCY - X

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     WASH FREQUENCY

 ** REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     TEMPERATURE INCREASE - C
     INLET FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     NUMBER
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE
 THROWAMAY PRODUCT
 WET SCRUBBING
 LIMESTONE
 AIR CORRECTION DIVISION,  UOP
 PROTOTYPE
 RETROFIT
X   97.20
      .0
  8
  7/75
  1/74
  1/74
 NR
 NR
 PACKED TOWER
 MOBILE BED PACKING
 TURBULENT CONTACT ABSORBER
 AIR CORRECTION DIVISION,  UOP
 18.0 X 40.0 X 90.0
 CARBON STEEL
 AISI 1110
 N/A
 ORGANIC
 NATURAL RUBBER
 BLACK NATURAL RUBBER
 PLASTIC/RUBBER MOBILE BALLS
  4
    11.1        (  83.0 GAL/1000 ACF)
     3.8        (  12.6 FT/S)
   212.35       (  450000 ACFM)
    95.0
    93.0
 PRIMARY COLLECTOR
 NR
 NR
 NR
 NR
 NR
 CONTINUOUS
  1
 IN-LINE
 STEAM
 NR
    30.6        (   55 F)
    51.7        (  125 F)
 NR
 NR
 CENTRIFUGAL
 BOOSTER
 NR
 NR
 NR
                                              F-69

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

SOUTHERN CALIFORNIA EDISON: MOHAVE 1A (CONT.)
 «* DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE
     NUMBER

 ** PUMPS
     SERVICE
     NR
 «* SOLIDS CONCENTRATING/DEWATERING
     DEVICE

 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE

 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE

**# SLUDGE

 ** TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 «* DISPOSAL
     NATURE
     TYPE
     LOCATION
     SITE TRANSPORTATION METHOD
     SITE TREATMENT
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
WET BALL MILL
COMPARTMENTED
NR
 1
NUMBER

****


CENTRIFUGE


THICKENER


VACUUM FILTER
FIXATION
PUG MILL
CONVERSION SYSTEMS
FINAL
POND
ON-SITE
TRUCK
NR
                   IPOZ-O-TEC]
                                             F-70

-------
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 - SEPTEMBER  1984
                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MM
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 »» FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RAN3E HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RAN3E CHLORIDE CONTENT - 7.

*«* PARTICLE CONTROL

 «* MECHANICAL COLLECTOR
     NUMBER
     TYPE

 ** FABRIC FILTER
     NUMBER
     TYPE

 ** ESP
     NUMBER
     SUPPLIER
     PARTICLE REMOVAL EFFICENCY -  7.

 ** PARTICLE SCRUBBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE

**» FGD SYSTEM
               (   .064 LB/MMBTU)
               (   .150 LB/MMBTU)
               (****** LB/MMBTU)
SOUTHERN CALIFORNIA EDISON
MOHAVE
2A
LAUGHLIN
NEVADA
D
   28.
   64.
******
 1560
  790
  790
  790
  160
COMBUSTION ENGINEERING
PULVERIZED COAL
BASE
********       (******* ACFM)
  132.2        (  270 F)
  152.         (  500 FT)
NR
*******        (**»** FT)
COAL
******
26749.

   10.00
******
********
******
      .40
******
********
******
 0
NONE
 0
NONE
RESEARCH-COTTRELL
   97.2
 0
NONE
N/A
N/A
N/A
N/A
N/A
N/A
N/A
               ( 11500 BTU/LB)
                11000-12000
                                              F-71

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

SOUTHERN CALIFORNIA EDISON: MOHAVE 2A (CONT.)
 «* GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY
     ENERGY CONSUMPTION - 7.
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP

 ** DESIGN AND OPERATING PARAMETERS

 #* QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     L/G RATIO - L/CU.M
     SUPERFICAL GAS VELOCITY - M/SEC
     INLET GAS FLOW - CU. M/S
     SOS REMOVAL EFFICIENCY - 7.
     PARTICLE REMOVAL EFFICENCY - X

 *« MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONFIGURATION
     NUMBER OF STAGES
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     TEMPERATURE INCREASE - C
     INLET FLUE GAS TEMPERATURE - C
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     NUMBER
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE
 THROWAWAY PRODUCT
 WET SCRUBBING
 LIME
 SO. CALIFORNIA EDISON/STEARNS-
 STEARNS-ROGER
 PROTOTYPE
 RETROFIT
X   97.20
      .0
  8
  2/75
 11/73
 11/73
 NR
 NR
 SPRAY TOWER
 OPEN CROSSCURRENT SPRAY
 HORIZONTAL SPRAY CHAMBER
 SO. CALIFORNIA EDISON/STEARNS-ROGER
 15.0 X 30.0 X 60.0
 CARBON STEEL
 AISI 1110
 N/A
 NR
 NR
 NR
 NONE
  4
     4.0        (
     6.6        (
   212.35       (
    95.0
    93.0
30.0 GAL/1000 ACF)
21.6 FT/S)
450000 ACFM)
 PRIMARY COLLECTOR
 NR
 NR
 NR
 VERTICAL
     1
 NR
 NR
 INDIRECT HOT AIR
 EXTERNAL HEAT EXCHANGER
 STEAM TUBE BUNDLE
    30.6        (   55 F)
    48.9        (  120 F)
 NR
 NR
 CENTRIFUGAL
 BOOSTER
 NR
 NR
 NR
                                             F-72

-------
SOUTHERN CALIFORNIA EDISON: MOHAVE 2A (CONT.)
                                                  UTILITY F6D SURVEY:  OCTOBER  1983  -  SEPTEMBER  1984
 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

  #*  PUMPS
     SERVICE
      NR
  ** SOLIDS CONCENTRATING/DEWATERING
      DEVICE

 *** SLUDGE

  ** TREATMENT
      METHOD
      DEVICE
      PROPRIETARY PROCESS

  »* DISPOSAL
      NATURE
      TYPE
      SITE TREATMENT

  *» WATER BALANCE
      WATER LOOP TYPE
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
SLAKER
NR
NR
NUMBER
 NR
 FIXATION
 MIX TANK
 DRAVO CCALCILOX1
 FINAL
 POND
 CLAY LINING
 CLOSED
                                               F-73

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER
                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY M/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RAN3E ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANSE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 *» ESP
     NUMBER
     TYPE
     INLET FLUE GAS TEMPERATURE - C
     PARTICLE REMOVAL EFFICENCY - 7.

 ** PARTICLE SCRUBBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE

»** FGD SYSTEM

 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     S02 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY
 ST.  JOE ZINC
 G.F. WEATON
 1
 MONACA
 PENNSYLVANIA
 D
    43.
   516.
 ******
   120
    60
 *****
 *****
    60
 COMBUSTION ENGINEERING
 PULVERIZED COAL
 ******
    75.03       (
   148.9        (
    23.         (
 FIBERGLASS
     3.2
    (   .100 LB/MMBTU)
    (  1.200 LB/MMBTU)
    (****** LB/MMBTU)
      159000 ACFM)
      300 F)
       75 FT)
    (  10.5 FT)
 COAL
 BITUMINOUS
 29075.

    11.50
 ******
 ********
 ******
     2.00
 2.0-4.5
      .20
 ******
 COLD SIDE
   148.9
    99.6
  0
 NONE
 N/A
 N/A
 N/A
 N/A
 N/A
 N/A
 N/A
 SALEABLE PRODUCT
 KET SCRUBBING
 CITRATE
 MORRISON ft
 MORRISON &
 PROTOTYPE
 RETROFIT
7.   99.60
    (  12500 BTU/LB)
     ******
    (   300 F)
KNUDSEN/U.S.B.M.
KNUDSEN
                                             F-74

-------
                                                  UTILITY FGD SURVEY:  OCTOBER  1983 - SEPTEMBER 196*
ST. JOE ZINC: 6.F. MEATON 1 (CONT.)

     UNIT DESIGN S02 REMOVAL EFFICIENCY - X
     CURRENT STATUS
     TERMINATION
     COMMERCIAL START-UP
     INITIAL START-UP
     CONTRACT AWARDED

 ** DESIGN AND OPERATING PARAMETERS

 *» QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     DIMENSIONS - FT
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER OF CONTACTING ZONES
     LIQUID RECIRCULATION RATE - LITER/S
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C
     S02 REMOVAL EFFICIENCY - X

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     NUMBER PER SYSTEM
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** REHEATER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 *» FANS
     NUMBER
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE
   90.00
 8
 9/82
 1/80
11/79
 0/77
NR
NR
PACKED TOWER
FIXED BED PACKING
N/A
26.0 DIA X 85.0
CARBON STEEL
AISI 1110
N/A
ORGANIC
VINLY ESTER
NR
INTALOX SADDLE
 1
  283.
   73.62
   48.9
   90.0
(  4500 GPM)
(  156000 ACFM)
(   120 F)
PRIMARY COLLECTOR
 2
IMPINGEMENT
BAFFLE
CLOSED VANE
ORGANIC
POLYVINYL CHLORIDE
INDIRECT HOT AIR
EXTERNAL HEAT EXCHANGER
STEAM TUBE BUNDLE
NR
NR
CENTRIFUGAL
BOOSTER
FORCED DRAFT
DRY
CARBON STEEL
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
                                             F-75

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 198*

ST. JOE ZINC: G.F. WEATON 1 (CONT.)
 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

 ** TANKS
     SERVICE
     SALEABLE BYPRODUCT
     REAGENT PREP PRODUCT
     MAKEUP WATER

 ** PUMPS
     SERVICE
     SULFUR SLURRY
     LEAN SOLUTION
     ******
     SULFUR TRANSFER
     SCRUBBER RECIRCULATION
     SULFUR LOADINS
     RICH CITRATE SOLUTION

 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE

*** SALEABLE BYPRODUCTS
     NATURE
     QUALITY - X

«** SLUDGE

 «* TREATMENT
     METHOD
     DEVICE
     PROPRIETARY PROCESS

 ** DISPOSAL
     NATURE
     TYPE
     SITE TREATMENT

 ** WATER BALANCE
     WATER LOOP TYPE

 ** FGD  SPARE CAPACITY INDICES
     ABSORBER - X

 ** FGD  SPARE COMPONENT INDICES
     ABSORBER
MIX TANK
N/A
AGITATED TANK
                                                NUMBER
NUMBER

   2
   Z
   I
   I
   4
   1
   2
NONE
ELEMENTAL SULFUR
   99.5
N/A
N/A.
N/A
N/A
NONE
N/A
CLOSED


     .0


     .0
                                              F-76

-------
                                                  UTILITY F6D SURVEY:  OCTOBER  1983  -  SEPTEMBER 1984
                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RAN3E SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** PARTICLE SCRUBBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE

*** FGD SYSTEM
                  .100  LB/MMBTU)
                 1.200  LB/MMBTU)
               (****** LB/MMBTU)
TENNESSEE VALLEY AUTHORITY
SHAWNEE
10A
PADUCAH
KENTUCKY
E
   43.
  516.
******
 1750
   10
   10
*****
   10
******
******
******
********
*******
******
NR
*******
               (******* ACFM)
               (**** F)
               (**** FT)

               (***** FT)
               (****** BTU/LB)
                ******
COAL
BITUMINOUS
******

********
******
********
******
    2.90
******
********
******
PACKED TOWER
MOBILE BED PACKING
TURBULENT CONTACT ABSORBER
NR
NR
NR
NR
PLASTIC SPHERES
  ** GENERAL DATA
     SALEABLE  PRODUCT/THROWAWAY  PRODUCT
     S02 REMOVAL  MODE
     PROCESS TYPE
     PROCESS ADDITIVES
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT  LEVEL
     NEW/RETROFIT
     UNIT DESIGN  S02 REMOVAL  EFFICIENCY  -  7.
     CURRENT STATUS
     TERMINATION
     INITIAL START-UP
THROWAWAY PRODUCT
WET SCRUBBING
LIME/LIMESTONE
VARIABLE - TEST FACILITY
AIR CORRECTION DIVISION, UOP
BECHTEL
PROTOTYPE
RETROFIT
   90.00
 8
 7/82
 4/72
                                              F-77

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

TENNESSEE VALLEY AUTHORITY: SHAWNEE 10A (CONT.)
 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     NUMBER Of CONTACTING ZONES
     DISTANCE BETWEEN GAS CONTACTING ZONES
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     NUMBER PER SYSTEM
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     WASH WATER SOURCE
     WASH FREQUENCY

 ** REHEATER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
       SHELL GENERIC MATERIAL TYPE
       SHELL SPECIFIC MATERIAL TYPE
       LINER GENERIC MATERIAL TYPE
       LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION  EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE
     MR
     NR
     PACKED TOWER
     MOBILE BED PACKING
     TURBULENT CONTACT ABSORBER
     AIR CORRECTION DIVISION, UOP
     NR
     NR
     NR
     NR
     NR
     NR
     PLASTIC/RUBBER MOBILE BALLS
      3
- CM    12.7        (     5.0IN)
        16.52       (   35000 ACFM)
       148.9        (   300 F)
     PRIMARY COLLECTOR
      1
     IMPINGEMENT
     BAFFLE
     CLOSED VANE
     NR
     NR
     SUPERNATANT .
     INTERMITTENT
     DIRECT COMBUSTION
     NR
     OIL
     NR
     NR
     CENTRIFUGAL
     BOOSTER
     INDUCED DRAFT
     DRY
     CARBON STEEL
     NR
     NR
     NR
     NR
     NR
     NR
     NR
     NR
     NR
     NR
     NR
     NR
     NR
     NR
                                              F-78

-------
                                                  UTILITY FGD SURVEY:  OCTOBER  1983 -  SEPTEMBER
TENNESSEE VALLEY AUTHORITY: SHAWNEE IDA (CONT.)
 ** TANKS
     SERVICE
     ABSORBER RECYCLE

 »« PUMPS
     SERVICE
     NR
 *» SOLIDS CONCENTRATING/DEWATERING
     DEVICE
     NUMBER

 ** SOLIDS CONCENTRATING/OEWATERING
     DEVICE
     NUMBER

*** SLUDGE

 *» TREATMENT
     METHOD
     DEVICE
     PROPRIETARY  PROCESS

 ** DISPOSAL
     NATURE
     TYPE
     SITE TREATMENT

 ** MATER BALANCE
     WATER LOOP TYPE

 tut FGD  SPARE  CAPACITY INDICES
     ABSORBER  - X

 ** FGD  SPARE  COMPONENT INDICES
     ABSORBER
NUMBER

****


NUMBER

«**«
CENTRIFUGE
 1
THICKENER
 1
DEWATERED
N/A
N/A
FINAL
LANDFILL
NONE
CLOSED
      .0
      .0
                                              F-79

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 1984

                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MM
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - '/.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - V.
     RANGE MOISTURE CONTENT - '/.
     AVERAGE SULFUR CONTENT - V.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - V.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** PARTICLE SCRUBBER
     NUM3ER
     INITIAL START-UP DATE
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE
     INLET GAS FLON RATE - CU.M/S
     INLET GAS TEMPERATURE - C

*** FGD SYSTEM

 ** GENERAL DATA
     SALEABLE PRODUCT/THROWAWAY PRODUCT
     SOS REMOVAL MODE
     PROCESS TYPE
     PROCESS ADDITIVES
     SYSTEM SUPPLIER
     A-E FIRM
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN S02 REMOVAL EFFICIENCY - 7.
     CURRENT STATUS
                  .100 LB/MMBTU)
                 1.200 LB/MMBTU)
               (****** LB/MMBTU)
TENNESSEE VALLEY AUTHORITY
SHAWNEE
10B
PADUCAH
KENTUCKY
E
   43.
  516.
******
 1750
   10
   10
*****
   10
******
******
******
********
*******
******
NR
*******
               (******* ACFM)
               (**** F)
               (**** FT)

               (***** FT)
               (****** BTU/LB)
                ******
COAL
BITUMINOUS
******

********
******
********
******
    2.90
******
********
******
 1
 4/72
VENTURI TOWER
VARIABLE-THROAT/TOP-ENTRY PLUMB BOB
N/A
GE ENVIRONMENTAL SERVICES
NR
NR
NR
NR
NONE
    1.7        (   3500 ACFM)
  148.9        (  300 F)
THROWAWAY PRODUCT
WET SCRUBBING
LIME/LIMESTONE
VARIABLE - TEST FACILITY
GE ENVIRONMENTAL SERVICES
BECHTEL
PROTOTYPE
RETROFIT
   90.00
 8
                                             F-80

-------
                                                  UTILITY F6D SURVEY:  OCTOBER  1983 - SEPTEMBER 1984
TENNESSEE VALLEY AUTHORITY: SHAWNEE 10B (CONT.)

     TERMINATION
     INITIAL START-UP

 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     NUMBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SUPPLIER
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     INLET GAS FLOW - CU. M/S
     INLET GAS TEMPERATURE - C

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     NUMBER PER SYSTEM
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** REHEATER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 »* DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
       SHELL GENERIC MATERIAL TYPE
       SHELL SPECIFIC MATERIAL TYPE
       LINER GENERIC MATERIAL TYPE
       LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION  EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE
 7/82
 4/7E
NR
NR
SPRAY TOWER
OPEN COUNTERCURRENT SPRAY
N/A
GE ENVIRONMENTAL SERVICES
NR
NR
NR
NR
NR
NR
NONE
   16.52
  148.9
(   35000 ACFM)
(   300 F)
PRIMARY COLLECTOR
 1
IMPINGEMENT
BAFFLE
CLOSED VANE
NR
NR
DIRECT COMBUSTION
NR
OIL
NR
NR
CENTRIFUGAL
BOOSTER
INDUCED DRAFT
DRY
CARBON STEEL
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
 NR
 NR
 NR
                                              F-81

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 198*

TENNESSEE VALLEY AUTHORITY: SHAWNEE 10B (CONT.)
 ** TANKS
     SERVICE                                    NUMBER
     ABSORBER RECYCLE                           ****
     SPARGER/OXIDIZER                           ****
     NR                                         ****

 ** PUMPS
     SERVICE                                    NUMBER
     NR                                         #***

 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE                                     NR

*** SLUDGE

 #* TREATMENT
     METHOD                                     DEWATERED
     DEVICE                                     N/A
     PROPRIETARY PROCESS                        N/A

 ** DISPOSAL
     NATURE                                     FINAL
     TYPE                                       LANDFILL
     SITE TREATMENT                             NONE

 ** WATER BALANCE
     WATER LOOP TYPE                            CLOSED

 ** FGD SPARE CAPACITY INDICES
     ABSORBER -7.                                    .0

 »* FGD SPARE COMPONENT INDICES
     ABSORBER                                        .0
                                             F-82

-------
                                                  UTILITY FGD SURVEY:  OCTOBER  1983 -  SEPTEMBER  1984
                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MM
NET UNIT GENERATING CAPACITY M/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANSE ASH CONTENT - '/.
     AVERAGE MOISTURE CONTENT - 7.
     RANSE MOISTURE CONTENT - 7.
     AVERAGE SULFUR CONTENT - 7.
     RAK3E SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

 *** PARTICLE CONTROL

 ** PARTICLE SCRUBBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
      LINER GENERIC MATERIAL
      LINER SPECIFIC MATERIAL
     GAS  CONTACTING DEVICE TYPE

 ***  FGD SYSTEM

 **  GENERAL  DATA
     SALEABLE PRODUCT/THROWAWAY  PRODUCT
     SOZ  REMOVAL  MODE
     PROCESS TYPE
     SYSTEM  SUPPLIER
     A-E  FIRM
     DEVELOPMENT  LEVEL
     NEW/RETROFIT
     CURRENT STATUS
     TERMINATION
      INITIAL START-UP

 ** DESIGN AND  OPERATING  PARAMETERS
TENNESSEE VALLEY AUTHORITY
SHAKNEE
IOC
PADUCAH
KENTUCKY
D
   43.         (  .100 LB/MMBTU)
  516.         ( 1.200 LB/MMBTU)
******         <****«* LB/MMBTU)
 1750
   10
*****
*****
   10
BABCOCK & WILCOX
PULVERIZED COAL
BASE
               (******* ACFM)
               (**** F)
               (  800 FT)

               (***** FT)
               (****** BTU/LB)
                ******
********
*******
  244.
NR
*******
COAL
BITUMINOUS
******

********
******
********
******
    2.90
******
********
******
 PACKED TOWER
 MOBILE BED PACKING
 TURBULENT CONTACT ABSORBER
 NR
 NR
 NR
 NR
 PLASTIC  SPHERES
 THROWAWAY  PRODUCT
 WET  SCRUBBING
 LIME/LIMESTONE
 COMBUSTION ENGINEERING
 BECHTEL
 PROTOTYPE
 RETROFIT
  8
  7/73
  4/72
                                              F-63

-------
UTILITY F6D SURVEY: OCTOBER 1983 - SEPTEMBER 1984

TENNESSEE VALLEY AUTHORITY: SHAKNEE IOC (COMT.)
 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE
     GAS CONTACTING DEVICE TYPE
     INLET GAS FLOW - CU. M/S

 ** MIST ELIMINATOR
     PRE-MIST ELIMINATOR/MIST ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** REHEATER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 #* DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE
     LINER GENERIC MATERIAL TYPE
     LINER SPECIFIC MATERIAL TYPE

 ** DUCTWORK
      SHELL GENERIC MATERIAL TYPE
      SHELL SPECIFIC MATERIAL TYPE
      LINER GENERIC MATERIAL TYPE
      LINER SPECIFIC MATERIAL TYPE

 ** REAGENT PREPARATION EQUIPMENT
     FUNCTION
     DEVICE
     DEVICE TYPE

 ** PUMPS
     SERVICE
     NR
NR
NR
PACKED TOWER
STATIC BED PACKING
MARBLE-BED SCRUBBER
NR
NR
NR
NR
NR
NR
GLASS MARBLES
   14.16       (  30000 ACFM)
NR
NR
NR
NR
NR
NR
DIRECT COMBUSTION
NR
OIL
NR
NR
CENTRIFUGAL
BOOSTER
INDUCED DRAFT
DRY
CARBON STEEL
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
                                                NUMBER

                                                *«**
 ** SOLIDS CONCENTRATING/DEWATERING
     DEVICE
                                                VACUUM FILTER
*** SLUDGE

-------
                                                  UTILITY FGD  SURVEY: OCTOBER 1983 - SEPTEMBER 1984

TENNESSEE VALLEY AUTHORITY: SHAWNEE IOC (CONT.)
 ** TREATMENT
     METHOD                                     DEWATERED
     DEVICE                                     N/A
     PROPRIETARY PROCESS                        N/A

 *» DISPOSAL
     NATURE                                     FINAL
     TYPE                                       LANDFILL
     SITE TREATMENT                             NONE
                                                F-85

-------
UTILITY FGO SURVEY: OCTOBER 1983 - SEPTEMBER 1984

                                           APPENDIX F
               DESIGN AND PERFORMANCE DATA FOR DISCONTINUED DOMESTIC FGD SYSTEMS
COMPANY NAME
PLANT NAME
UNIT NUMBER
CITY
STATE
REGULATORY CLASSIFICATION
PARTICULATE EMISSION LIMITATION - NG/J
S02 EMISSION LIMITATION - NG/J
NOX EMISSION LIMITATION - NG/J
NET PLANT GENERATING CAPACITY - MW
GROSS UNIT GENERATING CAPACITY - MW
NET UNIT GENERATING CAPACITY W/FGD - MW
NET UNIT GENERATING CAPACITY WO/FGD - MW
EQUIVALENT SCRUBBED CAPACITY - MW

 ** UNIT DATA - BOILER AND STACK
     BOILER SUPPLIER
     BOILER TYPE
     BOILER SERVICE LOAD
     DESIGN BOILER FLUE GAS FLOW - CU.M/S
     BOILER FLUE GAS TEMPERATURE - C
     STACK HEIGHT - M
     STACK SHELL
     STACK TOP DIAMETER - M

 ** FUEL DATA
     FUEL TYPE
     FUEL GRADE
     AVERAGE HEAT CONTENT - J/G
     RANGE HEAT CONTENT - BTU/LB
     AVERAGE ASH CONTENT - 7.
     RANGE ASH CONTENT - 7.
     AVERAGE MOISTURE CONTENT - 7.
     RANGE MOISTURE CONTENT - V.
     AVERAGE "SULFUR CONTENT - 7.
     RANGE SULFUR CONTENT - 7.
     AVERAGE CHLORIDE CONTENT - 7.
     RANGE CHLORIDE CONTENT - 7.

*** PARTICLE CONTROL

 ** PARTICLE SCRUBBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON NAME
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     GAS CONTACTING DEVICE TYPE

*** FGD SYSTEM

 ** GENERAL DATA
     SALEABLE PROOUCT/THROWAWAY PRODUCT
     502 REMOVAL MODE
     PROCESS TYPE
     SYSTEM SUPPLIER
     DEVELOPMENT LEVEL
     NEW/RETROFIT
     UNIT DESIGN PARTICLE REMOVAL EFFICIENCY
     UNIT DESIGN S02 REMOVAL EFFICIENCY - 7.
     CURRENT STATUS
     TERMINATION
     INITIAL START-UP
     CONTRACT AWARDED
 UNION ELECTRIC
 MEREMAC
 2
 N/A
 MISSOURI
 ******
 ******
 ******
 ******
  4135
   140
   125
   ***
   140
               (****** LB/MMBTU)
               (****** LB/MMBTU)
               (****** LB/MMBTU)
******
PULVERIZED
BASE
********
*******
******
NR
*******

COAL

(******* ACFM)
(**** F)
(**** FT)

(***** FT)
                (****** BTU/LB)
                 ******
COAL
******
******

********
******
********
******
    3.40
******
********
******
 PACKED TOWER
 STATIC BED PACKING
 MARBLE-BED SCRUBBER
 NR
 NR
 NR
 NR
 PLASTIC SPHERES
 THROWAWAY PRODUCT
 WET SCRUBBING
 LIMESTONE
 COMBUSTION ENGINEERING
 FULL SCALE
 RETROFIT
7.   99.00
    83.00
  8
  0/69
  3/68
  0/67
                                             F-86

-------
UNION ELECTRIC: MEREMAC 2 CCONT.)
                                                  UTILITY FGD SURVEY:  OCTOBER 1983 -  SEPTEMBER  1984
 ** DESIGN AND OPERATING PARAMETERS

 ** QUENCHER/PRESATURATOR
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** ABSORBER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     SHELL GENERIC MATERIAL
     SHELL SPECIFIC MATERIAL
     SHELL MATERIAL TRADE NAME/COMMON TYPE
     LINER GENERIC MATERIAL
     LINER SPECIFIC MATERIAL
     LINER MATERIAL TRADE NAME/COMMON TYPE

 ** MIST  ELIMINATOR
     PRE-MIST ELIMINATOR/MIST  ELIMINATOR
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** REHEATER
     GENERIC TYPE
     SPECIFIC TYPE
     TRADE NAME/COMMON TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC TYPE

 ** FANS
     DESIGN
     FUNCTION
     APPLICATION
     SERVICE
     CONSTRUCTION MATERIAL GENERIC TYPE

 ** DAMPERS
     FUNCTION
     GENERIC TYPE
     SPECIFIC  TYPE
     CONSTRUCTION MATERIAL GENERIC TYPE
     CONSTRUCTION MATERIAL SPECIFIC  TYPE
      LINER  GENERIC  MATERIAL  TYPE
      LINER  SPECIFIC MATERIAL TYPE

  »*  DUCTWORK
       SHELL GENERIC MATERIAL TYPE
       SHELL SPECIFIC MATERIAL TYPE
       LINER  GENERIC MATERIAL TYPE
       LINER  SPECIFIC MATERIAL TYPE

  **  REAGENT  PREPARATION EQUIPMENT
      FUNCTION
     DEVICE
      DEVICE  TYPE

  **  PUMPS
      SERVICE
      NR
  ** SOLIDS CONCENTRATING/DEWATERING
      DEVICE

 *** SLUDGE
NR
NR
PACKED TOWER
STATIC BED PACKING
MARBLE-BED SCRUBBER
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 NR
 WET BALL  MILL
 NR
 NR
 NUMBER

 *#**


 NR
                                              F-87

-------
UTILITY FGD SURVEY: OCTOBER 1983 - SEPTEMBER 198*
UNION ELECTRIC: MEREMAC 2 CCONT.)
 ** TREATMENT
     METHOD                                     NR
     DEVICE                                     NR
     PROPRIETARY PROCESS                        NR

 ** DISPOSAL
     NATURE                                     FINAL
     TYPE                                       NR
     SITE TREATMENT                             NR

 ** WATER BALANCE
     WATER LOOP TYPE                            CLOSED
                                             F-88

-------
TECHNICAL REPORT DATA
(Please read Instructions on the reverse before completing)
1.
4.
7.
9.
REPORT NO.
EPA 340/1-85-01%
TITLE AND SUBTITLE
Utility FGD Survey
October 1983 - September
Volume 1
2.
1984
AUTHOR(S)
M.T. Melia, R.S. McKibben, B.W. Pelsor
PERFORMING ORGANIZATION NAME At«
PEDCo Environmental, Inc.
11499 Chester Road
Cincinnati, OH 45246-010
12. SPONSORING AGENCY NAME AND ADC
U.S. Environmental Protec
Stationary Source Complia
401 M Street, S.W.
Washington, B.C. 20460
JO ADDRESS
0
1RESS
tion Agency
ince Division (EN-341)
3. RECIPIENT'S ACCESSION NO.
5. REPORT DATE
October 1984
6. PERFORMING ORGANIZATION CODE
8. PERFORMING ORGANIZATION REPORT NO.
10. PROGRAM ELEMENT NO.
11. CONTRACT/GRANT NO.
68-02-3963, Task No. 46
13. TYPE OF REPORT AND PERIOD COVERED
Final, Oct. 1983-Sept. 1984
14. SPONSORING AGENCY CODE
15. SUPPLEMENTARY NOTES
Sunmarized in EPA 340/1-85-014 - Utility FGD Survey Sunnary
EPA Task Manager - Sonva Stelmack (202) 382-2851
16. ABSTRACT
This report, which is generated by a computerized data base system,
represents a survey of operational and planned domestic utility flue gas
desulfurization (FGD) system. The three volume set summarizes information
contributed by the utility industry, system and equipment suppliers, system
designers, research organizations, and regulatory agencies. The data cover system
design, fuel characteristics, operating history, and actual system performance.
Also included is a unit-by-unit discussion of problems and solutions associated
with the boilers, scrubbers, and FGD systems.
The development status (operational, under construction, or in the planning
stages) , system supplier, process, waste disposal practice, and regulatory class
are tabulated alphabetically by utility company. Simplified process flow diagrams
of FGD systems, definitions, and a glossary of terms are attached to the report.
Current data for domestic FGD systems show 124 systems in operation, 25 systems
under construction, and 68 systems planned. The current FGD-con trolled capacity
in the United States is 47,255 W.
17
a.

DESCRIPTORS
KEY WORDS AND DOCUMENT ANALYSIS
b.lDENTIFIERS/OPEN ENDED TERMS

18
. DISTRIBUTION STATEMENT
Release unlimited
19. SECURITY CLASS (This Report)
unclassified
20. SECURITY CLASS (This page)
unclassified

c. COSATI Field/Group

21. NO. OF PAGES
22. PRICE
EPA Form 2220-1 (Rev. 4-77)    PREVIOUS EDITION is OBSOLETE

-------