EPA-450/3-76-013
March 1974

                                   COST
                 OF RETROFITTING
                          COKE OVEN
       PARTICULATE  CONTROLS
    U.S. ENVIRONMENTAL PROTECTION AGENCY
         Office of Air and Waste Management
      Office of Air Quality Planning and Standards
     Research Triangle Park, North Carolina 27711

-------
                                    EPA-450/3-76-013
                 COST
      OF RETROFITTING
            COKE OVEN
PARTICIPATE  CONTROLS
                     by

               Vulcan-Cincinnati, Inc.
               1329 Arlington Street
               Cincinnati, Ohio 45225
               Contract No. 68-02-0299
          EPA Project Officer: Justice Manning
                  Prepared for

       ENVIRONMENTAL PROTECTION AGENCY
          Office of Air and Waste Management
       Office of Air Onality Planning and Standards
       Research Triangle Park. North Carolina 27711

                   March 1974

-------
This report is issued by the Environmental Protection Agency to report
technical data of interest to a limited number of readers.  Copies are
available free of charge to Federal employees,  current contractors and
grantees, and nonprofit organizations - as supplies permit - from the
Air Pollution Technical Information Center, Environmental Protection
Agency,  Research Triangle Park, North Carolina 27711; or, for a fee,
from the National Technical Information Service, 5285 Port Royal Road,
Springfield, Virginia 22161.
This report was furnished to the Environmental Protection Agency by
Vulcan-Cincinnati, Inc. , Cincinnati, Ohio 45225, in fulfillment of
Contract No. 68-02-0299.  The contents of this report are reproduced
herein as received from Vulcan-Cincinnati, Inc. The opinions, findings,
and conclusions expressed are those of the author and not necessarily
those of the Environmental Protection Agency. Mention of company or
product names is not to be considered as  an endorsement by the Environmen-
tal Protection Agency.
                Publication No. EPA-450/3-76-013
                                    11

-------
                      TABLE OF CONTENTS
Section

  I       INTRODUCTION

  II      ESTIMATE BASIS

  III     DESCRIPTION - CONTROL SYSTEMS
          a)  Pipeline Charging
          b)  Halcon - Pushing Control System
          c)  Great Lakes Steel - Pushing Control System
          d)  Double Main

  IV      ESTIMATES AND ECONOMIC EVALUATION
          a)  Pipeline Charging - Total Installed Cost
          b)  Pipeline Charging - Operating Costs and Revenues
          c)  Pipeline Charging - Economic Evaluation
          d)  Halcon System - Total Installed Cost
          e)  Halcon System - Operating Costs
          f)  Halcon System - Economic Evaluation
          g)  Great Lakes Pushing Control System - Total Installed
                                                   Cost
          h)  Great Lakes Pushing Control System - Operating Costs
          i)  Great Lakes Pushing Control System - Economic Eval-
                                                   uation
          j)  Double Main - Total Installed Cost
          k)  Double Main - Operating Costs
          1)  Double Main - Economic Evaluation

  V       EFFECTIVENESS OF RETROFITTING COKE OVENS
          a)  General
          b)  Pipeline Charging
          c)  Halcon System
          d)  Great Lakes Steel System
          e)  Double Collecting Main

  VI      COST UPDATING

  VII     STATE AND LOCAL REGULATIONS RESULTING IN COKE OVEN
          CONTROLS

                             ill

-------
INTRODUCTION

        The intent, of this study is three fold:

    1.  Estimate the total investment required to retrofit
        pollution control devices to existing coke ovens.

    2.  Estimate the operating costs of these devices and
        evaluate the effects of these costs on the return
        on the investment.

    3.  Review the problems related to retrofitting pollution
        control equipment and the relative effectiveness of
        each control device.
                       - 1 -

-------
II   ESTIMATE BASIS

             In order to establish a basis for estimating the

     cost of coke oven pollution control equipment it was

     necessary to assume the capacity and number of ovens in

     the battery considered.

             The following was considered to be a typical

     battery for purposes of this report.

         1.  80 ovens - producing furnace coke.

         2.  Capacity of each oven is 16 tons blended coal.

         3.  Capacity of each oven is 12 tons coke.

         4,  Capacity of each oven is 10.1 tons furnace coke.

         5.  With larry car charging - 16 hours gross coking
             time.

         6.  With pipeline charging - 11 hours.

                                     Larry Car      Pipeline
                                     Charging       Charging

     Gross Coking Time - Hrs.              16            11

     Daily Coal Req. -Tons             1,920         2,770

     Annual Coal Req. - Tons
        (.95 x 365 days)              665,000       960,000
     I. 'Fuels and Combustion Handbook - A0J. Johnson, G.Ho Auth,
        McGraw Hill - 1951,  p. 144-145.
                             - 2 -

-------
                              Larry Car        Pipeline
                              Charging         Charging

Daily Coke Prod. - Tons          1,440           2,075

Annual Coke Prod. - Tons       500,000         720,000

Daily Furnace Coke - Tons        1,210           1,740

Annual Furnace Coke - Tons     420,000         605,000

Light Oil Prod. - M Gal./Yr.     2,128.0         3,072.0

Tar Prod. - M Gal./Yr.           5,685.7         8,208.0

Ammonium Sulphate - Tons/Yr.     6,996          10,099,,0

Coke Breeze and Pea Coke -
   Tons/Yr.                     80,000         115,000


        In order to make a realistic economic evaluation

of the capital costs of retrofitting coke ovens with the

"Pipeline Charging System" it was necessary that the total

coke production be divided into furnace coke and coke breeze -

pea coke.  The calculation of the annual return on invest-

ment is the total of the gross revenue  (revenue from sale

of furnace coke + revenue from sale of pea coke + coke breeze

and other by-products) less the operating costs (operating

cost + interest charges) plus the annual depreciation.  With-

out this differentiation the revenue from coke sales would

include the sales of coke breeze and pea coke at the same cost

per ton as furnace coke.  Realistically the price of coke breeze

and pea coke should compete with other fuels.  For purposes of


                         - 3 -

-------
this report its cost is $12oOO/ton<

-------
Ill  DESCRIPTION - CONTROL SYSTEMS




  A  Pipeline Charging




             Pipeline charging is a system of charging pre-




     heated coal to by-product coke ovens licensed by Coaltek




     Associates of Morristown, New Jersey.  The system consists




     of a preheating section and a pipeline system.




             The preheating system drys,  preheats, .stores and




     removes particulate matter from the flue gas vented to the




     air.




             Wet crushed coal is fed to the preheater where it




     is dried by hot flue gas and carried by the flue gas to a




     cyclone system to remove particulates„  The flue gas stream




     is then recycled to the preheater where its temperature




     is increased prior to contacting the wet coal.  A small




     stream of flue gas is vented to the air continuously.




     This vent to the air is water scrubbed and the water stream




     filtered and reused.  The coal fines recovered in the filter




     are returned to the preheater.




             The pipeline charge system conveys the coal from




     the charge bins to the individual ovens as required.  The




     preheated coal is conveyed in the pipeline by a system of
                            - 5 -

-------
jets supplied with superheated steam.

        It has been demonstrated that ovens utilizing

this process have reduced coking times and it is claimed

by the licensee ovens producing furnace coke could in-

crease production by as much as 50%.

        It has also been demonstrated that lower quality

coals may be satisfactorily utilized to produce furnace

cokec  A blend of 75% Illinois (Sesser)  and 25% Bishop

coal was successfully tested by Inland Steel.
   Pipeline charging preheated coal to coke ovens - Marting
   and Auvil - Rome, Italy - United Nations sympostum on
   "Developments in European and World Markets for Coking
   and Coke."

(3)preneating and Pipeline Charging of High Illinois -
   Coal Blends - Underwood and Knoerzer for By-Product Coking
   AISI - Regional Technical Meeting Nov. 9, 1972,,
                       - 6 -

-------
B    Halcon Pushing Pollution control System




             This system is licensed by the Interlake Steel




     Company and is supplied by the Aeronetics Corporation




     of Houston, Texaso




             This system utilizes an eductor to create a




     vacuum under a hood mounted on the coke guide and the




     hot car.  The motive force for the eductor is hot water.




     The water in turn is sprayed on to the coke as it is




     pushed into the hot car.  The vacuum from the eductor




     collects the vapors and particulates from the quenched




     coke, condenses the vapors and recirculates the water„




             A separate unit fitted with rail trucks con-




     tains the necessary pumps, eductor, valves, water heater




     and scrubber units0  This unit is attached to the hot




     car and is fully controlled by the hot car locomotive




     operator.  The hot car and coke guide are equipped with




     hoods which are connected to the eductor in the pump




     car.  Sprays are installed under the hoods to quench the




     coke.  The entire system travels back, and forth with the




     hot car locomotive.,
                            - 7 -

-------
Pushing Control System As Used On The Great Lakes Steel
Company Ovens

        The basic principle of this system is to collect

the emissions from the pushing operations into a moveable

hood over the coke quench car and gather it into a stationary

duct system which draws the gas into a Venturi Scrubbing

System, where it is cleaned and passed to the atmosphere.

        A stationary main collecting system is constructed

over the center line of the track for the full length of

the battery.  This main system is connected in parallel to

two Venturi Water Scrubbers.  Two large fans of about

75,000 cfm each draw the gases from the quench car into

the main and through the scrubbers before discharging it

to the air.  The water used in the scrubbers is recir-

culated to the quench sump.

        A moveable collecting hood, connected to the

coke guide on the battery side of the quench track, and

riding on a rail beam supported by bents on the other

side of the track, is located over the quench car and con-

nected to the stationary main with hydraulically operated

sleeves.  The dampers for that position are opened to the main

before pushing,,  The coke .guide is also covered with a hood

integral with that over the quench car.  Two cooling fans


                        - 8 -

-------
force air into the area immediately around the coke guide




and up into the main hood which is under a negative draft




from the large fans.




       . The collecting main is supported by the same struc-




ture upon which the moveable hood rides.




        The hood cotfer plate is stainless steel and fabricated




in easily removeable panels.  The collecting duct is made




from Cor-ten Steel.
                       - 9 -

-------
Double Main




        The double main is considered as a possible system




of pollution control of charging emissions.  A second main




collecting system is installed on the coke oven battery.




This permits the induction of charging emissions into two




collecting mains instead of one, therefore, in theory




doubling the gas handling capacity and reducing emissions.




In addition to the collecting main, new standpipes must be




installed as well as flushing liquor piping and pumps.
                       - 10 -

-------
IV    ESTIMATES AND ECONOMIC EVALUATION

 A    Pipeline Charging System

              This estimate includes the cost of all equipment

      and materials and the installation of a system to feed

      2,770 tons/day of coal to the battery.  It also includes

      the cost of installing the pipeline connection through

      the wall of the oven, (80 ovens)  the cost of installing

      a separate charging main, as well as the engineering

      construction coordination and the start-up costs of the

      owner.  The estimate does not include any allowance for

      increasing the by-product plant capacity.

              Equipment, Materials Direct Labor    $ 8,427,500
              Indirect Labor and Overhead            2,865,000
              Fee and Profit                         2,259,000

              Sub Total Preheat and
              Pipeline Charging                    $13,551,50.0

              Modify Ovens to Install
              Charging Connections                     250,000

              Fabricate and Install
              Charging Main                            374,000

              Sub Total                            $14,175,500

              Owners Coordination Cost                 105,000

              Start-Up Cost at 2.5% of
                 Pipeline Capital  $13,551,500         338,785

              TOTAL INSTALLED COST                 $14,619,285

                                           Say     $14,620,000

                                - 11 -

-------
B    Operating Costs and Revenues Incremental

             The operating costs and revenues for the "Pipeline

     Charging System" are based on the following:

         1.  Incremental Annual Operating Costs:

             a)  Additional Utilities  $0.38/Ton Coal $   364,800
             b)  Additional Operators at 72 MHR/Day       262,000
             c)  Maintenance Costs at 4% of Total
                    Installed Cost                        584,800

                 Sub; Total                            $ 1,211,600
             d)  Interest on T.I.C.  at 10%              .1,462,000

                 Sub Total       .                     $ 2,673,600
             e)  Coal Delivered to Preheater
                    at $!2.00/Ton                       3,540,000
             f)  Coal Delivered to Preheater
                    at $17,50/Ton                       5,162,500
             g)  Annual Operating Cost at $12.00        6,213,600
             h)  Annual Operating Cost at $17.50        7,836,000

         2. : Incremental Annual Revenues:
                                                                 14}
             a)  Light Oils 944,000 gals, at $0.41    $   387,040
             b)  Tar 2,522,300 gals, at $0.20             504,46oC4)
             c)  Ammonium Sulphate 3,103 tons at
                    $15.00/Ton                             46,551(4)
             d)  Coke Breeze and Pea Coke 35,000
                    Tons/Yr. at $12.00/Ton                420,000

                 Sub Total                            $ 1,358,051
             e)  Furnace Coke Sales at $54.00/Ton* '     9,990,000
             f)  Furnace Coke Sales at $40.00/Ton       7,400,000
             g)  Total Revenues at $54.00/Ton          11,348,051
             h)  Total Revenues at $40.00/Ton           8,758,051
     '4'Unit Prices from "Chemical Marketing Reporter" Feb. 18,  1974,

             Task Force Report.

                            - 12 -

-------
Economic Evaluation




        When it is assumed that no additional investment is




required to process the additional by-products produced from




the pipeline charging system an evaluation of the return on




investment can be made.




        For this evaluation several cases are studied.  Two




cases vary the.selling price of the coke from $54.00/ton^5'




to $40.00/ton, and two cases vary the purchase price of the




coal from $l2.00/ton to $17.50/ton when the incremental pro-




duction is 185,000 tons/year (44% increase in production),




and 124,600 tons/year  (30% increase in production).




        For the calculation of the ROI, the preheating and




pipeline investment is depreciated over 15 years and the op-




portunity cost or interest on the investment is 10%.  It is




further assumed that all costs, capital and operating are




chargeable to the incremental production.




        Fig. I plots the percent return on investment for two




coal prices against the selling price of furnace coke, as well




as the effect of the incremental furnace coke production.  In




the ranges studied the ROI is positive and therefore there




exists a payout for the investment.  In fact at $54»00^ ' for
' 'Gasp Task Force Report.
                       - 13 -

-------
furnace coke and $17.50 for coal the payout, even at the




lower incremental production rate, is good.




        It could be argued that the estimated capital costs




are too low.  For the basis used here an increase in the




capital costs of 30% would reduce the percent return on in-




vestment by one percentage point.




        The percentage increase in capital costs for retro-




fitting existing plants with the pipeline charging system is




in the range of 60-70%.  However, this percentage does not re-




present a true picture.  An 80 oven battery with an annual coke




capacity of 500,000 tons/year could be expected to cost between




$28,000,000 to $30,000,000.  But in fact we are saying that a




55 oven battery plus the pipeline costs could produce the same




amount of coke.  A 55 oven battery with pipeline charging would




cost in the range $28,000,000 to $32,000,000=  The cost com-




parisons above are on the basis of retrofitting the pipeline




charging.  Since'comparable work is less expensive when building




a new oven, the construction cost for a 55 oven battery with




pipeline charging could be somewhat lower,,




        The cost of retrofitting ovens with coal preheating and




pipeline charging will vary with the capacity of the preheating




system.








                       - 14 -

-------
        The ultimate size of any preheating system would be




dependent on it's location in relation to the ovens being served




and the distance of the coal feeding lines from the storage




hoppers to the ovens.  The cost would also be significantly




lower if the ovens were built with pipeline charging con-




nections already installed in the oven.  Therefore any mathe-




matical relationship of capacity to cost would not necessarily




be meaningful.
                       - 15 -

-------
                      FIG. I
          COKE  OVEN - PIPELINE CHARGING
            I  EFFECT OF COST OF COAL
       . AKD SELLING PRICE OF FURNACE  COKE
                • . ..    ON THE
            I  ...      -




            _L_ RETURN.. ON... INVE.S TMEN1L. „.'	„__.
     $l2.0C/Ton  Coal
     $ 17 . 50/Ton .Coal
  ?17.50/Ton Coal-
 30
  i


.—r_.
 _r
35
40
 •i
45
 I

 i
50
       Selling Price •-' Furnace Coke $/Ton
55
                      -  16 -

-------
Halcon System - Total Installed Cost

        This estimate includes two eductor - scrubber cars,

preassembLed and ready to set on track, two sets of hoods

and related hardware prefabricated to suit the operating and

spare hot car and coke guide.  The estimate includes the cost

of installing these hoods and hardware on each hot car and

coke guide as well as a track drainage system.  It also in-

cludes the cost of start-up and owners coordination costs.


        a)  Equipment and Material               $1,850,000
        b)  Field Assembly Costs - Direct Labor  	54^000

        c)  Sub Total                            $1,904,000

        d)  Contractors Overhead                     18,900
        e)  Contractors Profit              -    - 	10,800

        f)  Sub Total                            $1,933,700

        g)  Owners Coordination Cost                 11,OOP

        h)  Sub Total                            $1,944,700

        i)  Start-Up Costs 4.5%                      87,512

        j)  TOTAL INSTALLED COST                 $2,032,212
                       - 17 -

-------
Halcon System - Operating Costs

        The operating cost of this system, is based on power

requirement of 80 kw and heat requirement of 12.6 x 106 BTU/hr.

No additional manpower is required.


        a)  Power Cost $/Year               $  8,400
        b)  Heat                              99,800
        c)  Maintenance Cost at 6%           121,933

        d)  Sub Total                       $230,133

        e)  Interest on TIC at 10%           203.221

        f)  ANNUAL OPERATING COST           $433,354
                       - 18 -

-------
Halcon System - Economic Evaluation




        The return on investment with 15 year depreciation




is a negative $297,874„




        This amounts to $0.,71 per annual ton of furnace coke




or $0«,60 per gross annual ton of coke0




        Unless the effectiveness of controlling pushing




emissions with this method is proven, the negative return on




investment does not justify any expenditure of funds0




        The cost of the Halcon System is a function of the




number of quench cars required for a given battery„  For example,




the case estimated in this report is near the number of ovens




which would be limiting for one quench car to handle.  In this




report a push must be made approximately every 12 minutes„




Therefore, additional coke production would require an additional




Halcon System.  But for less production one system is still




required.
                       - 19 -

-------
:V  G    Great Lakes Pushing Control System - Total Installed Cost

                Installed Costs:

                a)  Collecting Duct, Stacks, Scrubber
                    Interconnecting Duct and Hardware   $  785,224

                b)  Civil - Structure and Concrete         143,190

                c)  Hood and Miscellaneous Steel           102,670

                d)  Venturi Scrubbers, Blowers,
                    Water Piping                           809,116

                e). Sub Total Installed Cost   .         $1,804,200

                f)  Engineering                            184,000

                g)  Fees                                    30,000

                h)  Sub Total                           $2,054,200

                i)  Start=Up Costs at 9%*                  186,000

                j)  TOTAL INSTALLED COST                $2,240,200
        * Because of the exposed hydraulic cylinder: linkages and
          bearings for sleeves and dampers it is expected that
          start-up costs will be higher than normal.
                                - 20 -

-------
H    Operating Costs For Great Lakes Steel Pushing Control System







             a)  Power                                $111,900




             b)  Operating Labor (24 MH/Day)             87,337.




             c)  Maintenance and Operating Supplies    156,800




             d)  Annual Interest at 10% TIC            224,000




             e)  ANNUAL OPERATING COST                $580,037
                            - 21 -

-------
Great Lakes Pushing Control System - Evaluation




        The return on investment when the above investment




is depreciated over 15 years is a negative $430,691/Year„




This amounts to $1.025 per annual ton of furnace coke or




$0o86 per annual gross ton of coke„




        Unless this method can demonstrate a positive effect




on the reduction of emissions from the coke oven pushing




operation, the negative return on investment does not warrant




the expenditure involved.




        The many variables which affect the cost of this type




of system do not lend themselves to meaningful mathematical




relationships between capacities and cost.  For example, if




two batteries of 80 ovens each were located end to end the




incremental cost of adding this system to the second battery




would be 75% of the cost of the first battery„  But those




same two batteries in any other position relative to one an-




other would be 100% of the cost of the first battery.
                       - 22 -

-------
Double Main - Estimate
        a)  Duct Cost                             $  450,000




        b)  Flushing Liquid Piping, Pumping, etc.    150,000




        c)  Modify Ovens - New Structure             280,000




        d)  Tie In To Boosters                        30,000




        e)  Flushing Piping and Pumps                100,000




        f)  Sub Total                             $1,010,000




        g)  Engineering Cost                          98,000




        h)  TOTAL INSTALLED COST                  $1,108,000
                       - 23 -

-------
K    Double Main - Operating Costs
             a)   Total Annual Operating Costs
                 10% of Total Installed Cost    .      $110,800
                            -  24  -

-------
Double Main - Economic Evaluation




        The return on investment when the installed cost is




depreciated over 15 years is negative $36,933,,  Since the




installation of a second main does not assure an effective




charging emission control the expense of this capital is not




justified.
                       - 25 -

-------
V    EFFECTIVENESS OF RETROFITTING COKE OVENS FOR POLLUTION CONTROL




A    General




             Little information is available concerning the actual




     particulate losses resulting from charging and pushing operations




     of coke ovens„  Some opinion exists that.the pollutants from




     an oven are split about 60% from the charging operation, 30%




     from the pushing operation and the remainder from the quenching




     operation.




             This split however should not be considered as re-




     presentative or typical.  There is a wide variation from plant




     to plant, depending on age of the ovens, quality and quantity




     of maintenance, types of coal used and operating practices.




             Considerable leakage can occur from doors whose seats




     have been damaged by improper handling or maintenance.  Leakage




     can also occur from warped or improperly luted charging hole




     covers,  A common source of leakage, particularly in older ovens,




     is from cracks from the coke side of the oven into the flues.




     This is more common at the end flues near the doors which are




     subject to rapid cooling after the pushing operation,,  Smoke




     leaks into the flues and leaves via the flue stack.  This




     leakage is difficult to control.,
                            - 26 -

-------
        The temperatures throughout the coke oven battery




are constantly changing as one oven is pushed and filled




with coal.  This temperature fluctuation is continuous.




However, if coal blends are changed or not kept uniform or




the moisture in the coal charged varies, these temperature




fluctuations can be more severe.  The movement which con-




stantly goes on because of these factors can cause leakage




from many points other than from charging, pushing and




quenching.




        Retrofitting operating coke ovens adds considerable




cost to any installation.  All work which involves the in-




sertion of opening into the oven must be very carefully




planned and executed so as to minimize the hazards to those




performing the work as well as minimizing any lost production.




Other construction work in the vicinity of any coke oven bat-




tery is constantly exposed to the movement of the coal and




coke handling equipment and results in work interruptions.
                       - 27 -

-------
B    Pipeline Charging




             In principle it appears that the pipeline charging




     system minimizes many of the possibilities for leakages which




     can occur during the charging cycle.  The charging hole covers




     do not have to be removed normally and therefore can be more




     permanently luted.  The charging hole covers are also not




     subject to damage by constant handling*  The pipeline system




     would also tend to eliminate the temperature fluctuations due




     to varying moisture content of the coalo  This system also




     eliminates the constant vibration caused by larry car travel




     over the battery.




             It appears that the pipeline charging system should




     be an effective means of reducing pollution from the charging




     operation, when operated properly.




             However, it is not free of all problems„  For example,




     the standpipe performance can still be restricted by carbon




     plugged steam jets, the charging connection to the oven can




     also be partially blocked.  Each of these could result in




     malfunction and possibly smoky charges.




             Pipeline charging also does not eliminate the problems




     discussed under V-A.




             As of the end of 1973 there were 192 ovens either




     equipped or in the process of being retrofitted with coal pre-





                            - 28 -

-------
heating and pipeline charging systems.  Twenty-four of these




ovens are on the Allied Chemical coke oven battery at Ironton,




Ohio.  These hav^e been in operation since October of 1970.




Seventy ovens were scheduled to be in operation with this




system at the Allied Chemical Co. ovens in Detroit, Michigan




late 1973.  Seventy-eight ovens at Tarrant (Birmingham)  are




to be retrofitted by early 1974 and an additional 20 in




Carling, France by the second quarter 1974.




        An objective evaluation of the emission control ef-




fectiveness of retrofitted pipeline charging systems should




be made when the ovens listed above are debugged and in oper-




ation.  Until then the economic evaluations made in Section




IV-C can only be considered as a guide.
                       - 29 -

-------
Halcon Pollution Control System


        In principle the Halcon System could be an effective


method of controlling emissions from the pushing operation.


It collects the gas vapors from the operation as well as the


emissions from the quenching operation.  When coke is quenched


in a conventional system emission entrainment results in its
         \

spread around the vicinity of the quench tower and is finally


washed off--by- rain into the water shed.  The Halcon System


would partially control this by keeping the emissions in the


circulating water system.  Excess water from the quench car is


drained to the quench sump and recirculated to the scrubber


car.  It also has the advantage of requiring the least inter-


ference with operation during the construction period„


        However, in practice the system must demonstrate that


the suction into the scrubber system is adequate to handle


all the gases and vapors from the push and quench operation


independently of wind direction and velocity.  It also must


demonstrate that it can withstand the severe erosion and cor-


rosion from circulating the quench water,,  If these can be


demonstrated it will be a relatively simple and effective con-


trol device.  To date these requirements have not been demon-


strated.




                       - 30 -

-------
Great Lakes Steel Pusher Control Device




        In principle this system should also be an effective




pusher emission control device.  However, it seems to be




relatively complex since there are many hydraulic cylinders




and damper linkages in the immediate vicinity of the ovens.




The general atmosphere in the immediate vicinity of the ovens




can be relatively corrosive and would subject the linkage pins




and bearings to adverse conditions and make maintenance very




high.




        As noted in the Halcon System, this system must also




demonstrate that the negative draft can contain emissions from




pushing independant of wind direction and force.  To date this




system has not adequately demonstrated that it can effectively




reduce emissions resulting from the coke oven pushing operation.
                       - 31 -

-------
V  E    Double Collecting Mains




                In order to increase the capability of the gas removing




        facilities i.e. the risers and main, some operators are con-




        sidering installation of a second gas main with its related




        auxiliaries.  This solution would most likely be considered




        for the longer ovens.  However, if space allows, it could be




        considered for shorter ovens.  In effect the capacity to remove




        gas and smoke during the charging operation doubles when this




        approach is used.  The double gas main also minimizes the ef-




        fects of momentary closing the gas passage in the oven top,




        because of improper charging procedures.  In the single uptake




        oven a blockage in the middle of the oven top would pressurize




        the passage opposite the uptake.  With the double main, both




        sides would still have free passage to an uptake.




                The installation of a second main, requires that a




        penetration be made through the roof of each oven.  This re-




        quires adequate sheilding of the heat from the immediate work




        area.  It also requires that once the roof has been penetrated




        that the work continue until it can be closed properly to allow




        continued operation.




                Like any repair or modification to an operating coke




        oven the work must be very carefully planned to minimize hazards
                               - 32 -

-------
to the men performing the work, the effects on production




and the mechanical effects on the oven itself.




        The double main increases the capacity of the system




to handle the oven gases by lowering the pressure in the oven,




both during charging operations and normal coking.  It there-




fore tends to minimize emissions during charging and allows less




back pressure build up in the oven during the coking period and




therefore reduce leakages to the air.  However, the principle




advantage of this system is that it in effect provides an ad-




ditional outlet for the emissions generated during charging.




If one gooseneck is carbonized the opposite member would per-




form the function.  Where only one gooseneck is provided this




condition would result in a greater emission of particulates„
                        -  33  -

-------
VI    COST UPDATING

              Updating the costs for the type estimate made for

      installed costs in this report can best be done by utilizing

      the Engineering News Record Cost Indexes for Skilled Labor and

      Materials as follows using December 27, 1973 as the base index.

      Divide the Engineering Index for Skilled Labor for the period

      desired by the Engineering Skilled Labor Index for December 27,

      1973, add to this Engineering Index for Materials for the per-

      iod desired divided by the Materials Index for December 27,

      1973.  Multiply this sum by one half the total installed cost

      of the item in question.

              For Example:  Pipeline Charging TIC = $14,620,000

      updated to January 31, 1974.

              14,620,000   (  1781.8     770.9  \     = $i4/517j660
                  2        V  1774.2     785.1
                             - 34 -

-------
VII
STATE AND LOCAL REGULATIONS RESULTING IN COKE OVEN CONTROL
       Alabama
                   Charging:  Opacity greater than 40% or No.
                   2 Ringelman for 5 minuter per coking cycle.

                   Pushing:  Opacity greater than 40% or No.
                   2 Ringelman for more than 1 minute.

                   Quenching:  Quenching towers require baf-
                   fles.

                   Miscellaneous:    (a) Each coke oven is con-
                   sidered as an individual oven, (b) Each
                   oven operator must maintain oven equipment
                   in good condition and exercise good oper-
                   ting practice, and  (c) maintains inventory of
                   coke oven doors 1 for 12 coke ovens operated.
       Illinois
                   No visible emission from charging port
                   except 15 seconds during any one charging
                   operation.  During that period opacity no
                   greater than 30%.

                   Quench Tower:  No greater than 30% opacity.

                   After December 31, 1974 all coke facilities
                   to be equipped with enclosed pushing and
                   quenching systems.

                   Work rules must be approved by A.P.C. Agency,

                   Emission from doors limited to 10 minutes
                   after start of coking cycle.  During that
                   period opacity no greater than 30%.
       Michigan
                   Opacity no greater than No. 2 Ringelman  for
                   not more than 3 minutes in any 30 minute
                   period.  No greater than No. 3 Ringelman  for
                   not more than 3 minutes in any 60 period  but
                   not more than 3 occassions during any 24  hour
                   period.
                              - 35 -

-------
Ohio            -  Opacity 20% or No. 1 Ringelman except 60%
                   or No. 3 Ringelman for not more than 3
                   minutes in any 60 minute period.
Pennsylvania    -  Opacity no greater than No. 2 Ringelman
(Allegheny County) not to exceed 8 minutes in any 60 minute
                   period.
Texas           -  Opacity of 30% averaged over 5 minute
                   period if built prior to January 31, 1972.
Virginia        -  Opacity no greater than No. 1 on Ringelman
                   except during charging and Ringelman No. 2
                   for periods- no more -than 2 minutes per
                   charge and 1 minute, per push.
                       - 36 -

-------
                                   TECHNICAL REPORT DATA
                            (Please read Instructions on the reverse before completing)
1. REPORT NO.
  EPA-450/3-76-013
                                                            3. RECIPIENT'S ACCESSION>NO.
4. TITLE AND SUBTITLE
  Cost of Retrofitting Coke Oven  Particulate Controls
5. REPORT DATE
   March  6.  1974
                                                            6. PERFORMING ORGANIZATION CODE
7. AUTHOR(S)
                                                            8. PERFORMING ORGANIZATION REPORT NO.
  Vulcan-Cincinnati, Inc.
                                                               JN-687
9. PERFORMING ORGANIZATION NAME AND ADDRESS
  Vulcan-Cincinnati, Inc.
  1329 Arlington Street
  Cincinnati,  Ohio  45225
                                                            10. PROGRAM ELEMENT NO.
11. CONTRACT/GRANT NO.
                                                               68-02-0299
12. SPONSORING AGENCY NAME AND ADDRESS
  EPA, OAQPS,  SASD,  CAB
  N.  C. Mutual  Bldg.
  Research  Triangle  Park, NC   27711
                                                            13. TYPE OF REPORT AND PERIOD COVERED
   Final
14. SPONSORING AGENCY CODE
15. SUPPLEMENTARY NOTES
  Support for  the Preferred Standards Path Analysis  for Polycyclic Organic Matter.
16. ABSTRACT            •

       This report provides estimates of the total  investment required to retrofit
  pollution control  devices on  existing coke ovens  based on the state-of-the-art
  in 1973.  Projected operating costs of these devices are estimated  along with
  an evaluation  of their effects on the return on  investment.  In addition some
  of the problems  related to retrofitting pollution control equipment are reviewed
  in relation  to the expected relative effectiveness of the control device.
17.
                                KEY WORDS AND DOCUMENT ANALYSIS
                  DESCRIPTORS
                                               b.IDENTIFIERS/OPEN ENDED TERMS  c. COSATI Field/Group
  Coke ovens
  Particulate  controls
  Costs
  Pipeline Charging
  Pushing Controls
13. DISTRIBUTION STATEMENT

  Release unlimited
                                               19. SECURITY CLASS (This Kepiirt/
                                                  Unclassified
                                                                          21. NO. OF PAGES
                   36
                                               20. SECURITY CLASS (This pan
                                                  Unclassified
                                                                          22. PRICE
EPA Form 2220-1 (9-73)

-------