EPA-450/3-78-043
November 1977

                       FLUE GAS
   DESULFURIZATION SYSTEM
    MANUFACTURERS SURVEY
   U.S. ENVIRONMENTAL PROTECTION AGENCY
       Office of Air and Waste Management
     Office of Air Quality Planning and Standards
    Research Triangle Park, North Carolina 27711

-------
      FLUE GAS DESULFURIZATION

     SYSTEM MANUFACTURERS SURVEY
             Prepared by

  Industrial Gas Cleaning Institute
    Stamford, Connecticut  06904
       Contract No. 68-02-2532
             Task No. 4
            Prepared for

U.S. Environmental Protection Agency
Strategies and Air Standards Division
      Economic Analysis Branch
       Research Traingle Park
        North Carolina  27711
            November 1977

-------
                     TABLE OF CONTENTS

                                                       Page

1.0  INTRODUCTION                                      1-1

2.0  CAPABILITIES OF MANUFACTURERS                     2-1

3.0  AVAILABILITY OF MANPOWER AND EQUIPMENT FOR        3-1
     DESIGN AND INSTALLATION OF FGD SYSTEMS

4.0  GUARANTEES                                        4-1

-------
                       LIST OF TABLES

Table                                                  Paqe
 1-1      Manufacturers Responding to the Survey       1-3
          and the FGD System(s) Offered by Each

 2-1      Projected Number of FGD Systems That         2-3
          Manufacturers Can Design and Install over
          a 15-year Period

 2-2      Sources of Personnel to Accomplish Various   2-4
          Stages of FGD System Design and Installation

 2-3      Time Required for FGD System Design,         2-5
          Installation and Start-Up

 2-4      Process Distribution of Planned FGD Systems  2-6
          on New Coal-Fired Utility Boilers

 3-1      Major Manufacturers of FGD System Components 3-3

 3-2      Manufacturers Capability to Meet the         3-4
          Demand for Ball Mills

 3-3      Manufacturers Capability to Meet the         3-5
          Demand for Clarifiers

 3-4      Manufacturers Capability to Meet the         3-6
          Demand for Fans

 3-5      Manufacturers Capability to Meet the         3-7
          Demand for Pumps

 3-6      Manufacturers Capability to Meet the         3-8
          Demand for Vacuum Filters

 3-7      Raw Material Specifications for Various      3-9
          FGD Systems
                            111

-------
                 LIST OF TABLES (continued)

Table                                                  Page

 4-1      Guarantees Offered by Manufacturers for      4-2
          SO2 Removal

 4-2      Summary of Performance Guarantees Offered    4-3
          by Manufacturers

 4-3      Willingness of Manufacturers to Provide      4-4
          Operation and Maintenance Service for
          FGD Systems
                            IV

-------
                     1.0  INTRODUCTION


     The purpose of this study is to assess the capability

of manufacturers of pollution control equipment to meet

current and future demands for flue gas desulfurization

(FGD) systems.  Both regenerative and nonregenerative FGD

systems are considered in the study.

     A survey form was prepared and sent to 18 representa-

tive manufacturers of FGD systems.  The following informa-

tion was requested:

     0    Type of FGD system manufactured.

     0    Capability of companies to design and install
          various sizes of FGD systems.

     0    Future use pattern of FGD systems.

     0    Manufacturers' guarantees.

     0    Raw material availability and specifications.

     0    Manpower and equipment availability for installing
          FGD systems.

     0    Willingness of manufacturers to provide for
          operation and maintenance services.

     Thirteen of the 18 manufacturers contacted either

completed or partially completed the form and returned it.
                           1-1

-------
Table 1-1 lists them and the FGD systems they produce.  The




information they furnished is found throughout the balance



of the report.
                           1-2

-------
                            Table 1-1.  MANUFACTURERS RESPONDING TO THE SURVEY AND THE FGD SYSTEM(S) OFFERED BY EACH
Manufacturer
1 . Babcock & Wilcox
Company
2. Chemico Air Pollution
Control Company
3. Chiyoda International
Corp.
4. Combustion Engi-
neering. Inc.
5. Davy Powergas, Inc.
6. Environeering, Inc.
7, Flakt, Inc.
8. FMC Corp.
9. Peabody Process
Systems, Inc.
10. Pullman, Inc.
11. Research-Cottrell,
Inc.
12. UOP. Inc.
13. Zurn Air Systems
Type of FGD System Offered
Regenerative system
Magnesium
oxide

X










Phosphate

X



•






We 11 man-
Lord




X







Catalytic
oxidation


X









Citrate







X


Nonregeneratlve system
Double
alkali

X




X



i
i *
X
Lime
X
X

X

X
X

X
X

X

Limestone
X
X

X

X
X

X
X
X
X

Chiyoda
thoroughbred
101


X









Sodium
carbonate






X



X

Hydro





X






 I
CO

-------
             2.0  CAPABILITIES OF MANUFACTURERS





     Presently more than 10 different processes are available



for desulfurization of boiler flue gas (Table 1-1).  These



processes can be broadly separated into two classes, regen-



erative and nonregenerative.



     A regenerative FGD system removes the sulfur dioxide



(SO_) and converts it to a marketable by-product, usually



elemental sulfur, sulfuric acid, or a concentrated S0_ gas



stream.  Magnesium oxide (MgO) scrubbing, the Wellman-Lord



process, the citrate process, the phosphate process, the



ammonium bisulfate process, charcoal adsorption, and the



Shell FGD system are examples of regenerative systems.



     A nonregenerative system removes the SO- from flue gas



by reacting it with a compound.  This reaction produces a



sludge which must be disposed of in an environmentally sound



manner.  Lime scrubbing, limestone scrubbing, the sodium



carbonate process, the Hydro process, the double alkali



process, and the Chiyoda Thoroughbred 101 process are



examples of nonregenerative systems.




     Only the following FGD systems are considered in this



report:
                           2-1

-------
     0    Lime scrubbing



     0    Limestone scrubbing



     0    Double alkali



     0    Wellman-Lord



     0    Magnesium oxide



     Table 2-1 summarizes the projected number of FGD



systems that manufacturers can design and install over three



5-year periods.  These figures are broken down into size



categories and the use of the present staff versus an



expanded staff.  The manufacturers were also queried re-



garding their sources of personnel to perform various stages



of FGD system design and installation.  Table 2-2 summarizes



the information they provided.



     The survey form included a request for estimates of



the time required to design, install, and start up the FGD



systems.  Table 2-3 presents average times and the ranges



of times submitted for various sized systems.



     The future use pattern of the various FGD systems was



calculated by PEDCo.  Table 2-4 presents this information.



     Responses to questions in this section of the survey



were received from 12 manufacturers.  The non-responding



manufacturers posses a small share of the total market.



Therefore the numbers shown in the following tables are



judged to be low by about 15 percent.
                           2-2

-------
ro
I
u>
               Table  2-1.   PROJECTED  NUMBER OF  FGD  SYSTEMS  THAT  MANUFACTURERS

                       CAN  DESIGN  AND INSTALL OVER  A  15-YEAR PERIOD3
Systems,
designed
5 MWC
20 MWC
50 MW
200 MW
1000 MW
Systems .
installed
5 MWC
20 MW°
50 MW
200 MW
1000 MW
Number of units
1978-1982
Present
staff
202
195
212
171
156

155
148
167
121
108
Expanded
staff
342
332
375
307
283

243
232
284
197
179
1983-1987
Present
staff
221
209
224
177
161

184
172
187
134
120
Expanded
staff
412
394
427
348
321

327
309
335
244
220
1988-1992
Present
staff
226
213
327
179
161

192
179
193
140
124
Expanded
staff
424
406
439
359
331

332
314
348
253
228
       Represents the responses of  12 manufacturers.   The  manufacturers  indicated
       that the size range of  200 to 800 MW would  not  have a  great  impact  on their
       capability to design or install units;  however,  other  sizes  would affect
       their capabilities.  The capability shown in  this table  refers  to both
       regenerative and nonregenerative systems.

       The difference between  the number of systems  designed  and  the number installed
       results from the long lead time required for  installation  of FGD  systems.

       One of the 12 responding manufacturers  indicated that  they would  not bid on
       5- and 20-MW units, which is reflected  in the fewer units  shown for these two
       sizes than for a 50-MW  unit.

-------
       Table 2-2.  SOURCES OF PERSONNEL TO ACCOMPLISH

   VARIOUS STAGES OF FGD SYSTEM DESIGN AND INSTALLATION
                            a ,b
      Item
  Number of
manufacturers
using in-house
  personnel
  Number of
manufacturers
using outside
    labor
Process design

Detailed engineering
 design

Equipment fabrication

  Scrubber vessels/tanks

  Fans/pumps

  Sludge disposal

System installation

  Supervision

  Crafts
      12

      11
       4

       1

       0



      10

       1
      1

      3
      9

     11

     11



      3

     11
  Some manufacturers indicated that they use both in-house
  personnel and outside labor to accomplish the different
  stages of FGD system design and installation.

  Represents the responses of 12 manufacturers.
                           2-4

-------
       Table 2-3.  TIME REQUIRED FOR FGD SYSTEM DESIGN, INSTALLATION, AND START-UP'
Size,
MW
<100
100-400
400-800
>800
Time required for
design and installation, months
Average
22.2
24.4
30.1
33.1
Range
6 to 36
8 to 36
18 to 42
20 to 42
Time required for start-up, months
Average
1.8
2.3
2.4
2.7
Range
0.5 to 6
0.5 to 6
0.5 to 7
0.5 to 7
to
I
     a
       Represents the responses of 12 manufacturers.

       "Start-up" is defined as the time between completion of plant construction and

       the capability of the plant to operate at an acceptable level of capacity.

-------
 Table 2-4.  PROCESS DISTRIBUTION OF PLANNED

FGD SYSTEMS ON NEW COAL-FIRED UTILITY BOILERS'
FGD process
Lime
Limestone
Double alkali
Wellman-Lord
Magnesium oxide
Other
Total
Percent distribution
38
52
3
3
2
2
100
  The following assumptions were used to calculate
  this distribution:

   0 Units coming on line through 1980 have been
     committed to a specific SO2 control device
     due to the long lead times for FGD system
     installation.

   0 All New England (U.S. EPA, Region I)  utilities
     will use regenerable systems.

   0 The distribution is applied to new units
     through year 2000.
                     2-6

-------
        3.0  AVAILABILITY OF MANPOWER AND EQUIPMENT



         FOR DESIGN AND INSTALLATION OF FGD SYSTEMS






     Construction of power plants and their FGD systems



requires the services of the same types of craftsmen.  The



key crafts required for power plant and FGD system installa-



tion are:



     0    Boilermakers



     0    Carpenters



     0    Electricians



     0    Ironworkers



     0    Laborers



     0    Millwrights



     0    Pipe fitters



     0    Welders



     The domestic construction industry is currently in a



slump.  Therefore, short-term growth requirements could be



met with few problems in most regions, except for the highly



skilled mechanical craftsmen (including welders).   As of



mid-summer 1977,  the following selected areas reported



existing or anticipated shortages of skilled craftsmen:
                             3-1

-------
          Location                      Craftsmen

     Denver, Colorado                 Carpenters
                                      Ironworkers

     Detroit, Michigan                Boilermakers
                                      Pipe fitters

     Boston, Massachusetts            Electricians

     Missouri and Nebraska            Boilermakers
                                      Pipe fitters

     North Carolina                   Carpenters

A selected number of large national power plant contractors

who were contracted indicated that a shortage of skilled

craftsmen in all disciplines is possible, indeed probable

even under the present New Source Performance Standards

(NSPS).   Unskilled laborers, on the other hand, will be

plentiful.  Even a 10 percent annual increase in the number

of craftsmen would be very difficult to maintain over an

extended period of time.  Moreover, the shortage of crafts-

men is anticipated to be more acute in areas remote from

high-population centers.

     Another survey was made of major component manufac-

turers to determine if the future demand for FGD system

components could be met under the alternative new source

performance standards.  The following components were of

concern:

     0    Ball mills

     0    Clarifiers
                             3-2

-------
     0    Fans




     0    Pumps



     0    Vacuum filters



     Table 3-1 lists the manufacturers contacted and the



equipment they manufacture.  The demand for additional FGD



system components for various sized plants was projected



through the year 1998 using standard engineering calcula-



tions.  Tables 3-2 through 3-6 present data on each com-



ponent.  In calculating the demand, a 500-MW capacity was



assumed for power plants coming on line in 1986 or later,



which would make the demand negligible for certain smaller



sized equipment.  This is evident in Tables 3-2 through



3-6.



     The results of this latter survey indicate that the



capacTty to manufacture components far exceeds the demand.



Table 3-4 shows a shortfall in the supply of large fans



during the 1978-82 and 1988-92 periods.  The shortages



would not be as great as the data indicate, however, because



all the manufacturers did not respond.  The data are further



qualified by the assumption used in calculating demand that



all new units coming on line after 1986 will be 500 MW or



greater in capacity.  This assumption slants the requirements



for equipment to larger capacities, whereas the manufacturers'



responses covered a wide size range.  An examination of the
                             3-3

-------
Table 3-1.  MAJOR MANUFACTURERS OF FGD  SYSTEM  COMPONENTS
Manufacturers
1. Allis-Chalmers
2. American Air Filter
3. Bird Manufacturing
Co.
4. Buffalo Forge Co.
5 . Combustion
Engineering
6. Denver Equipment
Co.
7. Dorr-Oliver Inc.
8. Environeering Inc.
9. Envirotech Corp.
10. FMC Corp.
11. Goulds Pump Inc.
12. Ingersoll-Rand Co.
13. Joy Manufacturing
Co.
14. Kennedy Van Saun
Corp.
15. Koppers Co. Inc.
16. UOP Engineering
Products Corp.
17. Worthington Pump
Inc.
18. Zurn Industries
Inc.
FGD System Component Manufactured
Fans




X


X




X


X

X
Ball
mills
X




X







X
X



Pumps
X


X


X



X
X




X

Vacuum
filters


X

X
X


X
X








Clarif iers





X
X

X
X




X



                           3-4

-------
        Table 3-2.  MANUFACTURERS CAPABILITY TO MEET

                 THE DEMAND FOR BALL MILLSa
Years
(Inclusive)
1978
to
1982
1983
to
1987
1988
to
1992
Size (tons/hr)
0-8
Demand*3

131


20


1

Capacity

662


860


860

8-16
Demand13

99


13


0

Capacity

594


710


710

16-24
Demand

186


86


426

Capacity

448


560


560

Represents the responses from 2 manufacturers.

The very low demand during certain time periods was derived based
on the assumption that the plants coming on line after 1986 will
be 500 MW units; therefore these plants will require larger
equipment.
                          3-5

-------
        Table 3-3.  MANUFACTURERS CAPABILITY TO MEET

                THE DEMAND FOR CLARIFIERS3'b
Years
(Inclusive)
1978
to
1982
1983
to
1987
1988
to
1992
Size (diameter-ft)
0-50
Demand^

50


2


0

Capacity

200


250


250

50-100
Demand0

119


21


2

Capacity

360


450


450

100-150
Demand

130


64


426

Capacity

400


500


500

Assume maximum height of 10 foot.
Represents the response of 1 vendor.
The very low demand during certain time periods was derived based
on the assumption that the plants coming on line after 1986 will
be 500 MW units; therefore these plants will require larger equip-
ment.
                          3-6

-------
                     Table  3-4.   MANUFACTURERS  CAPABILITY TO MEET THE

                                    DEMAND  FOR  FANSa'b
Years
(Inclusive)
1978
to
1982
1983
to
1987
1988
to
1992
Size (acfm)
180,000
Demand0
19
1
0
Capacity
450
625
625
300,000
Demandc
66
9
3
Capacity
410
575
575
360,000
Demandc
287
41
13
Capacity
370
525
525
420,000
Demand
800
263
852
Capacity
330
475
475
U)
I
       Assume AP = 18",  temperature = 300°F.

       Represents the  response from 1 manufacturer.

       The  very low demand during certain time periods was derived based on the assumption
       that the plants coming on line after 1986 will be 500 MW units;  therefore these plants
       will require larger equipment.

-------
        Table 3-5.  MANUFACTURERS CAPABILITY TO

              MEET THE DEMAND FOR PUMPS3'b
Years
(Inclusive)
1978
to
1982
1983
to
1987
1988
to
1992
Size (gpm)
0-5
Demand0

56

3

0
rooo
Capacity

112

6

112
5,000-10,000
Demand

3,132

850

2,342
Capacity

6,264

1,700

4,684
Assume specific gravity = 1.06 and AH = 150 ft.

Represents the responses of 2 manufacturers.

The very low demand during certain time periods was
derived based on the assumption that the plants coming
on line after 1986 will be 500 MW units; therefore
these plants will require larger equipment.
                         3-8

-------
U)
I
                       Table 3-6.   MANUFACTURERS CAPABILITY TO MEET

                              THE DEMAND FOR VACUUM FILTERS3
Years
(Inclusive)
1978
to
1982
1983
to
1987
1988
to
1992
Size, ft2
0 to 279
Demand*3

141


21


1

Capacity

244


340


352

279 to 588
Demand13

47


8


1

Capacity

260


260


260

588 to 833
Demand

114


46


212

Capacity

260


260


260

            Represents the responses from two manufacturers; 1 of the 2 manufac-
            turers did not predict the capacity in the size range 279 to 833
            sq.  ft.

            The  very low demand during certain time periods was derived based
            on the assumption that the plants coming on line after 1986 will
            be 500 MW units;  therefore these plants will require larger
            equipment.

-------
capacities on a total volume basis shows a demand of 954

million acfm, whereas the capacity is 1822 million acfm.

     Most manufacturers stated that the demand could be met

without expanding the number of production shifts or hours.

It should be noted that a response was received from only

half of the manufacturers contacted.

     The manufacturers responding to the FGD survey reported

ample availability of the raw materials used in their FGD

systems.  Table 3-7 shows raw material specifications for

the five FGD systems.

        Table 3-7.  RAW MATERIAL SPECIFICATIONS FOR

                    VARIOUS FGD SYSTEMS
     FGD system
                                   Raw materials
       Type
  Specifications
1. Lime

2. Limestone


3. Magnesium oxide

4. Double alkali

5. Wellman-Lord
Calcium oxide

Calcium carbonate


Magnesium oxide

Sodium carbonate

Caustic soda
90% CaO
90% CaCO3, pass
200 mesh

98.5% MgO

98% Na2C03

50% NaOH, 50 ppm
maximum chloride
concentration
                            3-10

-------
                      4 . 0  GUARANTEES






     The current new source performance standard for coal-




fired power plants is 1.2 Ib S02/10  Btu.  The following




alternative standards are being considered:




     0    90 percent SO-  removal




     0    0.5 Ib SO2/106  Btu.




The manufacturers surveyed indicate that they are willing to




offer guarantees of 90 percent S02 removal.  Many of them




are prepared to offer guarantees of better than 90 percent




on a case-by-case basis.   Table 4-1 presents a brief summary




of various guarantees offered.




     More than half the surveyed manufacturers indicated a




willingness to guarantee  the performance (availability)  of




their systems.  Ninety percent was the typical level of per-




formance guaranteed.  Table 4-2 summarizes information on




performance guarantees.




     All manufactuers responding to the survey were willing




to guarantee the cost of  their FGD systems.  Four manufac-




turers would guarantee their costs subject to an escalation




clause, and one would negotiate the terms of his guarantee.




None of the others specified the provisions of their guarantee,
                            4-1

-------
                    Table 4-1.   GUARANTEES OFFERED BY MANUFACTURERS FOR SO  REMOVAL
Company
                    <90%
                                             Level  of SO.  removal guaranteed
              90%
               >90%
   C

   D

   E

   F
           Would normally guarantee
           80 to 85%.
                                       Minimum guarantee given.
                                       Minimum guarantee give.
Minimum guarantee given.
This guarantee is normally given.
This guarantee is given where
inlet concentration is 500 to
4000 ppm.

This guarantee is given where
low-sulfur coal is fired.

Minimum guarantee given.
                                       This guarantee is usually given
                                       when coal  with 3 to 4% sulfur
                                       is burned.

                                       This guarantee is normally given
                                       when either low- or high-sulfur
                                       coal is burned.

                                       Minimum guarantee given.
Is willing to offer 95% guarantee on
case-by-case basis.

Guarantee of >90% is based on inlet SC>2
concentration.

Would guarantee 95% in all cases.

Have guaranteed up to 92% in the past.

Have guaranteed >90% in the past.

Depending upon the process, they would
guarantee >90%.

Have guaranteed up to 95% in the past.
                                                                          Are prepared to offer better than 90%
                                                                          when either low- or high-sulfur coal is
                                                                          burned, but would not guarantee less
                                                                          than 50 ppm SO2 concentration in exit
                                                                          stream.
                                   In many cases they guarantee 95% when
                                   high-sulfur coal is burned.
                                   May guarantee up to 95% on a case-by-case
                                   basis.
  Represents the responses of  12  manufacturers.
  Company names are deliberately  withheld.

-------
    Table 4-2.  SUMMARY OF PERFORMANCE GUARANTEES OFFERED

                      BY MANUFACTURERS3
Company
                              Guarantee offered
     Yes (level)
No
   A

   B

   C


   D
   F

   G

   H

   I

   J


   K

   L
Normally better than 90%
Typically 90% during performance
testing; sometimes up to 95%

Maximum of 90% based on boiler
hours

Yes (level of guarantee not dis-
closed)

Have guaranteed in excess of 90%

Normally 85 to 90% for 1 or 2 years
Maximum of 90% on a case-by-case
basis
                                        X

                                        X
                                        X

                                        X
  Represents the responses of 12 manufacturers.
  Company names are deliberately withheld.
                            4-3

-------
     The manufacturers were asked whether they would be




willing to contract for the operation and maintenance of the




FGD system after installation.  Table 4-3 summarizes their




responses.





    Table 4-3.  WILLINGNESS OF MANUFACTURERS TO PROVIDE




     OPERATION AND MAINTENANCE SERVICE FOR FGD SYSTEMS3
Company
A
B
C
D
E
F
G
H
I
J
K
L
Provide operation and
maintenance service
Yes
X


X

X
X
X
X

X
X
No

X
X

X




X


      Represents the responses of 12 manufacturers.
                           4-4

-------
                                   TECHNICAL REPORT DATA
                            (Please read Instructions on the reverse before completing)
1  REPORT NO.

    EPA-450/3-78-043
4. TITLE AND SUBTITLE
  Flue Gas Desulfurization System
  Manufacturers Survey
             5. REPORT DATE
              November  1977
             6. PERFORMING ORGANIZATION CODE
                                                            3. RECIPIENT'S ACCESSION-NO.
7. AUTHOR(S)
  V.  P.  Patel
                                                            8. PERFORMING ORGANIZATION REPORT NO.
3. PERFORMING ORGANIZATION NAME AND ADDRESS
  Industrial Gas Cleaning Institute
 700 N. Fairfax Street, Suite 304
 Alexandria, Virginia  22314
                                                            10. PROGRAM ELEMENT NO.
             11. CONTRACT/GRANT NO.

               68-02-2532,  Task 4
12. SPONSORING AGENCY NAME AND ADDRESS
  U.S.  Environmental  Protection Agency
  Office of Air Quality Planning and  Standards
  Research Triangle  Park, North Carolina 27711
             13. TYPE OF REPORT AND PERIOD COVERED
               Final
             14. SPONSORING AGENCY CODE
15. SUPPLEMENTARY NOTES
16. ABSTRACT
  A survey of manufacturers of flue  gas desulfurization  equipment was  conducted to
  determine the  industry's capability to meet the demand for control equipment
  required by a  change in the S0£ emission standards  for boilers.  The report details
  the  processes  available, the capability of companies to design and install various
  sizes of FGD systems,  manufacturers'  guarantees, raw material availability arid
  availability of  equipment and manpower.
17.
                                KEY WORDS AND DOCUMENT ANALYSIS
                  DESCRIPTORS
                                               b.IDENTIFIERS/OPEN ENDED TERMS
                              COS AT I Field/Group
  Air Pollution
  Sulfur Oxides
  Electric Utilities
Air  Pollution Control
Stationary Sources
Coal-Fired Boilers
   13B
13. DISTRIBUTION STATEMENT

  Unlimited
19. SECURITY CLASS IThis Report!
  Unclassified
21. NO. OF PAGES

     28
                                               20. SECURITY CLASS (This page>
                                                 Unclassified
                                                                          22. PRICE
EPA Form 2220-1 (9-73)

-------