United States
                    Environmental Protection
                    Agency
Off ice of
Solid Waste and
Emergency Response
Publication 9360.3-01 FS
December 1990
   «>EPA    A  Guide to  Developing
                    Action Memorandums
   Office of Emergency and Remedial Response
   Emergency  Response Division, OS-210
                   Qutek Reference Fact Sheet
 EPA prepares Action Memorandums for all Fund-lead removal actions. Action Memos describe a site's history,
 current activities, health and environmental threats, and proposed actions and costs. Action Memos also demonstrate
 that site conditions meet the criteria for a removal action outlined in section 300.415 of the National Contingency Plan
 (NCP) and document approval of the proposed action by the proper Headquarters' or Regional authority.  A
 confidential addendum to the Action Memo outlines EPA's enforcement strategy for the site. In addition to Fund-
 lead removal actions, EPA prepares modified Action Memos for enforcement-lead removals and special circum-
 stances such as actions that require additional funds, a change in the scope of the response, or an exemption to the
 statutory limits under section 104(c) of the Comprehensive Environmental Response, Compensation, and Liability
 Act (CERCLA).

 This fact sheet describes the essential components of Action Memos used to initiate a removal action, as well as the
 special cases identified above.  Additional information on preparing Action Memos is contained in the "Action
 Memorandum Guidance" (OSWER Directive 9360.3-01, September, 1990). This guidance is the first in a series of
 documents under development to replace the "Superfund Removal Procedures" (OSWER Directive 9360.0-03B,
 February, 1988).  Further information concerning this series is found at the end of this fact sheet.
INTRODUCTION

An Action Memo is the primary decision document sub-
stantiating the need for a removal action, identifying the
proposed response, and explaining the rationale for the
removal action. Action Memos are prepared by On-
Scene Coordinators (OSCs) prior to the start of a re-
sponse, or after the fact for removal actions initiated
under the $50,000 approval authority delegated to OSCs
foruseinemergency situations. If circumstances change,
supplemental Action Memos may be required later in
the response to support the need to continue a removal
action beyond the statutory limits of 12 months in
duration or $2 million in expenditures, to increase the
total project ceiling, to change the scope of the response,
or combinations thereof.  In addition, for removal ac-
tions expected at the outset to exceed the statutory limits
on time and/or money, the OSC must prepare an Action
Memo that justifies the need to undertake the proposed
response and that also meets the  statutory exemption
criteria from these limits.
  Section 113(k) of CERCLA requires the establishment
  of an  administrative  record  for the selection of a
  CERCLA response action.  The administrative record
  is the body of information used by the Agency to select
  a response action.  As the primary decision document,
  the Action Memo must demonstrate consideration of the
  factors affecting the removal decision.  Action Memos
  that do not adequately substantiate the need for a re-
  moval action or the selected cleanup method may unde r-
  mine the Agency's case for a cost recovery action.

  The outline beginning on the next page summarizes the
  required  contents of a basic Action Memo used to
  initiate a  removal action within the statutory limits.
  These Action Memos are approved by the appropriate
  EPA Regional Administrator, unless the OSC's $50,000
  authority has been invoked (in these cases,  the OSC
  approves the Action Memo).  Modifications to this

-------
format are required to prepare Action Memos for other
circumstances, and  are discussed  in the following
sections.

Purpose

Begin with a statement of purpose that identifies:
•   The type of action requested (e.g., approval of a
    removal request,  ceiling increase, etc.);
•   The site's name and location;
    The name of the lead respondent;
    Whetherthe response was initiated under the OSC's
    $50,000 authority, or if any nationally significant or
    precedent-setting issues are involved.

Site Conditions and Background

Consolidate known factual information describing the
site including:
•   Removal site evaluation findings, physical location
    information, site  and release characteristics, NPL
    status, and maps, pictures, or other graphics;
    Other actions to  date, both government-lead and
    private party-sponsored;
•   State and local authorities' roles, both past actions
    and potential for future response.

Threats to Public Health and Welfare

Explain how this incident meets the requirements for a
removal action by detailing:
    The  threats to public health and/or welfare as they
    relate to the criteria listed in section 300.415 of the
    NCP (e.g.,  contamination of drinking water sup-
    plies, threat of fire or explosion). Discuss only those
    threats that will be addressed by the removal action,
    beginning with the most serious.
•   The  results of health consultations, advisories, or
    other health risk advice from the Agency for Toxic
    Substances Disease Registry (ATSDR).

Endangerment Determination

Include the following statement, selecting the appropri-
ate substance category:
    "Actual or threatened releases of [hazardous sub-
    stances/pollutants and contaminants] from this site,
    if not addressed by implementing the response ac-
    tion selected in this Action Memorandum, may
    present an imminent and substantial endangerment
    to public health, or welfare, or the environment."

Proposed Actions and Estimated Costs

Describe the specific tasks involved in the proposed
removal action, with separate sections detailing:
•   Contribution to remedial performance;
•   Alternative technologies;
•   Results of the Engineering Evaluation/Cost
    Analysis (EE/CA) for non-time-critical actions;
•   Applicable or relevant and appropriate requirements
    (ARARs);
•   Project schedule;
•   Total project ceiling (see Figure 1, page 3).

Expected Change In the Situation Should Ac-
tion Be Delayed or Not Taken

Describe any expected changes in the situation should
action be delayed or not taken, and provide a worst-case
scenario.

Outstanding Policy Issues

Discuss remaining  policy issues not identified else-
where in the Action Memo.

Enforcement

Summarize the extent to which potentially responsible
parties (PRPs) are known, and whether they can or will
respond.  Place all remaining information concerning
the enforcement strategy  in a separate addendum (see
page 3).

Recommendation

Provide an approval  statement indicating that NCP
removal requirements have been substantiated and
summarize the total project ceiling. Include the follow-
ing statement:
    "This decision  document represents the  selected
    removal action for the  [site name], in [location],
    developed in accordance with CERCLA as amended.
    and not inconsistent with the NCP. This decision is
    based on the administrative record for the site."

-------
                                            FIGURE 1
                              Sample Removal Project Celling Estimate
   Extramnral
        Regional Allowaree Costs:
           Total Cleanup Contractor Costs
           (This cost category includes
           OSC estimates for ERCS,
           Regional ERCS, subcontractors,
           Letter Contracts, orders for services,
           Notices to Proceed, Alternative
           Technology Contracts, and lAGs
           with other Federal agencies. Also
           includes a 10-20% contingency.)
        Other Extramural Costs Not Funded From the RcriflnaJ Allowance:
           Total TAT, including multiplier costs
           Total NCLP
           Total ERT/REAC
        Subtotal, Extramural Costs

        Extramural Costs Contingency
         (20% of Subtotal, Extramural Costs; round to nearest thousand)

   TOTAL, EXTRAMURAL COSTS

   Intramnral Costs;
      Intramural Direct Costs
      Intramural Indirect Costs

   TOTAL, INTRAMURAL COSTS

   TOTAL, REMOVAL PROJECT CEILING
                                    $862,500
                                     $50,000
                                    $100,000
                                    $100.000

                                  $1,112,500


                                  +  $223.000

                                  $1335.500


                                     $9,900

                                    $18.000

                                    $27,900

                                  $1,363,400
Enforcement Addendum

Provide information on the following topics:
•   PRP search;
•   Notification of PRPs of potential liability and of
    the required removal action;
•   Decision whether to issue an order,
-   Negotiation and order issuance strategy.

Attachments

Append all attachments referred to in the body of the
Action Memo such as site maps ami pictures, ATSDR
documentation, previously approved Action Memos,
and the project schedule.
ACTION MEMOS FOR
ENFORCEMENT-LEAD ACTIONS

Action Memos must also be prepared for removal ac-
tions to be conducted by PRPs. These Action Memos,
however, do not need  to include estimated costs or
authorization for funding, and may be designated as
"Action Memo/Enforcement"

ACTION MEMOS FOR
SPECIAL CIRCUMSTANCES

The content of a basic Action Memo is modified in two
situations: when EPA determines at the beginning of a
response that an exemption to the statutory limits on
time and/or money will be needed, and to continue
removal actions already in progress. The approval of the

-------
Assistant Administrator for the Office of Solid Waste
and Emergency Response (AA, OSWER) is required for
all requests involving total expenditures over $2 mil-
lion. EPA Regional Administrators approve requests
for action totalling less than $2 million, as well as
exemptions to the 12-month limit

Combined Removal and Statutory
Exemption Requests

These Action Memos must provide the same informa-
tion described for the basic Action Memo, as well as
information demonstrating how site conditions meet the
CERCLA section 104(c) criteria for an exemption to the
time and dollar limits on removal actions.  This new
section, entitled "Exemption From Statutory Limits," is
placed immediately after the "Threats" section and uses
the threat information to justify either an:
   Emergency exemption (there is an immediate risk to
   public health or welfare or the environment; contin-
   ued  response actions  are immediately required to
   prevent, limit, or mitigate an emergency;  and assis-
   tance will not otherwise  be provided on a timely
   basis).
or a:
•  Consistency exemption (continued response actions
   are otherwise appropriate and consistent with the
   remedial action to be taken).

Action  Memos to Continue Response
Actions

Action Memos are occasionally required to continue
work approved by an original Action Memo, or to restart
work at the same site if the statutory limit on time has
been exceeded. The four basic types of requests are:
•  To extend a removal action beyond 12 months;
•  To increase the total project ceiling;
•  To increase the total project ceiling beyond
   $2 million;
•  To change the scope of response for the removal
   action.

Action Memos to continue response actions must cover
each of the categories required in the basic  Action
Memo outline, but may refer to the most recently ap-
proved Action Memo (which should be attached) in
order to avoid duplication.  If new or additional informa-
tion is available, it should be included in the appropriate
section of the new Action Memo.  For those Action
Memos requesting an exemption to the 12-month or $2
million limit, a section on "Exemption from Statutory
Limits" as described above should be  added.

SUPERFUND REMOVAL PROCEDURES
SERIES

The "Action Memorandum Guidance" is the first vol-
ume of  a ten-volume  series of guidance documents
collectively titled the "Superfund Removal Procedures".
These stand-alone volumes update and replace the single-
volume  "Superfund Removal Procedures" manual
(OSWER Directive 9360.0-3B), issued  in February,
1988.  Each volume  in  the series is dedicated to  a
particular aspect of the removal process and includes a
volume-specific Table of Contents, Reference List, and
Key Words Index. In  addition to the nine procedural
volumes listed in Figure 2, the series includes an Over-
view volume, containing a comprehensive Table of
Contents, List of Exhibits, Key Words Index, List of
Acronyms, and Glossary, for use as a quick reference.
The complete series of documents will be available in
1991. For further information on any volumes in the
series, contact the Superfund Removal Procedures se-
ries coordinator at (202) 382-4671.
                   FIGURE 2
         Volumes In Superfund Removal
               Procedures Series
  Overview

  The Removal Response Decision: Site Discovery to
    Response Decision

  Action Memorandum Guidance

  Response Management: Removal Start-up to Close-out

  Removal Enforcement Guidance for On-Scene
    Coordinators

  Public Participation Guidance for On-Scene Coordinators:
    Community Relations and the Administrative Record

  Removal Response Reporting

  Special Requirements

  Guidance on the Consideration of ARARs During
    Removal Actions

  State Participation

-------