EPA 450/5-80-002
                              CAPITAL

                        AND OPERATING COSTS

                     OF SELECTED AIR POLLUTION

                          CONTROL  SYSTEMS
                                by

                           R.  B.  Neveril

                            GARD, INC.
                     7449 North  Natchez  Avenue
                       Niles,  Illinois 60648

                      Contract No. 68-02-289S
        EPA Project Officer:   Frank  Bunyard/Winiam Vatavuk

                           Prepared  for

                  ENVIRONMENTAL PROTECTION AGENCY
                Office of Air and Waste Management
           Office of Air Quality Planning and Standards
           Research Triangle  Park, North Caroline 27711
                          December,  1978

-------
                                 NOTICE
This report was furnished to the Environmental  Protection Agency by GARD, INC.,
Niles, Illinois in fulfillment of Contract No.  68-02-2899.  The contents of
this report are reproduced herein as received from the contractor.   The
opinions, findings, and conclusions expressed are those of the author and not
necessarily those of the Environmental  Protection Agency.   Mention  of company
or product names is not to be considered as  an  endorsement by the Environmental
Protection Agency.

-------
                            TABLE OF CONTENTS
Section
  2

  3
  4
  6

  7



  APPENDIX

  APPENDIX

  APPENDIX-

  APPENDIX

  APPENDIX
  LIST OF TABLES

  LIST OF FIGURES

  INTRODUCTION
  1.1  Purpose of Manual
  1.2  Organization of Manual

  APPLICATION TO INDUSTRY

  COST ESTIMATING PROCEDURES
  3.1  Capital Costs
       3.1.1  Purchased Equipment Costs
       3.1.2  Installation Costs
  3.2  Annualized Costs
       3.2.1  Direct Operating Costs
       3.2.2  Indirect Operating Costs

  AUXILIARY EQUIPMENT
  4.1  Capture Hoods
  4.2  Ducting
  4.3  Gas Conditioning
  4.4  Pollutant Removal and Treatment (Dust)
  4.5  Ancillary Equipment (cooling  towers, pumps)
  4.6  Fans
  4.7  Stacks

  CONTROL DEVICES
  5.1  High Voltage Electrostatic Precipitators
  5.2  Venturi Scrubbers
  5.3  Fabric Filters
  5.4  Thermal and Catalytic Incinerator Systems
  5.5  Adsorbers
  5.6  Absorbers
  5.7  Refrigeration
  5.8  Flares

  SAMPLE COST ESTIMATES AND SYSTEM COST COMPARISON

  UPDATING COSTS TO FUTURE TIME PERIODS
  7.1  General
  7.2  Equipment Cost Updating Procedures

A  COMPOUND INTEREST FACTORS

B  EQUIPMENT COST INDEXES

C  GUIDE TO REFERENCES TO THE INDUSTRIES

D  GUIDE TO ASSOCIATIONS FOR THE INDUSTRIES

E  CONVERSION FACTORS TO SI MEASUREMENTS
 1-1
 1-1
 1-2

 2-1

 3-1
 3-2
 3-5
 3-9
 3-10
 3-13
 3-18

 4-1
 4-2
 4-15
 4-29
 4-44
 4-47
 4-57
 4-67

 5-1
 5-1
 5-9
 5-19
 5-31
 5-39
 5-50
 5-65
 5-72

6-1

 7-1
 7-1
 7-6
                                     ii

-------
                             LIST OF TABLES

TABLE                                                                  PAGE
NUMBER                                                                NUMBER
 2.1         INDUSTRY POLLUTANT SOURCES AND TYPICAL                    2-4
              CONTROL DEVICES

 2.2         DESIGN PARAMETERS FOR RESPECTIVE INDUSTRIES               2-10
              FOR HIGH EFFICIENCY PERFORMANCE

 2.3         EFFICIENCY OF CARBON ADSORPTION AND LEL'S                 2-11
              FOR COMMON POLLUTANTS

 3.1         CAPITAL COSTING                                           3-3

 3.2         COST ADJUSTMENTS                                          3-7

 3.3         CAPITAL COST SUMMARY                                      3-11

 3.4         BASIS FOR ESTIMATING ANNUALIZED COSTS                     3-12

 3.5         ESTIMATED LABOR HOURS PER SHIFT                           3-14

 3.6         GUIDELINES FOR PARTS AND EQUIPMENT LIFE                   3-16

 4.1         MINIMUM VELOCITIES AND VENTILATION RATES                  4-7
              FOR LOW CANOPY HOODS

 4.2         MATERIAL COSTS                                            4-14

 4.3         REFRACTORY ESTIMATING COSTS                               4-25

 4.4         DEFINITIONS FOR COOLING TOWER                             4-50

 4.5         PRICE ADJUSTMENT  FACTORS FOR WET-BULB                     4-50
              TEMPERATURES

 4.6         PRICE ADJUSTMENT  FACTORS FOR APPROACH AT                  4-50

 4.7         MOTOR RPM SELECTION GUIDE                                 4-62

 4.8         PRICING FACTORS FOR OTHER MOTOR TYPES                     4-62

 4.9         MOTOR TYPE SELECTION                                      4-62

 4.10        FAN SIZING FACTORS: AIR DENSITY RATIOS                    4-63

 5.1         BAG PRICES                                                5-32

 5.2         APPROXIMATE GUIDE TO ESTIMATE GROSS CLOTH                 5-32
              AREA
                                      iii

-------
                             LIST OF TABLES
TABLE                                                                    PAGE
NUMBER                                                                 NUMBER
 5.3         TECHNICAL ASSUMPTIONS FOR ESTIMATION OF                    5-48
              DIRECT OPERATING COSTS

 5.4         MINIMUM SHELL THICKNESS AT AMBIENT                         5-63
              TEMPERATURE

 5.5         COST OF TOWER PACKING                                      5-63

 5.6         ADDITIONAL COSTS FOR FABRICATOR'S                          5-64
              ENGINEERING, PURCHASING, ADMINISTRATION
              AND PROFIT
                                    IV

-------
                             LIST OF FIGURES
FIGURE                                                                  PAGE
NUMBER                            TITLE                                NUMBER
 4-1         CONTROL SYSTEM FLOW CIRCUIT                                4-3

 4-2         LOW CANOPY HOODS FOR COLD PROCESSES                        4-6

 4-3         RECTANGULAR CANOPY HOOD PLATE AREA                         4-10
              REQUIREMENTS VS. HOOD LENGTH AND L/W

 4-4         CIRCULAR HOODS PLATE REQUIREMENTS                          4-11

 4-5         LABOR COST FOR FABRICATED 10 GA. CARBON                    4-12
              STEEL RECTANGULAR CANOPY HOODS

 4-6         LABOR COST FOR FABRICATED 10 GA. CARBON                    4-13
              STEEL CIRCULAR CANOPY HOODS

 4-7         CARBON STEEL STRAIGHT DUCT FABRICATION                     4-19
              PRICE PER LINEAR FOOT VS. DUCT DIAMETER
              AND PLATE THICKNESS

 4-8         STAINLESS STEEL STRAIGHT DUCT FABRICATION                  4-20
              PRICE PER LINEAR FOOT VS. DUCT DIAMETER
              AND PLATE THICKNESS

 4-9         WATER COOLED CARBON STEEL STRAIGHT DUCT                    4-21
              FABRICATION PRICE PER FOOT VS. DUCT
              DIAMETER

 4-10        CARBON STEEL ELBOW DUCT RRICE VS. DUCT                     4-22
              DIAMETER AND PLATE THICKNESS

 4-11        STAINLESS STEEL ELBOW DUCT PRICE VS. DUCT                  4-23
              DIAMETER AND PLATE THICKNESS

 4-12        CARBON STEEL EXPANSION JOINT COSTS VS.                     4-24
              DUCT DIAMETER

 4-13        CARBON STEEL RECTANGULAR DAMPER PRICES                     4-27
              VS. AREA FOR L/W = 1.3

 4-14        CARBON STEEL CIRCULAR DAMPER PRICES VS.                    4-28
              DIAMETER

 4-15        CAPACITY ESTIMATES FOR MECHANICAL                          4-31
              COLLECTORS

 4-16        CRITICAL PARTIAL SIZE ESTIMATES FOR                        4-32
              MECHANICAL COLLECTORS

 4-17        MECHANICAL COLLECTOR PRICES FOR CARBON                     4-33
              STEEL CONSTRUCTION VS. INLET AREA

-------
                             LIST OF FIGURES
FIGURE                                                                   PAGE
NUMBER                            TITLE                                NUMBER


 4-18        MECHANICAL COLLECTOR PRICES FOR STAINLESS                   4^34
              STEEL CONSTRUCTION VS. INLET AREA

 4-19        MECHANICAL COLLECTOR SUPPORT PRICES VS.                     4-35
              COLLECTOR INLET AREA

 4-20        MECHANICAL COLLECTOR DUST HOPPER PRICES                     4-36
              FOR CARBON & STAINLESS STEEL CONSTRUCTION
              VS. COLLECTOR INLET AREA

 4-21        MECHANICAL COLLECTOR SCROLL OUTLET PRICES                   4-37
              FOR CARBON & STAINLESS STEEL CONSTRUCTION
              VS. COLLECTOR INLET AREA

 4-22         FABRICATED 40 FT HIGH "U" TUBE HEAT EXCHANGER             4-39
              PRICES WITH HOPPERS AND MANIFOLDS
 4-23         SPRAY CHAMBER COST VS. INLET GAS NOLUME                   4-41

 4-24         QUENCHER COSTS VS. INLET GAS VOLUME                       4-43


 4-25        PRICES FOR FABRICATED CARBON STEEL DILUTION                4-45
              AIR PORTS VS.  DIAMETER AND PLATE THICKNESS

 4-26        PRICES FOR SCREW CONVEYORS VS.  LENGTH  AND                  4-46
              DIAMETER

 4-27        PRICES FOR INSTALLED COOLING TOWERS FOR                    4-48
              UNITS OF CAPACITY < 1000 TONS

 4-28        PRICES FOR INSTALLED COOLING TOWER BASED ON                4-49
              WET-BULB TEMPERATURE = 82°F AND APPROACH
              =  10°F

 4-29        CAST IRON, BRONZE FITTED,  VERTICAL TUBINE                  4-53
              WET SUMP PUMP  PRICES FOR 3550  RPM

 4-30        CAST IRON, BRONZE FITTED,  VERTICAL TURBINE                 4-54
              WET SUMP PUMP  PRICES FOR 1750  RPM

 4-31         CAST IRON, BRONZE FITTED,  VERTICAL TURBINE                 4-55
              WET SUMP PUMP  PRICES FOR 1170  RPM

 4-32        PUMP MOTOR HP  VS.  CAPACITY AND  HEAD FOR                     4-66
              VERTICAL TURBINE PUMPS

 4-33        BACKWARDLY CURVED FAN PRICES VS.  CLASS, CFM                 4-59
           '   AND AP FOR ARRANGEMENT NO.  1
                                      VI

-------
                             LIST OF FIGURES

FIGURE                                                                  PAGE
NUMBER                            TITLE                                NUMBER


 4-34        BHP,  FAN RPM AND MOTOR AND STARTER PRICES                  4-61
              VS.  AP AND CFM

 4-35        FAN INLET AND OUTLET DAMPER PRICES AS A                    4-65
              FUNCTION OF CFM AND AP

 4-36        V-BELT DRIVE PRICES                                        4-66

 4-37        RADIAL FAN PRICES VS. SCFM AND AP FOR                      4-68
              ARRANGEMENT NO. 1

 4-38        FAN RPM AND MOTOR BHP FOR RADIAL FANS                      4-69

 4-39        RADIAL TIP FAN PRICES                                      4-70

 4-40        STARTER AND MOTOR PRICES FOR VENTURI                       4-71
              SCRUBBER APPLICATIONS (HIGH PRESSURE,
              HIGH BHP)

 4-41        FABRICATED CARBON STEEL STACK PRICE VS.                    4-73
              STACK HEIGHT & DIAMETER FOR 1/4 INCH
              PLATE

 4-42        FABRICATED CARBON STEEL STACK PRICE VS.                    4-74
              STACK HEIGHT & DIAMETER FOR 5/16 & 3/8
              INCH PLATE
                                                       S
 4-43        PRICES FOR TALL STEEL STACKS, INSULATED                    4-75
              AND LINED

 5-1         ELECTROSTATIC PRECIPITATOR CONTROL SYSTEM                  5-5

 5-2         DRY TYPE  ELECTROSTATIC PRECIPITATOR PURCHASE               5-7
              PRICES VS.  PLATE AREA

 5-3         VENTURI SCRUBBER  CONTROL SYSTEMS                           5-12

 5-4         1/8 INCH  THICK  CARBON STEEL  FABRICATED                     5-13
              SCRUBBER PRICE VS.  VOLUME

 5-5         METAL THICKNESS REQUIRED VS. VOLUME AND                    5-14
              DESIGN PRESSURE

 5-6         PRICE ADJUSTMENT  FACTORS VS. PLATE THICKNESS               5-15
              AND VOLUME

 5-7         SCRUBBER  INTERNAL SURFACE AREA AND SEPARATOR               5-16
              DIAMETER AND HEIGHT VS. WASTE INLET GAS
              VOLUME
                                      vii

-------
                             LIST OF FIGIRES
FIGURE                                                                  PAGE
NUMBER                            TITLE                                NUMBER

 5-8         INTERNAL GAS COOLER BUBBLE TRAY COST VS.                    5-17
              SEPARATOR DIAMETER
 5-9         FABRIC FILTER CONTROL SYSTEMS                              5-25
 5-10        INTERMITTENT, PRESSURE, MECHANICAL SHAKER                  5-26
              BAGHOUSE VS. NET CLOTH AREA
 5-11        CONTINUOUS,  SUCTION OR PRESSURE,  PULSE JET                 5-27
              BAGHOUSE PRICES VS.  NET  CLOTH AREA
 5-12        CONTINUOUS,  PRESSURE, MECHANICAL  SHAKER                    5-28
              BAGHOUSE PRICES VS.  NET CLOTH  AREA
 5-13        CONTINUOUS,  PRESSURE, RESERVE AIR BAGHOUSE                 5-29
              PRICES VS.  NET CLOTH AREA
 5-14        CUSTOM PRESSURE OR SUCTION BAGHOUSE PRICES                 5-30
              VS.  NET CLOTH AREA
 5-15        PRICES FOR THERMAL INCINERATORS WITHOUT                    5-36
              HEAT EXCHANGERS
 5-16        PRICES FOR THERMAL INCINERATORS WITH  PRIMARY                5-37
              HEAT EXCHANGER
 5-17        CATALYTIC INCINERATOR PRICES                                5-38
 5-18        ADSORPTION ISOTHERM FOR TOLUENE                             5-43
 5-19        PRICES FOR PACKAGED STATIONARY BED CARBON                   5-45
             ADSORPTION UNITS WITH STEAM REGENERATION
 5-20        PRICES FOR CUSTOM CARBON ADSORPTION UNITS                   5-46
 5-21        FABRICATED COST OF CARBON STEEL VESSEL                      5-58
 5-22        SKIRT AND SUPPORT COSTS  FOR CARBON STEEL VESSEL             5-59
 5-23        COST  OF NOZZLES                                            5-60
 5-24        COST  OF TRAY,  SUPPORT PLATE OR  DISTRIBUTOR                 5-61
 5-25        CASCADE REFRIGERATION SYSTEM  FOR  VAPOR  RECOVERY             5-67
 5-26        REFRIGERATION VAPOR RECOVERY  UNITS                         5-70
 5-27        INSTALLED COST OF INDUSTRIAL  VAPOR COMPRESSION              5-73
             REFRIGERATION SYSTEMS
 5-28        COST  OF ELEVATED FLARES                                     5-77
 5-29        COST  OF GROUND LEVEL  FLARES                                5-78
                                     viii

-------
                             LIST OF FIGURES
FIGURE                                                                 PAGE
NUMBER                            TITLE                               NUMBER

 6-1          FABRIC FILTER SYSTEM DESIGN                               6-4
 6-2          ELECTROSTATIC PRECIPITATOR SYSTEM DESIGN                  6-12
 6-3          VENTURI SCRUBBER SYSTEM DESIGN                            6-17
 7-1          CHEMICAL ENGINEERING PLANT COST INDEX                     7-3
                                      ix

-------
                                Section  1
                              INTRODUCTION

 1.1   Purpose  of Manual
      One  of the aims  of  the U.S.  Environmental  Protection Agency  (EPA)  is  to
 provide guidelines  and technical  assistance to  state and local  regulatory
 agencies  responsible  for controlling air pollution.  The purpose  of  this manual
 is to assist  those  agencies in  estimating the cost of air pollution  control
 systems for various manufacturers and processors who must comply with existing
 and future standards  or  codes.  At present, literature is available  which  gives
 generalized cost data for control systems based on industry averages.  However,
 there is  a wide range of magnitude in the cost data due to the variety of
 installations..  In some cases,  the cost of the control  device itself may only
 represent 25 percent of the total capital costs while in other cases, it may
 be as high as 90 percent.  These differences can be attributed to the cost
 of auxiliary equipment, method of controlling the source (direct exhaust or
 canopy hood, etc.), physical  location of control equipment with respect to
 the source, local code requirements, characteristics of gas stream, plant
 location,  and many other influencing factors.   In preparing this manual, the
 main objective was to identify the individual  component costs so that realistic
 system cost estimates can be  determined for any specific application based on
 the peculiarities of the system.
     In addition to capital  costs, methods  for estimating the operating and
maintenance costs are provided for each type of control  system so  that
annualized costs can be estimated.
                                      1-1

-------
1.2  Organization of Manual
     The cost estimating procedures and cost curves in this manual are provided
for those systems utilizing the following control devices:
     1)  High voltage electrostatic precipitators
     2)  Venturi scrubbers
     3)  Fabric filters
     4)  Thermal and catalytic incinerators
     5)  Adsorbers
     6)  Absorbers
     7)  Refrigeration
     8)  Flares
     In Section 2, a list of the design parameters for the various control
devices is provided and crossreferenced to the applicable industries and
pollutant sources that use these systems.  Section 3 describes the procedures
used in estimating the capital and annualized costs of these systems.  A
description of the operation and basic cost curvesVor these control devices
and the auxiliary equipment required in a completely integrated pollution
control system is presented in Sections 4 and 5.   This description outlines
the various design options available to the engineer and the impact these
options have on the total system cost.  These data represent equipment costs
based on a reference date of December, 1977 and are estimated to be accurate
to ± 20 percent, on a component basis, except where noted.  In Section 6, an
example is provided of a typical application which can be controlled by each
one of three possible particulate control devices.  However, the methods and
procedures, demonstrated in the example, are applicable to all industries where
the control of emissions uses one or more of these eight control systems.  A
method of extrapolating the costs to a future date is discussed in Section 7.
                                       1-2

-------
                                Section 2
                         APPLICATION TO INDUSTRY
     None of these eight control systems can be applied universally  throughout
 the  various industries.  For instance, adsorbers, absorbers and refrigeration
 are  effective only with gaseous pollutants while thermal and catalytic  inciner-
 ators require combustible particulates or vapors for proper operation.  Non-
 combustible particulate-laden gas streams must be controlled by precipitators,
 scrubbers, or fabric filters.  Precipitators and fabric filters are  used solely
 for  particulate collection while scrubbers may be used for both particulates
 and  gases (when used as a contactor/absorber).  The selection of a control
 system for a particular process, therefore, may be limited to only one or two
 types of control devices.  Table 2.1 lists industries with typical sources of
 pollutants and applicable control  devices that are used to control these
 emissions.
     In some cases, a control device may be compatable with the process but
 not  selected due to the particular plant location or cost of utilities.  For
 instance, the potentially high cost of maintenance and repair for damage due
 to freezing with scrubber systems  may preclude the use of these systems in
 some colder northern states.   The  high use of electrical  power and utilities
 associated with venturi scrubbers  would make these systems less attractive in
 areas where water is scarce or electrical  power is costly.   Combustion processes
 such as those that occur in flares and incinerators  may present safety hazards
 in some areas.
     Product recovery is possible  with all  of the control  devices  with the
 exception of flares and incinerators which chemically dispose of the pollu-
tants.   In many cases,  the  recovered product must be further treated to produce
a reuseable item,  particularly with scrubbers which  may replace an air
                                       2-1

-------
pollution problem with a water pollution problem if waste water treatment is
not incorporated into the system.
     Typical design parameters for the collection of particulates with, fabric
filters, venturi scrubbers, and precipttators are shown in Table 2.2.  These
represent the normal range of air-to-cloth ratios, venturi pressure drops, and
drift velocities associated with those control systems used in the collection
of parti oil ate pollutants from industries listed.
     For gaseous pollutants, the design parameters are specifically related to
the physical and chemical characteristics of the pollutant and the concentration
of the pollutant in the gas stream.  In the adsorption process, the concentra-
tion of pollutants is generally below the lower explosive limit and gas streams
are usually at atmospheric pressure where vapor pressures of pollutants are
low.  An adsorbent such as activated carbon is ideally suited for these
conditions in controlling hydrocarbon emissions from spray booths, printing
presses, and processes involving the evaporation of solvents.  The design
parameters for a carbon adsorber would therefore^depend on the adsorption
efficiencies of carbon.  Table 2.3 lists the types of solvents and the lower
explosive limit that might be expected in the exhaust gases from such sources.
The adsorption efficiency listed for each solvent provides the engineer with
the general range of adsorbent capacities required for sizing the control
device at the specified concentrations.
     The primary concept in designing an absorber is to provide the maximum
contact between the gas or solute and the liquid solvents since the rate of
mass transfer between the two is dependent on exposed surface.  The design para-
meters will depend on both the solubility of the gas in the solvent and the
inlet concentration.  Once the constituents and operating conditions are
defined, several different types of absorbers and some scrubbers, can be
                                       2-2

-------
 selected.  Preliminary design data and operating parameters for these systems
 are found in Sections 4 and 5 and in references 88 and 146.
     The chemical and physical properties of the pollutant are most important
 when refrigeration is used as a means of collection and removal.  The vapor
 pressure/temperature relationship for hydrocarbons and other constituents
 typically found in commercial  and industrial gas streams is provided in
 references 88, 146 and 147.
     Appendix C is a crossreference of literature information applicable to
each industry.   Appendix D lists trade associations related to industries
where additional information may be obtained.
                                      2-3

-------
Table 2.1   INDUSTRY POLLUTANT SOURCES AND TYPICAL CONTROL DEVICES
INDUSTRY
Asphalt Roofing
Basic Oxygen Furnaces
Benzene Handling &
Storage
Brick Manufacturing
Castable Refractories
Chemical ManufactuHm
Waste Disposal
Clay Refractories
Coal -fired Boilers
Conical Incinerators
Cotton Ginning
Degreasing
SOURCE
1) Saturator and
storage tanks
1) Basic oxygen furnace
2) Charging hood
1) Vents, storage
tanks
1) Tunnel kiln
2 Crusher, mill
3 Dryer
4) Periodic kiln
1 Electric arc
2 Crusher, mill
3 Dryer
4) Mold and shakeout
1) Miscellaneous
sources
1) Shuttle kiln
2) Calciner
3) Dryer
4) Crusher, mill
1) Steam generator
1) Incinerator
1) Incinerator
1) Degreaser tank
CONTROL SYSTEM
1) Scrubber,
preclpltator,
afterburner
1) Preclpltator,
scrubber, bag house
2) Same as 1
1) Afterburners,
adsorbers,
refrigeration
1) Scrubber, baghouse
precipitator
2) Baghouse, scrubber
3) Same as 1
4) Same as 1
1 Baghouse, scrubber
2 Same as 1
3 Same as 1
4 Same as 1
1 ) Afterburners ,
flares
1) Baghouse, precipi-
tator, scrubber
2) Same as 1
3) Same as 1
4) Baghouse, precipi-
tator
1) Preclpltator,
scrubber, baghouse
1) Scrubber
1 Scrubber
1) Adsorber,
refrigeration
CAPTURE DEVICE
1 ) Canopy hood and
direct exhaust
1) Full -canopy hood
2) Canopy hood
1) Direct exhaust
1) Direct exhaust
2) Canopy hood
3) Same as 1
4) Same as 1
1 Direct exhaust
2 Canopy hood
3 Direct exhaust
4 Canopy hood
1) As required
1 Direct exhaust
2 Same as 1
3) Same as 1
4) Canopy hood
1 Direct exhaust
1) Direct exhaust
1) Direct exhaust
1) Slot or canopy hood
TYPICAL GAS FLOW
DESIGN RATE
1) 10,000-20,000 cfm
Per saturator hood
handling a 36" wide
roll at line speeds
of up to 500 fpm
1) Function of lance
rate and hood
design
2) 300 fpm hood face
1) As required
1) Combustion air fan
capacity
2) 250 fpm hood face
3) Same as 1
4) Same as 1
1 Infilt. air
2 250 fpm hood face
3 Fan capacity
4 Same as 2
1) As required
1) Fan capacity
2) Same as 1
3) Same as 1
4) 250 fpm hood face
1) Induced draft fan
capacity
1) Combustion air rate
1) Combustion air rate
1 50 cftn/ft open area
TYPICAL GAS
TEMPERATURE
1) 80-300F
1 ) 3500-4000F
2) 150-400F
1) 70-1 OOF
1 ) 200-600F
2) 70F mill
3} 250F
4) Same as 1
1 3000-4000F
2 70F
3 300F
4) 150F
1) As required
1 150-800F kiln
2 Same as 1
3) 250F
4) 70F
1) 300F-700F
1) 400-700F
1 500- 7 OOF
1 70F

-------
                                                                              Table 2.1  (Continued)
INDUSTRY
Detergent
Manufacturing
Direct Fjring of Meat
Distilled Whiskey
Processing
Dry Cleaning
Electric Arc
Furnaces
Feed Mills
Ferroalloy Plants
a) HC Fe Mn
b) 50% Fe Si
c) HC Fe Cr
Gasoline Bulk
Terminals & Storage
Glass Manufacturing
Graphic Arts
SOURCE
1) Spray dryer
1) Smokehouse
1) Distillation
process
1) Washer, extractor,
tumbler
1) Arc furnace
2) Charging and
tapping
1) Storage bins
2) Mills/grinders
3) Flash dryer
4 ) Conveyors
1) Submerged arc
furnace (open)
2) Submerged arc
furnace (closed)
3) Tap fume
1) Vents, storage
tanks
1) Regenerative tank
furnace
2) Weight hoppers and
mixers
1) Presses
2) Lithographies, meta
decorating ovens
CONTROL SYSTEM
1) Scrubber, baghouse
1 ) Afterburners ,
electrical
precipitators
1) Adsorbers,
afterburners
1) Adsorber
1) Baghouse, scrubber,
precipitator
2) Same as 1
1) Baghouse, scrubber
2} Same as 1
3) Same as 1
4) Same as 1
1) Scrubber, baghouse,
precipitator
2) Scrubber
3) Same collector or
baghouse
1) Afterburners,
adsorbers,
refrigeration
1) Baghouse, scrubber
precipitator
2) Same as 1
1 ) Adsorbers ,
afterburners
2) Afterburners
CAPTURE DEVICE
1) Direct exhaust
1) Direct exhaust
1) As required
1) Direct exhaust
1) Direct exhaust,
full /side draft hood
2) Canopy hood
1) Direct exhaust
2) Canopy hood
3) Direct exhaust
4) Canopy hood
1) Full or canopy hood
2) Direct exhaust
3) Canopy
1) Direct exhaust
1) Direct exhaust
2) Canopy
1 ) Hoods
2) Hoods
TYPICAL GAS FLOW
DESIGN RATE
1) Fan capacity
1) 1-4 cfm/sf floor area
1) As required
1) Fan capacity
1) Function of lance
rate and hood design-
up to 200,000 acfm
2) 250 fpm hood face
1) 250 fpm canopy hood
face velocity
2) Same as 1
3) Air heater flow rate
(dryer)
4) Same as 1
1) 2500-5500 scfm/mw
with scrubber
2) a) 220 scfm/mw
b) 180 scfm/mw
c) 190 scfm/mw
3) 200 cf in/ft/
1) As required
1) Fan capacity
2) 200 fpm/ft2
1) 3,000-11,000 cfm/ press
2} 3,000-60,000 cfm/oven
TYPICAL GAS
TEMPERATURE
1) 180-250F
1) 120-150F
1 ) As requ i red
1) 70F
1) 3000F (direct
exhaust)
2) 150F (canopy)
1) 70F
2) 70F
3) 170-250F
4) 70F
1) 400-500F open arc
2) 1000-1200F
closed arc
3) 150F hood
1) 70-100F
1) 600-850F furnace
2) 100F mixers
1) 100F
2) 400-600F
ro
 i
in

-------
                                                                               Table 2.1  (Continued)
INDUSTRY
Gray Iron Foundries
Industrial & Utility
Boilers
Insulation Mire
Varnish
Iron Ore
Benefication
Iron & Steel
(Sintering)
Kraft Recovery
Furnaces
Lime Kilns
Maleic Anhydride
Miscellaneous
Refinery Sources
SOURCE
1) Cupola
2) Electric arc furnace
3) Core oven
4) Shakeout
1) Boiler
1) Spray booths
2) Flow coating
machines
3) Dip tanks
4) Roller coating
machines
1) Crusher
2) Sinter machine
1) Sinter machine
a) Sinter bed
b) Ignition fee.
c) Wind boxes
z) a) sinter crusher
b) Conveyors
c ) Feeders
1) Recovery furnace
and direct contact
evaporator
1) Vertical kilns
2) Rotary sludge kiln
1) Benzene storage
tanks, process vent
& Vac. refin. vent
1) Vents, storage
tank, etc.
CONTROL SYSTEM
1) Afterburner-baghouse
for closed cap,
Af terburner-prec 1 pi -
tator for closed cap
scrubber
2) Bag house, scrubber
pr eel pi tator
3) Afterburner
4) Bag house
1) Precipitator,
baghouse
1) Adsorbers, absorbers,
afterburners
2) Same as 1
3) Same as 1
4) Same as 1
1) Baghouse, scrubber
2) Same as 1
1) Precipitator,
baghouse, scrubber
2) Baghouse, scrubber
S
1) Precipitator,
scrubber
1) Baghouse, scrubber,
precipltator
2) Scrubber, precipi-
tator
1) Adsorbers, after-
burners
1) Afterburner, flare
adsorbers, absorbers
refrigeration
CAPTURE DEVICE
1) Direct exhaust
2) Direct exhaust, full/
side draft hood
3) Direct exhaust
4) Full/side draft hood
1) Direct exhaust
1) Direct exhaust
2) Exhaust hood
3) Exhaust hood
4) Exhaust hood
1) As required
2) As required
1) Down draft hood
2) Canopy hood
1) Direct exhaust
1) Direct exhaust
2) Direct exhaust
1) Direct exhaust
1) As required
TYPICAL GAS FLOW
DESIGN RATE
1) Tuyere air
+ Infll. door air
+ afterburner
second air
2) 2000 cfm/ft2 hood
opening
3) Fan capacity 9
4) 200-500 cfm/ft hood
1) Fan capacity
1) 100-150 cfm/ft2
booth opening
1) As required
2) As required
1) Based on bed size
2) 250 fpm hood face
1) Primary and
secondary air supply
capacity
1) Combustion air
rate
2) Combustion air
rate
1) As required
1) As required
TYPICAL GAS
TEMPERATURE
1) 1200-2200F
2) -2500F direct exh.
-400F hood
3) 150F
4) -150F
1) 250-800F
1) 100F
1) As required
2) As required
1 ) 150-400F
sinter machine
2) 70F conveyors
1) 350F
1) 200-1200F
2) 200-1200F
1) 70-100F
1) As required
ro
i
en

-------
Table 2.1 (Continued)
INDUSTRY
Municipal Incinerator
Non-Metatllc
Minerals Industry
Onshore Crude 011
Production
Organic Chemicals
Paint Manufacturing
Petroleum Catalytic
Cracking
Petroleum Storage
Pharmaceuticals
Phosphate
Fertilizer
Phosphate Rock
Crushing
SOURCE
1) Incinerator
1) Miscellaneous
sources
1) Vents, storage tanks
1) Miscellaneous
sources
1) Varnish kettles
1) CO boiler from FCC
1) Vents, storage
tanks
1) Reactor
2) Crystal Hzer
3) centrifuge
4) Filter, dryer
5) Dlst. column
1) Digester vent air
2) Filters
3) Sumps
1) Crusher & screens
2) Conveyor
3) Elevators
4) Fluldlzed bed calci-
ner, grinder & dryer
CONTROL SYSTEM
1) Scrubber, preclpl-
tator, baghouse,
afterburner
1} Scrubbers, baghouse
1) Adsorbers, after-
burners, refrlgeratlor
1) Scrubbers, adsorbers,
absorbers, refrigera-
tion flares
1 ) Afterburners
1) Predpltator
1 ) Afterburners ,
adsorbers,
refrigeration
1) Adsorbers, refrigera-
tion, Incineration
2) Sajne as 1
3) Same as 1
4) Same as 1
5) Same as 1
1 Scrubber, baghouse
2 Same as 1
3 Same as 1
1} Baghouse, scrubber,
preclpltator
2) Same as 1
3) Same as 1
4) Same as 1
CAPTURE DEVICE
1) Direct exhaust
1) As required
1) As required
1) As required
1) Exhaust hood
1) Direct exhaust
1) Direct exhaust
1) Direct exhaust
2) Direct exhaust
3) Direct exhaust
4) Direct exhaust
5) Direct exhaust
1) Hood
2) Sane as 1
3) Same as 1
1) Canopy hood
2) Same as 1
3) Same as 1
4) Direct exhaust
TYPICAL GAS FLOW
DESIGN RATE
1) Combustion air fan
capacity where
applicable
1) As required
1) As required
1) As required
1) 100-300 cfm/200-375
gal. Kettle
1) Regeneration air
rate + boiler
combustion air
1) As required
1) 50-300 scfm
2) 50-300 scfm
3) 10-50 scfm
4) 10-800 scfm
5) 500-900 scfm
1) Process stream rate
2) Same as 1
3) Same as 1
1) 350 cfm/ft belt width
at speeds ~200 fpm
500 cfm/ft belt width
at speeds ~200 fpm
2) 100 cfm/ft of casing
cross-section
(elevator)
50 cfm/ft of screen
area
3) Combustion air rate
4) Blower rate
TYPICAL GAS
TEMPERATURE
1) 500-700F
1) As required
1) 70-100F
I) As required
1) 500F
1 ) 500F
1) 70-100F
1) As required
2) As required
3) As required
4) As required
5) As required
1) 150F
2) Same as 1
3) Same as 1
1) 70F hoods
2) Same as 1
3) Same as 1
4) 600-1500F calciner

-------
                                                                               Table 2.1  (Continued)
INDUSTRY
Poly vinyl Chloride
Production
Portland Cement
Primary Copper, Lead,
Z1nc Smelters
Pulp and Paper
Refuse Waste Disposal
Rubber Products
(Tires)
Secondary Aluminum
Secondary Copper
Smelters
Service Stations
SOURCE
1) Process equipment
vents
1) Rotary Mln
a) Wet
b) Dry
2) Crushers and
conveyors
3) Dryers
1) Roaster, converter
1) Flu1d1zed bed
reactor
1 ) Furnace
1) Rubber mill and
mixers
1) Reverbatory furnace
2) El. Induction
furnace
3) Crucible furnace
4) Chlorinating station
5) Dross processing
6) Sweating furnace
1 ) Reverbatory
furnace
2) Crucible furnace
3) Cupola & blast
furnace
4 ) Converters
5. El. Induction
furnaces
1) Loading rack
CONTROL SYSTEM
1 ) Adsorbers ,
afterburners
1) Predpltators,
baghouses
2) Baghouses
3) Predpltators,
baghouses
1) Preclpltator,
scrubber, absorber
1) Scrubber
1 ) Afterburner
1) Baghouse
1) Scrubber (low energy)
+ baghouse,
preclpltator
2) Same as 1
3) Same as 1
4) Same as 1 *
5) Same as 1
6) Same as 1
1) Baghouse, scrubber,
preclpltator
2) Same as 1
3) Same as 1
4) Same as 1
5) Same as 1
1 ) Adsorbers ,
refrigeration
CAPTURE DEVICE
1) Direct exhaust
1) Direct exhaust
2) Canopy hoods
3) Direct exhaust
1) Direct exhaust
1) Direct exhaust
1) Direct exhaust
1) Canopy hood
1) Canopy hood (hearths)
direct exhaust
2) Same as 1
3) Same as 1
4) Same as 1
5) Same as 1
6) Same as 1
1) Direct exhaust,
canopy hood, full
hood
2) Same as 1
3) Same as 1
4) Same as 1
5) Same as 1
1) Balanced system/
direct exhaust
TYPICAL GAS FLOW
DESIGN RATE
1) Process gas stream
rate
1) Combustion air rate
where applicable
2) 250 fpm hood face
3) Same as 1
1) As required
1) Combustion air rate
1) As required
1) 100 fpm through face
1) Max. plume vol .
+ 20% (hearths)
2) Infiltrated air
3) Sane as 2
4) Sajne as 2
5) Same as 2
6) Same as 2
1) 200 fpm/ft2
canopy hood
2) Max. plume vol. + 20%
3) 1800 fpm Infiltrated
air (full hood)
4) Based on type capture
5) Same as 4
1) Loading flow rate
TYPICAL GAS
TEMPERATURE
1) -15 to 130F
1) 150-850F kilns
2) 70F crushers and
conveyors
3) 200F dryers
1) As required
1) 600-1500F
1) 500-700F
1) 70F
1) 1600F fluxing,
600F holding
hearth
2) Based on type
capture
3} Same as 2
4) Same as 2
b) Same as 2
6) Same as 2
1) 2500F direct tap
2) Based on type
capture
3) Same as 2
4) Same as 2
5) Same as 2
1) 70-1 OOF
ro
 i
CD

-------
                                                                                Table 2.1 (Continued)
INDUSTRY
Sewage Sludge
Incinerators
Surface Coatings -
Spray Booths
Vegetable 011
Processing
SOURCE
1) Multiple hearth
Incinerator
2) Flu1d1zed bed
Incinerator
1) Spray booth
1} Solvent extraction
process
CONTROL SYSTEM
1) Scrubber
2) Same as 1
1 ) Adsorber ,
afterburner
1) Adsorbers, scrubbers
CAPTURE DEVICE
1) Direct exhaust
2) Same as 1
1) Canopy hood
1} As required
TYPICAL GAS FLOW
DESIGN RATE
1) Combustion air
blower capacity
2) Same as 1
1) 150cfm/ft2 hood,
100 fpm booth
face velocity
1) As required
TYPICAL GAS
TEMPERATURE
1) 600 to 1500F
2) Same as 1
1) 70F
1) 100F
ro

10
1)  The table and listings are only intended as  a  guide  to  Illustrate  the  typical  range of  flow  rates and  temperatures  that  might  be expected with the
    designated control  systems.   The source  of these data are contained  In Appendix  C and cross-referenced to  industries  on  page  C-l    For further detail
    the user can refer  to the appropriate  EPA control  technique  documents  for  the  various industries and sources                   "                     '

-------
            Table 2.2  DESIGN PARAMETERS FOR RESPECTIVE
                       INDUSTRIES FOR HIGH EFFICIENCY PERFORMANCE
1.2
Industry
Basic oxygen furnaces
Brick manufacturing
Castable refractories
Clay refractories
Coal fired boilers
Detergent manufacturing
Electric arc furnaces
Feed mills
Ferroalloy plants
Glass manufacturing
Gray iron foundries
Iron and steel (sintering)
Kraft recovery furnaces
Lime kilns
Municipal incinerators
Petroleum catalytic cracking
Phosphate fertilizer
Phosphate rock crushing
Polyvinyl chloride production
Secondary aluminum smelters
Secondary copper smelters
Fabric Filter
Air-to-Cloth Ratio
Reverse
Air
1.5-2.0
1.5-2.0
1.5-2.0
1.5-2.0

1.2-.15
1.5-2.0

2.0
1.5
1.5-2.0
1.5-2.0

1.5-2.0


1.8-2.0




Pulse
Jet
6-8
9-10
8-10
8-10

5-6
6-8
10-15
9

7-8
7-8S

8-9


8-9
5-10
7
6-8
6-8
Mechanical
Shaker
2.5-3.0
2.5-3.2
2.5-3.0
2.5-3.2

2.0-2.5
2.5-3.0
3.5-5.0
2.0

2.5-3.0
2.5-3.0

2.5-3.0


3.0-3.5
3.0-3.5

2.0

Venturi
Scrubber
In. of
Water
40-60
35

11
15
10-40


40-80
65
25-60

15-30
12-40

40
15-30
10-20

30

Precip-
itator
Drift Vel
Ft/sec
.15-. 25



.22-. 35

.12-. 16


.14
.1-.12
.2-. 35
.2-. 3
.17-. 25
.2-. 33
.'12-.18

.35


.12-. 14
1)  High Efficiency -  an  outlet  loading of less than 0.04 gr/scf.

2)  Source -  see page  C-l, Appendix  C.
                                        2-10

-------
               Table  2.3   EFFICIENCY  OF  CARBON ADSORPTION  FOR  SELECTED
                          SOLVENTS AND SPECIFIED OPERATING CONDITIONS
Solvent
Acetone
Benzene
n-Butyl acetate
n-Butyl alcohol
Carbon tetrachloride
Cyclohexane
Ethyl acetate
Ethyl alcohol
Heptane
Hexane
Isobutyl alcohol
Isopropyl acetate
Isopropyl alcohol
Methyl acetate
Methyl alcohol
Methyl ene chloride
Methyl ethyl ketone
Methyl isobutyl ketone
Perchlorethylene
Toluene
Trichlorethylene
Trichloro trifluoroethane
V M & P Naphtha 2
Xylene
Average Inlet
Concentration
(ppm)
1,000
10
150
100
10
300
400
1,000
500
500
100
250
400
200
200
500
200
100
100
200
100
1,000
500
100
Acceptable
Ceiling
Concentration
(ppm)

25


25










1,000


200
300
200



Lower Explosive
Limit
(% by volume
in air)
2.15
1.4
1.7
1.7
n
1.31
2.2
3.3
1
1.3
1.68
2.18
2.5
4.1
6.0
n
1.81
1.4
n
1.27
n
n
0.81
1.0
Carbon
Adsorption
Efficiency
Ib solvent/
100 Ib
carbon
8
6
8
8
10
6
8
8
6
6
8
8
8
7
7
10
8
7
20
7
15
8
7
10
NOTE:
                                  2-11
1) Efficiencies are based on 200 cfm of 100  F  solvent-laden  air  (at  the
   specified concentrations) per hundred pounds  of carbon  per  hour.
   Source:   Manzone, R.R. et al.,  "Profitability Recycling Solvents  from
   Process  Systems", Hoyt Manufacturing corp,  Pollution  Engineering  Oct.  1973.
   More precise carbon estimation  procedures are given in  Section  5.5

2) Varnish  makers & painters naphtha.

-------
                              Section  3
                     COST  ESTIMATING PROCEDURES
      Several methods of varying degrees of accuracy are available  for  estimating
 the  capital costs of systems.  These  methods range from presenting overall
 installed costs on a per  unit basis,  to detailed cost estimates based  on
 preliminary designs, schematics, and  contractor quotes.  The least accurate
 method is the equating of overall capital costs to a basic operating parameter
 such  as tons per hour or  cfm.  An example is a typical installed cost  for a
 fabric filtration system  of approximately seven dollars per cfm.  This figure
 is developed from average costs of many installations which may range  from
 three to twelve dollars per cfm.  The low end of the range might represent an
 installation using standard equipment, installed by plant personnel,  and just
 marginally meeting current regulations.   The high end of the cost range may
 represent a system designed for:  1) the inclusion of standby equipment and
 redundant systems,  2) overprovision for safety,  3)  fully automated  operation
 with complex controls, and  4) expensive materials of construction or other
 custom features.  These factors affect both equipment and installation costs,
 and therefore the degree of accuracy produced using an estimating  method
 based on cfm alone would,  at best,  provide accuracies  in  an "order of magnitude"
 category (probable accuracy of +50%, -30%) Ref.  149.
     The detailed cost estimate, in turn,  can produce  accuracies of ±5 percent
 depending on the amount of perliminary engineering involved.   These estimates
 take many months of engineering effort and require process  and  engineering
 flow sheets, material and  energy balances, plot  plans,  and  equipment  arrange-
ment drawings before a cost estimate can be developed.  For first-cut estimating
purposes,, a technique for  developing capital  costs  must be  used that  is between
these two extremes that can provide accuracies of  approximately ±20- percent.
                                      3-1

-------
   The technique used in this manual for determining capital costs for a specific
pollution control system is based on the factored method of establishing direct
and indirect installations costs as a function of known equipment costs.  This
approach is basically a modified "Lang Method" of cost estimating whereby cost
factors for installation are  applied to the  cost of  the equipment.   The  result-
ing cost estimates  using this technique can  provide  accuracies  of plus or minus
20 percent for  new  installations.   This is somewhat  better than a  "study
estimate" which has an  error  limit  on the order of plus or minus 30  percent.
     The cost  factors developed  in  this  manual  are  based on both quoted and
estimated installation costs  of  pollution  control  systems.   The  annual  operating
costs  for these  systems are based on unit  costs for utilities  and operating
and maintenance  labor and materials  together  with  fixed percentages  of capital
costs  for the  indirect costs.
3.1  Capital  Costs
     The capital costs of a pollution control system  consisting  of  the delivered
                                                 s
equipment costs  for the control  device  and all  the  auxiliary equipment and
appurtenances  plus the direct and indirect costs of installation are  shown in
Table 3.1.   The  equipment costs  represent  a firm cost since these are obtain-
able from the  supplier's quoted  prices  or  from curves compiled from  average
costs  for the  specific type of equipment such as those  provided  in Section 4
and 5.  The cost of installation can vary  substantially from one system to
another depending on such features  as:  1)  the degree  of assembly of  the control
device; i.e.,  whether it is delivered as a  packaged unit or must be  field
assembled,   2) the geographic location  of  the plant in  regard  to local  wage
rates  and availability of contractors,   3)  the topography  of the land site
(whether the land is within the  battery limits or outside  and must be purchased),
4) the availability of service facilities,  i.e., whether electricity, water,
steam, etc., are at or near the  site, and   5) whether the  equipment  is  to
                                       3-2

-------
                       TABLE 3.1   CAPITAL COSTING
                                                    - (FABRIC FILTERS)
DIRECT COSTS
  D
      a)  Control Device
      b)  Auxiliary
          Instrument
          Taxes
          Freight
                  TOTAL
c)
d)
e)
  2)
      a)  Foundation
          Erection &
          Electrical
          Pi pi ng
          Insulation
          Painting
          Site Preparation
          Facilities &
                  TOTAL
b)
c)
d)
e)
f)
9)
h)
INDIRECT COSTS
  3)  INSTALLATION IN
      a)  Engineering
      b)  Construetio
      c)  Construction Fee
      d)  Start Up
      e)  Performance Test
      f)  Model Study
      g)  Contingencies
                  TOTAL
1* 2*
TYPICAL COST v COST
FACTOR ADJUSTMENT RANGE
IENT COSTS
ce
uipment
& Controls

L
ECT COSTS
& Supports
and! ing
tion
Buildings
[RECT COSTS
i Supervision
& Field Expenses
Fee
Test
>
i
Cost Per
Cost Per
0.10
0.03
0.05
1.00
0.04
0.50
0.08
0.01
0.07
0.02
As Req'd.
As Req'd.
1.72
0.10
0.20
0.10
0.01
0.01
None
0.03
9 17


X .5-3
X .3-1.6
X .2-2

X .2-2



X 0-2
X 0-2

X .5-3
X .5 - 1.5
X .5-2


X 1-10
3*
SYSTEM
COST FACTOR


0.05 to
0.01 to
0.01 to
l no
n Q4.
0.10 to
n Oft
o m
n n?
- 0.02
0 to
0 to
-1.28 to
0.05 to
0.10 to
0.05 to
- 0.01
- 0.01
0.03 to
-.1 « tn


0.30
0.05
0.10
1.0
2
2
6.18
0.30
0.30
0.20
0.30
7 in
      *  Based on Tables 3.2 and 3.3.
                                                 3-3

-------
be outside or enclosed in buildings.   The cost of retrofitting an existing
plant process may involve one or more of the conditions 1  to 5 plus it often
involves the dismantling and removal  of existing equipment, a task which could
be both costly and time consuming.
     In assessing the relationship between direct and indirect costs of
installation to the cost of equipment, it is necessary to  apply some adjust-
ments to those cost items that have a minor impact on equipment costs but are
heavily influenced by such items as plant size, plant location, safety and
type of process.  This is particularly true when considering the indirect
costs such as engineering, construction fees, and contingencies.  Cost factors
for engineering and construction fees will depend on whether the system
utilizes standard or custom designed equipment and if the  process entails
new technology or is simply a duplicate of an existing system.  Contingencies
may be based on whether the process is firm or tentative and subject to changes
     The cost factors and cost adjustments must also be evaluated on a per
system basis.  For instance, the cost of piping may be negligible for a fabric
filtration system but it becomes an accountable item for scrubbers or wet
precipitators.  The cost of insulation is only relevant to those processes
that handle hot gas streams or provide some type of cooling in the collection
process.
     The use of the cost factors and adjustments must be applied with some
engineering judgement.  The application of these factors will depend, to some
extent, on what is included in the cost of the equipment.   As shown in
Table 3.1, a typical cost factor can be developed which represents the
average cost factor based on the analysis of several similar systems.  In
the analysis of these systems, a deviation in some cost factors for the same
item can be attributed to some cost adjustment.  For instance, if a fabric
                                     3-4

-------
 filter is purchased as a standard unit and factory-assembled, the equipment
 cost will be higher than the same unit shipped "broken-down" or in modules;
 however, the installation costs for handling and erection will be lower for
 the factory-assembled unit.  If a typical cost factor for handling and
 erection was applied to the equipment cost of both units without a cost ad-
 justment, the error in the handling and erection costs of the factory-assembled
 unit essentially would be compounded.  Therefore, the typical cost factors,
 shown in column 1 of Table 3.1, which indicate the average values for each
 component cost for a particular type of pollution control system, are then
 multiplied by a cost adjustment to establish the system cost factor for a
 specific application.   The cost adjustments are used for any type of system
 and are solely provided as modifiers for the cost factor.  The cost adjustment
 can be considered as a means of compensating for cost variations  that are not
 directly attributable to the cost of equipment.  The system cost  factor is
 then multiplied by the total equipment cost to determine the estimated
 component cost in dollars.  A description of the capital cost components  with
 their cost factors, adjustments,  and their usage is  presented in  the following
 sections.
     3.1.1   Purchased Equipment Costs
     The purchased equipment costs  represent the delivered costs  of the
 control  device, auxiliary equipment, and instrumentation.   These  costs are
 developed by first establishing the  design and operating characteristics  of
 the equipment that will  satisfy the  pollution control  requirements  of a
specific industrial process.   The F.O.B.  costs  are then  established from
curves,  graphs, and data found in Sections 4 and 5 of this  manual which cover
 the cost of-the control  device and selected auxiliary equipment.  The prices
 listed represent flange-to-flange costs  and generally include internal
                                    3-5

-------
electricals and controls except where noted.  Instrumentation is not included
in Sections 4 and 5 since it is usually provided as an optional feature in
most equipment costs.  The typical cost factor for instrumentation can be
considered as 10% of the equipment costs as shown in Table 3.1  (Ref.  156).   A
cost adjustment is also provided for this component cost as shown in  Table  3.2.
Freight costs within the U.S. are generally 5% of the equipment cost  although
a cost adjustment must also be included for unusually remote or distant sites
as shown in Table 3.2 (Ref. 150).  The purchased equipment costs, which includes
the F.O.B. equipment cost, instrumentation, freight and taxes,  then becomes the
basis for determining the direct and indirect installation costs.  This is
done by multiplying the appropriate factor for each element by the purchased
equipment cost (NOTE:  Table 3.1 expresses the purchased equipment cost as
unity).
     Since the cost of delivered purchased equipment represents the basis for
determining installation costs, those items that are not field fabricated
should be accounted for as purchased components and included in the purchased
                                               s
equipment costs.  In typical factorial cost estimating methods such as the
Lang method, the cost of items such as hoods, ducting, etc., are only
included in the installation costs and usually represented as a percentage of
equipment costs.  These costs, however, can be as much as the cost of the
control device itself.  Since most of the ductwork is shop fabricated, cost
of the ductwork should be developed for each specific application and
included in the cost of auxiliary equipment.  Curves are provided in Section
4 to estimate the cost of these components.  Only the handling, erection,
insulation, and painting of the ductwork are included in the installation
costs and are designated as a percentage of the total equipment costs.  Thus,
the cost of items normally shop fabricated are accurately accounted for as
                                     3-6

-------
                                                   *
                       TABLE 3.2  COST ADJUSTMENTS

A)  INSTRUMENTATION                                            COST ADJUSTMENT
    1)  Simple, continuous manually operated                    0.5 to 1.0
    2)  Intermitten operation, modulating flow with
        emissions monitoring instrumentation                    1.0 to 1.5
    3)  Hazardous operation with explosive gases
        and safety backups                                          3
B)  FREIGHT
    1)  Major metropolitan areas in continental U.S.            0.2 to 1.0
    2)  Remote areas in continental U.S.                            1.5
    3)  Alaska, Hawaii, and foreign                                 2
C)  HANDLING AND ERECTION
    1)  Assembly included in delivered cost with
        supports, base, skids included.   Small  to
        moderate size equipment                                 0.2 to 0.5
    2)  Equipment supplied in modules, compact
        area site with ducts and piping  less than
        200 ft. in length.  Moderate size system                    1
    3)  Large system, scattered equipment with
        long runs.  Equipment requires fabrication
        at site with extensive welding and erection                1  to 1.5
    4)  Retrofit of existing system; includes
        removal of existing equipment and renova-
        tion of site.  Moderate to large system                     2
D)  SITE PREPARATION
    1)  Within battery limits of existing plant;
        includes minimum effort to clear,  grub,
        and level                                                    0
    2)  Outside battery limits; extensive leveling
        and removal  of existing structures;
        includes land survey and study                              1
    3)  Requires extensive excavation and land
        ballast and leveling.   May require
        dewatering and pilings                                       2
*
  Based on data obtained  in refs. 150, 156, 159.

                                     3-7

-------
                TABLE 3.2  COST ADJUSTMENTS (CONTINUED
                                                              COST ADJUSTMENT

E)  FACILITIES & BUILDINGS
    1)  Outdoor units, utilities at site                            0
    2)  Outdoor units with some weather enclosures.
        Requires utilities brought to site, access
        roads, fencing, and minimum lighting                        1
    3)  Requires building with heating and cooling,
        sanitation facilities, with shops and office.
        May include railroad sidings, truck depot,
        with parking area                                           2
F)  ENGINEERING & SUPERVISION
    1)  Small capacity standard equipment, duplication
        of typical system, turnkey quote                           0.5
    2)  Custom equipment, automated controls                     1 to 2
    3)  New process or prototype equipment, large
        system                                                      3
6)  CONSTRUCTION & FIELD EXPENSES
    1)  Small capacity systems                                     .5
    2)  Medium Capacity systems              ^                      1
    3)  Large capacity systems                                    1.5
H)  CONSTRUCTION FEE
    1)  Turnkey project, erection and installation
        included in equipment cost                                 .5
    2)  Single contractor for total installation                    1
    3)  Multiple contractors with A&E firm's super-
        vision                                                      2
 I)  CONTINGENCY
    1)  Firm  process                                                1
    2)  Prototype or  experimental process  subject
        *   u                                                     3 to 5
        to  change
    3)  Guarantee of  efficiencies and operating
        specifications requiring initial pilot tests,             5 to 10
        deferment of  payment until final certification
        of  EPA tests, penalty for failure  to meet
        completion date or efficiency.

                                      3-8

-------
 purchased  equipment.  The  cost burden for  handling and erecting  these  items
 becomes a  smaller portion  of the total  installed cost of the system, and
 hence, any inaccuracies in the percentage  factors will have a lesser effect
 on  the total estimated cost of the system.
     3.1.2  Installation Costs
     Installation costs consist of the direct expenses of material and labor
 for foundations, structural supports, handling and erection, electrical,
 insulation,  painting, site preparation, and facilities; plus the indirect
 expenses for engineering and supervision, construction and field expenses,
 construction fees, start up, performance tests, model studies,  and contingen-
 cies.  In  considering the direct costs, site preparation,  buildings and
 facilities are items that have little or no relationship to the cost of the
 purchased  equipment and therefore some cost adjustment,  as  shown in Table 3.2,
 must be used to compensate for added costs due to unusual  requirements.
 Examples of unusual  site preparation would be the removal  of existing structures
 before construction or a potential  site which is a  bog or  swamp.   Although
 handling and erection are related to equipment costs, some  adjustment must
 also be made for either field erection or factory assembly  of the control
 device and auxiliary equipment as well  as the type  of installation,  i.e.,  new
or retrofit of an existing  process.
     Variations in the indirect expenses can be substantial  since items such
as engineering, construction fees,  and contingencies  are related  to  contracting
methods and the overall  magnitude of the project rather  than the  equipment
costs.   These items  all  require some adjustment based on system size and
contracting arrangement.  Other cost items  such as  model studies  may appear in
unusual circumstances such  as  large electrostatic precipitator systems  or
         *
other systems where  the  level  of previous experience  may be  limited.
                                      3-9

-------
     In evaluating the installation costs of all  systems, it is assumed that
the installation is performed by an outside contractor and not by plant
personnel.   In addition, the cost factors will  change for different types of
systems since many of the components are dissimilar items.  Table 3.3 summarizes
the estimated cost factors for each system.  Cost adjustments of Table 3.2
should be applied to these cost factors, where appropriate, to develop the
estimated capital costs of a specific application.
3.2  Annualized Costs
     The typical annualized costs, shown in Table 3.4, consist of the direct
expenses of labor and materials for operation and maintenance, the cost of
replacement parts, utility costs, and waste disposal; plus the indirect costs
of overhead, taxes, insurance, general administration and the capital recovery
charges.   The unit costs  are only samples  and can vary significantly from
installation to  installation.  The direct  costs of labor and utilities are
based  on average  rates  as of December, 1977 that have been developed by the
                                               s
Bureau of  Labor  Statistics.  The cost of replacement parts is based on the
purchased  list price of those components and materials that have a known
limited life or  replacement schedule.  Waste disposal costs are only applicable
to some systems  where the collected pollutant has no value and must be removed
to a disposal site.   In most cases, the controlled pollutant can either be
recovered  and used again  in the primary process or is disposed of by the pollu-
tion control system itself, e.g., by combustion in incinerators and flares.
     The indirect operating costs are basically related to the capital invest-
ment with  the possible  exception of overhead.  Overhead expenses include the
cost of employee  fringe benefits, medical  and property protection, cafeteria
expenses,  etc. and are  accounted for as a  percentage of direct salaries or
payrol1.
                                      3-10

-------
                                         TABLE 3.3  CAPITAL COST SUMMARY*
DIRECT COSTS
  1)   PURCHASED EQUIPMENT. COSTS
      a)   Control  Device
      b)   Auxiliary Equipment
      c)   Instruments & Controls
      d)   Taxes
      e)   Freight
                  TOTAL
  2)   INSTALLATION DIRECT COSTS
      a)   Foundations & Supports
      b)   Erection & Handling
      c)   Electrical
      d)   Piping
      e)   Insulation
      f)   Painting
      g)   Site Preparation**
      h)   Facilities & Buildings**
                  TOTAL
INDIRECT COSTS
  3)   INSTALLATION INDIRECT COSTS
      a)   Engineering & Supervision
      b)   Construction & Field Expenses
      c)   Construction Fee
      d)   Start Up
      e)   Performance Test
      f)   Model Study
      ,g)   Contingencies
                  TOTAL
                Values  based on average of cost factors reduced from cost estimates.(Ref.  148, 160)
            **  Costs for site preparation, facilities, and buildings can be obtained from Reference  171,
ESP
As Req'd
As Req'd
0.10
0.03
0.05
1.00
0.04
0.50
0.08
0.01
0.02
0.02
As Req'd
As Req'd
1.67
0.20
0.20
0.10
0.01
0.01
0.02
0.03
2.24
VS












0.06
0.40
0.01
0.05
0.03
0.01




1.56
0.10
0.10
0.10
0.01
0.01
	
0.03
1.91
FF












0.04
0.50
0.08
0.01
0.07
0.02




1.72
0.10
0.20
0.10
0.01
0.01
	
0.03
2.17
T&CI












0.08
0.14
0.04
0.02
0.01
0.01




1.30
0.10
0.05
0.10
0.02
0.01
	
0.03
1.61
ADS












0.08
0.14
0.04
0.02
0.01
0.01




1.30
0.10
0.05
0.10
0.02
0.01
	
0.03
1.61
ABS












0.12
0.40
0.01
0.30
0.01
0.01




1.85
0.10
0.10
0.10
0.01
0.01

0.03
2.20
R












0.08
0.14
0.08
0.02
0.10
0.01




1.43
0.10
0.05
0.10
0.02
0.01
	
0.03
1.74
F












0.12
0.40
0.01
0.02
0.01
0.01




1.57
0.10
0.10
0.10
0.01
0.01
	
0.03
1.92

-------
                                 TABLE 3.4  BASIS FOR ESTIMATING ANNUALIZED COSTS
ISJ
 DIRECT OPERATING COSTS

 1)  Operating Labor
     a)  Operator
     b)  Supervisor

 2)  Operating Materials
 3)  Maintenance
     a)  Labor
     b)  Material

 4)  Replacement Parts

 5)  Utilities
     a)  Electricity
         Fuel  Oil
         Natural Gas
         Plant Water
         Water Treatment  & Cooling  Water
         Steam
         Compressed Air
 6)  Waste Disposal

 INDIRECT OPERATING COSTS
 7)  Overhead

 8)  Property Tax
 9)  Insurance

10)  Adminstration
11)  Capital  Recovery Cost

 CREDITS
12)  Recovered Product
b)
c)
d)
e)
f)
g)
                                                    COST FACTOR
$7.87/man-hour
15% of la

As Required

$8.66/man-hour
100% of 3a
As Required


$0.0432/Kwh
$0.47/gal
$1.98/Mcf
$0.25/1000 gal
$0.10/1000 gal
$5.04/Mlb
$0.02/1000 cf

$5-ld/Ton
                                                  80% of la + Ib + 3a
                                                  1% of capital costs

                                                  1% of capital costs

                                                  2% of capital costs
                                                  0.16275 (as an example
                                                  of 10% and an equipment
                                                  life of 10 years)
                                                  As Required
                                                                              REFERENCE

                                                               USDL,  BLS average mill  workers  rate $6.56/h
                                                               plus  fringes  of 20%,  May 1977.
                                                               Ref.  150
                                                                           Hourly rate of 10% premium
                                                                           labor
                                                                                           over operating
USDL, BLS Consumer Price Index for
500/Kw/md., May,-1977.
USDL, BLS Consumer Price Index, May 1977
USDL, BLS Consumer Price Index, May 1977
Ref. 156 updated 1977
Ref. 156 updated 1977
Fuel @ $4.19/M Lb steam plus ~ 16% oper & Main.
Ref. 156 updated 1977
                                                               Ref.  150

                                                               Ref.  150

                                                               Ref.  150

                                                               Ref.  150

-------
      The  operating costs must be adjusted for any credits that are obtained
 from  the  reuse or sale of recovered products or from the recovery of heat and
 energy  from the process.  Credits such as solvent recovery can significantly
 offset  control expenses and must be considered as an important factor in an
 accurate  cost analysis.
      3.2.1  Direct Operating Costs
      Labor and material costs for operation and maintenance of pollution
 control systems vary substantially between plants due to the degree of
 automation of the system, equipment age,  characteristics of the gas stream,
 operating periods and some generalizations must be made to  develop a  reason-
 able method of estimating these costs.   Normally these  costs represent from
 2 to 8 percent of the total  annualized  costs with the remainder reflecting
 the cost of utilities and capital  charges.   In  general, operating  labor  and
 supervision will  be  reduced  with increased system automation.   Small  systems
which operate intermittently or on  demand may require a full  time  operator
 for start-up, control, and shutdown while the system is in  operation.  In
 contrast, larger automated systems  operating continuously may only require
 a short  period per shift for monitoring purposes.  The total annual  labor
 cost  is also a function of the number of 8-hour operating shifts  per  year.
 Small plants may be expected to operate one shift per day,  five days  per
 week, and fifty weeks per year while large plants such  as those in the basic
 metals, petroleum, and chemical industries would be expected to operate
 three shifts per day for 365 days.   The operator labor, therefore, should be
 estimated on a man-hours per shift basis  for the particular types  of  system.
 For large, automated, continuously operated systems, the operating labor can
 be estimated as shown in Table 3.5.   Estimates  of maintenance labor are also
 provided for large capacity systems  handling non-corrosive  materials.  These
 estimates only reflect the cost of preventative maintenance.  Where periodic
                                     3-13

-------
               TABLE 3.5  ESTIMATED LABOR HOURS PER SHIFT*
CONTROL DEVICE                              OPERATING LABOR  MAINTENANCE LABOR
                                           (man-hours/shift)   (man-hours/shift)
Fabric Filters                                   2-4            1-2
Precipitators                                   .5-2           .5-1
Scrubbers                                        2-8            1-2
Incinerators •                                      .5               .5
Adsorbers                                          .5               .5
Absorbers                                          .5               .5
Refrigeration                                      .5               .5
Flares                                             -                .5
   Based  on  discussions with manufacturers and operators with corroborating
  data  from  refs..78s 82,  126 and  141.
                                     3-14

-------
replacement of major parts are required such as the replacement of filter
bags in a fabric filter or the replacement of adsorbent in adsorbers, the
labor cost for replacement should be equal to the material cost of the replace-
ment parts.  For small to medium size systems where the installed cost is
approximately $100,000, or less, the total cost of maintenance is assumed to
be 5 percent of the installed capital cost.
     The annual cost of replacement parts represents the cost of the parts
or components divided by their expected life.  Replacement parts are those
components and materials such as filter bags, catalyst,  and absorbents
which have a limited life and are expected to be replaced  on a periodic
schedule.   An estimate of the life of the parts  as well  as equipment,  as
shown in Table 3.6, is based on a qualitative judgement  of the type  of appli-
cation, maintenance service and duty cycle.  The guideline for average life
represents a process operating continuously with 3 shifts  per day , 5 to 7
days per week, handling moderate concentrations of non-abrasive dusts or non-
corrosive gases.  The guideline for low life applications  is based on a
continuous process handing moderate to high temperature gas streams with  high
concentrations of corrosive gases or abrassive dusts.   Applications having
high life expectancies for parts and equipment would be those operating  inter-
mittently or approximately one shift per day with gas  streams with low con-
centrations and at ambient gas stream temperatures.
     The cost of waste disposal considers  only the removal and hauling of a
dry contaminant to a nearby landfill area by an outside  contractor.
     To assist the user in developing the approximate  utility costs  for the
auxiliary equipment and control devices, the following equations and data
are provided.
                                     3-15

-------
         TABLE  3.6   GUIDELINES FOR PARTS AND EQUIPMENT LIFE1
MATERIALS AND PARTS LIFE
Filter bags
Adsorbents
Catalyst
Refractories
LOW
(Years)
.3
2
2
1
AVERAGE
(Years)
1.5
5
5
5
HIGH
(Years)
5
8
8
10
EQUIPMENT LIFE
     Electrostatic Precipitators
     Venturi Scrubbers
     Fabric Filters
     Thermal Incinerators
     Catalytic Incinerators
     Adsorbers
     Absorbers
     Refrigeration
     Flares
5
5
5
5
5
5
5 S
5
5
20
10
20
10
10
10
10
10
15
40
20
40
20
20
20
20
20
20
  Based  on  discussions with manufacturers  and operators with corroborating
  data from refs.  19, 20,  37,  38,  40,  78 and 82.
                                      3-16

-------
Fan Power
     The horsepower for various  fans is shown in Section 4, however, the
     following formulas can also be used.
               kwh = 0.746 (hp)(H) = 0.7«6gFH)(tf)(S6)(H)

     where :
               kwh = kilowatt-hours
               hp  = horsepower
               CFM = actual volumetric flow rate, acfm
               AP  = pressure loss, inches WG
               n   = efficiency, usually 60 - 70%
               H   = hours of operation
               SG  = specific gravity as compared to  air @  70°F,  29.92  inches
                                                                   mercury.
Pump Power
     The horsepower for pumps operating at various  flow rates  and pressure
     levels  is shown in Section 4, however, the  following formulas  can  also
     be used.

               kwh = 0.746 (hp)(H) = °-
     where :
               GPM = flow rate,  U.S.  gpm
               hd  = head of fluid,  feet
               SG  = specific gravity relative  to water @60°F,  29.92  inches
                     mercury
Baghouse Power (auxiliaries, motors,  etc.)
     Horsepower requirements for baghouse shaker motors,  reverse  air  fan motors,
etc. can j?e estimated at approximately 0.5  hp per 1000 sq.  ft.  of cloth.   Power
usage will depend on dust loading and cleaning  cycle.  Assuming a 50% usage
factor, power requirements would be  approximately 0.2 Kwh per  1000 sq.  ft.
                                    3-17

-------
Precipitator Power
     For approximation purposes, the power requirements for a precipitator can
     be assumed to be 1.5 watts per square foot of collection area, the range
     varying from 0.3 to 3 watts per square foot (ref. 168).
Incinerator Fuel
     The fuel requirements for incinerators depends on the exhaust gas flow
     rate, the inlet, outlet, and combustion temperatures, inlet gas composi-
     tion, and control efficiency.  The utility costs for incinerators can be
     determined from the operating cost curves and fuel requirements developed
     in the-EPA manual 450/3-76-031 "Report of Fuel Requirements, Capital Cost
     and Operating Expense for Catalytic and Thermal Afterburners", ref. 141.
     3.2.2  Indirect Operating Costs
     The indirect operating costs include the cost of taxes, insurance,
administration expenses, overhead, and capital charges.  Taxes, insurance, and
administration can collectively be estimated at 4 percent of the capital costs
while overhead charges can be considered assSO percent of the labor charges
for operation and maintenance of the system.  The annualized capital charges
reflect the costs associated with capital recovery over the depreciable life
of the system and is determined as follows:
                                                    i (1 + i\^
          Capital Recovery Cost = (capital costs) x n + -j)n . -j
     where:
          i = annual interest rate
          n = capital recovery period
     For average interest rates of 10 percent over a recovery period of 10
years, the capital recovery cost factor amounts to 0.16275 and the annual
capital charges are accounted for as 0.16275 times the capital costs.
                                      3-18

-------
For a 20-year period, the capital recovery cost decreases to 0.11746 times
the capital costs.  There are other depreciation methods such as Straight-
line, Declining Balance, etc. which can be used.  The Capital Recovery Factor
method is preferred by the EPA and 1s used in this manual.
                                     3-19

-------
                             Section 4
                        AUXILIARY EQUIPMENT
     The gas cleaning methods used by industry today are categorized by  the
technique of gas or particulate removal.  These techniques include:  (1)
electrostatic precipitation,  (2) fabric filtration,  (3) wet scrubbing,
(4) incineration,  (5) adsorption,  (6) absorption,  (7) refrigeration, and
(8) flares.  The properties and characteristics of the particular gas stream
will generally dictate which control option is appropriate.  In some cases,
several techniques may be suitable or the selection of one type in lieu of
the others may be based on efficiency and/or total costs (capital, maintenance,
and operating).
     For each technique selected in a particular application, a certain amount
of auxiliary equipment must be utilized with the control  device for the
efficient operation of the gas cleaning system.   The types  of auxiliary
equipment required will  depend on the application.  Hot processes may require
pre-coolers before the control  device or the addition of moisture may be
required for proper operation of the control  device.   The selection of the
auxiliary equipment is directly related to the size and operating characteristics
of the control  device.  Therefore,  to develop the  gas stream  inlet parameters
to the control  device, it is necessary to  select and  size the auxiliary equip-
ment which may affect those parameters.  Since most control systems require
the same auxiliary equipment, a  description and  estimated cost of the auxiliary
equipment is presented first and followed  by the description  of the control
devices and system costs.
                                      4-1

-------
     The arrangement of the auxiliary equipment with respect to the control
device is shown in Figure 4-1.  In general, all systems will require some
auxiliary equipment such as fans and ductwork.  The use of other auxiliary
equipment will be dictated by the physical characteristics of the pollutant
and gas stream, and the operating characteristics of the control device.
Descriptions of the various components that may be included as auxiliary
equipment for a system are provided in the following subsections.
4.1  Capture Hoods
     Although a variety of hood configurations are used throughout industry,
they can usually be catagorized as either canopy hoods or semi-closed hoods.
Canopy hoods are defined as round or rectangular hoods mounted at a distance
from the pollutant source so that the majority of the collected gas consists
more of induced air than the volume of generated fume, dust or gas.  Semi-
closed hoods are described as enclosures attached to or comparatively near
the source of pollutants so that the collected gas is primarily the generated
pollutant and the remaining air is induced through openings in the enclosure
for operational purposes.
      The type and  location of the capture device is directly related to the
 volumetric flow for the system.  For example, for fume capture at the source,
 a relatively small volumetric exhaust rate is required to contain and capture
 the dust .or pollutant.  As the capture device is moved farther from the source,
 the fume is allowed to disperse  and entrain  outside air.  The resulting dust
 envelope or plume  increases  in size as it mixes with the air, necessitating a
 larger  capture device to  contain it.  As the distance between the source  and
 the capture device increases, the volumetric flow rate for the control system
 also  increases.  Since the cost  of a control system is closely related to
                                       4-2

-------
            CAPTURE
             HOODS
                        DUCTING
                                                                    ANCILLARY
                                                                    EQUIPMENT
                                                               Pumps, Cooling Towers,
                                                                   And Controls
                     GAS
                 CONDITIONING
                      CONTROL
                      DEVICE
I
CO
Canopy Hoods,
Semi-Closed
  Hoods,
Direct Ex-
  haust
Side Draft Hoods
Water-Cooled
Refractory,
Carbon Steel,
Stainless Steel
U-Tube Cooler,
Quenchers,
Spray Chamber,
Mechanical
  Collectors
                                                                    POLLUTANT
                                                                     REMOVAL
                                                                        &
                                                                    TREATMENT
     FANS
STACK
Backward Curved,
Radial


In some applications the
fan may be ahead of the
control device.
                                                              Thickners & Clarifiers,
                                                              Vacuum Filters,
                                                              Bins and Elevators,
                                                              Screw Conveyors
                                          Figure 4-1   CONTROL SYSTEM FLOW CIRCUIT

-------
flow rate (in dollars per cfm), the type, configuration, and location of the
capture device will substantially affect the size and cost of the overall
system.
     The volumetric flow rate associated with canopy hoods is a function of
the dimensions of the hood and the average face velocity necessary to cause
induced air currents to direct the pollutant into the hood.  For cold
processes emitting pollutants, the configuration of the hood is most important
since this is the controlling feature of the velocity profile between the
source and the hood.  For hot processes or where the pollutant is given a
velocity from' the source, the hood has to contain the actual dimensions of
the plume and evacuate it at an exhaust rate at least equal to the rate at
which the plume is being generated.  Since cross drafts in the operating area
will affect the plume on the way to the hood, the overall dimensions of the
hood must be enlarged to compensate for the maximum plume drift.  The lateral
movement of the plume increases with the height of the hood opening above
the source; therefore, the hood dimensions substantially increase due to this
lateral movement as well as the distance from source to hood.
                                      4-4

-------
      Canopy hoods  can  be  round  or rectangular,  and high or low.   A hood may
 be considered  a  low canopy  hood when  the  distance  between  the hood and the
 source  does not  exceed the  approximate  diameter of the  source, or 3 feet,
 whichever is smaller (ref.  88).   For  best ventilation,  the canopy should be
 placed  as close  to  the source as  possible.   In  some cases  the operation of
 equipment,  such  as  overhead cranes, precludes the  location of the hood being
 very  close  to  the source.
      In general, for cold processes,  the  low canopy should extend around the
 source,  a distance  of  approximately 40  percent  of  the height  of the canopy
 above the source.   The exhaust  flow rate  can then  be determined by the general
 formulas  shown in Figure 4-2 for  both round  and  rectangular hoods.   The  required
 control  velocities  are  dependent  on the particular characteristics  and evolu-
 tion  of  the pollutant  in the process.  Typical velocities  are outlined in
 Table 4.1 for those  industry sources requiring low canopy  hoods on  cold
 processes.
      For  hot processes, the typical minimum ventilation rates normally required
 for low rectangular or circular canopy hoods can also be determined from the
 formulas  in Table 4.1.  The differential temperature (AT) represents the
 temperature difference between the source and the ambient air.  This is a
 generalized method of sizing low canopies and exceptions and modifications  to
 this method are described in Reference 88.
     The sizing of high canopy hoods over hot processes  becomes  considerably
more complicated.  The buoyant effect of the plume  is  caused by  the density
differences between the source and the surrounding  air.   As the  hot gases move
upward,  they entrain additional  air and the plume expands and cools.  The
volume of the plume as a function of height above a circular source can be
        -*
expressed as:
                                     4-5

-------
                                                        45  Minimum
                            TANK
                             OR
                           PROCESS
Not to be used where material is toxife and worker must bend over
   tank or process.
Side curtains are necessary when extreme cross-drafts are present.
    1.4PDV
Q = (W+L)DV
    WOV
    or
    LDV
for open type canopy.
P = perimeter of tank, feet.
V = 50-500 fpm.
for two sides enclosed.
W & L are open sides of hood.
V = 50-500 fpm.
for three sides enclosed. (Booth)
V = 50-500 fpm.
    Figure 4-2   LOW CANOPY HOODS FOR COLD PROCESSES  (ref. 151)
                             4-6

-------
Table 4.1   MINIMUM VELOCITIES AND VENTILATION RATES FOR LOW CANOPY HOODS
              RANGE OF CAPTURE VELOCITIES FOR COLD PROCESSES  (ref.  151)
   Condition of Dispersion
       of Contaminant


Released with practically no
velocity into quiet air.

Released at low velocity into
moderately still air.
Active generation into zone
of rapid air motion.
Released at high initial
velocity into zone of very
rapid air motion.
      Examp!es


Evaporation from tanks;
degreasing, etc.

Spray booth; intermittent
container filling; low
speed conveyor transfers;
welding; plating; pickling

Spray painting in shallow
booths;  barrel filling;
conveyor loading; crushers

Grinding;  abrasive
blasting,  tumbling
Capture Velocity, fpm


        50-100


       100-200
       200-500
       500-2000
                MINIMUM VENTILATION RATES  FOR  HOT PROCESSES  (ref. 88)


   Low Circular Hoods:

       Q = 4.7 (P)2'33(AT)<42

           where  Q   =  ventilation  rate, cfm
                  D   =  diameter of  hood, ft.
                  AT  =  temperature  difference  between hot source and
                       ambient temperature, °F

   Low Rectangular Hoods:


       Q = 6.2 (W)1'33(L)  (AT)'42

           where  Q   =  ventilation  rate, cfm
                  W   =  width of canopy, ft.
                  L   =  length of canopy, ft.
                  AT  =  temperature difference  between hot source and
                       ambient temperature, °F
                                    4-7

-------
     Q  =  7.4(h + 2d)K5 (H)'33
     where   Q  =  plume volume, cfm
             h  =  height above source, ft
             d  =  diameter of source, ft
             H  =  heat transfer 'rate from source to plume, Btu/min.
     The plume volume from a rectangular source can be determined as follows:
     Q  =  18.5(h + 2w)'59[L - w + 0.5(h + 2w)'88] (H)'33
     where   L  =  length of source, ft.
             w  =  width of source, ft.
     The predominant factor in this expression is the rate of heat transfer
to the plume.  A complete discussion of the methods of determining this heat
transfer rate is given in References 88 and 152.  Since the canopy hood at a
given height above the source is required to collect and exhaust this plume,
the volumetric flow rate must equal or exceed the plume volume.
     The semi-closed hood can be designed in many different configurations
which generally enclose the pollutant source.  The exhaust rate with these
devices is much lower than that from a canopy hood since collection is
accomplished at the source.  In order to contain the pollutant, the semi-closed
hood is usually maintained at a slight negative pressure to insure inward flow
of aspirated air.  The velocity of the air through the openings is a function
of the internal static pressure.  Different velocities are required for
different applications.  In addition, the sizing of the hood and the required
exhaust volume will depend on the particular process being controlled and the
size of the source.  Semi-closed hoods operating on hot processes may need
to be fabricated from special materials or water-cooled.
                                      4-8

-------
      Because of  the  variations  in applications and designs  for  each  source,
 the  design  and estimated costs  for semi-enclosed hoods should be determined
 from the data and curves illustrated in Reference 88.  For  the  purposes of
 this manual, only canopy hoods will be considered.
      Figures 4-3 through 4-6 contain data for estimating the equipment costs
 for  canopy  hoods.  Hood dimensions can be determined from Figure 4-2 or from
 recommendations in references 88, 129, 151 and 152 for most applications.
      Figure 4-3 gives plate area requirements for rectangular canopy hoods
 and  Figure 4-5 gives the corresponding labor costs for 10 Ga. carbon steel
 construction.  To establish the equipment cost, determine the length-to-width
 ratio (L/W) and the length for a given application,  and read the plate area
 required and the labor cost.  For example, if the hood is 20 ft long by 5 ft
                                                             2
wide, the L/W = 4, the plate required is  approximately 250 ft , and the
 fabrication labor cost is approximately $425.
     Figure 4-4 gives plate area requirements for circular capture  hoods  and
Figure 4-6 gives the labor costs for  10 Ga.  carbon steel  construction.
                            *
Determine the angle of slope ,  e, of  the  hood cone  (or the height-to-diameter
ratio) and the diameter of the  hood,  and  read the plate area required and  the
labor cost.   For example,  if the hood is  20  ft in diameter and  e =  50°, the
                                      2
H/D = .6, the plate required is  550 ft ,  and the  fabrication labor  cost is
$2010.
     To determine the total  fabricated  price,  the plate weight must be calcu-
lated, including 20% additional  for structural  supports.   The weight  of 10 Ga.
carbon steel is  5.625 lb/ft2.   The weight  of 1/4" plate is  about 10.30 lb/ft2.
 To determine angle of slope,  see Appendix C,  ref. 129, Fan Engineering,
 especially Figure  57, p  114.
                                    4-9

-------
cr
to
ct
LU
01
o.
o
cr
UJ
cr
                Slope of Hood «  350
                L = Lenth
                W = Width
                Curves Include 10% Scrap
                Skirt Not  Included
                For Water  Cooled Hoods
                Use Double- the  Plate Area
                                                                *=^E L/W = 4  ,
                                                                        =f  L/W -  8  -
CURVE EQUATIONS

A = 12 + 2.84 L2

A = 4 + 1.25 L2

A = 1 + 0.615 L2

A = .5 + 0.306 L2
                                   20           30          40

                                    L,  LENGTH  DIMENSION,  FT.


         Figure 4-3  RECTANGULAR  CANOPY  HOOD PLATE  AREA REQUIREMENTS VS.  HOOD LENGTH AND L/W

                                          4-10

-------
       1QO.OOO

-------
    CO

    O
    O
    CO
    «sc
    O
    o
    o
    o.
    o
    01
    •a:

1
io, poo
o 	
8
7
6
4
2
i
! i,opo
: 9_
i e.
>
; 7
: e
>
: 5..
i
J 4.
5
3 3
»
:
dOSL
-r- 	 	

' I
J—






i ' 1





























=
i i







+


















i


























i—









1







































































1







r !
1
;












F-r=

i If J i i














if j ,



i '/^ 7


I/ I/
I/ /
' v






hf i
/
/ -
/ y
//
/I/
/
r




j
A
*






h


^










^

^










=r^i
rpj *_
i

I











^










-








=











=





L/
^
^
i | i .




i ,


j
/
f

/I



^

/






/
f

r
i






/





= 1

/




/
'






=Tt=
T
f

f












L













-)



























*












=J

















E:








^i=






^



y
'







N

f













— r>
j/^
y

y
X^!





i
1
i

i









/
^J










L/W
1
2
4
8

— 4~i 	
i


f j !


I i
I i
i j



/ U
— -;-t— r-






1 * i./
I ' Jr
• jy^
i^i •
j f •
Jr'1
r I
l


i ' (

, ;


..^-, i . -
i ,

i ,
i


.

j
ht *
.Jffi i.
fc~=
54*
l/1^ ! J
d=|L/



1 1 1
1 ,


i j
\f
j
/
* I



—



1—

i

i

_l



--
4




r-
;
; 1
I










— m —

—

\ — i — ._j
rW=2
'-+-T-





•
—

t—
—
(—
—
t—




/
; ^



'S
s\



t






L
1
i
NOI
i.
2.
3.
4.
5.
6.
I
— _-.-
• ! ; ;
_i











pi
.-,



-

—











i
4^1

h±±^
M- H
"~








-^
-,








^

/I
^



?
•1:
5*


L/W=
-1 i
j
I
1
1




i

!


	 r-
"~ : '"'


•

.



i . •
i
i
' -U-i
ml
--r - i — :--
-1— i-t-r—
-^— 1~
	
=4

i t
rtt-
L-;.-!
— —


J 1 '
8 "

i

|
I

i
!
!
1
|

	 K-
	 . — . 	
, i

i
l"] !T"
J I
• I
1



-—-^LZ. J~
,^
U=-=i
p-^-l— J--M
[ ;
'
-• ' 	 : 	 '
	 t_r-


, j
i 1 i
, i
l
!
i

!
!
Slope of Hood = 35°
L = Lenqth
W = Width
Skirt not included
Fillet Weldtime for
skirt is included
- — i — '- ^—-
	 — ;-
1


I
1

i j
i ! '
1

i i !
— j — ] 	
— :r±d=
-! • i .
d;
j

:— --^..i



1
1
i j
1 i
; ,
1
! ' i
| i ! .
.


(at hood perimeter)
For water cooled hoods,
use douhlp thp man hniir<;
CURVE EQUATIONS


$=70.95+ 8.47L+2.97L
$=61.42+12.71L+1.59L
$=51.89+ 5.51L+ .66L
$=42.36+ 4.24L+ .33L
2
2
2
2

' l




--


_J

•


^

. • -^__
	











— t— j

r"
J_





3Ł
-*-[-
-|-i-



i


_i_
: :

i
,
i
i









1 1 ! ,






^^ 	


1
Costs Based :
on data from
Fuller Co.


J_
1
1

20    30    40     50    60    70    80

         ti HOOD LENGTH DIMENSION, FT.
                                                                   90   TOO
Figure 4-5   LABOR COST FOR FABRICATED  10 6A.  CARBON STEEL RECTANGULAR CANOPY  HOODS
                                          4-12

-------
                                =  65' m

                                       CURVE EQUATIONS

                                                     2
                                       89 + 9.2D+3.30
                                                   2
                                       28.50 + 3.6D
                                       101 + 6.3D + 6.4D
                                       615 - 120D + 20.2D
                                                       Costs Based
                                                       on data from
                                                       Fuller Co.
     loq
         0    10    20    30    40    50    60    70    80    90    100
                               D, HOOD DIAMETER, FT.
Figure 4-6   LABOR COST FOR FABRICATED 10 GA.  CARBON  STEEL  CIRCULAR CANOPY HOODS
                                     4-13

-------
               Table 4.2   MATERIAL COST (Ref.  160), Fuller Co,

CARBON
STEEL
CIRCULAR HOODS
RECTANGULAR HOODS
<. 3/16"
AF + $. 243/1 b
LG + $. 243/1 b
>_ 1/4"
AF + $. 227/1 b
LG + $. 227/1 b
    where A is total  plate area,  not including  structurals,
          L is length of hood,
          F is a pricing factor,  and
          G is a pricing factor.
F FACTOR
G FACTOR
DIAMETER
5
10
15
20
30
40
50
70
F
$ .90/ft2
.60
.50
.45
.40
.40
.35
.35
L/W
1
2
4
8
G
$12/ft
8
4
2
                            4-14

-------
     Since  10 Ga.  (.1382") is usually sufficient for hoods, the total  mass  of
the  hoods and structurals in the two examples is:
             250 ft2 x 5 .625 lb/ft2 x 1.2 = ~ 1690 Ib
             550 ft2 x 5.625 lb/ft2 x 1.2 =  - 3700 Ib
     The material cost, cut to size, is estimate from Table 4.2.
     Using these formulas, the material  cost is calculated to be:
             550 ft2 x $.45/ft2 + $.243/1b x 3700 Ib = 1150
              20 ft  x $4/ft  +  $.243/1b x 1690 Ib  =  490
     Hence the total price for the two examples is:
             35° Rectangular Hood, 20'  x  5':   $425 + $490 = $915
             50° Circular Hood,  20' dia:   $2010 + $1150 = $3160
     If skirts or booth walls are needed, figure material cost at $.243/lb.
The weight of the wall  will  be the plate  area (summation of the length times
width of each wall) times the material weight,   plus 20% additional  for
structurals.  For labor cost, figure cost at  $.30/lb.
4.2  Ducting
     Ducting has several  effects  on the size  and  cost of a  control system.
In addition to conveying  the  pollutant-laden  stream to  the  control device,
the ductwork can act as a heat exchange means for cooling of hot gases.
Also, it always  adds flow resistance or pressure  losses  that require added
horsepower for the fan.
     The four basic types of  ducting can  be classified as carbon steel,  stain-
less steel,  water cooled,  and refractory.  The differentiation between  types
                                    4-15

-------
is not necessarily based on construction alone but rather on the capability
of each to transport gases at different temperatures.   Water-cooled and refrao
tory ducts can convey gases at any temperature, but are economically used at
gas temperatures above 1500°F.  Stainless steel ducts are generally used with
gas temperatures between 1150°F and 1500°F or where the corresponding wall
temperature is below 1200°F.  Carbon steel ducts are used at gas temperatures
below 1150°F or where the wall temperature is less than 800°F.  In the transfer
of corrosive gases, stainless steel ducts can be used at lower temperatures.
For cold processes, carbon steel ducts are used exclusively for non-corrosive
gases.
     In designing ducts, a savings in the size of the ducts (increasing
velocity) will eventually be compensated for in fan horsepower, therefore,
the design velocity of the gas stream is maintained at a suitable conveying
velocity for the type of dust.  Typical velocities for industrial dusts are
listed as follows:(Ref. 88):
               DUST TYPE                   S        DUCT VELOCITY, fpm
     1)  Light Density - gases, smokes, zinc and             2000
         aluminum oxide fumes, flour, and lint
     2)  Medium/Light Density - grain, sawdust,              3000
         plastic and rubber dusts.
     3)  Medium/Heavy Density - iron and steel               4000
         furnace dusts, cement dusts, sandblast
         and grinding dusts, and most heavy
         industry dusts.
     4)  Heavy Density - metal turnings, lead                5000
         and foundry shakeout dusts.
     These velocities are presented as guidelines and have been developed from
practical experience and data obtained from industrial applications.  The
minimum velocity that must be maintained to prevent dust from settling in a
duct is determined from the following formulas.
                                      4-16

-------
      Vh   -   105  ()  d°'4                                  (ref.  152)
      where:      V.   =   horizontal  duct  velocity,  fpm.
                 SG   =   specific gravity (relative to water
                        at 60°F and 14.69 psia)
                  d   =   particle diameter, microns
      Vy  =  0.27  Vhd°'2                                      (ref. 152)
      where:     V   =   vertical duct velocity, fpm.
      The diameter of a  duct for a  specific design velocity and gas flowrate  is
determined by:
      D  =  13.54
     where:      D  =  duct diameter, inches
                 Q  =  gas flowrate, cfm
                 V  =  duct velocity, fpm.
     The formulas for determining the minimum duct velocity are based on
experimental data using relatively large clean dust particles (1-5 millimeters
in diameter).  In most industrial gas streams, the particulate is a mixture of
dusts inadequately identified as to size, configuration, and adhesive properties;
thus, the formulas tend to predict lower minimum velocities than those
recommended by industry.   A more detailed discussion of this is contained in
reference 152.
     Since the types and configurations  of ductwork are so varied, the cost of
these items must be estimated according  to size, type,  materials of construction
and plate thicknesses.   For ducting, the costs are developed on a per lineal
foot basts.
                                      4-17

-------
     The cost of the ductwork for any application must include accessories
normally associated with the conveyance of a gas stream.  These include elbows,
tees, expansion joints, dampers and transitions.  The costs of these items
are segregated from the cost of straight duct as shown in the following figures.
     For straight duct sections, Figure 4-7 gives the price for fabricated
carbon steel duct in dollars per foot as a function of duct diameter and
material thickness.  A 48-inch duct, 1/4-inch thick costs $83/ft.  Hence 100 ft
costs $8300.  Figure 4-8 gives prices for stainless steel construction and
Figure 4-9 gives prices for water cooled carbon steel duct.
     Figures 4-10 and 4-11 contain prices for carbon steel and stainless steel
elbow duct, respectively.  Prices are a function of duct diameter and material
thickness.
     For tees, the price will be 1/3 the corresponding price of an elbow
having the same diameter and thickness.  For transitions, the price will be
1/2 the corresponding elbow price (use large diameter for sizing).
                                            s,
     For expansion joints, Figure 4-12 contains prices for expansion joints
as a function of duct diameter.
     Table 4.3 contains pricing data for refractory materials.  Refractory
may be applied to capture hoods, straight duct, elbows, tees, transitions,
spray chambers, thermal and catalytic incinerators (for replacement), and
stacks.  The thickness of the insulation for these applications depends on the
thermal conductivity of the selected insulation, the temperature of the hot
face (refractory skin temperature), and the required temperature of the cold
face.  The following values may be used as a guideline in determining the
amount of insulation required when the temperature of the cold face is in a
still air environment at 80°F (ref. 153).
                                      4-18

-------
o
o
   700



   650




   600




   550
   500




§ 450

ctP -r r " n ~ ~ " • ' * t *- . • . . -I
Tp-ft • : - :: -[ • 4 -n T :] '• i • ~ ' ' * ^ ^ 14 1 ^ R-"-
• 1 1 1 1 j
i 1 1 , , L .
..i ... - : ::. • it. lit
i 1 4 i
L 4
*ss are based ";_"'"..}.'.' it i| "1 \.f

3 costs to 	 [ 	 1 1 	 1 . i i
V-UO V. J VW - - - - t 1 II
ic not <;plf- 	 1 J .4-Lj

I i (
s \ i '
_ „ 	 . . _ _ - -l-^-.. _i_ J^--Jt-
'-;•;•...__ - ; . _ _ .. _ . . 	 • „ ? * * . 1^,

f ...
• i ^ ' i ' j
i* t i
^ '
X ;
rf '
i^ - j .
r j i ^ i j T t
J 1 /Oil TU4^b _ H ' _ 4_ ^ ' '
J 1/Z Thick ^ ? .TT "J ;.4 r " " ~r

	 	 iT fl tC^ 4 	 . 	 1 	 ,_*_Ł 	 L_i 	 1_| 	
. .. _ ^, . .. . . _ j^y • • ~ i

j i j " ^ *" r j
' f * ' i l
f 1 L ' '""^ ""^
? ^**^/Q" T*l» 4 I* '
- _^, _ . _ _;. _ j/o iniCK •"" "j
-*_ _. 	 _--^?_.- -_ _ .. 1_: ft! _ 4._ I
? 	 . 	 , :. 	 	 	 r Plate
. * * i i 1 1 i
--.. .'-- - UL it" " •
.. -*• 	 . . ~ _ 4 44" ±r —
,* - 	 	 - - -) -f-f 	 h^ 	 ;
--.--..,---------- - ------ h -- -f-|-|---|- -.---I.

^ I i '
1 lit- L J

j 4 MI t " !
' ' * E I
:":±±''" *?;;;; 1/4" Thick Plate

^ '
'*•- • ~t ' — -i H , 1 1 1 1 1 1 • 1 1 , r ' " •
i i ' 1 1 1 1 i l — . - -r. .

* * | , J
:'!::-: :!'i 3/16" Thick Plate - Ł 	 l
......

1 Illl 1 lllll ^ r
:: : *:::T~ . f T IT \ T X Pp t t'll
., 	 1 - L LL 1 I
..j 	 ±. _L-tTt" L- M 14
1 -1-1- i i i' i 1 1 . m. . iij t

* • LI ^AIII^^O* Pnc'I'C Ho\rol nnarl fv*ran
— r — T^ ouuii,e. uub L:> ucvc i upcQ iroin —
i i r ' , " Qaia Trom rui ier LO.
fflT" M: -tri- l-m-i+Hl - !- Hlfil •-:
           10   20   30  40   50   60   70  80   90  100  110  120 130  140  150  160 170   180   190   200

                                         D, DUCT DIAMETER, INCHES
Figure 4-7   CARBON STEEL STRAIGHT DUCT FABRICATION PRICE PER LINEAR FOOT VS. DUCT DIAMETER AND  PLATE THICKNESS

-------
ro
o
      o
      o
      eg
      2
      cc
      LU
      D-
      O
      UJ
      LU
      V)
      to
      Ul
       Figure 4-8
                                                                                           Source:  Costs developed from
                                                                                                    data from Fuller Co.
                                                                                          130   "140   150"  160"" 170    180
                                 D, DUCT DIAMETER, INCHES


STAINLESS STEEL STRAIGHT DUCT FABRICATION PRICE PER LINEAR  FOOT  VS.  DUCT DIAMETER AND PLATE THICKNESS

-------
r\>
	 ' 	 	 - ...... - ~ .
	 - 	 -• •-- • 	 -- 	 -


•'-•'• NOTE: 1. Estimates include flanges ever
U A/I 	 n m Ł «.
aw im^jj 24 feet.
. Flanges and inner duct of 3/8
tjjtfg plate construction.
•- M4+44JI * stringers and outer, duct of I/
§ :::::: plate construction .
U_ 	
2 wo --imnjmiiUtiiiuiuuutiimuiiitiiuiiiim^i+iumuiui^H
2 ;:;;; ;:;:::v;;- -:::; ;;::;:;;:::. ;; :-.. ..- .-.;n;:-;:::. --I- -.
z Hittttttttttl 1 H mill Mm m i Hm i r in It m 1 Ml
H- 1 	 	 	 t"" '
_i : . . . 	 - 	 	 t... .
DC. ' 	 - 	 - 	 	 L -
UJ ::::::•;• . . - ..- 	 ..[....
Q. ttttrrH til 1 till till lit II t fu 1 1 mil II lluil'JI 1 till "
** 300 : ' ' ' :::;...::..: 	 :::.,..: 	 :...:::.; 	 L . : ; , .

||2 ::::.:::.:• " , ::• . 	 '
10 	 f - 	 - -
O 	 • ' • • • . . . . . . . : . .

	 -...['. . • ....
Ł ..::::::-.:- t ' . • '.:•-- 1 •.:.;•-•::.•
" ?no RffliltiMm W
Q 	 - - T • .>•
UJ
_l -•- 	 -.; . . 	 :... .. _ . i: .. .,1! ._ 	 ,.
3 .-.....--- j-j- Jrffr i. ?, -^ +(^(-
O :.::.". . < \\jjf T 1 i -
. i^i ; • • • , I '
f^ ' i ' '• :
UJ " 	 	 .:. . ..... tl. ,,., L L..f. . ... ill! .
^ 	 ... t : i !:i r . '!| ;|f
3e inn • • - ^ ;: ; ---------- t- ill M
•^ 1 Uu 	 i i i , f , ^ 1 1 i
ji '. •' :' !l I
	 j. . Ttt||4llli 	 :.:...II 	 : 	 4

	 •• • 	 • M ' r
o - -- i J.^iiLllli" 11
0 20 30
D, DUCT DIA
' \ | 1 1 . • 1 1 i 1 1 j • ] . . » • . • • i . .
	 ------.- - j l" | 7 r 1 " f I'l" ' ' 1 '• • • • I j ' ; '•:'•.'. ' . . ' '
1 j j 1 i ! j ! I i ! 1 ! 1 !".'•':;; i :;:;::
|:i L f ^LrtilLiZ[ - ili '• ;; illEiill-Pl;
y 1 ! • 'I i : u i n it, j i |F V
- \ T t r if itt T ifr^trt^ - ^tti
..!..._ .....:. 	 ;....! 	 _ 	 M+i.L^i.l -...+4. ll
- - 	 	 "' f . . T T T T
411 . . ' ° ' - ~ - ' " " . . - . " " -1.
••: ::•••: 	 - 	 •••:::::•: : : : : 	 7 7* ~ .
: : • : : .::.-. - • . -:..:• E . . : - . • . : - j ! : • : :
, - I, 	 ;• "- .:. E E:-: | r : : : f i • ' it ' i
|1|JH
- 	 	 .,.-. \ . , . 4--t.
	 	 •;.'-• 	 3" -
.,.!:.:::. : : , : : : . ! • 1
..,.!•' ;-.. ' : • || 	 . ' 1 ' " .:j ^
	 - •'' 	 ' H l ! ^ ••: \-±\\\ 	 I!' 1
,,•' • ' . ' ' • [ • 1 ' - - -j "
,.':''• 1 | : : .:•.:.• • ! ! ! I"" L ! : ; i : : j | : :
:,..;.. ., 	 	 ; 	 4- -uni '!li- : U;i" * ll:> • '• : ::
.:.+f. * + |t-.: $=51.84+4.450 j 1 : :'''.' '• \ ''•'•• •'•"''
	 i i •-..::!::: . :

1 I" r:|[ . Tl! ';.;! IMI it|| i :'• ^|j '••; : j
jiUliil iJ4 4i!liii!t 111 ';iilli lli: ;:'! • ''
I '. It!:! 1 i ". ' : : ' ' r U J. J.1 : i_ .. . . : : .
I'-HHj --4li-.il :
1 i; ! :m — J-i t . .. J i .; LL SniiiTTP" Tnctc Hpv/plnnpH fynm
'• ':' ! j ji 1 i ' !( data from Fuller Co.
j i YT JJj^jiN JiJ T ^"" ^T^1 •• • 1
ijiiil ffl ffl 11 i' i iii' ; '?' r j^iEi' :ii LJL :"
40 50 60 70 80
METER, INCHES
         Figure  4-9   WATER COOLED CARBON STEEL STRAIGHT DUCT FABRICATION PRICE PER FOOT VS. DUCT DIAMETER

-------
•tfl-
on
CL.
O

E
o
CD
CO



o
«=c
o
30, 000 -, 	 1
d

NOTE
i i
| !
1 i


H~H
1 I'|J

• i
i '• i




i t ]



' '• ,
'
1,000 =
=

i

LJ — L _

~ •






i.
2.
' i








i ' |




: ' t
i ; i

1 ) 1









f
u
t
Source:

J
inn -






i













MM
Estimc
R/D =
\






i f \
• f' '
/








I/

t ' » • J
/•/

'/]/'j
/!/(/






__L-1 	
ites
1.5
— 1 — I
ir
i
i i
- 1/2"



^
i— '
— i
-nX-2


/
f

/
f


j
t.
*


Xi Jf . 'V

J



L

Jr ' '
~f~ " '- •
f i ; .
' •
i ! :









I/


p-L-j 	 , 	 1


- ' . . ' -i
iclude
( i i
Thick
^
«•
_
^
fi_j 	

i


!
1

i '



J

I j
8" Thi
—i — i — 1 —
i


. -,
flangt
i i
Plate
_
LU=-
t*-1-?
^i-
— ~t>i
, t/v.-
X^ — r~
=^-3,
	 i 1 - . .
I i | 1

{ i
•

-
| :
\-\ :
1 i 1

!
i j
i

ck Pla

i ' '
C
- • 	 \
>s ^
/
MI-
^^
ne11 TI


i


1 j (
i : • .


! ;
j
j
-f-rt _,.
te
"TT-HT
~"[~~ * 1
JRVE E
S THICKNESS
Costs developed -
from data from -
Fuller Co. -



































..

j




I
[J.
i


1
1/2 $=-16
3/8 $=-12
1/4 $=- 8
3/16 $=- 9
1/8 $=.12
JILLLLIU.

1 • ~- • —
— -J — L. -- 1— -I —
— »-+ : jv
1 1^
xW
/4" Th
lick P



i

! f ;
' }



\ '.',',
;
1
i !
— i — i — ' — • —
3UATIO
EQUAT
.41+24
.89+21
.21+18
.38+16
.07D+.
LiLU.

jx"
Thick
ick PI
_1 	 1 	 1 	 ! 	
ate 3=
— ' — 7-7-


i i


i




, ! \


Ml!
MS
IONS
.710+ j
.10D+J
.410+.;
.760+.;
17602"
LUJ_L
---^— -'1
— i — \ — i —
i
1 i
H ' 1 1
Plate
I—T-T-I ^
ate :
u i i i -
1 — ' — —
•
j )
i i

-• ; ; ;



. I
1 i

— 1 ' ; — • —
-4-i-^-t-

180^ t
IBDi t
-4D Jr
?05D^_
1 ~
            0    20    40     60     80    100   120   140   160   180   200


                               D,  DUCT DIAMETER, INCHES



  Figure 4-10  CARBON STEEL ELBOW DUCT PRICE VS.  DUCT DIAMETER AND PLATE THICKNESS
                                    4-22

-------
100,000
LU
o
1— 1
OH
0.
O
Q
3 10,000-
LU
f
LU r
LU
I
i
1
—

1 1
NOTE :
j — i — i —


co pq
co 1-+3
LU j— . '

I— 4
CO












i nnn

-t— H-
1 | . •-—




i : , • — :— t—







: i i J
^ 	 T
i
! 1 ' ' '
I • ! ,
i i A
I /
1 : '


i

1

(
\ 1 1
1. E
2. R
3. C
f
i
!
1
| |
l\_ 1
1
St
/D
OS
roi
V
i

rrj/t^
' 1 I/ /
— L-/.

1 /' 1

f J / 1
r Vp

— >
/
/!
H

i

/ f \ \
1 • ••
1 i . •

/ 1
TT~
/
;

1
i i I
i mates
= 1.5
ts dev<
Tl Full!
2" Thi
-r-M-!-
— i — ' —
w
' /




f\ \
—, 	 i — j_
— i . --( - .- -
	 1- ' '
	 TU T
-J- IM1










1 L
inc
slop
>r C
:k P
1 1
j ;/
LL
lu<
ed
0.
la
H-
*
(L.
^
X

^


: > ' —

1
^=PCI
CKNES
1/2
3/8
1/4
3/16
1/8

J
S

J ! 1
de fl
from
te^-
.
f} i ' ,
r
Ą \
\
a
i
i*
r^
-
-i.j... j.
1/8"
-r-] 	 r
! 1 '
1 '
T



j
nge
iat
i 1
s =
a ±=
^
p —
1 I L<<
N
-3/1
i i f
I I ' I
i l I
6
— ! — | — i — t—
hick
P
' :
—, 	 .-, 	
^


— i '< • . : 1 ' i-
IVE EQUATIONS
ia
$=272+32
$=199+23
$=134+19
$=124+17
$=19.040-
J4-LU-
S^-3/Ł
1
11 1
i
— — i —
fhic
i i i
late-
4 •

• i
— 1 — H-
— f— j-

--i-
1 1
!" Thic
	 1— I —
Thick
i ' T
k Plat
j i
i i i






JATION
.30+2. 80^
!3D+l!46D,
.eD+l.QSD^
I-.703D2
^ :-:
\LS^f^-
,k Pla1
Plate
i i ;
e . ' ,
i : ! i
1


















i
;e


0
40
160
200
                                   80          120



                              D,  DUCT DIAMETER, INCHES



Figure 4-11   STAINLESS STEEL ELBOW DUCT PRICE VS.  DUCT DIAMETER AND PLATE THICKNESS
                      4-23

-------
 I

CO


§
o
o
•-3
    5000
                                                                   50          60

                                                             DUCT DIAMETER,  INCHES
                                 Figure 4-12   CARBON STEEL EXPANSION JOINT COSTS VERSUS DUCT DIAMETER

-------
                                                         TABLE 4.3

                                                REFRACTORY ESTIMATING COSTS
TYPE
Super Duty Firebrick, 3200°F
Insulating Castable, 2000°F
Dense Castable, 3000°F
Plastic, 3000°F
Ceramic Fibre Matt, 2300° F
APPLICATION/ FORM
Brick
Cast In Forms,
Trowelled, or Gunned
ii
Rammed w/Pneumatic
Hammer
Like Mineral Wool
THERMAL CONDUCTIVITY
(Btu/hr.-ft2.°F/in.) @
1000°F 2000°F
9.3 10.0
1.9 2.1
5.1 5.7
N/A N/A
N/A N/A
PURCHASED PRICE
($/cu. ft.)
$ 7
$ 6
$25
$13
N/A
INSTALLED COST
($/cu. ft.)
$90
$30
$75
N/A
$25
4*

HO
cn
         N/A = Not Available.

         Data based  on  ref.  37.

-------
                                                                   *
Hot Face Temperature (°F)     Cold Face Temperature (°F)         L/K.
                                          1200                    2.7
                                          300                    1.1
                                          400                    0.6
          1500
4.5
1.8
                                                                 1.0
                                          200                    6.0
          2000                          (  300                    2.6
                                          WO                    1.5

      where:  L  =  Insulation thickness, inches
              K  =  Thermal Conductivity, Btu/hr-ft2-°F/inch
                    (obtained from Table 4.3).

To estimate  the cost, determine the surface area to be lined, the thickness
of the lining, and the type of refractory tb be used.  Compute the cubic feet
of refractory required and multiply by the price obtained from Table 4.3.
     Prices for rectangular and circular dampers, with and without automatic
temperature regulated controls, are contained in Figures 4-13 and 4-14,
respectively.  Rectangular dampers are priced as a function of cross-sectional
area for length-to-width  (L/W) ratios of 1.0 to 1.3.  Circular dampers are
priced as a function of damper diameter.  These prices are for dampers only;
the type that may be used inside a duct.
                                     4-26

-------
      12
ill
NOTE:
                             1.
                             2.

                             3.
Dampers are louvered type.
For stainless steel construction,
multiply price by 3.0.
Price with controls 1s a nominal
estimate for temperature regulated
dampers.
Source:  Damper Design, Inc.

Do not extrapolate beyond range.
   o
   o
   o
   o
4*  DC
I   UJ
rv>  O-

"  I
   CD
   O
   UI
   o:
                                23456
                                              DAMPER CROSS-SECTIONAL AREA,  1000 SQ.  IN.

                                Figure 4-13   CARBON STEEL RECTANGULAR DAMPER PRICES  VS.  AREA

-------
o
o
o
to
UJ
OL

CL
O.



O


OŁ

•a:
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
n




: :":
' ' rt" ' ~ '
— - — h —
-.

! '
i
4
-r~\
— i-i — 1
. - - -
H

—
—
| 	
:•
— f
—
T

—
' ' ~.~ '.


—
—
:::;t::-

: ::
	
•
" "T1*1

~:~..:

!:•::
1.: ' : :

-._

-

NOTE:
;::Ei-::-:
• i|.:.
._..
-TtT
f*T
i —
•i— •
4
4...
-|—
P
--
/
1


	
::-:]
	 	 "
1
. i ^ :
. 1 '. , '
	 —

i.
2.
3.
4.
5.
i . i ' <
77—
1 ' - i
p 1 f '
I > ' '
\ 	
. J i.j-
P

C
F
n
F
{
i
c
[
1
iŁ
i : i i
*
Ł!
)amp
"or
lUlt
>ric
jsti
"egi
tour
>o r
•anc
• • • t
J—
«


ers
sta
ipl
.e v
ma1
ilal
%ce:
lOt
»e.
::
-L, .i
M
a»4*
ar
in"
y F
• . i
:e 1
:ed
I
ext
-H-
.: :'
y
•--M-
•e louv
ess st
irice t
i contr
ror ten
damper
Damper
;rapo!e
^
i ' . •
— —i
— t-H-
	

7*
ered t
.eel cc
>y 3.0.
•ols is
iperati
•s.
Desigr
ite be)
•.--I
=^3
^^i
7^t~" '
e. — — -
- --t- •
• - B
— .>_ .
j-" — i —
— t —
ffFTT-
ype.
nstruc
a non
ire
i, Inc
rond
. . i
-1-^
— .— _
t!
. . .
— ~
-y

*
- •
' • T"
	
l^j
' : ' '
-— r
tion
linal
i
• i
::•::! r -'
... J , . .
_ — r I . 1
— r-t - — • •-









L -j
/f •
/
/
/
^ i
t —
— 1
L
^^
-r; -1'
	
• - • • -
i


•
^ /
> r
/...
— - - - 1
	 ^ 	
i - - -



	 :._.
•


;
	 t

/
—
i

. -
T7-
....
1. .

^
—
- -
' ' -
- - --
           10    20    30    40    50    60    70    80    90    100   110

                                    DAMPER DIAMETER, INCHES



           Figure 4-14   CARBON STEEL CIRCULAR DAMPER PRICES VS. DIAMETER
120   130
                                          4-28

-------
 4.3   Gas  Conditioning
      Gas  conditioning  equipment  includes  those  components  which  precondition
 the  gas stream  prior to  the control device.  This equipment  consists  of mech-
 anical collectors, wet or dry coolers, dilution devices, etc., which  are used
 to temper or process the gas stream to provide  the most efficient and economical
 operation of the control device.
      Mechanical collectors, such as cyclones, are used in  some cases  as  pre-
 cleaners  to remove the bulk of the heavier dust particles.  These devices
 operate by separating  the dust particles from the gas stream through  the use
 of centrifugal  force.  Construction is such that centrifugal force is  exerted
 on the gas stream through the use of a tangential  inlet, producing a  downward
 vortex.   The particles impinge on the sides of the cyclone and are removed
 from  the  bottom.  The gas stream changes direction at the base of the  cyclone
 and exits in an upward vortex through an axial  outlet at the top of the  cyclone.
 Cyclones  are available as large diameter conventional cyclones or as units
 having small multiple tubes for higher efficiencies.   The efficiency of a
 cyclone collector is determined by the entering  gas  velocity and diameter at
 the cyclone inlet.   Theoretically, the higher the  velocity or the smaller the
 diameter,  the greater the efficiency and pressure  drop.   All  of these parameters
 can be correlated to the collector inlet area to establish the size  and
 ultimately the cost of conventional  cyclones.
     Multiple tube cyclones are designed for high  efficiencies and are normally
 used as a  primary control device rather than as  precleaners.   These  devices
consist of banks of tubes,  nine inches in diameter or less, and provide
efficiencies of up  to 80  percent for particle sizes of approximately 5 microns
 (ref. 154).   The cost of these  units is estimated  to  be $1.00 per cfm for
                                       4-29

-------
capacities of up to 1000 cfm, $0.60 per cfm for 5000 cfm,  and $0.50 per cfm
for capacities of 10,000 cfm or greater (ref.  154).
     For the purpose of precleaning, conventional  cyclones can remove the
majority of dust particles above 20-30 microns in  size to  reduce the loading
and wear on the primary control device.  Figure 4-15 provides a means of
estimating the volume capacity of mechanical collectors (conventional cyclones)
as a function of inlet cross-sectional area.  Figure 4-16  provides a means of
estimating the critical particle size for collectors vs. inlet area.  Critical
particle size is defined as the largest sized particle not separated from the
gas stream.  A guide to estimating cyclone shell thickness and pressure drop
can be obtained in references  154 and 169.
     Figures 4-17 through 4-21 contain pricing data for mechanical collectors
and components as a function of inlet area.
     For example, suppose 50,000 cfm is to be passed through a mechanical
collector  prior to entering a  baghouse.  A pair of 25,000 cfm capacity collec-
tors with  a pressure drop of 4" AP and an inl^t area of 9-1/2 sq. ft. would be
satisfactory for the purpose.  The critical particle size is found to be
28 microns.  For 10 Ga. carbon steel construction, the price of the collector
would be about $5100.  The cost of additional components would be:
             support:    $3100
             hopper:       880
            * scroll:      1600
                         $5580
     The total price per  collector  is thus  $5100 +  5580 = 10680.   In general,
price of collectors varies directly with  inlet  area  since the mass  of the unit
increases  with increasing area.  However,  these curves  give  prices  for only
single-unit collectors.   Multiple collectors  in parallel  can be  used for high

*Ductwork at outlet  of  cyclone to direct flow to  horizontal ducting.
                                      4-30

-------
                                                     (Ref. 160), Fuller Co
0    1   -2    34    56^78    9    10   11   12   13  14
                       A, COLLECTOR INLET AREA,  SQ.  FT.

      Figure 4-15   CAPACITY  ESTIMATES FOR MECHANICAL COLLECTORS
                               4-31

-------
                                                   (Ref. 160),  Fuller  Co
                        5    6    7    8    9    10  11
                        COLLECTOR INLET AREA, SQ, FT.
12   13   14
Figure 4-16   CRITICAL PARTIAL SIZE ESTIMATES FOR MECHANICAL COLLECTORS
                              4-32

-------
   8.00C
  6,000
o
O
  4,000
  2,000
      Q H-nf-rth
                   ;;r;rnT
                     f^.


                        ^

                                "f "' irn "~
                                  ^
                                                 ri^n

                                                                       x
                                                                          '.if.
                                :i:iir:|/T
                                                             "^
                                                                   1  rvtX jr
                                                                  /_
                                                          -,\w
                                                       J4-—
                                                       ^n
                                                      ^):.~
                                                           ••:•-!•
                                                             ••v-.--.
                                                                 :~]'

                                                                            ••t--—
                                                H--;
                                                           E| (Ref.  160),  Fuller Co,
4    5    6    7    8    9    10   11

   A, COLLECTOR INLET AREA,  FT2
                                                                                ^^
                                                                    12   13   14
  Figure 4-17.     MECHANICAL COLLECTOR PRICES  FOR CARBON  STEEL CONSTRUCTION VS.  INLET AREA
                                      4-33

-------
UJ
o
cr
o
o
u
0    1    2   .3    4    5
                                     $   f   8    9    10  11   12   13  14   15

                                   A, COLLECTOR INLET AREA, FT2
    Figure 4-18   MECHANICAL COLLECTOR PRICES FOR STAINLESS STEEL CONSTRUCTION VS.

                  INLET AREA
                                         4-34

-------
   3,000
QC
O
Q.
D-
   2,000
   1,000
     400
                                              Segment
                                                1
                                                2
                                                3
          EQUATIONS
                    Equation
                  P = 570 + 148A
                  P = 1026 + 143A
                  P = 1938 + 120A
Do not extrapolate beyond
range.
                    2     3
   7
                                                                     (Ref. 160), Fuller Co. =
T2
                                     A, COLLECTOR INLET AREA, FT2

         Figure 4-19   MECHANICAL COLLECTOR SUPPORT PRICES VS. COLLECTOR INLET AREA
                                             4-35

-------
       4,000
       3,000
       2,000
   D-
   O.
   O
       1,000
                                468

                                 A, COLLECTOR INLET AREA, FT2

Figure 4-20  MECHANICAL COLLECTOR DUST HOPPER PRICES FOR CARBON & STAINLESS  STEEL
             CONSTRUCTION VS. COLLECTOR INLET AREA
                                        4-36

-------
O
QŁ
O
     6,000

     5,600
                Steel
              Stainless
              Stainless
              Stainless
              Carbon
              Carbon
              Carbon
   Curve Equations
Thickness     Equation
  3/16"   P=513+618A-12.9A2
  10 Ga.  P=462+432A-12.0A2
  14 Ga.  P=352+307A- 9.W
  3/16    P=310+214A- 4.1A2
  10 Ga.  P=290+165A- 3.0A?
  14 Ga.
P=269+143A- 2.2A
                                     (Ref.  160) , Fuller Co.
                                     Do  not extrapolate  beyond  range
                             A, COLLECTOR INLET AREA, FT'

  Figure 4-21  MECHANICAL COLLECTOR SCROLL OUTLET PRICES FOR CARBON & STAINLESS STEEL
                         CONSTRUCTION VS. COLLECTOR INLET AREA
                                        4-37

-------
 flow rate when the flow capacity exceeds that of a  single  unit.   The price
 of these combination units can be estimated as the  summation  of  the  costs
 for each cyclone plus 20 percent for ductwork and structurals.
     Coolers and spray chambers are used with systems handling hot gases to
reduce the gas volume to the collector or, in the case of spray chambers, to
add moisture to the gas stream to reduce the resistivity and enhance  the elec-
trical characteristics of the dust for electrostatic precipitators.  Dry-type
coolers used expressly for cooling the gas stream without adding  water generally
consist of radiant "U-tubes" of 30 to 60 feet in height and between 12 and
36 inches in diameter.  These tubes are manifolded together both  in parallel
and in series to provide sufficient heat transfer surface to reduce the gas
temperature to a value compatible with operation of the control  device.  The
number of required "U-tubes" in series depends on the inlet gas temperature
and the required outlet gas temperature.  The number of "U-tubes" in  parallel
depends on the volume of gas being handled and the desired gas velocity per
tube.  A discussion of the design criteria and a method of sizing  U-tubes
coolers is contained in reference 88.  The cost of a cooler can be estimated
from the number of modular "U-tubes" of a given diameter and height based on
the desired temperature drop and flow rate for the particular application.
Figure 4-22 contains prices for  U-tube  radiant coolers as a function of the
number of units, the diameter of the tube, and the height of the tube.  The
term "units" refers to the number of U-shaped tubes; e.g., if the cooler
consists of three U-shaped tubes in series and four in parallel,  the total
number of units would be 12.  The tube diameters shown in Figure 4-22 are
those typically used in industrial applications, however, for other tube
diameters and material thicknesses, a cost estimate based on $1.20 per pound
may be used.
                                      4- 38

-------
  NOTE:   1
Price includes manifolds,
         and tube.
100
90
o
o
o
LU 8C
o
1— 4
a:
a.
ce
LU
cs
o
X
LU
1—
Ł 60
LU
1—
-=™
.LU
LU
to
g 40
Of
o
o
Ł30
o
»— 1
CQ
 4-

..


^4

.-,
H —

:!::


--!---
•::.j::;:
/
"/:

qji
...
tili
^

P

•*rr


'•!!
~-)
"T

1
-.•-
".,
' ' '
•*-1- -
::r
Q
> .-Tt
_-
(•-»*-
•;:
i •
.... . .-
M
. . ! i . .' . "
~i7
"•&..
Ł<•••:


| . .
••;:
"i?
-!*-


/:

r~



f
1— i-
• rr-
""T1"
'•:

I ! •
	
"^ "
4-J
i?
— i . .
:::^-:

::: :_:

T:
pfcl
1
— .-
-— T-r
1..
. .-
— -
i 1 ' '
irrt
rn±



--
nil
-r
1 	 *•
— — i-r-

Ą
"1
--
	 »

-r-



-r-|r
"U-

-J?


— j
77T
f*7
lr'
T. ft


..-:


[77773
::::


=r.
— h-
-iti
t^
^
F::

....
;ri-
T* • ~
,r-
H


...


:~







.!..

rrn.
V
•:-.:
J

- — „.
_™

mi


• i -
~trl





-/
:::L
IS
-t?


--4
Jr

= ,:}::::
4-


ju
^

i
— i • -

i



:
:

• •-. j
$>
I..: .
""



:::.

. .: .
MX
/
* \ '
•:::!-::
..:/*
/ *^
w^-
1 1
:.,d r.!:;:
j-.
'::j. :.
::::;::f


.:?:

-J
'"••*



i?

j
i
^ PRICE ADJUSTMENT FOR
HEIGHT
10'
20'
30'
40'
50'
60'



t





I ; •
'-::':\r.r.

: :.;:;:,






^L
. .....^
•••--•
. ; . : .

HEIGHT

". :'.'.'.
:: :H-

— -
i ' :
" . .

i

:;

::J


::..
— •
— -
"1 "
	 i_-

......

DEDUCT/ADD PER UNIT
12" 18" 36"
-$690 -$1070 -$222C
-$460 -$ 715 -$148<
-$230 -$ 355 -$ 74C
-0- -0- -0-
+$230 +$ 355 +$ 74C
+$460 +$ 715 +$148Ł
For stainless steel construction
multiply total price by 4.2.














)
) -
) ]
' I
2
  8
                           10   12   14   16   18  20   22   24   26   28
                                  NUMBER OF UNITS
Figure 4-22   FABRICATED 40 FT HIGH  "U"  TUBE  HEAT EXCHANGER PRICES WITH HOPPERS
             AND  MANIFOLDS
                            4-39

-------
     Wet-type coolers or spray chambers cool  and humidify the gas  by the
addition of water sprays in the gas stream.  For effective evaporation,  a
cylindrical chamber is usually provided to reduce the gas stream velocity at
the point at which the water is injected and where evaporation occurs.   The
diameter and length of the chamber is dependent on the maximum droplet  size
of the sprays, and the relative temperature and velocity of the gas stream and
water droplets.  Generally, gas stream velocities are maintained at approx-
imately 10 feet per second with inlet spray water pressures of approximately
100 psig.  Increasing the water pressure results in reduced water  droplet
size, faster evaporation, and consequently, smaller chambers.  The cost of
spray coolers is based on the size and volume of the chamber and the materials
of construction.  Figure 4-23 contains prices for spray chambers for various
inlet gas volumes.  The diameter of the chamber is based on a gas  stream
velocity of 10 feet per second and the length is based on an L/D of 3 which
is suitable for most spray cooling applications with water sprays  at 100 psig.
A discussion of the relationship between the water droplet diameter and the
time for complete evaporation is contained in reference 155.  The  quantity of
water required for spray cooling can be estimated from the desired change in
enthalpy of the gas stream divided by the latent heat of evaporation of the
water at the spray water temperature.  This assumes that cooling takes  place
along a constant wet bulb temperature line.  The volume flow rate  at the
cooler outlet can be determined by:
     n  -  1545 T     Wdg  .   Wwv
     Q  -  --
                                       4-40

-------
o
o
o
 I

CO



8
o

0Ł
LU
CO



CJ




i
Q.
CO
   40
   30
NOTE:  1. Based on chamber velocity of

          600 fpm.

       2. Length/Diameter = 3


       3. Carbon Steel construction.


       4. Does not include refractory.


       5. Spray chamber cost includes

          vessel and support rings,

          platform, ladder, gratings,

          spray system, and controls.

       6. Source:  Ref. 160, Fuller Co.
                 40          80          120         160         200


                                  INLET GAS VOLUME - 1000 ACFM



                   'Figure 4-23   SPRAY CHAMBER -COSTS VS. INLET GAS VOLUME
                              240
280
                                              4-41

-------
     where:      Q  =  Volume flow rate,  cfm
                T  =  Outlet temperature,  °R
                P  =  Pressure, Ib/ft
              Wdq  =  Weight of dry gas, Ib/min
              W    =  Weight of water vapor, Ib/min.
     The quencher, used for hot processes> is fundamentally the same as a
spray chamber; however, it is much simpler in operation and requires minimum
controls.  The objective of using a quencher is to reduce the gas stream
temperature to the saturation temperature and this is accomplished by flooding
the gas stream with cooling water.  Since the quencher is operated with more
water than required to reach saturation temperature,  outlet gas temperature
controllers are not necessary, nor are the banks of fine atomizing spray
nozzles which are normally operated by these controllers.  Quenchers are
usually fabricated from corrosion resistant materials, or are refractory
lined, and can be either horizontally or vertically oriented.  Costs for
quenchers, shown in Figure 4-24 are based on inVet gas volume and materials
of construction.  Quenchers also act as a precleaner for larger sized dust
particles with the collected slurries being returned to the waste treatment
facility.
     The simplest method of cooling is mixing the gas stream with ambient air
introduced through a dilution air port.  Dilution air ports are provided to
protect downstream components from "over-temperature" by diluting the hot gas
stream with cooler ambient air.  Dilution air cooling requires the least amount
of equipment compared to other types of cooling; however, the downstream equip-
ment such as the control device, fans, and ductwork are substantially increased
in size (and cost) to compensate for the additional air.  The components for
dilution cooling generally consist of a duct tee, damper, and temperature
                                      4-42

-------
    80
    70
    60
   50
o
o
o
(/>





O


or

UJ
z
(_}


UJ
   40
   30
   20
   10
                  40            80


                    ^



                     Figure 4-24   QUENCHER COSTS  VS.  INLET GAS VOLUME
                                           120          160        200

                                       INLET VOLUME - 1000's ACFM
                                              4-43

-------
controller.  The damper is continually adjusted for inspiring ambient air to
maintain the downstream gas temperature at a pre-set level.   The cost of the
equipment for dilution cooling, shown in Figure 4-25, is based on the duct
diameter and represents the cost of ductwork for various plate thicknesses,
damper, sensor and temperature controller.
4.4  Pollutant Removal and Treatment (Dust)
     Dust removal from collectors (baghouses, precipitators, cyclones) can be
accomplished intermittently by manual means or continuously by screw conveyors.
For applications having light dust concentrations, the collected dust is
stored in the hoppers of the control device and periodically emptied through
a valve for disposal by truck or local transport.  For heavy dust loading
(inlet dust concentrations in excess of 1 gr/dscf) screw conveyors are gener-
ally used to continuously remove the dust as it is collected.  The cost of
continuous removal equipment for heavy loading is based on the diameter of
the screw conveyor and its overall length.  Figure 4-26 contains prices for
                                               s
screw conveyor as a function of conveyor length and diameter.  As a general
rule, a 9-inch screw conveyor is satisfactory for gas flow rates of up to
100,000 acfm; 12-inch conveyors should be used for higher flow rates.  The
length of the conveyor depends on the physical configuration of the control
device and the distance to the disposal site or storage container.
     Waste removal and treatment facilities for both scrubbers and quenchers
generally consist of a thickener and vacuum filter or centrifuge.  The over-
flow from the thickener is recycled to the scrubber and quencher while the
heavier solids are removed for dewatering by the filter of centrifuge.  The
costs of thickeners, vacuum filters, and centrifuges are completely covered
1n the following reports, also listed 1n Appendix C as source Nos. 119 and
128.
                                     4- 44

-------
22
21
20
19
18
17
16
15
<~ 14
o
o
2 13
LU
a 12
Q-
O
CL.
« 10
o 9
P
d 8
0
1 i 1 -7
H—
CO
ct:
rf _
5 5
4
3
2
1

-^-
:.

NOTE

. '; •
'.'".]: •
•:|::--
r:: :•»::::


1 -
I

. . -j - . .
T::: f .i.:i.
. :"TTT
1
n:"1.---
•-- •;-
-
.::.:„.

M





':;:!;: '
..!....
:".):.-.

",±:



	 .
t — • T
.. .

... : I : . .
-------
T~~t~~''
— •
~"
.iuJ

: 1.
2.
3.
-T-
• :-;::::

•;}:;••



... i ...

: : . i: : : v
_iu4^_
•^rq™
T" — ~
	 , 	
:--^::-'l-^I--:
_^LU^
— .^ — .^
~;Ł:T~- •
-:p:
__^_



—I-
__,__
— ' t~" — r
^i^
1JT


Dampers are louvered type.
For Stainless Steel constructior
multiply price by 3.5 (includes
damper ductwork, and screens).
Price of included controls is a
nominal estimate for temperature
regulated dampers.
— r-~i::4::..J .. i :| • :!::.: ::. :: - ::. ::: : ' : :
i- 4--1-4-- -1 	 ' 	 1 -:...|- — l-r-f— -:.::: j .;

::ri:::
	 . . —
	 . . .

"-'"-'•'•
^
pi
=a;
r-F
....

:; ::!"^:_
^IIF-
	 j . _. .



— -_3 	
;:-:i;:, -^ -'




-••
:T::
-•-


i .' :

— T
- —
.. .
•_:i_:
i
--^,-::
::• .f-:-:j
-TT*. r.
^tz::::S:::

^
-t-
t.:i
r1— >
"-)



rtr
7-
— — JJ
•:;• '! !

-
-j:: ::':
• : .•:;
• • t



• j: •;

•III •:-
! ' • ' . :
_ ..!: j • !..__;;.."
^ '
. .j.: \'-^-^f.
. 	 j,-.L.^Ł
-• * —
::-:h- :

M
fjt
m
n
— „ —
^i.j;::
i--^.:: --::;:-•
--:if . 1 ..-:: :;t

$jf
^L-:::
	 1 	

	 .-,-_, 	 	 -






tnr

-^-.j. 	

[^
^ iy
;t- i /



1/2" Thick
""^•i/i "
: i: •.''• ./ : i :
. :J .... ,
H- -/r\..-~
i I j /
j i . ' ^
: /I 1 /A" Th
_J 	 f— :.—
•: J...:
: -.4.:..
: tJ'j*
j
•y JX '
..JJ. ... — ...
...... -.j
. ; • :
'. -. i
i

ick
i .
fefa*
; : ! : :;. ' '
'//i
ffi^f-^-
TTrET-'-"
8" Tl
z^n^d
[ 	
i
--

' •' i
.:. '-- J
J ' rt j : ;
t . .
	 .... . . ,
..
r:::^-:" \ •'-' - '• : : 	 :_j-""":
i"i rV ' i :

: ru-.j--.- y (j.-r--. } • ! ..-|- : ' I '
^5:":T"^:~ ~ ~ti" '
. . . . r, . .

— ._.
==F=

. 	 1
-:;•--)
• --r~[


: : ;
—-; — -] -:•-. 1 ...•.:
::-:
Ei::ii:j:--; -.; ..>. i . „....;.-

— }--

Ref. 160, Full
— l_t_i. 	 _..t — .
er Cc
-:-jz—
).)

.0'   10   20    30    40   .50   60    70
                                                      -90   100   110  120  130  140
                    DUCT & DILUTION AIR PORT DIAMETER,  INCHES

Figure 4-25  PRICES FOR FABRICATED CARBON  STEEL DILUTION AIR PORTS  VS.  DIAMETER
                                AND PLATE THICKNESS
                                         4-45

-------
*
     to
     LU
     a:
     a_
     LU




     I
     ce
     o
     CO
          8000
                                  1.  Prices include trough, screw,

                                      drive, fittings, and motor.


                                  2.  Heavy duty construction.


                                  3.  Source:  Ref. 160, Fuller Co.


          1000
w
                                                            50       60        70

                                                          LENGTH OF CONVEYOR, FT


                                     'Figure 4-26   PRICES FOR SCREW CONVEYORS VS. LENGTH AND DIAMETER
                                                                                     100
110

-------
      "Capital  and  Operating  Costs of  Pollution Control  Equipment Modules",
      Vol.  I  and  Vol.  II,  EPA-R5-73-023 a and b, July,  1973.  NTIS  PB  224-535
      &  PB  224-536.
      "Estimating Costs and Manpower Requirements for Conventional  Wastewater
      Treatment Facilities",  EPA 17090 DAN 10/71.  NTIS  PB 211-132.
 4.5   Ancilliary  Equipment
      Ancillary equipment  includes those items which may be required for the
 proper  simultaneous operation of several different types of auxiliary equip-
 ment  and,  therefore, the cost of this ancillary equipment can not be attributed
 to any  single  component.  For instance, the use of water-cooled duct, spray
 chambers,  quenchers, scrubbers, and absorbers may require a pump,  some piping
 and a cooling  tower as a water source for a closed-system operation.  If a
 specific control  system included a water-cooled hood,  lengths of water-cooled
 duct, a quencher and a scrubber, the required cooling  tower circuit would
 have  to be designed to handle the total  water requirements.
     Two figures  are given for pricing installed  cooling towers.   Figure 4-27
 applies for capacities less  than 1000  tons.   Figure  4-28 applies for capacities
 over  1000 tons (1 ton = 12,000 Btu/hr  of useful  refrigeration effect,  or 15,000
 Btu/hr of heat rejected).   The application  of Figure 4-28 is  more  complicated and
 is explained below.
      Figure 4-28 provides  prices for installed  cooling  towers as a  function  of
 the range and the water flow rate at a wet  bulb (W.B.)  temperature  of 82°F and
 an approach of 10°F.  See  Table 4.4 for definitions  of  terminology.  If the  W.B.
 is other than 82°F, Table  4.5 provides factors  for  adjusting  the price.   If  the
 approach is other than 10°F,  Table 4.6 provides  similar factors.
     For example, suppose  a  cooling  tower is  to operate under conditions of  72°F
W.B.  and a 20°F approach (leaving water temperature  = 92°F).   If the flow rate
        .»
is 50,000 gpm and the range  is 60°F, then the price  before  adjustments is
                                    4-47

-------
o
o
o
Ul

o
1-4

DC

QL,
O
O
o


a
to
                       1. Price  includes cooling  tower,  fans, pumps,

                          motors,  and installation.


                       2. Price  does not include  basin cost.
                  •;]Cost  1000 $ = 1.035 + 0.093265 T

                  i an ;j!
                                                                    Source:   Costs  developed from data from

                                                                  l!  MARLEY CO.  AND ECODYNE COOLING
                                                                     PRODUCTS  CO.
                                                                                     mm itii iMi:sHi"iiH;i iji- iijiii-i
                                                                                     ^•ftnR1!'; i7-11 l-t-HinrHllf-hn- r1-' ti't+i*'
          0
    400       500       600       700


', COOLING TOWER CAPACITY, TONS
900
1000
                 Figure 4-27  PRICES FOR  INSTALLED COOLING  TOWERS FOR UNITS  OF CAPACITY < 1000 TONS

-------
      8QQ :
o
o
o
o
I— I
CtL
Q.
 .
Ul

O
O
O
O

a
LU
          .:NOTE:
           1. See adjustment tables 2 & 3 if conditions
              other than WB=82°F and approach « 10*F.

           2. Price includes cooling tower, fans, pumps,
              motors, and installation.                 <

           3. Price does not include basin cost.
      600
      500
                  4.  Prices valid for units exceeding     J
                     1000  tons cooling capacity.
400 :iii
      200
      100
                              Source:  Costs developed  from data from
                               MARLEY  CO.  AND  ECODYNE COOLING
                               PRODUCTS  CO.
          0
                      20
30
CURVE EQUATIONS

            Equation

       $ = 34500 + 1.17 G

       $ = 34500 + 1.10 G

       $ = 34500 +1.01 G

       $ = 34500 + 8.76 G

       $ = 34500 + 7.90 G

       $ = 34500 + 6.89 G

       $ = 34500 + 5.80 G   :

       $ = 34500 + 4.43 G""i

       90        100       110
                                       40       50       60        70       80

                                         G, INLET FLOW RATE, 1000 GPM


Figure 4-28  PRICES FOR INSTALLED COOLING TOWER BASED ON WET-BULT TEMPERATURE = 82°F AND APPROACH = 10°F

-------
                   	Table  4.4	

                    DEFINITIONS  FOR  COOLING TOWER
      Approach:   The difference between  the  average temperature of
 the circulating water leaving the  device, and the average wet-bulb
 temperature of  the entering air.


      Range (cooling range):  The difference between the average
 temperature of  the water entering  the device, and the average
 temperature of  the water leaving it.


      Temperature, dewpoint:  The temperature at  which the condensation
 of water vapor  in a space begins for a  given state of humidity and
 pressure as the temperature of the vapor is reduced.  The temperature
 corresponding to saturation (100 percent relative humidity)  for a
 given absolute  humidity at constant pressure.
      Temperature, dry-bulb;   The temperature of  a  gas  or mixture  of
 gases indicated by an accurate thermometer after correction for
 radiation.
      Temperature, wet-bulb;  Thermodynamic wet-bulb temperature  is
 temperature at which liquid or solid water, by evaporating  into  air,
 can bring the air to saturation adiabatically at  the same temperature.
 Wet-bulb temperature (without qualification) is the temperature
 indicated by a wet-bulb psychrometer constructed  and used according
 to specifications.
            Table 4.5
Table 4.6
PRICE ADJUSTMENT FACTORS*
FOR WET-BULB TEMPERATURES
WET -BULB, °F
68
70
72
74
76
78
80
82
FACTOR, F2
1.54
1.46
1.38
1.30
1.22
1.15
1.07
1.00
PRICE ADJUSTMENT FACTORS*
FOR APPROACH AT
APPROACH, A°F
6
8
10
12
16
20
24
FACTOR, Fj
1.60
1.20
1.00
.85
.65
.50
.40
 * New Price = (P-34500) F]F2 + 34500 where P is the price from Figure 4-28.

** Data developed from MARLEY CO. and ECO'DYNE COOLING PRODUCTS CO.
                                  4-50

-------
 $620,000.  The adjustment factor for 72°F W.B. is 1.38 and the factor  for  a
 20°F approach is 0.5.  The installed cooling tower price is thus:
              (620,000 - 34,500) (0.5) (1.38) + 34,500 = - $438,500
     The fan motor horsepower is estimated as follows:
                    p
              HP = TEn/   where P is the price of the tower.
     The pump motor horsepower is estimated as follows:
              HP - gpm x 0.12.
     The basin area is estimated as follows:
                            p    p
              Basin Area = y^- ft .
     Since the approach in this example (the difference between the temperature
of the outlet water  and the wet-bulb temperature of the inlet air) is greater
than 10°F, the difference in enthalpy between the air and the water is greater
and consequently a smaller and less costly cooling tower would be required
for the same heat transfer capacity and ratio of gas-to-liquid flow rate.
On the other hand, because the wet-bulb temperature is lower than 82°F (72°F,
in this example), its absolute humidity is also lower.  (In other words, one
pound of air with an 82°F wet bulb temperature is capable of carrying more
water than a pound of air with a 72°F wet bulb temperature).  As a result,
to cool the same amount of water by evaporation, more air at 72°F W.B.
would be required than at 82°F W.B.  This, in turn, would require a relative-
ly larger cooling tower.   Hence, the cost adjustment factor taken from
Table 4.5 (1.38 in this example) would be greater than 1.0.
     Basins costs have not been provided since they vary so widely with the
individual application.  The basin may be used in conjunction with other
                                    4-51

-------
processes, which involves a proration of costs, and the basin may be constructed
in many types of soil and terrain, which can dramatically alter the first cost.
Basin  costs  should  be  estimated  on an  application basis through a basin con-
tractor.   As a  rough estimate, the installed cost of the basin can be consid-
ered to be approximately $70  per sq. ft. for the size of cooling towers shown
in  Figures 4-27 and 4-28.
     Figures 4-29,  4-30 and 4-31 contain prices for 3550 RPM, 1750 RPM, and
1170 RPM  cast iron, bronze fitted, vertical turbine wet sump  pumps.  These
pumps  can be used  for  scrubbers, cooling towers, water cooled duct, water
supply, and  similar applications.  Prices  are  a function of pump head in feet
and pump  capacity  in gpm.  The selection of the rpm of these  pumps should be
based  on  the design flow rate range  of the application as shown below.

                 FLOW  RATE  (gpm)              PUMP (rpm)
                    0-1,000                        3,550
                   500-5,000                     S  1,750
                 2,000-10,000                       1,170

     Generally, the capital cost of  the pump/motor combination varies
inversely with the rpm;  however, maintenance costs can be expected to higher
as  rpm increases.   Figure  4-32 provides a  means of estimating pump motor
horsepower for a given pump head and capacity.  These  curves  represent  the
nominal motor sizes used for  the indicated pump heads  and capacities.   If the
characteristics of a specific pump  (i.e.,  pump curve and rated efficiency) are
known, the equation in Section 3 may be used to determine the motor size.  In
this case, the selected motor must be  a standard size.  Motor prices may then
be  estimated using Figure  4-34 provided in Section 4.6.
                                     4-52

-------
co
      (St
      IT*
      0_
      CO
      o;
      Q-
      Qi
      m
      ro
           1400
           1300
      Ł    1200
           1100
                                                            ~,Ut nn Jtti Mr; n:i : ! ;:: Ult ir umnrrt
                                                                          CURVES BASED ON WATER.
                                                                          MOTOR NOT  INCLUDED.
                                                        PUMPS APPLICABLE FOR SCRUBBERS,
                                                        COOLING TOWERS, WATER SUPPLY,
                                                        PROCESS LIQUIDS, ETC.
                                                        SOURCE:   Ref.  160, Fuller Co.
                                                                                 IH

           1000
                                                                                                  900
                              400        500      600
                                     PUMP CAPACITY, GPM
Figure 4-29  CAST IRON, BRONZE  FITTED,  VERTICAL TURBINE WET SUMP PUMP PRICES  FOR  3550 RPM
1000

-------
                                          I   ;  I
I
cn
                   to
                   OH
                   O.
                   UJ
                  O
                  in
                        4000-T  NOTE:
                        3500
                1. CURVES BASED ON WATER
                2. MOTOR NOT INCLUDED
                3. PUMPS APPLICABLE FOR SCRUBBERS,
                   COOLING TOWERS, WATER SUPPLY,
                   PROCESS LIQUIDS, ETC.
                 4. SOURCE:   Ref.  160,  Fuller Co.
                   ^    3000
                        2500
2000*
                        1500
                        looo--
                        500
                             o
            600      1200       1800     2400      3000     3600     4200       4800      5400
                                       PUMP CAPACITY, GPM
                         Figure 4-30  CAST IRON,  BRONZE FITTED,  VERTICAL  TURBINE  WET SUMP  PUMP  PRICES  FOR 1750 RPM

-------
Ul
cr-
              a:
              o.
              D.
                  9000 w
                  8000 i i
                  7000
                                     mmmmm                                   ^::
mmiiF:ri
                  CURVES BASED ON WATER.

                  MOTOR NOT INCLUDED.
                  PUMPS ARE APPLICABLE  FOR SCRUBBERS
                  COOLING TOWERS, WATER SUPPLY,
                  PROCESS LIQUIDS, ETC.
                  SOURCE:  REF. 160,  Fuller Co.
                               iii   IBIMffltltltlP
                   3000
                   2000
                        0
      1000     2000      3000     4000      5000     6000

                                    PUMP CAPACITY, GPM

Figure 4-31  CAST IRON, BRONZE FITTED, VERTICAL TURBINE WET SUMP PUMP PRICES  FOR 1170 RPM

-------
     10000
o_
IS
n.
«c
u
       1000
        100
                  NOTE:  CURVES BASED ON WATER  EŁr
               0     30     60    90    120    150   170    210    240    270   300


                                         PUMP HEAD, FT



          Figure 4-32  PUMP MOTOR HP VS. CAPACITY AND HEAD FOR VERTICAL TURBINE PUMPS
                                         4-56

-------
 4.6   Fans
      Centrifugal  fans,  having either backward curved or radial tip  blades,
 are  used almost exclusively to transport the dust-laden gases through  the
 system.  The  backward curved fan provides the highest efficiency, but  because
 of its  inherent design, must be used downstream of the control device  where
 the  gas stream is relatively dust-free.  These fans are categorized  into
 Classes I through IV according to maximum impeller speeds and pressures.  The
 cost of the fan is based on its construction, class, volume, and pressure
 delivered at  standard conditions.  The radial tip fan, sometimes referred to
 as the industrial fan, operates at a lower efficiency, but is capable  of hand-
 ling dusty gas streams and can be used upstream of the control device.  The
 impeller of this fan consists of flat radial paddles which can be modified to
 include wear  plates for abrasive dust applications.  These fans can also be
 operated at high temperatures.  The cost of this type of fan is based on
 material of construction, total  volume, and pressure delivered at standard
 conditions.
      Radial tip fans are used almost exclusively in venturi  scrubber control
 systems because of their ability to operate at high pressures and tempera-
 tures with abrasive gas streams.   With scrubber systems,  a certain amount of
 carryover of  dust-laden water droplets can be expected which would be
 destructive to other types of fans operating at the impeller tip  velocities
 necessary for 20-80 inches W.G.  pressures.   The radial  tip fan can also be
 protected with wear plates and water sprays (for cleaning  blades) for dirty
 or highly abrasive gas streams.   The cost of radial  blade  fans is a  function
 of the actual  volume in cfm and the total  pressure delivered based on incre-
mental pressure ranges of 20,  40  and 60 inches  W.G.   Construction can be
either carbon  steel  for general purposes  or stainless  steel  for corrosive
                                     4-57

-------
gases.  Special linings are also available for unique conditions.
     The cost of the motor and motor starter for centrifugal  fans  is related
to the fan speed, total system pressure, gas volume flow rate, and selected
motor housing.  Fan speeds are chosen from a continuum, with aid of the fan
laws, to provide a desired head at a prescribed flow.  Motor speeds are chosen
from a set of perhaps only five discrete choices (Table 4.7).  Since belts
and pulleys are routinely used, fan speed and motor speed should be selected
as close to each other as possible.  The motor housings should be chosen for
the particular environment in which it will be operating.  Drip-proof motors
should be used in areas which are weather protected and relatively clean.
Totally enclosed motors should be used in dusty areas or areas exposed to
weather and severe splashing.  Explosion-proof motors must be used in hazardous
atmospheres where explosive fumes are present.
      Backwardly curved fans are priced as a function of the actual air flow
rate, pressure drop at standard conditions, and class, as given in Figure 4-33.
Standard conditions are defined as:             S
          pressure:       14.69 psia (sea level)
       temperature:        70°F
       gas density:       0.075 lb/ft3
      In many cases, fans are operated at different temperatures and pressures
(altitudes) and, therefore, a correction factor must be applied to equate the
actual operating conditions to a standard condition.  This correction factor
may be either a volume adjustment or a pressure adjustment.  In the following
figures, a pressure correction factor is used, therefore, the actual pressure
of the fan at operating conditions must be adjusted to standard conditions to
determine the size and cost of the fan.  If, for example, a Class III fan is
                                     4-58

-------
                                                                                                                                                loooon
4s.
 i
en
1000000
100000
10000
1000
c
Source:
T'i !|i!i'lti''l'-i-

.._jj
• -'i
i.: i •
_tr.;



.^
X
S*

•S

:•!
•^

'
•S


i i i -
•^
*Ł*
'"••\
!iii
Itn
!i(l
i; i
H.
ttr
ii
r -
i- .

P**1


:p


\:-f
fr.

#r




•??

~+~
:ii
Mji
~
ti"

ll::


•jr.

>•*

s?


rtf
*•.-

i**

















^

r1


#

••y








'•'
Data obtained from
Fuller Co.







r*





x"
•j-r*
*"^ •


;i;-
**"
















r***





^



Hr







^














'"






b-*
^x


^


sf





Jf'.

: l







. : : : •
:-S/**
9 - L""
i^r;L
. -,_,, ,
' "J<*



i^X;
' ! 1 i '
• •>>
. ,
IJ-t!
;TJX
! -






* : ! i
. i . .
: :)!;



i&
r^
v^
^

• '


>•"'
l>*
:;:•
^
riu
>H

I'i


TT"
:'i
:H!
t: '
i i
I1



It*
i !:
j-jj
i<



9
'»



r





PH
»-..
j :!
ft
|:;



J?
a
'




&
•#


#•






i-

!i-
l!i
':'•
x
/
^
x"
X
X




) 2 4 6 10 20 30
AP, in H20
(AT STANDARD CONDITIONS:
14.69 psia, 70°F)

^
/*
^
/-
/-
^





~\ '.:




•j^-
f
^^
X:

.X
^*-




•^
;-:;•

j|ii


•--






i.;_.
X
•X1




>•*
x



i**


_U-
•| ;










#
^


r*1





pr





















: •

1
^«

Ą
~
*H

>*


•i:







^
<•"
X


i^





:i-.


Fan
Class
I
II
IV
*Performance Ranc
(inches of v/ater
















•\\
|


s

K
^

#















^
>

X

I^1
\

**






\
*
•j

$















(f •


1 *
11 i
\-
*\

-I
Sr
V




,






iff:


, *Ł

•^
k "
• uy
' [Ui


;*z
\
\

n
(p

•-^

.




!•••' •

I


1^
n


x^
•J
^
iS
Ni
TP^


S
. >
1 • •




iq

-••*

'•?

IX
\
•ii
^


X


a
'i^1
|







^

^

fi(

4\
...
%
V
"1 '
:.h
IK
i^





•<
\
u_
ii'





Ff



H

^.
i**
*T

^







\,.
_.




n




tn
*HJ
?7
s
;

s







__




is

:\.




|

<

s












Bl

.
i

-



^
S
<












i


-: T




**• •

d
s
1
c
7











I -wna;


1 :':'!




! [*TTT

j : . '
'r
:^;::
» : *
S."T
• ^t
• -\
i fyt
^4*-
• -v









or


-.-.






' '.','.
&
•&
s
i : : i

V '











::;;




.~.


!l"


N""


_..










-.




-






:.

















T 	
"• iz:

J:::
















„






i'--.




•~
-








. — .
... . .

- - •








;::: i ;
nii i
tiu '
.:. :




.. . -





Performance Range*
Single Width
5" (« i!300 fpm to 2-M'i" 0 32UO fpm
8-1/2" @ 3000 fpm to 4-1/4" 0 4175 fpm
13-1/2" @ 3780 fpm to 6-3/4" 0 5260 fpm
Above Class III specifications
e designations are indicated by static pressure
at fan outlet velocity (feet per minute).

(


-






- . 10000

t - v*
* i 3800 w
o;
z
: u_
7-i 1000








inn

"or high temperature
;nvironment add 3*
( 250°F,to 600°F)
For stainless steel
2 construction multiply
price by 2.5.
NOTE: Fan price is lower at higher pressure drop because smaller fan wheel is
used at. higher rpm.
Figure 4-33 BACKWARDLY CURVED FAN PRICES VERSUS CLASS, CFM, AND F FOR ARRANGEMENT HO. 1

-------
to operate at.sea level with gas temperature of 70°F and is to handle a gas
volume of 20,000 CFM at 10" water, the price would be $3800.
     However, if a fan operates at a different pressure or temperature, an
adjustment must be made through the use of Table 4.10 to properly cost the
fan.  For instance, if actual conditions are:
          a.  gas temperature = 300°F
          b.  altitude = 1000 ft.
          c.  actual cfm = 50,000
          d.  actual AP = 10" static pressure
then the fan is priced as follows:
     1.  obtain fan sizing factor from Table 4.10 for 300°F at 1000 ft =  .672
     2.  actual 10" static pressure/.672 =  15" at standard conditions
     3.  enter Figure  4-33 with 50,000 cfm  and 15", read price of $8500 for
         Class IV  fan.  Since this  is a high heat application, (temperatures,of
         250 to 600°F), the  estimated price is $8500 x  1.03 = $8760.
     The prices for the motor and the starter are obtained from  Figure 4-34.
Enter the chart on the right with the gas flow rate and the static pressure
at  standard conditions.  For 10" S.P. and 20,000 cfm, find the point with
those coordinates  and  draw lines parallel to the  "FAN RPM" guidelines  and
the "BMP" guidelines.  Read  the fan rpm on  the scale to the right, read the
bnp on the. scale to the left.  Then read the price for  the type  of starter
needed and for the drip-proof motor at the  selected  rpm.   A guide to deter-
mining motor rpm is given  in Table  4.7.  For the  example,  the fan rpm  is
found to be about  1600 and the motor bhp is 44.   According to Table 4.7,  the
motor rpm should be 1800,  hence the corresponding price is about $700.*
   Prices in Figure 4-33 are based on bhp, however the motor would be
  purchased as a 50 hp motor (the closest nominal size).
                                      4-60

-------
                      1000
-Ł>
                                                                                                                                                FAN RPM
                                                                                                                                                     300
                                                                                                                                                      500
                                                    10"      -     "           10
                                             DRIP-PROOF MOTOR OR STARTER PRICE,  $
10'
                               NOTE:  Prices are for drip-proof motors only, for other types of
                                      motors, see Tables 48 ond 4.9.  Motors are purchased in
                                      standard sizes, but for estimating purposes, curve prices
                                      may be used.
                                      Data  obtained  from Fuller Co.
                                                         Figure 4-34   BMP, FAN RPM AND MOTOR AND STARTER
                                                                                          2   3  4  5 6 78 9
                                                                                                          10      20
                                                                                   AP, H?0  (AT STANDARD CONDITIONS)
                                                                              PRICES V?.  .'P A'i.: _R-1

-------
                                  Table 4.7

                          MOTOR  RPM SELECTION GUIDE
                 Table 4.8

   PRICING FACTORS FOR OTHER MOTOR TYPES
MOTOR RPM
3600
1800
1200
900
600
FAN RPM RANGE
2400 - 4000
1400 - 2400
1000 - 1400
700 - 1000
< 700
HORSEPOWER
I20
> 20
TOTALLY ENCLOSED
FAN COOLED
1.3
1.5
i
EXPLOSION PROOF
1.6
1.7
-p»

ro
                                                              Table 4.9

                                                         MOTOR TYPE SELECTION
                           Drip-proof:
                           In non-hazardous, reasonably clean
                           surroundings free of any abrasive
                           or conducting dust and chemical fumes,
                           Moderate amounts of moisture or dust
                           and falling particles or liquids can
                           be tolerated.

                           Totally Enclosed Non-Ventilated or
                           Fan Cooled^

                           In non-hazardous atmospheres con-
                           taining abrasive or conducting dusts,
                           high concentrations of chemical or
                           oil vapors and/or where hosing down
                           or severe splashing is encountered.
Totally Enclosed Explosion Proof:
Use in hazardous atmospheres containing:

Class I, Group D, acetone, acrylonitrile,
alcohol, ammonia, benzine, benzol, butane
ethylene dichloride, gasoline, hexane,
lacquer solvent vapors, naptha, natural
gas, propane, propylene, styrene, vinyl
acetate, vinyl chloride or xylenes;
Class II, Group G, flour, starch or
grain dust;

Class II, Group F, carbon black, coal
or coke dust;

Class II, Group E, metal dust including
magnesium and aluminum or their com-
mercial alloys.
                             Data  obtained  from  Fuller Co.

-------
                               Table 4/10  FAN SIZING FACTORS:  AIR DENSITY RATIOS


                                 Unity Basis  =  Standard  Air  Density of .075 lb/ft3

                 At sea level  (29.92 in.  Hg barometric pressure)  this  is  equivalent to dry air  at 70°F,
Air
Temp.
°F
70
100
150
200
250
300
350
400
450
500
550
600
650
700
Altitude in Feet Above Sea Level
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
15000
20000
Barometric Pressure in Inches of Mercury
29.92
1.000
.946
.869
.803
.747
.697
.654
.616
.582
.552
.525
.500
.477
.457
28.86
.964
.912
.838
.774
.720
.672
.631
.594
.561
.532
.506
.482
.460
.441
27.82
.930
.880
.808
.747
.694
.648
.608
.573
.542
.513
.488
.465
.444
.425
26.82
.896
.848
.770
.720
.669
.624
.586
.552
.522
.495
.470
.448
.427
.410
25.84
.864
.818
.751
.694
.645
.604
.565
.532
.503
.477
.454
.432
.412
.395
24.90
.832
.787
.723
.668
.622
.580
.544
.513
.484
.459
.437
.416
.397
.380
23.98
.801
.758
.696
.643
.598
.558
.524
.493
.466
.442
.421
.400
.382
.366
23.09
.772
.730
.671
.620
.576
.538
.505
.476
.449
.426
.405
.386
.368
.353
22.22
.743
.703
.646
.596
.555
.518
.486
.458
.433
.410
.390
.372
.354
.340
21.39
.714
.676
.620
.573
.533
.498
.467
.440
.416
.394
.375
.352
.341
.326
20.58
.688
.651
.598
.552
.514
.480
.450
.424
.401
.380
.361
.344
.328
.315
16.89
.564
.534
.490
.453
.421
.393
.369
.347
.328
.311
.296
.282
.269
.258
13.75
.460
.435
.400
.369
.344
.321
.301
.283
.268
.254
.242
.230
.219
.210
-p»

OJ
                 SOURCE:  AMCA STANDARD #402-66
                          AIR MOVING AND CONDITIONING ASSOCIATION, INC,
                          205 West Touhy Avenue
                          Park Ridge,  Illinois   60068

-------
If a magnetic starter is selected,  the price  is  about  $450.   Prices  for  motor
types other than drip-proof may be  estimated  using  Table  4.8.  A  totally
enclosed motor for this example would cost $700  x  1.5  = $1050.  The  selection
of a motor type may be made from Table 4.9.
     For conditions deviating from standard,  the following  steps  must be taken
to establish the motor and starter price.   Again consider the 300°F  application
from before.
     1.  Find the bhp from Figure 4-34 using  50,000 cfm and 15" S.P-  = 180 bhp
     2.  Correct the bhp by multiplying by the fan sizing factor:
         180 bhp x 0.672 - 121 bhp, actual.
     3.  Find motor and starter prices at 121 bhp.   The fan rpm does  not
         require adjustment.
     An inlet or outlet damper is usually required on  fans, and prices for
such are presented in Figure 4-35.   Note that the static  pressure is  measured
for standard conditions, as in Figure 4-33 and 4-34.  These dampers  are
supplied by the fan manufacturer and designed to match the  inlet  and outlet
configuration for each fan size.
     V-belt drives may be selected for applications where the desired fan
speed is not the same as standard motor speeds (nominally 600,  720,  900, 1200,
1800 and 3600 rpm).  These drives are used for fan/motor  combinations of up
to approximately 150 hp.  Fan drives above 150  hp  are usually direct drives.
Figure 4-36 contains prices for V-belt drives as a function of motor bhp and
fan rpm.  For direct drives, estimate price at 5% of the  motor price.
                                      4-64

-------
   1,000,000
     400,000
     200,000
     loo.ooo |4
 ac
 i—*

 
-------
oo
CD
GO
o

CD
Z
*-^
O
ID
_J
O
CJ
a:
o.
CO
 I

till NOTE: 1. Select V-Belt
            closest to Fan  RPK.
                                                       2.  Do not "Extrapolate"
                                                          prices for belts
                                                          above 140 HP
                                                          application.
                                                         nr (Ref. 160)
                            40         60       80
                              MOTOR  HORSEPOWER, HP

                        Figure 4-36   V-BELT DRIVE PRICES
                                      4-66

-------
     The method of estimating prices for radial tip fans is the same as for
backwardly curved fans.  Prices for radial tip fans operating under 20" S.P.
are given in Figure 4-37.  Figure 4-38 provides the data for determining the
fan rpm and motor bhp for radial tip fans.  Refer to Figure 4-34 to obtain the
motor and starter prices once the bhp has been determined.
     For radial tip fan applications involving greater than 20" S.P., Figures
4-39 and 4-40 should be used to estimate the fan and motor prices, respectively.
The static pressure must be converted to standard conditions as before, using
Table 4.10.
     For estimating the cost of custom heavy duty, radial tip induced draft
fans operating at pressures of 15 inches W.G., temperatures to 250°F, and
volumes of up to 400,000 acfm, the collective cost of the fan, motor, and
starter can be considered as 0.38 x ACFM delivered.  The breakdown of the
individual costs is approximately 0.19 for the fan, 0.15 for the motor and
0.04 for the starter.
4.7  Stacks
     Stacks are provided downstream of the fans for dispersion of the exhaust
gases above the immediate ground level  and surrounding buildings.   Minimum
stack exit velocities should be at least 1.5 times the expected wind velocity;
or for instance, in the case of 30 mph winds, the minimum exit velocity should
be 4000 fpm.  Small  stacks are asually fabricated of steel, which may be
refractory lined, and are normally limited to exit velocities  of approximately
9000 fpm.   Tall stacks, over 200 feet,  can be designed with liners of steel  or
masonry.  The cost of stacks is based on diameter, material  thickness and  type,
height, and whether a liner is provided.  The design of stacks  is  influenced
by local conditions  such as the maximum design wind load,  soil  bearing
                                     4-67

-------
   100,000^
    10,000=^
LU
                                                                                           •M-
                                                                                           LJ
                                                                                           U
                                                                                           cc
                                                                                           Q.
                                                                                           <
                                                                                           u.
     3,500^
     1,000
                                            100
                                                         For High Temperature
                                                         Environment add 6%
                                                         (  250°F to 600°F)

                                                         For Stainless Steel
                                                         Construction multiply
                                                         Price by 2.5.
                                                        Source:  Ref. 160
                 2   3457   10
                     AP, in H20
20
          Figure 4-37  RADIAL FAN PRICES VERSUS ACFM, ANDAP FOR ARRANGEMENT NO.  1

                                             4-63

-------
                                                                          ^100
MOTOR
 BHP
                                                                Source:   Ref.  160
                             2   3  4   6  8 10     20
                                AP, IN H20

             Figure 4-38  FAN RPM AND MOTOR BHP FOR RADIAL  FANS
                                     4-69

-------
*»

o
     o
     o
     o
     o
     I—I

     Q_
                         1. TP = Fan Pressure measured
                                 at standard conditions
                         2. For stainless steel construction
                            and rubber lined housing,
                            multiply price by 2.5.

                         3.  Source:  Ref. 160

                                                                                                             200
                                                   AIR  FLOW RATE,  1,000 CFM
                                               Figure  4-39   RADIAL  TIP FAN PRICES

-------
o
o
o
a.
       80 nr
       70  i
       60
40
       30
       10
      NOTE:   1.  Accuracy of this curve is t 50%.
                vary as a function of:
                a) Motor RPM
                b) Frame size
                c) Voltage
                d) Motor enclosure
                e) Type of starter
                                                         Prices will  •
                    2.
                  utt
                FTP = Fan Total pressure at
                      Standard Conditions
                                         : ffl
                    3. Source Ref.
                    I
                      j-iLU
                  m
                                Mi
                                   U
                                        ' '
                                        •m
                                          Jl*
                                            H?
                                                   lit
                                                    lit
                                                      ij'
                                                      '. . :

                                                             M
                                                                             i


                                                                                  :
                                                                                 ^

                                                                              I

                                                                                  Ł*
                                                                                           -


                                                                                            n
                                                                 i
                             t«

          0
20
                     40
60
140
160
180
                                                                                                         200
                                      80       100       120
                                     AIR FLOW RATE, 1000 CFM

Figure 4-40  STARTER AND MOTOR PRICES FOR VENTURI SCRUBBER APPLICATIONS  (HIGH PRESSURE, HIGH BHP)

-------
characteristics, seismic zone, and building code requirements.   Design
details and formulas for stacks are contained in ref.  157.
     Prices for stacks are given in Figures 4-41,  4-42 and  4-43.   Figures  4-41
and 4-42 are for carbon steel, unlined,  uninstalled  stacks  under  100'.   These
represent the size and range of stacks  normally encountered in  industrial
applications.  Figure 4-43 contains installed prices for  large  diameter stacks
over  200  Feet  in  height with  liners and insulation.  These stacks are
primarily used for  large  municipal installations such as power plants  and
incinerators.   Cost details are contained  in reference 158.
                                   4-72

-------
         10,000 p
    cc
    a.
    Q
    UJ
    on
    CD
    <:
    o
          9,000
          8,000
          7,000
         6,000
    §   5,000
4,000
         3,000
         2,000
         1,000
                1.  Plate Thickness:   1/4 inch.
              = 2.  Includes:   flange, stack,  cables,
                   clamps,  and surface coating.
                3.  Cables are stainless steel;
                   qty.: 4.
                4.  Source:  Ref.  160
                                           WEIGHT  OF 1/4"  STACK
                                      Diameter            Weight  (Ibs)
                                                          200  + 66  H
                                                          240  + 82  H
                                                          270  + 98  H
                                                                   340 + 114 H   =
                                                                   385 + 130 H   5
                                                                                 tt
                                                                   450 + 146 H   3,
                                                                   470 + 162 H   1
                                           50        60
                                       H, STACK HEIGHT, FT
Figure 4-41   FABRICATED CARBON STEEL STACK PRICE VS.  STACK HEIGHT & DIAMETER FOR 1/4 INCH PLATE
                                            4-73

-------
       a:
       o.
       s
              4,000
              3,000
              2,000
                                      40         50         60        70

                                           H, STACK HEIGHT, FT
Figure 4-42  FABRICATED CARBON STEEL STACK PRICE VS. STACK HEIGHT &  DIAMETER  FOR  5/16"  & 3/8"  PLATE
                                                  4-74

-------
 4000
3000
2000

jiisigffisa^S^^
;gŁShf%| p*SŁsŁ2E 40 F


:J: fi: fcjjit: ^j±E5ffi ^HS^iitd:|i
$ 4 t^ !t3-I-| 1 i j 3 -^^-t^p-1-^ — ^ Ł-^f 4-j^- -t-[—
"" " "*" ^ *^" \, ! IT' 7" Ti *"^ "^^T "^ ^^ ^ — * """"
4- X '4-14 ^--i- " 1 tt, —. 4 } j 1 1 J-L . , > . ! — ~ -*-r-4 t i . . — .4.
±: ::: SI* g S Effl S |: 1:: || g
1 |i|||iii iii i;;i;;lg 15 J"g
|:: |E:::t::: g E-^?:J^5 If: if 5 :|
j^^|-=:Ł^j :;u :::; -i rtr, :T,, = :r ^: :; i^. ^jF~ i— - • -^j^-
|J^^:-^::::::^J:H^|^-^


tJ!+trttttijnjig;i;U#tt!iiJM^
^^*|^S ^s|§Sip30 Ft I.D. Stai
^j|^^-:^g;g^s ^§SfS^§::i:
ffi^g^gSgg gSgl 20 Ft.
|i :EE|S:lg:§ 5w=^^~-§g8g:|:
1 li'slii l^silsailgiliili!!!!
|:i[|S J| 15 Ft. I.D
ilHSi E;giisl»§fi!^g;S^p
fiSii :SBBB3a**8":BIE^i
|:: :|: i|; ;;:; loading, minimal seis

1000
    0
              100
200
600
                            300      400       500
                                   HEIGHT, FT
Figure 4-43 PRICES FOR TALL STEEL STACKS, INSULATED AND LINE.D
700
                                       4-75

-------
                                Section  5

                            CONTROL DEVICES

     The following description  of the control devices is designed to provide
 the user with the basic concept of the operation of the device, the parameters
 required to size and cost it, and the required auxiliary equipment necessary
 for proper operation of the gas cleaning system.  The equipment cost of the
 control device is based on flange-to-flange costs.  The cost of the auxiliary
 equipment has already been discussed in the preceeding Section 4.  In this
 section, the description of the control  devices and the integration of the
 auxiliary equipment will be discussed so that the user can develop the capital
 and operating costs of a control system for any particular application.

 5.1  High Voltage Electrostatic Precipitators
     Gas cleaning by electrostatic precipitation is particularly suited for
 gas streams which can be easily ionized  and which contain  either liquid or
 solid particulate matter.   The method of removal  consists  of passing  the
 particle-laden gas through an electrostatic field produced by a high-voltage
 electrode and a grounded collection  surface.   The gas  is ionized by the high
 voltage discharge and the  particulate matter is  charged by the interaction
of the gas  ions.   The particles migrate  to  the collecting  surface  which has
an opposite polarity and are neutralized.   The adhesive properties of the
particles and the action of the electrical  field keep  the  particles on  the
collecting  surface and inhibit re-entrainment.  The particles are  removed  by
 rappers or  by other mechanical devices that vibrate the collector  surface  and
                                       5-1

-------
dislodge the participate, which drops by gravity to hoppers.   Usually this is
accomplished during normal operation, however, in cases where severe re-
entrainment is a problem, sections of the precipitator may be isolated during
rapping.  The particulate matter is removed from the hoppers  periodically by
either pneumatic or mechanical screw conveyors.
     Electrostatic precipitators are used extensively on large volume applica-
tions where the fine dust and particulate is less than 10-20  microns in size
with a predominant portion in the sub-micron range.  The precipitators can
achieve high efficiencies (in excess of 99%) depending on the resistivity of
the particulate matter and the characteristics of the gas stream.  Wet or dry
particulate can be collected including highly corrosive materials if the units
are suitably constructed.  Precipitators can be used at high  temperatures (up
to 1000°F) but are normally operated at temperatures below 700°F.  The static
pressure drop through the units is low, usually up to one-half inch W.G., for
units operating at normal gas velocities (2-8 feet per second).  The initial
capital cost of electrostatic precipitators is hi-gh; however, operating
(utility) and maintenance costs are reasonably low.  Safety precautions are
always required since the operating voltages are as high as 100,000 volts.
The overall size of electrostatic precipitators is comparable to fabric fil-
ters (baghouses) and space requirements are an important factor in the layout
and design of the facilities.
     The cost of the basic electrostatic precipitator is a function of the
plate area which, in turn, is a function of the required efficiency.  The re-
lationship of the plate area to efficiency can be shown by the Deutsch equation:
                                      5-2

-------
         E = 1 - e  '
 where   E = collection efficiency
         w = drift velocity, fps
                           o
         A ~ plate area, ft
         Q = flow rate, acfs

The Deutsch equation, though adequate for "scope"  cost estimates, furnishes
only an approximate method to estimate plate area.

     The electrical  characteristics of the dust, quantified by the drift
velocity, as shown  in the Deutsch equation, have a large effect on the collect-
tion efficiency and  plate area, and consequently, on the cost of the precip-
itator.  The resistivity of the dust varies with the temperature and moisture
content of the gas,  therefore, in some applications, auxiliary equipment may
be required to precondition the gas stream prior to entering the precipitator.
The addition of moisture in the gas stream together with low operating temp-
eratures will necessitate insulating the precipitator to prevent condensation
and subsequent corrosion problems.  The cost of the basic precipitator is
therefore separated  into insulated and non-insulated units.  Special  cost
factors can be incurred in the type of power supply such as automatic voltage
control, number of individual sections energized, type of rectifier,  etc.,
and also, in special materials of construction and special  plate design.
                                       5-3

-------
These factors are additive costs to the basic collector pri.ce and represent
custom features either required by the process or by the buyer's specifica-
tions.  For most applications, the cost curves presented in this manual are
sufficient.
     Figure 5-1 illustrates schematically the types of auxiliary equipment
that would be used in a gas cleaning system incorporating electrostatic
precipitators.  These include the capture device, ductwork, mechanical
collectors, coolers, spray chambers, fans, dust removal, and stacks.  A heat
exchanger or wasteheat boiler may also be used to cool the gases before
entering the precipitator.  The use of all or only some of this auxiliary
equipment will depend on the particular application and pollutant source.
In general, all systems will require a capture device, ductwork and a fan.
The capture device can be either a round or rectangular hood located near
the pollutant source or it can be directly connected to the source as, for
instance, a kiln or furnace.  These devices are usually refractory lined,
water-cooled, or simply fabricated from carbon steel depending on the gas
stream temperatures.  Refractory or water-cooled capture devices are used
where wall temperatures exceed 800°F; carbon steel is used for lower temperatures,
The ducting, like the capture device, should be water cooled, refractory or
stainless steel for hot processes and carbon steel for gas temperatures below
approximately 1150°F (duct wall temperatures <800°F).  The ducts should be sized
for a gas velocity of approximately 4000 fpm for the average case.  Normally,
radiant U-tube coolers would not be required unless the gas stream temperature
to the precipitator was above approximately 700°F.  Even in these cases it may
be prudent to use a spray chamber for cooling since the addition of moisture
                                      5-4

-------
           HOOD
                              DUCTWORK
en
en
         DIRECT EXHAUST-
                                                  RADIANT COOLER

                                                  SPRAY COOLER
                         STACK
        PRECIPITATOR
L a A a *?** *• * **rm
                 \
                                                                                               SCREW CONVEYOR
                                              MECHANICAL  COLLECTOR
                                   CONTROL DEVICE AND TYPICAL  AUXILIARY EQUIPMENT
                                 Figure 5-1  ELECTROSTATIC PRECIPITATOR  CONTROL  SYSTEMS

-------
will enhance the precipitation process.  Spray chambers may also be required
for cold processes where the addition of moisture will  improve precipitation.
For combustion processes where the exhaust gases are below approximately 700°F,
cooling would not be required and the exhaust gases can be delivered directly
to the precipitator.
     A backwardly-curved centrifugal fan located on the clean air side (down-
stream of the precipitator) would be a typical selection for a precipitator
application handling high concentrations of dust.  A mechanical collector in
this case may be used to reduce the dust loading on the precipitator if an
appreciable portion of the dust is  larger than 20 microns in size.  The selec-
tion and type of auxiliary equipment which must be integrated with the control
device to develop a workable control system should be based on engineering
judgement.
     Prices for dry type (mechanical rapper or vibrator) precipitators are
contained in Figure 5-2 .  Prices are  a function of, net plate area, which are
calculated using the Deutsch equation:

(1)        n = i .  e(-wA/Q)
      or
(2)        A = -Q In (l-n)/w
      where n is efficiency
           w is drift velocity, f/s
           A is net plate area, ft2
           Q is flow rate, cfs
         exp. is e, the Naperian log base
                                      5-6

-------
QL
D.

o:

p
«c

H-1
o.
t—t

LU

Q.
                                                    Based on data from

                                                    JOY/WESTERN PRECIPATION DIV
            10




Figure 5-2  DRY TYPE
                                    A, PLATE AREA, SQ.  FT.


                            ELECTROSTATIC PRECIPITATOR  PURCHASE  PRICES  VS.  PLATE AREA
                                         5-7

-------
     As an example, for gray iron foundries the drift velocity,  w,  is typically
0.12 f/s.  If 99% cleaning efficiency is required on a flow rate of 10,000 cfm
into the precipitator, the net plate area is calculated as  follows:
            A = (-10000 cfm)(In (l-.99))/(0.12 f/s)(60 s/m)
              = 6396 ft2
     For the required plate area read the price for  either  the insulated or
uninsulated precipitators, depending on design requirements.
     The cost of wet electrostatic precipitators is  very difficult  to estimate
because of the variety of designs and materials of construction. These devices
are used to collect particulate and mists which are  difficult or sometimes
impossible to collect with a dry precipitator.  The  operation is similar except
in the method of cleaning the plate area.  Instead of rappers or vibrators,
water is used to flush the plate area and remove the collected material.  Under
these conditions, corrosion becomes a major factor in the design of the units
and stainless steel and other corrosion resistant materials are  frequently
used.  As a rough estimate, the cost of wet precipitators can be considered to
be approximately 2.5 times the cost of a dry precipitator in  the range of
20,000 sq.ft. of plate area.  At 50,000 sq.ft., the  cost ratio reduces to
approximately 2.0(ref.  172).   Caution   should  be  used  in applying these factors
since materials of construction have a  large influence on costs.  For instance,
lead lined plates are used in the collection of acid mists  in wet precip-
itators.  The comparative costs of these units is approximately 10  times
the cost of a dry precipitator.
                                       5-8

-------
 5.2  Venturi  Scrubbers
      Venturi-type  scrubbers  are  capable  of  providing  high efficiency  collec-
 tion  of sub-micron dusts  which are not easily collected by other types of
 scrubbers.   Basically,  the scrubber is constructed with a converging  section
 of the  venturi  to  accelerate the gas  stream to a maximum velocity at  the throat
 section where impaction with the scrubbing  fluid or liquor occurs.  Fine drop-
 lets  of the scrubbing  liquor are atomized as a result of this interaction and
 the relative velocities between  the dust particles and droplets cause collision
 and agglomeration  as they proceed through the throat section.  Further agglo-
 meration occurs as the  gas stream is  decelerated in the diverging section of
 the venturi,  thus  producing  droplets  with the entrapped dust of a size easily
 removable by mechanical means.
      The pressure  drop  through the venturi  is a function of gas stream throat
 velocity and scrubbing  liquor flow rate, which in turn have been chosen for a
 desired collection efficiency on a given dust.  The smaller the dust particle
 size, the higher the pressure drop required.  As the pressure drop is increased,
 finer droplets  are atomized  to interact with the dust particles through impinge-
 ment  and agglomeration, with the consequent increase in collection efficiency.
 Increasing  the  pressure drop can be accomplished by either increasing the gas
 stream  throat velocity, increasing the scrubbing liquor flow rate or both.
 The relationship between  pressure drop and collection efficiency is the same
 for all   types of venturi  scrubbers irrespective of the size,  shape or general
 configuration of the scrubber.  Venturi  scrubbers are normally operated at
 pressure drops of between 6 and 80 inches W.G.  depending  on  the characteristics
of the dust, and at liquor flow rates  of 3 to  20  gpm per  1000  ACFM.   The
collection efficiencies range from 99+%  for one micron or larger  sized particles
to 90  to 99% for particles below  one micron size.
                                      5-9

-------
     A separator for removal  of the agglomerates from the gas stream is pro-
vided downstream of the scrubber.  These separators are usually of the cyclone
type where the gas stream and agglomerates are given a cyclonic motion which
forces the liquid and particles to impinge on the walls of the separator by
centrifugal force.  The separator normally consists of a cylindrical tank with
a tangential inlet located at the lower side of the tank and an exhaust outlet
located at the top of the tank on the centerline axis.  A cone bottom with out-
let is provided to collect the liquid slurry.  The collected particles settle
to the bottom of the cone and are removed to the water treatment facility while
the cleaner liquid above the sediment is removed and recycled to the scrubber.
     For hot processes, a considerable amount of water is vaporized in the
scrubber and upstream equipment (e.g., quencher)  which must be handled by the
fan.  Although the gas volume is reduced, a large portion remains as water
vapor which results in higher horsepower requirements and in higher operating
costs.  To alleviate this condition, a gas cooler can be incorporated into
the separator to cool and dehumidify the gas stream.  Several types of gas
coolers are used for this purpose; one type employs spray banks of cooling
water followed by impingement baffles while a second type utilizes flooded
plates or trays with either perforated holes or bubble caps to permit passage
of the gas stream through the bath of cooling water.  Several plates or trays
can be used in sequential stages to provide the necessary cooling and contact
time.
     In addition to its ability to remove sub-micron dusts, the venturi scrubber
with separator and gas cooler/contactor can also be used as a gas absorber.
These units have been used successfully in the removal of acid mists in the
chemical industry and the removal of S0"2 and S03 in municipal power plant flue
gases.
                                    5-10

-------
      The cost of the scrubber and separator are based on the volumetric flow
 rate, operating pressure, and materials of construction.  The sizes of the
 scrubber, separator, and elbow (vertically oriented) are determined from
 the actual inlet gas volume in acfm and priced accordingly for a basic plate
 thickness of 1/8 inch.  Additional cost factors are provided for different
 metal thicknesses, fiberglass or rubber liners, manual  or automatic venturi
 throat, and stainless steel  construction.   The plate thickness for the scrubber
 and separator is a function of the maximum operating design pressure and shell
 diameter.  As the volume flow rate and/or  pressure drop increase,  the metal
 wall thicknesses must also be increased to prevent buckling.   Some allowances
 for corrosion or erosion are usually added to  the  design conditions.  Typical
 design parameters for a scrubber and separator are based on a  scrubber inlet
 gas velocity of 3500 fpm and a separator superficial  inlet velocity of 600
 fpm.  For a given flow rate, the internal  surface  area  for the scrubber,
 elbow and separator can be determined to establish the  additive cost of a
 rubber or fiberglass liner.   Likewise,  the diameter of  the separator will
 determine the diameter of the trays  for an internal  gas  cooler.
     The auxiliary equipment normally associated with venturi scrubber systems
is shown schematically in Figure 5-3.  These include a capture  device and duct-
                                                         •
work, a quencher, dust removal and treatment, fan,  and a stack.
     Prices for venturi scrubbers are contained in  Figures 5-4  through 5-8.
To price a scrubber using these curves, use the following steps.
A.    Determine the gas volume entering the  venturi  section and  read the price
     for a 1/8" thick carbon steel  scrubber from Figure  5-4.   For example,  at
     100,000 ACFM the price is approximately $39,000.
                                   5-11

-------
  HOOD
                                 DUCTWORK
DIRECT EXHAUST
                        QUENCHER
I
ro
                                                                        FAN
                                                                SEPARATOR/
                                                                  COOLER
                                                                SCRUBBER
                                                                                                      STACK
                                                                       TO TREATMENT
                     CONTROL  DEVICE  AND  TYPICAL  AUXILIARY  EQUIPMENT
                 Figure 5-3  VENTURI SCRUBBER CONTROL SYSTEMS

-------
CJ1
I
OJ
:i
L. '
T '
fin nnn ?;
DUjUUUratjtJt
cc nnn
DOjUUU f"
i
en nnn J±i i
DU,UUU 0? |
ft-
—."
.;: . • i :!:-' '• I
.::.•:.• . 	 ..I.. .. i. .:. ..
". I ' :.
.
. :..: •
JJ^L.
r^
••

i:..
I:

ill
20

ri^ t
ill:

::; l
ii!
4C
•:;_:
: . i . : ,
:i


-ll L—
i :
!l
! :
•** trt-
iiii
. liii

:...

ii'r
'&


!•
;: iii ':. . [i:i




l •
1

r~
|
h
Ii

- i-:





Hi.
i;

'••r -:r:

~^.
•:~
•1
i!!
i!;i

n :
trn
; i
i
! i

iiii

rr-.-f-r j»
_j^t' "
%\~.\: •':
i'.' '.•'. "
: . ' : '
:i; ii
:"|'
. . . | ,

! i:
r^
I ;.
I !.
I

^i . :

; j
i!
:
i; : i
iiii .
) 60 80
t— T
: i r ;
Ha
'iii
;ti
i^ -
•ffT.i: /.
. •:; :.
;• ;':: i.i;
:; ''•'•' Jli

1 '1 ::;
::i
-(.•-^-i.dii

;: •'; 'i!
' "' }\i
;•-•••; ';'
;. jjj. --iii
— if" ;-"-
• • ! t U M^ '
r tin fin
iii HH
Iii Illi

{tter;
%'A


jtor, Pumps
5.
Dve


;: jit
j;:
'$
:1 '
"•;niii
u

1*1

-J\
'ill




Ii
pr
Dv
^ft
.... i
!"
'•'.' I
I .
: : ;
ijL |_
jte ^
dfef
t^-r-l
'l f*a
rw:;

illf *i
1 !;M|iS^
u'.liTfr!
L iifpftS
:jj jrti '•'*" 2.
„ -§dti
i^Lttrafffitr
TTf^iitf j:iT:
vi!-: :.;:r:7i- if
AH 1 1 ic 4-man
: ill Tf ^i-
H H]r " III:
': jtiftlHlI
Mji-HMi
j 1 !. . J ..
Iti trr1 'ii;
.1 tin uti ::!:
itMUUiii:
llBg

•1 rtri -i 	
TtHr!:::: ::::
4-c-
n :
I! '•

H!
ii i
.'I :
jjj


: i:

ii.

! ! '
iii
I-
::.!





;:;•.










—


\fr~


"


Item Factor
ji '"•••• A. Other Metal Thickness
^^!

r~f" t
; , f
. ' i
t ;•.... ,
f :4f '

M'^T i

iii; -:;;
i : •:!
1 ^ i ' ' '
il++«.i
L •
100
?. 316 Stainless Steel
:. 304 Stainless Steel
). 3/16" Rubber Liner
'.. Manual Variable
Venturi
-. Automatic Variable
Venturi
3. Fiberglas Lined
i fii
1
i iii:
m
ii

j

120
H":
i
i:|
!!
ifil !
1!!! !
iiii ;
:::::: : : :;t: "j
i: i: : oil i
i$ttf
See Figure
x 3.20
x 2.3 2
$3450
$6350
Add 15% of
for 1/8" (
Steel Sen
to total
•!i •. u: :;: :if
-f-}-| . > U it...
:{Hr!!; ; ii
ft:

5-
pr
:ar
jbb
3ri
t
t-
5
ic
bo
er
ce
P
B
n y
—
140 160 180 2(
                                             V, WASTE INLET GAS VOLUME, 1000 ACFM

                         Figure  5-4    1/8"  THICK CARBON  STEEL  FABRICATED  SCRUBBER PRICE VS.  VOLUME

-------
   1,000
o
 CM
CŁ
r>

oo
LlJ

O.


O


UJ
o

 «s
Q.
      10
                               V, WASTE INLET GAS,  1000 ACFM
           Figure  5-5   METAL THICKNESS REQUIRED VS. VOLUME  AND DESIGN PRESSURE
                                         5-14

-------
cr
o


§
to


i

-------
         3,000
tn
i
cr>
      cr
      to
      «=c
      LU
      o:
LU
O
«=c
Lu
CŁ
13
to
2,000 :i;l
         1,000
                     Scrubber  Internal  Surface Area ii;
                       Ventun
                       Elbow
                       Separator
                                               **"* °--W
                                               B-Jkitafell
                                                                    Source:  Ref. 160 , Fuller Co.
                                                                     Do not extrapolate  beyond range
                                       60       80      100      120      140

                                          V, WASTE INLET GAS, 1000's OF ACFM
                                                                                          200
                                                                                                 GO
                                                                                                 n>
                                                                                                 •o
                                                                                                 Oi

                                                                                                 o>
                                                                                                 o
                                                                                                 — i.
                                                                                                 fu
                                                                                                          ro
                                                                                                          -s
                                                                                                       co
                                                                                                       fD
                                                                                                       -o
                                                                                                       Oi

                                                                                                       CO
                  Figure  5-7  SCRUBBER INTERNAL SURFACE AREA AND SEPARATOR DIAMETER AND HEIGHT
                             VS. WASTE INLET GAS VOLUME

-------
      50,000
LU
O
i-^
Of.
O.
     40,000
     30,000
     20,000
     10,000
                                                           " Source-Ref 160,
          0

            0     •     5



         Figure 5-8  INTERNAL
10        15       20        25

  D, SEPARATOR DIAMETER, FT.

GAS COOLER BUBBLE TRAY COST VS. SEPARATOR  DIAMETER
                                        5-17

-------
B.    Determine the pressure drop across the scrubber required to obtain the
     desired efficiency (see Table 2.2) and find the required metal  thickness
     for the design inlet volume from Figure 5-5.   For 100,000 ACFM  and 30",
     the required metal thickness is 1/4"  plate (always round up to  the next
     standard plate thickness).
C.    From Figure 5-6, find the price adjustment factor for the design inlet
     volume and the material thickness found in Step B.  For 100,000 ACFM and
     1/4" plate, the factor is approximately 1.6.   Thus, the carbon  steel
     scrubber price is now $39,000 x 1.6 = $62,400.
D.    If stainless steel construction, rubber or fiberglass lining, or variable
     venturi section is to be included, refer to Figure 5-4 and adjust price
     accordingly.  For 304 stainless steel construction, the adjusted price
     would be $62,400 x 2.3 = $143,520.  If rubber linings are required, refer
     to Figure 5-7 to determine total square footage.
E.    If an internal gas cooler is to be used, determine the number of trays
     required based on an average of 5 Ibs of wateV* removed per sq.ft. of tray
     area with an outlet gas temperature of approximately 40°F above the inlet
     water temperature (this is valid for typical  scrubber outlet gas tempera-
     tures of 200°F or less, water spray temperatures of approximately 70°F,
     and superficial gas velocities of 600 fpm).  The total water to be removed
     is determined from the difference between the absolute humidities of the
     inlet and outlet gas conditions.  Determine the diameter of each tray from
     the separator diameter of Figure 5-7.  Read the price per tray  from
     Figure 5-8.  For 100,000 ACFM the separator diameter is approximately
     13.5 ft.; thus, the price for one tray is $14,000.  This price  includes
     the cost of the tray plus the cost of additional separator height needed
     to contain the tray.
                                     5-18

-------
 NOTE:  Radial tip fans are commonly used with scrubbers.

 5.3  Fabric Filters
      Gas cleaning by fabric filtration is suited for applications where dry
 particulates are handled or where water in the process gases is in the vapor
 state   The basic filter collector or "baghouse" is capable of operating in
 excess of 99% efficiency, although satisfactory operation of the system is
 contingent upon the characteristics of the gas stream and the particulate matter
 being removed.  Basically, the unit consists  of compartments containing rows
 of filter bags or tubes.   The particle-laden  gas is ducted to each compartment
 where the gas passes through the bags  while the particles are retained on the
 surface of the bags (the  particulate may be retained on  either the inside or
 the outside of the bags).  The pressure drop  across the  filter medium increases
 as the particulate collects on the fabric until  a  preset  time limit  is reached,
 at which time a section is isolated and the entrapped material  is  dislodged
 and collected in hoppers  located below the filtering area.   Baghouses are
 characterized by the methods and frequency of bag cleaning.   These methods  of
 cleaning are generally referred to as:   1)  shaker type,   2)  reverse air,  and
 3)  pulse jet.
     The  shaker type method of cleaning consists of hanging the bags on an
oscillating framework driven by a motor with a timer.  The baghouse is
separated into several compartments so that at periodic intervals, the gas
flow to a compartment is interrupted and the motors  and connected frames in
the compartment are activated with the subsequent shaking of the bags  to
remove the particulate.  The shaker type mechanisms  produce a violent  action
on the bags and, in general, produce more wear on the bags than other  types
           •                        -i
of cleaning mechanisms.  For this reason, shaker type cleaning is used in
conjunction with heavier and more durable fabric materials.
                                     5-19

-------
     The reverse air method of cleaning the bags is accomplished by passing
air countercurrent to the direction of the gas flow in normal  filtration
when the compartment is isolated for cleaning.  The reverse air is supplied
by a separate fan or in some cases, the pressure differential  across the bags
can be used to collapse the bags without the aid of a fan.   This type of
cleaning is used with fragile bags (such as fiberglass) or  lightweight bags
and usually results in longer life for the bag material.
     Bag cleaning by pulse jet is accomplished by the use of compressed air
jets located at the top of the bags.  Periodically, a blast of compressed air
is issued down the bag, rapidly expanding the bag to dislodge the particulate.
In some cases, this method of cleaning does not require the isolation of the
bags to be cleaned from the filtering process so that extra compartments
required for cleaning with the shaker and reverse air type  baghouses are not
needed.  In addition, the pulse jet baghouses can sustain higher filtering
velocities through the filter medium (higher air-to-cloth ratios) and there-
fore the overall size of the baghouse is reduced.
     Baghouses are also categorized as to the type of service and frequency
of bag cleaning and referred to as either intermittent or continuous duty.
Intermittent baghouses are cleaned after filtering is completed, i.e., after
the process stream is secured or shut down, usually at the  end of each day.
These baghouses operate with low dust loadings since they cannot be cleaned
while on stream.  Continuous baghouses operate indefinitely and cleaning of a
portion of the filter occurs at periodic intervals while the process gases
are being filtered by the remaining filter area.  Continuous duty baghouses
are more expensive than the intermittent type due to the accessories required
in the cleaning process and the additional filter area required for continuous
cleaning.
                                     5-20

-------
      The location of the baghouse with respect to  the  fan  in  the gas stream is
 also a factor in the capital  costs.   Suction  type  baghouses,  located on  the
 suction side of the fan, must withstand high  negative  pressures  and  therefore
 are more heavily constructed  and  reinforced than baghouses  located downstream
 of the fan  (pressure baghouse).   The  negative  pressure in the baghouse can
 result in the infiltration  of outside air which can result  in condensation,
 corrosion or even explosions  if combustible gases are being handled.  In the
 case of toxic gases,  this inward  leakage can have an advantage over  the pressure
 type baghouse,  where  leakage  is outward.  The main advantage of  the  suction
 baghouse is  that the  fan handling  the  process stream is located  at the clean
 gas  side of  the baghouse.   This reduces the wear and abrasion on the fan and
 permits  the  use of more  efficient  fans  (backwardly curved blade  design). However,
 since  the exhaust gases  from  each  compartment are combined in the outlet manifold
 to  the  fan,  the location of compartments with leaking bags is difficult to
 determine and adds  to the cost of  maintenance.  The outlet manifold from the
 baghouse is  connected to the  fans, usually located at ground level, and  a stack
is normally  required to  vent the gas  from the  fans.
     Pressure-type  baghouses are generally less expensive  since the housing
 must only withstand the differential  pressure across the  baghouse.   Maintenance
 is also  reduced  since the compartments can be entered and leaking bags can  be
 observed  with reasonable comfort while the compartment is in service.  With a
 pressure  baghouse, the housing acts as the stack to contain  the  fumes with  the
 subsequent discharge at the roof of the structure.   The main disadvantage of
 the pressure-type baghouse is that the fan is  exposed to  the dirty gases where
 constant  abrasion and wear may become a problem.
     The  design and construction of baghouses  are  separated  into two  groups:
 standard  and custom.  Standard baghouses are  pre-designed and  built as modules
                                     5-21

-------
which can be operated singly or combined to form units  for larger capacity
applications.  The custom or structural  baghouse is designed specifically for
an application and is usually built to the specifications  prescribed by the
customer.  The cost of the custom baghouse is much higher  than the standard
and is used almost exclusively in large capacity (large volume) applications.
The advantages of the custom baghouse are many and are  usually directed to-
wards ease of maintenance, accessibility, and other customer preferences.  In
standard baghouses, a complete set of bags are usually  replaced in a compart-
ment at one time because of the difficulty in locating  and replacing single
leaking bags, whereas, in custom baghouses, single bags are accessible and
can be replaced one at a time as the bags wear out.
     The type of filter material used in baghouses is dependent on the
specific application in terms of chemical composition of the gas, operating
temperature, dust loading, and the physical and chemical characteristics of
the particulate.  A variety of fabrics, either felted or woven, are available
and the selection of a specific material, weave,^finish, or weight is based
primarily on past experience.  The type of cloth will generally dictate the
type of bag cleaning mechanism to be used in the baghouse.  Usually, felted
fabrics use  pulse jet cleaning whereas woven fabrics use   mechanical shaker
or reverse air cleaning.  The type of yarn (filament, spun, or staple), the
yarn denier, and twist are also factors in the selection of suitable fabrics
for a specific application.  Because of the violent agitation of mechanical
shakers, spun or staple yarn fabrics of heavy weight are usually used with this
type of cleaning.  Filament yarn fabrics of lighter weight are employed with
reverse air cleaning.  The type of material will dictate the maximum operating
gas temperature for the baghouse.  Nominal operating temperatures for various
fabrics are listed as follows  (ref.  20):
                                     5-22

-------
                      COTTON:               180°F
                      POLYPROPYLENE:        180°F
                      NYLON:                200°F
                      ACRYLIC:              275°F
                      POLYESTER:            275°F
                      NOMEX:                425°F
                      TEFLON:               500°F
                      FIBERGLASS:           550°F
     The superficial  face velocity of gas  passing through the cloth affects
pressure drop and bag life.  The fundamental filtering parameters are based on
this velocity which is equal to the total actual  volumetric flow rate in cubic
feet per minute divided by the net cloth area in square feet.  This ratio is
referred to as the air-to-cloth ratio and is the basis for sizing and costing
baghouses.  High air-to-cloth ratios will reduce the size of the baghouse
(and subsequent cost) while low air-to-cloth ratios will  require larger units.
The air-to-cloth ratio will also determine the type of cleaning mechanism to
be used in the baghouse.  Shaker type and reverse air cleaning can be used
with air-to-cloth ratios of up to 4 to 1  while pulse jet cleaning can be
utilized with air-to-cloth ratios of up  to 10 to  1  or higher in special  cases.
The type of material selected as the filtering fabric will  also dictate the
range of air-to-cloth ratios to be used  in a particular application.  For in-
stance, polyester fabrics are normally used with  ratios of  up to 3 to 1,  while
fiberglass is usually limited to 2 to 1.  These limiting  ratios are the normal
"rule of thumb";  however, with light dust loading,  these  air-to-cloth ratios
can be exceeded in some cases.
                                     5-23

-------
     The cost reference for baghouses is based on the net cloth  area.   Net
cloth area is defined as the total  filter area available  for on-stream fil-
tration exclusive of the filter area in compartments  which are  isolated for
cleaning (in the case of intermittent filters, the net cloth area is  actually
the gross cloth area).  The net cloth area is determined  by the  air-to-cloth
ratio recommended for a particular  application, which is  principally  based on
the type of fabric, type of dust, carrier gas composition, and  the dust con-
centration.  The cost options of the fabric filter are therefore based on  the
following parameters as determined  by the type of application.
      1)   Type  of  fabric  and  air-to-cloth  ratio.
      2)   Intermittent or continuous  duty.
      3)   Pressure or  suction type  construction.
      4)   Standard or  custom  design.
      5)   Type  of  cleaning  mechanism.
      6)   Materials of construction.
      The typical  auxiliary equipment associated  wrth fabric filter systems  is
 shown schematically in Figure  5-9.  This  equipment includes the capture device,
 ductwork, radiant coolers, spray chambers, dilution  air  ports,  mechanical
 collectors, dust  removal equipment,  fans, and stack.
      Prices for mechanical shaker, pulse-jet, reverse-air,  and  custom fabric
 filters  (baghouses) are contained  in Figures 5-10 through 5-.14.  Prices are
 based on net cloth area, which is  calculated by dividing the gas volume
 entering the baghouse by the required air-to-cloth (A/C) ratio  (see  Table 2.2).
                                                                       2
 For example, to handle 100,000 ACFM at an A/C = 2.0  requires 50,000  ft net
                                                                              2
 cloth area.  The  price for a reverse-air, pressure-type  baghouse at  50,000  ft
 is $176,000.   For stainless steel  construction,  insulation, and suction-type
                                      5-24

-------
in
i
ro
Ul
         DIRECT EXHAUST
  FABRIC FILTER
V. n 0 O na
                                                                                                DUST  REMOVAL
                                              MECHANICAL COLLECTOR




                                  CONTROL DEVICE AND TYPICAL AUXILIARY  EQUIPMENT
                                      Figure 5-9  FABRIC FILTER CONTROL SYSTEMS

-------
U1
I
ro
CXI
             35
             30  i
25
20
          o
          o
          a  15
          OC
          Q.
                    Basic Baghouse Price =3.351 +1.84  x An
                                                                                Stainless Steel  Add On = 2.74
                                                                                  1.12 x An
                                                                                         m
                    1. Bags not included
    2.  Baghouse price in
W   3.  Net cloth area (An)  in
       1000 sq. ft.
                                                                                   -4 nil :^'i ::i  ittrtt 1:1: ::::
                                                                               t? Insulation Add On

                                                                               IT+ 0.84 x A
                                                                                               Source:  Ref
                                                                                                Fuller  Cu.
                                    S-Cuction Add On = 1.382 +  .12  x  A
                0
            24         6         8        10        12

                                     NET CLOTH AREA, 1000 SQ. FT.

          Figure 5-10  INTERMITTENT, PRESSURE, MECHANICAL SHAKER BAGHOUSE  VS.  NET CLOTH AREA

-------
r\>
-vj
o
o
o
                                       Stainless Steel Add On =1.65  + 5.0 x An
                      Basic Bagnouse Price
                                     5.37  +  7.6
                   1.  Bags not included
                   2.  Baqhouse price in $1000 ;;
                   3.  tlet cloth area (An)  in -^
                      1000 sq. ft.            ' '
                                                                                             Source: Ref 160
                                                                                             :Fullsr Co.
                                                               Insulation Add On = 4.91 +  2.4  x  An
                                             6         8        10        12       14

                                                  NET CLOTH AREA, 1000 SQ.  FT.

                   Figure 5-11   CONTINUOUS,  SUCTION OR PRESSURE, PULSE JET BAGHOUSE PRICES MS. NET CLOTH AREA

-------
01
I
ro
oo
O
O
O
         O
         I—I

         Q.
                                                              Stainless Steel  Add On
                                                                     1.9xAn
                 |  Basic Baghouse Price =
                 I  6.66 + 3".5 x An
                   1.  Bags  not  included}]
  2. Baghouse price in]
     $1000
  3. Net Cloth area
i    (AJ in 1000
1    sqn Ft.
  ms
Insulation Add On = 2.28 + 1.77

x An
                                                Suction Baghouse Add On = 2.26 + .25
                                                                                       Source: Ref  160^
                                                 NET  CLOTH  AREA,  1000  SQ.  FT.

                     Figure 5-12  CONTINUOUS,  PRESSURE,  MECHANICAL  SHAKER  BAGHOUSE  PRICES VS. NET CLOTH AREA

-------
ro
10
                                 SffiSMiK- ;:H
                                Basic  Baghouse  Price =  25.68 + 3.0
                                x An
                                                                             Stainless Steel Add On = 11.620+ 1.79
                   1.  Bags not included
               re  2.  Baghouse price in $1000
                   3.  Net cloth area (An)  in
                      1000 sq. ft.
                                                                               Insulation Add On = 11.2
                                                                                                   x An
                                                                Suction Add On = 1.69 + .32
                                                                             x A
                                                                                           Source:  Pef 160!
                                                     40       50        60       70
                                                 NET CLOTH AREA, 1000 SQ.  FT.
                      Figure 5-13  CONTINUOUS, PRESSURE, REVERSE AIR BAGHOUSE PRICES VS.  NET CLOTH AREA

-------
on
i
O
O
O
     UJ
     en
     o_
                      1. Bags not included
                      2. Baghouse price in $1000
                      3. Net cloth area (An) in
                         1000 sq. ft.
                      4.  Designed for continuous oper-
                         ation and reverse air cleaning
                     BAGHOUSE PRICE
                                           101.6 + 2.7 x An
                                                           INSULATION ADD ON = 38.0 + 1.4 x A
                                          if   STAINLESS  STEEL ADD ON  « 50.0 + 1.4    x An
                                                  150          200          250

                                               NET  FABRIC AREA, 1000  SQ.  FT.

                          Figure  5-14   CUSTOM  PRESSURE OR SUCTION  BAGHOUSE PRICES  VS.  NET  CLOTH AREA

-------
 design, the total  price without bags would be:
                 Baghouse             $176,000
                 SS                    100,000
                 Insulation             94,000
                 Suction                18,OOP
                 Total                 $388,000
      The prices  for bags may be determined from Tables  5.1  and  5.2.   From
 Table 5.2 obtain factor to calculate gross cloth area  (at 50,000 ft2  the
 factor is 1.11)  and from Table  5.1 obtain  the price per square  foot for the
 appropriate cloth  and  baghouse  type.  The  price of glass bags for the example
 is thus:                  •)                 0
                 50,000 ft* x  1.11 x  $.45/ft*  = $24,975
      Baghouse prices are flange-to-flange,  including basic  baghouse without
 bags,  10 foot support  clearance, and  inlet  and exhaust manifolds.  Pressure
 baghouses are designed for 12"  W.G.  and suction baghouses are designed for
 20" W.G.   Custom baghouse  prices are more  a function of specific requirements,
 than  of  pressure or suction construction so prices do not differentiate between
 pressure  or suction.   Custom baghouses are designed for continuous operation and
 normally  use reverse air cleaning.  All baghouses  except custom baghouses  are
 assumed to  be factory  assembled.
 5.4  Thermal and Catalytic Incinerator Systems
     Gas  cleaning by thermal or catalytic incineration is  well  suited for
 processes that emit combustible gases, vapors, aerosols, and particulates.
 These systems are used extensively in removing odors and in  reducing the opacity
 of visible  plumes from ovens, driers, stills,  cookers  and  refuse incinerators.
 The method  consists of ducting the exhaust process  gases to  a combustion chamber
which employs either a catalyst bed or direct-fired burners  to  combust the
contaminant gases to carbon dioxide and water  vapor.   Direct-fired gas burners
are more commonly used because of their simplicity  and reliability.   However,
                                     5-31

-------
                                              Table 5.1   BAG  PRICES  (S/SQ.FT.) Ref.  160
CLASS
Standard
> " ' ^ wi
Ł > °if '
Custom
TYPE
Mechanical shaker, < 20000ft
Mechanical shaker, >20000ft2
Pulse jet*
Reverse air
'•.••• .•..••,;•;,,•
Mechanical shaker
Reverse air
DACRON
.40
.35
.60
.35
:f;;-r:'::- . •:;:::.:;:
.25
.25
ORLON
.65
.50
.95
.60
',;"•-• ' ' .*•;•
' .' '"*" •: '•'•
.35
.35
NYLON
.75
.70
: .•.;'-.- ' '''••'• -.-. \
.70
'••'•'-•-.'•': •&•'':••.•••'••:';'•'•'
.45
.45
NOMEX
1.15
1.05
1.30
1.05
j&t >
.65
.65
GLASS
.50
.45

.45

.30
.30
POLYPROPYLENE
.65
.55
.70
.55
feH:W/^':
.35
.35
COTTON
.45
.40
:i":U:,;~.-:~*
.40

.40
.40
        * For heavy felt, multiply price by 1.5

                                           Table 5.2
APPROXIMATE GUIDE TO ESTIMATE

GROSS CLOTH AREA
01

CO
ro
NET CLOTH AREA
(Sq.ft.)
•j _
4001 -
12001 -
24001 -
36001 -
48001 -
60001 -
72001 -
84001 -
96001 -
108001 -
132001 -
180001 ON
4000
12000
24000
36000
48000
60000
72000
84000
96000
108000
132000
180000
UP
GROSS CLOTH AREA
(Sq.ft.)
Multiply by 2
1,5
1.25
1.17
1.125
1.11
1.10
1 . 09
1 . 08
1 . 07
1 . 06
1 . 05
1 . 04

-------
 catalytic  units  produce  combustion  at  lower  temperatures which  can  result  in
 lower fuel  costs.   In  direct-fired  thermal incinerators  (afterburners),  the
 contaminated  gas stream  is  delivered to the  refractory lined burner area by
 the  process exhaust system  or  by a  self contained blower.  The  introduction of
 the  gas  stream at  the  burners  insures  turbulence and complete mixing with  the
 combustion  products at the  highest  temperatures possible.  The  gas stream  and
 combustion  products then enter the  retention chamber at lower velocities to
 increase residence  time and ensure  complete oxidation of the combustibles.  To
 reduce fuel costs,  recuperative heat exchangers can be used downstream of  the
 retention chamber  to recover heat from the exhaust gases and preheat the inlet
 contaminated  gas stream.  A second method of recovering heat from the after-
 burner exhaust is  to recycle a portion of this gas to the inlet gas stream.
 The  efficiency of direct-fired afterburners depends on the type and concentra-
 tion of contaminants in the inlet gases, the operating temperature, the mixing
 of gases in the afterburner, and the residence time.   Heat exchangers, when
 added, increase the thermal efficiency and reduce fuel  costs at the expense of
 higher initial costs.  Secondary heat recovery may also be used to recover heat
 from the exhaust stream for use in the basic process  or for other purposes  such
 as ovens, dryers, vaporizers, etc.
     Direct-fired thermal incinerators can be provided  as packaged units  for
 small volume applications which include the basic chamber,  fan,  and controls.
 Larger units are usually custom designed or are modifications  of standard com-
ponents integrated into a complete unit.   The amount  of controls and instru-
mentation required for these systems will  depend on the characteristics of
the process gas stream.  Steady state processes require the least amount of
controls, .whereas fluctuating gas  streams  would require modulating controllers
for the burners,  recycled gas,  etc..  Most units only require  basic controls
such as safety pilots and flame failure shut-offs,  high temperature shut-offs
                                    5-33

-------
(fan failure),  temperature monitors and recorders.   The  fans  used for these
units are usually axial flow or low pressure centrifugal  type since pressure
drops for the incinerator alone are low (less than  2 inches W.6.).   If a heat
exchanger is included, the pressure drop may increase up to 6 inches W.G.
depending on the configuration of the heat exchanger and the  number of passes.
     An alternative to the direct-fired thermal incinerator is the catalytic
incinerator which utilizes a catalyst bed to oxidize the contaminants to carbon
dioxide and water vapor.  This reaction takes place at lower  temperatures
(650-1200°F) than the direct-fired incinerator (850-1800°F) and usually results
in lower fuel costs.  One of the limitations of the catalytic incinerator is
its susceptibility to fouling and degradation by particulates or metal poisons
such as zinc, lead, tin, etc.  For this reason, the gas streams containing
organic vapors or solvents are better suited for catalytic combustion while
those containing fumes and smokes should be controlled by the direct-fired
incinerator.
     The catalytic incinerator consists of the catafyst bed, preheat burners,
ductwork, fan, and controls.  The preheat burners are required to raise the
temperature of the inlet gas stream to a level compatible with the oxidation
reaction temperature of the catalyst.  To conserve on fuel costs, the preheat
burners can be regulated by controllers monitoring the exit gas temperature
of the catalyst bed.  As the bed temperature increases from heat transferred
by the exothermic reaction, the amount of heat supplied by the preheat burners
can be reduced accordingly.  This can result in a savings of approximately
40-60 percent in fuel costs as compared to the direct-fired incinerator.  The
catalytic incinerator, however, has a higher maintenance cost than the direct-
fired incinerator due to the necessity of periodically cleaning the catalyst
bed and the eventual replacement of the bed.  Catalytic incinerators are
                                     5-34

-------
available in packaged units  for small volume applications and custom units
for larger applications.  The normal pressure drops for catalytic incinerators
can be as high as 6 inches W.G. without a heat exchanger and 10 inches W.G.
with heat exchanger.
     The cost of thermal and catalytic incinerators is based on the inlet gas
volume flow rate, factors considering package or custom design, and whether a
heat exchanger is used for heat recovery.  The basic cost of the incinerators
includes the incinerator and base, fan, motor, starter, integral ductwork,
controls, instrumentation, and heat exchanger (where applicable).   For thermal
incinerators, the cost of the units also varies with the designed residence
time.   Longer residence times will  necessitate higher cost equipment due to
the longer and larger retention chambers.
     A minimum of auxiliary equipment is required for thermal  and catalytic
incinerators since the units are normally self-contained.   Usually some duct-
work, a fan, and a capture device are required to transport the process gas
stream from the source to the control device if the distance is appreciable.
A separate fan however is supplied with the incinerator to ensure  proper
distribution and mixing of the gases in the incinerator.   An exhaust stack is
also required to disperse the exhaust gases above the level  of  the surround-
ing buildings.
     Prices for thermal  incinerators including refractory  linings,  are  contained
in Figures 5-15 and 5-16.   Catalytic incinerator prices  are  found  in Figure
5-17.   Residence times for thermal  incinerators are based  on 0.5 seconds.   The
price of a thermal  incinerator without heat exchanger for  a gas volume  of
30,000 SCFM and 0.5 second residence time is $99,000.   With  a  heat exchanger,
the price would be $135,000.   The price of a custom catalytic  unit with heat
exchange would be $234,000 at 30,000 SCFM.  Note, gas volumes  are measured at
standard conditions.
                                    5-35

-------
i
u>
CD
       o
       o
       o
       Ul
       S   80
or
a.
a:
o
            60
            40
                             i
            20
                I


                                          if;


                                                                                                   TO
                                                                                g
                                                          Mote:
                                                         ^5.
                                                          6.
 Operating temperature of 1500°F
 Residence Time for incineration is
 0.5 seconds.
 Accuracy  of this  curve is  ;f 50%
 Price  includes incinerator, fan or  blower,
 controls  and instrumentation
 Prices will  vary  as  a function  of:
a.  Retention times
b.  Materials of construction

d.  Heat content of pollutant
Inlet concentrations  of 0-25% LEL light
hydrocarbons.
Process Temperatures of 70-300°F.
Oil fired burners.
Source: Ref. 37,  141,  160,  162
                                                                                                 4t
                                                    FLOW RATE, 1000 SCFM

                            Figure 5-15  PRICES FOR THERMAL INCINERATORS WITHOUT HEAT EXCHANGERS

-------
co
        o
        o
        o
        LU
a:
O-
            150
            130
                        UH
            no
        y    90
             70
             50
             30
             10
                        tut j
1
                                 I
                                 t;n
                   w
                       it
                        I
Mi
                                      iirt
                                         tir

                                        f
                                           fill
                                           ill:
                                           .1 t'
                             1
                             1
                                           '11!
                                              t
                                              in
                                                lit J
                                                       rt-
Note:
 1. Residence  time  of  0.5  seconds.
 2. Process Temperature  is  70  F
 3. Operating  temperature  is 1500°F
 4. Curve based on  35% heat recovery
 5. Accuracy of this curve  is  +_ 50%
 6. Price includes  incinerator, heat
    exchanger, fan.or  blower,  damper
    controls,  and instrumentation:
 7. Prices will vary as a function  of:
    a.  Retention times
    b.  Materials of construction
    c.  Special  controls
    d.  Heat content of pollutant.
 8. Inlet concentration of 0-25% LEL.
 9. Oil fired burners.
10. Source:  Ref.  37, 141, 160,  162
                                                                                                               1
                                                                                                             HI!
                                                       FLOW RATE 1000 SCFM

                           Figure 5-16  PRICES FOR THERMAL INCINERATORS WITH  PRIMARY  HEAT EXCHANGER

-------
en
CO
oo
       o
       o
       o
       UJ
       o
o:
o
                                        CUSTOM UNITS WITH 35% HR PRIMARY

                                        HEAT EXCHANGER
                                                                                   CUSTOM UNITS  WITHOUT HEAT
                                                                                     EXCHANGER
                                                                                1. Accuracies of ±50%.         '-
                                                                                2. Inlet  concentration up to    :
                                                                                  25% LEL  Light hydrocarbons  :
                                                                                  except packaged units.
                                                                                3. Operating temperature of
                                        PACKAGED UNITS
                                                                               4. Price includes incinerator.
                                                                                  fan or blower, stub stack,
                                                                                  controls and instrumentation.
                                                                               5. Source: ref. 37, 141, 160.
                                     (FOR CONCENTRATIONS UP
                                         TO 6% LEL)
            40
       0
                                                     FLOW RATE, 1000 SCFM

                                          Figure 5-17  CATALYTIC INCINERATOR PRICES

-------
      Reference  37  should be consulted for design and cost details of  inciner-
ators having different  residence times.  A thorough discussion of the difference
in  costs of materials is also included.   Longer residence time requires longer
residence  chambers and  consequently higher costs.  The type and temperature
limits of  the refractory linings will also affect the cost of the incinerator.
For approximation  purposes, a reduction in residence time from 0.5 seconds to
0.2 seconds will result in a cost reduction of 25 percent.  Increasing the
residence  time  to  1 second will increase the costs by approximately 25 percent.
Secondary  heat  recovery may be added through the use of a waste heat boiler or
a secondary heat exchanger.  The cost of secondary heat recovery is difficult
to  estimate because of the variety of devices used for this purpose.  If a
secondary  air-to-air heat exchanger is used downstream of an incinerator with
primary heat recovery, the added costs can be estimated to be 25 percent of
the incinerator/primary heat exchanger costs.
     The cost curves for thermal incinerators are based on an operating temper-
ature of 1500°F.  The cost of incinerators operating at other temperatures can
be determined by adjusting the inlet gas flowrates to account for the tempera-
ture difference as follows.
                Flowrate (SCFM) at t      t  + 460
(SCFM)  at t
(SCFM)  at t
                Flowrate (SCFM) at t      t  + 460
where:  t  =  new temperature, °F
        tb =  baseline temperature, 1500°F
5.5  Adsorbers
     Gas cleaning by adsorption is used primarily in  the removal  of organic
liquids and vapors from process streams.   The principles of adsorption and the
affinity of certain adsorbents for specific compounds are quite complex.
                                     5-39

-------
 The process  can be described as  the  mechanical  and  chemical  bonding  of  a
 substance on the surface of an adsorbent.   The  control  system  using  this
 principle  usually  consists  of  at least two  adsorbent beds with one bed  on
 stream adsorbing while the  second bed is regenerating.  Regeneration is usually
 accomplished by heating  the adsorbent to a  high temperature  to drive off the
 adsorbed  compounds.  Continuous adsorbers have also been devised where  adsorption
 and regeneration take place in different positions of the same bed, which is
 progressively displaced  through the  vessel.  Some problems that exist in adsorp-
tion systems are the result of solids in the process gas stream.   Particulate
matter in the gas stream can be detrimental  to adsorber beds by blinding the
adsorbent; therefore, efficient filters must be provided at the inlet to the
beds.  Corrosion is also a factor in the maintenance of the beds  and equipment,
and is usually related to the method of bed regeneration.   Activated carbon is
the most widely used adsorbent in industry;  however, other adsorbents such as
silica gel,  bauxite, and alumina are used for some specific processes.   The
                                                    s
regeneration of activated carbon adsorption beds is normally accomplished by
passing steam through the bed  in the opposite direction of the normal gas flow
during adsorption.  The  flow rate, temperature, and pressure of the steam
required for regeneration is dependent on the type and characteristics of the
adsorbate and the quantity adsorbed.  After regeneration,  the beds are normally
cooled by passing clean  air through the carbon before being placed on stream.
Fixed bed adsorbers usually consist  of at least two beds; one adsorbing while
the other is regenerating.  If the time for regenerating and cooling is longer
than the adsorption time, three beds may be used; one adsorbing,  one regenerating,
and one cooling.  The operations involved with switching beds from the adsorption
stage to the regeneration stage can be either manual or automatic.  Automatic
systems cost more due to the mechanisms and controls required.  Carbon adsorbers
                                      5-40

-------
 are  supplied  as  either  packaged units for small volume applications or  custom
 designed  units for  larger applications.  The units, as supplied, consist of the
 adsorber  beds, activated carbon, fans or blowers, controls, and the steam
 regenerator (excluding  steam source).
     The  capital cost for a carbon adsorber is based on the gross weight of
 carbon required  for the application.  The amount of carbon is determined by the
 ventilation rate, the type and mass emission rate of the pollutant, the length
 of the adsorption and regeneration cycle, and the carbon adsorption capacity at
 operating conditions.   The key design parameters that determine the size of the
 carbon adsorber  are the face velocity and the bed depth.  The desired face
 velocity  is approximately 80 to 100 feet per minute for most commercial and
 industrial applications involving solvent recovery and the depth of the beds
 may vary  from 6  inches  to 30 inches.  For air purification systems where the
 concentration of pollutants is in the order of 1 ppm or less, the desired face
 velocity  is reduced to approximately 40 fpm with bed depths of 0.5 to 3 inches.
 For a given ventilation rate in acfm, the face velocity and bed depth determine
 the working bed volume and consequently the weight of carbon.
     For  design purposes, the working bed volume for a selected cycle time  can
 be determined from the adsorption isotherm for the particular adsorbent and
adsorbate.  The adsorption isotherm is a plot of the adsorption capacity at
constant  temperature as a function of the vapor pressure or the relative partial
pressure of the adsorbate in the gas stream.   Normally,  the adsorption capacity
of an adsorbent increases with increased vapor pressure  and decreases  with
increased temperature.   Using the  appropriate adsorption isotherm,  the adsorption
capacity in pounds  adsorbed  per pound of adsorbent can be obtained  for the
desired operating conditions.   The adsorption capacity is then multiplied by a
                                     5-41

-------
design factor of between 0.1 and 0.5 to determine a working capacity.   From
discussions with manufacturers, a design factor of 0.25 is adequate for prelim-
inary sizing of most applications (Ref 151).  The weight of carbon for each bed
is then determined by multiplying the emission rate in pounds per hour by the
adsorption time in hours and dividing by the working capacity in pounds adsorbed
per pound of adsorbent.  For example, assume that toluene vapors at 70°F are to
be recovered from a source at a rate of 6.15 Ib/min. and the inlet concentration
to the adsorber is to be maintained at 25% of the lower explosive limit (LEL).
The LEL for toluene in air is 1.29% or 3.07 lbs/1000 cu.ft.; hence, 25% of the
LEL would be 0.32% or 0.768 lbs/1000 cu.ft..  The flow rate through the adsorber
is determined by dividing the recovery rate (6.15 Ibs/min) by the concentration
           _3
(0.768 x 10   Ibs/cu.ft.) to obtain a gas volume rate of 8000 cfm.  The vapor
pressure of the toluene  in air at a total pressure of 760mmHg  is determined
by multiplying the concentration (0.0032) by the operating pressure (760 mm Hg)
to obtain a pressure of 2.4mm Hg.  Using the adsorption isotherm in Figure 5-18,
the adsorption capacity in percent by weight at this vapor pressure is 35% or
0.35 Ibs of toluene per Ib. of carbon.  Note that the adsorption isotherm is
for operating temperatures of 21 °C (70°F) and operating pressures of 760mm  Hg
with a carbon adsorbent having a density of 27 Ibs/cu.ft..  A working  capacity
of 8.75% is obtained by multiplying the adsorption capacity from Figure 5-18
by a design factor of 0.25.  If the adsorption period is one hour per  bed, then
369 Ibs of toluene (6.15  Ibs/min x 60 min/hr) will be recovered per bed.  The
carbon requirements per bed will be 369 Ibs/hr divided by 0.0875 Ibs toluene/
Ib carbon or approximately 4200 Ibs per bed.
     Adsorption isotherms for other hydrocarbons are available from handbooks
and manufacturers literature.  These isotherms are developed for particular
                                    5-42

-------
•sf.
a.
CO
o
m
a:
                                                          Pressure:  760 mm Hg

                                                          Carbon:  27 Ibs/FP

                                                          Source:   Ref. 161
       0.01
                         TOLUENE VAPOR PRESSURE (mn Hg at 21°C)
       Figure 5-18  ADSORPTION  ISOTHERM FOR TOLUENE
                                            5-43

-------
adsorbents operating at certain pressures and temperatures.  Experimental work
has also been done by carbon adsorber manufacturers and others to determine
working bed capacities for various hydrocarbon emissions at a temperature of
100°F and a flow rate of 200 acfm per 100 Ibs carbon (see Table 2.3).  The value
of 200 acfm per 100 Ib. carbon represents the approximate combination of 80
feet per minute and a bed depth of 1.5 feet.  These values are based on
empirical data and caution should be exercised in their use.
     Prices for carbon adsorbers are presented in Figures 5-19 and 5-20, as a
function of total pounds of carbon in the unit.  The total or gross number of
pounds is determined by the adsorption rate and the regeneration rate of the
carbon for the emission being controlled.  A carbon adsorber will normally be a
dual system with one bed on-line adsorbing while the second bed will be off-line
regenerating.  A likely estimate of regeneration time for almost all applications
would be between 30 minutes and an hour.   The variation in regeneration time is
due to the type of solvent being desorbed and any drying and cooling requirements
Normally, one hour is the longest expected regeneration time.  The adsorption
phase generally requires one hour also; particularly where working bed capacity
may be low and the mass emission rate is high.  For some operations, such as
dry-cleaning and solvent metal cleaning where working bed capacity is high, a
longer adsorption phase may be desired.  This is likely if steam capacity for
desorption is not always available during a typical operating day.
     Figure 5-19 represents packaged units for automatic operation in commercial
and industrial applications.  Commercial applications cover dry-cleaning and
solvent metal cleaning.  Industrial applications include lithography and petro-
chemical processing.  Industrial requirements would increase costs 30 percent
over commercial requirements.  Industrial requirements would include heavier
                                    5-44

-------
tn


*>
en
         o
         o
         o
o

a:
LU
            80
            70
            60
            50
            40
         o

         2
            30
            20
            10
1, „ mrHHmm ,





	 	 I 	
,, .,, ,:,..:::, ... f:. .,::,,::;: , 1 j: •
! ,.: ;;.:•.!::... =:. :=: ii! : :!;;!:!; ii :{;}:: \
T r .,.,... 7 r .
;:: :!:,,:...:. 	 |I -' = ;"- - - - {•: •
1 : ;{t--Mfi:i '':,-;• I :; y
f (4 if.. ! : :- ::: ::•• : j
M--: : i" ti; :fi: | H
: : 5 AIM ••••••' | ] :1J
;: I I,'-:: JLl|.::::i;.: ::; :•::.;;
n/ - r? f :: t:I ^
| tj-H 	
i •* : tf|: j ••

;;i: ii1 •;: . .: |7 -tt ;:: | f :' "" ::
•:•; -:: ;: 1 ft f [ : p: :
. . 1 . . 1 i + ] 1 - J
: "L 1 L L wl f -1 ~4 "
.:! (liil, ju^ll.luLlI:;!} ;; :tIi.U
Ll iLir.i-: jtS ! :ittij-
0123
1**™* ::-; ; =;; ;;; 	 	 ;; E; ; -
!h:M!!i 	 MNiiMMiNNiMMii!
= ; :! !;: : i ; i : i! 	 Mi! =:::M iiii: ^i;
- ' '-'I ':'.': '•"•• • ' : ' ''• • 	 ' , ^''[ '- • 	 ! -:
iP^^H^^^^^^H^Hiffi

:''j ::-J|-M;'I:I: MJI j|j|!;|!: |||:1
':':- ' ' ::: :::: 	 j 	 ' ::: :' - :: - : '':
: .: J :. | ;;. j : :;-. :/: : ; : :: :• ::. : ;. :::. ::;i : | 	 ;;:
ffl|j|tnm}[nij}|{|S^lllfffl^
NOTE: 1. These prices are for basic
} If including adsorber, carbc
| or fan, controls, and st
;;. f- -: F |f
-1: 	 f-MI
i-:-"iS|iP
t: ::;: :::.iBi iiil
': -Efe
:l Cliiii
fit r • + * •
f IT ; ! ; l;
iifiiui
iiiiii si
!l U ! :i;: i : ::::
ailiiliiU Ui IU:
]h . l|i .ir : : !:::
alHl^'-iU--::
:H ni|:il| FT :l
Tt tbi d:i : : i :
:t J.i|t tl'i : ' :;
:l Hi Hii - :-:
ffl fi IHi H i i:
. 1. .11 t .If . I .
systems , J
n, blower |
earn *
i '•'•'•" \ '•$ '"• " regenerator. Special requ i r-anen us r:
I,.: :: .'.':: maV dOLlhlP thf> CO«it ;*!
r . : . ^ f j
: : 1 fT 2. These prices are for commer
: : .'., -. . ;.iiLti annl i rat i nn AHH Tn^l fnr

.:: ^ |; tions involving stringent
1 • \t •'• industrial standards.
' f i j ||||||j ffi|| ^ . ^niirrp; Rpf. 6Q , 160V 161
i j - - 	 i
pltl^T ::^
HI fmltillt}f^iti[{iiij|fffif||ml^ ' j|]|^:lllllillitiiill I' [j (I
45678
•cial ~
app 1 1 Ca- ...
166 A
t.
l|i
\' i T f 1
9 1(
               Figure 5-19   PRICES FOR PACKAGED
                                          WEIGHT OF CARBON,  1000 IBS.


                                        STATIONARY BED CARBON ADSORPTION UNITS WITH STEAM REGENERATION

-------
en
i.
•Ł>
CT>
        O
        O
        O
        O
03
oe.
o
to
o
        «c
        o


        o

        00

        o
                                                                                      INSTRUMENTATION AND

                                                                                      CONTROLS  INCLUDED.
                                                                        Source:   RUf.  40, 160, 161, 162
              0
                                   60         80


                                       TOTAL  WEIGHT OF
100       120      140


 CARBON,  1000 LBS.
                                     Figure 5-2Q   PRICES FOR CUSTOM CARBON ADSORPTION UNITS

-------
materials for high steam or vacuum pressure designs and more elaborate  controls
to assure safety against explosions and prevent hydrocarbon breakthrough.
Figure 5-20 presents custom units, mostly for industrial applications where  the
gas flow rate exceeds 10,000 acfm.  Table 5.3 is provided to estimate annualized
control cost requirements for steam, cooling water, maintenance, electricity,
and carbon replacement.  These values and assumptions represent the composite
of information provided by EPA contractual reports and in-house files.  To use
the values in Table 5.3 the required inputs are the pollutant emission rate,
recovery efficiency, annual operating hours, exhaust gas rate,  and the purchase
price.  The carbon weight used to determine the purchase cost can also be used
to estimate the carbon replacement cost.
      In Table 5.3, the steam consumption is based on the energy necessary to
heat  the bed and vessel from the operating temperature ( 100°F) to the solvent
boiling temperature plus the energy required to evaporate the solvent from the
bed.  The heat of evaporation is directly proportional to the quanity of solvent
present, however, the sensible heat added to the bed and vessel depends on the
amount of carbon and the design of the bed.   Some sources have  related the steam
usage to the quanity of carbon (0.3 Ibs steam per Ib carbon, Ref.  161), however,
for study estimates, a value of 4 Ibs steam per Ib.  solvent desorbed is reason-
ably accurate and acceptable.   The cooling water requirement varies directly
with the steam consumption rate in that it represents  the heat  removed in con-
densing  and subsequent cooling of low pressure saturated steam.   The electrical
requirement is based on a pressure drop of 20 inches W.G.  using a  bed depth of
1.5 feet of 8-14 mesh carbon.   The pressure  drop through a  carbon  bed is a
function of the carbon granule size,  the size distribution,  the packing of the
bed and flow velocity.   Given  a specific carbon bed, the pressure  drop through
the bed will  be proportional  to the square of the  superficial face velocity.
                                    5-47

-------
in
i
*>
00
                           TABLE 5.3  TECHNICAL ASSUMPTIONS  FOR ESTIMATION  OF  DIRECT OPERATING COSTS

              Item                           Assumption                                   Reference
              Steam Consumption              4 Ib per Ib.  pollutant  recovered              MSA, DOW, STAUFFER, VIC
              Cooling Water                  12 gal per 100  Ibs.  steam                    SHAW
              Electricity                    5 HP per 1000 ACFM                           STAUFFER, MSA
              Maintenance                    5% of equipment purchase  cost                 Compromise between DOW and MSA
              Carbon Replacement             Replace original  carbon every  five years      STAUFFER, MSA
              MSA - "Hydrocarbon Pollutant Systems  Study"  by MSA  Research  Corp.,  EPA Contract EHSD 71-72, January, 1973.
              DOW - "Study to Support New Source Performance Standards  for Solvent Metal Cleaning Operations", EPA
                    Contract 68-02-1329,  Dow Chemical  Co., June,  1976.
              STAUFFER - Private communication from J.  J/"Harte,  Stauffer  Chemical Co.  to  Richard Schippers, EPA,
                         April  11, 1977 on subject  of carbon adsorber costs for control of ketones and  toluene.
              VIC - Private communication from J. W.  Barber, Vic  Manufacturing Co., to  F.  L. Bunyard, EPA,  June  3, 1977.
              SHAW - "Carbon Adsorption/Emission Control  Benefits and Limitations", paper  presented  at  Surface Coatings
                     Industry symposium,  April 26,  1979.

-------
     Since many adsorption applications involve recovery of a re-useable
solvent, a by-product credit should be included in determining the annualized
costs of control.  This credit can have a substantial  effect on the amortiza-
tion rate of the capital costs of the equipment.   For  instance, in the previous
example of an adsorber recovering toluene at a rate of 369 Ibs per hour, the
control device cost based on a unit having two beds (8400 Ibs carbon total)
is $66,500 (see Figure 5-19).  The addition of taxes and freight at 8 percent
from Table 3.3 results in a purchased equipment cost of approximately $72,000.
The total  installed cost for a typical  installation (Table 3.3)  is  1.61  x
$72,000 or approximately $116,000.   The total  annualized cost can be determined
based on the following assumptions:   1)   5800  hours annual  operation,
2)  10-year equipment life,  3) 10% annual interest rate, 4) annual maintenance
cost of 5 percent of capital costs,  5) a value of $0.10 per pound for the
recovered product, and  6) operating labor requiring 360 man-hours per year at
$7.87/man-hour.  The cost basis is developed from Table 3.4 and the annualized
cost breakdown is as follows:
     1)  Operating labor ..... ---- ...................... ----------  $~  2,800
         (360 m-h x $7.87/m-h)
     2)  Maintenance --------- ..... -------------------------------  $~  5,800
         (0.05 x $116,000)
     3)  Carbon replacement at 5 year life -----------------------  $~  1,400
         (84g°Jb C  x $0.85/lb C)
            a yr
     4)  Steam ----------- .......................... --------------  $~ 43,200
         (369 Ib/hr x 5800 hrx'41b/lb x
     5)  Electricity ----------- ..... - ................ - ...........   $-   7,500
         (SOOOcfm x  gj cfm x °'74jLkwh  x 5800 hr x $0.0432/kwh)
                                     5-49

-------
     6)  Cooling water	•»	  $~  6,200
         /12 gpm         1476 1b steam   60 min   ,.ftnn ,     $0.10   \
         (T001b steam x	h?	x HF^ x 580° hr X 1000 gal'
     7)  Capital charges @ 22% --			-	—  $~ 25,500
         (based on 10 yr. life, 10% interest & 5.725% for taxes,
         insurance, admin., etc.)
     8)  By-product credit	-		($-214,000)
                                                      TOTAL        $-121,600

     The annualized costs for this example is a negative $121,600 indicating
a decided cost advantage to solvent recovery for this application.

5.6  Absorbers
     Gaseous pollutants in a process stream can be removed or reduced through
absorption using a solvent having a high gas solubility to dissolve or chemically
combine with the solute.  The combined solvent and solute can then be further
processed by stripping or desorbing to remove the solute and recover the solvent
                                                     s
for reuse.  In some cases the combined product may be returned to storage without
separation as in the case of hydrocarbon recovery in oil or gasoline.  Although
absorption is used as a basic process in the chemical industry for the manufac-
ture of acids and other chemical compounds, it is also used as an air pollution
control device for the removal of gaseous contaminants such as sulfur dioxide
and hydrogen sulfide from waste gas processes or the recovery of hydrocarbons
from bulk storage and transfer operations.
     The fundamental  concept in the design  of an absorber is  the provision for
good contact between the gas and the liquid.  To achieve this,  absorbers have
been developed by the various manufacturers with specific proprietary design
features.  Each design, however, can be categorized by the type of construction
                                     5-50

-------
and the method of contact employed.  These are typically identified as packed
tower, spray chamber, tray tower and venturi absorbers.
     Packed towers and tray towers are the most common absorbers used today
and the design considerations for each are amply covered in Reference 88.
Packed towers consist of a vertical column filled with irregular-shaped
packing, gas-liquid distributors, support plates for supporting the packing,
liquid sprays, and entrance and exit ports for the liquid and gas streams.
The gas and liquid flow through the column can be either concurrent or counter-
current, the latter being most often used.  In the countercurrent tower, the
gas enters the bottom of the column, passes through the packing material and
exits at the top of the column.  The liquid solvent is delivered to a manifold
of sprays or other devices at  the  top of  the column and is sprayed over the
packing to wet the entire surface.  The liquid solvent trickles down through
the packing countercurrent to  the gas flow rising through the column.  To
preclude channeling through the tower, particularly with long columns, distri-
butors are located at intervals to redistribute the liquid over the cross-
section of the column.  These distributor plates have selective openings for
both the gas and liquid.  Support plates are also required at intervals to
support the packing.   These plates which may provide a dual  function of both
a support plate and a distributor plate, should have a larger open area than
the column area with packing so that they do not substantially affect the
overall pressure drop.
     In the design of a packed tower,  four basic parameters  establish the size
and operating characteristics of the unit.  These include  column diameter,
pressure drop,  number of transfer units  and the height of  the transfer unit.
                                    5-51

-------
To determine column- diameter, the gas and liquid flow rates, gas and liquid
densities, type of packing, and the liquid viscosity must be known or estimated.
The superfical gas velocity and column diameter are determined from empirical
graphs which estimate the pressure drop correlation and generalized flooding
condition for various packings.  The flood condition is a point at which
increased gas flow will result in excessive pressure drop and liquid entrain-
ment in the gas stream.  Normally, design velocities for a packed tower are
based on a certain percentage of the superficial gas velocity at the flooding
condition.  This percentage is based on the orientation and type of packing
material.
     The performance of the tower is predicted from experimental data in two
forms:  1) the required number and height of transfer units, and  2) the gas
and liquid film mass transfer coefficients.  The use of either system is a
matter of choice and usually depends on the units in which the operational  and
equilibrium data are presented.  A thorough description of the development of
                                                     S
the design criteria for a packed tower absorber using the transfer unit system
is contained in Reference 88, "Air Pollution Control Manual" AP-40 and therefore
that system of units will be used in this discussion.  The transfer unit concept
offers the advantage of the characteristics of the packed tower being expressed
as a number of units with a corresponding height in feet.  The number of trans-
fer units is related to the efficiency of the absorption process itself, while
the height of the units is concerned with the geometric and flow characteristics.
     Using the transfer unit method of design, the column height can be deter-
mined from:
     column height = H   x N   + h
                                     5-52

-------
      where:    H   =  height  of  transfer  unit

               N   =  number  of  transfer  units

               h   =  added height  for vapor/liquid separation, cleaning, etc.


 The value,  h  ,  depends on the  specific  application, although it normally

 becomes  less  significant as H  „ and N   increase.  The height of the transfer
                             og      og

 unit,  H   ,  can  be  determined from:
              og
                                 0.5
                                                              (Ref. 88)
     where:  a.e.y are packing constants (see Ref. 88)
                                                                          2
             G  =  superficial gas mass flow rate through column (Ib/hr-ft )
                                                                        2
             L  =  superficial liquid flow rate through column (Ib/hr-ft )

             VG =  gas viscosity (Ib/hr-ft)

             PQ =  gas density (lb/ft3)

             D6 =• gas diffusivity (ft2/hr)
Although the above equation (obtained  from  Ref. 88) neglects the effect of the

liquid film resistance,  it is  sufficiently  accurate for study estimate designs.


     The number of transfer units,  N   , can be approximated by the following:


                            mg   y - mx     '"G

               NOQ = ln  [(1- -r)(Y1 -»"x2) + r^
                 s            m    2     2     m
                                 •"G
     where    m   =   slope  of  the solute/solvent equilibrium curve

                                                                  2
              G   =   superficial molar gas. flow rate (Ib-mole/hr-ft )


              L   =   superficial molar liquid flow rate (Ib-mole/hr-ft2)
                                     5-53

-------
           Y,  Y?   =   mole  fraction of  solute  in gas stream at  concentrated  and
                     dilute  ends  of  countercurrent tower, respectively
              X2   =   mole  fraction of  solute  in liquid  stream  at  dilute  end
                     of tower.
     This equation for N   is based on the work of Col burn (Ref.  Trans.  AICHE,
                        og
35,216 (1939) and is duscussed further in Reference 164.   It is  only applicable
to those systems where the equilibrium curve is linear or where  the solute
concentration is less than 3 percent by volume.  This encompasses most air
pollution control applications.
     An example problem illustrating the method of determining tower diameter,
height and type of packing, flow rates and pressure drop  for a packed tower
absorber is contained in Reference 88.  This design process must be completed
to establish the equipment cost criteria for this type of absorber.
     Tray towers are similar in many respects to packed towers.   Instead of a
gas-liquid interface on the surface of the packing, the gas is bubbled through
the liquid contained in a tray.  Several trays are arranged in a  vertical column
and the liquid cascades downward from one tray to the next.  The trays are
usually designed to permit vertical gas flow through bubble caps or perforations
while the liquid level in the trays is maintained by a weir.  Overflow from each
tray cascades to the next lower tray and is removed from  a sump  at the bottom of
the tower.  The gas flow enters the bottom of the tower and passes upward
through the openings of each tray, through the liquid held in each tray, and
finally exits at the top of the tower.  Theoretically, as the gas passes through
each tray, it is assumed that the gas mixes with liquid of uniform composition
and is in perfect equilibrium with the liquid.  Even if perfect  equilibrium is
                                     5-54

-------
assumed, the absorption efficiency would not necessarily be  100  percent.   The
absorption efficiency is limited by the solute concentration  in  the  solvent  and
the gas stream, the temperature, and other variables.  However,  perfect equil-
ibrium cannot be obtained on an actual plate and therefore it is necessary to
introduce a performance factor, known as the plate efficiency, to express  the
relation between the actual and an ideal plate.  A discussion of the development
of the design criteria for tray towers is also included in References 88 and 164.
For a given application, the tower diameter, type and number of trays, and
operating characteristics are needed to develop equipment and operating costs.
     A simpler type of absorber is the spray chamber which provides gas-liquid
contact without the use of packing material or trays.  These devices are also
used to cool hot gas streams or add moisture to the gas (see section 4).
Typically, a spray chamber consists of an empty vessel equipped with a
series of nozzles which spray liquid over the cross-section of the chamber
while the gas passes through the sprays.   The size of the droplets depends on
the type and size of nozzles and the pressure of the liquid supply.   Nozzles
can be selected to provide a nominal  droplet size, however, in the spraying
process, some drops agglomerate while other disintegrate into smaller drop-
lets.   The fine droplets have a tendency  to be entrained  and  carried away  in
the gas stream while the large droplets  traverse the gas  stream and  collect on
the walls of the chamber.   This combined  with the short contact time reduces
the efficiency of the absorption process  as such.   One advantage of  spray
chambers is that both particulate and  gaseous  contaminants  can be removed from
a gas  stream.   This is  of particular  importance with gases  that also produce
solid  deposits when reacted with the  liquid solvent.   Another advantage  of spray
chambers is the. possibility of cooling gas streams at high temperatures where
                                     5-55

-------
the packing material  in a packed tower might be affected by these high temper-
atures.   Spray chambers are used primarily where the absorbed gases have a
high solubility and only a few transfer units are required for the absorption
process.  To reduce the carry-over or entrainment of small droplets, the gas
velocity in a spray chamber must be low.  As a result, the diameter of the
chamber, and hence the cost, become rather large as the design flow rate is
increased.  To compensate for this, cyclonic spray chambers have been developed
where the gas enters the chamber through a tangential opening and the liquid
is injected at the axis through a row of nozzles.  The cyclonic action assists
the separation of the'liquid droplets from the gas and permits higher gas
velocities,  The cost of spray chambers is related to the type and thickness
of construction materials used, such as stainless steel, rubber-lined steel,
etc., and the configuration of the vessel in terms of diameter, height, and
tangential or axial inlet.
     Venturi absorbers are similar to spray chambers in that they too can be
used for gaseous and particulate removal.  As described in Section 5.2, the
venturi scrubber/absorber achieves contact between the gas and the liquid in
the throat of the venturi where the gas is accelerated to high velocities at the
point where the liquid is injected.  The shearing action of the high velocity
gas on  the liquid stream or droplets produces a fine mist and good dispersal.
The relative velocity between the gas and liquid droplets insures good contact.
 However,  the  contact  period is  short  and  the number of transfer  units  that
 can  be  expected  is  similar to that obtained  with  a  spray  chamber.   As  a
 result  of the  high  velocities in the  venturi  and  the fine droplets  generated,
 the  carry-over or entrainment is considerable and therefore  a mist  eliminator
 is generally  required  downstream to remove this  liquid from  the  gas  stream.
                                     5-56

-------
 To provide the high gas  velocity,  a  substantial  amount of energy must be dis-
 sipated in the venturi  in  the  form of pressure loss  and this  represents high
 power costs at the fan.  Maintenance costs  are also  increased due to the
 abrasion at the venturi  and fan  caused by the  impact of liquid in the gas
 stream.
     The costs  of spray chambers  and  venturi  scrubbers are covered in Sections
 4.3 and 5.2.    The cost  of absorption towers is  shown in Figures 5-21 through
 5-24.  The cost of these towers  depends on  the size, thickness,  and  materials
 of construction of the  vessel  since  these units  are  basically custom designed
 for individual  processes and applications.   To develop the design parameters,
 the design sequence demonstrated in  Reference  88 should  be followed  to deter-
 mine the tower diameter, pressure  drop,  and  the  number and height of transfer
 units for the  specific  application.   Figure  5-21 illustrates  the fabricated
 cost of a carbon steel  vessel  shell  in dollars per linear foot plus  the cost
 of two semi-elliptical  heads.  The height of the vessel  is determined by
 multiplying the number  of  transfer units  by  the  height of the transfer units
 plus  some  additional heinht for vapor/liquid separation at the top of the tower
 and cleanout at the bottom.(typically 2-3 ft plus 25% of the diameter, ref. 38).
 The shell  thickness is determined from Table 5.4 for the expected internal
 operating  pressures and temperatures.  In many  cases  a corrosion allowance of
 1/8-1/4 inch is also added to the minimum thickness for carbon steel  constru-
 tion.  The cost of the fabricated vessel alone, therefore, includes the cost
 of the shell plus the cost of two heads.  The fabricated cost  of a skirt which
 is provided for support of the  vessel and flange-type nozzles  for shell
penetrations must also be added to  the vessel cost.   Figure 5-22  reflects the
cost of skirts  which include a  base plate, anchors, an 18-inch diameter access
opening, two reinforced pipe openings and a  vent hole.  The thickness of the
                                     5-57

-------
    10,000
t/5
O
O
O
O
o
ac.

-------
00
CO



CO
4600





4400





4200





4000





3800





3600





3400





3200





3000





2800





2600





2400





2200
o
g   2000
CO
    1800
    1400
    1200
    1000
           r
           ±k
          0
                                               4ii
                                                         L
                                                        i L/
                                                         "
                                                           r
                                Source: Ref. 160, 165, 166
                 2345678


                                 SHELL DIAMETER (FT)
                                                                     10    11     12    13
                                                                                             14
                Figure 5-22   SKIRT AND SUPPORT COSTS FOR CARBON STEEL VESSEL
                                             5-59

-------
1800 i - -^L
1700 b=pi
1600 ^r-^
1500 ~^-—
| ; ' ''II
1400 H^
1300 HIE;
1200 ^=Ł
i ' ' "T •
— 1100
*~ 1 1 \'< ' 1 ; i ' ' 1
g 1000 =^i±S
o i i
UJ -l-r j--*— *•
W 900 H^
O i--14" -H — r
UJ 1
Ł 800 =5EJ|
i -I--1-1 — — r
Ul ---.131
i ;:1^;
< 700 ;|P?;
U. :S:::+:
600 ;=Ł=+;
500 :i;=g
400 || H
300 1 II | I ' I
200 Unffifji
i r*n " t iit- "
100 7, -^T
0 Ł::±:::
0 2
= :150 PSI
Ł3:4 Flanqe-T
-rj-*- ' ' ' ' j|ii i i i i
1 T "T •' •"*"[ *"T"T * I !
----i- ,iji i | i -I--J-.-
i ,.i . . j 1 ; -tit i . ( 1
pi-i-. — i-_*. | , | . — TJ;^
i=li?:g
Bjtj*-Ł— Ijtf
Rai
ype
4r^i-
i' ! i I
^rrr
4-> )-(..
Ill 	
t i t •
-p-H-
F
-rV
i 1 1
4-4-*-
, . j.. -
sed-Face G^t-^^ii-^.---^
Nozzles la-^f--.-^^^
-J-j t i- --i-j-- -f tJ4 t t i ~- . 1 ; i *-.*•-- | i-i-*- -i 	 i-i- -r-
^: 5:: ^ ^ -Si 3si -*: itti ^
:gi;l;l^ilgg:i|i
Fm!' :: : fi
li!4.jEEE±SEEEi;EEiEEEEEc 2)
iU_ ttt . r ii iiil lU . ^ i . i_L
:S: J:::!:^:3^:^:^:*::::^::
rrn. Ł IE - -r-4- • -4-h- t ; * • ^ — ._-_ -
|jl!!|l|j|||ji|||Tl[|iii |![|i|l|| ||llj||-
EEE!|EEE Source: Ref: 160, 165, 166 :;:;:;:;;:
4 6 8 10 12 14

J_. Xj.t J ;.l -,. jili 4-4-1 j- -J-T--1- ^j 1 i i-l-i j t |4-
._— ,i_p, 4 Tj. i * . i . , i I J , ! > : i , , 1 ,
i 	 -I- .. J_i 	 ! ! I . iiil ii|.{ 1 . ; ; | , r 	 1_
1-4- - .Ml j . IJ. 4- -4-- -j-i--.t -|-i r!^ -1-4 t j- ; r i ! 1 . ) [
H-- -H--J- : 1 - 1 - J--- j j I 4- 41 -M--J- -4--*- 1 ! i -
For manways and Handholes
50% for cost of blind fla
gaskets, hinges or davit.
For stainless steel
TYPE COST ADJUSTMENT
304 2.0 •
316 2.3
[ 1 1 ' ' ' [1 1 1 1 ' 1 1 1 1 1 1 1 ' 1 H 1 1 1 [ 1 1 | i 1 1 1 ' | • | | • ; *
16 18 20 22 ;
i t i
^rr
.; a. . .,-
TIT
i ri T i
TT4
-tt-
T'PT
1 ' i
, i i i
add
nge
•"'"T
24
H
TT1-'
H
tfr
i , i I-
i I
"TJ+
^.4 J j .
:±r:
/
±±tt
"^5
^-H
•H-1-
*"^"M~
- — H-
±3=r
— "T4"
>6
^rt
id
	 	
—
M
2
INSIDE NOZZLE DIAMETER (INCHES)
Figure 5-23   COST OF NOZZLES
              5-60

-------
     3800
     3400
     3000
     2600
LU
  UJ
I— QC
o: o
os:
o.
     2200
GO

a: CM
o
=3

2
a: co
S<  1800
>- or
er LU
2 a.
LUO
0.0
     1400
     1000
      600
      200
                 FOR  TRAYS  ONLY
                 COST PER TRAY MUST BE MULTIPLIED

                 BY COST ADJUSTMENT FACTOR

                    20
                           COST ADJUSTMENT FACTOR
                                                 304
                                                 TAILLESS
                                                 TRAY
                                  CARBON  STEEL

                                  DISTRIBUTOR
                                                                      CARBON STEEL TRAY
                                                        CARBON STEEL SUPPORT  PLATE
                                                                 FOR STAINLESS STEEL
                                                                 SUPPORT PLATE OR DISTRIBUTOR
                                                             ITEM:           COST FACTOR

                                                             SUPPORT PLATE     1.8

                                                             DISTRIBUTOR       1.3

                                                                      10
                             Source: Ref:'160, 165,  166
                                  4           68           10          12

                                           SHELL DIAMETER (FT)


                        Figure 5-24  COST OF TRAY, SUPPORT PLATE OR DISTRIBUTOR
14
                                                 5-61

-------
skirt should be approximately equal  to the thickness  of the  shell.   Figure 5-23
reflects the fabricated cost of nozzles for typical shell  penetrations such as
those required for the inlet and outlet for the gas and liquid,  relief valve
connections, pumpout alternates, spray inlets,  and manways.
     The cost of internal  tower equipment such  as support  plates, trays, and
distributors is shown in Figure 5-24.   The indicated  prices  apply to both tray
towers and packed towers and represent the installed  cost  per item.   The cost
of trays is based on quantities of 20 or more.   For quantities less  than 20,
the unit tray cost must be multiplied by the cost adjustment.  The cost per
cubic foot of internal packing is shown in Table 5.5.
     The summation of these costs represent the fabricator's shop costs.  Added
to this must be the fabricator's cost of engineering, administration costs,
and profit as determined from Table 5.6.
     As an example, the design calculations for a carbon steel packed tower as
outlined in the illustrative problem of Reference 88  indicate that the tower
diameter should be approximately 2 feet with a tower  height of approximately
15 feet.  The inlet gas flow rate is 520 cfm and the  liquid flow rate is 3 gpm.
The tower packing is to be  1-inch carbon steel  raschig rings and the absorber
is to be operated at ambient conditions of temperature and pressure.
      Under  these  conditions, a  1/4-inch place thickness for the shell may be
selected which would provide adequate  allowance for corrosion.  A suitable
inlet gas velocity  for this absorber would be approximately 1800 fpm which
would require  a gas inlet  and outlet of approximately 8-inch diameter.  A
suitable liquid inlet  and  outlet pipe  for 3 gpm would be approximately one inch.
A manway of 18 to 24 inch  diameter would normally be provided at the top and
bottom  for  larger diameter towers, however, for this small diameter tower, a
                                     5-62

-------
Table 5.4   MINIMUM SHELL THICKNESS AT AMBIENT TEMPERATURE  (CARBON STEEL)
Shell Diameter* (Ft)
Internal Pressure:
Atmospheric
25" WG
50" WG
100" WG
10 PSIG
100 PSIG
200 PSIG
2

1/8"
1/8"
1/8"
1/8"
1/8"
1/8"
1/4"
4

1/8"
1/8"
1/8"
1/8"
1/8"
1/4"
1/2"
6

1/8"
1/8"
3/16"
3/16"
1/4"
3/8"
3/4"
8

1/8"
1/8"
3/16"
1/4"
3/8"
1/2"
1"
10

1/8"
3/16"
1/4"
5/16"
7/16"
3/4"
1-1/4"
12

1/8"
3/16"
1/4"
5/16"
1/2"
3/4"
1-1/2"
*  For corrosion allowance add minimum of 1/8 inch.. Thicknesses  are for
   ambient temperatures and temperatures  up to 600°F.  Thickness correction
   factors for higher temperatures are:  1.04 for 700F; 1.14 for 750F;
   1.35 for 800F  (Ref.  165).
Table 5.5   COST OF TOWER PACKING (Ref. 160, 165, 166)
Type and Material
Pall Rings:
Carbon Steel
304 Stainless
Polypropylene
Intalox Saddles:
Polypropylene
Porcelain
Raschig Rings:
Carbon Steel
Porcelain
1 Inch
($/Ft3)

19
54
14

15
12

17
8
1-1/2 Inch
($/Ft3)

15
43
-

-
-

14
7
2 Inch
($/Ft3)

13
35
8

10
9

9
6
3 Inch
($/Ft3)

-
-
-

5
8

-
-
3-1/2 Inch
($/Ft3)

-
-
-

-
-

-
-
                                    5-63

-------
Table 5.6   ADDITIONAL COSTS FOR FABRICATOR'S ENGINEERING, PURCHASING,
            ADMINISTRATION AND PROFIT (Ref.  160, 166)
Total Cost of Fabricated Vessel
    Less than  $ 5,000
    $ 5,000 to $10,000
    $10,000 to $20,000
    $20,000 to $30,000
    $30,000 to $50,000
    $50,000 to $80,000
    Over $80,000
                                                           Cost Factor
                                                              0.25
                                                              0.23
                                                              0.20
                                                              0.19
                                                              0.18
                                                              0.17
                                                              0.16
                                     5-64

-------
12-inch hand hold can be provided at each end of the tower.   A drain in the
bottom head of the tower should also be provided for draining, flushing and
cleanout.

    Using Figure 5-21 the cost of the basic vessel is $420 for the heads plus
$52 per foot of shell or $1200.  The cost of the skirt, as determined from
Figure 5-22, is $1140.  The installation of nozzles for the various vessel
penetrations results in a cost of $2580 for three liquid nozzles at $120 each,
two gas inlet/outlet nozzles at $330 each, and two hand holes with blind
flanges at $780 each.
    The tower internals would consist of a packing support plate and two
distributors spaced at 5 foot intervals plus the internal  packing material.
The cost of the support plate and distributors, as determined from Figure
5-24, is estimated to be $1220.  The volume of packing required for a 15-foot
tower with a 2-foot diameter is approximately 47 cubic feet  and the estimated
cost of the packing, as determined from Table 5.5, is approximately $800.
The total fabricated cost of the packed tower is therefore $6940.  The
fabricator's sell price including engineering, administration costs, and
profit, but less taxes and freight,  is determined from Table 5.6  to be
$6940 x 1.23 or $8540.

5.7  Refrigeration

     Removal of gaseous contaminants in a process stream can be accomplished
by cooling the gas stream to condense and remove the contaminants.  Refrigera-
tion may be used alone or be combined with other processes for the removal or
recovery of gaseous  pollutants.   For instance, in the removal and recovery
of hydrocarbon vapors from the transfer operations at teminals and bulk plants,
                                    5-65

-------
refrigeration can be used singly to condense the vapors at atmospheric pressure
or it can be used in conjunction with a compressor for condensation and/or
absorption of the vapors at higher pressures and more moderate temperatures.
In absorption systems, refrigeration can be used to condition the solvent by
increasing its gas solubility characteristics at lower temperatures, thus
permitting both the solute and solvent to be the same product but in different
phases, i.e., gas and liquid.

     Vapor recovery systems utilizing refrigeration alone at atmospheric
conditions usually consist of a refrigeration unit, a heat exchanger/evaporator,
storage tanks for the chilled and defrost brines, and a vapor condenser.  For
low temperature applications, the refrigeration unit is normally a compound or
cascade multistage system providing temperatures to as low as -250°F-   In
general, compound systems are used for systems requiring temperatures  to
approximately -100°F and cascade systems are used for temperatures below -100°F.
The recovery of hydrocarbons typically found in the transfer operations of
petroleum products require temperatures of approximately -110°F and cascase
refrigeration systems are normally used.  In the cascade system, shown  in  Figure
 5-25,the condenser of one refrigeration stage acts as the evaporator  for the
 second stage to produce these lower temperatures.   The evaporator for the
 final stage of refrigeration is the heat exchanger/evaporator where a chilled
 brine is circulated and cooled.  A storage tank is provided for the chilled
 brine as a low temperature reservoir of coolant for the vapor condenser.   The
 gas  stream mixture of air and hydrocarbon  vapors enters  the  vapor  condenser
 where the hydrocarbons having boiling  temperatures  above approximately -100°F
 are  condensed and collected at the bottom  of the vapor condenser.   In  the
 condensing process, moisture in the gas stream is  also collected  as frost on
                                      5-66

-------
in
           Air- Cooled
           Condenser
            Compressor
Air
                                                     Reclaim
                                                       Heat
                                         From Refrigeration
                                         Compressors
                                                                                           Vapor/Ai r
                                                                                                 In
                                                                             Air Out
                                                                         Cold
                                                                         Brine
                                                                        Reservoir
                                        Defrost
                                         Brine
                                        Reservoi r
                                                                              Hydrocarbon
                                                                                  Out
                                                                                                               Condensed
                                                                                                               Water
                                                                                                               Vapor
                                                                                       Source:  Edwards Engineering Corp,
                      Figure 5-25   Cascade Refrigeration System for Vapor Recovery

-------
the condensing surface and periodically the condenser must be defrosted.  This
is accomplished by passing a defrost brine through the vapor condenser for a
short time period.  The defrost brine acts as a heat exchange medium by removing
heat from the refrigeration unit and transferring it to the vapor condenser.  A
separate storage tank is used as a warm brine reservoir.   For continuous vapor
recovery, two vapor condensers can be used; one condensing while the second is
defrosting.
     Refrigeration can also be used as an intermediate stage in a combined
process to remove hydrocarbon vapors.  Systems utilizing refrigeration in this
capacity are the Compression-Refrigeration-Condensation systems (CRC) and the
Compression-Refrigeration-Absorption systems (CRA).  In the compression-
frigeration-condensation process, the gas stream containing hydrocarbon vapors
is first passed through a saturator with recovered product to saturate the gas
stream beyond the flamability range.  The saturated gas stream is then passed
through the first stage of a two stage compressor where the gas is compressed.
An intercooler and liquid/gas separator are provided between stages to cool
                                                       s
and condense some of the more volatile vapors before the gas stream is
delivered to the second compressor stage.  The gas leaving the compressor
passes through a condenser where it is cooled to permit subsequent condensa-
tion of the remaining vapors.  This^condensate together with the condensate
from the intercooler are returned to storage tanks or to the saturator as
recovered product.
     In the Compression-Refrigeration-Absorption system, the flow scheme is
essentially the same with the exception of the replacement of the condenser
with an absorber.  The absorber in this process, however, is the primary unit
and the remaining components serve to condition the liquid and vapor entering
the absorber.  The vapor-laden gas is first passed through a saturator to
                                     5-68

-------
 saturate and maintain the gas mixture above the flamability level before  it  is
 delivered to the compressor.  A single stage compressor and aftercooler are  used
 to precondition the gas stream for absorption.  The gas then enters the absorber
 where it is sprayed by liquids chilled in a refrigeration unit.  The absorp-
 tion of the vapors by the liquid is promoted by moderate pressures and lower
 temperatures so that the remaining gases are essentially free of hydrocarbons
 and can be vented to the atmosphere.
      The CRC and CRA systems are proprietary systems which have been custom
 designed and fabricated for specific applications.  These systems are not
 actively marketed at this time.  Systems using only refrigeration can be
 adapted to many applications and the efficiency or vapor recovery capability
 of these systems depends on the vapor pressure and temperature characteristics
 of the pollutants and the gas stream.  Refrigeration systems are particularly
 well suited for applications such as the recovery of hyrdrocarbon vapors from
 gasoline marketing operations.  These systems are sold as packaged units con-
 taining all the piping, controls, and components and are usually provided
 skid-mounted with an appropriate weather enclosure.   The auxiliary equipment
 required to provide a complete vapor collection and recovery system might con-
 sist of a gas holder, liquid storage tanks, pumps, and piping between the
 pollutant source and the storage tanks.   The size and subsequently the cost
 of a vapor recovery unit will depend on  the operational schedule,  process
 flow rate, level of hydrocarbon emissions and the gas and liquid storage  capac-
 ities.
     The costs of refrigeration vapor recovery systems are shown in Figure
5-26.  The cost of the unit includes a complete skid mounted package containing
the refrigeration unit, brine storage, two condensing units, and pumps, valves
                                      5-69

-------
   o
   o
   •*>«>•
    
   s-
   o
   Q.
   (T3
   O

   '43
   (O

   O)
              250
             200
             150
100
              50
:i Re
;; Ou
:: IIHtllJ
i;:;;:
-Note
i 1}
i 2)
1 3)
|;:; 1
UttlM
imtJIl
trfttilm
!ill!!U!![l!
iliiii
illii
i^iiill i
• •••Hill *Ml
iiiiiiiliH-ii
Kmmm'itm «••
,.:;s:!:: :32
ts»:::!uiM
iiiiiMi!
lili
•:=;:;i:(imi
•••••••••••ill
•••••••••••Sin
friqeration Vapor Recovery Systems with - • •••••
tlet Condenser Temperatures to -110°F ;:; ;:; ;j
^HUfHHUItHrilltit-HiHIIIIIIIIIItlltlllllllltlllllllllltritUtt tt t
illlllllllliitltll'MllllilllllllllllllllllllFlllltillilllllllilllf l'rf 1 1
TBiiilSiii
i:. I T :
Normal power requirements include ^mffl|fm^li[||{ffl
brine pumps, compressor, condenser jMrnmlmffllBiflHlffl]
fan, controls & instrumentation. igm»||Mwff
For explosion proof units, multiply \ I ^ (,\(
by 1.2. •;;;;;:{* * ^.
' } f O-*.^t i '
Source: Edwards Engineering Corp. IfflifflPrlfffft iirfflfifflffffl
1 Lt 	 1 	 j '' 	 1
flffl||pt{{ti|i jj[p[j|ffijM^
•wimWtiliitH
illii llgiiiyillp:liilH^liligiiypHB|
w mmmt i 1
iiiiii !!!!! H Jilii i! jiilil!! II !
iilliiili JJiii ill ill! !,!0
!ii! II P ! !!H!ii H!ii!!0ilili!!!l!!!!!!!!! iilHHi! ! (ii
! piiii !!Hii!i!!iiiiHi!ii! 111!!
SI iii III
:•::..•::.:::: ': :. , . :. . . 1.;
; :: 	 	 ; 	 ..:.:: *i|ui.
•^•iilP^ Wifiiffll Hi
	 ii 	 r:;pT J;N^:'':: 	 t
• - ^ ?^^iij ;;; - i *t
»ppr L ^^siii|ii ttpiy
I; r^^t\\'' :! :;:::;;: - - i It
^'S&il Nil! MiiMiii ::: :ift|
^g^^^M|fi|M||!ii|;'!:|
WSiffi^Biiip{i^l Ą"
:•; :;: . Ill i» :: :• •-: ;;. It H it t-i vn :f
r-i viiii ' +- t- - 	 •- :f fffi ^T- }f T -ip tm
: : :i :1 : ; : i Ifflti *L = Jii
IfiBBBiiBli11 iiiPiji|
^^^^^BHwwii
MlPliliilllliPfiil1'!^^
m^ ISiffilii^^
!»(i!!::ijsj HnHninn i» inuig : ny m n m tmmai
i*2-«Jii«IiiM» ••• ••••••Iii* i • i ii •! * • t HI IHH*H
ssju:»!!ius. u: sscutn uiJut ir i u in{B
liiijipjyq iii'iiljliljnin il!| IJIP ifflHIUffiffi
••••i«3iiii* ••• ••• MB ii •••**•••! •!• 1 U EfUHBHIHM
:::!:!}[:«:• iinii- ijiii i|"ii!:::::«:ia jiimjj [fiilSJBiD
: ::: i:i:::i:::n: ;;;:! n!HI!"!»::!:!!» !li!l» !« ! < I!-HI
i::n i!ii!li:i:!:i !l:i: !!:!'!h!i::i:::i:Ji 1 Hiiiii lit hlUH!
i!|:; iiHUSiHiii ii:;:iijiiij:j;:;;;;;;i;;;::j iiijilHliigi i S iHiii
iii:: ::::;::::;::::;i:i:::::::;:::::n:::::;t:::i::::::;ii:{:::: r: : ::ii
•••••••••••••••• ••••••••••••••••••••«••••••**(••••»••**• •••Jiiiiitf>»i »•••
!••••• •••••••••••»•«•••••••••••••••••••••••••• ••••••« fiiiii*i*i st til*! •••
••«•!••• ••••••••ii|f •••••••••••••••••••• •••••••••« illl9|li*i|ii! 11111 •••
ipfMll Illii ••••••••••••••••••t •••»•• •••••••••• •••••If •••••••••••I iiiil •••
                                                                                                                          300
                                                                                                              200
                                                                                                                            100
                                                                                                                            0
                             100          200          300


                     Figure 5-26 Refrigeration Vapor Recovery  Units
                                                       400          500          600

                                                              Flow Rate (CFM)
700
800
                                                                                                                     (U

                                                                                                                     O
                                                                                                                    z

                                                                                                                     (U

                                                                                                                    to
                                                                                                                    to
                                                                                                                    -M
                                                                                                                                  CL>
                                                                                                                    O)

                                                                                                                    I
                                                                                                                    DL
                                                                                                                    (O

                                                                                                                    S-
                                                                                                                    o

-------
 and  controls.  These units are priced according to the continuous gas  flow
 rate in cfm which  is processed.   In transfer operations, this represents  the
 displaced volume of gas corresponding to the maximum continuous flow rate of
 product pumped; or, in terms of cfm, one cfm is equal to 7.48 gpm.  The
 condensing temperature for these  units is approximately -100 to -110 F which
 is sufficient to condense most of the heavier hydrocarbons.
      For gasoline  vapor recovery, the units have the capacity of recovering
 a minimum of 90% of the hydrocarbon vapor when the vapor entering the condenser
 consists of 35% gasoline hydrocarbon by volume; and of recovering 70% of the
 hydrocarbon vapor  when the vapor  entering the condenser consists of 15% gasoline
 hydrocarbon by volume.  At all feed conditions the partial pressure of the
 hydrocarbons in the vapor leaving the vapor recovery units is approximately
 0.38psia.  The recovery rate of other hydrocarbons, such as benzene or toluene,
 will  depend on the partial pressure of the hydrocarbons in the feed stream and
the corresponding  vapor pressure  of the  hydrocarbons  at the outlet   temperature
of approximately  -HOOF

      The pressure  drop through the vapor condensers ranges from approximately
 1 inch W.G. when the condenser is free of frost to 4 inches W.6. when the
 condenser is ready for defrosting.  The estimated normal  power consumption for
 the  units excluding fan/blower power costs for the gas stream and pump power
 requirements, if any, for the recovered product, is also  shown in Figure 5-26.
 The  average service and maintenance costs for these units are estimated to be
 approximately $150 per month based on  an optional  oreventative maintenance ser-
 vice provided by  the manufacturers.  The cost of this  service  is  the same  for
all  units.
                                     5-71

-------
     The costs shown in figure 5-26 are specifically for refrigeration vapor
recovery units used to recover hydrocarbons  from gas streams.   These systems
include vapor condensers,  defrost equipment, and other ancillary components re-
quired for these applications.  The cost of  industrial vapor compression refrig-
eration systems used for cooling other products  are shown in figure 5-27.   These
costs represent the complete system fully installed including the compressor,
condenser, evaporator, controls, foundations and all auxiliaries except the
piping runs for product or cooling lines. These systems are rated in tons of
refrigeration (12,000 Btu  per hour per ton of refrigeration) at various evapor-
ator temperatures.  As the evaporator temperature is lowered, the capacity of
a given refrigeration unit decreases.  In air cooling systems similar to the
solven recovery units shown in figure 5-25,  the  approximate relationship be-
tween gas flow rate and tons of refrigeration is given by
     Tons refrigeration =  4.5 Q   U.24 +  0.45 W) AT + 1076AVJ]
                                    12,000
         where Q = gas flow rate, SCFM
               W = humidity ratio, Ib water/1 b dry air ^
              AT = inlet air temperature minus evaporator
                   temperature, °F

  5.8 Flares
       Flares are used predominantly  in refineries  and in  the  petrochemical
  industry to burn waste gases which  normally are not economically  recoverable.
  In many cases  flares are used in the  event of  a process  upset or  some  other
  emergency condition where excess gases  and vapors  must be  vented  immediately.
  Under these circumstances, flares are normally used intermittently  with  pos-
  sible long  periods  of disuse.
                                     5-72

-------
   10,000,000,
 (A
 O
O
 c
•^*
 Q.
«^-
0.

•p
 O
 3
•o
 O

D.
c
•I—
a.

a.
O
O
O

W)
I/)
0)
o
O

TJ
OJ
10
•p
(O
-P
O
    1,000,000,0 :±tiia
      100,000,
       10,000,
                                                                           3   4  t,  6  7 « 9 10
                                         Tons of Refrigeration

                Figure 5-27   Installed Cost of Industrial  Vapor Compression
                                  Refrigeration Systems
                                                5-73

-------
     Flares are generally categorized  as  either ground or elevated flares.
By elevating the flare, the open flare can be  removed from potentially dangerous
ground areas and the products of combustion can be dispersed above the working
areas to reduce the effects of noise,  smoke, and objectionable odors.  As in all
combustion processes, an adequate air  supply and good mixing are required to
produce complete combustion and minimum smoke.  In the design of flares, this
is accomplished by injecting steam or  water into the combustion zone to produce
turbulence for mixing and to induce air into the flame.  Other techniques are
employed which rely on a blower assisted air supply instead of steam, however,
these are used to a lesser degree than the steam assisted flares.  The flaring
process, by itself, produces some undesirable  products and emissions such as
noise, light, smoke, SO , NO , and CO, however, by proper design these can be
                       X    A
minimized.  Shields and mufflers are sometimes provided to limit light and noise
and by proportioning the steam flow rate to the gas flow, smoke can be reduced
to invisible levels.
     The elements of an elevated flare generally consist of the stack, burner,
seal, pilot, ignition system and controls.  Many different configurations are
available and the differences between  each are due primarily to the method and
location of the air or steam injection and the design of the burner.  Included
in the stack of most flares is a flare seal to prevent air entering the stack
due to wind or the thermal contraction of stack gases, and to reduce the amount
of purge gas that may be needed to expel combustibles when the flared gas is
lighter than air.  Water seals may also be used as a seal and as a means of
directing the gas flow to alternate flares.  In addition, a knock-out drum is
provided as a separator for any liquid that may be entrained in the gas stream.
The knock-out drum and water seal are usually incorporated into the same vessel,
Elevated flares can be free standing, guyed, or structurally supported by a
                                     5-74

-------
 derrick.   Free  standing flares provide  ideal  structural  support.   However,  for
 very  high  units the costs increase rapidly and the foundation  and  nature  of
 the soil must be considered in both the static/dynamic and cost analysis.
 Derrick supported flares can be built as high as required since the system
 load  is spread  over the legs of the derrick.  This design provides for differ-
 ential expansion between the stack, piping and derrick.  The guy supported
 flare is the simplest of all the support methods.  However, a  considerable
 amount of  land  is required since the guy wires are widely spread apart.   In
 addition the waste gases must be near ambient temperature since any expansion
 or contraction due to temperature differences will  change the  tension in the
 guy wires  and cause structural damage.
     Some  flares are provided with auxiliary fuel to oxidize hydrocarbon vapors
 when the gas stream falls below the flammability range or can  no longer sustain
 a flame.   Control of the auxiliary fuel  is automatic, and this type of system
 is ideal for processes with large fluctuations of hydrocarbon gas compositions.
     Ground flares are used to dispose of waste liquids and gases.   These flares
may contain several  nozzles or burners and combustion can occur inside a
 refractory chamber or in an open pit.   Ground flares  and elevated flares can
 be used together in  an integrated system whereby excess waste gases can be
diverted from ground flares to an elevated flare.
     Elevated flare  diameters  are normally sized to provide vapor velocities
at maximum throughput of about 20 percent of the sonic velocity in  the gas.
The maximum pressure drop for a flare  is limited to approximately 2 psig
 (60 inches WG).   The height of a flare is based on  the ground level limitations
of luminosity, thermal  radiation, noise, height of  surrounding structures and
the dispersion of the exhaust  gases.   A  discussion  of these items  can  be found
                                    5-75

-------
in References 88 and 138.   Self supporting flares should be used for flare
tower heights of up to 50  feet, guyed towers to 100 feet, and derrick towers
above 100 feet.   The operating costs for a flare will  depend on the quantity
of purge gas and steam required and a discussion of these requirements is
given in Reference 138.  For general consideration, the quantity of steam
required can be  assumed to be 0.4 pounds of steam per pound of hydrocarbon.
For specific applications, Reference 138 should be consulted.  The use of
steam as a smoke suppressant for elevated flares can represent 92 to 98 percent
of the operating  costs.
     The capital cost of flares depends on the degree of sophistication desired
and the amount of appurtenances selected such as knock-out drums, seals,
controls, ladders, platform, etc.  The basic structure and support of the flare,
the size and height, the flow rate, and the auxiliary equipment are controlling
factors in the cost of the flare.  The capital investment will also depend on
the availability of utilities such as steam and natural gas, the variations in
the composition of the waste gases, and the frequency of flaring.  Typical
costs for elevated flares  range between $30,000 and $100,000 (Ref. 138).
Ground flares can be as much as ten times the cost of an elevated flare for the
same capacity range.  Blower assisted flares (force'd draft flares) are between
two to three times the cost of an equivalent conventional elevated flare
(Ref. 138).
     Figure 5-28 shows typical costs of elevated flares (self-supporting,
guyed, and derrick) versus gas flow rates.  The gases are assumed to have an
average molecular weight of 42.  For comparison purposes, a 12-inch diameter
flare (Figure 5-28) would be designed for an approximate gas flow of 70,000
Ibs/hr, an 18-inch diameter for 200,000 Ibs/hr, and a 30-inch diameter for
600,000 Ibs/hr.   The cost of ground level flares in shown in Figure 5-29.
                                      5-76

-------
o

O
QŁ
«t
UU
_J
LU

U_
to
O
u
      200
      180
      160
      140
      120
      100
       80
       60
       40
       20
''Nfir*
[i in miii c
• H Ł • " 	 + 	
PI :g:|:l
:;;li||i|:g
•:i;:: *i:S
E1"1 t'i :Ł• rJT *fr
Ei GUYED
::f (100' H
Ft f::Pr^T=p
:±: |i::::;5±:ip
" • J 	 t ""
DERRICK '^*|=S|| =
200' HIGH) g;-:|i5S^it
l||;|!i!|!!i!:;;=!!;|s|S|ll
E§iSg: Note:
EijJtTil:; 1) Cost incl
:|iirMitfcy and steam-
g| idj. si tjfi Łr t-fj: g ^ ±H| ^
gi^|iii|sis
r= rttt r= ^fa
Lides knoc
lot and i
-control
loyed for
if. 170
... . -f-f-- . f.. L •f-r-j-j-

-p^f
ko
gn
in:
sr
M:II
"T17
t,«.
F-S
(4
»»*
t"
jt
iti
»tr
nok
f^
UP
D1
•**
— 1
ttit
' ; i ' >
dr
on
um
el«
POF
HI

t-* *4
t— *•»-
4*t-« •-
-j«-*-
um<
cc
2n1
2SS
i&T
3aŁ
m
GH

; w
>nt
;at
0
^
^
• -4
-^TT
N«
'
" i ^"
jjn. 4 ^
1?:::
ith
rol.
ion
perc
~-
TfTT ~T
it; 'H'
•H-ft- -*•
u.-i...
•**• -M-J--J
itl 01
^
4— ~— .-.
^.I3T
ff T44*

1.
rrtf
-^-t—
TTT
=
•••-f
=c
                   100.       200
                          GAS FLOW,
  300       400      500        600
1000 LBS/HR 0 MOL. WT. OF 42
                          Figure 5-28   COST OF ELEVATED  FLARES
                                         5-77

-------
    400
    360
    320
    280
o
o
o
GO
LLJ
OL
O
cr:
CD
1/5
O
O
    240
    200
    160
    120
     80
     40




• 't f "t ""r"1
•- •-*-** . 1 j J- .«^-i-




irri-
ctr

L... t-M
tŁ
!K
III
^
t—
rrr
~lii
Trf

ite
Irr:
tH*

r
Ktt
--M-f
fr
+»*-f-
-fit
,4h!
Si
pmi
-— T/rfe-1^-^-1
rr?rrtT;±r' nrr z::: —
*TT" t*^T ' "*T' Tr^" T7
Note :
1) Cost i
with s
contrc
centre
enclos
2) Source

i. ^_ri jit^. ilii iUi. . . .4- *— 	 ~ * «-**
*T ITT 7 'i ' ' 1 1 	 IT * I M" 7*"T ^7 i '' ' Tf" tTtT
fii4tl%iSH
-.— »T ^^1 JUl ^1-4.— i iiL-4-l-,-. . J.
±^H---:|^H?i:— rti*jt-»:aa
ncludes knockout dn
eals, pilot and igm
1 instrumentation, s
1 instrumentation, a
ure for protection.
: Ref. 170

1
m
tion
taged-
nd

                 20        40        60       80        100

                         GAS FLOW 1000 LBS/HR. 9 MOL. WT.  42

                      Figure 2-29   COST OF GROUND LEVEL  FLARES
120
                                      5-78

-------
                               Section 6
           SAMPLE COST ESTIMATES AND SYSTEM COST COMPARISON
     To illustrate use of the manual, a case study on rotary kiln air
pollution control is presented here.  Since this manual provides very little
guidance regarding the design of air pollution control systems, it is essen-
tial that the user have prepared in advance an engineering design for
control of the pollutant source.  Care should be taken in the design because
a poor design is likely to result in unrealistic costs.  There may be many
system configurations that will satisfy the technical requirements, but only
one or two will cost the least.  In the example presented here, the engineer-
ing design is intended to demonstrate the use of the manual  and is simplified
in the interest of clarity and brevity.   Hence the design may not be optimal.
The reader should however, concentrate on understanding how the manual  is
used.  Engineering design techniques may be found in EPA Pub.  AP-40,  Air
Pollution Engineering Manual,  (see Appendix C, No.  88).
     Lime (CaO or CaO-MgO) is the product of the calcination of limestone
(CaCOg or CaCOg-MgCO.,).   Lime manufacturing involves several sources  of
pollutants.   The sources  include:
     a)  Quarrying - stripping, drilling,  blasting,  loading, and hauling.
     b)  Stone processing -  crushing,  pulverizing,  screening,  and  conveying.
     c)  Limestone calcining (kilns)
     d)  Lime hydration,  drying,  and bagging.
     e)  Fugitive dust,  roads, stockpiles,  transportation,  etc.
     This  section is  concerned solely  with  rotary lime kiln  operations.   Kilns
are basically of two types:   vertical  and  rotary.   Rotary kilns  are  used by
the majority (80-90%) of  lime plants and  they  represent the  largest  single
                                   6-1

-------
source of pollutants  in the  lime  industry.   The pollutants  are predominately
particulate matter.   Broadly speaking,  about 30% of the dust from rotary
kilns  is  less than 10y and the mean size is 30y.  The exhaust temperature
from rotary kilns depends on the  length of the kiln and other process variables
Lime kiln exhaust gas is usually  cleaned with venturi scrubbers or fabric
filters,  although electrostatic precipitators may also be used.  This case
study will show cost estimation for all three methods.  The following condi-
tions  are assumed:
     o  A typical 250 TPD rotary  kiln to be controlled at 1000 ft elevation.
     o  Required control efficiency of 99+%.
     o  Exhaust gas from kiln:  30,000 SCFM or 88,300 ACFM @ HOOF. *
     o  Control device to be located 200' from source.
     o  Direct exhaust from kiln.
     o  Duct velocity - 4000 fpm to prevent fallout
     o  Surrounding terrain does  not impose unusual constraints on system
        design and stack height (50').
CASE A - OUTLINE OF ENGINEERING CALCULATIONS FOR FABRIC FILTER
     Establish overall engineering design as follows:
         a.  Use polyester (275F) or glass bags (550F).
         b.  A/C ratio = 2 for glass bags.
                       = 3 for polyester bags.
         c.  Suction baghouse:
                       - reverse air,  insulated for glass bags
                       - mechanical shaker, insulated for polyester bags
         d.  Radiant coolers next to source.
         e.  Mechanical cyclone just prior to baghouse
         f.  Dilution air port provided for temperature modulation.
         g.  By-pass damper omitted.
   Composition:  N2-60%, C02-24%, H20-15%, 02-1%  (by volume),

                                      6-2

-------
     Figure 6-1 shows the system layout for a fabric filter operation.   The
following discussion outlines how the design parameters  are obtained for each
stage along the system.
Stage 1:      Direct exhaust from kiln, determine carbon  steel  elbow duct size:
                        88300 ACFM =  ?? ,  F 2
                         4000 fpm
             Hence, 64" duct (22.3 ft )  may be used, giving:
                        88300 AC™ •  3960  fpm
                         22.3 ft*
Stage 2:
a.  Assume no temperature  drop  from kiln  outlet  to  inlet  of
    radiant cooler.   Estimate that  about  600  F temperature  is
    required out of  the cooler.   Try initial  5000 fpm  through  two
    18" U tubes  in series.   Thus:
           88300 ACFM
             1.767 ft /tube  X  5000  fpm
                                           10 pairs of tubes in parallel
                 From engineering  calculations  for 40' high tubes, the
                 temperature  drop  for two tubes in series is 500F.  Thus
                 exit temperature  is 600F and gas volume is 60000 ACFM.
                 Pressure  drop is  2.1" W.G.  Estimated length of cooler
                 is  30 feet based  on tube spacing of 18" (see sketch).
                                                 -^•10 pairs of 2 tubes
                                   ^>    (r^^f      (units) each
                                      (cfc^
                                                         18" tube spacing
  Heat transfer calculation methods may be found in the  EPA publication  AP-40.
  See Appendix C, reference 88.
                                     6-3

-------
                                                                     Sc.rew conveyor
DESIGN PARAMETERS
SCFM
TEMPERATURE
ACFM
DUCT DIAMETER
STATIC PRES. (" WG)
1
30,000
1100 F
88,300
64"
Kiln
Draft
2
30,000
600 F
60,000
j
52"
-2.1"
3
30,000
530 F
56,000
52"
-2.7"
4
30,000
500 F
54,300
52"
-8.7"
5
38,600b
100 Fb
40,800b
52"
-
6
30,000^
68,600b
500 Fj
275 FD
54,300*
95,100b
Neglect
-
7
30,000*
68,600b
500 F?
275 Fb
54,300*
95,100b
Neglect
-14.7"
a - glass bag
b - polyester bag
                       Figure 6-1  FABRIC FILTER SYSTEM DESIGN

-------
                 From Chapter 3 of ref. 88, the quantity of heat removed from
                 the cooler is determined by:   Q = w( Ah) where w is in Ibs/hr
                 or scfh and  Ah is in Btu/lb  or Btu/scf.  The overall  heat
                transfer coefficient  (U)  is determined by  calculating the inside
                 and  outside  film  coefficients for  an 18-inch  diameter  tube with
                 a  velocity of 5000 fpm.  The log mean temperatures difference
                 (  Tm) is calculated  using an assumed ambient  temperature  of
                 100°F and an  inlet temperature of  1100°F and  an outlet temperature
                 of 600 F.  The total surface area  required is then determined
                 by:   A  = Q/U( ATm).   Since there  are 10 pairs of  tubes (units)
                 in parallel, the  developed length of each will  be:
                 L  =  A/10 ir  D where  D is the diameter  (1.5 ft).   The height
                 of the  cooler is  calculated by  dividing the  developed  length
                 L  of each  pair  by the number of vertical  columns  in each pair.
                 For  pressure drop calculations, also see  Chapter  2 of  Ref. 88.
             b.   Determine carbon  steel  duct diameter
                         60000 ACFM
                          4000  fpm
                                     =   ,,
                                        I0
                                        2
                 Hence  52"  duct  (14.7  ft ) may be used, giving:
                         60000 AC™  . 4080 fpm
                          14.7 fr
Stage 3.      Cooling of gas will  take  place over 200-30 = 170 ft. of duct.
             The calculations used in  stage 2 to determine the size of the
             U-tube cooler  are applied again.  The surface area of a 52"
             duct,  170  ft long is calculated to be 2314 sq. ft.  The overall
             heat transfer  coefficient is determined using a velocity of
             4080 fpm and a duct  diameter of 52".  An outlet temperature at
                                    6-5

-------
             the end of the duct must first be assumed to determine the log
             mean temperature difference.   If the calculated and assumed
             temperatures differ significantly, the procedures must be
             reiterated until both temperatures are approximately the same.
             For gas temperatures about 600°F and a velocity of 4000 fpm,  a
             temperature drop of 0.4 degrees per ft. is a reasonable
             assumption.  Using the overall heat transfer coefficient,
             assumed log mean temperature difference, and the surface area,
             the total heat transferred can be calculated.  The outlet
             temperature is determined from the change in enthalpy of the
             gas stream.   In  this  case, the outlet temperature is found
             to be 530 F.  This is reasonably close to the assumed temperature.
             The pressure drop through 170' of duct can be determined from
             the friction charts in chapter 2 of reference 88, corrected for
             the difference in density.  The pressure drop is found to be
             approximately 0.6" W.G.  The new ACFM at the end of the duct  is:
                                                     S
                         60000 ACFM X -r-    =  56000 ACFM
                                      I UOU K
             Expansion joints are usually provided between major components
             such as coolers, mechanical  collectors,  etc.; therefore,  two
             expansion joints are required,  one 52",  the other 64".
Stage 4.     Select two mechanical collectors in parallel to handle  28000
                                                                       2
             ACFM each.  For 6" pressure loss, the inlet area is 8.5 ft  and
             the critical parti cal size is 24 microns.  Mechanical collectors
             also provide some degree of cooling.  Manufacturers usually
             supply the expected heat losses for specific applications.  For
             gas temperatures at 500 F, a temperature drop of approximately
                                     6-6

-------
             30 F can be assumed.  Thus, the new gas volume after the
             mechanical collectors is:
                         56000 ACFM X    --  =  54,300 ACFM
Stage 5.     Dilution air port is provided for baghouse for modulation of gas
             temperature.  For glass bags, no dilution air will generally be
             required.  For polyester bags, dilution air is estimated as
             follows (neglecting the difference in heat capacities):
             (30,000 SCFM)(500F) + D (100F) = (30000+D)(275F)
                                         D  =  38,600 SCFM
Stage 6.     Hence total gas volume is 68,600 SCFM or 95,100 ACFM @ 275F for
             polyester bags, and is 54,300 ACFM @ 500F for glass bags.
             The baghouse is sized as follows:
             a.  For glass bags:
                                  =  27150 ft2 net cloth area.
             b.  For polyester bags:

                                  =  3170° f*2 net cloth area
             Baghouses are nominally sized for 6"  W.G.  Neglect  temperature
             drop through the baghouse.
Stage 7.     Total  pressure drop across  system is:
                 Radiant cooler            2.1"  W.G.
                 Ductwork                   .6
                 Mechanical  collector      6.0"
                 Baghouse                  6.0"
                                          14.7"  W.G.
                                     6-7

-------
             Size  fans  for  54,300 ACFM and  95,100 ACFM  for  glass and  polyester
             bags  respectively.  Assuming a stack height  requirement  of  50'
             and a cesign exit  stack  velocity  of 4000 fpm,  select  stack
             diameters  of 50" and 66" respectively.  Dust storage  is  also
             assumed to be  at or near the collection site so  that  50'  of 9"
             screw conveyor is  adequate  for dust removal.
COST ESTIMATE OF FABRIC FILTER  SYSTEM
     a.   (1)    64" carbon steel  elbow,  1/4" thick  (Figure 4-10)  -  $ 2,200
     b.   (20)  units of 18" carbon  steel  radiant cooler 40' high
         (Figure 4-24)  -                                          71,000
     c.   (170) feet of 52"  carbon steel  duct 3/16"  thick
         (Figure 4-7) -                                           11,900
     d.   (2)    carbon steel, 10 Ga.,  mechanical collectors  with
         inlet area = 8.5  ft2   -                                  19,240
                  Collector  (Figure  4-17)      $  4,360
                  Support   (Figure  4-19)           2,960
                  3/16" Hopper   (Figure 4-20)        86o
                  Scroll  (Figure 4-21)            1,500
                                 Total  Each   $  9,620
     e.   (1)    3/16" transition to  mechanical  collector
         (Figure 4-10) -                                              800
         (2)    expansion joints, one 52" one 64"  (Figure  4-12)  -    7,300
                                                    Sub-Total    $112,440
     (Filter with glass bags)
     f.   (1)    52" carbon steel dilution air port,  3/16"  thick
         (Figure 4-25) -                                         $  6,200
                                     6-8

-------
g.  (1) 27,150 ft  net cloth area, continuous, reverse
    air, insulated baghouse (Figure5-13)  -                     162,000
h.  Suction add-on (Figure 5-13)  -                              10,000
i.  (1 set) 27J50 X 1.17 = 31,765 sq ft  gross area
    glass bags (Table 5.1) -                                    14,300
j.  (1) 54,300 ACFM backwardly curved Class  IV fan at
    14.7" U.G. actual (29" standard)  (Figure 4-33) -              7,000
k.  (1) 1,800 RPM, 180 HP drip proof  motor
    (Figure 4-34) -                                              3,000
1.  (1) Magnetic starter with  circuit breaker
    (Figure 4-34) -                                              1,800
m.  (1) 50" diameter, 50' high stack, 1/4" thick
    (Figure 4-41) -                                              5,200
n.  (50) feet of 9" screw conveyor (Figure 4-26)                  3,900
                                       Sub-Total              $213,400
(Filter with polyester bags)
f.  (1) 66" carbon steel dilution air port,  1/4"  thick
    (Figure 4-25) -                                           $   8,600
                 2
g.  (1) 31,700 ft  net cloth area, continuous,
    mechanical shaker baghouse (Figure 5-12)  -                116,000
h.  Suction add-on (Figure 5-12)  -                            $  10,000
i.  Insulation add-on (Figure  5-12) -                           58,000
j.  (1) set 31,700 X 1.17 = 37,089 sq ft  gross
    area Dacron bags (Table 5.1)  -                              12,980
k.  (1) 95,100 ACFM backwardly curved Class  IV fan
    at 14.7" WG actual  (29" standard)  (Figure  4-33) -            10,000
                                6-9

-------
     1.   (1)  1,800  RPM,  300  HP,  drip-proof motor  (Figure 4-34)  -      4,800
     m.   (1)  magnetic starter with  circuit breaker
         (Figure 4-34)  -                                             3,000
     n.   (1)  66" diameter, 50'  high stack, 1/4" thick
         (Figure 4-41)  -                                             6,400
     o.   (50) feet  of 9" screw  conveyor (Figure 4-26)  -               3,900
                                          Sub-Total                 $233,680
     Total  capital  and annualized costs  for the fabric filter system are
summarized below; see Section 3 for installation,  maintenance and operating
cost factors with no cost adjustment.
                              CAPITAL COSTS
             Item                          Glass bags      Polyester bags
Auxiliary equipment and control device      $325,840        $346,120
Instruments and Control (10%)                 32,580          34,610
Taxes and freight (8%)                        26,070          27,690
       Purchased Equipment Cost             $384,490        $408,420
Direct and indirect installation costs
   (117% of equipment costs)                 449,850         477,850
   Total Installed Cost                     $834,340        $$886,270
                                     6-10

-------
                            ANNUALIZED COSTS
                      (8000 hrs/yr. or 1000 shifts)
               Item                           Glass bags      Polyester bags
Operating labor (2 hr/shift)                  $18,100          $18,100
General maintenance (1 hr/shift Smat'l.)       34,640           34,640
Replacement bags (life 1.5; 2 years)            9,530            6,490
  labor for replacement bags                    9,530            6,490
Electricity (1.08 M - 1.79 M kwh)              46,660           77,330
Overhead                                       28,340           28,340
Property tax, insurance, and administration
  Ł 4%                                         33,370           35,450
Capital charges @ 0.11746 @ 10%, 20 yrs.       98,000          104,100
Credits - assume negligible credit for         	          	
  recovered product
                   Total Annualized Costs    $287,170          $310,940
CASE B - OUTLINE OF ENGINEERING CALCULATIONS FOR ELECTROSTATIC PRECIPITATOR
     Establish overall engineering design as follows:
         a.  Drift velocity - .21  fps.  (average)
         b.  Insulated precipitator
         c.  Inlet gas temperature of 700F for good resistivity
         d.  Spray chamber next to source
     Figure 6-r2 shows the system layout for an electrostatic precipitator
     operation.  The following discussion outlines  how the design para-
     meters are obtained for each  stage along the system.
Stage 1.     Same as for Case A, Fabric Filter.
                                     6-11

-------
                                   Spray
                                   chamber
                                           \/
                                                                                    Screw conveyer
l\3
DESIGN PARAMETER
SCFM
TEMPERATURE
ACFM
DUCT DIAMETER
STATIC PRES. (" WG)
1
30,000
1100 F
88,300
64"
Kiln
Draft
2
32,770
800 F
77,900
60"

3
32,770
690 F
71,100
60"
-1.0"
4
32,700
690 F
71,100
Neglect
-1.5"
                                Figure 6-2  ELECTROSTATIC PRECIPITATOR SYSTEM DESIGN

-------
Stage 2.     For preliminary design purposes, assume spray cooling to 800 F
             with water at 60 F.  The water requirements are determined by
             the change in enthalpy of the gas stream from 1100 F to 800 F
             divided by the sensible heat gain and latent heat of evaporation
             per Ib of water from 60 F to 800 F.  The total water requirement
             is 129 Ibs per min or 15 gpm based on an assumed total  pressure
             of 280 ft including 230 ft for spray nozzles.   The added gas
             volume of 129 Ibs per min of water vapor is 2770 scfm.   The
             length of the spray cooler is assumed to be 35 ft.  The gas
             volume after the cooler will be:
                         32770 SCFM X    p   =  77900 ACFM
                     Calculate duct diameter:
                         77900 ACFM  _  ,Q  , f.2
                         "4000       "  19'5 ft
             Hence 60" duct (19.6 ft2) may  be  used.
Stage 3.      a.   Cooling through the duct is determined again  by the  method
             shown in chapter 3 of ref.  88.  The length of the duct is
             200 ft - 35 ft for the spray cooler or  165 ft.  The final
             temperature is 690 F at the end of the  duct and the new  gas
             volume at the preci pita tor  is:
                         77900 ACFM X 4i|2-4  =  71100 ACFM
                                      I &OU  K
             Two expansion joints will  be needed as  for baghouses.  The
             pressure drop is assumed to be  0.6" WG  for the duct and  0.4" WG
             for the spray chamber.
             b.   Size preci pi tator as follows:
                 A  =  -71,100 ACFM ln(l-.993)/(0.21 fps  x 60  s/min)
                 A  =  28,000 ft2
                                   6-13

-------
Stage 4.      Total  pressure  drop  across  system is:
                 Spray  chamber and duct  -  1.0" W.G.
                 Precipitator -            .5" W.G.
                             Total        1.5" W.G.
             Size fan for 71,100  ACFM.   Select a  50'  high  stack  57"  diameter
             Fifty feet of screw  conveyor  9"  in diameter will  be required.

COST ESTIMATE OF ELECTROSTATIC PRECIPITATOR SYSTEM
     a.  (1) 64" carbon steel elbow, 1/4"  thick
         (Figure 4-10)  -                                           $  2,200
     b.  (1) spray chamber @ 88,300 ACFM (Figure  4-22)  -             62,500
     c.  (165) feet of 60" carbon steel  duct 3/16" thick
         (Figure 4-7 )  -                                             13>500
     d.  (2) expansion joints, one 60" and one 64"
         (Figure 4-12)  -                                              7,800
     e.  (1) 28,000 ft2 precipitator, insulated
         (Figure 5-2 )  -                             s             300,000
     f.  (1) 71,100 ACFM backwardly curved Class  I fan
         at 1.5" W.G. actual (3.4" standard) (Figure 4-33) -          9,000
     g.  (1) 600 RPM, 50 BHP drip-proof motor (Figure 4-34) -         3,000
     h.  (1) magnetic starter with circuit breaker
         (Figure 4-34) -                                                500
     i.  (1) 57" diameter, 50' high stack, 1/4" thick
         (Figure 4-41) -                                              5,400
     j.  (50) feet of 9" screw conveyor (Figure 4-26) -               3,900
                                         Total                     $407,800
                                     6-14

-------
     The capital and annual!zed costs for the electrostatic precipitator
system are summarized as follows.
                              CAPITAL COSTS
             Item                                                 Cost
Auxiliary equipment and control device                          $407,800
Instruments and controls (10%)                                    40,800
Taxes and freight (8%)                                            32,600
                         Purchased Equipment Costs               $481,200

Direct and indirect installation costs (124% of
  equipment costs)                                               596,700
                       Total Installed Costs                  $1,077,900
                            ANNUALIZED COSTS
                      (8000 hrs/yr or 1000 shifts)
              Item                                                 Costs
Operating labor (0.5 hrs/shift)                               $    4,530
General maintenance (0.5 hr/shift & mat'l)                         8,660
Utilities:
      Electricity - fan and pump (2801 head for pump)              13,400
                    precipitator (1.5 watt/sq.ft.)                 14,500
      Water                                                        1,800
Overhead                                                           7,090
Property tax, insurance and administration @ 4%                   43,100
Capital charges @ 0.11746                                        126,610
Credits - same as Case A
                                 Total  Annualized Costs        $   219,690
                                     6-15

-------
CASE C - OUTLINE OF ENGINEERING CALCULATIONS  FOR VENTURI  SCRUBBERS
     Establish overall  engineering design as  follows:
     a.  Venturi scrubber pressure drop estimated at 15"  W.G.
     b.  Carbon steel,  unlined construction
     c.  Quencher next  to source
     Figure 6-3 shows the system layout for a venturi  scrubber operation.
     The following discussion outlines how the design  parameters are
     obtained for each  stage along the system.
Stage 1 .     Same as for Case A, Fabric Filter.
Stage 2.     a.  The quencher is sized to cool 30,000  scfm gas from 1100 F
                 to 220 F which requires heat transfer of approximately
                 510,000 Btu/min.  The quantity of water required is
                 approximately 55 gpm based on an inlet water temperature
                 of 60 F.  Since quenchers are normally supplied excess
                 water, assume a water rate of 60 gpm.  The pressure head
                 for the quencher is assumed to be 100 ft (43 psig).  The
                 quencher is estimated to be approximately 30 ft long.  The
                 new gas volume after the quencher is:
                 gas:  88,300 ACFM X      |j  =  38,500 AC FM
                 water vapor:  60 gpm X 8.33 Ib/gas X |fŁ4  X 21.1  cu ft/lb
                                                      OoU K
                                                             = 13500 ACFM
                 total:  38,500+13500  =  52,000 ACFM
             b.  Required duct size is:
                              52,000 ACFM   _  17 n f+2
                               4,000 fpm    "  IJ'U Tt
                 Hence a 48" (12.57 ft ) duct may be used giving:
                              5LOOOIACFM   .
                               12.57 ft*
                                    6-16

-------
                                Quencher  \/
                                                                             Water treatment
I
«>J
DESIGN PARAMETER
SCFM
TEMPERATURE
CFM
DUCT DIAMETER
STATIC PRES. (" WG)
1
30,000
1100 F
88,300
64"
K1ln
Draft
2
40,200
220 F
52,000
48"

3
40,200
190 F
49,700
48"
-1"
4
40,200
170 F
48,200
Neglect
-16"
                                      Figure 6-3  VENTURI SCRUBBER SYSTEM DESIGN

-------
 Step  3.       Using  the  heat  transfer  calculations  of  ref.  88,  the  gas
              temperature  will  be  190  F  after  170 ft of  duct.   The  new  gas
              volume will  be:
                          52,000 ACFM  X  |^-|   =  49,700 ACFM
              The pressure drop through  the  duct is 0.6" WG and a pressure
              drop of 0.4" WG is assumed for the quencher.
 Step  4.       The scrubber is sized for  49,700 acfm and  will be constructed
              of 3/16" steel  to allow  for corrosion.   The pressure  drop
              through the  scrubber is  estimated to  be  15" WG (typical average
              for lime'kilns, ref  19).  The  recirculating pump  horsepower is
              estimated to be 20  hp based on 10 gpm per  1000 cfm gas  flow and
              an assumed head of  100 ft.  Some sensible  cooling occurs  in the
              scrubber and this depends  on the inlet water conditions.   In
              this case, a temperature drop  of 20  F is estimated; therefore,
              the fan is sized for:
                          49,700 ACFM  X  f|Ł4   =   48,200 ACFM
                                        DOU  K          S
              A 48" stack  is  selected  for an approximate exit  velocity  of
              4000 fpm.

COST ESTIMATE OF VENTURI SCRUBBER  SYSTEM
     a.   (1)  64" carbon steel  elbow, 1/4" thick
         (Figure 4-10) -                                           $  2,200
     b.   (1)  quencher @ 88,300 ACFM (Figure  4-23) -                 28,000
     c.   (1)  quencher pump for 60  gpm  (Figure  4-29) -                    800
     d.   (170) feet of 48" carbon  steel  duct,  3/16" thick
         (Figure 4-7 ) -                                            11,900
                                     6-18

-------
     e.   (2) expansion joints, one 48" and one 64"
          (Figure 4-12) -                                              7,300
     f.   (1) 49,700 ACFM scrubber, 3/16" thick
          (Figure 5-4 ) -                                             31,200
     g.   (1) 48,200 ACFM radial-tip fan at 16" W.G. actual
          (20" standard) (Figure 4-37). -                             10,000
     h.   (1) 900 RPM, 225 HP drip-proof motor (Figure 4-34) -         8,000
     i.   (1) magnetic starter with circuit breaker
          (Figure 4-34) -                                              2,000
     j.   (1) 48" diameter, 50' high stack, 1/4" thick
          (Figure 4-41) -                                              5,000
                                       Total                        $106,400
     The capital and annualized costs for the venturi scrubber system are
summarized as follows.
                              CAPITAL COSTS
                  Item                                               Cost
Auxiliary equipment and control  device                             $106,400
Instruments and controls (10%)                                        10,640
Taxes and freight (8%)                                                8,500
               Purchased Equipment Costs                            $125,540
                  Item                                             Cost
Direct and indirect installation costs                             114,240
 (91% of equipment costs)
                 Total Installed Costs                            $239,780
                                     6-19

-------
                          ANNUALIZED COSTS
                     (8000 hrs/yr or 1000 shifts)
                  Item                                            Cost
Operating labor (2 hrs/shift)                                    $18,100
General maintenance (1 hr/shift + mat'l)                          34,640
Utilities:
      Electricity - fan power 1.34 Mkwh                           57,890
                    pump power (100  head)                          6,080
      Water       - 10 gpm/1000 acfm + quencher (at cost of
                    0.-10 $/1000 gal.  treated)                     26,880
Waste disposal -  Cost of waste treatment system is not
                             *
                  considered.
Overhead                                                          28,340
Property tax, insurance, and administration @ 4%                   9,590
Capital charges,0.16275 @ 10%, 10 yrs.                             39,020
Credits                                                           	
                                                     s
                                   Total Annual!zed Costs       $220,540

         SUMMARY OF SYSTEM COSTS FOR THREE METHODS OF CONTROL
     Item                   Filter          Precipitator       Scrubber
Capital Costs             $ 834,340         $ 1,077,900       $ 239,780
Annual!zed Costs          $ 287,170         $   219^690       $ 220,540
  The cost of wastewater treatment facilities can be established from
  ref. 128.  Water pollution and treatment are beyond the scope of this
  manual.
                                     6-20

-------
                                Section 7
                  UPDATING COSTS TO FUTURE TIME PERIODS
 7.1  General
     The methods for updating the costs given in this manual are contained in
 this section.  A separate procedure is described for each equipment type or
 cost item.  These procedures have been used to adjust old cost data to December
 1977 levels, when necessary, and these procedures are recommended for updating
 the costs for future time periods.  They have been kept as simple as possible.
 No attempt is made to predict future costs, since this is beyond the scope of
 this manual.  In general, the methods involve use of the Chemical Engineering
 (CE) plant cost indexes and U.S. Department of Labor, Bureau of Labor
 Statistics (BLS) wholesale price indexes.   Selected index accounts  are con-
 tained in Appendix B.
     These two sets of indexes were selected for applicability, consistency,
 specificity, and availability.  The CE index includes such process  industries
 as (among others):
        a.  chemicals and petrochemicals
        b.  fertilizers and agricultural  chemicals
        c.  lime and cement
        d.  man-made fibers
        e.  paints,  varnishes, pigments,  and allied .products
        f.  petroleum refining
        g.  soap glycerin and related products
        h.  wood, pulp, paper, and board
        i.  plastics
                 ,*
     These industries are representative of the  industries under the  attention
of this manual.   The CE indexes  are based  on 1957-1959 =  100 and are  adjusted
                                    7-1

-------
for labor productivity changes  not found in  other cost indexes.   Further
information is available regarding the make-up of the  indexes  and it  is pos-
sible to modify the indexes to  suit particular needs  (see Arnold, T.  H. and
Chi 1 ton, C. H., New Index Shows Plant Cost Trends, Chemical  Engineering.  Feb.
18, 1963, pp.  143-149.  Also refer to Appendix C, Source  Nos.  130 & 131).
    Table B-l  gives the CE indexes as farbackas 1957.  Figure 7-1 shows
how the overall CE plant index  has changed since its  inception.   The  following
are descriptions of the indexes regularly published by Chemical  Engineering.
    A.  ENGINEERING & SUPERVISION
        Engineering and Supervision is 10% of the total plant  index.
        It includes the following:
             33% Engineers
             47% Draftsmen
             20% Clerical
    B.  BUILDINGS
        Buildings is 7% of the  total plant index and is based  on a
                                                      s
        special BLS construction index in which the ratio of materials
        to labor is 53:47.
    C.  ERECTION & INSTALLATION LABOR
        Erection and Installation Labor is 22% of the total  plant
        index.  This is the average hourly earning as  determined by
        the BLS for the contract construction industry.
    D.  EQUIPMENT, MACHINERY, SUPPORTS
        Equipment, Machinery and Supports consists of 61% of the total
        plant index.  This index consists of:
                                      7-2

-------
I

CO
        X
        UJ

        o
        o
        o
                    58   59
60   61   62   63   64   65   66   67   68    69   70    71

                                YEAR
72   73   74   75  76   77  78
                             Figure  7-1   CHEMICAL ENGINEERING  PLANT  COST  INDEX

-------
1.   Fabricated Equipment - 37%
    Such as:   a.   boilers, furnaces,  and heaters
              b.   columns and towers
              c.   heat exchangers
              d.   condensers and reboilers
              e.   process drums
              f.   reactors
              g.   pressure vessels and tanks
              h.   storage tanks and spheres
              i.   evaporators
2.   Process Machinery - 14%
    "Off the shelf" items such as:
              a.   centrifuges
              b.   filters
              c.   mixing and agitating equipment
              d.   rotary kilns and dryers
              e.   conveyors and bucket elevatoVs
              f.   high-pressure vacuum or refrigeration
                  producing equipment
              g.   extruders
              h.   crushing and grinding equipment
              i.   thickeners and settlers
              j.   fans and blowers
3.   Pipe, Valves, and Fittings - 20%
4.   Process Instruments and Controls - 7%
5.   Pumps and Compressors - 7%
                            7-4

-------
         6.  Electrical Equipment and Materials - 5%
             Such as:  a.  electric motors
                       b.  transformers
                       c.  switch gear
                       d.  wire and cable
         7.  Structurals, Supports, Insulation, and Paint - 10%
             Such as:  a.  structural  steel
                       b.  foundation  materials
                       c.  insulation
                       d.  lumber
                       e.  paint
     Cost elements not included in the CE indexes include:
         a.  site clearing and preparation
         b.  insurance and taxes during construction
         c.  company overhead allocated to the project
         d.  contractor's overhead
     For purposes of this manual, the  CE indexes  have  been  used whenever there
is no specifically applicable BLS wholesale  price index.  The  BLS  indexes  used
are given in Tables B-2 thru B-20; the specific commodities  and associated
BLS code number and year of reference  are listed  below:
    Code No.     Base Year=100              Commodity              Table No.
    0312             1967           Cotton Broadwoven  Goods           B-2
    0334             1967           Manmade  Fiber Broadwoven Goods    B-3
    05310101         1967           Natural  Gas                      B-21
    0543          Dec/1970          Industrial  Power                 B-22
    07               1967           Rubber and Plastic Products       B-4
    10130246     '    1967           A-36, Carbon  Steel Plates         B-5
                                     7-5

-------
     Code  No.
     10130247
     10130262
     10130264
     1141

     11450133
     1147

     11730112
     11730113
     11730119
     11750781
     135
     13520111
     13520131
     13520151
     1392
Base Year=100
    1967
    1967
    1967
    1967

    1967
    1967

    1967
    1967
    1967
    1967
    1967
    1967
    1967
  Dec/1974
    1967
        Commodi ty
Stainless Steel  Plate
Carbon Steel Sheet
Stainless Steel  Sheet
Pumps, Compressors, and
Equipment
V-Belt Sheaves
Fans and Blowers, Except
Portable
10 HP, AC Motors
250 HP, AC Motors
50 HP, AC Motors
75 HP, 440 volt, AC Starters
Refractories
Fire Clay Brick, Super Duty
High Alumina Brick, 70 Pet.
Castable Refractories
Insulation Materials
Table No.
  B-6
  B-7
  B-8
  B-9

  B-10
  B-ll

  B-12
  B-13
  B-14
  B-15
  B-16
  B-17
  B-18
  B-19
  B-20
7.2  Equipment Cost Updating Procedures
     Using these indexes,  the procedures  for updating  the  purchase  costs of
each equipment type will  now be discussed.
                                                •
Electrostatic Precipitators
     Use CE Fabricated Equipment index.   For precipitators with  insulation,
     use the following composite index on the additional cost  only:
         1/2 (BLS #1392 factor) + (CE Fabricated Equipment Factor).
Venturi Scrubbers
     Use CE Fabricated Equipment index.   For rubber liners use BLS  #07  on
     the liner cost only.
                                     7-6

-------
Fabric Filters
     Use CE Fabricated Equipment index.  For filters with insulation,  use same
     procedure as for precipitators with insulation.  For stainless steel con-
     struction, use BLS #10130264 on the additional cost.  For filter  media
     use BLS #0312 or #0334.
Thermal and Catalytic Incinerators
     Use CE Fabricated Equipment index for custom units.  Use CE Process
     Equipment index for package units.
Adsorbers
     Same as for thermal and catalytic incinerators.
Absorbers
     Use CE Fabricated Equipment index
Refrigeration
     Use CE Process Equipment index
Flares
     Use CE Fabricated Equipment index
Ductwork
     Use CE Fabricated Equipment index.  For refractories,  however, use the
     appropriate BLS index; the base index is  #135.
Dampers
     Use CE Fabricated Equipment index.  For automatic dampers,  use CE
     Process Instruments and Controls  on that  portion  of price attributable
     to automatic control.
Heat Exchangers
     Use CE Fabricated Equipment index.
Mechanical  Collectors
     Use CE Process Machinery index.
                                     7-7

-------
Fans,  Motors,  and Starters
     For fans  use BLS #1147.   For motors use the appropriate BLS index; the
     base index is #1173.   For starters use BLS #11750781.   For V-belts use
     BLS #11450133.
Stacks
     Use CE Fabricated Equipment index.
Cooling Tower
     Use CE Fabricated Equipment index.
Pumps
     Use BLS #1141 index.
Dust Removal Equipment
     For screw conveyors,  use the CE Fabricated Equipment index.  For water
     treatment equipment,  use the appropriate CE or BLS index, depending on
     the equipment component.
                                     7-8

-------
       APPENDIX A




COMPOUND INTEREST FACTORS

-------
              Table A-l  1% COMPOUND  INTEREST FACTORS
        Single Payment

                 Present
                   Worth
                   Factor
 n                 P/F

 1               0.9901
 2               0.9803
 3               0.9706
 4               0.9610
 5               0.9515

 6               0.9420
 7               0.9327
 8               0.9235
 9               0.9143
10               0.9053

11               0.8963
12               0.8874
13               0.8787
14               0.8700
15               0.8613

16               0.8528
17               0.8444
18               0.8360
19               0.8277
20               0.8195

21               0.8114
22               0.8034
23               0.7954
24               0.7876
25               0.7798

26               0.7720
27               0.7644
28               0.7568
29               0.7493
30               0.7419

31               0.7346
32               0.7273
33               0.7201
34               0.7130
35               0.7059
40               0.6717
45               0.6391
50               0.6080
Uniform Series
Capital
Recovery
Factor
A/P
1.01000
0.50751
0.34002
0.25628
0.20604
0.17255
0.14863
0.13069
0.11674
0.10558
0.09645
0.08885
0.08241
0.07690
0.07212
0.06794
0.06426
0.06098
0.05805
0.05542
0.05303
0.05086
0.04889
0.04707
0.04541
0.04387
0.04245
0.04112
0.03990
0.03875
0.03768
0.03667
0.03573
0.03484
0.03400
0.03046
0.02771
0.02551
Present
Worth
Factor
P/A
0.990
1.970
2.941
3.902
4.853
5.795
6.728
7.652
8.566
9.471
10.368
11.255
12.134
13.004
13.865
14.718
15.562
16.398
17.226
18.046
18.857
19.660
20.456
21.243
22.023
22.795
23.560
24.316
25.066
25.808
26.542
27.270
27.990
28.703
29.409
32.835
36.095
39.196
                                    A-l

-------
               Table A-2   2%  COMPOUND  INTEREST  FACTORS
  1
  2
  3
  4
  5
  6
  7
  8
  9
10

11
12
13
14
15

16
17
18
19
20
21
22
23
24
25

26
27
28
29
30
31
32
33
34
35

40
45
50
Single Payment

         Present
           Worth
           Factor
           P/F

         0.9804
         0.9612
         0.9423
         0.9238
         0.9057

         0.8880
         0.8/06
         0.8535
         0.8368
         0.8203

         0.8043
         0.7885
         0.7730
         0.7579
         0.7430

         0.7284
         0.7142
         0.7002
         0.6864
         0.6730
                                               Uniform  Series
         0.
         0.
  .6598
  ,6468
0.6342
0.6217
0.6095

0.5976
0.5859
0.5744
0.5631
0.5521

0.5412
0.5306
0.5202
0.5100
0.5000

0.4529
0.4102
0.3715
Capita]
   Recovery
   Factor
   A/P

1.02000
0.51505
0.34675
0.26262
0.21216

0.17853
0.15451
0.13651
0.12252
0.11133

0.10218
0.09456
0.08812
0.08260
0.07783

0.07365
0.06997
0.06670
0.06378
0.06116

0.05878
0.05663
0.05467
0.05287
0.05122

0.04970
0.04829
0.04699
0.04578
0.04465

0.04360
0.04261
0.04169
0.04082
0.04000

0.03656
0.03391
0.03182
                                          Present
                                            Worth
                                            Factor
                                            P/A

                                          0.980
                                            ,942
                                            .884
                                            .808
  4.713

  5.601
  6.472
  7.325
  8.162
  8.983

  9.787
10.575
11.348
12.106
12.849

13.578
14.292
14.992
15.678
16.351

17.011
17.658
18.292
18.914
19.523

20.121
20.707
21.281
21.844
22.396

22.938
23.468
23.989
24.499
24.999

27.355
29.490
31.424
                                     A-2

-------
              Table A-3  3% COMPOUND INTEREST FACTORS
        Single Payment
                             Uniform Series
 1
 2
 3
 4
 5

 6
 7
 8
 9
10
11
12
13
14
15

16
17
18
19
20
21
22
23
24
25

26
27
28
29
30
31
32
33
34
35

40
45
50
Present
  Worth
  Factor
  P/F

0.9709
0.9426
0.9151
0.8885
0.8626

0.8375
0.8131
0.7894
0.7664
0.7441

0.7224
0.7014
0.6810
0.6611
0.6419

0.6232
0.6050
0.5874
0.5703
0.5537

0.5375
0.5219
0.5067
0.4919
0.4776
0.4637
0.4502
0.4371
0.4243
0.4120
0.4000
0.3883
0.3770
0.3660
0.3554

0.3066
0.2644
0.2281
Capita]
Recovery
Factor
A/P
1.03000
0.52261
0.35353
0.26903
0.21835
0.18460
0.16051
0.14246
0.12843
0.11723
0.10808
0.10046
0.09403
0.08853
0.08377
0.07961
0.07595
0.07271
0.06981
0.06722 s
0.06487
0.06275
0.06081
0.05905
0.05743
0.05594
0.05456
0.05329
0.05211
0.05102
0.05000
0.04905
0.04816
0.04732
0.04654
0.04326
0.04079
0.03887
Present
Worth
Factor
P/A
0.971
1.913
2.829
3.717
4.580
5.417
6.230
7.020
7.786
8.530
9.253
9.954
10.635
11.296
11.938
12.561
13.166
13.754
14.324
14.877
15.415
15.937
16.444
16.936
17.413
17.877
18.327
18.764
19.188
19.600
20.000
20.3b9
20.766
21.132
21.487
23.115
24.519
25.730
                                     A-3

-------
  1
  2
  3
  4
  5

  6
  7
  8
  L>
10

11
12
13
14
15

16
17
18
19
20

21
22
23
24
25

26
27
28
29
30
31
32
33
34
35

40
45
50
               Table A-4  4% COMPOUND INTEREST FACTORS

         Single Payment                        Uniform Series
Present
  Worth
  Factor
  P/F

0.9615
0.9246
0.8890
0.8548
0.8219

0.7903
0.7599
0.7307
0.7026
0.6756

0.6496
0.6246
0.6006
0.5775
0.5553

0.5339
0.5134
0.4936
0.4746
0.4564
0.
0.
 .4388
 .4220
0.4057
0.3901
0.3751

0.3607
0.3468
0.3335
0.3207
0.3083
0.2965
0.2851
 .2741
 ,2636
0.
0.
0.2534
0.2083
0.1712
0.1407
Capital
Recovery
Factor
A/P
1.04000
0.53020
0.36035
0.27549
0.22463
0.19076
0.16661
0.14853
0.13449
0.12329
0.11415
0.10655
0.10014
0.09467
0.08994
0.08582
0.08220
0.07899
0.07614
0.07358
0.07128
0.06920
0.06731
0.06559
0.06401
0.06257
0.06124
0.06001
0.05888
0.05783
0.05686
0.05595
0.05510
0.05431
0.05358
0.05052
0.04826
0.04655
Present
Worth
Factor
P/A
0.962
1.886
2.775
3.630
4.452
5.242
6.002
6.733
7.435
8.111
8.760
9.385
9.986
10.563
11.118
11.652
12.166
12.659
13.134
13.590
14.029
14.451
14.857
15.247
15.622
15.983
16.330
16.663
16.984
17.292
17.588
17.874
18.148
18.411
18.665
19.793
20.720
21.482
                                    •A-4

-------
 1
 2
 3
 4
 5

 6
 7
 8
 9
10
11
12
13
14
15

16
17
18
19
20
21
22
23
24
25

26
27
28
29
30
31
32
33
34
35

40
45
50
              Table A-5  5% COMPOUND INTEREST FACTORS

        Single 'Payment                        Uniform Series
Present
  Worth
  Factor
  P/F

0.9524
0.9070
0.8638
0.8227
0.7835

0.7462
0.7107
0.6768
0.6446
0.6139
0.5847
0.5568
  ,5303
  ,5051
0.
0.
0.4810
0.4581
0.4363
0.4155
0.3957
0.3769

0.3589
0.3418
0.3256
0.3101
0.2953

0.2812
0.2678
0.2551
0.2429
0.2314
0.2204
0.2099
0.1999
0.1904
0.1813

0.1420
0.1113
0.0872
Capital
Recovery
Factor
A/P
1.05000
0.53780
0.36721
0.28201
0.23097
0.19702
0.17282
0.15472
0.14069
0.12950
0.12039
0.11283
0.10646
0.10102
0.09634
0.09227
0.0&870
0.08555
0.08275
0.08024
0.07800
0.07597
0.07414
0.07247
0.07095
0.06956
0.06829
0.06712
0.06605
0.06505
0.06413
0.06328
0.06249
0.06176
0.06107
0.05828
0.05626
0.05478
Present
Worth
Factor
P/A
0.952
1.859
2.723
3.546
4.329
5.076
5.786
6.463
7.108
7.722
8.306
8.863
9.394
9.899
10.380
10.838
11.274
11.690
12.085
12.462
12.821
13.163
13.489
13.799
14.094
14.375
14.643
14.898
15.141
15.372
15.593
15.803
16.003
16.193
16.374
17.159
17.774
18.256
                                    A-5

-------
  1
  2
  3
  4
  5

  6
  7
  8
  9
10

11
ir
13
14
15

16
17
18
19
20

21
22
23
24
25

26
27
28
29
30
31
32
33
34
35

40
45
50
              Table A-6   6%  COMPOUND  INTEREST  FACTORS

         Single  Payment                         Uniform Series
 Present
   Worth
   Factor
   P/F

 0.9434
 0.8900
 0.8396
 0.7921
 0.7473

 0.7050
 0.6651
 0.6274
 0.5919
 0.5584

 0.5268
 0.4970
 0.4688
 0.4423
 0.4173

 0.3936
 0.3714
 0.3503
 0.3305
 0.3118

 0.2942
 0.2775
 0.2618
 0.2470
 0.2330

 0.2198
 0.2074
 0.1956
 0.1846
 0.1741

 0.1643
 0.1550
 0.1462
 0.1379
0.1301

0.0972
0.0727
0.0543
Capital
Recovery
Factor
A/P
1.06000
0.54544
0.37411
0.28859
0.23740
0.20336
0.17914
0.16104
0.14702
0.13587
0.12679
0.11928
0.11296
0.10758
0.10296
0.09895
0.09544
0.09236
0.08962
0.08718
0.08500
0.08305
0.08128
0.07968
0.07823
0.07690
0.07570
0.07459
0.07358
0.07265
0.07179
0.07100
0.07027
0.06960
0.06897
0.06646
0.06470
0.06344
Present
Worth
Factor
P/A
0.943
1.833
2.673
3.465
4.212
4.917
5.582
6.210
6.802
7.360
7.887
8.384
8.853
9.295
9.712
10.106
10.477
10.828
11.158
11.470
11.764
12.042
12.303
12.550
12.783
13.003
13.211
13.406
13.591
13.765
13.929
14.084
14.230
14.368
14.498
15.046
15.456
15.762
                                    A-6

-------
              Table A-7

        Single Payment

                 Present
                   Worth
                   Factor
 n                 P/F

 1               0.9346
 2               0.8734
 3               0.8163
 4               0.7629
 5               0.7130

 6               0.6663
 7               0.6227
 8               0.5820
 9               0.5'439
10               0.5083

11               0.4751
12               0.4440
13               0.4150
14               0.3878
15               0.3624

16               0.3387
17               0.3166
18               0.2959
19               0.2765
20               0.2584
21               0.2415
22               0.2257
23               0.2109
24               0.1971
25               0.1842

26               0.1722
27               0.1609
28               0.1504
29               0.1406
30               0.1314
31               0.1228
32               0.1147
33               0.1072
34               0.1002
35               0.0937

40               0.0668
45               0.0476
50               0.0339
7% COMPOUND INTEREST FACTORS

                     Uniform Series
Capital
Recovery
Factor
A/P
1.07000
0.55309
0.38105
0.29523
0.24389
0.20980
0.18555
0.16747
0.15349
0.14238
0.13336
0.12590
0.11965
0.11434
0.10979
0.10586
0.10243
0.09941
0.09675
0.09439
0.09229
0.09041
0.08871
0.08719
0.08581
0.08456
0.08343
0.08239
0.08145
0.08059
0.07980
0.07907
0.07841
0.07780
0.07723
0.07501
0.07350
0.07246
Present
Worth
Factor
P/A
0.935
1.808
2.624
3.387
4.100
4.767
5.389
5.971
6.515
7.024
7.499
7.943
8.358
8.745
9.108
9.447
9.763
10.0-j9
10.336
10.594
10.836
11.061
11.272
11.469
11.654
11.826
11.987
12.137
12.278
12.409
12.&J2
12.6*7
12.754
12.854
12.948
13.332
13.606
13.801
                                    A-7

-------
  1
  2
  3
  4
  5
  6
  7
  8
  9
10

11
12
13
14
15

16
17
18
19
20

21
22
23
24
25

26
27
28
29
30
31
32
33
34
35

40
45
50
               Table A-8  8% COMPOUND INTEREST FACTORS
                                          •
         Single Payment                        Uniform Series
 Present
   Worth
   Factor
   P/F

 0.9259
 0.8573
 0.7938
 0.7350
 0.6806
 0.6302
 0.5835
 0.5403
 0.5002
 0.4632

 0.4289
 0.3971
 0.3677
 0.3405
 0.3152

 0.2919
 0.2703
 0.2502
 0.2317
 0.2145

 0.1987
 0.1839
 0.1703
 0.1577
 0.1460

 0.1352
 0.1252
 0.1159
 0.1073
 0.0994
 0.0920
 0.0852
 0.0789
 0.0730
0.0676

0.0460
0.0313
0.0213
Capital
Recovery
Factor
A/P
1.08000
0.56077
0.38803
0.30192
0.25046
0.21632
0.19207
0.17401
0.16008
0.14903
0.14008
0.13270
0.12652
0.12130
0.11683
0.11298
0.10963
0.10670
0.10413
0.10185
0.09983
0.09803
0.09642
0.09498
0.09368
0.09251
0.09145
0.09049
0.08962
0.08883
0.08811
0.08745
0.08685
0.08630
0.08580
0.08386
0.08259
0.08174
Present
Worth
Factor
P/A
0.926
1.783
2.577
3.312
3.993
4.623
5.206
5.747
6.247
6.710
7.139
7.536
7.904
8.244
8.559
8.851
9.122
9.372
9.604
9.818
10.017
10.201
10.371
10.529
10.675
10.810
10.935
11.051
11.158
11.258
11.350
11.435
11.514
11.587
11.655
11.925
12.108
12.233
                                     A-8

-------
              Table A-9  10% COMPOUND INTEREST FACTORS

        Single Patient                        Uniform Series
                 Present
                   Worth
                   Factor
 n                 P/F


 1               0.9091
 2               0.8264
 3               0.7513
 4               0.6830
 5               0.6209
 6               0.5645
 7               0.5132
 8               0.4665
 9               0.4241
10               0.3855

11               0.3505
12               0.3186
13               0.2897
14               0.2633
15               0.2394

16               0.2176
17               0.1978
18               0.1799
19               0.1635
20               0.1486
21               0.1351
22               0.1228
23               0.1117
24               0.1015
25               0.0923

26               0.0839
27               0.0763
28               0.0693
29               0.0630
30               0.0573
31               0.0521
32               0.0474
33               0.0431
34               0.0391
35               0.0356

40               0.0221
45               0.0137
50               0.0085
Capital
Recovery
Factor
A/P
1.10000
0.57619
0.40211
0.31547
0.26380
0.22961
0.20541
0.18744
0.17364
0.16275
0.15396
0.14676
0.14078
0.13575
0.13147
0.12782
0.12466
0.12193
0.11955
0.11746
0.11562 S
0.11401
0.11257
0.11130
0.11017
0.10916
0.10826
0.10745
0.10673
0.10608
0.10550
0.10497
0.10450
0.10407
0.10369
0.10226
0.10139
0.10086
Present
Worth
Factor
P/A
0.909
1.736
2.487
3.170
3.791
4.355
4.868
5.355
5.759
6.144
6.495
6.614
7.1J3
7.367
7.606
7.824
8.022
8.201
8.365
8.514
8.649
8.772
8.883
8.985
9.077
9.161
9.237
9.307
9.370
9.427
9.479
9.5i:6
9.569
9.609
9.644
9.779
9.863
9.915
                                    A-9

-------
               Table A-10  12% COMPOUND INTEREST FACTORS

         Single Payment                        Uniform Series
                  Present
                    Worth
                    Factor
  n                 P/F


  1               0.8929
  2               0.7972
  3               0.7118
  4               0.6355
  5               0.5674

  6               0.5066
  7               0.4523
  8               0.4039
  9               0.3606
10               0.3220

11                0.2875
12               0.2567
13                0.2292
14               0.2046
15               0.1827

16               0.1631
17                0.1456
16                0.1300
19                0.1161
20                0.1037

21                0.0926
22                0.0826
23                0.0738
24                0.0659
25                0.0588

26                0.0525
27                0.0469
28                0.0419
29               0.0374
30               0.0334
31               0.0298
32               0.0266
33               0.0238
34               0.0212
35               0.0189

40               0.0107
45               0.0061
50               0.0035
Capita]
Recovery
Factor
A/P
1.12000
0.59170
0.41635
0.32923
0.27741
0.24323
0.21912
0.20130
0.18768
0.17698
0.16842
0.16144
0.15568
0.15087
0.14682
0.14339
0.14046
0.13794
0.13576
0.13388
0.13224
0.13081
0.12956
0.12846
0.12750
0.12665
0.12590
0.12524
0.12466
0.12414
0.12369
0.12328
0.12292
0.12260
0.12232
0.12130
0.12074
0.12042
Present
Worth
Factor
P/A
0.893
1.690
2.402
3.037
3.605
4.111
4.564
4.968
5.328
5.650
5.938
6.194
6.424
6.628
6.811
6.974
7.120
7.250
7.366
7.469
7.562
7.645
7.718
7.784
7.843
7.896
7.943
7.984
8.022
8.055
8.085
8.112
8.135
8.157
8.176
8.244
8.283
8.305
                                    A-10

-------
              Table A-ll  15% COMPOUND INTEREST FACTORS
        Single Payment
                 Present
                   Worth
                   Factor
                   P/F
                             Uniform Series
                      Capital
                        Recovery
                        Factor
                        A/P
                    Present
                      Worth
                      Factor
                      P/A
 1
 2
 3
 4
 5
 6
 7
 8
 9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
40
45
50
0.8696
0.7561
0.6575
0.5718
0.4972
0.4323
0.3759
0.3269
0/2843
0.2472
0.2149
0.1869
0.1625
0.1413
0.1229
0.1069
0.0929
0.0808
0.0703
0.0611
0.0531
0.0462
0.0402
0.0349
0.0304
0.0264
0.0230
0.0200
0.0174
0.0151
0.0131
0.0114
0.0099
0.0086
0.0075
0.0037
0.0019
0.0009
1.15000
0.61512
0.43798
0.35027
0.29832

0.26424
0.24036
0.22285
0.20957
0.19925

0.19107
0.18448
0.17911
0.17469
0.17102

0.16795
0.16537
0.16319
0.16134
0.15976

0.15842
0.15727
0.15628
0.15543
0.15470

0.15407
0.15353
0.15306
0.15265
0.15230

0.15200
0.15173
0.15150
0.15131
0.15113

0.15056
0.15028
0.15014
0.870
1.626
2.283
2.855
3.352
3.
4.
 .784
 .160
4.487
4.772
5.019
  ,234
  .421
  .583
5.724
5.847
5.
5.
5.
5.
6.
  ,954
  .047
6.128
6.198
6.259

6.312
6.359
6.399
6.434
6.464

6.491
6.514
6.534
6.551
6.566
6.579
6. b91
  , 600
  ,609
6.
6.
6.617

6.642
6.654
6.661
                                    A-ll

-------
              Table A-12   20%  COMPOUND  INTEREST FACTORS
  1
  2
  3
  4
  5

  6
  7
  8
  9
10

11
12
13
14
15

16
17
18
19
20

21
22
23
24
25

26
27
28
29
30

31
32
33
34
35

40
45
50
         Single  Payment

                  Present
                   Worth
                   Factor
                   P/F
0.8333
0.6944
0.5787
0.4823
0.4019

0.3349
0.2791
0.2326
0.1938
0.1615
0.1346
0.1122
0.0935
0.0779
0.0649
                              Uniform  Series
0.
0.
  .0541
  .0451
0.0376
0.0313
0.0261

0.0217
0.0181
0.0151
0.0126
0.0105

0.0087
0.0073
0.0061
0.0051
0.0042

0.0035
0.0029
0.0024
0.0020
0.0017

0.0007
0.0003
0.0001
Capital
Recovery
Factor
A/P
1.20000
0.65455
0.47473
0.38629
0.33438
0.30071
0.27742
0.26061
0.24808
0.23852
0.23110
0.22526
0.22062
0.21689
0.21388
0.21144
0.20944
0.20781
0.20646
0.20536
0.20444
0.20369
0.20307
0.20255
0.20212
0.20176
0.20147
0.20122
0.20102
0.20085
0.20070
0.20059
0.20049
0.20041
0.20034
0.20014
0.20005
0.20002
Present
Worth
Factor
P/A
0.833
1.528
2.106
2.589
2.991
3.326
3.605
3.837
4.031
4.192
4.327
4.439
4.533
4.611
4.675
4.730
4.775
4.812
4.844
4.870
4.891
4.909
4.925
4.937
4.948
4.956
4.964
4.970
4.975
4.979
4.982
4.985
4.988
4.990
4.992
4.997
4.999
4.999
                                   A-12

-------
     'APPENDIX B





EQUIPMENT COST INDEXES

-------
                              TABLE  B-l  CHEMICAL ENGINEERING PLANT COST INDEXES
    INDEX
 1978
ANNUAL
 JAN    FEB    MAR
 APR    MAY    JUN
 JUL    AUG    SEP
 OCT    NOV    DEC
CE Plant Index
Engineering &
 Supervision
Building
 218.8
 161.9

 213.7
210.6  213.1  214.1
159.2  159.6  159.9

207.0  210.5  210.3
215.7  216.9  217.7
160.3  160.6  161.0

211.1  212.8  214.0
219.2  221.6  222.8
161.6  162.0  162.3

215.0  214.3  216.3
223.5  224.7  225.9
162.6  165.4  168.2

217.2  217.8  218.1
Construction Labor
Equipment, Machinery
 Supports
Fabricated Equipment
 185.8
 240.6
 238.6
182.8  181.1  182.0
229.6  233.8  234.9

226.6  233.0  233.6
180.7  183.1  183.4
237.9  238.8  239.8

237.1  237.3  237.4
186.6  188.2  191.0
240.9  244.2  244.9

238.6  243.3  243.2
190.8  190.3  190.5
246.0  247.6  249.0

243.8  244.1  245.2
Process Machinery
Pipe, Valves &
 Fittings
Process Instruments &
 Controls
 228.3
 269.4

 216.0
218.1  221.6  222.7
256.0  262.2  264.0

209.8  211.0
224.3  225.5  226.8
266.0  .267.0  268.4

212.1  214.2  214.6
228.6  231.0  232.5
269.1  273.1  274.9

217.2  218.3  218.6
234.1  235.8  237.8
276.5  278.1  277.9

219.5  221.7  223.7
Pumps & Compressors
Electrical Equipment
 & Materials
Structural Supports
 Insulation & Paint
 257.5
 167.8
 249.1
248.4  250.3  250.6
162.5  162.9  162.8

235.5  236.8  240.7
254.2  256.3  258.2
164.6  166.4  167.9

246.6  247.4  250.1
258.6  258.8  259.1
168.7  169.5  170.0

250.5  253.6  254.7
260.9  266.6  268.1
170.5  173.5  174.1

256.1  258.0  258.7
            SOURCE:   Chemical  Engineering,  Economic  Indicators

-------
                         Table B-l  CHEMICAL ENGINEERING PLANT COST INDEXES
         INDEX
 1977
ANNUAL
 JAN    FEB    MAR
 APR    MAY    JUN
 JUL    AUG    SEP
 OCT    NOV    DEC
CE Plant Index
Engineering &
  Supervision
Building
204.1
162.1
199.1
198.7  198.5  199.3
158.3  159.0  159.7

194.0  193.6  195.3
200,3  201.4  202.3
160.4  161.0  161.7

196.7  197.3  197.2
204.7  206.4  208.8
162.4  163.1  163.8

199.0  201.0  204.2
209.0  209.4  210.3
164.4  165.1  165.8

203.6  203.5  204.1
Construction Labor
Equipment, Machinery
  Supports
       „>
Fabricated Equipment
178.2
220.9
216.6
178.5  176.3  175.7
213.2  213.6  214.8
208.3  208.3  208.9
175.6  175.9  176.8
216.2  217.7  218.8

210.2  211.9  212.8
177.1  178.1  180.8
222.3  224.3  226.8

219.8  222.1  223.9
181.5  180.9  181.2
226.9  227.7  228.7

222.9  224.4  226.2
Process Machinery
Pipe, Valves &
  Fittings
Process Instruments &
  Controls
211.6
247.7

203.3
205.8  206,1   207.1
236.3  238.1   241.0

199.5  199.6   200.1
207.8  209.0  210.1
244.6  246.5  247.3

200,8  201.5  201.5
212-:3  213.8  215.0
248.2  251.9  254.1

202.5  203.1  204.3
216.0  217.4  218.3
255.0  254.1  254.9

207.8  209.1  209.9
Pumps & Compressors
Electrical Equipment
  & Materials
Structural Supports
  Insulation & Paint
240.2
159.0

226.0
234.6  234.3  234.4
154.0  154.9  156.4

219.3  219.2  220.7
234.4  237.2  238.8
157.2  158.0  159.2

221.3  221.7  223.6
241.8  241.9  244.0
160.6  160.3  161.3

225.2  226.2  235.4
245.4  247.9  248.0
161.8  161.9  162.4

233.2  233.0  233.5
     SOURCE:  Chemical Engineering, Economic Indicators

-------
                         Table  B-l   CHEMICAL  ENGINEERING PLANT COST INDEXES
         INDEX
 1976
ANNUAL
 JAN    FEB    MAR
 APR    MAY    JUN
 JUL    AUG    SEP
                                                                OCT     NOV    DEC
CE Plant Index
Engineering &
  Supervision
Building
192.1
150.8
187.4
187.3  187.5  188.4
147.9  148.5  149.1
182.6  182.9  184.4
188.9  190.2  191.1
149.6  150.2  150.7
185.2  186.0  185.3
192.0  193.9  195.6
151.2  151.7  152.1
186.5  188.3  190.8
                                                              196.3  196.4  197.4
                                                              152.6  153.0  153.5

                                                              191.4  192.0  192.9
Construction Labor
Equipment, Machinery
  Supports
Fabricated Equipment
174.2
205.8
200.8
172.8  171.3  172.5
199.5  200.3  200.9

196.2  196.3  196.6
171.3  173.4  172.9
202.1  203.3  205.0
196.0  197.0  198.5
174.3  174.6  176.5
205.6  208.5  210.2

198.9  203.7  205.3
                                                              177.1  176.9  177.0
                                                              211.0  211.0  212.5

                                                              205.9  206.5  208.3
Process Machinery
Pipe, Valves &
  Fittings
Process Instruments  &
  Controls
197.5
232.5
193.1
191.6  192.9  193.1
222.9  223.0  223.9

188.2  189.6  190.0
                     193.8   194.9   196.9
                     229.0   231.9   235.1

                     190.4   191.3   192.5
                     198.0  199.0   200.7
                     235.8  236.9   238.0

                     193.2  193.3   195.3
                     201.7  202.8  204.5
                     239.1  236.8  237.3

                     197.1  197.5  198.7
Pumps & Compressors
Electrical  Equipment
  & Materials
Structural  Supports
  Insulation & Paint
220.9
148.9
209.7
211.5  217.7  218.0
145.0  145.6  146.1
202.6  202.3  204.9
219.5  219.4  221.2
146.9  147.3  147.6
205.5  206.5  206.7
221.3  222.6  223.9
147.6  148.9  150.6
207.5  213.3  216.8
                                                              223.2  223.7  228.7
                                                              153.8  153.9  153.4

                                                              216.8  216.4  217.0
     SOURCE:   Chemical  Engineering, Economic Indicators

-------
                                     Table B-l  CHEMICAL ENGINEERING PLANT COST INDEXES
CD
I
INDEX
CE Plant Index
Engineering &
Supervision
Building
Construction Labor
Equipment, Machinery
Supports
:abr1cated Equipment
Process Machinery
Pipe, Valves &
Fittings
'rocess Instruments &
Controls
Pumps & Compressors
Electrical Equipment
& Materials
Structural Supports
Insulation & Paint
1975
ANNUAL
182.3
141.8
176.9
168.4
194.7
192.2
184.7
217.0
181.4
208.3
. 143.0
198.6
JAN FEB MAR
179.4 179.5 180.7
139.6 139.8 140.2
173.1 173.6 174.7
166.7 164.2 167.4
191.6 192.3 192.9
190.7 190.6 191.6
179.1 179.9 181.4
209.8 212.9 212.8
177.6 177.8 177.7
208.7 208.7 208.7
141.5 141.7 142.4
198.6 198.2 198.4
APR MAY JUN
180.7 180.8 181.8
140.7 141.1 141.6
175.5 175.8 176.3
166.6 165.5 167.3
193.0 193.3 194.3
191.6 191.1 191.5
182.5 182.8 184.7
213.5 217.2 217.8
178.8 178.9 180.4
206.2 206.2 208.3
141.4 141.8 142.0
198.0 195.5 196.4
JUL AUG SEP
182.1 181.9 183.7
142.0 142.4 142.9
177.1 177.5 178.8
168.4 168.7 171.9
194.2 193.7 195.2
'190.0 190.0 191.4
185.5 185.1 186.3
216.0 216.7 219.9
180.2 181.2 183.3
209.1 207.6 209.4
151.5 141.6 .141.8
198.5 198.5 197.9
OCT NOV DFC
185.6 185.5 186.2
143.3 143.7 144.2
180.2 179.4 181.1
172.0 171.2 171.1
198.1 198.2 199.1
195.8 195.2 196.4
188.8 189.6 19C-?
221.6 222.6 223.3
186.3 186.6 187. Ł
209.1 209.1 209.0
143.1 143.7 143.3
200.7 200.7 201.2
               SOURCE: Chemical  Engineering,  Economic  Indicators

-------
                                  Table  B-l   CHEMICAL  ENGINEERING PLANT COST INDEXES (cont'd)
INDEX .
CE Plant Index
Engineering &
Supervision
Building
Construction Labor
Equipment, Machinery
Supports
Fabricated Equipment
Process Machinery
Pipe, Valves &
Fittings
Process Instruments &
Controls
Pumps & Compressors
Electrical Equipment
& Materials
Structural Supports
Insulation & Paint
1974
ANNUAL
165.4
134.4
165.5
163.4
171.2
170.1
160.3
192.2
164.7
175.7
126.4
172.4
JAN FEB MAR
150.0 150.7 153.8
131.6 131.9 132.2
156.7 156.4 158.8
162.7 162.4 162.3
147.7 149.0 153.7
147.3 148.7 152.7
143.1 143.7 146.8
162.6 163.2 169.9
152.0 153.4 158.2
144.0 145.8 150.6
109.7 110.3 112.3
s
145.0 147.5 155.0
APR MAY JUN
156.7 161.4 164.7
132.5 132.8 132.8
162.3 164.3 165.4
162.7 160.0 159.4
157.8 166.2 171.8
155.1 165.1 169.3
149.4 154.8 159.2
179.6 1B9.6 197.1
157.2 159.7 162.7
157.9 168.2 175.6
114.0 121.5 127.1
158.5 165.1 173.4
JUL AUG SEP
168.8 172.2 174.8
134.0 134.3 134.5
167.1 170.6 172.7
159.5 164.1 166.6
178.0 181.6 184.7
179.0 181.4 184.0
163.5 167.9 170.3
203.0 206.7 209.4
165.8 168.2 173.2
182.7 186.8 187.3
131.5 133.5 136.3
173.5 180.8 188.1
OCT NOV PFi
176.0 177.4 177.8
138.2 138.7 139.1
170.5 172.1 172.'-
165.8 166.9 165.6
186.5 188.1 188.8
186.0 186.1 186.8
172.9 175.7 177.2
209.7 208.3 208.7
174.1 175.2 176.9
195.8 206.9 206.9
138.2 141.4 141.4
187.4 191.9 1S2.4
03
I

(Tt
             SOURCE: Chemical Engineering, Economic Indicators

-------
                                Table B-l   CHEMICAL ENGINEERING PLANT COST INDEXES (cont'd)
INDEX
CE Plant Index
Engineering &
Supervision
Building
Construction Labor
Equipment, Machinery
Supports
Fabricated Equipment
Process Machinery
Pipe, Valves &
Fittings
Process Instruments &
Controls
Pumps & Compressors
Electrical Equipment
& Materials
Structural Supports
Insulation & Paint
1973
ANNUAL
144.1
122.84
150.6
157.9
141.9
142.5
137.6
151.3
147.1
139.5
104.2
140.9
JAN FEB MAR
140.8 140.4 141.5
112.0 112.0 122.3
146.5 146.9 148.3
158.9 155.8 154.8
138.3 138.8 140.7
140.0 140.0 140.9
134.3 134.5 135.1
146.1 146.1 149.2
145.0 144.9 145.8
137.0 137.0 138.4
100.6 100.6 102.1
137.2 137.2 140.0
APR MAY JUN
141.8 142.4 144.5
122.4 112.5 129.8
150.3 151.1 150.4
155.0 155.4 155.6
140.9 141.7 142.2
141.7 142.6 143.0
137.1 137.6 137.9
150.1 151.1 151.7
146.1 146.9 146.9
138.4 138.4 141.3
103.9 104.5 105.2
141.2 142.0 141.8
JUL AUG SEP
144.6 145.0 146.4
130.1 130.1 130.1
149.8 150.4 153.0
156.3 156.3 161.8
142.1 142.0 142.6
143.0 143.0 143.4
137.9 138.5 139.1
151.8 151.8 151.8
147.0 147.4 147.9
140.9 140.9 140.9
105.1 105.1 105.1
141.2 141.2 141.2
OCT NOV DEC
146.7 147.5 148.2
130.7 130.8 131.3
150.9 154.7 155.0
161.7 161.6 162.0
143.5 144.3 145.2
143.7 144.1 144.8
139.6 140.3 142.0
153.9 156.6 157.3
148.1 148.8 150.4
140.8 141.4 142.4
105.3 106.0 107.2
141.5 143.5 142.8
00
          SOURCE:  Chemical Engineering, Economic  Indicators

-------
                                    Table B-l  CHEMICAL  ENGINEERING  PLANT COST INDEXES (cont'd)
INDEX
CE Plant Index
Engineering &
Supervision
Building
Construction Labor
Equipment, Machinery
Supports
Fabricated Equipment
Process Machinery
Pipe, Valves &
Fittings
Process Instruments &
Controls
Pumps & Compressors
Electrical Equipment
& Materials
Structural Supports
Insulation & Paint
1972
ANNUAL
137.2
111.9
142.0
152.2
135.4
136.3
132.1
142.9
143.8
135.9
99.1
133.6
JAN FEB MAR
136.0 136.0 137.0
111.8 111.9 111.7
139.8 140.0 140.7
151.9 151.6 150.8
133.8 133.9 135.8
135.1 136.1 137.8
130.5 129.6 131.8
141.4 141.9 143.1
141.9 142.7 143.6
132.4 134.4 135.7
98.2 98.3 98.2
•f
131.2 131.9 132.1
APR MAY JUN
137.1 137.1 136.5
111.6 111.9 111.9
141.4 141.6 140.3
151.3 151.7 149.7
135.3 135.5 135.4
136.2 135.9 135.7
132.2 132.2 132.2
143.1 143.2 143.3
143.9 144.1 144.0
135.7 135.7 136.3
98.6 99.1 99.4
132.7 134.9 134.1
JUL AUG SEP
136.5 137.0 137.8
112.0 112.1 112.1
141.4 141.9 143.0
149.7 150.6 153.1
135.2 135.6 135.9
135.6 136.3 135.7
132.2 132.3 132.9
142.9 142.9 143.0
144.0 144.3 144.2
136.6 136.7 136.7
99.3 99.5 99.4
"133.8 134.2 134.4
OCT NOV DlC
138.2 138.4 139.1
112.0 112.1 112.1
144.1 144.5 145.0
154.5 154.7 156.7
135.9 136.0 136.5
136.8 136.6 137.5
132.9 133.1 133.6
143.3 143.6 143.6
144.1 144.2 144.7
137.7 137.0 137.0
99.3 100.0 100.1
134.5 134.5 134.6
CO
•I,
               SOURCE:   Chemical  Engineering,  Economic Indicators

-------
                                  Table B-l  CHEMICAL ENGINEERING PLANT COST INDEXES (cont'd)
INDEX
CE Plant Index
Engineering &
Supervision
Building
Construction Labor
Equipment, Machinery
Supports
Fabricated Equipment
Process Machinery
Pipe, Valves &
Fittings
Process Instruments &
Controls
Pumps & Compressors
Electrical Equipment
& Materials
Structural Supports
Insulation & Paint
1971
ANNUAL
132.3
111.4
135.5
146.2
130.4
130.3
127.1
137.3
139.9
133.2
98.7
126.6
JAN FEB MAR
128.2 129.1 129.9
111.1 111.2 111.2
130.0 131.5 132.9
142.5 143.3 142.8
125.7 126.7 128.0
125.5 125.6 127.9
125.4 125.7 126.3
131.0 132.0 132.7
134.0 138.6 139.3
129.1 135.8 135.8
101.1 100.2 99.2
120.1 120.6 123.6
APR MAY JUN
130.2 131.6 131.4
111.3 111.4 111.3
132.9 134.3 133.6
142.5 144.2 144.0
1.28.6 130.0 130.0
128.8 129.6 129.3
126.5 127.1 127.6
133.9 137.7 137.7
139.6 140.0 140.2
132.5 133.1 133.1
98.8 98.5 98.1
124.5 126.6 126.7
JUL AUG SEP
132.3 134.4 135.0
111.4 111.4 111.5
136.2 138.2 139.0
146.1 147.4 149.9
130.3 133.1 133.1
129.4 133.4 133.5
128.4 129.4 129.5
138.0 141.2 141.1
140.7 141.5 141.2
133.1 133.7 133.7
97.9 98.6 98.3
127.5 132.2 131.9
OCT NOV DFC
135.1 134.9 135.3
111.6 111.6 111.7
138.9 138.8 139.2
150.4 150.1 150.6
133.0 132.7 133.2
133.5 133.4 134.1
129.4 129.4 130.4
140.9 140.2 140./
141.2 141.1 141.5
133.7 132.4 132.4
98.3 97.7 97.7
131.9 131.9 132.0
DO
I

oo
            SOURCE:   Chemical  Engineering.  Economic Indicators

-------
                                   Table B-l  CHEMICAL ENGINEERING PLANT COST  INDEXES   (cont'd)
INDEX
CE Plant Index
Engineering &
Supervision
Building
Construction Labor
Equipment, Machinery
Supports
Fabricated Equipment
Process Machinery
Pipe, Valves &
Fittings
Process Instruments &
Controls
Pumps & Compressors
Electrical Equipment
& Materials
Structural Supports
Insulation & Paint
1970
ANNUAL
125.7
110.6
127.2
137.4
123.8
122.7
122.9
132.0
132.1
125.6
99.8
117.9
JAN FEB MAR
123.1 123.0 123.7
110.3 110.4 110.5
125.0 124.6 124.7
134.6 134.1 134.6
120.8 120.9 122.2
118.5 118.8 121.1
120.1 119.1 121.4
130.3 130.4 130.0
130.6 130.8 130.9
123.1 123.1 123.7
96.8 97.6 .98.3
114.7 114.9 116.7
APR MAY JUN
124.5 125.0 125.4
110.6 110.5 110.6
125.5 126.2 126.1
134.7 134.7 134.8
123.0 123.7 124.4
122.2 122.5 124.0
121.8 122.2 122.7
130.5 132.9 133.0
131.2 131.5 132.0
124.8 124.1 124.1
98.3 98.7 98.9
117.7 118.1 118.5
JUL AUG SEP
126.2 127.0 127.6
110.7 110.8 110.8
'127.4 128.6 130.1
136.6 139.0 141.4
124.9 125.1 125.1
124.1 124.2 123.8
123.3 123.5 124.8
133.8 133.9 132.4
132.0 132.6 133.6
125.6 125.6 129.1
100.8 101.5 .102.1
118.9 118.9 119.4
OCT NOV DEC
127.6 128.0 127.7
110.8 110.9 110.0
130.1 129.7 129.5
141.4 141.7 141.4
125.1 125.6 125.3
123.8 124.0 124.8
124.3 127.2 124.9
132.4 133.0 131.6
133.6 133.7 133.7
129.1 129.2 129.1
102.1 101.8 101.1
119.4 118.9 119.0
CO
I
ID
             SOURCE:  Chemical Engineering, Economic Indicators

-------
                                  Table B-l  CHEMICAL ENGINEERING PLANT COST INDEXES (cont'd)
INDEX
CE Plant Index
Engineering*&
Supervision
Building
Construction Labor
Equipment, Machinery
Supports
Fabricated Equipment
Process Machinery
Pipe, Valves &
Fittings
Process Instruments 8
Controls
Pumps & Compressors
Electrical Equipment
& Materials
Structural Supports
Insulation & Paint
1969 1968 1967
ANNUAL ANNUAL ANNUAL
119.0 113.6 109.7
110.9 108.6 107.9
122.5 115.7 110.3
128.3 120.9 115.8
116.6 111.5 107.7
115.1 109.9 106.2
116.3 112.1 108.7
123.1 117.4 113.0
126.1 120.9 115.2
119.6 115.2 111.3
92.8 91.4 90.1
112.5 105.7 102.1
1966 1965 1964
ANNUAL ANNUAL ANNUAL
107.2 104.2 103.3
106.9 105.6 104.2
107.9 104.5 103.3
112.5 109.5 108.5
105.3 102.1 101.2
104.8 103.4 102.7
106.1 103.6 102.5
109.6 103.0 101.6
110.0 106.5 105.8
107.7 103.4 101.0
86.4 84.1 85.5
101.0 98.8 98.3
1963 1962 1961 1960
ANNUAL ANNUAL ANNUAL ANNUAL
102.4 102.0 101.5 102.0
103.4 102.6 101.7 101.3
102.1 101.4 100.8 101.5
107.2 105.6 105.1 103.7
100.5 100.6 100.2 101.7
101.7 101.6 100.1 101.2
102.0 101.9 101.1 101.8
100.7 100.6 101.1 104.1
105.7 105.9 105.9 105.4
100.1 101.1 100.8 101.7
87.6 89.4 92.3 95.7
97.3 99.2 99.8 101.9
1959 1958 195;
ANNUAL ANNUAL ANNUAL
101.8 99.7 98.5
102.5 99.3 98.2
101.4 99.5 99.1
101.4 100.0 98.6
101.9 99.6 98.5
100.9 99.6 99.5
101.8 100.1 98.1
103.3 98.8 97.9
102.9 100.4 96.7
102.5 100.0 97.5
101.0 100.6 98.4
101.6 100.4 98.0
CD





O
            SOURCE:   Chemical  Engineering, Economic Indicators

-------
 MONTH
ANNUAL
                 Table B-2
                WHOLESALE PRICE  INDEXES
                FOR COTTON BROADWOVEN  GOODS,
                BLS 1 0312,  1967=100
1971
1972
1973
1974
110.6    122.3
         144.3
1975
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
DEC
108.0
108.2
108.5
109.0
109.8
111.0
112.1
112.2
111.6
111.6
112.1
113:1
116.9
118.0
119.6
120.5
121.5
122.9
123.3
123.1
124.4
125.2
125.7
126.4
127.7
130.3
132.0
135.8
137.8
141.8
146.2
147.7
152.0
154.4
160.6
165.5
170.6
172.4
173.0
174.8
174.7
184.4
188.5
185.4
184.6
178.3
176.0
171.1
167.3
163.3
161.3
163.9
168.6
' 170.6
173.7
175.7
176.6
189.2
195.3
199.6
         177.8    175.4
1976
1977
                                                        Discontinued
 MONTH
ANNUAL
                 Table B-3  WHOLESALE PRICE INDEXES
                            FOR MANMADE FIBER BROADWOVEN
                            GOODS, BLS #0334, 1967=100
1971
1972
1973
1974   S1975
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
DEC
94.1
94.0
94.6
96.8
99.2
102.4
103.6
106.0
106.1
105.1
106.7
109.3
111.5
112.5
112.7
114.9
116.6
118.0
118.6
118.4
118.2
118.3
120.3
122.4
124.7
125.8
133.0
139.4
145.3
147.7
147.1
147.8
152.8
154.9
156.6
158.4
159.7
161.5
161.7
162.7
168.3
'173.4
169.2
165.3
160.7
154.6
153.4
149.9
146.7
144.7
128.4
128.3
131.6
134.5
139.9
143.1
143.1
147.1
149.8
149.6
101.5
116.9    144.5    161.7   140.6
         1976
         1977
                                                         Discontinued
                              B-ll

-------
  MONTH
ANNUAL
 1971
                 Table B-4
 1972
                WHOLESALE PRICE  INDEXES FOR
                RUBBER AND PLASTIC PRODUCTS
                BLS # 07, 1967=100
 1973
 1974
1975
1976
1977
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
DEC
108.4
109.1
109.1
109.0
108.7
108.7
109.7
109.8
109.7
109.5
109.5
109.4
109.5
109.2
108.9
108.7
108.8
108.9
109.2
109.5
109.5
109.5
109.8
109.8
110.0
110.1
110.3
110.6
111.5
112.6
112.9
113.1
112.8
114.0
114.8
. 116.5
117.7
119.8
123.8
129.4
133.7
135.6
139.5
143.4
145.6
147.5
148.5
149.4
149.6
150.0
149.7
149.4
148.9
148.6
150.1
150.0
150.8
151.5
151.8
151.9
152.3
154.1
155.5
156.7
157.1
157.1
158.3
161.1
163.9
164.6
164.8
164.7
164.6
164.2
164.6
165.7
166.3
167.5
168.9
169.3
169.5
170.2
170.2
170.0
109.2    109.3    112.4    136.2   150.2    159.2    167.6
 MONTH
ANNUAL
                 Table B-5
1971
1972
                WHOLESALE PRICE INDEXES FOR
                CARBON STEEL PLATES,  A36
                BLS # 10130246, 1967=100
1973
1974    1975
        1976
132.3
141.0    146.7    181.6    213.2     228.2
        1977
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
DEC
119.0
119.0
128.8
128.8
128.8
128.8
128.8
141.0
141.0
141.0
141.0
141.0
141.0
141.0
141.0
141.0
141.0
141.0
141.0
141.0
141.0
141.0
141.0
141.0
146.7
146.7
146.7
146,7
146.7
146.7
146.7
146.7
146.7
146.7
146.7
146.7
152.1
152.1
161.3
161.3
173.3
173.4
199.7
199.7
201.7
201.7
201.7
201.7
212.9
212.9
212.9
212.9
212.9
212.9
208.9
207.8
207.8
218.8
218.8
218.8
219.8
219.8
219.8
219.8
219.8
219.8
219.8
240.2
240.2
240.2
240.2
240.2
240.2
240.2
240.2
240.2
240.2
240.2
256.5
256.5
256.5
256.5
256.5
256.5
                                  248.4
                             B-12

-------
 MONTH
ANNUAL
                 Table B-6
                WHOLESALE PRICE  INDEXES  FOR
                STAINLESS STEEL  PLATE
                BLS # 10130247,  1967=100
1971
1972
1973
1974    1975
1976
JAN
FEE
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
DEC
140.2
140.2
140.2
140.2
140.2
148.1
148.1
148.1
148.1
148.1
148.1
146:1
146.1
146.1
121.3
121.3
121.3
121.3
121.3
127.6
127.6
127.6
127.6
127.6
132.8
132.8
132.8
132.8
132.8
132.8
132.8
132.8
132.8
132.8
132.8
132.8
134.2
134.3
139.2
145.5
157.7
166.0
169.2
187.8
190.4
193.0
193.0
193.0
197.1
195.7
195.7
195.7
195.7
195.7
195.7
195.7
195.7
206.3
206.3
206.3
206.3
206.3
206.3
206.3
206.3
206.3
206.3
201.5
201.5
206.3
206.3
206.3
144.6    128.1    132.8    166.9   198.5    205.5
 MONTH

  JAN
  FEB
  MAR
  APR
  MAY
  JUN
  JUL
  AUG
  SEP
  OCT
  NOV
  DEC

ANNUAL
                 Table B-7  WHOLESALE PRICE INDEXES FOR
                            CARBON STEEL SHEET,
                            BLS #10130262, 1967=100
 1971
 1972    1973
         1974   S1975     1976      1977
119.5
119.5
119.5
119.5
119.5
119.5
127.5
127.5
127.5
127.5
127.5
127.5
124.1
134.5
134.5
134.5
134.5
134.5
134.5
134.5
134.5
134.5
134.5
134.5
134.5
134.5
134.5
134.5
134.5
134.5
134.5
134.5
134.5
137.5
137.5
137.5
137.5
137.5
142.0
146.6
155.8
'165.4
182.3
188.5
188.5
188.5
188.5
190.0
189.1
189.1
189.1
189.1
185.0
185.0
184.8
184.8
184.8
197.0
197.0
197.0
197.0
197.0
197.0
197.0
197.0
209.1
209.1
209.1
209.1
209.1
209.1
220.9
222.6
222.6
222.6
222.6
222.6
222.6
237.4
237.4
237.4
237.4
237.4
237.4
  123.5    133.6   135.3    167.6   189.3    205.0    230.0
                               B-13

-------
 MONTH

  JAN
  FEB
  MAR
  APR
  MAY
  JUN
  JUL
  AUG
  SEP
  OCT
  NOV
  DEC

ANNUAL
                  Table B-8  WHOLESALE PRICE INDEXES FOR
                             STAINLESS STEEL SHEET
                             BLS # 10130264, 1967=100
1971
1972    1973
1974    1975
1976
1977
130.8
130.8
130.8
130.8
130.8
138.1
138.1
138.1
138.1
138.1
138.1
137.1
137.1
137.1
138.1
138.1
138.1
120.4
120.4
117.5
117.5
117.5
117.5
117.5
117.5
117.5
117.5
117.5
123.4
124.5
124.5
124.5
124.5
124.5
124.6
• 124.6
126.8
128.6
134.9
140.1
153.6
159.6
163.9
173.1
174.9
174.9
175.8
178.9
178.9
169.6
169.3
169.3
169.3
162.6
162.9
162.9
162.9
162.4
156.9
156.7
162.6
162.6
164.2
164.2
164.2
164.2
164.2
174.4
176.3
176.3
176.3
176.3
185.0
186.6
186.6
186.6
200.1
203.4
205.6
205.6
202.7
202.7
200.3
200.3
135.0
126.4   122.1    157.1   165.3    168.8    197.1
 MONTH

  JAN
  FEB
  MAR
  APR
  MAY
  JUN
  JUL
  AUG
  SEP
  OCT
  NOV
  DEC

ANNUAL
                  Table B-9  WHOLESALE PRICE INDEXES FOR
                             PUMPS, COMPRESSORS,  AND EQUIPMENT
                             BLS # 1141, 1967=100
1971
1972    1973
1974    1975
1976
1977
119.3
120.0
120.5
121.6
121.9
121.9
121.9
122.3
122.3
122.6
122.2
122.2
122.4
123.2
123.5
123.5
123.0
124.2
124.9
124.6
124.6
124.7
124.8
124.8
125.0
125.1
125.2
125.9
126.2
127.7
127.5
127.7
127.6
128.6
131.4
131.7
132.1
133.4
135.5
138.7
142.5
147.7
154.0
162.7
163.8
168.8
176.8
179.5
180.5
184.3
184.4
186.2
187.3
187.3
187.9
188.8
189.2
189.9
191.3
191.1
192.2
194.9
195.8
196.2
195.9
197.4
197.5
198.5
199.6
200.9
201.4
203.6
205.5
205.3
206.4
206.6
209.2
210.3
212.9
213.7
215.1
216.0
218.5
219.1
121.6    124.0   127.5     153.0    187.4     197.8     211.6
                                B-14

-------
 MONTH

  JAN
  FEB
  MAR
  APR
  MAY
  JUN
  OUL
  AUG
  SEP
  OCT
  NOV
  DEC

ANNUAL
                  Table B-10  WHOLESALE  PRICE  INDEXES  FOR
                              V-BELT  SHEAVES
                              BLS *  11450133,  1967=100
1971
1972    1973
1974
1975    1976    1977
117.6
117.6
117.6
117.6
117.6
117.6
117.6
117.6
117.6
117.6
117.6
117*6
117.6
117.6
117.6
122.4
124.4
126.3
126.3
126.3
126.3
126.3
126.3
126.3
126.3
126.3
126.3
126.3
126.3
126.3
126.3
126.3
126.3
126.3
128.2
130.4
130.4
133.3
133.3
133.3
137.7
139.9
150.9
162.6
162.6
171.6
171.6
175.4
175.4
175.4
175.4
175.4
• 174.1
174.1
174.1
172.8
172.8
172.8
175.6
175.6
175.6
175.6
175.6
179.7
179.7
184.4
184.4
184.4
184.4
184.4
180.7
180.7
180.7
192.3
192.3
192.3
210.1
210.1
210.1
210.1
213.7
213.7
213.7
213.7
117.6
123.6   126.8    150.2   174.5   180.8   204.4
 MONTH

  JAN
  FEB
  MAR
  APR
  MAY
  JUN
  JUL
  AUG
  SEP
  OCT
  NOV
  DEC

ANNUAL
                  Table B-ll  WHOLESALE PRICE INDEXES FOR
                              FANS AND BLOWERS, EXCEPT PORTABLE
                              BLS # 1147, 1967=100
1971
1972    1973
1974
1975
1976    1977
120.8
121.0
123.1
122.2
122.2
124.6
124.9
124.9
125.3
125.3
125.3
125.5
125.6
127.3
128.6
128.8
128.8
128.8
128.8
. 128.8
129.9
130.0
130.0
122.4
132.4
132.6
133.1
134.4
134.4
135.0
135.0
135.2
137.5
137.7
137.6
137.6
138.2
138.5
145.5
146.4
158.6
' 171.8
178.6
183.2
185.3
188.6
192.3
192.6
197.9
198.2
198.6
198.8
201.3
202.4
205.4
205.4
205.8
206.4
206.6
206.5
206.5
207.1
210.1
213.9
214.1
214.2
216.0
216.0
216.1
221.7
221.7
221.9
224.7
226.4
226.8
224.1
224.8
228.8
230.5
231.1
233.7
233.9
233.9
234.4
123.8
129.0   135.2    168.3   202.8   214.9   229.4
                                B-15

-------
  MONTH

   JAN
   FEB
   MAR
   APR
   MAY
   JUN
   JUL
   AUG
   SEP
   OCT
   NOV
   DEC

 ANNUAL
                   Table  B-12   WHOLESALE  PRICE  INDEXES  FOR
                               MOTORS,  INTEGRAL  HORSEPOWER, A.C., 10 HP
                               BLS  #  11730112,  1967=100
     1971
 1972     1972
 1974
1975    1976    1977
122.1
113.6
109.1
104.0
104.0
104.0
102.2
101.6
101.6
101.6
101.6
101.6
99.6
99.6
99.6
101.1
105.6
105.6
105.6
105.6
105.6
105.6
111.5
111.5-
112.1
112.1
115.2
118.2
119.7
120.9
120.9
120.9
119.7
119.7
121.8
124.2
125.8
125.8
127.9
130.9
134.9
155.1
160.0
161.7
167.6
172.4
175.9
179.8
184.0
186.1
186.1
186.1
186.1
N/A
N/A
186.1
186.1
186.1
186.1
186.1
192.2
193.6
193.6
193.6
193.6
193.6
195.7
197.8
202.1
204.4
204.4
204.4
204.4
204.4
211.4
207.9
207.9
211.4
218.5
218.5
218.5
218 5
218.5
218.5
     105.6
104.7   118.8    151.5   185.9   197.4   213.2
    N/A = Not Available
 MONTH

  JAN
  FEB
  MAR
  APR
  MAY
  JUN
  JUL
  AUG
  SEP
  OCT
  NOV
  DEC

ANNUAL
                  Table B-13  WHOLESALE PRICE INDEXES FOR
                              MOTORS, INTEGRAL HORSEPOWER,  A.C.,  250 HP
                              BLS # 11730113, 1967=100
    1971
1972    1973
1974    1975
    N/A =
    128.3     127.8

Not Available
        136.3     142.8    N/A
       1976
                N/A
1977
123.9
123.9
123.9
125.6
129.0
129.0
130.7
130.7
130.7
130.7
130.7
130.7
125.1
.125.1
125.1
127.8
127.8
127.8
127.8
129.5
129.5
129.5
129.5
129.5
129.5
129.5
131.9
136.3
136.3
136.3
139.3
139.3
139.3
139.3
139.3
139.3
142.0
143.9
143.9
141.3
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
               N/A
                               B-16

-------
 MONTH

  JAN
  FEB
  MAR
  APR
  MAY
  JUN
  JUL
  AUG
  SEP
  OCT
  NOV
  DEC

ANNUAL
                  Table B-14  WHOLESALE PRICE INDEXES  FOR
                              MOTORS,  INTEGRAL HORSEPOWER, A.C.,  50  HP
                              BLS *  11730119, 1967=100
1971
1972    1973
1974    1975    1976    1977
115.1
98.9
98.9
98.2
98.2
98.2
95.9
95.2
95.2
95.2
95.2
95.2
99.6
99.6
99.6
101.5
105.6
105.6
105.6
105.6
105.6
105.6
111.5
111. .5
111.5
111.5
113.4
117.1
119.0
120.5
120.5
120.5
119.0
119.0
119.0
120.1
123.5
123.5
126.1
126.1
140.7
152.4
160.9
163.1
164.3
172.8
172.8
172.8
178.0
180.6
184.9
184.9
. 184.9
184.9
184.9
184.9
184.9
184.9
184.9
184.9
186.6
190.1
191.9
191.9
191.9
191.9
191.9
194.5
200.6
200.6
200.6
200.6
200.6
200.6
200.6
200.6
200.6
204.1
216.3
216.3
216.3
216.3
216.3
216.3
 98.3
104.7   117.6    149.9   184.0   194.4   208.7
 MONTH

  JAN
  FEB
  MAR
  APR
  MAY
  JUN
  JUL
  AUG
  SEP
  OCT
  NOV
  DEC

ANNUAL
                  Tabl* B-15  WHOLESALE PRICE INDEXES FOR
                              A.C. STARTERS, 75 HP, 440 VOLTS
                              BLS #11750781, 1967=100
1971
1972    1973
1974
^1975
1976    1977
106.8
105.5
105.5
105.5
105.5
105.5
105.7
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
112.4
115.4
116.1
116.1
116.1
123.4
' 130.0
132.0
132.0
133.0
141.0
143.7
143.7
143.7
143.7
143.7
143.7
143.7
143.7
143.7
143.7
147.0
N/A
150.3
146.7
152.0
152.0
152.0
150.0
152.0
152.0
152.0
152.0
155.0
163.3
163.3
163.3
163.3
163.2
163.2
163.2
163.2
163.2
163.2
163.2
166.2
173.8
176.3
176.3
108.5
112.4   112.4    128.5   144.9   154.9   166.5
                                B-17

-------
 MONTH

  JAN
  FEB
  MAR
  APR
  MAY
  JUN
  JUL
  AUG
  SEP
  OCT
  NOV
  DEC

ANNUAL
                  Table B-16  WHOLESALE PRICE INDEXES FOR
                              REFRACTORIES
                              BLS # 135, 1967=100
1971
1972    1973
1974    1975
        1976
1977
126.7
126.7
126.7
126.7
126.7
126.9
126.9
126.9
126.9
127.1
127.1
127.1
127.1
127.1
127.1
127.1
127.1
127.1
127.1
129.6
132.1
132.1
132.1
132.1 -
136.3
136.3
136.3
136.3
136.3
136.3
136.3
136.3
136.3
136.3
136.3
136.3
136.3
136.3
136.3
136.3
136.3
136.3
137.8
137.8
153.4
157.0
157.8
160.5
161.2
163.3
163.5
163.6
163.7
163.7
163.8
164.0
164.2
164.3
177.0
179.7
179.7
179.7
179.9
180.3
180.2
180.4
180.7
181.2
188.9
191.1
193.0
192.9
193.1
193.2
193.2
193.3
194.3
196.5
197.3
198.5
207.1
208.5
209.3
209.3
126.9
129.0   136.3    143.5   166.0   184.0   199.5
 MONTH
                  Table  B-17  WHOLESALE PRICE INDEXES FOR
                             FIRE CLAY BRICK, SUPER DUTY
                             BLS #  13520111, 1967=100
1971
1972    1973
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
DEC
ANNUAL
N/A =
129.0
129.0
129.0
129.0
129.0
129.0
129.0
129.0
129.0
129.0
129.0
129.0
129.0
Not Available
129.0
129.0
129.0
N/A
N/A
N/A
129.0
131.0
132.3
N/A
132.3
132.3
130.5

134.5
134.5
134.5
134.5
N/A
134.5
N/A
N/A
134.5
134.5
134.5
N/A
134.5

1974
1975    1976    1977
134.5
134.5
134.5
134.5
134.5
134.5
135.3
N/A
156.0
164.2
164.2
167.1
144.9
167.1
170.3
170.3
170.3
170.3
170.3
170.3
170.3
170.3
170.3
189.2
194.1
173.6
194.1
194.1
194.1
194.1
194.1
194.1
194.1
195.1
199.8
201.9
206.9
206.9
197.4
207.9
207.9
207.9
207.9
207.9
207.9
209.7
210.8
218.4
220.8
222.3
222.3
212.9
                                B-18

-------
  MONTH

   JAN
   FEB
   MAR
   APR
   MAY
   JUN
   JUL
   AUG
   SEP
   OCT
   NOV
   DEC

 ANNUAL
                  Table  B-18  WHOLESALE PRICE  INDEXES FOR
                              HIGH ALUMINA BRICK, 70 PCT.
                              BLS I  13520131,  1967=100
1971
121.1
1972    1973
1974    1975    1976     1977
119.8
119.8
119.8
119.8
119.8
121.5
121.5
121.5
121.5
122.7
122.7
122.7
122.7
122.7
122.7
N/A
N/A
N/A
122.7
130.4
134.5
N/A
134.5
134.5
146.9
146.9
146.9
146.9
N/A
146.9
N/A
N/A
146.9
146.9
146.9
N/A
146.9
146.9
146.9
146.9
146.9
146.9
154.6
N/A
170.4
178.7
178.7
181.2
183.4
189.0
189.0
190.1
190.1
190.1
190.1
192.4
192.4
192.4
209.3
211.5
211.5
211.5
212.9
212.9
212.9
212.9
215.5
215.5
219.3
221.1
224.7
224.7
224.7
224.7
224.7
224.7
227.6
229.6
229.6
229.6
240.0
242.6
244.5
244.5
128.1   146.9    158.6   193.3   216.3   232.2
     N/A = Not Available
 MONTH

  JAN
  FEB
  MAR
  APR
  MAY
  JUN
  JUL
  AUG
  SEP
  OCT
  NOV
  DEC

ANNUAL
                   Table B-19
1975    1976
      WHOLESALE PRICE INDEXES FOR
      CASTABLE REFRACTORIES
      BLS # 13520151, DEC 1974=100

      1977
100.8
100.8
100.8
101.9
101.9
101.9
101.9
102.7
102.7
102.7
105.3
108.6
102.7
109.9
109.9
110.0
110.0
110.0
110.0
110.0
110.8
112.3
113.2
116.2
116.2
111.6
116.9
116.9
116.9
116.9
116.9
116.9
117.6
117.6
123.2
123.2
125.1
125.1
119.4
                                  B-19

-------
 MONTH

  JAN
  FEB
  MAR
  APR
  MAY
  JUN
  JUL
  AUG
  SEP
  OCT
  NOV
  DEC

ANNUAL
                   Table 20  WHOLESALE PRICE INDEXES FOR
                             INSULATION MATERIALS
                             BLS #1392, 1967=100
 1971
 1972     1973
 1974
1975    1976    1977
126.2
126.2
126.2
126.2
134.5
134.5
134.5
134.5
134.5
134.5
134.5
134.5
. 134.5
134.5
134.5
134.5
142.7
138.8
136.8
136.8
137.5
137.5
137.5
137.5
137.5
137.5
138.4
138.4
138.4
138.4
138.4
138.4
135.0
135.0
135.0
137.9
139.2
139.2
139.2
139.9
146.9
149.8
152.0
156.0
169.6
169.6
187.2
189.2
189.7
189.7
189.7
189.7
189.7
194.1
203.0
203.0
201.4
201.4
201.4
201.4
201.4
201.4
215.7
210.6
210.5
210.5
210.2
210.2
219.1
220.6
220.6
220.6
223.1
223.1
228.2
228:2
228.2
236.4
238.1
238.7
251.7
244.9
245.3
244.5
 131.7
 136.9    137.4    150.5   192.2   212.6   235.9
  MONTH

   JAN
   FEB
   MAR
   APR
   MAY
   JUN
   JUL
   AUG
   SEP
   OCT
   NOV
   DEC

ANNUAL
                   Table  B-21   WHOLESALE PRICE  INDEXES FOR
                               NATURAL GAS
                               BLS #  05310101,  1967 = 100
1971
112.8
1972    1973
1974    1975    1976
121.0   131.3
               1977
109.5
107.9
109.7
110.8
112.2
113.0
113.0
112.6
114.2
114.7
114.7
113.5
116.3
116.6
117.6
119.6
120.3
120.2
120.6
122.1
122.8
123.9
125.9
126.2
125.1
125.4
125.8
127.4
129.1
130.1
131.1
133.3
135.8
135.9
135.4
141.5
140.9
145.0
147.8
148.4
149.8
151.7
152.6
154.3
159.8
162.1
173.1
175.3
180.5
190.5
190.0
205.8
222.0
219.7
228.3
223.1
229.4
229.5
225.7
239.5
236.1
236.1
248.5
257.0
259.8
273,0
279.0
294.1
294.3
356.8
408.1
360.6
331.1
384.2
392.8
405.0
420.2
410.3
N/A
N/A
N/A
N/A
N/A
N/A
155.1   215.3   292.0   N/A

       N/A  Not Available
                                 B-20

-------
 MONTH

  JAN
  FEE
  MAR
  APR
  MAY
  JUN
  JUL
  AUG
  SEP
  OCT
  NOV
  DEC

ANNUAL
                  Table B-22  WHOLESALE  PRICE  INDEXES  FOR
                              INDUSTRIAL POWER,  500  KWD
                              BLS # 0543, Dec  1967 = 100
1971
1972    1973
1974
1975    1976    1977
112.7
113.5
115.1
115.5
116.1
116.3
118.0
119.5
119.4
119.3
119.5
122.6 '
121.2
122.7
122.5
123.0
123.9
124.0
124.3
124.4
124.9
125.4
125.4
125.6
126.9
129.0
130.1
131.0
131.5
131.2
131.8
132.0
134.0
135.6
137.3
140.3
142.3
147.0
154.3
158.8
166.8
174.1
178.1
182.2
185.2
191.0
193.2
195.1
198.3
202.7
208.0
212.5
208.7
206.0
207.5
210.5
213.7
215.8
217.2
215.2
216.4
217.5
220.8
224.6
224.1
225.1
228.9
231.9
233.8
231.6
233.5
232.3
234.7
241.7
248.2
256.4
257.2
256.0
262.5
269.2
265.9
267.3
262.2
262.3
117.3    123.9   132.6    172.3   209.7   226.7   257.0
 MONTH

  JAN
  FEB
  MAR
  APR
  MAY
  JUN
  JUL
  AUG
  SEP
  OCT
  NOV
  DEC

ANNUAL
                  Table B-23  INDEXES OF AVERAGE  HOURLY  EARNINGS:
                              MANUFACTURING
                              1967 = 100
1971
1972    1973     1974  s 1975    1976    1977
132.1
132.7
133.2
133.6
134.5
135.0
135.5
136.1
136.8
137.5
138.0
138.8
139.5
139.7
140.4
141.1
141.8
142.7
143.7
144.5
145.4
146.5
147.0
147.9
148.7
149.6
150.6
151.7
153.5
. 155.5
156.6
158.0
159.6
161.3
162.5
163.7
164.8
166.1
167.7
168.6
169.7
171.0
172.2
173.3
174.5
176.0
177.0
177.4
178.8
180.0
180.9
181.9
182.5
183.6
185.3
186.6
188.0
188.4
189.8
191.0
192.3
193.4
194.3
195.6
196.9
198.5
200.3
201.2
202.7
204.2
205.4
206.3
129.3
129.0
131.3
127.5    135.4   143.6    156.0   171.5   184.7   199.3
   SOURCE:  U.S. Dept. of Commerce, Survey of Current Business
                                    B-21

-------
              APPENDIX C
GUIDE TO REFERENCES TO THE INDUSTRIES

-------
             LIST OF REFERENCES CROSS-INDEXED TO INDUSTRY SOURCE
INDUSTRY (or source of pollution)
Basic Oxygen Furnaces
Brick Manufacturing
Castable Refractories
Clay Refractories
Coal Fired Boilers

Conical Incinerators
Cotton Ginning
Detergent Manufacturing
Electric Arc Furnaces

Feed Mills
Ferroalloy Plants
Glass Manufacturing
Grey Iron Foundries

Iron & Steel (Sintering)

Kraft Recovery Furnaces

Lime Kilns
Municipal Incinerators

Petroleum Catalytic Cracking
Phosphate Fertilizer
Phosphate Rock Crushing
Polyvinyl Chloride Production
Portland Cement
Pulp and Paper (Fluidized Bed
    Reactor)
Secondary Aluminum Smelters
Secondary Copper Smelters
Sewage Sludge Incinerators
Surface Coatings - Spray Booths
List of References
5, 10, 11, 15, 24,  26,  34,  35,  36,  117
5, 24, 26, 35, 36,  82,  96,  97
5, 10, 26, 96, 97
5, 6, 24, 26, 36, 52,  96,  97
5, 6, 15, 24, 26, 34,  35,  36,  52,  61, 71,
76, 77, 83, 115, 123
5, 15, 26, 113, 116, 117
10, 26
5, 10, 24
5, 10, 11, 15, 16,  17,  24,  26,  28,  34,  35,
36, 67, 103, 104, 117
5, 10, 24, 26, 35,  78,  80,  117,  118
5, 10, 11, 15, 24,  26,  67,  82,  89,  99,  117, 167
24, 36, 117, 167
5, 6, 10, 15, 16, 17,  24,  26,  28,  32, 35,
37, 55, 78, 93, 101, 110,  117
5, 6, 10, 11, 15, 24,  26,  34,  35,  36, 37,
56, 82, 102, 103, 104,  105, 110, 117
1, 2, 3, 5, 10, 26, 27, 30, 31,  34, 3;,  63,
64, 72, 82, 90, 112, 117,  167
4, 6, 15, 19, 26, 35,  78
6, 15, 25, 26, 34,  58,  92,  94,  106, 107, 114,
115, 116, 117
5, 6, 15, 26, 34, 35,  37,  42,  82,  109.  117
5, 6, 10, 24, 26, 34,  35,  37,  78,  117
5, 24, 26, 34, 36,  117
5, 10, 24, 36, 37,  43
5, 6, 12, 15, 24, 26,  34,  35,  36,  74, 98, 11
1, 2, 3, 5, 10, 15, 27, 30, 31,  34, 63,  64,
90, 101, 112, 117
5, 13, 15, 19, 26,  34,  35,  36,  69,  95,  117
5, 15, 19, 26, 34,  35,  36,  69,  95,  100   117
5, 15, 26, 59, 114, 116, 117
24, 35, 37, 40, 42, 45, 57, 115
Multi-Industry General Articles
7, 8, 9, 14, 20-23, 24,  30,  33,  34,  37,  38,
39, 40, 41, 44, 46-51,  53,  54,  60, 61, 62,
65, 66, 68, 70, 71, 73,  75,  78,  79,  81,  82,
84, 85, 86, 87, 88, 91,  111, 115,  119-122,
124-127, 128, 129, 130,  131  , 132, 133, 134,
136, 137,  143, 144, 145, 148
                                  C-l

-------
                             LIST OF REFERENCES
Source
  No.
Title
APT 1C
 No.
NTIS
 No.
   1       Anon., "Control  of Atmospheric Emissions in       21385
          the Wood Pulping Industry",  Vol.  1,  Mar. 15,
          1970.   Contract  No.  CPA 22-69-18, NAPCA.

   2       Ibid Item #1, Vol.  3.                              21724

   3       Ibid Item #1, Vol.  2.                              21728

   4       Minnick, L.  J.,  "Control  of  Particulate           27434
          Emissions From Lime  Plants", June 14,  1970.
          63rd Annual  Meeting  APCA  Paper 70-73.

   5       Billings, C.  E.  and  Wilder,  J.  E.,  "Engineering    28580
          Analysis of  the  Field  Performance of Fabric
          Filter Systems",  June  14,  1970.   63rd  Annual
          Meeting APCA Paper  70-129 (performed under
          NAPCA Contract CPA  22-69-38).

   6       Anon., "Efficiency  Versus  Particle Size and        28821
          Approximate  Cost Information of Mechanical
          Collectors",  IGCI Pub.  Ml, Jan. 1968.

   7       Heneghan, W.  F.,  "Activated  Carbon - A Final       29088
          Filter", Pollution  Engineering, Jan/Feb,  1970,
          pp.  18-20.

   8       Ashman, R.,  "A Practical  Guide  to  Industrial       29089
          Dust Control", JIHVE,  Mar. 1971,  Vol.  38,
          pp.  273-282.

   9       Anderson, L.  W.,  "Odor  Control  in Rendering        29261
          by  Wet Scrubbing  - A Case  History";  1970,
          Carolina By-Products Company, Greensboro,  N.C.

  10       Anon,, "Pollution Control  Update, 1970", McGraw-   30462
          Hill,  Modern  Manufacturing,  July 1970, 6 pp.

  11       Vaiga, J., et al., "A  Systems Analysis  of  the      30698
          Iron & Steel  Industry", Battelle, May,  1969.

  12       Walling, I.  C.,  "Cement Plant Dust Collectors",    31538
          Pit &  Quarry,  July,  1971,  64(1):143-148.

  13       Cook,  C.  C.,  et al., "Operating Experience         31567
          With the Alcoa 398 Process for  Fluoride
          Recovery", Alcoa, Journal of the Air Pollu-
          tion Control Assoc., 21(8);479-483. Aug. 1971.
                                          184577
                                     C-2

-------
Source
  No.
                               Title
APTIC
 No.
NT IS
 No.
14      Wright T.  J., et al., "A Model for Estimating
        Air Pollution Control Costs", TRW, 64th Annual
        Meeting APCA, June 27, 1971, Paper 71-144.
        Work performed under Contract PH 22-68-60 (EPA).

15      Anon., "An Electrostatic Precipitator Systems
        Study", SRI, Oct. 1970, NAPCA Contract CPA 22-
        69-73.

16      Anon., "Systems Analysis of Emissions and
        Emissions Control in the Iron Foundry Industry",
        Vol. II, Feb. 1971, EPA Contract CPA 22-69-106,
        A. T. Kearney & Co., Inc.

17      Ibid Item 16, Vol. I. .

18      Ibid Item 16, Vol. III.

19      Anon., "Study of Technical and Cost Information
        for Gas Cleaning Equipment in the Lime and
        Secondary Non-Ferrous Metallurgical Industries",
        IGCI, NAPCA Contract CPA 70-150, Dec., 1970.

20      Anon., "Fabric Filter Systems Study", Vol. II,
        GCA Corp., Dec. 1970, NAPCA Contract CPA 22-69-
        38.

21      Ibid Item 20, Vol. I.

22      Ibid Item 20, Vol. IV.

23      Ibid Item 20, Vol. III.

24      Anon., "Air Pollution Control: A Practical Guide
        to  Information Sources for Business, Industry,
        and Municipalities", Purdue University Libraries
        Industrial and Technical Information Service, Apr.,
        1974.  Bibliography  listing of sources.

25      Stear, J. R., "Municipal Incineration: A Review of
        the Literature", .EPA, June, 1971, Office of Air
        Programs, RTP.

26      Anon., "Particulate  Pollutant Systems Study",
        Vol. Ill, Handbook of Emission Properties, EPA
        Contract CPA 22-69-104, May,  1971, MRI.

27      Weiner, J. and Roth, L., "Air Pollution in the
       . Pulp & Paper Industry", The Institute of Paper
        Chemistry, Bibliographic Series No. 237, Sup-
        plement I, 1970.
                                                                 31747
                                                                 32021    198150
                                                                 32247    198349
                                                                 32251    198348

                                                                 32252    198350

                                                                 32248    198137
                                                                 34691    200649
                                                                 34698

                                                                 34799

                                                                 34799

                                                                 34894
         200643

         200651

         200650
                                                                 34955    200514
                                                                 35574    2035?2
                                                                 35581
                                          C-3

-------
Source
  No.
Title
APT 1C
 No.
NTIS
 No.
  28      Greenberg,  J.  H.,  "Systems Analysis of Emissions:       35925
          The Iron Foundry  Industry", Chem Tech 1(12):  728-
          736, Dec.  1971.

  29      Victor,  I., "Control  of Gases  and Vapor Emissions       37254
          From Industrial and Dry Cleaning Processes  Com-
          paring Efficiency  and Operating  Cost of Incineration,
          Absorption, Condensation and Absorption Methods",
          Dec.,  1971, Conference paper preprint, U.  S.  Dept.
          of Commerce and WPCF.

  30      Mueller,  J.  H., "Fume and Odor Control  Systems          38195
          Compared  and Analyzed",  Wood & Wood Products,
          76(3): 48-50,  Mar.,  1971.

  31       Anon.,  "Harmonizing  Pulp and Paper  Industry with        59245
          Environment",  Proc.  of XV EUCEPA Conference,  Rome,
          May 7,  1973.

  32       Anon., "Economic Impact  of Air Pollution Controls                196500
          on Gray  Iron Foundry  Industry",  NAPCA  Pub. AP 74,
          Nov.,  1970.

  33       Oglesby, Sabert, et al.,  "A Manual  of  Electrostatic              196380
          Precipitator Technology,  Part  I  - Fundamentals",
          SRI, PHS CPA 22-69-73, Aug.  25,  1973.

  34       Ibid Item 33,  Part  II, Application  Areas.                        196381

  35       Anderson, H. S., et al.,  "User's Manual, Automated               198779
          Procedures  for Estimating  Control Costs and Emission
          Reductions,  Etc.", RTI,  PHS CPA 70-60, 1970.

  36       Anon., "Engineering and  Cost Effectiveness Study of              207506
          Fluoride Emissions Control", Jan. 1972, Vol. I, EPA
          Contract EHSD  71-14.

  37       Rolke, R. W.,  et al.,  "Afterburner  Systems Study",                21^:560
          EPA EHSD 71-3, Aug. 1972.
   *
  38       Calvert, J., et al., "Wet  Scrubber  System Study",                213016
          Vol. I, Scrubber Handbook, APT,  Inc.,EPA R2 72 118A, CPA
          70-95, July, 1972.

  39       Ibid Item 38,  Vol.  II, Final Report and Bibliography.            213017

  40       Juhola, A. J., "Package  Sorption Device System Study",           221138
          MSA Res. Corp., EPA R2 73  202,  EHSD 71-2, Apr. 1973.
                                    C-4

-------
Source
  No.
Title
                                                               APT 1C
                                                                No.
NTIS
 No.
41      Anon., "Proceedings of a Symposium on Control of                235829
        Fine-Particulate Emissions, Etc.", 1974, U.S.-U.S.S.R.
        Working Group Stationary Source Air Pol. Control Technology.

42      Anon., "Systems and Costs to Control Hydrocarbon                236921
        Emissions from Stationary Sources.

43      Carpenter, B. H., "Vinyl Chloride; An Assessment                237343
        of Emissions Control Techniques and Costs", RTPf
        EPA/650/2.  74097 EPA 68-02-1325, Sept., 1974.

44      Anon., "Proceedings, Symposium on the Use of Fabric             237629
        Filters for the Control of Sub-Micron Particulates",
        EPA 650-2-74-043, EPA 68-02-1316, Meeting, 1974.

45      Dowd, E. J., "Air Pollution Control Engineering and             238058
        Cost Study of the Paint and Varnish Industry",
        ARI, EPA 450-3-74-031, EPA 68-02-0259, June, 1974.

46      Anon., "Air Pollution: Control Techniques for                   240578
        Nitrogen Oxide", NATO Comm. on the Challenge of
        Modern Society, NATO CCMS 20, Oct., 1973.

47      Ibid Item 46, Hydrocarbon and Organic Sol vent,CCMS 19.          240577

48      Ibid Item 46, Carbon Monoxide, CCMS 18.                         240576

49      Ibid Item 46, Particulates, CCMS  13,            s               240573

50      Ibid Item 46, Sulfur Oxide, CCMS  12.                            240572

51      "Control Techniques For Particulate Air Pollutants",            190253
        USNGW, 1969, AP-51.

52      "Sulfur Codes Pose Dilemma for Coal", Envir. Sci.      37826
        Tech., 4(12):1104-1106, Dec., 1970.

53      Diamant, R. M. E., "The Prevention of Pollution,       38620
        Part XII", Heating and Ventilating Eng.,
        4-5(535): 398-406, Feb., 1972.

54      "Low Cost Electrostatic Precipitation", Filtration     38088
        Separation, 9(1): 52-59 Jan/Feb,  1972.

55      Anon., "Ford's Michigan Casting Center, Environmental  37498
        Control", Foundry, 100(3): F8-F11, Mar., 1972.

56
          Anon.,  "When  It Comes to Pollution Control, Steel
          Isn't Dawdling- It's Acting", 33 Mag. 10(1): 23-29,
          Jan., 1972.
                                  36286
                                      C-5

-------
Source
  No.
                     Title
APTIC
 No.
NTIS
 No.
 57
 58
 59
 Hayes,  C.  T.,  "Cut  Industrial  Pollution  by
 Eliminating  Gaseous  Waste", Automation,
 Cleveland  18(3):64-G5,  Mar.,  1971.
36516
 60
 61
 62
 63
 64
 65


 66


 67



 68



 69
 Fife, J. A.,  "Design of  the Northwest  Incinera-    28261
 tor  for the City of Chicago",  Proc. of Nat'l.
 Incinerator Conf., Cincinnati, Ohio, 1970, pp. 149-160.

 Sebastian, F. P. and Isheim, M. C., "Advances      28262
 in Incineration and Resource Reclamation",
 Proc. of Nat'l. Incinerator Conf., Cincinnati,
 Ohio, 1970, pp. 71-78.

 Mueller, J. H., "Cost Comparison for Burning       34716
 Fumes and Odors", Pollution Eng. 3(6):18-30,
 Nov/Dec, 1971.

 Jaeger, W. and Keilpart, T., "Pollution Control    31915
 Can  Pay Its Way - Even When Retrofit", Elec.
 Light Power, 48(6):73-75, June, 1970.   	

 Ottaviano, V.  B. and Lazan, S., "Air Pollution     31805
 Abatement Market for the Sheet Metal  Industry",
 Heating Air Conditioning Contractors, Vol.
 62:26-31, Aug., 1971.

 Burgess, T. L., et al.,  "Incineration of Malodor-  63161
 ous  Gases in Kraft Pulp Mills", Pulp Paper
 Mag.  Can., 75(5):92-96, May, 1975:

 Roberson, J.  E., et al., "The NAPCA Study of the   28095
 Control  of Atmospheric Emissions in the Wood
 Pulping Industry", TAPPI, 54(2): 239-244, Feb.,
 1971.

 Jones, A.  H.,  "The Basics of Dust Collection",    27279
 Plant Eng., 25(4):71-73, Feb.  18, 1971

 Ellison, W.,  "Wet Scrubbers Popular for Air       27282
 Cleaning", Power.  115(2):62-63, Feb.,  1971.

 Person,  R.  A., "Control of Emissions  from         29325
 Ferroalloy Furnace Processing", J.  Metals,
 23(4):17-29,  Apr., 1971.

 Mueller, J. H.,  "What It Costs  to Control         29299
 Process  Odors",  Food Eng.. 43(4):62-65, Apr.,
 1971.

 Swan,*D.,  "Study of Costs for Complying with      29376
 Standards for  'Control  of Sulfur Oxide  Emissions
 from Smelters",  Mining Congr.  J..  57(4):76-85,
Apr., 1971.
                                   C-6

-------
Source
  No.
Title
APT 1C
 No.
NFIS
 No.
  70      Calvert, Seymour, "Source Control by Liquid Scrubr     30868
          bing", In: Air Pollution, Arthur C. Stern (Ed.),
          Vol. 3, 2nd Ed., N.Y., Academic Press, 1968.

  71      Olds, F. C., "SO, Control: Focusing on New Targets",   31673
          Power Eng.. 75(8):24-29, Aug., 1971.

  72      Lardieri, N. T., "Present Treatment Practices in       35660
          Kraft Mills of Air-borne Effluents", Paper Trade
          J.., 142(15):28-33, 14 April, 1958.

  73      Taylor, D. H., "Recommendations for Dust Collection    35087
          Systems", Metal Progr. 98(6):63, Dec., 1970.

  74      Van DeWouwer, R., "Clinker Cooler Dust Collector       35990
          Recovers 60 TPD at Inland's Winnepeg Plant", Pit
          Quarry. 64(7):104-105, Jan., 1972.

  75      Alonso, J. R.F., "Estimating the Costs of Gas          35532
          Cleaning Plants", Chem. Eng.. 78(28):86-96.

  76      Benson, J. R. and Corn. M.,  "Costs of Air Cleaning     61840
          with Electrostatic Precipitators at TVA Steam Plants",
          J. Air Pollution Control Assoc.. 24(4):340-348, Apr.,
          1974, 7 Refs.

  77      Selzler, David R. and Watson, W. D., "Hot Versus S     58903
          Enlarged Electrostatic Precipitation of Fly Ash:
          A Cost-Effectiveness Study". J. Air Poll. Control
          Assoc., 24(2): 115-121, Feb., 1974, 25 Refs.

  78      Hardison, L.C.,  "Air Pollution Control Technology      62087
          and Costs in Seven Selected  Industries (Final Report}',
          Industrial Gas Cleaning Institute, Stamford, Conn.
          Office of Air and Water Programs, Contract 6b-02-
          0289, Rept. EPA-450/3-73-010, IGCI Rept. 47-173,
          724 p., Dec. 1973, 82 Refs.

  79      Nichols, Richard A., "Hydrocarbon-Vapor Recovery"      60808
          Chem. Eng.. 80(6):85-92, 5 Mar., 1973.  Presented
          at the Petroleum Mech. Engrg.Conf., New Orleans, La.,
          Sept. 17-21, 1972.'

  80      Shannon, Larry J.; Gerstle,  Richard W.; Gorman,        59566
          P. G.; Epp, P.G.; Devitt, T. W.; Amick, R.,
          "Emissions Control in the Grain and Feed Industry.
          Vol. I- Engineering and Cost Study", Midwest Res.
          Inst., Kansas City, Mo., Office of Air Quality
          Planning and Standards, Contract 68-02-0213, Rept.
          EPA 450/3-73-003a, 583 pp.,  Dec., 1973, 128 Refs.
                                   C-7

-------
Source                                                      APTIC     NTIS
 _Nu^_                    Title                              No.        No.


  81       Larson,  Dennis M.,  "Control  of Organic Solvent    56967
          Emissions by Activated Carbon", Metal  Finishing,
          71(12):62-65, 70,  Dec., 1973,  4 Refs.

  82       Hardison, L.C.  and  Greathouse,  Carroll A.,  "Air   57616
          Pollution Control  Technology and Costs in Nine
          Selected Areas (Final  Report)", Industrial
          Gas  Cleaning Inst.,  Stamford,  Conn.,  EPA Contract
          68-02-0301,APTD-1555,  616  pp.,  Sept.30,  1972,
          74 Refs.

  83       Schultz,  E.  A.;  Miller, W.E.;  Barnard, R.  E.;      60847
          and  Horlacher,  W.  R.,  "The Cat-Ox Project at
          Illinois  Power", Proc.  Am. Power Conf.,  Vol. 34:
          484-490,  April,  1972.

  84       Stout, Bruce G., "Selection  of  Air Pollution       62011
          Control  Equipment", Army Logistics Management
          Center,  Texarkana, Tex., Product/Production
          Engineering  Program.   Training  Center  Rept.
          USAMC-ITC-2-71-12, 82  pp., Julyr 1971,  13 Refs.

  85       Bagwell,  F.  A., Cox,  L.  F. and  Pirsh,  E. A.,       58729
          "Flue-Gas Filtering Proves Practical on  Oil-
          F.ired Unit",  Elec. World.  171 (10):26-27. Mar.  10,
          1969.

  86       Cosby, W. T.  and Punch,  G.,  "Cost  and  Perform-     57907
          ance of  Filtration and  Separation  Equipment,
          Dust Filters  and Collectors", Filtration
          Separation (Purley).  5(3):252-255,  May/June,
          1968, 1 Ref.

  87       Squires,  B.  J., "New Developments  in the Use of    57370
          Fabric Filter Dust Collectors",  Filtration Separa-
          tion (Purley). 6(2):161-170, Mar/Apr,  1969, 5 Refs.
          Presented at  the Filtration  Society, London,
          10 Sept., 1968.

  88       Daniel son, J. A., "Ai'r  Pollution Engineering
          Manual",  Air  Pollution Control  District County of
          Los Angeles,  U. S.  Environmental Protection Agency,
          Pub.  No. AP-40, May, 1973.

  89       Dealy, J. 0.  and Killin, A.  M.,  "Engineering and
          Cost Study of the Ferroalloy Industry", U. S.
          EPA,  EPA  450/2-74-008, May,  1974.

  90       Hendrjckson,  E. R., et al.,  "Control of Atmos-
          pheric Emission in the Wood  Pulping Industry",
          Environmental Engineers, Inc. and J. E. Sirrine Co.,
          Contract  No.  CPA 22-69-18, March.  1970, Report PB
          190-351.


                                    C-8

-------
Source                                                           APT1C    NTIS
  No.                        Title                                 No.       No.


  91      Cadman, T. W., "Elements of Pollution Control
          Economics", ICARUS Corp., Dec., 1973.

  92      "Interim Guide of Good Practice for Incineration at
          Federal Facilities", U. S. Dept. of Health, Education,
          and Welfare, Nov., 1969.

  93      Cowen, P. S., "Cupola Emission Control", Gray and
          Ductile Iron Founder's Society, Cleveland, Ohio,
          1967.

  94      Fernandas, J. H., "Incineration Air Pollution Control",
          Proceedings of1968 National Incinerator Conference,
          New York, N. Y., American Society of Mechanical Engi-
          neers, pp. 101-115.

  95      Anon., "Economic Impact of Proposed Water Pollution
          Controls  on the Nonferrous Metals Manufacturing
          Industry"- Phase II, Environmental Protection Agency,
          EPA-230/1-75-041, March,  1975.

  96      Anon., "Development Document for Effluent Limitations
          Guidelines and Standards  of Performance", Versar, Inc.,
          April, 1975, The Clay,  Gypsum, Refractory, and
          Ceramic Products Industries, Office of Water and
          Hazardous Materials, EPA, Contract No. 68-01-2633.

  97      Ibid  Item 96, Volume III, December 1974.      s

  98      Kreichelt, T. E., et al., "Atmospheric Emissions from
          the Manufacture of Portland Cement", U. S. Dept. of
          Health, Education, and Welfare, 1967.                            PBir)23c,

  99      Anon., "Development Document for Interim Final
          Effluent  Limitations Guidelines and Proposed New
          Source Performance Standards for the Calcium Carbide
          Segment of the Ferroalloy Manufacturing Point Source
          Category',1 U. S. Environmental Protection Agency,
          February  1975, EPA 440/1-75/038, Group I, Phase II.

 100      Anon., "Development Document for Proposed Effluent
          Limitations Guidelines  and New Source Performance
          Standards for the Secondary Copper Subcategory of the
          Copper Segment of the Nonferrous Metals Manufacturing
          Point Source Category,  U. S. Environmental Protection
          Agency, November 1974, EPA 440/1-75/032-c, Group I,
          Phase II.
                                       C-9

-------
Source
  NCK

 101
 102
 103
 104


 105
 106



 107



 10R
 109
 110
 111
APTIC
 No.
                      Title

Coughlin, R.W., et al., "Air Pollution and  Its
Control", American Institute of Chemical Engi-
neers, Symposium Series 1972, Volume 68, No. 126.

Anon., "Development Document for Proposed Effluent
Limitations Guidelines and New Source Performance
Standards for the Steel Making Segment of the Iron
& Steel Manufacturing Point Source Category, U. S.
Environmental Protection Agency, January, 1974,
EPA 440/1-73/024.

Anon., "Background Information for Standards of
Performance: Electric Arc Furnaces in the Steel
Industry", Volume 1 - Proposed Standards, October,
1974.

Ibid Item 103, Volume 2 - Test Data Summary,
Report No. EPA-450/2-74-017b.
Anon., "Economic Analysis of the Proposed Effluent
Guidelines for the Integrated Iron and Steel Industry",
February, 1974, Environmental Protection Agency,
Report No. EPA-230/1-73-027, A.  J. Kearny, Contract
No. 68-01-1545.

Anon., Municipal Refuse Disposal, Institute for Solid
Wastes of American Public Works  Association, 1970,
Public Administration Service, Chicago, Illinois.

Anon., 1968 National  Incinerator Conference, New York,
N. Y., Sponsored by ASME Incinerator Division.
Breaux, James C., Control of Particulate Matter in
Asphalt Plants.  Preprint, Louisiana Tech.  Univ.,
Continuing Engineering Education Div., pp.  80-91,
1970 (Presented at the Institute on Aspects of Air
Pollution Control, Ruston, LA, Oct. 8-9, 1970)
                                                              57401
American Petroleum Inst., Wash. D. C., Committee
on Refinery Environmental Control, Hydrocarbon
Emissions From Refineries.  # Pub-928, 64 p.,
July, 1973.

Remmers, K.» Dust Extraction From Cupolas by
Means of Venturi Tube Scrubbers, Giesserei
(Duesseldorf), 52(7): 191-193, April 1, 1965,
Translated from German, 11 p.

Cheremisinoff, Paul N., "Wet Scrubbers - A Special
Report", Pollution Engineering, May, 1974,
pp. 33-43.
NTIS
 No.
           PB 237840
           PB  237841
                                                             59178
                                                              61061
                                      C-10

-------
Source                                                                APTIC     NTIS
  No.                                Title                              No.        No.


  112       Bunyard, F. L., "Pollution Control for the Kraft Pulping
            Industry: Cost and Impact", Annual Meeting of the Air
            Pollution Control Association, June 14-19, 1970,
            APCA #70-74.

  113       Vickerson, George L., "Fly Ash Control Equipment for
            Industrial Incinerators", Proc. 1966 ASME Incinerator Conf.

  114       Guccione, Eugene, "Incineration Slashes Costs of Sewage
            Disposal", Chemical Engineering, Apr. 11, 1966, pp.144-146.

  115       "New Developments in Air Pollution Control", Proc. MECAR
            Symposium, New York, N.Y., Oct. 23, 1967-

  116       Corey,  Richard,  Principles and Practices of  Incineration,
            Wiley-Interscience, New York, N.Y., 1969.

  117       Stern,  Arthur C., Air Pollution, 2nd Ed., Vol. II & III,
            Academic Press,  New York, 1968.

  118       Smith,  Kenneth D., "Particulate Emissions from Alfalfa
            Dehydrating Plants — Control Costs and Effectiveness",
            EPA-650/2-74-007, Jan., 1974.

  119       "Capital and Operating Costs of Pollution Control Equip-            224-53f
            ment Modules", Vol. I & II, EPA-R5-73-023a & b, July,               224-53t
            1973.

  120       Liptak, B. 6., Environmental Engineers Handbook, Radnor,
            Chi 1 ton Book, 1974, 1340 p.

  121       Fraser, M. D. and Foley, G. J., Cost Models for Fabric
            Filter  Systems.   In: The 67th Annual Meeting of the Air
            Pollution Control Association, Denver, June, 1974, APCA
            # 74-96.

  122       Reigel, S. A., Bundy, R. P. and Doyle, C. D.  Baghouses -
            What to Know Before You Buy.  Pollution Engineering.
            1:32-34, May, 1973.                           ;

  123       Walker, A. B.  Experience with Hot Electrostatic Precipi-
            tators  for Fly Ash Collection in Electric Utilities.
            In: American Power Conference, Chicago, Research-
            Cottrell, Inc., April 29-May 1, 1974.

  124       Alfonso, J. R. F. Estimating the Costs of Gas Cleaning
            Plants.  Chemical Engineering, December 13, 1971, pp.  86-96.

  125       Schneider, G. G., Horzella, T. I., Cooper, J. and
            P. J. Striegl.  Selecting and Specifying Electrostatic
            Precipitators.  Chemical Engineering.  82 11:94-108,  May,
            1975.                                  ~~


                                         C-ll

-------
Source                                                        APTIC     NTIS
  No.                               Title                       No.        No.


  126       Anon.  Survey of Electrostatic Precipitator
            Operating and Maintenance Costs.   Water and Sewage
            Works, Reference Number - 1971, Aug.  31,  1971,
            pp.  R236-R237.

  1?7       Rymarz,  J.  *!.  and Klipstein,  D. H.   Removing Particulates
            From Gases.   Chemical  Engineering.   82  (21):  113-120,
            October, 1975.

  128       "Estimating Costs and  Manpower Requirements for Con-
            ventional  Wastewater Treatment Facilities",
            EPA  17090 DAN 10/71.                                       PB  211132

  129       Jorgensen,  Robert, Editor,  "Fan Engineering"; 6th  Ed.,
            Buffalo  Forge Company, New York,  1961.

  130       Arnold,  T.  H.  and Chilton,  C.  H.,  New Index Shows
            Plant Cost  Trends, Chemical  Engineering.
            Feb.  18, 1963,  pp. 143-149.

  131        Economic Indicators, Chemical  Engineering,  Every Issue.

  132        Gorman,  P.  G.,  "Control  Technology For Asphalt  Roofing
            Industry",  Midwest Research  Institute, Kansas City, Mo.,
            EPA  Contract  68-02-1324,  Rept. EPA 600/2-76-120, April  1976.

  133        Parsons, T. B.,  Shirley,  T. E., Piana, M. B., "Hydrocarbon
            Control  Cost  Effectiveness Analysis for Nashville, Tenn.,"
            Radian!Corporation, Austin, TX., EPA  Contract 68-02-2608,
            Rept.  EPA 904/9-78-003,  February, 1978.

  134        Burklin, C. E.,  Colley, S. D., Owen, M. L., "Background
            Information on Hydrocarbon Emissions From Marine Terminal
            Operations, Volume  I,  Discussion", Radian Corp., Austin,
            TX., EPA Contract  68-02-1319, Rept, EPA 450/3-76-038a,
            November, 1976.

  135        IBID Item 134, Volume  II, Appendices, Rept. EPA 450/
            3-76-0385.

  136        Pitruzzello, V. J., "The Control  of Hydrocarbon  Emissions
            From Gasoline Marketing Operations," EPA, Proceedings  of
            Air Pollution Control Association Annual Meeting, June, 1977.
                                       C-12

-------
Source                                                       APTIC
  No.                              Title                      No.
  137       Burklin, C. E., Cavanaugh, E. C., Dicker-man, J.  C.,
            Fernandes, S. R., "A Study of Vapor Control  Methods
            For Gasoline Marketing Operations: Volume I  -
            Industry Survey and Control Techniques," Radian  Corp.
            Austin, TX, EPA Contract 68-02-1319, Rept.  EPA
            450/3-75-046a, April, 1975.

  138       Klett, M. G., Galeski, J. B., "Flare Systems Study",
            Lockheed Missiles and Space Co., Huntsvilie, AL,
            EPA Contract 68-02-1331, Rept. EPA 600/2-76-079,
            March, 1976.

  139       Mcllvaine,  R. W., Ardell, M., "Research and Develop-
            ment and Cost Projections for Air Pollution Control
            Equipment," The Mcllvaine Co., Northbrook, IL, EPA
            P.O. DA-7-6086A, Rept. EPA-600/7-78-092, June, 1978.

  140       Bellegia,  F. L., Mathews, J.  D., Paddock, R. E.,
            Wisler, M.  M., "Update and Improvement of the Control
            Cost Segment of the  Implementation Planning Program",
            EPA Contact 68-02-0607, February, 1975.
   141       Anon.,  "Report of Fuel Requirements, Capital Cost
            and Operating Expense for Catalytic and Thermal
            Afterburners", CE Air Preheater Industrial Gas
            Cleaning  Institute, Stamford, Conn., EPA Contract
            68-02-1473,  Rept. EPA 450/3-76-031, September, 1976.

   142       Bryan,  R.  J., Yamada, M. M., Norton, R. L., Kokin, A.,
            "Evaluation  of Top Loading Vapor Balance Systems For
            Small Bulk Plants", EPA Contract 68-01-4140, Rept.
            EPA 340/1-77-014, April, 1977.

   143       Gammell,  D.  M.,  "Emission Control Technology For
            Marine  Terminals Handling Crudes and Gasoline",
            Robert  Brown Assoc., Carson, CA., EPA Contract
            68-02-2838,  March, 1978.

   144       Gisser, P.,  "Benzene Emission Control Costs In
            Selected  Segments of the Chemical Industry", Booz,
            Allen & Hamilton, Inc., Florham Park, N.J., Manu-
            facturing Chemists Association, Washington, D.C.,
            Rept. PB-283-781, June, 1978

   145       Anon.,  "Control  of Volatile Organic Emissions From
            Existing  Stationary Sources Volume I, Control Methods
            For Surface-Coating Operations", Rept. EPA-450/2-76-028
            November, 1976.
                                        C-13

-------
Source                                                       APTIC     NTIS
  No.                              Title                      No.        No.
  146       Perry,  et al.  "Chemical  Engineers  Handbook,

  147       Maxwell,  J.  B.,  "Data  Book  on  Hydrocarbons",
            Standard  Oil  Development Company.

  148       Anon.,  "Cost Estimates of Upgrading  Participate
            Matter  Controls  on Copper Smelter  Reverberatory
            Furnaces", Industrial  Gas Cleaning Institute,
            Stamford, Conn., EPA Contract  68-02-2532,
            March,  1977.

  149       Cost Engineer's  Notebook, American Association of
            Cost Engineers.

  150       C.  H. Chilton,  "Cost Engineering in  the  Process
            Industries",  McGraw-Hill, 1960.

  151       Anon, "Industrial  Ventilation"  10th  Edition,
            American  Conference of Governmental  Industrial
            Hygienist.

  152       Hemeon, W.C.L.,  "Plant and  Process Ventilation",
            Second  Edition,  The Industrial  Press, New York,
            N,Y.

  153       Loyal Clarke, "Manual  for Process  Engineering
            Calculations", McGraw-Hill, 1947

  154       Anon, "Air Pollution Manual" PartiI  Control
            Equipment, American Industrial Hygiene Association.

  155       Strauss W. "Industrial Gas  Cleaning" Pergamon
            Press, Second Edition  1975.

  156       Bauman, H.C.  "Fundamentals  of Cost Engineering
            in  the Chemical  Industry" Reinhold 1965

  157       Gaylord "Structural Engineering Handbook:
            McGraw Hill 1968.

  158       Anon, "Capital Costs of  Free Standing Stacks"
            Vulcan -  Cincinnati Inc, EPA Contact #68-02-0299

  159       Holland,  F.A., et  al., "How to Estimate
            Capital Costs",  Chemical  Engineering, April 1,
            1974.

  160       GARD in-house data.
                                      C-14

-------
                                                        APTIC      NTIS
                                                         No.         No.
161     Shaw, N.R., "Carbon Absorption/Emission
        Control Benefits and Limitations",  Paper
        presented at symposium on Volatile  Organic
        Compound Control in Surface Coating Industries,
        April 25-26, 1979 Chicago, 111.

162     Anon "Hydrocarbon Pollutant Systems Study"
        MSA Research Corp., EPA contract EHSD 71-72,
        January 1973.

163     Private communication with PGST  Company  and
        vendor quote.

164     Norman, W.S., "Absorption Distillation and
        Cooling Towers".  Wiley Press.,  New York,
        N.Y.  1961

165     Miller, J.S. et. al., "Cost of a Distillation
        Column" Chemical Engineering, April 11,  1977
166     Pikulik, A., et. al., "Cost Estimating for
        Major Process Equipment" Chemical  Engr,
        Oct. 10, 1977

167     Steenberg, L.R. "Air Pollution Control
        Technology and Costs, Seven Selected Emission
        Sources". EPA-450/3-74-060, Dec.  1974      s

168     White, H. J.; "Industrial Electostatic Precipita-
        tion", Addison-Wesley Publishing  Co., 1963.

169     Horzella, T. I., "Selecting, Installing and
        Maintaining Cyclone Dust Collectors", Chemical
        Engineering, January 30, 1978.

170     Anon., "Review and Comments on Report Entitled
        Capital and Operating Costs of Selected Air
        Pollution Control Systems", PEDCo Environ-
        mental, Inc., August, 1979.

171     Anon., Building Construction Cost Data, 35th
        Annual Edition, Means, 1977.

172     Based on discussions with T. Tarnok of Joy/
        Western Precipitation Division.
                                     C-15

-------
               APPENDIX D
GUIDE TO ASSOCIATIONS FOR THE INDUSTRIES

-------
                             ASSOCIATIONS
1.   Air Pollution Control Association
     4400 Fifth Avenue
     Pittsburgh, Pennsylvania 15213
Lewis H. Rogers
Executive Vice President
412/621-1100
2.   Brick Institute of America
     1750 Old Meadow Road
     McLean, Virginia 22101
R. W. Otterson
Executive Vice President
703/893-4010
3.   Refractories Institute  (Brick)
     1102 One Oliver Plaza
     Pittsburgh, Pennsylvania 15222
Bradford S. Tucker
Executive Secretary
412/281-6787
4.   Refractories and Reactive Metals
         Association
     P. 0. Box 2054
     Princeton, New Jersey 08540
Kempton H. Roll
Executive Director
609/799-3300
5.   American Boiler Manufactures Association
     Suite 317, AM Building
     1500 Wilson Boulevard
     Arlington, Virginia 22209
W. B. Marx
Executive Director
703/522-7298
6.   National Grain and Feed Association
     501 Folger Building
     Washington, D. C. 20005
Alvin E. Oliver
Executive Vice President
202/783-2024
7.   Grain Elevator and Processing Society
     2144 Board of Trade Building
     Chicago, Illinois 60604
Dean M. Clark
Secretary-Treasurer
312/922-3111
8.   American  Feed Manufactures Association
     1701 N. Fort Myer Drive
     Arlington, Virginia 22209
Oakley M. Ray
President
703/524-0810
9.   Midwest Feed Manufacturers Association
     521 E. 63rd Street
     Kansas City, Missouri 64110
Rex Parsons
Executive Vice President
816/444-6240
10.  American Glassware Association
     c/o Organized Service Corp. Managers
     One Stone Place
     Bronxville, New York 10708
Donald V. Reed
Managing Director
914/779-9602
                                     D-l

-------
11.  Associated Glass and Pottery Manufacturers
     c/o Harold L. Hayes
     Brush Pottery Company
     P. 0. Box 2576
     Zanesville, Ohio 43701
 Harold  L.  Hayes
 Secretary
 614/454-1216
12.  National Association of Manufacturers of
        Pressed and Blown Glassware
     c/o John H. Morris
     707 Winmar Place
     Westerville, Ohio 43081
13.  Sealed Insulating Glass Manufactures
        Association
     202 S. Cook Street
     Barrington, Illinois 60010
Warren W. Findling
Executive Vice President
312/381-8989
14.  Gray and Ductile Iron Founders' Society
     Cast Metals Federation Building
     20611 Center Ridge Road
     Rocky River, Ohio 44116
Donald H. Workman
Executive Vice President
216/333-9600
15.  Malleable Founder's Society
     20611 Center Ridge Road
     Cast Metals Building
     Rocky River, Ohio 44116
Lowell D. Ryan
Executive Vice President
16.  Non-Ferrous Founder's Society
     21010 Center Ridge Road
     Cleveland, Ohio
Benjamin J. Imburgia
Executive Secretary
216/333-2072
17.  Steel Founder's Society of America
     20611 Center Ridge Road
     Cast Metals Federation Building
     Rocky River, Ohio 44116
Jack McNaughton
Executive Vice President
216/333-9600
18.  Foundry Equipment Manufacturers
         Association
     1000 Vermont Avenue
     Washington, D. C. 20005
Charles E. Perry
Executive Secretary
202/628-4634
19.  American Iron and Steel  Institute
     150 East 42nd Street
     New York, New York 10017
John P. Roche
President
212/697-5900
                                      D-2

-------
20.  Ductile Iron Society
     P. 0. Box 22058
     Cleveland, Ohio 44122
  James H. Lansing
  Executive Director
  216/752-0521
21.  Roll Manufacturers Institute
     1808 Investment Building
     Fourth Avenue
     Pittsburgh, Pennsylvania 15222
  A. G. Karp
  Executive Secretary-
     Treasurer
  412/281-0908
22.  National Council of the Paper Industry
         for Air and Stream Improvement
     260 Madison Avenue
     New York, New York 10016

23.  American Paper  Institute
     260 Madison Avenue
     New York, New York  10016

24.  Paper Industry  Management Association
     2570 Devon Avenue
     Des Plaines, Illinois  60018

25.  Technical Association of the Pulp
         and Paper Industry
     One Dunwoody Park
     Atlanta, Georgia  30341

26.  National Lime Association
     5010 Wisconsin  Avenue, N.W.,
     Washington, D.C.  20016

27.  National Crushed Stone Association
     1415 Elliot Place, N.W.
     Washington, D.C.  20007

28.  Portland Cement Association
     Old Orchard Road
     Skokie,  Illinois  60076

29.  Fertilizer  Industry Round Table
     Glenn Arm, Maryland  21057
 30.  The  Fertilizer  Institute
     1015 18th  St. N.W.
     Washington,  D.C.   20036
  Ernest J. Bolduc, Jr.
  Executive Director
  Albert S. Thomas
  Secretary-Streasurer
  212/889-6200

  H. Mac Gregor Tuttle
  Executive Director
  312/774-6797

  Phillip  E. Nethercut
  Executive Secretary-
     Treasurer
  404/457-6352

  Robert S. Boynton
v.  Executive Director
  202/966-3418

  W. L. Carter
  President
  202/333-1536

  Robert D. MacLean
  President
  312/966-6200

  Paul J.  Prosser
  Secretary-Treasurer
  301/592-6271

  Edwin M. Wheeler
  President
  202/466-2700
                                     D-3

-------
 31.   Eastern  States  Blast  Furnace and
          Coke Oven Association
      c/o  Paul F. Ross
      Bethlehem Steel Corporation
      Johnstown, Pa.  15907

 32.   National Coal Association
      1130 17th St. N.W.
      Washington, D.C.  20036

 33.   Soap and Detergent Association
      475  Park Avenue South
      New  York, New York   10016

 34.   Manufacturing Chemists Association
      1825 Connecticut Avenue, N.W.
      Washington, D.C.  20009

 35.   American Petroleum Institute
      1801  K Street, N.W.
      Washington, D.C.  20006

 36.   Coordinating Research Council
      30 Rockefeller Plaza
      New  York, New York  10020

 37.   Independent Refiners Association
          of America
      1801  K Street, N.W., Suite 1101
      Washington, D.C.  20006

 38.  National  Petroleum Refiners
         Association
      1725 De Sales Street,  N.W.
     Suite 802
     Washington, D.C.  20036

39.  Western Oil  and Gas Association
     602 S. Grand Avenue
     Los Angeles,  California  90017

40.  Copper Development Association
     405 Lexington Avenue 57th Floor
     New York, New York   10017

41.  Copper Institute
     50 Broadway
     New York, New York  10004
 Carl  E.  Bagge
 President
 202/628-4322

 Theodore E. Brenner
 President
 212/725-1262

 William  T. Driver
 President
 202/483-6126

 Frank N.  Ikard
 President
 202/833-5600

 M. K. McLeod,
 Manager
 212/757-1295

 Edwin Jason Dryer
 General  Counsel
 202/466-2340
Donald C. O'Hara
Executive Vice President
202/638-3722
Harry Morrison
Vice President
213/624-.6386

George M. Hartley
President
212/867-6500

H. Fasting
Secretary
212/944-1870
                                    D-4

-------
42.  Aluminum Association
     750 Third Avenue
     New York, New York  10017

43.  Incinerator Institute of America
     2425 Wilson Blvd.
     Arlington, Virginia  22201

44.  American Public Works Association
     1313 East 60th Street
     Chicago, Illinois  60637

45.  National Solid Wastes Management
         Association
     1730 Rhode Island Avenue, N.W.
     Suite 800
     Washington, D.C.  20036

46.  Conference of State Sanitary
         Engineers
     Statehouse
     Charleston, West Virginia  25305

47.  American Society of Sanitary
         Engineering
     960 Illuminating Building
     Cleveland, Ohio  44113

48.  National Cotton Ginner's Association
     Box 120
     Maypearl, Texas  76064

49.  The Cotton Foundation
     1918 North Parkway
     Memphis, Tennessee   38112

50.  Cotton  Incorporated
     1370 Avenue of the America's
     New York, New York  10019

51.  National Cotton Council of America
     1918 North Parkway
     Memphis, Tennessee  38112
S. L. Goldsmith, Jr.
Executive Vice President
212/972-1800

Charles N. Sumwalt, Jr
Executive Director
703/528-0663

Robert D. Bugher
Executive Director
312/324-3400
304/348-2970
Sanford Schwartz
Secretary
216/696-3228
Peary Wilemon
Secretary-Treasurer
214-435-2741

Gieorge S. Buck, Jr.
Executive Vice President
J. Dukes Wooters, Jr.
President
212/586-1070

Albert B. Russell
Executive Vice President
  and Secretary
901/276-2783
                                    D-5

-------
             APPENDIX E
CONVERSION FACTORS TO SI MEASUREMENTS

-------
                              APPENDIX E
                 CONVERSION FACTORS TO SI MEASUREMENTS
     For a complete description of conversion factors to the International
System of Units (SI), the reader is referred to the "Metric Practice Guide,"
American Society for Testing and Materials, pub. #E 380-72, approved by the
American National Standards Institute, Std. #Z210.1-1973.  The following are
selected conversion factors that will accomodate all units found in this
document, as well as other pertinent units.  They are arranged alphabetically.
      To convert from
atmosphere (normal»760 torr)
British thermal unit *(Btu)
Btu/ft2
Btu/hour
                                                          Multiply by
                                                                    5
                                                        1.01325 *
  to
pascal (Pa)
joule (J)            1.05506 * 103
joule/metre2 (J/m2)  1.13565 * 104
Btu/pourid -mass

Btu/lbm-deg F (heat capacity)

Btu/s-ft2-deg F
calorie (International Table)
day
degree Celsius (C)
degree Fahrenheit (F)
degree Fahrenheit (F)
foot (ft)
foot2 (ft2)
foot3 (ft3)
foot/hour (fph)
watt (W)
joule/kilogram-
  (J/kg)
joule/kilogram-
  kelvin (J/kg-K) v
          2
watt/metre -kelvin
  (W/m2.K)
joule (J)
second (s)
kelvin (k)
degree Celsius
kelvin (k)
metre (m)
     o   p
metre  (m )
metre  (m )
                     0.29307

                     2.326 * 103

                     4.18680 * 103

                     2.04418 * 104
                     4.18680
                     8.64000 * 104
                     tk=tc + 273.15
                     tc =(tf-32)/1.8
                     V (V*59.67)/1.8
                     0.30480
                     9.29030 * 10"2
                     2.83168 * 10
metre/second (m/s)   8.46667 * 10
                                                                    -2
                                                                    -5
+ The Btu quantity used herein is that based on the International Table.
                                     E-l

-------
     To convert from
 to
                      Multiply by
 foot/minute (fpm)
 foot/second (fps)
 foot  /minute (cfm)
 foot  /second (cfs)
 gallon (U.S. liquid)  (gal)
 gallon (U.S. liquid)/day  (gpd)
metre/second  (m/s)
metre/second  (m/.s")
     3          3
metre /second (m/s)
metre /second (m /s)
metre  (m )
metre /second
  (n»3/s)
                      5.08000 * 10
                      0.30480
                                                                     -3
                      4.71947 * 10
                                  -4
                      2.83168 * 10
                                  -2
 gallon  (U.S.  liquid)/minute  (gpm)  metre, /second
                        •
 u-ain \qr)
 Horsepower  (hp)
 NDur (Hr)
 •-rich (•''n)
 inch2 («n2)
 inch of water (60F)
 kilowatt-hour (kwh)
minute (min)
parts per million (ppm)

pound-force (Ibf avoirdupois)
                o
pound-force/inch  (psi)
pound-mass (Ibm avoirdupois)
pound-mass/foot3 (lbm/ft3)

pound-mass/minute (Ibm/min)

pound-mass/second (Ibm/sec)
  ton (cooTing capacity)
  ton (short,  2000 Ibm)
 kilogram(kg)
 watt  (w)
 second(s)
 metre  (m)
     2   2
 metre   (m)
 pascal  (Pa)
 joule (J)
 second  (s)
               +
milligram/metre"
  (mg/m3)
 newton  (N)
 pascal  (Pa)
 kilogram (kg).
              3
kilogram/metre
  (kg/m3)
kilogram/second
  (kg/s)
kilogram/second
  (kg/s)
Btu/hr
kilogram (kg)  •
                      3.78541 * 10
                                  -3
                                                         4.38126 * 10
                                                                     -8
                     6.30902 * 10~5
                     6.47989 * 10"5
                     7.46000 * 102
                     3.60000 * 10 3
                     2.54000 * 10~2
                     6.45160 * 10~4
                     2.4884 * 102
                     3.60000 * 106
                     60.000
                     (molecular weight)/24.5
                     4.44822
                     6.89476 * 103
                     0.453592

                     1.60185 * 101
                     7.55987 * 10"3
                     4.53592 *  10"1
                     1.2000  * 1040
                     9.07185 *  102
                                     E-2

-------
                                  I I UINICAI  '•  ''Oil 1  DA I A
                                 1 Imltlii lll>ll\ i"l   ; in UN i n it. us/on N i NMI n it MMS
   Industrial  Emission Sources
   CO^LS
   Manual
   Fabric  Filters, Absorbers, Flares,
   Scrubbers,  Refrigeration
   Electrostatic Precipitators
   Adsorbers,  Incinerators
 Cost Estimation
 Techniques
 Capital Costs
 Annualized Costs
 Air Pollution Control-
 Systems
                                                                        v.. COSA I I I II-lil/l iliui|'
18. DISrHIBUTIONSTAIEMLNT

   Unlimited
in r,r CUMIT Y 1:1 ASS /inn
 Unclassified
•jv r.i i-inil ry c.i A'.s iiim /
 Unclassified
                                                                        71. NO. 01 I'ACil '.'.
                                                                           PHUT
EPA Form 2220-1 19-73)

-------