EPA 450/5-80-007
           CAPITAL AND OPERATING COSTS
             FOR INDUSTRIAL BOILERS
                 Prepared by

          PEDCo Environmental, Inc.
             11499 Chester Road
           Cincinnati, Ohio  45246
           Contract No. 68-02-3074
            Work Assignment No. 7
                  ?N 3400-G
             EPA Project Officer

              John M. Pratapas
          Economic Analysis Branch
Office of Air Quality Planning ar.d Standards
Research Triangle Park, North Carolina 27711
                Prepared for
    U.S. Environmental Protection Agency
Office of Air Quality, Planning and Standards
Rerearch Triangle Park, North Carolina 27711
                  June,  1979

-------
     This report was furnished to the U.S. Environmental Protec-



tion Agency by PEDCo Environmental, Inc., Cincinnati, Ohio, in



fulfillment of Contract No. 68-02-3074, Work Assignment No. 7.



The contents of this report are reproduced herein as received



from the contractor.  The opinions, findings, and conclusions



expressed are those of the author and not necessarily those of



the Environmental Protection Agency.
                              11

-------
                        TABLE OF CONTENTS


                                                             Page

Disclaimer                                                     ii

List of Figures                                                iv

List of Tables                                                  v

Acknowledgment                                               viii

1.0  Introduction                                              1

2.0  Specific Boilers and Characteristics                      3

     Boiler Configuration                                     24
     Design Heat Input Rate                                   24
     Fuel Analysis                                            24
     Fuel Consumption                                         26
     Excess Air Usage                                         26
     Flue Gas Characteristics                                 30
     Load Factor                                              31
     Utility Requirements                                     32
     Manpower Requirements                                    32
     Bottom Ash Disposal Requirement                          33

References for Section 2                                      34

3.0  Cost Estimates for New Boilers                           35

     Cost Estimating Procedure                                35
     Cost Estimates                                           48

References for Section 3                                      56

4.0  Equations for Boiler Costs                               57

     Methodology                                              57

Appendix A                                                   A~l

Appendix B                                                   B~l

Appendix C                                                   c~l


                               iii

-------
                         LIST OF FIGURES
No.
 1   Equipment Costs of Water-Tube Boilers (With Fans and
     Ducts) Firing Eastern Low-Sulfur Coal Versus Heat
     Input                                                   70

 2   Equipment Costs of Package, Fire-Tube Boilers (With
     Fans and Ducts) Firing Residual Oil, Distillate Oil
     or Natural Gas Versus Heat Input                        71

 3   Equipment Costs of Dual-Fuel, Water-Tube Boilers
     (With Fans and Ducts) Firing Residual Oil/Natural
     Gas or Distillate Oil/Natural Gas Versus Heat Input     72

 4   Total Turnkey Costs of Coal-Fired, Package, Underfeed-
     Stoker Boilers Firing Eastern High-Sulfur Coal or
     Subbituminous Coal Versus Heat Input                    73

 5   Total Turnkey Costs of Coal-Fired, Field-Erected
     Boilers Firing Eastern High Sulfur Coal or Subbi-
     tuminous Coal Versus Heat Input                         74

 6   Total Turnkey Costs of Package, Fire-Tube Boilers
     Firing Residual Oil, Distillate Oil, or Natural Gas
     Versus Heat Input                                       75

 7   Total Turnkey Costs of Dual-Fuel, Package Boilers
     Firing Residual Oil/Natural Gas or Distillate Oil/
     Natural Gas Versus Heat Input                           76

 8   Total Turnkey Costs of Dual-fuel, Field-Erected
     Boilers Firing Residual Oil/Natural Gas or Distillate
     Oil/Natural Gas Versus Heat Input                       77

 9   Operating and Maintenance Costs (Less Fuel Costs) for
     Various Boilers Versus Equivalent Hours Operated Per
     Year at Maximum Capacity                                78

10   Operating and Maintenance Costs (Less Fuel Costs) for
     Various Boilers Versus Equivalent Hours Operated Per
     Year at Maximum Capacity                                79

11   Operating and Maintenance Costs (Less Fuel Costs) for
     Various Boilers Versus Equivalent Hours Operated Per
     Year at Maximum Capacity                                80

                               iv

-------
                         LIST OF TABLES

Number                                                      Page
  1       List of Boilers Costed for Development of
            Cost Equations                                    4

  2       Design Parameters for Coal-Fired,  Package,
            Water-Tube,  Underfeed-Stoker Boilers              6

  3       Design Parameters for Coal-Fired,  Package,
            Water-Tube^  Underfeed-Stoker Boilers              7

  4       Design Parameters for Coal-Fired,  Package,
            Water-Tube,  Underfeed-Stoker Boilers              8

  5       Design Parameters for Coal-Fired,  Field-Erected,
            Water-Tube,  Spreader-Stoker Boilers               9

  6       Design Parameters for Coal-Fired,  Field-Erected,
            Water-Tube,  Spreader-Stoker Boilers              10

  7       Design Parameters for Coal-Fired,  Field-Erected,
            Water-Tube,  Spreader-Stoker Boilers              11

  8       Design Parameters for Field-Erected, Water-Tube,
            Pulverized-Coal-Fired Boilers                    12

  9       Design Parameters for Field-Erected, Water-Tube,
            Pulverized-Coal-Fired Boilers                    13

 10       Design Parameters for Field-Erected, Water-Tube,
            Pulverized-Coal-Fired Boilers                    14

 11       Design Parameters for Package, Fire-Tube
            Boilers Firing Residual Oil                      15

 12       Design Parameters for Package, Fire-Tube
            Boilers Firing Distillate Oil                    16

 13       Design Parameters for Package, Fire-Tube
            Boilers Firing Natural Gas                       17

 14       Design Parameters for Package, Water-Tube
            Boilers Firing Residual Oil                      18

-------
LIST OF TABLES (continued)

Number                                                       Page

 15       Design Parameters for Package, Water-Tube
            Boilers Firing Distillate Oil                    19

 16       Design Parameters for Package, Water-Tube
            Boilers Firing Natural Gas                       20

 17       Design Parameters for Field-Erected,
            Water-Tube Boilers Firing Residual Oil           21

 18       Design Parameters for Field-Erected,
            Water-Tube Boilers Firing Distillate Oil         22

 19       Design Parameters for Field-Erected,
            Water-Tube Boilers Firing Natural Gas            23

 20       Ultimate Analyses of Fuels Selected for the
            Boilers                                          25

 21       Typical Amounts of Excess Air Supplied to
            Fuel-Burning Equipment                           27

 22       Basic Equipment and Installation Items Included
            in a New Boiler Facility                         39

 23       Sources of Cost Data for Equipment and
            Installation Items Included in Boiler Plants     40

 24       Typical Values for Indirect Capital Costs          42

 25       Annual Unit Costs for Operation and
            Maintenance                                      43

 26       Direct Annual Operation and Maintenance Cost
            Items Associated with Boilers                    45

 27       Methods Used to Estimate Direct Annual Costs       46

 28       Estimated Capital and Annualized Costs of
            Package, Waters-Tube, Underfeed-Stoker Boilers
            Firing Coal                                      49

 29       Estimated Capital and Annualized Costs of
            Field-Erected, Water-Tube, Spreader-Stoker
            Boilers Firing Coal                              50
                               VI

-------
LIST OF TABLES (continued)


Number                                                      Page
 30       Estimated Capital and Annualized Costs of
            Field-Erected,  Water-Tube/ Pulverized-Coal-
            Fired Boilers                                     51

 31       Estimated Capital and Annualized Costs of
            Package, Fire-Tube Boilers                        52

 32       Estimated Capital and Annualized Costs of Dual-
            Fuel, Water-Tube Boilers Firing Residual
            Oil/Natural Gas                                   54

 33       Estimated Capital and Annualized Costs of Dual-
            Fuel, Water-Tube Boilers Firing Distillate
            Oil/Natural Gas                                   55

 34       Format for Presentation of Capital Costs of
            Industrial Boilers                                59

 35       Format for Presentation of Annualized Costs
            of Industrial Boilers                             61

 36       Cost Equations for Package, Water-Tube,
            Underfeed-Stoker Boilers                          63

 37       Cost Equations for Field-Erected, Water-Tube,
            Spreader-Stoker Boilers                           64

 38       Cost Equations for Field-Erected, Water-Tube,
            Pulverized-Coal-Fired Boilers                     66

 39       Cost Equations for Package, Fire-Tube Boilers       67

 40       Cost Equations for Water-Tube, Dual-Fuel
            Boilers Firing Residual Oil/Natural Gas           68

 41       Cost Equations for Water-Tube, Dual-Fuel
            Boilers Firing Distillate Oil/Natural Gas         69
                               vii

-------
                         ACKNOWLEDGEMENT





     This report was prepared for the Office of Air Quality,



Planning and Standards of the U.S. Environmental Protection



Agency.  The EPA Project Officer was John M. Pratapas.  PEDCo



appreciates his direction and assistance.



     The PEDCo Project Director was Mr. William F. Kemner.  Mr.



Larry L. Gibbs was Project Manager.  Principal authors were



Messrs.  Gibbs, John P. Abraham, Duane S. Forste, N. David Noe,



and Harry T. Kimball.
                             vzn

-------
                        1.0  INTRODUCTION





     The purpose of this study is to develop general equations to



relate the costs of various types of boilers to parameters such



as fuel type, fuel analysis, operating hours, and input capacity.



The equations are to represent a cross section of fuel types



including several ranks of coal, distillate oil, residual oil,



and natural gas, and a cross section of boiler types including



fire-tube, package water-tube, field-erected water-tube, stoker



coal-fired, and pulverized coal-fired.



     These equations will be used by the Office of Air Quality,



Planning and Standards (OAQPS)  as input to a computer model to be



used in evaluating the economic impacts of various alternative



regulatory scenarios as applied to new industrial boilers.



     The specific equations to be developed were for distillate



oil-fired fire-tube, residual oil-fired fire-tube, natural gas-



fired fire-tube, stoker coal-fired package water-tube, residual



oil/natural gas-fired package water-tube, distillate oil/natural



gas-fired package water-tube, stoker coal-fired field-erected



water-tube, pulverized coal-fired field-erected water-tube,



residual oil/natural gas-fired field-erected water-tube, and



distillate oil/natural gas-fired field-erected water-tube.  To



develop these equations,  51 specific boiler/fuel combinations

-------
were costed.  In addition, costs for 8 other boiler/fuel combina-



tions developed previously under Contract No. 68-02-2603, Task 19



were used in development of the equations.  This report summarizes



the equations for the 10 major boiler/fuel combinations and



presents detailed costs for the 59 specific boilers used in



developing these equations.



     In Section 2 are presented the characteristics of the spe-



cific boiler types, fuels, and sizes for which costs were pre-



pared.  Section 3 presents the detailed costs for 59 boilers and



the methodology used to obtain costs.  Section 4 presents the



equations describing boiler costs and the methodology for obtain-



ing these equations.  Appendices A, B, and C present the detailed



cost tables for the 59 boilers.

-------
            2.0  SPECIFIC BOILERS AND CHARACTERISTICS

     The boilers were selected jointly by PEDCo and OAQPS  for
detailed costing to cover the size range and fuel types of boilers
typically found in industrial use.  A minimum number of boilers
were chosen that would still provide a good basis for development
of boiler cost equations.  The boilers selected for detailed
costing are listed in Table 1.
     Operational and design parameters had to be specified for
the selected boilers before the costs could be estimated.  The
following key operating and design parameters are required for
each boiler:
     0    Boiler configuration
     0    Design heat input rate
     0    Fuel analysis
     0    Fuel consumption
     0    Excess air usage
     0    Flue gas characteristics
     0    Load factor
     The values determined for these operating and design param-
eters (Tables 2 through 19)  are based on published data and
practical knowledge of good boiler operating paractices.   The
methodology used to determine these values is described below.

-------
                TABLE  1.  LIST OF BOILERS COSTED FOR DEVELOPMENT OF COST EQUATIONS
Boiler type
Package water- tube, underfeed stoker
Package water-tube , underfeed stoker
Package water-tube, underfeed stoker
Package water- tube, underfeed stoker
Package water-tube, underfeed stoker
Package water- tube, underfeed stoker
Package water- tube, underfeed stoker
Package water-tube, underfeed stoker
Package water-tube, underfeed stoker
Package water-tube, underfeed stoker
Package water-tube, underfeed stoker
Package water-tube, underfeed stoker
Field-erected water-tube spreader stoker
Field-erected water-tube spreader stoker
Field-erected water-tube spreader stoker
Field-erected water-tube spreader stoker
Field-erected water-tube spreader stoker
Field-erected water-tube spreader stoker
Field-erected water-tube spreader stoker
Field-erected water-tube spreader stoker
Field-erected water-tube spreader stoker
Field-erected water-tube spreader stoker
Field-erected water-tube spreader stoker
Field-erected water-tube spreader stoker
Field-erected water-tube pulverized
Field-erected water-tube pulverized
Field-erected water-tube pulverized
Field-erected water-tube pulverized
Field-erected water-tube pulverized
Field-erected water-tube pulverized
Field-erected water-tube pulverized
Field-erected water-tube pulverized
Heat input,
106 Btu/h
15
15
15
15
30
30
30
30
60
60
60
60
75
75
75
75
150
150
150
150
200
200
200
200
200
200
200
200
400
400
400
400
Steam generating
Capacity, 103 lb/h
12.0
12.0
12.0
12.0
24.0
24.0
24.0
24.0
48.0
48.0
48.0
48.0
60.0
60.0
60.0
60.0
120.0
120.0
120.0
120.0
160.0
160.0
160.0
160.0
160.0
160.0
160.0
160.0
320.0
320.0
320.0
320.0
Fuel
Eastern high-sulfur coal
Eastern low-sulfur coal
Subbituminous coal
Eastern medium-sulfur coal
Eastern high-sulfur coal
Eastern low-sulfur coal
Subbituminous coal
Eastern medium-sulfur coal
Eastern high-sulfur coal
Eastern low-sulfur coal
Subbituminous coal
Eastern medium-sulfur coal
Eastern high-sulfur coal
Eastern low-sulfur coal
Subbituminous coal
Eastern medium-sulfur coal
Eastern high-sulfur coal
Eastern low-sulfur coal
Subbituminous coal
Eastern medium-sulfur coal
Eastern high-sulfur coal
Eastern low-sulfur coal
Subbituminous coal
Eastern medium-sulfur coal
Eastern high-sulfur coal
Eastern low-sulfur coal
Subbituminous coal
Eastern medium-sulfur coal
Eastern high-sulfur coal
Eastern low-sulfur coal
Subbituminous coal
Eastern medium-sulfur coal
(continued)

-------
TABLE 1.  (continued)
Boiler -type
Field-erected water-tube pulverized
Field-erected water-tube pulverized
Field-erected water-tube pulverized
Field-erected water-tube pulverized
Package fire-tube
Package fire-tube
Package fire-tube
Package fire-tube
Package fire-tube
Package fire- tube
Package fire-tube
Package fire-tube
Package fire-tube
Package water-tube
Package water-tube
Package water-tube
Package water-tube
Field-erected water-tube
Field-erected water-tube
Field-erected water-tube
Package water-tube
Package water-tube
Package water- tube
Package water-tube
Field-erected water-tube
Field-erected water-tube
Field-erected water-tube
Heat input,
106 Btu/h
700
700
700
700
5
5
5
15
15
15
29
29
29
30
60
100
150
200
400
700
30
60
100
150
200
400
700
Steam generating
Capacity, 103 lb/h
560.0
560.0
560.0
560.0
4.0
4.0
4.0
12.0
12.0
12.0
23.2
23.2
23.2
24.0
48.0
80.0
120.0
160.0
320.0
560.0
24.0
48.0
80.0
120.0
160.0
320.0
560.0
•Fuel
Eastern high-sulfur coal
Eastern low-sulfur coal
Subbituminous coal
Eastern medium-sulfur coal
Distillate oil
Natural gas
Residual oil
Distillate oil
Natural gas
Residual oil
Distillate oil
Natural gas
Residual oil
Residual oil/natural gas
Residual oil/natural gas
Residual oil/natural gas
Residual oil/natural gas
Residual oil/natural gas
Residual oil/natural gas
Residual oil/natural gas
Distillate oil/natural gas
Distillate oil/natural gas
Distillate oil/natural gas
Distillate oil/natural gas
Distillate oil/natural gas
Distillate oil/natural gas
Distillate oil/natural gas

-------
              TASLI: 2.   rrsiGN  PARAMETERS  For. COAL-FIRED,  PACKAGE,
                       WATEr.-TUDE,  UNDERFEED-STOKER  BOILERS
Thermal input, MW  (10° Btu/h)

fuel
Fuel rate,  kg/a
           (tona/h)

Analysis
  % aulfur
  % ash
  Heating value, kJ/kg
                (Btu/lb)

Exceas air,  %

Flue gas flow rate, m /a
                   (acfm)

Flue gaa temperature,  °K (°F)

Load factor, %

Utility requirementa
  Electricity, kw
  Process water, liters/a  (gpm)

Manpower requirementa
  Direct labor, man-yr
  Supervision, man-yr
  Maintenance labor, man-yr

Bottom ash disposal requirement,
  kg/h (ton/h)
  4.4 (IS)

Eastern high-
  sulfur coal
  4.4 (15)
4.4 (15)
Eastern low-  Subbituminous
  sulfur coal   coal'
  4.4 (15)

Eastern medium-
  sulfur coal
0.16
(0.64)
3.5
10.6
27,447
(11,800)
50
3.04
(6450)
478 (400)
60
190
0.30 (4.8)
5
2
2
0.14
(0.54)
0.9
6.9
32,099
(13,800)
50
2.88
(6100)
450 (350)
60
162
0.30 (4.8)
5
2
2
0.20
(0.78)
0.6
5.4
22,330
(9,600)
50
2.95
(6250)
450 (350)
60
233
0.30 (4.8)
5
2
2
0.14
(0.57)
2.3
13.2
30,703
(13,200)
50
2.98
(6325)
450 (350)
60
169
0.30 (4.8)
5
2
2
 46.16  (0.05)
 25.35  (0.03)   28.66 (0.03)   51.19 (0.06)

-------
               TABLE  3.  DESIGN PARAMETERS  FOR COAL-FIRED,  PACKAGE,
                         WATER-TUBE,  UNDERFEED-STOKER BOILERS
Thermal  input, MH (10° Btu/h)

Fuel


Fuel rate, kg/s  (ton/h)

Analysis
  % sulfur
  % ash
  Heating value, kJ/kg
                (Btu/lb)

Excess air,  %

Flue gas flow rate, m /s (acfm)
  if
Flue gas temperature, °K (°F)

Load factor, %

Utility  requirements
  Electricity, kW
  Process water,liters/3 (gpm)

Manpower requirements
  Direct labor, man-yr
  Supervision, man-yr
  Maintenance labor, man-yr

Bottom ash disposal requirement,
  kg/h (ton/h)
8.8 (30)

Eastern high-
sulfur coal

0.32 (1.27)
3.5
10.6
27,447
(11,800)

50

6.09 (12,900)

478 (400)

60
296
0.61 (9.6)
90.71 (0.10)
8.8 (30)

Eastern low-
sulfur coal
8.8 (30)
8.8 (30)
Subbituminoua  Eastern medium-
coal          sulfur coal
0.27 (1.09)
0.9
6.9
32,099
(13,800)
50
5.76 (12,200)
450 (350)
60
253
0.61 (9.6)
6
2
2
0.39 (1.56)
0.6
5.4
22,330
(9600)
50
5.90 (12,500)
450 (350)
60
364
0.61 (9.6)
6
2
2
0.28 (1.13)
\ 2'3
30,703
(13,200)
50
5.97 (12.650)
450 (350)
60
264
0.61 (9.6)
6
2
2
54.43 (0.06)    54.43  (0.06)   99.78 (0.11)

-------
                          TABLE  4.   DESIGN  PARAMETERS FOR COAL-FIRED,  PACKAGE,
                                    WATER-TUBE, UNDERFEED-STOKER  BOILERS
oo
              Thermal  input, MW (10° Btu/h)

              Fuel
Fuel rate, kg/s
           (tons/h)

Analysis
  t sulfur
  % ash
  Heating value,  kJ/kg
                 (Btu/lb)

Excess air, I

Flue gas flow  rate, m /s
                    (acfm)

Flue gas temperature, °K  (°F)

Load factor, %

Utility requirements
  Electricity, kw
  Process water,  liters/s (gpm)

Manpower requirements
  Direct labor, man-yr
  Supervision, man-yr
  Maintenance  labor, man-yr

Bottom ash disposal requirement,
  kg/h (ton/h)
                                  17.6 (60)
17.6 (60)
17.6 (60)
17.6 (60)
                                  Eastern high-   Eastern low-
                                    sulfur coal     sulfur coal
              Subbituminous  Eastern medium-
                coal           sulfur coal
0.64
(2.54)
3.5
10.6
27,447
(11,800)
50
12. IB
(25,800)
478 (400)
60
392
1.21 (19.2)
7
4
4
0.55
(2.18)
0.9
6.9
32,099
(13,800)
50
11.52
(24,400)
450 (350)
60
335
1.21 (19.2)
7
4
4
0.76
(3.12)
0.6
5.4
22,330
(9,600)
50
11.80
(25,000)
450 (350)
60
482
1.21 (19.2)
7
4
4
0.57
(2.25)
2.3
13.2
30,703
(13,200)
50
11.94
(25,300)
450 (350)
60
350
1.21 (19.2)
7
4
4
                                               181.42 (0.20)   99.78  (0.11)   117.92 (0.13)   199.56  (0.22)

-------
                   TABLE  5.   DESIGN PARAMETERS  FOR  COAL-FIRED, FIELD-ERECTED,
                                  WATER-TUBE,  SPREADER-STOKER  BOILERS
vo
Thermal  input, MH (10  Btu/h)
    4
Fuel


Fuel rate, kg/s (ton/h)

Analysis
  % sulfur
  % ash
  Heating value, kJ/kg
                (Btu/lb)

Excess air, t

Flue gas flow rate,  m /a
                   (acfm)

Flue gas temperature,  °K  (°F)

Load factor, %

Utility  requirements
  Electricity, kW
  Process water, liters/s  (gpm)

Manpower requirements
  Direct labor, man-yr
  Supervision, man-yr
  Maintenance labor, man-yr

Bottom ash disposal  requirement,
  kg/h (ton/h)
                                          22.0 (75)
22.0 (75)
22.0 (75)
22.0 (75)
Eastern high-
sulfur coal
0.80 (3.18)
3.5
10.6
27,447
(11,800)
50
15.24
(32,300)
478 (400)
60
425
1.52 (24.0)
8
4
4
Eastern low-
sulfur coal
0.69 (2.72)
0.9
6.9
32,099
(13,800)
50
14.21
(30,100)
450 (350)
60
363
1.52 (24.0)
8
4
4
Subbituminous
coal
0.99 (3.91)
0.6
5.4
22,330
(9600)
50
14.82
(31,400)
450 (350)
60
523
1.52 (24.0)
8
4
4
Eastern med
sulfur coal
0.72 (2.82)
2.3
13.2
30,703
(13,200)
50
14.73
(31.200)
450 (350)
60
379
1.52 (24.0)
8
4
4
                                          107.03  (0.12)
59.59  (0.07)   67.04 (0.07)  118.19  (0.13)

-------
           TABLE  6.   DESIGN  PARAMETERS  FOR  COAL-FIRED,  FIELD-ERECTED,
                          WATER-TUBE,  SPREADER-STOKER  BOILERS
Thermal input,  MVf (10° Btu/h)

Fuel


Fuel rate,  kg/a (ton/h)

Analysis
  % aulfur
  % ash
  Heating value,  kJ/kg
                 (Btu/lb)

Exceaa air,  t

Flue gas flow rate, m /s
                   (acfm)

Flue gas temperature, °K  (°P)

Load factor, %

Utility requirements
  Electricity,  kW
  Process water, liter a/a (gpm)

Manpower requirements
  Direct labor, man-yr
  Supervision,  man-yr
  Maintenance labor, man-yr
44.0 (ISO)
44.0 (150)
44.0 (150)
44.0 (150)
Eastern high-
sulfur coal
1.60 (6.36)
3.5
10.6
27.447
(11,800)
50
30.58
(64,800)
478 (400)
60
628
3.03 (48.0)
12
4
4
Eastern low-
sulfur coal
1.38 (5.44)
0.9
6.9
32,099
(13,800)
50
28.69
(60,800)
450 (350)
60
537
3.03 (48.0V
12
4
4
Subbituminous
coal
1.98 (7.82)
0.6
5.4
22,330
(9600)
SO/
29.64
(62,800)
450 (350)
60
773
3.03 (48.0)
12
4
4
Eastern med
sulfur coal
1.43 (5.63)
2.3
13.2
30,703
(13,200)
50
29.72
(63,000)
450 (350)
60
561
3.03 (48.0)
12
4
4
Bottom ash disposal requirement,
  kg/h (ton/h)
217.70 (0.24)
117.92 (0.13)   136.07  (0.15)  235.85 (0.26)

-------
        TABLE  7.   DESIGN PARAMETERS  FOR COAL-FIRED,  FIELD-ERECTED,
                       WATER-TUBE,  SPREADER-STOKER BOILERS
Thermal input. MW (10  Btu/h)

Fuel
Fuel rate,  kg/s
           (tons/h)

Analysis
  % sulfur
  % ash
  Heating value, kJ/kg
                (Btu/lb)

Excess air,  %

Flue gas flow rate, m /s
                   (acfm)

Flue gas temperature,  °K (°F)

Load factor, %

Utility requirements
  Electricity, kW
  Process water, liters/s  (gpm)

Manpower requirements
  Direct labor, man-yr
  Supervision, man-yr
  Maintenance labor, man-yr

Bottom ash  disposal requirement,
  kg/h (ton/h)
58.6 (200)
58.6 (200)
58.6 (200)
58.6 (200)
Eastern high-  Eastern low-
  sulfur coal    sulfur coal
              Subbituminous  Eastern medium-
                coal           sulfur coal
2.13
(8.48)
3.5
10.6
27,447
(11,800)
50
40.77
(86,400)
478 (400)
60
813
4.04 (64.0)
16
4
6
1.84
(7.25)
0.9
6.9
32,099
(13,800)
50
38.27
(81,100)
450 (350)
60
695
4.04 (64.0)
16
4
6
2.64
(10.43)
0.6
5.4
22,330
(9,600)
50
39.52
(83,700)
450 (350)
60
1001
4.04 (64.0)
16
4
6
1.91
(7.51)
2.3
13.2
30,703
(13,200)
50
39.65
(84,000)
450 (350)
60
726
4.04 (64.0)
16
4
6
281.20 (0.31)  163.28 (0.18)   181.42  (0.20)  317.49 (0.35)

-------
            TABLE 8.   DESIGN PARAMETERS  FOR FIELD-ERECTED,  WATER-TUBE,
                              PULVERIZED-COAL-FIRED BOILERS
Thermal input,  MW (10  Btu/h)

Fuel


Fuel rate,  kg/a (ton/h)

Analysis
  t sulfur
  t ash
  Heating value,  kJ/kg
                 (Btu/lb)

Excess air,  %

Plue gas flow rate, m /s
                    (acfm)

Flue gas temperature, °K  (°F)

Load factor, t

Utility requirements
  Electricity,  kw
  Process water, liters/s (gpm)

Manpower requirements
  Direct labor, man-yr
  Supervision,  man-yr
  Maintenance labor, man-yr

Bottom ash disposal requirement,
  kg/h (ton/h)
58.6 (200)
58.6 (200)
58.6 (200)
58.6 (200)
eastern high-
sulfur coal
2.13 (8.48)
3.5
10.6
27,447
(11,800)
30
35.30
(74,800)
478 (400)
60
2052
4.04 (64.0)
16
4
6
Eastern low-
sulfur coal
1.84 (7.25)
0.9
6.9
32,099
(13,800)
30
33.32
(70,600)
450 (350)
60
1754
4.04 (64.0)
16
4
6
Subbituminous
coal
2.64 (10.43)
0.6
5.4
22,330
(9600)
30
34.55
(73,200)
450 (350)
60
2526
4.04 (64.0)
16
4
6
Eastern med
sulfur coal
1.91 (7.51)
2.3
13.2
30,703
(13,200)
30
34.62
(73,400)
450 (350)
60
1831
4.04 (64.0)
16
4
6
163.28 (0.18)    90.71  (0.10)   99.78 (0.11)    181.42  (0.20)

-------
                  TABLE 9.   DESIGN PARAMETERS  FOR  FIELD-ERECTED,
                     WATER-TUBE, PULVERIZED-COAL-FIRED BOILERS
Thermal  input, MW (10° Btu/h)

Fuel


Fuel rate, kg/s  (ton/h)

Analysis
  % sulfur
  « ash
  Heating value, kJ/kg
                (Btu/lb)

Excess air,  «

Flue gas flow rate, m /s
                   (acfm)

Flue gas temperature, °K (°F)

Load factor, %

Utility  requirements
  Electricity, kW
  Process water, liters/s (gpm)

Manpower requirements
  Direct labor, man-yr
  Supervision, man-yr
  Maintenance labor, man-yr

Bottom ash disposal requirement,
  kg/h (ton/h)
117.2  (400)
117.2  (400)
117.2 (400)
117.2 (400)
Eastern high-
sulfur coal
4.27 (16.95)
3.5
10.6
27,447
(11,800)
30
70.63
(149,600)
478 (400)
60
4142
8.08 (128.0)
28
6
12
Eastern low-
sulfur coal
3.65 (14.49)
0.9
6.9
32,099
(13,800)
30
66.80
(141,500)
450 (350)
60
3540
8.08 (128.0)
28
6
12
Subbituminous
coal
5.25 (20.83)
0.6
5.4
22,330
(9600)
30
68.89
(146,000)
450 (350)
60
5097
8.08 (128.0)
28
6
12
Eastern medii
sulfur coal
3.82 (15.14)
2.3
13.2
30,703
(13,200)
30
71.35
(151,200)
478 (400)
60
3695
8.08 (128.0)
28
6
12
326.56 (0.36)
181.42 (0.20)   199.56  (0.22)  362.84 (0.40)

-------
                TABLE 10.   DESIGN PARAMETERS FOR FIELD-ERECTED,
                   WATER-TUBE,  PULVERIZED-COAL-FIRED BOILERS
Thermal Input,  MW  (10  Btu/h)

Fuel
Fuel rate,  kg/8
           (tons/h)

Analysis
  % sulfur
  % ash
  Heating value, kJ/kg
                 (Btu/lb)

Excess air,  %

Flue gas flow  rate, m /s
                    (acfro)

Flue gas temperature, °K  (*F)

Load factor, \

Utility requirements
  Electricity, kW
  Process water, liters/s (gpm)

Manpower requirements
  Direct labor, man-yr
  Supervision, man-yr
  Maintenance  labor, man-yr

Bottom ash  disposal requirement,
  kg/h (ton/h)
205.1 (700)
205.1  (700)
Eastern high-  Eastern  low-
  sulfur coal    sulfur coal
205.1 (700)

Subbituminous
  coal
205.1 (700)

Eastern medium-
  sulfur coal
7.47
(29.66)
3.5
10.6
27,447
(11,800)
30
123.55
(261,800)
478 (400)
60
7249
14.14 (224.0)
38
6
16
6.39
(25.36)
0.9
6.9
32,099
(13,800)
30
116.62
(247,100)
450 (350)
60
6195
14.14 (224.0)
38
6
16
9.19
(36.46)
0.6
5.4
22,330
(9,600)
30
120.93
(256,200)
450 (350)
60
8920
14.14 (224.0)
38
6
16
6.68
(26.52)
2.3
13.2
30,703
(13,200)
30
121.17
(256,900)
450 (350)
60
6466
14.14 (22
38
6
16
570.43  (0.63)   317.49  (0.35)  357.22 (0.39)   635.14  (0.70)

-------
     TABLE 11.
DESIGN  PARAMETERS FOR PACKAGE,  FIRE-TUBE
 BOILERS FIRING  RESIDUAL OIL
Thermal  input, MW (10  Btu/h)

Fuel

Fuel rate, m /h
           (gal/h)

Analysis
  % sulfur
  % ash              3
  Heating value, MJ/m
                 (Btu/gal)

Excess air, %

Flue gas flow  rate, m /s
                   (acfm)

Flue gas temperature, "K (°F)

Load factor, %

Utility  requirements
  Electricity, kW
  Process water,  liter/s (gpm)

Manpower requirements
  Direct labor, man-yr
  Supervision, man-yr
  Maintenance  labor, man-yr

Bottom ash  disposal requirement
  kg/h (tons/h)
1.5 (5)
Residual oil
0.13
(33.4)
3.0
0.1
41,714
(149,800)
15
0.75
(1,600)
478 (400)
45
59
0.10 (1.6)
4
0.5
4.4 (15)
Residual oil
0.38
(100.1)
3.0
0.1
41,714
(149,800)
15
2.21
(4,700)
478 (400)
45
114
0.30 (4.8)
4
2
1
8.5 (29)
Residual oil
0.73
(193.6)
3.0
0.1
41,714
(149,800)
15
4.28
(9,100)
478 (400)
45
236
0.60 (9.5)
4
2
1
               Negligible
Negligible
Negligible

-------
                          TABLE  12.   DESIGN PARAMETERS  FOR PACKAGE, FIRE-TUBE
                                        BOILERS FIRING DISTILLATE OIL
<3\
Thermal input,  MW (10°  Btu/h)

Fuel

Fuel rate,  m3/h (gal/h)

Analysis
  % sulfur
  % ash              ,
  Heating value,  MJ/m  (Btu/gal)

Excess air, \

Flue gas flow rate, m /s  (acfm)

Flue gas temperature, °K  (°F)

Load factor,  %

Utility requirements
  Electricity,  kW
  Process water,  llter/s  (gpm)

Manpower requirements
  Direct labor, man-yr
  Supervision,  man-yr
  Maintenance labor, man-yr

Bottom ash  disposal requirement,
  kg/h (ton/h)
                                               1.5 (5)

                                               Distillate oil

                                               0.14 (36.0)
                                               0.5
                                               Trace
                                               38,712 (139,000)
4.4  (15)

Distillate oil

0.41 (107.9) .
0.5
Trace
38,712 (139,000)
8.5  (29)

Distillate oil

0.79  (208.6)
0.5
Trace
38,712 (139,000)
15
0.81 (1700)
450 (350)
45
59
0.10 (1.6)
4
.5
15
2.36 (5000)
450 (350)
45
114
0.30 (4.8)
4
2
1
15
4.45
450
45
236
0.60
4
2
1

(9700)
(350)

(9.5)

                                               Negligible
Negligible
Negligible

-------
           TABLE  13.   DESIGN PARAMETERS FOR PACKAGE, FIRE-TUBE
                          BOILERS FIRING  NATURAL  GAS
Thermal  input, MW (10  Btu/h)

Fuel

Fuel rate, m3/s  (ft3/h)

Analysis
  % sulfur
  % ash              ,        ,
  Heating value, kJ/m  (Btu/ft )

Excess air,  %

Flue gas flow rate, m /s (acfm)

Flue gas temperature, °K (*F)

Load factor, %

Utility  requirements
  Electricity, kW
  Process water, liter/a (gpm)

Manpower requirements
  Direct labor, man-yr
  Supervision, man-yr
  Maintenance labor, man-yr

Bottom ash disposal requirement,
  kg/h (ton/h)
1.5 (5)
Natural gas
0.04 (5000)
Trace
Trace
37,218 (1000)
15
0.81 (1700)
450 (350)
45
59
0.10 (1.6)
4
.5
4.4 (15)
Natural gas
0.12 (15,000)
Trace
Trace
37,218 (1000)
15
2.45 (5200)
450 (350)
45
114
0.30 (4.8)
4
2
1
8.5 (29)
Natural gas
0.23 (29,000)
Trace
Trace
37,218 (1000)
15
4.74 (10,100)
450 (350)
45
236
0.60 (9.5)
4
2
1
Negligible
Negligible
Negligible

-------
                          TABLE 14.
                         DESIGN  PARAMETERS  FOR  PACKAGE,  WATER-TUBE
                            BOILERS  FIRING RESIDUAL  OIL
o>
Thermal input  , MW  (10° Btu/h)

Fuel

Fuel rate,  m /h
           (gal/h)

Analysis
  « sulfur
  % ash             ,
  Heating value, MJ/m
                 (Btu/gal)

Excess air,  %

Flue gas flow  rate, m /s
                   (acfm)

Flue gas temperature, °K  (*F)

Load factor, %

Utility requirements
  Electricity, kW
  Process water, liter/s  (gptn)

Manpower requirements
  Direct labor, man-yr
  Supervision, man-yr
  Maintenance  labor, man-yr

Bottom ash  disposal requirement,
  kg/h (ton/h)
                                                8.8 (30)

                                                Residual oil
17.6 (60)

Residual oil
29.3 (100)

Residual oil
44.0 (ISO)

Residual oil
0.76
(200.3)
3.0
0.1
41,714
(149,800)
15
4.62
(9800)
478 (400)
55
236
0.61 (9.6)
4
2
1
1.52
(400.5)
3.0
0.1
41,714
(149.800)
15
9.25
(19,600)
478 (400)
55
265
1.21 (19.2)
4
2
2
2.53
(667.6)
3.0
0.1
41,714
(149,800)
15
15.43
(32,700)
478 (400)
55
316
2.02 (32.0)
6
2
2
3.79
(1001.3)
3.0
0.1
41,714
(149,800)
15
23.12
(49,000)
478 (400)
55
379
3.03 (48.0)
8
2
2
                                                Negligible
Negligible
Negligible
Negligible

-------
                          TABLE 15.
                        DESIGN  PARAMETERS FOR  PACKAGE,  WATER-TUBE
                         BOILERS FIRING DISTILLATE  OIL
vo
Thermal input, HH  (10° Btu/h)       8.8  (30)    •   17.6 (60)       29.3  (100)     44.0 (150)

Fuel


Fuel rate, m /h
           (gal/h)

Analysis
  % sulfur
  % ash             ,
  Heating value, MJ/m
                 (Btu/gal)

Excess air, %

Flue gas flow rate, m /s
                   (acfm)

Flue gas temperature,  °K (°F)

Load factor, %

Utility requirements
  Electricity, kW
  Process water, liters/a (gpm)

Manpower requirements
  Direct labor, man-yr
  Supervision, man-yr
  Maintenance labor, man-yr

Bottom ash disposal requirement,
  kg/h (ton/h)                     Negligible     Negligible     Negligible     Negligible
Distillate
oil
0.82
(215.8)
0.5
Trace
38,712
(139.000)
15
4.36
(9.240)
450 (350)
55
236
0.61 (9.6)
4
2
1
Distillate
oil
1.63
(431.7)
0.5
Trace
38,712
(139.000)
15
8.73
(18,500)
450 (350)
55
265
1.21 (19.2)
4
2
2
Distillate
oil
2.72
(719.4)
0.5
Trace
38,712
(139,000)
15
14.53
(30,800)
450 (350)
55
316
2.02 (32.0)
6
2
2
Distillate
oil
4.09
(1080.0)
0.5
Trace
38.712
(139.000)
15
21.78
(46,200)
450 (350)
55
379
3.03 (48.0)
8
2
2

-------
                        TABLE  16.
                        DESIGN PARAMETERS FOR PACKAGE, WATER-TUBE
                          BOILERS FIRING NATURAL  GAS
K>
O
Thermal input, MW (10° Btu/h)

Fuel

Fuel rate, m /s
           (ft3/h)

Analysis
  % aulfur
  % ash             3
  Heating value, kJ/m   1
                (Btu/Ct )

Excess air, %

Flue gas Clow rate,  m /s
                   (acfm)

Flu* gas temperature,  °K (°F)

Load factor, %

Utility requirements
  Electricity, kW
  Process water, liters/s (gpm)

Manpower requirements
  Direct- labor, man-yr
  Supervision, man-yr
  Maintenance labor, man-yr
8.B (30)
Natural gas
0.24
(30,000)
Trace
Trace
37,218
(1000)
IS
4.43
(9,380)
450 (350)
55
236
0.61 (9.6)
4
2
1
17.6 (60)
Natural gas
0.47
(60,000)
Trace
Trace
37,218
(1000)
15
8.87
(18,800)
450 (350)
55
265
1.21 (19.2)
4
2
2
29.3 (100)
Natural gas
0.79
(100,000)
Trace
Trace
37,218
(1000)
15
14.77
(31,300)
450 (350)
55
316
2.02 (32.0)
6
2
2
44.0 (150)
Natural gas
1.18
(150,000)
Trace
Trace
37,218
(1000)
15
22.15
(46,900)
450 (350)
55
379
3.03 (48.0)
8
2
2
              Bottom ash disposal requirement,
                kg/h (ton/h)                    Negligible     Negligible     Negligible     Negligibli

-------
 TABLE  17.
DESIGN  PARAMETERS FOR FIELD-ERECTED,  WATER-TUBE
      BOILERS FIRING  RESIDUAL  OIL
Thermal  input, MW (10° Btu/h)

Fuel

Fuel rate, m /h
           (gal/h)

Analysis
  % sulfur
  % ash              ,
  Heating value, MJ/m
                 (Btu/gal)

Excess air, %

Flue gas flow rate,  m /s
                   (acfm)

Flue gas temperature,  °K (°F)

Load factor, %

Utility  requirements
  Electricity, kW
  Process water,  liters/a (gpm)

Manpower requirements
  Direct labor, man-yr
  Supervision, man-yr
  Maintenance labor, man-yr

Bottom ash disposal requirement,
  kg/h (ton/h)
                  58.6 (200)

                  Residual oil
117.2  (400)

Residual oil
205.1  (700)

Residual oil
5.05
(1335.1)
3.0
0.1
41,714
(149,800)
15
30.87
(65,400)
478 (400)
55
569
4.04 (64.0)
10
3
3
10.11
(2670.2)
3.0
0.1
41,714
(149,800)
15
61.73
(130,800)
478 (400)
55
885
8.08 (128.0)
18
4
4
17.69
(4672.9)
3.0
0.1
41.714
(149,800)
15
108.03
(228,900)
478 (400)
55
1453
14.14 (224.0)
23
4
7
                  Negligible
Negligible
Negligible

-------
                      TABLE 18.
               DESIGN  PARAMETERS FOR FIELD-ERECTED,  WATER-TUBE
                    BOILERS  FIRING  DISTILLATE OIL
10
K>
Thermal input, MH  (10  Btu/h)      58.6 (200)      117.2  (400)    205.1 (700)

Fuel


Fuel rate, n»3/h
           (gal/h)

Analysis
  % sulfur
  % ash             ,
  Heating value, MJ/m
                (Btu/gal)

Excess air, %

Plue gas flow rate, m /s
                   (acfm)

riue gas temperature,  °K (*F)

Load factor, %

Utility requirements
  Electricity, kW
  Process water, liters/s (gpm)

Manpower requirements
  Direct labor, man-yr
  Supervision, man-yr
  Maintenance labor, man-yr

Bottom ash disposal requirement,
  kg/h (ton/h)                    Negligible     Negligible     Negligible
Distillate
oil
5.45
(1438. 8)
0.5
Trace
38,712
(139,000)
15
29.07
(61,600)
450 (350)
55
569
4.04 (64.0)
10
3
3
Distillate
oil
10.89
(2877.7)
0.5
Trace
38,712
(139,000)
IS
58.14
(123,200)
450 (350)
55
885
8.08 (128.0)
18
4
4
Distillate
oil
19.06
(5036.0)
0.5
Trace
38,712
(139,000)
15
101.76
(215,600)
450 (350)
55
1453
14.14 (224.0)
23
4
7

-------
                  TABLE 19.
DESIGN PARAMETERS FOR FIELD-ERECTED,  WATER-TUBE

      BOILERS  FIRING NATURAL  GAS
to
U)
Thermal input, MH (10 Btu/h)
Fuel
Fuel rate, m3/s
(ftVh)
Analysis
% sulfur
% ash 2
Heating value, kJ/m ,
(Btu/ftJ)
Excess air, %
Flue gas flow rate, m /•
(acfm)
Flue gas temperature, °K (°F)
Load factor, %
Utility requirements
Electricity, kw
Process water, liters/a (gpm)
Manpower requirements
Direct labor, man-yr
.Supervision, man-yr
Maintenance labor, man-yr
58.6 (200)
Natural gas
15.7
(200,000)
Trace
Trace
37,218
(1000)
15
29.50
(62,500)
450 (350)
55
569
4.04 (64.0)
10
3
3
117.2 (400)
Natural gas
3.15
(400,000)
Trace
Trace
37,218
(1000)
15
59.04
(125,100)
450 (350)
55
885
8.08 (128.0)
18
4
4
205.1 (700)
Natural gas
5.51
(700,000)
Trace
Trace
37,218
(1000)
15
103.31
(218,900)
450 (350)
55
1453
14.14 (224.0)
23
4
7
                 Bottom ash disposal requirement,
                   kg/h (ton/h)                  Negligible    Negligible    Negligible

-------
BOILER CONFIGURATION



     Boiler configuration was specified as an initial step in the



selection of representative boilers.





DESIGN HEAT INPUT RATE



     This rate is based on the available capacities of the boil-



ers within the selected configurations.  The selection of the



capacity range reflects the most common capacities within a par-



ticular boiler configuration.





FUEL ANALYSIS



     Fuel type for each boiler was chosen as part of the initial



selection process.  The fuel analyses presented in Table 20 for



natural gas, distillate oil, and residual oil were determined



from data about "average" fuels presented by Babcock & Wilcox



 (1972).  The Babcock & Wilcox analysis of Birmingham natural gas



was selected as average.  The values selected for distillate oil



represent No. 2 fuel oil; they were selected from the middle of



the ranges presented, except for sulfur content, which was



selected from the upper part of the range for evaluation of a



distillate oil with a relatively high sulfur content.  The



analysis for the residual oil was selected from the ranges of



values given for No. 6 fuel oil; again, all values were taken



from the middle of the ranges except the sulfur value, which



comes  from the upper part of the range so that a high-sulfur



residual oil can be evaluated.
                              24

-------
                           TABLE 20.   ULTIMATE ANALYSES  OF  FUELS  SELECTED FOR  THE BOILERS*

-------
     Four coal analyses were used to represent the major coal-
producing areas and classes of coals available in the United
States.  Data from Babcock & Wilcox (1972) served as the basis for
the analyses of eastern high-sulfur, high-ash, bituminous coal;
eastern low-sulfur, low-ash, low-moisture, bituminous coal; and
western low-^sulfur, low-ash, high-moisture, subbituminous coal.
Versar, Inc. provided the analysis of eastern medium-sulfur, high-
ash, low-moisture bituminous coal.

FUEL CONSUMPTION
     Given the heat input rate specified for each selected boiler
in Table 1, fuel consumption was calculated by dividing the heat
input rate by the heating value of the fuel used.  For example,
if a package, water-tube, underfeed stoker with a heat input rate
of 8.8 MW thermal  (30 x 106 Btu/h) fires eastern coal at 27,447
kJ/kg, the amount of fuel required is equal to 8800 kJ/s T
27,447 kJ/kg, or 0.32 kg/s.
     Because input capacities are specified, it is not necessary
to consider the efficiencies of boiler heat transfer or fuel
burning.

EXCESS AIR USAGE
     The amount of excess air selected for each boiler type is
based on practical knowledge of good boiler operating practices.
Table 21 presents ranges  (percentages by weight) of excess air
common to different boiler types.  A value for each boiler was
                                26

-------
      TABLE  21.
TYPICAL AMOUNTS OF EXCESS AIR SUPPLIED
 TO FUEL-BURNING EQUIPMENTS
     Fuel
       Type of burners
Excess air,
% by weight
Pulverized coal
Coal
Fuel oil

Natural gas
     Partially water-cooled
      for dry-ash-removal

     Spreader stoker

     Chain-grate and
      traveling-grate stokers

     Underfeed stoker

     Multifuel and flat-flame

     Multifuel
  15-40

  30-60


  15-50

  20-50

  10-20

   7-15
  Babcock & Wilcox,  1963.
                              27'

-------
selected out of this range, based upon previous experience and
data on boiler operating characteristics.
     A mass balance was then performed to obtain the amount of
excess air.  The combustion air was assumed to have a temperature
of 27°C (80°F), a relative humidity of 60 percent, and a pressure
of 101 kPa  (14.7 psi).  The amount of air required for complete
combustion of the fuel was calculated on a molal basis from the
ultimate analysis of the fuel and the emission rates of the vari-
ous flue gas constituents.
     An example of the procedure is shown below using the pack-
age, water-tube, underfeed-stoker boiler with a heat input of 8.8
MW thermal  (30 x 106 Btu/h).
     The molal configuration for each of the gaseous constituents
of the flue gas  (determined by emission factors) is calculated by
dividing the mass rate by the molecular weight of the constitu-
ent.  The results for the example boiler are shown below:
          Constituent                   moles/h
     Carbon monoxide  (CO)                 0.09
     Hydrocarbons  (as CH4)                0.07
     Sulfur dioxide  (SO2)                 2.80
     Nitrogen oxides  (as NO2)             0.23
     The molal rate of each component is then calculated using
the  fuel mass rate per hour and the ultimate analysis of the
fuel.   The  results for the example boiler are tabulated below:
                              28

-------
                         Mass rate/
Fuel constituent         kg/h  (Ib/h)          Molal  rate
Carbon  (C)               12.44  (1646)           137.1
Hydrogen  (H2)             0.85   (113)            56.1
Sulfur  (S)                0.68    (90)             2.8
Oxygen  (O2)               1.26   (167)             5.2
Nitrogen  (N2)             0.25    (33)             1.2
Water (H20)               1.69   (223)            12.4
     The remaining flue gas constituents  (C02,  H20,  N2)  are  cal-
culated by molal balance by subtracting the calculated  moles of
emissions  (U.S. EPA, 1975) from the moles of  equivalent components
in the fuel.  For example, the CO and CH. represent  part of  the
carbon from the fuel.  Assuming the remaining carbon is oxidized
to CO2/  the molal quantity of C02 is 137.17 moles of carbon  minus
0.09 moles of CO minus 0.07 moles of CH4 or 137.01 moles of  CO2.
The results of similar analyses for the other flue gas  constit-
uents of the example boiler are as follows:
          Constituent              Molal quantity
            C02                       137.0
            H20                        68.5
            N2                          1'1
     To calculate the stoichiometric oxygen required, each flue
gas constituent is examined in terms of equivalent oxygen con-
tent.  The following is a presentation of data  for the  example
boiler.
                              29

-------
  Flue gas       Moles        Moles of ©2        Moles of
constituent    per hour   per mole constituent   per hour
CO 2
CO
CH4
SO,
H20
N0x (as N02)
N?
137.0
0.09
0.07
2.80
68.5
0.23
1.1
1.0
0.5
0.0
1.0
0.5
1
0.0
137.0
0.4
0.0
2.8
34.2
0.23
0.0
     Total                                        174.27

     Of the 174.3 moles of O2 required, the O2 in the coal sup-

plies 5.2 moles and the H.O in the coal supplies 6.2 moles.

Therefore the theoretical requirement from the combustion air  is

162.9 moles of 02.  The excess air for this boiler  is 50 percent

of stoichiometric.  Therefore the total oxygen required is 1.5

times the theoretical requirement, or 244.4 moles.  It was

assumed that the combustion air  is 21 percent oxygen and 79

percent nitrogen.  Therefore the N2  required is 919 moles.   The

weight of dry air supplied is then 15,256 kg/h  (33,564 Ib/h).  At

the previously assumed combustion air conditions, 6.0212 mole  of

water is contained in the wet air per mole of dry air  (24 moles

of H2O total).  The total wet combustion air supplied is then

15,453 kg/h  (33,996 Ib/h).


FLUE GAS CHARACTERISTICS

     The volume of the exit flue gas is dependent upon its compo-

sition, the amount of excess air, and the exit  temperature.  The

                               30

-------
total moles of the various flue gas constituents was determined

for each boiler in the excess air calculations.  At standard

conditions, the volume of a mole of gas is 10.2 m   (359 ft  ),

assuming ideal behavior.  Therefore the volume of the flue  gas at

standard conditions can be calculated.

     The actual volume of the flue gas must be calculated at the

flue gas temperature.  Assumed temperatures of the exit flue gas

from each boiler were based on typical temperatures from previous

boiler studies.  The calculated volumes of flue gas were then

adjusted from standard conditions to the actual temperature.  It

was assumed that the flue gas pressure is constant at 101 kPa

(14.7 psi) .

     For example, for a package, water tube,  under feed-stoker

boiler with a heat input of 8.8 MW thermal (30 x 10  Btu/h)  ,

total dry flue gas was calculated to be 1135.9 moles.   On a wet

basis, flue gas was calculated to be 1228.4 moles.  At the assumed

exhaust temperature of 478°K (400°F)  the flue gas volume is:

                            •a
     1228.4 moles/h x 10.2 in /mole x


          21,938 m3/h (775,204 ft3/h)
                                     2730
     21,938 m3/h * 3600 s/h =6.09 m3/s (12,900 ft3/min)



LOAD FACTOR

     Assumed load factors for the boilers were based on ranges of

load factors for industrial boilers.   Battelle (Locklin,  et al.,

1974) estimated load factors in industrial/ commercial boilers to

range from 30 to 80 percent.  Selection of values from the range
                               31

-------
for each representative boiler was based on previous boiler



studies and data on typical load factors.  The load factors are



believed to be representative of new industrial boilers supplying



process steam.





UTILITY REQUIREMENTS



     A boiler facility requires electricity to operate a variety



of equipment.  The equipment items include fans, controls,



pulverizers or stokers, feeders, crushers, conveyors, pumps,



compressors, lights, heating equipment, air conditioning, and



instrumentation.  For each boiler facility an estimate was made



of the electrical requirements for these equipment  items based on



boiler plants of similar size.



     Also a boiler requires make-up water to replace that lost in



the steam-condensation cycle.  For each of the boilers it was



assumed that 20 percent of the total water requirement is lost in



every condensate cycle.





MANPOWER REQUIREMENTS



     The labor required to operate a boiler facility consists of



operating labor, supervision, and maintenance labor.  The labor



requirement is based upon the number of men required to operate



the boiler on a continuous  (24 hour) basis.  The plant is assumed



to operate on a three shift basis with each man working the



equivalent of 2190 hours per year.  The estimates of manpower



requirements  reflect a conservative case with state laws that
                               32

-------
require an operator at all times for a boiler facility taken  into

account.  A less conservative approach could reduce these  labor

requirements to some extent and in cases of multiple boilers  at  a

single site, the requirement would be significantly reduced.


BOTTOM ASH DISPOSAL REQUIREMENT

     For coal-fired boilers the bottom ash disposal requirement

is calculated based upon the fly ash emission factors presented

in AP-42 (U.S. EPA, 1977).  For each type of boiler, the percent

bottom ash is as follows:

          Coal-firing mechanism    Percent bottom ash

          Pulverizer                      20
          Spreader stoker                 35
          Overfeed stoker                 35
          Chain grate stoker              75
          Underfeed stoker                75
          Other stokers                   75

The hourly rate of bottom ash is calculated as follows :

                                                   % bom ash
Bottom ash (tons/h)  = Coal feed (tons/h)  x

For example, for the 8 . 8 MW thermal (30 x 10  Btu/h) package

water-tube underfeed stoker boiler firing eastern high-sulfur

coal the bottom ash rate is :

Bottom ash = (1.27 ton/h)(10.6 * 100) (75 T 100)

           =0.10 ton/h
                               33

-------
                    REFERENCES FOR SECTION 2


Babcock & Wilcox.  1963.  Steam - Its Generation and Use, Thirty-
     seventh Edition.  New York City.

Babcock & Wilcox.  1972.  Useful Tables for Engineers and Steam
     Users, Twelfth Edition.  New York City-

Locklin, D.W., H.H. Krause, A.A. Putnam, E.L. Kropp, W.T. Reid,
     and M.A. Duffy.  1974.  Design Trends and Operating Problems
     in Combustion Modification of Industrial Boilers.  EPA
     R-802402, Battelle-Columbus Laboratories, Columbus, Ohio.

U.S. EPA.  1977.  Compilation of Air Pollutant Emission Factors,
     AP-42, Third Edition.
                                 34

-------
               3.0  COST ESTIMATES FOR NEW BOILERS





     Estimates were developed for the cost of new installations



of the boilers described in Section 2.  An outline of the pro-



cedures used in developing the costs is followed by the cost



estimates.






COST ESTIMATING PROCEDURE



     Cost of a boiler facility includes the costs of basic equip-



ment, the costs of installation, and the costs of operating and



maintaining the boiler.  A capital cost estimate is developed by



the following steps:



     0    Define the battery limits of the facility.



     0    Develop a list of equipment required.



     0    Obtain prices for each equipment item.



     0    Calculate installation costs.



     0    Calculate indirect capital costs.



     Costs are all-inclusive,  accounting for the material and



labor needed to complete an operational boiler plant.   The esti-



mates were prepared from a detailed equipment summary.  Estimates



of erection costs are based on experience and on actual cost of



erection at similar plants.



     Battery limits of the facility extend from the fuel-receiving



equipment to the ash disposal  site, inclusively.  Excluded are
                                35

-------
steam and condensate piping beyond the boiler building and
pollution control equipment.  Costs of ducting and the stack are
included.
     Based on guidelines presented by H.K. Ferguson  (Coffin,
1978), an equipment list was developed for each boiler.  The
major equipment items are described below.
     Water enters the system through a treatment process—for
this study a standard Zeolite softening system.  The makeup water
is then fed to a deaerator, which has a 15-minute holding capacity
at full flow.  The return condensate is piped to the condensate
return tank.  It is assumed that 20 percent makeup is required.
The overflow storage tank for the condensate return tank is sized
to hold the condensate generated in 1 hour at full load capacity.
     A continuous-blowdown flash tank and drain heat recovery
system recover all available heat from both the flash steam and
the drains.
     Two boiler feed pumps are provided, 100 percent capacity
each.  Automatic recirculation shutoff is not included.  A fixed
minimum-flow bypass orifice is used for simplicity.
     Each oil-fired boiler has 100 percent Maximum Capacity
Rating  (MCR) oil-burning capability and includes a storage tank
and transfer pump facility.  In the plant, a pump and heater set
are provided, consisting of two pumps  (100 percent capacity) for
firing of No. 6 oil.  Capacity of the  storage tank provides
approximately 7 days firing at MCR.
                                36

-------
     Coal is stored in the plant in overhead bunkers supported by
the building steel.  Coal is loaded into the bunkers by a con-
veying system designed to fill the bunkers completely during an
8-hour shift.  Bunker capacity is sufficient to operate the plant
for 24 hours at full load.
     The conveying system includes the under-track hopper, which
supplies a coal silo with 10 days' storage; a -bucket elevator or
belt conveyor, depending on building height (100 ft maximum for a
bucket elevator);  and an over-bunker tripper conveyor to load
each bunker section.  A crusher included with the hopper allows
some sizing of the coal feed.
     The stoker-fired plants include an under-bunker conveyor,
tripper mechanism, and a nonsegregating conical distributor to
the stoker hopper.
     The pulverized-coal-fired plant includes gravimetric feeders
to the pulverizers.
     Ash handling systems of the pneumatic type (dry)  transport
fly ash and bottom ash to a temporary storage silo for later
removal by truck.   The bottom ash handling equipment includes a
clinker breaker.
     Except for the pulverized-coal-fired boiler,  which requires
an air heater to dry the coal sufficiently, all boilers are
equipped with economizers.
     Controls are provided to regulate combustion, feedwater, and
flame safety.  The pulverized-coal-fired boiler also has an
electronic pulverizer control system for safe and reliable start-
ing of the pulverizers.
                               37

-------
     The building, constructed of insulated steel, includes a
small office area and employees' washroom.  No provision is made
for an enclosed control room for the operators; rather, the
boiler control panels are free-standing in front of the boiler
firing aisle.  Lighting, ventilation, ladders, gratings, and
painting are included.
     A 1 to 2 acre parcel of land is allocated to each of the
boilers.  Table 22 lists the basic equipment and installation
items included in' the capital cost estimates.  Table 23 lists the
sources of data used in estimating capital costs.  Costs were
obtained for the low-sulfur bituminous coal; costs were then
apportioned to the subbituminous, medium-sulfur, and high-sulfur
bituminous coals by use of factors obtained from boiler manu-
facturers.  Indirect capital costs were estimated as a percentage
of the installed equipment costs.  Table 24 lists the percentages
used for each item.
     The costs are based on a Greenfield boiler installation with
no pollution control equipment, located in the Midwest. Regional
cost factors may be used to estimate costs in areas other than
the Midwest.  The costs were adjusted to June 30, 1978.
     Annual operating and maintenance costs are based on require-
ments for labor, materials, and utilities as cited by manufac-
turers of boilers and auxiliary equipment and presented in  Section
2, together with the unit costs specified for the Midwest in
Table 25.
                               38

-------
TABLE  22.   BASIC EQUIPMENT AND INSTALLATION ITEMS INCLUDED
                 IN A NEW BOILER FACILITY
  Equipment:

       Boiler (with fans and ducts)
       Stack
       Instrumentation
       Pulverizers or Stoker system
       Feeders
       Crushers
       Deaerator
       Heaters
       Boiler feed pumps
       Condensate systems
       Water treating system
       Chemical feed
       Compressed air system
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel oil system

  Installation:

       Foundations and supports
       Piping
       Insulation
       Painting
       Electrical
       Building
                           39

-------
 TABLE  23.  SOURCES OF COST DATA FOR EQUIPMENT AND INSTALLATION
                 ITEMS INCLUDED IN BOILER PLANTS
  Equipment item
Sources of cost data
Boiler (with fans and ducts)
Stacks
Instrumentation
Pulverizers or stoker system
Feeders
Crushers


Deaerator


Heaters

Boiler feed pumps



 (continued)
Babcock & Wilcox Co.
Combustion Engineering, Inc.
Cleaver-Brooks Division of
Aqua-Chem
Erie City Energy Division of Zurn
E. Keeler Co.

Airtek
Rust Engineering
Richardson Cost Estimating Manual

Aedes Associates, Inc.
Babcock & Wilcox Co.
Combustion Engineering, Inc.
Cleaver-Brooks Division of
  Aqua-Chem
Erie City Energy Division of Zurn
E. Keeler Co.

Babcock & Wilcox Co.
Combustion Engineering, Inc.
Cleaver-Brooks Division of
  Aqua-Chem
Erie City Energy Division of Zurn
E. Keller Co.

Jeffrey Manufacturing Co.
Babcock & Wilcox Co.
Combustion Engineering, Inc.
Cleaver-Brooks Division of
  Aqua-Chem
Erie City Energy Division of Zurn
E. Keeler Co.

Pennsylvania Crusher Co.
Richardson Cost Estimating Manual

Chicago Heater Co.
Cochrane Environmental Systems

Richardson Cost Esimating Manual

Ingersoil-Rand
Richardson Cost Estimating Manual3
Richardson Cost Estimating Manual
                               40

-------
TABLE  23.   (continued)
Equipment items
 Sources  of  cost  data
Condensate system

Water treatment system


Chemical feed


Compressed air system


Coal handling system



Ash disposal system



Thawing equipment

Fuel oil system


Foundations and supports

Piping

Insulation

Painting

Electrical

Building
 Richardson  Cost  Estimating  Manual3

 Crane  Cochran  Zeolite
 Calgon Corp.

 Milton Roy  Co.
 Richardson  Cost  Estimating  Manual3

 Ingersoil-Rand
 Richardson  Cost  Estimating  Manual

 Jeffrey Manufacturing Co.
 Caterpillar Co.
 Richardson  Cost  Estimating  Manual

 Allen-Sherman-Hoff, Inc.
 United Conveyor
 Richardson  Cost  Estimating  Manual3

 Aedes  Associates, Inc.

 Coen Co.
 Aedes  Associates, Inc.

 Aedes  Associates, Inc.

 Aedes  Associates, Inc.

 Aedes  Associates, Inc.

 Aedes Associates, Inc.

Aedes Associates, Inc.

Aedes Associates, Inc.
  Richardson,  1978.
                              41

-------
      Table 24.   TYPICAL VALUES3 FOR INDIRECT CAPITAL COSTS
          Cost item
     Range of values
Engineering
Construction and field
  expenses

Contractor's fee
Shakedown


Performance test

Contingency
Working capital
8 to 20 percent of installed cost.
High value for small projects; low
value for large projects.
Recommend 10 percent

7 to 20 percent of installed cost.
Recommend 10 percent

10 to 15 percent of installed cost,
Recommend 10 percent

1 to 6 percent of installed cost.
Recommend 2 percent

Minimum value of $2000.

10 to 30 percent of total direct
and indirect costs dependent upon
accuracy of estimate.
Recommend 20 percent

15 to 35 percent of the total
annual operation and maintenance
costs.
Recommend 25 percent
  Devitt,  1979.
                              42

-------
 TABLE 25.  ANNUAL UNIT COSTS FOR OPERATION AND MAINTENANCE
                     (June 1978 dollars)
Cost factors
Direct labor, $/man-hour
Supervision, $/man-hour
Maintenance labor, $ /man-hour
Electricity, mills/kWh
3
Process water, $/10 gal
Coal, $/106 Btu
Eastern high-sulfur
Eastern medium-sulfur
Eastern low- sulfur
Subbituminous
No. 2 fuel oil, $/106 Btu
No. 6 fuel oil, $/106 Btu
Natural gas, $/106 Btu
Bottom ash disposal, $/ton
Recommended value
12.02a
15.63b
14.63a
25.80°
0.15d

0.74e
0.95f
1.166
0.42e
3.00g
2.2lg
1.95h
40. OO1
Engineering News-Record, June 29,  1978, pp. 52-52.  Average for
Chicago, Cincinnati, Cleveland, Detroit, and St. Louis.

Estimated at 30 percent over direct labor rate.

EEI members publication for June,  1978.  Average for Boston,
Chicago, Indianapolis, Houston, San Francisco,  and Los Angeles.

Peters, M.S., and K.D. Timmerhaus.   Plant Design and Economics
for Chemical Engineers, 2nd Edition.  McGraw-Hill Book Co.  New
York 1968.  p. 772.  Adjusted to 1978 prices using Nelson
Refinery Operating Cost Indexes for Chemicals.   July 1978.

Coal Outlook, July 18, 1978.  Spot market prices.

Average of prices for high- and low-sulfur coal.

Electrical Week, May issues, 1978.   Spot market prices.
              -•
Gas Facts, 1977.  American Gas Association.  Average U.S. price.

Based on $2/ton-mile and disposal  site 20 miles from plant.
                             43

-------
     Table 26 lists the elements of annual operating and main-
tenance costs; Table 27 indicates the methods used in developing
the costs; the boiler parameter tables  (Tables 2 through 19) show
the manpower requirements on which the labor costs are based.
     The cost of disposing of bottom ash from a coal-fired boiler
is based on a 32-km  (20-mi) one-way haul to ultimate disposal in
an environmentally sound landfill.  The bottom ash is assumed to
be wetted to 20 percent moisture and hauled in covered trucks.
The disposal cost components include truck loading, washing the
loaded trucks, truck transportation, road cleaning and repair,
truck unloading, washing the unloaded trucks, and landfill fees,
including treatment.  The ash disposal operation is conducted by
an outside contracting firm rather than the company itself.  The
waste disposal cost  is estimated at $44/Mg  ($40/ton).  This is a
conservative estimate of the average cost for a typical industrial
boiler with a heat input of about 30 MW thermal  (100 x 106 Btu/h).
Although the waste disposal cost can vary greatly depending upon
the haul distance and the method of disposal, this conservative
estimate reflects good environmental practice.
     Another component of operating cost is overhead, which
represents a business expense that is not charged directly to a
particular part of the process but is allocated to it.  Overhead
costs  include administrative, safety, engineering, legal, and
medical services; payroll expenses including PICA; employee
benefits; and public relations.  Overhead costs are usually
                                44

-------
TABLE 26.   DIRECT ANNUAL OPERATION AND MAINTENANCE COST ITEMS
                    ASSOCIATED WITH BOILERS
                   Operational labor
                   Supervision
                   Maintenance labor
                   Replacement parts
                   Electricity
                   Process water
                   Fuel
                   Waste disposal
                   Chemicals
                              45

-------
TABLE  27.   METHODS  USED TO ESTIMATE  DIRECT ANNUAL COSTS
     Cost item

  Operational labor



  Supervision



  Maintenance labor



  Replacement parts



  Electricity

    Oil or gas-fired boilers
    Stoker units
    Pulverized-coal-fired units
  Process water
  Fuel
  Haste disposal
  Chemicals
Method of obtaining cost

Multiply manpower requirements from
parameter tables by rate given in
Table 25.

Multiply manpower requirements from
parameter tables by rate given in
Table 25.

Multiply manpower requirements from
parameter tables by rate given in
Table 25.

Aedes Associates, Inc. determined
percentages of total equipment cost
based on actual jobs  (8 to 21%).

Based on major equipment and light-
ing loads.
  59 to 1453 kW
  162 to 1001 kW
  1754 to 6920 kW

Multiply kW by operating hours to
obtain annual kWh.  Multiply annual
kWh by electric rate given in Table
25.

Requirement calculated assuming 80
percent return of condensate  (20%
make-up).  Multiply annual usage by
water rate given in Table 25.

Fuel requirement calculated based
on design heat input multiplied by
hours per year operated based on
load factors given in Tables 2 to
19.  Multiply annual fuel require-
ment by appropriate rate from Table
25.

Requirement calculated from total
ash in fuel minus the quantity
emitted as fly ash.  Multiply the
annual quantity of wash by an
average cost of $40/ton for dis-
posal in an environmentally sound
landfill 20 miles from the plant
site.

Requirement calculated assuming
constant water quality and 80 per-
cent return of condensate  (20%
Bake-up).  Multiply amount of
chemicals used by average costs
obtained from chemical suppliers.
                                    46

-------
presented as payroll overhead and plant overhead.  Following are

the values used for each:

     Payroll overhead = 30 percent of operating labor

     Plant overhead = 26 percent of labor and materials.

     The capital investment in a boiler is generally translated

into annual capital charges.  These charges, along with the

annual operating costs, represent the total annualized cost of a

boiler.

     EPA classifies annual capital-related charges for cost

purposes under the following components:   general and administra-

tive costs, taxes, insurance;  a capital-recovery factor, which

represents a levelized principal and interest payment; and

interest on working capital.  The first three components are set

at a total of 4 percent of depreciable investment.  The capital-

recovery factor was determined at 10 percent interest over the

life of a facility.

     Capital recovery factors  are based on the following boiler

life expectancies:

                                      Expected life,
          Boiler type                    years	

     Package Scotch fire-tube                20
     Package water-tube                     30
     Field-erected water-tube                45

From these values for boiler life and the assumed interest rate

of 10 percent, the capital recovery factors calculated for each

boiler type are 'as follows:
                               47

-------
                                     Capital recovery
          Boiler type                   factor, %

     Package Scotch fire-tube              11.75
     Package water-tube                    10.61
     Field-erected water-tube              10.14


COST ESTIMATES

     Costs are estimated for all 59 of the typical boilers iden-

tified in Section 2.  The basic boiler costs were obtained as

verbal or written -quotations from various boiler manufacturers

including Babcock and Wilcox; Cleaver Brooks; Zurn Industries,

Inc.; Erie City; and Combustion Engineering.  Capital cost esti-

mates for auxiliary equipment (e.g., water treatment systems) are

based on quotations obtained from manufacturers in related projects,

     The estimated costs are summarized in Table 28 for the

package water-tube underfeed-stoker boilers firing the four

different coal types.  Detailed cost breakdowns for each of these

boilers are presented in Appendix A.

     The estimated costs are summarized for field-erected water-

tube spreader-stoker boilers firing the four coal types in Table

29.  The detailed costs are presented in Appendix A.

     Table 30 summarizes the estimated costs of field-erected

water-tube, pulverized-coal-fired boilers.  Detailed cost break-

downs are presented in Appendix A.

     The estimated costs for package fire-tube boilers are sum-

marized in Table  31 with the detailed costs presented in Appendix

B.
                               48

-------
               TABLE  28.   ESTIMATED CAPITAL AND ANNUALIZED COSTS OF PACKAGE, WATER-TUBE,
                                 UNDERFEED-STOKER BOILERS FIRING COAL
»
Size,
MM (10* BtU/h)
4.4 (15)
4.4 (IS)
4.4 (15)
4.4 (IS)
8.8 (30)
8.8 (30)
8.8 (30)
8.8 (30)
17.6 (60)
17.6 (60)
17.6 (60)
17.6 (60)
Coal
Eastern high-sulfur
Eastern low-sulfur
Subbituminous
Eastern medium-sulfur
Eastern high-sulfur
Eastern low-sulfur
Subbltuninous
Eastern medium- sulfur
Eastern high-sulfur
Eastern low-sulfur
Subbituminous
Eastern medium-sulfur
Capital costs
Grand total. $
1,245,000
1,094,600
1,487,300
1,133,200
1,891,300
1,665,200
2,257,100
1,723,000
3,021,800
2,670,700
3,594,100
2,758,100
Annual! zed costs
Direct cost
plus overhead
leas fuel, $
469.900
453,300
485,100
462,800
565,800
538,700
587,100
554,000
847,000
802,000
873,400
832.000
Fuel
Coats, $
58,300
91,500
33,100
74,900
116,700
182.900
66,200
149,800
233,400
365,800
132,500
299,600
Capital
charges, $
176,900
154,700
212,500
160,500
269,800
236,300
323,600
244,900
431,100
378,600
515,600
391,900
Total, $
705.100
699,500
730,700
698,200
952.300
957.900
976,900
448,700
1,511,500
1,546.400
1,521.500
1,523,500
Parameter
table No.
2
2
2
2
3
3
3
3
4
4
4
4
Cost
table
A-l. A-2
A-3, A-4
A-5, A-6
A-7, A-i
A-9. A-10
A-ll, A-12
A-l 3, A-14
A-15, A-16
A-17, A-l>
A-19, A- 20
A-21, A-22
A-23. A-24
vo

-------
                    TABLE 29.   ESTIMATED CAPITAL  AND ANNUALIZED  COSTS OF  FIELD-ERECTED, WATER-TUBE,
                                          SPREADER-STOKER  BOILERS  FIRING  COAL
Slie,
MH (106 BtU/h)
22.0 (75)
22.0 (75)
22.0 (75)
22.0 (75)
44.0 (ISO)
44.0 (150)
44.0 (150)
44.0 (150)
58.6 (200)
58.6 (200)
58.6 (200)
58. t (200)
Coal
Eastern high-sulfur
Eastern low-sulfur
Subbltumlnous
eastern medium-sulfur
Eastern high-sulfur
Eastern low-sulfur
Subbitumlnous
Eastern medium-sulfur
Eastern high-sulfur
Eastern low-sulfur
Subbltuminous
Eastern medium-sulfur
Capital costs
Grand total, $
4.587,700
4.064.200
5,440,700
4,192.200
8.784,200
7,804,100
10,395,800
8.041,900
10,510,200
9,355,200
12,411,400
9.637,500
Annual lied coats
Direct cost
(jlus overhead
less fuel, $
898, BOO
858,500
935,600
878,800
1,265,700
1,187,300
1,334.300
1,229,000
1,641,000
1,541.900
1,731,700
1,596,200
Fuel
Costs. $
291,700
457,300
165,600
374,500
583,400
914,500
331,100
749,000
777,900
1,219,400
441,500
998,600
Capital'
charges, $
638,300
563,100
760,000
581,700
1,225,900
1,084.500
1.455,700
1,119,500
1,465,000
1,298,000
1,736,500
1,339,700
Total. $
1,828,800
1,178,900
1,861.200
1,835,000
3,075,000
3,186,300
3.121,100
3,097,500
3,883,900
4,059,300
3,909,700
3.934,500
Parameter
table No.
5
5
5
5
•
C
6
C
7
7
7
7
Cost
table
A-25, A-26
A- 27, A-28
A-29, A-30
A-31, A-32
A-33, A-34
A- 35, A- 36
A-37. A-38
A-39, A-40
A-41. A-42
A-43, A-44
A-45, A-46
A-47, A-4B
UI
o

-------
TABLE 30.   ESTIMATED CAPITAL AND ANNUALIZED  COSTS OF  FIELD-ERECTED, WATER-TUBE,
                         PULVERIZED-COAL-FIRED  BOILERS
Size,
MM (106 Btu/h)
58.6 (200)
SB. 6 (200)
58.6 (200)
58.6 (200)
117.2 (400)
117.2 (400)
117.2 (400)
117.2 (400)
205.1 (700)
205.1 (700)
205.1 (700)
205.1 (700)
Coal
Eastern high-sulfur
Eastern low-sulfur
Subbltumlnous
Eastern medium-sulfur
Eastern high-sulfur
Eastern low-sulfur
Subbituninous
Eastern medium-sulfur
Eastern high-sulfur
Eastern low-sulfur
Subbitumlnous
Eastern medium-sulfur
Capital costs
Grand total, S
12.202,400
10,823,200
14,468,400
11.161,500
22,638,000
20,094,000
26,836,600
20,707,300
36,490.200
32.369.200
43,060,300
33,302,400
Annual lied coat*
Direct cost
plus overhead
less fuel, $
1', 766,900
1.656.200
1,901,500
1,701,400
3,068,300
2,878,200
3.288,800
2,960,700
4,200,000
3,912.500
4,509,900
4,044,300
Fuel
Coats. $
777.900
1,219,400
441,500
998.600
1,555,800
2,438,800
883,000
1,997,000
2,722,600
4,267,900
1,545,300
3.495,200
Capital
charges, $
1.702,900
1,504,400
2,025,600
1,554,100
3,159,500
2,792,500
3,758,200
2.883,000
5,096,800
4,500,900
6,035,000
4,639,500
Total, $
4,247,700
4,380.000
4,368,600
4,254,100
7.783,600
8,109,500
7,930,000
7,840,700
12,019.400
12,681,300
12,090,200
12,179,000
Parameter
table No.
8
8
8
8
9
9
9
9
10
10
10
10
Cost
table
A-49. A-50
A-51, A-52
A-53, A- 54
A-S5, A-56
A-57, A-58
A-59, A-60
A-61. A-62
A-63. A-64
A-CS, A-66
A-67. A-68
A-69, A-70
A-71. A-72

-------
                  TABLE 31.  ESTIMATED CAPITAL AND ANNUALIZED COSTS OF PACKAGE, FIRE-TUBE BOILERS
Site
MM (106 Btu/h)
1.5 (5)
4.4 (IS)
8.5 (29)
1.5 (5)
4.4 (15)
• .5 (29)
1.5 (5)
4.4 (15)
8. 5 (29)
Fuel
Residual oil
Residual oil
Residual oil
Distillate oil
Distillate oil
Distillate oil
Natural gas
Natural gas
Natural gas
Capital costs
grand total, $
243,700
404,200
602,500
241. BOO
404,800
610,900
236,600
389,300
580,900
Annua 11 zed costs
Direct cost
plus
overhead
leas fuel, $
201,300
322,400
347,800
201,300
322,400
347,800
201,300
322,400
347,800
Fuel
cost, $
43.600
130,700
252,600
59,100
177.400
343,000
38,400
115,300
222,900
Capital
charges, $
35,500
58,100
87,200
34,900
57,600
87,300
34,400
56,000
84,300
Total. $
280,400
511,200
687,600
295,300
557,400
778,100
274,100
493,700
655,000
Paraneter
table No.
11
11
11
12
12
12
13
13
13
Cost
table
B-l, 8-2
B-3, B-4
B-5, B-6
B-7, B-8
B-9, B-10
B-ll, B-12
B-13, B-ll
B-l 5, B-K
B-l 7. B-B
in
NJ

-------
     Estimated costs of dual-fuel water-tube boilers firing
residual oil/natural gas are summarized in Table 32 with detailed
costs presented in Appendix C.  Table 33 summarizes the estimated
costs of dual-fuel water-tube boilers firing distillate oil/natural
gas.   Detailed costs are presented in Appendix C.
                              53

-------
                TABLE 32.  ESTIMATED CAPITAL AND ANNUALIZED COSTS OF DUAL-FUEL, WATER-TUBE
                                      BOILERS FIRING RESIDUAL OIL/NATURAL GAS
Boiler type
Package
Package
Package
Package
Field-erected
Field-erected
Field-erected
Size, HH
(10* Btu/h)
8.8 (30)
17.6 (60)
29.3 (100)
44.0 (ISO)
58.6 (200)
117.2 (400)
205.1 (700)
Capital
cost*
Grand
total, $
(oil/gas)
802, 900/
793,500
1.230.500/
1,211,700
1.734,000/
1,702,700
2.276.600/
2,229,600
7.412.000/
7,349,300
13,225,9007
13,100,600
21,331,4007
21,112,200
Annual ii«d coat*
Direct coat
plus overhead
leaa fuel, $
(oil/gas)
359,400
420,200
520,800
625,900
868,100
1,393,700
1,898,300
Fuel
Coat a, f
(oil/gaa)
319,4007
281,900
638.9007
563,700
1,064,8007
939,500
1,597,2007
1,409,300
2,129.6007
1,879.000
4,259,1007
3,758,000
7,453,4007
6,576,600
Capital
chargea, $
(oil/gaa)
110,3007
109,300
168,5007
166,600
236,3007
233,200
308,6007
303,900
1,019,1007
1.012,900
1.815,3007
1,802.800
2.924,3007
2,902,400
Total, 9
(oil/gaa)
789,1007
750,600
1,227,6007
1,150,500
1,821,9007
1,693,500
2.531,7007
2,339,100
4,016,8007
3.760,000
7,468,1007
6,954,500
12,276,0007
11,377,300
Parameter
tablea
(oil/gaa)
14/16
14/16
14/16
14/16
17/1$
17/19
17/1>
Coat
tables
C-l, C-2
C-3, C-4
C-5, C-6
C-7, C-l
C-9, C-10
C-ll, C-12
C-13, C-14
in
•u

-------
                  TABLE 33.   ESTIMATED CAPITAL AND ANNUALIZED COSTS OF DUAL-FUEL, WATER-TUBE
                                      BOILERS FIRING DISTILLATE OIL/NATURAL GAS
Boiler type
Package
Package
Package
Package
Field-erected
Field-erected
Field-erected
Site, HH
(106 Btu/h)
8.8 (30)
17.6 (60)
29.3 (100)
44.0 (ISO)
58.6 (200)
117.2 (400)
205.1 (700)
Capital
coat a
Grand
total, $
(oil/gaa)
817, 200/
779,300
1,26 7, OOO/
1,191,100
1.806.500/
1,680,000
2,393,9007
2.204,200
7.483.5007
7,230,500
13.379.900/
12,874,000
21.609.400/
20,724,100
Annual lied coata
Direct coat
plua overhead
leae fuel, $
(oil/gaa)
359,400
420.200
520,800
625,900
868,100
1.393,700
1,898,300
Fuel
Coata, |
(oil/gaa)
433, 600/
281,900
867. 200/
563.700
1,443,4007
939,500
2.16B.100/
1,409.300
2,890,800/
1,879,000
5,781,600/
3,758,800
10, 117, BOO/
6,576,600
Capital
charges, $
(oil/gaa)
111, OOO/
107,200
171, 200/
163,600
242,6007
229.900
319,2007
300,200
1,021,3007
996.000
1.821.300/
1,770,700
2.935.900/
2,847,400
Total, *
(oil/gaa)
904. OOO/
748,500
1.458.600/
1,147,500
2,208,800/
1,690,200
3.113.200/
2,335,400
4,780,2007
3,743,100
8,996,6007
6,922,400
14, 952, OOO/
11,322,300
Parameter
tablea
(oil/gaa)
15/16
15/16
15/16
15/16
11/19
18/19
18/19
Coat
tablea
C-15, C-16
C-17, C-H
C-19, C-20
C-21, C-22
C-23, C-24
C-25. C-26
C-27, C-28
Ul

-------
                    REFERENCES FOR SECTION 3
Coffin, B.D.  1978.  Costing Examples of Industrial Applications,
     coal-fired Boiler Plants.  H.K. Ferguson Co., Cleveland,
     Ohio.

Richardson Engineering Services, Inc.  1978.  Process Plant Con-
     struction Estimating and Engineering Standards.  Solana
     Beach, California.

Devitt, T., P. Spaite, and L. Gibbs.  1979.  The Population and
     Characteristics of Industrial/Commercial Boilers.  PEDCo
     Environmental, Inc., Cincinnati, Ohio.
                             56

-------
                 4.0  EQUATIONS FOR BOILER COSTS

     In order to obtain costs for use by OAQPS in the overall
economic evaluation of various regulatory options on new boiler
installations, it was necessary to develop relationships between
boiler capacity, fuel, and costs.  In this task, equations were
developed to describe the costs of package fire-tube boilers
firing a variety of fuels, package water-tube boilers firing
a variety of fuels, and field-erected water-tube boilers also
firing a variety of fuels.  The following sections present the
methodology used in deriving these equations and the results of
the analysis.

METHODOLOGY
     The basic steps involved in deriving new boiler cost equa-
tions were:
     0    Detailed cost estimates
     0    Segmenting costs into appropriate categories
     0    Plotting costs versus input capacity
     0    Determination of cost equation form
     0    Derivation of cost equation
Detailed Cost Estimates
     Detailed cost estimates were made for the 51 boiler/fuel/
capacity combinations described previously.  In addition, from
previous work, 8 detailed cost estimates were available.
                               57

-------
Segmenting Costs Into Appropriate Categories
     In this study, equations were to be derived to describe five
major components of costs including equipment cost, direct installa-
tion costs, indirect installation costs, variable annual operating
and maintenance costs, and nonvariable annual operating costs.
     The equipment cost, direct installation costs, and indirect
installation costs are presented as subtotals in each detailed
boiler cost breakdown.  Table 34 lists all items included in each
subtotal.  Note that-contingencies, land, and working capital
have been excluded from the cost equations.  This allows the
reader to use site-specific values.  For the coal-fired boilers,
some of the equipment and direct installation cost items also
vary dependent upon the type of coal being burned.  Table 34 also
indicates the items which vary with coal types.
     The direct cost and overhead components of annual cost were
classified as either variable  (dependent upon the period of time
the boiler operated) or non-variable  (independent of boiler
operational time).  Table 35 shows the items classified as variable
or nonvariable.   It should be noted that although fuel is shown
as a variable cost item, for purposes of this study this cost was
excluded from the cost equations because the fuel cost can be
calculated separately as a direct product of fuel price and fuel
usage.  Capital charges have also been excluded.
Plotting Costs Versus Input Capacity
     The next step was to plot the costs in each category against
boiler input capacity by major boiler type/fuel classification.
For example, equipment costs for the three residual oil-fired
fire-tube  boilers were plotted against the appropriate heat input
                                  58

-------
      TABLE 34.  FORMAT FOR PRESENTATION OF CAPITAL COSTS
                     OF INDUSTRIAL BOILERS
CAPITAL COSTS
DATE OF ESTIMATE   June 30, 1978	(FOR COSTS INDEXING)
     EQUIPMENT COST

      Boiler  (with fans & ducts)              Variable
      Stack                                  	
      Instrumentation                        	
      Pulverizers or stokers
      Feeders                                 Variable
      Crushers                                Variablg-
      Deaerators                             	
      Heaters                                	
      Boiler feed pumps                      	
      Condensate systems                     	
      Water treating system                  	
      Chemical feed                          	
      Compressed air system
      Coal handling system                    Variable
      Ash disposal system                     Variable
      Thawing equipment                      	
      Fuel-oil system                        	
     Total Equipment Cost                    	

     INSTALLATION COST, DIRECT

      Boiler  (including founda-
       tions and steel)                       Variable
      Stack                                  	
      Instrumentation
      Pulverizers                             Variable
      Feeders                                 Variable
      Crushers                                Variable
      Deaerators                             	
      Heaters                                	
      Boiler feed pumps                      	
      Condensate system                      	
      Water treating system                  	
      Chemical feed                          	
      Coal handling system                    Variable
      Ash disposal system                     Variable
      Thawing equipment                      	
      Fuel-oil system                        	
N.A. - Not applicable.
(continued)
                          59

-------
 TABLE  34.   (continued)
INSTALLATION COSTS, DIRECT (cont.)

     Foundations and supports
     Ductwork (not incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation cost

TOTAL DIRECT COSTS
  (equipment + installation)

INSTALLATION COSTS, INDIRECT

     Engineering
      (10% of direct costs)
     Construction and field expense
      (10% of direct costs)
     Construction fees
      (10% of direct costs)
     Start-up (2% of direct costs)
     Performance tests  (minimum  $2000)

TOTAL INDIRECT COSTS

Contingencies
  (20% of direct and indirect costs)

Total Turnkey Costs
   (direct+indirect+contingencies)

Land

Working capital  (25% of total direct
  operating costs)

GRAND TOTAL
  (turnkey+land+working  capital)
                                                    Variable
                                                    Variable
                                                    Variable
                                                    Variable
                                                    Variable
                                                    Variable
                                                      N/A
                                                      N/A
                                                      N/A
                                                      N/A
N/A - Not applicable.


-------
 TABLE 35.  FORMAT FOR PRESENTATION OF ANNUALIZED COSTS
                  OF INDUSTRIAL BOILERS
Non— vari a hi g>
Non— variable
Mon — Va f "i a h 1 e»
DIRECT COST

     Direct labor
     Supervision
     Maintenance labor
     Maintenance materials
     Replacement parts
     Electricity
     Steam
     Cooling water
     Process water
     Fuel
     Bottom ash disposal
     Chemicals

     Total direct cost

OVERHEAD

     Payroll (30% of direct labor

     Plant (26% of labor, parts & maint.)

     Total overhead costs

BY-PRODUCT CREDITS

CAPITAL CHARGES

     G & A, taxes & insurance
      (4% of total turnkey costs)

     Capital recovery factor
      (      % of total turnkey costs)

     Interest on working capital
      (10% of working capital)

          Total capital charges

TOTAL ANNUALIZED COSTS
Nnn— x/ari a hi e*
Non-variable
Variable
Variable
Variable
Variable
Variable5
Variable
Variable
Variable



Non-variable

Non-variable

Non-variable

     N/A
     N/A
     N/A
     N/A
     N/A
     N/A
a Not included in the equations.
N.A. - Not applicable.
                         61

-------
capacities (i.e. 5, 15, and 29 x 106 Btu/h).  This step was fol-
lowed for all major boiler-fuel types including plots for residual
oil-fired fire-tube, distillate oil-fired fire-tube, natural gas-
fired fire-tube, stoker coal-fired package water-tube, residual
oil/natural gas-fired package water-tube, distillate oil/natural
gas-fired package water-tube, stoker coal-fired field-erected
water-tube, pulverized coal-fired field-erected water-tube,
residual oil/natural gas-fired field-erected water-tube, and
distillate oil/natural gas-fired field-erected water-tube.
Determination of Cost Equation Form
     Each plot is then examined to determine the approximate form
of the cost equation.  If the plot is a straight line, the equation
is a simple binomial of the form y = ax + b where a and b are con-
stants.  If the plot is curved, the points are replotted on log-
log scales and on semi-log scales.  If the plot on log-log scales
is a straight line, the equation is of the form y = ax , where a
and b are constants.  If the plot on semi-log scales is a straight
                                             cx
line, the equation will be of the form y = ab  , where a, b, and
c are constants.
Derivation of Cost Equation
     Depending upon which equation exhibits the best fit, a re-
gression analysis  is performed via a computer program which will
determine the values of the constants for each equation form.
Boiler Cost Equation Results
     The cost equations for the package water-tube underfeed stok-
er boilers are presented in Table 36.  Equations for field-erected
water-tube spreader stoker boilers are presented in Table 37.  Table
                               62

-------
         TABLE 36.  COST EQUATIONS FOR PACKAGE, WATER-TUBE,
                UNDERFEED-STOKER BOILERS3,b,c,d,e,f,g
Equipment cost
     y = 66,392x°*622  (11,800/z) + 2257x°*819
Direct installation cost
     y = 53,219x°*65  (11,800/z) + 2882x'°'796
Indirect installation cost
     y = 40,188x0'646  (11,800/z)0-926
Variable annual operating cost
     y = [6012x°*689  (11,800/z)0'9 (A/10.6)0'3] (H/5256)
Nonvariable annual cost
     y = [308,900 -I- 7176x] (11,800/z)°'166
a x = heat input rate (106 Btu/h)
  y = actual cost  ($)
c z = heating value of coal (Btu/lb)
  A = ash content of coal  (%)
£
  H = equivalent hours operated per year at maximum capacity.
  Costs are in June 1978 dollars.
^ Applicable to heat inputs ranging from 15 to 60 x 10  Btu/h.
  Does not include fuel cost.
  Excludes capital charges.
                                63

-------
          TABLE 37.  COST EQUATIONS FOR FIELD-ERECTED,
         WATER-TUBE/ SPREADER-STOKER BOILERSa'b>c'd'e'*»9
Equipment cost (size <150 x 106 Btu/h)
     y = 25,052x°*906 (11,800/z) + 4,626x°'868
Equipment cost (size > 150 x 106 Btu/h)
     y = 25,052x°*906 (11,800/z) + 14,205x°'714
Direct installation cost (size <_ 150 x 106 Btu/h)
     y = 45,468x°'757 (11,800/z) + 2,919x°*869
Direct installation cost (size > 150 x 10  Btu/h)
     y = 45,468x°-757 (11,800/z) + 9464x°'647
Indirect installation cost
     y = 21,154x°-867 (11,800/z)0'86
Variable annual operating cost*1
     y= 3,566x°*743 (11,800/z) (A/10.6) °'3 (^^)
Nonvariable annual costx
     y = 66,924x°*574  (11,800/z)°'188

a x = heat input rate (10  Btu/h)
  y = actual cost  ($)
  z = heating value of coal (Btu/lb)
  A = ash content of coal  (%)
e H = -equivalent hours operated per year at maximum capacity.
  Costs are in June 1978 dollars.
g Applicable to heat inputs ranging from 75 to 200 x 10  Btu/h,
  Does not include fuel cost.
1 Excludes capital charges.
                               64

-------
38 presents cost equations for field-erected, water-tube, pulver-
ized-coal-fired boilers.  The cost equations for package fire-tube
boilers are presented in Table 39.  In Table 40 are presented cost
equations for dual-fuel water-tube boilers firing residual oil/
natural gas.  The cost equations for dual-fuel water-tube boilers
firing distillate oil/natural gas are presented in Table 41.
     The algorithms are varied in form from boiler to boiler and
from fuel to fuel.  The equations are an approximation of the way
the actual costs of boilers vary with size, fuel,  and type.   The
equations are composites of the costs of many components that do
not vary in the same manner between sizes, boiler  types, and fuels.
However, comparisons of costs derived from the equations to  de-
tailed costs presented in the appendices, show that the equations
give costs at least within 8 percent of the detailed cost
estimates.
Plots of Various Detailed Cost Items Versus Heat Input Design Capacity
     Plots of different detailed cost items versus heat input
have been included.  The primary advantage of the  plots is that
cost trends are more readily observed than by examination of the
algorithms or detailed cost estimates.  They are also useful in
comparing costs of different boiler types.
     Figures 1, 2, and 3 provide the equipment costs of boilers
with fans and ducts versus heat input.  Plots of total turnkey
costs versus heat input are shown in Figures 4 through 8. Figures
9 through 11 show pperating and maintenance costs  (direct cost
plus overhead less fuel cost) versus equivalent hours of opera-
tion per year at maximum capacity for selected boilers.
                               65

-------
           TABLE 38.  COST EQUATIONS FOR FIELD-ERECTED,
     WATER-TUBE, PULVERIZED-COAL-FIRED BOILERS*>b,C,d,e,f,g
Equipment cost
     y = [904,426 + 14,564x] (11,800/z) + 92,079 + 3,107x
Direct installation cost
                n R R f>
     y = 24,019xu'°° • (11,800/z) + 17,395 + l,254x
Indirect installation cost
     y = 22,782x°'877 (11,800/z)0'87
Variable annual operating cost
     y « l,586x*'uuu  (11,800/z)0'9  (A/10.6)0'13

Nonvariable annual cost1
     y = 60,380x°'604  (lLJOOjO.26
                         z

a x = heat input rate  (106 Btu/h)

  y = actual cost  ($)

c z = heating value of coal  (Btu/lb)

  A = ash content of coal  (%)
o
  H = equivalent hours operated per year at maximum capacity.

  Costs are in June 1978 dollars.

^ Applicable to heat inputs ranging from 200 to 700 x 10  Btu/h,

  Does not include fuel cost.
1 Excludes capital charges.
                               66

-------
              TABLE 39.  COST EQUATIONS FOR PACKAGE
                   FIRE-TUBE BOILERSa'b,c,d,e
                       Residual Oil-Fired

Equipment cost                     y = 17, 3 6 Ox0*557
Direct installation cost           y = 4324x + 56,177
Indirect installation cost         y = 2317x + 29,749

Variable annual operating cost
  (heat input 5 15 x 106 Btu/h)    y = [580x + 3900]  (H/3942)

Variable annual operating cost
  (heat input >15 x 106 Btu/h)     y = [914x - 1114]  (H/3942)
Nonvariable annual
  (heat input <15 x 106 Btu/h)     y = ll,530x + 136,850
Nonvariable annual
  (heat input >15 x 106 Btu/h)     y = 900x + 296,300

            Natural Gas-Fired or Distillate Oil-Fired

Equipment cost                     y = 15,981x°*561
Direct installation cost           y = 4261x + 56,041
Indirect installation cost         y = 2256x + 28,649

Variable annual operating cost
  (heat input <15 x 106 Btu/h)     y = [580x + 3900] (H/3942)

Variable annual operating cost
  (heat input >15 x 10^ Btu/h)     y = [914x - 1114] (H/3942)

Nonvariable annual costg
  (heat input <15 x 10$ Btu/h)     y = ll,530x + 136,850

Nonvariable annual costg
  (heat input >15 x 106 Btu/h)     y = 900x + 296,300


  x = heat input rate (10  Btu/h) .

  y = actual cost ($} .
  H = equivalent hours operated
  per year at maximum capacity.

  Costs in June 1978 dollars.
  Applicable to heat inputs
  ranging from 1 to 30 x 106 Btu/h.

  Does not include fuel cost.
g Excludes capital charges.

                               67

-------
       TABLE 40.  COST EQUATIONS FOR WATER-TUBE, DUAL-FUEL
         BOILERS FIRING RESIDUAL OIL/NATURAL QASa/b/c/d
                         Package Units'
Equipment cost
Direct installation cost
Indirect installation cost
Variable annual operating cost
Nonvariable annual cost9
                             y * 15,925x
                             y = 54f833x
0.775
0.364
0.613
                             y = 16,561x
                             y = [202x + 24,262]  (H/4818)
                             y = 2048x + 266,078
                      Field-Erected Units
Equipment cost
Direct installation cost
Indirect installation cost
Variable annual operating cost
Nonvariable annual cost^
                             y = 86.02x + 714,824
                             y = 18,427x°-866
                             y = 16,306x°*835
                             y = [269x + 25,884]  (H/4818)
                             y = 31,628x°'61
a x = heat input rate  (106 Btu/h).
  y = actual cost  ($).
  H
equivalent hours operated per year at maximum capacity.
  Costs in June 1978 dollars.
e                                                      6
  Applicable to heat inputs ranging from 30 to 150 x 10  Btu/h.
  Does not include fuel cost.
g Excludes capital charges.
  Applicable to heat input ranging from 200 to 700 x 10  Btu/h.
                             68

-------
       TABLE 41.  COST EQUATIONS FOR WATER-TUBE, DUAL-FUEL
        BOILERS FIRING DISTILLATE OIL/NATURAL GASa,b,c,d
                         Package Units
Equipment cost
Direct installation cost
Indirect installation cost
Variable annual operating cost
Nonvariable annual costg
y = 14,850x
y = 54,620x
0.786
0.361
0.618
y = 15,952x
y = [202x + 24,262]  (H/4818)
y = 2048x + 266,078
                      Field-Erected Units
Equipment cost
Direct installation cost
Indirect installation cost
Variable annual operating cost
Nonvariable annual cost"
y = 8372x + 711,271
y = 18,262x°'865
y = 4812x + 431,779
y = [269x + 25,884]  (H/4818)
y = 31,628x°-61
a x = heat input rate (106 Btu/h).
  y = actual cost ($).
c H = equivalent hours operated per year at maximum capacity.
  Costs in June 1978 dollars.
e Applicable to heat inputs ranging from 30 to 150 x 10  Btu/h.
  Does not include fuel cost.
g Excludes capital charges.
h Applicable to heat input ranging from 200 to 700 x 10  Btu/h.
                             69

-------
I/I
o
•o
•o
c
S
CJ
5750
5500
5250
5000
4750
4500
4250
4000
3750
3500
3250
3000
2750
2500
2250
2000
1750
1500
1250
1000
  750
  500
  250
    0
                                          FIELD-ERECTED,
                                            PULVERIZED
                      FIELD-ERECTED,
                      SPREADER  STOKERS
              PACKAGE, UNDERFEED STOKERS
         0  40  80 120 160 200 240 280 320 360 400 440 480 520 560 600 640 680  720
                                 HEAT INPUT,  106  Btu/hr
     Figure 1.   Equipment costs of  water-tube  boilers (with fans and ducts)
                firing eastern low-sulfur coal  versus heat Input.
                                       70

-------
                  55


                  50


                  45


                  40
              S  35
                  30
                  25
                 20


                 15


                 10
                  5h


                  0
                          5    10    15    20    25    30

                           HEAT INPUT. 106 Btu/hr
  Figure 2.   Equipment costs of package,  fire-tube boilers  (with fans and
ducts) firing residual oil,  distillate  oil  or  natural gas versus heat input,
                                  71

-------
               200       300       400       500

                    HEAT INPUT, 106 Btu/hr
600
700
Figure 3.  Equipment costs of dual-fuel, water-tube boilers
 (with fans and ducts} firing residual  oil/natural  gas or
       distillate oil/natural gas versus heat input.

                         72

-------
  3600
  3400
  3200
  3000
  2800
£2600
o

^2400
o
to
o
2200


2000


1800


1600


1400


1200
  1000
     10    15    20    25    30    35    40    45    50
                             HEAT INPUT, 106 Btu/h
                                                         55    60    65
          Figure 4.  Total turnkey costs  of coal-fired,  package,
           underfeed-stoker boilers firing  eastern  high-sulfur
             coal or subbituminous coal versus  heat input.
                                  73

-------
 L SUBBITUMINOUS
       COAL
                          EASTERN HIGH-SULFUR COAL
SO   100   150   200   250   300   350   400   450   SOO   550   600   650   700
                      NEAT INPUT. 106 Btu/h
        Figure 5.   Total turnkey costs of  coal-fired,
     field-erected boilers firing eastern high sulfur
        coal or subbiluminous  coal versus  heat input.
                            74

-------
    500

    475

    450

    425

    400

    375

    350

    325

 „  300
 s.
 
-------
  1.8





  1.7





  1.6





  1.5





  1.4







 *o
 •o


^1.2
 
-------
  20.0


  19.0


  18.0


  17.0


  16.0


  15.0
  13.0
£12.0
o
  11.0


  10.0


   9.0


   8.0


   7.0
   6.0
     150   200   250   300   350   400   450   500   550   600   650   700

                            HEAT INPUT, 106 Btu/h
     Figure 8.  Total  turnkey costs  of  dual-fuel, field-erected
  boilers firing residual  oil/natural gas or distillate oil/natural
                        gas versus  heat input.
                                   77

-------
CO
VO
o
 J_
 0)
 o.
 tn
 10
 o
 "O
 to
 o
 o
 UJ
 o
 •a:
 CS
 O.
 o
     45
     40
     35
30
     25
     20
     15
     10
 	 PACKAGE UNDERFEED-STOKER BOILER,
              EASTERN HIGH-SULFUR COAL-FIRED,
              30 x 106 Btu/h

 	 PACKAGE, FIRE-TUBE BOILER, c
              RESIDUAL OIL-FIRED, 5 x 10b Btu/h

             PACKAGE FIRE-TUBE BOILER,
              RESIDUAL OIL-FIRED, 15 x 106 Btu/h

      	PACKAGE FIRE-TUBE BOILER,   ,
              RESIDUAL OIL-FIRED, 29 x 106 Btu/h   _
>
\	PACKAGE, WATER-TUBE, DUAL-FUEL BOILERS,
              RESIDUAL OIL/NATURAL GAS-FIRED,
              30 x 106 Btu/h

             PACKAGE, UNDERFEED-STOKER BOILER,
              EASTERN HIGH-SULFUR COAL-FIRED,
              15 x 106 Btu/h
            876 1752 2628 3504 4380 5256 6132 7008 7884 8760
            EQUIVALENT  HOURS  OPERATED  PER  YEAR AT MAXIMUM CAPACITY
   Figure  9.  Operating  and maintenance costs  (less fuel costs)
    for  various  boilers  versus  equivalent  hours operated per year
    at maximum capacity.
                                   78

-------
 4->
 CO
 Ol
 o
 T3
 CO
 O
 LU
 O

 •a:

 UJ
 •en
 03
 QC
 UJ
 a.
 o
     16
     14
     12
10
 8
 E   4
                        PACKAGE, UNDERFEED-STOKER BOILER-,
                         EASTERN.HIGH-SULFUR COAL-FIRED,
                         60 x 106 Btu/h

               -——  PACKAGE, WATER-TUBE, DUAL-FUEL BOILER,
                         RESIDUAL,OIL/NATURAL GAS-FIRED,
                         150 x 106 Btu/h
FIELD-ERECTED, SPREADER-STOKER BOILER,
 EASTERN HIGH-SULFUR COAL-FIRED,
 75 x 106 Btu/h

FIELD-ERECTED, SPREADER-STOKER BOILER,
 EASTERN HIGH-SULFUR COAL-FIRED,
 150 x 106 Btu/h
          876 1752 2628 3504 4380 5256 6132 7008 7884 8760

         EQUIVALENT HOURS OPERATED PER YEAR AT MAXIMUM CAPACITY
Figure 10.   Operating and maintenance costs  (less  fuel  costs)  for
  various boilers versus equivalent hours  operated per  year at
                        maximum capacity.
                               79

-------
      8
 3
 +>
 OQ

VO
 o
 J_
 
-------
             APPENDIX A

DETAILED CAPITAL AND ANNUALIZED COST
    TABLES FOR COAL-FIRED BOILERS

-------
 TABLE A-l.   ESTIMATED CAPITAL COSTS OF A PACKAGE,WATER-TUBE,
    UNDERFEED-STOKER BOILER FIRING EASTERN HIGH-SULFUR COAL
                WITH A THERMAL INPUT OF 4.4 MW
         (15 x 106 Btu/h;  150 psig/sat. temp,  design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
     EQUIPMENT COSTS

      Boiler  (with fans & ducts)
      Stack
      Instrumentation
      Stoker
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler  (including founda-
       tions and steel)
      Stack
      Instrumentation
      Stoker
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. - Not applicable.
                       $ 204,800
                           2,700
                       Incl. w/boiler
                       Incl. w/boiler
                       Incl. w/coal handling
                       Incl. w/coal handling
                       Incl. w/coal hand1ing
                            N.A.	
                           6,100	
                           5,000	
                           5,000	
                           1,400	
                            N.A.	
                          90,100	
                          65,500	
                            N.A.	
                            N.A.	

                         $380,600	
                         $  69.000	

                            1.500	
                        Incl. w/boiler
                        Incl. w/boiler
                        Incl. w/coal handling
                        Incl. w/coal handling
                            N.A.	
                            N.A.	
                            1.200	
                            1,000	
                            1,500	
                        	400	
                           53,800	
                           26,900	
                            N.A.	
                            N.A.
                               A-l

-------
 TABLE A-l.  (continued)
 INSTALLATION COSTS, DIRECT  (cont.)

     Foundations  and  supports                        23,400
     Ductwork  (not  incl. w/boiler)                 	N.A.
     Piping                                          23,400
     Insulation                                      17,6QU
     Painting                                         4.100
     Electrical                                      20.000
     Buildings                                       93.600

     Total installation cost                      .<: i^7 ,4nn

 TOTAL  DIRECT COSTS
  (equipment + installation)                       S 718.000

 INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct  costs)                       $  71,800
     Construction and field expense
       (10% of direct  costs)                          71,800
     Construction fees
       (10% of direct  costs)                          71,800
     Start-up  (2% of  direct costs)                   14,400
     Performance  tests  (minimum  $2000)    .            3,000

 TOTAL  INDIRECT COSTS                              $ 232,800

 Contingencies
  (20%  of direct and indirect costs)               $ 190,200

 Total  Turnkey Costs
   (direct+indirect+contingencies)                 1,141,000

 Land                                                  2,000

 Working capital  (25%  of total direct
  operating costs)                                   102.000

 GRAND  TOTAL
  (turnkey+land+working capital)  ,                SI.245.OOP


N.A. - Not applicable

a Quote from Zurn Industries,  Inc., May 25, 1978.

                             A-2

-------
TABLE A-2.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE, WATER-TUBE,
     UNDERFEED-STOKER BOILER FIRING EASTERN HIGH-SULFUR COAL
                 WITH A THERMAL INPUT OF 4.4 MW
           (15 x 106 Btu/h; 150 psig/sat. temp, design)
     DIRECT COST

          Direct  labor                             $ 131,600
          Supervision                                 68,500
          Maintenance labor                           64.100
          Maintenance materials
           Replacement  parts                           46.800
           Electricity                                 25.800
           Steam                                   	N.A.
           Cooling  water                            	N.A.
           Process  water                            	200
           Fuel                                        58,300
           Bottom ash disposal                         10.500
           Chemicals                                    2.000

           Total direct cost                        $ 407.800

      OVERHEAD

           Payroll  (30% of direct  labor             $  39.500

           Plant (26% of  labor,  parts  & maint.)        80,900

           Total overhead costs                     $ 120,400

      BY-PRODUCT CREDITS                                 N.A.

      CAPITAL CHARGES

           G & A, taxes & insurance
            (4%  of  total  turnkey costs)             $  45.600

           Capital  recovery factor
            (  10.61%  of total turnkey  costs)          121.100

           Interest on  working capital
            (10% of working capital)                   10.200

                Total capital charges               $ 176.900

      TOTAL ANNUALIZED  COSTS                        S 705.1QQ

      a  Included with replacement  parts.
      N.A.  - Not applicable.
                                A-3

-------
 TABLE A-3.  ESTIMATED CAPITAL COSTS OF A PACKAGE, WATER-TUBE,
    UNDERFEED-STOKER BOILER FIRING EASTERN LOW-SULFUR COAL
                WITH A THERMAL INPUT OF 4.4 MW
         (15 x 10° Btu/h; 150 psig/sat. temp, design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
     EQUIPMENT COSTa

      Boiler (with fans & ducts)
      Stack
      Instrumentation
      Stoker
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler (including founda-
       tions and steel)
      Stack
      Instrumentation
      Stoker
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. - Not applicable.
                        $ 175,000
                            2,700
                        Incl.  w/boiler
                        Incl.  w/boiler
                        Incl.  w/coal handling
                        Incl.  w/coal handling
                        Incl.  w/condensate
                             N.A.	
                            6,100	
                            5.000	
                            5.000	
                            1,400
                             N.A.
                           77,000
                           56.000
                             N.A.
                             N.A.
                        $  J28.200
                        $   59.000
                            1.500
                        Incl.  w/boiler
                        Incl.  w/boiler
                        Incl.  w/coal handling
                        Incl.  w/coal handling
                            N.A.	
                            N.A.	
                            1.200	
                            1.000	
                            1,500	
                        	400	
                           46.000	
                           23.000	
                            N.A.	
                            N.A.	
                               A-4

-------
 TABLE A-3.   (continued)
INSTALLATION COSTS, DIRECT  (cont. )

     Foundations and  supports                      — 20,000
     Ductwork  (not  incl. w/boiler)                 - N.A.
     Piping                                          2°'OQO
     Insulation                                      15.000
     Painting                                         3. 500
     Electrical                                      20.000
     Buildings                                       80.000

     Total  installation  cost                      $ 2 Q 2 , 1 n n

TOTAL  DIRECT COSTS
  (equipment +  installation)                       $ 620/300

INSTALLATION COSTS,  INDIRECT

     Engineering
       (10%  of  direct costs)                       $  62,000
     Construction and field expense
       (10%  of  direct costs)                          62,000
     Construction fees
       (10%  of  direct costs)                          62,000
     Start-up  (2% of direct costs)                   1 2 F 4 0 0
     Performance tests (minimum $2000)    .            3^000

TOTAL  INDIRECT COSTS                             $ 7.ni ,
 Contingencies
  (20% of direct and indirect costs)               $ 164.300

 Total Turnkey Costs
   (direct+indirect+contingencies)                   986.000

 Land                                                 2,000

 Working capital (25% of total direct
  operating costs)                                   106.600

 GRAND TOTAL
  ( turnkey* land+working capital)                  Sl.Q94r6on


N.A. - Not applicable.
aQuote from Zurn Industries, Inc., May 25, 1978.
                              A-5

-------
TABLE A-4.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE, WATER-TUBE,
    UNDERFEED-STOKER BOILER FIRING EASTERN LOW-SULFUR COAL
                WITH A THERMAL INPUT OF 4.4 MW
          (15 x 1()6 Btu/h; 150 psig/sat. temp, design)


    DIRECT COST

         Direct  labor                             $ 131.600
         Supervision                                 68,500
         Maintenance labor                           £&,1nn
         Maintenance materials                     	*
         Replacement  parts                           40.000
         Electricity                                 22.000
         Steam                                        N.A.
         Cooling  water                             	N.A.
         Process  water                             	200
         Fuel                                        91.500
         Bottom ash disposal                          6.300
         Chemicals                                    2.000

         Total direct cost                        $ 426.200

    OVERHEAD

         Payroll  (30% of direct  labor             $  39,500

         Plant (26% of  labor,  parts  & maint.)        79.100

         Total overhead costs                     S 118.600

    BY-PRODUCT CREDITS                                 N.A.

    CAPITAL CHARGES

         G  & A, taxes & insurance
          (4%  of  total  turnkey costs)             S  39.400

         Capital  recovery factor
          (10.61  % of total turnkey  costs)          104.600

         Interest on  working capital
          (10% of working capital)                   10.700

              Total capital charges               $ 154.700

    TOTAL ANNUALIZED  COSTS                        S 699.500
    	'__.	_,.	
    a  Included with replacement  parts.
    N.A.  -  Not applicable.
                              A-6

-------
 TABLE A-5.  ESTIMATED CAPITAL COSTS OP A PACKAGE,  WATER-TUBE,
       UNDERFEED-STOKER BOILER FIRING SUBBITUMINOUS COAL
                WITH A THERMAL INPUT OF 4.4 MW
         (15 x 106 Btu/h; 150 psig/sat. temp,  design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
     EQUIPMENT COST

      Boiler  (with fans & ducts)
      Stack
      Instrumentation
      Stoker
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler  (including founda-
       tions and steel)
      Stack
      Instrumentation
      Stoker
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. - Not applicable.
                       $  252,000
                            2,700
                       Incl. w/boiler
                       Incl. w/boiler
                       Incl. w/coal handling
                       Incl. w/coal handling
                       Incl. w/condensate
                             N.A.	
                            6,100	
                            5,000	
                            5,000	
                            1,400	
                             N.A.	
                          110,900	
                           80,600	
                             N.A.	
                             N.A.	

                       $  463,700	
                       $   85,000	

                            1,500	
                       Incl. w/boiler
                       Incl. w/boiler
                       Incl. w/coal handling
                       Incl. w/coal handling
                             N.A.	
                             N.A.	
                            1,200	
                            1,000	
                            1,500	
                        	400	
                           66,200	
                           33,100	
                             N.A.	
                             N.A.
                               A-7

-------
 TABLE A-5.   (continued)
 INSTALLATION COSTS,  DIRECT (cont.)

      Foundations and supports                       28,800
      Ductwork (not incl.  w/boiler)                     N.A.
      Piping                                         28,800
      Insulation                                     21,600
      Painting                                        5,000
      Electrical                                     20,000
      Buildings                                     115,200

      Total installation cost                     S 409.300

 TOTAL DIRECT COSTS
  (equipment + installation)                       S 873.000

 INSTALLATION COSTS,  INDIRECT

      Engineering
       (10% of direct costs)                       S  87.300
      Construction and field  expense
       (10% of direct costs)                          87.300
      Construction fees
       (10% of direct costs)                          87.300
      Start-up (2% of direct  costs)                   17,500
      Performance tests (minimum $2000)    .            3,000

 TOTAL INDIRECT COSTS                             S 282.400

 Contingencies
  (20% of direct and  indirect costs)               S 231.100

 Total Turnkey Costs
   (direct+indirect+contingencies)                 1.386.500

 Land                                                 2.000

 Working capital (25% of total direct
  operating costs)                                    98.8QQ

 GRAND TOTAL
  (turnkey+lahd+working capital)                  $1
N.A. - Not applicable
aQuote from Zurn Industries, Inc., May 25, 1978
                              A-8

-------
TABLE A-6.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE, WATER-TUBE,
        UNDERFEED-STOKER BOILER FIRING SUBBITUMINOUS COAL
                 WITH A THERMAL INPUT OF 4.4 MW
          (15 x 106 Btu/h; 150 psig/sat. temp, design)


     DIRECT COST

          Direct labor                            $	131,600
          Supervision                                 68'5QO
          Maintenance labor                           64,100
          Maintenance materials
          Replacement parts                           57,600
          Electricity                                 31,600
          Steam                                    	N.A.
          Cooling water                            	N.A.
          Process water                            	200
          Fuel                                        33,100
          Bottom ash disposal                      	6,300
          Chemicals                                    2,000

          Total direct cost                       $  395,000

     OVERHEAD

          Payroll  (30% of direct labor            $   39,500

          Plant  (26% of labor, parts & maint.)        83,700

          Total overhead costs                    $  123.200

     BY-PRODUCT CREDITS                            	N.A.

     CAPITAL CHARGES

          G & A, taxes & insurance
            (4% of  total turnkey costs)            $   55,500

          Capital  recovery factor
            (10.61  * of total turnkey costs)          147,100

          Interest on working capital
            (10% of working capital)                    9,900

               Total capital charges              $  212,500

     TOTAL ANNUALIZED COSTS                       $  730,700

     a Included with replacement parts.
     N.A. - Not applicable.
                               A-9

-------
 TABLE A-7.  ESTIMATED CAPITAL COSTS OF A PACKAGE, WATER-TUBE,
   UNDERFEED-STOKER BOILER FIRING EASTERN MEDIUM-SULFUR COAL
                WITH A THERMAL INPUT OF 4.4 MW
         (15 x 106 Btu/h; 150 psig/sat. temp, design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS INDEXING)
     EQUIPMENT COST3

      Boiler  (with fans & ducts)
      Stack
      Instrumentation
      Stoker
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler  (including founda-
       tions and steel)
      Stack
      Instrumentation
      Stoker
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing .equipment
      Fuel-oil system

N.A. - Not applicable.
                           182.700
                             2,700
                        Incl. w/boiler
                        Incl. w/boiler
                        Incl. w/coal  handling
                        Incl. w/coal  handling
                        Incl. w/condensate
                        	N.A.	
                             6,100	
                             5,000	
                             5.000	
                             1,400	
                        	N.A.	
                            80.400	
                            58,500	
                        	N.A.	
                        	N.A.	
                        S   341.800
                            61.600
                             1.500	
                        Incl. w/boiler
                        Incl. w/boiler
                        Incl. w/coal  handling
                        Incl. w/coal  handling
                        	N.A.	
                        	N.A.	
                             1.200	
                             1.000	
                             1,500	
                        	400	
                            48,000	
                            24,000	
                        	N.A.	
                        	N.A.	
                              A-10

-------
 TABLE A-7.   (continued)
INSTALLATION COSTS, DIRECT  (cont. )

     Foundations and supports                     — 2Q,9QQ
     Ductwork  (not incl. w/boiler)
     Piping                                          20,900
     Insulation                                      15,700
     Painting                                         3,700
     Electrical                                      20,000
     Buildings                                       83,500

     Total installation cost                      $ 303.900

TOTAL DIRECT COSTS
  (equipment + installation)                       $ 645.700

INSTALLATION COSTS,  INDIRECT

     Engineering
       (10% of direct costs)                       $  64.600
     Construction and field expense
       (10% of direct costs)                          64.600
     Construction fees
       (10% of direct costs)                          64.600
     Start-up  (2% of direct costs)                   12,900
     Performance tests (minimum  $2000)   „            3 ,000

TOTAL  INDIRECT COSTS                             $ 209,700

Contingencies
  (20%  of direct and  indirect  costs)               $ 171.100

Total  Turnkey Costs
   ( dir ect+indir ect+contingencies )                 1,026,500

Land                                                  2,000

Working capital  (25% of total direct
  operating costs)                                   104.700

GRAND  TOTAL
  (turnkey+land+working capital)                  Si. 133 r 200
aQuote from Zurn Industries, Inc., May 25, 1978
N.A. - Not applicable.


                              A-ll

-------
TABLE A-8.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE,WATER-TUBE,
   UNDERFEED-STOKER BOILER FIRING EASTERN MEDIUM-SULFUR COAL
                WITH A THERMAL INPUT OF 4.4 MW
          (15 x 106 Btu/h; 150 psig/sat. temp, design)


    DIRECT COST

         Direct labor                           $  131.600
         Supervision                                68.500
         Maintenance labor                          64.100
         Maintenance materials                    	a
         Replacement parts                          41.800
         Electricity                                22.900
         Steam                                        N.A.
         Cooling water                            	N.A.
         Process water                            	200
         Fuel                                       74.900
         Bottom ash disposal                        12.600
         Chemicals                                   2.OOP

         Total direct cost                       S 418.6QQ

    OVERHEAD

         Payroll (30% of direct labor            $  39.500

         Plant (26% of labor,  parts & maint.)        79.600

         Total overhead costs                     S 119.1QQ

    BY-PRODUCT CREDITS                                N.A.

    CAPITAL CHARGES

         G & A, taxes & insurance
          (4% of total turnkey costs)             S  41.100

         Capital recovery factor
          (10.61 % of total turnkey costs)          i08rQnn

         Interest on working capital
          (10% of working capital)                   10.500

              Total capital charges              S 160.500

    TOTAL ANNUALIZED COSTS                       S 6Q8f2nn

    a Included with replacement parts.
    N.A.  - Not applicable.


                              A-12

-------
      TABLE A-9.   ESTIMATED CAPITAL COSTS OF A PACKAGE,
WATER-TUBE, UNDERFEED-STOKER BOILER FIRING EASTERN HIGH-SULFUR
              COAL,. WITH A THERMAL  INPUT OF 8.8 MW
           (30 x 10° Btu/h? 150  psig/sat. temp, design)	
 CAPITAL  COSTS
 DATE  OF  ESTIMATE
in.  1178   (FOR COSTS INDEXING)
      EQUIPMENT COST3

        Boiler  (with fans and ducts)
        Stack
        In strumentation
        Stokers
        Feeders
        Crushers
        Deaerator
        Heaters
        Boiler  feed pumps
        Condensate systems
        Water treating  system
        Chemical feed
        Compressed air  system
        Coal handling system
        Ash disposal system
        Thawing  equipment
        Fuel-oil system

       Total Equipment  Cost

       INSTALLATION COSTS,  DIRECT

        Boiler  (including founda-
         tions  and steel)
        Stack
        Instrumentation
        Pulverizers
        Feeders
        Crushers
        Deaerator
        Heaters
        Boiler  feed pumps
        Condensate system
        Water treating  system
        Chemical feed
        Coal handling system
        Ash disposal system
        Thawing  equipment
        Fuel-oil system
             $  308.900
                  3.000
            Incl. w/boiler _
            Incl. w/boiler _
            Incl. w/coal handling
            Incl. w/coal handling
            _ 5.200 _
            _ N.A. _
                 13.400 _
            _ 7.700 _
            _ 8.000 _
            _ 1.400 _
            _ N.A. _
                136.700 _
                 99.500 _
            _ N.A. _
            _ N.A. _

             $  583.800 _
             $  105.300	

            	1.500	
            Incl. w/boiler	
            Incl. w/boiler
            Incl. w/coal handling
            Incl. w/coal handling
                  2.500	
            	N.A.	
            	3.000	
            	1.100	
            	2.000	
            	800	
                 81.900	
                 41.000	
            	N.A.	
            	N.A.
   N.A. - Not applicable.
                                A-13

-------
TABLE \A-9. (continued)
    INSTALLATION COSTS,  DIRECT (cont.)

     Foundations and supports                	35,100
     Ductwork  (not incl.  w/boiler)           	N.A.
     Piping                                  	41.000
     Insulation                              	29,300
     Painting                                	5 ,900
     Electrical                              	30rOOO
     Buildings                                   140.400

    Total Installation Costs                 $   520.800

    TOTAL DIRECT COSTS
     (Equipment + Installation)               $ 1,104,600

    INSTALLATION COSTS,  INDIRECT

     Engineering
      (10% of direct costs)                   $   110,500
     Construction and field  expense
      (10% of direct costs)                       110,500
     Construction fees
      (10% of direct costs)                       110,500
     Startup (2% of direct costs)             	22,100
     Performance tests (minimum $2000)        	3,500

    TOTAL INDIRECT COSTS                     $   357,100

    Contingencies
     (20% of direct and  indirect  costs)       $   292,300

    Total turnkey costs
     (Direct + Indirect  +  Contingencies)        1,754,000

    Land                                     	2,000

    Working capital (25% of  total  direct
     operating costs)                             135.300

    GRAND TOTAL
     (Turnkey,* Land + Working Capital)       $ 1,891,300
    a Quote from Zurn Industries,  Inc.,  May 25,  1978.

    N.A.  - Not applicable.

                               A-14

-------
              COAL WITH A THERMAL INPUT OF  8.8 MW
          (30 x 106 Btu/h; 150 psig/sat. temp, design)
DIRECT COST
     Direct labor                                 $—
     Supervision                                  —
     Maintenance labor                            —
     Maintenance materials                        —
     Replacement parts                            —
     Electricity                                  —
     Steam                                             1N>^'
     Cooling water                                	N'A;..
     Process water                                	!___
     Fuel                                            116.700
     Bottom ash disposal                              21.000
     Chemicals                                         2.300

     Total direct cost                            $  541.300

OVERHEAD

     Payroll  (30% of direct labor)                $   47.400

     Plant  (26% of labor, parts t maint.)             93.800

     Total overhead costs                         $  141,200
                  /
BYPRODUCT CREDITS                                      N.A.

CAPITAL CHARGES

     G I A, taxes & insurance
       (4% of  total turnkey costs)                 $   70,200

     Capital  recovery factor
       (LO.61* of total turnkey costs)                  186.100

     Interest on working capital
       (10% of working capital)                         13,500

          Total capital charges                   $   269.800

TOTAL ANNUALIZED COSTS                            $   952.300


a Included with replacement parts.

N.A. - Not applicable.

                                 A-15

-------
 TABLE A-ll. ESTIMATED CAPITAL COSTS OF A PACKAGE,  WATER-TUBE,
   UNDERFEED-STOKER BOILER FIRING EASTERN LOW-SULFUR COAL
              WITH A THERMAL INPUT OF 8.8 MW
          (30 x 106 Btu/h; 150 psig/sat. temp,  design)

CAPITAL COSTS
DATE OF ESTIMATE
June 30,  1978
(FOR COSTS INDEXING)
     EQUIPMENT COST

      Boiler (with fans and duct)
      Stack
      Instrumentation
      Stokers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COSTS, DIRECT

      Boiler (including founda-
       tions and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system '

 N.A. - Not applicable.
                     $   264.000	
                    	3.000	
                    Incl. w/boiler
                    Incl. w/boiler
                    Incl. w/coal handling
                    Incl. w/coal handling
                    	5.200	
                    	N.A.	
                    	13.400	
                    	7.700	
                    	8,000	
                    	1,400	
                           N.A.
                        116.800
                         85.000
                           N.'A.
                           N.A.
                        504.500
                         90.000
                          1,500
                    Incl.  w/boiler
                    Incl.  w/boiler
                    Incl.  w/coal handling
                    Incl.  w/coal handling
                   	2,500	
                   	2L.A..	
                   	3,000	
                   	1.100	
                   	2,000	
                   	800	
                   	70.000	
                   	35.000	
                   	N.A.	
                           N.A.
                            A-16

-------
TABLE A-11.(continued)
     INSTALLATION COSTS, DIRECT (cont.)

      Foundations and supports                	30.000
      Ductwock  (not incl. w/boiler)           	N.A.
      Piping                                  	35.000.
      Insulation                                   25.000
      Painting                                	5.000
      Electrical                              	30.000
      Buildings                                   120.000

     Total Installation Costs                 $   450.900

     TOTAL DIRECT COSTS
      (Equipment + Installation)              $   955.400

     INSTALLATION COSTS, INDIRECT

      Engineering
        (10% of direct costs)                  $    95.500
      Construction and field expense
        (10% of direct costs)                  	95.500
      Construction fees
        (10% of direct costs)                  	95.500
      Startup  (2% of direct costs)            	19,100
      Performance tests  (minimum $2000)        	3,500

     TOTAL INDIRECT COSTS                     $   309.100

     Contingencies
      (20% of direct and indirect costs)      $   252.900

     Total turnkey costs
      (Direct + Indirect + Contingencies)        1.517.400

     Land                                     	2,000

     Working capital  (25% of total direct
      operating costs)                        	145,800

     GRAND TOTAL
      (Turnkey + Land + Working Capital)      $  1,665,200
     a Quote  from  Zurn  Industries, Inc., May 25, 1978
     N.A. - Not applicable.

                                A-17

-------
TABLE A-12.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE, WATER-TUBE,
        UNDERFEED-STOKER BOILER FIRING EASTERN LOW-SULFUR
               COAL WITH A THERMAL INPUT OF 8.8 MW
          (30 x 106 Btu/h;  150 psig/sat.  temp,  design)


DIRECT COST

      Direct  labor                                  ?  157,9QO
      Supervision                                   	??f?£?—
      Maintenance labor                             	64,100
      Maintenance materials
      Replacement parts
      Electricity
      Steam
      Cooling water                                 	N>A*
      Process  water
      Fuel                                            182,900
      Bottom ash disposal                             12,600
      Chemicals                                     	2'300

      Total  direct  cost                             $  583f100

 OVERHEAD

      Payroll  (30%  of  direct  labor)                 $—47'400

      Plant  (26% of labor,  parts  & tnaint.)          	91fl°°

      Total  overhead costs                          $  138^500

                                                       N.A.
 BY-PRODUCT  CREDITS                                 —

 CAPITAL CHARGES

      G & A,  taxes  l  insurance                     §   60 7QO
       (4% of total turnkey costs)                  	'.	
      Capital  recovery factor                        161,000
       (10.61*  of  total turnkey costs)              	[	
      Interest on working capital
       (10%  of working  capital)                     	14f600

          Total  capital  charges                   $  236,300

 TOTAL ANNUALIZED COSTS                            $  957,900


 a  Included  with  replacement parts. -
 N.A.  - Not  applicable.
                                  A-18

-------
  TABLE A^13. ESTIMATED CAPITAL COSTS OF A PACKAGE,  WATER-TUBE,
        UNDERFEED-STOKER BOILER FIRING SUBBITUMINOUS COAL
                 WITH A THERMAL INPUT OF 8.8 MW
          (30 x 10°  Btu/h;  150 psig/sat. temp, design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30,  1978
(FOR COSTS  INDEXING)
     EQUIPMENT COSTa

      Boiler  (with fans and ducts)
      Stack
      In strumentation
      Stokers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COSTS, DIRECT

      Boiler  (including founda-
       tions and steel)
      Stack
      In strumentation
      Stokers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

 N.A. - Not applicable.
                     S  380,200	
                    	3,000	
                     Incl.  w/boiler
                     Incl.  w/boiler
                     Incl.  w/coal handling
                     Incl.  w/coal handling
                          5,200	
                         13.400
                          7,700
                          8_,000
                          1.400
                           N.A.
                        168.200
                        122.400
                           N.A.
                           N.A.
                     S  709.500
                     S  129,600
                          1,500
                     Incl.  w/boiler
                     Inel.  w/boiler
                     Incl.  w/coal handling
                     Incl.  w/coal handling
                    	2.SOO
                           N.A.
                         .3^000
                          1.100
                          2.OOP
                            800
                        100^800
                           N.A.
                           N.A.
                              A-19

-------
TABLE A=13.(continued)
    INSTALLATION COSTS, DIRECT (cont.)

     Foundations and supports                	43,200
     Ductwork  (not incl. w/boiler)           	 N.A.
     Piping                                        SO/TOT
     Insulation                                    36,000
     Painting                                	7.200
     Electrical                              	30.000
     Buildings                               	172.800

    Total Installation Costs                  $   631,300

    TOTAL DIRECT COSTS
     (Equipment + Installation)                $ 1.340.800

    INSTALLATION COSTS, INDIRECT

     Engineering
      (10% of direct costs)                    $   134.100
     Construction and field expense
      (10% of direct costs)                        134,100
     Construction fees
      (10% of direct costs)                        134,100
     Startup (2% of direct costs)             	26,800
     Performance tests (minimum $2000)        	3,500

    TOTAL INDIRECT COSTS                      $   432,600

    Contingencies
     (20% of direct and indirect costs)        $   354,700

    Total turnkey costs
     (Direct + Indirect + Contingencies)         2,128,100

    Land                                     	2,000

    Working capital (25% of total  direct
     operating costs)                         	127.000

    GRAND TOTAL
     (Turnkey> Land + Working Capital)        $ 2,257,100
     Quote  from  Zurn  Industries,  Inc., May  25,  1978
   N.A. - Not applicable.


                              A-20

-------
TABLE A-14.  ESTIMATED ANNUALIZED COSTS  OF A PACKAGE, WATER-TUBE,
          UNDERFEED-STOKER BOILER FIRING SUBBITUMINOUS
               COAL WITH A THERMAL INPUT OF 8.8 MW
           (30 x 106 Btu/h; 150 psig/sat. temp, design)
 DIRECT COST
      Direct labor                                 $  157,900
      Supervision                                      68,500
      Maintenance labor                                64.100
      hJaintenance materials
      Replacement parts                                86,400
      Electricity                                      49,400
      Steam    ^                                     _ N.A.
      Cooling water                                     N.A.
      Process water
      Fuel                                             b b , ^ u u
      Bottom ash disposal                              12,600
      Chemicals                                         2,30lT"
      Total direct cost                            $   507,900
 OVERHEAD
      Payroll (30% of direct labor)                $    47,400
      Plant (26% of labor, parts t maint.)             98,000
      Total overhead costs                         $   145,400
                   /
 BYPRODUCT CREDITS                                       N.A.
 CAPITAL CHARGES
      G & A, taxes & insurance
       (4% of total turnkey costs)                 $    85,100
      Capital recovery factor
       (10.61* of total turnkey costs)                 225,800
      Interest on working capital
       (10% of working capital)                        12,700
           Total capital charges                   $   323,600
 TOTAL ANNUALIZED COSTS                        '    5   976,900
a  Included with replacement parts.
N.A.  - Not applicable.
                                  A-21

-------
TABLE A-15.  ESTIMATED CAPITAL COSTS OF A PACKAGE, WATER-TUBE,
   UNDERFEED-STOKER BOILER FIRING EASTERN MEDIUM-SULFUR COAL
                WITH A THERMAL INPUT OF 8.8 MW
         (30 x 106 Btu/h; 150 psig/sat. temp, design)
 CAPITAL COSTS
 DATE OF ESTIMATE
June 30, 1978
(FOR COSTS INDEXING)
      EQUIPMENT COST

       Boiler (with fans & ducts)
       Stack
       Instrumentation
       Stoker
       Feeders
       Crushers
       Deaerators
       Heaters
       Boiler feed pumps
       Condensate systems
       Water treating system
       Chemical feed
       Compressed air system
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel-oil system

      Total Equipment Cost

      INSTALLATION COST, DIRECT

       Boiler (including founda-
        tions and steel)
       Stack
       Instrumentation
       Stoker
       Feeders
       Crushers
       Deaerators
       Heaters
       Boiler feed pumps
       Condensate system
       Water treating system
       Chemical feed
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel-oil system

 N.A.  - Not applicable.
                          276.000
                            3,000
                       Incl.  w/boiler
                       Incl.  w/boiler
                       Incl.  w/coal handling
                       Incl.  w/coal handling
                            5,200	
                             N.A.	
                           13,400	
                            7,700	
                            8.000	
                            1,400	
                             N.A.	
                          122,000	
                           89,000	
                             N.A.	
                             N.A.
                          525.700
                           94.000
                            1.500	
                       Incl. w/boiler
                       Incl. w/boiler
                       Incl. w/coal handling
                       Incl. w/coal handling
                            2.500	
                             N.A.	
                            3.000	
                            1.100	
                            2,000	
                        	800	
                           73,000	
                           37,000	
                        	N.A.	
                             N.A.	
                               A-22

-------
TABLE A-15.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports                      	31,000
     Ductwork  (not  incl. w/boiler)                 	N.A.
     Piping                                          37,000
     Insulation                                      26,000
     Painting                                         5,000
     Electrical                                      30,000
     Buildings                                      125,000

     Total installation cost                     $  468.900

TOTAL DIRECT COSTS
  (equipment +  installation)                      $  994r6QQ

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of  direct costs)                      $   99,500
     Construction and  field expense
       (10% of  direct costs)                          99,500
     Construction fees
       (10% of  direct costs)                          99,500
     Start-up  (2% of direct costs)                   19,900
     Performance tests (minimum $2000)    .            3,50lT

TOTAL INDIRECT COSTS                             $  321,900

Contingencies
  (20% of  direct and indirect  costs)              $  263,300

Total Turnkey  Costs
   (direct+indirect+contingencies)                 1,579,800

Land                                                  2,000

Working capital  (25% of total direct
  operating costs)                                   141,200

GRAND TOTAL
  (turnkey+land+working capital)                  SI.723.OOP
N.A. - Not applicable.


                              A-23

-------
TABLE A-16.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE, WATER-TUBE,
    UNDERFEED-STOKER BOILER FIRING EASTERN MEDIUM-SULFUR COAL
                 WITH A THERMAL INPUT OF 8.8 MW
           (30 x 106 Btu/h; 150 psig/sat. temp, design)
                                                      i

     DIRECT COST

           Direct  labor                            S  157.900
           Supervision                                 68,500
           Maintenance labor                           64,100
           Maintenance materials                    	
-------
TABLE A-17.  ESTIMATED CAPITAL COSTS OF A PACKAGE, WATER-TUBE,
    UNDERFEED-STOKER BOILER FIRING EASTERN HIGH-SULFUR COAL
                WITH A THERMAL INPUT OF 17.6 MW
          (60 x 106 Btu/h; 150 psig/sat. temp, design)
  CAPITAL COSTS
  DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
       EQUIPMENT COSTa

        Boiler  (with fans & ducts)
        Stack
        Instrumentation
        Stoker
        Feeders
        Crushers
        Deaerators
        Heaters
        Boiler feed pumps
        Condensate systems
        Water treating system
        Chemical feed
        Compressed air system
        Coal handling system
        Ash disposal system
        Thawing equipment
        Fuel-oil system

       Total Equipment Cost

       INSTALLATION COST, DIRECT

        Boiler  (including founda-
         tions and steel)
        Stack
        Instrumentation
        Stoker
        Feeders
        Crushers
        Deaerators
        Heaters
        Boiler feed pumps
        Condensate system
        Water treating system
        Chemical feed
        Coal handling system
        Ash disposal system
        Thawing equipment
        Fuel-oil system

  N.A. - Not applicable.
                          579.200
                            9^500
                       Incl.  w/boiler
                       Incl.  w/boiler
                       Incl.  w/coal handling
                       Incl.  w/coal handling
                           13,500	
                             N.A.	
                           18.000	
                            8.000	
                           12.500	
                            1.400	
                             N.A.	
                          146.300	
                          128.700	
                             N.A.	
                             N.A.	

                       S  917.100	
                          J.93.100
                            4.700	
                       Incl. w/boiler
                       Inc 1. w/boi1er
                       Incl. w/coal handling
                       Tncl. w/coal handling
                            3fOOP	
                        	NjAi	
                            4.800	
                            1,100	
                            2,100	
                            1,500
                           146.300	
                            58.500	
                             N.A.	
                             N.A.	
                                 A-25

-------
TABLE A-17-   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports
     Ductwork  (not incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation cost

TOTAL DIRECT COSTS
  (equipment + installation)

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)
     Construction and field expense
       (10% of direct costs)
     Construction fees
       (10% of direct costs)
     Start-up  (2% of direct costs)
     Performance tests  (minimum $2000)

TOTAL INDIRECT COSTS

Contingencies
  (20% of direct and indirect costs)

Total Turnkey Costs
   (direct*indirect+contingencies)

Land

Working capital  (25% of total direct
 operating costs)

GRAND TOTAL
  (turnkey+land+working capital)
       .?nn
      N.A.
    52,700
    41,000
     7,500
    60,000
   198,900
   845.400
$1.762.500
$  176.300

   176.300

   176.300
    35,300
     6,000

$  570.200
$  466.500


 2.799.200

     2.000
   220.600
$3,021.800
 Quote from Zurn Industries, Inc., May 25, 1978.
N.A. - Not applicable.
                            A-26

-------
TABLE A-18.  ESTIMATED ANNUALLZED COSTS OF A PACKAGE, WATER-TUBE,
     UNDERFEED-STOKER BOILER FIRING EASTERN HIGH-SULFUR COAL
                 WITH A THERMAL INPUT OF 17.6 MW
           (60 x 106 Btu/h; 150 psig/sat. temp, design)
       DIRECT COST
            Direct labor                           $	184,300
            Supervision                                136,900
            Maintenance labor                          128,200
            Maintenance materials
            Replacement parts                           99,500
            Electricity                                 53.200
            Steam      '                              _ N-A.
            Cooling water                            _ N.A.
            Process water                            _ 900
            Fuel                                       233,400
            Bottom ash disposal                         42,000
            Chemicals                                    4,000

            Total direct cost                      $   882,400

       OVERHEAD

            Payroll (30% of direct labor           $    55,300

            Plant  (26% of labor, parts & maint.)        142,700

            Total overhead costs                   $   198,000

       BY-PRODUCT CREDITS                            _ N.A.

       CAPITAL CHARGES

            G & A, taxes & insurance
             (4% of total turnkey costs)           $   112,000

            Capital recovery factor
             (10.61 % of total turnkey costs)           297.000

            Interest on working capital
             (10% of working capital)                    22,100

                 Total capital charges              $   431,100

       TOTAL ANNUALIZED COSTS                       S 1.511.500

       a Included with replacement parts.
       N.A. - Not applicable.
                                  A-27

-------
TABLE A-19.  ESTIMATED CAPITAL COSTS OF A PACKAGE, WATER-TUBE,
    UNDERFEED-STOKER BOILER FIRING EASTERN LOW-SULFUR COAL
                WITH A THERMAL INPUT OF 17.6 MW
         (60 x 10° Btu/h; 150 psig/sat. temp, design)
 CAPITAL COSTS
 DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
      EQUIPMENT COSTa

       Boiler (with fans & ducts)
       Stack
       Instrumentation
       Stoker
       Feeders
       Crushers
       Deaerators
       Heaters
       Boiler feed pumps
       Condensate systems
       Water treating system
       Chemical feed
       Compressed air system
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel-oil system

      Total Equipment Cost

      INSTALLATION COST,  DIRECT

       Boiler (including founda-
        tions and steel)
       Stack
       Instrumentation
       Stoker
       Feeders
       Crushers
       Deaerators
       Heaters
       Boiler feed pumps
       Condensate system
       Water treating system
       Chemical feed
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel-oil system

 N.A.  - Not applicable.
                          495^000
                            9.500
                       Incl. w/boiler
                       Incl. w/boiler
                       Incl. w/coal handling
                       Incl. w/coal handling
                           13,500	
                             N.A.	
                           18,000	
                            8,000	
                           12.500	
                            1,400	
                             N.A.	
                          125,000	
                          110,000	
                             N.A.	
                             N.A.	

                       $  792.900	
                          165.000
                            4.700	
                       Incl. w/boiler
                       Incl. w/boiler
                       Incl. w/coal handling
                       Incl. w/coal handling
                            3.000	
                        	N.A.	
                            4.800	
                            1.100	
                            2,100	
                            1.500	
                          125.000	
                           50,000	
                        	N.A.	
                             N.A.	
                               A-28

-------
TABLE A-19.   (continued)
INSTALLATION COSTS, DIRECT (cont.)

     Foundations and supports                        60,000
     Ductwork  (not incl. w/boiler)                      N.A.
     Piping                                          45,000
     Insulation                                      35,000
     Painting                                          6.400
     Electrical.                                      60,000
     Buildings                                       170,000

     Total installation cost                      $   733r6QO

TOTAL DIRECT COSTS
  (equipment +  installation)                       Slr526.500

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of  direct costs)                       S   152.700
     Construction and field expense
       (10% of  direct costs)                          152.700
     Construction fees
       (10% of  direct costs)                          152,700
     Start-up  (2% of direct costs)                     30.500
     Performance tests  (minimum  $2000)   ,        	6.000

TOTAL INDIRECT COSTS                              $   494.600

Contingencies
  (20% of direct and indirect costs)               S   404.200

Total Turnkey  Costs
   (direct+indirect+contingencies)                  2r425.300

Land                                              	2.000

Working capital  (25% of total direct
  operating costs)                                    243r4QO

GRAND TOTAL
  (turnkey+land+working capital)                   S2.670.700
aQuote from Zurn Industries, Inc., May 25, 1978.

N.A. - Not applicable.

                              A-29

-------
TABLE A-20.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE, WATER-TUBE,
     UNDERFEED-STOKER BOILER FIRING EASTERN LOW-SULFUR COAL
                 WITH A THERMAL INPUT OF 17.6 MW
           (60 x 10b Btu/h; 150 psig/sat. temp, design)


     DIRECT COST

           Direct labor                            $  184.300
           Supervision                                136,900
           Maintenance labor                          128,200
           Maintenance materials                    	i_
          Replacement parts                           85,000
          Electricity                                 45,400
          Steam                                         N.A.
          Cooling water                            	N.A.
          Process water                            	900
          Fuel                                       365,800
          Bottom ash disposal                         23,100
          Chemicals                                    4.000

          Total direct cost                       $  973.600

     OVERHEAD

          Payroll  (30% of direct labor            $   55,300

          Plant  (26% of labor, parts & maint.)       138.900

          Total overhead costs                    $  194,200

     BY-PRODUCT CREDITS                                 N.A.

     CAPITAL CHARGES

          G & A, taxes & insurance
            (4% of total turnkey costs)            $   97.000

          Capital recovery factor
            (10.61% of total turnkey costs)          257.3QQ

          Interest on working capital
            (10% of working capital)                   24.300

               Total capital charges              $  378.600

     TOTAL ANNUALIZED COSTS                       Sl.54fi.dnn

     a Included with replacement parts.
     N.A. - Not applicable.
                               A-30

-------
TABLE A-21.  ESTIMATED CAPITAL COSTS OF A PACKAGE, WATER-TUBE,
       UNDERFEED-STOKER BOILER FIRING SUBBITUMINOUS COAL
                WITH A THERMAL INPUT OF 17.6 MW
          (60 x 106 Btu/h; 150 psig/sat. temp, design)
 CAPITAL COSTS
 DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
      EQUIPMENT COST

       Boiler  (with fans & ducts)
       Stack
       Instrumentation
       Stoker
       Feeders
       Crushers
       Deaerators
       Heaters
       Boiler  feed pumps
       Condensate systems
       Water treating system
       Chemical feed
       Compressed air system
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel-oil system

      Total Equipment Cost

      INSTALLATION COST, DIRECT

       Boiler  (including founda-
        tions  and steel)
       Stack
       Instrumentation
       Stoker
       Feeders
       Crushers
       Deaerators
       Heaters
       Boiler  feed pumps
       Condensate system
       Water treating system
       Chemical feed
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel-oil system

 N.A. - Not applicable.
                       $  712,800
                            9,500	
                       Incl.  w/boiler
                       Incl.  w/boiler ~"
                       Incl.  w/coal handling
                       Incl.  w/coal handling
                           13.500	
                             N.A.	
                           18.000	
                            8.000	
                           12r500	
                            1.400	
                             N.A.	
                          180.000	
                          158.400	
                             N.A.	
                             N.A.	

                       SI.114.100	
                          237.600
                            4r7QO	
                       Incl. w/boiler
                       Tncl. w/boiler
                       Incl. w/coal handling
                       Tncl. w/cnal handling
                            3rQQQ	
                        	N.A.	
                            4r8QQ	
                            irinn	
                            2.100	
                            1.5QO	
                           180.000	
                            72.QQQ	
                              N.A.
                              N.A.
                                A-31

-------
TABLE A-21.  (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports                        86,400
     Ductwork  (not incl. w/boiler)                 	N.A.
     Piping            .                              64,800
     Insulation                                      50,400
     Painting                                         9,200
     Electrical                                      60,000
     Buildings                                      244,800

     Total installation cost                     $1r n 2 2 f 4 n 0

TOTAL DIRECT COSTS
  (equipment + installation)                      S2.136.500

INSTALLATION COSTS, INDIRECT

     Engineering
      (10% of direct costs)                      s  213,700
     Construction and field expense
      (10% of direct costs)                         213,700
     Construction fees
      (10% of direct costs)                         213.700
     Start-up  (2% of direct costs)                   42,700
     Performance tests (minimum $2000)   .             6,000

TOTAL INDIRECT COSTS                             $  689,800

Contingencies
  (20% of direct and indirect costs)              $  565,300

Total Turnkey Costs
   (direct+indirect+contingencies)                 3,391,600

Land                                                  2,000

Working capital (25% of total direct
 operating costs)                                    200,500

GRAND TOTAL
  (turnkey+land+working capital) -                 $3.594.100
aQuote from Zurn Industries, Inc., May 25, 1978

N.A. - Not applicable.


                             A-32

-------
TABLE A-22.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE, WATER-TUBE,
        UNDERFEED- STOKER BOILER FIRING SUBBITUMINOUS COAL
                 WITH A THERMAL INPUT OF 17.6 MW
           (60 x 106 Btu/h; 150 psig/sat. temp, design)

     DIRECT COST

           Direct labor                            $   194,300
           Supervision                                 136.900
           Maintenance labor                           I2ar20fl
           Maintenance materials                    _ a
           Replacement parts                           122,400
           Electricity                                  65,400
           Steam                                    _ N.A.
           Cooling water                            _ N.A.
           Process water                            _ 900
           Fuel                                        132,500
           Bottom ash disposal                          27,300
           Chemicals                                _ 4,000

           Total direct cost                       S   801.90Q-

     OVERHEAD

           Payroll  (30% of direct labor            $    55,300

           Plant  (26% of labor, parts & maint.)        148.700

           Total overhead costs                    S   204.000

     BY-PRODUCT CREDITS                            _ N.A.

     CAPITAL CHARGES

           G & A, taxes & insurance
            (4% of total turnkey costs)            S   115.700

           Capital recovery factor
            (10.61 % of total turnkey costs)
           Interest  on working capital
            (10%  of  working capital)                    20.100

               Total capital charges              S   515.600

     TOTAL ANNUALIZED COSTS                       g 1.521.500

     a Included  with replacement parts.
     N.A.  - Not  applicable.
                                A-33

-------
TABLE A-23.  ESTIMATED CAPITAL COSTS OF A PACKAGE, WATER-TUBE,
  UNDERFEED-STOKER BOILER FIRING EASTERN MEDIUM-SULFUR COAL
                WITH A THERMAL INPUT OF 17.6 MW
         (60 x 10° Btu/h; 150 psig/sat. temp, design)
 CAPITAL COSTS
 DATE OF ESTIMATE
June 30, 1978
(FOR COSTS INDEXING)
      EQUIPMENT COSTa

       Boiler (with fans & ducts)
       Stack
       Instrumentation
       Stoker
       Feeders
       Crushers
       Deaerators
       Heaters
       Boiler feed pumps
       Condensate systems
       Water treating system
       Chemical feed
       Compressed air system
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel-oil system

      Total Equipment Cost

      INSTALLATION COST, DIRECT

       Boiler (including founda-
        tions and steel)
       Stack
       Instrumentation
       Stoker
       Feeders
       Crushers
       Deaerators
       Heaters
       Boiler feed pumps
       Condensate system
       Water treating system
       Chemical feed
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel-oil system

 N.A.  - Not applicable.
                          516.8QQ
                            9.500
                       Incl. w/boiler
                       Incl. w/boiler
                       Incl. w/coal handling
                       Incl. w/coal handling
                           13.500	
                             N.A.	
                           18.000	
                            8.000	
                           12.500	
                            1.400	
                             N.A.	
                          130.500	
                          114.800	
                             N.A.	
                             N.A.	

                       S  825.000	
                       S  172r3QQ

                            4r700
                       Incl. w/boiler
                       Incl. w/boil
                       Incl. w/coal handling
                       Tncl. w/coal handling
                            3rOQO	
                        	N.A.	
                            4r8QQ	
                            lrlQQ	
                            2.100	
                            1.5QO	
                          130.500	
                           52.200	
                             N.A.	
                               A-34

-------
TABLE A-23.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations  and  supports
     Ductwork  (not  incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation  cost

TOTAL  DIRECT COSTS
  (equipment +  installation)

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of  direct  costs)
     Construction and field expense
       (10% of  direct  costs)
     Construction fees
       (10% of  direct  costs)
     Start-up  (2% of  direct costs)
     Performance  tests (minimum  $2000)

TOTAL  INDIRECT COSTS

Contingencies
  (20%  of direct and indirect  costs)

Total  Turnkey  Costs
   (direct+indirect+contingencies)

Land

Working capital  (25%  of  total  direct
  operating costs)

GRAND  TOTAL
  (turnkey+land+working capital)
    62.600
      N.A.
    47.000
    36,500
     6.700
    60,000
   177,500
   762.500
$lf587,500
$  158.800

   iSB,son

   iqa,ann
    31.800
     6.000

$  514r2QQ


$  42Qf300


 2r522fQOO

     2rQQO


   234.100


$2.758.100
aQuote  from Zurn Industries,  Inc., May 25, 1978.
N.A.  -  Not  applicable.

                             A-35

-------
TABLE A-24.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE, WATER-TUBE,
    UNDERFEED-STOKER BOILER FIRING EASTERN MEDIUM-SULFUR COAL
                 WITH A THERMAL INPUT OF 17.6 MW
           (60 x 106 Btu/h; 150 psig/sat. temp, design)

      DIRECT  COST

           Direct labor                            $  184.300
           Supervision                               136,900
           Maintenance labor                          128,200
           Maintenance materials                     	a
           Replacement  parts                           88,700
           Electricity                                 47,500
           Steam                                        N.A.
           Cooling  water                             	N.A.
           Process  water                             	900
           Fuel                                       299,600
           Bottom ash disposal                         46,300
           Chemicals                                    &,nnn

           Total direct cost                       $  936.400

      OVERHEAD

           Payroll  (30% of  direct  labor            $   55,300

           Plant (26% of  labor,  parts  &  maint.)       139.900

           Total overhead costs                    $  195.200

      BY-PRODUCT CREDITS                                 N.A.

      CAPITAL CHARGES

           G & A, taxes & insurance
            (4%  of  total  turnkey costs)            $  100.900

           Capital  recovery factor
            (10.61  %  of total turnkey  costs)          267.600

           Interest on  working capital
            (10% of working capital)                   23.400

                Total capital charges              $  391.900

      TOTAL ANNUALIZED  COSTS           ,            Slr523r5QQ

      a Included with replacement  parts.
      N.A.  - Not applicable.
                                A-36

-------
TABLE A-25.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED, WATER-TUBE
         SPREADER-STOKER BOILER FIRING EASTERN HIGH-SULFUR
                COAL WITH A THERMAL INPUT OF 22 MW
            (75 x  106 Btu/h; 150 psig/sat. temp, design)
   CAPITAL COSTS
   DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
        EQUIPMENT  COST*

          Boiler  (with fans  &  ducts)
          Stack
          Instrumentation
          Stoker
          Feeders
          Crushers
          Deaerators
          Heaters
          Boiler  feed pumps
          Condensate systems
          Water treating system
          Chemical  feed
          Compressed air system
          Coal handling system
          Ash disposal system
          Thawing equipment
          Fuel-oil  system

         Total Equipment Cost

         INSTALLATION COST,  DIRECT

          Boiler  (including  founda-
           tions  and steel)
          Stack
          Instrumentation
          Stoker
          Feeders
          Crushers
          Deaerators
          Heaters
          Boiler  feed pumps
          Condensate system
         'Water treating system
          Chemical  feed
          Coal handling system
          Ash disposal system
          Thawing equipment
          Fuel-oil  system

    N.A.  - Not applicable.
                           760,500
                            80,000
                            50,000
                           175,500
                       Incl.  w/coal handling
                       Incl.  w/coal handling
                            15,900	
                        	N.A.	
                            25,300
                             8,700	
                            15,000
                             1,400
                        	N.A.	
                           165,400
                           136,000
                        	N.A.	
                        	N.A.	

                       S 1.433,700
                           491.400
                            20.000
                            15.000
                       Incl. w/boiler
                       Incl. w/coal handling
                       Incl. w/coal handling
                             3.500
                        	N.A.	
                             5.500
                             1.300
                             2.500
                             1.500
                            175.500
                            70.200
                        	N.A.
                        	 N.A.
                                  A-37

-------
 TABLE A-25.   (continued)
 INSTALLATION COSTS,  DIRECT (cont.)

      Foundations and supports
      Ductwork (not incl.  w/boiler)
      Piping
      Insulation
      Painting
      Electrical
      Buildings

      Total installation cost

 TOTAL DIRECT COSTS
  (equipment + installation)

 INSTALLATION COSTS,  INDIRECT

      Engineering
       (10% of direct costs)
      Construction and field  expense
       (10% of direct costs)
      Construction fees
       (10% of direct costs)
      Start-up (2% of direct  costs)
      Performance tests (minimum $2000)

 TOTAL INDIRECT COSTS

 Contingencies
  (20% of  direct and  indirect costs)

 Total Turnkey Costs
   (direct+indirect+contingencies)

 Land

 Working capital (25% of total direct
  operating costs)

 GRAND TOTAL
  (turnkey*land+working capital)
    93,600
      N.A.
    58,500
    46,800
     8,200
    75,000
   234,000

Slr3Q2.5QO
$2f 736 ,.200
$  273.600

   273.600

   273r600
    54,700
     7.000

$  882.500


$  723.700


 4.342.400

     2.000


   243,300


$4.587.700
aQuote from Zurn Industries, Inc., May 25, 1978

N.A. - Not applicable.
                              A-38

-------
TABLE A-26.  ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED, WATER-TUBE,
        SPREADER-STOKER .BOILER FIRING EASTERN HIGH-SULFUR COAL
                      WITH A THERMAL INPUT  OF  22 MW
              (75  x 106  Btu/h;  150  psig/sat. temp, design)

         DIRECT COST

              Direct labor                           $    210.600
              Supervision                                136.900
              Maintenance labor                          128.200
              Maintenance materials                    	a_
              Replacement parts                          117. OOP
              Electricity                                 57.600
              Steam       •                             _ N.A.
              Cooling water                            _ N.A.
              Process water                            _ 1.10Q
              Fuel                                       291.700
              Bottom ash disposal                         25.200
              Chemicals                                    4.900

              Total direct cost                       S  973.200

         OVERHEAD

              Payroll (30% of direct labor            $   63.200

              Plant (26% of labor, parts & maint.)        154.100

              Total overhead costs                    S  217.300

         BY-PRODUCT CREDITS                                 N.A.

         CAPITAL CHARGES

              G & A, taxes & insurance
               (4% of total turnkey costs)            $  I73
              Capital recovery factor
               (10.14 % of total turnkey costs)           440.300

              Interest on working capital
               (10% of working capital)                   24,300

                   Total capital charges              $  638,300

         TOTAL ANNUALIZED COSTS                       $1.828.800

         a Included with replacement parts.
         N.A. - Not applicable.
                                    A-39

-------
TABLE A-27.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED, WATER-TUBE,
        SPREADER-STOKER BOILER FIRING EASTERN LOW-SULFUR COAL
                    WITH A THERMAL INPUT OF 22 MW
            (75 x 106 Btu/h;  150 psig/sat. temp, design)
    CAPITAL COSTS
    DATE OF ESTIMATE
June 30, 1978
(FOR COSTS INDEXING)
         EQUIPMENT COSTa

          Boiler (with fans & ducts)
          Stack
          Instrumentation
          Stoker
          Feeders
          Crushers
          Deaerators
          Heaters
          Boiler feed pumps
          Condensate  systems
          Water treating system
          Chemical feed
          Compressed  air system
          Coal  handling system
          Ash disposal system
          Thawing equipment
          Fuel-oil system

         Total  Equipment Cost

         INSTALLATION COST,  DIRECT

          Boiler (including founda-
           tions and  steel)
          Stack
          Instrumentation
          Stoker
          Feeders
          Crushers
          Deaerators
          Heaters
          Boiler feed pumps
          Condensate  system
          Water treating system
          Chemical feed
          Coal  handling system
          Ash disposal system
          Thawing equipment
          Fuel-oil system

   N.A.  - Not  applicable.
                           650,000
                            80,000
                            50,000
                           150.000
                       Incl. w/coal handling
                       Incl. w/coal handling
                            15.900	
                        	N.A.	
                            25,300	
                             8.700	
                            15.000
                             1,400	
                              N.A.
                           141.400
                           116.200
                              N.A.
                              N.A.
                       $ 1.253.900
                           420.000
                            20.000
                            15.QQQ
                       Tncl. w/boiler
                       Tnnl. w/coal handling
                       Tncl. w/coal handling
                        	3f500	
                        	N.A.	
                        	5r5QO	
                        	1.3QQ	
                             2.500
                             1.500
                           150.OOP
                            60.000
                              N.A.
                              N.A.
                                  A-40

-------
TABLE A-27.   (continued)
 INSTALLATION  COSTS,  DIRECT  (cont.)

      Foundations and supports
      Ductwork (not incl.  w/boiler)
      Piping
      Insulation
      Painting
      Electrical
      Buildings

      Total installation cost

 TOTAL DIRECT  COSTS
  (equipment + installation)

 INSTALLATION  COSTS,  INDIRECT

      Engineering
       (10% of direct costs)
      Construction and field expense
       (10% of direct costs)
      Construction fees
       (10% of direct costs)
      Start-up (2% of direct costs)
      Performance tests (minimum $2000)

 TOTAL INDIRECT COSTS

 Contingencies
  (20% of direct and indirect costs)

 Total Turnkey Costs
   (direct+indirect+contingencies)

 Land

 Working capital (25% of total direct
  operating costs)

 GRAND TOTAL
  (turnkey+land+working capital)
    80,000
      N.A.
    50,000
     7,000
    TSTOOl)
   200,000

S1.131r30Q
$2.385.200
S  238.500

   238r500

   23Rr5nn
    47.700
     7.000

S  770r2QQ


S  631,100
 3f786f500

     2,000


   275f70Q


$4,064,200  ^
a Quote from Zurn Industries, Inc., May 25, 1978.
N.A. - Not applicable.
                              A-41

-------
TABLE A-28.   ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED, WATER-TUBE
         SPREADER-STOKER BOILER FIRING EASTERN LOW-SULFUR COAL
                  COAL WITH A THERMAL INPUT OF 22 MW
             (75 x 10° Btu/h;  150 psig/sat. temp, design)
        DIRECT COST
             Direct labor                            $  210,600
             Supervision                                136,900
             Maintenance labor                          128,200
             Maintenance materials
             Replacement parts                          100,000
             Electricity                                 49,200
             Steam                                         N-A*
             Cooling water                            	N.A.
             Process water                                1,100
             Fuel                                       457,300
             Bottom ash disposal                         14,700
             Chemicals                                    4,900

             Total direct cost                       $1,102,900

        OVERHEAD

             Payroll (30% of direct labor            $   63,200

             Plant (26% of labor, parts & maint.)       149,700

             Total overhead costs                    $  212,900

        BY-PRODUCT CREDITS                                 N.A.

        CAPITAL CHARGES

             G & A, taxes & insurance
               (4% of total turnkey costs)            S  151.500

             Capital recovery factor
               (10.14 % of total turnkey costs)          384.000

             Interest on working capital
               (10% of working capital)                   27,600

                  Total capital charges              $  563.100

        TOTAL ANNUALIZED COSTS           .           SI.878.900
                       -*

        a Included with replacement parts.
        N.A. - Not applicable.
                                   A-42

-------
TABLE A-29.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED, WATER-TUBE,
          SPREADER-STOKER BOILER FIRING SUBBITUMINOUS COAL
                    WITH A THERMAL INPUT OF 22 MW
            (75 x 106 Btu/h; 150 psig/sat. temp,  design)
    CAPITAL COSTS
    DATE OF ESTIMATE
June 30, 1978
.(FOR COSTS INDEXING)
         EQUIPMENT COST0

          Boiler  (with fans & ducts)
          Stack
          Instrumentation
          Stoker
          Feeders
          Crushers
          Deaerators
          Heaters
          Boiler  feed pumps
          Condensate systems
          Water treating system
          Chemical feed
          Compressed air system
          Coal handling system
          Ash disposal system
          Thawing equipment
          Fuel-oil system

         Total Equipment Cost

         INSTALLATION COST, DIRECT

          Boiler  (including founda-
           tions  and steel)
          Stack
          Instrumentation
          Stoker
          Feeders
          Crushers
          Deaerators
          Heaters
          Boiler  feed pumps
          Condensate system
          Water treating system
          Chemical feed
          Coal handling system
          Ash disposal system
          Thawing equipment
          Fuel-oil system

    N.A. - Not applicable.
                           936,000
                            80,000
                            50,000
                           216^000
                       incl. w/coal  handling
                       Incl. w/coal  handling
                            15.900	
                        	N.A.	
                            25,300	
                            8.700	
                            15.QQQ	
                            1.400	
                        	N.A.	
                           203.600	
                           167.300	
                        	N.A.	
                             N.A.	

                       S 1.719.200	
                           6Qi.nnn
                            2Q.QQQ
                       Tnrl.  w/boiler
                       TnrO .  w/onal handing
                       Tnrl.  w/coal handl ing
                             550Q
                             1.3QQ
                             2.500
                             1.50Q
                           216. QQQ
                            86.400
                              N.A.
                              N.A.
                                   A-43

-------
TABLE A-29.  (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports                        115.200
     Ductwork  (not incl. w/boiler)                 	N.A.
     Piping                                           72.000
     Insulation                                       57.600
     Painting                                         10.100
     Electrical                                       75.000
     Buildings                                       288,000

     Total installation cost                     S  1,570.600

TOTAL DIRECT COSTS
  (equipment + installation)                      $  3r289r80Q

INSTALLATION COSTS, INDIRECT

     Engineering
      (10% of direct costs)                      S   329.000
     Construction and field expense
      (10% of direct costs)                          329.000
     Construction fees
      (10% of direct costs)                          329rQQO
     Start-up  (2% of direct costs)                    65,800
     Performance tests  (minimum $2000)   .              7,000

TOTAL INDIRECT COSTS                             $  1.059,800

Contingencies
  (20% of direct and indirect costs)              $   869.900

Total Turnkey Costs
   (direct+indirect+contingencies)                   5,219,500

Land                                               	2,000

Working capital (25% of total direct
 operating costs)                                      219.200

GRAND TOTAL
  (turnkey+land+working capital)                   $ 5.440.700


 aQuote  from Zurn  Industries,  Inc.,  May 25,  1978.

 N.A.  -  Not applicable.


                             A-44

-------
TABLE A-30.  ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED, WATER-TUBE
           SPREADER-STOKER BOILER FIRING SUBBITUMINOUS COAL
                    WITH A THERMAL INPUT OF 22.0 MW
              (75 x 106 Btu/h;  150 psig/sat. temp, design)
         DIRECT COST
              Direct labor                          $   210,600
              Supervision                             —136,900
              Maintenance labor                         128,200
              Maintenance materials
              Replacement parts                       _ 144,000
              Electricity                                70,900
              Steam
              Cooling water                            _ N.A.
              Process water
              Fuel                                      165,600
              Bottom ash disposal                        14,700
              Chemicals                                    4,900

              Total direct cost                      $   876.900

         OVERHEAD

              Payroll (30% of direct labor           $    63,200

              Plant (26% of labor, parts & maint.)       161.100

              Total overhead costs                   $   224.300

         BY-PRODUCT CREDITS                                 N.A.

         CAPITAL CHARGES

              G & A, taxes & insurance
               (4% of total turnkey costs)           $   208.800

              Capital recovery factor
               (10.14 % of total turnkey costs)          529.300

              Interest on working capital
               (10% of working capital)                   21.900

                   Total capital charges             $   760.000

         TOTAL ANNUALIZED COSTS                       SlrRfi1 r2nn

         a Included with replacement parts.
         N.A. - Not applicable.
                                    A-45

-------
TABLE A-31.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED WATER  TUBE,
     SPREADER-STOKER BOILER FIRING EASTERN MEDIUM-SULFUR COAL
                   WITH A THERMAL INPUT OF 22 MW
           (75 x 106 Btu/h; 150 psig/sat. temp, design)
   CAPITAL COSTS
   DATE OF ESTIMATE
June 30, 1978
(FOR COSTS INDEXING)
        EQUIPMENT COST

         Boiler (with fans & ducts)
         Stack
         Instrumentation
         Stoker
         Feeders
         Crushers
         Deaerators
         Heaters
         Boiler feed pumps
         Condensate systems
         Water treating system
         Chemical feed
         Compressed air system
         Coal handling system
         Ash disposal system
         Thawing equipment
         Fuel-oil system

        Total Equipment Cost

        INSTALLATION COST, DIRECT

         Boiler (including founda-
          tions and steel)
         Stack
         Instrumentation
         Stoker
         Feeders
         Crushers
         Deaerators
         Heaters
         Boiler feed pumps
         Condensate system
         Water treating system
         Chemical feed
         Coal handling system
         Ash disposal system
         Thawing equipment
         Fuel-oil system

   N.A.  - Not applicable.
                          678.600
                           80.000
                           50.000
                          156,600
                       Incl. w/coal handling
                       Incl. w/coal handling
                           15,900	
                             N.A.	
                           25,300	
                            8,700	
                           15.000	
                            1,400	
                             N.A.	
                          147,600	
                          121.300	
                             N.A.	
                             N.A.	

                       SI.300.400	
                          438.500
                           20.OOP	
                           15.000	
                       Incl. w/boiler
                       Inel. w/coal handling
                       Tncl. w/coal handling
                            3.500	
                        	N_JLi	
                            5.500	
                            1.300	
                            2.500	
                            1.500	
                          156.600	
                           62,600	
                        	N.A.	
                        	N.A.	
                                 A-46

-------
 TABLE A-31.  (continued)
INSTALLATION COSTS, DIRECT (cont.)

     Foundations and supports                     	93t5QO .
     Ductwork  (not incl. w/boiler)                 	N.A.—
     Piping                                          52,200
     Insulation                                      41,800
     Painting                                         7,300
     Electrical                                      75.000
     Buildings                                      208.800

     Total installation cost                     SI.175.600

TOTAL DIRECT COSTS
  (equipment +  installation)                      S2.476.OOP

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of  direct costs)                      $  247.600
     Construction and field expense
       (10% of  direct costs)                         247.600
     Construction fees
       (10% of  direct costs)                         247.600
     Start-up  (2% of direct costs)                   49.500
     Performance tests  (minimum $2000)   .              7,000

TOTAL INDIRECT COSTS                             $  799.300

Contingencies
  (20% of direct and indirect costs)              S  655.100

Total Turnkey  Costs
   (direct+indirect+contingencies)                  3.930.400

Land                                              	2.000

Working capital  (25% of total direct
  operating costs)                                    259.800

GRAND TOTAL
  (turnkey+land+working  capital)                   6/J.1Q2.20Q
aQuote from Zurn Industries, Inc., May 25, 1978.
N.A. - Not applicable.
                              A-47

-------
TABLE A-32.   ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED, WATER-TUBE,
       SPREADER-STOKER BOILER FIRING EASTERN MEDIUM-SULFUR COAL
                     WITH A THERMAL INPUT OF 22 MW
             (75 x 106 Btu/h; 150 psig/sat. temp, design)
        DIRECT COST
             Direct labor                           $   210.600
             Supervision                                136.900
             Maintenance labor                          128.200
             Maintenance materials                    	a_
             Replacement parts                          104.400
             Electricity                                 51.400
             Steam                                    	N.A.
             Cooling water                            	N.A.
             Process water                                1.100
             Fuel                                       374.500
             Bottom ash disposal                         27.300
             Chemicals                                    4.900
             Total direct cost                       $1,n39f300

        OVERHEAD

             Payroll (30% of direct labor            S   63.200

             Plant (26% of labor, parts & maint.)       15Qr8QQ

             Total overhead costs                    $  214
        BY-PRODUCT CREDITS                                 N.R.

        CAPITAL CHARGES

             G & A, taxes & insurance
              (4% of total turnkey costs)            s  157,200

             Capital recovery factor
              (10.14 % of total turnkey costs)          398.500

             Interest on working capital
              (10% of working capital)                   26,000

                  Total capital charges              $  581.700

        TOTAL ANNUALIZED COSTS                       Slr835.QQQ

        a Included with replacement parts.
        N.A. - Not applicable.
                                   A-48

-------
TABLE A-33.  ESTIMATED CAPITAL COSTS  OF A FIELD-ERECTED, WATER-TUBE,
     SPREADER-STOKER BOILER FIRING EASTERN HIGH-SULFUR COAL
                  WITH A THERMAL INPUT OF 44 MW
             (150 x 106 Btu/h; 450 psig/600°F design)  	
CAPITAL COSTS
DATE OF ESTIMATE
June 30,  1978
(FOR COSTS  INDEXING)
     EQUIPMENT COSTa

      Boiler  (with fans and ducts)
      Stack
      In strumentation
      Stokers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler  feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling  system
      .Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COSTS,  DIRECT

      Boiler  (including founda-
        tions  and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler  feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling  system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

   N.A.  -  Not  applicable.
                    S
     1.753,800
                         SOOjOOO
                         113^,500
                         227^600
                    Incl.  w/coal  handling
                    Incl.  w/coal  handling
                   	21.600	
                   	N.A.	
                   	44,500	
                   	9,200	
                          18,000
                   	1,500	
                   	N.A.	
                   	282,300	
                         167,500	
                    Incl.  w/coal  handling
                   	N.A.	

                    $   2,939,500
                    $     936,000 _

                   _ 50,000 _
                          25,000
                    Incl.  w/boiler
                    Incl.  w/coal  handling
                    Incl.  w/coal  handling
                           4,000
                           N.A.
                           7,000
                           1,500
                           3,000
                           1,500
                         292,500 find,  site prep.
                         117.000
                    Incl. w/coal  handling
                    __      N.A.
                                A-49

-------
TABLE A-«33.  (continued)
    INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports                	175f500
     Ductwork   (not incl. w/boiler)          	N.A.
     Piping                                  	81,900
     Insulation                              	87,800
     Painting                                	11,700
     Electrical                                   150,000
     Buildings                                    409,500

    Total Installation Costs                  $ 2,353,900

    TOTAL DIRECT COSTS
     (Equipment + Installation)               $ 5.293,400

    INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)                   $   529,300
     Construction and field expense
       (10% of direct costs)                       529,300
     Construction fees
       (10% of direct costs)                  	529,300
     Startup (2% of direct costs)                 105,900
     Performance tests                       	10,000

    TOTAL INDIRECT COSTS                      $ 1,703,800

    Contingencies
     (20% of direct and indirect costs)       $ 1,399,400

    Total turnkey costs
     (Direct + Indirect + Contingencies)        8,396,600

    Land                                            2,000
    Working capital (25% of total direct
     operating costs)                         	3g5f600
              •^
    GRAND TOTAL
     (Turnkey + Land + Working Capital)       $ 8.784.200
      Quote -from Babcock & Wilcox, Inc., August 17, 1978.

    N.A. - Not applicable.

                                A-50

-------
   TABLE A-34.   ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED
  WATER-TUBE,  SPREADER-STOKER BOILER FIRING EASTERN HIGH-SULFUR
               COAL WITH A THERMAL  INPUT OF 44 MW
            (150 x 106 Btu/h;  450 psig/600°F design)

DIRECT COST

   •  Direct labor                                $  315.900
     Supervision                                    136,900
     Maintenance  labor                             128,200
     Maintenance materials
     Replacement parts                              234,000
     Electricity                                     85,200
     Steam                                            N.A.
     Cooling water                                    N.A.
     Process water                                    2,300
     Fuel                                           583,400
     Bottom ash disposal                             50,500
     Chemicals                                        6,000

     Total  direct cost                           $1,542,400

OVERHEAD

     Payroll  (301 of direct  labor)               $   94,800

     Plant  (26% of  labor, parts  t maint.)           211,900

     Total  overhead costs                        $  306. 700
                  /
BYPRODUCT CREDITS                                     N.A.

CAPITAL CHARGES

     G & A, taxes t insurance
       (4% of total  turnkey costs)                $  335,900

     Capital recovery factor
       (10.14* of total turnkey costs)               851,400

     Interest on working capital
       (10%  of working capital)                       38,600

          Total capital charges                  si
TOTAL ANNUALIZED COSTS                            $3.075.000


a Included with replacement parts.
N.A. - Not applicable.
                                 A-51

-------
    TABLE A-35.  ESTIMATED CAPITAL COSTS  OF A  FIELD-ERECTED,
      WATER-TUBE, SPREADER-STOKER BOILER  FIRING  EASTERN LOW-
           SULFUR  COAL WITH A THERMAL INPUT OF  44 MW
             (150 x 106 Btu/h; 450 psia/600°F design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30.  1978
(FOR COSTS INDEXING)
     EQUIPMENT COST a

      Boiler (with fans and ducts)
      Stack
      Instrumentation
      Stokers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Cher.ical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COSTS,  DIRECT

      Boiler (including founda-
       tions and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

   N.A. - Not applicable.
                   $ 1.499.000	
                       300.000	
                       113.500	
                       194.500	
                   Incl.  w/coal handling
                   Incl.  w/coal handling
                   	21.600	
                   	N.A.	
                        44.500	
                   	9.200	
                        18.000 '	
                   	1.500	
                   	N.A.	
                       241.300	
                       143.200	
                   Incl.  w/coal handling
                   	N.A.	
                   $  2.586.300
                   $   800.000	

                       50.000	
                       25,000	
                   Incl. w/boiler
                   Incl. w/coal handling
                   Incl. w/coal handling
                   	4,000
                   	N.A.	
                   	7,000	
                   	1,500	
                   	3,000	
                        1,500
                      250,000 (incl. site prep.)
                      100.000
                  Incl. v/coal handling
                  	  N.A.
                               A-52

-------
TABLE A-35.. (continued)
   INSTALLATION COSTS, DIRECT  (cont.)

    Foundations and supports                	150 f 0.00
    Ductfcorfc^  (not incl. w/boiler)          	N.A.
    Piping                                  	70.000
    Insulation                              	75.000
    Painting                                	10.000
    Electrical                                   150.000
    Buildings                                    350.000

   Total  Installation Costs                  $ 2.047.000

   TOTAL  DIRECT COSTS
     (Equipment +  Installation)               $ 4,633,300

   INSTALLATION COSTS, INDIRECT

    Engineering
      (10% of direct costs)                   $   463,300
    Construction  and field expense
      (10% of direct costs)                       463,300
    Construction  fees
      (10% of direct costs)                       463,300
    Startup  (2% of direct costs)            	92,700
    Performance tests  (minimum $2000)       	10,000

   TOTAL  INDIRECT COSTS                      $ 1.492.600

   Contingencies
     (20%  of direct and indirect costs)       $ 1.225.200

   Total  turnkey  costs
     (Direct +  Indirect + Contingencies)        7.351.100

   Land                                     _^	2,000

   Working capital  (25% of total  direct
    operating  costs)                        	451,000

   GRAND  TOTAL
     (Turnkey + Land + Working  Capital)       $ 7.804.100
    a Quote from Babcock & Wilcox,  Inc., August  17,  1978.
    N.A.  - Not applicable.

                              A-53

-------
  TABLE A»36.  ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED,
     WATER-TUBE, SPREADER-STOKER BOILER FIRING EASTERN LOW-
           SULFUR COAL WITH A THERMAL INPUT OF 44 MW
           (150 x 106 Btu/h; 450 psig/600°F design)
DIRECT COST
            , v                                   $  315,900
     Direct labor                                  	nnn
     Supervision                                    136,900
     Maintenance labor                             .128,200
     Maintenance materials
     Replacement parts" ""                          200,000
     Electricity                                   — 72.8QQ
     Steam                                         - N-±Aj
     Cooling water                                 - N.A.
     Process water                                    2,300
     Fuel                                            914,500
     Bottom ash disposal                              27,300
     Chemicals                                     - 6f°°°

     Total direct cost                            $1,803,900

OVERHEAD

     Payroll (30% of direct labor)                $ — 94,800

     Plant (26% of labor, parts t maint.)            203'100

     Total overhead costs                         $   297,900
                  /
BYPRODUCT CREDITS                                     N'A*

CAPITAL CHARGES

     G i A, taxes t insurance
      (4% of total turnkey costs)                 ?
     Capital recovery factor
      (10.14* of total turnkey costs)                 745.400

     Interest on working capital
      (10% of working capital)                        45.100

          Total capital charges                  $ 1.084.500

TOTAL ANNUALIZED COSTS                           $ 3,186,300


  Included with replacement parts.
N.A. - Not applicable.

                                 A-54

-------
     TABLE A-37.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED,
      WATER-TUBE, SPREADER-STOKER BOILER FIRING SUBBITUMINOUS
                COAL WITH A THERMAL INPUT OF 44 MW
              (150 x 10^ Btu/h- 450 Psia/600cF design)	^^^
CAPITAL COSTS
DATE OF ESTIMATE
June 30^ 1978    (FOR COSTS  INDEXING)
     EQUIPMENT COST3

      Boiler  (with  fans and ducts)
      Stack
      In strumentation
      Stokers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler  feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal  system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COSTS, DIRECT

      Boiler  (including founda-
        tions  and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler  feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal  system
      Thawing equipment
      Fuel-oil system

    N.A. - Not applicable.
                   $  2,158,600	
                  	300,000	
                       113,500	
                       280,100
                  Incl. w/coal handing
                  Incl. w/coal hanidling
                        21,600
                  	N.A.	
                  	44,500	
                         9,200
                        18,000
                         1,500
                  	N.A.	
                  	347.500	
                  	206.200	
                  Incl. w/coal handling
                  	N.A.	

                   $  3.500.700	
                   S 1.152.000	

                  	50,000	
                  	25,000	
                  Incl. w/boiler
                  Jncl. w/coal handling
                  Incl. w/coal handling
                  	4,000	
                  	N.A.	
                  	7,000	
                  	1,500	
                  	3,000	
                  	  1,500
                       360,000 (incl. site prep.
                       144,000
                  Incl. w/coal handling
                  	 N.A.
                                A-55

-------
TABLE A-37. (continued)
    INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports                	216,000
     Ductwork   (not incl. w/boiler)          	N.A.
     Piping                                  	100,800
     Insulation                              	108.000
     Painting                                	14.400
     Electrical                              	150.000
     Buildings                               	504,000

    Total Installation Costs                  $ 2,841,200

    TOTAL DIRECT COSTS
     (Equipment + Installation)               $ 6,341,900

    INSTALLATION COSTS, INDIRECT

     Engineering
      (10% of direct costs)                   $   634,200
     Construction and field expense
      (10% of direct costs)                  	634,200
     Construction fees
      (10% of direct costs)                       634,200
     Startup (2% of direct costs)            	126,800
     Performance tests (minimum $2000)             10,000

    TOTAL INDIRECT COSTS                      $ 2,039,400

    Contingencies
     (20% of direct and indirect costs)        $ 1,676,300

    Total turnkey costs
     (Direct + Indirect + Contingencies)        10,057,600

    Land                                            2,000
    Working capital (25% of total direct
     operating costs)                         	336.200

    GRAND TOTAL
     (Turnkey + Land + Working Capital)        $10,395,800
      Quote from Babcock & Wilcox,  Inc.,  August 17,  1978
    N.A.  - Not applicable.

                               A-56

-------
  TABLE A-38.  ESTIMATED ANNUALIZED COSTS OF  A FIELD-ERECTED,
    WATER-TUBE, SPREADER-STOKER BOILER FIRING SUBBITUMINOUS
              COAL WITH A THERMAL INPUT OF 44 MW
            (150 x 106 Btu/h; 450 psig/600°F design)
DIRECT COST
     Direct labor                                 $  315.90.0
     Supervision
     Maintenance labor
     Maintenance materials
     Replacement parts                               288,000
     Electricity                                     104,800
     Steam                                             N»A'
     Cooling water
     Process water                                 _ 2,300
     Fuel                 '                           331,100
     Bottom ash disposal                              31, 5JKT
     Chemicals                                         6,OQO~

     Total direct cost                             $1,344,700

OVERHEAD

     Payroll  (30% of direct  labor)                 $   94,800

     Plant  (26% of  labor, parts  t maint.)            225.900

     Total overhead costs                          $  320.700

BYPRODUCT CREDITS                                      N.A.

CAPITAL CHARGES

     G & A, taxes & insurance                      §  4Q2 300
       (4% of total  turnkey costs)                  _ '
     Capital recovery factor
       (10.14* of total turnkey costs)               1,019,800

     Interest on working capital
       (10% of working capital)                         33,600

          Total capital charges                    $1,455,700

TOTAL ANNUALIZED COSTS                             $ 3,121,100
a Included with replacement parts.

N.A. - Not applicable.
                                  A-57

-------
TABLE A-39.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED, WATER-TUBE,
      SPREADER-STOKER BOILER FIRING EASTERN MEDIUM-SULFUR COAL
                   WITH A THERMAL INPUT OF 44.0 MW
              (150 x 106 Btu/h; 450 psig/600°F design)
    CAPITAL  COSTS
    DATE  OF  ESTIMATE
June 30, 1978
(FOR COSTS INDEXING)
        EQUIPMENT COST a

         Boiler  (with fans  &  ducts)
         Stack
         Instrumentation
         Stoker
         Feeders
         Crushers
         Deaerators
         Heaters
         Boiler feed pumps
         Condensate systems
         Water treating system
         Chemical feed
         Compressed air system
         Coal handling system
         Ash disposal system
         Thawing equipment
         Fuel-oil system

        Total Equipment Cost

        INSTALLATION COST, DIRECT

         Boiler  (including founda-
          tions and steel)
         Stack
         Instrumentation
         Stoker
         Feeders
         Crushers
         Deaerators
         Heaters
         Boiler feed pumps
         Condensate system
         Water treating system
         Chemical feed
         Coal handling system
         Ash disposal system
         Thawing equipment
         Fuel-oil system

   N.A. - Not applicable.
                       $ 1.565.000
                           300,000
                           113,500
                           203,000
                       Incl. w/coal handling
                       Incl. w/coal handling
                            21,600
                        	N.A.	
                            44,500
                             9,200
                            18,000
                             1,500
                        	N.A.	
                           252,000
                           150,000
                       Incl. w/coal handling
                        	N.A.	

                       $  2,678.300
                        $    835.000

                             50.000
                             25,000
                        Incl. w/boiler
                        Incl. w/coal  handling
                        Incl. w/coal  handling
                        	4.000
                        	N.A.	
                        	7,000
                        	1,500
                        	3,000
                        	1,500
                            261.000
                            104,000
                        Incl. w/coal  handling
                              N.A.
                                  A-58

-------
TABLE A-39.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports                     	157,0	
     Ductwork  (not incl. w/boiler)                	N.A.
     Piping                                           73,000
     insulation                                       78,000
     Painting                                         iu,uuu
     Electrical                                      150,000
     Buildings                                       365,000

     Total installation cost                     $ 2.125.000

TOTAL DIRECT COSTS
  (equipment +  installation)                      S 4.803.300

INSTALLATION COSTS, INDIRECT

     Engineering                                 ^
       (10% of  direct costs)                      $   480.300
     Construction and  field expense
       (10% of  direct costs)                          4anr3QQ
     Construction fees
       (10% of  direct costs)                          4anr30Q
     Start-up  (2% of direct costs)                     96.100
     Performance tests (minimum  $2000)   .        	1Q, QQQ

TOTAL  INDIRECT COSTS                              S  Tr547.QOO

Contingencies
  (20%  of  direct and indirect costs)               $  if27QrlQO

Total  Turnkey  Costs
   (direct+indirect+contingencies)                   7f62Qr400

Land                                              	2.000

Working capital  (25% of total  direct
  operating costs)                                     419,500

GRAND  TOTAL
  (turnkey+land+working capital)                   $ 8.041.900


aQuote  from Babcock &  Wilcox,  Inc., August 17, 1978.

N.A. - Not applicable.


                             A-59

-------
TABLE A-40.  ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED, WATER-TUBE,
       SPREADER-STOKER BOILER FIRING EASTERN MEDIUM-SULFUR COAL
                    WITH A THERMAL INPUT OF 44.0 MW
               (150 x 106 Btu/h; 450 psig/600°F design)
        DIRECT COST
             Direct labor                            $  315,900
             Supervision                                136f9QQ
             Maintenance labor                          i?Rr20Q
             Maintenance materials                    	a_
             Replacement parts                          208.800
             Electricity                                 76,100
             Steam                                     	N.A.
             Cooling water                             	N.A.
             Process water                                2,300
             Fuel                                       749,000
             Bottom ash disposal                         54,700
             Chemicals                                    6.000

             Total direct cost                       $1.677.900

        OVERHEAD

             Payroll  (30% of direct labor            $   94.800

             Plant  (26% of labor, parts & maint.)       205.300

             Total overhead costs                    $  300.100

        BY-PRODUCT CREDITS                             	N.A.

        CAPITAL CHARGES

             G & A, taxes & insurance
               (4% of total turnkey costs)            S  304.800

             Capital recovery factor
               (10.14 % of total turnkey costs)          772r7QQ

             Interest on working capital
               (10% of working capital)                   42.000

                  Total capital charges              $1.119.500

        TOTAL ANNUALIZED COSTS                       $3rQ97r5QQ

        a Included with replacement parts.
        N.A. - Not applicable.

                                   A-60

-------
TABLE A-41.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED, WATER-TUBE,
       SPREADER-STOKER BOILER FIRING EASTERN HIGH-SULFUR COAL
                   WITH A THERMAL INPUT OF 58.6 MW
               (200 x 106 Btu/h; 750 psig/750°F design)
    CAPITAL COSTS
    DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
         EQUIPMENT COSTa

          Boiler  (with fans & ducts)
          Stack
          Instrumentation
          Stoker
          Feeders
          Crushers
          Deaerators
          Heaters
          Boiler  feed pumps
          Condensate systems
          Water treating system
          Chemical feed
          Compressed air system
          Coal handling system
          Ash disposal system
          Thawing equipment
          Fuel-oil system

         Total Equipment Cost

         INSTALLATION COST, DIRECT

          Boiler  (including founda-
           tions  and steel)
          Stack
          Instrumentation
          Stoker
          Feeders
          Crushers
          Deaerators
          Heaters
          Boiler  feed pumps
          Condensate system
          Water treating system
          Chemical feed
          Coal handling system
          Ash disposal system
          Thawing equipment
          Fuel-oil system

    N.A. - Not applicable.
                       S 2.049.OOP
                           375,000
                           123.700
                           258.000
                           117.000
                       Incl.  w/coal handling
                            28.000	
                        	N.A.	
                            58.000	
                            18.000	
                            20.000	
                             1.500
                            18.000
                           316.000
                           205.000
                       Incl. w/coal handling
                        	N.A.	

                       $ 3.587.200
                       S 1.0B2rOQO
                            fi5rPOO	
                            4QrOQQ	
                       Tnel. w/boiler
                       Tr^cl. w/cnal handl ing
                       Tncl . w/c;oa3. handling
                        	6fOOP	
                        	N.A.	
                        	8.500	
                             2rPPP	
                             3.500
                             1.500	
                            322.000
                            146.000
                       Incl. w/coal handling
                                  A-61

-------
TABLE A-41.  (continued)
 INSTALLATION  COSTS,  DIRECT (cont.)

      Foundations  and supports                       199,OOP
      Ductwork (not incl.  w/boiler)                 	N.A.
      Piping                                         100.000
      Insulation                                     100.000
      Painting                                        12f QQQ
      Electrical                                     lfi5rQQQ
      Buildings                                      468.OOP

      Total  installation cost                     52.72P.5PP

 TOTAL DIRECT  COSTS
  (equipment + installation)                       S6,3P7r7PP

 INSTALLATION  COSTS,  INDIRECT

      Engineering
       (1P%  of direct costs)                       $  63P,8PP
      Construction and field  expense
       (1P%  of direct costs)                          630.800
      Construction fees
       (1P%  of direct costs)                          63P.8PP
      Start-up (2% of direct  costs)                   126,2PP
      Performance  tests (minimum $2PPP)    .            IP,PPP

 TOTAL INDIRECT COSTS                             S2.028.600

 Contingencies
  (20% of  direct and  indirect costs)               $1, 667,300

 Total Turnkey Costs
   (direct+indirect+contingencies)                 10,003,600

 Land                                                   2,000

 Working capital (25% of total direct
  operating  costs)                                    504,600

 GRAND TOTAL
  (turnkey*land+working capital)                  $10.510.200


 aQuote from Babcock  & Wilcox,  Inc., August 17, 1978.

 N.A.  - Not applicable.


                              A-62

-------
TABLE A-42.  ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED, WATER-TUBE,
        SPREADER-STOKER BOILER FIRING EASTERN HIGH-SULFUR COAL
                    WITH A THERMAL INPUT OF 58.6 MW
                (200 x 106 Btu/h; 750 psig/750°F design)
         DIRECT COST
              Direct labor                           $   421,200
              Supervision                                136.900
              Maintenance labor                          192.200
              Maintenance materials                    	&.
              Replacement parts                          304.200
              Electricity                                110.200
              Steam                                    	N.A.
              Cooling water                            	N.A.
              Process water                            	3.000
              Fuel                                       777,900
              Bottom ash disposal                          65.200
              Chemicals                                     7.500

              Total direct cost                       $ 2.018.300

         OVERHEAD

              Payroll  (30% of direct labor            $  126.400

              Plant  (26% of labor, parts & maint.)        274.200

              Total overhead costs                    S  400.600

         BY-PRODUCT CREDITS                            	N.A.

         CAPITAL CHARGES

              G & A, taxes & insurance
               (4% of total turnkey costs)            $  400.100

              Capital recovery factor
               ( 10.14% of total turnkey costs)          i f m4rAnn

              Interest on working capital
               (10% of working capital)                    50.500

                   Total capital charges              $ 1,465,000

         TOTAL ANNUALIZED COSTS                        $3.883.900

         a Included with replacement parts.
         N.A. - Not applicable.
                                    A-63

-------
TABLE A-43.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED, WATER-TUBE,
        SPREADER-STOKER BOILER FIRING EASTERN LOW-SULFUR COAL
                   WITH A THERMAL INPUT OF 58.6 MW
              (200 x 106 Btu/h; 750 psig/750°F design)
    CAPITAL COSTS
    DATE OF ESTIMATE
June 30, 1978
(FOR COSTS INDEXING)
         EQUIPMENT COSTa

          Boiler (with fans & ducts)
          Stack
          Instrumentation
          Stoker
          Feeders
          Crushers
          Deaerators
          Heaters
          Boiler feed pumps
          Condensate systems
          Water treating system
          Chemical feed
          Compressed air system
          Coal handling system
          Ash disposal system
          Thawing equipment
          Fuel-oil system

         Total Equipment Cost

         INSTALLATION COST, DIRECT

          Boiler (including founda-
           tions and steel)
          Stack
          Instrumentation
          Stoker
          Feeders
          Crushers
          Deaerators
          Heaters
          Boiler feed pumps
          Condensate system
          Water treating system
          Chemical feed
          Coal handling system
          Ash disposal system
          Thawing equipment
          Fuel-oil system

    N.A.  - Not applicable.
                        $ 1,751,200
                            375,000
                            123,700
                            220,800
                            100.QQQ
                        Incl. w/coal handling
                             28.000
                        	N.A.
                             58.000
                             18,000
                        	2QrQOQ
                        	1.500
                             15.000
                            270.000
                            175.000
                        Incl. w/coal handling
                        	N.A.
                        S 3.156.200
                            925.000
                             65rQQQ
                        	40.000
                        Tnr;!. w/boiler
                        Tnc!l. w/coal handling
                        Tnr-1 . w/cnal handl ing
                        	6rOQQ
                        	N.A.	
                        	8.5QQ
                        	2.OOP
                              3.500
                              1.500
                            275.000
                            125.000
                        Incl. w/coal handling
                        .	N.A.
                                  A-64

-------
TABLE A-43.   (continued)
INSTALLATION COSTS, DIRECT  (cont. )

     Foundations and supports                     - 170rOOO
     Ductwork  (not incl. w/boiler)                 - N.A.
     Piping                                           85,000
     Insulation                                       85,000
     Painting                                         10,000
     Electrical                                      165.000
     Buildings                                       400,000

     Total installation cost                     $ 2r366.500

TOTAL DIRECT COSTS
  (equipment +  installation)                      $ 5r522.70Q

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of  direct costs)                      »
     Construction and  field expense
       (10% of  direct costs)                          552,300
     Construction fees
       (10% of  direct costs)                          552,300
     Start-up  (2% of direct costs)                   110,500
     Performance tests (minimum  $2000)   .              10,000

TOTAL  INDIRECT COSTS                             $  1.777.400

Contingencies
  (20%  of  direct and indirect costs)              S  1.460.000

Total  Turnkey  Costs
   (direct+indirect+contingencies)                   8.760,100

Land                                              _ 2.000

Working capital  (25% of total direct
  operating costs)                                     593rlQQ

GRAND  TOTAL
  (turnkey+land+working capital)                    $Q
aQuote from Babcock & Wilcox, Inc., August 17, 1978.

N.A. - Not applicable.
                              A-65

-------
TABLE A-44.  ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED, WATER-TUBE,
         SPREADER-STOKER BOILER FIRING EASTERN LOW-SULFUR COAL
                    WITH A THERMAL INPUT OF 58.6 MW
               (200 x 106 Btu/h; 750 psig/750°F design)
        DIRECT COST
             Direct  labor                            g   42lr20Q
             Supervision                                 136.900
             Maintenance labor                           192.200
             Maintenance materials                     	§_
              Replacement  parts                           260.000
              Electricity                                  94.200
              Steam                                     _ N.A.
              Cooling water                             _ N.A.
              Process water                             _ 3.000
              Fuel                                      1.219.400
              Bottom ash disposal                          37.800
              Chemicals                                     7.500

              Total direct cost                         S2. 372. 200

         OVERHEAD

              Payroll  (30% of direct  labor              S  126.400

              Plant  (26% of  labor, parts  & maint.)        262.700

              Total overhead costs                      S  389.100

         BY-PRODUCT CREDITS                             _ N.A.

         CAPITAL CHARGES

              G & A, taxes & insurance
               (4% of total  turnkey costs)              $
              Capital recovery  factor
               (10.14 % of total turnkey costs)           888.300

              Interest on working capital
               (10% of working  capital)                    59,300

                  Total capital charges               $1.298.000

         TOTAL ANNUALIZED COSTS                       $4.059.300

         a  Included with replacement parts.
         N.A.  - Not applicable.
                                   A-66

-------
TABLE A-45.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED, WATER-TUBE,
          SPREADER-STOKER BOILER FIRING SUBBITUMINOUS COAL
                   WITH A THERMAL INPUT OF 58.6 MW
               (200 x 106 Btu/h; 750 psig/750°F design)
    CAPITAL COSTS
    DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
         EQUIPMENT COSTa

          Boiler (with fans & ducts)
          Stack
          Instrumentation
          Stoker
          Feeders
          Crushers
          Deaerators
          Heaters
          Boiler feed pumps
          Condensate systems
          Water treating system
          Chemical feed
          Compressed air system
          Coal handling system
          Ash disposal system
          Thawing equipment
          Fuel-oil system

         Total Equipment Cost

         INSTALLATION COST, DIRECT

          Boiler  (including founda-
           tions and steel)
          Stack
          Instrumentation
          Stoker
          Feeders
          Crushers
          Deaerators
          Heaters
          Boiler feed pumps
          Condensate system
          Water treating system
          Chemical feed
          Coal handling system
          Ash disposal system
          Thawing equipment
          Fuel-oil system

    N.A. - Not applicable.
                       $ 2.522.000
                           375,000
                           123,700
                           318,000
                           144,000
                       Incl. w/coal handling
                            28,000
                        	N.A.	
                            58,000
                            18,000
                            20.000
                             1,500
                            22,000 •
                            389,000
                            252,000
                       Incl. w/coal handling
                        	N.A.	

                       $ 4.271.200
                        $  1.332.000

                             65.000
                             40.000
                        Incl. w/boiler
                        Incl. w/coal  handling
                        Incl. w/coal  handling
                        	6.000
                        	N.A.	
                             8.500
                             2.000
                             3.500
                             1.500
                            396,000
                            180.000
                        Incl. w/coal  handling
                        	N.A.
                                   A-67

-------
TABLE A-45.   (continued)
INSTALLATION COSTS, DIRECT (cont.)

     Foundations and supports                        245,000
     Ductwork (not incl. w/boiler)                 	N.A.
     Piping                                          122,000
     Insulation                                      122.000
     Painting                                         14,000
     Electrical                                      165,000"
     Buildings                                       576,000"

     Total installation cost                      $3,278,500

TOTAL DIRECT COSTS
 (equipment + installation)                       $7,549,700

INSTALLATION COSTS, INDIRECT

     Engineering
      (10% of direct costs)                       $  755,000
     Construction and field expense
      (10% of direct costs)                          755,000
     Construction fees
      (10% of direct costs)                          755,000
     Start-up (2% of direct costs)                   151,000
     Performance tests  (minimum $2000)   .             10,000

TOTAL INDIRECT COSTS                              $2,426,000

Contingencies
 (20% of direct and indirect costs)               $1,995,100

Total Turnkey Costs
  (direct+indirect+contingencies)                  11,970,800

Land                                                   2,000

Working capital (25% of total direct
 operating costs)                                     438,600

GRAND TOTAL
 (turnkey+land+working capital)                  $12.411.400


 apuote  from Babcock & Wilcox,  Inc.,  August 17,  1978.

 N.A.  -  Not applicable.

                             A-68

-------
TABLE A-46.  ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED, WATER-TUBE,
           SPREADER-STOKER  BOILER FIRING SUBBITUMINOUS COAL
                    WITH A  THERMAL INPUT OF 58.6 MW
                (200 x 106 Btu/h; 750 psig/750°F design)
         DIRECT COST
              Direct labor                           $  421,200
              Supervision                               136,900
              Maintenance labor                         192,200
              Maintenance materials
              Replacement parts                          374,400
              Electricity                                135,700
              Steam                                        N-A*
              Cooling water                            	N.A.
              Process water                                3,000
              Fuel                                       441,500
              Bottom ash disposal                         42,000
              Chemicals                                    7,500

              Total direct cost                       $1,754,400

         OVERHEAD

              Payroll  (30% of direct labor            $  126,400

              Plant  (26% of labor, parts & maint.)       292,400

              Total overhead costs                    $  418.800

         BY-PRODUCT CREDITS                                 N.A.

         CAPITAL CHARGES

              G & A, taxes & insurance
                (4% of  total turnkey costs)            $  478.800

              Capital  recovery factor
                (10.14  % of total turnkey costs)        1.213.800

              Interest on working capital
                (10% of working capital)                   43,900

                   Total capital charges              $1.736.500

         TOTAL ANNUALIZED COSTS                       $3.909.700

         a Included with replacement parts.
         N.A. - Not applicable.
                                    A-69

-------
TABLE A-47.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED, WATER-TUBE,
      SPREADER-STOKER BOILER FIRING EASTERN MEDIUM-SULFUR COAL
                   WITH A THERMAL INPUT OF 58.6 MW
              (200 x 106 Btu/h;  750 psig/750°F design)
    CAPITAL COSTS
    DATE OF ESTIMATE
June 30, 1978
(FOR COSTS INDEXING)
         EQUIPMENT COSTa

          Boiler (with fans &  ducts)
          Stack
          Instrumentation
          Stoker
          Feeders
          Crushers
          Deaerators
          Heaters
          Boiler feed  pumps
          Condensate systems
          Water treating system
          Chemical feed
          Compressed air system
          Coal  handling system
          Ash disposal system
          Thawing equipment
          Fuel-oil system

         Total  Equipment Cost

         INSTALLATION  COST,  DIRECT

          Boiler (including founda-
           tions and steel)
          Stack
          Instrumentation
          Stoker
          Feeders
          Crushers
          Deaerators
          Heaters
          Boiler feed  pumps
          Condensate system
          Water treating system
          Chemical feed
          Coal  handling system
          Ash disposal system
          Thawing equipment
          Fuel-oil system

   N.A.  - Not  applicable.
                        S 1.828.000
                            375,000
                            123.700
                            231,000
                            104.000
                        Incl. w/coal handling
                             28,000
                        	N.A.
                             58,000
                             18,000
                             20.000
                        	1,500
                             16,000
                            282,000
                            183.000
                        Incl. w/coal handling
                               N.A.
                        $ 3.268.200
                            966.000
                             65.000
                             40.000
                        Incl. w/boiler
                              w/coal handl ing
                        Incl. w/coal handling
                        _ 6.000
                        _ N.A.
                        _ 8.500
                        _ 2.000
                        _ 3.500
                        _ 1.500
                            287.000
                            131.000
                        Incl. w/coal handling
                        _ N.A.
                                  A-70

-------
TABLE A-47.   (continued)
INSTALLATION COSTS, DIRECT (cont.)

     Foundations and supports                        178,000
     Ductwork (not incl. w/boiler)                 	N'A1
     Piping                                           89,000
     Insulation                                       89,000
     Painting                                         10/000
     Electrical                                      165,000
     Buildings                                       418,000

     Total installation cost                     $ 2.459.500

TOTAL DIRECT COSTS
  (equipment + installation)                      $ 5.727.700

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)                      $   572.800
     Construction and field expense
       (10% of direct costs)                          572.800
     Construction fees
       (10% of direct costs)                          572.800
     Start-up  (2% of direct costs)                   114,600
     Performance tests  (minimum  $2000)   .         	10,000

TOTAL INDIRECT COSTS                              $  1.843,000

Contingencies
  (20% of direct and indirect costs)               S  1.514.100

Total Turnkey Costs
   (direct+indirect+contingencies)                   9.084,800

Land                                              	2,000

Working capital  (25% of total direct
  operating costs)                                     550.700

GRAND TOTAL
  (turnkey+land+working capital)                   $ 9,637,500


aQuote from Babcock & Wilcox, Inc., August 17, 1978.

N.A. - Not applicable.

                              A-71

-------
TABLE A-48.  ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED, WATER-TUBE,
       SPREADER-STOKER BOILER FIRING EASTERN MEDIUM-SULFUR COAL
                    WITH A THERMAL INPUT OF 58.6 MW
               (200 x 106 Btu/h;  750 psig/750°F design)
        DIRECT COST
             Direct labor                           $   421,200
             Supervision                                136,900
             Maintenance labor                          192,200
             Maintenance materials
             Replacement parts                          271,400
             Electricity                                 98,400
             Steam                                         N-A-
             Cooling water                            _ N.A.
             Process water                                3,000
             Fuel                                       998,600
             Bottom ash disposal                         73. 600
             Chemicals                                    7.500

             Total direct cost                       S2.2Q2.8QQ

        OVERHEAD

             Payroll  (30% of direct labor            S  126.400

             Plant  (26% of labor, parts & maint.)       265.600

             Total overhead costs                    5  392rQQQ

        BY-PRODUCT CREDITS                                 N.A.

        CAPITAL CHARGES

             G & A, taxes & insurance
               (4% of total turnkey costs)            $
             Capital recovery factor
               (10.14 % of total turnkey costs)          921.200

             Interest on working capital
               (10% of working capital)                   55,100

                  Total capital charges              $1,339,700

        TOTAL ANNUALIZED COSTS              -         $3,934.500

        a Included with replacement parts.
        N.A. - Not applicable.
                                   A-72

-------
     TABLE A-49.   ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED,
      WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING EASTERN
         HIGH-SULFUR COAL WITH A THERMAL INPUT OF 58.6 MW
             (200 x 106 Btu/h; 750 psig/750°F design)  	
CAPITAL COSTS
DATE OF ESTIMATE
June 30,  1978
(FOR COSTS  INDEXING)
     EQUIPMENT COST a

      Boiler  (with fans and ducts)
      Stack
      In strumentation
      Pulverizers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler  feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling  system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COSTS, DIRECT

      Boiler  (including founda-
        tions  and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler  feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling  system
      Ash disposal  system
      Thawing equipment
      Fuel-oil system
                    $  2,492.100	
                         365.000	
                         228.000	
                         613.100	
                         128.700	
                     Incl. w/coal handling
                    	29.000	
                     Incl. w/boiler
                    	58.000	
                    	16.300	
                    	20.000	
                    	1.500	
                    	23.400	
                         308.800	
                         210.600	
                     Incl. w/coal handling
                    	N.A.	
                       4 .494 . 5Qfl
                     $  1.270.000	

                    	60.000
                    	35,000	
                     Incl. w/boiler
                     Incl. w/boiler
                     Incl. w/coal handling
                           5,000
                     Incl. w/boiler
                    	8,000	
                    	2,000	
                    	3,500	
                    	1,-SOO	
                         321,800 (incl. site prep.)
                         140,400
                     Incl. w/coal handling
                           N.A.
  N.A. - Not applicable.
                               A-73

-------
TABLE A-49.  (continued)
     INSTALLATION COSTS,  DIRECT (cont.)

      Foundations and supports
      Duct work (not incl.  w/boiler)
      Piping
      Insulation
      Painting
      Electrical
      Buildings

     Total Installation Costs

     TOTAL DIRECT COSTS
      (Equipment + Installation)

     INSTALLATION COSTS,  INDIRECT

      Engineering
       (10% of  direct costs)
      Construction and field expense
       (10% of  direct costs)
      Construction fees
       (10% of  direct costs)
      Startup  (2% of direct costs)
      Performance tests  (minimum $2000)

     TOTAL INDIRECT COSTS

     Contingencies
      (20% of direct and indirect costs)

     Total turnkey costs
      (Direct + Indirect +  Contingencies)

     Land

     Working capital (25% of total direct
      operating costs)

     GRAND TOTAL
      (Turnkey  + Land + Working Capital)
    210.600
      N.A.
     93.600
     93.600
     11.700
    160.000
    444,600
S 7
        ann
    147.100
     10,000
$ 2
        QDD
 1 1
        grin
      2,000
    536.ann
$l2.202.4nn
     a  Quote from Babcock  & Wilcox,  Inc., August  17,  1978.

     N.A. /- Not  applicable.
                              A-74

-------
   TABLE A-50.• ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED,
     WATER-TUBE,  PULVERIZED COAL-FIRED BOILER FIRING EASTERN
       HIGH-SULFUR COAL WITH A THERMAL INPUT OF 58.6 MW
            (200  x 106 Btu/h; 750 psig/750°F design)

DIRECT COST

     Direct  labor                               $  421.200
     Supervision                                    136,900
     Maintenance  labor                              192,200
     Maintenance  materials
     Replacement parts                             7^92,500
     Electricity                                    278.300
     Steam                                            N.A.
     Cooling water                                    N.A.
     Process water                                    3,000
     Fuel                                           777,900
     Bottom ash disposal                             37.300
     Chemicals                                        7.500

     Total direct cost                            $2.147.300

OVERHEAD

     Payroll  (301 of direct  labor)                $ 126,400

     Plant (26% of  labor, parts  t maint.)           271.100

     Total overhead costs                         $ 397.500
                  /
BYPRODUCT CREDITS                                     N.A.

CAPITAL CHARGES

     G 4 A, taxes t insurance
       (4% of total  turnkey costs)                 $ 466,500

     Capital recovery factor
       (10.14* of total turnkey costs)              1,182,700

     Interest on working capital
       (10% of working capital)                        53,700

          Total capital charges                   51,702,900

TOTAL ANNUALIZED COSTS                            $4,247,700


a Included with replacement  parts.

N.A. - Not applicable.
                                A-75

-------
    TABLE A-51.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED,
    WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING EASTERN
         LOW-SULFUR COAL WITH A THERMAL INPUT OF 58.6 MW
	(200 x 106 Btu/h; 750 psig/750°F design)	

CAPITAL COSTS
DATE OF ESTIMATE
June.30,  1978
(FOR COSTS INDEXING)
     EQUIPMENT COST3

      Boiler  (with fans and ducts)
      Stack
      In strumentation
      Pulverizers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COSTS, DIRECT

      Boiler  (including founda-
       tions and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system ,
                   $  2,130,000	
                        365,000	
                        228,000
                        524,500
                        110,000
                    Incl.  w/coal handling
                   	29,000	
                    Incl.  w/boiler
                   	58,000	
                   	16,300	
                   	20,000	
                   	1,500	
                   	20,000	
                        263.900	
                        160,000	
                    Incl.  w/coal handling
                   	N.A.	

                   $  3,946,200	
                   $ l,t)85,000	

                        60,000	
                        35,000
                   Incl. w/boiler
                   Incl. w/boiler
                   Incl. w/coal handling
                   	5,000	
                   Incl. w/boiler
                   	8,000
                   	2.000
                   	3,500
                   	1.500
                       275.000finel. site prep.)
                       120.000   	
                   Incl. W/eoal handling
                   	N.A.    	
  N.A. - Not applicable.
                                A-76

-------
TABLE A-51.  (continued)
    INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and  supports                	180,000
     Duct work  (not incl. w/boiler)          	N.A.
     Piping                                  	80,000
     Insulation                             	80,000
     Painting                                	10.000
     Electrical                                  160.000
     Buildings                               	380.000

    Total Installation  Costs                  $  2.485.000

    TOTAL DIRECT COSTS
      (Equipment +  Installation)               $  6.431.200

    INSTALLATION COSTS, INDIRECT

     Engineering                              c
       (10% of direct  costs)	
     Construction  and field expense
       (10% of direct  costs)                       643,100
     Construction  fees
       (10% of direct  costs)                       643.100
     Startup (2% of direct costs)                 128.600
     Performance tests  (minimum $2000)       	10,000

    TOTAL INDIRECT COSTS                      $  2.067.900

    Contingencies
      (20% of direct and indirect  costs)       $  1.699.800

    Total turnkey  costs
      (Direct +  Indirect + Contingencies)       10.198.900

    Land                                    	2,000

    Working  capital  (25% of total direct
     operating  costs)                        	622,300

    GRAND TOTAL
      (Turnkey + Land  +  Working  Capital)       $10,823,200
     a Quote from Babcock & Wilcox,  Inc.,  August 17,  1978
     N.A. - Not applicable.
                              A-77

-------
   TABLE A-52.-  ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED,
WATER-TUBE PULVERIZED-COAL-FIRED BOILER FIRING EASTERN LOW-SULFUR
              COAL WITH A THERMAL INPUT OF 58.6 MW
            (200 x 106 Btu/h;  750 psig/750°F design)


 DIRECT COST

      Direct labor                                $  421,200
      Supervision                                    136,900
      Maintenance labor                              192,200
      Maintenance materials
      Replacement parts                              250,000
      Electricity                                    237.900
      Steam                                            N.A.
      Cooling  water                                    N.A.
      Process  water                                    3,000
      Fuel                                          1,219,400
      Bottom ash disposal                             21,o61T
      Chemicals                                         7,500"

      Total  direct cost                           $2,489,100

 OVERHEAD

      Payroll  (30% of  direct  labor)                $  126,400

      Plant  (26% of labor,  parts  & maint.)            2finrtoo

      Total  overhead costs                         $  386.500
                   t
 BYPRODUCT  CREDITS                                     N.A.

 CAPITAL CHARGES

      G & A, taxes t insurance
       (4%  of  total turnkey costs)                 $  408,000

      Capital  recovery factor
       CL0.14« of  total turnkey costs)              1,034,200

      Interest on  working capital
       (10%  of working capital)                        62.200

          Total capital charges                   $1.504.400

 TOTAL ANNUALIZED  COSTS                            54,380,000


 3 Included with replacement parts.
 N.A.  - Not applicable.


                                A-78

-------
    TABLE A-53.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED,
  WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING SUBBITUMINOUS
              COAL WITH A THERMAL INPUT OF 58.6 MW
	(200 x 10° Btu/h; 750  psig/750° F design)	

CAPITAL COSTS
DATE OF ESTIMATE
June 30,  1978
(FOR COSTS  INDEXING)
     EQUIPMENT COST a

      Boiler  (with fans and ducts)
      Stack
      In strumentation
      Pulverizers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler  feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling  system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

      Total Equipment Cost

      INSTALLATION COSTS,  DIRECT

      Boiler  (including  founda-
        tions  and steel)
      Stack
      In strumentation
      Pulverizers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler  feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling  system
      Ash disposal  system
      Thawing equipment
      Fuel-oil system
                   $  3,067.200	
                        365,000	
                        228,000	
                        754.600	
                        158.400	
                   Incl. w/coal handling
                   	29.000	
                   Incl. w/boiler
                   	58.000	
                   	16.300	
                        20.000	
                   	1.500	
                        28.800	
                        380.000	
                        259.200	
                   Incl. w/coal handling
                   	N.A.	

                    $  5.366.000	
                    $ 1,56.0^-OOQ	

                        60,000	
                   	35,000	
                    Incl. w/boiler
                    Incl. w/boiler
                    Incl. w/coal handling
                   	5,000	
                    Incl. w/boiler
                   	8,000	
                   	2,000	
                   	3., 500	
                   	1,500	
                        396.000	
                        172,800	
                    Incl. w/coal handling
                   	N.A.
 N.A. - Not applicable.
                               A-79

-------
TABLE A-53. (continued)
    INSTALLATION COSTS, DIRECT (cont.)

     Foundations and supports
     Duct work (not incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

    Total Installation Costs

    TOTAL DIRECT COSTS
     (Equipment + Installation)

    INSTALLATION COSTS, INDIRECT

     Engineering
      (10% of direct costs)
     Construction and field expense
      (10% of direct costs)
     Construction fees
      (10% of direct costs)
     Startup (2% of direct costs)
     Performance tests (minimum $2000)

    TOTAL INDIRECT COSTS

    Contingencies
     (20% of direct and indirect costs)

    Total turnkey costs
     (Direct + Indirect + Contingencies)

    Land

    Working capital (25% of total  direct
     operating costs)

    GRAND TOTAL
     (Turnkey + Land +' Working Capital)
      259,200
        N.A.
      115.200
         .?nn
       14 .4DD
      160.000
      547,200
   3.455^000
S  P
          nnn
$	ga?  inn
     RR2.inn
     176 .400
       10,000
S  2,832,700
S  2.330.700
         ann
        2,000
     482.000
$ 14,468,400
      Quote from Babcock & Wilcox,  Inc.,  August 17,  1978.
    N.A.  - Not applicable
                             A-80

-------
   TABLE A-54.   ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED,
  WATER-TUBE,  PULVERIZED-COAL-FIRED BOILER FIRING SUBBITUMINOUS
              COAL WITH  A THERMAL INPUT OF 58.6 MW
            (200 x 106 Btu/h;  750 psig/750°F design)

DIRECT COST

     Direct labor                                 S  421.200
     Supervision                                     136,900
     Maintenance  labor                               192,200
     Maintenance materials
     Replacement parts                               360,000
     Electricity                                     342.500
     Steam                                             N.A.
     Cooling water                                     N.A.
     Process water          .                           3,000
     Fuel                                            441,500
     Bottom ash disposal                              23,100
     Chemicals                                         7,500

     Total direct cost                             $1,927,900

OVERHEAD

     Payroll  (30% of direct labor)                 $  126,400

     Plant  (26% of labor, parts  & maint.)            288'700

     Total overhead costs                          $  415.100
                  /
BYPRODUCT CREDITS                                      N.A.

CAPITAL CHARGES

     G l A, taxes t insurance
       (4% of total turnkey costs)                  $  559,400

     Capital recovery factor
       (10.14* of total turnkey costs)               1,418.000

     Interest on working capital
       (10% of working capital)                         48,200

          Total capital charges                    S7
TOTAL ANNUALIZED COSTS                             £4.368.600


3 Included with replacement parts.

N.A. - Not applicable.
                                 A-81

-------
  TABLE A-55.   ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED,
  WATER-TUBE,  PULVERIZED-COAL-FIRED BOILER FIRING EASTERN
     MEDIUM-SULFUR COAL WITH A THERMAL INPUT OF 58.6 MW
          (200 x 106 Btu/hr; 750 psig/750°F design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS INDEXING)
     EQUIPMENT COSTa

      Boiler (with fans & ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler (including founda-
       tions and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. - Not applicable.
                          $ 2.224.000
                              365.OOP
                              228rOQQ
                              548,nnn
                              115.QQQ
                          incl.  w/coal handling
                               29.000
                          incl.  w/boiler
                               58.000
                          	1 6r3QQ
                          	2QfQQQ
                          	1.500
                               21.000
                              276.OOQ
                              188.000
                          incl w/coal handling
                               N.A.	

                          $ 4.089.800
                          $ 1.133rOOQ
                               60.000
                               35fOOP
                          lnc;l ,  VT/hni
                          incl.  w/boiler
                          incl.  w/coal handling
                          	5fQOQ
                          incl.  w/boiler
                          	8fQQQ
                          	2,000
                          	3f5QQ
                          	lr50Q
                              287fOOP
                              125fOOQ
                          incl.  w/coal handling
                            A-82

-------
TABLE A-55.  (continued)
INSTALLATION COSTS, DIRECT (cont.)

     Foundations and supports                     	188,OOP
     Ductwork (not incl. w/boiler)                    N.A.
     Piping                                            84,000
     Insulation                                        84,000
     Painting                                     	10.000
     Electrical          .                             160,000
     Buildings                                        397.000

     Total installation cost                      $ 2,583,000

TOTAL DIRECT COSTS
  (equipment + installation)                       $ 6r672r8QQ

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)                       $   667.300
     Construction and field expense
       (10% of direct costs)                           667.3QQ
     Construction fees
       (10% of direct costs)                           667.300
     Start-up  (2% of direct costs)                     133,500
     Performance tests  (minimum $2000)   .         	10,000

TOTAL  INDIRECT COSTS                              $ 2.145.400

Contingencies
  (20%  of direct and indirect costs)               S lr763f6QQ

Total  Turnkey Costs
   (direct+indirect+contingencies)                  lQr581r8QQ

Land                                              	2PQOQ

Working capital  (25% of total direct
 operating costs)                                     577,700

GRAND  TOTAL
  (turnkey*land+working capital)                   $11,161,500
aQuote  from Babcock  & Wilcox, Inc., August 17, 1978.

N.A. -  Not  applicable.

                            A-83

-------
TABLE A-56.  ESTIMATED ANNUALZZED COSTS OF A FIELD-ERECTED,
WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING EASTERN
   MEDIUM-SULFUR COAL WITH A THERMAL INPUT OF 58.6 MW
        (200 x 106 Btu/hr; 750 psig/750°F design)
 DIRECT COST

      Direct labor                             S  421.200
      Supervision                                 136.900
      Maintenance labor                           192.200
      Maintenance materials                    _ a
      Replacement parts                           261.000
      Electricity                                 248.300
      Steam                                       N.A.
      Cooling water                               N.A.
      Process water                            _ 3 .000
      Fuel                                        998.600
      Bottom ash disposal                          42.000
      Chemicals                                _ 7.500

      Total direct cost                        $2.310.700

 OVERHEAD

      Payroll (30% of direct labor             $  126.400

      Plant (26% of labor,  parts & maint.)         262.900

      Total overhead costs                      $  389.300

 BY-PRODUCT CREDITS                                N.A.

 CAPITAL CHARGES

      G & A, taxes & insurance
       (4% of total turnkey costs)              $  423r3QQ

      Capital recovery factor
       (10.14 % of total  turnkey costs)          l f
      Interest on working capital                  c7
       (10% of working capital)                     ;>/,
           Total capital charges               $1,554,100

 TOTAL ANNUALIZED COSTS                        $4.254.100

 a Included with replacement parts.
 N.A.  - Not applicable.

                          A-84

-------
     TABLE A-57-  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED,
     WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING EASTERN
         HIGH-SULFUR COAL WITH A THERMAL INPUT OF 117.2 MW
             (400 x 106 Btu/hr; 750 psig/750°F design)
  CAPITAL COSTS
  DATE OF ESTIMATE.
June 30.  1978  fFOB COSTS INDEXING)
       EQUIPMENT COSTa

        Boiler  (with  fans  fc  ducts)
        Stack
        Instrumentation
        Pulverizers
        Feeders
        Crushers
        Deaerator
        Heaters
        Boiler  feed pumps
        Condensate systems
        Water treating system
        Chemical feed
        Compressed air system
        Coal handling system
        Ash disposal  system
        Thawing  equipment
        Fuel-oil system

       Total Equipment Cost

       INSTALLATION COST,  DIRECT

        Boiler  (including  founda-
          tions and steel)
        Stack
        Instrumentation
        Pulverizers
        Feeders
        Crushers
        Deaerator
        Heaters
        Boiler  feed pumps
        Condensate system
        Water treating system
        Chemical feed
        Coal handling system
        Ash disposal  system
        Thawing  equipment
        Fuel-oil system
                  $ 4,002,300
                     650,000
                     378.600
                     982,800
                     209.300
                   Incl. v/coal handling
                      60,000
                   Incl. w/boiler
                     150,000
                      25,000
                      60,000
                       4, OP'S"
                      46.800
                   1,170,000
                     386,100
                   Incl. v/coal handling
                      N.A.
                  $ 8,124,900
                  $ 2,538,900

                    Incl, w/equipment
                      llQrQQQ
                    Tncl. w/boiler
                    Tncl. w/boiler
                    Inel. w/eoal handling
                       12.000 '
                    Incl. w/boiler
                       18:000
                       16.000  .
                        2.000
                      737.100
                      304,200
                    Incl. w/coal  handling
                       N.A.
N.A. - Not applicable.
                              A-85

-------
 TABLE A-57.(continued)
 INSTALLATION COSTS,  DIRECT (cont.)

      Foundations  and supports                         386,000
      Duct work  (not  incl.  w/boiler)                   N.A.
      Piping                                            146,000
      Insulation                                       129,000
      Painting                                         .19.000
      Electrical                                       340,000
      Buildings                                         761,000

      Total installation  cost                      $  5,529,200

 TOTAL DIRECT COSTS
  (equipment  + installation)                       S13r654rinn

 INSTALLATION COSTS,  INDIRECT

      Engineering
       (10% of direct costs)                       $_L
      Construction and field expense
       (10% of direct costs)                        __L
      Construction fees
       (10% of direct costs)                          1,365,400
      Startup  (2% of direct costs)                   	273f100
      Performance  tests (minimum $2000)             	 *" ~"
TOTAL  INDIRECT COSTS                 '             $ 4,384,300

Contingencies
   (20% of direct and indirect costs)              $ 3,607,700

Total Turnkey Costs
  (direct+indirect+contingencies)                   21,646,100

Land                                                    4'00&

Working capital  (25% of total direct
 operating costs).                                     987,900

tSRAND TOTAL
-  (turnkey+land+working capital)                   $ 22,638,000


  Quote from Babcock &  Wilcox,  Inc., August  17,  1978.
N.A. - Not applicable.


                            A-86

-------
    TABLE A-58.   ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED,
     WATER-TUBE, PULVERI ZED-COAL-FIRED BOILER FIRING EASTERN
          HIGH-SULFUR COAL WITH A THERMAL  INPUT OF 117.2 MW
             (400 x 106 Btu/hr;  750 psig/750°F design)

 DIRECT COST

      Direct labor                                $   737,100
      Supervision                                     205.400
      Maintenance labor                               384,5^0"
      Maintenance materials                        _ a
      Replacement parts                               409,500
      Electricity                                     561.600
      Steam                                            N.A.
      Cooling water                                    N'A* —
      Process water                                     6.100
      Fuel                                           1 555 aoo
      Bottom ash disposal                              75 f. 50 6
      Chemicals                                         i
      Total direct cost                           $_3.951f5QO

 OVERHEAD

      Payroll  (30% of direct labor)                $   221,100

      Plant (26% of labor,  parts & jnaint.)             451,500

      Total overhead costs                         $   672,600

 BYPRODUCT  CREDITS                                     N>A>

 CAPITAL  CHARGES

      G & A, taxes £ insurance
       (4%  of total  turnkey  costs)                 $   865,800

      Capital recovery  factor
      (10.14^ of total turnkey costs)               2.194.900

      Interest on working capital
      (10% of working  capital)                         98,800

          Total capital charges                   $ 3,159,500

TOTAL ANNUALIZED COSTS                            $ 7,733,600

£
 Included in replacement parts.

N.A.  - Not Applicable
                               A-87

-------
      TABLE A-59.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED,
      WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING EASTERN
          LOW-SULFUR COAL WITH A THERMAL INPUT OF 117.2 MW
             (400 x 106 Btu/hr; 750 psig/750°F design)
   CAPITAL COSTS
   DATE OF ESTIMATE.
June 30, 1978  ryQR COSTS INDEXING)
        EQUIPMENT COST3

         Boiler (with fans fc ducts)
         Stack
         Instrumentation
         Pulverizers
         Feeders
         Crushers
         Deaerator
         Heaters
         Boiler feed pumps
         Condensate systems
         Water treating system
         Chemical feed
         Compressed air system
         Coal handling system
         Ash disposal system
         Thawing equipment
         Fuel-oil system

        Total Equipment Cost

        INSTALLATION COST, DIRECT

         Boiler (including founda-
          tions and steel)
         Stack
         Instrumentation
         Pulverizers
         Feeders
         Crushers
         Deaerator
         Heaters
         Boiler feed pumps
         Condensate system
         Water treating system
         Chemical feed
         Coal handling system
         Ash disposal system
         Thawing equipment
         Fuel-oil system
                   $  3.420.800
                       650,000
                       378.600
                       840,000
                       178,900
                     Incl. w/coal handling
                       60,000
                    Incl. w/boiler
                      150,000
                       25,000
                       60, POTT
                        4,000
                       40,OOlT
                    1,000, OOTT
                      330.000
                    Incl. w/coal handling
                       N.A.
                  $ 7,137,300
                  $ 2,170,000

                    Incl. w/equipment
                      110,000
                    Incl. w/boiler
                    JEncl. w/boiler
                    Incl. w/coal handling
                       12,000
                    Incl. w/boiler
                        18,OOlT
                        10,O
                        16,000
                           '
                         2,0'ffTr
                       630,000
                    inel. w/eoal  handling
                       N.A.
N.A. - Not applicable.
                              A-88

-------
TABLE A-59. (continued)
INSTALLATION COSTS, DIRECT (cont.)

     Foundations and supports                         330,000
     Duct work (not incl. w/boiler)                    N.A*—
     Pipina                                           125,000
     Insulation                                    	110,000
     Painting                                      	 If/OQQ
     Electrical                                       340,000
     Buildings                                        650,000

     Total installation  cost                      $_A
TOTAL DIRECT COSTS
  (equipment + installation)                       $11,936,300

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)                       $  1.193.600
     Construction and field expense
       (10% of direct costs)                         1,193,600
     Construction fees
       (10% of direct costs)                         1,193.6.0.0
     Startup  (2% of direct costs)                     238.700
     Performance tests  (minimum  52000)                 15.000

TOTAL  INDIRECT COSTS                 '             $  3,834,500

Contingencies
   (20% of direct and indirect costs)              $  3.154,200

Total  Turnkey Costs
  (direct+indirect+contingencies)                   18,925,000

Land                                                    4'000

Working capital  (25% of  total direct
  operating costs)                                   1,165
•GRAND TOTAL
.  (turnkey+land+working  capital)                   s2Qf094TOQO


a Quote  from Babcock  &  Wilcox, Inc., Augustl? , 1978.

N.A. - Not applicable.
                            A-89

-------
     TABLE  A-60.  ESTIMATED.ANNUALIZED COSTS OF A FIELD-ERECTED,
      WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING EASTERN
         LOW-SULFUR COAL WITH A THERMAL  INPUT OF 117.2 MW
             (400 x  106 Btu/hr;  750 psig/750°F design)
 DIRECT COST

      Direct labor                                $    737,100
      Supervision                                      205,400
      Maintenance labor                                384,500
      Maintenance materials                        _ a _
      Replacement parts                                350.000
      Electricity                                      480. OOP
      Steam                                            N.A.
      Cooling water                                    N.A.
      Process water                                      6,100
               v ^-      ,                              .
      Bottom ash disposal                                42  000
      Chemicals                                    '    ifi'
      Total  direct  cost                            $ 4,659,900

 OVERHEAD

      Payroll  (30%  of direct  labor)                S    221. 1QQ

      Plant  (26% of labor, parts  t maint.)              436.000

      Total  overhead costs                         $    657.100

 BYPRODUCT CREDITS                                      N^A

 CAPITAL CHARGES

      G i A, taxes  t insurance
      (4% of total turnkey costs)                 $    757,000

     Capital recovery factor
      (10.14^ of total turnkey costs)                1,919,000

     Interest on working capital
      (10% of working capital)                         116,500

          Total capital charges                   $2.792,500

TOTAL ANNUALI ZED COSTS                            $ 8,109,500


 Included with replacement parts.

 N.A.  - Not  Applicable


                               A-90

-------
     TABLE  A-61.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED,
         WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING
       SUBBITUMINOUS COAL WITH A THERMAL INPUT OF 117.2 MW
             (400 x 106 Btu/hr; 750 psig/750°F design)
  -CAPITAL COSTS
   DATE OF ESTIMATE.
June 30, 1978   (FOP COSTS INDEXING)
        EQUIPMENT COSTa

         Boiler (with fans i ducts)
         Stack
         Instrumentation
         Pulverizers
         Feeders
         Crushers
         Deaerator
         Heaters
         Boiler feed pumps
         Condensate systems
         Water treating system
         Chemical feed
         Compressed air system
         Coal handling system
         Ash disposal system
         Thawing equipment
         Fuel-oil system

        Total Equipment Cost

        INSTALLATION COST, DIRECT

         Boiler (including founda-
          tions and steel)
         Stack
         Instrumentation
         Pulverizers
         Feeders
         Crushers
         Deaerator
         Heaters
         Boiler feed pumps
         Condensate system
         Water treating system
         Chemical feed
         Coal handling system
         Ash disposal system
         Thawing equipment
         Fuel-oil system
                      4.926.OOP
                        650.000
                        378.600
                      1,209.600
                        257.600
                     Incl.  w/coal  handling
                         60.000
                     Incl.  w/boiler
                        150.000
                         25.000
                         60,000
                          4,000
                         57,600
                      1,440,000
                        475,200
                     Incl.  w/coal handling
                         N.A.
                    $  9/693,600
                    $  3,124,800

                     Incl.  w/equipment
                        iio.o"bT
                     Incl.  w/boiler
                     Incl.  w/boiler
                     Incl.  w/coal  handling
                         12,000
                     Incl.  w/boiler
                         18,000
                         10,000
                         16,000
                          2,000
                        907,200
                        374,400
                     Incl.  w/coal handling
                         N.A.
N.A. - Wot applicable.
                              A-91

-------
 TABLE  A-61.(continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and  supports                         4.75,0.0.0
     Duct work  (not incl. w/boiler)                   N.A.
     Piping             .                              180.000
     Insulation                                    	158,000
     Painting                                      	23,000
     Electrical                                    	340,000
     Buildings                                     	936,000
                •
     Total installation cost                      $ 6.686,400

TOTAL DIRECT COSTS
  (equipment + installation)                       $16,380,000

INSTALLATION COSTS, INDIRECT

     Engineering
      (10% of direct  costs)                       $ 1,638,000
     Construction and field expense
      (101 of direct  costs)                         1,638,000
     Construction fees
      (10% of direct  costs)                         l,638fOOO
     Startup (2% of direct costs)                   	327,6Qfl
     Performance tests  (minimum $2000)                 I5ronn

TOTAL INDIRECT COSTS                              $ 5y256f600

Contingencies                                     ,..     _ ,
   (20% of direct and  indirect costs)              » 4,3Z/,300

Total Turnkey Costs
  (direct+indirect+contingencies)                   25,Qfi3,Qnn

Land                                                    4 rQQQ

Working capital (25% of total direct
 operating costs)                                      868f700

•GRAND TOTAL
  (turnkey-Hand+working capital)                   $26,836,600


  Quote from Babcock & Wilcox,  Inc., August 17,  1978.

NYA. - Not applicable-.

                            A-92

-------
    TABLE A-62.  ESTIMATED ANNUALIZED COSTS FOR A FIELD-ERECTED,
         WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING
       SUBBITUMINOUS COAL WITH A THERMAL INPUT OF 117.2 MW
             (400 x 106 Btu/hry 750 psig/750°F design)
DIRECT COST

     Direct labor                                 $   737.100
     Supervision                                     205.400
     Maintenance labor                               384.500
     Maintenance materials                             a	
     Replacement parts                               504 fOOP
     Electricity                                     fioix?nn
     Steam                                            TJ.A.
     Cooling water                                    TJ.&.
     Process water                                     6.100
     Fuel                                            883.000
     Bottom ash disposal                              47.300
     Chemicals                                        J.6f OOP

     Total direct cost                            S 3.474.600

OVERHEAD

     Payroll  (30% of direct labor)                $   221.100

     Plant (26% of labor, parts & maint.)            476,100

     Total overhead costs                         s   697.200

BYPRODUCT CREDITS                                     N.A.

CAPITAL CHARGES

     G t A, taxes t insurance
      (4% of total turnkey costs)                 $ 1.038.600

     Capital recovery factor
      (10.14* of total turnkey costs)                2,632,700

     Interest on working capital
      (10% of working capital)                         86.900

          Total capital charges                   $  3^758.200

TOTAL ANNUALIZED COSTS                            $  7.930,000


alncluded in replacement parts.


N.A. - Not Applicable

                               A-93

-------
      TABLE A-63.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED,
      WATER-TUBE,  PULVERIZED-COAL-FIRED BOILER FIRING EASTERN
       MEDIUM-SULFUR COAL WITH A THERMAL INPUT OF 117.2 MW
             (400  x 106 Btu/hr; 750 psig/750°F design)
  CAPITAL COSTS
  DATE OF ESTIMATE.
June 30. 1978   frnp COSTS INDEXING)
       EQUIPMENT COST

        Boiler  (with fans  fc ducts)
        Stack
        Instrumentation
        Pulverizers
        Feeders
        Crushers
        Deaerator
        Heaters
        Boiler feed pumps
        Condensate systems
        Water treating system
        Chemical feed
        Compressed air system
        Coal handling system
        Ash disposal system
        Thawing equipment
        Fuel-oil system

       Total Equipment Cost

       INSTALLATION COST, DIRECT

        Boiler (including founda-
         tions and steel) .
        Stack
        Instrumentation
        Pulverizers
        Feeders
        Crushers
        Deaerator
        Heaters
        Boiler feed pumps
        Condensate system
        Water treating system
        Chemical feed
        Coal handling system
        Ash disposal system
        Thawing equipment
        Fuel-oil system
                    $ 3,571,300
                       fisn nnn
                       378.600
                       877,000
                       186,800
                     Incl. w/coal handling
                        60.000
                         . v/boiler
                       150,000
                        25,000
                        60,000"
                         4,00"0~
                        41,80"0"
                     1,044,000
                       344,500
                     Incl.  w/coal handling
                         N.A
                   $7,393,000
                   $2,265.500

                     Incl.  w/eouipment
                       110,000
                     Incl.  w/boiler
                     Incl.  w/boiler
                     Incl.  w/coal handling
                        12,000
                     Incl.  w/boiler
                        18,000
                        10,000
                       16,000
                        2,0015
                      657,700
                      271,400
                    Incj.. w/coal handling
                           "
N.A. - Not applicable.
                              A-9 4

-------
TABLE  A-63.(continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports                         344r500
     Duct work (not incl. w/boiler)                   N!A*
     Pipina                                           "0,500
     Insulation
     Paintina
     Electrical                                       340,000
     Buildings                                        678,600

     Total installation cost                     $  4,987,700

TOTAL DIRECT COSTS
  (equipment + installation)                      $ 12,380,700

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)                      $  1,238,100
     Construction and field expense
       (101 of direct costs)                         1,238,100
     Construction fees
       (10% of direct costs)                         ^»2^8,101p
     Startup (2% of direct costs)                      Z4/,6UU
     Performance tests  (minimum $2000)                 15,000

TOTAL INDIRECT COSTS                 '            $  3,976,900

Contingencies
   (20% of direct and indirect costs)             $  3,271,500

Total Turnkey Costs
  (direct+indirect+contingencies)                   19,629,100

Land .                                                   4,000

Working capital  (25% of total direct
 operating costs)                                   1.074.200

<3RAND TOTAL
  (turnkey+land+working capital)                  $ 20,707,300


a Quote from Babcock & Wilcox,  Inc.,  August 17,  1978.

N.A. - Not applicable.
                             A-95

-------
   TABLE \A-64.  ESTIMATED ANNUALIZED COSTS OF-A FIELD-ERECTED,
     WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING EASTERN
       MEDIUM-SULFUR COAL WITH A THERMAL INPUT OF 117.2 MW
            (400 x 10^ Btu/hr; 750 psig/750°F design)
DIRECT COST
     Direct labor                                 $  737,100
     Supervision                                     205,400
     Maintenance labor                               384,500
     Maintenance materials
     Replacement parts                               365,400
     Electricity                                     501,100
     Steam                                             N.A.
     Cooling water                                     N.A.
     Process water                                     6,100
     Fuel                                          1.997.000
     Bottom ash disposal                              84,000
     Chemicals                                        16,000"

     Total direct cost                            S4.296.600

OVERHEAD

     Payroll (30% of direct labor)                $  221,100

     Plant (26% of labor, parts t maint.)            440,000

     Total overhead costs                         $  661,100

BYPRODUCT CREDITS                                     N.A.

CAPITAL CHARGES

     G & A, taxes & insurance
      (4% of total turnkey costs)                 $  785,200

     Capital recovery factor
      (10.14* of total turnkey costs)               ifQQQf4QQ

     Interest on working capital                          ....
      (10% of working capital)                   '    107,400

          Total capital charges                   $ 2,883,000

TOTAL ANNUALIZED COSTS                            $ 7,840,700
a  Included with replacement parts.
 N.A.  - Not applicable.

                                A-96

-------
 TABLE A-65.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED,
 WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING EASTERN
    HIGH-SULFUR COAL WITH A THERMAL INPUT OF 205.1 MW
          (700 x 106 Btu/hr; 900 psig/750°F design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
     EQUIPMENT COST

      Boiler  (with fans & ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler  feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler  (including founda-
       tions  and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler  feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. - Not applicable.
                           $  6,487,000
                             1,250,000
                               610r800
                             1,625,000
                               334,000
                           incl.  w/coal handling
                          	85,000
                           incl.  w/boiler
                               195,000
                          	35,000
                                90,000
                                 4,000
                                60,000
                             1,747,000
                               819,000
                           incl. w/coal handling
                               N.A.
                           $13,341,800
                           $ 3,604,000
                           incl.  w/equipment
                               160,000
                           incl.  w/boiler
                           incl.  w/boiler
                           incl.  w/coal handling
                          	19,000
                           incl.  w/boiler
                          	25,000
                                16,000
                                28,000
                                 2,000
                             1.092,000
                               546,000
                           incl. w/coal hand1ing
                               N.A.
                            A-97

-------
 TABLE A-65.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports                          710,000
     Ductwork  (not incl. w/boiler)                     N.A.
     Piping                                            262,000
     Insulation                                        208,000
     Painting                                           32,000
     Electrical                                        650,000
     Buildings                                       1.365.000

     Total installation cost                       $ 8r719fQQQ

TOTAL DIRECT COSTS
  (equipment + installation)                        $22,060,800

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)                        $ 2.206.100
     Construction and field expense
       (10% of direct costs)                          2f306.100
     Construction fees
       (10% of direct costs)                          2f20fifinn
     Start-up  (2% of direct costs)                     441.200
     Performance tests  (minimum $2000)   .          	25.000

TOTAL INDIRECT COSTS                               S 7rQ84r5nn

Contingencies
  (20% of direct and indirect costs)                $ 5,829,100

Total Turnkey Costs
   (direct+indirect+contingencies)                   34,974,400

Land                                               	2,000

Working capital  (25% of total direct
  operating costs)                                    1,513,800

GRAND TOTAL
  (turnkey+land+working capital)                    $36,490,200


 Quote from Babcock & Wilcox,  Inc., August 17, 1978.
N.A. - Not applicable.


                           A-98

-------
TABLE A-66.  ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED,
WATER-TUBE, PULVERIZED-CO^L-FIRED BOILER FIRING EASTERN
   HIGH-SULFUR COAL WITH A THERMAL INPUT OF 205.1 MW
         (700 x 106 Btu/hr; 900 psig/750°F design)
 DIRECT COST

      Direct labor                             $ 1,000,300
      Supervision                                  205,400
      Maintenance labor                        	512,600
      Maintenance materials                    	a
      Replacement parts                            463,300
      Electricity                                  983,000
      Steam                                       N.A.
      Cooling water                               N.A.
      Process water '                          	10,600
      Fuel                                       2,722,600
      Bottom ash disposal                      	132,500
      Chemicals                                	25.000

      Total direct cost                        $ 6,055.300

 OVERHEAD

      Payroll  (30% of direct labor             $   300,100

      Plant  (26% of labor, parts & maint.)         567.200

      Total overhead costs                     S   867.300

 BY-PRODUCT CREDITS                               N.A.

 CAPITAL CHARGES

      G & A, taxes & insurance
        (4% of  total turnkey costs)             S 1.399.000

      Capital  recovery factor
        (10.14  % of total turnkey costs)          3.546.4QQ

      Interest on working capital
        (10% of working capital)                    151.400

           Total capital charges               $ 5.096.800

 TOTAL ANNUALIZED COSTS                        S12r019.4QQ

 a Included with replacement parts.
 N.A. - Not applicable.
                           A-99

-------
 TABLE A-67.  ESTIMATED  CAPITAL  COSTS  OF  A FIELD-ERECTED,
 WATER-TUBE, PULVERIZED-COAL-FIRED  BOILER FIRING EASTERN
     LOW-SULFUR COAL WITH A  THERMAL INPUT OF  205.1  MW
          (700 x 106 Btu/hr;  900  psig/750°F design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
     EQUIPMENT COST

      Boiler (with fans & ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler (including founda-
       tions and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. - Not applicable.
                           S  5,524,000
                             1,250,000
                               sio,ann
                             1,, "334,000
                               284,000
                           incl.  w/coal  handling
                          	85,000
                           incl.  w/boiler
                               195,000
                                35,000
                          	90.000
                          	4.000
                          	51.000
                             1,488,000
                               698.000
                           incl.  w/coal  handling
                               N.A.	

                           $11.698.800
                           $  3.069.000
                           incl. w/equipment
                               16QrOOO
                           incl. w/boiler
                           incl. w/boiler
                           incl. w/coal handling
                               19.000
                           incl. w/boiler
                          	25.000
                                16.000
                                28,000
                                 2.000
                               930.000
                              465.000
                          incl. w/coal handling
                          	N.A.	
                            A-100

-------
TABLE A-67.  (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and  supports                          605.000
     Ductwork  (not  incl. w/boiler)                    N.A.
     Piping                                            223,000
     Insulation                                        177.000
     Painting                                      	27,000
     Electrical                                        650,000
     Buildings                                       1,163,000

     Total installation cost                        $ 7,559,000

TOTAL  DIRECT COSTS
  (equipment +  installation)                         $19,257,800

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct  costs)                         $ 1.925.800
     Construction and field expense
       (10% of direct  costs)                          lr925.80Q
     Construction fees
       (10% of direct  costs)                          1,925,800
     Start-up  (2% of  direct costs)                     385.200
     Performance tests (minimum $2000)    .         	25.000

TOTAL  INDIRECT COSTS                                S 6r187.6QO

Contingencies
  (20%  of  direct and indirect  costs)                 $ 5,089,100

Total  Turnkey  Costs
   (direct+indirect+contingencies)                    30,534,500

Land                                              	2,000

Working capital  (25%  of  total direct
  operating costs)                                    1,832,700

GRAND  TOTAL
  (turnkey+land+working capital)                     $32,369,200


aQuote from Babcock & Wilcox,  Inc.,  August 17,  1978.

N.A. - Not applicable.


                            A-101

-------
TABLE A-68.  ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED,
WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING EASTERN
    LOW-SULFUR COAL WITH A THERMAL INPUT OF 205.1 MW
        (700 x 106 Btu/hr; 900 psig/750°F design)
 DIRECT COST

      Direct labor                              $ 1.000,300
      Supervision                              	205,400
      Maintenance labor                         	512,600
      Maintenance materials                     	a
      Replacement parts                             395,300
      Electricity                                  840,100
      Steam                                    	N.A.
      Cooling water                             	N.A.
      Process water                             	10,600
      Fuel                                       4,267,900
      Bottom ash disposal                       	73.600
      Chemicals                                     25,000

      Total direct cost                         $ 7.330.800

 OVERHEAD

      Payroll (30% of  direct  labor              $   300.100

      Plant (26% of  labor, parts  & maint.)          549.500

      Total overhead costs                      S   849.600

 BY-PRODUCT CREDITS                                N.A.

 CAPITAL CHARGES

      G & A,  taxes & insurance
       (4% of total  turnkey costs)              S 1.221.400

      Capital recovery factor
       (10.14 % of total turnkey  costs)           3rQ96.200

      Interest on working capital
       (10% of working capital)                     183.300

           Total capital charges                $ 4.500.900

 TOTAL ANNUALIZED COSTS                         S12,681

 a Included with replacement  parts.
 N.A.  - Not applicable.


                          A-102

-------
  TABLE A-69.  ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED,
WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING SUBBITUMINOUS
            COAL WITH A THERMAL INPUT OF 205.1 MW
           (700 x 106 Btu/hr; 900 psig/750°F design)
 CAPITAL COSTS
 DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
      EQUIPMENT COST*

       Boiler (with fans & ducts)
       Stack
       Instrumentation
       Pulverizers
       Feeders
       Crushers
       Deaerators
       Heaters
       Boiler feed pumps
       Condensate systems
       Water treating system
       Chemical feed
       Compressed air system
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel-oil system

      Total Equipment Cost

      INSTALLATION COST, DIRECT

       Boiler  (including founda-
        tions and steel)
       Stack
       Instrumentation
       Pulverizers
       Feeders
       Crushers
       Deaerators
       Heaters
       Boiler feed pumps
       Condensate system
       Water treating system
       Chemical feed
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel-oil system

 N.A.  - Not applicable.
                          $ 7.960rOOO
                            1. 250. OOP
                              61Q 800
                              409.000
                          incl.  w/coal handling
                               85,000
                          incl .  w/boiler
                              195,000
                               35,000
                               90,000
                                4,000
                               74,000
                            2,144,000
                            1,005,000
                          incl. .w/eoal handling
                              N.A. _

                           $15,855,800
                           $ 4.422.000
                           inc 1. w/ ecru ipmen t
                               160.000
                           incl. w/boiler
                           incl. w/boiler
                           incl. w/coal hand1ing
                           	19.000
                           incl. w/boiler
                           	25.000
                                16.000
                                28,000
                                 2.000
                             1,340,000
                               670.000
                           incl. w/coal handling
                               N.A.
                             A-103

-------
TABLE A-69.   (continued)
 INSTALLATION COSTS,  DIRECT (cont.)

      Foundations and supports                          871,000
      Ductwork (not incl.  w/boiler)                      N.A.
      Piping                                            322,000
      Insulation                                        255,000
      Painting                                           39,000
      Electrical                                        650,000
      Buildings                                       1,675,000

      Total installation cost                       $10,494,000

 TOTAL DIRECT COSTS
  (equipment + installation)                         $26,349,800

 INSTALLATION COSTS,  INDIRECT

      Engineering
       (10% of direct costs)                         $  2,635,000
      Construction and field  expense
       (10% of direct costs)                           2,635,000
      Construction fees
       (10% of direct costs)                           2,635,000
      Start-up (2% of direct  costs)                      527,000
      Performance tests (minimum $2000)    .         	25,000

 TOTAL INDIRECT COSTS                               $  8.457,000

 Contingencies
  (20% of direct and  indirect costs)                 $  6.961.400

 Total Turnkey Costs
   (direct+indirect+contingencies)                   41,768,200

 Land                                              	2,000

 Working capital (25% of total direct
  operating costs)                                     1.290.100

 GRAND TOTAL
  (turnkey+land+workin,g capital)                    $43 .060r300


 Quote from Babcock & Wilcox, Inc., August 17, 1978.

N.A. - Not applicable.


                            A-104

-------
  TABLE A-70.  ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED,
WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING SUBBITUMINOUS
            COAL WITH A THERMAL INPUT OF 205.1 MW
           (700 x 106 Btu/hr; 900 psig/750°F design)
   DIRECT COST

        Direct labor                             $ 1,000,300
        Supervision                              	205,400
        Maintenance labor                        	512,600
        Maintenance materials                    	a
        Replacement parts                        	569,500
        Electricity                                1,209,600
        Steam                                        N.A.
        Cooling water                            	N.A.
        Process water                            	10/600
        Fuel                                       1.545,300
        Bottom ash disposal                      	82,000
        Chemicals                                     25.000

        Total direct cost                        $ 5,160.300

   OVERHEAD

        Payroll  (30% of direct labor             $   300.100

        Plant  (26% of labor, parts & maint.)         594.800

        Total overhead costs                     $   894.900

   BY-PRODUCT CREDITS                               N.A.

   CAPITAL CHARGES

        G & A, taxes & insurance
          (4% of  total turnkey costs)             $ 1,670,700

        Capital  recovery factor
          (10,14  % of total turnkey costs)          4.235.300

        Interest on working capital
          (10% of working capital)                    129.000

             Total capital charges               $ 6.035.000

   TOTAL ANNUALIZED COSTS                        $12.Q9Qr2QQ

   a Included with replacement parts.
   N.A. - Not applicable.


                            A-105

-------
  TABLE A-71.   ESTIMATED CAPITAL COSTS OF A FIELD-ERECTED,
  WATER-TUBE,  PULVERIZED-COAL-FIRED BOILER FIRING EASTERN
    MEDIUM-SULFUR COAL WITH A THERMAL INPUT OF 205.1 MW
          (700 x 106 Btu/hr; 900 psig/750°F design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30. 1978
(FOR COSTS INDEXING)
     EQUIPMENT COST

      Boiler (with fans & ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler (including founda-
       tions and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. - Not applicable.
                          $ 5,762,000
                            1.250,000
                              610.800
                            1,443,000
                              296.000
                          incl.  w/coal handling
                               85.000
                          incl.  w/boiler
                              195.000
                               35P000
                               90rQQQ
                          	4fOOO
                               53.000
                            1,552,OOP
                              728.000
                          incl.  w/coal hand1i ng
                              N.A.	

                          S12.1Q3.800
                          S 3.201.000
                          incl.  w/equipment
                              160.000
                          inr;l.  w/bolle>r
                          incl.  w/boiler
                          incl.  w/coal handling
                               19fOOQ
                          incl.  w/boiler
                          	25fQQQ
                          	16rQQO
                               28rOQO
                          	2 .000
                              970.QQQ
                              485.QQQ
                          inr;l.  w/coal h^ndl i ng
                            A-106

-------
 TABLE A-71.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports                      	631,000
     Ductwork  (not incl. w/boiler)                    N.A.
     Piping                                            233,000
     Insulation                                        1*4,000
     Painting                                      	28,000
     Electrical                                        650,000
     Buildings                                       1,213,000

     Total installation cost                       $ 7,845,000

TOTAL DIRECT COSTS
  (equipment +  installation)                        $19.948.800

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of  direct costs)                        $ 1,994.900
     Construction and  field expense
       (10% of  direct costs)                          1.994.900
     Construction fees
       (10% of  direct costs)                          1.994.900
     Start-up  (2% of direct costs)                     399,000
     Performance tests (minimum  $2000)    .         	25,000

TOTAL INDIRECT COSTS                               $ 6.408.700

Contingencies
  (20% of direct and indirect  costs)                S 5.271.5QQ

Total Turnkey  Costs
   (direct+indirect+contingencies)                   31.629.000

Land                                               	2.000

Working capital  (25% of total direct
 operating costs)                                    lf671r4QQ

GRAND TOTAL                                        g
  (turnkey+land+working capital)                    $.*.*,302,4uu


aQuote from Babcock &  Wilcox,  Inc., August 17, 1978.

N.A. - Not applicable.
                            A-107

-------
TABLE A-72.  ESTIMATED ANNUALIZED COSTS OF A FIELD-ERECTED,
  WATER-TUBE, PULVERIZED-COAL-FIRED BOILER FIRING EASTERN
    MEDIUM-SULFURfiCOAL WITH A THERMAL INPUT OF 205.1 MW
        (700 x 10° Btu/hr,- 900 psig/750°F design)
DIRECT COST

     Direct labor                             $ 1,000,300
     Supervision                                  205,400
     Maintenance labor                            512,600
     Maintenance materials                    	S	
     Replacement parts                            412,300
     Electricity                                  876,800
     Steam                                       N.A.
     Cooling water                               N.A.
     Process water                            	10,600
     Fuel                                       3,495,200
     Bottom ash disposal                          147,20~0
     Chemicals                                     25,000

     Total direct cost                        $ 6,685,400

OVERHEAD

     Payroll  (30% of direct labor             $   300.100

     Plant  (26% of labor, parts & maint.)         554.000

     Total overhead costs                      $   854.100

BY-PRODUCT CREDITS                                N.A.

CAPITAL CHARGES

     G & A, taxes & insurance
       (4% of total turnkey costs)             $ 1,265,200

     Capital recovery factor
       ( 10.14% of total turnkey costs)          3.207.200

     Interest on working capital
       (10% of working capital)                    167,100

          Total capital charges               $ 4,639,500

TOTAL ANNUALIZED COSTS                        $12.179rQQQ

a Included with replacement parts.
N.A. - Not applicable.



                         A-108

-------
                APPENDIX B

DETAILED CAPITAL AND ANNUALIZED COST TABLES
  FOR PACKAGE, FIRE-TUBE BOILERS FIRED BY
     RESIDUAL OIL, DISTILLATE OIL, AND
                NATURAL GAS

-------
 TABLE B-l.  ESTIMATED CAPITAL COSTS OF A PACKAGE, FIRE-TUBE
  BOILER FIRING RESIDUAL OIL WITH A THERMAL INPUT OF  1.5 MW
     (5 x 106 Btu/h; 125 hp; 150 psig/sat. temp, design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS INDEXING)
     EQUIPMENT COSTa

      Boiler  (with fans & ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler  feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler  (including founda-
       tions  and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler  feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. - Not applicable.
                              19,100
                               2,000
                           Incl.  w/boiler

                          	N.A.	
                          	N.A.	
                           Incl.  w/condensate
                          	N.A.	
                               3.500
                               4,000
                               1,200
                           Incl. w/boiler
                           	N.A.	
                                N.A.	
                                N.A.	
                                N.A.	
                              13.000	

                              42,800
                               3.OOP
                               1.000
                           Incl.  w/ boiler
                           	MT A.	
                           	N.A.	
                           	N.A.	
                           	N.A.	
                           	N.A.	
                           	800	
                           	800	
                               1.000	
                           	200	
                                N.A.
                                N.A.
                                N.A.
                               3.OOP
                              B-l

-------
 TABLE  B-l.   (continued)
 INSTALLATION COSTS, DIRECT  (cont.)

      Foundations and supports                         2,500
      Ductwork  (not incl. w/boiler)                 	N.A.
      Piping                                          12,000
      Insulation                                       8,000
      Painting                                         2,500
      Electrical                                      10,000
      Buildings                                       35,000

      Total installation cost                      $  79,800

 TOTAL DIRECT COSTS
   (equipment + installation)                       $ 122,600

 INSTALLATION COSTS, INDIRECT

      Engineering
       (10% of direct costs)                       $  12,300
      Construction and field expense
       (10% of direct costs)                          12,300
      Construction fees
       (10% of direct costs)                          12,300
      Start-up  (2% of direct costs)                    2,500
      Performance tests  (minimum $2000)   .             2,000

 TOTAL INDIRECT COSTS                              $  41,400

 Contingencies
   (20% of direct and indirect costs)               $  32,800

 Total Turnkey Costs
    (direct+indirect+contingencies)                   196,800

 Land                                                  2.000

 Working capital (25% of total direct
  operating costs)                                     44.900

 GRAND TOTAL
   (turnkey*land+working capital)                   s 243,700


a Quote from Cleaver-Brooks, May 11, 1978.

  N.A. - Not applicable.

                               B-2

-------
TABLE B-2.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE, FIRE-TUBE
   BOILER FIRING RESIDUAL OIL WITH A THERMAL INPUT OF 1.5 MW
      (5 x 106 Btu/h; 125 hp; 150 psig/sat. temp, design)
   DIRECT  COST
         Direct labor                             S 105.300
         Supervision                             	Q_
         Maintenance labor                           16*000
         Maintenance materials                    	a
         Replacement parts                            8/000
         Electricity                                 6,000
         Steam                                        N.A.
         Cooling water                            	N.A.
         Process water                            	100
         Fuel                                       43,600
         Bottom ash disposal                      	N.A.
         Chemicals                                	700

         Total direct cost                        $ 179,700

    OVERHEAD

         Payroll (30% of direct labor )            $  31,600

         Plant (26% of labor,  parts & maint.)        33,600

         Total overhead costs                     $  65.200

    BY-PRODUCT CREDITS                                N.A.

    CAPITAL CHARGES

         G & A, taxes & insurance
          (4% of total turnkey costs)            $   7,900

         Capital recovery factor
          (11.75 % of total turnkey costs)           23,100

         Interest on working capital
          (10% of working capital)                    4.500

              Total capital charges              $  35,500

    TOTAL ANNUALIZED COSTS                        $ 280.400

    a Included with replacement parts.
    N.A.  - Not applicable.
                               B-3

-------
 TABLE B-3.   ESTIMATED  CAPITAL COSTS  OF A PACKAGE,  FIRE-TUBE
  BOILER FIRING  RESIDUAL  OIL WITH A THERMAL INPUT OF 4.4 MW
    (15 x  106 Btu/h;  300  hp; 150 psig/sat.  temp,  design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30,  1978
(FOR COSTS INDEXING)
     EQUIPMENT COST a

      Boiler (with fans & ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler (including founda-
       tions and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. - Not applicable.
                          $  36,100
                             2,700
                          Incl. w/boiler
                              N.A.
                              N.A.
                              N.A.
                             4,000
                              N.A.
                             6,100
                             5,000
                             1>400
                          Incl. w/boiler
                              N.A.
                              N.A.
                              N.A.
                              N.A.
                            22,000
                            77,300
                             5,000
                             1,500
                          Incl. w/boiler
                              N.A.	
                              N.A.
                              N.A.
                              1,500
                              N.A.
                             1,200
                             1,000
                             1,500
                               400
                              N.A.
                              N.A.
                              N.A.
                             4,000
                             B-4

-------
 TABLE B-3.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports                         3/500
     Ductwork  (not incl. w/boiler)                     N.A.
     Piping                                          20,000
     Insulation                                      10,000
     Painting                                         3,000"
     Electrical                                      15,000'
     Buildings           .                            50,000"

     Total installation cost                      $ 117,600

TOTAL DIRECT COSTS
  (equipment + installation)                       $ 194,900

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)                       $  19*500
     Construction and field expense
       (10% of direct costs)                          19,500
     Construction fees
       (10% of direct costs)                          19,500
     Start-up  (2% of direct costs)                    3,900
     Performance tests  (minimum  $2000)    .            2,000

TOTAL INDIRECT COSTS                              $  64,400

Contingencies
  (20% of direct and indirect costs)               $  51,900

Total Turnkey Costs
   (direct+indirect+contingencies)                   311,200

Land                                                  2,000

Working capital  (25% of total  direct
  operating costs)                                    91,000

GRAND TOTAL
  (turnkey+land+working capital)                   s 404,20_p_


a Quote from Cleaver-Brooks, May 11, 1978.

N.A. - Not applicable.
                              B-5

-------
TABLE B-4.  ESTIMATED ANNUALIZED COSTS OP A PACKAGE, FIRE-TUBE
   BOILER FIRING RESIDUAL OIL WITH A THERMAL INPUT OF 4.4 MW
      (15 x 106 Btu/h; 300 hp; 150 psig/sat. temp design)
    DIRECT COST

         Direct labor                            $ 105,300
         Supervision                                68,500
         Maintenance labor                          32,000
         Maintenance materials
         Replacement parts                          15,000
         Electricity                                11,600
         Steam                                        N.A.
         Cooling water
         Process water                            _ 2°0
         Fuel                                      130,700
         Bottom ash disposal                          N.A.
         Chemicals                                     800

         Total direct cost                       $ 364,100

    OVERHEAD

         Payroll (30% of direct labor)           $  31,600

         Plant (26% of labor, parts & maint.)       57,400

         Total overhead costs                    $  89,000

    BY-PRODUCT CREDITS                                N.A.

    CAPITAL CHARGES

         G & A, taxes & insurance
          (4% of total turnkey costs)             $ 12.400

         Capital recovery factor
          (11.75 % of total turnkey costs)          36.600

         Interest on working capital
          (10% of working capital)                  9,100

              Total capital charges              $ 58.100

    TOTAL ANNUALIZED COSTS                       S511.200

    a Included with replacement parts.
    N.A. - Not applicable.
                               B-6

-------
 TABLE B-5.   ESTIMATED  CAPITAL  COSTS  OF A  PACKAGE,  FIRE-TUBE
  BOILER FIRING  RESIDUAL  OIL WITH A THERMAL  INPUT  OF  8.5  MW
     (29  x 106 Btu/h;  700  hp; 150 psig/sat. temp, design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS INDEXING)
     EQUIPMENT COST

      Boiler  (with fans & ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler  feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler  (including founda-
       tions  and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler  feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. - Not applicable.
                          S  51,000
                              4,000
                           Incl.  w/boiler
                               N.A.	
                               N.A.
                               N.A.
                              5,000
                               N.A.
                             13,000
                              6.OOP
                              2.000
                              1,400
                               N.A.
                               N.A.
                               N.A.
                               N.A.
                             32,000
                          $ 114.400
                              9.000
                              2,000
                           Incl. w/bo i 1 er
                               N.A.
                               N.A.
                              2.500
                               N.A.
                              3rOQO
                              l.QQQ
                              2.000
                              1.500
                               N.A.
                               N.A.
                               N.A.
                              8. OOP
                             B-7

-------
TABLE B-5.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports                         15.000
     Ductwork  (not incl. w/boiler)                 	N.A.
     Piping                                           25,000
     Insulation                                       20,000
     Painting                                          4,000"
     Electrical                                       20,000
     Buildings                                        70,000"

     Total installation cost                       $ 183,000

TOTAL DIRECT COSTS
  (equipment + installation)                        $ 297,400

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)                        $   29,700
     Construction and field expense
       (10% of direct costs)                           29,700
     Construction fees
       (10% of direct costs)                        	29,700
     Start-up  (2% of direct costs)                    5.900
     Performance tests  (minimum $2000)   .            2,000

TOTAL INDIRECT COSTS                               $   97,000

Contingencies
  (20% of direct and indirect costs)                $   78,900

Total Turnkey Costs
   (direct+indirect+contingencies)                   473,300

Land                                                  2,000

Working capital (25% of total direct
 operating costs)                                    127.200

GRAND TOTAL
  (turnkey+land+working capital)                   s 602,50_0_


  Quote from Cleaver-Brooks,  May 11,  1978.
N.A. -  Not applicable.


                             B-8

-------
TABLE B-6.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE, FIRE-TUBE
   BOILER FIRING RESIDUAL OIL WITH A THERMAL INPUT OF 8.5 MW
     (29 x 106 Btu/h; 700 hp; 150 psig/sat. temp, design)
    DIRECT COST

         Direct labor                            $ 105.300
         Supervision                                68,500
         Maintenance labor                          32/000
         Maintenance materials                    	a
         Replacement parts                          25,000
         Electricity                                24,000
         Steam                                        N.A.
         Cooling water                                N.A.
         Process water                            	400
         Fuel                                      252,600
         Bottom ash disposal                      	N.A.
         Chemicals                                   1.000

         Total direct cost                        $ 508,800

    OVERHEAD

         Payroll  (30% of direct labor)            $  31,600

         Plant  (26% of labor, parts & roaint.)       60,000

         Total overhead costs                     $  91.600

    BY-PRODUCT CREDITS                                N.A.

    CAPITAL CHARGES

         G & A, taxes & insurance
           (4% of  total turnkey costs)             $  18r9QQ

         Capital  recovery factor
           (11.75  % of total turnkey costs)          55r6QQ

         Interest on working capital
           (10% of working capital)                  12.700

              Total capital charges               $  87.200

    TOTAL ANNUALIZED COSTS                        S  687,600

    a  Included with replacement parts.
    N.A. - Not applicable.
                               B-9

-------
 TABLE B-7.  ESTIMATED CAPITAL COSTS OF A PACKAGE, FIRE-TUBE
             BOILER FIRING DISTILLATE OIL WITH A
            g      THERMAL INPUT OF 1.5 MW
     (5 x 10  Btu/h; 125 hp; 150 psig/sat. temp, design)

CAPITAL COSTS
DATE OF ESTIMATE   June 30. 1978 _ (FOR COSTS INDEXING)


     EQUIPMENT COST a

      Boiler  (with fans & ducts)             $  19.100 _
      Stack                                      2.000 _
      Instrumentation                         Incl.  w/boiler
      Pulverizers                            _ N.A. _
      Feeders                                _ N.A. _
      Crushers                               _ N.A. _
      Deaerators                              Incl.  w/condensate
      Heaters                                     N.A. _
      Boiler feed pumps                          3f500 _
      Condensate systems                         4 r QOQ _
      Water treating system                      1/200 _
      Chemical feed                          Incl. w/boiler
      Compressed air system                       N.A. _
      Coal handling system                   _ MLA* _
      Ash disposal system                    _ N.A. _
      Thawing equipment                      _ N.A. _
      Fuel-oil system                           10.000 _

     Total Equipment Cost                    $   39,800 _

     INSTALLATION COST, DIRECT

      Boiler  (including founda
       tions and steel)
      Stack                                      inno
      Instrumentation
      Pulverizers
      Feeders                                _ N.A.
      Crushers                               _ N.A.
      Deaerators                             _ N.A.
      Heaters                                    N.A.
      Boiler feed pumps                      _ 800
      Condensate system                      _ 800
      Water treating system                      1.000
      Chemical feed                          _ 200
      Coal handling system                   _ N.A.
      Ash disposal system                    _ N.A.
      Thawing equipment                      _ N.A.
      Fuel-oil system                            2.500

N.A. - Not applicable.


                             B-10

-------
TABLE B-7.  (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations  and  supports                         2,500
     Ductwork  (not  incl. w/boiler)                 	N.A.
     Piping                                          12,000
     Insulation                                       8/000
     Painting                                         ^500"
     Electrical                                      10,000
     Buildings                                       3^>
      Total  installation  cost                     $  79,300

TOTAL DIRECT  COSTS
  (equipment + installation)                       $ 119,100

INSTALLATION  COSTS,  INDIRECT

      Engineering
       (10%  of direct costs)                       $  11,900
      Construction and field  expense
       (10%  of direct costs)                          11,900
      Construction fees
       (10%  of direct costs)                          11.900
      Start-up (2% of direct  costs)                     2,400
      Performance tests (minimum $2000)    .             2,000

TOTAL INDIRECT COSTS                             S  40.100

Contingencies
  (20% of direct and  indirect costs)              $  31.800

Total Turnkey Costs
   (direct+indirect+contingencies)                   191.000

Land                                                  2.000

Working capital (25% of  total direct
  operating costs)                                    48 .800

GRAND TOTAL
  (turnkey+land+working capital)                  $  241.80.fl.


a Quote  from Cleaver-Brooks, May 11, 1978.

N.A.  - Not applicable.


                               B-ll

-------
TABLE B-8.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE, FIRE-TUBE
  BOILER FIRING DISTILLATE OIL WITH A THERMAL INPUT OF 1.5 MW
       (5 x 106 Btu/h; 125 hp; 150 psig/sat. temp, design)
    DIRECT COST

         Direct labor                            $ 105,300
         Supervision
         Maintenance labor                          16,000
         Maintenance materials
         Replacement parts                           8,000
         Electricity                                 6,000
         Steam                                        N.A.
         Cooling water                                N.A.
         Process water                            	100
         Fuel                                       59,100
         Bottom ash disposal                          N.A.
         Chemicals                                     700

         Total direct cost                       $ 195,200

    OVERHEAD

         Payroll (30% of direct labor )           $  31,600

         Plant (26% of labor,  parts & maint.)        33,600

         Total overhead costs                     $  65.200

    BY-PRODUCT CREDITS                                N.A.

    CAPITAL CHARGES

         G & A,  taxes & insurance
          (4% of total turnkey costs)             S  7,600

         Capital recovery factor
          (11.75 % of total  turnkey costs)          22,500

         Interest on working capital
          (10% of working capital)                   4,900

              Total capital  charges              $ 34,900

    TOTAL ANNUALIZED COSTS                       $ 295.300

    a Included with replacement parts.
    N.A.  - Not applicable.
                               B-12

-------
 TABLE B-9.  ESTIMATED CAPITAL COSTS OF A PACKAGE FIRE-TUBE
 BOILER  FIRING DISTILLATE OIL WITH A THERMAL INPUT  OF  4.4 MW
     (15 x 106 Btu/h; 300 hp? 150 psig/sat.  temp, design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30,  1978
(FOR COSTS  INDEXING)
     EQUIPMENT COST3

      Boiler  (with fans  and duct)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler feed pumps
      Condensate systems.
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COSTS, DIRECT

      Boiler  (including  founda-
       tions  and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler  feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

 N,A. - Not applicable.
                    S 36.100
                        2.700
                   Incl. w/boiler
                      N.A.	
                      N.A.	
                      N.A.	
                        4,000
                      N.A.	
                        6.100
                  	5.000
                        1.400
                   Incl. w/boiler
                      N.A.	
                      N.A.	
                      N.A.	
                      N.A.	
                      16,000

                    $ 71,300
                    $   5.000

                        1,500
                   Incl. w/boiler
                      N.A.	
                      N.A.	
                      N.A.	
                        1,500
                      N.A.	
                        1,200
                        1,000
                        1,500
                          400
                      N.A.	
                      N.A.	
                      N.A.	
                        3,000
                              B-13

-------
TABLE B-9. (continued)
     INSTALLATION COSTS,  DIRECT (cont.)

      Foundations and supports               	3,500
      Duct work  (not incl.  w/boiler)          	N.A.
      Piping                                      20,000
      Insulation                                 10.000
      Painting                                     3,000
      Electrical                                 15.000
      Buildings                                   50,000

     Total  Installation  Costs                  $ 116.600

     TOTAL  DIRECT  COSTS
      (Equipment + Installation)               $ 187.900

     INSTALLATION  COSTS,  INDIRECT

      Engineering
       (10% of direct  costs)                   $  18.800
      Construction and field expense
       (10% of direct  costs)                      18.800
      Construction fees
       (10% of direct  costs)                      18.800
      Startup  (2%  of direct costs)            	3,800
      Performance  tests  (minimum $2000)       	2,000

     TOTAL  INDIRECT COSTS                      $  62.200

     Contingencies
      (20%  of direct and  indirect costs)       S  50.000

     Total  turnkey costs
      (Direct +  Indirect  + Contingencies)        300,100

     Land                                     	2,000

     Working capital  (25% of total direct
      operating  costs)                           102,700

     GRAND  TOTAL
      (Turnkey + Land  + Working Capital)       $ 404^800
    a Quote from Cleaver-Brooks, May 11, 1978.
    N.A. - Not applicable.
                                B-14

-------
 TABLE B-10. ESTIMATED ANNUALIZED COSTS OF A PACKAGE, FIRE-TUBE
   BOILER FIRING DISTILLATE OIL WITH A THERMAL INPUT 'OF 4 . 4 MW
       (15 x 106 Btu/h; 300 hp; 150 psig/sat. temp, design)

 DIRECT COST

      Direct labor                                   $  105,300
      Supervision                                        68,500
      Maintenance  labor                                 32.000
      Maintenance materials      '                   _ a
      Replacement  parts                                 15,OOU
      Electricity
      Steam                                        _ N.A.
      Cooling water                                _ N.A.
      Process vater                                _ 200
      Fuel                                              177,400
      Bottom ash disposal                                N.A.'
      Chemicals                                            800

      Total direct cost                            $   410.800

 OVERHEAD

      Payroll (30% of direct labor)                 $    31,600

      Plant (26% of labor,  parts & maint.)               57,400

      Total overhead costs                          $    89,000
                   /
 BYPRODUCT  CREDITS                                  _ N.A.

 CAPITAL  CHARGES

      G t A,  taxes & insurance
       (4%  of total turnkey costs)                   $    12,000

      Capital recovery factor
       (11.75*  of  total turnkey  costs)                   35.300

      Interest  on  working capital
       (10% of  working capital)                          10,300

           Total capital charges                    $    57,600

TOTAL ANNUALIZED  COSTS                              $   557,400


  Included with replacement parts.
N.A. - Not applicable.
                                  B-15

-------
TABLE B-ll.  ESTIMATED CAPITAL COSTS OF A PACKAGE, FIRE-TUBE
 BOILER FIRING DISTILLATE OIL WITH A THERMAL INPUT OF 8.5 MW
    (29 x 106 Btu/h; 700 hp; 150 psig/sat. temp, design)
  CAPITAL COSTS
  DATE OF ESTIMATE
June 30. 1978
(FOR COSTS INDEXING)
       EQUIPMENT COSTa

        Boiler  (with fans  &  ducts)
        Stack
        Instrumentation
        Pulverizers
        Feeders
        Crushers
        Deaerators
        Heaters
        Boiler feed  pumps
        Condensate systems
        Water treating system
        Chemical feed
        Compressed air system
        Coal  handling system
        Ash disposal system
        Thawing  equipment
        Fuel-oil system

       Total  Equipment Cost

       INSTALLATION  COST,  DIRECT

        Boiler  (including  founda-
         tions and steel)
        Stack
        Instrumentation
        Pulverizers
        Feeders
        Crushers
        Deaerators
        Heaters
        Boiler feed  pumps
        Condensate system
        Water treating system
        Chemical feed
        Coal  handling system
        Ash disposal system
        Thawing  equipment
        Fuel-oil system

 N.A.  - Not  applicable.
                          $  51,000
                             4,000
                          Incl. w/boiler
                              N.A.	
                              N.A.
                              N.A.
                             5,000
                              N.A.
                            13,000
                             6,000
                             2,000
                             1,400
                              N.A.
                              N.A.
                              N.A.
                              N.A.
                            25,000
                         $ 107,400
                             9,000
                             2,000
                          Incl. w/boiler
                              N.A.	
                              N.A.	
                              N.A.	
                             2.500	
                              N.A.	
                             3.000	
                             1.000	
                             2.000	
                             1.500	
                              N.A.	
                              N.A.	
                              N.A.	
                             6.000 	
                              B-16

-------
TABLE B-ll.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and  supports                       15/000
     Ductwork  (not  incl. w/boiler)                    N.A.
     Piping                                         25,000
     Insulation                                     20,000
     Painting                                        4,000
     Electrical                                     20,000
     Buildings                                      70,000

     Total  installation  cost                      S181fOOO

TOTAL  DIRECT  COSTS
  (equipment + installation)                       $288,400

INSTALLATION  COSTS,  INDIRECT

     Engineering
       (10%  of direct costs)                       $  28,800
     Construction and field expense
       (10%  of direct costs)                          28,800
     Construction fees
       (10%  of direct costs)                          28,800
     Start-up (2% of direct costs)                   5.800
     Performance tests (minimum $2000)    .           2.000

TOTAL  INDIRECT  COSTS                             $	94,200

Contingencies
  (20%  of direct and  indirect  costs)               $  76,500

Total  Turnkey Costs
   (direct+indirect+contingencies)                   459,100

Land                                                 2fnnn

Working capital (25% of  total direct
  operating  costs)                                  iAQ,pnn

GRAND  TOTAL
  (turnkey+land+working capital)                   $61Q.9QQ_
a Quote from Cleaver-Brooks, May 11, 1978

N.A. - Not applicable.


                               B-17

-------
TABLE B-12.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE, FIRE-TUBE
  BOILER FIRING DISTILLATE OIL WITH A THERMAL INPUT OF 8.5 MW
     (29 x 106 Btu/h; 700 hp; 150 psig/sat. temp, design)
    DIRECT COST

         Direct labor                            * 105'300
         Supervision                                68,500
         Maintenance labor                          32,000
         Maintenance materials
         Replacement parts                          25,000
         Electricity                                24,000
         Steam                                        N.A.
         Cooling water                            	N.A.
         Process water                            	400
         Fuel                                      343,000
         Bottom ash disposal                      	N.A.
         Chemicals                                   1.000

         Total direct cost                       $ 599.200

    OVERHEAD

         Payroll (30% of direct labor)            $  31,600

         Plant (26% of labor,  parts &  maint.)        60.000

         Total overhead costs                     S  91.600

    BY-PRODUCT CREDITS                                N.A.

    CAPITAL CHARGES

         G & A,  taxes & insurance
          (4% of total turnkey costs)             S  18,400

         Capital recovery factor
          (11.75 % of total  turnkey costs)           53,900

         Interest on working capital
          (10% of working capital)                   15.000

              Total capital  charges              S  87,300

    TOTAL ANNUALIZED COSTS                       <; 778,100
                     -»
    a Included with replacement parts.
    N.A.  - Not applicable.
                               B-18
S

-------
TABLE B-13.  ESTIMATED CAPITAL COSTS OF A PACKAGE, FIRE-TUBE
  BOILER FIRING NATURAL GAS WITH A THERMAL INPUT OF 1.5 MW
     (5 x 106 Btu/h; 125 hp; 150 psig/sat. temp, design)
 CAPITAL COSTS
 DATE OF ESTIMATE
June 30. 1978
(FOR COSTS  INDEXING)
      EQUIPMENT COST3

       Boiler (with fans & ducts)
       Stack
       Instrumentation
       Pulverizers
       Feeders
       Crushers
       Deaerators
       Heaters
       Boiler feed pumps
       Condensate systems
       Water treating system
       Chemical feed
       Compressed air system
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel-oil system

      Total Equipment Cost

      INSTALLATION COST, DIRECT

       Boiler  (including founda-
        tions and steel)
       Stack
       Instrumentation
       Pulverizers
       Feeders
       Crushers
       Deaerators
       Heaters
       Boiler feed pumps
       Condensate system
       Water treating system
       Chemical feed
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel-oil system

 N.A. - Not applicable.
                             19.100
                              2.000
                           Incl.  w/boiler
                          	N.A.	
                               N.A.	
                               N.A.	
                           Incl.  w/condensate
                               N.A.	
                              3.500	
                          	4rQQQ	
                          	I200	
                          	. w/boiler
                               N.A.	
                               N.A.	
                               N.A.	
                          	N.A.	
                             10,000	

                          5   39f800	
                              1,000
                           Incl.  w/boiler
                               N.A.	
                               N.A.
                               N.A.
                               N.A.
                               N.A.
                                800
                                800
                              1,000
                                200
                               N.A.
                               N.A.
                               N.A.
                              2,500
                              B-19

-------
  TABLE B-13.   (continued)
 INSTALLATION COSTS, DIRECT  (cont.)

      Foundations and supports                         2.500
      Ductwork  (not incl. w/boiler)                     N.A.
      Piping                                          12,000
      Insulation                                       8,000
      Painting                                         2,500
      Electrical                                      10,000
      Buildings                                       35,000

      Total installation cost                      $   79r30Q

 TOTAL DIRECT COSTS
   (equipment + installation)                       $  119.100

 INSTALLATION COSTS, INDIRECT

      Engineering
        (10% of direct costs)                       $   11.900
      Construction and field expense
        (10% of direct costs)                          11.900
      Construction fees
        (10% of direct costs)                          Ilr900
      Start-up  (2% of direct costs)                    2,400
      Performance tests  (minimum $2000)   .            2.000

 TOTAL INDIRECT COSTS                              $   40.100

 Contingencies
   (20% of direct and indirect costs)               $   31f800

 Total Turnkey Costs
    (direct+indirect+contingencies)                   191fQQQ

 Land                                                  2 .POD

 Working capital  (25% of total direct
  operating costs)                                   41rfinn

 GRAND TOTAL
   (turnkey+land+working capital)                   $  236.600


  Quote from Cleaver-Brooks,  May 11, 1978.

N.A. - Not applicable.

                               B-20

-------
TABLE B-14.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE, FIRE-TUBE
   BOILER FIRING NATURAL GAS WITH A THERMAL INPUT OF 1.5 MW
      (5 x 106 Btu/h; 125 hp; 150 psig/sat. temp, design)
    DIRECT COST

         Direct labor                            S 105.300
         Supervision                              	0_
         Maintenance labor                          16/000
         Maintenance materials                    	a
         Replacement parts                           8,OOP
         Electricity                                 6,000
         Steam                                        N.A.
         Cooling water                                N.A.
         Process water                            	100
         Fuel                                       38/400
         Bottom ash disposal                          N.A.
         Chemicals                                     700

         Total direct cost                       $ 174,500

    OVERHEAD

         Payroll  (30% of direct labor)           $  31,600

         Plant  (26% of labor, parts  & maint.)       33,600

         Total overhead costs                    $  65.200

    BY-PRODUCT CREDITS                                N.A.

    CAPITAL CHARGES

         G & A, taxes & insurance
           (4% of  total turnkey costs)            S   7.600

         Capital  recovery factor
           ( 11.75% of total turnkey  costs)          3?,4nn

         Interest on working capital
           (10% of working capital)                   4,400

              Total capital charges              $  34.400

    TOTAL ANNUALIZED COSTS                       $ 274,100

    a  Included with replacement parts.
    N.A. - Not applicable.
                                B-21

-------
TABLE B-15. ESTIMATED CAPITAL COSTS  OF A PACKAGE, FIRE-TUBE
  BOILER FIRING NATURAL GAS WITH A THERMAL INPUT OF 4.4 MW
     (15 x 10  Btu/h;  300  hp;  150  psig/sat. temp, design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30,  1978
(FOR COSTS INDEXING)
     EQUIPMENT COST3

      Boiler (with fans and ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COSTS, DIRECT

      Boiler (including founda-
       tions and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerator
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

 N.A. - Not applicable.
                    $    36.100
                  	2.700
                   Incl. w/boiler
                  	N.A.
                  	N.A.
                  	N.A.
                  	4.000
                  	N.A.
                  	6.100
                  	5.000
                  	1.400
                   Inel. w/boiler
                  	N.A.
                  	N.A.
                  	N.A.
                  	N.A.
                  	16.000

                    $    71,300
                    $     5,000

                          1,500
                   Incl.  w/boiler~
                  	N.A.
                  	N.A.
                  	N.A.
                          1,500
                  	N.A.
                  	1,200
                  	1.000
                  	1,500
                  	    400
                  	N.A.
                  	N.A.
                  	N.A.
                  	3^000
                             B-22

-------
TABLE 'B-15.(continued)
    INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and  supports                	3,500
     Duct work  (not incl. w/boiler)          	N.A.
     Piping                                  	20.000
     Insulation                              	iof OOP
     Painting                                	3,000
     Electrical                              	15rQQO
     Buildings            •                   	50, OOP

    Total Installation Costs                  $   116.600

    TOTAL DIRECT COSTS
      (Equipment +  Installation)               $   187,900

    INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct  costs)                   $    18,800
     Construction  and field expense
       (10% of direct  costs)                  	18,800
     Construction  fees
       (10% of direct  costs)                  	IB,BOO
     Startup (2% of direct costs)            	3 f800
     Performance tests  (minimum $2000)       	2.000

    TOTAL  INDIRECT COSTS                      $    62,200

    Contingencies
      (20% of direct and indirect  costs)       $    50,000

    Total turnkey  costs
      (Direct +  Indirect + Contingencies)     	300,100

    Land                                    	2,000

    Working  capital  (25%  of total direct
     operating  costs)                        	87,200

    GRAND TOTAL
      (Turnkey + Land  + Working  Capital)       $   389,300
    a Quote  from Cleaver-Brooks, May  11, 1978

    N.A.  - Not applicable.



                                 B-23

-------
  TABLE B-16. ESTIMATED ANNUALIZED COSTS OF A PACKAGE,FIRE-TUBE
     BOILER FIRING NATURAL GAS WITH A THERMAL INPUT OF 4.4 MW
        (15 x 106 Btu/h; 300 hp; 150 psig/sat. temp, design)

 DIRECT COST

     Direct  labor                                  $ 105.300
     Supervision                                      68,500
     Maintenance labor                               32,000
     Maintenance materials
      Replacement  parts                                j-5,9?0
      Electricity                                      11,600
      Steam                                             N.A.
      Cooling water
      Process water
      Fuel
      Bottom ash disposal
     Chemicals                                         _ son

     Total direct cost                             $ 348.7QQ

OVERHEAD

     Payroll  (30% of direct  labor)                 $  31,600

     Plant  (26% of labor, parts  & maint.)             57,400

     Total overhead costs                          $  89,000
                  /
BYPRODUCT CREDITS                                      N.A.

CAPITAL CHARGES

     G i A, taxes t insurance
       (4% of total turnkey costs)                  ?  12,000

     Capital recovery factor
       (11.75* of total turnkey costs)                 35,300

     Interest on working capital
       (10% of working capital)                         8'700

          Total capital charges                    $  56,000

TOTAL ANNUALIZED COSTS                             $ 493,700


  Included with replacement parts.

N.A. - Not applicable.


                                  B-24

-------
TABLE B-17.  ESTIMATED CAPITAL COSTS OF A PACKAGE, FIRE-TUBE
  BOILER FIRING NATURAL GAS WITH A THERMAL INPUT OF 8.5 MW
    (29 x 106 Btu/h; 700 hp; 150 psig/sat. temp, design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
     EQUIPMENT COST

      Boiler  (with fans  & ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler  feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

      Total Equipment Cost

      INSTALLATION COST,  DIRECT

      Boiler  (including  founda-
        tions  and  steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler  feed pumps
      Condensate  system
      Water treating  system
      Chemical  feed
      Coal handling  system
      Ash disposal  system
      Thawing equipment
      Fuel-oil  system

 N.A.  -  Not applicable.
                            51.000
                             4.000
                          Incl. w/hoiler
                              M a
                              N.A.
                              N.A.
                             5.000
                              N.A.
                            13.000
                             6.000
                             2,000
                             1.400
                              N.A.
                              N.A.
                              N.A.
                              N.A.
                            25.000
                         $ 107,400
                             9,000
                             2,000
                          Incl. w/boiler
                              N.A.	
                              N.A.	
                              N.A.	
                             2,500	
                              N.A.	
                             3,000	
                             1,000	
                             2,000	
                             1,500	
                              N.A.	
                              N.A.	
                              N.A.	
                             6.000	
                               B-25

-------
 TABLE B-17.  (continued)
INSTALLATION COSTS, DIRECT (cont. )
Foundations and supports
Ductwork (not incl. w/boiler)
Piping
Insulation
Painting
Electrical
Buildings
15,000
N.A.
25rOOO
20,000
4,000
20,000
70.000
      Total installation cost                      $  181fQQO

 TOTAL DIRECT COSTS
   (equipment + installation)                       $  288,400

 INSTALLATION COSTS, INDIRECT

      Engineering
       (10% of direct costs)                       $   28.800
      Construction and field expense
       (10% of direct costs)                           28.800
      Construction fees
       (10% of direct costs)                           28.800
      Start-up (2% of direct costs)                     5,800
      Performance tests  (minimum $2000)   .              2,000

 TOTAL INDIRECT COSTS                              $   94.200

 Contingencies
   (20% of direct and indirect costs)               $   76.500

 Total Turnkey Costs
   (direct+indirect+contingencies)                    459.100

 Land                                                   2,000

 Working capital (25% of total direct
  operating costs)                                     119,800

 GRAND TOTAL
   (turnkey+land+worki-ng capital)                   $ 580,900	 •
-------
TABLE B-18.  ESTIMATED ANNUALIZED COSTS OF A PACKAGE, FIRE-TUBE
   BOILER FIRING NATURAL GAS WITH A THERMAL INPUT OF 8.5 MW
     (29 x 106 Btu/h; 700 hp; 150 psig/sat. temp, design)
    DIRECT COST
         Direct labor                            $ 105,300
         Supervision                                68,500
         Maintenance labor                          32,000
         Maintenance materials
    a Included with replacement parts.
    N.A. - Not applicable.
                               B-27
         Replacement parts                          25,000
         Electricity                                24,000
         Steam                                        N.A.
         Cooling water
         Process water                            _ 400
         Fuel                                      222,900
         Bottom ash disposal                      _ N.A.
         Chemicals                                   1/000

         Total direct cost                       $ 479,100

    OVERHEAD

         Payroll  (30% of direct labor)           $  31,600

         Plant  (26% of labor, parts & maint.)       60,000

         Total overhead costs                    $  91.600

    BY-PRODUCT CREDITS                                N.A.

    CAPITAL CHARGES

         G & A, taxes & insurance
           (4% of  total turnkey costs)            $  18.400

         Capital  recovery factor
           (11.75  % of total turnkey costs)          53.900

         Interest on working capital
           (10% of working capital)                  12,000

              Total capital charges              $  84.300

    TOTAL ANNUALIZED COSTS                       S

-------
                APPENDIX C

DETAILED CAPITAL AND ANNUALIZED COST TABLES
           FOR DUAL-FUEL BOILERS

-------
TABLE C-l.  ESTIMATED CAPITAL COSTS OF A DUAL-FUEL, PACKAGE,
     WATER-TUBE BOILER FIRING RESIDUAL OIL/NATURAL GAS
               WITH A THERMAL INPUT OF 8.8 MW
         (30 x 106 Btu/h; 150 psig/sat. temp, design)
 CAPITAL  COSTS
 DATE  OF  ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
      EQUIPMENT  COST3

       Boiler  (with fans  &  ducts)
       Stack
       Instrumentation
       Pulverizers
       Feeders
       Crushers
       Deaerators
       Heaters
       Boiler  feed  pumps
       Condensate systems
       Water treating system
       Chemical  feed
       Compressed air system
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel-oil  system

      Total Equipment Cost

      INSTALLATION COST,  DIRECT

       Boiler  (including  founda-
        tions  and steel)
       Stack
       Instrumentation
       Pulverizers
       Feeders
       Crushers
       Deaerators
       Heaters
       Boiler  feed pumps
       Condensate system
       Water treating system
       Chemical feed
       Coal handling system
       Ash disposal system
       Thawing equipment
       Fuel-oil system

 N.A.  - Not applicable.
                          $  150,000
                               5.000
                          incl.  w/boiler
                               N.A.	
                               N.A.
                               N.A.
                               7.000
                               N.A.
                              13.500
                               3.500
                               8.000
                               1.500
                               N.A.
                               N.A.
                               N.A.
                               N.A.
                              33.000
                          $  221.500
                              10.000
                               3,000
                          incl. w/boiler
                               N.A.	
                               N.A.
                               N.A.
                               2.500
                               N.A.
                               3.000
                               l.OQO
                               2.000
                               1.500
                               N.A.
                               N.A.
                               N.A.
                               8.000
                             C-l

-------
TABLE C-l.  (continued)
 INSTALLATION COSTS, DIRECT  (cont.)

     Foundations  and  supports
     Ductwork  (not  incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation cost

 TOTAL DIRECT COSTS
  (equipment + installation)

 INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct  costs)
     Construction and field expense
       (10% of direct  costs)
     Construction fees
       (10% of direct  costs)
     Start-up  (2% of  direct costs)
     Performance  tests  (minimum  $2000)

 TOTAL INDIRECT COSTS

 Contingencies
  (20% of direct and indirect costs)

 Total Turnkey Costs
   (direct+indirect+contingencies)

 Land

 Working capital  (25%  of total direct
 operating costs)

 GRAND TOTAL
  (turnkey+land+working capital)
    15.000
   N.A.
    29,000
    20,000
     4,000
    21,000
    70,000
$  190,000
$  411,500
$
41,200
41,200
41.200
8,200
2,000
$
133.800
$  109.100
   654.400
     2.000
   146,500/137,100
$  802,900/793,500
 'Quote from Zurn Industries, Inc., May 25, 1978,
N.A. - Not applicable.
                            C-2

-------
TABLE C-2.  ESTIMATED ANNUALIZED COSTS OF A DUAL-FUEL, PACKAGE,
       WATER-TUBE BOILER FIRING RESIDUAL OIL/NATURAL GAS
                WITH A THERMAL INPUT OF 8.8 MW
          (30 x 106 Btu/h; 150 psig/sat. temp, design)
    DIRECT COST

         Direct labor
         Supervision
         Maintenance labor
         Maintenance materials
         Replacement parts
         Electricity
         Steam
         Cooling water
         Process water
         Fuel
         Bottom ash disposal
         Chemicals

         Total direct cost

    OVERHEAD

         Payroll  (30% of direct labor

         Plant  (26% of labor.- parts & ma int.)

         Total overhead costs

    BY-PRODUCT CREDITS

    CAPITAL CHARGES

         G & A, taxes & insurance
           (4% of  total turnkey costs)

         Capital  recovery factor
           ( 10.61% of total turnkey costs)

         Interest on working capital
           (10% of working capital)

              Total capital charges

    TOTAL ANNUALIZED COSTS
    a  Included with  replacement parts.
    N.A.  - Not applicable.
$  105,300
     68,51TD
     32,000
	a	
     30,000
     29,300
   N.A.
   N.A.
	400
   319,400/281,900
   N.A.
      1,000
 $   585,900 /548,400
     31,600
     61,300
     92,900
   N.A.
     26.200
     69.400
     14.700/13,700

    110.300/109,300

 S  789.100/750,600
                             C-3

-------
TABLE C-3.  ESTIMATED CAPITAL COSTS OF A DUAL-FUEL, PACKAGE,
     WATER-TUBE BOILER FIRING RESIDUAL OIL/NATURAL GAS
               WITH A THERMAL INPUT OF 17.6 MW
        (60 x 106 Btu/h; 150 psig/sat. temp, design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS INDEXING)
     EQUIPMENT COST a

      Boiler (with fans & ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler (including founda-
       tions and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. - Not applicable.
                              280.000
                                9.500
                          incl. w/boiler
                          	N.A	
                               N.A.
                               N.A.
                               13.500
                               N.A.
                               18.000
                                4.500
                               12.500
                                1.500
                               N.A.
                               N.A.
                               N.A.
                               N.A.
                               41.000
                              380.500
                               15.500
                                4.700
                          incl
                               MA
                               N.A.
                                  nnn
                               N.A.
                                48QQ
                                1100
                                2. 100
                                1.500
                               N.A.
                           c-4

-------
TABLE C-3.   (continued)
INSTALLATION COSTS, DIRECT (cont.)

     Foundations and supports
     Ductwork (not incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation cost

TOTAL DIRECT COSTS
  (equipment 4- installation)

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)
     Construction  and field expense
       (10% of direct costs)
     Construction  fees
       (10% of direct costs)
     Start-up  (2%  of direct costs)
     Performance tests  (minimum  $2000)

TOTAL  INDIRECT COSTS

Contingencies
  (20%  of direct and indirect costs)

Total  Turnkey Costs
   (direct+indirect+contingencies)

Land

Working capital  (25% of total  direct
  operating costs)

GRAND  TOTAL
  (turnkey*land+working capital)
    21,000
   N.A.
    43,000
    22,500
     4 .100
    26.500
    76.500
$  241,800
$  622,300
    62,200
    62,200
    62,200
    12,400
     3,500
$  202,500
$  165,000
   989,800

     2,000
   238,700/219.900
$1.230.500/1,211,7QC
 Quote  from Zurn Industries,  Inc.,  May 25,  1978.
N.A. -  Not applicable.
                           C-5

-------
TABLE C-4.  ESTIMATED ANNUALIZED COSTS OF A DUAL-FUEL, PACKAGE,
       WATER-TUBE BOILER FIRING RESIDUAL OIL/NATURAL GAS
                WITH A THERMAL INPUT OF 17.6 MW
          (60 x 106 Btu/h; 150 psig/sat. temp, design)
                                                 S  105.300
                                                     68.500
                                                     64.100
                                                 	a	
                                                     42.000
                                                     32.900
                                                     N.A.
                                                     N.A.
                                                 	800
                                                    638.900/563.700
                                                     N.A.
                                                      2 .200
                                                 S  954.700/879.500
                                                     31.600
DIRECT COST

     Direct labor
     Supervision
     Maintenance labor
     Maintenance materials
     Replacement parts
     Electricity
     Steam
     Cooling water
     Process water
     Fuel
     Bottom ash disposal
     Chemicals

     Total direct cost

OVERHEAD

     Payroll (30% of direct labor

     Plant (26% of labor, parts & maint.)

     Total overhead costs

BY-PRODUCT CREDITS

CAPITAL CHARGES

     G & A, taxes & insurance
      (4% of total turnkey costs)

     Capital recovery factor
      (10.61% of total turnkey costs)

     Interest on working capital
      (10% of working capital)

          Total capital charges

TOTAL ANNUALIZED COSTS
                                                     72.800
                                                    104.400
                                                     N.A.
                                                    105,000
                                                     23,900/22,000
                                                 $  168,500/166,600

                                                 $1,227,600/1,150,500
   a Included with replacement parts.
   N.A. - Not applicable.
                            C-6

-------
TABLE C-5.  ESTIMATED CAPITAL COSTS OF A DUAL-FUEL, PACKAGE,
     WATER-TUBE BOILER FIRING RESIDUAL OIL/NATURAL GAS
               WITH A THERMAL INPUT OF 29.3 MW
         (100 x 106 Btu/h; 150 psig/sat. temp, design)
CAPITAL COSTS
DATE OF ESTIMATE   June 30. 1978	(FOR COSTS  INDEXING)


     EQUIPMENT COST3

      Boiler  (with fans &  ducts)             $   440,000
      Stack                                       12,000
      Instrumentation                       incl. w/boiler
      Pulverizers                                N.A.	
       Feeders             .                       N.A.
       Crushers                                   N.A.
       Deaerators                             	I8/ OOP
       Heaters                                   N.A.
       Boiler feed pumps                      	35,000
       Condensate systems                     	5, 500
       Water treating system                  	16, OOP
       Chemical feed                          	1/500
       Compressed air system                     N.A.
       Coal handling system                      N.A.
       Ash disposal system                       N.A.
       Thawing equipment                         N.A.
       Fuel-oil system                             45,000

      Total Equipment Cost                    $    573,000

      INSTALLATION COST,  DIRECT

       Boiler (including  founda-
        tions and steel)                       $     18,000
       Stack                                  	5,500
       Instrumentation                        incl.  w/boiler
       Pulverizers                            	N.A.	
       Feeders                                	N.A.	
       Crushers                               	N.A.	
       Deaerators                             	3,500
       Heaters                                	N.A.	
       Boiler feed pumps                       	6, OOP
       Condensate system                       	1,500
       Water treating system                  	2/500
       Chemical feed                          	1/500
       Coal handling system                   	N.A.	
       Ash disposal system                    	N.A.	
       Thawing equipment                       	N.A.	
       Fuel-oil system                             18,000

 N.A.  - Not applicable.
                            C-7

-------
TABLE C-5.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports
     Ductwork  (not incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation cost

TOTAL DIRECT COSTS
  (equipment + installation)

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)
     Construction and field expense
       (10% of direct costs)
     Construction fees
       (10% of direct costs)
     Start-up  (2% of direct costs)
     Performance tests  (minimum $2000)

TOTAL INDIRECT COSTS

Contingencies
  (20% of direct and indirect costs)

Total Turnkey Costs
   (direct+indirect+contingencies)

Land

Working capital (25% of total direct
 operating costs)

GRAND TOTAL
  (turnkey+land+working capital)
     25,000
    N.A.
     57,000
     25,000
      4,500
     33,000
     88,000
 $   289,000
 S   862.000
     86.200
     86.200
     fifi.200
     17.200
     3,50Q
S  279f3QO


S  228r3QQ


 1.369.600

	2.000
   362.4QQ/331.1QQ
$1.734.000/1.702.700
 Quote from Zurn Industries, Inc., May 25, 1978
N.A. - Not applicable.
                            C-8

-------
TABLE C-6.  ESTIMATED ANNUALIZED COSTS OF A DUAL-FUEL, PACKAGE,
       WATER-TUBE BOILER FIRING RESIDUAL OIL/NATURAL GAS
                WITH A THERMAL INPUT OF 29.3 MW
          (100 x 106 Btu/h; 150 psig/sat. temp, design)
    DIRECT  COST

         Direct  labor
         Supervision
         Maintenance labor
         Maintenance materials
         Replacement parts
         Electricity
         Steam
         Cooling water
         Process water
         Fuel
         Bottom ash disposal
         Chemicals

         Total direct cost

    OVERHEAD

         Payroll  (30% of direct labor

         Plant  (26% of labor, parts & maint.)

         Total overhead costs

    BY-PRODUCT CREDITS

    CAPITAL CHARGES

         G & A,  taxes & insurance
           (4% of total turnkey costs)

         Capital recovery factor
           (10.61 % of total turnkey costs)

         Interest on working capital
           (10% of working capital)

              Total capital charges

    TOTAL ANNUALIZED COSTS
    a Included with replacement parts.
    N.A. - Not applicable.
    157,900
     68,500
     64,100
     50,000
     39,300
    N.A.
    N.A.
      1,400
  1,064,800/939,500
    N.A.
      3,700
$ 1,449,700/1,324,400
     47,400
     88,500
    135,900
    N.A.
     54,800
    145.300


     36,200/33,100

$   236,300/233,200

$ 1.821.9QO/1.693.5QQ
                             C-9

-------
TABLE C-7.  ESTIMATED CAPITAL COSTS  OF A  DUAL-FUEL,  PACKAGE,
     WATER-TUBE BOILER FIRING RESIDUAL OIL/NATURAL GAS
               WITH A THERMAL INPUT  OF 44 MW
         (150 x 106 Btu/h;  750 psig/750°F  design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS INDEXING)
     EQUIPMENT COST

      Boiler  (with fans & ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler  (including founda-
       tions and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. - Not applicable.
                              600,000
                               14,500
                          incl. w/boiler
                          	N.A.	
                               N.A.
                               N.A.
                               21,600
                               N.A.
                               53,600
                                6,700
                               18,000
                                1,500
                               N.A.
                               N.A.
                               N.A.
                               N.A.
                               50,000
                              765,900
                               20,000
                                6,500
                          incl . w/boiler
                               N.A.
                               N.A.
                                4 .000
                               N.A.
                                7.500
                                1,500
                                3,000
                                1.500
                               N.A.
                               N.A.
                               N.A.
                               20.000
                           C-10

-------
TABLE C-7.  (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports
     Ductwork (not incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation cost

TOTAL DIRECT COSTS
  (equipment + installation)

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)
     Construction  and  field expense
       (10% of direct costs)
     Construction  fees
       (10% of direct costs)
     Start-up  (2%  of direct costs)
     Performance tests (minimum  $2000)

TOTAL INDIRECT COSTS

Contingencies
  (20% of direct and indirect  costs)

Total Turnkey Costs
   (direct+indirect+contingencies)

Land

Working capital  (25% of total direct
  operating costs)

GRAND TOTAL
  (turnkey*land+working capital)
     30,000
    N.A.
     74,000
     30,000
      5,000
     40,000
    100,000
    343,000
$ 1,108,900
    110,900
    110,900
    110,900
     22,200
      3,500
    358,400
    293,500
  1,760.800

      2,000
    513.800/466.800
$ 2,276,600/2,229,60
  Quote from Zurn Industries,  Inc.,  May 25,  1978.

 N.A.  - Not applicable.
                            C-ll

-------
TABLE C-8.  ESTIMATED ANNUALIZED COSTS OF A DUAL-FUEL, PACKAGE,
       WATER-TUBE BOILER FIRING RESIDUAL OIL/NATURAL GAS
                WITH A THERMAL INPUT OF 44 MW
          (150 x 106 Btu/h; 750 psig/750°F design)
                                                 S  210.600
                                                     68.500
                                                     64.100
                                                 	a	
                                                     60.000
                                                     47.100
                                                     N.A.
                                                     N.A.
                                                      2.100
                                                  1.597.200/1.409.300
                                                     N.A.
                                                      5.500
                                                 S2.Q55rlQQ/l-867.2nQ
                                                     63.200
DIRECT COST

     Direct labor
     Supervision
     Maintenance labor
     Maintenance materials
     Replacement parts
     Electricity
     Steam
     Cooling water
     Process water
     Fuel
     Bottom ash disposal
     Chemicals

     Total direct cost

OVERHEAD

     Payroll (30% of direct labor

     Plant (26% of labor, parts & maint.)

     Total overhead costs

BY-PRODUCT CREDITS

CAPITAL CHARGES

     G & A, taxes & insurance
      (4% of total turnkey costs)

     Capital recovery factor
      (10.61 % of total turnkey costs)

     Interest on working capital
      (10% of working capital)

          Total capital charges

TOTAL ANNUALIZED COSTS
                                                    104.800
                                                    168.000
                                                     N.A.
                                                 S    70.400
                                                        ann
                                                     51r4nO/4fir7QQ

                                                               , 9 0 0

                                                             , 3 3 9 , 1 0 0
    a  Included with replacement parts
    N.A.  - Not applicable.
                            C-12

-------
TABLE C-9..  ESTIMATED CAPITAL COSTS OF A DUAL-FUEL, FIEJLD-ERECTED,
     WATER-TUBE BOILER FIRING RESIDUAL OIL/NATURAL GAS
               WITH A THERMAL INPUT OF 58.6 MW
        (200 x 106 Btu/h; 750 psig/750°F design)
CAPITAL COSTS
DATE OF ESTIMATE   June 30. 1978	(FOR COSTS INDEXING)


     EQUIPMENT COST

      Boiler  (with fans &  ducts)              $ lyZ91'?99
      Stack                                       262,800
      Instrumentation                             182,400
      Pulverizers                                 N.A.	
      Feeders              .                       N.A
      Crushers                                    N.A.
      Deaerators                             	29,000
      Heaters                                     N.A.
      Boiler feed  pumps                      	58,000
      Condensate systems                     	16.300
      Water treating  system                  	20,000
      Chemical  feed                          	500
      Compressed air  system                  	12,500
      Coal handling system                       N.A.
      Ash disposal system
       Thawing equipment                      	N. A.	
       Fuel-oil system                            150.000

      Total Equipment Cost                    $ 2.436.500

      INSTALLATION COST, DIRECT

       Boiler (including founda-                  868 000
        tions and steel)                      J	'.	
       Stack                                       50.000
       Instrumentation                        	28 ,QQQ
       Pulverizers                                TJ. A.
       Feeders                                _ N_JL
       Crushers
       Deaerators                             _ 5, QQQ
       Heaters                                    N.A.
       Boiler feed pumps                      	8tOOQ
       Condensate system                      	2,000
       Water treating system                  	3,500
       Chemical feed                          	1/500
       Coal handling system                   	N,A,
       Ash disposal system                        N.A.
       Thawing equipment
       Fuel-oil system                        	75,000

 N.A. - Not applicable.
                            C-13

-------
TABLE C-9.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports
     Ductwork  (not incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation cost

TOTAL DIRECT COSTS
  (equipment + installation)

INSTALLATION COSTS, INDIRECT

     Engineering
      (10% of direct costs)
     Construction and field expense
      (10% of direct costs)
     Construction fees
      (10% of direct costs)
     Start-up  (2% of direct costs)
     Performance tests  (minimum $2000)

TOTAL INDIRECT COSTS

Contingencies
  (20% of direct and indirect costs)

Total Turnkey Costs
   (direct+indirect+contingencies)

Land

Working capital (25% of total direct
 operating costs)

GRAND TOTAL
  (turnkey+land+working capital)
    144,000
    N.A.
    100,000
     75,000
      8,000
    128,000
    304,000
$ 1,800,000
$ 4.236.500
    423.700
    423.700
    423.7nn
     84.700
      5,000
S lr3fiQf8QQ


S lf119r5QQ


  6.716.800

	2.000
    693,200/630,500
$ 7,412,000/7,349,300
aQuote from Babcock & Wilcox, Inc., August 17, 1978.
N.A. - Not applicable.
                           C-14

-------
TABLE C-10.  ESTIMATED ANNUALIZED COSTS OF A DUAL-FUEL, .FIELD-ERECTED,
       WATER-TUBE BOILER FIRING RESIDUAL OIL/NATURAL GAS
                WITH A THERMAL INPUT OF 58.6 MW
          (200 x 106 Btu/h; 750 psig/750°F design)
    a Included with  replacement  parts,
    N.A.  - Not applicable.
                                                   S   263.2QQ
                                                      102.700
                                                       96.100
                                                        a
                                                      100.000
                                                       70.700
                                                       N.A.
                                                       N-A.
                                                  	2 .800
                                                        7.5QQ
DIRECT COST

     Direct labor
     Supervision
     Maintenance labor
     Maintenance materials
     Replacement parts
     Electricity
     Steam
     Cooling water
     Process water
     Fuel
     Bottom ash disposal
     Chemicals

     Total direct cost

OVERHEAD

     Payroll  (30% of direct labor

     Plant  (26% of  labor, parts  & maint.)

     Total overhead costs

BY-PRODUCT CREDITS

CAPITAL CHARGES

     G & A, taxes & insurance
       (4% of  total  turnkey costs)

     Capital  recovery  factor
       ( 10.14* °f total  turnkey  costs)

     Interest on working capital
       (10% of working  capital)

          Total capital  charges

TOTAL ANNUALIZED COSTS
                                                    2.129.600/1.879.000
                                                       N.A.
                                                   S2r772f6QQ/2.522.QQQ
                                                       79.000
                                                      146.100
                                                      225.100
                                                       M.A.
                                                      268 .700
                                                      681,100
                                                       69,300/63,100
                                                   $1,019,100/1,012,900

                                                   $4,016,800/3,760,000
                              C-15

-------
TABLE Oil. ESTIMATED CAPITAL COSTS OF A DUAL-FUEL, FIELD-ERECTED,
     WATER-TUBE BOILER FIRING RESIDUAL OIL/NATURAL GAS
               WITH A THERMAL INPUT OF 117.2 MW
        (400 x 106 Btu/h; 750 psig/750°F design)
CAPITAL COSTS
DATE OF ESTIMATE   June 30, 1978	(FOR COSTS INDEXING)


     EQUIPMENT COST3

      Boiler (with fans & ducts)             S 2;736r600
      Stack                                      5QOfQQQ
      Instrumentation                            302,800
      Pulverizers                                TJ. A.
      Feeders                                    N.A. _
      Crushers                                   N.A. _
      Deaerators                             _ 60. OOP
      Heaters                                    N.A. _
      Boiler feed pumps                          150.000
      Condensate systems                     _ 25f OOP
      Water treating system                  _ 6Qf OOP
      Chemical feed                          _ 4 rPOQ
      Compressed air system                  _ 25,000
      Coal handling system                       N.A. _
      Ash disposal system                        N.A. _
      Thawing equipment                          N.A. _
      Fuel-oil system                        _ 29P,PPP

     Total Equipment Cost                    S 4r153r4QQ

     INSTALLATION COST- DIRECT

      Boiler (including founda-
       tions and steel)                      $ 1,736,000
      Stack                                  incl . w/equipment
      Instrumentation                        _ 88.000
      Pulverizers                            _ 1LJL _
      Feeders                                _ N.A. _
      Crushers                               _ N.A. _
      Deaerators                             _ 12.000
      Heaters                                    N.A.
      Boiler feed pumps                      _ 18 ,000
      Condensate system                      _ 10, OOP
      Water treating system                  _ 16,000
      Chemical feed                          _ 2. OOP
      Coal handling system                   _ N.A.
      Ash disposal system                    	N.A.
      Thawing equipment                      	N.A.
      Fuel-oil system                            145,OOP

N.A. - Not applicable.


                           C-16

-------
TABLE C-ll.  (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports
     Ductwork (not incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation cost

TOTAL DIRECT COSTS
  (equipment + installation)

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)
     Construction  and field expense
       (10% of direct costs)
     Construction  fees
       (10% of direct costs)
     Start-up  (2%  of direct costs)
     Performance tests  (minimum  $2000)

TOTAL  INDIRECT COSTS

Contingencies
  (20%  of direct and indirect  costs)

Total  Turnkey Costs
   (direct+indirect+contingencies)

Land

Working capital  (25% of total direct
  operating costs)

GRAND  TOTAL
  (turnkey+land+working capital)
    264,000
    N.A.
    156,000
    100,000
     13,000
    272,000
    520,000
$ 3.352.000
$ 7.505.400
    750.500
    750.500
    750. 500
    150,100
     13,000
$ 2.414.600


$ 1.984.000


 11.904.000

_ 2.000
  1,319,900/1,194,600
$13.225.900/13.100.61
aQuote from Babcock & Wilcox, Inc., August 17, 1978.

N.A. - Not applicable.
                            C-17

-------
TABLE C-12.  ESTIMATED ANNUALIZED COSTS OF A DUAL-FUEL, FIELD-ERECTED,
       WATER-TUBE BOILER FIRING RESIDUAL OIL/NATURAL GAS
                WITH A THERMAL INPUT OF 117.2 MW
         (400 x 106 Btu/h; 750 psig/750°F design)
   DIRECT COST

        Direct labor
        Supervision
        Maintenance labor
        Maintenance materials
        Replacement parts
        Electricity
        Steam
        Cooling water
        Process water
        Fuel
        Bottom ash disposal
        Chemicals

        Total direct cost

   OVERHEAD

        Payroll (30% of direct labor

        Plant (26% of labor, parts & maint.)

        Total overhead costs

   BY-PRODUCT CREDITS

   CAPITAL CHARGES

        G & A, taxes & insurance
          (4% of total turnkey costs)

        Capital recovery factor
          ( 10.14% of total turnkey costs)

        Interest on working capital
          (10% of working capital)

             Total capital charges

   TOTAL ANNUALIZED COSTS
   a Included with replacement parts
   N.A. - Not applicable.
    473,800
    136,900
    128.200
    150.000
    110,000
   N.A.
   N.A.
      5.600
  4,259,100/3.758.000
   N.A.
     16.000
$ 5,279,600/4,778,500
    142.100
    231.100
    373.200
    N.A.
    476.200
  lr2Q7flQQ


    132.000/119.500

S 1.815.3QQ/1.802.800

$ 7.468.100/6.954.500
                            C-18

-------
TABLE C-13.  ESTIMATED CAPITAL COSTS OF A DUAL-FUEL, FIELD-ERECTED,
     WATER-TUBE BOILER FIRING RESIDUAL OIL/NATURAL GAS
               WITH A THERMAL INPUT OF 205.1 MW
         (700 x 10° Btu/h; 900 psig/750°F design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
     EQUIPMENT COST

      Boiler  (with fans & ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler  feed pumps
      Condensate systems
      Water treating system
      Chemical  feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil  system

      Total Equipment Cost

      INSTALLATION COST, DIRECT

      Boiler  (including founda-
        tions  and  steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler  feed pumps
      Condensate  system
      Water  treating  system
      Chemical  feed
      Coal handling  system
      Ash disposal  system
      Thawing equipment
      Fuel-oil  system

 N.A.  -  Not applicable.
                          $ 4.419.000
                              900.000
                              489.000
                              N.A.
                              N.A.
                              N.A.
                               85.000
                              N.A.
                              195.000
                               35.000
                          	90rQOO
                          	4.000
                               30.000
                              N.A.
                              N.A.
                              N.A.
                              490.000
                             6.737.0QQ
                           $  2,455,000
                           incl.  w/equipment
                              128,000
                              N.A.	
                              N.A.	
                              N.A.	
                                19.000
                              N.A.	
                                25,000
                                16.000
                                28,000
                           	2,000
                              N.A.	
                              N.A.	
                              N.A.	
                               245,000
                            C-19

-------
TABLE C-13.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports
     Ductwork (not incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation cost

TOTAL DIRECT COSTS
 (equipment + installation)

INSTALLATION COSTS, INDIRECT

     Engineering
      (10% of direct costs)
     Construction and field expense
      (10% of direct costs)
     Construction fees
      (10% of direct costs)
     Start-up (2% of direct costs)
     Performance tests  (minimum $2000)

TOTAL INDIRECT COSTS

Contingencies
 (20% of direct and indirect costs)

Total Turnkey Costs
  (direct+indirect+contingencies)

Land

Working capital (25% of total direct
 operating costs)

GRAND TOTAL
 (turnkey*land+working capital)
    484.000
    N.A.
    279,000
    165,000
     22,000
    520,000
    930,000
$ 5.318.000
$12.055.000
$ 1.205.500

  -.205.500

  1.2Q5r50Q
    241,100
     16,000

$ 3.873.600


$ 3.185.700


 19.114.300

	2.000


  2.215.100/1.995.900


$21.331.400/21.112.201
aQaote from Babcock & Wilcox, Inc., August 17, 1978.

N.A. - Not applicable.
                            C-20

-------
TABLE C-14.  ESTIMATED ANNUALIZED COSTS OF A DUAL-FUEL, FIELD-ERECTED,
       WATER-TUBE BOILER FIRING RESIDUAL OIL/NATURAL GAS
                WITH A THERMAL INPUT OF 205.1 MW
         (700 x 106 Btu/h; 900 psig/750°F design)
   DIRECT COST

         Direct  labor
         Supervision
         Maintenance labor
         Maintenance materials
         Replacement parts
         Electricity
         Steam
         Cooling water
         Process water
         Fuel
         Bottom ash disposal
         Chemicals

         Total direct  cost

    OVERHEAD

         Payroll (30%  of direct labor

         Plant  (26% of labor, parts & maint.)

         Total overhead costs

    BY-PRODUCT CREDITS

    CAPITAL CHARGES

         G & A, taxes & insurance
          (4% of total turnkey costs)

         Capital recovery factor
          (10.14 % of total turnkey costs)

         Interest on working capital
          (10% of working capital)

              Total capital charges

    TOTAL ANNUALIZED COSTS
 $   605,400
    136,900
    224,3W
     a	
    225,000
    180,650"
     N.A.
     N.A.
      9,700"
  7,453,461)76,576,600
     N.A.
     25,000
 $8,860,300/7,983,500



 $  181,600

    309,800
 $  491,400

     N.A.
 $  764,600


  1,938,200


    221,500/199,600

 $2,924,300/2,902,400

$12.276.000/11.377.300
    a Included with replacement parts.
    N.A. - Not applicable.
                             C-21

-------
 TABLE C-15.   ESTIMATED CAPITAL COSTS OF A DUAL-FUEL, PACKAGE,
     WATER-TUBE BOILER FIRING DISTILLATE OIL/NATURAL GAS
                WITH A THERMAL INPUT OF 8.8 MW
         (30  x 106 Btu/h;  150 psig/sat. temp,  design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30. 1978
(FOR COSTS INDEXING)
     EQUIPMENT COST
                    a
      Boiler  (with fans 6 ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler  (including founda-
       tions and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. - Not applicable.
                           $   150,000
                          	5,000
                           incl.  w/boiler
                               N.A.	
                               N.A.	
                               N.A.	
                                7,000
                               N.A.	
                               13T500
                                3,500
                          	8.000
                          	1,500
                               N.A.	
                               N.A.	
                               N.A.	
                               N.A.	
                               26,000

                           $   214,500
                               10,000
                                3,000
                           incl. w/boiler
                              N.A.	
                              N.A.
                              N.A.
                                2.500
                              N.A.
                                3.000
                               1.000
                                2.000
                               1.500
                              N.A.
                              N.A.
                              N.A.
                                6.000
                            C-22

-------
TABLE C-15.   (continued)
INSTALLATION COSTS, DIRECT (cont.)

     Foundations and supports
     Ductwork (not incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation cost

TOTAL DIRECT COSTS
  (equipment + installation)

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)
     Construction and field expense
       (10% of direct costs)
     Construction fees
       (10% of direct costs)
     Start-up  (2% of direct costs)
     Performance tests  (minimum  $2000)

TOTAL  INDIRECT COSTS

Contingencies
  (20%  of direct and indirect costs)

Total  Turnkey Costs
   (direct+indirect+contingencies)

Land

Working capital  (25% of total direct
  operating costs)

GRAND  TOTAL
  (turnkey+land+working capital)
   15.000
    N.A.
   29.000
   20,000
    4,000
   21,000
   70,000

$ 188.000
$ 402.500
$  40.300

   40.300

   40.300
    8,100
    2,000

S 131.000


$ 106,700


  640,200

    2,000


  175,000/137.100


$ 817.200/779.300
 aQuote from Zurn Industries,  Inc.,  May 25,  1978.

 N.A.  - Not applicable.
                            C-23

-------
TABLE C-16.  ESTIMATED ANNUALIZED COSTS OF A DUAL-FUEL,  PACKAGE,
      WATER-TUBE BOILER FIRING DISTILLATE OIL/NATURAL GAS
                WITH A THERMAL INPUT OF 8.8 MW
         (30 x 106 Btu/h; 150 psig/sat. temp, design)
   a Included with replacement parts.
   N.A. - Not applicable.
                                                     105.300
                                                      68.500
                                                      32.000
                                                      30.000
                                                      29.300
                                                     N.A.
                                                     N.A.
                                                         400
                                                       1,000
DIRECT COST

     Direct labor
     Supervision
     Maintenance labor
     Maintenance materials
     Replacement parts
     Electricity
     Steam
     Cooling water
     Process water
     Fuel
     Bottom ash disposal
     Chemicals

     Total direct cost

OVERHEAD

     Payroll (30% of direct labor

     Plant (26% of labor, parts & maint.)

     Total overhead costs

BY-PRODUCT CREDITS

CAPITAL CHARGES

     G & A, taxes & insurance
      (4% of total turnkey costs)

     Capital recovery factor
      (10.61 % of total turnkey costs)

     Interest on working capital
      (10% of working capital)

          Total capital charges

TOTAL ANNUALIZED COSTS
                                                     433,600/281,900
                                                     N.A.
                                                     700,100/548,400
                                                      31,600
                                                      61.300
                                                      92.900
                                                    N.A.
                                                      25.600
                                                      67.900
                                                      17.500/13.700

                                                 $   111.000/107,200

                                                 S   904.000/748.500
                            C-24

-------
TABLE C-17.  ESTIMATED CAPITAL COSTS OF A DUAL-FUEL,  PACKAGE,
     WATER-TUBE BOILER FIRING DISTILLATE OIL/NATURAL  GAS
               WITH A THERMAL INPUT OF 17.6 MW
         (60 x 106 Btu/h;  150 psig/sat. temp, design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS  INDEXING)
     EQUIPMENT COST

      Boiler  (with fans & ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler  feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler  (including founda-
        tions  and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler  feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. -  Not applicable.
                               280,000
                           incl.  w/boiler
                               N.A.
                               N.A.
                               N.A.
                                13,500
                               N.A.
                                187001)
                                 4,500
                               N.A.
                               N.A,
                                32.onn
                                15,500
                                 4,700
                           incl. w/boiler
                               N.A.	
                               N.A.
                               N.A.
                                 3,000
                               N.A.
                                 4,800
                                 1,100
                                 2,100
                                 1,500
                               N.A.
                               N.A.
                               N.A.
                                11,500
                            C-25

-------
 TABLE  C-17.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports
     Ductwork  (not incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation cost

TOTAL DIRECT COSTS
  (equipment + installation)

INSTALLATION COSTS, INDIRECT

     Engineering
      (10% of direct costs)
     Construction and field expense
      (10% of direct costs)
     Construction fees
      (10% of direct costs)
     Start-up  (2% of direct costs)
     Performance tests  (minimum $2000)

TOTAL INDIRECT COSTS

Contingencies
  (20% of direct and indirect costs)

Total Turnkey Costs
  (direct+indirect-f contingencies)

Land

Working capital (25% of total direct
 operating costs)

GRAND TOTAL
  (turnkey*land+working capital)
    21.000
   N.A.
    43,000
    22,500
     4.100
    26.500
    76.500
$  237,800
   6QQ.30Q
    60.900
    12.200
     3. 500
$  198.400


$  161.500


   969.200

     2.000


   295.800/219.900


$1,267.000/1.191.100
 .Quote from Zurn Industries, Inc., May 25, 1979.

N.A. - Not applicable.

                           C-26

-------
TABLE C-18.  ESTIMATED ANNUALIZED COSTS OF A DUAL-FUEL, PACKAGE,
      WATER-TUBE BOILER FIRING DISTILLATE OIL/NATURAL GAS
                WITH A THERMAL INPUT OF 17.6 MW
          (60 x 106 Btu/h; 150 psig/sat. temp, design)
    a Included with replacement parts.
    N.A. - Not applicable.
                                                      68,500
                                                     64.100
                                                     42.000
                                                     32,900
                                                    N.A; .
                                                    N.A.
                                                        800
                                                       2^200
                                                  SI.183.000/879.500
                                                      31,600
DIRECT COST

     Direct labor
     Supervision
     Maintenance labor
     Maintenance materials
     Replacement parts
     Electricity
     Steam
     Cooling water
     Process water
     Fuel
     Bottom ash disposal
     Chemicals

     Total direct cost

OVERHEAD

     Payroll  (30% of direct  labor

     Plant  (26% of  labor, parts  & maint.)

     Total overhead costs

BY-PRODUCT CREDITS

CAPITAL CHARGES

     G & A, taxes  & insurance
       (4% of  total  turnkey costs)

     Capital  recovery  factor
       ( 10.61 * of  total  turnkey  costs)

     Interest on working capital
       (10% of working  capital)

          Total capital  charges

TOTAL ANNUALIZED COSTS
                                                    867.200/563.700
                                                    N.A.
                                                      72,800

                                                  $   104.400

                                                      N.A.
                                                  $  '  38,800


                                                     102.800


                                                      29,600/22,000

                                                  $   171,200/163,600 _

                                                  $1.458.600/1.147.500
                             C-27

-------
TABLE C-19.  ESTIMATED CAPITAL COSTS OF A  DUAL-FUEL,  PACKAGE,
     WATER-TUBE BOILER FIRING DISTILLATE OIL/NATURAL  GAS
               WITH A THERMAL INPUT OF 29.3 MW
         (100 x 106 Btu/h; 150 psig/sat. temp, design)
CAPITAL COSTS
DATE OF ESTIMATE
June 30, 1978
(FOR COSTS INDEXING)
     EQUIPMENT COST

      Boiler  (with fans & ducts)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate systems
      Water treating system
      Chemical feed
      Compressed air system
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

     Total Equipment Cost

     INSTALLATION COST, DIRECT

      Boiler  (including founda-
       tions and steel)
      Stack
      Instrumentation
      Pulverizers
      Feeders
      Crushers
      Deaerators
      Heaters
      Boiler feed pumps
      Condensate system
      Water treating system
      Chemical feed
      Coal handling system
      Ash disposal system
      Thawing equipment
      Fuel-oil system

N.A. - Not applicable.
                          $  440,000
                              12,000
                          incl. w/boiler
                              N.A.	
                              N.A.	
                              N.A.	
                              18,000
                              N.A.	
                              35,000
                               5,500
                              16.000
                               1,500
                              N.A.	
                              N.A.	
                              N.A.	
                              N.A.	
                              35,000

                          $  563,000
                          $   18,000
                               5,500
                          incl. w/boiler
                              N.A.	
                              N.A.	
                              N.A.	
                               3.500
                              N.A.	
                               6.000
                               1.500
                          	2.500
                               1.500
                              N.A.	
                              N.A.	
                              N.A.	
                              13,500
                           C-28

-------
TABLE C-19.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports
     Ductwork (not incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation cost

TOTAL DIRECT COSTS
  (equipment + installation)

INSTALLATION COSTS, INDIRECT

     Engineering
       (10% of direct costs)
     Construction and field expense
       (10% of direct costs)
     Construction fees
       (10% of direct costs)
     Start-up  (2% of direct costs)
     Performance tests  (minimum  $2000)

TOTAL  INDIRECT COSTS

Contingencies
  (20%  of direct and indirect costs)

Total  Turnkey Costs
   (direct+indirect+contingencies)

Land

Working capital  (25% of total  direct
  operating costs)

GRAND  TOTAL
  (turnkey+land+working  capital)
    25,000
   N.A.
    57,000
    25,000
     4,500
    33,000
    88,000
   284.500
   847.500
    84 .800
    84,800
    84,800
    17,000
     3,500
$  274,900


$  224,500


 1,346,900

     2,000
   457,600/331,100
$1,806,500/1,680,0(
aQuote from Zurn Industries, Inc., May 25, 1978,

N.A. - Not applicable.
                            C-29

-------
TABLE C-20.  ESTIMATED ANNUALIZED COSTS OF A DUAL-FUEL,  PACKAGE,
      WATER-TUBE BOILER FIRING DISTILLATE OIL/NATURAL  GAS
                WITH A THERMAL INPUT OF 29.3 MW
         (100 x 106 Btu/h; 150 psig/sat. temp, design)
   a Included with replacement parts.
   N.A. - Not applicable.
                                                     157.900
                                                      68,500
                                                      64.100
                                                      50.000
                                                      39.300
                                                    N.A.
                                                    N.A.
                                                       1.400
                                                      3.7QQ
DIRECT COST

     Direct labor
     Supervision
     Maintenance labor
     Maintenance materials
     Replacement parts
     Electricity
     Steam
     Cooling water
     Process water
     Fuel
     Bottom ash disposal
     Chemicals

     Total direct cost

OVERHEAD

     Payroll (30% of direct labor

     Plant (26% of labor, parts & maint.)

     Total overhead costs

BY-PRODUCT CREDITS

CAPITAL CHARGES

     G & A, taxes & insurance
      (4% of total turnkey costs)

     Capital recovery factor
      (10.61 % of total turnkey costs)

     Interest on working capital
      (10% of working capital)

          Total capital charges

TOTAL ANNUALIZED COSTS
                                                   1.445.400/939.500
                                                    N.A.
                                                 $ 1.83Q.3QQ/1.324.40Q
                                                      47.400
                                                      88.500
                                                     135.900
                                                    N.A.
                                                      53.900
                                                     142,900
                                                      45,800/33,100
                                                 S   242ffinn/229,900

                                                 $ 2.208.80Q/1.690.200
                            C-30

-------
TABLE C-21.  ESTIMATED CAPITAL COSTS OF A DUAL-FUEL, PACKAGE,
     WATER-TUBE BOILER FIRING DISTILLATE OIL/NATURAL GAS
                WITH A THERMAL INPUT OF 44 MW
           (150 x 106 Btu/h; 750 psig/750°F design)

 CAPITAL COSTS
 DATE OF ESTIMATE   June 30, 1978 _ (FOR COSTS INDEXING)


      EQUIPMENT COST3

       Boiler  (with fans & ducts)            $  600.000 _
       Stack                                      14.500 _
       Instrumentation                       Incl. w/boiler
       Pulverizers                            _ N. A. _
       Feeders                                _ N.A. _
       Crushers           •                    _ N.A. _
       Deaerators                                 21f 600 _
       Heaters                                _ N.A. _
       Boiler  feed pumps                          53.600 _
       Condensate systems                          6 f 700 _
       Water treating system                      18f OOP _
       Chemical feed                               If500 _
       Compressed air system                  J _ N.A. _
       Coal handling system
        Ash  disposal  system                    _ N.A.
        Thawing  equipment                       _ N.A.
        Fuel-oil system                           39f OOP

       Total Equipment  Cost                   $  754,900

       INSTALLATION COST,  DIRECT

        Boiler (including  founda-
         tions and steel)                      $   2QfOQQ
        Stack                                      6.500
        Instrumentation                       Tncl.  w/boiler
        Pulverizers                            _ N. A.
        Feeders                                 _ N.A.
        Crushers                               _ TJ.A.
        Deaerators                                 4rQQQ
        Heaters                                 _ N.A.
        Boiler feed pumps                       _ 7f 500
        Condensate system                       _ 1,500
        Water treating  system                  _ 3f OOP
        Chemical feed                              1 r5on
        Coal handling system                   _ N.A.
        Ash  disposal  system                    _ N.A.
        Thawing  equipment                       -- N.A.
        Fuel-oil system                           15f OOP

  N.A.  - Not applicable.
                             C-31

-------
 TABLE  C-21.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and supports                         30,000
     Ductwork  (not incl. w/boiler)                 	N.A.
     Piping                                           74,000
     Insulation                                       30,000"
     Painting                                          5,000
     Electrical                                       40,000
     Buildings                                       100,000

     Total installation cost                      S  338.000

TOTAL DIRECT COSTS
  (equipment + installation)                       $1.092.900

INSTALLATION COSTS, INDIRECT

     Engineering
      (10% of direct costs)                       S  109.300
     Construction and field expense
      (10% of direct costs)                          109.300
     Construction fees
      (10% of direct costs)                          109,300
     Start-up  (2% of direct costs)                    21,900
     Performance tests  (minimum $2000)   .          	3,500

TOTAL INDIRECT COSTS                              $  353.300

Contingencies
  (20% of direct and indirect costs)               $  289.200

Total Turnkey Costs
  (direct+indirect+contingencies)                  lf735.400

Land                                               	2.000

Working capital (25% of total direct                 656,500/
 operating costs)                                     466.800

GRAND TOTAL                                       $2,393,900/
  (turnkey+land+working capital)                    9,?na


aBased on quote from Zurn Industries, Inc., May 25, 1978

N.A. - Not applicable.


                            C-32

-------
TABLE C-22.  ESTIMATED ANNUALIZED COSTS OF A DUAL-FUEL, PACKAGE,
       WATER-TUBE BOILER FIRING DISTILLATE OIL/NATURAL GAS
                  WITH A THERMAL INPUT OF 44 MW
             (150 x 10° Btu/h, 750 psig/750°F design)
     DIRECT COST

           Direct  labor
           Supervision
           Maintenance labor
           Maintenance materials
           Replacement parts
           Electricity
           Steam
           Cooling water
           Process water
           Fuel
           Bottom ash disposal
           Chemicals

           Total direct  cost

      OVERHEAD

           Payroll (30%  of direct labor

           Plant (26% of labor, parts & maint.)

           Total overhead costs

      BY-PRODUCT CREDITS

      CAPITAL CHARGES

           G & A, taxes  & insurance
            (4% of total turnkey costs)

           Capital recovery factor
            (10.61 % of  total turnkey costs)

           Interest on working capital
            (10% of working capital)

                Total capital charges

      TOTAL ANNUALIZED COSTS
   210.600
    68,500
    64.100
    60.000
    47.100
      N.A.
      N.A.
     2.100
 2.168.100/1.409,300
      N.A.
     5.500
S2.626.000/1.867.200
    63,200
   104.800
   168.000
      N.A.
    69.400
   1B4.10n
    65.700/46.700

   319.200/300.200 '''

           2,3 3 5,4 0 0
      a Included with replacement parts.
      N.A. - Not applicable.
                               C-33

-------
 TABLE C-23.   ESTIMATED CAPITAL COSTS OF A DUAL-FUEL, FIELD-
  ERECTED,  WATER-TUBE BOILER FIRING DISTILLATE OIL/NATURAL
             GAS  WITH A THERMAL INPUT  OF 58.6 MW
          (200 x  106  Btu/h;  750 psig/750°F design)
CAPITAL COSTS
DATE OF ESTIMATE   June 30, 1978	(FOR COSTS INDEXING)


     EQUIPMENT COSTa

      Boiler  (with fans & ducts)             $  1,704,000
      Stack                                      262,800
      Instrumentation                            182,400
      Pulverizers                            	N.A.	
      Feeders                                	N.A.	
      Crushers                               	N.A.	
      Deaerators                                  29,000
      Heaters                                	N.A.
      Boiler feed pumps                      	58,000	
      Condensate systems                     	16,300	
      Water treating system                       20,000
      Chemical feed                          	1.500
      Compressed air system                  	12,500	
      Coal handling system                   	N.A.	
      Ash disposal system                    	N.A.	
      Thawing equipment                      	N.A.	
      Fuel-oil system                            100,000

     Total Equipment Cost                    $  2,386,500

     INSTALLATION COST, DIRECT

      Boiler  (including founda-
       tions and steel)                      $    868.000
      Stack                                       50,000
      Instrumentation                        	28 .000
      Pulverizers                            	N.A.	
      Feeders                                	N.A.	
      Crushers                               	N.A.	
      Deaerators                             	5.000	
      Heaters                                	N.A.	
      Boiler feed pumps                      	8 .000	
      Condensate system                      	2.000	
      Water treating system                  	3.500
      Chemical feed                          	1.500
      Coal handling system                   	N.A.	
      Ash disposal system                    	N.A.	
      Thawing equipment                      	N.A.	
      Fuel-oil system                        	5Q.QOQ

N..A. - Not applicable.
                           C-34

-------
TABLE C-23.  (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations  and  supports
     Ductwork  (not  incl.  w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation cost

TOTAL  DIRECT COSTS
  (equipment +  installation)

 INSTALLATION COSTS,  INDIRECT

     Engineering
       (10% of  direct  costs)
     Construction and field expense
       (10% of  direct  costs)
     Construction fees
       (10% of  direct  costs)
     Start-up  (2% of  direct costs)
     Performance tests (minimum $2000)

 TOTAL  INDIRECT COSTS

 Contingencies
  (20%  of direct and indirect costs)

 Total  Turnkey  Costs
   (direct+indirect+contingencies)

 Land

 Working capital  (25%  of total direct
  operating costs)

 GRAND  TOTAL
  (turnkey*land+working capital)
    144 rnnn
      N.A.
    100.000
     75,000
      8,000
    128.000
    304,000
  i .775.nno
S 4.161.500
    416.200
     83,200
      5,000
$ 1.336.800


S 1.099.700


  6.598.000

 _ 2.000
    883.5QQ/63Q.5QQ
  7,483,500/7,230,500
 a Based on quote from Babcock & Wilcox, Inc., August 17, 1978

 N.A. - Not applicable.
                             C-35

-------
TABLE C-24.  ESTIMATED ANNUALIZED COSTS OF A DUAL-FUEL, FIELD-
    ERECTED, WATER-TUBE BOILER FIRING DISTILLATE OIL/NATURAL
              GAS WITH A THERMAL INPUT OF 58.6 MW
            (200 x 106 Btu/h; 750 psig/750°F design)
    DIRECT COST

         Direct labor
         Supervision
         Maintenance labor
         Maintenance materials
         Replacement parts
         Electricity
         Steam
         Cooling water
         Process water
         Fuel
         Bottom ash disposal
         Chemicals

         Total direct cost

    OVERHEAD

         Payroll (30% of direct labor)

         Plant (26% of labor,  parts & maint.)

         Total overhead costs

    BY-PRODUCT CREDITS

    CAPITAL CHARGES

         G & A,  taxes & insurance
          (4% of total turnkey costs)

         Capital recovery factor
          (10.14 % of total  turnkey costs)

         Interest on working capital
          (10% of working capital)

              Total capital  charges

    TOTAL ANNUALIZED COSTS
 $  263,200
    102,700
     96,100
 	a
    100,000
     70,700
 	N.A.
 	N.A.
 	2,800
  2,890,800/1,879,000
       N.A.
      7.500
$ 3,533,800/2.522,000
    $79,000
    146.100

   $225.100
       N.A.
   $263.900
     88.400/63.100

S 1.021.300/996.000

$ 4.780.200/3.743,100
    a Included  with replacement  parts.
    N.A.  - Not  applicable.
                             C-36

-------
TABLE C-25.  ESTIMATED CAPITAL COSTS  OF A  DUAL-FUEL, FIELD-
 ERECTED, WATER-TUBE BOILER FIRING  DISTILLATE  OIL/NATURAL
           GAS WITH A THERMAL INPUT OF 117.2 MW
          (400 x  106 Btu/h; 750 psig/750°F  design)
CAPITAL COSTS
DATE OF ESTIMATE   June 30, 1978	(FOR COSTS INDEXING)


     EQUIPMENT COSTa

      Boiler  (with fans & ducts)             $2,736,600	
      Stack                                     500,000	
      Instrumentation                           302,800	
      Pulverizers                            	N.A.	
      Feeders                                	N.A.	
      Crushers             '                  	N.A.	
      Deaerators                                 60.000	
      Heaters                                	N.A.	
      Boiler  feed pumps                         150,000	
      Condensate systems                         25.000	
      Water treating system                      60.000	
      Chemical feed                               4.000	
      Compressed air system                      25.000	
      Coal handling system                  	N.A.	
      Ash disposal system                    	N.A.	
      Thawing equipment                      	N.A.	
      Fuel-oil system                           195.000	

     Total Equipment Cost                    $4 .058 .400	

     INSTALLATION COST, DIRECT

      Boiler  (including founda-
        tions  and steel)                      Sl.736ronn
      Stack                                  Incl. w/equip.
      Instrumentation                            88.000	
      Pulverizers                            	N.a.	
      Feeders                               	N.A.	
      Crushers                               	^Ji*A-	
       Deaerators                                 12 fnnn
       Heaters                                 	N.A.
       Boiler feed  pumps                          18 fOOP
       Condensate system                          1Qfnnn
       Water treating system                     16,000
       Chemical  feed                              2.000
       Coal  handling system                   	N.A.
       Ash disposal system                    	N.A.
       Thawing equipment                       	N.A.
       Fuel-oil  system                           Q7rnnn

 N.A.  - Not  applicable.
                            C-37

-------
  TABLE C-25. .(.continued)
 INSTALLATION COSTS, DIRECT  (cont.)

      Foundations and supports
      Ductwork (not incl. w/boiler)
      Piping
      Insulation
      Painting
      Electrical
      Buildings
                              i
      Total installation cost

 TOTAL DIRECT COSTS
  (equipment + installation)

 INSTALLATION COSTS, INDIRECT

      Engineering
       (10% of direct costs)
      Construction and field expense
       (10% of direct costs)
      Construction fees
       (10% of direct costs)
      Start-up (2% of direct costs)
      Performance tests  (minimum $2000)

 TOTAL INDIRECT COSTS

 Contingencies
  (20% of direct and indirect costs)

 Total Turnkey Costs
   (direct+indirect+contingencies)

 Land

 Working capital (25% of total direct
  operating costs)

 GRAND TOTAL
  (turnkey+land+work}.ng capital)
    264,000
    	N.A.
    156,000'
    100,000
     13,000
    272,000
    520,000
 $3.304,000
 $7.362.400
 $  736.200

    736.200

    736.200
    147,200
     13,000

 $2.368.800


 $1.946.200


 11.677.400

      2.000


  1 .700.500/1.194,600


fti if-37Q, gnn/12,874 ,000
a Based on quote from Babcock & Wilcox, Inc., August 17, 1978

N.A. - Not applicable.
                             C-38

-------
TABLE C-26.  ESTIMATED ANNUALIZED COSTS OF A DUAL-FUEL, FIELD-
   ERECTED, WATER-TUBE BOILER FIRING DISTILLATE OIL/NATURAL
             GAS WITH A THERMAL INPUT OF 117.2 MW
           (400 x 106 Btu/h; 750 psig/750°F design)
DIRECT COST

     Direct labor
     Supervision
     Maintenance labor
     Maintenance materials
     Replacement parts
     Electricity
     Steam
     Cooling water
     Process water
     Fuel
     Bottom ash disposal
     Chemicals

     Total direct cost

OVERHEAD

     Payroll  (30% of direct  labor

     Plant  (26% of  labor, parts  & maint.)

     Total overhead costs

BY-PRODUCT CREDITS

CAPITAL CHARGES

     G & A, taxes & insurance
       (4% of  total  turnkey costs)

     Capital  recovery  factor
       (10.14  % of total turnkey  costs)

     Interest on working capital
       (10% of working  capital)

          Total capital charges

TOTAL  ANNUALIZED COSTS

a Included with replacement  parts.
N.A. - Not applicable.
                                                $   473.800
                                                    136r90Q
                                                    128.200
                                                  	a	
                                                    150,000
                                                    110,000
                                                  	N.A.
                                                  	N.A.
                                                      5,600
                                                  5,781,600/3,758,800
                                                  	N.A.
                                                     16.000
                                                S 6.802.100/4,778.500
                                                    142.100
                                                    231.100
                                                    373 .200
                                                       N.A.
                                                         i nn
                                                  1.184.100


                                                     170. inn/119. 5QQ

                                                 $ lrB21. 300/1. 770. 700

                                                 $ a
                              C-39

-------
 TABLE C-27.   ESTIMATED CAPITAL COSTS OF A DUAL-FUEL, FIELD-
   ERECTED WATER-TUBE BOILER FIRING DISTILLATE OIL/NATURAL
            GAS WITH A THERMAL INPUT OF 205.1 MW
          (700 x 106 Btu/h;  900 psig/750°F design)
CAPITAL COSTS
DATE OF ESTIMATE   June 30. 1978	(FOR COSTS INDEXING)
     EQUIPMENT COSTa

      Boiler (with fans & ducts)             S  4r419.0QQ
      Stack                                      900,000
      Instrumentation                            4flgfnnn
      Pulverizers                            	N.A.
      Feeders                                _ N.A.
      Crushers                               _ N.A.
      Deaerators                                  85.000
      Heaters                                _ N.A.
      Boiler feed pumps                          195,000
      Condensate systems                     _ 35.000
      Water treating system                       90.000
      Chemical feed                          _ 4.000
      Compressed air system                  _ 30 ,000
      Coal handling system                   _ N.A.
      Ash disposal system                    _ N.A.
      Thawing equipment                      _ N.A.
      Fuel-oil system                            325,000

     Total Equipment Cost                   $ 6.572,000

     INSTALLATION COST, DIRECT

      Boiler (including founda-
       tions and steel)                     $ 2. 455. OOP
      Stack                                  Incl.  w/equip.
      Instrumentation                            128 .000
      Pulverizers                            _ Tq.a .
      Feeders                                _ N.A.
      Crushers                               _ N.A.
      Deaerators                             _ 19f OOP
      Heaters                                _ N.A.
      Boiler feed pumps                      _ 25,000
      Condensate system                      _ 16,000
      Water treating system                  _ 28 , QQQ
      Chemical feed                          _ 2rQQQ
      Coal handling system
      Ash disposal system                    _ N.A.
      Thawing equipment                      _ TJ.A.
      Fuel-oil system                           I65f onn

N.A. - Not applicable.
                           C-40

-------
 TABLE C-27.   (continued)
INSTALLATION COSTS, DIRECT  (cont.)

     Foundations and  supports
     Ductwork  (not  incl. w/boiler)
     Piping
     Insulation
     Painting
     Electrical
     Buildings

     Total installation  cost

TOTAL  DIRECT COSTS
  (equipment +  installation)

INSTALLATION COSTS,  INDIRECT

     Engineering
       (10% of  direct costs)
     Construction  and field expense
       (10% of  direct costs)
     Construction  fees
       (10% of  direct costs)
     Start-up  (2%  of direct costs)
     Performance tests (minimum $2000)

TOTAL  INDIRECT COSTS

Contingencies
  (20%  of direct and indirect  costs)

Total  Turnkey  Costs
   (direct+indirect+contingencies)

Land

Working capital (25% of  total direct
  operating costs)

GRAND  TOTAL
  (turnkey+land+working capital)
    484,000
       N.A.
    279,000
    165.000
     22.000
    520.000
    930.000
        nnn
$11.810,000
$ 1,181,000

  1.181.000

  1.181.000
    236,200
     16,000

$ 3.795.200


$ 3.121.000


 18.726.200

      2.000


  2.881.200/1.995.900


$21,609,400/20,724,100
  Based on quote from Babcock & Wilcox, Inc., August 17, 1978

N.A. - Not applicable.
                             C-41

-------
TABLE C-28.  ESTIMATED ANNUALIZED COSTS OF A DUAL-FUEL, FIELD-
   ERECTED, WATER-TUBE BOILER FIRING DISTILLATE OIL/NATURAL
             GAS WITH A THERMAL INPUT OF 205.1 MW
           (700 x 106 Btu/h; 900 psig/750°F design)
   DIRECT COST

        Direct labor
        Supervision
        Maintenance labor
        Maintenance materials
        Replacement parts
        Electricity
        Steam
        Cooling water
        Process water
        Fuel
        Bottom ash disposal
        Chemicals

        Total direct cost

   OVERHEAD

        Payroll  (30% of direct labor

        Plant (26% of labor, parts & maint.)

        Total overhead costs

   BY-PRODUCT CREDITS

   CAPITAL CHARGES

        G & A, taxes & insurance
          (4% of total turnkey costs)

        Capital recovery factor
          (10.14 * °f total turnkey costs)

        Interest on working capital
          (10% of working capital)

             Total capital charges

   TOTAL ANNUALIZED COSTS
     605.400
     136.900
     224.300
    225.000
    180.600
  	N.A.
  	N.A.
      9.700
 10.117.800/6.576.600
  	N.A.
  	25.000
Sll.524.700/7.983.500
    181.600
    309.800
       ./inn
       M.A.
        nnn
  1.898 .800


    288,100/199.600

$ 2.935.900/2,847.400

S14. 952 r 000/11. 322. 300
   a Included with replacement parts
   N.A. - Not applicable.
                             C-42

-------