EAB CONTROL COST MANUAL

               (Third Edition)
              EPA 450/5-87-001A
     U.S. Environmental  Protection Agency
         Office of Air and Radiation
 Office of Air Quality Planning and Standards
           Economic Analysis Branch
Research Triangle Park,  North Carolina  27711
                February 1987

-------
                             NOTE:
A preliminary draft of this Manual  was distributed  in November 1986.
Since then, extensive revisions have been made to Section 5 ("Fabric
Filters") and minor changes to Sections 3 ("Thermal  and Catalytic
Incinerators") and 4 ("Carbon Adsorbers").  No revisions were made  to
Sections 1 and 2, however.

The pages in this Manual  have been  fastened together.  If desired,
they may be unfastened, hole-punched, and reassembled in a three-ring
binder.  This will facilitate the addition of updates when they become
available.

-------
                      OVERVIEW OF THE  MANUAL*
Completion
Section Date
1 INTRODUCTION 1/86
2 MANUAL ESTIMATING METHODOLOGY 1/86
3 THERMAL AND CATALYTIC INCINERATORS 7/86
4 CARBON ADSORBERS 7/86
5 FABRIC FILTERS 9/86
6 ELECTROSTATIC PRECIPITATORS
7 DUCTWORK
8 FANS
9 FLARES
10 REFRIGERATION UNITS
11 STACKS
12 PUMPS
13 GAS ABSORBERS
14 VENTURI SCRUBBERS
15 WASTEWATER TREATMENT FACILITIES**
16 CAPTURE HOODS
17 MECHANICAL COLLECTORS
18 PRECOOLERS (SPRAY CHAMBERS AND QUENCHERS)
19 SCREW CONVEYORS
20 COMPREHENSIVE SAMPLE COST-ESTIMATING PROBLEMS
21 ESCALATING COSTS
APPENDIX A COMPOUND INTEREST FACTORS
APPENDIX B EQUIPMENT COST INDICIES
APPENDIX C CONTROL EQUIPMENT VENDORS
Date To Be
Completed





FY 87
FY 87
FY 87
FY 87
FY 87
FY 88
FY 88
FY 88
FY 88
FY 88
Not Established
Not Established
Not Established
Not Established
Not Established
Not Established
Not Established
Not Established
Not Established
 *For more information about the Manual,  contact Albert Wehe,  Robert  Pahel-
  Short, or William Vatavuk (at FTS:629-5610).
**These are facilities that would be required to treat only the wastewater
  generated by venturi scrubbers, quenchers,  spray chambers,  and gas  absorbers.

-------
                            TABLE OF CONTENTS
                 Section
1      INTRODUCTION
  1.1  Role of Cost in the Setting of Regulations              1-1
  1.2  Purpose of Manual                                       1-2
  1.3  Organization of the Manual                              1-2
  1.4  "Uniqueness" of the Manual                              1-5
  References for Section  1                                    1-7
2      MANUAL ESTIMATING  METHODOLOGY
  2.1  Types of Cost Estimates                                2-1
  2.2  Cost Categories Defined                                2-3
       2.2.1  Elements of Total  Capital  Investment             2-3
       2.2.2  Elements of Total  Annual  Cost                    2-7
  2.3  Engineering Economy Concepts                           2-9
       2.3.1  Time Value  of Money                              2-9
       2.3.2  Cash Flow                                       2-9
       2.3.3  Annualization Methods                           2-14
  2.4  Estimating Procedure                                   2-15
       2.4.1  Facility Parameters  and Regulatory Options       2-15
       2.4.2  Control  System Design                           2-17
       2.4.3  Sizing the  Control System                       2-18
       2.4.4  Estimating  Total Capital  Investment              2-20

-------
                            TABLE OF CONTENTS
                 Section                                     Page
2 (Cont'd)
       2.4.5  Retrofit Cost  Considerations                    2-23
       2.4.6  Estimating Annual Costs                         2-25
  References for Section 2                 .                   2-33

3      THERMAL AND CATALYIC  INCINERATORS
  3.1  Process Description                                    3-1
       3.1.1  Elements of Combustion                          3-1
       3.1.2  Types of Incinerators                           3-6
  3.2  Design Procedure                                      3-8
       3.2.1  Design and Operating Features                   3-8
       3.2.2  Design Calculations                     '        3-10
  3.3  Estimating Total Capital Investment                    3-23
       3.3.1  Thermal  Incinerator Equipment Costs             3-24
       3.3.2  Catalytic Incinerator Equipment Costs           3-27
       3.3.3  Total  Capital  Investment for Incinerators       3-29
  3.4  Estimating Total Annual Cost                           3-30
       3.4.1  Direct Annual  Costs                             3-30
       3.4.2  Indirect Annual Costs                           3-34
  References for Section 3                                    3-35
  Appendix 3A
  Appendix 3B

-------
                            TABLE OF  CONTENTS
              Section
4      CARBON ADSORBERS
  4.1  Process Description                                   4-1
       4.1.1  Introduction                                   4-1
       4.1.2  Types of Adsorbers                             4-2
       4.1.3  Adsorption Theory                              4-6
  4.2  Design Procedure                                      4-11
       4.2.1  Sizing Parameters                              4-11
       4.2.2  Determining Adsorption  and  Desorption Times     4-13
       4.2.3  Estimating Carbon Requirement                   4-15
  4.3  Estimating Total Capital Investment                    4-20
       4.3.1  Fixed-Bed Systems                              4-21
       4.3.2  Cannister Systems                              4-26
  4.4  Estimating Total Annual  Cost                           4-28
       4.4.1  Direct Annual  Costs                            4-28
       4.4.2  Indirect Annual  Costs                           4-34
       4.4.3  Recovery Credits                               4-35
       4.4.4  Total Annual Cost                              4-36
  References for Section 4                                   4-37

-------
                            TABLE OF CONTENTS

    	Section	                          Page
5      FABRIC FILTERS
  5.1  Process Description                                    5-1
       5.1.1  Introduction                                    5-1
       5.1.2  Types of Fabric Filters                         5-2
       5.1.3  Auxiliary Equipment                             5-5
       5.1.4  Fabric Filtration Theory                        5-7
  5.2  Design Procedures                                      5-15
       5.2.1  Gas-to-Cloth Ratio                              5-15
       5.2.2  Pressure Drop                                   5-23
       5.2.3  Particle Characteristics                        5-24
       5.2.4  Gas Stream Characteristics                       5-25
       5.2.5  Pressure or Suction Housings                    5-27
       5.2.6  Standard or Custom Construction                 5-28
       5.2.7  Filter Media                                    5-29
  5.3  Estimating Total Capital Investment                    5-30
       5.3.1  Equipment Cost                                  5-30
       5.3.2  Total Purchased Cost                            5-40
       5.3.3  Total Capital Investment                        5-41
  5.4  Estimating Total Annual Costs      '                    5-41
       5.4.1  Direct Annual Cost                              5-41
       5.4.2  Indirect Annual Cost                            5-46
       5.4.3  Recovery Credits                                5-47
       5.4.4  Total Annual  Cost                               5-47
       5.4.5  Example Problem                                 5-48
  References for Section 5                                    5-54

-------
                                Section 1
                               INTRODUCTION
                             William M. Vatavuk
                      Economic Analysis Branch, OAQPS

1.1  Role of Cost in  the  Setting of Regulations
     Cost has an important  role in setting many state and federal air
pollution control regulations.  The extent of this role varies with the
type of regulation.   For  some types of regulations, cost is expl icitly used
in determining their  stringency.  This use may involve a balancing of costs
and environmental impacts,  costs and dollar valuation of benefits, or
environmental impacts and economic consequences of control costs.
     For other types  of regulations cost analysis is used to choose among
alternative regulations with the same level of stringency.  For these
regulations, the environmental goal is determined by some set of criteria
which do not include  costs.  However, cost-effectiveness analysis is employed
to determine the minimum  cost way of achieving the goal.
     For some regulations,  cost influences enforcement procedures or
requirements for demonstration of progress towards compliance with an air
quality standard.  For example, the size of any monetary penalty assessed
for noncompliance as  part of an enforcement action needs to be set with
awareness of the magnitude  of the control costs being postponed by the non-
complying facility.   For  regulations without a fixed compliance schedule,
demonstration of reasonable progress towards the goal is sometimes tied to
the cost of attaining the goal on different schedules.
     Cost is a vital  input  into two other types of analyses that also
sometimes have a role in  standard setting.  Cost is needed for a benefit-cost
analysis that addresses the economic efficiency of alternative regulations.

-------
                                    1-2
Cost is also an input into any analysis of the economic  impact  of  each
regulatory alternative.  An economic impact analysis  deals  with the  consequences
of the regulation for small  businesses, employment, prices,  and industry
structure.
1.2    Purpose of Manual
     The purpose of this Manual  is two-fold:   (1)  to  compile up-to-date
capital costs, operating and maintenance expenses, and other costs for
"add-on" air pollution control  systems and (2) to  provide a  comprehensive,
concise, consistent, and easy-to-use procedure for estimating and  (where
appropriate) escalating these costs.  ("Add-on" systems  are  those  installed
downstream of an air pollution source to control its  emissions.)
     The Manual estimating procedure rests on the  notion of  the "factored" or
"study" estimate, nominally accurate to within +_ 30%.  This  type of  estimate
is well suited to estimating control system costs  intended  for  use in
regulatory development.  Study estimates are sufficiently accurate,  yet do
not require the detailed, site-specific data inputs needed  to make "definitive"
or other more accurate types of estimates.
1.3    Organization of the Manual
     This Manual is a major revision of the 1978 edition of  the EAB  Control
Cost Manual,U) which, in turn,  was a revision of  the original  edition,
completed in 1976.  This third edition of the Manual  includes a more thorough
discussion of estimating methodology and more detailed design procedures
for an enlarged set of equipment types.  The appendices  have been  revised
to delete some infrequently used material, and to  include certain  new and
more useful material.
     The format of the Manual  has been changed to  one which  will permit more
flexibility in its updating and expansion.  To achieve this  flexibility

-------
                                  1-3
this edition will  be issued  in self-contained sections.  Each section will
address a logically separate topic, which can be either of a general nature
(e.g., this introduction)  or of a more specific, equipment-oriented nature
(e.g., fabric filters).  The sections which comprise this portion of the
Manual are listed  in Table 1-1, alongside the sections in the 1978 Manual
they will replace.
     Two changes in the  1978 Manual are indicated by Table 1-1.  First,
the numbering scheme is  different.  In the third edition, each type of
equipment, background topic, etc., is given its own number, for ease of
identification and to reinforce the intent that each section should "stand
alone".  Second, the auxiliary equipment items (e.g., ductwork), which were
collected into a single  chapter in the previous Manuals, are now also stand-
alone sections.  This was  mainly done to eliminate the confusion that arises
when classifying auxiliaries like mechanical collectors which can either
support a primary control  device or be control devices in their own right.
     The notion of a stand alone section is also new.  Where in the 1976
and 1978 Manuals,  the various capital and annual cost factors were collected
in an introductory section (old Section 3), now they are dispersed among the
sections covering the equipment types.  Each of these sections contains a:
     o  Process description, where the types, uses, and operating modes of
        the equipment item and (if applicable) its auxiliaries are discussed;
     o  Design procedure,  which enables one to use the parameters of the
        pollution source (e.g., gas volumetric flowrate) to size the equipment
        item(s) in question;
     o  Capital and annual costs for the equipment and suggested factors to
        use in estimating  these costs from equipment design and operational

-------
Table 1-1  Format of the EAB Control  Cost  Manual  (Third Edition)
Number
1
2
3
4
5

New Section
Title
"Introduction"
"Manual Estimating Methodology"
"Thermal and Catalytic Incinerators"
"Carbon Adsorbers"
"Fabric Filters"
(Other sections to be developed)
Number(s)
1
2,3
5.4
5.5
5.3

Old Section(s) Replaced
Title
"Introduction"
"Application to Industry"; "Cost Estimating
Procedures"
"Thermal and Catalytic Incinerator Systems"
"Adsorbers"
"Fabric Filters"


-------
                                  1-5

        (e.g., operating  hours) parameters.  These costs are presented in
        both graphical  and  equational forms wherever possible.
1.4   "Uniqueness"  of the Manual
        The Manual  presents a  different perspective on estimating air pollution
control  system costs  than other cost-oriented reports, such as:
     o  The Cost Digest:  Cost Summaries of Selected Envi ronmental Control
        Technologies^)
     o  A Standard  Procedure for Cost Analysis of Pollution Control Operations^)
     o  Evaluation  of Control  Technologies for Hazardous Air Pollutants^4)
     Although these reports (as well as many of the NSPS Background
Information Documents)  contain costs for add-on control systems, they do
not duplicate the Manual  for one or more of the following reasons:  (1)
their costs have been based either wholly or partly on data in the previous
Manuals; (2) they apply to  specific source categories only, whereas the
Manual data may be  applied  generally; (3) their estimating procedures and
costs are of less than  study estimate quality; or (4) they are not intended for
estimating costs used in  regulatory development.
     Reason (3) applies to  the Cost Digest, for example, as this report,
designed for use by non-technical personnel, contains procedures for making
"order-of-magnitude"  estimates (+_ 30% accuracy or worse).  A Standard Procedure,
conversely, was primarily intended for estimating costs for R&D cases (e.g.,
demonstration projects),  where some site-specific data are available.  Further,
although the latter report  contains a thorough list of equipment installation
factors, it contains  few  equipment costs.  The report, Evaluation of Control
Technologies, used  data and estimating procedures from the 1978 Manual  to
provide sound generalized procedures for estimating thermal  and catalytic

-------
                                   1-6
incinerator costs.  The third edition of the Manual  updates  and expands
this information.
     Finally, the second edition of the Manual  (published December 1978),
was one of the earliest of its kind.   It has been  extensively  used in
Agency regulatory development efforts.   Accordingly,  the Manual 's role in
the speciality of air pollution control  system  cost  estimating  is both
unique and secure.

-------
                                  1-7


References for Section 1:


1.  Neveril,  R. B.  (GARD, Inc.) Capital  and Operating  Costs  for Selected
    Air Pollution Control Systems, EPA,  Office of  Air  Quality  Planning
    and Standards,  Economic Analysis Branch, December  1978  (EPA 450/5-
    80-002).

2.  DeWolf, Glenn,  et al. (Radian, Inc.) The Cost  Digest:  Cost Summaries
    of Selected Environmental Control  Technologies.  EPA, ORD,  Office of
    Environmental Engineering and Technology, October  1984  (EPA-600/884-010).

3.  Vhl, Vincent W. ^ Standard Procedure for Cost  Analysis ^f  Poll ution
    Control Operations, Volumes I and II.  EPA, ORD, Industrial  Environmental
    Research  Laboratory, June 1979 (EPA-600/8-79-018a).

4.  Katari, Vishnu  (Pacific Environmental Services) Evaluation  of  Control
    Technologies for Hazardous Air Pollutants.  EPA, Air and Energy  Engineering
    Research  Laboratory, ORD, October 1985.

-------
                                Section 2
                       MANUAL  ESTIMATING METHODOLOGY
                              William M. Vatavuk
                      Economic Analysis Branch, OAQPS
     This section presents a methodology that will enable the  user,  having
knowledge of the source being  controlled, to produce study-level cost
estimates for a control system to  control that  source.  The methodology,
which applies to each of the control systems included in this  Manual, is
general  enough to be used with other "add-on" systems as well.  Further,
the methodology may also be applicable to estimating costs of  fugitive
emission controls and of other nonstack abatement methods.
     Before presenting this methodology in detail, we should first discuss
the various kinds of cost estimates and then define the cost categories and
engineering economy concepts employed in making the estimates.
2.1  Types of Cost Estimates
     As noted above, the costs and estimating methodology in this Manual
are directed toward the "study11 estimate, of +_ 30% accuracy.   According to
Perry's Chemical  Engineer's Handbook, a study estimate is ".... used to
estimate the economic feasibility  of a project before expending significant
funds for piloting, marketing, land surveys, and acquisition ... [However]
it can be prepared at relatively low cost with minimum data."(l)  Specifically,
to make a study estimate, the  following must be known:
     o  Location of the source within the plant;
     o  Rough sketch of the process flow sheet  (i.e., the relative locations
        of the equipment in the system);
     o  Preliminary sizes of,  and material specifications for, the system
        equipment items;

-------
                                   2-2

     o  Approximate sizes and types of construction  of  any  buildings  required
        to house the control  system;
     o  Rough estimates of utility requirements  (e.g.,  electricity);
     o  Preliminary flow sheet and specifications  for ducting and piping;
     o  Approximate sizes of motors required.(l)
     In addition, an estimate of the  labor hours  required for engineering
and drafting is needed, as the accuracy of an  estimate  (study or otherwise)
is highly dependent on the amount of  engineering work expended on the
project.
     There are, however, four other types of estimates,  three of which
are more accurate than the study estimate. These  are:(l)
     o  "Order-of-magnitude"--"a rule of-thumb procedure applied only to
        repetitive types of plant installations  for  which there exists good
        cost history".  Its accuracy  is >+30%.  (However, according to
        Perry's, "...no limits of accuracy can safely be applied to it.")
        The sole input required  for making this level of estimate is the
        control system's capacity (often measured  by the maximum volumetric
        fl owrate of the gas passing through the system).  So-called "six-
        tenths factor" estimates (not to be confused with factored
        estimates) are examples  of this type.
     o  "Scope'V'Budget authorization"/"Preliminary".  This estimate,
        nominally of _+ 20% accuracy,  requires  more detailed knowledge than
        the study estimate regarding  the site, flow  sheet,  equipment,
        buildings, etc.  In addition, rough specifications  for the insulation
       . and instrumentation are  also  needed.

-------
                                  2-3

     o  "Project control "/"Definitive" estimates, accurate to within + 10%,
        require yet  more information than the scope estimates, especially
        concerning the site,  equipment, and electrical  requirements.
     o  "Firm"/"Contractor's"/"Detai1ed".  This is the  most accurate (+_ 5%)
        of the estimate types,  requiring complete drawings, specifications,
        and site surveys.  Further, "[t]ime seldom permits the preparation
        of such estimates prior to an approval to proceed with the project."^)
     For the purposes  of regulatory development, study  estimates have been
found to be acceptable, as they represent a compromise  between the less
accurate "order-of-magnitude" and the more accurate estimate types.  The
former are too imprecise to be  of much value, while the latter are not only
very expensive to make, but require detailed site and process-specific
knowledge that most  Manual  users will not have available to them.
2.2  Cost Categories Defined
     The names given certain  "categories" of costs and  what they contain
vary considerably throughout  the literature.  Certain words like "capital
cost" can have vastly  different meanings, which can often lead to confusion,
even among cost estimators.  To avoid this confusion and, at the same time,
provide uniformity in  the Manual , basic terms are defined in this Section
and will  be used throughout.  The terminology used is adapted from that of
the American Association of Cost Engineers^).  Although it has been
developed for general  use,  it is readily adaptable to air pollution control
system costing.
2.2.1  Elements of Total  Capital Investment
     First, two general  kinds of costs are estimated, total capital investment
(TCI) and total annual  cost (TAC).  The total capital investment includes

-------
                                   2-4

all  costs required to purchase equipment needed for the control  system
(termed "purchased equipment" costs), the costs of labor and materials for
installing that equipment (termed "direct installation" costs),  site
preparation, building costs, and certain other costs which are termed
"indirect installation" costs.  Direct installation costs include  costs for
foundations and supports, erecting and handling the equipment, electrical
work, piping, insulation, and painting.   Indirect  installation costs include
such costs as engineering costs; construction and  field expenses (i.e.,
costs for construction supervisory personnel, office personnel,  rental  of
temporary offices, etc.); contractor fees (for construction and  engineering
firms involved in the project);  start-up and performance test costs  (to get
the control  system running and to verify that it meets performance guarantees);
and contingencies.  Contingencies is a catch-all category that covers  unfore-
seen costs that may arise, including (but certainly not limited  to)  "...
possible redesign and modification of equipment, escalation increases  in
cost of equipment, increases in  field labor costs, and delays encountered
in start-up."(2)
     These elements of total capital  investment are displayed in Figure
2-1.  Note that the sum of the purchased equipment cost, direct  and
indirect installation costs, site preparation, and buildings costs
comprise the battery limits estimate.  By definition,  this is the  total
estimate "... for a specific job without regard to required supporting
facilities which are assumed to  already exist..."(2) at the plant. This
would mainly apply to control systems installed in existing plants, though
it could also apply to those systems installed in  new plants when  no special
facilities for supporting the control system would be required.

-------
                             Figure 2-1
                                             Elements of Total  Capital  Investment
o Primary Control Device
o Auxiliary Equipment
    (including ductwork)
o Instrumentation3
o Sales Taxes3
o Freight3
o Foundations and Supports
o Handling and Erection
o Electrical
o Piping
o Insulation
o Painting
                              Purchased
                             •Equipment
                              Cost
            Land6

            Working Capital6
Total
Nondepreciable
Investment
o Engineering
o Construction and Field
    Expenses
o Contractor Fees
o Start-up
o Performance Test
o Contingencies
                              Direct
                             -Installation
                              Cost0

                              Site Preparation0

                              Buildingsd
                               Indirect
                               Installation
                               Costb
Total
Direct
Cost
 Total
 Indirect
 Cost
                                                                "Battery
                                                                 Limits"
                                                                 Cost
                                                                Off-Site
                                                                fac1Htes6
Total
Depreciable
Investment
                                                    Total
                                                    Capital
                                                    Investment
                                ro

                                en
a
b
c
d
These costs are factored from the sum of the control  device  and  auxiliary equipment costs.
These costs are factored from the purchased equipment cost.
Usually required only at "grass roots" installations.
Unlike the other direct and indirect costs, costs  for these  items  are not factored from the purchased equipment
cost.  Rather, they are sized and costed separately.
Normally not required with add-on control  systems.

-------
                                   2-6

     Where required, these supporting facilities  would  encompass units to
produce steam, electricity,  and  treated  water;  laboratory buildings, railroad
spurs, roads, and the like.   It  is unusual,  however,  for a  control system
to have one of these units (e.g.,  a power plant)  dedicated  to it.  The
system needs are rarely that great.  However,  it  may  be necessary—especially
in the case of control  systems  installed in  new or  "grass roots" plants--
for extra capacity to be built  into the  site generating plant to service
the system.  (A venturi  scrubber,  which  often  requires  large amounts of
electricity, is a good example  of  this.)  It is customary for the utility costs
to be charged to the project as  operating costs at  a  rate which covers both
the investment and operating costs for the utility.
     As Figure 2-1 shows,  there  are two  other  costs which may be included
in the total capital investment  for a control  system.   These are "working
capital", and "land".  The first of these, working  capital, is a fund set
aside to cover the initial  costs of fuel, chemicals,  and other materials,
as well as labor and maintenance.   It usually  does  not  apply to control
systems, for the quantities  of  utilities, materials,  labor, etc., they
require are usually small.  (An  exception might be  an oil-fired thermal
incinerator, where a small  supply  (e.g., 30-day)  of distillate fuel would
have to be available during  its  initial  period  of operation.)
     Land may also be required.  But, since  most  add-on control systems
take up very little space  (a quarter-acre or less)  this cost would be
relatively small.  (Certain  control  systems, such as  those  used for flue
gas desulfurization, require larger quantities  of land  for  the process
equipment, chemicals storage, and  waste  disposal.)

-------
                                  2-7

     Note also in Figure 2-1  that the working capital and land are
"nondepreciable" expenses.   In  other words, these costs are  "recovered"
when the control system reaches the end of its useful life (generally in 10
to 20 years).  Conversely,  the  other capital costs are "depreciable", in
that they cannot be recovered and are included in the calculation of the
income tax credit and depreciation allowance, whenever such  taxes are
considered in a cost  analysis.  (In the Manual methodology,  however,
income taxes are not  considered.  See Section 2.3.)
     Notice that when 100%  of the system costs are depreciated, m> salvage
value is taken for the system equipment at the conclusion of its useful life.
This is a reasonable  assumption for add-on control systems,  as most of the
equipment, which is designed  for a specific source,  cannot be used elsewhere
without modifications.  Even  if it were reusable, the cost of disassembling
the system into its components  could be as high  (or  higher)  than the salvage
value.
2.2.2  Elements of Total  Annual Cost
     The Total Annual Cost  (TAG) for control systems is comprised of three
elements:  "direct" costs,  (DC) "indirect" costs, (1C) and "recovery credits"
(RC), which are related by  the  following equation:

     TAC = DC H- 1C -  RC                                            (2-1)
Clearly, the basis of these costs is one year, as this period allows for
seasonal variations in production (and emissions generation) and is directly
usable in profitability analyses.  (See Section 2.3.)
     Pi rect costs are those which tend to be proportional or partially
proportional to the quantity  of exhaust gas processed by the control system
per unit time.  These include costs for raw materials, utilities (steam,

-------
                                   2-8

electricity, process and cooling water, etc.). waste treatment and disposal,
maintenance materials, replacement parts, and operating,  supervisory,  and
maintenance labor.  Of these direct costs, costs for raw  materials, utilities,
and waste treatment and disposal are variable, in that they tend to be a
direct function of the exhaust flowrate.  That is, when the flowrate is at
its maximum rate, these costs are highest.  Conversely, when the flowrate
is zero, so are the costs.
     Semi variable direct costs are only partly dependent  upon the exhaust
flowrate.  These include all  kinds of labor, maintenance  materials, and
replacement parts.  Although these costs are a function of the gas flowrate,
they are not 1 inear functions.  Even while the control  system is not
operating, some of the semi variable costs continue to be  incurred.
     Indirect,  or "fixed", annual  costs are those whose values are totally
independent of the exhaust flowrate and, in fact, would be incurred even if
the control  system were shut down.  They include such categories as overhead,
property taxes, insurance, and capital  recovery.
     Finally, the direct and indirect annual  costs are offset by recovery
credits, taken for materials or energy recovered by the control  system,
which may be sold, recycled to the process, or reused elsewhere at the
site.  These credits, in turn, must be offset by the costs necessary for
their purification, storage,  transportation, and any other costs required
to make them reusable or resalable.  Great care and judgement must be
exercised in assigning values to recovery credits since materials  recovered
may be of small quantity or of doubtful purity, resulting in their having less
value than virgin material.

-------
                                  2-9
     The various annual  costs  and their interrelationships are displayed  in
Figure 2-2.   A more thorough description of these costs and how they may
be estimated is given in Section 2.4.
2.3  Engineering Economy Concepts
     As mentioned previously,  the estimating methodology presented in
Section 2.4  rests upon the  notion of the "factored" or study estimate.
However, there are other concepts central to the cost analyses which must
be understood.  These are (1)  the time value of money, (2) cash flow, and
(3) annualization.
2.3.1  Time  Value of Money
     The "time value of money" is based on the truism that "...a dollar now
is worth more than the prospect of a dollar... at some later date."(3)
A measure of this value is  the interest rate which "...may be thought of  as
the return obtainable by the productive investment of capital."(3)
2.3.2  Cash  Flow
     During  the lifetime of a  project, various kinds of cash expenditures
are made and various incomes are received.  The amounts and timing of these
expenditures and incomes constitute the cash flows for the project.  In
control system costing it is normal to consider expenditures (negative cash
flows) and unusual to consider income (positive cash flows), except for
product or energy recovery  income.  By the simplifying convention recommended
by Grant, Ireson, and Leavenworth(4), each annual expenditure (or payment)
is considered to be incurred at the end of the year, even though the payment
will probably be made sometime during the year in question.  (The error
introduced by this assumption  is minimal, however.)  Figure 2-3, which
sh6ws three  hypothetical  cash  flow "diagrams", illustrates these end-of-
year payments.  In these diagrams, "P" represents the capital investment,

-------
                                        2-10
                      Figure  2-2   Elements of Total Annual Cost
o  Raw materials
o  Utilities
   -  Electricity
   -  Steam
   -  Water
   -  Others
      Variable
o  Labor
   -  Operating
   -  Supervisory
   -  Maintenance
o  Maintenance materials
o  Replacement parts
      •Semi variable
                      Di rect
                      Annual
                      Costs
                     o  Overhead
                     o  Property  Taxes
                     o  Insurance
                     o  Capital Recovery
                     o
                     o
Materials
Energy
                      Indirect
                      Annual
                      Costs
Recovery
Credits
                           Total
                           Annual
                           Cost

-------
                                 Figure 2-3       Hypothetical  Cash  Flow Diagrams
I.   P
II.  P
                                   All Values Are Constant Year (Real)  Dollars
                                  34567
8
10  Year
1 J I
A!I A2r A3j. A4
1 Y \
?
A5
?
\
f
A7
f
\
AS Ag
{
A10
P
1
A
i
A
, i
A,
A
\
A,
A
i
A
*• <
f
A
f \

*
A

                                                                                                     10  Year
III.
                                                                       .7
                  10   Year
i
i
.1
i
. A11
r >
, Al,
. Al,
, 1
' 1

-------
                                   2-12

while the A's denote the end-of-year annual  payments.   Note  that  in all
diagrams, the cash flows are in "constant"  ("real")  dollars, meaning that
they do not reflect the effects of inflation.   Also  note  that  in  the top
diagram (I), the annual payments are different  for each year.   (These
represent the control  system annual  costs (exclusive of capital  recovery)
described in Section 2.2.)  In reality, these payments  would be different,
as labor and maintenance requirements,  labor and  utility  costs, etc., would
vary from year to year.  A generally upward  trend in annual  costs would be
seen, however.
     In diagram II, these fluctuating annual payments have been converted
to equal  payments.  This can be done by calculating  the sum  of  the present
values of each of the annual payments shown  in  diagram  I  and annualizing
the total  net present value to equivalent equal annual  payments via a capital
recovery factor.  (See discussion in the following paragraphs  and in Section
2.3.3.)  Alternatively, it is adequate  to choose  a value  of  A equal to the
sum of the direct and indirect annual  costs  estimated for the  first year.
This assumption is in keeping with the  overall  accuracy of study  estimates
and allows for easier calculations.
     Finally, notice diagram III.  Here, the annual  costs (A^)  are again
equal, while the capital  investment  (P) is missing.  Put  simply,  P has been
incorporated into A1 so that A1 reflects not only the various  annual costs
but the investment as well.  This was done by introducing another term, the
capital recovery factor (CRF), defined  as follows:   "when multiplied by a
present debt or investment , [the CRF]  gives the  uniform  end-of-year payment
necessary to repay the debt or investment in n  years with interest rate i."(5)
The product of the CRF and the investment (P) is  the capital  recovery cost (CRC):
     CRC = CRF x P                                                 (2-2)

-------
                                  2-13

where:
     CRF = 1(1 + i)n                                                 (2-3)
Therefore, A* is the sum of  A and the CRC, or:
   .  A1 = A + CRF x P                                               (2-4)
     In this context, "n" is the control system economic life, which,
as stated above, typically varies from 10 to 20 years.  The interest rate
("i") used in this Manual  is a real  rate of 10% (annual).  This value is
used in most of the OAQPS cost analyses and is in keeping with current EAB
guidelines^) and the Office of Management and Budget recommendation for use
in regulatory analyses.'^'
     It may be helpful  to illustrate the difference between "real" and
"nominal" interest rates. The mathematical relationship between them is
straightforward: (6)
     (1 + 1n) = (1 + 1)(1 +  r)                                      (2-5)
where:
     inj = the annual  nominal and  real interest rates, respectively
        r = the annual  inflation rate
     Clearly, the "real" rate does  not consider inflation and is in keeping
with the expression of annual  costs in constant (i.e., real) dollars.
     EAB guidelines also recommend  the exclusion of income tax considerations
from cost analyses.(6)   Not  only does this simplify the analysis, but it
also allows for the calculation of  the "economic" costs of air pollution
control--i.e., the true cost to society.  Income taxes generally represent
transfer payments from one segment  of society to another and as such are not
properly part of the economic costs.

-------
                                   2-14

2.3.3  Annual ization Methods
     The above method of "smoothing out"  the investment  into  equal  end-of-
year payments, is termed the "equivalent  uniform annual  cash  flow"  (EUAC)
method.(8)  in addition to its inherent simplicity,  this method  is  very
useful when comparing the costs of two or more alternative  control  systems
(i.e., those which are designed to control  the same  source  to an equivalent
degree).  In fact, the EUAC's--or simply  the total annual costs—of two
competing systems may be compared even if both the systems  have different
economic lives, say 10 and 20 years.  We  recommend that  the EUAC method  be
used for control  cost work unless particular circumstances  preclude its
use.
     Comparisons of systems with differing economic  lives cannot be made,
however, using the other two annualization (i.e., profitability analysis)
methods--"present worth" and "internal rate of return".   The  "present
worth" (or "discounted cash flow") method involves the "discounting" of  all
cash flows occuring after year "0" (i.e., the system startup  date)  back  to
year "0".  These cash flows are discounted by multiplying each by a "discount
factor",    1     , where "m" is the number of years from year 0 to the  year
         (1 + i)m
in which the cash flow is incurred.  The  sum of these discounted cash flows
is then added to the capital  investment to yield  the "present worth" of  the
project.  The alternative having the highest present worth  would be selected
(in control system costing this is usually a negative number).  But when
comparing the present worths of alternative systems, the system lifetimes
must be equal for the comparison to be valid.(9)

-------
                                  2-15

     The third annualization  method, "internal  rate of return"  (IRR),  is
similar to the present worth  method, in that  it  involves the discounting  of
a series of unequal  cash  flows.  However, where with the PW method the
interest rate, "i",  is set  beforehand, in the IRR method the interest  rate
is solved for (usually via  trial-and-error) after arbitrarily setting  the
PW to zero.  When comparing alternative systems, the one with the highest
IRR is selected.(10) But  again, the alternative systems compared must  have
equal  economic lives.
2.4  Estimating Procedure
     The estimating  procedure used in the Manual consists of five steps:
(1)  obtaining the "facility  parameters" and  "regulatory options" for  a
given facility; (2)  "roughing out" the control  system design; (3) sizing
the control system components;  (4) estimating the costs of these individual
components; and (5)  estimating the costs (capital and annual ized) of the
enti re system.
2.4.1  Facility Parameters  and  Regulatory Options
     Obtaining the facility parameters and  regulatory options involves
not only assembling  the parameters of the air pollution source  (i.e.,  the
quantity, temperature, and  composition of the emission stream(s)),
but also compiling data for the facility's  operation.  (Table 2-1 lists
examples of these.)   Note that  two kinds of facility parameters are identi-
fied -- "intensive"  and "extensive".  The former are simply those variables
whose values are independent  of quantity or dimensions — i.e., the "extent"
of the system.  Conversely, "extensive" parameters encompass all size-dependent
variables, such as the gas  volumetric flowrate.

-------
                                    2-16

         Table 2-1   Facility Parameters and Regulatory Options

                            FACILITY PARAMETERS

     Intensive
       -  Facility status (new or existing,  location)
       -  Gas characteristics (temperature,  pressure,  moisture  content)
       -  Pollutant concentration(s) and/or  particle size distribution
     Extensive
       -  Facility capacity
       -  Facility life
       -  Gas flow rate
       -  Pollutant emission rate(s)
                             REGULATORY  OPTIONS
o    No control
o    "Add-on" devices
       -  Emission 1imits
       -  Opacity    "
o    Process modifications
       -  Raw material changes
       -  Fuel substitution
o    Others
       -  Coal desulfurization

-------
                                   2-17

     Like the facility parameters,  the "regulatory options" are  usually
specified by others.   These options are ways  to  achieve  a  predetermined
emission limit.  They range from  "no control" to maximum control  technically
achievable.  The option provided  will depend, firstly, on  whether the
emission source is a  stack  (point source),  a  process leak  ("process  fugitives"
source) or an unenclosed (or partly closed) area, such as  a storage  pile
("area fugitives" source).   Stacks  are normally  controlled by  "add-on"
devices.  As discussed above,  this  Manual will deal primarily  with these
add-on devices.  (However,  some of  these devices can be  used to  control
process fugitives in  certain cases, such as a fabric filter used in  conjunction
with a building evacuation  system.)  Add-ons  are normally  used to meet  a
specified emission level, although  in the case of particulate  emissions,
they may also be required to meet an opacity  level.
2.4.2  Control  System Design
     Step 2 — roughing out the control system design -- first involves
deciding what kinds of systems will  be priced (a decision  that will  depend
on the pollutants to  be controlled, gas stream conditions, and other factors),
and what auxiliary equipment will  be needed.  When specifying  the auxiliary
equipment, several questions need to be answered:
     o  What type of  hood  (if any)  will be  needed to capture the emissions
        at the source?
     o  Will a fan be needed to convey the  exhaust through the system?
     o  Is a cyclone  or another pre-cleaner needed to condition  the  exhaust
        before it enters the control  device?
     o  Will the captured pollutants be disposed of or recycled?  How will
        this be done?

-------
                                   2-18

     o  Can the on-site utility capacity (e.g., electricity)  accomodate  the
        added requirements of the control  system?
     The kinds of auxiliary equipment selected will  depend  on the  answers
to these and other site-specific questions.   However,  regardless of the
source being controlled, each system will  likely contain, along with the
control device itself, the following auxiliaries:
     o  Hood, or other means for capturing the exhaust;
     o  Ductwork, to convey the exhaust from the source, to,  through, and
        from the control system;
     o  Fan system (fan, motor, starter,  inlet/outlet  dampers, etc.), to
        move the exhaust through the system;
     o  Stack, for dispersing the cleaned  gas into the atmosphere.
2.4.3  Sizing the Control  System
     Once the system components have been  selected,  they must be sized.
Sizing is probably the most critical  step, because the assumptions made  in
this step will more heavily influence the  capital  investment  than  any other.
Before discussing how to size equipment, we  need to  define  the term.  For
the purposes of this Manual, "sizing" is the calculation (or  estimation) of
certain "critical" design  parameters for   a  control  device  against which
the purchased cost of that device is most  accurately correlated.  For
instance, the purchased cost of an electrostatic precipitator (ESP) is most
often correlated with its  collecting area.  This,  in turn,  is a function
of the exhaust volumetric  flowrate,  the overall  collection  efficiency and
the empirically-determined drift velocity, the ESP "critical" parameter.
(Table 2-2 lists examples  of these parameters.)

-------
                                  2-19

        Table 2-2   Examples of Typical Control Device Parameters'H'

                                 GENERAL

        Material of construction:  e.g., carbon steel
        Insulated?   Yes
        Economic life:  20 yr
        Redundancy3:   none

                             DEVICE-SPECIFIC

        Air-to-cloth ratio ("critical parameter"):  7.5 to 1
        Pressure drop:  6.0 in w.g. (inches water gauge)
        Construction:  suction (vs. pressurized)
        Duty:   continuous (vs. intermittent)
        Other features:  dilution air port (for exhaust temperature regulation)
a Refers to whether there  are any extra equipment items installed (e.g.,
  fans)  to function in  case the basic item becomes inoperative, so as to avoid
  shutting down  the entire system.

-------
                                   2-20

     Also listed in Table 2-2 are "general"  parameters which  must  also be
specified before the purchased cost of the system equipment can  be estimated.
Note that, unlike the control  device parameters,  these may apply to any
kind of control system.   These include materials  of construction (which may
range from carbon steel  to various stainless steels to fiberglass-reinforced
polyester), presence or absence of insulation,  and the economic  or "useful"
life of the system.  As  indicated in Section 2.3.2, this  last parameter is
required for estimating the annual capital  recovery costs.  The  lifetime
not only varies according to the type of the control  system,  but with the
severity of the environment in which it is installed.  (Representative
values for this and the  other control  device parameters will  be  presented
in those Sections of the Manual  covering them.)
2.4.4  Estimating Total  Capital  Investment
     The fourth step is  estimating the total  purchased cost of the control
system equipment.  These costs are available from this Manual  for  the most
commonly used add-on control  devices and auxiliary equipment.  Each type of
equipment is covered in  a separate section.   (See Table of Contents.)
     Most of these costs, in turn, have been based on data obtained from
control equipment vendors.  There are over one  hundred of these  firms, many
of whom fabricate and erect a variety of control  systems.-^2)  They have
readily available, current price lists of their equipment, usually indexed
by model designation.  If the items for which costs are  requested  are
fabricated, "off-the-shelf" equipment, then  the vendor can provide a
written quotation listing their costs, model  designations, date  of quotation,
estimated shipment date, and other information.   (See Figure  2-4 for a
sample quotation.)  Moreover, the quote is usually "F.O.B." ("free-on-board")

-------
                            Figure  2-4  Typical  Vendor Quotation
                                                                                  QUOTATION
 ocess Equipment Plant   (NOTE:  ComPa"y name and address hW been deleted.)
      r
          MAIL  DROP # 12
          U.S.  EPA
          RESEARCH TRIANGLE  PARK
          DURHAM.  NC  27711

          ATTN:  MR. BILL VATAVUK
                                                       QUOTATION NO.

                                                       DATE

                                                       REFERENCE
         85S23382

         9-23-85

         VERBAL - BUDGET
                                                  J
                 Thank you for your inquiry. We are pleased to submit our quotation as follows:
  QUANTITY
                                         DESCRIPTION
                         PRICE
              ITEM #1 PREHEATER
                                                                                  !  $ 7,147.00 EA.
             MODEL 191-19 SIZE #9 IMPERVITE SHELL & TUBE HEAT EXCHANGER WITH
             55.8 SQ. FT. OF HEAT TRANSFER  AREA AND CODE STAMPED

             ITEM #2 CONDENSER
                                                                                      7,430.00  EAc
             MODEL 191-19 SIZE #12 IMPERVITE SHELL & TUBE HEAT EXCHANGER WITH
             74.5 SQ. FT.  OF HEAT TRANSFER AREA AND CODE STAMPED
              APPROVAL DWG'S   2-3 WEEKS AFTER RECEIPT OF ORDER.

              THIS QUOTATION  IS IN CONFIRMATION OF OUR  PHONE CONVERSATION OF
              9/18/85.
ESTIMATED SHIPMENT _6_tO_8__ WEEKS AFTER
                                          RECEIPT OF ORDER
RECEIPT OF DRAWING APPROVAL
Prices are F.O.B.         >. Net 30 Days.                                -  •
Unless otherwise stated these prices are subject to acceptance within 30 days from date.
                                                              By.

ANY PURCHASE ORftER RESULTIMfi FROM THIS QUOTATION WILL BE SUBJECT TO THE CONTRACT TERMS AND CONDITIONS PRINTED ON TNE REVERSE SIDE OF THIS PAGE.

-------
                                   2-22

the vendor, meaning that no taxes,  freight,  or other  charges.are included.
However, if the items are not  off-the-shelf,  they  must  be  custom fabricated
or, in the case of very large  systems, constructed  on-site.  In such cases,
the vendor can still  give quotations—but  will  likely take much longer to
do so and may even charge for  this  service,  to recoup the  labor and overhead
expenses of his estimating department.
     As discussed in Section 2.2  in this Manual , the  total capital investment
is "factored" from the "purchased equipment  cost",  which in turn, is the
sum of the base equipment cost (control device plus auxiliaries), freight,
instrumentation, and sales tax.   The values  of these  installation factors
depend on the type of the control system installed  and  are, therefore,
listed in the individual  Manual  sections dedicated  to them.
     The costs of freight, instrumentation,  arid sales tax  are calculated
differently from the direct and  indirect installation costs.  These items
are "factored" also, but from  the base equipment cost (F.O.B. the vendor(s)).
But unlike the installation factors,  these factors  are  essentially equal
for all control systems.  Values  for these are as  follows:
        Cost	Range	Typical
Freight
Sales tax
Instrumentation
0.01
0
0.05
- 0.10
- 0.08
- 0.30
0.05
0.03
0.10
The range in freight costs reflects  the  distance  between the vendor and the
site.  The lower end is typical  of major U.S. metropolitan areas, while the
latter would reflect freight charges to  remote  locations such as Alaska and
Hawaii.U1)  The sales tax factors simply  reflect the  range of local and
state tax rates currently in effect  in the U.S.(13)

-------
                                  2-23

     The range of instrumentation factors is also quite large.  For systems
requiring only simple  continuous or manual control, the lower factor would
apply.  However,  if the control is intermittent and/or requires safety backup
instrumentation,  the higher  end of the range would be appl icabl e.(^)
Finally, some "package" control systems (e.g., incinerators covered in
Section 3)  have built-in controls, whose cost is included in the base
equipment cost.  In those cases, the factor to use would, of course, be zero.
2.4.5  Retrofit Cost Considerations
     The installation  factors  listed elsewhere in the Manual apply primarily
to systems  installed in new  facilities.  These factors must be adjusted
whenever a control  system is sized for, and installed in  (i.e, "retrofitted")
an existing facility.   However, because the size and number of auxiliaries
are usually the same in a retrofit situation, the total purchased cost of
the control  system would probably not be different from the new plant
purchased cost.  An exception  is the ductwork cost, for in many retrofit
situations  exceptionally long  duct runs are required to tie the control
system into the existing process.
     Each retrofit installation is unique; therefore, no  general factors
can be developed.  Nonetheless, some general information  can be given
concerning the kinds of system modifications one might expect in a retrofit:
     1.  Auxiliaries.   Again,  the most important component to consider is
         the ductwork  cost.  In addition, to requiring very long duct  runs,
         some retrofits require extra tees, elbows, dampers, and other
         fittings.
     2.  Handling and  Erection.  Because of a "tight fit", special care may
         need to  be taken when unloading, transporting, and placing the

-------
                              2-24

    equipment.  This cost could  increase  significantly if  special
    means (i.e., helicopters)  are needed  to  get the equipment on roofs
    or to other inaccessible places.
3.  Piping, Insulation,  and Painting.   Like  ductwork, large amounts
    of piping may be needed to tie  in  the control device to sources of
    process and cooling  water, steam,  etc.   Of course, the more piping
    and ductwork required,  the more insulation and painting will be
    needed.
4.  Site Preparation. Unlike the other categories, this cost may
    actually decrease, for most  of  this work would have been done when
    the original facility was built.
5.  Facilities.  Conceivably,  retrofit costs for this category could
    be the largest.   For example, if the  control system requires large
    amounts of electricity (e.g., a venturi  scrubber), the facility's
    power plant may not  be able  to  service it.  In such cases, the
    facility would have  to purchase the additional power from a public
    utility, expand  its  power plant, or build another one.  In any
    case, the cost of electricity supplied to that control system
    would likely be higher than  if  the system were installed in
    a new facility where adequate provision  for its electrical needs
    would have been made.
6.  Engineering.  Designing a control  system to fit into an existing
    plant normally requires extra engineering, especially when the
    system is exceptionally large,  heavy, or utility-consumptive.  For
    the same reasons, extra supervision may  be needed when the
    installation work is being done.

-------
                                  2-25

     7.  Lost Production.   This cost is incurred whenever a  retrofit control
         system cannot  be tied into the process during normally scheduled
         maintenance periods.  Then, part or all of the process may have to
         be temporarily shut down.  The revenue lost during  this shutdown
         period is a bonafide  retrofit expense.
     8.  Contingency.   Due  to the uncertain nature of retrofit estimates,
         the contingency (i.e., uncertainty) factor in the estimate should
         be increased.
     From the above points, it is apparent that some or most of these  instal-
lation costs would increase in a retrofit situation.  However, there may be
other cases where the retrofitted installation cost would be less than the
cost of installing the  system  in a new plant.  This could occur when one
control device, say an  ESP, is being replaced by a more efficient unit—a
baghouse, for example.   The ductwork, stack, and other auxiliaries for the
ESP may be adequate for the new system, as perhaps would the support
facilities (power plant, etc.).
2.4.6  Estimating Annual Costs
     Determining the total  annual cost is the last step in the estimating
procedure.  As mentioned in Section 2.2 the TAC is comprised of three
components -- direct and indirect annual costs and recovery  credits.  Unlike
the installation costs, which are "factored" from the purchased equipment
cost, annual cost items are usually computed from known data on the
system size and operating mode, as well as from the facility and control
device parameters.
     Following is a more detailed discussion of the items comprising the
total annual cost.  (Values/factors for these costs are also given in the
sections for the individual  devices.)

-------
                                   2-26

2.4.6.1   Raw Materials
     Raw materials are generally not required  with  control  systems.  Exceptions
would be chemicals used in absorbers or  venturi  scrubbers as absorbents or
to neutralize acidic exhaust gases (e.g.,  hydrochloric  acid).  Chemicals
may also be required to treat wastewater discharged  by  scrubbers or absorbers
before releasing it to surface waters.   But, these  costs are only considered
when a wastewater treatment system is exclusively dedicated to the control
system.  In most cases, a pro-rata waste treatment  charge is applied.  (See
section 2.4.6.5.)
     Quantities of chemicals required are  calculated  via material balancies,
with an extra 10 to 20% added for miscellaneous  losses.  Costs for chemicals
are available from the Chemical  Marketing  Reporter  and  similar publications.
2.4.6.2   Operating Labor
     The amount of labor required for a  system depends  on its size, complexity,
level of automation, and operating mode  (i.e., batch  or continuous).  The
labor is usually figured on an hours-per-shift basis.   As a rule, though,
data showing explicit correlations between the labor  requirement and capacity
are hard to obtain.  A typical  correlation is  logarithmic:
              Ll
     where:   Lj , Lg = labor requirements  for  systems 1 and 2
              vl» V2 = capacities of  systems 1 and 2 (as measured by the
                       gas flow rate,  for  instance)
                   y = 0.2 to 0.25 (typical ly) (14)
     The exponent in equation (2-6) can  vary considerably, however.  Conversely,
in many cases, the amount of operator labor required for a system will be
approximately the same regardless of  its size.

-------
                                  2-27

     A certain amount  must  be  added to operating labor to cover supervisory
requirements.   Fifteen per  cent of the operating labor requirement is
representative. (15)
     To obtain the annual labor cost, multiply the operating and supervisory
labor requirements by  the respective wage rates (in $/hr) and the system
operating factor (number of hours per year the system is in operation).
The wage rates also vary widely, depending upon the source category,
geographical  location, etc.  These data are tabulated and periodically
updated by the U.S. Department of Labor, Bureau of Labor Statistics, in its
Monthly Labor Review and in other publications.  Finally, note that these
are base labor rates,  which do not include payroll and plant overhead.
(See overhead  discussion below.)
2.4.6.3   Maintenance
     Maintenance labor is calculated in the same way as operating labor
and is influenced by the same  variables.  The maintenance labor rate,
however, is normally higher than the operating labor rate, mainly because
more skilled personnel are  required.  A 10% wage rate premium is typical.U5)
     Further,  there are expenses for maintenance materials -- oil, other
lubricants, duct tape, etc., and a host of small tools.  Costs for these
items can be figured individually, but since they are normally so small,
they are typically factored from the maintenance labor.  Reference 15
suggests a factor of 100% of the maintenance labor.
2.4.6.4   Utilities
     This cost category covers many different items, ranging from electricity
to compressed  air.  Of these,  only electricity is common to all  control
devices, where fuel oil  and natural gas are generally used only by

-------
                                   2-28

incinerators; water and water treatment,  by venturi  scrubbers, quenchers,
and spray chambers; steam, by carbon adsorbers;  and  compressed air,  by
pulse-jet fabric filters.
     Techniques and factors for estimating utility costs  for specific devices
are presented in their respective sections.  However,  because nearly every
system requires a fan to convey the exhaust gases  to and  through  it, a
general expression for computing the fan  electricity cost (Ce) is given
     Ce = 0.746 Q AP s 9 Pp
               6356 n                                              (2-7)
where:
     Q = gas flowrate (actual  ft^/min)
    AP = pressure drop through system (inches  of  water,  gauge)
         (Values for  AP are given in the sections  covering the equipment
          items.)
     s = specific gravity of gas relative to air  (1.000,  for  all practical
         purposes)
     9 = operating factor (hr/yr)
     ri = combined fan and motor efficiency (usually 0.60  to 0.70)
    Pe = electricity cost ($/kwhr).
A similar expression can be developed for calculating  pump motor electricity
requirements.
2.4.6.5   Water Treatment and  Disposal
     Though often overlooked,  there can  be a significant  cost associated
with treating and/or disposing of waste  material  captured by  a control system
that neither can be sold nor recycled to the process.
     Liquid waste streams, such as the effluent from a venturi scrubber,
are usually processed before being released  to surface waters.  The type

-------
                                  2-29

and extent of this processing  will, of course, depend on the characteristics
of the effluent.  For example, the waste can first be sent to one  (or more)
clarifiers, for coagulation  and  removal of suspended solids.  The  precipitate
from the clarifier is then  conveyed to a rotary filter, where most of the
liquid is removed.  The resulting filter cake is then disposed of, via land
filling, for example.
     The annual cost of this treatment is  relatively high--$1.00 to
$2.00/thousand gallons treated or more.(16)  Tne solid waste disposal costs
(via land filling, for example)  typically would add another $20 to $30/ton
disposed of.(^)   This,  however, would not include transportation to the
disposal site.  More information on these technologies and their costs is
found in References (16)  and (17).
2.4.6.6  Replacement Parts
     This cost is computed  separately from maintenance, because it is a
large expenditure, incurred  one  or more times during the useful life of a
control system.  This category includes such items as carbon (for  carbon
adsorbers), bags (for fabric filters) and catalyst (for catalytic
incinerators), along with the  labor for their installation.
     The annual cost of the  replacement materials is a function of the
initial parts cost, the parts  replacement labor cost, the life of the
parts, and the interest rate,  as follows:
     CRCp = (Cp + Cpl)CRFp                                             (2-8)
     where:  CRCp = capital  recovery cost of replacement parts ($/yr)
               Cp = initial  cost of replacement parts, including taxes
                    and freight  ($)
              Cpi = cost  of  parts replacement labor ($)
             CRFp = capital  recovery factor (defined in Section 2.3).

-------
                                   2-30

     In the Manual methodology, replacement  parts  are  treated  the  same  as
any other investment, in that they are also  considered an  expenditure that
must be amortized over a certain period.   Also,  the  useful  life  of the  parts
(typically 2 to 5 years) is generally less than  the  useful  life  of the  rest
of the control system.
     Replacement part labor will vary, depending upon  the  amount of  the
material, its workability,  accessibility  of  the  control device,  and  other
factors.
2.4.6.7   Overhead
     This cost is easy to calculate,  but  often difficult to comprehend.
Much of the confusion surrounding overhead is due  to the many  different
ways it is computed and to the several costs it  includes,  some of  which
may appear to be duplicative.
     There are, generally,  two categories of overhead,  payroll and pi ant.
Payroll overhead includes expenses directly  associated  with  operating,
supervisory, and maintenance labor, such  as:  workmen's compensation, Social
Security and pension fund contributions,  vacations,  group  insurance, and
other fringe benefits.  Some of these are fixed  costs  (i.e., they  must  be
paid regardless of how many hours per year an employee  works).   Payroll
overhead is traditionally computed as a percentage of  the  total  annual
labor cost (operating, supervisory, and maintenance).
     Conversely, pi ant (or "factory") overhead account  for expenses  not
necessarily tied to the operation and maintenance  of the control system,
including:  plant protection, control laboratories,  employee amenities,
plant lighting, parking areas, and landscaping.  Some  estimators compute

-------
                                   2-31

plant overhead by taking a percentage  of  all labor plus maintenance  material s(18)
while others factor it from the total  labor costs alone.(19)
     For "study" estimates, it is  sufficiently accurate to  combine payroll
and plant overhead into a single indirect cost.  This  is done  in  this  Manual .
Also, overhead will  be factored from the  sum of all labor  (operating,
supervisory, and maintenance)  plus  maintenance materials, the  approach
recommended in reference 18.  The  factors recommended  therein  range  from 50
to 70% (18)  /\n average value  of 60% is used in this Manual .
2.4.6.8   Property Taxes, Insurance, and  Administrative Charges
     These three indirect operating costs are factored from the system total
capital investment,  and typically  comprise 1,1, and 2% of it,  respectively.
Taxes and insurance are self-explanatory. "Administrative  charges"  covers
sales, research and development, accounting, and other home office expenses.
(It should not be confused with plant  overhead, however.)   For simplicity,
the three items are usually combined into a single, 4% factor* This value,
incidentally, is standard in all OAQPS cost analyses.
2.4.6.9   Capital Recovery
     As discussed in Section 2.3,  the  annualization method  used in the Manual
                                          \
is the equivalent uniform annual ized cost method.  Recall that the cornerstone
of this method is the capital  recovery factor which, when multiplied by
the total capital investment,  yields the  capital recovery cost.   (See
equation 2-2.)
     However, whenever there are parts in the control  system that must
be replaced before the end of  its  useful  life, equation 2-2 must  be  adjusted,
to avoid double-counting.

-------
                                   2-32





That i s:





     CRCS = CRFS [TCI - (Cp + Cpl)]                                (2-9)



where:



    CRCS = capital  recovery cost for control  system (3/yr)



     TCI = total capital  investment for entire system ($).



    CRFS = capital  recovery factor for control  system



The term (Cp+Cp-|) accounts for the cost of those parts that would be



replaced during the useful life of the control  system and the labor for



replacing them.  Clearly,  CRFS and CRFp will  not be equal  unless  the control



system and replacement part lives are equal.

-------
                                   2-33


 References for Section 2:

 1.   Perry, Robert H., and Chi 1 ton, Cecil  H.,  Perry's  Chemical  Engineer's
      Handbook  (Fifth  Edition).  New York:   McGraw-Hill,  1973,  pp.  25-12 to
      25-16.

 2.   Humphries, K. K. and Katell, S., Basic Cost  Engineering.  New  York:
      Marcel Dekker, 1981, pp. 17-33.

 3.   Grant, E.L., I reson, W.G.,  Leavenworth, R.S.,  Principles  ^f Engineering
      Economy.  Sixth Edition. New York:   John Wiley  & Sons,  1976, p.25.

 4.   Ibid., p. 35.

 5.   Ibid., p. 36.

 6.   EAB Guideline Memo:  "Interest Rates  for  Regulatory Impact Analyses
      (RIA)", May 27,  1982.

 7.   "Interim  Regulatory Impact  Analysis Guidance," Office  of  Management
      and Budget, June 5, 1981.

 8.   Grant, et al., Op. Cit., p. 67.

 9.   Ibid., p. 91.

10.   Ibid., pp. 107-131.

11.   Vatavuk,  W. M. and Neveril, R. B., "Estimating Costs of Air-Pollution
      Control Systems—Part I:  Parameters  for  Sizing Systems,"  Chemical
      Engineering. October 6, 1980, pp.  165-168.

12.   Pollution Equipment News, Pittsburgh:   Rimbach Publishing, 1982, pp.
      71-72.

13.   Internal  Revenue Service, Form 1040,  1985.

14.   Peters, M. S. and Timmerhaus, K. D.,  Plant Design and  Economics
      for Chemical Engineers  (Third EditionJTNew York:  McGraw-Hill, 1980,
      p. 195.

15.   Vatavuk,  W. M. and Neveril, R. B., "Estimating Costs of Air-Pollution
      Control Systems—Part II:  Factors for Estimating Capital and Operating
      Costs," Chemical Engineering, November 3, 1980, pp.  157-162.

16.   Ibid., "Part XVII:  Particle Emissions Control,"  Chemical Engineering,
      April  2,  1984, pp. 97-99.

17.   The RCRA  Risk-Cost Analysis Model: U.S.  Environmental Protection Agency,
      Office of Solid Waste, January 13, 1984.

18.   Peters and Timmerhaus, Op.  Cit., p. 203.

19.   Humphries and Katell, Op. Cit.. pp. 64-68.

-------
                              Section 3
                     THERMAL AND CATALYTIC INCINERATORS
                         i   Vishnu S. Katari
              Pacific Environmental Services (Durham, NC 27707)
                          William M. Vatavuk
                    Economic Analysis Branch, OAQPS
3.1  Process Description
     3.1.1  Elements  of Combustion
     Fume incineration,  a controlled oxidation process, is a technique
used for destruction  of  vaporous volatile organic compound (VOC) emis-
sions from industrial  waste gases.  In the process, the VOC content of
waste gases reacts  at  high temperatures with oxygen to form carbon
dioxide and water,  while liberating heat.  Three parameters: temperature,
residence time (also  referred to as "retention time" or "dwell time")
and turbulence (the "three Ts") have an interrelated effect upon the
final combustion performance.  To achieve good oxidation rates and
obtain release of the full heat content of the combustion products,
emission effluents  must  be held for sufficient residence times at
combustion temperatures  100°F or more above reported ignition
temperatures.   Further,  turbulent flow conditions must be maintained in
the incinerator for good mixing of the fuel combustion products with
incoming effluents,  so that a thorough homogeneity of combustion elements
(VOC and oxygen) may  be  achieved.  The ignition temperature of a given
VOC is the minimum  temperature at which the VOC reacts instantaneously
with oxygen.  Below this temperature (if the supply of heat were inter-
rupted) combustion  would slow down and gradually stop.
     Typically, the rudimentary combustion parameters for an incinerator
design are established empirically and no calculations are involved in
their estimation.  Of the 3 Ts, time and turbulence are fixed by

-------
     •:'                            3-2
incinerator design and air flow rate, and  only temperature  can  be  signi-
ficantly controlled.  The type of VOCs present in the waste gas usually
dictates the combustion temperature for a  required VOC destruction
rate.  Lower or higher combustion temperatures can be used  to a limited
extent, with corresponding variations in the residence time (e.g.,  an
incinerator can be designed for a lower residence time but  must operate
at a correspondingly higher combustion temperature).   The possibilities
of varying these parameters are limited, because the  combustion
temperature must always be above the ignition  temperature.   Moreover,
the cost savings realized from reducing the residence time  (and, in
turn, the incinerator size) generally are  not  large enough  to offset the
additional  expenses (e.g., fuel) resulting from compensating increases
in the combustion temperature.
     In general, the design of an incinerator  system  is based on
providing the required amounts of:   (1) heat to bring the waste gas to
the oxidation temperature and (2) oxygen for complete combustion.   The
waste gas heat and oxygen contents  determine,  respectively,  the auxiliary
heat and oxygen requirements (i.e., the lower  the waste gas heat and
oxygen contents, the higher are the auxiliary  requirements).  Either
natural gas or fuel oil can be used as an  auxiliary heat source while
ambient air is the usual  source of  oxygen.  Natural gas is  preferred
and used in most incinerators.  Oil-fired  burners have limited  turn-
down capabilities and require high  maintenance.  Depending  upon the
fuel availability and geographic location, some incinerators are designed
for a dual  fuel-burning capability  (natural  gas with  standby oil).  In
practice, a flue gas oxygen content of at  least 3 percent (by volume)
is used empirically to insure that  a sufficient amount of oxygen is
available for combustion.

-------
                                 3-3

     The waste gas heat content measures the potential heat of VOC that
would be released  as  heat of combustion upon the oxidation of the VOC.  The
heat and VOC contents of a waste gas are proportional to, and can provide
a measure of, each other.  They are also inherently  related to, and can
be expressed empirically, in terms of the VOC property "flammabil ity."
Flammability is characterized by two limits:  the lower explosive limit
(LEL) and the upper explosive limit (UEL).  These limits  represent,
respectively, the  smallest and largest amounts of VOCs which, when
mixed with air, will  burn without a continuous application of external
heat.  Major reference books present VOC flammabil ity (LEL and UEL)
data.  Table 3A-1  in  Appendix 3A  presents the flammability data for
several  VOCs commonly encountered in industrial waste gases.  To avoid
potential explosions, the VOC content of industrial waste gases released
to the atmosphere  is  normally outside the flammability limits.  The
majority of waste  gases contain low concentrations of VOCs.  For safety
reasons, their composition is typically limited to below 25 percent and
will seldom exceed 50 percent of the LEL level.  It has been empirically
determined that, upon combustion, most VOCs release approximately 50
Btu/scf of waste gas, if their concentration is at 100 percent of the
LEL.  Therefore, the  VOC content of a waste gas at less than 25 percent
LEL, the safe upper limit for incineration, will have a potential heat
content of less than  13 BTU/scf.
     The LEL and heat content values of a given waste gas can also be
related empirically to the temperature rise of the combustion flue
gases.  Upon combustion, each one percent of LEL of the VOC (i.e., a
potential heat content of 0.50 BTU/scf of waste gas) can  raise the
temperature of one ft^ of the waste gas by 27°F based on a heat capacity

-------
                                  3-4

of 0.018 BTU/ft3°F for dry air.   These empirical  relations  can  sometimes
be used in making qualitative observations  to determine  if  a  given waste
gas can be incinerated.  They can also be used to  make quick  and approxi-
mate estimates of the auxiliary  fuel  requirement.
     Most industrial  waste gases incinerated  are dilute  mixtures of
VOCs, air, and inert gas.  Thei r VOC  content  is very  low, and their
oxygen content exceeds that required  for combustion of both the VOC and
the auxiliary fuel.  If a waste  gas with a  VOC content over 25 percent
LEL is encountered, it is diluted to  bel ow  25 percent LEL prior to
incineration by adding outside air (thus increasing the  waste gas
volume flow rate to be treated).  However,  a  waste gas with a VOC content
from 25 to 50 percent LEL can be incinerated  without  adding dilution air,
provided the waste gas VOC levels in  the system are continuously monitored
via LEL monitors, to satisfy fire protection  regulations.
     A low-oxygen content waste  gas mixture of VOC, air, and  inert gases
could disrupt the burner flame stability.   Therefore, when  a waste yas
with less than 13 to 16 percent  oxygen content is  incinerated, the portion
of such waste gas used for fuel  combustion  is augmented  with  ambient air.
In a few applications, the waste gas  is an  inert gas  with a low VOC content
and negligible or zero oxygen content.  In  such cases ambient air is
provided for burning of both the waste gas  VOC and auxiliary  fuel.  In
rare cases, the waste gas is a rich VOC stream that can  support combustion
without auxiliary fuel.  Such a  rich VOC waste gas is treated as a fuel
and burned, either premixed or oxygen  free.  This  process is  sometimes
referred to as "direct flame incineration."  Figure 3-1  provides a f 1 ow
chart for categorizing a waste gas to  determine its suitability for
incineration.  (For more information  on waste gas  characterization,
see Appendix 3B.)

-------
                                         3-5

No
Auxiliary air may
be required tor
Incineration


The majority of mdmtrtd MM gnu tor Inelntmaon tal Mo omoory 1.
 CticuWim tor cngory 1 ira iddntMd m tr» turt tnd cticultliora tor
 •I cragorio (i.t. c«l»goo«i 1 through 6) in •ddmcKl m Apptndta 3B
            Figure  3-1. Flow chart for  categorization of a waste
               gas to determine  its suitability for incineration
                            and need for auxiliaries.

-------
                                  3-6

     3.1.2  Types of Incinerators
     Two types of incinerators are in  use:   thermal  and  catalytic.  The
combustion process,  as well  as equipment, design  concept, and calculations,
are essentially the same with both incinerator types.  The  only  exception
is that catalytic incineration is essentially  a flame!ess combustion
process, wherein a catalyst  bed is used  to  initiate  the  combustion  reaction
at much lower temperatures.
     Historically, the greatest reason for  using  a catalytic incinerator
has been to reduce fuel  consumption.   However,  because the  application of
either a thermal or a catalytic incinerator system without  a heat exchanger
(for recovery of flue gas heat) is now rare, the  savings associated with
catalytic incinerators are less significant.   Also,  this fuel economy for
catalytic incinerators is partially offset  by  increased operating costs for
maintenance (i.e., periodic  cleaning and replacement of catalyst).  Catalysts
undergo a gradual  loss of activity through  thermal aging, fouling, and
erosion of their surfaces.  Certain poisonous  contaminants, such as phospho-
rus, arsenic, antimony,  lead, and zinc,  also cause catalyst deactivation.
Catalytic incineration is not recommended for  waste  gases containing sig-
nificant concentrations  of particulate matter  (either  organic or inorganic)
that cannot be vaporized.
     The catalysts used  in catalytic incinerator  systems for gaseous
VOC control  are usually  precious  or base metals or their salts, either
supported on inert carriers, such as alumina or porcelain,  or unsupported.
Precious metal  oxide catalysts are less  brittle and more expensive than
base metal types, and are used in lesser amounts  per unit of waste gas
volume.  Of the precious metal  oxide catalysts, platinum/palladium
oxides are preferred.  Others include  rhodium,  nickel, and  gold.

-------
                                 3-7

Manganese dioxide is  the most commonly used base metal oxide catalyst.
     The types of VOCs  present  in the waste gas determine the operating
temperature required  in a catalytic unit.  The more stable VOCs are
generally the least reactive and  require higher inlet catalytic operating
temperatures.  Methane  is an example of a stable, low molecular weight
compound that requires  a  relatively high catalytic conversion temperature,
about 1,000°F.  Hydrogen, on the other hand, is extremely reactive,
having a conversion temperature of about 200°F.  To achieve a VOC
destruction efficiency  of at least 90 percent, the catalytic ignition
temperature for most  hydrocarbons must be between 400 and 500°F.
Higher temperatures are required to obtain higher VOC destruction
efficiencies.  When methane is  present along with other less stable
VOCs in a waste gas,  preheat temperatures lower than 1,000°F can be
used, because the less  stable VOCs burn first and generate heat.
     The auxiliary fuel requirement is the most significant operating
expense of an incinerator.  Further, the temperature rise of the
combustion products due to the  VOC heat release can be substantial.
Therefore, to minimize  auxiliary fuel expenses, a part of the heat from
the incinerator flue  gases is recovered.  This heat is usually recovered
in recuperative heat  exchangers, in which the heat from the flue gases
is exchanged with the waste gas.  Both countercurrent and cross-flow
types of heat exchangers  are used for this purpose.  When feasible,
heat may be recovered indirectly, by producing low-pressure steam in a
waste heat boiler. Further, heat recovery from the flue gases after
primary heat recovery (PHR) can be achieved by employing secondary heat
recovery (SHR) units.  Of course, SHR can be economical, only if the
secondary heat can be consumed  on-site and cheaper heat sources

-------
                                  3-8

are unavailable.  The PHR and SHR combinations  are  most  suitable  for
large installations where recovered secondary heat  may be  used  on-site
for water heating, air heating,  and other purposes.
     In general, a typical  incinerator system may include  the following
components:  (1) a fan to move the waste gas;  (2) a fan  to supply
ambient air, if required; (3) a  combustion unit (i.e., a refractory chamber
with burner for thermal  units, and a preheat  chamber with  burner  and
catalyst bed for catalytic units); (4)  heat recovery equipment
(optional, but almost always used); (5)  controls, instrumentation, and
control  panel; (6) a stack;  and  (7) in  the case of  catalytic units, a
filter/mixer to assure flow  distribution,  protect the  catalyst  bed from
flame impingement, and remove noncombustible  particulate matter.  In
addition, auxiliary equipment, such as  ductwork,  may be  required  in the
system.
3.2  Design Procedure
3.2.1  Design and Operating  Features
     The minimum waste gas characteristics data needed to  perform
incinerator design calculations  are the  waste  gas volume f 1 ow rate
and temperature, and the VOC composition.   The  waste gas flow rate
primarily determines the quantity of combustion flue gases  generated
which, in turn, dictates the size of an  incinerator system.  As discussed
in Section 3.1, the waste gas composition  determines the combustion air
requirements.  The waste gas and combustion temperatures,  along with
the waste gas volume flow rate and VOC  content, determine  the auxiliary
heat requirement and the heat exchanger size.   Finally,  the types of
VOC present in the waste gas determine  the combustion  temperature
required in the incinerator  for  optimum  oxidation.

-------
                                 3-9

     In the incineration  process, a waste gas is introduced to the
combustion chamber,  (or "preheat chamber," in the case of a catalytic
incinerator),  where  the waste gas temperature is raised to the
appropriate combustion  temperature by burning auxiliary fuel.  Because
of the high combustion  temperatures maintained, refractory chambers are
used in thermal  incinerators, while stainless steel or carbon steel
chambers are used  in catalytic incinerators.  In thermal incinerators,
the waste gas is heated and  retained for 0.3 to 1.0 seconds in the
combustion chamber at 100°F  or more above the ignition temperature,
which ranges from 1,000 to 1,400°F for most VOCs.  At these temperatures,
95 to 99 percent of  the VOCs in the waste gas are combusted.  As discussed
in Section 3.1,  the  resulting flue gases are exhausted via a stack to
the atmosphere,  after a part of their sensible heat is recovered via
direct exchange  with the  incoming waste gas.
     In catalytic  incinerators, the waste gas temperature is typically
raised in the preheat chamber to 500 to 600°F.  This is above the
catalytic ignition temperature of 400 to 550°F theoretically required
for 90 percent destruction of most VOCs.  (Thermal and catalytic ignition
temperature data for VOCs are well documented in the literature.  Table
3A-2 in Appendix A presents  catalytic ignition temperatures for several
common VOCs.)  The thoroughly mixed gaseous effluents from the preheat
chamber (where partial  oxidation may occur) are subsequently passed
through specially designed units containing catalyst elements, on the
surface of which oxidation occurs at an accelerated rate at temperatures
of 700-900°F--much lower  than typical thermal incineration combustion
chamber temperatures.  As the linear velocity through the catalyst bed
is high (600 to  1,200 ft/min.), the residence time is negligible.

-------
                                  3-10

For this reason residence time is rarely an important  factor  in the
design of catalytic incinerators.  The heat of reaction  from  the  oxidation
of the VOCs in the catalyst bed causes the gas temperature to increase as it
passes across the catalyst bed.  The amount of VOCs  present in the
waste gas determines the temperature increase  in  the catalyst bed.
     The desired catalyst bed outlet temperature  is  typically 700 to
900°F.  The maximum temperature to which the catalyst  bed can be exposed
continuously is limited to about 1,200°F.  Therefore,  the heat released
from the combustion reaction and, accordingly, the VOC content of the
waste gas are limited to about 20 percent LEL. (See Section  3.2.2. for
more details.)
     Depending upon the catalyst bed temperature  swings  (i.e., the
frequency at which it is subjected to extreme  temperature excursions),
the operating and maintenance practices, and the  particulate  matter and
specific catalyst poisons encountered, the catalyst  would have an
effective life of 2 to 10 years.  The amount of catalyst required
(measured by the standard hourly flue gas volume  flow  rate per unit
volume of catalyst or the "space velocity," hr'1), depends on the type of
catalyst used, but increases with the required VOC destruction efficiency.
The space velocity, incinerator gas velocity,  and pressure drop used
in the system design are determined experimentally.
     Finally, as in thermal incinerators, the  flue gases exiting the
catalyst bed are exhausted to a stack, usually after heat exchange with
the incoming waste gas.
     3.2.2  Design Calculations
     This section presents calculations for designing  an incineration
system to the level of detail  required by a study cost estimate.  Further,
these calculations only apply to dilute mixtures  of  VOCs, air, and inert gas.

-------
                                 3-11

These mixtures are typical of most industrial waste gases  (i.e., those
cases which require no outside  air for dilution or for combustion
of fuel  and waste gas  VOC--Category 1 in Figure 3-1 and Table 3B-1,
Appendix 3B).  Appendix 3B presents a general procedure applicable
to all  types of waste  gas compositions, including those requiring the
use of outside air for combustion or dilution purposes (i.e., Categories
1 through 6 in Figure  3-1 and Table 3B-1, Appendix 3B).
     Figure 3-2 is a simplified schematic of an incinerator system.  A
thermocouple in a thermal incinerator combustion chamber measures
temperature, and appropriate control circuitry alters the  rate of
auxiliary fuel entering the incinerator to maintain the desired combustion
temperature.  In catalytic incinerators, thermocouples installed in the
preheat chamber and catalytic bed perform the same function.
     The incinerator design calculations for the waste gas cases where
no outside air is added for either combustion or dilution  and where the
VOC content is low (i.e., Category 1) can be summarized by the following
step-wise approach. The items that must be calculated or estimated
in the design of any emission control system are those which determine
the system size, performance, and capital and operating costs.  In the
case of incinerators,  these items are:  (1) the auxiliary  fuel requirement
and flue gas flow rate; (2) for catalytic incinerators, the amount of
catalyst required; and (3) the pressure drop across the system.
     Item 1.  Calculate Auxiliary Fuel Requirement and Flue Gas Flow Rate.
     The calculations  of the auxiliary fuel requirement and the flue gas flow
rate constitute an important incinerator design item.  The flue gas flow rate
determines the incinerator system size and, consequently,  its capital cost.
The auxiliary fuel can be a major operating cost for an incinerator system,,

-------
                                                Uaste gas from the process
                                                                  (0)
Combustion
A1r« (4)
Auxiliary
Fuel (3)






Combustion
Chamberb
i
Heat Loss
L 
-------
                                 3-13
     Calculations of  the auxiliary fuel requirement and flue gas
flow rate are considered as one  item, because they are interrelated.
The specified flue gas  conditions determine the amount of auxiliary
fuel consumed which,  in turn, becomes a part of the flue gas.  The
necessary waste gas and combustion information to be compiled and
the calculations to be  performed are presented in the following
steps:
     Step 1.  Identify  the waste gas composition data.  These
              include:  the volume flow rate (Qj), scfm; temperature
              (Tl), °F; VOC content, % LEL; and heat content (hi),
              BTU/scf of waste gas.  The heat content of the waste
              gas is  a  function of the VOC content.  (The waste gas
              pressure  is not a design consideration, because the
              majority  of waste gases enter the incinerator at
              atmospheric pressure.)
     Step 2.  For thermal incinerators, determine the combustion
              temperature (T^) based on the desired VOC destruction
              efficiency.  Suggested combustion temperature (T$)
              values  for waste gases containing nonhalogenated VOCs
              are 1,600°F and 1,800°F, respectively, for 98 and 99
              percent VOC destruction efficiencies.  These temperatures
              correspond to a 0.75-second  residence time in the
              incinerator.  Higher temperatures of about 2,000°F
              (and 1-second residence time) are required for the
              destruction of halogenated VOCs by 98 percent or
              more.

-------
                    3-14

     For catalytic incinerators, select the preheat
temperature (Tg) considering the amount and type of VOCs
present in the waste gas.  Upon oxidation in the catalyst
bed, the heat content of the waste gas VOCs is  released
in the bed.  Consequently, the temperature of the bed  and
waste gas increase, as explained in Section 3.1.1,  by
about 27°F per each one percent of VOC LEL.  For most
VOCs oxidized on precious metal catalysts, the  suggested
preheat temperature (15) is 600°F.  For a waste gas content
of 4 to 10 percent LEL, this results in an average  catalyst
operating temperature of 700 to 900°F (i.e., 600°F  + [4
to 10]% LEL x 27°F/%LEL = 700 to 900°F).
     Less stable VOCs, such as monohydric alcohols,
aromatic hydrocarbons or propylene, can use lower catalyst
operating temperatures, on the order of 500°F.
     In rare cases, where the VOC content in the waste
gases is less than 2 percent LEL, higher preheat temperatures
(700-750°F), or more  catalyst than typically required, may
have to be used to obtain equivalent 700° to 900°F  catalyst
operating temperature and VOC destruction.  However, to
avoid this increase in fuel/catalyst costs, the VOC content
of the waste gas is increased when possible by  repeated
recycling of waste gases within the process being controlled,
before introducing them to the incinerator.
     Waste gases with VOC contents higher than  20 percent
LEL are not suitable for catalytic incineration, because

-------
                                   3-15

         the VOC  heat content released increases the catalyst bed
         temperature to beyond 1,200°F, the maximum permissible
         temperature to which the catalyst bed can be exposed
         continuously.
              Conversely, for the destruction of more stable VOCs,
         such as  methane, higher preheat temperatures (900-1,000°F)
         are used.  This, however, requires a lower maximum allowable
         VOC content--i.e., 7 to 11%.
Step 3.   (Applies to only catalytic incinerators.)  Calculate the
         catalyst bed outlet temperature (Tfi).  As indicated in
         Step 2,  Tfi should not exceed 1,200°F.  Further, as explained
         in Section 3.1.1, the heat of combustion released by the
         VOC in the waste gas increases the waste gas temperature
         by 27°F  for each one percent of LEL.  Because the average
         heat capacity of air is approximately 0.018 BTU/scf-°F,
         the waste gas heat content required to increase the waste
         gas temperature by 27°F would be equivalent to 0.5 BTU/scf.
         (0.018 x 27).  It follows that a waste gas VOC heat content
         of 1 BTU/scf would, when released through combustion,
         increase the waste gas temperature by about 55°F upon
         release  (2 x 27°F).  Therefore, we can write:
                  T6 = T5 + (Qi/Q5)(55)(h1)                      (3-1)
         where    1§ = Preheat temperature, °F, determined from
                       Step 2
                  hi = Waste gas heat content, (BTU/scf of waste
                       gas)
                     = Ratio of the waste gas flow rate at the
                       incinerator inlet to the flue gas flow rate
                       at the preheat chamber exit.  For dilute
                       waste gases consider the ratio to be equal
                       to 1, by neglecting the increase in flue
                       gas volume due to the fuel  addition.
                       1200°F

-------
                                    3-16

Step 4.  Determine the waste gas temperature at the incinerator inlet
         (T?) = the temperature at the heat exchanger outlet.
         With thermal  incineration, Tg must be no higher than
         1,000 to 1,1000F,  to avoid preignition of the waste gas
         before it reaches  the combustion chamber.  T£ is also
         limited by the heat VOC content of the inlet waste gas.  As
         eq. 3-1 indicates, the temperature rise realized in the
         combustion chamber is proportional  to this heat content.
         For example,  if a  20 percent LEL stream were incinerated,
         the temperature rise would be about 540°F (20 x 27°).
         Subtracting this from a combustion temperature of 1500°F
         yields a maximum T£ of about 950°F.  For catalytic
         incinerators, the  waste gas temperature (12) entering the
         preheat chamber can be as high as the preferred preheat
         temperature (15),  600°F.
              Broadly speaking, as ~\2 increases, the auxiliary fuel
         requirement (and cost) decreases. But at the same time,
         the size and  cost  of the recuperative heat exchanger
         increases, driving up the total  capital  investment of the
         system.  Thus, there is a trade-off between capital and
         operating costs, the extent of which depends upon the value
         of 1"2 selected. However, as this selection depends
         on the results of  a process optimization analysis, no
         firm guidance can  be given for selecting T"2—except that
         it should not exceed the design limits noted above.   The
         discussion that follows may guide one in performing such  an
         optimization.

-------
                    3-17
     First of all,  the waste  gas temperature  entering  the
combustion chamber/preheat  chamber  is determined  by the
heat exchanger heat transfer  performance  (denoted by (j)
or HE) and the waste gas  inlet temperature  (TI).
     For incinerator systems  with jru> heat exchangers
          T£ = TI  (the temperature  of the entering waste gas).
     For incinerator systems  with primary (recuperative)
heat exchangers, T£ is calculated from the  known  value of
the system's heat  exchanger heat transfer performance
($) and the following expressions:
          T"2 = TI  + (p (15 - TI) for thermal  incinerators
          1"2 = TI  + (p (Ts - TI) for catalytic incinerators
(Note:  Use of a secondary  heat exchanger has no  affect
on the T"2 value.)
     Theoretically, a heat  exchanger heat transfer performance
(0) approaching 100 percent is possible.  However, as  the heat
exchanger performance increases the required  heat transfer
area, the heat exchanger  cost increases enormously,
approaching infinity as (p approaches 100 percent.
Therefore, heat exchanger (p is selected based on  economic
considerations, as  well as  the waste gas and  flue gas  data.
Included among the waste  gas  and flue gas data which impose
limitations on (j) are:   (.1)  the flue gas temperature at

-------
                             3-18

         the heat  exchanger outlet  (Ty)  in  the  case  of  either type
         of  incinerator  and  (2) the waste gas VOC content in the
         case of thermal  incinerators.
              Depending  upon the flue gas constituents, mainly
         moisture  and  corrosive elements, Ty should  be  about SOOT,
         due to possible equipment  corrosion and condensation
         that may  occur  if it falls below this  temperature.
              The  value  of Ty is  related to (|) by the following
         equation:
         ()  =  Q"  [1  "  Tg - ij  ] for thermal  incinerators  (3_4)

                      Cl  -  TQ - TJ3 for catalytic incinerator  (3_5)

     where Qi,  0.5,  and 0.5  = waste  gas  flow  rate and  flue  gas  flow  rates
                             at the exit of  combustion  chamber and
                             catalyst bed respectively  (scfm)
         CP2» CP5»  and CP6  = Mean neat  capacities of  waste gas and
                             of flue gas at  the exit  of the combustion
                             chamber and catalyst bed,  respectively
                             (Btu/ft3°F)
              It is evident from the above equation that maximum
         possible $ increases with  the  value of T]_.   However,  T^  can
         never equal  or exceed Ty.
              The following heat transfer performance ((]))  capabili-
         ties are commonly  reported for typical  modular heat exchangers:
         35 to 40 percent for 1-pass, 45 to  50  percent  for 2-pass,  and
         65 to 70 percent for 3-pass units.
Step 5.  Calculate the amount of auxiliary fuel  required (0.3)  based
         on the following energy balance around the combustion chamber/
         preheat chamber (see Figure 3-2):

-------
                         3-19
    Amount  of
   sensible heat
     leaving
   Amount of
  sensible heat
    entering
                            Amount of
                           heat of VOCs
                            released
                              from
                            combustion
                                                  Amount  of
                                                 heat  of  fuel
                                                 released  from
                                                 combustion
(H5

(H5
HL) -

HL) -



where
(H2 +  H3)

(H2 +  H3)
               HL =
               \\2 =

               H3 =
               0.3 =
               h]_ =
               h3 =
     QI hi + Q3 (13  (for thermal  incinerators)  (3-6)

     03 h3        (for catalytic incine-     (3-7)
                   rators,  because VOC heat
                   content  is  not released
                   in the preheat chamber).

  Sensible heat of  flue gas at the combustion
  chamber/preheat chamber exit (BTU/min)
  Heat loss = 10% HS  (assumed)
  Sensible heat of  waste gas at the incinerator/
  preheat chamber inlet (BTU/min)
  Sensible heat of  fuel  used (BTU/min)
  0 (for fuel entering at ambient con-
  ditions)
  Waste gas flow rate (scfm)
  Auxiliary fuel  flow rate  (scfm)
  Waste gas heat content (BTU/scf of waste gas)
  Lower heating value (LHV) of fuel  (BTU/scf).
           By  substituting Hn- = Q-j Cpj  ATj , where Cp^ represents the

       mean heat capacity for the temperature difference of AT-,-

      (Tj-Tr,  the reference temperature) the sensible heat

      values of the gas streams leaving and entering the

      chamber  can be expressed by the following equations:
               H5 = Q5 CP5 AT5
                                       (3-8)
      where
= Mean heat capacity of  the flue gas  for the
  temperature interval of AJ5)  from the
  reference temperature  (70°F)  to the combus-
  tion temperature  (in the case of thermal
  incinerators)  or  to the preheat temperature
  (in the case of catalytic incinerators)^
  Cp5 = 0.0194,  0.0196,  and 0.0198 BTU/ft3°F
  for thermal  incinerator combustion
  temperatures of 1,600,  1.800, 2,000°F,  respect-
  ively, and 0.0183 BTU/ft3°F  for a catalytic
  incinerator preheat temperature of  600°F
               H2 = 0,2
                                        (3-9)

-------
                             3-20
         where    Cp2 = Mean heat capacity of the waste gas  for
                        the temperature interval   AT2  from the
                        reference temperature (70°F) to the
                        temperature at the inlet  of the incinerator/
                        preheat chamber (T2).  Cp2 = 0.0181  BTU/ftJ°F
                        for waste gas temperatures (Tj) up to 300°F
                   Q2 = Ql-
              Substituting the above enthalpy values for H2  and HS
         and QI + 0,3 = Q2 + Qa for 0.5 in eq.  (3-6) or  (3-7),
         rearranging the resulting equation,  and  accounting  for
         the heat loss yields the following (see  Appendix 3B for
         details):
                   Ch                33
                   Q  = Fuel  used, ft /std. ft of waste gas
                        1.1  CPR  AT 5  -  Cp?  AT?  -  hi
                           h3  -  1.1  C5 AT5                  (3-10)
Step 6.  Calculate the gas flow  rate leaving the combustion
         chamber/preheat chamber (Qs).  In the case  of  a  thermal
         incinerator,  because  the combustion takes place  pri-
         marily in the combustion chamber, the resulting  flue
         gas consists  of the products  of combustion  of  the waste
         gas VOCs and  the auxiliary  fuel.   In  the case  of catalytic
         incinerators, because fuel  is added in  the  preheating
         chamber to raise the  waste  gas temperature  for subsequent
         combustion in the catalyst  bed, the gases exiting the
         preheat chamber consist of  the waste  gas and the products
         of fuel  combustion.
              In the incineration of dilute VOC  waste gases  the
         flue gas flow rate is approximately equal to the total
         of the waste  gas flow rate  and fuel flow rate  used  for

-------
                                 3-21
              combustion,  because no outside combustion air is  used
              (i.e.,  Q4  =0).   (This is because, in the case of thermal
              incinerators, the increase in flow rate due to combustion
              of the  waste gas  VOCs and fuel is negligible.)  Therefore,
              as indicated above:
                        Q5 = Q2 + Q3                                (3-11)
              where     Q5 = Flue gas flow  rate (scfm)
                        Q2 = Waste gas flow rate (scfm)
                        0,3 = Auxiliary fuel burned (scfm)
     Item 2.  Establish  the Amount of Catalyst Required.
     The cost of catalyst  consumed or replaced represents a significant
catalytic incinerator operating cost item.  Therefore, the amount of
catalyst used and its expected  life must be accurately determined in
the initial  design of a  catalytic incinerator system.
     The amount of catalyst required usually depends upon the type and
age of catalyst used, types and amounts of VOCs encountered, the
destruction  efficiency required, and the amounts of potential reactants
present that impair the  catalyst activity, which is usually highest when
the catalyst is fresh.  Because in most cases only limited information
is available about the potential reactants and noncombustible particul ate
matter that  may be present in the waste gas, most catalytic incinerator
systems are  overdesigned to compensate for the unexpected.  The amounts
of catalyst  required  for the destruction of various types of VOCs are
usually established by laboratory tests by catalyst manufacturers.
     The amounts of precious metal catalysts commonly used are  1.5 and
2 ft3 per 1,000 scfm  waste gas  (equivalent to space velocities  of
40,000 and 30,000 hr1)  for 90  and 95 percent VOC destruction
efficiencies, respectively.(*)   The corresponding amounts of base metal

-------
                                  3-22
catalysts used are 4 to 6 ft^/1,000  scfm (i.e.,  space velocities of
15,000 to 10,000 hr'1).^)
     Item 3.  Determine the Pressure Drop  Required Across the System.
     The total pressure drop required across  an  incinerator system
determines the waste gas fan size and horsepower requirements, which,
in turn, determine the fan  capital cost  and electricity consumption.
     The total pressure drop across  an incinerator system depends on
the number and types of equipment included in the system and on
design considerations.  The estimation of  actual  pressure drop require-
ments involves complex calculations  based  on  the specific system's
waste gas and flue gas conditions and equipment  used.  For the purposes
of this section, however, the following  approximate values can be used:
                  Pressure  drop  (AP, in. t^O) across
                     Thermal  incinerators   =  4
                     Catalytic incinerators =  6
                     Heat exchangers:  35%   =  4
                                      50%   =  8
                                      70%   = 15
     Once the total  pressure drop required is estimated (as a summation
of the pressure drops across all  pieces  of equipment in the incinerator
system), the blower electricity  requirements  can be estimated from the
basic fan horsepower requirement equation.  For  example, at a combined
fan-motor efficiency of 62  percent,  the  fan horsepower equation dictates
that 0.19 kWh of electricity per hour is  required for moving 1,000 acfm
of flow rate at a 1-in. water pressure drop.  Therefore, the fan
power requirement is estimated by multiplying the total pressure drop
(inches of water) by the total flue  gas  flow  rate (thousand acfm) and
the 0.19 kWh/hr factor.  For the cases where  an  additional fan is

-------
                                 3-23
used to add outside  air to the system, its power requirement must be
calculated separately.   (See Section 2 of this Manual for more on how
to estimate electricity requirements.)
3.3  Estimating Total Capital Investment
     This section provides a general methodology for developing "study"
estimates of capital  costs (April 1986 dollars) for thermal and
catalytic incinerator systems.  The precision of the "study" cost
estimate (i.e., +30  percent) applies to the estimates presented herein.
In this method, the  total purchased cost of the system equipment is
the basis to which predetermined factors are applied, to estimate the
system direct and indirect installation costs.  (See Section 2 for a
more thorough discussion of this estimating method.)
     The purchased cost of an incinerator varies widely depending upon
several design factors.  Therefore, discretion is needed when using
generic incinerator  cost information.  Among the factors that influence
the incinerator purchased cost are supplier's design experience, materials
of construction, instrumentation, the type of heat exchanger used and the
nature of the installation, i.e., whether indoor, outdoor, ground level,
or roof top.
     The nature of the  installation has a particular effect on the system
design and, consequently, the cost.  Specifically, incinerator systems
for roof top installations are made of light weight material, while
equipment for outdoor locations can be preassembled in larger modules
than for indoor locations.  Traditionally, for thermal incinerators
stainless steel combustion chambers are used to achieve a maximum
equipment life (typically 15 years).  Several manufacturers offer

-------
                                  3-24
carbon steel units at costs of 60 to 70  percent  of that  for stainless
steel units.  Of course,  the life of such  equipment  will  be lower—
approximately 10 years.  Catalytic incinerators  will tolerate lower grade
material (e.g., carbon steel) better than  thermal units  because of their
lower operating temperatures.  However,  catalyst bed enclosures are mostly
fabricated of stainless steel.
     3.3.1  Thermal  Incinerator Equipment  Costs
     Figure 3-3 presents  thermal  incinerator equipment costs (April 1986
dollars) as a function of the waste gas  volume flow  rate  at standard
conditions of 70°F and 0  psig. This figure was developed  from cost
information received from three incinerator manufacturers for three
volume flow rates each.(3»4»5)  Analytical  equations for  these equipment
cost curves are presented in Table 3-1.   (The table  also  presents
analytical  equations for  catalytic incinerators, the cost curves for
which are discussed  in Section 3.3.2.) The equipment costs listed
represent all  the equipment in an incinerator system including a com-
bustion chamber with burner, waste gas fan, inlet and outlet plenums,
prepiping and prewiring,  instrumentation and  controls, a  10-ft stack,
and in the case of heat recovery, a primary heat exchanger.  The cost
data apply to the cases of dilute VOC content waste  gases (to which no
outside air is added) containing up to 25  percent LEL VOC and incinerated
at a 1500°F combustion temperature.
     The Figure 3-3  (or Table 3-1) cost  data can be  applied to other cases
of waste gas compositions including those  requiring  slightly different
combustion temperatures without introducing significant errors to the costs.
When these data are  applied to different combustion temperatures,

-------
                                  3-25
   1,000
vo
oo
Ol
(A
o
 Q.
•r-


 cr
                  O No HE   A 50% HE

                  D 35% HE  O 70% HE
HE » Heat Exchange j=g
                              Volume  Flow Rate, 1,000 scfm
                Figure  3-3.   Thennal  incinerator equipment cost estimates

-------
                               TABLE 3-1.  EQUATIONS FOR INCINERATOR EQUIPMENT  COSTS3

                                                (APRIL  1986  DOLLARS)
Extent of
heat
exchange
None
35%
50%
70%
1 n Eq =
In Eq =
In Eq =
In Eq =
Equipment cost equation for
thermal incinerators"
[14,402 -
[16,175 -
[15,784 -
[20,608 -
992(1 nQ)+
l,262(lnQ)+
l,165(lnQ)+
2,119(lnQ)+
70 (In
85 (In
81 (In
131 (1
Q)2] (IO-3)
Q)2] (IO-3)
Q)2] (IO-3)
n Q)2](10-3)
In Eq
In Eq
In Eq
In Eq
Equipment cost equation for
catalytic incinerators
= [24,086 -
= [27,170 -
= [26,497 -
= [21,685 -
3,252(1 n
3,789(1 n
3,650(ln
2,643(1 n
Q)+
Q)+
Q)+
Q)+
•».-»-.•«=»•
205
231
225
174
=»^a— e--a
(lnQ)2](10-3
(lnQ)2](lO-3
(lnQ)2](10-3
(lnQ)2](lO-3.
aThese equations should not be extrapolated outside the flowrate range of 5,000  to 50,000  scfm.
                                                                                                                     co
                                                                                                                     i
                                                                                                                     ro
15 Eq - Equipment cost in April  1986 dollars, Q - Volume flow rate in scfm.

-------
                                 3-27
it is assumed that the system will tolerate minor adjustments
to the incinerator face velocity  and  residence time values  resulting
from these temperatures.   Even if the system size were adjusted to
compensate for these different temperatures,the  resulting changes in
the equipment cost would  be minor.  For example, if a combustion chamber
were sized for a combustion temperature of 1,700°F instead  of 1,500°F
the cost increase due to  the increase in combustion chamber size would
be less than 5 percent.
     The Figure 3-3 and Table 3-1 cost data can  also be applied to
cases of waste gas compositions to which outside ambient air is added
for combustion.  In these cases,  the  flue gai flow rate at  standard
conditions must be substituted for the waste gas flow rate  in the
figure.
     3.3.2  Catalytic Incinerator Equipment Costs
     Figure 3-4 presents  catalytic incinerator equipment costs (April
1986 dollars) as a function of the waste gas volume flow rate at standard
conditions (70°F and 0 psig), developed from cost information received
from five equipment manufacturers.(6-10)   Analytical equations repre-
senting these cost data are presented in Table 3-1.  The equipment
cost data represent all the equipment in an incinerator system, including
the burner, fan, housing, skid mounting, instrumentation and controls,
a 10-ft stack, catalyst,  and where heat recovery is used, a primary
heat exchanger.  The cost data apply  to dilute VOC waste gases requiring
a temperature of 600°F at the preheat chamber exit/catalytic bed inlet.
The cost data can be applied to waste gases to which outside air is
added by substituting the flue gas flow rate at  standard conditions for
the waste gas flow rate in Figure 3-4.

-------
                              3-28
1,000
                                                      O No HE
                                                      D 35Z HE
                                                      A 50* HE y
                                                      O 702 HE !
                                                      HE = Heat Exchange
   50
                            Volume Flow Rate, 1,000 scfm
              Figure 3-4.  Catalytic incinerator equipment cost estimates

-------
                                 3-29
     3.3.3  Total  Capital Investment for Incinerators
     The total  incinerator capital investment as a percentage of equip-
ment cost varies with  the type of installation, i.e., whether custom or
package.  The type of  incinerator installation is an important consider-
ation.  For most nonchemical industry operations, such as drying ovens,
painting facilities, printing and coating operations and other processes
where incinerators are commonly used for VOC control, waste gas flow rates
generated are small.   Modular incinerator units, prefabricated and
preassembled, are most suitable for such flow rates.  The size of
skid-mounted modular units is limited to handling flows up to about
20,000 cfm, mainly because of limitations to the sizes of trucks carrying
them and access doors  at the plant sites.  Of course, larger units,
prefabricated and partially assembled, are possible for outdoor install-
ations.  Some incinerators handling up to 100,000 cfm, which are partly
field-fabricated and field-assembled, can be found in chemical plant
applications.  Typically, heat exchangers can accommodate gas flows from
3,000 to 20,000 cfm.   For larger flowrates, multiple heat exchangers
units are usually installed in parallel in a single incinerator system.
     For incinerators, the total capital investment varies from a small
percentage (about 110  percent) to more than 200 percent of the total
equipment purchased cost.  The custom installation charges of an incinerator
system, including incinerator and heat exchanger units, ductwork, fans,
and a tall stack if required, may amount to 300 to 400 percent of the
total equipment purchased cost, depending upon the installation.
     The skid-mounted  units ready to be placed on a concrete pad at a
prepared site incur the lowest installation expenses.  Roof top instal-
lations will require higher costs, field-assembled units even higher,

-------
                                  3-30

and field-fabricated and assembled units the highest costs.
     For estimating purposes, the total  capital  investment (TCI)  of  a
skid-mounted modular unit can be calculated  at 125  percent of the total
purchased equipment cost.  Conversely, Table 3-2 presents typical
estimated capital  cost factors applicable to custom installations of
both thermal and catalytic incinerator systems.   No cost  factor is
included for estimating ductwork cost in the table  because the ductwork
size and length  and, consequently, its cost will  vary with  the instal-
lation and the waste gas flowrate.  For both packaged  and custom  incine-
rator units, the ductwork capital  cost must  be estimated  separately.
Alternatively, in the case of custom units,  the  purchased cost of the
ductwork and other auxiliary equipment can be added to the total  incine-
rator equipment cost prior to applying the Table 3-2 factors  for  estimating
the total capital  investment.  (Note:   As Section 2 of the Manual
indicates, the TCI also includes costs for land, working  capital,  and
off-site facilities, which are not included  in the  direct/indirect
installation factor.  However, as  these items are rarely  required  with
incinerator systems, they will not be considered here. Further,  no
factor has been provided for site  preparation (S.P.),  or  buildings (Bldg.)
since these site-specific costs depend very  little  on  the purchased  equipment
cost.  Lastly, for the incinerator cases in  which outside air is  added
for combustion or dilution, the cost of the  fan  used for  this purpose
also must be estimated separately.)
3.4  Estimating Total Annual  Cost
     3.4.1  Direct Annual Costs
     For incinerator systems with  no heat exchanger, the  cost o'f  auxiliary
fuel is the major direct annual  cost.  Fuel  costs are  considerably

-------
                                     3-31
TABLE 3-2.  CAPITAL  COST  FACTORS FOR CUSTOM THERMAL AND CATALYTIC INCINERATORS3
     Cost Item
Cost Factor (Fraction of Indicated Cost)
DIRECT COSTS

  1) Purchased equipment  cost

     Incinerator
     Auxiliary equipment^
     Instruments and  controls0
     Taxes
     Freight

       Total Purchased  Equipment cost

  2) Direct installation  costs

     Foundations and  supports
     Erection and handling
     Electrical
     Piping
     Insulation
     Painting
     Site preparation (S.P)  Buildings
       (Bldg.)
       Total Installation Direct Costs
       Total Direct Cost

INDIRECT COSTS
          As
          As
required K
required )"
     0.1  A
     0.03 A
     0.05 A
                            B(=1.18A)
                  0.08 B
                  0.14 B
                  0.04 B
                  0.02 B
                  0.01 B
                  0.01 B
             As required
                  0.30 B + S.P. + Bldg.
                            1.30 B + S.P.  +  Bldg.
     Engineering and supervision                           0.10 B
     Construction and field  expenses                       0.05 B
     Construction fee                                     0.10 B
     Start-up                                             0.02 B
     Performance test                                     0.01 B
     Contingency                                          0.03 B	
       Total Indirect Costs                                        0.31 B	
       Total Direct and Indirect costs  = Total Capital Investment  |1.61 B + S.P.  + Bld"g<
Reference 11.

^Includes ductwork and any  other equipment normally not included with unit  furnished
 by incinerator vendor.

cCost of instrumentation and  controls often furnished by vendor.

-------
                                  3-32

lower for catalytic incinerators than  for thermal  units  because of the
lower operating temperature.   Besides  the fuel,  the  utility  requirements
for an incinerator include electricity  for the waste gas fan and, if
used, the ambient air fan.  Operating  labor is usually small for both
types of incinerators--0.5 hr/shift.(H)
     Maintenance costs of well-designed and  maintained thermal or catalytic
incinerators of either type are low, with a substantial  portion required
for the heat exchanger maintenance.   (Well-designed  and  fabricated heat
exchangers, i.e., stainless heat exchangers,  usually have lower maintenance
expenses.)  The incinerator unit maintenance  requirements may include
repairs to the refractory lining and blowers, maintenance of control
instruments, and cleaning of  flame rods,  if used.  Maintenance labor
may be estimated at 0.5 hr/shift. The  maintenance materials may be assumed
to equal  the maintenance labor cost.(H)
     Depending upon the incinerator and how it is  operated, the life
of a given load of catalyst may be 2 to 10 years.  A conservative
estimate of catalyst replacement cost  can be  based on the lower life
time--2 years.  The initial  costs of precious metal  and  base metal
(manganese dioxide) catalysts are $3,000/ft3(1)  and  $600/ft3 (2),
respectively.  Item 2 of Section 3.2.2  showed how  to estimate the
catalyst requirement (ft3).  Finally,  the catalyst replacement labor is
minimal compared to the catalyst cost.
     Based on these values and the estimating procedure  shown in Section 2,
the catalyst replacement cost (CRCcat)  would  be:
            =  Ccat x 1.08  x CRFcat                                (3-12)

-------
                                     3-33  ,

     TABLE 3-3.   SUGGESTED FACTORS FOR ESTIMATING INCINERATOR ANNUAL COSTS
    Item
          Suggested  Factor
Direct Operating  Costs

Operating labor9
  Supervisory  labor3
Maintenance labor
Maintenance materials9
Replacanent parts

Utilities:

  Fuel
  Electricity15'0
Indirect Operating Costs

Overhead

Administrative charges
Property tax
Insurance
Capital recovery cost6
0.5 hr/shift
15% of operating labor
0.5 hr/shift
100% of maintenance labor
Thermal incinerators:  None
Catalytic incinerators:   (See eq.  3-12)
The amount of fuel  required  is calculated from
Step 5 (Qs) of Section  3.2.

Use the following A P values in estimating elec-
tricity requirements:

  Thermal  incinerators    =  4 in.  water
  Catalytic incinerators  =  Sin.  water
  Heat exchange of
                                  35%
                                  50%
                                  70%

                                Ductwork and stack
                         =  4 in.  water
                         =  Sin.  water
                         =15 in.  water

                         =  As required
60% of sum of operating,  supervisory,  and maintenance
  labor and maintenance materials
2% X TCI?
1% X TCI°
1% X TCI
CRFs X [TCI - 1.08 x Crat]	
Reference 11.

     total A P of an incinerator system is the sum of base (i.e., incinerator)
  A P + heat exchanger A P.

cAn equation to calculate electricity requirements (kWh per hour) is given
 in Item 3 of Section 3.2.2.

dTCI = Total capital  investment.
     CRFs (system capital  recovery factor) is a function of the equipment life
 (10 years, typically)  and  the  opportunity cost of the capital (i.e., interest
 rate).  For instance,  for  a  10-year life and a 10% interest rate, CRFS = 0.1628.

-------
                                  3-34

     where:  Ccat = initial  catalyst  cost  ($)
             1.08 = factor accounting for  taxes  and  freight
           CRFcat = capital  recovery  factor  for  catalyst  (e.g., for  a
                    2-year life and  a 10%  interest  rate,  the factor would
                    be 0.5762).
     3.4.2  Indirect Annual  Costs
     As Table 3-3 shows,  the indirect (fixed)  annual operating costs
include capital  recovery; overhead;  and  property taxes, insurance, and
administrative charges.  The last  three  costs  can be estimated at 1
percent, 1 percent, and 2 percent  of  the total capital investment,
respectively.  The system capital  recovery cost  is based  on an estimated
10-year equipment life.  (The incinerator  system life varies from 5 to
15 years depending on the material of construction used and the durability
of the design.)   However, as Section  2 indicates, the system capital
recovery cost is the product of the  system capital  recovery factor
(CRFs) and the total capital investment  (TCI)  less the purchased cost
of the catalyst ("Crat x 1.08"),   This offset  is necessary to avoid
double-counting.
     Finally, overhead may be estimated  at 60% of the sum of operating,
supervisory, and maintenance labor and maintenance materials.  (See
Section 2 of the Manual for a detailed discussion of the  items comprising
the total annual cost.)

-------
                                   3-35

    References  for Section 3

1.  Telephone conversation:  Robert M. Yarrington (Engelhard  Corpora-
    tion,  Union,  NJ) with Vishnu S. Katari  (Pacific Environmental  Services,
    Inc.,  Durham, NC), June 2, 1986.

2.  Telephone conversation:  Bob Campbell  (Pillar Technologies,  Inc.,
    Hartland, WI) with Tom Rhoads (Pacific Environmental  Services, Inc.,
    Durham,  NC),  February 28, 1986.

3.  Correspondence: Ralph N. Stettenbenz (C-E  Air Preheater,  Combustion
    Engineering,  Inc., Wellsville, NY), to Vishnu S. Katari,  April  3,  1986.

4.  Correspondence:  Ronald J. Baschiere (Hi rt Combustion Engineers,
    Montebello, CA) to Vishnu S. Katari, April  7, 1986.

5.  Correspondence:  C.L. Bumford (Peabody Engineering,  Stamford,  CT)
    to Michael  K. Sink (Pacific Environmental  Services,  Inc., Durham,  NC),
    March  24, 1986.

6.  Correspondence:  Robert M. Yarrington (Engelhard Corporation,  Union,
    NJ) to Vishnu S. Katari, April 30, 1986.

7.  Correspondence:  Kent Lewis (C-E Ai r Preheater, Combustion Engineering,
    Inc.,  Wellsville, NY) and Vishnu S. Katari, June 16,  1986.

8.  Correspondence:  Robert Hablewitze (Pillar Technologies,  Inc., Hartland,
    WI) to Vishnu S. Katari, March 3, 1986.

9.  Correspondence:  Thomas Schmidt (Energy Development  Associates, Itascon,
    IL) to Michael K. Sink, March 7, 1986.

10. Correspondence:  Richard J. Ihde (TEC Systems, DePere,  WI) to  Michael K.
    Sink,  March 11, 1986.

11. Vatavuk, William M. and Neveril, Robert.   "Estimating Costs  of Air-
    Pollution Control Systems, Part II:  Factors  for Estimating  Capital and
    Operating Costs." Chemical Engineering, November 3,  1980, pp.  157-162.

-------
APPENDIX 3A.  LOWER AND UPPER EXPLOSIVE  LIMITS  FOR  VOCs

-------
                          3A-2
TABLE 3A-1.  FLAMMABILITY  CHARACTERISTICS OF  COMBUSTIBLE
              ORGANIC COMPOUNDS IN AIRa»b

Methane
Ethane
Propane
n-Butane
n-Pentane
n-Hexane
n-Heptane
n-Octane
n-Nonane
n-Decane
n-Undecane
n-Dodecane
n-Tridecane
n-Tetradecane
n-Pentadecane
n-Hexadecane
Ethyl ene
P ropyl ene
Butene-1
cis-Butene-2
Isobutylene
3-Methyl -Butene-1
Propadiene
1,3-Butadiene
Acetyl ene
Methyl acetyl ene
Benzene
Toluene
Ethyl benzene
o-Xyl ene
m-Xylene
p-Xyl ene
Cumene
p-Cymene
Cyclopropane
Cyclobutane
Cyclopentane
Cycl ohexane
Ethyl cyclobutane
Mol.
wt.
16.04
30.07
44.09
58.12
72.15
86.17
100.20
114.23
128.25
142.28
156.30
170.33
184.36
108.38
212.41
226.44
28.05
42.08
56.10
56.10
56.10
70.13
40.06
54.09


78.11
92.13
106.16
106.16
106.16
106.16
120.19
134.21
42.08
56.10
70.13
84.16
84.16
LEL,C
% vol .
5.0
3.0
2.1
1.8
1.4
1.2
1.05
0.95
0.85
0.75
0.68
0.60
0.55
0.50
0.46
0.43
2.7
2.4
1.7
1.8
1.8
1.5
2.6
2.0
2.5
1.7
1.3
1.2
1.0
1.1
1.1
1.1
0.88
0.85
2.4
1.8
1.5
1.3
1.2
UEL,d
% vol .
15.0
12.4
9.5
8.4
7.8
7.4
6.7
3.2
2.9
5.6






36
11
9.7
9.7
9.6
9.1

12
100

7.0
7.1
6.7
6.4
6.4
6.6
6.5
6.5
10.4


7.8
7.7

-------
                            3A-3
TABLE 3A-1.
               FLAMMABILITY  CHARACTERISTICS OF COMBUSTIBLE
                ORGANIC  COMPOUNDS  IN
                        (concluded)

Cycloheptane
Methyl cycl ohexane
Ethyl cycl opentane
Ethyl cycl ohexane
Methyl al cohol
Ethyl alcohol
n-Propyl alcohol
n-Butyl al cohol
n-Amyl al cohol
n-Hexyl alcohol
Dimethyl ether
Di ethyl ether
Ethyl propyl ether
Diisopropyl ether
Acetaldehyde
Propionaldehyde
Acetone
Methyl ethyl ketone
Methyl propyl ketone
Di ethyl ketone
Methyl butyl ketone
Mol.
wt.
98.18
98.18
98.18
112.21
32.04
46.07
60.09
74.12
88.15
102.17
46.07
74.12
88.15
102.17
44.05
58.08
58.08
72.10
86.13
86.13
100.16
LEL,
% vol .
1.1
1.1
1.1
0.95
6.7
3.3
2.2
1.7
1.4
1.2
3.4
1.9
1.7
1.4
4.0
2.9
2.6
1.9
1.6
1.6
1.4
UEL,
% vol .
6.7
6.7
6.7
6.6
36
19
14
12
10
7.9
27
36
9
7.9
36
14
13
10
8.2

8.0
Reference 1.

^Most common handbooks  (e.g., Reference 2) provide
 flammability information  for VOCs.

CLEL - lower explosive  limit

     - upper explosive  limit

-------
                             3A-4
             TABLE 3A-2.  CATALYTIC  IGNITION TEMPERATURE
                         FOR  90% CONVERSION3
    Component                        Temperature, °F

Hydrogen                                     220
Acetylene                                    395
Carbon monoxide                              425
Propyne                                      460
Propadiene                                   480
Propylene                                    500
Ethyl ene                                     550
jv-Heptane                                    575
Benzene                                      575
Toluene                                      575
Xylene                                       575
Ethanol                                      600
Methyl ethyl ketone                          700
Methyl isobutyl  ketone                       700
Propane                                      770
Ethyl acetate                                775
Dimethyl formamide                           800
Ethane                                       810
Cyclopropane                                 850
Methane	920
Reference 3.

-------
                                 3A-5

References for Appendix  3A

1.  Hilado, Carlos J., "How to Predict if Materials Burn,"  Chemical
    Engineering,  December 14, 1970, pp. 174-178.

2.  Handbook of Chemistry and Physics,  54th Edition. Cleveland:   The
    Chemical Rubber  Co., 1973-1974, pp. D85-D92.

3.  Organic Chemical  Manufacturing Volume 4:  Combustion Control  Devices,
    (EPA-450/3-80-026T;Research Triangle Park:  U.S. Environmental
    Protection Agency, Emissions Standards and Engineering Division.
    December 1980.   Report 3, p. 1-2.

-------
                               APPENDIX 3B

     This appendix  presents equations to estimate  flue gas and  fuel

requirements of  incineration systems combusting  all  types of waste

gas compositions.   These equations have been derived from energy  and

material balances around the incinerator system.   Figure 3B-1,  a

reproduction of  Figure 3-2, Section 3.2, is a schematic of an incinerator

system.  (All  streams  shown in Figure 3B-1 are also  identified  by the

same subscripts  in  the energy and material balances)
                                               Haste gas fro* the process
                                                            (0)
CoBfaustton
Air* (4)
Auxiliary
Fuel (3)




Conbustlon
Chaad>ero
(2)

Heat Loss U 	
(HI) p
Haste Gas (1)
I
. Catalyst . Heat
F1
Gi
"«,., "*»' <•> (Optional)
I
• Dilution Air* (0)
Flue Gas to
	 •* Vent/Stack/
ABblent (7)
               (a) Hhen required.
               (b) Referred to as Preheat Chamber In
                 the case of catalytic Incinerators.
               (c) Included only In catalytic Incinerators.
       Figure  38-1.   Schematic diagram of an incinerator system.


Energy Balance

The basic energy balance equation around the combustion chamber is:
1  Sensible heat
I    leaving
Sensible heat
  entering   J
Heat released
 from the
combustion of
    VOCs
  From Figure 3B-1, (H5 + HL) -  (H2 + H3  + H4)  =

  where:
       tHeat  released
      from  the combustion
           of fuel


+ Q3h3
                                                                              •J
                      H = Sensible heat of the stream identified by the
                          subscript, Btu/min
                      Q = Flow rate of the stream  identified by the sub-
                          script, scfm

-------
                                  3B-2

                    hi = Waste gas heat content released  upon  combustion,
                         BTU/scf of waste gas
                    h3 = Lower heating value (LHV)  of fuel  (BTU/scf)

Assume              H3 = 0 for fuel  at ambient temperature
                    H4 = 0 for ambient air
                    HL = 10% of H5

Therefore,      1.1 HS - H2 = QI hi  + 0.3 113

Substituting the sensible heat expression H  = Q Cp  AT in  the above  equation
yields:

        1.1 Q5 CP5 AJ5 - Q2 CP2 A T2 = QI h: + Q3 h3                (3B-1)

        where        Q = Flow rate (scfm)
                    CD = Mean heat capacity  for the temperature  interval
                     v   of AT, BTU/ft3 °F
                    AT = Temperature interval  from  TR (70°F) to  T identi-
                         fied by the subscript
                    hi = Waste gas heat content (BTU/scf  of waste gas)
                    h3 = Lower heating value (LHV)  of natural  gas
                         BTU/ft3

Material Balance (see Figure 3B-1)

An (approximate) material balance around the combustion chamber  yields:*

                  Q5 = Q2 + Q3 + Q4                               (3B-2)

where             QS = Flue gas flow rate (scfm)
                  Qg = Waste gas flow rate entering the system (scfm)
                  Q3 = Auxiliary fuel  burned (scfm)
                  Q4 = Ambient air used for  combustion (scfm)

     The quantities of Q£, 0.3, and 0,4 are estimated as follows:

     1) Waste gas entering the combustion chamber  (Q?)

                   = QO For cases of waste gases to which no dilution air
                        is added (i.e., Cases 1,2, and 4 through 6 in
                        Table 3B-1)

                   = QO (he/hd) For cases of waste  gases  to which dilution
                     air is added (i.e., Case 3 in  Table  3B-1)    (3B-3)

          where he = Waste gas heat content  before  dilution, BTU/scf
                hd = Waste gas heat content  after dilution.

*Strictly speaking, equation 3B-2 is a mole  balance,  not  a  material balance.
 However, because the moles (or volumes) of  the reactants (VOC,  fuel, air,
 etc.) entering the combustion chamber/catalyst bed approximately equal the
 moles of products leaving (H20, C02, N2, etc.), equation 3B-2 is accurate—
 at least for purposes of this Manual.

-------
                                 3B-3

     2)  Ambient air used  (Q&)

                       Q4  =  0  For dilute VOC waste  gases  (category 1  in
                            Table 3B-1)

                      Q4  = Q4,VOC + Q4,Fuel                          (3B-4)

          where   Q4 \jnr  = Ambient air used for the combustion of the
                          VOC
                         = Q2  [ani (X  + Y/4 - Z/2)i  - HIQ  ]  4.79
                                                       2
          where       m-j  = Volume content  of ith VOC component in the waste
                          gas
                 X, Y, Z  = Atoms  of C, Hg, and 02 in the  VOC
                      mo  = Volume content  of oxygen in  the  waste gas
                       2

                 0.4,Fuel  = Ambient air used for the combustion of the fuel
                         = 9.58  (base  amount of fuel burned)(1 + E)

          where        E  = Excess air  used, % of total  stoichiometric air
                          requi rement for fuel only

     3)  Auxiliary fuel  burned  (Q-Q

                  0,3 = Base  amount of  fuel burned (calculated  at zero
                       excess  air) + additional amount  of fuel  burned to
                       ensure  raising  the  excess air to the combustion
                       temperature, (i.e., 9.58E [base  amount  of fuel])
                     = Base  amount (1  + K)

          where    K = Excess  amount used, % of base amount

     The value of K can be determined  as follows:

     (Additional  fuel  used)

           = [9.58 (base  amount  of fuel) E + Additional fuel]  Cp5 ATs * (13*

          Therefore,

             Additional fuel used                                  (3B-5)
         K = Base amount  of  fuel

           = 9.58E/[(h3/CP5  AT5)  - 1]

           = Constant for a  given fuel and known values of  E and "t§

           = 0 for dilute  VOC  waste gases.
*In other words,  the  "additional  fuel" must heat both the  excess  air used
 in combustion  of the base fuel and itself, from the ambient  (reference)
 temperature to the combustion  temperature

-------
                                  38-4

Estimation of Combustion Flue Gases Generated
     Substituting the values of Q2, QS,  and  (fy  into the basic material
balance equation (Equation 3B-2) yields  the  following  expression:
             Q5 = Q2 + Q3 + Q2 l>i  (* + Y/4 -  Z/2), - mg  ] 4.79       (3B-6)
                  + 9.58 (base amount  of fuel)(l  + E)
However, the base amount of fuel = Q3/(l + K),  so that:
             Q5 = Q2 + Q3 + Q2 l>1  (X + Y/4 -  1/2) \ - m0  ] 4.79
                                                       2
                  + 9.58 Q3 (1 + E)/(l + K)                           (3B-7)
                = Q2 + Q3 (f°r dilute  VOC waste gases)
     The above equation applies to the waste gases to  which ambient air
is added for combustion purposes. However,  in  many cases, the waste  gas
contains air sufficient to provide partial or complete combustion air
requirements.  Table 3B-1 identifies various waste gas types and their
ambient air and auxiliary fuel requirements. Table 3B-2 presents the
equations for estimating the flue gas  (Qs) flow rate from the combustion
of each type of waste gas.
Estimation of Actual Amount of Auxiliary Fuel Burned (($3)
     Substituting the material balance equation (Equation 3B-2) into  the
energy balance equation (Equation 3B-1)  and  solving for Q3/Q2 (i.e.,  the
amount of fuel required per unit of waste gas flow rate) yields the
following expression:
 ?L_ LI [1 + Umi (X + Y/4 - 112)t-  mQ2)4.793 CpsATs-CCpoATo+hi]
 Q2 "         (h3 - 1.1 Cp5 AT5) - iO.54 (1  + E)  Cp5 AT5/(I + K)   (3B-8)

         1.1 Cps ATt; - Cp? AT? - hT    ,    ,., fc
       •	h!| - 1.1 Cps AT5 	   (for dTlute waste gases)
     The values of all items in the  above equation are specific to the
waste gas composition and fuel type.   Therefore,  the equation can be  further

-------
                                                           3B-5
                                     TABLE 3B-1.   CATEGORIZATION  OF  WASTE GAS STREAMS
Category
              Waste gas
Composition
Auxiliaries and other requirements
           Mixture of VOC, air, and inert gas with >16% 02
           and a VOC content <25% LEL (i.e., heat content
           <13 Btu/ft3)

           Mixture of VOC, air, and inert gas with >16% 02
           and a VOC content between 25 and 50% LEL (i.e.,
           heat content between 13 to 26 Btu/ft3)

           Mixture of VOC, air, and inert gas with <16% 02
           Mixture of VOC and inert gas with zero to
           negligible amount of 02 (air) and <100 Btu/scf
           heat content

           Mixture of VOC and inert gas with zero to
           negligible amount of 02 (air) and >100 Btu/scf
           heat

           Mixture of VOC and inert gas with zero to negligi-
           ble amount of 02 and heat content insufficient to
           raise the waste gas to the combustion temperature
                                       Auxiliary fuel  is  required.  No  auxiliary
                                       air is  requi red.
                                       Dilution  air is  required  to lower the heat
                                       content to  <13 Btu/ft3.   (Alternative to
                                       dilution  air is  installation of LEL monitors.)

                                       Treat  this  waste stream the same as cate-
                                       gories 1  and 2,  except augment the portions
                                       of the waste gas used for fuel burning with
                                       outside air to bring its  02 content to above
                                       16 percent.

                                       Oxidize it  directly with  a sufficient amount
                                       of ai r.
                                       Premix  and  use  it  as  a  fuel.
                                       Auxiliary fuel  and  combustion air for both
                                       the waste gas VOC and  fuel  are  required.

-------
                                            3B-6
Waste gas
category
                 TABLE 3B-2.  EQUATIONS FOR ESTIMATING FLUE GAS QUANTITIES
              Equations for flue gas flow rate (Qs), scfm
    1

    2

    3
    5

    6
Q5 = Q2 + Q3» where Q2 * Qo

Q5 = Q2 + Q3. where Q2 = QO (he/hd)

Q5 = Q2 + Q3 + Q4,Fuel > where

     °.4,Fuel = 9>58 (1+E) (Base amount of fuel used)

   = 9.58 Q3 (1+E)/(1+K)
              Q5 = Q2 + Q2 [aii (X + Y/4 - Z/2)i - mo ] 4.79 (1+E)
                                                     2
              Assumes no auxiliary fuel except for pilot is needed
P remix and use it as a fuel.

Q5 = Q2 + Q3 + 9.58 Q3 (1
                                     Q2 \^\ (X + Y/4 - Z/2)i -
m0 ] 4.79
  2

-------
                                 3B-7

simplified by substituting known values of these items.
     The values of Cp and K are established based on the waste gas
temperature, flue gas combustion temperature, and the type of fuel used
The overall  Cp value  of the flue gas is calculated more accurately from
the Cp values of the  flue gas components, which include C02, ^0, 02,
and N2.  Alternatively, as an approximation, the Cp value of air can be
substituted  for Cp values of the flue gas and the waste gas.  The mean
heat capacity values  for air are 0.0194, 0.0196, and 0.0198 BTU/ft3°F
for combustion temperatures of 1,600, 1,800, and 2,000°F, respectively.
The mean heat capacity value of air, to use with a waste gas at 100°F,
is 0.018 BTU/ft3°F.
     At a combustion  temperature of 1,600°F, K = 0.033 for a LHV of 900
BTU/ft3 for natural gas, an excess air of 10 percent, and a reference
temperature of 70°F.   When this value of K and the values of Cps' and
 ATs1 are substituted into equation 3B-8, assuming the waste gas
temperature to be 100°F, we obtain:
                     -  U8 hi + 293 < E mi 
-------
                                            3B-8
                  TABLE 3B-3.  EQUATIONS FOR ESTIMATING FUEL  REQUIREMENTS
Waste gas
category
T^
2a
3b,c
4
5
6


1.1 CpsAT^ - Cjp^AT? - hi
h3 - 1.1 Cp5AT5
1.1 Cp5At5 - Cp2ATo - h}
h3 - 1.1 Cp5AT^
1.1 CpciATt; - Cp2A
(h3 - 1.1 CP5AT5) - 10.
1.1 CpRATR + 1.1 [Smi (X
Waste gas is premixed an
Q3 1.1 [1 + (Emi (X +
Q2 " (h3 - LI
General eguation for fuel,
ft3/ft3 of waste gas


T, - h,
54 Cps AT5 (1+E)_/(1+K)
+ Y/4 - Z/2)i] 4.79 (1+E) Cp^ATR - Cp?AT? - hi
d used as fuel .
Y/4 - Z/2)i - m02) 4.79] Cp5AT5 - [Cp9AT9 + h, ]
Cp5AT5) - 10.54 (f+E) Cp5AT5/(l+K)
aThe waste gas for this category must be adjusted  for dilution  (See Table 3B-2).

bE - Excess ai r used
CK - Constant = 9.58E/[(h3/Cp5AT5)  - 1].

-------
                                 Section 4
                              CARBON ADSORBERS
                            William M.  Vatavuk
                      Economic Analysis Branch, OAQPS
                  William L.  Klotz  and  Robert L. Stallings
                        Research  Triangle Institute
                    (Research Triangle  Park, NC  27709)

 4.1   Process Description
      4.1.1   Introduction
      In air pollution control, adsorption  is employed to remove volatile
 organic compounds (VOC's)  from low to  medium concentration gas streams,
 when a stringent outlet concentration  must be met and/or recovery of the
 VOC  is desired.   Adsorption  itself is  a phenomenon where gas molecules
 passing through  a bed of solid particles are selectively held there by
 attractive  forces which are  weaker and less specific than those of
 chemical  bonds.   During adsorption, a  gas molecule migrates to the surface
 of the solid where it is held by physical atttraction releasing energy—
 the  "heat of adsorption",  which  approximately equals the heat of condensation.
 Adsorptive  capacity of the solid for the gas tends to increase with the
 gas  phase concentration.
      Some gases  form actual  chemical bonds with the adsorbent surface
 groups.  This phenomenon is  termed "chemisorption".
      Most gases  ("adsorbates") can be  removed ("desorbed") from the
 adsorbent by heating to a  sufficiently high temperature, usually via
 steam, or by reducing the pressure to  a sufficiently low value (vacuum
 desorption).  The physically adsorbed  species in the smallest pores of
 the  solid and the chemisorbed species  may  require rather high temperatures
 to be removed, and for all  practical purposes cannot be desorbed during
'regeneration.  For example,  approximately 3 to 5 percent of organics
 adsorbed on virgin activated carbon is either chemisorbed or very

-------
                                   4-2

strongly physically adsorbed  and,  for all  intents,  cannot  be  desorbed
during regeneration.(1)
     Adsorbents in large scale  use include activated  carbon,  silica gel,
activated alumina, synthetic  zeolites,  fuller's earth,  and other  clays.
This Section is oriented toward the use of activated  carbon,  a  commonly
used adsorbent for VOCs.
     4.1.2  Types of Adsorbers
     Five types of adsorption equipment are used  in collecting  gases: (1)
fixed regenerable beds;  (2) disposable/rechargable  cannisters;  (3)
traveling bed adsorbers; (4)  fluid bed  adsorbers; and  (5)  chromatographic
baghouses.C2)  Of these, the  most  commonly used in  air  pollution  control are
the fixed bed and cannister types.
     4.1.2.1  Fixed-bed  Units
     Fixed-bed units are normally  used  for controlling  continuous,  VOC-
containing streams over  a wide  range of flowrates,  ranging from several
thousand to several hundred thousand cubic feet/minute  (cfm).   The  VOC
concentration of streams treated by fixed-bed adsorbers  can be  as low as
several parts per billion (ppbv) by volume in the case  of  some  toxic
chemicals or as high as  25% of  the VOCs'  lower explosive limit  (LEL).
For most VOCs, this ranges from 2500 to 10,000 ppmv.(^)  Fixed-bed adsorbers
may be operated in either intermittent  or  continuous modes. In  intermittent
operation, the adsorber  removes VOC for a  specified time (the "adsorption
time"), which corresponds to  the time during which the  controlled source
is emitting VOC.  After  the adsorber and the source are  shut  down (e.g.,
overnight), the unit begins the desorption cycle during  which the captured
VOC is removed from the  carbon. This cycle, in turn,  consists  of three

-------
                            :.       4-3

steps:  (1) regeneration of the carbon by blowing steam through the bed
in the direction opposite to the gas flow; (2) drying of the bed, with
compressed air or a fan; and (3) cooling the bed to its operating tempera-
ture via a fan.  (In some designs, the same fan can be used both for bed
drying and cooling.)   At the end of the desorption cycle (which usually
lasts 1 to 1 1/2 hours), the unit sits idle until the source starts up
again.
     In continuous operation a regenerated carbon bed is always available
for adsorption, so that the controlled source can operate continuously
without shut down.  For example, two carbon beds can be provided:  while
one is adsorbing, the second is desorbing/idled.  As each bed must be
large enough to handle the entire gas flowrate while adsorbing, twice as
much carbon- must be provided than an intermittent system handling the
           ,j.                          ___________
same flowrate.  If the desorption cycle is significantly shorter than the
adsorption cycle, it may be more economical to have three, four, or even
more beds operating in the system.  This can reduce the amount of extra
carbon capacity needed or provide some additional benefits, relative to
maintaining a low VOC content in the effluent.  (See Section 4.2 for a more
thorough discussion of this.)
     A typical two-bed, continuously operated adsorber system is shown in
Figure 4-1.  One bed is adsorbing at all times, while the second is
desorbing/idled.  As shown here, the VOC-laden gas enters vessel #1
through valve A, passes through the carbon bed (shown by the shading) and
exits through valve B, from whence it passes to the stack.  Meanwhile,
vessel #2 is in the desorption cycle.  Steam enters through valve C,
passes up through the bed and exits through D.  The steam-VOC vapor

-------
       (Drying/Cooling
                 Air)
        Waste Gas
            (From
           Source)
System Fan
    (Drying/     M
Cooling A1r)     ^^
                    Steam
                                                                   Steam-
                                                                  VOC Vapor^
                                                                        Out
                                                                                      In
                                                                          Cooling
                                                                           Hater
                                                                                      1
  Total
Condenser
                                                                     VOC
                                                                   Condensate ^
                                                                   (To  Storage,
                                                                   Processing)
                                                                                          Decanter
                                                                                         r  Mater
                                                                                           (To Treatment/
                                                                                           Sewer)
                                                                         (To  Stack)
       Figure 4-1.  Typical  Two-Bed, Continuously Operated  Fixed-Bed  Carbon Adsorber System

-------
                                   4-5

mixture passes to a condenser, where cooling water condenses the entire
mixture.  The condensate next passes to a decanter, where the VOC
and water layers are separated.  The VOC layer is conveyed to storage.
If impure, it may receive additional processing, such as distillation.
Depending on its quality (i.e., quantity of dissolved organics), the
water layer is discharged either to a wastewater treatment facility or  to
the sewer.
     Once steaming is completed, valves C and D are closed and valve E  is
opened, to allow, air to enter to dry and cool the bed.  After this is
done, the bed is placed on standby until vessel #1 reaches the end of its
adsorption cycle.  At this time, the VOC-laden gas is valved to vessel  #2,
while vessel #1 begins its desorption cycle, and the above process is
repeated.
     In Figure 4-1, the system fan is shown installed ahead of the vessels,
though it could also be placed after them.   Further, this figure does not
show the pumps needed to bring cooling water to the condenser.  Nor does
it depict the solvent pump which conveys the VOC condensate to storage.
Also missing are preconditioning equipment  used to cool, dehumidify, or
remove particulate from the inlet gases.  Such equipment may or may not
be needed, depending on the condition of the inlet gas.   In any case,
preconditioning equipment will not be covered in this Section.
     4.1.2.2  Cannister Units
     Canm'ster-type adsorbers differ from fixed-bed units, in that they are
normally limited to controlling low-volume, (typically 100 ft3/min, maximum)
intermittent gas streams, such as those emitted by storage tank vents,  where
process economics dictate that toll regeneration or throw-away cannisters

-------
                                   4-6

are appropriate.  The carbon  cannisters may  not be desorbed.   Alternatively,
the carbon may be regenerated at  a  central facility.   Once  the carbon
reaches a certain VOC content, the  unit is shut down,  replaced with
another, and disposed of or regenerated by the  central  facility.   Each
cannister unit consists  of a  vessel, activated  carbon,  inlet  connection
and distributer leading  to the carbon bed, and  an outlet  connection  for
the purified gas stream.(4)  in one design (Calgon's  Ventsorb®),  150 Ibs
of carbon are installed  on an 8-inch gravel  bed, in a  55-gallon drum.
The type of carbon used  depends on  the nature of the  VOC  to be treated.
     In theory, a cannister unit  would remain in service  no longer than a
regenerable unit would stay in its  adsorption cycle.   Doing so would
prevent the allowable outlet  concentration from being  exceeded.  In
reality, however, poor operating  practice may result  in the cannister
remaining connected until  the carbon is near saturation.  This is because:
(1) the carbon (and often  the vessel) will probably be  disposed of,  so
there is the temptation  to operate  it until  the carbon  is saturated; and
(2) unlike fixed-bed units, whose outlet VOC concentrations are monitored
continuously (via flame  ionization  detectors, typically), cannisters are
usually not monitored.  Thus, the user can only guess  at  the  outlet
loading, and could tend  to leave  a  unit in place longer.
     4.1.3  Adsorption Theory
     At equilibrium, the quantity of gas that is adsorbed on  activated
carbon is a function of  the adsorption temperature and  pressure,  the
chemical species being adsorbed,  and the carbon characteristics,  such as
carbon particle size and pore structure.  For a given  adsorbent-VOC
combination at a given temperature, an adsorption isotherm  can be constructed

-------
                                   4-7

which relates the mass of adsorbate per unit weight of adsorbent
("equilibrium adsorptivity") to the partial pressure of the VOC in the
gas stream.  The adsorptivity increases with increasing VOC partial
pressure and decreases with increasing temperature.
     A family of adsorption isotherms having the shape typical of adsorption
on activated carbon is plotted in Figure 4-2.  This and other isotherms whose
shapes are convex upward throughout, are designated "Type I" isotherms.  The
Freundlich isotherm can be fit to a Type I curve; and it is commonly used
in industrial design.(2)
                          we  =   kPm                      (4-1)
                  where:  we  =   equilibrium adsorptivity
                                  (Ib adsorbate/lb adsorbent)
                           P  =   partial  pressure of VOC in gas
                                  stream (psia)
                         k,m  =   empirical parameters
     The treatment of adsorption from gas mixtures is complex and beyond
the scope of this Section.  Except where the VOC in these mixtures have
nearly identical adsorption isotherms, one VOC in a mixture will tend
displace another on the carbon surface.  Generally, VOCs with lower  vapor
pressures will displace those with higher vapor pressures, resulting in
the former displacing the latter previously adsorbed.  Thus, during  the
course of the adsorption cycle the carbon's capacity for a higher vapor
pressure constituent decreases.  This phenomonen should be considered
when sizing the adsorber.  To be conservative, one would normally base
the adsorption cycle requirements on the least adsorbable component  in a
mixture and the desorption cycle on the most adsorbable component.^)
     The equilibrium adsorptivity is the maximum amount of adsorbate the
carbon can hold at a given temperature and VOC partial pressure.  In

-------
I
o
W)
41
.a

o
 o
                                                            CF)
                            (Note:
                  Adsorbate Partial Pressure  (psia)
      Figure 4-2.  FreundHch (Type I) Adsorption  Isotherms

                   For Hypothetical Adsorbate

-------
                                   4-9

actual control systems, however, the carbon bed is never allowed to reach
equilibrium.  Instead, once the outlet concentration reaches a preset
limit (the "breakthrough concentration"), the adsorber is shut down for
desorption or (in the case of cannister units) replacement and disposal.
At the point where the vessel is shut down, the bed VOC concentration may
only be 50% or less of the equilibrium concentration.
     As equation 4-1 indicates, the Freundlich isotherm is a power function
that plots as a straight line on log-log paper.  Conveniently, for the
concentrations/partial pressures normally encountered in carbon adsorber
operation, most VOC - activated carbon adsorption conforms to equation
4-1.  At very low concentrations, typical of breakthrough concentrations,
a linear approximation to the Freundlich isotherm is adequate.  However,
the Freundlich isotherm does not accurately represent the isotherm at
high gas concentrations and thus should be used with care as such concen-
trations are approached.
     Adsorptivity data for several  VOCs were obtained from an activated
carbon vendor and fitted to the Freundlich equation.(5)  These VOCs are
listed in Table 4-1.  The adsorbates listed include aromatics (e.g.,
benzene, toluene), chlorinated aliphatics (dichloroethane),  and one
ketone (acetone).  However, the list is far from all-inclusive.  Additional
isotherm data are available from the activated carbon vendors, handbooks
(such as Perry's Chemical Engineer's Handbook), and the literature.
     Notice that a range of. partial pressures is listed with each set of
parameters, "k" and "m".  (Note:  In one case (m-xylene) the isotherm was
so curvilinear that it had to be split into two parts, each  with a different
set of parameters.)  This is the range to which the parameters apply.

-------
                                     4-10
          Table 4-1  Parameters  for  Selected Adsorption Isotherms3'15
Adsorbate
(1) Benzene
(2) Chlorobenzene
(3) Cyclohexane
(4) Dichloroethane
(5) Phenol
(6) TMchloroethane
(7) Vinyl Chloride
(8) m-Xylene

(9) Acrylonitrile
(10) Acetone
(11) Toluene
Adsorption
Temp. (°F)
77
77
100
77
104
77
100
77
77
100
100
77
Isotherm
Parameters
k m
0.597
1.05
0.508
0.976
0.855
1.06
2.00
0.708
0.527
0.935
0.412
0.551
0.176
0.188
0.210
0.281
0.153
0.161
0.477
0.113
0.0703
0.424
0.389
0.110
Range of
isotherm0
(psia)
0.0001-0.05
0.0001-0.01
0.0001-0.05
0.0001-0.04
0.0001-0.03
0.0001-0.04
0.0001-0.05
0.0001-0.001
0.001 -0.05
0.0001-0.015
0.0001-0.05
0.0001-0.05
a  Reference 5.

b  Each isotherm is of the form:   w = kPm.    (Set text for definition of terms)
   Data are for adsorption on Calgon type "BPL"  carbon (4 x 10 mesh).

c  Equations should not be extrapolated  outside  these ranges.

-------
                                   4-11

Extrapolation beyond this range—especially at the high end—can introduce
inaccuracy to the calculated adsorptivity.
     But high-end extrapolation may not be necessary,  as the following
will show.  In most air pollution control  applications, the system pressure
is approximately one atmosphere (14.696 psia).  The upper end of the
partial pressure ranges in Table 4-1 goes  from 0.04 to 0.05 psia.
According to Dal ton's Law, at a total  system pressure  of one atmosphere
this corresponds to an adsorbate concentration in the  waste gas  of 2,720
to 3,400 ppmv.  However, as discussed  in Section 4.1.2, the adsorbate
concentration is usually kept at 25% of the lower explosive limit (LEL).
For many VOCs, the LEL ranges from 1 to 1.5 volume %,  so that 25% of the
LEL would be 0.25 to 0.375% or 2.500 to 3.750 ppmv, which approximates
the high end of the partial pressure ranges in Table 4-1.
     Finally, each set of parameters applies to a fixed adsorption
temperature, ranging from 77° to 104°  F.  These temperatures reflect
typical operating conditions, although adsorption can  take place as low
as 32°F and even higher than 104°F.  As the adsorption temperature increases
to much higher levels, however, the equilibrium adsorptivity decreases to
such an extent that VOC recovery by carbon adsorption  may become economically
impractical.
4.2  Design Procedure
     4.2.1  Si zing Parameters
     Data received from adsorber vendors indicate that the size  and purchase
cost of a fixed-bed or cannister carbon adsorber system primarily depend on
four parameters:

-------
                                  4-12
     (1)  The volumetric flowrate of the  VOC  laden gas  passing  through
          the carbon bed(s);
     (2)  The inlet and  outlet  VOC mass loadings of the gas  stream;
     (3)  The adsorption time  (i.e., the  time a carbon  bed remains  on-line
          to adsorb VOC  before  being taken off-line for desorption  of
          the bed);
     (4)  The working capacity  of the activated carbon.
     In addition,  the cost  could also be  affected by other stream conditions,
such as the presence/absence of excessive amounts of particulate, moisture,
or other substances which would require the use of extensive  pretreatment
and/or corrosive-resistant  construction materials.
     The purchased cost  depends to a large extent on the volumetric
flowrate (usually  measured  in  actual ft^/min).  The flowrate, in  turn,
determines the size of the  vessels housing the carbon,  the capacities of the
fan and motor needed to  convey  the waste  gas  through the system,  and  the
diameter of the internal  ducting.
     Also important are  the VOC inlet and outlet gas stream  loadings,
the adsorption time, and the working capacity of the carbon.  These
variables determine the  amount  and cost of carbon charged to  the  system
initially and, in  turn,  the cost of replacing that carbon after it  is
exhausted (typically, five  years after startup).  Moreover,  the amount of
the carbon charge  affects the size and cost of the auxiliary  equipment
(condenser, decanter, bed drying/cooling  fan), because  the sizes
of these items are tied  to  the  amount of  VOC  removed by the  bed.   The
amount of carbon also has a bearing on the size and cost of  the vessels.
     To illustrate this  effect, for each  of a range of  flowrates, the VOC
inlet concentration was  increased ten-fold from 500 to  5000  ppm,  while

-------
                                  4-13
the respective flowrates and adsorption times were held constant.   The
resulting purchased costs obtained from a vendor increased by an averaye
of 27%.(6) Part of these increases was needed to pay for the additional
carbon required.  However, some was also needed for enlarging the  adsorber
vessels to accomodate the added carbon and for the additional  structural
steel needed to support the larger vessels.  Also, larger condensers,
decanters, cooling water pumps, etc., were necessary to treat the  more
concentrated VOC streams.  (See Section 4.3.)
     The VOC inlet loading is set by the source parameters, while  the
outlet loading is set by the VOC emission limit.  (For example,  in many
states, the average VOC outlet concentration from adsorbers may  not
exceed 25 ppm.)
     4.2.2  Determining Adsorption and Desorption Times
     The relative times for adsorption and desorption and the adsorber
bed configuration (i.e., whether single or multiple and series or  parallel
adsorption beds are used) establish the adsorption/desorption cycle
profile.  The cycle profile is important in determining carbon and vessel
requirements and in establishing desorption auxiliary equipment  and
utility requirements.  An example will illustrate.  In the simplest case,
an adsorber would be controlling a process which emits a relatively small
amount of VOC intermittently—say, during one 8-hour shift per day.
During the remaining 16 hours the system would either be desorbing or  on
stand-by.  Such a system would only require a single bed, which  would
contain enough carbon to treat eight hours worth of gas flow at  the
specified inlet concentration, temperature, and pressure.  Multiple beds,
operating in parallel, would be needed to treat large gas flows  (>100,OOU
std. ft^/min, generally)^), as there are practical limits to the  sizes

-------
                                  4-14
to which adsorber vessels can  be  built.   But,  regardless  of whether a
single bed or multiple beds were  used, the  system  would only be on-line
for part of the day.
     However, if the  process were operating continuously,  extra carbon
capacity would have to be built into  the  system.   The  amount of this
extra capacity would  depend on the number of carbon  beds  that would be
adsorbing at any one  time, the length of  the adsorption period relative
to the desorption period, and  whether the beds were  operating in parallel
or in series.  If one bed were adsorbing, a second would  be needed  to
come on-line when the first was shut  down for  desorption.   In this  case,
100% extra capacity would be needed.   Similarly, if  five  beds in parallel
were adsorbing at any given time, again only one extra bed would be
needed and the extra  capacity  would be 20%  (i.e.,  l/S>)--provided, of
course, that the adsorption time  were at  least five  times  as long as the
desorption time.  The relationship between  adsorption  time, regeneration
time, and the required extra capacity can be generalized.
     Mc = Mcl x.f                                                   (4-2)
where:  Mc, Mcj = amounts of carbon required for continuous or intermittent
                control  of a given source,  respectively (Ibs)
            f = extra capacity factor (dimensionless)
     The factor, f, is related to the number of beds adsorbing (NA) and
desorbing (NQ) in a continuous system as  follows:
              ND
       f= i +   /NA                                               (4-3)
(Note:  NA is also the number of beds  in an intermittent  system  that  would be
adsorbing at any given time.  The total number of beds  in the  system  would
be NA + N0.)

-------
                                  4-15
     It can be shown that the number of desorbing beds required in a continuous
system (NQ) is related  to the desorption time  (Op), adsorption time (0^), and
the number of adsorbing beds, as  follows:
                    NO
          Q D ie A(  /NA)                                        (4-4)
(Note:   e o is the total time needed for bed  regeneration, drying, and cooling.)
For instance, for an eight-hour adsorption time, in a continuously operated
system of seven beds (six adsorbing,  one desorbing) 0 Q would have to be 1 1/3
hrs or less (8 hrs/6 beds).   Otherwise, additional beds would have to be added to
provide sufficient extra capacity  during desorption.
     4.2.3  Estimating  Carbon Requirement
     4.2.3.1  Carbon Estimation Procedures Developed
     Obtaining the carbon requirement (Mc or Mc  ) is not as straightforward as
                                              I
determining the other adsorber design parameters.  When estimating the carbon
charge, the depth of the approach  used depends on the data and calculational
tools available.  In preparing this  Section of the Manual, we have developed
two procedures for estimating the carbon requirement.  The first procedure,
described in more detail  below, is based to a  large extent on rules-of-thumb.
This procedure, sometimes employed by adsorber vendors, is relatively
simple and easy to use, though it  normally yields results incorporating a
large safety margin.
     The second procedure yields  a more accurate estimate of the carbon
requirement but requires additional  input data.  In addition, the procedure
is of such mathematical complexity that a microcomputer is needed to use
it.  This procedure is  centered on the "BED_SIZE" model, developed by
William L Klotz of Research  Triangle Institute.  The program "...uses a
detailed mathematical description  of the adsorption process to predict the
bed size needed to* maintain  the effluent [outlet] concentration below a

-------
                                 4-16

defined allowable maximum when the inlet concentration is constant over
the time period for operation."^)  Inputs needed to run the program
include the inlet and desired outlet  ("breakthrough") VOC concentrations,
gas stream temperature,  and  the "breakthrough time," which is usually
equal  to the adsorption  time.  Other  inputs needed are the carbon particle
size and bed void fraction  and the gas superficial velocity through the
bed.  (Superficial  velocity is discussed in Section 4.3.1.) As outputs,
the program provides the carbon equilibrium capacity, working capacity
(see below),  the required  bed size (as measured by the bed depth) and
pressure drop, and  the bed  efficiency--"the percent removal of all ad-
sorbate entering the bed up to the breakthrough time."  This efficiency
is calculated by integrating the  ratio of VOC removed to the VOC inlet
rate over the entire adsorption cycle.  (See Section 4.4.3. for more on
this.)
     These BED_SIZE outputs, along with the bed superficial velocity and
other parameters, are input  to a  second model ("CARADS"), developed by
the Economic Analysis Branch.  This model is used to determine the carbon
requirement, size the adsorber vessels, and estimate the system capital
and annual costs in a manner similar  to the rule-of-thumb procedure
detailed in the next sections.  However, where the rule-of-thumb procedure
may be done by hand, a microcomputer  is needed to utilize the CARADS
model.
     4.2.3.2.  Carbon Estimation  Procedure Used in Manual
     The rule-of-thumb carbon esimation procedure is based on the "working
capacity" (wc, Ib VOC/lb carbon).  This is the difference per unit mass
of carbon between the amount of VOC on the carbon at the end of the

-------
                                  4-17

adsorption cycle and the amount remaining on the carbon at the end of the
desorption cycle.  It should not be confused with the "equilibrium capacity" (we)
defined above in Section 4.1.3.  Recall  that the equilibrium capacity
measures the capacity of virgin activated carbon when the VOC has been in
contact with it (at a constant temperature and partial pressure)  long
enough to reach equilibrium.  In adsorber design, it would not be feasible
to allow the bed to reach equilibrium.  If it were, the outlet concentration
would rapidly increase beyond the allowable outlet (or "breakthrough")
concentration until the outlet concentration reached the inlet concentration.
During this period the adsorber would be violating the emission limit.
     The working capacity is some fraction of the equilibrium capacity.
Table 4-2 compiles working capacities for selected VOCs.  These data were
obtained from an adsorber manufacturer.^)  For comparison, Table 4-2 also
shows the equilibrium capacities for some of these VOCs, which were computed
from the parameters given above in Table 4-1 in Section 4.1.  Note that
the working capacities range from 24 to  100% of the respective capacities
at equilibrium, with an average value of 48%.  This average approximates
the rule-of-thumb used by adsorber vendors--that is, working capacity
equals 50% of equilibrium capacity.  Further, like the equilibrium adsorp-
tivity, the working capacity depends upon the temperature, the VOC partial
pressure, and the VOC composition.  The  working capacity also depends on
the flow rate and the carbon bed parameters.
     The working capacity, along with the adsorption time and VOC inlet
loading, is used to compute the carbon requirement for a cannister adsorber
or for an intermittently operated fixed-bed adsorber as follows:

-------
                                     4-1-8
            Table 4-2.   Equilibrium  vs.  Working  Carbon  Capacity for

                                  Selected  VOCs(8)
Adsorption
Compound Temp. (°F)a
(1) Acetone
(2) Benzene
(3) Cyclohexane
(4) Toluene
(5) m-Xylened
100
77
100
77
77
Partial Carbon Capacities0
Press. (psia)b Equilibrium(we) Working(wc)
0.0147
0.000147
0.00441
0.00294
0.00147
0.0798
0.126
0.163
0.290
0.333
0.08
0.06
0.06
0.07
0.10
wc/we Ratio
1.0
0.48
0.37
0.24
0.30
                                                                     Average  U.48
a Temperature at which equilibrium  capacity  was  measured.
b Directly proportional  to the VOC  concentration  in the  influent (ppmv).
  Calculated as follows:
  Partial  pressure = Cone, (ppmv) x 14.696  psia x 10"6

c Measured as Ib of VOC/lb. of carbon.   Equilibrium capacities were calculated
  using parameters in Table 4-1;  working capacities were obtained from Reference
  8.

d Actually, the compound listed in  Reference  8 was "xylene."   The precise
  structure -- i.e., ortho, meta, or  para --  was  not  given.   However, as the
  molecular weight of all  three is  the  same,  we have  assumed  that the working
  capacity data would apply to m-xylene, as well  as to the other two isomers.

-------
                                  4-19

     Mci = mvoc efl                                               (4-5)
            wc
where:  "WOC = VOC inlet loading (Ib/hr)
Combining this with equations (4-2) and (4-3) yields the general  equation for
estimating the system total  carbon charge:
     Mc = mVOC 6fl (1 +  ND/NA)                                  (4-6)
            wc
Values for wc may be obtained from Table 4-2 or similar data sources.  If
no value for wc is available for the VOC (or VOC mixture) in question,
the working capacity may be estimated at 50% of the equilibrium capacity, as
follows:
     wc = 0.5 we(max)                                           (4-7)
where:  we(max) = the equilibrium capacity (Ib VOC/lb carbon) taken at
                  the adsorber inlet (i.e., the point of maximum VOC
                  concentration).
(Note:  To be conservative, this 50% figure should be lowered if short
desorption cycles, very high vapor pressure consituents, or difficult-
to-desorb VOCs are involved.)
                            *        *         *
     Example:  A source emitting 100 Ib/hr toluene is to be collected in a
carbon adsorber.  The system operates continuously, with two beds  adsorbing
at all times.  For convenience, adsorption and desorption times of 12 and
1.5 hours, respectively, have been chosen.  The total gas flowrate is
35,000 ft3/min at 77°F and 1 atmosphere (or approximately 200 ppmv of VOC).
Assume negligible quantities of particulate and moisture.  Calculate the
system carbon requirement.  Solution:  From Table 4-2, we find the working
capacity of toluene to be 0.07 Ib/lb carbon.  Since the regeneration time

-------
                                  4-20
(1.5 hrs)  is less  than  1/2 the adsorption time  (see eq.  4-4),  one  extra  bed
will be adequate.   Substituting these values into equation  4-6 yields  the
carbon requirement:
     Mc = (100 1b  VOC/hr)(12 hr)  (1 + 1/2)
          0.07 Ib  VOC/lb  carbon
        = approximately 25,700 Ibs.
     As equation 4-6 shows,  the  carbon requirement is directly  proportional
to the adsorption time.   This  would tend to indicate that  a  system  could
be designed with a shorter  adsorption time to minimize the carbon requirement
(and purchased cost).  There is  a trade-off here not readily apparent  from
equation 4-6,  however.   Certainly, a shorter adsorption time would  require
less carbon.  But, it would  also mean that a carbon bed would have  to  be
desorbed more  frequently.   This  would mean that the regeneration steam
would have to  be supplied to the bed(s) more frequently to remove  (in  the
long run) the  same amount of VOC.  Further, each time the  bed is regenerated
the steam supplied must  heat the vessel and carbon, as well  as  drive off
the adsorbed VOC.  And  the  bed must be dried and cooled after each  desorption,
regardless of  the amount of  VOC  removed.  Thus, if the bed is regenerated
too frequently, the bed  drying/cooling fan must operate more often, increasing
its power consumption.   Also, more frequent regeneration tends  to shorten
the carbon life.  As a  rule-of-thumb, the optimum regeneration  frequency for
fixed-bed adsorbers treating streams with moderate to high VOC  inlet
loadings is once every  8 to  12 hours.(1)
4.3  Estimating Total Capital  Investment
     An entirely different  procedure should be used in estimating the

-------
                                  4-21

purchased costs of fixed-bed and canm'ster-type adsorbers.  Therefore,
they will be discussed separately.
     4.3.1  Fixed-Bed Systems
     As indicated in the previous section, the purchased cost is a function
of the volumetric flowrate, VOC inlet and outlet loadings, the adsorption
time, and the working capacity of the activated carbon.  As Figure 4-1
shows, the adsorber system is made up of several different items.   Of
these, the adsorber vessels and the carbon comprise nearly 3/4 of  the
purchased cost.  There is also auxiliary equipment, such as fans,  pumps,
condensers, decanters, and internal piping.  But because these usually
comprise a small part of the total purchased cost, they may be "factored"
from the costs of the two major items without introducing significant
error.  The costs of these major items will be considered separately.
     4.3.1.1  Carbon Cost
     This cost (Cc,$) is simply the product of the initial carbon  require-
ment (Mc) and the current price of carbon.  As adsorber vendors buy carbon
in very large quantities (million-pound lots or larger), their cost is
somewhat lower than the list price.  Current vendor costs typically
range from $1.60 to $2.00/lb (spring 1986 dollars).  Taking the midpoint
of this range, we have:
              Cc = 1.80 Mc                                         (4-8)
     4.3.1.2  Vessel Cost
     The cost of an adsorber vessel is primarily determined by its dimen-
sions which, in turn, depend upon the amount of carbon it must hold
and the superficial gas velocity through the bed that must be maintained
for optimum adsorption.  The desired superficial velocity is used  to calculate

-------
                                  4-22

the cross-sectional  area  of  the  bed  perpendicular to the  gas  flow.   An
acceptable superficial  velocity  is established empirically,  considering
desired removal  efficiency,  the  carbon  particle  size and  bed  porosity,
and other factors.   For example,  one adsorber vendor recommends  a superficial
bed velocity of  85  ft/min(6),  while  an  activated carbon manufacturer cautions
against exceeding 60 ft/min  in systems  operating at one atmosphere.(5)
Another vendor uses  a 65  ft/min.  superficial face velocity  in sizing its
adsorber vessels.(9) Lastly, there are  practical limits to  vessel  dimensions
which also influence their sizing.   That  is, due to shipping  restrictions,
vessel  diameters rarely exceed 12 feet, while their length  is generally
limited to 50 feet.(9)
     The cost of a  vessel  is usually correlated  with its  weight.   However,
as the weight is often  difficult  to  obtain or calculate,  the  cost may be
determined from  the  external surface area.  This is true  because  the
vessel  material  cost — and  the  cost of fabricating that  material  —
is directly proportional  to  its  surface area.  The surface  area  (S,  ft^)
of a vessel is a function  of its  length (L) and diameter  (D), which  in turn,
depend upon the  superficial  bed  face velocity, the L/0 ratio, and other
factors.
     Most commonly,  adsorber vessels are  cylindrical in shape and erected
horizontally (as in  Figure 4-1).   In these cases, it can  be shown that:
          D = 0.127M V                                             (4-9)
                  Q
and:      L = 7.87(q'/vb)2                                           (4-10)
               'c
where:     v& = bed superficial velocity  (ft/min)
            i
          MC  = carbon  requirement per vessel  (Ibs)

-------
                                  4-23
           Q' = volumetric flowrate per^ adsorbing vessel (ft^/min)
Equations (4-9) and (4-10) also assume that the carbon occupies 1/3 of
the vessel volume(6»9) and that the carbon's bulk density is 30 lb/ft3.
     Finally, for a cylinder:
     S =    » D(L + D/2)                                               (4-11)
Similar equations can be developed for other vessel shapes, configurations,
etc.
     Based on vendor data, we developed a correlation between adsorber
vessel cost and surface area:(9)
     Cv = exp [18.827 - 3.3945 InS + 0.3090 (InS)2]               (4-12)
     where:  Cv = vessel cost (spring 1986 $), F.O.B. vendor
     and:  228 
-------
                                  4-24

points derived from costs supplied by an  equipment  vendor  (9),  we found
that, depending on the total  gas  flowrate (Q),  the  cost  of the  carbon and
vessels together comprised from 50% to 85% of the total  adsorber equipment cost.
These data points spanned a gas flowrate  range  of 4,000  to 500,000 scfm.  The
average of these points was 72%,  with a standard deviation of 16%.  Taking the
reciprocal of this average (i.e.,  1/0.72  = 1.39), we  can write:
        CA = 1.39[CC + CVJ                                             (4-13)
where:  Cc = cost of carbon
        Cv = cost of vessel(s)
        C/\ = cost of adsorber equipment
4.3.1.4.  Total Capital Investment
     As discussed in Section 2, in the methodology  used  in this  Manual, the
total capital investment (TCI)  is  estimated from the  total  purchased cost via
an overall direct/indirect installation cost factor.   A  breakdown of that
factor for carbon adsorbers is  shown in Table 4-3.  As Section  2 indicates,
the TCI also includes costs for land, working capital, and off-site facilities,
which are not included in the direct/indirect installation factor.  However,
as these items are rarely required with adsorber systems,  they  will  not be
considered here.  Further, no factors have been provided for  site preparation
(S.P.) and buildings (lildg.), as  these site-specific  costs depend very
little on the purchased equipment  cost.
     Note that the installation factor is applied to  the total  purchased
equipment cost, which includes  the cost of the  stack  and external ductwork
and such costs as freight and sales taxes (if applicable).   ("External  ductwork"
is that ducting needed to convey  the exhaust gas from the  source to the
adsorber system, and then from  the adsorber to  the  stack.   Costs for ductwork

-------
                                   4-25


Table 4-3.  Direct and Indirect Installation Factors  for Carbon Adsorbers3


Cost Item                            Cost Factor (Fraction  of  Indicated Cost)


DIRECT COSTS

 1) Purchased equipment cost

     Adsorber                               As  required)
     Auxiliary equipment"                   As  requi redj "
     Instruments and controls0                       0.1  A
     Taxes                            .             0.03  A
     Freight                                       0.05  A	  	
       Total Purchased Equipment cost                            B(=1.18A)

  2) Installation direct costs

     Foundations and supports                       0.08  B
     Erection and handling                          0.14  B
     Electrical                                     0.04  B
     Piping                                         0.02  B
     Insulation                                     0.01  B
     Painting                                       0.01  B
     Site preparation (S.P.), Buildings  (Bldg.)    As requi red	
       Total Installation Direct Costs               0.30  B + S.P. + Bldg.

       Total Direct Cost                                    1.30B + S.P. + Bldg.

INDIRECT COSTS

     Engineering and supervision                    0.10  B
     Construction and field expenses                 0.05  B
     Construction fee                               0.10  B
     Start-up                                       0.02  B
     Performance test                               0.01  B
     Contingency                                    0.03  B	
       Total Indirect Cost                                  0.31B
       Total Direct and Indirect Costs =  Total  Capital       p..616 + S.P. + BIcTgTl
	Investment	

a Reference 11.

b Includes external ductwork, stack, and  any other equipment  normally
  not included with unit furnished by adsorber vendor.

c Instrumentation cost usually included in  cost of vendor-supplied adsorber
  unit.

-------
                                  4-26

and stacks are shown elsewhere  in  this Manual.)   Normally,  the adjustment
would also cover the instrumentation  cost,  but this  cost  is usually included
with the adsorber purchased cost.   Finally,  note  that  these factors reflect
"average" installation conditions  and could  vary  considerably, depending upon
the installation circumstances.
     4.3.2  Cannister Systems
     Once the carbon requirement  is estimated using  the above procedure,
the number of cannisters is determined.   This is  done  simply by dividing
the total carbon requirement (Mc)  by  the  amount of carbon contained by each
cannister (typically, 150 Ibs.).   This quotient,  rounded  to the next
highest digit, yields the required number of cannisters to  control  the
vent in question.
     Costs for a typical cannister (Calgon's Ventsorb®) are listed  in
Table 4-4.  These costs include the vessel,  carbon,  and connections,
but do not include freight or installation  charges.  Note that the  cost
per unit decreases as the quantity purchased increases.   Each cannister
contains Calgon's "BPL" carbon  (4  x 10 mesh), which  is commonly used in
industrial adsorption.  However, to treat certain VOCs, more expensive
speciality carbons (e.g., "FCA  4 x 10") are  needed.  These  carbons  can
increase the equipment cost by  60% or more.(4)
     As fewer installation materials  and  labor are required to install  a
cannister unit than a fixed-bed system, the  composite  installation  factor
is consequently lower.  The only  costs required are  those needed to place
the cannisters at, and connect them to, the  source.  This involves  a
small amount of piping only; little or no electrical work,  painting,
foundations, or the like would be  needed.   Twenty percent of the sum of

-------
                                 4-27


Table 4-4 Equipment Costs  (Spring 1986 $) for a Typical  Cannister Adsorber9

           Quantity	Equipment Cost (each)b


           1-3                                   $687

           4-9                                    659

           10-29                                  622

           _>30                                    579


a Reference 4.

b These costs are F.O.B.,  Pittsburgh, PA.  They do not include taxes  and  freight
  charges.

-------
                                  4-28

the cannister(s) cost, freight  charges,  and applicable sales taxes would
cover this installation cost.
4.4.  Estimating Total Annual  Cost
     As Section 2 of this Manual  explains, the annual  operating cost is
comprised of three components:   direct costs, indirect costs, and
recovery credits.  These will  be considered separately.
4.4.1  Direct Annual Costs
     These include the following expenditures:  steam, cooling water,
electricity, carbon replacement,  operating and supervisory labor, and
maintenance labor and materials.   Of these, only electricity and solid
waste disposal would apply to  the cannister-type adsorbers.
4.4.1.1  Steam:
     As explained in Section 4.1, steam is used during the desorption
cycle.  The quantity of steam  required will depend on  the amount of
carbon in the vessel, the vessel  dimensions, the type  and amount of VOC
adsorbed, and other variables.   Experience has shown that the steam
requirement ranges from approximately ^ tp_ 4_ Ibs of steam/lb of adsorbed
VOC.(6»9)  Using the midpoint  of this range, we can develop the following
expression for the annual steam cost:
  Cs = 3.50X10"3 mvoc 9s ps                                    (4-14)
where:  Cs = steam cost ($/yr)
        9S = system operating  hours (hr/yr)
      mvoc = voc inlet loading (Ibs/hr)
        ps = steam price ($/thous. Ibs)
     If steam price data are unavailable,  one can estimate its cost at
120% of the fuel cost.  For example, if the local price of natural gas

-------
                                  4-29
were $5.00/million BTU, the estimated steam price would be $6.00/million
BTU » $6.00/thousand Ibs.  (The 20% factor covers the capital and annual
costs of producing the steam.)
4.4.1.2  Cooling Hater;
     Cooling water is consumed by the condenser in which the steam-VOC
mixture leaving the desorbed carbon bed is totally condensed.  Most of
the condenser duty is comprised of the latent heat of vaporization (AHV)
of the steam and VOC.  As the VOC AHV are usually small  compared to the
steam AHV (about 1000 BTU/lb), the VOC AHV may be ignored.  So may the sensible
heat of cooling the water-VOC condensate from the condenser inlet temperature
(about 212°F) to the outlet temperature.  Therefore, the cooling water
requirement is essentially a function of the steam usage and the allowable
temperature rise in the coolant, which is typically 30° to 40°F(6).  Using
the average temperature rise (35°F), we can write:
               CCW = 3.43CS Pcw                                     (4-15)
        where:  Ccw = cooling water cost ($/yr)
                pcw = cooling water price ($/thous. gal.)

If the cooling water price is unavailable, use $0.15 to $0.30/thousand
gallons.
4,4.1.3   Electricity:
     In fixed-bed adsorbers, electricity is consumed by the system fan, bed
drying/cooling fan, cooling water pump, and solvent pump(s).  Both the
system and bed fans must be sized to overcome the pressure drop through
the carbon beds.  But, while the system fan must continuously convey the

-------
                                  4-30

total gas flow through the system,  the bed  cooling  fan  is  only used during
a part of the desorption cycle  (one-half  hour  or  less).
     For both fans, the horsepower  needed depends both  on  the gas flowrate
and the pressure drop through the  carbon  bed.   The  pressure drop through
the bed (A PD) depends on several  variables, such as  the adsorption temperature,
bed velocity, bed characteristics  (e.g.,  void  fraction), and thickness.
But, for a given temperature and carbon,  the pressure drop per unit thickness
depends solely on the gas velocity.  For  instance,  for  Calgon's "PCB"
carbon (4 x It) mesh), the following relationship  holds:(5)
      APb/tb =0.03679 vb + 1.107 x  UT4 vb2                           (4-16)
     where:  APD/tb = pressure  drop through bed (inches of water/foot of
                     carbon)
             Vb = superficial bed  velocity  (ft/min)
     The bed thickness (tfc.ft)  is  the quotient of the bed  volume (V^) and the
bed cross-sectional area (Ajj).  For a 30  lb/ft3 carbon  bed density, this
becomes:
     tb = V^  =  0.0333Mc'                                          (4-17)
(For instance, for horizontally-erected  cylindrical  vessels,  Ab=LD.)
     Once APb is known, the system fan horsepower  requirement (hpsf) can be
calculated:
    hpsf = 2.50 x 10"4 Q APS                                         (4-18)
 where:  Q = gas volumetric flowrate  through  system  (ft-^/min)
       APS = total system pressure drop  = APb +  1

     (The extra inch accounts  for  miscellaneous  pressure  losses  through
the external  ductwork and other  parts of the  system.(6))

-------
                                  4-31

     This equation incorporates a fan efficiency of 70% and a motor
efficiency of 90%, or 63% overall.
     The horsepower requirement for the bed drying/cooling fan (hpcf)
is computed similarly.  While the bed fan pressure drop would still
be APt,, the gas flowrate and operating times would be different.  (For
example, to cool a bed from the regeneration temperature to the adsorption
temperature, would require from 3 to 3.5 SCFM/lb of carbon, based on a
30-minute cooling/drying time.)
     The cooling water pump horsepower requirement (hpcwp) would be computed
as follows:
          hpcwp = 2.52 x IP"4 qcwHs                                 (4-19)
                           n
          where:  qcw = cooling water flowrate (gal/min)
                    H = required head (normally 100 feet of water)
                    s = specific gravity of fluid relative to water at 60°F.
                    n = combined pump-motor efficiency
     Equation 4-18 may also be used to compute the solvent pump horsepower
requirement.  In the latter case, the flowrate (qs) would be different, of
course, although the same head—100 ft. of water--could be used.  The specific
gravity would depend on the composition and temperature of the condensed
solvent.  For example, the specific gravity of toluene at 100°F would be
approximately 0.86 at 70° F.  (However, the solvent pump horsepower is usually
very small—usually <0.1 hp.--so its electricity consumption can usually
be neglected.)
     Once the various horsepowers are calculated, the electricity usage
(in kWh) is calculated, by multiplying each horsepower value by 0.746 (the
factor for converting hp to kilowatts) and the number of hours each fan or

-------
                                  4-32

pump operates annually.   For  the  system  fan  and  cooling  water  pump, the hours
would be the annual  operating hours  for  the  system  (es).
     But for the bed drying/cooling  fan, the time  (%) would be much
shorter.  This is dependent on the time  the  bed  fan  is run  during a
desorption cycle, the number  of desorption cycles  per year, the adsorption
time (OA)» and other factors.  For instance,  for a three-bed system, with
a 12-hour adsorption time and a 0.5-hour bed cooling/drying time per
desorption cycle, the bed fan would  operate  8.33 hrs. for every 10U hrs
of on-stream (system) time.
     To obtain the annual electricity cost,  simply multiply kWh by the
electricity price (in $/kWh)  that applies to the facility being controlled
     For cannister units, use equation 4-17  to calculate the fan horsepower
requirement.  However, instead of AP^, use the following to compute the
total cannister pressure drop  (APc, inches  of water):(4) .
      APC = 0.0471QC + 9.29 x 10"4QC2                       .         (4-20)
                                                    •J
     where:  Qc = flowrate through the cannister (ft /min)
4.4.1.4.  Carbon Replacement:
     As discussed above, the  carbon  has  a different  economic life than
the rest of the adsorber system.   Therefore,  its replacement cost must be
calculated separately.  Employing the procedure  detailed in Section 2,
we have:
             CRCC = CRFC (1.08CC  + Ccl)                              (4-21)
             where:   CRFC = capital  recovery factor  for the carbon

                   1.08 = taxes and  freight  factor
                cc»  ccl  = initial  cost of carbon and carbon replacement
                          labor cost, respectively  ($/yr) (F.O.B. vendor)

-------
                                  4-33

     The replacement labor cost covers the labor cost  for  removing  spent
carbon from vessels and  replacing it  with  virgin or  regenerated carbon.
The cost would vary with amount of carbon  being replaced,  the  labor rates, and
other factors.  For example,  to remove and replace a 50,000  -  pound  charge
would require about 16 person-days, which, at  typical  wage rates, is equivalent
to approximately $0.05/lb repl aced.(12)
     A typical life for the carbon is five years.  However,  if the  inlet
contains VOCs that are very difficult to desorb, tend  to polymerize, or react
with other constituents, a shorter carbon  1 ifetime--perhaps  as low  as two
years—would be likely.'•*•'  For a five-year life and 10% interest rate, CRFC
= 0.2638.
4.4.1.5  Solid Waste disposal:
     Disposal costs are rarely incurred  with fixed-bed adsorbers, because
the carbon is almost always regenerated  in place, not  discarded.  In certain
cases, the carbon in cannister units  is  also regenerated,  either off-site
or at a central  regeneration  facility on-site.   However, most  cannister
adsorbers are disposed of once they become saturated.  The entire
cannister--carbon, drum, connections, etc.--is  shipped to  a  secure  landfill.
The cost of landfill disposal  could vary considerably, depending on  the
number of cannisters disposed  of, the location  of the  landfill, etc.
Based on data obtained from two large landfills, for instance, the
disposal cost would range from approximately $35 to  $65 per  cannister
excluding transportation costs.(13,14)
4.4.1.6  Operating and Supervisory Labor:
     The operating labor for adsorbers is  relatively low,  as most systems
are automated and require little attention.  One-half  operator hour  per

-------
                                 4-34

shift is typical. (11)   Add  to  this 15% to cover supervisory labor, as
Section 2 suggests.  The annual labor cost would then be the product of
these labor requirements and their respective wage rates ($/hr) which,
naturally, would  vary  according to the facility location, type of industry,
etc.
4.4.1.7  Maintenance Labor  and Materials:
     Use 0.5 hours/shift  for maintenance labor      and the applicable
maintenance wage rate.  If  the latter data are unavailable, estimate the
maintenance wage rate at  110% of the operating labor rate, as Section 2
suggests.  Finally,  for maintenance materials, add an amount equal to the
maintenance labor,  also per Section 2.
4.4.2  Indirect Annual  Costs
     These include  such costs as capital recovery, property taxes, insurance,
overhead, and administrative costs ("G&A").  The capital recovery cost is
based on the equipment  lifetime and the annual interest rate employed.  (See
Section 2 for a thorough  discussion of the capital recovery cost and the
variables that determine  it.) For adsorbers, the system lifetime is typically
ten years, except for the carbon, which, as stated above, typically needs to
be replaced after five  years. Therefore, when figuring the system capital
recovery cost, one  should base it on the installed capital  cost less the cost
of replacing the carbon (i.e., the carbon cost plus the cost of labor necessary
to replact it).  Substituting the initial carbon and replacement labor
costs from equation 4-21, we obtain:
     CRCS = [TCI -  (1.08CC  + Ccl)] CRFs                              (4-22)
where:  CRCS = capital  recovery cost for adsorber system ($/yr)
        TCI  = total  capital  investment ($)

-------
                                   4-35
       1.08 = taxes and  freight  factor
        Cci = initial carbon cost (F.O.B.  vendor)  and  carbon  replacement
              cost, respectively ($)
       CRFS = capital recovery factor for  adsorber system  (defined  in
              Section 2)„
For a ten-year life and  a  10% annual  interest  rate,  the CRFS  would  be
0.1628.
     As Section 2 suggests,  the  suggested  factor to  use for property taxes,
insurance, and administrative charges is $%  of  the TCI.  Finally, the overhead
is calculated as 60% of  the  sum  of operating,  supervisory, and maintence
labor, and maintenance materials.
     The above procedure applies  to cannister  units as well, except that,
in most cases, the carbon is not  repl aced--the entire unit  is.  Cannisters
are generally used in specialized applications.  The piping and ducting
cost can usually be considered  a  capital  investment with  a  useful life of
ten years.  However, whether the  cannister itself would be  treated as a
capital or an operating expense would  depend on  the particular application
and needs to be evaluated on a  case-by-case basis.
4.4.3  Recovery Credits
     These could apply to the VOC which  is adsorbed, then desorbed, condensed,
and separated from the steam condensate.   However, if the VOC layer contained
impurities or were a mixture of compounds, it  would require further treatment,
such as distillation.  Purification and  separation costs  are beyond the scope
of this Section.  Suffice it to say that  the costs of these operations could
offset and, if large enough, obliterate  any recovery credits.  In any case,
the following equation can be used to  calculate  these credits:

-------
                                  4-36

     where:    PVOC   =  resale  value of the captured VOC ($/lb)
              RC =  recovery credit ($/yr)
              E   =  adsorber VOC control efficiency
     By definition, the efficiency (E) is the difference between the inlet
and outlet VOC mass loadings, divided by the inlet loading.  However, during
an adsorption cycle the outlet VOC loading will increase from essentially
zero at the start of the cycle to the breakthrough concentration at the end
of the cycle. Because the efficiency is a function of time, it should be
calculated via integration over the length of the adsorption cycle.  To do
this would require  knowledge  of the temporal  variation of the outlet loading
during the adsorption  cycle.  If this knowledge is not available to the
Manual user, a conservative approximation of the efficiency may be made by
setting the outlet  loading equal to the breakthrough concentration.
4.4.4  Total Annual  Cost
     Finally, as explained in Section 2, the total annual cost (TAC) is
the sum of the direct  and indirect annual costs, less any recovery credits,
or:
     TAC = DC +  1C  - RC                                          (4-24)

-------
                                   4-37


                          References for Section 4


 1.  Correspondence:   Robert L. Stallings and William Klotz (Research Triangle
     Institute, Research Triangle Park, NC) to William M.  Vatavuk  (U.S.
     Environmental  Protection Agency, Office of Air Quality Planning and
     Standards, Economic Analysis Branch, Research Triangle Park,  NC),
     June 24, 1986.

 2.  Calvert, Seymour and  Englund, Harold M. (eds.).  Handbook  of  Air Pollution
     Control  Technology.   New York:  John Wiley & Sons, 1984, pp.  135-192.

 3.  Handbook of Chemistry and Physics, 54th Edition. Cleveland:   The Chemical
     Rubber Company,  1973-74, pp. D85-D92.
 4.  "Calgon Ventsorb® for Industrial Ai r Purification" (Bui letin  23-56a).
     Pittsburgh:   Calgon Corporation, 1986.

 5.  Adsorption Handbook.   Pittsburgh:   Calgon Corporation, 1980.

 6.  Correspondence:   Richard Selznick (Baron Blakeslee, Inc.,  Westfield, NJ)
     to William M.  Vatavuk, April 23, 1986.

 7.  Klotz, William L., "Documentation for Program 'Bed_Size'".  Research
     Triangle Institute (Research Triangle Park, NC), September 3, 1986.

 8.  Manzone, R.R.  et al.  "Profitability of Recycling Solvents  from Process
     Systems."  Pollution  Engineering, October 1973.

 9.  Correspondence:   James Jessup (M&W Industries, Inc.,  Rural Hall, NC)
     to William M.  Vatavuk, May 16, 1986.

10.  Matley,  Jay (ed.). Modern Cost Engineering.  New York:  McGraw-Hill
     Publications Co., 1984, p. 142.

11.  Vatavuk, William M. and Neveril, Robert. "Estimating  Costs of Air
     Pollution Control  Systems, Part II:  Factors for Estimating Capital
     and Operating  Costs."  Chemical Engineering, November 3, 1980, pp. 157-
     162.

12.  Telephone conversation:  Robert L. Stallings (Research Triangle Institute,
     Research Triangle Park, NC) with William M. Vatavuk,  September 11, 1986.

13.  Correspondence:   William Kitto (Chemwaste, Sulphur, LA) to William M.
     Vatavuk, July 25, 1986.

14.  Correspondence:   Jerry Lockl ear (6SX, Pinewood, SC) to William M.
     Vatavuk, July  25, 1986.

-------
                                  Section  5
                               FABRIC FILTERS
                               James  H.  Turner
                               Andrew S. Viner
                         Research  Triangle Institute
                    (Research  Triangle Park,  N.C.   22709)
                               John 0. McKenna
                                  ETS, Inc.
                           Roanoke, VA  24018-4394
                             Richard  E. Jenkins
                             William M. Vatavuk
                       Economic Analysis Branch, OAQPS

5.1  Process Description
5.1.1  Introduction
     A fabric filter unit consists of one or more isolated compartments
containing rows of fabric filter bags or tubes.  Particle-laden gas passes up
(usually) along the surface of the bags then radially through the fabric.
Particles are retained on the upstream face of the bags while the cleaned gas
stream is vented to the atmosphere.   The filter is operated cyclically
alternating between relatively long periods of filtering and short periods of
cleaning.  During cleaning, dust that has  accumulated on the bags is removed
from the fabric surface and deposited in a hopper for subsequent disposal.
     This device will collect particle sizes ranging from submicron to several
hundred microns in diameter at efficiencies generally in excess of 99 or 99.9
percent.  The dust cake collected on  the fabric is primarily responsible for
such high efficiency.  Gas temperatures up to 500 *F, with surges to 550 °F
can be accommodated routinely.  Most  of the energy used to operate the system

-------
                                    5-2
appears as pressure drop across the bags  and associated hardware and ducting.
Typical values range from 5 to 20 in.  of  water gauge.   Fabric filters are used
where high-efficiency particle collection is required.   Limitations are
imposed by gas characteristics (temperature and corrosivity)  and particle
characteristics (primarily stickiness)  that affect  the  fabric or its operation
and that cannot be accommodated economically.
     Important process variables include  particle characteristics, gas
characteristics, and fabric properties.   The most important design parameter
is the air- or gas-to-cloth ratio (volumetric flow  rate divided by fabric
         3        2
area, (ft /min)/ft ), and the usual operating parameter of interest is
pressure drop across the filter system.   The major  distinguishing operating
feature of fabric filters is the ability  to renew the filtering surface
periodically by cleaning.
5.1.2  Types of Fabric Filters
     Fabric filters can be categorized by several means, including type of
cleaning (shaker, reverse-air, pulse-jet),  direction of gas flow (from inside
the bag towards the outside or vice versa), location of the system fan
(suction or pressure), or size (low,  medium, or high gas flow quantity).
Cleaning methods are discussed more fully in this section, and the other
categories are described in Section 5.2.
5.1.2.1  Shaker Cleaning
     For any type of cleaning, enough energy must be imparted to the fabric to
overcome the adhesion forces holding dust to the bag.   In shaker cleaning,
used with inside to outside gas flow,  this is accomplished by suspending the
bag from a motor-driven hook or framework that oscillates.  Motion may be
imparted to the bag in several ways,  but  the general effect is to create a
sine wave along the fabric.  As the fabric moves outward, accumulated dust on

-------
                                     5-3
the surface moves with the fabric.  When the fabric reaches the limit of its
extension, the patches of dust have enough inertia to tear away from the
fabric and descend to the hopper.
     For small, single-compartment baghouses, a lever attached to the shaker
mechanism may be operated manually at appropriate intervals, typically at the
end of a shift.  In multicompartment baghouses, a timer or a pressure sensor
responding to system pressure drop initiates bag shaking automatically.  The
compartments operate in sequence so that one compartment at a time is cleaned.
Forward gas flow to the compartment is stopped, dust is allowed to settle,
residual gas flow stops, and the shaker mechanism is switched on for several
seconds to a minute or more.  The settling and shaking periods may be
repeated, then the compartment is brought back online for filtering.  Many
large-scale shaker systems employ a small amount of reverse air during the
shaker cycle to assist cleaning by deflating the bags.
     Parameters that affect cleaning include the amplitude and frequency of
the shaking motion and the tension of the mounted bag.  The first two
parameters are part of the baghouse design and generally are not changed
easily.  Typical values are about 4 Hz for frequency and 2 to 3 in. for
amplitude (half-stroke).' '  The tension is set to about 2 Ib/in. of bag
circumference when bags are installed.  Some installations allow easy
adjustment of bag tension, while others require that the bag be loosened and
reclamped to its attaching thimble.
     The vigorous action of shaker systems tends to stress the bags and
requires heavier and more durable fabrics.  In the United States, woven
                                   (2\
fabrics are used almost exclusivelyv ' for shaker cleaning.  European practice
allows the use of felted fabrics at somewhat higher filtering velocities.

-------
                                    5-4
5.1.2.2  Reverse-air Cleaning
     When glass fiber fabrics were introduced,  a gentler means of cleaning the
bags was needed to prevent premature  degradation.   Reverse-air cleaning was
developed as a less intensive way  to  impart  energy  to  the bags.   In this
method, gas flow to the bags is stopped  in the  compartment being cleaned,  and
a reverse flow of air is directed  through the bags.  This reversal  of gas  flow
gently collapses the bags and dust is removed from  the fabric surface by shear
forces developed between the dust  and fabric as the  latter changes  its
contours.  Another difference between reverse-air and  shaker cleaning is the
installation of sewn-in rings to prevent complete collapse of the bag, which
may be greater than 30 ft long, during cleaning.  Without these rings,
collected dust tends to choke the  bag as the fabric  collapses in on itself.
As with multicompartment shaker baghouses, the  same  cycle takes place in
reverse-air baghouses of stopping  forward gas flow  and allowing dust to settle
before cleaning action begins.
     The source of reverse air is  generally  a separate fan capable  of
supplying air for one or two compartments at a  gas-to-cloth ratio similar  to
that of the forward gas flow.
5.1.2.3  Pulse-jet Cleaning
     This form of cleaning uses compressed air  to force a burst of  air down
through the bag and expand it violently. As with shaker baghouses, the fabric
reaches its extension limit and the dust separates  from the bag.  In pulse
jets, however, gas flows are opposite in direction when compared with shaker
or reverse-air baghouses.  Bags are mounted  on  wire  cages to prevent collapse
while the dusty gas flows from outside the bag  to the  inside.   Instead of
attaching both ends of the bag to  the baghouse  structure,  the bag and cage

-------
                                     5-5
assembly generally is attached only at the top.  The bottom end of the
assembly tends to move in the turbulent gas flow and may contact other bags,
which accelerates wear.
     Although some pulse-jet baghouses are compartmented, most are not.  Bags
are cleaned by rows when a timer initiates the burst of cleaning air through a
quick-opening valve.  Usually 10% of the collector is pulsed at a time by
zones.  A pipe across each row of bags carries the compressed air.  The pipe
is pierced above each bag so that cleaning air exits directly downward into
the bag.  Some systems direct the air through a short venturi that is intended
to entrain additional cleaning air.  The pulse interrupts forward gas flow .
only for a few tenths of a second.  However, the quick resumption of forward
flow redeposits most of the dust back on the clean bag or on adjacent bags.
An advantage of online pulse-jet cleaning is the reduction in baghouse size
allowed by not having to build an extra compartment for offline cleaning.
Pulse jets normally operate at two or more times the gas-to-cloth ratio of
reverse-air baghouses.
5.1.3  Auxiliary Equipment
     The typical auxiliary equipment associated with fabric filter systems is
shown in Figure 5-1.  Along with the fabric filter itself, a control system
typically includes the following auxiliary equipment:  a capture device (i.e.,
hood or direct exhaust connection); ductwork; dust removal equipment (screw
conveyor, etc.); fans, motors, and starters; and a stack.  In addition, spray
chambers, mechanical collectors, and dilution air ports may be needed to
precondition the gas before it reaches the fabric filter.  Capture devices are
usually hoods that exhaust pollutants into the ductwork or direct exhaust
couplings attached to a process vessel.  Hoods are more common, yet poorly

-------
Hood
    Direct Exhaust
                                           Dilution Air
                                           Spray Cooler
                                                                         Fabric Filter
w
                                                                                                                         Ul
                                                                                                                         I
                                                                                                                         en
                                                                                                             Stack
                                                                                             Fan
                                                                                    Dust Removal
                                     Mechanical Collector
           Figure 5-1. Typical alternative auxiliary equipment items used with fabric filter control systems.

-------
                                     5-7
designed hoods will allow pollutants to escape.  Direct exhaust couplings are
less common, requiring sweep air to be drawn through the process vessel,  and
may not be feasible in some processes.  Ductwork provides a means of moving
the exhaust stream to the control device.  Spray chambers and dilution air
ports are used to decrease the temperature of the pollutant stream to protect
the filter fabric from excessive temperatures.  When a substantial portion of
the pollutant loading consists of relatively large particles, mechanical
collectors such as cyclones are used to reduce the load on the fabric filter
itself.  The fans provide motive power for air movement and can be mounted
before (pressure baghouse) or after (suction baghouse) the filter.  A stack,
when used, vents the cleaned stream to the atmosphere.  Screw conveyors are
often used to remove captured dust from the bottom of the hoppers.  Air con-
veying systems and direct dumping into containers are also used.
5.1.4  Fabric Filtration Theory
     The key to designing a baghouse is to determine^the face velocity that
produces the optimum balance between pressure drop (operating cost) and
baghouse size (capital cost).  Major factors that affect design face velocity
(or gas-to-cloth ratio), discussed in Section 5.2, include particle and fabric
characteristics and gas temperature.  Although collection efficiency is
another important measure of baghouse performance, it is generally assumed
that a properly designed and well run baghouse will be highly efficient.
Therefore, the design process focuses on the pressure drop.  There are several
contributions to the pressure drop across a baghouse including the pressure
drop from the flow through the inlet and outlet ducts, from flow through  the
hopper regions, and from flow through the bags.  The pressure drop through the
baghouse (excluding the pressure drop across the bags) depends largely on the

-------
                                    5-8
baghouse design and ranges from 1  to  2  Inches  of H2o'  '  in  conventional
designs and up to 3 inches of H^O  in  designs having  complicated  gas flow
paths.  This loss can be kept to a minimum (i.e.,  1  inch of H^O  or less) by
investing in a flow modeling study of the  proposed design.   A study of this
sort would cost on the order of $50,000 (in  1986).  The  pressure drop across
the bags (also called the tubesheet pressure drop) can be as high as 10 inches
of H20 or more.  The duct and hopper  losses  are  constant and can be minimized
effectively through proper design  based on a knowledge of the flow through the
baghouse.  (No.te:  A procedure for estimating  duct pressure losses is given in
the "Ductwork" section of this Manual.) The tubesheet pressure  drop is a
complex function of the physical properties  of the dust  and fabric and the
manner in which the baghouse is designed and operated.
     Fabric filtration is inherently  a  batch process that has been adapted to
continuous operation through clever engineering.  One  requirement for a
continuously operating baghouse is that the  dust collected  on the bags must be
removed periodically.  Shaker and  reverse-air  baghouses  are similar in the
sense that they both normally use  woven fabric bags,  run at relatively low
face velocities, and the filtration mechanism  is cake  filtration.  That is,
the fabric merely serves as a substrate for  the  formation of a dust cake that
is the actual filtration medium.  Pulse-jet  baghouses  generally  use felt
fabrics and run with a high face velocity  (about double  that of  shaker or
reverse-air baghouses).  Some investigators  feel that  the felt fabric plays a
much more active role in the filtration process.  This distinction between
cake filtration and fabric filtration has  important  implications for calcu-
lating the rate of pressure loss across the  filter bags. The theoretical
description of cake filtration is  quite different from that for  fabric
filtration, and the design processes  are quite different.

-------
                                     5-9
     The general equations used to design a baghouse follow beginning with the
reverse air/shake deflate type of baghouse.
5.1.4.1  Reverse Air/Shake Deflate Baghouses
     The construction of a baghouse begins with a set of specifications
including average pressure drop, total gas flow, and other requirements; a
maximum pressure drop is always specified.  Given these specifications, the
designer must determine the maximum face velocity that can meet these
requirements.  The standard way to relate baghouse pressure drop to face
velocity is given by the relation:
     AP(0) = Ssys(*)Vave                                                 (5-1)
where:
       AP(0) = the pressure drop across the filter, in. H20 (a
               function of time, 6)
     S   (0) = system drag, in. H,,0/(ft/min) (a function of time)
        V    = average (i.e., design) face velocity (ft/min)
               (essentially  constant)
For a multicompartment baghouse, the system drag is determined as the sum of
several parallel resistances representative of several compartments.  For the
typical case where the pressure drop through each compartment is the same,  it
can be shown that:
      sys
                    M
i=l
            -1
                                     1
                                        E
                                                        *	          (5-2)
where
         M = number of compartments in the baghouse
     S.. (6) = drag across compartment i

-------
                                    5-10
The compartment drag is a function  of  the  amount  of  dust  collected on the bags
in that compartment.  In general, the  dust will be distributed in a very
nonuniform manner.   That is,  there  will  be a  variation  of dust load from one
bag to the next and within a  given  bag there  will also  be a variation of dust
load from one area  to another.   For a  sufficiently small  area j within
compartment i,  it can be assumed that  the  drag  is a  linear function of dust
load:
where:
          S  = drag of a dust-free (freshly cleaned)  filter bag
          K2 = dust cake flow resistance,  [in.  H20/(ft/min)]/(lb/ft2)
     W.- .-(0) = dust mass per unit area of  area  j  in  compartment i
      1 1 J
If there are N different areas of equal  size within  compartment i,  each with a
different  drag S.  .,  then the total  drag for compartment i  can be  computed in
                ' i J
a manner analogous  to equation (5-2):
      ' -i X" /    • »f*-L»/*-'*.j\w/j»                                           V **  * /
The constants Sg and K~ depend upon  the  fabric  and  the nature and size of the
dust.  The relationships between these constants and the dust and fabric
properties are not understood well enough  to permit accurate predictions and
so must  be determined empirically, either  from  prior experience with the
dust/fabric combination or from laboratory measurements.  The dust mass as a
function of time is defined as:
                  6
                  I (CinV.(0)d0}                                         (5-5)
                  o

-------
                                    5-11
where:
        W  = dust mass per unit area remaining on a "clean" bag
       C^ = dust concentration in the inlet gas (gr/ft )
     Vn. (0} = face velocity in compartment i
It is assumed that the inlet dust concentration and the filter area are
constant.  The face velocity through each compartment changes with time,
starting at a maximum value just after cleaning and steadily decreasing as
dust builds up on the bags.  The individual compartment face velocities are
related to the average face velocity by the expression:
     Vave = E(V1(5)A1}/E{A1}                                             (5-6)
            =  E(V.}/M (for M compartments with equal area)
Equations (5-1) through (5-6) reveal that there is no explicit relationship
between the design face velocity and the tubesheet pressure drop.  On the
contrary, the pressure drop that results from a given design can only be
determined by the simultaneous solution of equations (5-1) through (5-5), with
equation (5-6) as a constraint on that solution.  This conclusion has several
implications for the design process.  The design requires an iterative
procedure:  one must begin with a known target for the average pressure drop,
propose a baghouse design (number of compartments, length of filtration
period, etc.), assume a face velocity that will yield that pressure drop, and
solve the system of equations (5-1) through (5-6) to verify that the calcu-
lated pressure drop equals the target pressure drop.  This procedure is
repeated until the specified face velocity yields an average pressure drop
(and maximum pressure drop, if applicable) that is sufficiently close to the
design specification.

-------
                                    5-12
5.1.4.2  Pulse-Jet Baghouses
     The distinction between pulse-jet baghouses and reverse-air and shake
baghouses is basically the difference between cake filtration and composite
dust/fabric filtration (noncake filtration).   This distinction is more a
matter of convenience than physics.   In reality, pulse-jet baghouses have been
designed to operate in a variety of  modes.   Some pulse jets remain online at
all times and are cleaned frequently.  Others are taken offline for cleaning
at relatively long intervals.  Obviously,  if a compartment remains online long
enough without being cleaned, then the filtration mechanism becomes that of
cake filtration.  A complete model of pulse-jet filtration therefore must
account for the depth filtration occurring  on a relatively clean pulse-jet
filter, the cake filtration that inevitably results from prolonged periods
online, and the transition period between  the two regimes.
     Besides the question of filtration mechanism, there is also the question
of cleaning method.  If a compartment is taken off-line for cleaning, then the
dust that is removed from the bags will fall  into the dust hopper before
forward gas flow resumes.  If a compartment is cleaned while online, then only
a small fraction of the dust removed from  the bag will fall to the hopper.
The remainder of the dislodged dust  will be redeposited (i.e., "recycled") on
the bag by the forward gas flow.  The redeposited dust layer has different
pressure drop characteristics than the freshly deposited dust.  The modeling
work that has been done to date focuses on  the online cleaning method.  Dennis
         (4}
and Klenrnr ' proposed the following  model  of drag across a pulse-jet filter:
     S = Se + (K2)CWC + K2W0                                             (5-7)
where:
         S = drag across the filter

-------
                                    5-14
     The disadvantage of the model represented by equations  (5-7) and  (5-8) is
that the constants, S , 1C, and W , cannot be predicted at this time.  Con-
sequently, correlations of laboratory data must be used to determine the value
of (PE). .  For the fabric-dust combination of Dacron felt and coal fly ash,
Dennis and Klemnr ' developed an empirical relationship between (PE)*wi the
face velocity, and the cleaning pulse pressure.  This relationship  (converted
from metric to English units) was as follows:

                      -0.65
     (PE)&W = 6.08 VP..                                                  (5-10)
where:
      V = face velocity (ft/min)
     P.. = pressure of the cleaning pulse  (usually 60 to 100 psig; see Section
      J   5.4.1.8)
It is not known how well the constants in equation (5-10) would fit the data
for a different dust/fabric combination.  Based on a limited amount of data,
it appears that the power law form of equation (5-10) may be a valid model for
(PE)«W.  However, equation (5-10) can be used as a first approximation to
estimate (PE).W for other fabric-dust combinations.
     Another model that shows promise in the prediction of noncake filtration
pressure drop is that of Leith and Ellenbecker' ' as modified by Koehler and
Leith.^ '  In this model,  the tubesheet pressure drop is a function of the
clean fabric drag, the system hardware, and the cleaning energy.
Specifically:
     AP = (1/2) [Ps + KjVf - ]{(PS - KjVf)2 - 4W0K2/K3}] + KyVf2         (5-11)
where:
     P  = maximum static pressure achieved in the bag during cleaning

-------
                                    5-15
     K, = clean fabric resistance
     Vf = face velocity
     K2 = dust deposit flow resistance
     K3 = bag cleaning efficiency  coefficient
     K  = loss coefficient for the venturi  at the inlet to the bag
Comparisons of laboratory data with pressure  drops computed from equation
(5-11)^     are in close agreement for a  variety of dust/fabric combinations.
The disadvantage of equation (5-11) is that the constants K,,  1C, and K3 must
be determined from laboratory measurements.  The most  difficult one to
determine is the K3 value, which can only be  found by  making measurements in a
pilot-scale pulse-jet baghouse.
5.2  Design Procedures
5.2.1  6as-to-Cloth Ratio
     The gas-to-cloth ratio is difficult  to estimate from first principles.
However, shortcut methods of varying complexity allow  rapid estimation.
Descriptions of three methods of increasing difficulty follow.  For shaker and
reverse-air baghouses, the third method is  best performed with publicly
available computer model programs.
5.2.1.1  Gas-to-Cloth Ratio From Similar  Applications
     Net gas-to-cloth ratio is equal to the total actual  volumetric flow rate
in cubic feet per minute divided by the net cloth area in square feet.  This
ratio reduces to units of feet per minute and affects  pressure drop and bag
life.  After a fabric has been selected,  the  gas-to-cloth ratio can be
determined using Table 5-1.  Column 1 shows the type of dust;  column 2 shows
the gas-to-cloth ratios for woven  fabric; and column 3 shows gas-to-cloth
ratios for felted fabrics.  The net cloth area is determined by dividing the

-------
                                    5-13
        S  = drag of a just-cleaned filter
     (IC)- = specific dust resistance of the recycling dust
        W  = areal density of the recycling dust
        l<2 = specific dust resistance of the freshly deposited dust
        W  = areal density of the freshly deposited dust
This model has the advantage that it can easily account for all three regimes
of filtration in a pulse-jet baghouse, i.e., cake filtration, depth filtra-
tion, and filtration in the transition region.  As in equations (5-1) to
(5-6), the drag and areal densities are functions of time  (0).  However, for a
pulse-jet baghouse with online cleaning, the filtration velocity is relatively
constant.  The pressure drop can thus be expressed as the  sum of a relatively
constant term and a term that increases due to dust build-up:
     AP = (PE)Aw + K2WQV                                                 (5-8)
where:
         AP = pressure drop (in. H20)
          V = filtration velocity (ft/min)
     (PE)Aw = [Se + (K2)CWC] V                                           (5-9)
Equation (5-8) describes the pressure drop behavior of an  individual bag.  To
extend this single bag result to a multiple-bag compartment, equation (5-7)
would be used to determine the individual bag drag and the total baghouse drag
would then be computed as the sum of the parallel resistances as in equation
(5-2).  Pressure drop would then be calculated as in equation (5-1).  It seems
reasonable to extend this analysis to the case where the dust is distributed
unevenly on the bag and then apply equation (5-7) to each  area on the bag,
followed by an equation analogous to (5-4) to compute the  overall  bag drag.
The difficulty in doing this is that one must assume values for W  for each
different area to be modeled.

-------
                                   5-16
                    Table £-1  Gas-tp-Cloth Ratios^7)
                       (ffVnnn)/(firof cloth area)
Dust
Alumina
Asbestos
Bauxite
Carbon Black
Coal
Cocoa, Chocolate
Clay
Cement
Cosmetics
Enamel Frit
Feeds, Grain
Feldspar
Fertilizer
Flour
Fly Ash
Graphite
Gypsum
Iron Ore
Iron Oxide
Iron Sulfate
Lead Oxide
Leather Dust
Lime
Limestone
Mica
Paint Pigments
Paper
Plastics
Quartz
Rock Dust
Sand
Sawdust (Wood)
Silica
Slate
Soap, Detergents
Spices
Starch
Sugar
Talc
Tobacco
Zinc Oxide
Shaker/Woven
Reverse-A1 r/Woven
2.5
3.0
2.5
1.5
2.5
2.8
2.5
2.0
1.5
2.5
3.5
2.2
3.0
3.0
2.5
2.0
2.0
3.0
2.5
2.0
2.0
3. -5
2.5
2.7
2.7
2.5
3.5
2.5
2.8
3.0
2.5
3.5
2.5
3.5
2.0
2.7
3.0
2.0
2.5
3.5
2.0
Pulse Jet/Felt
8
10
8
5
8
12
9
8
10
9
14
9
8
12
5
5
10
11
7
6
6
12
10
8
9
7
10
7
9
9
10
12
7
12
5
10
8
7
10
13
5
Generally safe design values—application requires consideration of particle
 size and grain loading.

-------
                                    5-17
gas-to-cloth ratio into the actual cubic feet per minute flow of the exhaust
gas stream.  For an intermittent-type baghouse that is shut down for cleaning,
this is the total, or gross, cloth area.  However, for continuously operated
filters, the area must be increased to allow the shutting down of one or more
compartments for cleaning.  Table 5-2 provides a guide for adjusting the net
area to the gross area, which determines the size of a continuously cleaned
filter.
5.2.1.2  Gas-to-Cloth Ratio From Manufacturer's Methods
     Manufacturers have developed nomographs and charts that allow rapid
estimation of the gas-to-cloth ratio.  Two examples are given below, one for
shaker-cleaned baghouses and the other for pulse-jet cleaned baghouses.
     For shaker baghouses, Table 5-3 gives a factor method for estimating the
ratio.  Ratios for several materials in different operations are presented,
but are modified by factors for particle size and dust load.  Directions and
an example are included.  Gas-to-cloth ratios for reverse-air baghouses would
be about the same or a little more conservative compared to the Table 5-3
values.
                                                   (g\
     For pulse-jet baghouses, another factor methodv ' has been modified with
equations to represent temperature, particle size, and dust load:

     V = A x B x 2.647T"0'2335 x (0.7471 + 0.0853 In D) x 1.0873 |_'0'06021
                                                                         (5-12)
where:
     V = gas-to-cloth ratio, ft/min
     A = material factor, from Table 5-4
     B = application factor, from Table 5-4
     T = temperature, *F (between 50 and 275)

-------
                            5-18
Table 5-2  Approximate Guide to Estimate Gross Cloth Area
                                                         (8)
Net Cloth Area
(ft2)
1-4,000
4,001-12,000
12,001-24,000
24,001-36,000
36,001-48,000
48,001-60,000
60,001-72,000
72,001-84,000
84,001-96,000
96,001-108,000
108,001-132,000
132,001-180,000
above 180,001
Gross Cloth Area
(ft2)
Multiply by 2
1.5
1.25
1.17
1.125
1.11
1.10
1.09
1.08
1.07
1.06
1.05
1.04

-------
                     Table  5-3   Manufacturer's Factor Method for  Estimating Gas-to-Cloth
                                                  Ratios  for  Shaker Baghouses
   .MATJRJAL	
 lardboaid
 ceds
 lour
 irain
Leather Dust
 Tobacco
Supply Air
Hood. Dust. Chips
              RATIO
                 OPERATION
                1
                2.3.4.5.6.7
                2.3.4.5.6.7
                2,3,4.5.6,7
                1.7.8
                1.4.6.7
                13
                1.6.7
                          3/1 RATIO
                    MATERIAL
                 Asbestos
                 Aluminum Dust
                 Fibrous Mat'l.
                 Cellulose Mat'l.
                 Gypsum
                 Lime (Hydraled)
                 Per lite
                 Rubber Chem.
                 Salt
                 Sand0
                 Iron Scale
                 Soda Ash
                 Talc
                 Machining Operation
                                              OPERATION
                          7.8
                          7.8
                          4.7,8
                          4.7.8
                          3,5.6.7
                          4,6.7
                          4.5.6
                          5.6.7.8
                          3.4.5,6,7
                          5.6.7.9.15
                        1.7.8
                        4.6.7
                        3.4,5.6.7
                        1,8
                                             2.5/1 RATIO
                                                             MATERIAL
                   Alumina
                   Carbon Black
                   Cement
                   Coke
                   Ceramic Pigm.
                   Clay& Brick Dust
                   Coal
                   Kaolin
                   Limestone
                   Rock, Ore Dust
                   Silica
                   Sugar
                                                                         OPERATION
                2.3,4.5.6
                4.5.6.7
                3,4,5.6,7
                2.3,5.6
                4,5.6,7
                2,4.6.12
                2.3.6.7.12
                4,5.7
                2.3,4,5,6,7
                2.3.4.5.6,7
                2.3.4.5.6.7
                3,4,5.6,7
                                                                                      MATERIAL
                                                      2/F"RATib"_'~""_"
                                                             OPERATION
    Ammonium Phos-
    phate Perl.
    Dialomaceous
    Earth
    Dry Pelrochem.
    Dyes
    Fly Ash
    Metal Powders
    Plastics
    Resins
    Silicates
    Starch
    Soaps
2.3.4.5,6,7

4,5.6,7
2.3.4,5,6,7,14
2,3,4,5.6,7
10
2, 3.4.5.6.7,14
2,3,4,5.6.7.14
2,3.4.5.6,7,14
2.3.4.5,6,7.14
6.7
3,4.5.6,7
                                                                                                                  MATERIAL
Activated Charcoal
 arbon Black
Detergents
Metal Fumes,
Oxides and
other Solid
Dispersed
Products
                                                                                                                               OPERATION
2,4,5.6.7
11.14
2.4,5,6.7
10,11
CUTTING
CRUSHING
PULVERIZING -
- 1
-2
  3
                    MIXING
                              -4
SCREENING - 5
STORAGE   - 6
CONVEYING - 7
GRINDING   -8
SHAKEOUT  -9
FURNACE FUME - 10
REACTION FUME- II
DUMPING       - 12
INTAKE CLEANING - 13
PROCESS         - 14
BLASTING        - 15
 B
  FINENESS  FACTOR
              MICRON SIZE
                  >100
                  50-100
                   10-50'
                    3-10
                    1-3
                   <1
              FACTOR
                 1.6
            DUST LOAD FACTOR
    loading GR. CU. FT.
           1 -3
           4-8
           9- 17
          18-40
              40
                     Factor
                      1.2
                      1.0
                       .95
                       .90
                       .85
                                         cn
                             This information constitutes a guide for commonly encountered situations and should  not  be con-
                             sidered a "hard-and-fast" rule. Air-lo-clolh ratios ore dependent on dust loading, size distribution,
                             particle shape and "cohesiveness" of the deposited dust. These conditions must be evaluated for
                             each application. The longer the interval between bag cleaning "Hie lower  the air-to-cloth  ratio
                             must be.  Finely-divided, uniformly sized particles generally form more  dense filter cakes  and re-
                             quire lower air-lo-clolh ratios than when larger particles are  interspersed with the fines.  Sticky,
                             oily particles, regardless of shape or size, form dense filler cakes and require lower air-to-cloth
                             ratios.
                             EXAMPLE:  Foundry shakeout unit handling 26000 CFM and collecting 3500 #/ hr. of sand.  The
                                        particle distribution shows 90% greater than 10 microns. The air is to exhaust to room
                                        in winter, to atmosphere in summer.
                                        3500  */„ ,  -5- 60 3$ - 26000 ^^ X 7000 ° '/«  =15.7 ^

                                       •Chart  A = 3/1  ratio. Chart B — Factor 1.0, Chart C —  .95; 3 ic  1  x  .95  --  2.9 air
                                        to cloth ratio. 26000  ~ 2.9 — 9,000 sq. ft.
  Reprinted with permission from Buffalo  Forge Company  Bulletin AHD-29.

-------
                                    5-20
          Table 5-4   Factors for Pulse-Jet Gas-to-Cloth  Ratios
                                                               (9)
A. Material Factor
15a
Cake mix
Cardboard dust
Cocoa
Feeds
Flour
Grain
Leather dust
Sawdust
Tobacco













12
Asbestos
Buffing dust
Fibrous and
cellulosic
material
Foundry shakeout
Gypsum
Lime (hydrated)
Perlite
Rubber chemicals
Salt
Sand
Sandblast dust
Soda ash
Talc







10
Alumina
Aspirin
Carbon black
(finished)
Cement
Ceramic pig-
ments
Clay and
brick dusts
Coal
Fluorspar
Gum, natural
Kaolin
Limestone
Perchlorates
Rock dust,
ores and
minerals
Silica
Sorbic acid
Sugar

9.0
Ammonium
phosphate-
fertilizer
Cake
Diatomaceous
earth
Dry petro-
chemicals
Dyes
Fly ash
Metal powder
Metal oxides
Pigments,
metallic
and synthetic
Plastics
Resins
Silicates
Starch
Stearates
Tannic acid

6.0b
Activated
carbon
Carbon
black
(molec-
ular)
Deter-
gents
Fumes
and
other
dis-
persed
products
direct
from
reac-
tions
Powdered
milk
Soaps
B. Application Factor
               Nuisance Venting
                 Relief of transfer
                 points, conveyors,
                 packing stations,  etc.

               Product Collection
                 Air conveying-venting
                 mills flash driers
                 classifiers, etc.

               Process Gas Filtration
                 Spray driers, kilns,
                 reactors, etc.
1.0
0.9
0.8
 In general physically and chemically stable materials.

DAlso includes those solids that are unstable in their physical or chemical
 state due to hygroscopic nature,  sublimation,  and/or polymerization.

-------
                                    5-21
     D = mass mean diameter of particle, pm (between 3 and 100)
     L = inlet dust loading, gr/ft3 (between 0.05 and 100)
     For temperatures below 50 *F, use T = 50 but expect decreased accuracy;
for temperatures above 275 °F, use T = 275.  For particle mass mean diameters
less than 3 /tm, the value of D is 0.8, and for. diameters greater than 100 /jm,
D is 1.2.  For dust loading less than 0.05 gr/ft ,  use L = 0.05; for dust
loading above 100 gr/ft , use L = 100.
5.2.1.3  Gas-to-Cloth Ratio From Theoretical/Empirical Equations
     5.2.1.3.1  Shaker and reverse-air baghouses—The system described by
equations (5-1) through (5-6) is complicated;  however, numerical methods can
be used to obtain an accurate solution.  A critical  weakness in baghouse
modeling that has yet to be overcome is the lack of a fundamental description
of the bag cleaning process.  That is, to solve equations (5-1) through (5-6),
the value of W  (the dust load after cleaning)  must be known.  Clearly, there
must be a relationship between the amount and  type of cleaning energy and the
degree of dust removal from a bag.  Dennis et  al.^   ' have developed
correlations for the removal of coal  fly ash from woven fiberglass bags by
shaker cleaning and by reverse air cleaning.  These correlations have been
incorporated into a computer program that generates the solution to the above
system of equations.'  '''  If one were to  apply the correlations
developed with coal ash and woven glass fabrics to  other dust/fabric
combinations, the accuracy of the results would depend on how closely that
dust/fabric combination mimicked the coal ash/woven glass fabric system.
Physical factors that affect the correlation include the particle size
distribution, adhesion properties of the dust  and fabric, and fabric weave,  as
well as cleaning energy.  More research is needed in this area of fabric
filtration.

-------
                                    5-22
     The rigorous design of a baghouse thus  involves  several  steps.  First,
the design goal  for average pressure  drop  (and  maximum pressure drop, if
necessary) must  be specified along  with total gas  flow rate and other
parameters, such as $e and K2 (obtained either  from field or laboratory
measurements).  Second, a face velocity is assumed and the number of
compartments in  the baghouse is computed based  on  the total gas flow, face
velocity, bag size, and number of bags per compartment (typical compartments
in the U.S. electric utility industry use bags  1 ft in diameter by 30 ft long
with 400 bags per compartment).  Standard practice is to  design a baghouse to
meet the specified pressure drop when one compartment is  off-line for
maintenance and  a second compartment  off-line for  cleaning.  The third step is
to specify the operating characteristics of  the baghouse  (i.e., filtration
period, cleaning period, and cleaning mechanism).  Fourth,  the designer must
specify the cleaning efficiency so  that the  residual  dust load can be
estimated.  Finally, the specified  baghouse  design is used to establish the
details for equations (5-1) through (5-6), which are  then solved numerically
to establish the pressure drop as a function of time.   The average pressure
drop is then computed by integrating  the instantaneous pressure drop over the
filtration cycle and dividing by the  cycle time.   If  the  computed average is
higher than the  design specification,  then the  face velocity  must be reduced
                     \
and the procedure repeated.  If the computed average  pressure drop is
significantly lower than the design specification, then the proposed baghouse
was oversized and should be made smaller by  increasing the face velocity and
repeating the procedure.  When the  computed  average pressure  drop comes
sufficiently close to the assumed specified  value, then the design has been
determined.  A complete description of the modeling process can be found in

-------
                                    5-23
the reports by Dennis et al.*  '   '  A critique on the accuracy of the.model
is presented by Viner et al.*  '
     5.2.1.:3.2  Pulse-Jet baghouses—The overall process of designing a pulse
jet baghouse is actually simpler than that required for a reverse-air or
shaker baghouse if the baghouse. remains online for cleaning.  The first step
is to specify what the desired average tubesheet pressure drop should be.
Second, the operating characteristics of the baghouse must be established
(e.g., online time, cleaning  energy).  Third, the designer must obtain values
for the coefficients in either equation (5-10) or equation (5-11) from field,
pilot plant, or laboratory measurements.  Fourth, a value is estimated for the
face velocity and the appropriate equation [(8) or (11)] is solved for the
pressure drop as a function of time for the duration of the filtration cycle.
This information is used to calculate the cycle average pressure drop.  If the
calculated pressure drop matches  the specified pressure drop, then the
procedure is finished.  If not,  then the designer must adjust the face
velocity and repeat the procedure.
5.2.2  Pressure Drop
     Pressure drop for the bags  can be calculated rigorously from the
equations given in the preceding  section if values for the various parameters
are known.  Frequently they are  not known.  For quick estimation, a maximum
pressure drop of 5- to 10-in.  H20 across the baghouse and 10- to 20-in H20
across the entire system can  be  assumed if it contains much ductwork.
     A comparable form of equations (5-1) and (5-3) that may be used for
pressure drop across the fabric  in a shaker or reverse-air baghouse is:
     AP = SeV + K2C.V20                                                 (5-13)

-------
                                    5-24
where:
     AP = pressure drop (In. H20)
     Sg = effective residual drag  of the fabric [in.  H20/(ft/min)]
      V = superficial face velocity or gas-to-cloth ratio (ft/min)
     K0 = specific resistance coefficient of the dust [in.
      *•   H20/(ft/min)]/(lb/ftz)
     C. = inlet dust concentration (lb/ft3)
      9 = filtration time, min
     Although there is much variability, values for Sg may range from about
0.2 to 2 in. H20/(ft/min)  and for  K2 from 1  or 2 to 30 or 40 [in. H20/(ft/
min)]/lb/ft.  Typical values for coal  fly ash are 1 to 4.  Inlet concen-
trations vary from less than 0.05  gr/ft  to  more than 100 gr/ft , but a more
nearly typical range is from 0.5 to 10 gr/ft .   Filtration times may range
from 20 minutes to 8 hours for continuous duty reverse-air and shaker bag-
houses, but 30 minutes to  4 hours  is more frequently  found.   Filtration times
for pulse-jet baghouses range from 2 to 60 minutes, but 5 to 20 minutes is
typical.  For pulse-jet baghouses,  use equations (5-8) and (5-10) to estimate
AP, after substituting C^t for WQ and (PE)Aw for SQ  V.
5.2.3  Particle Characteristics
     Particle size distribution and adhesiveness are  the most important
particle properties that affect design procedures.   Smaller  particle sizes can
form a denser cake, which  increases pressure drop.  As shown in Table 5-3 and
equation (5-12), the effect of decreasing average particle size is a lower
applicable gas-to-cloth ratio.
     Sticky particles may  require  installing equipment that  injects a
precoating material onto the bag surface, which acts  as a buffer that traps

-------
                                    5-25
the particles and prevents them from blinding or permanently plugging the
fabric pores.
5.2.4  Gas Stream Characteristics
     Moisture and corrosives content are the major gas stream characteristics
requiring design consideration.  The baghouse and associated ductwork should
be insulated and possibly heated to avoid condensation.  Both the structural
and fabric components must be considered, as either may be damaged.  Where
structural corrosion is likely, stainless steel substitution for mild steel
may be required, provided that chlorides are not present.  (Most austenitic
stainless steels are susceptible to chloride corrosion.)
5.2.4.1  Temperature
     The temperature of the pollutant stream to be cleaned must be above and
remain above the dew point of any condensables in the stream.  If the
temperature is high and it can be lowered without approaching the dew point,
spray coolers or dilution air can be used to drop the temperature so that
temperature limits of the fabric will not be exceeded.  The additional  cost of
a precooler will have to be weighed against the higher cost of bags with
greater temperature resistance.  The use of dilution air to cool  the stream
also constitutes a tradeoff between a less expensive fabric and a larger
filter necessary to accommodate the additional volume of the dilution air.
Generally, precooling would not be necessary if fabric that will  handle the
temperature and the chemical action of the pollutant stream is available.
(Costs for spray chambers, quenchers, and other precoolers are found in the
"Precoolers" section of the Manual.)  Table 5-5 lists several of the fabrics
in current use and provides information on temperature limits and chemical
resistance.  The column labeled "Flex Abrasion" indicates the fabric's
suitability for cleaning by mechanical shakers.

-------
                                    5-26
           Table 5-5  Properties of Leading Fabric Materials
                                                             (14)
Fabric
Cotton
Cres1anb

Dacron0




Dyne1c


Fiberglasd
Filtron6

Gore-Tex


Nomex0

Nylonc
Orlonc


Polypro-
pylene
Teflon0




Wool
Temp,
.pa
180
250

275




160


500
270

Depends
on
backing
375

200
260



200
450




200
Acid
Resistance
Poor
Good in mineral
acids
Good in most
mineral acids;
di solves par-
tially in con-
centrated H2S04
Little effect
even at high
concentration
Fair to good
Good to
excellent
Depends on
backing

Fair

Fair
Good to excel-
lent in mineral
acids

Excellent
Inert except
to fluorine



Very good
Alkali
Resistance
Very good
Good in weak
alkali-
Good in weak
alkali; fair
in strong
alkali

Little effect
even in high
concentration
Fair to good
Good

Depends on
backing

Excellent at
low temperature
Excellent
Fair to good
in weak alkali


Excellent
Inert except
to tri fluoride,
chlorine, and
molten alkaline
metals
Poor
Flex
Abrasion
Very good
Good to
very good
Very good




Fair to
good

Fair
Good to
Very good
Fair


Excellent

Excellent
Good



Excellent
Fair




Fair to good
 Maximum continuous operating temperatures recommended by the Industrial Gas
 Cleaning Institute.
 American Cyanamid registered trademark.
GDu Pont registered trademark.
 Owens-Corning Fiberglas registered trademark.
eW. W. Criswell  Div. of Wheelabrator-Fry,  Inc.,  trade name.
 W. L. Gore and Co., registered trademark.

-------
                                    5-27
5.2.4.2  Pressure
     Standard fabric filters can be used in pressure or vacuum service but
only within the range of about +25 inches of water gauge.  Because of the
sheet metal construction of the house, they are not generally suited for more
severe service.  However, for special applications, high-pressure shells can
be built.
5.2.5  Pressure or Suction Housings
     The location of the baghouse with respect to the fan in the gas stream
affects the capital cost.  A suction-type baghouse, with the fan located on
the downstream side of the unit, must withstand high negative pressures and
therefore must be more heavily constructed and reinforced than a baghouse
located downstream of the fan (pressure baghouse).  The negative pressure in
the suction baghouse can result in outside air infiltration, which can result
in condensation, corrosion, or even explosions if combustible gases are being
handled.  In the case of toxic gases, this inward leakage can have an advan-
tage over the pressure-type baghouse, where leakage is outward.   The main
advantage of the suction baghouse is that the fan handling the process stream
is located at the clean-gas side of the baghouse.  This reduces  the wear and
abrasion on the fan and permits the use of more efficient fans (backward-
curved blade design).  However, because for some designs the exhaust gases
from each compartment are combined in the outlet manifold to the fan, locating
compartments with leaking bags may be difficult and adds to maintenance costs.
     Pressure-type baghouses are generally less expensive because the housing
must only withstand the differential pressure across the fabric.  In some
designs the baghouse has no external housing.  Maintenance also  is reduced
because the compartments can be entered and leaking bags can be  observed while

-------
                                    5-28
the compartment is in service.  With  a  pressure  baghouse,  the housing acts as
the stack to contain the fumes with the subsequent discharge at the roof of
the structure, which makes it eas-ier  to locate leaking  bags.  The main dis-
advantage of the pressure-type baghouse is  that  the  fan is exposed to the
dirty gases where abrasion and wear on  the  fan blades may  become a problem.
Also, some applications require a  stack for dispersion  of  gaseous pollutants,
negating some of the construction  economics.
5.2.6  Standard or Custom Construction
     The design and construction of baghouses are separated into two groups,
                    (0\
standard and custom,v ' which are  further separated  into low,  medium, and high
capacity.  Standard baghouses are  predesigned and factory  built as complete
off-the-shelf units that are shop-assembled and  bagged  for low-capacity units
(hundreds to thousands of acfm throughput).  Medium-capacity units (thousands
to less than 100,000 acfm) have standard designs, are shop-assembled, may or
may not be bagged, and have separate  bag compartment and hopper sections.
High-capacity baghouses (larger than  50,000 or 100,000  acfm)  can be designed
as shippable modules requiring only moderate field assembly.   These modules
may have bags installed and can be shipped  by truck or  rail.   Upon arrival,
they can be operated singly or combined to  form  units for  larger-capacity
applications.  Because they are preassembled, field  labor  for installation is
less costly.
     The custom baghouse, also high capacity, is designed  for a specific
application and is usually built to the specifications  prescribed by the
customer.  Generally, these units  are much  larger than  standard baghouses.
For example, many are used on power plants.  The cost of the custom baghouse
is much higher per square foot of  fabric because it is  not an  off-the-shelf

-------
                                    5-29
item and requires special setups for manufacture and expensive field labor for.
assembly upon arrival.  The advantages of the custom baghouse are many and are
usually directed towards ease of maintenance, accessibility, and other
customer preferences.  In some very small baghouses, a complete set of bags
must be replaced in a compartment at one time because of the difficulty in
locating and replacing single leaking bags, whereas in custom baghouses,
single bags are accessible and can be replaced one at a time as leaks develop.
5.2.7  Filter Media
     The type of filter material used in baghouses is dependent on the
specific application in terms of chemical composition of the gas, operating
temperature, dust loading, and the physical and chemical characteristics of
the particulate.  A variety of fabrics, either felted or woven, is available
and the selection of a specific material, weave, finish, or weight is based
primarily on past experience.  The type of yarn (filament, spun, or staple),
the yarn diameter, and twist are also factors in the selection of suitable
fabrics for a specific application.  For some difficult applications, Gore-
Tex, a polytetrafluoroethylene (PTFE) membrane laminated to a substrate fabric
(felt or woven) or altered-surface fabrics may be used.  Because of the
violent agitation of mechanical shakers, spun or heavy weight staple yarn
fabrics are commonly used with this type of cleaning, while lighter weight
filament yarn fabrics are used with reverse-air cleaning.
     The type of material will limit the maximum operating gas temperature for
the baghouse.  Cotton fabric has the least resistance to high temperatures
(about 180 °F), while fiberglass has the most (about 500 *F).  The temperature
of the exhaust-gas stream must be well above the dew point of any of its
contained condensables as liquid particles will usually plug the fabric pores

-------
                                    5-30
quickly.  However, the-temperature must be below the maximum limit of the
fabric in the bags.  These maximum limits are given in Table 5-5,
5.3  Estimating Total Capital Investment
     Total capital investment includes costs for the baghouse structure, the
initial complement of bags, auxiliary equipment, and the usual  direct and
indirect costs associated with installing or erecting new structures.  These
costs are described below.
5.3.1  Equipment Cost
5.3.1.1  Bare Baqhouse Costs
     Six types of baghouses will  be considered:
                              Preassembled units

    Intermittent          Shaker                           Figure 5-2
    Continuous            Shaker                           Figure 5-3
    Continuous            Pulse-jet (common housing)       Figure 5-4
    Continuous            Pulse-jet (modular)              Figure 5-5
    Continuous            Reverse-air                      Figure 5-6
                          Field-assembled  units
    Continuous            Any method                       Figure 5-7
     Each figure gives costs for the filter without bags and additional  costs
for stainless steel construction and for insulation.  All  curves are based on
a number of actual quotes.  A least squares line has been  fitted to the quotes
and the line's equation is given.   However, extrapolation  should not be used.
The reader should not be surprised if he obtains quotes that differ from these
curves by as much as +25%.  Significant savings can be obtained by soliciting
multiple quotes.  All units include inlet and exhaust manifolds, supports,

-------
                                    5-31
platforms, handrails, and hopper discharge devices.  The indicated prices are
flange to flange.  Note that the scales on both axes change from one figure to
another to accommodate the differing gas flow ranges over which the various
types of baghouses operate.
     The 304 stainless steel add-on cost is used when such construction is
necessary to prevent the exhaust gas stream from corroding the interior of the
baghouse.  Stainless steel is substituted for all metal  surfaces that are in
contact with the exhaust gas stream.
     Insulation costs are for 3 inches of shop-installed glass fiber encased
in a metal skin.  One exception is the custom baghouse,  which has field-
installed insulation.  Costs for insulation include only the flange-to-flange
baghouse structure on the outside of all areas in contact with the exhaust gas
stream.  Insulation for ductwork, fan casings, and stacks must be calculated
separately as discussed later.
     The first baghouse type is the intermittent service baghouse cleaned by a
mechanical shaker.  This baghouse is shut down and cleaned at convenient
times, such as the end of the shift or end of the day.  Although few units are
sold, they are applicable for operations that require infrequent cleaning.
Figure 5-2 presents the unit cost with price in dollars  plotted against the
                                    15
gross square feet of cloth required.    Because intermittent service baghouses
do not require an extra compartment for cleaning, gross  and net fabric areas
are the same.  The plot is linear because baghouses are  made up of modular
compartments and thus have little economy of scale.  Because of the modular
construction, the price line should not be extrapolated  downward.  Costs for
both types of shaker baghouse include the shaker mechanism.

-------
                 Caution: Do not extrapolate.
                                                     Cost without bags- —
                                                  Stainless steel add on
                                                      Insulation add on
     $ = 1,875 + 0.450 ft 2
0
Source: ETS, Inc.
      6       8       10      12      14


      Gross Cloth Area (1000 ft ^




Figure 5-2. Equipment costs for intermittent shaker filters.
16
18
                                                                                  en
                                                               co
                                                               ro

-------
                                    5-33
     Figure 5-3 presents the same costs for a continuously operated baghouse
cleaned by mechanical shaker.  '    Again, price is plotted against the gross
cloth area in square feet.  As in Figure 5-2, the units are modular in
construction.  Costs for these units, on a square foot basis,  are higher
because of increased complexity and generally heavier construction.
     The third and fourth types are common-housing pulse jets  and modular
pulse jets.  The latter are constructed of separate modules that may be
arranged for offline cleaning, and the former have all bags within one
housing.  The costs for these units are shown in Figures 5-4 and 5-5,
respectively.    The cleaning system compressor is not included.  Note that in
the single-unit (common-housing) pulse jet, for the range shown, the height
and width of the unit are constant and the length increases; thus, for a
different reason than that for the modular units discussed above, the cost
increases linearly with size.  Because the common housing is relatively
inexpensive, the stainless steel add-on is proportionately higher than for
modular units.  Added material costs and setup and labor charges associated
with the less workable stainless steel account for most of the added expense.
                                                         15
Figure 5-6 shows the costs for the reverse-air baghouses.    The construction
is modular and the reverse-air fan is included.  The final type is the custom
baghouse which, because of its large size, must be field assembled.  It is
often used on power plants, steel mills, or other applications too large for
the factory-assembled baghouses.  Prices for these units are shown in
Figure 5-7.15
5.3.1.2  Bag Costs
     Table 5-6 gives the price per square foot of bags by type of fabric and
by type of cleaning system used.  The prices represent about a 10% range.  In
calculating the cost, the gross area as determined from Table  5-2 should be

-------
g 600
o>
       0
                        Caution:  Do not extrapolate.
                                                        Cost without ba
                                                       Stainless steel add on--
                                                         Insulation add on
                                                         i i  i  i i  i i  i  i i  r
10
                     20      30      40      50      60      70
                             Gross Cloth Area (1000ft2)
Source: ETS, Inc.; Fuller Co.
80
90
                                                                                       en
                                                                                       CO
                         Figure 5-3. Equipment costs for continuous shaker filters.

-------
                   Caution: Do not extrapolate.
Insulation add on
 o
Source: ETS, Inc.         GrossCI* Area (10001,2)


               "9- 5.4. Equipment cos(s ,„ pu(M^ niun (commm h^
                                                                            en

                                                                            CO
                                                                            en

-------
CD
CO
CD
0)


I
O

T3
O
O
O
   150
   125
   100
    75
    50
                        Caution: Do not extrapolate.
8
O
c
0)

Q.
"5

S   o
    25
                                    i  i  i  i  i  i  i  i  i
                                    Cost without bags
Stainless steel add on
                                                             Insulation add on
       0
       Source: ETS, Inc.
                                6       8      10       12       14

                                Gross Cloth Area (1000 ft ^



                         Figure 5-5. Equipment costs for pulse-jet filters (modular).
               16
18
                                                                                        cn
                                                                                        i
                                                                                        GO

-------
0
                 Caution: Do not extrapolate.
                                         Cost without baas
                                                 Stainless steel add on
                                                     Insulation add on
                                                                                01
                                                                                I
                                                                                co
10
Source: ETS, Inc.
20      30      40      50      60      70


        Gross Cloth Area  (1000 ft ^



      Figure 5-6. Equipment costs for reverse-air filters.
80
90

-------
O)
g 2500



O

-g 2000
o
o
o
 o
 o
O
0


Q.

"5
(7
111
1500
1000
 500
   0
                         Caution:  Do not extrapolate.
                                                      Cost without bags
                                                  Stainless steel add on
                                                    Insulation add on
        0
        Source: ETS, Inc.
                    100             200             300


                             Gross Cloth Area (1000 ft ^





                         Figure 5-7 Equipment costs for custom-built filters.
400
                                                                                       en
                                                                                       i
                                                                                       co
                                                                                       oo

-------
                                    5-39
                            Table  5-6   Bag Prices,
                          (3rd quarter 1986
Type of Cleaning
Pulse jet, TRD

Pulse jet, BBR

Shaker
Strap top
Loop top
Reverse air with
rings

Reverse air w/o
rl ngs
Bag Diameter
(Inches)
4-1/2 to 5-1/8
6 to 8
4-1/2 to 5-1/8
6 to 8

5
5
8

11-1/2
8
11-1/2
Type

0
0
0
0

0
0
0

0
0
0
PE
.59
.43
.37
.32

.45
.43
.46

.47
.32
.32
PP
0.61
0.44
0.40
0.33

0.48
0.45
NA

NA
NA
NA

1
1
1
1

1
1
1

1
1
1
NO
.88
.56
.37
.18

.28
.17
.72

.69
.20
.16
of Material3
HA
0.92
0.71
0.66
0.58

0.75
0.66
NA

NA
NA
NA
FG
1.
1.
1.
0.

NA
NA
0.

0.
0.
0.
29
08
24
95



99

76
69
53
CO
NA
NA
NA
NA

0.44
0,39
NA

NA
NA
NA
TF
9.05
6.80
8.78
6.71

NA
NA
NA

NA
NA
NA
NA = Not applicable.

Materials:
   PE = 16-oz polyester                FG = 16-oz fiberglass with 10% Teflon
   PP = 16-oz polypropylene            CO = 9-oz cotton
   NO = 14-oz nomex                    TF = 22-oz Teflon felt
   HA = 16-oz homopolymer acrylic

 Bag removal methods:
  TR = Top bag removal (snap in)
  BBR = Bottom bag removal

cldentified as reverse-air bags, but used in low pressure pulse applications.

NOTE:  For pulse-jet baghouses, all bags are felts except for the fiberglass,
       which 1s woven.  For bottom access pulse jets, the cage price for one
       cage can be calculated from the single-bag fabric area using:
In 50 cage lots
In 100 cage lots
In 500 cage lots
   Mild steel  cage

$ * 4.941 + 0.163 ftf
$ = 4.441 + 0.163 ft;
$ = 3.941 + 0.163 ft*
 Stainless steel cage

$ = 23.335 + 0.280 ftf
$ = 21.791 -i- 0.263 ft;
$ = 20.564 + 0.248 ft''
       These costs apply to 4-1/2-1 n. or 5-5/8-1n diameter, 8-ft and 10-ft
       cages made of 11 gauge mild steel and having 10 vertical wires and
       "Roll Band" tops.  For flanged tops, add $1 per cage.  If flow control
       Venturis are used (as they are in about half of the pulse-jet manufac-
       turers' designs), add $5 per cage.

For shakers and reverse air baghouses, all bags are woven.  All prices are for
finished bags, and prices can vary from one supplier to another.  For Gore-Tex
bag prices, multiply base fabric price by factors of 3 to 4.5.
Source:  ETS, Inc.
                  (15)

-------
                                    5-40
used.  Gore-Tex fabric costs are a combination of the base fabric cost and a
premium for the PTFE laminate and its application.   As fiber market conditions
change, the costs of fabrics relative to each other also change.  The bag
prices are based on typical  fabric weights,  in ounces/square yard, for the
fabric being priced.  Sewn-in snap rings are included in the price, but other
mounting hardware, such as clamps or cages,  is an added cost.
5.3.1.3  Auxi1iary Equipment
     The auxiliary equipment depicted in Figure 5-1 is discussed elsewhere in
the Manual.  Because hoods,  precoolers,  cyclones, fans, motors,  and stacks are
common to many pollution control systems,  they are  given extended treatment in
the following tentatively numbered separate  sections:  capture hoods in
Section 16, ductwork in Section 7, precoolers (spray chambers and quenchers)
in Section 18, cyclones in Section 17, fans  and motors in Section 8, and
stacks in Section 11.  If dust-removal equipment is to be considered,
Section 19 discusses screw conveyors.
5.3.2  Total Purchased Cost
     The total purchased cost of the fabric  filter system is the sum of the
costs of the baghouse, bags, auxiliary equipment, instruments and controls;
and of taxes and freight.  The last three items generally are taken as
percentages of the estimated total cost of the first three items.  Typical
values, from Section 2 of the Manual, are 10% for instruments and controls, 3%
for taxes, and 5% for freight.
     Bag costs can vary from less than 15% to more  than 100% of bare baghouse
cost, depending on type of fabric required.   This situation makes it inadvis-
able to estimate total purchased cost without considering both costs, and
prevents effective use of factors to estimate a single cost for the baghouse
and bags.

-------
                                    5-41
5.3.3  Total Capital Investment
     Using the Section 2 methodology, the total capital investment (TCI) is
estimated from a series of factors applied to the purchased equipment cost to
obtain direct and indirect costs for installation.  The TCI is the sura of
these three costs.  The required factors are given in Table 5-7.  Because bag
costs can have such a large effect on total purchased equipment cost, the
factors may cause overestimation of total capital investment when expensive
bags are used.  Using stainless steel components may also cause overestima-
tion.  Because baghouses may vary from small units installed within existing
buildings to large, separate structures, specific factors for site preparation
or for buildings are not given.  However, costs for buildings may be obtained
from such references as Means Square Foot Costs 1986.'  '  Land, working
capital, and offsite facilities are excluded from the table, as they are not
normally required.  For very large installations, however, they may be needed
and would be estimated on an as-needed basis.
     Note that the factors given in Table 5-7 are for average installation
conditions.  Considerable variation may be seen with other-than-average
installation circumstances.
5.4  Estimating Total Annual Costs
5.4.1  Direct Annual Cost
     Direct annual costs include operating and supervisory labor, operating
materials, replacement bags, maintenance (labor and materials), utilities,  and
dust disposal.  Most of these costs are discussed individually below.  They
vary considerably with location and time, and, for this reason, should be
obtained to suit the specific baghouse system being costed.  For example,
current labor rates may be found in such publications as the Monthly Labor
Review, published by the U.S. Department of Labor, Bureau of Labor Statistics.

-------
                                    5-42
            Table 5-7   Capital Cost Factors for Fabric Filters
                                                              (8)
 Direct Costs
        Factor
Purchased equipment costs;

Fabric filter

Bags                                                   A =

Auxiliary equipment
Instruments & controls
Taxes
Freight
         Total purchased equipment cost                    B =

Installation direct costs
    Foundations & supports
    Erection & handling
    Electrical
    Piping
    Insulation for ductwork
    Painting
    Site preparation (S.P.)
    Buildings (Bldg.)
          Total installation direct costs
           Total direct costs
Indirect costs
     Engineering & supervision
     Construction and field expense
     Construction fee
     Startup fee
     Performance test
     Contingencies
          Total indirect costs

   Total direct and indirect costs =  Total  capital  investment
        As
         estimated
Sum of  As
         estimated
        As
         estimated

        0.10 A
        0.03 A
        0.05 A
        1.18 A
        0.04 B
        0.50 B
        0.08 B
        0.01 B
        0.07 B
        0.02 B
        As required
        As required
        0.72 B +
        S.P. +
        Bldg.

        1.72 B +
        S.P. +
        Bldg.
        0.10 B
        0.20 B
        0.10 B
        0.01 B
        0.01 B
        0.03 B
        0.45 B

        2.17 B +
        S.P. +
        Bldg.
 If ductwork dimensions have been established,  cost may be estimated based on
         p
$10-12/ft  of surface for field application.   Fan housings and stacks may also
be insulated.15

-------
                                    5-43
5.4.1.1  Operating and Supervisory Labor
     Typical operating labor requirements are 2 to 4 hours per shift for a
                           fa\
wide range of filter sizes.v '  Small or we11-performing units may require
less time, while very large or troublesome units may require more.
Supervisory labor is taken as 15% of operating labor.
5.4.1.2  Operating Materials
     Operating materials are generally not required for baghouses.  An
exception is the use of precoat materials injected on the inlet side of the
baghouse to provide a protective dust layer on the bags when sticky or
corrosive particles might harm them.  Adsorbents may be similarly injected
when the baghouse is used for simultaneous particle and gas removal.  Costs
for these materials should be included on a dollars-per-mass basis (e.g.,
dollars per ton).
5.4.1.3  Maintenance
     Maintenance labor varies from 1 to 2 hours per shift.' '  As with
operating labor, these values may be reduced or exceeded depending on the size
and operating difficulty of a particular unit.  Maintenance materials costs
                                                   /0\
are assumed to be equal  to maintenance labor costs.v '
5.4.1.4  Replacement Parts
     The major replacement part items are filter bags,  which have a normal
operating life of 1 to 5 years with about 2 years being typical.   The
following formula is used for computing the bag replacement cost:
     CRCg = (CB -i- CL) x CRFg                                            (5-14)
where:
     CRCg = bag capital  recovery cost ($/year)
       C  = initial bag cost including taxes and freight ($)

-------
                                    5-44
       CL = bag replacment labor ($)
     CRFB = capital recovery factor whose value is  a function of the annual
            interest rate and the useful  life of the bags.   (For instance, for
            a 10% interest rate and a  2-year life,  CRFg = 0.5762.)
     The bag replacement labor cost (C.)  will  depend on such factors as the
number, size, and type of the bags; their accessibility;  how they are
connected to the baghouse tubesheet; etc.   For example,  in  a reverse-air
baghouse it would probably take from 10 to 20 man-minutes to change an 8-in.
by 24-ft bag that is clamped in place.  This bag has a filtering surface area
                      o
of approximately 50 ft .  If the replacement labor  rate were $21.12/h
                                                        2
(including overhead),  C.  would be from $0.07 to $0.14/ft  of bag area.  As
Table 5-6 shows, for some bags (e.g.,  cotton),  this  range of C.  would
constitute a significant fraction of the  purchase cost.   For pulse  jets,
replacement time would be about 5 to 10 man-minutes  for a 5-in.  by  10-ft bag
in a top-access baghouse.  These bag replacement times are  based on changing a
minimum of an entire module and on having typical baghouse  designs.  Times
would be significantly longer if only  a few bags were being replaced or if the
design for bag attachment or access were  atypical.
     This method treats the bags as an investment that is amortized over the
useful life of the bags, while the rest of the control  system is amortized
over its useful life (typically 20 years;  see Section 5.4.2).   Values of CRFD
                                                                            D
for bag lives different from 2 years can  be calculated from equation (2-3) of
the Manual.
5.4.1.5  Electricity
     Power is required to operate system  fans and cleaning  equipment.  Fan
power for primary gas  movement can be  calculated from equation (2-7) of the
Manual.  After substituting into this  equation a combined fan-motor efficiency

-------
                                    5-45
                                                   (IB)
of 0.65 and a specific gravity of 1.000, we obtain:v  '
     P.P. = 0.000181(0) (AP)(0)                                          (5-15)
where:
     P.P. = fan power requirement (kWh/yr)
       Q = system flow rate (acfm)
      AP = system pressure drop (in. hLO)
       Q = operating time (h/yr)
     Cleaning energy for reverse-air systems can be calculated from the number
of compartments to be cleaned at one time (usually one, sometimes two), and
the reverse gas-to-cloth ratio (from about one to two times the forward gas-
to-cloth ratio).  Reverse-air pressure drop varies up to 6 or 7 in. H^O
depending on location of the fan pickup (before or after the main system
     (IQ\
fan).v  '  The reverse-air fan generally runs continuously.
     Typical energy consumption in kWh/yr for a shaker cleaning system
                                           (2\
operated 8,760 h/yr can be calculated from:v '
     P = 0.053A                                                         (5-16)
where:
                              2
     A = gross fabric area (ft )
5.4.1.6  Fuel
     If the baghouse or associated ductwork is heated to prevent condensation,
fuel costs should be calculated as required.  These costs can be significant,
but may be difficult to predict.  For methods of calculating heat transfer
requirements, see Perry.*  '
5.4.1.7  Water
     Cooling process gases to acceptable temperatures for fabrics being used
can be done by dilution with air,  evaporation with water, or heat exchange

-------
                                    5-46
with normal equipment.  The last  two cases  require  consumption of plant water,
although costs are not usually significant.   Section 4.4 of the Manual
provides information on estimating  cooling-water costs.
5.4.1.8  Compressed Air
     Pulse-jet filters use compressed air at pressures of about 60 to
                                                                         (2\
100 psig.  Typical consumption is about 2 scfm/1,000 cfm of gas filtered.v '
For example, a unit filtering 20,000 cfm of gas uses about 40 scf of
compressed air for each minute the  filter is operated.
5.4.1.9  Dust Disposal
     If collected dust cannot be  recycled or sold,  it must be landfilled or
disposed of in some other manner.  Disposal  costs are site-specific, but they
may typically run $20 or $30 per  ton exclusive of transportation (see Sec-
tion 2.4) of the Manual.
5.4.2  Indirect Annual Cost
     These include such costs as  capital  recovery,  property tax, insurance,
administrative costs ("G&A"), and overhead.   The capital  recovery cost is
based on the equipment lifetime and the annual  interest  rate employed.  (See
Section 2 for a thorough discussion of the  capital  recovery cost and the
variables that determine it.)  For  fabric filters,  the system lifetime varies
from 5 to 40 years, with 20 years being typical. However,  this does not apply
to the bags, which usually have much shorter lives.   (See Section 5.4.1.4)
Therefore, as Section 2 of the Manual  suggests,  when figuring the system
capital recovery cost, one should base it on the installed capital  cost less
the cost of replacing the bags (i.e.,  the purchased  cost of the bags plus the
cost of labor necessary to replace  them).  In other  words;
     CRCS = [TCI-CB-CL] CRFS                                            (5-17)

-------
                                    5-47
where:
     CRCg = capital recovery cost for fabric filter system  ($/yr)
      TCI = total capital investment ($)
       Co = initial cost of bags including taxes and freight  ($)
       C. = labor cost for replacing bags ($)
     CRF  = capital recovery factor for fabric filter system  (defined in
        s   Section 2).
For example, for a 20-year system life and a 10% annual interest rate, the
CRFS would be 0.1175.
     The suggested factor to use for property taxes, insurance, and
administrative charges is 4% of the TCI.  Finally, the overhead is calculated
as 60% of the sum of operating, supervisory, and maintenance  labor, and
maintenance materials.
5.4.3  Recovery Credits
     For processes that can reuse the dust collected in the baghouse or that
can sell the dust in a local market, such as fly ash sold as  an extender for
paving mixes, a credit should be taken.  As used below, this  credit (RC)
appears as a negative cost.
5.4.4  Total Annual Cost
     Total annual cost for owning and operating a fabric filter system is the
sum of the components listed in Sections 5.4.1 through 5.4.3, i.e.:
     TAG = DC + 1C - RC                                                 (5-18)
where:
     TAC = total annual cost ($)
      DC = direct annual cost ($)
      1C = indirect annual cost ($)
      RC = recovery credits (annual) ($)

-------
                                    5-48
5.4.5  Example Problem
     Assume a baghouse is required for controlling fly ash emissions from a
coal -fired boiler.   The flue gas stream is 50,000 acfm at 325 *F and has an
ash loading of 4 gr/ft .  Analysis of the ash shows a mass median diameter of
7 ^m.  Assume the baghouse operates for 8,640 h/yr (360 d).
Design Gas-to-Cloth Ratio
     The gas-to-cloth ratio (G/C)  can be taken from Table 5-1 as 2.5, for
woven fabrics in shaker or reverse-air baghouses, or 5, for felts used in
pulse-jet baghouses.  If a factor method were used for estimating G/C,
Table 5-3 for shakers would yield the following values:  A = 2, B = 0.9, and
C = 1.0.  The gas-to-cloth ratio would be:
                           2 x 0.9 x 1.0 = 1.8.
This value could also be used for reverse-air cleaning.  For a pulse-jet unit,
Table 5-4 gives a value of 9.0 for factor A and 0.8 for factor B.  Equation
(5-12) becomes:

    V = 9.0 x 0.8 x 2.647 (275)~°*2335 x (0.7471 + 0.0853 In 7)
        x 1.0873
      = 4.69
     Because this value is so much greater than the shaker/reverse-air G/C, we
conclude that the pulse-jet baghouse would be the least costly design.*
    *This conclusion is based on the inference that a much higher G/C would
yield lower capital  and, in turn,  annual  costs.   However,  to make a more
rigorous selection,  we would need to calculate and compare the total annual
costs of all three baghouse designs  (assuming all  three are technically
acceptable}.  The reader is invited  to make this comparison.  Further
discussion of the effects of G/C increases, and  accompanying pressure drop
increases, on overall  annual costs will  be found in Reference 21.

-------
                                    5-49
Assume the use of online cleaning in a common housing structure and, due to
the high operating temperature, the use of glass filter bags (see Table 5-5).
At a gas-to-cloth ratio of 4.69, the fabric required is:
                    50,000 acfm/4.69 fpm = 10,661 ft2.
Baqhouse Cost
     From Figure 5-4, the cost of the baghouse ("common housing" design) is:
    Cost = 9,688 + 5.552 (10,661)                                       (5-20)
         = $68,878
    Insulation is required.  The insulation add-on cost from Figure 5-4 is:
    Cost = 1,428 + 0.931 (10,661)                                       (5-21)
         = $11,353
Bag and Cage Cost
     From Table 5-6, bag costs are $1.24/ft  for 5-1/8-in diameter glass
fiber, bottom removal bags.  Total bag cost is:
                     10,661  ft2 x $1.24/ft2 =  $13,220.
For 10-ft long cages, fabric area per cage = 5-1/8 in./12 in./ft x x x 10 ft =
13.42 ft    The number of cages = II
Table 5-6, individual cage cost is:

Total cage cost is:
13.42 ft2'  The number of cages = 10,661 ft2/13.42 ft2 = 795 cages.   From
                    3.941 +  0.163  (13.42  ft2) = $6.128.
                     795  cages  x $6.128/cage  =  $4,872.
Costs of Auxiliaries
    Assume the following auxiliary costs have been estimated from data in
other parts of the Manual;

-------
                                    5-50
                Ductwork                     $16,000
                Fan                           16,000
                Motor                          7,500
                Starter                        4,000
                Dampers                        7,200
                Screw conveyor                 4,000
                Stack                          8,000
                                             $62,700
Total Capital Investment
    Direct costs for the fabric filter system,  based on the factors in Table
5-7, are given in Table 5-8.   (Again,  we assume site preparation and buildings
costs to be negligible.)  Total  capital  investment is $412,315.
Annual Costs—Bags
    Table 5-9 gives the direct and indirect annual costs,  as calculated from
the factors given in Section  5.4.   For bag replacement labor,  assume 10 min
per bag for each of the 795 bags.   At  a maintenance labor rate of $21.12
(including overhead), the labor cost is $2,809  for 133 h.   The bags are
assumed to be replaced every  2 yr.  The replacement cost is calculated using
equation (5-14).
Annual Costs—Pressure Drop
    Pressure drop (for energy costs) can be calculated from equations (5-8)
through (5-10),  with assumed  values of 15 [in.  H20/(ft/min)]/(lb/ft2) for KZ,
100 psig for P., and a cleaning interval of 10  min.  We further assume that
              J
the G/C (4.69 ft/min) is a good estimate of the mean face velocity over the
duration of the filtering cycle.

-------
                                    5-51
              Table  5-8  Example Costs.for  Fabric Filter System
Purchased Equipment Costs
   Fabric filter (with insulation)                          $ 80,231
   Bags and cages                                            18,092
   Auxiliary equipment                                       62,700
                                                           $161,023 =  A

   Instruments and controls,  0.1A                            16,102
   Taxes, 0.03A                                               4,831
   Freight, 0.05A                                             8,051
         Total purchased equipment  cost                    $190,007 =  B

Installation Direct Costs
   Foundation and supports,  0.04B                             7,600
   Erection and handling, 0.50B                              95,004
   Electrical, 0.08B                                         15,201
   Piping, 0.01B                                              1,900
   Insulation for ductwork,  0.07B                            13,300
   Painting, 0.02B                                            3,800
   Site preparation
   Facilities and buildings                                     —
         Total installation  direct  costs                   $136,805

         Total direct costs                                 $326,812

Indirect Costs
   Engineering and supervision, 0.10B                        19,001
   Construction and field expense,  0.20B                     38,001
   Construction fee, 0.10B                                   19,001
   Startup fee, 0.01B                                         1,900
   Performance test, 0.01B                                    1,900
   Contingencies, 0.03B                                       5,700
         Total indirect costs                               $85,503

         Total capital investment                          $412,315

-------
                                    5-52
         Table  5-9   Example Annual Costs for Fabric Filter  Systems

Direct Annual  Costs
   Operating labor
      Operator,  6 h/day x 360 d/yr x  $12/h  =                        $25,920
      Supervisor, 15% of operator =                                   3,888

   Operating materials

   Maintenance
      Labor, 3 h/day x 360 d/yr x $13.20/h  =                         14,256
      Material,  equal to labor costs                                  14,256

   Replacement parts, bags, [2,809 +  (13,220 x  1.08*)] x 0.5762 =     9,845

   Utilities
      Electricity, 0.000181 x 50,000  acfm x 10.3 in.  H~0
       x 8,640 h/yr x $0.06/kWh =                     *              48,323
      Compressed air (dried and filtered),  2 scfm/1,000 acfm
       x 50,000 acfm  x $0.16/1,000 scfm x  60 min/h x 8,640 h/yr =    8,294
      Waste disposal, at $20/ton onsite for essentially 100%
       collection efficiency:


          1 1b   y 50.000 ft3.. 60 min   8.640 h     1 ton    $20 _
        7,000 gr *     mm   *    R   *  yr    * 2,000 Ib * Ton "
         Total direct annual costs                                 $272,896

Indirect Annual Costs
   Overhead, 0.6 x (25,920 + 3,888 + 14,256 + 14,256) =              34,992
   Property tax, 0.01 x 412,315 =                                     4,123
   Insurance, 0.01 x 412,315=                                         4,123
   Administration, 0.02 x 412,315=                                    8,246
   Capital recovery cost, (412,315 - 2,809 - 13,220 x 1.08)          46.439
    x 0.1175

         Total indirect annual costs                                 97,923

             Total annual cost                                     $371,000
                                                                   (rounded)

*The "1.08" accounts for freight and sales tax on the bags.

-------
                                    5-53
   VJ  = c.V0 = 4 gr/ft3 x 7 LI^   x 4.69 ft/min x 10 min = 0.0268 lb/ft2
    o    i                /,uuu gr                                      (5-22)

                                        -0.65                             -
    AP = 6.08 x 4.69 ft/min x [100 psig]     + 15 [In. H20/ft/min)]/(lb/ft^)

        ' x 0.0268 lb/ft2 x 4.69 ft/min = 3.32 in. H,0 across the fabric (when
         fully loaded).                            i
Assume the baghouse structure and the ductwork contribute an additional 3 in.
H20 and 4 in. H^O, respectively.  The total pressure drop is, therefore, 10.3
in.
Total Annual Cost
    The total annual cost is $371,000, nearly half of which is for ash
disposal.  If a market for the flyash could be found, the total annual cost
would be greatly reduced.  For example, if $2/ton were received for the ash,
the total annual cost would drop to $208,000 ($370,819 - $148,114 - $14,811),
or 56% of the cost when no market exists.  Clearly,  the total annual  cost is
extremely sensitve to the value chosen for the dust disposal cost in this
case.  In this and in similar cases, this value should be selected with care.
5.4.6  Acknowledgment
    We gratefully acknowledge the following companies for contributing data to
this section:
    Aget
    BACT
    BHA
    Dustex
    Fuller
    Griffin
    W. W. Sly
    Zurn

-------
                                    5-54
                          References for Section 5
 1.   Turner,  J.  H.,  "Bag Filtration," in Handbook of Multiphase Systems, ed.
     by G.  Hetsroni,  Hemisphere,  1982.
 2.   Turner,  J.  H.,  and J. D.  McKenna,  "Control  of Particles by Filters," in
     Handbook of Air Pollution Technology,  ed.  by S. Calvert and H. Englund,
     New York:John Wiley & Sons,  19847
 3.   Donovan, R. P.,  Fabric Filtration  For  Combustion Sources,  New York:
     Marcel Dekker,  Inc.,  1985, p.  201.
 4.   Dennis,  R., and H. A. Klemm,  "Modeling Concepts for Pulse  Jet
     Filtration." JAPCA. 30(1), January 1980.
 5.   Leith, D. and M. J. Ellenbecker, "Theory  for Pressure Drop in a Pulse Jet
     Cleaned Fabric Filter." Atm.  Environment.  14, 1980, pp. 845-852.
 6.   Koehler, J. L.  and D. Leith,  "Model Calibration for Pressure Drop in a
     Pulse-Jet Cleaned Fabric Filter,"  Atm. Environment, 17(10), 1983, pp.
     1909-1913.
 7.   Northrop Services, Inc.  Fabric Filter Workshop Reference  Materials. 1977
     Workshop.  Air Pollution Training  Institute.
 8.   Vatavuk, W. M.,  and R. B. Neveril, "Estimating Costs of Air-Pollution
     Control  Systems, Part II:  Factors for Estimating Capital  and Operating
     Costs," Chemical Engineering.  November 3,  1980, pp. 157-162.
 9.   Frey,  R. F., and T. V. Reinauer, "New  Filter Rate Guide,"  Air
     Engineering. 30 April 1964.
10.   Dennis,  R., et al. Filtration  Model for Coal Fly Ash with  Glass Fabrics,
     August 1977 (EPA-600/7-77-084  [NTIS PB 276489JJ.
11.   Owen,  M. K. and A. S. Viner,  Microcomputer Programs for Particulate
     Control, June 1985 (EPA-600/8-85-025a).
12.   Dennis,  R.  and H. A.  Klemm.   Fabric Filter Model Change; Vol. I. Detailed
     Technical Report.  February 1979 (EPA-600/7-79-043a (NlIS  PB 293551JJ.
13.   Viner, A. S., et al.  "Comparison of Baghouse Test Results  with the
     GCA/EPA Design Model."  JAPCA.  Vol. 34(8),  August 1984.
14.   Reigel,  S.  A. and R.  P. Bundy.   "Why the  Swing to Baghouses?"  Power.
     121-1, pp.  68-73, January 1977  (modified).
15.   ETS,  Inc.,  Suite C-103, 3140  Chaparral Dr.  SW, Roanoke, VA  24018-4394.
16.   Fuller Company,  P.O.  Box 2040,  Bethlehem,  PA  18001.

-------
                                    5-55
17.  R. S. Means Company, Inc., Means Square Foot Costs 1986, Kingston, MA.

18.  Perry, Robert H., et al., Perry's Chemical Engineers' Handbook  (Fourth
     Edition), New York:  McGraw-Hill, 1963, p. 6-20.

19.  Personal communication from Gary Greiner, ETS,  Inc., to Jim Turner,
     Research Triangle Institute, October 24, 1986.

20.  Perry, Robert H., et al.. Perry's Chemical Engineers' Handbook  (Sixth
     Edition), New York:  McGraw-Hill, 1984.

21.  McKenna, J. D., J. H. Turner, D. Furlong, and D. S. Beachler, Fabric
     Filters-Baghouses, I. Theory, Design and Selection, in preparation, ETS,
     Inc., Suite C-103, 3140 Chaparral Dr. 5W, Roanoke, VA  24018-4394.

-------