EPA-600/2-76-078
March 1976
Environmental Protection Technology Series
               COST  ESTIMATING  METHODOLOGY FOR
                               ONCE-THROUGH  COOLING
                   WATER DISCHARGE MODIFICATIONS
                                  Industrial Environmental Research Laboratory
                                       Office of Research and Development
                                      U.S. Environmental Protection Agency
                                Research Triangle Park, North Carolina  27711

-------
                                    EPA-600/2-76-078
                                    March 1976
   COST ESTIMATING METHODOLOGY

FOR  ONCE-THROUGH COOLING WATER

      DISCHARGE MODIFICATIONS
                      by

       John W. Hayden and Richard Mayer

             Acres American, Inc.
            The Liberty Bank Building
            Buffalo, New York 14202


            Contract No. 68-03-2053
             ROAPNo. 21AZU-021
         Program Element No. 1BB-392


     EPA Project Officer: James P.  Chasse

   industrial Environmental Research Laboratory
     Office of Energy, Minerals, and Industry
       Research Triangle Park, NC 27711


                 Prepared for

 U.S. ENVIRONMENTAL PROTECTION AGENCY
       Office of Research and Development
             Washington, DC  20460

-------
                        CONTENTS
Sections






I            CONCLUSIONS                                1




II           INTRODUCTION                               2




III          APPROACH                                   13




IV           METHODOLOGY                                18




V            REFERENCES                                209




VI           CONVERSION FACTORS                        211




VII          APPENDICES                                212
                            iii

-------
                         FIGURES


No.                                                  Page

1     Surface Discharges                                4

2     Submerged Discharges                              5

3     Once-Through Basic Discharge Systems
      and Possible Modifications                        6

4     Sample Worksheet - Carbon Steel Pipe,
      Worksheet 403.1                                  21

5     Design Data Required for Worksheet 403.1         24

6     Base Cost Computation on Worksheet 403.1         25

7     Cost Graph Corresponding to Cost Account
      403.1 and Worksheet 403.1                        26

8     Cost Adjustments on Worksheet 403.1              27

9     Sample Cost Category, Cost Summation
      Worksheet                                        29

10    Cost Category 10 Summation Worksheet             30

11    Example of Computations for Regional and
      Time Adjustment of Construction Cost             32

12    Example of Extrapolating to Future
      Start of Construction Data                       34

13    Computation of Total Project Costs               35

14    Computation of Power Outage Costs                37

15    Sample Computation of Annual Costs               39

102   Removal of Concrete Slabs                        56

103   Removal of Concrete (Non-Slab)                   56

105   Clearing and Grubbing                            57

108.1 Hauling Costs for Concrete Slabs                 58

108.2 Hauling Costs for Earth, Rock, or
      Broken Concrete                                  58
                           IV

-------
                    FIGURES  (cont'd)
 No.
Page
 201.1  Costs  for Material  and Land-Based
        Placement of  Riprap                            71

 201.2  Costs  for Materials and Offshore
        Placement of  Riprap                            71

 202.1  Costs  for Steel  Sheet Piling
        (Land  Installation)                             72

 202.2  Costs  for Steel  Sheet Piling                    72
        (Offshore Installation)

 203.1  Costs  for Piles  (Land Installation)             73

 203.2  Costs  for Piles  (Offshore Installation)         73

 300.1  Types  of Cooling Water Circulating Pumps        75

 301.1  Pumps  and Motors                               88

 301.2  Pump and Motor Installation                     89

 301.3  Costs  for Valves and Expansion Joints           89

 401     Costs  for Precast Concrete Pipe                112

 402     Cost for Gast-In-Place Box Conduit             113

 403.1  Cost for Carbon  Steel Pipe                     114

 403.2   Cost for Elbows, Reducers, and Connections     114

 404     Costs  for Corrugated Steel Pipe                115

 405     Cost for Fiberglass Pipe                       115

 406.2   Costs  for Pipe Installation  (Land)             116

 406.5   Dewatering Costs for Pipe Installation         116

 407.2  Costs  for Pipe Installation  (Marine)           117

500.1  Structural Supports                            120

500.4  Diameter Relationships                         134

501.1  Tunnel Excavation Costs for Dry Headings       134

                            v

-------
                    FIGURES (cont'd)


No.                                                 Page

501.2  Tunnel excavation Costs for Wet Headings      135

502.1  Costs for Rock Bolt Supports                  135
    j.
502.2  Costs for Shotcrete Support                   136

502.3  Cost for Continuous Horseshoe Rib Supports    136

502.4  Cost for Circular Rib Supports                137

502.5  Costs for Timber Lagging                      137

503    Costs for Tunnel Lining                       138

504    Costs for Tunnel Dewatering                   138

600.1  Conduit Diffuser                              139

600.2  Tunnel Diffuser                               140

601    Costs for Steel Nozzles                       154

603.2  Installing Individual Nozzles Into a
       Tunnel Manifold                               155

701.1  Costs for Structural Concrete,
       Concrete Placement                            164

701.2  Costs for Structural Concrete,
       Reinforcing Steel                             164

801    Cost for Fill Material                        172

802.1  Cost for Placement of Fill  (Land)             173

802.2  Cost for Placement of Fill  (Marine)           173

901.1  Costs for Earth Excavation  (Land)             187

901.2  Costs for Earth Excavation  (Marine)           187

902.1  Costs for. Rock Excavation  (Land)              188

904    Costs for Excavation Dewatering               188

1100   ENR 20-City Construction Cost Index           196

1201   Discharge Arrangement at Quad Cities          214

                           vi

-------
                         TABLES

No.                                               Page
1      Comparison of Results                         1
2      Cost Accounts for Cost Category 4            20
3      Site Preparation Cost Accounts               47
4      Cost Category I Cost Summation               48
5      Riprap Removal, Worksheet 101                49
6      Concrete Slab Removal, Worksheet 102         50
7      Concrete Removal (Non-Slab), Worksheet
       103                                          51
8      Sheet Piling Removal Pulling Costs,
       Worksheet 104.1                              52
9      Sheet Piling Removal Salvage Value,
       Worksheet 104.2                              52
10     Clearing and Grubbing, Worksheet 105         53
11     Reseeding, Worksheet 106                     53
12     Site Grading, Worksheet 107                  54
13     Hauling, Worksheets 108.1 & 108.2            54
14     Other, Worksheet 109                         54
15     Mobilization, Worksheet 110                  55
16     Erosion Protection Cost Accounts             63
17     Cost Category 2 Cost Summation,
       Worksheet 200                                64
18     Placement of Riprap (Land-Based),
       Worksheet 201.1                              65
19     Placement of Riprap (Marine),
       Worksheet 201.2                              66
20     Steel Sheet Piling  (Land), Worksheet 202.1   67
21     Steel Sheet Piling  (Marine)
       Worksheet 202.2                              68
22     Piles (Land), Worksheet 203.1                68
23     Piles (Marine), Worksheet 203.2              69
24     Concrete, Worksheet 204                      69
25     Other, Worksheet 205                         70
26     Mobilization, Worksheet 206                  70
                           vii

-------
                     TABLES (cont'd)

No.
27     Pump and Motor Characteristics
28     Pump Station Cost Accounts
29     Cost Category 3 Cost Summation,
       Worksheet 300                                81
30     Pumps and Motors, Worksheet 301.1            82
31     Installation, Worksheet 301.2                83
32     Expansion Joints and Valves,
       Worksheet 301.3                              83
33     Pile Foundation, Worksheet 302.1             84
34     Foundation Slab and Pit Walls,
       Worksheet 302.2                              85
35     Cover Slab, Worksheet 303.1                  85
36     Enclosure, Worksheet 303.2                   85
37     Foundation Excavation,  Worksheet 304         86
38     Steel Sheet Piling, Worksheet 305            86
39     Structure Backfill, Worksheet 306            86
40     Other, Worksheet 307                         87
41     Mobilization, Worksheet 308                  87
42     Conduit Cost Accounts                        99
43     Cost Category 4 Cost Summation,
       Worksheet 400                               101
44     Precast Concrete Pipe,  Worksheet 401        102
45     Cast-In-Place Box Conduit,
       Worksheet 402                               103
46     Steel Conduit, Worksheet 403.1              104
47     Steel Pipe Fittings, Worksheet 403.2        105
48     Corrugated Metal Pipe,  Worksheet 404        106
49     Fiberglass Pipe, Worksheet 405              106
50     Onshore Pipe Trench Excavation,
       Worksheet 406.1                             107
51     Laying Pipe on Land, Worksheet 406.2        107
52     Onshore Backfill, Worksheet 406.3           107
53     Pipe Support Systems, Worksheet 406.4       108
54     Dewatering, Worksheet 406.5                 108
                           viii

-------
                     TABLES  (cont'd)
NO,
55     Offshore Pipe Trench Excavation,
       Worksheet 407.1                             108
56     Laying Offshore Pipe, Worksheet 407.2       109
57     Offshore Backfill, Worksheet 407.3          109
58     Pipe Support Systems, Worksheet 407.4       110
59     Riprap Protection, Worksheet 407.5          110
60     Cofferdams, Worksheet 407.6                 110
61     Other, Worksheet 408                        111
62     Mobilization, Worksheet 409                 111
63     Rock Types                                  118
64     Rock Support Criteria                       123
65     Tunnel Cost Accounts                        126
66     Cost Category 5 Cost Summation,
       Worksheet 500                               127
67     Tunneling Excavation, Dry,
       Worksheet 501.1                             128
68     Tunneling Excavation, Wet,
       Worksheet 501.2                             128
69     Rock Bolts, Worksheet 502.1                 129
70     Shotcrete, Worksheet 502.2                  129
71     Horseshoe Rib Support, Worksheet 502.3      130
72     Circular Rib Support, Worksheet 502.4       130
73     Timber Lagging, Worksheet 502.5             131
74     Concrete Tunnel Lining, Worksheet 503       132
75     Tunnel Dewatering, Worksheet 504            132
76     Shafts, Worksheet 505                       133
77     Other, Worksheet 506                        133
78     Diffuser Cost Accounts                      145
79     Cost Category 6 Cost Summation
       Worksheet 600                               147
80     Steel Nozzles, Worksheet 601                148
81     Concrete Manifold, Worksheet 602.1          149
                           IX

-------
                     TABLES  (cont'd)

No.                                               Page
82     Steel Manifold, Worksheet 602.2             149
83     Steel Manifold Fittings, Worksheet 602.3    149
84     Installation of Conduit Diffuser,
       Worksheet 603.1                             150
85     Installation of Nozzles Into a
       Tunnel Diffuser,  Worksheet 603.2            150
86     Cofferdams, Worksheet 603.3                 150
87     Trench Excavation, Worksheet 603.4          151
88     Diffuser Support Systems, Worksheet 603.5   151
89     Riprap Protection, Worksheet 603.6          151
90     Trench Backfill, Worksheet 603.7            152
91     Single Port, Worksheet 604                  152
92     Other, Worksheet 605                        152
93     Mobilization, Worksheet 606                 153
94     Concrete Cost Accounts                      159
95     Cost Category 7 Cost Summation
       Worksheet 700                               160
96     Cast-In-Place Structural Concrete,
       Concrete Placement, Worksheet 701.1         161
97     Cast-In-Place Structural Concrete,
       Reinforcing Steel, Worksheet 701.2          161
98     Cast-In-Place Concrete (Marine),
       Worksheet 702                               162
99     Grouting, Worksheet 703                     162
100    Cushion Fill, Worksheet 704                 163
101    Other, Worksheet 705                        163
102    Mobilization, Worksheet 706                 163
103    Fill Cost Accounts                          167
104    Cost Category 8 Cost Summation
       Worksheet 800                               167
105    Material and Hauling Costs,
       Worksheet 801                               168
106    Placement of Fill  (Land), Worksheet 802.1   169

-------
                     TABLES (cont'd)
No.
107    Placement of Fill  (Marine),
       Worksheet 802.2                             170
108    Other, Worksheet 803                        171
109    Mobilization, Worksheet 804                 171
110    Excavation Cost Accounts            .        179
111    Cost Category 9 Cost Summation,
       Worksheet 900                               180
112    Earth Excavation (Land), Worksheet 901.1    181
113    Earth Excavation (Marine),
       Worksheet 901.2                             182
114    Rock Excavation  (Land), Worksheet 902.1     183
115    Rock Excavation  (Marine),
       Worksheet 902.2                             184
116    Shoring, Worksheet 903                      185
117    Excavation Dewatering, Worksheet 904        185
118    Other, Worksheet 905                        186
119    Mobilization, Worksheet 906                 186
120    Mobilization Cost Accounts                  191
121    Cost Category 10 Cost Summation,
       Worksheet 1000                              192
122    Mobilization, Worksheet 1001                192
123    Other, Worksheet 1002                       193
124    Capital Cost Resolution Accounts            201
125    Cost Category 11 Cost Summation             201
126    Time and Regional Adjustment Factor,
       Worksheet 1101                              202
127    Project Costs, Worksheet  1102               204
128    Power Outage Costs, Worksheet 1103          205
129    Annual Costs, Worksheet 1104                205
                            XI

-------
                         TABLES
 No.                                               page
 B-l     Labor Force  and Equipment Pool/
        Account  101                                 271
 B-2     Labor Force  and Equipment Pool,
        Account  102                                 272
 B-3     Unit  Cost  Data, Account 102                 272
 B-4     Labor Force  and Equipment Pool,
        Account  103                                 273
 B-5     Unit  Cost  Data, Account 103                 273
 B-6     Labor Force  and Equipment Pool,
        Account  104                                 274
 B-7     Labor Force  and Equipment Pool,
        Account  105  (Light Clearing)                275
 B-8     Labor Force  and Equipment Pool,
        Account  105  (Medium to Heavy Clearing)      275
 B-9     Unit  Cost  Data, Account 105                 276
 B-10    Labor Force  and Equipment Pool,
        Account  106                                 276
 B-ll    Labor Force  and Equipment Pool,
        Account  108                                 277
 B-12    Unit  Cost  Data, Account 108                 277
 B-l3    Labor Force  and Equipment Pool,
        Account  201.1  (Riprap, Stone, and
        Filter)                                     278
 B-14    Labor Force  and Equipment Pool,
        Account  201.1  (Cover Stone)                 278
 B-15    Unit  Cost  Data, Account 201.1               279
 B-16    Labor Force  and Equipment Pool,
        Account  201.2  (Riprap, Stone, and
        Filter)                                     279
B-17    Labor Force  and Equipment Pool,
       Account  201.2  (Cover Stone)                 280
B-18    Unit  Cost  Data, Account 201.2               280
B-19    Labor Force  and Equipment Pool,
       Account  202.1                               281
B-20   Unit  Cost  Data, Account 202.1               281
B-21   Labor Force  and Equipment Pool,
       Account  202.2                               282
                           xii

-------
No.                                               Page
B-22   Unit Cost Data, Account 202.2               282
B-2 3   Labor Force and Equipment Pool,
       Account 203.1                               283
B-24   Unit Cost Data, Account 203.1               283
B-25   Labor Force and Equipment Pool,
       Account 203.2                               283
B-26   Unit Cost Data, Account 203.2               284
B-27   Labor Force and Equipment Pool,
       Account 301.2                               285
B-28   Unit Cost Data, Account 301.2               285
B-29   Unit Cost Data, Account 402                 286
B-30   Unit Cost Data, Account 403                 286
B-31   Labor Force and Equipment Pool,
       Account 406.2                               286
B-32   Unit Cost Data, Account 406.2               287
B-33   Labor Force and Equipment Pool,
       Account 407.2                               287
B-34   Monthly Output Data, Account 407.2          288
B-35   Unit Cost Data, Account 407.2               288
B-36   Pumping Equipment and Labor Cost,
       Account 406.5                               289
B-37   Labor Force and Equipment Pool,
       Account 602.3                               290
B-38   Unit Cost Data, Account 602.3               290
B-39   Cost for Components of Structural
       Concrete, Accounts 701.1 and 701.2          291
B-40   Labor Force and Equipment Pool,
       Account 702                                 291
B-41   Labor Force and Equipment Pool,
       Account 703                                 292
B-42   Labor Force and Equipment Pool,
       Account 802.1  (Group 1)                     293
B-43   Labor Force and Equipment Pool,
       Account 802.1  (Group 2)                     293
B-44   Labor Force and Equipment Pool,
       Account 802.1  (Group 3)                     294
B-45   Unit Cost Data, Account 802.1               294
                           Kill

-------
No.                                               Page
B-46   Labor Force and Equipment Pool,
       Account 802.2                               295
B-47   Unit Cost Data, Account 802.2               295
B-48   Labor Force and Equipment Pool,
       Account 901.1  (Group 1)                     296
B-49   Labor Force and Equipment Pool,
       Account 901.1  (Group 2)                     296
B-50   Labor Froce and Equipment Pool,
       Account 901.1  (Group 3)                     297
B-51   Unit Cost Data, Account 901.1               297
B-52   Labor Force and Equipment Pool,
       Account 901.2  (Hard Material)               297
B-53   Labor Force and Equipment Pool,
       Account 901.2  (Firm or Soft Material)       298
B-54   Labor Force and Equipment Pool,
       Account 901.2  (Disposal)                    298
B-55   Unit Cost Data, Account 901.2
       (Side Cast)                                 298
B-56   Unit Price Data, Account 902
       (Onshore Disposal)                          299
B-57   Labor Force and Equipment Pool,
       Account 902.1                               289
B-58   Unit Cost Data, Account 902.1               300
B-59   Labor Force and Equipment Pool,
       Account 902.2                               300
                           xiv

-------
                    ACKNOWLEDGMENTS

The authors gratefully acknowledge the cooperation extended
by the following organizations:

   Commonwealth Edison Company, Chicago, Illinois
   Consolidated Edison Company, New York, New York
   Allis-Chalmers, Custom Pump Division, Milwaukee,
     Wisconsin
   Long Island Lighting Company, Hicksville, New York
   Philadelphia Electric Company, Philadelphia, Pennsylvania
   Niagara Mohawk Power Corporation, Syracuse, New York
   Cleveland Electric Illuminating Company
   Pacific Gas and Electric Corporation, San Ramon,
     California
   Main Yankee Atomic Power Corporation, Westboro,
     Massachusetts
   Wisconsin Electric Power Company, Milwaukee, Wisconsin
   Florida Power Corporation, St. Petersburg, Florida
   Consumers Power Company, Jackson, Michigan
   Duke Power Company, Charlotte, North Carolina
   Detroit Edison, Detroit, Michigan
   Tennessee Valley Authority, Chattanooga, Tennessee
   Rochester Gas and Electric Company, Rochester, New York
   Great Lakes Dredge and Dock Company, Chicago, Illinois
   Morrison-Knudsen Company, Atlanta, Georgia
   S. J. Grooves Construction Company, Syracuse, New York
   Corban Plastics, Tampa, Florida
   Beetle Plastics, Dayton, Ohio
   Lock Joint Pipe Company, Parsippany, New Jersey
   Armco Steel, Denver and Buffalo offices
   Bethlehem Steel Corporation, Buffalo, New York
   Penn Central Railroad, Buffalo, New York
                             xv

-------
             ACKNOWLEDGMENTS (cont'd)
A. 0. Smith-Inland Incorporated, Reinforced Plastics
  Division, Little Rock, Arkansas
Department of the Army, Corps of Engineers, Buffalo
  District, Buffalo, New York
Republic Steel Corporation, Buffalo, New York
U. S. Steel, Buffalo, New York
Clarence Sand and Gravel Corporation, Clarence, New York
                          xvi

-------
                       SECTION I

                      CONCLUSIONS
This manual enables a person not expertly skilled in cost
engineering to prepare a reasonably accurate estimate of the
costs for new once-through cooling water discharge systems
for thermal electric generating plants and for modifications
to existing once-through discharge systems.  Table 1 presents
four cases of modifications to existing discharge systems
and compares actual construction costs and estimates
prepared using traditional, more detailed procedures to
cost estimates prepared using the methodology in this manual.
The results obtained using this manual compare very favorably
with the actual construction costs and estimates shown,
demonstrating that this manual provides a relatively easy
means of preparing a reliable preliminary cost estimate or
testing the accuracy of another cost estimate.

             Table 1.  COMPARISON OF RESULTS
                    Estimated Cost,
                  Millions of Dollars
                          Actual Construction    Percentage
Plant         Manual       Cost or Estimate      Difference
Quad Cities    8.9              9.2                  4
Nine Mile      6-1              5.7                  6
 Point No. 1
Dresden         .12              .12
North Port
 Onshore       6.6              6.6
 Offshore     14               15                    9
     Appendix A for an example of the derivation of the
 data presented.

-------
                         SECTION II

                        INTRODUCTION
GENERAL

This manual presents a methodology for evaluating the engi-
neering and cost implications of constructing or modifying
once-through cooling water discharge systems of thermal
electric generating plants within the contiguous United
States.  The procedures presented provide persons not
skilled in cost engineering with a means of preparing
preliminary cost estimates from conceptual or design
drawings.  The user should, however, have a technical back-
ground and be familiar with once-through cooling water
di s charge sys terns.

Principal construction elements of discharge system construc-
tion and modification are identified and grouped into
categories.  Materials and installation methods are dis-
cussed for each construction element.  Data on labor,
materials, equipment, and productivity assumed in unit cost
development are provided.  A step-by-step procedure is given
for:
     1.   estimation of construction costs and
     2.   resolution of construction costs into project and
          annual costs.
An example is shown using the methodology and comparing re-
sults with actual construction costs for modifications to
an existing system.

-------
DISCHARGE SYSTEMS AND POSSIBLE  MODIFICATIONS


Discharge systems


For the purposes of  this manual,  once-through  cooling water

discharge systems are classified  into  two  categories:

surface discharge and submerged discharge.


The surface discharge category  includes two distinct types

of outfalls distinguished by  geometry  and  discharge
velocity:

     1.   open channel/ characterized  by a low velocity
          discharge  from an open  channel into  the receiving
          water at or close to  the shoreline  (see Figure 1);
          and

     2.   surface jet, characterized by a  high velocity
          discharge  from a conduit at  or near  the surface
          of the receiving water  (see  Figure 1).

The submerged discharge category  also  includes two types of

outfalls:
     1.   single port, consisting of the open end of a con-
          duit or other point source discharging beneath
          the water  surface (see  Figure 2); and

     2.   multiport  diffuser, consisting of a number of
          ports or slots arranged along a manifold and
          discharging at some depth below  the water surface
          (see Figure 2).
Discharge modifications


The four basic types of once-through cooling water discharge

systems and possible modifications thereof are shown in

Figure 3 and discussed briefly below:
     1.   Surface discharge open channel - Possible modifi-
          cations include:
          a.   Surface discharge open channel  (improved) -
               Increase channel width and install a weir to
               spread and thin the thermal plume.
                             3

-------
Discharge Channel
                OPEN CHANNEL
 Ccnduit
                 SURFACE  JET
             Fig. 1 - Surface Discharges

-------
SINGLE PORT DISCHARGE
                             Multi-port
 MULTIPORT   DISCHARGE
Fig. 2 - Submerged Discharges
            5

-------
    BASIC
    SYSTEMS
 Surface
Discharge
            Surface
            Discharge
            Improved
    POSSIBLE
    MODIFICA-
    TIONS
cr>
   Surface
     Jet
                    Surface
                      Jet
                    Improved
            Submerged
            Multiport
       Submerged
         Single
          Port
       Submerged
      Single Port
                  Single
                   Port
                 Improved
Submerged
Multiport
Submerged
 Single
  Port
Submerged
Multiport
Submerged
Multiport


Multiport
Improved
                          Fig. 3 - Once-Through Basic Discharge
                           Systems and Possible Modifications

-------
b.   Surface jet - Close off the open channel,
     install a conduit with an outfall located
     near the water surface and shoreline.

c.   Submerged single port - Close off the open ,
     channel, pump the heated effluent via a
     conduit or tunnel to a submerged outfall off-
     shore .

d.   Submerged multiport - Close the open channel,
     pump the heated effluent via conduit or
     tunnel and discharge the water through a sub-
     merged multiport diffuser.

Surface jet - Possible modifications include:

a.   Surface jet  (improved) - Attach a reducer to
     the end of the conduit to increase discharge
     velocity at the outfall.

b.   Submerged single port - Extend a conduit or
     tunnel to a submerged offshore point source
     outlet.
c.   Submerged multiport - Extend a conduit or
     tunnel to an offshore submerged location and
     discharge the heated effluent via a multiport
     diffuser.
Submerged single port - Possible modifications

include:
a.   Submerged single port (improved)  - Increase
     the outfall submergence depth by extending
     the tunnel or conduit into deeper water
     further from shore.
b.   Submerged multiport - Attach a multiport
     diffuser at the existing outfall point.
Submerged multiport - Possible modifications

include changing the diffuser angle of discharge
with respect to prevailing currents or changing
the discharge angle, spacing, number,  and diameter

of individual nozzles.

-------
Other types of discharge arrangements are used in once-
through cooling water systems, including modified spray
ponds and cooling ponds.  In these systems, heated water is
cooled by evaporation from ponds prior to discharge into the
receiving water via one of the systems discussed above.  The
methodology in this manual can be used to estimate costs for
such cooling and spray ponds.
ECONOMIC ANALYSIS - IMPORTANT ENGINEERING AND ECONOMIC
CONSIDERATIONS

Engineering considerations

The reader should be aware that the scope of this manual is
limited to the discharge system downstream of the condenser.
Therefore, engineering considerations for modifications to
existing systems assume flow rate and condenser temperature
rise to remain unchanged.

Discharge system modifications are generally of three types:
     1.   changes in outfall geometry;
     2.   changes in orientation of the discharge relative
          to predominant ambient currents; or
     3.   increases in the submergence of the outfall.
Key engineering factors involved in discharge system con-
struction and modification are discussed below.
     1.   Site preparation - Preconstruction and postcon-
          struction site work includes:
          a.    clearing trees and brush from the site;
          b.    removal of existing facilities that interfere
               with construction; and
          c.    grading and seeding after construction.
     2.   Erosion protection - Consideration is given to:
          a.    lining the outfall channel to prevent bank
               erosion due to high discharge velocities;
                             8

-------
     b.   constructing sea walls or bulkheads to
          protect shorelines from erosion due to waves,
          tides, or wakes; and

     c.   providing offshore protection, including
          riprap at the outfall for scour protection
          and breakwaters for protection against waves
          or to prevent recirculation between the
          discharge and intake.

3.   Pumping - Conversion from a gravity system or
     increasing velocity at the outfall of an existing
     submerged discharge system increases power require-
     ments which are met by providing a new pump
     station or by modifying an existing station.

4.   Conveyance to discharge point - Site geology and
     offshore working conditions are primary factors in
     deciding between a tunnel or conduit to convey
     cooling water in a submerged discharge system.

5.   Outfall configuration - Outfall geometry and
     orientation and type of diffuser, single port or
     multiport, are important considerations.
6.   Environmental protection - Consideration must be
     given to control of sediment, dust, turbidity,
     shock waves, noise, and other pollutants generated
     as a result of construction.  Provisions must be
     made for disposal of materials such as contami-
     nated sediments excavated from a lake bed and
     trees cleared from the site.  Construction methods
     and schedules can be adjusted to minimize damage
     to sensitive ecosystems.
7.   Construction methods - Previous experience in the
     area, site characteristics, and contractor
     preference will determine construction methods
     used.  Extreme variability in methods exists in
     the area between the shoreline and one-half mile
     offshore.
8.   Location - Hydrology, geology, and regional and
     local weather conditions significantly affect the
     factors listed.  For example, productivity in off-
     shore excavation is dependent on weather, bottom
     conditions, distance to safe harbor, and depth of
     water.

-------
Economic considerations

Within the discharge system requirements imposed by environ-
mental factors and the limitations of engineering practica-
bility, economic considerations are the ultimate determinant
of final design features.  Both total project  (first) costs
and annual costs are evaluated.

Total project costs include engineering and design, lands,
construction, supervision and administration, interest
during construction, and contingencies.  These costs are
sensitive to several factors that must be considered,
including site specific conditions and construction
materials, methods, and management.

Annual costs include amortization of depreciable and non-
depreciable capital investments, interest on bonds, taxes,
insurance, and operating expenses.  The annual cost figure
is sensitive to any changes in initial investment costs and
interest rates and to increased power requirements resulting
from a discharge system modification.

Generally, project costs for a submerged discharge system
are higher than for a surface discharge system, primarily
because of greater expenses for offshore and tunnel con-
struction and. because of the need for more materials at
higher unit prices, for example, large diameter conduit.
Annual costs are also higher with a submerged discharge
system, partly because of the greater initial  investment,
but also reflecting increased operating costs  due to the
need for pumping stations.
                             10

-------
ORGANIZATION

The manual is comprised of seven main sections, including
two appendices:

Section I  - Conclusions
Section II - Introduction

A general discussion of the general types of once-through
discharge systems and the engineering and economic con-
siderations used in system selection.  Possible modifica-
tions to existing once-through discharge systems are dis-
cussed.

Section III - Approach

A general discussion of procedures, assumptions, and bases
for data presented in the methodology.  Price levels, con-
tractor markup, unit costs, and categories of construction
elements are also discussed.

Section IV - Methodology

A step-by-step procedure for use of the manual, including
comments on interpretation of results.  Technical and cost
data are given for each significant element involved in new
construction and system modification.

Section V    - References
Section VI   - Conversion Tables
Section VII  - Appendices
                             11

-------
Appendix A - Case Study
An example showing application of procedures in manual to
an actual case of discharge system modification.  The results
obtained using the methodology are compared with actual
construction costs.
Appendix B - Unit Cost Data
Background data for unit costs used in this manual.
                             12

-------
                         SECTION III

                          APPROACH
GENERAL
The basic  step-by-step approach for  using this manual to
cost out new once-through discharge  systems or modifications
to existing once-through discharge systems is as follows:
Step  1

Select  the  desired system or modification either on the
basis of  information in this manual or other considerations,
Step  2

Prepare  or otherwise  obtain  conceptual or detailed drawings
of  the proposed system or modification.  Cost estimate
accuracy depends largely on  the  accuracy and amount of
detail in these drawings which,  in turn, depend on the
study phase and availability of  site information.  The
reader should note  that although the information presented
in  this  manual may  be useful in  system selection, system
design is not within  the scope of this manual.
Step 3

From the drawings, calculate the quantities specified in
the methodology and worksheets provided with this manual.
                              13

-------
Detail and accuracy of quantity take-offs should reflect
the desired accuracy of the cost estimate, but be consis-
tent with the detail and accuracy of the drawings.
Step 4

Derive project and annual costs for the proposed system or
modification by following the procedures recommended in
this manual and applying the appropriate cost factors and
curves.

The manual is organized into eleven cost categories.  Cate-
gories 1-10 give unit cost data and a procedure for esti-
mating construction costs.  Data for adjusting construction
costs for region and time and for calculating annual costs
are given in Category 11.  Definition of the categories and
the elements of each category, cost accounts, are given in
Section  IV.
TECHNICAL DATA

Engineering information on once-through discharge systems,
including system components, design features and rules-of-
thumb, and construction practices and phases, was compiled
from the following sources:
     1.   Analyses of existing discharge system designs
     2.   Contacts with engineers in the power utility
          industry
     3.   contacts with capital equipment manufacturers
     4.   Contacts with civil contractors
     5.   Company experience.
                             14

-------
COST DATA

Unit costs shown  in this manual were developed on the basis
of December 1974  labor rates  in the New York City area and
capital equipment and material prices and construction equip-
ment rates in  the northeast part of the country.  Results
are adjusted in Cost Category 11 for price levels in the
region and at  the date of  interest.

Unit costs for construction activities in Cost Categories
1 through 4 and 6  through  9 were developed using the
following five-step process:
     1.   Determine or assume site conditions
     2.   Select  the appropriate labor force and equipment
          pool
     3.   Select  labor and equipment rates
     4.   Assume  a productivity and calculate the unit
          cost
     5.   Add  material unit costs where necessary to deter-
          mine the total unit cost.
Information from  several sources was considered during the
unit cost analysis:
     1.   Civil contractors were contacted with regard to
          unit costs and labor and equipment requirements
          for  specific construction activities
     2.   Published cost data books were reviewed for con-
          struction material  costs and labor and equipment
          rates  (see References 1, 2, 3, and 4)
     3.   Manufacturers were  contacted for capital equip-
          ment and material costs
     4.   Power utilities  were consulted to determine actual
          costs of cooling water discharge systems
     5.   Bid  estimates from  over 300 contracts in the
          Engineering News Record were surveyed for civil
          construction unit cost data to compare with the
          unit costs developed for use in this manual.
                               15

-------
Contractor equipment costs for operation, maintenance, re~
placement, overhead, and profit were found to agree closely
with equipment rental fees compiled by the Associated Equip-
ment Distributors  (Reference 1) plus a markup of 10 percent.
Therefore, for simplicity, the latter method was used in
the development of unit costs for this manual.


It was  assumed that capital equipment and materials are
provided  by  the contractor.  The unit cost analysis used
manufacturer-quoted prices for capital equipment  (such as
pumps)  and some materials  (such as conduit).  Costs for
construction materials  (such as riprap) were derived from
cost data books and civil contractors.  Capital equipment
and material prices were marked up 15 percent for contractor
overhead  and profit.

Labor rates  are those recommended in Reference 3 with a
markup  of 40 percent for overhead and profit.

The unit  cost data for Cost Category 5, Tunnels, were
developed from Robert S. Mayo and Associates in Reference 5
and the Corps of Engineers in Reference 6.

Mobilization and demobilization costs are not included as
part of the  unit costs developed for Cost Categories 1
through 9.   Instead, they are treated as a separate item
(in Cost  Category  10) which is consistent with current
practice  for contract bids.

Some of the  data required in Cost Category 11 to estimate
annual  costs must be obtained from local sources  (for
example,  costs for lands, licenses, royalties, fees, rentals,
and leases).   Potential local sources for this data are
                              16

-------
identified.  Federal Power Commission annual reports,
References 7 and 8, give data for the cost of power and
cost of capital.  The capital cost resolution procedures
were adopted from Capital and Operating Costs of Pollution
Control Equipment Modules - Volume 1 - User Guide  (Reference
9).

Labor  and equipment costs, production rates, and material
costs  used to  develop unit costs for categories 1  through
4  and  6  through 9 are tabulated in Appendix B.

The  relationship between quantity and installation unit
cost is  dependent largely on mobilization and demobiliza-
tion costs and the  size of the  equipment required  on the
job  site. Equipment  selection, as it relates to job size,
is given in Appendix  B  and mobilization and demobilization
costs  can be estimated  from data in Category 10.   Material
prices will also vary with the  quantity required for the
project.   Material  prices used  in this study are averages
and  may  be conservative for very large projects and low
for  very small projects.
 VERIFICATION

 To test the validity of the unit cost data and methodology
 in this manual,  cost estimates were prepared for modifica-
 tions  to four existing once-through discharge systems  and
 compared to the  actual construction costs  or contract  bids,
 The results of the comparison are shown in Table 1.
                              17

-------
                        SECTION IV

                       METHODOLOGY
COST CATEGORIES

As described briefly in the previous section, the methodology
in this manual is based on dividing the construction or
modification of a once-through discharge system into eleven
cost categories (representing major components and construc-
tion phases).  The first ten categories reflect major con-
struction phases and design features involved in building
and modifying once-through discharge systems.  These ten
categories are broken down into elemental construction ac-
tivities and system components.  When applying the procedures
in this manual to a specific case/ quantity take-offs and
cost estimates are prepared for each applicable category
element.  The eleventh cost category includes cost adjustment
techniques and procedures to estimate annual costs.  The
eleven cost categories are as follows:
     1.   Category 1, Site Preparation - Preparing the site
          for construction and restoring the site after
          construction.
     2.   Category 2, Erosion Protection - Providing shore-
          line protection, channel lining, and breakwaters
          constructed of riprap, concrete, and sheet piling.
     3.   Category 3, Pumps - Modification of existing pump
          station or installation of new facility.
     4.   Category 4, Conduits - Materials and installation
          of various types of conduits.
     5.   Category 5, Tunnels - Elements of tunneling in
          consolidated and unconsolidated materials, in-
          cluding excavation, lining, support systems, and
          dewatering.
     6.    Category 6, Diffusers - Materials and installa-
          tion of submerged diffusers.
     7.    Category 7, Concrete - Material and placement of
          concrete.
                             18

-------
     8.   Category 8, Pill - Materials, hauling, and place-
          ment of earth, gravel, and sand.
     9.   Category 9, Excavation - Marine and land open-cut
          excavation; disposal of earth and rock spoil.
    10.   Category 10, Mobilization - Mobilization and de-
          mobilization costs.
    11.   Category 11, Capital Cost Resolution - Procedures
          to adjust project costs for region and time; cal-
          culation of annual costs, including resolution of
          project costs and estimation of other annual
          expenses.
COST ACCOUNTS

Each of the eleven cost categories is broken down into
elemental system components and construction activities
 (called cost accounts).  For example, Cost Category 4,
Conduits, consists of the cost accounts shown in Table 2.

Cost accounts represent the limit of detail used in this
manual for estimating costs.  Each cost account is pro-
vided with a worksheet giving step-by-step instructions
for computing the cost for that particular account.  In
most cases, the worksheets are similar to that shown in
Figure 4, with instructions specifying the design data and
quantity take-offs required, the proper unit cost to use
or cost graph to refer to, and any cost adjustments that
are necessary to compute the final cost for that particular
cost account.  In some cases, the worksheet instructions
direct the reader to use one or more other cost accounts in
                              19

-------
specified cost categories to compute the cost.   Referencing
other cost accounts in this manner avoids duplications of
cost accounts, such as those involving excavation,  which
are common to several cost categories.
                Table 2,  COST ACCOUNTS FOR
                      COST CATEGORY 4
Cost Account
Number
401
402
403.1
403.2
404
405
406.1
406.2
406.3
406.4
406.5
407.1
407.2
407.3
407.4
407.5
407.6
408
409
Description
Precast concrete pipe
Cast-in-place box conduit
Steel conduit
Steel conduit fittings
Corrugated metal pipe
Fiberglass pipe
Onshore excavation of pipe trench
Onshore pipe laying
Onshore backfill of pipe trench
Pipe support systems
Dewatering
Offshore excavation of pipe trench
Offshore pipe laying
Offshore backfill of pipe trench
Pipe support systems
Riprap protection for backfill
Cofferdam
Other
Mobilization
Cost accounts and corresponding worksheets and cost graphs
are given the same identifying number to avoid any confusion.
For example, Cost Account 403.1 uses Worksheet 403.1 and
Figure 403.1.  Similarly, Cost Account 406.5 uses Worksheet
406.5.  However, since this worksheet instructs the reader
to use another cost account for the cost computation, a
separate figure is not provided for Cost Account 406.5.
                              20

-------
Design Data Required

Pipe diameter                              	m

Wall thickness                             	cm

With or without stiffeners    	

Pipe length                             L =	m

Shop or field fabrication3    	



Base Cost

Enter Figure 403.1, read base         BUG =|	/m
  unit cost per lineal meter

Base cost = L x BUG                    EC =$
Cost Adjustments

Enter Figure 403.1, read design     F
  adjustment factors for wall       F
  thickness, stiffeners and
  fabrication                       F
Adjusted Base Cost

Adjusted base cost of materials
  and fabrication = BC x FD(!) x
  FD(2) x FD(3)
aFor diameters to 3.05 meters, assume shop fabrication,
    Fig. 4 - Sample Worksheet - Carbon Steel Pipe,
                   Worksheet 403.1
                            21

-------
 It is recommended that the reader prepare the cost estimate
 for a new or modified discharge system by using the cost
 categories in  numerical order.  This minimizes the chances
 for overlooking or, more likely, double-counting certain
 items.  For example, if the reader uses Cost Category 8,
 Fill, before Cost Category 4, Conduits, he might cost out
 fill operations involved with conduit installation; and later,
 when he uses Cost Category 4, he might inadvertently dupli-
 cate these same costs.

 The reader may find it necessary to use cost accounts more
 than once.  As previously mentioned, this frequently occurs
 with certain accounts, such as those involving backfill
 operations, which are common to several construction ac-
 tivities.  Multiple use of cost accounts occurs under other
 circumstances as well, such as changes in conduit diameter
 or changes in the type of material being tunneled which alter
 design data input.
STEP-BY-STEP PROCEDURE

The following paragraphs present a step-by-step description
of this manual's cost estimating methodology.  The procedures
described below are those required to complete steps 3 and
4 of the basic approach which were discussed in the pre-
vious section.  Examples are provided to illustrate the
procedures involved; and comments are inserted to aid the
reader's understanding and to point out notable exceptions.
The general procedures for Cost Categories 1 through 9
are covered in steps 1 through 6 below.  It is recommended
that the reader complete this entire 6-step sequence for
each cost category before proceeding to the next category
and that the reader handle Cost Categories 1 through 9 in
                              22

-------
numerical order.  Inputs for Categories 10 and 11 are based
on results from Categories 1 through 9 and do not follow
the general procedures described in steps 1 through 5.
Accordingly, the discussion of procedures for Categories
10 and 11 begins with step 6.
Step 1

Survey the cost accounts in the cost category being evalu-
ated, selecting those accounts which apply to the proposed
system or modification.

Note that cost accounts in Cost Categories 7 through 9 are
used primarily as inputs to accounts in Categories 1 through
6 and generally are not applicable in and by themselves.

For our example, assume that all estimates for Cost Cate-
gories 1 through 3 have been completed and that in survey-
ing Cost Category 4, Conduits, Cost Account 403.1 is one of
the accounts identified as applicable.
Step 2

For each applicable account, pull out the corresponding
worksheet.

Remember that cost accounts and corresponding worksheets
and cost graphs have the same identifying number.  Worksheet
403.1, which corresponds to Cost Account 403.1, is shown in
Figure 4.
                              23

-------
Step 3

In the spaces provided on the worksheet, enter the design
data required.

The data required, such as volume and type of material ex-
cavated, tunnel diameter and length, concrete volume and type
of reinforcing, is obtained from the drawings discussed in
the previous section in steps 2 and 3 of the basic approach.
Some worksheets provide guidelines or rules of thumb to use
in cases where the design data required are not readily
available.

In our example, we assume all necessary design data are
available and are entered as shown in Figure 5.
  Design Data Required
  Pipe diameter                               5* O 3   m
  Wall thickness                             __LJ2/Z__cm
  With or without stiffeners   tx> I Tn
  Pipe length                             L =  .5 SO   m
  Shop or field fabrication3   $
  aFor diameters to 3.05 meters, assume shop fabrication
               Fig. 5 - Design Data Required
                     for Worksheet 403.1
                              24

-------
Step 4

Determine the base cost following the instructions on the
worksheet.

In some cases, the worksheet provides the unit cost, which
is simply multiplied by the quantity involved to compute
the base cost.  In other cases, the worksheet references a
cost graph from which the base cost is read directly or
from which a unit cost is read and then multiplied by the
quantity involved to get the base cost.

As shown in Figure 6, Worksheet 403.1 references the
corresponding Figure 403.1  (shown as Figure 7) from which
we read a base unit cost of $l,550/meter for a pipe diameter
of 3.05 meters.  This base unit cost is multiplied by the
length of pipe to get the base cost.
  Base Cost
  Enter Figure 403.1, read base unit      BUG =$ // ££&   /m
    cost per lineal meter
  Base cost = L x BUG                      BC =$
              Fig. 6 - Base Cost Computation
                    on Worksheet 403.1
Step 5

Apply design adjustment factors to the base cost to deter-
mine the adjusted base cost.
                              25

-------

-------
Design adjustment factors are provided where variations
in parameters, such as component geometry or type of
material to be excavated or tunneled, result in significant
cost differences.  Some cost accounts do not require such
adjustments.  In these latter cases, the base cost calculated
in the step 4 above is the value of interest.

In our example, Worksheet 403.1  (see Figure 8) instructs
the reader to obtain design adjustment factors from Figure
403.1  Csee Figure 7) and to multiply the base cost by these
factors to get the adjusted base cost.
  Cost Adjustments
  Enter Figure 403.1, read design     pn^) =    /. 0
    adjustment factors for wall       „  ,,. _
    thickness, stiffeners, and        *DU;
    type of fabrication               F^3^ =   O.
  Adjusted Base Cost
                                  "•>
  Adjusted base cost of materials
    and fabrication = BC x Fn(l) x
    FD(2) x FD(3)           U       BC403.1
       Fig. 8 - Cost Adjustments on Worksheet 403.1
Step 6
                          t
Enter the adjusted base costs  (or base cost if no adjustments
are required) on the cost category cost summation worksheet
and determine total cost for category being evaluated.
                              27

-------
Remember that cost accounts in Cost Categories 7 through 9
are primarily used as input to cost accounts in Cost
Categories 1 through 6 and generally are not applicable in
and by themselves.  Consequently, it is unusual to use cost
summation worksheets for these three categories.  For Cost
Categories 1 through 6, the adjusted base costs are entered
and summed with the exception of cost accounts for mobiliza-
tion and demobilization which are entered and totaled on
the Cost Category 10 (Mobilization) summary worksheet.

In our example, the adjusted base cost for Account 403,1 is
entered on the Category 4 Cost Summation worksheet Csee
Figure 9) along with all other applicable accounts.  These
values are summed to get the total cost for this category.
The mobilization costs for Category 4 are entered in the
Category 10 summary worksheet (see Figure 10) and summed
with mobilization and demobilization costs for all other cost
categories to derive the total base cost for Category 10.
Step  7

Compute  the regional and time adjustment factor and deter-
mine  the revised total construction cost following the in-
structions in Category 11.

The total costs for Categories 1 through 10 are entered on
Worksheet 1101  (see Figure 11).  The sum of these entries
is the total construction cost which must be adjusted for
the region of the country where the plant is located and
the date construction is expected to begin or the price
level of interest.  The reader notes the regional adjustment
factor for the city nearest the plant site and determines
                              28

-------

Cost
Account
Number
401
402
403
403.1
403.2
bs^~ — ^-». 	
	 - ' — "•' '•• ' - 1 __ i -^*~**~~^ —I..,, _^~-
Other

agory 4 Total Cost
:ost in Account 1101)
Mobilization (Enter
Cost in Account 1001)


Base Cost
BC40, =$
flU J. • "• • -~"-
BC. , =$ —



BC4oe 3=$ H'^0
Bc40f 4=$ SL>f 3Z&
Bc40e 5=$ "2.1, loo

•*-^^~^~ ., . , «-""'*•. l_»~..^ ._ _ : : — ,_<~~~*
BC4QQ =$ —

BC, =$ /, 5*45", MO

MC =$6,6^00

\
Fig. 9 - Sample Cost Category,
   Cost Summation Worksheet
               29

-------
                      Worksheet 1001
  Data  Requirements
  Cost  Category                     Mobilization
  Number _                     Cost _
                                        = $ Z&
   2                                 MC2 = $  >C>, OOQ

   3                                 MC3 = $
   4                                 MC, = $
                                      4
   5                                 MC5 = $   —
   6                                 M.C, = $    , OOP
                                      D   "^ —
   7                                 MC? = $ _
   8                                 MCg = $_
   9                                 MCg = $_
  Base Cost
                                 BC
                                   IOOI
      Fig. 10 - Cost Category 10 Summation Worksheet
the Engineering News Record  (ENR) Construction Cost Index
(CCI) for the price level of interest or for the date con-
struction is expected to begin.  For instance, if a cost
comparison is desired with an estimate based on price levels
prevailing at some past date, the reader can look up the CCI
in an issue of the ENR corresponding to that date or refer
to Figure 1100 (shown as Figure 12 in this example), a graph
                             30

-------
of the CCI for the period 1969 to 1974.  If construction is
to start at some future date, the reader must project the
CCI perhaps by extrapolating Figure 1100.

In our example, we assume Minneapolis and January 1976 as
the place and start of construction.  Figures 11 and 12 show
the appropriate entries, CCI extrapolation, and computations
to derive the revised total construction cost.
Step 8

Calculate the total project cost following the instructions
given in Cost Category 11.

Project costs include all first costs less any cost incurred
for a temporary power outage during the switch over to a
modified discharge system.  Figure 13 shows the computations
required on Worksheet 1102 to derive the project costs.  If
the percentage of total construction costs for engineering
and general and administrative items is not known, a value
of 10 percent may be assumed.  There are no rules-of-thumb
for land-related costs.  In cases where a discharge system
modification is being considered, the utility might already
have the necessary lands, easements, and rights-of-way.  In
cases where a new system is being considered, these items
might not have been acquired.  In this latter situation, real
estate appraisals might be necessary.  The contingency fac-
tor varies with the detail and accuracy of the data available.
For estimates based on detailed and reliable drawings, a
contingency of 5 percent might suffice; for a planning-type
estimate based on conceptual drawings, a 25-percent contin-
gency is acceptable.
                            31

-------
                    Worksheet 1101


Data Requirements

Regional adjustment factor:

Atlanta -     .79          Kansas City -   .90
Baltimore -   .84          Los Angeles -   .90
Birmingham -  .73          Minneapolis -   .85
Boston -      .90          New Orleans -   .78
Chicago -     .91          New York -     1.00
Cincinnati -  .95          Philadelphia -  .90
Cleveland -   .94          Pittsburgh -    .89
Dallas -      .77          St. Louis -     .89
Denver -      .80          San Francisco - .94
Detroit -     .93          Seattle -       .85
City nearest to construction area        K	

Regional adjustment factor            FR =	Q_
Date construction is to begin or
  period of price level being
  considered

Engineering News Record             ENRX
  Construction Cost Index
  for above date (20-city avg.)

Time adjustment factor =              FT
  ENRX (    ) * 2097a

Regional and time adjustment         F__,
  factor = FT x FR
aThe Engineering News Record 20-city average for
 T\t*.r*£XH\\^CLf 19  1 Q74
 December 12, 1974
    Fig.  11 - Example of Computations for Regional
       and Time Adjustment of Construction Cost
                            32

-------
                     Worksheet 1101


 Data Requirements  (Cont'd)

 Total costs from Categories 1 through 10:
  BC3  =  $ 897, 7OQ
  BC5   =  $   —
  BC7   =  $    "
  BC8   -  $	-
  BC9


  BC10
  Total  Cost =  E  (BC-j^ through BC1Q)    BCT = $ 3t 7/3,7OO
  Revised Construction Cost

j  Total  cost = BCT x FRT            BC1101 = $ ^
     Fig.  11 - Example of Computations for Regional
        and Time Adjustment of Construction Cost
                              33

-------
0)
M

5
id


I?
•H
O
H

EH
CO
O
O


§
H
EH
U

§
EH
CO

§
O

Pi
        1200T
          1969 1970 1971 1972  1973  1974  1975 1976 1977 1978

                                   DATE
         Fig.  1100 - ENR 20-City Construction Cost  Index


         Fig.  12 - Example of Extrapolating to Future  Start

                   of Construction Data
                                34

-------
                    Worksheet 1102


Data Required

Total construction cost            BC

Cost for engineering and
  general and administrative
   10%
    100%   BC1101a
                                       noi
  Cost for lands, easements, and        BCL = $_
    rights-of-way

  Revised cost = BC,,n, + BC-,           BC, = $
    •  TH-I           J.J.U.L     ill             x   —
    + BCL

  Adjustment for contingencies  =       BC_ =
  Adjustment for escalation during
    construction = BC2 x
    ENRX (beginning)  + ENRX (end)
         2 x ENRX (beginning)

  Adjustment for interest during
    construction0 = BC3 x
    (1 + no.yrs. of construction x
     annual interest rate/100%) =
     BC3 x (1 + _[_ x 3 %/100%)

  Royalties,  licenses, fees, etc.         R = $_

  Total Project Cost = BC4 + R
!  aAssume 10 percent if detailed information is not
!   available.
I  .
1   With detailed information, use a factor of 5 percent;
j   for a planning estimate use 25 percent.
i
j  °See account discussion.
i
       Fig.  13 - Computation of Total Project Costs


                              35

-------
 The adjustment for cost escalation during  construction  is
 based on the average  CCI for  the construction period.   If
 the purpose of the estimate is  a cost  comparison with another
 estimate based on a fixed price level/  this  adjustment  is
 not necessary.  However, if a period of construction in the
 future is specified,  this adjustment will  require CCI pro-
 jections.  The adjustment for interest during construction
 is based on the assumption that interest is  paid during the
 entire construction period on the entire amount of capital
 needed for the project.   Costs  for royalties, licenses,  and
 other one-time fees are small  and may be assumed to be
 negligible if figures are not readily  available.
                                         •}

 In our example, as shown in Figure 13,  we  assume a value of
 10 percent for engineering and  general and administrative
 items; $111,000 for lands, easements,  and  rights-of-way; 5
 percent for contingencies; CCI's for a one-year construction
 period beginning in January 1977  (see  Figure 12 for the ex-
 trapolation of CCI values); 9 percent  for  the interest  rate;
 and $20,000 for royalties and other  fees.
 Step 9

 Compute costs  due  to  temporary  power outage  during switch-
 over to a  modified discharge  system.

 If  a plant shutdown is  necessary  during  the  switchover,
 the power  is assumed  to be  purchased from other members  of
 the regional power grid.

 In  our  example, a  750-megawatt  plant with a  capacity  factor of
 0.66  is assumed to  be shut  down for  one  week (See  Figure 14).
The unit cost  for power is  assumed equal to  $0.02l/kwh(replacement
power) minus $0.018/kwh  (production expenses) or $0.003/kwh.
                              36

-------
                      Worksheet 1103

  Data Required
  Period of outage                    T =    /	weeks
  Power generation losses             P = 8tttoc>o,OOG kwh
   =  [capacity x outage period
     x capacity factor]
  Unit cost of power                  U =  O.0Q3   $/kwh
   = purchase cost - normal
     production expenses

  Outage Cost
  T x P x U =                    BC1103 = £•
        Fig. 14 - Computation of Power Outage Costs
Step 10

Compute annual costs by resolving first costs and estimating
other annual expenses using the procedures recommended in
Cost Category 11.

As shown in Figure 15, annual costs include amortization of
the investment using the sinking fund method of deprecia-
tion; interest on the bond issue; rental and leasing costs;
operating expenses, assuming the only significant operating
expenses are those associated with pumping costs; insurance;
and property taxes; less tax credits for installation of

                             37

-------
capital equipment.  Rules-of-thumb are provided, for estimating
several of these items.

In our example, we assume the power plant to be 25 years
old at the time of modification, leaving a period of 15
years till the end of the assumed 40-year useful plant life.
This establishes the amortization period for the new invest-
ment.  We assume our sinking fund earns an annual return of
8 percent and use the table of sinking fund factors pro-
vided.  The salvage value of the new investment 15 years
hence is assumed to be $500,000.  The computations'involved
in amortizing the investment are illustrated in Figure 15.

Interest on the investment is calculated assuming the bond
issue must finance all first costs, including the cost for
a power outage during switchover.  Costs for renting or
leasing equipment or processes generally may be regarded as
negligible.

Pumping costs are the only operating costs assumed to be
significant in this analysis.  We use the recommended values
of 65-percent efficiency and $0.018/kwh.  We also assume
an average downtime of one month per year in determining
the annual operating hours.

Insurance and property taxes on the new investment are
calculated using the recommended percentage values.  The
tax credit computation assumes a straight line depreciation
and the income tax rate recommended on the worksheet.
                             38

-------
                    Worksheet 1104
1.  Amortization of depreciable capital investment and
    costs for power outage/ royalties, etc.
    Useful Life            Sinking Fund Factor/
    Years _            Annual Interest Rate

                              ii        12%

    3                      .30803     .29635
    5                      .17046     .15741
    7                      .11207     .09912
    10                     .06903     .05698
    13                     .04652     .03568
    15                     .03683     .02682
    18                     .02670     .01794
    22                     .01803     .01081
    25                     .01368     .00750
    28                     .01049     ,00524
    30                     .00883     .00414
    35                     .00580     .00232
    40                     .00386     .00130
    Remaining useful life of the plant   Y =  /   _ yrs

    Sinking fund factor (tabulated       F =
      above) for annual interest
      rate of
    Total project  (first) cost      BC     ~ $ 1
                                      H02
    Salvage value                        S = $
    Land costs                           L = $ ////
    Royalties, fees, licenses, etc.      R = $
    Depreciable capital investment      DC = $ ^,009
     BC1102 -  (S+L+R)

    Power outage costs              BCH03 = $ "ZS2f COO


     Fig. 15 - Sample Computation of Annual Costs


                          39

-------
     The amount amortized is =            D - $j       ^	
     depreciable capital investment
      + power outage costs +
      royalties, fees,  etc.
      [Dc + BCH03 + Rl

     Annual cost = F x  D                  C = $   /_5"%^33


 2.   Amortization of the non-            NC = $  /0>
      depreciable capital invest-
      ment (F x S).   Nc is a
      credit (see No. 9 below).


 3.   Interest on the capital invest-      B = 	
      ment.  Bond interest rate

     Interest payment = B%/100%  x        I  = $_
      (•of     -4- tir1   ^                    P
      (BC1102 + BC1103}

 4.   Rent or lease costs                 Ls = $_
6.   Insurance  (BC,,Q2  - L - R)  x         I=$_
      y  %b/ioo%


7.   Property taxes  (BC1102  ~ L  ~ R)      pt = $.
     x  Z %c/100%
8.  Tax credit

     Income tax rate                     I  =
                                          R
 5.   Operating costs.   Power re-
      quired in excess of the power
      required before  the addition
      or  modification

      = Theoretical  Power *  efficiency
                                         PS =    y£3/ C 77  w
      = fff00,000 watts x 100%/4*T %
    Annual  operating hours               H =   8/030	hrs

                           4         a
    Power costs  =  H x PQ x 0. */& /kwh    Z = $_
Fig. 15  (continued)  -  Sample Computation of Annual Costs


                            40

-------
                    Worksheet 1104

    Methods of depreciation:

    a.   Straight line depreciation
          Tax credit =
          Dc x IR%/(100% x Y)

          = $#aaft,a/3 x VB%/(100% x

    b.   Others (refer to tabulation below)
                DR
    Year     (deprec. rt.)
                                           = $
9.   Annual costs = Z (C - N,
                                                 Ti
                                              (annual)
                                              increments of
                                              depreciation)
                                                 Pt -
                                           -  $
 Assume $.018/kwh

^Assume 4 percent
•i
"Assume 2 percent
                        Assume 48 percent

                       2Refer to a depreciation schedule
                        for Dp for other than straight
                        line depreciation

                        If efficiency is not known,
                        assume a value of 65 percent
Fig. 15 (continued) - Sample Computation of Annual Costs
                          41

-------
 INTERPRETATION OF RESULTS

 Cost  data presented in the methodology were developed
 assuming average conditions.  Therefore, the user should
 not expect  results from this manual to be identical with a
 detailed bid estimate.  Also, items not specifically in-
 cluded in this tabulation of data, but which would fall
 into  the "other" cost account of each category might sig-
 nificantly  affect the cost.  To further complicate the
 situation,  present inflationary trends make estimating for
 any type of construction rather speculative, necessitating
 practically a weekly update to achieve accuracy and currency.

 Retrofitting involves both marine and land-based construc-
 tion.   Costs for construction along the land-shore interface,
 i.e.,  the littoral zone are extremely difficult to accurately
 predict.  Tunneling costs are also very difficult to fore-
 cast  because of factors such as variable subsurface conditions
 and seepage rates.

 A June 20,  1974, article in the Engineering News Record
 reported the results of a survey of types of estimates and
 compared results with actual construction costs.  Seventy-
 six reported an accuracy of +6 to -4 percent using complete
 quantity take-offs.  The sample was primarily for construc-
 tion  on land where construction costs are generally more
 consistent  than for marine work.  Therefore, for the types
 of construction considered in this study, the accuracy to
 be expected for a detailed estimate should be somewhat less.
 The user can expect an estimate developed using the method-
 ology  in this manual to be in the range of ± 15 percent
when detailed site data is provided.
                             42

-------
COST CATEGORY 1,
SITE PREPARATION
Information on razing existing facilities, clearing and
grubbing the site, and site grading is included.  Data on
hauling materials with a truck are also included.  Specific
data for each account are given in the following paragraphs.
Riprap removal, Account 101

Key parameters to consider in removing riprap are the size
of the stone and where the material is located.  The data
presented here do not consider offshore relocation.  In
almost every case, hauling the material from the site is
not a viable consideration.  However, hauling costs are
provided in Account 108.2.  It was assumed a crane with a
clam shell would be used to excavate the material.
Concrete slab removal,
Account 102
The key parameters are slab thickness, reinforcing and
access to the slab.  Removing a section of a slab used
for erosion protection along the shoreline or in a channel
are examples of this activity.  The maximum slab thickness
considered is in the range between 30 and 45 cm.  Rates of
production vary according to the following conditions:
     1.   Reinforcing
     2.   Thickness.
The data are for slabs with relatively easy access.  The
unit  cost was developed assuming a crane rigged with a
headache ball is used to break the slab.  The same crane

                           43

-------
is then rigged with a clam bucket for removal and piling
or loading the material onto a truck.  Reinforcing is
cut with an acetylene torch.
Concrete removal  (nonslab),
Account 103
The key parameters are the quantity of reinforcing and
access to the structure.  Blasting is one method to remove
the more massive type concrete structures.  Plant safety
requirements place restrictions on blasting near the
plant, and in some cases, it may not be allowed.  Cost
data were developed for demolition of reinforced and non-
reinforced concrete by blasting.  Concrete foundations,
walls and ground slabs greater than 45 cm thick are samples
of the types of structures considered in this account.
Steel sheet piling removal,
Accounts 104.1 and 104.2
The key parameters are the depth of penetration, access to
the piling and the condition of the material.  The material
may be salvaged for scrap or reused depending on the con-
dition of the material.  The productivity is related to the
depth of penetration.  The piling is removed with an ex-
tractor rigged on a crane.  Data presented do not reflect
removing a sheet pile structure requiring considerable
labor efforts to ready the piling for extraction.
                           44

-------
Clearing and grubbing,
Account 105
Key parameters to consider in the clearing and grubbing
operation are the density of the vegetation and the type
of disposal.  It was assumed that the material would be
disposed of on site.  Larger materials are sawed and buried,
The brush and branches are chipped and used as mulch.
Reseeding, Account 106

The key parameters are the seeding method and the material
costs.  Cost data reflect minimum site preparation and re-
seeding of the disturbed areas.
Site grading, Account 107

The key parameters are the area, depth of fill, and cost
of imported borrow.  Data for dumping and spreading the
material are given in Cost Category 8.
Hauling, Accounts 108.1 and 108.2

Key parameters are the haul distance, capacity of the truck,
type of road and material hauled.  Data reflect hauling
rock or earth over a paved road to the disposal area.

Unit costs were developed assuming two 7.6 cubic meter
trucks would haul rock or earth 3.22 kilometers  (2 miles)
to the dump.  For hauling materials, more than 3.22
kilometers, costs will increase $.50/m /kilometer; over
                           45

-------
 3.22 kilometers; for broken concrete and rock and $.30/
 m3/kilometer  for earth.  The base unit cost  for hauling
 slabs  is based on  the rate for hauling broken concrete.
 In  calculating the costs for hauling slabs, it was assumed
 the slab would increase in volume 25 percent when broken.

 Dump operations are included for material disposal.

 A suggested round-trip haul distance is included on each
 worksheet where hauling costs are appropriate.  It was
 assumed the disposal area would be closer  (given here as
 8 km)  than a  borrow site or quarry  (given here as 18 km) .
 Although, 8 kilometers for hauling materials from the site
 is  within the range of values presented in reference 2,
 the values suggested here are somewhat arbitrary.  When-
 ever possible, local conditions should be assessed to
 determine hauling  costs.
Mobilization, Account 110

Unit prices do not include mobilization and demobiliza-
tion  (referred to as mobilization) costs.  The user adds
the mobilization costs for each account that is used in
calculating the total Category costs.  A discussion of
mobilization costs is given in Category 10.

Table 3 presents the correlation between cost account
number, worksheet, and figure number.  Costs are cal-
culated using the procedure outlined in the introductory
remarks to this section and the worksheets in Tables 4
through 15.
                            46

-------
        Table  3.  SITE PREPARATION COST ACCOUNTS
Cost
Account
Number
Description
Figure
Number
Worksheet
Number
101
102
103
104


104.1



104.2


105


106

107
108
Riprap removal:  Costs
  for excavation and
  sidecasting material.

Concrete slab removal:
  Costs include break-
  ing and sidecasting
  the debris.

Concrete removal (non-
  slab) :  Costs include
  breaking and side-
  casting the debris.

Steel sheet piling
  removal.

Pulling costs to remove
  sheet piling and stock-
  pile on site.

Salvage credit for sheet
  piling removed.

Clearing and grubbing
  costs.

Costs for reseeding.

Site grading:  Costs for
  cut and fill opera-
  tions;
  .hauling, and spreading
  topsoil. (See Cost
  Category 8)

Hauling:  Costs for
  hauling materials.
 102
           101
  102
 103
  103
 105
           104.1
           104.2
  105
           106
           107
                            47

-------
  Table 3  (continued).  SITE PREPARATION COST ACCOUNTS
Cost    {
Account i
Number  ';  Description
                                    Figure
                                    Number
                                             Worksheet
                                             Number
108.1   ;  Hauling costs for trans-
            porting debris from
            breaking slabs.

108.2     Hauling costs for earth,
            rock, and broken
        I    concrete.

109     |  Other.
        i
110       Mobilization costs.
                                     108.1
                                     108.2
                                               108.1



                                               108.2



                                               109

                                               110
                Table 4.  COST CATEGORY 1
                	COST SUMMATION	

                      Worksheet  100
Cost
Account
Number
101
102
103
104
Description
Riprap removal
Concrete slab removal
Concrete removal
(nonslab)
Sheet pile removal
Base
Cost
BC101 =^
BC1QO =
BC =
103
1
104.1     Pulling costs

104,2     Salvage credit
         i
105       Clearing and grubbing

106      i Reseeding
         I	
                                  BC
                                    104.1
                                  BC
                                  BC
                                    105
                                    106
                           48

-------
          Table 4  (continued).  COST CATEGORY 1
                     COST SUMMATION
Worksheet 100
Cost
Account
Number
107
109
Description
Site grading
Other
Cost Category 1 Total Cost (Enter
cost in Account 1101)
110
Mobilization (Enter Cost
in Account 1001)
Base
Cost
BC =
BC =

BCjL =$

MC1 =?

                Table 5.  RIPRAP REMOVAL
                      Worksheet 101
Design Data Required

Haul distance to disposal site
   (round trip)a

Volume of riprap
     V =
                 Jem

                   3
           m
Base Cost
Base cost for excavating riprap =
  $5.40/m3 x V

Enter figure 108.2, read base
  unit cost for rock haul and
  disposal

Base cost for haul and disposal
  of riprap = V x BUG(2)

Total base cost = BC(1) + BC(2)
BC(1)  =
BUG (2) =$
BC(2)  =$

BC
                                      '101
=$
alf haul distance is not provided, assume  8-km round  trip.

                            49

-------
             Table  6.  CONCRETE SLAB REMOVAL

                      Worksheet 102
Design Data Required

Haul distance to disposal site
   (round trip)a                            	km

Slab thickness                             	cm

Type of reinforcing
   (non-reinforced, reinforced)   	
                                                      2
Slab area                               A =          m
Base Cost

Enter Figure 102, read base cost for
  breaking slabs and sidecasting
  debris                            BC(1) =$
Enter Figure 108.1, read base unit
  cost for haul and disposal of
  broken slab                       BUG (2)=$	    /m

Base cost for haul and disposal =
  A x BUG (2)                       BC(2) =$
Total base cost = BC(1) + BC(2)     BC    =$
                                       102  —
 If haul distance is not provided,  assume 8-km round trip.
                           50

-------
          Table 7.   CONCRETE REMOVAL (NON-SLAB)
                      Worksheet 103
Design Data Required

Haul distance to disposal site
  (round trip)a                            	km

Reinforcing (nonreinforced or
  reinforced)
Volume of concrete                      V =          m
Base Cost

Enter Figure 103, read base cost for
  breaking concrete and sidecasting
  debris                           BC(1)  =$
Enter Figure 108.2, read base unit
  cost for haul and disposal of con-
  crete debris                     BUG (2) =$
Base cost for haul and disposal
  of concrete debris               BC{2)  =$
Total base cost = BC(1) +
  BC(2)                            BC     =$
alf haul distance is not provided, assume 8-km round trip.
                           51

-------
             Table  8.   SHEET PILING REMOVAL
             	PULLING COSTS	

                     Worksheet 104.1
Design  Data  Required

Average depth of penetration            D =	m

Lineal  meters of sheet piling           L =	m



Base Cost
                                                      2
Penetration  area = D x L                   	m

Base cost  for pulling sheet piling =
  A x $20.50/m2                  BC, „. . =$
                                    '104.1
             Table   9.  SHEET PILING REMOVAL
             	SALVAGE VALUE	

                     Worksheet 104.2
Design Data Required

Type of steel sheet piling,
  weight per unit area                  W =	kg/m2

Area of steel sheet piling              A =          m2
Base Salvage Credit

Base salvage credit = W x A x
  $330/kg                        BSC104.2
                           52

-------
            Table  10.  CLEARING AND GRUBBING
                      Worksheet 105
Design Data Required

Type of clearing and grubbing
  (light, medium or heavy)a
                                                      2
Area of clearing and grubbing                 .	m
Base Cost

Enter Figure 105, read base cost


                                    BC
                                      105
aLight  - trees to 6-inch diameter.
 Medium - trees 6- to 10-inch diameter.
 Heavy  - trees 10- to 16-inch diameter.
                  Table  11 ,  RESEEDING

                      Worksheet 106


Design Data Required
                                                      2
Area of reseeding                       A =	m



Base Cost

Base cost = A x $0.37/m             BC., nfi =$	
'106
                           53

-------
                 Table  12.  SITE GRADING
                      Worksheet 107
Base Cost

Refer to Cost Category 8 and 9 for
  appropriate cost accounts and cost
  estimating procedures.
  Base cost = £ (appropriate         ^107
  base costs).
                   Table 3.3.  HAULING

                Worksheets 108.1 & 108.2
Costs for these accounts are incorporated within other
cost accounts as appropriate.
                    Table 14.  OTHER
                      Worksheet 109
Base Cost

Include costs not covered in this
  Category but that relate to Site
  Preparation.  Data presented in
  other accounts may be useful in
  estimating "Other" Costs.         BC,=$
                           54

-------
                Table  15.  MOBILIZATION

                     Worksheet 110
Data Requirement
Cost Account
Number	

101
102
103
104.1
105
106
107
108a
 Mobilization
 Cost	

 Add $3,300 for any one
 of these accounts and
 $6,600 if two or more
 are used
$700
$ 400
 See Cost Cat. 8
$600
Summation0
Mobilization Cost

Mobilization = the total of the
  summation column  (above)
                            MC  =$
                              1  ~~
 Add mobilization for hauling if accounts 101, 102, 103 or
 106 are used.
                           55

-------
Ul
     ™  10
     c«
        10'
        10
          10
                   ^n
10'

10
                                           4
                  AREA OF SLABS, square meters

              Curve    Description

                A      Reinforced, 30 to 45  (1) cm
                B      Reinforced up to 30 cm
                C      Non-reinforced, 30 to 45 cm
                D      Non-reinforced, up to 30 cm
                                                         H

                                                         -8
                                EH
                                W
                                8
                                                            10
                                           $Y
                                                       sP:/
10            10             10

     VOLUME OF CONCRETE,  cubic meters
              Fig. 102 - Removal of Concrete Slabs
                                      Fig.  103 - Removal of Concrete (Non-Slab)

-------
Ul
                            0}
                            M
                            m
                           H

                           o



                           m
                                                  10             10'

                                               AREA, square meters
                                        Fig.  105 - Clearing and Grubbing

-------
CD
       M
       5
       §
       01

       Q]
       En
       0}
       8
       H
           4 — H	
           3-
                2   4   6   8   10   12   14  16  18  20

              ROUND TRIP HAUL DISTANCE,  kilometers
         Fig.  108.1 - Hauling Costs for Concrete  Slabs
0)
•P
u
•H
•§
^
w
                                                          H
                                                          O
§
U
                                                         1
                                                              11
    10
                                                                        X
                                                                            /S
\S
                         A
                                                                                       B
                                                                                          x£
      0   2   4   6   8  10  12   14  16  18  20

        ROUND TRIP HAUL DISTANCE, kilometers

        Curve  Description

          A    Hauling rock and broken concrete
                  (nonslab) (disposal)
          B    Hauling rock w/o disposal
          C    Hauling earth with disposal
          D    Hauling earth w/o disposal

        Fig. 108.2 - Hauling Costs for Earth,
              Rock, or Broken Concrete

-------
COST CATEGORY 2, EROSION
PROTECTION MEASURES
Data on the materials and installation of riprap, concrete,
steel piling and piles are included.  The emphasis is on the
application of the materials to erosion protection.  How-
ever, data for steel sheet piling and piles apply to excava-
tion shoring and cofferdams.  Specific data for each account
are given in the following paragraphs.
Placement of riprap  (land-
based), Account 201.1	
Key parameters are the size and availability of the material.
Riprap is used in applications such as channel lining, and
sea walls (protection along a lake shore).  Riprap can also
be used to construct a rubble mound breakwater  which is a
rock dam extending off shore used to dissipate wave energy.
Another application of a breakwater is to separate the dis-
charge plume and intake structure for the plant to prevent
recirculation.  Riprap protection is placed in layers in-
creasing in particle size from the earth to the outer face.
The gradation prevents leaching and erosion of the soil
beneath the riprap blanket.  The stone sizes are grouped
into three types:
     1.   Filter - A gravel filter used beneath the riprap
          stone.  (Assume thickness is equal to one half the
          stone size) •
     2.   Riprap stone - Stones less than 1 cubic meter
          (assume a thickness equal to 0.6 meters).
     3.   Cover stone - individual stones of about 10 cubic
          meters volume.
Local availability will effect the material price and hauling
costs for riprap.  In many areas inland and along the east
coast, riprap must be hauled from distances of hundreds of
                            59

-------
kilometers.  A haul distance of 18 kilometers is given as a
basis  for estimating the contribution of hauling to riprap
costs.  However, when possible the user should consult
local  sources for information.

The smaller stones can be placed by dumping the material
from the truck on the slope with a minimum of spreading.
The cover stones are usually placed one at a time using a
crane  and a cable sling.
Placement of riprap
 (marine), Account 201.2
Key parameters are the size of the stone and availability of
the material.  The riprap stone may be used to protect the
area around the diffuser nozzles.  Placing the riprap stone
and filter offshore involves:
     1.   loading the material into scows?
     2.   towing the scows to the site; and
     3.   dumping the material.
The cover stones are placed offshore.  However/ offshore
applications of cover stone are often in a rubble mound
breakwater.  A typical breakwater is constructed using the
structure as a peninsula from which to place the stones.
For this type application, land-based costs are appropriate.
Costs for placing the cover stone offshore are given and
were developed by assuming:
     1.   a crane positioned on land loads the stones onto a
          flat-top barge;
     2.   the barge is towed to the offshore site; and
     3.   a crane barge  (a crane mounted on a barge) is used
          to place the stones.
                             60

-------
Steel sheet piling
(land), Account 202.1
Key parameters are the type of soil, material costs, the
depth of penetration and the bracing required.  Steel sheet
piling may be used as excavation shoring, for erosion pro-
tection, such as a bulkhead in a sea wall, or as channel
lining material.  The structure may be a single line of
piling or two lines connected with braces and empty or filled
with some material.  Bracing requirements vary at every site.
A conservative estimate of bracing requirements, $7/square
meter, was given in and adopted from Reference 4.  The costs
for materials depend on whether the material is new or used.
Sheet piling for temporary use such as for excavation shoring
may be rented.  It was assumed the piling to be left in place
is new material.  For temporary applications, material costs
reflect rental rates.  The piling may require trimming and
some welding work.  However, the cost was neglected.  The
piling is driven with a pile-driving hammer rigged on a crane
boom.  Wood piling data are not given because it is not used
as often as steel.
Steel sheet piling
 (marine), Account 202.2

Key parameters are the type of soil, material costs, depth
of penetration and the bracing required.  Steel sheet piling
placed offshore is used for cellular cofferdams and break-
waters.  The circular structures can be filled with soil,
gravel, or riprap stone.  Most of the time only a minimum
of bracing and pile supports are required because the inter-
lock strength of the piling carries the net outward earth
pressure.  If it is desirable to dewater a small area, indi-
vidual cells may be constructed using circular walers to
prevent collapse.
                            61

-------
 Piles  (land), Account  203.1

 Key parameters  are the type of pile, material, and the depth
 of  penetration.   Three materials are used to make piles:
 concrete,  steel,  and wood.  The piles considered here are
 foundation piles.  One dimension of pile for each material
 was selected to represent that material.  The error intro-
 duced  should not  significantly effect the results.
 Piles  (marine), Account 203.2

 Key  parameters are pile materials, depth of penetration, and
 the  type  of pile.  Piles driven offshore are used as
 bearing piles  for pipe support systems and to support sheet
 piling driven  in the water.  A crane barge rigged for driv-
 ing  piles is used to install the piles.
Concrete, Account 204

The key parameters are the application and the volume.  Two
applications are considered in this account.  Concrete slabs
are used as a channel lining material and for shore protec-
tion.  Costs for other concrete slabs and the cushion fill
placed between the earth and concrete are given in Category 7,
Concrete is also used in the construction of sea wall bulk-
heads.  Slabs are placed between steel piles.  The costs  for
the slabs and piles are given in Cost Category 7 and Cost
Category 2.
                            62

-------
Mobilization, Account 206


Unit prices do not include the cost for mobilization and

demobilization.  The user includes costs in accordance with

the construction on Worksheet 206.  A discussion of mobili-

zation costs is given in Cost Category 10.

                                         n-  '•
Table 16 presents the correlation between cost account num-

ber, worksheet and figure number.  Costs are calculated

using the procedure outlined in the introductory remarks of

this section and Worksheets 17 through 26.
             Table 16.  EROSION PROTECTION
                     COST ACCOUNTS
Cost
Account
Number
Description
Figure
Number
Worksheet
Number
201



201.1



201.2



202



202.1


202.2
Riprap:  Costs for cover
  stone, riprap stone,
  and filter material.

Costs for materials and
  land-based placement
  of riprap.

Costs for materials and
  offshore placement of
  riprap.

Costs for materials and
  installation of steel
  sheet piling.

Costs for materials and
  land-based installation,

Costs for materials and
  offshore installation.
                            63
 201.1
 201.2
 202.1


 202.2
 201.1
 201.2
 202.1


 202.2

-------
        Table 16 (continued).  EROSION PROTECTION
                     COST ACCOUNTS 	
Cost
Account
Number
203
203.1
203.2
204
205
206
Description
Costs for installation of
piles and the material.
Piles (land installation) .
Piles (marine installation) .
Costs for materials and
installation of concrete
erosion protective
measures.
Other
Mobilization
Figure
Number

203.1
203.2

—
—
Worksheet
Number

203.1
203.2
204
205
206
                Table 17.  COST CATEGORY 2
                	COST SUMMATION	

                       Worksheet 200
Cost
Account
Number
Description
        Base
        Cost
201



201.1


201.2

202

202.1
Riprap and filter
  material and place-
  ment

Placement by land-
  based equipment

Offshore placement

Steel sheet piling

Placement by land-
  based equipment


                   64
BC201.1=i-
BC
                                       BC
  201.2"
                                         202.1'

-------
          Table 17 (continued).  COST CATEGORY 2
                	COST SUMMATION	

                       Worksheet 200
Cost
Account
Number
202.2
203
203.1
203.2
204
205
Description
Offshore placement
Piles
Land installation
Marine
Concrete
Other
Base
Cost
BC202.
BC203.
BC203.
BC204
BC205
,-$
_
0 =

=

Cost Category 2 Total Cost
  (Enter cost in Account 1101)
BC.
=$

206
Mobilization
in Account
(Enter Cost
1001)
MC2 =$

                  Table 18.  PLACEMENT OF
                    RIPRAP  (LAND-BASED)
                      Worksheet 201.1
Design Data Required

Material

Volume of material
Haul distance (round trip) from
  borrow site to construction site
     V =
    Hd=-
           m
           km
 Cover stone, riprap stone, or filter stone.

3If haul distance is not provided and seems appropriate, assume
 18-km round trip (see the discussion for this account).
                            65

-------
             Table 18 (continued).   PLACEMENT OF
                   RIPRAP (LAND-BASED)

                     Worksheet  201.1
 Base  Cost
 Enter  Figure  201.1,  read  base  cost
   for  material  and placement      BC(1)
 Enter  Figure  108.2,  read  base  unit                      3
   cost for  hauling               BUG (2)  =$	/m

 Base cost for haul = V x  BUG(2)   BC(2)   =$	

 Total  base  cost  =  BC(1) + BC(2)   BC2Q1 1 ~£	
                Table 19.  PLACEMENT OF
                    RIPRAP (MARINE)

                    Worksheet 201.2
Design Data Required

Material3

Volume of material

Haul distance (round trip) from
  borrow site to shoreline
  staging areab
aCover stone, riprap stone, or filter stone.

 If haul distance is not provided and seems appropriate,
 assume 18-km round trip  (see discussion  for Account 201.1)
                            66

-------
            Table 19  (continued).  PLACEMENT OF
                    RIPRAP  (MARINE)

                    Worksheet 201.2


Base Cost

Enter Figure 201.2, read base cost
  for material and placement       BC(1)  =$
Enter Figure 108.2, read base unit
  cost for hauling                 BUG (2) =$	/m

Base cost for hauling = V x BUG(2) BC(2)  =?	

Total base cost = BC(1) + BC(2)    BC201 2~£	
                Table 20.  STEEL SHEET
                     PILING  (LAND)

                    Worksheet  202.1


Design Data Required

Area of sheet piling

Intended usage
   (temporary or permanent)        	


Base Cost

Enter Figure 202.1, read base  cost

                                  BC
                                     202.1
3
                             67

-------
                Table 21.  STEEL SHEET
                    PILING (MARINE)

                    Worksheet 202.2


Design Data Required
                                                      2
Area of sheet piling                       	m

Intended usage
   (temporary or permanent)        	
Base Cost

Enter Figure 202.2, read base cost


                                  BC202.2



                Table 22.  PILES  (LAND)

                    Worksheet 203.1


Design Data Required

Pile material  (concrete, steel, or wood)a
Total length of piles                      	m


Base Cost

Enter Figure 203.1, read base cost BCon- ,=$   	
                                     ** U J * JL        -- 	
aConcrete - square 20.3 cm tip and 40.6 cm butt
 Steel    - 30.5 cm x 30.5 cm H 24kg
 Wood     - 20.3 cm tip and 35.6 cm butt
                             68

-------
               Table 23.  PILES (MARINE)

                    Worksheet 203.2


Design Data Required

Pile material (concrete, steel, or wood)a
Total length of piles                      	m


Base Cost

Enter Figure 203.2, read base cost BC203 2=$	
 Concrete - square 20.3 cm tip and 40.6 cm butt
 Steel    - 30.5 cm x 30.5 cm H 24kg
 Wood     - 20.3 cm tip and 35.6 cm butt
                      Table  24.   CONCRETE
                         Worksheet  204
   Base Cost

   Concrete slab shore protection
     and channel lining:
     Refer to Cost Category 7  for
     estimating procedure (Cost
     Account 701).

   Bulkhead shore protection:   Costs
     for materials and placement. Vertical
     concrete slabs are given  in
     Cost Account 701. Costs  for
     H-piles for supporting the
     concrete slabs are derived
     from Cost Account 203.             BC204  =—
                             69

-------
                    Table 25.  OTHER
                      Worksheet 205
Base Cost

Include costs not covered in this
  category but that relate to
  erosion protection measures.
  Data presented in other accounts
  may be useful in estimating
  "Other" Costs.                     BCOA,. = $
               Table 26.  MOBILIZATION

                    Worksheet 206
Data  Requirements

Cost  Account     Mobilization
Number	     Cost	                 Summation

201.1           $3,700                       	
  Riprap  stone
  or  filter

201.1
  Cover stone )  $3,300  for                   	
202.1        )  one of  the accounts
203.1        )  (201.1-204) and
204              $6,600  for two or
                 more accounts

Haulinga         $600                         	

Mobilization for marine  equipment
  is  included in Categories 4 and 6


Mobilization Cost

Mobilization = the total of the
  summation column (above)               MC  =$
                                           £*     —••••». -   . . ._
a
 If account 201.1 is used and hauling costs  are  added to
 the estimate, include the mobilization  cost for hauling
                           70

-------
        10
    w
    rt
    %
    w
    8
    W   1 n
    9
-J   in
        io
          10
10'
10'
                 VOLUME, cubic meters
                                             VOLUME, cubic meters
             Fig. 201.1 - Costs for Material and Land-
                          Based Placement of Riprap
                                       Fig. 201.2 - Costs for Materials and Offshore
                                                    Placement of Riprap

-------
-J
ro
    £     6
    S   10
    to

    8
    1
10'
        10'
          10
                 10"
10'
                                                 w   6

                                                 io 10
                                                   10"
                                                   10
10
10'
10
           QUANTITY OF SHEET PILING, square meters




           Fig.  202.1 - Costs for Steel Sheet Piling

                        (Land Installation)
                                                            QUANTITY OF SHEET PILING, square meters




                                                          Fig. 202.2 - Costs for Steel Sheet Piling

                                                                       (Offshore Installation)

-------
-J
U)
     ?'  10
    8
    w

    1
                                                            10
                    LENGTH OF PILING, meters



                   Fig.  203.1 - Costs for Piles

                                (Land Installation)
 LENGTH OF PILING, meters



Fig. 203.2 - Costs for Piles

             (Offshore Installation)

-------
COST CATEGORY 3, PUMP STATION

Information on modifying an existing pump station or in-
stallation of a new facility is given.  Typically the
existing pump station is located upstream from the con-
denser.  Water enters the cooling system through the in-
take and is pumped into the condenser and discharged.
Installation of a new station will normally be done down-
stream of the condenser.
Pumps and motors, Account 301.1

The key parameters are capacity, total head, type of pump,
and salinity of the water.  Three types of pumps are used
for cooling water supply:
     1.   The vertical wet pit pump - This type is the
          least costly from the standpoint of space re-
          quirements.  The pump is the most common type
          encountered during the literature review and
          case studies.
     2.   The vertical dry pit - A pump with the advantage
          of being more easily maintained, but it is a bit
          more expensive in first cost than the vertical
          wet pit type.
     3.   Horizontal dry pit - This type requires more
          space than the others and the motor is subject
          to water damage because it is located below the
          water surface elevation.
The types of pumps are sketched in Figure 300.1.

Cost data for the vertical wet pit pump used in fresh
water and adjustment factors for the vertical dry pit
pumps and salt water pumping are given.  Costs for the
horizontal dry pit pumps are not included.  Material and
installation costs are separated as follows:
                             74

-------
        VERTICAL
        WET PIT
VERTICAL
DRY PIT
                         HORIZONTAL
                         DRY PIT
Fig.  300.1 - Types  of Cooling Water Circulating Pumps
                          75

-------
     1.   Pumps, motors and starter equipment and the cost
          to bring power from the substation to the motor
     2.   Equipment and labor costs required to set the
          pump and motor into place and make them opera-
          tional - Pump sizes and motor characteristics
          assumed in developing unit prices are given in
          Table 27.
                    Table 27.  PUMP AND
                   MOTOR CHARACTERISTICS

Pump
Capacity ,
mVsec
1.4
2.8
8.5
19.8

Speed,
rpm
880
587
351
220
Motor
Voltage,
Volts
460
460
4,160
4,160
The pumps and motors are selected based on the cooling
water flow rate and the increased head loss associated
with the new discharge.  A single pump is seldom chosen
to meet the pumping requirements for cooling water.  A
rule of thumb is to have 20 percent in excess of capacity
as a reserve.  The four sizes given here will not provide
the exact combination for every situation.  However, inter-
polation will provide a reasonable cost.

The trash racks and traveling screens of the existing pump
station will collect most of the debris that are drawn
from the intake.  After the water has passed through the
condenser, screening requirements are less stringent.  There-
fore,  an account for trash racks and traveling water
                            76

-------
screens is not included in pump costs.  The cost for
service water pumps are generally very small compared to
the circulating water pumps.  Thus, no costs are given.
Installation, Account 301.2

The key parameters are the pump and motor size and the
type of installation  (new pump station or modifying an
existing one).  Installation costs reflect using a crane /
and common and skilled labor to install the pump and
motor.  Costs for modifications to an existing station
will vary depending on the access to the pumps and motors.
In some installations an overhead gantry crane may be
provided while for others the equipment will have to be
hoisted out using a crane. It is assumed a crane will
be used to remove existing equipment, and the installation
and removal costs are equal.  Thus, the cost for installation
of pumps and motors into an existing facility is double
that for a new facility unless there is an existing empty
bay.

The costs for installation of valves and expansion joints
are included in costs for this account.
Valves and expansion joints,
Account 301.3
The key parameters are the type of valve and diameter of
pipe.

A common type of valve placed between the outlet pipe and
the pump is a motor-operated butterfly valve.  In many
                             77

-------
installations an expansion joint is placed between the
outlet piping and the pump to protect the pump installa-
tion.  Cost data for the butterfly valve and expansion
joints for diameters to 3.05 meters are given.
Pile foundation, Account 302.1

Pile foundations include the concrete pile cap and the
piles.  A discussion of concrete is given in Cost Category
7 and the piles in Cost Category 2.
Foundation slab, pit walls and
cover slab, Accounts 302.2 and 303.1
A discussion of these types of concrete structures are
given in Category 7.
Enclosure, Account 303.2

The key parameters are volume of the building required and
the type of construction material.

In warmer climates, a building may not be required and
weather-proofing the motor will suffice.  Means  (Reference
4) provides data on pre-engineered steel buildings.  Costs
include erection, normal doors, windows, and gutters.
Based on the data given in Means and company experience,
a value of $10/cubic meters of enclosure was selected.
                             78

-------
Foundation excavation,
Account 304
A discussion of structure excavation is given in Cost
Category 9.  Assume the excavation will have side slopes
of at least 2:1 and the outer dimensions are 1 meter beyond
the perimeter of the station.
Steel sheet piling, Account 305

A discussion of sheet piling costs is given in Cost
Category 2.
Structure backfill/ Account 306

A discussion of backfill operations is given in Cost
Category 8.  Estimate the volume of backfill by subtracting
the structure volume from the value used in Account 304
above.
Mobilization/ Account  308

Unit prices do not include mobilization and demobilization
costs.  The user is to add the mobilization cost as in-
dicated on the worksheet provided.  A discussion of mobil-
ization cost is given  in Cost Category 10.

Table 28 presents the correlation between cost account
number, worksheet, and figure number.  Costs are calculated
using the procedure outline in the introductory remarks to
this section and the worksheets in Tables 29 through 4.2.
                             79

-------
           Table 28.  PUMP STATION COST ACCOUNTS
Cost
Account
Number
301
301.1
301.2
301.3
302
302.1
Description
Mechanical - pumps and
motors
Costs for pumps and
motors
Installation costs
Costs for butterfly
valves and expansion
joints
Structural (below grade)
:
i
Pile Foundation: Costs
Figure
Number

301.1
301.2
301.3


Worksheet
Number

301.1
301.2
301.3
302.1

 302.2



 303

 303.1


 303.2

 304



 305


 306


307

308
  for the piles are given
  in Cost Category 2.
  Costs for concrete pile
  cap are given in Cost
  Category 7.

Costs for the foundation
  slab and pit walls.
  (see Cost Category 7)

Structural (above grade)

Costs for the cover slab.
  (see Cost Category 7)

Costs for an enclosure.

Costs for foundation
  excavation.  (see
  Cost Category 9)

Costs for piling.  (see
  Cost Category 2)
Structure backfill.
  Cost Category 8)

Other

Mobilization

                 80
                     (see
302.2
303.1


303.2

304



305


306


307

308

-------
Table 29.  COST CATEGORY 3
      COST SUMMATION

Cost
Account
Number
301
301.1
301.2
301.3
302
302.1
302.2
303
303.1
303.2
304
305
306
307
Worksheet 300
I
I
Description jj
1
Mechanical: Pumps «
and motors ?
Pumps and motors f BC3Q,
: Installation ( BC301
Valves and expansion !
i joints : BCom
' j U -I- •
;
Structural below \
grade
Pile foundation • BC302
i
Foundation slab 5 B^302
Structural above >
grade
Cover slab BC303
Enclosure BC303
Excavation , BC3Q4
Piling ; BC3Q5
; Backfill \ BC3Q6
, Other , BC307
Cost Category 3 Total Cost
(Enter Cost in Account 1101) BC3
308
Mobilization (Enter Cost MC3
in Account 1001)
Base
Cost
— *s
,=$
3=$
1=$
0 = $
1=$
.=$
=$
=$
=$
=$

=$

=$


            81

-------
                Table  30.   PUMPS AND  MOTORS

                      Worksheet 301.1


Design  Data  Required
                            2
Individual pump capacity  (m /sec)        Q  =    	
                                            (m3/sec)
                               X
Power requirements                       P  =	W

Number  of pumping units                  N  =	

Type of pumpa
Fresh  or  salt  water
 Base Cost
Enter Figure  301.1,  read base
   cost per pumping unit

Total base cost =BUC1 x N             BC
cost per pumping unit              BUG  =.i_
Cost Adjustment

Enter Figure  301.1, read adjust-      FD,
  ment factors for type of
  pump  (FD,)  and for fresh or
  salt water  (FD2)                    FD2
Adjusted Base Cost

Adjusted base cost = BC x FD, x

  FD2                             BC301.1
aVertical dry pit or vertical wet pit,
                           82

-------
                  Table  31.   INSTALLATION
                      Worksheet  301.2
 Design Data  Required

 Pump  capacity  (m  /sec)

 New pump  station  or
   modification to existing3

 Number of pumps                        N =
  Base  Cost

  Enter Figure  301.2,  read  base
    cost
  Total  cost for  installation =
                                       BC1 =1
    BC1  x  N                        BC301.2
   Costs  for  modifications  to  an  existing pump station
   assuming the old unit is removed.
                Table 32.  EXPANSION JOINTS
                	AND VALVES	

                      Worksheet 301.3
Design Data Required

Pump outlet pipe diameter                D =_
                                              meters

Number of valves                      N(V) =	

Number of joints                      N(J) =	
                             83

-------
        Table 32 (continued).  EXPANSION JOINTS
               	AND VALVES	

                     Worksheet 301.3
Base Cost

Enter Figure 301.3, read base
  cost for valves                     BC

Total cost for valves =
                                         ^
      x N(V)                           BC2  =$_
Enter Figure  301.3, read base
  cost for expansion  joints            BC.,  =$_
Total costs for expansion  joints
  = BC3 x N(J)                         BC4  =$_
Total base cost = BC0 + BC.        BCo      =$
                     £»      *±
               Table  33.  PILE FOUNDATION

                      Worksheet 302.1


Base Cost

Cost for piles (Cost  Category 2)       BC,  =$_
Cost for pile caps  (Cost Category  7)  EC,,  =$_
Total base cost = BC, + BC9       BCono
                    J-     ^          j U ^» JL
                           84

-------
               Table  34.  FOUNDATION SLAB
               	AND PIT WALLS	

                     Worksheet 302.2
Base Cost

Cost for foundation slab  (Cost
  Category 7)                         BC, =$_
Cost for pit walls                    BC2 =$_
Total cost = BC^ + BC2            BC3Q2 2 =—
                  Table  35.  COVER SLAB
                     Worksheet 303.1
Base Cost

Cost for cover slab or deck
   (Cost Category 7)               BC,.n, .. =$
                                    '303.1
                  Table  36-  ENCLOSURE

                     Worksheet 303.2


Design Data Required

Volume of building                      V =	m



Base Cost

Base cost = 10 x V                BC304 2 =^	
                            85

-------
            Table  37.  FOUNDATION EXCAVATION

                      Worksheet 304
Base Cost

Cost for excavation  (Cost           ^C304 =—
  Category 9)
              Table 38.   STEEL SHEET PILING

                      Worksheet 305
Base Cost

Cost for sheet piling (Cost
  Category 2)                       BC305
              Table  39.  STRUCTURE BACKFILL

                      Worksheet 306


Base Cost
Cost for structure backfill
  (Cost Category 8)                 BC
                                      306
                           86

-------
                    Table 40.  OTHER

                     Worksheet 307


Base Costs

Include costs not covered in this
  category but that relate to the
  pump station.  Data presented in other
  accounts may be useful in estimating
  "Other" costs.                      BC307



                Table 41.  MOBILIZATION

                     Worksheet 308


Mobilization Cost
 New pump station -$3,300              MC_ =$_
  The costs for mobilization of the
  equipment to excavate and backfill
  are  included in Category 4.a
aFor a new pump station, one crane could be used to install
 the pumps and for concrete work.  For a modification to an
 existing station, it was assumed that a crane from some
 other activity could be used.
                           87

-------
    5
    §

    1
00
CD
    <«
    •—•

    «
    tH
    H
    w
                         10              10


                       POWER, watts/pimp
Pump Type



Vertical wet pit


Vertical dry pit
Adjustment

Factor (FDi)



    1.0


    1.2




Adjustment
                                                               Fresh
                    1.0


                    2.0
                 Fig. 301.1 - Pumps and Motors

-------
oo
    o
    O
    o
    H
    •M-
    §

    H
16
12
8
4
0






















i






/







/
/





























/
/

/





y
/



x















/
/



/















/
1



s
'













/
/





X













/






XI













/







X"






































































Modification





















Ne













w













St













.at













io











•


n









































































            0   2   4   6   8   10  12  14  16  18   20



               PUMP CAPACITY, cubic meters/second
                                                          •H
                                                          O
I


I
O
O
O
u

E-i
H
                                                          W


                                                          1
                                                                        Butterfly Valves
                 DIAMETER, meters
            Fig. 301.2 - Pump and Motor Installation
         Fig. 301.3 - Costs  for Valves  and

                      Expansion Joints

-------
 COST  CATEGORY  4, CONDUITS

 Information  on the material and installation costs  for
 conduits  is  given in Cost Category 4.  Data given in
 Accounts  401 through 405 are for materials and Accounts
 406 and 407  are for installation.  The materials commonly
 used  for  conduits are:
      1.   concrete  (precast and cast-in place);
      2.   steel (corrugated metal and carbon steel); and
      3.   fiberglass.
 No definite  guidelines  for selection of pipe materials
 were  encountered in the case studies and literature sur-
 vey.   Differences in pipe materials are most evident in
 offshore  pipelines.  Precast concrete pipe is the heaviest
 pipe  and  requires larger equipment to lay pipe lengths
 equal to  steel and fiberglass pipe.  The additional weight
 of concrete  pipe has an advantage in water bodies where
 the currents may move a lighter pipe.  The steel pipe re-
 quires a  special coating; fiberglass does not, nor  does
 concrete.  Each of the pipes have standard fittings
 (elbows,  wyes,  etc.) but special carbon steel fittings
 can be fabricated on site.  Cast-in-place concrete  and
 carbon steel pipe are used most often for branching pipes
 and difficult  transitions.  The fiberglass pipe is  the
 lightest  and has no corrosion problems.  More care  is
 required  when  laying fiberglass pipe to prevent damage
 during laying.   The laying rates for all the conduits are
 dependent on diameter.

As a  rule of thumb, a system velocity between 2.0 and 3.0
meters/second  is used for sizing conduits.

Material handling can be an important consideration.  If
the pipe is  shipped to the site by rail, the material may
                            90

-------
be handled as many as three times before installing the
pipe into the trench.  Precast pipes are usually laid from
a crane barge offshore with two support cranes on land.

Costs for excavation, laying of the pipe, and backfill of
the pipe trench are given in separate accounts.  However,
the three are interrelated in the offshore work, and the
rate at which each operation is accomplished will affect
the total cost.  Equipment selection and productivity
used in developing unit prices reflect the interrelation-
ship between excavation, pipe laying, and backfill.

Data on the accounts are given in the following paragraphs.
Precast concrete pipe,
Account 401
Key parameters are the pipe diameter and the application.
Material costs are for a prestressed steel cylinder con-
crete pipe.  The pipe costs more for subaqueous use than
on land.  Prices reflect freight costs F.O.B. railcar to
any site approximately 645 kilometers from the point of
manufacture and include contractor markup.  Unit costs
include provision for the cost of fittings.  A maximum
diameter of 3.97 meters, except in the Northeast, where
the maximum is 3.66 meters is used on cost data sheets
because shipping restrictions prevent transporting larger
diameters.  Larger pipe diameters have been cast on the
site by the manufacturer, but these are special cases and
the costs are not given.
                            91

-------
Cast-in-place box conduit,
Account 402
Key parameters are formwork, reinforcing, placement and
finishing.  A square conduit with a wall thickness equal
to 15 percent of the inside diameter is considered.  The
cost reflects:
     1.  placing medium  (3,000 psi) strength concrete;
     2.  71 kilograms of rebar per cubic meter of concrete;
     3.  formwork costs  (which vary with the diameter); and
     4.  finishing costs.
Adjustment factors for the wall thickness are calculated
and shown in the cost data.  If this type is used off-
shore, costs for a cofferdam must be included.  Trenching,
backfill, cofferdams, and other installation costs are
not included.
Steel conduit and fittings,
Account 403.1 and 403.2
Key parameters are the diameter of the pipe and the method
of fabrication.  For diameters up to approximately 3.05
meters, it was assumed the pipe is shop fabricated (by the
manufacturer) and shipped to the site.  Larger diameters
have been shop fabricated, but it is a special order and
costs are not given.  Field fabrication for larger diameters
is done by field welding rolled steel plates.  The pipe
can be fabricated in the trench or positioned for offshore
laying.  If the pipe is fabricated in the trench, no
installation costs are added.  Field fabrication costs are
based to a large extent on data from Reference 12.  Shop
and field fabrication costs were developed for 1.27 cm
steel plate thickness.  Design adjustment factors for

                           92

-------
different plate thicknesses and for using hoop stiffeners
are given.  Fittings costs are given separately from the
pipe.  Steel fittings cost more than straight pipe because
of the additional welding required.
Corrugated metal pipe,
Account 404
The key parameter is the diameter of the pipe.  Up to 3.6 m
the pipe is  shop fabricated.  For diameters greater than
3.6 m the pipe is shipped to the site as galvanized plates.
The pipe is bolted together on site/ whether in the pipe
trench or positioned for offshore laying in completed
sections.  In either case, installation costs are added.
Fiberglass pipe, Account 405

The key parameter is the diameter of the pipe.  Fiberglass
pipe is shipped to the site  (except in the Northeast) in
diameters to 3.97 meters.  On occasion, this pipe has been
fabricated on site.  The costs for field fabricated pipe
are given.
Excavation of pipe trench
(land), Account 406.1
A discussion of land excavation is given in Cost Category 9
                            93

-------
 Laying pipe  on  land,
 Account 406.2
 Key parameters  are  the pipe material  and  fabrication.  The
 steel pipes,  corrugated metal,  and carbon steel  can be
 fabricated in the trench.  Installation costs are not
 added to the  material costs for cast-in-place concrete,
 or carbon steel pipe greater  than 3.05 m  diameter.  For
 diameters less  than 3.05 m, the carbon steel pipe can be
 shop or field fabricated.  Usually, the user can assume
 the pipe to be  shop fabricated  and installation  costs
 should be added.  Material handling is less of a problem
 when installation is on land.   The pipe can be offloaded
 into the trench from the truck  that hauls the pipe to the
 site or stockpiled  close enough to be handled by the crane
 used to install the pipe.  Therefore, no  costs for a yard
 crane are included  in this account.  The  lengths of pipe
 used to determine laying rates  are:
      1.   precast concrete  {4.9  meters for pipe diameters
          to 3.66 meters and 3.05 meters for pipe diameters
          greater than 3.66 meters);
      2.   corrugated metal  (7.3  meters); and
      3.   fiberglass (14.6 meters).
Onshore backfill, Account 406.3

Discussion of placement and the material used in backfill
of the pipe trench is given in Cost Category 8.
Pipe support systems,
Account 406.4
Data for the concrete or piles can be found in  the  dis-
cussion for Cost Category 7.
                            94

-------
Dewatering, Account 4_06. 5

The key parameter is the time required to lay the pipe
(see also the discussion for Account 904). Pumping costs
are given in terms of the dewatering period.
Offshore pipe trench excavation,
Account 407.1
A discussion of marine excavation is given in Cost
Category 9.
Laying pipe offshore,
Account 407.2
Key parameters are the weight of the pipe, length of the
pipe section installed, and meteorological conditions.  The
lighter pipes such as steel and fiberglass pipe can be laid
in longer lengths than concrete.  In some cases, manu-
factured lengths are joined on shore.  The lengths of pipe
sections assumed for developing laying rates are:
     1.   precast concrete  (9.8 meters for pipe diameters)
          to 3.66 meters and 6.1 meters for pipes 3.66
          or longer);
     2.   corrugated metal  (12.2 meters);
     3.   carbon steel  (12.2 meters for pipe diameters to
          3.66 meters and 6.1 meters for pipes 3.66 meters
          or longer)» and
     4.   fiberglass  (15.3 meters).
In offshore laying, all the pipes are joined using a bell
and spigot joint.  Divers bring together the sections
using bolts fixed to the outside of the pipe.  The depth
at which the pipe is laid will affect the costs because
of special rigging and diver problems.  An adjustment
                           95

-------
 factor  for  laying pipe in depths greater than 14 meters
 is  included.

 Material handling at the site is an important considera-
 tion.   In some cases, the pipe is off-loaded at the rail
 head, hauled  to a yard and reloaded onto a barge for
 transport to  the site.  Alternatively, the pipe can be
 transported to the site on a barge loaded at a port near
 the manufacturer's permanent or temporary plant.  Cost
 data are given for ground transport to the site  (the
 first case).

 Two support cranes on shore are considered in addition to
 a  flat  top  and crane barge used in laying the pipe.

 In some areas, water currents will cause siltation of the
 trench  to the extent of limiting the length of pipe that
 can be  laid.  An example is laying a pipeline in the surf
 zone of a lake or ocean.  A discussion of estimating costs
 for laying  pipe in the surf zone and river is given in
 Account 408.
Offshore backfill, Account  407.3

A discussion of backfilling the pipe trench including  the
cushion fill and common earth is included in Cost  Category
8.
Pipe support systems,
Account 407.4	

Key parameters are the foundation  (earth or  rock)  and the
weight of the pipe.  If in the area where  the  pipe is laid,
                            96

-------
the soil bearing capacity is poor, a concrete cradle
supported by piles may be required.  Data to estimate the
cost for the piles and concrete are included in Cost
Category 2 and Cost Category 7, respectively.  The lighter
pipes may require concrete anchors placed to restrict
movement.  Data for tremie concrete are given in Category
7.
Riprap protection, Account407.5

Riprap protection may be required to protect the backfill
from erosion.  A discussion of offshore placement of rip-
rap is given in Category 2.
Cofferdam, Account 407.6

In some instances, offshore work cannot be done by divers,
A cofferdam is constructed and the area dewatered.  An
example of the possible use for cofferdam is extending a
single port discharge further offshore.  If the existing
outfall were encased in concrete, the area might be de-
watered to permit attaching the additional pipe.
Other/ Account 408

Installation of the pipe in the river or the surf zone
is more costly than for conventional offshore laying
methods.  The contractor may over-excavate the trench to
allow for siltation.  However, over-excavation may not
be a viable alternative in some cases and the laying of
pipe may involve:
                           97

-------
      1.   building a trestle constructed of steel H-pile
          bents with steel beam stringers and wooden
          planks   (The trestle extends from the shore to
          where littoral currents no longer influence the
          pipe laying operation);
      2.   positioning a crane on the trestle for driving
          sheet piling to keep the currents from filling
          the trench with silt   (The crane can be used to
          excavate the trench, lay the pipe and backfill
          the trench);
      3.   placing concrete around top of the pipe to
          prevent erosion of the backfill.
 Costs for this type of operation are difficult to assess
 because  the  length of the zone is not well defined.  Also
 this  is  a method of construction and probably will not be
 delineated on the available drawings.  A rule of thumb for
 estimating the cost for building the trestle is to assume
 $l,500/meter.  Other costs such as shoring and pipe laying
 can be estimated using the procedures outlined in the
 manual.  Because the crane is working from the trestle,
 costs for land-based operations may be appropriate.  To
 estimate the length to which the special construction
 method applies, assume a water depth between 2 and 3 meters
 divides  the  surf zone and conventional laying methods.
Mobilization, Account  409

The cost for mobilization and demobilization is not  in-
cluded in the unit price.  The costs for mobilizing  equip-
ment to excavate the pipe trench, lay the pipe and back-
fill the trench are given.  A discussion of mobilization
is given in Category 10.

Table 42 presents the  correlation between cost account
number, worksheet, and figure number.  Costs are  cal-
culated using the procedure outlined in the introductory
                            98

-------
remarks to this section and the worksheets in Tables 43
through 62.
            Table 42.  CONDUIT COST ACCOUNTS
Cost
Account
Number
Description
Figure
Number
Worksheet
Number
401
402
403
403.1

403.2


404
405
406


406.1
Precast concrete pipe costs
  for materials for diameters
  to 4 meters•

Cast-in-place box conduit
  costs for in-place casting
  of square concrete conduits.

Steel conduit and fittings
  costs for materials and
  fabrication for diameters
  to 6 meters•

Pipe costs

Cost of fittings, including
  elbows, reducers and tees.

Corrugated metal pipe
  material and fabrication
  costs for diameters to 6
  meters.  Installation
  costs are not included.

Fiberglass pipe.  Costs for
  material and fabrication
  for diameters to 6 meters.
  Installation costs are not
  included.

Cost for land installation
  of pipe*

Costs for onshore excava-
  tion of pipe trench (see
  Cost Category 9)•
 401
 402
  401
  402
 403.1

 403.2


 404
  403.1

  403.2


  404
 405
  405
          406.1
                           99

-------
Table 42 (continued).   CONDUIT COST ACCOUNTS
Cost
Account
Number
406.2
406.3
406.4
406.5
407
407.1
407.2
407.3
407.4
407.5
407.6
408
409
Description
Costs for laying pipe onshore-
Costs for cushion fill and
trench backfill (see Cost
Category 8) •
Costs for pipe supports,
including concrete thrust
blocks, encasement,
cradles, and piles-
Cost for dewatering the
pipe trench.
Cost for marine installation
of pipe:
Offshore excavation costs
for pipe trench (see Cost
Category 9) .
Costs for laying pipe off-
shore .
Costs for fill cushion and
trench backfill (see Cost
Category 8) .
Costs for pipe supports ,
including concrete thrust
blocks , encasement ,
cradles, and piles-
Costs for riprap protection
for pipe trench •
Costs for materials and
construction of coffer-
dams used in pipe in-
stallation •
Other
Mobilization
Figure
Number
406.2
^•B*

406.5

• tM
407.2
— —

—
"
—
—
Worksheet
Number
406.2
406.3
406.4
406.5

407.1
407.2
407.3
407.4
407.5
407.6
408
409
                     100

-------
Table 43.  COST CATEGORY 4
      COST SUMMATION
Worksheet 400
Cost
Account
Number
401
402
403
403.1
403.2
404
405
406
406.1
406.2
406.3
406.4
406.5
407
407.1
407.2
407.3
Description
Precast concrete pipe
Cast-in-place box
culvert
Steel conduit
Steel pipe
Steel fittings
Corrugated metal pipe
Fiberglass pipe
Land installation of
pipe
Onshore excavation
Onshore pipe laying
Cushion fill and
backfill
Pipe supports
Dewatering
Marine installation of
pipe
Offshore excavation
Offshore pipe laying
Cushion fill and
-backfill
Base
Cost
BC401
BC402
BC403.
BC403.
BC404
BC405
BC406.
BC406.
BC406.
BC406.
BC406.
BC407.
BC407.
BC407.
=$

-i =
2~

=
T ~
*i~
o=
A~
5~
1 ~
J.
->=
0=

             101

-------
          Table 43 (continued).   COST CATEGORY 4
               	COST SUMMATION	

                      Worksheet 400
Cost
Account
Number
407.4
407.5
407.6
408
Description
Pipe supports
Riprap protection
Cofferdams
Other
Base
Cost
BC407.
BC407.
BC407.
BC408
A~
5~
6~


Cost Category 4 Total Cost
  (Enter Cost in Account 1101)
                                      BC
                                        4
409
          Mobilization  (Enter
            Cost in Account 1001)
                                             =$
            Table 44.   PRECAST CONCRETE PIPE

                      Worksheet 401

Design Data Required

Pipe diameter

Pipe length                             L =

Land or marine installation
                                                      m
                                                      m
Base Cost

Enter Figure 401, read base unit
  cost per lineal meter.

Base cost = L  x BUG
                                     BC
                                       BUG =$_

                                       401 =$
                           102

-------
                Table  45.  CAST-IN-PLACE
                	BOX CONDUIT	

                      Worksheet 402
Design Data Required

Width or height of square conduit          	_m

Wall thickness                             	cm

Length of pipe                          L =	m



Base Cost

Enter Figure 402, read base unit      BUG =$	
  cost per lineal meter

Base cost = L x BUG                   BC  =$
Cost Adjustments

Enter Figure 402, read design adjust-
  ment factor for wall thickness      F
                                       D
Adjusted Base Cost

Base cost of materials and fabrica-
  tion = BC x FD                     BC402~£-
                           103

-------
                Table 46.   STEEL CONDUIT

                     Worksheet  403.1


 Design Data Required

 Pipe diameter                              	m

 Wall thickness                             	cm

 With or without  stiffeners       	

 Pipe length                             L =	m

 Shop or field fabricationa
Base Cost

Enter Figure  403.1, read base unit
   cost per  lineal meter               BUG =$
Base cost = L x BUG                   BC  =$
Cost Adjustments

Enter Figure 403.1, read design      Fn^1^:
  adjustment factors for wall
  thickness, stiffeners and           D^  ':
  fabrication                        F  (3)>
Adjusted Base Cost

Adjusted base cost of materials
  and fabrication = BC x FD(1) x
  FD(2J XF
aFor diameters to 3.05 meters, assume shop fabrication.
                           104

-------
                    Table 47.   STEEL
                      PIPE FITTINGS

                     Worksheet 403.2
Design Data Required

Type  (elbow, reducer, tee,
  connection)                    	
Diameter  (if a fitting diameter
  varies, use largest diameter)            	m

Angle  (for reducer or connection)          	°

Number                                  N =	

Wall thickness                             	cm

With or without stiffeners



Base Cost

Enter Figure 403.2, read base unit
  cost per fitting                    BUG =$	
Base cost = N x BUG                   BC  =$
Cost Adjustments

Enter Figure 403.1, read design      F_(l)=_
  adjustment factors for wall        „  (2)=
  thickness and stiffeners and        D
  fabrication                        F  (3)=_

Adjusted Base Cost

Adjusted base cost of materials and
  fabrication for particular type
  of fitting = BC x Fn(l) x Fn(2)  BC,n., 9=$
V F ' "* v               U               tV3 • 4
   D
                           105

-------
            Table  48.  CORRUGATED METAL PIPE

                      Worksheet 404


Design Data Required

Pipe diameter                              	m

Pipe length                             L =	m



Base Cost

Enter Figure 404, read base unit
  cost per lineal meter               BUG =$	
Base cost = L x BUG                 BC404
               Table  49.  FIBERGLASS PIPE

                      Worksheet 405


Design Data Required

Pipe diameter                              	m

Pipe length                             L =	m



Base Cost

Enter Figure 405, read base unit
  cost per lineal meter               BUG =§
Base cost = L x BUG                 BCanR
                           106

-------
                 Table  50.  ONSHORE PIPE
                    TRENCH EXCAVATION

                     Worksheet 406.1


Base Cost

Refer to Cost Accounts 901 or 902
  for cost estimating procedure    ^406 i~§.	




             Table  51.  LAYING PIPE ON LAND

                     Worksheet 406.2


Design Data Required

Length of pipe                          L =	m

Diameter of pipe                        D =	m

Material                                   	



Base Cost

Enter Figure 406.2, read base unit
  cost per lineal meter               BUG =$	
Base cost = L x BUG               BC406.2 =—
               Table 52.  ONSHORE BACKFILL

                     Worksheet 406.3


Base Cost

Refer to Cost Category 8 for appro-
  priate cost accounts and estimating
  procedures                      BC406.3
                            107

-------
            Table 53.  PIPE SUPPORT SYSTEMS

                    Worksheet 406.4
Base Cost
Refer to Cost Category 7 for concrete
  costs and  2 for piling costs     BC4Q6.4 =—
                Table 54.  DEWATERING

                   Worksheet 406.5


Design Data Required

Length of pipes                          L = 	
             3
Pipe material                	

Diameter                                                     m
Base Cost

Enter Figure 406.5, read base unit
  cost for  Dewatering                BUG   =$
Base cost = BUG x L                BC.n/-  c =$
                                     4Ub.D  —
asteel,
 Concrete/ or
 Fiberglass Pipe
               Table 55.  OFFSHORE PIPE
                   TRENCH EXCAVATION

                    Worksheet 407.1


Base Cost

Refer to Cost Accounts  901 or 902
  for cost estimating procedure     BC,«.,
                                      407,


                           108

-------
             Table 56.  LAYING OFFSHORE PIPE

                    Worksheet 407.2


Design Data Required

Length of pipe                          L = 	m

Diameter                                D = 	m

Pipe material	
Depth of water                   	m



Base Cost

Enter Figure 407.2, read base unit
  cost per lineal meter              BUG =$	/m

Base cost = L x BUG                  BC  =$    ^	
Cost Adjustment

Enter Figure 407.2, read adjustment
  factor for water depth             FD =_
Adjusted Base Cost

Adjusted base cost for laying pipe
  offshore = BC x FD               BC407 '>==—
             Table  57.  OFFSHORE BACKFILL

                    Worksheet 407.3

B-'se Cost

Refer to Cost Category 8 for appro-
  priate cost accounts and cost
  estimating procedure            BC407 3
                            309

-------
            Table  58.  PIPE SUPPORT SYSTEMS

                     Worksheet 407.4


Base Cost

Refer to Cost Categories 7 and 2 for
  appropriate cost accounts and
  estimating procedures            BC407.4=—
              Table 59.  RIPRAP PROTECTION

                    Worksheet  407.5
Base Cost

Refer to Cost Account 201.2 for
  estimating procedure             BC.Q^ ,--$_
                 Table 60.  COFFERDAMS

                     Worksheet 407.6
Base Cost
Refer to Cost Category 2 for
  appropriate cost accounts and
  estimating procedures            BC.n_  =$
                                     T* U / * D ~~"~
                           no

-------
                    Table 61.  OTHER

                      Worksheet 408
Base Cost
Include costs not covered  in this
  category but that relate to
  conduits.  Data presented in other
  accounts may be useful in estimating
  "Other" costs.

Also the costs for the  surf zone are
  to be added in this account.       BC408 =—
                 Table 62.  MOBILIZATION

                      Worksheet 409


Data Requirement

                                Mobilization
Description                     Cost	  Summation

For offshore installation of
  a conduit add $96,000a          $96,000
For land installation of
  the conduit add                 $ 6,600

For hauling fill                  $   600
Mobilization Cost

Mobilization = the total of the
  summation column (above)               MC^ =$_
aThe mobilization costs are inclusive of accounts 407*1
 through 407.6.
                            Ill

-------
I-1
M
N>
                              OJ
                              4J

                              I
                              o
                              o
                              t-l
                              8
                              H
                                              2345



                                                PIPE DIAMETER, meters
                                    Fig.  401 - Costs for Precast Concrete Pipe

-------
0)
+J
o
o
o
rH
•w-
tm •



§


EH
H
I
PQ
4^_U
                        2f
                                                            Factors for Variation  in Wall  Thickness;
Diameter  	Wall Thickness  (on)	

(Meters)   15   30   45   60   75   90



   1      1.00  ~~   ——   ™"   —~   —~

   2      0.73 1.00 1.28 1.60  —

   3      0.60 0.79 1.00 1.22 1.46  —

   4       —  0.66 0.83 1.00 1.19 1.38

   5       —   —  0.70 0.85 1.00 1.16

   g       __   __   __  o.74 0.87 1.00
                 2345



               BOX CULVERT DIMENSION, meters
         Fig.  402 - Cost for Cast-In-Place Xox Conduit

-------
1
o
o
8
EH
                                                        10
                                                      c   8
                                                     •H
                                                     IM

                                                     §   6
                                                     iH
                                                     to-
                                                     V^
                                                     8
                                                     PL)
                                                     CO
                                                     <:
                                                                                     B
                INSIDE DIAMETER, meters
   Thickness (cm):  .635 .953 1.27 1.588 1.905 2.22
   Factor FD (1):   .50  .75  1.0  1.25  1.5   1.75

   With Stiffeners, FD(2)  =1.6
   Shop Fabrication, FD(3)  =  .65
        Fig.  403.1 - Cost for Carbon Steel Pipe
                                                                   INSIDE DIAMETER, meters
                                                           Curve
                                                             A   90° Elbow  (mitered)
                                                             B   Reducer  (plotted for larger diam.)
                                                             C   45° Connection
                                                             D   Tee Connection
                                                             E   45° Elbow  (mitered)
                                                               Fig. 403.2 - Cost for Elbows,
                                                                  Reducers, and Connections

-------
0)
o
o
to-
EH
el
8

K

W
    10

                                                      fc
                                                      5
                                                     o
                                                     o
                                                     •OT-
                                                     EH
                                                     CO
                                                     w
                                                         30
                                                         25
                                                     8   15
                                                     EH
                                                         10
                INSIDE DIAMETER, meters
                                                                    INSIDE DIAMETER, meters
       Fig.  404 - Costs for Corrugated  Steel Pipe
                                                              Fig. 405 - Cost for Fiberglass Pipe

-------
V)
a
o
o
              2345

                PIPE DIAMETER, meters


   	Precast Concrete Pipe

   - -  - -Fiberglass Pipe

   — — ^—Corrugated Metal Pipe

   x -  x   Carbon Steel (for shop fabrica-

             tion only)
             Fig.  406.2 - Costs for Pipe

                Installation (Land)
                                                    H
O

(0
u
0)
+J

S

o
o
                                                    o
                                                    o
                                                    o
                                                    H
                                                    to-
                                                    a
                                                    CQ
             2345


             DIAMETER OF PIPE, meters


           Precast Concrete Pipe
  - -  - - Fiberglass Pipe

  — — —- Corrugated Metal Pipe

   x - x  Carbon Steel Pipe  (Shop Fabricated)


     Note:  For field fabricated carbon steel

            pipe, use Adjustment Factor of 1.53



  Fig,  406,5 - Dewatering Costs f,or Pipe Installation

-------
           2345

             PIPE DIAMETER, meters
                                                    	 Precast Concrete Pipe
                                                    	 Fiberglass Pipe
                                                    	 Corrugated Metal Pipe
                                                    x - x Carbon Steel
                                                    Water Depth

                                                    Less than 14 m

                                                    Greater than 14 m
Adjustment
Factor

   1.0

   1.2
Fig. 407.2 - Costs for Pipe Installation (Marine)

-------
COST CATEGORY 5, TUNNELING

Data is provided for excavation, lining, support systems,
and dewatering.  A lay classification of rock characteris-
tics is adopted to simplify the discussion.  The correlation
between rock types, quality designation*and classification
is given  in Table 63.
                 Table  63.  ROCK TYPES
Rock Description
Hard and intact; hard
stratified or schistose
Massive, moderately jointed;
moderately blocky and seamy
Very blocky and seamy
Shattered and/or unconsolidated
Unconsolidated or completely
crushed; gravel or sand
RQDa
> 95
75-95
50-75
25-50
< 25
Classification
Excellent
Good
Fair
Poor
Very poor
 Rock Quality Designation:  A modified core recovery tech-
 nique based indirectly on the number of fractures and
 amount of softening or alteration in the rock mass as
 observed in cores from a 3-inch drill hole.

The system of using lay classifications is useful in the
discussion but often the descriptions overlap and do not
exactly fit all cases.  However, the discrepancies do not
adversely affect the estimating accuracy.

Rock quality affects excavation and the type of rock support
system.  In addition, costs are dependent on the type of
heading; wet or dry.  A wet heading is defined as having
                             118

-------
more than 0.4 cubic meters/minute of water flowing into the
tunnel.  If adequate information is available on conditions
expected along the proposed tunnel alignment, the tunnel
should be divided into reaches of generally similar charac-
teristics and the construction cost estimated for each
reach individually.

When the design information is limited, the user should as-
sume the best condition encountered will be classified as
fair.  Four support systems are used alone or in combination
depending on site conditions:
     1.   Rock bolts - Bolts used to tie rock closest to ex-
          cavation back into undisturbed strata.
     2.   Shotcrete - Mixture of sand and cement pneumatical-
          ly applied to roof and walls of tunnel.  In this
          study, costs include grouting for rock bolts.  For
          poor rock conditions, shotcrete is usually com-
          bined with other support alternatives  (see Figure
          500.1).
     3.   Horseshoe ribs - As rock conditions become poorer,
          continuous roof support is required.  A common
          support system consists of a series of horseshoe-
          shaped ribs made from steel wide-flange beams and
          separated by timber lagging  (see Figure 500.1).
     4.   Circular ribs - In poor quality rock, circular
          steel ribs support the circumference of the tunnel
          excavation (see Figure 500.1).
Types of support and relative sizes and dimensions associated
with the lay rock classifications are given in Table 64  (see
Reference 5).

Unless specifically noted, each support system is used inde-
pendently.  Thus when the user seeks the cost for a support
system, he should select the type given in his design plans
and use that cost alone  (except where noted in Table 64).
                             119

-------
                                   SYMMETRICAL ABOUT £
NJ
o
                                      STEEL RIS


                                    DESIGN CONCRETE LINE
                                    CLEARANCE LINE
                                    FOR SUPPORT
                                                             SHOT CRETE
                                                                           iScVV •••-
                              Circular  Rib
Horseshoe Rib
                                  Fig.  500.1 -  Structural Supports

-------
The design velocity for tunnels is approximately 2 to 3
meters/second.  Data for the accounts of Cost Category 5
are given in the following paragraphs.
Tunnel excavation, Account  501

Key parameters are the geological condition of the tunnel
area, the size of the tunnel and the type of heading  (wet
or dry).  Data are given for circular tunnels with a diam-
eter of 3 to 8 meters.  For other shapes/ assume an equiva-
lent diameter, or the height dimension of the tunnel.

Excavation costs vary substantially with the type of rock
and with the size of tunnel.  Data presented in "Tunneling-
The State of the Art", by R. S. Mayo and Associates  (Refer-
ence 5) were used as the source for excavation costs.

Costs were estimated for each of the following rock condi-
tions :
     1.   Dry headings in:
          a.   stratified or schistose rock  (excellent)?
          b.   massive moderately jointed rock  (good);
          c.   moderately blocky and seamy rock  (good);
          d.   very blocky  and seamy rock  (fair); and
          e.   completely crushed or unconsolidated sedi-
               ments  (very  poor).
     2.   Wet headings in:
          a.   competent rock  (excellent to poor); and
          b.   crushed rock or unconsolidated sediments
               very poor) ,
Tunnels may be excavated using a boring machine or by  con-
ventional means.  The data  given here are based on conven-
tional mining techniques.   For cooling water tunnels,  shaft

                            121

-------
headings are required and costs must be included for shaft
excavation and hoisting equipment.  It was assumed for all
excavation costs that tunnel spoil would be disposed of in
the immediate vicinity  (within one kilometer).  For opera-
tions in which a disposal area is not located nearby, the
hauling costs should be added to the excavation costs  (refer
to Category 1 for hauling costs).
Rock bolts, Account 502.1

Key parameters are the rock bolt spacing and the penetration
length.  Rock bolts are installed by drilling a hole into the
rock, placing the bolt and grouting the bolt into place
(optional).  The spacing is increased as the rock conditions
improve.  The bolts are placed into the crown of the tunnel
bore.  Refer to Table 64 for examples of rock bolt spacings
and the interrelationship of tunnel support systems.
Shotcrete, Account 502.2

Key parameters are thickness and the percent of the tunnel
crown covered.  Shotcrete is a structural measure used during
construction of the tunnel and is in addition to lining
(Account 503).  Shotcrete can be used alone as rock support
or in combination with other systems.  For poor or very poor
rock, shotcrete is usually used in combinations with other
support systems (refer to Table 64).
                           122

-------
                            Table 64.   ROCK SUPPORT CRITERIA
  Rock
  Quality
Rock Bolts .
Recommended*
Shotcrete  .
Recommended
Steel Sets  .
Recommended'
  Excellent
   (RQD  >  90)

  Good
   (75
-------
Structural steel supports,
Accounts 502.3, 502.4 and 502.5
Key parameters are the tunnel diameter spacing and size of
the members.  Mayo  (Reference 5) gives the support spacing
based on the comparison between rock loading and tunnel
dimensions.  The size of the members is based on the data
given in Reference 13.  Timber lagging is used between the
steel sets to contain loose rocks and separate the sets.
Concrete tunnel lining,
Account 503
The key parameter is the lining thickness.  An allowance
should be made for over-excavation of the tunnel and grout-
ing to fill voids between the lining.  A factor of 1.2 times
"neat line dimensions" is recommended.  The tunnel lining
does provide structural support.  However, the primary func-
tion is to reduce hydraulic friction loss.  All tunnels are
not lined but usually omitting the lining is reserved for
tunnels in excellent rock that were excavated using a boring
machine.
Tunnel dewatering, Account 504

The key parameter is the inflow rate.  Pump and pipe sizes
are assumed for given inflow rates.  The rental and labor
costs were calculated and related to the inflow.
                           124

-------
Shafts, Account 505

For cooling water tunnels, shaft headings are required and
costs must be included for shaft excavation hoisting equip-
ment and additional structural support.  Costs for shaft
headings are calculated by multiplying the total horizontal
tunnel costs times 2  (Reference 5).  If a shaft is to be
excavated offshore, it will probably be to connect some type
of diffuser.  The costs for the shafts are given here and
the costs for cofferdams and other installation charges are
included in Cost Category 6.

Mobilization is not given an account number.  Mobilization
costs are estimated to be 5 percent of the construction
costs.  The calculation is done on summary worksheet number
500.

To estimate the cost  for tunnel excavation and support sys-
tems, the outside diameter is used.  Whereas, selection of
the tunnel for hydraulic criteria is based on inside dimen-
sion.  The relationship between inside and outside diameter
for different rock quality designations is given in Figure
500.4  (placed with the cost graphs).

Table 65 presents the correlation between cost account
number, worksheet, and figure number.  Costs are calculated
using the procedure outlined in the introductory remarks to
this section and the worksheets in Tables 66 through 77.
                            125

-------
Table 65.  TUNNEL COST ACCOUNTS
Cost
Account
Number
501
501.1
501.2
502
502.1
502.2
502.3
502.4
502.5
503
504
505
506
Description
Costs for excavating tunnels.
Hauling costs are not in-
cluded.
Costs for dry tunneling.
Costs for wet tunneling.
Costs for support systems
are given for tunnel out-
side diameters from 3 to
8 meters.
Costs for rock bolt support.
Costs for shotcrete support.
Costs for horseshoe rib
support .
Costs for circular rib
support .
Costs for timber lagging
used between the ribs
to support loose stones .
Costs for concrete lining
for tunnel diameters
from 3 to 9 meters.
Costs for tunnel de-
watering.
Shafts: Costs for vertical
shafts are approximately
twice those for tunneling
horizontally.
Other
Figure
Number

501.1
501.2

502.1
502.2
502.3
502.4
502.5
503
504

— —
Worksheet
Number

501.1
501.2

502.1
502.2
502.3
502.4
502.5
503
504
505
506
              126

-------
               Table 66.   COST CATEGORY 5
               	COST SUMMATION	

                      Worksheet 500
Cost
Account
Number
501
501.1
501.2
502
502.1
502.2
502.3
502.4
502.5
503
504
505
506
Description
Excavation
Dry tunneling excavation
Wet tunneling excavation
Tunnel support systems
Rock bolts
Sho terete
Horseshoe ribs
Circular ribs
Timber Lagging
Tunnel lining
Tunnel dewatering
Shafts
Other
Base
Cost
BC-01 1=$
BC"01 -=$
BCem° i=^
BC™ „=$
BC,-ft-> o=$
BC50- 4=$
BC™ .=$
BO™ =$
BCenjj =^
BC-05 =$
nc =S
^nr; *

Total Cost Category 5 Adjusted Cost
  (Enter cost in Account 1101)
                                      BC
=$
Mobili zation
  BC5 x 0.05
                                      MCr
                           127

-------
            Table 67.   TUNNELING EXCAVATION,  DRY

                     Worksheet  501.1
Design Data Required

Tunnel outside diameter                    	m

Rock classification  (see Table 63)         	
Tunnel  length                           L =	m
Base Cost

Enter Figure  501.1, read base unit
   cost per  lineal meter               BUG =$_
Base cost = L x BUG               BC501 1 ~—
           Table 68.  TUNNELING EXCAVATION, WET

                     Worksheet 501.2
Design Data Required

Tunnel outside diameter                    	m

Rock classification  (see Table 63)
Tunnel or vertical shaft length         L =          m
Base Cost

Enter Figure 501.2, read base unit
  cost per lineal meter               BUG =$
Base cost = L x BUG               BCcm o
                                    O V J. • £*
a
 Figure 500.4 gives the relationship between  inside and
 outside diameter.

                           128

-------
               Table 69.  ROCK BOLTS



                     Worksheet 502.1




Design Data Required



Tunnel outside diameter                              m



Rock classification  (see Table 63)



Tunnel length                           L =          m






Base Cost



Enter Figure 502.1, read base unit

  cost per lineal meter               BUG =$
Base cost = L x BUG               BCcno i
                                    D U «& • .L
                 Table 70.  SHOTCRETE


                     Worksheet 502.2





Design Data Required



Tunnel outside diameter                    	m



Rock classification                        	



Tunnel length                           L =	m







Base Cost



Enter Figure 502.2, read base unit cost

  per lineal meter                    BUG =$	
Base cost = L x BUG               BC502.2
                           129

-------
             Table 71.   HORSESHOE RIB SUPPORT

                     Worksheet 502.3


 Design Data Required

 Tunnel outside diameter                    	m

 Rock classificationa
 Tunnel length                           L -	m
 Base Cost

 Enter Figure 502.3,  estimate base
   unit cost for given rock
   classification zone                 BUG =$
 Base cost = L x BUG               BC502  3  =s—
  Good,  fair or poor.   For poor or very poor rock,  recommend
  using  the costs for  circular ribs (see Worksheet  502.4).
  Rock classifications are given in Table 63.
             Table  72.  CIRCULAR RIB SUPPORT

                     Worksheet 502.4


Design Data Required

Tunnel outside diameter                       	m

Rock classification
Tunnel length                              L =
m
aPoor or very poor classification  (see Table  63).
                           130

-------
       Table 72 (continued).  CIRCULAR RIB SUPPORT

                     Worksheet 502.4
Base Cost

Enter Figure 502.4, estimate base
  unit cost for given rock
  classification zone                    BUG =$
Base cost = L x BUG                  BC502 4
                 Table 73.  TIMBER LAGGING

                      Worksheet  502.5


 Design  Data  Required

 Tunnel  outside  diameter                    	m

 Rock  classification                       	
 Tunnel  length                          L =	m
 Base  Cost

 Enter Figure  502.5,  read base  unit
   cost per  lineal meter               BUG =$_
Base  cost =  L  x  BUG               BC502.5 =—
 aGood, fair, poor, or poor with wet heading (see Tables
  63 and 64}.
                            131

-------
             Table 74.   CONCRETE TUNNEL LINING

                       Worksheet 503


 Design Data Required

 Tunnel outside diameter                    	m

 Rock classificationa
 Tunnel length                           L =	m
 Base Cost

 Enter Figure 503,  read base  unit
   cost per lineal  meter               BUG =$
 Base cost = L x BUG                 BC503
 aExcellent,  good to  fair, poor  (see Table  641.
               Table 75.   TUNNEL DEWATERING
                       Worksheet 504


Design Data Required

Seepage classification                        	

Length of wet heading                      L =  	m



Base Cost

Enter Figure 504, read base cost      BC_ft..  =$
  for wet heading lengths
                                        504
 Three seepage rates are given:  light, moderate, and heavy.
 Unless data is available, assume a moderate flow rate  for
 wet headings.
                            132

-------
                    Table 76.  SHAFTS

                      Worksheet 505


Data Required

Base cost for:

  Account 501                          BCcrn

  Account 502                          BCCrt0 =$

  Account 503                          B
    Total                              BC.J   =$
Base Cost

Base cost = BCL. x 2                    BC..-.. =$
              n                          DUD  —
                    Table 77.  OTHER

                      Worksheet 506


Base Cost

Include costs not covered in this
  category but that relate to
  tunneling.  Data presented in
  other accounts may be useful in
  estimating "Other" costs.            BC506
                            133

-------
CO
                                                           4J
                                                           
-------
OJ
(J1
    4J


    I
    O
    O
    O
    iH
    -co-
    H
    en
    O
    o
     a
         15
         10
                                                            24
 a!   20
 &
o
o

•CO-
H
s
o
H
M
                                                         w
  £•
0
                                                                 ^1  I
                                                                              Excellent to Good
                                                                                              10
                                             12
                 OUTSIDE TUNNEL DIAMETER, meters

           NOTE:   Dewatering  costs should be added to
                   total cost  determined from above base
                   unit  costs.
           OUTSIDE TUNNEL DIAMETER, meters
            Fig.  501.2  -  Tunnel  Excavation Costs for
                          Wet Headings
           Fig.  502.1 -  Costs  for  Rock Bolt  Supports

-------
CO
S-i
0)
4J
0)
o
o
t-l
H
CO
O
O
W
                                                                                    Excellent Zone
                                                                                             T
                OUTSIDE TUNNEL DIAMETER, meters

       NOTE:   For poor rock conditions, shotcrete

               support methods are usually combined
               with one of the other support
               alternatives.
     OUTSIDE TUNNEL DIAMETER, meters
         Fig.  502.2 - Costs for Shotcrete Support
Fig. 502.3 - Cost for Continuous Horseshoe
             Rib Supports

-------
CO
m
0)
4-1

-------
OJ
oo
     M
     
-------
COST CATEGORY 6, DIFFUSER


Information on materials and  installation of diffusers is

provided.  Three types of diffusers  considered are as follows:

     1.   Single port - A single  port discharge is a simple
          type of diffuser.   The  outfall is usually the open
          end of a conduit with a concrete structure for
          protection or to divert the flow vertically.  Costs
          for a single port discharge are given separately
          from the other diffusers in Account 604.

     2.   Conduit diffuser -  The  term "conduit diffuser"
          describes a series  of nozzles or slots arranged
          along a conduit manifold.   The conduit diffuser
          is set in a pipe trench on the lake bed and can
          be connected to the discharge pipe or a tunnel
           (see Figure 600.1).
         ^-&::v^v:vfr:v&v^
          M\#AW/A^v/>AV.W/^^
                 Fig.  600.1  -  Conduit Diffuser
                              139

-------
3.    Tunnel diffuser - The term "tunnel diffuser"
     refers to a series of nozzles individually
     grouted into a tunnel (See Figure 600.2).
            Fiy. 600.2 - Tunnel Diffuser
                       140

-------
The diffuser can be an extension of the conduit or tunnel,
and can  be  perpendicular to the conveyance pipe or any angle
in between.

The estimate for a conduit  diffuser is the  sum of the  in-
dividual costs for nozzles  (601), the manifold (602.1  to
602.3) and installation  of  the  diffuser as  a unit (603.1).
In addition, Accounts 603.2  to  603.7 may apply.  The pro-
cedure for estimating the cost  of a tunnel  diffuser is the
same as  for a conduit diffuser  except installation costs
are for  the nozzles only (603.2).

Data for the individual  accounts are presented in the
following paragraphs.
Steel nozzles, Account  601

Key parameters are the  construction material and the nozzle
diameter.  Cost data are provided for shop fabrication of
steel nozzles from 1.27 cm steel plate.  Precast concrete
pipe prices include an  allowance for pipe sections with the
nozzles attached as part of the manufacturing process.
Therefore, separate costs for concrete nozzles are not
given.  The costs for cutting the hole for the nozzles, or
for slots, into the steel pipe and welding nozzles to the pipe
can be neglected.  The  costs for steel nozzles are used for
the tunnel manifold application.
Manifolds, Accounts 602.1 to 602.3

If the manifold is a conduit, the pipe and fitting costs
given in Cost Category 4 can be used.  One example of
                             141

-------
 fitting costs is for reducers which are considered because
 the conduit diameter may decrease as the distance from the
 end of the conduit increases.  Decreasing the manifold
 diameter  is done to maintain uniform discharge and to pre-
 vent  siltation in the outer ends of the manifold.  If the
 manifold  is a tunnel-type, use the cost data given in
 Category  5.
 Installation of conduit
 diffuser, Account  603.1
 The  slots will be cut or the nozzles attached to the con-
 duit on  land.  Costs for installing this type of manifold
 can  be assumed to be equal to conduit installation costs.
 Refer to Cost Category 4 for information.  If the diffuser
 is at an angle to the conduit, costs for a concrete
 anchor block at the junction should be included in the
 estimate (see Cost Category 7).  A vertical shaft from a
 tunnel can be raised to the lake bed and a conduit manifold
 installed.  This method may require a cofferdam  (see
 Category 2) during excavation and connecting the manifold
 to the tunnel shaft.  Connection of a conduit manifold to
 the  end  of the pipe can be done underwater as part of the
 laying operation.
Installation of nozzles into a
tunnel diffuser, Account 603.2

Key parameters are the method of installation, the  number
of nozzles, and the depth of rock penetrated by the nozzle
riser.  Two methods that are used to install nozzles into
a tunnel are to:
                            142

-------
     1.   first mine  the  tunnel manifold, then drill the
          hole and grout  in  the nozzle (placing the nozzle
          after the tunnel is mined  requires tunnel de-
          watering, capping  the hole from the inside,
          drilling the  nozzle hole,  and grouting the nozzle
          into place);  or
     2.   drill holes into the rock  bottom and grout the
          nozzle  into the desired  location prior to mining
          the tunnel  (The nozzle, is capped to prevent
          water from  entering when the tunnel excavation
          reaches the nozzle).
Costs  for using a large drill mounted on a barge to drill
the nozzle holes  prior  to mining the tunnel, method No. 2
above, are given  in this  account.  Grouting costs can be
neglected  because the  hole  is only  drilled 3 to 5 cm
larger than  the nozzle  riser diameter.
Cofferdams, Account  603.3

A cofferdam may be used when  connecting a conduit manifold
to the end of  the tunnel.  Other applications of cofferdams
can be included in this account.  See Cost Category 2 for
the discussion on cofferdams.
Trench excavation, Account  603.4

A discussion of offshore  trench excavation is given in
Cost Category  9.
Diffuser support systems,
Account 603.5
A discussion of piles and concrete is included in Cost
Categories 2 and 7, respectively.
                             143

-------
Riprap protection, Account 603.6

To prevent bed scour caused by the jets, riprap is placed
in the area around the diffuser.  Information required to
estimate the cost for material and placement of the riprap
is given in Category 2.
Trench backfill, Account 603.7

The data required to estimate the costs for backfilling
the pipe trench are included in Cost Category 8.
 Single Port, Account 604

 The single port outfall usually includes a concrete struc-
 ture.  The costs for concrete are included in Cost Category
 7.
Mobilization/ Account 606

The costs for mobilization and demobilization are not in-
cluded in the unit prices.  If the diffuser is a tunnel
manifold, the cost for towing the drill to the site is
given as the mobilization cost.  The costs for mobilizing
the drill are not included.  If the diffuser is a conduit
manifold, the mobilization costs given in Category 4 are
sufficient.  A discussion of mobilization is given in Cost
Category 10.
                            144

-------
Table 78 presents the correlation between cost account
number, worksheet, and figure number.  Costs are calcu-
lated using the procedure outlined in the introductory re-
marks to this section and the worksheets in Tables 79
through 93.
             Table 78.  DIFFUSER COST ACCOUNTS
 Cost
 Account
 Number
Description
Figure
Number
Worksheet
Number
 601
 602
 602.1
 602.2
Costs are provided for
  fabrication of steel
  nozzles.

Manifolds  (material and
  fabrication as appropri-
  ate)

Costs for steel manifolds
  (see Cost Account 403)

Costs for concrete mani-
  folds (see Cost Accounts
  401 and 402)
 601
 601
         602.1
         602.2
                            145

-------
Table 78 (continued).  DIFFUSER COST ACCOUNTS
Cost
Account
Number
602.3







603
603.1

603.2


603.3

603.4

603.5

603.6

603.7

604
605
606
Description
Costs for fittings, such as
tees and reducers, for
steel pipe manifolds are
provided in Cost Account
403.2. For concrete mani-
folds, fitting costs are
included in straight pipe
costs.
Installation costs
Conduit manifold (see Cost
Category 4)
Costs for installing indi-
vidual nozzles into a
tunnel
Costs for cofferdams
(see Cost Category 2)
Excavation costs (Cost
Category 9)
Costs for support systems
(see Cost Category 2 & 7 )
Costs for riprap protec-
tion (see Cost Category 2)
Costs for backfill (see
Cost Category 9)
Single Port
Other
Mobilization
Figure
Number
••«.








— —

603.2


WH

__

—.—

__

___

—
—
—
Worksheet
Number
602.3








603.1

603.2


603.3

603.4

603.5

603.6

603.7

604
605
606
                      146

-------
Table  79.  COST CATEGORY 6
      COST SUMMATION
Worksheet 600
Cost
Account
Number
601
602
602.1
602.2
602.3
603
603.1
603.2
603.3
603.4
603.5
603.6
603.7
604
605
Description
Nozzles
Manifolds
Concrete manifold
Steel manifold
Steel fittings
Installation
<
Conduit manifold
Nozzles
Cofferdams
Excavation
D iff user Support
Scour protection
<
, Backfill
Single Port
r
1 Other
Cost Category 6, Total Cost
(Enter cost in Acct. 1101)
606
Mobilization (Enter
Cost in Acct. 1001)
Base
Cost
BC -$
BC60° 1 =^
B^6Q° ° =^
B<"'602 ^ ~$
BC603 1 =$
BCC03 " =$
OUJ.&
BC603 3 =$
BC603 4 =$
BCC03 - =$
BC,03 c =$
D V) O • D
BCeo3 . =$
BC601 =$
BC6Q5 =$

BC£ =$
D ,;,,';, ; ;;, , ," _ ' ",, ,;;

MC =$


            147

-------
                 Table  80.  STEEL NOZZLES

                      Worksheet 601


Design Data Required

Nozzle inside diameter                     	m

Riser length3
                                           	m

Number of nozzles                       N =
Base Cost

Enter Figure 601, read base unit
  cost per nozzle                     BUG =$
Base cost = N x BUG                    BC =$
Cost Adjustments

Enter Figure 601, read design adjust-
  ment factor for the riser length(f)  F.
Adjusted Base Cost

Adjusted cost = BC x FD             BC60l "1.
  The  riser length "f"  is  the distance from the (horizontal)
  nozzle centerline to  the top of the manifold minus 1.5
  times  the nozzle diameter.
                           148

-------
             Table  81.  CONCRETE MANIFOLD


                     Worksheet 602.1
Base Cost
Select Cost Account 401 for precast
  concrete pipe or Cost Account 402
  for cast-in-place conduit, whichever
  is appropriate.

Base cost = BC401 or BC4Q2        BC602.1
               Table 82.   STEEL MANIFOLD

                     Worksheet 602.2


Base Cost

Refer to Cost Account 403' Steel
  Conduit.  Base cost = BC4Q3     BC602 2  =—
           Table  83.  STEEL MANIFOLD FITTINGS

                     Worksheet 602.3
Base Cost

Refer to Cost Account 403.2

Base cost = BC4Q3>2               BC602.3
                           149

-------
               Table 84.   INSTALLATION OF
               	CONDUIT DIFFUSER	

                     Worksheet 603.1


 Base Cost

 Select  cost account  406.2  for dry in-
   stallation within  an offshore coffer-
   dam or 407.2  for underwater installation

 Base cost = BC406<2  or BC407>2    BC      =$
          Table  85.  INSTALLATION OF NOZZLES
          	INTO A TUNNEL  DIFFUSER	

                     Worksheet 603.2
Design Data Required

Number of nozzles                       N =
 Length of the riser                     L =    	m
Base Cost

Enter Figure  603.2, read base
  cost

Base cost =                        BC^__ _=$
                                     oil J. z —
                  Table  86.  COFFERDAMS

                     Worksheet 603.3


Base Cost

Refer to Cost Account 202.2

Base cost = BC2Q2>2               BC603.2
                           150

-------
              Table 87.   TRENCH EXCAVATION

                     Worksheet 603.4
Base Cost
Refer to Cost Category 9 and select
  the cost from either Cost
  Account 901 or 902

Base cost = BC9Q1 or BC9Q2        ^603.4
           Table 88,  DIFFUSER SUPPORT SYSTEMS
                     Worksheet 603.5
Base Cost

Refer to Cost Category 7

Base cost = the base cost from the
  appropriate account in Cost
  Category 7                      BC603.5
              Table 89.  RIPRAP PROTECTION

                    Worksheet 603.6
Base Cost
Refer to Cost Account 201.2

Base cost = BC2oi.2                BC603.6 =—
                           151

-------
               Table 90.   TRENCH BACKFILL

                    Worksheet 603.7
Base Cost

Base cost = base cost from the
  appropriate accounts in Cost
  Category 8.                      BC603 7 =—
                 Table 91.   SINGLE PORT
                      Worksheet 604
Base Cost

Refer to Cost Category 7 for
  estimating procedure               B<~604 ~:L
                    Table  92.  OTHER

                      Worksheet 605

Base Cost

Include costs not covered in this
  category but that relate to the
  diffuser.  Data presented in
  other accounts may be useful in
  estimating "Other" costs.         BC,.... =$
                                      bUD  —
                           152

-------
                 Table 93.  MOBILIZATION

                      Worksheet 606
Mobilization Cost

Mobilization = $30,000 if the diffuser
  is a tunnel diffuser.  If the total
  length of offshore pipe is the
  manifold for a conduit diffuser,
  add $96f000.   (Caution:  do not
  duplicate costs in Account 408.)     MCg -$_
                            153

-------
      N
      N
      o
      •w-
      EH
      Ul

      8
I-1
Ol
                                                                             Adjustment Factors Fn
                                                                             Nozzle Diameters  (m)
           .2       ,4       .6      .8      1.0     1.2


                     NOZZLE DIAMETER, meters
Dimension
(m)
1.0
2.0
5.0
10.0
20.0
30.0
f
.458
1.00
1.32
2.34
3.98
7.30
10.62

.61
0.90
1.10
1.80
3.02
5.41
7.80

.915
0.84
1.00
1.50
2.33
4.00
5.67

1.065
0.84
1.00
1.45
2.22
3.75
5.27
               Fig. 601 - Costs  for  Steel Nozzles

-------
tn
01
n)
   V I
   €
O
w

ffl
                           10             10

                        NUMBER OF NOZZLES
Curve

  A

  B

  C
                                                                                 Riser Lengths, f

                                                                                 0 to 6 meters

                                                                                 6 to 15 meters

                                                                                 Greater than 15
           Fig. 603,2 - Installing Individual Nozzles
                        Into a Tunnel Manifold

-------
COST CATEGORY  7, CONCRETE

Information on material and placement costs for concrete are
given  in this  category.  Data for each of the accounts are
given  in the following paragraphs.
 Structural concrete, Accounts
 701.1  and 701.2
 The  key parameters are concrete material and placement costs,
 reinforcing quantity, the area of formwork, and finishing
 costs.  The data presented in References 2 and 4 suggest
 grouping  structural members with similar values for the
 key  parameters.  For example, concrete costs for a wall or
 suspended slab will be more expensive than a pipe cradle or
 encasing  a pipe in concrete without formwork.  Therefore,
 three general groups of structural  members were selected.
 The  groups are:
     1.    suspended slabs, beams and walls;
     2.    spread footings, grade slabs, and pile caps; and
     3.    concrete structures with no reinforcing steel
           and little or no formwork requirements.
 The  deck  and walls for a pump station or other box type
 structure  would fit into Group 1.  Channel lining or the
 floor of the pump station and the pile caps used for a
 structure  foundation would fit into Group  2.  Concrete cradles
 cast on site are an example of Group 3.

Material costs for concrete can vary according to special
admixture  requirements and strength.  Costs given are for
medium strength (3000 psi) concrete without special admix-
tures.   The cost differential between low  strength  (2,500 psi)
                             156

-------
and high  strength  (5,000  psi)  concrete is  $7/cubic  meter.
It was not  considered in  presentation of the  costs.

Concrete  for  the type of  structures  considered here can be
placed with a crane  and concrete  bucket.   The crane can also
be used in  formwork  and placing the  steel.

Reinforcing is separated  in  the accounting because this is
common practice for  presenting estimates.  The costs for
rebar reinforcing  are given.   A rule of thumb for mesh re-
inforcing is:   It  costs about  twice  as  much as rebar rein-
forcing installed.
Concrete (marine), Account 702

The key parameters are the thickness of the structure and
waste.  Tremie concrete may be used for pipe support, par-
tial encasement of a pipe to give the conduit added weight,
or thrust blocks for nozzles and the manifold.  The concrete
is transported to the offshore site and placed using a flex-
ible hose extending down to within the formwork for the
structure being placed.  Because the concrete is being placed
underwater, the top layer of the structure will be destroyed
by the mixing of concrete and water.  Therefore, an allowance
for waste should be included in the quantity measured from
the neat lines on a drawing.  A waste allowance of 20 percent
is appropriate.  The unit cost was developed using the costs
for:
     1.   a flat-top barge and a tug boat to tow concrete
          trucks to the site?
     2.   two cranes mounted on barges, one to swing a hop-
          per between the concrete trucks and the flexible
          hose and the other to support the flexible hose; and
                            157

-------
      3.    costs for labor and a  diver are  also included.
 Grouting,  Account 703

 The key parameter is the rock  conditions.   Data  are  for
 foundation grouting or forming a  grout  curtain to  cut off
 a water bearing strata.   Grouting quantities  can be  mea-
 sured in terms  of the  take.

 The term "take" is defined as  the ratio of  the volume of
 material that is pumped  into a hole(s)  to the drilled hole
 volume.  The unit costs  for grout will  vary inversely to
 the take.   Costs given are for a  badly  fractured rock.  The
 take is assumed to be  double the  hole volume  for a 1.22 cm
 diameter hole.   Estimating take is difficult  even  with de-
 tailed site data.   In  many cases, grouting  is bid  in terms
 of cost per bag of cement and  quantity  of sand.  Although
 the data given  will provide some  measure of the  cost,  the
 user should recognize  the limitations.  Costs for  chemical
 additives are not included.
Cushion  fill/ Account  704

The gravel base placed beneath a grade slab  is  similar  to
the gravel filter used beneath riprap.  Data for  cushion fill
are obtained from Cost Account 201.1  (Filter material).
Mobilization/ Account 706

Unit prices do not include mobilization and demobilization
costs.  Costs for mobilizing equipment should be  added only
                            158

-------
if a large concrete structure, other than the pump station,
is included in the modification.  Otherwise, mobilization
costs given in Category 3 will suffice.  A discussion of mo-
bilization is given in Cost Category 10.

Table 94 presents the correlation between cost account number,
worksheet, and figure number.  Costs are calculated using the
procedure outline in the introductory remarks to this section
and the worksheets in Tables  95  through 102.
           Table  94.  CONCRETE COST ACCOUNTS
Cost
Account
Number
701

701.1
701.2
702
703
704
705
706
Description
Cast-in-place structural con-
crete costs for material and
placement of concrete and
reinforcing steel
Concrete placement
Reinforcing steel
Cast-in-place concrete
(marine)
Costs for grouting
Cushion fill (see Cost
Account 201.1)
Other
Mobilization
Figure
Number


701.1
701.2
.;
	
--
	
	
Worksheet
Number


701.1
701.2
702
703
704
705
706
                            159

-------
              Table 95.  COST CATEGORY 7
                   COST SUMMATION	

                    Worksheet 700
Cost
Account
Number
701
701.1
701.2
702
703
704
705
Description
Structural concrete
Concrete placement a
Reinforcing steela
Concrete (marine) a
Grouting
Cushion fill
Other
Cost Category 7 Total Cost
(Enter cost in Account 1101)
706
Mobilization (Enter
cost in Acct. 1001)
Base
Cost
BC701.
BC701.
BC702
BC703
BC704
BC705
BC?
MC?
1 =$
, -$
=$
=$
=$
=$

=$


=$


aThe user is cautioned that most of the time the costs for
 these accounts are used in other categories.  Do not enter
 here if they are used in another category.
                            160

-------
                Table 96.  CAST-IN-PLACE
           STRUCTURAL CONCRETE, CONCRETE PLACEMENT

                   Worksheet 701.1


Design Data Required

                     3
Category of structure

Volume of concrete                                       m
Base Cost

Enter Figure 701.1, read, base cost    BC7Ql 1
 Base  Cost
Enter Figure  701.2  read  base  cost     BC701  2 =—
 1.   Suspended slabs, beams, walls.
 2.   Spread footings, grade slabs, and pile caps.
 3.   Structures with little or no reinforcing.
             Table  97.  CAST-IN-PLACE STRUCTURAL
                   CONCRETE,  REINFORCING STEEL

                   Worksheet 701.2

 Design Data  Required
                      a
 Category  of  structure              	

 Weight of reinforcing steel                   	kg
al.   Suspended  slabs, beams,  and walls.
 2.   Spread  footings, grade  slabs,  and pile caps.
 3.   Structures with little  or  no reinforcing.

blf weight of reinforcing steel  is not available,  assume
 values shown in the following tablet


                            161

-------
     Table  97  (continued).  CAST-IN-PLACE STRUCTURAL
                CONCRETE,  REINFORCING STEEL

                Worksheet 701.2
                             Weight  of  Reinforcing
          Category           to  assume/  kg/m3  of cone.

              1                      89
              2                      71
              3                   0-20
                Table  98.   CAST-IN-PLACE
                    CONCRETE (MARINE)

                      Worksheet  702
 Design Data  Required

 Volume of concrete                        V =          m
 Base  Cost

 Base  cost  =  V x  $86.30/m              BC702 ~—
 aUnless  detailed data  is  available, add  20 percent  to
 design  volume of concrete  for waste during underwater
 placement.
                 Table  99.   GROUTING

                     Worksheet  703


Design Data Required

Volume of drilled holes                   V =	m3


Base Cost

Base cost = 2V x $231.90/m             BC703 =^	
                             162

-------
               Table  100.  CUSHION FILL

                    Worksheet 704
Base Cost
Refer to Cost Account 201.1 for
  cost estimating procedure           BC
                                        7ru
                   Table 101.  OTHER

                     Worksheet 705


Base Cost

Include costs not covered in this
  category but that relate to
  concrete.  Data presented in
  other accounts may be useful in
  estimating "Other" costs.           BC705 =—
               Table 102.  MOBILIZATION

                     Worksheet 706


Mobilization Cost

For a large structure other than
  the pump station, add $3,300        MC?   =$_
                             163

-------
                                              10
                                           to
                                           M
                                           id
                                           8
                                           u
                                           w
                           10'
10
   10
10"
  VOLUME CONCRETE, cubic meters
           WEIGHT OP REINFORCING,  kilograms
Fig. 701.1 -  Costs  for Structural

 Concrete, Concrete Placement
      Fig. 701.2 - Costs for Structural

        Concrete, Reinforcing Steel

-------
COST CATEGORY 8, FILL

Data on the costs of material and placement of fill are
Given in this category.

Data for the accounts of Cost Category 8 are given in the
following paragraphs.
Material and hauling
costs, Account 801
The key parameters are the cost of the material and the
haul distance.  A discussion of hauling costs is given in
Cost Category 1.  The types of fill considered in this
account are unclassified earth, sand, gravel (either bank
run or graded) and topsoil.  Costs for stone fill such as
riprap are included in Cost Category 2.  Costs for operating
the borrow are included in the material costs.
Placement of fill (land),
Account 802.1
Key parameters are the working area, methods of compaction,
and extent of compaction.  Placement of material can be
classified into three groups.  The groups are as follows:
     Group 1 - The costs for a grader to spread fill that
     has been dumped from a truck are given.  Compaction
     costs are not included.  Spreading topsoil or filling
     swales are examples of activities included in this
     group.
     Group 2 - Placement and compaction of fill around
     structures.   Costs for placement of the material with
     a loader and using hand tampers to compact the fill
     are given.   Placing fill around conduits and the pump
     stations are examples of this group.
                             165

-------
      Group 3 - Placement  and compaction  of  fill  in  an  open
      area.  Costs  were  developed  assuming that a vibrating
      roller is used  for compacting  granular material and  a
      sheepsfoot roller  for  compacting  earth material.  When
      the area immediately around  the pipe has been  compacted
      by hand,  any  additional compaction  requirements can  be
      met using machine  compaction.
 Placement of fill  (marine),
 Account 802.2
 The key parameter  is  the  type  of placement.  Backfill of  the
 pipe trench or placing  cushion fill  in the pipe  trench  can
 be done by loading the  material into scows, towing the  scows
 offshore and releasing  the material  into the trench  from  the
 scow.   If the fill is to  be  used in  a cell cofferdam, costs
 for off-loading the material using a crane mounted on a barge
 are given.   Costs  for backfill using material that was  side
 cast are included.
 Mobilization, Account  804

 Unit prices do not  include mobilization and demobilization
 costs.  Mobilization costs for the equipment used to backfill
 the pipe trench and pump station are given in Cost  Category  4
 and Category 3, respectively.  Therefore, mobilization  costs
 for dumping and spreading fill will generally be the only
 costs added from this  account.  A discussion of mobilization
 is given in Category 10.

Table 103 presents  the correlation between cost account num-
ber, worksheet, and figure number.  Costs are calculated
using the procedure outline in the introductory remarks to
this section and the worksheets in Tables 104 through 109.
                            166

-------
              Table 103.  FILL COST ACCOUNTS
Cost
Account
Number
801
802
802.1
802.2
803
804
Description
Material and
Placement of
hauling costs
fill
Cost placement and com-
paction of fill on land
Placement of
(marine)
Other
Mobilization
fill offshore


Figure
Number
801

802.1
802.2
—
—
Worksheet
Number
801

802.1
802.2
803
804
                Table  104.  COST CATEGORY 8
                	COST SUMMATION	

                      Worksheet 800
Cost
Account
Number
Description
        Base
        Cost
801
802
802.1
Material and hauling
  costs3

Placement of fill


Placement of fill
  (land)
BC
                                      801
BC
BC
aThe user is cautioned that most of the time the costs
 for these accounts are used in other categories.  Do
 not enter here if they are used in another category.
                            167

-------
          Table 104 (continued).   COST CATEGORY 8
                      COST SUMMATION
Worksheet
Cost
Account
Number Description
802.2 Placement of fill
(marine)
803 Other
Cost Category 8 Total Cost
(Enter cost in Acct. 1101)
804 Mobilization (Enter
cost in Acct. 1001)
800
Base
Cost
BCono ~=$ 	 	
®^nm ~$

BCR =$

MCQ =$

           Table 105.  MATERIAL AND HAULING COSTS

                       Worksheet 801
Design Data Required

Type of fill material

Haul distance  (round t;rip)a
  from the borrow site
Volume of fill                           V =               m3
 If haul distance is not known, assume an 18-km haul.
                            168

-------
   Table 105  (continued).  MATERIAL AND HAULING COSTS

                    Worksheet 801




Base Cost

Enter figure 108.2, read base        BUG = $	/m3
  unit cost for hauling.

Base cost for hauling = BUG x V      BC1 = $	


Enter Figure 801, read base cost     BC~ = $
 Cost Adjustment

 Enter Figure 801,  read adjustment    F   =
   factor for material
 Adjusted Base Cost

 Adjusted base cost = (BC0  x F_ )    BConi  =  $
                        2     D        801
           Table  106.   PLACEMENT  OF FILL  (LAND)

                     Worksheet  802.1
 Design  Data  Required

 Nature  of  the placement  operation
  group number                  	

 Volume  of  fill                            v * 	m
aGroup 1 - Dump and spread  fill
 Group 2 - Hand compaction  of  fill
 Group 3 - Machine compaction
                             169

-------
    Table 106  (continued).  PLACEMENT OF FILL  (LAND)



                    Worksheet 802.1
Base Cost
Enter Figure 802.1, read base cost   BCono ,=$
                                       o\]ji • J-
          Table 107.  PLACEMENT OF FILL  (MARINE)



                    Worksheet 802.2
Design Data Required



Nature of the placement operation3
Volume of fill                            V =             m3
Base Cost



Enter Figure 802.2, read base cost BC0._ 0=$
                                        I ,2
 Backfill of a pipe trench; placing fill into a cofferdam

 or backfill using excavated material side cast along the

 trench.
                           170

-------
                     Table  108.  OTHER

                       Worksheet 803
Base Cost
Include costs nbt covered in this
  category but that related to
  Fill.  Data presented in
  other accounts may be useful in
  estimating "Other" costs.           BC0ft0=$
                                        803
                 Table 1Q9.  MOBILIZATION

                       Worksheet 804
 Data Requirements

 802.1       Mobilization costs for Group        Summation
             1 of the land placement of
             fill is $1,700
aThe costs for Group 2 is $900
 The costs for Group 3 is $800
 Mobilization Cost

 Mobilization = the total of the summation
   column.  Usually only Group 1 of account
   802.1 will be considered (see the
   discussion for this account).         MCg =$_
 aUse the costs for group 2 and 3 only if there is a large
  structure other than the pumping station that requires
  backfill.
                            171

-------
   (0
   i-l
   O
   •a
   b •
   §
   w
   I
to
        10"
10'
        ID"
—
—--..-



















/

- -


















/
s
—
rr.

















/
/

-_
""-
















/
/




















/



i
















^




Tl
t
--i









j



/
/





\- -1
4-----1

^r ~
i
~i







I/
/







'• •
—










/
'








--

__._








/
/









...
J
-







^
^










j
-
-
-







/











— i
-







/












-
_j
--






/













L
— f—
1




x1




i









4: 	
t—



/
'





j









	 i
_._.
	
	

/
S
















-J
—
—

/
/"

















_
II
/
r


















                       Fill Material

                       Unclassified Earth
                       Bank Run Gravel
                         or Sand
                       Graded Gravel or
                         Sand
                       Topsoil & Loam
Adjustment Factor/ Fp

        1.00
        3.63

        4.33

        4.70
          10"
                  10
10'
                   FILL VOLUME,  cubic  meters
               Fig. 801 - Cost for  Fill  Material

-------
        10
    0)     c

    %   10
    U
    w
    9
    ffl
(A)
        10
        10'
          10'
10'
10"
                                  10
                    VOLUME, cubic meters
                                                VOLUME,  cubic meters
           Fig.  802.1 -  Cost for Placement of Fill (Land)
                                            Fig.  802.2 - Cost for Placement of
                                                         Fill (Marine)

-------
COST CATEGORY 9, EXCAVATION


Data are given for land and marine open cut excavation.  Tun-

nel excavation is not included in this category.


Data for each account are given in the following paragraphs.
Earth excavation (land),
Account 901.1
Key parameters considered are volume of excavation and the

physical size of the excavation.


The volume of excavation and the  physical size of the trench

or foundation will affect the choice of equipment.  For the
relatively small excavation volumes encountered in this type
of construction, the size of the  excavation has the greater
influence on equipment costs.


Land-based earth excavation, therefore, is grouped according

to size of the excavation.  The volume of excavation is im-
plied in the choice of equipment.  The groups are:

     1.   Structures and trench excavation for small buildings,
          for additions to existing buildings and for smaller
          pipes - Production rates are low, yet the labor and
          equipment costs are relatively high.  Unit costs
          were developed for using a hydraulic backhoe to
          excavate the material.

     2.   Structure excavation for larger structures such as
          a pumping station - The sizeof the equipment used
          and the associated costs do increase.  However, the
          production rates improve.  Unit costs include the
          cost for a crane rigged with a clam or dragline.

     3.   When pipe diameters approach the size that require
          a trench width equal to that of  a  scraper,  less  costly
          excavation methods can  be used - The costs for
          using a scraper to excavate the material was used
          in unit cost development.
                             174

-------
Water problems and the necessity  for  shoring add to the cost
of excavation, see Accounts 903 and 904 and may reduce pro-
ductivity.  The cost data given in this account were developed
assuming the area enclosed in shoring can be dewatered and is
large enough not to hamper production significantly.
Earth excavation  (marine),
Account 901.2
Key parameters are the volume of excavation, type of material,
the method of disposal, and production rates.  It is assumed
the equipment production time will be 16 days per month, and
the work periods will be 24 hours per day for a six-day week.
The production for days spent actually excavating material
will vary according to weather delays, maintenance require-
ments, and the distance to a protected harbor.  The working
season affects annual production time.  In the northern
climate, the work season is 7 to 8 months compared to 12
months in the south.  All these variables affect the costs
making an "average" unit cost difficult to assess.

The information presented for this type of excavation is
related to the consistency of the material and method of
disposal.  Materials are classifed into three groups and a
type of excavation equipment assumed for each.  The groups
and equipment are:
     1.   A hard material (a till or weathered rock) - It was
          assumed excavation is done with a barge-mounted
          backhoe (dipper dredge) with spuds that secure it
          to the bottom for leverage.
     2.   A firm cohesive material - Excavation of this type
          of material will be done using a barge-mounted
          clamshell dredge.   (Sand is an example of firm
          material).
     3.   Soft material (unconsolidated silt) - Excavation
          of this material will also be done with a clamshell
          dredge.  Production rates will improve over  (2) above.
                             175

-------
The minimum bottom width that can be dug with the dipper
dredge  is  7 to 8 meters.  The clam can excavate a 3-meter
wide  trench.  When this equipment works in shallow water the
trench  will be excavated to 30 meters wide.

Offshore excavation relates exclusively to digging the pipe
trench.  The materials excavated from the trench can be side
cast  along the trench or disposed of on shore in designated
areas.  On-shore disposal requires the addition of scows
and tug boats to the equipment pool for transporting the
spoil to shore.  The haul distance offshore then becomes a
factor.  It is assumed the distance to the shore offloading
point is within a kilometer of the excavation area.  Costs
for maintenance of the disposal area are left to the user.
Data presented in this manual will be useful.
Rock excavation  (land),
Account 902.1
Key parameters are the dimensions of the trench and disposal
of the material.  A narrow deep trench will require more
control holes per unit volume of rock, and cleanup costs are
more because of the equipment size limits.  Differences in
unit prices for a narrow and wide trench are reflected in
the productivity assumed.  An arbitrary division between a
narrow and wide trench is 5 meters.  The trench in many
cases will be over-excavated to allow .8 meters of sand for
pipe bedding.  The user should include an allowance for this
in the estimate.  Costs for a rock drill and a crane with
clam to remove the rock from the trench are used in developing
unit costs for this account.
                             176

-------
Powder costs are included  as  a  lump  sum of  $3/cubic  meter.
Rock excavation  (marine),
Account 902.2
Key parameters are the volume,  the  disposal of  the materials,
and production rates.  A production time of 16  days per month
and a work period of  6 days per week is assumed.  For some of
the work, a period of 24 hours  per  day is  assumed.  The same
limitations on production  exist for this account as for account
901.2.

The methodology assumed for excavation of  rock  offshore is
to:
     1.   blast the rock;
     2.   load the blasted material with a dipper dredge into
          a scow;
     3.   tow the material to shore;  and
     4.   transfer material from  the scows to trucks or to
          a stockpile for  disposal.
Powder costs are added as  a lump  sura of $3/per  cubic meter.
The trench is often over-excavated  to minimize  clean-up
work and to allow for placing a sand bedding for the pipe.
Assume over-excavation to  be 1  meter.
Shoring, Account 903

A discussion of sheet piling used for excavation shoring is
given in Cost Category 2.
                              177

-------
Excavation Dewatering,
Account 904
Key parameters are the initial and the sustained dewatering
requirements.  The procedure used here is to:
     1.   assume an inflow rate;
     2.   develop the costs for pumping on a per week basis;
     3.   equate the excavation time and the pumping time;
     4.   divide the production rate into the total volume
          of excavation; the quotient is the pumping time
          (production rates used are the same as those used
          in developing the unit costs) •
Therefore, given the inflow, the volume of excavation and
the group number, (see Account 901.1) sustained dewatering
costs can be estimated.  Initial dewatering costs are not
given.
Mobilization, Account 905

Unit prices do not include the cost for mobilizing and de-
mobilizing equipment.  Mobilization costs were added for
marine and land installation in Category 4.  A discussion of
mobilization costs is given in Cost Category 10.

Table 110 presents the correlation between cost account num-
ber, worksheet, and figure number.  Costs are calculated
using the procedure outline in the introductory remarks to
this section and the worksheets in Tables 111 through 119.
                             178

-------
          Table 110.  EXCAVATION COST ACCOUNTS
Cost
Account
Number
Description
Figure  Worksheet
Number  Number
901

901.1
901.2
902

902.1



902.2
903
904



905

906
Earth excavation

Earth excavation  (land):
  Costs for earth excava-
  tion of channels, founda-
  tions, and pipe trenches

Earth excavation  (marine):
  Costs for excavation of a
  pipe trench for three
  general types of material
  and for alternative
  disposal methods

Rock excavation

Rock excavation (land):
  Costs for onshore rock
  excavation

Rock excavation (marine):
  Costs for excavation of
  pipe trench offshore in
  rock material

Shoring:  Shoring costs  for
  foundation and trench ex-
  cavation using steel sheet
  piling  (see Category 2)

Dewatering:  The cost of de-
  watering for foundation
  and trench excavation

Other

Mobilization
901.1
901.2
904
901.1
901.2
        902.1
        902.2
        903
904



905

906
                             179

-------
             Table 111.  COST CATEGORY 9
                   COST SUMMATION	

                    Worksheet 900
Cost
Account
Number
901
901.1
901.2
902
902.1
902.2
903
904
905
Description
Earth excavation
3.
Earth excavation (land)
Earth excavation
(marine)3
Rock excavation
Rock excavation (land)a
Rock excavation
(marine) a
3
Shoring for excavation
Dewatering during
excavation3
Other
Cost Category 9 Total Cost
(Enter cost in Account 1101)
906 Mobilization (Enter
cost in Acct. 1001)
Base
Cost
B^om i ~$
BCqni 0 =$
B^rtA-i 1 =$
BCono „ =$
BCD03 =$
BCD01 =$
BCD05 =$

BC0 =$


MCq =$


The user is cautioned that most of the time the costs
for these accounts are used in other categories.  Do
not enter here if they are used in another category.
                            180

-------
           Table  112.  EARTH EXCAVATION  (LAND)

                      Worksheet 901.1
Design Data Required

Type of excavation3

Volume of excavation                    V =          m

Haul distance  (round trip) from   .
  excavation site to disposal site         	   km
Base Cost

Enter Figure 901.1, read base cost
  for excavation                   BC(1)  =$
Enter Figure 108.2, read base unit
  cost for hauling                 BUG(2) =$
Base cost for hauling = V x
  BUG(2)                           BC(2)  =$
Total base cost = BC(1) + BC(2)    BC9Q1
al.  Trench or small foundation
 2.  Large foundation
 3.  Channel or large trench

 If haul distance is not given and hauling is known to
 be a factor assume 8-km round trip.
                           181

-------
          Table  113. EARTH EXCAVATION  (MARINE)

                      Worksheet 901.2


Design Data Required

Type of excavation  (soft, firm, hard)3     	
                                                     •5
Volume of excavation                    V =	___m

Disposal method                  	
                          c
Haul distance  (round trip)                 	km
Base Cost

Enter Figure 901.2, read base cost
  for excavation                     BC(1)=$
Enter Figure 108.2, read base
  unit cost for haul                BUG(2)=$
Base cost for hauling = V x
  BUC(2)                             BC(2)=$
Cost Adjustment

Enter Figure 901.2, read design adjust-
  ment factor for disposal method       F_=
                                         JLJ -
Adjusted Base Cost

Adjusted cost =  ((BC(1) x Fn) +
  BC(2))                   U       BC901.2=L
 Soft - Sand or unconsolidated silt.
 Firm - Clay or other cohesive material.
 Hard - Till or soft, weathered rock.

 Side cast or hauled to shore

 From the shoreline to a land disposal area.  If this  haul
 distance is unknown, assume an 8-km round trip.

                           182

-------
            Table 114.  ROCK EXCAVATION  (LAND)

                       Worksheet 902.1


Design Data Required

Volume of excavation                     V =
Haul distance (round trip) from ex-
  cavation site to disposal sitea            _ km
Bottom width of the trench
                                            m
Base Cost

Enter Fig. 902.1, read base
  cost for excavation                BC(1) =$

Enter Figure 108.2, read base
  unit cost for hauling              BUG(2)=$

Base cost for hauling =
  V x BUG (2)                         BC(2) =$_

Total base cost = BC(1) + BC(2)     BCgo2 1=^-
alf haul distance is not given and hauling is known to
 be a factor, assume 8-km round trip.
                            183

-------
            Table  115.  ROCK EXCAVATION  (MARINE)

                      Worksheet  902.2
Design Data Required

Volume at excavation                 V = 	m

Haul distance  (round-trip)3
  from shoreline to disposal
  area                                                    km
Base Cost

Base cost for offshore rock
  excavation = $55.40/m3 x V     BC(1) = $_

Enter Figure 108.2, read base
  unit cost for rock haul and
  disposal                      BUG(2) = $

Base cost for haul and
  disposal of waste rock
  V x BUG (2)                     BC(2) = $_

Total base cost = BC(1) +
  BC(2)                         BC      = S
 If haul distance is not given and hauling  is known
 to be a factor assume 8-km round-trip.
                            184

-------
                    Table 116.  SHORING

                       Worksheet 903
Base Cost
Reder to Cost Category 2 for cost
  estimating Procedures.  Base cost =
  Z (appropriate base costs from
  Account 202).                      BC903
             Table 117.  EXCAVATION DEWATERING
                       Worksheet 904
Design Data Required

Volume of excavation                       V = _ m

Type of excavation group                       _
Base Cost

Enter Figure 904, read base cost       BC904
aGroup 1 - Trench or small foundation
 Group 2 - Large foundation
 Group 3 - Channel or large trench
                           185

-------
                    Table 118.  OTHER

                      Worksheet 905
Base Cost
Include costs not covered in this
  category but that relate to
  excavation.  Data presented in
  other accounts may be useful in
  estimating "Other" costs.            BC
                                         905
                Table 119.   MOBILIZATION

                      Worksheet 906
Data Requirement

Cost Account           Mobilization
Number                 Costs                  Summation
            No.)
          1             $1,000
          2             $3,300
          3             $1,500

902. la                  $4,000
Mobilization Cost

Mobilization = the total of the
  summation column (above)              MCg = $_
aThese costs are included only if there is excavation other
 than for a pump station or a pipe trench.
                            186

-------
CD
        10'
     (0
     o
     •o
     I
        10"
                  o*
                   o y

                                         o£
                                                        co
                                                        ^4
                                                        id
                               o
                               T3
                                                            io
          10
10"
10
                  VOLUME OF EXCAVATION, cubic meters
              Fig. 901.1 - Costs  for  Earth  Excavation
                            (Land)
                                              VOLUME OF EXCAVATION, cubic meters
                                                                    Description

                                                                  Hard Material
                                                                  Firm Material
                                                                  Soft Material
                                                                Adjustment Factor
                                                                for Onshore Disposal F

                                                                       -1.07
                                                                       1.09
                                                                       1.09
                                         Fig.  901.2 -Costs for Earth Excavation
                                                      (Marine)

-------
    co
    M
    cd
        10'
    w     >

    8   ^
00   CO

oo   <>
        10'
           10
   .&-
10"
10
                                                             10
                                                          o
                                                          •o
                                                          o
                                                          u

                                                          w
                                                            io
                                                              10
                                                          ••by
10"
                                                                  10'
                  VOLUME EXCAVATION, cvibic meters
                                         VOLUME EXCAVATION,   cubic meters
              Fig.  902.1 - Costs for Rock Excavation

                           (Land)
                                       Fig. 904 - Costs for Excavation Dewatering

-------
COST CATEGORY  10, MOBILIZATION

Information on the  costs  for mobilization and demobilization
of equipment used in  construction of the facilities  is  given.
The costs  for  field offices, mobilization of supervisory  peo-
ple, etc., is  included in overhead costs.   The key parameters
affecting  mobilization are the location of the site  relative
to equipment location and whether the contractor uses his
equipment  or rents  the equipment.   Obviously,  if the job  is
in the  immediate area of  the equipment,  the cost for mobili-
zation  will be minimal.   Also, the contractor  may choose  to
rent the equipment  from a local firm,  thus effectively  eli-
minating the cost for mobilization.   It is not possible to
predict the location  of equipment nor whether  or not the
contractor will rent  or use his own equipment.   Therefore,
it is assumed  the equipment will have to be towed (marine) or
shipped to the site.

Data for estimating mobilization costs are given for all  the
categories except tunnels.   Equipment for  tunneling  is
specialized, and there is very little published data available
to base an estimate for mobilization.  Therefore, mobilization
costs for  tunnels are given as a percentage of the total
costs for  that category.   Data from contracts  listed in the
Engineering News Record were used to develop a reasonable
percentage to  apply to tunneling costs for mobilization.
Analysis of 50 contracts  given by Engineering  News Record
revealed that  approximately 5 percent of the total construc-
tion cost  is included in  mobilization and  demobilization.

No trend with  regard  to total construction cost was  found.
For costs  ranging from 0  to 1 million,  1 million to  10  mil-
lion, and  10 million  to 100 million, the percentages for
mobilization and demobilization were 4.0,  4.9,  and 5.0, re-
spectively.
                            189

-------
The mobilization data are grouped into two accounts.  The
first account  included data for all categories except tun-
neling.  The second account relates to tunneling only.
Mobilization, Account 1001

Land Based -

The key parameters are equipment location, type, and weight.
Mobilization costs may include:
     1.   shipping costs expended in getting the equipment to
          the construction site  (rail freight plus the cost
          to off-load and truck the equipment to the site is
          on weight basis), and
     2.   the labor, supplies, and equipment required to pre-
          pare the equipment for operation (Equipment shipped
          by rail is partially disassembled.  Crane booms are
          taken off and the tracks are removed from a crawler
          tractor, for example.  In addition, most of the
          lubricants are removed).
Demobilization costs include preparation of the equipment for
shipping and hauling it to the railroad loading area.  The
data given for mobilization include trucking and equipment
preparation costs.  The mobilization costs given represent
the assumed upper limit of costs; beyond which the contrac-
tor would rent local equipment.

Marine -

The key parameters are the location of the equipment relative
                                                    i
to the job site and the number of pieces of equipment.

The equipment is towed to the site with tug boats.  To de-
velop the mobilization costs, the towing time required and
                             190

-------
the number of equipment items requiring towing must be con-
sidered.  The construction is grouped into categories based
on the type of conveyance to the offshore discharge.
     1.   Tunnel - If a tunnel is used, the offshore require-
          ments will be equipment for the activities of Cost
          Category 2 and Category 6.  The rental rate for one
          tug boat for two weeks is assumed.
     2.   Conduit - If a conduit is used, the offshore re-
          quirements increase.  The rental rate for three
          tug boats for two weeks is assumed; one for excava-
          tion, one for the lay barge, and one for backfill
          of the trench.
Mobilization for tunneling,
Account 1002
Mobilization for tunneling work includes electrical, ventila-
tion, and other equipment.  Insufficient published data was
located to prepare an estimate for mobilizing tunneling
equipment.  Therefore, based on the Engineering News Record
data, a markup of 5 percent is suggested.

Table 120 presents the correlation between cost accounts and
worksheets.  Costs are calculated using the introductory re-
marks to this section and the worksheets in Tables 121-123.


           Table 120.  MOBILIZATION COST ACCOUNTS
Cost
Account
Number
1001
1002
Description
Mobilization
Other
Figure
Number
—
—
Worksheet
Number
1001
1002
                             191

-------
               Table  121.  COST CATEGORY 10
               	COST SUMMATION	
                      Worksheet 1000
Cost
Account
Number
Description
                                           Base
                                           Cost
1001
1002
            Mobilization
            Other
                        BC1002 - i-
 Cost Category 10 Total Cost
   (Enter cost in Acct. 1101)
                                   BC
                                     10
                               = $
                 Table 122.   MOBILIZATION
                      Worksheet 1001
 Data Requirements
 Cost Category
 Number	
 1
 2
 3
 4
 5
 6
 7
 8
 9
                                       Mobilization
                                       Cost
                                           = $
                                       MC2  = $_
                                       MC3  = $_
                                       MC4  = $_
                                       MC5  = $_
                                       MC6  = $_
                                       MC?  = $_
                                       MCg  = $_
                                       MC9  = $_
Base Cost
Total
                           192

-------
                   Table 123.  OTHER
                     Worksheet 1002
Base Cost

Include costs not covered in this
  category but that relate to
  mobilization.  Data presented in
  other accounts may be useful in
  estimating "Other" costs.        BC1002 = —
                          193

-------
COST CATEGORY 11, CAPITAL
COST RESOLUTION
 The  information provided in this category gives the user the
 capability to:
      1.   adjust the unit price for regional and time varia-
          tions;
      2.   determine project costs; and
      3.   resolve the capital costs into annual costs.

 Most of the data that are used to develop project and annual
 costs are in the form of percentages applied to the construc-
 tion costs or added cost items such as land or leasing costs,
 The  values for some cost burdens cannot be included in the
 manual.  An approximate value is given for the factors or a
 source for the data is identified.  Whenever possible, local
 data sources should be used.  Data for the accounts of this
 category are given below.
Time and regional adjustment
factor, Account 1101	
The key parameters are cost escalation, regional price dif-
ferences and the initial price levels.  The prices are for
the New York City area in December 1974.  The regional ad-
justment factors were derived using the average of the ad-
justments given in References 2, 3, and 4.  Regional adjust-
ment factors are tabulated on the worksheet provided for  this
account.

Data provided in the Engineering News Record  (EMR) were cho-
sen to reflect price escalation because it is readily avail-
able, the indexes are revised weekly, and the data are consi-
dered  good  indicators of price trends in the construction
industry,   Two indexes are presented in the ENR that reflect
                              194

-------
the cost trends in construction wages and material:  the
Building Cost Index and the Construction Cost Index.  The
Building Cost Index is based on material costs and skilled
labor.  Common labor is substituted for skilled labor in the
Construction Cost Index.  The authors of Engineering News
Record suggest the Construction Cost Index should be used
when the costs for common labor are a large percentage of the
total cost.  That description for common labor hours
applies  to the type of work considered here.  Therefore,
the 20-cities average Construction Cost Index was adopted.
The December 1974 value of the ENR Construction Cost Index,
2097, is given in the worksheet for this account.  Use
Figure 1100 to project beyond December 1974.  Data are provi-
ded from 1969 to 1974, projection beyond December 1974 is
left to the user.
Total project costs,
Account 1102
The key parameters are the percentages and values selected
and the order in which they are applied.  Project costs in-
clude, in addition to the construction costs, burdens
to the owner for:
     1.   engineering and general and administrative costs
          (Engineering costs include design costs, model
          studies, and construction supervision.  General
          and administrative costs include payrolls, records,
          and construction management.  A value of 10 percent
          is considered representative for this cost markup)?
     2.   land costs  (Costs for easements, rights-of-way,
          and purchase of land required to accommodate the
          discharge system or its modification must be con-
          sidered.  Local county officials and real estate
          salesmen are sources for data);
     3.   contingency  (The value of contingency should re-
          flect the type of input data used.  If the quanti-
          ties were taken from detailed drawings, a contingency
                           195

-------
0)
CP
4J
•H
O

o
CM
X
H
Q
S
H

EH
CO
O
O
o
H
E-i
EH
CO

§
O
w
         2500
         2400
         2200
                                        [Mir .i  ,,  .1,,-,,^
         1200-
            1969 1970 1971 1972  1973 1974 1975  1976  1977 1978


                                    DATE
       Fig. 1100 - ENR 20-City Construction Cost Index
                             196

-------
          of 5 percent may be appropriate.  A contingency of
          25 percent may be more appropriate for a planning
          type estimate);

     4.   escalation during construction   (Construction costs
          are calculated in base year dollars.  Because of
          inflation, the prices will rise over the construc-
          tion period.  The procedure used to calculate es-
          calation is to assume a cash flow and apply escala-
          tion to the costs in each year.  In most cases,
          the construction period for this type of work will
          be less than three years.  Values of the construc-
          tion cost index for the period from 1969 to Decem-
          ber 1974 are plotted in Figure 1100.  Dividing the
          project average ENR Index for the construction
          period by its base year value provides an adjust-
          ment factor for escalation.  Projection beyond
          December 1974 is left to the user);
            .'
     5.   interest during construction   (The cost for inter-
          est on the capital required at the time of con-
          struction.  The interest rate depends on the capi-
          tal structure of the utility.  The user should
          contact a stock broker to determine the interest
          rate on bonds for the utility considered); and

     6.   royalties, licenses, fees, etc.   (One-time costs for
          licenses and miscellaneous fees should be consi-
          dered.  State and Federal agencies can provide the
          data for estimating license costs.  If no data are
          available, because this item is small, it may be
          assumed as zero).
Power outage costs,
Account 1103
The key parameters  are  the  time,  the plant capacity  factor
and the unit cost of  equivalent or  replacement power.  It
was assumed the utility can purchase the power.  Outage costs
do not imply cost for interim power generation equipment.
In many cases the actual conversion from the old to new sys-
tem will  not cause  an interruption in  power genera-
tion.   Extended plant downtime may  be avoided by construction
of a temporary discharge  system.  Construction costs for a

                             197

-------
temporary discharge  can be  estimated  using the data in Cate-
gories  1 through  10  and should  be  included in  the total
construction  costs.   The  annual maintenance, period may be an
appropriate time  to  complete  the conversion.   However, there
will be cases where  interruption of power  is unavoidable.
The power outage  period is  a  value that  the user  must  supply.

The unit cost for power during the outage period is equal
to the cost to purchase the replacement power from another
utility minus normal production expenses.  The region, the
utility and the regional power grid demand at the time of
outage will all affect the unit power costs.  The user should
contact the utility for specific data, including an  appropriate
plant capacity factor.
Annual Costs, Account  1104

Annual costs are useful  in comparing  systems  because the
costs are resolved  to  a  common base.   The  remaining useful
life of the plant and  the life discharge system should be
assumed to be equal.   The date the  thermal electric plant
became operational  can be fo.und  in  Reference  7,  which lists
data for all the plants  in the United States.  Assume the
initial plant life  is  40 years in calculating the remaining
useful life.  Annual costs include  those listed below:
     1.   Amortization of the depreciable  capital investment,
          royalties, licenses, fees,  etc., and power outage
          costs, _	  -'--_........   '   _. 		
          Depreciable  capital investment represents the
          amount of the  original value (or worth)  that
          will  decrease  with time.   The depreciable capital
          is calculated  by  subtracting the land costs and

                              198

-------
     salvage value from the total project costs.  Costs
     fqr royalties, licenses, fees, etc. and power out-
     ages .are one-time charges that are neither depre-
     ciable nor exactly non-depreciable.  Amortization
     of these one-time charges is lumped with the de-
     preciable investment.  Annual costs for the items
     considered here are calculated by establishing a
     sinking fund payment.  At the end of the useful
     life of the facility, the sum of the payments plus
     interest will equal the original investment.  Sink-
     ing fund factors for interest rates of 8 and 12 per-
     cent are given in the worksheet for this account.

2.   Amortization of the non-depreciable capital invest-
     ment
     It is assumed land costs are recoverable at any time,
     Therefore, the non-depreciable investment is the
     salvage value of the facility.  The annual costs
     for depreciation are calculated using the sinking
     fund factors given for amoritzation of the depre-
     ciable capital investment.  Salvage value is a
     credit and is included as a negative fixed charge.
     The pumps will have some salvage value, but the
     costs to remove th'.e pumps at the end of the useful
     life may exceed the credit.  Therefore, the salvage
     credit can be assumed to be negligible in most cases.

3.   Interest on  the capital  investment
     If the  initial investment  is  financed by a bond
     issue the  interest payments on the bond issue are
     included in  the annual costs.  Interest rates on
     bonds will vary with the area and  the  capital struc-
     ture of the  utility.  The  interest rate value for
     utility bonds can be obtained from a  local  stock
     broker.

4.   Rent or lease costs
     The  costs  for renting or leasing equipment or pro-
     cesses.  Generally  this  type  of  cost  is  not im-
     portant for  the  systems  considered.


5"   Additional°operating costs attributed to the dis-
     charge  Modification.  Only the  differential cost
     for  pumping  is included in this  item.
 6.    Insurance
                                                   s
                                                  in-
.  insurance rates will be based on the utility;
  total system and will depend on the type of i~
  surance!  A value of 4 percent is considered
  appropriate to apply to the total project cost.

-------
    7.   Property taxes
         Property taxes can be determined from county
         agencies in the area.  The property taxes may
         be assumed at 2 percent of the total project
         costs.

    8.   Tax credit
         The tax credit for installation of capital equip-
         ment is included here.  A tax credit is based
         on:

         a.   the income tax rate (assume 48 percent is
              applied to the depreciable capital)?


         b.   depreciation rate (The depreciation rate
              varies according to useful life.  Tables of
              depreciation rates are readily available);

         c.   depreciable capital (The total project costs
              less the land costs and salvage value of the
              facility equals the depreciable capital); and

         d.   depreciation schedules (Straight-line double
              declining, sum of digits, etc. are some
              schedules used.  Depreciation schedules are
              readily available.  Therefore, no values are
              given).

The differential cost for maintenance of the pumps is consi-

dered negligible.


Table 124  presents the correlation between cost account

number, worksheet, and figure number.  Costs are calculated

using the procedure outlined in the introductory remarks

to this section and the worksheets in Table 125 through 129.
                              200

-------
                Table 124.  CAPITAL COST
                   RESOLUTION ACCOUNTS

Cost
Account
Number

Description

i [
j Figure Worksheet
1 Number Number
i 	
s
1101
Time and regional adjustment  i
  factor
1101
1102
1103
1104
' Project costs
S Power outage costs
i Annual costs
i
1 — ) 1102
i i
i ~ ; 1103
I — ! 1104
              Table  125.  COST CATEGORY 11
                     COST SUMMATION

Cost
Account
Number
1101
1102
1103
1104


i
Description
Construction costs
Project costs
Power outage costs
s
Annual costs
',

Base
Cost
BC1101 =$
^ 1 1 02 "*
A. J. U £
BC1103 =^
B<""1104 =*

                           201

-------
            Table 126 (continued).  TIME AND
               REGIONAL ADJUSTMENT FACTOR

                     Worksheet 1101
Data Requirements

Regional adjustment factor:


Atlanta -        .79
Baltimore -      .84
Birmingham -     .73
Boston -         .90
Chicago -        .91
Cincinnati -     .95
Cleveland -      .94
Dallas -         .77
Denver -         .80
Detroit -        .93
                            Kansas City -       .90
                            Los Angeles -       .90
                            Minneapolis -       .85
                            New Orleans -       .78
                            New York -         1.00
                            Philadelphia -      .90
                            Pittsburgh -        .89
                            St. Louis -         .89
                            San Francisco -     .94
                            Seattle -           .85
City nearest to construction area

Regional adjustment factor

Date construction is to begin or
  period of price level being
  considered

Engineering News Record
  Construction Cost Index for
  above date (20-city average)

Time adjustment factor =
  ENRX  (     )  T 2097a

Regional and time adjustment
  factor = Fm x F_.
            X    K
                                     F  =
                                   ENRX =
                                     F  =
                                     RT
aThe Engineering News Record 20-city average for
 r\or>em'ht*Tr 1 ? .  1 Q74
 December 12, 1974
                            202

-------
                 Table  126.   TIME AND
              REGIONAL  ADJUSTMENT FACTOR

                    Worksheet 1101
Data Requirements  (cont'd)

Total costs from Categories  1  through  10:

    = $
BC2 = $_
BC3 = $_
BC4 = 1
BC5 = $_
BC6 m
BC? = $_
BC8 '
BC9 = 1
BC10= 1
Total Cost = Z  (BC-j^ through BC1())     BCT =$_
Revised Construction Cost

Total cost = BCT x FRT             BC1101
                           203

-------
               Table 127.  PROJECT COSTS

                    Worksheet 1102
Data Required

Total construction cost          BC1101 = —
Cost for engineering and            BCE =  $_
  general and administrative
  	% x B
  100 %

Costs for lands, easements, and     BCL =  $_
  rights-of-way

Revised cost = BC1101 + BC£ + BCL   BC-j^ =  $_
Adjustment for contingencies =      BC~ =  $_
  PIP  v  M 4-   SrVl flfiSb^
  CV^- X  V J. T   t>/J.UUt>/

Adjustment for escalation during    BC3 =  $_
  construction = BC2 x
  ENRX  (beginning) T ENRX  (end)
      2 x ENRX (beginning)

Adjustment for interest during      BC. =  $_
  construction0 = BC^ x
  (1 + no.yrs. of construction
  x annual interest rate/100%) =
  BC3 x  (1 + 	 x 	%/100%)

Royalties, licenses, fees, etc.       R =  $_
Total Project Cost = BC4 + R     BCH02 = —
aAssume 10 percent.

 With detailed information, use a factor of  5  percent;
 for a planning estimate, use 25 percent.

 See account discussion.
                            204

-------
               Table 128.  POWER OUTAGE COSTS

                       Worksheet 1103

Data Required

Period of outage                T =            weeks

Power generation losses         P =            fcwh
  = [capacity x outage              "
    period x capacity factor]

Unit cost of power              U = 	 $/kwh
  = Purchase cost - normal
    production expenses

Outage Cost

T x P x U =                BC1103
                 Table 129.  ANNUAL COSTS

                       Worksheet 1104
  1.   Amortization of depreciable capital
      investment and costs for power outage,
      royalties, etc.
      Useful Life                 Sinking Fund Factor,
      YearsAnnual  Interest  Rate
      3
      5
      7
      10
      13
      15
      18
      22
      25
      28
      30
      35
      40


                             205
8% 12%
.30803
.17046
.11207
.06903
.04652
.03683
.02670
.01803
.01368
.01049
.00883
.00580
.00386
.29635
.15741
.09912
.05698
.03568
.02682
.01794
.01081
.00750
.00524
.00414
.00232
.00130

-------
          Table 129 (continued).  ANNUAL COSTS

                      Worksheet 1104


     Remaining  useful  life  of  the  plant    Y =	 yrs,

     Sinking  fund  factor  (tabulated  above)  F = 	
       for  annual  interest  rate  of    %
    Total project  (first)  cost        BCH02  =  —
    Salvage value                          S  =  $
    Land costs                            L =  $
    Royalties, fees, licenses, etc.       R =  $
    Depreciable capital investment =     D  =  $
      BC1102 "  CS+L+R)                    c    ~~

    Power outage costs               BClin_ =  $_
    The amount amortized is =
    depreciable capital investment        D = $_
      + power outage costs +
      royalties, fees, etc. or

      Dc + BC1103 + R
    Annual cost = F x D                   C = $
2.  Amortization of the non-             NC = $_
      depreciable capital invest-
      ment  (F x S). NC is a credit
      (see No. 9 below).

3.  Interest on the capital invest-       B = _
      ment.  Bond interest rate

    Interest payment = B%/100% x         I  = $_

      (BC1102 + BC1103}
4.  Rent or lease costs                  L  =  $
                           206

-------
         Table  129  (continued).   ANNUAL  COSTS

                    Worksheet  1104
5.  Operating costs.  Electric power
    in excess of the power required
    before the addition or modification

    = Theoretical Power * efficiency     p  = 	w
    a* 	watts x 10 0%/	%

    Annual operating hours                H =            hrs,

    Power costs = H x P^x 	/kwha       Z = $
6.  Insurance (BClino -L-R)x          I = $
         %b/100%
7.  Property taxes (BC1ino - L - R)      P  = $
      x 	%c/100%
8.  Tax credit

                     d
      Income tax rate                     „
                                          Xx
    Methods of depreciation:

    a.  Straight line depreciation
          Tax credit = Dc x IR%/         T± = $	
          (100% x Y)
          = $	 x 	%/(100% x Y)

    b.  Others  (refer to the following tabulation)
aAssume $.018/kwh      cAssume 2 percent
 Assume 4 percent       Assume 48 percent
                            207

-------
           Table  129  (continued).   ANNUAL COSTS



                      Worksheet 1104




                                                     Ti
                                                 (annual

                 D             .j.                 increments of

    Year      (deprec. rt.)      R       Dc        depreciation)
                                    T       T
                                    1 =  Z  i  =
9.  Annual costs = Z  (C - N  +  I  + L   +  Z  +  I  +  p.  -  T, )
                           c    p    s             *    x
f$

 Refer to a depreciation schedule for DR  for other  than


 straight line depreciation
                           208

-------
                          SECTION V


                        REFERENCES
1.   Associated Equipment Distributors.  1974 Rental Distri-
     butors, 25th Edition.  Associated Equipment Distributors,
     Oak Brook, Illinois.  1974.  165p.


2.   McKee-Berger-Mansueto Inc.  Building Cost File - 1974
     Unit Prices, Eastern Edition.  Construction Publishing
     Company, Inc., New York.  1973.  266p.


3.   McGraw-Hill Information Systems Company, and Wood and
   '  Tower Inc.  1974 Dodge Manual for Building Construction
     Pricing and Scheduling.  McGraw-Hill Inc., New York.
     1974.  202p.
4.   Godfrey, R.S.  Means Building Construction Cost Data -
     1974.  Robert Snow Means Company, Inc., Broxbury,
     Massachusetts.  1974.  290p.


5.   Mayo, R.S., Thomas Adair, and Robert J. Jenny.  Tunneling •
     The State of the Art, R.S. Mayo and Associates, Lancaster,
     Pennsylvania, for U.S. Department of Housing and Urban
     Development, Washington, D.C.  Contract H-766.  January
     1968.  270p.


6.   Corps of Engineers.  Engineering and Design, Tunnels and
     Shafts in Rock.  Department of the Army, Office of the
     Chief of Engineers, Washington, D.C.  Engineer Manual
     Number 1110-2-2901.  December 1973.  300p.


7.   Bureau of Power.  Steam - Electric Plant Construction
     Cost and Annual Production Expenses, Twenty-third Annual
     Supplement - 1970.  Federal Power Commission, Washington,
     D.C.  Publication Number FPC S-209.  166p.
                            209

-------
                    REFERENCES  (cont'd)
8.   Federal Power Commission.  The 1970 National Power
     Survey, Part 1.  U.S. Government Printing Office,
     Washington, B.C.  December 1971.  400p.


9.   Blecker, H.G. and T.W. Cadman.  Capital and Operating
     Costs of Pollution Control Equipment Modules, Volume 1.
     U.S. Environmental Protection Agency, Washington, B.C.
     Publication Number EPA-R5-73-023a.  July 1973.  225p.


10.  Study Suggests Quantity Take-Off Estimating Most Accurate.
     Engineering News Record, 192 (26):84-89.  June 1974.


11.  Rown, A.M., F.R. Bowerman, and N.H. Brooks.  Biffusers
     For Bisposal of Sewerage in Sea Water.  Transactions
     ASCE, Volume 126, Part III:  pp344-388.  March 1961.


12.  Herkimer, H.  Cost Manual for Piping and Mechanical
     Construction.  New York, Chemical Publishing Company, Inc.,
     1958.  176p.


13.  Proctor, R.V. and T.L. White.   Rock Tunneling With Steel
     Supports.  Commercial Shearing and Stamping Company,
     Youngstown, Ohio.  1969.  290p.


14.  Construction Scoreboard.  Engineering News Record,
     193 (25):21.  Becember 1974.
                             210

-------
                        SECTION VI
                    CONVERSION FACTORS
Data for converting from English to the International System
of Units is given below:
   One acre              =
   One cubic foot        =
   One cubic yard        =
   One foot              =
   One foot per second   =
   One gallon            =
   One gallon per minute =
   One horse power       =
   One inch              =
   One mile              =
   One pound             =
   One pound per         =
     square inch
   One square foot       =
   One square yard       =
   One ton  (short)       =
   One yard              =
4047 square meters
0.0283 cubic meters
0.7646 cubic meters
.3048 meters
18.29 meters per minute
3.785 x 10"3 power
.0630 liters per second
745.7 watts
2.54 centimeters
1.6093 kilometers
0.4536 kilometers
703.1 kilograms per square meter

.0929 square meters
0.8361 square meters
907.2 kilograms
0.9144 meters
                             211

-------
                        SECTION VII

                        APPENDICES

                                                      Page
APPENDIX A - Case Study                                213

APPENDIX B - Background Unit Cost Data                 269
                            212

-------
                       APPENDIX A

                       CASE  STUDY
GENERAL

An example  is  included  here  to  illustrate the application
of the procedures  in  the manual to  an actual case of once-
through cooling water discharge system modifications.  A
project description and step-by-step procedure for estimat-
ing the costs  are  given.   The results using the method-
ology in the manual are compared with the actual construc-
tion costs.

The cost data  for  this  project  and  the others listed in
Table 1, not included here,  are not part of the information
used to develop the unit costs  for  the manual.
The basis  for  comparison of  the  costs is as follows:
     1.    Manual  - Construction  costs are December 1974
           level and  are adjusted for the project location.
           A contingency of 5 percent is added  (the data
           were considered as detailed information).
     2.    Plant data - Actual  construction costs for the
           modifications to the once-through cooling water
           discharge  were furnished by the utility owner.
           The  costs  are escalated from the mid-point of
           the  construction period to December  1974.
PROJECT DESCRIPTION
Project:  Quad Cities - Station Units 1 and  2
          Commonwealth Edison Company
          Chicago, Illinois
                            213

-------
 Quad-Cities Station  is  a  nuclear fueled steam electric
 generating plant  located  about 34 kilometers north of Moline,
 Illinois on the Illinois  shore of the Mississippi River,
 (Pool 14).  The plant consists of two-809 mWe boiling water
 reactors which withdraw 65  cubic meters per second from the
 Mississippi River for condenser cooling.  The plant has an
 open cycle condenser cooling system which discharges heated
 cooling water into the  river.

 The original shoreline  "side-jet" discharge system consisted of
 a concrete lined  channel  with sheet pile slot jet emptying
 into the Mississippi River.   This was used as an interim
 system to meet the scheduled start-up date.  In 1972, the
 interim discharge system  was modified to a multiport dif-
 fuser type consisting of  two underwater carbon steel diffuser
 pipes with nozzles discharging water perpendicular to the
 shoreline.  The discharge arrangement is shown in Figure 1201.

 All quantities and related  information used in the cost de-
 velopment were determined from drawings provided by Common-
 wealth Edison Company.
               Multiport
                Diffuser
                 Flow

       Mississippi River
        Existing
        Discharge
         Channel
        Permanent
Cofferdam Structure
Discharge
                              Inlet Structure
   Fig. 1201 - Discharge Arrangement at Quad Cities
                             214

-------
ESTIMATE
The following estimate includes costs for:
     1.   construction of a cofferdam across the discharge
          channel;
     2.   removal of riprap from the existing channel bank
          and excavation of a new channel to divert the flow
          into the inlet structure;
     3.   construction of a concrete and steel sheet pile
          inlet structure; and
     4.   installation of carbon steel pipe on land and a
          multiport diffuser offshore.   (Nozzles are arranged
          along the conduit from near the shore to the off-
          shore end of the pipe.)
The inlet structure is constructed by first driving piling
to form a rectangular area, excavating the material from
within the rectangle, installing the pipes and concrete
structure and finally backfilling with sand to the original
ground level.
Cost Category 1

Account 101, Riprap removal  (Worksheet 101) -

The riprap removed from the channel is assumed to be stock-
piled on site and used for lining the new channel section.
Therefore, hauling costs are not included.
                            215

-------
                  Table 5.   RIPRAP REMOVAL

                      Worksheet 101
 Design Data Required
 Haul  distance  to disposal site                /]*   km
   (round trip)a

 Volume of riprap                        V =   30Q    m
Base Cost

Base cost for excavating riprap =
  $5.40/m3 x V                      BC(1) =
Enter figure 108.2, read base
  unit cost for rock haul and                   .* *
  disposal                          BUG (2)=$  /M fl,   /mj

Base cost for haul and disposal                  . .
  of riprap = V x BUG (2)            BC(2) =$  /V. 4.

Total base cost = BC(1) + BC(2)     BCIQI =$
alf haul distance is not provided, assume 8-km round trip.
Accounts 102, 103, 104.1, 104.2,
and 105 do not apply	
                            216

-------
Account 106, Reseeding  (Worksheet 106)  -
                    Table  11.   RESEEDING

                       Worksheet 106
 Design Data Required

 Area of reseeding


 Base Cost

 Base cost = A x $0.37/m
                                        A =
                                     BC, ne. =$
                                       J.UO
m
Account 107, Site Grading
(Worksheets 802.1, 901.1 and 107) -
A cut and fill operation is assumed.  Material and hauling
costs are not included because earth excavated from the pipe
trench and from within the sheet piling enclosure can be

used to balance cut and fill.  Costs are calculated on Work-
sheets 802.1 and 901.1, then transferred to Worksheet 107.
           Table 108.   PLACEMENT OF FILL (LAND)

                    Worksheet 802.1
Design Data Required

Nature of the placement operation
  group number

Volume of fill
                                            .
                                        v =
  Group 1 - Dump and  spread  fill
  Group 2 - Hand compaction  of  fill
  Group 3 - Machine compaction

                           217

-------
Base Cost

Enter Figure 802.1, read base      BC802
  cost
Enter Figure 108.2, read base
  unit cost for hauling           BUG (2)  =$
Base cost for hauling = V x
  BUG(2)

Total base cost = BC(1) + BC(2)
            Table 114.  EARTH EXCAVATION  (LAND)

                      Worksheet 901.1


Design Data Required

Type of excavation                       Jj	
Volume of excavation                    V =	/"7v»@ m

Haul distance  (round trip) from   ,
  excavation site to disposal  site         	 •" "•   km
Base Cost

Enter Figure 901.1, read base
  cost for excavation             BC(1)   =$
al.  Trench or small foundation
 2.  Large foundation
 3.  Channel or large trench

 If haul distance is not given and hauling  is known  to
 be a factor, assume 8-km round trip.
                             218

-------
                  Table 12.  SITE GRADING

                      Worksheet 107
Base Cost

Refer to Cost Category 8 and 9 for
  appropriate cost accounts and cost
  estimate procedures.
  Base cost = £  (appropriate
  base costs).                    BC
                                    107
                                          =$
Accounts 108 and 109 do not apply
Account 110 Mobilization  (Worksheet 110) -
                  Table 15.  MOBILIZATION
                      Worksheet 110
Data Requirement

Cost Account
Number	

101
102
103
104.1
105
106
107
108*
Mobilization
Cost	

Add $3,300 for any one
of these accounts and
$6,600 if two or more
are used
$700
$400
See Cost Cat. 8
$600
                                             Summation
                                                 +00
                                                SZoo
                            219

-------
Mobilization Cost
Mobilization = the total of the
  summation column (above)
MC-, =
 Add mobilization for hauling if accounts 101, 102, 103 or
 106 are used.
The costs from each account are entered on cost summary
sheet for Category 1.
                 Table 4.  COST CATEGORY 1
                      COST SUMMATION	

                       Worksheet 100
Cost
Account
Number
101
102
103
104
104.1
104.2
105
106
107
Description
Riprap removal
Concrete slab removal
Concrete removal
(nonslab)
Sheet pile removal
Pulling costs
Salvage credit
Clearing and grubbing
Reseeding
Site grading
Base
Cost
BC101
BC102
BC103
BC104.
BSC104
BC105
BC106
BC107
= />£££>
- /V./
= /K4.
i = A/. A-
„=(-) A/, A,
MA.
= Z, t3
= -Zt&e

                             220

-------
109
Other
BCIQQ = MA,

Cost Category 1 Total Cost
   (Enter cost in Account 1101)
BC,
=$

110

Mobilization (Enter
Cost in Account 1001)
MCn =$ <£? 9^?


Cost Category 2
Account 201.1, Placement of riprap
 (land-based)  (Worksheet 201.1) -
A total of 835 m  of riprap is needed to line the new channel
to the inlet structure.  Costs for material and hauling are
not included for the riprap stockpiled  from removal opera-
tions  (Account 101).  The costs  for placement and material
and hauling of riprap are included for  the remaining 535
cubic meters of riprap.
                  Table 18.  PLACEMENT OF
                    RIPRAP  (LAND-BASED)
                      Worksheet  201.1
                  ;
Design Data Required
Material3
Volume of material
Haul distance  (round trip) from
  borrow site to construction site
                             221
      v =   535~
     Hd=-
             km

-------
Base Cost

Enter Figure 201.1, read base
  cost for material and place-
  ment                            BC(1)   =$  /2,
Enter Figure 108.2, read base                 a f
  unit cost for hauling           BUG (2)  =$  /£ y£>   /rn

Base cost for haul = V x BUG (2)   BC(2)   =$
Total base cost = BC(1) + BC(2)   BC2oi 1 =$  / 7*030
aCover stone, riprap stone, or filter stone.

 If haul distance is not provided and seems appropriate,
 assume 18-km round trip  (see the discussion  for this
 account).
                  Table 18.  PLACEMENT OF
                    RIPRAP  (LAND-BASED)
                    Worksheet 201.1
Design Data Required
        a
Material           _       m    ^	  .	

                                                         3
Volume of material                      V =	3 OQ   m

Haul distance  (round trip) from   .
  borrow site to construction site     H, =     	     km
                                        a  	
                             222

-------
Base Cost

Enter Figure 201.1, read base
  cost for material and place-                 **
  ment                            BC(1)   =$   /g SO
                                 X "bcef
Enter Figure 108.2, read base      ^
  unit cost for hauling           BUG(2)  =$   ^

Base cost for haul = V x BUG(2)   BC(2)

 'otal base cost = BC(1)

  70'fa./   BCzo/./ f'
Total base cost  =  BC{1)  + BC(2)    BC—,  ,  =$
aCover  stone,  riprap stone,  or filter stone.
 If haul distance  is not provided and seems  appropriate,
 assume 18-km  round trip (see discussion for this
 account) .
Account  201.2  does  not apply


Account  202.1,  Steel  sheet piling (land)  -


Refer to Worksheet  for costs of the  piling  used  in the inlet

structure.
                   Table  20.   STEEL SHEET
                       PILING (LAND)

                     Worksheet  202.1


Design Data Required

Area of sheet piling                       2«*>-^£	.m

Intended usage                                     ^.
  (temporary or permanent)            Kev>n»^./^t»S£
                             223

-------
Base Cost

Enter Figure  202.1, read base
   cost                            BC
                                    202.1
Accounts 203, 204, and 205 do not apply.


Account 206 Mobilization  (Worksheet 206) -




                  Table 26.  MOBILIZATION

                      Worksheet 206
 Data Requirements

 Cost Account          Mobilization
 Number	          Cost	        Summation

 201.1                 $3,700                3i 70£>
   Riprap  stone
   or filter

 201.1
   Cover stone )       $3,300 for one
 202.1         )       of the accounts
 203.1         )       (201.1-204) and
 204                   $6,600 for two or
                      more accounts          3

 Hauling3              $600

 Mobilization for marine equipment
   is included in Categories 4 and 6
Mobilization Cost

Mobilization = the total of the
  summation column (above)        MC_     =   7,
alf account 201.1 is used and hauling costs are  added to the
 estimate, include the mobilization cost  for hauling.

                             224

-------
Costs for each account are entered on the summary worksheet
for Category 2.
                Table 17.  COST CATEGORY 2
                	COST SUMMATION	

                      Worksheet 200
Cost
Account
Number
201

201.1
201.2
202
202.1
202.2
203
203.1
203.2
204
205
Description
Riprap and filter
material and place-
ment
Placement by land-
based equipment
Offshore placement
Steel sheet piling
Placement by land-
based equipment
Offshore placement
Piles
Land installation
Marine
Concrete
Other
Base
Cost


BC i , -$_,
*D^* ~~ ^
Jji,.- _ _ _ ^ *^ o

BC202 1 =$
e.\l f, m -L
RP =S
on? 9 * ...

BC 3 , =$
£.\> J . i
BCo«T 0 =5 	
BC204 =$



/e.e*t>
AS.4.

U*,0tX>
A/. A.

MA.
A/.A
MA.
— .

Cost Category 2 Total Cost
  (Enter cost in Account 1101)
                                          -$
206
          Mobilization  (Enter
            Cost in Account 1001)
                                          =$    7
                            225

-------
Cost Category 3 does not apply.


Cost Category 4

Accounts 401 and 402 do not apply.

Account 403.1, Steel pipe  (Worksheet 403.1) -

Information supplied by Commonwealth Edison indicates that
the pipe was shop fabricated and shipped to site.  Pipe costs
are for onshore piping only.  The conduit offshore is used
as a manifold for the diffuser.  Therefore, costs are given
in Category 6.
                 Table 46.  STEEL CONDUIT
                       Worksheet 403.1
Design Data Required
Pipe diameter                                 <*ft       m
Wall thickness                                 "Zf^     cm
With or without stiffeners
Pipe length                             L      715*
Shop or field fabrication             S
                                                        nt
                            226

-------
Base Cost

Enter Figure 403.1, read base
  unit cost per lineal meter      BUG     =$
Base cost = L x BUG               BC      =$ JfiZ
                                            ' ' "
Cost Adjustments

Enter Figure 403.1, read design   F  (1)
  adjustment factors for wall      D. .
  thickness, stiff eners and        D( 2)
  fabrication                     FD(3)
Adjusted Base Cost

Adjusted base cost of materials
  and fabrication = BC x F  (1) x
  FD(2) x FD(3)           D       BC403.1
a
 For diameters to 3.05 meters, assume shop fabrication.
Account 403.2, Carbon Steel pipe
fittings  (Worksheet 403.2) -
                     Table  47.  STEEL
                       PIPE FITTINGS

                      Worksheet 403.2
Design Data Required

Type (elbow, reducer, tee,
  connection)
Diameter  (if a fitting diameter
  varies, use largest diameter)            _ *f, V &
m
                             227

-------
Angle  (for reducer or connection)

Number                                  N =
Wall thickness                                 ?, S*V    cm

With or without  stif feners            t4J//X o c* ZJ"


Base Cost

Enter Figure  403.2, read base
  unit cost per  fitting           BUG    =$
Base cost = N x BUG               BC      =$
Cost Adjustments

Enter Figure 403.1, read design   FDd)
  adjustment factors for wall     v  o\
  thickness and stif feners and     Dl  '
  fabrication                     F
Adjusted Base Cost

Adjusted base cost of materials
  and  fabrication for particular
  type of  fitting = BC x F  (1) x
  PD(2) x  FD(3)           D       BC      -$   702.0
Accounts 404 and 405 are not applicable.
Account 406.1, Onshore pipe trench
excavation  (Worksheets 901.1 and 406.1)  -
The pipe trench is large and excavation can be  done  with a
minimal amount of dewatering.  Costs  for excavation  are
calculated on Worksheet 901.1 and transferred to 406.1.
                            228

-------
            Table 112.   EARTH EXCAVATION (LAND)

                      Worksheet 901.1
Design Data Required

Type of excavation3
Volume of excavation                    V =   "2 O <0$O m3
Haul distance  (round trip)  from  ,
  excavation site to disposal  site               A    km
Base Cost

Enter Figure 901.1, read base
  cost for excavation             BC(1)   =$  &€J>t OCO

Enter Figure 108.2, read base
  cost for hauling         *       BUG (2)  =$   3*
Base cost for hauling = V x    *•''/*' sr
  BUG (2)                          BC(2)   =$  ^T 02-O

Total base cost = BC(1) + BC(2)   BC901.! =$  9S, 02~€>
al.  Trench or small foundation
 2.  Large foundation
 3.  Channel or large trench
blf haul distance is not given and hauling is known to
 be a factor assume 8-km round trip.
                            229

-------
                 Table 50.  ONSHORE PIPE
                    TRENCH EXCAVATION

                     Worksheet  406.1
Base Cost

Refer to Cost Accounts 901 or
  902 for cost estimating pro-
  cedure                          BCAne.  , =$
                                       ' . L  —
Account 406.2, Onshore pipe
laying  (Worksheet 406.2) -
Base cost = L x BUC               BC406 2
              Table  51.  LAYING PIPE ON LAND

                    Worksheet 406.2


Design Data Required

Length of pipe                          L ~____7^_	m

Diameter of pipe                        D =    ^ g£  m

Material


Base Cost

Enter Figure 406.2, read base
  unit cost per lineal meter      BUG     =$
                            230

-------
Account 406.3, Onshore fill
(Worksheets 802.1 and 406.3) -
The material used for backfill is that excavated from the
pipe trench.  Hand compaction is assumed for 25 percent of
backfill placed.  The remaining fill is machine compacted.
           Table 106.  PLACEMENT OF FILL  (LAND)
                     Worksheet  802.1

Design Data Required
Nature of the placement opera-
  tion group number^                 	Z-
Volume of fill                          V -   *f7&&   m3
Base Cost
Enter Figure 802.1, read base
  cost                            BC802.1 =£-
aGroup 1 - Dump and  spread  fill
 Group 2 - Hand compaction^of  fill
 Group 3 - Machine compaction
                             231

-------
            Table 106.   PLACEMENT OF FILL  (LAND)

                     Worksheet 802.1
Design Data Required

Nature of the placement opera-              _
  tion group number3                 	«5	

Volume of fill                          V     /4£ / 3 O  m3
Base Cost

Enter Figure 802.1, read base
  cost                            BCono T =$
 Group 1 - Dump and spread fill
 Group 2 - Hand compaction of fill
 Group 3 - Machine compaction
                Table 52.  ONSHORE BACKFILL

                     Worksheet 406.3


Base Cost

Refer to Cost Category 8 for appro-          ^*> ^
  priate cost accounts and esti-
  mating procedures               BC406 3 =—
                            232

-------
Acounts 406.4, 406.5 and 407.1
Through 4Q7»6 do not apply


The offshore conduit is used as a manifold for the diffuser.
Therefore, costs for offshore pipe is included in Category 6.
(If a pipe were used to convey the water to a diffuser, costs
for the pipe would be included here.)


Account 409, Mobilization  (Worksheet 409) -
                  Table  62.  MOBILIZATION

                      Worksheet 409


Data Requirement

                          Mobilization
Description               Cost	    Summation

For offshore installation  $96,000           	
  of a conduit add
 $96,000a

For land installation      $ 6,600
  of the conduit add

For hauling fill           $   600


Mobilization Cost

Mobilization = the total of the
  summation column  (above)         MC4   -$
••—•i	.^^—•».  ii i    	
aThe mobilization costs are inclusive of accounts 407.1
 through 407.6.
                            233

-------
Enter costs from each account onto the summary worksheet
for Category 4.
                Table 43.   COST CATEGORY 4
                      COST SUMMATION
Worksheet 400
Cost
Account
Number
401
402
403
403.1
403.2
404
405
406
406.1
406.2
406.3
406.4
406.5
Description
Precast concrete pipe
Cast-in-place box
culvert
Steel conduit
Steel pipe
Steel fittings
Corrugated metal
pipe
Fiberglass pipe
Land installation
of pipe
Onshore excavation
Onshore pipe laying
Cushion fill and
backfill
Pipe supports
Dewatering
Base
Cost
BC401
BC402
BC403.1
BC403.2
BC404
BC405
BC406.1
BC406.2
BC406.3
BC406.4
BC406.5
=$ //.A.
=$ MA.
=$2.3£,07,T
=$ 7C7.&
-$ MA.
=$ M/t.
-S 9 ST.* 10
=$ £0j£Z*T
=$ +<>, &*
=$ M A.
=$ A/, /I,

                            234

-------
407
407.1
407.2
407.3
407.4
407.5
407.6
408
Marine Installation
of pipe
Offshore excavation
Offshore pipe laying
Cushion fill and
backfill
Pipe supports
Riprap protection
Cofferdams
Other
BC407 1 t=$
BC407 2 =$
BC407 3 "$
BC407 4 "$
BC407 5 =$
BC407 6 "$
BC408 **'

MA.
A/. A.
#,4.
#. A.
A/,*,
A/. A.
MM,

Cost Category 4 Total Cost
   (Enter Cost in Account 1101)
BC,
409
          Mobilization  (Enter
            Cost in Account 1001)
MC
=$
Cost Category 5 does not apply.
Cost Category 6

Account 601, Nozzles  (Worksheet 601) -

It is assumed that all nozzles are shop fabricated from
1.27 cm thick carbon  steel plate, and the nozzles are
welded to the manifold pipe before offshore placement.

Two types of nozzles, conventional and stub, are used for
the diffuser system.  The stub nozzle is the riser,  (dimen-
tion "f")  without an  elbow to divert the flow.  To determine
                            235

-------
stub nozzle costs, adjustment factors for two conventional
nozzles of the same diameter are read from Figure 601.  If

the difference in "f" values used to select the adjustment
factors is equal to the stub nozzle height, a second adjust-

ment factor is derived (FD2).  Multiply this factor times
the value read from graph in figure 601.
                 Table 80.   STEEL NOZZLES
                      Worksheet 601
 Design  Data  Required

 Nozzle  inside diameter

 Riser length3

 Number  of nozzles
                                                       m
                                              £>*&>!
                                                       m
                                        N =
                                               / C>
Base Cost

Enter Figure 601, read base
  unit cost per nozzle

Base cost = N x BUG
                                  BUG     =$  3  ICO

                                  BC      =$
Cost Adjustments

Enter Figure 601, read design
  adjustment factor  for the
  riser length  (f)


Adjusted Base Cost

Adjusted cost = BC x FD
                                   D
                                  BC
                                    601
                                              Q,
                                          =$
 The  riser length "f" is the distance from the  (horizontal)
 nozzle  centerline to the top of the manifold minus 1.5
 times the nozzle diameter.
                          236

-------
                 Table  80.  STEEL NOZZLES

                     Worksheet 601
Design Data Required

Nozzle inside diameter
Riser lengtha                                   ,       m

Number of nozzles                       N =


Base Cost

Enter Figure 601, read base
  unit cost per nozzle              BUG   =$
Base cost = N x BUG                 BC    =$
Cost Adjustments

Enter Figure 601, read design
  adjustment factor for the
  riser length  (f)                  FD
Adjusted Base Cost

Adjusted cost = BC x FD             BC601 =$
aThe riser length "f" is the distance from the (horizontal)
 nozzle centerline to the top of the manifold minus 1.5
 times the nozzle diameter.
                            231

-------
                  Table  80.   STEEL  NOZZLES

                      Worksheet  601


 Design  Data Required

 Nozzle  inside  diameter                         X 2£   m

 Riser length                                  £>, fe/    m

 Number  of  nozzles                      N =_^


 Base Cost

 Enter Figure 601, read base
  unit  cost per nozzle              BUG   -=$
Base cost = N x BUG                 BC    =$
Cost Adjustments

Enter Figure 601, read design
  adjustment factor for the
  riser length  (f)                  F
                                     Q
Ad j usted Base Cost

Adjusted cost = BC x FD             BCfini
aThe riser length "f" is the distance from the  (horizontal)
 nozzle centerline to the top of the manifold minus  1.5
 times the nozzle diameter.
                            238

-------
                  Table  80.   STEEL NOZZLES

                      Worksheet  601
Adjusted Base Cost

Adjusted cost = BC x FD             BC601 =$
Design Data Required

Nozzle inside  diameter                           •     m

Riser length3                                  ^^/   m

Number of nozzles                       N =


Base Cost

Enter Figure 601, read base
  unit cost per nozzle              BUG   =$  £,,
Base cost = N x BUG                 BC    =$  2£V*j 00O


Cost Adjustments

Enter Figure 601, read design
  adjustment factor for  the
  riser length  (f)                  FD
aThe riser length "f" is the distance from the (horizontal)
 nozzle centerline to the top of the manifold minus 1.5
 times the nozzle diameter.
                           239

-------
                 Table  80.  STEEL NOZZLES

                     Worksheet  601


Design Data Required

Nozzle inside diameter                         *£V^>/   m
Riser  length3                                  Qf&/   m

Number of nozzles                       N =


Base Cost

Enter  Figure 601, read base
  unit cost per nozzle              BUG   -$  3, /CO

Base cost = N x BUG                 BC    =$
Cost Adjustments

Enter Figure 601, read design
  adjustment factor for bhe
  riser length  (f)                  FD    =  0,
Ac* j usted Base Cost

Adjusted cost = BC x FD             BC601
aThe riser length "f" is the distance from the  (horizontal)
 nozzle centerline to the top of the manifold minus 1.5
 times the nozzle diameter.

                             240

-------
Account 602.1 does not apply.


Account 602.2, Steel manifolds
(Worksheets 403.1 and 602.2) -


Costs for installation of conduit offshore is calculated on

Worksheet 403.1 and transferred to Worksheet 602.2.
                 Table 46.  STEEL CONDUIT

                     Worksheet 403.1


Design Data Required

Pipe diameter                                 V, PP    m
Wall thickness                                 g,5^   cm

With or without stiffeners
Pipe length                             L      //OO    m

Shop or field fabrication


Base Cost

Enter Figure 403.1, read base
  unit cost per lineal meter      BUG     =$_
Base cost = L x BUG               BC      =$_
Cost Adjustments
Enter Figure 403.1, read design   FD^
  adjustment factors for wall     p  (2)   =    MA.
  thickness, stiffeners and        D
  fabrication                     FD( J   ~—
                             241

-------
 Adjusted Base  Cost

 Adjusted base  cost  of  materials
   and  fabrication = BC x FD(1) x
   FD(2)  x FDC3)                    BC403.1
                                      A &**>
 aFor diameters  to 3.05  meters,  assume shop fabrication.
                  Table  82.   STEEL MANIFOLD

                      Worksheet 602.2


 Base  Cost

 Refer to Cost  Account 403,  Steel
   conduit.   Base  cost =  BC4Q3      BC602  1  =$
Account  603.1,  Installation  of conduit
diffuser (Worksheets  407.2 and 603.1)  -
              Table  56.   LAYING OFFSHORE PIPE

                  Worksheet  407.2


Design Data Required

Length of pipe                           L     // 00    m

Diameter                                 D =    */, &&  m

Pipe material                        L*,rlt>*>
Depth of water            JLt-d^   -j-b&-«~   /*/   m
                            242

-------
Base Cost

Enter Figure 407.2, read base
  unit cost per lineal meter      BUG     =$
Base cost = L x BUG               BC      =$ 979, OOP


Cost Adjustment

Enter Figure 407.2, read
  adjustment factor for water
  depth                           p            /
                                   D
Adjusted Base Cost

Adjusted base cost for laying
  pipe offshore = BC x FD         BC407 2 =$
                Table 84.  INSTALLATION OF
                    CONDUIT DIFFUSER	

                     Worksheet 603.1


Base Cost

Select cost Account 406.2 for dry
  installation within an offshore
  cofferdam or 407.2 for under-
  water installation.

Base cost = BC4Q6>2 or BC407>2    BC6Q3>1 =$
                            243

-------
Account 603.2 and 603.3 do not apply.
Account 603.4, Trench excavation
 (Worksheets 901.2 and 902.2 and 603.4)
           Table 113.  EARTH EXCAVATION  (MARINE)
                     Worksheet 901.2


Design Data Required

Type of excavation  (soft, firm,
  hard)a                                    _

Volume of excavation                    V = /3£e 
-------
Adjusted Base Cost

Adjusted cost =  (BC(1)  x Fn)
                           D
aSoft - Sand or  unconsolidated silt.
 Firm - Clay or  other  cohesive material.
 Hard - Till or  soft,  weathered rock.

 Side cast or  hauled to  shore.

GFrom the shoreline to a land disposal  area.  If this haul
 distance is unknown,  assume  an 8-km round trip.
            Table  115.   ROCK  EXCAVATION  (MARINE)

                   Worksheet 902.2


 Design Data Required

                                                        3
Volume at excavation                    V =    *rPC/   m

Haul distance  (round  trip)a
  from shoreline  to disposal
  area                                     	£>
Base Cost

Base cost for offshore  rock
  excavation =  $55.40/m3 x V      BC(1)   =$
Enter Figure 108.2, read base
  unit cost for rock haul and
  disposal  (curve A)              BUG (2)  =$   6, ID

Base cost for haul and
  disposal of waste rock
  V x BUG (2)

Total base cost = BC(1)+BC(2)
alf haul distance is not given and hauling is known to be a
 factor, assume 8-km round-trip
                            245

-------
               Table  87.  TRENCH EXCAVATION
                    Worksheet 603.4
Base Cost

Refer to Cost Category 9 and               ^
  select the cost from either
  Cost Account 901.1 or 901.2

Base cost = BCg^^ or BC901_2    BC6()3>4 =$_
Accounts 603.5 and 603.6 do not apply
Account 603.7, Trench backfill
 (Worksheets 801, 802.2 and 603.7) -
          Table  105.  MATERIAL AND HAULING COSTS

                  Worksheet 801


Design Data Required

Type of fill material
Haul distance  (round trip)a
  from the borrow site                      _ / £   km

Volume of fill                          V =
                            246

-------
Base Cost

Enter figure 108.2,  read  base
  unit cost for hauling              BUG   =$
Base cost for hauling =  BUG  x V     BC..   -$
Enter Figure  801,  read base
  cost                               BC   =$  //£>t e>0Q
Cost Adjustment

Enter Figure  801,  read
  adjustment  factor  for
  material                           FD    =


Adjusted Base Cost

Adjusted base cost = (BC2  x Fn)
                             D            •$
 If haul distance  is not known, assume an 18 -km haul.
          Table  1Q5.  MATERIAL AND HAULING COSTS

                   Worksheet  801


Design Data Required

Type of fill material                S4#?t£ H//

Haul distance  (round trip)
  from the borrow site                        /C>
                                                        *\
Volume of fill                          v =  /^/ 9&0  m
                            247

-------
Base Cost

Enter Figure 108.1, read base
  unit cost for hauling             BUG   =$
Base cost for hauling = BUG x V     EC^   =$
Enter Figure 801, read base
  cost                              BC    =$   /I SOP
Cost Adjustment

Enter Figure 801, read
  adjustment factor for
  material                          F

Adjusted Base Cost

Adjusted base cost =  (BC0 x F )
  +BC,                  2    D      Bc801 •$ / 23,
alf haul distance is not known, assume an 18 -km haul.
          Table 107.  PLACEMENT OF FILL  (MARINE)

                   Worksheet 802.2


Design Data Required

Nature of the placement              a   L  f
  operation3                        QmtlLw

Volume of fill                          V =  /Vff 3&O m3
                             248

-------
Base Cost

Enter Figure 802.2, read base
  cost                            BC802.2
 Backfill of a pipe trench; placing fill into a cofferdam
 or backfill using excavated material side cast along
 the trench.
                Table 90.  TRENCH BACKFILL

                    Worksheet 603.7


Base Cost
                                           /.e> So. e>e>e>
Base cost = base cost from the
  appropriate accounts in Cost
  Category 8.                     BC603 7 =
Accounts 604 and 605 do not apply.


Account 606, Mobilization  (Worksheet 605) -
                              249

-------
                 Table 93.  MOBILIZATION
                     Worksheet 606
Mobilization Cost

Mobilization = $30,000 if the diffuser
  is a tunnel diffuser.  If the total
  length of offshore pipe is the
  manifold for a conduit diffuser,
  add $96,000.  (Caution:  do not
  duplicate costs in Account 408.)
MCg -1
Enter costs for each account onto the summary worksheet for

Category 6.
                Table 79.   COST CATEGORY 6
                	COST SUMMATION	

                    Worksheet 600
Cost
Account
Number
601
602
602.1
602.2
602.3
603
603.1
603.2
Description
Nozzles
Manifolds
Concrete manifolds
Steel manifolds
Steel fittings
Installation
Conduit manifold
Nozzles
Base
Cost
BC601
BC602.1
BC602.2
BC602.3
BC603.1
BC603.2
=$ zt

_<*
=$
=$ 1'
=$

9*tf ttO
$o$fSi>o
MA,
N,A,
79, t>f>o
MA

                            250

-------
603.3
603.4
603.5
603.6
603.7
604
605
Cofferdams
Excavation
Dif fuser Support
Scour protection
Backfill
Single Port
Other
BC6 =$ A/,4.
BC603 1 =$ #•*•
BC603 5 *$ MA'
BC603 6 =$ ^'^
BC «$ Zi^grz.US"
603.7
BC =$ A;. 4,
Bc£05 =$ M/l,

Cost Category 6, Total Cost
  (Enter cost in Account 1101)
BC,

606
Mobilization (Enter
cost in Account 1001)
MC, =$ 
-------
                 Table 96.  CAST-IN-PLACE
          STRUCTURAL CONCRETE, CONCRETE PLACEMENT

                    Worksheet 701.1
Design Data Required

Category of structure                _ / _

Volume of concrete                     V =  / & O


Base Cost

Enter Figure 701. 1, read base
  cost                            BC701.1 =$
                                                      nt
                                                       3
 1.  Suspended slabs, beams, walls
 2.  Spread footings, grade slabs, and pile caps.
 3.  Structures with little or no reinforcing.
                 Table  96.  CAST-IN-PLACE
          STRUCTURAL CONCRETE, CONCRETE PLACEMENT
                     Worksheet 701.1


Design Data Required

Category of structurea                   3	

Volume of concrete                      V =    || &OQ  m
                            252

-------
Base Cost

Enter Figure 701.1, read base
  cost                            BC
                                    701.1
 1.  Suspended slabs, beams, walls.
 2.  Spread footings, grade slabs, and pile caps.
 3.  Structures with little or no reinforcing.
Account 701.2, Reinforcing  (Worksheet 701.2) -


The unit weights of reinforcing assumed are 89 kg/m  and

10 kg/m  for structure categories 1 and 3, respectively.
            Table 97.  CAST-IN-PLACE STRUCTURAL
            	CONCRETE, REINFORCING STEEL

                      Worksheet 701.2
Design Data Required

Category of structurea               	/	

Weight of reinforcing steel                 MfZOO   kg


Base Cost

Enter Figure 701.2 read base
  cost                            BC701.2 =$
al.  Suspended slabs, beams*,- and walls.
 2.  Spread footings, grade slabs, and pile caps.
 3.  Structures with little or no reinforcing.
blf weight of reinforcing steel is not available, assume
 values shown in the following table:
                             253

-------
                             Weight of  Reinforcing
          Category           to assume, kg/ifl3 of  cone,

              1                          89
              2                          71
              3                          0-20
            Table  97.  CAST-IN-PLACE STRUCTURAL
                 CONCRETE, REINFORCING STEEL

                    Worksheet 701.2


Design Data Required

Category of structure                	J3	

Weight of reinforcing steel                 /^V^tt^  kg
Base Cost

Enter Figure 701.2 read base
  cost                            BC701>2 =$_
al.  Suspended slabs, beams, and walls.
 2.  Spread footings, grade slabs, and pile caps.
 3.  Structures with little or no reinforcing.

 If weight of reinforcing steel is not available, assume
 values shown in the following table:
                             Weight of Reinforcing
          Category           t:o assume, kg/m3 of cone.

             1                          89
             2                          71
             3                         0-20
Accounts 702, 703, 704, and 705 do not apply.
                             254

-------
Account 706, Mobilization  (Worksheet 707) -
Refer to worksheet.
                 Table 102.  MOBILIZATION

                     Worksheet 706
Mobilization Cost

For a large structure other
  than the pump station, add
  $3,300
MC?   =$ 3, 30O
Enter the charts from each account onto the summary worksheet
for Category 7.
                Table 95.  COST CATEGORY 7
                     COST SUMMATION	

                    Worksheet 700
Cost
Account
Number
701
701.1
701.2
702
703
Description
Structural concrete
Concrete placement
3
Reinforcing steel
Concrete (marine)
Grouting
Base
Cost
BC701.1
BC701.2
BC702
BC703
=$ \ZI*,t>oo
»$ 2.^.000
=$ MA,
=$ N<*.

                            255

-------
704
705
Cushion fill
Other
BC704
BC705
Cost Category 7 Total Cost
(Enter cost in Account 1101) BC^
706
Mobilization (Enter
cost in Account 1001)
MC7
« <*•'
= $

*$,


= $


MA.
AS, A,

\fott>e>o


3, ^>oo


  The  user  is  cautioned  that most of  the  time  the  costs  for
  these  accounts  are  used  in other categories.   Do not enter
  here if they are  used  in another category.
 Cost  Category  8
Account  801, Material and
hauling  costs  (Worksheet 801)  -
 Sand  fill  is placed within the  steel  sheet piling  enclosure,

 Costs are  given here and in Account 802.1.
          Table 105.  MATERIAL AND HAULING COSTS
                      Worksheet  801
Design Data Required

Type of fill material

Haul distance  (round trip)
  from the borrow site

Volume of fill
V =
Jem

m3
                            256

-------
 Base Cost

 Enter Figure  108.1,  read base
   unit  cost for  hauling           BUG     =$
 Base  cost  for hauling = BUG x V   BC1      =$;
 Enter Figure  801,  read base
  cost                             BC
 Cost Adjustment

 Enter Figure  801,  read adjust-
  ment  factor for  material        F       -   3,(c>3


 Adjusted Base Cost

 Adjusted base cost = (EC,  x F_)
  +BC1                             BC801    "$-
  If haul distance  is  not known,  assume  an  18-km haul.
Account  802.1, Backfill  (land) Worksheet  802.1) -


It is assumed the  sand is  hand compacted.
           Table 106.  PLACEMENT OF FILL  (LAND)

                     Worksheet  802.1


Design Data Required

Nature of the placement operation        «
  group number
Volume of fill                          v =   7 &O
                            257

-------
 Base  Cost

 Enter Figure  802.1,  read base

   COSt                            BC802.1
  Group  1  -  Dump  and  spread  fill
  Group  2  -  Hand  compaction  of  fill
  Group  3  -  Machine compaction
             Table 106.   PLACEMENT OF FILL  (LAND)

                      Worksheet  802.1
Nature  of  the placement operation3
Design Data Required

  iture of the \
  group number                       	^	

Volume of fill                          V *   7/Z&&  m3


Base Cost

Enter Figure 802.1, read base
  cost                            BC802.1 =$
aGroup 1 - Dump and  spread  fill
 Group 2 - Hand compaction  of  fill
 Group 3 - Machine compaction
Accounts 802.2 and 803 do not apply.


Account 804, Mobilization  (Worksheet  804)  -
                              258

-------
                 Table  109.  MOBILIZATION

                     Worksheet 804
Data Requirements

802.1
Mobilization costs for Group
1 of the land placement of
fill is $1,700
The costs for Group 2 is $900*

The costs for Group 3 is $800*
Summation
                                  Boo
Mobilization Cost

Mobilization = the total of the
  summation column.  Usually only
  Group 1 of Account 802.1 will be
  considered (see the discussion
  for this account).               MC
                                     8
                               -S '"700
aUse the costs for groups 2 and 3 only if there is a large
 structure other than the pumping station that requires
 backfill.


Enter the costs from each account onto the summary worksheet

for Category 8.
                Table 104.  COST CATEGORY 8
                	COST SUMMATION	

                      Worksheet 800
Cost
Account
Number
801
802
Description
Material and hauling
costs^
Placement of filla
Base
Cost
BC Q1 *$" 7/f£li>

                           259

-------
802.1


802.2


803
Placement of fill
  (land)a

Placement of fill
  (marine)a

Other
     .! -$ /*, 300
BC
  802.2  Z-

BC»_   =$
Cost Category 8 Total Cost
   (Enter cost in Account 1101)
BC,
                                *$.

804
Mobilization (Enter
cost in Account 1001)
MC0 ='$ Jr70&


 The user is cautioned that most of the time the costs for
 these accounts are used in other categories.  Do not enter
 here if they are used in another category.
Cost Category 9


Account 901.1, Earth excavation (Worksheet 901.1) -
                                               &

It is assumed excavation of material from within the sheet

pile inlet structure is comparable to excavation of a large

foundation.   Excavated material is used for on-site back-

fill.  Therefore, hauling costs do not apply.
                            260

-------
            Table  112.  EARTH EXCAVATION  (LAND)

                     Worksheet 901.1
Design Data Required

Type of excavation3"                  _ 2- _

Volume of excavation                    V -   7&&C>  m3

Haul distance  (round trip) from
  excavation site to disposal
  siteb                                         *— *    km
Base Cost

Enter Figure 901.1, read base
  cost for excavation             BC(1)   =$
Enter Figure 108.2, read base
  unit cost for hauling           BUG (2)  =$
Base cost for hauling «• V x
  BUG (2)                          BC(2)
Total base cost = BC(1) + BC(2)   BC901.1 ~$
al.  Trench or small foundation
 2.  Large foundation
 3.  Channel or large trench
blf haul distance is not given and hauling is known to
 be a factor, assume 8-km round trip.
                            261

-------
               Table 112.   EARTH EXCAVATION (LAND)

                    Worksheet  901.1
 Design  Data  Required

 Type  of excavation
Volume of excavation                    V =  (p
 Enter  Figure  108.2,  read base
   unit cost for hauling            BUG (2)   =$
Base  cost  for  hauling = V  x
  BUG (2)                           BC(2)
Total base  cost = BC(1)  4-  BC(2)    BC90i  i  =$
                                                        *"

 Haul  distance  (round  trip)  from
   excavation site  to  disposal
   siteb                                         -      km
Base  Cost

Enter Figure  901.1,  read base
   cost  for  excavation             BC(1)   =$
al.  Trench or  small  foundation
 2.  Large foundation
 3.  Channel or large trench

 If haul distance  is  not  given and  hauling is  known to be a
  factor, assume 8-km round trip.
Account 901.2, Earth excavation  (marine)  -


All costs for earth excavation  (marine) are  included in

Account 406.1.


Accounts 902.1 - 903 do not apply.


                            262

-------
Account 904, Dewatering during excavation -


Seepage is assumed to be minimal and dewatering costs are
neglected.


Account 907 does not apply.



Account  908,  Mobilization (Worksheet  908) -


Mobilization  costs  for  group 3  are shown on  the worksheet.
                  Table 119.   MOBILIZATION

                      Worksheet 906
 Data  Requirement

 Cost  Account       Mobilization
 Number             Costs _           Summation

 901. la (Group No.)
             1        $1,000                  —
             2        $3,300                  —
             3        $1,500                J

 902. la               $4,000
 Mobilization Cost

 Mobilization = the total of the
   summation  column (above)           MCg    -$  /,
aThese costs  are included only if there  is  excavation other
 than for  a pump station or a pipe trench.


Enter the  costs  from each account onto the  summary worksheet

for Category  9.
                             263

-------
                Table 111.   COST OF CATEGORY 9
                	COST SUMMATION	

                        Worksheet 900
Cost
Account
Number
901
901.1
901.2
902
902.1
902.2
903
904
905
Description
Earth excavation
Earth excavation
(land)a
Earth excavation
(marine)3
Rock excavation
Rock excavation
(land)3
Rock excavation
(marine)3
Shoring for excava-
tion3
Dewatering during
excavation3
Other
Cost Category 9 Total Cost
(Enter cost in Account 1101)
906 Mobilization (Enter
cost in Account 1001)
Base
Cost

BC301,-» ">*•
BC90, , =S

BC903 =$
BC90. =$


MA,
A/' A.
AU,
N, X,

BCQ =$

*/V, &oo


MCQ =$

/.Soo


aThe user is cautioned that most of the time the costs for
 these accounts are used in other categories.  Do not
 enter here if they are used in another category.

                             264

-------
Cost Category  10
                 Table 122.   MOBILrzATION
                     Worksheet 1001
Data Requirements
          Cost Category
          Number	
                1
                2
                3
                4
                5
                6
                7
                8
                9
Mobilization
Cost
MCX =$_
MC2 =£
MC3 =$_
MC4 =$_
7. 7-0 g>
MC5 =$   —

MC6 "1
MC? =$_
MCg =$_
MC9 =$_
Base Cost
Total
BCIOOI •$
                            265

-------
               Table 122.  COST CATEGORY 10
               	COST SUMMATION	

                     Worksheet 1000
Cost
Account
Number
1001
1002
Description
Mobilization
Other
Base
Cost
BC1001 =$ IW*'1*0
BCioo~ =$ N'*'

Cost Category  10 Total Cost
   (Enter cost  in Account 1101)
    BC
                                    IO
                         =$
Time and Regional Adjustment
 (Worksheet 1101) -	
The construction site is located near Chicago.  All costs

were based on a 1.00 adjustment factor for time.   (A com-

parison  is made by updating the actual costs for the

project to December 1974 level.)
                   Table 127.  TIME AND
                REGIONAL ADJUSTMENT FACTOR

                   Worksheet 1101
Data Requirements

Regional adjustment factor:
Atlanta -
Baltimore -
.79
.84
Kansas City
Los Angeles
                            266
.90
.90

-------
Birmingham -     .73          Minneapolis  -      .85
Boston -         .90          New Orleans  -      .78
Chicago -        .91          New York  -       1.00
Cincinnati -     .95          Philadelphia -     .90
Cleveland -      .94          Pittsburgh -      .89
Dallas -         .77          St. Louis -        .89
Denver -         .80          San Francisco -    .94
Detroit -        .93          Seattle -          .85

City nearest to construction area          £h

Regional adjustment factor           F
                                      R
Date construction is to begin or
  period of price level being
  considered
Engineering News Record
  Construction Cost Index  for
  above date  (20-city average)       ENRX =   '2-O
-------
Revised Construction Cost

Total cost = BCT x FRT            BCH01  =$  ^
 a
 The  Engineering News Record 20-city average for
 December  12, 1974.
 Comparison to  actual  costs  - Commonwealth Edison indicated
 that the total construction costs added up to the amount
 of $7,748,000  (excluding  the costs of engineering and model
 studies).

 According to information  obtained from the owner, most of
 the construction was  carried out during the 1972 fiscal
 year.   For purposes of comparison, the above amount must
 be adjusted to 1974 price levels.

 Assuming June  1972 as a base for actual construction, the
 ENR index  corresponding to  this date equals 1761.  The ENR
 for December 1974 equals  2097.

 The adjustment factor for the actual cost is:
     F  = 2097  _
      T 1761  " -1-19

Adjustment  of  the actual  construction cost gives a total
amount  = $7,748,000 x 1.19  - $9,220,120, rounded to
$9,220,000.

A comparison of the actual  cost in terms of 1974 prices and
the estimated  cost using  the manual indicates a variation
of  $43,000 or  approximately 3.7 percent of the actual cost.
                            268

-------
                           APPENDIX B

                    BACKGROUND UNIT COST DATA
GENERAL

This  appendix gives  the user a detailed description of the
components  of unit cost development.   Cost levels,  data
sources  and provision for contractor  overhead are as given
in  Section  III,  Approach.

It  is assumed time for one shift in excess of 8  hours per
day or 40 hours  per  week is charged at double the normal
labor rates.   Installation costs for  land based  operations
are based on 5-8 hour days per week.   A 4-week month is used
as  the base time period when the work includes marine oper-
ations.  Work periods,  days per week  and hours per  day, vary
depending on the type of marine operation.  Marine  work periods
are given in a footnote below the appropriate table.   Labor
and equipment costs  are not separated for offshore  operations.

Rates for the equipment operator and  foreman  are  based on the
type of  equipment on the job site.  The cost  of  an  equipment
operator for  a bulldozer,  for example,  is less than for a
crane operator.   Also,  a foreman that oversees an operation
with a bulldozer is  assumed to receive  less than  a  foreman
in  charge of  work requiring a crane.

The data presented here  include  the following:
     1.    Identification of a representative  labor  force
          (number and type  of workers)  and equipment pool
          (size  and  number  of pieces  of  equipment)  for the
          activity considered
     2.    Labor  and  equipment costs
                             269

-------
     3.   Production rates
     4.   Installation costs
     5.   Where appropriate, material costs which are added
          to installation costs to obtain the total unit
          cost.
The unit cost background information is grouped according to
the cost categories used in the methodology.  However, the
system of cross referencing between categories is not adopted.
Unit cost data are given only for the accounts where the
figures are located or calculations are done.  For example,
to locate the background information on unit costs for pipe
trench excavation, the user must go to Cost Category 9 and
not Category 4.

The data are tabulated as follows:
     1.   Labor force and equipment pool - The information
          pertinent to items  (1) and (2) above is given in
          table(s) for each account.
     2.   Unit cost data - The unit cost for labor and equip-
          ment, equal to the total of labor and equipment
          costs divided by the production rate, is presented
          in the second table(s).  In addition, where mater-
          ials are a part of the total unit cost, material
          costs are given.
The format of the tables is modified for some of the accounts
of cost categories 4 and 7 to improve the clarity of presen-
tation.

Data for Cost Category 5 and accounts that have only material
costs are not included.
                             270

-------
COST CATEGORY 1
Riprap removal, Account 101
                Table B-l.  LABOR FORCE AND
                EQUIPMENT POOL, ACCOUNT 101
Labor
Equipment
Operator
Oiler
Laborer
Foreman
TOTAL
Cost,
$/week
861
*i
726
654
934
3,175
Equipment
Crane
(5.44 x 10 kg)a
Clam Bucket
(2.3m3)

TOTAL
Cost,
$/week
1,100
167


1,267
 The capacity of equipment is given within parentheses.
Costs, productivity, and the unit cost for Account 101 are
listed below:
     1.   Labor and Equipment
     2.   Productivity
     3.   Unit Cost
$4442/week
820m3/week
$5.40/m3
                            271

-------
Concrete slab removal/ Account 102
                Table B-2.  LABOR FORCE AND
                EQUIPMENT POOL, ACCOUNT 102
Labor
Foreman
Equipment
Operator
Oiler
2 Laborers
TOTAL
Cost,
$/week
934
861
726
1,308
3,829
Equipment

Crane .
(5.44 x 10 kg)
Clam (2.3 m3)
Headache ball
TOTAL
Cost,
$/week

1,100
167
60
1,327
          Table B-3.  UNIT COST DATA, ACCOUNT 102
Description
Labor and Equipment,
$/week
Productivity, m"/week
Installation unit
cost, $/m2
Reinforced
Thickness,
to 30 cm
5,156
1,000
5.20
30-45
cm
5,156
750
6.90
Non-Reinforced
Thickness, 30-45
to 30 cm cm
5,156
1,500
3.40
5,156
1,225
4.20
                            272

-------
Concrete removal, Account 103
                Table B-4.  LABOR FORCE AND
                EQUIPMENT POOL, ACCOUNT 103
Labor
Foreman
2 Equipment
Operators
Driller
Blaster
4 Laborers
2 Oilers
TOTAL
Cost,
$/week
934
1,722
825
800
2,616
1,452
8,349
Equipment
Crane
(5.44 x 104kg)
Clam Bucket
(2.3m3)
Track Drill
(14 cm)
Air compressor
(25.5 mVmin.)

TOTAL
Cost,
$/week
1,100
167
344
35^

1,961
          Table B-5.  UNIT COST DATA, ACCOUNT 103
Description
Labor and Equipment,
$/week
Productivity, m3/week
Installation Unit Cost,
Material, powder, etc.,
$/m3
TOTAL UNIT COST, $/m3
Reinforced
10,310
125
82.50
3
85.50
Non-Reinforced
10,310
250
41.20
3
44.20
                            273

-------
Sheet piling removal, Account 104
                Table B-6.  LABOR FORCE AND
                EQUIPMENT POOL, ACCOUNT 104
Labor
Foreman
4 Pile Drivers
Equipment
Operator
2 Oilers
TOTAL
Cost,
$/week
934
3,300
861
1,452
6,547
Equipment
Crane .
(5.44 x 104kg)
Extractor
Leads
Compressor
(25.5 m3/min.)
TOTAL
Cost,
$/week
1,100
190
30
350
1,670
Costs, productivity, and the unit cost for Account 104 are
listed below:
     1.   Labor and Equipment
     2.   Productivity
     3.   Unit cost
     4.   Salvage credit
$8,217
400 m^/weeks
$20.50/m2
$330/kg
Clearing and grubbing, Account 105
                             274

-------
Table B-7.  LABOR FORCE AND EQUIPMENT POOL,
	ACCOUNT 105  (LIGHT  CLEARTWft)
Labor
3 Laborers
Equipment
Operator
Oiler
Foreman
TOTAL
Cost/
$/week
1,962
825
726
898
4,411
Equipment
Dozer
(67,113 W)


TOTAL
Cost,
$/week
586


586
Table B-8.  LABOR FORCE AND EQUIPMENT POOL,
  ACCOUNT 105  (MEDIUM TO HEAVY CLEARING)
Labor
3 Laborers
2 Equipment
Operators
1 Oiler
Foreman
TOTAL
Cost,
$/week
1,962
1,650
726
898
5,236
Equipment
Chipping
Machine
Dozer
(67,113 W)


TOTAL
Cost,
$/week
200
586


786
                    275

-------
           Table B-9.  UNIT COST DATA, ACCOUNT 105
Description
Labor and Equipment,
$/week
2
Productivity/ m /week
Unit Cost, $/m2
Vegetation Density
Light
4,997
28,400
.18
Medium
6,022
20,400
.30
Heavy
6,022
16,200
.37
Reseeding, Account 106
               Table B-10.  LABOR FORCE AND
               EQUIPMENT POOL, ACCOUNT 106
Labor
2 Laborers
Teamster
TOTAL
Cost,
$/week
1,308
649
1,957
Equipment
Truck (3.8m3)
York Rake
TOTAL
Cost,
$/week
104 "
250
354
Costs, productivity, and the unit costs for Account 106 are
listed below:
     1.   Labor and Equipment
     2.   Productivity
          Installation Unit Cost
3.
4.

5.
          Material - seed
            fertilizer & limestone
          TOTAL UNIT COST
$2,311/week
13,500 m2/week
$0.17/m2
$0.20/m2

$0.37/m2
                             276

-------
Hauling, Account 108
               Table B-ll.  LABOR FORCE AND
               EQUIPMENT POOL, ACCOUNT 108
Labor
2 Drivers
1 Laborer
Equipment
Operator
Oiler
TOTAL
Cost,
$/week
1,298
654
825a
726a
1,952
Equipment
2 Trucks
Dozer
(67,113 W)

TOTAL
Cost,
$/week
550
586a

550
 Additional costs for operation of the disposal area.
          Table B-12.  UNIT COST DATA, ACCOUNT 108
Description
Labor and Equipment,
$/week
Productivity ,
mvweek
Unit Cost, $/m
Earth Rock3
Haul
2,502
1,850
1.35
Disposal
4,639
1,850
2.50
Haul
2,502
1,250
2.00
Disposal
4,639
1,250
3.70
aFor slabs it is assumed the in-place volume increases 25
 percent; productivity is assumed to be 4,200 m2/week for
 slabs 0-30 cm thick and 2780 m2/week for slabs 30-45 cm
 thick.
                             277

-------
COST CATEGORY 2
Placement of riprap (land-based),
Account 201.1 (Sheet 1 of 2)	
       Table B-13.  LABOR FORCE AND EQUIPMENT POOL,
         ACCOUNT 201.1  (RIPRAP, STONE AND FILTER)
Labor
Foreman
Equipment
Operator
2 Laborers
1 Oiler
TOTAL
Cost,
$/week
934
825
1,308
726
3,793
Equipment
Hydraulic 3
Backhoe (1.9 m )


TOTAL
Cost,
$/week
1,750


1,750
      Table B-14.  LABOR FORCE AND EQUIPMENT POOL,
      	ACCOUNT 201.1 (COVER STONE)
Labor
Foreman
3 Laborers
Oiler
Equipment
Operator
TOTAL
Cost,
$/week
934
1,962
726
861
4,483
Equipment
Crane .
(5.4 x 10 kg)
Leads

TOTAL
Cost,
$/week
1,100
30

1,130
                            278

-------
       Table B-15.  UNIT COST DATA, ACCOUNT 201.1
Description
Labor and Equipment,
Productivity, m /week
Installation Unit Cost,
$/m3
Material, $/m
TOTAL UNIT COST, $/m3
Riprap
Stone
5,543
925
6.00
16.00
22.00
Filter
5,543
925
6.00
9.50
15.50
Cover
Stone
5,613
300
18.70
13.00
31.70
Background data for Placement
of Riprap  (marine), Account  201.2
        Table B-16.  LABOR FORCE AND EQUIPMENT POOL,
          ACCOUNT 201.2  (RIPRAP STONE AND FILTER)
Labor
Equipment
Operator
Oiler
2 Laborers
Foreman
TOTAL
Cost,
$ /month
4,322

4,066
7,325
5,230
21,443
Equipment
Crane (5.4 x 104kg)
•a
Tug Boat
2 Scows3
Clam (2.3m3)

TOTAL
Cost,
$ /month
4,400
60,000
6,000
664

71,064
^Equipment is fully manned 6 days/week,  8 hours/day.
                             279

-------
          Table  B-17.   LABOR FORCE AND EQUIPMENT POOL,
                  ACCOUNT 201.2 (COVER STONE)	
Labor
Equipment
Operator
Foreman
Oiler
4 Laborers
TOTAL
Cost,
$/month
4,822

5,230
4,066
14,650
28,768
Equipment
4
Crane (5.4 x 10 kg)
Crane Barge
Flat Top Bargea
Tug Boata

TOTAL
Cost,
$/month
4,400
60,000
5,000
60,000

129,400
Equipment is fully manned 6 days/week,  8 hours/day.
        Table B-18.   UNIT COST DATA,  ACCOUNT 201.2
Description
Labor and Equipment
$ /month
Productivity, m /month
Installation Unit Cost,
$/m3
Material, $/m
TOTAL UNIT COST, $/m3
Riprap
Stone
92,507
12,500
7.40
16.00
23.40
Filter
92,507
12,500
7.40
9.50
16.90
Cover
Stone
158,168
3,000
52.70
13.00
65.70
                             280

-------
Steel Sheet piling  (land),
Account 202.1
               Table B-19.  LABOR FORCE AND
              EQUIPMENT POOL, ACCOUNT 202.1
Labor
Foreman
2 Equipment
Operators

2 Oilers

4 Pile Drivers
TOTAL
Cost,
$/week
934
1,686


1,452

3,300
7,372
Equipment
Crane (5.4 x 104kg)
Hammer (Diesel)

Leads & Misc.

Air Compressor
(25 iri3/min.)
TOTAL
Cost,
$/week
1,100
300

150

350

1,900
        Table B-20.  UNIT COST DATA, ACCOUNT 202.1
Description
Labor and Equipment,
$/week
2
Productivity, m /week
Installation Unit Cost,
$/mZ
2
Material, $/m
2
TOTAL UNIT COST, $/m
j
Application
Permanent
9,272
500
18.55
50.00
68.55
Temporary
9,272
300
30.90
10.00
40.90
                             281

-------
Steel sheet piling (marine),
Account 202.2
               Table B-21.  LABOR FORCE AND
              EQUIPMENT POOL, ACCOUNT 202.2
Labor
4 Pile Drivers
Foreman
2 Laborers
Equipment
Operator
Oiler

TOTAL
Cost,
$ /month
18,480
5,230
7,325
4,822
4,066

39,923
Equipment
3
Crane Barge
Air Compressor
(25 m3/min.)
Hammer (Diesel)
Leads & Misc.
Tug Boat3
Flat Top Bargea
TOTAL
Cost,
$/month
60,000
1,400
1,200
600
60,000
5,000
128,200
 Equipment is fully manned, 6 days/week, 8 hours/day.
        Table B-22.  UNIT COST DATA, ACCOUNT 202.2
Description
Labor and Equipment,
$ /month
2
Productivity, m /month
Installation Unit Cost,
2
Material, $/m
TOTAL UNIT COST, $/m
Permanent
168,123
3,300
51
50
101
Temporary
168,123
2r200
76.40
10
86.40
                             282

-------
Piles (land), Account 203.1
               Table B-23.  LABOR FORCE AND
              EQUIPMENT POOL, ACCOUNT 203.1
Labor
Foreman
2 Equipment
Operators
2 Oilers
4 Pile Drivers
TOTAL
Cost,
$/week
934
1,686
1,452
3,300
7,372
Equipment
Crane (5.4 x 104kg)
Hammer (Diesel)
Leads & Misc.
Air Compressor
(25 mVmin.)
TOTAL
Cost,
$/week
1,100
300
150
350
1,900
        Table B-24.  UNIT COST DATA, ACCOUNT 203.1
Description
Labor and Equipment ,
$/week
Productivity, in/week
Installation Unit Cost/
$/m
Material, $/m
TOTAL UNIT COST, $/m
Materials
Wood
9,272
1,500
6.18
7.50
13.68
Concrete
9,272
750
12.36
22.00
34.36
Steel
9,272
1,050
8.83
30.00
38.83
Piles  (marine), Account 203.2
               Table B-25.  LABOR FORCE AND
               EQUIPMENT POOL, ACCOUNT 203.2
Labor
4 Pile Drivers
Cost,
$/month
18,480
Equipment
Crane Barge .
(5.44 x 10 kg)
Cost,
$ /month
60,000
                              283

-------
       Table B-25 (continued).  LABOR FORCE AND
             EQUIPMENT POOL, ACCOUNT 203.2
Labor
Foreman
2 Laborers
1 Equipment
Operator
1 Oiler
TOTAL
Cost,
$ /mo nth
5,230
7,325
4,822
4,066
39,923
Equipment

Air Compressor
(25 m3/min.)
Hammer (Diesel)
Tug Boat
Flat Top Bargea
TOTAL
Cost,
$ /month

1,400
1,200
60,000
5,000
128,200
Equipment is fully manned 6 days/week, 8 hours/day.
      Table B-26.  UNIT COST DATA, ACCOUNT 203.2
                                      Materials
Description
Labor and Equipment,
$ /month
Productivity, m/month
Installation Unit Cost,
$/m
Material, $/m
TOTAL COST, $/m
Wood
168,123
6,500
25.85
7.50
33.35
Concrete
168,123
3,500
48.00
22.00
70.00
Steel
168,123
4,500
37.35
30.00
67.35
                          284

-------
COST CATEGORY 3
Installation, Account 301.2
               Table B-27.  LABOR FORCE AND
               EQUIPMENT POOL, ACCOUNT 301.2
Labor
Equipment
Operator
2 Millwrights
1 Pipe fitter
2 Laborers
Foreman
Oiler
TOTAL
Cost,
$/week
861
882
1,017
1,308
934
726
5,728
Equipment
Crane .
(5.4 x 104kg)
Leads




TOTAL
Cost,
$/week
1,100
30




1,130
       Table B-28.  UNIT COST DATA, ACCOUNT 301.2
Description
Labor and Equipment,
$/week
Productivity ,
Pumps/week
Installation Cost,
$/pump
PUMP SIZE (m /sec)
1.4 2.8 8.49 19.8
6,858

3

2,286

6,858

2

3,429

6,858

1

6,858

6,858

1

6,858

                            285

-------
COST CATEGORY 4
Cast-in-place box conduit, Account 402
        Table B-29.  UNIT COST DATA, ACCOUNT 402

Description
Formwork
Concrete Placement
Steel Reinforcing
Finish Work
Unit Cost
$40.90/ra2
83.20/m3
55.40/m3
5.00/m2
Steel conduit and fittings, Account 403
         Table B-30.  UNIT COST DATA, ACCOUNT 403
Description
Field Fabricated Pipe
Shop Fabricated Pipe
Cost, $/kg of Steel
1.60a
1.00
 Material, labor and equipment for erection and welding are
 reflected in the unit cost.
Laying pipe on land, Account 406.2
               Table B-31.  LABOR FORCE AND
               EQUIPMENT POOL, ACCOUNT 406.2
Labor
Equipment
Operator
Oiler
Cost,
$/day
172

145
Equipment
Crane (5.4 x 104kg)

•-
Cost,
$/day
220


                            286

-------
        Table B-32.  UNIT COST DATA, ACCOUNT 406.2

                     (Unit Cost, $/meter)a
Diam. ,
meters
1.52
1.83
2.44
3.05
3.66
4.27
4.88
5.49
6.10
Precast
Concrete
48
52
.'•?
62
77
164
197
247
—
— •"•
Corrugated,
Steel Pipe
56
62
79
99
263
295
328
394
394
Fiberglass
Pipe
44
51
64
79
108
128
154
180
— —
Carbon Steel
Pipe
90
104
125
157
__
__
__
__
-—
 Joint sealing costs and/or connecting costs are included
 in installation prices.


5If the diameter exceeds 3.66 meters, installation costs for
 multiplate pipe are based on installation costs quoted by
 manufacturers.
Laying pipe offshore, Account 407.2
               Table B-33.  LABOR FORCE AND
               EQUIPMENT POOL, ACCOUNT 407.2
Labor
Foreman
2 Equipment
Operators
2 Oilers
5 Laborers
6 Divers
TOTAL
Cost,
$ /month
5,232
9,644

8,131
18,312
23,500
64,819
Equipment
2 Cranes (on land)
(5.4 x 104kg)
a.
Flat Top Barge
Lay Bargea
Tugboat

TOTAL
Cost,
$ /month
8,800

5,000
60,000

60,000
133,800
^Equipment is fully manned 6 days/week, 8 hours/day.

                              287

-------
      Table B-34.  MONTHLY OUTPUT DATA, ACCOUNT 407.2
Diam.
meters
1.52
1.83
2.44
3.05
3.66
3.96
4.88
5.49
6.10
Precast
Concrete
351
351
293
234
146
146
146
—
—
Corrugated
Steel Pipe
439
439
365
365
292
292
220
220
220
Figerglass
Pipe
640
640
550
550
457
457
365
365
— —
Carbon
Steel Pipe
439
365
365
292
292
220
220
220
— —
Laying pipe offshore, Account 407.2


      Table B-35.  UNIT COST DATA, ACCOUNT 407.2

                  (unit cost, ($/m) )a
Diam. ,
meters
1.52
1.83
2.44
3.05
3.66
3.96
4.88
5.49
6.10
Precast
Concrete
566
566
678
849
1,360
1,360
1,360
—
~*
Corrugated
Steel Pipe
452
452
544
544
680
680
903
903
903
Fiberglass
Pipe
310
310
361
361
435
435
544
544
— —
Carbon
Steel Pipe
452
544
544
680
680
903
903
903
—
 For water depths greater than 14 meters, it was assumed
 production was curtailed by 20 percent.  The data presented
 in Table B-36 are for water depths less than 14 m.  An ad-
 justment factor is given in Figure 407.2.
                              288

-------
Background data Sheet for
dewatering, Account 406.5
           Table B-36.   PUMPING EQUIPMENT AND
               LABOR COST, ACCOUNT 406.5
Labor
1 Oiler





Cost,
$/week
726





Pump Capacity,
m3/min .
.252
.630
1.260
2.520
5.670
7.875
Cost
$/week
72
86
110
175
289
408
 *The unit  cost for dewatering, per meter of pipe installed,
  is calculated by dividing the assumed  laying rate for
  each  pipe material into the  pumping  costs  (not shown).
                              289

-------
COST CATEGORY 6
Installation of nozzles into
a tunnel diffusely Account 602.3
               Table B-37.  LABOR FORCE AND
               EQUIPMENT POOL, ACCOUNT 602.3
Labor
Foreman
Master
Mechanic
3 Equipment
Operators
2 Oilers
2 Pile Drivers
4 Laborers
2 Divers
Tenant



TOTAL
Cost,
$/month
9,714
8r580

26,860

15,100
17.160
j
27,206
14,560
8,580



127,760
Equipment
Platform
Derrick
Big Bore Drilling
Rig w/Drill Wt.
& Boring Unit
2 Compressor Units
(25 m3/min. )
Flat Top Barge
Cherry Picker
4
Crane (5.4 x 10 kg)
Concrete Pump
(1 wk/month
-a
Tug Boat
TOTAL
Cost,
$ /month
70,000
25,000
75,000


2,800

5,000
1,500
4,400
500

60,000
244,200
 Equipment is fully manned 6 days/week, 12 hours/day-
       Table B-38.   UNIT COST DATA, ACCOUNT 602.3
Description
Labor and Equipment,
$/month
Productivity ,
nozzle/month
Installation Unit Cost,
$/nozzle
Rounded Unit Cost
$/nozzle
0-6m
Depth
371,960
3
123,990
124,000
6m to
15m Depth
371,960
2
185,980
186,000
Over 15m
Depth
371,960
1
371,960
372,000
                             290

-------
COST CATEGORY 7
Structural concrete,
Accounts 701.1 and 701.2
            Table B-39.  COST FOR COMPONENTS OF
      STRUCTURAL CONCRETE, ACCOUNTS 701.1 AND 701.2
Component
Placement, $/m
Formwork, $/m
Finishing, $/m
Sub-Total for 3
Concrete Work, $/m
Reinforcing, $/kg
Group Number
1
63
166
76

305
1.06
2
63
97
_1P.

180
.90
3
63
15
—

78
.90
Concrete marine, Account 702
               Table B-40.  LABOR FORCE AND
               EQUIPMENT POOL, ACCOUNT 702
Labor
4 Laborers
Foreman

TOTAL
Cost,
$/month
14,650
5,230

19,880
Equipment
Crane Barge
w/two cranes
Tug Boat
Hopper , truck
Flat Top Barge
TOTAL
Cost,
$ /month
60,000
60,000
500
5,000
125,500
Equipment if fully manned 6 days/week, 8 hours/day,
                             291

-------
Costs, productivity, and the unit cost for Account 702 are
listed below:
1.
2.
3.
4.
5.
          Labor and Equipment
          Productivity
                        $145,38!0/month
                        4,000 m /month
Installation Unit Cost  $36.30/m
Material                $50/m
TOTAL UNIT COST         $86.30/m
Grouting, Account 703
               Table B-41.  LABOR FORCE AND
               EQUIPMENT POOL, ACCOUNT 703
Labor
Foreman
Driller
4 Laborers
Equipment
Operator
Oiler
TOTAL
Cost,
$/week
898
825
2,616
825
726
5,890
Equipment
Air Compressor
(25 mVmin.)
Track Drill
(14 cm)
Concrete pump

TOTAL
Cost,
$/week
350
344
500

1,194
Costs, productivity, and the unit cost for Account 703 are
listed below:
     1.   Labor and Equipment
     2.   Productivity
     3.   Installation Unit Cost
     4.   Material Cost
            (1:1 cement grout mix)
     5.   TOTAL UNIT COST
                               $7,084/week
                               40 m /week
                               $177.10/m3
                               $54.80/m3
                               $231.90/nf
                             292

-------
COST CATEGORY 8
Placement of fill  (land), Account  802.1
        Table B-42.  LABOR FORCE AND EQUIPMENT POOL,
        	ACCOUNT 802.1  (GROUP 1)
Labor
Equipment
Operator
Laborer
Foreman
Oiler
TOTAL
Cost,
$/week
825
654
898
726
3,103
Equipment
Grader



TOTAL
Cost,
$/week
300



300
        Table B-43.  LABOR FORCE AND EQUIPMENT POOL,
                   ACCOUNT 802.1  (GROUP 2)
Labor
Foreman
Equipment
Operator

Oiler
4 Laborers
TOTAL
Cost,
$/week
898
825


726
2,616
5,065
Equipment
4 Hand
Compactors
Industrial
tractor with
loader and
backhoe
TOTAL
Cost,
$/week
352

516



868
                             293

-------
        Table B-44.  LABOR FORCE AND EQUIPMENT POOL,
                   ACCOUNT 802.1 (GROUP 3)
Labor
Foreman
2 Equipment
Operators
Oiler
TOTAL
Cost,
$/week
898
1,650
726
3,274
Equipment
Dozer (67,113 W)
Vibratory Rollera
(towed)

TOTAL
Cost,
$/week
586
480

1,066
 Add $163 for a self-propelled sheepsfoot roller used for
 compaction of earth.
        Table B- 45.  UNIT COST DATA,  ACCOUNT 802.1
                                    (Group Number)
Description
Labor and Equipment,
$/week
Productivity, tti /week
UNIT COST, $/m3
1

3,403
3,000
1.13
2

5,933
1,800
3.30
3
Earth*
4,503
2,500
1.80
Gran . °
4,340
2,500
1.74
 Self propelled sheepsfoot roller.
Vibrating roller (towed).
                           294

-------
Placement of fill  (marine), Account 802.2
               Table B-46.  LABOR FORCE AND
               EQUIPMENT POOL, ACCOUNT 8 02; 2
Labor
Foreman
Equipment
Operator
Oiler
2 Laborers
TOTAL
Cost,
$ /month
5,230
4,822

4,066
7,325
21,443
Equipment
Crane (5.4 x 104kg)
Tug Boata
2 Scowsa
Clam (2.3m3)
Crane Barge
TOTAL
Cost,
$ /month
4,400
60,000
6,000
668
60,000
71,068
 Equipment is fully manned 6 days/week, 8 hours/day.

 3Crane barge for filling offshore cofferdam.
        Table B-47.  UNIT COST DATA, ACCOUNT 802.2
                                  Placement^
Description
Labor and Equipment,
$/month
Productivity, m /month
UNIT COST, $/m3a
Dumped
92,511
12,800
7.20
Offloaded
152,511
13,600
11.20
aUnit cost for backfill with  side cast material is assumed
 to equal 75 percent of excavation  costs  for a firm
 material or $4.62/m3.
                             295

-------
COST CATEGORY 9
Earth excavation  (land), Account  901.1
        Table B-48.  LABOR FORCE AND EQUIPMENT  POOL,
         	ACCOUNT 901.1  (GROUP  1)	
Labor
Equipment
Operator
Foreman
Laborer
TOTAL
Cost,
$/week
825
898
654
2,377
Equipment
Hydraulic Backhoe
(.76 m3)


TOTAL
Cost,
$/week
753


753
         Table B-49,  LABOR FORCE AND EQUIPMENT POOL,
         	ACCOUNT 901.1  (GROUP 2)	
Labor
Foreman
Equipment
Operator
Oiler
Laborer
TOTAL
Cost,
$/week
934
861
726
654
3,175
Equipment
Crane (5.44 x 104kg)
Clam (2.3 m3)


TOTAL
Cost,
$/week
1,100
167


1,267
                            296

-------
        Table B-50.  LABOR FORCE AND EQUIPMENT POOL,
        	ACCOUNT 901.1  (GROUP 3)
Labor
Foreman
2 Equipment
Operators
2 Oilers
Laborer
TOTAL
Cost,
$/week
934
1,650
1,452
654
4,690
Equipment
2 Scrapers
(15.2 m3)
Push Dozer
(223,710 W)

TOTAL
Cost,
$/week
4,414
990

5,404
        Table B-51.  UNIT COST DATA, ACCOUNT 901.1
Description
Labor and Equipment ,
$/week
Productivity, m3/week
UNIT COST, $/m3
Group Numbers
1
3,130

500
6.26
2
4,442

1,000
4.44
3
10,094

7,500
1.35
Earth excavation  (marine). Account 901.2
        Table B-52.  LABOR FORCE AND EQUIPMENT POOL,
                   ACCOUNT 901.2  (HARD MATERIAL)
Labor
Foreman


TOTAL
Cost,
$/month
15,691


15,691
Equipment
Tug Boata
Crew Boata
Dipper Dredge3
TOTAL
Cost,
$ /month
100,000
13,000
270,000
383,000
Equipment is fully manned 24 hours/day, 6 days/week,

                             297

-------
       Table B-53.  LABOR FORCE AND EQUIPMENT POOL,
            ACCOUNT 901.2 (FIRM OR SOFT MATERIAL)
Labor
Foreman
TOTAL
Cost,
$/month
15,691
15,691
Equipment
Clamshell Dredgea
Tug Boata
Crew Boata
TOTAL
Cost,
$/month
180,000
100,000
13,000
293,000
Equipment is fully manned 24 hours/day, 6 days/week.
      Table B-54.  LABOR FORCE AND EQUIPMENT POOL,
      	ACCOUNT 901.2  (DISPOSAL)
Labor
Equipment
Operator
Oiler
Laborer
TOTAL
Cost,
$/month
14,465
12,197
10,987
37,649
Equipment
Crane (5.44 x 104kg)
3 Scows (1500 m3)a

TOTAL
Cost,
$ /month
4,400
15,000

19,400
Equipment is fully manned 24 hours/day,. 6 days/week.  The
scows are towed to shore using the tug boats listed in
tables B-53 and B-54.
  Table B-55.  UNIT COST DATA, ACCOUNT  901.2  (SIDE  CAST)
Description
Labor and Equipment,
$ /month
Productivity, m /month
UNIT COST, $/month
Hard
Material
398,691
50,000
7.97
Firm
Material
308,691
50,000
6.17
Soft
Material
308,691
100,000
3.09
                            298

-------
                Table B-56.  UNIT PRICE DATA,
               ACCOUNT 902  (ONSHORE DISPOSAL)
Description
Labor and Equipment
$/month
Productivity, m /month
UNIT COST, $ /month
Hard
Material
455,740

50,000
9.11
Firm
Material
365,740

50,000
7.31
Soft
Material
365,740

100,000
3.66
Rock excavation  (land), Account 902.1
               Table B-57.  LABOR FORCE AND
               EQUIPMENT  POOL, ACCOUNT 902.1
Labor
Foreman
2 Equipment
Operators
Driller
Blaster
4 Laborers
2 Oilers
TOTAL
Cost,
$/week
934
1,686
825
800
2,616
1,452
8,313
Equipment
Crane (5.4 x 104kg)
Clam Bucket
(2.3m3 rigged)
Track Drill (14 cm)
Air compressor
(25,5. nr/min.)

TOTAL
Cost,
$/week
1,100
167
344
350

1,961
                             299

-------
         Table B-58.   UNIT COST DATA, ACCOUNT 902.1
Description
Labor and Equipment/
$/week
Productivity, m /week
Unit Cost, $/m3
Material (powder) , $/m
TOTAL UNIT COST, $/m3
Wide Trench
> (75 meters)
10,274

575
17.86
3.00
20.86
Narrow Trench
< (25 meters)
10,274

400
25.70
3.00
28.70
Rock excavation (marine), Account 902.2
               Table B-59.   LABOR FORCE AND
               EQUIPMENT POOL, ACCOUNT 902.2
Labor
Foreman
Equipment
Operator
Oiler
Laborer

TOTAL
Cost,
$ /month
15,691
14,465

12,197
10,987

53,340
Equipment
Drill Boata
Powder Scowa
Tug Boat
Dipper Dredge3
Crewboat
Crane (5.44 x 104kg)
TOTAL
Cost,
$/month
225,000
3,000
60,000
270,000
13,000
4,400
575,400
 Equipment is fully manned 24 hours/day, 6 days/week.
                           300

-------
Costs, productivity, and the unit cost for Account 902.2 are
listed below:
     1.   Labor and Equipment        $628,740/month
     2.   Productivity               $12,000 m /month
     3.   Installed Unit Cost        $52.40/m3
     4.   Material  (powder)           $3.00/m3
     5.   TOTAL UNIT COST            $55.40/m3
                              301

-------
                                TECHNICAL REPORT DATA
                         (Please read Instructions on the reverse before completing)
1. REPORT NO
 EPA-600/2-76-078
 2.
4. TITLE AND SUBTITLE
 Cost Estimating Methodology for Once-Through
 Cooling Water Discharge Modifications
                            3. RECIPIENT'S ACCESSION-NO.
                            5. REPORT DATE
                             March 1976
                            6. PERFORMING ORGANIZATION CODE
7. AUTHOR(S)

John W. Hayden and Richard Mayer
                            8. PERFORMING ORGANIZATION REPORT NO.
9. PERFORMING ORGANIZATION NAME AND ADDRESS
Acres American, Inc.
The Liberty Bank Building
Buffalo, New York  14202
                            10. PROGRAM ELEMENT NO.

                            1BB392; ROAP 21AZU-021
                            11. CONTRACT/GRANT NO.

                            68-03-2053
 12. SPONSORING AGENCY NAME AND ADDRESS
 EPA, Office of Research and Development
 Industrial Environmental Research Laboratory
 Research Triangle Park, NC 27711
                            13. TYPE OF REPORT AND PERIOD COVERED
            13. TYPE OF REPORT AN!
            Final; 6/74-6/75
                            14. SPONSORING AGENCY CODE
                             EPA-ORD
15. SUPPLEMENTARY NOTES pTO^ci officer for this report is James P. Chasse, Environmental
 Research Laboratory, Corvallis, Oregon 97330.
 is. ABSTRACT Tne repOrt gives a, methodology for evaluating the engineering and cost
 implications of constructing or modifying once-through cooling water discharge  sys-
 tems of thermal-electric generating plants within the contiguous U.S. The procedures
 give (to persons not skilled in cost engineering) a means of preparing preliminary
 cost estimates from  conceptual or design drawings.  The user should, however, have
 a technical background and be familiar with once-through cooling water discharge
 systems.  Principal  construction elements of discharge system construction and
 modification are identified and grouped into categories.  Materials and installation
 methods are discussed for each construction element. Data is given on labor, mater-
 ials, equipment, and productivity assumed in unit cost development.  A step-by-step
 procedure is given for: (1) estimating construction costs, and (2) resolving construc-
 tion costs  into project and annual costs.  An example is shown using the methodology;
 the result  is compared with actual construction costs for modifications to an existing'
 discharge  system.
17.
                             KEY WORDS AND DOCUMENT ANALYSIS
a.
                DESCRIPTORS
                b.lDENTIFIERS/OPEN ENDED TERMS
                                                                     cos AT i Field/Group
Pollution
Cost Estimates
Cost Engineering
Electric Power Plants
Cooling Water
Revisions
Design
Construction
 Costs
Materials Esti-
 mates
Installing
Once-through Cooling
13B
14A,05A
                         10B
                         13A
                                13M,05C

-------