United States
                 Environmental Protection
                - Agency
f/EPA         Report  of  Audit
                         Report of Audit of
                     EPA, Region 8's Administration
                   of Superfund Cooperative Agreements

                   Audit Report No. E5eH7-08-0005-71992
                         September 30, 1987

-------
                               TABLE OF CONTENTS
SCOPE AND OBJECTIVES  	    1

SUMMARY OF FINDINGS 	    2

ACTION REQUIRED 	    4

BACKGROUND 	    4

FINDINGS AND RECOMMENDATIONS

     1 - MONITORING OF PRE-REMEDIAL AND REMEDIAL
         FUNCTIONS REQUIRES REGIONAL ATTENTION	    7

     2 - REGIONAL ADMINISTRATION OF COOPERATIVE
         AGREEMENTS SHOULD BE STRENGTHENED 	   26

     3 - REGIONAL OVERSIGHT OF RECIPIENT FINANCIAL
         MANAGEMENT SYSTEMS NEED IMPROVEMENT	   36

ATTACHMENT 1 - REGION 8 RESPONSE TO DRAFT AUDIT REPORT	   42

REPORT DISTRIBUTION	».	   63

-------
               UNITED  STATES ENVIRONMENTAL PROTECTION AGENCY
                  OFFICE OF THE INSPECTOR GENERAL FOR AUDITS
                                WESTERN DIVISION

                            2^^ Main Street, Suite 22Q
                             San Francisco, CA 94105
                                  415 974-7084
                                      September 30, 1987
SUBJECT:
FROM:
TO:
          Report on Audit of EPA, Region 8's
          Administration of Superfund
          Cooperative Agreements
          Audit Report No. E5eH7-08-0005-71992
                       lgr-jftcucww ^^J^^t^
          Truman R. Bee
          Divisional Inspector General for Audit
          Western Divisioa

          John Shearer
          Regional Administrator
          EPA, Region 8
SCOPE AND OBJECTIVES

We have performed an audit  of the EPA,  Region 8's administration of the Super-
fund cooperative agreements awarded to  states under the Comprehensive Environ-
mental Response, Compensation,  and Liability Act of  1980.   The  primary objec-
tives of our audit were to:

     - Determine the adequacy of  Regional  policies,  procedures,  and practices
       for administration and management of cooperative agreements under CERCLA.

     - Review  for  compliance of  Regional policies,  procedures,  and practices
       with National Superfund guidance,

     - Ascertain that  the  objectives of the  cooperative  agreements were being
       achieved.

Our review  of the  management and supervision  of  the cooperative agreements
covered the period August 24, 1982 through February 28, 1987.

Our examination was made in accordance with Standards for Audit of Governmental
Organizations, Programs, Activities, and Functions issued  by  the  Comptroller
General of  the United States,  and accordingly,  included such  tests of  the
records and  other  auditing procedures  as were considered  necessary  in  the
circumstances.  We  reviewed the  Region's system of  internal controls relating
to the management  and  supervision of the cooperative agreements  to the extent
necessary to accomplish  the stated objectives of the audit.   Internal control
deficiencies noted  in  the  above  areas have  been included in the  "Summary of
Findings" and  "Findings and Recommendations"  sections of this report.

-------
SUMMARY OF FINDINGS

We concluded that the Region needed to more effectively manage the $6.4 million
of cooperative agreements awarded to date.  Since  the activities addressed in
the agreements covered serious hazardous waste  conditions,  it is important that
increased regional attention be directed to the agreements.  We found that pre-
remedial and remedial work were not performed timely and effectively, and the
completion of remedial work at four environmentally sensitive National Priori-
ties List (NPL) sites was significantly behind  schedule.  We also noted a lack
of aggressiveness in the Region's monitoring of other cooperative agreement
requirements, and an absence of regional guidance  to its Regional Project Man-
agers.  Further, the audit disclosed a need for improved regional procedures
for monitoring the financial.management systems utilized by the cooperative
agreement recipients.  In general, we attribute these conditions to a need for
more regional involvement in the states' cooperative agreements.

The results of our review are summarized in the following subparagraphs, and
detailed, along with related recommendations, in the "Findings and Recommen-
dations" section of this report.

1 - MONITORING OF PRE-REMEDIAL AND REMEDIAL FUNCTIONS REQUIRE REGIONAL ATTEN-
TION

The Region has not developed adequate procedures for monitoring the pre-reme-
dial and remedial functions included in the cooperative agreements to assure
that they were performed in a timely and effective manner.  As a result, we
noted that the pre-remedial functions, which included preliminary assessments
(PAs), site inspections  (Sis), and Hazard Ranking  System  (HRS) scoring have
required an average of more than two years to complete, and in some cases, have
remained incomplete.  In addition, the reliability of some of the pre-remedial
work has been questionable.  These conditions have precluded timely determina-
tions as to whether additional hazardous waste  sites should be included on the
Superfund National Priority List  (NPL), and also delayed the initiation of sub-
sequent clean-up actions.  In the remedial area, delays of up to 5 years were
experienced in completing the Remedial Investigations/ Feasibility Study (RI/FS)
at four sites.  Two of the delayed projects were the Milltown Reservoir site in
Montana, and the Arsenic Trioxide site in North Dakota, which were experiencing
problems with arsenic in the drinking water supplies.  In addition, a decision
was delayed on the proposed actions necessary to clean-up the arsenic, copper,
barium, lead, and zinc which were found at the  Silver Bow Creek NPL site in
Montana.  Further, little progress had been made on the RI/FS for clean-up of
the wind blown tailings and contaminated groundwater identified at the Sharon
Steel site in Utah.  All of the above NPL sites represent significant environ-
mental hazards, which require priority attention to assure  that further reme-
dial action is initiated in a timely manner.  We believe that the above defi-
ciencies have been allowed to continue because  the Region had not established
an aggressive policy of monitoring the performance aspects  of the cooperative
agreements  (see page 7).

-------
2 - REGIONAL ADMINISTRATION OF COOPERATIVE AGREEMENTS SHOULD BE STRENGTHENED

The Region  needed to  improve its procedures  for managing  the administrative
aspects of  its  Superfund cooperative  agreements.   Without adequate procedures
there was no assurance that maximum environmental benefits will be derived from
the $6.4 million of  Superfund cooperative agreement funds.  The inadequate re-
gional actions along with recipient deficiencies have resulted in a relatively
poor performance  under the  cooperative agreements.  This condition was  pri-
marily attributable  to the fact  that the  Region  had  not:   (i)  taken an  aggres-
sive role  in assuring  the completion of the  required cooperative  agreement
work; (ii)  provided  the  Regional  Project Managers  with  adequate  guidance  to
perform their responsibilities;  (iii)  prematurely awarded  a cooperative agree-
ment to a  recipient  that did  not meet the financial, technical, and experience
requirements described in 40  CFR 30.301;  (iv)  required recipients to establish
the site specific  schedules  required by EPA guidance;  (v) maintained the Com-
prehensive Environmental  Response, Compensation, and Liability Information Sys-
tem (CERCLIS) in  an" adequate manner; and  (vi) established an  adequate  working
relationship with  the State  of Utah for performance  of the cooperative agree-
ment goals  and  objectives.   We  believe that  improvements in the  above areas
will require that  the Region  more aggressively monitor the recipients' coopera-
tive agreement activities (see page 26).

3 -  REGIONAL OVERSIGHT OF RECIPIENT FINANCIAL MANAGEMENT SYSTEMS NEED IMPROVE-
MENT

Regional oversight of recipient  financial management systems required improve-
ment to assure  that  the systems were  adequately maintained.   The  Region was
unaware that the  recipients  were not  in  compliance with  the  Letter of Credit
(LOG) User's Manual, and therefore did not have the information needed to pro-
perly manage and disburse Federal funds.   In addition, our audit disclosed that
additional review  of the  recipients' accounting  systems was necessary to assure
the proper  accountability of the  $6.4 million  of  cooperative agreement funds
which have  been awarded  to date.   Specificially, we found that the Cash Trans-
action Reports  (SF-272) had not been submitted within the  required time frames,
and that the Financial Status Reports  (FSR) were either not submitted  or sub-
mitted late.  The  FSR problems  were  previously reported  in an EPA,  Office  of
the Inspector General (OIG)  report' issued January  27,  1986.  Although the Re-
gion provided assurances that corrective  action would  be  taken,  the deficien-
cies have  continued  to exist.  Additionally, we found  that the regional staff
were making  changes  to  recipients'  SF-272 Reports  without properly notifying
the certifying  official  of   the alterations.   We consider  this  to  be a poor
internal control  procedure.   The  audit also disclosed that the  Region needed
to strengthen  its review of recipients'  accounting and  reporting  systems  to
assure that  all deficiencies were  appropriately detected and  corrected.  In
this respect, it  was noted that major deficiencies  in  the State  of Utah's ac-
counting system and  LOG  procedures were not  identified  during a recent  regional
review.  We  attributed the above conditions to  a general  lack of regional at-
tention to the  financial aspects of the cooperative  agreements, and  inadequate
monitoring of  the recipients'  financial management  systems  (see  page  36).

-------
A draft audit report was provided to the Region on August 12, 1987, and the Re-
gion responded  to the draft report on  September  21,  1987.   An  exit conference
was held with  regional representatives  on September 22, 1987.   The Region gen-
erally concurred  with the findings and recommendations  contained  in the draft
report.  However,  in several instances, the Region provided additional comments
to clarify the  information provided  in  the audit  report.  In this respect, the
Region commented  that  a number of factors contributed  to  its management defi-
ciencies during the period of  the  audit.   These  factors included:   (i) general
start-up problems  with the  relatively  new Superfund program; (ii)  organization
changes within  EPA and the  Region;  (iii)  inadequate  staffing  at  all levels,
(iv) a turnover of the technical  staff;  (v)  an uncertainty of  funding during
the 18 month Superfund re-authorization  slow-down?  (vi) a  continual  shifting
of national  priorities; and (vii)  a program speed-up  after re-authorization.
We acknowledge the Region's  comments,  but believe that more effective  regional
management procedures  could have  reduced  the impact  of  the  above  factors.

The Region's comments have been summarized and incorporated into  each finding
in the  "Findings  and  Recommendations11  section  of this report,  along  with ap-
propriate auditor  comments,  as necessary.  In addition, the Region's  complete
response has  been includes  as • Attachment 1  to this report.   Certain of the
comments included  in the Region's  response to the draft  report  resulted in our
making revisions to the final audit report.

ACTION REQUIRED

In accordance with EPA Directive 2750,  the Action Official is  required to pro-
vide this  office  a  written  response of  the  actions taken  or  proposed  to be
taken on  the audit  recommendations  within 90 days  of the  audit  report date.

BACKGROUND

The "Superfund"  program was  established  by  the Comprehensive  Environmental
Response, Compensation, and  Liability  Act of 1980 (CERCLA),  Public Law 96-510,
enacted on  December  11, 1980.   The Superfund program  was created  to protect
public health and  the  environment from release, or threat of release, of hazard-
ous substances  from  abandoned hazardous  waste sites  and other sources  where
response was not  required  by other Federal laws.   A Trust Fund  was established
by CERCLA to provide  funding  for  responses ranging from control  of emergency
situations to  provision of permanent remedies  at uncontrolled  sites.  CERCLA
authorized a $1.6 billion program financed  by  a five-year environmental tax
on industry and some general revenues.   CERCLA requires that response, or pay-
ment for response, be sought from those responsible for the problem, including
property owners, generators, and transporters.

CERCLA was  revised and expanded by the Superfund Amendments and Re-authoriza-
tion Act of 1986  (SARA),  Public Law  99-499, enacted October 17,  1986.   SARA
reinstituted the  environmental tax  and  expanded the taxing mechanism available
for a  five-year period..  It authorized an $8.5 billion program  for the 1987-
1991 period.   The Trust 'Fund  was renamed the Hazardous  Substance Superfund.

-------
The basic  regulatory blueprint  for  the Superfund Program is the  National  Oil
and Hazardous Substances  Contingency Plan (NCP),  40  CFR Part 300.   The NCP was
first published  in  1968 as part of  the Federal Water  Pollution Control Plan,
and has been  substantially revised to meet CERCIA requirements.   The NCP lays
out two broad categories  of response:   removals  and  remedial response.   Re-
movals are relatively  short-term responses, and modify an earlier program un-
der the Clean Water Act.   Remedial  response  is  long-term planning and action
to provide permanent remedies for serious abandoned  or uncontrolled hazardous
waste sites.

CERCLA recognizes that the Federal  Government can only  assure  responsibility
for remedial  response  at a limited  number of sites  representing  the greatest
public threat.   It therefore  requires  the maintaining of an  NPL, which must be
updated at least annually.  The NPL is composed primarily of  sites which have
been ranked on  the  basis  of  a  standard  scoring system,  which  evaluates their
potential threat  to public health.   In  addition,  each  State  was  allowed to
designate its  highest   priority site,  without regard  to the  ranking  system.

CERCLA section 104(c)(3)  provides  that no remedial actions  shall  be taken un-
less the state  in which the release occurs enters into a contract or coopera-
tive agreement with  EPA to provide certain assurances,  including cost sharing.
At most sites, the  state must pay 10 percent  of the  costs of  remedial action.
Pre-remedial activities  (preliminary  assessments,  site  inspections)  remedial
planning (remedial investigations, feasibility studies, remedial designs),  and
removals may  be  funded at 100  percent by EPA.   For facilities operated  by a
state or political subdivision at the time of  disposal of hazardous substances,
the state must  pay  at  least  50 percent  of  all response costs, including  re-
movals and remedial planning previously conducted.

Region 8 had awarded 10 cooperative agreements with a total value of about $6.4
million to 5  of the 6 states within  the Region as  of the  date  of our audit
field work.   A  $32,988 cooperative  agreement was subsequently awarded to the
remaining state  (South Dakota)  in  March 1987.  The cooperative  agreements were
awarded by the Region for a variety of purposes including:   (i) the performance
of pre-remedial  tasks,  (ii)  state  lead  for  specific  sites  in   the remedial
stages, and (iii) management assistance during pre-remedial and remedial phases
of the process.   The cooperative agreements awarded by the  Region are identi-
fied below:

-------
  No.             Recipient

V008427     Utah Dept. of Health
V008433     Wyoming Dept. of Environ-
              mental Quality
V008457     North Dakota Dept. of Health
V008414     North Dakota Dept. of Health
V008415     Montana Dept. of Environ-
              mental Sciences
V008430     Montana Dept. of Environ-
              mental Sciences
V008416     Montana Dept. of Environ-
              mental Sciences
V008435     Colorado Dept. of Health
V008459     Colorado Dept. of Health
V008462     Colorado Dept. of Health
 Amount         Purpose

$1,282,046   Multi-Site Coop. Agree.

    63,295   Multi-Site Coop. Agree.
    10,000   Multi-Site Coop. Agree.
   319,033   Arsenic/Trioxide RI/FS

 2,294,996   Silver Bow Creek RI/FS

   101,897   PA/SI Program

 1,091,085   Mi11town RI/FS
   231,845   Multi-Site Mgmt. Asst.
    45,000   PA/SI Program
 1,000,000   South Adams County
Total Program Funding
$6,439,197

-------
                          FINDINGS AND RECOMMENDATIONS

1 - MONITORING OF PRE-REMEDIAL AND REMEDIAL FUNCTIONS REQUIRES REGIONAL ATTENTION


Regional procedures  for  monitoring  the  pre-remedial  and  remedial  functions
specified in  the cooperative  agreements  needed  to  be strengthened  to assure
that the functions were performed in a timely  and effective  manner.   The pre-
remedial functions, which included  preliminary  assessments  (PAs),  site inspec-
tions (Sis),  and hazard  ranking  systems  (HRS)  scoring packages have required
an average of more than two years to complete, and in some cases, have remained
incomplete.  In  addition, the reliability of  some of the pre-reitedial work has
been questionable.  These conditions have precluded timely determinations as to
whether the applicable  hazardous  waste sites should be included on the Super-
fund National Priority  List (NPL),  and also  delayed the initiation  of subse-
quent clean-up actions.  In the  remedial  area, delays of  up to  5 years  were
experienced in completing the Remedial Investigation/Feasibility Studies (RI/FS)
at four environmentally sensitive sites.   Two of the delayed projects included
the Milltown Reservoir  site in. Montana, and the Arsenic Trioxide  site in North
Dakota, which  were experiencing  environmental problems  with  arsenic  in  the
drinking water supplies.   In addition, a decision was  delayed  on  the proposed
actions necessary to clean-up the arsenic, copper, barium, lead, and zinc which
were found at the  Silver Bow Creek NPL site  in Montana.   Further, little pro-
gress had been made on the RI/FS for the wind  blown tailings and contaminated
groundwater problems identified at  the Sharon Steel site in  Utah.  All of the
above NPL  sites  represent  significant  environmental  hazards,  which  require
priority attention to  assure that  further remedial action  is initiated  in a
timely manner.  Vfe believe that the above conditions occurred, in part, because
the Region was  not aggressive  in requiring performance under  the cooperative
agreements.

Background

The Superfund process is described in detail in Subpart F of  40 CFR 300.  This
CFR establishes  the  methods and  criteria  to be  used in determining  the ap-
propriate response to  be followed when hazardous substances are  released,  or
there are substantial threats of release to the environment.  The ultimate goal
of a Superfund action  is to initiate a permanent remedy  for the affected hazard-
ous waste site.  The  Superfund process can generally  be  divided into the fol-
lowing three phases and their related subphases:

     1.  Discovery and  Ranking  (Pre-remedial)

         - Site  Discovery
         - Preliminary  Assessment
         - Site  Inspection '
         - Immediate Removal (if necessary)
         - Hazard Ranking System Scoring
         - Nomination for National Priority List  (if appropriate)

-------
     2.  Remedial Planning

         - Remedial Investigation
         - Feasibility Study
         - Record of Decision
         - Remedial Design

     3.  Remedial Implementation

         - Remedial Action
         - Initial Remedial Measures
         - Operation and Maintenance

The Region has  awarded  10 cooperative agreements  with a total value  of about
$6.4 million.   The  cooperative agreements cover a variety of  areas,  including
the pre-remedial program, remedial action at a particular site, or pre-remedial
and remedial  action at multiple  sites within  a  state.   With South  Dakota's
receipt of a  cooperative agreement in March  1987, each state in  Region 8 now
has a cooperative agreement  for performance of at least  part  of  the pre-reme-
dial program.   According  to the Region's  latest  CERCLIS report, dated  February
11, 1987, there were  804 hazardous waste  sites in the Region, 38  of which are
listed on the NPL.   The  above  report included about  170 sites on which a PA
had not  been  performed,  and  538 which could potentially require an  SI.  The
enactment of  the  Superfund Amendments and  Reauthorization Act of 1986 (SARA)
established new priorities for the Superfund  program.  As a  result of  the gen-
eral dissatisfaction with the slow  progress  of the  program,  SARA included a
requirement that all  sites listed on  CERCLIS at the  time of  its  enactment on
October 17, 1986, had  to have a PA completed by January  1988, an  SI  completed
by January 1989,  and an  HRS  scoring package within  four years of  enactment.

Completion of Preliminary Assessments Are Behind Schedule

Our review disclosed that the completion  of PAs  required under the cooperative
agreements awarded to the States of Utah, Wyoming, and South Dakota were behind
schedule.  In addition,  we found  that, on a region-wide basis, an average of
449 days elapsed  between the dates that  the  PA  report was  issued and the date
that the next pre-remedial step, an SI field visit,  was performed.   These de-
lays have precluded the Region  from making timely assessments  of  the degree of
severity of the hazardous waste problems at the affected sites.

The PA  is  the  first  step in the  actual  site evaluation process.  The PA at-
tempts to evaluate  the  magnitude of the  potential hazard,  identify the source
and the  nature  of the  release,  and  identify potentially responsible  parties.
A site must be  listed on the CERCLIS  before  the PA can be  performed.   In con-
ducting the PA, some  or alj of  the  following data gathering techniques may be
performed:  (i) interviews with government personnel, (ii) review of govern-
ment files,  (iii)  review  of  geological,  hydrological,  and  topographical data
available from  government and other sources,   (iv) review of well  logs, meteo-
rological, land use and planning data, and (v)  a  perimeter (off-site) inspec-
tion.  After  the PA is  completed,  the Region  must  determine  whether or not the

-------
site merits further  action,  or if  it  should be placed in a  pending category.
If further action  is to be  initiated,  the next step  in  the  pre-remedial pro-
cess would be the completion of an SI.

Utah Cooperative Agreement.  The  cooperative agreement provided  for  the com-
pletion of 21  PAs  by September 1985.   However,  none  of the PAs were completed
as of  that  date, and  the performance  period was extended to  September 1986.
While the state  had  prepared draft copies of all  of  the  PAs  by the end of the
revised performance  period,  only three  PAs had  been approved  by EPA.   One
factor contributing  to the  state's  delays was  a  lack of adequate  control of
the specific  action  dates that  the individual  PAs  were  to  be  performed  and
submitted for  review.   As a  result,  we  noted  that  13, or more  than  half, of
the PAs were  submitted to the Region  simultaneously  on March  28,  1986.   Un-
fortunately, the Region reciprocated by  returning the results  of its reviews
on 17 PAs to the state on June 10, 1986.   Neither the state nor the Region had
the resources to deal with a periodic heavy workload caused by the simultaneous
submission of large groups of PAs.  We  believe that this workload problem could
have been avoided  if the Region  and the  state  had prepared a mutually accept-
able delivery schedule for  the PA reports at the  beginning of  the year.   Such
a schedule would have  helped spread submission  of these  reports  on an orderly
basis over the year.   Even when the PAs were  submitted there were problems with
the timeliness of the  Region's completion of its  reviews.  In this respect, an
average of 150 days were required for the Region to review the PAs submitted by
the state.  To illustrate, the draft PA for the  Lark Tailings site was initial-
ly submitted on  December 5,  1985.  However,  the Region did not comment on the
draft report until June 10, 1986.  A  revised PA  was  resubmitted  by the  state
on September 2,  1986,  or about 271 days  after  its original submission.   As of
September 16, 1986,  the PA had not  yet been approved  by the Region.  Another
illustration of the Region's review delays occurred at the American Barrel Yard
site.  Two draft PAs were submitted by the  state for this site, including an
initial submission in  April  1986.  Neither of  the draft  PAs  had been approved
by the Region as of September 1986.   The draft PAs  indicated  a major health
concern because transient people  had access to the thousands of barrels at this
site, which have shown  a strong presence  of gases.

Wyoming and South Dakota Cooperative Agreements.   The Wyoming cooperative agree-
ment required that a total of  39  PAs be performed.  However,  the state was un-
able to meet  this  commitment.  While the state  had  a fairly active PA program
during the early stages of the cooperative agreement, the Superfund activities
in the state  came  to a virtual halt after the  state's only  cooperative agree-
ment employee  resigned in June  1986.   This  inactivity continued  for about 9
months until the Region authorized the Field Investigation Team (FIT) contrac-
tor to begin  performing  PAs in  the state in an  effort  to  meet  the  SARA re-
quirements.

With respect to  the  South -Dakota cooperative agreement,  we  noted that work on
20 PAs was not performed, because of an 11-month delay in awarding  the coopera-
tive agreement.  The state  requested the agreement in May 1986,  but it was not
awarded until April  1987.  While  the Region ultimately used  the FIT contractor
to perform four  of  the PAs,  the majority of  the PA work was not performed.

-------
Untimely Actions on Completed PAs.  In addition to the delays in completing the
PAs, there were also  delays  in  acting  on the PAs  once they were completed.  In
this regard,  we reviewed  the time taken to initiate action  on the  PAs  com-
pleted for  31 regional sites.  The review,  which included  several  sites from
each state, disclosed that an average of  449 days  elapsed between the date of
the final PA  report and the  date  that  an SI  field visit was initiated.  To il-
lustrate, the Yankton Landfill  in South  Dakota, had a PA completed on September
1, 1981.  The PA report recommended that further remedial action in the form of
an SI be performed.  However, an SI site visit was not initiated until November
7, 1985, or over  4 years  later.  The resultant  SI report was not completed un-
til November  5, 1986, or more than 5 years after the PA report.  Some other ex-
amples of significant delays experienced in  following up on completed PAs  were
as follows:

                                                    No. of Days
                                                 Between Completed
                Site                            PA and SI Field Visit

     Salt Lake City Landfill No. 1 & 2, Utah            2,202
     Whitewood Custom Treaters, South Dakota    .        1,295
     Syro Steel, Utah                                     435
     Standard Oil-Greybull, Wyoming                       364

Many of the problems  concerning the lack of  timely performance of the PAs  were
attributable  to the  fact  that  neither  the  state nor regional  personnel  con-
sidered the PA  process to be of a  high priority.   This has  resulted  in the
performance of  PAs only when spare time was available.  This attitude was a
contradiction of the objectives of the cooperative agreements which established
performance of  PAs and Sis  as important  action  items.  The  PAs  represent an
important part of  the Superfund process, and are  the first step in identifying
and prioritizing  sites,  which may require some form of remedial action.   Ac-
cordingly, we believe they  should  be accorded  sufficient priority  to assure
that they are completed and  acted upon in a timely manner.

Regional Comments and Cur Evaluation

Regional Comments.  The Region stated that  during the  period covered  by the
audit, there  was   no  Headquarters or  regional requirements to  complete  pre-
remedial tasks within a specific time period.  The Region therefore indicated
that its performance  was  not  inconsistent with  any  established agency policy
or procedure.  The Region also commented that its  Strategic Planning and Man-
agement System  (SPMS) targets  were  generally met  for pre-remedial  work.  In
addition, the Region  provided the following specific comments on the various
topics discussed in the finding.

     1.  Completion of Preliminary Assessments Are Behind  Schedule.   The Re-
gion stated that PA and SI work, and listing  new sites on the NPL were very low
priority during the time covered by the  audit.  It stated that the emphasis was
directed towards completing  RI/FS and  remedial efforts at sites already on the
NPL.  In addition, until  SARA was enacted,  there were  no specific time frames
for completion of  the PA  or SI at a particular site.  The Region therefore did
not agree with  our conclusion that the average days cited in the report repre-
sented an untimely situation.
                                      10

-------
     2.  Utah  Cooperative  Agreement.   The Region  stated  that the  Utah-EPA
Memorandum of Understanding included  a mutually agreed upon delivery and review
schedule.  It believed  that this  should help to alleviate many of the problems
experienced  in the past.  The  Region  also anticipated the Memorandum of Under-
standing would be the model  for  agreements with  other states  in  the Region.

     3.  Wyoming  Cooperative  Agreement.  The Region  commented that the status
of pre-remedial work  in Wyoming was at a virtual standstill at the time of the
audit.  It noted  that pre-remedial work  had a very  low  priority.   The Region
also stated  that  the state was within  its  rights not to hire an employee to con-
tinue the Superfund work.

     4.  Untimely Actions on  Completed  PAs.  The Region  explained that there
was no statutory  time requirement for initiating an  SI upon completion of the
PA.  It also stated  that the  level of  staffing at the Region precluded timely
action on all PAs and  Sis.  The  Region further contended that  it  had met its
SPMS targets, and that  all priority sites had been completed during the period
of the audit.  The  Region did not  agree  with the audit  report  statement that
"neither the state nor  regional personnel considered the PA process to be of a
high priority."   The  Region commented  that its SPMS targets had been  met in
this case.

PIG Evaluation.   The  Region's  comments are  acknowledged.  However,  it remains
our position that the average number of days required to  move from PA to a SI
stage is excessive.   We  do not believe  that  the comment  concerning the lack
of Headquarters guidance  is responsive  to our concern.   Effective management
practices dictate that  improvements  be  made whether or not  Headquarters had
provided guidance.  With  the   inclusion of  time frames in SARA,  we agree that
this problem should diminish.

The Region also   asserted that the State of  Wyoming was  clearly  within its
rights to refuse  to hire  a Superfund  person to  complete  the  work under the co-
operative agreement.  While this  may  be the case, we do  not believe that such
an action was within  the spirit of the cooperative  agreement process.  In our
opinion, a state should not be  allowed to  delay  the Superfund cooperative agree-
ment process  indefinitely because  it had not  acted  in a  responsible manner.
We believe that this  is an area  where  the Region must become more aggressive
with the states to assure that the Superfund program continues to move forward.
                                   >
In responding to  our  finding  relating to untimely  action  on completed PAs, the
Region indicated  disagreement  with  our general conclusion that  PAs  were a low
priority.  However, the Region contradicts  itself  in  responding to  our finding
related to delays in  completion of preliminary assessments  under the Utah co-
operative agreement.  In  that  portion of  its response, the Region advised that
PA activity  was a low priority.   In addition, the  Region's comments on the ac-
complishment of its SPMS  targets  were  not relevant  to this  audit.   The audit
covered the  shortfalls  in accomplishing  the goals and  objectives  of  the co-
operative agreement.  As  such, we  did not  review  either the validity or the
accomplishment of the SPMS objectives.   It is obvious, however,  that the SPMS
target goals were more easily  attainable than those provided for in the cooper-
ative agreement.
                                      11

-------
Inadequate Site Inspections

We found that the Sis  being performed in Region 8 were not always accomplished
in accordance with EPA requirements or in a timely manner.  In this respect, we
found problems with  the  quality of the work performed for 7  of  9 Sis reviewed
in Utah and  South Dakota.   Further,  we  noted that an average of more than 10
months was required  to  complete the  SI process.  With  the exception  of the
State of Utah,  which performed  its  own  Sis,  the Sis were,  for  the most part,
being accomplished by  the FIT contractor.  It was  the  intention of the Region
to expand the  states'  participation  in  the  SI process.  If  this is  the case,
additional training  on the  SI process will be required.  In addition, regional
oversight of the  states' performance will have to  be  increased  to assure ade-
quate performance.   Also,  written guidance,  concerning the  performance of the
SI, had not been prepared by the Region.

The purpose of an SI is  to characterize  the problems at a site.   It should also
ascertain what, if any,  further action is necessary,  and determine if the site
should be considered for .inclusion  on  the NPL.   The  major  objectives  are to
(i) determine  if  there  ig, any  immediate  danger  to persons  living  or working
near the site  and if  an immediate  removal  action is  necessary, (ii) provide
sufficient information to develop the most accurate HRS  score,  and (iii) iden-
tify the major sources of contamination.

The steps taken to acquire  the information necessary  for an SI may include the
following: (i)  measurement  of ambient  conditions,  (ii)  documentation  of the
conditions of waste  materials containment, topography,  geology,   and hydrology,
(iii) identification of  local populations  and natural  resource areas, (iv) re-
view of operators records,  (v)  collection  of on and  off-site stream, ground-
water, air,  soil, and leachate samples,  (vi) analysis  of  samples  including
quality assurance  and  quality  control  review of the analysis,  and (vii) pre-
liminary HPS scoring to determine  that adequate data  are available  to score
the site.

Problems With Quality of Sis.  We  reviewed 9  SI  reports and concluded that  7
failed to meet the  requirements of EPA, Office  of Solid Waste and Emergency
Response (OSWER)  Directive   9345.1-1,  dated  December  1985.   This  directive
stated that the two  most important purposes of the SI were to:

     "...!) understand the potential  threat posed by a site—to the extent pos-
sible within the limited scope of the SI, and

     "2) to determine  the need  for  further Superfund  activity  at a hazardous
substance site."

The 9 Sis reviewed included Sis performed by  Utah, as  well as some previously
performed by South Dakota.-  As  indicated, we found that 7  Sis  failed to meet
at least one of the  two  criteria established by the OSWER directive.  The most
common deficiency was  the failure to perform the necessary sampling during the
SI process.  In addition, most of the Sis concluded that additional site test-
ing should be performed.  In our opinion, this was not an  acceptable conclusion.
The primary purpose  of an SI  is to  assess the eminent  danger of the site, and
to assure continuation of  the remedial process.  The resources available to EPA
                                       12

-------
under its hazardous waste program are not adequate to perform additional Sis on
the same  site.   This is particularly  true  when only  one SI should  have been
necessary.  The results of our review of the Sis are summarized in the subpara-
graphs below.

     Old Sioux  Falls  Landfill,  South Dakota.   A site visit  was made  in June
1979, and the SI report  was  completed in March 1985.   Our review of the report
disclosed that  it was of relatively poor quality, and was prepared by someone
other than the  inspector that performed the  field  visit.  We also noted that
no sampling had  been  performed in conjunction with the  SI.   Additionally,  the
files did not document or otherwise indicate why it took almost 6 years to com-
plete the SI process.  Although the SI  report commented that the site had been
abandoned and built over,  there  was no indication that this had  been the cause
for any delay.  In summary, it was our opinion that very little effort had gone
into the preparation  of  the SI report.   It  therefore  did not appear that any-
thing was accomplished by performance of the SI.

     St. Regis  Paper  Co.-Wheeler Division,  South Dakota.  The field  visit was
conducted in January 1983._ The resultant SI report, which was not dated, indi-
cated that no  sampling had been performed.   The report noted that  samples of
groundwater, waste, runoff, and  soils were needed.  The report  also indicated
the possibility  of contamination  of drinking water  due to  the  presence of
pentachlorophenol and creosote sludges.  In view of the potential environmental
problems and the lack of sampling, it appeared  that the  results  of the SI are
of little  value in  ascertaining whether  future remedial work  is  necessary.

Since the reports  reviewed did not fulfill  the primary objectives of an SI, it
appears that additional  regional training  on the techniques of  performing an
SI is required.  Also, the Region's procedures need to be improved to document
whether or not  the Region  considered the  Sis performed  by  the states  to be
acceptable or unacceptable.   The project files for the  9 Sis reviewed did not
indicate whether the  Region considered  the  work unacceptable, or if additional
work at the sites was required.  The Region has the responsibility for assuring
that the states possessed  the necessary technical  staff  and facilities to per-
form the Superfund work before the cooperative agreement was awarded.  In addi-
tion, the Region was  responsible for monitoring the progress of the states SI
activity under  the  cooperative agreements.   Our review  disclosed that the Re-
gion has not fulfilled these  responsibilities.  The Region has not provided the
states with any written instructions, training, or other guidance detailing the
minimum requirements  for performance of an  SI.  Unlike the FIT contractor, the
state agencies  are not  required to submit a  sampling plan prior  to  making a
site visit for SI sampling and site characterization.  As such, it is important
that the states be provided detailed  instructions  on the procedures to be fol-
lowed in performing an SI.

Delays in Completing SI Reports.  In addition to the quality problems, we found
that significant delays  were experienced in  the  issuance of the  final SI re-
ports.  In this  regard,  an average of 313 days elapsed between the date that
the SI  site  visit was made and  the date that the SI  report  was issued.  When
this time  is  combined with the  449-day average delay in following up on the
PAs, a  total  of  762 days,  or more  than 2  years,  are  required to determine
whether the  site  represented a  significant  environmental  hazard.  We noted
                                      13

-------
that several of the sites which have been delayed in the SI process represented
significant hazardous waste problem areas  which should have proceeded to reme-
dial action as soon as possible.  One of these sites, the Wasatch Chemical site
in Utah,  represented one  of  the  most  serious  hazardous  waste  sites  in  the
state.

The Wasatch Chemical  site  is located in an  industrial  area of Salt Lake City.
The site was  found to present a serious potential health hazard as  a  result of
ground and  surface water  contamination.  However,  our review disclosed that
clean-up action on this site had not progressed to the remedial stage, although
more than 2 1/2 years had passed since an initial SI was performed in tMay 1984.
The SI report,  stated "As the Huntsman-Christensen pond may be representing a
serious potential hazard to an important municipal well and is releasing toxic
and carcionogenic  compounds to the  local ground and  surface waters, it is felt
that further  CERCIA action  there  should  be given a  high priority."   An  HRS
score of  51.02 was established as a  result of  the  SI.   However,  it  was  not
until June  1985,  about  one-year later, that  the  state  performed  a  CERCIA site
inspection.  Various,  parts of  this  site have been  leased and subleased to a
number of  chemical companies  which used  the  facilities   to  mix,  blend,  and
package pesticides and herbicides.  The  site actually  consists of two separate
parts.  One part  (Lot 6)  covers 3.68 acres  of partially  fenced,  but otherwise
undeveloped land, except for a cement encased pond which has been used for bulk
hazardous and  toxic waste  storage.   The balance  of the site consists of 10.89
acres of  property containing  a number of  structures  used  in the past  for a
variety of purposes.  The 1984 SI covered only Lot 6.  A subsequent 1985 SI was
conducted and  included  sampling of the whole  site.  The SI resulted  in an HRS
score of 87.5 on September 13, 1985.  Both of  the HRS scores were far in excess
of the 28.5 minimum required  for consideration for  inclusion on  the  NPL.  Al-
though the  significant  hazardous waste  problems  at  this site have been known
since 1984, long-term remedial action has not been initiated.

During the SI performed in 1985, a group of forty-eight 55-gallon drums, numer-
ous smaller containers, and 13 compressed  gas cylinders were discovered at the
site.  The  containers  were  in a  severely  deteriorated   condition.   Samples
showed the  hazardous  wastes  contained  elevated  levels  of  2-4-D,  Xylene,
Anthracene, Nepthalenes, and  Phenonthrenes.   Soil samples also showed elevated
levels of  2,  4, 5-T,  other organics, and heavy metals.   The cylinders were not
sampled because of doubts regarding their structural  integrity.   On  the basis
of the sample results,  the state requested  the Region  to  conduct an immediate
removal of  the drums,  containers,  cylinders, and contaminated soil  from the
site.  The  immediate removal was conducted during the months of March and April
1986.  Approximately  19 of the 48 drums were found  to contain Dioxin contami-
nated wastes.

The Dioxin  level  of some of the containers  reached  as high as 9,000 to  12,000
parts per  billion (ppb),  which was  far in excess of the  5 to 10 ppb standard
allowed for industrial  areas.  The drums  currently  remain  stored  at the site
and locked  in a metal shed.

There has apparently been some reluctance on  EPA's part to  list the entire site
on the NPL because a  portion  of the site is subject to the requirements of the
Resource Conservation and  Recovery Act (RCRA) program.   As a result, it is our
                                       14

-------
understanding that  only Lot 6  is  being considered for  the  NPL.   However, the
state contended  that the whole  site should be  listed  on the  NPL because the
release of contaminants "...on the site are unrelated to current RCRA practices
and all parties have demonstrated a  staunch unwillingness to conduct necessary
remedial investigations or undertake remedial activities at the site."  In this
respect, the  Potentially Responsible Parties  (PRPs)  on this site represent a
major obstacle to  the  commencement of any  remedial action.   The  state has at-
tempted to negotiate an agreement with the  PRPs since mid-1984 without success.
As a result,  the state has  subsequently filed a civil action in  Federal court
to force the  PRPs  to  participate in  the  site  clean-up and to  reimburse the
state for  its oversight  costs.   The suit  is  pending with  no date  for final
resolution.  There  were 11  PRPs named in the  suit.  This could  prove  to be a
very lengthy  process which  may result in further  lengthy delays  in the actual
remedial action  at the site.   A memorandum issued by  EPA on  March  20, 1984,
entitled Participation of Potentially Responsible Parties in Development of Re-
medial Investigations and Feasibility Studies under CERCLA clearly stated that
"The Agency will not engage in lengthy negotiations with PRPs over whether PRPs
will conduct the RI/FS."  This policy was established to preclude an obstinate
or uncooperative PRP from .unduly delaying remediation of a hazardous  site con-
dition.  It appears that the  intent of  this  policy was not  followed  at the
Wasatch Chemical site.

Regional Comments and Our Evaluation

Regional Comments.  The Region  agreed  that  procedures for conducting an SI are
necessary.  However, it stated that the resources necessary to prepare the pro-
cedures were  not  available.   The  Region  also  coitroented  that  the  procedure
should be prepared  by  Headquarters to assure  consistency between the Regions.
The Region also provided the following additional comments on the other matters
discussed in the finding.

     1.  Quality of Sis.  The  Region contended that an  SI will often result in
the conclusion that additional sampling was required at a particular site.  The
Region maintained there are simply  too many variables at a site to expect that
a small number of samples will be adequate.

     2.  Old Sioux  Falls Landfill, South Dakota.  The Region commented that, at
the time that this  SI  was conducted, there  was no requirement that sampling be
perfornBd.

     3.  St.  Regis  Paper Co.-Wheeler Division,  South Dakota.  The Region com-
mented that sampling at this site was not conducted because it was not required
at the time the SI  was performed.

     4.  The  Region agreed  that additional training  in  the  SI  area was neces-
sary for the  state  staffs. •' However, the Region was not willing to unilateral-
ly develop procedures  for performing the Sis.   The Region also indicated that
it monitored  the  states'  Superfund performance  via  the quarterly reports.

     5.  Wasatch Chemical Site, Utah.  The Region explained the  circumstances
under which Utah filed  the legal action against the Wasatch  PRPs.   It noted
that it was the most appropriate action at  that  time.
                                       15

-------
PIG Evaluation.  As  explained previously, we  believe that,  in the  absence of
Headquarters guidance,  the  Region should establish the procedures necessary to
maintain an effective  Superfund program.  Such procedures would  assist states
in meeting the requirements  for performing Sis.  Our  additional comments, keyed
to the balance of the Region's response,  are as  follows:

     1.  We recognize  that  there  may be a problem with the performance of ade-
quate sampling during  the normal site visit.   However,  the  need  to constantly
revisit sites to  perform additional  sampling  is,  in our  opinion,  an ineffec-
tive practice in  view  of the additional time  and cost required.   It  is  our
understanding that  similar problems  regarding the adequacy of  sampling prac-
tices have occured  on  a  nationwide basis.   To  help  correct this problem,  EPA
Headquarters has  developed  a guidance document, OSWER Directive  9345.1-11, to
assist in planning  a site sampling strategy.   Our audit disclosed  that such a
sampling strategy had  not been developed for  most of the Sis  reviewed in Re-
gion 8.  Without  an  adequate sampling plan,  the necessity for follow-up visits
is increased.

     2.  The Region responded .that there was no  requirement for  sampling at
the Old  Sioux Falls Landfill.   Without a  sampling  requirement,  practically
nothing was accomplished  by performing the SI,  since it revealed nothing more
about the site than was previously  known.

     3.  The  Region indicated  that  sampling  was  not required.    However,  it
should be  noted  the  form used  to conduct  the SI at this site specifically
identified the sampling that should have  been  performed.

     4.  It remains  our position that if a  void in guidance exists, the Region
should initiate the  procedures necessary to  correct the problem.   With respect
to the comment that  the Region monitors the  PA and SI program by review of the
quarterly reports, we  consider this  comment to be non-responsive to  our con-
cern.  Our review disclosed  that very little actual information was transmitted
via the quarterly reports.   Certainly the quality of the  work  performed could
not be reviewed via a quarterly report.

     5.  We did not question whether  or not the  litigation taken at the Wasatch
Chemical Site by  the state was appropriate.    Our point was that the litigation
should not  be allowed  to indefinitely  stall  the RI/FS  process  at the  site.
                                   >

Hazard Ranking System Scoring Problems

Our review disclosed that the procedures used by  the Region to review and ap-
prove HRS  scoring packages  were  not  adequate.  As a result, the  HRS scoring
packages submitted  in support of  the Olsen-Neihart  Reservoir, and the Silver
Creek Tailing sites  were npt adequate to withstand the challenges made by out-
side sources.  In addition, the  Region's handling of the HRS  scoring package
for the potentially  significant Kennecott Copper  site was  inadequate.  Since
most of the HRS scoring packages prepared in Region 8 were applicable to sites
in the State  of  Utah,  we limited  our review to  that state.  The actual HRS
scoring was performed by both  state  and the  FIT contractor.  Progression of
a site through the  pre-remedial process  to  eventual  remediation of  a serious
                                       16

-------
health threat  is  dependent,  in part, on  how well the HRS  scoring package was
prepared and supported.  An  HRS  score that is not based upon adequate support-
ing information will  not withstand the challenges of a potentially responsible
party or of local government entities.

The purpose for  the HRS scoring system is to provide a  method of establishing
the relative risk  or danger of  a  site  in relation to all  other  sites by con-
sidering the (i) population  at risk,  (ii)  the hazard potential of the substance
at the site, and (iii) the  potential for contamination  of drinking water sup-
plies, direct human contact, and the destruction of sensitive ecosystems.  Com-
putation of the  HRS score is based  on data developed during  the SI.   The HRS
score ranges between  0 and 100.   A score  of  28.5  or more  is  required  for nom-
ination to the NPL.   The major  factors to be considered during the HRS process
are (i)  the observed release,  (ii) the route  of exposure  characteristics,
(iii) the  containment measures  taken to minimize or prevent migration  of  a
contaminant, (iv)  the waste characteristics,  and  (v)  the  targets,  such  as
populated areas, which may be affected by a migrating contaminant.

Olsen-Neihart Reservoir, Utah. . This site was included on the October 15, 1984,
NPL update.  The SI  was performed by state  staff.   The HRS  scoring  was per-
formed by the  FIT,  and the  site  was given a score of  33.75.   During prepara-
tion for negotiations with  the  PRP  for  the site,  the  regional  staff  became
concerned about the  inadequacy of the data supporting the  HRS score.   Some of
the deficiencies  noted were;  (i)  the upgradient  and downgradient groundwater
samples were taken 4  years apart;  (ii)  no data on the depth of the aquifer and
whether the wells were  completed  to the  aquifer  of  concern;  and (iii) based
on the data available, there had  not been an observed release to the surface
waters.  These data were  critical to achieving  the  HRS score of 33.75.  The
significance of the deficiencies  noted  made it difficult to understand how the
HRS score had been  initially accepted without questions  being raised as to the
adequacy of the  HRS scoring package.  These  questions  should have  been asked
during the  quality assurance  review  performed  on  the  HRS   scoring  package.
Based on subsequent sampling work performed by the state, we understand that
the site is to be recommended for  elimination from the NPL.

Silver Creek Tailings Site,  Park City, Utah.  The  state performed an SI on this
site and issued  a report on August  10, 1985.  The report recommended the site
be considered for the NPL.  The site was  located within a resort community, and
consisted of about 80  acres of mine' tailings that  vary in depth from one to ten
feet.  A tract of expensive custom homes and  commercial buildings were con-
structed on the  site during the past  several years.   The  soil samples showed
high concentrations of lead, cadmium, arsenic,  and silver.  The FIT contractor
assigned an HRS score of 38.4 to the site on January 15, 1985.  The City subse-
quently engaged a consultant to review the accuracy of the HRS scoring package.
The consultant raised several issues concerning  the  reliability  of  sampling
data, the validity of the' conclusions reached,  and  the resultant  HRS  score.
Specifically, the  consultant challenged  the  state's  conclusion concerning the
interconnection of aquifers underlying the site and the validity of the surface
water sampling technique employed  by the  DEH staff.  Upon receipt and review of
the consultant's  report, EPA Headquarters urged that the Region conduct more
sampling to confirm the validity of the  HRS score.  However, the Region initial-
ly refused to conduct  additional testing  to support the HRS score.  It has sub-
sequently initiated an extensive reevaluation of the site.
                                      17

-------
Kennecott Copper Sites.  The  Kennecott  Copper  sites potentially  represented
the most  significant hazardous  waste sites  in the  State of  Utah.   However,
little action  has  been  taken to  ascertain the full extent of  the  hazardous
waste problems at these  sites,  or to initiate a schedule of corrective action.
In this  regard,  there were nine  individual  Kennecott Copper sites  listed on
the CERCLIS.   Only three of  these had either  a PA or  SI  performed  under the
cooperative agreement.

An SI of the Kennecott  Tailings  Pond located in Magna, Utah  was conducted by
the state in July 1985.  The  pond, which covered approximately 5,000 acres, has
been built up  to a height  of 80 to 90 feet.   It  is bordered on the  south by
the Oquirrh Mountains,  on  the north  by  the Great Salt  Lake,  and on  its other
sides by marshy alkali flats  and fresh water creeks and canals.  A draft report
summarizing the  results  of the  SI was issued by the state  in December 1985.
The draft report  indicated that the pond  had  high  levels of arsenic,  lead, and
chromium.  A preliminary HRS  score of 79.15 was calculated based on  a scoring
of air, groundwater,  and surface water releases.   It should be noted that the
tailings pond  was  in close proximity to local  population  and industry.  This
was reflected in the draft  SI report which  stated "Should the tailings ponds be
found to present environmental  hazards,  the  potential for impacts  upon local
population and industries is  high."

Although the actual SI was conducted in July 1985, no action had been taken by
the Region as of the end of 1986 to recommend  that this site be included on the
NPL.  The files  are vague  as to the cause for the excessive delay.   However,
the results  of a FIT review issued in September 1986 disclosed  problems with
the sampling  rationale  used  in the  SI.   The  review concluded  that  the data
were not adequate  to support an  HRS  score,  although it  indicated that there
was a definite problem  with  the  Kennecott Tailings site.  The  files  did not
explain why  it  took 9 months for  the Region  to conclude that the sampling was
inadequate.  Since  the actual sampling was performed in July 1985,  there was,
in reality, a  14-month delay in determining  that  the sampling was inadequate.
As of  June  1987,  little  progress had  been  made  towards correcting  the HRS
scoring deficiencies and rescoring the site so  that  it  could be  nominated for
inclusion on the NPL.  We  were advised that the PRP was voluntarily conducting
groundwater studies of the  general area of this site.  It  should be noted that
the PRP's study may take several  years to  complete,  and even then there is no
assurance that  the PRP  will move forward after the study to  clean-up this
site.  We therefore believe that EPA should  immediately take the lead on this
site, and have  the FIT  perform  the work required  and prepare an adequate HRS
scoring package.

Regional Comments and Cur Evaluation

Regional Comments.  The  Region provided the following specific comments.

     1.  Silver  Creek Tailings  Site,  Park City,  Utah.   The  Region provided
additonal comments  to clarify  its position regarding the  additional sampling
required for this site.  The  Region indicated  that  it did not oppose additional
sampling at the site,  but did not believe  that  the site represented an iirmedi-
ate threat  to the  connunity.  The  Region indicated it preferred to conduct
the additional sampling  subsequent to NPL listing.
                                       18

-------
     2.  Kennecott  Copper  Site.   The  Region  enphasized that  the  HRS package
submitted by the state was  tentative  until  the  Region had completed its quality
assurance review.   The  Region further  contended  that  the package submitted by
the state for  Kennecott could not  be adequately documented,  and was  therefore
not adequate to support  the HRS  score.  The Region indicated that it  is in the
process of having the state resample  the  site under an expanded SI.  The Region
also commented that it had  repeatedly told the state of  its intentions to list
the site on the NPL should  the SI substantiate  such a listing.  The Region also
agreed that it  should take  the  lead  for this  site, if  the state hesitated to
take appropriate action  on  a timely basis.

PIG Evaluation.  The Region's comments  provide  additional clarification for the
basis of its actions on the  above  two sites.   However,  in both instances, the
Region's lack of  aggressive action has contributed to the delays at the sites.
The Region commented that  it repeatedly told the state that the Kennecott Cop-
per site would be  nominated  for the  NPL, if the  SI supported  such an action.
However, we found  no documentation in the  official  project files  to support
this assertion.     ...
                          -T-
Lack of Progress at NPL  Sites

We observed that progress towards remediation at several of  the  NPL sites speci-
fied in the cooperative  agreements  was slew and  sporadic.   It  was  our opinion
that Superfund activities  at these sites were  not well  managed by the Region.
In this respect, the Region did not assure that the states expedited action on
these sites, but  instead allowed the state agencies to move at their own pace.
In most cases,  this pace was quite slow.   While some  delays were attributable
to local opposition against moving  forward  in the  Superfund process, we did not
find that the Region actively assisted the  states when these situations occur-
red.  In the subparagraphs  below,  we discuss the lack  of progress  at the fol-
lowing four NPL sites:   the Milltown  Reservoir  Sediments Site, Montana;  the
Arsenic Trioxide  Site,  North Dakota;  the Silver Bow Creek  Site,  Montana;  and
the Sharon Steel Site, Utah.

Milltown Reservoir  Sediments  Site,  Montana.  Samples taken  from drinking  wells
in thecommunity ofMilltown,Montana,in  1981, showed  elevated  levels  of
arsenic in the drinking  water supply. Milltown is adjacent to the Milltown Dam
where the Big Blackfoot  River joins the Clark Fork River.  The Milltown Dam was
built in 1906  to provide hydroelectric power to the  area.  Although the facil-
ity remains in operation,  the  reservoir has been filled over the  years  with
mine tailings.  The Clark  Fork River basin  is  the location  of several  NPL
sites, including  the Anaconda  Smelter Site,  the Montana  Pole Site,  and  the
Silver Bow  Creek Site.  The total distance  from the Silver  Bow Site to  the
Milltown Reservoir  Site  is  about 120 miles.

The Region awarded  a cooperative agreement to  the Montana Department of Health
and Environmental Services  on June 27,  1983,  for preparation of an RI/FS at
the site.  The  site was nominated  for and included on the NPL in  the fall of
1983.  As an  intermediate  remedial measure, the  water supply system for  the
households with contaminated water was replaced  in 1985.   The  firm of Harding
Lawson Associates (HLA)  was hired  to perform the  RI/FS.  However, HIA had dif-
                                       19

-------
ficulty with the performance of the required  tasks, and fell about 6 months be-
hind schedule.  This  condition,  in addition to the poor quality of work, ulti-
mately led  to  a termination of HLA's  contract by the  state  in February 1987.
In this regard,  the state  reported  in one of  its quarterly  reports that "The
draft FS report  was poorly done and it was becoming evident that the contrac-
tor, Harding Lawson Associates, was not performing as  expected."   The report
also commented  on  problems with  the  RI/FS report and  stated that  "The main
area of discrepancy was with the  Arsenic speciation...HLA has had some trouble
in validating their data  in regard to  arsenic speciation."   The report further
stated that  "The draft  FS  report was received  on  11/13/86.   It  was evident
that little work had  been done since the 1985 version.  Comments from the 1985
version were not incorporated  into the draft...It was felt it was poorly done."
As a result of the termination and  the problems  with  the  quality of the work,
some of the testing performed by  HLA  may have  to be redone.   This could delay
the initiation of  further remedial action  although more than  3 1/2 years have
passed since the cooperative agreement was  awarded.

Arsenic Trioxide Site,  North Dakota.   Normal  drinking  water sampling disclosed
the existence of arsenic  in the drinking water  supplies of Lidgerwood, Rutland,
and Wyndmere, North Dakotaf. The  sampling levels  were  either at the maximum or
exceeded the maximum levels allowed under EPA's mandated Safe Drinking Water
Act (SDWA).  In addition,  wells  in  the  surrounding rural  farming communities
were also found  to contain high  levels of arsenic.  A  specific  source of the
arsenic contamination was not  readily  identifiable.  This situation resulted in
the award of a cooperative agreement  to the  North Dakota  Department of Health
on August  24,  1982,  for the  purpose  of identifying the  extent  and potential
sources of  contamination.  The cooperative agreement specified that work would
be completed by December  3, 1984.

Our audit disclosed that the  required  work  had  not been  completed,  although
about five  years  had passed  since  the  initial  cooperative  agreement award.
Because of the poor quality of the documentation  in  the project files, we were
not able to ascertain  the  cause  of  the delays.  Additionally,  there  was  no
indication as to what actions were taken by  the  Region to encourage the state
to speed up their  progress. However,  a memorandum in  the  file stated that one
year of the delay  was  attributable to  the fact  that  the  state was  unable to
hire personnel.  Obviously  the State of North Dakota did not attach a very high
priority to the  site since they  did not assign  other  state  personnel to work
on the project.   As  a  result of  the  delays,  EPA Headquarters urged that the
Region take back the  site lead, and complete the RI/FS as a Federal lead site.
The Region  opposed this suggestion contending  that the  delays had been beyond
the state's control,  and that  a change  in  lead responsibilities may damage its
working relationship  with  the state.   The Region therefore granted  the state
an additional time extension,  and agreed to have an EPA FIT contractor assist
in the completion   of the various tasks  remaining under the  RI/FS.  These ef-
forts did  result  in  a  Record of Decision  (ROD) being reached  in September
1986, for all areas of  the  site,  except  for the Town of Lidgerwood.  A ROD for
Lidgerwood was not expected to be completed  before  September 1987, because of
a controversy  over the funding of  its  water  supply  system.  The  RI/FS con-
cluded that the  contamination was affecting  an area of 171  square miles con-
taining a  population of about 4,500.   Contamination  of  the  groundwater ap-
                                       20

-------
peared to  have two  sources.   The  first  source was  from naturally  occuring
arsenic contained in shales native to the area.  The second source of contamin-
ation was from arsenic-laced bait used to control grasshopper infestations from
about 1936 until the mid-1940's.  The program to fight the grasshopper infesta-
tion was funded by a combination of Federal, state, and local governmental pro-
grams.  The project  file indicated that  the state liability and  cost sharing
at this site  were considered  because  of this role  in  the grasshopper control
program.  However,  there was   no  documentation indicating  whether the  state
liability issue had been  resolved.   In addition, the files did not discuss the
Federal government's liabilities, although  it  also participated in the control
program.

Silver Bow Creek Site, Montana.  The  original site  was  added to  the NPL  in
September 1983.   It extended  approximately 15  miles  upstream from  the  con-
fluence of the Clark Fork River and Silver  Bow  Creek.   EPA awarded a  coopera-
tive agreement to  the  Montana  Department of Health  and Environmental  Services
in September 1983, for performance of an RI/FS at the site.  It was subsequent-
ly determined that an  additional 9-mile area may also  qualify as an NPL site.

As a  result,  in April  1984,  the FIT  completed  an SI and  HRS scoring package
for this additional  area.  The site  was scored at 49.9 and  was added to the
original Silver Bow  Creek NPL site, extending that site 9 miles further up the
Silver Bow Creek.   The site contained arsenic,  cadmium,  copper,  barium, lead,
and zinc.  There  have  also  been releases  of  PCPs via  groundwater discharges
from the Montana  Pole  NPL site.  A removal  team has been assessing the poten-
tial for  acute health  impacts  from  the presence  of elemental  mercury at  a
public ball  field within the  boundaries  of the  Silver Bow  Creek  site.   Al-
though the site has  been on the NPL since September 1983, the RPM estimated it
would be at  least two years before adequate information would be available to
make a well  informed decision  on  the  future  remedial  actions required at the
site.  This  situation  would result  in a  study period of  5 to  6  years,  at a
minimum, before completion of  the RI/FS.

Sharon Steel Site, Utah.  This site is  located  in a  heavily populated suburb
of Salt Lake City,  Utah.  The  site  consisted  of approximately  260  acres of
tailings from  a mine milling  facility which operated  from about 1880 to 1959.
The tailings are 40 to  50 feet deep in some locations.   Releases from the site
in the form  of wind blown tailings and  contamination of groundwater have been
documented.  The  site  received an flRS  score of 72.03  and was included on the
NPL in  October 1984.   In addition,  the site  was  incorporated into the multi-
site cooperative  agreement  awarded to  the Utah Department of Health in Septem-
ber 1984.   Progress at  this  site has been very  slow, and  development  of an
acceptable workplan  has been unsatisfactory.  Problems  with the notifications
and negotiations  with  the PRPs also had  a negative effect on progress at this
site.  Although  this site has been on  the NPL for over  2  1/2 years, little
actual RI/FS  work has  been  accomplished.   As  a result  of Federal litigation
against the  PRPs,  EPA assumed  the lead  for the site  in early 1987.  The Fed-
eral  lead  RI/FS was anticipated to begin  with groundwater  sampling in June
1987.  It  therefore  appears  that substantial additional effort will  be required
before the RI/FS at  this  site  is completed.
                                       21

-------
Regional Comments and Our Evaluation

Regional Comments.  The  Region did not  agree that the states  were allowed to
move at their own pace.   It expressed a  dissatisfaction with the pace of state
activities under  CERCIA.  The  Region also  commented that  it  was encouraging
the states  to be  more  efficient and timely.   With  respect to  the specific
issues discussed in this  finding,  the Region provided the following additional
comments.

     1.  Milltown Reservoir Sediments Site, Montana.  The Region commented that
progress on the Milltown  Reservoir and Silver Bow Creek  sites  in Montana were
impacted by (i) the delay in re-authorization of CERCIA, and  (ii) the complexity
of the sites  which are part of a chain of four NPL sites encompassing 77 oper-
able units.  With respect to the Milltown site,  the  Region disagreed that the
RI/FS for the site was significantly behind schedule.  It contended that the 3
1/2 years cited in our report was not  an  accurate portrayal of the actual delay.
The Region also stated that we should only  consider  the delay period from the
time the ROD  for the  water supply  system was proposed  in  1985,  rather than
from inception of  the cooperative  agreement in 1983.  The  Region agreed that
site specific schedules would be useful  tools for monitoring state performance.
The Region  also  stated  that it was  planning to  implement  specific schedules
for each site.

     2.  Arsenic Trioxide Site, North Dakota.  The Region commented that it did
not assume the lead  on this site, as urged  by Headquarters, because it wanted
to put the project back on schedule, and desired to build the state's capabili-
ties.  The  Region did not  agree that it delayed  action in  order to maintain
good relations with  the  state.  It  also considered our statement concerning
the state's attachment of a low priority for the site to  be speculative, and
suggested that we delete the  statement   from the report.   The Region further
commented that the  decision to fund  the Lidgerwood water  treatment facility
resulted from a  change in EPA  national  policy at EPA  Headquarters.  As  a re-
sult, the decision to perform a ROD for the Lidgerwood  facility  was not made
until mid-1987.

     3.  Silver Bow  Creek  Site,  Montana.  The Region  stated the audit report
misstated the area  of the  specific  site  being  addressed  in the report.  The
response indicated that  the whole  Silver Bow Creek  site consisted  of  a 120-
mile area.  Due  to  the size and complexity of this  site,  including the Butte
addition, the Region  contended  that it may take longer than  the normal time
period to complete the RI/FS.   The Region's comments also discussed the causes
for delay including a  lack of  funding, inadequate  resources,  and a  low seasonal
rainfall.

     4.  Sharon Steel Site, Utah.   The  Region claimed that the lead for this
site was not  taken back  ad  a  result of  unsatisfactory progress  by the state.
According to  the  Region, the  site became a Federal lead site  because  of the
initiation of Federal litigation against the PRPs.   The  Region commented that
"...EPA as a matter of policy  assumes the lead  for RI/FSs in every instance in
which EPA initiates litigation."
                                       22

-------
PIG Evaluation.  The  Region disagreed that it allowed the states to perform at
their own  pace.  However,  the Region provided  no new  information  that would
allow us to modify our  conclusion.   On the  basis  of our review  of the sites
discussed  in this audit  report,  we consider  our conclusion to represent a rea-
sonable assessment  of the Region's actions.  Our  evaluation  of  the balance of
the Region's  response  is  keyed  to  the regional  comments  summarized above.

     1.  The Region disagreed that the site was significantly behind schedule.
However, according  to an office  memorandum prepared by the  State Project Of-
ficer for  the  Milltown site,  dated December 29,  1986, one of  the reasons for
terminating Harding Lawson  Associates was because  they were  4 to 6 months be-
hind schedule.   Also, we were not aware that work on the replacement of the
water supply  system  and  the  characterization of  Milltown site  were mutually
exclusive  of each other.   It therefore remains our position that  the period
of delay should be measured from the date of the  cooperative  agreement.   We
recognize  that  many Superfund sites are unique and complex,  however, the more
than 3  1/2-year  delay   experienced   under  this   project  appears  excessive.

     2.  Our statement regarding  the  Region's desire to maintain good relations
with the state was based on  a July 26,  1985,  memorandum from the regional Super-
fund Remedial  Branch   Chief  to the Director  of the Waste  Management Division.
In the discussion  of  whether the EPA should assume the lead  for the site, the
memorandum stated  "This would  enable EPA to meet  the deadlines  committed to,
with the downside  risk of  damaging  EPA-State relations across more than just
the Superfund Program."   With respect to our statement that the state placed a
low priority on this  site,  we believe that the  almost 4 year delay in comple-
tion of work and the  state's inaction for a one-year period support our con-
clusion.

     3.  Our information concerning the area covered by the Silver Bow Creek
Site was taken  directly from regional documentation  contained  in the coopera-
tive agreement.   Contrary to  the Region's  comment,  the site did not include
the whole  120-mile area.   In addition, the February 1987 EPA  Region  8  Fact
Sheet described the site as extending 15  miles  upstream from the  Clark Fork
River and  Silver Bow  Creek.  While we  recognize  that this is a  very complex
site, we do not believe that  a  5 to  6-year study period to complete the RI/FS
represented a reasonable  time  frame.

     4.  The comments on the  Sharon  Steel site clarify the  basis for EPA as-
sumption of the Federal lead.  However, the fact  remains  that  more than 2 1/2
years have passed  with little  RI/FS  work  completed.  During the exit confer-
ence, the  Region also modified its comment concerning  EPA's assumption  of a
lead when  EPA  has initiated  litigation.    It  indicated that  EPA generally
assumed the lead when it initiated litigation,  but that there was  no written
policy in  this  regard.    ..-;

RECOMMENDATIONS

We recommend that the Regional Administrator:

     1.  Improve  the  timeliness  and  effectiveness in  which the  cooperative
agreement  pre-remedial functions  are performed by:
                                       23

-------
         a.  Placing  a higher priority  on the  conpletion of the PA,  SI,  and
the HRS scoring packages.

         b.  Reducing  the elapsed time  required to  complete the PAs,  and to
initiate and complete the Sis and HRS scoring packages.

         c.  Improving the  monitoring  of the performance  of  the  PAs,  Sis,  and
HRS scoring package by the  cooperative agreement recipients.

         d.  Assuring  that  the Sis  are  performed  in accordance with  the  EPA
guidance contained  in  OSWER Directive 9345.1-1.  In  this  regard, the Region's
acceptance or rejection  of  the completed Sis should  be  documented in the pro-
ject files.

         e.  Requiring states  to  submit  a site sampling plan for their Sis to
the Region for review and approval prior to commencing field work.

         f.  Providing adequate training to applicable  state personnel in  the
PA, SI, and  HRS areas  to,  assure that they  have the necessary  background  and
capabilities to perform in  these areas.

         g.  Taking immediate  action to  assure  that the  complete Wasatch Chem-
ical site is recommended for inclusion on the NPL.

         h.  Improving regional reviews  of the HRS scoring packages to assure
that they are effectively prepared and reported.

         i.  Taking the lead responsibility for the Kennecott Copper sites,  and
expediting the completion of an adequate HRS  scoring package for the Kennecott
Tailings Pond site.

     2.  Improve the  management  of  the  NPL sites  included in the cooperative
agreements to assure that timely actions are being performed.  In this respect,
special attention  should be given to  expediting action on the  four following
NPL sites:  the Milltown Reservoir Sediments site; the  Arsenic Trioxide site;
the Silver Bow Creek site;  and the Sharon Steel site.

Regional Comments and Our Evaluation
                                   >
Regional Comments.  The  Region generally  agreed with the recommendations  in-
cluded in the audit report.  However,  the Region's proposed actions on Recom-
mendation numbers  I.e.,  l.d.,  and I.e.  are not  as encompassing as we recom-
mended.  Our recommendations provided  for approvals  of  certain actions.  How-
ever, the Region responded  that,  in fact, they plan  to  cease certain approval
functions now performed.  In this  regard,  the Utah  Memorandum of Understanding
will not require that the Region approve  PAs,  SI sampling plans, or Sis.  The
only approval will be at the HRS stage of the preremedial process.

PIG Evaluation.  In view of the deficiencies  we found in  the pre-remedial pro-
gram, the  move towards  less  regional oversight (i.e.  approvals) is,  in  our
                                      24

-------
opinion, inappropriate.   Vfe believe  such a  practice  will have  a detrimental
effect upon  the program.   We  therefore urge  the Region  to  reconsider this
course of action until the states have demonstrated the capability  to adequately
perform the required pre-remedial tasks.
                                      25

-------
2 - REGIONAL ADMINISTRATION OF COOPERATIVE AGREEMENTS SHOULD BE STRENGTHENED
The Region has not developed  the procedures  necessary to  adequately manage its
Superfund cooperative  agreements.   As a  result, there  was no  assurance  that
maximum environmental  benefits  will be derived from the $6.4 million of Super-
fund cooperative agreement  funds  awarded to date.   The inadequate regional ac-
tions, along  with recipient  deficiencies have  adversely  effected performance
under the  cooperative agreements.   Vfe attributed  this  condition  to  numerous
factors including  the following:  (i)  the Region had not  adequately monitored
the completion of  the required cooperative  agreement work; (ii)  the  Regional
Project Managers  (RPMs)  were not  provided adequate  guidance  to perform their
responsibilities; (iii)  some cooperative agreements were  prematurely awarded
to recipients that did not meet  the financial, technical,  and  experience re-
quirements described in 40  CFR  30.301; (iv)  the Region had not required recip-
ients to establish the site  specific  schedules required by EPA guidance; (v)
the Comprehensive Environmental Response, Compensation,  and Liability Informa-
tion System  (CERCLIS)  was  not  adequately maintained; and  (vi)  the Region and
the State of Utah had  not .established  an adequate working relationship for the
performance of the  cooperative  agreement goals and objectives.   Improvements
in the  above areas  will require  more aggressive  regional monitoring  of the
recipients' cooperative agreement  activities.

Background

The cooperative agreement program in Region 8  is managed by the State Program
Section of  the  Hazardous Waste Management  Division.   The use  of cooperative
agreements is  authorized by  Sections 104(c)  and  104(d)  of the  CERCIA.   The
cooperative agreements allow a state  or a  political subdivision thereof to
take or  to participate  in  any necessary actions  provided  under  CERCIA given
that the state or political subdivision possess the necessary  skills and capa-
bilities to  do  so.   The agreement is also used  to delineate  EPA and state
responsibilities for  the actions to be  taken  at the site,  to obtain required
assurances, and as a commitment of  Federal  funding.   EPA uses the cooperative
agreement as  a  means  of encouraging  state  participation in Superfund activi-
ties such  as the  pre-remedial programs,  state management assistance  on EPA
lead activities, and state  lead sites.   EPA Headquarters has published various
policy and  guidance  documents for use in  implementing  the Superfund program.

Procedures for managing  the cooperative agreements are discussed  in the publi-
cations entitled  "State  Participation in the  Superfund Remedial Program"  (the
"purple book"), and  the  "Superfund State-Lead Remedial Project Management Hand-
book".  These publications  provide guidance to both the EPA and  state staffs
for the  systematic application  of clean-up activities under Superfund remedial
response projects at NPL sites.  The publications  also provide detailed infor-
mation on each step  of the'remedial process and explain why the step  is neces-
sary.

More Aggressive Regional  Role is Necessary

The Region  has  not taken an  aggressive  role in assuring the completion of the
required cooperative  agreement  work.  This  has contributed significantly to a
                                       26

-------
lack of effective Superfund programs  in many of  the states, including one state
which only  recently received a cooperative  agreement after a long delay.  Once
a cooperative  agreement was awarded  to a  state, the  Region was not aggressive
in initiating  effective oversight of the  state's activities.   The states were
therefore given  a large degree  of latitude  in  establishing their cooperative
agreement Superfund programs.   Such an approach would only be effective if the
recipient states  have  the desire and capability to meet the  goals and objec-
tives of  the program.   We did  not find that the  states  in Region 8 possessed
these attributes and therefore the  Region's  approach  was  not fully successful.
To the  contrary, the  combination  of inadequate  regional and  state action re-
sulted in  ineffective  performances  under  the  cooperative  agreements.  There
was no  indication that the  Region initiated any penalties or  other sanctions
against the  cooperative agreement  recipients for instances of non-performance.
Instead, the Region merely reestablished the goals and objectives into the sub-
sequent year's  cooperative  agreement.  While we recognize  the Region's desire
is to have the  states  fully participate in the program, it is  our opinion that
the Region  should more aggressively pursue instances  on non-performance.  Some
examples of  areas which require more  active  regional  involvement are summarized
below.

Wyoming Cooperative Agreement.  A  multi-site cooperative  agreement was awarded
to Wyoming  to  perform  39 PAs,  to  assist in  the  performance of  19 Sis, and to
complete 11  hazard  ranking  system (HRS) packages.   It also provided  for the
state to review  EPA's  SI reports and  HRS scoring packages, and to assist in the
management at CERCLIS  sites.  We found the state's performance of the above re-
quirements to  be unsatisfactory.  There had been no work  performed under the
cooperative  agreement  during a 9  month period.  This  condition  occurred  when
the state's  sole cooperative agreement employee resigned  in June 1986.  After
this date there  was a  virtual  stop in all  Superfund activity within the state.
The Region apparently  did not take  timely action to remedy the condition, since
we found no  documentation in the project files  indicating that it emphasized to
the state the  importance of filling  the position.  This cooperative agreement
inactivity continued until  the Region  authorized the FIT  contractor  to begin
performing PAs  in an  effort to meet the SARA deadlines established  for the
pre-remedial program.

Utah Cooperative Agreement.  Qjr recent audit of the  state's cooperative agree-
ment disclosed that, as of September  1986, the state  had not fulfilled the per-
formance goals  and  objectives established in the cooperative  agreement.  Spe-
cifically, required work had not been completed  in the areas of hazardous waste
site forward planning, remedial investigations,  and  site  feasibility studies,
including studies at two sites  included on the NPL.   In addition, 21 PAs and 14
Sis specified  in the cooperative agreement have  not been effectively performed,
and the completion  of the required reports were behind schedule.  These condi-
tions could  have a  detrimental affect on  the public  health and safety of area
residents, since  appropriate action was not taken to alleviate known hazardous
conditions.  This included sites with high concentrations of lead, arsenic, and
other heavy  metals.      -

During the first year  of the cooperative agreement the Region became aware that
the state was a difficult recipient to work  with. The state made it clear that
it was  either incapable or unwilling to perform in  accordance  with the terms
                                       27

-------
and conditions  of the cooperative agreement.  However, the Region did not take
effective action  to  bring the state into compliance or to terminate the agree-
ment.

North Dakota Cooperative Agreement.  The state was awarded a cooperative agree-
ment on  August  24, 1982, for a  total project  cost of $242,716.  The award was
made to  enable  the state  "to  investigate the elevated arsenic concentrations in
southeastern North Dakota, and determine if the area is meritorious for further
consideration and mitigation  under the  superfund program of CERCLA."  The area
was titled the  "Arsenic Trioxide Site".  The state's progress in completing the
required scope  of work has been unsatisfactory.   In  this respect,  more than 4
years have passed and required work remained  incomplete.   Part of  the problem
was attributable  to  the stoppage of work  by the state for about one year be-
cause it was unable  to hire personnel.   As a result  of the  long  delay,  EPA
Headquarters urged the Region to take  back the lead on the site.  However, the
Region refused, because it believed that this would  have a damaging effect on
EPA-state relations.  Again, we believe that the Region's passive attitude with
respect  to the  accomplishment of the program objectives has been a contributing
factor to the state's ineffective performance  under the cooperative agreement.

Delay in Awarding Cooperative Agreement to South Dakota.  Although the state
did not  have a  cooperative agreement at the  time  of our audit,  it was attempt-
ing to obtain an  agreement.   In this regard, the state submitted an application
for a $32,988 agreement in May 1986.   In  the  application,  the  state indicated
that a multi-site cooperative agreement was required to fund 20 state-lead PAs,
and to provide  management assistance  on 5 EPA-lead inspections.   Although the
Region considered the application  acceptable,  it  indicated  it was  unable to
make an  award  because of a  lack of funding.   It is our opinion  that,  due to
the small amount  requested by the applicant,  funding  could have been arranged
from alternate  sources.  Due  to the delay,  a cooperative  agreement was  not
awarded  until March  1987.   In the interim, EPA had to utilize its  FIT contrac-
tor to perform  four PAs.  While this arrangement accomplished some of the back-
log of work, it did not give  the state the opportunity to develop its own capa-
bilities or experience.

Regional Comments and (Xir Evaluation

Regional Comments.  The  Region disagreed  that it  was not aggressive  in ful-
filling  its  oversight  responsibility.   The Region cited  Utah as  an example
of its  aggressive oversight,  stating  that  it had jeopardized the EPA-state
relationship in order to fulfill its responsibility.  The Region also commented
that the staffing allowed by EPA Headquarters  for oversight  was very limited.
With respect to the individual states cited in the finding, the Region provided
the following additional comments:

     1.  State  of Wyoming.' The Region responded that the Division Director and
staff had contacted  the state on several occasions  in an  attempt to convince
them to  fill the  vacant Superfund position.   This incident occurred during the
period of limited Superfund  funding, and at  a  time when a program slowdown was
in effect.
                                      28

-------
     2.  State of Utah.  The Region took exception to our comment regarding the
potential detrimental effect on the public health and safety of area residents.
The Region considered the  comment to  be speculative and possibly incorrect be-
cause no detrimental effect had been documented during the audit.

     3.  State  of North  Dakota.   The  Region stated that  it was  not passive
in dealing  with  the  state,  and  has  taken  aggressive  action to  correct the
problems with the project.

     4.  State of South Dakota.   The  Region commented that the application for
the South Dakota  cooperative agreement was  received during the period  of re-
duced Superfund  funding.  It  also stated  that EPA  Headquarters  was not ap-
proving agreements for pre-remedial work at that time.

PIG Evaluation.  The Region  objected  to  our conclusion  that  it had  not  ful-
filled its  oversight responsibility   in  an  aggressive  manner.   However,  the
material reviewed during the course of our audit, and the lack of any documen-
tation to support the Region's response,  do not provide sufficient evidence to
support its objection.  .

The Region also stated  that we were speculative in our comments concerning the
potentially detrimental  public health  effects at the Utah sites.   It is noted
that our comments  on the potential health  effects were  taken from the  appli-
cable PAs and Sis.   The specific instances of  actual environmental harm would
be documented during the RI/FS process.

Regional Project Officers Require Additional  Guidance

The Region had not developed guidance  to  assist the RPMs in the performance of
their cooperative agreement  administrative  responsibilities.   In this respect,
the Region had not established uniform RPM procedures concerning:  the official
content and organizational structure of the site project records; controls over
the receipt and disposition of work products  submitted to the Region for review
or approval; the  procedures  for reviewing the  cooperative  agreement work pro-
ducts, and for notifying recipients of the  status of the reviews.   It  is our
opinion that the establishment of formal written regional procedures would help
assure a more consistent treatment of cooperative agreement  issues by the re-
sponsible RPMs.  It appears that the Region was hesitant to invest the time and
effort required to develop the written procedures due to the  ever  changing na-
ture of the  Superfund program.  However/  the basic  steps  of the pre-remedial
and remedial phases of  the process  are well established and unlikely to  change
significantly, and therefore would only  have to  be reinforced in a guidance
package.  Except  for some  basic information,  there is  a  general  absence  of
national guidance  in the  pre-remedial area.   The regional  guidance document
could help to fill this gap.

Organization and Content of Project Files.  Our review disclosed that the
organization and  content of the Superfund project  files varied  widely between
RPMs.  Such variations  were not  unexpected,  since  the  Region had not  estab-
lished a standard for  organizing  the files  or minimum  file  content require-
ments.  We believe that the standardization  of the  project  files  would assist
                                       29

-------
management on all projects,  but would be particularly important for the large,
complex, and  controversial hazardous waste  sites.   In this  regard,  our audit
disclosed that  essential  information on  the status  of  PAs and  Sis  was  not
always readily  available  in the project  files.  In  some instances,  the  RPM
found that the information had  been  filed elsewhere.  However, there were other
cases where the  information could not  be located by  the  RPM.   Similarly,  the
project files generally did not contain  documentation summarizing the results
of telephone  calls or  discussions  which the  RPMs may  have had.   Since  the
RPMs deal with  many  issues  on a verbal  basis, it  is  important that this  in-
formation be documented  and  incorporated  into the project files.  In addition,
such documentation would be valuable  if a new RFM was assigned.

Control of Work Products.  The  Region has not established procedures to control
the receipt and transmittal  of  work  products submitted for regional review and
approval.  The work  products involved  ranged from  general  correspondence  in-
quiries concerning the  cooperative  agreement,  to  specific technical documents
such as PAs  and Sis.   The  importance of  maintaining  such a control  was evi-
denced under  the  Utah  . cooperative  agreement.   In  this  instance,  the  state
claimed that  it  had  submitted  documents  to  the Region.   However,  the Region
indicated they were  never received.   Under  the  current  system,  there was no
means of adequately  resolving this  discrepancy, since  records  controlling  the
receipt of documents  were not  maintained.   Because of the  importance  of ade-
quately protecting  the  documentation  relating to  Superfund hazardous  waste
sites in the event of future negotiation or litigation actions, we believe that
the Region should establish some minimum document control procedures.

Procedures for Reviewing frfork Products and Notifying the Recipients of
tus of the Reviews.  The Region has not established  standard procedures or time
frames for the  RPMs  to  follow  in their review and  approval  of  recipient work
products.  Instead, each RPM performed the  review function  in  their  own way.
Under these conditions, there was no  assurance  that  the reviews were consistent
from state to state.  The importance  of establishing time frames for completion
of regional reviews  was illustrated  under the  Utah  cooperative  agreement.   We
noted that, as of  September 1986, the Region was taking  an  average of 78 days
to review the PAs and Sis  submitted  by  the state.  An  update of this condition
in February 1987, indicated  that this time period had been extended to 150 days
for PAs and  reduced to  60 days for  Sis.   In  either  case,  these time periods
appear excessive,  and indicate a need for some realistic time  frames for com-
pletion of regional reviews.  In those cases  where a difficult site may require
more time, the time frames could be adjusted.

In addition, the Region had not established procedures for notifying recipients
as to the  status of the  PA  or SI reviews.   Some RPMs  discounted the need  for
this procedure and stated  that  the recipients were informed  of the status on a
verbal basis.  However,  we were unable  to substantiate this  statement, because
such information was not documented in the  project files.   In this respect,
State of Utah personnel  indicated that they had not  been informed of the reason
for delays in the  review of its PAs  and  Sis.  Since the  Utah PAs and Sis were
requiring several months to  review,  some  form of official notification is con-
sidered essential.  Another  RPM ccnrnented that when a recipient waited a rea-
sonable time and no  written comments were received  from the  RPM,  the recipient
                                       30

-------
should assume that the work product was approved.   Again, this is a poor prac-
tice, which could result in incorrect assumptions and potential embarrassment to
the Region.  In our  opinion,  the use  of a simple form letter would provide the
recipients with the  status information necessary,  and also  serve  as an effec-
tive form of documentation for the project files.

Regional Comments and Our Evaluation

Regional Comments.  The  Region  indicated that development of  program guidance
was the  responsibility of EPA  Headquarters.   It further commented  that  guid-
ance developed at the regional  level  could result  in  inconsistencies  between
regions.  The Region agreed  that standardization of  the project  files  would
be beneficial, and  stated that  such  an effort  is underway.   In  addition,  the
Region generally  concurred with our observation concerning  the review  of work
products, and indicated  that it is  in  the process  of implementing  change  by
development and use  of a model  Superfund Memorandum of Agreement.   The agree-
ment will  include a schedule of target review  periods,  as  well  as  other  re-
quirements.  The  Region  did not  respond  to our comments concerning the  control
of work products.  "       ^

PIG Evaluation.   We  considered  the Region's comments  to  be responsive to  our
recommendations.  In regards  to  the Region's  comments  concerning  the responsi-
bility for developing  program guidance,  it should  be noted  that  the  Region
modified its  position during the audit  exit conference.   At that  time,  the
Region agreed that regionally developed guidance may be  useful in areas  where
the national office was not active.

Premature Cooperative Agreement Award

Our review disclosed that the State of Utah cooperative agreement was awarded,
although the state had not fulfilled the requirements of 40 CFR 30.301.   At the
time of the  cooperative  agreement award in December 1984, the Utah Department
of Health  did not possess the  required financial,  management,  nor technical
capabilities necessary  to perform the  objectives  of  the  cooperative  agree-
ment.  40 CFR 30.301 provides that assistance will be awarded only if  the  ap-
plicant can meet certain criteria, including:

     "(1) Financial  resources,  technical qualifications,  experience, organiza-
tion, and  facilities adequate  to'carry out  the  project,  or a  demonstrated
ability to obtain these;

     "(2) Resources  to meet the  project  completion  schedule  contained  in  the
assistance agreement;

     "(4) Accounting  and  auditing procedures adequate  to  control property,
funds, and assets, as required in Subpart E of this part".

During the initial  period of performance under .the  agreement,  the  state  had
neither the technical or managerial staff,  nor the necessary accounting proce-
dures to  perform the  required  tasks.   In addition,  the state  did not  move
rapidly to acquire the required staff or skills to  adequately perform the  co-
operative agreement  requirements.  Four months  expired  before the  first pro-
                                      31

-------
gram staff member was  hired.   By the end of June 1985, the staff had increased
to four.  This  staffing level  was totally inadequate to meet the objectives of
the agreement.

Regional Comments and  Our Evaluation

Regional Comments.  The Region did not  comment on the  above condition.  How-
ever,  in  its response  to our  draft  audit report, the  State  of Utah commented
that neither the Region nor the state expected  the  objectives established in
the cooperative agreement  to  be  accomplished within  the original period  of
performance.

PIG Evaluation.  In  our opinion,  the state's response acknowledged  that  the
cooperative  agreement  was awarded prematurely.

Failure to Establish Specific Site Schedules

We found that the Region had not required the cooperative agreement recipients
to develop the  site specific schedules required  to properly  manage the status
of the  sites.   In  this regard,  the  "purple  book" states that "Prior  to  the
initiation of remedial activities at a  site  on the  NPL,  EPA will,  in close
coordination with the  state,  develop a site specific  schedule  for the site in
question.  OSWER requires  the development of  a schedule  for every NPL site."
The failure  to  develop site specific schedules appears to stem from  a reluc-
tance, on  the part  of both EPA and the  state,  to accept  responsibility  for
meeting any  scheduled  action dates.   In our opinion,  the  site  specific sched-
ules are  necessary  and  would  help alleviate  delays and misunderstandings  be-
tween the  Region and  the  states  by  establishing responsibilities.   This  was
particularly true with respect  to the Olsen-Neihart  site in Utah.   The  ini-
tiation of a site specific schedule  for  this  site  probably would have avoided
the conflict between the Region and  the  state with respect to the notification
of the PRPs.  In this  instance,  the  site schedule would  have  established  the
mutual responsibilities between  the Region and the state, early in the planning
process, and therefore avoided the lengthy delay which occurred.

Regional Comments.  The Region agreed that site  specific  schedules would be a
useful tool,  and indicated that such schedules  would  be initiated  for  each
site.
                                  t
CERCLIS Information Not Fully Accurate

Our review disclosed that the  Region's  CERCLIS  management  information system
did not  contain current or  accurate information on many  Superfund sites.   In
this regard,  the CERCLIS  did not always  indicate  whether  PAs,  Sis,  or  HRS
packages had been completed for  the NPL sites.  For example,  the Smuggler Moun-
tain, Rocky  Mountain Arsenal,  and Martin Marietta Aerospace  sites in  Colorado
did not  show that  HRS packages had  been completed for these  sites,  although
all of the  sites were included  on the NPL.   Since the  HRS  packages were  nor-
mally completed before a site was included  on the NPL, it  appeared that  this
information  may have been overlooked.  A similar  situation existed with respect
to Sis performed at the Mackay Landfill site,  and the Highland Boy Smelter site
                                       32

-------
in Utah.   In these instances,  the  SI completion dates were not included in the
CERCLIS, although  the  Sis were performed.   We believe that additional regional
efforts are  required to assure that  the site status information included on the
CERCLIS is  as up-to-date  as possible.  A  current and accurate  CERCLIS would
serve as  a valuable tool in  the  overall management  of the  Superfund sites.

Regional Comments.  In response to our draft report,  the Region indicated that
the CERCLIS  served no real purpose in  a regulatory or program management sense.
It also commented  that CERCLIS was  not used  to set regional priorities in the
preremedial  program.   Further, in the exit conference, the Region  noted that
CERCLIS was  revised and would  become the  cornerstone  of a comprehensive Super-
fund information system.

Need for Improved Working Relationships in the State of Utah

The lack of  satisfactory  progress towards the remedial phase of hazardous waste
clean-ups in Utah  has  been significantly hindered by  a strained working rela-
tionship between the. state.and the Region.
                          r-
An example  of this problem  occurred  in the  Fall of  1985  as  a result  of the
state's procurement of a well  drilling contractor  at  the Olsen-Neihart Reser-
voir site.   The  Region did not approve the award, and stated  in a November 8,
1985, letter that  the procurement was  not consistent  with 40 CFR Part 33.  The
Region therefore recommended that  the  state reprocure the  services  in compli-
ance with  Federal  procurement  requirements.   During  the next  several months,
the difference in  state  and EPA attitudes and perceptions of how the Superfund
program should  operate became clearer.  There  were   several  instances during
this period  in which the state staff seemed adamant and almost defiant in their
positions.   In a letter to the Region, dated December  2,  1985,  the Utah Super-
fund Program Manager  stated that  the  state intended to award  the contract to
the successful bidder  over  the Region's  objections.    In  addition,  the letter
also addressed  the Region's  oversight  and  coordination  under  Superfund  by
stating "...it  is  clear that  EPA  perceives its oversight  role as supervising
item-by-item all  state activities under  the MSCA."   The letter  continued by
offering this suggestion, "As  an alternative to item-by-item  supervision, the
state recommends that  EPA oversee state activities on a periodic review/audit
basis, as it does with most  delegated  programs."  The letter also cited several
examples of  the Region's  inability to  provide  the necessary time and resources
to perform  their  review of  state  activities on  a  timely basis.  Upon receipt
of this letter,  the Region informed the state  that if they were  to award the
contract without reprocurement, any costs associated  with  the procurement and
the resulting work would  not be allowed for Federal funding due to the noncom-
pliance with Federal procurement requirements.   In a  subsequent response, the
state wrote  to the Region on  January  2,  1986,  stating that "...our experience
with EPA's  Superfund process has fallen short  of a partnership.  We seem to be
more often  antagonists than partners.  After reading your letter of December
19, 1985,  I  am again  frustrated by  the whole  Superfund  process and sometimes
wonder if  it is really .in  the state's  interest to  participate."  The letter
continued, "If this is the manner  in which EPA chooses to resolve issues, then
our efforts  in Superfund are doomed  to failure."
                                      33

-------
It is  apparent that the state would  prefer to implement the Superfund program
in Utah with a minimum of intrusion and oversight by EPA.  However, because of
problems with the state's performance  under the  cooperative agreement,  it ap-
pears  that  continued  regional  monitoring  will  be necessary.   The Region has
attempted to improve the working  relationship and to  ease the state's appre-
hensions by  means of  initiating monthly visits by  the RPMs.  During the visits,
discussions  were  held  on matters of material concern and interest.  While this
is a step  in the right  direction,  the  state indicated they would  like to have
the visits  expanded to  include contact, between  the  state and EPA technical
staff  as well.

We did not  find  that  similar relationship problems  existed  with the  other
states in  Region  8.  The Utah  condition was apparently unique because  of the
attitude of  the state, and the volume  of work  which the state was required to
pass through EPA  for review and approval.   In this regard, Utah  was  the only
state  that had assumed  full  responsibilities for performing PAs  and  Sis, and
for preparing the required reports.  While  the state  and regional staffs were
aware  of their problem/  it will be necessary for the staffs to make addition-
al efforts to improve their  mutual cooperation and willingness to  work togeth-
er.  Only  in this manner can the  mutual benefits of a successful cooperative
agreement be reached.

Regional Comments.  The  Region did not object to our  finding,  but clarified
that the  Superfund  Remedial  Branch  Chief  and  the Superfund  Program Section
Chief  accompanied the RPM during the monthly visits  whenever possible.   Other
regional staff  members also attended whenever possible.   Thus, the Region be-
lieved it  was taking necessary  steps to improve  relationships  with  the  State
of Utah.

RECOMMENEftTIONS

We recommend that the Regional Administrator:

     1.  Establish  a more active regional role in the monitoring of the recip-
ients' cooperative  agreement activities.  This role  should include procedures
for initiating  actions,  including appropriate penalties and sanctions, against
the recipients  that do not perform in  accordance  with the requirements of the
cooperative  agreements.   In  this,  regard,  the performance  of  the States  of
Wyoming, Utah,  and  North Dakota  (Arsenic  Trioxide  Site)  should be  closely
monitored.

     2.  Develop  written procedures to assist  the RPMs  in the performance of
their  cooperative agreement  administrative responsibilities.   The procedures
should, as a minimum, cover:

         a.   The  official content and organizational structure of the site pro-
ject records.

         b.   The  controls over the receipt and disposition of work products sub-
mitted to the Region for review or  approval.

         c.   The  maximum time frames for the review of work products.
                                       34

-------
    d.  The  notification of recipients  on the  status of regional  reviews if
    work is not complete.

     3.  Assure that  the recipients have  the  necessary qualifications to meet
the requirements  of 40 CFR  30.301 prior to award  of a cooperative agreement.

     4.  Require  the  recipients  to prepare site specific schedules for all NPL
sites as required by  the "purple book".

     5.  Place additional emphasis on updating and maintaining the CERCLIS in a
current and accurate  condition.

     6.  Continue to  coordinate  with the State of Utah in an effort to develop
an effective working  relationship.  As a minimum, these efforts should include
more frequent  coordination  and  interchange  between the  state and  regional
staffs.

Regional Comments.  The Region  generally concurred  in the  audit report recom-
mendations.  The  Region  anticipated that its Memorandum  of  Understanding with
Utah will serve as  a  model for  similar agreements with other states within the
Region.  It also  commented that it  will continue to cooperate  with EPA Head-
quarters to develop additional staff guidance.
                                       35

-------
3 - REGIONAL OVERSIGHT OF RECIPIENT FINANCIAL MANAGEMENT SYSTEMS NEED IMPROVE-
MENT
The Region had not developed the monitoring procedures necessary to assure that
adequate financial management systems were maintained by the cooperative agree-
ment recipients.  As a result,  the Region  was not aware  that  the recipients
were not in  compliance with the Letter of  Credit (LOG)  User's Manual/ and did
not have the  information  needed to properly manage and disburse  Federal funds.
In addition,  there  was no assurance that the recipients maintained accounting
systems necessary  to  account  for  the  $6.4  million  of cooperative  agreement
funds which  have  been awarded to  date.   Specifically, we  noted that  the  Cash
Transaction Reports  (SF-272)  had not been  submitted within the  required  time
frames, and  that  the Financial Status Reports  (FSR) were  either not submitted
or submitted  late.    The  SF-272 problem was  previously reported  in an  EPA,
Office of  the Inspector  General  (OIG)  report,  issued January 27,  1986.   Al-
though the Region provided assurances that  corrective action would  be taken,
our review disclosed that the condition continued to  exist.   Additionally,  we
found that the  regional - staff were changing certified  SF-272 Reports without
written notification to the recipient.   We consider this  to be  an ineffective
internal control  procedure.   The  audit  also disclosed that the Region needed
to strengthen its review  of  recipients' accounting  and reporting  systems  to
assure that  all deficiencies  were detected  and corrected.   In this  respect,
it was noted that major deficiencies in the  State of  Utah's  accounting system
and LOG procedures  were  not  identified during a recent regional  review.   We
attributed the  above conditions to a lack of regional attention to the finan-
cial aspects  of the  cooperative agreements, including the recipients' financial
management systems.

Background

Each of the  cooperative agreements awarded  by the Region  contained  a special
condition providing  that  reimbursement under  the agreement would be by the Let-
ter of Credit method,  and that the  recipient  would comply with the requirements
of the Letter of Credit User's Manual.  The  LOG User's  Manual requires  the reci-
pient to submit a SF-272 Report within 15  working days following the  end  of
each calendar quarter.  In addition, Comptroller  Policy Announcement No. 85-5,
Financial Reporting  Requirements for Superfund  Recipients, effective  September
30, 1985, specified  that .Superfund recipients must submit an FSR within 90 days
after the  close of  the budget period.   Prior to September  30, 1985, recipients
were required to  submit an FSR within 30 days  after each calendar quarter.  If
the budget period was longer  than  one year,  the report was to be submitted an-
nually based on the  anniversary of the  budget period.  The purposes  of these
reporting requirements were to  (i)  allow EPA  the opportunity to monitor the ex-
penditure and status  of  Federal  funds under the agreements, and  (ii) assure
that cash draw downs are  directly  related and  closely timed to the actual dis-
bursement needs  of  the project.  The cooperative agreement special conditions,
as well as paragraph 25.50 of the  EPA Accounting Manual state that failure of
the recipient to comply with the  LOG requirements could result in the revoca-
tion of the  LOG and  change  to  the  reimbursable  method of financing.
                                       36

-------
Financial Reporting Procedures Not Adequately Monitored

Our review  disclosed  that the  Region's  Financial Management Division  had not
established adequate  procedures for  assuring  that  required LOG  requirements
were followed.  We  found  that 4 of the  5  cooperative agreement recipients had
not met  the  requirement for timely submission of the SF-272 Report,  and that
none of  the recipients had fully complied with the FSR submission requirements.
As previously  stated,  the LOG  User's Manual  provides  that the SF-272 Report
should be  submitted within  15 working  days following the  end of a  calendar
quarter, and the FSR should be  submitted annually within  90 days of the end of
the budget period.  Without  accurate and timely  financial  reports,  the Region
did not  have  the  information necessary to approve the  recipients'  payment re-
quests.  The extent of the reporting delays are shown in the following subpara-
graphs.

late SF-272 Reports.  We found that, of the 5 cooperative agreement recipients,
only North Dakota had submitted its SF-272 Reports within the 15-day submission
requirement.  The  following  schedule shows  that  the reports submitted  by the
other four states were from 5 to 75 days late.

                                 SF-272 Reports            Working
                        Due Date*Date Submitted    Days Late

                        01-21-86          03-18-86            40
                        04-22-86          05-07-86            11
                        07-21-86          09-15-86            40
                        10-21-86          11-19-86            21
                        01-21-87          02-04-87            10

         Colorado        07-21-86          08-07-86            13
                        10-21-86          10-28-86             5

        Wyoming         01-21-87          02-05-87            11

         Montana         01-21-86          05-06-86            75
                        04-22-86          05-06-86            10

* Includes  a  factor for the 15 days allowed by the  LOG User's  Manual  for sub-
mission  of the reports.

As shown above, Utah did not  submit the  SF-272 Report required for the quarter
ended June  30,  1986 until September 15, 1986.  For  the quarter ended December
31, 1986, the required report  was not submitted until February 4,  1987.  The
delayed  submissions did not preclude  the Region  from approving the  State of
Utah's $259,454 payment request for the quarter  ended December 31,  1986.  The
Region's payment  approval' on January  28,  1987,  was made one  week  before the
SF-272 Report was  submitted.   Similarly, by the  time Colorado  submitted a SF-
272 Report for the quarter ended June 30, 1986, the  Region had already approved
a $261,800 payment for this period.

We also  noted that the Region's  Financial Management Division has  followed a
practice of changing the recipients' certified SF-272 Reports.  While the reci-
pients were notified  of the  changes by telephone, an amended SF-272 Report was
                                        37

-------
not submitted to EPA with  the  necessary certifications.   In addition,  we found
no documentation in the files  indicating that the recipients concurred with the
changes made  by the Region.   Also,  the project records did  not indicate that
the original state  certifying  official was made aware of the changes.  For ex-
ample, the SF-272 Report submitted by the Montana Department of Agriculture, for
the quarter ended December 31,  1986, was originally certified by the Administra-
tor of the Centralized  Services  Division.   The  report was subsequently changed
by the Region without  advising the  certifying  official.  According  to a hand-
written notation on the SF-272  Report,  a person other  than the Administrator
was verbally notified of  the change.  In addition,  there was no documentation
indicating that the  recipient  organization concurred with  the adjustment.  We
believe that the the Region's practice of  changing  the  SF-272  Reports repre-
sents a poor internal control  procedure.  A more  effective  procedure would re-
quire that the SF-272 Report be returned to the certifying official for correc-
tion and recertification.

Failure to Comply With FSR Submission Requirements.  Although  the FSRs  were to
be submitted  annually,  within 90 days  of the  close of the  budget  period,  we
found that  the  FSRs  had --never   been submitted  under  cooperative  agreements
awarded to Utah, Colorado, and Montana  (Agreement No. V008416).  While the FSRs
were submitted  for  recent  periods under four  other cooperative agreements, the
submissions were late  for two of the agreements.   One  of  the FSRs  which was
submitted late  was  applicable  to the North Dakota  cooperative agreement.  Al-
though North  Dakota had an  EPA   cooperative  agreement since 1983,  it  did not
submit its  initial  FSR until  November 22, 1985.   This  FSR  covered all prior
periods through August  30,  1985.  Its subsequent  submission, covering the per-
iod ended October 30,  1985,  was   not submitted  until December 8,  1986.   A sum-
mary of  the  FSR submission  problems, through  December  30,  1986,  is included
below.
                                                  No. of FSRs
    State

  Utah
  Colorado
  Montana
  Montana
  Montana
  Wyoming
  North Dakota
   Total
 Cooperative
Agreement No.

  V008427
  V008435
  V008416
  V008415
  V008430
  V008433
  V008414
Required to be
   Submitted

     3
     2
     9
     8
     2
     2
    13
    39
   Not
Submitted

   3
   2
   9
   7
   1
   1
  11
  34
Submitted Late

none submitted
none submitted
none submitted
      1
      0
      0
      2
      3
In view of  recipients'  failure to comply with the FSR submission requirements,
the Region  did  not have sufficient information  to  effectively monitor the fi-
nancial aspects  of the cooperative agreements.   The regional FSR deficiencies
were previously  reported in DIG Audit Report  No.  P5EH5-11-0028-60470,  issued
January 27,  1986.   In its response to  the  report,  the  Region stated that "Re-
gion VT11  converted  its  letters of  credit to  the Letter of Credit Treasury
Financial Communications System  (LOC-TFCS) during the first, quarter of FY 1985.
The LOC-TFCS allows the agency 24 hours to either allow or reject draw downs on
                                       38

-------
the letters of credit.  This allows us to reject draw downs if the required re-
ports are not received."  Our current audit showed that the above procedure was
not followed.  To  the contrary, the Region has  continued to allow draw downs,
although the recipients were  not in compliance with  the  LOG  User's Manual re-
porting requirements.

Region 8 Needs to Strengthen Its Reviews of Recipient Accounting Systems

The Region has established  procedures for conducting  limited reviews of reci-
pient accounting and financial  reporting systems.   However, we  believe  that
these procedures need to  be strengthened to assure  that  all accounting system
deficiencies are detected and  corrected.  While the  limited  scope review per-
formed by  the  Region on  the  Utah  Division  of Environmental Health  (DEH)  ac-
counting system was a positive management action,  we found  that  the reported
results were  not entirely  accurate.   In this  respect,  the  resultant  report
prepared by the Region, on  July 11, 1986, contained the  following two conclu-
sions, which our subsequent audit found to be incorrect.

     1.  The report concluded that "The  recipient's  grant accounting records,
procedures, and internal controls provided acceptable records of accountability
for program funds."

     2.  The report also  concluded  that  "The recipient's  letter of credit draw
down procedures for Federal funds were adequately controlled and excess amount
of funds were not being requested."

Acceptability of the Utah DEH Accounting System.  Although the  Region's  review
indicated that the  Utah DEH accounting and internal  control  systems  were ade-
quate, our audit, which was current through  June 30, 1986, found that this was
not the case.  The  DEH had  not  implemented the accounting procedures necessary
to accurately account for its Superfund  expenditures or to comply with the ac-
counting system requirements prescribed in 40 CFR 30.510 or 40 CFR 30.301 (a) (4).
We also noted that  there were major inadequacies in the accounting system used
to record and accumulate  costs  incurred under the  $1.2 million multi-site co-
operative agreement.  These  inadequacies included (i) the use of unacceptable
labor charging and  recording  practices, which  have  allowed DEH  to allocate
employee indirect time charges  as direct labor,  and to transfer labor costs to
the cooperative agreement  from other projects without adequate documentation,
and (ii) a  lack  of  segregation of allowable and unallowable costs in the ac-
counting records.   These accounting deficiencies represent significant internal
control weaknesses which adversely affected the integrity  of the accounting sys-
tem, and  jeopardized the  Federal  government's  ability  to  recover  Superfund
costs from responsible parties.

Adequacy of Utah DEH Letter of Credit Draw Down Procedures.  The  regional  re-
view concluded that the  IjOC draw down procedures were adequate.   However, our
audit concluded that DEH  had not  complied with the DOC  requirements provided
for in the special  conditions of its cooperative agreement or in the IOC User's
Manual.  As a result, the ICC has not been effectively utilized as a means of
obtaining reimbursements  under  the $1.2  million multi-site  cooperative agree-
                                       39

-------
ment.  Specifically,  our review disclosed  that  (i)  required LOG financial re-
ports were  not submitted  or were submitted  late,  (ii)  LOG draw down amounts
were not  properly calculated,  and  (iii)  LOG draw  downs were  not made  on a
timely basis.

We believe that more  thorough  regional reviews would highlight the presence of
any such  shortcomings.   It  is noted that  since  the issuance of our Utah DEH
draft audit  report, the  Region has been working closely  with the DEH to assure
that corrective actions are  taken.   However,  the above examples illustrate that
the recipients'  financial  management systems must be more thoroughly reviewed
by the  Region to  assure that  they  are properly  able to  account  for Federal
funds and that LOG requirements are  fully met.

RECOMMENDATIONS

We recommend that the Regional Administrator:

     1.  Initiate written procedures for use  in administering the LOG method of
reimbursement.  These procedures should, as a minimum, require that:

         a.  Recipients comply with  the reporting  requirements contained in the
LOG User's Manual which  require that the SF-272  Report be submitted within 15
working days following each calendar quarter, and the  FSR within 90 days fol-
lowing the end of the budget period or on each anniversary of the  budget period.

         b.  LOG draw down requests be  rejected  in those  instances where the
above reporting requirements have  not been  met.

         c.  All SF-272 Reports requiring changes  be returned to  the certifying
official for correction and  recertification.   Under  no circumstances should the
changes be made by regional  personnel.

         d.  Consider the  revocation  of  LOG  privileges  for those recipients,
which continue  to not   fulfill the  requirements  of the  LOG  User's  Manual.

     2.  Improve the Region's  reviews of recipient accounting systems to assure
that accounting system deficiencies  are detected and corrected.

REGION 8 COMMENTS AND OUR EVALUATION

Region 8 Comments.  The  Region generally concurred  with the audit recommenda-
tions and provided the following specific comments:

     Recommendation No. l.a.   The  Region concurred  with the recommendation on
the SF-272 Reports, and stated that  written procedures were included in the LOG
User's Manual, which was  provided to each recipient.   It  also  indicated that the
regional grants  management  reviews  reiterated the  importance  of the require-
ments.  The  Region further commented  that  it maintains a tickler  file,  and
now calls  recipients to remind  them of  the  report due  dates.   Letters  are
also sent  by  the  Grants  Management Branch  to  recipients whose  reports  are
overdue.
                                     40

-------
     With respect  to the FSPs, the Region  commented  that it has implemented a
tracking procedure to monitor  the submission of the timeliness of the FSRs.  It
also indicated that  additional staff has been assigned to the Grants Management
Branch to assist in  this area.

     While the Region agreed  that  some FSRs were not submitted  or submitted
late, they did not agree with the number of  such reports discussed in the au-
dit report.   The  Region indicated that the requirement for  the  submission of
quarterly FSR reports was  not required before February 1984.  The Region also
stated that  all  overdue FSRs  had been submitted except  for one  in Colorado.
It further  commented that Colorado's  Letter  of Credit  privileges would be
revoked, if the overdue FSR was not submitted promptly.

     Recommendation  No. 1.b.   The Region  indicated that  it  was  reasonable to
disapprove draw downs, if a state was  consistently late and the number of days
exceeded 10 or more  working days late.  It did not agree that  such action was
necessary when the state had a legitimate reason.

     Recommendation  No. .I.e. .  The Region agreed that stronger internal controls
were needed.  It  also commented that SF-272 Report changes made by the Region
were very minor.   However,  its policy has  been revised and all corrections are
returned to the certifying official for approval.

     Recommendation  No. l.d.   The Region  indicated that  it  will  consider the
revocation of LOG  privileges  in cases where  there is a blatant  or consistent
disregard for the requirements.   It further commented  that the  states  were
making progress in submitting  their reports more  timely.

     Recommendation  No. 2.  The Region agreed that its accounting system review
procedures needed  to be  strengthened.   It also commented that the Headquarters
Grants Administration Division was  in the process of  developing a model check-
list for training  regional staff.

PIG Evaluation.  We  found that the Region's comments  were generally responsive
to the intended purpose  of  our recommendations.  However, the Region disagreed
with our conclusions concerning the requirement  to submit quarterly FSRs.  We
believe that  it has  been EPA policy/ since  inception of the program, to require
the submission of  FSRs on  a quarterly basis.   This  policy was  reiterated in
EPA Comptroller Policy  Announcement No.  85-5,  dated  September  9,  1985,  which
stated that "Recipients of assistance under the Superfund program were required
to submit the SF  269,  'Financial  Status Report', quarterly instead of annually
as required  for non-Superfund recipients.  This information was  required to
ensure proper monitoring and  accountability of recipients  activities during
the early implementation stages of the program.   Now that EPA's experience with
the Superfund program has grown,  the need for  this additional  reporting has
diminished.   Considering the administrative burden of this additional reporting
by Superfund  recipients, we  have reevaluated the need  for this financial data
on a quarterly basis."
                                       41

-------
                                                                         ATTACHMENT
»SB,
                     UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
y^*"^,*                             REGION VIII
  ^PR°lfc°                        999  18th STREET-SUITE 500
  QUtlu -D                     DENVER, COLORADO  80202-2405
  tiHWn-oK
                                 SEP 2 1

  Mr.  Truman  R.  Beeler
  Division Inspector General  for
    Audit
  Office of the  Inspector  General for
    Audits
  Western  Division
  U.S.  EPA
  211  Main Street, Suite 220
  San  Francisco, CA   94105

  Dear Mr.  Beeler:

       We  have completed our  review  of your office's  "Draft Audit Report
  No.  E5eH7-08-0005  Report oi EPA, Region VIII's Administration of Superfund
  Cooperative Agreements".  Our  specific comments on  the audit report are found
  in Attachment  One  to this letter.

       We  have made  a careful review of your findings and while not agreeing
  with  many of them  can certainly agree with you that we need to do a better job
  of managing this complex Superfund Cooperative Agreement program.  In fact,
 many  of  our comments will indicate the positive management improvements we
  have  made since the audit was  conducted.

       We  appreciate the effort your office expended  in conducting this audit
  and your recommendations for improving our management.  Likewise, we hope you
  appreciate our objections to many  of your findings  and will  carefully consider
 what  we  believe are needed corrections of fact.

       We  shared the draft audit report within the States in our Region.  The
 comments  we received from the  States are incorporated in our review.

       One of our major concerns with the draft audit report,  and one which we
  believe  should be  included in a modification to the final report concerns the
 draft's  inclusion of very broad conclusions drawn about Region VIII's
 management effectiveness (or alleged lack of effectiveness).  An example is
 the very  first statement in the "Summary" section that reads "The Region has
  not effectively managed the programmatic and administrative aspects of its
 cooperative agreements."  This major finding, along with others such as we did
  not perform "timely and effectively", and that there was a "lack of active
  regional  involvement", are:somewhat conjectural and not fully supported by the
  findings  of fact which make up the major portion of the audit.

       We  believe a more appropriate beginning sentence in the "Summary" section
 would read:  "The  Region needs to  more effectively manage the programmatic and
  administrative aspects of its cooperative agreements."  This sentence would
  better reflect the actual findings of the audit and our extensive comments on
 your  findings.  In addition, all  the other very broad conclusions about our
 management of  the Cooperative  Agreement program should be modified accordingly
  and put  more in conformance with the actual facts.
                                    42

-------
     Obviously our management was not perfect, but we believe the record shows
we were very much involved in working with our states to administer this
program during a difficult period.  We do not believe your audit accurately
reflects these efforts.

     Again, thank you for your efforts in helping us improve our program
management.  We would like to have an exit audit before issuance of the Final
Report.  Martha Nicodemus, the Regional Audit Coordinator, will contact your
office to make  acceptable arrangements.

                                            Sincerely,
                                             James J. Scherer
                                             Regional Administrator
Enclosures
                                    43

-------
                                  Attachment 1

EPA Comments on "Draft Audit Report No. E5e H7-08-0005-Report of EPA Region
8's Administration of Superfund Cooperative Agreements"

                        COMMENTS  ON  "SUMMARY OF  FINDINGS"

1)   Page 2, first paragraph - In reference to the IG's finding that "The
     Region has not effectively managed..." its cooperative agreements we
     strongly believe the IG must place this major conclusion in a realistic
     historical context.

     Specifically, Region VIII has experienced a number of factors which
     contributed to Regional management difficulties during the period of the
     audit.  These factors included:

          general  start-up problems with the relatively new Superfund program;

          organization and reorganization;

          inadequate staff

          technical staff turnover

          management staff turnover

          uncertain funding during the 18 month Superfund re-authorization
          si ow-down

          shifting national  priorities

          program speed-up after reauthorization

     Certainly the management of any program must expect to deal as a normal
     course with some of these factors.  However, the combination of these
     factors during the period covered by the audit had an impact on program
     management effectiveness.  We believe, however, that the facts support a
     record of active involvement in the administration of our State
     cooperative agreements as we, along with the States, have worked to
     overcome the major problems presented by the factors listed above.

2)   Page 2, first paragraph - A second finding in this first paragraph that
     "it is important that increased regional  attention be directed to the
     agreements" is one with which we can only agree.  Again, we believe our
     record - as brought out by these comments and Attachments - points out
     our efforts to increase the effectiveness of management of the
     cooperative agreement program.
                                   44

-------
     The comments below are addressed to  specific  "findings and
     recommendations", pp. 6-26.  To the  extent that they address draft audit
     "summary" statements, pp. 1-5, it should be so noted.

                   COMMENTS ON "FINDINGS  AND RECOMMENDATIONS"

1)   Page 6, first paragraph - All of the references throughout the report to
     the time taken to complete preremedial functions should be prefaced with
     a statement that for the time period covered by the audit, there were no
     EPA Headquarters or Regional requirements to complete any of the
     activities (PA, SI, HRS) within any  specified time period.  Indeed, the
     very nature of the preremedial program is one in which State and Regional
     priorities change and certain activities are started or stopped with no
     expected or required regularity.  We certainly agree that establishment
     of delivery schedules for preremedial activities is necessary.  Only
     since the enactment of SARA in October of 1986 has there been established
     the requirement for EPA to complete  PA, SI, and HRS activities according
     to any schedule.  The Region's performance prior to this time, therefore,
     was not inconsistent with any established Agency procedures, regulations,
     or statutory requirements.  Moreover, the report should make mention of
     the fact that the Region met its preremedial SPMS requirements for all
     but one of the years in question (1985) with that year's effort falling
     but a few short due to confusion about the CERCLIS data base and its
     requirements.

2}   Page 6, first paragraph - The audit makes reference to a decision that
     was delayed on proposed actions necessary to clean up arsenic, copper,
     barium, lead,  and zinc which were found at the Silver Bow Creek NPL site
     in Montana.  The audit report does not state which part of the site is
     referred to, or which actions were delayed.  We believe the auditor is
     referring to the Colorado Tailings operable unit.

     We would point out that in August, 1986, a cleanup decision was delayed
     at this operable unit for several reasons:  1) The FS concluded no public
     health problem existed; 2) lack of assured funding due to the delay in
     reauthorizing CERCLA; and 3) insufficient data to support a unilateral
     order for cleanup.  A draft,FS was completed, however, and will prove
     useful later.   The Colorado Tailings operable unit has been included as
     part of a larger operable unit for which a feasibility study is scheduled
     in March 1989.

3)   Page 6, first paragraph - In reference to the statement concerning delays
     in the RI/FS process at the Sharon Steel site, we would point out that
     EPA Region VIII has/assumed control over this process and has made it a
     Federal lead.   Federal  lead was necessitated by DOJ filing a court action
     on EPA's behalf.  A complete RI/FS is presently underway - groundwater,
     soil, and air sampling and analysis of environmental and human health
     impacts - with the RI report scheduled for completion Spring 1988.
                                 45

-------
4)   Page 7, last two paragraphs  - The report is very critical of delays in
     completion of Preliminary Assessments  (PAs) and Site Inspections (Sis)
     and implies that higher priorities should have been given to these
     efforts.  Hie report ignores the fact  that PA/SI work and listing new
     sites on the NPL was a very  low priority activity during the Superfund
     slowdown program that was in effect for a period of over a year and
     one-half.  The National program directed the Regions to put most of their
     efforts into continuing RI/FS work, and remedial actions and remedial
     designs for sites already on the NPL.  The pace of adding new sites OP
     the list was indeed not a high priority in Region VIII, nor was it a high
     priority in any other Region in EPA.   Nonetheless, we have considerably
     tightened up on the time frames for the conduct of such actions since the
     enactment of SARA.

     In addition, we would point out that during the time period covered by
     the audit, there were no requirements  for the EPA Regional  offices to
     proceed to the SI. stage for any site within any prescribed time period,
     thus making any "average number" of days between such activities an
     invalid measure of Regional performance.  To then make the leap that such
     an average number of days somehow precluded "timely assessments of the
     degree of severity of the hazardous waste problems at the affected sites"
     is unsupportable by any evidence that  an imrnminent or substantial  threat
     was posed by any of the sites which were examined during the draft audit.

5)   Page 8, first full paragraph - EPA Region VIII agrees that a mutually
     acceptable delivery and review schedule for EPA review of State
     deliverables is needed and such has been arranged in at least one State
     via conclusion of the EPA-Utah Superfund Memorandum of Agreement (SMOA).
     A copy of the SMOA is Attachment 2.  Time frames and review procedures
     will be instituted for other Region VIII States patterned after the Utah
     SMOA.

6)   Page 8, second and third full paragraphs - The audit report is critical
     of the Wyoming cooperative agreement since the State lost an employee and
     was unable to fill the position immediately.  The report fails to
     recognize again the slowdown phase that we were in, even though it does
     recognize that we utilized the FIT contractor to perform PAs in that
     state in order to continue progress.   Wyoming's decision not to hire a
     Superfund person is clearly within the State's rights.   You should refer
     to attachment 3 for Wyoming's explanation of their situation.  EPA
     resumed preremedial work in the State when it was clear that EPA
     contractor resources would again be available and that the State would
     not in the meantime hire and resume work itself.

     Also on page 8, (last full paragraph), it is stated that the South Dakota
     cooperative agreement was not awarded  until April 1987 even though it was
     requested in May of 1986.  Again, it was not stated that there was no
     national money available for this activity until March of 1987.  The
     Region should be commended for its quick obligation of funds when they
     became available.
                                 46

-------
7)   Page 8, last two sentences and p.  9,  remainder of paragraph - The
     reference to how long it took for  certain  sites to move from the PA to
     the SI stage can be attributed to  two major  factors:  1) the lack of any
     requirement that sites  "move" from PA to SI  within any specific time
     period, and 2) the limit on resources given  Region VIII EPA to do Sis  (a
     function of the workload model which  assigns resources based on annual
     SPMS targets established by Headquarters).   The draft audit fails to
     acknowledge that EPA met or came close to  meeting its SPMS targets for
     Sis in each of the years examined.  The Region was clearly addressing
     those sites which had the highest  collective priority of EPA and the
     States.  That other Sis still need to be done is not the issue.  EPA will
     be doing Sis for the next several  years.   Instead, the report should
     acknowledge that the Region accomplished the SI review of its priority
     preremedial sites in the years examined.

8)   Page 9, second paragraph - There is a comment that "neither the state nor
     regional personnel considered the  PA  process to be of a high priority".
     We disagree.  Region VIII has considered the PA process to be a priority
     in as much as our annual SPMS targets (which measure the priority that HQ
     places on this activity) have been met given the limited resources
     provided.

9)   Page 9, second paragraph - In regard  to the  time factor, refer to our
     comment number 1.

10)  Page 9, last full paragraph - In regard to the time factor, refer to our
     comment number 1.  We agree that written guidance concerning the
     performance of an SI is necessary.  This guidance should be prepared by
     EPA Headquarters to insure consistency from  one EPA Region to another.
     The Region has been and will continue to be  hardpressed for resources to
     prepare such guidances.

11)  Page 10, second to last paragraph  - The draft audit comment that SI
     conclusions which note  "that additional site sampling should be
     performed" are "not an acceptable  conclusion" is contrary to National
     Superfund program experience in dealing with potentially hazardous waste
     sites.   EPA site inspections, frequently reach such a conclusion even
     after six years experience with the program.  There are simply too many
     unknowns at the time of site inspections to  believe that a small  number
     of original samples can effectively capture  the nature of the threat
     posed by any site.  EPA and the States continually revisit sites for SI
     followup work.  Indeed such a category of  activity (SIF - or Site
     Inspection Followup) was created by EPA HQ to track time spent on such
     needed activities. •.

12)  Page 10, last full paragraph - The audit information on the Old Sioux
     Falls Landfill did not reference that at the time this SI was conducted
     there were no requirements that sampling be  done at site inspections.
     There was simply no guidance from  HQ.
                                  47

-------
13)  Pages 10-11, last paragraph of page 10, first paragraph of page 11, -
     Sampling was not done at the St. Regis Paper Co., So. Dakota site because
     it was not required by any guidance at the time.

14)  Page 11, first full paragraph - Region VIII agrees that additional
     regional training on the techniques of performing an SI is required.
     Such training was provided to the State of Utah earlier in FY 87 and will
     be provided to any other States who desire to take on the lead for SI
     work in future years.  As noted earlier, the Region has not been and is
     not now in the position of being able to unilaterally devise written SI
     instructions or guidance as the draft audit report suggests should be
     done.  Regarding the monitoring of State progress under cooperative
     agreements, the draft audit report should note that Region VIII did
     monitor via quarterly reports those activities conducted by States with
     Superfund monies and requested such reports be submitted whenever there
     was a delay.  In Utah's case, the issues surrounding the submission of
     quarterly and financial reports have already been discussed in the audit
     of that State's cooperative agreement.  North Dakota, Colorado, and
     Wyoming preremedial deliverables have been routinely tracked by Region
     VIII staff, in a close, cooperative working relationship with those
     States.  The draft audit report should also note that the preremedial
     work done by South Dakota during the period of this audit review was not
     done under a CERCLA cooperative agreement but rather under a RCRA 301?
     grant, with its much less specific reporting requirements.  Now that the
     State of South Dakota is fully funded under a CERCLA cooperative
     agreement, Region VIII and the State are working closely to accomplish
     the mutually agreed upon preremedial workload remaining in the State.

15)  Page 12, last paragraph - The State should be commended for Us
     initiative in pursuing legal action and negotiations with the Wasatch
     PRPs.  At the time the State took this action, EPA had not yet proposed
     the site for listing on the NPL.  Therefore, the site was not eligible
     for fund money for the conduct of the RI/FS.  The State action was the
     only option available.  The State has continued these negotiations since
     listing on the NPL in accordance with a recently signed Site Enforcement
     Agreement with EPA.
                                 >
     Based on EPA's RCRA/CERCLA NPL listing policy, EPA Headquarters has
     determined that only the Lot 6 portion of'the Wasatch Chemical Site can
     be listed.  This limited Wastch Lot 6 site has been proposed in the
     Federal Register for public comment.

16)  Page 14, first paragraph - The report notes that EPA Headquarters urged
     the Region to conduct more sampling at the Silver Creek Tailings site and
     that the Region initially refused.   EPA Region VIII has always supported
     the collection of additional data at the Silver Creek Tailings site.  The
     Region and Headquarters disagreed over the timing of additional data
     collection.  It was the Regional position at the time that the original
     flawed HRS package should be identified as such by timely action on the
     NPL listing; then additional data collection to resco're the site could
                                 48

-------
     proceed.   As  the  data  from  the  site  indicated  the  potential for long term
     problems rather than an  imminent and substantial endangerment to those
     living around it,  this seemed an appropriate course of action.  EPA
     Region VIII did decide in the fall of 1986  to  move forward with
     additional data collection  because it had become clear that final action
     on the MPL listing was not  occurring and only  a well-designed,
     well-executed technical  study would  answer  the concerns that had been
     raised.  The  site was dropped from the NPL  by  the  SARA amendments in
     October 1986.

     Also, the  conclusion regarding  aquifer interconnection in the HRS package
     was  supported both by the State (at  the time the SI was completed) and by
     EPA  (at the timeThe HRS was completed).

17)  Page 14, second full paragraph  - The reference to  a "preliminary HRS
     score of 79.15" should note that until  a site  is formally nominated by a
     Region, a  score remains  tentative subject to quality control and quality
     assurance  review.  In the case  of the Kennecott Tailings draft HRS
     packages prepared by the State  of Utah, the score  of 79.15 could not be
     documented or otherwise  supported and the draft package was returned to
     the  State  for reconsideration.   The  Kennecott  tailings will be resampled
     by the State  under an expanded  site  investigation and HRS to be funded by
     the  Region in FY 88.  There is  no evidence  to  support the statement that
     "we  sense  a reluctance by the Region to list the site on the NPL because
     the  PRP was voluntarily  conducting some groundwater studies of the
     general area  of this site."  We have repeatedly told the State that it is
     our  intent to proceed with listing of the site should site data be
     obtained to support such a listing.

     We have only  been concerned with  the quality of the data to document
     listing on the NPL in order that we  may ultimately prevail in our
     action.  We certainly agree with  the report's  recommendation that the
     Region directly take the lead on  the listing of the Kennecott facility if
     this becomes  necessary.

18)  Pages 15-17,  paragraphs  referring to the Mi 11 town and Silver Bow Creek
     (SBC) sites.   In general, the audit  report  fails to account in its
     evaluation for two important factors:

a.   The one year  delay in reauthorization  of CERCLA resulted in carrying out
     only the most critical  Super-fund  activities during FY-86 and half of
     FY-87.  The Montana CAs  reviewed  by  the auditor covered only remedial
     investigations feasibility studies (RI/FS), and pre-remedial
     activities.   Funding of these  CAs (as well as other RI/FS activities)
     received low  priority during the  slowdown,  and progress was significantly
     slowed.
                                 49

-------
b.   The Silver Bow Creek (SBC) and Milltown sites are part of a complex chain
     of four sites on the Clark Fork River, each one in itself complex.   EPA
     has currently identified 77 separate operable units among these sites.
     It was not until well after these sites were listed on the NPL that EPA
     realized how complex the interaction among these sites really was.   For
     example, the SBC site was envisioned as only 25 miles long when listed.
     Now, it appears to be more properly 120 miles long, and includes the
     entire city of Butte. This realization has meant realignment and addition
     of priorites at all four sites along the Clark Fork River.

19)  Page 15, first full paragraph - The report states the conclusion that the
     Region does not manage Superfund activities but instead allows the  State
     agencies to move at their own pace.  We disagree.  The Region is not
     content with the pace of the State activities in CERCLA.   We are on
     record in several States, by evidence of the IG's own data in this
     report, to push states to be more efficient and more timely in the
     conduct of their Superfund activities.  This is clearly illustrated by
     the Region solving the problem of the North Dakota cooperative agreement,
     as well as our insistence in the State of Utah that project schedules be
     expedited even to the detriment of our relationships with that State.

20)  Page 15, and also pages 18 and 19, paragraphs concerning  the Milltown
     site -  We question the contention that "completion of the remedial
     investigation/feasibility study for the Milltown site is  significantly
     behind schedule".  This observation is presumably based on guidance
     timelines for RI/FS activities.  However, as noted in the IG findings,
     more than one phase of RI/FS activities has been conducted at the
     Milltown site.  The first phase identified the need for an alternative
     water supply for persons whose private wells were contaminated by the
     Milltown materials.  A Record of Decision was signed for  this action in
     April  1984 and expanded in August 1985.  Subsequent to this initial  ROD
     another phase of investigative activities was initiated,  to coincide with
     preparation of a feasibility study for the final  remedy.   Therefore, the
     appropriate start date for the current RI/FS activities should not  be
     from the date of site listing on the NPL, nor the initial  cooperative
     agreement with the State of Montana.  The start date should be the
     initiation of the current phase of activities, approximately April  1985.

     Concerning the IG's statement that "This condition, in addition to  poor
     quality of work, ultimately led to a termination of HLA's contract  by the
     state in February 1986," and the IG report quoting a State quarterly
     report as saying "The draft FS report was received on 11/13/87",  we would
     reply that the dates presented in the IG report are incorrect and
     misleading as to the; progress of the Milltown site activities.
     Termination proceedings were initiated against HLA in February 1987, and
     the draft FS report was received on 11/13/86.
                                  50

-------
The significance of these errors lies in the realization that the
termination proceedings only began this year and were initiated by the
State within three months of the true date of receipt of the faulty FS
report.  Re consider this reasonable given the legal and technical
determinations which must be made prior to initiating those proceedings.
We anticipate the ensuing termination activities will take a substantial
amount of time to finalize.  In the meantime, the EPA Montana Office is
exploring with the State a means of continuing the RI/FS without waiting
for termination proceedings to be completed.

Concerning the IG's contention that the Region was not aggressively
monitoring performance aspects of the cooperative agreement and was
"content to allow the state agencies to move at their own pace."  We
would point out that documentation is available in the project files
which clearly indicates that the Agency was monitoring the State and
contractor activities on a timely basis.  Some evidence of this is the
presence of quarterly status reports submitted by the State; minutes of
meetings held between Jthe Agency and the State to discuss site progress,
including termination proceedings; and memos from the EPA Remedial
Project Manager to the State addressing poor contractor performance.
(Examples are found in Attachment No. 4).

More significantly, it was noted in the IG findings that the EPA
attempted in early 1985 to change the Mi 11 town site from a State-lead to
a Federal-lead project in an effort to expedite RI/FS and, ultimately,
remedial action activities.  This effort, initiated by EPA as a result of
schedule slippage, was unsuccessful because of the strong political
opposition.

On page 19 of the audit report it is stated that the Region did not
require CA recipients to establish site specific schedules.  This
observation applies to Mi 11 town CA, and we believe it to be an accurate
critique.  Strict schedules included in the cooperative agreement would
allow both CA signatories to monitor project status independently and
objectively.  A schedule for future activities will be included in the
next CA for the Milltown site, which is anticipated to be finalized the
1st quarter of FY 1988.

Concerning the IG's recommendation that "...special attention should be
given to expediting action on the (among others) Milltown Reservoir
Sediments site", (page 19), we would reply that, as discussed above, EPA
and the State are currently exploring ways to continue the RI/FS without
waiting for contractor termination proceedings to be complete.  However,
termination proceedings will need to be completed before the RI/FS can be
considered final.  The'principal reason is that a large amount of data
has already been collected, and the quality of this data will in part
determine how much additional data must be collected.  The State is
attempting to obtain all of the data acquired by the contractor and this
has proved to be a difficult task.  Once obtained, all data will require
                               51

-------
     validation to determine what contractor costs and fees are justified.
     The REM  II oversight contractor for the project has been tasked with
     validation duties, but has fallen seriously behind schedule in these
     efforts, due to prioritization of REM II site assignments and a shortfall
     in level of effort hours available.

21)  Page 16, paragraphs on the Arsenic Trioxide site - In reference to  the
     second paragraph, the Region's main objective in not taking back the
     Arsenic Trioxide project from the State of North Dakota was to attempt  to
     put the project back on schedule and to build State capabilities for
     future work, not to maintain good State/EPA working relationships as
     stated.  The success of the Region in achieving this objective is
     testimony to the appropriateness of our action.

     In another sentence in the second paragraph it is stated that "Obviously
     the State of North Dakota did not attach a very high priority to the site
     since they did not assign other State personnel  to work on the project."
     We find this statement speculative on the State's motives and believe it
     should be deleted.  Direct contact by the IG with North Dakota Superfund
     administrators on this issue may well be appropriate.

     The sentence in this same paragraph that states "A ROD for Lidgerwood was
     not expected to be completed before September, 1987, because of a
     controversy over the funding of its water supply" should be clarified.
     The controversy and delay resulted from a change in EPA HQ policy.
     Originally, HQ said there would be no funding for water treatment works
     built to comply with requirements of the Safe Drinking Water Act.   Later
     this policy was changed.

     Also, the comments on the Lidgerwood ROD should note that the decision
     even to do a ROD for the already completed Lidgerwood action was not made
     until halfway through the FY 87.   The actual  completion of the ROD  at
     this location has absolutely no bearing on any real  or potential  health
     risk, as the population of Lidgerwood is already being served by an
     alternative water system.   In addition,  the Region has decided to
     continue treating this site as a Fund lead site and has not named the
     State or Federal  government as responsible parties.

22)  Pages 16-17, paragraph on the Silver Bow Creek site - The audit report
     states that the Silver Bow Creek (SBC) site has been on the NPL since
     September 1983, and that the RPM estimated that an RI/FS study period of
     5 to 6 years, at a minimum, would be necessary.   The audit states that
     this constituted insufficient progress.

     The audit report appears  to confuse the  effort and dates associated with
     the Butte addition with those of the remainder of the SBC site.   It
     apppears that the auditor spoke only to  the RPM assigned to the Butte
     portion of the SBC site.   Additionally,  the report does not recognize
     several other important factors.
                                52

-------
     As the/audit has acknowledged, the Butte portion (the 9 additional  miles)
     was not added (actually, proposed to be added to the NPL) until  March
     1986.  EPA began forward planning activities (scoping of the RI) in
     Septmeber 1986,  or soon therafter as resources became available.  The
     Butte portion of the SBC site, an extremely complex mix of public health,
     ground water and political issues, consists of a town of 35,000
     residents, a 4,000-mile maze of underground mine workings, and an
     abandoned open pit copper mine.  It may indeed take much more that the
     "normal" RI to arrive at a workable, cost effective, and protective
     remedy for such a site.

     The remainder of the SBC site is equally complex.  Its boundaries extend
     from the town of Butte to Milltown Dam, approximately 120 river  miles;
     substantially more than envisioned when the site was listed on the NPL  in
     September 1983.   (The audit report describes the original site as being
     15 miles long and downstream from the confluence of the Clark Fork River
     and Silver Bow Creek.  The original site was 25 miles long, and  was
     upstream of the confluence.)

     Initially, the State prepared an RI/FS work plan totaling $1.4 million.
     EPA had only $850,000 available at the time.  Slightly more than a year
     passed while the RI/FS work plan was modified to address priorities and
     funding limitations, and while the EPA Region VIII struggled to  obtain
     the full $1.4 million.  Portions of the RI/FS were initiated in  the
     spring of 1984.

     However, during the delay in reauthorization of Superfund, few
     substantial tasks were undertaken during FY-86 and half of FY-87, with
     the exception of those at the Colorado Tailings operable unit.  Lack of
     assured funding and the constant need to stretch thin resources  even
     thinner during this period, resulted in little ability on the State's and
     EPA's part to commit to funding a long-term effort.  Additionally,  two
     consecutive drought years have prevented the collection of hydrologic
     data necessary to complete the RI.  Completion of the RI/FS has  also been
     delayed because of the need to modify the original RI/FS work plan to
     meet the evolving requirements of guidance, SARA, and the NCP.

23)  Page 17, paragraph on the Sharon Steel site - As previously stated in
     these comments,  EPA Region VIII has assumed the lead on the Sharon Steel
     site and a compete RI/FS is well underway.  Also, our major reason for
     taking back the lead on this site was because of our involvement in
     Federal litigation, not lack of progress.  The statement that "lack of
     action (by State) resulted in EPA taking back the lead ..." is
     inconsistent with EPA's representations to the State.

     EPA placed the Sharon Steel RI/FS on hold in the spring of 1986  pending
     conclusion of EPA's negotiations with the PRPs.  (At the time the State
     assumed the lead, EPA advised the State that EPA would later be
                                      53

-------
     negotiating with PRPs, but would not allow that to delay the RI/FS).
     Prior to concluding those negotiations, in October, 1986,  EPA initiated
     litigation against the PRPs, including a claim to enjoin the PRPs  to
     conduct the RI/FS.  In February 1987, EPA advised the State  that because
     EPA had initiated litigation against the PRPs and needed to  control the
     RI/FS in order to meet court imposed information requirements,  EPA would
     assume the lead for the RI/FS.  At that time and since,  EPA  has advised
     the State that EPA as a matter of policy assumes the lead  for RI/FSs  in
     every instance in which EPA initiates litigation.

24)  Pages 17-18, "Recommendations" -
     la and Ib - The Region has adopted the national  program  emphasis on
     meeting the PA and SI goals of SARA, schedules and goals which  did not
     exist for the preremedial  program during the time covered  by the audit.

     Ic - The Region will  be improving the monitoring of work performed under
     State cooperative agreements although a formal 'approval  role for PAs  and
     Sis will not exist.  The Region and HQ will  maintain,  as always, an
     approval role over all HRS packages prepared by States under cooperative
     agreements.

     Id - The Region will  not have an'approval  role over State-prepared Sis
     per the example established in the EPA-Utah  Superfund Memorandum of
     Agreement recently negotiated.  All applicable guidance  on the  conduct of
     Sis will be provided  to the States once Region VIII has  received such
     from HQ.

     le - Region VIII will  review and comment on  sampling plans prepared by
     the States, but there is no 'approval role for EPA per the  terms of the
     recently developed SMOA with Utah,  We expect that the Utah  SMOA will be
     used as the model  for other such agreements  in Region VIII.

     If - Region VIII will  continue to provide training to State  personnel in
     all  aspects of the preremedial program for which guidance  and criteria
     have been established.

     Ig - Recommendation is made that the Region  take immediate action  to
     assure that the complete Wasatch Chemical  site is  recommended for
     inclusion on the NPL.   The Region has, in fact,  on more  than one occasion
     recommended in writing that the entire Wasatch chemical  site be placed on
     the NPL.  The Region  has discussed this issue with EPA Headquarters in
     the context of the RCRA/CERCLA NPL listing policy.

     Ih - The Region agrees with this recommendation  and has  had  a full time
     staff person dedicated to  the quality control  review of  HRS  packages
     since January 1986.
                                 54

-------
     li - The Region intends to award the State of Utah a cooperative
     agreement in FY 88 which provides funding for a State-lead expanded site
     inspection at the Kennecott Tailings site per the State's request.

25)  Page 19, the middle of the paragraph - It is stated that the cooperative
     agreement program is managed by the State programs section of the Air and
     Waste Management Division.  This is the incorrect name of this Division,
     which was originally restructured in February of 1985.  This Division's
     correct name is the "Hazardous Waste Management Divison".

26)  Page 20, top of the page - It is stated that the Region is reluctant to
     initiate effective oversight of the State's activities.  We disagree.
     The Region wants effective oversight of State activities in the conduct
     of its responsibilities under Superfund and we intend to improve our
     performance.  The Region's insistence in the State of Utah that it
     perform in accordance with its agreement in spite of the damage it  did to
     the State - EPA relationship illustrates the Region's intent in carrying
     out its responsibilities.  Also, the auditor's opinion concerning giving
     the States "wide latitude" neglects to mention that the Region is only
     provided .004 FTE in the workload model for each PA and .015 FTE for each
     SI conducted per year in the region, whether by FIT or the six Region
     VIII States.  We have given the States and the preremedial  program
     consistently more staff effort than the limited FTE allowed by the  HQ
     model for this activity.

     With respect to page 20, in the second paragraph, the Region did not sit
     idly by during the time that the State lost an employee in Wyoming  for a
     period of 9 months.   We were, after all, in a slowdown period and we were
     limited in our ability to respond effectively using the FIT contractor.
     In addition, the report seems to reflect that unless we have a written
     record in the file,  that we never discuss our concerns with the State.
     The fact of the matter is that the Division Director of this program
     personally discussed this with the Head of the Department of
     Environmental  Quality of the State of Wyoming on at least two occasions
     and was able to get a commitment to have this position filled in spite of
     a State freeze on hiring.  In addition, Regional staff also had several
     conversations with the State expressing concern over the inability  of  the
     State to promptly fill this vacancy.

27)  Page 20, last full  paragraph - The comment that "these conditions could
     have a detrimental  affect (sic) on the public health and safety of  area
     residents" is speculative if not incorrect in its absence of any
     supporting documentation of such a "detrimental  affect."

28)  Page 21, first paragraph, North Dakota - It is again stated that the
     Region had a passive attitude with respect to the accomplishment of the
     program objectives.   We disagree.  The Region, in fact, took aggressive
     action to correct the problems in North Dakota and ultimately was
     successful  in its efforts.  In the middle paragraph, we do not accept  the
                                  55

-------
     criticism implied that although the Region considered the application for
     a cooperative agreement in South Dakota to be acceptable, it was unable
     to make an award because of a lack of funding.  Clearly,  this was not a
     priority activity of Regions during the slowdown phase of Superfund.  Use
     of the FIT contractor seemed the reasonable approach and certainly was in
     agreement with the national guidance to not award any cooperative
     agreements during the slowdown phase.

29)  Page 21, last full paragraph, South Dakota - The comment that the Region
     should have made "alternative funding arrangements" fails to capture the
     realities of the time period.  First, EPA cannot unilaterally terminate
     cooperative agreements without strong evidence of State malfeasance.
     Regional and State concurrence on any deobligations were therefore
     required and unlikely at the time.  The Region, moreover, had little to
     no guarantee that any funds deobligated (even assuming mutual agreement)
     would have been returned to the Region for allocation to some other
     State.  HQ, in fact, was at the time looking to deobligate monies from
     CAs to use elsewhere in the program (contractors, CLP, etc.) and there
     was almost a certainty that deobligated State CA funds would not have
     come back to the Region.

30)  Page 21, last paragraph - The Region did not develop RPM guidance related
     to CA oversight because that was a national responsibility represented in
     the State Participation in the Superfund Remedial Program Manual (Purple
     Book).  The quarterly report and review procedures were those established
     at the national level and adopted by the Region in its management of the
     CA process.  It would have been counterproductive to the national
     Superfund program to establish regional-specific requirements that could
     have allowed the Agency to be easily challenged on a national consistency
     basis.  A regional guidance document would have been a reckless effort in
     the light of this risk.

31)  Page 22, first full paragraph - The Region agrees that the
     standardization of project files would assist the management of all
     projects and such an effort is underway, funded as it has been in FY 87
     by the availability of funds under the reauthorized statute.  Such
     support funding was not available prior to this time.

32)  Page 22, bottom paragraph - In regard to the time factor, refer to our
     comment number 1.  The emerging SMOA provisons will establish target
     review periods, noting that there will always be occasions when even
     these targets will have to be missed.

33)  Page 24, last paragraph - The criticisms of the CERCLIS data base should
     note that until late FY 87 the CERCLIS system was used only to report PA
     and SI SPMS accomplishments.  The dates of HRS packages might have helped
     fill data gaps created by CERCLIS originators, but served no real purpose
     in a regulatory or program management sense and as such received little
                                     56

-------
     attention by the Region.  We have determined that several PA and SI
     reports have been completed but not entered on CERCLIS, but again the
     program did not suffer as a result.  Current site status information on a
     HQ data base was not the basis for setting Region preremedial  priorities
     in the early years of the program .  The Region met its national targets
     and in the process addressed those sites of most concern to EPA and the
     States at the time.

34)  Page 24, first paragraph, - It is stated that the Region did not meet
     cooperative agreement requirements in awarding the Wyoming cooperative
     agreement since the State employee who worked on the agreement ultimately
     resigned.  We fail to understand this criticism.  Certainly, the State
     had the capability when the award was made.  If we followed the reasoning
     in the I.G.'s report, we would not make any cooperative agreement awards
     to any of our small States, including South Dakota, since there is a
     possibility that there may be turnover and need for extension  of project
     periods to accomplish' the work.

35)  Page 25, last full paragraph - The IG mentions monthly visits  with Utah,
     but states that only RPM's attend.  This is not accurate.  The Superfund
     Remedial Branch Chief and the Superfund Program Section Chief  always
     attend these monthly meetings.  Also, as needed, other Superfund section
     chiefs and Regional Counsel staff will attend.

36)  Page 26, Recommendations - The Region acknowledges many of the goals
     contained in these recommendations.  The Utah SMOA in attachment 2 is the
     model  which we will use to improve and strengthen our administration of
     Superfund cooperative agreements.  We will continue to work with EPA
     Headquarters to develop appropriate guidance for the State and EPA staffs.

37)  The remaining comments are made on the audit's findings concerning Region
     VIII's financial management systems:
                                   57

-------
FINDING  NO.  3  -  Regional Oversight of  Recipient Financial Management Systems
                 Need  Improvement


     Auditor's Recommendation 1
1.    Initiate written procedures for use in administering the LOG method of
      reimbursement.  These procedures should, as a minimum, require that:

      a.   Recipients comply with the reporting requirements contained in the
          LOG User's Manual which require that the SF-272 Report be submitted
          within 15 working days following each calendar quarter, and the FSR
          within 90 days following the end of the budget period or on each
          anniversary of the budget period.

      Region's Response

      Late SF-272 Reports:

      We concur with the auditor that states were late in submitting their SF
272 reports.  However, ourranalysis shows that the number of days reported in
the audit finding is overstated since it is based on calendar days instead of
working days.  This resulted in a variance of 4 to 68 days instead of the 7 to
105 days as indicated in the finding.

      Written procedures are included in the LOG users manual which is provided
to each assistance recipient.  The recipient is also made aware of the
requirements when a review is made by the Grants Management Branch personnel.
Internal control procedures include maintaining a tickler file, calling
recipients prior to the due date to remind them of reporting requirements,
notifying the Financial Management Officer of late respondents who in turn
informs Chief of Grants Management Branch.  Reminder letter(s) will be sent by
the Grants Management Branch to recipients whose reports are overdue.

      Failure to Comply with FSR Submission Requirements

      We concur with the auditor that annual FSR's for Superfund Cooperative
Agreements (CA) were not submitted within the required 90-days of the close of
the budget period.  We have implemented a tracking procedure to monitor
submission of all program grant FSR's which includes a series of three
progressively emphatic reminder letters to each of the recipients (see
attachment).  Since instituting this procedure, timely submittal of FSR's in
program grants has increased significantly.  Superfund recipients' reports
will  be more aggressively monitored to ensure that they meet the regulatory
due dates.  An additional FTE has been assigned to the Grants Branch Superfund
program to assist in this area.  The person is on board and is developing a
tracking system for administrative requirements of Superfund cooperative
agreements.

      The auditor makes reference to a previous DIG report dated January 27,
1986, regarding timely submission of FSR's and states that the Region had
assured the DIG that corrective action would be taken.  Although the Region
certainly agrees that timely FSR's are important to financial management of
the cooperative agreements, we believe the statement that this issue was
included
                                    58

-------
 in the referenced DIG report  is inaccurate.  The issue of late SF 272 reports
 was raised in  that  DIG  report, and  the  Region instituted the LOC-TFCS system
 to reject drawdowns on  the letter of credit if the SF-272's were not received.

      We have  taken action and will continue to take action against those
 states that are late in submitting  their FSR's.  For example, the Assistant
 Regional Administrator  for Policy and Management made a trip to Utah last year
 to talk directly with the Director  of the Division of Environmental Health
 regarding late submission of  their  FSR's.  He told the Director at that time
 that we would  be forced to institute sanctions against the state if they did
 not improve their timeliness  in this area.  Since that time, the reports from
 Utah have been submitted much more  promptly for their program grants,   More
 attention will be devoted to  Superfund  FSR's in the future since we have an
 additional person in the Grants Branch  to monitor this activity.

     We.do not agree with the auditor that 39 FSR's were required to be
 submitted through December 30, 1986.  The auditor's report states that FSR's
were to be submitted annually, within 90 days of the close of the budget
 period.  This  is consistent with the General Grant Regulations applying to all
 assistance agreements which require that FSR's be submitted within 90 days
 after the end of the budget period.  In reviewing the Superfund Cooperative
 Agreements, we noted a  special condition which required the States to submit
quarterly progress reports, but this should not be confused with the SF-269
 Financial Status Report.  If  the auditors believe that quarterly FSR's were
required from Superfund recipients on a quarterly basis from inception of the
 program through September 1985, please  indicate where you found such a
requirement.   Otherwise, the number of  FSR's listed in the draft audit report
could not be correct, e.g. 13 reports due from North Dakota.

     Our records indicate the following annual FSR's were required during the
period covered by this audit:

               Cooperative          FSR's          FSR's    FSR's Submitted
State          Agreement No.      Required       Submitted       Late	

Utah           V008427              2                 1              1
Colorado       V008435              2                 00
Montana        V008416              3                 3              1
Montana        V008415              3                 3              1
Montana        V008430            - 1                 1              0
 N. Dakota      V008414              4                 20
Wyoming        V008433              1                 1              0
   TOTAL                            16                11              3

     Since the time the audit was performed, all  overdue FSR's have been
submitted with the exception of one in  Colorado.   We are making efforts to
obtain this outstanding FSR and are considering cutting off the Letter of
Credit privileges for this State under  the Superfund program if it is not
submitted promptly.
                                    59

-------
     Auditor's  Recommendation l.b.   LOG  draw down requests be rejected in
those instances where the reporting  requirements have not been met.

     Region's Response

     The Region does concur with the auditor's finding that no LOG drawdown
requests were rejected when reporting requirements were not met.  The decision
for not rejecting drawdowns was based on the fact that the states had a low or
negative cash balance and had significant sums of money due them.  Since the
states were being reimbursed for their expenses and not receiving advances  as
many states do, the Region did not believe it was appropriate to withhold
funds.  During the audit period, the Financial Management Section personnel
checked the drawdown request to determine if the recipient had a low cash
balance on hand and/or if a large sum was due.  If this was the case, the
drawdown request was approved.  The  present procedures include the above steps
with modifications to the approval step.  If no response is received from the
recipient to the reminder letters on timely submission of the required reports
(see paragraph l.a.) the Grants Management Branch Chief will  notify the
Financial Management Officer to reject drawdowns on letter of credit until  the
reports have been received.  The reminder letter for SF 272 reports will  give
the recipient ten (10) working days  from receipt of the letter to respond.

     It appears reasonable to the Region to disapprove drawdowns if the state
is consistently late and the number  of days Is significant (10 working days).
It does not seem reasonable to take  this action with a state who has a
legitimate reason, such as Wyoming.  Wyoming consistently submits its reports
before the due date.  The exception  noted in the audit report was due to the
shortage of staff when the person assigned to submitting the reports was on
maternity leave.  When she returned, the reports were again submitted timely.
Reasonableness should be a factor in rejecting drawdowns.

     Auditor's Recommendation I.e.   All SF-272 Reports requiring changes be
returned to the certifying official  for correction and recertification.  Under
no circumstances should the changes  be made by Regional personnel.

     Region's Response

     The Region does agree that stronger internal controls are needed.  The
regional personnel did in fact make,  changes, however, in most cases they
believed the changes were very minor.  The Region's current policy is to send
back all corrections to the certifying officer.  In Montana, there are 3
certifying officers who are contacted when a change needs to be made.  In the
case referenced 1n the audit report, the document was sent to the certifying
official contacted by phone who may  not have been the certifying official
signing the original document.  The  Region is now sending changes to the
certifying official signing the document.

     Auditor's Recommendation l.d.   Consider the revocation of LX privileges
for those recipients which continue  to fail to fulfill the requirements of the
LOC User's Manual.

     Region's Response;

     The Region will always consider this action in cases where there appears
to be blatant or consistent disregard for the requirements.  We have


                                     60

-------
considered this action already e.g., Utah, and will  take it again when the
situation calls for it.  However, with one exception, this action does not
appear to be justified at this time.  The States are making an effort to
submit their reports in a timely manner and are calling or writing to inform
the Regional Office of the reason for being late.

     Auditor's Recommendation 2

     Improve the Region's reviews of recipient accounting systems to assure
     that accounting system deficiencies are detected and corrected.

     Region's Response:

     The auditor believes that the Region's accounting system review
procedures need to be strengthened to assure that all accounting deficiencies
are detected and corrected.  The Region and the Agency as a whole agree with
this assessment.  At the Superfund Administrative Management Conference in
Seattle in July 1987, Headquarters Grants Administration Division indicated
they are in the process of developing model cooperative agreement checklists
and training of regional staff on oversight review protocals.

     The Region's review procedures consist primarily of survey and oversight
of the recipient's accounting system relative to the EPA awarded assistance
agreements.  The reviews are not a substitute for audits.  The region is not
authorized to conduct audits, and we make it clear to the recipient that our
reviews are to identify problem areas to management so that potential problems
can be averted early in the process.  The Regional  reviews generally follow
the "Survey of Grantee's Management Systems" program contained in the
Assistance Administration Manual, Appendix 19-3.  The review performed
consists of a limited judgmental sample selection of the grant expenditure
documents, together with interviews of the responsible recipient accountant.
A general verbal walk-through of the accounting practices and maintenance of
records is described.  Subsequent verifications are  made of selected revenue
and/or expenditure documents.

     In regard to the Utah Department of Health, Administrative Services
Bureau of Finance Section review performed by the Region, the auditor
indicated that the statement concerning the adequacy of the accounting records
procedures and internal control procedures was inaccurate.  We only reviewed
the EPA grant accounting procedures implemented for  use by the Finance
Section.  We did discuss in detail with the Financial Manager and staff
accountant the reconciliation of the Finance Section financial data to the
State Financial Information and Resource Management System (FIRMS).  We were
advised that the original FIRMS revenue and expenditure data entries were
rearranged into cost categories for management and reporting purposes by the
Finance Section.  We concluded, based on our limited scope of review (and it
was made perfectly clear both orally and in writing to the state that our
review function should not be construed as an audit) that the recipient's
accounting practices and procedures were adequate.   Since the issue of the
Utah accounting system and how it relates to the State FIRMS system was
                                 61

-------
dropped from the Utah Superfund audit report as a result of the exit
conference with the State and the OIG, we believe strongly that it should be
dropped from this report.  If the 016 could not determine conclusively that it
was not adequate without further study, then the Region should not be
criticized for failure to identify it as a major problem based on a limited
review.

     Acceptability of the Utah Accounting System

     The auditor stated that although the Regional  review indicated that  the
Utah DEH accounting and internal control systems were adequate,  they found
that this was not the case.  The auditors found inadequacies in  the following
areas:

     (i)  Use of unacceptable labor charging and recording practices,  which
     allowed DEH to allocate employer indirect time charges as direct labor,
     and to transfer labor costs to the cooperative agreement from other
     projects without adequate documentation. During prior years the recipient
     and EPA Regional Grants Management staff have  had discussions on the
     labor cost allocation procedures.  It was concluded that the Department
     of Health sufficiently demonstrated that their cost allocation
     methodologies were being consistently recorded and reported.   However,
     the auditor's recommendations regarding the allocation of indirect costs
     and the possible accounting advantages to the  state will  be discussed
     with the recipient for possible inclusion in the indirect cost pool  and
     resolution of the pending audit finding.

     (ii)  The auditor stated that transferred labor costs of the cooperative
     agreement from other projects were made without adequate documentation.
     At the time of our review, we were advised that the majority of these
     transfers of labor costs were required because of the revision of certain
     cost center code numbers.  Selected vouchers were reviewed  at the time
     which appeared to indicate the code numbers were changed.   In future
     reviews, our personnel will perform more indepth reviews to ensure the
     propriety of cost transfers.

     (iii)  The auditor stated that the DEH accounting system lacked
     segregation of allowable and unallowable costs.  At the recent exit
     conference regarding the DEH Superfund audit,  discussions on this audit
     finding were held.   The recipient appeared to  have sufficiently explained
     the Finance Section's method of recording grant allowable costs.  Any
     costs determined not to be grant eligible costs were recorded and paid
     with the funds in the State general fund account.  We will  not make  any
     further comment on this deficiency since Utah's response to the audit
     finding appears to be acceptable to the auditors.
                                 62

-------
                             DISTRIBUTION


                                                     Copies

Office of the Inspector General

Headquarters Office                                    5
  Inspector General (1)
  Deputy Inspector General (1)
  Director, Audit Operations Staff (3)
Chief, Programs Assistance Unit (Hqs)                  1
Divisional Office                                      3
Other DIGA's (1 each)                                  5

Regional Office     •=••

Regional Administrator, Region 8                       2
Director, Waste Management Division                    3
Director, Office of Policy and Management              1
Audit Follow-Up Coordinator                            1

Headquarters Office

Director, Grants Administration Div.
  (Hqs)  (PM-216)                                       1
Director, Office of Emergency and Remedial
  Response (Superfund) (WH-548)                        1
Comptroller (PM-225)                                   1
                                  63

-------