6061
  MUNICIPAL WASTEWATER TREATMENT
      TECHNOLOGY FACT SHEETS

-------
COLLECTION SYSTEMS

-------
SEWERS, SEPTIC TANK EFFLUENT PUMP PRESSURE                                       FACT SHEET
        x"

Description - A septic tank  effluent pump (STEP) pressure sewer has a septic tank and a pump at each service
connection.   The pumps discharge septic tank effluent into a completely pressurized pipe system terminating at a
treatment plant or a gravity sewer.  Because the mains are pressurized, there will be no infiltration into them,  but
Infiltration and inflow into the house sewers and the septic tanks can occur. The volume of the septic tanks is often
1000 gallons but varies widely.  They remove grit, settleable solids, and grease. The pumps typically are 1/3 to 1/2
hp (0.25 to 0.37 kW) and require 110-120 V.  They are designed to pump septic tank effluent; they have larger
clearances than potable water pumps, but will not pump raw sewage solids.  The head and flow rate provided by
the pumps are typically about 50 ft and 15 gpm but vary widely.  The working volume of the pump well is typically
about 40 gallons.  The discharge line from the pump is equipped with at least one check valve and one gate valve.
Electrical service is required at each service connection.  The pipe network can contain closed loops but typically
does not  The sewer profile typically  parallels the ground  surface profile, and the  horizontal alignment can be
curvilinear.  Plastic pipe is typically used; it is  economical in small sizes, and It resists corrosion by the septic
wastewater.   The minimum  diameter is  typically  1 1/4 in  (30 mm) for service connections and the smallest mains.
Cleanouts are used to provide access for flushing. Automatic air release valves are required at or slightly downstream
of summits  in the sewer profile.  Because of  the small diameters, curvilinear horizontal alignment, and profile
paralleling the ground surface, excavation depths and volumes are typically much smaller for a STEP pressure sewer
than for conventional sewers, sometimes  requiring only a chain trencher.


Common Modifications - A service connection at sufficiently high elevation may be served by gravity, omitting the
pump and creating a hybrid STEP/SDES  (small  diameter effluent sewer) system.  The use of a gravity connection
in this situation is advantageous because a pump would be subject to siphoning and air-binding.  Hybrid designs
are common in current practice.   In-line lift  stations can also be used if required by  the terrain or for  cost-
effectiveness.

Pipe networks with closed loops can be used to provide continuing service in case of a main break.

Two-compartment septic tanks may be more efficient at retaining solids, but single-compartment tanks have performed
well.  Septic tanks with  integral  pump vaults are available; they reduce excavation on-lot.

Several dwelling units or other  service locations can be clustered to a single septic tank, which should have an
increased volume depending on the total population equivalent it serves.  Duplex pump wells may be required on
larger services. Clustered service connections have often led to disputes over billing and responsibility for nuisance
conditions and service calls (Bowne, ad.) .


Technology Status - EPA has reported funding 86 STEP Systems (USEPA, 1988); an unknown number of STEP
Systems have been built without EPA funding.  The technology has been used in the US at least since 1970 (USEPA,
1977).


Applications - STEP systems are most cost-effective where housing density is low, where the terrain has' undulations
with relatively high relief, and where the system outfall must be at a higher elevation than most or all of the service
area  They can also be effective where flat terrain is combined with high ground water or bedrock, making deep cuts
excessively expensive.  They can be cost-effective even in densely populated areas if the terrain is sufficiently difficult
for gravity sewers.

STEP systems do not have the  large excess capacity typical of conventional  gravity sewers.  Therefore they must
be designed with an adequate allowance  for future growth if that is desired.

Where pressure sewers  are indicated, the choice between STEP  and GP (grinder pump) systems depends on two
main factors.  First, the costs of on-lot facilities will  typically be over 75%  - perhaps well over 90% • of the total
system cost.  Therefore, the system with the lower average on-lot cost will ordinarily have the lower total cost. STEP
systems have the advantage of  allowing some service connections to be gravity connections in some cases, thus
lowering on-lot costs.  GP systems must have the pumps (and  grinders) at all service connections. The second
factor is the relevance of design velocities.  GP systems require a higher velocity because they carry the sewage

-------
solids and grease.  STEP systems will better tolerate the low flow conditions that occur In locations with a highly
fluctuating  seasonal occupancy and in locations with slow buildout  from a relatively small initial population to the
ultimate design population.


Limitations - STEP  sewers are usually not as cost-effective as SDES systems, conventional gravity sewers, or flat
grade sewers where the treatment location is at a tower elevation than the service area, and the undulations are of
low relief.

STEP lines may follow rear property lines when constructed in older neighborhoods, because the house plumbing
exits  the rear of the house. General purpose easements are required.

Septic tanks must be well constructed.  They may collapse if poorly designed or manufactured. Septic tanks should
be watertight.  Typically a large majority of existing septic tanks must be replaced in all but the most recent housing
tracts. Excessive infiltration, amounting to as much as ten times dry weather flow or more, may occur through leaking
house sewers, leaking septic tanks, or disused leaching fields connected to the septic tanks.  These problems can
be avoided with proper design and maintenance. Inflow from basement drains, house footing drains, or roof drains
can also greatly exceed sewage flow and should not be allowed.

Septic tanks must  be pumped at regular intervals, typically (and conservatively) once every three to five years.
General purpose easements are needed for access to  the septic tanks.  Septage handling and treatment must be
provided.

Because the wastewater is septic, it is essential to control odor and corrosion. Without controls, odors  are typically
noticeable at lift stations and automatic air  release valve locations.  Odors can be absorbed efficiently and
cost-effectively in soil absorption beds (Bowker et al., 1985). Odors can also be controlled by injecting air or oxygen
into the system; by chemically oxidizing the septic  tank effluent  with chlorine, hydrogen  peroxide, or potassium
permanganate; by  adding metal salts to precipitate sulfides; by adding  nitrate to decrease microbial reduction of
sutfate to sulfide; or by adding an alkali to raise the pH and decrease the emission of hydrogen sulfide (Bowker et
al., 1985).
                       ,  ,                          .                           ,
Corrosion  can be  controlled by using corrosion-resistant materials such as plastic pipe  throughout  the system.
Concrete  septic tanks should  have  a corrosion-resistant coating.   Corrosion can be particularly  severe in
non-corrosion-resistant  conventional sewers to which the STEP system Is connected. This  can be controlled by
limiting the ratio of effluent to raw wastewater or by aerating the effluent at the point of entry into the conventional
system.  The techniques of odor control  listed above, other than soil absorption,  also control corrosion (Bowker et
al., 1985).

Solids and grease typically do not accumulate in a STEP system because they  are largely removed in  the septic
tanks.  Biological slimes grow on the inside of the pipe, and can become significant if the velocity is consistently
below 1 fps (0.3 m/s).  These slimes can be sloughed off by flushing at a velocity greater than 1 fps (0.3 m/s) (Otis,
1985).


Typical  Equipment/No, of Mfrs. (Thomas  Register, 1988) - septic tanks (275), septic tanks with integral pump vaults,
pump wells, pumps, float controls, electrical boxes, plastic pipe (332), plastic sewer pipe (21).


Performance - The  septic tanks typically remove about  50% of BOD, 75% of suspended solids, virtually all grit, and
about 90% of grease.  Therefore, clogging is not a problem. Also, the wastewater reaching the treatment plant will
typically  be weaker than raw sewage.  Typical average values of BOO and  TSS are  110  mg/I and 50 mg/l,
respectively-  On the  other hand, septic tank effluent has virtually zero dissolved oxygen.

Primary sedimentation Is not required In treating septic  tank effluent.  Sand filters  are effective secondary treatment.
Activated sludge processes are also effective. Effluent responds  well to aerobic treatment, but odor control at the
headworks of the treatment plant should receive extra attention.

-------
Design Criteria - A wide variety of design flows has been used. A typical design flow formula is Q » 15 + 0.5D,
where Q is the design flow In gpm and D is the number of dwelling units served. The 15 gpm is the minimum flow
expected from one pump, and the 0.5 gpm per dwelling unit may  be obtained by assuming an average per capita
flow of 50 gpd, 3.5 persons per dwelling unit, and a peaking factor of 4.  The operation of the system under various
assumed conditions should be simulated by computer as a check on the adequacy of the design.   No standard
allowances for infiltration and inflow have been established; the designer must estimate these flows based on local
conditions.  A  minimum velocity of  1 fps Is typically imposed (WPCF,  1986).  Flows  and velocities  in hybrid
SDES/STEP systems call for careful designer judgment.

Septic tanks must be  watertight and able to withstand pressures caused by high ground water and/or overburden
without collapse. Septic tanks may also need to be anchored to prevent flotation by high ground water.  The volume
of the tank should be  at least 1000 gallons for a single-family dwelling, and larger for commercial establishments or
clustered service connections.                      ,


Reliability - STEP systems  are highly reliable;  typical mean times between service calls (MTBSC). not  Including
scheduled operations and preventive maintenance, range from about 3.5 to 7.7 years (WPCF, 1986).  These data
include some of the earnest STEP systems constructed jn the US,  Call-out maintenance usually results from some
problem with the pump, float switches, or electrical panel (WPCF, 1986). Maintenance typically must be performed
within 24 hours of the call, since a buffer volume of about 200 gallons is typically available in the septic  tank.

Preventive maintenance includes annual inspection of the on-lot facilities, particularly the pump, float switches, and
electrical panel  The pump wett should be cleaned if necessary, and the accumulation of septage in the septic tank
should be noted.   Normal operation requires  periodic  pumping of septage from  each  tank,  typically (and
conservatively) once every three to five years, but once every 10 to 12 years may be adequate (Bowne,  ad.). Sewer
flushing may be required occasionally.

General easements are needed to allow  access to the on-lot facilities for maintenance and septage pumping.


Environmental Impact - Construction impacts are typically lower than with conventional sewers, because excavation
is usually shallow, sometimes requiring only a chain trencher.  On the other hand, a significant amount of construction
Impact is shifted on-lot, because septic tanks must be inspected, repaired, and/or replaced.  When the system begins
operation,  odors may be a problem at  some  points In the system,  but they can be controlled by the methods
described above. The impacts on water quality and residuals disposal can be less than with conventional systems,
because the  required treatment plant can be simpler, and the amount  of residual solids (sludge and septage) Is
smaller.


Energy Consumption - The individual pumps  at the service connections consume  little energy.   For a typical
single-family dwelling, 200 gpd of effluent will be pumped at 10 gpm,  giving a pump operating time of 20 min/day.
A 1/2 hp pump will thus consume about  45 kWhr/yr.  At $0.10/ kWhr,  the annual energy cost of the pump is about
$4.50.                               .       .


Costs - STEP systems can have as  much as 90% or more of their construction costs on-lot.  This  is an added
advantage for new developments with slow buildout, since only a small proportion of the total system cost is tied
up in the initial outlay for the sewer lines.

Construction costs vary widely, depending principally on the topography,  housing density, and subsurface conditions
in the service area  A 1989 telephone survey yielded the following construction costs:  the total construction costs
of 5 systems varied from $5,200 to $36,000 per septic tank (December, 1989 dollars), with an arithmetic average of
$16,000 per tank; the total construction cost of 3 systems varied from $9 to $54 per gpd (December, 1989 dollars),
with an arithmetic average of $32 per gpd. The accuracy of the survey data Is rather low, but It gives a rough
estimate of the  magnitude and variability of costs.

The following unit costs are rough estimates of typical construction costs  (Mahoney, 1989):
Pipe material and Installation cost:

-------
                                 Material and Installation  Costs ($/ft)
Diameter                         PVC            pvc           Polyethylene
 0°)                             SDR 26         SDR 35           SDR 7

  2                              3.45                             2.83
  4                              5.70            Z52
  6                              8.55            8.37
  8                              16.45            4.05
 10                                              6.00
 12                                              7.35
 15                                             11.80

Trench Excavation and Backfill Costs (soil excavation, no dewatering needed):

 40 hp chain trencher, 8 in wide, 4 ft deep                                 $0.60/ft
 backhoe, 3/8 C.Y. bucket, 0 to 1 side slope, 2 ft wide.  4 ft deep            $3.16/ft
 backhoe, 1/2 C.Y. bucket, 0 to 1 side stope. 2 ft wide,  8 ft deep            $5.32/ft
 backhoe, 1/2 C.Y. bucket, 1 to 1 side slope, 2 ft wide,  8 ft deep            $17.20/ft

Septic tank (1000 gal), 50 ft service line, pump well, pump, and controls; installed (White, 1980; adjusted for inflation):
$3,500 per service connection.

These unit cost figures are not complete enough  nor site-specific enough for estimating the costs of a particular
system, but they are intended to highlight the major cost elements of a STEP system and their potential variability.

Reliable data on operation and maintenance costs are difficult to obtain.   Estimates of $110/yr per STEP unit plus
$430/yr per mile of sewer have been used (Gidley and Gray, 1987, adjusted for inflation). The former figure includes
energy, septage removal,  preventive maintenance, service calls, and pump replacement.


References -

1. Bowker, Robert P.G., John M. Smith, and Neil A. Webster, Design Manual: Odor and Corrosion Control in Sanitary
Sewerage Systems and Treatment Plants, EPA/625/1-85/018, October 1985.

2.  Bowne, William, personal communications.

3.  Gidley, J.S., and D.D.  Gray, "A Comparison of Conventional Sewers Using Clay Pipe with Alternative Sewers,'
report to the National Clay Pipe Institute, Lake Geneva,  Wl, May  19, 1987.

4.  Mahoney, William D.,  ed.-in-chief, Means Assemblies Cost Data 1990,  R.S.  Means Co. Kingston, MA 1989.

5.  Thomas Register of American Manufacturers and Thomas Register Catalog File, Thomas Publishing Co.  New
York, 1988.

6.   U.S. EPA,  Alternatives for   Small Wastewater Treatment Systems:   Pressure  Sewers/Vacuum Sewers,
EPA-625/4-77-011, 1977.

7.  U.S. EPA, Municipal Wastewater Conveyance and Treatment: Technological Progress  and Emerging  Issues,
1988, Office of Municipal Pollution Control (WH-595), Municipal Facilities Division,Washington, D.C.. September 1988.

8. Water Pollution Control Federation, 'Alternative  Sewer Systems,1 Manual of Practice FD-12, Alexandria, Virginia,
1986.

9. White, G.B., 'Fundamental Elements and Cost Consideration of Pressure Sewer Systems," M.S.E. Problem  Report,
West Virginia University, Morgarrtown, WV, 1980.

-------
Flow Diagram -
                     On-Site STEP Components: Alternative A
                              Separate Pump Well
                         Septic Tank
             Pump Well
_

4 U j
House
lumbing
-1

Scum
- _

r^
-
Sludge


                                                         Check
                                                          Valve
                                             V
                                                        Effluent
                                         Float Switches    Pump
             Automatic Air
             Release Valve
                    On-Site STEP Components: Alternative B
                             Integrated Pump Well
                       r
                    4"  I  .
Septic Tank
T
                                          Pump Well
                                                  C
                House
              Plumbing
1
Scum
«
i
v
*
* ,
* /
Gate
Valve
£_/
                             /Main

                            .Check
                             Valve

                            Effluent
                             Pump
                                           Float Switches

-------
SEWERS, SMALL DIAMETER EFFLUENT                                                     FACT SHEET

       ^
Description - A small diameter effluent sewer (SDES) collects effluent from septic tanks at each service connection
and transports it by gravity to a treatment plant or a gravity sewer. Synonyms include small diameter gravity sewers,
septic tank effluent drains, and small bore sewers. The volume of the  septic tanks is often 1000 gallons but varies
widely.  They  remove grit, settleable solids, and grease, and they attenuate peak flows significantly.   Both the
horizontal and vertical alignments of the pipes can be curvilinear. The pipe network contains no closed loops. Uphill
sections can be used, provided that there is enough elevation head upstream to maintain flow in the desired direction,
and that there  is no backflow into any service connection. Minimum diameters  can be 2 in (50 mm) or less. Plastic
pipe is typically used; it is economical in small sizes, and it resists corrosion by the septic wastewater.  Cleanouts
are used to provide access for flushing.  Manholes are used infrequently, usually at major junctions of main lines.
Air release risers  are required at or slightly downstream of summits  in the sewer profile.  Because of the  small
diameters and flexible slope and  alignment of the SDES, excavation depths and volumes are typically much smaller
than with  conventional sewers, sometimes requiring only a  chain trencher.


Common Modifications - Two varieties of SDES systems have been used: the variable grade effluent sewer (VGES)
and  the minimum grade effluent  sewer (MGES).  The VGES allows flexibility of horizontal and vertical alignment,
provided that there is enough elevation head to maintain flow in the desired direction, and that there is no backflow
into any service connection at design flow.  In the MGES, minimum downward slopes are Imposed. In some cases,
horizontal alignments have been required to be straight, and larger minimum diameter constraints have been imposed.
Therefore the  MGES is more conservative and more costly than the VGES.

In both the MGES and the VGES, individual service connections can be equipped with a septic tank effluent pump
unit, creating a hybrid with the septic tank  effluent pump (STEP) pressure sewer. The use of STEP connections is
advantageous when excavation costs can be reduced enough to offset pumping costs.  Hybrid designs are common
in current practice. In-line lift stations can also be used if required by the terrain or for cost-effectiveness.

Two-compartment septic tanks may be more efficient at retaining solids, but single-compartment tanks have performed
well.

Several dwelling  units or other service locations  can be clustered to  a single septic  tank, which should have an
increased volume depending on the total population equivalent It serves.


Technology Status - The  EPA has reported funding 151 SDES systems (USEPA,  1988);  an unknown number  of
systems have been built without EPA funding.  The earliest SDES System reported in the US was built in 1975 (Otis,
1985).


Applications - SDES  systems are likely to  be most cost-effective where the housing density is low, the terrain has
undulations of low relief, and the  elevation  of the system terminus is lower than all,  or nearly all, of the service area
They can also be effective where the terrain is too flat for conventional gravity sewers without  deep excavation.

SDES systems do not have the large excess capacity typical of conventional  gravity sewers. Therefore they must
be designed with an adequate allowance for future growth  if that is desired.


Limitations • SDES systems are usually not as cost-effective as pressure sewers if the treatment location is at a higher
elevation than the service  area, or undulations are of high relief. In either case, lift stations are  needed.  In general,
SDES systems are not  cost-effective unless the topography is such  that the  sewer  profile can stay  close to the
ground surface without using a large number of lift stations.

SDES lines often  follow rear property  lines  if constructed in  older neighborhoods, because house plumbing exits to
the rear. Topography often requires the crossing of private property also.  General purpose easements are required.

Septic  tanks must be well constructed and watertight  They may collapse  If poorly designed or manufactured.
Typically a large majority of existing septic tanks  must be replaced in  all but the most recent housing tracts.

-------
Excessive infiltration, amounting to as much as ten times dry weather flow or more, may occur through leaking house
sewers, septic tanks, or disused leaching fields connected to the septic tanks. These problems can be avoided with
proper design and maintenance.  Inflow from basement drains, roof drains, or house footing drains can also greatly
•xceed sewage flow and should not be allowed.

Septic tanks must be  pumped at regular intervals, typically (and conservatively) once  every three to five years.
General purpose easements are needed for access to the septic tanks.  Septage handling and treatment must be
provided.

Because the wastewater is septic, ft is essential to control odor and corrosion.  Without controls, odors are typically
noticeable at lift stations, drop manholes, air release risers, and some service connections (through the septic tank).
Odor generation  can  be reduced by avoiding splashing in manholes.  Odor  can  be absorbed efficiently and
cost-effectively in soil absorption beds (Bowker et al., 1985).  Odors can also be controlled by injecting air or oxygen
Into the system; by chemically oxidizing the septic tank effluent with chlorine,  hydrogen  peroxide, or potassium
permanganate; by adding metal salts to precipitate sulfides; by adding nitrate to decrease microbial reduction of
sulfate to sutfide; or by adding an alkali to raise the pH and decrease the emission of hydrogen sulfide (Bowker et
al., 1985).

Corrosion can be controlled by  using corrosion-resistant materials such as plastic pipe throughout the system.
Concrete septic  tanks should  have a  corrosion-resistant  coating.   Corrosion can be  particularly severe in
non-corrosion-resistant conventional sewers to which the SDES system is connected. This can  be controlled by
limiting the  ratio of effluent to raw wastewater or by aerating the effluent at the point of entry into the conventional
system. The techniques of odor control listed above, other than soil absorption,  also control corrosion  (Bowker et
al., 1985).

Solids and  grease typically do not accumulate in an SDES system because they are largely removed In the  septic
tanks.  Grit  can enter through manholes, and so they should be avoided, or built with closed pipes  passing through.
Biological slimes grow on the inside of the pipe, and can become significant if the velocity is consistently below 1
fps (0.3 m/s). These slimes can be sloughed off by flushing at a velocity greater  than 1 fps  (0.3 m/sec) (Otis,1985).


Typical Equipment/No, of Mfrs. (Thomas Register,  1988) - septic tanks (275), plastic pipe (332), plastic sewer pipe
(21).


Performance - The septic tanks typically remove atooul 50% of BOD, 75% of suspended sottds, virtually all grit, and
about 90%  of grease.  Therefore, clogging is not a probtem.  Also, the wastewafer teaching the treatment plant will
typically be weaker than raw sewage.  Typical  average values of  BOD and  TSS  are 110 mg/I and 50  mg/l,
respectively.  On the other hand, septic tank effluent has virtually zero disserved oxygen.

Primary sedimentation  is not required in treating septic  tank effluent. Sand filters are quite effective in treatment.
Effluent responds well  to aerobic treatment, but odor control at the headworks of the treatment plant should receive
extra attention.


Design Criteria - Design flows of 50 to 80 gpcd (190 to 300 I/cap-day) are typically used for both VGES and MGES
systems,  with peaking factors of 2 to 4 (Otis, 1985). No standard allowances for infiltration and inflow  have  been
established, but conservatively large per capita flows and/or peaking factors  have been used instead.  Alternatively,
the designer  must estimate infiltration  and  inflow based on local conditions.   Flows and  velocities in hybrid
SDES/STEP systems call for careful designer judgement.

MGES design criteria are conservative. Minimum velocities of 1 to 1.5 fps (0.3 to 0.45 m/sec), with the pipe flowing
full or half-full, have been  imposed; the minimum diameter has  typically been  4 in (100 mm) (Otis, 1985).   The
minimum  velocities cannot be maintained in the upper reaches of a system except by the use of unusually steep
slopes. Minimum (downward)  slopes are specified for each diameter based on minimum velocity; the criteria can
lead to steeper slopes  than required in conventional gravity sewers, obviating some of the  potential for cost savings
lead to steeper slopes than required in convernionai gravny sewers, ooviaimg some or tne potential for co

VGES design criteria are less stringent, taking fuller advantage of the benefits of SDES technology.
                                                                                                  Often  no

-------
minimum velocity constraint is imposed, and the minimum diameter is typically 2 In (50 mm) (WPCF, 1986). No slope
requirements are imposed other than to make the design hydraulically feasible.

Septic tanks must be watertight and able to withstand pressures  caused by high ground water and/or overburden
without collapse. Septic tanks may also need to be anchored to prevent flotation by high groundwater.  The volume
of the tank should be at least 1000 gallons for a single-family dwelling, and larger for commercial establishments or
clustered service connections.


Reliability - A pure SDES system (with no STEP units and no lift stations) has no moving parts, and is highly reliable
in operation.  Call-out maintenance  is typically very infrequent;  the only likely cause is a construction accident
breaking a line. Preventive maintenance consists of periodic flushing of low-velocity lines. Normal operation requires
the periodic pumping of septic  tanks, typically (and conservatively) once every three to five years, but once every
10 to 12 years may be adequate (Bowne, ad.). Sewer flushing may be required occasionally.  General easements
are needed to allow access to the on-lot facilities for maintenance and septage pumping.


Environmental Impact  - Construction impacts are typically less  severe than with conventional  sewers, because
excavation is typically shallow, sometimes requiring only a chain trencher.  On the other hand, a significant  amount
of construction impact is shifted on-lot, because septic tanks must be inspected, repaired, and/or replaced. When
the system begins operation, odors may be a problem at some points in the system, but they can be controlled by
the methods described above.  The impacts on water quality and residuals disposal can be less  severe than with
conventional systems, because the required treatment plant can be simpler, and the amount of residual solids (sludge
and septage) is smaller.


Energy Consumption - A pure SDES system (with no STEP units  and no lift stations) requires no energy for normal
operation.


Costs - SDES systems can have as mucft as 90% of their construction costs on-lot.  This is an added advantage
for new developments with siow buildout, since only a small proportion of the total system cost is tied up in the initial
outlay for the sewer lines.

Construction costs vary widely, depending principally on the topography, housing density, and subsurface conditions
in the service area  A 1989 telephone survey yielded the following construction costs:  the total construction costs
of 15 systems varied from $3,500 to $69,000 per septic tank (December 1989  dollars), with an arithmetic average of
$14,000 per tank; the total construction cost of 7 systems varied from $6 to $43 per gpd (December, 1989 dollars),
with an arithmetic average of $22 per gpd. The accuracy of the survey data is rather low, but it gives a rough
estimate of the magnitude and variabilities of costs.The following unit costs are rough estimates of typical construction
costs (Mahoney, 1989)

Concrete septic tank and service  line installed (1000 gal)            $1,200
Fiberglass septic tank  and service line installed (1000 gal)           $1,300-
                               , .,      ,
Pipe material and installation cost:

        Pipe            Material and Installation Costs ($/ft)
      Diameter           PVC            PVC            Polyethylene
        (in)              SDR  26         SDR 35         SDR 7

         2               3.45                            2.83
         4               5.70            2.52
         6               8.55            3.37
         8              16.45           4.05
        10                              6.00
        12                              7.35
        15                              11.80

-------
Trench Excavation and Backfill Costs (Soil excavation, no dewatering needed):

      ' 40 hp chain trencher, 8 in wide, 4 ft deep
        backhoe, 3/8 C.Y. bucket, 0 to 1 side slope,
        2 ft wide, 4 ft deep

        backhoe, 1/2 C.Y. bucket, 0 to 1 side slope,
        2 ft wide, 8 ft deep

        backhoe, 1/2 C.Y. bucket, 1 to 1 side slope,
        2 ft wide, 8 ft, deep
                                                       $0.60/ft


                                                       $3.16/ft


                                                       $ 5.31/ft
                                                       $17.20/ft

STEP unit, pump well, and controls (White,  1980, adjusted for inflation):

        $2,500 per unit

These unit cost figures are not complete enough nor site-specific enough for estimating the costs of a particular
system, but they are intended to highlight the major cost elements of an SDES system and their potential variablity.

Reliable data on operation and maintenance  costs are difficult to obtain.  Planning estimates of $50/yr per septic tank
plus $430/yr per mile of sewer have been used (Gidley and Gray, 1987, adjusted for inflation).  The former figure
includes septage removal, preventive maintenance,  and service calls.
 Flow Diagram -
                                Air
                          Release Valve
                              House
                            Plumbing
                                                Onsite Septic Tank
                                                        Access Port
                                                                                           Main

-------
References -

1.  Bowker, Robert P.O., John M. Smith, and Neil A. Webster, Design Manual: Odor and Corrosion Control In Sanitary
Sewerage Systems and Treatment Plants, EPA/625/1-65/018. October 1985.

2.  Bowne, William, personal communications.

3.  Gidley, S., and D.D. Gray, 'A Comparison of Conventional Sewers Using Clay Pipe with Alternative Sewers,' report
to the National Clay Pipe Institute, Lake Geneva, Wl, May 19, 1987.

4.  Mahoney, William D., ed.-in-chief, Means Assemblies Cost Data 1990, R.S. Means Co., Kingston, MA, 1989.

5.   Otis. R. J., 'Septic Tank Effluent Drainage: An Alternative Wastewater Collection Method*, Proceedings 1985
International Symposium  on Urban  Hydrology, Hydraulic Infrastructures and Water Quality Control, University of
Kentucky, Lexington, Kentucky, July 1985.

6.  Thomas Register of American Manufacturers and Thomas Register Catalog File, Thomas Publishing Co., New
York, 1988.

7. U.S. EPA, "Municipal Wastewater Conveyance and Treatment: Technological Progress and Emerging Issues, 1988,
Office of Municipal Pollution Control (WH-595), Municipal Facilities Division, Washington, D.C., September 1988.

8.  Water Pollution Control  Federation, "Alternative Sewer Systems," Manual of Practice FD-12. Alexandria, Virginia,
1986.

9. White, G.B., "Fundamental Elements and Cost Considerations of Pressure Sewer Systems,' M.S.E. Problem Report,
West Virginia University, Morgantown, 1980.

-------
SEWERS, GRINDER PUMP PRESSURE                                                     FACT SHEET
       s

Description • A grinder pump (GP) pressure sewer has a pump at each service connection.  The pumps are 1 hp
(0.75 kw) or more, typically require 220 V. and are equipped with  a grinding mechanism that macerates the solids.
The  head and flow rate provided by the pumps are typicalry about 50 to 100 ft and 10 to 15 gpm but vary widely.
The  pumps discharge into a completely pressurized pipe system terminating at a treatment plant or a gravity sewer.
Because the mains are pressurized, there will be no infiltration into them, but infiltration and inflow into the house
sewers and the pump wells can occur.  In areas where the GP sewer system has replaced septic tank and leaching
field systems, these may  be retained for emergency overflow, but  they should be separated from the pump well by
a gate valve which  is only opened when emergency overflow is needed. Otherwise, the septic tank and leaching
field can become sources of large volumes of infiltration. The discharge line from the pump is equipped with at least
one check valve  and one gate valve.  Electrical service is required at each service connection.  The pipe network
typically has no closed loops.  The sewer profile typically parallels the ground surface profile. Horizontal alignment
can be curvilinear.   Plastic  pipe is typically used; it  is economical in small sizes, and it resists corrosion.  The
minimum diameter is typically 1  1/4 in (30 mm) for service connections and the smallest mains. Cleanouts are used
to provide access for flushing.  Automatic air release valves are required at or slightly downstream of summits in the
sewer profile.  Because of the small diameters, curvilinear horizontal alignment, and  profile  paralleling  the ground
surface, excavation depths and volumes are typicalry  much smaller for a GP pressure sewer than for conventional
sewers, sometimes requiring only a chain trencher.


Common Modifications -  Centrifugal and positive displacement pumps have been used.  The latter have a discharge
nearly independent of head, somewhat simplifying design and analysis.

In-line lift stations can also be used if required by the terrain  or for cost-effectiveness.

Several dwelling  units or other service locations can be clustered to a single pump well, which should have an
increased working volume depending on the total population equivalent it serves. Clustered service connections have
often led to disputes over billing and responsibility for nuisance conditions and service calls  (Bowne, ad.). Duplex
pump wells are often used on clustered, commercial, institutional, or other larger services.


Technology Status - EPA has reported funding 152 GP systems (USEPA, 1988); an unknown number of GP systems
have been built without EPA funding. The technology has been in use since the late 1960's.  Some pressure sewer
systems using ejectors rather than grinder pumps had been built  a few years earlier  (USEPA, 1977; Clift, 1968).


Applications • GP systems are most cost-effective where housing density is tow, where the terrain has  undulations
with relatively high relief,  and where the system outfall must be at  a higher elevation than most or all of the service
area They can also be effective where flat terrain is combined with high ground water or  bedrock, making deep cuts
excessively  expensive. They can be cost-effective even in densely  populated areas if the  terrain is sufficiently difficult
for gravity sewers.

GP systems do not have the targe excess capacity typical  of conventional gravity sewers. Therefore they must be
designed with an adequate allowance to future growth If that is desired.

Where pressure sewers are indicated, the choice between GP and STEP (septic tank effluent pump) systems depends
on two main factors.  First, the costs of on-lot facilities will be typically over 75% - perhaps  well over 90% - of the
total system  cost. Thus, there will be a strong motive In favor of using the system with the less expensive on-tot
facilities for a particular project  STEP systems may allow some  gravity service connections, thus lowering on-lot
costs.  GP systems must have a pump at each service connection to grind the solids. The second factor is the
relevance of design velocities.  GP systems require a higher velocity  because they  carry the sewage solids and
grease.  STEP systems will better tolerate the low flow conditions that occur in locations with a highly fluctuating
seasonal occupancy and in locations with slow buildout from a relatively small initial population to the ultimate design
population.

GP units can be used at individual homes to discharge into a conventional gravity sewer at a higher elevation.

-------
Limitations - GP sewers are usually  not as cost-effective as SDES (small  diameter  effluent sewer) systems,
conventional gravity sewers, or flat grade sewers where the treatment location Is at a lower elevation than the service
area and the undulations are of low relief.

OP lines may follow rear property lines when constructed in older neighborhoods, because the house plumbing exits
the rear of the house. General purpose easements are required.

Excessive infiltration, amounting to as much as ten times dry weather flow or more, may occur through house sewers.
teaky pump well covers, or disused septic tanks and leaching fields connected to the pump wells. These problems
can be avoided with proper design and maintenance.  Inflow from basement drains, house footing  drains, or roof
drains can also greatly exceed sewage flow and should not be allowed.

Without controls, odors are typically noticeable at lift stations and  automatic air release valve locations.  Odor can
be absorbed efficiently and cost-effectively In soil  absorption beds (Bowker et at.. 1985).  Odors can also be
controlled by injecting air or oxygen into the system; by chemically oxidizing the sewage with chlorine, hydrogen
peroxide,  or potassium permanganate;  by adding metal salts to precipitate sulfides; by adding nitrate to decrease
microbial  reduction of sulfate to  sulfide;  or  by adding an  alkali  to raise the pH  and decrease the emission  of
hydrogen sulfide (Bowker et al., 1985).

Corrosion can be controlled by using corrosion-resistant materials throughout the system, such as plastic pipe. The
techniques of odor control listed above, other than soil absorption, also control corrosion (Bowker et aJ., 1985).


Typical Equipment/No, of Mfrs. (Thomas Register, 1988) - pump wells, grinder pumps, float controls, electrical boxes,
plastic pipe (332), plastic sewer pipe (21).


Performance - The wastewater reaching the treatment plant will  typically be stronger than that found  in conventional
systems because of the lower infiltration. Typical design average concentrations of BOD and TSS are 350 mg/l each
(WPCF. 1986).


Design Criteria  - A wide variety of design flows has been used. When positive displacement pumps are used, the
design flow is obtained by multiplying the pump discharge  by the  maximum number of pumps expected to be on
simultaneously.  When centrifugal pumps are  used, the same formulas as for STEP systems may be used; a typical
one is Q =  15 + 0.5 D, where Q is the flow in gpm, and D is the number of equivalent dwelling units  served (WPCF,
1986). The flow of 0.5 gpm per dwelling unit may be obtained by  assuming an average per capita flow of 50 gpd,
3.5 persons per dwelling unit, and  a peaking factor of 4.  The operation of the system under various assumed
conditions should be simulated  by computer  as a check on the adequacy of the design.   No standard  allowances
for infiltration and inflow have been established; the designer must estimate these flows based on local  conditions.
A minimum velocity of about 2 fps is typically imposed.


Reliability  -  GP systems are highly reliable; typical mean times between service calls (MTBSC), excluding routine
operations and preventive maintenance, are on the order of  5 to 10 years (WPCF, 1986).  These data include  some
of the earliest GP systems constructed in the US. Higher horsepower motors (3-5 hp) may provide greater reliability
for larger service connections. Call-out maintenance usually  results  from some problem with the pump, grinder, float
switches, or electrical panel (WPCF, 1986).  Maintenance typically must be performed within 4-6 hours of the call,
since the buffer volume in the pump well is typically only about  40  gallons. Thus maintenance personnel should be
on call 24 hours per day. An exception may be made if disused septic tanks and/or leaching fields are  retained for
emergency overflow.  However, the septic tank and leaching field must be separated from the pump well by a gate
valve to prevent Infiltration.  The gate valve would have to  be  opened by the homeowner when the overflow was
needed.

Preventive maintenance Includes the annual Inspection of the on-lot facilities, particularly  the pump,  float switches,
and electrical panel, and the cleaning of the pump well.

General easements are needed to allow access to the on-lot facilities for maintenance.

-------
Environmental Impact - Construction impacts are typically lower than with conventional sewers, because excavation
is usually shallow, sometimes requiring only a chain trencher. On the other hand, a significant amount of construction
Impact is shifted on-let  When the system begins operation, odors may be a problem at some points in the system,
but they can be controlled by the methods  described above.   .


Energy Consumption - The individual pumps at the service connections consume  little energy.   For a typical
single-family dwelling, 200 gpd of sewage will be pumped at 10 gpm, giving a pump operating time of 20 min/day.
A  1 hp pump will thus consume about 90 kWhr/yr.  At $0.10/kWhr, the annual energy cost of the  pump is about
$9.00.


Costs - Systems can have as much as 90% or more of their construction costs on-let  This is an added advantage
for new developments with slow buildout, since only a small proportion of the total system cost is tied up in the initial
outlay for the sewer lines.

Construction costs vary widely, depending principally on the topography, housing density, and subsurface conditions
in the service area  A  1989 telephone survey yielded the following construction costs: the total construction costs
of 8 systems varied from $2,000 to $74,000 per  grinder pump (December, 1989 dollars), with an arithmetic average
of $22,000  per pump;  the total construction cost of 7 systems varied from $6 to $41 per gpd (December, 1989
dollars), with an arithmetic average of $22 per gpd.  The accuracy of the survey data is rather low, but it gives a
rough estimate of the magnitude and variability  of costs.

The following unit costs are rough estimates of typical construction costs (Mahoney, 1989 a,b,c,d):

Pipe material and installation cost:

Pipe            Material and Installation Costs ($/ft)
Diameter         PVC            PVC            Polyethylene
(in)             SDR 26         SDR 35          SDR 7

 2               3.45                           2.38
 4               5.70            2.52
 6               8.55            3.70
 8              16.45            4.05
10                               6.00
12                               7.35
15                              11.80
       • •
Trench Excavation  and Backfill Costs  (soil excavation, no dewatering need):

40 hp chain trencher, 8 in wide, 4 ft deep                          $ 0.60/fl
backhoe,  3/8 C.Y. bucket, 0 to 1 side slope, 2 ft wide, 4 ft deep      $ 3.16/ft
backhoe,  1/2 C.Y. bucket, 0 to 1 side slope, 2 ft wide, 8 ft deep      $ 5.32/ft
backhoe,  1/2 C.Y. bucket, 1 to 1 side slope, 2 ft wide, 8 ft deep      $17.20/fl


Simplex ginder pump, pump well, controls, 50 ft house sewer, 50 ft pressure service Rne; installed:  $3.300 per service
connection.

These unit cost figures are not complete enough nor site-specific enough for estimating the costs of a particular
system, but they are intended to highlight the major cost  elements of a GP system and their potential variability.

Reliable data on operation and maintenance costs are difficult to obtain.  Estimates of $170/yr per grinder pump plus
$430/yr per  mile of sewer have been used (Gidley and Gray, 1987, adjusted for Inflation).  The former figure includes
energy, preventive maintenance, service calls, and pump  replacement.

-------
 Flow Diagram
                                    On-Slte Grinder Pump Component

                                            Pump Well
                                      -~r
                                    4"
House Plumbing


Float Switches x
                       Gate
                       Valve
                                               Check \
                                               Valve  \?
                                                                      Main
                                                           , Grinder Pump
                                                                    Main
                                                                   Sewer
                                                 Flow Direction
 References -
 1.  Bowker, Robert P.G., John M. Smith, and Neil A. Webster, Design Manual: Odor and Corrosion Control in Sanitary
 Sewerage Systems and Treatment Plants, EPA/625/1-65/018, October, 1985.

 2.  Bowne, William, personal communication.

 3.  Clift, Mortimer A.,  'Experience with Pressure Sewerage", Journal of Sanitary Engineering Division, ASCE, Vol. 94,
 No. SA5, pp. 849-865, October, 1968.

 4.  Gidley, J.S., and  D.D. Gray, 'A Comparison of Conventional Sewers Using Clay Pipe with Alternative Sewers,'
 report to the National Clay Pipe Institute, Lake Geneva, Wl,  May 19, 1987.

 5.  Manoney, William D., ed.-in-chief, Means Assemblies Cost  Data 1990, R.S. Means Co., Kingston, MA, 1989.

 6. Thomas Register of American Manufacturers and Thomas Register Catalog File, Thomas Publishing Co. New York,
 1988.

7.   U.S.  EPA,  Alternatives for Small  Wastewater  Treatment  Systems:   Pressure Sewers/Vacuum Sewers,
EPA-625/4-77-011, 1977.

8.  U.S. EPA, "Municipal Wastewater Conveyance and Treatment:  Technological Progress and Emerging issues,'
1988, Office of Municipal Pollution control (WH-595), Municipal Facilities Division, Washington, D.C., September, 1988.

9. Water Pollution Control Federation, 'Alternative Sewer Systems," Manual of Practice FD-12. Alexandria, Virginia,
1986.

10.  White, G.B.,  "Fundamental  Elements and Cost Considerations of Pressure Sewer Systems,' M.S.E. Problem
Report, West Virginia University, Morgantown, WV, 1980.

-------
SEWERS, VACUUM                                                                         FACT SHEET

       s
Description -  A vacuum sewer system has three major subsystems: the central collection station, the collection
network, and the on-site facilities.  Vacuum is generated at the central collection station and is transmitted by the
collection  network throughout the area to be served. Sewage from conventional plumbing fixtures flows by gravity
to an on-site holding tank.  When about 10 gallons of sewage has been collected, the vacuum interface valve opens
for a few seconds allowing the sewage and a volume of air to be sucked through the service pipe and into the main
The difference between the atmospheric pressure behind the sewage and the vacuum ahead provides the primary
propulsive force. The fact that both air and sewage flow simultaneously  produces high velocities which prevent
blockages. Following the valve closure, the system returns to equilibrium and the sewage comes to rest at the low
points  of the collection network. After several valve cycles,  the sewage reaches  the central collection tank, which
Is under vacuum.  When the sewage reaches a certain level, a conventional non-clog sewage pump discharges It
through a force  main  to a treatment plant or gravity Interceptor.

The vacuum interface valve is the unique component of a vacuum sewer system. These valves operate automatically
using pneumatic controls.   The on-site facilities do not use any electricity.  The valve is placed in a valve pit which
is buried above the holding tank. Plastic pipe is used throughout a vacuum sewer system.  The gravity flow house
sewer  is usually 4-inch pipe. It contains an external vent to admit air when the valve cycles, thus preventing the house
plumbing traps from being sucked dry. Typical service connections are 3-inch pipe, and mains range from 4 to 10
inches depending  on  the flow and layout. Joints are either  solvent-welded or vacuum-certified rubber ring type.

The profile of the collection network makes  use of the limited ability of vacuum propulsion to flow upward in order
to avoid excessive excavation.  Where the ground slopes in the flow direction more than 0.2 %, the pipe parallels
the  ground.  Otherwise the pipe is laid with a downward slope of about 0.2 % until the depth becomes excessive.
When  this occurs, a lift formed by two 45-degree elbows and a short length of pipe is inserted to gain elevation.
The typical  lift raises  the pipe by 2 feet or less,  but higher lifts have been used.  Division valves are usually placed
at main junctions and at 1500 foot Intervals to facilitate troubleshooting and repairs.  Service lines or tributary mains
always join the continuing main from above through a wye.

Several mains may be served by a single collection station.  Each main is  connected directly to the  collection tank
through a division valve. Air flows from the  collection tank through a  vacuum reserve tank to the vacuum pumps,
which  discharge to the atmosphere. Dual vacuum pumps are provided to improve reliability. Both  liquid ring and
sliding vane pumps have been used. Automatic controls cycle the vacuum pumps alternately to maintain the vacuum
in the desired range, usually 18 to 23 feet of water. A backup diesel-generator set is used to maintain service during
electrical outages.   An airtodialing telephone alarm is provided to summon the operator in case of malfunctions.

                                                  ' • i
Common Modifications - Detailed design recommendations  differ among  manufacturers and engineers.  In some
cases, depressed  lengths of pipe  are  substituted for  holding tanks.  A single interface valve may serve several
houses, a school,  or  a small business area Service lines  may be as small as  2 inches and  mains may be 2.5
inches. A few systems use vacuum toilets, which require about 1 quart per  flush, contain their own interface valves,
and have their own vacuum service lines. Cleanouts may be  provided to improve access to mains.

The vacuum  reserve volume may be provided in the collection tank rather than in a separate vacuum reserve tank.
One manufacturer  offers an ejector type vacuum pump in which sewage from the collection tank is recirculated by
a centrifugal  sewage pump as the  primary fluid  in a multiphase jet pump.  This scheme replaces the conventional
vacuum pump with an ordinary sewage pump and an ejector which has no moving parts. In addition, the structural
load on the collection tank is reduced because it  Is at atmospheric  pressure.  Another manufacturer provides a
factory-assembled, skid-mounted central collection station which can handle design sewage flows of up to 150 gpm.
A building to house this station must be erected locally.

In addition to residential applications, vacuum plumbing Is used in office buildings, hospitals, factories, and marinas.
Vacuum plumbing  is widely used on both naval and passenger ships.

Technology Status - On January 1, 1990, there  were 42 residential vacuum sewer systems operating  in 12 states,
including Alaska and Florida These systems serve more than 50,000 persons using 100 central collection stations,
more than 10,000 vacuum interface valves, and about 160 vacuum toilets.  The first of these systems has operated
since 1970.  All but 3  systems use the same brand of interface valves.

-------
Applications - Vacuum sewers are most  likely to be cost-effective when excavation costs are high, population
densities are  tow to moderate, and the topography is flat to moderately rolling. They are well suited for combined
sewer separation projects in urban areas where the inconvenience of construction must be minimized. Other factors
favoring vacuum sewers are the need for water conservation and the need to minimize the risk of sewage spills.


Limitations - Vacuum systems have the highest energy consumption of all collection technologies, and they require
responsive operation and maintenance programs.  The propulsive force is limited so the total rise in  lifts should not
exceed about 26 feet.


Typical Equipment/No, of Mfrs. (Thomas,  1988; Anonymous. 1989) - Interface valves/3, vacuum toilets/2, vacuum
pumps/26, pipe/37, valve pits/3,  collection tanks/11, electrical controls/35,  sewage  pumps/58, diesel-generator
sets/268, prefabricated central collection stations/1.


Design Criteria - Although there are no universally accepted criteria, the following are widely used.

The maximum capacity of a 2-inch interface valve is 20 gpm.
The maximum capacity of a 3-inch Interface valve is 30 gpm.
The minimum vacuum head needed to operate an interface valve is 5 feet of water.

         pipe size        max flow        max length         minimum slope
         3 inch         30  gpm        300 ft           larger of 0.8*ID or 0.2 %
         4 Inch         38  gpm        2000 ft          larger of 0.8*ID or 0.2 %
         6 inch         105 gpm        no limit         larger of 0.4*ID or 0.2 %
         8 Inch         210 gpm        no limit         larger of 0.4*ID or 0.2 %
         10 inch         375 gpm        no limit         larger of 0.4*ID or 0.2 %

    ID  = internal diameter

The sum of frictional and lift losses should not exceed about 13 feet of water.  FrictionaJ losses  may be estimated
using a modified Hazen-Williams formula  The recommended height of a lift is 1  foot in pipe sizes  up to 4-inches
and 1.5 feet in larger pipes. The loss due  to a lift Is taken as the invert to invert rise less the internal  diameter.  Lifts
should be at least 5 feet apart in service lines and 20 feet  apart in mains.

Use dual vacuum pumps; size each  to handle airflow at design conditions.  Use dual sewage pumps; size each to
handle design flow.  The collection tank volume is at least three times the working volume. Choose the working
volume so a  sewage  pump starts every 15 minutes at design flow.  Use a 400 gallon vacuum reserve tank.  The
vacuum  pump run time should be from 1  to 3 minutes.


Reliability - Reliability has improved greatly  due to changes in hardware and design concepts. Interface valves should
be rebuilt every 10 years; controllers, every 5 years.  Both  jobs are performed in-shop. Central  collection stations
require daily  routine maintenance. Vacuum pumps may need an overhaul every 7.5 years and replacement every
15 years. Sewage pumps may need seal  changes every 4 years and pump replacement every 10 years.  Interface
valves jammed open, or damaged mains  may require immediate attention to restore vacuum.   A 1989 telephone
survey found that 15 systems (4360 valves)  reported mean times between service calls (MTBSC) ranging from 0.2
to 20.5 years  per valve.  When weighted by the number of valves in each system, the overall MTBSC was 6.9 years
per valve.


Environmental Impact - Construction impacts  may be much less  than conventional sewers because of reduced
excavation. Risk of sewage spills is  minimal since pipes are under vacuum.  Aeration of sewage in  mains reduces
odor problems.

-------
Costs • Costs are highly site-specific. These are generalized estimates based on a 1989 telephone survey of 32 out
of 42 U. S. vacuum systems, on bid tabulations, and on information from manufacturers and design engineers. AJI
costs are'December 1989 dollars ( ENR Construction Cost Index = 4679).

Based on data from 17 systems, the total construction cost of a vacuum sewer system may range from $ 7,000 to
$ 18,000 per valve.  Note that  one valve may serve more than one house.

A more detailed estimate can be based on the following typical installed unit costs, but wide variations from these
values are to be expected.

3-inch interface valve, pit, cover	$2,000.00  each
4-inch house vent	60.00  each
4-inch gravity flow house sewer  	5.00  per foot
3-inch vacuum service pipe	7.00  per foot
4-Inch vacuum main	8.00  per foot
6-inch vacuum main	11.00  per foot
8-inch vacuum main  ..	 14.00  per foot
10-inch vacuum main	 19.00  per foot
4-inch division vaVe	350.00  each
6-inch division valve	500.00  each
8-inch division valve	700.00  each
10-inch division valve  	1,000.00  each
4-inch cleanout	150.00  each
6-inch cleanout	180.00  each
150-gpm  prefabricated central  collection
station, including building, excluding land	  116,000.00  each

The cost  of custom built central collection stations for design flows in excess of 150 gpm ranges from $ 1000 to
$3000 per valve,  excluding land.
           Annual Operation and Maintenance:
 activity
 on-siie (per valve):
 check valve timing
 rebuild controller
 overhaul valve
 service calls
 annual total per valve

 mainline:
 operate division valve

 central collection station:
 telephone service
 daily inspection
 change oil
 change filters
 overhaul vacuum pumps
 replace vacuum pumps *
 change sewage pump seals
 replace sewage pumps **
 annual total per station
 frequency

   1/1 year
  1/5 years
 1/10 years
1/6.5 years
   1/1 year
360/1 year
  12/1 year
   1/2 year
1/15 years
1/15 years
2/10 years
1/10 years
   parts
     ($)

   4.40
   0.70

   5.10
 300.00
 100.00
 240.00
 242.00
  28.00
 616.00
 160.00
 744.00
2430.00
  labor
(hours)
    0.5
    0.2
    0.2
    0.3
    1.2
                     0.5
  180.0
   MO
    2.0
    3.0
    2.0
    2.0
    4.0
  205.0
Two 10-horsepower, 174 cfm sliding vane vacuum pumps at
$ 6.650.00 each.  Sinking fund assumes 5 % interest.
•* Two 7.5-horsepower sewage pumps ( 250 gpm at 40 ft head )
at $ 4,675.00 each.  Sinking fund assumes 5 % Interest.

-------
 Power consumption varies with design flow, length of mains, lift, and quality of maintenance.  Based on records
 from 5 systems, annual power consumption ranges from 72 to 600 kWh/valve.  A value of 500 kWh per valve per
 year is'recommended for preliminary estimates.

 These estimates are summarized  by the following formula

  C = 2430*NS + 205*LR*NS + 0.5*LR*NDV + 5.1*NIV + 1.2*LR*NIV
     +  500*NIV*ER
 where:
     C
     NS
     LR
     NDV
     NIV
     ER
=annual operation and maintenance cost in December 1989 dollars.
=number of central collection stations.
=labor rate including fringe benefits and overhead in December 1989$/hour.
=number of division valves.
=number of vacuum Interface valves.
=electric power rate in December 1989$/kWh.
 Flow Diagram -
                                                                                   vacuum
                                                                            Vacuum  p
                                                                            Reserve
                                                                             Tank
                                                                       Division   Sewage £
                                                                        Valve    Pump
 References -

 1.  Airvac.  Airvac Vacuum Sewage[sic] Design Manual. Airvac Division of Burton Mechanical Contractors Inc
 Rochester, Indiana, 1989.

 2. Anonymous, " A Reader's Guide to Products, Services, and Manufacturers.' Public Works, vol. 120, no 5 Aoril
 15, 1989.                                                                                       '  '

 3. Envirovac, Inc., E-vac Vacuum Sewer Systems, Rockford, Illinois, 1985.

4. Thomas Register of American Manufacturers. Thomas Publishing Company, New York, NY,  1988.

5. Water Pollution Control  Federation, 'Alternative Sewer Systems," Manual of  Practice No. FD-12,  Alexandria,
Virginia, 1986.

-------
SEWERS, CONVENTIONAL GRAVITY                                                         FACT SHEET
       x

Description - A conventional gravity sewer carries raw sewage by gravity.  It is designed by traditional, conservative
criteria such as those embodied in Ten State Standards' (GLUMRB. 1978). Manholes are included to allow access
for cleaning.  Normally, the pipes slope constantly downhill, but in adverse topography lift stations and force mains
often must be included in the collection system to avoid excessive excavation or to reach a fixed elevation at the
system outfall.


Common Modifications -  To pass under  an obstruction without resorting to pumping or excessive excavation,
inverted siphons can be  used.  An inverted siphon is a depressed sewer that flows full at low pressure with gravity
as the motive force.

Older cities frequently have combined sewers, in which both sewage and storm water runoff are carried.  In dry
weather, the sewage flows in a small  depression at the invert of the sewer and flows to a treatment plant. During
rain storms or times of rapid snow melt, large amounts of runoff mixes with the sewage in combined sewers and may
pass untreated through  combined sewer overflows directly into a watercourse.  Combined sewer overflows are
designed to divert excessive flows before they reach the treatment plant; an interceptor or storage system may collect
combined sewer overflows for later treatment.

Various pipe materials have been used, including vitrified clay, asbestos cement, reinforced concrete, cast iron, ductile
Iron, polyvinyl chloride (PVC), and acrylonitrife-butadiene-styrene  (ABS).


Technology Status  - Widely used for  many years


Applications -  Conventional gravity sewers are  best suited to densely  populated  service areas with a relatively
constant, gentle slope toward a desirable treatment plant location.
    '•,*-*•**      *"                     " -'-   i
  4   4 ''   .     I  ~ ';    *
Limitations  -  Conventional gravity sewers  can  be  inordinately  expensive where  adverse slopes require  deep
excavation,  many lift stations,  or  where the population density of the service  area is low.


Performance - No treatment occurs in conventional gravity sewers except dilution by infiltration and inflow and a small
amount of aeration.


Design Criteria - A  typical average flow allowance is 0.38 m3/cap-day (100 gal/cap-day), which includes Infiltration
and inflow.  Alternatively, a separate allowance for infiltration and inflow can be estimated.  Sewers are designed to
carry peak flow rates, usually calculated by multiplying the average flow by  a peaking factor; a typical  formula is
QMAX/QAVE = (18+yP)/(4+VP) where P  is the population in thousands (GLUMRB, 1978).  This formula yields peaking
factors ranging from about 4.2 for 8 service population of 100 to 2 for a population of 100,000. The minimum pipe
diameter is typically 200  mm (8 in). This conservative criterion avoids the clogging of the sewer by large objects.

Conventional gravity  sewers  are designed to avoid pressure flow at all times.  They must  also have sufficient
downward slope to  prevent the deposition of solids and grease.  To this end,  they are typically  designed  to provide
a velocity of at least 0.6 m/sec (2 fps) when full.  Manning's formula is typically used to calculate flows, slopes and
velocities.                                         '

-------
                Minimum Slopes for Conventional Gravity Sewers (GLUMRB, 1978)
          Nominal
           Sewer
          Diameter
        (mm)   (in)
        200
        230
        250
        300
        360
        380
        410
 8
 9
10
12
14
15
16
 Minimum
 Slope
(m/100 m)
(ft/100 ft)

   0.40
   0.33
   0.28
   0.22
   0.17
   0.15
   0.14
                                         Nominal
                                         Sewer
                                         Diameter
                                        (mm)  (In)
460
530
610
690
760
910
18
21
24
27
30
36
Minimum
 Slope
(m/100 m)
(ft/100 ft)

  0.12
  0.10
  0.06
  0.067
  0.058
  0.046
 Manholes are typically placed at the ends of Hoes,  at every change of stope, alignment, or diameter, and at least
 every 120 m (400 ft) for sewers up to 380 mm (15 in) in diameter and every 150 m (500 ft) for sewers of 460 to 760
 mm (18 to 30 in) (GLUMRB,  1978).

 Inverted siphons (depressed sewers) are typically designed with at least two barrels, and a minimum diameter of 150
 mm (6 in). The smallest barrel should  be designed to carry the minimum flow, and the inlet works (distribution box)
 should be designed to split higher flows among two or more barrels in such a way as to maintain velocities of at least
 0.92 m/sec (3 fps).


 Design  for Life Safety  - Confined space hazards and explosion hazards from sewer gases must be avoided.  The
 principal point of human entry into conventional gravity sewers is the manhole.  No one should ever enter a manhole
 without a standby person at the surface, who should be in radio contact with rescue personnel trained and equipped
 to perform confined  space rescues. The concentrations of oxygen  and toxic gases should  be  determined by a
 portable gas monitor before entry.  A portable blower and air hose should be used to ventilate the  manhole.  A
 person  entering the manhole should be on a harness attached to a hoist erected above the manhole.  The standby
 person  should be able to hoist the entering person out of the manhole even if the  latter becomes unconscious.


 Reliability - Conventional gravity sewers are ordinarily highly  reliable. They often require periodic flushing or cleaning
 to remove deposits of solids and grease. Unlined concrete or cast iron pipes are subject to corrosion and may
 require  expensive  lining or replacement after a few years of service.  Lift stations, usually associated with gravity
 sewers, require frequent maintenance and cleaning.


 Environmental Impact - The environmental impact of conventional gravity sewers arises from their construction, the
 release  of sewer gases, and the  operation of the lift stations normally associated with them.


 Energy consumption - A pure gravity sewer uses no energy  in operation, but flushing and cleaning consumes some
 energy,  and associated lift stations consume energy in operation and maintenance.
Costs -  Construction costs vary widely, depending on factors such as pipe size, excavation depth, subsurface
conditions, site accessibility, type of materials, and quality of installation.  Operation and maintenance costs also vary
widely and are difficult to estimate because both the O&M and accounting practices of sewer authorities vary.  In
particular, It is not easy to determine what costs are incurred by different parts of the system (i.e., gravity mains, lift
stations, force mains,  etc.).

-------
Flow Diagram -
                                   On Lot Components
                                                                                     Main
                                             "- 6"
                      Main
References •

1. Great Lakes - Upper Mississippi River Board of State Sanitary Engineers(GLUMRB), Recommended Standards
for Sewage Works, Health Education Services, Albany, NY, 1978.

2.  Metcalf and  Eddy,  Inc. Wastewater Engineering: Collection and Pumping of Wastewater, New York,  NY,
McGraw-Hill, 1981.

3. Pettit, T., and H.  Unn, 'A Guide to Safety in Confined Spaces,' National Institute for  Occupational Safety  and
Health, Publication No. 87-113. Cincinnati, Ohio, July 1987.

4. U.S. EPA, "Construction Costs for Municipal Wastewater Conveyance Systems: 1973-1979," EPA/430/9-31-003,
January 1981.

5. U.S. EPA, "Operation and Maintenance Costs for Municipal Wastewater Facilities," EPA/430/9-81-004, September
1981.

-------
UFT STATIONS                                                                            FACT SHEET


Description - A sewage pumping station (lift station) is a structure housing pumps that propel sewage to a higher
elevation.  Its primary components are inlet works; a wet well, In which incoming sewage is briefly stored;  pumps;
controls that turn the pumps on and off when the sewage in the wet well reaches specified elevations; and valves
necessary to shut down the station for maintenance or repair. The pumps discharge into a force main, (pressurized
sewer).
                *
Lift stations have been classified by capacity as follows (WPCF, 1981):

                                                                Capacity
                Class                           fl/s)                                    (gprrrt
                Very small                      <6                                     <100
                Small                           6-20                                   100-300
                Medium                         20-200                                 300-3000
                Large                           >200                                   >3000


They become increasingly complex as their capacity increases.  Prefabricated stations are available up to about 400
l/s (6000 gpm), but lift stations can be custom-designed and built  in place at any size.


Common Modifications - Lift stations can be designed with either conventional or submersible pumps. Conventional
pumps require a dry well; only the pumps' suction piping enters the wet well.  Submersible pumps are designed to
work submerged in liquid; therefore they  are  placed in the wet well,  and the lift  station requires no dry well.
Submersible pumps are coupled to piping by quick-disconnect fittings, are mounted on guide rails, and are connected
to a lifting chain so that they can be removed for service without the entry of maintenance persons into the wet well.

Non-clog pumps capable of passing solid spheres up to 2 1/2 to 3 Inches in diameter are typically used (GLUMRB,
1978). In very small stations, grinder pumps may be used. Submersible pumps are self-priming; some conventional
pumps may require external priming by water or vacuum.  When non-clog pumps are used, trash baskets or bar
screens are used In the inlet works to remove solids too large to pass through the pumps. A wide variety of pumps
has been used, including various types of centrifugal pumps, turbine pumps and Archimedes screw pumps.

Lift stations should contain at least two pumps.  The pumps are actuated by level controls mounted in the wet well.
The most common type of level control is the mercury float switch; others include diaphragms, bubblers, electrodes,
ultrasonic level detectors, and pressure transducers.  In duplex stations, containing exactly two pumps, one is
designated the lead pump and comes on first; the other is designated the lag pump and comes on only if the lead
pump is unable to keep pace with the  inflow of sewage. To equalize wear on the pumps, controls are set to alternate
the lead and lag pumps, either at every pumping cycle or at a set time interval.  In stations containing three or more
pumps, the pumps may be set to come on in sequence. The pump off level is  either the  same for all pumps, or
they are set to  go off in reverse sequence.  Alternatively the third pump may be used as a standby or emergency
pump, while the first two operate as in a duplex station.

Swing disc check valves, ball check valves,  and other types of  check valves  are used to prevent backflow through
the pumps.  Plug valves, ball valves, or gate valves  are typicafy used as  shut-off valves to Isolate a  pump for
maintenance or replacement

Telemetry can  be used to monitor the operation of lift  stations from a remote site.


Technology Status - Widely used for many years


Application - Lift stations are used to pump sewage uphill to avoid excessive excavation.  Extant data suggests that
as more adverse topographies have been sewered, the frequency of lift stations in conventional gravity sewers has
increased  significantly-

-------
Umltatlons - LJtt stations must be located where they will not be subject to flooding or must be protected against It
Very small lift stations can be built In the street right-of-way, but larger stations may require a house lot or larger plot
of land  Lift stations require electrical power, which can be supplied from nearby power lines or from a dedicated
generator. In any case, a standby generator is required for continued operation In case the primary power source
falls.  Surge control Is needed to avoid damage to pumps and piping from hydraulic transients (water hammer).

Potentially lethal  hazards to maintenance workers arise from toxic and explosive gases or oxygen deficiency in
confined spaces. Ventilation is imperative »the wet well is large enough for human entry. Odors emanating from
lift stations must be controlled.  A variety of  odor control techniques is available.  Corrosion of all metal parts  within
a lift station can be severe.

All but the smallest lift stations should be Inspected daily and require frequent preventive maintenance.  Trash baskets
and bar screens must be cleaned, and grease and sediment accumulations must be removed from the wet well
before they foul the pumps and controls.


Performance -  No treatment is achieved except for the removal of  large objects from trash baskets or bar screens
or the grinding of solids in lift  stations using grinder pumps.


Design Criteria - A lift station  should have  more than one pump, and the pumps must  be capable of delivering
 maximum design flow with the  largest pump out of service.  The pumps must be sized for the fun range of flow rates
 and heads expected; each  pump should operate near its best efficiency point.   Therefore, both maximum and
 minimum design flows must be carefully estimated.

 Fluid velocities must be capable of transporting all suspended matter and grease through the pumps and pipes. For
 raw sewage, the minimum velocity is 0.6 m/s (2 fps), but  at least 1.1 m/s  (3.5 fps) is preferred.  In sewer systems
 carrying septic tank effluent, the minimum velocity can be 0.3 m/s (1 fps) or less, because most of the suspended
 matter and grease has been removed in the septic tanks.  Minimum velocity should also be maintained through the
wet well to avoid the deposition of solids there. To prevent scouring of the pumps and pipes by grit in raw sewage
 pumping, and to prevent excessive head losses and surge control difficulties in all applications, the velocities should
 not exceed 2.5 m/s (8 fps).

The pumps must be selected and  located in relation to  the wet well so that the net positive suction head available
 (NPSHA) during the most severe conditions of operation exceeds the net positive suction head required (NPSHR).
This criterion prevents cavttation, the  formation of gas bubbles in the fiufeJ within the pump when the liquid pressure
drops below the vapor pressure of the gas, which decreases efficiency and output and can severely damage the
impeller.

The working volume  (volume between pump on and pump off levels) In the wet well should be large enough to
ensure that no  pump  operates less than five minutes at a  time;  this criterion is desirable to increase  pump lifetime.
The working volume should also be small enough so that the retention time of sewage  in the  wet well does not
exceed 30 minutes; this criterion is desirable to avoid the  development of  septic conditions in the wet well. These
criteria may be impossible to satisfy if the range of flows is large, and the latter one is  moot in a sewer system
carrying septic  tank effluent.

A valve pit allowing the hydraulic feotefion of the entire Kft station should be located outside the wet well so that the
lift station can be shut down in emergencies without entry into the wet well.


Design for Life Safety - At least three types  of potentially lethal hazards in lift stations must be  reckoned with:
confined space hazards, explosion hazards, and electrical hazards.

Forced ventilation must be provided in any lift station  large enough to be entered.  The ventilation can  be continuous
or intermittent; in  addition, the  blowers should be on whenever anyone is  in the station.   Continuous ventilation of
wet wells should provide at least 12 air changes per hour; and intermittent ventilation, at least 30 (GLUMRB, 1978).
Matches should also lock In the open position to prevent  accidental lock-ins.

-------
Maintenance procedures should also be planned for life safely.  No one should ever enter a lift station alone. One
person should always remain outside with radio or telephone contact with rescue personnel.  No one should enter
a lift station without checking the concentration of oxygen and toxic gases within, either with a permanent or portable
gas monitor.  Rescue personnel, and preferably  maintenance personnel, should have self contained breathing
apparatuses (SCBA) for entry into potentially toxic or oxygen-deficient atmospheres.  Persons entering the wet well
should be on tethers attached to hoists so that they can be pulled out without endangering the would-be rescuers'
lives.

To avoid explosions, electrical wiring and circuitry should be designed for Intrinsic safety, that is, no failure should
produce a discharge of enough energy to ignite explosive gases  potentially present in the lift station.  Other spark
sources, such as arc welding, must also be avoided.
                          i               •-.--•               .               •   ,         ,
Electrical panels should  be Installed in accordance with local codes, and all  applicable  provisions of the National
Electric Code (NEC) and the National Electrical Manufacturers Association (NEMA)  standards should be observed.


Reliability - Pumps, controls, and electrical circuits can fail.  Because lift stations are often in remote locations in the
sewer system, they should be equipped with telemetry or an autodialing alarm system or both, so that maintenance
personnel can respond quickly to malfunctions. Metal  parts exposed to the  corrosive atmosphere in a lift  station
should  be corrosion-resistant, or they  may frequently need to be  painted or replaced. Each pump should have a
run-hour meter and  a cycle counter for the scheduling of O&M operations.


Environmental Impact - Lift stations produce waste streams In addition to the sewage which ultimately reaches a
treatment plant or overflow discharge.  These are gases  vented to the atmosphere and cleanings from trash baskets
and bar screens.    Uft stations  use energy, resulting  in an indirect environmental impact,  and their construction
potentially impacts their  immediate  surroundings.


Energy Consumption - Uft stations consume energy in  both pumping and maintenance.


Costs - Costs include site acquisition, construction, operation and maintenance, including energy costs.

The construction cost ts peneraJty related to the flow capacity of the lift station.  At a given capacity, there  is little
correlation between head and cost (Newton and Sanks, 1989).  Figures 1 through  3  present the construction cost
curves  of Newton and  Sanks  (1989) for wet well/dry well,  submersible pump,  and  prefabricated  lift stations,
respectively. Figure 4 shows the envelope of all the curves in Figures 1 to 3.  A significant number of data  points
lie outside the curves shown; the curves  give only a general expectation of costs. The costs shown do not include
engineering, legal services, land, administration, or interest during construction. These  additional costs may as much
as  double the costs shown in the Figures.

Operation  and  maintenance  costs vary considerably, partly because the  policies  of sewer authorities vary
considerably.  For small and very small lift stations, maintenance  costs can be much more significant than energy
costs, largely because of the travel, labor and overhead cost of frequent inspections. For larger stations, the life-
cycle energy cost may be  10-25% of the construction cost, and the maintenance cost perhaps half  again as much.

-------
   CONSTRUCTION COSTS Of LIFT STATIONS
      WETWEll f MY y»EU (N€WTON 1 SANKS. 190)
   to*.
8 io«.
      1C2            103            104            !05
                              FLOW(QPM)
              FIGURE 1. Conaruaun Costs ol Wei Wrt / Dry Wei UK Stations
              (Ntwton and Sanks. 19«3|  COSTS are nD«c.. 1989 Dollars
      CONSTRUCTION COSTS OF LIFT STATIONS
        PREFABRICATED (NEWTON AND SAMS. 1M>)
                            FU/tt (GPM)
               FX3URE 3 Construction Com ol PrttaDreawd UK SUMns
               (Ntwwn and So**. 19«9) COB tin it OK.. 1989 Dollars
CONSTRUCTION COSTS Of LIFT STATIONS
 •UWCRSOU *>*» (NEWTON ANDSAMCS. 1M)
                       FLOW(OPM)
        FIGURE 2  Corwffsxoon Con Of SuGflWlAM Pi^D Uft Staoons
        fflmcn ano Sana, igai Cou 
                                                                                  8
                                                                                      .1.
                                                                                                   UPPEBCOST
              to3            10*             ios
                       FLOWIOPU)
          FIGURE 4  Constnxtiori COC8 ot Utt Stations
          (Nwrton and Sams. UBS', Cots ari «i DK.. 1989 Dollars

-------
 Flow Diagram -
             Wet Well
               Quick-disconnect

Submersible Pump System
                                                              Sump Pump

                                                          Dry Well System
 References -

 1. Bowker. R.P.G., J.M. Smith, and NA Webster, Design Manual: Odor and Corrosion Control in Sanitary Sewerage
 Systems and Treatment Plants, EPA/625/1-85/018, October 1985.

 2. Great Lakes - Upper Mississippi River Board of State Sanitary Engineers (GLUMRB), Recommended Standards
 for Sewage Works, Health Education Services, Albany, NY, 1978.

 3. • Metcalf and Eddy, Inc., Wastewater Engineering:  Collection and Pumping of Wastewater, McGraw-Hill, 1981.

 4.  Newton, D., and R.L Sanks, 'Costs', Chapter 29 in Robert L Sanks, ed.-in-chief, Pumping Station Design,
 Butterworth Publishers, Stoneham,  MA, 1989.

 5. Pettit, T. and H. Linn, A Guide to Safety in Confined Spaces, National Institute for Occupational Safety and Health,
 Publication No. 87-113, Cincinnati,  Ohio, 1987.

 6. Submersible Wastewater Pump Association, Submersible Sewage Pumping Systems Handbook, Lewis Publishers,
 Inc.,  Chelsea, Ml, 1986.

7. U.S. EPA, 'Construction Costs for Municipal Wastewater Conveyance Systems: 1973-1979; EPA/430/9-81-003.
 1981.

8. Water Pollution Control Federation, 'Design of Wastewater and Stormwater Pumping Stations,' Manual of Practice
No. FD-4, Washington. DC, 1981.

-------
FORCE MAINS
                                                                                            FACT SHEET
Description * A force main is a pipe carrying sewage under pressure. This fact sheet will deal exclusively with force
mains that exit  lift stations in predominantly  gravity flow collection  systems.  Such force mains typically have no
service connections entering them.


Technology Status - Widely used for many years


Applications - Force mains are used to transport  sewage uphill to  avoid excessive excavation in a predominantly
gravity flow collection system.  They may be required within the system or at Its terminus to lift sewage to a treatment
plant.


Limitations - Surge control is needed to avoid damage to pumps and  piping from hydraulic transients (water hammer).


Performance -  No treatment is achieved in force mains.


Design Criteria  - Fluid velocities must be capable of carrying all suspended matter and grease through force mains.
For raw sewage, the minimum velocity is 0.6 m/s (2 ft/s), but at least  1.1 m/s (3 ft/s) is preferred.  In systems carrying
septic tank effluent, the minimum velocity can be 0.3 m/s (1 ft/s) or less, because most of the suspended matter and
grease has been removed in the septic tanks.  To prevent scouring  of the  force main by grit in raw sewage, and to
prevent excessive head loss and surge control difficulties in all applications, the velocities should generally not exceed
2.4 m/s (8 ft/s). The Hazen-Williams C factors  used in the design of new systems range from 100 for small, unlined
ductile iron to  150 for larger plastic pipe.


Reliability - Property designed force mains  are highfy  reliable.   Some pipe  materials, however, such as unlined
concrete and cast iron may be severely corroded or eroded after a few years and may need to be lined or replaced.


Environmental  Impact - Force mains have minimal environmental impact,  except during construction or in case of
a line break.


Energy Consumption - The lift stations associated with force mains consume energy in pumping and maintenance.


Flow Diagram -
                             — .	     %draulic Grade Une
                                                     Flow Direction

-------
References -
1.  Great Lakes • Upper Mississippi River Board of State Sanitary Englneers(GLUMRB), Recommended Standards
for Sewage Works, Health Education Services, Albany, NY, 1978.
2.  Sanks, Robert L, ed. In chief, Pumping Station Design, Butterworth Publishers, Stoneham, MA, 1989.

-------
FLAT GRADE SEWERS                                                                      FACT
       X

Description - A flat grade sewer carries raw sewage by gravity, ft is a variant of the conventional gravity sewer and
is designed to criteria less stringent than those embodied In Ten State Standards' (GLUMRB, 1978). In particular,
flatter slopes and smaller pipe diameters are allowed.  Manholes are included to allow access for cleaning.  Normally,
the pipes slope constantly downhill, but in adverse topography lift stations and force mains must be included in the
collection system to avoid excessive excavation or to reach a fixed elevation at the system outfall.


Common Modifications - To pass under an obstruction without resorting to pumping or excessive excavation, inverted
siphons can be used.  An inverted siphon is a depressed sewer that flows full at low pressure with gravity as the
motive force.

Various pipe materials can be used, including vitrified clay, asbestos cement, reinforced concrete, cast iron,  ductile
iron,  polyvinyl chloride (PVC), and acrylonitrile-butadiene-styrene (ABS).

Technology Status - Flat grade sewers have been widely used in Nebraska for many years and occasionally used
in other states.  For example, the city of Phoenix, Arizona has adopted reduced slope criteria for gravity sewers
Demonstration projects  in Las Vegas, Nevada and Lacey, Washington have used 6-in lateral sewers.


Applications - Flat grade sewers are best suited to densely populated service areas with a relatively constant, gentle
slope toward  a desirable treatment plant  location.  Because  of relaxed  design criteria compared to conventional
gravity sewers, flat grade sewers can also be cost-effective in many locations with lower population density and flatter
or adverse topography.  Specifically, where the ground surface slope is less than 0.4%, the typical 200-mm (8-in)
conventional gravity sewer pipe will require deep  excavation and lift stations, and a flat grade sewer may not.


Limitations - Flat grade  sewers can be inordinately expensive  when adverse slopes require deep excavation, many
lift stations, or both, or  when the population density  of the  service area is very low.  In no  case will they be more
expensive than conventional gravity sewers.


Performance • No treatment occurs in flat grade sewers except dilution by infiltration and inflow and a small amount
of aeration.


Design Criteria - A typical average flow allowance is 0.38 rtf/cap-day (100 gal/cap-day), which includes infiltration and
inflow. Alternatively, a separate allowance for infiltration and inflow can be estimated (Metcalf and Eddy, 1981). Flat
grade sewers  are designed to carry peak flow rates, usually  calculated by multiplying the average flow by a peaking
factor; a typical formula is QMAX/OAVE = (18+yf)/(4+yp).  where  P is the population in thousands.  This formula yields
peaking factors ranging from about 4.2 for a service population of 100 to 2 for a population of 100,000.

The minimum pipe diameter is typically 150 mm (6 In),  although pipes as smail as the house sewers, typically 100
mm (4 In),  could be used.   In sewers not flowing near capacity, the smaller diameters have a higher velocity than
the conventional 200-mm (8-in) sewer.

Flat grade sewers are designed to avoid pressure flow at all times. They should also have sufficient downward slope
to prevent the deposition of solids and grease, but they are  not so stringently designed with respect to this criterion
as conventional gravity  sewers.  Full pipe velocities as small  as 0.27 m/sec (0.9 fps)  have  been used.

Manholes are  typically placed at the ends of fines, at every change of slope, alignment, or diameter, and  at least
every 120 m (400 ft) for sewers up to 380 mm (15 in) in diameter and every 150 m (500 ft) for sewers of 460 to 760
mm (18 to  30 in).  Manhole criteria are the same as  for conventional gravity sewers.

-------
 Design for Life Safety - Confined space hazards and explosion hazards from sewer gases must be avoided. The
 principal point of human entry Into flat grade sewers is the manhole. No one should ever enter a manhole without
 a standby person at the surface, who  should be In radio contact with rescue personnel trained and  equipped to
 perform confined space rescues. The concentrations of oxygen and toxic gases should be determined by a portable
 gas monitor before entry.  A portable  blower and air hose should be used to ventilate the manhole.  A person
 •ntering the manhole should  be on a harness attached to a hoist erected above the manhole. The standby person
 should be able to hoist the entering person out of the manhole even If the latter becomes unconscious.


 Reliability - Flat grade sewers are ordinarily highly reliable.  They may require periodic flushing or cleaning to remove
 deposits of solids and  grease.  In theory, flat grade sewers should require more maintenance than conventional
 gravity sewers because of their flatter  slopes and smaller diameters.  Long experience in  small communities In
 Nebraska, however, indicates that maintenance  requirements are similar to those of conventional gravity sewers.

 Velocity criteria are usually applied to full pipe flow, but the amount of deposition of solids and grease  depends on
 the velocity in the partially full pipe during operation.  The flat grade sewer is effective partly because the actual
 velocities for partially fun pipes are greater in the smaller  100-mm  (4-in) and 150-mm (6-in) pipes than in the 200-
 mm (8-in) pipes typically required  In  conventional gravity  sewers.

 Unlined concrete or cast iron pipes may require expensive lining or replacement after a few years of service.  Lift
 stations, usually associated with gravity sewers, require frequent maintenance and cleaning.


 Environmental Impact - The environmental  impact of flat grade sewers arises from their construction, the release of
 sewer gases, and the operation of the  lift stations normally associated with them.


 Energy Consumption - A pure gravity sewer uses no energy in operation, but flushing and cleaning consumes some
 energy, and associated lift stations consume energy in operation and maintenance.


 Cost -  Construction costs  vary  widely, depending on factors such as pipe size, excavation  depth, subsurface
 conditions, site accessibility, typo of materials, and quality of installation.  Operation and maintenance costs also vary
 widely  and are difficult to estimate because both the O&M and accounting practices of sewer authorities vary.  In
 particular,  H is not easy to determine  what costs are incurred by different parts of the system (i.e., gravity mains, lift
 stations, force mains, etc.).


 References -

 1.   Dewberry &  Davis, 'Innovative  Site  Utility Installations; H-5558,  US Department  of  Housing  and Urban
 Development, August 1983.

 2   Gidley,  J.S.,  'Case Study  No. 11:  Ericson, Nebraska: Flat Grade Sewers.' EPA  National Small  Flows
 Clearinghouse, West Virginia  University, Morgantown, WV, September 1987.

 3.  Great Lakes - Upper Mississippi River Board of State Sanitary Engineers(GLUMR8), Recommended Standards
 for Sewage Works, Health Education Services, Albany, NY, 19?a

 4. Metcalf and Eddy, Inc., Wastewater Engineering: Collection and Pumping of Wastewater, McGraw-Hill. New York,
 NY,  1981.

 5. NAHB  National Research Center, 'Challenge and Response -Volume I: Affordable Residential Land Development:
A guide for Local Government and Developers,' US Department of Housing and Urban Development, July 1987.

6. Pettit. T., and H. Unn, A Guide to Safety In Confined Spaces, National Institute for Occupational Safety and Health,
Publication No. 87-113, Cincinnati,  Ohio, July 1987.

-------
7.  U.S. EPA, 'Construction Costs for Municipal Wastewater Conveyance Systems: 1973-1979,' EPA/430/9-81-003,
January 1981.

8.  U.S. EPA, 'Operation and Maintenance Costs for Municipal Wastewater Facilities,' EPA/430/9-81-004, September
1981.

-------
DISINFECTION

-------
CHLORINAT1ON (DISINFECTION)                                                             FACT SHEET


Description - Chlorine continues to be the most widely used chemical for the disinfection of wastewater In the U.S.
The major advantages of chlorine over alternative disinfectants are Its cost-effectiveness, Its reliability, and Its efficacy
against a host of pathogenic organisms.  When chlorine (Cy is dissolved in water, a mixture of nypochlorous (HOCI)
and hydrochloric (HCI) acids is formed. Chlorine exists predominantly as HOCI below pH 7.6 and as OCr above pH
7.6. HOCI and/or OCr is defined as free available chlorine, with the hypochlorous acid being the primary disinfectant

Chloramines (NH2CI, NHCIj, and NHCy are formed when chlorine reacts with ammonia-nitrogen present in secondary
effluent.  At pH 7 to 8 and chlorineiammonia-nitrogen mass ratios of 5:1  or less, monochloramine is formed; at a
tower pH, dichloramine is formed. Studies have indicated that monochloramine may be a more efficient and reliable
disinfectant than, free chlorine since the more reactive free chlorine residual is dissipated in organic reactions and is
not available for disinfection.       •             ......

Chlorine is typically supplied as liquified gas in cylinders.  Chlorinators apply gaseous chlorine to a feed stream which
is then injected into a mixing zone in the chlorine contact  chambers.  Initial mixing  and effective contact times are
essential for good process performance.  Generally. 15  to 30 minute contact periods are required at peak flow.


Common Modifications - The two chemicals used for chlorination are chlorine gas and hypochlorite salts.  Calcium
hypochlorite (Ca(OCI)j,) is in granular form,  while sodium hypochlorite (NaOCI) is handled in liquid form.  Sodium
hypochlorite is generally preferred over the calcium hypochlorite because of low maintenance and safety.  It is,
however, more costly and requires greater storage area.  In remote areas and at smaller plants (up to 0.1 mgd),
granular hypochlorites are sometimes chosen.  Lithium hypochlorite (LJOCI) may be preferred in this case  because
of the scaling problems associated with Ca(OCI)2. Advantages of hypochlorinalion over chlorination Include increased
safety in transporting, storing, and handling of chemicals; however, chemical costs are generally much higher. Where
reduction or elimination of chlorine discharge  is necessary, dechlorination (most often with sulfur dioxide) may be
utilized.


Technology Status - Chlorination is applicable to all size plants, the process control is wen developed, the relative
complexity of the technology is considered simple to moderate, and O&M sensitivity is minimal.   It remains the
dominant disinfection process for both water and wastewater. Pressure to strictly control the level  of residual chlorine
in wastewater discharges has resulted in refinements for better control sysiems and contactor design.  Dechlorination
is used at a growing number of plants to counter the negative effects of chlorine residuals in receiving waters.


Limitations - The effectiveness of chlorination is pH and temperature dependent   Chlorine win react with certain
chemicals in the wastewater, leaving only the residual  for disinfection.  Wastewater components contributing to
chlorine demand include:  reduced iron and sulfur compounds, ammonia nitrogen, organic nitrogen, tannins, uric and
numic acid, cyanides, phenols, and unsaturated organics.  Cysts of Endamoeba histolytica and Giardia lamblia,
Mycobacterium  tuberculosis, some viruses, and eggs of parasitic worms show resistance to chlorine.  Consistent
disinfection In nitrified effluents containing organic nitrogen may pose problems, even when a measured free chlorine
residual  is present

Chlorine is toxic to aquatic  estuarine. and marine organisms. An additional hazard te the carcinogenic potential of
chtoro-organic compounds.  Chlorine gas is  potentially toxic  when inhaled, and chlorine transport poses a risk.
Special handling is required and emergency response plans are required under right-to-know regulations for on-site
storage of gaseous chlorine.  Chlorine gas  and the hypochlorites are also highly corrosive.


Applications - The major application for chlorine in wastewater treatment is disinfection of pathogens and prevention
of waterbome disease- however, chlorine is also used  In wastewater treatment for: control of  odors, algae, flies,
sludge bulking, and foaming;  prevention of septiclty and filter  ponding; improving grease and scum removal; and
destruction of cyanides and phenols.

-------
 Typical Equipment/No, of Mfrs. - chlorinators/24; chlorine analyzers/34; feeders/34; leak detectors/23; mixers/79; pH
 controllers/51; scales/39.
      s

 Performance - Chlorination Is an effective disinfectant and can consistently meet bacterial limits generally Imposed
 by discharge permits.  Efficiency Is directly  related to the level of treatment, and is dependent upon good mixing in
 a highly turbulent regime, followed by good plug flow In the contact chamber.  Chlorine doses will vary, depending
 on upstream treatment levels, chlorine demand, and disinfection requirements.  Typical doses range between 5 and
 15 mg/L  Failure to provide  adequate treatment prior to disinfection will  Increase chlorine  requirements and/or
 decrease bacteria removal efficiency.


 Design Criteria - Chlorination systems encompass delivery, mixing, residual analysis, dose control, and contactor
 basin. The choice between gaseous chlorine and hypochlorite is governed by economic considerations together with
 safety and handling hazards of gaseous chlorine.   Despite higher unit costs, it may be advantageous to use a
 hypochlorite (calcium, sodium, lithium) to minimize the risks of transporting liquid chlorine through urban areas.

 Mechanical mixers or diffusers are used to Introduce chlorine  or hypochlorite Into the wastewater.  Mixing should
 occur In the most turbulent zone  (velocity  2 to 3 ft/sec) of the effluent entrance to the contact chamber and be
 completed in less than 3 seconds.  A common method of control is a feed back compound control loop using
 chlorine residual and flow as Input. Most smaller plants control dose normally on the basis of either chlorine residual
 or flow.

 A chlorine contacting device is typically a serpentine  chamber. It Is important that short circuiting be minimized, plug
 flow conditions be closely approached, comers be rounded to minimize dead flow areas, and the velocity of the
 contacting stream be sufficiently high  (0.1 to 0.2 fps) to prevent solids deposition.  The length to width ratio should
 be greater than 50 (preferably 70}  and the  height to width  ratio of the wetted section should be less than 1.  If the
 effluent is transported for a long distance for discharge the effluent or outfall line may be suitable for chlorine contact.

 Disinfection is dependent on contact time and chlorine dose. Values may range from a 30 minute contact time and
 a chlorine dose of 3 to 6 mg/L to  meet a fecal coliform  requirement of 200 MPN/100 ml_ to a dose of 15 mg/L or
 more and contact times  greater than one  hour to  meet a total coliform of 2.2  MPN/100 mL  Several empirical
 equations are used to predict disinfection efficiency.

 Dose levels will be dependent on  the level  of treatment; dosage ranges typically found are:

 Untreated wastewater (pre-Cy                          6-25 mg/L
 Primary clarifier effluent                                5-20 mg/L
 Chemical precipitation effluent                          3-12 mg/L
 Trickling filter plant effluent                             3-15 mg/L
 Activated sludge plant effluent                          2-9  mg/L
 Activated sludge/multimedia filtration                    1-6  mg/L


 Reliability - The equipment required is not complex and chlorine is  relatively easy  to  apply  and control during
 wastewater treatment.   Chlorinalion destroys enteric pathogenic organisms; however,  it may not  be  universally
 effective in destroying harmful bacteria, and Its virucidal effectiveness may also  be poor under some circumstances
 (e.g., monochloramine is a very slow-acting  virucide).  The mechanical feed and contact systems are considered very
 reliable.


 Environmental Impact - Chlorine gas concentrations of 15 to 20 ppm for 30 to 60 minutes are dangerous; higher
 concentrations for very  brief  periods can be fatal.  Chlorination can result In the  formation  of carcinogenic
 chloroorganics.

The USEPA has established toxiclty criteria for total residual chlorine  In receiving waters. In freshwaters the acute level
Is 19 mg/L (1-hour average) and the  chronic level is 11 mg/L (4-day average).  The saltwater acute and chronic
criteria are 13 mg/L (1-hour the  average) and 7.5 mg/L (4-day average), respectively.  Due to the toxiclty of chlorine

-------
 residuals at such low concentrations and the high limit of analytical detection (50 to 100 mg/L) chlorine induced
 toxicity in the receiving stream is difficult to control.


 Chemicals Required - Chlorine gas, liquid sodium nypochlortte, or dry calcium or lithium hypochtorite.


- Residuals Generated - The low concentration of residual chlorine remaining after treatment Is acutely toxic to aquatic
 We, and Its elimination may significantly Improve the biological conditions of the receiving waters. It is not currently
 possible to predict the identity of all the chloro-organtes resulting from chlorination. Some chloro-organics are potential
 carcinogens,  mutagens, or toxins; however, effluent levels of chlorinated by-products are below levels known to be
 acutely toxic  to aquatic life.  Most chlorinated organic compounds produced by chlorination are  polar or  of low
 molecular weight and do not bioaccumulate.


 Potential For Improved  Toxics  Management - The primary rationale for wastewater disinfection is to prevent' the
 spread of waterborne diseases and to protect public health.  Chlorination does not offer an opportunity for improved
 toxics management
  Flow Diagram -
                             Chlorine Oas
                                               Chlorinator
                                              Chlorine
        Solution-^.
        Water
Eductor
                           Influent-**-
J 	
1

„



                                                                                                EffkMnt
                                            MxingTank
                                              Contact Tank
 Energy Notes - Energy requirements for chlorination are primarily for heating, lighting, and ventilation. Total annual
 energy requirements for 1,10, and 100 mgd plants are 1£100 kWh/yr/mgd, 1.800 kWh/yr/mgd, and 250 kWh/yr/mgd,
 respectively.  When the rate of chlorine withdrawal exceeds 1000 to 1500 Ib/day, an evaporator Is generally used to
 convert the liquid chlorine to gas.  Energy requirements for the evaporator (excluding mixing) can be estimated from:
 kWh/yr « 11.8 x Ib Clj/day.
 Costs - Estimated capital costs  (1989) for 1,  10, and  100 mgd plants  are $130,000, $600,000 and  $3,000,000
 respectively  0AM costs are estimated to be 2.6.1.4 and 0.8 cents/1,000 gal. respectively at an average dose of
 6 mg/L These Increase to 3.2, £0. and 1.2 cents/1.000 gal at a dose of 10 mg/L

 Chemical costs of chlorine  gas and  hypochlorite vary  considerably depending upon the locality, demand, and
 availability  1989 prices quoted for CI2 were: $0.0425 - $0.06/lb for 90 ton tank cars; $0.10/lb for 55 ton rail cars;
 $0.25 to $0.275/lb for 1 ton cylinders;  and $0.50 to $0.55/lb for 150 Ib cylinders.  Liquid sodium hypochlortte
 percent) prices quoted were $0.50/gal -$1.75/gal.

-------
References -

1.  California Department of Health Services, Wastewater Disinfection for Health Practices. Sanitary  Engineering
Branch, Sacramento, CA., February 1987.

2.  Eastern Research Group, Municipal Wastewater Disinfection Policy Development Document. 4th Draft. Eastern
Research Group, Arlington, MA.. 1989.

3. Trussel, R.R., W.L Fisher, and K.H. Conarroe, 'Operational Experiences of Chlorination/Dechlorination Systems,'
In Alternate Effluent Disinfection Systems - Preconference Workshop Proceedings. Water Pollution Control Federation,
Alexandria, VA., 1986.

4.  U.S. EPA, Design  Manual: Municipal Wastewater Disinfection,  Office of Research  and Development,  Water
Engineering/Research Laboratory, EPA/625/1-86/021, Cincinnati. OH.. 1986.

5. Water Pollution Control Federation, Wastewater Disinfection, Manual of Practice No. FD-10, Alexandria, VA.,  1986.

6.  Water Pollution Control Federation Disinfection Committee, 'Assessing the Need for Wastewater Disinfection,'
Journal Water Pollution Control Federation. Vol. 59. No. 10, 1987.

7.  White, G.C., Handbook of Chlorination, 2nd Ed., Van Nostrand Reinhold Company Inc. New York,  NY., 1986.

-------
DECHLORINAT10N                                                                           FACT


pescriPtlon - The practice of dechlorination has seen dramatic growth in the past decade due to rising concerns over
chlorine toxiclty and  protection of fish and wildlife.  Dechlorination removes all or part of the chlorine residual  and
halogenated organics remaining after chlorination, and reduces or eliminates toxicity harmful to aquatic life In receiving


Treatment with sulfur dioxide (SOg) is the most common method of dechlorination, as described by the following
reactions:
S02 + HOCI +  HaO - SO*"8 + Cf + 3H+ (free chlorine)

S02 + NHaCI + 2HzO - S04* + Cr + 2H+ •»- NH4* (combined chlorine)         :

S02 systems use the same types of equipment as chlorination, and are easily and economically retrofitted to existing
chlorination facilities. The material is supplied In liquefied form in canisters or cylinders. Sodium bisulfite is also used
for dechlorination, primarily with smaller plants where feed rates for SO2 are impractical.


Common Modifications - Several dechlorination agents are available. The  most common agent is SO2 because of
cost and the ability to use existing chlorination equipment without modification. Sulfrte compounds are also used
(sodium sulfite,  sodium bisulfite or sodium metabisulfite), primarily at smaller installations with equivalent SO2 feed
rates less than 100 Ib/day, or at large installations where storage of S02 is  considered hazardous. When dissolved
in water, these salts produce the same active ion (SOa"2). Granular activated carbon (GAG)  has seen  only limited
success due to its inability to  remove organochloramines when organic nitrogen is high,  difficulties in designing
effective carbon beds, and long detention times.

Hydrogen peroxide (HjO^ has also had limited success due to its ineffectiveness in removing chloramines, problems
with side reactions, instability and cost. Aeration and holding lagoons have also been used  ; however, aeration Is
ineffective in removing undissociated HOCI and chloramines. Free chlorine and to a lesser extent, chloramines, can
be destroyed by sunlight; however,  decay  rates are a function of cloud cover and latitude.


Technology Status - The technology of dechlorination. particularly with sulfer dioxide or sutfite, is well established.
In 1987, over 500 wastewater treatment plants practiced dechlorination.  Dechlorination is encouraged and sometimes
required in many states for receiving  waters designated as important for aquatic life. It is used extensively throughout
California and is required  in Maryland (306 out of 335 POTWs dechlorinate) for Class 1, 2, and 4 wastewater plants.
Other states moving to  restrictive  limits  for total residual  chlorine include New Jersey, Pennsylvania, Virginia,
Minnesota and Ohio.  Colorado and Oregon each have one major plant practicing dechlorination.


Applications - Dechlorination is applicable when a chlorine residual is undesirable, typically in cases where discharge
is to sensitive receiving waters.


Umitations - Chtorination/dechlorinalton is "more complex to operate and maintain than just chlorination alone.  Major
difficulties are the  inability to measure residuaf S02 and problems in the continuous  measurement of a zero  or low
chlorine residual.  Many halogenated organics are also rapidly formed upon chlorine addition,  and are unaffected by
application of SO*


Typical EQuipment/No.  of Mfrs.  - Dechlorination equipmerU/3; sulfur dioxide control systems/4;  onslream chlorine
analyzers/30; chlorinators/24.


Performance - Total chlorine residual can be reduced to essentially zero with S02; however, overdosing of  S02 Is
necessary for consistent dechlorination.  If a contact chamber  is used, aftergrowth of microorganisms, Including

-------
conforms, may occur;  however,  the mlcrobial increase shortly after dechtorination may not pose a risk to public
health, and application of the coliform standard  at the chlorine contactor effluent may be permitted.

PeslgrfCrtterla - A major difficulty In dechlorination control is the inability to measure residual SO2 or problems In the
continuous measurement of a zero or low chlorine residual.  As a result, most systems operate with a feed forward
control using flow and the chlorine residual after disinfection.  Feedback control using a chlorine bias is also a
common method. On a mass basis, 0.9  parts S02 or  1.46 parts NasHSOa or 1.34 parts Na^Oj Is required to
remove 1.0 part chlorine residual.  In practice, a higher dose is required to completely dechlorinate.  Excess S02
provides a buffer against rapid changes In demand. The amounts of S02 added typically range from 10 to 50 percent
excess.

The maximum safe rate of S02 gas withdrawal on a continuous basis at 21 °C Is 0.9 kg (2 lb)/hr  for a 68 kg (150
Ib) container, or  11.4 kg (25 lb)/hr for  a  ton container.  For  higher gas withdrawal rates, the  lower half of the
containers or  cylinders may  be immersed in a liquid bath or surrounded with strip heaters (temperatures  not
exceeding 52°C). For liquid withdrawal, the maximum rate of removal is 135 kg (300 lb)/hr. Higher withdrawal rates
are possible with pressurization or by padding with dry air or nitrogen up to 515 kPa (60 psig).  Reaction with chlorine
residual is rapid, and separate contact chambers are normally not used. Contact times are  typically 1 to 5 minutes.
Materials of construction are the same as with chlorination with the exception that line and auxiliary valves must have
316 SS trim instead of monel.


Reliability - No simple analytical method is presently available to determine free SOa. Process operation is therefore
difficult, and S02 overdosing is necessary to assure compliance with residual chlorine standards. The process can
be considered very reliable mechanically, and reliable from a process standpoint.


Environmental Impact - HjSO, and HCI are products of S02 dechlorination in small  amounts but are generally
neutralized in the  wastewater.  Based on laboratory experiments, residuals of sulfite dechlorination are at least three
orders of magnitude less toxic than ozone or chlorine.

No cases of sulfur compounds effecting dissolved oxygen  consumption  or pH change in receiving waters or In
dechlorinated effluents  have been reported. In pilot studies, no significant oxygen depletion occurred  until sulfur
dioxide overdoses exceeded  50 mg/L  ft is not  uncommon, however,  to find plants with post  aeration after
dechlorination to assure that dissolved oxygen requirements are met.


Chemicals Required - Sulfur dioxide is most commonty used, followed by sodium bisulfite, sodium metabisulfite,
and sodium sulfite.
FJow Diagram -
                                                                   SUfonator
          RowM»t»f
                                        Contact Chamber
                 Typical Chlorination Dechlorination System(wlth feed forward dechlorination control)

-------
Potential For Improved Toxics  Management - Bioassay studies have shown that acute toxlclty  of dechlorinated
wastewater Is less than the toxicrty of the  chlorinated wastewater.  While the greater part of toxiclty produced by
             remOV8d ** dechlorinatlon- additional treatment (e.g., activated carbon) may be required to reduce TOX
Energy Notes -  Energy requirements for 1, 10,  and 100 mgd facilities are 10,000, 1,000. and 200 kWh/yr/mgd,
respectively.  Facilities using more than 1,000 Ib SOj/d may use electrically heated evaporators to convert liquid S02
to gas. The energy required for the evaporator, not Including mixing, can be estimated: kWh/yr - 16.8 x Ib SCyday.


Costs - Adjustment  of the 1980 I/A Assessment  Manual  cost estimates  to  1989 (ENR Index = 4,700) yields
construction costs of $39,000, $88,000 and $244,000 for 1,  10 and 100 mgd plants, respectively.  Equivalent annual
O&M costs ere $13,000, $41,000, $207,000, assuming 20 Ib SOa/Mgal.

The total  cost of chlorination is reported  to increase by  approximately  30 to 50 percent  with the addition of
dechlorination. O&M costs for 6 facilities in 1985 were reported to range from $0.08 to $0.28/1,000 gallon.

Chemical  costs  (1989) for S02 were 0.042 to 0.55/lb in 150 Ib cylinders; $0.165 to $0.35/lb in 1 ton cylinders; and
$0.115/lb. in  17 to 20 ton tank cars.  Sodium bisulfite and sodium metabisulfite were quoted at $0.32/lb.  Sodium
sulfite was $2.84/lb.


References -

1.  California Department of Health Services, Wastewater Disinfection for  Health Practices, Sanitary Engineering
Branch. Sacramento, CA., February 1987.

2.  Eastern Research Group,  Municipal Wastewater Disinfection  Policy  Development Document, 4th Draft,  Eastern
Research Group, Arlington, MA., 1989.

3.  Helz, G.R. and L  Kosak-Cnanning, *Dechlorination of Wastewater  and  Cooling Water,' Environmental Science
and Technology, Vol. 18,  No, 2, 1984.

4.  Stefan, H.G.  and T.R. Johnson, •Dechlorination Basin Hydraulics,* Project Report No. 250, St Anthony Falls
Hydraulic Laboratory, University of Minnesota, Minneapolis, Ml.,  1986.

5.  Trussel, R.R., W.L Fisher, and K.H. Conarroe, 'Operational experiences  of chlorination/dechlorination systems,'
In Alternate Effluent Disinfection Systems - Preconference Workshop  Preconference Workshop Proceedings, Water
.Pollution Control Federation.  Alexandria, VA., 1986.

6.  U.S. EPA,  Innovative and Alternative Technology Assessment Manual, EPA/430/9-78-009, Cincinnati. OH.. 1980.

7.  U.S. EPA, Design Manual: Municipal Wastewater Disinfection, U.S.  Environmental Protection Agency. Office of
Research & Development, Water Engineering Research Laboratory. EPA/625/1-86/021. Cincinnati, OH., 1986.

8. Water Pollution Control Federation, Wastewater Disinfection, Manual of Practice No. FD-10. Water Pollution Control
Federation, Alexandria, VA., 1986.

9.  Water Pollution Control Federation Disinfection Committee. 'Assessing  the Need for Wastewater Disinfection;
Journal, Water Pollution Control Federation, Vol.  59. No. 10, 1987.

10. Water  and Engineering Management.  1989  Buyers Guide  and Reference Handbook. Water  Engineering &
Management,  July,  1989.

11. White. G.C..  Handbook of Chlorination.  2nd Ed., Van Nostrand Reinhold Company Inc. New York.  NY.. 1986.

-------
OZONE DISINFECTION (AIR AND OXYGEN)                                                  FACT SHEET
Pescriftion '°*™ (OJ Is one of the most powerful oxidizing agents available and has been used commercially
as a disinfectant for over a century,  h Is a more potent disinfectant  and chemical oxidant than chlorine and will
oxidize i chemically react™ organic and inorganic substances.  Ozone increases dissolved oxygen (especially when
02 to the feed gas), and can reduce BOD, COD, color, and odor in the final effluent. Ozone reacts quickly, requiring
relatrvely tow contact  time.  K will break down to elemental  02 in a short time; as such, on-sHe generation is
necessary.                                                                 •         •        «

03  te produced when  a high voltage alternating current Is  imposed  across  a  discharge  gap containing an
oxygen-bearing gas.   Some O2 molecules split and recombine with other O2 molecules to form 03.  The  electric
discharge is sometimes termed corona or silent arc or brush  discharge,  and is influenced by voltage, frequency,
dielectric material and  thickness, discharge gap, and absolute pressure within the gap. Corona discharge generators
produce 03 concentrations ranging from 0.5 to 4.0 percent by weight When 02 is the feed  gas, most of the O2
passes  through the generator unchanged.  The unused O2 is either reused in the upstream    aeration basin or
recycled through the generator.

Ozone  injection Into  the  wastewater may be accomplished  via  mechanical mixing devices, countercurrent  or
concurrent flow columns, porous  diffusers or jet injectors.


Common Modifications - Major process configurations include air feed,  O2 feed, and O2 recycle systems. O2 recycle
is seldom used.  Air feed is most common in plants where oxygen is not available. O2 feed is used at locations that
have pure oxygen activated sludge  plants; the unused 02 (90 percent)  from the O3 disinfection is used in the
biological treatment process.  O3  generation equipment and power requirements are about 50 percent lower for an
O2  feed system because two to three times as much O3 is produced with high purity Oj at  a given input to the
generator.  The tower cost of producing O3 may be offset,  however, by the  higher cost of obtaining high purity 02
to feed  the generator.  If 02 can be used in the biological system, economics will  generally favor high purity 02 feed
gas.

Low frequency generators produce 1 to 1.5 percent by weight O3 using air  feed, and 2 to 3 percent by weight 03
using O2 feed at the same power requirement  Medium frequency generators produce 2 to 2.5 percent by weight
03  using air feed, and 4 to 6 percent by weight O, using O2 feed at the same power requirement  High frequency
generators produce the same amount of 03 as low frequency generators  but with fewer dialectrics.  Three types of
generators are commercially available: the Otto plate type, the tube type, and the Lowther plate type. The tube type
generator Is the  most  widely used for wastewater disinfection and Is capable of generating O3 from both air and 02,
which is dried and cooled to -60°F.  Operating gas pressure ranges from 3 to 15 psig and peak voltage is -between
15  to 19 kV at 2000 Hz.


Technology Status - As of November 1985, 24 U.S. wastewater  treatment plants disinfected with Oj, with 3 additional
plants under design or construction.  Process control is considered 'developing' as opposed to Veil developed1 for
Ct the technology is considered complex in comparison to C^ and UV.  Ozonation also shows high sensitivity to
O&M as opposed to  minimal for  Cfe, and moderate for UV.


Applications - Ozonation is an alternative to chlorination. The  process does not have a residual and by- products
are considered minimal and far less detrimental than those generated through chlorination. If oxygen activated sludge
is used. O3 is economically attractive, since a source of pure oxygen is already available.


Limitations - Ozonation is energy  and capital intensive, and generally requires a high quality effluent to be effective.
h is not typically considered for application to secondary level effluents.  O, demand is elevated by high organlcs
and nitrites  and achieving bacteriological standards is more difficult with wastewaters containing high suspended
solids.  Wastewaters with very high 0, demands may  not be good candidates for 0, disinfection.

Typical EQuipment/Nlo. of Mfrs. - ozone generators/5; ozonators/6; ozone decomposers/2; system manufacturers/22.

-------
 Performance - Ozone te a more effective bactericide and vlrucide than chlorine. Effectiveness Is directly proportional
 to dosage, exclusive of O3 demand.  At dosages of 2 to 10 mg/L and contact times less than  15 minutes, ozone is
 demonstrated to  affect residual densities consistent with secondary and tertiary requirements, and effective virus
 mactrvation. Primary factors affecting disinfection efficiency are: short-circuiting, mixing, transfer efficiency, and contact
 time.


- Design Criteria - Dosages for disinfection typically range from 5 to 15 mg/L, with 15 to 30 minute contact times.  The
 Oj demand is ultimately dictated by the quality and quantity of wastewater treated, and the design dosage is selected
 to meet the highest 03 demand.

 The most efficient system was reported to be a fine bubble diffuser (2 - 5 mm diameter) in deep basins (16-20 feet
 deep), with plug  flow conditions achieved by staging.  With respect to transfer  efficiency,  it is recommended that
 diffusers be -installed  as deep as practical,  and that minimum design criteria be established at the warmest water
 temperature,' the  lowest pH value, and the lowest anticipated value for O3 demand (i.e., the best water quality
 condition).  A minimum of 3 stages should be provided in the 03 contactors, with each stage isolated to simulate
 plug flow conditions and to  minimize short  circuiting. To achieve 200  FC/100 mL disinfection  levels, the minimum
 contact time should be at least 6 minutes and preferably at least 10 minutes at design peak flow rates.  For more
 stringent standards, the contact time should be lengthened; and pilot studies should be conducted to determine the
 optimum contact times and  dosage requirements.


 Reliability - Mechanically reliable, and highly reliable in inactivating microorganisms.  The most common operational
 problems that have been identified  include undersized  moisture removal  systems,  improperly  designed ozone
 contactors,  inefficient 03 off-gas destruction, 03 leakage from piping, inadequate air drying in air dessicant dryer,
 improper  sealing of  the O3 contact  tanks, and  malfunctioning O3 concentration monitors.   Key O&M design
 considerations for reliable service Include: delivery of clean feed gas at -60°F; maintenance of generator coolant flow;
 operation of generator within design parameters; effective contact of O3 with wastewater; and maintenance of ambient
 O3 below safe limits.


 Environmental Impact - 03 te considered a toxic chemical.  The maximum allowable ambient  O3 concentration for
 an 8 hr working day is 0.0002 mg/L (0.1  ppm by volume), which is significantly less than the O3 concentration in the
 off-gas, normally  1.0 mg/L (500 ppm  by volume).  Methods for treating excess  03 in the off-gas include thermal,
 thermal/catalyst, and catalyst destruction. Although O3 is toxic to aquatic life at  low concentrations, residual O3 Is
 unstable in water, dissipating rapidly due to the low partial pressure above the liquid and the reactive nature of the
 03 with oxidizable materials.

 The reaction of O3  with organic material generally results in the destruction of the original organic molecule and
 formation  of a more  biodegradable product with lower molecular weight.  However, in some cases, particularly
 pesticides, a more toxic intermediary may be formed.   The possibility  that 03 may produce potentially dangerous
 epoxides has been  suggested.


 Chemicals Required - Of 39 plants using O3 for disinfection, 27 use air for feed  gas and 12 use  O2 (all oxygen
 activated sludge plants).


 Residuals  Generated • Residual 03 has been shown to be toxic; however, 03 toxlclty Is no greater than residual
 chlorine and  it decomposes  more rapidly.   At dosages used in  wastewater disinfection, any residual 03 would be
 short-lived.


 Potential For Improved Toxics Management - Ozone will oxidize cyanides, phenol and other dissolved toxic organlcs;
 In combination with activated carbon, ozonation can achieve effective (>95 percent) removal of trihalomethanes.  As
 an alternative to chlorination, It would significantly diminish concerns related to the formation of toxic organics or to
 residual toxicity in the receiving water.

-------
 Flow Diagram -
Air
Treatment
-*-
Ozon*
Q*n*retor
-.*•
Ozone
Contadhg
->•
Ozon*
Destruction
^ V*nt

Oxyg«n F»rf
HahPurtty
Oxygen
+*
Ozon*
Generator
~^-
Ozon*
ContactktQ
-*-
Oxyg»n Ffecycl*
Dew Point
Treatment
i
^
Ozone
Generator
i
-**
Ozon*
Contacting
~+~
Ozon*
Destruction
Oxygen
-^ Activated
Sludg*

Ozon*
Destruction

Qffc. "Oxyoen
^" Activated
— i Sludg*
                                                                                                •Vwit
                                                                                                  •V*nt
                                                                                 •V*nt
                                   R*cycl* Oxygen
                    Diagrams showing feed-gas flow of typical ozone disinfection processes


 Energy Notes - Power requirements for high purity oxygen feed systems are 3 to 4 kWh per Ib O3 per day excluding
 02 power requirement, with an  average  O3 concentration of 2 to 4 percent weight in the  parent gas. Power
 requirements  for atmospheric process air (-60°F dew  point) are 10 to 13 kWh per Ib 03 per day  including air
 preparation with an average O, concentration of 1 to 1.5 percent weight in the parent gas.
 References -

 1.  Ozone Research and Development Corporation, Ozonation Design Manual, Phoenix, KL, 1967.

 2.  Rakness, K.L, Brenner, R.C., Hegg, B.A., and A.G. Hill, 'Practical Design Model for Calculating Bubble Dlffuser
 Contractor Ozone Transfer Efficiency.'  Ozone Science & Engineering, Vol.  10. pp.  173-214. 1988.
    i         ,
 3.   Robson. M.,  Operational  Experiences  of Ozonation  Facilities,  Alternative  Effluent Disinfection Systems
 Preconference Workshop, Water Pollution Control Federation. October 5.  1986.

 4. Water Pollution Control Federation, Wastewater Disinfection, Manual of Practice No. FD-10. Alexandria, VA., 1966.

 5.  Water Pollution Control Federation Disinfection Committee, 'Assessing the Need for Wastewater Disinfection,'
 Journal. Water Pollution Control Federation, Vol. 59. No. 10. 1987.

 6. Water  Pollution Control Federation.  Buyers Guide/1989 Yearbook. Vol. 61 (S). 1989.

7   US  EPA, Design Manual: Municipal Wastewater Disinfection. Office of Research  and  Development, Water
Engineering Research Laboratory, EPA/625/1-66/021. Cincinnati, OH. 1986.

8.  White,  C.G., Handbook of Chlorination. 2nd  Ed., Van Nostrand Reinhold Company, Inc.  New York, NY.. 1986.

-------
ULTRAVIOLET DISINFECTION                                                              FACT SH£ET


           - Lmravioiet light in the far UV range is an effective germicidal agent It is a physical process. reVing on
 K ,  Hfl  ^ 8ner£D' **   B 99netiC material *the ce" C°NA and RNA).  The damage It causes results In
^inability of the cell to replicate. The optimum wavelength is between 250 and 270nm. The source of this energy
£ in almost all cases, a standard low pressure mercury arc  germicidal lamp, which has Its maximum output at
253.7nnx  These lamps are typically 0.75 and 1.5 meters long (arc length) and 1.5 to 2.0 cm In diameter.

UV equipment Is designed to have a number of lamps arranged In a reactor at centerline spacings ranging from 5
to 10 cm.  The lamps are inserted into quartz sheaths; these lamp/quartz assemblies are submerged  in the water
to provide maximum contact  with the  liquid. The size of the system is defined by the number of lamps; this is a
function of the lamp output  and spacing,  the flow rate, the Initial coliform levels, and the 'UV demand" of the
wastewater.. This demand is described by the UV transmittance or UV absorbance of the liquid, measured at 253.7
nm.

The "open channef modular system design is the most common configuration for treated wastewater applications.
It Is generally  comprised of several gravity flow, open  channels (depending on  plant size  and  the degree
ofredundancy) that hold one  or more  banks of lamps in series.  These are placed in the channel as modules that
can be easily removed for maintenance and repair.   In addition to the  lamp/quartz modules, the second  major
equipment element is the power/control pane! which  contains the lamp ballasts, operating monitors, and ground
fault interrupters.  The panels are generally designed to control a channel and/or bank of lamps, and are placed in
close proximity to the lamp reactors.


Common Modifications • Nearly all UV  systems use germicidal lamps that are sheathed in a quartz  sleeve  and
submerged in the liquid. There are some non-contact designs that suspend the lamps outside a 7 to 10 cm diameter
thin wall Teflon pipe that is transparent to the UV wavelengths and carries the liquid.  Other designs have the
 lamp/quartz assemblies fixed within large steel shell  reactors with piped inlet and outlets. These can be gravity flow,
or under  pressure.   The open channel  configurations can have the lamps placed horizontally or vertically in the
channel.  Accessary equipment will generally include ground fault Interrupters for each module, a UV intensity meter,
and a  cleaning system.              ,

In-place cleaning systems have included mechanical wipers and ultrasonic transducers, both of which have proven
to be ineffective. Automated chemical  recirculation may be used on some systems; these require isolation of the unit
and recirculation of a cleaning solution to restore the quartz surfaces.  An aeration header Is also typically installed
in these systems (beneath the lamp assemblies) to provide additional surface scouring. Automatic, In place systems
have not been wholly effective, particularly when applied to the open channel designs.  Most often manual chemical
cleaning is very effective and efficient. An auxiliary  cleaning tank aids this procedure.  The modules are lifted from
the channel and dipped into the tank's cleaning solution (with agitation), and then rinsed.

Liquid  level control (maintained  above the  top lamp/quartz) In the channel is accomplished by  several methods.
These  include a downstream  mechanical counterweight gate which works well over a wide range of flow, although
It appears to have problems  at very low flows.  Effluent weirs are used,  but It is important to have sufficient weir
length  to  minimize the  variation of depth over the weir.  Automatic level control gates are also used, controlled by
level sensors in the channel.

Medium pressure mercury arc lamps  have  been used as the UV source in some applications.  These tend to be
smaller lamps with  significantly higher intensity at the 253.7 wavelength, and have other  spectral fines within the
germicidal range. Experience is limited  with these systems.


Technology Status - There are over 500 operating plants in the U.S.. representing a rapid increase from an estimated
50 plants in 1984  The earlier first generation' systems were closed shell or non-contact Teflon pipe designs, with
a small number of open channel configurations. The dominant configuration now is the open channel design wtth
modular lamp/quartz Inserts.   These  comprise approximately three-quarters  of all operating plants,  and are the
preferred design for most new plants.

-------
 Design procedures for the process are In place,  but design parameters that are empirically based are not fully
 developed.  As such, design  sizing should be kept conservative.  Pilot studies may be considered If treated effluent
 Is available, particularly to develop data on the wastewater characteristics (initial bacterial densities, UV absorbance,
 and variability), and to assess the quartz surface fouling  potential (and procedures to clean the surfaces).


 Applications - UV disinfection Is applicable to effluents treated to secondary levels or belter.  Solids levels greater
 than 30 mg/L will limit the performance of UV systems to toss  than secondary requirements.  UV disinfection Is
 particularly applicable as an alternative to chorinatlon In cases where dechlorination is required or where there are
 overriding concerns with safety.  The process can be retrofitted to existing chlorination plants by Inserting the open
 channel modular design Into the chlorine contact chambers.


 Limitations -.-The UV process may not be  suitable In cases where there is excessively high absorbance at 253.7
 nm, or where there are high turbidity and suspended solids levels. Bacteria that are occluded in participates will not
 be affected by the UV radiation;  these will, in effect, form the performance limit for the process.  A  screening
 calculation for biological treatment plants Is to take 25% and 90% of the square of the effluent suspended solids
 (mg/L) to estimate the fecal and total cpliforms associated with the solids, respectively.

 Photoreactivation of UV exposed bacteria will result in an average increase of approximately one order of magnitude
 from the density Immediately after UV exposure. This is an enzymatic repair mechanism that Is catalyzed by exposure
 to visible light (sunlight); most organisms have this ability, although viruses do not. Design sizing can, however, take
 this repair into account In order to assure that effluent limits are  met on a consistent basis.


 Typical Equipment/No, of Mfrs. -  UV  systems are typically sold as complete  units, comprising the lamp/quartz
 modules, power supply and tamp  ballast panels, instrumentation, channel inserts, and level control devices.  There
 are an estimated five manufacturers that supply the municipal market.


 Performance - UV systems have  been demonstrated capable of meeting limits of secondary and tertiary levels.
 Colifomns associated with suspended solids can limit the lower  levels  attainable by the process,  and photorepair
 may interfere if not properly taken into account in the design of the system.

 A major factor in apparent system failures has  been attributed to lack of attention to cleaning,  or an  Inability to
 effectively clean the quartz surfaces. The newer modular designs allow for easy access to the quartz; these must
 be cleaned  on a preventive maintenance basis.


 Design Criteria -  UV  disinfection efficiency  is defined by the dose, which is the product of the UV  intensity and the
 exposure time (microwatts/cm2 x seconds equals microwatt-seconds/cm2).  UV intensity is a function of the UV lamp,
 the  lamp spacing, and the "sinks" of energy that will attenuate the radiation available for  disinfection.  Time  is a
 function of the reactor hydraulic characteristics and its proximity  to ideal plug flow.

 Attenuation of energy will be  through three primary mechanisms. The first Is aging of the  lamps,  in which the UV
 output of the lamp diminishes with operating time. This will usually be to a level between  65 and 75% of Its rated
 output within the first 2000 hours; It will remain at this level for the remainder of its operating life. Design should be
 for this "end of life" output. The second attenuation win be dependent  on the transmissibility of the quartz sheath.
 New quartz  will transmit 90 to 95% of the UV energy, but with time, aging and  surface abrasion will cause this to
 diminish.  Good maintenance should afiow an average quartz transmittance of 75 to 80%.  The third attenuation will
 be through the UV demand of the liquid itself. Design should reflect the expected transmittances at peak conditions,
 and on filtered samples. Typical values of UV transmittances (at 253.7nm, in a 1 cm cell) for wastewaters undergoing
varying degrees of treatment  (assuming a basically domestic plant) are 40 to 50% for a primary effluent, 55 to 65%
for a secondary plant, 60 to 70% for an advanced secondary plant, and 70 to 80% for a tertiary  plant

Hydraulic design demands a  close approximation of  ideal plug flow, with minimal dispersion.  Good approach and
exit conditions  about the  lamp battery are important, assuring  approximately equal velocities across the reactor
cross section through the length of the reactor.  In  open channel designs, perforated stilling plates can be used

-------
                                                 M *****ratio 
-------
The UV process does require 'expendables1.  These are primarily the lamps which have an operating life between
8000 and 12000 hours, and the ballasts and quartz, which will need to be replaced on a toss frequent basis (three
to five years).


Potential for Improved Toxics Management - Use of UV light as an alternative to chlorine would serve to reduce the
toxics problems that have been associated with chtorination disinfection.


Flow Diagram -
     \ss ss~*
Control/Poww
Cabhwts _.





m







n


      i*nfc«l
L*v») Control
    Gate
            Influent
            ChatvMl
                                       S»cOon

                          ClwnrMl Control D*vtc*
 /
 /
 /
 /
/
 /
/

#
/
/
\
                                        Han
                                                                        Efflumt
                                                                        Chanoal
              Typical Layout of UV Open Channel Configuration (with horizontal lamp placement)


 Energy Notes -  The UV process requires electrical energy to power the lamps. Overall power requirements can
 be estimated on the basis of 100 watts per 1.5m arc lamp, or 60 wans per 0.75m lamp.  Power utilization is based
 on the actual number of lamps In operation.  As a general rule, one should expect to have  an average of 40 to 50%
 of the system In operation at a given time.


 References •

 1.  Scheible, O.K., Ultraviolet Disinfection, In  Proceedings, Field Evaluations of Municipal  Wastewater Treatment
 Systems, U.S. EPA-Risk Reduction Engineering Laboratory, Cincinnati, OH., 1988.

 2.  Scheible, O.K. M.C  Casey,  and A. Fomdran, "Ultraviolet Disinfection of Wastewaters from Secondary Effluent
 and Combined Sewer Overflows,' EPA/600/2-86/005, NTIS No. PB86145182, U.S. EPA-Municipal Engineering Research
 Laboratory, Cincinnati, OH., 1986.

 3.  U.S. EPA, Design Manual - Municipal Wastewater Disinfection, U.S. EPA Office of Research and Development,
 EPA/625/1-86/021, Cincinnati, OH., 1986.
4.  U.S. EPA, Ultraviolet Disinfection Special Evaluation Project, Region 5, Chicago, IL, September 1988.

-------
SLUDGE

-------
WET AIR OXIDATION OF SLUDGE, LOW PRESSURE                                         FACT SHEET
     S

Description - Low pressure wet air oxidation of sludge involves the heating of sludge to a temperatures of between
150 to 210°C at a pressure of 150 to 400 psig for periods of 15 to 40 minutes with or without air.  This process
should result in a sludge being dewaterable with minimal or no chemical conditioning. Thermal conditioning results
in a breakdown In the sludge cell structure, sterilization of the sludge pathogen content, and a slight solids reduction
through oxidation and solubilization of the volatile suspended solids. The warm sterilized sludge remains susceptible
to bacterial recontamination which can produce obnoxious odors and pose a disease risk.

In the low pressure wet air oxidation process,  sludge is passed through a heat exchanger into a reactor vessel,
where steam is injected to bring the temperature  and pressure  within  the reactor vessel to the necessary range.
After treatment, the sludge passes back through the heat exchanger and is then discharged to a thickener- decanter
tank.  The Incoming sludge solids concentration is generally in the range of 3 to 8 percent and the sludge solids
should  be screened or ground prior to thermal conditioning.  The thickened conditioned  sludge may be directly
applied to the land or dewatered by centrifuge, vacuum filter, plate and frame, filter press, or belt filter press.


Common Modifications - Several proprietary variations exist. Normally, air Is injected Into the reactor with the sludge.
This configuration is the most common (95 percent of low pressure wet air oxidation facilities). The process can also
be conducted at a higher temperature and pressure, generally resulting in more complete oxidation of the volatile
solids.

  * .*''•*-"  1"       ' '                !       '      -
Technology Status - Low pressure wet air oxidation of sludge was first introduced in Europe in 1935, but installations
in the United States did not begin to appear until the 1960s.  To date over 60 installations have been installed In the
United States.


Applications • Low pressure wet air oxidation is practiced  as a sludge conditioning method  to reduce the costs of
sludge  dewatering and  ultimate disposal.  The benefits include:  (1) improved dewatering characteristics of treated
sludge with minimal or no chemical condatoning; (2) significantly  reduced pathogen content making the conditioned
sludge  more suitable for ultimate disposal by land application; (3) suitability for sludges which cannot  be stabilized
biologically; and (4)  reduction in size of subsequent  dewatering  equipment.


Limitations - The process has high operating  costs, and is not normally  economical at small treatment plants.
Skilled supervision and maintenance are required due to the high temperatures and pressures involved. Inadequate
operator attention has been known  to result in system reliability problems.  Expensive materials are required to
prevent corrosion and withstand the  operating conditions.  Heavy metal concentrations in sludges are  not reduced.
The  sludge supernatant and filtrate  recycle liquor are strongly colored and contain  a  very high concentration of
soluble organic compounds and ammonia nitrogen. This stream must either be pretreated prior to return to the head
of the treatment plant or included in the calculation of biological system organic loading.  The process  produces an
odorous gas stream that must be collected and treated before release.


Typical  EQuioment/No. of Mfrs. - Several manufacturers supply  complete proprietary thermal sludge conditioning
processes.


Performance - Thermal conditioning of sludge results in (1)  destruction of pathogens (the sludge remains susceptible
to recontamination);  (2) decrease hi volatile solids loading to downstream processes of 30 to 40 percent due to
oxidation and solubilization of the volatile suspended solids; (3) reduced or eliminated need for chemical conditioning;
(4) improved thickening and dewatering properties.


Physical/Chemical/Bloloolcal Aids  - Process requires an addition of heat, but eliminates or reduces  the need for
chemical conditioning prior to  dewatering.  Scale inhibitors may be required for the boiler. Intermittent  acid washing
to remove scale will  be required in the exchangers, pipes, and reactor.

-------
Residuals Generated - The liquid sldestream Is generally about 75 percent or more of the sludge flow (by volume);
typical characteristics - BOD. 5.000 to 15.000 mg/l; COD, 10.000 to 30.000 mg/I; NH3-N. 500 to 800 mg/l; P, 140 to
250 mg/l; TSS, 9,000 to 12,000 mg/I; VSS. 8,000 to 10,000 mg/l; pH. 4 to 6.

The liquid sidestream is generally amenable to biological  treatment but can  increase the organic loading to  a
treatment plant by up to 30 to 50 percent If the plant has not been  designed for this additional load, pretreatment
of the liquid sidestream prior to return will be necessary.  The composition of this sidestream can vary among the
various processes.  It may contain a high proportion of non-biodegradable matter.  This matter is largely humic acids
which can give rise to unpleasant odors.  The actual chemical composition of  the liquid  sidestream  should be
determined by detailed chemical analysis of a  pilot unit A possible treatment process for a high  concentration
sidestream can consist of filtration, aeration and activated carbon adsorption for non-biodegradable organics.


 Design Criteria - Temperature: 150 to 210°C, Pressure: 150 to 400 psig, Detention Time: 15 to 40 minutes, Influent
 Sludge Concentration: 3 to 8 percent, Steam Consumption:  600 Ibs per 1,000  gallons of sludge.


 Reliability - Careful operator attention is required.  Mechanical and process reliability appears adequate as long as
 sufficient operator attention is provided; however, a number of installations have experienced reliability problems as
 a result of inadequate operation training and attention, as well as short service  lives of key components.


 Environmental Impact - The liquid sidestream has a very high organic loading which may  cause plant upsets and
 a colored effluent.  The gaseous sidestream is odorous and proper odor control must be practiced.  Heavy metals
 generally remain insoluble  and wi« be disposed of in the sludge.
 Flow Diagram
             RAW SLUDGE
SLUDGE
HOLDING
TANK


SCRECN
OR
GRINDER


FEED
PUMP
                        EXHAUST GASES -•-
                          SUPERNATANT
                    CONDITIONED SLUDGE
References -

1.  Ewing. Lewis, et. al., "Effects of Thermal Treatment of Sludge on Municipal  Wastewater Treatment Costs',
EPA/600/2-78-073. June 1978.

2. Metcalf & Eddy, Inc., Wastewater Engineering: Collection, Treatment, Disposal, McGraw-Hill.

3. U.S. EPA, 'Process Design Manual for Sludge Treatment and Disposal,' EPA/625/1-79-011, September 1979.

-------
WET AIR OXIDATION OF SLUDGE, HIGH PRESSURE                                         FACT SHEET

1  "   **"
Description - High pressure/high temperature wet air oxidation (HPO) is a process in which sludge is completely
oxidized at high temperature, pressure and air concentration. This process can be an alternative to incineration, and
results In a similar ash residue.  There are two general types of HPO equipment, aboveground and deep-well type
The deep-well type is called a Vertical Tube Reactor (VTR).

In the HPO process, sludge is first ground or screened to reduce the size of the feed solids.  Next, the solids
concentration is adjusted to between 2 and 8 percent by either dilution or thickening.  In the above ground systems,
a high pressure pump then  pumps the sludge through a heat exchanger into a reactor vessel  Air is mixed with the
sludge before entering (and sometimes In) the reactor.  Steam is added in the reactor during startup. During normal
operation, the oxidation process generates excess heat and steam is no longer needed. The oxidized sludge passes
back through the heat exchanger to recover heat and is then discharged to a thickener-decanter tank. The pressure
in the reactor must be sufficient to prevent the water from vaporizing at the temperature selected for the reaction.

The VTR units do not require a high pressure pump.  Pumpage is required only to overcome friction losses and
differences in elevation of the sludge storage and decant tanks.  The VTR obtains the high pressures required for
the process using the hydrostatic head at the bottom of the system.


Common Modifications - Several proprietary vacations exist for HPO. for example oxygen may  be .used in lieu of,
or in addition to, air as the oxidant source.


Technology Status - Wet air oxidation of  sludge was introduced in the earty 1960s.  There are few installations In
operation.  The VTR process was developed in the 1970s and operating experience is  limited to one full-scale
prototype operated with some success during 1984 and 1935. Several municipalities (e.g., Houston)  have chosen
the VTR process due to  its expected lower operating cost relative to the pumping requirements.


Applications - Wet air oxidation of sludge can be an alternative to incineration as a solids reduction process.  The
resulting oxidized sludge is easy to dewater and does not  usually  require conditioning chemicals.  The volume of
sludge solids may be reduced by 70 percent or more depending on the volatile solids and moisture content of the
feed sludge.  The oxidized  sludge is sterile and innocuous.


Limitations - The  process has a very high capital cost.  The operating cost may be offset somewhat by energy
recovery from the oxidized sludge. The operating cost of the VTR process may be lower than for the aboveground
units due to the lower pumping costs.  Operating data are very  limited for either process configuration and hence
reliable  estimates of the total costs  are not available.  The aboveground HPO process produces an odorous gas
sidestream that must be collected and treated before release. The  liquid sidestreams of HPO systems may have a
significant concentration  of soluble  organic compounds and ammonia nitrogen concentration which  may require
pretreatment prior to returning to the head of the treatment plant.  HPO systems require specialized supervision and
maintenance due to the high temperature and pressure involved.  The process produces an odorous gas stream that
must be collected and treated.


Typical Equipment/No, of Mfrs. - Two manufacturers supply  complete VTR processes on a privatization or purchase
basis.  Several  manufacturers supply complete aboveground HPO processes.


Performance - Wet air oxidation of sludge results in: (1) the oxidation of volatile solids, with reductions of up to 70
percent, (2) the destruction  of pathogens, (3) Improved sludge dewatering properties, and (4) the possible removal
of some toxic pollutants.

-------
 Physlcal/Chemical/BioloQical Aids - The HPO process requires addition of heat during startup until the process
 become autogenous.  Scale inhibitors may be required for the boiler.  Intermittent acid washing to remove scale
 may be required In the heat exchangers, pipes, and reactor.


 Residuals Generated - The quality of the liquid sidestream improves with a higher degree of oxidation.  The quality
 may be similar to a thermal conditioning liquid sidestream for less complete oxidation processes. In the VTR process,
 nearly complete oxidation Is claimed, but full scale operation  information is lacking.


 Potential for Improved Toxics Managements - When operated in the upper temperature  range, the HPO processes
 potentially can  provide essentially complete destruction of a broad range of hazardous  and toxic compounds.


 Design Criteria - Temperature: 210 to 315°C, Pressure:   1,000  to 1,800 psig, Detention Time:  15 to 60 minutes,
 Influent Sludge Concentration:  2 to 8 percent


 Reliability - Highly trained operations personnel with machinist skills are required for HPO  systems,  especially for
 aboveground HPO units with high pressure pumps and piping. Reliability data are not available for the VTR process.
 The HPO  systems  have generally  been abandoned by municipalities due to limitations (cost, odors,  sidestream
 problems and overall maintenance difficulties).


 Environmental  Impact - Toxic  compounds may be destroyed in higher temperature units.  Heavy metals remain
 insoluble and pass through system and remain  in the  sludge.  The liquid sksestream may have a high organic
 loading.  The gaseous sidesiream may be odorous in lower  temperature processes.  Potential for explosion with
 improper O&M. Subsurface effects of VTR systems must be considered for each potential application  site.
 Flow Diagram - Above Ground -
                RAW SLUDGE
SLUDGE
HOLDING
TANK


GRINDER
OR
SCREEN


FEED
PUMP
                            EXHAUST wzs
                            SUPERNATANT
                         OXIDIZED SLUDGE
References -
1.  Kaufman, Leonard A. and Hermann Peterscheck. 'Modeling Vertech's Mile Long Multi-phase Reaction Vessel',
Chemical Engineering Science (G.B.), Vol. 41, No. 4, 1986. pp 685-692.

2.  U.S. EPA. "Process Design Manual for Sludge Treatment and Disposal,' EPA/625/1-79-011, September 1979.

3.  U.S. EPA. "The City of Longmont, CO., Aqueous-Phase Oxidation of Sludge Using the Vertical Reaction Vessel
System", Water Engineering Research Laboratory, Cincinnati, Ohio, January 1987.

-------
SLUDGE DRYING, THERMAL                                                                 FACT SHEET
        x"

Description - In the thermal drying process, the moisture in the sludge is reduced to 8 to 10 percent (by weight) by
hot air evaporation of the moisture.  For economic reasons, the moisture content of the sludge must be reduced as
much as possible through mechanical means prior to sludge drying.  The available thermal sludge drying techniques
are flash, rotary,  toroidal, multiple hearth and atomizing spray.

Flash drying is the instantaneous vaporization of moisture from solids by introducing the sludge into a hot gas
stream.  The wet sludge cake is first blended with some previously dried sludge in a mixer to improve pneumatic
conveyance. The blended sludge is mixed with hot gases from the furnace at about 1,200 to 1,400°F (650 to 760°C)
and then fed into a cage mill in which the mixture is agitated and the water vapor flashed. The residence time in the
cage mill is a matter of seconds. The sludge, which has been dried to a moisture content of 8 to 10 percent, is then
separated from the spent drying gases in a cyclone, with part of the dried sludge being recycled for mixing  with
incoming wet  sludge cake and the remainder being screened and  sent to storage.  The exhaust gases must be
treated to control odors.

A rotary dryer  consists of  a cylinder which is slightly inclined from the horizontal and revolves at above four to eight
revolutions per minute.  The  inside of the dryer usually is equipped with flights or baffles throughout its length to
break up the sludge.  Prior to the rotary dryer, wet cake is mixed with previously heat  dried sludge in a pug  mill.
The  system may Include cyclones for sludge and gas separation, dust collection scrubbers, and a gas incineration
step. Sizing devices may be added after th? rctary dryer to separate, crush and screen the dried sludge.

The  toroidal dryer uses the jet mill principle, in which heated air is injected into a doughnut-shaped drying vessel to
create a high speed air current which dries and classifies sludge solids simultaneously.  Dewatered sludge is pumped
into  a mixer where It is blended with previously dried sludge to make the mixture free flowing. The blended material
is fed into the doughnut-shaped dryer where it comes into contact with heated air at a temperature of 800 to 1,000°F.
The  particles are dried  and broken up into fine pieces.   A portion from the whirling stream of dried fine sludge
.particles and air is withdrawn, and dried solids are separated from the airstream.

The  multiple hearth furnace is adapted for heat dtying of sludge by incorporating fuel burners at the top and bottom
hearths, plus down draft  of the gases.  The dewatered sludge cake  is mixed in a pug mill with  previously dried
sludges before entering the furnace. Also, fluidized bed drying has been used ahead of fluidized bed furnaces.

Atomizing drying involves spraying liquid sludge upward into  a vertical tower through  which hot gases pass
downward. Dust carried with  hot gases is removed by a wet scrubber or dry dust collector. A high-speed centrifugal
bowl can also be used  to atomize the liquid sludge into fine particles and to spray them into the top of the drying
chamber where  moisture  is transferred to the hot gases.


Technology Status - Although heat drying of sludge was developed more than 50 years ago, it Is not widely used.
The rotary dryer/pelletization process currently has three successfully operating facilities (Largo, FL; Cobb and Clayton
Counties, GA)  and three planned facilities (Boston, MA; Tampa, FL;  and Hagerstown, MD).  Sludge drying facilities
in Orlando. FL and Washington, DC have been unsuccessful.


Application - Sludge drying can be an effective way to process stabilized sludge prior  to ultimate sludge disposal
when the sludge is to be applied to land for agricultural and horticultural uses. Although It is an expensive process,
It can become a viable alternative If the product can be successfully marketed (e.g., Milorganite). An acceptable
product for marketing should have a total nitrogen content greater than 3.5 percent.  Dried sludge sells m  bulk for
up to $20 per  percent nitrogen per  product ton.


Limitations  - Processing costs  are  high relative to other  options and markets may not be available for the end
product.  Skilled operators are required to manage  sludge drying systems.  Without odor control, odors can  be  a
problem.

-------
 Typical Equipment/No, of Mfrs. - Complete heat drying systems are generally proprietary.  The major equipment
 components  include:   mixers, furnaces,  cyclones, screens, dryers, wet  scrubbers, dust collectors, air blowers,
 heaters, spraying devices, sludge feed pumps and handling equipment.


 Performance  - Heat drying destroys most of the bacteria In the sludge.  However, undigested heat dried sludge is
. susceptible to putrefaction in land applications If thick layers on the ground are allowed to become wet. Heat drying
 does not cause any significant decrease  of the  heavy metals concentration in the sludge.  In general, the natural
 nutrient content of heat dried sludge is only about 5% nitrogen  (approximately 5-10-5 N/P/K).  However, ft is an
 excellent slow-release nitrogen fertilizer for golf courses, orange groves, etc.


 Physical. Chemical and Biological Aids - Nitrogen and phosphorus may be added to increase nutrient values of the
 dried sludge.


 Residuals Generated  - All the solids  captured in the  wet scrubbers  and dry solids collectors are recycled and
 incorporated  in the end products. Wastewater from odor control devices and coolers must be treated by recycling
 through the plant


 Design  Criteria - The  most critical  consideration is to  produce a high solids cake in dewatering.  Approximately
 1,400 BTU are needed to vaporize  one pound of water, based on a thermal  efficiency of 72  percent.  Less fuel
 would be required with additional heat recovery.  Chemical scrubbers are used, or chemicals are added prior to
 heat drying.  Excessive drying tends to produce a sludge that is dusty or contains many fine particles, which Is less
 acceptable for marketing, and should be  avoided.  The finer material might possibly be desirable as a binder for
 chemical fertilizer or for making larger pellets. Wet scrubbers and/or solids collectors are needed.  Standby heat
 drying equipment is needed for continuous operation.


 Reliability - Careful operator attention by trained operators is required.  Although mechanical and process reliability
 have been demonstrated, some equipment has proved to be unreliable and has had to be shut down (e.g., Orlando,
 FL).


 Environmental Impact  - Potential for explosion and air pollution if the system is not property operated and maintained.
 Strong odors may be produced by the process.
 Flow Diagram -
                            EXHAUST CAS SEPARATOR AND TREATMENT I
          DEWATERECT
                 i
          SLUDGE
DRIED

SLUDGE
                                   HEAT
                                   AGENT
 References -

 1.  Pollution Equipment News, 1989 Buyers Guide, November 1988.

 2.  U.S. EPA, 'Sludge Handling and Conditioning1, EPA/430/9-78-002, February 1978.

-------
 Flow Diagram -
       COOUNC At* DISCHARGE	.   |
             SLUDGE INLET—v   ^Q
     COMBUSTION
     A« RETURN
      RABBLE Aftu
    SHAFT COOUNC AIR
FLOATING DAMPER
        FlUC CASES OUT
                                              CAS EXHAUST
    DRYING ZONE
    SUPPLEMENT AL
        FUEL
    COMBUSTION ZONE
                                                  RABBLE ARM AT
                                                  CACH HEARTH
                                            COOLMC ZONE
         ASH DISCHARGE
                                                           FURNACE EXHAUST
                                     SCRUBBER
                                                                                           INDUCED
                                                                                           DRAFT FAN
                                                                                               SCRUBBER
                                                                                                WATER
                                                                                          1 DRAIN
                                            COOUNC AIR FAN
 References -
 1.  Brunner, Calvin R., Design of Sewage Sludge Incineration Systems, 1980.
 2.  Brunner, Calvin R., Incineration Systems, Selection and Design, Van Nostrand Reinhold Co. NY NY 1984.
 3.  Chemical Engineering Equipment Buyers Guide Issue 1989. McGraw Hill. NY, NY August 1988.
 4.  Engineering-Science, Inc., Review of Newer European Sludge Handling, Dewatering, and Incineration Technology,
 A Trip Report, Fairfax, Virginia, March 1988.
 5.  Engineering-Science, Inc., Proprietary Incinerator Design and Modeling. Fairfax, Virginia,  November 1988.
 6.  Hazardous Materials Control Research Institute, Municipal Sewage Treatment Plant Sludge Management, No. 17,
 Silver Spring, Maryland, 1987.
 7.  Hazardous Materials Control Research Institute, Municipal Sewage Treatment Plant Sludge Management, No. 18,
 Silver Spring, Maryland, 1987.
 8.  Hazardous Materials  Control Research Institute, 1987  Hazardous Materials  Control Directory,  Silver Sphng,
 Maryland, 1987.
9.  U.S. EPA, •Municipal Wastewater Sludge Combustion Technology.'  EPA/625/4-85/015. September 1985.
10. U.S. EPA, -Multiple Hearth and Fluid Bed Sludge Incinerators. Design and Operational Considerations,* EPA/430/9-
85-002,  September 1985.
11.  U. S. EPA/Radian Corporation, Municipal Waste Combustion Study, Data Gathering Phase, 1985.
12.  Water Pollution Control Federation,  Incineration, Manual  of Practice No. OM-11, Atexandria, Virginia, 1988.

-------
INCINERATION Of SLUDGE, FLUIDEED BED FURNACE (FBF)                                FACT SHEET


Description. The purpose of Incineration is to destroy the organic fraction of the sludge thai  is generated during
wastewater treatment. During the incineration process residual moisture is first removed from the sludge cake  and
then organic matter is thermally destroyed.  Inerts  In the sludge remain as a  residual ash  Sludge should be
dewatered to 55 to 85 percent moisture prior to incineration in order to minimize the energy  required to remove the
residual motsttire.  Fluidized bed furnaces (FBF) typically use sludge at the drier end of this range.  To obtain the
information needed for process selection and design, each sludge to be incinerated must be subjected to thorough
physical-chemical analysis.

The FBF is a vertically oriented, cylindricalry shaped, refractory lined steel shell that contains a sand bed situated over
fluidizing air diffusers called tuyeres. A typical FBF is 9 to 25 feet in freeboard diameter with a 2.5 foot thick sand
bed. Dewatered sludge is usually fed into or just above the bed.  Air injected at 3 to 5 psig simultaneously fluidizes
both the bed of hot sand and the incoming sludge. Temperatures of 1,300 to 1,500°F are maintained within the bed.
Typical residence times are 2 to 5  seconds. As  the sludge bums, the entire  ash production and some sand are
carried out the top of the  FBF.  The overall combustion process occurs in two zones.  Within the bed  (zone 1)
evaporation of water and pyrotysis  of organics occur nearly simultaneously.  In the freeboard  area  (zone 2) fixed
carbon and combustible gases are burned.  Zone  2 acts as an afterburner, but may not be as efficient as a  separate
unit. When needed, supplemental fuel may be injected above or directly into the bed. Sand make-up requirements
are generally 5 percent of  bed volume every 100  to 300 hours of operation.


Common  Modifications - A hot or warm windbox design uses heat exchanged from combustion gases to preheat
the air  before injection.  Cold windbox designs inject ambient air directly into the  FBF. Water spray systems are
used in some units for temperature control where sludges having higher heating values are  incinerated. Some
incinerator heat exchange  designs  use an  intermediate heat exchange medium such  as heated oil, hot  water or
steam to transfer process  heat to the influent sludge or other  POTW streams. This heat exchange  method tends
to be less costly and easier to replace than conventional shell and tube  type exchangers.  As emission standards
become stricter, multiple air pollution control units are being used in combination. A separate afterburner Is not
normally required for control of organic emissions. The vast majority of FBF incinerators Installed since 1978  use
a combination of venturi and Impingement tray scrubbers to control emissions.


Technology Status • Approximately  20 percent of  wastewater sludge Is managed by the incineration  process.   The
FBF has gained increased popularity since its 1961  introduction. As of 1985,  38 FBFs at 33 facilities were in use,
with capacities varying from 0.7 to 145 dry tons per day. The average capacity was 23 dry tons per day.  This small
capacity reflects the tendency for smaller plants to prefer FBFs over multiple hearth furnaces due to FBF's  ability to
be  intermittently operated and the simplified O&M requirements of FBFs.


Applications - Incineration is frequently considered as an alternative for plants handling wastewater flows greater than
10  mgd.  n  is a good alternative for  urban areas lacking other options, provided that air pollution controls are
adequate   Some sttes, however, have had difficulties in obtaining permits from regulatory agencies.  With appropriate
modifications and careful operation, screenings, grit, scum and grease can also be handled.  Because the sand bed
of the FBF acts as a heat s**, tf»  FBF may be used for Intermittent operation with a minimum amount of start-up
time  For exampto I can be restarted after a weekend shutdown with 1 to 2 hours of heating. The FBF also requires
less excess air and toss fuel than the multiple hearth design.  As wan other incinerators, the potential exists for energy
recovery and recycling of ash for use hi road surfaces or  building blocks or for materials reclamation.


Limitations - The fluidized bed requires a minimum  amount of air to maintain bed fluidizatlon, regardless of the amount
of waste feed  The FBF may therefore exhibit optimum power consumption at rts design point, but higher power
consumption at  lesser feeds. Feed  to the FBF must be via positive displacement pumps °r
screw/plunger type feeders. Because the air emissions contain  sludge ash and elutrsted sand, higher energy verttun
scrubber systems are often required.

-------
Typical EQuloment/No. of Manufacturers - FBFa/11, Air Fans/53, Screw Pumpe/Ptoton Pumps/11, Supplemental Fuel
Bumers/2S.  Preheatecs/60, Venturl  Scrubbera/57, Impingement Tray Scrubbers/35. ESP/23,  Bag Houses/62, Ash
Conditioning/6.


Performance • The ash volume produced Is typteaffy 30 to 40 percent of the dry solids fed to the unit  As much
as 35 percent of the total heat Input to the FBF may be recovered using high efficiency neat exchangers (85 percent
efficiency).


Design Criteria - Bed loading rate to typically 44 to per ff-nr of water for a hot windbox design and 35 to per ft*-hr
of water  for a cold windbox design.  Bed velocity » 2 to 3 feet per second, bed expansion -  30 to 60 percent,
maximum operating temperature above the bed » 1,500°F (desired operating temperature within the bed is typically
100°F lower): Combustion air requirements  should be determined by an utimate analysis of  sludge combustibles.
Excess air » 20 to 45 percent


Unit Process ReHabittv - The FBF tsetf Is comprised of few mechanical components with the exception of the forced
draft fan.  The majority of problems tend to  occur with the auxiliary equipment needed to  support an FBF system.
Sand, ash and flue exhaust from the FBF tend to cause corrosion problems with downstream scrubbers  and heat
exchange equipment  Slagging problems associated wtth the presence of soluble potassium and sodium have also
been reported.  A common problem during hot s-andby is the drying and hardening of the sludge feed in the Injection
ports which can result m problems with screw feeders and sludge handling equipment  Scaling  problems with the
preheater and venturi scrubber have also been reported.  Failure of the refractory dome just below the sand bed has
occurred in some Instances.


Environmental Impact • Scrubber technology to generally sufficient to meet existing paniculate emissions requirements,
but  new  regulations may require more complex equipment,  such as wet  electrostatic prectpttators, to handle sub-
micron particles, particularly for larger Installations with higher total mass  emissions.

The controlled emission rates of metals and organics wffl vary  as a function of sludge  composition, Incinerator
operating parameters, and types of air pollution control equipment used.  Emission  rates  must be assessed on an
Individual sludge basis.  Except for mercury and to a lesser extent arsenic, cadmium,  and lead,  incinerators  emit only
a small fraction of the metals found In sludge.


Chemicals Required • Supplemental fuel ofl or natural gas to required for non-autogenous sludges, incinerator start-
up and standby and afterburner operation, If required. When available, digester gas to often used as the primary fuel.
Other fuels Include waste oil and bunker oiL


Residuals Generated • The combustion gases and nearly aHtheashexKthetopofthe FBF. The total ash produced
to between 20 and 50 percent of the dry solids content of the sludge, and depends upon the combustible fraction
of the sludge. The oh generated may be considered hazardous  V, upon leaching by current extraction procedures,
the teachate contains levels of specific metals or organJcs m excess of published standards.


Potential  for Improved Toxics Management • The FBF generally results In lower emission rates for volatile organics
as compared to a multiple hearth furnace that to not equipped wtth  a separate afterburner.

-------
Flow Diagram -
                             EXHAUST AND ASM
  BURNER
SUPPVJTMfNTAL
    FUEL

 TUYERES
                                                                          CAS EXHAUST
                                                                 FAN
                                                         PREHEATER
                                                   J /VENTURI
                                                     	
                              RCCYO.E WATER
                                                        MAKEUP WATER
                                                                                     WATER
                                                                                    DRAIN
                                                                                    ASH
 References -
 1.  Brunner, Calvin R., Design of Sewage Sludge Incineration Systems, 1980.
 2.  Brunner, Calvin R., Incineration Systems. Selection and Design, Van Nostrand Reinhold Co. NY, NY. 1984.
 3.  Chemical Engineering Equipment Buyers Guide Issue 1989. McGraw Hill. NY, NY. August 1988.
 4.  Engineering-Science, Inc., Review of Newer European Sludge Handling. Dewatering, and Incineration Technology,
 A Trip Report. Fairfax, Virginia, March 1988.
 5.  Engineering-Science, Inc.. Proprietary Incinerator Design and Modeling. Fairfax, Virginia, November 1988.
 6.  Hazardous Materials Control Research Institute, Municipal Sewage Treatment Plant Sludge Management. No. 17,
 Silver Spring, Maryland,  1987.
 7.  Hazardous Material Control Research Institute, Municipal Sewage Treatment Plant Sludge Management, No. 18,
 Silver Spring, Maryland,  1987.  '
 8.   Hazardous  Materials Control Research Instftute.  1987 Hazardous Materials Control Directory. Sifcer Spring,
 Maryland. 1987.
 9.  U.S. EPA, "Municipal Wastewater Sludge Combustion Technology." EPA/625/4^5/015, September 1985.
 10. U.S. EPA, -Muttiple Hearth and Fluid Bed Sludge Incinerators. Design and Operational Considerations," EPA/430/9-
 85-002,  September 1985.
 11. U. S. EPA/Radian Corporation,  Municipal Waste Combustion Study. Data Gathering Phase, 1985.
 12. Water PoLution Contro. Federation. Indneration, Manu* of Practk* No. OM-11. Alexandria, Wginia. 1988.

-------
LAND APPLICATION OF SLUDGE                                                           FACT
                             ** ^9 dlsposal te a P"*9™*1 •"dfl* management alternative because of Its low
                         hr 22! recycte **" * "» ***••  " utilizes ^ p»*** *•"** a* "dogS
             the sal to absorb, adsorb, and decompose waste constituents in the sludge. The primary objectives
of design and management are to provide an environmentally safe final disposal for the waste, maintain the land's
potential for future use, and gain and maintain public acceptance.

The quality of the  sludge  depends on the characteristics of the original wastewaters and the manner in which the
sludges are subsequently treated (e.g., aerobic and anaerobic digestion, thickening, lime stabilization, conditioning
dewatering, composting, heat drying, etc.). Sludge characteristics that are important to land application include water
content,  degree of stabilization and pH.  The water content determines transportation costs and the method of
application; stabilization influences btodegradability, pathogen destruction and odor potential; and pH determines the
potential for leaching metate from the soil/sludge and the subsequent  metals  uptake by crops.  Beneficial sludge
constituents include nitrogen,  phosphorous, potassium and certain trace metals that act as fertilizer nutrients, and
organic material that serves as a soil conditioner.  Careful management is needed to control pathogens, toxic metals,
and toxic organics.

Land applied sludge can be an excetient substitute for commercial fertilizers and soil amendments, and can be cost
effective for both the municipality applying the sludge and the application site which accepts  the sludge. The use
of wastewater sludge as a source or suppte.Ter: of fertilizer nutrient to enhance  crop production  is widespread in
the United States.  Commercial timber and fiber production lands, as wed as federal and state forests, are potential
application sites. Sludges have also been successfully applied to disturbed or marginal lands (e.g., mining or mineral
processing  operations, sandy and  unproductive  areas, etc.) to enhance  reclamation and revegetation.  Land
application to a dedicated disposal site is also practiced.


Common Modifications - Methods vary for transporting and applying sludge to the land site.  The same transport
vehicle that hauls sludge to the application site can atso be equipped to apply the sludge to the land. In other cases,
the transport vehicle hauls sludge to the site and transfers it to an application vehicle and/or storage facility. Sludges
are also pumped and transported by pipeline to storage facilities at the site, and then transferred to an application
vehicle.

The sludge application method and the schedule for applying sludges are dependent on the characteristics of the
sludge and soils, and on the types of crop. Three categories of crops are usually grown:  agronomic or row crops,
forage crops and  grasses, and forested systems.  Sludge can be applied to either the land surface  (spreading or
spraying) or to the  land subsurface  by  Incorporating (Injection, disking, or plowing) the sludge into the topsoil.
Dewatered sludge  cannot be pumped or sprayed, and typically is spread over the surface and then plowed or disked
Into the soil.


Technology Status • Land treatment systems can be designed to provide an acceptable means of waste management
that is reliable and predictable.  Agricultural utilization  of sludge is extensively practiced.  Sludge application to forest
lands and land r«damatJon sites Is practiced to a limited extent  In some cases, land sites are dedicated to sludge
disposal.


Limitations - Sludge contains constituents (I.e., heavy metals, toxic organics, and pathogens) potentially harmful to
crops or animals and humans who consume the crops. However, good  management practices have been developed
to limit the potential for harm that exists by way of soil and water contamination, crop damage, and accumulation
of harmful components In the food supply.

Land applied sludge is generally required  to undergo a stabilization  Process to  Significantly Reduce  Pathogens
(PSRP7 Crops for direct  human consumption require either a minimum of 18 months between sludge apPl.cat,on
and  growing or the sludge must undergo  PSRP  prior to application.   These PSRP processes may «ck*a
composting heat  drying,  heat treatment, thermophilic aerobic digest.on, pasteurization, Irradiate, etc. Federal
regulations also include limits  on cadmium, polychkxobiphynyls (PCBs) and soil pH.

-------
During periods of the year when the soil is wet, frozen or snow covered,  sludge often can not be applied and
storage (e.g., stockpiles, lagoons, tanks, digesters)  Is necessary.  For maximum crop yield when using sludge the
application of certain additional fertilizer elements such as potassium may be required.  For forest land utilization, both
control of public  access and access to some forest lands for conventional  sludge application equipment may be
difficult   For  disturbed  or marginal land reclamation,  some grading and  other  site preparation  steps  may be
necessary.  For dedicated land disposal, land may have to be purchased or leased and build up of metals in the soil
might limit future  use.


Applications - For agricultural utilization, sludge contains macronutrfents (nitrogen, potassium and phosphorous) and
micronutrients (boron, manganese, copper, molybdenum and zinc) and can be a valuable soil conditioner. For forest
land utilization, sludge contains nutrients and essential micronutrients often lacking in forest soils and organic matter
which can Increase the permeability of fine-textured clay soil or Increase the water-holding capacity  of sandy soils.
For reclamation of disturbed  and marginal lands, sludge organic  matter can Improve granulation, reduce plasticity
and cohesion, increase  water holding capacity and soil CEC, supply plant nutrients, and increase the buffering
capacity of the soil.


Typical Eoulpment/No. of Mfrs. - Surface application equipment Includes farm tractors, tank wagons, special applicator
vehicles equipped with flotation tires, tank trucks, and Irrigation systems. Subsurface application equipment Includes
tractor-drawn tank wagons with Injection shanks or tank (nicks fltted nth flotation tires and  injection  shanks.
Dewatered sludges require handling equipmb.it v;mDar to that used in applying animal manures, limestone, or solid
fertilizers.   Dewatered sludge is typically surface-applied  and then Incorporated  by plowing or disking.  More
specialized and/or heavy duty equipment may be used for applying sludge to forest and reclamation sites.


Performance - Land  application  is a viable, environmentally sound, and cost-effective technology without nuisance
or adverse environmental effects if property designed and managed. Sludges with minimum concentrations of metals
and organics can be applied at rates meeting the nitrogen or phosphorus requirements of the vegetation. It Is unlikely
that copper, zinc, and nickel will cause human health problems In properly managed systems.  Cadmium Is  typically
the metal of concern and may determine the life of the application site.


Design Criteria - If proper steps are taken In designing the system, very few sites are totally unacceptable  for land
application  of municipal sludge.  However, there are a number of site-specific factors which  should be assessed
adequately  prior to determining whether a particular site can be used effectively for  land application.  These Include
soil type, flooding susceptibility,  slope, depth to seasonal groundwater table,  permeability of the most restrictive soil
layer, cropping patterns, vegetative cover, and organic matter content  Since many suitable sites will not be Ideal,
the planner must carefully consider such factors when choosing actual application sites and designing projects.

Once a suitable application site has been selected and the process objectives defined, proper sludge loading rates
are determined.  Thi» process often Involves characterizing the waste for a number of constituents. The following
constituents are generally of most concern  for municipal sludges:  pathogens,  phosphorous, nitrogen, cadmium,
copper, nickel, lead,  and zinc When sludge Is applied at rates to meet the nitrogen requirements of the crops being
grown, nitrogen losses in excess or those expected from commercial fertilizer use should not be expected.

Existing federal sludge application regulations are primarily based on cadmium content New regulations have been
proposed and are scheduled to be finalized in October, 1991. Until then, POTWs should follow the "Sewage Sludge
Interim Permitting  Strategy* for  permit writers.  This recommends that In the absence of promulgated technical
standards, the primary source should be the document "Evidence for Writing  Case-by-Case Permit Requirements for
Municipal Sewage Sludge* (December 1989).


Reliability - With proper site selection, design, and operation, land application systems are very reliable.


Environmental Impact - In 1983, over 200 hearth and environmental experts from the United States,  Canada and
Europe met in Denver, Colorado to assess the state-of-the-art for  sewage sludge use and disposal.  The published

-------
                               flu?!flct ""* ™«ulalion8 w»r8 adequately Protective at puttie health and the
            provided thai sewage sludge was used in accordance with those  provisions.  The conclusions were
that:

(1) Guidelines  have been developed to enable the environmentally safe use of  sewage sludge containing median
concentrations of metals and organics when the sludge  Is applied at agronomic rates based upon nruoaen or
phosphorus utilization by crops;                                                                   ^

(2) Concentrations of synthetic organics In sludges are generally tow,  but high concentrations may exist in some
sludges.  Most synthetic organics are decomposed in soil.  Current Federal regulations for PCBs in sludges are
adequate to protect human health;

(3) Groundwater monitoring for nitrate-nitrogen is not needed where sludge nitrogen additions do not exceed fertilizer
nitrogen recommendations for the crop grown;

(4) Utilization of sludge for reclamation of disturbed land at rates higher than those for agricultural land, when property
Implemented and managed,  improves the quality of soils,  groundwater or vegetation;

(5)  With proper management and safety allowances based on research data, land application is a safe, beneficial
and acceptable alternative for treatment of municipal wastewater and sludges;

(6)  In terms of current detection capacity, Federal sludge disposal criteria are adequate to protect human health from
pathogenic microorganisms.


References -

1. ASCE, Land Application of Wastewater Sludge:  A Report of the Task Committee on Land Application of Sludge,
Committee on Water Pollution Management, Environ. Engineer. Div., American Society of Civil Engineers, 1987.

2.  Brockway,  D.G., 'Forest Land Application of Municipal Sludge,' Biocycle, September 1988.

3.  Crttes,  R.W.. "Land Use  of Wastewater and Sludge,' Environmental Science and Technology. Vol. 18, No. 5.
1984.

4. Demirjian. Y.A., A.M. Joshi and T.R. Westman, 'Fate of Organic Compounds in Land Application of Contaminated
Municipal Sludge,' Journal of Water Pollution Control Federation, Vol. 59, No. 1, 1987.

5.  Jensen, R. "Sludge Management Activities in Texas; Biocycle,  March 1988.

6.  Mays, DA and P.M. Giordano, "Land Spreading In the Tennessee  Valley," Biocycle. September  1988.

7. Loehr, R.C., WJ. Jewed, J.D. Novak, W.W. Ciarkson, and G.S. Friedman, Land Application of Wastes, Vol. II. Van
Nostrand Reinhold Co. NY, NY, 1979.

8.  Page. A.L, T.Q. Logan and JA Ryan, ed., Land Application of Sludge.  Lewis Pub.. Inc. Chelsea, Ml. 1987.

9  Page A.L  TL Gleason  J E Smith, IX Iskandar, and LE. Sommers, ed., Proceedings of the 1983 Workshop
on Utilization of Municipal Wastewater and Sludge on Land. University of California. Rivers.de. CA. 1983.

10.  Reed, B. and M.  Matsumoto, -Land  Application of Wastewater Sludge.' Pollution Engineering, December 1988.

11. U.S. EPA. A Practical Technology: Land Application of Sludge - A Viable Alternative (a fotoout). September 1983.

M  U.S. EPA,  EPA Municipal Sludge Management Policy. Notice Federal Register. June 1Z Vol. 49, 24358. 1984.

13. U.S. EPA, EPA's Policy Promoting the Beneficial Use of Sewage  Sludge and the New Proposed Technical Sludge
Regulations. Office of Water.  Washington, D.C. June  1989.

-------
14.  U.S. EPA, Environmental Regulations and Technology:  Use and Disposal of Municipal Wastewater Sludge.
EPA/625/10-84-003.  Ondnnatl, OH., 1984.
       ^

15.  U.S. EPA, Guidance for Writing Case-by-Cas« Permit Requirements for Municipal Sewage Sludge, December
1989.

16.  U.S. EPA, Handbook, Estimating Sludge Management Costs, EPA/62S/6-85-010, Cincinnati, OH., 1985.

17.  U.S. EPA, Process Design Manual for Land Application of Municipal Sludge, EPA/625/11-83-016, Cincinnati, OH..
1983.

18.  U.S. EPA, Sewage Sludge Interim Permitting Strategy: Notice Federal Register  October 20, VoL 54, 43124.

19.  Walker, J!M., -Public Acceptance: Winning Strategies for Land Application,' Btocyde, May-June 1986.

-------
IN-VESSEL COMPOSTING                                                                   PACT SHEET
      x

Description - Composting is the biological decomposition of the organic constituents of wastes.  The process can
erther be aerobic or anaerobe. Those systems designed for composting municipal sewage sludge mSSoS^S
strive to be a thermophylic aerobic decomposition process in which microorganisms metabolize dewaiered organic
sludges to a relatively stable organic residue, CO,, r^O, and heal. Operating parameters are specified to assure that
the heat generated by the composting process has  been sufficient to reduce pathogen content in the compost
product to an acceptable level. The resultant humus-like compost material Is an excellent low-grade fertilizer and soil
conditioner.

Irvvessel composting is a mechanical configuration of this process, In which the sludge Is treated In a closed reactor
The sludge  is typically premtxed with an amendment (such as sawdust or wood chips)  and recycle.  Air is diffused
Into the  reactor through the compost material for temperature and moisture control,  and to provide oxygen for
biological metabolism. The air is typically exhausted  directly to an odor treatment system before discharge to the
atmosphere. The process is usually accomplished m two stages, whereby the major composting activity taxes place
in the first stage; the second stage is used for curing and may  be carried out In a second vessel and/or an exterior
pile.  As an enclosed process,  In-vessel composting is easier to fit for full off-gas collection/treatment. and Is generally
more automated than conventional open windrow or static pile compost systems.


Common Modifications  -  Reactor design  can  vary  In configuration, incorporating either vertical or horizontal
flow-through, circular or rectanguJar tanks, and static or dynamic operation. In agitated (dynamic) reactors the
sludge/amendment mixture is  mechanically mixed  fin-place, or  as It is moved through the reactor).  This maintains
uniform heat and air distribution. In non-agitated (static) reactors the mixture may be loaded at the top and withdrawn
from the  bottom (relying on gravity to force plug flow movement  down  through the  reactor), or forced through
horizontally with a hydraulic ram.  tt can even consist of a static  pile system contained within a building.  Air is
supplied  by  a  variety of different blowers and pumps, depending upon  the system, the air  path length and the
resistance to air flow.


Technology Status - There were 19 full scale In-vessel composting plants operating In the Unites States, as of 1988,
with 24 in the design, bid or construction stages.  This is a significant increase from the three that were In operation
in 1985.  Sludge loading  capacties range front 1 to 78 dry tons per day. Operating experience is limited at this point
and designs vary.   The process can be considered an emerging technology because  of the limited number of
installed plants. The  control requirements and the computerized nature  of the  aeration and temperature control
systems Introduce a significant degree of complexity to the process.


Applications -  In-vessel composting Is an  alternative to  conventional open-pile composting  operations.  The
advantages over non-enclosed composting methods include enhanced ability to collect process and curing air for
odor control Improved aesthetics, reduced impact of ambient weather conditions, reduced land requirements,  and
generally  tower manpower requirements.   Composting  is  particularly applicable In areas where there is a ready
market or user for the compost product.


Limitations - By tar the most cribc* consideration for sludge composting systems to the ability to control odor.
Critical steps for successful control Induce (a) an inventory of all sources of odor,  ^'^f^^™ <* ^
types and amounts  (b)  a determination of the typical  meteorological conditions throughout each  day and each
season (c) setting a level of odor detectable In the neighborhood that is acceptable to residents, and (d) based upon
mSeling anTme^urement, appropriate* determining the proper mixture of ^^^^SfSSS^S
and/or dispersion  For the majority of systems the air  from most all sources, including sludge transfer, mixing,
coZyingSg anS unloading. processing, curing and storage, will have to be  treated by scrubbing, combust-on
and/or dispersion.
Destroying and dispersing the odors is not routine. Chemical K™^^"^™™"?*^'^
level of monitorina for successful operation.   Thermal regenerative combustion may be a simple odor treatment
                                                                              ™
•                 i    scr       inhe future.  Good communjy
should start at the facility planning stage and continue on through arting. setting an acceptable odor standard, and

-------
ongoing operation. Careful Investigation and documentation of the source of odors (both from the sludge composting
facility and elsewhere m the neighborhood) Is critical,  it establishes the credibility of successful odor control for a
facility, an Important  element m the facility's relationship with local neighborhoods.

Composting systems often have major problems because they have not realized that specific market uses require
specific product characteristics. This goes well beyond simply meeting EPA temperature requirements for pathogen
control Some end uses can successfully accept compost products with widely differing properties and others can
not A mixture of end uses should be available because sludge and processing conditions often may cause the final
product characteristics to differ, and a small change In product characteristics can  preclude some end uses, and
hence eliminate a portion of the market

The off-gases from composting are high In humidity, organic compounds and ammonia which can cause a harsh
working environment Furthermore, these off-gases are very corrosive and, In fact, some of the organic constituents
can dissolve epoxy coatings.  Consequently,  great care is needed to pick the proper products for construction of
both the building and the various system components (e.g., blowers and duct work).  There have been considerable
problems with materials handling equipment Many of these problems are being overcome as experience is gained
with the design and  construction needs for conveyors, unloading devices, mixing devices, screening devices, etc.
If a proposed system will Include new types of components that have not previously been tested for the particular
application, careful pretesting of the proposed component Is strongly  recommended.


Typical Equipment/No,  of Mfrs. - In-vessel wen post systems/8;  conveyers/12; dewatering systems/22; materials
handling/15;  mixing/8; odor control system/3;  screens/6; tubing, aeration/2,


Performance • in a survey of 8  In-vessel composting systems In 1988, 3 were operating at reduced capacity because
of odor or mechanical problems, 2 were down for modifications to structure and/or odor control systems, and 3 were
processing all available sludge. The two major problem areas experienced by most or all of the plants surveyed were
odor control and materials handling. Alt systems can achieve pathogen  kills  and stable end products.

Sludge/amendment/recycle ratios were variable. Depending on the site, these ratios exhibited a range of  1: 0.5 to
1.6: 0.6 to 10, somewhat higher In the use of amendment and recycle than anticipated by the original design.  The
sludges were 16 to 30 percent  solids; the solids content in the initial compost mix ranged between 33 and 50 percent
solids.  The first stage solids output ranged from 33 to 65 percent


Design Criteria - The sludge to be composted should  have a solids content of 18 to 30 percent, with a volatile
solids content greater than 50 percent  The pH must be between 6 and 9, and the carbon to nitrogen ratio between
25  to 35:  1.  The sludge to amendment (with  recycle) ratios should yield  an infeed mixture in the range of 35 to 45
percent solids. This win generally require a sludge:  amendment:  recycle ratio in the range of 1:  0.5 to 2:1 to 3.
The ratio and percent solids wiH depend on the quality and type of amendment and recycle. The minimum hydraulic
residence time should be 12 to 20 days, with  a system sludge residence time greater than 60 days. There should
be  at  least 3 days  residence time at a temperature  greater than 55°C to  meet  current EPA •PFRP* pathogen
requirements.

Because of the complexity of  odors produced,  odor control systems employ a spectrum of removal mechanisms
(e.g., multiple wet chemica) scrubbers, Wofilters, bubbling through waste water, biologically  activated  suspensions,
and chemical oxidation). R Is necessary to model dispersion characteristics to screen sttes,  establish maximum
allowable  emissions, determine supplemented stack or ventilation needs, and develop flexible odor control plans.
Supervisors and operators should receive training in composting theory and operation. Very often, the training has
been inadequate and failures have  occurred,  sometimes resulting in  prolong periods of shut  down for expensive
repair.  Visits to successfully operated sites are also recommended.


Reliability  •  Composting and  In-vessel composting are still emerging technologies with respect to other sludge
disposal processes,  and problems need to be resolved before this technology sees widespread use.

-------
                            Management - Studies show that composting can detoxify oily sludges pesticides
                                                                                             '
and herbicides   »,  cflazJnon, parathton, DDT, carbaryl,  etc.)
                    *naefObto ***** * *""*•* <**"!»* to landfarmlng and incineration, composting Is safer
Environmental  Impact -  Heavy metal contamination of soil and groundwater following compost application is a
concern.  Cadmium and toad are most often mentioned as the driving force for regulating distribution and marketing
of sludge products;  however, copper,  nickel, zinc, and molybdenum may show the greatest potential for plant
accumulation and effects on man.  Restrictions on land application generally appry only to heavy metal content.  If
the compost is to  be used for root crop or leafy vegetable production, time/temperature requirements to achieve
further pathogen reduction (PFRP)  is  essential.


Costs - Installed costs (1988) for six operating plants ranged between $200,000 and $700,000 per dry ton/day design
capacity, with  an average of $535,000.  These costs include modifications and anticipated upgrades to  improve
operations. Operation and maintenance costs, based on a survey (1988) of eight operating plants, ranged  between
$71  - $319/dry ton,  with an average of $175/dry ton; The  major components were labor, $30 • $lOO/dry ton;
amendment, $20 to $130/dry ton; power, $15 - $75/dry ton;  and maintenance,  $25 - $80/dry ton.  Revenues from
compost sales may vary from $2 to $l9/ycP depending on local pricing policies and the quantities that are purchased.
If supply exceeds  demand, the  plants will  stockpile, give It away, pay to  have It hauled away, or sell It back to
system supplier.


References •

1.  Benedict, A. H., E. Epstein and  J. Alpert, 'Composting Municipal Sludge: A  Technology Evaluation,' U.S. EPA,
EPA/600/2-87/021. 1987.

2.  Biccycle, The Biocycle Guide to Composting Municipal Wastes, The J.  G. Press, Inc. Emmaus, PA., 1989.

3.  Biocycle, The Biccycle Guide to In-Vessel Composting, The J. G.  Press. Inc. Emmaus, PA., 1986.

4.  Donavan, J. F., •Setecting a Composting Method,'  Environmental Engineering   Proceedings, 1987 Specialty
Conference, American Society of Civil Engineers, Orlando, FL, 1987.

5. Goldstein, N.. W. A. Yanko, J. M. Walker and W. Jakubowskl. •Determining Pathogen Levels in Sludge Products,1
Biocycle,  May/June  1988.

6.  Gouin, F., •Compost Standards for the Horticultural Industry,' Biocycle,  August 1989.

7. Haug, a T., •Composting Design  Criteria, Part I: Feed Conditioning.' Biocycle, Vot 27. No. 7, 'Part II: Detention
Time; BtocycJe', VoL  27 No. 8. "Part III: Aeration,' Biocycle, April 1986.

8. Johnston. J.. J. F. Donovan and A. B. Plncince, 'Operating and Cost Data for In-Vessel Composting.'  Biocycle,
April 1989.

9.  Murray C  M . -Odor Control Strategies and Experiences at the Montgomery County Composting Facility; In
Proc. ofthe Nat. Conf. on Municipal Sewage Treatment Plant Sludge Management,  May 27-29., Sponsored by  the
Hazardous Materials  Control Research Institute, Silver Spring, MD., 1987.

10. U.S. EPA, -Composting of Municipal Wastewater Sludges; A Technology Evaluation. EPA/625/-MB/014. August
1985.

11.  U.S.  EPA,  -Summary Report:  In-Vessel Composting of Municipal Wastewater  Sludge;  EPA/625/5^9/016,
September 1989.

-------
12. Walker. J.. N. Goldstein and B. Chen, •Evaluating the In-Vwse) Composting Option. Pan I and II,' Btocyde. April
1986 and May/June 1986.
       «•

13. Walker, J. M., Translating Research Into Large-Scale Production Facilities.'  Btocycle. May/June 1987.


14. Wlllson, G. B. and D. Oalmat, •Measuring Compost Stability,' Blocyde, August 1986.

-------
CARVER-GREENFIELD SLUDGE DRYING
     *•

Description - The Carver-Greenfield (C-G) Process Is a patented system for drying various types of
ntiuftng munepil wasiewater sludge.  A carrier or fluidlzing oiltemixed w«h wetl
rton* 0.1  te pumped through a multiple* evapcXtion  and/or  mechan.cS


The  evaporated water (up to 99 percent recovery)  to condensed and discharged, and any entrained carrier oil is
Sf8^!^8!^  "**    "I! ** feed fluldlzing tanfc ^ dried 
-------
The City of Los Angela* (first generation) light oil C-Q plant has experienced start-up problems.  Almost two years
were spent Improving mechanical equipment reliability after Its mechanical completion In late 1986.  During this
period the're were numerous problems wtth various parts of the system.  Substandard equipment was upgraded or
replaced, provisions were made for coping wtth equipment and piping abrasion problems, and operating methods
were modified. Some of the earlier problems with the Hyperion C-Q system and solutions are discussed In reference
4.

The transition to design, start-up and operation of the C-Q chemical process technology has been difficult for both
the designers and the municipalities.  A major Investment of time and money has been required for learning the best
approach and appropriate specialists to use.  Start-up of new chemical process technologies such  as light oil C-
Q technology requires very specialized skills and significant funding (amounting to 10 to 20 % of the capital budget).

A team of refinery/petrochemical start-up operations specialists was assembled during the later part of  1988. They
updated the  O&M manuals and established comprehensive procedures for sampling and monitoring  the system.
Their experience,  comprehensive  approach and  around-the-clock supervision  paved the way for  a number of
additional improvements that resulted in the attainment of continuous operation of two of the  three C-Q treatment
trains at Hyperion at approximately 40% of design capacity with on-stream reliability as high as 87% during a several
month period.

There  stilt  have been  significant  periods of shut down  for further modifications and improvements,  e.g.,  the
replacement of undersized motors in slurry pumps, providing more vacuum (as called for In the original design) and
control of fugitive odor emissions. Start-up a. id taalnment of a greater percentage of design capacity was hampered
during 1989 by lack of a given skilled start-up team being consistently assigned to the task.  The requirements for
starting-up and operating these facilities are clearly discussed In reference 1.


Design Criteria - Parameters affecting design  Include  sludge composition (solids, water, and Indigenous sludge oil
levels), application of final product, and energy prices.  Multiple-effect evaporator systems are  usually favored over
MVR designs when solids concentrations are greater than 15 percent and/or when steam to cheaper than electricity.
An oil to solids ratio of 6 to 1 Is typically used for municipal sludge. The evaporator pressures are between 2 and
14.7 psia generally with 3 to 5 effects.


Reliability - C-G Process plants typically have availability factors of 85 to 90 percent  However, this reliability has not
yet been demonstrated for the appfcation to sludge drying wth Sght  oil technology because K  is an emerging
technology and a very fcnfted number of these facflWes are available for  evaluation. Start-up problems have been
and are expected to be greater than for established treatments.  The designer  believes that redundancy Is essential
for key equipment within a process train, but does not consider redundant trains necessary.


Environmental Impact - 01 soluble orgartcs should be removed from the sludge during the sludge drying process,
and non-volatile metals should remain wtth solid particles. Volatile metals (toad  and particularly mercury)  may require
air pollution control devices If the dried sludge Is Incinerated.  Dried sludge from the City of Los Angeles plant was
classified as hazardous waste by the California WET procedure due to cadmium; however,  cadmium levels were not
found to be hazardous by the Federal  EP Tcodctty hazardous waste test

Since the process  Is fully enclosed and under vacuum, odor problems should be minimal, especially now that further
efforts have been made for collecting and combusting odors, including odorous vent gases.   Pathogens,  bacteria,
and viruses present in  the sludge  are destroyed due to a one hour detention time  at 300 to 350°F in  the de-oiler.
The oil-soluble toxic and hazardous compounds In the sludge are extracted by the carrier oB and  Incinerated or
disposed of In other safe ways.


Chemicals Required - The oil makeup design  requirements are:  20 Ibs/ton dry solids at $0.20/lb for light oil (narrow
fraction wtth a boiling point of 204°C); and 160 Ibs/ton dry solids at $0.08/lb for heavy oil (light gas oil, net cost after
fuel credit).

-------
Residuals Generated - The feed sludge Is separated into solids, water and sludge oil  The gaseous emissions ire
collected and incinerated.  In the heavy oil version, the sludge oil remains with the solids and is fed to an incinerator
for energy recovery.  Evaporated water te condensed and returned to the wastewater treatment plant

Potential For Improved Toxics Management - The process aids in incineration of toxic materials present In municipal
sludge. By  removing the water, high flame temperatures can be achieved in the incinerator, and destruction of toxic
and hazardous compounds and the formation of non-teachable ash are enhanced. In fertilizer applications, sludge
oil and oil-soluble compounds (e.g., toxic and hazardous pesticides, insecticides, etc.) are removed from the sludge,
and  pathogens are destroyed.   Thus far the fluidized  bed  incinerators at Hyperion, with their efficient  scrubbing
systems,  have  effectively  controlled  emissions during the combustion of the dry  sludge powder from the Carver-
Greenfield process.


Energy Notes - Current energy requirements range from  200 to 363 BTU/?b water evaporated.  The manufacturer
suggests that a value no  greater than 500 BTU/lb be used for preliminary estimating purposes.


Flow Diagram -
                                    Carrier Oil
  Moist
  Feed -|
  Solids
            Flufdizing
              Tj
Evaporaton
  and Ho*
Exchanger*
                                                 Dried
                                                 Solids
                                                 in Oil
                                                                     Flash
                                                                     Still
Centrifuge
                                                                     J
                                                                            Sewage OU (Fuel)
                  Sewage Oil and
                  Carrier Oil
                                                                               1
                                                                                   Solid* and
                                                                                   Carrier Oil
                                                                             Deoiler
                                                                        (Hydroextractor;
                                                     Water to POTW
                                                                                I 96% Sc
                                                                                I Fertili
                                                                                     i Solid* (Fuel or
                                                                                 Fertilizer)
        -^  ..... ^i- iMe
      . The fol.ow,ng table lists
The Figures represent C-G      an
the feed is municipal sludge conim
                                                  oil plants in operation or construction, with associated costs
                                                            t^ufacturer.  These estimated costs assume
                                                       mS-1989 construction at a clear and level site;  process
                                                            peering fees are included; crude oil priced «
                                                                       - 10 to

-------
                      (Dry Ton.
                        240
 («*••«

 UWMT County
Oeotn  County

Autofty.
                         80
 Burtngkin Murtr
 Ct«1v»l«rt«
           ESTIMATED INSTALLED CX)ST
           OF CARVER-GREENFIELD PROCESS
                     (MID-1989)
            50  100 150 200  250 3OO 350
            SLUDGE CAPACITY (DRY TONS/DAY)
References -
                                                                 ESTIMATED O & M COST
                                                               FDR CARVER-GREENFIELD PROCESS
                                                                        (MID-19G9)
                                                                 v/o CREDITS
                                                                 w/FUEL CREOITS
                                                               50  100  150 200  250  300 350
                                                               SLUDGE CAPACITY (DRY TONS/DAY)
1.  Gonzates, M., F.Y.W. Uao, K.A. Pluenneke, G. Rowe, and  M.J. Sieke, -Startup and Operation of   Chemical
Process Technologies in ine Municipal Sector - The Carver-Greenfield Process for Sludge Drying,' U.S. EPA, Office
Of Water, EPA/430V09-8S-007, August 1989.

Z Hoteombe, T.C., Personal Communication, Dehydro-Tech Corporation, East Hanover, NJ. 07936, 1989.

3. Walker, J., Carver-Greenfield Sludge Drying Systems, Status Report, July 27, U.S. EPA Office of Municipal Pollution
Control, Washington. D.C., 1988.

4.  Walker, J.  and J. Zirschky, Summary of the 1987  Carver-Greenfield Sludge Drying Technology Workshop:
Problems and Solutions,  U.S. EPA Office of Municipal  Pollution Control.  Washington, D.C.,  EPA/430/09-87-010,
September 1987.

-------
COMPOSTING SLUDGE, STATIC PILE
                                                8hxj°6 * "*™ *** "B"* materials *e <**«•* to • stab)e
   ,n ^u«01T^f   s   °blC Or8anism8-  * the static pile process, wastewater sludge is converted to
 compost in a four-step process in approximately eight weeks.

 Preparation . Sludge is mixed with a bulking material such as wood chips to provide the necessary structure and
 porosity for aeration and to tower the moisture content of the compost mix to about 60 percent.  Following mixing,
 the aerated pile is constructed by placing the compost mix over a network of porous pipe that has been covered
 with wood chips to insure good distribution of air. The pile Is then covered with screened or unscreened compost
 for odor control and insulation. The goal is to  achieve  uniform aeration, sufficient moisture removal, temperature
 control, and partial odor screening. The exact layout of aeration, wood chips,  pile heights and Insulation to achieve
 these goals may vary.

 Stabilization - The aerated pile undergoes decomposition  by thermophilic organisms, whose activity generates
 sufficient  energy to heat the aerated pile.   Although higher temperatures can be achieved, optimum microbial
 decomposition occurs between  45 to 60°C (113 to 140°F).  Aerobic composting conditions and  temperature
 regulation are maintained by drawing air through the pile at a predetermined rate.  The effluent air stream must be
 appropriately scrubbed and dispersed to achieve good control of odor [2].  After about 21 days the decomposition
 rate and  pile temperature  declines.  The p>'.3 fc then taken  down and the compost is either screened or cured
 depending upon the intended use of the finished product and te moisture content  Compost pile temperature must
 be maintained at 55°C for a minimum  of three  days  to assure disinfection.   Periodic stability testing, germination
 testing  and pathogen monitoring may be desirable.

 Screening - Unscreened compost should have  a moisture content of between 40 to 45  percent to facilitate clean
 separation of the compost from the bulking material and prevent dusting.  The unscreened compost can be dried
 prior to screening by aeration of the stabilized compost in storage piles of about 8 feet height following the 21 day
 composting period, by  restacking, or by spreading the stabilized compost out  with a front- end loader to a depth of
 12 inches and turning It. Screening can be performed with a rotary screen or a vibrating-bed screen.  The bulking
 material is usually recycled.

 Curing  • Either before or after screening, the compost Is stored in piles for about 30 days to complete stabilization
 and to assure no offensive odors remain. The piles should be aerated while curing to prevent anaerobic odors. The
 compost is then ready for utilization as a low grade fertilizer, a soil amendment, or for land  reclamation.


 Common Modifications • 1.  Individual pile - This method is as previously described.  2. Extended pile - Each day's
 pile is constructed against the shoulder  of the previous day's pile, forming a continuous  or extended pile, and
 resulting in  a savings of space and materials. Individual or extended piles can be constructed under a roof with or
 without side drops, or inside a wide span building.  Although the static pile  process generates sufficient heat to be
 left uncovered, a roof and/or partial enclosure will improve process control  and reliability if the facility  is located in
 a cold  or wet cflmate.  Enclosures will also Improve the ability to control odor  by collection, scrubbing and/or
 dispersion  Air from tt» building must  be collected and treated If upflow aeration Is used. If downflow aeration is
 used, the building air can be handled by dilution and dispersion, but the process air must  be collected and treated.


 Technoloqy Status -  A December 1988 survey  identified 61  operational aerated static pile facilities with 10 under
 construction and 13 in  planning and design m the United Stales.  State of the art static pile  facilities as of October
 1988 include the Montgomery County Composting Facility (Site II), Washington Suburban Sanitary Comm.ss.on, Sirver
 Sprina  MD  and sludge composting facilities at Sussex County Municipal Utilities Authorrty,  Hardyston Township. NJ.
 and Hampton Roads . VA.  ThTuse  of temperature feedback to automatically control aeration  to maintain the desired
 pile temperature is becoming more widespread.  Promising research is ongoing in the areas of odor control and co-
 composting with leaves, yard waste, and  municipal and  industrial solid waste streams.


Applications - The static pile method Is less sensitive to climatic conditions and allows for better odor and temperature
control than windrow composting.

-------
 Limitations - 1) Odor generation and release to the main environmental problem at composting Installations.  Site
 cleanliness, development of an area odor Inventory, thorough knowledge of the site meteorology and a strong public
 relations background provide the basis for effective odor control  Close attention and high operator skill level are
 required to properly operate odor scrubbers and related chemical handling facilities.  2} Planning to ensure effective
 final product marketing and distribution must be accomplished  3) The design must  consider variations In sludge
. and wood chip quality, and should employ a conservative estimate of sludge percent solids.  If the dewatered sludge
 ts 3 to 5 percent wetter than anticipated,  up to 80 percent more wood chips may be required, which will significantly
 increase the required composting and storage areas.


 Typical  Equipment • Commonly used equipment, which to readily available, Includes:  front-end loaders; perforated
 plastic pipe; blowers; rotary or vibrating-bed screens; odor scrubbers; prefabricated buildings.


 Performance • Well-operated static pile facilities routinely produce compost which to free of salmonella and with a total
 solids content of 51 to 69 percent  and bulk densities of 900 to 1,500 pounds per cubic yard.


 Chemicals Required • Odor scrubbers may require sodium hydroxide, sodium hypochkxite, and sulfurtc add.


 Residuals Generated • Final product to compost  Leachate from piles must be collected and treated.


 Potential For improved Toxics Management -  Heavy metals entering the process remain In the final product  but
 may be diluted with the addition of bulking materials.  The degree of removal of organic toxic substances  is  not
 known,  but Indications are that many organics will degrade.


 Design  Criteria - Wood  chip  mix requirement for  a sludge with 18 percent solids to 3.5 to 5.0 cubic yards wood
 chips/wet ton  of sludge; compost  mix  moisture content to about 60 percent; compost pile height to 8 to 10 feet;
 aeration rate to 2,000 to 4,000 cubic feet per hour  per dry ton of sludge; unscreened   compost generation to 4.0 to
 5.0 cubic yards per wet ton sludge; screened compost generation to 0.5 to  1.0 cubic yards/wet ton sludge.  For
 determining land requirements typical detention times are: composting • 24 days; curing * 30 days; bulking agent
 storage » 60-90 days.  The facilities should be manned  eight to ten hours per day, five to six days per week.  O&M
 costs/dry ton average $154, and typically range from $125 to  $175.


 Reliability  • Process reliability  to  good  once pile  construction techniques, aeration piping  configurations and
 appropriate aeration flow rates and sequencing have been established.  Operator training, moisture  control,
 homogenous  initial mix and  adequate aeration have been found  to  be  the most important  factors for effective
 composting.  The use of a single experienced person to oversee mixing operations appears to ensure consistent
 and proper Initial mot moisture content and  mix homogeneity.  Capability to control and record  pile  temperature 24
 hours per day In order to meet temperature/time requirements to  necessary to  ensure  proper pathogen control.
 Emergency power In the form of Independent dual feeds or a standby generator set  to desirable to provide aeration
 continuity  In the event of primary power source failure.


 Environmental  Impact - The four major concerns of adjacent  communities are odor generation, notes, sightliness,
 and traffic patterns.  These concerns must be carefully  addressed.

-------
 FlowDiagram
    SLUDGE
            MIXING
CONSTRUCT
  PILES
   BULKNG
    AGENT
     L.	•
 Schematic • Individual Aerated Pile -
                      AIR
      COVER-SCREENED
      OR  UNSCREENED
      COMPOST

        MIX-SLUDGE  AND
        BULKING AGENT
              PERFORATED PIPE

 Schematic • Extended Aerated Pile -
 FORCED
AERATION
                                             CURING
                DRAIN FOR-
                CONDENSATES
                                                       SCREENING
CURING/
STORAGE
 USES/
MARKET
                                           ODOR FILTER-PILE OF
                                           SCREENED COMPOST
                                EXHAUST FAN
                            AIR
    COVER-SCREENtD
    OR UNSCREENED
    COMPOST
          MIX-BULKING ACE NT
          AND SLUDOC

          BULKING AGCNT BASE

                  PERFORATED PIPC
                    NON-PERFORATED PIPE
                                          LOW POINT FOR
                                          CONDENSATE
                                          DRAINAGE
                                                                   •^
                               ODOR FILTER-PILE OF
                               SCREENED COMPOST
                                           OPTIONAL
                                           CENTRAL
                                           ODOR
                                           SCRUBBING
                                           FACILITIES
Section • Extended Aerated Plte -

     FINISHED COMPOST  REMOVED MERE-
                           MIXTURE TO BE COMPOSTED ADDED HERE

-------
References -
V  Goldstein, Nora, •Composting Facilities In me United States, 1987 Survey,' BloCvcle. Vol 29, No. 10, pp. 27-32,
November-December, 1988.
2.  Water Pollution Control Federation, tPA's Beneficial Use of Sludge Awards,' Operations Forum, Vol. 5, No. 10,
pp. 31-35. October 1988.
3.  U.S. EPA, 'Composting Municipal Sludge:  A Technology Evaluation,' EPA/600/2-87-021, 1987.
4.  U.S. EPA, •Composting of Municipal Wastewater Sludges,' EPA/625/445/014, August 1985.
5.  U.S. EPA, •Process Design Manual For Sludge Treatment and Disposal,' EPA/625/1-79-001, September 1979.

-------
               T                             WhiCh * ""^ avallable'Include8:  «™post.ni (windrow turning),
front-end loaders, rotary or vlbrat.ng-bed screens, blowers, perforated plasiic pipe, prefabricated wide-span roof*.'

Performance - Windrow composting routinely produces compost free of salmonella and with a total solids content
of up to 60 percent
Chemicals Required - None
Residuals Generated - Final product Is compost  Leachate from the windrow area must be collected and treated.


Potential For Improved Toxics Management - Heavy metals entering the process remain In the final product  The
degree of removal of organic toxic substances is  not known, but Indicators are that many organtes will degrade.


Design Criteria - Bulking Agent requirement for a sludge with 18 percent solids « 5.0 to 7.0 cubic yards cured
compost or 3.5 to 5.0 cubic yards wood chips per wet ton of sludge; compost mix moisture content = about 60
percent; windrow dimensions * 4 to 8 feet high and 12 to 15 feet wide at base; unscreened compost generation
= 5.5 to 7.0 cubic yards per wet ton  sludge (cured compost as bulking agent) or 4.0 to 5.0 cubic yards per wet
ton sludge (wood chips as bulking agent).  Arec requirements  can be calculated based on a mass balance of the
planned  operation.  Detention times for calculating area requirements are:  composting * SO days; curing  « 21
days; bulking agent  storage  (I required) « 60  to 90 days.  O&M costs/dry ton typically vary from $80 to $156.


Reliability - Windrow composting has good reliability as established with a  number of operating facilities. Operating
reliability is enhanced by covering key operating areas such as the mixing area.  The use of all paved surfaces is
generally essential to reliability of both  the windrow and static pile methods. As with the static pile process, reliability
appears to be enhanced by using only one person to oversee initial mixing operations to obtain consistency In proper
moisture content and homogeneity of the  mix.
 Environmental  Impact -  Potential for aerosol distribution of pathogens dictates careful attention to downwind land
 use.  Odor generation, aesthetics, noise, and traffic are concerns of great Import to nearby communities that also
 must be carefully
 Flow Diagram -
          SLUDGE
                     MIXMC
                                                                                             uses/
                                                            I       \

-------
COMPOSTING SLUDGE. WINDROW                                                          FACT SHEET

       x

Description - Composting Is the process by which sludge or other solid organic materials are convened to a stable
disinfected form by thermophilic aerobic .organisms.  In the windrow process the windrows  are turned periodically
to provide oxygen to the microorganisms responsible for the degradation of the sludge organics and to remove the
heat and moisture released by the process. Windrow composting is the predecessor to static pile composting and
Involves the  same basic sequential steps of  compost mix preparation, biological stabilization of the sludge, and
screening. Windrow composting differs from the static pile method in the way that the compost mix is aerated. The
compost mix Is aerated In the windrow process by natural draft and by mechanically turning the windrows.  In the
static pile process, aeration Is provided by mechanical ventilation of the compost mix

Preparation - A waste must have a porous structure and a moisture content of 40 to 60 percent to be compostable.
Sludge to be composted Is mixed with a bulking agent such as wood chips, sawdust, or compost to provide the
necessary structure and  porosity and to adjust the moisture content of the mix to the  proper range. The compost
mix is then placed In an  extended windrow, typically 4 to 8 feet high and 15 feet wide.  Windrows can be hundreds
of feet long depending on available space.

Stabilization • The stabflteatlon (active composting) period Is characterized by heating of the windrow as the compost
mix undergoes decompostion by thermophilic organisms. Although higher temperatures can  be achieved, optimum
activity occurs between 45 to 60°C (113 to 140°F). Therefore to control the temperature of the compost mix  and to
provide additional oxygen to the organisms, ti'.e «. ndrows are turned and remixed by front-end  loader or a composter.
The stabilization  period  requires approximately six weeks.   During the early part of the stabilization period the
decomposition rate and,  as a result, the heat production and oxygen demand are high, while  in the latter part of the
stabilization period the decomposition rate decreases. Therefore, the windrows are turned more frequently  during
the early part of the  decomposition  period.

Curing - A curing, period of approximately two weeks is provided at the end of  the active  composting period to
allow the process to come to completion, provide additional moisture removal and allow temperature stabilization.

Screening • If a bulking agent such  as wood chips is used, a screening step is required to remove  and recycle the
bulking agent prior to use of the finished compost. If cured compost or sawdust is used as the  bulking  agent, no
screening is  needed prior to use.


Common Modifications  - A  common variation of the  windrow  method  Is to supplement  aeration provided by
mechanically turning with induced aeration. This is usually done by placing the windrows over aeration pipes located
in grated trenches.  The air is then drawn through the piles by mechanical blowers In a similar manner to that used
with the static pile method. The windrows can also be constructed under cover, such as a wide-span metal buildings
without side  walls, to increase reliability In cold or wet climates.


Technology Statut - A December 1988 survey of compost sites Identified 34 operational windrow facilities In the
United States. Rve of these sites are aerated windrow type operations.  Six more windrow composting facilities (of
which  3 are  aerated windrow operations)  were in the planning and design stage and there were  7 windrow pilot
projects.


Applications - The windrow composting method Is most suitable for less populated and remote sites with warm dry
climates and where minimization of  capital Investment is a criteria.


Limitations •  Windrow composting is land Intensive.  Dust generated from mixing, windrow turning, and from the
windrow surfaces can be a problem.  Los Angeles County Sanitary District indicates that the best way to  control
odors and minimize  complaints at  Its traditional windrow composting facility is  to limit the size  of the compost
operation during the  summer to 500 wet tons per day.

-------
Windrow Turning
 References •
 1. Goldstein, Nora. "Composting FacMies in the United States, 1987 Survey." Bipc^ Vo. 29, No. 10, pp. 27-32,
 November-December, 1988.
 2. Water PoUullan Control Federation, -EPA's Beneficial Use of Sludge Awards; Operations Forum, Vol. 5. No. 10,
 pp. 31-35. October 1988.
 3. U.S. EPA, -Composting MunicipaJ Sludge:  A Technology Evaluation." EPWWVMWai, 1987.
 4  U S EPA, -Composting of Municip* Wastewater Sludges; EPA/625/4^5/014. August 1985.
 5  u S EPA  "Process Design Manual For Sludge Treatment and Dfcpos*; EW/B2SM-7M01, September 1979.

-------
ON-SITE SYSTEMS

-------
SAND FILTER
                                                                                             FACT SHEET


            -  Stow sand filtration of wastewater  is not a  new technology.  These filter*  were often  used by
                                                         «•"-» *S and land cosS fciLS, «^12
                                                         i» particularly applicable to treating septic tankimuent
2TJ^2l   nT^8  W CfU8t8fS * resWflnc«-  ** wastewater from  small commerial and  Institutional
developments^ It has been  used extensively for this purpose over the last twenty years.  With some modifications,
as explained below, sand filtration can produce a high quality effluent with a minimum of operation and majrttenance
requirements.  Sand filters generally require increased land area over conventional mechanical treatment processes.


Common Modifications - Three variations of the stow sand filters are used extensively for biological  wastewaier
treatment  They are burled sand filters, open (single pass) Intermittent sand filters, and recirculating sand fitters.
Site specific conditions and design intent dictates the type of sand filter utilized.

Buried sand filters are constructed below grade and covered with backfill material.  A 4- to  5-ft deep  excavation.
lined with an impermeable membrane is prepared for the filter.  Underdrains, surrounded by graded gravel or cashed
rock, are located at the bottom of the Hned pit The upstream ends of the underdralns are vented to grade.  A thin
layer of fine gravel is placed over the underdrain gravel to prevent erosion of filter sand Into the underdralns.  After
placement  of the filter sand, another layer of washed graded gravel or crushed rock is placed  over the filter surface
with the wastewater distribution piping.  This pip. ig  is also vented to the surface. A layer of geotextile/filter fabric Is
installed on top of the gravel and the entire filter cavity Is backfilled. Buried sand filters are commonly used for small
flows such as individual homes and small commercial  establishments.  These filters are designed to perform tor
periods of  time up to 2 years without the need for  maintenance.

Open (single-pass) Intermittent sand filters are similar to buried sand filters except that the surface of the filter is
accessible. High hydraulic and organic loadings are generally used.  In cold climates, removable insulated covers
may be used.  In addition to perforated distribution piping, wastewater may be applied periodically by surface flooding
(with splash plates in tne canter and/or at the comers) or through spray distribution in warm climates.   Intermittent
sand filters are beds of medium to coarse sands, usually 24 to 36 inches deep underlain with gravel and collection
drains.  Septic tank, Imhoff tanks or secondary effluent is intermittently applied In a generally uniform manner to the
surface and percolates through the sand to the bottom of the fitter. The underdrains collect the filtrate and convey
It to additional treatment (disinfection) processes and/or discharge.

Recirculating sand filters are open filters that  utilize coarser sand and  employ filtrate reclrcuiatton.  Wastewater is
intermittently dosed from a recirculatton  tank, which  receives both settled waste (e.g. septic tank effluent) and filtrate.
A recirculation rate of 3:1 to 5:1 Is typical. A  portion  of the filtrate is diverted for further  treatment (disinfection) or
disposal during each dose or when the recirculation tank is full, depending on the design approach".


Technology Status  - Sand filters have  demonstrated  a capability of producing a high  quality secondary effluent
Several process modifications have been Investigated at a pilot scale as a means of enhancing  removal  efficiency
of soluble  organtea, phosphorus and coliforms.  However, the  application of these modifications awaits further
demonstration  Enhanced nitrogen removal has been  demonstrated utilizing  a modified recirculating sand filter.
Treatment of septte tank effluent by anaerobic  upftow filters prior to sand filtration may allow significant reduction tn
sand filter size wtth no reduction m performance.

Stow sand  filtration is w«tJ-adapied to smafl tows wastewater treatment  Intermittent sand filters compare favorably
m economics and performance with extended aeration package piants and tegoon systems. The use of sand flHratton
systems* puticuteV well  suited for small communities that do not  have the skilled personnel or  me financial
         !»>w3tth« operation staff required for more highly  mechanized conventional treatment facilities.


                        and recirculating sand  filters provide a proven method of advanced secondary wastewater
                               SS  ***  » ^ communities, small clusters of homes. IndMduaJ residences
                              Sand I  filter systems are  moderately inexpensM MO build and have  tow  energy
              Additionally, operation of sand  filter systems does not requ,re hghly stated personnel.

-------
Typtoal Equipment/Number of Mfrs. • Piping, washed graded gravel/crushed stone, geotextite/filter fabric and sand
media are all  kxafy supplied.
       *

Limitations - Land availability may Hmlt the application of Intermittent sand filters.  Odors from open intermittent filters
receiving undiluted septic tank effluent may require a buffer zone between the  system and adjacent dwellings.
Covered, Insulated filters may be required in areas wth extended periods of subfreezlng weather.  Excessive long-term
rainfall  and run-off are detrimental to  uncovered. Internment and redrculating  filter  performance.  Appropriate
measuree should be taken to divert runoff from the filter.  Because intermittent sand filtration to larger/ a biological
process, wastewater should be evaluated to confirm process capability.  Use of Intermittent sand filters may be limited
In areas where suitable sand to unavailable, unless a suitable substitute media to available.


Performance'  - Under normal  operating  conditions, Intermittent sand fitters will produce high quality effluents,
consistently better than that produced by mechanical package plants, and superior to that achieved with conventional
facultative lagoons.  Concentrations  of BOOS  and TSS of approximately  10 mg/L  or  less are typically achieved
through intermittent sand  filtration as  compared to 30 and 30 mg/L for extended aeration units.  Nitrification of 80
percent or  more of the applied ammonia to typically achieved.  Removal of phosphorous to initially possible, but
quickly exhausted, and reduction in fecal conform bacteria to generally between two and three logarithms.

Clogging of the surface of open or redrculating filters eventually occurs as the pore space between the media grains
begins to fill with Inert and biological material,  hitter clogging requires media regeneration. The removal of this top
layer of sand  and replacement with dean sand to typically performed to accomplish thto.  Chemical oxidation  of the
dogging layer utilizing hydrogen peroxide may be attractive where media to costly.  Waste sand can be disposed
of at a landfill or recycled (stabilization  may be required).


Peston Criteria -

Design Factor                   Burled                   Open                    Redrculating

Pretreatment                                      Minimum of Sedimentation

Media
  - Effective Size                 0.35-1.0 mm             0.35-1.0 mm              0.35-1.5 mm
  - Uniformity Coeff.              <4                      <4                      <4
  •Depth                        24-36 In,                 24-36 la                 24-36 in.

Hydraulic Loading                <\2 gpd/ft2             2-5 gpd/ft2               3-5 gpd/ft2
                                                                                   (forward flow only)

Organic Loading                                  <5 x 103 tos BODj/day/n2

Redrcuiatkxi  Ratio*               N/A                      N/A                     3:1 to 5:1

Dosing Frequency               >2/day                  >2/day                  5-10 mirt/30 minutes

                                                                                         9
Process ReHabiary - Sand filtration to a highly stable, reliable biological treatment process  amenable to variations in
organic and hydraulic  loading  with Uttie effect on effluent quality.   Sand filter effluent to extremely low in turbidity,
which facilitates all methods of disinfection V required. Simplicity of process operation reduces risk of process upset
due to mechanical/electrical failure of more conventional systems.


Environmental Impact - Intermittent sand filters require increased land requirements presenting  possible site utilization
restrictions.  A buffer area to nearby dwellings  may be required for open intermittent filters due to potential odor.

-------
Flow Diagram -
                        TYPICAL RECIRCULAT1NG INTERMITTENT! SAND PILTPB
                      RiwWi
                             ToDudurje



< 	







ROM V»Jve t
I
1
— ; 	 L
1
\



». d»_

Media

*ft^ :•*/£*:»**<
Free Access
SmdFUia





                                                       Recroiliuon
                                                         Tmk
                                OPEN (SINGLE-PASS) SAND FILTER


                                     INSULATED COVER
                 Effluent
                 Pump
                                                          Dianbunoo Pipe
                                                          \^WW*VUUI
                                                 	/
             Pe* Gravel
            DischMje—•
                                                                          24--36'
                                                                     	   21CT
                GndedGnvel
                 1M U> 1 W
         CoUecuon
OpenJ<
mPipe
                                   TYPICAL BUPIgP SAND FILTER
                                                                              24 • 36 In.
P«rtor*t*d or Op*
  tint Dl*trtbutor«
       Graded Gravtl 1/4~ to 1 MT
                                                                              >8ln.
                                                      P«rforvt*d or Optn
                                                     Joint Pip*. Tirpapcr
                                                       Ov»r Op«n Joints

-------
References •
1.  MKchell, 0, Using Upflow Anaerobic Fitters As Pretreatment For Sand Filtration of Septic Tank Effluent, University
of  Arkansas, 1985.
2.  Sandy, AT, WA Sack, and S.P. Dbc, •Enhanced Nitrogen Removal Using a Modified Redrculating Sand Filter
(RSF2)', Proceedings of Fifth National Symposium on Individual Community Sewage Systems, Chicago, Illinois, 1987.
ASAE Publication 1-88, America Society of Agricultural Engineers, Si Joseph, Michigan.
3.   State of Oregon Department of Environmental Quality, Final Report:  Oregon On-Slte  Experimental Systems
Program, December, 1982.
4.  U.S. EPA, Disposal Systems Design Manual, EPA/625/1 ^80-012,  October 1980.
S.  U.S. EPA, •Wastewater Stabilization Lagoon Intermittent Sand  Filter  Systems,' EPA/600/2-8-032, March 1980.
6.  U.S. EPA, Technology Assessment of Intermittent Sand Filters,' April 1985.

-------
TANK TmKK COLLECTION                                                               FACT SHEET
                                 " r9CetVM " """^ "*" a home <* «™™«*X establish*** and stores
                                 ,
M ! wwi It Is pumped out and hauled to a treatment plant by a tank truck.  The vaults are similar to septic tanks but
they have no outlet piping and must be water-tight The volume can be 1000 gallons  on the stta  Otherwise, the vault should be sized  equal to  the volume of the
 largest  pumping truck that can easily serve the location, (t would not be cost-effective to have  a vault larger than
 the capacity of the pumping truck.

 The alarm should be located  in a prominent place to attract the homeowner's attention.  The alarm level should be
 positioned to allow one or two clays' reserve volume after the alarm is activated. The designer should also specify
 water conservation devices.


 Reliability - The ay*em to highly reliable If the system operator pays  attention to the need for pumping.  The high
 water alarm may M, and then the homeowner will eventually notice sluggish discharge from house plumbing and
 surface discharge of raw sewage.  To Insure  performance, a  maintenance contract with a hauler or  utility is highly
 recommended.


Safety Considerations - The vault  presents confined space hazards; the atmosphere within may be deficient In oxygen
or mav  contain poisonous sewer gases.  No one should enter the vault unless it has been verified that the oxygen
concentration to it toast 19%.  Forced ventilation should be used  to bring fresh air into the vault before entry. No
one should enter the vault unless there Is a standby person outside.  The person enteringshould be harnessed to
a hoist in such a way that he can  be hauled out by the standby person even If he  becomes unconscious.


Environmental Impact - Tank truck collection will not have a large environmental impact unless a vault begins to teak
            lUucha case, ground water or surface water may be contaminated, creat,ng a potential hearth hazard

-------
 Energy Consumption - A significant amount of energy Is consumed by the pumping truck In travel

     x

 Costs • The following table presents typical vault coats. Including excavation, material, and Installation.
       Volume (gal)          Coat ($)           Alarm coat ($)      Total Cost ($)

                                                                         1220
                                                                         1370
                                                                        .1570
                                                                         1970
                                                                         2170
                                                                         4770
                                                                         6670

 A family of four using a 2000-gallon tank and requiring pumping twice monthly would incur a coat of $100 to $200
 per month. Nonresidentlal or commercial property owners can expect to pay about $2.50 to $5.00 per 100 gallons
 under a long-term maintenance contract with readily available service.


 Flow Diagram -
1,000
1,250
1.500
zooo
£500
4,000
5.000
850
1,000
1.200
1.600
1,800
4.400
6.300
370
370
370
370
370
370
370
A IK^^K* 1 I B^^K ^^^^PwW^p i aw^e*
AJtffTi j 1 Ipl -•
*> Pumpout ACCMS Port
\
ii "--^
_«. _«. «»




j Switc/i



1 -2 Days' R«s*rv« Vo*omt



*Vtaatta atann m a consocuous locanon
adapiwl iron fnanci 
-------
SEPTIC TANK ABSORPTION BED                                                           FACT


Description - A septic lank system to the traditional, me* wide* used method of on site treatment and disposal of
                   «
 6 the basic method of wastewater treatment and disposal, site permitting.  The treatment and disposal component
 include a septic tank and a subsurface absorption system.                                  ^^

 Wastewaier generated from the residence is collected and transported through the house drains to the buried septic
 tank. WKhin the septic tank, gravity causes the solids to sink to the tank bottom and the grease and scum to float
 The solids collected undergo some decay by anaerobic digestion.  Septic tank effluent  is then  conveyed to the
 absorption bed system. The effluent then percolates through the absorption system and into the natural soil

 Absorption  beds and trenches are the most commonly used option  of  soil absorption  systems.   Trenches are
 shallow, level excavations, usually 1 to 5 feet deep and 1 to 3 feet wide. The bottom is filled with 6 Inches or more
 of washed gravel or crushed rock over which is placed a slngie line of perforated distribution piping. Additional rock
 is then placed over and around the pipe. A semipermeabie barrier is then  placed at the top of the stone to prevent
 backfill from migrating into the stone trench.  Both the bottom and sJdewalte of the trenches serve as mfiltrative
 surfaces.  Absorption  beds differ from trenches in that they are wider than 3 feet,  may contain more than one
 distribution  pipe, and are recommended only In sandy, permeable soils.  The  bottom area of the  bed effectively
 constitutes the infiltrative surface.


 Common Modifications - Design of  subsurface  disposal beds and trenches varies  greatly  due to specific site
 conditions.  In sloping areas serial distribution may be used  by arranging the trenches so that each trench to utilized
 to Its capacity before effluent overflows Into the succeeding trench.  A dosing or pressurized distribution system may
 be used to ensure complete distribution of the effluent Alternating valves may also be utilized to alternate bed/trench
 use to allow drying out or resting of the system

 Fiber reinforced plastic (FRP), fiberglass or polyethylene septic tanks may be substituted for conventional precast
 concrete tanks which have replaced previously used steel and hand made brick tanks.

 In areas where coarse aggregates are not readily available gravefless trench  systems may be economically employed.
 This system replaces the coarse aggregate with a finer material such as a sand fill for development of the absorption
 bed.

 Where high groundwater  and permeable soils exist on a site, LPP (tow pressure piping)  systems may be utilized.
 The LPP system consists of shallow gravel trenches installed 9 to 12  inches below grade.  Wastewater effluent is
 then dosed into the trenches through  distribution piping. Use of these systems to dependent on natural soil and
 groundwater conditions.  Dose volumes must not exceed void space within the trench system.  Ends of laterals
 must be accessible for flushing.


 Technology Status - Septic tank absorption systems  are  the most widely used  methods of orvsite wastewater
 treatment and disposal.   Due to  Its common use and cost effectiveness, almost  one-fourth  of the United States
 population depends on such a system.


 Applications - Absorption  bedsArenches are used for Individual residences and establishments generating domestic
 wSewaterin rural ind suburban areas where site conditions are favorable for on-site wastewaier treatment and
 disposal Property designed and  constructed systems require minimal maintenance and can operaie In all chmates.


 UmHations - Soil absorption systems are limited by  natural sofl type  and p™rtb«* bedrock  **V***'*«
 davations  and site topography  Systems may be used In soils having  a percolation rate between 1 and 120 rmVin.
 Ho^T'eOmiSn ySS?V»  upper limit for bed/trenches. A 3 to 4 ft  depth should be ma.nta.ned between the
h«£^ bo^oT am I bedrock or  seasonal* ™gh groundwater.  Regulations pertaining  to sel back requ.rements
I™ ^^                          w*" wei£, surface waiers and property lines are common s«e limKations

-------
Property operating systems present no inconvenience or Impacts to the homeowner.  Systems wtth minor operating
problems may have occasional effluent ponding at grade causing wet/soggy areas wtthln the property, potential odors
and possible health hazards. Reducing water consumption m the residence should be practiced In all cases but In
particular tf minor operating problems are observed. Failed systems pose  serious health hazards.
Typical Equipment/No, of Mfrs.
gravel are supplied locally.
> Septic tanks, distribution piping and bed/trench aggregate and porous barriers over
Performance • Performance Is primarily a function of site evaluation, system design and construction techniques
employed. Pollutants are removed from the effluent by physical, chemical and biological processes in the soil zone
adjacent to the field.  However, chlorides and nitrates may readily penetrate coarser, aerated soils to groundwater.


Residuals Generated • As part of the treatment process,  sludge and scum materials are generated within the septic
tank. Removal of this material (septage) should occur once every 3 to 5 years.


Design Criteria • Typical state-code required design flows vary between 75 gal/person/day and 150 gal/bedroorrVday.
Trench/bed depth to typicaHy 1 to 3 ft  Trench width  to 1 to 3 ft and bed width to greater than 3 ft.  Infiltration rates
of natural soil up to 60 mln/ln to usually the uppur limit  Bed/trench bottom application rates are 0.2 to \2 gpd/ft2.
Perforated distribution lateral design to 1 lateral/trench and multiple laterals/bed.  Minimum depth from trench/bed
bottom to bedrock/seasonally high groundwater to 2 to 3 ft Length of distribution lateral to typically <100 ft. Spacing
between trench sWewalte to 1.5 to 6.0 ft  Depth over trench/bed bottom to 0.5 to 2.0  ft.  Greater cover may be
placed over systems In cold climates. Trench/bed rock amounts are .75 to 2.5 inch washed gravel or crushed rock.

Sotis wtth percolation  rates  less than  1 min/ln can be used V the son to amended with a layer of sandy loam or sand.
Systems with rates near GO min/ln should receive great care during construction activities not to smear or compact
inflltrative surfaces.

Process Reliability -Septic tank/absorption systems that are properly sited, designed, constructed and maintained
have demonstrated an efficient and cost effective method of on-slte wastewater treatment and disposal.  Operating
without mechanical equipment,  absorption systems have service lives In excess of 20 years.

The use of water conserving plumbing fixtures (tow flow toilets and shower heads) to a recommended precaution.
Retrofit of water conserving plumbing fixtures has proven effective In correcting marginal system malfunction.


Environmental Impact  • Improperly designed, sited, and constructed systems  can contaminate groundwaters with
pollutants.  High density development utilizing absorption systems in well aerated soils can Increase nitrate levels of
surrounding groundwaters.  Falling systems can result in effluent ponding creating odors, aesthetic, and public health
hazards.
Flow Diagram

-------
References -

1.  Anderson, J.L, R.E. Machmeir, and M.P. Gaffran, •Performance of Gravelless Seepage Trenches m Minnesota.
Summef Meeting, American Society of Agricultural Engineers. June 1983.

2.  Frltton, D.O., W.E. Sharpe, A.R. Jarrett, CA Cote, and G.W. Peterson, 'Restoration of Failing On-Lot Sewage
Disposal  Systems; U.S. EPA MERL,  1984.  Summarized in: Sharpe, Cole, Frltton, 'Restoration of Falling On-Slte
Wastewater Disposal  Systems Using Water Conservation, Journal of the Water Pollution Control Federation, vol. 56,
NO. 7. pp 858^66.

3. U.S. EPA, 'Onsrte Wastewater Treatment and Disposal Systems Design Manual1, EPA/625/1-80-012, October 1980.

-------
SEPTIC TANK MOUND SYSTEM                                                            FACT
                       lI("l!Sind SyStem te * method * 0fV8*e w wwnunlly domestic wastewater treatment and
                       to me conventional septic tank-absorption system. a mound system is a pressure dosed.
absorptton system thai  is elevated above the  natural soil surface  In a sand fill.  Ths general design configuration
overcomes certain site restrictions such as stowty permeable soils, shallow permeable soils over porous bedrock and
permeable soils with water tables somewhat higher than otherwise allowable by local codes  Ths system consists
of a septic tank, dosing chamber and the elevated mound.

The design of the septic tank-mound system  is based on expected daily wastewater volume and the  natural soil
characteristics.  Wastewater generated by the source(s) Is collected and transported through pipes to the burled
septic tank. Within the  septic tank, gravity causes solids to sink to the bottom white grease and scum float to the
top.  The solids collected undergo some degree of decay by anaerobic digestion. Septic tank effluent is then
conveyed to a dosing chamber.  Within the dosing chamber, effluent is stored to a volume equivalent to a design
dose.  At the dose time, effluent is pumped or siphoned to the elevated absorption area and distributed through a
distribution network located in the coarse aggregate at the top of the mound.  The effluent then passes through the
aggregate and Infiltrates the sand flit.  The sand and the biological mat which develops  treats the wastewater and
permits the spread of the filtrate over a large area of native soil cafled the basal area. The basal area required for
infiltration beneath the sand mound is determined and controlled  by the  hydraulic capacity of the underlying soil.
For small  community systems, determination of the lateral hydraulic conductivity  and estimate of groundwater
mounding beneath the  bed is normafty requ»ed.


Common Modifications • Dependent upon site characteristics, the  absorption area within the mound system for an
individual home can ether be a bed or a series of trenches. The  shape  of the mound,  however, depends on the
permeability of the natural soil and the slope of the site.  A rectangular mound with the long axis parallel to the slope
contour is always preferred for individual home systems and generally required for all  community-sized mounds.
Natural soils having a percolation rate stower than 60 min/ln require the absorptton mound to be narrow and extend
along  the contour as far as possible.  The mound serving an individual home can be made more square In soils
having a percolation rate faster than 60 min/ln and f the water table to greater than 3 feet below the  natural ground
surface.

In areas with colder climates the distribution piping and manifold should be sloped to drain  back to the dosing tank
between doses to prevent  pipe freezing.  Either the check valve is  removed from the  pump discharge line,  or a 1/4
inch deep hole is drilled into the discharge line to aitow backftow,

A synthetic geotextlle/fitter fabric is preferred  over straw or untreated building paper  between the top of the  stone
bed/trench and the cover material to prevent clogging of the stone.

Operations monitoring and maintenance is facilitated by providing access  risers with covers  over the tank and  pump
chamber.  Operating  conditions such as absorption bed ponding  can  be reviewed  utilizing inspection wells.


Technology Status - Septic tank-mound systems have proven to be a successful on-slte wastewater treatment and
disposal system tor areas with slowly permeable soils and bedrock/high groundwater tables.   Mound systems
designed  and constructed as described have been in use for twenty years.  The first mound systems were  installed
over 30 years ago.

During construction of mound systems, special attention should be paid to assure that the basal area of the system
is property scarified, and that compaction of the basal area and downgradient water movement sues pnor to the sand
fill installation is minimized.


            - A septic tank-mound system provides a proven on-sfte and small community wasiewater treatment and
                        wild ** conventional septic  tank-absorption systems.   Site restncttons overcome by
                         slowV permeable soils, porous bedrock  and high groundwater condftor* Pnmanry used
                     areas, prop^V designed and constructed systems require m.nimum maintenance  and can
operate in all climates.

-------
Limitations - Elevated mound systems  require more space than conventional systems because of sand  nil
requirements.  Slope  Imitations of the site are more restrictive than for conventional systems.   Systems may not
operate property on sotts with  a percolation rate over 120 min/»a Systems with pumps require  an electrical power
source and Increased maintenance. The addition of the dosing system and sand fill raise the total construction costs
above those of conventional absorption systems. For small community systems, capacities are generally limited to
no more than 35,000  gallons per day.


Typical Equipment/No, of Mfrs.  - Pump chamber, tank, septic tanks, piping, pumping equipment, and system controls
are suppled locally.


Performance •  Performance of the mound system to a function of the site evaluation, design, construction and
maintenance procedures used for the system.  BOO, TSS, bacteria, and viruses are effectively removed by the soil
under proper conditions. However, nitrates are not removed and are transmitted to the groundwater.


Residuals Generated - As part of the treatment process, sludge and scum materials are generated In the septic tank.
Removal of the septic tank contents (septage) should occur once every 3 to 5 years for Individual homes and more
frequently for larger systems.


Design  Criteria • Typical design flow requirements for Individual  homes vary between 75  gal/person/day and 150
gal/bedroom/day.  Mound height at center to 3.5 to 5.0 ft Side slopes  should be  no steeper than 3:1. Percolation
rates of natural soils are up to  120 mln/lnch.  Absorption area application rate to 1  gpd/sq. ft Basal area application
rates are 0.1 to 1.2 gpd/sq. ft  Sand fU depth beneath the absorption bed to 1 ft min over slowly permeable sols, 2
ft mm. In shallow soil or high groundwater. Absorption bed/trench depth to 9 inches (min).

Absorption bed/trench stone to 0.75 to 2.5 inches washed gravel or crushed rock.  Crushed limestone to unsuitable
unless dotomitic.  Mound sand shall be a wed graded sand conforming to the criteria for the group SW in ASTM
Standard D 2487.  Sand conforming to group SP may be used after careful evaluation of the effective grain size,
particle size distribution and compacted  permeability. Distribution  laterals  are 1 to 3 inch diameter.  Distribution
perforation is 0.25 to 0.375 Inches diameter. Spacing between holes to 2 to 10 ft  Dosing frequency to 1 to 4 times
per day dependent on soH characteristics.


Process Reliability -  Properly  designed, constructed  and operated  orvstte septic  tank mound  systems have
demonstrated an efficient and economical alternative to public sewer systems In suburban  and rural areas.  System
We for property sited, designed, installed and maintained orvstte and community mound systems may equal or exceed
20 years.

In a case study of over 3,500 mounds constructed In Wisconsin, ninety-seven (97) percent of an mounds, and virtually
all mounds constructed according to modem design criteria were found to be operating satisfactorily.


Environmental Imoacj • Due to me elevated mound's size, shape and height, aesthetic issues may arise regarding
the visual impact of the system'on small flat  sites.  Impact may be reduced or eliminated If during design of the
system efforts are made to Incorporate the mound  into the existing landscape.   Drainage patterns, and land use
flexibility may also  be  impacted due to the mound location.  Improperly sited, designed or constructed systems can
contaminate surrounding land surfaces waters when effluents are not effectively absorbed by the  soil system. These
failing systems result in  effluent ponding creating odors, aesthetic problems and public health hazards.

-------
Flow Diagram -
                                            Pressure Distribution Network
                      Top Soil Cover
                  Filter
                  Fabric
                                                                         Observation Port
                                                                    From Septic Tank
                                                                    and Pump Chamber
References -

1.   Converse,  J.C. and E.J. Tyter, Wisconsin Mound  Performance,' Small Scale Waste Management Project,
University of Wisconsin, 1986.

2.   Converse, J.C.  and E.J. Tyler,  "On-Ste Wastewater Treatment Using  Wisconsin Mounds on Difficult Sites,' in
Proceedings of the Fourth National Symposium on individual and Small Community Sewage Systems, American
Society of Agricultural Engineers, 1985.

3.   U.S. Department of Housing and Urban Development, 'A Reference Handbook on  Small Scale Wastewater
Technology,' April 1985.

4.  U.S. EPA, 'Onslte Wastewater Treatment and Disposal Systems Design Manual,' EPA/625/1-80-012, October 1980.

-------
COMMUNITY SOfl. ABSORPTION SYSTEM                                                  FACT
                         treatment/disposal  
-------
Destan Crttaria . Alhough community toll absorption systems may have to conform to local regulations for single
dwelling systems, tnto should not be • problem since the design criteria will generally be more conservative for a
community soil absorption system than for a single home system.  In addition to conformance to local regulations,
design of a community sod absorption system should Include an analysis of the extent of groundwater mounding
below a sou absorption system and the Impact of nitrate addition to the groundwater.  Groundwater mounding can
be estimated In a variety  of ways, but the design of the soil absorption system should Insure that the groundwater
does not  mound to within 2 to 4 feet of the infiltrattve  surface.   Community  soil absorption  systems should be
designed to permit resting cycles, (Le., an additional son absorption system with an area equivalent in size to the soil
absorption system should be provided). Trench bottom application rates range from 0.2 to 1.2 gpd/Tt8 depending
upon son  conditions.   Design  flows  are  normally  based  on local  and/or  state  regulations, but  actual flow
measurements should be used tf possible to determine either excessive Inflow/Infiltration or  the degree of water
conservation  practiced.  Dosed systems should drain or  be constructed below the frost line.  Drained pipe volume
should be  less than 10% of  the dose volume.  The pressure maintained  at the end of the lateral farthest  from the
manifold connection should  be 1 to 2 psi.
Reliability • With proper site evaluation, a property designed, constructed, and operated soil absorption system Is very
reliable.
Environmental Impact - Possible nitrate and chkxlde addition to groundwater.
Flow Diagram •
                               TYPICAL TRENCH SYSTEM
                                                               Backfill
                                      Perforated
                                      Distribution
                                      Pipe
                                                                     Barrier
                                                                    Material
                                                                           in. Rock
 Wattr Table or
Creviced Bedrock

-------
References •

1.  Fieldfng, M.B.; •Groundwater Mounding Under Leaching Beds,1 Proceedings of the 3rd National Symposium on
Individual and Small Community Sewage Treatment, American Society of Agricultural Engineers ASAE Publication
No. 1-82, December 1981.

i   Hampton,  Mark J.,  Pto  S.  Lombardo, and D. Bruce Wile, •Determination  of a  Site's Hydraulic Capacity;
Proceedings of the 5th National Symposium on Individual and Small Community Sewage Systems, American Society
at Agricultural Engineers, ASAE Publication 10-87, December 1987.

3.  Helm, R., J. Quinn,  and W.  Zyzniewski,  Planning Guide for Wastewater Duster Systems in Illinois, Illinois
Department of Energy and Natural Resources, 1984.

4. Nettles. D.L, and RC. Ward, 'Design Methodology for a Large Scale Soil Absorption Bed for Septic Tank Effluent,'
Proceedings of the 4th National Symposium on Individual and Small Community Sewage Systems, American Society
of Agricultural Engineers, ASAE Publication No.  07-85, December 1984.

5.  Siegrist,  Robert L, et al., 'Large Soil Absorption Systems for Wastewaters from Multiple-Home Developments,'
EPA/600/2-86/023, February 1986.

6. Tyler, E. Jerry, et al.. 'Design and Management of Subsurface Soil Absorption Systems,1 EPA/600/2-85/070, June
 1985.

-------
BIOLOGICAL SECONDARY TREATMENT

-------
Design Criteria -

Total Tank Volume:

Food/Mass (F/M):

Number of Tanks:

Number of Cycle/Day:

Tank 0«pth:

Aeration System:
Operation Policy:
 Decanter.
 Automatic Controllers:
Equivalent to 0.5 to 2 times the average daily flow.

0.05 to 0.4 per day depending on application.

Typically 2 or more.

2 to 6 cycles/day are typically recommended.

10 to 20 ft  15 fl  to typically recommended.

Sized to deliver necessary oxygen during the react stage only.  Oxygen requirements
should be  estimated as for conventional activated sludge.  Several aerator types have
been used successfully.  Jet motive aeration appears to be advantageous since I can
be  used to mix only or mix and aerate.  Oxidation ditch alternative employs rotors for
bor, functions.

The time required for the five stages (including Idle) of operation have not been definitively
established.  The react phase for existing SBR installations range from 0.5 to 1.5 hours.
Periods of  aeration and non-aerated mbung can be manipulated to achieve denttrtfication
or phosphorus removal.

Several commercial decanter mechanisms are available, but some have been engineered.
Decanter design should preclude the possibility of discharging floating solids. Decanter
problems have characterized  some of the earliest SBR systems.

Microprocessor controllers operate pumps, aerators,  and varves based  on timers and
float switches. Automatic controllers should be programmable.
 Environmental Impact - Sludge disposal, odor potential, and energy consumption.
 Flow Diagram -
                Bar Screen  C°mn]!nuWf    Grit Chamber
                                              Sludge Handling System
                                                                             Influent
                                                                                r;...v.;,.;f
                                                                                £* »".*•'«%••*.*
                                                                                                Aeration
                                                                                                Settle
                                                                                        EfHuenj_
                                                                          Discharge
                                                                                |	4-Waste
                                                                                1               *    Sludge

-------
SEQUENCING iATCH REACTORS                                                           FACT SHEET


Description . A sequencing batch reactor (SBR) It a form of activated sludge treatment process.  An SBR facility
typically consists of parallel reactor tanks, wtth aeration/mixing systems, decanters, and sludge withdrawal systems.
The SBR treatment process occurs In a five-stage cycle in a reactor tank. The five stages are FIN, React, Settle, Draw,
and Idle.  During the 'Fill* stage, wastewater fills the tank and mixes with the mixed liquor settled during the last
cycle.  The tank is typically mixed during the flu stage, and can be aerated as an option.  Organic and nitrogenous
oxidation occur primarily during the 'React* stage under aerated conditions. Aeration and mixing are stopped during
the •Settle* stage to allow solids to settle.  Effluent is decanted from the tank during the 'Draw stage followed by
withdrawal of solids from the bottom of the tank during the Idle* stage.  This stage accounts for the time in which
one reactor  has finished  Its cycle and the other reactor(s) has not finished filling.


Modifications - Two patented •semi batch* systems are available that operate as generally described above but
continually accept  influent flow.  Also,  another system to available that performs SBR functions in oxidation ditches
without the  use of external clariflers.  An  SBR can be designed for BOD removal, nitrification, denttrtfication, or
phosphorus removal. Phosphorus removal can be by biological means.


Technology Status - There are at least 30 municipal and 30 Industrial SBR facilities m operation or under construction.
For example,  Idaho Spring, Colorado; Pootesville, Maryland; and  KJmbertlng Qty, Missouri  treat some of  their
wastewater with SBRs. SBR technology has been fully  developed.  The  design  of SBR facilities,  however, varies
greatly.  SBR facilities appear to be somewhat tower in cost than activated sludge facilities, and exhibit much greater
flexibility m terms of performance capability.


Applications • SBR fadflttes are used for munkdpei and  industrial wastewater treatment SBR facilities are capable
of  high levels of carbon  oxidation, nitrification, denltriffeation, and  phosphorus  removal.  In addition to general
application to wastewater treatment, SBRs should be considered where space is limited.


Limitations • Limitations are similar to that of activated sludge with regard to sensitivity to toxic loads. They generally
require somewhat  less O&M and energy than conventional activated sludge systems.  Also, the process depends
on reliability of automatic controllers for valves, pumps,  aeration  systems, and decanter systems.


Typical Equipment/Number of Mfrs. - SBR (Control Packages) Systems/approx 4; Aerators/at least 36; Automatic
Valves and ContrcXs/approx 15; Decantors/Approx 4.


Performance • (not necessarily all at one set of operating conditions)

        BOO* Removal          -  85-96%
        TSS Removal           -  85-96%
        NH3-N OxWatton        -90-95%
        Total Nitrogen Removal  •  85 - 90%
        Total Phosphorus       •  < 1 mg/l effluent (biological removal)


Chemicals Required - Chemicals can be used If biological conditions for phosphorus removal are not suitable.


Residuals Generated • Essentially the same as any activated sludge system operated wtth similar solids retention time.


Process Reliability - The process appears to be at least as reliable as a conventional activated sludge process.  The
process also appears to  better control bulking sludge and exhibits greater flexibility with nutrient removal.

-------
References -
1.  Arora, Madam L, and Peggy B. Umphres, Technical Evaluatkxi of Sequencing Batch Reactors,' EPA/68-03-1821,
September 1984.
2.   Irvine, Robert  L, and Uoyd H. Ketchum, "Full-Scale Study of Sequencing Batch Reactors,' EPA/600/2-83-020,
March 1983.   *
3.   Irvine, Robert L, Technology Assessment  of Sequencing Batch Reactors,' EPA-600/2-85/007. February 1985
4.   Irvine,  Robert t_ and Uoyd H. Ketchum. "Sequencing  Batch Reactors for Biological Waste Treatment,' in
Environmental Reviews, V.18, No. 4, CflC Press Inc., Boca Raton, FL

-------
TRICKUNG FB.TBV8OUDS CONTACT                                                     FACT

      s

pescriptkyi-Th»trid(»ngTOef/»o)ktt contact (TF/SQ process
Typical components of the process include primary treatment, trickling filter, solids contact step  secondary dartfier
and a return sludge capability.  In the TF/SC process primary effluent is applied to trickling filters; trickling filter effluent
to mixed with return secondary clarifier sludge In a small aeration tank (hydraulic detention time < 1 hr)- and aeration
tank effluent Is flocculated, settled  and discharged.  Return activated sludge (HAS) may be aerated prior to mixing
with the TF effluent or the contact process can take place In the reaction zone of a ftocculator/cterifier.  The aerated
solids contact is a solids flocculatton/aggtomeration process  which captures the pin floe typical of trickling fitter
effluent  It reduces suspended solids and associated BOD. The solids retention time In the aerated solids contact
tank is less than 2 days. Longer detention and solids retention times generalry connote a TF/activated sludge process
(2-stage  biological system).


Common Modifications  - A TF/SC  can be  operated by 1) aerating  only  the TF effluent/RAS mixture  in  a
ftocculator/clartfier; 2} aerating RAS only; or 3) aerating both.


Technology Status - There are at least 11 operating plants and at least 30 facilities ft planning or design phases.
The operational data base reported In the literature, however, Is based on only seven facilities.


Applications • TF/SC process Is well suited to upgrading existing TF facilities to increase flow capacity or to meet
20/20 to 10/10 BODS and TSS (mg/I), respectively.


Limitations • The TF/SC  produces both primary and secondary sludges, requires a knowledgeable operator, and
consumes power  for pumps and  aerator*  The TF in a TF/SC system  to typically  larger than a TF for a TF/AS
system.  The TF/SC system requires an influent pump station  to dose the TF.


Typical  Equipment/No. Mfrs. - Clarifier equipment/38; Aeration equipment/30; Ftoculator/Ctarifiers/30; Rock media
supplied localry; Trickling filter equipment/16.


Performance - TF/SC process has been reported to achieve the following monthly average effluent quality treating
municipal wastewater when  the trickling filter Itself to not overloaded.

         BODS:   5 • 20 mg/I
         TSS:    5 - 20 mg/l


Reliability . The existing TF/SC facilities are reported to be operating consistently and reliably.  Insufficient data exist
to determine long turn reliability under a wide range of operating conditions.


Environmental Impact  - Odor problems. fDter  flies.  Increased sludge production over TFs and consumes  more
energy than TF but less  than activated sludge.


Residuals Generated • Primary and secondary sludge.

-------
Design Criteria - DennMv* design standards have not been established. However, the design parameters for seven
existing facilities are presented betow(l):
                                                  TotesooAZ    Oconto Fafls.Wl   CorvaWs.OR     Medford.OR
Design Flow (mgd)
        Average Dry Weather Flow
        Peak Wet Weather Flow
Design Loading (1,000 Ib/day)
        BOD
        SS
Primary Overflow  Rate (gpd/sq ft)
Trickling Filter
        Media Type
        BOD Loading (ttVday/1000 cu ft)
Return Sludge Aeration Time (33% return
        rate), Minutes
Aerated Solids Contact Time (total flow
        Including recycle), minutes
Ftocculator Center Welt
        Percent of Qartfier Area
        Detention Time (total flow
        Including recycle), minutes
Secondary Ctartfler
        Overflow Rate Based on Total
        Oartfler Area (gpd/sq ft)
Sldewater Depth (ft)
        8.3
       17.7

       24.0
       21.6
       970

Plastic/Rock
     55/9.1
          9

         13

         25
        440
         16
 0.38
 0.75

 0.67
 0.79
 370

Rock
  35
   8

  16

  38
 300
  15
  9.7
 28.0

 T0.9
 11.5
 980

Rock
  24

   9

   2

  12

  25
 470
  18
  18.0
  60.0

  35.0
  28.0
  1030

Plastic
  115
    5

    5
  480
    15
• Contact time at existing flow of 8.8 mgd plus 33% return rate is 39 minutes.
Flow Diagram -
  Primary
  Effluent
                  Trickling
                    Filter
              XIX
                Mixed
Aerated Solids  , Liquor.
 Contact Tank,
     Secondary
      Clarifier    Flocculator
                  Center Well
                                                                                             Treated
                                                                                             Effluent
             Waste Sludge
                                                                Return Sludge
  Mode 1

-------
                   Trickling
                    Filter
   Primary
   Effluent
              Waste Sludge
     Mod* 2
Mixed Liquor
                                         Return Sludge
                                         Aeration Tank
                          Secondary
                           Clanfier
                                                               Return Sludge
Flocculator
Center Well
                                                                                               Treated
                                                                                               Effluent
    Primary
    Effluent
    Mode 3
                   Trickling
                     Filter
               Wast&Sludge
               Mixed
Aerated Solids  u
-------
EXTENDED AERATION, MECHANICAL AND DIFFUSED AERATION
                                                                                           FACT
DESCRIPTION. The extended aeration (EA) process is a low rate modification of activated sludge treatment.  The
F/M toad.no, te in the range of 0.05 to ft 15 Ib. BOD, /d/lb MLVSS and the aerator detention time is typlc^yThourT
Primary clarification Is rarely used.  The tow loading rate minimizes waste activated sludge  (WAS) production by
allowing significant  endogenous decay of the sludge mass.  In addition the  WAS produced is already partially
stabilized because of the tong liquid and solids residence times utilized. High solids retention times (SRT) are used
{20 to 40 days) allowing significant nitrification, although nitrification Is temperature sensitive and falls off at waste
temperatures below 15" C. Extended aeration plant processes typically include coarse screening and/or comminution,
activated sludge  aeration including  air generation  facilities, clarification Including skimming  and sludge return
equipment,  and a disinfection  contact basin with associated disinfectant (usually chlorine) storage  and feeding
facilities. An aerated sludge hokSng tank is also normally provided which allows sludge  digestion and facilitates
sludge handling and disposal.

Aeration may be provided by either diffused Of  mechanical aerators.  Both plug  ftow and complete mixing  flow
patterns are utilized. Aeration tanks are typically rectangular, although both square and round tanks are in use.


Common Modifications  • Other aerobic suspended growth processes with tong solids residence times such as the
oxidation ditch and the sequencing batch reactor may be used.  Ftow equalization is often specified upstream of EA
plants receiving highly variable or periodic flows such as from schools  to avoid plant upset due to hydraulic surges.
Granular media filtration following the final clarifier Is commonly required by some states to maintain a consistentfy
high quality effluent. AJum or ferric chloride is sometimes added to the aeration tank for phosphorus  removal.
 Technology Status - Highly developed and widely used.
Typical Equipment/No, of Mfrs.
aeration equipment/over 10.
                               Package treatment plants/over 20; diffused aeration equipment/over 10; mechanical
 Applications - The process is extensively applied for treatment of smafl flows (toss than 75,000 gallons/d) such as
 those generated by housing subdivisions, small municipalities, isolated small businesses, institutions, and schools.
 Pro-engineered 'package' plants (steel or concrete modules) are typically utilized. The process is also used for the
 treatment of certain industrial wastes using a completely mixed flowsheet
 Limitations -Long detention times and tow loading rates result in relate* high power «^aptal COM p«r gallon
 of wasiewater treated as compared to the conventional activated sludge  process.  Some EA package plants
 experience occasional high effluent suspended solids toss due to poor solids inventory management, high ftow
 laS^Snal^esign or inadequate operator attention. As a result some states discourage the mstallaion of
 I^E?Sw pS«ap«Sv^ flowVtess than around 10,000 to 15,000 gallons per day.  Freeing problems
 may occur in cold climates especially where above ground tanks are utilized.
Performance
BOD5   Removal
NH4 - N Removal (at 20 to 40 day SRT
                                                                                35 . 95%
                                                                                60-99%
                                                               sirs
                                                               0.7 . -.0 ». «- « •»— — *
 B005 removed.

-------
Designed Criteria • A partial listing of design criteria for the EA modification of the activated sludge process is
summarized as follows:
        Volumetric loading, to BOCyd/1,000 ft»
        MISS, mg/1
        F/M, ID BODj/d/lb MLVSS
        Aeration detention time, hours
        (based on average daily flow)
        Standard ft3 air/lb BOD, applied
        to 0,/Uj BOD, applied

        Solids retention time, days
        Recycle ratio (R)
        Volatile fraction of MLSS
8 to 15
2.500 to 6,000
0.06 to 0.15
18 to 36

3,000 to 4,000
2.0 to 2.5 (Based on 1.5 to oyib B005 removed  + 4.6 Ib O,/
NH«-N removed)
20 to 40
0.75 to 1.5
0.6 to 0.7
Process Reliability • Reliability Is good tf sufficient operator attention is provided.  Particular attention must be given
to biological solids control and wasting. In addition adequate solids handling and storage capacity must be provided.


Environmental Impact - Sludge disposal; odor potential; and energy consumption.


Flow Diagram •
Screened and/or Complete Mix
Raw Wastewater
i ' Aerauon lanic


Clarifier
Return Sludge ,
Sludge
f


Excess ,.
Sludge J
Chlorination

Aerobic
Digestion
Effluent
*^
To Disposal

Energy Notes - Assumptions:  Based on power for blower, froth spray pump and comminutor.  Power cost + $
.07/kWh
Costs - Assumptions:

1.  Construction cost includes comminutor, aeration basin, darifier, chlorine contact chamber, aerobic digester,
chlorine feed facility, building, fencing for extended aeration package plants between 0.01 and 0.1 Mgal/d. Detention
time:  24 hours (based on average daily flow).

2. Operation and maintenance costs assume sludge Is hauled from the site 5 times per year and that compliance
testing is performed monthly.

-------
                                     OPERATION flND MfllWTtNRNCt COSTS
                                              •at tewater Flaw, M
                                                 il / IMWMI   i
                                                                              11
                                                                       CMU
                                         KIM CMI
                     Construction Cost
                 Ulattewater Flow, M gal/d
                                                 o.io
                                                          100000
                                                              *
                                                            z «
                                                           10000
                                                                             Electrical energy
                                                                 o.oi     Ufasteweter Flow, M gal/d
                                                                                                       O.:o
References -
1.  U.S. EPA Technology Transfer, -Wastewater Treatment Facilities for Sewered Small Communities'. EPA/625/1-
77-009, October 1977.
2. U.S. EPA, 'Package Treatment Plants - Operations Manual", EPA/430/0-77-005, April 1977.
3. Water Pollution Control Federation. 'Operation of Extended Aeration Package Plants,' MOP No. OM-7. 1985

-------
MISCELLANEOUS

-------
HYDROQRAPH CONTROLLED RELEASE LAGOONS
                                                                                            FACT SHEET
                                                  *floon is a lagoon used to temporally store treated effluent
                                           A HCR ta000n' •«**»- * " *""»"< S3   control device and
                                    " ' *** ^^ anajyste durin9 I"*™ to*"*3" P****'  Sl°ra9« lagoon
                     »         (aflef diSCharge) to M <** to Discharge). The sides ofsuxage lagoons should
             to resist erosion due to changing water levels.

The «mmflow monitoring systems typically measure stream stage which is then  related to stream (low.  Stream
25^S ^ •1^rid ** ultrasonic "^ "**«*• by level ftoat switches or bubbler tube In a stilling well, and by
relying on the U.S.G.S. to provide daily flow estimates from a nearby gauging station.

Discharge systems can be operated automatically or semi-automatically based on Input from the  stream monitoring
system   The discharge system typically consists of motor or pneumatically operated valves, motor driven sluice
gates, floating weirs, or variably sized pumps.


Technology Status - There are at least 20 systems in design, construction, or operation.  The existing HCR lagoons
are reponed to be working wed.


Applications - HCR lagoons are best suited  to areas In which land costs are tow and  stream  flow Is seasonally
variable.  The applicability of HCR lagoons must be  analyzed in terms  of seasonal stream assimilative capacity,
projected effluent  quality, and the cost of storage capacity. HCR  lagoons are typically used In conjunction with
lagoons,  but can sJso be used with other treatment processes.


Limitations • The use of HCR lagoon technology can be limited due to land limitations,  eofl  conditions adverse for
constructing basins; and stringent  year-round treatment requirements.  Variable flow discharge schemes are not
allowable in all states.


Typical Equipment/No, of Mrfs. - Ultrasonic level sensors (bubbler/float) - at least four. Automatic valves and controls -
approximately 15.


Performance - HCR lagoons are not designed to treat wastewater. although, some treatment probably does occur.


Design Criteria - In general, HCR lagoons are designed to maintain receiving stream  water quality by restricting
discharge during periods of tow flow.  The permissible quantity of effluent that can be discharged should be related
to stream flow b*Md en the assimialoiy capacity of the stream.  Required storage should be based on an analysis
of historical stream flow data and ttw discharge schedule stipulated by the State/local  regulatory agency.  Precipitation
data and  nearby stream flow data for a similar drainage basin may be used If historical data is not available for the
receiving  stream.

The discharge system should be designed to discharge at variable rates in order to minimize storage.

System Infiltration  should be investigated  and corrected If  necessary.


Reliability  - HCR lagoons have been very reliable in maintaining stream water quality.

-------
Environmental Impact? • Odor potential owing to variable lagoon levete. Animate may t*com« trapped In the lagoon
If the sides of the basins are lined with a plastic liner.
Flow Diagram •
                         Wastewater
                         Cell
Storage
Cell
                                                               Control
                                                               System
                                Lagoon System
                                      Flow
                                      Meter
                                                                            Data
                                                                           1 Transmission
f
                                                              Discharge     Flow
                                                              Structure      Meter
                                  Receiving
                                  Water
References -

1.  HM, Donald 0., and Victor L ZJtta, •Hydrograph Control Release, State of the Art,* Mississippi State University,
MSSU-GRS-CE-80-7, September 1980.

2.  Zlrschsky, John, and Rlcnard  E.  Thomas, "State of the Art Hydrograph Controlled Release (HCR) Lagoons,'
Journal of the Water Pollution Control Federation, Vol. 59,  No. 7, July 1987.
3. ZJtta, Victor L. and Donald O. HJU, •Hydrograph Control Release:  Methodologies for Predicting Storage Periods
on Ungaged Streams,* Mississippi State University, MSSU-EfRS-CE-63-1, September 1982

-------
SEPTAGE RECEIVING STATION                                                  "           FACT 8HE£T
             «.!???fle^*^nfl 8taUo" Pfovidee for the transfer, preliminary treatment, storage and equalization
                       ZZ I?."?!!!™? consist  °f • receiving area, screening and degritting equipment and a
                                       of a sloped ramp, washdown equipment and a coarse bar screen.  This
                                       (preferred) and open pit discharges. A channel placed in front of the bar
                                          holding tank allows for mixing, aeration and equalization.  Mixing and
«,*«„- ,« ^         maintain uniformity and keep the waste fresh.  Equalization allows for controlled addition of
septage to the waste stream, thus protecting downstream processes from slug loading effects.  Additional features
include sampling/monitoring equipment, solids handling pumps, and odor control


Common Modifications - Grtt removal can either precede or follow storage  and equalization.  If a grit chamber
precedes equalization, ft must be designed to handle the discharge of individual or multiple trucktoads of septage
as they arrive. If storage and equalization precede grit removal, the degrttdng process can be designed to handle
the average flow.  Cyclone degrttters may be substituted for aerated grft chambers V average solids concentration
Is less than 2 percent  Grtt classifiers are a common  addition to degrttlng  equipment

For colder climates, dumping pits should Include hot  steam equipment for thawing frozen valves, hose lines, etc.
Vibrating  screens have been  used  successfully in place of coarse bar screens. Vibrating screens offer smaller
openings that  collect more solids but they Increase capital cost, maintenance,  and energy requirements.  Where
land application  is Involved, longer term storage may be  required during adverse weather conditions. Lagoon
storage facilities should be considered In such cases.  If septage is discharged to an interceptor sewer where flows
are high, storage facilities may not be required.  Odor control can be accomplished with chlorine, hypochtortte, ozone,
activated  carbons, and soil gas niters.

Access to receiving  stations can be automated through the use of coded plastic cards. The cards are inserted into
a computer.  The computer can identify the  hauler, time, date of entry and quantity of septage.  Access can be
controlled at the dumping site or at a gate restricting vehicular traffic to the site.  Automation allows for 24-hour
access to facilities without sacrificing control  over discharges.


Technology Status - The use of septage receiving stations is widespread hi Europe, specifically Germany, Sweden
and Norway.  Relatively fewer operating examples exist in the United  States.  Manual monitoring programs are far
more common than the automated systems.  Receiving station automation is generally ymited to controlled gate
access,


Applications - Receiving stations can be placed at the headworks of  a conventional wastewater treatment plant a
septage treatment plant on a land treatment site, or at a sewage collection system manhole.


Typical Equipment - Bar screens or racks (mechanically cleaned are preferred) aeration equipment; holding tank(s);
solids  handling pump(s);  flow controls;  odor control equipment; piping, valves and hose connections.


Performance - Preliminary treatment of  septage can reduce suspended solids  signiftoanty.   However, designers
should not assume any other oc*utant reductions. Bar screens with 0.25 Inch opemngs can remove several cube
feet of solids per 1000 gallons of septage depending  on source characteristics.

Controlled addition of septage to downstream treatment facilities is recommended.  This allows slow  addition of
»S Wo^^mrtam^eby minimizing potential for biological and/or solids overloading  of downstream

treatment  facilities.


           Reasonaby reliable with property designed connections, tank sizes,  process equipment and 04M.

-------
Design Criteria -
Bar Screen
Hauler Truck Hoe* Connection
Piping and vaJves
Screen Channel
Holding Tank Capacity
< 0.25 In. spacing for mechanical screens
> 0.75 In. spacing for manually cleaned screens
4 In. diameter
8 m. diameter
6 to 10 feet m length, sloped for minimum velocity of 2 feet per second
Septage storage tank capacity  should be adequate for minimum two day peak
septage volume.
Environmental Impact • Land requirements are minimal.   Energy is required for pumping, mechanically cleaned bar
screens, aeration and mixing and odor control   Solids will be generated that require disposal.  Odors may be
associated with dumping, pretreatment (screening), and residuals disposal (land application).

r —
Raw |
Septa** t^
x*
fcxnaustAir
i_» Odor Control
fH System

__/ \_^±u^
\ 1 *— ^ i

i
i
• To
1 ^^^^^ Ti'fl iinir*nt
Processes
Dumping Receiving/ Handling Aerated Grit
Station Storage Pump(s) Chamber or
and Tank(s) Cyclone Degriuer
Bar Screen
References -
1. U.S. EPA, Handbook - Septage Treatment and Disposal, EPA 625/6-84-009.
2. U.S. EPA, Septage Management, EPA-600/8-80-032.
3. U.S. EPA, Pilot Scale Evaluations of Septage Treatment Alternatives, EPA-600/2-78-164.
4.   U.S. EPA  Design Manual: Odor and Corrosion Control In Sanitary Sewerage Systems and Treatment Plants,
EPA-625/1 -85-018.

-------
NON-WATER CAR^OE TOILETS                                                         FACT 8HE£T



             ?^                                                                   The maJn advantage
 must be disposed SSSSSL '"j'"*"11* (30-40%) and atrength of wastewater to be dlapoaed on-site.  Greywater
 are descrt£^     ^   *'   ^ Variad°ns * NWC toilflte "^ no**"*- *• ™ "^°° P«™anen7 types
                                   ** ,t0 **•* Wtch^ "* toitot ""a" 
-------
Performance - Biological toilets,  when well operated, can produce a soil conditioner, but Its handling should be
controlled due to biological hazards.  User acceptance is fair.  Incinerating toilets successfully convert waste to ash,
when operated properly.  User acceptance is fair.  Oil recirculatlng toilets work well but may clog during  overuse
without proper maintenance.  User acceptance Is also fair.


Design Criteria -  Biological toilets are typically sized for up to 2-4 people.  Variations exist which can be sized for
more people and/or also accept kitchen wastes. Incinerating toilets are typically designed for 2-4 people.  Incineration
cycles  can accommodate a maximum of approximately 4 uses.   Electrical units  require 120/24OV service and
consume 0.5 to  1  kw-hr per vtsft.  Oil recirculatlng toilets require that accumulated wastes must be pumped out
periodically or that the concentrated  wastes  be treated and disposed of. Provisions should  be made for flush oil
^circulation pumps and treatment/disinfection of flush oil
Reliability • Approved NWC toilets are reliable If operated correctly.
should be considered with caution.
                                                                 Many non-approved designs are available and
Environmental Impact • Water consumption can be reduced by one third and on-site direct discharge of toilet wastes
may be eliminated from the ground or surface waters.  Biological toilets conserve nutrients when product is used for
ornamental gardening (CAUTION:  Product from toilet should not be used for gardening for human consumption).
Odors and insects may be problems.
Incinerating toilets consume energy and, may cause odors.
wastes, usually In lanofits.
                                                          ON ^circulating toilets require ultimate disposal of oily
Chemicals Required - Biological toilets require bulking agents and insect controls. Incinerating toilets require paper
Vners and odor control chemicals.  Oil recirculating toilets require flushing oU, deodorizes, and disinfectants.
Residuals - Biological toilet:   partially stabilized soil conditioner  and excess liquid.
recirculatlng toilet: accumulated wastes and exhausted filter media.
                                                                                 Incinerating toilet:  ash.  Oil
Flow Diagram -
 Toilet Wastes .
Toilet Wastes
                   Tata
                              VOIIllUCt
Toilet Waste* ^
s
Oil
RflBICUlJtiOl
t
\
"^
P
OU
Sepuuon
Treatment


Waste* ^
P
Storage

To disposal ,.
>

-------
1-  ^~S Cl ** R L*00^- •Composting Prtvy Wastes at Recreation Sites; Compost Science/Land Utilization,
pp. 36-39, January-February 1979.

Z  Lombard© & Assodates, Inc., 'State-oMhe-Art Assessment of Compost ToHets and Greywater Treatment Systems,'
Prepared for the Winthrop Rockefeller Foundation, Uttie Rock, AR, February 1980.

3.  Otis, Richard J. and W.C. Boyle, "U.S. EPA Training Seminar for Wastewater Alternatives for Small Communities,
On-stte Alternatives,' August 14-18, 1978, August 28-September 1, 1978.

4.  Smith,  E.D., C.P.C. Poon,  S.R Struss, J.T. Bandy, and R.J. Schofee, 'Appropriate Technology for Treating
Wastewater at Remote Sites on Army Installations,'  U.S. Army Corps of Engineers, Technical Report N-160, April
1984.

5.  State of Nevada Department of Transportation,  Final Report: Experimental Project NV-81-1, Trinity  Rest Area:
Clh/us Multaim Organic Waste Treatment System and Restroom Building, 1984.

6. U.S. EPA Technology Transfer, 'Alternatives for Small Wastewater Treatment Systems, On-stte Dteposal/Septage
Treatment  and Disposal,' EPA/625/4-77-011, October 1977.

7.  Vendor literature, Research  Products/Blankenshlp (Incinerating toDets), Dallas, TX, 75220.

-------