RESEARCH TRIANGLE INSTITUTE
                                                           RTI
    STATE EXPERIENCE INTEGRATING POLLUTION
               PREVENTION INTO PERMITS
     EPA/4S6/R-98/W13
                         Prepared for:
                         US Environmental Protection Agency
                         Office of Air Quality Planning and Standards
                         Leo Stander, Work Manager

                         Prepared by:
                         Research Triangle Institute
                         Melissa Malkin
                         Jesse Baskir
                         Aarti Sharma
3040 Cornwallis Road • Post Office Box 12194 • Research Triangle Park, North Carolina 27709-2194

-------
Disclaimer

This report was prepared by Research Triangle Institute for EPA, Office of Air Quality
Planing and Standards. The report consists of a review of the efforts different states are
making to incorporate pollution prevention into their environmental permitting programs and
an evaluation of the effectiveness of these efforts. By sponsoring such a review, EPA is not
endorsing or discouraging use of these types of efforts. This document is not official EPA
guidance. This document provides insight into the innovative and creative efforts that states
are making to promote pollution prevention through environmental permits in all media. It is
hoped that providing this information will spur other states and EPA to adopt techniques that
seem effective and appropriate. It is also hoped that this information will provide a starting
point for discussion of pollution prevention in permitting, which has traditionally been based
on pollution control.

Information for this report was gathered from published documents and conversations with
parties involved. State agency personnel were given the opportunity to review a summary of
the information they provided, and any comments were incorporated into the text.

This review is not a comprehensive survey of all state efforts. This is primarily due to time
and budget constraints. Omission of particular state efforts certainly does not imply judgement
as to its usefulness.

-------
Executive Summary   	l

1      Introduction	4

2      Integration of P2 into Permitting: Different Approaches	8
             Permit Flexibility	8
                   Pre-Approved Changes	8
                   Emissions Caps	11
             P2 Planning Incorporated Into Permit 	12
             Evaluating a P2 Option for Permit Compliance	14
             P2 Conditions as Part of Permit ,	16
             Providing P2 Information in Permit Application Process	18
             Multi-Media Permits	19
             Permits Fees Structures  	20
             Accelerated Permit Review	21
             Extended Compliance Time	22
             Alternative or Reduced Monitoring as Reward for P2	 22
             Use of Inspectors to Promote P2  	24
             Incorporating P2 into the Underlying Rule	25

3      Conclusions	26

Appendix A	28

References	29

Resources  	30

-------
Executive Summary

In its implementation of the Clean Air Act Amendments of 1990 (CAAA), the EPA is seeking
ways to promote pollution prevention. The CAAA's Title V creates an Operating Permits
program that requires facilities to have all of their federal and state air requirements and
compliance schedules within one document, known as the operating permit. These permits do
not contain new requirements beyond those already mandated by state and federal law.
Permits are one of the primary vehicles by which environmental law and policy are applied to
industry.

To explore how pollution prevention (P2) can be integrated with the Title V program, EPA's
Office of Air Quality Planning and Standards (OAQPS), which is responsible for developing
regulations under the Act's Title V Operating Permits provisions, established two pilot
projects. These projects explored how pollution prevention and operational flexibility could be
integrated with permits issued to a pharmaceutical firm (Merck) and a semiconductor
manufacturer (Intel). In addition to EPA's efforts, many states are examining ways of
promoting pollution prevention and providing operational flexibility to facilities.

In support of these pilot projects and its other efforts to investigate  ways to integrate P2 with
the Title V program, EPA tasked Research Triangle Institute (RTI) to review existing national,
state and local  efforts to integrate P2 into permits and to assess the  effectiveness of these
efforts. However, the scope of this report does not address how OAQPS could promote the
promising efforts identified here and elsewhere.

RTI found that many states were testing out ideas for using their permitting
activities to promote P2, including efforts in all stages of the permit life, from pre-
issuance to inspection and enforcement.  For the most part, systematic qualitative
or quantitative evaluations of these efforts were not available. On the next page,
we summarize the major types of P2 integration efforts that were identified.

-------
  Summary of Efforts to Promote P2 in Permits

  Permit Flexibility
  This report gives examples of two ways to provide flexibility under a permit:
       1) allowing the facility to make changes as long as it remains within an
       emissions cap and;
       2) allowing the firm to make preapproved changes without applying for a
       permit modification.
  The permits reviewed in this category were all pilot studies or applied to special
  industry sectors. If the EPA and states can  adequately enforce these flexible
  permits then these permits could provide permitted facilities the ability to
  respond much more quickly to market conditions.

  Pollution Prevention Planning
  Mandatory P2 planning is in use in many states: incorporating it into permits may
  increase the scope of the facilities that are affected by P2 planning requirements.
  Planning is likely to be more effective if it is used in advance of obtaining a
  permit, rather than afterwards, when resources may have been expended on
  pollution control strategies. However, in the special case of firms who are
  receiving source-specific determinations of control during which it is found that
  control devices are too costly for that source, requiring the facility to create a P2
  plan as a permit condition could promote P2 in a situation which would otherwise
  remain uncontrolled.

  Mandatory P2 planning for good operating practices and maintenance, and even
  requiring certification that some good operating practices are being used, seems
  particularly promising. In part this approach is promising because good
  operating practices are relatively inexpensive and usually effective P2 measures.
  New Jersey's experience with the asphalt manufacturers industry provides a
  strong example of the potential success of this type of approach.

  Consideration of P2 for Compliance with Permit Limits
  Mandatory consideration of P2 for compliance may be effective to direct firms'
  attention to P2, but efforts to promote P2 for compliance must be coupled with
  efforts to remove regulatory barriers to using P2 for compliance. EPA and the
  states need to develop more experience finding enforceable ways to allow firms
  to use P2 measures to meet emissions limits and technology-based limits.
|| Attention to special projects like the Intel flexible permit project will provide	

-------
(further insight on the viability of P2-based approaches to compliance.

-------
Offering Extended Compliance Schedules to Facilitate Pollution Prevention
Use of extended compliance schedules for firms that want to use P2 for
compliance can be a valuable tool in situations where more time is needed to
facilitate implementation of a P2 option for compliance.

Reduced Permit Fees for Firms Using Pollution Prevention
Offering reduced fees or alternative monitoring to firms that reduce their emissions through P2
can be an effective incentive for firms to explore and implement P2. Like all incentives,
however, it will only work to the extent that firms and regulators are aware of it, understand
it, and thus are willing to use it.

Promoting Pollution Prevention through Permit Inspectors
Use of permit inspectors to promote P2 can be effective. Inspectors who are observing
potential violations and can point these out along with ways to use P2 to avoid such violations
are likely to be able to get the attention of a facility. Care must be taken to avoid potential
confusion about when inspectors are acting in their role as enforcement personnel and when
they are offering non-mandatory suggestions. In addition, P2 at the inspection stage should not
be emphasized at the expense of steps taken earlier in the facility's operation under a permit.

Incorporating P2 into Underlying Rules
Incorporation of P2 into underlying rules and elimination of P2 disincentives can be an
effective way for EPA to promote P2, not just at pilot facilities but at all facilities affected by
the rule. Including explicit permission to use P2 for compliance with a rule sends a strong
message, and removes disincentives for facilities and regulators to build P2 into their operating
permits.

-------
 1     Introduction

 In its implementation of the Clean Air Act Amendments of 1990 (CAAA), the EPA is seeking
 ways to promote pollution prevention. The CAAA's Title V creates an Operating Permits
 program that requires facilities to have all of their federal and state air requirements and
 compliance schedules within one document,  known as the operating permit. These permits do
 not contain new requirements beyond those already mandated by state and federal law.
 Permits are one of the primary vehicles by which environmental law and policies are applied
 to industry.

 To explore how pollution prevention (P2) can be integrated with the Title V program, EPA's
 Office of Air Quality Planning and Standards (OAQPS), which is responsible for developing
 regulations under the Act's Title V Operating Permits provisions, established two pilot
 projects. These projects explored how pollution prevention and operational flexibility could be
 integrated with permits issued to a pharmaceutical firm  (Merck) and a semiconductor
 manufacturer (Intel). In addition to EPA's efforts, many states are examining ways of
 promoting pollution prevention and providing operational flexibility to facilities.

 In support of these pilot projects and its other efforts to investigate ways to integrate P2 with
 the Title V program, EPA tasked Research Triangle Institute (RTI) to review existing national,
 state and local efforts to integrate P2 into permits and to assess the effectiveness of these
 efforts. Discussion of the approaches provides a conceptual framework for understanding
 where P2 can fit into environmental permits. This review  of available  techniques may help
 EPA and states to identify ideas to explore further. However, the scope of this report does not
 address how OAQPS could promote the promising efforts identified here and elsewhere.

 To conduct this study, RTI gathered information by contacting federal and state regulators and
 other individuals who had experience with P2 in permits. RTI attempted to identify the major
 tools being used to promote integration of P2 into permits for air and other media, but did not
 attempt to identify every initiative that addressed P2 in permits. References to further  sources
 of information about integration of P2 in permits are provided, and references to literature or
 published information about P2 in permits are contained within the text of this report, even
 where we were unable to speak to individuals to obtain an evaluation of the work.

 To a certain degree, activities to promote P2 through permits were a matter of attempting to
ensure that permits do not create a disincentive to P2. For example, a  facility that has a P2
 idea may find that it requires a permit modification to implement this change.  If the change
triggers New Source Review (NSR) under the Clean Air Act, the facility may be
 required to undergo significant review of its proposed change under complex
 NSR regulations. NSR may dictate that the facility  install best available control
technology (BACT) even where the P2  change that the facility proposes will

-------
 reduce actual emissions. This problem has been addressed to some extent in
 EPA guidance on NSR reform which applies an NSR exemption to pollution
 control or pollution prevention projects, but the exemption is not broad, and
 there are projects which fit the EPA definition of P2 that may not fall under the
 NSR guidance (USEPA, 1994).

 RTI found that many states were testing out ideas for using their permitting
 activities to promote P2, including efforts in all stages of the permit life, from pre-
 issuance to inspection and enforcement. For the most part, systematic qualitative
 or quantitative evaluations of these efforts were not available. The following
 approaches to integration were identified:

       •>     Providing flexibility to allow facilities to make P2-oriented changes
            without needing a permit modification
       >     Providing for facility  level P2 planning by incorporating the planning
            process into the permit application procedure
       -     Providing for facility  level P2 planning by requiring a facility to
            develop a P2 plan as a condition of the permit
       *     Including P2 conditions in permit
       »•     Providing information on ways to use P2 for compliance with permit
            limits
       >     Multimedia Permits as a way to promote P2
       »•     Modified permit fee structures to provide incentives for P2
       *     Providing accelerated permit review as an incentive for P2-related
            applications and modifications
       >     Providing extended compliance time for facilities who use P2 as
            compliance method
       »•     Allowing alternative monitoring as an incentive for P2
       >     Promoting P2 through permit inspections
       >     Incorporating P2 into the rules on which permit limits are based

This report describes research methods' and summarizes information gathered by RTI to
characterize and analyze current efforts by states to integrate P2 into their permitting activities.
In gathering information, RTI attempted to ascertain whether P2-integration hi permits efforts
had been followed by qualitative or quantitative evaluations of the effectiveness of the effort in
terms of quantity of pollutants reduced as a result of the P2 condition in the permit, or in
terms of whether removal of P2 disincentives had led to increased use of P2. This kind of
evaluation is almost universally absent  from these efforts. Thus, the information provided in
this report about the success of efforts to integrate P2 into permitting is anecdotal.

In addition to not having adequate evaluative efforts built into them, often P2-in-permits
efforts have been implemented as pilots or on a case-by-case basis, thus anecdotal assessments

-------
 are not based on a large sample of experiences,1
                       What is Pollution Prevention?

 Pollution  prevention  is defined as source reduction  and other practices that reduce or
 eliminate the creation of pollutants through increased efficiency in the use of raw materials,
 energy, water or other resources, or protection of natural resources by conservation. Source
 reduction includes any practice which reduces the amount of any hazardous substance or
 pollutant prior to recycling or treatment, including equipment or technology modifications,
 process modifications, reformulation or redesign of products, substitution of raw.materials
 and improvements in housekeeping, maintenance, training or inventory control.

 Pollution  prevention explicitly  does not include add-on  controls like thermal oxidizers,
 wastewater treatment processes  and scrubbers that have traditionally been the basis for
 compliance with operating permit limits  under  air and  water environmental protection
 programs.
       1 One state agency representative said that he wished more states and EPA Regions
would begin implementing their own pilot programs in addition to calling him to ask how his
pilot project is going.

-------
 Some Common Examples of P2

 P2 Through Modification of Process Equipment

 Use of alternative spray equipment for applying finishes to products can reduce the quantity
 of coatings materials needed for a given product. Two common alternative spraying methods
 are high volume, low pressure nozzles and air-assisted airless application equipment to
 replace conventional air atomized spray systems. Reducing materials use is one of the
 characteristics of effective P2 (since the more of the material that is used is incorporated into
 the finished product, less waste is produced). This also saves money for the manufacturer.

 P2 Through Good Operating Practices and Preventative Maintenance

 Good operating practices and preventive maintenance can prevent pollution in a number of
 ways. The State of New Jersey recommends that asphalt manufacturers employ P2
 techniques like conducting annual burner adjustments and examination of dryer flights.
 These promote clean burning and thus reduce emissions (New Jersey, 1994). Good operating
 practices for other industries might include frequent inspection of pipes for leaks (early
 repair of leaks can reduce chemical or water waste); improved inventory control to reduce
 the quantity of materials that go out of date; and placing covers on dumpsters and other
 sources of potential stormwater contamination.

 P2 Through Materials Substitution

 Substitution of less-hazardous or less-polluting materials for hazardous ones  is  a common P2
 technique. Many firms are switching away from chlorinated solvents like trichloroethylene
 in favor of alternatives like aqueous cleaning. Materials substitution is not a panacea,
 however. For instance, switching from solvents to aqueous cleaning can eliminate a
 hazardous air pollutant problem, but create additional burdens on wastewater treatment
 facilities or the local publicly owned treatment works.

 Pollution Prevention Through Planning

 A pollution prevention plan is an ongoing assessment of the firm's waste and pollution
 generation. This first step  in the P2 process involves investigating the wastes that are
 generated, identifying areas in which those wastes can be reduced, and the costs associated
with the wastes. Planning  for P2 is the first step in implementing P2. P2 plans may be simple
 and focus on reducing or eliminating one substance (like reducing solvent use or reducing
plating sludge generation) or they may be more detailed and look at all wastes from the
 facility. Facility P2 assessment guides like EPA's "Facility Pollution Prevention Guide" can
facilitate the P2 planning process (EPA 1992).

-------
2    Integration of P2 into Permitting: Different
      Approaches

Information about the specific efforts and their effectiveness is presented in the
foDlowing sections. The efforts undertaken by states have been grouped under 12
headings, each corresponding to a different way of approaching the P2
integration problem. A description of the type of approach is provided, followed
by examples of how the approach is applied in the different states identified by
this report. Table 1 summarizes the different efforts described, and shows how
well-established the effort is in the state.

2.1   Permit Flexibility

There is the perception in the regulated community that lack of, flexibility in operating permits
prevents them from implementing beneficial changes,  including some P2 changes (Inside EPA,
1995). A facility's permit often specifies in detail the equipment and/or chemicals that will be
used for a given process. Making a change in their process to implement P2, like switching to
a lower-VOC coating process could trigger the need to apply for a permit modification or even
to comply with New Source Review requirements.

Various EPA and state efforts have tried to incorporate flexibility into permits to overcome
this disincentive.  Some of these efforts have the objective of specifically removing a
disincentive to P2 or to innovation. In other cases, a permitting agency may be able to offer a
flexible permit in exchange for the facility undertaking P2 projects that they might not
otherwise have done. Here we examine examples of permit flexibility through 1) preapproval
of certain changes and 2) emissions caps that set an overall plantwide limit but provide latitude
in how these limits are met.

2.1.1        Pre-Approved Changes

One way to remove a disincentive for P2 is to preapprove certain changes so that
a facility is not required to go through the process of permit modification when it
chooses to make these changes. This may provide flexibility so that the facility
can react quickly to market conditions to make changes as needed. It may also
be a way for a permitting agency to encourage specific kinds of P2 changes.

Some flexibility is already available in the existing air permit process nationwide
in that facilities in their application can provide for alternative operating
scenarios. A permit that incorporates these alternatives allows the facility to
move between these scenarios as needed without applying for permit
modification. The State of Delaware, for instance, routinely solicits as many

-------
operating scenarios as possible because they want to avoid having to process
permit modifications (A. Farrell, Del. DNREC, personal communication). Often,
however, firms do not apply for different operating scenarios in their permits,
possibly because to do so can require substantial additional
                                    10

-------
TYPE OF P2
INTEGRATION EFFORT
USED

Flexibility
Planning in
Permit Application
Planning as a Permit
Condition
P2 Conditions in Permit
Providing P2
Information for
Compliance
Multimedia Permits
Modified Fees
Structures
Accelerated Review,
Extended Compliance
Alternative Monitoring
P2 Promotion Through
Inspectors
ORGANIZATION
CA







4


OE





4A




U.S.
Region 9









5
IL







2


IA




2





MA




2
3




MN



4


5



NC








2

NJ
1A

1A.3
1A

4A




NY





4A




OAQPS,
CTG








2,6

OR
4









TX
2









VW

1A








Wl


1A



1
3



-------
TYPE OF P2
INTEGRATION EFFORT
USED


P2 in Underlying Rule

ORGANIZATION


CA



DE



U.S.
Region 9


IL



IA

2.
1A
MA



MN



NC

2

NJ



NY



OAQPS.
CTG


OR



TX



wv



Wl



12

-------
Table 1
The x-axis shows the state involved in the effort.
The y-axis shows the type of P2-integration effort being used.
The code in the matrix shows how well-established the effort is.
   Code
   1)  Consistently applied to all permits issued by relevant agency
   1A) Consistently applied to all permits in some subset of facilities
   2)  Available to all permit applicants/holders if they request it or meet certain
       conditions
   3)  Applied on a case -by-case basis
   4)  One-time use or used in pilot project
   4A) Pilot project, very early implementation or planning
   5)  Still a conceptual stage                                        j 3
   6)  In EPA Guidance                                    :

-------
work (P. Lloyd, NC DEM, personal communication). The flexibility provided by
the alternative operating scenarios is also limited to the scenarios that are
foreseeable at the time of permit application, whereas a firm engaged in a
highly dynamic field (e.g., Pharmaceuticals or computers) may be continually
updating its processes.

The EPA, in recognition of the need for flexibility, has released a proposed
rule for Title V programs that explicitly provides for preapproved changes
(EPA 1995a). The pre-approved changes can help facility streamline the
paperwork they must do when they want to make changes, as can building
alternative operating scenarios under existing air permits. Preapproval of very
specific changes, like the New Jersey example described below, and building
alternate operating scenarios into the permit both are limited to changes that
are foreseeable at the time of permit issuance. Provisions like those in the
Intel draft permit that provide parameters for pre-approved changes, but do
not prescribe them are  likely to provide more flexibility. It may be difficult to
apply the concept of pre-approved changes widely in Title V permits because
the types of changes will vary industry by industry or even site by site, and it
could be quite time-intensive for permit writers to attempt to develop such
conditions for every permit.

      Examples of Using Pre-Approved  Permit Changes to Create  Flexibility

Oregon

The draft Intel Title V permit (discussed at page 4) preapproves changes at the
facility within certain limits. Intel may increase its maximum capacity to emit
VOCsif:

      >     The increase is offset by emission reductions achieved through
            the facility's pollution prevention plan (see discussion below);
      »•     Permitted air pollution control devices are not changed nor
            performance degraded;
      >     The numerical VOC emissions per unit product prescribed under
           the facility-specific Reasonably Available Control Technology
            (RACT) rules are not violated;
      >     The P2 "good operating" practices prescribed under the facility-
           specific RACT are not violated;
      *•     Source-specific compliance monitoring is not affected
      >•     No new applicable requirement is triggered

Because the Intel facility has not been operating under the draft permit, it is
impossible to tell whether its preapproved changes have had the effective of

                                   14

-------
boosting P2. The Oregon DEQ noted that these preapprovals have the effect of
approving the changes that the state "would have approved anyway," thus
they remove a needless obstacle. Intel is required to file notice of the changes
with the department (G.Yun, ODEQ, personal communication).

The limitation that preapproved changes must stem from the facility's required
P2 plan provides coherence between the requirements of the permit; it clearly
indicates that the P2 plan should not be a paper exercise but should be a tool
used by the facility to reduce emissions. It also has the effect of providing
preferential regulatory treatment to P2 changes.

New Jersey
                                                               •.
New Jersey has incorporated pre-approved changes into permits for auto
plants. Existing manual painting operations are pre-approved to convert to
robotic spray (which is generally considered to be more efficient and is a P2
measure). This is applicable to only two facilities in the state, and information
about whether they have taken advantage of the preapproval was not available
(New Jersey, 1994).

Facilities participating in New Jersey's pilot facility wide permit program may
make changes without state approval  if the change is developed through a
pollution prevention plan and the change does not increase emissions into air
or water, does not cause an increase in generation of waste per unit of
production, and does not add a new process. Only one facility is currently
operating under this type of permit, thus it is too early to say whether the
nexus between the P2 plan and flexibility will have the desired effect
(S.Anderson, NJDEP, personal communication).

Minnesota

3M and the state of Minnesota used pre-approved permit changes as a way to
reduce the disincentives for P2 at the 3M plant in St. Paul (Style, 1994).
Changes to production lines can be undertaken and are listed in the permits.
3M is required to notify the state agency before making a listed change and
after the change is implemented; it can propose unlisted changes that are
consistent with the listed ones, and if approved, can operate under the same
permit. This lets the facility incorporate P2 changes and process
improvements that let it increase production without requiring a permit
modification.
                                   15

-------
2.1.2       Emissions Caps

Bubbles and emissions caps are another way that states have attempted to
create permit flexibility. Bubbles and emissions caps work by setting limits on
total emissions of various pollutants from a whole facility rather than
prescribing a limit for every source of the pollutant in the facility. This enables
the facility to choose the most efficient method of achieving their overall
allowable level, perhaps by over-reducing emissions at one source while
under-reducing at another. These reductions can be made with P2 or with
treatment technologies, so emissions caps do not inherently promote P2.
Nevertheless, they may remove a disincentive to take P2 measures.

Flexibility under emissions caps can be used as a reward for facilities who
implement P2. It is not clear whether enforcement of emission caps will be
more difficult due to the increased complexity of calculating the total
emissions from all sources under the cap.

      Examples of Bubbles or Emissions Caps

Texas

The Texas Natural Resource Conservation Commission, New Source Review
Section, began accepting applications for flexible permits in 1994. They have
received 10 applications so far and have approved two flexible permits. The
flexible permits are based on an emissions cap or multiple emissions caps for
a particular site. This program is not designed with a pollution prevention
objective. Rather it is designed to ease the administrative burden on firms and
thus to encourage firms that have been "grandfathered" in the air program to
obtain permits in exchange for emissions reductions based on best available
control technology (BACT) (S.Hildebrand, personal communication).

Minnesota

The Minnesota Pollution Control Agency has proposed a pilot project under
the EPA's Project XL2 that uses emissions caps to promote flexibility. The
state proposes to work with facilities to develop multimedia permits in which
facilities agree to emissions  reductions that are beyond the levels required by
existing regulation. In exchange, the state will give them greater operating
      2 Project XL is a voluntary EPA national pilot program designed to foster innovation in
industrial environmental protection. As of this writing, pilot sites are being screened, but it is
likely that some of the pilots will involve improvements in the permit process.

                                   16

-------
flexibility using an emissions cap. One pilot is underway with the 3M plant in
Hutchinson, Minnesota. Others may be forthcoming if the state's proposal to
Project XL is approved (Project XL, 1995).

2.2   P2 Planning Incorporated Into Permit

A pollution prevention plan is a written document that identifies sources of
significant wastes and/or emissions at a facility and identifies measures that
can be taken to prevent the generation of those wastes and pollutants. Many
states have instituted a requirement that certain industries prepare facility P2
plans. These states do not require implementation of the P2 plans. The
rationale behind requiring planning but leaving implementation up to the
individual firm is that by forcing firms to analyze P2 options, firms will become
aware of opportunities to  save money and reduce waste through P2 and will
take those opportunities that are feasible.

P2 planning components  can be incorporated into environmental permits
either by requiring a P2 plan as part of the permit application or by requiring
that the facility develop a  P2 plan within the first year or so of permit issuance.
The program may require either submission of that plan or certification of
progress toward the goals of that plan.

P2 plans in permits potentially overlap or duplicate state mandatory planning
requirements in states that have such legislation. P2 plans in permits,
however, differ from state planning laws in that:

      1. P2 planning laws in most states apply to large quantity generators of
      hazardous waste. It is unclear at this time how many facilities that will
      need Title V permits fall within that category.

      2. P2 planning that  is incorporated into permits may become part of the
      public record, while in many state planning laws, the plan is
      confidential, and is  kept on site, or a "clean" executive summary is
      submitted to the state.

      3. P2 planning requirements incorporated in permits often focus
      attention on one or  two regulated substances of particular concern,
      rather than being broadly drafted as many state mandatory planning
      laws are. For instance, RTI reviewed some Wisconsin water discharge
      permits that targeted specific toxics, and some that targeted only
      chlorides. P2 planning  requirements in permits tend to be media
      specific as well — planning in air permits focuses on compliance with air
      limits, but they may make reference to the desirability of avoiding cross-

                                   17

-------
      media transfer of pollutants.

The overall effectiveness of mandatory P2 planning is unclear (both within the
permit process and in other state laws). Rozell and Brower (1993) conclude
that Oregon's general P2 planning law has been very successful with large
companies and less so for smaller facilities. They base that assessment on
compliance with planning requirements, interest in training and technical
assistance and other correspondence with industry, but they note that it is not
possible to currently measure the direct reductions attributable to the
requirement.  P2 planning conditions in the permit may be a useful way to
direct facility attention at P2 approaches to compliance, particularly where the
facility is not otherwise subject to a statewide P2 planning requirement.
Planning requirements that take effect after the permit is issued may be useful
where it is not immediately clear what P2 measures the facility might take as
part of the permit If the permit writers can spot obvious P2 avenues, then they
may be able to incorporate a planning condition to require the facility to
evaluate that avenue.

Mandatory P2 planning as a component of permit application has the
advantage of drawing a facility's attention to P2 early in the process, rather
than after they have drawn up a  permit application that relies on pollution
control. However, incorporating  a P2 plan in an application creates potential
public access to the plans, creating a disincentive for facilities to participate
in such planning (Anderson and Herb, 1994).

      Examples of Use of P2 Plans in Permit Context

Oregon

The draft Intel permit provides that after issuance of the permit, the facility
shall create a pollution prevention plan. The  permit lists specific required
elements that must be in the plan. The planning process is given impetus in
that preapproved changes in the permit (discussed above at page 10) are tied
to the pollution prevention plan under the permit.
                  /•
New Jersey

In New Jersey's pilot permit issued to the Schering corporation, the state
struggled with ways to set individual limits based on the facility's P2 plan.
New Jersey points out that incorporating the state P2 planning process into
the permit application process moves the permit process towards a more
integrated view of facility data, rather than basing P2  plans on one set of
numbers and regulatory compliance on a second set  of numbers (S.Anderson,

                                   18

-------
 NJDEP, personal communication).

 Other permits in New Jersey require P2 planning after the permits are issued.
 Asphalt manufacturers are required to conduct P2 plans. These are primarily
 based on maintenance and good operating practices. The permittees are
 required to submit forms to the state quarterly showing that they have taken
 some preventive maintenance or good operating practice steps during that
 quarter. This requirement was developed in conjunction with the industry
 trade group, and has been very successful (L.Mikolajczyk, NJDEP, personal
 communication).

 Wisconsin

 Some Wisconsin Water Pollution Discharge Elimination permits contain
 requirements that the facility develop P2 plans that target chloride discharges.
 These are being applied to permits in the dairy sector and for POTW permits
 with the specific goal of reducing chloride emissions in anticipation of
 statewide chloride standards. The permits prescribe certain elements of the
 plans, but no review of quality is made by the department. This is a relatively
 new effort, so no assessment of P2 promotion is possible, but the industry in
 general is reportedly "pretty receptive" to drawing up the plans (R.Larson,
 WDNR, personal communication).

 2.3   Evaluating a P2 Option for Permit Compliance

 One of the ways that states have attempted to incorporate P2 into permits is to
 require permittee to evaluate P2 measures as a compliance option before
 considering control strategies. This has the effect of strongly stating the
state's preference for P2 as a compliance strategy. It also may be able to
 create an environment where P2 is not viewed as optional or as a special
effort, but is an  integral part of thinking about process design.

 Requirement of consideration of P2 before compliance may be an effective
way to direct a facility's attention towards P2 if they traditionally have used
 pollution control to meet regulatory standards. There may, however, be
 regulatory barriers to use  of P2 for compliance, that will interfere with
application of the P2 methods the firm identifies. For instance, there may be
concerns by the EPA regions or the state about the enforceability of using
certain P2 measures for compliance.

 Industry is likely to be interested in information about reducing emissions to
 levels that allow them to reduce their regulatory review. One major stumbling
block to such an approach in the Clean Air Act may arise when facilities try to

                                  19

-------
use P2 to qualify as a synthetic minor. If the P2 measures they want to take
cannot be prescribed as federally enforceable limits, they may have to go
through the full Title V permit review process. Although there is some
question about whether EPA is allowed to require federal enforceability of
limits as a precondition to reduce review for synthetic minors, it may remain
an impediment at the state level unless states begin widely incorporating
enforceable P2-obtained limits into permits (National Mining Association et al.
v. EPA).

A second barrier to use of P2 to meet permit limits may occur in the situation
where a P2 measure which will effectively reduce the facility's actual
emissions still increases their potential to emit. If the potential to emit is
above applicable thresholds, it will trigger New Source Review (NSR) under
the Clean Air Act and may create a conflicting requirement to install best
available control technology (BACT). Even if BACT is not required, the NSR
process is complex and can be time consuming.

      Examples of Evaluation of a P2 Option for Compliance

Oregon

Intel's draft permit requires it to manage all its air emissions using a pollution
prevention approach, Once they begin operating  under the permit, they will
also develop a series of measurement indicators that will be used to generate
data on whether "P2 first" is an effective or feasible management option for air
emissions (Pollution Prevention Northwest, 1994).

West Virginia

West Virginia's State air toxics rule requires facilities to consider source
reduction before looking at control for their required top-down evaluation of
best available technology (BAT). The state required a demonstration that
source reduction had been considered before it issued permits for control
devices at affected facilities. This program affected 26 companies when the air
toxics rule was implemented. The state offered technical assistance to the
companies, and worked with them before their permit submission. West
Virginia found the process to be very successful, and reports large air toxics
reductions at individual facilities through P2 (R. Atkinson, WVAPCA, persona)
communication).

Minnesota

In the permit for Artistic Finishes, a wood finishing facility in Minnesota, the

                                   20

-------
company is directed to conduct a study of P2 approaches to reducing VOC
emissions. If the company's study identifies acceptable substitutes for VOC-
containing materials, then a schedule for the implementation of these
becomes an enforceable part of the permit. If no acceptable substitutes are
identified, then the permit directs that company to institute control based-
approaches (WRITAR, 1994).

New Jersey

New air regulations in New Jersey require facilities to consider P2 before they
consider pollution control options. The P2-consideration-first requirement was
also instituted in the permit issued to Schering Plough under the state's pre-
pilot multimedia permit efforts. That permit has only been in effect since
December 1994, and the air regulations since 1995. Thus is it too early to tell if
more P2 is occurring than previously. Nevertheless, the state believes that it
is an important incentive to push firms towards  bringing P2 thinking into how
they do business (S.Anderson, NJDEP, personal communication).

2.4   P2 Conditions as Part of Permit

In addition to requiring the consideration of P2 possibilities, it is also possible
to incorporate more specific P2 conditions into an operating permit. The
research for this report identified three major mechanisms for incorporating
P2 as a permit condition:

      1) The permit could specify certain P2 measures that a facility is
      required to take (e.g., annual adjustment of burners to ensure efficient
      combustion).

      2) Where P2 is being used to meet permit limits, these P2 measures can
      be written into the permit in the same way pollution control measures
      would be incorporated into a permit.

      3) where a facility has gone beyond compliance, in special
      arrangements with the permitting authorities, the permit may codify
      this.

The prescription of P2 conditions in permits is contrary to the premise that
often accompanies P2 policy in this country that P2 should be a voluntary
effort and every company is the best judge of the most effective P2 choices
for its own facility. P2 conditions in permits can be made more flexible by
requiring only that the facility investigate P2 and implement those options that
make sense at that facility. This may be particularly effective in industries

                                  21

-------
where P2 measures have not been widely implemented. In such a situation,
wider use of good operating practices and preventive maintenance can have
significant impact on emissions and hazardous waste generation at relatively
low costs.3

Where P2 compliance options are offered in a regulation, then enforcement of
those options through a permit is appropriate, since the company has already
made the choice to use this form of compliance rather than using control.
Indeed,  integration of enforceable options to use P2 as a compliance
mechanism under the normal regulatory structure has the potential to provide
added flexibility to industry in their choice of compliance options and to
remove the over-reliance on end-of-pipe treatment.

      Examples of Including P2 Conditions in a Permit

New Jersey

Asphalt manufacturers in New Jersey are both required to have plans for
reducing carbon monoxide and hydrocarbon emissions and to report
quarterly on good operating practices that they are using. This requirement
was implemented in consultation with the industry trade association as part of
a request by the state that industry show progress towards emissions goals
for the industry (New Jersey, 1994).

Indiana

P2 conditions are prescribed in permits for VOC sources who are using
materials substitution to comply with Indiana's non-control technology
guideline RACT standard. The P2 condition requires the facility to document
reduction in use of VOC-containing materials, and it is analogous to the
reduction documentation required when using pollution control devices to
achieve the required reductions (J.McCabe, IDEM, personal communication).

Minnesota

The 1991 permit for Sheldahl, a manufacturer of electronic circuitry in
Minnesota contains a P2 condition in the form of a required phase-out of
      3 It is often assumed that if a P2 practice is profitable, that industry would already be
taking advantage of it. Experience has shown that this is not always true. There are still many
facilities that can profit from application of P2, and which might not investigate these options
without incentives or requirements.

                                  '22

-------
methylene chloride (dichloromethane) facility wide. The levels were capped in
1991, and a schedule for a facility-wide phase out instituted (Style, 1994). It is
anticipated that the reductions will be achieved through a combination of
prevention and substitution of a non-chlorinated VOC. The permit does not,
however, specify that these are the methods that must be used.

2.5   Providing P2 Information in Permit Application Process

Provision of technical P2 support and information in the permit application
process is an additional mechanism that states can use to promote P2.
Provision of information at the time of permit application can be an effective
mechanism to promote P2. Rozell and Brower (1993) found that most facilities
want and need compliance assistance more than they need help with pollution
prevention planning under Oregon's P2 Planning Law. This finding suggests
that compliance assistance targeted to P2 may be welcomed in the regulated
community as well as provide an opportunity to promote P2. It is also clear
from discussions with states in the course of this research that the earlier in
the permit process that a state can suggest P2, the more likely it is to be
effective.

It may, however, be a challenge to find ways to use P2 to comply with some
rules. Often standards are written from a pollution-control viewpoint, as in the
case of the non-Control Technology Guideline RACT standard in Indiana,
described at page 23. In that situation, the EPA wanted the RACT standard to
be written to reflect reductions achieved with pollution control rather than
reduction in use of VOCs. Examples of P2-friendly standards are provided at
page 25.

      Examples of Provision of P2 Information in Permit Application Process

Indiana

Indiana's Compliance Technical Assistance Office presented seventeen Title V
permit workshops which included discussion of use of P2 for compliance. The
staff who ran the workshops for Indiana felt that this effort had been very
successful, and that when they began talking about using P2 for compliance
after discussing the control options, "you could just see the little light bulbs
going on over people's  heads" (T.Neltner, IDEM, personal communication).

Massachusetts

Massachusetts and Indiana have included information about P2 opportunities
in materials distributed  with their Title V applications or notices, and

                                  23

-------
responders were referred to state technical assistance offices where
appropriate. Since these notices went out relatively recently, it is too early to
tell whether firms are using P2 in their permit application planning. Indiana is
in the process of developing statewide P2 measures that might provide some
insight into how effective such efforts have been, although it will be difficult
for them to attribute reductions to one or another of their specific programs
(D.Gallagher, formerly with MA DEP; T.Neltner, IDEM, personal
communications).

2.6  Multi-Media Permits

Currently, most environmental operating permits are issued on a single media
basis. The use of multimedia permits might be able to eventually replace these
sometimes-conflicting or duplicative requirements with a single standard for
environmental protection. Multimedia  permits may also reduce cross-media
transfers of pollutants, which is a goal of P2. The concept of multimedia
permitting is not exclusively directed at P2, but conceptually it could be a tool
to leverage P2 in permits.

For instance, in permit application process, a multimedia team of permit
writers can more easily point out cross-media transfer problems, the cross-
media impacts of control or prevention efforts for one media. Including a
pollution prevention specialist on that team (as Massachusetts has done) can
further promote P2 (D.Fine, Mass. DEP, personal communication). On the
other end of the spectrum, multimedia permits may be just an administrative
convenience, as is the case at some Massachusetts disposal facilities which
use multimedia permits as a way of coordinating duplicative requirements,
particularly for solid waste and air.

The multimedia permit process is just beginning in many states. As with any
new concept, there seems to be a steep "learning curve," leaving questions
about what the effectiveness of these efforts will be over the long term. The
EPA will be following up with various multimedia permit efforts and will be
subjecting them to a series of evaluative examinations (N.Roy, USEPA,
personal communication). This effort over the next one or two years will
hopefully provide  good guidance on the strengths and weaknesses of such an
approach.
                                  24

-------
      Examples of Multimedia Permits

 New Jersey

 New Jersey has issued one facility-wide permit under its pilot multimedia
 permit program. This program explicitly requires a combination of the
 facility's media permits with its P2 plan (New Jersey has a state mandatory
 facility planning law). The state has tried to set emissions limits based on the
 data collected for the P2 plan. In this way, it feels that the emissions limits
 make more sense, and the P2 plan is made more meaningful (S.Anderson, NJ
 DEP, personal communication).

 New York

 New York State is in the planning phase of a multimedia environmental permit
 to promote P2. New York believes that seeing the multimedia impacts of
 compliance requirements through a multimedia permit can help a facility
 prioritize areas for P2 action as well as point out opportunities for P2
 (J.Higgins, NYDEC, personal communication).

 Delaware

 The State of Delaware is beginning a pilot multimedia permit process which
 will integrate a pollution prevention assessment as part of the permit
 application. The State will assist the facility in the P2 assessment and work
 with the facility to eliminate various waste streams or reduce them below
 permitting levels (A.Farrell, DNREC, personal communication).

 2.7   Permits Fees Structures

 One mechanism for promoting P2 in permits is to offer reduced permit fees to
facilities that demonstrate that they are implementing P2 into their permitted
 activities. Firms currently pay a fee per ton of pollutant generated for air
 pollutants, so there is a "built-in" incentive for reduction. Likewise, many
states are exploring the use of general permits under the Title V program;
these would allow certain smaller emitters to avoid the full facility-specific
 permit application process, and simply register their operations. This too
would be an incentive to bring emissions down below the threshold of the
 limit for general permits. The incentive of reduced fees is more likely to be
effective in situations where the P2 measures that can be taken to meet
thresholds are relatively inexpensive.

      Examples of Use of Permits Fee Structures to Promote P2

                                   25

-------
Wisconsin

Wisconsin has successfully used reduced fees in combination with reduced
reporting requirements to promote P2 through its stormwater permits. Firms
that can show uncontaminated stormwater runoff (almost entirely obtainable
by P2 measures like covering a dumpster or keeping potential contaminants
away from stormwater) can reduce their annual fee by $100 or $200 annually.
The Wisconsin program, described on page 23, also offers reduced
monitoring to sites that substantially reduce the contamination in their runoff.
This program has been heavily promoted by the state and industry was
involved in developing it. The combination of reduced fees, reduced reporting
and extensive promotion of P2 in the Wisconsin stormwater program has
induced many firms to spend well more than the cost of the fees to implement
P2 practices that would allow them to have uncontaminated runoff (R.Larson,
Wl DNR, personal communication).

Minnesota

Minnesota is considering use of hazard-based fees as a TUR-incentive. This
would go beyond the uniform reduction incentive provided by per-ton fees on
air pollutants, and instead would scale the cost per ton to match the potential
harm. In theory, the result should be a preferential reduction of the most
hazardous substances first. The state has undertaken analysis to ascertain
the political feasibility of such a move. A survey shows that this would be
politically acceptable to their survey sample. The state is following up with
further study (Minnesota Pollution Control Agency, 1994).

2.8   Accelerated Permit Review

Firms often complain that they are reluctant to make production changes that
would require a permit modification because the time to approve such a
modification would make the project infeasible. Providing accelerated review
for permit modifications that involve P2 projects may remove one disincentive
to making P2 changes. For many permits, however, there may be mandatory
public notice periods that would hinder a state's ability to accelerate the
permit review time.
                                  26

-------
      Examples of Accelerated Permit Review

California

An EPA-state program in California (Project MERIT) offered expedited review
of air permit modifications if the focus of the permit change was P2. They
considered the demonstration successful, and achieved their goal of
demonstrating that it could be done. However, continuing work on this kind of
preferential review was set aside in favor of work on more comprehensive
streamlining of permitting procedures in California (D.Reich, U.S. EPA,
personal communication).

Illinois

The State of Illinois has offered expedited review for the past two years for
permit modification applications that incorporate a P2 component. The state
has a formal mechanism for submitting a request for expedited review. The
determination that the permit does contain P2 is made by staff from the Office
of Pollution Prevention. The formal process has not been used often, but an
informal process is relatively common. In the informal process, the facility
that wants to make a P2 change calls the State Pollution Prevention Office,
which has good ties to the media permitting offices. The Office will then call
and informally request that this permit be expedited. Usually, the review
process can be reduced by one half to one third. A representative from the
Illinois office of P2 indicated that while firms appreciated the extra help
expediting their P2 permit changes, this was not a direct incentive to institute
P2 if a firm was not already planning to use P2 (T.Wallin, IOPP, personal
communication).

2.9   Extended Compliance Time

states occasionally have been able to provide extended compliance schedules
to firms who want to implement P2. Offering extended compliance schedules
may  provide a short-term environmental detriment which can be weighed
against long term benefits that may accrue from a facility's  implementing of
P2 rather than pollution control.
                                  27

-------
      Examples of Offering Extended Compliance Time for P2 Projects

Wisconsin

Wisconsin water quality permit applicants can obtain an extended compliance
schedule to enable them to implement P2. A regulator cites an example of a
situation in which he was able to build an extra year into the compliance
schedule so that a firm could use P2 to meet regulatory limits. If the extra time
had not been provided, it would have been impossible for that firm to come
into compliance using P2 (D.Hantz, Wl DNR, personal communication).

Region 9

EPA Region 9's small business incentives policy gives firms 18 months of
compliance extension if they are using P2 rather than the usual six for normal
measures. We were not able to find out how successful this effort was in
promoting P2, but it provides an example of a state that has instituted a P2
incentive.

Texas

Texas' Natural Resource Conservation Commission, in its flexible permit
program under NSR is able to offer firms up to five years to come into
compliance with BACT prescribed by the flexible permit (see page 12). This
program is not designed to especially promote P2, but rather demonstrates an
example of a situation where extended review can be offered where it will help
a facility reduce emissions over the long term (S.Hildebrand, TNRCC, personal
communication).

2.10  Alternative or Reduced Monitoring as Reward for P2

The states and the EPA have been interested in finding incentives that they
can offer to firms in exchange for the firms commitment to either go beyono
compliance, or to perform some extra P2 measures. One possibility is to offer
the firm  the opportunity to do less monitoring or record keeping. The rationale
for such concession is that if the firm is well below regulatory thresholds, then
there is  less danger to the public health if they are not monitoring as strictly.

Where P2 efforts are relatively easy to take, as in the stormwater case, the
incentive of reduced monitoring is likely to be more successful. Where the P2
effort requires a larger investment, the incentive of reduce monitoring may not
be adequate to offset the costs. In addition, the effectiveness of the incentive
is likely  to depend on how widely know it is and how well the regulators and

                                  28.

-------
 regulated community understand it.

      Examples of Reduced Monitoring

 Wisconsin

 In Wisconsin, reduced sampling and reduced planning and reduced fees are
 offered to firms that can show uncontaminated stormwater runoff (almost
 entirely obtainable by P2 measures like covering a dumpster or keeping
 potential contaminants away from stormwater). This has reportedly been very
 successful as an incentiv ;, although the fees involved are relatively low ($100
 or $200 per year), the combined reduced sampling and chemical testing
 combined with the reduced fee resulted in firms being willing to invest in
 implementing P2 practices. This program has been heavily promoted by the
 state and industry was ii volved in developing it (R.Larson, Wl DNR, personal
 communication).

 North Carolina

 A broader situation of reduced monitoring as a reward for use of P2 occurs
 when a standard is written such that demonstration of the use of a technology
 or input or work practice is the required compliance demonstration; thus the
 facility is not required to keep records on usage and emissions factors or
 monitor for emissions, but merely must certify application of the given
 technology. This is shown in the situation in North Carolina where state RACT
 rules allow use of low-VOC-emission coatings for various industries as an
 alternative to prescribing a numerical daily emissions limit. The record
 keeping requirement is thus reduced from a requirement of monitoring
 coating use daily and calculating emissions based on emissions factors to
 merely certifying use of one of the compliant coatings. Although the reduction
 in record keeping is significant, the program was described by one regulator
 as only marginally effective in promoting P2. In part this is because not many
 facilities know about it or about how to take advantage of the alternative
 regulations, in part because the coatings switch is perceived to be fairly
 difficult, and there are quality concerns in making the conversion. In the case
 that RTI reviewed, the facility was already committed to using low-VOC paints,
 and had applied for a permit modification without realizing that they could
 obtain reduced reporting requirements (P.Lloyd, NCDEM,  personal
 communication).

 Indiana

The Indiana non-Control Technology Guideline RACT standard for VOCs has

                                  29

-------
various record-keeping, monitoring and testing requirements for facilities that
are meeting RACT by using control technologies, but where they meet RACT
by substituting non-VOC materials for high-VOC ones, they only have the
recordkeeping requirement. An Indiana regulator who worked on the standard
also noted that the state's compliance review burden was significantly
reduced in cases of facilities that had used material substitution for
compliance (J.McCabe, IDEM, personal communication).

U.S. EPA

The EPA's Permit Improvement Team4 (PIT) has also shown interest in
alternative monitoring as a P2 incentive, suggesting that two tracks of
compliance monitoring be offered to facilities but this appears not to have
been implemented thus far (U.S. EPA, 1995b).

EPA guidance for capture efficiency for the coatings industry incorporates an
alternative monitoring component, which would allow states to allow firms to
use statistical methods to show compliance rather than more expensive direct
monitoring. The firm would, however, have to be operating well below
permitted levels to meet the criteria for this method. This could provide a good
incentive for facilities that are committed to going beyond compliance, either
as part of EPA pilot programs or as part of other commitment to an improved
environmental record (U.S. EPA, 1995c).

2.11  Use  of Inspectors to Promote P2

Not only can P2 conditions and planning be incorporated into a specific
permit, but the permit inspection process may be an effective tool for
promoting P2. Permit inspectors may be very well acquainted with the
operations of the regulated industries. Thus,  some states have attempted to
train their inspectors to be able to identify P2 opportunities or to promote P2
in other ways.

Use of inspectors to promote P2 has promise because they are actually inside
the facilities and can observe specific opportunities for improvement. An
inspector who is observing potential violations and can point out ways to
avoid such  violations is in a good position to get the attention of a facility's
management. Nevertheless, the inspector's job must remain focused on
      4 The Permit Improvement Team is composed of EPA and state regulators. The Team is
charged with identifying improvements to the permit system and mechanisms for implementing
the improvements.

                                  30

-------
 collecting legal evidence regarding regulatory compliance. Use of permit
 inspectors to promote P2 has the potential of creating confusion about
 whether the inspector is there for enforcement or for promoting voluntary
 changes. This confusion may result in the inspector's P2 suggestions being
 incorrectly perceived as requirements. Further, the types of knowledge
 required of good inspectors and good P2 technical assistance staff are
 different. Inspectors must be regulatory experts, while technical assistance
 staff must have industrial process knowledge (Helbrecht, 1994).

 EPA Region 1 summarized its positions on.regulatory and nonregulatory
 approaches to promoting P2 in a 1993 white paper. The Region emphasized
 the need to clearly distinguish between compliance assistance and
 enforcement activities. The white paper emphasized the potential danger of
 confusing these two roles when  permit inspectors also have a role in
 compliance assistance, including P2 assistance (USEPA, Region 1,1993).
      Examples of Using Inspectors to Promote P2

U.S. EPA Region 9

EPA Region 9 evaluated the use of inspectors to do waste minimization
opportunity assessments at facilities. They concluded that they did not have
the resources or technical capabilitites for such a program, and that it would
also be at odds with their principal mission of compliance (L.Magnuson, U.S.
EPA, personal communication).

Indiana

Indiana inspectors distribute P2 information during inspections and have been
trained in P2. They can suggest operational improvements but not
-reeingineering. There were concerns that going further would put too much
burden on inspectors or create a conflict of interest (T.Neltner, IDEM, personal
communication).

2.12 Incorporating P2 into the Underlying Rule

An important way of incorporating P2 into permits is to incorporate P2 into the
underlying rule. This can be accomplished either by prescribing the P2
measure directly (as in the case of prescribing certain work standards or
maintenance efforts) or by basing a numerical limit on the emissions
reductions that can be achieved by P2 measures. Rules may also promote P2

                                  31

-------
by explicitly allowing for P2 measures to be used for compliance, or by
creating similar incentives for use of P2 as for control measures.

      Examples of Incorporating P2 into Rules

Indiana

When Indiana was developing its non-CTG RACT rule, they discovered that
many facilities to which this rule would apply were planning to use materials
substitution to reduce their VOCs. This caused some concern by Region 5
whether these kinds of reductions would be enforceable. The region felt that a
RACT requirement of 81% reduction through pollution control was a more
enforceable requirement. The state was able to work with EPA to develop a
three-tier rule that explicitly allows P2 as a compliance strategy:

            Tier 1 facilities reduced their VOCs 98% from a calculated
            baseline through documented reduction in use of VOC containing
            materials or through add-on controls.
            Tier 2 facilities are those that could achieve 81% reduction
            through substitution or control. These facilities were required to
            not only do the complex baseline calculations, but also to make a
            demonstration that they could not achieve a 98% reduction.
      *     Tier 3 facilities are those that could not achieve 81% reductions.
            These facilities had to make a demonstration that they could not
            achieve the reductions, and a case-by-case RACT was set for
            these facilities.

This rule facilitates use of material substitution (P2) in a context that might
have required exclusively pollution control requirements. In addition, all the
facilities that achieved 98% reduction did so by material substitution, and thus
were exempted from the requirement to make a demonstration that lesser-
reducing facilities had to make of inability to reach 98% (J.McCabe, IDEM,
personal communication).

Also in Indiana, the state found that it had written a rule in which facilities
could comply with coatings limits by using control devices or using high
volume low pressure (HVLP) guns and work practices.  The  rule prescribed
that if the P2 measures were used, that the facility had to also include a
training component to its use of P2 for compliance. This was seen as a
disincentive, so the state revised the rule to require a training component for
firms that were using a control device to comply (T.Neltner, IDEM, personal
communication).
                                  32

-------
 Indiana's pollution prevention office conducts review of all state
 environmental rules and suggests changes that can make them more P2
 friendly or remove P2 disincentives. This has resulted in the modification of
 approximately ten rules since the program began.

 3    Conclusions

 Many states and some federal programs are trying to integrate P2 into their
 permitting activities. These efforts occur at all stages of the life of the permit,
 from pre-issuance to permit inspections.
 Often, activities to promote P2 through permits involved removing P2
 disincentives contained within the existing permit structure. Other efforts
 concentrated on providing direct incentives for P2 efforts. Still other
 integration efforts aimed at directly incorporating P2 concepts and conditions
 into the permit. Many of these P2 integration efforts are still at the pilot stage,
 or are applied to a small segment of individual industries. Often, too, these
 efforts are not followed up with systematic evaluation of the effectiveness of
 the efforts, forcing those who want to extend such efforts to rely on anecdotal
 evaluations of the effort. Even with anecdotal evaluations, it is difficult to draw
 broader conclusions about how well any given P2-integration  approach will
 work because the effectiveness of the method will vary according to the
 context in which it is applied.

 Although it is impossible to make broad generalizations based on the results
 of this report, it is possible to parse out some factors which were present in
 several of the programs that  reported successful integration of P2 into
 permits:

            The  mechanism  of the integration effort is consistent with the
            state's underlying P2 mandate and philosophy

            Regulators worked with other stakeholders (e.g.,  industry, the
            EPA Region) to solve potentially contentious issues

            The  regulators worked with regulated facilities early in the
            process

These factors will be important for states to consider as they embark on
efforts to promote P2 through the permit process. They will also be important
for the EPA to understand as the Agency works with the states to manage the
Title V Permit programs and other environmental permit programs.
                                   33

-------
Appendix A

Contact Information for P2 Integration Efforts

Deborah Gallagher, formerly of Massachusetts Department of Environmental
      Protection,
      (617) 933-2800

Steve Anderson, New Jersey Department of Environmental Protection, (609)
777-0518

Rick Atkinson, West Virginia Air Pollution Control Agency, (304) 558-4022

Andrea Farrell, Delaware Department of Natural Resources and Environmental
      Conservation, (302) 739-3822

Doug Fine, Massachusetts Department of Environmental Protection, (617)
574-6862

David Hantz, Wisconsin Department of Natural Resources, (608) 267-7664

John Higgins, New York Department of Environmental Conservation, (518)
457-7688

Susana Hildebrand, Texas Natural Resource Conservation Commission, (512)
239-1300

Roger Larson, Wisconsin Department of Natural Resources, (608) 267-7664

Peter Lloyd, North Carolina Department of Environmental Management, (919*
733-3340

Leif Magnuson, U.S. EPA Region 9, (415) 744-2153

Janet McCabe, Indiana Department of Environmental Management, (317) 233-
5694

Robert McCarron, Minnesota Pollution Control Agency, (612) 296-7324

Louis Mikolajczyk, New Jersey Department of Environmental Protection, (609)
292-9258
                                 34

-------
Thomas Neltner, Indiana Department of Environmental Management, (317)
232-8172

Susie Peck, Massachusetts Department of Environmental Protection, (617)
292-5870

Dan Reich, EPA Region 9, (415) 744-1343

Nikki Roy, U.S. EPA, (202) 260-8636

Tom Wallin, Illinois Office of Pollution Prevention, (217) 782-8700

George Yuri, Oregon Department of Environmental Quality, (503) 229-6093

References

Anderson, S. and J. Herb, "Building Pollution Prevention into Facilitywide
      Permitting," Pollution Prevention Review, Autumn 1992, pp. 415-429.

Helbrecht, L, "Integrating Pollution Prevention and Compliance: How Far Can
We Go?," Pollution Prevention Review, Summer 1994, pp. 331-336.

Inside EPA, "Interview with Mary Nichols," July 7,1995, p.5.

Minnesota Pollution Control Agency, Air Quality Division, "The Feasibility of
      Using Fees to Control Toxic Air Emissions," Prepared for the US E.P.A.,
      Region V, St. Paul, Minnesota, June 1994.

National Mining Association et al. v. EPA (95-1006).

Neltner, T.G., "Integration of P2 into Environmental Regulations: Indiana's
      Approach," Presented at the Pollution Prevention Roundtable
      Conference, Fall, 1994.

New Jersey, Annual Report of Pollution Prevention Activities Undertaken by
      NJ Air Quality Regulation Program, Trenton, N.J., July 29,1994.

Pollution Prevention Northwest, "Incorporating P2 into Title V Permits,"
Pacific Northwest Pollution Prevention Research Center, Seattle Washington,
November/December 1994.

Project XL Summaries of Current Applications available from Rob  Mellinger,


                                   35

-------
      ICF Administrative Support contractor for Project XL, (703) 934-3941,
      1995.

Rozell, O.K. and R.W. Brower, "Pollution Prevention Facility Planning: The
      Oregon Experience," Pollution Prevention Review, Summer, 1993, pp.
      277-283.

Style, R.L., "Pollution Prevention in Air Quality Programs - a Progress
      Report," Pollution Prevention Review, Spring 1994, pp. 229-232.

U.S. EPA, Office of Research and Development, "Facility Pollution Prevention
Guide," EPA/600/R-92/088, Washington, D.C., May, 1992.

U.S. EPA, Region I, "Pollution Prevention White Paper: The Relationship
Between Compliance/Enforcement and Voluntary, Non-Regulatory Programs,"
New York, N.Y., April 29,1993

U.S. EPA, Office of Air Quality Planning and Standards, "Memorandum re:
Pollution Control Projects and New Source Review (NSR) Applicability,"
Durham, N.C., July, 1994.

U.S. EPA, Proposed Rule 40 CFR 51, 70, and 71, Available on EPA Office of Air
      Quality Planning and Standards Technology Transfer Network (TTN)
      Electronic Bulletin Board, Durham, N.C., 1995a.

US E.P.A., Permit Improvement Team Task Force Reports,  Distributed as
      Background Materials for 1995 Stakeholder Meetings, Washington, D.C.,
      1995b.

U.S. EPA, Office of Air Quality Planning and Standards, "Guidelines for
      Determining Capture Efficiency," Durham, N.C., January 9,1995c.

Waste Reduction Institute of Training and Applications Research, "Resource
Guide: Pollution Prevention Strategy Workshop for U.S. EPA Region 4 State
and Local Air Programs," Minneapolis, Minnesota, February 1994.
                                  36

-------
Resources

U.S. EPA, Office of Research and Development, "Facility Pollution Prevention
Guide," EPA/600/R-92/088, Washington, D.C., May, 1992.

US E.P.A., Office of Air Quality Planning and Standards, "Pollution Prevention
Resource Guide for Supporting Clean Air Act Regulatory Development,"
Prepared by Research Triangle Institute, Research Triangle Park, N.C.,
September, 1993.

U.S. EPA Permit Improvement Team, "Inventory of State/Local/Federal Permit
Improvement Efforts," Expected available by early 1996. Contact: David Everly
(202) 260-4287.

WRITAR, "Resource Guide: Pollution Prevention Strategy Workshop for U.S.
EPA Region 4 State and Local Air Programs," Minneapolis, Mn., February
1994.                                   	

                    State Experience Integrating
                    Pollution Prevention into Permits
                    EPA/456/R-98/003

-------