&EPA United States Environmental Protection Agency Office of Municipal Pollution Control (WH-546) Washington DC 20460 July 1986 Water Energy in Municipal Waste Water Treatment An Energy Audit Procedure and Supporting Data Base Final Report ------- ENERGY IN MUNICIPAL WASTEWATER TREATMENT AN ENERGY AUDIT PROCEDURE AND SUPPORTING DATA BASE FINAL REPORT Contract Number 68-01-6433 Submitted To: U.S. Environmental Protection Agency Municipal Construction Division (WH547) Office of Water Programs Attention: Mr. James Wheeler 401 M Street, SW Washington, D.C. 20460 Submitted By: CARLTECH ASSOCIATES, INC. OVERLOOK CENTER, SUITE 301 5457 TWIN KNOLLS ROAD COLUMBIA, MD 21045 ------- TABLE OF CONTENTS 1. SUMMARY 1 2. INTRODUCTION 2 3. METHODOLOGY 4 3.1 Introduction 4 3.2 Project Plans 4 3.3 Task 1 4 3.4 Task 2 5 3.5 Task 3 7 Exhibit 3-1 8 Exhibi t 3-2 9 Exhibit 3-3 10 4. RESULTS 14 4.1 Operating Plant Energy Survey Method 14 4.2 Operating Energy Estimation Method 14 4.3 Acquisition Energy Estimation Method 15 4.4 Case Examples 15 Exhibit 4-1 16 5. CONCLUSIONS AND RECOMMENDATIONS 17 5.1 Conclusions 17 5.2 Recommendations 17 6. FUTURE WORK 19 7 . REFERENCES 20 ------- SECTION 1 SUMMARY EPA regulations require a methodology for determining energy requirements of municipal wastewater treatment because treatment plant construction and operation consume significant amounts of energy. Energy is a major driver of both operating and capital costs. In addition, most of the energy consumed is drawn from irreplaceable natural resources. In recognition of these factors, EPA requires analysis of the energy effectiveness of alternative types of wastewater treatment. The purpose of this project was to develop appropriate procedures to perform this analysis. Two types of energy were addressed during this project: o Operating Energy - energy expended during routine operation of a wastewater treatment plan; o Acquisition Energy - energy expended during the construction phase of a wastewater treatment plant. A means was developed to: o Evaluate energy consumption of operating wastewater treatment plants; o Estimate operating energy requirements of planned and operating wastewater treatment plants; and o Estimate acquisition energy of wastewater treatment plants. The energy evaluation method enables wastewater treatment staff to prepare estimates of energy use for existing plants and compare them to operating experience of typical plants of similar design. Methods have been developed for planners to estimate acquisition and operating energies of planned wastewater treatment alternatives to compare among process alternatives. ------- SECTION 2 INTRODUCTION A methodology for determining total energy requirements of municipal waste- water treatment plants is needed to satisfy requirements of EPA's May 12, 1982 Regulation, "Grants for Construction of Treatment Works" 35.2030(b) (3)(VI) "Facilities Plan Contents." The regulation requires evaluation of the energy effectiveness of alternative technologies considered by municipalities and other submitting organizations. Energy is an important contributor to both operating and capital costs of wastewater treatment plants and has a major effect on the cost effectiveness of treatment alternatives. Data on total energy consumption of wastewater treatment are found in many diverse sources and have not been assembled or analyzed on a unified basis. In recognition of this situation, EPA has adopted regulations requiring development of a means to analyze the energy effectiveness of types of wastewater treatment. This project has been performed in response to the regulations. The goals of the project were to collect data concerning energy consumption of wastewater treatment plant construction and operation; to present data on a consistent basis; and to develop a methodology which can be used by planners to evaluate wastewater treatment process alternatives and by operators to calculate actual operating energy and to evaluate changes in operating procedures. The project was divided into three tasks: o Task 1 - Obtain, aggregate, and analyze data; evaluate the CAPDET computer program (previously developed by EPA and the U.S. Army Corps of Engineers). o Task 2 - Develop a methodology for energy evaluation and apply it to case studies. o Task 3 - Aggregate Task 1 and Task 2 results, and present as Final Report. This report concerns the conduct of all three tasks. The report is organized in the following fashion: o Section 1 contains the summary of work performed. o Section 3 discusses the methodology used to conduct this study. o Section 4 presents and discusses results: description of the methodology for estimation of operating and acquisition energies; ------- description of the operating plant energy survey method; and - operating and acquisition energies for unit processes dis- cussed in Task 1 (1). o ' Section 5 presents conclusions and recommendations. o Section 6 describes relevant future work. o Section 7 contains references. o Appendix A presents the energy estimation and survey procedures. o Appendix B presents illustrative case examples. o Appendix C presents alternative methodologies. ------- SECTION 3 METHODOLOGY 3.1 INTRODUCTION This section describes the overall approach of this project. It is divided into subsections as follows: o Project Plans; o Task 1; o Task 2; and o Task 3. 3.2 PROJECT PLANS Projects plans for this study were prepared and delivered in 1981 and 1982. They discussed development of acquistion and operating energy procedures, tables, and equations for use by planning and operating personnel. 3.3 TASK 1 Task 1 consisted of : o Choosing unit processes for analysis; o Literature review; o Data analysis; and o CAPDET evaluation. Unit processes were chosen starting with the list of processes addressed in EPA publications. Input from the EPA Project Officer was then used to reduce the number of candidate processes to about 75 unit processes. These processes were further examined to assess the quantity of data available from other contractors and from the literature. Approximately 25 technologies were rejected because of insufficient data; the remaining 50 unit processes are discussed in this report. The literature review consisted of: o Database searches - we examined more than 900 titles from eight databases and selected about 100 for this study; ------- o EPA Small Wastewater Flows Clearing House - we examined more than 1000 different titles pertaining to small wastewater flows and selected about 20 for use in this study. o Knowledgeable Individuals - we conducted telephone interviews with knowledgeable•individuals who furnished valuable information. Data was also obtained from the literature on the selected wastewater treatment unit processes. Both acquisition and operating energy data was identified for treatment plant design flow in the range of 0.5 to 100.0 million gallons per day. Acquisition energies were calculated using a building block approach based upon 1967 wastewater treatment plant costs for commodities (materials used in plant construction and operation). These acquisition energies are included in the manual portion of this report. Literature data on operating energies were found and examined for nearly all of the 50 unit processes discussed in this report. Data presented in the literature varied so widely (1) that comparison among authors and with our calculated values was not possible. Insufficient data were available for smal1-wastewater-flow treatment unit processes and for recovered energy. These were, therefore, not addressed in this study. Data are currently being generated for these processes and we believe that both small flows and energy recovery equipment can be covered by future studies. The applicability of the CAPDET computer program was reviewed by calculating acquisition energies using the 1981 version of CAPDET. Results indicated that: o CAPDET calculates construction costs for 25 unit processes (1) using non-parametric equations. o CAPDET appears to adjust internally generated costs via use of adjustment factors of 10 to 15 percent. Task 2 consisted of using data obtained during Task 1 to develop a means to estimate both acquisition and operating energies of wastewater treatment units. 3.4 TASK 2 3.4.1 Operating Plant Energy Evaluation Methodology The energy survey method developed during this project is presented in the manual (Appendix A). This method was developed from data obtained in Task 1 (1), past energy audits of wastewater treatment plants furnished by EPA (2,3) and from University of Wisconsin course notes (4) instructing municipal officials in audit procedures for public facilities, including wastewater treatment plants. Charts, tables and methods of analysis were examined and synthesized to produce the manual. ------- 3.4.2 Energy Estimation Methodology A methodology was developed to calculate acquisition and operating energies which uses tables as a shortcut whenever possible. This methodology includes step by step instructions for use by both planning and operating personnel and is presented as a manual in Appendix A of this report. The methodology developed is divided into two parts: o Acquisition Energy and o Operating Energy. These are subdivided into simplified and detailed methods. Acquisition energies are those energies consumed in the development of the facility itself, including energies of materials and construction. Operating energies are those energies required to perform wastewater treatment once the plant is in place. 3.4.3 Acquisition Energy Calculation The acquisition energy estimation method used in the manual was discussed in the Task 1 Report (1). Design assumptions affecting acquisition energies are presented in Exhibit 3-1. Using detailed commodity estimates for each treatment unit process, commodity requirements are multiplied by appropriate unit embodied energies, their sum resulting in the treatment unit acquisition energy.' Acquisition energy tables were prepared using this " method and they are presented in the manual as a simplified method for the eleven wastewater treatment unit processes studied. The detailed method is also presented in the manual to estimate acquisition energies for unit processes lacking tables. 3.4.4 Operating Energy Calculation Operating energies were calculated for 50 unit processes during this project using data supplied by Culp/Wesner/Culp. Operating energy values for the following eight additional unit processes were obtained from an EPA report (5) Comminutors; Grit Removal (nonaerated); Pumping (Raw Wastewater); Lagoons (Aerated); Land Treatment (Slow Rate and Overland Flow); Microstraining; Overland Flow; and Sludge Transport (Truck). These operating energy requirements include power and fuel. Twenty one unit processes include embodied energy of consumable chemicals (Exhibit 3-2). Electrical energy values were converted using 3.413 MBtu/MWatt. Project operating energy requirements are based on design assumptions which include detention times, raw wastewater strength, treated wastewater analysis, et cetera. ------- Important engineering parameters (other than flow) which affect operating energies were identified. These are found in Exhibit 3-3. Equations were developed to adjust operating energy values for these parameters and to calculate energy use ranges. These were aggregated into tables for presentation in the energy estimation manual. The tables present: o Average or typical operating energy requirements for each waste- water treatment unit; o High and low extremes of operating energy; o Parameters affecting operating energies and values for typical, high, and low energy use designs; and o Equations for using these parameters to adjust the typical opera- ting energies. 3.4.5 Case Examples Twenty-five case examples were prepared to illustrate the use of the methodology developed during this study. Examples consist of three acquisition energy problems and 22 operating energy problems. Eleven operating energy examples were based on the literature and others were developed independently. Methods and use of tables was displayed in the case examples to clarify the steps needed to calculate energies. 3.5 TASK 3 Task 3 consisted of incorporation of client comments on the Task 2 Report and preparation of the Draft Final Report. Concurrent with conduct of Task 3 (as initially defined) we completed work on additional unit processes funded by a contract modification. Discussion of the additional processes is included in the Draft Final Report. ------- EXHIBIT 3-1 DESIGN PARAMETER VALUES FOR ACQUISITION ENERGIES UNIT PROCESS NAME Activated Sludge Basins Sub. Turbine Anaerobic Digesters Centrifugation Clarifiers Filtration Incinerators, Multiple Hearth Pure Oxygen Activated Sludge Con. Basins Dissol. System Cryo. Generation Rotating Biological Contactors Sludge Pumping Trickling Filters Vacuum Filtration UNITS 0.5 mgd HYDRAULIC CAPACITY 1.0 mgd 10 mgd 100 mgd cu ft 24 hp cu ft 12 gpm sq ft sq ft sq ft cu ft 3 ton/day ton/day sq ft 500 gpm cu ft 9 sq ft ,000 25 ,000 3 850 70 50 ,200 .45 .45 ,000 3 ,000 11 48,000 50 23,000 6 1,700 140 100 6,500 .85 .85 1,000,000 5 18,000 22 460,000 440 230,000 60 17,000 1,400 1,000 62,000 8.0 8.0 10,000,000 45 180,000 220 3,900,000 3,800 2,300,000 600 170,000 140,000 5,800 520,000 61 61 100,000,000 360 1,800,000 2,200 ------- EXHIBIT 3-2 UNIT PROCESSES INCLUDING EMBODIED ENERGY OF CONSUMABLE CHEMICALS IN OPERATING ENERGIES Alum Addition Lime Addition Chlorination Granular Activated Carbon Regeneration Biological Nitrification, Trickling Filter Biological Nitrification, Biological Nitrification, Centrifugal Dewatering, Centrifugal Dewatering, Dewatering, Thickening, Thickening, Thickening, Press Centrifugal Centrifugal Centrifugal Centrifugal Belt Filter RBC's Suspended Growth Basket Centrifuge Low G Solid Bowl Centrifuge High G Solid Bowl Centrifuge Basket Centrifuge Low G Solid Bowl Centrifuge High G Solid Bowl Centrifuge Diaphragm Filter Press Breakpoint'Chlorination SO Dechlorination Vacuum Filtration ------- EXHIBIT 3-3 IMPORTANT OPERATING ENERGY PARAMETERS Technology or Subtechnology Important Parameters Activated Sludge o Submerged Turbine o Pure Oxygen o Diffused Air o Mechanical Aeration Biological Nitrification o RBC's NaOH Feed System o Suspended Growth Aeration System NaOh Feed System and NaOH o Trickling Filter Recycle Pumping NaOH Feed System and NaOH Breakpoint Chlorination o Mixer o NaOH/Feed System Chemical Addition o Alum o Lime Chlorination Clarifiers Dechlorination (S07) Oxygen Transfer Eff. (Ibs. 02/hp.-hr.) Oxygen Transfer Eff. (Ibs. 0 /hp.-hr.) Type of 0^ Generation Oxygen Transfer Eff. (Ibs. 0 /hp.-hr.) Oxygen Transfer Eff. (Ibs. 0 /hp.-hr.) Hydraulic Loading Rate (gpd/sq ft) Dose (mg/L) Oxygen Transfer Efficiency (Ibs/hp-hr) Oxygen Requirement (Ibs/MG) Dose (mg/L) Recycle Ratio TDH (ft) Dose (mg/L) Detention time (min) Dose (MG/L) Dosage (mg/L) Dosage (mg/L) Dosage (mg/L) Overflow Rage (GPDPSF) Dose (mg/L) 10 ------- Digestion o Aerobic o Anaerobic Dissolved Air Floatation Filtration Granular Activated Carbon Lagoons o Aerated o Facultative Land Treatment o Slow Rate o Overland Flow Microstraining Ozonation Preliminary Treatment o Comminutors o Screens o Grit Removal Pumping o Raw Wastewater o In Plant o Sludge RBC's Sludge Quantity (Ibs/MG) Oxygen Transfer Eff. (Ibs. 09/hp. hr.) Sludge Quantity (Ibs/MG) Connected hp Solids Quantity (Ibs/MG) Loading Rate (Ibs/Sq ft-day) TDK. (Ft) TDK, (ft.) Connected hp Detention Time (days) TDH (Ft) TDK (Ft) Loading Rate (GPMPSF) Dose (mg/L) Connected Hp* Mechanical Cleaning * Detention Time (Min.) Connected Hp* TDH (Ft) TDH (Ft) TDH (Ft) Hydraulic Loading Rate (GPDPSF) 11 ------- Sludge Dewatering o Basket Centrifuge Polymer/Feed System o Low G and High G Solid Bowl Centrifuge Polymer/Feed System o Filter Press, Diaphragm Press Lime/Feed System Fed /Feed System o Filter Press, Belt Polymer/Feed System o Drying Beds o Vacuum Filter Sludge Incineration, Multiple Hearth Sludge Quantity (Ibs/MG) Sludge Concentration (% solids) Sludge Quantity (Ibs/MG) Dose (Ibs/ton) Sludge Quantity (Ibs/MG) Sludge Concentration (% solids) Sludge Quantity (Ibs/MG) Dose (Ibs/ton) Solids Quantity (Ibs/MG) Loading Rate (Ibs/Sq ft-hr) Dose (mg/L) Solids Quantity (Ibs/Sq ft-hr) Dose (mg/L) Solids Quantity (Ibs/Sq ft-hr) Sludge Quantity (Ibs)MG) Sludge Concentration (% Solids) Sludge Quantity (Ibs/MG) Dose (Ibs/ton) Solids Concentration (Percent) Sludge Quantity (Ibs/MG) Loading Rate (Ibs/hr/sq/Ft) Sludge Quantity (Ibs/MG) Dose (Ibs/ton) Solids Concentration (Percent) Sludge Thickening o Basket Centrifuge Polymer/Feed system o Low G and High G Solid Bowl Centrifuge Polymer/Feed System o Gravity o Dissolved Air Flotation Sludge Quantity (Ibs/MG) Sludge Concentration (% solids) Sludge Quantity (Ibs/MG) Sludge Quantity (Ibs/MG) Sludge Concentration (% solids) Sludge Quantity (Ibs/MG) Loading Rate (Ibs/Sq ft) Sludge Quantity (Ibs/MG) Solids Quantity (Ibs/MG) Loading Rate (Ib/Sq ft-day) 12 ------- Sludge Transport Trickling Filters o Low Rate o High Rate, Rock Media o High Rate, Plastic Media Ultraviolet Light Disinfection Solids Concentration (Percent) Sludge Quantity (Ibs/MG) Distance (Mi.) None of Significance Recycle Ratio, TDH (Ft) Recycle Ratio, TDH (Ft) None of Significance * Not addressed in this report 13 ------- SECTION 4 RESULTS This section discusses the results of performance of this project, included are: o Method for surveying operating energy requirements of existing plants, o Methods for estimation of operating energies, o Methods for estimation of acquisition energies. 4.1 OPERATING PLANT ENERGY SURVEY METHOD The energy evaluation method developed in the course of this project is included in the manual presented in Appendix A. This manual enables operating plant personnel to examine and evaluate energy use by their operating plant. The method is divided into two portions: o Examination of motors, and o Examination of fuel consumption (applies to incinerators, process heat, etc.) The plant operator is instructed to divide the plant into subunits. Each subunit is then examined to count the motors and other fuel-using equipment. Subunit totals are then added and compared with the overall utility bill. Guidance is presented on measuring duty cycles to include intermittent operations. 4.2 OPERATING ENERGY ESTIMATION METHOD This section summarizes the methods developed for estimation of operating energy by wastewater treatment plant operating and planning personnel. The manual presented in Appendix A contains the result. These methods were developed for the unit processes presented in Exhibit 4-1. They use tables and adjustment procedures for important engineering parameters affecting the design of wastewater treatment plants including flow rate, size, pump head, detention time, etc. In addition, ranges of operating energy are provided in the manual for those cases where the design parameters have not been established or where rapid estimation is desired. 14 ------- 4.3 ACQUISITION ENERGY ESTIMATION METHOD This section summarizes the method developed for estimation of acquisition energy. The manual presented in Appendix A is the result. A method was developed using detailed plant designs to estimate the acquisition energies of various types of wastewater treatment unit processes. Tables were developed from that method for the unit processes listed in Exhibit 4-1. Procedures to adjust the acquisition energies for flow rates are described in the manual. In addition, the detailed method is presented so that other unit process acquisition energies can be estimated when detailed design information is available. 4.4 CASE EXAMPLES Twenty-five case examples were prepared to illustrate the use of the method- ology developed during this study. The titles of the case examples are pre- sented in Exhibit 4-2 and the case examples are presented in Appendix B. Examples consist of three acquisition energy problems and 22 operating energy problems. Eleven operating energy examples were obtained from the literature and 14 were prepared independently. 15 ------- EXHIBIT 4-1 A. ACQUISITION ENERGIES UNIT PROCESSES Activated Sludge Anaerobic Digesters Centrifugation Clarifiers Filtration Multiple Hearth Incineration Pure Oxygen Activated Sludge Rock Media Trickling Filter Rotating Biological Contactor Sludge Pumping Station Vacuum Filtration B. OPERATING ENERGY UNIT PROCESSES Activated Sludge Diffused Air, Coarse Bubble Diffused Air, Fine Bubble Mechanical Aeration Submerged Turbine Activated Sludge, Oxygen Breakpoint Chlorination Biological Nitrification Suspended Growth Trickling Filters RBC's Chemical Addition Alum Lime Chlorination Clarifiers Dechlorination (S02) Digestion Aerobic Anaerobic Filtration Granular Activated Carbon Regeneration Lagoons, Aerated Land Treatment Slow Rate Overland Flow Micros training Ozonation Preliminary Treatment Comminutors Grit Removal (Aerated) Grit Removal (Nonaerated) Screens Pumping In Plant Wastewater Sludge Rotating Biological Contactors Sludge Dewatering Basket Centrifuge Low G Solid Bowl Centrifuge High G Solid Bowl Centrifuge Filter Press - Diaphragm - Belt Drying Beds Sludge Incineration Multiple Hearth Sludge Thickening Basket Centrifuge Low G Solid Bowl Centrifuge High G Solid Bowl Centrifuge Gravity Thickening Dissolved Air Flotation Trickling Filters Low Rate, Rock Media High Rate, Plastic Media High Rate, Rock Media Super High Rate, Plastic Media Ultraviolet Light Disinfection 16 ------- SECTION 5 CONCLUSIONS AND RECOMMENDATIONS This section presents conclusions drawn during the performance of this project and recommendations for both EPA and operating personnel to use the methods developed during this task. These are presented below: 5.1 CONCLUSIONS The following conclusions were drawn from this study: o A simple energy survey of operating plants to estimate existing energy use can be performed by plant engineers, plant superinten- dents, etc. o Operating energies can be estimated using two methods: Simplified - using project-generated tables, and Detailed - using adjustment equations. o Acquisition energies can be estimated using two methods: Simplified - using project-generated tables, and Detailed - requiring detailed cost estimates. 5.2 RECOMMENDATIONS Recommendations are as follows: o The energy survey method should be used to estimate energy use in operating wastewater treatment (WWT) plants. o Our simplified acquisition energy estimation method may be used for the unit processes covered. o The detailed acquisition energy method must be used for other processes. o The simplified operating energy estimation may be used for most energy estimates. o The detailed operating energy estimation method may be used whenever more accurate estimates are needed and engineering parameters are available. 17 ------- o Estimation methods should not be extended outside the size range .0.5 - 100 MGD design flow. o Users should obtain engineering parametric data for cases under study whenever this data is available. 18 ------- SECTION 6 FUTURE WORK Future work on this project should include expansion of the methodology gen- erated in this report to include additional unit processes. Future work should also include validation of the modified CAPDET computer program for estimation of both acquisition and operating energies. Acquisition energies presented during this report were, based upon gross estimates of unit embodied energies produced by the University of California at Davis. These embodied energies are in turn based on material presented by the Center for Automatic Computation (CAC) of the University of Illinois using data gathered in 1968. Use of energy in manufacturing has altered greatly since that time, and these figures are likely to be high. Therefore, future work on this project should include a revalidation of the unit embodied energy figures used in our calculations. The methodology discussed in this report does not include small-flow unit processes (e.g., grinder pumps, septic tanks) as data were not available. This report also does not address recovered eaergy processes (such as digester gas combustion and incinerator heat recovery) as data were not available. These data are currently being generated and will be available in the near future. Therefore, future work should include analysis of small-flow unit and energy recovery processes when data are available. 19 ------- SECTION 7 REFERENCES 1. CARLTECH ASSOCIATES, "Energy In Municipal Wastewater Treatment — An Energy Audit Procedure and Supporting Database - Task 1 Report" Prepared under EPA Contract No. 68-01-6433 (March, 1982) 2. U.S. EPA Unpublished Draft Energy Audit Report - Kentucky Wastewater Treatment Plant (1982). 3. U.S. EPA Unpublished Draft Energy Audit Report - Florida Plant (1982). 4. University of Wisconsin, "Municipal Energy Conservation Manual," Prepared by the University of Wisconsin - Extension, Department of Engineering and Applied Science (1979). 5. G.M. Wesner et.al, Energy Conservation in Municipal Wastewater Treatment, MCD 32, Prepared under EPA Contract No. 68-03-2186, Task 9 (March 1978). 20 ------- |