BACKGROUND   DOCUMENT
        STANDARDS APPLICABLE TO OWNERS AND OPERATORS
    OP.HAZARDOUS WASTE TREATMENT, STORAGE, AND DISPOSAL
      FACILITIES UNDER RCRA, SUBTITLE C,  SECTION 3004
  TfSneral Facility Standards for Location of Facilities
          (40 CFR 264, Subpart B, Section 264.18)
This document (ms. 1941.34) provides background information
     and support for EPA's hazardous waste regulations
            U.S. ENVIRONMENTAL PROTECTION AGENCY
                     December 30, 1980

-------
                                   Contents


  I.    INTRODUCTION 	   1

 II.    RATIONALE FOR REGULATION 	   2

       A.    RCRA Authority and Mandate	   3

       B.    Damage Incidents  	   3

       C.    State Legislation and Regulation  	   5

            1.   Seismic Considerations 	   6

            2.   Endangered and threatened species
                   and their critical habitats  	   7

            3.   Floodplains  	   7

       D.    Related Federal Legislation and
              Regulation	10

            1.   Wetlands	10

            2.   Floodplains	11

            3.   Seismic considerations 	  11

       E.    Contacts with other Federal Agencies
              and Professionals	j.3

III.    RESPONSES TO COMMENTS ON THE PROPOSED
         REGULATIONS AND RATIONALE FOR THE
         FINAL REGULATIONS	  .  ,  .   .  15

       A.    Active Fault Zone	15

            1.   Summary of proposed standard 	  15

            2.   Rationale for proposed standard   	  16

            3.   Response to comments	16

                 a.   The definition of active fault
                      zone and the area affected by
                      the standard	16

                 b.   Design and construction of facility
                      to mitigate seismic considerations.  ...  20

                 c.   Basis for restricting facilities
                      in active fault zones   	  22

-------
          d.   Miscellaneous comments   .  .  .......   23

     4.   Rationale for the final
            regulation (§264.18{a))   ..........   24

          a.   Fault Displacement and Associated
                 Deformation ............  •  •   26

          b.   Ground Motion ..............   46

          c.   Ground Failure  .............   49

     5.   Summary of the seismic regulation   ......   52

B.   Regulatory Floodway ................   53

     1.   Summary of proposed standard
            (250.43-l(b) )  ...............   53

     2.   Rationale for proposed standard   .......   53

     3.   Response to comments .............   54

          a.   The lack of a variance procedure   ....   54

          b.   The requirement for an analysis
               where regulatory floodways have
               not been designated ...........   55

          c.   Unavailability/inadequacy of
               regulatory floodway maps   ........   56

          d.   Regulation of location in
               regulatory floodways is
               inappropriate ..............   53

     4.   Rationale for deletion of the
            proposed standard  .............   58
C.   Coastal High Hazard Areas
     1.   Summary of proposed standard
            (§250.43-l(c)) 	  61

     2.   Rationale for proposed standard	gjL

     3.   Comments received  	    g2

     4.   Deferral of final action	g2

D.   Floodplains •	64
                                                     *  •
     1.   Summary of proposed standard
            (S250.43-l(d))
     2.   Rationale for proposed standard   .......  54

-------
     3.    Response to comments	66

          a.    The definition of floodplain	66

          b.    Executive Order 11988 and
               WRC's Guidelines	66

          c.    Information utilized in mapping
               the 500-year flood and flood
               insurance maps	70

          d.    The impacts of the proposed
               standard	74

          e.    Suggested alternatives to
               the proposed standard 	  77

          f.    The variance to the proposed
               standard	84

          g.    The proposed special wastes .......  90

          h.    Miscellaneous comments  	 ....  93

     4.    Rationale for the floodplain regulation  ...  95

          a.    Hazards associated with
               location	95

          b.    The one-hundred-year flood  	  99

          c.    The standard	104

          d.    Definitions	 108

          e.    EPA policy and Executive
               Order 11988	109

          f.    The guidance manual	110

     5.    Summary of the floodplain regulation
            (§264.18(b)) 	 Ill

E.   Wetlands	112

     1.    Summary of proposed standard
            (§250.43-l(e)) 	 112

     2.    Rationale for proposed standard  	 112

     3.    Response to comments	114

          a.    The definition of wetlands	114
                          1*1
                          111

-------
          b.   The "NOTE" to the proposed stan-
               dard; NPDES and §404 permits
          c.   Executive Order 11990 ..........  125

          d.   Miscellaneous Comments  .........  127

     4.   Current status of regulating siting
            in wetlands  ................  129
          a
Values of wetlands	129
          b.   Potential damages to
               wetlands and consequences ........ 130

          c.   EPA policy  ....... .  ....... 132

          d.   Applicable existing programs
                 and deferral of regulation  ...... 133

F.   Endangered and Threatened Species
       and Critical Habitats .............. 136

     1 .   Summary of proposed standard
            (§250.43-l(f)) ............... 136

     2.   Rationale for proposed standard  ....... 136

     3.   Response to comments ............. 137

          a.   The Endangered Species Act  ....... 137

          b.   The phrase "to be likely" ........ 138

          c.   Protecting endangered species
               outside of their critical
               habitats
          d.   Locating in a critical habitat  ..... 139

     4.   Final disposition  ......... ..... 141

          a.   Potential damages

          b.   The Endangered Species Act
               and Part 122  ........
                               ............. 143

G.   Sole Source Aquifers  ..........
                                               '
                                                         ,.,
                                                         J.4O
     1.   Summary of proposed standard
            (S250.43-l(g))
     2.   Rationale for proposed standard  ......   146


                           iv

-------
     3.    Response to comments	147

          a.   The standard is too lenient	147

          b.   The standard is too stringent	151

          c.   Miscellaneous comments  .	153

     4.    Rationale for deletion of the
            proposed standard  	 154

          a.   Protection provided by
               facility standards  	 154

          b.   Inappropriate use of sole
               source aquifer designation  	 157

H.   Buffer Zone	159

     1.    Summary of proposed standard
            (§250.43-l(h) )	159

     2.    Rationale for proposed standard  	 159

     3.    Response to comments	160

          a.   Impact on existing facilities 	 160

          b.   Surrounding land use	163

          c.   Comments specific to facility
               type	165

          d.   Alternate suggestions for the
               length of the buffer zone	169

          e.   The "NOTE" to the standard	172

          f.   General comments  	 173

     4.    Rationale for deletion of the
            proposed standard  	 178

          a.   Ignitable, reactive, and
               incompatible wastes 	 179

          b.   Spills	182

          c.   Dissipation and control
               of discharges	183

          d.   Odors and noise	183

-------
IV.  RESPONSE TO COMMENTS ON RELATED  ISSUES	J.84

     A.   General Comments  	  184

          1.   Existing facilities  	  184

          2.   Geographical impact  	  185

          3.   Applicability	186

          4.   Degree of hazard	188

          5.   General site selection standards
               vs. specific operating and design
               standards	189

          6.   Hazardous waste vs. hazardous
               materials management 	  191

          7.   State/local regulation of
               facility location   	  191

          8.   Variances	  .  194

     B.   Miscellaneous comments   	  196

     C.   Additional Location  Standards 	  200

     D.   Permafrost Areas  	  204

          1.   Proposed approach to
               permafrost areas 	  204

          2.   Response to comments	204

          3.   Deferral of final action	206

V.   REGULATORY LANGUAGE  	  208

          §264.18 Location Standards  	  208

          Part 264, Appendix VI	

VI.  REFERENCES	
                                                   	•

          Technical Documents	
                                VI

-------
I.   INTRODUCTION




     On December 18, 1978 EPA proposed a comprehensive set of



regulations covering the management of hazardous wastes.  This



proposal included rules governing the location of hazardous waste




management facilities (40 CFR 250.43-1, General Site Selection



standards; 43 FR 59000).



     In May, 1980, the Agency promulgated standards governing the



management of hazardous wastes by existing facilities during the



interim status period (45 FR 33154 et seq.)  For any given facil-



ity, the interim status period extends from the effective date



of the regulations  (November 19, 1980 for most provisions) until



the receipt (or denial) of a permit.  Other than for direct sur-



veillance and enforcement, there is to be little direct interac-



tion between the Agency and the regulated community; i.e., the



Agency will not be  regularly reviewing designs, plans, operating



methods, or technical information concerning the facility.



Evaluating the adequacy of a facility is, properly, the subject



of the permitting process.



     The May, 1980  interim status standards do not include



regulations for general site selection.  Existing facilities,



which are the only ones eligible for interim status, have



already been sited and are usually in operation.  For a given



facility, any decision that it is not satisfactorily located can



have major repercussions, not only for the faciliy but for the



management of wastes in the area as a whole.  Such decisions



require careful study of the technical facts and the. opportunity




for the owner or operator and for the general public to present






                              - 1 -

-------
their views and to defand their positions.  Such reviews and



due process procedures are part of the permitting process and



cannot be readily accommodated during the interim status period.



     This document provides background information and support



for the general Location standards around which permits will be



granted.  It explains how the regulations have come to be written




as promulgated.



     This document is organized into six sections.  Following



this introduction the Agency presents (Section II) the reasons



why the regulation of site selection is important and necessary.



Section II also explores State and other regulatory precedents



and identifies some of the external sources of expertise who



assisted the Agency.  Next, in Section III, the Agency summarizes



the December, 1978 proposed regulations,  the rationale for them,



and public comments received on them.  These comments are then



analyzed and a rationale for the substance of each final require-



ment is presented.  Section IV analyzes and responds to comments



on related issues including whether and to what extent location



requirements should be different for new or existing facilities.



Complete final regulation language can be found in Section V.



Section VI contains the list of references.



II.  RATIONALE FOR REGULATION




     This section contains the reasons why the location of



hazardous waste management facilities is important and why the



Agency has chosen to develop regulations covering site selection.



Also,  in this section, the Agency explores how states and other



Federal agencies have regulated the location of facilities and






                              - 2 -

-------
how these regulations and legislation have served as a precedent



for the RCRA requirements.  This section also identifies non-



government experts who have assisted agency staff in exploring



issues and developing these final requirements.



     A.   RCRA Authority and Mandate



          In Section 3004 of Subtitle C of the Solid Waste Disposal



     Act, as amended by the Resource Conservation and Recovery



     Act  (RCRA) of 1976, (42 U.S.C. §§6901 et seq.), the Congress



     of the United States requires the Administrator of the U.S.



     Environmental Protection Agency (EPA) to promulgate regula-



     tions to establish such standards, for hazardous waste treat-



     ment, storage, and disposal facilities "as may be necessary



     to protect human health and the environment".



          EPA is to promulgate regulations specifying standards,



     which inter alia include requirements for -



               "the location, design, and construction of



               such hazardous waste treatment, disposal,



               or storage facilities,-" [emphasis added].



     The  Agency considers this language to be a specific mandate



     for  these regulations.



     B.   Damage Incidents



          Instances of past damages to human health and the



     environment are sometimes used as justification for standards



     which are designed to prevent the future occurance of such



     damages.  It was difficult to find examples of damages that



     were solely caused by the presence of a facility at a parti-



     cular location; usually careless waste management practices






                              - 3 -

-------
were the primary cause of trouble, though poor location often
contributed to the extent of damages.  In addition to damage
incidents, EPA used its best professional judgment to predict
potential damages that could occur due to locating in various
environmentally sensitive areas.  Many of the potential damages
are obvious, or they can be deduced from past damages to similar
structures.  For example, tank and lagoon dikes can be rup-
   •h
tured by seismic activity.  It is thus not wise to locate such
facilities near known faults.
     Structural damages resulting from recent earthquakes have
been extensively documented.  A three volume report on the
San Fernando, California earthquake of February 9, 1971
includes a detailed discussion of the damages to building
structures, utilities, transportation systems,  and storage
tanks.  The San Fernando earthquake is considered "moderate"
as it was assigned a rating of 6.6 on the Richter magnitude
scale.  (The great San Francisco earthquake of 1906 has been
assigned a Richter magnitude of 8.3.)
     Volume II of this report contains a detailed description
of the effects of the earthquake on steel and concrete storage
tanks.1  Because tanks are employed for treatment and storage
of hazardous waste, a discussion of damages to these units is
included here.  Although the tanks reported on were used to
store water, it is reasonable to assume that similar damages
would occur to tanks containing hazardous waste.
                         - 4 -

-------
     Common tank failures included buckling of the walls of
steel tanks, collapse of tank roofs, and separation of
connecting valves and fittings from tanks.  Other damages to
steel tanks included failure of riveted connections, displace-
ment of tanks from their foundations, floor deformation, dis-
lodging of an internal overflow pipe, failure of the weld
between the shell and floor plate, sloshing of water, and
rocking of tanks.  The weld failure between the shell and the
floor plate allowed water to empty from the tank which eroded
several cubic yards of earth from under, and adjacent to,
the tank.  The concrete foundation of one tank broke in two
because of the rocking of the filled tank and the differential
earth movement under the tank.  One cylindrical tank of rein-
forced concrete suffered cracking of the walls, and water
leaked from most of the cracks.
     There are however, several documented incidents involving
flooding of hazardous waste management facilities.  Summaries
of these incidents can be found on pages 96, 97, and 98 of this
document.  These incidents illustrate the need for either
locating outside of floodplains or designing facilities to
withstand flood waters.
C.   State Legislation and Regulation
     EPA reviewed the solid and hazardous waste management
legislation, regulations, and guidelines of several States
to ascertain the various approaches that were used by the
States to regulate the location of solid and hazardous waste
facilities and to determine what elements the States deemed

                         - 5 -

-------
     important to consider when siting hazardous and solid waste

     facii ities.

          1.   Seismic Considerations

               The Texas Technical Guideline on Site Selection

          and Evaluation (No. 2)2 suggests factors that should be

          taken into consideration when selecting the location of

          an industrial-solid waste disposal facility.  Active

          faults and high seismic risk zones are two factors

          included for consideration.

               Minnesota^ includes a provision in its hazardous

          waste facility location regulations which states that,

               "No person shall establish, construct, or
               operate a hazardous waste facility in a
               location where the topography, geology,
               hydrology, or soil is unsuitable for the
               protection of the groundwater and surface
               water."  [emphasis added]

               California regulations for land disposal4 at Class I

          disposal sites  prohibit siting over zones of active

          faulting (i.e., where evidence indicates that there may

          be movement in the disposal area along a fault trace

          during the active life of the site, which may be infinite

          in the case of some conservative toxic materials) or

          where other forms of geologic change (e.g., liquefaction

          due to seismic shocks, landslide,  and subsidence) would
* Class I disposal sites may receive all waste groups.  They must
  provide complete protection to ground and surface waters for
  all time so as to prevent hazard to public health and wiid£tfe
  resources.
                              - 6 -

-------
impair the competence of natural features or artificial

barriers which prevent continuity with usable waters.

2.   Endangered and threatened species and their
       critical habitats

     In selecting a disposal site that will pose the

least amount of threat to the environment, the Texas

Guidelines5 suggest that areas be chosen with a low

fauna and flora diversity.  Also included are suggestions

to avoid wildlife refuges, migration routes, and areas

of unique plant and/or animal communities.

     In New York State,6 related legislation illustrates

that effects on endangered and threatened species and

their habitats are considered important in determining

significant effects on the environment.  The (New York)

State Environmental Quality Review Act (SEQR) requires

that all state, regional, and local government agencies

determine whether actions that they directly undertake,

fund, or approve might have a significant effect on the

environment.  Specifically, one group of criteria are:

     "the removal or destruction of large quantities
     of vegetation or fauna; the substantial inter-
     ference with the movement of any resident or
     migratory fish or wildlife species; impacts on
     a threatened species of animal or plant or the
     habitat of such a species;"  (§617.11).

3.   Floodplains

     When selecting a disposal site, the Texas Guide-

lines 7 suggest that floodplains and fluvial terrace

deposits be avoided.
                    - 7 -

-------
                Minnesota8 prohibits hazardous waste facilities

           from locating in floodplains.
                                                                  q
                The Pennsylvania Solid Waste Rules and Regulations'

           prohibit sanitary landfills (§75.24), composting

           facilities (§75.34),  and Class III* construction and

           demolition waste disposal sites (§75.33) from locating

           in areas subject to flooding once in every 100 years

           (i.e.,  in the 100-year floodplain).

                The following regulations are less stringent in

           that they allow location in a flood zone provided that

           certain measures have been taken to prevent inundation

           of the facility.

                For Class II** construction and demolition waste

           disposal, Pennsylvania allows location in areas inundated

           more frequently than once every 100 years if the site is

           approved by the Department of Environmental Resources.

           Criteria for approval are: "types and volumes of wastes,

           methods of emplacement, flood protection, erosion control,

           and compatibility with land and water uses."  (§75.33)

                The Iowa Solid Waste Disposal Commission10 requires

           proposed sanitary landfills to submit a "plan" detailing
 * Class III - waste materials resulting from the construction or
   demolition of buildings and other structures which may include
   but are not limited to, wood,  plaster,  metals, asphaltic substances,
   and Class I and Class II wastes.  (§75.33(b))

** Class II - waste materials resulting from land clearing, grubbinq
   and excavations which may include trees,  brush,  stumps,  vegetative
   material, and Class I wastes.   (§75.33(b))
                               - 8 -

-------
various aspects of the facility's operation and expected



impact.  A landfill is granted a permit only if Its plan



is approved by the Commission.  A portion of the report



that must be submitted as part of the plan requires veri-



fication that the site is outside a floodplain or shore-




land unless proper engineering and sealing of the site



will render it acceptable, ajid that prior approval of



the Iowa Natural Resources Council and, where necessary,



the U.S. Army Corps of Engineers has I been obtained.



     New York11 prescribes that secure (solid waste)



land burial facilities must be located at least five



feet above a floodplain unless provisions have been



made to prevent the encroachment of flood waters.



     Oklahoma Industrial Waste Management Rules and



Regulations1^ state that, "No [industrial waste] disposal



site or processing facility located at an elevation of



less than two (2) feet above a one-hundred-year flood



elevation shall be granted a permit, unless in the



Department's [Department of Health] judgment adequate



flood control measures have been provided in the site



or facility design and construction.  Flood control



measures shall include protection against flooding to



at least two (2) feet above the one-hundred-year flood



elevation."  (§3.5)
                    — 9 —

-------
D.   Related Federal Legislation and Regulation



     1.    Wetlands



          To determine if the Section 404 and Section 402



     programs under the CWA adequately preserved and protected




     wetlands,  EPA reviewed regulations promulgated under



     those sections of the CWA.   In a statement of its



     General Regulatory Policies (33 CPR 320), the U.S. Army




     Corps of Engineers lists functions of wetlands that



     they consider important.  It is stated that each activity



     requiring a permit will be  evaluated to determine whether



     it  is primarily dependent on being located in, or in



     close proximity to, the aquatic environment and whether



     feasible alternative sites  are available.  The Corps



     also states that each wetland site will be evaluated



     with the recognition that it is part of a complete



     and interrelated wetland area.13




          The EPA Final Guidelines for the Specification of



     Disposal Sites for Dredged  or Fill Material are also



     part of the 404 program. These Guidelines are used to



     evaluate proposed sites for the disposal of dredged or



     fill material.  They contain thorough procedures for



     evaluating impacts of a discharge on human health or



     welfare, and the effects on municipal water supplies,



     plankton, fish, shellfish,  wildlife, and adjacent



     aquatic ecosystems.  Great  detail is also devoted to



     evaluating the effects of the discharge on the chemical



     and physical aspects of the wetland.






                         - 10 -

-------
     The NPDES (Section 402) permit program, administered



by EPA, sets effluent limitations for point source dis-



charges to waters of the United States.  The effluent




limitations are set in order to protect public water



supplies, populations of fish, shellfish, and wildlife,



and to permit recreational use of the water.  The Agency



believes that this program adequately protects human



health and the environment with respect to point source



discharges to wetlands.



2.   Floodplains



     The Federal Insurance Administration (FIA) of the



Federal Emergency Management Agency (FEMA) administers



the National Flood Insurance Program (NFIP), which makes



flood  insurance available (in participating communities)



to property owners at a reasonable cost, in return for



which  communities are required to carry out floodplain



management measures to protect lives and, reduce property



loss.14  This program has resulted in a National effort



to map floodplains and regulate floodplain development.



     EPA reviewed FIA's minimum requirements for com-



munities participating in the NFIP.1^  EPA could thereby




determine the scope and degree of restriction which is



applied to structures located in floodplains in communi-



ties participating in the NFIP.



3.   Seismic considerations



     EPA reviewed the seismic activity controls that the



Nuclear Regulatory Commission (NRC) uses in siting nuclear








                    - 11 -

-------
power plants and the Corps of Engineers uses in design4-n9

dams.16  Particularly helpful were two reports prepared by

the NRC:

(1)  U.S. NRC - Information Report.  Identification
     of Issues Pertaining to Seismic and Geologic Siting
     Regulation, Policy, and Practice for Nuclear Power
     Plants.  April 27, 1979.  SECY-79-300.

(2)  U.S. NRC.  Comparison of U.S. Federal Agencies
     Seismic, Geologic and Gee-technical Siting Regula-
     tions and Guidelines for Critical Structures.
     Presented at GSA Symposium:  Geological Informa-
     tion - Problems in Transfer from Scientist to
     Policy Maker, Toronto, Canada; October 26, 1978.

These publications allowed EPA to gain insight into how

other agencies regulate for faulting and vibratory

ground motion and the advantages and disadvantages of

their approaches.

     EPA also reviewed a preliminary draft of 10 CFR

Part 61, Disposal of Low-level Radioactive Waste and

Low-activity Bulk Solid Waste prepared by the NRC.  The

criteria for determining site suitability (§61.96),  state

that a disposal facility is not allowed to be located

in an area having a peak horizontal ground acceleration

of greater than 0.25g with a recurrence interval of less

than 500 years (note: a 500-year recurrence interval is

equivalent to a 90% probability that the ground accel-

eration will not be exceeded in 50 years).
                    - 12 -

-------
E.   Contacts with other Federal Agencies and Professionals



     In developing the final regulations, the Agency used a



number of sources in addition to the very valuable informa-



tion received by comment on the December, 1978 proposed regu-



lations.  There are, of course, a number of very excellent



reports, studies, and other documents on such subjects as



flooding and seismic activity and means of safeguarding



structures against them.  A list of those used extensively



can be found in the References and list of Technical Documents



(Section VI).  In addition, EPA used the expertise of some



specialists (e.g., hydrologists, professional engineers,



and geotechnical engineers).  Specifically, the Federal



Insurance Administration of the Federal Emergency Management



Agency provided EPA with information on how flood insurance



maps are prepared and the availability of flood insurance



maps, and answered technical questions for us.  Memoranda



of those meetings are in the Administrative Record for the



Location standards.  (See references 67 and 71.)



     In addition, a private consultant (Mr. Charles L. Taylor)



assisted EPA in developing the basis for the final standard



on seismically active areas.  Mr. Taylor is both a registered



geologist and engineering geologist in the states of Cali-



fornia and Oregon.  Working with Woodward-Clyde Consultants



in San Francisco, California, he has gained extensive exper-



ience in conducting, supervising, and managing geotechnical



investigations for a wide variety of projects.  He has been



involved in developing criteria and procedures to identify,






                         - 13 -

-------
evaluate, and classify fault activity, and is especially



experienced in the subject of ground deformation adjacent to



active fault traces.  He is presently involved in developing



and evaluating criteria for nuclear waste management.



Mr. Taylor also serves a number of public agencies in Northern




California.



     Before Mr. Taylor was enlisted to assist EPA with



seismic considerations, Agency staff periodically consulted



scientists at the U.S. Geological Survey in Denver,  Colorado



and the U.S. NRC in Bethesda,  Maryland.
                         - 14 -

-------
III.  RESPONSES TO COMMENTS ON THE PROPOSED REGULATIONS AND RATIONALE

      FOR THE FINAL REGULATIONS

      In December of 1978 (43 PR 59000) EPA proposed standards for

 the location of facilities in active fault zones, regulatory flood-

 ways, coastal high hazard areas, 500-year floodplains, wetlands,

 critical habitats of endangered and threatened species, recharge

 zones of sole source aquifers, and, for the location of active

 portions of facilities with respect to the facility's property line.

 The Agency received extensive comments on these proposed standards.

 In this Section, the Agency presents the results of analysis of

 these comments and supports the decisions made regarding the content

 of the final requirements.  This is done on a regulation-by-regulation

 basis in the sequence they appeared in the proposal.

      Each proposed requirement is first summarized and the rationale

 for it at the time of proposal is presented.  Then the comments

 received are summarized and analyzed, and finally the rationale

 is presented in support of the final regulation and the decisions

 made concerning it.  In the comment analysis section, paragraphs

 labeled "C:" summarize the comment, while those labeled "R:" con-

 tain the Agency's response.

      A.   Active Fault Zone

           1.   Summary of proposed standard (§250.43-l(a))

                The proposed standard prohibited all hazardous waste

           facilities from locating in an active fault zone.  "Active

           fault zone" was defined in proposed §250.4l(b)(2) as,

                "a land area which, according to the weight of
                geologic evidence, has a reasonable probability
                of being affected by movement along a fault to


                               - 15 -

-------
            the extent that a hazardous waste facility would
            be damaged and thereby pose a threat to human
            health and the environment."

       2.    Rationale for the proposed standard

            Movement of land areas adjacent to an active fault

       clearly poses a threat to the integrity of structures,

       which may lead to uncontrolled release of hazardous

       waste,  therefore constituting a danger to human health

       and the environment.  The Agency believed that there

       were no existing,  practicable engineering methods for

       design of a facility to assure structural integrity

       during a serious earthquake.   Therefore,  EPA proposed

       that no facility be allowed to locate in active fault

       zones.

       3.    Response to comments

            a.   The definition of active fault  zone and the

            area affected by the standard.

 Comment:         The definition of an active fault  zone is

            imprecise, thus making it difficult  for owners or

            operators to determine whether  their facilities

            are located in active fault zones.   Without a more

            precise definition, or additional guidance,  many

            widely different interpretations of  the standard

            are possible.

Response:         EPA agrees that the proposed definition was

            imprecise and that because of this,  the exact area

            affected by the standard would  be difficult to

            determine.  In the standard which EPA intends to


                           - 16 -

-------
               finalize the area affected by the standard  is

               precise:  the area within 200 feet of a Holocene

               fault.*

          C:        The definition is so encompassing that  it would

               include large areas of the western United States.

          R:        Areas within 200 feet of a Holocene fault

               will include a very small percentage of available

               land in the western United States.17

          C:        Magnitude and frequency should be specified

               in the definition of active fault zone.

          R:        Magnitude is important in assessing ground

               motion and displacement along a fault.  When EPA

               proposes a standard which addresses ground motion,

               magnitude will be considered.  EPA has made the

               judgment that all new facilities must be 200 feet

               from any Holocene fault in order to protect against

               damage due to displacement and deformation.  Frequency

               of recurrent activity has been considered by using

               the Holocene epoch as a basis for evaluating fault

               activity.  It is expected that younger faults have

               a shorter recurrence interval of displacement.18
* For the sake of brevity, in this document the term "Holocene
  fault" will be used to mean a fault which has had displacement
  in Holocene time.
                               - 17 -

-------
C:        The definition does not conform to the general



     interpretation of active fault zone which is, a



     fault along which there is evidence of movement or




     seismic activity during the past 10,000 to 20,000




     years.



R:        One of the reasons that EPA chose not to use




     the term active fault (zone) in the final standard



     is because a survey of past geologic literature




     shows that active fault (zone)  has been defined in



     many different ways.  Generally,  it was defined



     using geologic information available at the time,



     or a definition was tailored to the purpose of a



     particular project.^




          EPA believes that using a criterion of dis-



     placement within an identifiable period of geologic



     time will eliminate the confusion associated with



     using a term with many recognized meanings.



          However, the time frame suggested by the com-



     menter is largely in conformance with the Holocene



     epoch which represents about the last 11,000 years,



     although in some parts of the United States  the



     limits of the Holocene may range from 10,000 to



     15,000 years ago.




C:        The definition should only cover areas  having



     the potential for Richter Scale 7.0 or greater



     earthquakes (the commenter provided no information



     as to why this particular magnitude was selected).






                    - 18 -

-------
R:        The final standard will be directed towards



     the potential for surface faulting and not earth-



     quake ground motion.  The basis for using Richter



     magnitude 7.0 and greater earthquakes to identify



     significant faults (or fault zones) does not seem



     reasonable for a ground faulting standard since



     small magnitude earthquakes can cause damage to



     structures located near the epicenters.



C:        The definition should only cover areas that



     have been active during the last 11,000 years so



     that it will conform with the California Geologic



     Hazards Act's definition.



R:        The final standard is based on faults which



     have had displacement during Holocene time.  EPA



     realizes that this is consistent with the California



     Geologic Hazards Act's definition.  This consistency



     will help in implementing the standard as maps



     will be available for Holocene faults in California.



C:        An active fault zone should be qualitatively



     defined; for example, the United States Geological



     Survey (USGS) has defined zones for determining



     degree of seismic activity.  Facilities in the



     USGS's Zone 3 (the most active zone) should be



     screened; however, do not exclude all hazardous



     waste sites from this zone.



R:        EPA believes that reliance on a qualitative



     system is unnecessary because the actual location






                    - 19 -

-------
     of  faults  would  certainly be a variable in the

     screening  process.   Thus,  the end result would be

     the same as  that under  the seismic standard where

     the permit applicant is required to determine if

     there are  any Holocene  faults near the facility

     (specifically, within 200 feet of portions of the

     facility where treatment,  storage,  or disposal will

     be  conducted).   However,  the USGS's seismic risk map

     can be used  as a general  indicator of the location

     of  faulting  activity because it is based on historic

     seismic activity which  correlates strongly with dis-

     placements along Holocene faults.

     b-    Design  and  construction of facility to mitigate
            seismic considerations

C:        Facilities  should  be allowed to be located in

     active fault zones  if the facility is designed and

     constructed:

          to withstand the expected seismic activity of

          the area; in particular,  the fault zone slip-

          page  effects on a  facility.

          with  a  certain prescribed safety factor tailored

          to the  seismic activity of the area.

          so that hazardous  waste is not likely to escape

          and cause substantial hazard.   (This should be

          determined  using a case-by-case analysis.)

R:        At this time it is impracticable from economic,

     engineering, and architectural points of view to



                   - 20 -

-------
design a critical structure to withstand serious



damage under the stress of surface fault rupture.2^



EPA has therefore prohibited facilities from locating



within 200 feet of a Holocene fault because the



damaging effects of major fault displacement and



deformation associated with historical surface


           v&
faulting hag occurred within this width.



     EPA has learned that it is not appropriate



to use safety factors for designing structures to



withstand certain degrees of ground motion.  The



concept of using safety factors is becoming obso-



lete because is it difficult to achieve agreement



on what is an appropriate safety factor.21



     EPA has determined from available information



that significant gaps in the knowledge of how



hazardous waste facilities would be affected by



different ground motion parameters (e.g.,  accelera-



tion, velocity, significant duration) exist at this



time.  The state-of-the-practice is advanced enough



and acceptable procedures are available to design



and construct civil engineering structures to with-



stand earthquake shaking.  Although it is  assumed



that these procedures may be modified so that they



can be applied to units used to manage hazardous



waste, there are no commonly accepted "standards"



for design and construction of such units.








               - 21 -

-------
          EPA is not in agreement with the commentor

     that suggested a design and construction perfor-

     mance standard.  EPA. believes that ground motion,

     and displacement and deformation should be con-

     sidered separately because of their inherent

     differences.

     c.   Restricting facilities in active fault zones
            should be based on:

C:   -    the "degree of hazard" of the waste being

          treated, stored,  or disposed at the facility.

          the particular treatment,  storage and disposal

          method used by a facility.

     -    the probability that a certain magnitude of

          earthquake will occur.

R:        EPA has not developed a comprehensive Degree

     of Hazard system.  For a discussion of this issue,

     see the Degree of Hazard Background Document that

     accompanied the Phase I rules.

          With regard to ground motion,  EPA cannot deter-

     mine how to restrict facilities  based on the parti-

     cular waste management methods used at the facility

     because the differential effects of different ground

     motion parameters on the components (e.g., landfills,

     tanks, incinerators, etc.) of a  facility are not

     known.

          With regard to displacement and deformation,

     EPA has set a distance of 200 feet from a Holocene



                    - 22 -

-------
     fault as the set-back distance for all new facilities.



     It seems plausible to EPA however, that some facili-



     ties may be able to locate at some distance within



     200 feet from a Holocene fault and not pose a threat



     to human health and the environment in the event of



     fault displacement.  In the preamble to these rules,



     EPA requests comment on what may be appropriate set-



     back distances from Holocene faults for facilities



     which contain different operational units and,  if



     variable set-back distances would be justified on



     the basis of the nature and quantity of waste managed



     at the facility.  EPA also requests that commenters



     specify their reasoning and justify distances which



     are suggested with technical data to the degree



     possible.



          Probabilities of certain magnitudes of earth-



     quakes are not available for most regions in the



     U.S. where earthquakes commonly occur.  Beyond this



     problem, it would not be appropriate for EPA to



     specify a certain magnitude of earthquake because



     the damage caused by a certain magnitude of earth-



     quake is dependent upon the structures at a facility



     and the local geologic conditions.



     d.   Miscellaneous comments.



C:        The hazard posed by locating a facility in



     an active fault zone may be less than the hazard



     posed to the population along transportation routes





                    - 23 -

-------
     from generation sites in active fault zones to



     facilities located in "non-active fault zones".



R:        The seismic standard should not result in the



     transportation of wastes over long distances.  Trans-



     portation distance may increase by a few miles;



     however, EPA believes that minor increases in trans-



     portation are justified due to the hazards associated



     with locating within 200 feet of a Holocene fault.



     The rule does not affect existing facilities.



C:        Additional flexibility needs to be provided



     so that facilities will be allowed to locate in



     areas that are protected by structures outside the



     facility and not built or controlled by the operator.



R:        EPA knows of no structures that can be located



     outside a facility that would render a facility



     earthquake resistant.  Engineering methods to make



     a facility earthquake resistant are tied to the



     direct design, construction,  and operation of the



     structural components of a facility.



4.   Rationale for the final regulation (§264.l8(a))



     It cannot yet be claimed that there is only one



cause of all earthquakes.  A minor cause of earthquakes



is volcanic activity.  Some deeper earthquakes may perhaps



be related to sudden changes in rock properties due to



motion deep within the Earth's mantle.  However, most



destructive, shallow-focus earthquakes appear to be asso-



ciated with a sudden rupturing (faulting) of the Earth's





                    - 24 -

-------
crust.  (The crust is a rock layer of varying thickness,
ranging from 30 miles under continents to 3 miles under
oceans, which is found world-wide and is composed of
mainly basaltic and granitic rocks.)  The resulting earth-
quakes are caused by the sudden releases of accumulative
strain energy.  The rupture, or break, is called a fault
and is generally accompanied by displacement of blocks
either vertically or horizontally or both, on opposite
sides of the fracture.22
     Hazardous waste management facilities wtll be located
in areas of the United States which have been the sources
of historical earthquakes and which are expected to be
the sources of earthquakes in the future.23,24  since
some of these historical earthquakes resulted in damage
to existing structues there is also the potential for
damage to hazardouos waste facilities.  The damage may
or may not be of consequence to the performance of the
facility.  Historical damage to structures has been
associated with displacement and deformation along
faults, strong ground motion (shaking), and ground (or
soil) failure.  Therefore, in locating hazardous waste
management facilities in areas which have been subject
to historical earthquakes, consideration should be given
to the potential for surface faulting, ground motion,
and ground failure.
                     - 25 -

-------
a.   Fault Displacement and Associated Deformation



     Faults are fractures along which rocks on one



side have been displaced with respect to those on



the other side.  Displacement is the relative move-



ment of any two sides of a fault measured in any



direction.  The displacement may be confined to the



subsurface or it may continue to the Earth's surface.



Geologists refer to the intersection of a fault



and the earth's surface as a fault trace.  Displace-



ments along a fault can be horizontal, vertical,



or a combination of both and can be on the order of



a few inches or feet to as much as 20 feet or more.25



The width of an individual fault trace is generally



on the order of several feet to several tens of



feet.26  There are three main types of faults and



each is characterized by a distinctive type of



movement and geometry.  (Figure 1)  Strike-slip



fault displacement is essentially a horizontal



lateral motion along a nearly vertical fault plane.



Structures placed across or in the vicinity of a



strike-slip fault can be subject to shortening



(compression), lengthening (extension), and distor-



tion (deformation) as well as displacement.  Normal-



slip fault displacement is primarily a vertical



(down drop) separation with one side of the fault



down in relation to the other side.  Structures



located across a normal-slip fault are generally





                - 26 -

-------
                        STRIKE-SLIP
  MAY HAVE A
  VERTICAL COMPONENT
  IN EITHER DIRECTION
                                  ^5^1
                                  f f f^m  w .     jfsi**£it
                                    •;^?$..^.
                                    ;S-o»-o:i:.<»!<
                                    LO^ >v^,.On.-.C
                       NORMAL-SLIP
MAY HAVE
STRIKE-SLIP
COMPONENT IN
EITHER DIRECTION
MAY HAVE
STRIKE-SLIP COMPONENT
IN EITHER DIRECTION
                         REVERSE-SLIP
                                 FIGURE /

                    THREE TYPES OF FAULT DISPLACEMENT
                                 - 27 -

-------
subjected to a horizontal lengthening across and



down the scarp (steep slope) produced by the faulting,



A reverse-slip fault is essentially a ver^tical



thrusting of the upper block over the lower block.



Structures located across reverse-slip faults are



generally subject to shortening (compression) across



the fault scarp.  Displacement of normal-slip and



reverse-slip faults also subjects structures that



are near the fault trace to distortion.27



     Seismically active areas usually do not contain



only one fault, but a number of faults grouped



together.  These faults are grouped within a well



defined width or zone.  Such a grouping is commonly



referred to as a "fault zone" since it consists of a



zone (a width) with several individual faults.



     M.G. Bonilla studied historic instances of



surface faulting in the continental United States



and adjacent parts of Mexico.  His study has provided



the most comprehensive data on the spatial relation-



ship of faults.  The following classification system



is based on his work.28




     The general fault zone usually can be divided



into a main fault zone, a branch fault zone, and a



secondary fault zone (Figure 2).  The spatial rela-




tionship of individual faults in the fault zone has



resulted in this classification system.  The main



fault zone contains the main fault (i.e., the fault






                - 28 -

-------
             an:
   Figure 2.  Zones of fault rupture
(I) main fault zoney (II) branch fault;
      and (III) secondary faults.
                    - 29 -

-------
with the greatest displacement, length, and continuity)



and closely associated faults.  The width of the main



zone of faulting has been reported to range up to



3,000 feet, but in most of the cases (71%) (reported



by Bonilla, 1967) the width was less than 1,600 feet



and for half (50%) the width was less than 550 feet.



(Figure 3)  Occasionally, faults diverge from and



extend well beyond the main zone of faults and are



referred to as branch faults.   Secondary faults are



completely separate spatially from the main fault



and sometimes form several hundred feet to a few miles



from the main fault.  Associated with main,  branch,



or secondary faults are often small, subsurface



faults evident as fault planes in a geologic investi-



gation.  These planes run parallel to the fault and



typically are considered a part of that fault.



     Adjacent to the fault rupture is commonly found



a zone of deformation.  This is an area where the



ground has been bent or warped as a consequence of



the two surface planes moving relative to one




another.  Surface deformation is frequently reported



within a zone of several tens  to several hundred



feet wide.3°'31  Structures located within this



zone are subject to distortion and are likely to be



subject to damage.
                - 30 -

-------




,



7



c



4
M

*



'


,




M



M JH
















....

*
it
•












• . - .






• "
lit
• •
M
A


'


....

w kl
• 41


^

u

" .
» joi jos 0.1 • o.s


V 11
o

«" M
a
Sl« Sit M
A • A
n
D





V- •
A

V

m.,
a




Hfl













IIITI»«














• O O liiiii-iiii lutu
• B O in — l lulu
A A A MiinioiiMi lull.
A ^ ^ itvitti item
. . 1 . . ..1 . ..!....

          IISTAICC rian ciiTEitiiit or HM» ieic T» ootti tost or ingicuce u«t (mitt)

          Figure 3.  Distance to outer edge of zone as
                      related to earthquake magnitude.

   Roman  numerals indicate,  for each of the  four  types of faults,
the greatest distance to the outer edge of the  main zone (I), the
zone of branch faults (II),  and the zone of  secondary faults (III)
                                - 31 -

-------
     Structures located across a fault at the time



of surface faulting will be subjected to fault dis-



placement.  The amount of and direction of displace-



ment and deformation will depend upon the type of



fault (strike-slip, normal-slip, or reverse-slip),



the amount of displacement (a few inches or feet to



as -much as 20 feet), the attitude of the fault plane,



and the surficial geology.33  At the present time it



is generally not practicable to design most structures



to withstand serious damage under the stress of sur-



face fault rupture.  Mitigating measures are available



for lifelines (pipelines, electrical lines, roads,



canals, etc.) and earthen structures (dams, embank-



ments, fills, etc.) which must cross a fault subject



to displacement.  The best protection,  however,  for



hazardous waste facilities is to avoid faults subject



to displacement.  Consequently, the regulation which



EPA intends to finalize prohibits location of portions



of a facility where treatment, storage, or disposal



of hazardous waste will be conducted within a distance



(200 feet) of the fault.  This distance typically



covers the zone of deformation.




     The purpose of the seismic regulation at




§264.18(a) is to protect facilities from the damage



which may occur due to displacement of a fault and



the associated deformation.  In this regulation EPA



intends for fault to be a generic term which includes






                - 32 -

-------
               fault traces, fault planes, faults which do not have

               surface expression, main faults, branch faults, and

               secondary faults.

                    EPA reviewed seismic criteria for the State of

               California when determining an exclusion width for

               hazardous waste management facilities.  The Alquist-

               Priolo Special Studies Zones Act of 1972 regulates

               development in California near Holocene faults.  In

               accordance with the Special Studies Zones Act, the

               California State Mining and Geology Board has

               established that:  (1) no structure for human occu-

               pancy will be permitted to be placed across a Holocene

               fault trace; and (2) no structures will be permitted

               within 50 feet of a Holocene fault unless an appro-

               priate geological investigation demonstrates an

               absence of (Holocene) branches of that fault.  The

               latter standard is intended to represent minimum

               criteria only, for all structures.  The Mining and

               Geology Board recommends that certain essential

               (e.g., schools and hospitals) or critical structures*

               should be subject to more restrictive criteria at

               the discretion of. cities and counties in Calif ornia. 35

                    California's rules for siting liquefied natural

               gas facilities prohibit liquefied natural gas tanks

               from being sited within 100 feet of a capable fault.36
* Examples of critical structures are dams, reservoirs, nuclear reac-
  tors, tall buildings, schools, prisons, and structures containing
  large quantities of potentially explosive or toxic materials.34


                               - 33 -

-------
     Recency of Faulting - EPA does delimit the time



period of last displacement of the fault; the seismic



standard specifies faults which have had displacement



in Holocene time.  The Holocene is a geologic time



period extending from approximately 11,000 years ago



to the present.  More specifically; it is the most



recent epoch of the Quaternary period.  Hoiocene



deposits are those formed within this time period,



during which climatic and sea level conditions, and



geomorphic processes have been similar to or are



ongoing with those now prevailing.



     The presence of faulting can be established



through physiographic features,  and stratigraphic and



structural relations within the Quaternary or Pre-



Quaternary deposits.  The recency of fault activity



is more difficult to establish in Quaternary or older



deposits.  In this case, ongoing or Holocene processes



superimposed upon the Quaternary and older deposits



must be identified and evaluated in terms of fault



related discontinuities.  Such processes mainly in-



clude soil formation and profile development, and



weathering, all processes in which some sort of



layering is developed.  In areas where layering is



not obvious, age dating of materials at various




depths can be carried out to establish time horizons.



     Where the above methods of fault identification



and activity assessment cannot be achieved, seismic








                - 34 -

-------
records and historic methods may help to identify
               to
fault areas and^establish    activity.37

     While many areas of the United States have

Holocene deposits and landforms of significant extent

such that evaluation of fault presence and activity

can be achieved, there are areas where Holocene

deposits and landforms are not well developed, as

in areas where glacial activity has stripped the

surficial ground cover and left highly resistant

rock such that inspection of Holocene deposits and

landforms for fault related features is hindered,

and the presence of potentially active or active

faults and the recency of possible fault movements

cannot with this means be adequately assessed.  In

situations of this sort, reference to seismic epi-

center plots and historic records must be utilized,

as well as identification and close examination of

possible fault related features expressed in Pleisto-

cene and older deposits.

     Where deposits or landforms of known Holocene

age are offset or displaced by faults, movement along

the fault is established to have occurred within

Holocene time.  As major geologic processes such as

faulting are long lived, lasting millions or tens

of millions of years, movement along faults within

the past 11,000 years can reasonably be considered

to represent a high potential for future activity


                - 35 -

-------
along a fault.38  For example, faults of Hoiocene



age, as a class, have a greater probability of



future activity than faults classified as Quaternary




age (last 2-3 million years).39



     In the proposed rule,  EPA used "active fault



zone" to delimit faults of concern.  "Active fault



zone" was defined as, "a land area .which, according



to the weight of geologic evidence, has a reasonable



probability of being affected by movement along a



fault to the extent that a hazardous waste facility



would be damaged and thereby pose a threat to human



health and the environment."



     EPA has decided not to use the terms "active



fault" and "active fault zone" because of the various



and sometimes conflicting definitions commonly in use



and cited in publications.40  Other disadvantages of



using the proposed definition are that it is difficult



to achieve agreement on the meaning of the phrases,



"weight of geologic evidence" and "reasonable proba-



bility", and there is no set of criteria that can be



used to demonstrate activity (or non activity) of a



fault.




     EPA decided to use Hoiocene faults as the group



of faults which are significant to hazardous waste



facilities based on the following criteria:



     (1)  The time period selected for defining the



          range of last fault movement should be






                - 36 -

-------
          long enough to provide a level of accep-



          table risk,



     (2)  Faulting within the time period should




          be recognized by surface features or sub-



          surface displacements,



     (3)  The time period can be related to a



          geological time with identifiable deposits



          or features which can be used to establish



          the time of last displacement (should the



          need arise).



     Faults which have had displacement in Holocene



time are the group of faults which are most widely



used in current engineering practice41'42 and for



evaluating the hazard of surface fault rupture.4^



It should additionally be noted that the hazard of



surface fault rupture is not only based on the



recency of activity but also on the recurrence of



faulting along existing faults.  With respect to



the latter basis, future faulting generally is



expected to recur along pre-existing faults.44



     The U.S. Army Corps of Engineers and the Nuclear



Regulatory Commission both use capable fault (in



general, movement within the last 35,000 years) to



define the recency of fault activity that concerns



them.  The harm and damage which may result from the



structural failure of a dam or nuclear reactor in



the event of fault displacement is, in most cases,






                - 37 -

-------
greater than that which would occur as a result of



damage to a hazardous waste facility.  The spread of



radiation is difficult, if not impossible, to contain.



Undoubtably there would be a great loss of life and



property if a large dam were to fail in the vicinity



of a large population center.



     In summary, EPA uses the  concept of "displacement



along Holocene faults" because it:



     Identifies a specific geological time frame



     (within about the last 11,000 years).



     Represents a specific, unique, and recognizable



     group of geological deposits.



     Represents an area of investigation,  research,



     and mapping by Federal and State agencies which



     will provide more specific data that  can be



     used for siting.



     Is a concept which can be demonstrated and



     agreed on within the geological profession.



     Existing Facilities - EPA intends to  exclude



existing facilities from the seismic standard on the



basis of concern about the impact of possible facility



closure on hazardous waste capacity, about the prac-



ticability of moving existing  facilities,  and, the



relative infrequency of seismic activity.   Since the



Agency was unable to include provisions in the



standard for designing facilities (unlike  the 100-



year floodplain standard where the facility can be





                - 38 -

-------
designed to prevent washout) to withstand the effects




of surface faulting, closure or moving would be the



only alternatives for existing facilities.  Moving




or closing existing facilities may be impractical in



some cases.  For example, on-site storage and treatment



facilities may be associated with existing manufac-



turing operations which must store or treat waste -to



at least some extent as an integral part of their



operations.  Movement or closure of these storage



facilities might result in movement or closure of



the manufacturing facility.  Off-site storage facil-



ities can be closed or moved, but this would impact



existing hazardous waste capacity, possibly in areas



where shortages already exist.  Since storage typically



is associated with other hazardous waste management



facilities, such as incinerators, the impact would



go beyond storage alone.  Should this standard be



applied to incinerators and land disposal facilities



in the future (as is likely when further standards



under Part 264 are promulgated for those facilities)



the impact on capacity would be more direct.  In the



case of existing landfills, closing a facility (with



the waste in place) would not significantly reduce



the potential for damage associated with faulting.



Finally, given the relative infrequency of seismic



activity, the Agency believes that there is a very low



potential for an earthquake occuring before most






                - 39 -

-------
existing facilities close at the end of their normal




lifetime.



     Nevertheless, EPA is not fully convinced that




the standard should not apply at least to existing



storage facilities (or incinerators) and has requested



comment on this issue in the preamble to these regu-



lations.  In particular, the Agency asked for comment



on the number of existing facilities currently



located in areas restricted by this standard, and



the impact this restriction would have on those



facilities and on capacity in the area where they



are located.  After reviewing this information the



Agency will reconsider whether this standard should



apply to existing facilities.



     Demonstration of Compliance (Part 122)  - The



owner or operator of a facility must demonstrate



compliance with the seismic standard as part of his



permit application.  For facilities that are located



in areas of the United States which are riot likely



to be subject to seismic activity the demonstration



will be a simple one.  Appendix VI to Part 264



contains a list of the political jurisdictions in



the United States in which owners or operators of



new facilities must demonstrate that there are no



Holocene faults within 200 feet of portions of the



facility where treatment, storage, or disposal of



hazardous waste will be conducted.  (See Section V






                - 40 -

-------
of this document.) If the political jurisdiction  in



which a facility is located is not listed in Appendix



VI as needing to comply, the owner or operator has



complied with the seismic standard.



     The list in Appendix VI is taken from the



Applied Technology Council's (ATC) map entitled,



"Map For Coefficient Aa".  (Figure 1-1, in Tentative



Provisions for the Development of Seismic Regulations



for Buildings.)45  This map is based on the earlier



work by Algermissen and Perkins (1976) which resulted



in a contour map of the United States which estimated



the maximum ground acceleration to be expected from



earthquakes occuring in the U.S.46  It was based pri-



marily upon the historic seismic record and represents



the best work done thus far on estimating the relative



earthquake hazard in the United States as a whole.



To a minor degree, data on the distribution of faults



was used.  The ATC modified this map by increasing



the scale and inserting the boundaries of counties



and other political jurisdictions.  The ATC map shows



seven zones of increasing ground acceleration.  The



political jurisdictions listed in Appendix VI are



those which are likely to be subject to an estimated



,10g of ground motion (specifically effective peak



acceleration).  Based on the work by Howard and others



(1978) and a review of other available data it appears



that the areas of the United States most likely to be





                - 41 -

-------
influenced by earthquakes with associated surface


faulting are within the .10g contour.47 In addition,


the regions in the Eastern United States which have


experienced reasonably large damaging earthquakes


in the past are outlined by the -10g contour (i.e.,


Charleston, S.C.; New Madrid, Mo.; New England).48


     EPA has attempted to minimize the cost of


compliance with the seismic standard in all cases,


but particularly for facilities where the risk of


seismic activity is very low.


     Because a demonstration of compliance with the


seismic standard is made as part of the permit appli-


cation, Part 122, Subpart B, §122.25(a) contains pro-


cedures which must be followed to adequately demon-


strate compliance with the standard.  The permit


applicant is provided with several alternative study


approaches because site-specific conditions will


vary considerably due to type of faults, geologic


structure of the area, and the existence of published


data.  The information developed during the study

       **
must be^sufficient quality to be acceptable to geolo-


gists experienced in identifying and evaluating


seismic activity.


     Study approaches may include a review of


published geological data, an aerial reconnaissance,


an analysis of aerial photographs, a geological recon-


naissance of the site, or trenching.  EPA intends to



                - 42 -

-------
require these studies to be carried out to different



distances from the facility; specifically, 3000 feet




and 5 miles.  These distances are generally accepted



within the geologic profession as distances which



must be investigated to conclusively make the demon-




strations required.  These distances are also based



on results of geological studies, the most imporant



of these is by M.G. Bonilla (1967) which analyzes



historic surface faulting in the continental United



States and adjacent parts of Mexico.  Bonilla has



indicated that the maximum distance from the center-



line of the main zone of surface faulting to the



outer edge of that zone is on the order of 3,000 feet.



Bonilla also found that some branch and secondary



faults do appear within the zone.49  Therefore, if



an area within 3,000 feet of the site is studied and



there is no evidence of Holocene faulting, EPA is



confident that the facility is not located within a



main fault zone where the large-scale damage due to



displacement and deformation occurs.



     The other study distance is five miles.  Regional



studies include a review of published geological data



and an aerial reconnaissance to cover an area within



a five mile radius of the site.  Five miles is speci-



fied here because surface faulting data (Bonilia,



1967) indicate that the majority (81%) of branch and




secondary faults associated with the main Holocene






                - 43 -

-------
fault zone occur within five miles from the centerline



of the main zone.  This distance is also accepted as



a regional study distance by the Nuclear Regulatory



Commission (NRC) for siting nuclear power plants50 and



by the State of California Public Utilities Commission



for siting of liquefied natural gas facilities.51



     The NRC specifies that sites within about five



miles of a surface capable fault greater than 1,000



feet in length are usually not suitable for a nuclear



power station.  In any case, extensive and detailed



geologic and seismic field studies and analyses'



should be conducted for such a proposed site.



     The level of effort which will be required to



make the demonstration to comply with the standard



will depend upon the amount of evidence which indi-



cates that Holocene faulting is likely or unlikely.



For example, if Holocene faults have been mapped



within one mile of the facility the owner or operator



may want to trench at the outset because, even though



the other procedures are followed through, the data



may indicate that trenching must be done to conclu-



sively make the demonstration.  On the other hand,



if no published data indicate faulting within (for



example) 5 to 10 miles of the site, an aerial recon-



naissance may be all that is required to sufficiently



demonstrate lack of faulting activity.  A guidance/



permitting manual for the Location standards win be






                - 44 -

-------
available shortly which will provide greater detail



on the study procedures identified in Part 122.



     Location of Holocene Faults - The United States



Geological Survey (USGS) and some State geological



agencies are identifying Holocene fault displacements



in present mapping programs, and mapping of Holocene



deposits is becoming more widespread..  Both of these



will be of benefit in locating acceptable waste facil-



ity sites.  The recent map by Howard and others^ _



Preliminary map of young faults in the United States



as a guide to possible fault activity - shows the parts



of the U.S. where Holocene faults have been identified:



the Western United States and the New Madrid area in



the Midwest.  At present, no Holocene faults have



been identified on the East Coast.



     The map by Howard and others provides some indi-



cation of where Holocene faults are likely to be found.



Geological studies will be necessary to assess the lo-



cation of any Holocene faults in the vicinity of a site.



This is expected to require review of available litera-



ture published by the USGS and State geological agencies,



with more site-specific studies in the Western United



States and the New Madrid area.  The growth faults along



the Gulf Coast (i.e., see Howard and others), are not



considered the source of earthquakes or likely to have



large displacements (if any) and therefore, should



not be considered in the context of seismicity.






                - 45 -

-------
     The State of California has the greatest number



of mapped Holocene faults.  California's Alquist-



Priolo Special Studies Zones Act of 1972 required,



among other things, the mapping of traces of some of



the major faults in California which have had displace-



ment in Holocene time.  The status of this mapping



program is contained in the California Division of



Mines and Geology's Special Publication 42 (Revised



March 1980), entitled Fault - Rupture Hazard Zones



in California by Earl W. Hart.



     Techniques for identifying Holocene faults will



be discussed in the guidance/permitting manual.



Scientific reports also exist which identify criteria



which can be used to recognize faults which may be



of Holocene age.  One good report is "State-of-the-



Art for Assessing Earthquake Hazards in the United



States" by David B. Slemmons (1977).53



b.   Ground Motion



     Seismic waves generated by an earthquake travel



in every direction away from the source and are



manifested in the vibrations of the material beneath



a structure and the structure itself.  Ground motion



pertains to the energy released by the earthquake,



expressed in terms of intensity and duration, as



transmitted through the ground.  Damage from strong



ground motion (shaking) is caused by the transmission



of earthquake vibrations from the ground into the



structure.  Ground motion is fundamentally different



                - 46 -

-------
than displacement and deformation for damage in the



former is only secondarily related to distance from



the fault.  Thus, the impact that ground motion has



upon structures is a function of the energy charac-



teristics of the ground located between the facility



and the epicenter of the earthquake, and the design



of the structure.  A facility may be located adjacent



to or hundreds of miles away from the displaced fault



and still be damaged by the resulting ground motion.



     There has been some attention given to the



design of earthquake resistant structures.  Perhaps



the most significant efforts to date have been by



the Nuclear Regulatory Commission, ^4 ancj -the study by



the Applied Technology Council entitled "Tentative



Provisions for the Development of Seismic Regulations



for Buildings".  However, few data exist that relate



ground motion dynamics to adequacy of engineering



design for various operational units at hazardous



waste facilities.  Thus, EPA is not presently pre-



pared to set a ground motion standard until it can



determine which components of ground motion (e.g.,



acceleration, velocity, significant duration) should



be the subject of design for different operational



units (e.g., tanks, surface impoundments, incinerators)



at facilities.  This requires an analysis of data on:



(1) probability of occurrence of different magnitudes



of earthquakes, (2) types of construction needed to






                - 47 -

-------
protect against the different levels of ground motion,


and (3) the feasibility and costs of such construction.

    OJ\                                         .
Such analysis is needed for each operational unit of«.


hazardous waste facility.  In order to resolve these


uncertainties, it is apparent that information from


the fields of geology and engineering which could be


utilized in designing hazardous waste facilities for


seismic considerations must be gathered and analyzed


by the engineering community.


     EPA has decided that a ground motion considera-


tion will not be included as part of the present


seismic standard because of the lack of knowledge in


the following four areas:


1.   Which components of ground motion should be


     used for the full range of operational units


     at facilities.


2.   The level of ground motion which is critical to

                   o?
     the full range^operational units at facilities.


3.   The designs which could be used to make a


     facility resistant to the pertinent component


     of and level of ground motion.


4.   The costs of earthquake resistant designs.


     EPA has invited the public to comment on these


areas of concern in the preamble to the Location


standards.
                - 48 -

-------
c.   Ground Failure



     Ground failure occurs when the energy charac-



teristics of an earthquake cause a particular piece



of ground to lose its qualities of support.  This



may occur in several different forms to include land-



sliding, liquefaction, settlement, and lurching.



While the cause of damage due to ground failure origi-



nates with ground motion, actual damage to a facility



results because of the failure of the ground in or



near the facility.  It is common for earthquake-



triggered landslides to occur as renewed movements



of deposits resulting from previous landslides.  Areas



subject to slope instability and strong earthquakes



could be subject to earthquake-triggered landslides.



     Liquefaction occurs when granular, essentially



conesionless soils undergo small to complete losses



of shear strength due to the buildup of fluid pres-



sures in the soil pore water caused by cyclic loading



during earthquakes.  When the loss in strength is low



to moderate, partial liquefaction may cause ground



settlement and associated ground cracking.  However,



when liquefaction is complete, the soil can behave



as a fluid, and catastrophic failures,  including



soil flows and landslides, have occurred as a result.



Partial liquefaction during strong ground shaking



may occur in dense to very dense cohensionless



soils,  complete liquefaction typically occurs only






                - 49 -

-------
in loose to medium dense cohesionless soils.



     Seismic settlement is also typically associated



with cohesionless soil deposits but can occur in



poorly placed or uncompacted man-made fill.  The



strong ground shaking that occurs during earthquakes



will densify loose granular soils.  When these soils



are above the groundwater table, their densification



and resulting ground subsidence will occur rapidly.



When located below the groundwater table, the pore



water pressures that have developed during the



shaking must begin to dissipate before a decrease in



soil volume can occur and, as a result,  settlement



occurs at a rate commensurate with the flow of water



from the cohesionless soil layer.



     Lurching may be generally defined as the develop-



ment of all types and sizes of irregular ground frac-



tures, cracks and fissures associated with ground



motion, settling, and the passage of surface wave



phases during earthquakes.  In this general sense,



ground cracks that occur as a result of liquefaction,



compaction, settlement, or lands!iding may be termed



lurch cracks.  More specifically, lurching involves



the seismically induced lateral movement and spreading



of ground toward a free face, together with the



development of associated tension cracks in the



ground behind the free face.
                - 50 -

-------
     There are simplified procedures for assessing



the potential for liquefaction on the basis of bore-



holes drilled on the site and the level of ground




acceleration expected at a given site.  The density



of the subsurface granular deposits and the ground



acceleration value are necessary items.



     The assessment of the potential for lurching



and earthquake induced landslides are generally not



subject to analytical procedures but are based on



historic observations.  They are commonly assessed



on the basis of performance of similar materials



during historical earthquakes.55



     As in the case of ground motion, EPA does not



have sufficient data relating ground failure risks



to hazardous waste facility siting and design.



Therefore, EPA does not at present include a ground



failure standard; although the Agency plans to



propose such a standard in the future.  To assist



EPA in this regard, the Agency has requested (in the



preamble) data on the various issues relating to a



ground failure standard to include:



(1)  Is it necessary to distinguish between hazardous



     waste facility types when setting a standard?



(2)  Should the standard involve a prohibition from



     locating facilities in areas of possible failure



     or should the standard allow location of



     facilities in such areas if properly designed?






                - 51 -

-------
     (3)  What types of ground and soil conditions are



          reasonably part of a standard?



     (4)  What types of tests would be definitive for



          demonstrating compliance?



5.   Summary of the seismic regulation (§264.l8(a))



     Portions of new facilities where treatment, storage,



or disposal of hazardous waste will be conducted must not



be located within 61 meters (200 feet) of a fault which



has had displacement in Holocene time.



     "Fault" means a fracture along which rocks on one



side have been displaced with respect to those on the



other side.



     "Displacement" means the relative movement of any



two sides of a fault measured in any direction.



     "Holocene" means the most recent epoch of the



Quarternary period, extending from the end of the



Pleistocene to the present.
                     -  52  -

-------
     B..   Regulatory Floodway

          ^*    Summary of the proposed standard (§250.43-l(b)

               The proposed standard prohibited hazardous waste

          facilities from locating in a regulatory floodway.

          "Regulatory floodway" was defined in proposed

          §250.41(b)(70)  as,

               "the channel of a river or other watercourse and
               the adjacent land areas that must be reserved in
               order to discharge the 100-year flood without
               cumulatively increasing the water surface eleva-
               tion more than a designated height".

          Regulatory floodways are selected by communities parti-

          cipating in the National Flood Insurance Program (NFIP)*

          within the limits imposed by FIA's minimum criteria.

          The proposed regulation required an owner or operator

          to obtain an analysis using FEMA-approved methods to

          determine whether the facility would be located within

          the regulatory floodway if such boundaries had in fact

          been mapped.

          2.   Rationale for the proposed standard

               Regulatory floodways are typically those portions

          of the 100-year floodplain which are frequently flooded

          and which becomes areas of major flood dynamics during

          large floods.  According to the Federal Insurance

          Administration of FEMA, in regulatory floodways "flood-

          waters exert their maximum pressures, erosion is greatly
* The NFIP is presently managed by the Federal Emergency Management
  Agency (FEMA) - Federal Insurance Administration (FIA).
                              - 53 -

-------
accelerated and loss potential is increased." (43 FR 6046,



February 10, 1978) If flood flow is impeded by structures



in this critical portion of the floodplain, flood heights



will increase causing an increase in the area flooded.



Hazardous waste facilities were therefore prohibited from



locating in regulatory floodways because occupying this



portion of the floodplain would result in greater flood



damages to others as well as increasing the probability



that hazardous waste would be released to the environment.




3.   Response to comments



     a.   The lack of a variance procedure.



C:        Because the standard is unfairly rigorous,



     particularly for existing facilities, exceptions



     to the standard should be allowed.  The following



     conditions for examption were suggested by the



     commenters:



     i.   existing facilities - if these facilities pose



          no threat to human health and the environment.



               if it can be demonstrated that no signi-



               ficant adverse effects would result.



    ii.   new and existing facilities - if the permit



          applicant can demonstrate that inundation of



          the facility would not significantly exacerbate



          the damage caused by flood waters.



   iii«   storage facilities within railroad yards located



          near major waters and facilities within chemical




          plants - if inundation of these facilities would






                    - 54 -

-------
          create no greater environmental damage than that


          which would occur by inundation of the railyard


          or chemical plant themselves.


    iv.   all facilities - if it can be demonstrated


          that the facility will not be inundated.


R:        The requirement controlling location in


     regulatory floodways has been dropped because the


     "no washout" flood standrd is deemed sufficiently
                            A

     stringent to provide the same level of protection.


     Inherent to the no washout standard is the right


     to locate in a 100-year floodplain (to include the


     regulatory floodway) provided that the owner or


     operator can satisfy the standard.  Of course no


     facility will be located within the regulatory


     floodway if the locality prohibits such development


     in these areas.  Since the National Flood Insurance


     Program requires communities in the program to


     restrict development within the regulatory floodway,


     new hazardous waste facilities would probably be


     barred from such areas.  The RCRA flood standard


     does not and is not intended to override any local


     prohibition of development in the regulatory


     floodway.  No standard, therefore, is required.


     b-   The requirement for an analysis where regula-

            tory floodways have not been designated.


C:   (i)  Verification by an EPA Administrator of the


     results of the analysis conducted by industry





                     - 55 -

-------
     should be required because this would assure that

     such results would be both carefully considered

     and subject to regulatory control.

    (ii)  The analysis should not be required if the

     owner or operator can demonstrate that the location

     of a facility is not subject to regulatory floodway

     designation.

   (iii)  Most of the designated regulatory floodways

     are located in urban areas; however,  oil and gas

     operations are usually located in rural areas.   In

     light of the number of wells drilled each year

     (48,000 in 1978) and the present oil shortage,

     analyzing almost ail drilling areas would be too

     costly and time-consuming.  Furthermore, an analysis

     would be unnecessary if EPA does not intend to

     prohibit drilling of an oil well in a regulatory

     floodway.

R:        The requirement controlling location in regu-

     latory floodways has been dropped for reasons stated

     above.

     c.   Unavaiiabilty/inadequacy of regulatory flood-
            way maps.

C:   (i)  The maps which have been developed often only

     take into consideration distance from waterways

     and do not factor in differences in elevation in

     determining the boundaries of the floodway.
                    -  56 -

-------
    (ii)   The maps are often faulty to the point that




     regulatory floodways have been designated in areas



     which are not even within the applicable floodplain.



   (iii)   In many areas of the country, the designation



     of regulatory floodways is not complete.  Further-



     more, few, if any, regulatory floodways were desig-



     nated when existing facilities were built.  Penalizing




     existing facilities is unnecessarily rigorous.



    (iv)   Neither the definition nor the regulation  pro-



     vide any guidance as to what precise areas would



     be or are regulatory floodways.  EPA should enable



     companies to obtain information on regulatory



     floodways that is pertinent to their facilities.



R:        The Federal Insurance Administration (FIA)



     maps regulatory floodways according to a defined



     set of procedures.  After FIA provides floodway-



     related data to a community, the community may



     increase the area which they choose to designate



     as the regulatory floodway in order to provide



     greater protection from flooding.  Thus, the extent



     and degree of protection which regulatory floodways



     provide differs among communities participating in



     the National Flood Insurance Program.  This is  one



     reason that the regulatory floodway would be an



     undesirable regulatory criterion for EPA to use.



          EPA agrees that mapping of floodways is far



     from complete.






                    - 57 -

-------
     d.   Regulation of location in regulatory floodways
            is inappropriate.

C:        The regulatory floodway defined by the FEMA

     was not developed as a national standard for the

     location of land disposal  facilities and therefore,

     it cannot be realistically utilized for this purpose,

R:        EPA disagrees with the commenter for the

     protection sought by a regulatory floodway provision

     is as applicable to FIA programs as it is to RCRA's

     directive of protection of human health arid the

     environment.  As explained above,  this protection

     is provided by the     floodplain standard coupled

     with any local bar on development.

4.   Rationale for deletion of  the proposed standard

     EPA has decided not to promulgate a final standard

for locating in regulatory floodways.   The information

below has prompted EPA to make  this decision:

     (1)  As of July 1979,  only 1,000 communities in the

     NFIP had maps with regulatory floodways delineated.

     At that time, approximately 16,000 communities were

     in the NFIP.  As a result,  it would be difficult

     to know whether most facilities were in compliance.

     (2)  Although FIA maps regulatory floodways, the

     community may extend the boundaries in order to

     provide greater flood protection to the community.

     Thus the community has the final word (provided

     that they are more stringent) in specifying the



                    - 58 -

-------
     extent of the regulatory floodway.  As a result,



     implementation would be non-uniform and non-equitable.



     (3)  Communities that have floodway maps are required



     to establish FIA1s minimum standards.  Section



     19l0.3(d)(3) of FIA's minimum standards states



     that a community must, "Prohibit encroachments...



     within the adopted regulatory fioodway that would



     result in any increase in flood levels within the



     community during the occurence of the base flood



     (100-year flood) discharge" (emphasis added).56



     These community standards are applied through a



     permitting system for all development in the 100-



     year floodplain; a hazardous waste facility would



     be subject to that permitting system.  As a result,



     a RCRA requirement would be redundant of the FIA



     standards.



     (4)  Regulatory floodways are always within the



     100-year floodplain.  A hazardous waste facility



     located in, or planning to locate in, a regulatory



     floodway would therefore be subject to the 100-



     year floodplain location standard.  Thus, a regu-



     latory floodway requirement would overlap signifi-



     cantly with the 100-year floodplain standard.



     EPA believes that regulating development in




floodways is probably best left up to communities which



have designated regulatory floodway since they must, at



a minimum, ensure that FIA's regulations are implemented.






                    - 59 -

-------
     EPA anticipates that problems might arise  if  a



standard was written for location of hazardous  waste




facilities in regulatory floodways.  Problems include



the unavailability of maps which would necessitate



hydraulic analyses to determine the extent of the



regulatory floodway; and then, the potential exists



for a community to designate a more extensive regulatory



flood at a later date.



     Because, according to FIA's minimum requirements,



any obstruction in a regulatory floodway which causes



any rise in the base flood (100-year flood) elevation



is prohibited, EPA anticipates that very few hazardous



waste facilities,  if any, would be permitted to locate



in the floodway.  Even fewer facilities would be allowed



to locate if the communities adopted more stringent



requirements than FIA.   Thus, FIA indirectly protects



human health and the environment from the potential



hazards of a hazardous  waste facility locating in a



regulatory floodway.  Further, EPA's 100-year floodplain



standard provides  sufficient protection against the



washout of hazardous waste in a floodway.
                    - 60 -

-------
C.   Coastal High Hazard Areas

     1.   Summary of the proposed standard  (§250.43-l(c))

          The proposed standard prohibited hazardous waste

     facilities from locating in a coastal high hazard area.

     However, a discretionary approval of a facility located

     in a coastal high hazard area was allowed if the facility

     owner or operator could demonstrate that measures had

     been taken to ensure that the facility would not be

     inundated by high velocity waters.  "Coastal high hazard

     area" was defined in proposed §250.41(b)(15) as,

          "the area subject to high velocity waters,
          including, but not limited to, hurricane
          wave wash or tsunamis as designated on Flood
          Insurance Rate Maps (FIRM) as zone VI-30".

     In cases where the coastal high hazard zone had not

     been designated by the Federal Emergency Management

     Aency (FEMA) the owner or operator was required to

     obtain an analysis using FEMA-approved methods to

     determine if the facility is located in a coastal high

     hazard area.

     2.   Rationale for the proposed standard

          According to FEMA, coastal high hazard areas are

     those portions of the 100-year floodplain "where flooding

     is not only most frequent and damaging, but where natural

     and beneficial values of the land and water interface

     are at their maximum."  (43 FR 6042, February  10, 1973)

     Because a facility located in these areas would not only

     be highly susceptible to flooding and wave action, but



                         - 61 -

-------
would also pose a potential threat to these ecologically



valuable areas, the intent of the proposed standard was



to prohibit facilities from locating in coastal high



hazard areas unless they could be engineered to provide




needed safety.



3.   Comments received



     Of the few comments received, several proposed



that the analysis required if the facility was located



in a non-designated area imposed an unnecessary additional



burden.  The standard should be limited to areas subject



to coastal high hazard designations.  A couple of



commenters proposed that the degree of hazard presented



by the facility be taken into account when determining



whether a facility need comply with the standard.  One



commenter went further and proposed that the standard



be entirely dropped because it, when linked to the 500-



year flood standard, would adversely affect a large



number of facilities, particularly in the Gulf Coast



area.  Only one commenter suggested that the note be



dropped and that there be an absolute ban against place-



ment of facilities in coastal high hazard areas.



4.   Deferral of final action



     EPA has deferred final action on a specific standard



for location in coastal areas because the floodplain



standard provides significant, if not complete, protec-



tion.  All coastal high hazard areas are within the



100-year floodplain and therefore siting in these areas








                    - 62  -

-------
will be subject to control under the 100-year floodplain



standard.  The 100-year flood in coastal areas is accom-



panied by some degree of wave action and this wave



action must be accounted for when the facility is




being designed, constructed, operated, and maintained



to prevent washout by a 100-year flood.



     With respect to a standard specifically on coastal



high hazard areas, EPA recognizes the problems presented



by incomplete mapping of coastal areas.  Of 1,465



coastal communities in the National Flood Insurance



Program, coastal high hazard areas have been mapped for



724 (July 1980 estimate by FEMA).  According to FEMA,



mapping of all coastal high hazard areas is to be



completed by 1983.



     For the above reasons, EPA has deferred promulga-



tion of a specific coastal high hazard standard.   In



the preamble to the Location standards, EPA requests



comment on what additional action - beyond the floodplain



standard - the Agency should take in order to protect



human health and the environment in coastal areas.



EPA will continue to investigate this problem with FEMA



and those in charge of implementing the Coastal Zone



Management Act, 16 U.S-C. 1451 et. seq.
                    - 63 -

-------
D.    Floodplains

     1.    Summary of the proposed standard (§250.43-l(d))

          The proposed standard prohibited the location of

     hazardous waste facilities in a 500-year fioodplain.

     However, the owner or operator of a facility could

     obtain a discretionary approval to locate in a 500-year

     fioodplain if he could demonstrate at the time of permit

     issuance that the facility would not be  inundated by a

     500-year flood.  The 500-year flood was  defined in

     proposed §250.41(b)(31) as,

          "a flood that has a 0.2 percent or  one in
          500 chance of recurring in any year.  In any
          given 500-year interval, such a flood may not
          occur, or more than one such flood  may occur."

     2.    Rationale for the proposed standard

          Disposal of hazardous waste in floodplains may

     have several significant adverse impacts:  (1) If not

     adequately protected from flooding, wastes may be inun-

     dated by water and flow from the site,  contaminating

     downstream waters; (2) Since floodplains generally have

     hydraulic connection to wetlands, surface water, and

     ground water, location of hazardous waste facilities

     in floodplains may result in leachate contamination of

     ground water; (3) Development in the fioodplain may

     restrict the flow of flood water, causing greater

     flooding upstream; and (4) Development in the fioodplain

     may reduce the size and effectiveness of the flood-flow

     retaining capacity of the fioodplain, which may cause



                          - 64 -

-------
a more rapid movement of flood waters downstream,

resulting in higher flood levels and greater flood

damages downstream.

     The Agency sought to make the standard consistent

with the U.S. Water Resources Council (WRC) Guidelines

for Implementing Executive Order 11988, "Floodplain

Management" (43 FR 6030-6055, February 10, 1978).  While

the guidelines use the 100-year floodplain as its basic

level of protection, a greater level of protection is

suggested for critical actions.  The WRC Guidelines define

"critical actions" as those actions for which even a

slight chance of flooding would be too great.  The

Guidelines further explain that a key question to ask

in determining whether an action is critical is:

     If flooded, would the proposed action create
     an added dimension to the disaster as could
     be the case for liquefied natural gas ter-
     minals and facilities producing and storing
     highly volatile, toxic, or water reactive
     materials?  (43 FR 6043)

Hazardous waste facilities seemed to meet this definition.

     The intent of the proposed standard was to prohibit

placement of facilities within the floodplain unless

the facility owner or operator could demonstrate that

the facility was engineered and located so as not to

be inundated by the 500-year flood.
                    - 65 -

-------
3.   Response to comments

     a.   The definition of floodplain

C:        The definition of "floodplain" should define

     the concept in general, and should not include

     reference to a specific frequency of occurence.

R:        EPA agrees that the term floodplain should be

     generally defined.  For purposes of regulation,

     however, a frequency must be stated so that the

     limits of the area subject to the requirement and

     the elevation of the flood can be determined.  In

     the floodplain standard, the Agency has defined

     the 100-year flood and the 100-year floodplain.

C:        The Agency's definition of floodplain is

     inconsistent with E.G. 11988.

R:        EPA's proposed definition was consistent with

     the E.O. except for an error in transcription.

     The word "areas" was erroneously substituted for

     "waters".

     b.   Executive Order 11988, "Floodplain Management"
            and WRC's Guidelines

C:        The E.O. makes no specific mention of a "500-

     year floodplain", and gives EPA no authority to

     regulate them.   The E.O. defines floodplains as

     areas subject to a "one percent or greater chance

     of flooding in any given year," i.e., a 100-year

     floodplain.  Therefore, the 100-year flood should

     be used as the criterion in the floodplain standard

     in order to be consistent with the terms of the E.O.


                    - 66 -

-------
R-        The commenter is correct in stating that E.G.



     11938 only refers to the base or 100-year flood.



     The final standard is consistent with the E.O. in



     specifying the 100-year floodplain as the minimum



     floodplain of concern.  There may be situations



     where greater protection is warranted.  EPA is



     separately considering whether a stricter standard


                                               fa
     is warranted for certain situations.  Such change
                                               A


     will be subject to a separate rulemaking procedure



     and therefore opportunity for public comment.



C:        The E.O. is directed exclusively to Federal



     Government agencies and not to private industry.



     If EPA wishes to apply the terms of the E.O.  to



     private industrial facilities by analogy,  it  should



     offer at least some plausible reason for doing so.



R:        EPA does not rely on the Executive Order to



     regulate private industrial facilities in flood



     prone areas.  The authority to so regulate is



     found in Section 3004 of RCRA.



          The Executive Order requires Federal agencies



     to include provisions for the evaluation and  con-



     sideration of flood hazards in the regulations



     and operating procedures for licenses, permits,



     and loan and grantin-aid programs it administers



     (Sec. 2(c)). EPA considers the floodplain standards



     as satisfying Section 3004 while being consistent



     with the Executive Order.




                    - 67 -

-------
C:        Reliance by EPA upon the Executive Order is



     subject to challenge because no EIS was prepared



     for the E.G. nor was any notice published or public



     hearings hald on the E.O. as mandated by Section 4



     of the Administrative procedures Act.  For these



     reasons, the E.O. is null and void,  and therefore,



     it has no binding effect upon any Federal agency



     in developing its regulations,  permit issuing



     procedures,  or policies.



R:        The Executive Order was not the basis for



     specifying floodplain protection as  discussed in



     response to  the first comment.



C:        Reliance by EPA upon WRC's Guidelines to imple-



     ment the Executive Order is  subject  to challenge



     because although the the Executive Order provides



     that Federal agencies must incorporate the existing



     procedures of the Unified National Program for



     Floodplain management of the WRC into their regu-



     latory structures (Section 2(d)),  the Executive



     Order does not give the WRC  authority to create



     general new  "guidelines" which go beyond the scope



     of the Executive Order (i.e.,  the Executive Order



     only refers  to the 100-year  floodplain).  WRC's



     authority under the E.O. is  limited  to "guidance"



     regarding the location of floodpiains where existing



     maps of the  Federal Insurance Administration do  not



     adequately delineate the location of a floodplain







                    - 68 -

-------
     (Section 2(a)(1)).




R:        The Agency's proposed 500-year floodplain



     standard was based on the need to protect human



     health and the environment from inundation of hazar-



     dous waste management facilities by floods.  Thus



     EPA was relying on its own authority and mandate



     under Section 3004 of RCRA and not on either the



     E.O. or WRC's Guidelines.  EPA believes it is imple-



     menting the spirit of both by attempting to protect



     human health and the environment from the conse-



     quences of inundation of hazardous waste management



     facilities by most floods.



C:        EPA has improperly applied the Guidelines to



     implement the E.O. because whether or not a Federal



     action is a "critical action" must be determined



     on a case-by-case basis-  To properly follow the



     requirements of the Guidelines, EPA should have



     structured the proposed rules so as to allow for



     a case-by-case determination of what constitutes



     a "critical action".



R:        The final standard requires a case-by-case



     evaluation to determine whether the no washout



     requirement has been satisfied.  As mentioned above,



     EPA is considering a separate rulemaking procedure



     to determine whether a requirement stricter than



     the 100-year flood standard should be imposed for



     special situations and if so how that would be






                    - 69 -

-------
     accomplished.  There is insufficient data to

     justify such a standard at this time.

C:        The E.O. contains no prohibition on the siting

     of facilities in 100-year floodplains.  Instead,

     it requires careful consideration of alternatives

     and minimization of potential harm,  both of which

     are consistent with limiting the coverage of this

     standard to 100-year floodplains.

R:        The proposed regulation was not an outright

     prohibition but included a variance  "note" allowing

     such location upon demonstration that inundation

     of the facility would not occur.

     c.   Information utilized in mapping the 500-year
            floodplain and flood insurance maps

C:        Because historical flood data in the United

     States varies from none to a maximum of 120 years,

     it is impossible to calculate,  statistically or

     technically, an accurate 500-year floodplain.  In

     other words, extrapolation to 500-years results in

     considerable uncertainty when estimating the height

     of inundation and the lateral extent of the 500-year

     flood.

R:        EPA agrees that there is considerable uncer-

     tainty involved in mapping the 500-year floodplain

     because available data must be extrapolated to 500

     years.  This one principle reason EPA has used the

     100-year flood as the final requirement.
                    - 70 -

-------
C:        Where extrapolation of data is used  in deter-



     mining the 500-year floodplain, there will be room



     for considerable debate by various sources and



     authorities.  Because of the unavailability of



     information, and the margin for debate, the more



     commonly accepted 100-year floodplain restriction



     should be used.



R:        EPA agrees that using the 500-year floodplain



     as the minimum floodplain of concern would have



     resulted in more controversy over the boundaries



     of the floodplain of concern.  Because the 100-year



     flood is the standard, the commenter's point is no



     longer of concern.



C:        The study and research required to determine



     a 500-year floodplain would, in most cases, be



     prohibitively costly, particularly in the Western



     United States where there is a dearth of rainfall



     and flood records.  The 100-year flood should be



     the standard flood.



R:        The amount of study and research required to



     determine a 500-year floodplain would probably not



     be much more than that required to determine a 100-



     year floodplain because the records available are



     finite.  However, the accuracy of the determination



     would suffer and the cost would be greater because



     of the degree that available data would have to be



     extrapolated to determine the 500-year floodplain.






                    - 71 -

-------
C:        EPA agrees that if all facilities were mride



     to comply with a 500-year floodplain requirement



     there would be a delay because 500-year floodplain



     maps are not widely available.  A 1979 estimate was



     that only 3,000 of the 16,876 communities partici-



     pating in the National Flood Insurance Program had



     Flood Rate Maps (FIRM) which delineated the 500-year




     floodplain.



C:        Maps which delineate the 500-year floodplain



     have not been developed for many sections of the



     country and will not be ready for 3-5 years.



     Nearly 90% of all FEMA flood maps are Flood Hazard



     Boundary Maps (FHBM), which delineate only the



     boundaries of the 100-year floodpiain.  A 100-year,



     or more frequent, floodplain should be established



     as the criterion.



R:        See response to previous comment.  One of the



     reasons that EPA has established the 100-year



     floodplain as the floodplain of concern is because



     maps which delineate the 100-year floodplain are



     available for more flood prone communities.



C:        The floodplain restriction should be deleted



     because no reliable generalized floodplain map



     currently exists for either the 100-year or 500-



     year floodpiain.




R:        The Flood Insurance Rate Maps (FIRM) produced



     by the Federal Insurance Administration are based






                    - 72 -

-------
     on the best available data and statistical techniques.



     These maps will be discussed later.  EPA believes



     that the 100-year floodplain criterion is necessary



     to protect human health and the environment.



C:        Using Flood Insurance Rate Maps is inappro-



     priate because they are not based on accurate,



     technically sound engineering surveys.



R:        FIRM'S are based on available historical infor-



     mation, hydrological analyses (to obtain flood flow



     frequency) and hydraulic analyses (to obtain flood



     elevations).  The FIRM'S are prepared by professional



     engineering firms which must follow a detailed



     guidance manual given to them by FIA.  They are the



     best and most reliable maps that are widely available.



C:        Because flood insurance maps generally do not



     delineate floodplains less than 200 feet wide, no



     information is available for small streams and tri-



     butaries.  This lack of information will make it



     extremely difficult to make siting decisions for



     new power plants and associated disposal facilities.



R:        EPA will require an owner or operator to deter-



     mine if his facility is located in the 100-year



     floodplain if the floodplain is less than 200 feet



     wide and not mapped.  Mapping procedures are suffi-



     ciently detailed by the Federal Insurance Administra-



     tion so that an owner or operator can determine if



     this facility is within a 100-year floodplain.







                     - 73 -

-------
C:        The method of predicting a 500-year flood



     should be stated and explained.



R:        EPA. agrees that some guidance should be given



     to owners or operators on how to determine a 100-



     year flood and floodplain.  A guidance/permitting




     manual for the Location standards will be available



     shortly after these regulations appear in the Federal



     Register.  This manual will provide information on



     how to determine the elevation of the 100-year flood.



     d.   The impacts of the proposed standard



C:        The standard will have a substantial impact on



     existing facilities that need to be near a source



     of water (e.g., NPDES treatment facilities that



     discharge to waters of the U.S.,  chemical plants



     and refineries, and vessel cleaning plants); most



     of them are in the 500-year floodplain.



          Possible consequences are that these facilities



     would:




          -    be unable to comply, even on a compliance



               schedule.




               experience a competitive disadvantage.



               have to sustain tremendous moving costs.



               have to close because of the monumental



               financial impact even if the facility was



               well designed and environmentally sound.



R:        EPA believes that the impacts on existing



     facilities that need to be near a source of water








                      -  74  -

-------
     will be greatly reduced because:  (1) the flood-



     plain of concern is now the 100-year floodplain,



     and (2) existing facilities need not comply until



     they are required to file an application for Part B



     of their RCRA permit.  At that time these facilities



     need not be moved.  They are to be modified if they



     do not comply with the standard as soon as possible



     in accordance with a compliance schedule.  Since all



     facilities must comply, there are no competitive



     advantages to any firm.



C:        The 500-year standard is overly restrictive by



     eliminating substantial sections of the country as



     potential sites for new facilities.  This result is



     not in the public interest in light of the shortage



     of suitable sites which meet the other Section 3004



     requirements.



R:        By reducing the floodplain of concern to the



     100-year floodplain, there will be less restriction



     on the siting of new facilities.  New facilities



     are not prohibited from locating in 100-year flood-



     plains in this rule, but rather are required to



     design their facility to prevent washout by the




     100-year flood.



C:        This standard is overly restrictive for Florida,



     It is estimated that as much as 80-90% of the State



     would be in the 500-year floodplain.  It is recom-



     mended that the 100-year floodplain be used because







                    - 75 -

-------
     it is mapped extensively by several agencies and




     data is available.  Others commented that the



     entire Houston-Galveston area, not to mention



     the rest of the Gulf Coast, is included within a



     500-year floodplain.  It should be noted that the



     nation's largest concentration of refineries and



     petro-chemical plants and the chlor-aikali industry



     is located in that area.  The 500-year requirement



     alone could preclude the use of many acceptable



     and safe sites for disposal of hazardous wastes.



R:        EPA agrees and has adopted the 100-year flood



     standard.  EPA is aware of the concentration of



     industry on the Gulf Coast.  The regulations now



     require that these existing facilities comply with



     the 100-year flood standard as soon as possible



     after applying for a RCRA permit or that the owner



     or operator satisfy the variance provision.



C:        The possibility of a 500-year flood is  very



     remote and does not justify the expense and  limi-



     tation placed on otherwise available sites.   Further-



     more, it seems to exceed the degree of" restriction



     necessary to protect human health and the environ-



     ment in the siting of new facilities.  The 100-year



     floodplain should be used.




R:        Available data presently only justifies the



     use of the 100-year standard.  This standard is



     widely used by other Federal agencies and states.57






                    - 76 -

-------
          There may be particular wastes or facility



     types or combinations thereof which justify a



     greater degree of protection.  Such situations



     are being considered in a separate ruiemaking.



     e.   Suggested alternatives to the proposed standard



C:        The 500-year floodplain should be used only



     where sufficient data exist.  In other areas, a



     minimum of a 100-year floodplain or a maximum of



     a 200-year floodplain should be used if sufficient



     information is available.



R:        EPA cannot be more or less stringent with respect



     to locating in floodplains simply on the basis of how



     much information is available on a floodplain.  Under



     this approach, identical facilities would be subject



     to different degrees of restriction depending upon



     how much information was available for a particular



     floodplain.  If the commenter intended that the



     floodplain of concern should be determined by both



     availability of data and the type of facility; EPA



     does not have sufficient data to tailor the standard



     to facility type.



C:        Because data for accurately determining the



     elevation of the 500-year flood are limited and



     because many industrialized areas are already within



     the 500-year floodplain, EPA should reduce the



     required floodplain elevation to a more reasonable
                     - 77 -

-------
     level taking into account available data and



     relative potential for disaster.



R:        EPA has adopted the 100-year floodplain for




     reasons already discussed above.



C:        Commenters stated that the 100-year floodplain



     should be used because: (l) flood level information



     is available and verified in many cases, (2) it



     would provide adequate protection,  (3)  it is econo-



     mically justifiable, (4) more land  would be available



     for siting, (5) the possibility of  a 500-year flood



     is remote, and (6) the 500-year fioodplain is not a



     recognized design tool.



R:        EPA agrees with many of these  comments.



     While the Agency recognizes that a  500-year standard



     would afford a higher level of protection,  at present



     the Agency does not have sufficient information that



     would justify a need for the added  level of protec-



     tion over that provided by the 100-year floodplain



     standard.  The 100-year flood is the most widely



     used standard in various Federal and state programs



     addressing the hazards associated with flooding.




     Of twenty four states that regulate floodplains,



     eighteen use the 100-year flood as  the regulatory




     standard.  The Federal Insurance Administration,



     and the U.S. Army Corps of Engineers have adopted



     the 100-year flood as their standard on which to




     base floodpiain management measures.58  Because of






                    - 78 -

-------
     this common use, engineering expertise in designing



     for the 100-year flood is available.



C:        EPA should specify the 100-year floodplain or



     the greatest flood on record, whichever is greater.



Rj        EPA believes that specifying the 100-year



     floodplain in all cases is a more reliable deter-



     mination and it ensures a greater degree of equality



     in regulating facilities.  The greatest flood on



     record is not a good tool to use in regulating



     because the degree of restriction would be almost



     solely dependent upon the number of years that



     elevations of floods have been recorded.



C:        The 50 to 100-year floodplains should be speci-



     fied in view of the protection afforded by flood



     control measures such as dikes, dams, and levees



     now in existence.



R:        One reason that the 100-year floodpiain was



     specified in the final rule is that it is used



     as the floodplain of concern in many states and



     other Federal agencies, and accordingly it is a



     common design tool which flood control measures



     now in existence can protect against.



C:        The 50-year floodplain should be used because



     sufficient data are available to accurately define



     the range of this area, and because it would be a



     more realistic design parameter.









                    - 79 -

-------
R:        EPA believes that the 100-year floodpiain



     standard will provide the minimum level protection



     to human health and the environment in the case of



     hazardous waste facilities.   A 50-year standard



     would result in an unacceptable frequency of



     flooding and in an unacceptable degree of damage



     in the event of a larger flood.



C:   The 10-year floodpiain should be used because;



     (i)  it can be readily determined,  and



    (ii)  here a true potential exists for environmental



          problems as the result of siting a new hazardous



          waste treatment,  storage,  or disposal facility.



R:        The response to the previous comment applies



     here.



C:        State agencies should determine floodpiain



     requirements based on scientifically justified



     and site-specific criteria.



R:        RCRA (§3004) requires that EPA promulgate



     regulations with respect to location in order to



     protect human health and the environment, and



     §3006 requires that States which receive final



     authorization must have requirements that are equi-



     valent to EPA's.  As stated before, EPA believes



     that the minimum floodpiain of concern cannot be



     less than the 100-year floodpiain.   Of course, a



     State may specify a more stringent requirement



     (e.g., a 200-year or a 500-year floodpiain) if it






                    - 80 -

-------
     believes that a greater degree of restriction is



     necessary to protect human health and the environ-



     ment in that State and if it believes the require-



     ment can be adequately implemented.



C:        EPA should specify that location will be



     restricted in an area subject to greater than a



     one percent chance of flooding in any given year.



     This requirement would allow for flood prevention



     measures to be taken into account whereas the



     proposed approach (i.e., specifying a certain



     year floodplain) did not.  For example, it is



     unclear whether the definition of a 500-year flood



     would change if flood prevention measures were to



     prevent its occurance.



R:        The definition of a 100-year or 500-year flood



     would not change if flood prevention methods were



     to "prevent" its occurrence but the area defined



     as the 100-year or 500-year floodplains would change,



     For example, if dikes or levees were constructed



     in an area which was defined to be within the 100-



     year floodplain and because of such construction



     the area was no longer susceptable to being flooded



     by the 100-year flood, that area would thereafter



     not be considered to be within the 100-year flood-




     plain.



C:        Floodplain restrictions should be developed




     according to facility type (i.e., land disposal







                    - 81 -

-------
     or thermal treatment facility)  taking into account



     type and amount of waste.   For  example,  secure



     landfills should never be  allowed to locate in a




     500-year floodplain.



R:        EPA believes that the 100-year floodplain is



     the minimum floodplain of  concern for all hazardous



     waste facilities.  In the  future, EPA may specify



     a less probably flood for  wastes or facility types



     that it deems require more protection in order to



     protect human health and the environment.  At



     present, data are not available to tailor the



     standard to particular facility types.



C:        The standard should specify the 100-year



     floodplain, and it should  only  apply to  facilities



     which manage very hazardous waste.  The  amount of



     water from a 500-year flood will have substantial



     dilution capability, such  that  most marginally



     hazardous waste will be rendered non-hazardous



     before it crosses the property  line.



R:        See response directly above.  In general, the



     dilution capacity of a 100-year flood is less than



     that of a 500-year flood.   However,  the  Agency



     has no data on the degree  wastes would be diluted



     and thereby be rendered innocuous before they




     cross the property line.  This  would be  a highly



     variable phenomenon which  does  not lend  itself to



     a universal regulation.






                    - 82 -

-------
C:        The standard should only apply to land dispo-



     sal facilities because the emplaced waste will be



     inundated eventually.




R:        See previous responses.



C:        A case-by-case evaluation of each facility



     should be undertaken so that, for example, on-site



     storage awaiting pickup or treatment (including



     incineration) is not unnecessarily forbidden.



R:        The permitting official will have to review



     each RCRA application with an understanding of



     the types of operational units at the facility in



     order to determine if the owner or operator is in



     compliance with the 100-year floodplain standard.



     No hazardous waste management activity is outright



     forbidden in the 100-year floodplain standard.
                     - 83  -

-------
     f.    The variance to the proposed standard



C:        The meaning of the term "inundated" is unclear,




     making the variance provision subject to various




     interpretations.



R:        The proposed standard would have allowed the




     placement of a facility within a 500-year flood-



     plain if the applicant would demonstrate that no



     inundation by flood waters would result.  Protec-



     tion from inundation is not the only method of pro-



     tecting the environment and the public from the



     effects of flooding.  Other measures involve flood



     proofing, which allows the waters to inundate the



     facility, but prevents the hazardous waste from



     leaving the facility.  Proper anchoring or elevation



     of containers may in fact be less "expensive than



     the construction of dikes or flood walls which the



     same level of protection would be provided.  Thus,



     the inundation provision was dropped in favor of



     the washout provision with the effect of expanding



     the means by which owners or operators could comply



     with the standard.




C:        Allowing facilities that would not be inun-



     dated to locate in the 500-year floodplain is not



     practical because:




          it is impossible to guarantee beyond all



          shadow of a doubt that a facility will not



          be flooded;






                    - 84 -

-------
          large volume sites would be required to con-



          struct prohibitively expensive dikes or



          berms, and




          it would preclude the use of sites that would



          only be inundated for a few hours with no



          lasting adverse impact.



     The commenter that supplied the last reason sug-



     gested that the "Note" be changed to require that



     the facility not be inundated by the 100-year



     flood, and so that any inundation by a 500-year



     flood will not cause a significant impact on the



     environment.



R:        EPA has concluded that sufficient flood tech-



     nologies exist to provide protection against



     flooding.  Thus, EPA has eliminated the presumption



     against locating within a fioodplain in favor of



     showing that adequate technologies are used to



     protect against washout.



          EPA has concluded that inundation of a site



     should not be the sole criterion.  Flood proofing



     is also effective where flood waters reach the



     facility, but due to adequate anchoring or eleva-



     tion of tanks and incinerators for example, the



     wastes are not washed out.  Washout, the standard



     adopted, can be satisfied either by preventing




     inundation or by flood proofing.
                    - 85 -

-------
     The difference between inundation and washout

of waste is illustrated in the Guidance Document

for the Classification of Solid Waste Disposal

Facilities;

     "A facility protected against inundation is
     not necessarily protected against washout of
     the waste.  A facility can be inundated with-
     out washing out, and washed out without being
     inundated.  The former occurs when waste is
     covered or held by vegetated soil, and the
     base flood inundates the surface but does not
     erode and wash out waste.  The latter can
     occur when the facility is diked or the waste
     covered up to the 100-year level, but the dike
     or covering is insufficient protection and the
     waste is eroded and carried away." 59

     If upstream flooding is a concern, the note

should be written to require an economic and

safety evaluation to demonstrate that excessive

cost prevents locating the facility elsewhere and

that the risk to human life is within acceptable

limits.

     Upstream flooding is always a concern in a

comprehensive floodplain management program.

However, in these rules, EPA has only considered

upstream flooding in an indirect way.  For example,

by preventing incinerators and containers from

being washed away, potential problems of blocking

the flow of flood waters is reduced.  EPA has left

direct regulation of concerns that determine the

extent of upstream flooding to local and State

governments.



               - 86 -

-------
     A variance to the standard should be granted



under each of the following conditions:



     if inundation of the facility would not sig-



     nificantly exacerbate the damage caused by



     the flood waters.




     if it can be shown that hazardous waste will



     not be released to the environment if the



     facility is flooded.



     if inundation of the facility will not cause a



     significant adverse impact on the environment.



-    if it can be demonstrated that applicable en-



     vironmental protection standards will not be



     violated.



     if inundation of the facility will not present



     an environmental or public health hazard either



     because of the inherent characteristics of



     the facility design or because of the nature



     of the contingency plans that will be acti-



     vated if flooding is threatened.



     if contaminated ground water conditions already




     exist.



     if the facility  is located on waterways that



     are flow or level controlled, such as the



     rivers in the TVA system.



     if inundation of an on-site facility will



     create no greater environmental damage than



     that which would occur by inundation of the







                - 87 -

-------
          plant of which the facility is a part.



          if adequate design criteria are present,



          based on site-specific analysis.



          if there is no practicable alternative to



          location in the floodplain, and if all prac-



          ticable measures have been taken to minimize



          harm to or within the floodplain (such an



          analysis is required in E.O.   11988).   In



          making these findings EPA should take  into



          account economic,  environmental,  and other



          pertinent factors.



R:        The prescriptive part of the  final standard,



     which requires that facilities within the 100-year



     floodplain must be designed,  constructed, and



     operated and maintained to prevent washout  of  any



     hazardous waste, is consistent with the comment



     that facilities should be allowed  to locate in



     the floodplain if it is shown that hazardous



     waste will not be released to the  environment  if



     the facility is flooded,  and with  the comment



     that suggested a variance based on a case-by-case



     analysis of the facility's design.



          EPA does not agree that a facility should be



     allowed to locate in a floodplain  if contaminated



     ground water conditions already exist.   EPA does



     not sanction further degradation of ground  water.



     Furthermore, hazardous waste in flood waters may







                    - 88 -

-------
adversely impact other facets of human health and




the environment such as life adjoining wetlands and




streams and potable groundwater some distance from



the facility.  Therefore, contaminated ground



water should not be a variance condition.



     Another issue concerns facilities that are



located or want to locate in floodplains alongside



waterways that are flow or level controlled.  If a



facility is located in a 100-year floodplain where



the stream or river is contained during the 100-year



flood by a system of dikes, levees, berms, revet-



ments, or other structures such that the natural



100-year floodplain is no longer subject to flooding



by the 100-year flood, then the facility is in



compliance with the final floodplain standard.



     The hazard presented by an on-site facility is



the same as that presented by an off-site facility.



Because an industrial plant may be flooded is no



justification for not requiring the hazardous



waste facility to be protected from flooding.



     EPA has chosen not to prohibit facilities from



locating in the 100-year floodplain if a practicable



alternative exists because EPA believes that if the



facility complies with the floodplain standard,



then human health and the environment are adequately




protected.
               - 89  -

-------
Comments specific to the proposed "special
  wastes"

     Summary of comments

     This standard is unreasonable for a lead

smelter furnace slag pile because there would

be no measurable damage to the environment due

to the low solubility of the slag material.

There should be an exemption for these and

other facilities, which, if flooded, would

not adversely affect human health arid the

environment.

     This standard is overly broad and inappro-

priate for new power plants and associated

disposal facilities.

     Special waste disposal facilities should

not have to comply with this standard because

it has been estimated that 64% of existing

electric utility generating stations are located

in floodplains.  In addition, it is expected

that Major Fuel Burning Installations (MFBI's)

are located in floodplains because, like elec-

tric utilities, they are dependent on water

resources for cooling, and often use coal

transported by barge.  Piping in water would

be costly and may result in additional impacts.

     Utility wastes such as fly ash and bottom

ash are not volatile, corrosive, reactive or



          - 90 -

-------
     toxic.  If a 500-year flood did occur, these



     wastes would not be of much concern.  For




     these reasons, this restriction is unreasonable.



°         In the Southwest, copper mining wastes



     are deposited in gulleys, ravines, and arroyos



     (flow areas) in desert regions.  During rain



     storms, run-off from the desert flows into



     these drainage areas.  It is impossible to



     pile this enormous amount of material on the



     ridges that separate these gulleys.



°         If metal mining wastes are deemed hazar-



     dous under the Act, most of that industry



     may have to cease operations because mining



     wastes are quite often located in or near



     natural stream drainages which may be in the



     500-year floodplain.



     Response to comments



     As a result of Congressional amendment to



the Solid Waste Disposal Act, regulation of many



proposed special wastes has been temporarily



deferred.  The effects of disposal of these



wastes on human health and the environment are



being studied.  The results of these studies



will determine if the wastes will be regulated




under Subtitle C.



     The deferred wastes include:



(1)  Fly ash waste, bottom ash waste, slag waste,







                - 91  -

-------
     and flue gas emission control waste generated



     primarily from the combustion of coal or other



     fossil fuels.



(2)  Solid waste from the extraction, beneficiation,



     and processing of ores and minerals, including



     phosphate rock and overburden from the mining




     of uranium ore.



(3)  Cement and kiln dust waste.



(4)  Drilling fluids, production waters, and other



     wastes associated with the exploration,



     development, or production of crude oil or



     natural gas or geothermal energy.



     In the interim, these wastes would be subject



to regulation only under applicable provisions of



other State and Federal laws.   However, Congress



has directed EPA to protect human health from



exposure to radioactive wastes which are used in



construction and land reclamation.  These solid



wastes include wastes from the extraction, bene-



ficiation, and processing of phosphate rock,



and overburden from the mining of uranium ore.



     With respect to the comment on existing



electric utility stations:  the proposed site



selection standards only applied to new sources




of utility waste and did not apply to existing



utility waste disposal facilities.  The commenter



misunderstood the proposed utility waste standards.







                - 92 -

-------
h.   Miscellaneous comments




     Pursuant to the Federal Water Pollution Con-



trol Act  (FWPCA) amendments of 1972, all industrial



wastewater treatment facilities must be designed



and constructed to withstand the 100-year flood.



EPA is reversing past policy which has resulted



in the expenditure of millions of dollars.



     The  FWPCA amendments of 1972 do not require



ail industrial wastewater treatment facilities to be



designed  and constructed to withstand the 100-year



flood.  However, the Flood Disaster Protection Act



of 1973 (Pub. Law 93-234, December 31, 1973) requires,



with certain exceptions, that grantees purchase flood



insurance on or after March 2, 1974, as a condition



of receiving any form of Federal assistance for con-



struction purposes.  Thus, receipt of construction



grants for municipal wastewater treatment facilities



is contingent upon compliance with applicable flood



insurance regulations (see 40 CFR 30).



     The  environmental damage created by the



flooding  of a facility by a 500-year flood will be



insignificant in relation to other environmental



damage caused by the flood waters from such a storm.



     Flooding of a facility by the 100-year flood



has the potential to cause environmental damage.



The actual damage is of course dependent upon



facility  specific wastes involved.






               - 93 -

-------
C:        EPA should consider the costs required for



     compliance against the environmental benefits



     achieved.  For example, petroleum industry disposal




     sites, and water treatment facilities appear to



     pose little risk to the environment while retro-



     fitting these facilities would cost billions.



R:        Since protecting facilities against the 100-year



     flood is widely used in other Federal programs and



     by many States, the costs presumably are not pro-




     hibited.  EPA, in the case of existing facilities,



     will provide a reasonable period of time during



     which an existing facility is to come into com-



     pliance.  Cost burden, presumably, will be taken



     into account setting the compliance schedule.



C:        Hazardous waste facilities can be designed




     and constructed in a manner that will protect



     human health and the environment even in the event



     of a 500-year flood.




R:        EPA agrees that technologies are available to



     protect against the 100-year flood.  The data are



     not as convincing for the 500-year flood because




     of the limited experience with such floods.




C:        The selection of the 500-year floodplain as a



     siting criterion appears arbitrary and capricious



     and it is not supported by data.




R:        EPA acknowledges that almost no data exist on



     the 500-year flood and its effects.  For this reason






                    - 94 -

-------
     EPA has modified the standard to the more commonly



     used 100-year flood.




C:        If wastes are properly stabilized or encap-



     sulated or neutralized, EPA should permit the use



     of environmentally sound disposal in the 500-year



     floodplain.




Rs        Facilities are allowed in 100-year flood plains



     if they can meet the no washout standard or the



     variance  (hazardous waste safely carried away).



     The standard does not allow a variance if the wastes



     are stabilized or neutralized.  Consideration will




     be given to such variations in a separate rulemaking



     which will be subject to public comment.



4.   Rationale for the floodplain regulation



     a.   Hazards associated with location



          Locating hazardous waste facilities in flood-



     plains may have several significant adverse effects



     on human health and the environment:  (1) wastes



     which are exposed to flood waters (e.g., in piles,



     surface impoundments) may produce more leachate,



     and be washed out and carried variable distances



     from the site, thus creating a potential for con-



     taminating surface water, ground water, aquatic life,




     and soils, or directly affecting human health by



     direct contact; (2) tanks, incinerators, and treat-



     ment units may not be capable of resisting the hydro-



     static and hydrodynamic loads (inducing the effects






                    - 95 -

-------
of buoyancy) and thus, the structure may be weakened

by seam failures and/or may be physically dislo-

cated; and (3) containers may be carried away by

flood waters, and opened or caused to leak, or

they may be handled at their new location by

persons who are not aware of the hazardous nature

of the contained waste.

     As discussed in Section II of this document

there are some documented instances of flood damage

to hazardous waste management facilities.  The

following documented incident concerns drums (i.e.,

containers) being carried away from a reclaiming

facility that is located in a 100-year floodplain.
     In July 1975 in Mount Hoiley, North Carolina,
drums containing wastes from a chemical reclamation
plant were washed downstream in Fites Creek by
heavy rains.  No fish kills were reported although
an unusual odor emanated from the creek.^0  The
plant subsequently went out of business and closed.
     The following damage incident is the subject

of a pending civil action.  The alleged damages

presented below are exacerbated by frequent flooding

of the site.
     The Brooklawn site, containing four or five
pits or ponds, is located in East Baton Rouge Parish,
Louisiana.  It contains a variety of chlorinated
hydrocarbons, organic chemicals of the anthracene/
phenanthracene groups, styrene tars, vinyl chloride,
lead, silver, and chromium.  In one sample taken
at the site, the total chlorinated hydrocarbon
organic fraction is almost 11,000 parts per million.
The site is low-lying, swampy, and is in the flood-
               - 96 -

-------
plain of the Bayou  Rouge  and  the  Mississippi River.
Floods regularly  inundate the site,  carrying the
stored wastes away  from the property.  These wastes
have escaped Into the  Bayou Baton Rouge, Devil's
Swamp, and the Mississippi River.  These chemicals
allegedly are destroying  and  have destroyed near
wildlife habitats,  especially marsh  and swamp lands,
making them uninhabitable for animal and vegetative
life.  Many animals, including fish, alligators,
turtles, cattle,  and birds have already been killed.
Considerable numbers of trees and other plants have
been killed.52
     The next two damage  incidents  involve pits

and lagoons that are  located in 100-year floodplains.

Both of these incidents could possibly have been

prevented if 2  feet of freeboard were maintained

or if a secondary containment system was available.

However, taken  together,  these four instances

illustrate the  potential  for harm to human health

and the environment when  a  facility is located in

a 100-year floodplain.


     In November 1970, sludge from an oil repro-
cessing plant in Douglassville, Pa. was released
to the Schuylkill River after heavy rains caused
one of the walls of a lagoon to break.  When
Hurricane Agnes flooded the Schuylkill in June of
1972, the waters flowed over the tops of the
lagoons, carrying more sludge to the river and
causing further damage downstream.  The trees and
waters of the river were  left coated with oil
following the incident.   Since June 1972, there
have been minor releases  of oil sludge to the
river due to flooding, but  nothing of the magni-
tude of the damage caused by Hurricane Agnes.°3


     An eleven-acre chemical waste site in
Lamarck, Texas  was the location of a waste over-
flow in 1961 due to heavy rains which accompanied
Hurricane Carla.  This site consists of approxi-
mately 7 pits (each 12 to 25 feet deep) with earthen


                - 97 -

-------
dikes.  The pits contained such industrial wastes
as tars, acids, chlorides, catalysts, lead and
mercury.  Heavy rainfall causes the pits to over-
flow and drain into ditches which connect with
Highland Bayou.  The waste site was closed in
1976, and cleanup efforts are underway.^4
     Locating any structure in a floodplain will

additionally (1) restrict the flow of flood

water usually causing greater flooding upstream,

and (2) reduce the natural valley storage of the

floodplain which may cause greater discharges

which in turn cause higher flood levels and greater

flood damages downstream.  Because these are

general concerns (i.e., they apply to all struc-

tures), which are dependant on the physical charac-

teristics of a particular channel and watershed,

and the degree of floodplain development, EPA

believes that it is logical for local laws and

zoning ordinances to regulate floodplain develop-

ment with respect to these general concerns.

Communities participating in the NFIP are required

to promulgate regulations which take into account

the degree of flood-flow restriction and the

retaining capacity of the floodplain.  The flood-

plain regulation in these Location standards is

tailored to preventing damages that may result if

a hazardous waste facility is located in a 100-year

floodplain.



               - 98 -

-------
b.   The One-Hundred-Year  Flood




     EPA. cited the minimum floodplain of concern



as the 500-year  floodplain in the proposed rule.



The numerous comments  received on this standard have



been answered individually in a previous section



of this document.  Commenters most  frequently



suggested that EPA use the 100-year floodplain as



the minimum floodplain of  concern.  Reasons given



were that; (1) flood level information is available



and verified in  many cases, and thus (2) there



would be less of a margin  for debate in boundary



determinations (compared to the 500-year flood-



plain), (3) it is consistent with the degree of



restriction necessary  to protect human health and



the environment, (4) more  land would be available



for siting new facilities,  (5) it is economically



justifiable, and (6) it is consistent with Executive



Order 11988.



     Other commenters  suggested that the 50 and



10-year floodplain be  specified.  The overriding



reasons given were that information is available



to accurately determine these floodplains and



that facilities  can be designed to  be protected



against that degree of flood hazard.  EPA has re-



jected these commenters' suggestions because EPA



believes that the 10 and 50-year floodplains repre-



sent too high a  probability that the land area






               - 99 -

-------
will be flooded, particularly in the case of



land disposal facilities where leachate production



is a concern.  Also, these higher probability



floodplains will be particularly hard hit in the



event of a larger flood.



     EPA has specified the 100-year floodplain as



the minimum floodplain of concern in the standard.



Comments on the proposed rule were the major



factor in EPA's decision.  EPA met with various



Federal Insurance Administration (FIA) employees



to investigate the validity of commenters1 con-



cerns and suggestions.  FIA was particularly



helpful with technical matters and in providing



us with information on the National Flood Insurance



Program (NFIP) and on the availability of flood-



plain maps.  Flood Hazard Boundary Maps (FHBM)



have been prepared for nearly all (e.g., except



for approximately five) communities that have been



identified as flood prone (i.e., any land area



susceptible to being inundated by water from any



source65) by FIA.66  The FHBM delineates the boun-



daries of the 100-year fioodplain but does not



give elevations.  There were approximately 20,238



communities identified as flood-prone as of July,



1980.67  if a 100-year flood level is not available



from another source, it can be determined from



the FHBM.  A qualified hydrologist will be able






              - 100 -

-------
to make this determination  with  less than a days

work or FIA can be contacted to  aid in determining

the 100-year flood elevation at  a particular loca-

tion.68  Of the 16,876  (estimate as of July, 1980)

communities that have been  accepted into the

National Flood Insurance  Program approximately

4,846 have Flood Insurance  Rate  Maps (FIRM)69 which

delineate the 100-year  floodplain with flood eleva-

tions.  Where these maps  are available, determining

if a facility is located  in a  100-year floodplain

should be a simple task.

     Because a uniform  set  of  maps is available

from FIA for nearly all flood  prone communities

the 100-year floodplain standard will be easier

to comply with and there  should  be fewer disputes

over boundary determinations.

     By specifying the  100-year  flood,  EPA is also

maintaining consistency with E.O. 11988, FIA, and

most States.  A booklet published by FIA on the

NFIP states that the 100-year  flood standard,


     "...is used by Federal agencies in the admin-
     istration of programs  as  they relate to the
     floodplains.  In addition,  the same standard
     is required either by  law or regulation in
     most States and is used in  the administration
     of State programs  in virtually every State."70


     Because the 100-year floodplain is the most

commonly used standard  in Federal and State program



              - 101 -

-------
the final standard should be easier to implement



as engineers will be familiar with the parameters



involved in designing, construction, or retrofitting



a facility.



     Until other data are presented to the Agency



indicating the need for a different minimum flood



level, the 100-year flood has been selected as



the minimum flood for this rule.  However, EPA does



not conclude that this level necessarily is suffi-



cient protection for human health and the environ-



ment for all hazardous waste management facility



situations.  EPA is currently considering issuance



of a proposed rule that would allow the Regional



Administrator to require more stringent standards



where circumstances would so warrant.  Such a change



though is not part of this rulemaking.



     FIA usually does not map floodplains that are



less than 200 feet wide; therefore, mapped informa-



tion would probably not be available for floodplains



less than 200 feet wide.  FIA does not  (normally) map



floodplains that are less than 200 feet wide for the



following reasons:



(1)  This width typically represents a  transition



     zone where flooding becomes a drainage problem



     and is controlled by culverts or sewers.



     Culverts and sewers are extremely expensive



     to evaluate hydraulically.






              - 102 -

-------
(2)  The hazard represented by such a straam



     flooding is typically not great because



     only shallow flooding is experienced.



(3)  Floodplains less than 200 feet wide are fre-



     quently subject to local zoning ordinances



     and easements.




(4)  Alteration of natural drainage systems and the



     watershed frequently occurs during development



     which would result in FIA having to frequently



     reevaluate the floodplain.71



     Where FIA omits an area because of the 200 foot



exclusion, the owner or operator will have to deter-



mine if his facility is within the 100-year flood-



plain.  FIA mapping procedures may be used to make



this determination.



     Another issue concerns the permanence of a



100-year floodplain.  In other words, "the 100-year



floodplain is not fixed; it is subject to changes



caused by future urban development and flood control



improvements, including physical structures and



land conservation practices, i.e., it may expand



or contract in the future."72  If the elevation of



the 100-year floodplain is reevaiuated such that a



facility which was previously outside of the 100-



year floodplain is now within the floodplain, the



owner or operator, probably when the permit expires



or upon notification from the permit issuer, will






              - 103 -

-------
  have to modify the facility to comply with the



  standard.   The owner or operator and the permitting



  authority can work out a reasonable time period to




  achieve compliance.



c.  The standard



       In developing a floodplain standard, EPA ruled



  out a prohibition of facilities in the 100-year flood-



  plain both because of the potential impacts of such a



  standard on new and existing facilities and because



  of the availability of techniques to protect the



  facility from the effects of floods.  The Agency



  believes that with proper safeguards and careful



  design, hazardous waste management facilities can



  be located acceptably in the 100-year floodplain.



       FIA's minimum requirements (24 C.F.R.



  §1910.3(c)(3)) for new construction and substantial



  improvements of any commercial, industrial, or



  other nonresidential structure in the 100-year



  floodplain specify that either the lowest floor,



  including basement, must be elevated to the level



  of the 100-year flood elevation; or, together with



  attendant utility and sanitary facilities, must:



  (l) be floodproofed so that below the 100-year




  flood level the structure is watertight with walls



  substantially impermeable to the passage of water?



  and (2) have structural components capable of



  resisting hydrostatic and hydrodynamic loads and






                - 104 -

-------
effects of buoyancy.^3




     EPA believes that FIA's requirements are



reasonable and that the general principles could



be applied to operational units of a hazardous



waste facility.  Owners or operators who can show



compliance with the FIA requirements should have



no difficulty obtaining a RCRA permit, unless



circumstances of waste type, location, and/or



design lead the Regional Administrator to a deci-



sion that an unacceptable risk may still exist.



EPA is leaving the regulation of structures that



are not used directly to manage hazardous waste



(e.g., offices, sanitary facilities) up to local



authorities.  Undoubtedly these structures will



have to conform to similar standards, especially



if the facility is located in a community that is



in the NFIP.



     The Army Corps of Engineers has specified the



use of dikes, covers, and flood walls to keep flood



waters away from facilities.  They have issued tech-



nical manuals on designed construction techniques



and methods for ascertaining the proper levels of



structural integrity for these retaining devices.74



Similarly the Nuclear Regulatory Commission has



thoroughly researched how one protects elements of



a nuclear facility from the hazards of flooding.



Thus, there is considerable practicable experience








              -  105  -

-------
with issues of appropriate flood prevention tech-



niques . 75



     Professionally trained engineers should be



versed in principles of hydrodynamics and hydro-



statics.  These areas of study are part of the



educational curriculum at engineering school.



Because of the education and practical experience



of engineers, EPA concludes that a 100-year flood



standard would not require novel engineering solu-



tions.  The state of the art is sufficient to



satisfy most engineering requirements.'^



     Based on inquiries with engineering professors



and professional engineers^? it appears that hazar-




dous waste facilities can be divided into two groups



with respect to methods which can be used to prevent



washout of waste, i.e., those which require flood



protection (not allowing flood waters to reach the



facility or active portions thereof) and those



which require flood proofing (allowing flood waters



to come into contact with structures but preventing



damage to them).  Facilities within the group which



require flood protection are landfills, surface



impoundments, land treatment, and waste piles.  The



most common method of flood protection is the con-



struction of levees around the facility.  The general



rule for the height of the levee is that is should



be the elevation of the flood which it is designed






              - 106 -

-------
for plus a safety factor of  3  feet.  The Army Corps



of Engineers has prepared an Engineer Manual




(EM 1110-2-1913) for Design  and Construction of



Levees.  It is important for levees to be designed



properly; for example, placing the levee material



on the ground surface without clearing and grubbing



could eventually result in voids being formed where



humas has decomposed.  Internal drainage networks



result which undermine the structural integrity of



the levee.  Structural components of facilities



such as tanks, containers, incinerators, and



structures utilized in thermal, chemical, physical,



and biological treatment can be flood proofed.



Of course, flood protection  measures also may be



needed at these facilities if waste is exposed at



the 100-year flood level; for example, in an



uncovered tank.  The Corps of Engineers has pro-



duced a general manual entitled, "Flood-Proofing



Regulations" which will be of use to owners or



operators and permitting officials.



     The Agency believes that it may be possible



for some owners or operators to institute manage-



ment procedures instead of design provisions,



which can adequately safeguard against washout of



wastes.  A provision has therefore been included



which allows owners or operators to demonstrate as



part of the permit application that they can safely






               - 107 -

-------
remove the waste before the area is flooded and



store the wastes in a permitted facility that is



not vulnerable to flood waters.  For example, this



might be done by keying waste removal procedures



to a certain river stage.  When the river approaches



flood stage, the drums can be loaded on trucks and



moved.  The owner or operator will have to demon-



strate that procedures are in effect and equipment



is available at all times to accomplish removal



in a short period of time.



     The final standard specifies the same opera-



tional and design standards for new and existing



facilities.  EPA believes that existing facilities



pose an equal hazard to human health and the



environment when located in the 100-year floodplain.



However, in order to decrease the impact of these



standards on existing facilities,  and to avoid



disruption of the waste management system in the



Region, existing facilities may be given a reason-



able period of time to comply with the standard



by means of a compliance schedule that is part of



their RCRA permit.



d.   Definitions




     The term "flood" is difficult to define.



"Perhaps it is enough to say that a condition of



flood exists when the discharge of a river cannot



be accommodated within the margins of its normal







              - 108  -

-------
channel,  so  that  the water spreads over adjoining
ground upon  which crops or forests are able to
flourish."78  In  the finai rulej  EpA ig deflning
the  "100-year  flood" as a flood which has  a one
percent  chance of being equalled  or exceeded in
any  given year.   This includes  the smaller size
but  more frequent floods (e.g., 50- and 20-year
floods)  and  excludes the larger but less frequent
flood  (e.g.,  500-year flood).   The height  of the
100-year flood is called the  100-year flood eleva-
tion.  It  is a statistical concept;  over a signifi-
cantly long  period of time, one would expect  this
flood elevation to be equalled  or exceeded once
in 100 years.   However,  it is recognized that  in
any  given  100-year interval,  the  100-year  flood
may  not  occur, or more than one such  flood may
occur.   The  land  flooded by this  size flood is
termed the "100-year floodpiain".
e.   EPA policy and Executive Order  11988
     In  the  proposed rule,  EPA  cited  Executive Order
11988 as the authority for prohibiting  facilities
from locating  in  the 500-year floodpiain (unless
the  demonstration in the "Note" was made).   Executive
Order 11988  differs from the wetlands Executive Order
in that  it "applies to federal agencies authorizing
private work in floodplains, as well  as to federal
activities and funding and work on  federal floodpiain
              - 109 -

-------
land".79  EPA policy essentially reiterates the



purpose of E.O. 11988 which is to avoid wherever




possible the long and short term impacts associated



with the occupancy and modification of floodplains.



However, given the shortage of hazardous waste



facilities, the fact that many industrial on-site




facilities are located within 100-year floodplains,



and the availability of flood prevention technologies,



the standard does not require an analysis of prac-



ticable alternatives.



f.    The guidance/permitting manual



     A guidance/permitting manual that has been



prepared to accompany the Location standards pro-



vides information as to where FIA flood maps can be



reviewed or copies obtained.  Other sources of



floodplain maps are listed such as the U.S. Geolo-



gical Survey and the U.S. Army Corps of Engineers.



If a facility owner or operator disputes a flood-



plain boundary or elevation that was previously



determined, procedures will be identified for an



owner or operator to follow in order to resolve



the disparity.



     Steps will also be outlined that an owner or



operator or a hydroiogist can follow to determine




the 100-year flood flow and then, the 100-year



flood elevation.
              - 110 -

-------
          Examples of how to prevent washout will be



     provided and technical design and construction



     manuals for use in this regard will be listed.




5.   Summary of the floodplain regulation (§264.l8(b))



     Hazardous waste facilities that are located within



the 100-year floodplain must be designed, constructed,



operated and maintained so as to prevent washout of



any hazardous waste by a 100-year flood.  This require-



ment can be waived if the owner or operator either



demonstrates that emergency procedures initiated at the



facility would result in the safe removal and storage



of the waste before flood waters reach the facility.



Existing facilities must be in compliance with this



standard within a reasonable period of time from the



date that a RCRA permit is issued.



     The following terms are defined in the standard:






"100-year flood" means a flood that has a one percent



chance of being equalled or exceeded in any given year.






"100-year floodplain" means any land area which is



subject to a one percent or greater chance of flooding




in any given year from any source.





"Washout" means the movement of hazardous waste from



the active portion of the facility as a result of




flooding.
                    -  Ill  -

-------
E.   Wetlands

     1.    Summary of proposed standard (§250.43-1(e))

          The proposed standard prohibited hazardous waste

     facilities from locating in a wetland.  An owner or

     operator of a facility could obtain a discretionary

     approval for locating a facility in wetlands if the

     facility was operated under a NPDES permit,  and if

     dredging or filling of a wetland was associated with

     the facility, that he obtained a permit under Section

     404 of the Clean Water Act (P.L. 95-217).

          In proposed §250.41(b)(100),  "Wetlands" were

     defined as,

          "those areas that are inundated or saturated by
          surface water or groundwater at a frequency and
          duration sufficient to support, and under normal
          circumstances do or would support, a  prevalence of
          vegetation typically adapted for life in saturated
          or seasonally saturated soil conditions."

     Swamps, marshes, bogs, sloughs,  potholes,  wet meadows,

     river outflows, mudflats, and natural ponds  were cited

     as examples of environments that would be  classified as

     "wetlands".

     2.    Rationale for the proposed  standard

          The nation's coastal and inland wetlands are vital

     natural resources of great hydrological, ecological,

     economic,  and social importance.  Wetlands provide

     natural flood and storm control, sediment  and erosion

     control, recharge of aquifers, natural purification of

     waters, and flow stabilization of streams  and rivers.




                        - 112 -

-------
Wetlands produce large quantities of nutrients which



support complex ecosystems extending into estuaries



and streams, well beyond the marshes and wetland areas.



Wetland habitats support fish,  shellfish, mammals,



waterfowl, and other wildlife  fauna and flora.  More-



over, wetlands are used in the  production of many



agricultural products  (food and fiber) and timber, as



well as for recreational, scientific, and cultural



pursuits.^0



     The alteration and destruction of the wetland



resource through draining, dredging, filling and other



means has had an adverse cumulative impact on wetlands



and other aquatic resources.   Recent estimates indicate



that between 30 and 40 percent  of the 127 million acres



of original wetlands in the lower 48 states have been



irrevocably destroyed.81  The  intent of the proposed



standard was to minimize the potential adverse effects



on wetlands that may be associated with hazardous waste




facilities.



     One objective of the Clean Water Act (CWA) is to



"restore and maintain the chemical, physical, and



biological integrity" of the waters of the United



States  (Section 101).  Because  some wetlands are part



of the waters of the United States, EPA and the Corps



of Engineers have promulgated  regulations to protect



these wetlands from the adverse impacts of discharges




of pollutants, and dredged or  fill material.






                   - 113 -

-------
     Section 402 regulations require that a NPDES per-



mit be obtained for the point source discharge of



pollutants into waters of the United States.  Since



hazardous wastes are pollutants, as defined by the CWA



(Sec. 502(6)), the discharge of hazardous waste from



a point source into wetlands requires a NPDES permit.



     Section 404 regulations require the Army Corps of



Engineers to issue permits pursuant to criteria issued



by EPA for the discharge of dredged or fill material



into waters of the United States.   The primary protec-



tion sought under Section 404 is a consideration of the



effects upon the wetland environment from the construction



and continued presence of a facility in a wetland.



3.   Response to Comments



     a.   The definition of wetlands



C:   i.   EPA should use the definition of wetlands -



          (1)  in E.O. 11990 because the same meaning



               was intended and E.O. 11990 is cited as



               the authority for wetland protection.



          (2)  that is used by the COE, as well as



               their method of designating value to



               wetlands developed pursuant to §404(b)



               of the Clean Water Act.



          (3)  used by the Department of Interior as




               well as their system for classifying



               wetlands.








                  - 114 -

-------
     ii.  Wetlands should be defined as:  "those areas



          which are inundated or saturated by surface



          or ground water at a frequency and duration



          sufficient to support, and that under normal



          circumstances do support, a prevalence of



          vegetation typically adapted for life and



          are capable of tolerating life in saturated



          soil conditions.  Wetlands generally include



          swamps, marshes, bogs and other periodically



          inundated or saturated areas, such as sloughs,



          prairie potholes, wet meadows, river overflow



          and river backwater areas, mud flats,  and



          natural ponds.  This term should be broadly



          construed to include those areas which in



          fact perform the wetland values described in



          40 C.F.R. §230.4-l(a)(l)(i) to (vi)."



R:        EPA1 s authority under RCRA is sufficient to



     justify promulgating standards to protect wetlands.



     Therefore, EPA does not rely on the Executive



     Order's authority, but does cite it as reflecting



     federal concern for preserving our wetlands.



          EPA believes that definitions should be consis-



     tent to the greatest degree possible between Federal



     agencies and particularly within EPA itself.   The



     definition of wetlands in Part 122 (45 FR 33424,



     May 19, 1980) is identical to the definition used



     by the Corps and EPA in implemeting Section 404.









                   - 115 -

-------
     It is also the same definition used by the §4004



     (RCRA)  program,  and it is substantively the same



     as the  definition in E.O. 11990.   It would be



     counter productive to unilaterally modify the



     definition of wetlands.   Therefore, when EPA



     promulgates a location standard for wetlands,



     in all  likelihood the definition  of wetlands in



     Part 122 will be employed.



          The Department of Interior's definition and



     wetlands classification system may be a good system



     for future use.   At this time however,  data are



     still being gathered and many areas have not been



     mapped.  When the inventory is complete, it should



     facilitate the management of wetlands and deepwater



     habitats on a sound, multiple-use basis.^2  DQI




     anticipates that all Federal agencies will adopt



     its classification system and maps when the inven-



     tory is complete.



C:        Maps which correspond with the proposed defi-



     nition  of "wetlands" are not available.  Identifying



     the boundaries of wetland areas places a difficult



     burden  on industry which could cause a delay in



     the approval of hundreds of disposal facilities.



R:        Since RCRA at present will rely on the Section



     404 permitting program,  there is  no added burden on



     the applicant for he must determine, irrespective of



     RCRA, whether the site is in a wetland for Section






                   - 116 -

-------
               404 purposes.  This being the case, the owner or

               operator of a facility would contact the appro-

               priate District Office of the Corps of Engineers

               for assistance in determining whether the site is

               in a wetland.

          C:        The proposed definition of "wetlands" is

               sweeping, and as such, it would include substantial

               land areas - almost the entire states of Florida

               and Louisiana - making it difficult to site

               disposal facilities in these and other states.

          Rs        The definition of wetlands used by EPA and the

               Corps in the Section 404 program does not contain

               the phrase "or would support" that was used in the

               proposed definition of wetlands.  Thus the Section

               404 program's definition is more precise than the

               proposed definition.

          C:        EPA should not consider all wetlands to be

               alike:

                    there are significant differences in the eco-

                    logical value of various types of wetlands

                    (e.g., freshwater and estuarine*);  different
*  The commenter stated that freshwater wetlands are able to re-
   ceive large volumes of nutrient-laden water because the water is
   dispersed over a large area, and the plant life is adapted to
   filtering nutrients, from the water.  However, inhabitants of
   estuarine-type wetlands must already cope with widely varying
   salinities.  When organic and industrial waste is discharged into
   these wetlands,  an additional stress is realized: bioaccumulation
   of  toxic substances.  The discharge may go downstream with the
   ebb tide; however, it returns with the natural flowage.


                             - 117 -

-------
          types of wetlands should be defined separately



          in the regulations and these differences



          should be reflected in the siting criteria.



          wetlands which contribute little toward wild-



          life protection or as  a nutrient source may



          be more valuable as disposal sites if they



          are near communities.   In light of the pending



          shortage of suitable land for disposal purposes



          the value of a wetland,  and hence its suita-



          bility as a disposal site,  should be determined



          by the permit writer on a case-by-case basis.



R:        In determinations made under Section 404,  the



     ecological value of wetlands is considered.  In



     cases where the Section 404 permitting process  has



     been completed.  EPA believes that the value of a



     particular wetland has been carefully considered.



          The RCRA program of EPA is concerned about



     wetlands which are not part of "waters of the United



     States" and therefore not subject to CWA jurisdiction.



     EPA is deferring specific regulation of siting  in



     wetlands until the exact scope of the CWA is deter-



     mined and other related problems are solved.



          EPA cannot make sweeping judgements about  the



     values of one type of wetland over another.  Until



     proven otherwise, all wetlands are assumed to be



     valuable and worth preserving.
                   - 118 -

-------
     b.   The "NOTE" to the  proposed  standard; NPDES
            and §404 permits         ~~  "          •


C:        Because the  location  of  a facility  in a wet-

     land would bring  about  the ruin  of the wetland, the

     note is at variance  with the  purpose for which the

     standard was written (i.e., the  protection of wet-

     lands), and therefore should  be  deleted.  However,

     because the removal  of  a small wetland may not

     endanger or interfere with wildlife, an  owner or

     operator of a  facility  should be able to remove a

     wetland if the wetland: (1)  is  no larger than

     1/2 acre discrete and distant from other such

     wetlands;  (2)  does not  play a significant role

     in life history stages  of  migratory and  resident

     wildlife; and  (3) is not part of or recharge to

     an underground drinking water source.

R:        The commenter's approach of allowing facil-

     ities  to locate in wetlands if the wetland exhibits

     certain characteristics is broadly included in

     the Section 404 evaluation procedures.   However,

     the 404 program goes farther  in  that•it  considers

     alternate locations  and how a facility could be

     built  to minimize damage to the  wetland.  The

     latter two factors that the commenter suggested

     are considered by the Corps and  EPA  in evaluating

     §404 permit applications.   The first factor  is

     not considered in and of itself, but rather  only




                    - 119  -

-------
     in so far as the size of a wetland affects the



     wetland's productivity,  habitat value,  water



     purifying capability, or any of the other factors




     evaluated by the Corps and EPA.



C:        There is no reason to prohibit location of a



     facility in a wetland if the owner or operator



     can demonstrate:



          that there will be no harm to human health



          and the environment and that applicable



          Federal requirements for the protection of




          wetlands will be met.



          compliance with the proposed Human health and



          environmental standards.



          that there will be no discharges to the wet-



          land (this additional variance provision



          would make it possible for storage facilities



          to locate in a wetland).



R:        EPA has not scoped out its final approach to



     siting hazardous waste facilities in wetlands.



     However, human health and the environment are pro-



     tected to some degree by other regulations now in



     existence.  Environmental and human health concerns



     are considered in the Section 404 permitting proce-



     dures and NPDES effluent limitations and the RCRA



     facility standards.




          The proposed human health and environmental



     standards are largely redundant requirements for






                   - 120 -

-------
     compliance with regulations under other statutes



     that a facility is required to comply with inde-



     pendently.  The exception  is the proposed ground-



     water human health and environmental standard



     which is now expressed in  the groundwater monitoring



     regulations and the facility standards.



          In response to the last comment, it would not



     be appropriate to allow location in a wetland solely



     on the condition that there would be no discharge



     of hazardous waste to the  wetland.  Wetlands are



     not good building sites in their natural state and



     therefore must be modified to some degree before



     the facility is constructed.  This modification



     in and of itself may destroy acres of wetlands.



     Of course, discharges to wetlands are not permissable



     unless they are in accordance with applicable federal



     (e.g., NPDES), state, and  local permits.



C:        The only condition under which a facility



     should be allowed to locate in a wetland is if the



     facility design assures proper protection of the



     wetland.  If this condition is met, the appropriate



     NPDES and dredge and fill  permit should be issued.



R.        Facility design may ensure "proper protection"



     of a wetland after the facility is constructed in



     a wetland however, such a  standard would have



     limited utility as a location standard.  Further-



     more, NPDES and dredge and fill permits are only






                   - 121 -

-------
     required for discharges to wetlands.



C:        A permit under RCRA should not be limited by



     requirements for a permit under the NPDES or the



     Section 404 programs because there will be facil-



     ities which are not subject to either of these



     programs, and thus, no basis would exist for a



     permit under RCRA even where impacts of locating



     a facility in a wetland would be minimal.  Further-



     more, the RCRA, NPDES, and 404 programs are con-



     cerned with three different problem areas and the



     creation of interlocking authority may result in



     confusion rather than serve the public interest.



R:        At present EPA and the U.S. Army Corps of



     Engineers (COE) have not come to an agreement on



     the appropriate scope of the definition of "fill



     material" in regulations promulgated pursuant to



     the Clean Water Act.  Until this is resolved, the



     exact set of circumstances under which the owner



     or operator of a hazardous waste facility would



     be required to obtain NPDES or §404 permits is



     not known.  When the scopes of these CWA programs



     are sorted out, EPA intends to fill the gaps



     in protection of human health and the environment



     where they exist in relation to hazardous waste



     facilities.  In doing this, EPA will consider



     determinations made under the NPDES and Section 404



     programs so that duplication will be minimized.






                    - 122 -

-------
C:        By requiring  a  facility to obtain a  NPDES



     permit, EPA  is  not solving  the problem;  it  is



     "passing the buck" by forcing facilities  to submit



     to CWA jurisdiction.




R:        As stated  before,  it was improper for  EPA to



     require a  NPDES permit for  locating  in wetlands.



     Such requirements  has been  deleted.



C:        The requirement  for  a  NPDES permit in  the



     proposed "NOTE" should be deleted because:



     -    if the  facility  has  a  point source discharge



          into  navigable waters,  then a permit is



          already required under FWPCA, such that the



          requirement for  a NPDES permit  under RCRA is



          redundant.



          if the  facility  has  no point source  discharge,



          then  the proposed RCRA requirement is  unau-



          thorized arid  invalid.



          the NPDES  program has  no provisions  for



          transportation-related discharges to wetlands.



          the deposition of solids into a wetland



          facility does not constitute a  point source



          discharge  to  navigable waters.



          even  though the  purpose of the  discharge may



          be waste disposal, solid waste  discharges



          into  navigable waters  are generally  more



          subject to the 404 program than the  NPDES



          program; this interpretation is consistent






                   - 123 -

-------
          with Congressional intent since discharges



          causing material hydroiogic modification



          clearly constitute "fill material"  within



          the meaning of Section 404.



          Congress directed EPA to issue environmental



          guidelines  to govern disposal  sites (§404(b)(l))



          and to prohibit disposal at a  site  upon deter-



          mining that the discharge would have an unac-



          ceptable adverse effect on the environment



          (§404(c)).   These responsibilities  would be



          redundant if dual permits under §§402 and 404



          were required.  Such redundancy would conflict



          with the national policy of §10l(f) that EPA



          "prevent needless duplication  and unnecessary



          delays" in  its implementation  of the Clean



          Water Act.   The control of disposal in wetlands



          should only be under regulations promulgated



          in accordance with Section 404 of the Clean



          Water Act.




R:        EPA agrees  that NPDES permits  are indepen-



     dently required  under the CWA for discharges of



     pollutants from  a point source into waters of the



     U.S.   EPA's intent in the proposed  standard was



     to allow a facility to locate in a  wetland if the



     owner or operator had independently obtained a



     NPDES permit under §402 of the CWA.









                   - 124 -

-------
          NPDES permits are issued for point sources




     such as a truck delivering trash to a wetland.



     Therefore, the commenter was incorrect in stating



     that the NPDES programs has no provisions for




     transportation-related discharges to wetlands.



          The subject matter of the remainder of these



     comments was discharges to wetlands.  Discharges



     to wetlands are regulated under the CWA.  As was



     stated previously, the scope of the CWA programs



     needs to be decided upon before EPA can determine



     what its role for protecting wetlands under RCRA



     should be.



     c.   Executive Order 11990 - Protection of Wetlands



C:        The Executive Order does not give EPA the



     authority to prohibit construction of hazardous



     waste disposal sites in wetlands because:



          Section I(b) of Executive Order 11990 states



          that the Executive Order does not apply to the



          issuance by Federal agencies of permits for



          activities involving wetlands on non-Federal




          property.



          The Executive Order does not flatly ban con-



          struction in wetlands, but provides that it



          may be allowed where, based on economic,



          environmental, and other pertinent factors,



          there is no practicable alternative to such



          construction, and that the proposed action






                    - 125  -

-------
          includes all practicable measures to minimize



          harm to wetlands which may result from such



          use.  EPA should also adopt this approach as



          the basis for determining whether a permit will



          be granted to a facility located in a wetland



          because this will provide adequate and equal



          protection for both Federal and non-Federal



          wetlands and at the same time permit the regu-



          latory authority to exercise some discretion.



          Because no EIS was prepared for the Executive



          Order, nor was any notice published or public



          hearings held on the Executive Order as mandated



          by Section 4 of the Administrative Procedures



          Act.  For these reasons,  the Executive Order



          is null and void,  and therefore,  it has no



          binding effect upon any Federal agency in



          developing its regulations,  permit issuing



          procedures,  or policies.



R:        EPA agrees that Executive Order 11990 does



     not apply to the issuance of permits to private



     parties for activities involving wetlands which



     are located on non-Federal property.  However, EPA



     does not rely on the Executive Order as authority



     for regulating for wetland conditions.   Authority



     is found in RCRA itself in Section 3004 which grants



     the Administrator authority to promulgate standards



     "necessary to protect human health and the environ-




                   - 126 -

-------
     ment  ... [for] the  location,  design,  and construc-




     tion of such hazardous waste  treatment, disposal



     or storage facilities."   Executive  Order 11990 is



     cited to show the long standing  federal interest




     in protecting wetlands.   EPA  policy pronouncements



     of May 1973 and November  1979 similarly state the



     Agency's vital concern for preserving this natural



     resource.^3




          EPA has not formulated a comprehensive approach



     for siting in wetlands at this time.



     d.   Miscellaneous  comments



C:        EPA should delete the entire "wetlands" sec-



     tion until the Agency develops a thorough-going



     program related to  the location of  facilities and



     the discharges from such  facilities in wetlands.



R:        EPA is deferring specific regulation of the



     siting of hazardous waste facilities in wetlands



     until the interface between the CWA and RCRA can



     be determined in this regard.



C:        EPA has offered no valid justification for a



     ban on construction in wetlands.



R:        EPA does not ban construction in wetlands.



C:        Rules for operation  in a wetland should be



     provided in this standard because careful operating



     procedures can minimize the potential risk of a



     wetland discharge site.  Operating procedures that



     were suggested by the commenters are:  (1) routine






                   - 127 -

-------
     monitoring for leachate in selected areas surrounding



     the site at approximately monthly intervals; and



     (2) bimonthly sampling of surface water areas.



R:        EPA is not writing regulations for a wetland



     discharge site in the Location standards.  However,



     operating procedures which are designed to prevent



     contamination of the area surrounding the facility,



     regardless of the type of land area it is, are pro-



     vided in the facility standards.   Most pertinent to



     the commenters'  suggestions are the ground-water



     monitoring requirements.   Other operating and



     design requirements are specified for operational



     units where leaks to ground water or surface water



     may not be readily detected (e.g.,  controls to pre-



     vent overfilling of tanks,  and liner and impervious



     base requirements.



C:        RCRA regulations should not  prohibit disposal



     in wetlands.




R:        The proposed regulation did  not prohibit dis-



     posal in wetlands.
                  - 128 -

-------
          4'    Current status of regulating siting in wetlands

               a.    Values of wetlands

                    The federal government has actively sought to

               protect wetland resources* for we recognize that

               the nation's coastal and inland wetlands are vital

               natural resouces of great hydroiogical, ecological,

               and social importance.  In recent years, the public

               and lawmakers have also come to realize that wet-

               lands must be preserved in order to maintain an

               ecologically stable and balanced environment.  The

               protection of wetlands has become a vitally impor-

               tant priority in the effort, to restore and maintain

               water quality and preserve natural hydrologic

               cycles.84  Wetlands purify and regenerate water,

               control flood waters, and provide food and habitat

               for wildlife.  Commercially important fish and

               shellfish harvested along the Atlantic and Pacific

               Coasts and in the Gulf of Mexico depend on coastal

               estuaries and their wetlands for food sources,

               spawning grounds, and for support of various
* EPA,  in adopting this approach, utilizes the Section 404 defini-
  tion  of wetlands which is:

      "Wetlands" means those areas that are inundated or
     saturated by surface or ground water at a frequency
     and duration sufficient to support, and that under
     normal conditions do support, a prevalence of
     vegetation typically adapted for life in saturated
     soil conditions.  Wetlands generally include swamps,
     marshes,  bogs, and similar areas.


                             - 129 -

-------
stages of their life cycles.  In addition, wetlands

provide essential resting, wintering, and nesting

grounds for many species of migratory waterfowl,

other waterbirds and songbirds.85

     Wetlands are also a valuable tool in flood-

plain management.  Marshes and swamps along coasts,

rivers, and lakes protect shorelines and banks from

erosion.  Wetlands additionally have the capacity to

store floodwaters temporarily and in some instances

to reduce the volume and severity of floods.86

For example, the Corps of Engineers concluded after

a five year study that flooding  problems in the

Charles River Basin in Massachusetts could best

be resolved by maintaining 8,500 acres of wetlands

in their natural state.87

     More recently, chemists have begun to appre-

ciate the ability of wetlands to buffer aquatic

ecosystems from the inroads of pollution.  Thus

wetlands may prove to be a valuable resource in

protecting our water supply from the increasing

number of contaminants which enter our environ-

ment .88

b.   Potential damages to wetlands and consequences
       of damage

     EPA is aware that indiscriminate placement of

hazardous waste facilities in wetlands is likely

to contribute to the degradation of that resource.




              - 130 -

-------
Draining or filling  in the wetland will probably



be required to produce stable  foundations for



buildings, roads, tanks,  etc.   Draining and filling



not only could destroy the area of the wetland that



is drained or filled, but it could also have secon-



dary impacts such as an alteration of water circu-



lation patterns, or  a deficit  in habitat area or



food availability.




     Impacts from spills  or other emergency inci-



dents would also be  more  likely to do extensive



harm to a wetland and hydrologically connected



areas because;  (1) wetlands are usually part of a



hydroiogic cycle which could be connected to



drinking water  sources and other water bodies,



(2) a high water table exists  and thus transport



of contaminants to ground water and surface water



is expedited, and  (3) wetlands  are fragile eco-



systems themselves and therefore cannot absorb



external pressures to the degree that other eco-



systems can  (see 38  FR 10834).



     The EPA standard should be preventive rather



than corrective.  The causal relationship between



an action in a wetland area and the diminution of



water quality,  flooding,  or the disappearance of



a species of fish is not  always readily recognized.



Moreover the cumulative  impact of excessive encroach-



ments in a wetland might  not be apparent in the







               - 131  -

-------
immediate area of the facility but could manifest
                                          Qrt
itself at lower elevations in a watershed.0^

c.   EPA policy

     This policy of protection has taken several

forms.  EPA as early as May 1973 stated its policy

that:

     It shall be the Agency's policy to minimize
     alterations in the quantity or quality of
     the natural flow of water that nourishes
     wetlands and to protect wetlands from adverse
     dredging or filling practices, solid waste
     management practices, siltation or the addi-
     tion of pesticides, salts or toxic materials
     arising from nonpoint source wastes and
     through construction activities, and to
     prevent violation of applicable water quality
     standards from such environmental insults.

     Several years later in 1977, the Administra-

tion issued Executive Order 11990 entitled "Protec-

tion of Wetlands" which requires Federal agencies

to take action to minimize the destruction,  loss

or degradation of wetlands.  While the Order did

not apply to permitting activities by its terms,

the Order focused federal concern on preservation

of the nation's wetlands.

     On July 5, 1979 EPA, building upon this Execu-

tive Order, reaffirmed its wetland policy in the

"Statement of Procedures on Floodplain Management

and Wetlands Protection".  EPA required that

existing regulations and procedures be amended to

incorporate the policies and procedures set forth

in this Statement.  The EPA policy was:


              - 132 -

-------
     The Agency shall avoid wherever possible the
     long and short term impacts associated with
     the destruction of wetlands and the occupancy
     and modification of floodplains and wetlands,
     and avoid direct and indirect support of
     floodplain and wetlands development wherever
     there is a practicable alternative.

d*   Applicable existing programs and deferral of
       regulation

     In developing a regulatory program as author-

ized by Section 3004 of RCRA, EPA has sought to

achieve consistency with these policies.  There

are three aspects of facility construction and

operation which should be considered for wetland

locations.  The first is the impact, without regard

to the nature of wastes handled by the facility,

that the construction and actual presence of the

facility will have upon the wetland environment.

The second is the impact of planned discharges

from the facility and the third is the potential

impact of accidental and unplanned discharges of

hazardous waste into the wetland environment.

     In reviewing the proposed rule and comments

on it, EPA considered not promulgating a wetland

location standard under RCRA, but rather just

ensuring that the permit applicant had obtained

permits under the NPDES and Section 404 programs

if they were required to do so under the Clean

Water Act.  EPA previously determined that these

existing programs adequately protected wetlands




               - 133  -

-------
from the adverse impacts of the construction and




actual presence of the facility, and adverse impacts



from planned discharges from the facility.  In the



later stages of developing the location standards



promulgated today, it became apparent that EPA



could not go forth with such an approach for three



fundamental problems exist.  One,  the U.S. Army



Corps of Engineers (COE) and EPA had not come to



an agreement on the appropriate scope of the defi-



nition of "fill material".  Until this is resolved,



the exact set of circumstances under which the owner



or operator of a hazardous waste facility would be



required to obtain NPDES or §404 permits is not



known.  Two, not all wetlands are "waters of the



United States" and therefore, they are not under



the jurisidiction of the Clean Water Act-  EPA



could not rely on either the NPDES or the §404



program for these wetlands.  The third problem



relates to a COE policy of issuing general or



nationwide Section 404 permits for some wetlands



and certain activities in wetlands, rather than



issuing individual §404 permits.  These wetlands



and activities are permitted by class and each



action is not scrutinized individually.  EPA



believes that the suitability of a wetland for



siting of a hazardous waste facility must be



determined on a case-by-case basis.





               -  134  -

-------
     EPA is deferring specific regulation of the



siting of facilities in wetlands until it is clear



to EPA what the extent of coverage of the NPDES and



Section 404 programs will be.  EPA expects, however,



to retain the presumption against siting facilities



in wetlands which was expressed in the proposed



rule, and to promulgate standards as necessary to



address situations not covered by NPDES and Section



404 programs.  EPA will consider determinations



made under the NPDES and Section 404 programs so



that duplication will be minimized.



     EPA believes that in the interim wetlands will



be sufficiently protected against the unintentional



discharge of hazardous waste through facility com-



pliance with the Part 264 standards.  Examples of



Part 264 requirements that would protect wetlands



in the vicinity of facilities include:  maintenance



of freeboard at surface impoundments, controls to



prevent overfilling of tanks, diversion of run-on



and collection of run-off for piles, land treatment



facilities, and landfills.  Forthcoming regulations



to protect ground water and surface water from the



adverse effects of land disposal facilities will



also protect wetlands.  This list  is by no means




complete.
               -  135  -

-------
F.   Endangered and Threatened Species and Critical Habitats



     1.   Summary of the proposed standard (§250.43-l(f))



          The proposed standard prohibited hazardous waste



     facilities from locating in areas where they would be



     likely to jeopardize the continued existence of endangered



     and threatened species, or where the facility would



     destroy or adversely modify their critical habitat.



     The standard provided for a discretionary approval for



     location in a critical habitat if the owner or operator



     consulted with the Office of Endangered Species (U.S.



     Fish and Wildlife Service, Department of the Interior)



     prior to demonstrating (at the time a permit is issued)



     that operations carried out by the facility would not



     jeopardize the continued existence of endangered and



     threatened species located within the critical habitat.



          Species that are endangered or threatened are



     listed in 50 CFR Part 11, Section 4 pursuant to the



     Endangered Species Act of 1973 (P.L. 93205, 16 U.S.C.,



     1530 et seq.).  Critical habitats of endangered and



     threatened species are listed in 50 CFR Part 17 (1760



     et seq.).



     2.   Rationale for the proposed standard



          The Endangered Species Act of 1973 was enacted to



     conserve the ecosystems and habitats upon which endan-



     gered and threatened species depend for their existence



     and to provide a program for the conservation of such



     endangered and threatened species (Sec. 2(b)).  This was






                        - 136 -

-------
to be accomplished by  requiring all Federal agencies,



in consultation with the  Secretary of the  Interior or



the Secretary of  Commerce,  to  utilize their authorities



in furtherance of the  purposes of the Act  (Section 7).



EPA proposed this standard  to  insure that  owners or



operators locate  and operate their facilities so as not



to (1)  jeopardize the  continued existence  of endangered



and threatened species or (2)  result  in the destruction



or adverse modification of  the critical habitats of



those species.



3.   Response to  Comments



     a.   The Endangered  Species Act  (ESA)



C:        The standard is much broader than the ESA



     (the commenter did not explain why he thought this



     was so).



R:        The proposed regulation language is the same



     as, with minor modifications that are not substantive,




     Section 7(a)(2)  of the ESA.



C:        The standard is unnecessary because the



     regulated community  already knows it  has to comply



     with the ESA.   It should  not be  necessary to incor-



     porate the  features  of each predecessor law into the




     regulations  of  each  new  law.



R.        EPA does  not agree  that the proposed standard




     was unnecessary.   Although Section  9  of the ESA



     applies to  any  person subject  to the  jurisdiction



     of the United  States,  Section  7  specifies EPA's






                    - 137  -

-------
     responsibilities under the ESA.   The proposed

     standard reiterated EPA's responsibilities; the

     content of that standard now appears in Section

     122.12 (Part 122 - permitting requirements; see 45

     FR 33428, May 19,  1980.)

     b-   The phrase "to be likely"  in the proposed
            standard

C:        The phrase should be deleted because it

     weakens the standard.   If there  is any possibility

     of jeopardizing endangered and threatened species,

     a facility should not  be allowed to locate.

R:        EPA disagrees with the commenter's interpre-

     tation of the effect of the phrase "to be likely".

     That phrase was included to strengthen the provision,

     After an action jeopardizes a species,  it may be

     too late for the species to recover.  The "to be

     likely to jeopardize"  language follows the statutory

     language of the ESA.

C:        "To be likely" should be deleted because

     "jeopardize" itself connotes a subjective determi-

     nation without the addition of the adverbial

     modifer, "likely".  The "likely" to jeopardize

     language would facilitate the prohibition of siting

     of facilities on the sheerest speculation.

R:        The phrase "is not likely to jeopardize" is

     found in Section 7(a)(2) of the  ESA.  Regulations

     promulgated by the Departments of the Interior




                   - 138 -

-------
     and Commerce under Section 7 have defined "taking"

     to clarify the actions which would be "likely to

     jeopardize" an endangered or threatened species.

     "Taking" is defined as harassing, harming, pursuing,

     hunting, wounding, killing, trapping, capturing or

     collecting, or attempting to engage in such conduct.

     (See 43 FR 875.)  "Taking" is also used in Section

     9 of the ESA.

     c.   Protecting endangered species outside of their
            critical habitats

C:        Endangered species should only be protected

     in their designated critical habitats.

R:        EPA disagrees with the commenter.  The ESA

     requires all Federal agencies and any person

     subject to the jurisdiction of the United States

     to protect endangered species wherever they occur.

     Preservation of endangered species would not be

     accomplished if these species were allowed to be

     "taken" as soon as they went beyond the boundaries

     of their designated critical habitats.

     d.   Locating in a critical habitat; the "NOTE" to
            the proposed standard

c.        The "NOTE" should be deleted because the very

     location of a facility in a critical habitat would

     probably jeopardize the continued existence of an

     endangered species given the documented evidence

     of damage caused by the treatment and storage of

     hazardous waste.


                   - 139 -

-------
R:        If a facility is located or is proposed to be



     located within a critical habitat EPA is required



     to ensure that such action will not appreciably




     diminish the likelihood of the survival and recovery



     of endangered and threatened species.  Furthermore,



     under the ESA, owners or operators are implicitly



     required to evaluate if the construction,  presence,



     and operation of their facility will result in the



     taking of endangered or threatened species.



C:        The "Note" does not indicate how it is to be



     demonstrated that facility operations will not



     jeopardize the continued existence of endangered



     species.  Furthermore, once a permit is issued,



     there are no means of preventing careless  spillage



     and leakage of deadly chemicals which would result



     in irreparable damage to endangered and threatened



     species.



R:        If a facility is located or proposes  to locate



     in a critical habitat, EPA will determine,  in



     consultation with the Department of Interior or



     Commerce, if the facility will appreciably diminish



     the likelihood of the survival and recovery of



     endangered and threatened species.   A facility that



     is permitted pursuant to the Part 264 standards



     presumptively will not cause careless spillage



     and leakage of waste.









                   - 140 -

-------
        C:         A  framework  for  consultation  should be  set up

             to ensure  that  all  pertinent  and necessary informa-

             tion  is supplied  to the  Department  of  Interior

             prior to any decision regarding the location of a

             facility in a critical habitat.

        R:         EPA no longer  requires that owners or operators

             consult with the  Department of the  Interior.  The

             Department of Interior (DOI)  is currently writing

             final regulations for the  consultation process

             mandated by Section 7 of the  ESA.   This consul-

             tation  process  is only applicable to consultation

             between Federal agencies and  the Secretary of the

             Interior.   The  regulations soon to  be promulgated

             by DOI  will specify the  information that is

             necessary  to present  during a consultation.

        4.   Final disposition

             a.    Pot ent i a1  damag e

                   Many  species of  plants,  fish,  and wildlife

             have  become threatened or  endangered or extinct in

             the past through  the  cumulative effects of human

             activities.* Habitat destruction,  excessive
Endangered species are  species which are in danger of extinction
throughout all or a significant portion of their range except for
species of the Class  Insecta determined by the Secretary of Commerce
to be a pest whose protection would present an overwhelming and over-
riding risk to man.   Threatened species are species which are likely
to become endangered  species within the foreseeable future throughout
a significant portion of their range.  (Section 3, ESA)
                           - 141 -

-------
             killing, and contact with an environment which has

             become,  in recent years, increasingly contaminated

             with a complex array of toxic chemicals are factors

             which contribute to the demise of these species.

             Indirect poisoning or debilitation can result from

             the biological magnification of toxic elements or

             compounds in the food chain.

                  Locating, constructing, and operating hazardous

             waste facilities, if not adequately regulated, can

             lead to further reductions in populations of endan-

             gered and threatened species.  Possible impacts

             include removal of critical habitat,* restricting

             the movement of species, and degrading the environ-

             ment near the facility (e.g., increasing siltation

             of rivers, degrading air quality).  Thus, EPA

             believes that it is important to evaluate effects

             on endangered and threatened species and their

             critical habitats when a hazardous waste facility

             is being located or when an existing facility is

             applying for a permit.

                  As of January 31, 1980 there were 228 species

             listed as endangered and 44 species listed as

             threatened in the United States.90  Lists of
Critical habitat is the area,  together with contained biological
and physical elements,  which are necessary for the conservation
of the species. (For greater detail see Section 3(5)(A) of the
ESA. )
                           - 142 -

-------
endangered and threatened species are periodically



published in the Federal Register.  The last such



listing appeared on May 20, 1980 in Volume 45,



Number 99 (p. 33768-81) of the Register.  Critical



habitats are also published in the Federal Register.



t>.   The Endangered Species Act and Part 122



     EPA's authority for protecting endangered and



threatened species and their critical habitats is



contained in both the ESA and the RCRA.  RCRA



inherently accounts for protection of endangered



and threatened species and their critical habitats



by specifying that location standards must be



promulgated which protect the environment.  Section



2 of the Endangered Species Act of 1973, as



amended, specifies that all Federal departments



and agencies are to seek to conserve endangered



and threatened species and to utilize their



authorities in furtherance of the purposes of the



ESA.  Those purposes include providing a means



whereby the critical habitats of endangered and



threatened species may be conserved and providing



a program for the conservation of endangered and



threatened species.  Section 7 of the ESA specifies



that Federal agencies must take no action which is



likely to jeopardize the continued existence of



any endangered or threatened species or result in



the destruction or adverse modification of critical







              - 143 -

-------
habitats of such species unless the agency has



been granted an exemption for the action by the



Endangered Species Committee (such as the case of




the Tellico Dam project in Tennessee).



     Part 122 of the Consolidated Permit Regulations



(45 PR 33290; May 19, 1980) contains a section



(§122.12) which lists Federal laws which EPA is



required to comply with.  The ESA is listed and



EPA's requirements under Section 7 stated.  EPA



is required to ensure that the facility which it



is permitting is not likely to jeopardize the



continued existence of any endangered or threatened



species or adversely affect its critical habitat.



     Section 9 of the ESA applies to any person



subject to the jurisdiction of the United States.



Thus, owners or operators are subject to require-



ments under that Section irrespective of RCRA.



Section 9 regulates, among other things, the



taking, possession, and transport of such species.



     EPA has therefore determined that the Endangered



Species Act adequately protects endangered and



threatened species and their critical habitats



such that a separate requirement in the Location



standards is unnecessary.




     Owners or operators of facilities should contact



the Regional Offices of the U.S. Fish and Wildlife




Service (Department of Interior) and State agencies






              - 144 -

-------
that have responsibility for protected species



for current listings of endangered or threatened



species and information on the location of critical



habitats.  A guidance/permitting manual on the



Location  standards contains a section on compliance



with the  ESA.   Owners or operators and permitting



officials shpuld  consult this manual for help in



determining if  the  facility has the potential to



adversely affect  a  listed  species or a designated



critical  habitat.
                - 145 -

-------
Sole Source Aquifers

1.   Summary of the proposed standard ( §250.43-1 (g.)}

     The proposed standard prohibited hazardous waste

facilities from locating in the recharge zone of a sole

source aquifer.  The "Note" to the proposed standard

specified that a facility could be allowed to locate in

the recharge zone of a sole source aquifer if it could

be demonstrated (at the time of permit issuance) that

the facility is located, designed, constructed, operated,

maintained, and monitored to prevent endangerment of

the sole source aquifer.

     "Sole source aquifers" were defined in proposed

§250.4l(b)(82) as,

     "those aquifers designated pursuant to Section
     I424(e) of the Safe Drinking Water Act of 1974
     (Pub. L. 93-523) which solely or principally
     supply drinking water to a large percentage
     of a populated area".

2.   Rationale for the proposed standard

     Approximately 123 million Americans rely on ground

water for drinking purposes.  Ground water also supplies

36% of all irrigation water and about 25% of the fresh

water used by industries dependent on their own water

supply facilities.  Six states depend on ground water

for more than half of their water needs.^1  Sole source

aquifers are unique and highly important natural resources

because they are, by definition, the principal source of

drinking water for population centers.
                   - 146 -

-------
     Aquifers are  replenished  through recharge zones
which are permeable to rainfall and surface run-off and
through which the  aquifer  is susceptible to contamina-
tion.  The location of a hazardous waste facility in
the recharge zone  is undesirable because:
(1)  degrading a portion of the recharge zone reduces
     the amount of uncontaminated. water available for
     use;
(2)  the contaminants would be more likely to migrate
     to adjacent areas of  the  aquifer, and to surface
     waters.
     The purpose of the proposed regulation was to
prohibit the location of facilities in the recharge zone
of sole source aquifers.   However, the Agency allowed
facilities to locate in the recharge zone of a sole
source aquifer, at the discretion of the permitting
authority, if the  owner or operator could demonstrate
that such location would not endanger the aquifer.
3.   Response to comments
     a.   The proposed standard is too lenient
     Summary of Comments
     (i)  The safety of all drinking-water-quality
          aquifers must be assured under RCRA and the
          SDWA so  that the intent of both of these Acts
          are fulfilled.
    (ii)  The siting restriction should be expanded to
          apply to location of facilities:
                   - 147 -

-------
       -     in the  recharge  zone  of  every under-



            ground  drinking  water source



            in the  watershed of a public  drinking




            water supply



            upstream of  or in the recharge zone  of



            any aquifer



(iii)   The  "Note" to the proposed standard should be



       deleted.  In view of  the limited number of



       available drinking water sources,  and  the



       potential social,  environmental and economic



       costs that would  be involved  if an aquifer



       was  polluted "by  mistake"  (i.e., the degree



       of protection required was miscalculated), no



       hazardous waste facility should be permitted



       in the recharge zone  of a  sole source  aquifer.



       EPA  should not opt for the short-term  accommo-



       dation of conditionally allowing hazardous



       waste facilities  to locate in the  recharge



       zone of sole source aquifers  when  the  long



       term water supply of  our nation is at  stake.



 (iv)   There should be no condition  under which  a



       facility could be located  in  the recharge




       zone of a sole source aquifer unless positive



       assurances are provided to prevent groundwater



       pollution.



  (v)   The  standard does not provide much protection



       for  states where  a sole source aquifer has





               - 148 -

-------
      not been designated.
(vi)  No hazardous waste facility should be sited
      near the zone of "important aquifers" because
      of:
           the uncertainties surrounding the effec-
           tiveness of the design and management
           criteria required by EPA in Section 3004;
           the weaknesses of the endangerment con-
           cept and the proposed human health and
           environmental standards; and
           the possibility of spills, other accidents
           or human error.
 To more precisely regulate where, in relation to
 aquifers, a facility would/would not be allowed to
 locate, the commenter suggested that EPA establish
 three categories of aquifers and classify every
 known aquifer accordingly.  The three categories
 and their attendant siting specifications follow.
 0    No facility should be allowed in the recharge
      zone of a priority aquifer unless the permit
      applicant can show that no alternate site
      exists within a multi-state area.  This
      category includes all aquifers which,
           meet the criteria for sole or principal
           sources contained in the proposed 40 CFR
           §148 (42 FR 51620)


               -  149  -

-------
     discharge into wetlands or high quality



     surface waters



     are high quality present or potential



     drinking water sources



     are so designated by a §208 agency under



     the Clean Water Act or the §4002 planning



     process of RCRA



     have less than 10,000 ppm total dissolved



     solids



Facilities should be allowed to locate over



the recharge zone of other underground drinking



water sources (UDWS) if the facility complies



with all of the §3004 criteria.  To be included



in this category are aquifers which, although



they may be actual or potential drinking



water sources, warrant less protection because



of either existing contamination, availability



of other drinking water sources, or the



absence of significant surface water effects.



Facilities should be encouraged to locate



over underground non-drinking water sources.



This category includes aquifers which are



saline, highly polluted or otherwise of



severely limited value.  Facilities located



over these facilities will still have to



comply with all §3004 regulations.
         - 150 -

-------
When classifying an aquifer, EPA  should additionally
consider the number of people who depend, or will
depend, on the aquifer.
Response
     EPA agrees that  the proposed standard was too
restrictive  in the universe of aquifers that it
protected.   The RCRA  program is aimed at not
allowing contamination of any water that may be
used.  This  includes  ground water and surface
water that is used, or may be used in the future
for drinking water, agriculture,  irrigation, or
industrial purposes.  The specific facility stan-
dards provide significant ground  water protection.
     It would not be  practicable  for EPA to restrict
location in  the recharge zones of ail UDWS's
because a majority of the United  States would be
included in  such a restriction.   Additionaly, EPA
believes that it would be inappropriate for this
Agency to classify all aquifers in the U.S.  EPA
believes that such a  classification scheme should
be left up to the States.
b.   The standard is  too stringent
Summary of Comments
(i)  The standard should only apply to land treat-
     ment, land storage, and land disposal facil-
     ities because these facilities are the only
               -  151  -

-------
      facilities  that present any substantial



      threat to aquifers.   The proposed standard



      will result in numerous unnecessary demon-




      strations of facility adequacy.



(ii)   The "NOTE"  to the standard should be amended



      so that facilities are allowed to locate in



      the recharge zone of a sole source aquifer



      provided that measures are taken to prevent



      endangerment of the  aquifer at distances



      greater than 500 feet from the facility and



      so that existing water wells within 500 feet



      of the facility are  not endangered.   This



      revision would increase the number of available



      disposal sites and is in agreement with the



      purpose of  RCRA and  the SDWA.



 Response



      EPA agrees  that land disposal facilities pose



 more of a threat to ground water than other facility



 types.   Because  of this,  the Phase II land disposal



 regulations are  keyed to  protecting groundwater from



 contamination by hazardous waste facilities. EPA



 believes that because the facility standards are



 designed to provide maximum protection to ground



 water from contamination  that a location standard



 to protect aquifers would be redundant.
               - 152 -

-------
  c.    Miscellaneous comments




  (i)   The Safe Drinking Water Act (SDWA) applies



       to facilities which present a "significant



       hazard to public health".  Until such time



       that a SDWA standard is defined for ail



       activities that take place in the recharge



       zone of a sole source aquifer, there should



       not be a special standard for hazardous waste



       management facilities.  The commenter also



       objected to the RCRA standard being more



       stringent than the "SDWA standard".



 (ii)   Because all components of a facility (e.g.,



       tanks, incinerators, storage areas) are poten-



       tial threats to an aquifer, each component



       should be required to have berms to control



       spill and precipitation run-off.



(iii)   The recharge zone of an aquifer does not



       necessarily remain constant over time.   Hydro-



       logic changes could cause the recharge zone



       to expand thereby circumscribing a facility



       which was previously outside the recharge



       zone.  Such a facility would de facto be in



       violation of the standard.



 (iv)   The standard is unnecessary because sole



       source aquifers are protected under the SDWA.



  (v)   Retain the proposed siting restriction.










                - 153 -

-------
     Response



          There are no plans to write regulations under



     the Safe Drinking Water Act for all activities in



     recharge zones of sole source aquifers.  Restric-



     tions in these zones under the SDWA only apply to



     new underground injection wells.



          Requirements for control of spill and preci-



     pitation run-off are examples of facility standards



     which serve to protect ground water.   A summary of



     some of these standards follows in the discussion



     of the protection provided to ground water by the



     facility standards.  EPA does not however, require



     spill and run-off control for all components of a



     facility? rather, only where EPA believes that a



     potential hazard exists from spills or run-off.



4.   Rationale for deletion of the proposed standard



     EPA has decided not to promulgate a final location



standard concerning recharge zones of sole source



aquifers.  This decision is based upon (1) the protec-



tion that the facility standards will provide to all



underground drinking water sources (UDWS)  and (2) weak-



nesses discovered in using the group of aquifers that



have been designated as sole source as the subject of a



location standard for hazardous waste facilities.



     a.   Protection provided by facility standards



          Taken together, the Phase I and Phase II Part




     264 and 265 standards provide for a comprehensive



                   - 154 -

-------
system of waste management which  is designed,  among



other things, to minimize, if not prevent, any con-



taminant from reaching any point  of ground water use.



This approach applies equal protection to water



that is used for drinking, irrigation, agriculture,



and industry.  Most of the Part 264 and 265 regu-



lations directly or indirectly protect ground-



water such that an exhaustive review would be too



lengthy to include here.  Examples of standards



which protect groundwater follow:



-    Waste piles.  Run-on must be diverted away



     from a waste pile.  Piles which are used to



     treat or store waste must be equipped with a



     containment system to include a leachate and



     run-off collection and control system and a



     base.  The containment system must be designed,



     constructed, maintained, and operated to prevent



     discharge into the land, surface water,  or



     ground water during the life of the waste pile.



     Tanks-  At the time of permit application the



     Regional Administrator will  assess the ade-



     quacy of the tank design, including the foun-



     dation, structural support,  seams, and pressure



     controls.  Owners or operators are required to



     inspect their tanks in order to detect cracks,



     leaks, corrosion or erosion  which may lead to




     cracks or leaks, or wall thinning.






              - 155 -

-------
Surface impoundments.  Surface impoundments



used to treat or store waste must be designed



to prevent discharge into the land and ground



water, and to surface water during the life



of the impoundment by use of a containment




system.



Areas that are used for storage of containers



must have a containment system that is capable



of collecting and holding spills, leaks, and



precipitation.



Leaks are minimized by the inspection stan-



dards.  Requirements include inspection of



areas where containers are stored; containment



systems 7 construction materials of a tank,



and emptying the tank for a thorough examina-



tion of the condition of the inside of the



tank when necessary to detect corrosion or



erosion of the tank sides and bottom.



The standards for management of ignitable,



reactive, and incompatible wastes will mini-



mize discharges of waste resulting from vio-



lent reactions or corrosion of containment



systems.




EPA intends to promulgate land disposal



regulations which provide maximum protection



to surface water and ground water.
         - 156 -

-------
     Given that land disposal facilities are most

likely to be the cause of groundwater pollution,

the land disposal regulations are key to EPA's

belief that all water sources will be protected by

the facility standards.  The groundwater monitoring

requirements provide for early detection of ground

water contamination.

t>.   Inappropriate use of the sole source aquifer
       designation

     While protecting sole source aquifers by

restricting location of hazardous waste facilities

appears to be a reasonable approach to preserving

a portion of the water supply of the nation, a

closer look at the criteria which are used to

designate a sole source aquifer and future conse-

quences of such designation provide insight into

the problems associated with that approach.

     One of the criteria for designating a sole

source aquifer is that the aquifer must provide

over 50 percent of the drinking water for an area.

Water sources protected by the hazardous waste

program are not limited by present use or the size

of the dependent population.  An aquifer may not

be deemed important enough to warrant designation

as a sole source aquifer until a large population

has settled in an area for which the aquifer supplies

drinking water.  It would not show foresight if a



               - 157  -

-------
hazardous waste facility siting restriction were



only to apply when the aquifer was actually desig-



nated.  In contrast, the facility standards and



the groundwater monitoring requirements seek to



protect all present and potential water sources.



     Another potential consequence of using the



recharge zone of sole source aquifers as a siting



standard is that an interested group might try to



have an aquifer designated as sole source in order



to make it more difficult to site a hazardous



waste facility in that area.  A reduction in



hazardous waste management capacity could result



due to successful sole source designations, and



the increasing number of obstacles to siting



facilities.  It would also represent improper use



of the system under the SDWA to designate aquifers



as sole source.
              - 158 -

-------
H.   Buffer Zone




     1<   Summary of the proposed  standard  (§250.43-1 (h))



          The proposed standard required that active portions



     of hazardous waste facilities be located at a minimum



     of 60 meters  (200 feet)  from  the facility property line.



     A variance to the proposed standard was provided in



     the form of a "Note".  Lesser, distances would be allowed



     if it could be demonstrated that unexpected releases



     or discharges of hazardous waste could be controlled



     before they crossed the  facility property boundary.



     2.   Rationale for the proposed standard



          A distance between  the active portion and the



     property line of a facility provides a buffer area



     between the active portion of a facility and the area



     beyond the periphery of  the facility.  The Agency



     believed that a buffer zone would reduce risks to human



     health and the environment in the vicinity of the



     facility by allowing unexpected discharges resulting



     from acute incidents such as  fires, explosions, and



     spills, and chronic incidents such as underground leaks,



     to dissipate, dilute, or be brought under control before



     going beyond  the facility's property line.



          A buffer zone could be of aesthetic value by con-



     cealing a facility that  otherwise might be an eyesore.



     In addition, buffer zones might minimize the level of



     noise and reduce the strength of odors which reach areas




     beyond the facility.





                        - 159 -

-------
     The selection of a 200 foot buffer zone was based



on the State of Oklahoma's Rules and Regulations for



Industrial Waste Management.92  Oklahoma prohibits



ultimate disposition of industrial waste within 200 feet



of the permit boundary, thus providing a precedent for



the proposed regulation.  Although other states require



buffer zones of narrower width (e.g., Wisconsin - 20



feet, New York 50 feet; and Pennsylvania - 25 feet),



these regulations only pertain to municipal solid waste.



Since hazardous waste poses a greater risk to human



health and the environment than municipal solid waste,



Oklahoma's more stringent regulation for industrial



waste was adopted.  A specific numerical distance was



specified in order to facilitate enforcement and to



provide a tangible point of reference.



3.   Response to comments



     These comments are responded to in a general way



because the proposed standard has been deleted.



     a.   Impact on existing facilities



     (i)  Establishing a 200 foot buffer zone will place



          an undue hardship on existing facilities where:



               The site is completely built upon such



               that either part of the facility will



               have to be dug up and relocated, or



               additional land will have to be purchased.



               Additional land is not available because



               the land surrounding the facility is






                   - 160 -

-------
            already occupied by another party.



            The facility will have to bear the cost



            of digging up and relocating the waste



            (e.g.,  as in a surface impoundment)  and



            possibly threatening human safety in the



            process.



 (ii)   The impact on existing on-site facilities



       would be costly and it would render otherwise



       suitable land unnecessarily useless.  In  addi-



       tion, relocation within a plant or industrial



       area may be difficult or impossible if addi-



       tional land is not available.   These impacts



       are not balanced by meaningful environmental



       benefits due to the nature of the site and



       the adjacent property.



(iii)   Existing facilities should be exempt from the



       proposed standard if:



       -    The site is bounded by uninhabited or



            industrialized areas.



            The facility owner or operator can demon-



            strate that there is minimal danger  from



            operating closer than 200 feet from  the



            property boundary line.



 (iv)   Existing impoundments should be exempt from



       the buffer zone requirement because in many



       cases impoundments are located immediately



       adjacent to the plant property line and







                - 161 -

-------
        construction  of  a  buffer  zone  would be costly



        and  might  jeopardize  the  structural integrity



        of the  impoundment due  to the  limited  working



        space between it and  the  property line.



   (v)   The  degree of hazard  of contained waste  should



        be taken into consideration when  specifying



        the  width  of  a buffer zone for existing  lagoons



        that are located less than 200 feet from a



        river or a highway.



  (vi)   The  standard  is  overly  stringent  for existing



        facilities where the  waste being  managed is



        of a minor hazard.



 (vii)   This standard could significantly reduce the



        usable  area of existing facilities.



(viii)   If existing facilities  in areas where  space



        is at a premium  or unavailable (e.g.,  chlor-



        alkali  plants in heavily  industrialized  areas



        of the  Northeast)  were  made to comply  with



        this standard, they would experience a compe-



        titive  disadvantage.



  (ix)   A facility that  is located on  property 400



        feet wide  by  400 feet long or  smaller, would



        be forbidden  to  treat,  store or dispose  of



        hazardous  waste  because of the 200 foot  buffer



        zone requirement.
                 -  162  -

-------
  Response




       EPA agrees that requiring existing facilities



  to institute a 200 feet buffer zone would be un-



  necessarily burdensome.  The protection provided



  to human health and the environment would not be



  congruent with the expense which would be required



  in most cases.  In fact, it could be detrimental



  to human health and the environment if existing



  facilities were made to close for noncompliance



  with the buffer zone standard.  EPA additionally



  agrees that requiring 200 feet at every facility



  is too inflexible.



  b.   Surrounding land use



  (i)  The standard should allow a buffer zone less



       than 200 feet where no residences are closer



       than 50 feet from the property line.   Facil-



       ities located in a remote area or in an



       industrialized area do not need a large




       buffer zone.



 (ii)  Hazardous waste disposal facilities should



       not be located within 1 mile of residentially



       zoned land areas because odors can be a



       problem when weather conditions are favorable



       and, to protect the welfare and health of



       people in adjacent residential zones.



(iii)  The terrain and the type of neighbors (i.e.,



       residential or industrial) surrounding a hazar-






                - 163 -

-------
        dous  waste  disposal  site  should be  taken into



        consideration when determining  the  required




        length of the buffer zone.



  (iv)   This  requirement  should be  a  permit condition



        so that surrounding  land  use  and facility




        operation can be  taken into consideration by



        the regulatory  authority.



   (v)   EPA should  clarify its position on  the  loca-



        tion  of disposal  sites relative to  population



        centers.



  (vi)   Facilities  should not be  located in population



        centers because:



        -    Explosions may  expose  thousands of people



             to toxic airborne substances.



        -    Leachate from chemical landfills may



             travel more  than 200 feet  in porous soil



             and contaminate public or  private  wells.



 (vii)   A minimum buffer  zone of  50 feet should be



        required from the active portion of all



        facilities  to public and private wells.



(viii)   A minimum buffer  zone should  be required from



        the active  portion of all facilities to lakes,



        streams, rivers,  occupied dwellings, highways,



        public parks, and historical  sites.



   Response




        EPA agrees  that it is preferable to locate



   hazardous  waste  facilities away  from residential






                -  164 -

-------
  areas and population centers.  However, EPA believes



  that equal protection should be provided at a



  facility regardless of the surrounding land use.



  c.    Comments specific to facility type



  (i)   Storage facilities.




            This standard is excessive for small



            storage facilities (i.e., facilities that



            store only a few barrels of waste)  and



            for generators in urban areas that  store



            hazardous waste.



       -    A buffer zone should only be one among



            many engineering parameters to take into



            consideration when designing a storage



            facility.



 ( ii)   Treatment and storage facilities



       -    A buffer zone is unnecessary due to the



            diking, surface water diversion, and



            containment requirements for these



            facilities that are specified in other



            sections of the proposed rules.



(iii)   Treatment facilities:



            The standard is oppressive and costly



            due to the difficulty associated with



            acquiring land in an industrial area.



            EPA should be aware of, and consistent



            with, local zoning ordinances and industry



            standards that restrict the placement of






                - 165 -

-------
           treatment  facilities  relative  to property



           lines.



           A lesser buffer  zone  would be  appropriate



           for  a treatment  facility which converts



           toxic and  hazardous waste to inert



           material for  use in saleable products.



           It is inappropriate for EPA to dictate



           specific distances, particularly for



           treatment  facilities.



           The  size of the  buffer zone should be



           sufficient to provide adequate space and



           time to detect and correct any ground or



           surface water contamination and,  adequate



           distance to protect the health of area



           residents.



(iv)   Land  disposal facilities:



           A minimum  of  200 feet should be required



           around a land disposal facility.




           200  feet is appropriate for landfills.



      -     A 50 foot  buffer zone would be adequate



           for  landfarms in light of the  prohibition



           of ignitable  and volatile waste from



           landfarms.



      -     A 200 foot buffer zone is inadequate and




           arbitrary  for landfills, landfarms,



           basins, and surface impoundments because  of



           the  threat posed by airborne contaminants






              - 166  -

-------
             and the trackout of toxic substances by



             vehicles (discussed in the Phase I



             Background Document on Landfills).



   (v)   The standard is excessive for vessel cleaning



        facilities because after the residue in the



        vessel is diluted with water,  its degree of



        hazard is not commensurate with a 200 foot



        boundary zone.



  (vi)   Facilities which handle phosphate related



        wastes should be exempt from this standard



        because of the low hazard of these wastes.



 (vii)   Waste oil recycling facilities should be



        exempt from the standard because adequate safe



        guards against accidental spills or discharges



        are already controlled under Section 311 of



        the Spill Prevention, Control, and Counter-



        measure (SPCC)  Plan of the Clean Water Act.



(viii)   Because used oil is generated in urban areas,



        used oil reprocessing facilities are more con-



        veniently and economically operated in, or



        adjacent to, urban areas.  The proposed buffer



        zone requirement would necessitate the acquisi-



        tion of more land.  This additional cost



        could lower the profit margin to a degree



        that operating the reprocessing facility



        would be uneconomical.  The alternative of



        locating further away from an urban area






                - 167  -

-------
     where land is less expensive will probably not



     be viable because of increased hauling costs.




Response



     EPA agrees that requiring the same buffer



zone width at all facilities would be inequitable.



Hazards from leaks, spills, and explosions are




dependent upon the types of wastes handled at a



facility, the size of the facility (i.e., the



number of tanks, landfills, etc.)* and the types



of operational units (i.e., tanks, containers,



surface impoundments, etc.) at a facility.



     EPA also agrees that some of the protection



provided by surface water diversion or collection



and containment requirements reduce the need for



a buffer zone-  Additional protection is provided



at treatment and storage facilities in the facility



standards by the set-back requirements for tanks



and containers that hold ignitable and reactive



waste.



     One reason that EPA has not included a general



buffer zone standard in the final rules is that the



Agency believes that it is better to set such a



requirement at the local level.  Regional factors



such as population density, land availability, and



proximity of the facility to residences, schools,



and hospitals can be factored into the distance



required.





              -  168  -

-------
 d'    Alternate suggestions for the length of the
         buffer zone


  (i)   The requirement for a 200 foot buffer zone is

 excessive and should be reduced to (a maximum of)

  100  feet because:

            100 feet is sufficient in most cases,

            and this distance is consistent with

            state experience with safely operated

            facilities rather than on Oklahoma's

            regulation which is not backed by any

            experience.

            Many states only require a 50 to 100

            foot buffer zone.  For example,  Pennsyl-

            vania has found that a 50 foot buffer

            zone amply serves environmental interests.

 (ii)   The standard should require a 50 foot buffer

       zone.  If a larger buffer zone is required,

       it should be specified in the facility's

       permit.

(iii)   The standard should require a 100 foot buffer

       zone with the caveat that EPA may require a

       greater distance in cases posing a particular

       hazard to neighboring properties.

 (iv)   The standard should require a 100 foot buffer

       zone in order to be consistent with existing

       set-back policies regarding floodplains, wet-

       lands, and surface mining.




                - 169 -

-------
   (v)   The  "note"  to the standard should be deleted



        and  the  requirement for  a 200 foot buffer



        zone should be replaced  with  a 100 foot



        buffer zone requirement.   This revision will



        curtail  the growth of facilities'  property



        ownership,  which  is advantageous  because



        sloppy operations may take place  in unneces-



        sarily large sites.



  (vi)   200  feet is generally acceptable  unless the



        site operator can show evidence that a  lesser



        distance would adequately protect  human health



        and  the  environment.   The buffer  zone should



        not  exceed  200 feet.



 (vii)   The  standard should require a distance  of 300



        feet between the  active  portion of a disposal



        facility and the  facility's property line;



        this suggestion is based on data  derived



        from the lateral  subsurface migration of



        septic tank effluents.



(viii)   If the other (proposed)  regulations for dis-



        posal facilities  are  followed properly  (thus,



        preventing  escape of  fugitive emissions in



        all  three directions)  and the monitoring



        equipment is installed in the proper location,



        the  buffer  zone could be substantially  reduced,



        perhaps  to  20 feet or less.










                - 170 -

-------
(iv)   The buffer zone should have the same width as



      the average thickness of the bottom seal of a



      landfill, or alternatively; the buffer zone




      should have the same width as the distance



      from the top of the landfill to its bottom



      seal.  The latter option is derived from a



      consideration of contruction parameters.   Both



      of these options permit the concurrent or sub-



      sequent installation of a barrier which should



      substantially seal in potential fugitive



      emissions through ground migration.



 Response



      These comments illustrate the arbitrary nature



 of a general buffer zone requirement.   A reasonable



 buffer zone distance can only be set for a defined



 set of circumstances (e.g., treatment  or storage



 of reactive waste in a tank) or, on a  case-by-case



 basis during the permitting process.  At present,



 EPA believes that a general buffer zone requirement



 is unnecessary because of the protection that  the



 facility standards provide to human health and the



 environment.  If EPA becomes aware of  a situation



 where a buffer zone or set-back distance is needed



 to adequately protect human health and the environ-



 ment, EPA may, at that time, either specify a cer-



 tain distance (as in the case of containers holding



 ignitable and reactive waste), or leave it up to






               -  171  -

-------
  the permitting  official  to set  an appropriate buffer



  distance  based  on  site-specific determinations.



  e.    The  "NOTE"  to the standard



  (i)  Detailed guidance should be given as  to how



       the  owner  or  operator can  demonstrate that



       his  facility  can meet the  provisions  of the



       "note".  There should be a delineation of



       the  acceptable means  of  controlling unexpected



       releases and,  what  constitutes  "sufficient"



       proof.  Also,  the design base release and



       other data should be  described.



 (ii)  It is difficult, vague,  potentially burdensome,



       expensive,  and/or impossible to  demonstrate



       compliance with the note.



(iii)  The«,conditions of the note are redundant to



       the  requirements for  contingency plans and



       emergency  procedures  specified in Section



       250.43-3.



 (iv)  An exemption  from the 200-foot limit  should



       be allowed if contingency  plans  or emergency



       procedures  adequately handle probable and



       possible incidents.



  Response




       EPA  agrees  that compliance with  the proposed



  "NOTE" would be difficult  to  demonstrate.   EPA



  also agrees that the final Contingency plan and



  Emergency procedures (Subpart D)  and  Preparedness







               -  172  -

-------
 and  Prevention (Subpart C) standards provide some




 of the  protection to human health and the environ-



 ment that the proposed buffer zone standard was



 meant to provide.



 f.    General comments




 (i)   This standard fails to make any distinction



      in the degree to which a waste is hazardous.



      It is excessive for relatively low hazard wastes



      (e.g., utility waste).  Also, "moderately"



      hazardous waste should be exempt from the buffer



      zone requirement.  This Is particularly true



      of phosphate related waste (e.g., gypsum)



      where the standard would cripple phosphate



      operations.



( ii)   A specific distance for a buffer zone should



      not be specified because:



           It is too arbitrary and inflexible to be



           universally applicable and therefore



           will be excessive in some cases and



           insufficient in others.



           This approach allows no consideration of



           site specific operating and design condi-




           tions .



           It will prevent construction and opera-



           tion of facilities near industrialized



           areas and near manufacturing plants



           located in towns or cities where sizeable




               - 173  -

-------
            pieces  of  land  are hard  to  find.



            Distance from the boundary  line  is  not



            relevant to  the general  safety or operating



            performance  of  a facility.



(iii)   Suggested  alternatives to  specifying  a buffer



       zone  distance are:



            Requiring  that  "adequate buffer  zone  be



            maintained to allow for  safety".



            That  EPA require proof that a  facility



            has adequate technologies and  "emergency



            plans"  to  control accidental discharges



            or releases  of  hazardous waste.



            Requiring  structural  protection  (e.g.,



            a dike).   This  would  be  far more  effective



            in protecting the public from  an  explosion.



       -     Requiring  that  a satisfactory  facility



            design  be  demonstrated.



 (iv)   The need for and, if required, the  size  of a



       buffer zone  should be determined on an indi-



       vidual site  basis.



  (v)   Revise the standard  to take into account;



       (1) the nature  and type of hazardous waste,



       (2) surrounding land use,  and (3) the  function



       of the active portion of the  facility.



 (vi)   Protection of neighbors against  spills and



       explosions should not be considered within



       the regulatory  sphere.





               - 174  -

-------
 (vii)   EPA has not demonstrated the relevance of



        the buffer zone to the matter of protection



        of human health and the environment.



(viii)   The purpose(s) of the buffer zone should be



        directly stated in the standard.  If it is



        not stated, buffer zone adequacy may not be



        addressed by facility operators.  The following



        purposes were suggested by the commenters:



        -    Provides adequate space and time to



             detect and correct any ground or surface



             water contamination before such contami-



             nation reaches the adjoining property.



        -    Provides adequate distance to protect



             the health of area residents.



        -    Provides access for emergency equipment.



  (ix)   The standard does not provide for protection



        of the public from noise or airborne pollutants



        resulting from facility operations; particu-



        larly in the case of catastrophes (e.g.,



        chemical fires, uncontrolled reactions,



        explosions).



   (x)   A 200 foot buffer zone does not adequately



        protect the safety of the general public7



        particularly if the facility manages ignitable,



        reactive, and/or incompatible waste.



  (xi)   The Agency should clarify that the term,



        "property line" refers to the perimeter




                 -  175  -

-------
        property  line  and  not  to  the  right-of-way



        boundaries  around  and  through the property.



 (xii)   The  requirement  is unclear  because the  boun-



        dary of the storage, treatment,  or disposal



        facility  may not be the same  as  the owner's



        or operator's  property boundary.



(xiii)   The  standard significantly  reduces the  capa-



        city and/or the  size of the usable area of a



        site.   It is particularly onerous for small



        facilities  because the buffer zone will consume



        an inordinate  percentage  of facility acreage.



 (xiv)   The  proposed standard  is  contrary to the rights



        of individuals to  the  use of  their property.



  (xv)   Because a regulator finds it  easier to  deny  a



        variance  rather  than grant  one,  many owners  or



        operators may  have to  comply  with the standard



        in its most stringent  aspect  even though it



        is impractical and unnecessay for them  to do



        so.   Furthermore,  the  use of  present and



        potential sites  which  would require a variance



        will be discouraged.



 (xvi)   200  feet  is the  minimum acceptable buffer



        distance  because:



             It will provide wording  space to attempt



             to correct  discharges  and a time delay



             before a  discharge would contaminate



             external  property.




                 - 176 -

-------
          It will prevent adjacent property from



          being contaminated before detection takes



          place and thus, costly remedial actions



          and law suits would be avoided.



Response




     Many of these comments have been responded to



in responses to buffer zone comments preceding these.



However, EPA does want to respond to a few commenters



who brought up different issues.  First, protection of



neighbors against spills and explosions at a hazardous



waste facility is certainly within EPA's mandate under



RCRA to protect human health.  However, contrary to



what another commenter suggested, EPA does not believe



that protecting the public against noise is within



RCRA's mandate.  Noise is usually controlled by local



ordinance.  EPA's facility standards do not contain



specific requirements for airborne pollutants during



"catastrophes".  Provisions are in place for the



emergency coordinator at a facility to assess the



danger to the surrounding public in the event of an



emergency, so that evacuation can be initiated imme-



diately if necessary.  Other facility standards



which protect the public from airborne pollutants



are in the incineration, thermal treatment, and



prohibition of open burning (except for restricted



detonation or burning of explosives) regulations.







             - 177 -

-------
        4.   Rationale for deletion of the proposed standard

             EPA has reevaluated the need for a buffer zone at

        hazardous waste facilities.  This reevaluation was

        prompted by the numerous comments received on the pro-

        posed standard and a subsequent comparison of the pro-

        tection afforded by the proposed buffer zone standard

        and that provided by the Part 264 and Part 265 standards.

        EPA determined that a general buffer zone requirement

        would be redundant of the facility standards.

             It is clear after reviewing the numerous comments

        submitted on the proposed buffer zone requirement that

        it is hard to specify a single buffer zone distance that

        is appropriate for, and feasible to institute at all

        hazardous waste facilities.  As one commenter pointed

        out, a single buffer zone distance is too arbitrary and

        inflexible to be universally applicable and therefore,

        it would be excessive in some cases and insufficient

        in others.

             Commenters suggested many factors that would

        influence the size of the buffer zone that is needed

        at a facility.  These factors included the type and

        size of the facility, the volume and degree of hazard

        of waste(s) handled at the facility, type of land use
Although unknown in practice, the purposes of the proposed buffer
zone standard cited in the rationale for the proposed standard
provide insight into the protection that EPA believed a buffer
zone could provide.
                           -  178  -

-------
surrounding the facility, and operating procedures prac-



ticed at the facility; particularly contingency plans



and emergency procedures.   It was also pointed out



that a buffer zone standard would be  impossible, or



extremely burdensome to  implement at  existing facilities.



     a.   Ignitable, reactive, and incompatible wastes



          One purpose of the proposed standard was to



     reduce risks to human health and the environment in



     the vicinity of the facility in  the event of a fire,



     explosion, or spill.  With respect to the first



     two; fires and explosions are usually associated



     with ignitable or reactive wastes or, the mixing



     of incompatible wastes.  The presence of toxic or



     corrosive waste may increase the hazards associated



     with a fire or explosion, but these waste are



     usually not the source of such acute incidents.



          The Agency has taken a different approach in



     the Phase I and Phase  II rules to protecting human



     health and the environment from  incidents such as



     fires and explosions which might occur during



     treatment, storage, or disposal  of ignitable,



     reactive and incompatible waste.  Instead of



     providing buffer zone protection through a location



     standard, the Agency has elected to tailor the



     protection to type  of waste handled at a facility



     and the operating units present  at a facility.
                    -  179  -

-------
     The regulations not only contain general



requirements for ignitable, reactive, and incom-



patible waste (Subpart B, §265.17), but specific



procedures for managing ignitable, reactive and



incompatible waste are specified for piles (§§264.256



and .257), containers (§§264-176 and .177), tanks



(§§264.198 and .199), surface impoundments (§§264.229



and .230), landfills (§265.312 and .313), and



chemical, physical, biological (§§265.405 and .406)



and land treatment (§§265.281 and  .282) facilities.



Ignitable and Reactive Wastes



     Standards which are most similar to the



proposed buffer zone requirement are "set-back"



distances for containers and tanks.  Specifically,



containers holding ignitable or reactive waste



must be located at least 15 meters (50 feet)  from



the facility's property line.  Covered tanks



which are used to treat or store ignitable or



reactive waste must be in compliance with the



National Fire Protection Association's (NFPA's)



buffer zone requirements for tanks, contained in



Tables 2-1 through 2-6 of the "Flammable and



Combustible Code - 1977."




     The remaining final standards for ignitable



and reactive waste are operational requirements



designed to prevent emergency incidents such as



fires and explosions.








              - 180 -

-------
Incompatible Wastes




     The final standards concerning management of



incompatible waste require that  incompatible wastes



must be separated during management.  For example,



storage containers holding hazardous waste that is



incompatible with any waste or other materials



stored nearby in other containers, piles, open



tanks, or surface impoundments must be separated



from the other materials or protected from them



by means of a dike, berm, wall,  or other device



(§264(5).I77(c)).  Under Section 264(5).17(b),



incompatible wastes and materials can only be



mixed or commingled if this does not:



(1)  Generate extreme heat or pressure, fire or



     explosion, or violent reaction;



(2)  Produce uncontrolled toxic  mists, fumes,



     dusts, or gases in sufficient quantities to



     threaten human health or the environment;



(3)  Produce uncontrolled flammable fumes or gases



     in sufficient quantities to pose a risk of




     fire or explosions;



(4)  Damage the structural integrity of the device




     or facility; or



(5)  Through other like means threaten human health




     or the environment.



     In addition, the waste analysis (§264(5).13)



standards are designed to ensure that owners and






              - 131 -

-------
operators know the identity and nature of the



wastes that they manage so that emergency incidents



due to mistaken identity will be minimized.




b.   Spills



     The Agency believes that the final Subtitle C



standards also adequately protect human health and



the environment from spills of hazardous waste.  The



purpose of the proposed buffer zone standard with



respect to spills was to provide a medium to bring



the hazardous waste into control before it crossed



the facility's property boundary and also to allow



the waste to dilute before it crossed the facility's



property boundary.  The final rules contain standards



for prevention of spills (e.g., maintaining sufficient



freeboard in uncovered tanks (§264(5).192) and



surface impoundments (§264(5).222)), containment of



spills (e.g., containment systems for storage areas



(§264.175)), and emergency procedures for cleaning up



of spills (§264(5).56 - Emergency Procedures).



The Preparedness and Prevention Standards specify



that adequate aisle space must be maintained at a



facility at all times to allow the unobstructed



movement of spill control and other emergency equip-



ment .   The contingency plan and emergency procedures



are required to be carried out immediately, and



therefore the spill should be controlled or at




least  purposefully diluted or decontaminated before






              - 182 -

-------
it crosses the facility's property line.



c.   Dissipation and control of discharges



     Another purpose of the proposed buffer zone



standard was to allow discharges resulting from



underground leaks to dissipate or be brought under



control before crossing the facility's property



line.  Operating and design requirements for the



different components (e.g., tanks, landfills)  of



facilities are designed, in part, to prevent under-



ground leaks.  Groundwater monitoring (Subpart F)



is required for components of facilities that  are



likely to be a source of underground leaks (e.g.,



landfills and surface impoundments) unless adequate



protection is otherwise provided.  For those parts



of facilities that are less likely to be a source



of underground leaks, inspections are required



(i.e., inspection of construction materials of



tanks (§264(5).194)).



d.   Odors and Noise



     The last purpose of the proposed buffer zone



standard was to conceal facilities and reduce



odors and noise reaching the surrounding community.



EPA believes that minimum set-backs for aesthetic



purposes are best handled at the local level.



     In summary, EPA believes that the Subtitle C



regulations will provide the needed degree of



protection to human health and the environment.






              - 183 -

-------
IV.   RESPONSE TO COMMENTS ON RELATED ISSUES
     A.    General Comments
          This section addresses those comments which were made with
     respect, to the general site selection standards taken as a whole,
          1.   Existing facilities
     C.         The general site selection standards (especially
          the standards concerning active fault zones,  regulatory
          floodways,  coastal high hazard areas, 500-year flood-
          plains,  and wetlands)  are overly stringent and will
          result in the closing of many well  designed and constructed
          existing facilities.   The performance (i.e.,  not causing
          environmental harm) of existing facility should be con-
          sidered  before deciding that  the facility must be closed
          for noncompliance with a specific design standard.   To
          force these facilities to close would create  a serious
          shortage of acceptable hazardous waste disposal facil-
          ities.   Furthermore,  to apply site  selection  standards
          to such  facilities would be contrary  to  Congressional
          intent to apply  only those standards  "as may  be necessary
          to protect  human health  and the environment".   If human
          health and  the environment are  already being  protected,
          site  selection standards  are  not necessary within the
          meaning  of  RCRA.
                           - 184 -

-------
     2.   Geographical  Impact  of  the  standards




C:        The site selection standards  will  rule  out con-



     struction and continued operation  of  facilities in



     many areas of the  country except at prohibitive cost.



     This is particularly true for  facilities that are or



     would be located in industrialized river valleys, the



     Gulf Coast, the Eastern States,  and California.  For



     example, coastal areas of states that border the



     Atlantic Ocean and the Gulf  of Mexico are designated



     as within a 500-year floodplain, coastal high hazard



     area, and regulatory floodway.



          This will create a serious  shortage of acceptable



     sites for hazardous waste facilities  in these areas,



     and it will pose a significant threat to public health



     due to the need to transport waste through populated



     and congested areas in order to reach facilities which



     can meet the siting requirements.  In addition, trans-



     portation costs will increase  waste management costs.



     Response to issues #1 and #2



          In the Location standards, the Agency has tried to



     lessen the impact  on facilities while continuing to pro-



     tect human health  and the environment.  Variance proce-



     dures, permit-conditional requirements, and a reasonable



     period of time for existing  facilities to comply with



     the floodplain standard provide the flexibility that



     is necessary so that certain geographical areas and



     existing facilities are not  inordinately penalized.






                        - 185 -

-------
     The Agency believes that the Location standards



are necessary to protect human health and the environment.



The subject areas of the Location standards were chosen



because the Agency feels that location in these areas



requires additional safeguards, or an absolute prohibi-



tion in the case of new facilities within 200 feet of



a fault which has had displacement in Holocene time.



     Furthermore, if existing facilities are designed



and operated in what EPA considers an environmentally



acceptable manner for the area that they are located



in, there should not be any problem in complying with



the floodplain standard.



     EPA believes that increased flexibility in the



Location standards should prevent the unnecessary



closing of facilities and therefore should prevent any



subsequent shortage of facilities and increased trans-



portation of hazardous waste.



3.   Applicability of site selection standards



     The site selection standards should not be applied



equally to all types of facilities.  In particular,



incinerators (or other facilities that destroy waste)



should not be restricted in siting considerations



because these facilities do not contain sufficient



quantities of waste to cause substantial harm to human



health or the environment.  There is inequity in applying



the same site selection criteria to treatment facilities



and land disposal facilities.  The general site selection









                   - 186 -

-------
standards should only  include  requirements  that
must be met by all treatment,  storage,  and  disposal
facilities.
     The proposed rules  contained  a  General Site
Selection section (250.43-1) and additional siting
requirements for landfills,  surface  impoundments, and
landfarms.  EPA has used the same  approach  in  the
Phase II rules.
     The relationship  between  a land disposal  facility
and groundwater and soil types necessitates a  more
in depth consideration of those parameters  when siting a
land disposal facility.   Therefore,  the  Phase  II rules
will specify additional  location requirements  for land-
fills, surface impoundments, and land treatment facilities
if they are deemed necessary (i.e.,  if  the  facility
standards are not adequately protective).
     EPA believes that the Location  standards  should
(§264.18) apply equally  to all facility  types.  However,
the floodplain standard  is only applicable  to  facilities
subject to regulation  under  Part 264, Subparts  I, J, K,«./»
-------
     it can be demonstrated that they can be safely operated



     or that adequate  safeguards can be provided.   The



     concept of the  general site selection standards is in-



     consistent with the  concept of minimizing the danger of



     release of hazardous waste  through specific operating




     and design standards.



R:        EPA believes that the  Location standards reinforce




     rather than contradict the  protection to human health



     and the environment  that  is afforded by the operating



     and design standards.   The  Agency believes that the



     standards which protect the facility from the environ-



     ment (e.g.,  100-year floodplain)  are necessary in order



     to minimize the possibility of uncontrolled release of



     hazardous waste because of  additional hazards associated



     with locating in  these areas.   Although not included in



     these Location  standards, other standards serve to



     protect the environment from the  adverse impacts of



     the facility (e.g.,  locating in a wetland or  critical



     habitat).  Those  standards  provide necessary  screening



     of facilities for potential impacts because fragile



     environments can  be  disturbed  or  destroyed simply by a



     facility locating there,  and indirect impacts such as



     increased traffic volume  compound the degradation.



          EPA agrees that in some cases,  the integrity of



     the design,  construction, operation,  and maintenance of



     the facility precludes the  need for a location standard.



     The deletion of the  proposed sole source aquifer general






                        - 190  -

-------
     siting standard is a case in point where EPA felt that

     protection of human health and the environment was ade-

     quately provided by the facility standards.  Thus, EPA

     deleted that location standard.

     6.    Inequity of regulations regarding hazardous waste
            and hazardous material management

C:        Facilities which store, treat, or incinerate

     hazardous waste pose no greater threat to human health

     and the environment than manufacturing plants which

     generate or store hazardous materials on-site,  and thus

     it is inequitable to regulate the location of the former

     and not the latter.  Also, it is unreasonable not to

     allow on-site storage, treatment, or incineration of

     these hazardous materials once they become hazardous

     wastes .

R:        RCRA takes effect once a material becomes a

     hazardous waste.  Manufacturers who generate hazardous

     waste are subject to the law and its regulations.  On-

     site facilities which store, treat, or incinerate

     hazardous wastes are also subject to the law and its

     regulations.  To alter this pattern of coverage would

     require legislative changes.

     7.    State/local regulation of facility location

C:        The standards should be less detailed in order to

     allow state/local authorities to develop regulations

     which are tailored to the characteristics of the

     individual state/locality.




                         -  191  -

-------
R:        Standards need to be as detailed as necessary to



     allow compliance.   EPA considers the level of detail in



     the Location standards appropriate.   States may not set



     requirements that  are less stringent than the Federal



     EPA program; however, they may set stricter requirements



     to tailor the standards to their particular circumstances,



C:        The standards should be more detailed in order to



     assist the States  in determining the suitability of



     hydroiogic, geologic, and soil parameters for the



     location of hazardous waste facilities.



R:        EPA will provide assistance on  determining the



     suitability of hydroiogic, geologic, and soil parameters



     by making available guidance manuals to  accompany the



     Location standards and the land disposal regulations.



C:        In view of the political difficulties associated



     with establishing  facilities in certain  states, and the



     possibility of inadequate disposal capacity,  if states



     fail to mandate means to allow facilities to locate



     within their boundaries, EPA should  step in and require



     the states to do so.



R:        RCRA does not give EPA the authority to step in



     and require States to mandate means  to permit estab-



     lishing facilities within their boundaries.  "Section



     3006(b) of RCRA provides that State  programs can only



     be approved if they are 'equivalent  to'  and 'consistent



     with1  the Federal  program."  (45 FR  33395, May 19, 1980)




     RCRA therefore "speaks only to the 'inconsistency1 of







                        - 192 -

-------
     State program submissions, not of State laws generally".




     However, "...State programs which contain provisions




     that prohibit treatment, storage or disposal of hazardous



     waste within the State, will be deemed inconsistent if



     the prohibition has no basis in human health or environ-



     mental protection." (45 FR 33395)  (See 45 FR 33395



     for a further discussion of this issue.)




C:        Where an owner or operator must demonstrate under



     the notes that his facility will not pose a threat to



     human health and the environment, state, as well as



     Federal, approval should be required in order to sanction



     the location of the facility.  In addition, where two



     or more notes are involved, a public hearing should be



     required so that local input can also be taken into



     cons ideration.



R:        All variance provisions that the permit applicant



     wants to comply with and demonstrations that the appli-



     cant wants to make will appear as cbnditions for issuance



     in the draft permit.  Pursuant to the Part 122-124 regu-



     lations (45 FR 33290, May 19, 1980),  issuance of a Federal



     permit does not relieve applicants from compliance with



     State requirements, therefore State approval is always



     required where the State has such authority, regardless



     of whether its program is approved.  Where EPA has juris-



     diction over the hazardous waste program,  State and local



     input can be submitted during the public comment period



     or at the public hearing.  Public hearings are held if






                        - 193 -

-------
     there is a significant degree of public interest in

     the draft permit.   See Part 124 (45 FR 33484,  May 19,

     1980) for more detail on the procedures for a  public

     hearing and procedures for appealing a permit.

C:        Site specific considerations are best handled at the

     State level (in contrast to the Federal or local level)

     because municipal  politicians are subject to intense

     local pressure to  disallow the location of facilities

     in their areas; i.e., municipal leaders may restrict

     the location of facilities in their localities based

     on political rather than environmental considerations.

R:        State politicians can likewise be subject to

     political pressures.  EPA has specified minimum Location

     standards and has  left many areas open where a state

     can fill in additional Location standards for  such

     concerns as odors, noise,  and proximity to residences,

     hospitals, and schools.

     8.   Variances to  the proposed coastal high hazard
            area, 500-year floodplain, wetlands, critical
            habitat, sole source aquifer, and buffer zone
            standards.

C:        The Regional  Adminstrator will-be unable  to give

     the necessary attention and in-depth study that each

     request for a variance demands.

R:        The variance  provisions have been minimized leaving

     a manageable burden on the Regional Administrator.

C:        The "Notes" should be included as part of the

     regulations because:



                        - 194 -

-------
          Even though they have the weight of law, if they



          were part of the rules, there would be no question




          as to the use of alternative engineering specifi-



          cations for some facilities.




          The legal effect of a note to a regulation is



          uncertain.




Rs        EPA has deleted the use of notes in the final



     standards.  Comments are provided for clarification.



C:        The "Notes" to the proposed standards should be



     deleted because:



     -    There is no reason to accept the attendant risk of



          allowing facilities to locate in environmentally



          sensitive areas.



          The standards should be applied uniformally across



          the nation.



     -    Performance standards at the time a permit is



          issued cannot ensure future reliability.



     -    They are contrary to EPA's Congressional  mandate



          and the intent of RCRA, which are to protect health



          and the environment.



R:        it is common practice to incorporate variances



     into standards.  In this case,  variances were  considered



     necessary because of the diversity of hazardous  waste



     facility designs and the range of wastes that  are poten-



     tially managed at a facility.  Variances are alternate



     means of providing equal protection to human health and



     the environment.  Sufficient flexibility has been  incor-






                        - 195 -

-------
          porated into the location standards so that variances,



          except in the case of the floodplain standard, were not




          necessary.



               EPA must also consider the impact of the standards



          and the ease with which the regulated community will be




          able to comply with such standards.  For example, where a



          standard has the potential to close many existing facil-



          ities and an alternate procedure is available which will



          be equally protective of human health and the environment



          and yet will result in less of an impact to the regulated



          community, EPA believes that owners or operators should



          be allowed to demonstrate compliance through the alternate



          procedure.



               Future reliability of a facility is ensured by the



          facility standards.  Also the location of a facility



          will be considered when a RCRA permit is modified or



          revoked if new information or standards indicate that a



          threat to human health or the environment exists which



          was unknown at the time for permit issuance (§122.15(c)).



     B.   Miscellaneous Comments



C:        If facilities are prohibited from the subject areas of



     the siting standards, forthcoming technological advancements



     to cope with siting in these areas will be stifled.



R:        The Agency does not agree.  Technological innovation could



     prompt the Agency to revise its regulations.  EPA supports the



     development of technologies to cope with siting in environmen-



     tally sensitive areas.






                             - 196 -

-------
C:         Federal lands should be screened for potential use as




     disposal sites because the large quantities of waste that will



     be designated "hazardous" will need disposal sites.




R:         EPA ls exploring with other Federal agencies both the



     desireability and the possibility of siting hazardous waste



     treatment,  storage, and disposal facilities on Federal lands.



     Results of this review will be incorporated, where appropriate,



     as amendments to the regulations.




C:         There should be no blanket prohibition against the use of



     any area as a disposal site; evaluation of each site would



     be more appropriate.




R:         EPA agrees with this commenter except in the case of facil-



     ities that propose to locate within 200 feet of a fault



     which has had displacement in Hoiocene time.  The technology



     is not available to build a safe facility within that area.



          An evaluation of each site is provided for in the



     permitting process.  The permitting official will evaluate



     if the location of the facility is in compliance with all



     applicable regulations.



C:         Due to the variable nature of the geology and climatology



     of the United States, the same site selection criteria can-



     not apply to every area of the States.  For example,  if



     waste acid/metal solutions which are hazardous due to their



     toxicity are released from a landfill in areas with basic



     soils, the acid would be neutralized and the metals immo-




     bilized by the cation exchange capacity of the soil.



R:         EPA has tried to make the Location standards flexible




     enough so that they can be applied to every area of the States.




                             - 197 -

-------
          States with authorized hazardous waste programs under



     §3006 of RCRA can specify additional or more stringent siting




     criteria that are needed in their States.



C:        The general siting requirements are not specific or



     stringent enough to assure that facilities will be sited in



     the best possible manner, and to adequately protect human



     health and the environment.



R:        EPA believes that the Location standards are specific and



     stringent enough to assure that facilities will be sited so



     that human health and the environment will be protected in



     those areas that are the subject of the standards.  EPA realizes



     however that the Location standards are not complete and EPA



     will continue to propose and finalize additional standards as



     the need arises.



C:        The special considerations that need to be taken into



     account for the geography of Louisiana are only accounted for



     through the note mechanism.



R:        It is difficult to answer this comment, as the commenter



     did not specify what he meant by "geography of Louisiana".



     However, EPA believes that adequate leeway has been provided



     in the Location standards.



C:        Many ponds and lagoons that are part of NPDES permitted



     facilities will fail the site selection criteria.




R:        Since NPDES permitted facilities are near surface water,



     the only Location standard that would directly impact NPDES facil-



     ities is the 100-year floodplain standard.  These facilities will



     be accommodated through the use of compliance schedules in their






                             - 198 -

-------
     permits.   EPA does not believe that the Location standards
     (§264.18)  will significantly burden NPDES ponds and lagoons.
C:         The  rules concerning protection of ground water should be
     strengthened.
R:         Because land disposal facilities pose a greater threat to
     contaminating ground water than other facility types,  more
     restrictive siting requirements may be specified in Subparts
     K,  M and  N, where they are deemed necessary, for protection
     of  ground water.
C:         The  proposed siting standards go beyond normal engineering
     design considerations and limit future expansion capabilities.
R:         The  Location standards are largely performance standards,
     and as such do not require particular designs.   Engineering
     designs do exist whereby the performance standards  can be  met.
     For example, the engineering technology exists  to reinforce an
     incinerator so that it can stand up and remain  intact  under the
     forces of a 100-year flood.  The guidance/permitting manual on
     the Location standards will provide information on  engineering
     design considerations.
          The  Location standards do not limit future expansion
     capabilities (i.e., future expansion is not specifically
     regulated) where the expansion is in conformance with  the
     Location  standards.  Commenters were particularly concerned
     that the  proposed buffer zone standard would limit  future
     expansion capabilities.  Because this standard  has  been
     deleted EPA believes that this concern has been largely
     relieved.

                             - 199 -

-------
     C.    Comments Requesting Additional Location Standards



          Comments were received which recommended consideration



     of additional Location standards.  These are summarized and




     responded to below.



C:   Farmland - because the treatment, storage,  and disposal of



     hazardous waste near farms has frequently endangered the



     quality of the farms'  livestock and produce.



R:        Although contamination of farmland may have occurred in



     the past from environmentally unsound treatment, storage, or



     disposal of hazardous  waste, the Part 264 and 265 operating



     and design requirements (in particular, the standards con-



     cerning spill confinement, diversion of run-on and collection



     of run-off, ground-water monitoring, and inspections) are



     designed, among other  things,  to minimize the potential



     for contaminating adjacent land by direct and indirect means.



C:   Surface water (rivers, lakes,  oceans, and reservoirs) -



     because much of the damage attributable to hazardous waste



     has occurred in these  areas, and has resulted in the contami-



     nation of drinking water and fisheries.



R:        The Section 3004  facility standards will minimize



     indirect contamination of surface water.  The standards



     controlling run-on and run-off, spills, leachate, and ground



     water monitoring will  be most effective in this regard.



     Surface waters are additionally protected by the floodplain



     siting restriction.




          Hazardous waste facilities will have to obtain permits



     pursuant to Sections 402 and 404 of the Clean Water Act  if







                             - 200 -

-------
    the facility  discharges pollutants or dredged or fill  material
    to surface waters.   Wild and scenic rivers  are also protected
    by Federal law.   (The guidance/permitting manual on the
    Location  standards  has a section on compliance with the  Wild
    and Scenic Rivers Act.)
          Because  of  these protection mechanisms already in place,
    EPA does  not  believe that an additional siting standard  is
    needed  for surface  waters.
C:   Cultural  resources  - because Section 106 of the National
    Historic  Preservation Act of 1966, as amended,  directs ail
    Federal agencies having direct or indirect  jurisdiction  over
    proposed  Federal or Federally-assisted undertakings to assess
    the effect of such  undertakings on any district,  site,
    building, structure, or object that is included in  or  eligible
    for  inclusion in the National Register of Historic  Places.
    In addition,  Federal agencies must give the Advisory Council
    on Historic  Preservation an opportunity to  comment  on  any
    such  undertaking in accordance with the Council's Procedures
    for the Protection of Historic and Cultural Properties (36
    CFR Part  800).
          because  Executive Order 11593 requires Federal agencies
          to consider, in consultation with the  Advisory Council,
          the  effect  of their programs and plans on both federally-
          owned and nonfederally-owned sites, structures, and
          objects  of  historical, architectural or archeological
          significance.

                             - 201  -

-------
R:        Part 122 - EPA administered permit programs - requires



     (§122.l2(b)) that the Regional Administrator adopt measures



     when feasible to mitigate potential adverse effects of the



     permitted activity on properties listed or eligible for



     listing in the National Register of Historic Places.  That



     Section further states that: "The Act's requirements are to



     be implemented in cooperation with State Historic Preserva-



     tion Officers and upon notice to, and when appropriate, in



     consultation with the Advisory Council on Historic Preser-



     vation." (see 45 FR 33428, May 19, 1980)



          Thus, EPA will consider effects on historical, architectural



     or archaeological sites before making a final decision on a



     permit application.  The guidance/permitting manual on the



     Location standards contains a section on compliance with



     the National Historic Preservation Act.



C:   Recreation resources - because the generator or permit



     applicant should be made aware of Section 6(f)  of the Land



     and Water Conservation Fund Act of 1965, as amended, and the



     provisions of the Surplus Property Act.  Both of these Acts



     may impact the permitting of hazardous waste facilities in



     certain locations.



R:        Land acquired pursuant to the Land and Water Conservation



     Fund Act and the Surplus Property Act will probably not be



     available for use as the site of a hazardous waste facility



     because of the purpose for which those areas are set aside.



     In any case, EPA cannot list every law that a permit applicant



     might be affected by.






                             - 202 -

-------
C:   Federal land - facility owners or operators should be made



     aware that facilities will not be allowed to locate on public



     land unless the Federal agency having administrative respon-



     sibility for that land approves the installation of the



     facility, and the owner or operator complies with all con-



     straints imposed on it by the responsible Federal agency.



R:        Although what this commenter suggested seems like a



     reasonable approach, EPA has not as yet formulated a policy



     with respect to locating hazardous waste facilities on



     Federal lands.  EPA will call upon other Federal Agencies



     including the Departments of Agriculture, Interior, Defense,



     the Council on Environmental Quality  (CEQ), and the Office



     of Management and Budget  (OMB) to be  directly involved in



     developing the policy.
                              - 203 -

-------
D.   Permafrost Areas



     I.    Proposed approach to permafrost areas



          In the preamble to the proposed rules (43 FR 58985,



     December 18, 1978), EPA recognized that permafrost areas



     are fragile ecosystems with a significant potential for



     erosion and groundwater contamination.  As such, the



     Agency believes that these areas should be protected from



     the uncontrolled siting of hazardous waste facilities.



     However, because the only State where permafrost areas



     are found is Alaska, the Agency also believes that it



     is more appropriate for the State of Alaska to determine



     what measures are needed to protect these areas.



     2.    Response to comments



C:        Permafrost areas should be classified as extremely



     sensitive (the commenter did not provide a rationale



     for his viewpoint).



R:        EPA agrees with the commenter in concept.  As was



     stated in the preamble to the proposed rules, EPA be-



     lieves that permafrost areas are "very fragile ecosystems."



C:   EPA's approach to permafrost areas is satisfactory,



     however, it is questionable whether relaxation in such



     fragile terrain is compatible with RCRA, and whether



     it sets an undesirable precedent - that is, will other




     states be able to regulate siting in environmentally



     sensitive areas in their state.



R:   EPA does not intend to take a relaxed attitude toward



     permafrost areas in Alaska.  EPA will continue to








                        - 204 -

-------
     study this problem until a standard can be proposed.



     If a State considers an environmentally sensitive area



     in their state to be an important consideration in



     siting facilities, and EPA has not promulgated a stan-



     dard that addresses these areas, EPA believes that



     states should promulgate such standards in keeping



     with the spirit of RCRA's mandate.




C:   The same logic used to allow Alaska to regulate perma-



     frost areas should also apply to States which have



     specific agencies set up to regulate certain industrial



     activities such as oil and gas exploration.



R:   EPA does not agree with the commenter.  Allowing States



     to regulate hazardous wastes from certain industrial



     activities does not follow logically from allowing



     Alaska to regulate siting of facilities in permafrost



     areas (if that were the case).  Permitting States to



     regulate hazardous waste from certain industrial activ-



     ities would result in a waste being regulated differently



     depending on which state the waste was managed in.  A



     potential result would be lenient regulation in States



     that want to attract industry.  If EPA was to allow



     States to regulate wastes from certain industries, EPA



     would have to set minimum standards.  This is in effect



     what will happen if EPA can fulfill its long term goal



     of writing industry specific standards in Part 266



     because a State can be authorized to carry out the



     Subtitle C regulatory program under RCRA if a States'






                        - 205 -

-------
program is equivalent to the Federal program.




Deferral of final action



     EPA received little comment on whom should write a



standard for locating in permafrost areas, EPA or the



State of Alaska.  After consulting with the Alaska



Department of Environmental Conservation, it is apparent



that there are no standards which regulate siting of



hazardous waste facilities in permafrost areas in



Alaska.  According to State officials, the Alaska



Department of Environmental Conservation is awaiting



the completion of studies on permafrost being conducted



by the University of Alaska at Fairbanks before



considering how such a standard should be written.



     EPA recognizes permafrost as an important site



condition which warrants a standard.  However, we do



not have sufficient background information at present



to justify a standard.  We are continuing to study this



problem and will come out with a standard at a later



time.  Should Alaska promulgate an adequate standard



as part of its State program, EPA would probably not



promulgate a standard.




     There are many unfavorable conditions associated



with permafrost areas which suggest that the location



of hazardous waste facilities in these areas should be



controlled.  Heat generated by operational units at a



facility may cause the permafrost to warm to 32°F and



thus melt.  This heated area .does not provide an accep-






                   -  206  -

-------
•table degree of ground support  for  structures located



on it; it can cause settling of the structures  (opera-



tional units at a facility) and structural damage.




     Permafrost itself is not stable and  is known to



cause ground movement with the  consequence of damaging



structures.  The frozen ground  will push-up, blistering



the surface of the land with jagged pieces of frozen



soil.



     A related problem has to do with thawing of the



surface or  "active" layer of permafrost during the



short summer season.  The ground surface  thaws to a



deptTi of  several inches, leaving the ground very wet.



"Summer travel on this thawed surface can disrupt the



fragile tundra vegetation.  This, in turn, can lead to



severe erosion."93  Thus, hazardous waste management




activities  may have to be restricted to certain times




of the year.
                    - 207 -

-------
V.   REGULATORY LANGUAGE



§264.18  Location standards



(a)  Seismic considerations



     (l)  Portions of new facilities where treatment, storage, or



disposal of hazardous waste will be conducted must not be located



within 61 meters (200 feet) of a fault which has had displacement




in Holocene time.



     (2)  As used in paragraph (a)(i) of this Section:



     (i)  "Fault" means a fracture along which rocks on one side have



          been displaced with respect to those on the other side.



    (ii)  "Displacement" means the relative movement of any two



          sides of a fault measured in any direction.



   (iii)  "Holocene" means the most recent epoch of the Quarternary



          period, extending from the end of the Pleistocene to the



          present.



[Comment:  Procedures for demonstrating compliance with this standard



in Part B of the permit application are specified in §122.25(a)(11).



Facilities which are located in political jurisdictions other than



those listed in Appendix VI of this Part, are assumed to be in com-



pliance with this requirement.]



(b)  Floodplains




     (1)  A facility located in a 100-year floodplain must be



designed, constructed,  operated and maintained to prevent washout



of any hazardous waste by a 100-year flood unless the owner or



operator can demonstrate to the Regional Administrator that



procedures are in effect which will cause the waste to be removed




safely,  before flood waters can reach the facility, to a location




where the wastes will not be vulnerable to floodwaters.




                             - 208 -

-------
[Comment;   The location where wastes are moved must be a facility



which is either permitted by EPA under Part 122 of this Chapter,




authorized to manage hazardous waste by a State with a hazardous



waste management program authorized under Part 123 of this Chapter,



or in interim status under Parts 122 and 265 of this Chapter.]



     (2)  As used in paragraph (b)(l) of this Section:



     (i)  "100-year floodplain" means any land area which is



          subject to a one percent or greater chance of flooding



          in any given year from any source.



    (ii)  "Washout" means the movement of hazardous waste from



          the active portion of a facility as a result of flooding.



   (iii)  "100-year flood" means a flood that has a. one percent



          chance of being equalled or exceeded in any given year.



[Comment;  (1) Requirements pertaining to other Federal laws



which affect the location and permitting of facilities are found



in §122.12 of this Chapter.  For details relative to these laws,



see EPA's manual for SEA (special environmental area) requirements



for hazardous waste facility permits.  Though EPA is responsible



for complying with these requirements, applicants are advised to



consider them in planning the location of a facility to help




prevent subsequent project delays.]
                              -  209  -

-------
                      Part 264, Appendix VI
        Political Jurisdictions* in which Compliance with
                 §264.18 (a) Must be Demonstrated
ALABAMA
  none

ALASKA
  Aleutian Islands
  Anchorage
  Bethel
  Bristol Bay
  Cordova-Valdez
  Fairbanks-Fort Yukon
  Juneau
  Kenai-Cook Inlet
  Ketchikan-Prince of Wales
  Kodiak
  Lynn Canal-Icy  Straits
  Palmer-Wasilla-Talkeena
  Seward
  Sitka
  Wade Hampton
  Wrangell Petersburg
  Yukon-Kuskokwim

ARIZONA
  Cochise
  Graham
  Greenlee
  Yuma

ARKANSAS
  Arkansas
  Clay
  Cleburne
  Craighead
  Crittenden
  Cross
  Fulton
  Greene
  Independence
  Izard
  Jackson
  Lawrence
ARKANSAS (continued)
  Lee
  Lonoke
  Mississippi
  Monroe
  Phillips
  Poinsett
  Polk
  Prairie
  Randolf
  Sharp
  St. Francis
  Stone
  White
  Woodruff

CALIFORNIA
  all

COLORADO
  Archuleta
  Conejos
  Hinsdale
  Mineral
  Rio Grande
  Saguache

CONNECTICUT
  all

DELAWARE
  none

FLORIDA
  none

GEORGIA
  Banks
  Barrow
  Bartow
* These include counties, city-county consolidations,  indepen-
  dent cities, and, in the case of Alaska, election districts,
                          - 210 -

-------
GEORGIA (continued)
  Bryan
  Builoch
  Burke
  Candler
  Catoosa
  Chatham
  Chattooga
  Cherokee
  Clarke
  Cobb
  Columbia
  Dade
  Dawson
  De Kalb
  Effingham
  Elbert
  Emanuel
  Fannin
  Floyd
  Forsyth
  Franklin
  Fulton
  Glascock
  Gilmer
  Gordon
  Greene
  Gwinnett
  Habersham
  Hall
  Hancock
  Hart
  Jackson
  Jasper
  Jefferson
  Jenkins
  Johnson
  Lincoln
  Lumpkin
  Madison
  McDuffie
  Morgan
  Murray
  Newton
  Oconee
  Oglethorpe
  Pickens
  Putnam
  Rabun
  Richmond
  Rockdale
  Screven
  Stephens
GEORGIA (continued)
  Talaferro
  Towns
  Treutlen
  Union
  Walker
  Walton
  Warren
  Washington
  White
  Whitfield
  Wilkes

HAWAII
  Hawaii
  Honolulu
  Maui

IDAHO
  Bannock
  Bear Lake
  Bingham
  Bonnevilie
  Caribou
  Cassia
  Clark
  Franklin
  Fremont
  Jefferson
  Madison
  Oneida
  Power
  Teton

ILLINOIS
  Alexander
  Bond
  Christian
  Clark
  Clay
  Clinton
  Coles
  Crawford
  Cumberland
  Douglas
  Edgar
  Edwards
  Effingham
  Fayette
  Franklin
  Gallatin
  Hamilton
                           - 211 -

-------
ILLINOIS (continued)
  Hardin
  Jackson
  Jasper
  Jefferson
  Jersey
  Johnson
  Lawrence
  Macoupin
  Madison
  Marion
  Massac
  Monroe
  Montgomery
  Moultrie
  Perry
  Pope
  Pulaski
  Randolf
  Richland
  Saline
  Shelby
  St. Clair
  Union
  Wabash
  Washington
  Wayne
  White
  Williamson

INDIANA
  Gibson
  Knox
  Posey
  Sullivan
  Vanderburgh

IOWA
  Fremont
  Mills
  Page

KANSAS
  Anderson
  Atchison
  Brown
  Coffey
  Doniphan
  Douglas
  Franklin
  Geary
  Jackson
  Jefferson
  Johnson
KANSAS (continued)
    Leavenworth
    Linn
    Lyon
    Marshall
    Miami
    Morris
    Nemaha
    Osage
    Pottawatomie
    Riley
    Shawnee
    Wabaunsee
    Washington
    Wyandotte

  KENTUCKY
    Ballard
    Bell
    Caldwell
    Galloway
    Carlisle
    Crittenden
    Fulton
    Graves
    Harlan
    Henderson
    Hickman
    Letcher
    Livingston
    Lyon
    Marshall
    McCracken
    Trigg
    Union
    Webster

  LOUISIANA
    none

  MAINE
    all

  MARYLAND
    none

  MASSACHUSETTS
    all

  MICHIGAN
    none

  MINNESOTA
    none
                           -  212  -

-------
MISSISSIPPI
  none

MISSOURI
  Boilinger
  Butler
  Cape Girardeau
  Carter
  Crawford
  Dent
  Dunk1in
  Franklin
  Howell
  Iron
  Jefferson
  Madison
  Mississippi
  New Madrid
  Oregon
  Pemiscot
  Perry
  Reynolds
  Ripley
  Scott
  Shannon
  St. Charles
  Ste. Genevieve
  St. Francois
  St. Louis
  St. Louis City
  Stoddard
  Texas
  Washington
  Wayne

MONTANA
  Beaverhead
  Broadwater
  Cascade
  Deer Lodge
  Flathead
  Gallatin
  Granite
  Jefferson
  Lake
  Lewis and Clark
  Madison
  Meagher
  Missoula
  Park
  Powell
  Sanders
  Silver Bow
MONTANA (continued)
   Stillwater
   Sweet Grass
   Teton
   Wheatland

 NEBRASKA
   Cass
   Gage
   Jefferson
   Johnson
   Lancaster
   Sarpy
   Otoe
   Nemaha
   Pawnee
   Richardson

 NEVADA
   all

 NEW HAMPSHIRE
   all

 NEW JERSEY
   Bergen
   Essex
   Hudson
   Hunterdon
   Mercer
   Middlesex
   Monmouth
   Morris
   Passaic
   Somerset
   Sussex
   Union
   Warren

 NEW MEXICO
   Bernalillo
   Catron
   Grant
   Hidalgo
   Los Alamos
   Rio Arriba
   Sandoval
   Santa Fe
   Sierra
   Socorro
   Taos
   Torrance
   Valencia
                           - 213 -

-------
NEW YORK
  Albany
  Bronx
  Clinton
  Columbia
  Delaware
  Dutchess
  Erie
  Essex
  Franklin
  Fulton
  Genesee
  Greene
  Hamilton
  Herkimer
  Jefferson
  Kings
  Lewis
  Montgomery
  Nassau
  New York
  Niagara
  Oneida
  Orange
  Orleans
  Otsego
  Putnam
  Queens
  Rensselaer
  Rich!and
  Richmond
  Rockland
  Saratoga
  Schenectady
  Schoharie
  St. Lawrence
  Suffolk
  Sullivan
  Ulster
  Warren
  Washington
  Westchester
  Wyoming

NORTH CAROLINA
  Alexander
  Alleghany
  Anson
  Ashe
  Avery
  Buncombe
  Burke
NORTH CAROLINA  (continued)
  Cabarrus
  Caldwell
  Catawba
  Cherokee
  Clay
  Cleveland
  Gaston
  Graham
  Haywood
  Henderson
  Iredell
  Jackson
  Lincoln
  Macon
  Madison
  McDowell
  Mecklenburg
  Mitchell
  Polk
  Richmond
  Rowan
  Rutherford
  Stanly
  Surry
  Swain
  Transylvania
  Union
  Watauga
  Wilkes
  Yancey

NORTH DAKOTA
  none

OHIO
  none

OKLAHOMA
  At oka
  Bryan
  Carter
  Choctaw
  Cleveland
  Coal
  Creek
  Garvin
  Grady
  Haskell
  Hughes
  Johnston
  Latimer
                           - 214 -

-------
OKLAHOMA (continued)
  Le Plore
  Lincoln
  Marshall
  McClain
  McCurtain
  Mclntosh
  Murray
  Muskogee
  Okfuskee
  Oklahoma
  Okmulgee
  Pittsburg
  Pontotoc
  Pot.tawat.omie
  Pushmataha
  Seminole
  Stephens
  Tulsa

OREGON
  none

PENNSYLVANIA
  Berks
  Bucks
  Carbon
  Chester
  Lackawanna
  Lancaster
  Lebanon
  Lehigh
  Luzerne
  Monroe
  Montgomery
  Northampton
  Pike
  Schuylkill
  Susquehanna
  Wayne
  Wyoming

RHODE ISLAND
  all

SOUTH CAROLINA
  all

SOUTH DAKOTA
  none

TENNESSEE
  Anderson
TENNESSEE (continued)
  Bledsoe
  Blount
  Bradley
  Campbell
  Carroll
  Carter
  Claiborne
  Cocke
  Crockett
  Cumberland
  Dyer
  Fayette
  Gibson
  Grainger
  Greene
  Hamblen
  Hamilton
  Hancock
  Hard email
  Hawkins
  Haywood
  Henry
  Jefferson
  Johnson
  Knox
  Lake
  Lauderdale
  Loudon
  Madison
  McMinn
  Meigs
  Monroe
  Morgan
  Ob ion
  Polk
  Rhea
  Roane
  Scott
  Sequatchie
  Sevier
  Shelby
  Sullivan
  Tipton
  Unicoi
  Union
  Washington
  Weakley

TEXAS
  none
                           - 215 -

-------
UTAH
  Beaver
  Box Elder
  Cache
  Carbon
  Davis
  Duchesne
  Emery
  Garfieid
  Iran
  Juab
  Millard
  Morgan
  Piute
  Rich
  Salt Lake
  Sanpete
  Sevier
  Summit
  Tooeie
  Utah
  Wasatch
  Washington
  Wayne
  Weber

VERMONT
  all

VIRGINIA
  Bland
  Buchanan
  Carroll
  Craig
  Dickenson
  Floyd
  Giles
  Grayson
  Lee
  Montgomery
  Puiaski
  Roanoke
  Russell
  Scott
  Smyth
  Tazewell
  Washington
  Wise
  Wythe
WASHINGTON
  Chelan
  Clallam
  Clark
  Cowlitz
  Douglas
  Ferry
  Grant
  Gray Harbor
  Jefferson
  King
  Kitsap
  Kittitas
  Lewis
  Mason
  Okanogan
  Pacific
  Pierce
  San Juan Islands
  Skagit
  Skamania
  Snohomish
  Thurston
  Wahkiakum
  Whatcom
  Yak ima

WEST VIRGINIA
  Mercer
  McDowell
  Monroe
  Summers

WISCONSIN
  none

WYOMING
  Fremont
  Lincoln
  Park
  Subiette
  Teton
  Uinta
  Yellowstone National  Park
                           - 216 -

-------
TERRITORIES OF THE UNITED STATES:

American Samoa
  all

Commonwealth of the Northern Mariana Islands
  all

Guam
  all

Puerto Rico
  all

U.S. Virgin Islands
  all
                           - 217 -

-------
VI.  REFERENCES

i.   Subcommittee on Water and Sewerage Systems.  "Earthquake
     Damage to Water and Sewerage Facilities", in Volume  II  of
     The San Fernando, California Earthquake of February  9,  1971.
     Geological Survey Professional Paper 733; 1971.

2.   Texas Department of Water Resources - Industrial Solid  Waste
     Management.  Technical Guideline No. 2; Site Selection  and
     Evaluation.  Issued:  5/13/76, Revised:  3/1/78.

3.   Minnesota Pollution Control Agency - Hazardous Waste Manage-
     ment Rules.  6 MCAR §4.9004 Location, Operation, and Closure
     of a Hazardous Waste Facility.  June 11, 1979.  (Draft: HW4,
     June 3, 1977).

4.   California State Water Resources Control Board - Waste  Dis-
     charge Requirements for Nonsewerable Waste Disposal to  Land.
     Article 2, §25lO(g).  January 1978.

5.   Op. Cit., Texas Technical Guideline No. 2

6.   New York State Environmental Quality Review, Part 617.
     Adopted:  September 1, 1978.  Effective: November 1, 1978.

7.   Op. Cit., Texas Technical Guideline No. 2.

8.   Op. Cit., Minnesota Rules, 6 MCAR §4.9004.

9.   Pennsylvania Department of Environmental Resources.  Chapter 75,
     Solid Waste Management Rules and Regulations.  Effective:
     June 27, 1977.

10.  Iowa Solid Waste Disposal Rules.  Chapter 28 - Sanitary Land-
     fills, §28.2.  Effective: October 1, 1971; last revised:
     August 31, 1978.

11.  New York State Department of Environmental Conservation.
     Part 360, Solid Waste Management Facilities.  §360.8 Facility
     Requirements.  May 17, 1977.

12.  Oklahoma State Department of Health Rules and Regulations
     for Industrial Waste Management.  3.0 Permit Requirements for
     Industrial Waste Disposal Sites or Processing Facilities.
     Effective: June 12, 1979.

13.  U.S. Army Corps of Engineers,  DOD.  Part 320 - General
     Regulatory Policies.  Federal Register.  Vol. 42, No. 138.
     Tuesday, July 19, 1977; p. 37133.

14.  U.S. Federal Emergency Management Agency.  "This is the
     Federal Emergency Management Agency".  March 1980.
                             - 218 -

-------
15.   U.S Department of Housing and Urban  Development, Federal
     Insurance Administration.  Federal Register.  Vol. 41,
     No. 207.  Tuesday, October 26,  1976; p.  46962-92.

16.   U.S. Department of the Army.  Office of  the Chief of Engineers.
     "Earthquake Design and Analysis  for  Corps of  Engineers Dams."
     April 30, 1977.  Regulation No.  1110-2-1806.

17.   Howard, K.A. and Others.  Preliminary Map of  Young Faults in
     the United States as a Guide to  Possible Fault Activity.
     1978.  U.S.G.S. Miscellaneous Field  Studies Map, MF-916.

18.   Taylor, C.L. and L.S. Ciuff.  Fault  Displacement and Ground
     Deformation Associated with Surface  Faulting; Proceedings of
     the Current State of Knowledge of Lifeline Earthquake
     Engineering.  ASCE Conference,  Los Angeles, Calif., Aug. 30 -
     31, 1977.

19.   Slemmons, David B. and Roy McKinney.  Definition of "Active
     Fault".  May 1977.  U.S. Army Engineer Waterways Experiment
     Station; Miscellaneous Paper S-77-8.

20.   California Division of Mines and Geology.  "Guidelines for
     Evaluating the Hazard of Surface Fault Rupture."  CDMG Note
     No. 49, revised January 1977.

21.   Taylor, Charles L. Associate Engineering Geologist, Woodward-
     Clyde Consultants, San Francisco, California.

22.   U.S. Environmental Protection Agency.  Draft guidance/permitting
     manual for the Location standards; Seismic Considerations,
     Appendix A.  December 29, 1980.

23.   Op. Cit., Map of Young Faults, 1978.

24.   Algermissen, S.T. and David M. Perkins.  A Probabilistic
     Estimate of Maximum Acceleration in  Rock in the Contiguous
     United States.  1976.  U.S.G.S. Open File Report 76-416.

25.   Op. Cit., U.S. E.P.A.  Draft guidance/permitting manual;
     Seismic Considerations, p. 11.

26.   Op. Cit., Taylor and Cluff.  1977.

27.   Op. Cit., U.S. E.P.A.  Draft guidance/permitting manual;
     Seismic Considerations, p. 6 and Appendix B.

28.   Bonilla, M.G.  Historic Surface Faulting in the Continental
     United States and Adjacent Parts of  Mexico. 1967. U.S.G.S.
     Reactor Technical Publication TID-24124.

29.   Ibid, p. 6.

30.   Op. Cit., Taylor and Cluff.  1977.

                             - 219 -

-------
31.  Taylor, Charles L.  "Comments on 61 Meters  (200 foot)  Set-
     Back Distance".  December 15, 1980.

32.  Op. Ctt., Bonilla, 1967.  p. 22.

33.  Op. Cit., Taylor and Cluff.  1977.

34.  California Seismic Safety Commission.  Goals and Policies
     for Earthquake Safety in California.  May 10, 1979.  p.  25.
     SSC 79-04.

35.  Hart, Earl W.  Fault-Rupture Hazard Zones in California.
     Revised March 1980.  California Division of Mines and
     Geology Special Publication 42.

36.  California Public Utilities Commission.  Liquefied Natural
     Gas Facilities Safety Standards.  Effective: July 5, 1979.
     §193.115 and Appendix B.

37.  Op. Cit., U.S. E.P.A.  Draft guidance/permitting manual;'
     Seismic Considerations,  Appendix C.

38.  Ibid.

39.  Op. Cit., California Division of Mines and Geology, CDMG
     Note No. 49.

40.  Op. Cit., Slemmons and McKinney, 1977.

41.  Ibid.

42.  Op. Cit., Department of the Armyt Regulation No. 1110-2-1806,

43.  Op. Cit., California Division of Mines and Geology, CDMG
     Note No. 49.

44.  Ibid.

45.  Applied Technology Council associated with the Structural
     Engineers Association of California.  Tentative Provisions
     for the Development of Seismic Regulations for Buildings.
     June 1978.National Bureau of Standards (U.S.), Special
     Publication 510.

46.  Op. Cit., Algermissen and Perkins, 1976.

47.  Op. Cit., U.S. E.P.A.  Draft guidance/permitting manual;
     Seismic Considerations,  p. 14-18.

48.  Op. Cit., Algermissen and Perkins, 1976. p. 24

49.  Op. Cit., Bonilla, 1967.  p. 21.
                             - 220 -

-------
50.   U.S. Nuclear Regulatory Commission.   General  Site  Suitability
     Criteria for Nuclear Power  Stations.   Regulatory Guide 4.7,
     Revision 1, November 1975.

51.   Op. Cit., California Public Utilities Commission,  LNG Facility
     Safety Standards.  Appendix B.

52.   Op. Cit., Map of Young Faults,  1978.

53.   Slemmons, D.B.  State-of-the-art  for  Assessing Earthquake
     Hazards in the United States  -  Faults and  Earthquake
     Magnitude.  May 1977.  U.S. Army  Corps of  Engineer Waterways
     Experiment Station.  Report No. 6, Misc. Paper S-73-1.

54.   See, for example:  U.S. Nuclear Regulatory Commission.
     Seismic Design Classification.  Regulatory Guide No. 1.29,
     Revision 3, September 1978.

55.   Op. Cit., U.S. E.P.A.  Draft  guidance/permitting manual;
     Seismic Considerations, Appendix  A.

56.   Federal Emergency Management  Agency,  Federal  Insurance
     Administration.  The Floodway;  A Guide for Community Permit
     Officials.  September 1979.   Community assistance series,
     No. 4.  HUD-529-FIA.

57.   Op. Cit., U.S. E.P.A.  Draft  guidance/permitting manual;
     Floodplains.  December 2, 1980.

58.   Ibid.

59.   U.S. Environmental Protection Agency, Office of Solid Waste.
     Guidance Manual for the Classification of  Solid Waste Disposal
     Facilities.November 1979. p.  8-18,19.

60.   Peace, Dick.  Regional Supervisor, Mooresville, North Carolina
     Regional Department of Natural  Resources and Community Develop-
     ment.  Confirmed by telephone by  Karen Walker, Environmental
     Scientist, E.P.A., Washington,  D.C.,  on May 16, 1980.

61.   Beane, Jim.  N.C. Department  of Natural and Economic Resources,
     Division of Community Assistance.  Confirmed by telephone by
     Karen Walker, Environmental Scientist, E.P.A., Washington, D-C.,
     on May 16, 1980.

62.   The case of United States of  America  v. Petro Processors of
     Louisiana, Inc., et al., Civil  Action No.  80-358-B.  United
     States District Court, Middle District of  Louisiana.  Filed
     on July 15, 1980.

63.   Kuchinski, Leon.  Pennsylvania  Department  of  Environmental
     Resources, Regional Solid Waste Manager.   Confirmed by
     telephone by Karen Walker,  Environmental Scientist, E.P.A.,
     Washington, D.C., on May 15,  1980.

                             - 221 -

-------
64.  Ingraham, R.J.  Commanding Officer, Marine Safety Office,  U.S.
     Coast Guard.  Confirmed by telephone by Karen Walker, Environ-
     mental Scientist, E.P.A., Washington, D.C., on May 16,  1980.

65.  U.S. Federal Emergency Management Agency, Federal Insurance
     Administration.  "National Flood Insurance Program."  §1909.1
     Definitions.  Federal Register.  Vol. 41, No. 207.  Tuesday,
     October 26, 1976.

66.  Memorandum from Cindy Hoppmann (Environmental Scientist, U.S.
     E.P.A., Washington, D.C.) to the Administrative Record  dated
     November 13, 1980.  "Coverage of Flood Hazard Boundary  Maps."

67.  Memorandum from Cindy Hoppmann to the Administrative Record
     dated November 13, 1980.  "Meeting with Craig Wingo, P.E.;
     Branch Chief, Map Appeals and Revisions, Program Implementa-
     tion Division, Federal Insurance Administration."

68.  Ibid.

69.  Ibid.

70.  U.S. Department of Housing and Urban Development, Federal
     Insurance Administration.  "Questions and Answers:  The
     National Flood Insurance Program".  March 1977, p. 3.

71.  Memorandum from Cindy Hoppmann to the Administrative Record
     dated November 17, 1980.  "Meeting with FIA hydrologist,
     Brian Mrazik."

72.  U.S. Environmental Protection Agency, Office of Solid Waste.
     Environmental Impact Statement - Criteria for Classification
     of Solid Waste Disposal Facilities and Practices.  December
     1979.  SW-821, p. III-3.

73.  Op. Cit., U.S. FEMA, FIA.  41 PR 46976.

74.  U.S. Department of the Army, Corps of Engineers, Office of
     the Chief of Engineers.  Wall Design - Flood Walls.  January
     1948.  EM 1110-2-2501.

     U.S. Department of the Army, Office of the Chief of Engineers.
     Design and Constructionof Levees.  31 March 1978.
     EM 1110-2-1913.

     U.S. Department of the Army, Office of the Chief of Engineers.
     Flood - Proofing Regulations.  June 1972.  EP-1165-2-314.

75.  U.S. Nuclear Regulatory Commission "Flood Protection for Nuclear
     Power Plants".  Regulatory Guide No. 1.102.  Revision 1,
     September 1976.

76.  Memorandum from Cindy Hoppmann to the Administrative Record
     dated December 2, 1980.  "Flood Proofing and Flood Protection
     Technology".

77.  Ibid.

                             - 222 -

-------
78.  Strahler, Arthur N. and Alan H. Strahler.   Introduction to
     Environmental Science.  1979.  Hamilton Publiching  Company,  p.331.

79.  Dawson, Alexandra D., J.D.  "Land Use  Implications  of  Wetland
     and Floodplain Regulation."  Zoning and Planning  Law Reports.
     Vol. 2, No. 12.  November 1979, p. 181.

80.  Op. Cit., EIS; SW-821.  p. 111-18.

81.  Horwitz, Elinor L.  Our Nation's Wetlands.  An  Interagency
     Task Force Report.  1978.  p. 1  U.S.  Government  Printing
     Office No. 041-011-00045-9.

82.  U.S. Department of Interior, Fish and  Wildlife  Service.
     Classification of Wetlands and Deepwater Habitats of the United
     States.December 1979.p.2.FWS/OBS - 79/31.

83.  U.S. Environmental Protection Agency.  "Protection  of  Nation's
     Wetlands - Policy Statement."  Federal Register.  Vol.  38,
     No. 84.  Wednesday, May 2, 1973; p. 10834-5.

     U.S. Environmental Protection Agency.  "Implementation  of
     Procedures on the National Environmental Policy Act".
     Appendix A - Statement of Procedures on Floodplain  Management
     and Wetlands Protection.  Federal Register.  Vol. 44, No.  216.
     Tuesday, November 6, 1979; p. 64191-3.

84.  Myhrum, Christopher B.  "Federal Protection of Wetlands through
     Legal Process."  Boston College Environmental Affairs Law  Review.
     Vol. 7, No. 4.  p. 568.

85.  Op. Cit., Horwitz, p.  1.

86.  Ibid.

87.  Op. Cit., Myhrum,  p. 573.

88.  Ibid.  p. 573.

89.  Ibid.  p. 574-575.

90.  U.S. Department of Interior,  Fish and Wildlife Service.  "Box
     Score of Species Listings".  Endangered Species Technical Bulletin.
     February 1980, Vol. V, No. 2.  p. 8.

91.  U.S. Environmental Protection Agency.  The Report to Congress;
     Waste Disposal Practices and their Effects on Ground Water.
     January 1977.

92.  Oklahoma State Department of Health Rules and Regulations for
     Industrial Waste Management.   4.0 Minimum Specifications for
     Controlled Industrial Waste Surface Disposal Sites.   Effective:
     June 12, 1979.

93.  Solid Waste on Federal Lands in Alaska;  A Report to Congress.
     Executive Summary Report.   p. 6.

                             - 223 -

-------
               Technical Documents Not Specifically
          Referenced in the Background Document But Used
               in Developing the Location Standards


Floodplains

Department of the Army, Office of the Chief of Engineers.  A Per-
spective on Flood Plain Regulations for Flood Plain Management.
June 1976.  EP-1165-2-304.

U.S. Army Corps of Engineers, Gaiveston District.  Guidelines for
Identifying Coastal High Hazard Zones.  June 1975.

U.S. Army Corps of Engineers, Coastal Engineering Research Center.
Shore Protection Manual, Volumes I, II, and III.  1977.

U.S. Department of the Interior, Bureau of Reclamation.  Design of
Small Dams.  1977.  (GPO Stock No. 024-003-00119-8).

U.S. Water Resources Council.  Guidelines for Determining Flood
Flow Frequency.  Bulletin 17A of the Hydrology Committee.  Revised:
June 1977.

U.S. Federal Emergency Management Agency, Federal Insurance and
Hazard Mitigation.  Statement of Work for Flood Insurance Studies.
April, 1979.
                             - 224 -

-------