WATER POLLUTION CONTROL
OIL AND HAZARDOUS MATERIALS PROGRAM SERIES   OHM 7106 002
   Pesticide  Poisoning of  Pond Lick  Lake, Ohio
            Investigation  and Resolution
ENVIRONMENTAL  PROTECTION AGENCY  •
                         •  OFFICE OF  WATER  PROGRAMS

-------
   Pesticide Poisoninq_of Pond Lick Lake, Ohio
          Investigation and Resolution
              June 2 - July 5, 1971
                  FINAL REPORT
                   Prepared by
Ryckman, Edgerley, Tomlinson and Associates,  Inc
               St. Louis, Missouri
          under Contract No.  68-01-0045
                       for
         Environmental Protection Agency
     Division of Oil and Hazardous Materials
           •"Office of Water Programs "
                Washington, D. C.

-------
                          FOREWORD


This report is one of a program series on the prevention  of
and responses to discharges of oil and hazardous materials
into the navigable waters of the U.S.  These actions are
carried out under the provisions of Section 11 and  12 of  the
Water Quality Improvement Act of 1970  (PL 91-224).  Other
reports have discussed topics on the state of the art, pre-
vention techniques and types of materials that may  be con-
sidered hazardous polluting substances.

The United States Environmental Protection Agency  (EPA) re-
cognized that an immediate response is essential in dealing
effectively with environmental incidents.  Therefore, in  1970
a program was organized through the Division of Oil and Haz-
ardous Materials of the Water Programs Office of EPA which
would facilitate a rapid response to hazardous spill emerg-
encies throughout the U.S.  The program calls for close co-
ordination between state, federal and private organizations.
In order to minimize the response time, and to supplement EPA
resources, several private contractors have been chosen in
various parts of the country to work with EPA on spills of
oil and other hazardous polluting substances.  Ryckman, Edgerley,
Tomlinson and Associates, Inc. (RETA) is one of those contract-
ors chosen to provide on site technical assistance  to EPA
during such emergencies.

This report prepared by the contractor describes the efforts
of the United States Environmental Protection Agency in ren-
dering assistance to the State of Ohio in order to combat a
potentially dangerous spill of a pesticide mixture in the
Pond Lick Reservoir near Portsmouth in southern Ohio.   The
investigation and resolution of this emergency,  as described
in the following report, were directed by the Division of Oil
and Hazardous Materials as On Scene Spill Coordinator,  with
the emergency technical assistance provided by the contractor
and the extensive support and able field activities of the
State of Ohio Department of Natural Resources.

               Dr. C. Hugh Thompson
               The Division of Oil and Hazardous Materials
               Office of Water Programs
               Environmental Protection Agency
               Washington, D. C.
                             11

-------
                       TABLE OF CONTENTS
Title Page	   i
Foreword	ii
Table of Contents	iii
List of Tables	   v
List of Figures	   v

SPILL DEFINITION	   1

ACTIVATION OF STATE AND FEDERAL RESPONSE TEAMS 	   4

     Initial Communications  	 . 	   4
     Organization and Personnel  	   6

INVESTIGATION AND RESOLUTION 	   6

     Chronological Overivew  	   6
     Treatment Process Selection 	   9
     Treatment System  	  13

EPILOGUE	22

     Unresolved Critical Issues  	  . 	  22
          A.  Ecological Recovery of Pond Lick Lake  .   .  22
          B.  Alternate Countermeasures  	  24

     Critique of Response Actions and Recommendations   .  25

     Incident at Shawnee:  Its Significance  	  27

APPENDIX A.  CHRONOLOGY OF PROJECT 	  28

     Exhibit A.  Statement of Work from
                 EPA/Washington to RETA
                 Authorizing Contract
                 No. 68-01-0045	28

     Exhibit B.  Chronology  	  29

     Exhibit C.  Critical Decisions  	  29

APPENDIX B.  SITUATION REPORTS, ENDRIN/STRYCHNINE
                 HAZARDOUS POLLUTING SUBSTANCE SPILLS   .  38

     Situation Report No. 1	39
     Situation Report No. 3	59

APPENDIX C.  GEOLOGICAL REPORT ... 	  73
                             ill

-------
APPENDIX D.  ALTERNATE STRATEGIES CONSIDERED 	  77



APPENDIX E.  TREATMENT SYSTEM  	  81




     Pilot Plant	81



     Design of Prototype Plant 	  84




     Construction  	  89




     Operation   	91



     Notes on Operation of Carbon Filter Plant 	  98




APPENDIX F.  FIELD DATA	108



     Sample Location Map	109



     Gas Chromatograph Analysis  	 Ill



     Fish Bioassay Analysis  	 114



     Temperature Profile, Pond Lick Lake	120




     Biological Survey 	 121



     Pilot Plant Data	128



     Prototype Plant Data	133



APPENDIX G.  NEWS RELEASES	138
                             IV

-------
                   LIST OF TABLES


No.    Title


1      Toxicity of Endrin                                3

2      Sequence of Events                                8

3      Pilot Plant Operating Data                       14

4      Typical Treatment Plant Operation                20


                  LIST OF FIGURES
1      Spill site location and its proximity to
       Ohio River                                        2

2      Watercourses threatened by poison in Pond
       Lick Lake                                         5

3      Project Organization                              7

4      Diversion dam and by-pass system installed
       at Pond Lick Lake                                10

5a     Spillway structure of Pond Lick Reservoir        11

5b     Temporary dam to cut off flow from influent
       stream to Pond Lick Lake                         11

6      Broadcasting activated carbon over surface
       of lake                                          12

7      Pilot plant start-up and operation               15

8      Gas chromatograph and Technician                 16

9      EPA On Scene Spill Coordinator and
       emergency response consultant work on
       last minute details of prototype treat-
       ment plant                                       18

10     Placement of activated carbon filter
       plant at Pond Lick Lake                          19
                           -v-

-------
No.    Title                                          Page


11     EPA Consultant checks flow of contaminated
       lake water into completed activated carbon
       filter assembly                                  21

12     North-South cross section, Pond Lick,
       Ohio Region                                      74

13     East-West schematic                              75

14     Isometric schematic of pilot plant               82

15a    Pilot plant under construction                   83

15b    Loading carbon in pilot plant column             83

16     Activated carbon filter for Pond                 87

17     Floating support for electric submersible
       pump installed to eliminate air bubbles
       in the carbon filter                             94

18     Spillway of dam and discharge of by-pass
       pipe during heavy rain                           96

19     Pona Lick Reservoir sample points               110
                         -vi-

-------
         PESTICIDE POISONING OF POND LICK LAKE, OHIO
                INVESTIGATION AND RESOLUTION
                    June 2 - July 5, 1971

                      SPILL DEFINITION

Pond Lick Reservoir  is located in the Shawnee State Forest
approximately ten miles southwest of Portsmouth, Ohio and
125 miles east of Cincinnati on the Ohio River.  (See Figure
1.)  At one time it served as a reservpir for an honor camp
of the Ohio penal system until that facility was closed down
several years ago.  With boating and fishing permitted, the
reservoir presently serves as a popular recreational site
within Shawnee State Park.  The lake is about 1,000 feet long
and 250 feet wide at its widest point, with regular shores
and no swamps.  A watershed of about 4.5 square miles drains
into the lake, which is about 35 feet deep at its deepest
point, with an average depth of about 15 feet.

On June 2, 1971 approximately one gallon of a mixture of a
concentrated pesticide solution and strychnine-treated corn,
which is often used for rodent control, was deliberately
dumped into the lake.2   Although the pesticide poison was
contained in a plastic gallon container which apparently
floated on the lake for a period of time, it eventually con-
taminated the lake and within days killed the lake wildlife,
including an estimated 3,400 sunfish, carp, blue gills, and
other fish together with numerous frogs, snakes, and other
aquatic life.  The plastic gallon container was eventually
recovered from the lake by the State of Ohio.  The pesti-
cide was determined to be an 18.6% Endrin wettable emulsion
with a petroleum hydrocarbon content of 73% and an inert con-
tent of 8.4%.  The wettable Endrin emulsion rapidly goes into
suspension in water; by the time the spill was discovered,
the Endrin had mixed with all the surface waters of the lake.
The measured Endrin concentration^ of greater than 9 parts
per billion  (ppb) in the lake water is consistent with the
estimated lake volume (approximately 15 million gallons) and
the assumed magnitude of the spill.  In the absence of normal
      Also referred to as Pond Lick Lake and Shawnee Lake.
     2
      Later a suspect was arrested and held in $3000 bail on
charges of destroying state property and wildlife.

      As discussed below, the concentration varied with depth
and was significantly less below the thermocline.

-------
   SPIU.SITE    PORTSMOUTH
      X
OHIO  RIVER
                     Figure I -  Spill site
                     location and  its prox-
                     imity to Ohio River.

-------
rains, the relatively low flow rate of Pond Lick Creek, which
was approximately 20 gallons per minute in the days  following
the spill, ensured that by the time EPA was contacted  and
emergency cleanup operations began several days later,  the
poison was still largely confined to the lake.  Nevertheless
by June 10, eight days following the spill, all the  fish up
to a distance of two-tenths of a mile downstream from  the
lake were killed and noticeable toxic effects in fish  and
other aquatic life up to a distance of six-tenths of a mile
downstream were noted.  Beyond that distance the aquatic
life was apparently normal.

The strychnine  (0.05 - 1.0%) that was spilled with the Endrin
was in an insoluble form on dried corn.  It was not  s mat-
ter of great concern in the incident because it was  not pre-
sent in large concentrations and strychnine readily breaks
down when exposed to sunlight.  Endrin, however,, is one of
the most toxic and persistent of the chlorinated hydrocar-
bons, and was present in concentrations considered to be  •,
toxic to humans, and deadly to fish and other aquatic life"1'
and wildlife, as shown in Table 1.

                           TABLE 1

                     TOXICITY OF ENDRIN
    Species

P. Calif ornica
P. Pulex
Blue gill
Gammarus Lacustris
                                            0,8
                                           20.0
                                            0.2
                                            4.7
                                  10 mg/kg
                                   3 mg/kg
                                   7 mg/kg
                                  14 mg/kg
      Dog
      Monkey
      Rabbit
      Quail
 (1)  "iReport oj[ theT Committee on_
      FWPCA, 1968.
 (2)   McKee and Wolf, Water Quality^ Criteria, 2nd ed
      Sacramento, California.
      For example TL1QO for blue gills is 0,6 ppb  (96 hours)

-------
The extreme toxicity of Endrin is compounded in seriousness
by two important facts:   (1)  it does not degrade rapidly
and, in fact, may persist in an aquatic environment for as
long as ten years; and  (2)  it is subject to "biological
magnification" in the aquatic food chain.  That is, even
if it were present in vastly diluted concentrations from
that found in the lake, which could happen if it were
allowed to continue downstream, primary producers and pre-
dator organisms can concentrate the poison in their bodies
to a high degree by feeding upon other organisms that have
picked up lesser amounts of the Endrin poison.  In this way
aquatic life such as catfish might pick up levels of Endrin
in their bodies that exceed Federal Drug Administration
standards for human consumption even though the aquatic en-
vironment contains only trace amounts of Endrin.

       ACTIVATION OF STATE AND FEDERAL RESPONSE TEAMS

Initial Communications

When the spill was discovered, officials of the Ohio Depart-
ment of Natural Resources were concerned by the proximity of
Pond Lick Lake to the Ohio River.  As shown in Figure 2, the
lake is less than 10 miles from the Ohio River.  The spill
thus posed a potential threat to the river.  Because of the
potential magnitude of the problem, on June 10 the Department
of Natural Resources asked the Chicago office of EPA for
assistance.  Because the threat to the Ohio River was suf-
ficiently great to require EPA assistance in the incident,
Mr. Angell Sidio of the National Field Investigative team of
the Cincinnati office of EPA reported to the site on June 10.
Dr. C. Hugh Thompson, Division of Oil and Hazardous Materi-
als of EPA/Washington was informed of the spill on June 12.
Due to the imminent and substantial threat to the Ohio River,
the Emergency Response Contractor, Ryckman, Edgerley, Tom-
linson and Associates  (RETA) was activated to provide im-
mediate on-site technical assistance to determine the ade-
quacy of the measures already implemented by the State and
to suggest alternate countermeasures.  In addition, the con-
tractor was asked to provide technical advice to Mr. Sidio
and other EPA personnel on-site, and to undertake limited
downstream observations and photographs necessary to prepare
an incident report dealing with the causes, effectiveness
of counter measures, timeliness of response, short-term and
long-term effects of the spill and steps that may be taken
in the future to prevent such a spill incident.

-------
Ul
                                                           THREATENED WATERCOURSE
                                                                          Figare 2 - Watercourses
                                                                          threatened by  poison in
                                                                          Pond Lick Lake.

-------
Organization and Personnel

The organization and management of this project is depicted
schematically in Figure 3.  The diagram illustrates the work-
ing relationship between the State of Ohio, the United States
Environmental Protection Agency and the Emergency Response
Contractor.

William B. Nye, Director of the Ohio Department of Natural
Resources, was ultimately responsible for the success of the
project.  Through his efforts, adequate manpower was made
available for all tasks.  Dr. C. Hugh Thompson, Chief, Haz-
ardous Materials Branch of the Division of Oil and Hazardous
Materials, EPA/Washington, directed the teams organized to
efficiently resolve the hazardous spill emergency.  The emer-
gency contractor, RETA, as advisor to the Environmental Pro-
tection Agency, provided immediate on-site technical exper-
tise.

                INVESTIGATION AND RESOLUTION

This section presents  (1) a broad overview of the project
through a brief chronological tabulation of events; (2) a
description of key events leading to the selection of the
design, construction, start-up and operation of the treatment
plant.

Chronological Overview

Table 2 outlines the daily activities of key personnel of the
State of Ohio, the U. S. Environmental Protection Agency,
and the Emergency Response Contractor.  Table 2 is an attempt
to illustrate some of the interactions that occurred during
the incident from the initial spill of the Endrin to notifica-
tion and activation of the State/Federal response team and sub-
sequent design, construction, and operation of the prototype
treatment plant.  The sequence of events for each day are
listed under the group most responsible for them.   By studying
the chart, the progress of the project can be followed and the
contributions of each team member ascertained.

Further elaboration of the chronological events with em-
phasis on project initiation and activation and the critical
decisions which controlled the direction of action by the
team, is presented in Appendix A, Chronology of_ Project.

-------
             FEDERAL GOVERNMENT
                UNITED STATES
        ENVIRONMENTAL PROTECTION AGENCY
                                                 STATE OF OHIO
                                        DEPARTMENT OF NATURAL RESOURCES
                                           W,  NYE/  DIRECTOR
     NATIONAL
      FIELD
   INVESTIGATIVE
      TEAM
CINCINNATI, OHIO
     A,  SIDIO
       EPA
   REGION V
CHICAGO,  ILLINOIS
       FIELD OFFICE
     WHEELING/  VI,  VA,
     R,  B,  GRIFFITH
    DIV,  OF OIL AND
  HAZARDOUS MATERIALS
K, E,  BIGLANE,  DIRECTOR
  HAZARDOUS MATERIALS
         BRANCH
C,  H,  THOMPSON, CHIEF
         FIELD OFFICE
        EVANSVILLE,  IND,
        D,  H,  STOLTENBERG
               DIVISION OF
                WILDLIFE
              D,  ARMBRUSTER
                E,  RIDGE
                                             EMERGENCY
                                             RESPONSE
                                            CONTRACTOR
                                       G,  M,  BARSOM,  RETA
                                         PROJECT MANAGER
                                       S,  J,  RYCKMAN, RETA
                                           FIELD MANAGER
DIVISION OF
   WATER
A, WALKER
H, EAGAN
                                           OHIO STATE
                                           UNIVERSITY
                                               GAS
                                           CHROMATOGRAPH
                                            D,  HOWARD
ASSISTANT
DIRECTOR
D, MEEKER
                                              CHIEF
                                             ENGINEER
                                         J, SWARTZMILLER
                           FIGURE 3 -- PROJECT ORGANIZATION

-------



OHIO


















EPA






















D C*1*A
RETA





SEQUENCE OF EVENTS
Wed. (Thursday
June 2 | June 10
Poison IDNR asks
dumped ii
lake in
Ohio
















































i EPA for
assis-
tance








EPA
notified
National
Field
Team to
scene


































Friday
June 11
Spillway
dammed









Bioassay
Fish die
2 hours
G. G.
sample
to Cinn.

Dam
spillway































Sat.
June 12
Diversio
dam
s tarted
Activate
Carbon o
lake







C. H.
Thompson
notified

Informa-
tfor,
gathered

National
Field
Investi-
gative
Team in-
put to
Hazard-
ous
Material
Branch









RETA
notified

Accepts
job








Sunday
June 13
Finish
diversio
sion dam
Begin
by-pass

Raise
Sandbags

Post
guard
around
lake
Bioassay
& Chem-
ical
analyses

Stream
damage
survey .
Suggest
stop
using
wells in
area.














RETA to
field
from
Dayton &
St .Louis

Assess
damage
Recom-
mend no
more
carbon


Monday
June 1U
Raised
dam
Built
by-pass
Set up
pumps







Depth
sample s
taken,
temper-
ature
profile

C. H.
Thompson
receives
report
















Prepared
situa-
tion
report,
Tuesday
June 15
Formal
assis-
tance
request
sent to
EPA

W. Nye,
meets
CHT in
travel
to site


CHT to
Columbus
meets
with DNR
travels
to site

CHT de-
cides
pilot
plant
needed

Compre-
hensive
sampling
program
reques-
ted








Design
Pilot
Plant ,
start
delivered con-.
to CHT
Second
report
sent





struc-
tion






Wed.
June 16
Power in
stalled
at dam
W. Nye
locates
G. C. at
O.S.U.

Build
pilot
plant


CHT
attempts
to lo-
cate EPA
carbon
filter
plants.
All are
in use

CHT
works to
find GC














Build
pilot
plant

Pilot
Plant
Opera-
tion
begun at
Thursday
June 17
- 2:a.m.
G. C.
arrives
at dam
with
D. Howart

Telephon<
installed
at site




2 a.m.
CHT, D.
Howard
set up
G.C.

Results
at lOa.m
pilot
plant
working

CHT
locates
tank for
proto-
type
plant

Dec ides
to build
proto-
type
based on
pilot
plant
success
Operate
and
sample
pilot
plant

Begin
design
calcula-
10: 30p.m. t ions on





prbto-
tvpe
J r
plant


Friday
June 18
G.C.
analysis
shows
good
pilot
plant
opera-
tion

Build
proto-
type
plant

6 a.m.
Repairs
Pilot
Plant

CHT
directs
con-
struc-
tion of
proto-
type















Detailed
Construc-
tion
descrip-
tion by
SJR







Sat.
June 19
Complete
proto-
type
plant








Construe
tion con'
tinues

Plant in
opera-
tion
5:30 p.m

Air
bubbles
in fil.
ter
cause
problems
shut
down
proto-
type
plant




















Sunday
June 20
Modify
filter
Dave
Howard
briefed
on safety

Dave
Howard
briefed
on safety


Modify
filter

CHT
leaves

Dave
Stolten-
berg in
charge

















Modify
filter

Restart









Monday
June 21
State to
pick up
as EPA
pulls
out



































Filter
Modifi-
cations
with
state

Need for
24 hour
opera-
tors
noted




\fed.
June 23
Electric
submer-
sible
pump
ordered
to stop
air
bubbles

































Opera-
ting &
emer-
gency
proceed-
ure
instruc-
tions
created






Thur sday
June 2t
Slectric
"ump
Operation
2:-30 p.m.
No air
in filter



































Friday
June 25
Heavy
rain,
lake
level
rises
18"








Confer-
ence CHT
about
heavy
rain
condi-
tions




















fl
Sat.
June 2 6
Condi-
tions
stabi-
lized
Con-
struc-
tion of
emer-
gency
spillway
filter
begins




























HBLE 2
Monday
June 28
Filter
and
spillway
filter
operate
to *»00
GPM




































KEY:

DNR Ohio Department of
Natural Resources
EPA Federal Environmental
Protection Agency
RETA Ryckman, Edgerley,
Tomlinson, & Associates

CHT Dr. C. H. Thompson
SJR S. J. Ryckman
G.C. Gas Chromatograph

-------
Treatment Process Selection

The Ohio Department of Natural Resources undertook the pro-
ject under the leadership of William B. Nye, whose objective
throughout was to handle the project in the best interests
of the citizens of Ohio and cleanse the lake as quickly as
possible.  The Ohio team initiated the critical first step
of isolating  the reservoir.  They accomplished this by sand-
bagging the spillway, building an earth diversion dam up-
stream from the lake, and providing two 2,500 GPM pumps and
10 inch aluminum piping to enable Pond Lick Creek to bypass
the now isolated reservoir  (see Figures 4, 5a and 5b).  The
dam was completed Sunday night, June 13, 1971, and the pump-
ing system was completed on Monday, June 14.  The bypass
system was a temporary one designed to protect the lake if
rain occurred in the area.  Because of its limited capacity
in the event of a heavy rain, Ohio officials stressed the
need for a quick cleanup action.  Bags of activated char-
coal were added to the spillway to cleanse the seepage and
a pump was added in the downstream stilling basin to pump
the seepage back into the reservoir.

The first EPA support to arrive on the scene was the National
Field Investigative Team  (NFIT) from Cincinnati.  Together
with the Ohio group they first attempted to reduce the con-
centration of Endrin in the reservoir by broadcasting appro-
ximately 6,800 pounds of 40 mesh granular activated charcoal
(see Figure 6).  The method had the advantages of being quick,
easy and inexpensive, and it achieved a limited reduction in
Endrin concentration.  However, subsequent investigation
showed that for the type of activated carbon available, the
contact time, that is, the time before the activated carbon
settled to the lake bottom, was insufficient to reduce the
Endrin concentration to tolerable levels.  Furthermore, un-
less subsequently removed, the Endrin could adversely effect
the benthos or desorb from the carbon into the lake water.

The Emergency Response Contractor made a systematic investi-
gation of the extent of the contamination, the effects, the
topographic characteristics pertinent to a solution of the
problem, and a study of possible countermeasures.  On the spot
observations were collected and issued in a series of situa-
tion reports on June 14 through June 18, for the use of the
men working at the site, for EPA information, and for later
use as documentation (see Appendix B).

Upon arrival at the site on Sunday, June 13, the Contractor
reviewed and agreed with Ohio's plans for the diversion dam
and pumping system and recommended increasing the height of
the sandbags on the spillway.  The Contractor also suggested

-------
    DIVERSION  DAM
H
O
                                                                     oh—VALVE  BOH
                                                                      U—ORIGINAL  DAM
SPILLWAY
STILLING WELL
   BY-PASS PUMPS
                                                                        FIGURE 4
                                                                  DIVERSION DAM AND BY-
                                                                  PASS  SYSTEM INSTALLED
                                                                   AT  POND LICK  LAKE

-------

Figure 5a - Spillway structure of  Pon
            Note sandbagc                     md
            of activated ca
            from contar.

Fiqure 5b -
;...*orary dam to cu

         s upstream


-------
Figure 6 -
Broadcasting activated carbon over surface
of lake in an early attempt to remove
Endrin from the water.  (Courtesy Ports-
mouth Times)
                        12

-------
to NFIT that the public be kept away from the area.  NFIT
advised the state and officials implemented the quarantine
later in the day Sunday.

An initial concern was the possible contamination of ground
water, and nearby wells in particular.  The Department of
Natural Resources, Division of Water, provided the Contractor
with well logs and basic information which enabled rapid re-
porting on the geology of the area.  This information showed
that a 40 foot thick layer of impermeable shale separated
the lake from ground water, andj that ground water in the
area was very poor.  Many drilled wells are dry or provide a
flow of less than five gallons,per minute.  It was concluded
that it was unlikely that any ground water contamination
would occur unless the entire:lake were to drain to the Ohio
River flood plain at one timef  The flood plain contains
aquifers which are potential!^ very good sources of water.
These aquifers might be endangered by either a rapid dis-
charge of the water or activity such as landfilling bottom
material scraped from the lake.  A complete geological de-
scription of the region surrounding Pond Lick Reservoir is
presented in Appendix C.

Treatment System

Next, and most importantJ it was essential to devise an
effective means of eliminating the Endrin contamination.
The countermeasures which were proposed and discussed are
presented in Appendix D.  However, the method of treating
the lake water by running it through an activated carbon
contact bed seemed most attractive.  Because of the earlier
failure of carbon to significantly reduce the Endrin concen-
tration, the EPA Oij Scene Spill Coordinator (OSSC) made the
decision on June 15, 1971, to construct and operate a pilot
plant to determines

     a.   the ability of carbon to remove Endrin and pro-
          duce an effluent non-toxic to aquatic life.

     b.   the absorptive capacity of activated carbon for
          Endrin.

     c.   the necessary loading rates for proper carbon con-
          tact and Endrin absorption.

     d.   how to best construct the filter system.

     e.   whether a pre-filter was needed to remove suspended
          material.


                             13

-------
The Emergency Response Contractor designed the pilot plant
based upon rough sketches provided by the EPA On Scene Spill
Coordinator (OSSC)  and aided the Ohio workers in building the
plant on the night of June 15.  The plant was in operation by
the afternoon of the next day, June 16.  The pilot plant
installed on the dam is shown undergoing adjustments in
Figure 7.

In order to optimize operation of the pilot plant, it was
necessary to monitor the Endrin concentration influent and
effluent to the process.  The only available analytical
instrumentation was located in the EPA Cincinnati labora-
tories.  This was inadequate to properly optimize the pilot
plant performance because of the several days delay involved
in transporting the sample to Cincinnati.  In order to al-
leviate this constraint, the OSSC initiated an intensive
nation-wide search to locate a portable gas chromatograph
and operator that could be flown to the spill site.  The
OSSC search, which began on June 13, was successfully con-
cluded on June 16 by the State of Ohio following a lead of
the OSSC.  The Ohio State University instrument was trans-
ported to the site and set up in an old CCC camp kitchen which
was quickly converted into a laboratory.  With the OSSC's help,
the operator1 calibrated the chromatograph and placed it in
operation in the early hours of June 17, 1971 (see Figure 8).
                           TABLE 3

                 PILOT PLANT OPERATING DATA
Endrin Concentration (pjDb)
Influent
6.66
6.66
6.66
6.66
6.66
6.66
6.66
6.66
6.66
Effluent
0
0
0
0
0
0
0
0.050
0.050
Flow
gpm

3.7
3.3
7.5
7.3
1.1
7.0
7.0
5.7
Hours of
Operation
0
1
2
3
4
5
10
11
40
Gallons
Treated
0
220
420
870
1,340
1,410
3,550
3,970
13,880
      David Howard, Ph.D. candidate, Department of Biology
Ohio State University.                                   J
                             14

-------
Figure 7  - Pilot plant start-up and operation.
                       15

-------
Figure 8  - Gas chromatograph and technician are
            pressed into vital analytical work
            on site within 6 hours after arrival
            on scene.   (Courtesy Portsmouth Times)
                      16

-------
Based on the success of the pilot plant as shown by the data
in Table 3, the OSSC decided to see if enough equipment was
available to construct a large scale treatment plant based
on the design parameters verified by the pilot plant.  By a
search of EPA resources, the OSSC was able to locate a large
cypress box built for a research project in water treatment
methods.  This container was of a suitable size for the Pond
Lick treatment plant and the OSSC and Shawnee State Park per-
sonnel 1 were able to arrange immediate shipment of the box
on Thursday night, June 17.  The treatment system design was
completed Thursday night and construction began at dawn Friday,
June 18.  Figure 9 shows the construction in progress.  By
Saturday evening the filter was finished and placed in opera-
tion.  Several operational difficulties were discovered and
corrected by design modification and operation over the next
week.

Two types of trouble plagued the plant:  first, fine carbon
particles were washed out of the filter and were trapped by
the material forming the top of the filter, which was a com-
bination of vermiculite, clay and cloth.  This was corrected
by replacing the top with a wire screen assembly.  The second
problem was that of air drawn into the suction side of the
supply pump which was a converted military fire pump.  The
air bubbles disturbed the carbon bed and allowed Endrin to
short circuit untreated.  This was reflected in effluent read-
ings from the treatment plant, which is presented in great
detail in Appendix F.  The final solution to this problem was
the installation of a submersible electric pump in the lake on
June 23.  The placement of the activated carbon filter plant
is depicted schematically in Figure 10.

To increase the rate of treatment a second, gravity operated
filter was built by damming the lower end of the spillway
and letting water flow up through a bed of carbon in the bot-
tom of the spillway near the stilling well.  A treatment rate
of about 400 gpm was maintained since early July using this
scheme.  Samples were taken regularly from the stilling well
and analyzed by gas chromatography.  If the Endrin level ex-
ceeded a value of 0.4 ppb in this pool, emergency procedures
outlined in Appendix E, Notes on Operation Section, were put
into effect.  Table 4 below includes typical operation data
for the pressure filter.  More complete data is collected in
Appendix F, Field Data.  Figure 11 shows an Emergency Response
engineer evaluating the flow and performance of the completed
and installed filter assembly.
      Mr. Everett Ridge, District Supervisor, Department of
Natrual Resources, State of Ohio, and his staff.

                             17

-------

Figure 9  - T''                              'tor s
            emergem      sulta:
            details of protot-
                                 •; to 1
            filter undergoes modification by
                     orkers a-        ick Lake.
            (Courtesy Portsmouth Times)

-------
 DIVERSION 0AM
BY-PASS PUMPS
                                                                       VALVE  BOX

                                                                   J^-ORIGINAL  DAM

                                                                       ELEC. SUBMERSIBLE PUMP
QMD-bf^K
  LAKE
                                                                    -—SPILLWAY
                                                                       STILLING  WELL
                                                                             LOW METER
                                                               CARBON FILTER BOX
                                                                       FIGURE  10
                                                                PLACEMENT OF ACTIVATED
                                                                CARBON  FILTER  PLANT
                                                                  AT  POND  LICK  LAKE

-------
                           TABLE 4




              TYPICAL TREATMENT PLANT OPERATION
Date
6/19
6/20
6/20
6/21
6/22
* 6/24
6/24
6/24
6/25
Endrin Concentration (ppb)
Lake
3.8
7.2

9.0
6.15
7
7


Effluent
0
0
0.063
0.100
.65
.1
.03
.2
.28
Flow Rate Number of
Hours in
(gpm) Operation
47
91
198
115
118
168
168
178
169
0
13.5
23.5
38.5
63
69
75.5
86.5
90.5
* Submersible electric pump placed in operation
                             20

-------
Figure 11 - EPA consultant checks the flow of con-
            taminated lake water into the completed
            activated carbon filter assembly.  Filter
            was placed in operation one week after
            EPA was notified of spill.   (Courtesy
            Portsmouth Times)
                      21

-------
                          EPILOGUE
The dispatch with which the State of Ohio, the U. S. Environ-
mental Protection Agency and the Emergency Response Contractor
investigated and resolved the hazardous spill emergency at
Pond Lick Lake is a credit to the scientific and engineering
capabilities and manpower and resource mobility of each or-
ganization.  The cleanup and removal of Endrin proceeded
carefully, thus eliminating any threat to the Ohio River and
the surrounding populace.

During and following any such operation, however, certain
improvements, modifications and unresolved issues become
evident; these bear great significance for the future re-
solution of emergencies such as the incident at Shawnee.
The following briefly summarizes those critical yet unresolved
issues as well as suggested improvements to incident control
procedures.


Unresolved Critical Issues

During the crisis period, several issues were raised which
were discarded in favor of other alternatives.  Some of
these issues need to be focused upon for their value and use
in preventing and controlling future incidents.

A.    Ecological Recovery of Pond Lick Lake

It appears from the available information that the long-term
ecological damage resulting from the strychnine will be mini-
mal.  Endrin, however, is a highly toxic chlorinated hydro-
carbon pesticide with high toxicity to both fish and mamma-
lian forms.  Although it is a stereo isomer of Dieldrin, it
differs from Dieldrin in that it has higher acute toxicity,
it is more rapidly metabolized in plant and animal tissues,
and it does not appear to be a persistent insecticide in
vertebrates.1  For this reason, it is possible that problems
with biological magnification will be less with Endrin than
would be the case with other chlorinated hydrocarbon pesti-
cides .

In order to adequately assess these problems, it will be nec-
essary to determine the present chemical, physical and biolo-
gical characteristics of the tributaries into and out of the
lake as well as the lake itself and the Endrin concentrations
in water, mud, and the aquatic food chain over a period of
at least one year.
       Shell Technical Bulletin, Summary of Basic Data  for
Technical Endrin, Shell Chemical Company, San Romon, California
and Jager, K.W., Aldrin, Dieldrin, Endrin and Telodrin,
Elsevier Publishing Company, New York, 1970, p.  86.
                              22

-------
Prior to the implementation of either the limited survey or
the complete evaluation, it will be necessary to conduct pre-
liminary studies to determine the overall nature of the phy-
sical environment and the biological community in order to
best locate sampling sites and to determine those parameters
which are most significant.  A complete evaluation should be
conducted according to the following outline.

I.    Sampling Locations:  Total of 8 locations; one above
      lake, two within lake, three in Pond Lick Run, two on
      Turkey Creek.  Care must be taken to assure that the
      stream sites selected comprise similar aquatic habitats
      whenever possible.

II.   Frequency of Sampling:  Total of 6.  One immediately
      after selection of permanent sites, one within one
      month, quarterly for a period of 1 year.

III.  Determinations at Each Site:
      A.  Pesticides:  Analyses for pesticides should include
          determination of other chlorinated hydrocarbons as
          well as Endrin since this will provide available
          background information and does not greatly increase
          the time or cost involved in analyses.

          1.  Water:  From each stream station and during
              periods of stratification, from two to three
              depths within the lake.
          2.  Fish:  At each site as available for major species,
          3.  Bottom Sediments:  At each site.
          4.  Periphyton and/or Macroinvertebrates:  Nature
              of these samples will depend on the nature of
              the aquatic communities present.

      B.  Chemical:  The nature of chemical analyses to be
          routinely conducted depends on the quality of the
          water in the lake and its tributaries, and the
          nature of any pollutants which may be present.
          Routine analyses such as D.O., pH, Alkalinity,
          Hardness, Phosphate, Nitrate, Ammonia, and B.O.D.
          should be carried out.

      C.  Biological:  Biological studies should be conducted
          at each site.  In addition to the specific studies
          described below, observations of other organisms and
          communities should be made during each sampling per-
          iod in order to determine if additional effects of
          the Endrin pollution are evident and the overall
          pattern of recovery of the aquatic community.


                               23

-------
          1.   Benthic Organisms:   Samples will be taken at
              lake stations with  a dredge suitable for the
              bottom type in question.   Stream samples will
              be taken with a dredge or Surber sampler.  The
              kinds and numbers of organisms present will be
              determined.  Samples from similar habitats will
              be compared for composition, number and diversity.
          2.   Plankton:  Samples  for plankton studies will
              be collected and concentrated by means of the
              plankton centrifuge and examined to determine
              the kinds (to genus)  and numbers of organisms
              present.
          3.   Periphyton:  At each site, if available, for
              composition only.
          4.   Fish:  At each site if possible.  Collections
              will be made by seine hauls, gill nets or shock-
              ing, depending on conditions.  Determinations
              as to kinds, numbers, and age class should be
              made.

B.    Alternate Countermeasures

Several promising alternate treatment schemes were proposed
but ruled out due to the lack of  reliable design information
in the literature or immediate feasible implementation.
These alternate countermeasures are presented in great detail
in Appendix D.  Some of these, such as barging the poisoned
water to sea, would be too expensive to consider seriously,
but several materials were proposed for in-place treatment
of the lake.   Powdered activated  carbon, fly ash, bentonite,
and topsoil or peat were mentioned for this purpose.  Simple
jar tests performed at the site could have established the
usefulness of any or all of these materials if reliable de-
sign and scale-up factors existed in the literature.  The
economics of each of these alternatives appears to be extre-
mely favorable and should be compared with the activated car-
bon filter system built.  Since the geological report showed
no likelihood of ground water contamination, a system of sink-
ing the Endrin to the bottom might be desirable.


An issue which was to be resolved was what should be done with
bottom muds containing Endrin. If the sides were scraped per-
haps the best place to put the muds is in the bottom of the
lake.  The bottom could be sealed with a layer of bentonite
or fly ash.  Perhaps these materials would absorb any Endrin
which desorb from the muds.  Resolution of this issue would
relate to the ecological recovery program presented above.
                             24

-------
The last, and perhaps most important  issue,  is  the  alternate
method proposed which would let the lake recover naturally,
Allowing natural recovery would not only be  inexpensive, with
the cost dependent upon monitoring used, but it would be extre-
mely useful in gaining knowledge of how recovery occurs so
that predictions could be made about  a larger lake  or river
which could not be treated.  The remoteness  and geological
isolation of this lake made it an ideal area for study.

Critique of Response Actions and Recommendations

During the course of the emergency spill cleanup operation, it
was recognized that certain improvements and modifications
could be made to the spill incident control  procedures.  These
suggestions are presented as follows:

1.    Working within existing state organizations,  all states
should designate an Oil and Hazardous Materials Branch with
responsibility to coordinate state response  and to  interface
with U. S. Environmental Protection Agency  (EPA) programs and
On Scene Spill Coordinators.

2.    Correspondence and lines of communication should be
opened between these State agencies and the  U.  S. Environmental
Protection Agency.  This project required a  great deal of co-
operation between State, Federal, and private individuals to
accomplish the objective of removing  the Endrin as  expediti-
ously as possible.  Without cooperation the  project could not
have succeeded.  Under conditions such as these a close work-
ing rapport is necessary in the field.

3.    A Spill Response Notebook or Damage Assessment Manual
should be developed by the U. S. Environmental  Protection Agency,
for distribution and use by various concerned agencies and
organizations.

4.    These notebooks, along with an  explanation of the full
breadth of the U. S. Environmental Protection Agency program
should be presented in a series of seminars  to  the  designated
State teams.

5.    Field Preparedness Package

To allow rapid mobilization of the Emergency Response Contractor,
a field preparedness package should be maintained by the con-
tractor at all times.  This unit would contain:  slide rule,
notebooks, engineering handbooks, Damage Assessment Manual,
and Polaroid camera.  The field preparedness package should
possibly contain sampling equipment and containers  similar to those
                              25

-------
used by the Contractor.   These containers allow refrigerated
samples to be sent by air anywhere in the world simply by using
insulation material.   This field preparedness package is not
thought of as a complete portable lab, but rather a "first-aid
kit" which will make  the initial response a more efficient
operation.

6.    Manpower Scheduling

In an emergency such  as  that created by a spill of Endrin
there is an optimum number of personnel to send to the site
to effect remedial action.  The area affected by the spill
and the degree of danger to humans, wildlife, and livestock
in the area will dictate the level of manpower required and
the duration of their stay.  The Contractor recommends that
one senior level engineer or principal representing the
Emergency Response Contractor and one Project Officer repre-
senting the U. S. Environmental Protection Agency be dis-
patched to the scene  prior to authorization of support ser-
vices.  Based upon their review and on-site evaluation, the
level of technical response should be authorized.  To support
the response team on  significant spills, one clerical level
person should also be sent.  This person will be available
to answer telephones, relay messages, type, and correlate the
field notes of the professionals.

7.    Effective Coordination and Project Communication

      a.  To effectively assess the damage caused by a spill
          of this nature, the Emergency Response Contractor
          operates in two areas.  The field team on site re-
          lies heavily on the activities of the home office
          staff for support information.  This is a good con-
          cept but to work efficiently, it requires excellent
          communications; thus the suggestion above for cleri-
          cal support in the field.  Limited telephone faci-
          lities in the  field and large distances between the
          phones and  the site of the spill made communication
          at Pond Lick Lake unreliable.  In the event of
          future spill incidents, the telephone company
          should be requested to immediately install adequate
          telephone service at the field site, or portable
          equipment,  i.e., radios, etc.  EPA should plan for
          these devices  in future remote areas.

      b.  Release of  information to the public should be
          handled in  a manner which will dispel rumors and
          misconceptions.  This can be most effectively
                             26

-------
          accomplished by establishing an on-site press
          office manned by designated EPA and State offi-
          cials.  The Contractor should have no contact with
          the press unless the OSSC asks for assistance or
          approves a press release.

Incident art Shawnee:  Its Significance

The importance of the unresolved critical issues and the sug-
gested improvements to the incident control procedures can-
not be underestimated.  In retrospect, however, these are
relatively minor concerns.  The element most crucial to the
resolution of the problem was the human response which the
emergency spill necessitated.  A basic concern for the health
and welfare of the populace in the surrounding area motivated
the initial efforts of the State of Ohio and the subsequent
actions taken by the U. S. Environmental Protection Agency
and the Emergency Response Contractor.  It is essentially
this human element which led The Portsmouth Times' to say:

"We can take great pride in the response of the many agencies
concerned with clearing the lake of the poison.  We can take
pride in the fact that the discovery came early enough to
prevent harm to persons who use the lake.  We can take pride
in the efforts of every individual concerned with the action
in any way."
1 The Portsmouth Times, Monday, June 21, 1971, p. 6.  For
 additional newspaper references to the emergency spill, see
Appendix G.
                             27

-------
                     APPENDIX A


                Chronology of Project


This Appendix includes:

     1.  Exhibit A.   Statement of Work from EPA/Washington
                     to  RETA authorizing Contract No«  68-01-0045.

     2.  Exhibit B.   Chronology

     3.  Exhibit C.   Critical Decisions


                      Exhibit A

      Statement of Work  from EPA/Washington to
            RETA authorizing Contract No.


Background

On June 2 or 3, approximately one (1) gallon of a mixture
of concentrated pesticide (18.6% Endrin) and strychnine
treated corn was dumped  into Lake Shawnee (area three (3)
acres) in Shawnee State  Park.  Shawnee State Park is about
ten  (10) miles southeast of Portsmouth, Ohio.  Mr0 Roach
of the Department of Natural Resources of Ohio asked for
help from the Environmental Protection Agency (EPA),
Chicago, Thursday, June  10.  Because of the imminent and
substantial threat to the Ohio River and downstream users
thereof, EPA response was required,  Mr. Andy Sidio of
the National Field Investigative Team (NFI) of Cincin-
nati responded June 10 and took samples of the lake and
receiving stream Pond Lick and Turkey Creek.  6800 Ibs .
of .40 mesh activated carbon were broadcasted by Mr. Sidio's
crew across the surface  of Lake Shawnee.  Mr. Robert Can-
tor dispatched Wheeling, West Virginia, Regional Oil and
Hazardous Material Personnel to aid and/or relieve Mr.
Sidio and the NFI, June 12, 1971.

Task to be Performed

The emergency Response Contractor was activated and, if ac-
cepts, will undertake to accomplish the following:

   1.  Provide Mr. Sidio and other EPA personnel on-scene
       with immediate (June 12, 1971) technical advice, by
       phone, on adequacy of existing activated carbon
       treatment or suggested modifications thereof and
       advise on other alternative countermeasures;

                          28

-------
   2.  provide Mr. Sidio or other EPA personnel on-scene
       with technical advice once the Contractor is on-
       scene (June 13, 1971);

   3.  undertake limited downstream observations to sup-
       plement the work already underway by the NFI, June
       13-15, etc; and

   4.  collect sufficient technical information and photo-
       graphs to prepare an incident report dealing with
       the cause, effectiveness of countermeasures, time-
       liness of response, short-term and long-term effects
       of the discharge, and steps that may be taken in
       the future to prevent such a discharge.  This re-
       port is due to the Project Officer in Washington,
       D. C., July 15, 1971.
                      Exhibit B

                     Chronology
The following table outlines the daily activities of key
personnel of the States of Ohio, the U. So Environmental
Protection Agency, and Ryckman, Edgerley, Tomlinson and
Associates (RETA) throughout the project from the initial
spill of Endrin to notification and activation of the
State/Federal response team and subsequent design, con-
struction and operation of the prototype treatment plant.

The sequence of events for each day are listed under the
group most responsible for them.  By studying the chart,
the progress of the project can be followed and the con-
tributions of each team member ascertained.

                      Exhibit C
                 Critical Decisions
In anticipation of an incident similar to the one reported
here, the Division of Oil and Hazardous Materials of EPA
had set up an agreement with RETA to provide technical as-
sistance and support to EPA to minimize damage to the en-
vironment by a release of hazardous materials.  The ex-
tremely rapid rate at which a solution to the problem was
reached and implemented is a compliment to all who partic-
ipated and to their ability to work together under trying
circumstancese  The activities at Pond Lick Lake were di-
rected by a cooperative team consisting of the U» S. En-


                          29

-------




OHIO



















EPA






















fj ff A
KblA





Wed.
June 2
Poison
dumped ii
lake in
Ohio

















































SEQUENCE OF EVENTS
Thursday
June 10
DNR asks
i EPA for
assis-
tance










EPA
notified
National
Field
Team to
scene

































Friday
June 11
Spillway
dammed











Bioassay
Fish die
2 hours
G. C.
sample
to Cinn.

Dam
spillway






























Sat.
June 12
Diversio
dam
started

Activate
Carbon o
lake







C. H,
Thomp son
notified

Inf orma-
tior
gathered

National
Field
Investi-
gative
Team in-
put to
Hazard-
ous
Materials
branch









RETA
notified

Accepts
ob







Sunday
June 13
Finish
diversio
sion dam

Begin
by-pass

Raise
Sandbag s

Post
guard
around
lake
Bioassay
& Chem-
ical
analyses

Stream
damage
survey.
Suggest
stop
using
wells in
area.














RETA to
field
from
Dayton &
St .Louis

Assess
damage
Recom-
mend no
more
carbon


Mond ay
June 14
Raised
dam
Built
by-pass
Set up
pumps







Depth
sample s
taken,
temper-
ature
profile

C. H.
Thompson
receives
report
















Prepared
situa-
tion
report ,
Tuesday
June 15
Formal
assis-
tance
request
sent to
EPA

W. Nye,
meets
CHT in
travel
to site


CHT to
Columbus
meets
with DNR
travels
to site

CHT de-
cides
pilot
plant
needed

Compre-
hensive
sampling
program
reques-
ted








Design
Pilot
Plant ,
start
delivered con-.
to CHT
Second
report
sent




struc-
tion





Wed.
June 1 6
Power in
stalled
at dam

W. Nye
locates
G. C. at
O.S.U.

Huild
pilot
plant


CHT
attempts
to lo-
cate EPA
carbon
filter
plants.
All are
in use

CHT
works to
find GO














Build
pilot
plant

Pilot
Plant
Opera-
tion
begun at
Thursday
June 17
- 2: a.m.
G. C.
arrive s
at dam
with
D. Howarc

Telephon<
installed
at site




2 a.m.
CHT, D.
Howard
set up
G.C.

Results
at 10a.m.
pilot
plant
working

CHT
locates
tank for
proto-
type
plant

Decides
to build
proto-
type
based on
pilot
plant
success
Operate
and
sample
pilot
plant

Begin
design
calcula-
10:30p.m.tions on




proto-
type
plant


Friday
June 18
G.C.
analysis
shows
good
pilot
plant
opera-
tion

Build
proto-
type
plant

6 a.m.
Repairs
Pilot
Plant

CHT
directs
con-
struc-
tion of
pro t o-
type















Detailed
Construc-
tion
descrip-
tion by
SJR






Sat.
June 19
Complete
proto-
type
plant










Construe.
tion con.
tinues

Plant in
opera-
tion
5:30 p.m

Air
bubbles
in fil-
ter
cause
problems
shut
down
proto-
type
plant



















Sunday
June 20
Modify
filter
Dave
Howard
briefed
on safety

Dave
Howard
briefed
on safety


Modify
filter

CHT
leave s

Dave
Stolten-
berg in
charge

















Modify
filter

Restart








Monday
June 21
State to
pick up
as EPA
pulls
out




































Filter
Modifi-
cations
with
state

Need for
24 hour
opera-
tors
noted



Ved.
June 23
Electric
submer-
sible
pump
ordered
to stop
air
bubbles

































Opera-
ting &
emer-
gency
proceed-
ure
instruc-
tions
created





Thursday
June 24
ilectric
himp
Operatior
2:30 p.m.

lo air
in filter



































Friday
June 25
Heavy
rain,
lake
level
rises
18"








Confer-
ence CHT
about
heavy
rain
condi-
tions




















T
Sat.
June 26
Condi-
tions
stabi-
lized

Con-
struc-
tion of
emer-
gency
spillway
filter
begins




























ABLE 2
Monday
June 28
Filter
and
spillway
filter
operate
to 400
GFM




































KEY:

DNR Ohio Department of
Natural Resources
EPA Federal Environmental
Protection Agency
RETA Ryckman, Edgerley,
Tomlinson, & Associates
CHT Dr. C. H. Thompson
SJR S. J. Ryckman
G.C. Gas Chromatograph

-------
vironmental Protection Agency, the State of Ohio and Ryckman ,
Edgerley, Tomlinson and Associates (RETA).

Pond Lick Lake is a small lake of approximately three
acres surface area and a length of about 1,000 feet.  The
depth is 35 feet maximum and an average of approximately
15 feet,,  The volume is approximately 15 million gal-
lons.  The shore characteristics are regular with steep
banks and no swampy zone.

The lake was formed behind a dam built during the de-
pression by CCC labor groups.  It served as a reservoir
for an honor camp of the Ohio penal system until it was
closed a few years ago.  The current use is recreational,
with fishing and limited boating.  The lake and its water-
shed are located in Shawnee State Park about seven miles
southwest of Portsmouth, Ohio, some 110 miles from Cin-
cinnati and 100 from Columbus.

The lake is used for fish, aquatic life and wildlife.  The
affected population living downstream from the lake before
it flows into the Ohio River is between 50 to 200.  There
were four or five wells threatened, according to the Ohio
National Resources Division.

In this section of the report we have attempted to collect
the critical decisions which were made and which controlled
the direction of action by the team.  These decisions are
as follows:

1.  State of Ohio Requests U. S. EPA Assistance.
    The State of Ohio Department of Natural Resources asked
    the federal EPA for help June 10 due to the threat of
    Endrin poison entering the Ohio River.   An EPA team,
    under the leadership of Andy Sidio of the Cincinnati
    Field Investigative team, responded June 10.  Mr. Sidio
    assessed the initial damage and through the Wheeling,
    W. Va. EPA field office contacted Dr. C. H. Thompson,
    Chief, Hazardous Materials Branch, Water Quality Office
    of EPA in Washington.

2.  Ohio Takes Steps to Contain the Lake.
    An initial decision was made by the Ohio Department of
    Natural Resources to contain the lake by sandbagging
    the spillway and building a diversion dam and by-pass
    at the head end of the lake to isolate the entire lake.
    Approximately 6,800 pounds of granular (40 mesh) acti-
    vated carbon was spread on the lake.   This did not sig-
    nificantly reduce the Endrin concentration because it
    settled to the bottom too fast to contact a significant
    amount of Endrin.


                          31

-------
3.  EPA Activation of RETA Response Team.
    The initial contact with RETA was  made at 5:30 p.m.  on
    June 12,  1971 (Saturday) by Dr. C. H.  Thompson, of the
    Environmental Protection Agency, in a  telephone call
    to Dr. G.  M. Barsom.  Dr0 Thompson is  Chief of the
    Hazardous  Materials Branch, Water  Quality Office,  EPA,
    Washington,  This telephone conversation reported pre-
    liminary  information available on  the  spill of Endrin and
    strychnine into Pond Lick Lake in  Shawnee State Forest
    near Portsmouth, Ohio.

    RETA personnel had several conversations with Dr,  Thomp-
    son concerning the EPA Contract 68-01-0045,  its acti-
    vation, and the preliminary information transfer.

    Mr. John Blake, EPA Contract Officer,  held a contract-
    ual discussion with D. W. Ryckman, RETA President, and
    requested a preliminary cost estimate.

    At 7:30 p.m., a conference of key  RETA staff was held
    to discuss preliminary evaluation  and  proposed action.
    A decision was made by the staff to accept the assign-
    ment.  This acceptance of the assignment was made  in a
    telephone conference call between  D. W.  Ryckman, G.  M0
    Barsom and C. H. Thompson at 9:30  GST.  Additional infor-
    mation on the scope of work was transmitted at this  time.

    At 11 p.m. a conference call was held  between G. M.
    Barsom, D. W. Ryckman and S. J. Ryckman (Dayton, Ohio)
    with Mr.  Sidio.  There was a two-hour  discussion of  the
    situation, action to date, the recommended course of
    action, and the schedule verification  of participants.

    During Saturday night and into the early morning hours
    of Sunday, the RETA staff made manpower allocations  and
    mobilized field equipment.  Schedules  for transportation
    were assigned, and at 7:00 a.m. GST the RETA team was
    dispatched to the field from St. Louis and Dayton.

    At 11:00 a.m. Sunday the 13th of June, the field crew
    called the St. Louis office to say they were leaving the
    motel to meet with the EPA and State of Ohio men on the
    site.  Contact was made at the site by Mr. S. J. Ryck-
    man from Dayton, and Dr. C. Lue-Hing and Mr. W. E. An-
    derson from St. Louis with Mr. A.  Sidio, EPA, and Mr
    Redett, State of Ohio.


**•  RETA Makes First Observations and Recommendations.
    RETA field personnel endorsed the  isolation of the lake
    and sandbagging to raise the height of the spillways.

                          32

-------
RETA recommended that no more carbon be spread on the
lake until its effectiveness to sorb the Endrin and
its effect on the lake biota and groundwater could be
determined.  Federal and state officials agreed and
no granular carbon was spread in the lake after June 12.

Spill definition information was gathered and transmit-
ted to_the St. Louis office.  Isolation of the lake by
the Ohio Department of Natural Resources was largely
completed on Sunday and sample locations on the lake
and downstream were established.  The RETA team dis-
cussed possible treatment of the spill with Mr. Redett.

Dr. Thompson called the RETA office Sunday afternoon and
was given the status of the project.  Arrangements were
made to deliver Situation Report No. 1 (see Appendix B)
to him in Denver on Monday at the Annual AWWA confer-
ence.  Sunday evening, S. J. Ryckman, RETA Field Man-
ager, was contacted for information for the first re-
port.  Following is a summary of Situation Report No. 1.

  A.  Spill Definition
  As nearly as can be determined, on June 2, 1971, a
  one gallon plastic container filled with approximately
  one gallon of Endrin mixed with corn kernels soaked
  with strychnine (rat bait) was dumped into Pond Lick
  Lake in Shawnee State Forest, Portsmouth, Ohio, by
  an irate citizen.

  According to the manufacturer's specifications, the
  Endrin was a wettable emulsion in an oil based dis-
  persing agent, 18.6% by weight Endrin, 73% by weight
  petroleum hydrocarbon and 8.4% by weight inert.  Be-
  tween 1/2 to 3/4 gallon of Endrin is believed to have
  been in the bottle.  The wettable Endrin emulsion ra-
  pidly goes into suspension in water and by the time
  the spill was discovered, had mixed with all the sur-
  face waters of the lake.  Samples were analyzed by
  Friday, June 11 in Cincinnati by the Environmental
  Protection Agency.  Endrin was reported as 8.5-9.5 ppb
  by these.tests*  This figure was in agreement with
  bioassay data.

  The strychnine (0.05-1.0%) was in insoluable form
  on dried corn, which amounted to approximately 1/2
  gallon.  This caused little damage to the environ-
  ment since strychnine breaks down when exposed to
  sunlight and was not a matter of great concern through-
  out the incident.
                        33

-------
The public was warned of the polluted water by radio,
television and newspaper, signs saying "Poisoned
Water" posted around the lake and downstream and 2k
hour patrols guarded the lake.  The access roads^
were closed during the entire period after the dis-
covery of the spill and continue to be closed as the
lake is being pumped dry.

No hazardous polluting substance was spilled after
the lake outlet was sandbagged on Thursday, June 10th,
Before that the substance had travelled downstream
approximately 1 mile.  After the lake was sandbagged,
the water was contained in a concrete dissipating
basin and recycled into the lake by a pump.
B.  Ecological Damage
The apparent ecological damage is as follows:

  1.  There were approximately 3,500 dead fish, both
      in the lake and downstream,,  They were mostly
      blue gills, bull heads and catfish and were
      killed within a few days as the Endrin spread.
  2.  About 3,400 fish were estimated to be dead in
      the lake.  A downstream survey showed a complete
      kill for 0.2 miles below the dam, heavy damage
      with most forms of aquatic life dead in the
      0.2 - 0.6 mile region, recovery in the 006 - 1.0
      mile stretch and no apparent damage at distances
      of greater than one mile»
  3.  A muskrat was caught after swimming in the lake,
      and shipped to the State Health Department in
      Columbus for observation.  The muskrat died.
  4.  Two dead opossums were reported by one of the
      men representing the State of Ohio.
  5.  Several types of large and small fish - perch,
      catfish, sucker - have been observed alive at
      intervals since June 2.
  6.  On June 18, a sr-i!:e was seen swimming in the water
      by the spillway.  Some sick bluegills were seen
      the same day, also some frogs swimming near the
      surface.
  7o  Mr* Gilbert Helwig of the Ohio State Department
      of Natural Resources reported seeing two couples
      swimming from the dock at the lake on June 8,
      1971.  He told them the lake was poisoned and
      that they should get out.  He did not get their
      names.  Another employee of the Ohio DNR re-
      ported chasing several people away who were swim-
      ming in the lake.  The total seen swimming was
      about twelveo  No names were given.  Mr. Helwig
      later heard a rumor that a boy was in University

                    34

-------
        Hospital,  Columbus, Ohio, badly swollen,  who
        claimed to have gone swimming in the lake.

  Construction of  a diversion dam across the upper  end
  of the lake was  progressing well and completion was
  to be achieved Sunday night.  Light, intermittent rain
  was falling and continued to fall for several days.
  The pumping system to convey the diverted water
  around the poisoned lake was completed on"Monday, June
  14.  This system was designed as a temporary device
  to try to protect the lake if rain occurred in the
  area.  Ohio Department of Natural Resources stressed
  the importance of immediate action due to the limit-
  ed capacity of this system and its temporary nature.

  The watershed above the lake is about 4 1/2 square
  miles but the area receives frequent heavy showers;
  in summer, there may be 2 to 4 inches of rain at
  one time.

  It is fortunate that no heavy rain occurred between
  the time of the spill and construction of the dam
  eight days later.  A heavy rain then could have pushed
  a large amount of the poisoned water over the spill-
  way and into the Ohio River.  A rain gauge was in-
  stalled later and recorded over 2 inches of rainfall
  on Friday, June 25.

On Monday, June 14th, Situation Report No. 1 was de-
livered to Dr. Thompson in Denver by E. Edgerley, RETA
Senior Vice President.  William Nye, Division of Water
Resources, State of Ohio, expressed a need to meet  with
Dr. Thompson.  A flight schedule was arranged by RETA
staff so that Dr. Thompson could meet with Mr. Nye  on
Tuesday morning in Columbus, Ohio.

Situation Report No. 2 was written Monday, showing  that
the contaminated lake water was not a threat to ground
water.  Published standards for Endrin toxicity to
aquatic  life were contained in this report.

Pilot Plant is Needed
T*he failure of the initial spreading of the carbon  to
reduce the Endrin concentration raised the need to  com-
prehensively evaluate other possible counter measures,
(Appendix D).  Tuesday evening, June 15, the decision
was made to construct and operate a pilot plant to  de-
termine :

a.  Ability of an activated carbon column to remove
    Endrin and produce a non-toxic effluent;
b.  Adsorptive capacity of activated carbon;

                      35

-------
c.  Necessary loading rates for proper carbon contact
    and Endrin adsorption;
d.  How to best construct a filter system;
e.  Whether a pre-filter was needed to remove sus-
    pended material.

Dr. Thompson made the decision to use a pilot plant
in order to quickly verify the information^needed.
Other counter measures (detailed in Appendix D) were
evaluated and ruled out either because of process or
construction short comings or because a long time was
required to establish the validity of the process.
The Ohio Department of Natural Resources^and RETA co-
operated in designing and building the pilot plant.
A crew worked all night Tuesday, June 15^with RETA
engineers to construct the plant.  The pilot plant
went into operation Wednesday, June 16.  Dr. Thompson
and S. J. Ryckman were at the pilot plant when the
gas chromatograph arrived from Ohio State University,,
Dr. Thompson immediately turned to the installation
of the instrument as noted below.

Portable On-site Gas Chromatograph is Needed.
One of the first areas recognized as a potential
trouble spot by the RETA team on Sunday, the 13th
of June was that of sample analysis.  Dr. Cecil Lue-
Hing of RETA expressed the desirability of an on site
Gas Chromatograph to allow rapid analysis of samples.
On Sunday, samples were being sent to Cincinnati for
analysis, a workable arrangement for defining the prob-
lem, but not for monitoring and controlling  the treat-
ment system.  RETA relayed the request to Dr. Thompson.
Dr. Thompson was attending the AWWA meeting  in Denver
and discussed the need with other conferees.  Several
leads emerged from the discussion.  Ohio State Univer-
sity was a possible source as was EPA in Wheeling, West
Virginia, Cincinnati, Ohio and Chamblee, Georgia.  Dr.
Thompson, John Cox, John Blake and Dr. Aron Rosen,
all of EPA, spent a great deal of time in trying to lo-
cate an available unit, without success.  All of the
EPA units were in use on research projects and unavail-
able for the Shawnee Lake Operation.  Dr. Thompson and
Director Nye  discussed the need and Mr. Nye worked
with Ohio State University to provide an instrument and
an experienced man to run it.  Finally Mr. Nye sent word
the 16th of June that the instrument was available.

Decision to Build Prototype Plant
The pilot plant was successfulin removing Endrin from
the lake water at its design loadings as shown by
early gas chromatography of effluent samples and fish
bioassays.  The next decision was to try to build a

                      36

-------
prototype plant capable of treating large amounts of
water.

A critical factor was locating equipment available to
build the plant which would meet the design criteria
established by the pilot plant, or which could be mo-
dified to do so in a short time.  Dr. Thompson,
through EPA in Cincinnati, found that some large
cypress tanks were in storage at Cincinnati.  Size es-
timates allowed a rough calculation of capacity, which
was found to be suitable.  Dr. Thompson flew to Cin-
cinnati to inspect the tanks, found them satisfactory
and ordered the prototype plant designed using locally
available supplies such as PVC drain pipe.  The plant
went into operation Saturday, June 19.  Details of its
construction and operation are given in Appendix EB
On Sunday, June 20, certain problems developed and some
redesign was required.

Prototype Modifications
The top of the filter was originally designed with a
layer of vermiculite to allow expansion of the carbon
bed.  This material broke down and clogged a muslin
cloth designed to stop carbon fines from escaping.
The top of the filter was redesigned to eliminate both
the muslin and vermiculite.  This helped operation but
air being drawn into the pump supplying the filter
caused channeling of the bed.  A submersible pump was
installed instead of the original gasoline pump to
stop the flow of air into the carbon filter.  The
filter has been operating successfully since that time.
Samples are periodically taken and analyzed with the
gas chromatograph (G.C.) to ensure that Endrin is not
discharged to the receiving stream.
                      37

-------
                     APPENDIX B

        SITUATION REPORTS, ENDRIN/STRYCHNINE

         HAZARDOUS POLLUTING SUBSTANCE SPILL
The absence of documented information about the hazardous
spiLL emergency coupled with the poor communications
system in the vicinity of Pond Lick Lake necessitated
a means should be devised to provide reliable and factual
information to all involved.  This included the State of
Ohio field team and headquarters personnel, personnel from
two Environmental Protection Agency Regional offices, and
RETA field team and headquarters personnel.  Thus,  RETA
initiated the use of situation reports to communicate the
most current and accurate information regarding the spill
and vital to its resolution.  These reports proved  essen-
tial in guiding and supporting the decision making  process
and in communicating the nature of the spill to the Congrees
of the United States and to the general public.  Two of
the most essential situation reports are presented  as
follows.  The first one was delivered to Environmental
Protection Agency headquarters in Washington,  D.C.  and to
Dr. Hugh Thompson in Denver within 48 hours of RETA project
activation.
                         38

-------
                  STRICTLY  CONFIDENTIAL
                                   Situation Report No.
                                   RETA No.
                                                862-1
                                   TIME PERIOD:

                                        From:  5:30 pm 6/12/71
                                        To;   11:30 pm 6/13/71
TO:   Dr. C. H. Thompson
      Environmental Protection Agency
      1921 Jefferson Davis Highway
      Arlington, Virginia 22202
FROM:   Ryckman, Edgerley, Tomlinson and Associates, Inc
        500 Coronet Building
        225 S. Meramec
        St. Louis, Missouri 63105
                     ENDRIN/STRYCHNINE
             HAZARDOUS POLLUTING SUBSTANCE SPILL

                       SHAWNEE LAKE
                     PORTSMOUTH, OHIO
                       RETA 862-1
                           39

-------
                      TABLE OF CONTENTS









LETTER OF TRANSMITTAL	      i




TITLE PAGE	     ii




TABLE OF CONTENTS	    ill




CHAPTER  I  EVENTS LOG	      1




        II  PERSONNEL	      2




       III  SPILL DEFINITION 	      4




        IV  PROBABLE COUNTER MEASURES	      9




         V  METEOROLOGY AND CLIMATOLOGY REPORT  	     1Q




        VI  GEOLOGICAL REPORT	     11




       VII  SAMPLING PROGRAM REPORT	     14




      VIII  AERIAL RECONNAISSANCE REPORT 	     16




        IX  PROPOSED ECOLOGICAL RECOVERY PROGRAM  ....     17




         X  NOTES  	
                              40

-------
   I. EVENTS LOG
   Date        Time
           (Nautical time)
                                   Event
6/12/71
1730




1830


1900


1915


1930
              2030




              2200




              2230


              2300
6/13/71
0130
              0200
              0300
C. H. Thompson, EPA, called G. M.
Barsom, RETA, to report preliminary
information available on spill of
endrin and strychnine.

C. H. Thompson to B. N. Sampley,
report pending activation of B.O.A.

C. H. Thompson to D. W. Ryckman,
activation of B.O.A. preliminary
information transfer.

J. Blake to D. W. Ryckman, contractual
discussion.  Request for preliminary
cost estimate.

Conference of key RETA staff:  G. M.
Barsom, D. W. Ryckman, E. Edgerley,
H. D. Tomlinson, Ralph Clark, Joel
Harrod, Cecil Lue-Hing, Jim Chaney,
Joe Dieterman, Russ Tirella.  Pre-
liminary evaluation and proposed action.

Joel Harrod call to Weather Corporation
for present and forecasted weather in
the damage area.  Intermittent thunder-
showers .

D. W. Ryckman, G. M. Barsom telephone
conference with C. H. Thompson.  Trans-
mit tal of additional information on
scope of work.
C. H. Thompson call to A. Sidio (EPA,
Cincinnati, man-on-site)

Conference call by G. M. Barsom, D. W.
Ryckman and S. J. Ryckman with A. Sidio.
Two hour discussion of situation, action
to date,  recommended course of action,
schedule verification of participants.
G. M..Barsom, D. W. Ryckman conference
regarding schedule, manpower allocations
and mobilization.

H. D. Tomlinson, Joe Dieterman, Bill
Anderson, Jim Chaney to RETA laboratory
and warehouse to mobilize field equipment

G. M. Barsom final schedule verification,
manpower allocation and mobilization.
                                   41

-------
   Date
    Time
          Event
6/13/71
0100 - 0300

    0700


    1030

    1100



    1200
                    1315
                    1345
                    1800
                    2138
RETA planning meeting.
RETA team dispatched to field
from St. Louis and Dayton.
RETA strategy sessions begin.

Contact from field crew
leaving motel base to meet
with EPA, State men on site.

St. Louis (DPC) contacted EPA
(Cincinnati) for background.
Dr. Rosen gave basic information
on concentration 8.5-9.5 ppb.
use of activated carbon.  Rough
size of lake, depth, sandbagging
of spillway.

SJR report from field.  Confirmed
Dr. Rosen's information.  In-
dicated work proceeding on di-
version dam at head end of lake;
expect it finished by tonight.
Strychnine not the problem due to
its inclusion on corn and low
concentration.

Dr. Hugh Thompson called; given
status of project.  Told us his
plans to go to Denver and to go
to field Tuesday.  E.  Edgerley
to deliver report to H. Thompson
in Denver Monday.  Effect on
ground water discussed.  Need
for carbon samples from the
bottom discussed.

Information form assembled.

Contacted S. J. Ryckman for up-
dated report.  Information on
Report I transmitted.
                                 42

-------
II.    PERSONNEL
      1.   EPA/Washington Headquarters:
              Project Officer;    Pr.  G- H* Thompson
              Alternate:          Mr.  Russ Wyer
      2.   RETA Personnel   (Name, Title, Function)
           Headquarters:
              1.   G. M.  Barson
              2.   D. P.  Clement
              3.
              4.   Support:  S. J.  Clement,  Geologist
           Field:
               1.  S.  J.  Ryckman
               2.  Cecil  Lue-Hing
               3.  Wm. E. Anderson
               4.   Support:

       3.   EPA/Field Personnel (Name, Title, Function)
               1.  Angell Sidio  Cincinnati - Cinti group  chief
               2.  Dick Daun     in charge Cinti group  in  absence of A.S
               3.  Nelson Thomas Chief Biologist
               4.  Mr. Griffith  Wheeling, W. Va. Biologist  -  sampling
            State Crews:   (Name,  Title,  Function)
            John S. Barrett, Asst. Chief Eng. Dept of Wat.  Resources
                 Supervise upstream damming and diversion
            Dan Armbruster, Chief Div«»of Wildlife, Dept.of  Wat.  Res.
            Everett Ridge, District Supervisor, Div of Wildlife,
                 Dept. of Wat. Res.
            Mr. Toss, Coordinator of Parts
            Robert Redeft, Wat. Resources - cleanup
                              43

-------
III.   SPILL DEFINITION

       Date:	6/2/71
       Time:
       Location;    Shawnee  Lake,  Shawnee  Lake St.  Park,  Portsmouth,Ohio
           SUBSTANCES SPILLED	QUANTITY

      Strychnine (0.05-1.0%)  on
       corn (rat bait)                               1/2 gallon

      Endrin  WE (Wettable emulsion)
       18.6% by wt.                                  3/4 gallon

       73%   by wt.  petroleum hydrocarbon
        8.4% by wt  inert
       How Spilled:  Dumped from 1 gallon plastic bottle into
      the  lake by  irate citizen.  Attempted to sink bottle by
      hitting it with rocks.  Bottle recovered (date of recovery
      unknown).

       Affected Area:  (Describe and sketch)
           Surface Area:   3 acres
           Depth:   35'  maximum    Average: 15   ?     Range:  35-0
           Volume: 15 x 10  gallons
           General Topographic Features:
           Shore Characteristics:
           Regular - steep banks.   No swampy zone

          •Estimated Water Shed Area:
                              44

-------
III.   SPILL DEFINITION  (Continued)

      Designated Water Use
                Potable                  ____  Agricultural

                Recreational             _  Industrial

                Fish, aquatic life
                      & wild life
      Affected Population:  50 - 200 (estimates vary)
      Affected Water Supplies  (Surface, Ground):
         4-5 wells threatened
         Ohio Nat. Res. Div sending well logs 6/14/71

      Hazardous Polluting Substances going over Spillway:
           X  Contained i-n concrete energy dissipating basin

           ___ Not contained


      Public Warning System:
          _JL Radio - TV - Newspaper
          	X  signs ~ Poisoned Water

          	^_ Patrols - 24 hr guard suggested by SJR implemented by
                           Angell Sidio
             Access roads closed.
      Presence or absence of livestock
        None noted by field crew.
        Some along Turkey Creek.
      Apparent Ecological Damage:
           X  pish 3400 dead fish removed - 50 still floating,  blue gills,
                                            bull heads, catfish.
              Wildlife
          _X. Aquatic Life -

          _ Other
        Fish buried in polyethylene bags
                              45

-------
III.   SPILL DEFINITION (Continued)
      Apparent Movement and Dispersion of Hazardous Polluting
      Substance:
           Sketch area — Maps at end.
           Define affected zones  (1) Lake - apparent complete  kill;
           (2)  0-0.2 miles below  spillway - complete kill;   (3)  0.2-0.6
           miles below spillway -  damage, sick fish, great effect;
           Dominant mechanism of diffusion   (4) Below  1 mile,  aquatic
                                                   life appears normal.
                   Molecular
                X  Turbulent  (wind)
                X  Mass transport - stream flow now blocked  by
                                    sand bags on  spillway
           Quiescent pools  - on  shale bedrock downstream from dam
           Aerial photos  -  NO
      Characteristics of Receiving Stream:
           Size:      Small
           Depth:     0"-6"
           Width:     6"
           Velocity:  Very slow  -  20-30 gpm flow
           Rapids:    No
           Turbidity:    None
           Shore line:   Normal
           Bank condition:  Solid
           Water appearance:
           Observable damage:
              Property:    None

              Life:  Dead and sick fish and frogs  as  above.
                               46

-------
III.   SPILL DEFINITION  (Continued)

      Known Characteristics of Hazardous Polluting Substance:

           Solubility:  Endrin insoluble.  Wettable emulsion disperses
           Structure:                                        easily.

           Physical: \ Toxic vapors if heated to decomposition
:i
           Chemical:

           Biological: TL10Q 96 hr.  0.6 ppb (blue gills)
           Ecological:

           Toxicity:

              Man:  Enter via skin contact - 10 mg/kg orally cause
              Other life forms:                              sickness

           Health:
      Estimated time available for designated action:
           Time available    2 weeks - solution required 1 week


           Designated Action:   Pilter through activated carbon
           Basis of Decision:
            Known adsorption  of endrin on A.C.
            Lack of chemical  treatment
            Insensitive to biological treatment
                               47

-------
Ill   SPILL DEFINITION  (Continued)
      Profile of Affected Area:
 I
                c o
                                'I
                 I 000 '
      Area Map:
                                                                 h 0
                                                                 ft  f>t\rtJ
                                 48

-------
IV.   PROBABLE COUNTER MEASURES:
                               Material
                               Supplies
Containment:
Counter
Measures

Dam lake
                    Isolate  lake
                    and  let
                    settle
Manpower
Reqmnts.

Met by
    Ohio
             Better
             dam and
             diversion
                                              Technique
Estimated
Time
Required
                          Months to
                          3 years or
                          more
                   Chem ppt.
                   or
                   carbon
            Chemicals
            Spreaders
              Settle
                or
               ppt.
Week
Treatment;
If con-
centration
gradient
drain
bottom/
treat re-
maining
pool

Filter
Water
                                pumps
                                chemicals
              pump
               and
              filter
Week (?)
 Removal:
                                Activated
                                carbon
                                filter
                                operators
                                pump
                    Filter
                    Water
              pump
              lake
              through pipe
              filter
                          Carbon
                          in hydraulic
                          structure
                    Filter
                    Water
                          Carbon
                          in bags
                          pulled
                          through
                          water.
                                49

-------
V.   METEOROLOGICAL AND CLIMATOLOGICAL REPORT
Weather:
  Since
  Spill

Thunde r s t o rms
Intermittent
                                      Present
Thunders t orm
 24-48 hour
 Forecast

Thundershowers
Wind  (Beaufort
      Scale):
                        <.5 knots
Rainfall

  Quantity:
                       Very little
  Time:
                       10  -  15  min
  Effect on
   Water
   Level
                      minimal
                              50

-------
VI.    GEOLOGICAL REPORT
       1.  Location:
           Quadrangle:   Pond Run Quad  (7-1/2 Minute USGS)


           County:       Scioto

           City, etc.    6  -  7 Mi S.W*  Portsmouth, Ohio

           Drainage Basin  Turkey Creek trib. to Ohio River


       2.  Purpose(s) of Lake and Age

           Designated Legitimate Use:   fishing (Flood Control?)
           Lined

           Unlined   X  (?)


        3.  Lake Configuration:
           Surface Area  3 acres

           Shape:         triangle

           Depth:         30+ feet

           Shore Line:   Regular - steep banks, no swampy zone

           Surrounding Topography:
                    Steep, parallel ridges - 45  slope

                              51

-------
VI.  GEOLOGICAL REPORT

     4.  Bottom Sediments (mud/water interface)


         Ooze thickness          ,
                                 •


         Permeability            ?


         Was bottom scraped in construction process?
     5.  Nature of bedrock
           Shale - generally impervious;   thickness  of  shale or
           underlying formations  not  known -  little  ground
           water in area.
     6.  Nature of Shoreline        see  #3 above
     7.  Aquifer characteristics  - shale underlying formations
                                   not known

         Size          7
                       •


         Depth
         Transmissibility  (rate of movement and time of  travel
         of contaminants)
                               52

-------
VII.  SAMPLING PROGRAM  (Spatial and Temporal Distribution)

      Station No.               Date:               Time:
      Air/Water Interface
          Physical
          Chemical
          Biological
                                    Frequency
                Analytical
                Procedure
      Vertical Profiles

          Physical
Frequency
Analytical
Procedure
          Chemical
          Biological
      Mud/Water  Interface

          Physical
Frequency
Analytical
Procedure
          Chemical
           Biological
                               53

-------
VII.  SAMPLING PROGRAM (Continued)

                                                    Analytical
      Shore Zone                    Frequency       Procedure

          Physical


          Chemical


          Biological
      Current System

          Floatables


          Drift Card's


          Current Drogues



      Collect Dead Species



      Microscopic Work



      Well Water Sampling
                                54

-------
VIII.   AERIAL RECONNAISSANCE  REPORT
                                55

-------
IX.     PROPOSED ECOLOGICAL RECOVERY PROGRAM
                              56

-------
Source reference:
                                       Water Quality  Criteria,   Second  Edition
                                       by  McKee  and Wolf;   State Water  Quality
                                       Control Board,   Sacramento,  California
 ENDRIN
  1. General.  Endrin is the  common name  for  the
 chemical l,2,3,4,10,10-hexachloro-6,7-epoxy-l,4,4a,5,6,7,8,
 8a - octahydro -1,4,5,8 - endo - endo - dimethano -napthalene
 (364). It is insoluble in water, acetone, and benzene, and
 slightly soluble in alcohol  (2997).  Although endrin is
 said to have a strong residual toxieity as does its closely
 related compound, dieldrin (3005), endrin is reported to
 disappear "relatively rapidly" based upon  analyses of
 water, mud, aquatic vegetation, and surviving fish  tis-
 sues (3170). Also, another report states that endrin does
 not persist in soil and presents no accumulation problem,
 but  this report  advises not  to contaminate  areas fre-
 quented by wildlife (3171).
  2. Cross Kef erences.  Chlorinated Hydrocarbons, Diel-
 drin.
  3. Effects Upon Beneficial Uses.
  a. Stock and   "Wildlife Watering.  The  acute oral
 LD50 value for  laboratory rats has been  reported  at
 values ranging from  7.3 to 48 rag/kg of body weight
 (2992, 2999, 3002, 3005, 3172, 3173). Chronic feeding of
 100 mg/kg in the diet of males and 25 mg/kg for females
 gave significant  mortality to the same degree. Endrin
 has been used as a broadcast spray at up to 2.5 Ibs/acre
 to control field rodents (3005). Younger males and older
 females appear to be more susceptible than their counter-
 parts (3173).
  Dogs appear to be more sensitive than rats.  Death
 occurred within six weeks at  dietary levels as low as 10
 mg/kg, abnormal effects at 4 mg/kg (3005).  Oral LD80
 values for male  and female monkeys were 3 mg/kg of
 body weight, female rabbits 7-10 mg/kg. and male and
 female guinea pigs 36 and 16 mg/kg (3173).
  Inclusion of endrin at 1 mgAg in the diet of growing
 quail resulted in  high mortality rates. Young pheasants
 failed to survive  on a diet containing 5 mg/kg of endrin.
 However, no ill effects were noted  when quail were  fed
 winter diets containing 1 mg/kg. Hatchability of eggs
 and  viability of chicks were adversely affected by the in-
 clusion of endrin in the reproduction diet  (3044, 3045).
 The  inclusion of 1 mg/kg in the diet will cause a 40 per-
 cent or more decrease in the reproduction of  quail. The
 amount of endrin that will produce at least 50 percent
 mortality  in bobwhite quail and ringneck pheasant con-
 sidering all stages of the life  cycle  arc 5 and  14 mg/kg,
 respectively (2994, 2996).
  The LD50 values of one-week old chicks  is 3.5 mg/kg
of body weight.   Young chickens,  two-months  old,  in-
curred a 10 percent mortality at 4.3 mg/kg. In chronic
feeding  tests with chicks up to seven weeks of age, 95
percent died at 12 mgAg. 15 percent at 6 mgAg (3005).
                                                b. Fish and Aquatic Life.  Fish are highly sensitive
                                              to endrin. Various figures noted in the literature are as
                                              follows:
                                              Concentration
                                                of Endrin
Type of
mo/1
0.0006
0.001


0.0015
0.003
0.003
0.003
0.005
0.005
0.006
8.051
0.1
0.14
0.61
4.2
10.7
20
Fish
BlueRills
Guppies


Golden shiners
Bass
Bluest!!
Goldfish
Carp ftngerllngs
Carp fmserlings
Carp fingerlings
Salmon
Fish
Carp fingerllngs
5-day carp fry
4-day cary fry
2-day carp larvae
Carp eggs
Results
96-hour Tlim
Abnormal behavior In
B hours (20°C),
death in 24 hours
TLn,
TLm
TLm
TLm
48-hour TLm, (28°C)
2 4 -hour TLm
48-hour TLm (1S°C)
96-hour TLm (20'C)
Death
48-hour TLm (8'C)
24-hour TLm (20'C)
24-hour TLm (20°C)
24-hour TLm (20°C)
24-hour TLra (20°C)
Reference
3012


2992
3005
3005
3005
3005
3012
3175
8012
8174
3102
3012
8175
3175
3175
3175
                                                Field applications to rice paddies of one or two Ibs/
                                              acre remained toxic to fish for over one month (3175).
                                              Although laboratory studies indicated a TLm value for
                                              endrin of between 1.0 and 1.5 ng/1, a dose of 1.0 jig/1 to
                                              a pond gave no results. A second dose of 1.0  ng/1 was
                                              administered, but was still without effect. Rapidly lower-
                                              ing temperatures were thought to be inhibiting the lethal
                                              effects (3176, 3178). Endrin,  used  in sugar cane fields
                                              to combat borers, has washed into streams during  heavy
                                              rains, causing fish kills (3177).
                                                The 96-hour TLm values of endrin to fathead minnows
                                              in hard and soft water at 25° C were, respectively, 1.3
                                              and 1.0 jig/1. Tests with bluegills, goldfish,  and guppies
                                              in soft water at 25°C gave values of 0.60,  1.9, and 1.5
                                              jig/1 respectively (3000).
                                                In a  series  of screening  tests of  a large number of
                                              compounds, rainbow trout, bluegill  sunfish, and the sea
                                              lamprey all died within 14 hours at 12°C when exposed
                                              to a 5 mg/1 concentration of an  18J percent emulsion of
                                              endrin  (2976). The estimated concentration of endrin
                                              required to immobilize Daphnia magna in 50 hours at
                                              20°C is 352 |ig/l (3255).
                                                     57

-------
 Source reference:   Report of  the Committee on Water
                       Quality Criteria,  Federal Water
                       Pollution  Control  Administration,
                       U.  S.  Department  of the Interior,
                       April, 1968.

                        TABLE III-5A. Pesticides*
                              INSECTICIDES
      [48-hour TLm values from static bioassay, in micrograms per liter. Exceptions are noted.]
Gamma rus
Stream invertebrate >
Pesticide
Abate 	 -

Aldrin" 	

Allethrin 	
Azodfin 	
Aramite 	
Baygon* 	
Baytex' 	

Benzene hexachloride
(lindane).
Bidrin 	
Carbaryl (sevin) 	
Carbophenothion
(trithion).
Chlordane'- 	
Chlorobenzilate 	
Chlorthion 	
Coumaphos — 	
Cryolite 	
Cyclethrin 	
ODD (IDE)5- 	 —
DDT" 	
Delnav (dioxathion) __
Delmeton (systex) 	
Diazinon • 	
Dibrom (naled) __ 	
Dieldrin ' 	
Dilan .. 	
Dimethoate
(cygon).
Dimethrin 	
Species
.Pteronarcys 	
californica.
.P. californica ...

_P. californica 	


-P. californica „_
-P. californica 	

P. californica 	

-P. californica 	
-P. californica 	


-P. californica . .





-P. californica 	
-P. californica 	


-P. californica __
-P. californica 	
-P. californica. _.

P. californica 	


Dichlorvos ' (DDVP) — p. cafifornica
Disulfoten (di-syston)._p. californica
Dursban 	 .

Endosulfan (thiodan) _
Endrin 8 	 	
EPH 	 —
Ethion 	 	 -
Ethyl guthion • 	
Fenthion 	 	 	 -
Guthion • 	
Heptachlor" 	 	
Kelthane (dicofel) 	
Kepone _ 	
Malathion • 	 	
Methoxychlor* _. 	
Methyl parathion * 	
Morestan _. 	 	
Ovex 	 ._
Paradichlorobenzene .
Parathion ' 	
Perthane 	
Phosdrin * . 	 - ..
Phosphamidon 	
Pyrethrins 	 .
Rotenone 	 -. .
Strobane' 	 -
Tetradifon (tedion) ...
TEPP" 	
Thanite 	 	 . -
Thimet . - 	 -.
Toxaphene * 	
Trichlorofon
(dipterex).'
Zectran 	 	
-Peteronareella
badia
-P. californica 	
-P- californica 	

-P. californica 	

-P- californica 	
-P. californica 	
-P. badia 	
-P. californica 	

P. badia . .__
-P. californica 	

-P. californica 	
-P- californica.

.P. californica

-P. californica 	
.P californica. .
.P. californica 	
.P californica 	
P. californica 	




..P. californica 	
P. badia... ...

P. californica 	
TLm
100

8

28


110
130

8

1,900
1.3


55





1,100
19


60
16
1.3

140


10
18
1.8

5.6
0.8

14

39
8
4
3,000

6
8

40
1,500

11

9
460
64
900
7




7
22

16
Cladocerans *
Species


Daphnia 	
put ex.
D. pulex 	

D. magna 	

Simocephalus
serrulatus.
D. pulex 	

D. pulex 	
D. pulex 	 	
D. magna 	

S. serrulatus
S. serrulatus..
D. magna 	
D. magna 	
D. pulex 	
D. magna 	
D. pulex 	
D. pulex 	


D. pulex 	
D. pulex 	
D. pulex 	
D. magna 	
D. magna 	


D. pulex 	


D. magna 	
D. pulex 	
D. magna
D. magna 	
D. pulex 	
D. pulex 	
D. magna 	
O. pulex _ ...
D. magna 	

D. pulex 	
D. pulex 	 . .
D. magna 	



D. pulex 	
D. magna 	
D. pulex 	
D. magna 	
D. pulex 	
D. pulex 	



D. magna 	

D. pulex 	
D. magna 	

D. pulex 	
TLm


28

21

345

3.1

460

600
6.4
0.009

20
550
4.5
1
5,000
55
3.2
0.36

14
0.9
3.5
240
21
2,500


0.07


240
20
0.1
0.01

4
0.2
42
390

1.8
0.8
4.8



0.4
9.4
0.16
4
25
10



450

15
8.1

10
Fish"
Species
Brook trout--

Rainbow 	
trout.
do 	
do 	
Bluegill 	
Fathead 	
Brown t. 	

Rainbow t 	

do 	
Brown t. 	
Bluegill . ..

Rainbow t 	
do 	


Rainbow t 	

Rainbow t 	
Bass 	 .
Bluegill _ .
do 	
do 	 __
Brook t. 	
Bluegill 	
do 	
do 	

Rainbow t 	
Bluegill
do . 	
Rainbow t 	

do 	
Bluegill 	
do
do
Rainbow t 	

Rainbow t 	
do 	
do
do
Brook t. 	
Rainbow t 	
Bluegill
do _
do 	
Rainbow t 	
Bluegill
Rainbow t 	
do
do 	
do - 	
Bluegill 	
Rainbow t.- .
Bluegill 	
Fathead 	

Bluegill 	
Rainbow t 	
do 	

do 	
lacustris,*
TLn,
1,500

3

19
7,000
35
25
80

18

8,000
1,500
225

10
710


47,000

9
2.1
14
81
30
78
3.4
16
9,600

700
700
40
20

1.2
0.2
17
230


10
9
100
37.5
19.5
7.2
8,000
96
700
880
47
7
17
8,000
54
22
2.5
1,100
390

5.5
2.8
160

8.000
TLm
640

12,000

20

100
50
70

88

790
22
28

80


0.14


1.8
2.1
690

500
160
1,000
600
400


1
70
0.4

64
4.7
36
3.2


0.3
100


1.8
1.3






310
3.8
18
350

140
52

70
70
60

76
• See notes following Table III-5B.
                              58

-------
                    STRICTLY  CONFIDENTIAL
                                Situation Report No.	3_

                                RETA No.  862-1
                                TIME PERIOD:

                                     From: 12:00 noon,  June 14,  1971

                                     To:   6:00 p.m.  June 17,  1971
          Dr. C. H. Thompson, Project Officer
          Environmental Protection Agency
          1921 Jefferson Davis Highway
          Arlington, Virginia 22202
FROM:     Dr. George M. Barsom, Project Manager
          Ryckman, Edgerley, Tomlinson and Associates, Inc.
          225 S. Meramec
          St. Louis, Missouri 63105
                           RETA 862-1
DATE: June 18, 1971	

                               59

-------
I.   INFORMATION FROM THE FIELD
    Major effort appears to center on the construction
    of a pilot plant to run at about 10 GPM.
    1.  The pilot plant is built around a commercial
        swimming pool filter being used as a  rapid sand
        filter to remove some organic material and silt
        from the water.  The output of the pool filter
        is fed to a vertical carbon column 18" diameter
        and 7% ft. tall.  This system will be used to
        establish the required contact time and perhaps
        carbon capacity.
   C
                a-
1






-\



0 «
0
•HW^^^^B
- ^ £* -C C
AC f \ w<
	 2- 	 C a*\t>

pool
              •la 0 V\
            C. 0
     Uke
        The inlet dam structure  is  working  well.   Rain
        estimated V  in a 3% - 4 hour  period  -  6/15 was
        captured and  pumped around  the lake by  one of
        two pumps available. The quantity  of water pumped
        was not known but was thought  to  be about  3000 GPM.

        Ohio State University is providing  a  gas chromat-
        ograph on the scene. Installation  should  be
        complete by June 17, 1971.   This  will permit more
        rapid evaluation of the  pilot  plant.

        There is a possibility of a 50,000  GPD  portable
        plant being brought to the  site either  as  a large
        scale pilot plant or to  control the level  of the
        lake if very  heavy rain  would  raise the level.

        Some bottom samples have been  taken and are being
        analyzed in Cincinnati.
                             60

-------
II.  Ecological Damage and Recovery Survey

     A program to assess the ecology of the damaged area needs
     to be formulated and implemented.  Benthic and periphyton
     samples in the lake, inlet stream and discharge streams
     need to be collected and analyzed.  Pond Lick Creek has
     suffered visible damage 1/2 mile below the spillway as
     was noted in situation report #1.  The ecological study
     is needed to make sure no further damage occurs in con-
     nection with treating the lake or eventual discharges
     from the spillway.  A series of sample stations, outlined
     on the schematic map attached, need to be studied.  Station
     1 would be upstream of the new dam area and thus serve as
     a control.  Fish and invertebrates from this area should
     be analyzed for background endrin levels.  Benthetic and
     periphyton samples are needed also.  Stations 4-6 on Pond
     Lick Creek would show damage done by the endrin before it
     was controlled and also be monitor points downstream dur-
     ing the treatment process.  Stations 7 and 8 in Turkey
     Creek should also be monitored but do not show lethal
     damage.  They may show a concentration of pesticide in
     the aquatic population and are thus important.
     Wells in the area have been located from state records
     and (see attached maps) wells along Turkey Creek should
     be tested now and monthly to verify that ground water con-
     tamination has not occurred.
     Stations 2 and 3 in the lake will require vertical profile
     sampling as well as bottom samples.
     Water samples should note pH, D-0- and endrin each week
     and daily measurements of endrin will be needed below the
     discharge point if the treated water is released to the
     stream.  In any case, fish should be put in the product
                               61

-------
     water from the  treatment  system each  1/2  to 1  hour as a
     check of  the  effectiveness  of  treatment stream samples.
     Ecological and  biological samples  will probably be needed
     every 4-6 weeks  to monitor the recovery of the stream
     system.

III.  Recommendations for Laboratory Work on Countermeasures
     We are not aware of any laboratory work that has been done
      on determining  which  one  of several types of activated car-
      bon will  give the best removal of  endrin  from  the lake
     water.  Screening a number  of  samples in  jar tests under
      standard  laboratory conditions is  highly  desirable before
      a pilot study is run.   This will allow the pilot study to
      determine the detention time and pretreatment  needed for
      the most  efficient type carbon. Without  such  a study the
      pilot plant and full  scale  process as well may be set up
      using a carbon less efficient  and  therefore more expensive
      than necessary.  RETA feels strongly  that laboratory test-
      ing is necessary and  should include GC and bioassay studies
      to show removal of endrin.

 IV.   Countermeasures Available
      To date,  several Countermeasures have been proposed.  Some
      are more  attractive than  others economically and in pro-
      bable effectiveness.   However, without the previously men-
      tioned laboratory studies it is impossible to  determine
      with certainty what is the  best alternative.  The decision
      as to what alternative will be used must  be made in the
      field by  those with first-hand information. During this
      time, the RETA office facilities became a research and supply
      information center.
      The listing below summarizes the Countermeasures.  Each
      is then shown in more detail on a  separate page.
                                62

-------
 A-.       ^-
te^-^
     T^K^
           J
 /,i/<''•, A v ?'•

     £s)
  .  ,.. Iff
  ('?''$>
, , "/ y> Mi'
D'.*np Oyo
          ,
          '

^\  ^ 1 J '«  ^VR*v *.  f • *  L
\- VV-VjJTJ-/- -'  \ A. i


\\^^rK>sV '

-------
                                                                                T-
•   .'•'•   V ..'A.-  A-'-V.Y'Y  !J"'   'jr.
              '..".'  '   ."/•'' ;-   ~  •-'-  'V. •  \  •'•'•.:
>->.,>     -.\\V     '    ••••••   '  .'-M '   :   ''
                                                                             ..

                                                                             '*' Sv 'll   1
                                                                               >V
^ v
                                             EVE  ,NN{"S T  A JVB  . ; P ,V0  U , K  S -T
                           ^4:v;'7:---^-rx          ;:-
                                                               '-
                                  -          .     .

                                                  ^^0 Onl°
                                                  •ui  "
                                                                       •• \r>  ,,
                                                                      /. i \ >• /1  ,i

                                                   '-• ~-"j* -.     i\ j -• -• .   "^- '
                                                  •>iMt»Ay   ""r-v.'v.v/ /.••-••••.   s' , ,

                                                 r*~s?.-  Met   vr-'  .-• •'/   •"••*r-""-t"
                                                 ^ .: ^.   LKlv     ( ^ ;..-.- ,. /  ,  ,;,  .  -

                                                 '.jtr '  '••-.,-i'i  v.,r^'..'  •///
                                                 ^ .- ' -•'-•' .'{*• -K r" \; •••/'   ' ' ' «'•', . • ' • ' ,  . .'
                                                 ?•  ;  .,'>*•/-''\  .. >j i.".^-- ?,•',','••• i  . //•• •
                                                  . '  ••••  .--70 y ^x ~  -/•'  .•• •  '/
                                                 .,  //••;.-,/VX /V   vV/'A •   .../  -
                                                                                    a1*4

-------
1.  Treat lake with bentonite slurry.  Let settle.
2.  Treat lake with fly ash and let settle.
3.  Spread activated carbon onto the surface of the
    lake and let it settle.
4.  Allow lake to recover itself.  Monitor and bioassay
    extensively to gain knowledge useful in a larger
    spill.
5.  Spray irrigate the endrin water onto surrounding land.
6.  Load contents of lake into barges  and take to sea.
7.  Build an activated carbon filter and pass the lake
    through it.
                            65

-------
       COUNTERMEASURE


1.  Spread a slurry of bentonite on the
    Lake, allow to settle and spread a
    second layer a week later to seal
    the endrin to the bottom.
       REFERENCE


Settling characteristics,
R. L. Folk, Petrology of
Sedimentary Rocks, Uni-
versity of Texas, 1965
  Flow Diagram
  Materials

  Boat to apply bentonite slurry

  Slurry making equipment - pump and mixer
  Approximately 1 ton bentonite ($80 -  $100)

  1 ton will give 2 100 mg/1 applications  if  the lake volume
  really is 15 million gallons.

  Readily available.


  Procedure and Technique

  Bentonite absorbs well, settles slowly,  so  it would scrub the whole
  lake and is cheap.  The second layer  would form a seal preventing
  desorption.  Jar tests could quickly  determine the dose.   The size
  could be chosen to give 18 - 48 hours contact time before the clay
  is all on the bottom.  This is an inexpensive operation,, both from
  materials and labor viewpoint and seals  the endrin into a favorable
  area geologically, preventing ground  water contamination.
                                  66

-------
       COUNTERMEASURE                                REFERENCE


2.   Spread fly ash on the surface of the lake.    Fly Ash   J  D  Eye
    Let  it settle, adsorbing endrin on the       Research, University
    surface  on the way down.                     of Cincinnati
  Flow Diagram
                 L en he
        777777777777
              t-afre  Be>#0»*  S
   Materials

   Fly ash -  amount determined by jar tests.   Should be available
   for hauling costs  from almost any coal-fired power plant.
   Procedure  and  Technique

   Spread fly ash as  a powder on the surface of  the lake and let it
   settle.  A second  application may be useful to seal the endrin in
   and prevent desorption into the bottom water of the lake.

-------
       COUNT ERME AS URE                                  REFERENCE!


3.  Spread powdered activated carbon              Suggested by early
    on the lake and let settle.                    action of State of
                                                  Ohio.
  Flow Diagram
  Materials


   Powdered activated carbon -  equivalent  to Aqua-Nu-Char.   App.  9£/lb.
  One  firm offered enough carbon free to  treat the lake.  This was  an
  estimated 200  Ibs.  of material.
   Procedure  and  Technique


   Spread the activated carbon and  let  it  settle,  picking up endrin as
   it falls.   This requires  a fine  powdered carbon,  not a granular
   material.
                                   68

-------
     COUNTERMEASURE
                                                     REFERENCE
 Let the lake recover  itself,
Flow Diagram
Dr. R. E. Hanson,
Shell Chemical Co.
Agriculture Products Div.
San Ramon, California
(telephone 6/15/71  to
 D. Clement,  RETA,
St. Louis)
Materials
Procedure and Technique

Monitor the recovery in terms  of  endrin  in Pond Lick Creek and
Turkey Creek.  Level of endrin involved  is not thought to present
a hazard to man or livestock now.  The time required to allow fish
to live in the lake again could be determined.  Caged bluegills
or continuous bioassay with stream side  tanks are possible.  This
would permit gathering information useful if a much larger lake
were poisoned when it would be impractical to treat it.
                                 69

-------
       COUNTERMEASURE
      REFERENCE
5. Spray irrigate onto surrounding  land.
   Flow Diagram
Telephone conversation
6/16  SJR/GMB - SJR/DPC

Absorptive capacity of
soil.  Sc.D. Research,
J. D. Eye, University
of Cincinnati, 1966.
       rpe
            \\*-f
   Materials
   Pipeline to Ohio River flood plain or truck transport to the
   flood plain.  Irrigation equipment to apply to soil.
   Procedure and Technique

   Soil is a good adsorbant of endrin and probably would filter the
   endrin out of the water.  The golf course on the Ohio river flood
   plain may be a possible area to irrigate but the possibility of
   contaminating ground water aquifers shown on the geologic section
   map in report #2 is greatly increased.  The cost of pipeline or
   truck to the irrigation area is probably too great to make this
   possible. Head loss on pipe system makes a gravity flow distri-
   bution doubtful.
                                   70

-------
      COUNTERMEASURE                                 REFERENCE

6.   Load contents of lake on to
    barges and take to sea for dumping.
  Flow Diagram
  Materials

 Probable barging costs - $1.00 - 1.25 mil/ton-milev  would need
 about 18 standard 840,000 gallon barges.  This is expensive and
 the barges couldn't go into the Gulf to dump.  Would also require
 pipeline or trucks to load barge.

 Costs per telephone call to Ralph Clark 6/16/71
  Procedure and Technique


  Transport by pipe "or truck to barge.  Take- to mouth of Mississippi
  River and discharge slowly if weather did not permit risking river
  barges in open sea.
                                  71

-------
        COUNTERMEASURE
                                                       REFERENCE
7.   Activated carbon filter systems.
   Flow Diagram
           o ° o
           O CJ O
           Ooo
  P.'/ff
                                               JAWWA
                                               Vol. 57, p. 185,
                                               February, 1965
                                               Effectiveness of A.C
Materials
                                            Q
1.  Activated carbon approximately 2,500 ft.

    20 - 40 #/ft3   Cost $12,000 - $20,000

2.  Confinement structure

    pressure vessel - app. $12,000

3.  Ditch or wooden structure

    to hold carbon - app. $5,000

4.  Regeneration, disposal of carbon

Procedure and Technique

1.  Pressure filter assembly built on site.

2.  A. C. in a ditch lined with polyethyline.
                                                      FAB, carbon manu-
                                                      facturers - telephon
                                                      conferences
   3.  A. C. in a wooden structure on surface of ground.

   Calculations based on 1000 GPM, 15 minutes detention time,  indicate
   need for 2500 ft3 carbon.  Carbon weighs 30 - *+0#/ft3
   Recycle to lake possible and desirable
   until process well under control                   Field discussion

   Regenerate carbon in furnace to destroy endrin - by contract
                                    72

-------
                    APPENDIX C
                 GEOLOGICAL REPORT


The Department of Water, Division of Natural Resources,
provided RETA with well logs and basic information which
permitted the completion by Monday, June 14, 1971, of
an^analysis of the danger to ground water in the area.
This information showed that a 40 foot thick layer of
impermeable shale separated the lake from ground water,
and that ground water  in the area was very poor.  Many
of the grilled wells are dry or provide a flow of less
than five gallons per  minute.  RETA concluded that it
was unlikely that any  ground water contamination would
occur unless the entire lake were to drain to the Ohio
River flood plain at one time.  The Ohio River flood
plains do contain aquifers which potentially are very
good sources of water  with well yields of 1000 GPM ex-
pected.  They should not be exposed to the poison by
activities such as landfilling bottom material scraped
from the lake.  The geological report with Figures 12
and 13 follows:
I.  Groundwater

There is little chance of seepage of Pond Lick Lake water
into groundwater.  The bedrock under the lake is largely
impermeable shale with some  interbedded sands.  Most of
the sands are poorly sorted  and not good aquifers.  Fur-
thermore, they are thin  and  isolated from each other by
interbedded shales. The  shales effectively isolate the
sand layers so little water  can collect _or flow through the
sand.  Maximum yields for these sands might be app. 5 gpm.

The Berea sandstone, which is probably 50 feet below lake,
consists of interbedded  sandstone and shale with sands up
to two feet thick.  The  Berea may yield some water, but
because of interbedded shales, it is not a good aquifer.

The first good aquifers  below the lake are Devonian lime-
stone and dolomites of Middle Devonian age which are 600
feet below the lake, and probably bear brackish water.


The only other aquifer in the area is the alluvial deposit
in the Scioto and Ohio Valleys.  The Pond is isolated from
these alluvial materials by  the above described shales
and contamination would  not  be a problem unless the mater-
ial in the lake overflowed and ran down Turkey Creek to

                         73

-------
               5  Ml
                                                                       5
        SUKIBUAY  -5M
BEDFORD  SWAU5.
                                                     OUIO  R1V5R
                                                              1-2
                                                   SOUTH  CROSS SS£TION|
                                                             OMtO

-------
    IOOO
01
                                                      SJ-tALS.  I DEV)
     4 oo
                                                                                                        '. O>
                                                                                      K c .--

-------
the Ohio Flood plain.  The lake is 200 feet above the
alluvial material and isolated from it by impermeable
shale layers as shown by cross sections, Figures 12 and 13.
II.  Geologic Column at Pond Lick Lake

Surface - Cuyahoga Shale and Sandstone; total thickness
of 300 feet, 20/30 feet of this layer is below lake level,
gray shale, sandstone and siltstone, poorly sorted, not
a source of groundwater.  Lower Cuyahoga is Buena Vista
member.  Sandstones are from 1" to 16" thick with inter-
bedded shale.

Sunbury Shale:  20-30 feet,  Dark Shale.  Not water bearing.

Berea Sandstone:  20-60 feet,  gray sandstones up to 2 feet
thick with interbedded shales.  May carry some water lo-
cally.  Sand is generally not  well sorted and is there-
fore not a good aquifer.

Bedford Shale:  50-110 feet, gray interbedded sandstone
and shale.  Sands are thin.   Does not bear water.

Ohio Shale:  ^00 feet, black shale.  Does not bear water.
                         76

-------
                      APPENDIX D

            ALTERNATE STRATEGIES CONSIDERED

The primary consideration  of  the field team was to find a
satisfactory method to eliminate the poison from the lake
rapidly since the upper diverting dam was  only temporary and
could not be relied upon for  long-term protection.

The costs of different treatment methods were roughly esti-
mated, as was the time required to  implement the plan.  These
strategies were forwarded  to  the field where they were dis-
cussed with other ideas formulated  on site and by Dr. Thompson.

Also sent to the field was  information on  performance stan-
dards required in terms of  Endrin toxicity tolerances.  This
information is shown in this  appendix.

Initial failure of the activated carbon spread on the lake
to remove Endrin led to the feeling that a pilot plant assembly
was necessary prior to any  further  large scale use of carbon.

Public concern and the need to do "something" to show removal
of the poison was a factor  involved in the decision to use a
removal technique rather than a less expensive in-place treat-
ment of the Endrin.

This section of the report  discusses seven alternate treat-
ment methods in some detail.  The methods  are:

1.  Treat lake with bentonite slurry.  Let settle.
2.  Treat lake with fly ash and let settle.
3.  Spread powdered activated carbon onto  the surface of the
    lake and let it settle.
4.  Allow lake to recover  itself.   Monitor and bioassay
    extensively to gain knowledge useful in a larger spill.
5.  Spray irrigate the Indrin water onto surrounding land.
6.  Load contents' of lake  into barges and  take to sea.
7.  Build an activated carbon filter and pass the lake through
    it.

COUNTERMEASURE                           REFERENCE

1.  Spread a slurry of bentonite on     Settling characteristics.
    the lake, allow to settle and        R. L. Folk, Petrology of
    spread a second layer  a week later   Sedimentary Rocks, Uni-
    to seal the Endrin to  the bottom.    versity of Texas, 1965.

Materials
Boat to apply bentonite slurry.
Slurry making equipment -  pump and  mixer


                           77

-------
Approximately 1 ton bentonite ($80 - $100)
1 ton will give approximately 100 mg/1 applications if the
lake volume really is 15 million gallons.
Readily available.

Procedure and Technique
Bentonite absorbs well, settles slowly, so it would scrub
the whole lake and is cheap.  The second layer would form a
seal preventing desorption.  Jar tests could quickly deter-
mine the dose.  The size could be chosen to give 18 - 48 hours
contact time before the clay is all on the bottom.  This is
an inexpensive operation, both from materials and labor view-
point and seals the Endrin into a favorable area geologically,
preventing ground water contamination.


COUNTERMEASURE                           REFERENCE

2.  Spread fly ash on the surface of     Fly Ash.  J. D. Eye
    the lake.  Let it settle, adsorb-    Research, University
    ing Endrin on the surface on the     of Cincinnati.
    way down.

Materials
Fly ash - amount determined by jar tests.  Should be available
for hauling costs from almost any coal-fired power plant.

Procedure and Technique
Spread fly ash as a powder on the surface of the lake and
let it settle.  A second application may be useful to seal
the Endrin in and prevent desorption into the bottom water
of the lake.

COUNTERMEASURE                           REFERENCE

3.  Spread powdered activated carbon     Suggested by early
    on the lake and let it settle.       action of State of
                                         Ohio.

Materials

Powdered activated carbon - equivalent to Aqua-Nu-Char.  App.
9£/lb.  One firm offered enough carbon free to treat the lake.
This was an estimated 200 Ibs. of material.
Procedure and Technique

Spread the activated carbon and let it settle, picking up
Endrin as it falls.  This requires a fine powdered carbon,
not a granular material.
                           78

-------
GOUNTERMEASURE

k.  Let the lake recover  itself.
                                         REFERENCE

                                         Dr. R. E. Hanson,
                                         Shell Chemical Co.
                                         Agriculture Products Div,
                                         San Ramon, California
                                         (telephone 6/15/71 to
                                         D. Clement, RETA,
                                         St. Louis).
Materials
Procedure and  Technique

Monitor the recovery in  terms  of  Endrin in Pond Lick Creek
and Turkey Creek.   Level of  Endrin involved is not thought
to present ,a hazard to man or  livestock now.  The time re-
quired to allow  fish to  live in the lake again could be
determined.  Caged  bluegills or continuous bioassay with
stream side tanks are possible.   This would permit gathering
information useful  if a  much larger lake were poisoned when
it would be impractical  to treat  it.
COUNTERMEASURE

5.  Spray  irrigate  onto surrounding
    land.
                                         REFERENCE

                                         Telephone conversation
                                         6/16  SJR/GMB - SJR/DPC
                                         Absorptive capacity of
                                         soil.  Sc.D. Research,
                                         J. D. Eye, University
                                         of Cincinnati, 1966.

Materials
Pipeline to Ohio River flood plain or truck transport to the
flood plain.  Irrigation equipment to apply to soil.

Procedure and Technique
Soil is a good adsorbant of Endrin and probably would filter
the Endrin out of the water.  The golf course on the Ohio
River flood plain may be a possible area to irrigate but the
possibility of contaminating ground water aquifers shown on
the geologic section map in Appendix C is greatly increased.
The cost of pipeline or true* to the irrigation area is prob-
ably too great to make this possible.  Head loss on pipe
system makes a gravity flow distribution doubtful.
COUNTERMEASURE

6.  Load contents  of  lake on^to barges
    and take  to  sea for  dumping.
                                         REFERENCE
                            79

-------
Materials

Probable barging costs -  1.00 - 1.25 mil/ton-mile, would
need about 18 standard 84-0,000 gallon barges.  This is ex-
pensive and the barges couldn't go into the Gulf to dump.
Would also require pipeline or trucks to load barge.
Costs per telephone call to Ralph Clark 6/16/71.

Procedure and Technique
Transport by pipe or truck to barge.  Take to mouth of
Mississippi River and discharge slowly if weather did not
permit risking river barges in open sea.
COUNTERMEASURE

7.  Activated carbon filter systems.
Materials

1,
                                     REFERENCE

                                     JAWWA
                                     Vol. 57, p. 185,
                                     February, 1965
                                     Effectiveness of A.C,
Activated carbon approximately 2,500 ft.
20 - 40 #/ftJ  Cost $12,000 - $20,000
Confinement structure
pressure vessel - app. $12,000
Ditch or wooden structure
to hold carbon - app. $5,000
Regeneration, disposal of carbon
Procedure and Technique

1.  Pressure filter assembly built
    on site.
2.  A. C. in a ditch lined with
    polyethylene.
3.  A. C. in a wooden structure on
    surface of ground.

Calculations based on 1000 GPM, 15
minutes detention time, indicate need
for 2500 ft^ carbon.  Carbon weights
30 -
                                     FAB,  carbon manufacturers
                                     telephone conferences.
Recycle to lake possible and desir-
able.  Field discussion until pro-
cess well under control.

Regenerate carbon in furnace to de-
stroy Endrin - by contract.
                                     Field discussion.
                           80

-------
                      APPENDIX  E

                   TREATMENT SYSTEM

This section of the report details the decision to build a
pilot plant to measure the effectiveness of a carbon filter
and illustrates the means by which the successful operation
of the pilot plant led directly to the design, construction,
and operation of the prototype  plant built to treat Pond
Lick Lake.

Pilot Plant

The combined field team  of State, Federal and RETA
consultants felt a definite need  to evaluate activated
carbon in a pilot scale  operation after the failure to
function of the first carbon applied to the lake.

Published literature (JAWWA 57:181-199, 1965) showed that
activated carbon was effective  in removing Endrin at a
loading rate of 0.5 GPM/cubic foot of carbon.  The pilot
plant was built with this flow  as the loading criteria.

Tuesday afternoon in a meeting  of all present field personnel,
Dr. Thompson suggested and Mr.  Nye approved design and con-
struction of a pilot plant.  RETA engineers designed the plant
from a rough sketch by Dr. Thompson.

The decision was made about 6 p.m.  By 9 p.m. construction
had started, a pressure  filter  from a swimming pool had been
located and arrangements made to  ship it to the site the next
day.  Electricity was ordered and installed about daybreak
Wednesday.  Welders worked through the night Tuesday to fab-
ricate a column to hold  the carbon bed.  Construction was
completed and the plant  put in  operation Wednesday afternoon.
The pilot plant under construction is shown in Figures 14, 15a,
and 15b.

The pilot plant was designed to answer several questions in
a planned operating period of 24-48 hours:
1.  Determine the Endrin adsorption capacity of activated
    carbon.  This figure would  give an estimate of the
    carbon needed to treat the  entire lake if it were to
    be filtered.
2.  Determine the residual level  of Endrin and thus the
    removal efficiency of the activated carbon process.  This
    would also indicate  the ability of the system to meet
    effluent standards for Endrin in water.
3.  Confirm suitability  of the  chosen loading rate and study
    effects of varying the rate.

                           81

-------
                                                                                                                                        EFFUURHIT
                                                                                                                                        L.IMK.
                                              PRESSURE  
-------
Figure 15a - Pilot plant under construction,
Figure 15b - Loading carbon in pilot plant column,


-------
4.  Show if a prefliter to remove organic material was needed.

5.  Provide, by running until breakthrough, an estimate of the
    life of the carbon.

6.  Demonstrate that an upflow filter assembly would provide
    greater carbon utilization by agitating the bed sufficiently
    to continuously expose fresh carbon surfaces.

7.  If needed, evaluate different grades and brands of avail-
    able carbons (this did not prove necessary).

The plan of operation was to take frequent samples and send
them to Cincinnati for gas chromatographic analysis, with con-
current fish bioassays at the site, since there was not a
chromatograph available at the site at that time.  By Wednesday
afternoon the Department of Natural Resources had located a
G.C. at Ohio State University which was available for use at
the site.   It was moved to the site and installed between 1:30
a.m. and ^:00 a.m. Thursday, as described in the critical
decisions section.

The pilot plant showed the available carbon was effective
and Thursday afternoon Dr. Thompson made the decision to
build a prototype plant to treat the entire lake.  The pilot
plant was kept in operation to find the capacity of the carbon
bed and ran until June 25 without reaching breakthrough.   A
power failure occurred due to heavy rains on June 25,  and in
restarting the pilot plant after the power was restored,  a
high flow rate occurred which washed the carbon out of the column,
destroying the pilot plant.  Its operation was terminated shortly
thereafter.

Design of Prototype Plant

The upflow carbon filter was designed by first determining
what basic equipment that might possibly be used was avail-
able, and then applying the design parameters obtained in
the pilot plant study to this equipment to calculate the
rate at which this system could treat the lake water.   Since
the resulting rate was found to be acceptable, the auxiliary
portions of the system were then sized and all necessary parts
listed and either obtained or redesigned so that existing
parts could be used.  The obvious purpose of utilizing avail-
able equipment wherever possible was the saving of time.

The first item sought was a tank or basin to hold the carbon.
Temporary modification of portions of the spillway from the
lake was an early consideration.  On-site construction of a
wooden frame for holding the carbon was also contemplated.
In the search for a tank, Dr. Thompson, in discussion with
                           84

-------
Dr  Sid Hana of Cincinnati  EPA,  discovered  that some wooden
tanks of 3" thick cypress with  inside  dimensions of 4' x 18'
x 7' high, which had previously been constructed for research
in water treatment, were owned  by  EPA  and located in Cincinnati.
The State quickly provided  an airplane to transport Dr. Thompson
to Cincinnati to inspect the  units and dispatched a flat-bed
truck to the city to save time  if  the  tank  proved to be sat-
isfactory.  Dr. Thompson located and measured a suitable unit
and made necessary  arrangements for its use.  Had the tanks
been unsuitable, he would have  cancelled the trucks by radio
from his plane.

The pilot plant had operated  well  up to a rate of-7.5 gpm,
which was a volumetric  loading  rate of 0.5  gpm/ft  and a
surface loading of  3.5  gpm/ft .  Above 8.0  gpm, there was
increased expansion of  the  bed  and lift out of the carbon
through the top restraint.  The available depth in the large
tank was only 6 feet, compared  to  7 feet in the pilot plant
unit.  This resulted in a lower surface loading and decreased
tendency for the carbon to  be lost in  the upflow at the same
volumetric loading  of 0.5 gpm/ft .   The total flow corresponding
to the design rate  was  216  gpm,  or approximately 1/3 mgd.  The
maximum permissible flow through the filter was calculated to
be 225 gpm.

The decision was made to use  one of these tanks on Thursday
afternoon and it was delivered  on  Thursday  night at 11:30
p.m.  Until the box was examined more  closely for location
of reinforcing bars and joints,  very little of the design
of inlet and outlet piping  could be done.   The tank was sent
to the garage at the Shawnee  State Forest headquarters, where
welding equipment and other facilities were available.

Preliminary design  sketches prepared by Dr. Cecil Lue-Hing
and Joe Dieterman showed dual 8" diameter PVC inlet manifolds
running the entire  length of  the box and resting on the bottom.
They were spaced with centers one  foot from the two sidewalls
and drilled on both sides with  1/2" diameter holes every 6".
The weight of the filter material  was  supported on three rows
of concrete blocks  spaced at  2'  centers, covered by expanded
metal grating, 1/8" grid hardware  cloth, and muslin.  The 6'
bed of activated carbon was shown  to be covered by another
layer of muslin to  separate the carbon from a V layer of
vermiculite on top.  The purpose of the vermiculite was to
provide a cushion against excessive packing of the carbon.
The filter bed was  held in  place by reverse construction ot
the filter bottom - muslin, 1/8" grid  hardware cloth, and
finally expanded metal  grating.  Two by four stringers placed
upright at 24" intervals held the  filter top secure and the
water level was maintained  above the filter box by adding
                            85

-------
2 x 12 boards as risers on three sides of the tank.   One end
of the tank top was shown as an overflow weir,  with  the flow
being caught in an overflow box which emptied through a bottom
effluent pipe.   The tank and risers were lined with  continuous
plastic liner to minimize leakage.   A copy of  this  field
design sketch   is  presented in Figure 16.     The
map sketch, Figure ID,  shows the location of the pump and
filter at the lake.

The activated carbon specified was  that used in the  pilot
plant - Galgon Filtrasorb 400,  12 x 40 mesh.  Calgon repre-
sentatives had verified that the quantity required,  approx-
imately 26,000 Ibs., was available  from a production facility
in nearby Catlettsburg, Kentucky.  They also indicated that
they would repurchase the spent carbon.

Inlet piping was also originally specified as 8" PVC pipe,
with the two manifolds under the filter combining at a Y
section, which then changed to metal plumbing with an 8"
globe valve.  However, it was soon determined that the large
pipe sizes and fittings would not be obtainable from stock.
The design was modified to 6" PVC manifold pipes in the filter
coming out into an elbow and a tee-section with the  common
header valved with a 4" gate valve.  Galvanized piping up-
stream from the valve were shown as a flow meter, a tee-section
leading to a by-pass (also with a gate valve),  and a connection
onto the fire hose from the pump.  All these fittings were
originally designed as 4", but the use of a 3" meter with its
extremely high head loss compared to the remainder of the
fittings made the use of 3" piping much more reasonable.  The
meter was loaned to the project by the Portsmouth Water De-
partment .

A pump with approximately the head-discharge characteristics
needed for the filter system was already owned by the Ohio
DNR and located in Chillicothe.  The pump, powered by a gasoline
engine, was used very infrequently to flood marshes  and was
stand-by equipment for fire-fighting.  The pump was fitted
to use 2-1/2" fire hose on the discharge side and 4" hard
rubber hose on the intake side.  A strainer and float for
the intake were also designed.

Although a pressure sand filter had been used in the pilot
plant to protect the carbon column from suspended solids in
the lake water, the decision was made to eliminate this unit
from the full-scale treatment operation.  This was primarily
because of the very low suspended solids in the lake - an
average turbidity of 7 units coming into the sand filter and
4 in the effluent from the pilot plant carbon filter.  In
three full days of operation, the pressure loss through the
sand filter had not increased perceptibly.


                           86

-------

I-URDWARS CLOTW ^~
WINDOW SCRREM 	

-LOW IN
f
t* FVC 6CWBR "^
£»i oe VA/L-TU \A>*1

~>
"~W: ^ i
.Tin •V;:-v?.': i AkCTWATSD -CA«BO»
k\ '.•is&^-*; / (
|' ^^:- 1 / '




* i
(
} ^


                                                            _nJ.
                                                             LJ^-IC/ OV6RPLOW PIP«
                                                               PLOW OUT

                                                              •UARDWARB. CLOTH
                                                              — S, RATING!

                                                              -~£OMC. BLOCKS
    V4C-L-BS ON C."
                                       ONL.Y)
                                 nnnEin®

    W-^g)—

    f*i«e9 fc. ji ^^•Tffcl
S'WATBIR M»TBR
!
                       BYPASS TO LAJCE
                                           «iOBME»SlBL.B PUMP
                                           IN
                                                                  ACTIVATED  CARB.O^4
                                                                  FILTER FOR. POMD
                                                                  LICK  RESERVOIR

-------
 DIVERSION DAM
BY-PASS PUMPS
                                                                        •VALVE  BOX

                                                                     ^—-ORIGINAL  DAM

                                                                        ELEC. SUBMERSIBLE PUMP
                                                                        SPILLWAY
                                                                        STILLING WELL
                                                                              FLOW METER
                                                                'CARBON  FILTER  BOX
                                                                         FIGURE  10
                                                                 PLACEMENT OF  ACTIVATED
                                                                 CARBON  FILTER   PLANT
                                                                   AT  POND  LICK  LAKE

-------
The locations^of the pump, filter,  and piping were largely
dictated by site conditions  near  the  spillway.  Because of
the by-pass pipes lying between the roadway and the paved
parking area near the  spillway, it  was not easily possible
to place the filter in this  otherwise desirable location
Therefore,^it was lifted  from the truck by a crane and placed
almost against the pipeline  at the  edge of the roadway.  The
pump, which was readily movable because the unit was mounted
on^wheels, was located on a  concrete  pad  at the edge of the
spillway just a few inches above  lake level.  This minimized
the length of suction  hose needed and the suction head on the
pump.

Several modifications  were made from  the  design described
above as a result of construction or  operation difficulties.
These changes are described  in the  following two subsections.

CONSTRUCTION

In order to accommodate the  concrete  blocks between the
sidewalls  of  the tank  and the inlet manifolds, the PVC pipes
were actually placed close to the third points across the
bottom rather than one foot  from  the  sidewalls.  After the
holes for  the inlet pipes were cut  and the pipe inserted,
held in place by brackets, and the  holes  sealed, the filter
box was ready to be moved to the  lake site.  The plastic
liner was  installed and several existing  fixtures on the
box were also modified or sealed  at the garage before moving
the filter tank.

The box was leveled by placing wood shims under corners on
the downhill  side, with main emphasis on  keeping the weir
level.  The thickest skim needed  was  about 2".  Subsequent
experience indicated that the wood  was inadequate to support
the weight of the tank when  filled  with water.  The wood at
the intake end of the  tank crushed, resulting in a level
overflow end  but a torque and distortion  of the tank.

The bottom screens were cut  and placed in the tank with
careful work  at the edges and overlaps.   Before the muslin
was put in, a field conference was  held and it was decided
that the possibility of the  muslin  blinding with fines in
the water  or  carbon was great enough  and  the difficulty in
removing the muslin would be so great that the muslin should
not be installed.  It  was decided to  use  a *+" layer of gravel
in place of the muslin to prevent loss of carbon through the
bottom screen.  Some gravel  was available in the State Forest
It was loaded onto a dump truck,  washed,  and placed in the
tank without  any significant time loss.   A sample of the
gravel was taken for later size analysis.
                            89

-------
While the bottom was being installed, the weir plate and
overflow box were also being constructed.  The weir plate
was simply a tin sheet molded to the top of the 3" cypress
board, providing a smooth, broad-crested weir that brought
the overflow away from the edge of the tank so that the
overflow box could catch it.  A3' deep by 2' wide box built
of spruce lumber was attached to the end of the tank at an
approximate 15° angle.  This permitted insertion of a sec-
tion of 10" aluminum pipe into the bottom of the low side
of the box to drain the box, rather than the original design
of a pipe coming out of the bottom.  The advantages of this
change were many:  no elbows would be required to direct the
flow into the spillway; there was no downward force on the
piping which would require a more substantial attachment to
the overflow box; and a greater flow could be accommodated
because of the low head loss characteristics of the revised
flow design.

Before loading the activated carbon, additional cleaning of
the gravel was ordered.  This was accomplished by connecting
the pump and inlet piping and adding the risers to the top of
the tank.  Two by fours placed flat to hold the plastic liner
topped by 2 x Vs on edge were used for risers instead of
the 2 x 12 planks originally specified.  The flat 2 x Vs
were to restrain the upward movement of the screen edges
and prevent bubbling of carbon along the walls, a problem
encountered in the pilot plant.

Flow of water through upflow unit cleaned the gravel within
15 minutes and also showed leaks.  Most of these were between
sideboards in the filter which would swell shut within a day.
Some of the larger cracks were caulked with waterproofing
compound.  However,  the major leaks were at the joints in
the PVC inlet piping.  These were later repaired by S. J.
Ryckman and Dr. Thompson when the tank was drained by mixing
a patching compound of the sealant used for the PVG pipes
and ground PVC.  This paste was built into a 45° weld around
all the joints and then covered by a black plastic tape,
followed by nylon filament strapping tape.  Dr. Thompson
also ordered a complete new manifold in case of failure of
the joints.


The carbon was then added to the tank filled with water.
Trucks full of 60 Ib. bags of the carbon were parked next
to the side of the tank.  Temporary scaffolds were laid
along the top of the filter to permit the workers to easily
move about the top.   The bags were handed to the workers on
top, who cut holes in the bags and permitted the carbon to
empty from the bags  slightly submerged.  This procedure
                           90

-------
eliminated much of the dust problem usually associated with
handling carbon and gave uniform density  in packing of the
bed.  When the carbon was nearly at overflow level, about a
foot of water was drained from  the tank.  The bed could then
be walked on without any significant compaction.  The surface
was leveled with rakes and the  water surface again raised to
the top of the carbon for the final leveling process, using
the water level as a guide.

Again because of possible blinding, the muslin between the
carbon and vermiculite layers was eliminated.  It was de-
cided that separation of the vermiculite  from the carbon
could be achieved by floatation of the lighter vermiculite.
Four inches of dry vermiculite  was spread over the drained
carbon bed and a layer of muslin spread over the top, with
the edges lapped over the filter walls to eliminate leakage
of filter material.  The two restraining  screens were next
added, followed by 2 x 4 stringers notched to fit partly
under the protruding 2 x Vs in the riser section.  The
filter was then ready for operation.

OPERATION

Lake water was started through  the filter at 5:10 p.m. on
June 19.  The pump had been operating for several hours at
about 180 gpm«  with the flow bypassed back into the lake.
The initial flow rate of 40 gpm was achieved by opening
the valve to the filter and then partially closing the by-
pass.  The effluent at first contained many carbon fines and
had a gray color.  However, there was no  boiling or carbon
leakage.  The pressure gauge on the inlet read 2-1/2 psi,
as  it continued to do throughout the start-up and early
operation of the plant, indicating that-the total head loss
through the filter was only slightly above the static head.

A record of filter operation was started  and has since been
maintained.  The first week's record is presented in Appendix F.

Soon after flow was started through the filter, the need for
one change became obvious.  The 2x4 braces on the filter
top obstructed the flow along the top to  the extent that the
water level at the inlet end was four to  five inches higher
than at the overflow.  This variation in  heads would affect
the flow pattern up through the filter and nearly resulted
in  overflowing the filter wall  at the inlet end.  Notches
and eventually rectangular sections were  removed from the
braces to minimize the surface  differential along the filter
top.
                            91

-------
Subsequent increases in the loading rate on the filter
revealed other problems with the filter top.  At rates
above 90-100 gpm,  large amounts of carbon leaked around
the edges of the muslin.  When the muslin was attached to
the walls with wooden strips to eliminate the leakage, the
screen began to bulge upward in the center where it was
not restrained by braces.  An attempt to increase the flow
to the design rate (215 gpm ) at 6:30 a.m. on June 20 re-
sulted in the structural failure of the top as the braces
were pushed out and the screens dislodged.

Dismantling of the top showed the cause of the failure.
Disintegrated vermiculite granules had created a layer_of
pasty consistency of 1/16 to 1/8" thickness on the entire
surface of the muslin cloth.  Blinding of the cloth had
caused the pressure build-up.

The decision was immediately made to remove the muslin and
vermiculite and replace it with a fine mesh screen and pos-
sibly sand and gravel to prevent the carbon from escaping.
Instead of floating the vermiculite to separate it from the
carbon, it was scraped off the top with shovels.  Six inches
of carbon was also removed to provide space for the sand and
gravel layers, if needed.  The remaining carbon bed depth
of 5'2" would accommodate a flow rate of 187 gpm  under de-
sign conditions, as shown in Appendix F, Section 6.

To facilitate any further removal of the filter top,  it was
constructed as an integral unit and then slid into position
and secured.  Two by fours were used to construct the frame,
to which the    40 -mesh screen was stapled.  In place, the
frame rested on the unexpanded carbon bed and left V' of the
freeboard to the screen for bed expansion.  The hardware cloth
and expanded steel grating were placed on top of the screen
and held in place by another frame similar to the bottom one
that was nailed to the sidewalls of the tank to prevent leak-
age of carbon around the edges.  No sand or gravel was added
until the screen was tested by itself.

The start-up procedure of slowly increasing the flow rate was
again used.  Because the carbon fines had been removed during
the previous operation of the carbon bed, very little turbidity
was observed.  At first, however, small carbon granules rose
through the screen and then redeposited on top of the screen.
The total loss of carbon due to this problem was only about
1/2 foot3, all during the first 30 minutes after start-up.
Consequently, no sand or gravel was added.

As the flow was increased to about 100 gpm,  another poten-
tial operational problem was noted.  Large air bubbles rose
                           92

-------
through the filter and escaped  at  the  same places on the top
at frequent intervals.  The  amount of  bubbling  increased pro-
portionately with the flow rate.

To keep the bubbles from  forming channels through the carbon,
injection of more carbon  into the  filter was first attempted'
as a countermeasure.  To  accomplish this, operation of the
filter was temporarily halted and  the  water level drawn down
about three feet.  A three  inch diameter hole was cut through
the sidewall just above the  lowered water level and a flange,
nipple, and gate valve were  attached to the outside of the
hole.  The original water level was restored and carbon slurry
was then pumped from a 55 gallon drum  into the  tank with a
trash pump.  Three 60~lb. bags  were added near  the overflow
end of the filter by this technique.   The injection brought
the unexpanded carbon bed up to the screen in the portion of
the filter where the addition occurred.

The added carbon did not  reduce the bubbling, although it
appeared to have repaired the channeling caused by the bub-
bles.  During the injection  process, the decision was made
by the field staff to obtain a  submersible electric pump to
replace the gasoline-powered pump.  The suction head on the
exposed part of the intake piping  for  the pump was thought
to be the source of the air  in  the filter system.  Also, sub-
stitution of the submersible pump  would increase the depend-
ability of the system, reduce manpower requirements, and
permit more versatility of  intake  location.  For the two
days it took to locate, purchase,  assemble, and transport
the pump to the site (June  21-June 23) , operation was con-
tinued with the old pump  at  the highest rate which did not
cause turbulent bubbling, 116 gpm.

The submersible pump was  mounted on a  floating  platform as
shown in Figure 17 so that  the depth of  the intake could be
adjusted.  Sections of fire  hose were  used to carry the lake
water from the pump to the  filter.  By anchoring the platform
at different locations in the lake, the pump could be moved
to points were the  Endrin concentrations were highest.

Before the submersible pump  reached the site, Endrin concen-
trations in the effluent  began  to  rise.  The system was shut
down and the necessary modifications for addition of the new
pump were made.  The gasoline-powered  pump was  kept in its
position as a standby in  case of power failure.

When the system was restarted with the submersible pump, the
initial effluent samples  showed very high Endrin concentra-
tions (0.9 ppb).  However,  after three to four  hours of
                           93

-------
Figure 17 - Floating support for electric submersible
            pump installed to eliminate air bubbles
            in the carbon filter.  Filter operated
            well at 180 GPM with this pump.
            (Courtesy Portsmouth Times)
                      94

-------
flushing   the  channels  formed by the bubbling were  repacked
by the upflow  of  water  and the effluent concentrations dropped
to an acceptable  level.

Endrin levels  in  the stilling basin and downstream  in Pond
Lick were  monitored closely by G-C analysis  as  shown in
Figure  and fish  bioassay to insure that the high levels did
not reach  the  stream.   A pump and hose were  available at the
stilling basin to repump water into the lake if high levels
were detected.  Because the capacity of the  stilling basin
was only about 20,000 gallons, or two hours  detention time
at 170 gpm,  there was a necessity for frequent  sampling of
the effluent.   Fish were placed in the water on top of the
filter to  provide rapid detection of a breakthrough.  They
were kept  on the  top by placing a screen across the overflow.

Additional protection against unexpected breakthrough was the
continued  operation of  the pilot plant.  With an approximate
three-day  lead time and operating at the same loading rate,
the pilot  plant carbon  could be expected to  reach its absorp-
tive capacity before the large filter and provide a warning.
However, as indicated earlier, the pilot plant  ceased opera-
tion after the carbon column was partially lost in  start-up
after  the  June 26 power failure.

Notes  on plant operation were prepared for the  assistance of
state personnel at the  time that the EPA and RETA field team
left the site.  The notes included sampling  schedules and
outlines of actions to  be taken in the event of possible
emergencies.  A copy of the notes is presented  at the end
of this section.

On June 21,  a morning rain of 0.6 inches and an evening rain
•of 1.03 inches caused a total lake rise of U to 4-1/2 inches,
but resulted in no operational problems.  The bypass pumps
were able  to control the water level above the  diversion dam
and no increase in turbidity of the lake water  was  observed.
The discharge of  the pumps is shown in Figure 18. However, on
the night  of June 25 and early morning of June  26,  a 2.15
inch downpour was recorded at the lake.  Working through the
night  to reinforce the  diversion dam and keep the water above
it pumped  down, the state DNR employees were finally forced
to cut a trench through it to prevent the entire dam from
being  lost.   The  lake level rose rapidly, causing a need for
additional sandbags around the spillway.  The final increase
in lake level from the  rain was 18 inches.

The rainstorm created additional difficulties.   For nine hours
Friday night and  four hours Saturday night,  there was loss
of electrical power at  the site.  This resulted in  lightning
problems and inactivated the submersible pump.   In  addition,
the work on the diversion dam and rapid runoff  into the lake
caused high turbidity,  especially at the upper  end  of the  lake

                             95

-------

Figure 18 - Spillway of dam and discharge of
            by-pass pipe during heavy rain.
                      96

-------
The turbidity was severe enough  to have caused shut-down of
the carbon filter, but the filter was  already out of operation
because of the power failure.

As the lake level continued  to rise  on the morning of June
26, and the possibility of the lake  water either topping or
breaking through the sandbags around the spillway appeared
imminent, an emergency treatment system that could be placed
somewhere down-stream from the lake  overflow was sought.
After consulting with Dr. Thompson by  telephone, the state
DNR personnel began construction of  an upflow filter in the
spillway chute by damming the chute, placing a surface baffle
upstream, and packing the section of the chute between the
dam and the baffle with 200  bags of  activated carbon.

Lake water was directed into the emergency filter by siphon-
ing from the lake into the spillway.   No meter or accurate
measurement of flow could be obtained, but the siphoning rate
was estimated at  200 gpm.

Before power was  restored, the effluent pipe from the large
carbon filter was redirected and extended to run over the dam
and discharge below the emergency filter in the chute.  The
turbidity  in the  lake  subsided considerably by the time power
was restored, especially near the surface.  Therefore, the
filter was re-started  soon thereafter.  High concentrations
of Endrin  in the  effluent were again measured at the start-up,
but were flushed  out within  the  same three-hours' period as
before.  Because  of the apparent efficient performance of the
emergency  filter  and  the need to lower the lake level rapidly,
both  systems have been  operative since that time, resulting
in a  combined treatment rate of  approximately 400 gpm.  _The
corresponding draw-down of lake  level  has been about 4 inches
per day.
                           97

-------
                 NOTES ON OPERATION
               OF CARBON FILTER PLANT
                 Pond Lick Reservoir
                    June 25,  1971
                    Prepared by:

                     Ken Axetell
                  Dave Stoltenberg
Section                 Contents

   1           Routine Monitoring,

   2           Start-up and Shut-down Procedures

   3           Plant Operating Procedures

   4           Emergency Procedures

   5           Instructions for Recharging Filter
                         98

-------
                         Routine Monitoring

     Routine  monitoring will be primarily by gas chromatographic
analysis  of samples  for endrin and by fish bioassay.   Monitoring
of  lake water and discharge is primarily fish bioassay and  gas
chromatographic analysis for endrin.   The specific  test for en-
drin requires about  1 1/2 hours analysis time.   Results of  fish
killed by the endrin are measured at  24 and 48 hours.   These two
analyses  are  the only means being used to determine whether the
lake water is being  treated adequately.

Filter Start-up Period - For the first 5 days of operation
(June  23  - June 21),  samples should be taken at frequent inter-
vals.  The recommended schedule is given below:

In  the lake -
     a)   one vertical profile every other day on the north side
         of the lake  near the dam.  Depths of O1, 3',  5', 7', and
         15'
     b)   surface grid of lake every day at the following locations:
         upper end of lake, center of lake, location of vertical
         profile, and intake to filter plant
     c)   if concentration at intake has been varying significantly
         (over 2 ppb), take a second intake sample during the day
     d)    when the lake level has receded about 1',  take sediment
         samples from the exposed bank to determine the need for
         washing the  shore line of deposited endrin

Effluents -
     a)   filter plant effluents at approximate 3-hour  interval:;
         around the clock
                                  99

-------
     b)  two pilot plant samples per day, preferably morning and



         evening






Stream samples -



     a)  daily samples at stilling basin, bioassay shed, and at



         bridge over Pond Lick



     b)  one sample per day at other fish bioassay locations






     Be certain not to contaminate samples by placing hands or



objects into the samples or their containers.





Normal Operation - After the filter system has reached equilibrium,



fewer samples will be required to monitor the unit.   Upset in either



the filter or the lake or stream may necessitate a return to the



more frequent sampling schedule.





In the lake -



     a)  vertical profile as described above every fifth day



     b)  surface grid of the lake as described above every other



         day



     c)  intake sample every day (this is included in surface grid



         every other day)






Effluents -



     a)  filter plant effluents at 6-hour intervals



     b)  one pilot plant sample per day





Stream samples -



     a)  one sample per day at every bioassay location



     b)  sample every other day at stilling basin, bioassay shed,





                                100

-------
         and bridge when there is no bioassay in progress at the

         site
                 Start-up and Shut-down Procedure^
To Filter
       A
                                                  By-pass
                                                (3)
                                    Check
                                    Valve
                                       (2)  Meter
                                     V
                                      A
jtandby
  Irilot

  Ma In
  Inlet
Start-up

     Gate valve (1) should be closed.

     Gate valve (3) should be open.

     Gate valve (4) should be closed.

     Gate valve (5) should be open.

1.  Throw pump disconnect switch to "on" position.

2.  Gradually open gate valve (1) to fully opened position.

3.  Throttle gate valve (3) to obtain desired flow (check on flow

    meter).

4.  Step #3  should be done over a 1.5-30 minute period.

5.  If possible, another person should be located on filter top to

    observe  possible velocity currents and/or bubbles.


Shut-down

1.  Open by-pass valve (3) to fully opened position.

2.  Close gate valve (1).

3.  Shut off pump at disconnect switch on telephone pole.

                               101

-------
                    Plant Operating Procedures






1.   Total flow readings should be taken periodically,  preferably



    at the times of effluent sampling.   The readings should be



    recorded in the table shown on the  next page,  and  the other



    values in the table filled in.   Any noteworthy events which



    occurred in the filter system should also be recorded in the



    "REMARKS" column.   One copy of these tables should be kept at



    the filter site and others sent to  the Division of Natural



    Resources Columbus office  and EPA  Evansville  office.



2.   If operation at high flow rates continues to give  effluent



    concentrations exceeding 0.4 ppb of endrin, more carbon should



    be injected into the filter by the  same procedure  used on



    June 22.  Additional injection points should be drilled at



    the middle and inlet end of the filter.



3.   Lake level should  be recorded at the same time each day on a



    separate data sheet to indicate lake drawdown  rate.



4.   The expected decrease in maximum flow rate caused  by addition



    of each 40 foot section of intake piping (fire hose) would be



    15 to 20 gpm.
                               102

-------
                                           FILTER OPERATION CHART
O
U)
Date

Time

Hours of
Operation

Large
Meter

Small
Meter

Flow,
Total

Gallons
Since Last
Reading

Flow
Rate,
gpm

Effluent
Endrin,
ppb

Remarks


-------
                      Emergency Contingencies
       Emergency
    Corresponding Action
1.   turbidity increase
    in lake
2.  power loss
3.   filter effluent
    exceeds 0.20 ppb
    endrin
a.  shut down filter plant

b. if only moderate, keep pilot plant
   in operation to determine fouling
   effects

c. if excessive, shut down pilot
   plant

d. operator contact Dave Stoltenberg
   (EPA) or Jim Ryckman (RETA)
   Dave Stoltenberg - (812)  423-6871,
   X 264
   Jim Ryckman - (513)  293-4353
a. as a precautionary measure, at-
   tempt to seal the 2 exposed
   couplings on the suction side of
   the army surplus pump

b. turn off switch to submersible
   pump

c. open by-pass valve

d. start gas-powered pump and regu-
   late flow by shutting down by-pass

e. do not operate at a flow rate in
   excess of 180 gpm or at which
   bubbling occurs

f. shut off gate valve on pilot plant
   inlet and remove electrical plug
a. laboratory immediately notifies
   State operator
                              b.  operator checks  filter top for
                                 channeling or other malfunction
                                 and checks flow  rate;  check for
                                 dead fish on filter top

                              c.  consider slowing flow  rate until
                                 another effluent sample can be
                                 analyzed

                               104

-------
    filter effluent
    exceeds 0.20 ppb
    endrin (continued)
    filter effluent
    exceeds 0.40 ppb
    endrin
    inlet pipe failure
6.   heavy rainfall
d. step up sampling schedule to once
   every three hours with priority
   given to analyses


a. divert effluent back into lake by
   moving pipe from spillway to lake

b. continue monitoring effluent at
   3-hour intervals

c. if experimentation with flow rate
   reduction, sampling at inlet for
   high endrin levels, and injection
   of carbon slurry all fail to re-
   duce the effluent level, the EPA
   personnel listed under Id should
   be contacted

d. preparation should be made for
   recharging the filter per the
   attached instructions

e. if effluent has exceeded 0.40 ppb
   for more than 6 hours before pipe
   is diverted, downstream samples
   should be taken.  If these also
   exceed 0.4 ppb, water should be
   released from Roosevelt Reservoir
   at the rate of 5 MGD for 8 hours
a. shut off pump

b. if failure is in PVC pipe section,
   attempt to keep split section in-
   tact and drain filter through 1"
   line.  Replace PVC inlet piping
   with the entire replacement sec-
   tion available on site.

c. if leakage or failure in in metal
   pipe, isolate with gate valver.,
   remove and replace
a. check to see that lake by-pass
   pumps are manned and that the
   pumps can keep the water level in
   the dammed-up area below dam top


  105

-------
       Emergency
Emergency Contingencies      (continued)

  	Corresponding Action	
6.  heavy rainfall
       (continued)
        b. record rise in lake level on data
           sheet

        c. record rainfall gauge reading on
           data sheet

        d. if rainfall continues for long
           period (more than a day), consider
           possibility of using runoff flow
           in Pond Lick for diluting some
           untreated lake water which could
           be released into spillway	
                      Important Phone Numbers
EPA
    Hugh Thompson


    Dave Stoltenberg


     ^aron Rosen
       (bioassays)
    Office   (703)  557-7663
    Home     (703)  560-6491

    Office   (812)  423-6871, Ext.  264
    Home     (812)  477-3239

    Office   (513)  684-4375
OHIO
    Tom Stewart
    Home
(614)   882-3706
RETA
    Jim Ryckman

    St. Louis Office
       (Cecil Lu-Hing,
        Joe Dieterman)

    Ken Axetell
    Number at lab
Office
Home
(513)
(513)
(314)
229-3847
293-4353
862-3424
    Office
    Home
(703)
(703)
893-8410
560-0218
             (614)  858-5950
                               106

-------
                 Instructions for Recharging Filter

 1.  Follow  standard shut-down procedure.
 2.  Drain filter through 1" line.
 3.  While filter is draining, remove filter top by removing  lateral
    braces,  prying 2x4 strips away from side walls,  and  sliding
    screen  and its support member out the overflow-end of  filter.
 4.  Contact Calgon representative (Al Gaber,  Calgon Center,  P. 0.
    Box 1346,  Pittsburgh, Pa.  15230, (412)  923-2345) concerning
    trucking arrangements for return of carbon.
 5.  Line dump truck bed and walls with muslin and pull truck to
    side of filter.
 6.  Shovel  the moist carbon into the truck bed,  taking care  that
    the workers minimize contact with the carbon.   All should be
    protected with waterproof boots, long-sleeved shirts,  and glover,
 7.  Do not  disturb gravel underflow system and keep workers  off
    the top of PVC pipe inlet manifolds.
 8.  Refill  the tank with lake water.
 9.  Add carbon by the same method used for originally  filling the
    tank.
10.  Draw water level down to height of screen frame bottom and
     level the carbon bed using the water surface as a  guide.
11.  Replace filter top and use standard start-up procedure-
                                 107

-------
                     APPENDIX F

                     FIELD DATA
 There are 7 sections of data presented in this Appendix.
This data was collected by Federal, State and RETA personnel
and transmitted to St. Louis for incorporation in this re-
port.  This is all the data received by RETA.

Section 1 contains a map sketch of Pond Lick Lake with sampling
locations in the lake shown.  The symbols shown there match
fish bioassay, temperature profile and gas chromatography
analysis tables throughout this Appendix.

Section 2 is gas chromatography data run at Taft Center,
Section 3 contains results of early fish bioassay tests to
determine the extent of kill.  These data depict a gradual
decrease of Endrin concentration with increasing depth.
When compared with the temperature data in Section 4, the
figures show that the temperature gradient was at least part-
ly responsible.  Section 5 shows a biological survey of the
watercourse conducted by EPA.

Section 6 shows pilot plant data and notes which were used to
design the prototype plant.

Section 7 contains notes on operation of the prototype as
well as the effluent concentrations of the filter.  These
analyses were the quality control on the filter and were used
to determine if discharge of the effluent was possible or if
it needed to be recycled to the lake until the filter operation
improved.
                          108

-------
      SECTION 1




SAMPLE LOCATION MAP
           109

-------
Figure /*?
 Lick

-------
         SECTION  2
 GAS CHROMATOGRAPH ANALYSIS

Taft Center, Cincinnati, Ohio

Date  6/15/71	
No.
	




















Sample Location
RIGHT DAM
Surface
5'
10'
14'
MID DAM
Surface
5'
10'
15'
LEFT DAM
Surface
5'
10'
15'
POWER LINE
Surface
5'
RIGHT CENTER
Surface
5'
10'
LEFT CENTER
Surface
5'
10'
	 	 	 • 	 	
Cone . ppb
•>>BIWlH«*W_«—»^_^M—M-M»a>IIM^^»-WH«>

6.8
6.9
2.1
0.1

7.0
6.5
0.7
0.3

6.7
6.5
0.8
0.1

6.3
7.0
7.4
7.0
0.5
7.5
7.1
0.3
1_- 	
Remarks
••••••••^^••••••-•••••••••i. .— . 	 ••Hi- 	 " --"•-.. . —i

After pumping stillinq
well into right dnm

















J 	 	
              111

-------
                OTHER ENDRIN SAMPLES
DATE
TIME
SAMPLE #
LOCATION   DEPTH
5-10
6-18
6-16
6-19
19
18

19
19

20
19
21




21
22




22
23




23
„
__
__
_ _
__

__
_ _
H .
_ _
_ _
— _




__
1800
1800
1800
1800
1800
1800
1730
1730
1730
1730
1730
1730
C22
B23
B24
B25
28

3k
B36
B37
B46
C47
B67
B68
B69
B70
B71
C72
B84
B85
B86
B87
B88
C89
B102
B103
B104
BIOS
B107
C108
	 . - *
9.6
3.565
__
4.050
_ _
0.375

3.665
0.667
9.083
7.200
5.950
7.050
9.050
6.900
0.750
8.200
7.400
6.200
6.100
0.500
6.100
6.150
7.100
7.300
7.200
7.300
4./+00
0.600
7.300
rjr — 	
30' below spillway
H/3
LS
LS
LS
bottom near center
of dam
Intake
LS
LS
LS
H/3
LS
LS
LS
LS
LS
H/3
LS
LS
LS
LS
LS
H/3
LS




H/3
5'
15'
5'
15'


5'
7'
3'
5'
5'
3'
5'
7'
15'
0'
1'
0'
3'
15'
7'
5'
0'
0'
3'
5'
7'
15'
0'
                        112

-------
            ENDRIN CONCENTRATION AT INTAKE
DATE
TIME
SAMPLE #
[ENDRIN]
  PPB
6-17

6-18

6-19

6-20
6-21
6-22

6-23
0030
0300
  7
  ?
1605
1615
1030
1630
0800
1130
  Al

   16
  A19
   31
   27
   40
   77
   76
   82
   92
   98
 8.795

 3.100
 3.450
 3.800
10.750
 5.333
 7.800
 7.650
 6.150
 6.850
 6.900
Initial lake sample
run at lab
In surge tank
                           113

-------
                SECTION 3
           FISH BIOASSAY ANALYSIS

           First set of samples
           Time Test Set Up     16;30
L = lethal   D = distress   A = active
  Date  6/13/71

C = calm
No-
LS





H/3






Sample Location
Spillway off
drainpipe
3:1 dilution
5'
10'
15'
H/3 @ power line
center
Surface
5'
Center - 25'
below earth dam,
turbid
0-4
Hours

3C

2L,1D
3C
3C







4-8
Hours

3C

3L

3C


3L
3L


3L
8-12
Hours




1L,2A








12 - 24
Hours

1L,2D



3C







Remarks

3L 30+ hrs.


ZL 24+ hrs
3C 96+ hrs.







                          114

-------
PISH BIOASSAY ANALYSIS
                                Date  6/13/71
           Time Test Set Up   22:30	



L = lethal   D = distress   A = active   C = calm
NO.
LS







H/3





Sample Location
Spillway off
drainpipe
Surface 2:1
dilution
Surface undilut-
ed
51
10'
15'
Center line
Surface
5'
Inflow above
earth dam
Dilution water
upstream 200'
from earth dam
Spillway etfluen
after carbon
0-4
Hours




3D
ID



3L

ID


4-8
Hours




3L
2L





3L


8-12
Hours


3L


3L




3L

1L
1L
12 - 24
Hours






1D,2L
3C




2C
3L
Remarks














                115

-------
           FISH BIOASSAY ANALYSIS
           Time Test Set Up   10:30
Date 6/14/71
L = lethal   D = distress   A = active   C = calm
No.















Sample Location
Below stillwell
approx, 200'

Below stillwell
approx. .8 mile
downstream
(ballfield)
. 6 mile logging
road
Note : Fry in
good cond. at
1 mile
Turkey Creek
Seepage 200 to
300' below dam
0-4
Hours

1L













4-8
Hours















8-12
Hours

2L,1D




3C

1C,2L



2D,1L

3C
12 - 24
Hours

3L












3C
Remarks
Minnows in
bait bucket
were dying
readily, sug-
gesting a
poor lot of
fish

3L @ 48 hrs.






                          116

-------
           FISH BIOASSAY ANALYSIS
           Time Test Set Up  18;25
Date  6/14/71
L = lethal   D = distress   A = active   C = calm
NO.
LS



LCS



RCS


RS



LC


CC

RC
	 i
Sample Location
Surface
5'
10'
15'
Surface
51
10'
15'
Surface
5'
10'
15'
Surface
5'
10'
15'
Surface
51
10'
Surface
5'
10'
Surface
5f
10'
.
0 - 4
Hours
3L
3L
2D
1D,2L
1D,2L
3D
3C
3C
1D,1L
1D,2L
3C
3C
2D.1L
3L
2C,1L
3C
2D,1L
2D,1L
3C
2D,1L
c
1D,2L

2L
._....
4-8
Hours





















,
8-12
Hours




















3L
3L
	
12 - 24
Hours


3L
1D,2L
3L
3L
2C,1L
3L
3L
3L
1A,3L
3L
3L

2C,1L
3C
3L
3lj
2C,1L
3L
3L
1D,2L

2C.1L
1 " •••
Remarks



3L @ 38 hrs.


3L @ 38 hrs.

Stillbox
pumped to RS
aefore sampl*
taken



3L @ 38 hrs.



3L @ 38 hrs.



•• '— i— - i H - 	 • 	 — 	 •
                           117

-------
           FISH BIOASSAY ANALYSIS
           Time Test Set Up    18 :25	 Date  6/14/71




L = lethal   D = distress   A = active   C = calm
No.
H/3

LH

RH












Sample Location
Surface
5'
Surface
5'
Surface
5'
25' from crest
after stillwell
was pumped
Drainage through
carbon
Sample from
above earth
diversion dam
5 minnows left
in bucket, sur-
vived 18 hours
0-4
Hours
2D,1L
2D,1L
3L
1D,2L-
3L
2D,1L
3L










4-8
Hours

















8-12
Hours









14 hours
2D,1L






12 - 24
Hours
3L
3L

3L

1C,2L



16 hours
3L


3L



Remarks





3L @ 20 hrs.











                          118

-------
L = lethal
FISH BIOASSAY ANALYSIS



                    11:00
               - 4T T. B


  D = distress   A = active
           Reruns
           Time Test Set Up
  Date 6/16/71


C = calm
NO.






Sample Location
Dilution water
of 6/13/71
Above diversion
dam 6/13/71
LH 5' - 6/14/71
Dam seepage at
crest
0-4
Hours

3C

3C
3L

4-8
Hours






8-12
Hours






12 - 24
Hours

3C

3C

3C
Remarks

3L @ 69 hrs.

2L @ 69 hrs.

3C @ 69 hrs.
                            119

-------
                        SECTION 4
                     TEMPERATURE PROFILE
                       POND LICK LAKE
                       Date 6/16/71
            Total Depth             Temperature  C
Station     at Station      Surface     5'     10'     15
  LS            15'
  LCS           17'
  RCS           16'
  RS            15'
  LC            11'
  CC            11'
  RC            10'
  H/3            8'
  LH             5'
  RH             6'
  Note:  Temperatures determined with thermistor probe
27.
27.
27.
28.
27.
27.
26.
27.
27.
27.
5
5
5
0
0
0
5
0
0
0
25
25
25
25
24
25
25
24
25
25
.0
.0
-0
.5
.5
.0
.5
.5
.0
.5
16
16
16
17
16
18
15



.5
.0
.5
.0
.0
.0
.5



10
11
11
10






.5
.0
.0
.5






                            120

-------
     SECTION 5




BIOLOGICAL SURVEY
            121

-------
 •i-n
               BIOLOGICAL 8UHVET
                              . Bo.
               Hour6,79   Biologist
:r«aa Location t
            Qjt
                              tfk of fond L
                 >o
         County
 tncral Station Description:

      Width:  Ave.  /<""     Depth:  Ava.

              ****•   20'
      Color:
      letimated Current  (fpa):   /yj"/

      Bottoa: (%)  Rock   $" r   C. Soul
                 Rubblo
                              F. Sat4
                  C. Grevoiyo  Silt

                  ?. Gravel *e
        Data:
                              Good.
               PH
                              D. 0.
               Other
 lologioal ColLectloot:
 uspler
          Qual.
         L  M
  Eck.
L  M  R
  Pet.
L  M  R
 Surbor
L  11  R
                                           M  R
 3. Of
 unplea
                                 I     I
 spth
                                f
                                   "
 Be .Remarks on back  of card
Unproductive  area.   Frog,  crayfish,  water-
penny,  minnows and  fingerlings observed.
         122

-------
                BIOLOGICAL SURVEY
             L / c fc /?
                    ,,
                            sta<
               Hour
                            Blologlot
Stresa Location:

       Stata
                           County
                 '
                         0

          . y/-n30Loa/0
 Oeneral Station Description:
       Width:  ATS.   /£	Dapth:  Ave. 3^
               Kax.  ~~7
       Color:
       Eatieated Current (fpa):   
-------
OOBO-20
               BIOLOGICAL SURVHf
Stream
T^Y
             A
                            Sta.  No.
     L//(/.7l— Hour/47 TO  Biologist

Stream Location:   2

Bottom:
           Rock
                               C. Sand
                  Rubble JO    F. Sabd^

                  C. Gravelj£__Sllt	

                  F.
         Data:
                         Cond.
                               D. 0.
               Other
 biological Collections
 Jampler
     Qual.
    L M  R
             Eck.
           L  M  R
                           Pet.
                          L  M  R
                                            M  R
 fo. of
 templeo
 icpth
 lee Remarks  on bock of card

Unproductive  area.   Frog,  crayfish,  water-
penny, minnows and  fingerlings'observed.
                 124

-------
               BIOLOGICAL SUETS?
Stress
                        n   Sta. I*'o.
                            Biolojjlst
Stresa Location:
       State
                           Coun'ov
              / w'^»
Q«jscral Station Etescr
       Width i  Are.   ?
                             Copth:  Avo.
                                    Mas."
       Color:
       Estiiaat«d Current (fps):  L
       Bottoa:  () Rock -TO    C.
                  Bubble /o
                              p. S£c
                  C. Gravel IO Silt
                  F.
Dhenlcal Datai Tesp, Corid.
PH
D. 0.
Other


Jloloslcal Collectioaos
Jaapler
lo. of
isnplea
>epth
Qual.
L H R


Eck.
L H R


S^Hfe%L M R
y ;•
J" 3"
    Rcaaraa  oa  oacs of cara
Shale in substrate.   Caddis  fly, waterpenny,
elmidae, isopid, mayfly, crayfish.
                125

-------
                BIOLOGICAL SURVE3T
Btresa
               /
Sta. No.

Btologigt
Date  W/A/7)   Hour/ 7.'
Stream Location:   /?'i?//'f/eAJ  •*"*!

       Stcto   ^yV;j        County
 General  Station Description:
       Width:  Ave.   tf	I>spth:  AVQ.
               Kax.    I              Max."
       Color:
                 Current (fps):    ^'7

       Bottoa: ($  Rock /P      C.  Sand  /°
                   Rubble iT   P.  Sand
                   C. GravelJfjSilt_

                   T. GravQi_2f"'Clay
 Chemical Data:  Teop.
    Cond.
                                D. 0.
                Other
Biological Collectiona :
Soapier
Ho. of
Samples
Dopth
Qual.
L 21 B


Eck.
L II R


Pet.
L M R


Surber
L II it-
1
^
C M R


 See Rcaar&o on baca of cara

Shale  dominant, poor substrate)  no organisms,
                 126

-------
  o-n
                BIOLOGICAL
        73.
       f 0*J LfCK
                             Sta.  Ho.
                             Blolc^ict
 ;rcsm
                                    ?nouf A
        State
                           County
        Color:
                Current (fps):    
 Xjpth
3ce
             on  cacx 01' card
Salamander,  mayfly, waterpenny,  minnows
observed.
              127

-------
     SECTION 6




PILOT PLANT DATA
          128

-------
            POND LICK LAKE PILOT  PLANT

         Activated Carbon Sorption of Endrin
Carbon Volume:   10.25 Cu.Ft.
Raw Endrin:   8.7 & 9.5 (Local)
Date:
Time:
  6-16-71
  11:30 pro
                               6.6ppb (Taft)
DATE
6/16/71
6/17/71









5/17/71
6/18/71


•••••••^1 fc 1 U , •!!
TIME
11:30 P
12:30 A









10:30 A
3:30 P
5:50 P
7:50 P
10:00 P
-. . —
RUNNING
HOURS
0
1
2
3
4
5
6
7
8
9
10
11
40
42
44
46.5
	 - - 	 —
FLOW
METER
GALLONS
33290
33312
33332
33377
33421
33428
33468
33501
33546
33590
33632
33674
34665
34782
34889
35002
- — "—
FLOW
LAST
HOUR
GALLONS
120
220
200
450
440
70
400
330
450
440
420
420
9910
1170
1070
1130
• 	 --— ~~
FLOW
GPM
Fill
3.7
3.3:
7.5
7.3
1.1
6.7
5.5
7.5
7.5
7.0
7.0
5.7
8.3!
8.9
7.5
fmu 	 "•
ENDRIN
ppb
TAFT
Up Op














-
LOCAL
sratior
0
0
0
0
0
0
0
0



0.050

0.050
•I. • 	 '

s

1

2
3







4


 1
 2
 3
 4
Increase flow to 7.5 gpm
Carbon loss
Repair Filter
sss s£Jss n
repaired;  rate reduced to 7.5  gpm
                         129

-------
             POND LICK LAKE PILOT PLANT

         Activated Carbon Sorption of Endrin

Carbon Volume:  10.25 CtuFt.
Raw Endrin:  8.5
Date:  6-19
Time:
DATE
6/19/71




6/20/71



6/21/71




6/22/71

TIME
3:05 A
8:00 A
12:00 A
3:25 P
7:30 P
1:00 A
4:00
7:30 P
9:30 A
10:30 A
2:00 P
4:30 P
7:30 P
8:00 P
8:30 A
9:10 A
RUNNING
HOURS
51.5
56.5
59
62.5
66.5
72

90.5

106.5
109
111.5
111.5
112
124.5
125
FLOW
METER
GALLONS
35162
35375
35478
35613
35775
35993

36728

37361
37459
37558
37558
37580
37981
3S014
FLOW
LAST
HOUR
GALLONS
1600
2130
1030
1350
1620
2180

7350

6330
980
990

220
4010
330
FLOW
GPM
5.3
7.3
6.9
6.6
6.8
6.6

6.7

6.6
6.5
6.6

7.3
5.4
3.2
ENDRIN
ppb
TAFT
















LOCAL
0.050
0.050

0


0

0






0.2
                                                           1
                                                           1,2
  1.  Small carbon loss  in effluent  catch.

1,2.  At 10:00 am shut down plant  to fix gasket;  restarted
      at 11:30 am.   Diverted pilot Clow to  spillway side of
      dam.

  3.  No problems experienced with operation,  system is in
      equilibrium.

  4.  Shut  down to  remove sand filter from  system;  start up
      at 7.5 gpm.

  5.  Flow  rate adjusted to 7.5 gpm--valve  had been changed
      during night.
                         130

-------
             POND LICK LAKE PILOT PLANT

         Activated Carbon Sorption of Endrin
Carbon Volume:
Time:
10.25 Cu0Ft.

      °n 6/22/71> raw
                                             increased  to  7.6ppb
DATE
5/22/71


6/23/71







6/24/71

6/25/71

TIME
11:00 A
1:30 P
4:30 P
8:00 A
8:30 A
11:00 A
11:30 A
1:30 P
7:00 P
8:00 P
10:00 P
3:00 A
2:00 P
10:00 A
11:00 A
RUNNING
HOURS
127
129.5
132.5
148
148.5
151

153.5
159
159

171
177
197
198
FLOW
METER
GALLONS
38102
38222
38370
38882
38897
38995
39012
39093
39308
39308
39358
39654
39896
40728
40770
FLOW
LAST
HOUR
GALLONS
880
1200
1480
5120
150
980

980
2150
0

3460
2420
8320
420
FLOW
GPM
8.0
8.0
8.2
5.5
5.0
6.5

6.5
6.5


4.8
6.7
6.9
7.0
ENDRIN
ppb
TAFT















LOCAL


0
0


0.100



0
0





1

2



3


4



 1.  Reduced flow to 6 gpm.
 2.  Increased flow to 7 gpm.
 3.  Power plant down for I hour at 7:00 pm to wire,  in the
     electric motor.  Restarted at 5.0 gpm.

 4.  Increased to 7.0 gpm at 8:00 am.

                          131

-------
          ACTIVATED CARBON LOADING RATES
PILOT PLANT                     20" dia. x 7'0"
                             15.25 ft3   2.18 ft2
Flow rate, gpm     Volumetric loading     Surface loading
                     gpm/ft3                gpm/ft2
       8*                 0.52                3.7
       7                  0.46                3.2
       6                  0.39                2.8
       5                  0.33                2.3

*  Lift out of carbon occurred at this flow rate.
    (Design value  0.5gpm/ft3 = 7.5gpm)
PROTOTYPE PLANT                  18'  x 4' x 5'2" = 373 ft3
                                                    72 ft2
Flow rate, gpm     Volumetric loading     Surface loading
                     gpm/ft3                gpm/ft2
     220                  0.59                3.1
     210                  0.56                2.9
     200                  0.54                2.8
     190                  0.51                2.6   ,  .      ,
                                            y	design value
     180                  0.48                2.5
     170                  0.46                2.4
     160                  0.43                2.2
     150                  0.40                2.1
     140                  0.38                1.9
     130                  0.35                1.8
     120                  0.32                1.7
     110                  0.30                1.5
     100                  0.27                1.4
                          132

-------
       SECTION 7




PROTOTYPE PLANT DATA
              133

-------
                                  CARBON FILTER PLANT
Gallons
Hours of Large Small Since Last
Date Time Operation Meter Meter Total Reading
6-19 1400
1430
1710 0
1830
1930 2 1/2
2000 3
w 2030 3 1/2
2045 3 3/4
2100 4
2130 4 1/2
2300 6
6-20 0130 8 1/2
0405
000
7700
7700
8300 ?
14750
16200
18800
21000
21000
25300
33800
47500

0
7700
0

7050
1450
2600
2200
0
4300
8500
13700

Flow Effluent
Rate, Endrin,
GPM ppb Remarks

Fill tank and wash
gravel; load with
carbon
0.00 Start of operations
(5:30 p
sample )
0 Sample 32
47 0
48 Full flow operation
87 0 Sample 35
147 Shut down to reprime
pump
Restart
144
95
92 0 Sample 38
0
0630
13 1/2
74800
27300
91
Rate increase*! to
210 gpm.  Filter top
failed, operation ceased
shortly thereafter

-------
        - 2 -




CARBON FILTER PLANT
Date Time
6-20 1315
1330
1600
1700
1910
2200
6-21 0000
(-•
£ 0400
0800
1030
1300
1600
2000
2330
6-22 0200
0500
Hours of Large Small
Operation Meter Meter

15
17 1/2
18 1/2
20 1/2
23 1/2
25 1/2
29 1/2 211300 14300
33 1/2
36 248500 16800
38 1/2
41 1/2
45 1/2
49 353:33 22650
51 1/2
54 1/2
Gallons Flow Effluent
Since Last Rate, Endrin,
Total Reading GPM ppb Remarks
74800
75400
93600
106200
129400
165000
197000
225600
252100
265300
282490
303400
332000
355650
373040
393980
0
600
18200
12600
23200
35600
32000
28600
26500
13200
17200
20900
28600
23650
17400
20900
40 gpm, restart
operation
40
202 0 Sample 48
210 0.150 210 gpm 50
194 0.160 52
198 0.063 54
266 ? Questionable flow read-
ing; sample 56
119 0.055 57-cut down flow be-
cause of high endrin/
bubbles
111 0.050 Sample 58
88 0.084 62
115 0.100 65
116
119 73
113
116
116

-------
        - 3 -
CARBON FILTER PLANT
Date Time
6-22 0800
0905
1100
1330
6-23 2015
2045
w 2200
6-24 0000
0120
0235

0300
0600
0845
0900
1150
Hours of Large Small
Operation Meter Meter
57 1/2
58 1/2
60 1/2
63
63
63 1/2
64 1/2
66 1/2
68
69

69 1/2
72 1/2
75 1/2
75 1/2
73 1/2 576390 38000
Total
415430
423000
437000
454700
458160

474500
494070
508900
520920

526110
555400
9
585480
614400
Gallons
Since Last
Reading
21600
7600
14000
17700
-

16300
19600
14800
12000

5200
29300

30100
28900
Flow
Rate,
GPM
120
117
122
118


155
164*
185*
160*

208*
163*

167
170
Effluent
Endrin,
ppb



0.65

0.914
0.925
0.102
0.055
0.105
0.140


0.030


Remarks
Sample 74

Sample 78
Shut-down because of
high endrin concent.
Restart with electric
motor % 50,75 gpm
Reach full flow of
169 gpm; sample 106
Sample 111



@ front end of tank
top





                           Av. =  168 gpm  which is pump cpy.

-------
CARBON FILTER PLANT
(continued)
Date Time
6-24 1300
1330
1440
1445
2030
2245
6-25 0030
w 0200
0500
0800
1015
Hours of Large Small
Operation Meter Meter
79 1/2 586400 38800
79 1/2
80
81
•*- 20 min. shut-down
86 1/2
89
90 1/2
92 705800 45650
95 735500 47350
98 763800 48980
100
Gallons Plow Effluent
Since Last Rate, Endrin,
Total Reading GPM ppb Remarks
625200
626300
631800
640100
697900
719080
736740
751450
782850
812780
836590
10800
-
5500
8300
57800
21200
17700
14700
31400
29900
23800
155

183
185
178 0.203
157 0.350
169 0.283
163
174
166 0.060
177 0.093
Stop pump to remove
section of fire hose
Restart @ 185 gpm


Reduced pump rate
because of high endrin



Increased flow rate to
180 gpm at 8 a.m.

-------
                   APPENDIX G

                  NEWS RELEASES
Included as follows is a chronological selection of news
releases pertaining to the hazardous spill emergency at
Pond Lick Lake,,  These articles appeared in newspapers
within the State of Ohio and in newspapers throughout the
country, including the New York Times.
                        138

-------
                PORTSMOUTH,  OHIO, THURSDAY, JUNE 24, 1971

  NEW PUMP.  A new pump, capable of moving more  of  the  poisoned water from Shawnee
Lake through the filtered charcoal bin, is in opsration today.  The pump, assembled in Salem
and flown here by the Ohio Department of Natural Resources,  is shown (foreground) mounted
on steel barrels.  The pump itself, capable of pushing 169 gallons of water a minute through the
filler (background) is beneath the surface  of the lake.  The new pump was installed by Rvck-
man Edgerley Tomlinson & Associates of  St. LDUIS, under  the direction of Tom Stewart of the
Ohio Department of Natural Resources. Gary D. Hiles, 24, of 411 Sinton St., has been charged
with putting poison in the lake.  (Times photo by Billy  Graham.)
                      139

-------
 Bypass    Built   At   Poisoned   Lake
  PORTSMOUTH, Ohio (Special) —
Ohio Department  of Natural Re-
sources workmen  were construct-
ing  a  dam and bypass Sunday to
reroute fresh  water  around the
pesticide-poisoned Pond Lick Res-
ervoir  in  nearby  Shawnee State
Park.
  Everett Ridge, wildlife supervi-
sor  for the  District Four Depart-
ment of Natural Resources, said at
5 p. m.  Sunday that the dam was
partially built, but would not be
completed before sunset Sunday as
Department  of Natural Resources
officials had hoped.
  Ridge  said  that  about 7200
pounds  of activated carbon have
been dumped into the lake in an
attempt to absorb the-pesticides, a
mixture of Endrin and strychnine.
  Robert  Redett, chief of forestry
and  reclamation for  the Depart-
       From the  CINCINNATI  ENQUIRER, June  14,  1971
            PORTSMOUTH, OHIO, TUESDAY, JUNE 8, 1971
                           Water Samples

                           Studied As Fish

                           Die In State Lake
                            More than 4,000 fish have died
                           in Shawnee Lake during the last
                           few days and state officials are
                           trying to determine the cause.
                            Larry Rine, state game pro-
                           tector, said water samples are
                           being .sent to Columbus. He said
                           several fish were seen floating
                           on the surface of the water last
                           Thursday. More and more fish
                           surfaced and now officials fear
                           all species in the lake may be
                           dead.
                            Rine said a strong smell from
                           ;he dead fish is keeping people
                           away from the lake.
ment  of  Natural  Resources  said
workmen  were  installing  several
large pumps to pump fresh incom-
ing water around the reservoir. Re-
dett  said workmen also were in-
stalling 2400  feet of 20-inch pipe
through which the incoming water
will be pumped.

   Redett  said very little water was
coming into the reservoir. He said
most  of the  incoming water was
seepage.

   BUT JOHN BARRETT, assistant
chief engineer for the Natural Re-
sources Department, said state
workers had begun building a huge
filter in the spillway of the lake in
case a heavy rain raises the water
level.

   Nelson Thomas, a biologist for
the federal Environmental Protec-
tion Agency,  said it is too early to
determine if  the carbon treatment
will be a complete success in puri-
fying the water, but said he was
optimistic it would.

   Gary  D.  Hiles, 24,  of  Forts-
mouth, is being held in the Scioto
County  jail  on five  charges  in
connection with poisoning the lake.

   He is  accused of dumping a gal-
lon of corn soaked with strychnine
and a hall gallon of Endrin  into
the lake. No motive has been giv-
en.

   The  poison  killed  all acquatic
wildlife   in  the lake, including
about 3400 fish and a large number
of frogs, crawfish and snakes.

-------
PORTSMOUTH, OHIO, THURSDAY, JUNE 10, 1971
              City Man Is


              Charged  In

              Poison Case

                A 24-year-old Portsmouth man
              is in the Scioto County jail in
              lieu of  bonds totaling $3,300 on
              charges of poisoning  fish  in
              S'hawnee Lake.
                The man, Gary D. Hiles,  24,
              of 411 Sinton St., pleaded inno-
              cent today in Municipal Court to
              killing fish in Shawnee Lake by
              posioning. Bond was set at $100.
                He entered no plea to a charge
              of destruction of property and
              bond was set at $1,000.
                He also entered no plea to a I
              charge of putting poison in a
              reservoir and bond was set at
              $2,000.
                He pleaded  innocent  to two
              charges cf prohibition against
              placing deleterious substances in
              the waters of the state. No date
              has been  set  for  hearing and
              bond was set at $100 on each
              count. He is to return to court
              June 17 on the other charges.
                Hiles was arrested at 9:10 p.m.
              Wednesday by  Sheriff John P.
              Knauff and Ohio  Division of
              Wildlife officers  after  an  in-
              tensive investigation  into  the
              poisoning of thousands  of fish
              in the lake.
                Between 3,000 and 5,000 fish
              have died in the lake during the
              last few days and state officials
              are attempting to determing the
              cause.
                Hiles is  accused  of  putting
              poison  in  the lake on June 2.
              Water   samples   are   being
              checked by the State Depart-
              ment of Health.
                Officials have asked the pub-
              lic not  to use the lake until any
              possible danger can  be deter-
              mined. The lake  is  near  the
              former Shawnee Honor Camp.
  PORTSMOUTH,  OHIO
  THURSDAY,  JUNE  17,
  1971
 Hiles Denies Guilt!

 On Two Charges;

 Hearing Slated
  Gary D. Hiles, 24, of 411 Sinton
 St., entered innocent pleas this
 morning in Municipal Court to
 two felony charges in connection
 with the poisoning of Shawnee
 Lake June 2.
  He  entered the  pleas  o n
 charges of destruction of prop-
 erty  by destroying about 3,400
 fish  and  putting poison  in  a
 reservoir. Hiles remains in the
 county jail in lieu of $2,000 bond
 on the poison charge and $1,000
 on the destruction of  property
 charge. A  preliminary  hearing
 is set June 30.
  Hiles entered innocent pleas
 last week to three misdemeanor
 charges and went to jail in lieu
 of $100 bond on each count. One
 charge was  poisoning  fish in
 the lake, and two  other charges
were placing deleterious sub-
stances in the  waters of  the
state.
                                                      141

-------
    From  the  PORTSMOUTH TIMES,  Friday, June 11,  1971
NJ
          Teams    Continue   Sampling
                      Trace   Poison   Spread
     By PAUL NELSON
     Times Staff Writer
  Federal  Environmental  Pro-
 tection  Agency  officials  from
 Cincinnati took  samples  from
SUawnee Lake today in an effort
 to determine the concentration
of poison that has killed  thou-
 sands of fish in and  near the
lake.
  Working in the lake area and
downstream in portions of Tur-
key Creek were Loys Parrish, a
biologist; Darrell DeRuiter, san-
i t a r y  engineer, and Richard I
Johnston, aquatic sampler.
 Parrish said the team had been
instructed  by their  office  in
Cincinnati to determine what
has poisoned flic lake and how
much of the poison was used.
He said a high concentration of
the suspected poison, Endrin,
which is a pesticide, could af-
fect the Ohio River if a flash
flood or heavy rains drench the
area.
  'Our  concern is the  Ohio
River  and  that's  why  we're
here,"  Parrish  said. He said
Endrin will dilute in water but
it could take a long time. He
added  that the problem could
be more serious if a gallon of
the substance actually was put
in the lake.
  Everett Ridge, district super-
visor of Ohio Department of Na-
tural  Resources Division  of
Wildlife said he has contacted
medical experts  in Columbus
and Cincinnati and  they have
estimated  that  a large con-
centration of Endrin could take
as long as  10 years to disperse.
  Without rain, the  substance
could remain  in the lake  for
some time, Parrish said. A
stench surrounds the area and
little  aquatic  life  is visible.
Warning signs have been posted
around the lake but no guards
were noticed when Times  news-
men visited the area this morn-
ing.  Children  were observed
playing on the  banks of Turkey
Creek further downstream.
  Sheriff John  Knauff had dep-
uties and special deputies knock-
ing  on doors  of nouses  along
        Turkey Creek  Thursday  night
        warning them  of ttie  possible
        danger.
         Parrish said the  results of
        the  analysis  of  the  samples
        taken will be sent to state of-
        ficials in Columbus.
         The man charged with causing
        the poisoning of some 3.400 fish,
        Gary D. Hiles, 24, of 411 Sinton
        St., is being held  in the Scioto
        County jail under bonds totaling
        $3,300. on five charges in con-
        nection with the  poisoning of
        the lake.
                         Dale Roach, enforcement su
                        pervisor  for ihe Ohio  Depart-
                        ment of Natural Resources wild-
                        life division said, "There is no
                        known method of diluting En-
                        drin and  there is  no  way  to
                        isolate it."
                         Officials  are guessing that
                        about a half-gallon of the pesti-
                        cide and possibly as much or
                        more  strychnine was  dumped
                        into the  lake. Hiles reportedly
                        gave no reason.
                         Roach  said Endrin is one  of
                        the more toxic of the chlorinat-
                        ed hydrocarbon pesticides and
                        is used for  mouse control  in
                        orchards during the winter. He
                        said that Endrin "is the most
                        toxic compound for aquatic life.
                        Tests have shown that .003 parts
                        per million in water  will kill
                        fish. By contrast, .01 parts per
                        million are harmful to humans."
                         Merl DeVoe, state game pro-
                        tector, may have suffered a re-
                        action from the poison when the
                        retrieved a jug from the  lake
                        for tests, Roach said.
                         Very little  water has moved
                        over the dam so far into Turkej
                        Creek. Dead  fish  have  been
                        sighted about a half-mile below
                        the dam.
                         Roach said no one, including
                        health officials and Shell Chem-
                        ical Co.,  which makes  Endrin.
                        has' any idea how to counteracl
                        or, dissipate it.
                         Roach said there was no truth
                        to earlier reports that the drink-
                        ing water in Shawnee  State
                        Park comes from the lake. He
                        said he did not know if any of
                        the people living downstream
                        iuse the water for drinking.
                          Authorities have not given a
                        motive  for the lake poisoning.
                          They reportedly arrested Hiles
                        after receiving a tip from some-j
                        one who works with h;m at a'
                        Portsmouth pesticide firm.
                          The Endrin had been  in the
                        jug that  was  recovered,  but
                        Roach said he did not know how
                        ful it was when  emptied  into
                        the lake. The strychnine  was
                        | found in shelled corn, a com-
                        jmon method for controlling
                        j sparrow s.

-------
                PORTSMOUTH, OHIO, SATURDAY, JUNE 12, 1971
 Officials  Try  Charcoal To  Trap
Poison Dumped In Shawnee Lake

Ditching Is
Started To
Divert Flow
 Teams direc-ted by state and
federal officials continued work
today to neutralise  a deadly
pesticide dumped into Shawnee
Lake June 2. and prevent a
spill into Turkey Creek, an Ohio
River tributary.
 Activated charcoal is being
dumped into the Pond Lick res-
ervoir to absorb the poison,
Endrin, which has killed more
than 2.500 fish and frogs, and a
ditch is being dug to rechannel
Pond Lick around the three-acre
lake.
 Gary D. Miles. 24. of 411 Sin-
ton St., who is charged with
poisoning the reservoir, has
pleaded innocent to three of the
five charges filed in the case.

-------
                                     Portsmouth,  Ohio,   June  12,   1971,   pg.   2
4-
  David  Meeker,  assistant  di
rector of  the  Ohio Departmen
of Natural Resources, said fed-
eral  charges  may be  brought
against Miles, who was formerly
employed by  a  firm  that uses
pesticides.
  Everett Ridge, district super-
visor of the wildlife division  of
the state  department  of natural
resources,   said   work   would
continue   through  the weekend
to  contain the  polluted water
and deactivate the poison.
  This morning's  rain  wasn't
expected  to create any problem
since the water level was about
four  indies below the  top  of
the  spillway  which  has  been
sandbagged for  additional pro-
tection.
  Water   samples  are  being
checked regularly  to determine
the  effectiveness  of charcoal
purification. The poison's streng-
th was estimated  Friday to be
13  times  the  federal guideline
maximum for  safe drinking wa-
ter.
  The lake  holds  an estimated
 15,000 gallons of water and this
 may have to be pumped out and
 filtered  and  the   poison-laden
 charcoal and mud  dredged from
 the bottom of the reservoir.
  During their investigation, of-
 ficials recovered  a jug which
 they said had contained Endrin,
 and strychnine     impregnated
 corn, which is  often used  for
 killing sparrows.
  Dead  crawfish  have been
 found along the creek  a half-
 mile  below  the reservoir  and
 area residents have been warn-
 ed  not to use water from the
 stream.
  Meeker said in Columbus re-
 channeling  should take only one
day and would clear the way for
 pumping the lake dry and dredg-
 ing the charcoal and the absorb-
 ed  pesticide from  the bottom.
  Loys Fairish,  a  federal  En-
viromental   Protection  Agency
biologist, said a high concentra-
 tion of Endrin would take up to
10 years  to  disperse.
                                                                                                       POISONED LAKE. Thousands of fish have been killed  as the
                                                                                                     result of the poisoning of waters of Shawnee Lake* (top). Officials
                                                                                                     believe the three-acre lake was contaminated by a strong pesti-
                                                                                                     cide known as Endrin and also with strychnine. Representatives
                                                                                                     of the Federal  Environment  Protection Agency  office at Cin-
                                                                                                     cinnati (bottom) check  samples of water and aquatic life which
                                                                                                     may cause poisoning of the Ohio River. Left to right are Loys
                                                                                                     Parrish,  biologist; Darrell DeRuiter,  sanitary engineer,  and
                                                                                                     Richard  Johnston, aquatic sampler.  (Times photos by Billy
                                                                                                     Graham.)

-------
PORTSMOUTH, OHIO, MONDAY, JUNE 14, 1971
145

-------
                                                     ^__ \  L _r	,__,,,_,„,,, mllu   ,                 -_•! •! _            	   |  .  _

 State   Continues   To  Fight  Poison

 In   Shawnee   Recreational   Lake
     By ROBERT BASS
     Times Staff Writer
 Simulated laboratory tests in
Memphis,  Tenn.,  may develop
a method to clear the poison
from Shawnee Lake.
 Samples of the poisoned water
have been sent to Memphis for
the tests to be conducted by con-
sultants of the U.S. Environ-
mental Protection Agency.
 William B. Nye, Ohio Natural
Resources director, said Tues-
day any decision on methods of
clearing the lake of the poison
will have to await results of the
tests.
  He said the 7;200 pound of car-
;bon spread over the three-acre
[lake in Shawnee State Forest
'has failed to reduce the lake's
poison level substantially.
  The state had hoped  the
activated  carbon would dilute
the poison spilled into the lake
June 2. The gallon of Endrin,
a pesticide, and strychnine, the
poison, killed tine lake's aquatic
life.
  The measured poison level of
from eight to nine  parts per
billion in the lake Sunday had
decreased  to from six to seven
parts by Tuesday, Nye said.
  The amount remains highly
poisonous,  he said.
  The state's natural resources
director said it is felt that steps
already taken to isloate the pois-
oned water and preventing its
spread are sufficient.
  Nye said the following three
alternatives for clearing Shaw-
nee Lake are under study:
  Using a  system of  controlled
carbon  filtration, similar to
ter to water suitable for drink-
ing. Under this proposal, the
lake water would be pumped j
through carbon, rather than
soreading the carbon on water,
as was done last weekend.
 Converting  the lake into a
biological lagoon of the type
used for sewage treatment.
 Using clay or some other com-
pound to absorb the poison.
 Nye returned to Shawnee Lake
Tuesday for renewed consulta-
tion with state and federal per-
sonnel attempting to find a solu-
tion to the problem  of the lake
poisoning.
 Poisoning of the lake is  re-
ported to have resulted in an
official count of 3,400 dead  fish.
This probably is about half the
total kill, Larry G. Rine, Scioto
County game protector, said.
  For safety's sake, the  lake
has been isolated.
  The spillway from Shawnee
Lake to Pond Lick and Turkey
Creek is sandbagged and sealed.
To prevent seepage, additional
sandbags  and plastic  sheets
have been placed there. A bed
of carbon to filter any water
seepage has been set up.
!  Beyond the dam, a catch bas-
in has been created, and any
water getting through is being
returned by pump to the lake.
  A cofferdam has been estab-
lished at the rear of the lake,
and any rainwater running off
is being diverted around the
lake.
  Officials had feared the pois-
oned water might flow into the
Ohio River and cause problems
with water systems downstream.
  The lake, located about 10
miles west of Portsmouth, had
been a popular recreation area
for picnickers, fisherman and
sunbathers.
 Accused on five counts in con-
nection with the poisoning, Gary
D. Hiles remains in Scioto Coun-
ty Jail  in lieu of $3,300 bond.
He is scheduled to appear i n
Municipal Court Thursday morn-
ing.
                                                                  PORTSMOUTH, OHIO, WEDNESDAY, JUNE 16,1971

-------
             The Cincinnati Enquier, June 11, 1971
Poison   Threatens

 Ohio  River   Water
      By BOB ROTHE
  Enquirer Environment Reporter
  PORTSMOUTH — The dumping
of poison into Shawnee Lake in a
state park near here has killed all
of the aquatic life in the lake and
poses a continuing threat to Ohio
River water.
  THE POISON dumped into the
three-acre lake was a combination
of Endrin,  a powerful pesticide,
and strychnine, S c i o t o County
Sheriff John Knauff said. He esti-
mated that about a half gallon of
each entered the lake.
  "There is no known method of
diluting  the compound and there
is no way to isolate it," said Dale
Roach, enforcement supervisor for
the Ohio Department of Natural
Resources' wildlife division.
   There is also some concern on
 the part of the federal Environ-
 mental Protection Agency officials
 that the poison could be carried
from  the lake along the Turkey
Creek tributary to the Ohio Kiver,
thereby possibly threatening water
supplies of those communities -
which get their water supply from
the Ohio.
  The poisoning apparently oc-
curred June 2, Knauff said.
  Garry D. Hiles, 24, Portsmouth,
has been named in five charges in
connection with the incident,
Knauff said.
  Endrin is one. of the more toxic
of  the chlorinated  hydrocarbon
pesticides and is use;' for mouse
control in orchards during the win-
ter.

  ROACH EXPLAINED  that En-
drin is the most toxic known com-
pound for  aquatic  life. (Tests have
shown that .003 parts of Endrin to
a million parts of water will kill
fish; by contrast .01 parts per mil-
lion is harmful to humans.)
  Efforts are being made to pre-
vent persons from having direct
contact with the poisoned lake,
Roach said.
  One  of the wildlife division's
game protectors, Merl DeVoe, may
have suffered a reaction from the
poison when he recovered a  jug
from the lake, Roach said.
  He also  noted  concern  that
some persons may be using the
12-mile stretch of Turkey Creek be-
low the lake for water supply.
  It is hoped that if the com-
pound gets into the Ohio River the
dilution from the large volume of
water will decrease the poison be-
low harmful levels.
   For  the  present the poisoned
water is contained in the man-
made lake with the exception of
small amounts that the wind has
lifted over the dam. In these in-
stances there have been fish killed
as  far as a  half mile below the
dam.
  The total fish kill has been esti-
mated at 3400.
  Hiles, who is being held in the
county jail in lieu of $3300, faces
charges of destruction of property,
administering of  poison and three
counts of killing fish. Entry of a
plea will be heard next Thursday
in municipal court in Portsmouth.

-------
    THE NEW YORK TIMES, SUNDA Y, JUNE 27, 1971
   Pesticide  Poisons Lake   in   Ohio
      By GEORGE VECSEY
      Special to The Xe\v York Timss
    PORTSMOUTH, Ohio, June
   22 — Until three weeks ago,
   Shawnee Lake  was just an-
   other quiet  fishing  hole  in
   the southern Ohio hill coun-
   try.  Then  somebody  with
   half a  gallon   of  pesticide
   turned it into  five  acres of
   death.
    Within two days,  all 3,400
   sunfish  and  carp and  blue-
   gill  in  the man-made  lake
   floated dead on the surface,
   along with numerous frogs
   and snakes.
    Since  then, officials  from
  Federal,  state,  local, college
  and  private  sectors  have
  worked  around  the  clock to
  prevent  damage to  humans,
  to the water downstream and
  to the total environment  of
  Shawnee State  Park.
    They say they will save the
  lake  by August, but at  a
  cost of at least $30,000,  not
  to  mention man-hours  lost
  from other jobs.
   A   suspect,   24-year-old
  Gary D. Hiles of Portsmouth,
  has  been arrested and  held
  in $3,000 bail on charges of
  destroying state property and
  wildlife.  Officials say there
  are witnesses who saw Mr.
  Hiles throw a jug into the
  lake  and  there   is  a report
  that  Mr.  Hiles was upset af-
  ter being dismissed by a com-
  pany   that  distributes  the
  pesticide, Endrin.  Mr.  Hiles
  has pleaded not  guilty to the
  charges.
I   A "Restricted" Chemical
   Endrin  is similar to DDT,
  according  to  William  Nye,
  director of the Ohio  Depart-
 ment  of  Natural Resources.
 The chemical  is  "restricted"
 by the state for  limited  use
 as a rodent  killer but it is
 sold  to any  private  citizen.
 Mr. Nye said that Endrin was
 dangerous at one part per bil-
 lion and  lethal at that dos-
 age  "in prolonged usage."
   The  manufacturer   says
 that Endrin breaks down  in
 three months, but Mr. Nye
 insists that the process often
  takes two years.
                                        Associated Press
Officers of the Environmental Protecting Agency check
for signs of aquatic life in  the waters, poisoned by a
chemical, of Pond Lick Reservoir, near Portsmouth, Ohio.
                              148

-------
          New York  Times,  June  27,  1971,  p.  2
   "If  a  drug  is  dangerous
 for 'human consumption, you
 need a  prescription for it,"
 Mr. Nye said. "But if a chem-
 ical is not  for human  con-
 sumption, it's available with-
 out a prescription. Yet it can
 go into  the  food chaan by
 clinging to a plant  for two
 years  and being  eaten by
 cattle  and  passed on to in-
 fants in milk."
   Because  Endrin   is   not
 broken down by  water,  the
 officials  felt  obliged  to  re-
 move it  from Shawnee Lake
 before  it  floated  through
 seven miles of creeks and in-
 to the Ohio River. But there
 was no   simple,  established
 procedure for the job.
  While  Mr. Nye  summoned
his staff from all  over Ohio,
a young  graduate  micro-biol-
ogist from Ohio State Univer-
sity, David  Howard, brought
down    a   chromatograph,
which  tests water  samples
but had  never  been trans-
ported outside the  laboratory
in Columbus. The  chromato-
 graph  soon  indicated  that
 the  toxic  level  was  eight
 parts per billion  throughout
 the lake,
   Stream and Spillway Shut

   Meanwhile,   the   feeding
 stream above the lake and
 the  spillway  below  were
 closed  off, and a  cleaning
 system was devised  by Mr.
 Nye, Dr.  Hugh  Thompson of
 the Environmental Protection
 Agency  in  Washington  and
 Dr. S. James  Ryckman of a
 St.  Louis and Dayton water
 consulting firm.
   The men set  up a model
 system, pumping water from
 the lake  into a small tank,
 then  running  the   water
 through  a carbon  chemical,
 "filtrasorb," which had been
 rushed, at cost, by the Cal-
 gon Company from its plant
 at  Catlettsburg, Ky.  Filtra-
 sorb drew the pesticide from
 the water—"adsorbed" is the
 technical  word—and  passed
 the  purified  water out  the
 other side.
  Dr. Ryckman demonstrated
 the purity of  the water. He
 drank some  of it.
  Then Dr. Thompson called
 for a cypress-board tank with
 a capacity of  24,000  pounds
from the  Environmental A-
gency's   Cincinnati   office.
Pumps and hoses were assem-
bled from various sources,
including   the  local  fire
department. Calgon delivered
600 sixty-pound  bags  of Fil-
trasorh. The  pumps   pushed
  Tht New York Times   Jimt27,1971
 water upward at 500 pounds
 per  minute  throughout  the
 chemical in the cypress -tank.
 And  clean water began  to
 flow downstream again.
  The scientists  say it will
 take them  21 days to lower
 the lake by  10- feet.  If  the
 water is clean  at that  level,
 they will cleanse the sides of
 the lake and refil it. They feel
 they will be finished by Au-
 gust,  when the lake will  be .
 restocked   with  fish  from
 state hatcheries.
  "I  think  this is a classic ex- ;
 ample of forgetting the  bu- j
 reaucracy   and  just  getting j
the job done," Dr. Thompson i
said.   "Everybody  cooperat- |
 ed — particularly the  local
workmen who  have worked
late every  night.  We're just
sorry it happened in the first
place."
                                  149

-------
                 PORTSMOUTH, OHIO, THURSDAY, JUNE 17, 1971
 Filters  Will  Clear Lake
      By ROBERT BASS
      Times Staff Writer
  An active  carbon  filtration
 plant may  extract the poison
 from Shawnee Lake waters.
  Representatives of a water re-
 source consultants firm  expres
 sed confidence  the procedure,
 being initiated for a trial period,
 will work.
  That trial  period was begun
 Wednesday  afternoon with  a
 pilot plant set up and  placed in
 operation at the lake  by Ryck-
 man-Edgerley-Tomlinson  and
 Associates of St. Louis.
  This firm of consultants in wa-
 ter, solids and air resources has
 been engaged for  the Shawnee
 Lake  project under contract
 with the U.S.  Environmental
 Protection Agency.
  The pilot plant is to  be in op-
 eration for a trial period of  24
 hours a  day for  several days.
 If it suceeds, a larger, prototype
 plant will be set up at the lake.
1  Dr. Cecil   Lue-Hing,  a  vice
 president of  the St. Louis firm,
 said the prototype plant would
 be   the  equivalent of a small
 water treatment  plant  of  the
 type the Army might set up  at
 an  advanced base.
  It would be the equivalent, too,
 of  a water  treatment plant a
 small city of perhaps 10,000 per-
 sons would use, he added.
  "We do feel confident the poi-
 son can be removed by activat-
 ed  carbon filtration and  absorp-
 tion," another spokesman for the
 St.  Louis firm said.
  The pilot activated carbon ab-
 sorption plant was set  up at the
 lake and placed in operation  by
 Dr. Lue-Hing; Joseph  Dieter-
 man, senior associate, and Wil-
 liam (Bill) Anderson, senior en-
 vironmental engineer, with the
 St.  Louis firm.
  The portable pilot plant uses
 a pressure pump and hoses, a
 swimming pool filter, and a tall
 metal activated carbon column.
  Water  pumpd  from the lake
 is filtered and absorbed  in acti-
 vated carbon. Surfaces of the
 activated carbon  particles will
 pick up the poison from  the wa-
 ter. Hopefully,  clean,  filtered
 water then can be returned  to
 the lake.
                                "We'll keep this portable plant! ficer, and all work at  Shawnee
 in  operation  for  two,  possibly
 three,  days,   depending  upon
 what we find out," Dr. Lue-Hing
 said.
   Marvin  Katz,  Ohio Depart-
 ment of Natural Resources chief
 of public  information, said  the
 pilot carbon alteration plant
 Lake is being coordinated under
 his supervision.
  The  complex problem of ex-
 tracting the Endrin, a pesticide,
 and strychnine, the poison, from
 Shawnee Lake is the first  proj-
 ect in which the federal Environ-
 mental Protection Agency's Di-
 project will determine which is  vision of  Hazardous Spill Pro-
 the  more effective method  of'tection ever has been involved.
 removing  poison from the t'ke  This division was founded only
 —the controlled carbin filtration  nine months ago.
 procedure, or  the  method  d   Redebt said Wednesday there's
 spreading  carbon on the water, I, a possibility a  gas chromatl
 as was done last weekend.
   He added that tests of Shaw-
 nee Lake water samples  being
 conducted in the federal Envir-
 onmental Protection Agency la-
 boratories in Memphis, Tenn.,
 will have an influenceing  effect
graph  can be  brought  to  the
Shawnee Lake project for quick,
on-tbe-scene  analysis  of  lake
water samples.
  He said the apparatus would
make  it unnecessary to  send
further samples to Taft  Lab-
 on any ultimate decision in co-       .   fa c"iocinnati or to the
 ping with the problem of  the  laboratories in Memphis.
 poisoned  water.                 Dieterman added that the gas
   "But, we do want  to take a  chromatigraph  cauld  analyze
 close look at all possible van-  water saniples in about an hour.
 ables —  even the variables on  Effectiveness of the pilot act-
 the alternatives."               ivated carbon filtration and ab-
   Alternatives under  consider-  sorption plant project could be
 ation are the possibilities ot  d€terrain^ at the scene> he sadd.
 converting the lake into a biolo-   The lake and its poisoned wa-
 gical lagoon of the type used for  ter are isolated and  Contained;
 sewage treatment; or **>•*£  the problem of removing,  or ex-
 other type of compound to  ab-  ^^g the   isfln is ^t to be
 sorb the  Ppison.                solved, Redett said.
   Katz said that if the pilot plant   Shawnee Lake has been a pop-
 project ig successful,  the  pos-
 sibility of setting up the larger
 prototype plant downstream in
 the area  of the causeway, will
 be considered.
i   Robrt Redett, assistant chief
 of the Ohio Department of Re-
 sources of  Forestry,  said the
 prototype  plant would be larger,
 modified  version  of  the pilot
i plant.
   Katz said no decision yet has
 been made on  funding of the
 total project, nor is it yet known
 how much the total project ul-
 timately will cost.
   The bulk of the costs involv-
 ed so far has been taken care
 of by state funds.
   Work at Shawnee Lake is a co-
f operative project of the Ohio De-
 partment  of Natural Resources
 and the U.S. Envimmental Pro-
 tection  Agency.
   Dr. Hugh  Thompson of the
 federal Environmental  Protec-
tion Agency, is the project of-
ular recreation area for fisher-
men, picnickers and sunbathers.
Even before the poisoning, swim-
ming at the lake had been pro-
hibited.
  Aquatic  life  in the lake has
been killed by the poison. "It,
therefore,  must  be considered
highly toxic." Redett said.
                                                150

-------
             Portsmouth,   Ohio,  June  17,  1971,  pg.   2

  PILOT PLANT.  A portable pilot plant for  activated carbon filtration and absorption was set
up and placed in operation at poisoned Shawnee Lake  Wednesday afternoon  by  representatives
of Ryskman-Edgerley-Tomlinson and Associateof St.  Louis,  Mo., employed  under contract for
the poison removal project by the U.S.  Environmental Protection Agency. In top photo, William
(Bill) Anderson,  (left), senior environmental engineer, and Joseph Dieterman, senior associate,
with the St. Louis firm, activate the portable plant's pressure pump.  In bottom photo, Dr. Cecil
Lue-Hing,  (extreme left), a vice president of the firm, Dieterman and Anderson make final ad-
justments before starting the plant on its approximate three-day trial  period.   If the  trial plant
succeeds, a larger prototype will be set up at Shawnee Lake.  (Times photos  by  Billy Graham.)
(Another photo on Page 16.)
                                      151

-------
Portsmouth,   Ohio,  June   19,  197L,  pg.  2
 however,  the  period may  be
 longer, depending upon how oft-
 en the  treatment plant's tons
 of filtering charcoal will  have
 to be changed.
   Total costs of the complicated
 and involved  project of  remov-
 ing the poison from Shawnee
 Lake  are expected  to  exceed
 $100,000, William B. Nye, direc-
 tor of the Ohio Department of
 Natural Resources, said.      j
   It has been estimated that ap-
 proximately  $50,000  has  been
 spent  on the project  since the
 poison, spilled into the lake June
 2, was discovered June 4.
   Katz said  it  isn't yet known
 how cost will be apportioned inj
 this joint project of  the  Ohio
 Department of  Natural Resour-
 ces and the U.S. Environmental
 Protection Agency.
   The new treatment plant is
 capable of filtering 230,000 gal-
 lons of water a  day from the 15-
 million-^ailon  Shawnee  Lake.
   Dr. Thompson, the project of-
 ficer at the site, said, however,
 it will handle water flow at ap-
 proximately  the same rate  as
 that handled  by the  successful
 pilot plant.
   Built   of   hastily-assembled
 available materials, the proto-
 type plant is to be operated on
 the "fail safe design concept,"
 Dr. Thompson said.
   The  water  is to be filtered
 from the upstream side of the
 dam, so that  any leakage or
 drainage will go back into Shaw-
 nee Lake — or  Pond Lick Res-
 ervoir, he said.
  Water is being pumped  from
 the lake  and  into the filtering
 tons of activated charcoal par-
 ticles in the big cypress board
 box, then released into the  spill-
way on  the other side of the
dam.
  From there, it's  to flow down
Pond  Lick and  into  Turkey
Creek,  and, eventually, into the
Ohio River.
  "It's  a  shame,  really,  that
the clean, filtered water is go-
ing into the spillway. Once it's
filtered  in  the treatment plant,
it's cleaner than most drinking
water," Dr. Thompson said.
  The  project officer  said the
prototype  plant  would   more
than meet the water treatment
needs of a community of 10,000
persons.
  The water filtration system is
 to be in operation until the con-
 centration remaining in the lake
 is infinitesimal, and the water
 is unquestionably  safe,  the pro-
 ject officer said.
  Samples taken from the lake
 before  and after  filtration  are
 analyzed in  the gas chromato-
 graph  operated   in  a  former
 Shawnee Honor Camp  building
 by a young Ohio State University
 graduate student — David How-
 ard of Dayton.
  Howard, working on  his doc-
 torate in OSU's Department of
 Microbiology, said the precision
 chromatograph  can analyze a
 water sample in 45 minutes.
  "Once a sequence of  samples
 is started in the chromatograph
 any sample in the sequence can
jbe analyzed  in 15 minutes,"  he
 said.
  The  OSU   graduate  student
 said the little pilot water treat-
 ment plant  set up on the dam
'at  Shawnee Lake by  the  St.
 Louis firm of Ryckman-Edgerly
 Tomlinson and Associates "did
 indeed do the job."
  He  said the water that came
 out of the filter system in the
 old submarine ballast tank was
 pure — "cleaner  perhaps than
 most  of the water we drink."
  In the first 11 hours after the
 little  experimental water treat-
 ment plant was placed in oper-
 ation,  it filtered  14,000  gallons
 of water. A total  of 17,000 gal-
 lons of water had been filtered
 through  the  pilot plant  by 2
 p.m.  Friday.
  Thirty-nine samples had been
 analyzed in the chromatograph
 by 2 p.m. Friday. Results of the
 tests left little doubt the experi-
 mental plant  was filtering the
 Endrin,  strychnine  and  other
 sediment from the water with
 great efficiency.
  Once this was established, the
 little  pilot plant was taken  off
its 24-hour schedule, and work
started   immediately on con-
struction of the larger prototype
plant.
  Technicians of  the St.  Louis
firm had set up the pilot plant
 under  construction with  aofrd
 under contract with the federal
 Environmental Protection Agen-
cy.
  Dr.  Thompson flew to Cincin-
 nati to get the big box for the
 prototype  plant.  It  had ben
 part of a large-scale water treat-
 ment  plant  operating  at  the
 Taft Center laboratories in Cin-
 cinnati
   Under Dr.  Thompson's super-
 vision,  employes  of  the  Ohio
 Division of Forestry in Shawnee
 :Forest helped construct the pnf-
 totype in the garage  near  the
 Division of Forestry's headquar-
 ters.
   The box was moved to the site
 of the  lake's dam by  flatbed
 truck and lowered into place
 by massive hooks.
   The prototype  system,  enhan-
 ced  by the  ready availability
 of the chromatograph,  not only
 is to work with  water  samples.
 lit also is to test  sediment taken
 ait intervals from the lake bot-
 tom.
   There was no need for a plan
 to drain the lake if there is no
 toxic  content in the sediment,
 Howard  said.
   The OSU graduate student is
 to remain here until the poison
 : removal project  at the lake is
 complete.  Dr. Thompson plans
 to return  to  Washington, D.C.
 in a "day or so," he said.
   Katz and motion picture and
 still  camera  crews  from the
 Ohio Department of Natural Re-
 sources  were at the lake site
 Friday.  Among  others  at the
 site was  S.  James  Ryckman.
 vice president of the Ryckman-
 Edgerley-Tomlinson firm of wa-
 ter  and  air  resources  consul-
 tants.
   Assistant ranger at Pond Lick
 Reservoir,  Frank Tackett, said
 that  since the  development  of
 the  new  Turkey  Creek Lake
 and the improvement  program
 at Roosevelt Lake,  "We've been
 attempting to  encourage the pub-
 lic to use  those facilities."
   He said  there's  no lifeguard
 at Pond Reservoir, or Shawnee
 Lake, and swimming isn't per-
 •mitted there.
j  "It is a shame, though, be-
 cause some retired, older peo-
 ple  had  been coming  out  to
 Shawnee Lake on weekends and
 would spend a whole day fish-
 ing, Tackett said.
   Poison removal work  at the
 lake has increased the number
 of visitors to  Pond Lick  Reser-
 voir, and Tackett says he flunks
 the next  few weekends could
 bring between 300 and 400 peo-
 ple out here to look around."   i
                                  152

-------
 Portsmouth,   Ohio,  June  17,  1971,  pg.  3
  PIPELINE.  Part of the cofferdam system set up at poisoned Shawnee Lake is this pipeline
which Robert Redett,  assistant chief of the Forestry Division of the Ohio Department of Natural
Resources, says has  done a highly-effective job of diverting recent rain  run-off around the
lake. The pipeline has kept rainwater run-off from causing an overflow of poisoned water from
th.e lake.
                          153

-------
          PORTSMOUTH.  OHIO, SATURDAY, JUNE 19, 1971
           Outlook Is
           ^GoocF For
           Clear Lake
                By ROBERT BASS
                Times Staff Writer
            Shawnee Lake should be clear-
           ed of its poison by  early Aug-
           ust.
            "Guesstimates" that the com-
           plex  poison  removal  project
           should be completed within 45
           days  were  made by conserva-
           tionists  who set up  a larger,
           prototype water  filtration plant
           at the lake late Friday.
            Its operation begun this morn-
           ing, this prototype plant replac-
           es the smaller pilot, or experi-
           mental plant set up at the lake
           last Wednesday.
            Decision to build and to use
           the larger, but more  compact
           prototype plant  came after it
           was  discovered  that the little
           experimental plant was working
           with watch-charm efficiency.
  The portable pilot plant, with
its precision pressure pump and
hoses, its swimming pool filter,
and  its  old  submarine ballast
tank filled with activated char-
coal, has been disassembled.
  Now operating in its place is
the prototype plant with huge,
rectangular box; 15,000 pounds
of activated  carbon, and pres-
sure pump capable of  pumping
500 gallons of  water a minute.
  Samples of Shawnee Lake wa-
ter, before and after they're fil-
tered through  the big box of
activated charcoal particles, are
to be analyzed in a gas chroma-
tograph   brought  to   Shawnee
Lake  late Thursday from Ohio
State  University's Department
of Microbiology.
  This sophisticated instrument
is to give almost instant analy-
sis to Shawnee Lake water sam-
ples, making it unnecessary to
send those samples either to the
U.S.  Environmental Protection
Agency  laboratories  in  Mem-
phis, Tenn., or  to  Taft Central
laboratories in Cincinnati.
  The  new  water  treatment
plant, with its  system  of water
filtration  and absorption by ac-
tivated carbon  particles, is to
be in operation until water re-
maining in  the lake tests  out
absolutely safe, Dr. Hugh  C.
Thompson of  the  federal  En-
vironmental Protection  Agency,
said.
  The consensus is  that  thir
should occur within 45 days.
  Marvin Katz, Ohio  Depart-
ment of Natural Resources chief
of  public  information,  said,
154

-------
Portsmouth,  Ohio,  June  19,  1971,  pg.   3
  PROTOTYPE.   Success of the little pilot, or experimental
water treatment plant at poisoned Shawnee Lake resulted Fri-
day in quick development of the larger, more compact proto-
type plant, which is to use about 250 bags of activated charcoal
granules in its filtration system inside the huge box.  In top
photo, S. James Ryckman, vice president of the St. Louis firm
of water and air resources consultants that developed and set
up the successful pilot plant; and Dr. Hugh C. Thompson of the
federal  Environmental and Protection Agency,  the poison re-
moval project officer, finalize plans for setting up the prototype
plant, upon which employes of the  Ohio Division of  Forestry
(background) are working.  In center and bottom photos, David
Howard, graduate student in the Ohio State University De-
partment of Microbiology, uses the precision  gas chromato-
graph,  brought in from OSU Thursday night,  in analysis  of
water samples taken from the  poisoned lake.  The  recorded
peaks in the graph in center photo are the Endrin content in un-
filtered  waler samples: the long, firm straight lines  are the
pure analysis of the filtered samples.  In bottom  photo, Howard
uses a hyperdemic syringe to inject a watc: sample into the
machine.
   155

-------
            For 119  Years A Dependable Portsmouth Institution
Published daily except Sunday
by Thomson-Brush-Moore Newspapers, Inc.
                   Member Associated Press
                   Established March 23, 1852
Monday, June 21,  1971
                                  Page  6
                    A First We Didn't  Need
  Some of our records are such that we may be
proud  of them in a  constructive sort  of way.
Some  records  are such that we'd rather not
think of  them, and  others are such that  we
can  be proud,  despite the fact that  perhaps
we'd rather the need never had come up.
  Of  course we would have preferred that the
poisoning of Shawne Lake never had occurred.
We would have preferred to have left it alone,
filled with  fish and circled by  fishermen.
  Unfortunately, this didn't happen. The lake
was poisoned and thousands of fish were killed.
Many fishermen were deprived  of their pleas-
ures, and many other people were worried be-
cause of the potential threat if the poison had
escaped the lake's confines.
  We can be proud of none of these.
  We can  take great pride in the response of
the many agencies concerned with clearing the
lake of the poison. We can take pride in the fact
that  the discovery came early enough to pre-
vent  harm to persons who use the lake. We can
take pride in  the efforts  of every individual
concerned with the action in any way.
  Since we had the problem, we also can take
pride in the fact that this is the place where
the recently created United States Environmen-
tal Protection Agency got its first real test.
  The agency,  not yet a year old,  was called
into the case early, and this action perhaps is
to be credited  for quick decisions on steps to
take in fighting poisons.
  It has been more than two weeks since first
signs  of the poison were reported, but the re-
searchers have had complete cooperation from
everything, including the weather,  in  striving
to overcome the problem.
  Now it appears that success is only a matter
of time. Experiments  have proved that the pois-
on can be  eliminated by mechanical-chemical
processes,  and the potential danger to the lake
and to the waters which get the lake  overflow
will not be endangered.
  Early estimates were that a natural clearing
of the lake would take up to 10 years were no
less than frightening, especially  in considera-
tion of the current growth  and development in
Shawnee State Forest. Now, with estimates that
the lake will be cleared within as little  as 45
days,  it appears that we can stamp "success"
on the project.
  Expense has been no problem. Every agency
concerned has gone all the way, setting no limit
on efforts to clear poison. Such cases are rare,
but this- has been an unusual case from the be-
ginning.
  If there is any pride to be had in such a case,
we are proud that the first  real test of the U.S.
Environmental Protection Agency, with its al-
allied  agencies, found its first success here.
  We hate to think of what could have  happen-
ed had this case been a failure.
                                         156

-------