v>EPA
                      United States
                      Environmental Protection
                      Agency
                     Office of Water
                     Washington, D.C.
EPA 832-F 99-074
September 1999
Decentralized Systems
Technology Fact  Sheet
Mound  Systems
DESCRIPTION

The mound system was originally developed in
North Dakota in the late  1940s and called the
NODAK disposal system.   Some soil types are
unsuitable for conventional  septic  tank  soil
absorption systems.  As a result, alternative systems
such as the mound system can be used to overcome
certain soil and site conditions.

The mound design in predominate use today was
modified from the NODAK design by the University
of Wisconsin-Madison in the early 1970s. Although
there  are now many different mound designs in use,
this fact sheet will focus on the Wisconsin design.
The Wisconsin mound has been widely accepted and
incorporated into many state regulations.

The three principle components of a mound system
are a  pretreatment unit(s), dosing chamber and the
elevated mound.  Figure 1 illustrates a Wisconsin
mound system.

APPLICABILITY

Mounds  are  pressure-dosed  sand  filters that
discharge directly to natural soil. They lie above the
soil surface and are  designed to overcome site
restrictions such as:

•    Slow or fast permeability soils.

•    Shallow  soil cover over creviced or porous
     bedrock.
                    The main purpose of a mound system is to provide
                    sufficient treatment to the natural environment to
                    produce an effluent equivalent to, or better than, a
                    conventional onsite disposal system.

                    ADVANTAGES AND DISADVANTAGES

                    Listed  below  are   some  advantages  and
                    disadvantages of mound systems when compared to
                    other alternative onsite systems.

                    Advantages

                    •    The mound system enables use of some sites
                         that would  otherwise be unsuitable  for
                         in-ground or at-grade onsite systems.

                    •    The natural soil utilized in a mound system is
                         the upper most horizon, which is typically the
                         most permeable.

                    •    A mound system does not have a direct
                         discharge to a ditch, stream, or other body of
                         water.

                    •    Construction damage is minimized since there
                         is little excavation required in the mound area.

                    •    Mounds can be utilized in most climates.

                    Disadvantages

                    •    Construction costs are typically much higher
                         than conventional systems.
     A high water table.

-------
                                            TOP SOIL
                                                                           OBSERVATION TUBE
                                                                             ./DISTRIBUTION
                                                                            / LATERAL
                                                                                      SAND
                                                                                     'FILL
                   ;..- • "^
                           v-.'-j  - -  ... .----v >:'
               .r^'
                                                           BASAL AREA -
                                                           PLOWED LAYER -J
-.. ABSORPTION
    AREA
HIGH WATER.-
ALARM SWITCH
                                   - PUMP SWITCH
          SEPTIC TANK
                            DOSING CHAMBER
                                                    MOUND
Source: Converse and Tyler, Copyright© by the American Society of Agricultural Engineers, reprinted with permission, 1987.

                FIGURE 1 SCHEMATIC OF A WISCONSIN MOUND SYSTEM
•     Since  there  is  usually  limited permeable
      topsoil  available  at  mound  system sites.
      Extreme care must be taken not to damage
      this layer with construction equipment.

•     The location of  the mound may  affect
      drainage patterns and limit land use options.

•     The mound may have to be partially rebuilt if
      seepage or leakage occurs.

•     All systems require pumps or siphons.

•     Mounds may not be aesthetically pleasing in
      unless properly landscaped.

DESIGN CRITERIA

Two  factors  that   determine   the   size  and
configuration of a mound  are; how the  effluent
moves away and the rate at which it moves away
from the system. The  prediction of the movement
and rate of movement is done from  studies of the
soil and site information obtained.  To ensure proper
performance of the mound  system,  the following
concepts must be  included  in  the design and
construction process:
                               •     1) Leaving the topsoil in place but plowing it
                                        before placement of the fill.

                               •     2) Using a coarse sand fill meeting grain size
                                        distribution specifications.

                               •     3) Using pressure to uniformly distribute the
                                       effluent over the seepage area.

                               Soil Depth

                               A suitable depth of soil is required  to treat the
                               effluent before it reaches the limiting condition, such
                               as  bedrock,  a  high water  table,  or  a  slowly
                               permeable soil  layer. Although the separation
                               distance varies, it is usually between 1  and 4 feet.

                               Site and Design

                               To  date,  siting and  design experience at sites
                               suitable for mound systems indicates that absorption
                               systems should  be long  and narrow  and should
                               follow the contour (i.e., level). The more restrictive
                               the site, the narrower and longer the system. Table
                               1  gives the soil criteria  for a Wisconsin  mound
                               based on research and field experience.

-------
   TABLE 1  RECOMMENDED SOI LAND
   SITE CRITERIA FOR THE WISCONSIN
        MOUND SYSTEM BASED ON
   RESEARCH AND FIELD EXPERIENCE
 Parameter
   Value
 Depth of high water table
 (permanent or seasonal)

 Depth to crevice bedrock

 Depth to non-crevice bedrock

 Permeability of top 10 in.

 Site slope

 Filled site

 Over old system

 Flood plains	
    10 in.

    2ft.

    1 ft.

Moderately low

    25%

    Yesa

    Yesb

     No
 a Suitable according to soil criteria (texture, structure,
 consistence).
 b The area and backfill must be treated as fill because it
 is a disturbed site.

 Source: Converse and Tyler, 1990.

High Water

The  high  water table  is  determined by direct
observation (soil boring),  interpretation  of soil
mottling, or other criteria. The bedrock should  be
classified as crevice, non-crevice semi-permeable, or
non-crevice impermeable. This will determine the
depth of sand media required.

Percolation and Loading

Percolation tests are  used in some jurisdictions to
estimate the  soil permeability  because they  are
empirically related to the loading rate. Loading
rates should be based on the soil texture, structure,
and consistence, using the percolation test only to
confirm morphological interpretations.

Mounds

Mounds can be constructed on sites with slopes up
to 25%. The  slope  limitation  is  primarily  for
construction safety, because it is difficult to operate
equipment  on  steep slopes,  and  they  pose a
construction hazard. From a hydraulic perspective,
mounds can be positioned on steep slopes.
Sites

In the case of filled sites, fill material is placed on
top  of the natural  soil and may  consist of soil
textures ranging from sand to clay. Sufficient time
must be allowed for the soil structure to stabilize
before  constructing   a  system.   Many   more
observations are required for filled  areas.

When evaluating the soil loading rate for a mound
over an old or failing in-ground system, the soil over
the system must be considered to be disturbed, and
thus, treated  as  a filled site. If a mound is to be
placed over a large in-ground system,  a detailed
evaluation of the effluent movement should be done.

Mounds  should not be installed in flood  plains,
drainage  ways,  or  depressions   unless   flood
protection is provided. Another siting consideration
is  maintaining the horizontal separation distances
from water supply wells,  surface waters, springs,
escarpments, cuts, the boundary of the  property,
and the building foundation.  Sites with trees and
large boulders can make it  difficult in preparing the
site. Trees should be cut to the ground surface with
tilling around stumps. The size of the mound should
be increased to provide sufficient soil to accept the
effluent  when   trees  and  boulders  occupy   a
significant amount of the surface area.

The actual size of a mound system is determined by
estimating the sand fill loading rate, soil  (basal)
loading rate, and the linear loading rate.  Once these
values are established, the mound can be sized for
the site.  The final  step is to design the effluent
distribution network and the pumping system.

PERFORMANCE

One factor that determines good performance is the
type of sand fill material. A suitable sand is one that
can adequately treat the wastewater.  Suitable sand
should contain 20% or less material greater than 2.0
mm and 5% or less finer than 0.053 mm. It should
also have a size distribution that meets certain sieve
analysis specifications, ASTMC-33 specifications,
or meets limits for effective diameter and coefficient
of uniformity.

-------
For  design  of residential  mounds,  the  daily
wastewater volume is determined by the number of
bedrooms  in  a  house.  Typical  design  flow
requirements for individual homes are up to  150
gallons  per  day  (gpd) per  bedroom.   Design
specifications for mound systems are usually the
same for both  large and small flows for typical
domestic  septic tank  effluent.  Higher  strength
wastes must be  pretreated to the levels of domestic
septic tank effluent, or lower hydraulic loading rates
may be applied.

IMPLEMENTATION

In Wisconsin, the success rate of the mound system
is over 95%, which is due to their emphasis on
siting, design, construction and maintenance.

Years of monitoring the performance of mound
systems have shown that mounds can consistently
and  effectively treat and dispose of wastewater.
Studies have shown evidence that some nitrogen
removal  does  occur  in mound  systems  when
approximately 2 feet of natural unsaturated soil is
below the fill material.

Mound Systems in Wisconsin (State-Wide)

Using relatively conservative  soil  criteria,  many
states have accepted the Wisconsin mound system
as an  alternative when conventional  in-ground
trenches and beds are not suitable. The Wisconsin
mound system  has  evolved into  a viable onsite
system for  the treatment of wastewater  from
individual, commercial, and community systems by
overcoming some of the site limitations and meeting
code requirements and guidelines.

In 1978, an experimental  study was initiated to
evaluate  soil/site  limitations  for the Wisconsin
mound (see Converse  and  Tyler,  1987a).   The
objectives of this research study were to determine
whether the  existing soil/site limitations on mounds
were too restrictive and to determine the minimum
soil/site limitations under which the mounds would
perform without affecting public health  and the
environment. The experimental approach was to
design, construct, and evaluate sites with mound
systems  that  currently  did  not  meet  code
requirements due to  failing systems.
The  sites selected for this study had to fit the
objectives of the research and generate a reasonable
amount of wastewater to be mound  treated. The
sites selected had to have:

1.      Fill soil placed over natural soil.

2.      A high water table where the seasonal high
       water table level was less than  60 cm below
       the ground surface.

3.      Slowly permeable soils  that  were rated
       slower than moderately permeable soils.

4.      Steep slopes greater than 12%.

5.      Mounds over existing failing systems.

6.      A combination of the above.

Over 40 experimental mounds were  constructed
between 1979  and 1983 on sites that did not meet
the code requirements; 11  of these  mounds are
described in detail in this study. Site evaluations
were done by certified soil scientists, plans prepared
by designers were reviewed and approved by the
state, and licensed contractors installed the systems
with  inspections by  county  sanitarians  during
construction.

The study concluded that the overall performance of
the mounds was very good. The systems functioned
satisfactory on filled sites, on sites with a high water
table (seasonal water table 25 to 30 cm from the
ground surface), on steep slope sites  (up to 20 to
25%), on sites with slowly permeable soil, and on
top of failing systems. Leakage occurred at the base
of the mound on some sites during extremely wet
conditions, but the effluent quality was good, with
fecal counts generally less than 10 colonies per 100
ml in saturated  toe  effluent. It was found that
Wisconsin mound systems can be constructed on
difficult sites if the system is designed using linear
loading rates, which  are established based on the
horizontal and vertical acceptance rates of the soil
for each system.

-------
Failure of Mound System in Wisconsin

Expansion of a Wisconsin firm's mound system in
1978, resulted in a clogging and seepage problem.
The  system  was  originally built  to  handle  65
employees at 750 gpd and was now serving a staff
of 165. This expansion created a failure  of  the
mound system due to hydraulic overload. To solve
this problem, the mound system was expanded and
a water conservation program  was initiated. The
expansion of the mound  increased the hydraulic
capacity to 2,600 gpd (Otis, 1981.)

In November 1979,  the  mound  system  failed
again—this time due to a biological clogging mat.
The clogging mat was removed by using 450 gallons
of a  10% solution of hydrogen peroxide. The
mound system was operating successfully within 2
days. However, further research indicates that  for
structured natural soils other than sand, hydrogen
peroxide may reduce the soil infiltration rate, and
thus, may not be an effective procedure to eliminate
soil clogging.

A third failure occurred in January 1980, again due
to hydraulic overload. The firm had expanded its
employee base to 215 employees, with an average
daily  flow of 3,000 gpd.  There was no  room
available to expand the mound system itself, so  the
firm redesigned the pumping chamber to avoid large
peak flows, allowing the mound system to receive
optimum dosing without failure.

OPERATION AND MAINTENANCE

The  septic tank and dosing chamber should  be
checked for  sludge and scum buildup and pumped
as needed to avoid carryover  of solids into  the
mound. Screens  or filters can be used to prevent
large  solids  from  escaping the septic tank. The
dosing  chamber,  pump,  and  floats  should  be
checked annually  and replaced or  repaired  as
necessary. It is  critical that the septic tank and
dosing  chamber be  watertight.    In addition,
electrical parts and conduits must be checked  for
corrosion.   Flushing  of the laterals  annually is
recommended.

When a mound  system is properly installed and
maintained, it should last for a long period of time.
In general, the maintenance required for mounds is
minimal.  However, as  with any  system,  poor
maintenance could lead to early  system failure.
Possible problems that can occur in an improperly
designed or constructed mound system include:

•    Ponding in the absorption area of the mound.

•    Seepage out of the side or  toe of the mound.

•    Spongy areas developing on the side, top,  or
     toe of the mound

•    Clogging  of the distribution system.

Practices that can be used to reduce the possibility
of failure in a mound system include:

•    Installing water-saving devices to reduce the
     hydraulic  overload to the system.

•    Calibrating  pumps   and  utilizing  event
     counters and running time  meters.

•    Timed dosing to dose equally sized doses on
     regular intervals throughout the day.

•    Diverting surface water and roof drainage
     away from the mound.

•    Preventing traffic on the mound area.

•    Installing  inspection tubes in the mound  to
     check for  ponding.

•    Keeping deep-rooted plants (shrubs and trees)
     off the mound.

•    Planting  and  maintaining grass  or other
     vegetative cover on the mound surface  to
     prevent erosion  and  to  maximize  water
     uptake.

•    Stand-by power for the pump.

Follow  all  instructions  recommended by  the
manufacturer. All equipment must be tested and
calibrated  as recommended  by  the  equipment
manufacturer. A routine operation and maintenance
(O&M) schedule should be developed and followed

-------
for any mound system in addition to checking local
codes.

COSTS

The cost of a mound system is dependent on design
costs,  energy costs,  the  contractor  used,  the
manufacturers, land, and the characteristics  of the
wastewater. Table 2 lists some typical capital and
O&M  costs  for a  mound  system  serving  a
three-bedroom single home at a flow rate of 450
gpd (150 gallons per bedroom).  Septic tank costs
were estimated at $1 per treated gallon. It should be
noted however, that costs will vary from site to site.
To keep construction costs to a minimum, use good
quality and local materials, when available.

TABLE 2 TYPICAL COST ESTIMATE FOR
   A MOUND SYSTEM (SINGLE HOME)
 Item
    Cost ($)
 Capital Costs
 Construction Costs

    Septic tank (1000 gallon
    concrete tank)

    Dosing chamber (includes
    pump and controls)

    Mound structure
     1,000


     2,000


     6,000
 Total Construction Costs
     9.000
 Non-Component Costs

    Site evaluation

    Permits
      500

      250
 Total Costs
     9,750
 Annual O&M Costs

    Labor @$20/hr.

    Power @8 cents/kWh

    Septic tank pumping
   20 per year

   35 per year

 75 to 150 every 3
	years	
Source: Ayres Associates, Inc., 1997.
REFERENCES

1.      Converse,  J. C. and E.  J. Tyler.  1987a.
       On-Site   Wastewater  Treatment   Using
       Wisconsin Mounds  on  Difficult  Sites.
       Transactions of the ASAE. 1987. American
       Society of Agricultural Engineers, vol. 30.
       no. 2. pp. 362-368.

2.      Converse,  J. C. and E.  J. Tyler.  1987b.
       Inspecting and Trouble Shooting Wisconsin
       Mounds. Small Scale Waste Management
       Project. University of Wisconsin-Madison.
       Madison, Wisconsin.

3.      Converse,  J. C. and E. J.  Tyler. January
       1990. Wisconsin Mound  Soil Absorption
       System Siting, Design, and  Construction
       Manual.  Small Scale Waste Management
       Project. University of Wisconsin-Madison.
       Madison, Wisconsin.

4.      Otis, R. J.  1981. Rehabilitation of a Mound
       System.   On-Site   Sewage   Treatment:
       Proceedings  of  the   Third  National
       Symposium  on  Individual  and  Small
       Community Sewage  Treatment. American
       Society  of  Agricultural  Engineers.  St.
       Joseph, Michigan.

5.      U.S. Environmental  Protection  Agency
       (EPA).  1980.  Design Manual:  Onsite
       Wastewater  Treatment  and  Disposal
       Systems. EPA 625/1-80-012, EPA Office of
       Water.   EPA  Municipal  Environmental
       Research Laboratory. Cincinnati, Ohio.

ADDITIONAL INFORMATION

Mr. Richard J. Otis, Ph.D., P.E., DEE
Ayres Associates
2445 Darwin Road
Madison, WI 53704-3186

National Small Flows Clearing House at
West Virginia University
P.O. Box 6064
Morgantown, WV 26506

-------
The mention of trade names or commercial products
does not constitute endorsement or recommendation
for  use by the U.S. Environmental Protection
Agency.
                                                         For more information contact:

                                                         Municipal Technology Branch
                                                         U.S. EPA
                                                         Mail Code 4204
                                                         401 M St., S.W.
                                                         Washington, D.C., 20460


                                                         IMTB
                                                         Extelence fh tompfance through optfhial tethnftal solutfons
                                                         MUNICIPAL TECHNOLOGY    ~

-------