United States
                   Environmental Protection
                   Agency
Office of
Inspector General
Washington, D.C.  20460
«xEPA         Report of Audit
                            CONSOLIDATED REPORT ON
                       ERA'S COST RECOVERY ACTIONS AGAINST
                         POTENTIAL RESPONSIBLE PARTIES
                             E5EH4-11-0066-61534

                              September 24,  1986

-------
                       AUDIT REPORT E5EH4-11-0066-61534

            CONSOLIDATED REPORT ON EPA'$ COST RECOVERY ACTIONS
                  AGAINST POTENTIAL RESPONSIBLE PARTIES


                            TABLE OF CONTENTS                 PAGE

                             j
SCOPE AND OBJECTIVES 	   1

SUMMARY OF FINDINGS 	   2

ACTION REQUIRED 	   4

BACKGROUND 	   5

FINDINGS AND RECOMMENDATIONS 	   6

1.  EPA NEEDS TO ACTIVELY PURSUE SITES UNDER $200,000 	   6

2.  BANKRUPT POTENTIAL RESPONSIBLE PARTIES IMPACT ON EPA'S
    ABILITY TO RECOVER CLEANUP COSTS UNDER CERCLA 	  13

3.  EPA NEEDS TO COMPLETE NEGOTIATIONS WITH RESPONSIBLE
    PARTIES IN A MORE TIMELY MANNER 	  19

4.  EPA NEEDS TO IDENTIFY AND TRACK STATUTE OF LIMITATIONS
    (SOL) DATES	  25

5.  EPA NEEDS TO IMPLEMENT A COMPREHENSIVE MANAGEMENT
    INFORMATION SYSTEM (MIS) TO TRACK ENFORCEMENT
    ACTIVITIES 	  31

EXHIBITS

  EXHIBIT A - COMPLETED NON-NATIONAL PRIORITY LIST REMOVAL
              SITES WITH CLEANUP COSTS UNDER $200,000 	  35

  EXHIBIT B - SCHEDULE OF COMPLETED REMOVAL ACTIONS ON CLEAN-
              UP COSTS UNDER $200,000 THROUGH SEPTEMBER 30,
              1985 	  36

  EXHIBIT C - COMPLETED NON-NATIONAL PRIORITY LIST REMOVAL
              SITES WITH CLEANUP COSTS BETWEEN $200,000 AND
              UNDER $500,000 IN VALUE THAT MAY NOT BE
              RECOVERED 	  42

  EXHIBIT D - SCHEDULE OF SUPERFUND SITES THAT THERE IS A
              BANKRUPTCY CASE AGAINST POTENTIAL RESPONSIBLE
              PARTIES 	  43

  EXHIBIT E - NEGOTIATIONS AS OF SEPTEMBER 30, 1985 	  45

-------
                            TABLE OF CONTENTS                 PAGE
                                (CONT'D)
APPENDIX 1 — SEPTEMBER 10, 1986 RESPONSE TO DRAFT AUDIT
              REPORT FROM THE ASSISTANT ADMINISTRATOR, OFFICE
              OF SOLID WASTE AND EMERGENCY RESPONSE 	  56

APPENDIX 2 — ADDITIONAL OIG COMMENTS TO OSWER's RESPONSE
              DATED SEPTEMBER 10, 1986 	  61

APPENDIX 3 — DISTRIBUTION OF AUDIT REPORT 	  64

-------
        UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

                       WASHINGTON, D.C. 20460
                                                               OFFICE OF
                                                          THE :NSPECTQR GSNEPAL
MEMORANDUM

SUBJECT:  Audit Report No. E5EH4-11-0066-61534
          Consolidated Report On EPA's Cost Recovery
          Actions Against Potential Responsible Parties
FROM:     Ernest E. Bradley
          Assistant Inspector General for Audit (A-f09)
TO:       J. Winston Porter
          Assistant Administrator for Solid Waste and
            Emergency Response (WH-562A)


SCOPE AND OBJECTIVES

We have completed a review of the Environmental Protection Agency's (EPA)
efforts to have potential responsible parties clean up hazardous waste
sites or pay for the cleanup performed by the Federal government under
the Comprehensive Environmental Response, Compensation, and Liability
Act (CERCLA) of 1980.  CERCLA provides that the parties responsible for
the hazardous waste conditions at disposal sites should either perform
cleanups themselves or reimburse the Government for cleaning up the sites.
The objectives of our review were to:  (1) identify the problems associated
with obtaining reimbursement for removal actions that were funded by the
Hazardous Substance Response Trust Fund (Trust Fund); and (2) determine
whether internal controls were adequate to ensure that EPA was pursuing
all enforcement actions necessary to achieve cost recovery.

We conducted our review at EPA Headquarters and EPA Regions 3 and 4.
Our review covered EPA's cost recovery actions from December 11, 1980
(inception of CERCLA) through September 30, 1985; and Agency policies,
procedures and new Initiatives through May 30, 1986.  Our scope included:

     1.  Reviewing CERCLA policies, procedures, guidance documents and
         other information related to the enforcement of CERCLA;

     2.  Interviewing senior EPA Headquarters and Regional officials, key
         contractor officials, and attorneys from the Department of Justice
         to obtain their views on EPA's hazardous waste site cleanup programs;

-------
     3.  Reviewing monthly financial management reports, quarterly manage-
         ment accountability reports, the legal enforcement docket system,
         and quarterly enforcement accomplishments to determine how effec-
         tive EPA efforts were in having potential responsible parties
         clean up hazardous waste sites or recover cleanup costs; and

     4.  Examining selected case files to determine delays affecting sites
         from progressing towards settlement or cost recovery.

Our review was performed in accordance with the Standards for Audit of
Governmental Organizations, Programs, Activities, and Functions (1981
Revision), as promulgated by the Comptroller General of the United States.
Accordingly, our examination included tests of accounting records and
other auditing procedures we considered necessary in the circumstances.
Deficiencies disclosed as a result of our review are included in the
Findings and Recommendations section of this report.  We have no irrdica-
tion that items not tested would disclose further weaknesses beyond those
described in the Findings and Recommendations section.

This report consolidates the results of our reviews at EPA Headquarters,
Region 3, and Region 4 conducted by the Internal, Mid-Atlantic and Southern
Audit Divisions of the Office of Inspector General.  We issued individual
reports to each of the two Regional Administrators.  The findings and
recommendations developed during our audits of Regions 3 and 4 were previously
discussed with and provided to the appropriate Regional Administrator for
comment.  In addition, the findings and recommendations developed in our
Regional reports and at Headquarters were discussed with appropriate Head-
quarters officials.  Also, we issued a flash report, on September 5, 1984,
alerting the Agency to problems with its enforcement activities.

SUMMARY OF FINDINGS

As of September 30, 1985, EPA had obligated $1.3 billion in Trust Fund
monies.  During this same time period, the Agency had negotiated 84 cost
recovery cases, totaling $26 million, which resulted in the Trust Fund
being reimbursed $14 million from 72 cases.  This represents a cost
recovery ratio of 1.1 percent of total Trust Fund obligations.  This
does not include the Agency efforts in negotiating clean up actions to be
performed by responsible parties, or responsible parties who were not
technically capable of performing a cleanup who paid Into the Trust Fund
to finance the work ("cash out").  Unless EPA becomes more aggressive in
pursuing cost recovery actions, its ability to clean up the nation's
worst hazardous waste sites could be Impeded because the Trust Fund will
not be sufficiently replenished.

Cost recovery activities are becoming Increasingly more important in the
cleanup process.  According to a General Accounting Office (GAO) report
dated May 6, 1986, EPA may need to spend as much 'as $80 billion to clean
up 4,000 of the worst hazardous waste sites over the next 30 years.  EPA
estimates that about half of these sites will be cleaned up or financed
by responsible parties, while the remaining sites will be cleaned up by
using Trust Fund monies.  EPA can replenish the Trust Fund by obtaining
reimbursement for work 1t has completed at hazardous waste sites.  The

-------
funds recovered will allow EPA to increase the number of sites that will
receive attention.  By increasing the number of sites to be cleaned up,
EPA will alleviate the ever increasing hazardous waste threats to the
public and environment.

We found EPA had encountered various problems in replenishing the Trust
Fund, because it was not taking aggressive cost recovery actions.  However,
some of the problems encountered were outside EPA's immediate control.
The issues outside of EPA's control may eventually need to be resolved by
Congress and the courts.  We also found EPA's recovery activities were
hampered because it did not have a coordinated comprehensive systematic
structure for overseeing cost recovery actions.

We found EPA was not aggressively pursuing cost recovery actions against
potential responsible parties where funds expended for cleanup were under
$200,000.  Based on Agency records, we identified 182 completed removal
actions under $200,000, totaling $6,130,209, where cost recovery actions
were not being pursued by EPA.  In addition, we calculated that EPA could
potentially lose over $60 million in the next 20 years if cost recoveries
for removal actions are not pursued.  EPA officials attributed the overall
lack of cost recovery action primarily on resource constraints, and the
fact that the expenditures required to recover costs may approach the
costs of the cleanup itself.  The expenditures incurred by the Agency in
preparing and pursuing a cost recovery action are potentially recoverable
from the responsible parties.  We recognize resource constraints may
limit the number of cost recovery actions.  However, failure to undertake
minimal cost recovery activities or explore alternative methods for recover-
ing costs on sites under $200,000 would adversely affect the Congressional
goal of cleaning up hazardous waste sites.

An issue which was somewhat outside the control of the Agency was potential
responsible parties filing for bankruptcy.  As of September 30, 1985, bank-
ruptcy claims totaled over $65 million.  Of the $65 million, EPA actually
recovered $27,165.  We found that the Agency was not taking aggressive
and timely action in filing for cost recovery when the potential reponsible
party filed for bankruptcy.  This could jeopardize the Agency's ability
to preserve its right as a creditor.  Also, it is especially important for
EPA to establish itself as a creditor, since the courts have been leaning
towards giving Government units first priority after secured creditors.
EPA, by increasing its efforts, may stand.in a better position to recover
funds and be recognized as a first priority creditor.

Even though the Agency had a policy prescribing a 60-day cut-off period
for negotiations, we found 67 percent (276 of 411) of the negotiations
lasted an average of 279 days.  Fifteen of the site negotiations over 60
days, amounting to $3,598,700 in clean-up costs, were concluded without a
settlement or cost recovery reached with potential responsible parties.
Agency officials informed us that the 60-day cut-off period was not
realistic and negotiations are usually lengthy when several responsible
parties were involved.  EPA can improve its monitoring of negotiations
with responsible parties by requiring regional offices to maintain
documentation supporting the continuation of a negotiation and tracking

-------
milestone dates in an information system.  Also, to ensure that established
milestones are met, EPA needs to inform the responsible parties of the
negotiation timefnames.  Thus, if a reasonable settlement did not appear
feasible, negotiations can be broken off and cost recovery pursued through
civil action after EPA cleans up the site.

Historically, there has been considerable confusion over whether a statute
of limitations (SOL) will apply to CERCLA cases.  The Congress may resolve
this issue in the CERCLA reauthorization bill.  However, until this issue
is resolved by Congress or the Federal courts, EPA is at risk.  We identified
65 completed removal actions, totaling $2,917,200, which may violate "tort
law" if not filed on or before December 31, 1986.  EPA officials believe
that this area presents a low risk to the Agency.

Overall, EPA could have a better managed CERCLA enforcement program if it
had a comprehensive management information system (MIS) which would consoli-
date the data now contained in other Agency MISs.  In addition, the new
system should include information on SOL dates, and negotiation milestone
dates which currently are not being collected.  As the number of enforce-
ment actions increase in the future, this system will be crucial to
monitor enforcement activities and ensure all significant milestones are
being met.  EPA will not have the resources or time to manually search
through individual regional project site files or review various MIS
reports to determine the status of enforcement activities.  Realizing the
need for a comprehensive MIS to improve monitoring of CERCLA enforcement
activities, EPA is in the process of developing such a system.

The above audit results are discussed in detail in the "Findings and
Recommendations" section of the report.

The Assistant Administrator (AA) for Solid Waste and Emergency Response
provided formal written comments on our draft audit report in a memorandum
dated September 10, 1986.  The AA generally agreed with our recommendations
and indicated that over the next several months the Agency will be reviewing
and revising its Superfund policies and procedures.  We have summarized the
AA's position to appropriate locations in the report and included the complete
response as Appendix 1.  We also discussed the results of our audit with
senior officials of the Office of Solid Waste and Emergency Response and the
Office of Enforcement and Compliance Monitoring on July 10, 1986.

We realize that the proposed Superfund bill will bring about some changes
regarding the issues discussed in the report.  However, EPA would continue
to have responsibility to clean up hazardous waste sites.  Therefore, we
believe that EPA will continue to need a sound enforcement program.  We
made this review to determine how the Agency could more effectively
manage its CERCLA enforcement program.

ACTION REQUIRED

In accordance with EPA Directive 2750, the action official is required to
provide this office a written response to the audit report within 90 days
of the audit report date.  The Action Official's response should include
an action plan with specific milestone dates for each corrective action
that was not fully implemented.

-------
BACKGROUND

On December 11, 1980, Congress enacted the Comprehensive Environmental
Response, Compensation, and Liability Act of 1980 (Public Law 96-510).  This
Act, commonly known as Superfund, provides for liability, compensation,
cleanup, and emergency response for hazardous substances released into the
environment and uncontrolled and abandoned hazardous waste sites.  Superfund
broadly defines two types of response actions:  removal and remedial.
The former term represents relatively short-term responses, while the latter
represents actions of longer duration leading to permanent resolution.

To fund removal and remedial actions, title II, subtitle B, established a
$1.6 billion Trust Fund to help clean up these sites.  The Trust Fund was
to be collected over a 5-year period from taxes on petroleum and certain
chemicals and from Federal appropriations.  Further, CERCLA requires that
parties responsible for the hazardous conditions at the sites either perform
the cleanups themselves or reimburse the Government for cleaning up the
sites.

EPA's enforcement authority to recover the costs of cleanup activities
performed by the Government comes from sections 106 and 107 of CERCLA.
Section 106(a) of CERCLA authorizes the issuance of". . . such orders as
may be necessary to protect public health and welfare and the environment."
Section 107 provides that, "past and present owners and operators of a
site, and generators and transporters who contributed hazardous substance
to a site, shall be liable for all costs incurred by the U.S. Government,
a state, or any other person, and for damages to or loss of natural
resources."

The Office of Waste Programs Enforcement (OWPE) and the Office of
Enforcement and Compliance Monitoring (OECM) are the Headquarters offices
responsible for overall management of the CERCLA enforcement programs.  OWPE
provides policy direction to the regions for waste enforcement activities.
In addition, OWPE develops objectives, strategy, programs, and evaluation
criteria for regional enforcement programs.  OECM is responsible for:  (1)
developing national policies and procedures for uniform, fair and appropriate
enforcement of the environmental statutes and regulations; (2) monitoring
implementation of national policy by the regional offices; and (3) reviewing
for quality the legal and factual development of those cases which, because
of national or precedential significance, are referred to Headquarters from
the regions prior to referral to the Department of Justice.  Because EPA
is decentralized, the majority of EPA CERCLA actions are the responsibility
of the regions.  Thus, Headquarters plays more of an oversight role while
the regions actually carry out the program objectives.

CERCLA enforcement actions can occur at different points in the cleanup
process and Involve both regional and Headquarters program offices.  This
creates difficulty in identifying and tracking milestones of CERCLA enforce-
ment activities.  In general, the following actions occur once a responsible
party Is identified:  (1) EPA attempts to negotiate with the responsible
party(ies) in order to reach a settlement for cleaning up the site; and (2)
if a settlement was not reached, EPA can cleanup the site with Federal funds
funds and seek to recover the cost of cleanup later.

-------
FINDINGS AND RECOMMENDATIONS

1.  EPA NEEDS TO ACTIVELY PURSUE SITES UNDER $200,000

The Agency was not aggressively pursuing cost recovery actions against
potential responsible parties where funds expended for cleanup were under
$200,000.  Despite a recent policy authorizing the regions to negotiate
with potential responsible parties for settlements, the extent of EPA's
pursuing these cases was questionable due to the higher priority given to
large dollar sites.  As of September 30, 1985, we identified 182 non-National
Priority List (NPL) completed removal actions, totaling $6,130,209, where
funds may never be recovered if cost recovery actions are not pursued.  EPA
officials believe that the costs associated with these site costs may never
be recovered because the Agency resources needed to recover the expenditures
may outweigh the actual costs recovered.  We understand that resource con-
straints may limit EPA's pursuit of all hazardous waste sites.  However,
EPA's failure to pursue sites under $200,000 would ultimately impact on
EPA's replenishing the Trust Fund and would send a signal to potential
responsible parties that the Agency was not serious about recovering
site cleanup costs.  We calculated that EPA could potentially lose over
$60 million in the next 20 years if cost recoveries for removal
actions are not pursued.  In addition, projected increases in hazardous
waste sites may only increase the likelihood of cost recovery efforts not
being taken on sites under $200,000.  EPA's policy could adversely
affect the Congressional goal of cleaning up hazardous waste sites.

EPA Needs To Take Aggressive Action To Recover Over $6.1 Million In Trust
Fund Expenditures'                                                       ~~

We identified the total number of completed Superfund sites with expendi-
tures under $200,000, from the inception of CERCLA through September 30,
1985.  Also, we reviewed EPA's efforts to pursue cost recovery actions
for these sites.  We limited our analysis to removal sites since these
sites are generally intended for shorter-term responses to releases of
hazardous substances and are generally limited by CERCLA section 104 to
six months in duration and $1 million.  We requested and received from
the Emergency Response Division (ERD) and the Office of Program Management
(0PM) the names of all sites with completed removal actions on or before
September 30, 1985.  We found that EPA had completed 376 non-NPL removal
actions, totaling $76,534,439 in obligations, through September 30, 1985.
Of the 376 removal actions, we found 248 removal actions (66 percent),
totaling $11,474,856, which were under $200,000 in cleanup costs (refer
to Exhibit A).  Our review further disclosed that 182 of the 248 sites
were not being pursued by EPA for cost recovery.

Section 107 of CERCLA provides that past and present owners and operators
of a site, and generators and transporters who contributed hazardous
substances to a site, may be held liable for all costs of removal and
remedial actions undertaken by the United States, a state or any other
person.  The Federal government can attempt to recover cleanup costs in
a lawsuit or, if the circumstances favor 1t, can agree to a settlement
with the responsible parties.  The settlement would normally require the
responsible parties to voluntarily reimburse the Trust Fund (and possibly
others) for cleanup costs incurred.

-------
Based on the data reflected in the Agency's information systems, we
reviewed the extent of EPA's pursuit of cost recovery on sites under
$200,000.  During our review of Region 3, we identified 63 sites (as of
September 30, 1984), totaling $2,240,134, where cleanup costs were under
$200,000.  In determining whether EPA was actively pursuing cost recovery
for these sites, we found that 18 of the 63 sites were completed non-NPL
removal actions costing under $200,000.
                               i
Our review of the 18 completed removal actions disclosed that Region 3 had
taken action to recover cleanup costs from responsible parties in four
instances.  For two of these four actions, Agency expenditures totaled
$71,340 while the settlements resulted in recoveries of $58,504.  The
Region referred to Headquarters for action the remaining two removal
sites, totaling $255,756.  Regional  personnel  informed us that no actions
were currently planned to recover any costs from responsible parties for
the remaining 14 completed sites, totaling $728,822.

Region 3, in its response to our Regional report, indicated that the
remaining removals were not referred for cost  recovery because there were
no viable responsible parties associated with  the removals.  We requested
Region 3 to provide us with documentation that no viable responsible parties
existed.  On- July 28, 1986, the Regional Administrator (RA) responded to
our Region 3 report with a follow-up memorandum.  In his response the
RA indicated that action is still ongoing at approximately half of the
sites which originally had no viable parties.

In Region 4, we identified 37 removal sites (as of September 30, 1984), •
totaling $1,726,888, where site expenditures would not exceed $200,000.
We reviewed the Agency's records and found that 24 of 37 sites, totaling
$958,288, were completed removal actions under $200,000.  Cleanup activity
at the 24 sites had been completed for several months.  However, negotia-
tions with the responsible parties for cost recovery were not scheduled.
For example, removal activity was completed at J&L Drum, TN in October 1982
at a cost of $44,015.  Removal work at Caldwell County, NC was completed
in July 1983 at a cost of $39,990.  However, cost recovery action had not
been initiated or planned at these sites at the time our fieldwork was
completed.

Regional officials attributed the overall lack of cost recovery action on
sites under $200,000 primarily to resource constraints and existing policy
guidance which discouraged cost recovery action on sites under $200,000.
Regional officials further explained that other factors such as strength
of evidence, financial viability of the responsible party, risk of litigation
and amount of funds involved also Influenced their decisions regarding
pursuit of cost recovery actions.

We reviewed the Office of Waste Programs Enforcement (OWPE) and the
Office of Enforcement and Compliance Monitoring (OECM) management reports
to determine whether the Agency was pursuing cost recovery actions on the
248 removal actions we Identified as of September 30, 1985.  Our review
of the OECM's Docket System, OWPE's Case Management System, Superfund
Comprehensive Accomplishment Plan (SCAP) and the Removal Tracking System
disclosed that the Agency was not pursuing cost recovery actions on 182
removal sites EPA-wide, amounting to $6,130,209.  (Refer to Exhibit B.)

-------
Confusion Exists Over How to Handle Small Cost Recovery Cleanup Actions

To provide more cost effective methods of settling cost recovery claims,
EPA issued a policy entitled "Interim CERCLA Settlement Policy," dated
December 5, 1984, which stated, in part that:

     "The Regions are authorized to conclude settlements in certain
     types of hazardous waste cases on their own, without prior review by
     Headquarters or DOJ.  Cases selected for this treatment would normally
     have lower priority for litigation.  Categories of cases not subject
     to Headquarters review include negotiation for cost recovery cases
     under $200,000, and negotiation of claims filed in bankruptcy.  In
     cost recovery cases, the Regions should pay particular attention to
     weighing the resources necessary to conduct negotiations and litigation
     against the amounts that may be recovered, and the prospects for
     recovery.  . ."

     "Specific details concerning these authorizations will be addressed
     in delegations that will be forwarded to the Regions under separate
     cover.  Headquarters is conducting an evaluation of the effectiveness
     of existing delegations and is assessing the possibility of additional
     delegations."

Prior to issuing the Settlement Policy, the Agency generally pursued
cost recovery actions only on sites where total cleanup costs exceeded
$200,000.  While the December 5, 1984, Settlement Policy authorized the
regions to negotiate settlements with potential responsible parties where
total cleanup costs did not exceed $200,000, Headquarters never delegated
authority to the regions to actually approve and sign settlement agreements.
We also noted that the Settlement Policy stated that priority should be
given to sites where cleanup costs exceed $200,000.

In our review of Region 3, CERCLA Removal Enforcement Section personnel
stated there was a target on case referrals sent to Headquarters annually
for cost recovery, and these referrals were limited to sites over $200,000.
This target was established in the Agency's Strategic Planning and Manage-
ment System (SPMS).  As a result, the Enforcement Section's priority was
to refer sites over $200,000 to Regional Counsel for review and subsequent
referral to Headquarters.  Furthermore, Region 3 personnel stated that
sites under $200,000 were not referred to Regional Counsel because the
OECM and the Department of Justice (DOJ) normally will not pursue cost
recovery actions on any site under that amount.  However, OECM personnel
told us that SPMS does not limit case referrals to sites over $200,000
and they had never refused to pursue a case for cost recovery, although
they admitted that higher priority is placed on sites over $200,000.

The EPA Administrator, in a February 13, 1985, speech indicated that EPA
must pursue cost recovery actions.  The following indicated the direction
he planned:
                                    8

-------
     "Let's remember that EPA's mission is progress in achieving
     environmental improvement.  We achieve that progress by setting
     sound standards and enforcing them.  The regulated community must
     know that we are committed to assuring this progress.  We encourage
     them to help us move forward on a voluntary basis.  But where they
     are unwilling, we will vigorously enforce our laws and our standards.
     ...   It will be our policy to take action to recover all costs
     incurred by government in'Superfund response actions."

On July 12, 1985, OECM and the Office of Solid Waste and Emergency Response
(OSWER) jointly issued a memo to the regions addressing small  cost recovery
referrals.  The memo stated:

     "Based on discussions among our staff and Regional enforcement
     personnel, it appears that confusion exists regarding Agency policy
     on referring CERCLA cost recovery cases valued at less than $200,000.
     . . .  Although the Agency has placed a higher priority on referring
     cost recovery cases with expenditures in excess of $200,000, there are
     situations where referring small cost recovery actions is entirely
     appropriate.  For example, where we have initiated settlement discus-
     sions which have failed to produce a settlement because of the
     recalcitrance of the responsible parties, referral would  generally
     be appropriate to demonstrate the Agency's commitment toward enforce-
     ment as a vehicle to compel private party response at CERCLA sites.
     In addition, where a region has no case for more than $200,000, where
     an enforcement presence would serve a deterrent effect, where a
     Region's other enforcement priorities allow for the expenditure of
     resources to support a small cost recovery case, or where the circum-
     stances are ripe for testing some important aspect of law, referral
     of such as case would be appropriate."

While this memo showed that Headquarters intended the regions  to pursue
small cost recovery cases under $200,000, at the time of our review the
regions had not received formal delegation from Headquarters to implement
this guidance.  In addition, Region 4 stated in its response to our April 18,
1986 audit report:

     "As, 01G is aware, the Headquarters policy has been and continues to
     be that, generally cost recovery referrals are a low priority at
     sites where "minor" costs have been incurred (previously  $200,000,
     now proposed as $500,000 under the October 4, 1985 draft  CERCLA
     settlement policy).  The basis for this policy, including resource
     constraints and cost-effectiveness has been articulated in several
     Headquarters policy documents."

Apparently, from these comments confusion still exists as to how to
handle sites under $200,000.  EPA plans to raise the dollar limit to
$500,000 for small case recovery cleanups.  In our opinion, this would
further compound the problem since the number of completed sites and the
resulting dollar values would Increase.  For example, as of September 30,
1985, the number of completed removals between $200,000 and $500,000
totaled 19, with a dollar value of $5,761,002, that may not be recovered
(Refer to Exhibit C.)

-------
A major obstacle faced by EPA was that it could not compromise Section 107
cost recovery actions if they exceed $20,000 or if the settlement resulted
in the Agency recovering less than 100 percent of incurred costs.  CERCLA
does not authorize EPA to compromise cost recovery claims.  The only other
statutory authority under which EPA may compromise claims of the United
States is the Federal Claims Collection Act of 1966.  According to the
law, if EPA wants to settle a claim for less than 100 percent, or that is
over $20,000, the settlement must be referred to DOJ for final approval.
For this type of recovery action the regions must refer the settlement
package to EPA Headquarters for concurrence and then Headquarters will
refer the package to the DOJ.  In discussions with an OECM official  he
stated that this procedure was causing an added burden to the Headquarters
staff.

As previously mentioned, EPA was not actively pursuing sites where costs
expended from the Trust Fund were under $200,000.  We discussed this issue
with both Regional and Headquarters senior management.  Region 3 officials
emphasized that OSWER personnel had verbally instructed them not to pursue
sites under $200,000.  OWPE informed us that some sites either do not
have a viable responsible party or a potential responsible party can not
always be found.  In addition, senior Headquarters representatives from
both OWPE and OECM informed us that these costs were not actively pursued
since resource constraints often limited EPA's cleanup efforts to higher
priority or large dollar (over $200,000) sites.  In the early years of
the Superfund program, EPA was faced with a huge number of existing and
threatening hazardous substance releases and the need to conserve and use
Trust Fund resources most efficiently.  As a result, EPA targeted its
enforcement resources on those sites where there was a greater likelihood
of successful action.  We recognize that EPA's pursuit of all hazardous
waste sites may not be a prudent decision in light of limited resources.
However, in our opinion, failure to even undertake minimal cost recovery
activities in pursuing cost recovery for these sites increases the potential
of responsible parties avoiding their liability and this will consequently
impact on the amount of funds available for cleanup of hazardous waste sites,

Future Impact On The Trust Fund

In December 1984, as required by Section 301 (a)(b)(c) of CERCLA, EPA
submitted a report to Congress projecting the size and focus of the
Superfund program and future funding needs.  According to the study, EPA
assumed that:  (1) there were about 25,000 hazardous waste sites; (2) 2,500
of these 25,000 would be NPL sites; and (3) cost recovery from responsible
parties would be at a rate of 47 percent for removals.  We estimated the
future dollar impact of the Agency's policy on the Trust Fund by identifying
the Agency's projections for the future number of removals and the average
dollar amount involved for removals under $200,000.  The following informa-
tion and assumptions used in the calculation came from EPA's Section 301
study.

EPA's Section 301 study predicted that 190 removals will be performed each
year.  One hundred and fifteen of these removals will be at non-NPL sites
and will average less than $200,000 per site.  Based on historical data
                                    10

-------
we calculated that potentially over $60 million will be lost to the Trust
Fund in the next 20 years if cost recoveries for removal  actions under
$200,000 continue to be ignored.  Presented below is our calculation.

     0 190 removals per year - 30 NPL removals = 160 non-NPL removals

     0 160 non-NPL removals x 72 percent (removals under $200,000)  =
       115 removals under $200,000
                               t
     0 115 removals per year under $200,000 x $49,532 average cost  of a
       removal = $5,696,180 per year

     0 $5,696,180 per year x 20 years of removal activities = $113,923,600

     0 $113,923,600 x 53 percent nonrecovery rate = $60,379,508

This calculation did not take into account any increased cost for inflation
over the 20 year period.  Further, the recovery rate of 47 percent  assumed
by EPA may be too high.  For example, GAO in a March 29, 1985, report stated
that the figure of 47 percent for cost recovery for removals was an optimistic
assumption based on what EPA hopes to accomplish rather than the actual 21
percent rate experienced for removals to date.  We discussed this calculation
with OERR's Chief, Office of Program Management and he stated that  the calcula-
tion was reasonable.

Alternative Methods of Pursuing For Cost Recovery Would Permit Recovery
While Saving Resources

Given the number of incidents or sites at which EPA had spent Trust Fund
monies, cost recovery cases have the potential to severely drain Agency
and DOJ enforcement resources.  While the Agency is authorized to seek
recovery of all Trust Fund monies, the costs associated with case referral,
case preparation and litigation for cases involving removal or small remedial
actions in some cases may approach the cost of the cleanup itself.   In order
to use Agency resources effectively the Agency needs to explore alternative
methods for pursuing cost recovery actions.

In a March 1986 article entitled:  The Need for Innovative Environmental
Enforcement, the Acting Assistant Administrator for OECM indicated that
alternative approaches are available for EPA to pursue cost recovery
claims.  In the article he stated the following:

     "EPA can make more effective and efficient use of its existing
     resources by exploring other means of bringing and resolving
     enforcement actions, and making the present system more efficient.
     . . . Some of these cases could be handled by arbitration.  An
     example of this type of case, in which the need for arbitration is
     more apparent, are cost recovery cases under Section 107 of the
     CERCLA ....  EPA and the regulated community must be willing to
     depart from the traditional judicial and administrative enforcement
     procedures in some cases - especially those under CERCLA - in favor
     of generally - accepted alternative procedures which promise economies
     of time, money and other resources.  Arbitration, both binding and
     non-binding, and mediation would seem to be highly suitable
     alternatives."
                                    11

-------
We discussed with EPA officials the use of arbitration as one alternative
to pursuing cost recovery actions in court.  Regional Counsel in Region 3
informed us that filing a cost recovery action in court is a more viable
option, since arbitration has no precedential value.  Furthermore, they
would not like to see the resolution of cases put into the hands of an
arbitration board.  Region 4 officials, while reacting favorably to the
concept of an arbitration board, expressed reservations about the ability
of an arbitration board to negotiate settlements if there were several
responsible parties involved or if the responsible parties deny liability.
Some Headquarters legal officials believe that, while arbitration eliminates
the need to go to court and reduces litigation costs, the process is still
time consuming for the region and settlements are generally reduced.  However,
we believe that arbitration should be pursued in the absence of any other
action being taken.

In addition, we discussed the possibility of giving these cases to'private
attorneys outside the Agency on a contingency basis for fees.  OECM
officials told us this may be a viable solution to reducing the impact on
EPA attorney resources.

Conclusion

We recognize that all hazardous waste sites may not be actively pursued
where cost recovery from responsible parties is required.  While resource
constraints and pursuit of high dollar sites may be conserving the Trust
Fund, we believe that the Agency should take a more active role in pursuing
sites under $200,000.  EPA should make every effort to negotiate with
responsible parties to recover cleanup costs.  We believe that a reasonable
effort should be made to recover costs on all sites.  Agency management needs
to evaluate the cost of pursuing cost recovery actions in court against the
prospect of actually recovering costs.  Agency management also needs to
include in its evaluations the fact that costs incurred for cost recovery
actions are potentially recoverable.  As the number of hazardous waste
sites increases, EPA must aggressively pursue cost recovery to ensure
replenishment of the Trust Fund.

OSWER Comments And 016 Evaluation

The Assistant Administrator for OSWER will take our recommendations into
consideration when updating Agency policies and procedures.  The Assistant
Administrator further stated that the new Superfund bill expressly allows
for alternative dispute resolution procedures.  In addition, the AA stated
that the new bill would give EPA administrative authority to pursue cost
recovery actions under $500,000, and it should not be necessary to hire
outside attorneys.  We believe 1f the proposed new law gives Superfund
the authority to handle cases under $500,000 through administrative
means, the Agency will be in a better position to pursue cost recovery
actions.  However, since the Agency has limited personnel resources and
priority may still be given to high dollar cases, we still believe that
outside attorneys on a contingent basis will be of benefit to the Agency.
                                    12

-------
Recommendations

We recommend that the Assistant Administrator for the Office of Solid
Waste and Emergency Response:

     1.  Require that minimal cost recovery actions (e.g., notification,
         demand letters) be pursued for sites where funds expended are
         under $200,000.  Also, Headquarters should weigh the costs to be
         incurred for litigation versus the costs to be recovered before
         pursuing a cost recovery action.

     2.  Develop and issue specific policies, procedures and negotiating
         strategies for settling cases under $200,000 ($500,000) to the
         regions to ensure a consistent Agency approach.

     3.  Examine the possibility of using an arbitration board or some
         similar mechanism as an alternative to filing cost recovery
         actions in court.

     4.  Pursue the possibility of giving cost recovery actions under
         $200,000 to outside attorneys on a contingency basis for fees.

2.  BANKRUPT POTENTIAL RESPONSIBLE PARTIES IMPACT ON EPA'S ABILITY TO
    RECOVER CLEANUP COSTS UNDER CERCTA"

EPA may not recover millions of dollars spent for cleanup activities at
hazardous waste sites because some potential responsible parties (PRPs)
file for bankruptcy.  During our review, we identified 22 ongoing sites
with cleanup costs in excess of $65.2 million, from the inception of CERCLA
through September 30, 1985, where costs may not be recovered because of
potential responsible parties filing for bankruptcy.  Of the $65 million,
EPA had actually filed claims against bankrupt parties for over $57 million.
Of this, EPA was awarded $47,859, of which $27,165 was received on 2 of the
22 bankruptcy cases.  The Agency needs to make improvements in two areas:
filing for cost recovery actions against bankrupt parties and establishing
a system to identify bankrupt parties.  Improvements in these two areas
would enhance EPA's cost recovery efforts.  Due to the uncertainty which
surrounds the bankruptcy issue, as well as the potential of PRPs to avoid
their responsibilities, the Agency must take aggressive action during the
early stages of the bankruptcy proceedings.  This will place the Agency
in a better position since Its claims conceivably could be classified as
a first priority claim (I.e., administrative expenses) under bankruptcy
rules.

The OECM is responsible for pursuing legal enforcement actions against
bankrupt parties.  EPA regional offices are responsible for developing and
referring bankruptcy cases to OECM.  To assist the regions in developing
CERCLA enforcement actions against bankrupt parties, OECM issued, "Guidance
Regarding CERCLA Enforcement Against Bankrupt Parties," on May 24, 1984.
This policy encourages consistency in current and future bankruptcy cases
brought by EPA.  The guidance provides, 1n part:  (1) a discussion of
enforcement theories available to the Agency to pursue bankrupt parties
under CERCLA; and (2) an overview of the relationship between cost recovery
under CERCLA and bankruptcy law.  Currently, a new procedure is being
circulated for review.
                                    13

-------
The Bankruptcy Reform Act of 1978, commonly referred to as the Bankruptcy
Code, states that a claim may be based on a right to payment as a result
of work completed and cost incurred.  There are two types of bankruptcies,
(Chapter 7 and Chapter 11) that a corporation can seek.  Chapter 7 bank-
ruptcy is when a corporation actually "walks out" and quits its business.
This usually happens because liabilities outweigh the assets and the
corporation does not plan to reorganize.  The corporation can accomplish
this by placing itself in a Chapter 7 bankruptcy with the approval  of the
court, or it can be forced into it by its creditors with court approval.
Thus, the assets are used to pay off creditors.  In a Chapter 11 bankruptcy
the corporation plans to continue its business and have debts previous to
its bankruptcy request worked out with its creditors during the reorganiza-
tion phase.  The corporation will actually be paying current business costs
during the period as an ongoing business while it is in negotiation for
payment of previous debts.  In both types of bankruptcies the court is
involved as well as the creditors.

Under section 507 of the Bankruptcy Code, the claims of secured
creditors (i.e., repayment of loans) are satisfied fully before assets
are distributed to any unsecured creditors.  Section 507 also sets up the
priority structure for the satisfaction of unsecured claims.  The priority
order for such claims are:

     1.  Administrative expenses  .  . . and any fees and charges assessed
         against the estate . . . ;

     2.  Unsecured claims allowed under section 502(b) of the Bankruptcy
         Code (certain claims arising in involuntary cases);

     3.  Allowed unsecured claims for wages, salaries, or commissions,
         including vacations, severance and sick leave pay;

     4.  Allowed unsecured claims for contributions to employee benefit
         plans;

     5.  Allowed unsecured claims of individuals, to the extent of $900
         . . .  ; and

     6.  Allowed (certain) unsecured (tax or penalty fee) claims of
         Governmental units.

Under the Bankruptcy Code it appears that an EPA claim would be classified
as a sixth priority claim.  However, in a recent bankruptcy case, T.P.
Long Chemical,  Inc. (Case No. 581-906), the Ohio Federal District Court
classified cleanup costs as administrative expenses or a first priority
claim under the bankruptcy rules.  Thus, this ruling has placed the
Agency in a better position to. recover cleanup costs.  Region 5 Regional
Counsel's response to this opinion states that:
                                    14

-------
     "This ruling is significant in that it is the first time to my
     knowledge that a Bankruptcy Court has held that expenses of an
     environmental cleanup under CERCLA are administrative expenses of
     the bankruptcy's estate.  While the court did not allow the Agency
     to stand ahead of perfected secured interest holder, the classifi-
     cation of Government cleanup costs as administrative expenses places
     the claim of the Agency well ahead of most creditors."

Current Status Of Agency Bankrupt Actions

We requested from the Acting Associate Enforcement Counsel for Hazardous
Waste Enforcement at Headquarters, a status report on CERCLA bankruptcy
actions.  We wanted to determine (1) the number and dollar value of
bankruptcy cases being pursued by the regions, and (2) the amount of
funds that had been recovered from bankrupt parties.  OECM provided us
with a status report of CERCLA bankruptcy actions as of September 30,
1985.  We also used a Financial Management System report to determine
the recovered amount (refer to Exhibit D).  These reports disclosed the
following:

     1.  The Agency identified 22 bankruptcy cases, totaling $65,150,841;

     2.  The Agency had actually filed claims against the above bankrupt
         parties for $57,245,705; and

     3.  The Agency, while awarded $47,859, had actually recovered
         $27,165 in cleanup costs from 2 of the 22 bankrupt cases,
         as of September 30, 1985.

As shown above, the Agency had filed 22 bankrupt cases; yet, the Agency
had not been very successful in recovering costs.  We discussed the
results with OECM personnel who told us that the Agency would rather use
its resources against a PRP with adequate resources.  However, we believe
that the Agency must be able to balance its actions against PRPs among
viable and less viable parties so that industry will note that EPA will
pursue all cost recovery actions to the fullest extent possible.

Management Of Bankruptcy Cases

The Agency was not taking aggressive and timely action in filing for cost
recovery when the PRP had filed for bankruptcy.  This can result in the
Agency not being able to preserve its right as a creditor.  In addition,
EPA did not have an effective monitoring system to determine if and when
a PRP goes bankrupt.  This is critical since EPA would only have a limited
time in which to present its claim.

     Filing For Cost Recovery

The primary objective of cost recovery is to provide reimbursement of
expenditures to the Trust Fund.  A second objective is to encourage
voluntary actions by responsible parties.  EPA's cost recovery strategy
generally calls for the initiation of cost recovery efforts as soon as
total costs are known.
                                    15

-------
The Agency must establish itself as a creditor.  If this is done, the
Agency will legally put the responsible party on notice that it expects
payment and if the PRP goes bankrupt, EPA would be on file as a creditor.
Thus, EPA would receive notice of bankruptcy (order of relief) and other
creditor's notices which are important so that it will know the status of
the proceedings.

In a January 30, 1985, memorandum entitled " Procedures for Documenting
Costs for CERCLA Section 107 Actions" the Director, OWPE stated that, "It
is the Agency's intention that some type of action be taken to recover
expenses for every site where Federal money was expended.  The Agency
plans to have all cases dealt with in a timely and efficient manner."  To
accomplish this Headquarters should refer the bankruptcy claim to the
Department of Justice for filing by a specific due date or a special
exception must be requested.  Prompt referral of bankruptcy cases is
necessary to preserve the Agency's claim as a creditor.  The Agency has
to file a "proof of claim" to be assured of preserving its rights as  a
creditor.  The proof of claim under a bankruptcy may be the only remedy
left for the Agency to recover funds from a bankrupt PRP.

An April 7, 1986, article in the Legal Times entitled "DOJ Gets More
Aggressive in Chapter 11 Cases" contained a comment made by Associate
Deputy Attorney General Jay B. Stephens.  He stated:

     "... that the Justice Department finally has awakened to the
     realization that "there are great potential dollars our there: for
     the government to collect.  Previously, he said, "competing interests"
     and priorities have kept the department and its prosecuters from
     focusing on bankruptcy matters."

With this in mind, EPA should be aggressive in seeking reimbursement  for
cleaning up sites, especially in the early stages when the PRP is filing
for bankruptcy.  We believe that if the case is pursued early, a more
favorable outcome may result since the Agency would have established  the
priority of its claim in relation to other creditors.

EPA recognizes the need to pursue judicial actions against bankrupt parties.
However, even if EPA finds a responsible party to be financially sound at
the time identified, there is no guarantee that the PRP will not file for
bankruptcy at a later date.  Consequently, an OECM attorney believes  that
while a cost recovery action can be initiated before completion of a
remedial investigation/feasibility study, this would not preclude a
responsible party from declaring bankruptcy to avoid liability.

     The Need For Aggressive Action Against Bankrupt Parties

EPA needs to file claims against PRPs as soon as possible in order for
the Agency to reserve its right to recover claims on costs associated
with site cleanup of bankrupt parties.  If EPA does not file a claim and
the bankrupt party does not place EPA on its creditors list, the Agency
may lose its creditor status.  This would occur because the court would
not know that EPA is a creditor.  Thus, no distribution of any available
                                    16

-------
funds could be made to EPA.  Also,  if EPA does not file or files in later
stages of bankruptcy, there is the  possibility of:  (1) abandonment of the
site; (2) other administration costs "eating up"  the assets;  (3) and the
sale of assets at "fire sale" prices, or other methods to dilute the assets
prior to and during the bankruptcy.  This could be done without EPA having
a say in the matter.  In addition,  an aggressive  stand against bankrupt
parties may bring out more PRPs that will  absorb  the cost of  cleanups or
catch fraudulent schemes.  For-example, in a recent bankruptcy declaration,
(Thomas Solvent Co. (TSC)). the U.S. has filed a  CERCLA section 107
complaint to recover cost associated with site cleanup.  Part of the new
case will be against Richard Thomas, individually, and four corporations
which were "spun-off" from TSC prior to TSC's bankruptcy.

A major obstacle faced by EPA was when does it become a creditor.  We
discussed this issue of EPA's rights to claim as  a creditor with an
attorney from OECM.  We asked when  is EPA "officially" a creditor so that
it will be necessary for the bankrupt party to list the Agency as a creditor,
The OECM attorney stated that some  PRPs interpret it to be at the time of
a demand letter, while others do not.  Further, when EPA sends out a demand
letter, the letter should state that EPA is an official creditor.  The
attorney also stated that EPA is supposed to be notified when a PRP goes
bankrupt.  However, if a responsible party does not "interpret" EPA to be
a creditor, EPA may not be notified.  If EPA is not notified  of a PRP's
bankruptcy filing, it will not be able to file a  claim in sufficient time
to preserve its right of claim.  Further, a PRP could go bankrupt and EPA
could have no knowledge of this. We were also told that to develop a
system that EPA would know if PRP goes bankrupt would be difficult since
a party could be bankrupt in many different states and districts.

Under a Chapter 7 bankruptcy, as explained in the June 30, 1985, memorandum
entitled, "Procedures for Documenting Costs for CERCLA § 107  Actions," a
claim must be filed within 90 days  from the first meeting of  the creditors
unless an extension is moved for or granted.  Under Chapter 11 a claim must
be filed by the date set by the court.  However,  to file a claim timely,
EPA must know the date that a proof of claim has  to be filed.  It is
important that EPA becomes aware of any PRP bankruptcies and  acts in a
timely manner.  As previously stated, EPA needs to be aware of a bankruptcy
at the earliest stage so that it can attend creditors meeting and thus be
able to support Its position effectively.  If the Agency does not become
aware of bankruptcies early or does not act in a  timely manner, the poten-
tial for recovering costs lessens.

EPA Does Not Have An Adequate System To Determine
When A PRP Goes Bankrupt'

We found that there was no list of  all PRPs.  Thus, when EPA  is notified
of a PRP filing for bankruptcy, it  had no listing to refer to.  It is
important that the Agency place more emphasis on  these bankrupt parties
since it may be the last chance in  which the Agency can preserve its
rights.  This 1s the only way the Agency can establish its priority on
the distribution of the debtor's estate.
                                    17

-------
EPA did not have a system in place to determine if a PRP files for
bankruptcy.  The court will only notify EPA when a PRP files for bank-
ruptcy if EPA is listed as a creditor by the bankrupt party.  In those
cases where the court notified EPA that the PRP was filing for bankruptcy,
EPA did not have adequate policies and procedures to take the necessary
action to establish the priority of its claim in relation to other
creditors.  As a result, when a notice came in, EPA did not know to who
it should go.  OGC is developing new procedures to ensure that the Agency
can respond in a timely manner.  It is necessary that the Agency's
attorneys:  (1) receive notification of all PRP bankruptcy claims, and
(2) be notified when a PRP sends bankruptcy notices to creditors.  The
Agency needs to be on record as a creditor in sufficient time so that it
can attend the meeting of creditors (usually not less than 20 or more
than 40 days after the order of relief).  Also, the Agency's attorney
handling a bankruptcy case must be able to receive any notices sent to a
creditor on a timely basis so that he/she can respond within the time
stated on the notice.

CONCLUSION

The intent of the enforcement program is to compel responsible party clean-
up of hazardous waste sites or to have them pay for cleanups performed by
the Government.  In our opinion, responsible parties declaring bankruptcy
impacts on funds available for cleanup of other sites.  We believe that
EPA should be more aggressive in filing early claims against responsible
parties.  By increasing its effort, EPA may stand in a better position to
recover funds earlier, and potentially prevent the PRP from declaring
fraudulent bankruptcy.  In addition, failure to aggressively recover cost
expended from the Trust Fund will not only reduce the number of hazardous
waste sites that EPA could clean up, but also demonstrate to PRPs that they
can avoid reponsibilities by filing for bankruptcy.

OSWER Comments And PIG Evaluation

In response to the draft audit report, the Assistant Administrator
indicated that OSWER will review and revise the Bankruptcy guidance
regarding timeliness of actions and procedures for establishing EPA
claims.  In addition, OSWER will consider revising the demand letters to
include appropriate official creditor language.  OSWER did not comment on
our recommendation concerning priority of claims.

RECOMMENDATIONS

We recommend that the Assistant Administrator for Solid Waste and
Emergency Response:

     1.  Use more explicit language in the demand letter identifying EPA
as an "official creditor", thus no interpretation of the demand letter
will be required by the PRP;

     2.  Establish procedures on how to take the necessary action(s) to
establish EPA's priority claim in relation to other creditors;
                                    18

-------
     3.  Coordinate with the Office of General  Counsel  on developing new
procedures and a system that will permit EPA to take timely action, once
it is notified of a PRP's bankruptcy filing; and

     4.  Coordinate with OECM to try and balance Agency actions against
both viable and nonviable PRPs especially in light of the courts'  recent
leaning towards giving Governmental units first priority on hazardous
waste cases after secured credftors.

3.  EPA NEEDS TO COMPLETE NEGOTIATIONS WITH RESPONSIBLE PARTIES
    IN A MORE TIMELY MANNER"

Negotiations with responsible parties were not  always fully successful  and
often extend well beyond established Agency timeframes  for conducting nego-
tiations.  Even though the Agency has a policy  prescribing a 60-day cut-off
period for negotiations, we found that EPA did  not have a coordinated or
systematic structure for tracking negotiations  to ensure timely completion.
We estimated that 276 (67 percent) of 411 negotiations  were either (1)
ongoing from fiscal 1984 or (2) initiated in fiscal  1985 and had exceeded
60 days, with negotiations, lasting an average  of 279 days.  Fifteen of
the site negotiations over 60 days, amounting to $3,598,700 in clean-up
costs, were concluded without a settlement or cost recovery reached with
responsible parties. In addition, even though they did  not exceed 60 days
in length, we found 31 negotiations in the amount of $6,733,000 which were
considered unsuccessful  since they did not result in a  settlement.  Also,
we found 43 additional negotiations that had outcomes that were fund
financed actions for which we were unable to obtain dollar amounts from
either SCAP or CMS.  EPA officials informed us  that cutting off negotiations
is a judgment call based on the progress made and usually negotiations  were
not concluded by the 60-day cut off period.  Even though various systems
were supposed to track enforcement progress, we were unable to determine
the current status or results of all negotiations.  Untimely negotiations
delay sites from progressing toward cost recovery through litigation and
ultimately may weaken the Agency's position to  reach a settlement with
responsible parties to clean up sites.

Superfund enforcement actions can occur at different points in the cleanup
process and can involve both regional and Headquarters  personnel.  In
general, these actions include:  (1) identification of the responsible
parties; (2) notification of the responsible parties by letters showing
their potential liability for cleaning up the site; and (3) negotiations
between EPA and the responsible parties to determine whether a mutually
agreeable settlement is possible.  EPA may also negotiate with responsible
parties to determine whether they will perform  various phases of site
cleanup, such as the remedial investigation/feasibility study (RI/FS),
cleanup of surface problems at the site, or cleanup of groundwater
contaminated at the site.  EPA may negotiate for one phase at a time or
for several phases at once.
                                    19

-------
If negotiations are successful, the terms of the agreement between EPA
and the responsible parties are incorporated into an administrative
consent order or consent decree.  The financial settlement alternative is
similar to costs recovered for the Trust Fund, because the responsible
parties contribute money while EPA arranges for the cleanup.  If negotia-
tions prove unsuccessful, EPA can (1) clean up the site itself with Trust
Fund money or (2) issue a unilateral administrative order or obtain a
court order forcing the responsible parties to clean up the site.  When
EPA cleans up the site, it attempts to recover the cleanup costs from
the responsible parties at a later date.  In issuing a unilateral admini-
strative order or obtaining a court order, the reponsible party must
comply with the terms of the.order or pay fines or treble damages.

Since the beginning of the Superfund program, the goal of negotiations
was to secure privately managed or financed cleanup of hazardous substance
releases.  The timeframes for completing negotiations have generally
remained the same throughout the history of CERCLA.  For example, on
February 23, 1982, a memorandum entitled, "Hazardous Waste Compliance
and Enforcement Program Guidance" was issued by the Office of Solid Waste
and Emergency Response.  The memorandum mentioned that if substantive
negotiations, which are believed to lead to a satisfactory resolution
within a short period of time (normally 60 days or less), have not been
entered into within 30 days of the date of response required by the notice
letters, Regional program offices should proceed with administrative action
or litigation.  In addition, on August 26, 1983, EPA issued a policy docu-
ment entitled, "Guidance on Pursuing Cost Recovery Actions Under CERCLA,"
which indicates that a reasonable period of time for most negotiations is
60 to 90 days.  This policy also maintains that the negotiation timeframes
be disclosed to the responsible parties as a deadline to reach an agreement,

The most recent EPA policy which discusses the timing of negotiations is
contained in the "Interim CERCLA Settlement Policy," dated December 5,
1984.  This guidance mentions that a Negotiations Decision Document (NDD),
which follows completion of the RI/FS, makes the preliminary identification
of the appropriate remedy for the site.  Prelitigation negotiations between
the government and the responsible parties should normally not extend for
more than 60 days after approval of the NDD.  If significant progress is
not made within a reasonable amount of time, the Agency will not hesitate
to abandon negotiations and proceed immediately with administrative action
to litigation.  While the type of negotiation undertaken by the Agency
may vary, the general timeframe for conducting negotiations with respon-
sible parties was 60 days.

The basic working document used by EPA .to plan and manage CERCLA enforce-
ment activities is the Superfund Comprehensive Accomplishment Plan (SCAP).
The SCAP provides information on each region's plans for enforcement
activities on a quarterly basis and records whether those activities were
accomplished within the expected quarter.  One item which SCAP tracks is
negotiations with responsible parties.  We reviewed SCAP to determine the
results of negotiations that were ongoing in fiscal 1985.  Also, we wanted
to determine the length of negotiations.  By reviewing the SCAP we found
that 411 negotiations were ongoing with responsible parties.  However,
                                    20

-------
the SCAP was updated every fiscal  quarter to only include any additional
negotiations which were started.  There was no detailed information provided
on the status of the ongoing negotiations or how long they were in progress.
Furthermore, we were unable to identify exact start dates for the 411 negotia-
tions.  Headquarters officials from the Office of Waste Programs Enforcement
(OWPE) informed us that the SCAP is a Superfund management tool to monitor
regional progress of various site  activities.  The SCAP does not provide
detailed information on these activities.  For monitoring purposes, OWPE
officials believe that tracking progress by fiscal  quarters is adequate,
and that reporting details, such as specific dates for each site was not
warranted.  However, OWPE referred us to the Case Management System (CMS)
which contains specific dates on various enforcement actions.

We obtained a copy of a CMS report to determine whether the negotiations
were completed, what the results were, and the length of time that EPA
spent negotiating with responsible parties.  We found that the CMS, in
general, provides critical milestone dates for such enforcement actions
as administrative/unilateral orders, case referrals to the Department of
Justice, cases filed, and settlements with responsible parties.  The CMS
does not monitor or track negotiations per se but only the end result,
(e.g., if the case was referred to Headquarters).  In addition, EPA did
not have a system that pointed out that a negotiation was taking longer
than 60 days and may need to be cut off.

Using the SCAP and CMS reports, we extracted pertinent information to
estimate the length of the 276 negotiations we reviewed.  Also, we found
another 16 actions for which we could not determine the length of negotia-
tions (refer to Exhibit E).

Our review of SCAP and CMS results for the 292 negotiations disclosed the
following:

     0 104 sites did not appear to have been completed by September 30, 1985.
       Based on the Agency's records, these negotiations are still ongoing.

     0 100 sites appear to have concluded with settlements with responsible
       parties.  We believe these  negotiations were successful.

     0 43 sites appear to have been transferred to the Trust Fund (fund
       financed action) for potential EPA cleanup.  Since these negotia-
       tions did not result In a private party clean up, we consider these
       negotiations to be unsuccessful.

     0 11 sites appear to have concluded with EPA issuing unilateral
       administrative orders.  We believe these negotiations were
       unsuccessful.

     0 6 sites were either (1) transferred to another EPA program for
       action, (2) transferred to a state for action, (3) involved bank-
       rupt parties, or  (4) had no action listed.
                                    21

-------
     0 4 sites appear to have concluded with referrals to the Department
       of Justice.  We consider these site negotiations unsuccessful since
       they did not result in a settlement with responsible parties.

     0 2 sites appear to have concluded with cost recovery actions.  We
       consider these negotiations successful.

     0 22 sites had outcomes that could not be determined from the system.

We concentrated on identifying negotiations which lasted over the 60-day
cut-off period as stated in Agency guidance.  Our review of the 411 site
negotiations disclosed that 276 (67 percent) exceeded the 60-day Agency
policy, with the average negotiation taking 279 days.  Of these 276 negotia-
tions, it appeared 15, totaling $3,598,700, concluded with no settlement
being reached with the responsible parties (i.e., fund financed, issuance
of unilateral administrative order or subsequent referral/filing to the
Department of Justice).  We were not able to determine the dollar amounts
for the 43 fund financed actions.

The Superfund program is generally implemented in the regions.  Headquarters
officials informed us that detailed site negotiation documentation should
be available in the regional offices.  However, in Region 3 our review
was hampered because many of these pertinent documents (notice and demand
letters, responsible party correspondence, minutes of negotiations, etc.)
could not be located.  For example, in 5 of 25 site files (20 percent)
reviewed, we could not determine the duration of the negotiations which took
place between the Region and the responsible parties.  This was due to the
fact that the Regional site files were generally not organized.  Furthermore,
our review of Superfund enforcement information maintained by Region 3 dis-
closed that there was no system that provided comprehensive information on
all enforcement actions.

Region 3 could provide information on dates such as when (1) notice letters
were sent to responsible parties; (2) administrative orders and consent
decrees were issued; and (3) judicial enforcement actions were referred to
EPA Headquarters and the Department of Justice.  However, at the time of
our review, the Region did not have any report or system that showed the
dates when (1) responsible party searches began and ended; (2) response to
notice letters and subsequent correspondence were received; (3) negotiations
with responsible parties began and ended; (4) settlements with responsible
parties were reached; and (5) responsible parties performed cleanup actions
at a site 1n compliance with administrative orders and consent decrees.  Our
review of the Superfund enforcement action information maintained by Region 3
disclosed that most of this information was maintained 1n individual site
files.

In Region 4, we could not review and evaluate the status of negotiations
of the Region's 151 Superfund sites because the information could not be
obtained without a detailed review of the Individual project files.  The
status of negotiations was not monitored and controlled on an ongoing
basis at all sites.  While the Region had been moderately successful in
negotiating settlements for certain phases of site cleanup, the Agency
                                    22

-------
guidelines for conducting negotiations within 60 days had not been con-
sistently met.  In addition from information available, it was sometimes
difficult to determine precisely when negotiations were initiated and
concluded.  Of the 29 sites reviewed, 9 different negotiations lasted
from 6 months to 30 months.  In response to our Region 4 report, the
Region had taken steps to limit negotiations following the completion of
a workplan to 60 days or less.  Also, the Region had earlier implemented
procedures for tracking the milestones of remedial and enforcement processes
of each site which should help.

While many of the above regional and Headquarters systems and reports track
and monitor various enforcement actions, they did not record critical mile-
stone dates for enforcement activities occurring at all sites.  Consequently,
EPA did not have a mechanism to track all critical enforcement milestone
dates (i.e., length of negotiations) in any systematic manner from initia-
tion through completion.

The General Accounting Office (6AO)  in a May 1986 report "Responsible
Party Clean Up Efforts Required Improved Oversight" stated that, "Experience
with EPA's settlement process has shown that it may take 2 years or more
to complete a remedial investigation and feasibility study.  Subsequent
negotiations and settlements to establish remedy selection, design, and
implementation may add yet another year, even before cleanup begins."

In addition, an EPA contractor in a March 14, 1986, study showed the
following on negotiations:

     — Pre-RI/FS negotiations should not last for more than 60-90 days
        actually lasted for an average period of 195 days.

     — Study findings for both elapsed time and workdays required indicate
        that more effort is being expended on (Pre-RI/FS) negotiations
        than had been assumed by Headquarters.

     -- Remedial design/remedial action (RD/RA) negotiations which should
        last about 60-90 days based on current policy, actually lasted
        about 250 days.

     — Although data is limited, the study results indicate that the
        elapsed time required for (RD/RA) negotiations is significantly
        longer than either prior budget assumptions or the OWPE policy on
        the conduct of settlement discussions anticipated.

We discussed with both legal and Superfund officials at Headquarters and
the Regions the reasons why negotiations with responsible parties are so
time consuming.  For example, negotiations were lengthy at the Delaware
City PVC Plant (15 months) in Region 3 because the 106 administrative
orders for the feasibility study and remedial cleanup was the first of its
kind, and there were disagreements over the consent order's wording.  Also,
Headquarters policy changes had to be reflected in the consent order and
this delayed its issuance.
                                    23

-------
At Headquarters, in a discussion with a senior attorney from OECM, we
were told that the 60-day cut off period for negotiations is not realistic
and that negotiations are usually lengthy when they involve several
responsible parties.  In addition, if an agreement cannot be reached with
all RPs involved, then the negotiations tend to drag on.  Furthermore,
in Region 3, we found only a few instances where the Region had informed
the responsible parties that the negotiation period would be only 60
days.  In our opinion, if the responsible parties were told there was a
time limit on negotiations, site cleanup and fund reimbursement may be
expedited.

However, EPA officials argue that negotiations have resulted in favorable
settlements to compel responsible party cleanup of hazardous waste sites.
Senior OWPE management believe that the success of the negotiation process
should be measured against the settlement reached with responsible parties.
Furthermore, Superfund and legal enforcement representatives stated that
they may negotiate at length because, in their opinion, the likelihood of
reaching a settlement with responsible parties is greater than pursuing the
case through litigation.

CONCLUSION

While we recognize EPA's recent success to compel responsible party clean-
ups through negotiations, we believe the negotiation process needs to be
made more timely.  While we agree with EPA that the current 60-day cut-off
to complete negotiations may be unrealistic in some instances, we believe
that some cut-off period must be established in conducting negotiations
with responsible parties.  As we stated earlier, 276 of the 411 negotia-
tions exceeded the 60-day Agency policy.  These 276 negotiations averaged
279 days.  EPA must re-evaluate its December 5, 1984, guidance and establish
a more realistic timeframe to complete negotiations with responsible parties,
Furthermore, EPA should improve its monitoring of all negotiations by
requiring regional offices to maintain information on meeting this goal
in any enforcement management system.  To ensure that these timeframes
are met, EPA should inform all responsible parties prior to beginning
negotiations of the cut-off period.  If negotiations approach the cut-off
period without a reasonable settlement, then they should be broken off by
EPA, and cost recovery pursued through civil action.  Negotiations with
responsible parties are an essential part of the enforcement process.
Failure to conduct timely negotiations would, in our opinion, increase the
likelihood of responsible parties delaying or potentially avoiding their
liability (i.e., declaring bankruptcy) which may ultimately weaken EPA's
efforts to recover cleanup costs on future hazardous sites.

OSWER Comments And PIG Evaluation

The Assistant Administrator for OSWER indicated that OSWER will re-evaluate
their present policy, procedures and negotiation timeframes under the new
Superfund bill and will take our recommendations into consideration.  We
agree with this action.  However, to evaluate how OSWER has acted on our
recommendations, we need to be advised on the new revised policy and
procedures.
                                    24

-------
Recommendations

We recommend that the Assistant Administrator for Solid Waste and
Emergency Response:

     1.  Re-evaluate the Agency's present policy and procedures to ensure
that timeframes set for negotiations are reasonable.  Also, timeframes
should not be exceeded unless it can be documented in the files that
significant progress is being made.

     2.  Require that specific steps in the negotiation and settlement
process are planned, scheduled, and initiated in a systematic and orderly
manner in order to minimize delays in the settlement process.

     3.  Require Agency negotiators to notify responsible parties that
the negotiations must be concluded within the Agency's established timeframe.

     4.  Require the regional offices to maintain information on the
length of negotiations and whether this conforms to the goal  established
by EPA.

4.  EPA NEEDS TO IDENTIFY AND TRACK STATUTE OF LIMITATIONS (SOL) DATES

EPA could potentially fail to recover millions of dollars in cleanup
costs by not filing cost recovery actions within the "statute of limita-
tions" (SOL) period.  Although Agency policy states that court actions
should be brought timely, there was no formal system to identify and track
SOL dates.  During our audit, we identified 65 non-NPL completed removals
sites, totaling $2,917,200, which may be lost if cost recovery actions
are not filed on or before December 31, 1986.  While some of these sites
may ultimately be referred to the Department of Justice, EPA may eventually
violate the SOL unless agreement can be reached on what is the SOL period.
Consequently, responsible parties could completely avoid any financial
liability for the cleanup of hazardous waste sites if appropriate cost
recovery actions are not filed in court within the SOL period.  Despite
confusion as to when the SOL period should start, this issue will become
more significant in the next few years as an increasing number of sites
progress toward cleanup.  Although EPA is aware of the situation, formal
procedures and a system need to be developed to ensure that:   (1) all
cost recovery actions are filed timely regardless of the SOL; and (2) SOL
dates are identified for all cleanup sites on a current and ongoing basis.

EPA Needs To Improve Its Timing of Cost Recovery Actions

Historically, there has been considerable confusion over whether a SOL
will apply to CERCLA cases and, if so, when it would start.  Since CERCLA
did not mention an SOL time period in which an enforcement action must be
filed, EPA over the past years issued conflicting guidance in order to
minimize the risk in recovering expended funds.  Both the August 1983
Agency policy (when dollars are first expended) and the February 1984
internal OWPE policy (upon completion of a response action) adopted a 3-year
SOL period.  OWPE believed it would be extremely cumbersome and make for
"piecemeal litigation" to file cases when funds are first expended because
                                    25

-------
expenditures for a site frequently extend over a period of several  years.
The House of Representatives CERCLA reauthorization bill proposes a 3-year
SOL period from when a response action is completed.  In our flash  audit
report, we recognized that the CERCLA reauthorization legislation may
resolve this issue for future sites but may not "grandfather" cases prior
to its passage.

The Comprehensive Environmental Response, Compensation, and Liability Act
of 1980 (CERCLA) did not mention a time period in which a cost recovery
action must be filed to avoid violation of the SOL.  EPA officials  at
Headquarters and in the regions told us that CERCLA cases could fall
either under Federal law (six years), or tort law (three years).

To help clarify the issue, EPA issued a document entitled "Guidance on
Pursuing Cost Recovery Action Under CERCLA" on August 26, 1983.  This
guidance stated:

     "There is some doubt at this time as to precisely which limitation
     period will be applied to a cost recovery action . . . since it  is
     possible that a court may see CERCLA actions arising out of the
     tortious conduct of others, cost recovery actions should be brought
     within three years. ...  In order to avoid argument on this  point
     and to eliminate a potential bar to recovery, the Agency should
     attempt to commence all cost recovery action within three years  of
     the date dollars are first expended."

The OWPE issued supplemental guidance in the form of a memorandum on
February 15, 1984, stating that EPA should observe a three year SOL
period that begins on the completion date of a response action.  However,
this guidance was never officially issued to the regional offices for
implementation.

On September 5, 1984, we issued a flash report expressing our concern
that a number of potential cost recovery actions under CERCLA might be in
jeopardy due to the uncertainty surrounding a CERCLA SOL.  On March 26,
1985, the Agency issued a response to our flash report.  In addressing our
concern over the uncertainty surrounding the SOL for cost recovery  actions,
the Agency response stated, in part, that:

     "We need to differentiate between a legal definition of the SOL  under
     CERCLA and the establishment of timeliness for referrals of CERCLA cost
     recovery actions.  The Agency must strike an appropriate balance between
     the need to minimize any risks to the government's ability to recover
     expended funds and the operational realities of the CERCLA program
     and the cost recovery process."

     Legal Definition

The position of the Government (EPA and Department of Justice) is that
there is no SOL under CERCLA, but 1f there was, 1t would be six ^ears from
completion of a response action.  There are cases now in the courts which
may provide some case law on whether no SOL applies, a six-year SOL
applies, or whether three years is the appropriate limitation period.
                                    26

-------
On March 26, 1985, EPA issued a discussion paper on a New Hampshire court
ruling concerning the SOL on CERCLA cases.  The case involved a responsible
party attempting to block a New Hampshire claim for cost recovery under
CERCLA by implying that the SOL had expired.  The judicial  decision was
that the State claim should not be dismissed since the three-year SOL
(under Section 112 of CERCLA) does not apply to judicial actions for cost
recovery.  EPA, in its discussion paper, concluded that:
                               i
     "It is important to note that this is the first definitive ruling
     concerning the SOLs for cost recovery actions under CERCLA.  Although
     the opinion concerns a claim brought by a state under Section 107 of
     CERCLA, we would expect a similar ruling on claims by the United States,
     The decision is strong support for the proposition that Congress
     intended to allow Federal and state governments to undertake judicial
     actions for reimbursement of removal, remedial, and response costs
     expended under CERCLA at any time."

While we recognize /the significance of the decision, we believe there
still is uncertainty surrounding the SOL.  For example, EPA mentions in
its response to our flash report that there is a risk that the courts
may take a contrary review, such as selecting the start date rather than
the completion date as the SOL time period or holding to a three-year SOL.
An OECM attorney re-emphasized that the above case is the first decision
concerning the SOL, and that several other cases may have to be decided
to clarify this issue.  In addition, EPA in its response indicated that
the Congress and the courts will be making the definitive determination
on the SOL.

The CERCLA reauthorization bills specifically address the SOL for cost
recovery.  The Senate version, dated September 26, 1985, provides that a
claim must be presented or action commenced within six years after the
date of completion of the response action (Statute of Limitations,
SE142(a), Section 113).  However, the House of Representatives version
provides that an initial action for recovery of costs must be commenced
within three years after completion of the removal action or within six
years after initiation of physical on-site construction of a remedial
action (Section 113, Litigation, Jurisdiction, and Venue, (g) Statute of
Limitations, (2) Action for Recovery of Costs).  If the House's version
takes precedence, the SOL for removal actions will be three years from
completion of the action.

Until such time that this issue is satisfactorily resolved by either the
Congress or the Federal courts, we believe EPA should utilize a conserva-
tive date for SOL:  three years from the completion of the removal action.

For long-term remedial projects the Agency also needs to take action to
ensure that the necessary documentation will be available to support the
Agency's cost recovery actions.  The Chief, Superfund/RCRA Procurement
Branch, Procurement and Contracts Division (PCMD) has already initiated
some action by requesting a class deviation from the Federal Acquisition
Regulations (FAR).  On March 21, 1986, the Chief requested a FAR deviation
be processed that will require contractors to retain records for a period
                                    27

-------
of 10 years in lieu of 3 years after final payment.  This deviation would
apply to all Superfund contracts.  However, a recent audit by the U.S.
Army Audit Agency, "Superfund Management U.S. Army Corps of Engineers,
Washington, D.C.," dated 24 April 1986, revealed that the Army's current
documentation requirements were not adequate, in that accounting documents
are to be kept 6 years, 3 months from payment.  As such, the required
documentation from the Corps of Engineers may be destroyed before litiga-
tion is begun.  The Agency in its August 1, 1986, response indicated that
it is currently negotiating with the Corps of Engineers to ensure that
Corps contracts contain the same records retention requirements as EPA
contracts.  This would help minimize the likelihood of the Corps contractors
destroying necessary documentation before EPA files a case for cost recovery.

     Timely Filing

In their response to our flash report concerning the SOL, the Assistant
Administrator for OSWER and Assistant Administrator for OECM stated that:

     "... for reasons of good management, it is appropriate to establish
     an earlier date for filing cost recovery actions regardless of the
     statute of limitations.  Evidence is fresher, knowledgeable personnel
     are more likely to be available and the Fund can more likely be
     replenished if actions are brought as soon as possible."

Subsequently, on October 7, 1985, the Assistant Administrator for OSWER
and the Assistant Administrator for OECM issued a joint memorandum to the
regions on the "Timing of CERCLA Cost Recovery Actions."  The purpose of
the memorandum was to provide guidance on when cost recovery actions
should be initiated under § 107 of CERCLA.  The memo also noted that the
above policy guidance was not intended to limit any actions, but was
intended to assist EPA regional offices in the management of cost recovery
actions.  Specifically:

     (1)  Cost recovery action should be initiated within one year of
completion of a removal action at a non-National Priorities List Site.

     (2)  Cost Recovery action should be initiated as soon as practicable
after signing the Record of Decision, usually within 18 months of that
time for remedial actions.  However, cost recovery actions should not
begin until the Remedial Design Phase is completed.

The above policy was further included in the Agency's Operating Guidance
FY 1987 (page 12).

In order for EPA to have an effective and efficient cost recovery program,
it must establish "early" timeframes and plans for initiating and filing
cost recovery actions.  Without such plans and timeframes, EPA will
experience great difficulty in handling the hundreds of CERCLA cost recovery
cases over the next several years.  In addition, with an established plan
EPA will be able to properly allocate resources to ensure timely settlements.
Thus, EPA would be able to accomplish the ultimate goal, early replenishment
of the Trust Fund, which would allow the Agency to clean up additional
hazardous waste sites at an earlier time.
                                    28

-------
EPA Needs To Track SOL Dates

Despite confusion over the SOL time period, EPA needs to develop a manage-
ment information system to identify and track SOL dates for initiating
cost recovery actions against responsible parties.  On September 5, 1984,
we issued a flash audit report to bring this significant issue to the
immediate attention of management.  We reported that there was no formal
system or procedures in place to provide management an overview of cost
recovery actions in regard to the SOL.  In addition, We found while
Superfund personnel were generally aware of the status of their own
individual cases, there was no comprehensive record of the status of all
cases.  We recommended that:  (1) EPA develop a comprehensive listing of
all cleanup actions to date; and (2) implement a system and procedures to
identify and track cost recovery actions in regard to SOL dates.

In November 1984, OWPE developed a process to review completed removal
actions and completed units of remedial actions to assure that cost
recovery cases were filed before the SOL expired.  This process used
three years from the completion of the removal/remedial action as the
ending date for SOL purposes.  OWPE informed the regions that this report
was to be reviewed for accuracy and possible action on a quarterly basis.

In our review of Region 3, we found that on November 27, 1984, Headquarters
sent the first of these quarterly reports to the region.  It showed the SOL
period for actions that were completed for three years or were approaching
three years from completion in fiscal  1985.  This report identified four
removal actions and Region 3 confirmed that cost recovery had been initiated
on three of these sites.  The fourth site had no financially viable respon-
sible parties.  Our review disclosed that there were an additional three
removal actions that the OWPE report did not identify.  Although these
three cases were filed with the Department of Justice, the fact that neither
Headquarters or Region 3 identified these sites indicates that the OWPE SOL
review process alone was not sufficient to assure that cost recovery actions
were filed before the SOL expires.

In Region 4 our review disclosed that the Region could encounter signifi-
cant problems with cost recovery actions that are ongoing at two major
sites.  On one site, the Regional Superfund Comprehensive Accomplishment
Plan (SCAP) indicates negotiations were scheduled for the third quarter of
fiscal 1985.  However, under the most conservative assumption, the SOL
would have expired in September 1984.  The Regional SCAP also shows that
for the second site a responsible party search was scheduled for the third
quarter of fiscal 1985.  However, the SOL would have potentially expired
in the second quarter of fiscal 1985.

Throughout the audit, we briefed senior OWPE and OECM management on the
status of our review.  When asked about their response to our September 5,
1984, flash audit report on the SOL, they provided us a memorandum from
the Director, OWPE to the acting Assistant Administrator for OSWER on the
status of that response.  The memorandum states, in part, that:
                                    29

-------
     "We are presently compiling information, including completion dates
     on all removal actions.  Me are in the process of developing a
     computer tracking system for cost recovery to identify and track
     cost recovery actions.  The current docket system in OECM allows us
     to track cost recovery referrals to Headquarters, referrals to the
     Department of Justice, and filings of complaints and certain
     additional information.  Our new system will also be able to track
     the activities associated'with CERCLA 107 cases, which include dates
     of expenditures, SOL, issuance of demand letters, and actual
     expenditures associated with site response actions."

On March 26, 1985, EPA issued a response to our flash report.^ EPA
agreed with our recommendations to establish a system to identify and
track response actions and key dates for cost recovery and is currently
developing such a system.  In the interim period, the Agency established
a manual system to track significant dates on site specific basis.
However, the OWPE did not address our recommendation of developing a
comprehensive listing of potential SOL dates even after informing the
Assistant Administrator for OSWER (in a February 1985 memorandum) that
this was being compiled.  OWPE did indicate that information on potential
SOL dates were available.  However, the dates were not monitored since
the Agency had agreed on a 6-year SOL period and no sites were in danger
of violating the SOL period.

Subsequent to the Agency's response to our flash report, we wanted to
identify at Headquarters all completed non-NPL removals which may violate
the SOL if not filed on or before December 31, 1986.  We requested a
listing from OERR identifying all removal actions completed on or before
December 31, 1983.  This listing provided us information on sites that
would reach the 3-year SOL period on or before December 31, 1986.  We
elected to use the more conservative timeframe of three years after
completion for a removal action.  We found that there were 106 removal
actions, amounting to $14,609,558.  Subsequently, we attempted to deter-
mine whether these sites had been filed for cost recovery actions.  Due
to the lack of a centralized management information system to monitor
site status, we were forced to rely on several Superfund and legal
enforcement management documents to determine whether cost recovery
action was initiated.  Our review of the legal docket system and the case
management system disclosed that 65 removal actions, totaling $2,917,200,
may be lost if cost recovery actions are not filed by December 31, 1986.

Discussions with Headquarters officials revealed they did not view the
SOL as a serious problem.  As discussed in EPA's response to the OIG
flash audit report, Headquarters officials discussed their position that
the 6-year statute of limitations applied'as well as recent progress in
developing a tracking system as steps taken to minimize a potential SOL
violation.  Consequently, EPA believes that this area is a low risk.
While we recognize and commend the Agency's progress, we believe that
inadequate identification and tracking of SOL dates is still a serious
problem.
                                    30

-------
As discussed above, we identified 65 non-NPL completed removal sites,
totaling $2,917,200, which may violate the SOL if not filed on or before
December 31, 1986.  We believe the SOL is a potential risk to cost recovery
since a final decision was not made on the issue by either Congress or
the Federal courts.  Until this issue is resolved, EPA is still  at risk
in recovering costs expended from CERCLA.  The Agency can minimize the
risk by aggressively pursuing cost recoveries in accordance with revised
guidance.

OSWER Comments and PIG Evaluation

In the September 10, 1986 memorandum, the Assistant Administrator for
OSWER indicated that work was initiated on a tracking system that will
identify all removal actions and pinpoint significant enforcement-related
dates, including the statute of limitations dates.  In addition, OSWER
and OECM have requested that the Regions review the universe of removal
actions for purposes of potential cost recovery actions.

The response states that the new Superfund bill  directly addresses the
issue of the statute of limitations.  However, as we stated in our report,
depending on which version of the Superfund bill may be passed,  the SOL
period can vary.

RECOMMENDATIONS

We recommend that the Assistant Administrator for Solid Waste and Emergency
Response:

     1.  Proceed under the more conservative tort law timeframe (three
         years after completion of a removal) until such time the issue
         is resolved by Congress or the courts.

     2.  Include and track in the comprehensive listing of all removal
         actions the SOL date.

     3.  For those sites where the SOL is about to expire, take immediate
         action to initiate negotiations or referrals to DOJ.

     4.  Ensure that cost recovery actions are being Initiated within one
         year of completion of a removal action at non-NPL sites.

5.  EPA NEEDS TO IMPLEMENT A COMPREHENSIVE MANAGEMENT INFORMATION SYSTEM
    (MIS) TO TRACK ENFORCEMENT ACTIVITIES

EPA would have a better managed CERCLA enforcement operation with a
comprehensive management Information system which would consolidate the
information now contained in various Agency Information systems.  At the
time of our review, the Agency used several information systems to collect
and maintain site-specific enforcement information.  Each of these systems
served a useful but particular management Information need.  However,
currently no one system provides all Agency managers with all the timely
and consistent data needed to effectively manage and/or evaluate its
Superfund enforcement program.  Even though EPA enforcement program
managers have indicated that a system providing comprehensive information
for tracking enforcement actions is beneficial, EPA has not developed
such a system.
                                    31

-------
OSWER has recognized that its current information system needs improvement.
In December 1984, an EPA contractor completed an internal study for OSWER
which recommended that a comprehensive information system be developed.
The Agency is now developing such a system.  If properly developed and
implemented, the new system could:  (1) reduce or in some instances
eliminate the conditions noted in this report on the problems with the
Agency's cost recovery effort; and (2) improve the overall Agency manage-
ment of CERCLA enforcement activities.

We found that CERCLA enforcement information was contained in various
management and financial information systems:  Superfund Comprehensive
Accomplishments Plan (SCAP); the Case Management System (CMS); Enforcement
Docket System; CERCLA Information System (CERCLIS); and Financial Manage-
ment System.  While we noted that each of these systems served a particular
useful management need, none of the systems was designed to serve as a
integrated system which would contain specific milestones and financial
information to adequately monitor CERCLA enforcement activities.  Agency
officials were required to use outputs from multi systems and manually
search through individual regional project site files to determine
the enforcement status of any given hazardous waste site.

In our audits of Regions 3 and 4, we experienced difficulty in determining:
(1) site status and (2) cost recovery activities from the various automated
information systems.  As a result, we had to manually generate pertinent
site and program information such as:  (1) information on bankruptcy cases;
(2) the length of time taken for the negotiation process; (3) progress in
pursuing enforcement actions against potential responsible parties; and
(4) the statute of limitations dates.  OWPE, which is the responsible office
for managing the CERCLA enforcement program, was unable to provide us with
detailed statistical information in such areas as length of negotiation,
and the number of sites where the statute of limitations was expiring or
had expired.  As a result, we were required to extract the information
from several reports.  In addition, our request for information on the
number and amount of bankruptcy claims had to be referred to the regions.
Regional personnel manually generated this data from the project files
since the systems did not contain this information.

In a February 6, 1985 memo, the Director, OWPE agreed that the information,
we requested, would be of benefit and could assist in a better management
of the CERCLA enforcement program.  Additionally, both Regions 3 and 4
agreed that a comprehensive automated management information system was
needed.  Region 4, in fact, had developed an automated regional site
tracking system to improve control over the status of its enforcement
actions.  However, at the time of our review, we were unable to review
the status of negotiations and the cost recovery actions at all of the
Regions' Superfund sites due to the voluminous correspondence and data
in the individual project files.  This information could not be obtained
without doing a detailed review of the individual project files.

Our audit findings indicate a need to collect additional information in a
automated format.  Our review of Region 3 showed that the Region did not
have any reports or system that reported the dates when:  (1) responsible
                                    32

-------
party searches began and ended; (2) responses to notice letters and sub-
sequent correspondence were received; (3) negotiations with responsible
parties began and ended; (4) settlement with responsible parties were
reached; and (5) responsible parties performed cleanup at a site in
compliance with administrative orders and consent decrees.

In addition, our review of the regions were hampered because many of the
pertinent documents (notice and demand letters, responsible party
correspondence, minutes of negotiations) could not be located because the
site files were generally not well  organized.  Even though Region 3
agreed with the findings and implemented a central filing system for
enforcement data, the need and benefits of an automated MIS are still
apparent and valid.

As previously mentioned, enforcement actions may be taken by both regional
and Headquarters offices and by both EPA and DOJ.  As a result, we believe
there is a need to be able to quickly determine the current status of a
site and the responsible Agency office.  Currently, the Agency has no
system which would provide this type of information, and there is a
potential for sites to be lost or for site activities not to be taken.

CONCLUSION

Despite these shortcomings, we recognize the Agency's efforts to improve
its reporting capabilities for enforcement actions.  However, we believe
improvements are still needed in order for Agency officials to effectively
manage the CERCLA enforcement program.  In our opinion, as the number of
enforcement actions increase in the future, it will become increasingly
necessary to maintain comprehensive Superfund enforcement.tracking
information.

We believe a comprehensive management information system offers
many benefits.  First, the information will allow managers to determine
how long different steps in the enforcement process are taking so that
reasonable time frames for completing these steps can be set.  Second, it
will provide an easy way to determine whether the time frames set for the
enforcement process are being met.   Third, the information will help
managers in workload planning by providing data on upcoming steps.
Fourth, the information will help management to more easily respond to
information requests from Congress  and other sources.

OSWER Comments And PIG Evaluation

The Assistant Administrator for OSWER in the September 10, 1986 memorandum
made no specific comments with regard to our recommendations for this
finding.  As stated in our report,  we believe Agency officials need to
make improvements to effectively manage the CERCLA enforcement program.
                                    33

-------
RECOMMENDATIONS

We recommend that the Assistant Administrator for Solid Waste and Emergency
Response:

     1.  Designate the development of the CERCLA enforcement system as
         a high priority item; and
                               i
     2.  Require that pertinent site-specific enforcement information
         on bankrupt cases, statute of limitations, negotiation milestone
         dates, etc. be included as data elements in the new MIS.
                                    34

-------
                                                       EXHIBIT A
               COMPLETED NON-NATIONAL PRIORITY LIST
Region

  1

  2

  3

  4

  5

  6

  7

  8

  9

 10
Totals
iL SITES WITH CLEANUP COSTS UNDER
Total Number of
Compl eted
Removal Sites
Under $200,000
as of 09/30/85
16
15
32
65
40
18
11
7
35
9
"258
$200,000
Total Obligations
of Removal Sites
Under $200,000
as of 09/30/85
$ 997,475
644,237
1,792,501
2,768,504
1,902,972
608,703
589,519
169,320
1,473,392
528,233
$11,474,856
                                35

-------
                  SCHEDULE OF COMPLETED REMOVAL ACTIONS ON
                        CLEANUP COSTS UNDER $200,000
                        "THROUGH SEPTEMBER 30, 1955"
                                                               EXHIBIT B
                                                               Page 1 of 6
REGION
NAME OF SITE
  1        Bourdeaudhui
  1        Bursey Asbestos
  1        Castle Hill
  1        Cyanide Incident
  1        Dean Street
  1        Gonic Sites
  1        Great Diamond Island
  1        Hougels Neck
  1        Keswick Road
  1        Lake Sunapee
  1        Matarazzo
  1        Pointer Asbestos

  1        Total Sites - 12

  2        Abandoned Drum
  2        Abandoned Drums Erie Canal
  2        Blue Poly Drum
  2        Blue Spruce International
  2        Fort Totten
  2        Horseshoe Road Dump
  2        Kearny Drum Dump #1 & #5
  2        Kearny Drum Dump #2
  2        Long Island Beach
  2        Signo Trading
  2        Mallkill Well

  2        Total Sites - 11
 COMPLETION
   DATE

 6/14/1985
 5/28/1985
  5/9/1984
 1/23/1983
  8/3/1983
 3/13/1985
 4/18/1983
 3/19/1985
11/10/1983
  6/9/1984
 5/28/1985
  7/1/1985
                                  2/19/1982
                                  7/16/1982
                                  2/24/1984
                                 11/15/1983
                                  4/21/1983
                                  7/12/1985
                                   5/3/1985
                                  4/13/1985
                                  8/13/1982
                                   7/3/1984
                                  3/16/1984
   TOTAL
OBLIGATIONS

   $145,120
     22,000
        190
      1,528
    180,000
   •150,000
        829
      5,000
        194
     31,732
     10,000
     25,000
   $571.593"
                      $  1,146
                           675
                           777
                         3,291
                             0 I/
                        60,000
                        92,131
                        42,000
                         1,095
                       134,325 2/
                        18,315
                      $353,755
                                     36

-------
                                                               EXHIBIT B
                                                               Page 2 of 6
REGION
NAME OF SITE
  3        Baltimore Iron & Metals
  3        Biedler Road
  3        Boyertown Scrap Metal
  3        Caustic Midnight Dump
  3        Columbia Park Drum
  3        Coons Run
  3        East Cumberland Street
  3        Evans Trail
  3        Eweing Road Drum Site
  3        Fennel Road
  3        Interstate 70 Acid Spill
  3        Locomotive Junkyard
  3        Mt. Pocono
  3        Old Garage
  3        Patrick Diehl
  3        Piney Creek Drum
  3        Pottstown Abandoned Trailer
  3        Richardson Property
  3        Security Boulevard
  3        Semco PCB Site
  3        Springer Septic Services
  3        Stoneman Property
  3        Tinicum Marsh
  3        Vulcanized Rubber & Plastics
  3        Wheeling Hill
  3        Yokum Chlordane Contamination

  3        Total Sites - 26
 COMPLETION
    DATE

  2/1/1984
  6/8/1983
 5/19/1983
 3/24/1983
 1/25/1985
  9/6/1983
 9/28/1984
  8/8/1984
10/24/1984
 7/11/1985
 5/31/1984
 3/15/1984
 1/24/1984
  2/8/1985
  1/8/1985
  7/6/1985
  5/2/1985
  2/5/1985
  3/4/1985
10/31/1984
 2/13/1984
 6/19/1985
 9/23/1983
  7/6/1983
12/28/1983
 3/20/1984
   TOTAL
OBLIGATIONS
                                                         73
                                                          4
                                                         35
                                                          1
                                                        151
                                                        109

                                                        169
                                                         25
                                                         11
                                                         16
                                                          1
                                                         45
                                                          6
                                                         50
                                                         15
                                                        180
                                                         43
                                                        115
                                                        142
                                                         55
                                                          5
                                                        154
                                                         42
                                                          4
                                                         18
       ,656
       ,707
       ,181
       ,409
       ,238
       ,279
        797
       ,372
       ,000
       ,163
       ,657
       ,228
       ,729
       ,699
       ,678
       ,452
       ,583 21
       ,038
       ,830
       ,490
       ,412
       ,113
       ,968
       ,696
       ,570
       ,387
                                                     $1,481,332
  4
  4
  4
  4
  4
  4
  4
  4
  4
  4
  4
  4
  4
  4
Abandoned Drum                    7/28/1984
Abandoned Drum                    8/11/1983
Abandoned Drum/Hillsborough       9/17/1982
Abandoned Drum/Hillsborough       9/17/1982
Abandoned Drum/Marathon            1/1/1985
Ahoskie Midnight Dump             3/29/1985
Buckhorn Pesticide F1re           3/28/1985
Buford Highway                   11/20/1984
Bush Brothers Plating             8/31/1985
C. D. Buff                        3/21/1985
Caldwell County                   7/15/1983
Callahan Drum                    10/28/1983
Canton Plating & Bumper Works    12/19/1984
Cape Fear Wood Preserving         3/19/1985
                     $
     1,812
     1,821
     6,996
     3,976
     4,187
     3,000
    15,000
     5,000
   120,000
    20,000
    39,976
     7,963
   200,000
   150,000
                                     37

-------
                                                               EXHIBIT B
                                                               Page 3 of 6
REGION
NAME OF SITE
  4        Catoosa County Labpack
  4        Caustic Chemical
  4        Coal Branch Hollow  «
  4        Creosote Tanks Release
  4        Davenport Creosote Spill
  4        Everhart Lumber Site
  4        Ft Oglethorpe Drum
  4        GA Highway 138
  4        Gail Foster Property
  4        Hadaway Road
  4        Head PCB Spill
  4        Horry Co. Fireworks
  4        Ivy Road (Bessie Runner)
  4        J & L Drum Site
  4        Jimmy's Truck Stop
  4        Johnson Property Site
  4        Lake Kathy Road Spill
  4        Lake Worth Inlet
  4        Lummis Island
  4        McAllister Drum Site
  4        Midnight Dump
  4        Midnight Dumping (KY)
  4        Midnight Dumping/Guilford
  4        One-Hour Koretizing
  4        Payco Pallet and Drum
  4        PCB Midnight Dump
  4        Pembroke Pines
  4        Petro Chemical
  4        Rock Bridge Park
  4        Rome Coal Tar
  4        Roosevelt Highway Spill
  4        S. Electroformlng
  4        Scotts Creek Battery
  4        Simpson Road Drum
  4        Snapper Lane
  4        St. John River
  4        Unknown Chemical Discharge
  4        Villa Rica-H1gh Point Rd
  4        Western Carolina Smelting
  4        Williams Pesticide Site

  4        Total Sites - 54
 COMPLETION
    DATE

 4/30/1985
 7/20/1983
 6/24/1985
 9/28/1984
 8/19/1983
 5/23/1984
 2/28/1985
 4/12/1984
 7/13/1984
 4/29/1985
  2/7/1985
 2/18/1985
10/30/1984
10/26/1982
  5/1/1985
 4/16/1984
 1/18/1985
  6/4/1985
 4/10/1984
 1/13/1984
 8/24/1984
 7/28/1984
 7/17/1981
 7/30/1984
 4/10/1984
 2/15/1983
12/19/1982
10/28/1983
 1/25/1984
 5/19/1985
12/15/1983
 8/30/1984
 1/25/1985
 4/15/1985
10/14/1983
 10/3/1984
 12/3/1982
 5/17/1984
 12/5/1984
  4/9/1983
   TOTAL
OBLIGATIONS

 $    4,000
      9,930
     32,000
     50,000
     54,533
     10,500
      6,000
      5,544
      3,000
      3,000
     20,000
     90,000
     15,000
     40,782
     12,OOU
     50,000
     13,000
      2,158
     25,000
     87,025
     50,000
      9,529
      1,954
     14,000
     25,464
     36,019
     19,765
    175,858
     25,000
    100,000
     34,937
     28,000
     87,000
     27,000
      3,225
     11,284
      4,289
     16,612
     81,000
     10.616
 $1,874.75?
                                    38

-------
                                                              EXHIBIT B
                                                              Page 4 of 6
REGION
NAME OF SITE
 5        Abandoned Chemicals
 5        Abandoned Drum
 5        Abandoned Drum
 5        Abandoned Drums-Ecorse
 5        Bloomington Capacitor Site
 5        C-Way
 5        Chemical Drum
 5        Chicago Drum
 5        Cyanide Incident
 5        Drums on Beach
 5        Elkhart Site
 5        Floyd Hutter
 5        Fort & Scotten Streets
 5        GP & K, Inc.
 5        1-69
 5        Midnight Dump, W. 58th Street
 5        Midnight Dumping
 5        Millpoint (Spring Lake)
 5        Niles Township
 5        Oak Creek
 5        R. J. Trucking
 5        Seaway Warehouse
 5        Sorrento Site
 5        St. Louis River

 5        Total Sites - 24
 COMPLETION
    DATE

 4/18/1983
  7/3/1983
 7/16/1982
 6/27/1984
  2/1/1985
11/26/1984
  7/1/1982
 7/22/1984
 8/17/1984
  7/2/1982
 3/25/1985
 6/10/1984
 4/16/1984
 6/10/1985
  3/6/1985
 4/28/1983
 10/1/1981
  7/6/1984
 3/20/1985
 1/31/1985
  7/9/1985
 7/17/1984
 3/31/1984
 8/27/1984
   TOTAL
OBLIGATIONS

   $ 46,402
      1,569
      1,142
      6,095
     53,559
     21,749
      3,487
     22,317
        494
      2,628
     93,122
      1,424
      8,713
      9,428
     16,049
        456
     23,970
      2,501
     16,236
      5,000
     18,695
     28,443
      3,239
      1,103
   $387,82f
 6
 6
 6
 6
 6
 6
 6
 6
 6
 6
 6
 6
 6
Acrylonitril Spill                 4/3/1984
Amoco Dock 31                      3/8/1982
Chemical Drums-Padres Island     10/17/1984
Haddock Airport                    2/5/1985
Houston Ship Channel               1/4/1984
Jack Dennis Pesticide Burnsite    3/18/1983
Near Wills Point                  5/14/1983
Padre & Mustang Islands I         3/27/1985
Panther Creek                     3/11/1982
South of Waco                      5/5/1983
Stonewall Drug Dump               6/13/1985
Styrene Spill                     2/22/1984
W. J. Oil                          2/3/1984

Total Sites - 13
                      $  2,250
                         3,643
                         5,119
                        15,000
                         5,000
                        32,381
                         9,652
                       160,422
                         3,037
                         3,792
                         7,000
                         7,065
                        54,777
                      $309,138
                                    39

-------
                                                               EXHIBIT B
                                                               Page 5 of 6
REGION
NAME OF SITE
  7        Blue River Flood
  7        Flood Damage
  7        Franklin/Gimblin St.'
  7        Holly Street Drum Site
  7        Rockwood School District

  7        Total Sites -  5

  8        Gene Murren
  8        Green River Cyanide
  8        Montgomery Ward Store
  8        Vaagan-Dahle Farm

  8        Total Sites - 4

  9        A. S. Power Plant
  9        Abandoned Drum
  9        Abandoned Drum
  9        Angeles National Forest
  9        Big Spring Ranch
  9        Bloomfield Avenue
  9        Cherokee Trucking
  9        Crystal Cove Beach
  9        Cyanide Spill
  9        Drainage Ditch
  9        Echo Bay Station
  9        L. Fricker Co.
  9        Laguna Beach II
  9        Long Beach Drum
  9        M/V Victoria II Keehi Lagoon
  9        Mystery Dump
  9        N Tulip St. - Escondido
  9        Parkside Drive
  9        PCB Transformers
           (includes 31 subsites)
  9        Riverside Pesticide
  9        Roic-Sun Valley
COMPLETION
   DATE

6/30/1984
2/22/1983
 5/2/1984
6/29/1984
7/23/1984
                                  3/30/1984
                                  1/23/1985
                                  5/15/1984
                                  7/20/1984
                                  7/24/1984
                                  5/27/1982
                                  8/22/1984
                                  7/23/1982
                                  4/21/1983
                                  7/13/1984
                                  2/15/1985
                                  8/22/1983
                                  5/16/1985
                                   1/4/1984
                                  4/26/1983
                                  7/19/1985
                                  4/29/1984
                                  8/20/1984
                                  9/15/1985
                                 12/14/1981
                                  3/15/1985
                                  3/21/1984
                                  9/21/1984

                                  6/10/1985
                                  6/20/1985
   TOTAL
OBLIGATIONS

     36,006
     31,323
     26,537
     29,000
     49,007
                                                       $171,873
                     $ 16,268
                        3,000
                      106,000
                       24,419
                     $149.687
                     $ 27,321
                        1,580
                        2,000
                        4,370
                        3,780
                        3,243
                      105,503
                        3,561
                        8,500
                        1,994
                        9,015
                      175,999
                        1,266
                        1,069
                       50,000
                        6,989
                       44,541
                        6,231
                        4,707

                       27,490
                      100,000 2/
                                     40

-------
REGION
NAME OF SITE
  9        Sacramento River
  9        Satala Power Plant
  9        South Half Moon Bay
  9        Tafuna Power Plant
  9        Tuba City Acid Tank
  9        Unknown Chemical Drums
  9        Washo Drum

  9        Total Sites - 28

 10        Abandoned Drum
 10        Municipal Landfill
 10        Ohlson Mountain PCB
 10        PCB Contamination
 10        Spokane Drum Fire

           Total Sites - 5

           Total Completions - 182
COMPLETION
   DATE

2/16/1983
7/18/1984
8/14/1985
7/19/1984
9/10/1982
5/11/1983
8/28/1985
                                   3/9/1984
                                  5/20/1982
                                  8/23/1985
                                  6/17/1983
                                  6/21/1985
                                                               EXHIBIT B
                                                               Page 6 of 6
   TOTAL
OBLIGATIONS

   $  2,363
     20,214
     20,000
     40,276
     34,140
      1,394
      2,500
   $710,04F
                     $  1,058
                        6,181
                      101,399
                        8,571
                        3,000
                     $120,209'
                   $6,130,209
 I/  Financial Management Division's records shows an obligation through
     September 1985 of $675.

 2/  OWPE states that these sites are targeted for action in the SCAP.
                                     41

-------
                                                        EXHIBIT C
             COMPLETED NON-NATIONAL PRIORITY LIST REMOVAL SITES
Region

  1

  2

  3

  4

  5

  6

  7

  8

  9

 10
Totals
WITH CLEANUP COSTS BETWEEN
AND UNDER $500,000 IN VALUE THAT MAY
t
Total Number of
Completed Removal
Sites Between
$200,000 - $500,000
as of 09/30/85
1
1
5
4
3
2
1
2
0
0
19
$200,000
NOT BE RECOVERED
Total Obligations
of Removal Sites
Between
$200,000 - $500,000
as of 09/30/85
$ 400,112
293,332
1,648,633
1,108,000
970,907
460,878
442,140
437,000
0
0
$5,761,002
                                     42

-------
-p-
CO


SCHEDULE
THERE IS
OF SUPERFUND SITES THAT
EXHIBIT D
Page 1 of 2

A BANKRUPTCY CASE AGAINST
POTENTIAL RESPONSIBLE PARTIES

Region
1
2
2
3
3
3
4
5
5
5
5
5
5

Case/Site Name
Johns Manville, NH
Syncon Resins, Inc.
Combe Fill
Landfills, NJ
North
South
Bruin Lagoon, PA
Drake Cheml cal , PA
L.A. Clarke & Sons
American Creosote, FL
A&F Materials, IL
Electric Utilities
Corp, IL
Isantl Solvent, MN
Liquid Disposal , MI
Long, T.P. OH
Peerless Plating, MI

Total EPA Claim
Against Bankruptcy
Responsible Party
$1,100,000
1,867,596
228,530
88,879
1,222,446
1,200,000
65,492
7,000,000
100,000
176,575
777,727
321,505
37,859
139,339
(Note 1)
Date of
Bankruptcy
8/26/82
10/19/81
11/13/81
02/08/77
00/00/81
03/11/83
05/21/82
Not Known
09/19/83
07/00/83
04/00/82
05/29/81
08/22/83

Date of
Claim
11/30/84
03/21/83
01/22/86
12/09/83
12/20/83
11/02/84
07/22/82
06/00/83
10/19/84
09/13/83
01/13/83
07/29/83
01/01/85

Total CERCLA
Funds Spent
Through
Sept. 30, 1985
$1,100,000
2,809,732
228,530
88,879
3,578,356
1,630,341
Not Known
1,261,724
586,694
1,000,000
995,000
2,777,247
37,859
147,650

Total Funds
Awarded Notes
$ -0-
-0-
-0-
_o-
-0-
-0-
-0-
-0-
-0-
-0-
-0-
-0-
-0-
37,859 Note 2
-0-

-------
                                                                                EXHIBIT D
                                                                                Page 2 of 2
5
5
6
6
6
7
7
9
Thomas Solvent, MI
Crystal Chemical, TX
Hardage Disposal Site
Metcoa, TX
Triangle Chemical, TX
Aidex Corp, IA
Charter, MO
Metate Asbestos
4,335,006
814,879
979,550
332,669
148,653
12,000
34,000,000
2,297,000
$57,245,705
04/06/84
09/24/81
01/28/85
Not Known
06/00/81
02/05/79
04/20/84
02/25/83
08/21/84
07/15/82
06/03/85
01/24/84
09/23/82
06/22/81
11/18/84
08/10/83
3,477,195
1,548,152
Not Known
336,798
332,669
2,214,015
34,000,000
7,000,000
$65,150,841
                                                                                  ==========
   -0-
   -0-
   -0-
   -0-
   -0-
 10,000 Note 3
   -0-
   -0-
$47,859 Note 4
Total Sites
        22
Notes
Note 1
 Note 2
 Note 3
 Note 4
 The above information is a result of OECM's generated data.  The column "Total CERCLA
 Funds Spent Through September 30, 1985" does not represent the actual expenditures as of
 September 30, 1985.  They may represent estimates, funds expended through the date of
 claim, and approximate amounts through this period.  The current FMS does not show all
 site specific costs.  Thus, it is difficult to obtain the exact expenditures per site.  To
 obtain such amounts it would require Agency personnel to go to many different
 sources.
 EPA received $14,198 as payment for this case.
 EPA received $12,967 as payment for this case.
 EPA received $27,165 as payment for this amount.

-------
                                    NEGOTIATIONS AS OF SEPTEMBER 30, 1985
                                                   (Note 1)
                                                                                            EXHIBIT  E
                                                                                            Page 1  of  11
REG
NAME OF SITE
     Beacon Heights Landfill
     Laurel Park, Inc.
     Charles George
     Grovel and Wells 1 & 2
     Hocomonco Pond
     Norwood PCB/Grant Gear
     Plymouth Harbor
     Resolve Inc
     Salem Acres
     Silreslm Chemical
     McKin Co.
     O'Connor Site
     Ulnthrop Town Landfill
     Coakley Landfill
     Exxon
     Flmble Door
     Gonic (Two Drum Sites)
     Keefe Environmental Services
     Rodgers Mobile Home
     Savage
     Central Landfill
     Landfill & Resource Recovery
     Peterson/Puritan Inc
     P1c1llo Farm
     Stamina Mills
     Western Sand and Gravel
                         (KES)
 QUARTER
INITIATED

3rd Qtr 85
3rd Qtr 84
3rd Qtr 85
2nd Qtr 85
3rd Qtr 85
3rd Qtr 85
1st Qtr 85
3rd Qtr 85
2nd Qtr 85
3rd Qtr 84
2nd Qtr 85
2nd Qtr 85
3rd Qtr 85
2nd Qtr 85
3rd Qtr 85
3rd Qtr 85
4th Qtr 84
Not Known
3rd Qtr 85
4th Qtr 85
2nd Qtr 85
3rd Qtr 84
Not Known
3rd Qtr 85
3rd Qtr 85
2nd Qtr 84
 QUARTER
COMPLETED
                                                    3rd Qtr 85
4th Qtr 85
4th Qtr 85

4th Qtr 85
3rd Qtr 85
1st Qtr 86

1st Qtr 85
2nd Qtr 85
                                                    1st Qtr 85
                                                    1st Qtr 85
                                                    4th Qtr 85
 ESTIMATED LENGTH
   OF NEGOTIATION
THRU FY 86 2nd QTR.

    315 days
    360 days
    315 days
    405 days
    315 days
    315 days
    495 days
    315 days
    405 days
    450 days
    225 days
    405 days
     90 days
     90 days
    180 days
    315 days
     90 days
    Not Known
    315 days
    225 days
    405 days
    180 days
    Not Known
    315 days
    315 days
    540 days
OUTCOME
                                   Settlement
NOTES
Settlement
Settlement

Settlement    (2)
Fund Fin. Action
Unilateral Order

Fund Fin. Action
Cost Recovery
                                   Fund Fin.  Action
                                   Fund Fin.  Action
                                   Settlement
              (2)

-------
                                                                                            EXHIBIT E
                                                                                            Page 2 of 11
REG
NAME OF SITE
     Abestos Dump
     Chemical Leaman Tank Lines, Inc.
     D'lmpeMo Property
     Fried Industries
     GEMS
     GEMS
     Johnson & Towers
     Johnson & Towers
     KIN-BUC Landfill
     King of Prussia
     Lipari Landfill
     Llpari Landfill
     Lone P1ne Landfill
     Lone P1ne Landfill
     M & T Dellsa
     MKY Corporation
     Price Landfill
     Quanta Resources
     Quanta Resources
     Ringwood Mines
     Scientific Chemical Processing (Carl)
     Scientific Chemical Processing (Carl)
     Scientific Chemical Processing (Newark)
     Syncon Resins
     Tabernacle Drum Dump
     Clothier Disposal
     Fulton Terminals
     G. M. Central Foundry
     Hudson River PCB's
 QUARTER
INITIATED

3rd Qtr 84
2nd Qtr 85
2nd Qtr 85
3rd Qtr 85
3rd Qtr 85
4th Qtr 85
2nd Qtr 85
2nd Qtr 85
1st Qtr 85
1st Qtr 84
3rd Qtr 84
2nd Qtr 85
1st Qtr 84
1st Qtr 85
3rd Qtr 85
4th Qtr 85
2nd Qtr 85
3rd Qtr 85
2nd Qtr 85
2nd Qtr 85
3rd Qtr 85
3rd Qtr 85
3rd Qtr 85
3rd Qtr 85
2nd Qtr 84
2nd Qtr 85
2nd Qtr 85
2nd Qtr 84
1st Qtr 84
 QUARTER
COMPLETED

3rd Qtr 85
4th Qtr 85
3rd Qtr 85
                                                    3rd Qtr 85
                                                    3rd Qtr 85
                                                    1st Qtr 86
                                                    3rd Qtr 85

                                                    3rd Qtr 85

                                                    1st Qtr 86



                                                    2nd Qtr 85
                                                    3rd Qtr 85
                                                    3rd Qtr 85
 ESTIMATED LENGTH
  OF NEGOTIATION
THRU FY 86 2nd QTR.

    360 days
    180 days
     90 days
    315 days
    315 days
    225 days
    405 days
    405 days
    180 days
    540 days
    675 days
    405 days
   Not Known
    495 days
    315 days
     90 days
     90 days
    315 days
     90 days
    405 days
    180 days
    315 days
    315 days
    315 days
    360 days
    405 days
    405 days
    450 days
    540 days
OUTCOME

Settlement
Settlement
Not Known
NOTES
                                                                                                     (2)
                                   Cost Recovery
                                   Settlement
                                   Fund Fin.  Action


                                   Settlement
                                   Settlement

                                   Settlement

                                   Settlement
                                                 (4)
                                   Unilateral  Action
                                   Settlement
                                   Fund  Fin. Action

-------
                                                                                            EXHIBIT  E
                                                                                            Page 3 of  11
REG
NAME OF SITE
     Olean Wellfield(McGraw-Edlson)
     Pollution Abatement Services (PAS)
     SAG Harbor/Nabisco
     Volney Landfill
     Wide Beach
     Fibers Public Supply Wells
     Frontera Creek
     Juncos Landfill
     Puerto Rico Chemical
     Upjohn Facility

     Dover AFB
     Harvey & Knott Drum
     Tybouts Corner Landfill
     Tybouts Corner Landfill
     Limestone Road
     Mid-Atlantic Wood Preservers
     Sand Gravel & Stone
     United Rigging
     Ambler Asbestos Site
     Amchem Dioxin
     Domino Salvage Yard
     Drake Chemical
     Fischer & Porter
     Havertown PCP Site
     Henderson Road
     Lackawanna Refuse
     Lavelle Borehole
     Letterkenny Army Depot
     McaDoo Associates
     Mill Creek
 QUARTER
INITIATED

3rd Qtr 85
3rd Qtr 85
1st Qtr 85
2nd Qtr 85
3rd Qtr 85
4th Qtr 85
3rd Qtr 85
2nd Qtr 84
4th Qtr 84
1st Qtr 84

1st Qtr 85
3rd Qtr 85
4th Qtr 84
2nd Qtr 85
3rd Qtr 84
3rd Qtr 85
4th Qtr 84
3rd Qtr 85
1st Qtr 85
2nd Qtr 84
2nd Qtr 85
1st Qtr 85
1st Qtr 84
4th Qtr 84
3rd Qtr 85
4th Qtr 85
3rd Qtr 85
1st Qtr 85
3rd Qtr 84
3rd Qtr 84
 QUARTER
COMPLETED
                                                    3rd Qtr 85
                                                    1st Qtr 86
                                                    Not known
                                                    1st Qtr 85
                                                    1st Qtr 85

                                                    Not Known

                                                    2nd Qtr 86
                                                    4th Qtr 85
                                                    3rd Qtr 85
                                                    4th Qtr 85
                                                    4th Qtr 85
                                                    2nd Qtr 85
                                                    1st Qtr 85
                                                    1st Qtr 85
                                                    1st Qtr 86

                                                    1st Qtr 86
                                                    2nd Qtr 85
                                                    1st Qtr 85
 ESTIMATED LENGTH
  OF NEGOTIATION
THRU FY 86 2nd QTR.

    315 days
    315 days
    180 days
    405 days
    315 days
     90 days
    315 days
    270 days
    585 days
    855 days
                  315 days
                   90 days
                  405 days
                  675 days
                  315 days
                  540 days
                   90 days
                  180 days
                  540 days
                  180 days
                   90 days
                  360 days
                   90 days
                  180 days
                  225 days
                  180 days
                   90 days
                  180 days
                  67b days
OUTCOME
                                   Fund Fin.
NOTES
          Action
              (2)
                                   Settlement
                                   Fund Fin.  Action
                                   Settlement
                     Transferred to RCRA(2)

                     Settlement

                     Fund Fin. Action (2)

                     Settlement
                     Settlement
                     Fund Fin. Action (3)
                     Settlement       (2)
                     Fund Fin. Action
                     Not Known
                     Settlement
                     Unilateral Order
                     Settlement

                     Fund Fin. Action
                     Fund Fin. Action (2)
                     Not Known

-------
                                                                                               EXHIBIT E
                                                                                               Page 4 of 11
   REG
    NAME OF SITE
00
Moyers Landfill
Palmerton Z1nc
Swissvale Auto Parts
Taylor Borough Dump
Tyson's Dump
Tyson's Dump
United Metal Traders
Westinghouse #2
Avtex Fibers Site
Culpepper Wood Preservers
Defense General Supply FF
East Kane Tar Pits
Fort A. P. H111
Hampton Cylinders (Moor-F1ta)
IBM Manassas Site
Big John's Gullet Pile
B1g John's Salvage-Holt Rd
Georges Creek
Helzer Creek
Manila Creek D1ox1n
Mobay Chemical
Monsanto (Plant Road)
Monsanto Landfill
Monsanto Plant
Nitro Dump
Ordnance Works Disposal
Poca Mine
Smith Douglas
South Charleston
 QUARTER
INITIATED

3rd Qtr 85
4th Qtr 84
3rd Qtr 84
3rd Qtr 85
1st Qtr 85
4th Qtr 85
Not Known
4th Qtr 84
2nd Qtr 85
3rd Qtr 85
1st Qtr 85
4th Qtr 85
1st Qtr 85
1st Qtr 85
3rd Qtr 85
4th Qtr 84
2nd Qtr 85
1st Qtr 85
1st Qtr 85
1st Qtr 85
3rd Qtr 85
1st Qtr 84
1st Qtr 85
4th Qtr 84
1st Qtr 85
4th Qtr 84
1st Qtr 85
4th Qtr 85
1st Qtr 85
 QUARTER
COMPLETED
                                                                4th Qtr 85
                                                                2nd Qtr 85

                                                                2nd Qtr 85

                                                                1st Qtr 85
2nd Qtr 85
1st Qtr 86
4th Qtr 85
1st Qtr 85

4th Qtr 85
4th Qtr 85
4th Qtr 85

3rd Qtr 85
4th Qtr 85

4th Qtr 85
1st Qtr 85
4th Qtr 85

4th Qtr 85
 ESTIMATED LENGTH
   OF NEGOTIATION
THRU FY 86 2nd QTR,

    315 days
    360 days
    270 days
    315 days
     90 days
    225 days
   Not Known
    585 days
    405 days
    315 days
    495 days
    225 days
     90 days
    360 days
     90 days
     90 days
    405 days
    270 days
    270 days
    270 days
    315 days
    540 days
    270 days
    585 days
    270 days
     90 days
    270 days
    225 days
    270 days
OUTCOME
NOTES
                                   Settlement
                                   Settlement

                                   Not Known

                                   Settlement
Settlement
Settlement
Civil Action Ref.
Unilateral Order

Not Known
Settlement
Settlement

Settlement
Settlement

Settlement
Fund Fin. Action
Settlement     (1)

Not Known

-------
                                                                                           EXHIBIT E
                                                                                           Page  5 of  11
REG
NAME OF SITE
     Perdido Groundwater Contamination
     Saraland Apartments
     City Industries
     H1pps Road Landfill
     HolUngsworth Solderless Terminal Co,
     Miami Drum Services
     NW 58th Street
     Pickettvllle Road Landfill
     Zellwood Ground Mater Contamination
     Marzone/Chevron Co
     Powersv1lie
     A1rco
     Harrison City
     Flowood
     Gautier 011(Seaboard)
     Chemtronlcs Inc
     Dockery Property
     Mart1n-Mar1etta/Sodyeco
     Potter Pits
     Independent Nail
     Medley Farms
     Palmetto Wood Preserving
     Palmetto Wood Preserving
     Galloway Pits

     Acme Solvent Reclaiming
     Alburn Indnerator/HAAS
     Crab Orchard/Sangamo Dump
     Cross Brothers
     Environmental Dynamics
     KERR-MCGEE
 QUARTER
INITIATED

1st Qtr 85
3rd Qtr 85
4th Qtr 85
2nd Qtr 85
4th Qtr 85
2nd Qtr 85
2nd Qtr 85
4th Qtr 85
3rd Qtr 84
1st Qtr 85
1st Qtr 85
1st Qtr 85
4th Qtr 85
3rd Qtr 85
2nd Qtr 85
3rd Qtr 85
4th Qtr 85
3rd Qtr 84
4th Qtr 85
4th Qtr 85
4th Qtr 85
4th Qtr 85
2nd Qtr 85
4th Qtr 85

3rd Qtr 85
3rd Qtr 85
4th Qtr 84
2nd Qtr 85
2nd Qtr 84
3rd Qtr 84
 QUARTER
COMPLETED

1st Qtr 86
4th Qtr 85
                                                   2nd Qtr 85
                                                   3rd Qtr 85
                                                   1st Qtr 86
                                                   1st Qtr 86

                                                   2nd Qtr 86
                                                   3rd Qtr 85
                                                   4th Qtr 85
                                                   3rd  Qtr  85
                                                   2nd  Qtr 86
                                                   2nd  Qtr 86
                                                   3rd  Qtr 85
                                                   2nd  Qtr 85
 ESTIMATED LENGTH
  OF NEGOTIATION
THRU FY 86 2nd QTR.

    360 days
     90 days
    225 days
    405 days
    225 days
    405 days
    405 days
    225 days
    270 days
    180 days
    360 days
    360 days
    225 days
    270 days
     90 days
     90 days
    225 days
    675 days
    225 days
    225 days
    225 days
    225 days
     90 days
    225 days

    315 days
    270 days
    540 days
     90 days
    360 days
    675 days
OUTCOME

Settlement
Settlement
NOTES
                                   Fund F1n.  Action
                                   Settlement
                                   Fund F1n.  Action
                                   Settlement

                                   Settlement
                                   Settlement
                                   Settlement
                                   Not  Known
                                   Unilateral  Order
                                   Civil  Action  Ref.
                                   Settlement
                                   Fund  Fin. Action
                                   Settlement     (2)

-------
                                                                                                EXHIBIT E
                                                                                                Page 6 of 11
    REG
    NAME OF SITE
Ul
o
KERR-MCGEE
KERR-MCGEE (Kress Creek/West Branch)
KERR-MCGEE(Reed-Keppler)
KERR-MCGEE(Residential Areas)
KERR-MCGEE(Sewage Treatment Plant Site)
NL Industries/Taracorp Lead Smelter
Pagel1s Pit
Riverdale Chemical Co
Sheffield (U. S. Ecology)
Velslcol Chemical Corp
Uauconda Sand & Gravel
American Chemical Service
Bennett Stone Quarry
D1mar Corp
Enviro-Chem
Fisher-Calo
Fort Wayne Reduction Dump
Lemon Lane Landfill
Main Street Well Field
Main Street Well Field
Midco I
M1dco I
Midco II
Midco II
Meal's Dump
Neal's Landfill
Seymour Recycling
Wayne Waste 011
Wedzeb Enterprises
Westlnghouse Sites
American Steel Works
Berlin & Farro
Berlin & Farro
Burrows Sanitation
QUARTER
INITIATED
1st Qtr 84
Not Known
Not Known
Not Known
Not Known
1st Qtr 85
4th Qtr 85
4th Qtr 84
2nd Qtr 85
1st Qtr 85
4th Qtr 84
3rd Qtr 85
Not Known
3rd Qtr 85
3rd Qtr 84
3rd Qtr 85
3rd Qtr 85
Not Known
3rd Qtr 85
3rd Qtr 85
1st Qtr 84
2nd Qtr 85
1st Qtr 85
2nd Qtr 85
Not Known
Not Known
1st Qtr 84
4th Qtr 85
2nd Qtr 84
1st Qtr 84
4th Qtr 85
1st Qtr 84
3rd Qtr 85
3rd Qtr 85
QUARTER
COMPLETED

4th Qtr 85
4th Qtr 85
4th Qtr 85
4th Qtr 85
3rd Qtr 85
1st Qtr 86
2nd Qtr 85
4th Qtr 85
4th Qtr 85

1st Qtr 86
3rd Qtr 85
4th Qtr 85
1st Qtr 86
1st Qtr 86
4th Qtr 85
3rd Qtr 85
4th Qtr 85
4th Qtr 85
3rd Qtr 85
3rd Qtr 85
3rd Qtr 85
3rd Qtr 85
3rd Qtr 85
3rd Qtr 85

1st Qtr 86
1st Qtr 86
3rd Qtr 85
Not Known

2nd Qtr 86
4th Qtr 85
 ESTIMATED LENGTH
   OF NEGOTIATION
THRU FY 86 2nd QTR,

    855 days
   Not Known
   Not Known
   Not Known
   Not Known
    180 days
     90 days
    180 days
    180 days
    270 days
    585 days
    180 days
    Not Known
     90 days
    540 days
    180 days
     90 days
   Not Known
     90 days
     90 days
    540 days
     90 days
    180 days
     90 days
    Not Known
    Not Known
    855 days
     90 days
    630 days
    540 days
    Not Known
    8B5 days
    225 days
     90 days
OUTCOME
NOTES
Fund Fin. Action
Fund Fin. Action
Fund F1n. Action
Fund F1n. Action
Settlement
Not Known
Settlement
Settlement     (2)
Fund F1n. Action

Not Known
Settlement
Settlement
Not Known
Not Known
Fund Fin. Action
Settlement
Settlement
Settlement
Settlement
Settlement
Settlement
Settlement
Settlement
Settlement

Not Known
Unilateral
Settlement
Settlement

Settlement
Fund Fin. Action

-------
                                                                                            EXHIBIT  E
                                                                                            Page 7 of 11
REG
NAME OF SITE
     Dow Chemical Co (Midland)
     Ionia City Landfill
     K. L. Avenue Landfill
     K. L. Avenue Landfill
     Kareckas Farm
     Kentwood Landfill
     Mason County Landfill
     MES Co/Joe Wilds
     Metamora Landfill
     OTT/Story/Cordova Chemical
     Packaging Corp of America
     Tar Lake
     U. S. Aviex '
     Whitehall Municipal Wells
     Burlington Northern
     FMC-Northern Ordinance
     Isantl
     Joslyn Manufacturing & Supply
     New Brighton/Arden Hills
     NL/Taracorp
     Rellly Tar & Chemical Corp
     South Andover(Andover Sites)
     South AndoverJAndover Sites)
     St. Louis River
     University of Minnesota
     Whlttaker Corp
     American Steel Drum
     Arcanum Iron & Metal
 QUARTER
INITIATED

3rd Qtr 84
3rd Qtr 85
3rd Qtr 85
4th Qtr 85
1st Qtr 85
3rd Qtr 85
4th Qtr 85
2nd Qtr 85
3rd Qtr 85
1st Qtr 84
2nd Qtr 84
3rd Qtr 84
3rd Qtr 85
3rd Qtr 84
1st Qtr 84
2nd Qtr 85
2nd Qtr 85
1st Qtr 84
2nd Qtr 84
4th Qtr 84
1st Qtr 84
2nd Qtr 85
4th Qtr 85
2nd Qtr 85
3rd Qtr 85
2nd Qtr 85
1st Qtr 85
4th Qtr 85
 QUARTER
COMPLETED

2nd Qtr 85
4th Qtr 85
1st Qtr 86
2nd Qtr 86
2nd Qtr 85
1st Qtr 86
1st Qtr 86
3rd Qtr 85
4th Qtr 85
2nd Qtr 86
2nd Qtr 85
1st Qtr 86
4th Qtr 85
3rd Qtr 85
2nd Qtr 85
1st Qtr 86
1st Qtr 86
Not Known

2nd Qtr 85
3rd Qtr 85
4th Qtr 85

2nd Qtr 86
                                                    2nd Qtr 85
                                                    1st Qtr 86
 ESTIMATED LENGTH
   OF NEGOTIATION
THRU FY 86 2nd QTR.

      270 days
       90 days
      180 days
      180 days
       90 days
      180 days
       90 days
       90 days
       90 days
      810 days
      360 days
      540 days
       90 days
      360 days
      450 days
      270 days
      270 days
      Not Known
      720 days
      180 days
      540 days
      180 days
      225 days
      360 days
      315 days
      405 days
       90 days
       90 days
OUTCOME
NOTES
                                                                                       Settlement
                                                                                       Settlement
                                                                                       Not Known
                                                                                       Fund Fin. Action(2)(3)
                                                                                       Settlement
                                                                                       Not Known
                                                                                       Not Known
                                                                                       Settlement
                                                                                       Fund F1n. Action (2)
                                                                                       Fund Fin. Action
                                                                                       Settlement
                                                                                       Not Known
                                                                                       Settlement
                                                                                       Settlement
                                                                                       Settlement
                                                                                       Not Known
                                                                                                        (4)
                                                                                      Transferred to State(2)

                                                                                       Settlement
                                                                                       Settlement
                                                                                       Fund Fin. Action
                                                                                       Fund  Fin.  Action
                                   Unilateral Order
                                   Not Known
                                                                                                        (2)

-------
                                                                                                EXHIBIT  E
                                                                                                Page  8 of  11
    REG
    NAME OF SITE
Ul
ro
Cecil Undsey
Mid-South
Bayou Bonfouca
Bayou Sorrel 1
Citgo
Cleve Reber
Cleve Reber
Homestake Mining
Lee Acres(DOI)
South Valley
South Valley
Hardage/Crlner   .
Okemah Drum Site
Bailey Waste Disposal
Bio-Ecology Systems
Brio Refinery
Brio Refinery
Crystal Chemical
Crystal City
Dixie 011 Processors
French Limited
Harris-Farley Street
Hastings Radio Chemical
Hill Sand Co
Industrial Transformers
Koppers
Motco
Motco
Odessa Chromium  I
Odessa Chromium  II
Petrochemical System
Sheridan Disposal
South Cavalcade
 QUARTER
INITIATED

4th Qtr 85
4th Qtr 85
3rd Qtr 85
2nd Qtr 85
3rd Qtr 85
3rd Qtr 85
3rd Qtr 85
3rd Qtr 85
3rd Qtr 85
1st Qtr 84
3rd Qtr 84
2nd Qtr 85
3rd Qtr 85
2nd Qtr 85
1st Qtr 84
1st Qtr 85
1st Qtr 85
4th Qtr 84
3rd Qtr 85
4th Qtr 85
1st Qtr 85
3rd Qtr 84
4th Qtr 85
1st Qtr 85
3rd Qtr 85
1st Qtr 85
4th Qtr 84
4th Qtr 84
1st Qtr 85
1st Qtr 85
1st Qtr 85
3rd Qtr 85
1st Qtr 85
 QUARTER
COMPLETED

1st Qtr 86

4th Qtr 85

4th Qtr 85
1st Qtr 86
4th Qtr 85

4th Qtr 85
1st Qtr 85
2nd Qtr 85

4th Qtr 85
3rd Qtr 85
2nd Qtr 85
3rd Qtr 85
2nd Qtr 85

4th Qtr 85

3rd Qtr 85
4th Qtr 85
                                                                 4th  Qtr  85
                                                                 2nd  Qtr  85
                                                                 2nd  Qtr  85
                                                                 2nd  Qtr  85
                                                                 3rd  Qtr  85
                                                                 3rd  Qtr  85
                                                                 2nd  Qtr  85

                                                                 2nd  Qtr  85
 ESTIMATED LENGTH
   OF NEGOTIATION
THRU FY 86 2nd QTR,

       90 days
      225 days
       90 days
      405 days
       90 days
      180 days
       90 days
      315 days
       90 days
      360 days
      270 days
      405 days
       90 days
       90 days
      450 days
      180 days
       90 days
      585 days
       90 days
      225 days
      180 days
      450 days
      225 days
      495 days
       90 days
       90 days
      180 days
      180 days
      180 days
      180 days
       90 days
      315 days
       90 days
OUTCOME
NOTES
Not Known

Fund F1n. Action

Settlement
Not Known
Not Known

No Action
Settlement
Fund F1n. Action

Settlement
Fund Fin. Action
Fund Fin. Action
Settlement
Settlement

Fund Fin. Action

Settlement
Settlement
                                   Fund Fin.  Action
                                   Settlement
                                   Fund Fin.  Action
                                   Civil  Action Ref.
                                   Fund Fin.  Action
                                   Fund Fin.  Action
                                   Fund Fin.  Action

                                   Settlement

-------
                                                                                                 EXHIBIT E
                                                                                                 Page 9 of 11
     REG
    NAME OF SITE
in
Co
      8
A1dex
Chemplex
Mason City Coal
Cherokee County
Cortland Container
John's Sludge Pond
Elliot Shooting Park
Findett
Fulbrlght Landfill
Riverfront Landfill
Riverfront Landfill
St. Joseph Landfill
Union Carbide Agricultural Prod.
Environmental Services Inc
Hastings G. W. Contamination

Anaconda Smelter
Anaconda(Mill Creek)
Burlington Northern RR
California Gulch
Denver Radium
Denver Toluene
H111 AFB
Koppers Co
Martin Marietta/Denver Aerospace
Micronutrlents International
Ogden Defense Depot
PDC Spas
Sharon Steel/Midvale Smelter
Smuggler Mt.
Tooele Army Depot
Wasash Chem
 QUARTER
INITIATED

2nd Qtr 84
1st Qtr 85
4th Qtr 85
4th Qtr 85
3rd Qtr 84
1st Qtr 84
4th Qtr 85
2nd Qtr 85
3rd Qtr 85
2nd Qtr 85
3rd Qtr 85
4th Qtr 85
4th Qtr 85
4th Qtr 84
4th Qtr 85

3rd Qtr 84
4th Qtr 85
1st Qtr 85
4th Qtr 85
2nd Qtr 85
4th Qtr 85
3rd Qtr 85
1st Qtr 85
3rd Qtr 85
4th Qtr 85
3rd Qtr 85
1st Qtr 85
2nd Qtr 85
2nd Qtr 85
3rd Qtr 85
4th Qtr 85
 QUARTER
COMPLETED

Not Known
2nd Qtr 85
                                                                  1st Qtr 85

                                                                  1st Qtr 86
                                                                                 ESTIMATED LENGTH
                                                                                   OF NEGOTIATION
1st Qtr 85
1st Qtr 86
1st Qtr 86

4th Qtr 85
1st Qtr 86
2nd Qtr 86

2nd Qtr 86
2nd Qtr 86

2nd Qtr 85
3rd Qtr 85
4th Qtr 85
THRU FY 86 2nd QTR.
Not
90
225
22b
180
855
90
405
315
405
315
225
225
585
225
180
90
360
225
180
90
270
495
270
180
315
90
90
180
315
225
Known
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
days
OUTCOME

Not Known


Unilateral

Settlement








Settlement
Settlement
Settlement

Fund Fin.
Unilateral
Settlement

Settlement
Settlement

Unilateral
Fund Fin.
Settlement


NOTES
(4)



Order




(2)
(3)








Action
Order





Order
Action




-------
                                                                                                EXHIBIT  E
                                                                                                Page  10  of 11
    REG
    NAME OF SITE
    NAME OF SITE
    10
Ul
*•-,.
NOTES
Indian Bend Mash Area
L1tchf1eld Airport Area
Aerojet General
Del Norte City Pesticide Storage Area
Falrchlld Camera & Instrument Mt. View
Intel Mt. View
Montrose Chemical
NEC Electronics
Norwalk Dump
Raytheon
Slltec Corp

Bunker H111
Bonneville Power Adm
Gould Inc
Martin Marietta Aluminum
Commencement Bay, S. Tacoma (12A)
Commencement Bay/Tacoma Tar Pits
Northslde Landfill
Queen City Farms Inc
Strandley
Western Processing Co
Williams & Son
 QUARTER
INITIATED

3rd Qtr 84
3rd Qtr 84
4th Qtr 84
4th Qtr 85
3rd Qtr 85
3rd Qtr -85
2nd Qtr 84
3rd Qtr 85
3rd Qtr 85
3rd Qtr 85
3rd Qtr 85

2nd Qtr 85
1st Qtr 85
2nd Qtr 85
2nd Qtr 85
3rd Qtr 84
3rd Qtr 84
Not Known
4th Qtr 85
1st Qtr 85
3rd Qtr 85
2nd Qtr 85
 QUARTER
COMPLETED

2nd Qtr 85
2nd Qtr 85
2nd Qtr 86

4th Qtr 85
4th Qtr 85
2nd Qtr 85
4th Qtr 85
4th Qtr 85
4th Qtr 85
4th Qtr 85
2nd Qtr 85
4th Qtr 85
4th Qtr 85
1st Qtr 85
1st Qtr 85
1st Qtr 85
1st Qtr 86
3rd Qtr 85

4th Qtr 85
 ESTIMATED LENGTH
   OF NEGOTIATION
THRU FY 86 2nd QTR.

      270 days
      270 days
      540 days
      225 days
       90 days
       90 days
      360 days
       90 days
       90 days
       90 days
       90 days

      405 days
       90 days
      180 days
      180 days
      180 days
      180 days
      Not Known
       90 days
      180 days
      315 days
      180 days
OUTCOME
NOTES
                                                                                                    Settlement
                                                                                                    Unilateral Ord
                                                                                                    Settlement

                                                                                                    Settlement
                                                                                                    Settlement
                                                                                                    Fund Fin. Action
                                                                                                    Settlement
                                                                                                    Civil Action  Ref.
                                                                                                    Settlement
                                                                                                    Settlement
Settlement
Settlement
Settlement
Settlement
Settlement
Fund Fin. Action
Settlement
Settlement

Settlement
(1)  The Information above was generated from OWPE's  SCAP report  on  negotiations dated 10/25/85 and
     5/16/86.  These negotiations were ongoing prior  to FY 85,  Initiated  in  FY 85, completed in FY 86
     (2nd quarter), or FY 85 negotiations ongoing thru FY 86 (2nd quarter).   The estimated  length of
     negotiation was obtained by giving a value of 90 days for  each  full  quarter and giving a value
     of 45 days for each initiated and completed quarter.

-------
                                                                                                EXHIBIT  E
                                                                                                Page 11  of 11


(2) The Information was not shown on the FY 86 SCAP report as being transferred; thus we were unable to determine
    the status of negotiations.  We requested the Information from the Office of Waste Program Enforcement, Compliance
    Branch (OWPE - CB) and they provided us with Information on a quarter completed basis, status(ongoing/transferred)
    and Initiated date 1f needed.  We  did not put 1n this chart negotiations which were In the FY 85 SCAP report,
    but were told that they were completed in FY84 In the review by the above mentioned office.  We also did not
    Include Information on two sites which we were told were Federal facilities and should not be Included In  SCAP.

(3) The dates were changed since they were apparent mistakes and OWPE corrected them.

(4) The outcome was found as a bankrupt case (See Exhibit D).
Oi
Ul

-------
                                                          APPENDIX 1
                                                          Page 1 of 5
            UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                          WASHINGTON, D.C.  20460


                              SEP  I 0086
                                                                 OFFICE OF
                                                      SOLID WASTE AND EMERGENCY RESPONSE
MEMORANDUM


SUBJECT:  Draft Consolidated Report on EPA's Cost Recovery
          Actions Agains-t Potential Responsible Parties
                   Ff(  •     "
   FROM:  jLltattftOflP«
          Assistant Administrator
           \y
     TO:  Ernest E. Bradley 111
          Assistant Inspector General for Audit


     Thank you for the opportunity to respond to the subject audit report.
We are  concerned that the findings as they are presented in the report do not
reflect the  total  scope  of  the  enforcement  program.  The  enforcement program
has  three basic strategies.   First, we  negotiate with  the responsible party
or parties to undertake  the cleanup or to pay EPA upfront for the costs  of
the  cleanup (cashout).   If  the  negotiations fall,  EPA then has two remaining
choices:  Either  to take the responsible party to court to compel a cleanup
 action or to use  the Fund and subsequently to recover the costs of cleanup
 from the responsible party.  We feel that it would provide balance to the S®e APPendix
 report to include the number of settlements we have achieved that require   ote
 responsible parties to clean up the site.  As on September 30, 1985, we had
 settlements worth approximately $477 million in cleanup,  175 cases filed
 worth  $306 million in cleanup, and $137 million filed  for cost recovery.

      Another concern we have about the report is the cost recovery  ratio  of
 1.1 percent of Trust Fund  expenditures.  We feel  that this  is a  very poor
 characterization  of our cost recovery  program for*a number  of reasons.   First,
 the analysis compares total funds obligated with total cash received through gee
  cost recovery as of September 30, 1985.  Using the total funds obligated is  Append!
  not indicative of the site work that  is completed, the  time  it  takes to      Note 2
  prepare a case once work is complete, and  the existance  of a viable responsible
  party at those sites where work  has  been done.   Additionally, the scope of
  your  audit  was limited to removals,  yet  your analysis takes  into consideration
  all Superfund costs.   Finally, all Superfund costs are not cost recoverable.
  For  instance, it is Agency policy not to recover research and development
  costs.
                                        56

-------
                                                           APPENDIX 1
                                                           Page 2 of 5
     A better characterization would be to compare the amount of funds
expended at a completed site that has a viable responsible party, to the
amount of cost recovery achieved through cases filed and cases in negotiation.
It should be mentioned that in FY 1986, we expect to double the amount of
cost recovery that we achieved In. the first five year of the fund.

     Our next concern is your statement on page 10 that, "potentially over
$60 million will be lost to the fund in the next 20 years if cost recov- See Appendix 2
erles for removal actions under $200,000  continue to be ignored."  Although Note 3
$60 million may not be recovered over the next 20 years, it will not be due
to ignoring cases under $200K.  It will be due to not having a viable
responsible party.

      The next concern is  your statement  about "the  Congressional goal of
establishing a self-sustaining Fund to clean up  the hazardous  waste sites".
The Congressional goal is to clean up the nation's  worst  hazardous waste
 sites.  Since we estimate that more than half of the sites  are abandoned  and
 have no viable responsible party against which to cost recover, your  inter- See
 pretation of the Congressional goal would not appear to be  reasonable. A   Appendix 2
 more accurate statement would be to say that it is important that EPA maintain Note 4
 an aggressive cost recovery program because EPA will be able to clean up
 additional sites with the recovered funds.   It is also Important to note
 that Congress must appropriate these dollars to EPA, before they can be
 used.

      Our final  concern is related  to  the 199 sites under $200,000, that are
 not being pursued by  EPA.   In  reviewing  the  sites  listed in exhibit A, we   See
 have determined that  almost  50 percent of the sites are under  $10,000.  In  Appendix  2
 weighing our staffing resources against  the  amount of  recoverable dollars,  Note 5
 cases under  $10,000  represent  a low priority.

      Before  addressing each  of your specific recommendations, we want to
 point out that  the new Superfund bill will  bring some  changes.  Over  the next
  several months,  we will  be  reviewing  our existing  policies and  procedures and
  will be revising them to incorporate the new provisions.   During this process,
  we will also take your recommendations Into consideration in updating our
  policies and procedures.
                   .*
  PIG Recommendation'- Small Case Policies

       1.  Require that minimal cost recovery actions (e.g., notification,
           demand letters) be pursued for sites where funds  expended  are
           under $200,000.  Also, Headquarters should weigh the costs  to
           be incurred for litigation versus the costs to be recovered,
           before pursuing a cost recovery action.

       2.  Develop and issue specific policies, procedures,  and negotiating
           strategies for settling cases under $200,000 ($500,000) to the
           Regions to ensure a consistent Agency approach.
                                     57

-------
                                                          APPENDIX  1
                                                          Page 3 of 5
     3.  Examine the possibility of using an arbitration board or
         some similar mechanism as an alternative to filing cost
         recovery actions in court.

     4.  Pursue the possibility of giving cost recovery actions under
         $200,000 to outside attorneys on a contingency basis for
         fees.

OSWER Response

         Under the new Superfund, cases under $500,000 now can be
         handled through admnistratlve means.  We will be reviewing
         existing policies and requirements of the new law, and we
         take into consideration your recommendations.  The new Super-
         fund bill expressly allows for alternative dispute resolution
         procedures.  Since the new law gives us administrative author-
         ity to pursue cost recovery actions under $500,000, it should
         not be necessary to use outside attorneys.

QIC Recommendation - Bankruptcy Cases

     1.  Use more explicit language in the demand letter identifying
         EPA as an "official creditor," thus no interpretation of the
         demand letter will be required by the PRP.

     2.  Establish procedures on how to take the necessary action(s) to
         establish EPA's priority claim in relation to other creditors.

     3.  Coordinate with the Office of General Counsel on developing
         new procedures and a system that will permit EPA to take
         timely action, once it is notified of a PRP's bankruptcy filing.

     4.  Coordinate with OECM to try to balance Agency actions against
         both financially viable and nonviable PRPs, especially in light of
         the courts''recent leaning towards giving governmental units first
         priority on hazardous waste cases after secured creditors.

OSWER  Response

         We will consider  revising our demand letters to include the
         appropriate "official creditor" language.

         The Bankruptcy Guidance issued by OECM will be reviewed and
         revised as appropriate in light of the suggestions made re-
         garding timeliness of actions and procedures for establishing
         EPA's claims.
                                     58

-------
                                                         APPENDIX 1
                                                         Page 4 of 5
PIG Recommendation - Negotiation Policy

     1*  Re-evaluate the Agency's present policy and procedures to
         ensure that timeframes .set for negotiations are reasonable.
         Also, timeframes should not be exceeded unless it can be
         documented in the files that significant progress is being
         made.

     2.  Require that specific steps in the negotiation and settlement
         process are planned, scheduled, and initiated in a systematic
         and orderly manner in order to minimize delays in the settle-
         ment process.

     3.  Require Agency negotiators to notify responsible parties that
         the negotiations must be concluded within the Agency's estab-
         lished timeframe.

     4.  Require the Regional offices to maintain information on the
         length of negotiations and whether this conforms to the goal
         established by EPA.

OSWER Comments
         We will re-evaluate our present policy and procedures and
         timeframes for negotiations under the new law, and take your
         recommendations into consideration.

PIG Recommendation -  Statute of Limitation (SOL)

      1.  Proceed under the more conservative  tort law timeframe (three
         years after  completion of a removal) until such time as the
         issue is resolved by Congress  or the Courts.

      2.  Include and  track the SOL date in the comprehensive listing
         of all removal actions.

      3.  For  those  sites where the SOL  is about  to expire,  take immediate
         action to  initiate negotiations or  referrals  to DOJ.

 OSWER Response

         The  new  Superfund bill  directly addresses  the issue  of  the
         statute  of limitations.

         OSWER has  initiated work on a  tracking system that will  identify
         all  removal actions and pinpoint  significant  enforcement-related
          dates,  Including statute of limitations dates.

         OSWER and OECM have already asked the Regions to  review the  universe
          of removal actions for purposes  of potential cost recovery actions.
                                      59

-------
                                                           APPENDIX 1
                                                           Page 5  of 5
         Current guidance ("Timing of CERCLA Cost Recovery Actions")
         requires that CERCLA actions be initiated in a manner that
         ensures compliance with any applicable statute of limitations
         and also ensures that the evidence does not become stale.

     We appreciate the opportunity to comment on the draft consolidated audit
report.  If you have any questions regarding our comments, please call Brad
Campbell on 382-4478.
cc:  Jack McGraw
     Gene Lucero
     Brad Campbell
                                        60

-------
                                                    APPENDIX 2
                                                    Page 1 of 3
                    ADDITIONAL 01G COMMENTS TO OSWER'S
                    RESPONSE DATED SEPTEMBER 10, 1986


The following notes present the OIG's response to OSWER's comments which
were not addressed in the body of the report:
Notes
         OSWER presented some dollar figures on settlements achieved with
         responsible parties (RPs).  After receiving this response, we
         requested further clarification of these figures from OSWER.
         OSWER indicated that:  (1) the $477 million was money received
         from RPs to actually clean up the sites and was not part of the
         $1.3 million Trust Fund obligations; (2) $225 million of the
         $306 million was also included in the $477 million figure
         mentioned above; and (3) the remaining $81 million of $306
         million represents the value of cleanups EPA is pursuing through
         the court system.  None of the above figures were part of the
         $1.3 billion Trust Fund obligations.  In addition, the $137
         million is money that EPA is trying to recover by requesting
         the Department of Justice to file for cost recovery.  The $137
         million is a part of the $1.3 billion Trust Fund obligations.

         We-believe that the 1.1 percent cost recovery ratio is not a
         poor characterization since it shows the actual percentage of
         total funds the Trust Fund received through cost recovery.
         We are pointing out that $14 million, or 1.1 percent, of the
         $1.3 billion obligated from the Trust Fund for cost recovery
         efforts as of September 30, 1985 have been returned to the Trust
         Fund by collections from responsible parties.  Obligations are
         mainly a combination of two important accounting transactions:
         (1) disbursed amounts and (2) estimates of future expenditures
         that may occur.  Thus, obligations represent the expenditures
         and best estimate of expenditures the fund has or intends to
         incur.  While it would be unrealistic to expect EPA to recover
         all Trust Fund expenditures, the Agency needs to be more aggressive
         in pursuing its cost recovery actions.

         We agree that cast recovery actions are resource intensive and
         may not always be practical.  However, we are concerned that
         the current practice of selective enforcement may deplete the
         Trust Fund and exempt numerous responsible parties from financial
         liability for cleanup costs.  All funds recovered, regardless
         of the amount are considered important since they replenish the
         Trust Fund and may be utilized for future cleanups.

         In addition, the scope of our audit was not limited to just
         removals.  Three of the findings consisted of remedial as well
         as removal actions.
                                    61

-------
                                                    APPENDIX 2
                                                    Page 2 of 3
Notes
 3       We believe that the Agency needs to strengthen its methods in
         pursuing cases under $200,000.  In his response, the Assistant
         Administrator for Solid Waste and Emergency Response commented,
         "Although $60 millipn may not be recovered over the next 20
         years, it will not be due to ignoring cases under $200,000.  It
         will be due to not having a viable responsible party."  The
         Agency stated that it uses a priority system in pursuing cases
         and that cases under $200,000 have a lower priority than larger
         dollar cases.  We realize that some of the costs may not be
         recovered due to a lack of viable responsible parties.  However,
         when there is a viable responsible party, the low priority given
         to these cases may still result in the funds not being recovered.
         In addition, we have serious reservations about establishing a
         threshold for initiating cost recovery actions.  Should a
         threshold be established, it could encourage responsible parties
         to establish multiple hazardous waste sites in order to avoid
         financial liability for cleanup costs.

 4       While we agree with OSWER's statement that some sites may be
         abandoned and have no viable responsible party, we believe
         overall EPA must pursue an aggressive cost recovery program.
         We believe EPA should pursue cost recovery actions at all sites
         to the extent such actions can be pursued on a cost effective
         basis (e.g., negotiations, filing of lawsuit, etc.)  Such a position
         will show that EPA will use strength in the process of recovering
         funds.

 5       We would like to provide clarification in 3 areas.  First,
         OSWER's comment should refer to Exhibit B and not Exhibit A.
         Second, based on a special printout provided by OSWER that
         showed some of the sites were listed under entirely different
         names, the number of sites under $200,000 was subsequently
         changed from 199 to 182 sites.  Third, while cases under $10,000
         1n value may not have the highest priority, we believe all sites
         need to be evaluated for potential cost recovery action.  In his
         response to the Region 4 audit report, the Regional Administrator
         stated:

              "Since the established floor for cost recovery actions is
              $500,000, recovery actions costing less than $500,000 are a
              lower priority at both EPA-HQ and at the Department of
              Justice (DOJ).  Therefore, cost recovery for sites under
              $200,000 is practically nonexistent.  In HQ, the Office of
              General Counsel (OGC) as well as Region IVs Office of
                                    62

-------
                                           APPENDIX 2
                                           Page 3 of 3
     Regional Counsel (ORC) are not prepared to pursue or
     negotiate settlements at these low dollar sites.  Until
     authority to settle these cases administratively is delegated
     to the regions, very few of these cases will  be pursued."

In our opinion, all  sites should be examined to determine the
need for negotiations and possible filing of a case.  Thus, the
negotiation team would be able to show strength.  In addition,
we believe alternative methods such as the use of  outside attorneys
on a contingency basis for fees should still be explored.
                           63

-------
                                                          APPENDIX 3


                       DISTRIBUTION OF AUDIT REPORT


                                                            Copies

A.  Office of Inspector General (A-109)                       10

    Inspector General (1)
    Deputy Inspector General (1)
    Director, Audit Operations Staff (3)
    Divisional Inspectors General  for Audit (5)

B.  Headquarter*s Office

    Assistant Administrator for Solid Waste
     and Emergency Response (WH-562A)                          3
    Deputy Assistant Administrator for Solid
     Waste and Emergency Response (WH-562A)                    1
    Assistant Administrator for Enforcement
     and Compliance Monitoring (LE-133)                        1
    Comptroller (PM-225)                                       1
    Agency Follow-up Official (PM-225)                         1
     Attn:  Resource Management Division
    Associate Administrator for Regional
     Operations (A-101)                                        1

C.  Regional Office
                                                             #
    Regional Administrator, Region III                         1
    Regional Administrator, Region IV                          1
                                    64

-------