QUESTIONS AND ANSWERS ON WATER QUALITY STANDARDS
1. When did the water quality standards program begin?
The water quality standards program was provided for in the Water Quality
Act of 1965. This Act was part of the Federal Water Pollution Control
Act which has since gone through several amendments including the
Clean Water Restoration Act of 1966 (89-753), the Water Quality
Improvement Act of 1970 and the Federal Water Pollution Control Act
Amendments of 1972 (PL92-500).
2 . Who administers the water quality standards program?
Administration of the program has been assigned to the Water Planning
Division, Office of Water Planning and Standards, Environmental
Protection Agency. Previously the Division of Water Quality Standards
was assigned this responsibility. Prior to December 2, 1970, the
Federal Water Quality Administration, U.S. Department of the Interior,
administered the program upon succeeding the Department of Health,
Education and Welfare.
3. How many jurisdictions are included in the water quality standards program?
The Water Quality Act of 1965 provided standards coverage for all fifty
states, Guam, Puerto Rico, the Virgin Islands, and the District of
Columbia. Public Law 92-500 added the Trust Territory of the Pacific,
and American Samoa.
4. Do water quality standards apply to all waters?
Water quality standards now apply to all interstate and intrastate
waters; in the 1965 Act, only interstate waters were covered.
5. What did the original law require states to do in order to establish
standards?
First, the Governor or water pollution control agency had to file, by
October 2, 1966, a letter of intent that the State, after public hearings,
would, before June 30 1967, adopt (a)/ water quality criteria applicable
to interstate waters or portions thereof within the state, and (b) a
plan for the implementation and enforcement of the criteria. Second,
the state had to adopt such criteria and plans and submit them to
the Federal Government for approval.
6. What is required of the States under the new law to establish standards?
The new law expands standards coverage to include all intrastate waters
and establishes precise timetables for EPA and state action with regard
to establishment, review, and approval of standards. The basic procedure
of State adoption of standards through public hearings and submittal
-------
to EPA for approval is unchanged. After the initial review period
provided in the law, standards are redefined to include only uses
and criteria. It also adds additional jurisdictions to the program
(see question 3).
7. What are the requirements for standards to be approved?
Water quality standards must be such as to protect the public health
and welfare, enhance the quality of the water, and serve the purposes
of the Act.
8. Who actually sets the standards?
The states, through public hearings, set stream classifications and
appropriate criteria to meet those classifications. They also adopt
an implementation plan. The standards are then submitted to EPA
for review and approval. The Administrator of EPA may promulgate
standards only when a state fails to adopt standards consistent with
the Act within the time allowed by the Act.
9. Are water quality standards approved for all states?
Yes. Standards have been approved wholly or in part for all 54
jurisdictions covered in the previous law. The standards for some
states were approved with exceptions. As of December 1, 1972, water
quality standards were completely approved for 50 jurisdictions;
4 (111., La., Ohio, and Michigan) have incomplete approvals.
10. What are water quality standards?
Water quality standards have four components. They are (1) numerical
and narrative criteria applied to (2) specific stream use classifications,
(3) a plan for implementation and enforcement, and (4) an antidegradation
statement which is included through a policy determination made by
the Federal Governmeaid ,
11. What are stream use classifications?
Stream use classifications identify the use to be made of a particular
stretch of a river, lake, or coastal water, such as recreation,
drinking water, industrial use, agricultural use, fish and wildlife
propagation, or a combination of these uses.
12. What is %he stream use classification policy?
It is the policy of EPA that all water should be protected for
recreational uses in and on the water and for the preservation and
propagation of desirable species of aquatic biota. Other lower stream
uses are permissable by special exception only.
-------
What are water quality criteria and what kind of water characteristics
are covered by the criteria?
The numerical criteria are scientific determinations of the specific
characteristics of water which would permit the appropriate uses
agreed upon by the state and EPA. Limits on such pollutants as
bacteria, toxic substances, and taste and odor producing substances
in the water are included.
14. Are all criteria given in numerical form?
No. Some criteria are narrative; where possible, numerical criteria
are used.
15. Are criteria for similar stream uses comparable throughout the
United States?
Yes. Criteria may vary from place to place reflecting natural conditions
16. Can water quality criteria differ within the same state?
Yes. Water quality criteria vary within the state depending upon
the use to be made of the receiving water. Water quality criteria
may also vary on each stream depending on the use to be made of
each section of the stream.
What kind of characteristics are covered by the criteria?
Standards include criteria for the physical and microbiological
properties of water, inorganic chemicals, organic chemicals, and
radioactivity. These water properties, constituents, and pollutants
are described by parameters, i.e., color; odor; turbidity; settleable
and dissolved solids; temperature; pH; fecal coliform; dissolved
oxygen; radiation; toxic substances; chemicals; oil; etc. Criteria
are set for each parameter to protect the water use assigned.
18. What does the EPA use to determine the acceptability of criteria?
The basis for such judgements are the recommendations made by the
National Technical Advisory Committee in its report to the Secretary
of the Interior on Water Quality Criteria, April 1, 1968.
19. Are there any exceptions to the recommendations made by the National
Technical Advisory Committee?
Yes. Standards may be lower, or less stringent, than recommended
criteria levels if it can be proven that the water in its natural
state has such lower criteria.
-------
20. Are the NTAC criteria .scientifically sound, or are they out of date?
They are scientifically sound, although as with all specific measures
they are subject to debate. At the present time, they are the best
measures available. They are continually being reviewed.
21. What are implementation plans?
Implementation plans are step-by-step plans specifying what actions
are to be taken by polluters to enable them to meet Federal/State
standards by a certain date.
22. Can high quality waters be permitted to deteriorate as long as
approved water quality standards are met?
No. An antidegradation provision in standards prohibits the deterioration
of high quality waters, except as a result of necessary economic and
social development as agreed to by both the State and EPA.
23. Do all states have an antidegradation provision in their standards?
Yes.
24. (a) Have any states adopted standards for intrastate waters as yet, and
(b) are those states that have not done so required to adopt intrastate
standards?
(a) Yes (b) Yes
All but a few states have adopted standards for intrastate waters.
Others have adopted such standards for some of their streams. Those
states that have not adopted standards for intrastate waters have
until March 18, 1973 to do so. The states whose intrastate standards
were adopted earlier, had until November 18, 1972 to submit them
to EPA for review and approval.
25. Is the purpose of water quality standards to return all waters to
their original state?
No. Water quality standards establish water quality goals based
on designated stream uses.
26. Where is information available on the approval status of the standards
for each state?
This question can be answered by the State water pollution control
agency or EPA though its regional offices or at its Washington D.C.
headquarters. The standards for each state also appear in the
Federal Register at 40 C.F.R, Part 120.
-------
27. Are copies of the water quality standards for each state available?
Yes, from the state water pollution control agency.
28. Can EPA legally disapprove standards adopted by a state?
Yes.
29. What happens to the standards if they are disapproved?
EPA first advises the state what revisions are required. If a stfcte
fails to adopt the necessary revisions within the time frames specified
in the law, EPA must initiate promulgation procedures.
30. How does EPA promulgate standards?
Proposed standards are published in the Federal Register and final
standards are promulgated 190 days later unless the state had adopted
approvable standards in the interim. Public comments are solicited
on the proposed standards.
31. Has EPA or its predecessor agencies ever promulgated standards for
a state?
No. Proposed standards were published for Iowa and Alabama, but
in both cases state action made subsequent.promulgation unnecessary.
32. Must a state hold a public hearing to establish or review water quality
standards?
Yes. In addition, the new law states that the Governor of a State or the
state water pollution control agency of such state shall from time to
time (but at least once each three year period, beginning on Oct. 18, 1972)
hold public hearings for the purpose of reviewing applicable water
quality standards and, as appropriate, modifying and adopting such
standards.
33. Once adopted by the states and approved by EPA, may standards be
modified or revised?
Yes.
34. Who can initiate revisions or modifications?
Either at the request of the sdtdite or on his own initiative, the
Administrator of EPA is empowered to take steps for the revision 06
standards.
-------
35. How can approved standards be revised?
Any component of a state's water quality standards may be revised
by the individual state, following its own administrative procedures
for revision. Failure to react to the Administrator's request within
the time frames specified in the law may require EPA to promulgate
revisions.
36. How likely is it that standards will be revised?
With continued advances in the science and technology of water pollution
control, it is expected that many of the water quality standards
approved to dat« will be improved as required in the years ahead.
37. What is done to ensure that standards are met?
Each state has a surveillance and monitoring system to verify compliance
with standards.
38. What type of enforcement actions can be taken by states?
Enforcement methods available to the states include: requiring permits,
issuing specific orders for a polluter to take action by a certain
date, holding public hearings, issuing cease and desisit orders, and
finally, initiating court action.
39. Can the federal government enforce standards?
Yes. Once standards submitted by the states are approved, they become
Federal/State standards and are subject to federal enforcement action.
40. How can EPA enforce standards?
The issuance of permits under section 402 of the new law will be the
principal method for enforcing standards. They will also be enforceable
under section 309, by administrative or judicial order. However, if
a discharger has filed a permit application, EPA may not proceed against
him prior to December 31, 1974 for failure to comply with water quality
standards until final administrative disposition of the application.
In addition, municipalities have a 180-day grace period beginning
October 18, 1972 in order to file their permit application/ and during
this grace period, EPA may not take action against them for violation
of water quality standards.
41. What sources of pollution are included in implementation plans?
Pollution problems associated with municpal and industrial wastes are
included in all plans. Pollution originating from combined severs,
vessels and marinas, agricultural wastes, acid mine drainage, and
other sources are included in varying degrees.
-------
42. What are the basic causes of pollution?
The causes of water pollution fall into two broad categories--
untreated of inadequately treated wastes from easily indentified,
point-of-origin sources such as municipal waste treatment discharges,
and waste from diffuse or non-point sources--silt or fertilizers
washed into a stream during a heavy rain, for example.
43. What is a "mixing zone" that is called for in some standards?
A mixing zone is a limited area of a receiving water where water
quality is permitted to be lower that that prescribed by the standards.
Its function is to provide a restricted area where wastes can be
assimilated by the water.
44. Who is going to have to pay for cleaning up the waters?
We all will, as corporations, taxpayers, and as consumers. Pollution
control is a complex, expensive, and time-consuming process.
45. What is the difference between water quality standards and effluent
standards or limitations?
Water quality standards apply to the natural aquatic environment of
and conditions within a stream while effluent limitations apply
directly to the characteristics of wastes at the point of discharge
into the water.
46. Are there effluent limitations now?
Yes in some states. Criteria for industry-wide effluent limits
are now being developed by EPA.
47. Can we really ever expect to get cleaner water?
Our national goal is to see that the discharge of pollutants into
navigable waters be eliminated by 1985 and as an interim goal, water
quality to permit recreation in and on the water and for the propagation
and preservation of fish, shellfish, and wildlife by July 1, 1983.
48. Are standards setting or revisions conferences included in the
new law?
No.
49. With the new law providing for permits and effluent limits, why
do we need water quality standards ?
To define our water quality goals.
50. What are the time frames for action on standards as provided by
the new law?
See the table included on the next page.
7
-------
CHRONOLOGICAL TIMETABLE OF EVENTS AND REQUIREMENTS
RELATING TO SECTION 303
November 18, 1972 (30 days): submission by States of existing
water quality standards for infra-
state waters. 303(a)(2).
January 18, 1973 (90 days): water quality standards for interstate
waters remain in effect unless
notification of inconsistency. 505(2)(1).
March 18, 1973 (150 days): submitted existing intrastate water quality
standards remain in effect unless
notification of inconsistency. 305 (a) (2) .
April 18, 1973 (180 days): revision of inconsistent interstate water
quality standards by State or promulgaticr.
by EPA. 303(a)(1). |
i
April 18, 1973 (180 days): adoption and submission by State of water
• quality standards for intrastate waters for
which no standards were previously adoptee
303(a)(3).
June 18, 1973 (240 days): revision of inconsistent existing intrastate
water quality standards by State or pronulga
tion by EPA. 303(a) (2).
July 18, 1973 (270 days): newly adopted and submitted water quality
standards for intrastate waters approved
unless notification or inconsistency.
303(a)(3).
October 18, 1973 (one year): revision of inconsistent newly adopted
and submitted intrastate water quality
standards by State or promulgation by
EPA. 303 (a) (3).
------- |