United States

            Environmental Protection

            Agency
         Region V

         230 South Dearborn

         Chicago, Illinois 60604
June 1979
            Water Division
4>EPA
Environmental      Draft
Impact Statement

Alternative Waste
Treatment Systems
for Rural Lake Projects

Case Study Number 2
Green Lake Sanitary
Sewer and Water District

-------
    DRAFT ENVIRONMENTAL IMPACT STATEMENT


        WASTEWATER TREATMENT SYSTEMS

           FOR RURAL LAKE PROJECTS

        CASE STUDY No. 2:  GREEN LAKE

       SANITARY SEWER AND WATER DISTRICT

         KANDIYOHI COUNTY, MINNESOTA
              Prepared by the

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

                 REGION 5

            CHICAGO, ILLINOIS

                   and

               WAPORA, INC.

             WASHINGTON, D.C.
                                    Approved by:
                                     ohn McGuire
                                     legional Administrator
                                    June 1979

-------
                    DRAFT ENVIRONMENTAL IMPACT STATEMENT
                            GREEN LAKE STUDY AREA
                         KANDIYOHI COUNTY, MINNESOTA
                                 Prepared by
                US Environmental Protection Agency, Region V



Comments concerning this document are invited and should be received by

August 13, 1979	.


For further information, contact:

Mr. Gregory A. Vanderlaan, Project Monitor
230 South Dearborn Street
Chicago, Illinois  60609
312/353-2157



                                  Abstract

     A 201 Facilities Plan was prepared for the Green Lake Sanitary Sewer and
Water District in 1976.  The Facilities Plan concluded that extensive sewering
would be required to correct malfunctioning on-site wastewater disposal systems
and to protect the water quality of Green Lake.

     Concern about the high proposed costs of the Facilities Plan Proposed
Action prompted re-examination of the Study Area and led to preparation.of
this EIS.  This EIS concludes that existing wastewater treatment plants in
the area may upgraded, and that complete abandonment of on-site systems
is unjustified.  Alternatives to the Facilities Plan Proposed Action have
therefore been developed and are recommended by this Agency.

-------
                              LIST OF PREPARERS

     This Environmental Impact Statement was prepared by WAPORA, Inc. under
the guidance of Gregory Vanderlaan, EPA Region V Project Monitor.   Key
personnel for WAPORA included:

     WAPORA, Inc.
     6900 Wisconsin Avenue
     Chevy Chase, MD  20015

          Eric Hediger         - Project Manager
          David Twedell, Ph.D. - Assistant Project Manager
          Gerald Peters        - Project Director

     In addition, several subcontractors and others assisted in preparation
of this document.  These, along with their areas of expertise, are listed
below:

Aerial Survey
     Environmental Photographic Interpretation Center
     Vint Hill Farms Station
     Warrenton, Virginia
          Barry Evans

Engineering
     Arthur Beard Engineers
     6900 Wisconsin Avenue
     Chevy Chase, Maryland
          David Wohlscheid, P.E.
          David Stewart

Financial
     A. T. Kearney Associates
     699 Prince Street
     Alexandria, Virginia
          Charles Saunders

Sanitary Survey
     University of Michigan Biological Station
     Pellston, Michigan
          Mark Hummel

Septic Leachate Analysis
     K-V Associates
     Falmouth, Massachusetts
          William Kerfoot, Ph.D.

Soils Interpretation
     USDA, Soil Conservation Service
     Willmar, Minnesota
          Allan G. Giencke
     St. Peter, Minnesota
          Richard Paulson

-------
                                SUMMARY

CONCLUSION

     Most on-site systems around  Green  Lake and Nest Lake  are operating
satisfactorily.   Approximately  30 septic tank  effluent plumes  entering
Green Lake  and  15 plumes  entering Nest  Lake have been identified,  along
with  a  few  septic  system  surface malfunctions;   Backup  of sewage  in
these systems is  relatively infrequent.   On-site systems do  not  appear
to be a significant  contributor of nutrients to Green Lake  -- only 8% of
the  total  phosphorus  input to  this  lake  is estimated to come  from  ef-
fluent plumes.  Effluent plumes  only constitute an estimated 1%  of  the
total phosphorus budget of Nest Lake.

     In the  Facilities  Plan,  septic  systems were  suspected  of contri-
buting to  water quality and  potential  public  health  problems  although
there was little evidence  to support this  suspicion.  Neither the  Facili-
ties  Plan  Proposed Action  nor  the EIS  Alternatives are  expected  to
either adversely  or beneficially  affect  the water quality  of  the open
bodies of  Green Lake  or Nest Lake.  The  lack  of measurable improvement
in  the  quality  of  these  open waters suggests  the  significance  of  the
non-point  source  loading  associated with the  Middle  Fork  of  the Crow
River.  This  loading  constitutes  an estimated  73%  and 96%  of the total
phosphorus  input  to Green  Lake  and Nest Lake,  respectively.  Any  im-
provement  in  the  lake water quality associated  with  wastewater manage-
ment  schemes  presented  in  this EIS is likely to  be masked by tributary
loads of the above magnitude.

     Many of the on-site systems presently in use within  the EIS Service
Area  are poorly maintained  and many are inadequately designed.   Routine
maintenance  for  all on-site  systems  and upgrading  of inadequately  de-
signed systems  will substantially reduce the number  of problems  caused
by  them.   Where problems  cannot be solved by routine maintenance  or  up-
grading  alone,  alternatives  to  the  conventional  septic  tank -- sub-
surface absorption  systems  are  feasible  in the  Study Area  which will
minimize or eliminate the problems.

     Future growth  in  the  Green Lake Service Area depends  on the  number
of  new lots  that  can  be developed at the allowable density.  Wastewater
disposal alternatives relying on continued use of on-site  systems  around
the  lake  would  restrict both the  number of new lots as well  as  their
density.    An effect  of  these  limitations would  be to  preserve  the
present character of the community.

     Total  present  worth for  the centralized  alternatives  (Facilities
Plan  Proposed Action, EIS  Alternatives  1, 2,  and  3)  are  substantially
higher than for the decentralized alternatives  (EIS  Alternatives  4,  5,
6,  and Limited  Action).   As calculated  in this EIS, the  Facilities Plan
Proposed Action is  57% more  expensive  than EIS  Alternative  5  and 191%
more  expensive  than Limited Action .  Differences  in  water quality  im-
pacts  of  the  alternatives  are  not proportionate  to these  large dif-
ferences in   costs.   Because  of the high  costs and limited benefits to

-------
water  quality  with   the   centralized  alternatives  (Facilities  Plan
Proposed Action  and EIS Alternatives  1,  2,  and 3), they  are  not cost-
effective and therefore cannot be funded by EPA.

DRAFT EIS RECOMMENDATIONS   --   Because   EIS  Alternatives   4   and   5
(decentralized approaches  with land  application)  and 6  (decentralized
approach with upgrade/expansion of wastewater treatment plants at Spicer
and New  London)  can all be considered cost-effective, and because  they
differ   substantially   from   the  Facilities   Plan  Proposed   Action
(centralized  approach  with stabilization ponds),  the  recommendation  of
this EIS is  to  return  the grant  application  to  the Green Lake Sanitary
Sewer and.Water  District  (GLSSWD) for additional  Step 1  analysis.   The
scope  of  additional  analysis  will  depend  on  the  applicant's   own
decisions regarding the feasibility  of  the  small  waste  flows approach
for  Green  Lake  and Nest Lake  and  the merits  of  land application  for
wastewaters  from Spicer and New London.

     Alternatives 4, 5,  and  6 differ in the type and location of treat-
ment and disposal  facilities  for Spicer's and New London's wastewaters.
The  GLSSWD  will  need  to  conduct additional Step  1  analyses,  funded  by
EPA,  of  alternatives   to  serve  Spicer  and  New  London  jointly  or
separately.   EPA encourages the use of land application and will require
evaluation  of land  application  including  detailed site  analyses.   If
GLSSWD  chooses  Alternative  6, the  Step  1  analyses  must include  the
following:

     •    Applicant's  own  analysis   of  the  feasibility  and costs  of
          treatment plant upgrading;

     •    Engineering,   cost  and  environmental  analysis  of sludge  man-
          agement options; and

     •    Engineering,   cost,  and environmental  analysis  of  effluent
          disinfection options.

EPA  will participate  in  funding additional  site  specific analyses  of
existing on-site systems, their design, usage and environmental impacts.
These additional analyses will address:

     •    Development  of  a site-specific  environmental  and engineering
          d^ta base;

     •    Design of the management organization; and

     •    Start-up, af;the management district.

The  applicant will: need  to  complete additional Step  1  requirements  by
taking the following actions (40 CFR 35.918):

     •    Certify  that construction  of  the  project and  operation  and
          maintenance  program will  meet  local,  State and Federal  re-
          quirements.   As  a first step,  this  certification  involves a
          lot-byrlot investigation  of existing  septic tank systems  and
          site  suitability  for  wastewater  treatment.   If  it  can  be
                                  ii

-------
          demonstrated that  existing systems do not degrade  lake  water
          quality or  promote public health problems, despite  the  find-
          ings  of the  lot-by-lot  investigation,  then  the  GLSSWD  may
          initiate  variance  procedures  for these  systems  under  the
          Minnesota Shoreland Management  Act  which has  been  adopted and
          amended by Kandiyohi County.   The specific variance that  would
          be negotiated between  the GLSSWD and the  County involves the
          Act's  stipulation  that  there be  a 4-foot vertical  distance
          between  the bottom  of  the  septic tank  drainfield and  the
          highest known groundwater elevation.

     •    Obtain assurance of unlimited access to each individual system
          at  all reasonable  times  for such purposes  as  inspections,
          monitoring,  construction,  maintenance,  operations,  rehabili-
          tation and replacement.

     •    Plan for a  comprehensive  program of regulation and inspection
          for individual systems.

HISTORY

     In November 1975, the Green Lake area Facilities Plan was submitted
to  EPA Region V by the  Green  Lake Sanitary Sewer and  Water  District
acting as  the applicant  for funding under the EPA  Construction Grants
Program.   The  GLSSWD Service Area  encompasses  the  City  of  Spicer, the
Village of New London,  and the residential area surrounding  Green  Lake.
Portions of  New London Township,  Green Lake Township,  Irving Township
and Harrison Township  are included in this Service  Area.  At the  time,
the City of Spicer and village had already been  sewered  and were operat-
ing their own sewerage facilities.

     the Facilities  Plan  identified  the  following  problems  associated
with  the  existing centralized wastewater  collection and  treatment fa-
cilities :

     •    The present  Spicer and New London  sanitary sewer  systems are
          both  subject to  potentially  excessive  infiltration/inflow.

     •    The Spicer  and  New London treatment plants do not  meet Minne-
          sota  Pollution   Control Agency  1974  discharge  requirements.

     The following problems  associated  with existing on-site systems in
the Study Area  were  also  addressed by  the  facilities planners in 1976:

     •    An  estimated  55%  of the  on-site wastewater  disposal systems
          around  Green Lake  cannot comply with  the 4  foot  separation
          parameter specified in the Minnesota Shoreland Management Act;

     •    The  same  55%  of  the  individual  disposal systems  cannot be
          upgraded  to comply with  the  Shoreland Management  Act because
          of  the small  size of the  platted lots  around Green  Lake;

     •    Individual disposal systems around Green Lake are contributing
          to  the  nutrient  loading of  this  basin  (approximately 23%

                                  iii

-------
          greater than the total  discharge  loading  from Spicer and New
          London);  and

     •    Many  of  the  older  individual  on-site  systems  installed
          approximately 20  years ago may be  cesspools.

     The alternative involving  centralized  collection  and treatment by
waste stabilization lagoons was  selected as  the Facilities Plan Proposed
Action because it proved to  be  the most cost-effective of the two final
alternatives considered.   The  Proposed  Action is  cited to be  in con-
currence with the comprehensive water and sewer  plan adopted  by Kandi-
yohi County in 1973.

EIS  ISSUES

1.   COST  EFFECTIVENESS

     The total capital cost  for the Facilities Plan  Proposed Action was
estimated  in  the Plan  (August, 1976) to be $4.4 million.  This repre-
sents  an investment of  approximately $875  per  person  and  $3,709 per
existing dwelling unit  within the  Facilities Plan Proposed Service Area.

     It  is  questionable whether total elimination  of septic tanks will
have a strong positive  impact on overall lake  quality.

2.   IMPACTS ON WATER QUALITY

     Although indirect  evidence  was  presented in  the  Facilities Plan
indicating  that  there may be  a  water quality  problem  attributed  to
malfunctioning lakeshore  septic systems,  the  relationship  between de-
teriorating  water  quality  and  inadequately  functioning  septic systems
was not  documented.  With  the  exception of  two isolated  cases involving
high  nitrate nitrogen  levels  (greater  than  10  milligrams  per  litre
(mg/1)) in domestic wells  along  the south shore of Green  Lake, claims of
possible hazards  to the public health have been unsubstantiated.

3.   ECONOMIC IMPACT

     The average  local share per residence  of the total capital costs
for  the  Facilities  Plan Proposed Action  is approximately $2,180.  The
Plan  estimates the  ;annual user charge  per  resident to  be $194, which
includes  annual  debt  retirement  of  the  amortized  local  share  of the
project  cost and annual O&M  costs.  The user  charge  represents approxi-
mately  1.4%  of  the  average annual  income  for  year-round residents.
Seasonal residents, particularly  those in smaller,  less  expensive homes
may come under considerable pressure to sell their property.

4.   INDUCED GROWTH  AND SECONDARY IMPACTS

     Based  upon  their  experience with  previous  wastewater management
projects in rural lake  areas, the  Minnesota  Pollution Control Agency has
concluded that sewering of  Green Lake may cause the  following:
                                 iv

-------
     •    Increased development of  lakeside  areas;
     •    Increased  development of  adjacent  non-lakeside  areas;  and
     •    A shift from seasonal to  permanent occupancy.

5.   PUBLIC CONTROVERSY OVER WATER QUALITY

     Residents of  Harrison  Township  and Irving Township have expressed
concern over  the Facilities Plan  -  proposed stabilization pond  (i.e.,
lagoon) system  and its potentially  adverse effects upon  local ground-
water quality.  Farmers and  other  citizens  who live in the  vicinity of
the proposed  treatment site focus their  concern on  the  potential for
contamination of domestic  water supply  wells through lagoon seepage  into
sandy soils.  This  concern  exists  despite the  fact  that the  Plan  recom-
mended  installation of  an   impermeable  bentonite   liner  during  lagoon
construction.

ENVIRONMENT

Soils

     Opportunities  for  suitable treatment of domestic wastewater exist
at selected  sites  throughout the  Study Area.   Major factors  restricting
the  use  of  some soils for  on-site  waste  disposal  systems  are  perme-
ability and  a seasonal high water table.   The  extreme  variability of
these glacial soils, in some cases  on a lot-by-lot basis along the Green
Lake  shoreline,  is significant as it  requires that detailed soils and
groundwater  investigations  be  performed prior  to construction of soil-
dependent treatment systems.

Surface  Water  Resources

     Nest Lake, with  an area of 945  acres,  is  classified as  a eutrophic
system.  The  irregular configuration of its shoreline, which restricts
water  circulation  patterns,  allows for build-up of nutrients and algae
in its many embayments.

     Green Lake is the focal point  of the  Study Area,  occupying  approxi-
mately 5400  acres;  its  primary tributary  is the Middle Fork  of  the  Crow
River.  Green Lake's  water  quality has remained stable over the  past  7
years, and it is classified  as  a moderately  fertile  (mesotrophic)  sytem.

     There is no  evidence that existing systems are contributing  signi-
ficant bacterial  loads  to Green Lake.   Bacterial levels along nearshore
areas  were  generally  below  the Minnesota  State Health Department and
MPCA  standards for  recreational waters.   Values in  excess  of the  stand-
ards  were found  in inlet  and outlet  streams and these  levels could not
be attributed to septic tank leachate.   Kerfoot (1979)  detected  very low
levels  of fecal  coliforms   (generally  less than 10  counts/100 ml) in
surface water  (Nest Lake and  Green  Lake)  located  at the discharge of
septic leachate plumes.
                                 v

-------
Grovmdwater Resources

     Groundwater serves as  the  source  of drinking water for  the  entire
EIS Service Area; it is plentiful and generally of good quality.   Local-
ized  high nitrate  concentrations  were  found  in  groundwater during  a
sample 97  wells on  Green  Lake in  July 1977.  Only two samples  showed
nitrate  concentrations  in  excess  of the  public  health drinking  water
standard  of  10  mg/1.   These wells  were  located  on  the northeast  and
eastern Green Lake shoreline.
Additional Studies

     During the  preparation of this  EIS,  EPA pursued  three  additional
studies in order to evaluate the need for improved wastewater  management
facilities  in  the  EIS Service  Area.    They  are  briefly  described  as
follows:

     1)   An aerial  survey was performed by EPA's Environmental  Photo-
graphic Interpretation Center (EPIC)  during August 1978.  Results  of the
survey indicate  that septic system  surface malfunctions are not  wide-
spread in the  EIS  Service  Area.  Only 3 marginally failing  systems were
identified  along  the Green  Lake  shoreline.   One  currently failing and
one marginally failing  system  were  detected on the north shore  of Nest
Lake.  Examination of these aerial photographs  indicated that  near-shore
aquatic plant  growth  is  spotty and inconclusive  in terms of correlating
it with septic tank malfunctions.

     2)   A sanitary survey  was  conducted  by the University of Michigan
during November  1978.   The results  indicate  that  11% of the  on-lot
systems inspected  had problems attributed  to  site limitations such  as
permeability and  depth to  seasonal  high groundwater.   Less than  1%  of
the  systems inspected  had repairable problems.    The  remainder  of  the
systems surveyed  showed no  problems.   There are  relatively  few  septic
tank systems which pose public  health problems  as a result of  backups  or
ponding.

     3)   A study of septic effluent  (leachate) movement into  Green Lake
and Nest Lake was conducted during March 1979.

     The  following, observations were obtained from  the shoreline pro-
files, analyses of groundwater  and surface  water  samples, and  evaluation
of groundwater flow rates and patterns:

     o    A total  of 64 locations  exhibited effluent  plume  character-
          istics.  Of these, 26 originated  from surface  water  discharges
          and 38 from groundwater leachate.

     o    The  most pronounced   source  of leachate was  inflow from  the
          Middle Fork of the Crow River into Nest Lake.

     o    A noticeable  undocumented  source  of  phosphorus  loading  was
          observed originating  from  the discharge stream of  an  unnamed
          lake near the sewered town  of Spicer.


                                   vi

-------
     •    The observed pattern of plumes  on  Green Lake correlated with
          projected groundwater inflow  for the surficial deposits.  Most
          plumes were  found  on  the north and west shorelines with few
          observed for the  south and east  segments.

Existing  Population and  Land Use

     Approximately 65% of  the EIS  Service Area  population is seasonal;
these residents are  located  primarily  in  the unsewered area surrounding
Green Lake.   The  permanent resident  population,  located throughout the
Service Area, is  characterized by a relatively low income that is below
the average  income  for the State  of  Minnesota.   This can be attributed
to  the  fact  that a  large portion of the  population  is  comprised of
elderly people, who  are  retired and  living  on  fixed incomes.  In 1970,
persons 65  years  or older accounted for  23% of  all  persons on poverty
status in the Study Area.

     Land  use  in  the  Service Area consists  of  two small urban centers
(Spicer City and  New London Village);  permanent and  seasonal  family
residences;  agricultural  areas;  commercial  areas;  and  open  land con-
sisting of woodlands  and  wetlands.    The  aesthetic appeal  and  recre-
ational  value  of  the  area  has  resulted  in  substantial  residential
development around Green  Lake.
ALTERNATIVES

     Based upon the high  cost  of  conventional wastewater collection and
treatment technology and questions concerning the eligibility of the new
sewers, 7 new  alternatives were developed  in  this  EIS.  These alterna-
tives evaluated alternative  collection  systems (pressure sewers), treat-
ment techniques  (land  application),  individual  and multi-family septic
systems (cluster systems), and  water  conservation.

EIS  ALTERNATIVE 1

     Same as  the  Facilities Plan  Proposed Action  (centralized collec-
tion;  treatment by  stabilization pond),  except  that  pressure  sewers
would be substituted for gravity sewers.

EIS  ALTERNATIVE 2

     Same as EIS Alternative  1, except  that a mechanical oxidation ditch
plant would be substituted for  stabilization ponds.

EIS  ALTERNATIVE 3

     New London  Village,  City of  Spicer,  western  shore of Green Lake,
residential/commercial  area  between  New London Village  and Nest Lake,
and the eastern half of Nest  Lake  would discharge their wastewaters to a
rapid  infiltration  plant  located   north  of Nest Lake.   Effluent is re-
covered  and  discharged to the Middle  Fork of the  Crow River.   The re-
mainder  of  the EIS  Service  Area   would  be served  by  a  combination of
cluster systems and on-site  systems suitable to  local conditions.


                                 vii

-------
   EIS ALTERNATIVE 4

        Same  as  EIS Alternative  3  except  that  wastewater  generated  by
   residents on eastern half of Nest  Lake  would be treated by a combination
   of  on-site systems and cluster systems  instead of the rapid infiltration
   system.

   EIS ALTERNATIVE 5

        Same  as  EIS Alternative 4,  except  that  a  spray irrigation system
   would be substituted for the rapid infiltration system.

   EIS ALTERNATIVE 6

        Existing  sewage  treatment plants  at  Spicer and New London would be
   upgraded  to  tertiary treatment and  expanded  where necessary to accom-
   modate  design  flow.   Discharge of  treated  wastewaters  does  not change
   from existing  locations.  Remainder  of EIS Service Area to be served by
   a combination of on-site systems  and cluster systems.


   Limited Action

        Same  as EIS  Alternative  6  except  that  western shore of Green Lake
   and residential/commercial area between New London  and Nest Lake to join
   the rest  of  the EIS  Service Area  on on-site systems.  There would be no
   cluster systems under this alternative.

        Project costs were most directly related to the extent of sewering.
   No  cost advantage was obtained with the use of pressure sewers.

   Implementation

        Local  jurisdictions have  the  legal  and  financial  capability  of
   implementing  small  waste   flows  districts.   Although  the  concept  of
   public  management of  septic  systems  has not been  legally  tested  in
   Minnesota, present  sanitary codes have been interpreted as authorizing
   such management by local governments.  Some, but  not many local juris-
   dictions  have  experience  in  the  organization  and  operation  of small
   waste  flows  districts.   California  and  Illinois  provide  some specific
   examples.

   Impacts  of the Alternatives

        Five  major categories  of  impacts  were relevant in the selection of
   an  alternative.  These categories  included:  surface water; groundwater;
   environmentally  sensitive  areas;   population  and   land use;  and socio-
   economics.

   Surface Water
0
        None of the Alternatives is  expected  to have any significant impact
   on  the  present trophic  status  of Green  Lake or  Nest  Lake.   Both Nest
                                    vi i:

-------
Lake and Green Lake will have only  a  slight  improvement in overall water
quality.

     Phosphorus input to Woodcock  Lake will decrease dramatically (more
than 50%)  under  any proposed wastewater  management scheme evaluated in
this EIS.

Groundwater

     No significant primary  or  secondary  impacts on groundwater quality
are anticipated either as a  result  of the  short-term construction activ-
ities or long-term  operation of any  of  the various alternatives.   This
is  mainly  because  all  of  the  water quantitites  associated  with  the
alternative are  relatively  miniscule in  comparison with the estimated
groundwater storage,  recharge  from  all   other  sources,  and available
groundwater yield.

Primary Impacts

     No significant short-term impacts on   groundwater quality are anti-
cipated to  result from the construction  activities of any of the alter-
natives.  Conclusions with  respect to long-term  impacts are as follows:

     •    Impacts on bacterial  quality are  expected to be insignificant
          for  all alternatives.

     •    Continued use of ST/SAS may result in minor impacts associated
          with shoreline algal growths.

     It is possible  that  some nitrates from wastewater applied to land
might reach surface waters  via  overland  runoff, lateral interflow* in
soils,   or  transport in percolating groundwaters.  However, application
rates for  spray  irrigation  of  effluents  would be  set  to maximize crop
uptake  of   nitrogen,  minimizing   its  concentrations  in   groundwater.
Because  of the high application rates for  rapid infiltration, recovery
of  renovated  effluent  by  recover wells  or drains  may  be  necessary.

Environmentally Sensitive Areas

     Development  on steep  slopes  around  Green  Lake  and Nest  Lake is
possible with  any  of  the  alternatives.   This  would  result in erosion,
sedimentation, and  transfer  of  nutrients  to the  lakes.   The Facilities
Plan  Proposed Action  and EIS Alternatives  1  and 2 may have a somewhat
greater  impact  in  this respect than would the  Limited  Action  or  EIS
Alternatives  3, 4,  5, or 6.

Population and Land Use  Impacts

     •    A majority of residences  directly  contiguous to  Green Lake and
          Nest Lake  and  not  located  within  the  boundaries of Spicer or
          New  London  are  currently  utilizing   on-site  waste  disposal
          systems.   An estimated 30 to 40  additional lakeshore acres are
          likely to  be  developed with provision  of centralized sewerage
          facilities.
                                 ix

-------
     ©    Some increase in the  density  of residential development along
          the  lake   is   also   likely   to  result   from    centralized
          facilities.

     •    Population growth  of  5 to  10% above levels possible  without
          centralized facilities may accompany  anticipated  increases  in
          residential acreage and intensity.

     o    Centralized  facilities  will  place  severe  financial pressure
          upon  lower-  and  middle-income  families,  resulting  in   the
          dislocation  of  many  less  affluent  residents.   In   addition,
         • these alternatives  will accelerate  the conversion  of occupancy
          patterns  from  seasonal to year-round status.   Disruption  of
          the prevailing  community  environment will  be  a  possible  by-
          product  of  economic  and  financial  pressures associated with
          centralization.

     e    Decentralized wastewater  management  facilities  should only
          moderately  influence   the  composition  and  character  of  the
          Green Lake area.

Economic  Impacts

     Annual  user  charges  are  higher for the  centralized  alternatives
than  the  decentralized alternatives with respect to  the currently  un-
sewered portion of the Study  Area.   The  centralized alternatives  place a
significant financial burden  and  displacement  pressure on households  in
the unsewered areas.  The  Limited Action alternative and EIS Alternative
5 and  6  are  the  only ones not identified as  a  high-cost project  for  the
unsewered  area.   None of the  alternatives  has  been identified  as  a
high-cost project  with respect  to New London   and  Spicer.   Significant
financial burden and displacement pressure are  much lower  in  New London
and Spicer as compared to  the remainder  of the  EIS Service Area.
                                 x

-------
                    TABLE  OF  CONTENTS
Summary	    i
List of Tables	    xviii
List of Figures	    xx
Symbols and Abbreviations	    xxii


               I - INTRODUCTION, BACKGROUND, AND ISSUES

A.   Project History and Description	     1

     1.   Background	     1
     2.   Location.	     1
     3.   History of the Construction Grant Application	     5
     4.   The Green Lake Area Facilities Plan	     6

          a.   Existing Wastewater Treatment Facilities	     8
          b.   Existing Problems with Water Quality and
               Wastewater Treatment Facilities	     12
          c.   Proposed Solutions:  Alternatives Addressed
               in the Facilities Plan	     13
          d.   The Facilities Plan Proposed Action	     14

B.   Issues of this EIS	     14

     1.   Cost Effectiveness	 .     14
     2.   Impacts on Water Quality	     14
     3.   Economic Impact	     16
     4.   Induced Growth and Secondary Impacts	,    16
     5.   Public Controversy Over Water Quality	     16

C.   National Perspective on the Rural Sewering Problem	     16

     1.   Socioeconomics	     17
     2.   Secondary Impacts	 . .y. .	     19
     3.   The Need for Management of Decentralized Alternative
          Systems	;	     20

D.   Purpose and Approach of the EIS and Criteria for
     Evaluation of Alternatives	     21

     1.   Purpose	     21
     2.   Approach	     21

          a.   Review of Available Data	     21
          b.   Segment Analysis	     22
          c.   Review of Wastewater Design Flows	     22
          d.   Development of Alternatives	     22
          e.   Estimation of Costs for Alternatives	     22
          f.   Evaluation of the Alternatives	     22
          g.   Needs Documentation	     22
          h.   Public Participation	     23
                                    xi

-------
                                                                 Page

     3.   Major Criteria For Evaluation of Alternatives	     23

          a.   Cost	     23
          b.   Significant Environmental and Socioeconomic
               Impacts	     24
          c.   Reliability	     Ik
          d.   Flexibility	     24


                      II - ENVIRONMENTAL SETTING

A.   Physical Environment	     26

     1.   Topography	     26
     2.   Geology	     28

          a.   Bedrock Geology	     28
          b.   Surficial Geology	     28

     3.   Soils	     28

          a.   Soil Suitability for Wastewater Treatment	     33
          b.   Prime Agricultural Lands	     33

     4.   Atmosphere.	     39

          a.   Climate	     39
          b.   Air Quality	     39
          c.   Odors	     40
          d.   Noise	     40

B.   Water Resources	     40

     1.   Water Quality Management	     40

          a .   Clean Water Act	     40
          b.   Federal Agency Responsibilities for
               Study Area Waters	:	     42
          c.   State Responsibilities in the Green Lake
               Study Area	     43
          d.   Local Responsibilities for Water Quality
               Management	     43

     2.   Groundwater Hydrology	     43
     3.   Groundwater Quality	     45
     4.   Groundwater Use	     46
     5.   Surface Water Hydrology	     46

          a.   Size of the Drainage Basins	     49
          b.   Tributary Flow	     49
          c.   Lake Hydraulic Retention Time	     49
          d.   Precipitation	     49
          e.   Hydraulic Budget	     50

                                    xii

-------
                                                               Page
     6.   Surface Water Use Ami Classification	    50
     7.   Surface Water Quality	    50

          a.   Nutrient Budget...	    50
          b.   Lake Water Quality.	    53
          c.   Phosphorus Loading - Trophic Condition
               Relationships	    53
          d.   Bacterial Contamination in Shoreline Areas	    53

     8.   Flood Prone Areas	'. .    55

C.    Existing Systems	    55

     1.   Summary of Existing Data	    55

          a.   Investigation of Septic Leachate Discharges
               into Green Lake.	    55
          b.   Environmental Photographic Interpretation
               Center (EPIC) Survey	    57
          c.   Green Lake Construction Grants Sanitary
               Survey	. . .	    57

     2.   Types of Systems	    60
     3.   Compliance with Sanitary Codes	    60
     4.   Problems with Existing Systems	    65
     5.   Public Health Problems		.	    65

          a.   Backups/Ponding	    65
          b.   Groundwater Contamination	    66
          c.   Water Quality Problems	    66
          d.   Other Problems	    67

D.    Biotic Resources	    67

     1.   Aquatic Biology.	    67

          a.   Aquatic Vegetation	'.	    67
          b.   Fishes...	    69
          c.   Waterfowl, Shore and Wading Birds	    70

     2.   Terrestrial Biology	    70

          a.   Forest	    70
          b.   Wildlife	    71

     3.   Wetlands	    71
     4.   Threatened or Endangered Species	    72

E.    Population and Socioeconomics	    72

     1.   Population	: . . .    72
                                    xiii

-------
          a.   Introduction	    72
          b.   Existing Population	    73
          c.   Population Projections	    73

     2.   Characteristics of the Population	    76

          a.   Income.	    76
          b.   Poverty Levels	    77
          c.   Employment	    77

     3.   Housing Characteristics	    82
     4.  ' Land Use	    85

          a.   Existing Land Use	    85
          b.   Future Land Use	    85
          c.   Growth Management	    87

     5.   Cultural Resources.	    91

          a.   Archaeological Resources	    91
          b.   Historical Resources. . '. . . . :	    91

     6.   Recreation	    91

          a.   Potential	    91
          b.   County Parks	    91
          c.   Wildlife Areas	    91
          d.   Public Access	    93

                   III - DEVELOPMENT OF ALTERNATIVES

A.   Introduction	    95

     1.   General Approach	    95
     2.   Comparability of Alternatives:   Design Population...    97
     3.   Comparability of Alternatives:   Flow and Waste
          Load Projections	    97

B.   Components and Options	    99

     1.   Flow and Waste Reduction	    99

          a.   Residential Flow Reduction	    99
          b.   Minnesota Ban on Phosphorus	    102
          c.   Rehabilitation of Existing Sewers To Reduce
               Infiltration and Inflow	    103

     2.   Collection.	:	    103
     3.   Wastewater :Treatment	    105

          a.   Centralized Treatment—Discharge to Surface
               Waters. '...-.'.:	    106
          b.   Centralized Treatment—Land Disposal	    109
          c.   Decentralized Treatment and Disposal	    112
                                    xiv

-------
     4.   Effluent Disposal.:'..". ... .	     116

          a.   Reuse.1': .'.'-;"•.";:.;:i'";-.-. .'•.•.•.• ..':•..'.'....	     116
          b.   Discharge to  Surface  Water	     116
          c.   Land Application	     117

     5.   Sludge Handling and  Disposal	     117

C.   Reliability of Components	     120

     1.  'Sewers		     120
     2.   Centralized  Treatment	     121
     3.   On-Site Treatment.		     122
     4.   Cluster Systems	     122

D.   Implementation. . . . .	     123

     1.   Centralized  Districts		     123

          a.   Authority	     123
          b.   Managing Agency	     124
          c.   Financing.. . ..	     124
          d.   User Charges		     124

     2.   Small Waste  Flow Districts	     125

          a.   Authority	     125
          b.   Management	     126
          c.   Financing	     129
          d.   User Charges	     129

                            IV  -  ALTERNATIVES

A.   Introduction	     131

B.   Alternatives. .	     132

     1.   No Action	     132
     2.   Facilities  Plan Proposed Action	     132
     3.   EIS Alternative  1	     135
     4.   EIS Alternative  2.	     135
     5.   EIS Alternative  3			     135
     6.   EIS Alternative  4	     141
     7.   EIS Alternative  5	     141
     8.   EIS Alternative  6...-	     141
     9.   Limited Action Alternative	     144

C.   Flexibility  of the Alternatives	     146

     1.   Facilities  Plan Proposed Action	     146
     2.   EIS Alternative 1.	     146
     3.   EIS Alternative 2	     146
                                     xv

-------
     4.    EIS Alternative 3	    146
     5.    EIS Alternative 4	    147
     6.    EIS Alternative 5	    147
     7.    EIS Alternative 6	    147
     8.    Limited Action Alternative	    147

D.   Costs of the Alternatives	    147

                              V - IMPACTS

A.   Surface Water Quality	    149

     1.    Primary Impacts	    149

          a.   Analysis of Eutrophication Potential	    149
          b.   Bacterial Contamination	    151
          c.   Non-Point Source Loads	    154

     2.    Secondary Impacts	    154

B.   Impacts on Groundwater	    154

     1.    Groundwater Quantity Impacts	    154
     2.    Groundwater Quality Impacts		    155
     3.    Mitigative Measures	    156

C.   Population and Land Use Impacts	    156

     1.    Introduction.	    158
     2.    Population,"	    159
     3.    Land Use....	    159
     4.    Changes in Community Composition and Character	    159

D.   Development of Environmentally Sensitive Areas.	    159

     1.    Floodplains and Shoreline Areas	    160
     2.    Wetlands.. *;...•	    160
     3.    Natural Are^s.			    161
     4.    Archaeological and Historical Sites.	    161
     5.    Steep Slopes.'	    162
     6.    Prime Agricultural Land	    162

E.   Economic Impac^.,	    163

     1.    Introduction.,.	    163
     2.    User Charges.	    163
     3.    Local Cost; Burden		    167
     4.    Mitigative Measures	    168

F.   Impact Matrix. .-..,•	    169
                                    xvi

-------
                                                                 Page

                  VI --CONCISIONS;AND RECOMMENDATIONS

A.   Introduction.	    172

B.   Summary of Evaluation.	    172

C.   Conclusions. . . . ... . ......... . . ... ... .	    175

D.   Draft EIS Recommendation	    176

     1.   Small Waste Flows Approach for Green Lake
          and Nest Lake. . .  ;	    176
     2.   Wastewater Management for Spicer and New London	    177

E.   Implementation.	    178

     1.   Compliance with State and Local Standards in the
          Small Waste Flows District	     178
     2.   Ownership of On-Site Systems Serving
          Seasonal Residences		     179

               VII - THE RELATIONSHIP BETWEEN SHORT-TERM
                    USE AND LONG-TERM PRODUCTIVITY

A.   Short Term Use of the Study Area	    180

B.   Impacts Upon Long-Term Productivity	    180

     1.   Commitment of Non-Renewable Resources	    180
     2.   Limitations on Beneficial Use of the Environment....    180

                 VIII - IRREVERSIBLE AND IRRETRIEVABLE
                        COMMITMENT OF RESOURCES                   181

              IX  - PROBABLE ADVERSE ENVIRONMENTAL IMPACTS
                        WHICH CANNOT BE AVOIDED                   182

Glossary	 . .	         183
Bibliography	         196
                                    xvii

-------
                              TABLES




Table




   1-1    Projected 1995 Design Flow, Green Lake Facilities

II-l

II-2

II-3

II-4
II-5

II-6

II-7
II-8
II-9

11-10

11-11
11-12
11-13

11-14
11-15
11-16

11-17

11-18

11-19

Plan 	
Location and Lithologic Characteristics of Surficial
Deposits 	
Description of Mapped Soils in the Green Lake
Study Area 	
Physical Characteristics of Green Lake, Nest Lake,
and Woodcock Lake 	 	
Water Budget for Nest, Green, and Woodcock Lakes,...
Phosphorus and Nitrogen Budgets for Nest, Green,
and Woodcock Lakes 	
Types of On-Site Systems Found Along Green Lake
Shoreline 	
Summary of Data for On-Site Systems. 	 	 	 	
Results of Sanitary Survey 	
Population and Dwelling Units (1976-2000) in the
Proposed Service Area 	
Kandiyohi County Percent Share of Employment by
Industry I960 and 1970 	
Selected Services - 1972 	 	
Retail Trade - 1972 	 	
Financial Characteristics of the Local Governments
in the Green Lake Study Area 	
Housing Characteristics 1970 	
Housing Value - 1970 	
Single-Family Residential Development Restrictions
Imposed by Kandiyohi County 	
Recreational Potential of Lakes Within the
Study Area 	
Major Wildlife Management Areas Within the
Study Area 	
Public Access to Lakes in the Green Lake Study
Area 	 	 	
15

31

35

48
51

52

62
64
68

75

78
79
80

81
83
84

90

92

92

94
                                   xviii

-------
Table                                                            Page

III-l     Green Lake EIS Seryice-'Area Design Population
          and Flow (Year 2000)	     98

III-2     Estimated Savings with Flow Reduction Devices	     101

III-3     Small Waste Flow Management Functions by Operational
          Component and by Basic and Supplemental Usage	     127

 IV-1     Alternative Summary	     133

 IV-2     Cbst Effectiveness of Alternatives	     134

  V-l     Total Phosphorus Inputs Associated with the
          Various Alternatives for Green and Nest Lakes	     152

  V-2     Comparison of Population and Land Use Impacts.......     157

  V-3     Financial Burden and Displacement Pressure	     164

  V-4     Annual User Charges	     165

 VI-1     Alternative Selection Matrix	     173
                                     xix

-------
                             FIGURES

Figure                                                           Page

  1-1     Location of the Green Lake Study Area	    2

  1-2     Photographs of Green Lake Study Area	    3

  1-3     Base Map of the Green Lake Study Area	    4

  1-4     EIS Study Area	    7

  1-5     Existing Wastewater Treatment Facilities in the
          Green Lake Study Area	    9

  1-6     New London Sewage Treatment Plant	    10

  1-7     Spicer Sewage Treatment Plant	    11

  1-8     Monthly Cost of Gravity Sewers	    18

 II-1     Slopes of Greater Than 15 Percent Within the Green
          Lake Study Area	    27

 II-2     General Geologic Sequence Within the Green
          Lake Study Area	    29

 II-3     Surficial Geology of the Green Lake Study Area	    30

 II-4     Soil Limitations of the Green Lake Study Area	    32

 II-5     General Soils Map of the Green Lake Study Area	    34

 II-6     Hydrogeology of the Green Lake Study Area	    44

 II-7     Surface Water Hydrology of the Green
          Lake Study Area	    47

 II-8     Trophic Conditions of Nest Lake and Green Lake
          (1972-1973)	    54

 II-9     Flood Hazard Areas of the Green Lake Study Area	    56

 11-10    Location of Septic Leachate Plumes Around
          Green Lake and Nest Lake	    58

 11-11    Results of Aerial Observation of Septic Tank
          System Malfunctions	    59

 11-12    Results of 1978 EPA Construction Grant Survey	    61

 11-13    Green Lake Segment Location Map	    74

 11-14    Existing Land Use of the Green Lake Study Area	    86

 11-15    Future Land Use; Map of the Green Lake Study Area....    88
                                    xx

-------
Figure                                                           Page

III.-l     STEP System	   105

III-2     Flow Diagram of Facilities Plan Proposed Action	   106

III-3     Flow Diagram of Facilities Plan Proposed Action	   107

III-4     New London Wastewater Treatment Plant Upgrade	   108

III-5     Spicer Wastewater Treatment Plant Upgrade	   109

III-6     Flow Diagram -- Spray Irrigation	   Ill

III-7     Flow Diagram -- Rapid Infiltration	   Ill

III-8     Flow Diagram -- Rapid Infiltration	   112

III-9     Cluster System Sites Investigated During
          All Studies	   115

111-10    Spray Irrigation; Rapid Infiltration
          Illustration	   118

III-ll    Land Application Sites	   119

 IV-1     Proposed Facilities Design Process	   136

 IV-2     Location of Proposed Stabilization Pond and F.P.P.A..   137

 IV-3     EIS Alternative 1	,	   138

 IV-4     EIS Alternative 2	 .	   139

 IV-5     EIS Alternative 3 Map	   140

 IV-6     EIS Alternative 4 Map	   142

 IV-7     EIS Alternative 5 Map	   143

 IV-8     EIS Alternative 6 Map	   145

 VI-1     Phosphorus Loadings by Source Contributors	   150

 VI-2     Tropic Status of Green and Nest Lakes	   153
                                   xxi

-------
                          SYMBOLS AND ABBREVIATIONS
P

V

v
AWT

BOD

cm

DO

ft2

fps

g/m /yr

GP

gpcd

gpm

I/I

kg/yr

kg/cap/yr

kg/mile

lb/cap/day

mgd
An asterisk following a word indicates that the term is
defined in the Glossary at the end of this report.  Used
at the first appearance of the term in this EIS.

less than

greater than

Rho

Mu, micro

Nu

Sigma


     TECHNICAL ABBREVIATIONS

advanced wastewater treatment

biochemical oxygen demand (5 day)

centimeter

dissolved oxygen

square foot

feet per second

grams per square meter per year

grinder pump

gallons per capita per day

gallons per minute

infiltration/inflow

kilograms per year

kilograms per capita per year

kilograms per mile

pounds per capita per day

million gallons per day
                                     xxii

-------
mg/1

ml

mph

msl


MPN

N

NH3-N

NO -N

NFS

O&M

P

pH
ppm

psi

SS

STEP

STP

ST/SAS

TKN

TP-P

PS/1

EPAECO
DNR

EIS
milligrams per litre

millilitre

miles per hour

mean sea level—implies above msl unless otherwise
indicated

most probable number

nitrogen

ammonia nitrogen

nitrate nitrogen

non-point source

operation and maintenance

phosphorus, or "as phosphorus"

measure of acidity or basicity; <7 is acidic;
>7 is basic

phosphate

parts per million

pounds per square inch

suspended solids

septic tank effluent pumping

sewage treatment plant

septic tank/soil absorption system

total Kjeldahl nitrogen

total phosphorus as phosphorus

micrograms per liter

name of a mathematical model


  NON-TECHNICAL ABBREVIATIONS

Minnesota Department of Natural Resources

Environmenal Impact Statement

              xxiii

-------
EPA

EPIC

FWS


GLSSWD

HUD

MPCA

NOAA


NES

NPDES

RCM

SCS


STORE!

USDA

USGS
United States Environmental Protection Agency

Environmental Photographic Interpretation Center (of EPA)

Fish and Wildlife Service, United Stated Department of
the Interior

Green Lake Sanitary Sewer and Water District

United States Department of Housing and Urban Development

Minnesota Pollution Control Agency

National Oceanic and Atmospheric Administration, United
States Department of Commerce

National Eutrophication Survey

National Pollutant Discharge Elimination System

Rieke Carroll Muller Associates, Inc.

Soil Conservation Service, United States Department of
Agriculture

STOrage and RETrieval (data base system of EPA)

United States Department of Agriculture

United States Geological Survey, Department of the
Interior
                                    xxiv

-------
                                 CHAPTER I

                 INTRODUCTION, BACKGROUND AND ISSUES
A.   PROJECT HISTORY AND DESCRIPTION
          I
1.   BACKGROUND

     Partial Federal  aid in funding of municipal wastewater facilities
is authorized by Section 201 of the  Federal  Water Pollution-Control Act
Amendments  of  1972  (FWPCA),  Public  Law  92-500.   Funding  of projects
under Section 201  is  subject  to the provisions of the National Environ-
mental Policy Act  of  1969  (NEPA), Public Law  91-190.  Section 102(2)(C)
of NEPA  requires the  preparation of an environmental impact statement
(EIS) on  major  Federal  actions  significantly affecting the quality of
the human environment.  Guidance for preparation  of  this EIS is provided
by the Council on  Environmental  Quality's "Preparation of Environmental
Impact Statements:  Guidelines"  August 1, 1973  (40  CFR  Chapter V, Part
1500) and the Environmental Protection Agency's  "Manual for Preparation
of  Environmental  Impact  Statements  for  Wastewater Treatment  Works,
Facilities  Plans,  and  208 Areawide Waste  Treatment Management Plans"
July  1974.   Individual provisions   of  revised Council on Environmental
Quality guidelines  issued November  29,  1978  have  been  followed where
practicable.

     Federal funding  of proposed  wastewater  collection  and treatment
facilities in the  Green  Lake  Study  Area  of  Kandiyohi County, Minnesota
(see Figure 1-1) has  been  requested and  is  the subject of this Environ-
mental  Impact  Statement   (EIS).  Construction   of   the  facilities  was
recommended  in   the  "Preliminary   Feasibility   Report-Water  Pollution
Control Facilities  Green Lake Kandiyohi  County,  Minnesota", which will
be described later in this  Chapter.

2.   LOCATION

     Located approximately  100  miles west  of the  Minneapolis-St. Paul
metropolitan area, the Green  Lake Study  Area  comprises  about 24 square
miles of rolling fields,  farmlands,  wetlands,  and residential/commerical
lake-side  development (see  Figure 1-2).   It  includes  parts of New London
Township,  Green  Lake  Township,  Irving Township,  and Harrison Township,
as  illustrated  in  Figure  1-3.  The Facilities Plan Proposed Service
Area1 is also illustrated  in  Figure 1-3.  The combined year-round popu-
lation of  the  Study  Area  is  estimated  to  be 2,400, with  this figure
swelling to approximately 6,900 during  the vacation  season.
     Also referred to in  this  EIS  as the Green Lake Sanitary Sewer and
     Water District (GLSSWD)  Service  Area.

-------
   \
              MINNESOTA
             GREEN LAKE STUDY AREA
             HEBf LONDON
                 SPICER
                ©WILLBIAR
               KANDIYOHI
                 COUNTY
FIGURE I- 1  LOCATION OF THE GREEN LAKE STUDY AREA

-------
                FIGURE 1-2



PHOTOGRAPHS OF THE GREEN LAKE STUDY AREA
                                                             •

-------
                          FIGURE I- 3   BASE MAP  OF  THE  GREEN  LAKE  STUDY  AREA
                                              LEGEND


                                   	  	 TOWNSHIP BOUNDARIES


                                          EIS STUDY AREA BOUNDARY


                                          FACICITIES PLAN PROPOSED SERVICE AREA
NEW LONDON
  TOWNSHIP
                                                       IRVING TOWNSHIP
                                                      I CHETHICH LANGE SIATE

                                                      WILDLIFE MANAGEMENT AREA , T
           GREEN  LAKE
         LAKE
TOWNSHIP
                                                     HARRISON  TOWNSHIP

-------
3.   HISTORY OF THE  CONSTRUCTION GRANT APPLICATION
     A substantial amount of consideration was  devoted to the wastewater
management needs of the Study Area  before the preparation of the Environ-
mental Impact Statement.  A  chronology  of  the  actions  taken before and
during this study is listed  below.
1973
March 21,.1974

               5-



November 1974

December 16, 1974




February 21, 1975



April 3, 1975


April 24, 1975


August 28, 1975



November 20, 1975

November 25, 1975


March 2, 1976

August 16, 1976
Petition  of  the  Kandiyohi  County  Board  of  County
Commissioners to  establish  the Green Lake  Sanitary
Sewer  and Water  District  (GLSSWD),  in  accordance
with Minnesota Statutes,  Chapter 116A.

Agreement  for  Engineering  Services  between  Rieke
Carroll  Muller  Associates,  Inc.  and  the  County  of
Kandiyohi, Minnesota  for  a preliminary  survey  in
accordance with Minnesota Statutes 116A.

National Eutrophication  Survey  report  on Green Lake.

Submittal of  Preliminary Feasibility Report  on Water
Pollution  Control  Facilities   for  Green  Lake  and
vicinity, Kandiyohi County,  Minnesota to Kandiyohi
County Commissioners.

National  Pollution  Discharge  Elimination  System
(NPDES)  permit   issued  for   municipal   wastewater
treatment facility at  Spicer, Minnesota.

NPDES permit  issued for  municipal wastewater treat-
ment facility at New London,  Minnesota.

Establishment of  the GLSSWD by the Kandiyohi County
Board of Commissioners.

Official Application  for Construction Grants  under
the  Federal   Water Pollution   Control  Act  by  the
GLSSWD

State "priority"  certification  of proposed  project.

Application   for   construction  grant  received   by
United States Environmental  Protection Agency (EPA).

Step I Grant  offer made  by EPA  Region  V.

Additional  Facilities   Plan   Information   for  the
GLSWSC  submitted  to   Minnesota  Pollution   Control
Agency (MPCA).
September 17j 1976  Cohcerned Property Owners of Green  Lake  request  EPA
                    to prepare an EIS.

-------
September 18, 1976  Facilities Plan public hearing.
October 29, 1976
Submittal  of  preliminary  feasibility  report  and
supplemental information to MPCA.
September 28, 1976  MPCA requests Kandiyohi County  to  expand facilities
                    plan.

December 17, 1976   Submittal  to  MPCA  for  evaluation  of  additional
July 19, 1977

October 1977
facilities plan alternatives.

Notice of Intent to prepare an EIS

Preparation of EIS begins.
December 21, 1977   First public information meeting  to  discuss the EIS
                    process and  specific issues related to  Green  Lake.
May 17, 1978


October 1978
Formation  of  the  Green  Lake  Citizen's  Advisory
Committee.

First Citizen's  Advisory Committee meeting  to dis-
cuss EIS project scope and issues.
December 20, 1978   Second  Citizen's  Advisory  Committee   meeting   to
                    discuss  the  preliminary  EIS   alternative  report.

4.   THE  GREEN LAKE AREA FACILITIES  PLAN

     In November 1975, the Green Lake area Facilities Plan was submitted
to  EPA Region  V  by  the  Green  Lake Sanitary  Sewer and Water  District
acting  as  the  applicant  for  funding under the EPA Construction  Grants
Program.  The  GLSSWD Service Area  (as distinct from the Proposed  EIS
Service Area  illustrated  in Figure  1-4) encompasses the City of Spicer,
the  Village of New  London,  and the residential area  surrounding Green
Lake.   The  following items together constitute the  Facilities  Plan  for
the proposed GLSSWD Service Area (Rieke Carroll Muller Associates, Inc..,
1976):

     ®    Preliminary  Feasibilty  Report  on  Water  Pollution  Control
          Facilities  Green Lake Vicinity, Kandiyohi County,  Minnesota,
          prepared by Noyes Engineering Service and Rieke Carroll  Muller
          (RCM) Associates, Inc., dated December 16, 1974;  and

     e    Supplemental information  submitted to  the GLSSWD dated  August
          16, 1976.

     It must be emphasized here that although the  Facilities  Plan  ad-
dressed the implementation of both a  centralized  wastewater collection
and  treatment  system and  a water supply system to  serve Green Lake area
residents,  this EIS will only evaluate the construction and operation of
wastewater  management facilities.   The EPA Construction Grants Program
serves  to  partially  fund  wastewater  collection and  treatment systems,
not water distribution systems.

-------
FIGURE  1-4
EIS  SERVICE AREA
                 LEGEND

              EIS SERVICE  AREA
                        (METRIC" LAMGF S{ATE
                       WILOLIFE MANAGEMENT AAE

-------
      The following section summarizes the Facilities Plan's descriptions
  of  existing wastewater treatment facilities, water quality problems, the
  need  for the  project,  alternative solutions, and  the  course of action
  proposed.  It  should be noted that conclusions reached in the Facilities
  Plan  and reviewed here  are not necessarily those  reached  in this EIS.

  a.   Existing Wastewater Treatment Facilities

      There  are two  communities  in the  Green  Lake  Study  Area that are
  each  served  by independent sanitary sewer and storm sewer systems:  New
  London  Village and the City of Spicer.  The location of existing waste-
  water  treatment facilities serving these  communities  and their respec-
  tive discharge  points  are illustrated in Figure  1-5.   A brief descrip-
  tion of these  facilities  is presented below.

      New London Sewage Treatment Plant.   The  New  London  plant,  con-
  structed  in  1954,  provides primary treatment prior  to  discharge to the
  Middle  Fork  of the Crow River (see  Figure  1-6).  The  existing plant
  consists  of  a  control building which  houses  a  dry well on the lower
  level,  and controls,  office,  and laboratory space  on  the upper level.
  The treatment  plant contains,  in addition to  the  control  building,  a
  primary  clarifier or  settling  tank   (see  Figure  1-6)  and  a separate
  anaerobic  sludge  digester (see Figure  1-6).   Sludge drying beds (see
  Figure  1-6)  are also located on the  premises.   The treatment plant was
  designed for  an average daily flow of 129,000 gallons per day  (gpd).  No
  historical operating data  are available.  However, during preparation of
  the Preliminary Feasibility Report in August 1974, wastewater  flows were
  found  to  average  approximately 104,000  gpd  during normal  weather and
  130,000 gpd during wet weather.

      New London initiated  planning in 1969 to upgrade its present waste-?
  water  treatment facility.  The plans were completed in 1971.  The MPCA,
  however,  did not  approve the plans as  submitted because of a question
  regarding  the  handling  of chemical  sludge  produced in  the  phosphorus
  removal process.

      Spicer Sewage Treatment Plant.  This plant,  constructed  in 1954, is
  a  conventional primary plus  secondary wastewater  treatment plant with
  anaerobic  sludge  digestion.  The  plant consists  of a control building
  which  houses  a primary  clarifier  on the upper  level and  a trickling
  filter  on the  lower level  (see Figure 1-7).  The primary treatment unit
  is  a  "Spiragester" which  is a treatment unit combining a primary settl-
-  ing tank with  an anaerobic sludge digestion  tank at two levels similar
  to  an  Imhoff  tank.  The trickling filter unit is  a high rate,  tile media
  unit  with  a   rotating  splash plate  type distributor.   A  small final
  clarifier,  a   chlorine  contact chamber,  and  some  deteriorating sand
  sludge  drying  beds  are  located outside  of  the  control  buidling.  The
  plant  was  designed for an  average daily flow  of 86,000 gpd.  In August
  1974,  wastewater  flows averaged approximately 112,000 gpd during normal
  weather  and  116,000 gpd  during wet  weather.   No historical  wastewater
  flow  data  are available.  The  treatment plant  discharges  to Woodcock
  Lake  (see  Figure 1-7).

-------
FIGURE 1-5
                                                    EXISTING WASTEWATER  TREATMENT FACILITIES IN
                                                        THE GREEN LAKE  STUDY AREA
                                                                      LEGEND

                                                         A NEW LONDON WASTEWATER TREATMENT FACILITY

                                                            SPICER WASTEWATER TREATMENT  FACILITY
                  LONDON
              SERVICE AREA
                                                                           DIETRICH LANGE SJATE

                                                                          WILDLIFE MANAGEMENT AREA .

SPICER
SERVICE
AREA
                               WOODCOCK^	^,
                                 LAKE

-------
                          FIGURE 1-6
               NEW LONDON  SEWAGE TREATMENT PLANT
    Primary Clarifier
New London Plant Discharge

Anaerobic Sludge Digester
   Sludge Drying Beds
                               10

-------
        FIGURE 1-7
SPICER SEWAGE TREATMENT PLANT
       Control Building
Discharge to Woodcock Lake
           11

-------
     On-Site Systems.   Wastewater  generated  in the  remaining  parts of
the  Green  Lake  Study  Area  are  generally treated  by septic tank-soil
absorption systems (ST-SAS).  The  actual  size  and design of  these soil-
dependent  on-site systems  varies  considerably  according  to  when  the
system was installed and  what  sanitary  codes were in  effect  at the  time
of  installation.  There  are also  some summer cottages which supplement
in-house sanitary facilities with  outhouses or  chemical toilets.

b.    Existing   Problems  with Water Quality  and  Wastewater
     Treatment  Facilities

     The Facilities Plan has identified the  following problems associ-
ated with  the existing centralized wastewater collection and treatment
facilities:

     •    The present  Spicer and  New London  sanitary sewer  systems are
          both subject to  potentially excessive  infiltration/inflow.  A
          Phase  II  infiltration/inflow  survey is  recommended  for  each
          community;  and

     •    The  Spicer   and  New London  treatment  plants  do  not   meet
          Minnesota Pollution  Control  Agency 1974  discharge  require-
          ments.   In  order to  meet these requirements additional,  more
          efficient treatment capability  is  required  in each community.
          Plant operation improvements at  the existing Spicer-New London
          water  pollution control facilities  do not offer  the possi-
          bility  of  raising plant performance  to  levels  required by
          MPCA.

     The following problems  associated  with  existing  on-site systems in
the  Study  Area were also addressed by the facilities planners in 1976:

     •    An  estimated  55% of the on-site  wastewater disposal systems
          around  Green Lake cannot  comply  with the  4  foot separation
          parameter2   specified in the  Minnesota  Shoreland Management
          Act;

     •    The  same  55%  of  the  individual   disposal  systems cannot be
          upgraded to  comply with the Shoreland Management  Act because
          of  the small  size of  the platted  lots  around  Green Lake;

     •    Based upon EPA survey data, individual  disposal  systems around
          Green  Lake  are  contributing  to the nutrient loading of  this
          basin.    The  Facilities  Plan  indicated  that  the amount of
     The  Act  stipulates  that there be  a vertical  distance  of 4  feet
     between  the  bottom of  the  septic tank drainfield and the  highest
     known groundwater elevation.
                                  12

-------
          wastewater discharged to  Green Lake  from  septic tank drain-
          fields along its shoreline was  approximately 23% greater than
          the  total  discharge loading  from  Spicer and New  London (by
          letter,   William  Hendrickson,  RCM,  to  James  Roth,  MPCA,
          December 17,  1976);  and

     »    Many of the older individual  on-site  systems installed approx-
          imately 20 years ago may  be  cesspools*,  which are prohibited
          under current sanitation codes.

     The  Facilities  Plan  also  indicated  that Green Lake,. Nest Lake,
Woodcock Lake and the Middle Fork  of the Crow River have become increas-
ingly  rich  in nutrients  (nitrogen and  phosphorus)  because treatment of
municipal wastewater  at  plants in  Belgrade  (located  13  miles north of
the Study Area), New London and Spicer  is  inadequate.

c.   Proposed  Solutions: Alternatives Addressed  in the
     Facilities  Plan

     Given the reported constraints  and problems associated with current
wastewater management  practices in  the Study  Area,  a comprehensive set
of preliminary  alternative wastewater  management schemes was considered
in the facilities planning process for  the communities of New London and
Spicer as well as residents of Green Lake.  These are:

     •    Centralized wastewater collection and treatment by lagoons and
          mechanical facilities;

     e    Decentralized treatment  by individual on-site systems, cluster
          systems, and mound systems;

     «    Combinations  of  centralized  and  decentralized  collection/
          treatment options;

     e    Land application;

     •    Direct reuse of treated  wastewater;

     e    Discharge of  the District's  wastewater  to  the Willmar treat-
          ment facility (9 miles southwest of the Study Area);

     •    Upgrade or expand existing treatment plants at New London and
          Spicer;  and

     9    Install holding  tanks  in  lots  where groundwater is too high
          for compliance with  the  provisions of the Shoreland Management
          Act.

     Based  upon  cost-effectiveness  analysis   and  feasibility  of  com-
pliance with existing local codes, specifically the Shoreland Management
Act, only two alternatives were advanced for evaluation of  impact.  Each
provides  wastewater collection and treatment  for  the  entire GLSSWD.
                                  13

-------
     Alternative 1.   Centralized collection and treatment by waste  sta-
bilization lagoon  (180-day storage capacity) with controlled,  discharge1
to the Middle Fork of the Crow River east of Green Lake.

     Alternative 2.   Centralized collection and treatment by mechanical
oxidation ditch with continuous discharge to the Middle Fork of the  Crow
River east of Green Lake.

d.   The  Facilities  Plan Proposed Action

     The;  alternative  involving centralized collection and treatment by
waste stabilization lagoons was selected  as the Facilities Plan Proposed
Action because  it proved to be the most  cost-effective* of the  two final
alternatives considered.   The Proposed Action is cited  to be in  con-
currence  with  the  comprehensive   water  and  sewer  plan  adopted by
Kandiyohi  County  in  1973.    This proposed  alternative  is   discussed
further in Chapter III.

     The  projected  (1995) wastewater flows developed in the Facilities
Plan for  the Green  Lake Sanitary Sewer and Water  District are-  presented
in Table 1-1.
B.   ISSUES OF  THIS  EIS

     The purpose of  this  EIS  is to respond to  concerns  raised  regarding
the Facilities Plan  Proposed  Action identified by review agencies  (es-
pecially  the EPA),  local  officials and  the  public.  These  concerns,
involving, the possibility of  significant  environmental  impacts,  include
the following:

1.   COST  EFFECTIVENESS

     The total capital  cost for the Facilities Plan Proposed Action; was
estimated in the Plan  (August,  1976)  to  be $4.4 million.  This  repre-
sents  an investment  of: approximately  $875 per person  and  $3,709 per
existing dwelling unit  within  the  Facilities Plan Proposed Service' Area.
(see Figure  1-3).  The considerable disparity  of incomes between  rural
and urban area residents  means that the burden of these  costs  will fall
most heavily on those people least  able to afford them.

     It  is  also  questionable  whether  even total elimination  of  septic
tanks  will  have  a strong positive impact on overall  lake quality/.  An
assessment must  be  made  of all the major nutrient*  sources, such as
precipitation,  point  source*  discharges,  non-point source*  run^-off;, as
well as  septic  tank effluents,  before  it can  be demonstrated that the:
level  of commitment  of resources for proposed  large-scale facilities is
necessary.

2.   IMPACTS ON WATER QUALITY

      Although indirect evidence was presented  in  the Facilities  Plan
indicating  that  there  may  be  a  water  quality  problem- attributed to
                                  14

-------
TOTAL
                                                             Table I- 1

                                       PROJECTED 1995 DESIGN FLOW. GREEN LAKE FACILITIES PLAN
     SOURCE
                             1ST QUARTER
                            DEC, JAN, FEB
                      2ND QUARTER
                     MAR, APR, MAY
                       3RD QUARTER
                     JUNE, JULY, AUG
                        4TH QUARTER
                      SEPT. OCT. NOV
                     ANNUAL
                     AVERAGE
Spicer

     Flow, gal/day


New London

     Flow, gal/day


Green Lake

     Flow, gal/day


Nest Lake

     Flow, gal/day
133,000
156,000
 60.000
 32,000
133.000
156.000
 61.000
 32,000
H9.600
144,000
216,000
 66,400
133,000
156,000
 62,000
 32,000
137,000
153,000
100,000
 41,000
     Flow, gal/day
381,000
382.000
576,000
383,000
430,500

-------
malfunctioning  lakeshore  septic  systems,  the  relationship  between
deteriorating water quality and  inadequately functioning septic systems
was not documented.  With  the  exception  of two  isolated cases involving
high  nitrate nitrogen  levels  (greater  than  10  milligrams  per  litre
(mg/1))  in  domestic  wells along  the south  shore  of  Green Lake  (by
letter, William  Hendrickson,   RCM,  to James  Roth,   MPCA,  December  17,
1976), claims of possible  hazards  to  the public health have been unsub-
stantiated.

3.   ECONOMIC IMPACT

     The  average  local  share   per  residence of the  total capital costs
for  the Facilities  Plan Proposed Action  is approximately $2,1,80-^.   The
Plan  estimates the  annual user  charge  per resident  to  be $194,  which
includes  annual  debt retirement of  the amortized  local  share  of  the
project cost  and annual O&M costs.  The  user charge  represents approxi^
mately  1.4%  of  the  average   annual  income for  year-round  residents.
Seasonal  residents, particularly those in  smaller, less expensive homes
may come under considerable pressure to sell their property.

4.   INDUCED GROWTH AND SECONDARY IMPACTS

     Based  upon  their  experience  with  previous  wastewater  management
projects in rural lake areas,  the Minnesota Pollution  Control  Agency has
concluded that sewering  of Green Lake  may cause  the following:

     ®    Increased development of lakeside areas;
     o    Increased  development  of   adjacent  non-lakeside  areas;  and
     t>    A shift from seasonal to permanent occupancy.

5.   PUBLIC  CONTROVERSY OVER WATER  QUALITY

     Residents of  Harrison Township  and  Irving Township have expressed
concern  over the Facilities  Plan -  proposed  stabilization pond (i.e,
lagoon) system  and its  potentially adverse effects  upon local ground^-
water  quality.  Farmers and other citizens who live  in the vicinity .of
the  proposed treatment  site focus  their concern on  the  potential  for
contamination of domestic water supply wells through  lagoon  seepage into
.sandy  soils.  This concern  exists  despite  the  fact  that the  Plan
recommended installation of an impermeable  bentonite  liner during lagoon
construction.
C.   NATIONAL  PERSPECTIVE ON THE RURAL SEWERING PROBLEM

     The EIS  issues  discussed  above  are not unique  to  the proposed plan
for  wastewater  management  in the  Green Lake Study Area.  They are typi-
cal  of  the concerns  raised by a large number of wastewater projects for
rural  and  developing communities  that  have been submitted  to  EPA for
     This  figure  is based  on  RCM's  estimate of local share of project
     capital costs (December 17, 1976) and the estimated  number of  resi-
     dences in the Facilities Plan Proposed Service  Area  in  1976.

                                  16

-------
funding.  The  scope of the problem has  grown in the last  few  years  as
controversy has mounted over the high costs and possible impacts of pro-
viding conventional sewerage facilities to small communities.

1.   SOCIOECONOMICS
     To assess  the reasons  and  magnitude  of the cost burden  that  many
proposed wastewater  collection projects would impose on  small communi-
ties,  EPA  studied  more than  250  facilities plans  from  49-states  for
pending projects for  communities  under 50,000 population  (Dearth 1977).

     EPA found  that,  even with substantial State and Federal  construc-
tion grants, the costs of conventional sewering are  sometimes  beyond the
means of families  in  rural and serai-rural  areas.  This  was particularly
true  for   those communities  where the  new  facilities  proposed  would
result in annual user charges of more  than  $200 per  household.

     The Federal government has developed criteria to identify high-cost
wastewater facilities projects (The White House Rural Development Initi-
atives  1978).   Projects are  considered  to place a  financial  burden on
rural community users when annual user charges (debt service plus opera-
tion and maintenance) would exceed:

     •    1.5% of median household incomes  less than $6,000;

     •    2.0%  of  median household incomes between  $6,000  and $10,000;
          and

     •    2.5% of median household incomes  over $10,000.

Annual user charges exceeding these criteria would materially  affect the
households'  standard  of living.   Federal  agencies   involved  in funding
wastewater  facilities  will  work  with  the  community  to   achieve  lower
project costs through a change in the  project's scope or design.  If the
project's   scope  or design  is  not changed, the agencies will  work  with
the community until  they are assured  that  the community is aware of the
financial  impacts of undertaking the high-cost project.

     It is  the  collection  system  that  is  chiefly  responsible  for  the
high  costs  of conventional  sewerage  facilities for  small communities.
Typically,   80%  or  more of  the  total capital  cost for newly serviced
rural  areas  is  spent  for  the collection  system.   Figure  1-8  indicates
that  the costs  per residence for  gravity  sewers  increase  exponentially
as population  density decreases.  Primary  factors  contributing to  this
cost/density relationship were found to be:

     •    greater  length of  sewer pipe per dwelling in  lower-density
          areas;

     •    more problems  with grade,  resulting in more lift stations or
          excessively deep sewers;
                                  17

-------
                  FIGURE 1-8
  40




CO

I 30


o
a.
Ł

c
o



«o
OT

O
O
  10
                  COST ($/nonth)= 43e
       Source1 Dearth 1977
          2    4     6     8    10    12    14

            POPULATION DENSITY (persons/acre)



         MONTHLY COST OF GRAVITY SEWERS
                      18

-------
     0    regulations or criteria which set eight inches as the smallest
          allowable sewer pipe diameter;  and

     0    inability of  small  communities to spread capital  costs  among
          larger populations sewered previously.

In addition to  the  comparatively high costs of  sewers,  facilities  were
sometimes found to be more expensive than necessary due to:

     o    Oversophistication  in  design,  large energy  requirements,  and
          costly maintenance and operator expense;

     «    Use  of  expensive construction  materials  such as  non-locally
          produced brick and  block  and terrazzo  when  a prefab steel and
          concrete building would do; and

     ©    Abandonment  of  existing   treatment works   without  economic
          justification.

2.   SECONDARY IMPACTS

     Installation of  centralized collection  and  treatment  systems  in
previously unsewered areas can have  dramatic effects on development and,
hence, on the  economy,  demography and environment of  rural communities..
These effects can be desirable, or they may substantially offset commun-
ity  objectives  for water  resource   improvement,   land  use planning  and
environmental protection.
               i                                            i
     A community's potential  for recreational, residential,  industrial,
commercial  or  institutional   development  is determined   by  economic
factors such as the  availability of land, capital,  skilled manpower and
natural  resources.    However,  fulfillment of   this  potential  can  be
limited by  the unavailability  of facilities  or  services  such  as  water
supply, sewerage, electric  power distribution and transportation.   If a
missing community service  element is supplied,   development  of  one  type
or  another  may take  place  depending upon  prevailing local  economic
factors.   Such development is  considered to be "induced growth" and is a
secondary impact  of  the provision   of  the essential   community  service
element.                                                    '

     Secondary impacts of new wastewater facilities may be  highly desir-
able.  For example, diversification of the local employment base may be
possible  only  when  sufficient  wastewater  collection  and  treatment
capacity  is provided  for commercial or  industrial  development.   On the
other  hand,  new commercial or industrial development  may not  be  com-
patible with  existing  recreational or  agricultural   interests.   Resi-
dential development  accompanying expansion of the employment  base may
take place on  prime  agricultural land, steep  slopes or wetlands, or may
otherwise infringe on valued natural features.
                                  19

-------
3.    THE  NEED  FOR  MANAGEMENT  OF  DECENTRALIZED ALTERNATIVE
     SYSTEMS

     A promising  alternative  to expensive centralized sewer systems  in
rural areas is a decentralized wastewater management system.  Both engi-
neering and management are  integral  parts of such a  system  and  "decen-
tralized alternatives," as  used  in  this  EIS,  incorporate both  engineer-
ing and management elements.

     Briefly,  the  engineering element consists  of  the use  of existing
and new on-site  systems,  rehabilitation  or replacement of those  systems
where necessary, and construction of small-scale off-site systems where
existing onsite systems are not acceptable.

     The management  element consists of continuing supervision  for  the
systems'  installation,  maintenance and rehabilitation and of  appropriate
monitoring of the systems'  environmental  impacts.

     While  other  factors  such as  soil  characteristics,   groundwater
hydrology and lot  configurations are highly important, adequate  manage-
ment  may  be critical  to  the success  of decentralized alternatives  in
many  communities.   Similarly, lack  of adequate management  undoubtedly
contributed to past  failures  of many on-site  wastewater  facilities and,
therefore,  the  lack of  trust in which  they  are held by local  public
health officials and consulting engineers.

     Historically, State  and  local  health officials were not  empowered
to  regulate  installation of  on-site  systems  until  after World  War  II.
They  usually  acted in only an advisory  capacity.   As the adverse con-
sequences of unregulated use  of the septic tank-soil  absorption  systems
became  apparent  in  the  1950's and 1960's,   they  were  granted  new
authority.  Presently more  health officials  have authority  for permitt-
ing and  inspecting or denying  new  installations,  and they  can  require
renovation and  replacement  of on-site systems.   However, their  role  in
the operation and  maintenance of on-site systems remains largely advi-
sory.  There  is seldom either  a budget  or the authority to inspect  or
monitor a system.

     In the Clean  Water  Act Amendments of 1977,  Congress recognized  the
need  for  continuing  supervision  and  monitoring  of on-site systems.  EPA
regulations implementing  this  Act  require that before  a  construction
grant for on-site  systems  is  awarded,  the applicant must meet a number
of requirements such as:

     o    Certify  that  it will be responsible for properly  installing,
          operating and maintaining  the funded systems;

     &    Establish a  comprehensive  program for regulation  and  inspec-
          tion of  on-site  systems that will include  periodic testing of
          existing potable water wells and more  extensive monitoring of
          aquifers; and

     ©    Obtain assurance of unlimited access to each individual system
          at all reasonable times for  inspection, monitoring,  construc-
          tion,  maintenance,  operation,  rehabilitation and  replacement.

                                  20

-------
     In some  cases  implementation of these  requirements  by municipal-
ities may  be  hindered by lack of  state  enabling  legislation for small
waste flow management districts and by lack  of  adequately trained man-
power.  The municipality  may  have  no control over the former and be at a
disadvantage because of the  latter.  Other implementation factors, over
which  municipalities  should  have  control,  are  discussed  in  Section
III.D. of this EIS.
D.   PURPOSE AND APPROACH OF THE  EIS AND CRITERIA FOR
     EVALUATION OF ALTERNATIVES

1.   PURPOSE

     This EIS documents  EPA's review and analysis of the application for
EPA Step 2  funding  of the  Facilities  Plan Proposed Action.   Based upon
this review, the Agency  will take one  of several actions:

     •    Approve the grant application,  possibly with recommendations
          for design changes and/or measures to mitigate impacts of the
          Facilities Plan Proposed Action;

     •    Return  the application with  recommendations  for  additional
          Step 1 analysis;

     •    With the  applicant's  and State's  concurrence,  approve Step 2
          funding for  an  alternative  to  the Facilities  Plan  Proposed
          Action, as presented  in this EIS; or

     •    Reject the grant  application.

     The review and  analysis focused on the issues identified in Section
I.E. and was  conducted  with an awareness of the more general considera-
tions of rural sewering  problems discussed in Section I.C.  Major empha-
sis has been  placed  on  developing and evaluating alternative wastewater
management  approaches to be compared  with  the  Facilities Plan Proposed
Action.

2.   APPROACH

     The review  and  analysis reported in  this  EIS  included  a series of
tasks, which  were undertaken  in approximately  the following sequence:

a.   Review of  Available Data

     Data presented  in  the Facilities Plan and  other  sources  were re-
viewed  for  applicability   in   development  and/or  evaluations  of  the
Facilities  Plan  Proposed  Action and  of  the  new alternatives developed
for the EIS.  Documents  consulted are listed in the bibliography at the
end of this volume.
                                  21

-------
b.   Segment Analysis

     As a basis  for  revised  population  projections  and  for development
of alternatives,  the  EIS Proposed Service Area was  partitioned  into  a
number of segments.   The  number of dwellings in each segment was counted
from  black  and  white  aerial photographs.   Available  information  on
soils,  depth  to  groundwater,  water  quality  problems,  environmentally
sensitive areas and  land  use  capabilities was tabulated for each segment
and the tabulations used to  make preliminary  estimates  of the need for
off-site wastewater  disposal.

c.   Review of  Wastewater  Design Flows

     Available population projections were revised on the basis  of the
segment house  counts.  New EPA  guidelines  for estimating  design  waste-
water flows were  then  used to revise the year 2000 wastewater flow pro-
jections.

d.   Development of  Alternatives

     First,  technologies that might  potentially reduce project costs or
minimize  adverse impacts while  still  solving  existing  problems  were
examined.   Four  categories  of alternative technologies --  flow  reduc-
tion,  low-cost  sewers,  decentralization,  and land  application  -- were
considered  according  to  their  functions  in  a  wastewater  management
system.   Next,  several specific areawide  alternatives  were  developed,
combining the  alternative  technologies  into complete  wastewater man-
agement systems  that would serve the Proposed  Service Area.   The tech-
nologies and the alternatives are described in Chapter III.

e.   Estimation of Costs  for Alternatives

     In order  to assure comparability  of  costs  between the  Facilities
Plan  Proposed  Action  and new alternatives,  all  alternatives  were de-
signed to serve a fixed design year population.  Total present worth and
local  user  charge  estimates  were based  upon unit  costs listed  in  a
separate engineering report  (Arthur Beard Engineers, Inc.  1978).

f.   Evaluation of the Alternatives

     The new alternatives were developed with a  knowledge of the local
environmental  setting  and  with the understanding that  they will  be
evaluated under criteria from several disciplines.  The general criteria
for  evaluating  the  Facilities Plan  Proposed  Action  and the  new  alter-
natives are listed in Section I.D.3 below.

g.   Needs  Documentation

     The need for improved treatment  of  New London's and Spicer's waste-
water is clear and is not an  issue in this EIS.  However,  the effects of
lakeshore septic systems on water quality and public health had not been
clearly  documented  in  the  Facilities  Plan.  Because  determination of
                                  22

-------
eligibility  for  Federal  funding   of   a   substantial  portion  of  the
Facilities Plan  Proposed Action will be  based  on the documentation of
these effects, several supplemental  studies were conducted:

     o    an  aerial  survey  of visible  septic  tank system malfunctions
          using  low-altitude  color  and  infrared   photography  by EPA's
          Environmental  Photographic   Interpretation   Center  (EPIC);

     •    estimation  of  the  existing  Green Lake nutrient  budget  and
          empirical modeling of  the  lake's  eutrophication status;

     •    a sanitary  survey of  lakeside  residences  to evaluate usage,
          design and condition of on-site  systems;

     e    a "Septic  Snooper" survey to locate and  sample  septic tank
          leachate plumes entering Green Lake and Nest Lake  from nearby
          on-site systems;

     •    a  hydrologic  survey  by  K-V  Associates  to  determine  base
          hydrologic data for the Study  Area; and

     •    evaluation  and mapping  by  the Soil  Conservation  Service of
          soils  within potential  cluster  and   land  application sites.

h.   Public Participation

     The Green Lake  Citizen Advisory Committee  was formed to aid EPA in
the  development  process  of  alternative  treatment and disposal systems
for  their  community.   The  committee has  convened  on  two occasions over
the  past  eight  months  to  discuss  EIS  scope  and  issues  as  well  as
preliminary EIS alternatives.

     The results of these needs  documentation studies were not available
for  consideration  in the  initial  development   of  alternatives.   The
results  of each  study  have required  continuing modification  of  the
alternatives as initially designed and have been the basis for necessary
refinements in the  determination of the eligibility  for Federal funding
of any new sewers around  Green Lake.

3.   MAJOR CRITERIA FOR  EVALUATION OF ALTERNATIVES

     While  the  high  cost   of sewering  rural communities is a primary
reason  for examining  alternative approaches to wastewater  management,
cost is not the only criterion.  Trade-offs between cost and  other major
impacts will  have  to  be  made.  The  various criteria  are defined below.

a.   Cost

     With some exceptions for innovative  technologies, EPA construction
grant regulations allow funding  of only  the most cost-effective alterna-
tives.  Cost-effectiveness  has  been measured here as the total present
worth of  an alternative, including  capital costs   for facilities needed
now, capital costs for facilities required  later in the 20-year planning
period, and operation and  maintenance  costs  for all wastewater facili-
ties.  Salvage value  for facilities expected  to be in service after 20

                                 23

-------
years has been  deducted.   Analyses  of cost-effectiveness do not  recog-
nize differences between public and  private  expenditures.

     The  responsible  municipality  or  sanitary district  will recover
operation, maintenance and local  debt  retirement costs  through periodic
sewage bills.   The  local economic  impact  of new wastewater facilities
will be felt  largely  through  associated  residential  user charges.  Only
publicly  financed  costs  were  included  in  residential  user  charges.
Salvage was  not factored into  residential user charges.

     According to the  Facilities Plan,  the local share of the total pro-
ject cost per residence will be approximately $1,950.  In addition, some
homeowners  may  incur  costs  that they  would  directly  have to  pay  to
contractors.  Installation of  gravity  house sewers  on private land and
renovation or replacement of  privately owned on-lot  systems for season-
ally occupied  dwellings  are  not  eligible  for  Federal  funding and are
seldom financed  by  municipalities.   These  private  costs are identified
for each alternative.

b.    Significant   Environmental  and    Socioeconomic   Impacts

     The  system  selected for  the Proposed  Service  Area will  impact  on
environmental  and  socioeconomic   resources  within  the  Study  Area.
Following a  comprehensive  review  of possible impacts of the Facilities
Plan Proposed Action  and  the  new alternatives,  several  types of impacts
were determined  to  warrant in-depth  evaluation and discussion in this
EIS.  These impacts  are classified as follows:

     o    Surface Water Quality Impacts;
     o    Groundwater  Impacts;
     o    Population and Land  Use Impacts;
     o    Economic Impacts; and
     0    Infringement on Environmentally Sensitive Areas.

c.   Reliability

     Reliability  criteria  for  the alternatives include  both ability  to
remedy existing water  quality  problems  and prospects  of  protecting water
quality in the future.  This  first criterion was applied in the analysis
of  surface  and  groundwater  impacts  of  the  alternatives  presented  in
Chapter IV.   That analysis assumed that the collection, treatment and
disposal  units  of  each alternative  would   operate  effectively  as de-
signed. The  second  criterion  recognizes  that all structural, mechanical
and electrical facilities are  subject to  failure.

d.   Flexibility

     The  capability of an alternative to accommodate increasing  waste-
water  flows from future development  in the Proposed  Service Area  is
referred  to  as its flexibility.  In order  to  demonstrate the relative
levels of investment  for different  alternatives,  all were designed and
costed to provide service for the  .same population  —  the design year
population projected in Chapter II.   However, factors such as the  amount
of  land that could  be developed using on-lot systems or the ability  to
                                  24

-------
increase  the  capacity  of a  treatment plant  might have a  significant
effect on future  development  in the Study Area.  The  capability of the
alternatives to  accommodate  increased wastewater  flows is  reviewed in
Chapter III.  The effects of  the alternatives'  flexibility on population
growth are predicted in Chapter IV.
                                  25

-------
                              CHAPTER II

                       ENVIRONMENTAL SETTING
     Evaluation of the courses of action open to EPA in  the  consideration
of  improved  wastewater management for  the Green Lake  Study Area  must
begin with an  analysis  of the existing situation.  This chapter  offers
an  inventory of  baseline  conditions  in the natural  environment, divided
into such  categories  as soils, groundwater, surface water  and biology.
Social and economic  aspects  of the man-made environment are  discussed,
along with the  functioning of wastewater treatment  facilities presently
in operation.

     Maximum use  was  made of available information in the analysis  of
the  Study  Area's environmental setting.  It was necessary, however,  to
undertake  additional  field  work  in  order to obtain more  comprehensive
data that  would  be  utilized  to document a need  for improved  wastewater
management  facilities  and  develop   appropriate alternatives  to   the
Facilities Plan Proposed Action.   For example,  this  information was  used
to  resolve such  key  issues  as the need to sewer the entire  shoreline of
Green Lake  and the need  to   include  a  portion  of Nest  Lake  in the  EIS
Service Area.  The new studies included:   a sanitary survey;  a sampling
of  leachate  plumes  from  septic  systems; an aerial  survey  of visible
septic tank  malfunctions;  a  soils survey; estimation of nutrient loads
entering Green Lake;  and  modeling of the lake's trophic condition.   In
general,   data  given  in the  tables  are not repeated in  the text,  and
readers  wishing  more  information should  use the  Appendices for  more
complete explanations and  details.
A.   PHYSICAL  ENVIRONMENT

1.   TOPOGRAPHY

     Topographic relief within the Green Lake Study Area was formed by a
mass of retreating glacial ice between ten and sixty thousand years ago.
Elevations range from 1300 feet above mean sea level (msl)  just north of
Green Lake  to  1160 feet above msl immediately east  of  Green Lake.  The
Study Area  is drained  primarily  by  the Middle Fork of  the  Crow  River.

     There  are  two  distinct topographic areas  found  within  the  Study
Area.   Forested,  rolling topography  and  steep slopes  characterize  the
area north  of  Green Lake while the area  east  and  southeast of the Lake
becomes more  level and  is  primarily agricultural.  A  large  wetland is
located east of Green Lake.

     Most slopes within the  Study Area are  gentle (1 to 4%),  but some
areas  contain  slopes  greater  than  15%  (Figure  II-l).   These  latter
locations are considered less suitable for land development.
                                  26

-------
                                                     FIGURE II-l   SLOPES GREATER THAN 15 PERCENT WITHIN THE
                                                                           GREEN LAKE STUDY AREA
                                                                                 LEGEND

                                                                         SLOPES GREATER THAN 15%

                                                                  NOTE:  NUMBERS IN LAKES INDICATE
                                                                           LAKE ELEVATION
Source: USGS
1967; USGS
date unknown  ,  ~^-^j
                 %

-------
2.   GEOLOGY

a.   Bedrock Geology

     Bedrock underlaying the Study Area is comprised of undifferentiated
Precambrian igneous and metamorphic rock material.   The predominant rock
types are  gneiss,  granites  or schists, overlain by a surficial layer of
glacial drift.  A  general  overview of the geologic  sequence within  the
Study Area is shown in Figure II-2.

b.   Surficial  Geology

     All  surficial  material within  the  Study Area was deposited  by an
ice advance ten and sixty thousand years ago.   The  extent  and  lithologic
characteristics of surficial material within the Study Area are shown in
Figure II-3 and described in Table II-l.

     East  of Green Lake  along the  Middle  Fork of  the  Crow  River  are
deposits  of  surficial outwash  composed  of fine to  coarse  grained sand
and gravel with  traces  of silt and  clay.  However,  the majority of  the
Study Area is made up of undifferentiated glacial till made up  of poorly
sorted calcareous*  silt  (Lindholm et al. 1974).  Sand and gravel lenses
of varying thicknesses may be found throughout the  Study Area.

3.   SOILS

     In  the   Green Lake  Study Area,  soil  suitability  determines  the
extent to which alternatives to centralized wastewater treatment-surface
water discharge systems may be developed.  Following a soil survey,  the
US Department  of Agriculture, Soil  Conservation Service  (SCS)  normally
provides  soil  suitability   data,   including  permeability,   depth   to
seasonally high groundwater,  compaction,  and  expansion to engineers  and
planners for use  as a decision making tool in the  preliminary  selection
of  wastewater management  alternatives.   Alternatives  involving  soil-
dependent  components  are  discussed  in  Chapter   III.    The   SCS  has
scheduled completion  of the Kandiyohi County Soil Survey  for  1983,  but
limited soil suitability  data  is  available for the  Study  Area.   During
this project,  SCS personnel  have augmented this  limited  data base  by
mapping an additional 700 acres in the Study Area.   This additional data
were used to  identify potential  land  application  and cluster  system
sites in  the vicinity of  Green Lake (discussed in  Chapters III and IV).
The extent of mapped  SCS  data, except those areas  selected as  potential
cluster system sites (see Appendix A-l) is shown in Figure II-4.

     Soils in the Green Lake Study Area were developed by  weathering  and
erosion from the underlying glacial deposits.   Vegetative  processes have
created a  surface  layer  of rich, dark  soils one to three feet  thick.
These soils  are  underlain  by  glacial till composed of sand and  gravel
several hundred feet thick.

     The four primary  soil  groups represented within the  Study Area  and
their limiting factors are listed  below.   The term  "limiting factors" as
used in these characterizations,  refers  to a possible deterrent  to  the
operation of on-site  sewage disposal systems (see  Appendix A-2).   These
                                  28

-------
1300'-
1200'-
1100
1000-
900
 800'
 700
                                                                       LEGEND
                                                       |      I OVERBURDEN
                                                       \\\\\1 SAND AND GRAVEL,  BURIED;
                                                                  CONFINED
E'-..'?V?.] UNDIFFERENTIATED DRIFT
                                                              UNDIFFERENTIATED  IGNEOUS AND
                                                                  METAMORPHIG ROGKS
                                                        't': Linclliolm et.al.  197A
           FIGURE 11-2   GENERAL GEOLOGIC  SEQUENCE WITHIN THE GREEN LAKE STUDY AREA

-------
                                                              FIGURE II-3    SURFICIAL GEOLOGY OF THE GREEN
                                                                               LAKE STUDY AREA
                                                                                   LEGEND


                                                                         UN1JIFFERENTIATED DRIFT (END MORAINE)

                                                                         SURFICIAL OUTWASH

                                                                         UNDIFFERENTIATED DRIFT (TILL ^
Source:  Lind-
holm et. al.
1974           , ^

-------
                                               Table II-l

                      LOCATION AND LITHOLOGIC CHARACTERISTICS OF SURFICIAL DEPOSITS
                     Thickness
                       (ft.)
               Location  in
               Study  Area
                    % of
                 Study Area
                   Lithologic Characteristics
Alluvial
 Variable
Streams and
Rivers
              Thin deposits of sand, gravel, silt,
              or clay.
Surficial
Outwash
   0 - 100
 (20 -  50
 commonly)
East of
Green Lake
              Fine to coarse-grained sand and
              gravel; some silt and clay, stratified;
              commonly moderately to well sorted.
Undifferentiated
Drift (till
plain)
 100 - 500
(200 - 500
 commonly)
Northeastern
corner of
Study Area
  3%
Primarily gray, calcareous, silty till;
unstratified and unsorted, contains
buried sand and gravel lenses of
varying extend and thickness.
Undifferentiated
Drift (end
moraine)
 100 - 500
(200 - 500
 commonly)
All except
North and
East of
Green Lake
^82%
Primarily gray, calcareous, silty till;
unstratified and unsorted; includes
some ice - contact.  Sand and gravel
of largely unknown extent, contains
buried sand gravel lenses of varying
extent and thickness.

-------
                                                            FIGURE II-4    SOIL LIMITATIONS OF THE GREEN
                                                                            LAKE STUDY AREA

                                                                                    LEGEND
                                                                          SEVERE LIMITATIONS  FOR ON SITE
                                                                                WASTEWATER DISPOSAL

                                                                          SLIGHT TO MODERATE  LIMITATIONS
                                                                                FOR ON-SITE WASTEWATER
                                                                                DISPOSAL

                                                                        I  AREA NOT YET MAPPED BY THE SOIL
                                                                                CONSERVATION  SERVICE
        20OO   4Onn
Source:  Soil
Conservation Ser-
ice, Willmar Of-
fice 1977

-------
factors  include  (1)  steepness  of  slope,  (2)  stoniness,  (3)  depth  to
bedrock, (4) depth to seasonally high groundwater,  and (5)  permeability.
However, use of  the  term,  limiting factors,  does  not eliminate  the  soil
groups from consideration (see Appendix A-3).   The  four soil  groups  are:

     •    The  Lester-Clarion-Salida  group is  comprised of  steep  well
          drained  loam,  intermixed  with  sandy  soils.   The   limiting
          factor"" within this group is steep  slopes.

     •    The  Salida-Esthervile-Clarion  group is  comprised  of  well  to
          excessively well drained sand and gravel  intermixed with loam.
          Rapid  permeability,   steep  slopes  and  high groundwater  are
          Limiting factors in this group.

     •    The  Esthervile-Biscay-Peat  group   is   comprised  of  poorly
          drained  loamy  glacial outwash underlain  by sand  and  gravel.
          Seasonal  high water  table  is   the  limiting  factor  in  this
          group.

     •    The Clarion-Storden-Peat group is comprised of well drained to
          poorly  drained  loamy  soils with  marshes.   Permeability  and
          seasonal high water table are limitations in this soil.

     General locations of these soils are  shown in Figure II-5;  they are
described in greater detail in Table II-2.

a.   Soil  Suitability for Wastewater Treatment

     A generalized map of the Study Area displaying soil limitations for
on-site wastewater disposal systems is shown  in Figure II-4.  The feasi-
bility of utilizing  land  application methods  for  the disposal of waste-
water  within  the  Study Area  depends  upon the suitability of the soils
present.

     Within the  Study Area,  the  major factors restricting  the use  of
some  soils  for on-site waste  disposal systems are  permeability and  a
seasonal high water table.   In acknowledgement of  this problem,  thirteen
potential sites  for cluster*  systems were examined  by the  SCS at the
request of EPA.  Also examined and mapped  by  SCS was one potential spray
irrigation"1' site, and one potential rapid  infiltration* site.

     The results  of these  field  investigations and  maps of the suit-
ability of  these  sites  for wastewater disposal are  located  in  Appendix
A-l.

b.   Prime Agricultural  Lands

     The SCS has  set forth general guidelines for a national program of
inventorying prime and  unique  farmland (42 F.R.,  August 23,  1977).   Any
action  (such as  construction of interceptors, highways, buildings)  that
tends  to  impair the  productive capacity of American  agriculture is of
concern  to  SCS because  such action may reduce the  land's capacity for
producing food,  fiber,  feed,  foliage and other crops.   SCS  in  coopera-
tion  with   other  interested state  and local  agencies  is  inventorying
these  lands  to   determine  the  potential  effects  of construction  and

                                  33

-------
FIGURE II-5
GENERAL SOILS MAP OF THE GREEN
   LAKE STUDY AREA
                    LEGEND

           LESTER-CLARION-SALIDA GROUP

   i-.:ŁM] SALIDA-ESTERVILLE-CLARION GROUP

           ESTERVILLE-BISCAY-PEAT GROUP

           CLARION-STORDEN-PEAT GROUP

           GRAVEL PITS
                        Source:  Kandiyohi County  [Mn.]
                        Planning Commission 1973;  By
                        telephone, Al Gienke, Soil Con-
                        servation Service, 2 November

-------
                                                                      Table  II-2

                                               DESCRIPTION OF MAPPED SOILS IN THE GREEN LAKE STUDY AREA
Soil Type
Description
Depth (In)
Location Within the
    Study Area
                 Depth to
                 Seasonal
Permeability    High Water        Suitability for
   (in/hr)      Table (ft)    On-Site Waste Disposal    Soil Capability Class**
Alluvium
             Poorly drained mixed
             alluvial soils
                                      Variable
Biscay       Poorly drained soils       0-20
             formed in loamy gla-      20-36
             cial outwash;  under-      36-60
             lain by sand and
             gravel

Clarion      Well drained loamy         0-17
             soils; formed  in          17-32
             calcarous glacial         32-60
             till under prairie
             vegetation

Dickenson    Well to somewhat           0-30
             excessively drained;      30-50
             moderately coarse         50-60

Esterville   Well drained sandy         0-13
             and loamy soils           13-18
                                       18-60

Glencoe      Deep, very poorly          0-35
             drained soils  form        35-48
             in glacial till in        48-60
             depressions and
             swales in the
             uplands
                                  Along streams and
                                  drainageways
                                  especially north
                                  of Creen Lake

                                  Scattered in north-
                                  east corner of the
                                  Study Area
                                  Scattered north of
                                  Creen Lake,  between
                                  Creen and West Lakes
                                  Southeast of Green
                                  Lake

                                  North and south of
                                  Nest Lakes
                                  Widely distributed
                                  particularly west
                                  of Creen Lake

                                  Between Nest and
                                  Creen Lakes
                                                                            Variable
                                        0.6-2.0
                                        0.6-2.0
                                        0.6-2.0
                                        0.6-2.0
                                        0.6-2.0
                                        0.6-2.0
                                        2.0-6.0
                                        6.0-20.0
                                        6.0->20.0

                                        2.0-6.0
                                        2.0-6.0
                                        6.0-20.0
                                                                                             2-4
                                                                   Severe; flood hazard
                                          2-2.0
                                          2-2.0
                                                            0.2-2.0
                                          1-3        Severe; high water
                                                     table
                                           >6        Slight; <5% slope
                                                     moderate; 5-14%
                                                     severe; >14%
                                           >10       Slight; <5%
                                                     moderate; 9-14%
                                                     severe; permeability

                                           >6        Slight; 0-8%
                                                     moderate; 8-15%
                                                     severe; >15%

                                          0-3        Severe; high water
                                                     table
                                                                               IIw
                                                        II w if slope is <2%
                                                        I & lie if slope <5%
                                                        Hie & IVe
                                                        III w drained
                                                        VW undrained
     "Capability subclasses are soil groups within one class;  they are designated by a small letter which follows the Roman Numeral II.  (There
     are no subclasses in Class I because these soils have few limitations.)   Examples are "e" = risk of erosion is main limitation; "w" = wet
     soil; "s" = droughty, shallow,  or stony soil.   Class I and Ile/w/s soils are the criteria upon which prime agricultural land is identified
     In Kandiyohi County.

-------
                                                                      Table II-2

                                         DESCRIPTION OF MAPPED SOILS IN THE GREEN LAKE STUDY AREA  (Continued)

Soil Type
Hamel
Houghton

Description
Deep, poorly drained
soils formed in loamy
glacial till tn
swales, rims of
depressions, drain-
ageways and foot-
slopes
Very poorly drained
soils formed In thick

Depth (in)
0-22
22-41
41-60
0-66

Location Within the
Study Area
Scattered between
Nest and Green taken
Scattered northwest
of Nest Lake

Permeability
(in/hr)
0.2-2.0
0.2-0.6
0.6-2.0
Variable
Depth to
Seasonal
High Water Suitability for
Table (ft) On-Site Waste Disposal Soil Capability Class**
1-3 Severe; high water II w drained
table and slow IV w undrained
percolation
0-1 Severe; wetness III w
and ponding
             herbaceous organic
             deposits

Lester       Undulating to steep,       0-9
             well drained soils         8-36
             formed In glacial         36-60
             till on convex
             upland slopes

Harkey       Very poorly drained        0-32
             soils formed In           32-60
             deposits of organic
             material over sand

Marsh        miscellaneous lands      Variable
             with shallow lakes,
             and sloughs; peaty
             muck or a loamy
             mineral soil

Nlcollet     Deep, moderately           0-17
             will to somewhat          17-36
             poorly drained soils      36-60
             formed under tall
             grass prairie in
             loamy glacial till
Scattered throughout      0.6-2.0          >5
the Study Area            0.6-2.0
                          0.6-2.0
Along shores of           6.0-10.0        0-1
Green Lake                6.0-20.0
Northeastern corner      Variable        Above
of Study Area; south                     water
of Green Lake between                    table
Woodcock & George
Lake

Widespread distribu-      0.6-2.0       3.0-5.0
tion southeast of         0.6-2.0
Green Lake                0.6-2.0
Moderate; 2-12%
Severe; >12% slope
Severe; high
water table
Severe; ponded
Severe; high water
table
lie <6% slope
Hie 6-12% slope
                                                                               IV w

-------
                                                         Table II-2

                            DESCRIPTION OF MAPPED SOILS IN THE GREEN LAKE STUDY AREA (Continued)
Soil Type . Description
Okoboji Very poorly drained
soils in saucer-like
depressions or sloughs
in uplands; formed In
local alluvium or
waterworked glacial
sediments under marsh
grass or sedges
'.0
~""*J Palms Very poorly drained
soils in deposits of
organic material
over loamy mineral
deposits
Salida Shallow excessively
drained gravelly
sandy loam



Sandia Excessively drained
soils formed in coarse
outwash materials
under grass prairie
on valley trains and
glacial outwash
plains
Storden Deep, somewhat
excessively drained
soils formed in
Depth (in)
0-32

32-60






0-35
35-60



0-8
8-12
32-60



0-8
0-8
8-12
12-60



0-8
8-60

Location Within the
Study Area
North of Nest and
Green Lakes







North of Green Lake




South of Nest between
George Lake and
Woodcock Lake, North
of Green Lake


Distributed widely
north of Nest Lake
& west part of
Green Lakes between
George & Woodcock
Lakes

Widespread and
scattered north of
Green; between
Permeability
(ln/hr)
0.06-0.2

0.06-0.2






6.0-1.0
0.6-2.0



6.0-2.0
>20.0
>20.0



6.0-20.0
6.0-20.0
>20.0
>20.0



0.6-2.0
0.6-2.0

Depth to
Seasonal
High Water Suitability for
Table (ft) On-Site Waste Disposal
0-3 Severe; slow
permeability
High water table






0-1 Severe; high water
table; ponding



>6 Moderate;
permeability ,
slopes
Severe ;
permeability ,
slopes
>6 Slight; <8% slope
moderate; 8-15%
severe; >15%




>6 Slight; <8%
moderate; 8-15%
severe; >15%
Soil Capability Class"
III w 0-2% slope








III w











IV-s to VII-s






He 2-6% slope
Hie 6-12% slope

glacial till
Green and Nest Lakes;
south of Nest Lake;
between Woodcock and
George Lakes.

-------
                                                                      Table TI-2

                                         DESCRIPTION OF MAPPED SOILS IN THE GREEN LAKE STUDY AREA (Concluded)
Soil Type
Talcot





Wadena



Webster


Description Depth (In)
Very poorly drained
nearly level soils
formed in fine out wash
of Lacustrine sediments
over sand and gravel on
outwash plains
Well drained loamy
soils underlain by
calcarous sand &
gravel
Deep, poorly drained
soils that formed In
loamy glacial till
0-23
23-30
30-60



0-13
13-20
30-60

0-17
17-31
31-67
Location Within the
Study Area
North of Nest and
Green Lakes; also
more widespread
north & west of
Nest Lake

Scattered in north-
eastern corner


Scattered north &
southeast of Green
Lake
Permeability
(in/hr)
0.6-20.0
0.6-20.0
6.3+



2.0-6.0
2.0-6.0
>20.0

0.6-2.0
0.6-2.0
0.6-2.0
Depth to
Seasonal
High Water Suitability for
Table (ft) On-Site Waste Disposal
0-3 Severe; high water
table & rapid




>6 Slight; >6%
moderate; 6-12%
severe; <12%

1-3 Severe; poorly
drained & high
water table
Soil Capability Class**
II w 0-10% slope





II s 0-2% slope

lie 2-6% slope

II w 0-2% slope


             high In lime
             carbonates
Source:   USDA-SCS Soil Series Report

-------
development.  Because  the  Kandiyohi County  soil survey by the  SCS  has
not yet  been completed, none of the land  in the Green Lake Study Area
has  as  yet been  designated  as  prime  or  unique  agricultural  land.
However,  preliminary  designation  of  prime  agricultural  land has been
made for  several soil  series within the  Study Area.   These designations
are listed in Table II-2.
4.   ATMOSPHERE

a.   Climate

     Both the Canadian Arctic  and the Gulf of Mexico affect the climate
of the Green  Lake  Study  Area.   The region  lies,  in  effect, in a funnel
for the cold  air of the  far north as  well  as warm Gulf air,  the  major
source of precipitation.   Consequently,  its climate  is characterized by
frequent precipitation and marked changes in temperature.

     There are normally 5 to 10 winter days with temperatures falling as
low as 20°  to 30°  below  0°F.   Although summer temperatures rarely reach
100°F, they sometimes exceed 90°.  The available climatological data for
Willmar and New London is summarized in Appendix B.

     More climatological  data  is available for St.  Cloud,  about 45 miles
northeast of  the Study  Area  (see Appendix  B).   There, average  annual
precipitation  (water  equivalent) is  26.8  inches,  approximately  60% of
which  occurs   during  the  growing season,  between  May and , September.
Snowfall  averages   43.1  inches  per  year.   Relative humidity  averages
approximately 82% in the  morning and 60% at noon.

     The average wind speed is  approximately 8 mph (National Oceanic and
Atmospheric Administration (NOAA)  1976).   Wind  is  generally  from the
south in the summer and from northwest in the winter.

     Damaging storms such as tornadoes and freezing rain are infrequent,
and  ice  storms occur less  than  once  a year on the  average.   The Study
Area lies slightly  north and  east of  the major  storm paths.  Neverthe-
less,  localized  damage from heavy  rains,  wind,  or  hail  from  thunder-
storms is experienced each year (NOAA 1976).

b.   Air  Quality

     The ambient air quality as measured in the City  of Willmar is good.
High-volume sampler readings for total suspended particulates show that
in  1976  neiUier the  primary  (260.00  ug/m   at 25°C)  nor  the secondary
(150.00 ug/m  at 25°C) 24-hour State ambient air quality standards were
exceeded  (Minnesota  Pollution  Control Agency  (MPCA)  1977).   No testing
is performed for other air pollutants in the Study Area.

     Kandiyohi  County  is  in  a Minnesota Prevention  of  Significant
Degradation (PSD) Class  2  zone.   Moderate degradation of air quality is
allowable, but a review is required for 19 major source categories (MPCA
1972).
                                  39

-------
c.   Odors

     There have been few complaints by residents of the Green Lake  Study
Area  about objectionable odors associated with on-site  septic  systems,
the  Spicer  wastewater   treatment  plant  or  the New  London  wastewater
treatment plant.

d.   Noise

     The  ambient noise  level* within  the Study  Area  is estimated  at
approximately  40 decibels* (Scale A) which  is considered typical of  a
quiet  outdoor  community (US Department of Transportation  1978).   High-
ways,  motorboats,   or   aircraft  flyovers  generate louder sounds, but
otherwise  no excessive  noise  sources have been identified in the  Study
Area.
B.   WATER RESOURCES

1.   WATER QUALITY MANAGEMENT

     Water resources management  is  a  complex of  many  elements,  in which
the Federal government, the State and  the locality  all have  an  interest.
To  name  just  a few of  these elements  --  irrigation, municipal water
supply, maintenance of navigable waters,  and protection  of  the  product-
ivity  of  the soil  --  illustrates  the broad range of activities under
this  heading.   Among  the  most important, however,  is preservation or
restoration of the quality of US  waters.   In  the  Federal  Water Pollution
Control Act  (P.L.  92-500,  1972)  and the  Clean Water Act  that amended it
in  1977  (P.L.  95-217),  Congress  outlined a  framework  for comprehensive
water  quality  management  which  applied  to  groundwater as well  as to
surface waters.

a.   Clean Water Act

     Water quality is  the responsibility  of the EPA in coordination with
the  appropriate State  agency,  in this  case the  Minnesota  Pollution
Control Agency  (MPCA).   However, with passage of  the Clean Water Act,
all Federal  agencies  were instructed  to safeguard water quality stan-
dards  in  carrying  out their  respective  missions.   As the  lead agency,
EPA  coordinates  the national  effort,  sets  standards,  and  reviews the
work of other agencies,  some  of  which are assigned responsibilities in
line with  their traditional missions.   For  example,  the Army Corps of
Engineers maintains its  jurisdiction  over dredging  permits in commer-
cially  navigable   waters  and  their adjacent  wetlands  and  in coastal
waters but  now  must also  consider  water quality.   The Coast Guard has
jurisdiction over  oil  spill  cleanup.   The Act officially draws certain
other  agency  activities  into  the  water  pollution control  effort:  for
example,   it  authorizes  Federal  cost-sharing  in agricultural  projects
designed to  improve water quality  by  controlling  farm runoff.  In the
case of SCS, these new responsibilities may be in addition to, or as the
case may be, may  dovetail  with SCS programs  to  reduce soil erosion, or
to construct headwaters impoundments for  flood control.
                                  40

-------
     In  delineating  the  responsibilities  of  the  various  levels  of
government  for  water  quality,  Congress  recognized the  rights  of  the
States with regard  to  their waters.   It authorized aid to the States in
funding the development  of plans for control  of pollution,  development
of State  water  quality  standards  (which may  be more  restrictive  than
Federal standards), and  research.  When a State meets  certain criteria,
it is  certified by  EPA as the entity responsible  for  administration of
the  activity  in question.   The  EPA  may deny  certification,  and  in  all
cases it retains power of enforcement of established standards,  State or
Federal.  The  State of  Minnesota  is one  of the  states  which  has  been
granted certification by EPA.

     Among the goals and deadlines set in the Clean Water Act are these:

     "it is the national goal that the discharge of pollutants into
     the navigable  waters  be eliminated by 1985... an interim goal
     of water quality  which provides for the protection and propa-
     gation  of   fish,  shellfish,  and  wildlife  and provides  for
     recreation in  and  on  the  water (is  to)  be  achieved  by July
     1, 1983".

     This  landmark  legislation  requires  that  publicly  owned treatment
works  discharging  effluent  to  surface  waters  must  at least  provide
secondary treatment,  i.e., biological oxidation of  organic  wastes.   It
directed  that municipalities  must  provide  the  "best available  tech-
nology" by  1983 and  that in appraising  their options  localities  must
address  both the  control   of^  all  major sources  of   stream pollution
(including  combined sewer overflows  and  agricultural,  street and other
surface runoff) and the  cost-effectiveness of various  control measures.
The  use  of  innovative  and  alternative  technologies  must  also  be
considered.

     The  key  provisions  in  water  quality  planning stipulate  that to
receive aid a State must provide a continuing planning process.   Part of
Section 208 requires  the states  to  inventory  all  the  sources of pollu-
tion  of surface and  groundwaters,  both  point*  and non-point*,  and to
establish priorities   for  the correction of  substantial water  quality
problems within a  given  area.  The 208 plans are intended to provide an
areawide and, taken together, a  statewide, framework for the more local
decisions on treatment facilities.

     The Section  303E  Basin Plan (Upper Portion Upper Mississippi River
Basin) that includes the Green Lake Study Area was completed  in December
1975 by MPCA.

     Section 201 of the Act  (under which the Green Lake area  application
for  funds was made) authorizes EPA  to  make  grants to  localities toward
the  improvement or  construction  of facilities for treatment  of existing
water  quality  problems.   EPA may  determine  whether   an environmental
impact  statement  is required  on a  proposed project (see Section I.B).
Where  the state  has been certified and assumes responsibility for water
quality,  EPA retains  authority  to  approve  or  reject  applications  for
construction grant  funds for treatment facilities.
                                  41

-------
     The local political jurisdiction has  traditionally  been  responsible
for  meeting  the  wastewater  treatment  needs  of  the community.  Local
jurisdictions now  have  the benefit  of Federal and State assistance  in
meeting water quality standards and goals.

b.   Federal  Agency   Responsibilities  for  Study  Area Waters

     The following  Federal agencies are responsible for insuring water
quality in the Study Area:

     o    EPA:

          Administers the Clean Water Act;
          S'ets Federal water quality standards;

     o    EPA Region V:

          Administers the  grant  program  described  above  in  Illinois,
          Indiana, Michigan,  Minnesota, Ohio  and  Wisconsin;

          Provides  partial funding  for preparation of  the  Green Lake
          Facilities Plan.   Region V's responsibilities  in the  construc-
          tion  grant program  in  general  and  specifically  toward the
          application  made in the  Facilities  Plan are  discussed   in
          Section I.B;

     o    US Army Corps of Engineers:

          Controls dredging and  construction activities  in commercially
          navigable  streams,   their  100-year  floodplains  and  adjacent
          wetlands through a permit system;

     o    US Department of Agriculture:

          Under the  Rural  Clean  Water Program  will provide cost sharing
          for  soil  conservation  practices  designed to  improve water
          quality.   (The  program will  probably  be assigned  to SCS;  it
          has not been funded by Congress  at  this time,  however);

     •    Soil Conservation Service (SCS):

          Agency's mission is to control wind and water  erosion,  to sus-
          tain  the  soil  resource  base and to reduce deposition of soil
          and related pollutants into the  water system;

          Conducts  soil  surveys.    Established  guidelines   for  inven-
          torying prime or unique agricultural  lands;

          Works with  farmers and  other land  users on erosion  and  sedi-
          mentation problems;

          Gathers information  at  the county  level as part of program  of
          study  and  research  to  determine new  methods of  eliminating
          pollution from agricultural sources;
                                  42

-------
     •    Fish and Wildlife  Services:

          Provides technical  assistance  in  development  of  208  plans.

c.    State  Responsibilities  in   the  Green  Lake   Study  Area

     The  following entities  have  responsibilities  for water  quality
management in Minnesota:

     a    Minnesota Pollution  Control Agency  (MPCA):

          Implements  water pollution control laws and establishes regu-
          lations.  This agency has authority to  issue  permits  to dis-
          charge  pollutants  into  surface  waters under  the  National
          Pollutant Discharge  Elimination  System (NPDES)  and  to  set
          discharge levels.   MPCA  also establishes  criteria  and  stan-
          dards applicable  to interstate  and  intrastate  waters.   The
          standards are being revised and are in  draft  form as  of May,
          1979.  A water quality Management  Basin Plan  was  prepared by
          MPCA  in  December  1975   (MPCA 1975).    Although  a  complete
          regional plan,  this document has little site specific data on
          the Study Area;

     e    Minnesota Department of Natural Resources (DNR):

          Identifies,   categorizes  and maintains  existing  natural  re-
          sources, including  surface water  bodies.  DNR reviews  county
          actions   and  submits recommendations  on industrial  and  agri-
          cultural permits;

     •    Department  of Health:

          Reviews   plans  on  public water  and  sewer  improvements  and
          regulates on-site  sewage  disposal systems.

d.    Local   Responsibilities   for  Water   Quality  Management

     •    Kandiyohi County:

          Administers   the  Shoreland  Management  Ordinance  which  estab-
          lished  criteria   for  land use  "along   the  shores  of  lakes,
          streams  and  rivers,  and in natural  environment areas".

2.   GROUNDWATER HYDROLOGY

     The buried outwash  aquifer  found in  the  undifferentiated  glacial
drift (see Figure  II-6) constitutes the major groundwater aquifer in the
Study  Area.    The  aquifer  of sand  and  gravel   is  under  confined  or
artesian* conditions.  The  underlying  igneous and metamorphic rocks do
not constitute significant  groundwater aquifers  (Lindholm et al.  1974).

     The outwash aquifer  is  on the  order of 50 feet in thickness with an
upper surface elevation of  approximately 1150 feet above msl (see Figure
II-6).  Depth  to  the  top  of the aquifer ranges from about 20 feet to 70
                                  43

-------
                            LEGEND
SAND AND GRAVEL, SURFLC1AL;
    UNCON FINED
SAND AND GRAVEL, BURIED;
    CONFINED
DIRECTION OF GROUNDWATER
    MOVEMENT
POTENTTOMETRIC SURFACE  OF
    AOU1FER
            i-
,TOP OF BURIED OUTWASH ZONE
 WELL
         .'.';!•'»•'I UN DIFFERENTIATED  DRIFT
                UNDIFFERENTIATED  IGNEOUS AND
                    METAMORPHIC ROCKS
                CROW  RIVER  WATERSHED
                    BOUNDARY
              A
           1300'-
Direction of Groundwoter
           Movement
                    Source:  Lindholm et.al. 1974
 FIGURE II-6    HYDROGEOLOGY OF THE GREEN  LAKE  STUDY AREA
                        44

-------
feet within the  Study  Area.   The potentiometric or pressure  surface  of
the water  within the  outwash  aquifer as  seen in the  cross-section  of
Figure  II-6  tends  to  slope  southwards  through  the  Study Area.   This
southward  slope  indicates the  direction of  flow through the  aquifer.

     Precipitation within the Study  Area averages 27.6 inches annually.
Of  this  amount,  24.2  inches  is lost  to the  atmosphere  through evapo-
transpiration and 3.3 inches  are accounted for by runoff.   The remaining
0.1 inch percolates downward  to  become groundwater mainly  in  the shallow
glacial  moraines.   Discharge from  these  shallow moraines takes  place
principally in  the North, South,  and Middle  Forks  of the Crow River.
Indications are that very little of the groundwater recharge  reaches the
buried outwash aquifer found  in  the Study Area.

     The specific  capacities of wells in the  outwash  aquifer may  be  as
high  as  50  gallons per  minute per  foot  of drawdown.   With available
drawdown ranging  from 10 to  80 feet, well yields of  several thousand
gallons per minute  may be obtained.   Lower well yields are found within
the southern portion of the  Study Area due to the potentiometric surface
of the aquifer sloping downward  in that direction.

3.   GROUNDWATER QUALITY

     Groundwater in  the  buried  outwash aquifer of the  Study  Area  is  of
the calcium magnesium bicarbonate type found throughout most  of the Crow
River watershed.

     Total hardness* of  water  in the Study Area is approximately 300  to
350 mg/1.   This  is  very high  when  compared  to  a  normal of  about 100
mg/1.   The dissolved  solids*  content within the Study Area can range  up
to  400 mg/1,  an  amount considered moderate to high when compared to the
recommended State  limit  of 500 mg/1.  The iron  content,  with a median
value of 0.59 mg/1 generally  exceeds the  US Public Health  Service drink-
ing water  standard of  0.3 mg/1 (Lindholm et  al.  1974).   However,  this
high  iron  content  occurs naturally and  is not the  result of pollution.

     The results  of a  survey  of  97  wells surrounding Green Lake  near
Spicer  sponsored  by  the Green  Lake Property  Owners Association  and
undertaken  by Noyes  Engineering  Service  in -July  1977,   are  shown  in
Appendix C-l.   Parameters tested  were orthophosphate,  total  coliforms,
and nitrates reported as nitrate nitrogen (NO_-N).

     Nitrate  nitrogen  was observed  in 28 of  the 97  wells  tested.   Of
these, only two exceeded the  10  mg/1 permissible limit with levels of 12
mg/1 and 48 mg/1.  Twenty-eight wells were positive for total coliforms,
and nineteen showed the presence of orthophosphates.

     Of  the  total  sample of  wells,  seven  were positive  for all  three
parameters, five  for both nitrates  and  coliforms, five  for  both  coli-
forms  and  orthophosphates,  and two for  both nitrates  and  orthophos-
phates.  The data indicate that a number  of wells have been contaminated
but are  insufficient  to  implicate human wastes  as the source.  Infor-
mation on  specific well  construction and maintenance would be necessary
to  implicate  human waste as  the source  of  pollution.   This  information
was not reported with the water sample analysis.

                                  45

-------
     The outwash aquifer is confined by an impermeable upper layer which
would indicate  that  contamination has been entering  the  specific wells
directly as a result of poor well construction,  rather than entering the
aquifer by  downward  infiltration and percolation through  the  soil.   An
improperly constructed well permits surface runoff to percolate directly
into  the groundwater  through  annular  space.*   The irregular,  spotty
nature of the contamination among the tested wells is also supportive of
this view.

4.   GROUNDWATER USE

     Groundwater  sources  provided nearly all of  the  potable  water from
the  Study  Area.   Total  water  use  in  the Crow River  Basin in  1969
exceeded  8  billion  gallons  (22  million  gallons per  day (mgd))  with
municipal  and  rural  domestic  water use  accounting for  approximately
one-half  (Lindholm et al.  1974).

     The  communities of New London and Spicer each have two wells which
serve as  the sources  of  municipal water supply.  In  1973,  the average
daily  consumption was  87,000  and  143,000  gallons  per  day   (gpd)  for
Spicer  and  New London, respectively (RCM, December  16,   1974).   It  is
estimated that by the year 2000, average water use within the Study Area
will be  0.59  mgd.  Lindholm et al. (1974) has indicated that the buried
outwash  aquifer  within  the  Study  Area  will  generally  yield adequate
water   quantities  for   municipal,   industrial,   rural   domestic  and
irrigation uses.

5.   SURFACE WATER HYDROLOGY

     Green  Lake,  Nest Lake,  and the Middle Fork of  the  Crow River are
major  surface  water  resources  located  in  the  Study Area  (see  Figure
II-7).   Woodcock Lake  is one  of  many small lakes  in the Study Area,
located west of Green Lake.  It is included as part of the surface water
resources  study in this  EIS because it  receives the  effluent from the
Spicer  STP.   Woodcock  Lake is  said  to occasionally  overflow  into Green
Lake  (EPA 1974).   The  Middle Fork of the Crow River originates south of
Belgrade,  Minnesota  and   receives  the  surface   water  drainage  of  the
entire  Study  Area.  As  it meanders  southward  past New  London and the
nearby  New  London sewage treatment plant,  the  river enters  Nest Lake
from  the  north  which,  in turn,  overflows  into  the  eastern end of Green
Lake.   The  River eventually leaves the Study Area  to the east, passing
through  the wetlands  of  the Dietrich State  Wildlife Management Areas.

     Physical characteristics pertaining to the hydrology of the surface
waters  serve  to describe  and differentiate the lakes and streams in the
Study Area.   Specific  hydrologic and morphologic characteristics of the
lake  or stream  not only  form the surface water system in which chemical
and  other factors operate and  interact but are themselves major factors
in  that  interaction.   Size of  drainage basin,  tributary  flow,  lake
volume,  hydraulic retention  time and precipitation  directly influence
the   quantity   and  quality  of surface  water   resources.   Table  II-3
presents  the physical characteristics  of the lakes.   Additional dis-
cussions  on these parameters follow in the next few paragraphs.
                                  46

-------
                                                            FIGURE  II-7
SURFACE WATER HYDROLOGY OF THE GREEN

       LAKE STUDY  AREA




       LEGEND
                                                                          •>-^ WETLANDS


                                                                         	*- DIRECTIO'I OF'FLOW


                                                                         cfs - CtiUU;  FEET  PER SECOND


                                                                             • GAGING  STATION


                                                                            — DAM
-c-
-j
                                                                                             ^.   MANAGEMENT AREA ,.
     Source:   USCS

     19f7,  dnte  un-

     known

-------
                                Table II-3

              PHYSICAL CHARACTERISTICS OF GREEN LAKE, NEST LAKE,
                  AND WOODCOCK LAKE (EPA NES SURVEYS, 1974)
Parameter                              Green Lake   Nest Lake   Woodcock Lake

Drainage Basin Area (Square miles)       129.6       121.7           1.07

Lake Surface Area (Acres)                5,406         945            125

Lake Mean Depth (Feet)                      21          15           2.5

Maximum Depth (Feet)                       110          40              8

Inflow (cfs)*                             42.4        37.6

Outflow (cfs)*                            42.4        37.6

Lake Volume (Acre/Feet)                113,526      14,175            312

Mean Hydraulic Retention Time (Years)      3.7         0.5


*  Average flow from October 1972 to October 1973.
                                      48

-------
a.   Size  of Drainage Basins

     The drainage  basin sizes of  Green  Lake, Nest  Lake,  and Woodcock
Lake are 129.6,  121.7,  and  1.07  square miles respectively.  The larger
watersheds   act  as  significant  catchments  of  precipitation  which is
transferred as  runoff  to the  lakes.   Woodcock Lake  occupies  a larger
portion of  its  total watershed  (drainage  basin)  than do Green Lake and
Nest Lake.   That is, Green  Lake's drainage basin-to-lake surface  area
ratio is 15:1,  Nest  Lake's  is 82:1,  while that of Woodcock Lake is  5:1.

b.   Tributary Flow

     The Middle  Fork of the  Crow  River  is  the  major tributary in the
Study Area.  The U.S.  Geologic Survey (USGS)  has maintained a continuous
recording  stream  flow  gauge  on  the Middle  Fork  of the  Crow  River
approximately 2  miles east  of Green  Lake  (see Figure  II-7) since 1949.

     For a  period  of 28 years from 1949-1977, the average  flow was  50.6
cubic feet  per  second  (cfs),  or  1.43 cms.  The maximum flow during  this
period was  408  cfs  (11.5 cms).  Mean annual runoff is estimated to be
3.84 inches/year (USGS  1977);  this is a low rate which can be accounted
for  by  high evaporation and  transpiration loss  from  many lakes,   pot-
holes,  and partially drained marshes  in the region (Rieke Carroll Muller
Associates, Inc. 1976).

     Twelve measurements of  stream  flow were made during National Eutro-
phication Surveys  (NES)  from  October  1972 to October  1973  at the outlet
of Green Lake,  in  the  channel connecting  Green Lake and Nest Lake, and
approximately 1  mile above  Nest  Lake (see Figure II-7).   Mean flows at
the  upstream  station and Green  Lake outlet  of  the Middle Fork of the
Crow River  were  determined  to be 37.6 cfs  (1.0 cms)  and 42.4 cfs (1.20
cms), respectively  during the study period.

     Municipal  wastewater   discharges  from  the  Belgrade  and  the  New
London treatment plants supplement the flow of  the Middle Fork of the
Crow River.   In 1972,  the  National Eutrophication Survey  estimated the
combined wastewater discharge from these  plants to  be  0.26 mgd, or  0.40
cfs.  This,  however,  represents only  0.7% of the average discharge of
the  Middle  Fork of  the Crow River.    During periods  of low flow,  this
proportion would substantially increase.

c.   Lake  Hydraulic Retention  Time

     Assuming complete  mixing, the retention time of  a lake is the  time
required for  natural processes  to  replace  the  entire volume  of  its
water.   Nest  Lake  has  a  relatively  short  retention  time  of 0.5 years
(NES 1974),  while  Green Lake has  a  longer retention time of 3.7 years
(NES 1975).   Since inflow  and  outflow measurements were  not  taken in
Woodcock Lake, EPA  did  not  estimate a hydraulic retention time.

d.   Precipitation

     The average precipitation in the  Study Area during  1972-1973 was
reported to be  28.1  inches  (71.4 cm) by  EPA's NES  study.  The value is

                                  49

-------
slightly higher than the annual  average  over  the recorded period (24.5
inches or 62.2 cm).

e.   Hydraulic Budget

     A  generalized  hydraulic  budget for  a  lake includes the hydraulic
inputs  such  as  tributary  inflow,  precipitation and groundwater and the
outputs  such  as  tributary outflow,  evaporation,  and groundwater.  The
hydraulic budgets of  Nest Lake,  Green Lake and Woodcock Lake are sum-
marized  in  Table II-4.   Evaporation was determined  by  the difference
between  the  total  input and  total output for  each lake.   Most of the
information presented  is  derived  from EPA's  NES studies (1974,  1975).

6.   SURFACE WATER USE AND CLASSIFICATION

     Surface  waters  in  the  Study  Area  are  popular for  many aquatic
activities,   including   swimming  and  fishing.   They  are also  used  to
assimilate wastewater effluent.  These waters  are  not used  for domestic
water supply.

     The  State  of  Minnesota  has  classified uses of its surface  waters
and  assigned  appropriate  classification  to each body of water.  Water
quality  standards for  the classifications and uses appear in Appendix
C-2.  For a  lake or stream classified under two or  more uses, the more
restrictive standards  apply.

     The Middle Fork of the Crow River has been classified 2B, Fisheries
and  Recreation,  to  permit the  propagation  and  maintenance of  cool  or
warm  water   sport  or  commercial  fishes and  be  suitable  for aquatic
recreation of all kinds,  including bathing, for which the waters  may be
usable  (MPCA, Water  Pollution Code (WPC)  14, 1973).

7.   SURFACE WATER QUALITY

     This section presents the water  quality conditions of Nest Lake,
Green Lake,  and Woodcock  Lake in the following order:  nutrient budget,
open water quality, phosphorus  loading-trophic  condition relationships,
and shoreline conditions.   The discussion is intended to  put the surface
water quality into  perspective  by independently presenting  the nutrient
budget  and lake water  quality, and connecting  these two aspects by using
the   simplified  phosphorus   loading-trophic   condition  relationships.
Finally,  the  shoreline problems  in  terms of bacteria contamination is
discussed.   Most  of   the  information   presented  is  synthesized from
studies  conducted by the  EPA National Eutrophication Survey in 1972 and
1973  and by  the Minnesota Pollution Control  Agency in  1976,  1977, and
1978.

a.   Nutrient  Budget

     Nutrient budgets  for  Nest  Lake,  Green  Lake, and Woodcock Lake are
shown in Table  II-5 in terms of phosphorus  and nitrogen  using data from
the  EPA 1972-1973  surveys.  As indicated, the  combination  of tributary
inflow  and wastewater  treatment  plant discharges contributes a signifi-
cant  amount  of nutrients  into  Nest Lake and  Green  Lake.   In  contrast,
                                  50

-------
                                Table II-4

        WATER BUDGETS FOR NEST LAKE, GREEN LAKE, AND WOODCOCK LAKE
              (1972-73) IN 106 M3/YR — FROM EPA NES (1974)
                                   Nest Lake
    Inputs

    Middle Fork Crow River
    Immediate Drainage
    Precipitation
                        Total
45.2
 2.2
 2.8
50.2
    Outputs

    Outlet                           48.2
    Evaporation (by difference)        2.0
                        Total        50.2
                                   Green Lake
1.  Inputs
    Outlet from Nest Lake
    Immediate Drainage
    Precipitation
                        Total
48.2
 4.4
15.6
68.2
2.   Outputs

    Outlet to Middle Fork
      Crow River
    Evaporation (by difference)
                        Total
55.2
13.0
68.2
    Inputs

    Immediate Drainage
    Precipitation
    Spicer Treatment Plant
                        Total
                                   Woodcock Lake
0.27
0.38
0.14
0.79
    Outputs

    Evaporation
    Overflow into Green Lake
                        Total
0.38
0.41
0.79
                                     51

-------
                                Table II-5
      PHOSPHORUS AND NITROGEN BUDGETS FOR NEST LAKE, GREEN LAKE AND
          WOODCOCK LAKE (1972-73) IN KG/YR - FROM EPA NES (1974)  '
1.  Inputs
    Middle Fork Crow River
    Precipitation
    Immediate Drainage
    Septic tanks
2.  Outputs

    Outlet to Green Lake

3.  Retention
                             Total
                    Nest Lake

             Phosphorus    Nitrogen
              4,197.8
                 73.0
                 59.1
                 40.0
              4,369.9
              1,912.7

              2,457,2
           82,930.2
            4,744.2
            1,122.7
            1.589.0
           90,386.1'
           69,956.0

           20,430.1
1.  Inputs
    Outlet from Nest Lake
    Precipitation
    Immediate Drainage
    Septic Tanks
2.  Outputs

    Outlet

3.  Retention


1.  Inputs

    Tributary Inflow
    Precipitation
    Immediate Drainage
    Septic Tanks
    Point Sources


2.  Outputs

3.  Retention
                             Total
Total
                     Green Lake

             Phosphorus    Nitrogen
              1,912.7
                437.9
                 59.1
                195.4
              2,605.1
           .69,956.0
           27,151.1
            1,109.1
            7,336.4
          105,552.6
                975.2      46,834.1

              1,629.9      58,718.5

                  Woodcock Lake
             Phosphorus    Nitrogen
                  3.1
                 36.3
                  1.4
                523.4
564.2
  508.0
  526.8
   66.7
4,005.6
5,107.2
                                     52

-------
the septic tank systems  only  contribute  a  small portion of the nutrient
into these  two  lakes.   Because of  the  limited  data base available for
Woodcock Lake, the  nutrient budget  derived and  presented is considered
to  be  the  best  estimation with  available  data  and  standard  loading
methodologies used by the EPA.   See  Appendix  C-10 for an illustration of
the phosphorus loads,  by major nutrient source,  into  Nest Lake,  Green
Lake,  and Woodcock Lake,  in  terms  of percentage.

     The results  in Table II-5  indicate  over  50% retention of phosphorus
for both Nest Lake  and  Green  Lake.   As  to nitrogen, the retention per-
centage differs  considerably  between the  two  Lakes.   Woodcock Lake is
expected to  retain most of the nutrients  entering  the  Lake  due to its
landlocked nature.

b.   Lake  Water  Quality

     Data  collected  by  EPA and MPCA have  been  analyzed for Nest Lake,
Green Lake,  and  Woodcock Lake.   The four key water quality parameters
(total phosphorus,  chlorophyll  Ł,  secchi  depth,  and hypolimnetic dis-
solved oxygen saturation level)  are  plotted over the period from 1972 to
1978 and presented  in Appendix  C-3.  These graphs are used to assist us
in understanding  the open water conditions  of the lakes.

     The results  of the  analysis  suggest  no definite  trend  as to the
water  quality  of these  lakes  during the  last  7  years.  That  is,  the
variation  of water  quality  over  this   period  is  no more  than annual
fluctuations, inherent  with  the  system.   The  water quality! conditions
seem  to  have  remained   relatively  steady  during the  last  few years.
According  to the  simple trophic  classification system, Nest  Lake and
Woodcock Lake are eutrophic  and Green Lake  is mesotrophic.

     For a general  description  of lake  water quality, see Appendix C-4.

c.   Phosphorus  Loading-Trophic Condition Relationships

     This  section  examines   relationships  between  phosphorus  inputs
(Section II.B.7.a)  and  the  resulting water  quality (Section II.B.7.b).
Such  relationships  are  needed  to  predict trophic  responses which would
result from  phosphorus  loading  scenarios associated with various waste-
water management  alternatives.   A  detailed  description of the procedures
required to  examine these relationships  using  Dillon's  model (1975) is
presented in Appendix C-5.  Only the salient  features of the results are
included in  this  discussion.   Figure II-8 shows the trophic conditions
for Nest Lake and  Green Lake  based on the 1972-1973 data by EPA.  Con-
current  with  the  results   in the previous  section,   Dillon's  model
describes Nest Lake as eutrophic and Green  Lake mesotrophic.

d.   Bacterial  Contamination  in Shoreline Areas

     Investigations of fecal and total coliforms were made in Green Lake
by  Southwest  State  University   (1972-1973,   1975-1977),  ;Green  Lake
Property  Owners  Association (1970-1971),  and MPCA  (1968-1969).  Along
the nearshore  areas of  the  Lake  bacterial  levels were generally below
the Minnesota  State Health Department  and MPCA standards for  swimming
                                  53

-------
0.01
1.0
               10.0
       MEAN DEPTH (METERS)

L= AREAL PHOSPHORUS INPUT (g/m2/yr)
R= PHOSPHORUS RETENTION COEFFICIENT
PS HYDRAULIC FLUSHING RATE (yf1)
                                                         100.0
    FIGURE H-8   TROPHIC CONDITIONS OF NEST LAKE AND GREEN
                         LAKE (1972-1973)

-------
areas.   Values  in  excess of  the  standards  were commonly  found  in the
Green Lake  inlets  and  outlets,  particularly  at  the Old  Mill  Outlet.

8.   FLOOD  PRONE  AREAS

     The Green Lake Study Area  includes areas designated as flood hazard
zones by the US Department  of  Housing and Urban Development (HUD) Flood
Insurance Program.  The  zones  delineate regions that have a 1% chance of
flooding in any given year.  These flood hazard zones include Nest Lake,
Jessie  Lake, Lake Calhoun, the  Middle Fork of the Crow River and land on
either  side of  it, and  a large area of land located west of the City of
New  London.   The   flood  hazard zones  are delineated  in  Figure  II-9.
C.   EXISTING SYSTEMS

     There are two existing  wastewater treatment plants within the Green
Lake  Study  Area.   One plant  serves  the city  of  Spicer and  the other
serves New London.  These two  are discussed in detail in the Facilities
Plan  for  the  Green Lake vicinity.   The rest of the  development  in the
Study Area is  served by on-site systems.

     When the  Facilities Plan was  drafted, information  about  on-site
systems was very  limited.   It  was  assumed,  however, that  many  of the
on-site  system  did not  comply with  the  newly  drafted  standards  for
septic tanks which are detailed in the Kandiyohi County Zoning Ordinance
(County Planning Commission 1972).   This Ordinance is further discussed
in this Section.

     Septic tanks  were suspected  of contributing  to public health and
water  quality  problems  although there  was little evidence  to  support
this suspicion.   Three studies  were recently undertaken by EPA to deter-
mine the  extent and distribution of problems with on-site systems.  The
results of  these  studies,  discussed in  this  section, are  intended  to
identify potential water quality or public health problems.  This iden-
tified  information will  be  used  to determine  grant  eligibility  for
collector sewers  and to provide a basis  for predicting the design, costs
and impacts of continued  use of on-site  systems.

1.   SUMMARY OF  EXISTING DATA

     Three studies were undertaken by EPA to evaluate existing lakeshore
systems and problems resulting  from these systems:

a.   "Investigation of  Septic  Leachate  Discharges into Green
     Lake,  Minnesota"  (Kerfoot,  1978).

     A through-the-ice  septic  leachate  survey was  conducted along the
shorelines of  Green Lake and  Nest Lake in Kandiyohi County, Minnesota
during March,  1979.   This  study was  undertaken  to determine  whether
groundwater plumes  from nearby septic  tanks  were  emerging along the
lakeshore  causing  elevated  concentrations  of  nutrients.   Septic tank
leachate  plumes  were  detected  with an  instrument  referred  to  as  a
"Septic Snooper."   The instrument is equipped  with analyzers to detect
                                  55

-------
                                                            FIGURE  11-9    FLOOD HAZARD AREAS OF THE GREEN
                                                                                  LAKE STUDY  AREA
                                                                                     LEGEND

                                                                                 FLOOD  HAZARD AREAS
                                                                                            | WETMICH LANCE ST.ATE
                                                                                            WIDLIFE MANAGEMENT AdEA .
                                             GREEN   LAKE
Source;   HUD
    1977

-------
both organic and inorganic chemicals  from  domestic wastewaters.  Surface
and groundwater sampling  for nutrient  and bacteria  (surface water only)
were coordinated  with the septic  leacliate profile  to clearly identify
the source of the leachate.

     The  following  observations  were obtained  from the shoreline pro-
files,  analyses of groundwater  and  surface water samples, and evaluation
of groundwater flow rates and patterns:

     •    A  total  of 64  locations  exhibited  effluent plume character-
          istics.   Of these,  26 originated from  surface water discharges
          and  38  from  groundwater  leachate.   The  locations-  of  these
          effluent plumes is  shown  in Figure 11-10.

     •    The  most  pronounced  source  of  leachate  was  inflow  from  the
          Middle  Fork of  the  Crow  River  into  Nest  Lake.   The  daily
          winter  loading  of  phosphorus  was estimated  at  8.6  kg/day
          compared  to  total  loading from all groundwater plumes around
          the lake of .15 kg/day.

     •    A  noticeable  undocumented  source of  phosphorus  loading  was
          observed  originating  from the discharge stream of an unnamed
          lake near the sewered town of Spicer.

     •    The  observed pattern  of  plumes  on Green  Lake correlated with
          projected groundwater inflow for the surficial deposits.  Most
          plumes  were  found  on the  north and  west shorelines with  few
          observed for the south and east  segments.

     The detailed results of  this  "Septic  Snooper" study is presented in
Appendix C-6.

b.   "EPIC Survey"  (EPA,  1978)

     An aerial  photographic  survey  was  conducted by EPA's Environmental
Photographic  Interpretation  Center  in order to  detect any surface mal-
functions  within  the Study  Area.   The survey  was  made on August 20,
1978.   Results of  the  survey,  shown  in Figure 11-11  indicated that
surface malfunctions were not widespread.   Only  three  marginally failing
systems  were  found  along the  Green Lake  shoreline  and  two  of these
failures were located on the  north shore.   One currently failing and  one
marginally  failing  system were detected  along  the  north shore of Nest
Lake.   A  system that gave an indication  of previously failing or exhi-
bited potential for failing  was  considered a marginally failing system.

     A  brief  description of  EPIC's Green Lake septic  system  analysis is
included  in Appendix C-7.

c.   Green  Lake  Construction  Grants  Sanitary  Survey (1978)

     An on-site  sanitary survey  of the Green Lake Proposed Service Area
was  conducted from November 6  through November 26,  1978.  This  survey
consisted of  a sample 74  (12%)  of the residences around  Green Lake which
participated  survey.  This sample is sufficiently large  to  enable  one to
                                  57

-------
                                                        FIGURE 11-10   LOCATION OF SEPTIC LEACHATE PLUMES AROUND

                                                                        GREEN  LAKE AND  NEST  LAKE
                                                                                       LEGEND


                                                                             	• GROUNDWATER PLUME



                                                                             	• STREAM SOURCE PLUME



                                                                            | 24 | SEGMENTS
                                                                                                                          oo
                                                                                                                          i/V
Source: Kerfoot

         1978
                               ^O-V-ys^^_i

                               's^^~"l_

-------
                                                 FIGURE II- 11   RESULTS OF AERIAL OBSERVATION OF SEPTIC TANK SYSTEM
                                                                          MALFUNCTIONS,  EPIC 1978
                                                                               LEGEND

                                                                         FAILING SEPTIC TANK SYSTEMS

                                                                         MARGINALLY FAILING SEPTIC TANK SYSTEMS
Source:  EPIC 1978

-------
make  some  conclusions about  the  suitability of on-lot systems  as  per-
ceived by  the  general public.   It is to be noted that those interviewed
during the survey were  year-round  residents;  their  septic  tank drain-
fields had not been  allowed  to "rest" during the off-season,  as  would
likely be the case with drainfields owned by seasonal residents.

     The purpose  of  this study was to identify the extent of violations
of the sanitary  code and the extent, nature,  and  distribution  of prob-
lems  resulting from  on-site  systems.   The study showed  that  despite
widespread violations  of standards  for ST/SAS  (septic tank-soil absorp-
tion systems) very few systems experienced recurring backups or  ponding.
The condition of the systems surveyed between November 6 and November 29
is described in Figure 11-12.

2.   TYPES OF SYSTEMS

     The data  gathered  during  the  Sanitary Survey  indicated that  most
on-lot systems within the EIS Proposed Service Area included one or two
septic tanks accompanied by a single or double  leachfield* (40%) or by a
trench*  (33%)  (1978).   In some instances, however, it was apparent that
the residents  were  not quite sure of the type  of system.   Data  in Table
II-6  shows  the types of on-site systems along the Green Lake shoreline.
Both  leachfields* and trenches* provide final  treatment and disposal of
septic  tank effluent.   A  leachfield  requires  less  lawn  area than  a
trench  but  has   much less  sidewall  area available  for  treatment  of
sewage.

     Data  gathered  during the Sanitary Survey indicate that the use of
alternative  systems  such as holding tanks, mounds and outhouses are not
widespread  throughout   the  Service  Area.  Some  residents  have  made
efforts  to overcome  severe  site  limitations  by  installing mounds,  but
this  type  of system numbers few.   The county has recommended conversion
to  cluster  systems,  or  multi-family  filter  fields  in  some  instances
where  site  limitations  are  severe  but  in each  instance some  of  the
residents  were too  reluctant  to  accept  this  type of  system  (by tele-
phone,  Steve  Peterson,   Kandiyohi  County  Tax  Assessment Office,  May
1979).

3.   COMPLIANCE WITH  SANITARY CODES
     Enforcement  of the  Kandiyohi  County  Zoning Ordinance,  passed  in
1972,  began in  1973.   Prior to  that  time no  standards  were enforced.
Under  Subtitle  1-408,  regulating the construction, repair and upgrading
of  individual  sewage  disposal  systems  (see  Appendix C-8),  newly  con-
structed ST/SAS should meet the following standards:

     •    The  system should consist  of a watertight septic  tank  and a
          soil  absorption  system.   Any  alternative  methods  of  sewage
          disposal  are  subject  to rules and regulations  of  the  MPCA  (6
          MCAR; 4.8040).
                                  60

-------
       FIGURE  11-12
                                                                        RESULTS OF 1978 EPA CONSTRUCTION GRANT  SURVEY
                                   LEGEND


                                 NO PROBLEM APPARENT

                            OlJtf) PROBLEM,  REPAIRABLE


                                 PROBLEM,  WITH SITE LIMITATION
                                                                               20
                                                                          (2) V    0(0)
                                                                        0(0) /X  A(0)
                                                                        A(2) 21
GREEN  LAKE
                                               •B.OLIFE MANAGEMENT AREA,
  •(9)
  0(0)
  A(0)
     0    20CO   400O

Source:  Mark Hummel

         November

         1978

-------
                                                                 Table  II-6

                                         TYPES OF ON-S1TE SYSTEMS FOUND ALONG GREEN LAKE SHORELINE
                                                        (BASED ON SANITARY  SURVEY)*
Shoreline
Area
North Shore
West Shore
South Shore
East Shore
Total Shore
Number
Survey
Segments (%)
12-17 33
(13Z)
9, 10, 11 11
(20Z)
22, 23, 24 20
<11Z)
18-21 10
(5Z)
74
(12Z)
Septic Tank
+
Leachfield
19
2
2
2
25
Septic Tank
+
Trench
7
6
3
5
21
Septic Tank ,
Leach Tank,
Leachfield
3
1
2
0
6
Septic Tank ,
Leach Tank,
Trench Outhouse
1 1
0 0
2 1
1 0
4 2
Septic
Tank
Only
0
0
1
1
2
Holding
Tank
1
0
0
0
1
Don't
Knov
1
2
9
1
CM
VD
11
Source:  Green Lake Construction Grants Sanitary Survey.  H. Hummell, 1978.
 *   In  some  instances,  the type of system was based on the resident's best guess.

-------
     •    The set-back distance  from  a  domestic water supply or general
          development lakes must be a  minimum of 50 feet.

     •    Distance between  the  soil  absorption system and the  depth to
          groundwater or bedrock shall be a minimum of 4 feet.

     •    The size  of the  septic  tank and  the soil  absorption  system
          must meet the criteria outlined in Appendix C-7.

     The  County  has   indicated  that  enforcement  of  the  Ordinance  is
generally more  stringent  for  sites located along the  lakeshore  than in
other parts  of  the  county where lots are  generally  larger.   However, a
percolation  test  is  not  required prior to septic  tank system  installa-
tion  in  any part of  the  Study  Area  (by telephone,  Steve  Peterson,  Tax
Assessment  Office,  May 1979).   Many  of the  on-site system located on
unsuitable  sites  serve  seasonal  residences.   Several  residents  are
interested  in converting  from seasonal  to permanent status but hesitate
to upgrade  or  replace their  on-site  systems with a  more  suitable one,
until the issues raised in this  EIS are resolved.

     Many  existing  systems  do  not  comply  with  the Kandiyohi  County
Ordinance  because  the development  and  enforcement  of  standards  for
on-site  systems is  recent and  because  there  are  limitations on  the
enforcement  of  the  standards relating to  site limitations.   The data
gathered during the  sanitary  survey  provides the best indication of the
types of violations  of the standards  and  the  location of  non-complying
systems.  Table II-7 summarizes available information  on  violations of
standards for on-site systems.  Major violations include:

     Well Setback Distance.  A setback distance of 50 feet  from the well
is intended to provide an adequate setback distance so that bacteria and
nutrients are sufficiently  removed (or  diluted in the case of nitrates)
as  the  wastewater  percolates  through  the  soils  matrix.   Table  II-7
indicates that  21%  of the sites surveyed violated the standard for well
setback  distance.   Most   (50%)  of  the violations  were found  along  the
east shore, although a significant number of sites along the north (32%)
and  south  (26%) shores were  also  in violation  of  the setback distance
standard.

     Lake Setback Distance.   Only  the north  shore  of Green Lake  had a
significant number of soil absorption units which were located too close
to the Lake (30%).   Generally,  homes  along  Green  Lake and their accom-
panying  ST/SAS  are  setback  a  good  distance  from the shoreline.   The
setback distance of 50 feet from the lake is intended to minimize leach-
ing of nutrients from on-site systems  into surface waters.

     Undersized Septic Tanks.   Septic tanks  which  are too  small for the
number of  residents using  them can  lead  to  several problems  including
backups into the house and poor solids removal in the septic tank.  Poor
solids removal may lead to clogging of the soil absorption  unit.

     Records on the  size  of the septic  tanks  were  not maintained prior
to enforcement  of  the ordinance; the size of  the  septic  tank in 53% of
the  homes  surveyed  could  not  be identified.   Where information  was
                                  63

-------
North Shore
West Shore
South Shore
East Shore
Total
                                                                 Table  II-7

                                                    SUMMARY OF DATA ON  ON-SITE  SYSTEMS
                                                         (BASED ON  SANITARY SURVEY)
Number
Surveyed
(Z Total)
33
(13%)
11
(20%)
20
(11%)
10
(5%)
74
(12Z)
Number of
Systems
>10 yr.
(% Total)
20
(65%)
4
(36%)
11
(58%)
7
(78%)
42
(56%)
Average
Age
15
11
12
15
13
System Setback
<50 ft.
from Well
10
(32%)
1
(9%)
5
(26%)
5
(50%)
21
(29%)
System Setback
<50 ft.
from Lake
9
(30%)
0
0
1
(11Z)
10
(8%)
House Setback
Range - ft.
(Mean)
31-450
(172)
40-100
(85)
48-225
(84)
50-300
(137)

Septic Tanks
Undersized
21 Don't Know
50Z+
4 Don't Know
14%
10 Don't Know
50%
4 Don't Know
50%
39
Source:  Green Lake Constructions Grants  Sanitary  Survey.  M.  Hummel,  1978.
                                                                                                                          based on limited
                                                                                                                          no. of residents
                                                                                                                          who knew this
                                                                                                                          information

-------
available, the survey data indicated that  50% of  the  sites on the south,
north, and  east shores had  undersized  septic tanks.   Only 14% of the
septic tanks found along the  western shore were undersized.  This shore-
line has  the  fewest  number of ST/SAS which are  older  than  10 years and
consequently a  larger  number  comply with  the standards for septic tank
size.

     Site Limitations.   Because  no  percolation  test  is  required for  a
permit and  because depth  to  groundwater  is shallow throughout much of
the  Proposed  Service Area, it  is  suspected  that  many on-site 'systems
violate the standards  with respect  to site limitations.  MPCA standards
for  individual  sewage  treatment  systems  (WPC-40) require that the size
of the drainfield be determined by  the soils percolation  rate.  Although
the SCS soils  survey has  not  been  completed for the  Study  Area, avail-
able survey data indicate that the  soils are quite  variable.  Generally,
suitable  sandy and  sandy loam  soils are found along  Green  Lake, but
impervious  clay areas  are not  uncommon.   Some excessively  permeable
soils along the  west shore,  and some impervious soils around Nest Lake
have  been  noted  as  having  site   limitations   (by  telephone,  Steve
Peterson,  May 1978).

4.   PROBLEMS  WITH EXISTING  SYSTEMS

     Numerous   violations  of  the  standards   for   ST/SAS  conditions
throughout  some parts of  the Study Area  have  led  to  the  question of
whether existing  systems  along the  lakeshore are causing public health
or water quality problems.  The distinction should  be made between water
quality and public  health problems  on   the  one hand  and  nuisance or
community improvement problems on the other hand.  On-site systems known
to  contribute  to violations  of  water quality standards  or changes in
trophic status  pose  water quality  problems.   Public  health  problems may
result from ponding  of effluent  on the soil surface  or contamination of
groundwater supply  in  excess  of drinking  water  standards.  Where  lakes
are used  for  contact recreation, violation of the fecal coliform  stan-
dard  also  constitutes  a   public health  hazard.   Community improvement
problems  include  odors,  restrictions on  water  use and  restrictions on
building expansion.

5.   PUBLIC HEALTH PROBLEMS

a.   Backups/Ponding

     Despite numerous  alleged violations  of the County's standards for
on-site  systems,  and  an  alleged   shallow  depth  to  groundwater  found
throughout  much of  the   Proposed  Service Area, the  number of  systems
which pose  public  health  problems  as a  result of backups or ponding is
relatively  few.  The County has  indicated that where problems do  occur
they  are  usually the  result  of residents  converting from  seasonal to
permanent  status.   When  this happens,  the individual  soil absorption
systems may not be  large enough to  accommodate the extra flow.  Con-
version from  seasonal  to  permanent  status has been most frequent  along
the eastern shore.

     The  County  indicated  that  the  number of failures around Nest Lake
is  also  low;  although  impermeable  soils  are  found  in  some areas, the

                                 65

-------
lots are adequately sized and many of the systems  have been upgraded  (by
telephone, Steve Peterson, May 1978).

     Based  on  data  gathered during  the Sanitary  Survey  only  13%  (9
systems)  had  ever  experienced  problems  with  backups   or   pondings.
Appendix C-9 summarizes  data on these systems.  At  least  three of  these
problem systems were in need of maintenance  which  is expected  to  correct
the problem.   Only five  ST/SAS  or  7% of those surveyed had  backups  or
ponding on more than one occasion each year.   It is  not clear  that  these
problems are the  result  of site limitations.   All of these systems were
more  than 10 years  old, at  least  one  septic  tank was undersized  and
three  had  a poor  maintenance record.   However,  all five  systems were
suspected of being in an area where the groundwater  level  was  high  (less
than 8 feet).  The location of these few systems with recurring problems
was limited to the north and east shores of  the lake.

     The EPIC aerial  photographic survey was  flown  in August  of  1978 to
identify  surface  malfunctions.   As  Figure   11-11  shows,  only  three
marginally  failing  ST/SAS were  detected along the Green Lake  shoreline.
The two marginally failing systems observed  along  the north shore may be
in an area with a high groundwater level.  Since many of the systems  are
poorly maintained,  however,  these surface malfunctions cannot be attri-
buted  to  site limitations  without  further  investigation.  One  failing
and one marginally failing system were observed along the  north shore of
Nest  Lake.   Some  impervious soils  are  known  to  exist  in  this  area.

b.   Groundwater Contamination

     As  discussed   in   Section  II.B.2  only  localized   high  nitrate
concentrations in groundwater have been found  in the Study Area.  Out of
97  water  well  samples  tested  in  July 1977,  only  two samples showed
nitrate  concentrations   in  excess of the public  health drinking  water
standard  of 10  mg/1.   Their samples  were  from wells located in  the
northeast and  east lakeshore  areas (see Appendix  C-l for well data).

c.   Water Quality  Problems

     Based  on data  available through the National Eutrophication Survey
and  the  results of  the   "Septic  Snooper" analysis   (see II.B.I)  septic
tanks  are  not significantly  contributing to  water  quality degradation.
It  is  estimated  that septic tanks contribute  only 6% of the total  phos-
phorus  load to Green Lake  and  that the lake is  mesotrophic  in  status.
Kerfoot  (1979)  observed  that  only a  small  number of septic leachate
plumes were being discharged into Green Lake during  a March 1979  survey.
These  plumes  were associated  mainly with sites  along  the north shore;
the  phosphorus  loadings  at  a location adjacent  to  the plumes were  in-
significant compared  to  the load contributed  by  the  Middle Fork of  the
Crow River.

     There  is  no  evidence  that  existing  systems  are  contributing
significant  bacterial loads.   Bacterial levels  along nearshore  areas
were  generally below the  Minnesota State  Health  Department and MPCA
standards   for  recreational  waters  (Green  Lake Property  Association
1970-1971;  MPCA  1968-1968;  and  SW  State University 1975-1977).  Values
in  excess  of the  standards were found  in inlet  and outlet streams  and

                                  66

-------
these levels could not  be  attributed to septic tank leachate.  Kerfoot
(1979) detected very  low levels., of; fecal, coliform (generally less  than
10 counts/100 ml) in  surfaced Water; located  at  the  discharge  of  a  septic
leachate plumes.

d.   Other Problems

     Some  residents  served by on-site  systems have reported localized
algal growth  along  the Green  Lake shoreline.   While localized algal
growth may be  considered  a  nuisance since  it interferes with recrea-
tional activity and  is  aesthetically displeasing,  it is not  necessarily
indicative of a water quality problem.

     The  sanitary  survey  investigated the  extent  of  Cladophora  growth
along the  Green  Lake shoreline.   Since  the natural nutrient level  in
Green Lake is low,  growth of the filamentous algae,  Cladophora is  depen-
dent  on  localized  nutrient sources.  Table II-8 summarizes  the results
of the  Cladophora  study.   The  dead Cladophora found  washed up  on  the
north and west  shore may  not have  grown  adjacent to  those  sources.
Green Lake had been lowered prior  to  the  time of the  survey and there
were  signs  of  dead  Cladophora  along  the   shoreline  where  no  live
Cladophora was  found in water.

     Dense  patches  of  Cladophora  were  observed  only  along the north
shore and at the point of outflow of the  Canal  on  the east shore.
D.   BIOTIC RESOURCES

     Of the 16,700 acres in the Green Lake  Study Area,  40% is  water,  19%
is forested, 30%  is  under cultivation,  and 4% is developed for  residen-
tial  and  industrial  purposes,  (including  the New London  National Fish
Hatchery).  The 7% remaining  is in open space:  wetlands,  hay  meadows,
fallow land in  private  ownership,  Minnesota wildlife  refuges  or Federal
waterfowl  areas.  Scattered  throughout  the Study Area, the forests  and
open  lands provide habitat  for a variety of wildlife,  including amphi-
bians, reptiles, birds,  and mammals.

     The State of Minnesota regards wildlife as a resource and regulates
the  shooting  of upland birds  and game  mammals,  as well  the taking  of
fur-bearing animals  in  season.  A major concern  about the Green Lake
project is  the  maintenance or improvement of  the quality of  lake  and
stream waters in  a manner that will conserve valuable wildlife  habitat.

1.   AQUATIC BIOLOGY

a.   Aquatic Vegetation

     The  production  of  plant material ultimately  determines  the number
and kinds of animals  that can be supported  in a lake or stream.   Further-
more, the number of species of aquatic plants and their relative numbers
indicate in a qualitative manner the degree of nutrient pollution of  the
water.  In the  poor  quality  water of  midwestern eutrophic |lakes,  the
relatively  few  species  of aquatic  vascular  plants*  are  dominated  by
                                  67

-------
                                  Table II-8

                          RESULTS OF SANITARY SURVEY
                       (# of Homesltes with Cladophora)
Shoreline
North
West
South
East
Total
Homes
Surveyed
33
11
20
10
. 74
Slight to
Moderate
Cladophora
5**
5
9
4
21
Heavy
Cladophora
2
0
0
o***
2
Heavy
Dead*
6
5
0
0
11
*     This algae was not necessarily associated with the home adjacent to where
      algae was found.

**    Only 16 sites were free of ice cover.

***   Heavy Cladophora growth was found near canal.
                                      68

-------
water  milfoil.    Blue-green  algae  or  late  summer  algal  "blooms"  may
produce green-colored  water  in eiitrophic lakes  and  foul-smelling piles
of decaying vegetation on the shorelines (Lind and Cottam 1969).

     A limited  survey  of the aquatic plants  of Green Lake  and Nest Lake
conducted  in  1971 by  DNR found a mix  of semi-aquatic*  (shoreline)  and
rooted aquatic  plants"  but no  water milfoil.  The algal blooms reported
to be  heavy at times  in the Nest Lake did  not  appear  to  significantly
reduce light  penetration  during  critical  times of year for  the rooted
plants.

     The DNR  surveyors  estimated  that only  1% of the  surface of Green
Lake was  covered with  emergent plants  (bulrushes,  cattails,  manna  and
other  grasses)  probably  because  of  its great  average depth  and  the
absence  of embayments.   Green  Lake's exposed  shoreline  \is  regularly
scoured by  waves  and  ice, both detrimental  to  the  production of rooted
aquatic vegetation.  In Green  Lake,  rooted aquatic plants  were found to
a depth of 35 feet, indicating very clear water.  Rooted vegetation grew
from depths of  30 feet in Nest Lake,  7% of  whose surface  was estimated
to be covered with emergent plants.                        i

b.   Fishes

     Green Lake  and Nest Lake  are important for recreation; and serve as
habitats and  spawning  areas for fish  and  wildlife.   Thes;e  lakes  have
been classified by the  Minnesota DNR  as  follows (by  telephone/ Elvin
Tews, October 1978):
Lake      Ecological Classification

Green     Bass, panfish, walleye

Nest      Bass, panfish, walleye
            (northern pike)
Management Classification
              i
     Same Species

     Same Species
The fact  that  the management classification is the same as the ecologi-
cal  classification indicates  that  the  composition  of the  fishery is
consistent with management goals based on the physical parameters of the
lakes.

     Woodcock  Lake supports populations of  only  bullheads! and minnows.
The  fauna is  determined  in part  by frequent  "winterkills",  or  fish
die-offs, caused  by  severe reductions in the level of dissolved oxygen.
Winterkills are most common in shallow lakes where a long period of snow
cover  can  reduce  or  prevent  significant photosynthesis  by  aquatic
plants.   In Woodcock Lake, this problem is aggravated by the high oxygen
demand  resulting  from the  breakdown of organic  wastes discharged from
the Spicer wastewater treatment facility.                  :

     The  most  recent survey  of lake fishes was  conducted; by Minnesota
DNR  in 1971 (by  telephone,  Elvin  Tews,  October 1978).  A  list of the
number of species and their relative densities  for  Green  jLake and Nest
Lake appears in Appendix E-l.  Although the densities varied, the

                                  69

-------
similar  composition  indicates a  healthy  diversity of  sport  and rough
fishes  in  these  lakes.   Results of  the  survey are  summarized  in the
following table which also shows  changes since  1954.
Lake      1971 Status

Green     Walleyes,  perch,
          rockbass,  green
          sunfish,  bull-
          heads, pumpkin-
          seed above State
          average;  others
          average.

Nest      Walleyes,  perch &
          bluegills  above.
Change since 1954
	survey	

Increase in number
of bluegills;  de-
crease in cisco.
White crappie
decline in number.
   Important as
 spawning grounds for

  Walleyes, smallmouth
  bass, panfish,
  cisco
Northern pike
and panfish.
     DNR  from  its  surveys  concluded  that  population fluctuations are
common natural occurrences and  that  the  Lakes are supporting large and
diverse fish populations.   (The New  London Fish Hatchery produces only
Salmon fry and fingerlings for release  in Lake Superior).

c.   Waterfowl,  Shore and  Wading Birds

     The  Study  Area  provides varied  nesting and  feeding  habitat for
waterfowl  and  other  water  birds.   It contains  five Federal waterfowl
protection areas plus the Dietrich  Lange  State Wildlife Management  Area.
Such marsh birds  as  great blue heron,  black-crowned  night heron, little
green heron and American egret feed  on fish,  crustaceans,* insects and
small vertebrate  animals living in shallow water or  adjacent wetlands.
Waterfowl, including mallards,  American  mergansers, and  Canada  geese
breed and  feed  on area  lakes.  Although  most birds are  summer residents
only,  some,  such as  the small  numbers  of Canada geese which  use the
unfrozen section  of  the  Middle Fork  of the Crow  River and feed  in  corn-
fields,  remain   in   the  Study Area   throughout  the  winter  months.
Kandiyohi County,  located near the  Mississippi Flyway, and with  about  40
State and Federal wildlife and waterfowl  areas, attracts migratory  birds
(including waterfowl) especially in the autumn.

2.   TERRESTRIAL BIOLOGY

a.   Forest

     The  major  forests  in the  Study  Area  are  mixed  hardwood types,
including  many  elm   and  cottonwood trees  (Kandiyohi  County  Economic
Development Plan  1977).   Forested  areas  are confined primarily  to  river
and  stream banks, lakeshores  and  steep  hills; the  largest are located
north of  Green  Lake  and Nest Lake.    With the soils of the Study Area
continuing to be  productive for agricultural  crops,  neither  reforesta-
tion nor growth of the timber or pulp industry is likely in  the  foresee-
able future there.
                                  70

-------
b.   Wildlife

     Vertebrate  wildlife  is  found  throughout  the  Study Area  wherever,
there is  habitat for  feeding  or nesting.   Wildlife  is likely  to  con-
centrate  in  the state wildlife  management areas and Federal  waterfowl
protection areas,  but undeveloped  private  lands  are probably  locally
important  as  well.   Hunters  seek  ring-necked  pheasants   in  the  high
quality habitat provided  by small wetlands found on  many farms  south and
east of Green  Lake,  and  the ruffed grouse and  American woodcock in the
forests.  Migratory waterfowl are major game  birds.

     The  forests,  especially  those  north  of  Green  Lake,  provide  im-
portant habitat  for  the  most valuable big game  animal,  the  white-tailed
deer, which  although  it feeds  mostly  in  open  lands  and  crop  lands,
usually spends  periods of inactivity  in  forests.  Other hunted  species
that may  rely  heavily or solely on  forest habitat are both  fox and  gray
squirrels, raccoons,  and to  a  lesser extent,  red  foxes  (by  telephone,
Charles Gernes,  24  October 1978).   Mammalian species in the Study  Area
valuable  for  sport   or  as  food for valuable  mammals are  listed  in
Appendix E-2.   Of  these,  a small mammal, the 2-ounce meadow vole may be
the most  numerous;  it is a staple food item in  the  diets of most larger
carnivorous  mammals  as well  as  of  hawks, owls, and many large  snakes.
Meadow voles are numerous  in grasslands  or cattail  marshes, often shar-
ing  the  latter with  their  close relative,  the muskrat.   According  to
Charles  Gernes, Manager of  the  New London Fish  Hatchery,  both  the
American bald eagle, classified as endangered by the Federal Government,
and the great  horned owl hunt in the  Study Area; the owls nest there as
well.

3.   WETLANDS

     Wetlands deserve particular  consideration  because  of their role in
purifying water, their value to wildlife, their  potential susceptibility
to the  adverse  effects of construction,  and their diminishing  frequency
of occurrence within the  Study Area.

     The  State  of  Minnesota  recognizes  that wetlands  are  valuable for
preserving and  maintaining  groundwater  levels,  as habitat  for  wildlife,
and as spawning grounds for certain important fishes,  including northern
pike.  Even lands not available for  public use or not connected with any
navigable  waterway  are considered to  be a  resource  of the State;  the
alteration of  a wetland  larger than 50 acres requires an application by
the landowner and a subsequent hearing.   In the  event that permission to
drain the  wetland  is denied, the State must be  prepared to  purchase the
lands under either the State or Federal waterbank system.

     Part  of the State's concern about the preservation of wetlands  is
the  realization that although  they  can  be  destroyed,  directly  or  in-
directly,  within  a   short  time, wetlands  cannot  be  reconstructed  or
restored  like  terrestrial or  water  environments.  Wetlands are formed
over  hundreds   or  thousands  of  years by deposition  of sediments  and
organic  debris during natural  processes,  creating  acid,  water-logged
soils and  a  range  of other features that cannot be restored after harsh
disturbance.   For instance, the lowering of the  water table  by as little
                                  71

-------
a:; two or  three  feet  can cause  the  organic matter  in  the peaty soils to
br lost  through  oxidation within a  short span  of  months  or years  (de-
pending partly on whether the  soils are burned).  The  raising of the
water table 5 years  later  will  not  restore the  conditions that formerly
existed,  and in this sense  wetlands  cannot be  restored.

     The lack  of shallow  embayments  and coves  along  Green Lake's  sym-
metrical  shoreline  retards  the  development  of   large wetlands areas
there.

     Ditching to  improve the drainage  for agricultural purposes  has led
to the  loss  of  much  wetland   area  within  the  Green  Lake  Study Area,
decreasing  wildlife  habitat.    Nevertheless,   on  almost  every farm,
patches  of land  remain,  some   several  acres  in extent, which  are too
poorly drained to be plowed and  planted.   (Such  moist  patches of  wetland
may be  vegetated by  cattails,  sedges,  willows  and alders.   Crops are
generally planted right, up  to the edge  of intermittent  streams, drainage
ditches or  hay meadows.)   In addition  to those  near agricultural areas,
there  are   several  extensive wetlands  near  other lakes  and  streams,
covered by  herbaceous  growth and dominated by cattails.   Many of these
wetland areas have  been  incorporated into State-run wildlife management
areas and  Federally managed waterfowl  areas.  The  total wetland  acreage
is estimated to be approximately 7%  of  the Study Area  (see Figure II-7).

     Wetlands  are vital  to  the  maintenance  of  wildlife  populations.
Alteration  of  some  proportion  of  wetlands  would  alter both  fish and
wildlife  populations  and   almost  certainly  reduce   the  recreational
potential of the  Study Area.

4.   THREATENED OR  ENDANGERED SPECIES

     Kandiyohi County does not lie  within  the primary  or peripheral
range of the  gray wolf,  nor  is  it within either the  breeding or winter
habitat of the American bald eagle.   Both animals have  Threatened status
and are protected by  the  Endangered Species  Act of 1973 (P.L. 93-205).
Furthermore, none of  the two  species of butterflies  or five species of
plants that have been proposed  for special   status by the US Fish and
Wildlife Service  is  known in Kandiyohi  County.   According to a letter of
iO April 1979 of D.H.  Rasmussen,  Acting Regional  Director,  US Fish and
Wildlife Service, no  species  of  plant  or animal  that is  additionally
protected by Minnesota law  is known  to  exist in  the Study Area.
E.   POPULATION AND  SOCIQECONOMICS

1.   POPULATION

a.   Introduction

     Population  information  for the  Green  Lake Study  Area  is derived
from published data  and  primary field data  collected during the prepar-
ation  of  this EIS.   Published information  from  the US  Bureau  of the
Census and other  sources  is available  for  Kandiyohi  County and  the minor
civil  divisions  (villages,  cities,  and  townships)  within  the County.
                                  72

-------
The Study Area consists of New London Village,  Spicer City,  and  portions
of the New  London  Township,  Green Lake Township,  Harrison Township,  and
Irving Township.   It is not possible to accurately disaggregate  existing
published data below the  township  level for the purpose of  describing
the population characteristics of the portions  of  the townships  included
in the Study  Area.   Thus,  published socioeconomic data is presented  for
the entirety  of  each  of  the minor civil divisions  wholly  or partially
within the Study Area.

     Primary  field  data was  gathered for the Proposed EIS  Service Area
(see Figure 1-3).   For the purpose of  this  study,  the Propos.ed Service
Area was  divided into  25  segments.   A map of  the segments  is contained
in  Figure  11-13.   Population  related  data collected through  primary
field study include the number of permanent and seasonal dwellings.   The
dwelling  counts  served  as  the  basis  for  estimates  of  permanent  and
seasonal population within the Proposed Service Area.

b.   Existing Population

     The  Proposed  Service  Area had an  estimated  1976  permanent popula-
tion of  2,400 and  a seasonal population of  4,500.   The  1976  population
estimates were based on  field surveys.   Thus,  the Proposed  Service Area
had  a  total  summer population  of  6,900  with seasonal  and permanent
residents accounting  for  65%  and  35% of the  total,  respectively.   New
London Village and  Spicer  City had the largest number and proportion of
permanent residents, while Green Lake Township, New London Township,  and
Irving Township all had large seasonal populations (see Table  II-9  for a
detailed  breakdown  of  1976  permanent and seasonal  population  by minor
civil divisions).   No  data  specific  to the Proposed  Service  Area  are
available on  either the  permanent or seasonal  population prior  to  1976.

c.   Population Projections

     Permanent and  seasonal  baseline Proposed  Service Area populations
were projected for  the year 2000.  Permanent population projections were
based on projections developed by the Minnesota State Demographer (1978)
and the  Kandiyohi  County  Planning Commission (1977) for the minor  civil
divisions containing the  Proposed  Service Area.  These projections were
applied  to  the 1976 Service  Area estimates  and adjusted  to reflect  the
proportion  of  future  population  growths  in minor  civil  divisions
expected to occur within the Proposed Service Area.

     Seasonal population for the year 2000 was  projected on  the  basis of
1976 estimated seasonal population.   Projections  of seasonal  population
for  the  year 2000  were   estimated  for  each  segment  of  the  Proposed
Service  Area.  The  future  ratio of seasonal to permanent population  was
revised  downward to reflect  the assumption that the ratio is  declining.
Built into  this  assumption is the understanding  that  the conversion of
seasonal  residences  to permanent residences  will  outnumber  new  seasonal
residential construction.   A drop  of 20% in  seasonal population  (from
4,500 to 3,600) is projected to occur by the year  2000.

     A  total  summer  population was  calculated  based on  seasonal  and
permanent population.  Permanent,  seasonal  and total summer populations
                                  73

-------
                                                               FIGURE  11-13   GREEN  LAKE  SEGMENT  LOCATION  MAP
                                                                                       LEGEND






                                                                                          SEGMENTS
Source: beaiu i9/b

-------
TABLE II-9








Green Lake Township
Irving Township
New London Township
New London Village
Splcer City
TOTAL SERVICE AREA
POPULATION
1976
K
0
B
CO
rH
a
o
958
1,453
2,685
734
1,071
6,901


4-t
S
1
&
73
138
721
734
735
2,401



a
|
1
885
1,315
1,964
0
336
4.500
2000
^
H
B
en
|H .
a
u
Ł
1.024
1.696
3.513
734
1.440
8.407


w '
S
1
Ł
316
646
1,941
734
1.170
4.807



rH
g
1
708
1.050
1.572
0
270
3,600
DWELLING UNITS
1976
M
9j
B
w
•a
Ł
168
265
539
220
310
1,502


4J
g
a

'•• s ••-..
1 .:
91
87
208
563
220
402
1,480
•,"'"! •••*'• '
• ,-. - :-:---' s.

'Sv'--.-
'
- •"-••', -.
lie
175
262
0
45
600

-------
are listed In  Table  II-9.   A detailed explanation of the methodology of
cal uatjag these  population projections  is  provided in  Appendix  F-l.

     fa  the  year  2000,  the  total  summer population of  the  Proposed
Ser :.;.;•: Anva is  projected  to be 8,407, an increase of 18% over the  1976
pop ' • !;.!. on  estimate.   The  largest  absolute  increase is  projected  to
occ<   in New London  Township which is expected to gain 828 residents by
the ,rŁar 2000.   The  permanent to seasonal population  ratio  is  expected
to  :.ncrease.   This  trend  has  been incorporated  into  the  population
pro  Ltiaa to  reflect  the  tendency for second homes  to  be converted to
ful  Mrae use.
2.   CHARACTERISTICS OF  THE POPULATION

a.   Income

     The data presented  in  this  section are for the State of Minnesota,
Kan iyohi  County,  New  London Township,  Green Lake Township,  Harrison
Tow .ship, Irving Township,  New London Village, and the City  of Spicer.
Characteristics were  selected because of their  importance  in analyzing
the  financial  effects that  the  various wastewater management alterna-
tive  could have  on  individual  households.   The  data presented  below
represent income figures  for permanent residents.   No  data is available
for population income of seasonal residents.

     In.  1970,  the  mean  average  family income  in  the Green  Lake  Study
Area  was $9,285  (see Appendix  F-2).  Although the  Study Area's  mean
fam.ily  income  was  slightly  greater  than the  county  mean,  it was  sub-
stantially  less  than  the  national  and  state  figures of $10,999  and
$11,048.   Significant  variation  in mean incomes, of the individual  com-
munities within  the  Study   Area  were  evident,  ranging  from a low  of
$6,f26  in  Irving  Township  to a  high  of  $14,385  in Harrison Township.
Thus,  it appears  that while aggregate figures for the Study Area  were
indicative  of a moderate income  area, pockets of  low  income households
were present.

     Compared  to  Minnesota,  both  Kandiyohi County  and  the  Green  Lake
Study  >Area were  characterized  by  a  large  proportion of  lower  income
families  (see Appendix   F-2).   Approximately 50% of the families  in
Minnesota  had an  income in  1970  of  less  than  $10,000,   while  similar
statistics  for  the  county   and  the  Study  Area were  61.3%  and  64.6%,
respectively.

     The relatively low incomes  experienced in the  Study Area could have
been the result of a number  of factors such as:

     ©    The agricultural  and tourism orientation of  the local economy
          providing  relatively  low  skill/low wage employment opportu-
          nities;  and

     o    A  large  portion  of the population  was  comprised  of  elderly
          people,  who were retired and living on fixed  incomes.
                                  76

-------
b.   Poverty Levels
     *
     In  1970  there  was a  slightly higher  incidence  of poverty  among
families in  the Study  Area  and Kandiyohi  County  than in the  State  of
Minnesota  (see  Appendix F-2).   The  family poverty  rate  for the  Green
Lake Study Area was 10.8% for  this  period and for the state was  8.2%.
The proportion  of  families with incomes below the poverty level  varied
considerably among  communities  in   the  Study Area from a high  of 22.8%
in Irving Township to a low 4.4% in Spicer Village.

     A large proportion of persons with incomes  below  the poverty level
are elderly or 'retired and living on fixed incomes.   In 1970, persons  65
years or older accounted for  23% of all  persons of poverty status  in the
Study Area (see Appendix F-2).   New London Township  had an especially
high number (44%) of people who were 65  years or  older  and classified  as
living in poverty.

c.   Employment

     In  1970,  Kandiyohi County and  the State of  Minnesota  were  char-
acterized  by  similar employment characteristics  with  the exception  of
two  sectors:   agriculture and  manufacturing.  Kandiyohi County and the
region were relatively more dependent on agriculture  for employment than
the  state  as  a  whole.   More  current information on  this  trend  will not
be available until  the  1980  Census.   The county's  manufacturing employ-
ment  was  considerably   lower  than  either  the  region  or  the  State.
Although  agricultural  activity  has been  declining  since  I960,  the
service  and  trade  industries  have become  the primary   sources  of
employment (see Table 11-10).

     Tourism played  a  significant  role  in the local  economy  In  1972.   A
comparison of tourism-related services in Minnesota and Kandiyohi  County
shows  the   importance   of  these  activities  to  the  county  (see  Table
11-11).  Hotels,  automotive and  amusement  services   accounted  for  a
larger proportion  of services  in the county than  in the  State.   Retail
trade statistics  reinforce the  observation of the importance of tourism
to the local economy (see Table 11-12).   Over 20% of  all retail  trade  in
Kandiyohi  County in  1972 was  related   to building  material  and  farm
equipment compared to 7% for  Minnesota.   This divergence could be  attri-
buted  to  retail  sale  for farm equipment since  the  local  economy was
largely oriented toward agriculture.

     Financial Characteristics.   Financial characteristics of the local
governments in  Green Lake  Study Area are presented in  Table  11-13.   The
information includes taxable valuation  of real property, total revenue
receipts,  total current expenses, total capital outlay, and total in-
debtedness.  Such information is helpful in evaluating  various financing
alternatives available to local governments.

     In  Minnesota,  counties  serve as agents  for  subordinate government
units,  acting  as  the  collector  and distributor  of taxes  and grants.
Revenues are generated  from three major  sources:
                                  77

-------
                               Table 11-10

                     KANDIYOHI COUNTY PERCENT SHARE OF
                    EMPLOYMENT BY INDUSTRY 1960 and 1970
Agriculture

Construction

Manufacturing

Transportation

Wholesale and
  Retail Trade

Finance

Public
  Administration

Service (.1)

Utilities and
  Communication

Mining
State
1960
14.9
5.7
20.1
5.1
20.1
4.2
3.9
22.0
2.4
1.5
1970
7.7
5.7
21.0
4.1
22.0
4.6
3.8
27.6
2.5
1.0
Region 6E
1960
37.4
5.9
10.6
3.2
18.5
2.4
2.5
17.7
1.7
0.1
1970
21.9
6.2
19.4
2.8
20.7
2.6
2.7
21.7
1.9
0.1
Kandiyohi
I960 1970
29.8 '
7.2
8.5
6.4
18.3
3.1
2.8
21.9
1.8
0.2
17.4
6.6
11.1
4.6
24.6
2.7
3.1
27.7
2.1
0.1
(1)  Includes business and repair services, personal service workers, en-
     tertainment and recreation, professional and related services workers,

Sources:  Minnesota Socio-Economic Population
          Characteristic-Employment, Volume 2.

          Minnesota Analysis and Planning System (MAPS).
                                    78

-------
                               Table II -11
                          SELECTED SERVICES - 1972
                           Minnesota
                               Kandiyohi County(1)
                    Receipts      Percent of    Receipts     Percent of
                    ($1.000)  Industry Receipts ($1,000)  Industry Receipts
 Hotels
$  188,879     10.8
$  332
14.9
Automotive
  Services
   185,916     10.7
   369
16.6
Amusement
   192,008     11.0
   326
14.7
Total Services       1,734,051
                              2,223
(1)  Excludes Willinar
Source:  U.S. Department of Commerce, Bureau of Census, Census of Selected
         Services 1972.                                                 '
                                    79

-------
Building
 Materials .and
 Farm Equipment

General
 Merchandise
Food Stores
Automotive
 Dealers
Gasoline
 Service
 Station
Apparel Stores
Furniture Stores
Eating and
 Drinking Places
Drug Stores
Miscellaneous
 Retail Stores

Total
                                Table 11-12
                            RETAIL TRADE - 1972
                            Minnesota
 	     Kandiyohi County(1)
  Sales     Percent of      Sales    Percent of
($1.000)    all Trade     ($1.000)   all Trade
$   601,195    7.1
 1, 240,686   14.8
 1,583,252    18.9
 1,503,205    17.9
   710,548     8.5


   369,731     4.4


   378,425     4.5



   659,344     7.8


   246,132     2.9



 1,059.879    12.7

$8,352,397
$   4,233    23.0


     (D)


    2,449    13.3



    4,130    22.4
    2,722    14.8


     (D).      —


      404      2.2



    1,245      6.7


      (D)



    2,180     11,8

  $18,370
(1)  Excludes Willmar.
(D)  Withheld to avoid disclosure.
Source:  U.S. Department of Commerce, Bureau of Census, Census of Retail
         Trade-1972.
                                    80

-------
                                                                          Table  11-13

                             FINANCIAL  CHARACTERISTICS  OF  THE  LOCAL GOVERNMENTS  IN  THE GREEN LAKE STUDY  AREA
                   Taxable
                    Valuation
                                     Knndtyohl
                                     Countv
                                             (1)
                                     $79,584,606      .$3.360,24(1
                                                                               (2)
                                  Creen Lake         Harrlson
                                  Township __ ^      Township  _     Townshlji     Townsh I
                                                                               New London<2)     Hew  Condon(2)
                                                                                                                    Village
                                                    $2,567,957      $2.174,262   $3,851,864        $1,110,839
                                                                                                                                    Sptcer Village

                                                                             $1,567,827
                   Total
                    Revenue
                    Receipts
                    6,8/i6,234
                                      27,671
                  24,968
28,461
                                                                                   41,877
108,821
139,862
CD
                   Total
                    Current
                    Expense
Total
 Capital
 Outlay
                   Total
                    Indebtedness
                   6,271,202
                                         67,894
                                       3,464,780
25,180.
                                                          6,714
                  19,430
15,900
                                                                                          20,933
                                             30,565
103,147
                                                                                 97,589
                                                                                                                                         218,000
                Sources:  (1)  Report of the State Auditor of Minnesota.  Revenues,  Expenditures and Debt of Local Governments In Minnesota.   August 1977.

                         (2)  Report of the State Auditor of Minnesota.  Revenues,  Expenditures and Debt of the Towns In Minnesota.  January 1978.

                         (3)  Report of the State Auditor of Minnesota.  Revenues,  Expenditures and Debt of the Cities In Minnesota,  November  1977.

-------
     »    General property tax;
     e    Federal revenue sharing;  and
     6    State aid  to local governments,  usually $25-$30 per  capita.

     From  these  revenues,  expenditures  for  general  government  and
capital outlays are  made.   Counties,  townships,  and cities  all can take
on debt in the form of general obligation bonds.   The  debt limit  on such.
bonds is  set  at 6-2/3% of the taxable valuation of the government unit.
General obligation bonds  require  voter approval in Minnesota.   In con-
trast, revenue  bonds  have  no set  debt limit and do not require a public
referendum.

     According  to Table  11-13  only the entities of Kandiyohi  County and
Spicer Village  have  outstanding debt.   At  the end of fiscal  year 1975
Kandiyohi County had  a total indebtedness of $3,464,780.  Of  this debt
$1,155,000  were  general  obligation  bonds;  $2,109,780  were  special
assessment bonds; and  $200,000  were  other types of bonds.  The  general
obligation debt amounts to $1,155,000, which was relatively low compared
to a  debt limit of  $5,252,684.  The  Village of Spicer's debt was com-
prised of $18,000  in  general  obligation bonds and $200,000  in  special
assessment  bonds.    Spicer  had  a  debt  limit  of  $104,417  on  general
obligation bonds.

3.   HOUSING CHARACTERISTICS

     The  total  dwelling  unit count for the  Proposed EIS  Service  Area in
1976  was  1,502  units.  Of these,  753 units or 50%, were occupied on a
year-round basis.   In 1970,  seasonal units accounted for 11.9% of the
housing stock in Kandiyohi County  (see Table 11-14).

     Age  characteristics  of the  permanent  housing  stock  provide  an
indication  of  construction  trends in  the   area.   The  distribution of
housing ages  for the Study Area closely corresponds to age distribution
for  the   State  and county.   However,  a wide  variation  in ages exists
between the  communities within the  Study Area.   Irving  Township  has a
relatively old  stock,  with 81.7%  of units built before  1939.   Both New
London  Township and  Green  Lake  Township  experienced  substantial  in-
creases in  residential construction  between 1965  and 1970,  while very
little construction  activity was  evident in the villages of  New London
and Spicer.

     The  median value  of owner-occupied units and the median  gross rent
for  rental  units  in  the  Study Area were  considerably  lower than the
national  and  state medians (see Table 11-15).  The low  values could be
attributed to such factors as:

     9    The rural location of the Study Area;

     6    The structural  conditions  and amenities  of  individual units;
          and

     9    Second homes  and vacation  homes are often of lower  value than
          year-round units.
                                  82

-------
                                                               Table  11-14




                                                      HOUSING CHARACTERISTICS  1970
Minnesota
Number Percent

Total Dwelling Units
Permanent
Seasonal
Of Permanent
Occupied
Vacant
Of Occupied
Owner Occupied
Renter Occupied
Age of Permanent Housing
Oo Built after 1965
•,{J3 Built between 1939-1964
Built before 1939

1,276
1,219
56
1,153
65

824
329
Stock
155
461
602

,082
,591
,491
,946
.645

,634
,312
,478
,590
,523


95.6
4.4
94.6
5.4

71.5
28.5
17.8
37.8
49.4
Kandlyolii
County
Number

11,109
9,791
1,318
9,272
519

7,065
2,207
1,007
3,198
5,504
Percent


83
11
94
5.

76.
23.
10.
32.
57.


.1
.9
.7
.3

.2
.8
.3
.7
.0
Study
Nunher

2,428
1,601
827
1,505
96

1,255
250
197
485
919
Area
Percent


65
34
94
6



.9
.1
.0
.0

83.4
16
12
30
57
.6
.3
.3
.4
Croon l.nko
Township
Number

410
364
186
219
5

229
30
47
78
139
Percent


58,
41 .
90
I,

R8,
11.
17
29.
52.


.7
,3
.1
.9

.4
.6
.8
.5
.7
Harrison
Township
Number

3R6
198
188
193
5

143
50
15
46
137
Percent


51
48
97
2

74
25
7
23
69


.3
.7
.5
.5

.1
.9
.6
.2
.2
I rvinp.
Township
Number

373
175
196
161
14

151
10
19
13
143
Percent


46.9
53.1
92.0
8.0

93. R
6.2
10.9
7.4
81.7
New London
Township
Number
662
450
212
393
52
331
67
94
179
177
Percent

68
32
88
11
63
16
20
39
39

.0
.0
.4
.A
.2
.6
.9
.8
.3
New London
VlUaEe
Number Percent
285
281
4
271
10
219
52
11
81
189

98.6
1 .4
96.4
3.6
80.8
19.2
3.9
28.8
67.3
Splcnr
Village

292
233
39
223
10
182
41
11
88
134


85.7
14.3
95.3
4.3
81 .6
10.4
4.7
37.8
57.5
Sources:  U.S. Census of Housing, Summary Date .ind Fifth Count  Sumnnry Tnpcs,  1970.

-------
                               Table II -15

                           HOUSING VALUE - 1970


                                     Median Value                 Median
                                Of Owner Occupied Unit          Gross Rent


        United States                 $17,130                      $110


        Minnesota                     $18,054                      $117


        Kandiyohi County              $14,779                      $ 94
Source:  U.S.  Bureau of the Census,
         County and City Data Book - 1972.
                                    84

-------
     Little  information  concerning  the  characteristics   of   seasonal
dwelling  units  in  the  Study  Area  is  available.1   The  1970  census
provides detailed  information on housing age, tenure patterns,  vacancy
rates, and other housing  characteristics for permanent  residences only.
Seasonal units  by  nature of  their  use  as  second homes or  vacation  re-
treats  are  likely  to differ  from  year-round homes  in  terms  of  size,
value, condition and amenities.

4.   LAND  USE

a.   Existing  Land  Use

     Significant land uses in the Study Area include (see Figure  11-14):

     •    Small urban communities of  New London Village and the  City of
          Spicer with a mix of commercial,  residential and  institutional
          uses;

     •    Single family residential/recreational development adjacent to
          the shoreline of Green Lake and Nest Lake;

     •    Agricultural lands; and

     •    Open land consisting  mostly of woodlands, wetlands and lakes.

     Major  transportation  routes   serving  the  area  include  Minnesota
Routes 9 and 23 which run east-west  and US  71 which provides north-south
circulation.   The Burlington  Northern Railroad runs north-south through
the Study Area but does not provide  direct  service to the area.

     The lakes,  streams,  woods,  and hills  in the area provide  aesthetic
value which,  combined with the recreational value of Nest Lake  and Green
Lake  has  resulted  in  considerable  residential   development  of  land
bordering  these  lakes.   A majority  of  these homes  are  occupied on  a
seasonal basis only.

     Other   than   scattered,    tourist-serving   commercial   functions
throughout  the  townships,  most  commercial  activities are located  in
village  centers  or the  approaches  thereto.    Industrial land  uses  con-
stitute  a minor  percentage  of land  use  activity within the Study Area.
The  major  industrial  activities are gravel pit  operations  located  pri-
marily  in  the Green  Lake Township-New London Township portions  of  the
Study Area.

b.   Future Land Use

     A Comprehensive  Zoning  Ordinance for  Kandiyohi County was prepared
in 1977, and contained a zoning map.  This  map was reviewed to  obtain an
appraisal  of  future  land use  patterns.   This zoning map is  the  only
     Although specific  information  is  available for permanent units,  it
     is  not  reasonable  to  assume  that  permanent  and seasonal  units
     exhibit similar characteristics.
                                  85

-------
FIGURE 11-14   EXISTING LAND USE OF THE GREEN
                  LAKE STUDY AREA
                         LEGEND
   WILDLIFE MANAGEMENT
       AREAS

   SINGLE  FAMILY  RESI-
       DENTIAL

   WETLANDS /VEGETATED
       AREAS
      AGRICULTURAL
vffi-^:! COMMERCIAL
    A TRAILER PARK
    g CAMPGROUND
                                 Source:  USGS 1967;
                                 U3GS date unknown;
                                 USGS 1975; Kandiyohi
                                 County Board of Com-
                                 missioners 1971
                                                            vD
                                                            OO

-------
available information relating to future land use patterns  for  the  Study
Area.  A majority of future land uses in the Study Area will be residen-
tial and  agricultural (see Figure  11-15).   As  can be  seen  from Figure
11-15,  future  residential  land  uses  were projected to be  concentrated
around Green  Lake,  Nest Lake,  Woodcock Lake,  New  London Village  and
Spicer Village.

c.   Growth Management

     Kandiyohi County's  Shoreland Management Ordinance established  the
major land development controls affecting acreage adjacent  to Green Lake
and Nest Lake.  The Minnesota  Shoreland Management Act  requires counties
throughout  the  State  to adopt  regulations  which attempt   to  reconcile
future lakeshore development  pressures  with the environmental  sensitiv-
ities and development capabilities of a lakeshore.

     The Kandiyohi County  Shoreland  Management  Ordinance has been  inte-
grated with the  county zoning ordinance  (see Figure 11-15).   Shoreland
acreage around Green Lake and  Nest Lake has (with minor exceptions) been
zoned  R-l  Residential:  Shoreland  Management District.  The  shoreland
management district  is  intended  to  accommodate  residential development
"along the shores  of lakes,  streams and rivers, and  in natural environ-
ment areas,"  while "retain(ing)  the physical features  of  the  shoreland
and natural areas."

     Permitted uses   in  the   shoreland  management district  include  the
following:

     •    General agricultural pasture and minimum tillage  cropland uses
          (drainage   of   wetland  areas   without Planning Commission
          approval is prohibited);

     •    Single-family non-farm detached dwellings,  included individual
          mobile homes, of either a seasonal or permanent nature;

     •    Parks and other public recreation facilities  owned or operated
          by county or other governmental agencies;

     •    Public  and private  camping  and  outing areas  operated on  a
          non-profit basis; and

     •    Historic sites and markers, commemorative public  areas.

     Conditional  uses permitted  in  the shoreland management  district,
subject  to public  comment  and  Planning Commission  and   County  Board
review and approval, are:

     •    Golf  clubhouses, country  clubs,  or  public swimming  pools;

     •    Public  sewage  treatment  facilities,   and  similar  essential
          public utility and service structures;

     •    Recreation-oriented commercial establishments;
                                  87

-------
                                                         FIGURE 11-15   FUTURE LAND USE MAP OF THE GREEN
                                                                              LAKE STUDY AREA
                                                                                 LEGEND

                                                                              AGRICULTURAL

                                                                              RKSTDKN'nAL
Source:  Kandi-
yohi County Board
of Commissioners
1971

-------
     •    Churches;

     •    Recreational  vehicle  camping  (subject  to  Minnesota  health
          regulations; and

     •    Planned  residential   subdivision   developments   (subject  to
          special requirements).

     Special  provisions  for  planned  residential  subdivisions  relax
established density  restrictions  for  the  purpose of encouraging cluster
development, multiple dwellings  and modular  unit developments.   Minimum
required  land  area   is  20 acres.  Public  or community water  and sewer
systems  are  required.    Maximum permitted   residential  densities  are
doubled, provided that  25%  of the land (lakeshore area) is reserved for
public use  and  75%  of the lakeshore is left  in a natural  state.  County
Planning  Commission  and  County  Board  review  and approval of planned
residential subdivision plot  and site plan,  together with issuance of a
conditional  use  permit,  are  required under terms  of the  provision.

     Additional  provisions   influencing  the development  of  shoreland
acreage include:

     •    Restriction of  cutting  or other disturbance of  natural forest
          ecology within  a  100  foot  wide strip  paralleling  the shore-
          line ;

     •    Prohibition  of  construction in   areas  requiring grading  or
          filling where  such activity may impair  water quality through
          erosion and sedimentation;

     •    Allowance  for  clustered  residential  development, subject  to
          plan  approval by  the Commission of Natural  Resources and the
          County  Commissioners,  with  higher net  residential  densities
          conditional upon  provision   of  central  sewage  facilities and
          preservation of open space  through restrictive  deed covenants
          or public dedication; and

     •    Establishment   of   procedures  for   designation  of  special
          districts  in areas of  acute  environmental sensitivity re-
          quiring more  stringent protective  measures  than those other-
          wise available.

     Minimum  lot size,  frontage,  and  setback  from the  lakeshcre for
single-family   residential   development   in   the  shoreland  management
district vary with a lake's  classification (see Table 11-16).

     Green  Lake  and  Nest Lake  have   both   been  classified as  general
development lakes.   A maximum density of two dwelling units per acre is
possible  for  residential  development  in   these  shoreland  management
districts.  Densities of  up  to four dwellings per acre are possible for
approved  planned  residential  subdivisions   or   cluster  developments.

     The  zone  outside  contiguous  lake areas are  restricted  to general
agricultural activities including cash crops  and animal husbandry.  This
is done  to  regulate  the encroachment of non-farm  activities on agricul-
tural lands.
                                  89

-------
                                 Table 11-16

                    SINGLE-FAMILY RESIDENTIAL DEVELOPMENT
                   RESTRICTIONS IMPOSED BY KANDIYOHI COUNTY

                             Minimum     .      Minimum        Minimum Setback
 Lake Classification         Lot Size        Lot Frontage     from Lakeshore

Natural Environment
  Lake (NE)                80,000 sq.ft.        200 ft.     .      200 ft.

Recreational
  Development .Lake (RD)    40,000 sq.ft.        150 ft.           100 ft.

General Development
  Lake (GD)                20,000 sq.ft.        100 ft.            75 ft.
          Source:  Kandiyohi County Shoreland Management Ordinance
                                      90

-------
5.   CULTURAL RESOURCES

a.   Archaeological Resources

     The Minnesota State  Historical  Society  has  indicated  the  presence
of a number of important  archaeological sites within the Study Area.   It
is  reported  that the area  immediately  to the east  of Green  Lake  was
occupied by  a Sioux  Indian Village led  by  Little Crow,  a  hereditary
chieftain and last of his dynasty.  Remnants of a corn storage hole  are
still to be  seen at this campsite.  Lakotah Sioux bands  established a
great camp  on the north shore  of  Green Lake.  This camp existed for well
over 100 years.  The burial mounds  for the camp were located just south
of the Green  Lake outlet.   This  is  one  of the larger Indian mound com-
plexes in the State of Minnesota.

B:   Historic Resources

     The State Historic Preservation Officer  (SHPO) has identified sites
and buildings of  historic significance in  the Study Area.  However, none
is  listed  on the National Register of Historic  Sites.   The  Green Lake
Village was homesteaded beginning in 1869, with a number of settlements
as well as a  post office,  and grist mill.  One of the first missionary
sites  in  the state was  located  contiguous  to the  Indian camp  on  the
north shore of Green  Lake.

6.   RECREATION

a.   Potential

     One of the  prime attractions of the  Green Lake Area is its recrea-
tional potential.  Major  activities include  boating,  fishing,  camping,
and swimming.   Table  11-17 indicates in relative terms how much use each
lake has received and  the potential  for overuse.

b.   County Parks

     County Park  4.   This  park  is  located  on  the southwest  shore  of
Green Lake  in the community of  Spicer.    This park is  used only during
the day as a  public  beach and picnic area.  It is 8 acres in  size  and
contains picnic tables, bathhouse, beach,  off-street parking, fireplaces
and a well.

     County Park  5.   This  park  is  situated  on  County Road 30  on  the
northeast shore  of Green  Lake.   It  is a  heavily  wooded area with camp-
sites, picnic area and paved roads.

c.   Wildlife Areas

     Several wildlife management areas managed by the Minnesota Depart-
ment of Conservation exist within the Study  Area.   These are listed in
Table 11-18 and  delineated  in  Figure 11-13.  In addition,  three Federal
waterfowl protection  areas exist  near Green Lake.
                                  91

-------
Green

East

Wood

Nest
                                 Table 11-17

                       RECREATIONAL POTENTIAL OF LAKES
                            WITHIN THE STUDY AREA
Name
:n
: Woodcock
lcock

Acres
5,820
150
170
1,020
Shore
Miles
11.2
2.7
3.7
8.1
Crowding
Potential
Negligible
High
High
Low
Relative
Water
Crowding
High
High
Medium
High
            Source:  Kandiyohi County Planning Commission, 1971.
                                 Table 11-18

                       MAJOR WILDLIFE MANAGEMENT AREAS
                            WITHIN THE STUDY AREA
Name of Unit
Dietrich Lange
Ringo Nest
Total
Acres
Owned
1,045
452
1,497
Acres
Projected
448
448
Miles From Town
3 E-NE Spicer
2 NW Spicer

            Source:  Kandiyohi County Planning Commission,  1971.
                                     92

-------
Municipality

Townships of
New London,
Iriving,
Green Lake,
Village of
Spicer

Same as
above
New London
Township

Same as
above
                                 Table 11-19

                        PUBLIC ACCESS TO LAKES IN THE
                            GREEN LAKE STUDY AREA
   Lake
Green Lake
Nest Lake
Shore
Miles
Green Lake    11.2
Same
 as
above

 8.1
Nest Lake     Same
               as
              above
     Facility
    Description
           County Park No. 5 •
           swimming, boating,
           rafting, camping
County Park No. 4 -
swimming, boating,
rafting, diving

Wayside Rest
           Public access point
Approximate
 Shoreline
 Frontage
                          800 ft.
  600 ft.


 1500 ft.


  100 ft,
   Source:  Telephone interview with T. Peterson, 6E Regional Development
            Commission, Willmar, Minnesota, 3/15/78.
                                      93

-------
d.   Public Access

     Public access  to  Green Lake and  Nest Lake is  relatively limited
(see Table 11-19).  Although there is  a total of approximately 23 miles
of  lake  shoreline  in  the Study Area,  less than 3% of  the  lakeshore is
available for public access.
                                  94

-------
                              CHAPTER III

                    DEVELOPMENT OF ALTERNATIVES
A.   INTRODUCTION

1.   GENERAL APPROACH

     New alternative systems for wastewater  collection and  treatment in
the Proposed EIS  Green  Lake  Service  Area  (see Figure  1-4) are. developed
in  this  chapter.   In  Chapter  IV,  the alternatives  are  described and
compared, in  terms  of  cost-effectiveness, with  the Proposed Action in
the  Facilities  Plan Report:   Proposed Green  Lake  Sanitary Sewer and
Water  District  (Rieke   Carroll  Muller  Associates  1976).   Chapter  V
assesses  the  environmental   and  socioeconomic  impacts  of all   these
systems.

     The development of new alternatives  in the EIS  focuses  on  those
aspects and implications of  the proposed  wastewater management plan for
the  Service  Area which  either have  been  identified  as major issues or
concerns, or were not adequately  addressed in the Facilities Plan.  The
high  cost  of  the Facilities  Plan  Proposed Action  and  the potential
impact on area residents make the  cost-effectiveness of proposed facili-
ties a major  concern.   Since  the  collection  system accounts  for approx-
imately 80% of  the  Proposed  Action,  the  extent  of servicing necessary,
along with alternative wastewater  treatment systems and the  use of  newer
technologies for wastewater collection are investigated in  detail.  The
development of  alternative  treatment facilities  has been undertaken by
matching  available  technologies,  both conventional  and  alternative or
innovative,   to  the site  conditions,  such as soil  characteristics and
housing density in the Proposed EIS Service Area.

     Chapter I  of this   EIS  emphasized that  an  important issue is the
overall  need   for  the  project   proposed  in   the  Facilities   Plan.
Documenting a clear need for  new wastewater facilities  requires evidence
that the existing on-lot  systems  are directly  related to water quality
and public health problems.  Such a need is  shown  when  one  or  more of the
following conditions exist:

     •    Standing pools of septic tank effluent or  raw domestic sewage
          in yards  or public  areas where  direct contact with residents
          is likely.

     o    Sewage  in  basements  from  inoperable  or  sluggish  sewage
          disposal systems.

     •    Contaminated   private wells  clearly  associated  with  sewage
          disposal systems.

     The Proposed  EIS  Service Area  exhibits some indirect  evidence of
the unsuitability of site  conditions  for  on-site soil  disposal systems.
The  evidence  includes  high groundwater,  slowly  permeable  soils,  small
                                  95

-------
lot  sizes,  proximity  to lakeshores  and substandard  setback  distances
between wells and  private wastewater facilities.  Available information
on  these  factors  was used  early  in the  preparation of  this  EIS  to
develop the decentralized alternatives  designated EIS Alternatives 3, 4
5, and 6.

     Indirect  evidence   is  insufficient  to  justify  Federal  funding,
however.  Federal  water  pollution  control legislation and regulations
require documentation of  actual water quality or public health problems.
Section  II.C.  summarizes  the  extensive  efforts  mounted during  the
preparation of this  EIS  to document  and  quantify  the  need for improved
facilities around Green Lake.

     The  dollar  cost  of the  Facilities Plan  Proposed Action  and  its
impact  on area residents make cost  effectiveness  an issue equally  as
important as  documentation.    Since  the  collection system  accounts  for
the  major  share   of the construction  costs  in  the  Facilities  Plan
Proposed Action, the extent  that sewers are needed and the use of other
technologies  for wastewater  collection  have been investigated in detail
here,   as   have   alternative  wastewater   treatment  systems.    The
technologies assessed are listed below:
             WASTEWATER MANAGEMENT COMPONENTS AND OPTIONS
Functional Component

Flow and Waste Load
Reduction
Options
     household water conserva-
     tion measures
     ban on phosphorus
     rehabilitation of existing
     sewers to reduce
     infiltration and inflow
Collection of Wastewaters
Wastewater Treatment
Processes
Effluent Disposal
     limited service area
     pressure sewers
     vacuum sewers
     gravity sewers

     conventional centralized
     treatment plus chemical
     treatment to reduce
     phosphorus concentrations
     land application
     on-site treatment
     cluster systems

     subsurface disposal
     land application
     discharge to surface
     waters
                                  96

-------
Sludge Handling                         -    anaerobic digestion
                                            dewatering

Sludge Disposal                         -    land application
                                            landfilling
                                            composting
                                            contract hauling

     Next,  appropriate  options  were  selected  and  combined  into  the
alternative systems that are described  in Chapter IV.  The last section
of Chapter III considers  implementation, administration and financing of
the alternatives.

2.   COMPARABILITY OF  ALTERNATIVES:  DESIGN  POPULATION

     The  various   alternatives  for  wastewater  management  in  the  EIS
Service Area must  provide equivalent  levels of service if their designs
and costs  are  to  be  properly compared.  A design population of 8407 has
been  assumed  (see  Section II.E.I)  in  the  following  evaluation  of
alternatives.   The  design  population  is  that population  projected  to
reside in  the  EIS  Service Area  in the year 2000.   The methodology used
to develop this estimate  is  presented  in Appendix E-l.

     The same year 2000 design population has been used as the basis for
all the EIS alternatives and the  Facilities Plan Proposed Action in the
interest  of equitable comparison;  it  must  be  recognized,  however,  that
each  alternative  carries its own constraints  and that  the  wastewater
management system chosen may itself be  a significant determinent of the
EIS Service Area's actual population  in  the year 2000.
3.   COMPARABILITY OF ALTERNATIVES:   FLOW AND WASTE
     LOAD  PROJECTIONS

     Design  flows  for  centralized  treatment  facilities  and  for  the
cluster systems are based  on a  design  domestic sewage flow of 60 gallons
per  capita  per day  (gpcd)  in  residential  areas  for both permanent and
seasonal residents.  Infiltration and inflow* (I/I) into gravity sewers
was  added  to  the  calculated sewage  flow  in  appropriate alternatives.
These data  are summarized  in Table  I1I-1.

     The design flow  used  in the  Facilities Plan for the Proposed Action
ranged  from  15-190 gpcd,  including  I/I.   To  compare  costs  properly in
this  EIS,   flows  developed  for  the EIS  alternatives were   used  to
re-calculate flows  for  the Proposed  Action.

     The  domestic   sewage  generation  rate  depends  upon   the  mix  of
residential,'commercial, and institutional  sources in the area.  Studies
on  residential  water usage   (Witt,  Siegrist,  and  Boyle  1974;  Bailey et
al.  1969;  Cohen and Wallman  1976)  reported  individual  household water
consumptions varying widely between 20  and 100 gpcd.  However,  averaged
values  reported  in those studies  generally  ranged  between  40-56 gpcd.
On  a  community-wide  basis,  non-residential domestic (commercial, small
                                  97

-------
                                                 Table III-l

                                         GREEN  LAKE  EIS  SERVICE AREA
                                   DESIGN POPULATION AND FLOW (YEAR 2000)
New London Area

Nest Lake Area
(eastern half Nest Lake)

Spicer Area
(Spicer Village, west
 shore Green Lake)

Green Lake Area
(remainder Green Lake)
   TOTAL
POPULATION

   1282

 .  1542


   1913
   3670
   WINTER
POPULATION

   1116

    686


   1504
   1787
 TOTAL
FLOW (MGD)

 .077

 .092


 .114
 .221
  WINTER
FLOW (MGD)

  .067

  .041


  .091
                                                   .108
                                                                            oo
INFILTRATION
                                 .504
                                 .038
                                   .307
                                   .038
      TOTAL
   8407
                                                     5073
                 .542
                   .345

-------
industrial,  and  institutional) water  use increases  per  capita flows.
The extents of such increases are  influenced by:

     •    the importance of the community  as a  local or regional trading
          center;

     •    the  concentration  of  such  water-intensive institutions  as
          schools  and hospitals; and

     •    the level of small industrial  development.

For  communities  with populations  of less than  5,000,  EPA regulations
allow design  flows in  the  range  of 60  to 70 gpcd  where existing per
capita  flow  data  is  not  available.   In  larger communities,  and  in
communities within Standard Metropolitan  Statistical  Areas, the maximum
allowable flow ranges up to 85 gpcd.

     Water  consumption   by  seasonal   users   varies   much  more  than
consumption  by  permanent  residents.   The actual  rates  of consumption
depend upon such factors  as type  of  accommodations in the area and type
of recreation areas  available.  EPA  regulations  (EPA  1978) suggest that
seasonal population can be  converted to equivalent permanent population
by using the following multipliers:

          Day-use  visitor     0.1  to  0.2

          Seasonal  visitor    0.5  to  0.8

     A  multiplier  of  1.0   was   applied to  the  projected  seasonal
population  to  account  for  both  day-use   and  seasonal  visitors.
Considering   the   possible   error   in  projecting   future   seasonal
populations,  the   preponderance   of  present   seasonal  visitors  using
well-equipped  private  dwellings   and   the  lack  of  data  on  day-use
visitors,  this  multiplier  was  thought conservative  i.e.,  it probably
overestimates flows to some degree.

     The design flow figure  of 60 gpcd  does  not reflect reductions in
flow  from   a  program   of   water  conservation.    Residential  water
conservation devices, discussed in Section III.B.l.a,  could reduce flows
by 16 gpcd.   Later in this chapter,  to demonstrate probable impacts of
such  reduction  in  flow,  the  Facilities  Plan   Proposed Action  has  been
redesigned and recosted.
B.   COMPONENTS  AND  OPTIONS

1.   FLOW AND WASTE  REDUCTION

a.   Residential Flow Reduction Devices

     A variety of devices which reduce  water  consumption and sewage flow
are available.  A  list of some of the devices is presented in Appendix
F-l with  data on  their water saving potential  and costs.  Most of these
devices will  require no  change in the  user's hygienic habits and are as
                                  99

-------
maintenance-free as standard fixtures.  Others, such as compost toilets,
may  require  changes in hygiene practices  and/or  increased maintenance.
The  use  of any  of  these  devices  may be justified  under  certain condi-
tions , for instance when no other device can provide adequate sanitation
or  when  excessive   flows  cause  malfunctions  of  conventional  on-site
septic  systems.   In  most  cases,  however,  the justifications  for flow
reduction devices are economic.

     Table  III-2 presents  a  list of proven  flow reduction devices and
homeowner's  savings  resulting from  their  use  locally.   Data  on the
devices listed in Appendix F-2 and local cost assumptions listed beneath
the table were used to develop these estimates.  The homeowner's savings
include   savings  for  water  supply,  water  heating  and  wastewater
treatment.   With a  combination  of shower  flow  control  insert device,
dual  cycle  toilet and  lavatory  faucet flow  control  device  the annual
savings would be approximately $80 per year.

     If all  residences  in  the Proposed EIS Service Area were to install
these  flow  reduction devices,  they could  not all  save  the $1.40/1000
gallons  in  wastewater treatment costs  (see  assumption in Table III-2).
This is due to the fact that a substatial portion of this charge goes to
pay  off  capital, operation and maintenance costs which will remain con-'-
stant  even  if flow is reduced.  For everyone to benefit fully from flow
reduction then  wastewater  collection,  treatment and disposal facilities
would  have  to be  designed with flow capacities  that  reflect the lower
sewage flows.   Use  of the three  types  of  devices cited above would re-
duce per capita  sewage flows by approximately  16 gpcd.  To calculate the
cost-effectiveness of community-wide flow reduction, the Facilities Plan
Proposed Action  (see Section IV.B.2) was redesigned and recosted using a
design flow based on 44 gpcd instead of 60 gpcd.

     The  estimated  savings   in  project  capital  cost (1980)  would  be
$1,245,000  and  the  operation and  maintenance  cost  savings  would be ap-
proximately  $8,000 per  year.  To  achieve this  savings,  approximately
$9,000  worth of  flow  reduction devices would be necessary.  The total
present  worth*  of  savings   over  the  20-year design period  would  be
$1,126,000 or 13% of the Facilities Plan Proposed Action.

     These  economic  analyses  of homeowner's, saving  and  total present
worth  reduction assumed all  dwellings  would  be  sewered.   However, for
dwellings which  continue to use on-site systems the economic benefits of
flow  reduction  devices cannot  be readily  estimated.   State regulatory
agencies  generally   do   not  allow  a  reduction   in  the  design  of
conventional  on-site  systems  based  upon proposals to  use flow reduction
devices.  However, it is likely that reduced  flows will prolong the life
of soil adsorption systems there by saving money  in the long run.

     With  some  decentralized technologies,  substantial  reductions  in
flow   may   be  required  regardless  of  costs.   Holding  tanks,  soil
adsorption    systems   which   cannot   be   enlarged,   evaporation   or
evapotranspiration  systems and sand mounds are examples of technologies
which  would  operate with less risk of malfunction if  sewage flows could
be  reduced  to the minimum.  Sewage flows  on the  order of 15 to 30 gpcd
can  be  achieved  by  installation  of  combinations  of  the  following
devices:

                                  100

-------
                               Table III-2

            ESTIMATED SAVINGS WITH FLOW REDUCTION DEVICES
Shower flow control insert device
Dual cycle toilet3
Toilet damming device
Shallow trap toilet8
Dual flush adapter for toilets
Spray tap faucet .
Improved ballcock assembly for toilets
Faucet flow control device
Faucet aerator
First Year
Savings
(or Cost)
$41.29
7.96
10.72
8.97
7.64
(65.33)
4.35
5.14
0.89
Annual Savings
After First
Year
$43.29
2.7 . 96
13.97
13.97
11.64
11.87
7.35
8.14
3.39
o
  First year expenditure assumed to be difference in capital cost between
  flow-saving toilet and a standard toilet costing $75.
Assumptions
Household:  Four persons occupying dwelling 328 days per year.   One bathroom
            in dwelling.

Water Cost: Private well water supply.  Cost of water = $0.02/1000 gallons
            for electricity to pump against a 100 foot hydraulic head.

Water Heat- Electric water heater.  Water temperature increase = 100 F.
ing Cost:   Electricity costs $0.03/kilowatt-hour.  Cost of water heating =
            $7.50/100 gallons.

Wastewater  Assumed that water supply is metered and sewage bill is based on
Cost:       water supply at a constant rate of $1.40/1000 gallons.  Rate is
            based on a 1980 Study Area sewage flow of 0.5 mgd and local costs
            of $254,000 in 1980 for the Facilities Plan Proposed Action as
            estimated in this EIS.
                                     101

-------
     o    Reduce lavatory water  usage  by installing spray tap  faucets.

     Ł>    Replace standard toilets with  dual  cycle or other low  volume
          toilets.

     o    Reduce shower  water  use  by  installing  thermostatic  mixing
          valves and flow control  shower heads.   Use of showers  rather
          than baths should  be encouraged whenever  possible.

     o    Replace older  clothes washing machines  with  those  equipped
          with  water-level   controls  or  with  front-loading machines.

     o    Eliminate  water-carried toilet wastes by  use of  in-house  com-
          posting toilets.

     ©    Recycle bath and  laundry  wastewaters   for  toilet flushing.
          Filtering  and disinfection  of bath and laundry  wastes  for  this
          purpose  has   been  shown  to   be  feasible  and  aesthetically
          acceptable   in  pilot  studies   (Cohen   and   Wallman   1974;
          McLaughlin   1968).    This   is  an  alternative  to   in-house
          composting  toilets  that  could  achieve  the  same  level  of
          wastewater flow reduction.

     o    Recycle bath  and  laundry wastewaters for lawn  sprinkling  in
          summer.   The feasibility  of  this  method  would  have  to  be
          evaluated   on a trial  basis  in  the  Study Area  because  its
          general applicability is  not  certain.

     e    Commercially available  pressurized toilets  and air-assisted
          shower heads using a common air compressor of small horsepower
          would  reduce  sewage volume  from  these  two largest household
          sources up to 90%.

b.   Minnesota Ban on Phosphorus

     Phosphorus  is  frequently the  nutrient controlling  algae growth  in
surface waters and is therefore an  important influence on lake or  stream
eutrophication.  Enrichment of  the waters  with  nutrients encourages the
growth of  algae and other  microscopic plant life; decay of the  plants
increases biochemical  oxygen  demand, decreasing dissolved  oxygen  in the
water.   Addition of nutrients  encourages  higher  forms  of plant  life,
thereby hastening the  aging  process  by which a lake  evolves into a bog
or  marsh.   Normally,  eutrophication  is a  natural process proceeding
slowly over thousands of years.   Human  activity  however,  can greatly
accelerate  it.   Phosphorus  and other nutrients, contributed to surface
waters by  human wastes,  laundry  detergents and   agricultural runoff,
often  result  in over-fertilization,  over-productivity of  plant matter,
and  "choking"   of  a body  of water  within a few  years.  Appendix  C-4
discuss  the process and data  pertinent for the Green Lake  Study Area.

     In  1977 the Minnesota  legislature limited  the amount  of phosphorus
in  laundry  and  cleaning  supplies  sold  in the state to 0.5%.  Presently,
there  is no  enforcement  of  this  law because an injunction has  been
issued as a result of a lawsuit.
                                  102

-------
     The  Minnesota  Pollution  Control  Agency  estimates  that  for the
Minneapolis-St.  Paul area  (where  a  local  phosphorus ban is  in effect) a
35%  reduction  in  phosphorus  loading in  raw  wastewater  effluent has
resulted.  The Twin Cities  have  experienced  a 1.1 pound per capita per
year  reduction  in  phosphorus  loading  from 1971 to 1974 (by telephone,
Craig Affeldt, MPCA,  April, 1978).

     Treatment plants and  on-site disposal  facilities  in the Study Area
could  experience  a   similar  reduction  in   phosphorus  concentration.
However,  such  characteristics  of the  Green  Lake  area  as  the number of
residential laundry facilities may  differ  from  those in the communities
where data were  collected.   Clearly,  the  extent of phosphorus" reduction
can only  be determined  by  a survey of the characteristics  of the Study
Area.   One  approach  to  the  reduction  of  phosphorus  is to  require that
household detergents  be free of phosphates.

     Reduction of phosphorus by  control of detergents  will not  achieve
the effluent discharge  limits  of  1  mg/1 (see Appendix G-l  for Effluent
Limits)   for    discharges   to   area   lakes   or   their    tributaries.
Consequently,  facilities for phosphorus removal  is  required  in treatment
plants which discharge  to  any  of the surface water bodies  in the Study
Area except for  the Middle Fork of the Crow  River below Green Lake.  A
phosphorus ban would  result in  an unquantifiable reduction in phsophorus
entering surface waters with septic  tank leachate.

c.   Rehabilitation  of Existing Sewers  To Reduce Infiltration
     and  Inflow

     Infiltration/Inflow Analyses conducted in New London and Spicer for
the Facilities  Plan  revealed that infiltration  was substantial  in both
sewer systems  and that combined sewers in  New London receive significant
inflow.  Sewer system evaluation surveys (SSES), were recommended in the
Facilities Plan and were performed in May  1978.  The costs and projected
flow reduction for  the rehabilitation effort  are incorporated in  all EIS
Alternatives except No Action.

2.   COLLECTION

     The collection system proposed  in the Facilities   Plan  is estimated
to cost  $6.4  million  -- 80% of the  total  cost of  the Proposed Action --
and  is  the single most expensive portion of the sewerage facilities.
Since not  all parts  of collection systems are  eligible for Federal and
State funding,  the costs of the collection system can affect the  local
community  more  than  other  components  of   the   project.   There  is,
therefore, considerable incentive at local,  state  and national levels to
choose less expensive alternatives to conventional sewer systems.

     Alternative means of wastewater collection  are:

     •    pressure  sewers  (including  grinder pumps or  STEP (systems);

     •    vacuum sewers; and

     •    small diameter gravity sewers (Troyan  and Norris  1974).
                                  103

-------
     An alternative collection  system  may economically sewer areas with
site conditions that increase the cost of conventional sewerage, such as
shallow  depth to  bedrock,   high  groundwater  table,  or  hilly terrain.
Housing  density  also  affects  the  relative  costs  of  conventional  and
alternative wastewater collection techniques.

     The  alternative  most  extensively  studied  is  collection  by  a
pressure  sewer system.   The  principles  behind  the  pressure system and
the  gravity  flow system  are opposite to each other.   The  water system
consists  of  a single  point of  pressurization  and a  number  of  user
outlets.   Conversely,  the  pressure sewer  system  has  inlet  points  of
pressurization and a single outlet.  Pressurized wastewater is generally
discharged to the treatment facility or to a gravity sewer.

     The  two  major  types  of pressure sewer systems are the grinder pump
(GP)  system  and the  septic tank  effluent  pumping  (STEP)  system.   The
differences between  the two  systems  are in  the on-site equipment  and
layout.   The  GP system  employs individual grinder  pumps to convey raw
wastewater to  the  sewer.   In the STEP system septic tank effluent from
individual households is pumped to the pressure main.

     The advantages of pressure sewer systems are:

     o    elimination of infiltration/inflow;
     o    reduction of construction cost; and
     o    use  in varied site and climatic conditions.

The  disadvantages  include   relatively high  operation and  maintenance
cost,  and the requirement  for  individual home  STEP systems or grinder
pumps.

     Vacuum  sewers  provide  similar advantages.   Their  major components
are vacuum mains, collection tanks and vacuum pumps, and individual home
valve  connection systems.   A recent review  of vacuum sewer technology,
however,  noted significant  differences among design of four major types
of current systems (Cooper and Rezek 1975).

     As   a  third  alternative  to  conventional  gravity  sewers,  small
diameter  (4-inch)  pipe  can be used if septic tank effluent, rather than
raw  waste,  is  collected.    Such  pipe  may  result  in  lower  costs  of
materials, but the systems  retain some  of  the  disadvantages of larger
sewers.   The  need  for deep excavations and pump stations is unaffected.

     This  document  analyzed the   reliability,  site requirements,  and
costs  of the  alternative  sewer systems  considered  for the  Green Lake
area.   The  STEP-type  low-pressure sewer  system  was  found  the  most
advantageous  of  the  three  alternatives.   A  preliminary  STEP system
serving   residents  around  .Green  Lake  was,  therefore,  developed  to
determine  the differences  in project costs  if  it  were substituted for
the  gravity system specified by the Facilities Plan.  The arrangement of
the  STEP system house pump and  sewer  line  connection is illustrated in
Figure III-l.
                                  104

-------
                                         CONTROL PANEL
                                         8 ALARM LIGHT
                                                 LEVEL SENSOR
                                                 ON OFF LEVEL
                                                         /-PRESSURE SEWER/
                                                         L	^^      \ COMMON
                                                                      TRENCH
                                                           FORCE MAIN
EXISTING GRAVITY
SEWVGT PIPING

EXISTING SEPTIC TANK
                                                TANK UNIT
             TYPICAL  PUMP  INSTALLATION  FOR PRESSURE SEWER
                             Figure  III-l
3.   WASTEWATER TREATMENT

     Wastewater treatment options  include three categories:  centralized
treatment  prior  to discharge  into surface water;  centralized treatment
prior to disposal on  land;  and  decentralized  treatment.

     "Centralized  treatment" refers  to  treatment  at  a  central site of
wastewater  collected by  a  single  system and  transported to  a central
location.   Centralized treatment systems  may serve all or a part of  the
service  area.   Centrally treated  effluent may be  discharged to surface
waters  or  applied  to the  land; the  method and  site  of disposal affect
the treatment process requirements.

     "Decentralized  treatment"  defines   those   systems  processing  a
relatively  small amount  of wastewater.   Decentralized treatment can be
provided  on-site or  off-site.   Typically,  effluent  disposal occurs in

                                   105

-------
close proximity to  the  source  of sewage elimiating the need  for costly
transmission of sewage to distant disposal  sites.

     A major purpose of this EIS is to assess  the  technical  feasibility,
relative costs, environmental impacts, and  implementation  problems asso-
ciated with these three  approaches to wastewater  treatment in the  pro-
posed Green Lake EIS Service Area.

a.    Centralized   Treatment —  Discharge  to  Surface   Waters

     The Middle Fork of the Crow River, east of Green  Lake,  was selected
by the Facilities Plan  as the  point of disposal for treated wastewater.
The  Facilities Plan  evaluated two  options for centralized  treatment:
wastewater   stabilization  lagoons,   which  would  permit   controlled
discharge of treated  wastewater;  and a mechanical  oxidation ditch which
would allow for continual discharge.

     Four methods of  centralized  treatment  involving  effluent discharge
to surface  water were  developed  for the new alternatives  in this  EIS,
including a waste stabilization lagoon, a mechanical oxidation ditch,  an
extended  aeration  treatment plant  and  an activated  sludge  plant.   A
rapid  infiltration  system,  which   involves the discharge  of recovered
wastewater to the Middle Fork of the Crow River, is discussed  in  Section
III.3.b.  All  methods of treatment, which  are  briefly described below,
were designed to comply with MPCA's current effluent standards listed  in
Appendix G-l.

     The  first centralized  treatment scheme  for  the new  alternatives
consists  of a  0.59 mgd  stabilization  lagoon facility with  controlled
effluent discharge  to the Middle Fork of the  Crow  River.   The facility
involves a  dual or  parallel system of ponds operating in  series which
allow  for   the  shutting  down  of  one side during  the  low flow winter
months.  The  ponds  will  require an  area of 75 acres  located at a  site
east of Green Lake.

     The  treatment  process  is  identical  to that   proposed   in the
Facilities  Plan.  A  flow  diagram  of this  plant is presented in Figure
III-2.  The "preliminary treatment" component shown in the diagram simply
involves the removal of coarse  solids.
RAW
WASTEWATER
PRELIMINARY
TREATMENT


STABILIZATION
POND


CKLORINATION
                                                         PERIODIC
                                                       _ DISCHARGE  M|OOLE FO(JK
                                                                 CROW RIVER
                          STABILIZATION POND
                        CONTROLLED DISCHARGE
                             Figure III-2
                                  106

-------
     The  second  centralized treatment  method  considered  for the  EIS
Service Area  includes a 0.59 mgd  mechanical oxidation ditch  plant with
continuous discharge  to the Middle Fork  of  the  Crow River east of Green
Lake.  The  treatment  process  is  identical to  that  proposed  in  the
Facilities  Plan.   Tertiary filtration is  included  in  this  process  to
provide  sufficient  removal of  organic  substances  (BOD,, and suspended
solids)  in compliance with  MPCA effluent  quality  standards.  A flow
diagram   of   this  plant   is   illustrated   in  Figure   III-3.    Again,
preliminary treatment  involves  the removal of  coarse solids.
RAW
PF
T
WASTEWATER
1ELIMINARY
REATMENT



OXIDATION
DITCH

                                                                     DISCHARGE TO
                                                                     MIDDLE  FORK
                                                                     CROW  RIVER
                                             t
                                           SLUDGE
                                           HAULING
                    OXIDATION DITCH WITH FILTRATION
                             Figure  III-3
                                   107

-------
       The  third method  of  centralized treatment  evaluated in the  deve-
  lopment  of new  alternatives  in this EIS involved  the upgrading of  the
  Village  of New London's  wastewater treatment plant.   The  existing  plant
  has   sufficient  capacity  to  meet  the  design  flow  but  only  provides
  primary  treatment.  The  upgraded plant  (0.10 mgd) will provide  tertiary
  treatment  of wastewater  and  consists of a conventional activated sludge
  process,  chemical  addition for  phosphorus  removal  and filtration (see
  Figure  III-4).
RAW
WASTEWATER
                                                                 CHLORINATION
    [DISCHARGE
    I TO MIDDLE
	1 FORK CROW
       RIVER
              LEGEND

             EXISTING
             PROPOSED ADDITIONS
                                             SLUDGE
                                            HAULING
                               PROPOSED UPGRADE OF
                               NEW LONDON PLANT
                               Figure III-4
       The fourth method  of centralized treatment  that  was  developed as a
  component  of  one  of the new  alternatives  involved  the  upgrading  of
  Spicer's secondary  treatment plant.   The  existing  plant does  not have
  sufficient capacity  to  meet the design flow.  Enlargement of the Spicer
  plant  to  design  flow  capacity required  the preliminary design of  a
  parallel plant.   The capacity of the parallet plant  (0.054 mgd)  is equal
  to the difference between the capacity of the existing plant  (0.086 mgd)
                                    108

-------
design flow  (0.14 mgd).  The  parallel plant was designed as  a prefabri-
cated  extended  aeration plant  with  filtration and  phosphorus  removal
(see Figure III-5).
             PRELIMINARY
              TREATMENT
                                 j  a POLYMER
                                  -~	J
                                                               LEGEND

                                                          	 EXISTING
                                                          	PROPOSED ADDITIONS
                                                        FILTRATION
                                                          n
                                                     CHLORINATION
                                  PREFABRICATED
	H EXTENDED AERATION  I	
           PLANT     |
      L—T	'
                                                                 DISCHARGE TO
                                                                  WOODCOCK
                                                                    LAKE
                                    SLUDGE
                                   HAULING
                    PROPOSED UPGRADE AND ENLARGEMENT
                              OF SPICER PLANT
                              Figure III-5
b.   Centralized  Treatment —  Land Disposal

     Land  treatment of municipal  wastewater  involves  the use of  plants
and the  soil to remove many wastewater constituents.  A  wide  variety of
processes can be used  to  achieve many different objectives of  treatment,
water  reuse,   nutrient  recycling,   and  crop  production.   The   three
principal types of  land application systems are:

     1.   Slow  rate (irrigation)
     2.   Rapid infiltration (infiltration-percolation)
     3.   Overland  flow  (EPA 1977).
                                   109

-------
     The  effluent  quality  required  for  land  application in  terms  of
organic  content  (BOD and  suspended solids) is not as  critical as with
stream  discharge  options.   Pretreatment  of  wastewaters  is  necessary,
however,  to  prevent nuisance  conditions,  insure  a  higher  level  of
constituent  removal  through the soil, reduce  soil  clogging,  and insure
reliable   operation   of   the   distribution  system.    Generally,   the
equivalent  of  secondary treatment  of wastewaters  is  required  prior  to
land  application.  (Great Lakes Upper Mississippi  River  Board  of State
Sanitary Engineers 1971).

     Storage  of  wastewater is  necessary  with  land application systems
for  nonoperating  periods  and periods   of  reduced  application  rates
resulting  from  climatic  constraints.   In  Minnesota  land  application
systems  must have storage  facilities for  holding  wastewaters  over the
winter months.

     A  recent  memorandum  from  EPA  may  alter  the   requirements  for
pretreatment  prior   to   land   application.   To  encourage  both  land
treatment  and  land   disposal  of  wastewater,  EPA  has  indicated  that:

     "A universal minimum of secondary treatment for direct surface
     discharge...will  not be accepted  because it  is  inconsistent
     with the basic concepts of land treatment.

      ...the  costs  of  the  additional  pre-application  increment
     needed   to  meet  more  stringent  pre-application  treatment
     requirements  [than  necessary] imposed  at the State or local
     level would be ineligible for Agency funding and thus would be
     paid for from State or local funds."   (EPA 1978)

     The  EPA  policy  has   important  ramifications  for  land treatment
alternatives.  By  allowing Federal funding of land used  for storage and
underwriting  the  risk of failure  for  certain  land-related projects the
policy promotes their consideration.

     The Facilities Plan (August 16, 1976) did not develop a land appli-
cation  system for  the proposed  Service  Area.   In this EIS,  both the
spray irrigation and  rapid  infiltration methods of land application were
evaluated  as  treatment  options  for  the EIS  Service  Area.  These are
described below.

     Spray  irrigation.  The 0.24 mgd spray irrigation facility evaluated
in  one  of  the new  alternatives  for  this  EIS consists  of preliminary
treatment (bar screen, comminator, primary settling basin), a stabiliza-
tion pond,  and a chlorination process to disinfect the effluent prior to
its  application  on  cropland.   The  treatment  plant  component  would
provide  secondary  treatment prior to spray irrigation as recommended by
the  MPCA (MPCA  1972).   An application  rate of  2  inches per  week was
determined  after  calculating the  nitrogen loading rate and  found that
there would be no need for tinder-drainage at this rate.  Higher loading
rates may produce  poor crop growth.  Alfalfa  was the chosen cover crop
over  corn  since  alfalfa   allows  a  higher application  rate  with its
growing  season limited  solely by climatic  factors.    The pond system
                                   110

-------
shall have a  storage  period of 210 days.
is illustrated in Figure III-6.
A flow diagram  of  this plant
                                                                SPRAY
                                                                IRRIGATION

RAW
WASTE
WATER

NARY
TREAT-
MENT








                             LAND  APPLICATION
                             SPRAY  IRRIGATION
                             Figure III-6
     Rapid Infiltration.  The  rapid  infiltration method  of  land treat-
ment is evaluated  in two of the new  wastewater  management alternatives
(0.34 mgd and  0.24 mgd).   Rapid infiltration of wastewater was selected
for further  investigation  as  a component option, because it usually re-
quires  less  area  for  operation  as  compared  to  spray  irrigation.
Furthermore,  as  a  result  of  reduced  land  requirements  the  site  can
usually  be   located  closer  to wastewater  transportation lines,  thus,
reducing capital, operation and maintenance costs of interceptors and/or
force mains.

     After land  application the  renovated wastewater will be drawn from
recovery wells (see Figure III-7) and discharged into the Middle Fork of
                    RECOVERY OF RENOVATED HATER 8V WELLS
                             Figure III-7
                                  111

-------
the  Crow  River  above  Nest  Lake.   Consideration in  selection of  the
method of  land application and a  potential  site are  discussed  in  the
section  on  disposal  options.   A  flow  diagram  of  this  plant   is
illustrated in Figure III-8.
RAW .
WASTE
WATER

PRELIMI-
NARY
TREAT-
MENT


•t>

STABILIZATION POND




CHLORINATION



1

RAPID
NFILT

RATIOI

BASINS
1
RECOVERY
OX TO
•a
/ MIDDLE FORK
/r CROW RIVER
"WELLS
                              LAND  APPLICATION
                              RAPID  INFILTRATION
                             Figure III-8


c.   Decentralized Treatment and Disposal

     A number of technologies are available which can provide decentral-
ized  treatment  either  on-site  or  at  sites near  the point  of  sewage
generation.  Disposal of treatment wastewaters can be to  the  air,  soil
or surface waters and normally  occurs near the treatment site.  Some of
the available technologies  are:

     o    Alternative toilets:

               Composting toilets

               Toilets  using  filtered and  disinfected bath and laundry
               wastewater

               Waterless toilets using  oils  to carry and  store  wastes

               Incineration toilets

     o    On-lot treatment  and disposal:

               Septic tank  and soil absorption systems (ST/SAS)

               Septic tank  and  dual, alternating soil  disposal  system

               Aerobic  treatment and  soil disposal system

               Septic tank  or  aerobic  treatment  and sand  filter  with
               effluent  discharge to  surface waters

               Septic tank  and evapotranspiration system
                                  112

-------
               Septic tank and mechanical evaporation system

               Septic tank and sand mound system

               Rejuvenation  of  soil   disposal   fields   with  hydrogen
               peroxide (H?0~) treatments

     •    Off-lot Treatment and Disposal:

               Holding tanks

               Cluster systems  (multiple  houses  served by a common soil
               disposal system)

               Community  septic  tank  or  aerobic  treatment  and  sand
               filter with effluent discharge to surface water

               Small  scale  lagoon with  seasonal effluent  discharge  to
               surface waters

               Small  scale  lagoon  with  effluent  discharge  at  rapid
               infiltration land application site

               Small  scale  lagoon with  seasonal effluent  discharge  at
               slow rate land application site

               Small  scale,  preconstructed  activated sludge  (package)
               treatment  plants  with  effluent  discharge  to  surface
               waters.

     Because all of  the  developed  portions of the Study Area are tribu-
tary  to  lakes,  decentralized  technologies  which discharge  to  surface
waters are  not  further considered  here.  All of the remaining technolo-
gies,  used  alone   or  in  combination  with  each  other  or  with  flow
reduction  devices,  could  be useful in  individual situations  within the
Study  Area.   It  is  expected  that,   technologies   selected  for  each
dwelling will be appropriate  to the problem being  remedied (or  lack of
problem) to the soil  and  groundwater site  characteristics,  and  to the
expected use of the systems.

     Lacking necessary information to select appropriate technologies on
a  site-by-site  basis,  this EIS assumes that the  best known and  most
reliable  decentralized technologies  will  be  used.   Continued  use  of
on-site  septic  tanks  and  soil absorption systems  is  the  technology of
choice  where acceptable  public health and  environmental impacts  are
attainable  with them.  Where  on-site systems (including alternatives to
ST/SAS)  are not  economically, environmentally  or  otherwise feasible,
cluster  systems are  assumed to be used.  The assumption that only these
two  technologies  will be used  is  made  here to  form  the basis  for cost
and   feasibility   estimates  and   is   not  meant   to  preclude  other
technologies for  any  site(s).  Estimates of their  frequency of repair
and construction are conservative to reflect the possibility that other,
more appropriate technologies may be more expensive.
                                  113

-------
     Continued  use  of  septic  tank-soil  absorption  systems for  most
dwellings  in  the  Proposed EIS Service Area would  perpetuate violations
of Minnesota's Shoreline  Management  Act  as discussed in Section II.C.3.
However, the  substantial amount  of  field investigation  undertaken for
this EIS  has  indicated  that  most existing  systems are  operating  with
acceptable environmental  and  public  health impacts.  More detailed site
investigations  may  indicate  that  renovation  or  replacement of  some
existing on-site  systems  is  necessary.   To estimate the investment this
might  require,   it  is assumed  that  50% of  on-site  systems will  be
replaced with new septic tanks and soil absorption systems.

     Detailed  site   evaluations  may  show   for  some  dwellings  that
continued .use of  on-site systems  is not  feasible  or that repairs for a
number  of  dwellings  is  more expensive  than  joint  disposal.   Cluster
systems  are  subsurface  absorption  systems  similar  in  operation  and
design  to  on-site  soil  absorption  systems  but  are  large  enough  to
accommodate  flows  from  a  number  of  (approximately  20)  dwellings.
Because  of the  need  to collect  and  transport wastes,  cluster  systems
include  limited  collection  facilities   using pressure   sewers,  small
diameter  sewers  and/or  pumps  and  force mains.    Generally,  existing
septic tanks would continue to be used for settling and stabilization of
wastewater.

     An  analysis  of  soil  conditions  at 13 sites  around  Green Lake was
conducted  in  October 1978 by the Soil Conservation Service, St.  Peters,
Minnesota.  With the  exception of one site south of the lake, 50 to 100%
of each site had only  slight  or moderate limitations for subsurface dis-
posal of  septic  tank effluent.   The size and distribution of apparently
suitable sites is such that any portion of Green Lake shoreline could be
served  by  cluster systems  if necessary.   Before use of  sites for this
purpose,   additional  analysis  of  soils  and   groundwater  would  be
necessary.  The  locations of sites  investigated by the  SCS as  well as
cluster  system  sites  considered  in  preparation of  the Facilities Plan
are  illustrated  in Figure  III-9.  The results of  the  October 1978 SCS
investigations are presented  in Appendix A-l.

     The exact number  and locations of dwellings requiring off-site dis-
posal  of  wastewater  would be  determined after detailed  evaluation of
existing systems are  estimated to be abandoned.

     The cost for cluster systems were developed based on the design of
a "typical" cluster system serving approximately 20 residences along the
shoreline  of Green Lake and Nest Lake.  The costs include a 50% replace-
ment of  septic  tanks.  The total cost for cluster systems to serve 25%
of existing residences was then based on the cost per residence from the
typical cluster system design.  Design assumptions for this cluster sys-
tem  design appear  in  Appendix H-l.  Design  criteria for  the  cluster
systems  recommended  by the  State  of Minnesota  was considered  in the
development of  the typical cluster system design.  Presently, there are
a number of successfully operating cluster systems in Otter Tail County,
Minnesota  (by  letter,  Larry Krohn,  Department  of  Land  and Resource
Management, Otter Tail County, October 18, 1978.
                                  114

-------
                                                       FIGURE III-9

CKHT
              "«IO««L |  NEW LONDON1  \f^:
                                  MIDDLE FORK
                                  CKO»  RIVER
               -~™ M&.<~  ,irj/';'-;'
              "si »«rc«E»y   /•'.'-• lr >1 : "
                       '": J ^
L
     IS'
    -'COO    4ry»
                ''
               rJ  \LAXE

               "~ /
                                           GREEN  LAKE
M*  WOODCOCK;
   _XtxWf
                              LOCATION OF POTENTIAL CLUSTER SYSTEMS IN THE
                                        GREEN LAKE  STUDY AREA


                                            LEGEND

                             LOCATION  OF  POTENTIAL CLUSTER SYSTEM SITE
                                 IDENTIFIED  IN THE PREPARATION OF THE
                                 FACILITIES  PLAN
                         M* POTENTIAL CLUSTER SYSTEM SITE  MAPPED BY THF
                                 SOIL CONSERVATION SERVICE  (OCTOBER 1978)
                                                                               (Source:   Attachment  No.  1, Green  Lake
                                                                                Sanitary Sewer and Water District,  File
                                                                                No.  741001-2]
                                                                    H

-------
4.   EFFLUENT DISPOSAL

     Three approaches exist  for  disposal  of treated wastewater.   Reuse,
perhaps the most desirable of the three,  implies  recycling of the  efflu-
ent by  industry,  agriculture or  groundwater recharge.   Land application
takes advantage of  the  absorptive and renovative capacities of soil  to
improve effluent quality and reduce the quantity  of  wastewater requiring
disposal.   Discharge to  surface  water  generally  implies  the  use  of
streams  or  impoundments  for  ultimate  disposal of treated  effluent.
a.
Reuse
     Industry Reuse.  There  is  no  industrial  development in the  Study
Area, consequently industrial reuse does not seem to be a  feasible  means
of effluent disposal.
     Agricultural Irrigation.   The  use  of   treated
irrigation is addressed in Section III.B.4.6.
                                                   wastewaters  for
     Groundwater Recharge.   Groundwater  supplies  all  of  the  potable
water in  the  EIS Service Area.  The availability of  ample quantities  of
water from  sand and  gravel  deposits is  a  significant resource of the
area.  There  is  no evidence  that these resources are  being  depleted  to
the extent that supplemental  recharge is necessary.   Wastewater reuse  by
groundwater recharge has therefore not been  evaluated.

b.   Discharge to Surface Waters
          i
     This EIS evaluates surface water discharge of treated wastewater  at
several locations in the Green Lake Study Area, as listed  below:
Treatment Method

Waste stabilization pond


Mechanical oxidation ditch


Rapid infiltration, with reno-
vated wastewater collected

Conventional activated sludge


Extended aeration
                              Potential Location of Surface
                              	Water Discharge	

                              Middle Fork of the Crow River
                              below Lake Calhoun

                              Middle Fork of the Crow River
                              below Lake Calhoun

                              Middle Fork of the Crow River
                              above Nest Lake

                              Middle Fork of the Crow River
                              above Nest Lake

                              Woodcock Lake
     Effluent  quality  limitations  promulgated by the MPCA and EPA  will
govern  the feasibility of implementing any of  the  wastewater  treatment
components  listed  above.    Concern  over  low dissolved  oxygen  due  to
                                  116

-------
organic loading  (BOD,,  and  Total  Suspended Solids [TSS]) of  streams  has
prompted the MPCA to stipulate effluent limitations  of 5 mg/1 BOD,,  and 5
mg/1 TSS  (see  Appendix G-l).   Concern over the cultural eutrophication*
of  lakes  in  Minnesota  has  prompted  MPCA   to  stipulate  that  total
phosphorus levels in  effluent  be restricted to 1.0 mg/1.  The  State is
currently  reviewing effluent  limitation requirements  and  expect  some
revision  of  the standards  in  approximately  one  year.   The  effluent
quality limitation  regarding total phosphorus  for  discharge to  lakes,
however,  will  remain at  1 mg/1  (by telephone, Lanny Piessig,  MPCA,  20
October 1978).

c.   Land Application

     Land application methods of  wastewater treatment  that  are evaluated
for potential  use in  the Study Area have been briefly described in Sec-
tion III.D.S.b.  These methods, spray irrigation and rapid  infiltration,
are  illustrated  in Figure  111-10.  The  locations  of  land  application
sites evaluated in this EIS are shown in Figure III-ll.

     Soil  suitability  for renovation  of wastewater at  these locations
has been  determined by SCS on the basis of on-site  field investigations
conducted  in  1978.   Maps  illustrating soil suitability of  these  sites
are  included  as  in Appendix  A-l.   Both sites have soils  with  moderate
permeability  for the  most  part,  and  have   moderate  limitations  for
wastewater disposal.

     The rapid infiltration site, located north of Nest Lake, is charac-
terized by gently rolling  knolls and side  slopes.  The  sandy and loamy
soils are  well drained and deep  to groundwater.  The  depth  to  the sea-
sonal high water table is estimated to  be  10  to 20 feet  based upon an
inspection of  a  nearby abandoned quarry several hundred yards away from
the rapid infiltration site.   This site is reported  to be representative
of the  soil  conditions that  exist beneath  the  rapid  infiltration  site.
(Interview, Al Giencke,  Soil  Scientist,  SCS,  Kandiyohi, County, October
24,  1978).   There  are  no  streams  that  traverse  the potential  land
application area.   The sandy-loamy  soils  at   the spray  irrigation site
are also well drained.

     It  is  emphasized  here  that  any serious  consideration  given  to
implementing  an  EIS alternative  involving  either rapid  infiltration or
spray irrigation must  be preceded by a  detailed  field  investigation of
the  existing  soil   and  groundwater  conditions.   The  detailed  soils
mapping of these two  sites performed by SCS personnel during the course
of this project is useful only as a planning tool for  the development of
wastewater management alternatives.

5.  SLUDGE HANDLING  AND DISPOSAL

     Two  types of sludge would be generated by the  wastewater treatment
options  considered  above:   chemical/biological sludges from secondary
and  terriary  treatment processes;  and solids  pumped  from  septic tanks.
The residues from treatment by lagoons and land application are  grit and
screenings.   Since  the  oxidation  ditch was  not selected,  sludge  from
                                  117

-------
                              FIGURE III-  10

                    LAND APPLICATION METHODS EVALUATED
                       FOR THE GREEN LAKE  STUDY AREA
                          EVAPOTRANSPIRATION
                                            CROP
SPRAY
APPLICATION
  ROOT ZONE
   SUBSOIL-
vr.r_^ q- ^ 'v fwl Y  ,- i. N  
-------
                                                                    FIGURE  III-ll  POTENTIAL LAND APPLICATION  SITES  IN THE
                                                                                          GREEN  LAKE STUDY AREA
                                                                                                   LEGEND

                                                                                           POTENTIAL LAND APPLICATION  SITES
       I	\
Rapid Infiltrotion.
Treatment Site
                                         ==•  Spray Irrigation
                                              Treatment Site
            $ X*»—^»-^^—^^--^—-*"1—^^.^^^s_,-s*.**M

            • _*-_*• ,_^- ~^i~^r^^s-^^^f**^s~^^s*^fi+^f~J

                                                                                                            DIETRICH LANGE STATE
                                                                                                           WLfXlFE UANAGEMENT M, (
                                                       GREEN^^LAKE

-------
this source was not considered further by the Facilities Plan.   Disposal
of  sludge  from stabilization ponds  was  not addressed in detail  by the
Facilities Plan.

     This EIS  has  estimated  the costs of these alternatives by assuming
that a  contract hauler  would be responsible for hauling and disposal of
sludge.  A  cost of  $81  per million  gallons of sewage was  used,  based
upon $30/1000  gallons of sludge and 2700 gallons of  sludge per million
gallons  of  sewage.   These  costs  have  been  incorporated  into  the
cost-effectiveness analysis presented in Chapter IV.

     Alternatives  using  residential  septic tanks  for on-lot  systems,
cluster systems, or STEP sewer systems must provide  for periodic removal
and disposal of the accumulated solids.   For the purpose of design and
costing these alternatives, it is assumed that pumping would occur every
3  years and  would  cost $45 per  pumping.   Local  septage  haulers  are
licensed to operate in Kandiyohi County.   Farm lands  are typical septage
disposal sites.
C.   RELIABILITY OF COMPONENTS

1.   SEWERS

     Gravity Sewers.   When  possible,  sewer systems  allow  wastewater to
flow  downhill  by force  of  gravity.   This  type  of  system,  known  as
gravity  sewer,  is  highly  reliable.   Designed  properly,  such  systems
require  little  maintenance.   They  consume  no  energy  and  have  no
mechanical components to malfunction.

     Problems  associated with gravity  sewers  include clogged  pipes,
leading  to  sewer backups;  infiltration/inflow,  increasing the volume of
flow beyond  the  design  level; and broken  or misaligned  pipes.   Major
contributors  to  these  problems  are  improperly jointed  pipes and  the
intrusion of  tree roots  into  the sewer,  which tend to be more prevalent
in older systems.

     Where ground slope  is  opposite to the direction of sewage flow, it
may  be  necessary to pump  the sewage through  sections of  pipe  called
force  mains.    The  pumps  add  a  mechanical  component which  increases
operation  and maintenance  (O&M)  requirements and decreases  the  system
reliability.  To  assure uninterrupted operation of the system, two pumps
are  generally installed, providing a  backup in case one  malfunctions.
Each is  usually able to handle at least twice the peak flow.  A standby
generator is  usually provided to ensure operation of the  pumps  in case
of a power failure.

     Because the  flow through  force mains is intermittent,  solids  may be
deposited during periods of no flow.   In addition,  when  the pumps shut
off,  the sudden  cessation  of flow may  cause the hydraulic conditions
known as "water  hammer"  in the force main, a phenomenon marked by sudden
sharp surges in water pressure that may result in burst pipes.  However,
both  deposition of  solids  and water hammer  may be  controlled  through
proper  design procedures.    The  reliability of properly  designed force
mains is comparable  to that  of gravity sewers.

                                  120

-------
     Pressure Sewers.   Pressure  sewers  transmit wastewater uphill  when
ground topography  does  not allow  gravity flow.  Because the  system  is
always under pressure, pumping  is  required to force the wastewater  into
the sewer

     Grinder Pumps.  Grinder pumps are  used  primarily to grind and  pump
raw domestic  sewage from  an  individual house to the  collection  system
and  occasionally  for  small  lift  stations.   They  are  either  of  the
semi-positive displacement  or  the  centrifugal type, depending upon the
mode of operation.   The  reliability of both types is high.

     One problem may arise  during  a  power failure.   Standby power for a
grinder pump would  not usually  be  available at  an  individual  house and
the residence would be  without  sewage removal.   This is a lesser problem
than  might  be  supposed,  for  a  power  failure   would  curtail  many
operations that generate  wastewater.

     There were  problems  in the  operation of  the  first generation  of
grinder pumps when  pressure  to  pump  wastewater or  power to  grind  solids
was  insufficient.   Modifications  have  been  made   in  their design and
construction, and  the  second generation  of these pumps  is appreciably
more  reliable.   Periodic  maintenance  is  required  to  clean or  replace
parts of the grinder pump.

     Septic Tank Effluent Pumps* (STEP).  It  is  sometimes  desirable  to
pump wastewater  from an  existing septic tank rather than directly  from
the  house,  using  STEP   rather  than  a  grinder  pump.   In  this  way
difficulties associated  with suspended solids are largely avoided.   STEP
pumps  are  relatively  simple modifications  of conventional sump  pumps.

     The reliability of STEP made  by experienced manufacturers is good.
Newer  entries  into the   field  have  not  yet accumulated the  operating
experience  necessary  to  demonstrate  conclusively  the reliability  of
their products.  In the  event  of failure  of  a  STEP system, an overflow
line may be  provided, which permits  passage of the septic tank effluent
to the old drainfield  for emergency disposal.

     Pipes.  Pressure  sewer pipes are  subject to the  same problems  as
force  mains,  discussed  above.    As  with force mains,  proper design can
prevent clogging and breaking  of pipes, the most  common  cause of sewer
problems.  Because  pressure sewer piping  has no mechanical components,
the reliability is high.

2.   CENTRALIZED  TREATMENT

     Conventional.   The  reliability of conventional wastewater  treatment
has been  tested by time.   Most unit processes have been used for  many
years, and there  is consequently  much information  on their design and
operation  in nearly all  climates.   In general,  the larger the  treatment
facility,  the more  reliable its operation, because the large  volumes of
flow  require multiple  units per  treatment  process.   For instance,  a
large  facility  will  have  several  primary  clarifiers,  and  if  one
malfunctions,   the  remaining   units   can  handle  the   entire   load.
Therefore, difficulties  that arise  as  a result of  failure of a  single
                                  121

-------
unit process, or of severe weather conditions such as heavy rain or very
cold temperatures,  are less likely to affect  operations.   Conventional
wastewater  treatment  plants can  be designed  to  handle most  problems.

     Advanced Treatment.  Advanced treatment serves  primarily  to remove
toxic substances and nutrients  that would stimulate biological  activity.
The technology  is  relatively new;  experience in design and operation of
advanced  treatment  processes   is  therefore  limited.   However,   when
designed properly, the reliability of these processes is high.

     Land Application.   Application  of treated  sewage effluent to  the
land is  still  infrequent in the  United  States, but its use-is growing
steadily. .  Local  climatic conditions  such as  heavy  rains or  very  low
temperatures  may  make  the  technique unsuitable  in a  particular  area.

     Potential problems with land application include:   groundwater con-
tamination;  dispersal  of microbial mass  by airborne  transport;  odors;
surface  water contamination;  accumulation of metals in the vegetation;
and possible toxic effects upon  local animals.  These  problems  can be
minimized  with proper  design,  but  there  is not  yet  the  extensive
practical  experience   required  to develop  advanced design technology.

3.   ON-SITE TREATMENT

     Septic Tanks.  The design and operation of modern septic tanks have
benefited   from  long  experience.   Properly designed  and  maintained,
septic  systems  will provide satisfactory  service with  minimum mainte-
nance.   Care  must  be  taken not to put materials  in the system that may
clog it.   The principal maintenance requirement,  is  periodic pumping of
the tank, usually every two or three years.

     Problems  of  septic  systems  include  heavy rain  saturating  the
ground,  clogged drainfields  caused by  full  septic tanks, clogged or
frozen pipes, and  broken pipes.   Current environmental laws restricting
sites  according to soil suitability, depth  to  groundwater and bedrock,
and other factors are  limiting  the cases  where  septic  systems  can be
used.

     Sand Mounds.   Elevated sand mounds four or five feet above original
ground   level  are  an   alternative   treatment  system   where  siting
restrictions  do not allow the use of standard drainfields.  Because they
do  not  always  provide satisfactory service and  are  considerably more
expensive  than  conventional drainfields,  they  have not been universally
accepted.

4.   CLUSTER SYSTEMS

     Cluster  systems   are  localized  wastewater  disposal  mechanisms
servicing  several  (approximately  20)  residences.   The  reliability is
similar  to that of  a septic  system, except that a  malfunction affects
not  just  one,  but a  number  of  residences.   Because  a  cluster  system
requires  more piping  to connect individual houses to the treatment tank
than does a series of individual systems, there is a greater chance for
                                  122

-------
pipes to break or clog,  or for I/I  to  occur  during  heavy  rain.   If pump-
ing is  required,  the  reliability of the system declines because of the
mechanical nature of the pumps and  their dependence upon  electricity for
power.

     The experience with cluster systems in  Otter Tail  County, Minnesota
is described in Appendix F-3.
D.   IMPLEMENTATION

     The  process  by  which  a  wastewater  management  plan • is  to  be
implemented  depends  upon  whether   the  selected   alternative   relies
primarily  upon  centralized  or  decentralized components.   Since most
sanitary  districts  have in  the past been  designed around  centralized
collection  and  treatment  of  wastewater,   there  is  a  great  deal  of
information  about  the  implementation of such  systems.  Decentralized
collection and treatment is,  however,  relatively new and there  is  little
management experience on which to draw.

     Regardless  of  whether   the   selected   alternative is   primarily
centralized or decentralized,  four aspects of  the  implementation program
must be addressed:

     •    There must be  legal  authority  for a managing agency to exist
          and financial authority for  it  to  operate.

     •    The  agency must  manage construction,  ownership and  operation
          of the sanitary district.

     e    A choice must  be made between  the several types of  long-term
          financing that  are  generally required  in paying   for capital
          expenditures  associated with the project.

     e    A  system  of  user charges  to  retire capital  debts,  to cover
          expenditures  for  operation  and maintenance,  and to  provide  a
          reserve for contingencies  must  be  established.

     In  the  following  sections,  these  requirements are examined first
with  respect  to centralized  sanitary districts,  then  with  respect to
decentralized districts.

1.   CENTRALIZED DISTRICTS

a.   Authority

     The  Green Lake  Area Facilities Plan identified the proposed Green
Lake  Sanitary  District  as  the  legal  authority  for  implementing   the
Plan's  Proposed  Action.   Under Chapter  176A of the  Minnesota  statutes,
the  District  would have  the  authority  to  implement this system  and to
contract with the villages and townships  for services.
                                  123

-------
b.    Managing Agency

     The  role  of  the  managing  agency  has  been  well  defined  for
centralized  sanitary  districts.   In  general,  the agency  constructs,
maintains  and  operates  the  sewerage  facilities.   Although  in  fact
different contractual relationships exist between the agencies and their
service  areas,  for  the  purposes  of this  document  ownership  of  the
facilities  may  be  assumed  to  reside  with  the  agency.   For  gravity
sewers,  such  ownership  has  traditionally  extended  to  the  private
property.   For  STEP  or  grinder  pump stations  connected  to  pressure
sewers several options exist:

     o    The station may be designed to agency specifications, with the
          responsibility   for   purchase,   maintenance  and   ownership
          residing with the homeowner.

     o    The station may be specified and purchased by the  agency, with
          the homeowner repurchasing and maintaining it.

     o    The  station may  be   specified  and owned  by the agency,  but
          purchased by the homeowner.

     o    The  station  may  be  specified,  purchased and owned  by  the
          agency.   Regardless,   however,  of  the  option selected,  all
          residences are treated equally.

c.   Financing

     Capital  expenses  associated with  a  project may  be  financed  by
several  techniques.  Briefly, they are:

     o    pay-as-you-go methods;
     ©    special benefit assessments;
     e>    reserve funds ; and
     a    debt  financing.

     The Facilities   Plan  indicated that  much  of the  Proposed  Action
would  not be  funded by Federal and State  grants,  and recommended that
loans  be sought from  the  Farmers  Home  Administration.  The Plan  did
indicate that  Spicer  and   New London  should  seek  such  construction
grants.

d.   User Charges

     User charges  are set at a level that will provide for repayment of
long-term  debt  and   cover  operating  and  maintenance  expenses.   In
addition, prudent  management agencies frequently a.dd an extra charge to
provide  a contingency  fund for  extraordinary expenses and replacement of
equipment.

     The implementation program proposed  by the  Facilities  Plan is an
example  of  a  scheme  calling  for  a  County  to  recover  the costs  of
wastewater management  from the  local municipalities.  The municipalities
                                  124

-------
would,  in  turn,   charge  the  users  of  the  system.   Because  of  the
potential  economic impacts,  the charges  must be  carefully  allocated
among various  classes of users.   Recognized  classes of users  include:

     «    Permanent residents/Seasonal residents
     9    Residential/Commercial/Industrial users
     9    Presently sewered  users/Newly sewered users
     9    Low- and fixed-income residents/Active  income  producers

     Each class of user imposes different requirements on  the  design and
cost of each alternative,  receives different benefits, and  has different
financial capabilities.

2.   SMALL WASTE FLOW DISTRICTS

     Regulation of on-lot sewage  systems has  evolved  to the point where
most  new  facilities   are  designed,  permitted  and inspected by  local
health  departments   or  other  agencies.   After  installation,   local
government  has  no further  responsibility  for these systems  until  mal-
functions  become   evident.    In  such  cases  the  local  government  may
inspect arid issue permits for repair of the systems.   The  sole basis for
government  regulation  in this field has been its obligation  to  protect
public health.

     Rarely have  governmental  obligations  been interpreted more broadly
to include  monitoring  and  control of other effects  of on-lot  system use
or misuse.  The general  absence of information concerning septic system
impacts on ground and surface water quality has been coupled with a lack
of knowledge of the operation of on-site systems.

     Methods  of   identifying  and dealing  with the  adverse  effects  of
on-lot  systems  without building  expensive sewers are  being  developed.
Technical  methods include  both  the  wastewater  treatment  and  disposal
alternatives discussed in Section III.B and improved monitoring of water
quality.   Managerial  methods  have already been developed  and are being
applied in various communities as discussed in Appendix  1-1.

     As  with  any  centralized  district,  the issues of  legal  and  fiscal
authority,  agency management, project financing, and user charges  must
all be resolved by small waste flow districts.

a.   Authority

     Minnesota presently has  no legislation which explicitly  authorizes
governmental  entities  to manage wastewater facilities  other  than those
connected   to   conventional   collection  systems.    However,   Minnesota
Statutes  Sections 444.085,  444.065 and 444.075, and Chapter 116A have
been  interpreted  as  providing  cities,  villages,  counties, and special
purpose water  and sewer  districts,  respectively,  with sufficient powers
to manage decentralized facilities (Otis and Stewart 1976).

     California  and   Illinois,  to  resolve interagency  conflicts  or to
authorize access  to private properties for inspection and maintenance of
wastewater  facilities, have  passed  legislation specifically intended to
                                  125

-------
facilitate  management  of  decentralized  facilities.   These  laws  are
summarized in Appendix 1-2.

b.   Management

     The purpose  of  a small waste flow district is to balance the costs
of management with the needs of public health and environmental quality.
Management of  such  a district implies formation of  a  management agency
and  formulation  of  policies for  the agency.  The  concept of  such  an
agency  is  relatively new.   Appendix  1-3  discusses   this  concept  in
detail.

     The range of functions a management agency may provide for adequate
control  and use  of  decentralized  technologies is  presented  in Table
III-3.   Because the  level  of funding for these functions  could become
an economic burden, their costs and benefits should be considered in the
development of  the  management agency.  Major decisions which have to be
made  in  the  development  of  this  agency  relate  to  the  following
questions:

     ®    Should  engineering and operations functions be provided by the
          agency  or by private organizations under contract?

     ©    Would off-site  facilities  require  acquisition of property and
          right-of-way?

     o    Would   public  or  private  ownership  of  on-site  wastewater
          facilities be more likely to provide cost savings and improved
          control of  facilities operation?

     o    Are there environmental, land use, or economic characteristics
          of   the  area   that  would  be  sensitive  to  operation  and
          construction  of  decentralized  technologies?  If  so,  would
          special   planning,   education   and  permitting   steps   be
          appropriate?

     Five  steps  are  recommended  to  implement an  efficient,  effective
program  for the management of wastewater in unsewered areas:

     o    Develop a  site-specific environmental  and  engineering  data
          base;

     o    Design  the management organization;

     o    Agency  start-up;

     o    Construction and rehabilitation of facilities; and

     o    Operation of facilities.

     Site Specific Environmental and Engineering Data Base.    The  data
base  should  include groundwater monitoring,  a house-to-house investiga-
tion  (sanitary survey),  soils and engineering studies, and  a  survey of
                                  126

-------
                                    Table III-3

          SMALL WASTE FLOW MANAGEMENT FUNCTIONS BY OPERATIONAL COMPONENT
                        AND BY BASIC AND SUPPLEMENTAL USAGE
   Component
       Basic Usage
      Supplemental Usage
Administrative
Engineering
Operations
Planning
User charge system
Staffing
Enforcement
Adopt design standards*
Review and approval of plans*
Evaluate Existing systems/
  design rehabilitation
  measures
Installation inspection*
On-site soils investigations*
Acceptance for public
  management of privately
  installed facilities

Roqtine inspection and
  maintenance
Septage collection and
  disposal
Groundwater monitoring
Grants administration
Service contracts supervision
Occupancy/operating permits
Interagency coordination
Property and right-of-way
  acquisition
Performance bonding
  requirements

Design and install facilities
  for public ownership
Contractor training
Special designs for alternative
  technologies
Pilot studies of alternative
  technologies
Implementing flow reduction
  techniques
Emergency inspection and
  maintenance
Surface water monitoring
                                  Land use planning
                                  Public education
                                  Designate areas sensitive
                                    to soil-dependent systems
                                  Establish environmental, land
                                    use and economic criteria
                                    for issuance or non-issuance
                                    of permits
* Usage normally provided by local governments at present,
                                        127

-------
available technologies  likely  to  function adequately in the area.  This
baseline  information will  provide  the  framework  for  the  systems  and
technologies appropriate to the district.

     A  program for  monitoring groundwater  should include'  sampling of
existing  wells and  possibly additional  testing  of the  aquifer.   Such
monitoring  should be instituted  early enough to provide  data  useful in
selecting and designing wastewater disposal systems.

     The  sanitary  survey should  include interviews with residents  and
inspections  of  existing systems.   A  trained  surveyor  should  record
information on lot size and location; age and use of dwelling, location,
age, and  type  of sewage disposal system; adequacy of the maintenance of
the existing system; water-using  fixtures;  and problems with the exist-
ing system.

     Detailed site analyses may be required to evaluate operation of the
effluent  disposal fields  and to determine the  impacts  of effluent dis-
posal  upon local groundwater.  These  studies  may include  probing  the
disposal  area; boring  soil  samples;  and  the  installation  of shallow
groundwater observation shafts.   Sampling  of the  water • table downhill
from  leach fields  aids  in evaluating  the  potential  for  transport of
nutrients  and  pathogens  through  the  soil.   Soil  classifications near
selected  leach fields may  improve correlations between soils  and leach
field  failures.   An  examination of  the  reasons , for  the  inadequate
functioning of existing wastewater systems may avoid such problems with
the rehabilitation or construction of new systems.

     Design the Management  Organization.  Both  the Facilities  Plan  and
the  EIS  have  recommended   the  Green  Lake  Sanitary  Sewer  and  Water
District  as the  agency best suited  to managing.wastewater facilities in
both  unsewered  and  sewered  areas  of  the  Study Area.   The  role of
organizations  such  as the Department of  Health .should, be examined with
respect  to  avoiding interagency conflicts and duplication of effort and
staffing.                                             :.

     Determination  of the  basic  and supplementary management functions
to be provided will  be  influenced by the  technologies appropriate to the
Study  Area.   In this  respect,  the  questions  raised  earlier regarding
formulation of management policies must be resolved.

     The  product of  these analyses should be an organizational design in
which  staffing  requirements, functions,  interagency  agreements,  user
charge  systems and procedural  guidelines  are defined.

     Agency Start-Up.   Once the  structure  and responsibilities  of  the
management  agency have been defined, public review; is  advisable.  Addi-
tional  personnel required  for construction and/or  operation  should be
provided.   If  necessary,  contractual arrangements with  private organiza-
tions  should  be developed.  Acquisition  of property should  also be
initiated.

     Construction and Rehabilitation of Facilities.  Site data collected
for the  environmental and engineering data base should  support selection


                                   128

-------
and design of  appropriate  technologies  for individual residences.   Once
construction and  rehabilitation begin,  site conditions may be  revealed
that   suggest   technology   or  design  changes.    Since   decentralized
technologies   generally  must  be  designed  to  operate  within   site
limitations instead of overcoming them,  flexibility should be provided.
Personnel authorized to  revise  designs  in the field would provide  this
flexibility.

     Operation of Facilities.   The administrative planning, engineering,
and operations  functions listed in Table  III-4 are  primarily  applicable
to  this  phase.   The  role of  the management  agency  would  have  been
determined in the organizational phase.  Experience  gained during agency
start-up  and   facilities construction  may indicate  that  some  lower  or
higher level of effort will be necessary to insure long term  reliability
of the decentralized facilities.

c.   Financing

     The financing of a small waste flows  district is similar  to that of
a  centralized  district.   Such  financing  was  discussed  in   Section
III.D.I.e.

d.   User Charges

     Although renovation and replacement costs for on-site systems  owned
by  permanent   residents  are  eligible  for Federal  funding,   such  costs
incurred  by  seasonal  residents  are  not.   The  major difference in  the
financing  of   the  two systems  arises  from  the question of  seasonals1
ownership of on-site  systems.   With  respect to the  Study  Area,  where a
significant proportion  of  the  users  would be seasonal,  the  absence  of
Federal funding would  transfer  a large fraction of  the project  costs to
the local users.   This would  be  reflected in either 1) capital outlays
by  the  users   for  construction,  2)   increased  user   charges  covering
increased local costs or 3) both.

     User charges  and  classes have been discussed in Section  III.E.l.d.
The significance of decentralized districts  lies in the  creation  of  an
additional class  of users.   Since residents of  such districts may  be
differentiated  in  terms  of  centrally  sewered  areas  and  decentralized
areas, user charges may  differ.  As  a result many  different  management
functions are conjoined.   For example,  permanent users on septic systems
may be  charged less  than  those  on  central  sewers.   Seasonal  users  on
pressure  sewers may have high annual costs associated with amortization
of  capital expenses;  permanent  users  of pressure sewers  may  be charged
less than seasonal users, because Federal  funding reduced their  share of
the capital  costs.   Alternatively, the management  agency may choose  to
divide all costs equally among all users.   For the analyses in this EIS,
public  ownership  of  permanent  and  seasonal on-site  systems  has  been
assumed.

     Problems  such as these  have not been  adequately  addressed by the
historical  sources  of  management  information.    Development  of  user
charges by  small  waste flows districts will  undoubtedly  be  complicated
                                  129

-------
by the absence of such historical records.  EPA is preparing an analysis
of equitable means  for recovering costs  from users  in  small waste flow
districts and combined sewer/small waste flow districts.
                                  130

-------
                              CHAPTER  IV

                          EIS ALTERNATIVES
A..  INTRODUCTION

     The  preceding   chapter   described  options  for  the   functional
components of wastewater  management  systems for the communities in  the
Study  Area.   This  chapter  examines  alternative wastewater  management
plans, or alternative courses  of action for  the Study Area.   A No Action
Alternative and a Limited Action Alternative are also examined.

     The  Proposed  Action developed  in  the Facilities Plan  (described
earlier) provides for centralized collection and treatment of wastewater
generated  in  the  area  shown  in  Figure 1-3.   In  response to  concerns
about the need  for  and  expense of the  Proposed  Action,  the  development
of  EIS   alternatives  emphasized  decentralized  and  alternative   or
innovative technologies:  alternative  collection systems,  decentralized
treatment  and  land  disposal  of wastewaters.   The  EIS alternatives
provide for management  of wastewaters  in a  slightly  larger Service Area
than that proposed in the Facilities  Plan.   The eastern half  of the Nest
Lake shoreline was added to  the Facilities Plan Proposed Service Area in
order to  examine  the  water  quality impacts  each alternative  would have
on  this  eutrophic  lake  (see  Section II.B.7.C.).   The  data  gathered
during  the  1979 "Septic  Snooper"  survey indicated a need for  improved
wastewater  management  facilities  on  this  portion  of Nest Lake  (see
Figure  11-10).   Five of the  EIS alternatives,  including the Limited
Action Alternative use decentralized  treatment to partly avoid the  costs
of sewers.

     Because the cost of  collection  in the  Proposed  Action is high,  the
cost effectiveness of pressure sewers,  vacuum sewers, and  small-diameter
gravity sewers was compared.   These sewers were, therefore, incorporated
into the design of two completely centralized systems,  one calling  for a
stabilization pond (EIS  Alternative 1), the  other for an oxidation  ditch
(EIS  Alternative  2).   However, pressure  sewers did not  prove to be a
cost-effective  method for collection  of wastewater in the   Green Lake
Service Area.

     Where site  conditions  such as soils and  topography  are  favorable,
land   disposal   of  wastewater  offers  advantages  over conventional
biological treatment systems  that discharge  to surface  waters:  the  land
is used  as a natural treatment facility system; reduced  operation  and
maintenance may result from  relatively simple operations;  and savings in
capital and operating costs  are possible.

     Analysis   of   decentralized   treatment   technologies   and   site
conditions revealed that there are feasible  alternatives to sewering  the
entire  Green  Lake,  and part  of the  Nest Lake  shorelines.   It  would be
possible  to  combine multi-family  filter  fields (cluster  systems) with
rehabilitated and  new on-site treatment systems to meet  the  wastewater
treatment needs in portions  of the Study Area.
                                   131

-------
     The assumptions used in  design  and  costing  of  the  alternatives are
presented in Appendix H-l.  The  major features of the  Proposed Action,
the EIS Alternatives, and the Limited Action Alternative are listed in
Table IV-1.
B.   ALTERNATIVES

     The action proposed by  the  Facilities  Plan has been compared with
the  "do-nothing"   (no  action)  alternative,  and  seven  new  approaches
developed in this  EIS.   The  alternatives  discussed  below  are  summarized
in  Table  IV-1, and Table  IV-2  lists the  cost-effectiveness of each.
Detailed cost  data for  each  alternative  are provided in Appendix H-2.
To facilitate the  development of  wastewater  management  alternatives, the
Proposed EIS Service Area  was  divided into  24 segments; the location of
these is shown in  Figure 11-13.

1.    NO ACTION

     The EIS  process  must  evaluate  the  consequences  of  not  taking
action.   This "no  action" alternative implies that EPA  would not  provide
funds to support  new construction,  upgrading, or expansion of existing
wastewater  collection   and  treatment  systems.    Presumably,   no  new
facilities  would be built;  wastewater would  still be treated in existing
plants and  on-site systems.

     If  this  course  of  action  were taken,  additional  flows  to  the
treatment plants  at Spicer  and  New London  would be prohibited  because
the  plants   are  already  overloaded  and  have  difficulty  meeting MPCA
effluent  discharge  standards.   Existing  on-site   systems  in  the  EIS
Service Area would  continue  to  be used in their present conditions.  In
the  absence  of a  small  waste  flows  management  agency,  the Kandiyohi
County Tax  Assessors Office would continue to issue  permits to build and
repair on-lot systems.

     The No Action  Alternative  is  unlikely  to be selected.   It  implies
that  the  treatment plants at  New London and Spicer would continue to
violate  NPDES  and  MPCA  discharge  conditions.   Consequently,  new
facilities  to  adequately treat wastewaters  would  be needed in the near
future.

2.    FACILITIES PLAN PROPOSED  ACTION

     The  Facilities  Plan  recommended treatment  of   all wastewaters
generated in the  Proposed  Service  Area in a stabilization pond treating
0.63  mgd.    The  plant,  located  east  of   Green   Lake,   would   retain
wastewater  for 210 days  and periodically  discharge effluent  to  the
Middle Fork  of  the Crow River (see Chapter  I for  a  brief  description of
the Proposed Action).  The design of the  proposed  facilities is outlined
in detail in Chapter VII of the Green Lake  Area Facilities Plan (Rieke
                                   132

-------
                                                                                          Table IV-1

                                                         REGIONAL ALTERNATIVES FOR THE EIS SERVICE AREA - SUMMARY OF MAJOR COMPONENTS
  Alternative


  Facilities Plan
  Proposed Action


  EIS Alternative  III
  EIS Alternative 02
  EIS Alternative 03
U)
U>
  EIS Alternative
  EIS Alternative 05
  EIS Alternative 06
  Limited Action
Centralized
Treatment


Stabilization
Lagoons (0.63 MGD)
                         Stabilization
                         Lagoons  (0.59 MCD)
                         Oxidation  Ditch
                         (O.S9  MCD)
                         Stabilization
                         Lagoons  followed by
                         rapid  infiltration
                         (0.38  MGD)
                         Same  as  EIS Alterna-
                         tive  S3  (0.28  MGD)
Stabilization
Lagoons followed
by spray Irrigation
(0.28 MCD)

Upgrade the existing
New London plant to
meet permit require-
ments (0.12 MGD).  Up-
grade and expand the
existing Splcer plant
to meet permit require-
ments (0.15 MCD)

Upgrade the existing
New London plant to
meet permit require-
ments (0.09 MGD).  Up-
grade and expand the
existing Splcer plant
to meet permit require-
ments (0.12 MCD)
                                                    Centralized
                                                    Service Area
All proposed
Service Area
                            All proposed
                            Service Area
                            All proposed
                            Service Area
                            All proposed Service
                            Area except North, East
                            and South Shores of
                            Green Lake
New London Village,
Splcer City, and
connecting segments

New London Village,
Splcer City, and
connecting segments
                                                     New  London Village,
                                                     Splcer  City, and
                                                     connecting segments
                                                     New  London  Village
                                                     and  Splcer  City  only
                                Additional BOD5
                                and Total Suspended
                                Solids (TSS) Removal
Not required due
to the detention
time (210 days)

Not required due
to the detention
time (210 days)

Mixed-Media
Filters (sand beds)
                                Not required because
                                of the effluent dis-
                                posal technique
Not required because
of the effluent dis-
posal technique

Not required because
of the effluent dis-
posal technique
                                Mixed-Media Filters
                                (sand beds)
                                Same as EIS Alterna-
                                tive 06
Effluent
Disposal


Discharge to the
Middle Fork of
the Crow River

Discharge to the
Middle Fork of
the Crow River

Discharge to the
Middle Fork of
the Crow River

Land application by
rapid infiltration-
recovery wells will
withdraw 7SZ of the
effluent and dis-
charge to the Middle
Fork of the Crow River

Same as EIS Alterna-
tive 03
Land Application.by
spray Irrigation.
Revenue crop is
alfalfa.

New London:  Middle
Fork of the Crow River

Splcer:  Woodcock Lake
                          Same as Els Alterna-
                          tive 16
                                                      On Lot and
                                                      Cluster Systems
                                                                                                                                          No
North, Ease, South
Shores of Green Lake
North, East, South
Shores of Green Lake,
east half of Nest Lake

North, East, South
Shores of Green Lake,
east half of Nest Lake
                                                      North, East, South
                                                      Shores of Green Lake,
                                                      east half of Nest Lake
                            On-lot:  entire Green
                            Lake Shoreline, except
                            Splcer City

                            Cluster:  No
                             Alternative
                             Collection Method

                             Conventional (gravity)
                             collection
                                                                                                                   Combination (STEP) pressure
                                                                                                                   sewers and force mains
                                                                                                                                                                       Combination  (STEP)  pressure
                                                                                   Conventional  (gravity)
                                                                                   collection
                                                                                                                                               Conventional (gravity)
                                                                                                                                               collection
                                                                                                                                                                       Conventional  (gravity)
                                                                                                                                                                       collection
                             Conventional  (gravity)
                             collection
                             Conventional  (gravity)
                             collection

-------
                                                              Table IV-2

                                                COST-EFFECTIVE ANALYSIS OF ALTERNATIVES


                         FACILITIES PLAN                         EIS 3          EIS 4          EIS 5          EIS 6      LIMITED
                          PROPOSED ACTION   EIS 1    EIS 2   (25% CLUSTER)   (25% CLUSTER)  (25% CLUSTER)  (25% CLUSTER)  ACTION
Present Project
  Construction
  Costs (x$l,000)
8,156.1      8,826.1  8,639.1     4,827.1        3,957.1        A,217.1        2,830.1     1,483.7
Future Project
  Construction
  Costs (x$l,000/yr)
   38.0
 28.5     28.5
38.9
                                                    39.9
                                                                   39.9
                                                                   39.9        24.9
Total Present Worth
  (x$l,000)
8,411.3      9,394.2  9,475.5     6.113.7        5,092.6        5,365.5        4,507.5     2,887.2
Average Annual
  Equivalent Cost
  ($)
  770.5
860.5    868.0       560.0
              466.5
                                                                  491.5
                                                                  412.9       264.5

-------
Carroll Muller Associates  1974)  and  the  process  is  illustrated  in Figure
IV-1.  As discussed in  Chapter  III,  the Facilities  Plan Proposed Action
has  been  upgraded  in this EIS  in order that its cost-effectiveness be
compared to that of the  EIS Alternatives.

     The   Proposed  Service  Area   and   location  of   the  proposed
stabilization pond  are  illustrated in Figure  IV-2.

3.    EIS  ALTERNATIVE 1

     EIS Alternative 1, with  a  design  flow of 0.59  mgd, is  identical to
the  Proposed  Action involving  treatment  by  stabilization  ponds.   The
intent  of  New  Alternative   1  was  to  consider  different collection
methods.  'Low pressure sewers  and  low  pressure  sewers  in  combination
with conventional  gravity sewers  were  considered.   None of  the segments
studied was  advantageous  for alternate  methods of collection.  In all
cases  the  conventional collection  system proved  to be  the most  cost
effective method.   The  area   to be  served  by the system,  the  treatment
plant  location  and the transmission  line  routings are shown  in Figure
IV-2.

4.   EIS  ALTERNATIVE  2

     EIS  Alternative  2 is  a modification of  one  of  the  alternatives
examined  in   the Facilities   Plan  (August  1976),  with pressure sewers
again used in conjunction with  gravity services to  collect  sewage  prior
to  treatment  at  an  oxidation  ditch  plant.   Discharge   of treated
wastewater (0.59 mgd)  as  in  EIS  Alternative  1, would  be  to the Middle
Fork of the Crow River.  This alternative is  illustrated in  Figure  IV-4.

5.   EIS  ALTERNATIVE  3

     EIS Alternative 3  is partly decentralized;  portions of  the  Green
Lake EIS Service Area would  employ on-site  and cluster  systems  while the
remaining  flow would be  treated  by land  application  (rapid  infiltra-
tion).  This  alternative is   illustrated  in Figure  IV-5.  Approximately
0.38  mgd  (from the  western  part of  the area)  would  be  collected and
conveyed to a central treatment  facility.

     Wastewater  would   be   pretreated   in   a   stabilization   pond,
chlorinated,    and   disposed   of  by  rapid   infiltration.    Renovated
wastewater would   be drawn  from  recovery  wells and  discharged  to the
Middle Fork of the  Crow River.

     The remaining portions  of  the  Green Lake shoreline would  be served
by  a  combination  of cluster systems  and on-site  systems   suitable to
local   soil   conditions.    The   preliminary  design,  comparison,  and
assessment of  decentralized  systems  (in this Alternative  as well as EIS
Alternatives  4,  5, and 6)  were  based  upon  the following  assumptions:

     Cluster Systems.  Cluster  systems  would be used for  those parts of
the  EIS Service  Area where  rehabilitation  and  continued use of on-site
systems  would  result  in  unacceptable  public  health  or  environmental
                                   135

-------
           Figure IV-1
RAW
WASTEWATER
PRELIMINARY
TREATMENT
«*- —

STABILIZATION '
POND


CHLORI NATION
PERIODIC
DISCHARGE

                                          .MIDDLE  FORK
                                          CROW  RIVER
  STABILIZATION POND
CONTROLLED DISCHARGE

-------
FIGURE  IV-2    FACILITIES  PLAN ALTERNATIVE
                        LEGEND

                       SEWERED SEGMENTS

                       PUMP STATIONS

                       FORCE MAIN

                       GRAVITY SEWER
                                  WETftlCH LANGE STATE
                                 WILDLIFE MANAGEMENT AREA .
                          0.63mgd
                       STABILIZATION
                       LAGOON (POND)

-------
FIGURE IV-3   EIS ALTERNATIVE 1




                LEGEND



             SEWERED SEGMENTS
           • PUMP STATIONS



           • - FORCE MAIN



             GRAVITY SEWER
                                                           oc
                                                           en
         [o.59n>gdi

      STABILIZATION

       LAGOON(POND)

-------
FIGURE IV-4   EIS ALTERNATIVE  2


              LEGEND

            SEWERED SEGMENTS

            PUMP STATIONS

            FORCE MAIN

            GRAVITY SEWER
       MECHANICAL
    OXIDATION DITCH
                 \

-------
                                                             FIGURE IV-5   EIS ALTERNATIVE  3



                                                                         LEGEND




                                                                      SEWERED SEGMENTS




                                                                      ON-SITE/CLUSTER SYSTEM SEGMENTS




                                                                    »  PUMP STATIONS




                                                                    -  FORCE MAIN




                                                                      GRAVITY SEWER
0.38mgd


   RAPID

INFILTRATION

    SITE
                                      GREEN ^_ LAKE
                                                                                                                      o
                                                                                                                      Iff

-------
impacts.    It  was  assumed  that  25%  of   those   residences  utilizing
decentralized systems would be tied into cluster systems;  suitable  soils
exist  at  the  sites  for which  these  systems are  proposed.   The  costs
developed were based  on  a  "typical" cluster system that  would  serve 23
residences.

     On-lot Systems.   Residences not served  by sewers  or  cluster systems
would use on-lot  systems.   This alternative would include a program of
replacement  or  rehabilitation  of  on-lot   systems where  necessary to
alleviate existing malfunctions.

     The  specific requirements  for upgrading existing  on-lot  systems
were  estimated by  analysis of  the  data  presented  in  the  Green  Lake
sanitary survey,  the  "Septic  Snooper" investigation,  and other  environ-
mental data.   Based  upon  these, 50% of the on-lot  systems were assumed
to  require  replacement  of  both  septic   tank  and  drainfield.   Site
evaluations  and  selection of appropriate replacement or  rehabilitation
technologies are  likely  to  result in variation  from this assumption in
both  the  number  of  systems  affected  and the mix  of  technologies.  The
assumption of  50% replacement  results in cost estimates expected  to be
conservatively high.

6.   EIS  ALTERNATIVE 4

     EIS Alternative  4 is  identical  to Alternative  3  except   that the
areas  surrounding Nest  Lake  would be  added  to  the areas  that  were
proposed  for  on-site  treatment  in Alternative  3.  Consequently,  flow
from  the  sewered  area would be reduced by  0.10 mgd  to  0.28 mgd.  Flows
from  the  City  of Spicer,  the Village of New London,  and segments  1, 2,
9,  10 and 11  would  be collected and treated by land application  using
rapid infiltration.

     The  locations  of  wastewater  facilities  and  service  areas for
Alternative 4 are shown in Figure IV-6.

7.   EIS  ALTERNATIVE 5

     New Alternative  5  is  identical to Alternative 4 except that  spray
irrigation would  be  substituted for rapid  infiltration.   An application
rate  of 2  inches/week was used based on the nitrogen loading'  rate.  The
crop  chosen  was  alfalfa  because a high rate of application and because
the plant  is a perennial.   Storage of wastewater  for 15  weeks  was used
in design of the  facilities (EPA, 1977).

     The  locations  of cluster systems,  on-site  disposal  areas,  and the
land application  site  (0.28 mgd) are shown  in Figure IV-7.

8.    EIS ALTERNATIVE 6

     This alternative would include decentralized  treatment  for  portions
of  the EIS  Service Area.  The area would be  divided into  two centralized
districts;  one for the City  of Spicer  and  segments 9,   10, and 11, and
the other for  the Village of New London and  segments 1 and 2.  All  other
areas of Green Lake and Nest Lake would utilize  a  combination  of cluster
systems.

                                   141

-------
                                                                FIGURK IV- 6   -.IS ALTERNATIVE 4

                                                                               LEGEND
     SSg^iHSSWSAWSSSiij -«-J>
•«JO»U. <|SNEW3;?LbNDOr*a  f=
                                                                         i| SEWERED SEGMENTS
                                                                            ON-S1TE/CLUSTER SYSTEM  SEGMENTS

                                                                            PUMP STATIONS

                                                                            FORCE MAIN
                                                                            GRAVITY SEWER
0.28mgd
   RAPID
INFILTRATION
    SITE
                                         GREEN ~ LAKE

-------
                                 ?IGURE  IV-  7  EIS  ALTERNATIVE 5


                                               LEGEND


                                            SEWERED  SEGMENTS


                                            ON-SITE/CLUSTER SYSTEM SEGMENTS


                                         •  PUMP STATIONS


                                            FORCE MAIN


                                            GRAVITY  SEWER
 0.28mgd
  SPRAY
IRRIGATION
                                                         [otŁT«ICM LANGC St*TE
                                                          WK.OLIFE MANAGEMENT AAEA .,-
          GREEN—LAKE
                                     JESSC LAKE-]

-------
     The New  London and  Spicer  treatment plants  would  be upgraded  to
tertiary* (advanced) treatment and their capacity expanded to  handle the
design flows.   The New London plant has sufficient hydraulic capacity to
meet  design  flow  (0.12  mgd)  but provides  only  primary  treatment.
Aeration, alum addition, final clarification,  mixed-media filtration and
chlorination would be added in upgrading the plant.

     The  Spicer  plant  does  not have  sufficient hydraulic capacity  to
handle  the design flows  (0.086 mgd)  and would  be  expanded  by  con-
structing a parallel plant.  Upgrading from secondary to  advanced treat-
ment  would require provision  of  the  following  processes:   alum  and
polymer   addition,   a   prefabricated   extended   aeration   plant   and
mixed-media filters.

     A map of this alternative is presented in Figure IV-8.

9.   LIMITED ACTION

     A "limited action" wastewater management alternative for  the design
period has been developed and evaluated in this EIS.   Under this  scheme,
there  would  be  no expansion  of presently  sewered  communities   in  the
Study Area (i.e., New London and Spicer).   The existing sewage treatment
plants  at  New  London  and Spicer  would both  be upgraded  to tertiary""
(advanced) treatment with capacity expanded as  necessary  to  handle the
design  flows.   The capacity  of  these  facilities  is increased  only  to
handle  wastewater  generated  by  growth in  the existing  sewered  areas.
The  design  flow of the New  London  plant  is estimated to  be  0.098  mgd;
effluent discharge  would  be  to the Middle Fork  of the Crow River above
Nest  Lake.  The estimated year  2000 flow  of the Spicer  plant  is  0.12
mgd, with effluent discharged to Woodcock Lake.

     Existing and  future  residences in the EIS  Service  Area  outside  of
New  London  and Spicer would  be  served by on-lot  systems.  As with EIS
Atlernatives  3,  4,  5,  and  6,  it  is  assumed  that  50% of  the  on-lot
systems  would  require  replacement  of  both  septic tank  and  drainfield
over  the design  period.   No  cluster systems are proposed for  service in
this alternative.

     Implicit  in  this  alternative  is  the assumption  that the  designated
wastewater  management  agency   would   not  be  authorized  to  acquire
easements and  rights-of-way or otherwise secure land, given that  no  land
application systems or cluster systems are proposed.

     The configuration of the Limited Action Alternative  is very  similar
to that for EIS Alternative 6:  The former has no cluster systems around
Green Lake and Nest Lake, and segments 1,  2, 9, 10, and 11 are served by
on-site systems, no sewers.
                                   144

-------
                                     FIGURE  IV-8    EIS ALTERNATIVE 6

                                                   LEGEND

                                                SEWERED SEGMENTS

                                                ON-SITE/CI.USTER SYSTEM SEGMENTS

                                                SEWAGE TREATMENT PLANT

                                                FORCE MAIN

                                                GRAVITY SEWER
                                  NEW LONDON STP UPGRADI
                                     (NO EXPAND)
NEW LONDON COLLECTION
     SYSTEM (NEW)
 -CITY  OF SPICER COLLECTION
       EXPAND/UPGRADE
               GREENE-LAKE
   SPICER STP
UP-GRADE AND EXPAND
              „.,  WOODCOCK
              24    LAKE

-------
C.   FLEXIBILITY OF  ALTERNATIVES

     The flexibility of  the  Proposed Action and  the EIS Alternatives to
accommodate  future  growth   in   the  service  Area   along  with  their
operational  flexibility  over  the design  period is  evaluated  in this
section.
1.   FACILITIES PLAN PROPOSED ACTION

     This  alternative  provides  good  flexibility for  growth  since, as
long  as  land  is  available,  stabilization  ponds  can be  expanded to
accommodate  increased  flows  relatively easily.   Flexibility for future
growth is, however, reduced somewhat because  the  entire proposed Service
Area is to be sewered.   More  flexibility for  future  expansion is usually
available  for alternatives that  require  a smaller initial commitment of
resources.

2.   EIS  ALTERNATIVE 1

     Except  for  the  use of  pressure  sewers  for wastewater collection,
this alternative  is  identical to  the  Facilities Plan Proposed Action.
Such pressure sewers  provide  more flexibility for design than do gravity
sewers since pressure sewers  do not  require suitable ground contours for
economical  construction.  The  flexibility for expansion  is  the same as
for the Facilities Plan Proposed  Action.

3.   EIS  ALTERNATIVE 2

     With  the exception of  the  treatment process,  this  alternative is
identical to EIS Alternative  1.   The treatment scheme in EIS Alternative
2 provides  greater flexibility of  operation  than does  the stabilization
pond.  The flexibility of expanding  an  oxidation  ditch  is dependent upon
the availability of  land.  Much  less  land, however, is required for an
oxidation ditch  than  for a  stabilization pond.

4.   EIS  ALTERNATIVE 3

     Unlike the alternatives that propose discharges of effluent to the
Middle Fork  of  the Crow River, EIS  Alternative 3 proposes that effluent
be  disposed  of  by  rapid  infiltration.   The  addition  of  preliminary
treatment  and rapid   infiltration  to  the stabilization  pond  treatment
process  reduces  operational   flexibility  over  the  plain stabilization
pond process.   From  the standpoint  of  expansion, rapid infiltration is
less flexible than spray irrigation  because siting restrictions are more
severe.   However,  rapid  infiltration requires much  less  land  area than
spray irrigation.  Also, the  operational  flexibility of rapid infiltra-
tion is  good since  it  has a wide  range of possible application rates,
and can be  used  year round,  even in cold  weather.   EIS Alternative 3 is
somewhat  more flexible  than  previous  alternatives because  only part of
the proposed  Service Area would be sewered.  This limits  the initial
commitment  of  resources  and increases   the  flexibility  for  future
planning and design.

                                   146

-------
5.   EIS ALTERNATIVE  4

     Operational flexibility is the same  as  for EIS Alternative 3.  The
flexibility  for future  expansion  is  slightly  greater  than  for EIS
Alternative  3  because  the  amount  of sewered area  is  slightly   less.

6.   EIS ALTERNATIVE  5

     This alternative is similar to EIS Alternative 4 except that  spray
irrigation,  rather than  rapid  infiltration,  would  be  used for effluent
disposal.   Spray  irrigation is  subject  to  fewer  siting restrictions,
therefore  has  increased flexibility  for expansion, but  requires much
more land  than rapid infiltration.   The  range  of  application rates is
more  limited   for   spray   irrigation  than  for  rapid  infiltration.
Additionally, spray  irrigation  may  not be  feasible  in very cold weather.

7.   EIS ALTERNATIVE  6

     Upgrading and expanding an  existing  facility  provides  less  flexi-
bility than  does constructing  a  new one.  When planning and designing a
new  treatment  plant,  factors   such  as location,  treatment process, and
plant configuration  can be optimized.  When expanding  or upgrading an
existing facility,  the  components  that  are  already in use constrain the
design  and  reduce flexibility.   Upgrading  and  expanding  the existing
Spicer  and  New  London  wastewater treatment  plants  appears  to  be  a
relatively  simple operation.   Since the improvements  will involve only
process   additions  with little  or  no  interactions  between new and
existing components,  the main limitation  of  flexibility will  be the
availability of surrounding  land  for expansion.

8.   LIMITED ACTION

     The Limited Action  Alternative represents the  maximum decentralized
approach of all wastewater management  schemes  evaluated in  this EIS.
With no  provision  of improved collection and treatment facilities for
present   and  future  residents   outside currently  sewered areas, it also
represents   the  least   flexible   of  all  alternatives  in  terms  of
accommodating future  growth  in  the  EIS Service Area.

D.   COSTS OF ALTERNATIVES

     Project  costs  were  grouped  by  capital  expenses,  operating and
maintenance  expenses,   and  salvage values   of the equipment  and land
required  for  each  alternative.   A  contingency fund  amounting  to
approximately  25%  of capital  costs  was  included  to provide  for such
expenses as  engineering and legal  fees,  acquisition  of rights-of-way,
and  administration.   The   methodology  and  assumptions  used  in the
analyses  are  described in Appendix H-l.   Detailed  costs   for each
alternative are also  presented  in Appendix H-2.
                                   147

-------
     The present  and future project  costs for  the  upgraded Facilities
Plan Proposed Action, EIS Alternatives and Limited Action are summarized
in  Table  IV-2.   The  analyses  of  total  present  worth  and  annual
equivalent costs of  each alternative  are also presented  in  this  table.
(Debt service on financing and  local share is not included.)   Discussion
of Federal/State cost sharing  and remaining local costs  is  included in
Section V.E.
                                   148

-------
                               CHAPTER V

                                IMPACTS

A.   IMPACTS ON SURFACE WATER QUALITY

1.   PRIMARY IMPACTS

a;   Analysis  of Eutrophication Potential

     This  section  discusses  the effect of nutrient loading "associated
with  different  wastewater  management  alternatives  upon  the  trophic
status of  open  waters  in Nest Lake, Green Lake, and Woodcock Lake.  To
evaluate  the impact of  each alternative, nutrient  loading levels for
phosphorus were calculated.  The empirical model  developed by Dillon was
used  to project  future  trophic  conditions  associated  with different
phosphorus  loading scenarios  based on  the  EIS  wastewater management
alternatives.

     The  major  sources  of phosphorus  for Nest Lake,  Green Lake, and
Woodcock  Lake  were  identified  earlier   in  the   following  order  of
significance:

     •    tributaries  (Middle  Fork  of the Crow  River  to Nest Lake and
          from Nest Lake to Green Lake);

     •    wastewater treatment plants (Belgrade and  New  London to Middle
          Fork Crow River and Spicer to  Woodcock  Lake);

     •    septic tank systems; and

     •    immediate drainage around  the  lake.

The relative  contributions of phosphorus  to  Nest Lake,  Green Lake, and
Woodcock  Lake  made  by  these  sources   under  present  conditions are
illustrated  in  Figure  V-l.   Other sources  known  to  contribute  to
nutrient  loading  such  as groundwater, detritus,  waterfowl, and .release
from  sediments  are less  significant in the  Study  Area  in terms of the
time scales considered.

     Future Phosphorus  Loading Scenarios.    In  this  analysis,  future
phosphorus  loading  levels have been projected for the year 2000.  The
immediate problem  in deriving these loads is the phosphorus loading in
the Middle  Fork of the  Crow River  upstream  from  Belgrade.  This load
varies with  the  flow  in the river from  year  to year.  A normalized load
proportional to the average flow in  the  river over  the record period was
used.  Furthermore, this  normalized load  was assumed to remain the same
'until  the  year 2000, because future land use changes  were uncertain.
Phosphorus  output  from Nest Lake represents a significant  contribution
to  Green  Lake.   In  this  analysis,   the  retention   coefficient for
phosphorus  in Nest Lake  observed  during   1972-73  (56%)  was used.   The
septic  tank  leachate,  and  wastewater  treatment  plant  discharge  loads
were  calculated  according  to  each  wastewater  management  alternative
                                    149

-------
    4,000
o
    3,000
_J
V)
i  2,000
i
    1,000
                  96%
                       NEST
                       LAKE
                                               LEGEND
     JNON-1'OINT SOURCE  (TR I BUTAK I ES)
                                     8%
                                     2%
17%
                                    73%
      | NON-POI NT SOURCE  ( 1 MMEI) I ATI.
            DRAINAGE)

      SEPTIC TANKS

      POINT SOURCES

      PRECIPITATION AND  SEPTIC
                  TANKS  (WOODCOCK
                  LAKE)
    GREEN
     LAKE
                                                        i%
                                                      93%
WOODCOCK
  LAKE
                          Figure V-l
COMPARISON OF PHOSPHORUS LOADINGS BY SOURCE CONTRIBUTIONS  FOR
                   THE GREEN LAKE STUDY AREA
                              150

-------
developed.   The  immediate drainage  contribution  is usually  relatively
insignificant in  this case  and  was assumed  to  be constant  until  year
2000  for  practical  purposes.   The .total  phosphorus inputs  associated
with various alternatives  for  Nest  Lake and Green Lake  are presented in
Table  V-l.   The  1972-73  loading  levels  are  included  for  comparison.

     Future Trophic Conditions.  Figure V-2 summarizes  the  results  from
the  modeling analysis  with respect  to various  wastewater  management
alternatives.  Nest  Lake  is predicted  to  remain eutrophic for  all the
alternatives with  slight  improvement  in water quality.   Green Lake  will
also  maintain  its  trophic  status  in  the mesotrophic  category.   This
small  improvement  in the  quality  of open waters suggests  the  signifi-
cance of the non-point source loading associated  with the Middle Fork of
the  Crow  River  which  is  uncontrollable at the present  time.   In  addi-
tion,  cautions  have to  be exercised when interpreting  the  results be-
cause  of  the yearly variation  of phosphorus  inputs  existent in  the
River.  That is,  this  variation  may be so  significant that it masks, the
reduction  of  phosphorus   inputs   incurred   for  Green  Lake  by   some
alternatives.                                       -•-••

     The modeling  analysis described  above cannot be  used to assess the
trophic status  of Woodcock  Lake,  due  to  the landlocked  nature  of  this
water  body.   In any  event,  phosphorus  input to Woodcock Lake  will de-
crease dramatically (more than 50%)  under any proposed wastewater manage-
ment  scheme  evaluated in  this EIS.  This  reduction  would result  from
either  the  discontinuation of the  present Spicer  wastewater treatment
plant  discharge or from  the proposed upgrading of  the  plant  to provide
effluent phosphorus concentrations of 1.0 mg/1.

b.   Bacterial  Contamination

     Lakes  in  the  Study  Area have met State standards 'for fecal  and
total  coliform bacteria.   Where  human  wastes have been  implicated  as  a
contributor  to coliform  counts in the lakes, it  is expected that all of
the  wastewater  management alternatives should effectively  abate such  a
problem.

     Land application  of wastewater is an effective way of eliminating
or immobilizing sewage-borne pathogens particularly if some pretreatment
(stabilization  pond)  precedes  the  application  (Johnson et  al.  1977).
Bacterial pathogens  undergo  rapid die-off  in the soil  matrix.   Studies
have  shown  the  summer  survival  rate  of fecal coliforra  organisms to be
0.001% after a period of 35 days (Miller 1973).

     With  the   centralized alternatives,  pumping station  malfunctions
could  result  in  substantial  bacterial  contamination  of  the  lakes.
Rigorous  inspection  and maintenance of pumping stations,  back-up  elec-
trical power supplies,  standby pumps  and  an overflow alarm would  mini-
mize  the  possibility  of  this happening.    Similar  measures should be
taken with pumping stations for cluster systems.
                                    151

-------
                              Table V-l




     TOTAL PHOSPHORUS INPUTS (KG/YR) TO NEST LAKE AND GREEN LAKE






   Alternative                   Nest Lake               Green Lake




1972-73 Conditions               4,329.9                  2,605.1




No Action                        3,029.2                  1,969.1




l'& 2 (Proposed Action)          2,355.8                  1,679.6




    3                            2,707.8                  1,827.7




    4                            2,386.4                  1,686.3




    5                            2,,355.8                  1,672.9




    6                            2,474.0                  1,724.9
                                   152

-------
    1.0 C
CVJ
 E
    O.I
   0.01
                                  I    I
            EUTROPHiC
    NEST LAKE
  1972-1973 CONO. °
     NO ACTION O
  ALTERNATIVE 3 *
  ALTERNATIVES
ALTERNATIVE 1,2,4,5
'GREEN LAKE
 O 1972-1973 COND.
 O ALTERNATIVES 1-6, AND NO ACTION
                                               OLIGOTROPHIC
                        I   I  I  I  I I  1
                                     I   I   I  I I  I
      1.0                           10.0                           100.0
                          MEAN DEPTH (METERS)

                   L=AREAL PHOSPHORUS  INPUT (g/m2/yr)
                   R=PHOSPHORUS RETENTION COEFFICIENT
                   P-HYDRAULIC FLUSHING RATE (yr"1)

      FIGURE V- 2  TROPHIC STATUS OF NEST  LAKE AND GREEN LAKE
                    IN TERMS OF VARIOUS WASTEWATER
                   MANAGEMENT ALTERNATIVES
                                153

-------
c.   Non-Point  Source  Loads

     Primary impacts on  surface  water  quality  related to the construc-
tion of ST/SAS and the  replacement  of old  systems is likely to result in
increased soil erosion.   Similarly,  installation of sewers,  especially
those that pass under the many  small drainage ways leading to the lakes,
will increase erosion.

     Compliance with state  and local  soil erosion control requirements
could substantially reduce the  erosion  problem and the subsequent impact
on water quality.

2.   SECONDARY  IMPACTS

     Increasing  housing   development   along  lake  shores may  increase
nutrient   and   sediment    loads   into   the   lake  as   a   result   of
the following:

     o    increased runoff from construction of  impervious surfaces such
          as rooftops and parking areas;

     »    lawn  and  garden  fertilization  creating  unnaturally  high
          nutrient levels in the  runoff; and
     \
     e    soil disruption  by  human activities   (i.e.,  housing construc-
          tion, leveling  of forested area,  etc.).

Soil organic debris and dissolved materials mobilized  and transported to
temporary  runoff  channels  during storms  are  settled, filtered  and
absorbed on  the  land or  in pools if the  runoff  channels are long or if
adequate  storage  areas,   such  as  wetlands, occur.   Increasing housing
density normally  accelerate storm runoff thereby increasing not only the
amount  of  runoff but  also  its ability to  erode soil and to transport
contaminants.
B.   IMPACTS ON GROUNDWATER

     Groundwater  impacts  fall  into two categories, those affecting the
available  quantity  of  the  resource,  and those  affecting  its quality.

1.   GROUNDWATER QUANTITY IMPACTS

     The  conversion  from  sewage disposal practices based on  individual
soil  absorption  systems  to central  collection and  treatment systems
without land application of effluent can result  in  a  loss of groundwater
recharge.  The  significance  of  this loss depends upon its relationship
to  the  recharge  from  all  other  sources,  including  downward infiltration
and  percolation  from  precipitation and surface  water bodies  and  inflow
from adjacent aquifers.   The precise quantification of  this significance
requires an accurate delineation of the aquifer(s)  plus knowledge  of its
hydrology  (precipitation,  runoff,  evapotranspiration,  discharge,  etc.)
                                    154

-------
and hydraulic  characteristics  (transmissivity*,. storage  coefficients*,
etc.)-   There  is  not enough  data to  attempt  such quantification  for
Green Lake.

     Because the confining layer above the buried outwash aquifer in  the
Study Area  is  impermeable,  essentially no significant recharge  of this
aquifer takes place by means  of infiltration within the  boundary of  the
aquifer which includes the  entire  Study Area.   The aquifer is  recharged
mainly by underflow from  the surficial glacial deposits northwest of  the
Study Area,  but  the  extent  of recharge  is  unknown  (Lindholm et  al.
1974).  Because  the  source of  recharge is  outside of  the  Study Area,
none  of  the alternatives  will affect  this  aquifer.  Furthermore,  the
estimated domestic water use by the Facilities Plan Proposed  Action of
0.63  mgd  in the year 2000  is  very small and unlikely to  significantly
affect quantities  of  water within the buried  outwash  aquifer  or sur-
ficial groundwater which  Lindholm  et al., indicated will  support addi-
tional development for domestic and irrigation supplies  (1974).

2.   GROUNDWATER QUALITY IMPACTS

     Human  wastewater disposal  can affect  the quality of  groundwater
through three  main types of  pollutants.   The  first type  includes sus-
pended  solids,  bacteria  and  other  forms of  organic  matter  which  are
normally removed  by  downward movement  through approximately  5  feet of
soil  above  the  water table of aquifers.  These  contaminants are very
unlikely to reach the  buried outwash  aquifer  because  the  impermeable
confining  layer  provides  an adequate  barrier depth to  this  aquifer is
generally more than 20 feet.

     Groundwaters  overlying the buried outwash  aquifer are  more sus-
ceptible to  the  influence  of  wastewaters applied to the  soil  either by
land  application  or  through  soil absorption  systems.   The  surficial
aquifer is  apparently unconfined and the water table is  near the ground'
surface  in  many places  near lakes.  Organic  or bacterial  contamination
of this  surficial  aquifer  by  spray irrigation  or  rapid  infiltration of
wastewaters  can  be avoided by  using only sites  where  the  water  table
will  remain  deeper than  6  feet below ground  surface and  where soils  are
fine enough to filter wastewater efficiently.  The most likely source of
contamination to  this aquifer  is  soil absorption  systems  in  low-lying
areas.   It  was  partially on  the  basis  of such  contamination that  the
applicant  applied  for grants  to  build sewers.   While  there  is little
doubt  that  these  contaminants  enter  the  surficial  aquifer  in  some
places, their effects appear  from  available  data to be  very localized.
Well  data   submitted  by  the  applicant  shows   the presence  of  total
coliform  bacteria  in  some  wells  but  there  is   no   support  to  the
implication  that  their  source  was  soil  absorption  systems.  A more
likely  cause of the  well  contamination is the design and  condition of
the wells themselves.   Nevertheless, if continued use of  soil absorption
systems  is  recommended,  a  substantial program of well  inspection  and
sampling  should be  undertaken to include  location of  suspect wells;
inspection  of  their  casing,  seal   and  grouting;  identification of  all
potential  sources  of  contamination near the  wells; sampling of properly
designed wells  for fecal  coliform  bacteria,  and nitrates  at a minimum;
and measurement of groundwater flow direction and rate in representative
areas around the lake shores.

                                    155

-------
     In the Study Area,  the impermeable confining layer above  the  buried
outwash aquifer  should  also serve  as  an effective barrier against  the
entry  of   nitrates  into  the aquifer  by infiltration.   The  surficial
aquifer is not so protected and is likely receiving nitrates  from  soil
absorption systems  as  well  as  from agricultural sources and  lawn  fer-
tilization.  With the exception  of  two wells sampled by the  applicant,
groundwater have  nitrate  concentrations below the drinking water stan-
dard of  10 mg/1  as  nitrogen.   As  housing  densities increase in areas
dependent  on  soil  absorption  systems,  nitrate  levels  will increase
especially if development  involves multiple  rows  of dwellings.  A  sampl-
ing program  to determine  the  levels  and sources of nitrates  and other
contaminants in wells is  required if  alternatives using soil  absorption
systems aire funded.

     It is possible that  some  nitrates from wastewater applied to  land
might  reach  surface waters  via  overland runoff,  lateral interflow"'  in
soils,  or  transport in percolating groundwaters.  However,  application
rates  for  spray  irrigation  of  effluents  would  be set  to maximize  crop
uptake  of  nitrogen,   minimizing  its   concentrations   in   groundwater.
Because of the high application rates  for rapid  infiltration, recovery
of  rennovated  effluent by  recover wells or drains  may be  necessary.

3.   MITIGATIVE MEASURES              \

     Groundwater quality should  be  carefully monitored for  all alterna-
tives  involving the"use of ST/SAS's,  cluster systems and land applica-
tion systems   to  check  that  water quality  is  not being significantly
degraded and to  signal  the existence  of malfunctions,  inadequate  treat-
ment or the need  for corrective action.

     The potential for groundwater contamination  from the sewage  lagoons
required in the  Facilities  Plan Proposed Action  and  EIS Alternatives 1,
3, 4 and 5 will be low if  the lagoons  are adequately designed.  Existing
engineering and hydrogeologic procedures would prohibit the  construction
of these systems  directly  in the aquifer, and would  require an adequate
distance between the lagoon bottom and the groundwater.   Also,  an  imper-
vious  layer of soil material such as  bentonite  clay would  be used  as a
line for  the  lagoons'  sides and bottom to  insure leakage  of  untreated
wastewater does  not occur.   As a final protection measure,  groundwater
quality monitoring wells would be used to identify any changes in  ground-
water  quality  that may be a  result  of  leakage  from  a sewage  lagoon.
This would insure  that corrective  action  could be  taken before  any
serious contamination develops.
C.   POPULATION AND  LAND  USE  IMPACTS

     Population  and land  use  impacts  associated  with  various  system
alternatives  are  evaluated   in  this section  (see  Table  V-2).   These
impacts are summarized below:
                                    156

-------
                                 Table V- 2

               COMPARISON  DEPOPULATION AND LAND USE IMPACTS
                 ASSOCIATED WITH MAJOR SYSTEM ALTERNATIVES
    co
    •H C
    4J O
    C -H
    Q) 4-1
    to a f
    0) i-l 4J
    <4-< 3 ?
    -i
&   4_i

O to co
H 0) C
d) 4-1 CU
> 4J 4-1
cu n) C
Q PL, H
                   Increase in lakeshore den-
                   sities and in extent of
                   shoreline development.
                                          Continued scattered  residential
                                          development,  limited by  on-
                                          site limitations  in  lakeshore
                                          areas.
o
u
      O O
      u u
•H
C
d
      o ,c
      u u
             Accelerated conversion
             from seasonal to year-
             round occupancy status;
             loss of lower-income
             population base due to
             displacement pressure.
               Increase in lakeshore
               densities and in extent
               of shoreline develop-
               ment .
                                                Existing  composition influenced
                                                by demographic  pressures un-
                                                related to  facility provision.
Continued scattered residen-
tial development, limited by
on-site limitations in
lakeshore areas.
                                      157

-------
     o    A majority of residences  directly contiguous  to  Green Lake  and
          Nest Lake and not  located  within the boundaries of  Spicer  or
          New  London   are  currently  utilizing  on-site  waste  disposal
          systems.   An estimated 30 to 40 additional  lakeshore acres  are
          likely to be developed with provision of centralized sewerage
          facilities.

     «    Some increase in the  density of residential  development along
          the lake is  also likely to result from centralized  facilities.

     o    Population growth  of  5  to  10% above  levels possible  without
          centralized  facilities may  accompany  anticipated  increases in
          residential  acreage and intensity.

     «    Centralized   facilities  will  place  severe financial  pressure
          upon  lower-  and  middle-income families,  resulting  in  the
          dislocation  of  many  less   affluent  residents.   In  addition,
          these alternatives  will accelerate  the conversion  of occupancy
          patterns  from  seasonal  to  year-round status.   Disruption  of
          the  prevailing  community  environment  will be   a  possible
          by-product of economic and financial pressures associated with
          centralization.

     o    Decentralized  wastewater  management  facilites  should only
          moderately  influence   the   composition  and  character  of  the
          Green Lake area.

1.   INTRODUCTION

     The  capacity  of  an area  to  support  development varies with  the
degree  to  which wastewater facilities  are site-related.  On-lot waste-
water treatment  facilities  are  site-dependent because they  are  limited
to sites with  suitable soils.   Sewers allow development to  be much more
independent of site characteristics because the soil  permeability, slope
and  drainage are  not  such  strong  constraining factors.   Thus,  sewers
increase the  inventory of developable land.    Sewers  also  increase  the
possible  density  of  development.   The  amount  of  additional  growth
actually occurring  in  the area  if sewers are  provided is dependent  not
only  upon  increases in  development  potential but also upon  demand  for
additional  residential  development in  the  area.  This demand reflects
the residential amenity of the area in comparison to  other areas and  the
reduction in the cost of residential land when the supply  of developable
land is increased.

     Population and land  use impacts are estimated in this  Section  for
completely  centralized  (Proposed Action  and  EIS  Alternatives  1  and 2)
and  completely dencentralized  (No Action)  alternatives.   Impacts  are
also  estimated  for EIS  Alternatives  3,  4,  5 and 6,  which  incorporate
partial  sewering   and   cluster  systems.   These  alternatives,  while
described as  decentralized,  are actually hybrid or intermediate systems
in terms of population and land  use impacts.
                                     158

-------
2.   POPULATION

     If centralized facilities were provided, minor differences in popu-
lation would  occur over levels  expected  for decentralized facilities.
With  centralized  facilities,  population  in  the Service. Area  would be
anticipated to increase between  5 to  10%  above  the levels expected for
decentralized wastewater management  alternatives.   Centralized facili-
ties would concentrate growth within the nearshore segments of the Green
Lake  EIS  Service  Area.  With site-dependent, decentralized facilities,
nearshore  areas  would be developed  at a lower  density or may  not be
developed at all,  resulting  in more development  in areas remote from the
lakeshore.,

3.   LAND  USE

     Implementation of  centralized  facilities  should not significantly
affect future land use except  in certain lakeshore segments.   Segment-
by-segment analysis of  the  Green Lake  shore  yielded  an estimated "30 to
40  lakeshore  acres likely  to be developed only with provision of cen-
tralized facilities.

4.   CHANGES IN  COMMUNITY COMPOSITION AND  CHARACTER

     The composition and character of  the Green  Lake community would be
only  slightly influenced by  the provision  of  centralized facilities.
Additional  costs   of  wastewater treatment   would  displace some  lower
income  permanent   and   seasonal  residents.   These  residents   would be
replaced by higher  income persons able to afford the additional waste-
water  treatment costs.  Higher  costs  would also accelerate the current
trend  of  seasonal  to  year-round residence  because  fewer  people could
afford to maintain second  homes.

     The rural character of the  area  would be  diminished only slightly
by the increased amount of land  that would be devoted to residential and
associated  uses  with  centralized  facilities.   Moderate  change  in the
character of the area could  also  occur  with EIS Alternatives 3, 4, 5 and
6  as  population growth and land development would  take place in areas
serviced by sewers and the numerous  cluster systems.

     Adoption of  a  Limited Action or a No Action  Alternative  would
encourage preservation  of the area's prevailing  community character and
composition.  There would be very little  economic displacement pressure
in  the Green Lake area  and  land  use patterns  would be  unlikely to
change.
D.   DEVELOPMENT ON  ENVIRONMENTALLY  SENSITIVE AREAS

     The  following  areas  have been identified as being environmentally
sensitive to building or construction  in the  Study Area:
                                     159

-------
     o    Floodplain and shoreline area;
     o    Wetlands;
     e    Natural areas;
     ®    Archaeological and historical  sites;
     e    Steep slopes;  and
     o    Prime-agricultural land.

     As stated in Section  II.E.4,  implementation of EIS Alternatives  1
or 2  or the Facilities  Plan Proposed Action  would probably result  in
conversion of  approximately 30 to  40 acres from agricultural to  resi-
dential use.   If no  wastewater treatment  facilities  are  provided,  no
substantial conversion of agricultural lands is likely.

1.   FLOODELAINS AND  SHORELINE  AREAS

     The 100-year floodplain  in  the Study  Area includes  a  narrow  ribbon
of land along the Middle Fork of the Crow River and  surrounds  the  numer-
ous  lakes  located in the  Study  Area.  The largest individual areas  of
floodplain in the Study Area  have been incorporated into the  New  London
Fish  Hatchery  and the  Dietrich  Lange Wildlife Management Area and  are
consequently under State and Federal protection.

     Kandiyohi County has  a  floodplain  management ordinance intended to
provide suitable areas for orderly and aesthetic development which would
retain the natural  features  of  the shoreline and adjacent areas.   This
ordinance, which  recognizes that control of shoreline development  will
assist  in  the maintenance  of  good  water quality and the  prevention  of
erosion,  is  critical  to the  development of the 22 miles of  shoreline
around Green Lake and Nest Lake.   Placement and construction of sanitary
and wastewater disposal facilities are governed by the  ordinance  (Kandi-
yohi  County  Overall Economic  Development Plan  1977).  It  also requires
that the basement floor of any structure to be  used  for human  habitation
be more than 4 feet  above the 100-year flood elevation.

     Primary physical  impacts on  the shorelines would  occur with  all
alternatives; such  impacts are likely  to  be more severe  with the  cen-
tralized  treatment  systems i.e., EIS Alternatives  1 and  2,  Facilities
Plan Proposed Action which require construction of sewer  lines.

2.   WETLANDS

     Figure  II-7  indicates that wetlands are  widespread throughout  the
Study  Area.   More  than 1800 acres  of wetlands  are  under Federal  and
State management as  part of waterfowl protection and wildlife  management
areas.  Potential impacts  of construction  on  privately owned wetlands
also  need  to be  assessed in view of  the importance  of wetlands  to both
groundwater levels and wildlife and because the agricultural practice of
ditching  and draining  lands  has  already   reduced  certain wetlands  to
small areas.

      If    a     centralized    alternative     is    chosen,     primary
construction-related  impacts  on certain wetlands  will be unavoidable.
The  water table might  be  lowered,  erosion  and  siltation  increased,
streamflow altered and  habitat  modified.   Impacts might  be minimized by
excavating during  low flow or during the  six  cold  months of the  year,

                                    160

-------
and by immediate restoration of the area.   However,  wetland  areas may be
permanently damaged if the water table  even drops  one  or  two feet.   Some
wetlands may  become  dried up by  a process that may not be  reversible.

     Wetlands might be permanently altered by EIS Alternatives 1,   3,  4
and 5.   Scattered throughout the  areas  of the selected land  treatment
sites, wetlands  could be  avoided  during   construction.  In  selecting  a
site,   the   importance  of  any  wetland to  the watershed,  its storage
capacity, its habitat  type,  and the effects of construction on wildlife
should be considered.

     There  are currently no regulations regarding  discharge  of  municipal
wastewater   into  wetlands  other  than  the  requirement to  obtain   a
Minnesota  Pollution   Control  Permit  (MPCP).   Nevertheless, compliance
with effluent limitations  for  surface  water would be  required  (by  tele-
phone, Dale Wikre, MPCA,  April 1978).

3.  NATURAL AREAS

     The  existing  natural  areas  within  the Study Area have   been
delineated   in Figure  11-13  and include  State wildlife  management and
Federal waterfowl protection areas.

     In  addition, current  easements   give the Federal  government the
right   to manage additional  acreage  of waterfowl  habitat  in  the  Study
Area if they so decide (Economic Development Plan  1977).  The large size
and low  population  density of  these  wetlands  means that the direct
impacts  on  these wetlands  resulting  from wastewater  management alter-
natives  should  be minimal.  However,  secondary impacts  resulting from
human activities could pose future problems for these  areas.' The degree
to which development  rates  will differ among the  alternatives  cannot be
determined.

4.  ARCHAEOLOGICAL AND  HISTORICAL  SITES

     Numerous archaeological sites are  believed to be  located within the
Proposed Service  Area.   Several historic  sites are located  in  the  Study
Area.   Construction of pipelines  around  Green Lake arid  Nest Lake  could
have potentially significant impacts on these sites with  EIS Alternative
1  and  2 and  the Facilities Plan  Proposed Action.  Those  alternatives
which  provide  increasingly  centralized   sewerage  service  would   have
greater  long-term secondary impacts due to induced growth  and develop-
ment near the lakes.

     Upon  the  selection  of a  final  alternative,  detailed  designs and
specifications  will have  to be sent to the  State  Historic  Preservation
Officer.   At  that time,  detailed  site investigations  will  be  performed
by  an  archaeologist/historian  to  resolve  potential conflicts with any
archaeological or historic site which could be disturbed  by  construction
activities.
                                    161

-------
5.   STEEP  SLOPES

a.   Primary Impacts

     The  difficulties  of  installing  on-lot  systems  on  steep  slopes
appear to be a  factor  historically  limiting  home  construction of lake-
shore and other  level  of  rolling  sites.  Nonetheless, suitably designed
on-site  systems  may be  constructed  on  steep  slopes,  as  can  sewers.
Adherence to the Sediment and Erosion Control Act of 1972 should mini-
mize the impacts of erosion  from construction.

b.   Secondary  Impacts

     The availability of off-lot  treatment systems provided for cluster
systems, along with the apparent  demand  for residential development may
result in construction  activity on steep-sloped  areas.  Accelerated soil
erosion  particularly  on  any steep bluffs  surrounding  the  lakes  can
result  in  additional  non-point  source runoff in  the form of sediment.

c.   Mitigative Measures

     The municipalities should adopt performance standards with specific
slope-density provisions.   Developers would then  have  to  meet the per-
formance  standards  burden  of  proof  that  the  sloped  areas  are  not a
hazard  to development.  Zoning ordinances  should  limit growth in steep
sloped areas.

     If cluster  systems or  septic tanks  are  placed in areas with steep
slopes  a  series of drop  boxes  should be  used.  With this  method,  no
hillside seepage should occur unless  the sewage flow exceeds the design
capacity.

6.   PRIME  AGRICULTURAL  LAND

     Some agricultural  land within  the Study Area will be used for the
implementation of all potential actions.   For areas  requiring extensive
sewering  (EIS  Alternatives  1  and  2 and  the  Proposed Action),  it  is
estimated that 30 to 40 acres of land would be used for the construction
of  sewer  lines  and wastewater treatment facilities.  The EIS Alterna-
tives that  rely on decentralized cluster  systems (3, 4,  5  and 6) may
require  significant  acreage for  construction,  but  these  clusters are
concentrated to  the north  of Green Lake,  where sandy-gravelly (non-
prime)  agricultural  land  would be  used.  No treatment  facilities are
proposed  for  the area  of greatest  concentration  of prime agricultural
land, to the south of Green  Lake.
                                    162

-------
E.   ECONOMIC  IMPACTS

1.   INTRODUCTION

     The economic impacts of the alternative  wastewater  systems  proposed
for the Proposed  Green  Lake Service Area  are evaluated  in  this  section.
These  impacts  include:   the financial  pressure  placed on residents  to
move away  from  the  Service  Area;  financial pressure  to  convert  seasonal
residences  to  year-round   residences;  and   the  net  benefits  of  water
quality on the economy of the Green Lake area EIS  Service Area."

2.   USER CHARGES

     User  charges represent  the  costs  billed periodically  to  the waste-
water  system  customers.   Total  annual user  charges have been developed
for  seven alternative  wastewater  systems.   The user charge consists  of
three parts:  debt service (repayment of principal and  interest), opera-
tion  and   maintenance  costs, and  a  reserve  fund  equalling  20% of  the
capital costs.  Annual  user charges are presented in Table V-3 and  are
expressed  in  terms  of  1)  the  entire  Service Area,  2)  the currently
sewered communities  of Spicer  City and New  London Village,  and  3)  the
currently  unsewered  portions of   the  proposed Green  Lake EIS  Service
Area.

a.   Eligibility

     Eligibility  refers  to  that portion of  wastewater  facilities  costs
determined  by EPA to  be  eligible  for  a  Federal  wastewater  facilities
construction  grant.   Capital costs of wastewater  facilities are funded
under Section 201 of the 1972 Federal Water Pollution Control  Act Amend-
ments.  Section 201  enables EPA to fund 85%  of the total eligible capi-
tal  costs  of  innovative and alternative systems.   Innovative  and alter-
native systems considered in the EIS Alternative  include land  treatment,
pressure  sewers,  cluster  systems, and  septic tank rehabilitation  and
replacement.

     The  percentage  of capital  costs  that  is eligible for Federal  and
State  funding greatly  affects the cost that  local users must  bear.  The
capital costs of treatment, on-site  systems, and cluster systems were
assumed  to be  fully  eligible  for  grant  funding.  However, collector
system  capital costs  were   subject  to Program Requirements  Memorandum
(PRM 78-9).   This PRM established three main  conditions  that  must be  met
before collector sewer costs may be declared  eligible:

     •     Systems in use  for disposal of wastes  from the existing popu-
           lation  are creating  a  public  health  problem,  contaminating
           groundwater or violating point  source  discharge  requirements;

     •     Two-thirds of the design  population (year 2000) served by a
           sewer must have  been  in residence  on  October  18,  1972;  and

     •     Sewers  must   be  shown to be  cost-effective  when compared  to
           decentralized or on-site alternatives.
                                    163

-------
                                  Table V-3

                 FINANCIAL BURDEN AND DISPLACEMENT PRESSURE
                                              Spicer/New          Currently
Alternative                Entire System    London Village     Unsewered Area
Facilities Plan Proposed
Action

a Displacement Pressure        1-5%             1-5%                1-5%
a Financial Burden            10-20            10-20               10-20
o Can Afford                  80-90            80-90               80-90

EIS Alternative 1

e Displacement Pressure        5-10%            1-5%                5-10%
o Financial Burden            20-30            10-20               20-30
o Can Afford                  70-80            80-90               70-80

EIS Alternative 2

• Displacement Pressure        1-5%             1-5%                5-10%
« Financial Burden            10-20            10-20               20-30
* Can Afford                  80-90            80-90               70-80

EIS Alternative 3

• Displacement Pressure        1-5%             1-5%                1-5%
• Financial Burden            10-20            10-20               20-30
e Can Afford                  80-90            80-90               70-80

EIS Alternative A

• Displacement Pressure        1-5%             1-5%                1-5%
• Financial Burden            10-20            10-20               10-20
• Can Afford                  80-90            80-90               80-90

EIS Alternative 5

0 Displacement Pressure        1-5%             1-5%                1-5%
« Financial Burden            10-20            10-20               10-20
• Can Afford                  80-90            80-90               80-90

EIS Alternative 6

• Displacement Pressure        1-5%             1-5%                 <1%
• Financial Burden            10-20            10-20               10-20
• Can Afford                  80-90            80-90               80-90

Limited Action

• Displacement Pressure         <1%             1-5%                 <1%
9 Financial Burden             5-10            10-20                1-5
« Can Afford                  90-95            80-90               95-99
                                     164

-------
     A determination of the eligibility of wastewater management facili-
ties in  the Green Lake Study Area  for  Federal funding  has been made by
the  Facilities  Planning  Branch of EPA,  Region  V  (June  1979).   This
determination  stipulates   that  capital  costs  involved  in  95% of  the
publicly-owned  on-site  systems  along  Green Lake   will be  eligible for
85%  Federal  funding.  Ninety-five  (95) percent  of  the cluster system
capital  costs  proposed   in  the decentralized  alternatives  are  to  be
eligible  for  85% Federal  funding.   The State  of Minnesota's  funding of
these  systems will  be 60% of  the  non-Federal  eligible capital costs.

     Furthermore,  gravity  collector  sewer  (not  interceptor)  capital
costs  will- be  80%  eligible  for 75%  Federal  funding.   Pressure  sewer
capital  costs will   be 80%  eligible  for   85% Federal  funding.   State
funding  of these  systems will  be  80% of  the  non-Federal  share of eli-
gible  costs.   Neither hook-ups  for  gravity  and pressure   systems  or
operation  and maintenance (O&M)  costs are  eligible for funding under the
EPA Construction  Grants Program.

b.   Calculation of  User  Charges

     User  charges are  presented in Table  V-4.   The user  charges have
been  calculated  for  two   different conditions:    1)  the  costs of  the
system were divided  equally  among  all of  the system's  users throughout
the  currently  sewered  (Spicer  City  and  New  London Village)  and  the
unsewered  areas,  and 2)  the  costs were prorated  between  the currently
sewered  and  unsewered portions  of  the  Proposed  Service   Area.   The
Facilities  Plan  allocated  local costs to  future  residents  of the Plan's
Proposed  Service Area.  The  authors of the  Facilities  Plan  assumed the
allocation  would  be  based on  each  resident's  proportionate  share of
collection  and  treatment  costs.    The allocation method  of spreading
                               Table V-4

                           ANNUAL USER CHARGES
 Alternative

 Facilities Plan Proposed Action

 E1S Alternative 1

 EIS Alternative 2

 EIS Alternative 3

 . EIS Alternative 4

 EIS Alternative 5

 EIS Alternative 6

 Limited Action
Cost Distributed Evenly
  Over Entire System

      160

      190

      210

      150

      130

      120

      130

      ' 80
  Spicer City/
New London Village

     160

     110
     100

     140

     150

     150

     120
  Currently
Unsewered Areas

   170

   240

   240

   180

   120

   110

   120

    60
    All  on-lot systems  along the  lake  are assumed  to be publicly-owned.
                                     165

-------
costs  throughout  the  entire  system  is presented  for  the  purpose  of
illustration.    To  be  equitable,  the  costs  for areas  to  be  served  by
existing  sewers have  been segregated  from  those  associated with  the
unsewered areas.  This prevents the situation where the sewered areas of
Spicer City and New London Village subsidize the construction and opera-
tion of sewerage in the currently unsewered areas.

     The  calculation of  the  user  charges was  based  on  local  capital
costs being paid  through  the  use of a  30  year bond at 6-7/8% interest.
Some communities may be  eligible for a 40 year loan at 5% interest from
the Farmers Home  Administration  to reduce the financial burden of local
capital costs.  The  Facilities  Plan used an  interest  rate of 7% over a
20  year period  in  the  computation of  the various alternatives  cost.

     The centralized alternatives i.e., Facilities  Plan Proposed Action,
EIS Alternatives 1 and 2 are the most costly to the unsewered area users
(and all  users  if costs  are spread out  over  the entire system).  Total
annual user charges  for  each  household range  from  $160  to $210 for the
entire  system,  $170  to $240  for the unsewered areas,  and  $110  to $160
for the communities Spicer and New London.

     EIS  Alternatives 3,  4,  5,  and  6  combine centralized  and decen-
tralized  components   and  are  less  costly  than the centralized alter-
natives  for  the total  system  and the  currently unsewered areas.    The
costs  of  these alternatives  for Spicer and New London  Village  are not
significantly different from  the costs of the centralized alternatives.
Annual user charges  range from $120 to $150 for the entire system, $100
to  $150  for Spicer  and New London,  and $110  to $180  for  the currently
unsewered areas.

     The  Limited  Action  Alternative offers the  lowest  user  charge over
the entire system and incurrently unsewered areas,  while EIS Alternative
3 offers the lowest user charge in Spicer and New London.

     The decentralized alternatives involve the least amount of sewering
and the  lowest  annual user charges for  the  entire  system and residents
in the currently unsewered areas.

     In addition  to  user  charges, households  in the newly sewered areas
would  have  to  pay  the capital  costs  (approximately $25  to $1,950 for
each connection)  of  a house sewer on their property to connect to grav-
ity and pressure collector sewers.  Seasonal homeowners also may have to
pay  the  full  price  for  the replacement or rehabilitation of their on-
site systems  (septic tanks and soil absorption  systems)  if they do not
cede these systems to the local wastewater management agency.  Assuming,
however,  a high   proportion  of  public on-site  system ownership,  EIS
Alternatives 3, 4,  5 and 6 would  offer a  substantial  reduction in pri-
vate costs.  Overall, private  costr, would vary from household to house-
hold due  to the differences in the distance to the collection sewer and
the condition of on-site systems.
                                    166

-------
3.   LOCAL COST  BURDEN

a.   Significant Financial  Burden

     High-cost wastewater  facilities  may place  an excessive  financial
burden on  users of  the  system.   Excessive burdens  may  cause  families to
alter  their  spending  patterns   substantially  by  diverting  money from
their  normal  expenditure  categories.   The Federal  government has de-
veloped criteria  to identify high-cost  wastewater projects  (The White
House  Rural Development  Initiatives  1978).   A project is identified as
high-cost when the annual user  charges  are:

     •    1.5% of  median household incomes  less than  $6,000;
     •    2.0% of  median household incomes  between $6,000 and $10,000;
          or
     e    2.5% of  median household incomes  greater  than $10,000.

     The 1978 median household  income  for  the proposed Green Lake Study
Area has been estimated  to be  $18,000  for permanent  residents.  No data
are  available  for seasonal resident income  characteristics.   According
to  the Federal criteria,  annual  user charges  should  not  exceed 2.5%
($450) of  the $18,000  median household income figure.  Any  alternative
having annual user  charges  exceeding  $450  is identified as  a  high-cost
alternative and is  likely to place a  financial  burden oh users of the
system.  None of  alternatives are classified as  a  high-cost  alternative
under the Federal  criteria.

     Significant  financial  burden is  measured by  comparing  annual user
charges with the distribution of household  incomes.   Families not  facing
a significant financial  burden  are the only families  able to afford the
annual wastewater user  charges.   The percentage  of households  estimated
to face a significant financial  burden  under each of  the alternatives is
listed in Table V-2.

b.   Displacement Pressure

     Displacement  pressure is  the determination  of  the percentage of
families likely to move away from the  EIS  Service Area as a  result of
costly user charges.  Displacement is measured by determining the  number
of  households  having annual user charges  exceeding  5% of their  annual
income.  Displacement pressure  for each of  the alternatives is  listed in
Table V-2.

     Displacement  pressure for  the entire  system ranges from 1-10% with
the  greatest  displacement pressure occurring  under  EIS Alternative 1.
Residents  of  Spicer  City and New London Village  would  face displacement
pressures of 1-5% under each of the alternatives.   Displacement pressure
is  greatest under EIS  Alternatives 1  and 2  for  the  currently  unsewered
area.
                                   167

-------
c.   Conversion Pressure

     Costs of  providing  wastewater  facilities are likely to accentuate
the  trend of  converting seasonal  residences to  permanent residences
already underway in the area.   Capital  requirements impose a higher cost
burden on seasonal  residences  than  on  permanent  residences on the basis
of relative use.  Seasonal residences are  used only three or four months
during the year are charged  capital  costs  throughout  the year.  This may
place a  financial  burden on  seasonal  residents who are supporting full
year  residences in  addition  to seasonal  residences.  The  higher cost
burden of  centralized alternatives  will exert more  conversion pressure
than the lower cost decentralized alternatives.   The  averaging of opera-
tion  and maintenance  costs  among permanent  and  seasonal  residents  in
addition to capital costs will intensify conversion pressures.

4.   MITIGATIVE MEASURES

     The significant financial burden and  displacement  pressure on users
in  the  currently unsewered areas may  be  mitigated by the selection  of
EIS Alternatives 4,  5  or 6.   The local wastewater management authority
may seek to obtain a loan or grant from the Farmers Home Administration.
Such a loan would decrease annual user  charges by spreading out the pay-
ment  of  the  local  share  over  a  longer  period  of time with  a lower
interest rate.  The impacts  of financial burden on seasonal users may  be
mitigated  by  not.  charging  the  seasonal  residents  for  operation  and
maintenance  during  the  months  that   seasonal  residences  are  vacant.
                                   168

-------
 IMPACT CATEGORY
                                  SECTION V.F.

  COMPARISON OF ENVIRONMENTAL  IMPACTS ASSOCIATED WITH MAJOR SYSTEM ALTERNATIVES

                      IMPACT TYPE
 RESOURCE              & DEGREE    .    IMPACT DESCRIPTION
 Surface Water
 Quality
.Nutrient
'loading
                     Eutrophicatlon
                     potential
Primary:
long-term
                     Primary:
                     long-terra
All Alternatives:
Nutrient loads from septic tank drainfields and municipal'
vastewater treatment plant discharges are reduced with Limited
Action, Proposed Action and EIS Alternatives 1-6, but tributaries
continue to be a major source of phosphorus and nitrogen.
Estimated total phosphorus load (with phosphorus ban)
decreases (relative to existing conditions) as follows:
Green - 27-33*; Nest - 24-27*; Woodcock - 77-921.

All Alternatives:

Green Lake - eutrophlcation potential decreased most sharply
with complete sewering of Service Area (P.A. and EIS Alterna-
tives 1 and 2).  EIS Alternative 5 (spray irrigation), and EIS
Alternative 344 (rapid infiltration):  Sharpest decrease
in loading •» eutrophication potential is still within the
range imposed by existing conditions.

Nest Lake and Woodcock Lake - eutrophication potential
decreases but lake remains eutrophic  (nutrient rich).
Groundwater
                     Groundwater
                     quantity
                     Groundwater
                     quality
Environmentally
Sensitive Areas
Floodplaln
                     Shoreline
                     Primary:
                     long-term
                                          Secondary:
                                          long-term
                     Primary:
                     long-term
                     Secondary:
                     long-term

                     Primary:
                     short-tern
                                          long-term

                                          Secondary:
                                          long-term

                                          Primary:
                                          short- and
                                          long-term
                                          Secondary:
                                          long-term
                 All  Alternatives:
                 Failure  to  return vastewater  flows  to  groundwater  system
                 results  in  negligible  loss  of  groundwater  recharge, to  outwash
                 aquifer(s).

                 All  Alternatives:
                 Losa of  aquifer  surface  recharge  area  as a result  of possible
                 development  of  impervious surface cover  is minimal.       ^^-^'

                 No Action:
                 With the continued  reliance on septic  systems,  there Is the
                 possibility  of  localized high  groundwater  nitrate  concentra-
                 tions.   Phosphorus  from  septic systems will continue to
                 leach in amounts sufficient to support localized algae growth.

                 EIS  Alternatives 1.  2, Proposed Action:

                 Sewering the entire  lakeshore  area  eliminates any  possibility
                 of septic systems as a source  of  nitrates  for localized
                 groundwater  contamination and  phosphorus as a nutrient source
                 for  localized algae  growth.

                 EIS  Alternatives 3,  4, 5. and  6:  A combination of renovation of
                 septic systems  and  cluster  system construction  around  lakeside
                 areas will  significantly reduce nitrate  and phosphorus levels
                 leaching into groundwater systems.

                 All  Alternatives:

                 Impacts  on  flood hazard  areas  are expected to be minimal.

                 EIS  Alternatives 1,  2, 3. and  Proposed Action:

                 Construction impacts are unavoidable and directly  related  to
                 total length of  sewer  lines.

                 Impacts  are  judged  to be minimal.

                 Development  avay from the lake (tiers) may be directly
                 related  to  number of miles  of  sewer lines.

                 EIS  Alternatives 4.  5, 6. and  Limited  Action:

                 Construction impacts will be unavoidable.   Duration of Impacts
                 depends  on  season and method of construction and extent  of
                 restoration.

                 Development  will be  variable in Study  Areas depending  on
                 proximity to sewer  line  or  suitability for  on-lot  soil
                •disposal system.
                                                          169

-------
IMPACT CATEGORY
Environmentally
Sensitive Areas
(Continued)
RESOURCE


Wetland
                     Archaeological/
                     Historical Sites
                     Steep Slopes
                     Prime
                     Agricultural
                     Lands
Population
                     Rate of growth
                                         IMPACT TYPE
                                           & DECREE
                     Primary:
                     short- and
                     long-term
                                          Secondary:
                                          long-term
                     Primary and
                     Secondary:
                     short- and
                     long-term

                     Primary:
                     short-term
                                          long-term
                                          Secondary:
                                         .long-term
                     Primary:
                     short-term
                                          Secondary:
                                          long-term
                     Secondary:
                     long-term
                                                          IMPACT DESCRIPTION
EIS Alternatives 1. 2, 3, and Proposed Action:
Construction Impacts will be unavoidable.  Extent of impact
will be directly related to extent of sewerage.  Duration of
Impact vlll relate to the timing of construction and the
swiftness of restoration.

EIS Alternatives 4, 5, 6, and Limited Action:

Except for unavoidable effects of construction, impacts will
be minimal.

All Alternatives:

Some development may occur near or in verlands, although leas
so in the centralized treatment plans.

All Alternatives!

Potential Impacts due to construction and Induced growth can
be minimized with proper identification of valued sites.


All Alternatives!

Temporary increaaea in erosion and sedimentation can be
minimized with proper construction methods.  Impacts would
be more significant for EIS Alternatives 1, 2, and the
Proposed Action.

EIS Alternatives 3, 4, 5, 6, and Limited Action;
Impacts associated with decentralized alternatives will be
minimal because only systems designed for steep slopes will
be used.

Limited Action;

Development will continue to be minimal, and impacts will be
slight with the use of proper design.

EIS Alternatives 1, 2, and Proposed Action;

Increased development may result with extensive sewerage.

EIS Alternatives 3, &, 5, and 6:

Less  induced growth will result compared to EIS Alternative 1,
2, and Proposed Action.

Limited Action:

No significant  impact is expected  to occur.

EIS Alternatives 1-6 and Propoaed Action:
About 30-40 acres will be used for combinations of  sewer
lines, ditches, lagoons, and/or treatment facilities.

Limited Action:

Large lot  requirements may result  in  some loss of prime
agricultural lands.

EIS Alternatives 3, 4, 5, and 6:
Some prime agricultural  lands may be  lost to  induced growth
near cluster systems.

EIS Alternatives 1, 2, and Proposed Action:

Because  induced growth will occur primarily near the lakes,
less  prime agricultural  land will be  lost.

Proposed Action, EIS Altnmatives 1 and  2;
Population growth  in  projected to  Increase between  5 and  101
above that possible without centralized  facilities.

EIS Alternatives 3, 4, 5, and 6; Limited Action:
Growth opportunities  will be moderate.

No Action;
Growth opportunities  are limited.
                                                         170

-------
IMPACT CATEGORY


Land Use
RESOURCE


Developable
acreage
                                          IMPACT TYPE
                                           & DECREE
                                          Secondary:
                                         .long-term:
Local Economy
                     Development
                     patterns and
                     density
Financial Burden
Displacement
Pressure
                     Secondary:
                     long-term
Primary:
long-term
                     Conversion
                     Pressure
                                                           IMPACT DESCRIPTION
 Proposed Action, EIS Alternatives 1 and 2;

vProvision of site-Independent facilities. Increased the inventory
 of developable acreage.  Less than 30 to 40 lakeshore acres were
 found which were likely to be developed.

 EIS Alternatives 3, 4, 5, and 6; Limited Action:

 Development opportunities are considered to be limited for
 these alternatives.

 Mo Action:

 Development is considered limited.

 Proposed Action, EIS Alternatives 1 and 2:

 Some increase in the density of residential development along
 the lake is likely.

 EIS Alternatives 3, 4, 5, and 6:

 Development density vill remain at approximately the same
 rate.

 Proposed Action, EIS Alternatives 1 and 2:

 Displacement pressure (5-30%) and financial burden (30-60Z)
 are highest for the residents of currently unsewered areas.
 Splcer and New London Village residents would face displace-
 ment pressures ranging from 1-10% and a financial burden
 ranging from 10-40?.

 EIS Alternatives 3. 4. 5, and 6:
 Displacement pressure would range from <1-5Z and financial
 burden from 5-30Z for residents of the currently unsewered
 areas.  The residents of Splcer and New London Village would
 face displacement pressure ranging from 1-5% and a financial
 burden ranging from 10-20%.

 All Alternatives:
 Conversion pressure in the currently unsewered area would be
 highest under the centralized alternatives (Facilities Plan
 Proposed Action, EIS Alternatives 1 and 2) and minimal under
 the decentralized alternatives (EIS Alternatives 3, 4, 5, and
 6).  Conversion pressure would be (moderate for the residents
 of Splcer and New London Village.  Conversion pressure would
 be highest under the Facilities Plan Proposed Action and lowest
 under EIS Alternative 3.
                                                         171

-------
                              CHAPTER VI
                  CONCLUSIONS AND  RECOMMENDATIONS
A.   INTRODUCTION

     As discussed in Section  I.D.I,  EPA  has  several possible courses of
act. on in addition  to  the  Facilities Plan Proposed Action.   The Agency
may

     «    Approve the  original  grant application,  possibly with recom-
          mendations  for   design  changes  and/or measures  to  mitigate
          impacts of the Facilities  Plan  Proposed Action;

     o    Return  the   application  with  recommendations  for additional
          Step I analysis;

     »    With the  applicant's and  State's  concurrence,  approve Step II
          funding for  an  alternative  to the  Facilities Plan Proposed
          Action;

     o    Reject the grant  application.

     The choice of one of  the above  options  depends upon  how the Altern-
atives in the EIS compare  to the  Facilities  Plan Proposed Action.

B.   SUMMARY  OF EVALUATION

     Four primary criteria  were  used in  selecting  the EIS Reommendation
costu,  impact,  reliability,  and   flexibility.   Within  each  category
several  factors  were  compared.    Cost  factors for  example,  included
present worth, user charges for  central  sewered areas,  small waste  flow
district user  charges,  and total  1980 private  costs.  Impacts which EPA
considers to be  decisive  in selection of an alternative are identified
and  considered.   The  reliability  of  alternatives  is  measured against
centralized collection and treatment as the  standard.

     A matrix  offers  a simple way to visualize the relationship between
alternatives and  the  criteria used  to evaluate them.  By tabulating for
each alternative the factors that influence  the range of  choice, one can
quickly  compare  the  effect  of  each alternative upon  that factor.  A
matrix  relating  alternatives to environmental  impacts  is  presented in
Section V.F.   Table VI-1 presents  a matrix  summarizing  the  relationship
between  the  alternatives  and their  costs, environmental impacts, reli-
ability, and flexibility.

     Table  VI-1  also  ranks the  alternatives  according  to  their total
present worth.  This ranking has  two purposes:

     «    Costs  are easily  quantifiable, perhaps  the  least subjective
          measure of value.
                                   172

-------
                                                                                           Table  Vl-l

                                                                                  ALTERNATIVE SELECTION MATRIX
                          COSTS

                              SHALL
                     SP1CER/   HASTE   ONE
                      NEW     FLOW    TIME
             PRESENT LONDON   DISTRICT HOUSE-
              WORTH   USER    USER    HOLD
            (xl.OOO) CHARGE    COSTS  CHARGE
                                                           ENVIRONMENTAL  IMPACTS
                                                                                                                 SOCIOECONOMIC IMPACTS
Facilities
Plan
Proposed
Action
            8.411.3
                      160
                                170   1.950
         vj
         OJ
EIS
Alternative 9,394.2   110
SI
EIS
Alternative 9.475.5   150
12
240
240
         25
         25



SURFACE WATER
QUALITY
IMPACTS
o Nutrient loads
from septic
tank drain-
fields and
municipal
wastewater
treatment
plant dis-
charges are
'
• Tributary
continues to
be a major
source of
. nutrients
• Estimated
phosphorus
load de-
creases 27-
33Z for
Green Lake
and 24-27Z
for Neat
Lake
• Eutrophica-
tlon> poten-
tial sharply
decreases
• Neat and
Woodcock
Lakes remain
eutrophic .
Same as
Proposed
Action
Same as
Proposed
Action



CROUNDWATER
QUALITY
IMPACTS
• Elimination of
septic systems
as a source of
any ground-
water pollu-
tion
























Same as
Proposed
Action
Same as
Proposed
Action


ENVIRON-
MENTALLY
SENSITIVE
AREAS
o Construction
Impacts are
unavoidable
and direct-
ly related
to the num-
ber of sewer
miles
• Long-term
Impacts are
minimal
• Possible in-
creased
development
away from
the lake may
encroach In
sensitive
areas.













" Same a a
Proposed
Action
Same as
Proposed
Ac t ion




POPULATION
IMPACTS
Population
increase
of 5-10Z
greater
than
expected
























Same as ~
Proposed
Action
Same as
Proposed
Ac t ion




LAND
USE
• Increase In
density of
residential
development
around
lake shore
areas is
likely
• Less than
30 to 40
lakeshore
acres are
likely to
be develop-
ed

















Same as
Proposed
Action
Same as
Proposed
Action
FINANCIAL DISPLACEMENT
BURDEN Z PRESSURE Z
SMALL SMALL
SPICER/ WASTE- SPICER/ WASTE-
NEW FLOW NEW FLOW
LONDON DISTRICT LONDON DISTRICT
20- 30- 5- 5-
30Z 40Z 10Z 10Z




























10- 50- 1- 20-
20Z 60Z 51 30Z

10- 40- 1- 10-
202 50Z 5Z 20Z

                                                                                                                             FLEXIBILITY
                                                                                                                         Reduced  flexibility
                                                                                                                         In  terms of  design
                                                                                                                         changes; but there
                                                                                                                         is  flexablllty  for
                                                                                                                         added  treatment
                                                                                                                         capacity
                                                                                                                        Same as Proposed
                                                                                                                        Action
                                                                                                                        Same as Proposed
                                                                                                                        Action
                                                                                                                                                  RELIABILITY
High, centralized
collection and
treatment haa been
tested and proven.
Pumps may be subject
to periodic failure.
Higher than Proposed
Action because of
fever pumps subject
to failure.

Same aa Proposed
Action

-------
                                                                                           Table  VI-1
                                                                             ALTERNATIVE SELECTION MATRIX (Continued)
                          COSTS

                               SHALL
                     SPICER/   WASTE   ONE
                      NEW      FLOW    TIME
             PRESENT LONDON  DISTRICT HOUSE-
              WORTH   USER     USER    HOLD
            (xl.OOO) CHARGE    COSTS  CHARGE
EIS
Alternative 6,113.7   100
03
180
        470
EIS
Alternative 5,092.6   140
04
EIS
Alternative 5,365.5   150
15
EIS
Alternative 4,507.5   150
06
Limited     2.887.2   120
Action
Alternative
120
110
120
                                 60
        190
        190
        190
ENVIRONMENTAL IMPACTS

SURFACE WATER
QUALITY
IMPACTS
Same as
Proposed
Action except
nutrient load-
Ing from
septic tank
will be re-
duced but not
eliminated
Same as EIS
Alternative 03

Same as EIS
Alternative 03

Same as EIS
Alternative 03

Same as EIS
Alternative 03


CROUNDWATER
QUALITY
rMPACTS
• Significant
reduction of
nitrate and
phosphorus
levels leach-
Ing Into ground-
water systems.
but not
eliminated
Same as EIS
Alternative 03

Same as EIS
Alternative 03

Same as EIS
Alternative 03

Same as EIS
Alternative 03

ENVIRON-
MENTALLY
SENSITIVE
AREAS
Same as
Proposed
Action






Same as
Proposed
Action
Same as
Proposed
Action
Same as
Proposed
Action
Same as
Proposed
Action


POPULATION
IMPACTS
Growth •
opportun-
ities will
be moder-
ate




Same as EIS
Alterna-
tive 03
Same as EIS
Alterna-
tive 03
Same as EIS
Alterna-
tive 03
Same as EIS
Alterna-
tive 03
SOCIOECONOMIC IMPACTS
FINANCIAL
BURDEN Z


LAND
USE
Development
opportuni-
ties for
this type of
alternative
is consider-
ed limited


Same as EIS
Alternative
03
Same as EIS
Alternative
03
Same as EIS
Alternative
03
Same as Els
Alternative
03

SPICER/
NEW
LONDON
10-
20Z







10-
20Z

10-
20Z

10-
20Z

10-
20Z

SMALL
WASTE-
FLOW
DISTRICT
20-
30Z







5-
10Z

5-
10Z

10-
20Z

1-
5Z

DISPLACEMENT
PRESSURE Z

SPICER/
NEW
LONDON
1-
51







1-
5Z

1-
5Z

1-
5Z

1-
5Z

SMALL
WASTE-
FLOW
DISTRICT FLEXIBILITY
1- Increased flexibll-
5Z ity for future land
planning because of
the decentralized
nature of the
alternative; good
flexablllty for
adding treatment
capacity
<1Z Same as EIS
Alternative 03

<1Z Same as EIS
Alternative 03

<1Z Same as EIS
Alternative 03

<1Z Same as EIS
Alternative 03

                                                                                                                                                                                  RELIABILITY
Limited:  Proper
maintenance of on-8lte
and cluster systems
should Improve reli-
ability of these sys-
tems.  Any systems
located In areas of
marginal soils, shal-
low geology or shallow
water will be subject
to failure.

Same as EIS Alterna-
tive 13
                                                                                                                                               Same as EIS Alterna-
                                                                                                                                               tive 03
                                                                                                                                               Same as EIS Alterna-
                                                                                                                                               tive 03
                                                                                                                                               Same as EIS Alterna-
                                                                                                                                               tive 03

-------
     o    EPA  Construction  Grants, regulations require  selection  of the
          most  cost-effective Jalternative,   that  is,  the  alternative
          meeting project goals  with  the least total present worth with
          acceptable..environmental and socioeconomic impacts.

     Selection of the cost-effective alternative requires identification
of trade-offs  between ;costs and other criteria.   The evaluation factors
.included with total present worth in Table VI-1 are those EPA has deter-
mined to be  most  important in identifying trade-offs  for  this project.

C.   CONCLUSIONS

     In  regard to the  existing  on-site  systems  around Green  Lake and
Nest Lake, information  gathered  during the preparation of  this EIS has
indicated the following:  1) Approximately 25 effluent plumes were found
entering Green Lake  and  12 entering  Nest Lake.  2)  Five  septic  system
surface  malfunctions*  were  confirmed by field  verification  of  aerial
photography.   3)  Sanitary  surveys  have   revealed  that periodic  sewage
backups  in  some  households  have  occurred.   4)  Effluent  plumes  from
septic systems  do not  contribute significant quantities of nutrients to
Green  Lake  or Nest  Lake.   While  detailed  site-by-site   analysis  may
reveal more  problems,  field studies conducted so far  indicate that the
percentage of systems causing problems are small.

     Most of the  on-site systems presently in use within the EIS Service
Area are poorly maintained  and many are inadequately designed.  Routine
maintenance  for all  on-site  systems  and upgrading  of inadequately de-
signed systems will  substantially reduce the  number  of problems  caused
by them.

     Where problems cannot be solved by routine maintenance or upgrading
alone, alternatives  to the  conventional septic tank  --  subsurface ad-
sorption systems  are  feasible in the Study Area which will minimize or
eliminate the problems.

     Future  growth in  the  Green Lake watershed  depends  on how many new
lots  can be  developed  and  the  allowable density.   Wastewater disposal
alternatives relying on  continued use of on-site systems as compared to
extensive sewering around the lake would restrict both the number of new
lots as  well as their density.  An effect of these limitations would be
to preserve  the present character of the community.

     Total present  worth  for the centralized  alternatives (Facilities
Plan  Proposed  Action,  EIS  Alternatives  1, 2, and  3)  are  substantially
higher than  for the  decentralized alternatives  (EIS  Alternatives 4, 5,
6, and Limited Action).   As  calculated in this EIS, the Facilities Plan
Proposed Action  is 57%  more expensive  than  EIS Alternative  5 and 91%
more  expensive than  Limited  Action.   Differences  in  water quality im-
pacts  of  the  alternatives  are  not  proportionate  to  these  large dif-
ferences in  costs.

     Because  of  the  high  costs  and  limited  benefits  to  water quality
with  the centralized alternatives  (Facilities Plan  Proposed Action and
EIS  Alternatives  1,  2  and  3),  they are  not  cost-effective and are not
recommended.

                                   175

-------
     The  No  Action  Alternative  was  unacceptable   for  three  reasons:

     e    Existing treatment  plants  at  New  London and  Spicer do  not
          comply with effluent requirements  and  contribute  substantially
          to  high productivity in Nest Lake  and  Woodcock  Lake.

     o    There are some problems with on-site  systems in  the  remainder
          of  the  Proposed EIS  Service Area  which  should  be  addressed
          through monitoring,  improved maintenance  of the existing  and
          future systems,  residential water  conservation, and  renovation
          or  replacement of existing systems.

     o    Improved surveillance and  regulation of on-site systems  in  the
          Green  Lake watershed  to  insure   maintenance  of  the  lake's
          unique scenic  and recreational values  is recommended.

     The  remaining  alternatives,  EIS  Alternatives  4,  5 and 6,  include
the use.1 of alternative  on-site and  small scale  off-site systems  around
Green Lake and  Nest Lake.   They differ in their  methods  for treating  and
disposing of New  London's  and Spicer's wastewaters:  Alternative  4 uses
joint pretreatment and rapid infiltration; Alternative 5  uses  joint pre-
treatment  and   spray irrigation;  and  Alternative   6  employs  separate
tertiary treatment facilities for both communities.

     Costs and  environmental impacts are similar for these  three altern-
atives. .  Lack  of  detailed data  on  site  characteristics  creates  some
uncertainty in  the determination of  reliability for  the  land  application
alternatives.   In  addition the  possible  unavailability  of  land  appli-
cation sites  may prove a potential problem for implementation.

D.   DRAFT EIS RECOMMENDATIONS                                i

     Because  EIS  Alternatives  4 and  5  (decentralizedi  approaches with
land  application)  and 6  (decentralized  approach with upgrade/expansion
of  wastewater  treatment  plants  at  Spicer  and  New  Lont'on)  can  all  be
considered cost-effective,  and because  they differ  sul^stariitally from
the   Facilities  Plan  Proposed  Action  (centralized < approach with
stabilization  ponds),  the recommendation of  this EIS is  to  return  the
grant  application  to the  Green  Lake  Sanitary Sewer  and Water District
(GLSSWD)  for  additional   Step  1  analysis.   The  scope;  of  additional
analysis  will  depend  on  the  applicant's own   decisions,  regarding  the
feasibility  of the small  waste  flows approach  for Greco  Lake  and Nest
Lake  and  the merits  of  land application for wastewaters  from Spicer  and
New London.                                              :

     Alternatives 4,  5,  and  6 differ in the type and location of treat-
ment  and  disposal  facilities  for Spicer's and New London's wastewaters.
The  GLSSWD will need to  conduct additional Step 1  analyses,  funded by
EPA,  of  alternatives  to  serve  Spicer  and  New   London  jointly   or
separately.  EPA encourages the use  of land  application  an'd will require
evaluation of   land  application  including  detailed site 'analyses.   If
GLSSWD  chooses Alternative  6,  the  Step 1  analyses must include  the
following:                                                 •
                                   176

-------
     •    Applicant's  own analysis  of  the  feasibility  and  costs  of
          treatment plant upgrading;

     •    Engineering,  cost  and environmental  analysis  of sludge  man-
          agement options; and

     •    Engineering,  cost,  and  environmental  analysis  of  effluent
          disinfection options.

EPA  will  participate  in funding additional  site  specific analyses  of
existing on-site systems, their design,  usage and environmental impacts.
These additional analyses will address:

     •    Development  of  a site-specific environmental  and  engineering
          data base;

     •    Design of the management  organization; and

     •    Start-up of the management  district.

The  applicant  will need  to  complete additional Step  1  requirements  by
taking the following actions  (40 CFR  35.918):

     •    Certify  that construction  of the  project  and  operation  and
          maintenance  program  will  meet   local,   State  and  Federal
          requirements.  As  a  first  step,  this certification involves a
          lot-by-lot  investigation of existing septic tank  systems  and
          site  suitability  for wastewater  treatment.   If  it can  be
          demonstrated  that  existing systems do not degrade  lake  water
          quality  or  promote public  health  problems,  despite  the  find-
          ings  of  the lot-by-lot  investigation,  then  the  GLSSWD  may
          initiate  variance   procedures  for  these  systems  under  the
          Minnesota Shoreland  Management Act which  has been adopted and
          amended by Kandiyohi County.  The specific variance that  would
          be  negotiated  between the  GLSSWD and the County involves  the
          Act's  stipulation  that  there be  a 4-foot  vertical  distance
          between  the  bottom  of  the  septic tank  drainfield and  the
          highest known groundwater elevation.

     •    Obtain assurance of unlimited access to each individual system
          at  all  reasonable  times  for such  purposes  as  inspections,
          monitoring,  construction,  maintenance, operations,  rehabili-
          tation and replacement.

     •    Plan  for  a  comprehensive program of regulation and inspection
          for individual systems.
E.   IMPLEMENTATION

     Management  of  centralized and  decentralized  wastewater facilities
is  discussed  in Section III.D. and Appendix  1-3.   Two  topics which the
District will  have  to address in regard  to  small  waste flow management
are discussed below.
                                   177

-------
1.   COMPLIANCE  WITH  STATE  AND  LOCAL  STANDARDS  IN
     THE  SMALL WASTE  FLOWS  DISTRICT               j
     As discussed in Section  II.C. many  existing on-site systems do not
conform to  current  design standards  for site,  design o.r distance from
wells  or  surface waters.   For  some  systems,  such  as  those with under-
sized  septic  tanks,  non-conformance  can  be  remedied  relatively easily
and  inexpensively.   In other cases   the remedy may  b-.i  disruptive and
expensive and should be undertaken only  where the  need jis  clearly  iden-
tified.   Data  on the  effects  of  existing systems indicate • that many
existing  non-conforming systems, and  future  repairs thiit still may not
conform to  design  standards,  may operate  satisfactorily.   Where com-
pliance with design, standards  is either  1)  unfeasible jor too expensive
or 2) site monitoring  of ground and surface waters  shows  that acceptable
ircpacts are  attainable,  then  a variance procedure tojallow renovation
and continued use of non-conforming system is  recommended.  Decisions to
grant variances  should be based on  site-specific  data Jor on a substan-
tial history of similar sites in the  area.
                                                      I
     Local and  state  decisions on variance  procedures would likely be
influenced by  the degree of  authority vested  in  the  small waste  flows
district.   If  the district  has the  authority and sufficient financial
means to  correct  errors,  plus the  trained personnel  to minimize errors
in  granting  variances, variance  procedures may  be   more  liberal than
where  financial  and professional  resources are  limited.  Higher  local
costs, caused by  unnecessary  repairs  or  abandonment of systems would be
expected  to  result from  very conservative or  no  variance guidelines.
Conversely,  ill-conceived or  improperly  implemented variance procedures
would cause frequent water quality problems and demands  for more expen-
sive off-site technologies.

2.   OWNERSHIP  OF ON-SITE SYSTEMS SERVING  SEASONAL RESIDENCES

     Construction Grants  regulations  allow Federal funding for renova-
tion and replacement of publicly owned on-site systems  serving permanent
or seasonally occupied residences and of  privately  owned  on-site systems
serving   permanent    residences.    Privately   owned   systems   serving
seasonally  occupied  residences- are  not  eligible  for Federally funded
renovation and replacement.

     Depending  on the extent and  costs  of  renovation and replacement
necessary for  seasonal  residences, the  municipalities or a small  waste
flows  district  may  elect to  accept  ownership of  the on-site systems.
Rehabilitation  of  these  systems would   then be   eligible  for Federal
assistance,  and local  costs  for seasonal  residents  would  be dramatically
reduced.  Any  decision to  accept  ownership on  a  community-wide  basis
should  await the  conclusions  of  the site-specific  environmental and
engineering analyses  and  preliminary determination of the functions of
the management agency.  Ownership of seasonally used  systems may create
responsibilities that  the  agency is not  equipped to discharge.
                                   178

-------
                             CHAPTER VII

             THE RELATIONSHIP  BETWEEN SHORT-TERM USE
                    AND  LONG-TERM PRODUCTIVITY
A.   SHORT-TERM USE OF  THE STUDY AREA

     The Green Lake  Study Area has been, and will  continue to be used as
a residential/recreational  area.   The  site was initially disturbed when
construction of houses began approximately 20 years  ago.

     Disturbance of  the  site by routine residential/recreational activi-
ties will continue.   Implementation of either the  action proposed by the
Facilities  Plan  or   recommended  in  this  EIS  is  not  expected  to alter
these disturbances.
B.   IMPACTS UPON LONG-TERM  PRODUCTIVITY

1.   COMMITMENT  OF NON-RENEWABLE RESOURCES

     If  the  Facilities  Plan Proposed Action were  implemented,  an in-
creased potential  for  development may result in  some  loss  of terrestrial
habitat.  Such would be expected to a lesser extent by  implementation of
the EIS Recommendations.

     Non-renewable resources associated with either action would include
concrete for  construction.  Consumption of electric  power by pumps may
also increase.  Manpower  would  also be committed to  the construction,
operation and management of new or rehabilitated facilities.

2.   LIMITATIONS OF BENEFICIAL USE  OF THE ENVIRONMENT

     Aquatic recreation  is one of the major benefits enjoyed  by people,
residents  and  visitors  alike,  in the  Green Lake  Study Area.  Public
access  to  this  5400 acre  recreational resource  has  become increasingly
restricted over the past  20 years, with approximately 85% of  the  Green
Lake  shoreline  currently  supporting  year-round and  seasonal cottage
development.  It  is judged  that  the implementation of any centralized
wastewater management plan, such  as the Proposed Action or EIS Alter-
natives  1  and  2,  would  significantly  increase the  current  level of
recreational  activity through  induced  near-shore  development.    This
activity may become aesthetically  displeasing to current  residents,  many
of  whom come to  Green Lake  during  the vacation season  to leave  urban
crowds.  The  implementation of decentralized EIS alternatives  (3,  4, 5,
6,  and  Limited Action)  would have  a   less  significant  effect  on the
recreational  benefits  of  the Green Lake  area, because   induced growth
would be less dense and more scattered than that afforded  by centralized
wastewater management.
                                  179

-------
                             CHAPTER  VIII

    IRREVERSIBLE  AND  IRRETRIEVABLE  COMMITMENT  OF  RESOURCES
     The resources that would be committed during implementation  of  any
of the EIS Recommendations include those associated with construction and
maintenance  of  wastewater systems.   These  were  discussed  in Section
VI.B.I.

     In  addition.! growth expected  in the Study  Area  would -require  a
commitment ,of  resources  to  the  construction  of  new  dwellings  and
commercial  establishments,  construction  or  improvement  of  roads  and
facilities associated  with water sports.  Besides construction materials,
such  as  lumber,  steel,  concrete  and  glass,  electricity and  manpower
would also be committed to new development.

     Human resources  would include  construction  personnel and, perhaps
infrastructural  personnel to service the added community needs.
                                   180

-------
                             CHAPTER  IX

       PROBABLE  ADVERSE IMPACTS WHICH CANNOT  BE AVOIDED
     If  the  action proposed by  the  Facilities  Plan were  implemented,
some destruction of  terrestrial  habitat would result  from  construction
of new  dwellings.   Such  would  be true,  but to a lesser extent, if  any
EIS Recommendations were  implemented.

     Construction of  sewage  lagoons or new sewer  lines  would disturb  the
soil, resulting in  sediment  runoff.  This runoff  would  cause a  temporary
increase in siltation in both  streams and offshore  areas.   This  type of
runoff  can  also  be caused  by  the  extensive  excavation  required during
upgrade  or  rennovation  of  on-site septic  systems  and off-site  cluster
systems.
                                   181

-------
                               GLOSSARY
ACTIVATED SLUDGE PROCESS.  A method of secondary wastewater treatment in
     which a  suspended microbiological culture is maintained  inside an
     aerated treatment basin.   The  microbial  organisms oxidize the com-
     plex organic matter in the wastewater to  carbon dioxide,  water, and
     energy.

ADVANCED WASTE TREATMENT.   Wastewater treatment beyond the secondary or
     biological  stage  that  includes removal of nutrients  such as  phos-
     phorus  and  nitrogen  and  a  high percentage  of  suspended  solids.
     Advanced waste treatment,  also known as  tertiary treatment,  is the
     "polishing  stage"  of  wastewater  treatment  and  produces  a  high
     quality of effluent.

AEROBIC.  Refers to life or processes that occur only in the presence of
     oxygen.

ALGAL BLOOM.  A  proliferation of algae on the surface of lakes,  streams
     or  ponds.   Algal  blooms  are  stimulated by  phosphate  enrichment.

ALKALINE.  Having  the qualities  of a base,  with  a pH of more  than 7.

ALLUVIAL.  Pertaining  to material  that  has been  carried by  a  stream.

ALTERNATIVE  TECHNOLOGY.   A  technology  whose  use  has been widely sup-
     ported  by  experience,  but  is  not a  variant  of  conventional bio-
     logical or physical/chemical treatment.

AMBIENT AIR.   The unconfined portion of the atmosphere; the outside air.

ANAEROBIC.   Refers  to life  or processes  that  occur in  the  absence of
     oxygen.

ANNULAR  SPACE.    The   open  space between particles  of  soil  material.

AQUATIC  PLANTS.   Plants  that  grow in water,  either  floating on the
     surface, or rooted emergent or submergent.

AQUIFER.  A  geologic  stratum or unit that contains water and will allow
     it  to  pass through.   The water may  reside   in  and  travel  through
     innumerable spaces between rock grains in a sand or gravel aquifer,
     small  or  cavernous openings  formed  by solution  in a  limestone
     aquifer, or fissures,  cracks,  and  rubble in such harder rocks as
     shale.

ARTESIAN AQUIFER.  A  water-filled layer  that  is sufficiently compressed
     between less permeable  layers  to cause the water to rise above the
     top  of  the aquifer.   If the  water  pressure  is  great,  water will
     flow freely from artesian wells.

ARTESIAN  WELL.   A well  in  which flow  is sustained  by the hydrostatic
     pressure of the aquifer.  See Artesian Aquifer.
                                   182

-------
BACTERIA.  Any of a large group of microscopic organisms living in soil,
     water or organic matter,  important to man because of their chemical
     effects as  in  nitrogen  fixation,  putrefaction,  or fermentation,  or
     as pathogens.

BAR SCREEN.  In wastewater treatment,  a screen that removes large float-
     ing and suspended solids.

BASE  FLOW.   The  rate  of movement  of  water  in  a  stream  channel  which
     occurs typically during rainless  periods when stream flow is main-
     tained largely or entirely by discharges of groundwater.

BASIC  USAGE.   In  regard to  functions of  small waste  flow  districts,
     those  which  would  be  required  to  comply with EPA  Construction
     Grants regulations governing individual on-site  wastewater systems.

BEDROCK.  The solid rock beneath the soil and subsoil.

BIOCHEMICAL  OXYGEN DEMAND  (BOD).   A  measure of  the amount  of  oxygen
     consumed in  the  biological  processes that decompose organic matter
     in water.   Large  amounts  of organic waste  use  up  large1  amounts  of
     dissolved oxygen;  thus,  the  greater the degree  of pollution,  the
     greater the BOD.

BIOMASS.   The  weight of  living  matter in a  specified  unit of environ-
     ment.   Or,  an expression of  the  total  mass  or weight  of  a given
     population of plants or animals.

BIOTA.  The plants and animals  of an area.
BOD .    See  "Biochemical Oxygen  Demand."   Standard measurement  is made
     for 5 days at 20°C.
BOG.   Wet,  spongy  land;  usually  poorly  drained,  and  rich in  plant
     residue, ultimately producing highly acid peat.

CALCASEOUS.  Resembling,  containing  of composed  of  calcium  carbonate.

CAPITAL  COSTS.   All. costs  associated  with installation  (as  opposed to
     operation) of a project.

CAPITAL EXPENDITURES.  See Capital Costs.

CHLORINATION.  The  application  of chlorine to drinking water, sewage or
     industrial  waste  for  disinfection   or  oxidation  of  undesirable
     compounds.

COARSE FISH.  See Rough Fish.

COLIFORM BACTERIA.   Members  of  a large group of  bacteria  that flourish
     in  the feces and/or intestines of warm-blooded animals, including
     man.   Fecal  coliform bacterial,  particularly Escherichia coli (E.
     coli),  enter  water  mostly  in fecal matter, such as sewage or feed-
                                   183

-------
     lot  runoff.   Coliform  bacteria apparently  do  not  cause  serious
     human diseases,  but these organisms are abundant in polluted waters
     and  they  are  fairly easy  to  detect.   The  abundance of  coliform
     bacteria  in  water,  therefore,   is   used  as  an  index  to  the
     probability  of  the  occurrence of  such  diease-producing  bodies
     (pathogens)  as  Salmonella,  Shigella,  and  enteric viruses.   These
     pathogens are relatively difficult  to  detect.

COLIFORM  ORGANISM.   Any of  a  number of organisms common to  the intes-
     tinal tract  of  man and  animals whose presence  in  wastewater is an
     indicator  of  pollution  and   of  potentially  dangerous  bacterial
     contamination.

COMMINUTOR.  A machine that breaks  up wastewater solids.

CONNECTION FEE.  Fee charged by municipality to  hook up house connection
     to lateral sewer.

CLUSTER  SYSTEM.   A  soil  dependent  waste  disposal  system  that  uses  a
     common septic drainfield for up to  25  individual residences.

CRUSTACEANS.    Zonal   growths  of  algae,  masses,  lickens, or  liverwarts
     having variable  coverage  and  thickness of only  a  few  centimeters.

CUBIC FEET PER SECOND (cfs).   A measure  of  the amount of water passing a
     given point.

CULTURAL  EUTROPHICATION.  Acceleration by  man  of  the  natural  aging
     process of bodies of water.

DECIDUOUS.  The term  describing  a  plant that periodically  loses all of
     its  leaves,  usually in  the  autumn.  Most broadleaf  trees  in North
     America,  and  a  few conifers,  such  as  larch and cypress,  are decid-
     uous .

DECOMPOSITION.  Reduction of the net energy level  and change in chemical
     composition  of   organic  matter by action  of  aerobic  or anaerobic
     microorganisms.    The breakdown  of complex  material  into  simpler
     substances by chemical or biological means.

DETENTION  TIME.   Average  time required to flow through  a  basin.  Also
     called retention time.

DETRITUS.  (1) The heavier debris moved  by natural watercourses, usually
     in  bed  loam  form.   (2) The sand,  grit, and  other coarse material
     removed by differential sedimentation  in a relatively short period
     of detention.

DISINFECTION.  Effective killing by  chemical  or  physical  processes of
     all  organisms capable of causing infectious  disease.  Chlorination
     is  the  disinfection  method commonly  employed  in  sewage treatment
     processes.
                                   184

-------
DISSOLVED  OXYGEN  (DO).   The  oxygen  gas  (0  )  dissolved  in water  or
     sewage.  Adequate  oxygen  is  necessary for maintenance of  fish and
     other  aquatic  organisms.   Low  dissolved  oxygen  concentrations
     generally are  due  to presence  of excessive organic  solids  having
     high BOD in inadequately treated wastewater.

DRAINAGE BASIN.   (1)  An area from which  surface  runoff  is carried away
     by  a  single drainage system.   Also  called  catchment area,  water-
     shed,  drainage  area.    (2) The  largest natural  drainage  area sub-
     division of a continent.  The United States has been divided  at one
     time or  another, for  various administrative purposes, into some 12
     to 18 drainage basins.

DRAINAGEWAYS.   Man-made  passageways,  usually lined with grass  or rock,
     that carry runoff of surface water.

EFFLUENT.  Wastewater or other liquid,  partially or completely treated,
     or  in  its  natural  state,  flowing out of a reservoir,  basin,  treat-
     ment plant, or industrial treatment plant, or part thereof.

EFFLUENT LIMITED.  Any  stream  segment for which  it  is  known  that water
     quality  will meet  applicable  water quality  standards  after  the
     application of effluent limitations.

ELEVATED  MOUND.    A   mound,  generally  constructed  of  sand,  to  which
     settled  wastewater  is   applied.  Usually  used  in  areas  where con-
     ventional on-site treatment is inadequate.            '  ,,

ENDANGERED  SPECIES  (FEDERAL  CLASSIFICATION).  Any  species- of  animal or
     plant declared  to  be  in known danger of  extinction throughout all
     or  a  significant part  of its  range.   Protected under  Public Law
     93-205 as amended.

ENDANGERED  SPECIES  (STATE  CLASSIFICATION).   Minnesota's  list  includes
     those species on the Federal list that are resident for any part of
     their life cycle in Minnesota.  It also includes indigenous species  J
     the State believes  are uncommon and in need of study.
                  i
ENDECO.  Type 2100 Septic Leachate Dector.  See "Septic Snooper".

ENVIRONMENT.   The  conditions  external  to a particular object,  but
     generally  limited   to   those  conditions  which have  a direct  and
     measurable  effect  on  the object.   Usually  considered  to  be the
     conditions  which   surround   and  influence  a  particular  living
     organism,  population,  or  community.   The  physical  environment
     includes  light,  heat,   moisture,   and  other  principally  abiotic
     components.   The components  of the  biotic environment  are other
     living organisms and their products.

ENVIRONMENTAL  IMPACT STATEMENT.   A  document  required by  the  National
     Environmental  Policy  Act  (PL  91-190,  1969)  that  is used  in the
     decision-making  process  to  evaluate  the effects  (impacts)  of  a
     proposed action on the human, biological,  and physical environment.
                                   185

-------
EPILIMINION.  The  upper layer  of  more or  less  uniformly warm,  circu-
lating,  and  fairly   turbulent  water  in  lakes   during   the   spring
heating season.

EROSION.  The process by which an object is eroded,  or worn away,  by the
action  of   wind,   water,   glacial   ice,   or   combinations   of   these
agents.  Sometimes used  to  refer  to  results  of  chemical  actions  or
temperature  changes.    Erosion  may  be  accelerated  by  human  activ-
ities .

EUTROPHIC.   Waters  with a  relatively large concentration  of  nutrients
and  hence  'a  large production  of organic  matter,  often  shallow,  with
periods of oxygen deficiency.

EUTROPHIC LAKES.   Shallow  lakes,  weed-choked  at the edges and  very rich
     in  nutrients.   The  water  is  characterized  by  large  amounts  of
     algae, low  water transparency,  low dissolved oxygen  and  high BOD.

EUTROPHICATION.   The normally slow aging process by which a lake evolves
     into  a  bog or marsh,  ultimately  assumes a completely  terrestrial
     state  and  disappears..  During  eutrophication  the  lake becomes so
     rich  in  nutritive compounds,  especially  nitrogen  and  phosphorus,
     that  algae  and plant  life become  superabundant,  thereby  "choking"
     the lake and  causing  it eventually to dry  up.   Eutrophication may
     be accelerated by human activities.

EVAPOTRANSPIRATION.   A process by  which  water  is evaporated  and/or
     transpired from water, soil, and plant surfaces.

FECAL  COLIFORM  BACTERIA.    The  group of organisms common  to the  intes-
     tinal tracts of man and of animals.  The presence of fecal coliform
     bacteria in water  is  an indicator of  pollution  and of  potentially
     dangerous bacterial contamination.

FLOE.  A sheet of floating  ice.

FORCE MAIN.  Pipe designed  to carry wastewater under pressure.

GLACIAL DEPOSIT.   A mass  of rock, soil, and earth material deposited by
     a  melting  glacier.   Such material  was  originally picked  up and
     carried  along  its path by  the  glacier,  and  usually  varies  in
     texture  from  very  fine  rock  flour  to  large  boulders.   Named
     according to their location and shape.

GLACIAL DRIFT.   Material which  has  been  deposited  by  a  glacier or in
     connection  with  glacial  processes.   It  consists  of  rock  flour,
     sand,  pebbles,  cobbles, and  boulders.  It may  occur in a  heter-
     ogeneous mass or  be  more  or  less  well-sorted, according  to its
     manner of deposition.

GRAVITY  SYSTEM.    A  system  of  conduits  (open  or  closed) in which no
     liquid pumping is  required.

GROUNDWATER.  Water that is below the water table.
                                   186

-------
GROUNDWATER  RUNOFF.   Groundwater  that  is   discharged  into  a  stream
     channel as spring or seepage water.

HABITAT.   The  specific place  or the  general  kind of  site  in which  a
     plant  or  animal  normally  lives  during  all  or  part  of  its  life
     cycle.

HOLDING TANK.  Enclosed tank, usually of fiberglass or concrete, for the
     storage  of  wastewater  prior  to  removal  or  disposal  at  another
     location.

HYDROPONIC.  Refers  to  growth  of plants in a nutrient solution, perhaps
     with the mechanical support of an inert medium such as  sand.

HYPOLIMNION.  Deep, cold and relatively undisturbed water separated from
     the surface layer in lakes.

IGNEOUS.   Rock  formed  by  the  solidification of  magma  (hot  molten
     material).

INDIAN MOUND SYSTEM.  See Elevated Mound.

INFILTRATION.  The  flow of  a  fluid  into  a  substance  through  pores or
     small openings.  Commonly  used  in hydrology to denote the flow of
     water into soil material.

INFILTRATION/INFLOW.  Total  quantity of water  entering  a sewer system.
     Infiltration means  entry  through such  sources as  defective  pipes,
     pipe joints, connections,  or manhole walls.  Inflow signifies dis-
     charge  into  the  sewer  system through service  connections from such
     sources as  area or foundation drainage,  springs  and swamps,  storm
     waters, street wash waters, or sewers.

INTERCEPTOR  SEWERS.   Sewers used to  collect  the  flows from  main and
     trunk  sewers  and carry them to a central  point  for treatment and
     discharge.   In  a combined  sewer system,  where  street runoff from
     rains is  allowed  to  enter the system along the sewage,  interceptor
     sewers allow some of the sewage to flow untreated directly into the
     receiving  stream,  to  prevent the treatment plant  from being over-
     loaded.

INNOVATIVE  TECHNOLOGY.   A   technology  whose  use  has  not  been  widely
     documented  by  experience   and  is  not  a  variant  of  conventional
     biological or physical/chemical treatment.

LAGOON.   In  wastewater  treatment, a shallow pond,  usually man-made, in
     which  sunlight,  algal  and bacterial action and  oxygen interact to
     restore the wastewater to  a reasonable state of purity.

LAND TREATMENT.   A  method  of treatment in which the  soil,  air, vegeta-
     tion, bacteria,  and fungi  are  employed  to remove pollutants from
     wastewater.   In its most  simple  form,  the method  includes  three
     steps:  (1)  pretreatment  to screen out large  solids; (2) secondary
     treatment  and  chlorination; and  (3)  spraying over cropland, pas-
                                   187

-------
     ture, or natural vegetation to allow plants and soil microorganisms
     to remove additional pollutants.   Much of the sprayed water evapo-
     rates, and the  remainder  may be allowed to percolate  to  the water
     table,  discharged  through  drain  tiles,  or   reclaimed  by  wells.

LEACHATE.   Solution  formed  when water percolates  through  solid  wastes,
     soil  or  other materials  and extracts soluble  or  suspendable sub-
     stances from the material.

LEACHFIELD.  Soil component  of a septic system which removes particulate
     matter and nutrients.

LIMITING  FACTOR.   A factor  whose absence, or  excessive concentration,
     exerts some restraining influence upon a population.

LOAM.   The textural  class  name  for soil  having  a moderate amount  of
     sand, silt, and  clay.   Loam soils contain 7  to 27% of clay, 28 to
     50% of silt, and less  than 52% of sand.

LOESS.   Soil  of wind-blown origin, predominantly  silt and fine sand.

MACROPHYTE.   A  large  (not   microscopic)  plant, usually in an  aquatic
     habitat.

MELT  WATER.   Water which is  formed from the melting of  snow,  rime,  or
     ice.

MESOTROPHIC.  Waters with a  moderate supply of nutrients and no signifi-
     cant production of organic matter.

MESOTROPHIC LAKE.   Lakes of intermediate characteristics between oligo-
     trophic and eutrophic.   They contain a moderate supply of nutrients
     and plant life.

METHEMOGLOBINEMIA.   The  presence  of methemoglobin  in the blood.   Methe-
     moglobin is  the  oxidized  form of hemoglobin  and   it  is  unable to
     combine reversibly with oxygen.

MICROSTRAINER.   A  device for screening  suspended  solids that  are  not
     removed by sedimentation.

MILLIGRAM  PER  LITER  (mg/1).   A concentration of  1/1000  gram  of a sub-
     stance in  1  liter of  water.   Because  1  liter of pure water weighs
     1,000  grams,  the concentration  also can be stated  as  1  ppm (part
     per  million,  by  weight).   Used to measure and report the  concen-
     trations  of most  substances which  commonly  occur in  natural  and
     polluted waters.

MORPHOLOGICAL.  Pertaining to Morphology.

MORPHOLOGY.  The form or structure of a plant or animal, or of a feature
     of  the  earth, such as a  stream,  a lake, or  the  land in general.
     Also,  the  science  that  is  concerned with the study of  form  and
     structure  of  living organisms.   Geomorphology  deals  with  the form
     and  structure of  the earth.

                                    188

-------
NON-POINT SOURCE.  A  general  source of pollution not originating from a
     single controllable source.   Surface  water runoff is an example of
     a non-point source that is not easily controlled.

NUTRIENT BUDGET.  The amount of nutrients entering and leaving a body of
     water on an annual basis.

NUTRIENTS.   Elements  or  compounds  essential  as  raw  materials  for
     organisms  growth and development,  e.g.  carbon,  oxygen,  nitrogen,
     and phosphorus.

OLIGOTROPHIC.    Waters with  a  small  supply of  nutrients and 'hence  an
     insignificant production of organic matter.

OLIGOTROPHIC LAKES.   Deep  lakes that have a low supply of nutrients and
     thus  contain  little organic matter.   Such  lakes  are characterized
     by high water transparency and high dissolved oxygen.

ORDINANCE.  A municipal or county regulation.

OUTWASH.   Drift carried  by  melt  water  from  a  glacier and  deposited
     beyond the marginal moraine.

OUTWASH PLAIN.   A  plain formed by material deposited by melt water from
     a  glacier  flowing  over  a more or  less flat surface of large area.
     Deposits  of this origin are  usually  distinguishable from ordinary
     river deposits by  the fact that they often grade into moraines and
     their constituents  bear evidence  of  glacial origin.   Also called
     frontal apron.

PARAMETER.  Any  of a  set of  physical properties  whose values determine
     characteristics  or behavior.

PERCOLATION.    The  downward  movement of  water  through pore  spaces  or
     larger voids in soil or  rock.

PERMEABILITY.. The property or capactiy of porous rock, sediment, or soil
     to transmit a fluid,  usually  water or air;  it  is a measure of the
     relative  ease  of   flow  under  unequal pressures.   Terms  used  to
     describe  the  permeability of  soil are:   slow, less  than 0.2 inch
     per  hour;  moderately  slow, 0.2 to 0.63 inch; moderate, 0.63 to 2.0
     inches;  moderately  rapid.  2.0 to 6.3  inches; and rapid,  more than
     6.3  inches per hour.  A very slow class and a very rapid class also
     may be recognized.

PETROGLYPH.  An ancient or prehistoric carving or inscription on a rock.

PHOSPHORUS LIMITED.   Of all  the primary nutrients  necessary to support
     algal growth,  phosphorus  is  in the  shortest  supply and therefore
     can  limit additional algal growth.

PHYTOPLANKTON.   Floating plants, microsopic  in size,  that  both supply
     small animals with food  and give polluted water its green color and
     bad  taste.
                                   189

-------
POINT SOURCE.  A stationary source of a large individual emission.   This
     is  a  general  definition;  point  source  is  legally and  precisely
     defined in Federal regulations.

POVERTY  LEVEL.   An index  providing  a range  of poverty  income  cutoffs
     adjusted by such factors as family size, sex of family  head, number
     of  children under  18  years of age,  and farm or non-farm residence.

PREHISTORIC.   A term  which  describes the  period of human  development
     that   occurred   before   the  advent  of   written   records.    More
     generally,  any period  in  geologic  time  before written  history.

PRESENT WORTH.  The sum of money that must be set aside  at the beginning
     of  the  planning period  in order to  amortize the costs  of a project
     over the planning period.

PRESSURE SEWER  SYSTEM.   A wastewater collection  system  in  which house-
     hold  wastes  are   collected  in  the  building   drain and  conveyed
     therein  to the pretreatment  and/or pressurization  facility.   The
     system  consists  of  two major  elements,  the on-site  or  pressuri-
     zation  facility,  and  the primary conductor pressurized sewer main.

PRIMARY  PRODUCTION.' Growth  of  green plants resulting from  solar energy
     being fixed as sugar during'photosynthesis.

PRIMARY  TREATMENT.   The  first  stage  in  wastewater treatment  in  which
     substantially  all floating  or  settleable solids  are  mechanically
     removed by screening and sedimentation.

RAPID INFILTRATION.  A form of land treatment where  wastewater is placed
     into spreading basins and  applied to the  land  to  undergo percola-
     tion into the soil.

RARE SPECIES.   A  species  not Endangered or  Threatened  but  uncommon and
     deserving of further study and monitoring.  Peripheral  species, not
     listed  as  threatened, may  be included  in  this  category along with
     those  species  that were once "threatened" or  "endangered"  but now
     have increasing or protected, stable populations.

RECHARGE.  The process by which water is added to an aquifer.  Used also
     to  indicate the  water that is added.  Natural  recharge occurs when
     water from rainfall or a stream enters the ground and percolates to
     the water table.   Artificial recharge by spreading water on absorp-
     tive ground over  an aquifer or by injecting water through wells is
     used to store  water and to protect  groundwater  against the intru-
     sion of sea water.

ROOTED  AQUATIC  PLANTS.  Aquatic  or  water borne  plants  which take root
     below water.
                                   190

-------
ROUGH FISH.  Those fish species considered to be of low sport value when
     taken  on tackle,  or of  poor eating  quality;  e.g.  gar,  suckers.
     Rough  fish  are  more  tolerant  of  widely changing  environmental
     conditions than are game fish.  Also called coarse fish.

RUNOFF.  The  portion  of rainfall,  melted snow  or  irrigation water that
     flows  across  the  ground  surface  and  eventually  is  returned  to
     streams.  Runoff  can pick  up pollutants  from the air  or  the land
     and carry them to the receiving waters.

SANITARY SEWERS.  Sewers that transport only sanitary wastewater.   Storm
     water runoff is carried in a separate system.   See sewer.

SANITARY SURVEY.  A method  used to determine possible  sources  of water
     quality  and public  health  problems  and  to locate  inadequately
     functioning  wastewater  systems  by  making site-specific  investi-
     gations of existing lots and systems.

SCENIC  EASEMENT.   A  partial transfer  of land  rights to preserve  the
     aesthetic attractiveness of the land by restricting'activities such
     as  the  removal of  trees,  placement of billboards,  or  development
     incompatible with the scenic qualities  of the  land.  Just compensa-
     tion  is  given  to  owners for rights lost.   The right of  legal tres-
     pass  is generally not included as part  of this easement.

SECCHI DISK.  A round plate, 30 cm (1 foot)  in diameter, that is used to
     measure  the  transparency of  water.   The disk is  lowered  into  the
     water until  it no  longer can be seen  from the  surface.  The depth
     at which  the disk  becomes  invisible is a  measure of transparency.

SECONDARY TREATMENT.  Wastewater treatment in which bacteria  consume the
     organic  parts  of  the  wastes.  This biochemical action  is  accom-
     plished  by  use of  trickling  filters or the  activated  sludge pro-
     cess.   Effective  secondary treatment may  remove  approximately 90%
     of both BOD- and suspended solids.

SEEPAGE CELLS.  Unlined  wastewater lagoons  designed so that  all or part
     of wastewater percolates into the underlying soil.

SEMI-AQUATIC.  Plants that can exist on both land and in water.

SEPTIC SNOOPER.  Trademark for the ENDECO (Environmental Devices Corpor-
     ation)  Type  2100 Septic Leachate  Detector.  This  instrument con-
     sists  of an underwater  probe,  a water intake  system,  an analyzer
     control  unit  and  a  graphic  recorder.   Water  drawn  through  the
     instrument  is  continuously analyzed for  specific fluorescence and
     conductivity.   When  calibrated  against  typical  effluents,  the
     instrument  can  detect   and  profile effluent-like  substances  and
     thereby  locate  septic  tank  leachate or other  sources  of domestic
     sewage entering lakes and streams.

SEPTIC .TANK.   An underground  tank used  for the collection  of domestic
     wastes.   Bacteria  in the wastes decompose  the  organic  matter,  and
                                   191

-------
     the  sludge  settles  to  the bottom.   The  effluent  flows  through
     drains into the ground.   Sludge is pumped out at regular intervals.

SEPTIC  TANK  EFFLUENT  PUMP  (STEP).   Pump  designed  to transfer  settled
     wastewater from a septic tank to a sewer.

SEPTIC  TANK  SOIL  ABSORPTION SYSTEM (ST/SAS).   A system of  wastewater
     disposal in  which  large solids are retained in a tank;  fine solids
     and liquids  are  dispersed  into the surrounding soil  by  a system of
     pipes.

SEWER, COMBINED.   A  sewer,  or system of sewers,  that is  used to collect
     and conduct  both sanitary  sewage  and storm-water  runoff.   During
     rainless periods,  most  or  all  of  the flow  in a  combined  sewer is
     composed of  sanitary  sewage.   During a storm,  runoff increases the
     rate of flow and may overload the sewage treatment  plant  to which
     the sewer  connects.   At such times,  it is common to divert some of
     the flow,  without treatment, into the receiving water.

SEWER, INTERCEPTOR.  See Interceptor Sewer.

SEWER, LATERAL.  A sewer designed and installed to collect sewage from a
     limited number  of  individual properties  and conduct it  to  a trunk
     sewer.  Also known as a street sewer or collecting sewer.

SEWER, SANITARY.  See Sanitary Sewer.

SEWER,  STORM.   A conduit that collects and transports storm-water run-
     off.   In  many  sewerage systems,  storm  sewers  are separate from
     those carrying sanitary or industrial wastewater.

SEWER, TRUNK.   A sewer designed and installed to collect sewage from a
     number of lateral sewers and conduct it to an interceptor sewer or,
     in some cases, to a sewage treatment plant.

SHOALING.  The  bottom effect that influences the height of waves moving
     from deep to shallow water.

SINKING  FUND.   A  fund  established  by  periodic  installments  to provide
     for the retirement of the principal of term bonds.

SLOPE.  The incline of the surface of the land.  It is usually expressed
     as  a  percent (%) of  slope  that equals the number of feet  of fall
     per 100 feet in horizontal distance.

SOIL  ASSOCIATION.   General  term used  to  describe  taxonomic  units of
     soils, relative proportions, and pattern of occurrence.

SOIL LIMITING FACTOR.  Any physical characteristic which impedes
     the proper renovation of wastewater in soils.

SOIL  TEXTURAL  CLASS.   The classification of  soil material  according to
     the proportions  of sand,  silt,  and  clay.   The  principal  textural
     classes  in  soil,  in increasing  order of  the  amount  of  silt and
                                   192

-------
     clay, are  as  follows:  sand,  loamy sand,  sandy  loam, loam,  silt
     loam, sandy  clay  loam,  clay  loam, silty  clay  loam, sandy  clay,
     silty clay, and  clay.  These  class names are modified to  indicate
     the  size  of  the sand fraction  or the  presence  of  gravel,  sandy
     loam, gravelly loam,  stony  clay,  and cobbly loam, and are  used on
     detailed  soil  maps.   These terms  apply only  to individual  soil
     horizons or to the surface  layer  of a soil type.

STATE EQUALIZED VALUATION  (SEV).  A measure employed within a State to
     adjust actual assessed valuation  upward  to  approximate true market
     value.  Thus  it is possible to  relate debt burden  to  the  full value
     of taxable property in each community within that  State.  •

SPRAY IRRIGATION.   Desposing of  semi-treated wastewater by spraying upon
     the land at slow application rates.

STRATIFICATION.  The  condition  of a lake, ocean, or other body  of water
     when  the  water  column is  divided  into  a  relatively cold  bottom
     layer and  a  relatively warm  surface  layer, with a  thin  boundary
     layer (thermocline) between them.   Stratification generally occurs
     during  the  summer and during  periods  of ice cover  in the  winter.
     Overturns, of  periods of  mixing,  occur in the spring and  autumn.
     This condition is most common in  middle latitudes  and is  related to
     weather conditions, basin morphology, and altitude.

STUB FEE.  See Connection Fee.

SUCCESSION.  The  ecological  process  by  which terrestrial and  aquatic
     environments  age.

SUPPLEMENTAL  USAGE.    In  regard  to   functions   of  small waste  flow
     districts, those  which are not  required to comply1 with EPA  Con-
     struction Grants  regulations  governing  individual,  on-site waste-
     water  systems.    May  be  necessary  to  achieve  administrative  or
     environmental objectives.

SUSPENDED  SOLIDS  (SS).  Small  solid  particles  that contribute  to  tur-
     bidity.    The  examination   of  suspended  solids  and  the  BOD  test
     constitute the two  main  determinations for water  quality performed
     at wastewater treatment facilities.

TERTIARTY TREATMENT.   See Advanced Waste Treatment.

THREATENED SPECIES  (FEDERAL CLASSIFICATION).   Any species  of animal or
     plant that  is likely  to  become  an  endangered  species within the
     foreseeable  future throughout all  or  a significant part  of its
     range.  Protected under Public  Law 93-205, as amended.

TILL.   Deposits  of  glacial drift  laid  down in place  as the  glacier
     melts.  These deposits  are neither sorted  nor stratified  and  con-
     sist of a  heterogeneous  mass  of  rock flow,  sand,  pebbles,  cobbles,
     and boulders.
                                   193

-------
TOPOGRAPHY.  The  configuration  of a surface area  including  its  relief,
     or relative  evaluations, and the  position of its natural and man-
     made features.

TRICKLING FILTER PROCESS.  A method of secondary wastewater treatment in
     which the  biological growth  is  attached to  a  fixed medium,  over
     which wastewater  is  sprayed.   The filter  organisms  biochemically
     oxidize  the   complex  organic matter  in  the  wastewater to  carbon
     dioxide, water, and energy.

TROPHIC LEVEL.  Any  of  the feeding levels through which  the passage of
     energy  through  an  ecosystem  proceeds.   In simplest  form,  trophic
     levels   are:   primary   producers   (green  plants)   herbivores,
     omnivores, predators, scavengers,  and decomposers.

WATER QUALITY.  The relative condition of a body of water as  judged by a
     comparison between  contemporary  values  and  certain more or less
     objective standard values for biological, chemical,  and/or physical
     parameters.   The  standard  values  usually are based  on a  specific
     series  of  intended  uses,  and may vary as  the  intended uses vary.

WATER TABLE.  The upper level of groundwater that is not confined by an
     upper  impermeable   layer  and  is  under  atmospheric  pressure.   The
     upper  surface  of   the  substrate  that  is  wholly   saturated  with
     groundwater.

WATERSHED.  The area drained by a stream.

WELL LOG.   A chronological  record of the soil  and  rock  formations en-
     countered  in the   operation  of sinking a  well,  with either their
     thickness or the elevation of the top and bottom of each formation
     given.   It  also usually includes statements about  the lithologic
     composition  and water-bearing  characteristics  of  each formation,
     static and pumping water levels, and well yield.

ZONING.  The regulation by governmental action (invested by the State to
     cities, townships,  or counties)  of the use of the land, the height
     of buildings, and/or  the proportion of the land surface that can be
     covered by structures.
                                   194

-------
                             BIBLIOGRAPHY
Acroyd,  E.A.,  W.C.  Walton,  and  D.L.  Hills.   1967.  Groundwater  con-
     tribution to  streamflow and its relation  to  basin  characteristics
     in  Minnesota.   Report  of  Investigations  6.   Minnesota  Geological
     Survey.  University of Minnesota,  Minneapolis.

Ames Engineering and  Testing Co.   1976.   Report and logs of exploratory
     soil borings  for  sanitary  sewer,  Green Lake  MN.  Unpublished data.

Ames Engineering and Testing Co.  Undated.  Report of subsurface investi-
     gations for Green Lake sanitary sewer, Spicer MN.   (Mimeo) Ames IA.

Arthur Beard Engineers,  Inc.   1978.   correspondence regarding:  1)  unit
     prices and  collector sewer construction costs; 2)  wastewater  flow
     projections for  Green Lake;  and 3)  "typical" cluster system, Green
     Lake.  Chevy Chase, MD.

Clean  Water  Act of  1977.  Public  Law  95-217.   (33  U.S.C.  466 et seq.)

Cohen, S.  and  H.  Wallman.  1974.  Demonstration of waste flow reduction
     from households.  Environmental Protection Agency, National Environ-
     mental Research Center.   Cincinnati, OH.

Cooper,  I.A.,  and J.W.  Rezek.   1977.    Septage treatment and disposal.
     For EPA,  Technology Transfer.
                                                           I
Council  on Environmental Quality.   1973.   Preparation of environmental
     impact statements:  Guidelines.  1 August 1973.

Dearth,   K.H.    1979.    Current   costs   of   conventional   approaches.
     Presented  at EPA National  Conference on Less  Costly  Wastewater
     Treatment  Systems   for Small   Communities.    12-14  April  1977.
     Reston, VA.

Dillon,  P.J.   1975.   The application of the phosphorus-loading concept
     to  eutrophication  research.    Scientific  Series  No.  46.   Canada
     Centre for Island Waters.  Burlington, Ontario.

Endangered species Act of 1973.   Public Law 93-205.

Environmental Protection  Agency, Environmental  Photographic Interpreta-
     tion Center.   1978.

EPA.   July  1974.   Manual for preparation of environmental impact state-
     ments  for wastewater  treatment works,  facilities  plans,  and 208
     areawide waste treatment management plans.  July 1974.

EPA.   June 1975.   Cost  of  wastewater  treatment  by  land  application.

EPA.   June  1976.   Small  community wastewater   treatment  facilities.
                                   195

-------
EPA.  October  1977.   Process  design manual for land  treatment  for land
     treatment of municipal wastewater.  EPA 625/1-77-008.

EPA.  January 1978a.  Construction costs for municipal wastewater treat-
     ment plants, 1973-1977.  MCD 37.

EPA.  May  1978b.   Analysis  of O&M costs for municipal wastewater treat-
     ment systems.  MCD 39.

EPA.  May  1978c.   Construction  cost for municipal  conveyance  systems,
     1973-1977.  MCD 38.

EPA,  National Eutrophication  Survey.   1974a.   Report  on Green  Lake,
     Kandiyohi County, Minnesota.  Working Paper No.  101.

EPA,  National  Eutrophication  Survey.  1974b.   Report  on  Nest  Lake,
     Kandiyohi County, Minnesota.  Working Paper No.  117.

EPA, National  Eutrophication Survey.   1974c.   Report on  Wagonga  Lake,
     Kandiyohi County, Minnesota.  Working Paper No.  133.

EPA, National  Eutrophication Survey.   1975.   Report on Woodcock  Lake,
     Kandiyohi County, Minnesota.  Working Paper No.  141.

Federal  Water  Pollution Control  Act  Amendments  of  1972,  Public  Law
     92-500.

Fisheries  Research Unit.   1955.   Lake survey  report.    Diamond  Lake,
     Kandiyohi County.

Fisheries  Research  Unit.   1955.   Lake  survey  report.    Nest  Lake,
     Kandiyohi County.

Gates, Larry  F. ,  and  Howard F.  Krosch.  1975.  Water quality monitoring
     program  on representative  fish lakes,   1974.   Special  Publication
     No.  111.   Minnesota Department  of Natural Resources,  Division of
     Fish and Wildlife.

Giencke, Allan G.   1978.  Various correspondence to WAPORA, Inc.
     regarding  soil suitability for  wastewater treatment in  the  Green
     Lake vicinity.

Great Lakes  Upper Mississippi River Board of State  Sanitary Engineers.
     1978.  Recommended standards for sewage works.  Albany,  NY.

Green Lake  Property Owners  Association.  1970-1971.   Bacterial data for
     Green Lake.

Green  Lake Property  Owners  Association.   1976.   A  book  of names  and
     numbers.  Directory for Green Lake.

Green Lake  Sanitary Sewer and Water District.  Attachment No.  1.   File
     No. 741001-2.
                                   196

-------
Groszyk,  Walter.   1977.   Septic  tank problem  analysis:   Impact  on
     groundwater.  Information memorandum 77-164.   USEPA,  Water Planning
     Division, Washington DC.

Hummel, Mark.   Green Lake  construction grants sanitary  survey.   1978.

Illinois  Environmental   Protection  Agency.   1977.   Issuance  of  final
     Illinois  guidelines for  the preparation  of facilities plans  for
     unsewered communities.   Memorandum.  16 September 1977.

Johnson, Elden.  1969.  The  prehistoric peoples of Minnesota.   Minnesota
     Historical Society.  St. Paul MN.

Jones, R.A.  and  G.F.  Lee.   1977.  Septic Tank disposal systems as phos-
     phorus  sources  for surface  waters.   EPA-600/3-77-129.   Robert  S.
     Kerr Environmental Research Laboratory.

Kandiyohi  County Board  of Commissioners.   July 1977.   Kandiyohi  County
     Overall Economic Development Plan.

Kandiyohi  County  Board of  Commissioners.   1977.   Letter,  to  Paul E.
     Davis,   MPCA,   from  Virgil  Olsen.    Additional  information  to
     facilities plan.

Kandiyohi  County Board  of Commissioners.   1973.   Kandiyohi  County Sub-
     division regulations.   Willmar MN.

Kandiyohi  County Board  of   Commissioners.   1977.  Resolution  amending
     comprehensive zoning ordinance.  (Mimeo) Willmar MN.

Kandiyohi  County  Board  of  Commissioners.    1971.    Zoning  ordinance,
     Kandiyohi County, Minnesota.  Willmar MN.

Kandiyohi  County Historical Society.   Undated.   A guide  to historical
     sites in Kandiyohi County, Minnesota.   Willmar MN.

Kandiyohi  County Planning  Commission.   1973.   Comprehensive water and
     sewer plan  for Kandiyohi County, Minnesota.

Kandiyohi  County Soil and Water  Conservation  District.   Undated.   Con-
     servation  needs  for  the  future:   Kandiyohi  County,   Minnesota.

Kandiyohi  County Zoning Administrator.   Undated.   Home sewage treatment
     systems, Kandiyohi County.   (Mimeo).  Willmar MN.

Kerfoot,  W.   1979.   Investigation  of   septic  leachate discharges  into
     Green Lake  and  Nest Lake, MN.   K-V Associates, Inc., Falmouth, MA.

Library  Reference Service,  Federal Aid  in  Fish and  Wildlife.   1974.
     Minnesota State Index:   Fish.  Denver CO.

Lindholm,  G.F., D.F. Farrell, and J.O.  Helgesen.  1974.  Water resources
     of  the  Crow River  watershed,  south-central  Minnesota.   Hydrologic
     investigations  atlas   HA-528.   US Geological  Survey,  Reston VA.

                                   197

-------
Machmeier, Roger  E.   1977a.   Get  to know your  septic  tank.   Extension
     Folder  337.    University  of   Minnesota   Agricultural   Extension
     Service, St.  Paul.

Machmeier, Roger E.   1977b.   How to run a percolation  test.   Extension
     Folder  261.    University  of   Minnesota   Agricultural   Extension
     Service, St.  Paul.

Machmeier, Roger E.   1977c.   Town and country sewage treatment.   Exten-
     sion Bulletin 304.   University of Minnesota Agricultural Extension
     Service, St.  Paul.

Machmeier, Roger E.  1978.  Shoreland sewage treatment:   Recommendations
     for  identifying  and eliminating  nonconforming  systems.   Extension
     Bulletin  394.   University  of  Minnesota  Agricultural   Extension
     Service, St.  Paul.

McLaughlin, E.R.   1968.   A  recycle system for conservation of water in
     residences.  Wate and Sewage Works 115(4):175-176.

Minnesota  Analysis  and  Planning  System,  Institute  of  Agriculture,
     University of Minnesota.

Minnesota  Bureau  of Fisheries.  1959.  Lake  survey  information  summary
     sheet:  Green Lake.

Minnesota  Department  of Administration.   1976.   Minnesota  state publi-
     cations.  St. Paul MN.

Minnesota  Department of  Conservation.   1970.   Rules  and  regulations.
     Chapter 6:   Statewide  standards  and  criteria for management shore-
     land areas.  St. Paul MN.

Minnesota  Department  of  Conservation,  Division of Game and Fish.  1964.
     Sounding map, Green Lake, Kandiyohi County MN.

Minnesota  Department  of  Convervation,  Division of Game and Fish.  1964.
     Sounding map, Nest Lake, Kandiyohi County MN.

Minnesota  Department  of  Conservation,  Division of Game and Fish.  1964.
     Sounding map, Diamond Lake, Kandiyohi County MN.

Minnesota Department of Conservation, Division of Waters.  1959.   Hydro-
     logic atlas of Minnesota.  Bulletin No. 10.   St. Paul MN.

Minnesota Department of Manpower Services.   Undated.   Employment by type
     and   broad   industrial   sources   1971-1975,   Kandiyohi  County.
     Unpublished report.

Minnesota  Department of  Natural  Resources.   1976.   Rules and  regula-
     tions.   Chapter  6:    NR 92-84.   Standards  and  criteria  for  the
     management of municipal  shoreland areas.  St. Paul MN.

Minnesota  DNR.    1975.   The  uncommon ones:   Animals  and  plants  which
     merit special consideration and management.

                                    198

-------
Minnesota DNR.   Undated.   Proposed  rules  NR 5020-5029:   Standards  and
     criteria  for granting  permits  to change  the course,  current,  or
     cross section of public waters.   (Mimeo).

Minnesota Division of  Game and  Fish.   1971.   Fisheries  lake  survey;
     Green Lake.  MN.

Minnesota Division of Game and Fish.   1971.  Fisheries lake survey, Nest
     Lake.

Minnesota Division of  Game and  Fish.   1971.   Fisheries  lake  survey,
     Diamond Lake.

Minnesota Division of Game  and  Fish, Bureau of Research  and Planning.
     1958.  Fisheries lake survey report:   Green Lake, Kandiyohi County.

Minnesota  Pollution  Control Agency.   1977.   Draft  program for  land
     disposal of  municipal  wastewater sludges.   (Mimeo).   Roseville MN.

MPCA.  1977.  Land application  and utilization of septage:  Recommended
     guidelines.   (Mimeo).  Roseville MN.

MPCA.  1972.   Recommended design  criteria for disposal of effluent by
     land application.  MPCA #566. 9  p.

MPCA.   1972.   (WPC2)  Rules, regulations,  classifications,  and  water
     standards.   St. Paul MN.

MPCA.  1972.   Rules and  regulations.   Chapter 1:   Ambient air quality
     standards.

MPCA.   Undated.   Proposed  rules governing standards  for  individual
     sewage treatment systems.   Roseville MN.

MPCA, Division of Solid Waste.   1973.  Solid waste disposal regulations.
     St.  Paul MN.

MPCA, Division of Water Quality.   1975.  Recommended design criteria for
     sewage stabilization ponds.   (Mimeo)  Roseville MN.

MPCA,  Division  of  Water  Quality.    1975.    Upper  portion,   upper
     Mississippi  River  basin plan.   Department of  Administration,  St.
     Paul, variously paged.   Vol.  1 and Vol. 2.

MPCA, Division of Water Quality.   1972.  Recommended design criteria for
     disposal of  effluent by land application.   (Mimeo)  Roseville  MN.

MPCA, Division of Water Quality.   Undated.  Report memorandum on investi-
     gation of water quality of  Green Lake, Kandiyohi County.

MPCA.  1973.   Minnesota State Rules,  Regulations,  classifications,  and
     water standards.   WPC 14.

Minnesota Socio-Economic Population  Characteristic-Employment Volume 2.
                                   199

-------
Minnesota  Soil  Conservation  Service.   January 1978.   Watershed-river
     basin status report.

Minnesota  State  Planning Agency:   Kandiyohi County  Population  Projec-
     tions 1975-2000.

Minnesota State Planning Agency, Water Resources Coordinating Committee.
     1969.   Background  information  for framework  statewide  water  and
     related  land  resources planning in Minnesota.   Technical Bulletin
     No. 2.  St.  Paul, MN.

Morey,  G.B.  (Complier).   1976.   Geologic  map  of  Minnesota.   Miscella-
     neous Map Series, Map M-24.  Minnesota Geological Survey-University
     of Minnesota, Minneapolis.

Nason,  Wehrman,  Chapman Associates, Inc.  July 1971.   Kandiyohi County
     Comprehensive Plan.  Minneapolis MN.

National Environmental Policy Act of 1969,  Public Law 91-190.

National Interim Primary Drinking Water Regulations.   40 CFR 141.

National  Oceanic  and  Atmospheric  Administration,  Environmental  Data
     Service.  1976.  Local climatological  data:  St. Cloud, MN.   Annual
     summary  with  comparative  data.   USDC  National  Climatic  Center,
     Asheville NC.

Noyes  Engineering  Service.    1977.   Green  Lake  well  water  survey.
     (Mimeo).  Willmar MN.

Noyes  Engineering  Service  and  Rieke  Carroll  Muller  Associates,  Inc.
     December  16, 1974.  Preliminary feasibility report, water pollution
     control   facilities,   Green   Lake  vicinity,   Kandiyohi  County,
     Minnesota.

Nupson, H.   2970-1.   Reports  to Green Lake Property Owners Association.
     Work orders 2379, 5375, and 7892.  Minnesota Valley Testing Labora-
     tories, Inc., New Ulm MN.

Paulson,  Richard 0.,  SCS.  1978.  Letter  to  Eric  Hediger.   Information
     concerning soils for Green Lake area.

Pollution  Control  Agency.  Undated.  6  MCAR.   4.8040 Individual sewage
     treatment systems standards.

Public Water and Sewer Systems, Chapter 116A.01.

Report  of the State Auditor of Minnesota.   Revenues, expenditures,  and
     debt of the cities  in Minnesota.  November 1977.

Report  of the State  Auditor  of  Minnesota.   Revenues,  expenditures  and
     debt of local governments  in Minnesota.  August  1977.

Report  of the State Auditor of Minnesota.   Revenues, expenditures,  and
     debts of  the towns  in Minnesota.  January  1978.

                                   200

-------
Rieke  Carroll  Muller  Associates Inc.   1976.   Water pollution  control
     facilities  plan,  Green  Lake  Sanitary  Sewer  and  Water  District.
     Hopkins UN.

Rieke Carroll Muller Associates,  Inc.   1977.   Letter to James P.  Roth,
     MPCA,  From  William  G.   Hendrickson.   Additional  information  to
     Facilities Plan.   July 25, 1977.

Rose, Robert.  1978.  Field notes:  Green Lake.

Safe Drinking Water Act.   Public Law 93-523.

Southwest  State  University.    1972-1973,  1975-1977.  Water  quality data
     sheets for Green Lake.

State of  Minnesota.  Undated.   [Legislation  concerning]  Water pollution
     control; sanitary districts.  Sees.  115.15-115.42.

State  of  Minnesota.   1975.   Outdoor  recreation  system  (Legislation,
     Chapter 86A).

STORET.   1977.   Printouts on Green Lake, Kandiyohi County,  MN.

Swanson,  Lester W.   1977.  Inventory  and evaluation,  s'oil  and  water
     resources:  Soils  and engineering  interpretations  for  New  London-
     Green  Lake-Diamond  Lake  area.   USDA Soil  Conservation  Service,  in
     cooperation  with  Kandiyohi  County Soil  and  Water  Conservation
     District,  Willmar MN.

Troyan, J.J., and D.P.  Norris.   March 1977.   Cost-effectiveness analysis
     of  alternatives  for  small  wastewater  treatment systems.   For EPA
     Technology Transfer.  Municipal Design  Seminar on Small Wastewater
     Treatment Systems.  Seattle WA.

US Bureau of the Census.    1972.  County and City Data Book.

US  Census  of  Housing.   1970.   Summary  Data .and  Fifth Count  Summary
     Tapes.

USDA Soil  Conservation Service.   1977.   Proposed rule,  prime and unique
     farmlands:  Important farmland inventory.   42 F.R.  42359, 23 August
     1977.

USDA  Soil  Conservation  Service.   1971.   Soil  survey  interpretations.
     Lincoln NE.

USDA  Soil  Conservation  Service,  in  cooperation  with  MN  Agricultural
     Experiment  Station.   1966.   Soil  survey  laboratory  data  and
     descriptions  for  some  soils  of  Minnesota.   Soil  Survey Investi-
     gations Report No. 9. 79 p.

US Department  of Commerce.  1972.  Bureau of Census.  Census of Retail
     Trade  1972.
                                   201

-------
US  Department  of  Commerce.   Bureau  of  Census.    Census  of  Selected
     Services 1972.

US Department  of Commerce,  Bureau  of Economic Analysis.   1977.   Local
     area personal income 1970-1975, Vol. 5:   Plains region.

US  Department  of  Interior,  National  Park  Service.   1976.   National
     Register of Historic Sites.   Washington DC.

USGS, Water  Resources  Division.   1977.  Index map  of  Minnesota showing
     availability of flood-prone area maps published by USGS.   St. Paul.

Vollenweider,  R.A.   1968.   The  scientific  basis  of  lake  and  stream
     eutrophication,    with   particular  reference   to phosphorus  and
     nitrogen  as  eutrophication factors.  Technical Report  OECD.  DAS/
     CSI/68.   27:1-182.  Paris, France.

Walton,  William  C.    1972.   Lists  of  references   and  selected books
     bearing on water  resources  in  Minnesota.  Water Resources Research
     Center,   University of  Minnesota  Graduate School, Minneapolis  MN.

White House Rural Development Initiatives 1978.

Zappetillo,  David B.,  and  Howard  F.  Krosch.   1976.   Water  quality
     monitoring  program on  representative  fish  lakes,  1975.   Special
     Publication No.  114.  Minnesota DNR, Division of Fish and Wildlife.
                                   202
                                                           GPO 941 -904

-------