DOE
EPA
United Stales
Department of
Energy
Sol id Fuel s Mining
and Preparation Division
Washington DC 20241
United States
Environmental Protection
Agency
Office of Energy, Minerals, and
Industry
Washington DC 20460
EPA-600/7-78-124
July 1978
            Research and Development
            An Engineering/
            Economic Analysis
            of Coal Preparation
            Plant Operation
            and Cost

            Interagency
            Energy/Environment
            R&D  Program
            Report

-------
                RESEARCH REPORTING SERIES

Research reports of the Office of Research and Development, U.S. Environmental
Protection Agency, have been grouped into nine series. These nine broad cate-
gories were established to facilitate further development and application of en-
vironmental technology.  Elimination of traditional grouping was consciously
planned to foster technology transfer and a maximum interface in related fields.
The nine series are:

      1    Environmental  Health Effects Research
      2,   Environmental  Protection Technology
      3.   Ecological Research
      4.   Environmental  Monitoring
      5.   Socioeconomic Environmental  Studies
      6.   Scientific and Technical Assessment Reports (STAR)
      7.   Interagency  Energy-Environment Research and Development
      8.   "Special" Reports
      9.   Miscellaneous Reports

This report has been assigned to the INTERAGENCY ENERGY-ENVIRONMENT
RESEARCH AND DEVELOPMENT series. Reports in this series result from the
effort funded  under the 17-agency Federal Energy/Environment Research and
Development Program. These studies relate to EPA's mission to protect the public
health and welfare from adverse effects of pollutants associated with energy sys-
tems. The goal of the Program is to assure the rapid development of domestic
energy supplies in an environmentally-compatible manner by providing the nec-
essary environmental data and control technology. Investigations include analy-
ses of the transport of energy-related pollutants and their health and ecological
effects;  assessments of,  and development of, control  technologies for energy
systems; and  integrated assessments of a wide range of energy-related environ-
mental issues.
This document is available to the public through the National Technical Informa-
tion Service, Springfield, Virginia 22161

-------
                                       EPA-600/7-78-124
                                       July 1978
     AN ENGINEERING/ECONOMIC ANALYSIS OF
  COAL PREPARATION PLANT OPERATION AND COST
     UNITED STATES DEPARTMENT OF ENERGY
SOLID FUELS MINING AND PREPARATION DIVISION
           WASHINGTON, D.C.  20241
       Contract Number ET-75-C-01-9025
  OFFICE OF ENERGY, MINERALS, AND INDUSTRY
     OFFICE OF RESEARCH AND DEVELOPMENT
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
           WASHINGTON, D.C.  20460

-------
                          DISCLAIMER NOTICE
THE VIEWS AND CONCLUSIONS CONTAINED IN THIS DOCUMENT ARE THOSE OF THE
AUTHOR AND SHOULD NOT BE INTERPRETED AS NECESSARILY REPRESENTING THE
OFFICIAL POLICIES OR RECOMMENDATIONS OF THE DEPARTMENT OF ENERGY OR
THE UNITED STATES GOVERNMENT.

-------
                               PREFACE
     The following report presents the results of a study conducted by
the Hoffman-Muntner Corporation of Silver Spring, Maryland, for the
United States Department of Energy under Contract Number ET-75-C-01-9025.
This effort, funded through the Federal Interagency Energy/Environment
Research and Development Program, was performed under the technical
direction of Mr. W. E. Warnke of the U. S. Department of Energy, Solid
Fuels Mining and Preparation Divison.  The purpose of this study was to
identify the costs associated with the various types and levels of physical
coal preparation processes currently available.  Although data of this
type have been previously generated in fragmented form, it was the objec-
tive of this study to give a comprehensive presentation having a uniform
time base.  A methodology was developed that permits meaningful comparison
of the relative costs of coal cleaning.  This technique was applied to
current technology and economics, but can also be utilized in the future
with appropriate index adjustment.
     To accomplish this objective, eight existing coal preparation plants
were selected for anaylsis.  These plants range in complexity from a rela-
tively simple jig plant to a rather sophisticated preparation circuit
utilizing heavy media, froth flotation, and thermal drying.  Each of
these plants is discussed separately with an analysis of the individual
process and the level of cleaning achieved as supported by the specific
washability data.  Additionally, the major cost components such as capital,
labor, and materials are summarized to arrive at the total cost of clean-
ing for each plant.  These analyses are presented from the perspective
of the preparation plant operator and do not assess the many user oriented

-------
benefits resulting from coal cleaning.  In addition to increased heat
content, these benefits include lower emission control, transportation,
boiler maintenance, and ash disposal costs.
     For background, general discussions are provided covering the various
types of coal cleaning processes.  These discussions include brief de-
scriptions of the processes and associated equipment with cost data de-
tailing their impacts on the total cost of preparation.
                           ACKNOWLEDGEMENTS
     The author wishes to express sincere appreciation to those many
dedicated individuals in the coal industry who took the time out from
their busy schedules to make available the current preparation plant
operating data, a portion of which is summarized in Section 5.0.  With-
out their patience and understanding, this study could never have been
accomplished.  Further, the author wishes to extend many thanks to those
knowledgeable members of the preparation equipment manufacturing community
who were so very cooperative in providing the price and technical data in-
cluded throughout this report.  Finally, the author wishes to convey a
special expression of appreciation to Messrs. W. E. Warnke, A. W. Deurbrouck,
and R. E. Hucko of the Department of Energy, Solid Fuels Mining and Prepara-
                                                           i   i
tion Divison, for their valuable counsel and constructive suggestions
during the course of the program.  It was indeed an honor and privilege
to work on an important study of this type with so many capable personnel,
too numerous to mention.

-------
                           TABLE OF CONTENTS

                                                                   Page

PREFACE	 i

ACKNOWLEDGEMENTS	,	 i i

LIST OF FIGURES 	 vi

LIST OF TABLES	 ix

1.0 INTRODUCTION	   1

2.0 PREPARATION PLANT COMPLEX 	   8
  2.1 Coal Handling and Storage 	  14
      2.1.1 Coal Storage	  15
      2.1.2 Conveyors	  18
      2.1.3 Tramp Iron Removal	  20
      2.1.4 Loading Facilities	  22
  2.2 Cleaning Equipment	  25
      2.2.1 Size Reduction Equipment	  30
      2.2.2 Screens	  40
      2.2.3 Baum Jig	  53
      2.2.4 Heavy Media Vessels	  64
      2.2.5 Cycl ones	  67
      2.2.6 Concentrati ng Tables	  77
      2.2.7 Froth Flotation	.\.	  84
  2.3 Other Equipment and Facilities	  89
      2.3.1 Dewatering Equipment	  89
            2.3.1.1 Centrifugal Dewatering Equipment	  90
            2.3.1.2 Vacuum Disc Filter	  99
            2.3.1.3 Vor-Siv 	 102
            2.3.1.4 Thermal Dryer 	 106
      2.2.2 Static Thickener	 113
      2.2.3 Coal Sampling Equipment	 116

3.0 SMALLER SIZE PREPARATION PLANTS	 119

4.0 OPERATIONAL AND OTHER FACTORS INFLUENCING COST	 128
  4.1 Plant Utilization	 129
  4.2 Coal Quality 	 133
  4.3 Capital Amortization	 135
      4.3.1 Capital Amortization Defined	 135
      4.3.2 Capital Amortization Applied	 137
  4.4 Cost of Btu Loss in Cleaning	 143
                                   m

-------
                    TABLE OF CONTENTS (Continued)

                                                                Page

5.0 PREPARATION PROCESS EXAMPLES	 I46

     5.1 Example 1 - Jig Process - Simple		 I48
         5.1.1 General Description	 148
         5.1.2 Capital Amortization	 I59
         5.1.3 Operating & Maintenance Costs	 159
         5.1.4 Discussion of Performance and Cost	 161

     5.2 Example 2 - Jig Process - Intermediate	 164
         5.2.1 General Description	 164
         5.2.2 Capital Amortization	 176
         5.2.3 Operating & Maintenance Costs	 176
         5.2.4 Discussion of Performance and Cost	 178

     5.3 Example 3 - Jig Process - Intermediate	 180
         5.3.1 General Description	 180
         5.3.2 Capital Amortization	 191
         5.3.3 Operating & Maintenance Costs	 191
         5.3.4 Discussion of Performance and Cost	 193

     5.4 Example 4 - Jig Process - Complex	 196
         5.4.1 General Description	 196
         5.4.2 Capital Amortization	 212
         5.4.3 Operating & Maintenance Costs	 212
         5.4.4 Discussion of Performance and Cost	 214

     5.5 Example 5 - Heavy Media Process - Simple	 217
         5.5.1 General Description	 217
         5.5.2 Capital Amortization	 228
         5.5.3 Operating & Maintenance Costs	 228
         5.5.4 Discussion of Performance and Cost..	 230

     5.6 Example 6 - Heavy Media Process - Complex	 232
         5.6.1 General Description	 232
         5.6.2 Capi tal Amorti zati on	 246
         5.6.3 Operating & Maintenance Costs	 246
         5.6.4 Discussion of Performance and Cost	 248

     5.7 Example 7 - Heavy Media Process - Complex	 251
         5.7.1 General Description	 251
         5.7.2 Capital Amortization	 261
         5.7.3 Operating & Maintenance Costs	 261
         5.7.4 Discussion of Performance and  Cost	 263

     5.8 Example 8 - Heavy Media Process - Complex	 265
         5.8.1 General Description	 265
         5.8.2 Capital Amortization	 282
         5.8.3 Operating & Maintenance Costs	 282
         5.8.4 Discussion of Performance and Cost	 284
                                   IV

-------
                     TABLE OF CONTENTS (Continued)
                                                                 Page
      5.9 Summary of Preparation Process Examples	  285
6.0 FUTURE PROSPECTS FOR COAL PREPARATION 	  287
REPORT DOCUMENTATION PAGE With Abstract 	  297

-------
                            LIST OF FIGURES
Figure Number                                                       Page
     2-1           Typical Coal Preparation Complex	   9
     2-2          Cleaning Plant Central Control  Panel	  12
     2-3          Coal Storage Silo	  17
     2-4          Tramp Iron Removal From Raw Coal 	  20
     2-5          Rotary Breaker Installation	  30
     2-6          Cutaway View of Rotary Breaker.	  31
     2-7          Primary Size Reduction Equipment 	  34
     2-8          Application of Scalping Screen	  42
     2-9          Application of Raw Coal Sizing Screen	  43
     2-10         Pre-Wet Screen i n Operati on	  45
     2-11         Applicaton of Desliming Screen 	  46
     2-12         Drain and Rinse Screen For Heavy Media Recovery ..  48
     2-13         Sieve Bend Mounted Ahead of Vibrating Screen 	  50
     2-14         Cutaway View of Sieve Bend Manufactured by
                  Heyl & Patterson, Inc	  51
     2-15         Cutaway Views of Baum Jig	  56
     2-16         Cutaway Views of Batac Jig	  62
     2-17         Daniels Heavy Media Precision Washer	  66
     2-18         Heavy Media Cyclone in Inclined Position  	  70
     2-19         Cutaway View of Operating Cyclone	  71
     2-20         Water-Only Cyclone Installation	  72
     2-21         Top View of Concentrating Table with Distribution
                  of Products by Si ze  	  78
     2-22         Double-Deck Concentrating Table
                  (Deister  Concenco  "88")	  82
                                    VI

-------
                  LIST OF FIGURES (Continued)

Figure Number                                                       Page
     2-23        Froth Flotation Cells in Operation 	  85
     2-24        Vibrating Screen Basket Centrifugal Dryer-
                 Horizontal Type (WEMCO Model 1100)	  91
     2-25        Vibrating Screen Basket Centrifugal Dryer-
                 Vertical Type  (H & P Hurricane Model)	  93
     2-26        Scroll Type Centrifugal Dryers (CMI Model EB-36)..  95
     2-27        Vacuum Disc Filter (10 Feet 6 Inch Diameter 12
                 Disc Version)	 100
     2-28        Vor-Siv Conical Sieve	103
     2-29        Fluid-Bed Thermal Dryer Installation
                 (FMC Fluid-Flo Model)	 109
     2-30        Cutaway View of Fluid-Bed Thermal  Dryer
                 (ENI Coal-Flo  Model)	 110
     2-31        Cross-Section  of Static Thickener	 114
     2-32        Top View  of Static Thickener  	 115
     2-33        Three-Stage Coal Sampling System - (Denver
                 Equipment Division of Joy)  	  118
     3-1         Layout of Unitized Jig	  121
     3-2         Flow Sheet of  Unitized Jig  Plant  	  122
     3-3         Two-Cell  Diaphragm Jig	  123
     5-1         Example 1 - Jig Process - Simple
                 Preparation Plant Flow Sheet	  149
     5-2         Example 2 - Jig Process - Intermediate
                 Preparation Plant Flow Sheet	165
     5-3         Example 3 - Jig Process - Intermediate
                 Preparation Plant Flow Sheet	 181
     5-4         Example 4 - Jig Process - Complex
                 Preparation Plant Flow Sheet	197
     5-5         Example 5 - Heavy Media Process -  Simple
                 Preparation Plant Flow Sheet  	218

-------
                      LIST OF FIGURES (Continued)

Figure Number                                                      Page

     5-6          Example 6 - Heavy Media Process - Complex
                  Preparation Plant Flowsheet 	  233

     5-7          Example 7 - Heavy Media Process - Complex
                  Preparation Plant Flow Sheet	  252

     5-8          Example 8 - Heavy Media Process - Complex
                  Preparation Plant Flow Sheet	  266

     6-1          Hypothetical  Flotation Plant With Fine
                  Refuse  Disposal  - Simplified Process  Flow Sheet..290
                                vm

-------
                            LIST OF TABLES

Table Number                                                       page

   2-1         Clean Coal Produced Annually by Major
               Mechanical Cleaning Methods	  54

   2-2         VC-48 and'vC-56 Capacity and Performance	  94

   2-3         Model EB-36 Capacity and Performance	  96

   2-4         Coal Thermally Dried In Comparison to
               Annual Product! on	  107

   5-1         Example  1 - Jig Process - Simple
               Preparation Plant Performance	  152

   5-2         Example  1 - Jig Process - Simple
               Washability Data of Assumed Plant Feed -
               3/4  Inch Fraction	  153

   5-3         Example  1 - Jig Process - Simple
               Washability Data of Assumed Plant Feed -
               3/4  Inch X 0 Fraction  	  154

   5-4         Example  1 - Jig Process - Simple
               Preparation Plant Operating and Maintenance
               Personnel	  155

   5-5         Example  1 - Jig process - Simple
               Preparation Plant Capital Requirements	  156

   5-6         Example  1 - Jig Process - Simple
               Operating and Maintenance Costs	  160

   5-7         Example  2 - Jig Process - Intermediate
               Preparation Plant Performance	  168

   5-8         Example  2 - Jig Process - Intermediate.
               Cumulative Washability Data of Assumed
               PI ant Feed	  169

   5-9         Example  2 - Jig Process - Intermediate
               Preparation Plant Operating and
               Maintenance Personnel	  170

   5-10        Example  2 - Jig Process - Intermediate
               Preparation Plant Capital Requirements	  172

   5-11        Example  2 - Jig Process - Intermediate
               Operating and Maintenance Costs	  177
                                   IX

-------
                        LIST OF TABLES (Continued)

Table Number                                                       Page

    5-12       Example 3 - Jig Process-- Intermediate
               Preparation Plant Performance ...................... 184

    5-13       Example 3 - Jig Process - Intermediate
               Composition of Assumed Plant Feed By
               Size Fraction
    5-14       Example 3 - Jig Process - Intermediate
               Cumulative Washability Data of Assumed
               Plant Feed ........................................... 186

    5-15       Example 3 - Jig Process - Intermediate
               Preparation Plant Operating and
               Mai ntenance Personnel ............................... 187

    5-16       Example 3 - Jig Process - Intermediate
               Preparation Plant Capital Requirements ............. 188

    5-17       Example 3 - Jig Process - Intermediate
               Operating and Maintenance Costs .................... 192

    5-18       Example 4 - Jig Process - Complex
               Preparation Plant Performance ....................... 201

    5-19       Example 4 - Jig Process - Complex
               Composition of Assumed Plant Feed by
               Size Fraction ...................................... 202

    5-20       Example 4 - Jig Process - Complex
               Composition of Assumed Feed to Batac
               Jigs by Size Fraction .............................. 203

    5-21        Example 4 - Jig Process - Complex
               Cumulative Washability Data of Assumed
               Feed to Batac Ji gs ................................. 204

    5-22       Example 4 - Jig Process - Complex
               Preparation Plant Operating and
               Maintenance Personnel ............................... 205

    5-23       Example 4 - Jig Process - Complex
               Preparation Plant Capital Requirements ............. 207

    5-24       Example 4 - Jig Process - Complex
               Operating and Maintenance Costs .................. ____ 213

-------
                         LIST OF TABLES  (Continued)

Table Number

     5-25       Example 5 - Heavy Media  Process  - Simple
                Preparati on PI ant Performance	   222

     5-26       Example 5 - Heavy Media  Process  - Simple
                Preparation Plant Operating and  Maintenance
                Personnel	   223

     5-27       Example 5 - Heavy Media  Process  - Simple
                Preparation Plant Capital  Requirements  	   224

     5-28       Example 5 - Heavy Media  Process  - Simple
                Operating and Maintenance  Costs	   229

     5-29       Example 6 - Heavy Media  Process  - Complex
                Preparation Plant Performance  	   236

     5-30       Example 6 - Heavy Media  Process  - Complex
                Washability Data of Assumed Plant Feed  -   •>
                3/4 X % mm	  237

     5-31     ^ Example 6 - Heavy Media  Process  - Complex
                Washability Data of Assumed Plant Feed  -
                7h X 3/4 Inch Fraction  	  238

     5-32       Example 6 - Heavy Media  Process  - Complex
                Preparation Plant Operating and  Maintenance
                Personnel	  239

     5-33       Example 6 - Heavy Media  Process  - Complex
                Preparation Plant Capital  Requirements	  241

     5-34       Heavy Media Process - Complex
                Operating and Maintenance  Costs  	  247

     5-35       Example 7 - Heavy Media  Process  - Complex
                Preparation Plant Performance	  255

     5-36       Example 7 - Heavy Media  Process  - Complex
                Preparation Plant Operating and  Maintenance
                Personnel	  256

     5-37       Example 7 - Heavy Media  Process  - Complex
                Preparation Plant Capital  Requirements  	  257

     5-38       Example 7 - Heavy Media  Process  - Complex
                Operating and Maintenance  Costs  	  262

-------
                      LIST OF TABLES (Continued)

Table Number                                                       Page

    5-39        Example 8 - Heavy Media Process - Complex
                Preparation Plant Performance	270

    5-40        Example 8 - Heavy Media Process - Complex
                Washability Data of Assumed Plant Feed -
                1% X 3/8 Inch Fraction	271

    5-41        Example 8 - Heavy Media Process - Complex
                Washability Data of Assumed Plant Feed -
                3/8 X 1/8 Inch Fraction	272

    5-42        Example 8 - Heavy Media Process - Complex
                Washability Data of Assumed Plant Feed -
                1/8 X 0 Inch Fraction	273

    5-43        Example 8 - Heavy Media Process - Complex
                Preparation Plant Operating and Maintenance
                Personnel	274

    5-44        Example 8 - Heavy Media Process - Complex
                Preparation Plant Capital Requirements	•	276

    5-45        Example 8 - Heavy Media Process - Complex
                Operating and Maintenance Costs 	 283

    5-46        Summary of Preparation Process Examples.	 286

    6-1         Hypothetical Flotation Plant With Fine Refuse
                Disposal - Preparation Plant Capital Requirements.. 292

    6-2         Hypothetical Flotation Plant With Fine Refuse
                Disposal - Operating and Maintenance Costs	295
                                   xii

-------
 SECTION 1,0
INTRODUCTION

-------
1.0 INTRODUCTION

     Unlike the manufacture of certain chemicals and metals where a
specific process will give reasonably constant results, there is no
universal approach to the production of clean coal  by physical  preparation
techniques.  This occurs due to the substantial  variability in  the physical
and chemical composition of coal from seam to seam and even within the seam
itself.  Therefore, a given preparation process  that is effective with a
coal from one seam may be inappropriate with a coal  from another seam in
achieving a comparable level of cleaning.  For this  reason, the particular
approach taken to coal cleaning must be designed around the specific coal
and the desired end results within the economic  constraints of  the situation.
     Although there is a myriad of approaches to coal cleaning, the
technology is founded on relatively few basic physical principles.
Nearly all physical cleaning techniques being applied today rely either
upon specific gravity or surface characteristics to  effect a separation
of the coal from the undesirable constituents such as ash and pyritic sulfur.
Most of the specific gravity processes and all of those relying upon
surface characteristics are wet in nature.  For those wet processes
based upon specific gravity, the medium of separation is water either by
itself or mixed with a substance such as magnetite to give the  mixture
a density slightly greater than that of coal.  These processes  are per-
formed in a variety of vessels and other devices described in Section 2.0
of this study.  The major process based upon surface characteristics (or
surface chemistry) is froth flotation.  As covered in more detail by
Section 2.2.7, this process creates a condition  which encourages the coal

-------
to adhere to air bubbles and float and the refuse to sink.  In a coal
preparation plant, these physical separation techniques are applied by
themselves or in combination to most economically achieve a desirable
end product given the physical and chemical composition of the raw coal.
     To determine the physical and chemical properties of the raw coal
around which the preparation process is designed, it is necessary to
obtain a representative sample.  The importance of this sample cannot be
overemphasized since it constitutes the root of flow sheet (process)
design and thus equipment selection.  A screen analysis is normally made
of this sample showing the size consist of the future plant feed.  This
has particular significance by showing the amount of finer material in
the feed which is a  critical factor in selecting the cleaning approach
and sizing the equipment.  Further, a washability study (float and sink
analysis) is made of these size fractions to show the separation of coal
from the undesirable constituents (ash and sulfur) at various specific
gravities.  The combination of this data permits the preparation plant
designer to focus on the critical points of separation and thereby de-
termine the approach best suited to achieve the desired results.  In
many situations, the process objective is to maximize the reduction of
ash forming constituents.  However, in light of today's increasing en-
vironmental restrictions, the optimization of sulfur removal  as well as
ash is of prime importance.
     Many times the material on which this detailed analysis is performed
is obtained from core samples which are seldom representative of the raw
coal as mined.  This occurs because an insufficient number of samples are
collected and the mininq method directly influences the amount of refuse

-------
and  fines  in  the mined product.  Unfortunately, this situation can be
very costly and necessitate substantial plant redesign in order to
approximate the projected plant performance.  For this reason, more ex-
tensive sampling should be conducted and performed in a manner which
closely simulates the effects of the particular recovery (mining) tech-
nique.
    Since there is by necessity such a variety of approaches to the
physical preparation of coal,  there is no single figure for the "cost
of coal cleaning."  Our studies have shown there is a range of costs
from less than $2.00 to over $4.00 per ton of raw plant feed depend-
ing upon the capacity and make-up of the preparation circuit.  Each
cost within this range is a composite of the capital  and operating
and maintenance costs associated with a specific plant during a given
time frame.  Time is a factor due to the inherent variability within
any given coal seam as previously mentioned.  Although two  preparation
plants may have an identical  input capacity and essentially the same
equipment, their individual  "cost of cleaning" will more than likely
be different for a variety of reasons.   Assuming consistent accounting
methods, these reasons include differences in:  1) raw coal feed;
2) operating procedures;  3)  clean coal  specification; and 4) local
cost of labor, material,  and services.   Many times these differences
can be significant due to more or less advantageous conditions for
refuse disposal.  In spite of the specificity of coal cleaning costs,
meaningful generalizations can be made concerning the cost of various
processes.  At the lower end of the above range ($?..00 to $4.00 per ton

-------
input), would be an intermediate size plant screening out the finer
material and  cleaning only  the coarser size fractions with inexpensive
equipment such as the Baum jig.  The upper end of the range,  approaching
$4.00 per ton input, would be representative of a plant cleaning all
size  fractions with  thorough  treatment of the finer material  by
such  equipment as  heavy  media cyclones and froth flotation in addition
to fairly extensive thermal drying.
    It should be noted that this range of cleaning costs is that ex-
perienced by  the coal preparation plant operators.  However,  this is
only a portion of the economic equation for coal cleaning.  In order  to
determine the true (net) cost of preparation from an overall  economic
perspective one must also account for the benefits accruing to the user
of clean coal.  These benefits which should appropriately be  set off
against the operator's cost include:
    1. Increased Heat Content of Cleaned Coal
       (Greater Btu content per unit weight)
    2. Transportation Savings
       (Less weight to ship for same Btu content)
    3. Pulverizing Cost  Savings
       (Less  cleaned coal needs to be pulverized for same Btu content
       required to meet  output)
    4. Boiler and Related Equipment Maintenance Savings
       (Clean coal is less  corrosive)
    5. Ash Disposal Cost Saving
       (Clean coal leaves less bottom and fly ash)

-------
    6. Lower Emission Control Costs
       (Less particulate and SCL from clean coal)
This being the case, the complete equation for coal preparation
is:
    Net Cost of Cleaning = Operator's Cost - User Benefits
Since these user benefits can only be accurately quantified on a
site specific basis, they are not considered by this study.  Only the
range of operator's cost will be addressed.
    It is the primary purpose of this study to give better definition
to this wide range of costs.  This is accomplished by looking at a
spectrum of actual preparation plants and examining the major elements
in their particular cost of cleaning.  These eight plants presented in
Section 5.0 range from a relatively simple jig plant to a variety of
fairly complex preparation circuits utilizing a number of heavy media
techniques, froth flotation, and thermal drying.   In each case, a .dis-
cussion is given of the plant performance and cost which identifies
for the reader those factors in the design of the plant and/or the
manner in which it is being operated which are most influential on
cost.  Using the cost relationships from these actual  preparation plant
examples as a base and one's own washability data, the capital and
operating and maintenance (O&M) cost of almost any contemporary cleaning
process can be estimated with reasonable accuracy. Understandably, the cost
developed in this manner for any given process handling a particular
coal would only be an approximation of what might be experienced.  How-
ever, it should be a useful planning tool for the would-be preparation

-------
plant operator to anticipate capital requirements and O&M costs.
Such information permits an assessment of market conditions in relation-
ship to the minimum price for which the clean coal could be sold to
yield a certain rate of return or otherwise satisfy one's economic
criteria for investment.
    In the following section, a brief discussion is presented of each
major element within the preparation plant complex and, as appropriate,
how it generally impacts the capital requirements and O&M cost.  This
discussion is also intended to give the reader some broad exposure
to the technical aspects of coal preparation which should aid in
understanding the sensitivity of cleaning cost  to approach  and
operational variances.

-------
      SECTION 2,0
PREPARATION PLMT COFPLEX

-------
2.0 PREPARATION PLANT COMPLEX

     As addressed by this study, the coal preparation complex consists

of the cleaning plant and any outside facilities and equipment associated

with the cleaning process.  These additional items include the raw and

clean coal storage areas, water clarification facilities (ponds or

thickeners), conveyors, coal and refuse vehicles, sampling system, load-

out facility, and thermal drying if applicable.  A typical preparation

complex is arranged as shown in Figure 2-1  below.
                RAW  COAL BELT
                                                              CLEANING
                                                                PLANT

                                                             CLEAN COAL BELT
                                                              THERMAL DRYER
                                                                STATIC THICKENER
                                 FIGURE  2-1

                      TYPICAL  COAL  PREPARATION  COMPLEX
                                      9

-------
Layout -
     Normally, it is desirable to locate the preparation complex as close
as possible to both the mining activity and transportation.  This elimi-
nates much of the initial expense and long term maintenance of long dis-
tance conveying, trucking, or other means of getting the coal to the plant
and then to a suitable location for final transport to market.  However,
this  is not always possible due to the unavailability of sufficient land
area, required services, or unsuitable topography.  Therefore, the final
selection of the preparation plant site must be made on the basis of the
economic and practical realities of the given situation.
      Once a suitable  site is selected, the layout of the complex will
be a  function of capacity and cleaning approach.  Regardless of the approach,
most  cleaning plants are multi-level steel frame buildings reaching 100
feet  or more in height.  This type of sturdy construction is necessary to
support the vibrating and other heavy equipment in addition to the weight
of the material flow.  Some cleaning plants have as many as twelve levels
 permitting  the  preparation  equipment to  be sequentially located on various
floors to make the most efficient use of gravity.  In addition to reducing
 the  initial  cost  of the  plant,  this arrangement  helps to lower the operating
and maintenance cost by limiting the pumping and piping requirements.
Construction -
      Although the actual construction of even a large preparation complex
can be  accomplished within  a year, a minimum of three years is more reason-
able  in view of today's conditions.  The major contributor to this extended
period  is the governmental  requirement that an environmental impact statement
(EIS) be filed and approved before a preparation plant can be built. Assuming
                                     10

-------
there are no problems with filing the EIS, a minimum of 18 months is re-
quired for compliance.  This period further assumes there are no law suits
filed and all paperwork is processed by EPA in a timely fashion.  Unfortun-
ately, this situation presents a real problem to the organization behind
the future plant in terms of arranging financing and making other commit-
ments.  While this lengthy process goes on, costs rise and previous  plans
need to be reevaluated.  Another factor to be considered which can in-
fluence the construction period is the equipment lead-time.  Many essential
items such as belting have a delivery of one year or more.
      It is not  uncommon to arrange for construction of the entire coal
preparation  complex under one  contract.  Although the prime contractor
is responsible  for  "delivering" the  complex on a turn-key basis, many
subcontractors  are  involved due to the diversity of specialities required.
Prior to  1970 such  contracts were almost always firm fixed price.  How-
ever, since  the early 1970's,  most construction agreements are carefully
worded  to allow for cost escalation  as a result of material price in-
creases and  sometimes labor.
Operation -
      All  of  the larger cleaning plants being built today are operated
from  a central  control room with the aid of sophisticated electronics.
This  permits a  single cleaning plant operator to monitor the functioning
of a  facility handling 1500 tons per hour  or more of raw coal.  By look-
ing at a  single control panel  of the type  shown in Figure 2-2 , the
operator  can tell whether or not each major piece of equipment within
the plant is operating.  Should a  serious  problem  develop  within  the
plant,  all  affected equipment  is  automatically  shut  down  to  avoid damage.
                                    11

-------
In addition to the plant operator, there are a number of other per-
         sonnel required to operate and maintain a preparation complex.
                For more detail on the numbers and types of such
                            personnel, the reader is referred to the
                                        specific plant examples
                                               presented in Section 5.0,
                                                   Figure  2-2
                                      Cleaning  Plant  Central  Control  Panel
Cost -
     As of mid-1977, the total  capital  cost  for  the  larger  coal  prepara-
tion complexes examined by this study was  in a range from around $7,000
to $23,000 per ton hour input.   These eight  plants  had design  input
                                   12

-------
capacities from as much as 1600 tons per hour (tph) down to 600 tph.
Although capital costs for plants in this range are somewhat sensitive
to capacity, they are influenced most by the sophistication of the
cleaning plant itself and the outside facilities such as thermal dryers.
In this regard, some plants will have complete or partial redundancy of
critical pieces of higher maintenance equipment.  Such an arrangement
permits servicing of these items without shutting down the entire plant.
The additional capital cost of this arrangement can many times be justi-
fied on the basis of increased operating efficiency and output.  An ex-
pansion of this theory is the implementation of complete parallel clean-
ing circuits which theoretically makes  the plant capable of continuous
operation at varying levels of production.  Another factor which can have a
significant impact upon the initial cost of a complex is the amount of site
preparation required.  The capital cost for each of the preparation plants
examined by the study is presented in detail by Section 5.0 along with a
discussion of which elements have the greatest cost impacts.
     The balance of this section is devoted to a brief description of
the major elements comprising the preparation plant complex.  For ease
of understanding, these have been separated into three categories,
1) Coal Handling and Storage; 2) Cleaning Equipment; and 3) Other
Facilities.  As appropriate, the influence of each major element upon
the total cost of the preparation complex is given.
                                    13

-------
2.1  Coal Handling and Storage
     Depending upon the layout of the particular preparation plant a
significant portion of the total capital investment will be tied up in
coal handling and storage equipment and facilities.  As addressed by
this study, this category of items includes:
          1)  Raw and Clean Coal Storage;
          2)  Conveyors Handling Coal & Refuse;
          3) , Removal of Tramp Iron; and
          4)  Clean Coal Loading Facilities.
Certainly, the cost of all of these items will vary with the magnitude
of  the plant.  However, additionally their cost will be quite sensitive
to  geographic, environmental, and other factors based upon the site
specific conditions.  In the case of coal storage, closed or silo storage
will cost about five times as much as an open pile of comparable capacity.
Even though this is a severe cost penalty to pay for the advantages of
closed storage, it might possibly be justified on economic grounds and/
or  necessary to meet local environmental restrictions.  Conveyors are
another major expense which vary mostly with the plant layout.  However,
other factors such as the need for secure enclosures or special founda-
tions and supports can radically affect their costs.  Loading facilities
also vary significantly from plant to plant depending upon their level
of sophistication.  The following subsections describe these coal
handling and storage facilities items in greater detail and some of the
principal factors influencing their cost.
                                   14

-------
2.1.1 Coal Storage
     The storage of the raw coal prior to entering the preparation plant
as well as the clean product itself is a significant factor in the over-
all plant layout.  At the raw coal end, adequate storage must be avail-
able to allow for fluctuations in the mining activities while maintaining
a sufficient backlog of material to be efficiently fed to the preparation
plant.  Likewise, at the clean coal end, adequate storage arrangements
must be made consistent with the operation of the plant and shipping
commitments/schedules.  Whether the clean coal is transported to the user
via barge, unit train, or truck, the storage arrangement must provide for
the efficient withdrawal of the material to minimize loading time.
     The options for storage are either open or closed.  In this country
the trend is toward closed storage in the form of large cast-in-place
concrete silos holding as much as 15,000 tons.  However, in some situations,
the classic open storage consisting of a stacking tube and reciprocating
feeders is still determined to be appropriate.  The shift toward silos
is evidenced by the fact that one large organization engaged in the con-
struction of both forms of storage, indicates it is booking orders for
silos at the rate of better than 10 to 1 over open style arrangements.
     Factors influencing the use of silos rather than open storage include:
     1.  Helps insure consistency of feed to preparation plant.  Typically,
         a more uniform material in size and moisture content is withdrawn
         from a silo.
                                    15

-------
     2.   Environmental.   Due to  the dust  and  run-off  from  open  coal
         storage,many situations dictate  the  use of closed storage.   In
         areas  near urban centers,  regulatory bodies  demand such  arrangements,
     3.   Space  Considerations.   Since a silo  requires less land for  the
         same volume of  storage, the price and availability of  such
         additional space can sometimes be a  determining factor.
     4.   Protection from Freezing.   Frozen coal  piles can  be not  only an
         inconvenience but a costly problem.   Although silos provide
         greater protection from moisture and thus freezing, freeze-up
         can occur during extended  severe cold periods such as  the winter
         of 76-77.  When this does  occur, it  requires the  top layer  to be
         broken-up with  jack-hammers or other methods.
     5.   Aesthetics.  Either for internal reasons or  external pressures,
         appearance can  influence the selection of closed  storage.
     Although the cost of maintaining a concrete silo is limited, some
periodic maintenance is  required.  Patching or replacement of portions of
the lining must be performed from time to time.   If coal is permitted to
directly impact the side of the silo at the intake, it will eventually
wear through the wall.  To avoid or mitigate  this situation, baffle  plates
are being installed on many existing silos and most new ones to  deflect the
material.  These plates  must be replaced  periodically to avoid  costly
damage to the silo.
     Today, it  is not uncommon to have single coal silos in the range of
10,000 to 15,000 tons. When greater storage capacity  is required, multiple-
silo configurations are  applied.  The cost of silos in this tonnage class
                                    16

-------
will range from $50 to $125 per ton of storage.  This wide variance
relates to local geologic conditions and the cost and availability of
labor and materials.  As an example, in parts of Illinois, concrete can
be purchased for as little as  $30  per cubic yard, whereas in certain
West Virginia  locations the same volume of mix will cost as much as $75.
These enormous differences in  material cost relate to local competitive
conditions and the distance from source to construction site of not
only the mixed concrete but the components of the mix.
      For the purpose  of approximating  the  current  (mid-1977) capital cost
of  the  various preparation  plants  examined  under Section 5.0,  a cost of
$110  per ton of  storage was  used  for larger cast-in-place concrete silos.
Although in  the  upper part  of the  above  range,  this  figure is  felt to be
a  reasonable estimate of  the  total  cost of  such facilities which can be
adjusted by  the  readers to reflect  exceptional conditions in their particular
area.   The  capital  cost determined in  this manner  is  the fully constructed
price of the silo  alone and  does  not include any of  the necessary conveyors
to  and  from the  structure.   As shown below  in Figure  2-3, such conveying
requirements can  be extensive.
                               FIGURE 2-3
                            COAL STORAGE SILO
                                    17

-------
2.1.2 Conveyors
     Another element common to all coal preparation plants, regardless
of how simple, is a variety of conveying requirements.  These requirements
can be quite extensive depending upon the plant size and layout.  For
even medium size operations, it is not uncommon to move material several
hundred feet from raw coal storage into the plant and then a comparable
distance from the plant to the load-out area.  Additionally, conveyors
are required to handle the refuse from the plant and if thermal drying
is included a further conveying requirement must be met.
     Although vibrating conveyors have some application for moving coal
short distances in and around a preparation plant, their use is limited.
The major conveying requirements are met with belt conveyors which come
in a wide range of sizes and configurations.  As applied to a preparation
plant, belt conveyors are selected on the basis of their ability to
deliver given dry and wet tonnages between two points at a specified
rate.  Such factors influence the belt width and material, idlers, drive
motors, structural requirements, etc.
Belt Conveyor Costs -
     Depending upon the width and type of belt, distance traveled,
elevation, and structural and foundation requirements, the price of belt
conveyors will vary significantly.  Therefore, based upon a sampling of
mid-1977 prices for actual installations, we have established general
installed pricing guidelines for various belt widths on a per linear
foot basis.  These estimated prices have been observed in determining
the capital requirements for the coal preparation plants examined under
Section 5.0 of this study.  They are as follows on the next page:

                                    18

-------
                   36 Inch Width - $480 Per Foot
                   42 Inch Width - $520 Per Foot
                   48 Inch Width - $560 Per Foot
                   54 Inch Width - $600 Per Foot
     Although there may be special applications for belt conveyors of
smaller or larger widths than those given above, our experience
indicates their use is limited.  These prices are indicative of quality
Installations requiring some "normal" foundation work and include all
labor, materials, and electrical hook-up necessary for construction of
a fully tested conveyor.  We feel they are valid for estimating the
cost of lengths between 100 to 500 feet which do not have exceptional
elevation requirements.  When this occurs, the price can increase by
as much as a factor of two or more.  Conversely, when ground level
conveyors can be installed without extensive foundation work, a signi-
ficant savings over these estimated prices will be realized.
     Our purpose in identifying the estimating procedure observed is
to give users of the study the opportunity to make their own adjust-
ments for significant variances brought on by unique site specific
conditions.  Since certain conveying requirements would exist whether
there was a coal preparation plant or not, only those belts considered
unique to the plant have been included in the capital costs presented
in Section 5.0.  For example, transporting of the material from the
mining area to raw coal storage has not been included.
                                19

-------
2.1.3  Tramp  Iron  Removal
     During the mining process, stray ferrous material is loaded out with
the raw coal  and can find its way into the preparation plant.  This
material comes from broken tools, continuous mining bits, and other miner
induced sources.  Although the amount of such material, known as tramp
iron,  is relatively small, it can cause significant damage to the coal
preparation equipment if not removed at an early stage in the process.
Some of this debris is removed by rough screening (scalping) or by the
rotary breaker if such steps are in the pre-preparation coal handling
equipment.  However, even if these types of equipment are present, it is
common to place an electromagnet over the conveyor belt feeding the plant
to  insure the removal of the tramp iron.
     Typically the magnet is suspended by threaded rods and turnbuckles
over the trajectory of the material being discharged from the belt con-
veyor  as shown in Figure 2-4.
      SELF  CLEANING
         BELT
                                                                  ELECTROMAGNET
                                                            CAPTURED
                                                            FERROUS
                                                            MATERIAL
                              FIGURE 2-4
                  TRAMP IRON  REMOVAL  FROM RAW  COAL
                                  20

-------
When the conveyor speed is 350 feet per minute (FPM) or more, this
arrangement promotes maximum removal efficiency since influence of the
magnetic field is most effective when the material is "opened-up" in
flight.  Additionally, the material is moving directly toward the face
of the magnet and the momentum of any tramp iron assists in its capture
by the magnet.  Such magnets are available in both manual and self-
cleaning types as well as explosion proof designs.
     From a design standpoint, the magnet should normally be at least
as wide as the width of the belt.  Other factors influencing the
selection of an appropriate tramp iron magnet are:

       1.  Depth of Feed
       2.  Suspension Position
       3.  Tramp Iron Size  (minimum & maximum)
       4.  Size Consist of  Feed
       5.  Belt Speed
       6.  Feed Rate
       7.  Operating Temperature Range
       8.  Head Pulley Material
       9.  Head Pulley Diameter
       10.  Available Current  (AC or DC)
       11.  Degree of Troughing  Idlers  (if magnet  is  not
           placed over head pulley)
                                    21

-------
2.1.4 Loading Facilities
      Following the preparation process, the clean coal  is normally
conveyed to an open or closed storage area to await transportation
to the user via any number of methods.  In some cases, this may be as
simple as a conveyor belt direct to the power plant.   Where short
distances are involved, trucks also fill an important role.  However,
most prepared coal is transported via railroad or barge.   When available,
transportation via water is the least expensive of the two major methods.
Barge loading facilities normally consist of a docking area capable of
handling six to eight barges each having a capacity of 1000 to 1500
tons.  Coal is fed into the barges via a telescoping tube at the rate
of 1000 to 1500 tons per hour (tph).  The cost of such facilities varies
significantly depending upon the difficulty of placing pilings and
other structural members necessary to secure the docking  area.  How-
ever, based upon the cost of recently completed facilities of this
type, $1.5 million dollars is a good approximation for a  river location
capable of loading at the rate of 1000-1500 tph.
      The most common method of coal shipment is the railroad.  For
obvious reasons, rate preference is given to train-load shipments.
Therefore, it is advantageous to the plant operator,  if delivery com-
mitments allow, to accumulate the clean product until there is a suffi-
cient amount of coal  to fill a complete train of 80 to 100 cars, each
holding up to 100 tons.  For larger coal preparation plants making
numerous train-load shipments annually, it is usually of economic
                                  22

-------
benefit to negotiate a unit-train arrangement.  Although there is a
variety of unit-train agreements unique to the given situation, the
normal arrangement is to dedicate the particular train to hauling
coal between two specific points over an extended term.
   When appropriate to the particular situation, unit train can pro-
vide a substantial savings over regular railroad shipment.   In order
to maximize the savings associated with this method of transportation,  a
fast efficient loading system must be available.  There are currently
in existence many unit train load-out facilities which have the cap-
ability of loading a 100-car train in less than four hours.  For ex-
ample, at the Leahy Plant of Amax Coal, cars are automatically flood
loaded at the rate of 5500 tph from a 200-ton over the track, loading
bin.  The bin receives 5500 tph via a 296 foot long 7 foot  wide belt
from a 15,000 ton concrete silo with eight 750 tph reciprocating
feeders.  This rapid car loading rate is possible with the  installation
of a special bin with pneumatic gates which are controlled  by an elec-
tronic system actuated by beams of light directed across the railroad
tracks.  As the cars pass through the beams of light, the position of
the empty hopper is known and the loading bin gates opened  or closed
accordingly.  With this system, the average 100-car unit train loading
time is broken down as follows:
                  Train Loading            110 Minutes
                  Train Switching          100 Minutes
                  Delays                    20 Minutes
                                   Total   230 Minutes or 3 Hours and
                                                        50  Minutes
                                    23

-------
   Similar success has been achieved with over the track silos where
the train passes through a tunnel at the base and is flood loaded.
  Although the costs associated with these facilities are justified by
the resultant savings, they add significantly to the initial capital
requirements.  Depending upon the sophistication of the arrangement,
unit-train loading facilities will add from $400,000 to a million
dollars or more to the total cost of the complex.  Since there is
such a wide cost range, a figure of $500,000 was applied to those prep-
aration plants covered by Section 5.0 where unit-train facilities were
appropriate.  This figure was selected as being representative of an
adequate  facility which readers may amend to fit their particular
circumstance.  Further, the reader may wish to delete such cost en-
tirely on the grounds that it is not attributable to coal preparation
since even without cleaning some type of loading facility would be
required.
                                    24

-------
2.2 Cleaning Equipment
     Although the entire preparation plant complex must be considered
as an integrated functioning unit, we have, later in this section,
separated the major items of equipment directly involved in the coal
cleaning process for individual discussion.  The majority of these
pieces of equipment are found inside the cleaning plant.  However,
certain pieces such as rotary breakers and scalping screens do perform
an important cleaning function outside the plant proper.  Each major
category of equipment provides a particular function which takes on
varying degrees of importance depending upon the raw coal and the
preparation process or processes being applied.  Before discussing
these individual categories of equipment,a few general  comments on the
major coal cleaning processes are in order.
     As mentioned in the Introduction, most physical cleaning methods
are wet in nature.  The most common of these methods uses water as the
separation medium.  Prior to 1940, nearly all wet cleaning was accom-
plished by some method based upon water only.  Since that time, heavy
media processes have been gaining in popularity, but, as indicated by
Table 2-1  , are not as widely used as water only cleaning.  Some of the
more common equipment utilizing this medium include jigs, concentrating
tables, and hydrocyclones.  The water separation technique employed by
the first two pieces of equipment is based upon the phenomenon of hindered
settling.  Briefly stated, when a mixture of water and solids is agitated
it responds as a single fluid of high specific gravity, with each
solid particle tending to behave independently of all other particles.
                                    25

-------
Therefore, as any given particle begins to settle, it is settling in
a medium which effectively has a higher specific gravity than water.
The objective of physical coal cleaning methods employing this technique
is to simulate a specific gravity close to that necessary to effect the
desired separation of the coal from the accompanying heavy impurities
(refuse).
     As with all approaches to coal cleaning, there are relative strengths
and weaknesses which make one process more or less advantageous under
various conditions.  The advantages of water only cleaning processes
include:
          1.  Lower capital and operating cost than heavy
              media processes of comparable capacity.
          2.  When the amount of near-gravity material is 10%
              or less, - The efficiency of separation can approach
              that achieved with heavy media processes.
          3.  Can be cost-effective as a primary rough washer
              prior to heavy media thus reducing the more expensive
              heavy media cleaning capacity.
     As would be expected from the above description of hindered settling,
the major limitation of water only processes is their inability to make
a sharp separation between coal and refuse.  When there is a significant
amount of near gravity material present care must be exercised in apply-
ing this technique so as to not discard too much coal which could be
economically recovered by another process.
     As commonly applied today, separation of coal and refuse by heavy
media processes is accomplished in a suspension of magnetite and water.
By varying the amount of magnetite, a medium can be created which has
a specific gravity close to the desired gravity of separation as
                                  26

-------
determined by float-sink analysis.  Although expensive (approximately
$70.00 per ton), magnetite has superior properties to any additive
developed for this purpose thus far.  In addition to being non-toxic,
magnetite can be effectively recovered by magnetic separators.  Further,
because of its high density, the volume concentration of magnetite is
kept low.  As an example, when only ten pounds of magnetite is added
to one gallon of water the specific gravity of the mixture is increased
to approximately 1.8 grams per cubic centimeter.
     Equipments based upon this separation process include heavy media
vessels and cyclones.  As discussed later, these equipments take on
various configurations based upon the size and composition of the
material they are handling.  Generally, these equipments are more
costly to install and operate than those using water only as the
separation medium.  The higher capital cost is mainly attributed to
the additional equipment and facilities associated with pumping,
monitoring, and recovery of the magnetite.  Operating costs are higher
because of the greater equipment capacity to maintain and the loss of
magnetite which can be over a pound per ton of clean coal product. Further,
careful sizing of the feed to heavy media processes is necessary to minimize
undersized material.  Such material is separated less effeciently and
tends to increase magnetite consumption by contaminating the circulating
medium.  In spite of these higher costs and performance limitations,
equipment based upon the heavy media separation process can provide
a more economic solution to cleaning certain coals.  Since the sharpness
of the separation can be controlled more closely than water-only processes,

                                   27

-------
such equipments can still work well in the presence of larger amounts
(25% or more) of near-gravity material.  This means that when applied
to a closely sized feed, they will be able to approach the theoretical
separation limits of the float-sink analysis.
     The final  major cleaning process to be covered, before discussing
the individual  equipment, is froth flotation.  This process relies upon
the surface chemistry of coal to effect a separation of coal  and its
accompanying refuse.  Its major advantage is the ability of this process
to clean very fine size coal (approaching zero).  To effect a separation,
a slurry of coal and water is conditioned with frothing and collecting
reagents.  Then, as air is bubbled through the slurry, the coal  particles
attach themselves to the bubbles and report to the surface as a  froth  where
they can be collected.   The clay and shale impurities  stay in the slurry
and are drawn off separately as refuse.  When applied to higher rank
coals (bituminous and anthracite), flotation can be very effective
in reducing the ash content although it is not as effective in re-
moving pyrites as some other processes such as concentrating tables
and hydrocyclones.   Besides the difficulty of controlling the accuracy
of the separation,  one of the major limitations of this process is that
it is presently only effective when treating non-oxidized bituminous
coals and anthracites.   Further, since the response time is slow, the
slurry must be retained for an extended period creating the need for
excessive handling  capacity.  This weakness is being somewhat overcome
through more e/ficient mechanical designs.
                                   28

-------
     As currently applied, most preparation plant design centers around
either a water only or heavy media process.  In both cases, froth flota-
tion may be used on the finer size (28 mesh X 0 and 100 X 0) fractions
depending upon the economics of the particular cleaning application.
However, this is not to say that water-only and heavy media processes
cannot be effectively applied in the same coal  preparation circuit.   As
an example, water-only cyclones are commonly used as roughing cleaners
which produce a low gravity overflow product that reports to clean coal.
The underflow product is then retreated in heavy media cyclones at a
somewhat higher specific gravity of separation.  Then, finer size fractions
can be handled by additional water-only cyclones, concentrating tables,
and/or froth flotation as appropriate to most economically achieve the
desired end product.  By combining these processes, some of the more ex-
pensive heavy media capacity can be eliminated  thereby making for a  more
cost-effective preparation circuit.  In Section 5.0 there are some examples
of combined processes.  Specifically, Examples  6 and 7 use heavy media
and froth flotation while Example 8 uses heavy media and concentration
tables.
     This very brief exposure to the major cleaning processes should aid
in the reader's understanding of the following sub sections which describe
the equipment used to implement these processes.  Where appropriate, an
indication is given as to the sensitivity of cost to capacity or other
measurable factors.
                               29

-------
2.2.1 Size Reduction Equipment

     Almost without exception,  coal being handled by a preparation

plant will at some point from the mine to load-out be reduced in

size.  Typically, in many larger preparation plants cleaning both the

coarse and finer size fractions there will be a sequence of size re-

ductions.  The first or primary reduction will normally take place

prior to the coal entering the cleaning plant.  One widely used approach

is to feed the raw coal from storage to a rotary breaker which, as

described below, not only performs a size reduction function but also

removes some debris.  This arrangement is as shown in Figure 2-5.
          BELT FROM
       RAW COAL STORAGE
ROTARY BREAKER
    FEED BELT
TO CLEANING PLANT
                              FIGURE 2-5

                    ROTARY  BREAKER  INSTALLATION

     The  rotary breaker  is not a positive crushing device, but instead

accomplishes  its  size  reduction function through the gravity impact of

the  coal  dropping from a height to break it to the desired size.  A more

complete  understanding of  this action can be had by looking at Figure 2-6

which  is  a cutaway  view  of a  breaker manufactured by the McLanahan Corpor-

ation.
                                   30

-------
 FEED END
OF.BREAKER
                         ROTATING DRUM
                         COVERED WITH
                         REPLACEABLE
                         SCREEN PLATES
  ROTATING
LIFTING SHELVES
  (LIFTERS)

                                                               REFUSE-PASSES
                                                                THROUGH DISCHARGE
                                                                 END OF BREAKER
                                 PRODUCT FROM BREAKER
                                  PASSES THROUGH SCREEN
                                  PLATES INTO COLLECTION HOPPER
                                FIGURE 2-6
                       CUTAWAY VIEW OF ROTARY BREAKER
        Essentially, the breaker consists of a rotating drum lined with
   screen plates having openings equivalent to the desired product size.
   As the raw feed enters the breaker, it is picked up on lifters attached
   to the inside of the rotating drum and then fractures as it drops on
   other coal or the screen plates.  That material which breaks to within
   the size of the screen plate openings passes through and is fed to the
   cleaning plant.  Rock and other material which do not fracture to the
   size of the screen plate openings move along the length of the drum until
   they are discharged through the refuse end of the breaker.  If properly
                                        31

-------
matched to the particular raw feed, this piece of equipment can perform a
valuable and efficient initial cleaning function.  Advantages of breakers
include: minimum fines, high capacity-to-horsepower ratios, and ability
to reject coarse refuse.  The disadvantages included: operation influenced
by moisture content of feed, not appropriate for finer sizing, and
difficult to adjust product size.
     The rotary breaker is the one  type of physical cleaning equipment
which  performs its function by relying upon the difference in hard-
ness between coal and rock.  Coals  which are too hard will not
completely  fracture over the length of the drum with the  result being
a  significant portion of coal will  be lost through the refuse end of
the  breaker.  The hardness of a coal is normally expressed as a
Hardgrove Grindability  Index number.  The higher the number, the softer
the  coal.   For example, a Hardgrove number of 80 to 100 indicates a
softer coal, whereas a  number of 40 to 60 relates to a harder coal.
As a general rule, rotary breakers  are not applicable for coals having
a  Hardgrove Index much  below 50.   In these cases, a positive action
crusher would be used for reducing  the raw coal to the proper size
consistent  with the cleaning process or processes selected.
     Depending upon the manufacturer and application, rotary breakers
come in a range of diameters from  7 to 12 feet and lengths up to
20 feet.  Maximum feed  size is based upon the feed opening of the
breaker.  In the case of breakers manufactured by the McLanahan
Corporation, the following relationships exist:
            Breaker Diameter:  7 Ft.  9 Ft.  11 Ft.  12 Ft.
            Maximum Feed Size:  12  In.  18 In.  24 In.  30 In.
                                      32

-------
Although the feed opening can be modified to meet a specific
application, the McLanahan Corporation does not recommend deviating
far from these relationships.
     In addition to feed size, moisture content, and hardness, the
selection of a rotary breaker is based upon the required capacity.
The capacity is influenced by the amount of refuse in the feed and
the allowable limits of oversize and undersize product.  As stated
above, the product size is determined by the openings in the screen
plates.  If oversize is permitted in the product, the capacity of
the breaker may be increased by making the openings 1/4 to 1/2 inch
larger than the desired product.
     As would be expected, the F.O.B. factory prices of rotary breakers
vary with size, design, and manufacturer.  For example, one manufacturer
has a line of 10 ft. diameter breakers which cost from $100,000 to
$130,000 in 12 and 16 ft. lengths, respectively.  These units have
nominal capacities of 500 to 1400 tons per hour depending upon the
specifics of the coal and product requirements as noted above.  Another
manufacturer has a 9 ft. diameter, 15 ft. long unit which sells for
$80,000, and an 11 ft. diameter, 18 ft.  long breaker at $95,000.  Although
all of these units perform the same basic functions, they do have
different design configurations which may show advantages under
varying applications.  Another factor to consider is the extent to
which the unit is assembled when it arrives on site.  Some breakers
come from the manufacturer nearly fully assembled thus reducing
installation time and cost.  However, for the purpose of approximating
the installed cost of outside equipment of this type, including the
necessary structural work as shown in Figure 2-5, an amount equal
to  two times the F.O.B. factory price is representative for mid-1977.
                                  33

-------
     In addition to the rotary breaker, there is a variety of large
scale crushers for making a primary size reduction of run-of-mine
coal.  These units are available from a number of manufacturers in
various configurations capable of handling feed sizes up to 60 inches
cube at rates as high as 3,000 tons per hour (tph).   Two of the more
popular crusher configurations of this type are the single roll  crusher
and the single rotor impact crusher shown in Figure 2-7.
                           '
     SINGLE  ROLL  CRUSHER                            SINGLE  ROTOR
                                                   IMPACT CRUSHER
                              FIGURE 2-7
                 PRIMARY  SIZE  REDUCTION  EQUIPMENT
      Units  of this  type  are designed  to operate at slow speeds so as
 to  produce  a  fairly uniform product and limit  the  generation of fines
 which can be  detrimental  to the  efficient  functioning  of the plant.  Of
 these two configurations,  the single  roll  crusher  has  been the standard
 primary reduction piece  in the coal industry.  This  popularity relates
 to  its ability to rapidly  reduce slabby feeds  of almost any hardness to
 cubical  products with  a  limited  amount  of  fines.   Roll crushers are
 further characterized  by low  headroom and  power consumption as well
 as  the ability to handle wet, sticky  feeds with a  high percentage of
 clay.   The  only  major  operational  weakness of  a single roll crusher is
 relatively  low reduction ratios  of about 6 to  1.   Other configurations

                                  34

-------
       such as the double roll crusher have even lower ratios (4 to 1).  This
       limitation is overcome by the impact type crushers which have reduction
       ratios of as high as 30 to 1.
            However, the final selection of a crusher is based upon the
       nature of raw coal, the feed size, the desired product size, and the
       required capacity.  With regard to the nature of the raw coal, the
       following characteristics are important:  1)  hardness (Hardgrove index);
       2)  moisture content; and 3)  percent and type of refuse.  The feed size
       is important to determine the dimensions of the crusher, particularly
       the roll diameter in the case of that type crusher.  Capacity is a
       function of all of the factors thus far considered.  For single and
       double roll crushers, most manufacturers determine the capacity by
       first calculating the theoretical ribbon.  The theoretical ribbon
       is the solid ribbon of coal and/or rock which would pass through the
       crusher without taking into account the crushability of the particular
       material.  This theoretical ribbon which considers the bulk density of
       the feed and the space occupied by the roll elements or teeth is cal-
       culated as follows:
                      THEORETICAL RIBBON CAPACITY (tph) =
Roll  Diameter X Roll Width X Roll  Speed X Crusher Setting X Bulk Density X Time
                       Conversion Factors (1728 X 2000)

               Where:   Roll  Diameter & Width is in inches
                       Roll  Speed (RPM X TT) = Peripheral Speed
                       Crusher Setting = Desired Product Size X 2/3
                       Bulk Density is in Pounds/Cubic Feet
                       Conversion Factors:   Time = 60 Minutes/Hour
                                            1728 Cubic Inches = 1 Cubic Foot
                                            2000 Pounds = 1  Ton
                                          35

-------
Once the theoretical ribbon capacity is known,the actual or practical
capacity is merely a function of the crushability (hardness
factor) of the material.  This relationship is as follows:

ACTUAL RIBBON CAPACITY  (tph) = THEORETICAL RIBBON X HARDNESS FACTOR

     For most coal the actual capacity is approximately 2/3 the theoret-
ical and 1/3 for rock.  However, the capacity for coal or rock is the
same in most situations because rock is twice as heavy as the coal but
has twice the hardness.  From the above relationships, it is observed that
an adjustment of the roll speed and/or increase or decrease of the
product size will result in a direct change in capacity.  Another rule-
of-thumb exercised by the crusher industry is that as the capacity of
the crusher is exceeded by 10-15%, the amount of oversize material in-
creases radically.
     As would be expected, the F.O.B. factory price of crushers is
related to feed size and rate (capacity), type of design, and manufacturer.
Further, the price is sensitive to the duty cycle.  Manufacturers offer
a range of machine strengths varying from heavy duty crushers applicable
for use on harder coals with abrasive refuse to lighter duty machines
handling clean coal from which the majority of the refuse has been re-
moved.  For estimating  the cost of heavier duty primary size reduction
equipment as a function of feed size and capacity, the F.O.B. factory
prices of the "Coalbuster" line of single rotor impact crushers gives
a good approximation.   A picture of this type of crusher produced by
the Jeffrey Manufacturing Division of Dresser Industries was presented
                                   36

-------
in Figure 2-7.  This piece of equipment sells for from $36,500 to
$161,000 depending  upon feed capacity.  These machines are externally
adjustable  to permit  product sizes  of  from  6 to  2  inches.  Although
the final selection and thus price will vary with  the particular
application,  the following specific pricing may  be used as a guide:
                            Nominal Capacity Based
Nominal  Feed  Size           Upon a  5-6" Product           Price
        30"                       300 tph                  $36,500
        40"                       600 tph                  $65,360
        50"                       900 tph                  $73,800
        60"                       1750 tph                  $113,700
        60"                       2600 tph                  $161,000
The above nominal feed sizes are rarely encountered due to the mechanized
mining  methods employed today.  However, the crusher feed openings are
kept wide to  allow  for variations in the raw coal  as well as handle
greater volume.
     Smaller  scale  reduction equipment capable of reducing coal to a
size of 2 inches or less is also available from a wide variety of
sources.  This category of equipment is typically referred to as secon-
dary, since its normal function is to crush coal which has already been
reduced from  its ROM state.  A typical  application is to further reduce
the larger clean coal  product from a coarser cleaning process such as a
Baum jig or heavy media vessel  prior to load-out or additional  cleaning.
However, depending upon the mining method and other factors,  crushers of
this type can be applied in a primary role treating ROM coal.
                                 37

-------
     As stated above, secondary size reduction may take place several
times within the cleaning plant depending upon the sophistication of
the process.  Double and multiple roll type crushers are commonly
used for this secondary reduction of coal to smaller sizes.  However,
there are configurations which combine the compression crushing concept
of the traditional roll crusher with the inherent high capacity capability
of the impact type crusher.  One such unit is the "Flextooth" crusher
produced by Jeffrey Manufacturing.  The trade name of this line of
crushers is derived from the design of the crushing elements which per-
mits them to "flex" back away from the crushing area when experiencing
tramp iron or other uncrushables.  This unit, as with the roll type
crushers, is characterized by a slower operating speed to promote
uniformity of product and limit the creation of fines.
     As would be expected, the cost of secondary crushing equipment is
most sensitive to feed size and capacity.  Capacity is greatly influenced
by the desired product size and moisture content.  This latter factor
can be extremely significant when crushing clean coal following wet
processes such as a heavy media vessel or Baum jig.  When the moisture
content of  the crusher feed is high, the smaller particles will tend to
stick  to the rollers, thereby degrading performance.  To cope with this
problem, wipers are installed to scrape the sticking material from be-
tween  the crusher teeth.   In the case of some double roll crushers, each
roll may be operated at a  different speed to help alleviate this problem.
     Normally, these secondary units are not as  large as the primary
cursher  since they are only handling a portion of the plant feed.  Further,
they are lighter duty because much of the hard,  abrasive refuse has been
                                   38

-------
 separated from the softer coal.  As with primary crushers, the final
 selection and thus price of secondary size reduction units will  vary
 with the specifics of the situation.  However, for the purpose of esti-
 mating the cost of secondary crushers on the basis of capacity the follow-
 ing F.O.B. factory prices give a reasonable approximation as of mid-1977:
                                Nominal Capacity Based
Nominal Feed Size         Upon a 2 Inch or Less Product Size     Price
       14"
       14"
       20"
       24"
       24"
       28"
       30"
 Although  the feed to this  equipment  would  rarely  reach  the  nominal  sizes
 noted above, the feed openings  are kept large  to  accommodate  the  volume
 and variation in feed consistency.   The capacities  above  are  based  upon
 a 2 inch  product; as the product size is cut in half, the capacity  is
 likewise  affected.   Since  this  equipment is  normally used inside  the
 cleaning  plant, its fully  installed  cost is  between 2 and 3 times the
 above prices.
165
245
500
635
1065
1540
2500
$8,800
$12,100
$20,400
$33,100
$48,300
$59,000
$94,100
                                     39

-------
2.2.2 Screens
     There is not a coal preparation plant in existence that does not
utilize a stationary or vibrating screen in some portion of the circuit.
Screens perform a variety of sizing and collection functions critical
to the overall success of the preparation process.  These functions
include:
     1.  Coarse Scalping of Smaller Material Prior To Initial Size
         Reduction.
     2.  Separation of Various Sizes of Material Throughout The Process.
     3.  Collection of fluids combined with the coal or refuse.  This
         may  take the form of simple dewatering or the draining and
         rinsing of the material to remove and collect the expensive
         heavy media (eg. magnetite).
     As noted elsewhere, the proper selection and maintenance of
screens is essential to the realization of the predicted performance
and life expectancy of the screens themselves as well as other
pieces of equipment within the circuit.  For example, if a screen is
passing a coarser material ahead of  cyclones, the predicted  classification
will not be achieved and wear will be accelerated.  Situations of this
type are rapidly reflected in increased operating and maintenance
costs brought on by greater amounts of downtime for repair and replace-
ment with the associated materials and labor.   It is for these reasons
                                    40

-------
that a rigidly enforced screen maintenance procedure should be followed
in all preparation plants.  In addition to lubrication and alignment, this
procedure should include a provision for periodically checking the tension
on the screen decks as well as the surface for holes.  When the wire cloth
is loose, it results in excessive stress which leads to broken wires, the
major cause of premature cloth failure.
     Initially the selection of screens is merely a function of plant
size and cleaning method.  Influencing this selection are such factors as:
1) feed rate to screening station; 2) maximum size anticipated; 3) size
analysis of feed; 4) required separation and efficiency; and 5) percent solids
in feed. However, there are other important considerations which will in-
fluence the initial cost as well as the longer term operating and main-
tenance expense.  These additional considerations involve such things as
existing regulations regarding safety as well  as noise and dust emission.
For this reason, explosion proof motors may be required at dry screening
stations in addition to rubber or polyurethane decking to reduce noise.
Special noise reduction mountings and dust enclosures may also be necessary
on vibrating screens.  Since there is such a large set of variables
affecting screen selection and thus cost, we have not as yet developed
a simple formula for determining capital cost without knowing details of
the screening application.  Therefore, for the purpose of approximating
the capital cost of the preparation plants examined under Section 5.0,
actual price quotations as of mid-1977 were obtained from various screen
manufacturers and applied accordingly.
                                   41

-------
SCALPING FUNCTION -
     This activity which normally takes place outside of the actual prep-
aration plant is often applied ahead of the primary size reduction equip-
ment such as a rotary breaker or coal crusher.  One such application  is
shown below in Figure 2-8.
           RAW COAL

ROTARY
BREAKER

                                                            REFUSE
      5  Inch X 0
5 Inch X 0
                                                     TO PREPARATION PLANT
                             Figure 2-8
                   APPLICATION OF SCALPING SCREEN
      The  raw coal is conveyed to a feed box located above the scalping
 screen.   In addition to absorbing the initial impact of the coal drop-
 ping  off  the conveyor belt, the feed box spreads the material over the
 screen for more efficient operations.  Normally, the scalper is a
 rugged single deck vibrating screen mounted at a 20° angle to promote
 material  flow and separation.  In a typical installation as shown above,
 the screen will pass 5 inch or less material with the oversize going
 to the breaker for further reduction.  This is a cost-effective
 arrangement by reducing the amount of breaker capacity needed and also
 permitting the breaker to function more efficiently.
      The  material which fractures to the size of the breaker screen
                                    42

-------
plate openings passes through and joins that which was scalped off
by the scalping screen.  Rock and other debris which did not break
down to 5 inches or less passes out the refuse end of the breaker and
is disposed of accordingly.
SIZE SEPARATION  FUNCTION  -
     Following the scalping operation as described above, the coal must
be separated into sizes suitable for load-out as is or further treatment
within the preparation plant.  Typically, the coal enters a feed box
ahead of the sizing screen.  As with the scalping screen, this feed
box reduces the impact of the coal onto the screening surface and pro-
motes a more even materials flow.  Commonly, the sizing screen is a
double deck vibrating type mounted on an angle of approximately 20 degrees
in the manner shown below in Figure  2-9.
                             5 Inch X 0
                1-1/4  Inch
                  1/4  Inch
RAW COAL SIZING
     SCREEN
                                                 5X1/4  Inch
                                                         TO  COARSE
                                                          CLEANING
                      1/4  Inch  XOJTQ F|N£
                                        CLEANING

                                FIGURE 2-9
                   APPLICATION OF RAW COAL SIZING SCREEN
 Depending upon the nature of the coal, the top deck will have openings
 in the  range of  1 to  1 % inches.  Bottom deck openings  are determined by
 the manner  in which  the  finer material will be handled, but are normally
                                    43

-------
h inch or less.  The inclined vibrating double deck arrangement is
conducive to good separation of the material and thus promotes removal
of the finer particles.  This removal is important in that the effective-
ness of such coarser cleaning methods as the jig and heavy media vessel
is improved  when less fine material is present.  Based upon the level
of preparation, the material passing through the sizing screen may go
either to load-out or into the fine coal cleaning circuit of the plant.
The larger material passing over the screen will move onto an optional
pre-wet screen prior to coarse cleaning.
Pre-Wet Screening Function  -
     A further extension of the separation process occurs at the pre-wet
screen.  This function is described above as optional in that it may be
combined with the sizing operation or omitted entirely depending upon
the make-up of the material to be subjected to additional cleaning.
When there is a significant amount of finer particles still trailing
along  with  the coarse  material, a low pressure  spray of  water can  en-
courage  their  removal  prior  to entering the cleaning vessel.  Typically,
the pre-wet  screen  is  a  horizontally mounted double deck type which
vibrates  to  encourage  the  distribution  and  separation of the material
over  the  two screening surfaces.  This  reduces  the depth of material  on
each  deck and  thus  exposes  greater  surface  area  to the washing  action  of
the water spray as  shown  Figure 2-10, which is  a photograph of  a  pre-wet
screen in operation.
      Typically, the top  deck of the pre-wet screen has openings of
approximately one  inch with  the bottom  deck passing material of 1mm  or
less.   All  material passing over these screens  is fed to the course

                                    44

-------
                                                                      WATER
                                                                         SPRAY
                                FIGURE 2-10
                       PRE-WET SCREEN IN OPERATION
washing vessel (jig or heavy media).  The fines passing through are handled
by a number of other methods depending upon the nature of the material  itself
and the sophistication of the fine cleaning portion of the preparation  plant.
In some cases the material may be dewatered in a centrifugal dryer and  con-
sidered clean or refuse based upon its composition relative to the clean
coal specification.  Where it has been determined economic, this fine material
may undergo additional cleaning.  If a fine coal cleaning circuit is included
in the plant, this and the less than 1/2 inch material will be further  sized
on what is referred to as a desliming screen.
Desliming Screen Function -
       As mentioned above, the function of the desliming screen is to per-
form a further sizing of the finer material making for more efficient cleaning
                                     45

-------
in the fine coal  portion of the plant.  This screen is normally a horizon-

tally mounted single deck type which vibrates while receiving a spray of

water to encourage the separation of the extremely fine materials; i.e.

less than 1/2 mm (28 mesh).  The name desliming comes from the function

it performs since it removes very fine material.  Depending upon the nature

of the sulfur content in the coal, this very fine material may contain a

high percentage of pyritic sulfur which was released during mining or

earlier  in the preparation process by crushing.  To improve efficiency and

reduce the size of the  desliming screen, the material normally first passes

over  a sieve  bend as shown Figure 2-11.


       1/2 Inch  X  0

                   ~                    DESLIMING SCREEN


                                               1/2  hich X 28 Mesh

                    BEND  X                   T0 FURTHER
                                   ^            FINE CLEANING

                        28  MESH X 0
                      TO ULTRA-FINE
               CLEANING OR DISPOSAL

                                FIGURE 2-11

                      APPLICATION OF DESLIMING  SCREEN

       To promote better separation, the depth of material on the deck should

  be kept  to a minimum. The 1/2 mm or greater material  passing over this screen

  proceeds to  the next portion of the fine cleaning circuit which may include

  Deister tables and/or cyclones.  The less than 1/2 mm material which was

  washed  through the screen may be either directed to froth flotation cells

  or cyclones  for further recovery of clean coal or to a static thickener for

  eventual disposal.  Obviously, the option elected must be based upon the

  economics specific to  the situation.   However, current technology and
                                       46


-------
environmental considerations along with the price of coal are increasing
the economic applicability of such finer recovery techniques.
FLUIDS COLLECTION FUNCTION -
     Of the functions performed by screens, those involving the collection
of fluids are most influential on plant capital and operating costs.  One
such cost saving function occurs in the recovery of dense media by drain
and rinse screens.  These screens promote a higher recovery.of expensive
heavy media such as magnetite which helps to keep operating costs down.
Another cost saving function is performed by dewatering screens.  By re-
ducing most of the free water mixed with the coal, these screens not only
improve the handling properties of the solid material, but also help to
reduce the capacity of other dewatering equipment in the preparation plant.
Heavy Media Recovery Function -
     Drain and rinse screens are positioned in the preparation circuit to
handle the clean product as well as the reject from any prior equipment
in which a dense media such as a magnetite/water slurry was the vehicle of
separation.  Since the fluid accompanying the material from heavy media vessels
and cyclones contains a high concentration of an expensive material  such as
magnetite, these screens are used to collect as much of this fluid as
possible so that it may be reused.  This process is normally accomplished
by a horizontally mounted double or single deck vibrating screen over
which a low pressure spray of water is applied to rinse off the heavy media
clinging to the coal and refuse.  To aid the process and reduce the screen
size, the material normally passes first over a sieve bend or cross-flow
screen as shown in Figure 2-12.  The vibrating motion promotes better
separation of the material over the screen decks giving greater effective-
ness to the rinsing action of the water spray.  For this reason, one of the
                                      47

-------
               FEED!
                    \
                SIEVE
                 BEND
                               DRAIN & RINSE SCREEN


_ _A_ j
4

X

TO LOAD-OUT 0
FURTHER DEWATER


                             HEAVY
                             MEDIA
t
DILUTE
MEDIA
                              FIGURE 2-12
             DRAIN & RINSE SCREEN FOR HEAVY MEDIA RECOVERY
key design criteria is to size the screen properly so the bed depth is kept
to a minimum.  As noted in the figure above, those fluids collected over
the first half of the screen are referred to as heavy media and those
from the second half as dilute media.   Under normal  operation, most plants
route the heavy media directly back to the vessel or cyclone media feed
circuit and the dilute media to magnetic separators which recover the
magnetite for reuse.  Typically, the screen openings of the bottom deck
are kept small, thereby passing the fluid containing the magnetite but
only negligible solids.  When a double deck arrangement is used, this
screen can also serve in a sizing capacity.
Dewatering Function -
     As the name implies, the primary purpose of dewatering screens is to
remove as much of the free moisture as possible in the material they handle.
The need to perform this function is universal to preparation processes in-
volving both heavy media and water only.   In the case of heavy media pro-
cesses, the dewatering screen may be applied immediately following the
                                    48

-------
drain and rinse process where heavy media was recovered from the clean pro-
duct and the refuse.  For water only processes, like the Baum jig, dewater-
ing screens are normally the first piece of equipment treating the "float"
from the jig as well as the refuse.
     Typically, the dewatering function is performed by a horizontally
mounted single deck vibrating screen.  In many installations, a sieve bend
is placed ahead of the screen.  Unlike the drain and rinse screens used
for heavy media recovery, dewatering screens have dams at intervals along
the screening surface.  These dams develop greater bed depth by restricting
the flow of material and thus give the vibrating action of the screen a
better chance to beat out the water.  Depending upon the particular situa-
tion, these screens may eliminate the necessity for further dewatering
before load out or disposal.  However, in all cases, they improve the
handling characteristics of the material and reduce the load on subsequent
dewatering equipment such as centrifuges.
Sieve Bend Functions -
     In several of the foregoing screening applications, a sieve bend
played an option role ahead of the screen as shown in Figure 2-13.  When
mounted in this way, it not only serves as a feed box to help distribute
the material over the width of the screen but also aids the sizing and
dewatering functions by reducing the load on the screen.  A sieve bend can
also be applied in the preparation circuit by itself to accomplish these
latter two functions.  To explain this action, the reader is referred to
Figure 2-14 which is a cutaway view of a sieve bend manufactured by Heyl
& Patterson, Inc.  As the material enters the feed inlet, a series of
baffles in the sieve bend feed box spread the material so that the slurry
                                     49

-------
                SIEVE BEND
                               FIGURE  2-13



               SIEVE BEND MOUNTED AHEAD OF  VIBRATING  SCREEN



is fed evenly over the width  of the  curved  screen deck.  By the arrange-



ment of the feed spout, the slurry actually drops tangentially onto the



screening surface.  As the layer of  slurry  flows down  the curved  screen,



the thickness is reduced as it passes  over  the  horizontal screen  wires.



In practice, the depth of the slurry decreases  by increments of about



one-quarter the slot width each time it passes  a slot.   As an example,



for a screen opening (slot width)  of 1  mm,  the  thickness of the



slurry layer being shaved off by each  wire  is about 1/4  mm.  This 1/4 mm



thick cut can only transport  particles of up to 1/2 mm in size.   There-



fore, plus 1/2 mm solids pass over the sieve bend.  The  result  is a
                                    50

-------
mo BOX
SIEVE UNO
 GAKf DISCHARGE
                                                                FEED INUT
                                                              "UNIViRSAl"
                                                               REVERSING
                                                               MECHANISM
                                                        EFFLUENT
                                FIGURE 2-14

                      CUTAWAY  VIEW OF  SIEVE  BEND
               MANUFACTURED BY  HEYL & PATTERSON,  INC.
                                       51

-------
reasonably efficient separation of the feed solids at a size considerably
smaller than the screen openings.   This feature of the sieve bend extends
the practical application of screening to much finer coal  sizes by re-
ducing the problem of blinding.
     Sieve bends come in a range of widths, curvatures,and screen (slot)
openings depending upon the application.  When placed ahead of a screen, the
width is normally selected to be one foot less than the screen.  These
simple devices have several advantages which include requiring no operat-
ing power, limited space, minimum supporting structure, and very little
maintenance.  By reversing the sieve bend periodically, the thickness of
the slurry layers passing through the screen openings can be controlled
and uniform  performance maintained.  The sieve bend can be reversed until
the triangular wire becomes worn to the extent that the screening is too
coarse.  According to Heyl & Patterson, Inc., records indicate that the
screening size remains nearly constant during the life of the sieve bend.
     The cost of sieve bends vary as a function of screen curvature and
width.  For  example, a Heyl & Patterson Inc. sieve bend with a radius of
2 ft 6 in and 4 ft wide has a mid-1977 F.O.B. factory price of $2,600 or
$650 per foot of width whereas one with a 5 ft radius and 4 ft wide sells
for $3,952 or $988 per foot.  For purposes of approximating the current
capital cost of the various preparation plants examined under Section 5.0,
a per foot of width price of $800 was applied uniformly regardless of radius
                                   52

-------
2.2.3 Baum Jig
     The term jig describes a machine used for classifying materials
of different specific gravities or unit weights by the pulsation of a
stream of water flowing through a bed of the materials.  As the water
pulsates or "jigs" up and down, the heavier material is encouraged to
settle to the bottom of the bed and the lighter material  to rise to the
top.  After this classification is made, the heavier material  (sink) and
the lighter material (float) may be drawn off separately.  This process
can be particularly effective for the separating of heavier refuse from
run-of-mine coal.  Since coal has a specific gravity of 1.3 to 1.5, it
will tend to "float" and the accompanying impurities such as quartz
(specific gravity of 2.6), pyrite (5.0), and slate (2.6 to 3.3)
will tend to "sink."  The overwhelming number of jigs in  this  country
are of the Baum type.  A more complete explanation of this important
piece of cleaning equipment is given later in this section.
     Although one of the oldest coal cleaning methods, the jig continues
to play a dominant role in the domestic preparation industry.   According
to Bureau of Mines data covering the 1964 to 1975 period, the  jig has
continued to be the major mechanical cleaning method in the United States.
During 1975, jigs put out over 124 million tons of clean  coal  which was
46.6% of the total clean coal produced for that year.  Following the jig,
magnetite heavy  media processes accounted for 27.1% of the total for that
year.  The third most utilized method is  concentrating tables which
contributed 10.7% of the clean coal in 1975.  The relative roles these
methods have played in prior years is summarized in Table  2-1.
                                   53

-------
                              TABLE 2-1
                 CLEAN COAL PRODUCED ANNUALLY BY
                MAJOR MECHANICAL CLEANING METHODS
                       (Thousand Short Tons)

Year

1975
1974
1973
1972
1971
1970
1969
1968
1967
1966
1965
1964
Total
Clean Coal
Produced
266,993
265,150
288,918
292,829
271,401
323,452
334,761
340,923
349,402
340,626
332,256
310,203
Percent Produced By -
Jigs

46.6%
48.8
45.9
44.5
42.5
43.4
46.3
46.6
46.2
46.0
45.6
47.0
Magnetite
Heavy Media
27.1%
25.9
25.8
25.3
25.9
23.7
21.4
20.7
18.9
*
*
*
Concentrating
Tables
10.7%
10.9
12.1
13.1
13.1
13.6
13.5
13.9
14.2
13.3
13.0
13.2
 *Magnetite Heavy  Media  Not  Reported  Separately from other Heavy Media
  processes.
 Source:  Based Upon  U.S.  Bureau  of Mines, Mineral  Industry Surveys,
         Coal-Bituminous  and Lignite  Annual,  1964-75, Prepared in
         Division  of Fuels Data  and Division  of Coal.
      Jigs are applicable to a wide range of coal  sizes.   In the  past,
 they  have  even been applied to  raw feeds having chunks as big as 10 inches.
 However, they are most practically used on top sizes of 3 to 6 inches.
 The major  limitations of the jig are that the amount of near gravity
 material should not exceed  10%  and they are  most efficient at high separating
 gravities  of  1.5 or more.   As a general rule, jigs can effect reasonably
 good  separations on  sizes down  to %  inch and produce limited results on coal
 sizes as small as 48 mesh.
     In the foregoing text and  for the balance of this section, reference is
made to the ability of a jig to effect a separation at a certain specific
                                      54

-------
gravity.  Although technically incorrect, one common simplification of
this subject is to think of the jig producing a clean coal  ("float")
having the same ash and sulfur content as that part of the  feed to the
jig which would float on a solution having that particular  specific
gravity.  In other words, if the specific gravity analysis  (float-sink
test) of the feed to the jig shows that the ash and sulfur  contents of
the float at 1.6 specific gravity are 10% and 1%, respectively, then the
jig is said to be effecting a separation at 1.6 if its product has
similar ash and sulfur contents.  This approach gives a very rough
approximation of the actual specific gravity of separation, since it
does not consider the amount of float 1.6 (misplaced product)  in the
sink 1.6 and vice versa.
     As stated above, jigging is a process to stratify a bed of particles
according to their density.  This is accomplished by alternate expansion
and compaction of the bed of particles in a pulsating fluid flow which
encourages the higher density particles to migrate toward the  bottom of
the  bed  and the lower density particles to move toward the upper portion
of the  bed .  This density stratification is accomplished  in  spite of
the great differences in size and shape of the particles.  To  better
understand the mechanics of this process, the reader is referred to the
cutaway views of a Baum jig presented in Figure 2-15.
     This particular jig is a five cell, two compartment model, produced
by the Jeffrey Manufacturing Division of Dresser Industries.  In the
front view, the inside of the first compartment is shown which consists of
two cells.  Although not visible in the drawing, the second compartment
has three cells which perform the same functions.  As the slurry of raw

                                   55

-------
          Air
           Chamber
Stratified
 Bed of Coal
 & Refuse
 Particles
                                                            Refuse
                                                             Elevator
                                                                Float
                                                            (Clean Coal)
Water
                                                                       Direction
                                                                        of Flow
                Side View
                                                        Front View
                              FIGURE 2-15

                       CUTAWAY VIEWS OF BAUM JIG



   feed  enters  the jig, water  is  forced  up  through the bed of coal and  ac-

   companying  refuse.  This  force is  sufficient to lift the bed and  "open it

   up"  in  suspension  in the  water.  Then, the external force pushing the water

   up through  the  bed  is  quickly  removed  and gravity creates the force  to pull

   the water back  through the  bed to  encourage the stratification of the parti-

   cles  in the  bed according to their density as discussed earlier.  Looking  at
                                     56

-------
 the side view of Figure 2-15 which  is  a  cross-section  of  any  of  the  five
 cells, one  can  get  a  feel  for how these  upward and downward currents
 of water are  created.   A blast of air  in the air chamber  forces water
 up  through  the  screen  plate  in that cell.  This action is referred to
 as  the pulsion  stroke  of the  jig.  As  this air pressure is quickly
 released, the water is  permitted to return to its natural  level just below
 the  screen  plate.   This action is referred to as the suction stroke
 since as  the  pressure  in the  air chamber is released, the water is some-
 what pulled back  through the  bed comparable to the action of a suction
 pump.  The  completion  of the  pulsion and suction strokes  is considered a
 cycle.   In  a  Baum jig,  the speed may be adjusted to the particular re-
 quirement but nominally each  cell operates around 22 cycles per minute.
 Although  the  cells  in  each compartment operate together,  they are se-
 quenced  with  the  cells  in  the other compartments to permit the build-up
 of  adequate pressure  before opening the valve into the air chamber.
     As  the bed of  particles  moves along the screen plate in each com-
 partment, the heavier  material will sink to the bottom of the bed.  At
 the  end  of  each compartment,  this bottom layer is drawn off as reject
 through a gate  and  then picked up in a bucket elevator having  perforated
 baskets for partial  dewatering.  The material  in the  upper layer  of the
 bed  passes  over ("floats")  to the next compartment where a further sep-
aration is  effected.  That material  which "floats" through all  jig com-
partments is  the product from the jig.   Depending upon the sophistication
of the particular cleaning  process,  the reject from the last compartment,
sometimes referred  to as middlings,  may be reclaimed  for further  treatment.
                                     57

-------
     Jigs are sized to the particular coal cleaning requirement on the
basis of tons of feed per hour per square foot of effective jigging area.
Specifically, this is the area of the screen plates over which the bed
moves.  This capacity is influenced by three factors relative to the
make-up of the feed.  In the following order, these are:
     1.  Percent of Near Gravity Material
     2.  Percent of Fine Material (% in.  X 0)
     3.  Refuse Volume
     The first two factors are especially critical  to the performance of
the jig.  When the near gravity material  is 10% or less, a relatively
"black and white" separation exists.  However, over 10% near-gravity
material presents a more difficult washing situation.  A very close
second to the percent of near-gravity material is the amount of fine
material in the feed as determined by screen analysis.   When the jig is
fed  more than one ton per hour per square foot of jigging area of 1/4 inch XO
material there is not as sharp a separation.  If this guideline on  fines
is observed and the percent of near gravity material is not over 10%, up
to 5 tons per hour per square foot of jigging area may be fed to a typical
Baum jig.  How these factors affect capacity can be observed in the
following example:
     Given:
          Raw Coal Feed:  400 tph of 5 in. x 0
          Near Gravity Material at Washing Gravity: 5-10%
          Percentage of  % in. x 0: 25%
          Refuse Volume:  Not sufficient to be a limiting factor
                                   58

-------
     Solution:
        Based upon near gravity material  percentage of 10% or less,  jig
        should be able to handle 5 tons per hour per square foot of
        jigging area or 80 square feet wodld be sufficient.   However,
        since 25% of the feed is 1/4 inch XO, or 100 tph,  100  square  feet
        of jigging area should be available to  meet the  1  ton  per hour
        per square foot test.
        Therefore, a jig having a minimum of 100 square  feet  of jigging
        area is sufficient to handle the  400 tph.
     Baum jigs are produced by a few major companies in  this  country and
come in a variety of standard sizes.  Some indication of the  larger
sizes available and their cost is given by the  following list of F.O.B.
factory prices of Jeffrey Manufacturing's Baum  jigs:
Width of
Screen Plate
6
7
7
Number of
Compartments
2
2
3
Number
of Cells
4
5
6
Jigging
Area
72 ft2
105 ft2
168 ft2
Nominal
Capacity
350 tph
500 tph
800 tph

Price*
$107-118,000
$125-140,000
$168-185,000
*Based upon mid-1977 price quotations.

For the purpose of estimating the installed price of a piece  of equipment
of this type, a number of between 2.5 and 3 times the F.O.B.  factory  price
gives a reasonable approximation.  In those coal  preparation  circuits
considered under Section 5.0 of this study, the above pricing/capacity
relationships'were observed.
                                     59

-------
Batac Jig -
     A modified form of the Baum type jig is the Batac jig which is manu-
factured in this country by the Roberts and Schaefer Company under
exclusive license from Humboldt Wedag in Germany.  Normally, the Batac
jig is intended for use in cleaning finer size coal having a top size
of around 3/4 inch.  These jigs come in various configurations depending
upon the feed rate, washability, density, and grading of the raw coal.
The length of the jig bed and its subdivision depends on the percentage
of heavy product or the number of separation cuts, whereas the feed rate
generally determines the bed width.
     The Batac jig is considered a hydropneumatic device which differs in
several ways from the conventional Baum jig.  A few of these differences
are:
     1.  Pulsations are produced directly beneath the bed screen
         (instead of in an adjacent chamber), in multiple chambers
         distributed uniformly throughout the jig.  Air pulses in
         each chamber are controlled independently.
     2.  Instead of moving a large volume of water, with its attendant
         slow-surge characteristics, the multiple chambers in the
         Batac jig each move a small volume of water, allowing rapid
         initial surge, and precisely controlled frequency and shape
         of the jig stroke.
     According to the manufacturer, the Batac jig can be designed with
wider beds thus providing significantly higher throughput in the same
                                   60

-------
space required by a conventional Baum jig.  This is possible because of
its improved operating efficiency and the elimination of the adjacent air
chamber.
     The general configuration of a Batac jig is presented in Figure 2-16
along with an identification of the major components.   Using this Figure
as a reference, the raw coal is introduced over the full width of the jig
bed as shown by point A.  Pulsations in the first two  cells separate the
coal and middlings from the coarse refuse, forming separate layers of these
materials.  The layer of heavy refuse is discharged at the end of the second
cell as shown by point B.  To ensure relative purity of the product leaving
the first two cells, bed depth is monitored constantly (point H), and
the opening of the discharge gate adjusted automatically to control bed
depth.
     Cells 3 and 4 utilize a feldspar bed to carry the coal, middlings and
fine refuse which pass over the bridge plate from cell 2.   Because the jig
bed screen in these two cells is large (16 mm), as the feldspar bed lifts
and separates in response to water surges, the fine refuse sifts down
through the bed and screen  (point D).  By the time the incoming product
reaches the end of cell 4, only coal and middlings remain, and these pass
over a bridge into cell 5.
     Cell  5 operates much the same as cell 2, with the coarser middlings
serving as the jig bed, and being discharged through a controlled-size
gate at the end of the  cell  (point E). Finer middlings, together with coarse
and fine  clean  coal pass over another bridge into cell 6.  In cell 6, with
its feldspar bed, fine middlings are discharged through the bed and screen
(point  F),  leaving clean coal to  flow out of the jig  (point  I)  onto  dewatering
equipment.
                                  61

-------
        End View
                                          Side  View
Major Components -  A.
                    C,
                    D.
                    E.
Raw coal inlet
Coarse refuse discharge
Refuse Collecting hopper
Fine refuse discharge
Coarse middling product
 discharge
Fine middling product
 discharge
Middling product
 collecting hopper
Bed depth sensors
I. Clean, washed coal outlet
J. Air chambers
K. Water inlets
L. Air distributing pipes
M. Air distribution chamber
N. Exhaust air collecting chamber
0. Exhaust air pipes
P. Valve control
                                     Figure 2-16

                               CUTAWAY VIEWS OF BATAC JIG


             The air inlet and outlet valves for the surge chambers(point J) under

        Z'.Y^ oatac jig are operated by air cylinders and quick air releases to get

        the necessary rapid actuation. Air cylinders, in turn, are actuated by

        solenoid-controlled air valves (point P).  Sequencing of these valves, and
                                           62

-------
the air releases is controlled by solid-state electronic circuitry mounted
on removable panels in the master control panel. Panels are "programmed"
for the particular material being handled, so that only a substitution
of these panels is ordinarily required to modify operation of the jig
for differing materials.
     Based upon a high volatile 3/4 X 0 raw coal having 15% to 20%
28 mesh X 0 material, the following capacities, requirements, and costs
are presented as a function of the three standard Batac jig widths.
 Bed     Maximum   Jigging   Water   Jigging  Approximate  Approximate F.O.B.
Width   Feed Rate    Area    Supply    Air      Total      Factory Price 3]
 in        TPH     Sq Meters GPM 1]   CFM 2]   Horsepower   1st Qtr. 1977
Meters
3
4
5
360
480
600
18
24
30
3,600
4,800
6,000
2,800
3,800
4,800
275
330
340
$560,000
$585,000
$610,000
1]  At 11.4 psig pressure measured at the inlet header for raw coal feeds
    containing not more than 35% refuse material.
2]  At 6.4 psig measured at the jigging air distribution chamber.
3]  Includes the Batac, Jigging Air Supply Blower, Control Air Compressor,
    and Refuse and Middlings dis-posal elevators.
The maximum feed rates will be less as the top size is reduced and/or the
percentage of minus 28 mesh material  in the feed increases.
    Under Section 5.0 of this report, a preparation plant (Example 4) is
considered which includes two Batac jigs  in its fine cleaning circuit.
                                    63

-------
2.2.4 Heavy Media Vessels
     As the name implies, heavy media vessels effect a separation of coal
from the accompanying refuse by creating a medium having a specific gravity
equivalent to the desired specific gravity of separation.  This establishes
an environment which encourages the coal to float and the heavier refuse
to sink in a manner which closely simulates that predicted by specific
gravity (float-sink) analysis.  As mentioned earlier, heavy media vessels
can perform a relatively sharp separation by accurately controlling the
amount of magnetite in the solution.  Normally, vessels of this type
are used on coarser size fractions down to % inch.  Although more expen-
sive to install and maintain than a Baum jig of comparable capacity,
heavy media vessels can show economic advantage with coals having
a  large percentage of near gravity material necessitating a sharper degree
of separation.  The initial cost of this category of equipment is higher
since in addition to the vessel itself, it is necessary to have adequate
circuitry to recover for reuse the expensive heavy media (magnetite).
This not only includes magnetic separators and the associated pumping,
piping, etc., but also the equipment used to monitor and maintain the
proper density of magnetite in the vessel's circulating  medium.   Operating
costs are also higher than comparable capacity Baum jig  cleaning circuits
due to the cost of the magnetite lost in the washing process  in  addition
to the greater amount of equipment requiring power and periodic  maintenance.
     Heavy media vessels are manufactured by several  companies in this
country and come in a variety of sizes and configurations.   The  major
differences in these equipments relate to the methods used for introducing
the raw feed into the washer as well  as recovering and discharging the  float
                                      64

-------
and sink products.   Large  scale washers  can  handle  raw  feeds  approaching
800 tons per hour.   One  such  larger  unit is  the  Daniels Precision  Washer.
This has a trough type design utilizing a transverse  flow where the
feed to the vessel and the discharge of the product are transverse to
the direction of the flight conveyor which collects and rejects the
refuse.  Another unique feature of this equipment is the submergence
baffle which immediately forces the feed to the vessel under the sur-
face of the medium (water and magnetite) where the actual  separation
occurs.  As the float material rises to the surface it overflows the
side of the tank.  Figure 2-17 is a top view of this equipment clearly
showing the rectangular conveyor which collects the refuse off the
bottom of the tank and discharges it at the far end of the vessel.
     As would be expected, the cost of heavy media vessels varies with
capacity.  However, the price is most sensitive to the particular style.
For example, a drum type separator manufactured by the WEMCO Division
of Envirotech Corporation which is capable of handling a feed of 500 tons
per hour (tph) costs $125,000.  A 500 tph capacity Barvoy heavy media
vessel manufactured by the Roberts and Schaefer Company costs less than
$50,000 as of mid-1977.  Obviously, each of these units has its own
unique features which make it more or less advantageous under varying
coal preparation requirements and conditions.  The point to be made
here is that there is no single price per ton of capacity appropriate
for estimating the cost of this particular category of cleaning equip-
ment.   This being the case, the prices used for approximating the capital
cost of the heavy media vessels appearing in the preparation plants con-
sidered under Section 5.0 of this study were based on specific quotes.
                                  65

-------
            Refuse Flight
              Conveyor
en
CTv
                                                    FIGURE 2-17

                                        DANIELS HEAVY MEDIA PRECISION WASHER
                                                                                                              Refuse Reject
                                                                                                                End of
                                                                                                                Vessel
                                                                                                              Washed Coal
                                                                                                                 (Float)
                                                                                                                 Overflow


-------
2.2.5 Cyclones


     Essentially, the cyclone is a hydraulic centrifuge working on the


vortex principle.  The slurry of coal may be pumped or fed by gravity

to this device.  When properly applied, this versatile piece of equip-


ment can be an efficient part of the coal preparation plant.  Cyclones


provide a wide range of functions in a variety of coal preparation


circuits.  These functions fall  into three major categories:


     1)  Size Separation - Performed by the classifying cyclone.


     2)  Dewatering - Performed by the thickening cyclone.


     3)  Separation of Refuse from Coal - Performed by either a heavy


              media or water-only (hydro) cyclone.

     The size and number of cyclones in any given preparation circuit


will vary with the specific application.  The size of a cyclone is de-


termined by the physical and chemical nature of the coal  slurry to be


processed as well as its volume and desired performance.   This perform-


ance is influenced by such factors as:


     1)  Solids concentration of the feed.


     2)  Size distribution and specific gravity of the solids.


     3)  Desired classification size.


     4)  Required concentration of underflow and dilution of


              overflow.


     Depending upon the application, cyclones come in a range of sizes
                   i*'.

and shapes up to 30 inches in diameter.  The initial cost of any given


type and size cyclone will vary significantly based upon the selection


of the lining.  These replaceable linings are selected on the basis of
                                   67

-------
their wear resistant qualities.  A. proper selection of lining to
meet the conditions of corrosion and abrasion can aid in reducing
maintenance costs.  Liners of urethane, ceramic, rubber, Nihard,
and other materials are offered by such cyclone manufacturers as
Heyl & Patterson and Krebs Engineers.  For more abrasive applications
all ceramic lining is appropriate.  Where less abrasive coal  slurry
is being fed to the cyclone, a combination of urethane and ceramic
lining may be all that is necessary.  This concept of using a combina-
tion of linings cost-effectively addresses the specifics of the wear
factors actually being experienced in various portions of the cyclone.
As an example, urethane may be employed to line the upper portions of
the cyclone where less wear is experienced, while the extreme abrasion
resistance of ceramic is most .appropriate in the lower portions.  The
use of combination linings is made possible by a sectionalized construc-
tion where the metal housings are fitted with replaceable linings.
This sectionalized approach not only permits an effective matching of
lining material to subjected abrasion, but also yields cost savings by
eliminating the need to replace the entire lining when only a portion
is worn.
     When cyclones with expensive wear resistant liners were first in-
troduced, there was a reluctance on the part of industry to adopt them
due to high initial cost.  This cost can be as much as twice that
of a comparable capacity unit.  However, over the past eight years,
their proven record of reducing long term maintenance costs has brought
about acceptance.  As a result, the major cyclone manufacturers are
                              68

-------
now employing this concept of using better grade linings and combinations
thereof in spite of their initial higher cost.
     Even though significant advances have been made in the construction
and application of cyclones used by the coal cleaning industry, it is
difficult to get accurate maintenance cost data.  Such costs are greatly
influenced by the manner in which other portions of the plant are main-
tained.  Specifically, if proper care is taken of the equipment "up-
stream" from the cyclones, then the feed is consistent with the design
and lining.  However, improper care such as when screens are not properly
maintained, can result in a much coarser feed entering the cyclone and
rapidly accelerating wear on the lining.
Heavy Media Cyclones -
     Heavy media cyclones can perform an effective and efficient cleaning
of  intermediate size coals.   In  these cases where there are  large amounts
of near gravity material  and/or the desired specific gravity of separation
is low, these devices play critical roles.   These devices  provide a  degree
of operational  flexibility in that you  may readily vary the specific gravity
of separation over a wide range.   As the name implies,  the separation
achieved by these devices is principally controlled  by  the specific  gravity
of the medium which in practice ranges  between 1.35  to  1.80.   In almost
all  cases this  medium is  a suspension of magnetite and  water.  The feed
to this type of cyclone may be pumped or gravity fed.   Although a heavy
media cyclone is normally mounted in the inclined position as shown  in
Figure 2-18, it is capable of operating  in the upright  position as well.
(The particular heavy media cyclone shown in Figure  2-18 is manufactured
by Heyl  & Patterson, Inc.).
                                 69

-------
                            FIGURE 2-18
              HEAVY MEDIA CYCLONE IN INCLINED POSITION
     To better understand the workings of heavy media cyclones, the reader
is referred to Figure 2-19, which is a cutaway view of a washing cyclone.
A slurry of water, coal, refuse, and magnetite is fed tangentially into
the conically shaped body of the cyclone.  As this slurry is carried around
the feed chamber, specific gravity differentials are set up which vary from
the air core to the cone wall and from the bottom of the vortex finder to
the apex of the cone.  These differentials create an environment which en-
courages the lighter particles in the slurry to move toward the core.
Conversely, the heavy materials are encouraged to stay against the cone
wall, or if caught in the central low gravity section of the cone near
                                    70

-------
       FEED INLET
      FEED CHAMBER
          CONE WALL
                                                       OVERFLOW
                                               OVERFLOW ORFICE
                                                 (VORTEX FINDER)
                                               AIR CORE
                                               APEX OF CONE
                                               UNDERFLOW ORFICE
                               FIGURE 2-19

                CUTAWAY VIEW OF OPERATING CYCLONE

the air core to quickly sink away toward the wall.   These  specific

gravity differences and centrifugal  effects within  the rotating  mass

of magnetite, water, and solids are  responsible for a relatively sharp

separation of coal  and refuse.   Heavy media cyclones come  in  a  variety

of sizes up to thirty inches in diameter and several types of linings

are available with  varying degrees of wear resistance.  There are slight

design variances among manufacturers, each claiming superior  performance

characteristics.
                                   71

-------
  Water-Only Cyclones -
       Commonly referred to as hydrocyclones, water-only cyclones
  are gravimetric separators used to sort particles of coal and accompany-
  ing refuse according to specific gravity using only water and centri-
  fugal force.  Although it may be applied as an independent cleaning
  unit, this type of cyclone is a particularly valuable processing tool
  when used in multiple stages or in conjunction with other washing
   equipment.   As  shown  in  Figure  2-20, which  is a  bank of  Heyl and
   Patterson hydrocyclones, this type of cyclone has a cylindrically
   shaped  body  with  a conical bottom.  It differs from the  typical heavy
                      FEED
                                                  OVERFLOW
MANIFOLD
                                                                UNDERFLOW
                          FIGURE 2-20
                 WATER-ONLY  CYCLONE  INSTALLATION
                                       72

-------
media washing cyclone in that it  is short and stubby as opposed to a
long tapered conical appearance.  Additionally, the water-only cyclone
has an adjustable vortex finder which is longer and also has larger
overflow openings for a given diameter than other type cyclones.  There
are other design variations depending upon the manufacturer.
      From an operational standpoint, the raw feed enters the cyclone
tangential to the feed chamber where separation occurs.  As in the
case of the heavy media cyclone,  the lighter particles report up
through the vortex finder and exit through the larger overflow opening
at the top of the cyclone.  The heavier particles (refuse) exit through
the opening in the center (apex)  at the bottom of the cyclone.  The
diameter of a water-only cyclone  is principally selected on the basis
of the size of the coal and the efficiency required.  In general, the
smaller the particle size, the smaller will be the required diameter.
For intermediate size coal, diameters of between 12 and 30 inches are
selected as appropriate.  Finer sizes are handled by units of 8 to 14
inches in diameter.  One popular  application is to use 12 or 14 inch
hydrocyclones on the 28 x 100 mesh size fraction in combination with froth
flotation because of their abililty to remove pyrite particles and the
difficulty in floating this size.
     Other design features which  influence performance include:  1) verti-
cal clearance between lower edge  of the vortex finder and the cyclone
bottom; 2) diameter of the vortex finder; 3)apex diameter; 4) solids
concentration in the feed to the  cyclone; and 5) pressure at the feed
inlet.  The particular specific gravity at which the water-only cyclone
                                   73

-------
effects a separation is determined by varying the dimensions of the
discharge orifices.   This specific gravity of separation is decreased
as the diameter of the vortex finder is decreased or the apex diameter
is increased.  As would be expected, this same result occurs as the
vertical clearance between the lower edge of the vortex finder and the
cyclone bottom is increased.   This latter type of adjustment is made
simpler and more precise by water-only cyclones with hydraulic vortex
finder lift mechanisms.
     Also affecting the operating specific gravity of separation is the
solids concentration.  This concentration is directly scaled to the hydro-
cyclone diameter; the smaller the diameter, the lower the percent solids.
Normally, this concentration is between 8% and 15% by weight.  As the
concentration is increased, the specific gravity of separation also in-
creases.  This is a critical  operating parameter since if feed concentra-
tions are too high or low, undesirable results occur.  Specifically, too
high a percentage of solids results in increased particle interaction
and thus less accurate separation of coal and refuse.  At the other end,
too low a percentage of solids will also injure performance because the
hydrocyclone will begin to separate on the basis of particle size like
a classifying cyclone resulting in excessive amounts of misplaced coal.
     As long as there is adequate feed pressure to generate a vortex,
changing the inlet pressure apparently has little impact on the perform-
ance of the water-only cyclone.  By increasing the pressure, there will
be a slight elevation in the specific gravity of separation as well as the
                                    74

-------
processing capacity.  However, it is not recommended as an economical
means to achieve this latter objective since such increased pressure
accelerates wear on the cyclone lining.  As a general rule, the follow-
ing minimum inlet pressure relations apply:
Cyclone
Diameter
8
10
12
15
20
24
26
Maximum
Feed Size
28 mesh
10 mesh
% inch
% inch
h inch
3/4 inch
3/4 inch
Dry Feed
Rate
3-5 tph
4-8 tph
8-16 tph
15-25 tph
25-45 tph
40-70 tph
50-90 tph
Inlet
Pressure
8 psi
10 psi
12 psi
12 psi
15 psi
15 psi
15 psi
Maximum
% Solids
8-10
10
10-15
12
15
15
20
     According to an article by Ellis J. O'Brien of Dravo which appeared
 in the January 1976 issue of Coal Age, the pros and cons of water-only
 cyclones are summarized as follows:
     Advantages
     1. Simple design with no moving parts and little maintenance.
     2. Once initial adjustments have been made, usually no further
        adjustments are necessary.
     3. Operate with water only and without a heavy medium or reagent;
        therefore, heavy-media or reagent consumption is eliminated
        and no magnetite recovery system is needed.
     4. Requires limited space for operations
     5. Does not require pre-screening.
     6. Will clean oxidized raw coal down to 100 mesh while flotation will
        not.
                                    75

-------
          7.  Will  reduce pyritic sulfur more effectively from 28 mesh x 0
             coal  than flotation.
     Disadvantages
          1.  Large quantities of water are required for proper operation
             of the hydrocyclone circuit,  therefore more horsepower.
          2.  Separations obtained in a hydrocyclone aren't nearly as
             sharp as those characteristic of the dense-media cyclone
             or Deister table.
          3.  Not for difficult-to-clean coals.
          4.  Good refuse and a clean coal  cannot be produced simultan-
             eously from a single unit.
     The prices of all types of cyclones vary with size, lining, and
unique design features mostly influenced by the particular manufacturer.
Since there is a multitude of size/lining/manufacturer combinations,  it
was necessary to obtain specific price quotations on those cyclones in
the preparation plants addressed under Section 5.0.  However, as a
general rule for estimating the installed price of the cyclone portion
of the coal preparation circuit, a figure of between 2 and 3 times the
FOB factory price gives a reasonable approximation including necessary
piping and manifolding.  In the case of all ceramic linings the lower
multiplier would apply and for the same cyclone having a less expensive
lining, the higher figure would be appropriate.  For heavy media cyclone
installations, there will be the additional cost of the media control  and
recovery circuitry which adds appreciably to the total installed price.
                                   76

-------
2.2.6 Concentrating Tables
     Commonly referred to just as "tables" or as Deister tables (the
name of the principal domestic manufacturer), the concentrating table
has a proven record of efficiently cleaning certain coals in a size
range of 3/4 inch to zero.  Tables cannot be adjusted to provide separa-
tions lower than 1.45 to 1.50 specific gravity.  Like jigs, their separa-
tion efficiency is adversely affected when more than 10% near gravity
material is present.
     The concentrating table effects a separation of coal from the ac-
companying refuse according to size and specific gravity by flowing
a mixture of coal and water over a vibrating table having a series of
riffles.  Basically, the table consists of a pair of steel  channels
upon which is mounted a rubber-covered deck and a drive mechanism.  The
flat, rhomboid-shaped deck is approximately 17 feet long on the clean-
coal side and 8 feet long on the refuse side.  It is supported in an
essentially horizontal plane, but slopes enough (perpendicular to the
motion of the deck) so that water fed along the upper long side will
flow across the table surface and discharge along the lower clean-coal
side.  The deck is attached to a differential motion drive which gives
it a quick return conveying motion, moving material lying on the table
surface away from the drive end.
     Attached to the rubber covering on the deck is a system of rubber
riffles tapering toward the refuse end of the table and parallel to the
direction of the conveying motion as shown in Figure 2-21.   Standard body
riffles are approximately % inch high at the drive end of the table.
                                    77

-------
       Feed
        Box
Dressing
 Water
 Boxes
                                                                 Ri ff1es
    Table
    Dri ve
                                                                    €
                           Clean Coal  Side
                                                   €
             Clean Coal
             Middlings
       Q    Refuse
                               FIGURE 2-21
           TOP VIEW OF CONCENTRATING TABLE WITH DISTRIBUTION
                          OF PRODUCTS BY SIZE


Between each set of three or four body riffles are high (over 1  inch at
the drive end) "pool" riffles.   These riffles form dams., behind  which
stratification of the bed occurs.  Low-density particles ride over the
riffles, reporting to the clean-coal  side of the table; high-density
particles are carried behind the riffles by the differential-motion drive
to the refuse end of the table.  At one corner of the long diagonal and
above the deck is a feedbox with a slotted bottom to spread the feed onto
                                    78

-------
the deck.  Beside the feedbox and along that side of the deck is a
trough, having adjustable gates through which the flow of dressing
water is distributed to the deck.
     Because of the reciprocating action of the table and the transverse
flow of water, the feed fans out immediately upon contacting the table
surface.  The upward slope of the table toward the refuse end, usually
1/8 to % inch per foot, and the retaining effect of the pool riffles
cause the slurry to form a pool near the feedbox.  In this pool, the
bed of material is several particles deep and substantially above the
standard riffles.  This area becomes the zone of primary stratification.
In this  zone, the shaking motion of the deck combined with the cross
current of  water  stratifies  the  particles  by density, similar to the
action  of the jig washer  described  in  Section 2.2.3.
      The essence  of  table performance  is the stratification according
to size and specific  gravity  that occurs behind  the riffles.  This
results from the  differential  shaking  action of  the deck.  The particles
that  make up the  feed  become  arranged  so that the finer and heavier
 (more dense) particles  are at  the bottom and the coarser and lighter
 (less dense) particles  are at  the top.  The finer, more dense particles
are carried out by the  table movement  toward the refuse side at a faster
rate  than the coarser,  more dense particles.  The larger pieces of lower
specific gravity  ride on  the  top layer of  particles and flow on down the
slope of the deck reporting to the  clean coal side.  Such movement is en-
couraged by the cross flow of wash water at right angles to the shaking
movement of the table.  Since  stratification and separation of particles
are not complete as a result of any one riffle, a series of riffles is
                                     79

-------
used, repeating the cycle of stratification and hindered settling from
riffle to riffle, obtaining purer refuse products as the particles spread
out and progress forward and downward over the table.  Conversely, the
purer, cleaner coal is discharged at the drive side of the table.
     As presented  in  Figure 2-21, successive samples collected along the
clean and refuse sides of the table, starting at the drive motor side,
show a steady increase in ash content and a steady decrease in the average
particle size for each individual specific gravity fraction.
     Concentrating tables are provided with a number of adjustments which
are used to obtain the best possible operation.  Among these  are:  (1) reci'
procating speed, (2) length of stroke, (3) feed rate, (4) amount and
distribution of wash water, (5) water-to-sol ids ratio of the  feed pulp,
(6) uniformity of feed,  (7) riffle design, (8) side tilt and  (9) end
elevation.  The reciprocation of the deck usually is 260 to 290  strokes
per minute depending on  the characteristics of the raw coal and  the feed
rate.  If there are high percentages of refuse in the raw coal or if
the feed rate is high, an increase in the frequency is required.
     Closely related to  the frequency is the amplitude.  The amplitude
and frequency are varied to maintain the mobility of the bed necessary
for stratification while retaining the coal on the deck long  enough
for proper separation.   In order to move large quantities of refuse
material along the deck, an amplitude as long  as 1% inches may be re-
quired.  Conversely,  the stroke may be less than % inch  long when coals
containing high percentages of near-gravity material are washed.  The
amplitude and frequency  of the stroke are decreased as the amount of
                                     80

-------
near-gravity material in the feed increases.  A nominal 3/8 inch x
0 feed would require a stroke amplitude of about 3/4 inch and frequency
of 275 strokes per minute.  Generally, a fine feed will require a higher
speed and shorter stroke than a coarse feed.
     The cross slope and amount and distribution of dressing water to
the table can be changed easily and quickly to compensate for minor
variations in feed rate and composition.  The cross slope is generally
less than 5 degrees, and the dressing water side of the table is higher
than the clean-coal side.  The feed dilution (water to solids ratio)
used on a table washing 3/8 inch x 0 is 2 to 1.   As the top size of
the feed increases the water to solids ratio increases.
     Perhaps the most important of all table adjustments is the end
elevation or the amount of upward inclination of the deck measured
along the line of motion from the feed end to the discharge end.  By
creating a moderate slope which the high specific gravity particles will
climb more readily than will the low specific gravity material, the sep-
aration is greatly improved.  The high specific  gravity particles are
forced to spread out in a thin, wide band which  permits a much sharper
separation to be made between clean coal, middling, and refuse products.
The amount of end elevation increases with feed  size and specific gravity.
Typically, a 3/8 inch X  0 feed would require approximately 3 to 4 inches
of end elevation depending upon the specific gravity of the refuse.
     The capacity of a concentrating table is a  function of the size
consist, the percentage of reject, and the washability of the feed.
                                   81

-------
As a general rule, capacity increases directly with the size consist,
limited by the percentage of reject above 20%.  However, as the diffi-
culty of cleaning decreases, feed rates can be increased.  The
majority of all installations treating bituminous coal are handling
the 3/8 in. x  0 or % in. x 0 size fractions.  Most of the tables installed
in recent years have a double-deck configuration.
     The two major double-deck design configurations manufactured by
the Deister Concentrator Company are the regular Concenco "88" Diagonal -
Deck Coal Washing Table and the High Capacity Refuse Discharge (HCRD)
version of  the same.  This latter configuration is designed for washing
coals containing more than 20% reject.  As depicted by Figure 2-22, the
"88" series tables are built for suspension mounting via wire
ropes in vertical pairs or in a four-deck stack arrangement.  This arrange-
                               Figure  2-22
        DOUBLE-DECK CONCENTRATING TABLE (DEISTER CONCENCO "88")
                                  82

-------
merit eliminates to a large extent two of the major disadvantages of con-
centrating tables.  Specifically, it reduces the floor space requirements
and the need for shock absorptive mounting to handle the impact of the
drive mechanisms.  As a  general  rule, each twin-deck is capable of
efficiently washing up to 25  tons per hour (tph) of % x 0 or 30 tph of
3/4 x 0 feed containing  less  than 20% reject.  The FOB factory price as
of mid-1977 for the standard  model  twin-deck table was $18,326.  The
HCRD model  is  approximately  $2,000  more per double-deck.  Both prices
include the necessary drive  motor,  mounting hardware, controls, and
up  to  six days field  service  for start-up and demonstrating the satis-
factory performance of the tables.   In addition to the basic price of the
tables, there  is  an additional  hardware expense associated with the feed
distributors.   These  devices  divide the stream of slurry into prede-
termined amounts consistent with the capacity  of the  table.   The  primary
importance of feed distributors is to assure  uniform  feed to all  deck
surfaces so that common  table settings will  provide consistent separating
results.   They come in stationary or revolving configuration.,  which are
selected on the basis  of capacity and the  required number of splits.   As
an indication of their cost,  a stationary  8-way distributor sells  for
$2,500 and a comparable  capacity revolving type has an  F.O.B.  factory
price of $6,500.   These  prices were used for approximating the capital
cost of those preparation plants considered under Section 5.0 where tables
were part of the cleaning circuit.
                                   83

-------
2.1.1 Froth Flotation
     As mentioned at the beginning of this section, froth flotation relies
upon the surface chemistry of coal to effect a separation of coal from
its accompanying refuse. This is the major process capable of cleaning
particle sizes down to zero.  To achieve this separation, frothing and
conditioning reagents are added to a slurry of water and fine feed (coal
and refuse particles).  Then, as air is bubbled up through the slurry,
the coal particles attach themselves to the bubbles and are carried to
the surface where they can be collected as a concentrated overflow product.
The refuse particles remain below the surface and are discharged at the
underflow opening at the bottom of the vessel.
     As shown in Figure 2-23, the froth flotation process is performed in
large  steel tanks having a series of compartments or cells.  This picture
clearly shows the coal  laden froth floating at the top of each cell and the
skimmers which  remove this product.  Each cell has its own agitating device
at the bottom of the tank to keep the slurry in suspension and distribute
the air bubbles.  These agitating devices vary substantially among the
several domestic manufacturers  which include the  Daniels  Company,  Denver
Equipment  Divison of Joy, Heyl  &  Patterson, and WEMCO  Division of  Enviro-
tech.  A slurry of  coal, frother, conditioners, and water  is fed into one  end
of the series or bank of cells.   The solids concentration  of this  slurry will
vary between 4% and 12%.  A series of several cells is necessary  in order
to assure adequate  time for the coal to come in contact with the air bubbles.
The slurry moves from one cell  to the other during which  time that coal which
            c
has been floated to the surface overflows the edge of  the  cell as  a concen-
trate  of about  25%  solids.  This  concentrate is normally  routed  to a vacuum
                                   84

-------
                          Figure 2-23



                FROTH FLOTATION CELLS IN OPERATION









filter or other dewatering device before going to a thermal dryer for final



moisture reduction.  The non-coal particles also move from cell to cell but



below the surface until they reach the far end of the tank. Here they are re-



jected through a discharge box or similar mechanism with the bulk of the



vessels' fluid.   In most of the preparation plants today, this high
                                  85

-------
moisture reject product is routed to the static thickener where the
solids are settled out prior to ultimate disposal.
     In the froth flotation process, one of the significant expenses is
the necessary additives which are essential to performance.  These re-
agents fall into three groups which are: 1) frothers; 2) collectors or
promoters; and 3) modifying agents.  As the name implies, the frother
or frothing agent makes possible the creation of a stable froth which
will last long enough to support coal particles on the surface and hold
them there until they are removed.  MIBC (Methyl Isobutyl Carbinol) is
the most common frother used today.  Since these frothing agents are not
recoverable, they must be carefully selected not only on the basis of
their effectiveness with the particular coal but also their price. Also,
as their name implies, the collectors or promoters perform the function
of promoting contact between the coal particles and the air bubbles by
selectively forming a thin coating over only the coal particles to make
them water repellent.  The most common substances used as collectors are
fuel oil and keorsene.  There are some newer reagents which have both
frothing and collecting properties, thereby reducing the number of additives.
     The final group of additives, the modifying reagents, perform a
variety of functions as appropriate to the particular coal being treated.
Within this classification are: depressing agents, activating agents, and
pH regulators.  Depressing agents are used to inhibit the flotation of
non-coal particles by coating them so they will not adhere to the air
bubbles picking up the coal.  Substances used for this purpose include
sodium and potassium cyanides which have proved effective on iron sulfide
                                  86

-------
(pyrite) particles.  Activating agents alter the surface chemistry of the
coal so that it more readily responds to the filming action of the collector
reagent.  The pH regulator controls the degree of acidity or basicity of
the flotation slurry.  Establishing the proper pH level  is a critical
operating parameter which greatly influences the performance of the flota-
tion process.  When the pH is between 6 and 7.5, recovery of most coals is
highest.  As a general  rule, the ash content of the froth increases with
the pH, and the pyritic sulfur content goes down.
      The price of froth flotation installations will  vary with the size
 and number of cells as well as the manufacturer.  Since each set or
 bank of cells has only one feed box where the slurry  enters and one
 discharge chamber through which the refuse is rejected, there is not
 a simple per cell price for a given capacity installation.   Therefore,
 it is necessary to price out the particular configuration.   For ex-
 ample, one manufacturer offers a bank of three flotation cells, each
 having a volume of 300 cubic feet (nominally 15-20 tph  of feed per cell)
 for $34,000 and a bank of four for $38,000.  This latter configuration
 is  offered  by another firm for $35,000.  Although the  300 cubic feet
 capacity cell seems to be the most popular, smaller cells of 100 cubic
 feet each and larger ones at 500 cubic feet are also  used for treating
 bituminous coal.  A four cell installation of 100 cubic feet per cell
 sells for $28,000 and  the 500 cubic feet version sells  for $45,000.
                                    87

-------
One manufacturer currently has a cell with 1000 cubic feet which is
supposedly capable of handling up to 40 tons per hour of feed at a
solids concentration of between 5% and 10%.  These larger capacity
cells have not been required to any great extent in the past since
only a small percentage of the preparation plant feed normally is
processed to this extent.  However, as more larger fine coal plants
are put into operation, there will be an increase in demand.
     These mid-1977 F.O.B. factory prices were used to approximate
the capital cost of the froth flotation portions of the coal prepara-
       4>
tion plants considered in Section 5.0.  These prices are only the
"tip of the iceberg" for a fully installed flotation system.  This is
because there are extensive pumping and piping requirements which
add appreciably to the cost as well as the system for controlling
the flow  of necessary chemical additives.  As a general rule, the
total installed price will be slightly over three times the basic
equipment cost.
                                   88

-------
2.3 Other Equipment and Facilities
     Besides those major pieces of coal handling and storage equipment
described in Section 2.1 and the cleaning equipment covered in the
preceding section, there are other principal components of the modern
coal preparation complex.  Although a limited number of these facilities
and equipment are located within the preparation plant, the majority
are separate structures.  Many of these other items play a critical role
in the overall performance of the plant.  These functions include de-
watering of the clean coal and refuse products, water clarification, and
accurate sampling of the clean coal at the end of the preparation
process prior to shipment.  In the following sub-sections, brief
 descriptions  of these other items are  presented along with their cost as
a function of size and sophistication.
     2.3.1 Dewatering Equipment
          As covered previously, most physical coal preparation techniques
employed today involve wet cleaning processes.  During these processes,
the clean coal and refuse products created pick up substantial moisture
which must normally be reduced to some extent.  In the case of the clean
coal, the amount of dewatering required is a function of the purchase
specification as well as the economic and practical realities.of trans-
porting and handling a high moisture commodity.  Dewatering of refuse
is a less defined issue since the preparation plant operator need only
reduce the moisture content to the point where the material can be
properly disposed.  Since fine solids have a larger surface area per
                                     89

-------
unit weight than coarser size fractions, they retain relatively more
water and therefore necessitate the availability  of greater dewatering
capacity at the preparation plant.  Depending upon the amount of finer
coal and refuse generated by the particular process, the dewatering
function can constitute a significant portion of  the capital and opera-
ting cost of a plant.  There are several forms of dewatering equipment
which are applied as appropriate to the size consist of the material
and the required final moisture content.  These are categorized as
centrifugal, vacuum filter, and thermal.  Brief descriptions of these
equipments and their cost is presented in the balance of this sub-
section.
     2.3.1.1  Centrifugal Dewatering Equipment
          As would be expected, this category of  dewatering equipment
performs its moisture reducing function by subjecting the wet material
(coal o.r refuse) to centrifugal forces sufficient to drive out as much
of  the  unwanted water as possible.  The design objective of these
machines is not only to reduce the moisture content of the feed but also
to  maximize its recovery with minimum degradation.  Centrifugal  dewatering
equipment  is offered  in a range of sizes and configurations by a number
of  domestic manufacturers each having their own unique design features.
However, the majority of this equipment can be categorized by the follow-
ing types:
     1. Vibrating Screen Basket (Horizontal and Vertical Types)
     2. Scroll-Type
     3. Screen Bowl Type
     4. Solid Bowl Type
                                   90

-------
      (1) Vibrating  Screen Basket Type

          Vibratory  screen basket type centrifugal  dryers are offered

  by several firms  in  horizontal and vertical  designs.    Figure  2-24  shows

  one such unit of  the horizontal type manufactured by the WEMCO Division

  at Envirotech.  As depicted by the cross-sectional  view of the centrifuge
                                            BELLEVILLE    ECCENTRIC WEIGHT  SCREEN BASKET  FEED
                                             WASHER
                                                 RUBBER BUFFER      BACK PLATE ; FEED PIPE
                                               BUFFER PLATE

                                               SHEAVE
                                            BEARING
                                                    RUBBER
                                                    MOUNT
                                             BUFFER PLATE
                                                            MAIN SHAFT
       Effluent
      Discharge
Dewatered
Solids are
Discharged
Through Opening  in  Base
                                              MECHANISM HOUSING      BUFFER RING  DISCHARGE HOUSING


                                                       CENTRIFUGE MECHANISM
                              FIGURE 2-24

VIBRATING SCREEN BASKET CENTRIFUGAL DRYER-HORIZONTAL  TYPE (WEMCO MODEL 1100)

  mechanism, the material  to be dewatered enters  the  small  end of the re-

  volving cone-shaped  screen basket.  The free  moisture accompanying this

  material passes  through  the screen and the  solids move outward along the

  surface of this  cone-shaped screen until  they are discharged over the
                                       91

-------
edge of the basket.  The vibratory action of this revolving basket,
aids the dewatering process by breaking up the capillary cavities in
the material.  According to the manufacturer's data, this unit is capable
of reducing the surface moisture of finer size coal from 30-35% to 8-9%
and from 6-10% to 3% on coarser size fractions with product recoveries
of 97% or better.  In terms of capacity, the smaller version of this
centrifuge (Model 1100) is capable of dewatering up to 200 tons per
hour (tph) of Ik X % inch feed or 120 tph of 3/8 inch X 28 mesh.   The
larger model (Model 1300) can handle nearly 300 tph of 1% X % inch or
180 tph of 3/8 inch X 28 mesh.  These units, which are not recommended
for material less than 28 mesh, sell for $26,000 to $30,000 F.O.B. factory.
     A horizontal type is also available from the Bird Machine Co. (Models
1150 and 1300).  Depending upon the consistency of the feed, these units
are capable of handling throughputs of up to 275 tph.  These units sell
for approximately $50,000 each.
     Vertical designs of the vibrating screen basket type centrifugal
dryer  are  offered  by several firms  including the Bird Machine Company,
Centrifugal and Mechanical Industries, Inc. (CMI), and Heyl and Patterson
(H&P).  Figure  2-25 is a cutaway view of the H & P Hurricane Model showing
how the slurry enters the feed chute at the top and plows down to a
feed chamber where a rotating distributor deposits it on the rotating
basket.  At  the same time as vertical vibrations are moving the material
up  the basket, centrifugal motion is forcing it outward against the
basket screen.   This process  forces the free moisture through the screen
where  it is  discharged.  As dewatered solids reach the top of the basket,
                                    92

-------
CO
                           FEED
                           SLURRY
                                                  FIGURE 2-25

               VIBRATING SCREEN  BASKET  CENTRIFUGAL  DRYER-VERTICAL  TYPE  (H  & P  HURRICANE  MODEL)

-------
they are discharged over the lip and fall through an opening in the base
of the machine.  As with all centrifugal dryers, the capacity of this
machine varies with the consistency of the feed.  According to the man-
ufacturer, the Hurricane Model can reduce the moisture content of 150 tph
of 1/4 inch X 48 mesh coal from over 20% to less than 6%%. Several  manufac-
turers offer units of this type in a wide range of prices depending upon
design features and quality of construction.
     CMI also has a line of vertical type vibrating screen basket cen-
trifugal dryers.  These are the VC-48 and VC-56 models which have F.O.B.
factory prices of $28,200 and $49,800, respectively.  According to the
manufacturer, these have the capacity and performance at various  size
fractions as presented in Table 2-2.  This data is based upon feed
moisture concentrations of 30% or less.
                               TABLE 2-2
                VC-48 AND VC-56 CAPACITY AND PERFORMANCE
                        Solids Capacity in tph            Product
   Size  Fraction          VC-48         VC-56         Surface Moisture %
3 X % inch                200           325                 2.0
2 X k inch                igo           315                 2.0
1% X k inch               180           300                 2.0
1 X % inch                160           270                 2.5
2 inch X 28 mesh          160           270                 2.5
1% inch X 28 mesh          150           255                 2.5
h X % inch                140           235                 3.0
1  inch X 28 mesh          140           235                 3.5
% inch X 28 mesh          125           210                 5.0
3/8 inch X 28 mesh        115           195                 6.5
 % inch X mesh            110           185                 7.5
                                    94

-------
     (2) Scroll Type



     One of the most popular scroll type centrifugal dryers is the



Model EB-36 manufacturered by CMI.  Figure 2-26 shows two of these



units installed in a coal preparation plant.  This type of unit consists
                           FIGURE  2-26



            SCROLL  TYPE CENTRIFUGAL DRYERS (CMI  MODEL  EB-36)
                                    95

-------
of two conical drums; one turning inside the other at a slightly differ-
ent speed.  The outer drum, or basket, is made of stainless steel wire
with replaceable screens mounted on its inner surface.  The inner
(scraper) drum carries the scraper blades or flights which control the
solid material movement across the screen.   As the material enters at
the top, these blades move it downward over the screen through which
the moisture is ejected by centrifugal force.  Eventually, it is worked
down to the discharge area of the dryer where it falls by gravity through
an opening in the bottom of the machine.  The moisture and any fine
particles passing through the screen are gathered in a trough around
the periphery of the machine and discharged through effluent openings.
The capacity of this equipment is dependent upon the feed size, surface
moisture, particle shape, and end product requirements.   As a general
rule, as the percentage of fines increases, there will be a decrease
in capacity and an increase in the surface  moisture of the product.  Ac-
cording to the manufacturer, the Model EB-36 has the capacity and perform-
ance at various size fractions as presented in Table 2-3.   This data is
based upon feed moisture concentrations of  40% or less.
                               TABLE 2-3
               MODEL EB-36 CAPACITY AND PERFORMANCE
 Size Fraction   Solids Capacity in tph    Product Surface Moisture %
3/8 inch X 28 mesh         80                           6 Q
h inch X 28 mesh           60                           6 Q
1/8 inch X 28 mesh         50                           6_5
1/16 inch X 28 mesh        35                           7_5
This unit sells for just over $23,000 F.O.B. factory.
                                 96

-------
     (3) Screen Bowl Type
     The centrifugal dryers discussed thus far are most effective where
the size consist of the wet feed is above 28 mesh.  The screen bowl type
centrifugal dryer manufactured by the Bird Machine Company is designed
to dewater finer size clean coal in the 28 mesh X 0 range. In many applica-
tions, this particular equipment can be used instead of a vacuum filter
to handle the fine coal concentrate from froth flotation or other finer
coal products.  According to the manufacturer, this machine can reduce
the moisture  content of a 28meshX 0 flotation concentrate containing 15% to
20% 325 mesh size particles to 12% to 14% while achieving a 96% to 98%
solids recovery.  This is substantially less than the moisture content
of the filter cake produced by vacuum filters which is normally around
20%.
     This machine has a horizontal configuration which utilizes some of
the same centrifugal dewatering techniques found in the rotating screen
basket designs covered earlier.  From an operational standpoint, the
screen bowl makes a two-step separation.  The initial separation takes
place in the solid section of the bowl where centrifugal force aids
the removal of most of the free moisture in the feed.  Following this,
the solids move via a conveyor screw onto the screen section of the
bowl where most of the remaining moisture is forced through the openings
in the rotating screen.  At the end of screen section, the dewatered
solids are discharged into a collection chamber and drop by gravity
through an opening in the base of the machine.
     This Bird screen bowl centrifuge is available in various sizes
                                    97

-------
ranging from capacities of 5 tph to as much as 75 tph, depending upon
the feed particle size.  Units having these capacities sell for $50,000
and $235,000, respectively.  Although these units are significantly
higher in price than comparable capacity vacuum disc filters, this
higher initial cost should be evaluated in terms of the unit's perform-
ance and the potential for lower operating and maintenance costs.  One
readily visible operating cost savings comes from the approximately
30% less power consumption over a disc type filter.  Another fertile
area for evaluation is the impact on reducing thermal dryer capacity
which as discussed later adds appreciably to the cost of coal  preparation.
     (4) Solid Bowl Type
     This final type of centrifugal dewatering equipment is also appli-
cable to finer size material.  Such machines are mainly used in the
same capacity as refuse vacuum disc filters to handle the underflow
from a static thickener.  They clarify the water and produce a solid
material suitable for disposal.  This machine has a horizontal configur-
ation which has two principal elements.  One is a rotating bowl which
is the settling vessel and the other is a scroll conveyor which ad-
vances the settled solids to the discharge ports.  The clarified liquid
and the solids are discharged at opposite ends of the machine.  As the
bowl rotates, the centrifugal force causes the slurry to form an annular
pool, the depth of which is determined by adjustable effluent weirs.
A portion of the bowl at the solids discharge end has a smaller diam-
eter to form  a drainage deck above the level of the pool.
                                   98

-------
     According to the Bird Machine Company, which manufactures this type
of centrifuge, it is capable of producing a solids product of 30% to 35%
moisture and clean liquid when dewatering feeds having a large concentra-
tion (75-85%) of particles less than 325 mesh.  These units are available
for capacities of 2h tph to 30 tph at a cost of approximately $40,000 to
$220,000, respectively.  Although they require substantial horsepower to
accelerate the heavy slurry, this type of equipment still requires approx-
imately 50% less horsepower than comparable capacity vacuum disc filter
installations.
      2.3.1.2 Vacuum Disc Filter
      The disc type vacuum filter is the principal  piece of dewatering
 equipment used in the coal  preparation industry for handling clean
 coal  and refuse with large amounts of material  below 28 mesh.   As
 mentioned previously, this equipment is commonly used to reduce the
 moisture content of the froth concentrate from flotation prior to
 thermal  drying, as well as handle the static thickener underfow.   This
 equipment is offered in a wide range of capacities by such companies
 as the Denver Equipment Division of Joy and Peterson Filters Corporation.
      As shown in Figure 2-27, the vacuum disc filter consists of a
 series of discs mounted over a trough shaped tank so that slightly
 less than half of the disc is below the edge.  These discs are covered
 on both sides with a fine mesh filter cloth or other suitable filter
 medium.   To be effective, this medium must permit the passage of air
 but not become clogged by the material being filtered.  The discs are
 mounted on a hollow shaft with a complex plumbing arrangement permitting
                                   99

-------
                           FIGURE 2-27
         VACUUM DISC FILTER (10 FT 6 INCH DIAMETER 12 DISC VERSION)

the application of suction and pressure to  the surface  of each disc,
as well as the withdrawal  of the fluid collected.   The  slurry to be
dewatered is fed into the trough at which time suction  is applied
pulling the slurry toward the disc surfaces.   In order  to pull the
fluid through the filter surface, an air flow of about  5 cubic feet
per minute (CFM) per square foot of filter surface is normally applied
when processing froth concentrate and about 3 CFM per square foot of
filtering surface when handling thickener underflow.  As a result of
this action, the solids portion of the slurry is deposited on the disc
surface.  Then, the discs are rotated approximately 120 degrees carrying
                                   100

-------
with them the solids or filter cake retained on their surfaces.  At this
point the filter cake is loosened from the disc surface by reversing
the pressure (blower action) and scraped off into a discharge chute.
The moisture content of this cake will vary from 20% up, depending
upon the makeup of the slurry.
     The capacity of a vacuum disc filter is influenced by the solids
concentration of the slurry to be dewatered and the amount of material
less than 325 mesh.  However, as a very general rule, between 40 and
60 pounds per hour per square foot of filtering area is appropriate
when dewatering clean coal and about 20 pounds per hour per square foot
for refuse.  For example, a 12 foot 6 inch diameter disc filter having
12 discs has 2,736 square feet of effective filtering surface.  There-
fore, on a  load philosophy of 40 pounds of clean coal per hour per
square  foot, this size vacuum filter should be able to handle a maximum
of 110,000  pounds or 55 tons per hour.  Normally, it is a good idea
to have some excess filtering capacity to allow for variations in the
concentration of the feed.
     Although there are some design differences among the various vacuum
disc filters on the market, there is not as much variance in their price
for a given capacity unit as might be expected.  A representative sample
of mid-1977 F.O.B. factory prices is as follows:
Disc Diameter     Number of Discs      Filtering Area       Price
10 ft 6 inches          7               1,085 sq.ft.     $90,000
11 ft                   6                 960 sq. ft.     $ 70,000
11 ft                   8               1,280 sq. ft.     $ 85,000
12 ft 6 inches         10               2,280 sq. ft.     $120,000
13 ft                  12               2,880 sq. ft.     $128,000
                                    101

-------
Besides capacity, prices will be significantly influenced by the type
of filter medium selected.  This is not only an important decision from
the standpoint of initial cost, but also operational performance and
reduced maintenance.  For example, stainless steel wire mesh will cost
over three dollars per square foot but last as much as 10 to 15 times
longer than a cheaper filter medium such as saran.
     2.3.1.3 Vor-Siv
     Although one of the major principles governing the operation
of the Vor-Siv is centrifugal force, a discussion of this stationary
dewatering device was omitted from the earlier section on centrifugal
dewatering equipment to allow separate coverage.  The Vor-Siv was de-
veloped  by the Polish coal industry and is currently manufactured in
this country by  the Perforated Metals Division of the National-
Standard Company under an exclusive licensing agreement.  It is designed
to handle high volumes of solids in a water slurry.  Some of the ways
this equipment has  been applied in coal preparation circuits include
dewatering ahead of centrifuges, desliming ahead of concentrating
tables,  and as protection devices ahead of thickeners and flotation
 cells.   The  unit can  handle  particles  less than 3/8 inch size  in slurries
 of 10% to 30%  solids  concentration.  A single  unit can handle  such a slurry
at feed  rates up to 3200  gallons per minute and thereby produce 150 tph
of dewatered material.
     To  better understand the operation of this device, the reader is
referred to Figure  2-28 which shows the major  components and a simulated
flow pattern.  Feed is introduced to the unit  through a directional
                                 102

-------
                   CIRCULAR RACEWAY
                 FEED
SIMULATED FLOW PATTERN
                                                                            GUIDING TROUGH
INLET NOZZLE


DISCHARGE OUTLET FOR
DEWATERED AND CLASSIFIED
MATERIAL

COLLECTION BOX
FOR EFFLUENT
                                          FIGURE 2-28

                                     VOR-SIV CONICAL SIEVE

-------
nozzle and onto a circular raceway.  A certain minimum head is necessary
to accelerate the feed slurry against the walls of the raceway, causing
partial stratification of solids away from the associated water.  Normally
gravity is sufficient to create this necessary feed force.  As the semi-
stratified feed stream loses energy, it spills from the raceway into a
conical basket of radially slotted profile wire.  The remaining energy
in the feed stream creates a downwardly spiral ing vortex flowing per-
pendicular to the slotted openings in the upper three fourths of the
basket.   Free water and, depending upon the slot aperture, undersized
solids are accelerated through the basket, becoming an effluent product.
As water  is extracted and the vortex continues to lose energy, the
circular  swirl gives away to an axial path downward along the lower one
fourth of the basket.  Slotted openings in this section are placed per-
pendicular to those in the upper section.  Since feed travel has
changed from the horizontal flow into a downward drop, these slots again
provide a "crossflow" action enhancing the final stages of water removal.
The  simulated flow pattern in Figure 2-28, shows how the vortex action
causes the solid particles to change their radial position and flow down-
ward along a steep spiral path on the surface of the screen to the dis-
charge outlet at the point of the vortex.
      One  of this device's principal advantages is its high capacity.
While most stationary screens and sieves are limited to feed rates of 28
to 30 gpm per square foot of screen surface, Vor-Sivs have been success-
fully applied at rates of 50 to 60 gpm per square foot of screen surface.
Even at these high feed rates, water removal and undersize rejection
                                    104

-------
 efficiency have been equal  to or better than achievable with con-
 ventional  equipment.  Other advantages include:   they require no
 lubrication,  generate no noise or vibration, require essentially no
 operator attention or adjustment, and maintain consistent performance
 over a wide range of feed variables.   Capital  cost studies have shown
 the devices to be quite desirable when contrasted with conventional
 dewatering equipment in new plant design.  Retrofit applications have
 also been quite popular.
      As of mid-1977, the F.O.B. factory price of a Vor-Siv was approxv
mately $15,500 to $17,000 depending upon the size of the two-part re-
placeable screen sections.
                                   105

-------
     2.3.1.4 Thermal  Dryer
     The final  major piece of dewatering equipment to be discussed is
the thermal dryer.  This evaporation process is normally applied to
fine and intermediate (typically less than 1 inch) size clean coal
which has not been sufficiently dried to meet the specified moisture
level by the various centrifugal and vacuum filter dewatering tech-
niques discussed earlier.  Thermal drying is an expensive process
from both the standpoint of initial capital requirements as well as
the long term operating and maintenance costs.  In this country, the
application of thermal drying to physically cleaned coal has decreased
from 19.8% in 1970, to 13.4% in 1975.  Moreover, the actual tons dried
have decreased by nearly 50%, i.e., 64,165 in 1970 and 35,681 in 1975.
Although there are many forms of dryers, the dominant thermal drying
method  is fluid-bed which has been growing in acceptance in recent
years as shown by Table 2-4.  The drop in tons of physically cleaned
coal and thus those subjected to thermal drying decreased during the
the 1973 to 1975 period due to several factors.  The major factor was
the sharp increase in demand for coal and thus there was less of a
necessity to perform these costly processes.  Another influence was
the tighter environmental/emission control regulations which have
forced the discontinuance of dryers at some locations rather than in-
stall and/or modify the facilities to comply.  In addition, as noted
previously, the operation and maintenance problems and costs are
enough by themselves to encourage detailed investigations of other
options and strategies before initiating thermal drying.  Therefore,
                                  106

-------
                                                  TABLE 2-4

                         COAL THERMALLY DRIED IN COMPARISON TO ANNUAL PRODUCTION*

                                          (Thousand Short Tons)
Year
1975
1974
1973
1972
1971
1970
Production
648,438
603,406
591,738
595,386
552,192
602,932
Mechanically
Cleaned
266,993
265,150
288,918
292,829
271,401
323,452
Thermally
Dried
35,681
36,045
46,202
53,235
48,105
64,165
% Dried
of Total
Production
5.5%
6.0
7.8
8.9
8.7
10.6
% Dried
of Total
Cleaned
13.4%
13.6
16.0
18.2
17.7
19.8
% Dried By
Fluidized-Bed
72.5%
68.3
66.9
64.1
67.7
66.4
* Bituminous & Lignite
Source: Based Upon U.S. Bureau of Mines, Mineral  Industry Surveys,  Coal-Bituminous  and  Lignite  Annual  1970-75,
        Prepared in Division of Fuels Data and Division of Coal.

-------
it should be employed only after a careful evaluation of the economies
as they relate to the realities of the marketplace.  In other words,
if it does not pay to dry - don't.
     Due to the nature of the process, the thermal drying function is
conducted in a separate facility linked only with the main coal prepara-
tion plant by way of a conveyor.  A view of such an installation ap-
pears as Figure 2-29, which is an intermediate size unit manufactured
by the FMC Corporation.  These are sophisticated installations which can
account for over 25% of the capital cost of the total preparation plant
complex when a substantial portion of the output is dried.  A more pre-
cise understanding of this relationship can be obtained from a review
of Examples 2, 3, 4, 6, and 8 in Section 5.0 which have varying thermal
drying requirements.  To meet these various requirements, fluid-bed driers
are  offered by several companies in a wide range of capacities, each
with its own unique design features.  Some appreciation for their
sophistication can be gained from Figure 2-30, showing a cutaway view
of a thermal dryer manufactured by the ENI Division of Lively Manu-
facturing.  Being a well defined portion of the overall preparation
process permits a fairly accurate appraisal of the capital and 0 & M
costs associated with thermal drying.  The following is an example of
the capital cost as of mid-1977 for a medium size fluid-bed dryer.
     Description of Drying Requirementi
     Bituminous Coal % inch X 0
     Reduce Moisture from 13% to 5% at the rate of 350 tons per hour
                                 108

-------
                                        1
                       FIGURE 2-29



FLUID-BED THERMAL DRYER INSTALLATION (FMC FLUID-FLO MODEL)
                           109

-------
                 TEST PLATFORM
      DUST COLLECTOR
         CYCLONES
 EXHAUST FAN DUCT
 MIST ELIMINATOR STACK








       FURNACE BY-PASS STACK


          DRYER FEED CONVEYOR
            /

            DRYER FEED
           CONTROL BIN
             DRYER ROLL FEEDER
                 FURNACE
                   STOKER ROOM
       DUST
      HOPPERS
  EXHAUST FAN
    MOTOR
                   VENTURI SCRUBBER

  MOTOR & FAN   INSTRUMENT AIR COMPRESSOR
ACCESS PLATFORM
                 f STO HER FUEL
                    CONVEYOR
                 OVERFIREFAN
            FORCED DRAFT FAN
         DRIED PRODUCT
           CONVEYOR

       TEMPERING AIR DAMPER
    DISCHARGE AIR LOCKS

MIST ELIMINATOR
                              FIGURE 2-30

    CUTAWAY  VIEW OF  FLUID-BED  THERMAL DRYER (ENI  COAL-FLO MODEL)
                                110

-------
Description of Drying Facility:
  One (1) 10' X 14' FMC Fluid-Flo Dryer with connected horsepower
  of 2200 hp.  Complete with roll feeder, stoker, furnace, ductwork,
  fluidization chamber, hood, cyclone dust collectors, exhaust fan,
  scrubber, stack, feed bin, fuel conveyors, fuel bin, ash conveyor,
  insulation, dust screws and automatic temperature controls.
                                            Price $ 950,000
Installation of Dryer including foundation, structural steel, motors,
  motor controls, wiring, piping, field erection, and start-up service.
                                            Price $1,650,000
                TOTAL DRYER CAPITAL COST	$2,600,000
     In order to generate the heat necessary to achieve the required
moisture reduction, this dryer would be consuming approximately 6 tons
per hour of coal having a nominal heat content of 12,500 Btu/lb.  If
we assume  that  such a  coal  has a  cost of $20 per ton to the preparation
plant operator, then,  the fuel cost per ton of dried coal would be:
                 6 tons/hr  X $20/ton = $0.343/ton
                     350 ton/hr
If this particular plant was producing an  additional 550 tons per hour
of clean coal for a total output  at 900 tph, then the fuel cost impact
per ton of total product would be:
                 6 tons/hr  X $20/ton
                 	 = $0.133/ton
                     900 tons/hr
     In addition to the fuel  (coal) necessary  to operate the thermal
dryer, electricity is  another major operating  cost  factor.  Using  the
standard relationship  between kilowatts and  horsepower  of  0.745 kw = 1  hp,
                                    111

-------
an estimate of the electric power consumption and cost of operating the
thermal dryer can be made.  In the case of a dryer having 2200 hp the
following calculations apply:
     0.745 kw/hp X 2200 hp = 1,639 kw
     With 80% efficiency, consumption would be:
                     l^p. = 2,048.75 ^ 2,050 kw
                      U.o
Assuming an electric rate for a large industrial user of between
$ 0.03 & $ 0.05 per kilowatt hour, electricity cost per hour would
be  - $ 0.04/kwh x 2,050 kw = $82.00 per hour.
     Therefore, if a dryer of this size (2200 hp) is processing
350 tons of coal per hour, the electric cost on a dried ton is -
     $82.00/hour - 350 tons/hour = $ 0.23/ton
                 •
If  the plant was producing an additional 550 tons for a total clean
coal output of 900 tph, then the impact on each ton of clean coal
would  be -
     $82.00/hr - 900 tons/hr = $ 0.09/ton
     This tells us that the impact of thermal drying electric cost
alone  is $ 0.09 per ton.  Since there is normally a comparable volume of
horsepower in the balance of the preparation plant, the overall
electricity cost will be roughly $ 0.18 to $ 0.20 per ton of clean
coal.  If the electric rate was $ 0.05 per kwh, then this cost could
be  as  high as $ 0.23 per ton.
     This is just one example of a fluid-bed thermal drying application.
Each case will not only vary with the volume and size of the  feed but  also
according to the nature of the coal itself and  the specified  end product.
                                   112

-------
However, when some level of thermal moisture reduction is necessary,
the volume of material fed to the dryer should be kept to an absolute
minimum in order to limit the high capital and 0 & M costs referred to
above.  As has been said previously regarding other portions of the
preparation plant, the applicability and/or necessity of thermal dryers
must be determined on a specific case basis where the further reduction
in moisture is weighed against the required end product and how and
where it will be handled and eventually consumed.
2.3.2 Static Thickener
     The majority of the coal preparation plants in operation today and
all those built in recent years have a closed water system.  What this
means is that the effluent from the cleaning plant must be handled in
such a way that the solids and liquid are separated before being released
into the environment.  With the increase in fine coal cleaning and
the use of continuous mining methods, a greater amount of solid material
winds up in the waste water from the preparation plant.  Although settling
ponds are still used to a large extent, the most common method of clarify-
ing this waste water is with the use of a static thickener.
     As shown in Figure 2-1, the typical static thickener is a circular
tank usually of concrete or steel construction which is located close to
the cleaning plant.  To understand the workings of this critical piece
of water clarification equipment, the reader is referred to Figure 2-31
showing a cross-sectional representation of a static thickener.  The
liquid effluent from the plant is fed via a trough into the feedwell at
                                    113

-------
 FEED TROUGH FROM PLANT
WALKWAY    DRIVING
          MECHANISM    FEEDWELL
                                                                            CLEAR
                                                                            OVER-
                                                                            FLOW
             SOLIDS UNDERFLOW PUMPED
               FROM THIS AREA
                                                               ROTATING RAKE
            TANK BOTTOM
                        FIGURE 2-31
              CROSS-SECTION OF STATIC THICKENER

the center of the thickener.  This can be seen in Figure 2-32 which
shows the slurry moving out to the center of the tank and into the feed-
well -whose rim is about one foot above the liquid level.  As this slurry
flows from the feedwell out toward the edge of the tank, the solids tend
to settle.  This settling is encouraged by the addition of flocculants
and other chemicals.  The settled solids are pushed along the bottom of
the tank by slow moving rakes.  These rakes or plows are driven by a
heavy duty, all weather, mechanism located at the center of the tank.
Because of the slope of the tank bottom, these solids are moved toward
the center of the tank from which they are pumped to a vacuum filter or
other dewatering device. Once dewatered, this solid underflow material is
normally disposed of with the coarser refuse from the plant. However, in
some plants, this thickener underflow has desirable enough properties to
warrant blending it back in with the clean coal product.  The clarified
                                  114

-------
                                              DRIVE  MECHANISM
FEEDWELL IN CENTER
 OF TANK
                                DIRECTION OF FEED
                              FIGURE  2-32

                      TOP  VIEW OF STATIC THICKENER

                                   115

-------
liquid overflows the outer edge of the tank into a trough from which it
is pumped back into the plant's water system for reuse in the cleaning process.
     Static thickeners are sized according to the anticipated clarifica-
tion requirements of the plant plus a reasonable margin for variations
in the quality of the raw feed.  This is necessary since during the
mining of any given seam, substantial variations in composition will be
experienced.  Also, in cold weather when the coal is damp and muddy,
greater amounts of clays and other fine material are brought into the
plant and must be handled by the water clarification system.  This
problem can be particularly acute in the case of strip mined coal.
      Depending upon the requirement, static thickeners are constructed
in a  range of sizes up to over 200 feet in diameter.  Although the
price will vary with the sophistication and quality of the drive mech-
anism, a very good approximation of the total installed price of a con-
crete type between 90 and 200 feet in diameter is $2,000 oer foot of
diameter.  In this size range, the drive mechanism alone will account
for 45-55% of the total installed price.  This mid-1977 composite price
will  also be subject to the cost and availability of local materials
of construction but to a lesser extent than that for concrete silos
discussed in Section 2.1.1.
      2.2.3 Coal Sampling Equipment
     A detailed discussion of coal sampling techniques and equipment
is beyond the scope of this report.  However, it will suffice to say
that with the trend toward larger and more complex coal preparation
plants, there will be an increasing need for efficient and accurate

                               116

-------
analysis of the clean coal product prior to its leaving the plant.
Such data is particularly important where blending is practiced or coal
is prepared for slurry pipelining.  This need may also be accentuated
by the application of pending environmental regulations which might re-
quire precise documentation on the amount of sulfur which was present
in the as-mined coal and was removed by the cleaning process.
     Regardless of the cleaning plant's level of complexity, some analysis
of the raw and clean coals is necessary to evaluate performance.  Many
times the sampling procedure is not just for the benefit of the
preparation plant operator, but is part of a purchase specification.
Under these circumstances, the coal is sampled before it leaves the plant
and then again at the destination.  Depending upon the individual contract
relationship, this data can provide the basis for applying bonuses or
penalties according to variances  in the as received product in comparison
with predetermined ash, moisture, sulfur, and Btu limits.
     Coal sampling equipment is offered in a wide range of sizes and
sophistications.  There are multi-stage sampling systems which are of
such size and complexity that they are constructed as a separate building
(tower) adjacent to the cleaning  plant or part of the load-out facility.
Sampling systems of this type can cost over half a million dollars and
are usually found only at very large plants.  An indication of this
complexity is given in Figure 2-33, which schematically represents a
coal sampling system manufactured by the Denver Equipment Division of
Joy Manufacturing Co.  Since there is such a variance in the application
and need for sampling systems, a  figure of $300,000 was used to estimate
                                    117

-------
          Primary
          Sampler
          Secondary
          Sampler
                                                            Collector
           Reject
           Conveyor
                              FIGURE  2-33

    THREE-STAGE COAL SAMPLING SYSTEM - (DENVER EQUIPMENT DIVISION OF  JOY)

this capability for all larger preparation plants considered under  Sec-

tion 5.0 rather than the cost of the system actually being used.  This way

the total capital cost of any given plant was not biased for comparative

purposes because of its particular system.
                                  118

-------
           SECTION 3,0
SMALLER SIZE PREPARATION PLANTS
               119

-------
3.0 SMALLER SIZE PREPARATION PLANTS
     Although the major thrust of this study was to more accurately define
the costs associated vith preparation plants of 500 tons per hour raw coal
input or greater, it may be useful to the reader to have some indication of
the costs related to smaller scale operations.  As in the case of larger
plants, the final cost of the plant is a function of the many variables unique
to the particular situation.  Two of the most important variables are the
washability of the coal and the end product specification.  These will dic-
tate the make-up of the cleaning circuit and to what extent the material
must be dried.  As indicated elsewhere in this report, the extent to which
the product must be dewatered has a very significant impact upon the initial
capital requirements and the on-going 0 & M costs.
     Preparation plants can meet a variety of needs in the smaller scale op-
eration. In some cases, a mine can clean a portion of its production with a
simple "semi-portable" plant and come up with a marketable product. There are
a number of smaller size plants being offered by  such firms as Coal Process-
ing Equipment, Inc., Jeffrey Manufacturing Division of Dresser Industries,
and RAPCO, Inc.  These plants come in a wide range of sophistications, some
of which are even capable of finer size coal recovery. Although there is
not much interest yet, one application for these smaller plants may be in
the recovery of coal from existing refuse piles.  The economics of such an
arrangement can be quite favorable under some circumstances since there is
no mining or mine development cost necessary and therefore more investment
in cleaning equipment can be made while still yielding an acceptable rate
of return.
                                    120

-------
Jeffrey  Unitized  Jig Coal  Cleaning Plant
     One smaller size coal preparation plant is the Jeffrey unitized jig
plant.   This  is a packaged coal  washing  plant  utilizing  a  Jeffrey  two-cell dia-
phragm jig  as the cleaning unit.   The plant which  has  a  nominal capacity of 150
tph  of feed is structurally arranged as  shown  in Figure 3-1 below.
                                     FIGURE 3-1
                               LAYOUT OF  UNITIZED JIG

     The  plant  comes  as  a  package  containing  all equipment, structural steel,
 interconnecting chutes,  piping,  electrical distribution system, lighting, siding
 and roofing  and other materials  necessary for construction.  The purchaser
 supplies  an  appropriate site, foundations,  power  supply and  fresh water  supply.
 The cost  of  the raw coal delivery  system and  the clean coal handling system is
 not included and can  be  supplied either  by Jeffrey or the purchaser.
General Process  Description -
     As shown in Figure 3-2,  the raw coal is delivered by belt conveyor to the
jig feed chute where the raw coal  is mixed with water.
                                    121

-------
                   •RAW COAL
                   •CLEAN COAL
                   REFUSE
                   -CLEAR WATER
                   • WASTE WATER
                                    FIGURE 3-2
                         FLOW SHEET OF UNITIZED JIG PLANT
     The raw coal then reports to the two-cell diaphragm jig where  the coal
is washed.  The refuse material is removed from the jig by  bucket elevators  for
dewatering.  The refuse is dewatered on a double deck screen with the coarse
refuse reporting to a 50 ton refuse bin.  The fine refuse  (-28  mesh)  and water
report to waste.
     The clean coal from the jig is dewatered and sized on  a double deck
vibrating screen.  The 1/2 inch coal passing over the top  deck  of the dewatering
screen is crushed to the desired product size. The 1/2X1/4 inch  coal passing over
the second deck of the screen  is further dewatered in a centrifugal dryer.  The
1/4 inch X 0 material reports to a sump from which it is pumped  to clarification
cyclones.  The underflow from  these cyclones is partially  dewatered and deslimed
by sieve bends before being combined with the 1/2X1/4 inch  material  for centri-
fugal  drying.  The overflow from these cyclones reports to a  head  tank for
                                       122

-------
recirculation to the jig.  The  slimes and water from the sieve bends and the
centrifuge combine  with  the  fine refuse  and  report  to  waste.   The  clean  coal
from the crusher and the centrifugal dryer is collected as a final product for
loading or storage.
     The fine waste (fine  refuse and slimes  from the sieve bends and centrifugal
dryer) will generally  report to settling ponds for  clarification.  A closed
circuit using a thickener  and vacuum filter  could be provided as an option.
Such an option has  not been  considered in the estimated price of the system
appearing at the end of  this section.
     The mechanical  action bringing  about the separation of the raw feed into
clean coal (float)  and refuse (sink) is  shown by  Figure 3-3,  which also  identifies
the major component of a two-cell jig.
                                     FIGURE 3-3
                               TWO-CELL DIAPHRAGM JIG

                                        123
                                                            AV OPEN i »3 Pl*T€
                                                               CONIEC TI I«
                                                                Cfl iX « IB*

-------
Plant Performance -
1.  Capacity
     The performance of the unitized jig plant is dependent strictly on the
performance of the jig since it is the only piece of washing equipment used.
All other equipment has been sized to handle the maximum tonnages and flows
which the jig is capable of handling.  The nominal capacity of the jig is
150 tph.  The actual capacity of an individual plant is based on the size
consist of the coal to be washed and its washability characteristics.  As
the separation becomes more difficult (i.e., fine coal  cleaning or a large
amount of near gravity material), the capacity of the jig is reduced to allow
for proper cleaning.  As the separation becomes easier (i.e., coarse coal
washing or little near gravity material), the capacity increases.
2.  Coal Quality
     The clean coal quality produced by the unitized jig plant is dependent
on the washability characteristics of the raw coal and  the limitations of
the jig.
     The two-cell diaphragm jig will generally wash the coarser size feed (plus
1/4 inch) at a specific gravity between 1.50 and 1.60.   It will  wash finer coal
(1/4 inch X 28 mesh) at a somewhat higher specific gravity, generally around
1.80, and its ability to wash very fine coal (minus 28  mesh) is negligible al-
though some cleaning does occur.  The minus 100 mesh material is discarded as
refuse.  The following example will help to illustrate this performance.
                                          124

-------
       Given a raw  coal with  the  following washability characteristics;
                             ANALYSIS  OF  THE  RAW  FEED
        Size  Fraction

        +1/4  inch
        1/4 inch  X  28  mesh
        28 mesh X 100  mesh
        -100  mesh

        Total
% of
Total
57.12
33.17
8.77
0.94

% S
1.05
0.95
1.12
1.84

Btu/lb
11,947
11,602
9,555
7,890
                        100.00
1.03
11,585
% Ash

14.23
16.07
21.27
30.44

15.61
                         WASHABILITY  DATA  -  PLUS  1/4  INCH
 Specific
 Gravity
SINK   FLOAT
1.35
1.40
  50
  60
1.35
1.40
1.50
1.60
1.80
1.80
 Specific
 Gravity
SINK
_
1.35
1.40
1.50
1.60
1.80
FLOAT
1.35
1.40
1.50
1.60
1.80
_

% REC.
68.8
7.4
9.2
3.0
2.4
9.2
% REC.
66.7
7.8
7.8
3.0
2.7
12.0
57.12% of
Individual
Dry Basis
% ASH % S
4.64 0.72
11.04 1.07
18.52 1.34
25.85 1.81
38.28 2.72
74.21 2.58
WASHABILITY DATA
33.17% of
Individual
Dry Basis
'% ASH %'S
4.15 0.65
10.96 0.89
18.86 1.31
29.56 2.05
42.05 2.56
74.59 1.80
Total Sample
Btu/lb % REC.
13,515 68.8
12,541 76.3
11,350 85.4
10,130 88.4
Cumulative
Dry Basis
% ASH % S
4.64 0.72
5.26 0.75
6.69 0.82
7.34 0.85
7,900 90.8 8.14 0.90
1,982 100.0 14.23 1.05
- 1/4 INCH X 28 MESH
Total Sample
Btu/lb % REC.
13,535 66.7
12,437 74.5
11,091 82.3
9,331 85.3
7,226 88.0
2,203 100.0
Cumulative
Dry Basis
'% ASH % S
4.15 0.65
4.86 0.68
6.19 0.74
7.01 0.78
8.09 0.84
16.07 0.95

Btu/lb
13,515
13,420
13,198
13,094
12,959
11,947
Btu/lb
13,535
13,420
13,199
13,063
12,884
11,602
                                         125

-------
     If only the coarser size (+1/4") was washed the following clean coal quality
from the plant would be expected on a dry basis:
          % WT.                                                      % Btu
       RECOVERY     % MOISTURE     % ASH     % SULFUR     Btu/lb     RECOVERY
         88.4           <6         7.34        0.85       13,094      96.9
This is the quality of the + 1/4" material only.  The quality of the composite
clean coal (+1/4" clean coal and -1/4" raw coal) would be:
          % WT.                                                      % Btu
       RECOVERY     % MOISTURE     % ASH     % SULFUR     Btu/lb     Recovery
         93.4           <6         12.08       0.92       12,259      98.8
     If all the raw coal sizes were fed to the plant, the following clean coal
quality would  be expected:
          % WT.                                                      % Btu
       RECOVERY     % MOISTURE     % ASH     % SULFUR     Btu/lb     Recovery
         89.3           <6         8.97        0.87       12,673      97.7
     The choice between washing only the coarser coal or all raw coal sizes is a
 judgement  decision, dependent on the desired clean coal quality and  the washa-
bility.  In some cases the-1/4 inch material needs little if any cleaning and could
 bypass the plant with very  little detrimental effect on the clean coal quality.
In other cases, as the one above, the washing of the fine coal along with the
coarse coal produces a better overall clean coal.
3.  Capital Cost
    The initial capital cost of a unitized jig plant excluding raw coal and
clean coal handling facilities, site preparation, foundations, power supply
and fresh water supply, is  approximately  $650,000.  The cost of the  excluded
items will vary greatly, depending on site configuration and location. However,
                                     126

-------
the average expected cost of these items would be approximately $450,000.
This gives a total  average cost of $1.1 million.  Placed on the basis of
150 tph raw coal  input, this translates to $7,300 per ton hour input.  As
would be expected,  this is slightly higher than larger simple jig plants of
the type described  by Example 1 in Section 5.0.
                                          127

-------
                  SECTION





OPERATIONAL AND OTHER FACTORS INFLUENCING COST
                      128

-------
4.0 OPERATIONAL AND OTHER FACTORS INFLUENCING COST
     This section is devoted to a brief discussion of the major factors
which influence the cost of coal preparation irrespective of the type of
cleaning process.  Although some of these factors such as plant utiliza-
tion are controllable to some extent, others like diminishing coal
quality are more a reality of the times.
4.1 Plant Utilization
     Obviously, there are 8,760 hours in most years (24 hours/day x
365 days/year).  Although these can be considered the maximum potential
number of working hours per year, there are some practical considerations
brought on by custom and the nature of the process as well as the legal
and union realities of the environment in which business functions. By
custom, we are referring to the fact that most workers today are geared
to a forty hour or less work week, the observance of certain holidays,
and annual vacations.  Also limiting the number of hours a particular
process can be fully functional are the practical/economic limits im-
posed by the necessity to shut down for scheduled and unscheduled
maintenance and the doubtful availability of an unlimited pool  of
qualified personnel to fill-in when the regular staff is absent.  Addi-
tionally, in some industries, such as coal preparation, there is not a
continuous supply of raw material available.  Finally, the legal and
union restrictions on the number of hours and designated days an employee
can work without being paid premium wages influence the total number
of hours a particular operation will be productive during any given
year.
                                  129

-------
     In a capital  intensive industry such as coal  preparation, the
greater the plant can be productive, the less will  be the capital cost
burden carried by each ton of clean coal.  Additionally, the more the
plant can run continuously, the less time will be lost in start-up and
shut down.  To try and assess the impact of such "lost" time, the in-
fluence of the union contract imposed work hours is discussed below.
Plant Efficiency - Impact of Union Contract
     The most recent National Bituminous Wage Agreement of 1974, which
was effective through 5 December 1977, provided for preparation plant
and supporting personnel (outside employees) to have a 7 hour and 15
minute work day.  Included in the 7.25 hours is a 30 minute lunch break.
For this 7.25 hours per day and 36.25 hours per week, the employer must
pay the overtime wage rate of time and one-half for the additional
time worked.
     Considering the practical application of this  number of hours to
the efficient operation of a preparation plant gives some food for
thought which has encouraged operators to use overtime in spite of the
cost.   It  is standard practice at plants to conduct three shifts per
day beginning at 8 A.M., 4 P.M. and 12 A.M.  Assuming two of these
shifts are operating and no overtime is incurred, it will take 30 minutes
to an hour to start-up and the plant will be shut-down between 30 minutes
and an hour before the shift is over if overlapping scheduling of
workers is not permitted.  This means that a minimum of one hour and
45 minutes of potential operating time is lost before the next operating
shift comes on duty; i.e., half an hour starting up, half an hour to shut
down plus 45 minutes between shifts.  Then, it will take the second
                                    130

-------
 operating shift between 30 minutes and an hour to get the plant
 functioning at capacity again.  Toward the end of this shift, the plant
 will again have to be shut down which will mean a loss of another 30
 minutes to one hour.  Therefore, during the period from  8 A.M. to
 12 midnight when there was potentially sixteen hours of operating time,
 the plant only produced coal during a maximum of 12.5 hours.  This was
 calculated as follows:
     Total  Potential  Operating Hours                  16.0
       Between 8 AM and 12 Midnight
     Less:
            8 A.M. Shift Start-Up                      0.50
            8 A.M. Shift Shut-Down                     0.50
            Break Between Shifts                        .75
            4 P.M. Shift Start-Up                      0.50
            4 P.M. Shift Shut-Down                     0.50
            Break Between Shifts                        .75
              Total Lost Operating Time                3.50
                Net Operating Time                              12.5
Since the half an hour at the beginning of the day and the conclusion
of the second shift is essential, an additional 2.5 operating  hours
might be picked up if overtime was incurred.
     One way of evaluating the impact of this lost operating time is to
look at the additional expenses and income associated with the extended
period.  For the purposes of this analysis, it is assumed the  preparation
plant is capable of producing 1000 tons of clean coal per hour and
that a profit of $2.00 per ton is realized.  This amount is meant to
Be a conservative estimate of the profit after considering all normal
                                   131

-------
mining and preparation costs.  Therefore, on the income side, if an
additional 2,500 tons of clean coal were produced, $5,000 would be
available to cover the increased labor costs.
Current Industry Practice
     During the initial phase of this study conducted during 1975-1976,
we had determined that preparation plants typically operate approximately
3,380 hours per year out of a possible 8,760 for an annual utilization
of 38.6%.  This was based upon data collected from plant operators and
other industry sources.  However, data collected during the first half
of 1977 indicate that our previous utilization level was high.  Many
instances were recorded where operators ran the plant two shifts and
performed maintenance on a third.  Unfortunately, although they were
paying for 14.5 operating hours  (two 7.25 hour shifts), the plant would
only function 11 to 13 hours per day.  Compounding this problem of
utilization was the fact that with vacations, holidays, special leave,
sick days, and unaccountable absences, the plant might only operate
200  days  per year.  Variations of these current conditions are reflected
in the operating and maintenance costs of the actual preparation plants
examined  in Section 5.0.
      Those costs such as capital amortization which are sensitive to output
(plant utilization) have been allocated on the basis of the given plant
functioning at the nominal capacity indicated on its flow sheet for
2600 hours per year.  This is equivalent to two 7.25 hour operating
shifts (UMWA) 200 days per year  reduced by 1.5 hours per day to allow
for  start-up on the first shift  and shutdown on the second.  This assumes
                                    132

-------
overlapping of workers on operating shifts.  Although this represents
only a 30% utilization of the plant on an annual basis, it is not
uncommon in recent years due to  unscheduled work stoppage, mining
production delays, and  other factors.  However, it is assumed that
not all operations are plagued by these difficulties and those that
are, will  be able to increase their utilization.  Therefore,  the oper-
ating and maintenance costs presented for each preparation plant example
are summarized on the basis of a raw coal input and clean coal output
under both a 30% and 40% utilization.   This latter utilization figure
equates to 13 hours per day for 270 days  per year '(3510 hours) and rep-
presents an upper bound on being able to  retain a maintenance shift for
every two operating shifts with the plant layout considered.   Higher
utilization can obviously be achieved if  redundant preparation circuits
were to be included which would permit ongoing maintenance without total
plant shutdown.  Although there may be definite economic advantage assoc-
iated with such an approach under certain conditions, only one such plant
was examined and thus no definite conclusions can be drawn.
4.2. Coal Quality
     The material withdrawn from the coal seam  before being subjected
to any form of preparation is referred to as run-of-mine.  In addition to
actual coal, this mined product includes rock and other impurities taken
from the ground as part of the mining operation.  Since the introduction
of modern mining machinery and methods, the quality of this material
has diminished.  This reduced quality is reflected in lower yields from
                                  133

-------
preparation plants due to the greater amounts of refuse in the raw
feed.  In order to compensate for this situation, existing plants have
had to be redesigned to provide greater refuse handling capacity so as
not to reduce the desired quality of the clean coal product.  Several
years ago, plant yields of 80 - 90 % were not uncommon.  However, today,
it is equally not uncommon to observe coal preparation plants having
yields in the range of 50 %.  Needless to say, this requirement for greater
refuse handling capacity makes for higher capital and operating and
maintenance costs, not to mention the larger refuse disposal problem.
This  latter problem can be particularly  acute  due to the environmental
regulations governing refuse disposal and the lack of suitable landfill
areas.

      Some of the specific factors which contribute to the degradation of
the  run-of-mine coal are as follows:
      1.  Mining Machinery - Increased usage of continuous mining equipment.
         Due to the manner in which this equipment functions, greater
         amounts of material above and below the coal  seam (roof and
         floor) are loaded out with the coal than occurs in conventional
         mining.
      2.  Mining Methods -
         A)  Greater use of water for dust control,  In an attempt to
             meet dust limitations, an increasing amount of water is
             now used in the mining process.  This water places into
             suspension such undesirable impurities as clay and rock
                                    134

-------
             dust which  are  eventually loaded out with  the  coal  and
             wind up  at  the  preparation plant.
        B)   Requirement for continuous clean-up.   Federal  regulations
             direct the  removal  of excess  material  from the mining
             area to  keep passages fully open.   Thus, it is more convenient  for
             the miner to load out all  the material  in  the  way at one
             time rather than make a  separate coal  and  rock cycle.
     3.  Quality of Coal  Seams - Many of the  coal  seams  being mined today
        contain large amounts of impurities  which  cannot be avoided in
        the  mining process  and are therefore loaded out directly with
        the  coal.
     This  diminishing coal quality is reflected in terms of higher  capital
cost for the same capacity plant.  Additionally, operating  and maintenance
costs are  affected  especially in the  areas of refuse disposal  and  chemical
                                                              »
expense associated  with  water clarification.
4.3 Capital Amortization
     4.3.1 Capital  Amortization Defined
     Whether a plant is  bought outright, financed through a third  party,
or leased over an extended period, the total  capital costs  represent an
outlay of funds to  someone which must be accounted for  in determining
the overall cost of coal cleaning.   If the company operating the prepa-
ration plant had sufficient  liquidity to purchase the installation with-
out outside assistance,  they  still must account for these  funds invested
                                    135

-------
which they have elected to withdraw or divert from other income pro-
ducing opportunities.  Not only do they want to recover these funds
during the useful life of the plant, but they should also receive a fair
rate of return based upon other investment alternatives.  If a plant  is
fully leased  through an outside source, the operator's  total lease payments
consist of both the  plant cost and a "fair rate of return" to a third party
in  the form of interest. Although the period of recovery and the rate of
return/interest will vary, this same "cost of capital" reasoning applies
regardless of the source of funds; only the mechanics differ.  This
 mechanical  process  normally takes the form of spreading the  cost of the plant
 over its  output  and is  referred to as capital amortization.
      Nhere a  company has  purchased the plant with its own or borrowed
 funds,  the capital  is  "recovered" as depreciation and is listed as an
 expense attributable to each unit of output.  If the preparation plant
 is  leased,  the payments are also allocated as an expense to each ton  of
 clean coal  produced.   Therefore, it is obvious that whether any given
 plant is  financed or leased, the capital cost per unit of output will  be
 reduced as the plant produces more clean coal.  This becomes a significant
 factor in the case  of larger more sophisticated preparation  plants, due
 to  the increasingly capital intensive nature of their processes.  A
 general  indication  of this trend comes from the following summarization
 of  current capital  requirements for a variety of preparation plant sizes
 and complexities as covered in Section 5.0.
                                      136

-------
                                           Input  Feed     Capital Cost
Example            Type Of Plant              Rate      Per Ton Hr Input
   1            Jig - Simple                  600 tph      $  6,600
   2            Jig - Intermediate          1000 tph        13,700
   3            Jig - Intermediate          1000 tph        12,100
   4            Jig - Complex               1600 tph        14,300
   5            Heavy Media - Simple        1400 tph        13,800
   6            Heavy Media - Complex         600 tph        22,400
   7            Heavy Media - Complex         600 tph        14,000
   8            Heavy Media - Complex         900 tph        23,200
These figures are only intended to show the magnitude of preparation
capital costs and do not imply any general relationship concerning the
capital cost of one process over another.  Such a discussion is reserved
for Section 5.0 where the reader has the opportunity to review the make-
up of the individual plant and better understand why its cost differs
from another plant of comparable input capacity.
     In the following sub-section, an explanation is given  of the  factors
influencing capital amortization and the rationale used to develop the
approach applied under Section 5.0.  It is noted that the approach  dis-
cussed therein is only one of many possible ways of spreading the cost of
the preparation complex over the output of the plant.  Should the  readers
feel another approach better represents their particular circumstance, it
may be substituted without affecting the accuracy of the other costs of
operation presented for each of the preparation process examples.
     4.3.2 Capital Amortization Applied
     As indicated earlier, there are a variety of approaches to spreading
the preparation plant capital cost over the material processed.  Whether
you are allocating this cost to each ton of raw  coal fed to the plant
or each ton of clean product, the figure arrived at  under all approaches
                                      137

-------
is sensitive to the following factors:
    1)  total capital required
    2)  plant capacity
    3)  operating hours per period (utilization)
    4)  cost of money
    5)  period over which plant is written-off
    Certainly, the first two factors will be directly related to the
magnitude and complexity of the particular preparation plant.  For most
operations today, the third factor, that of plant utilization, will vary
within a range of between 30% and 40%.  It is acknowledged that some ex-
ceptions do  exist at either end of this range.  However, in the absence
of  redundant preparation equipment, it is uncommon for a plant to actually
operate more than 40% of the time.  This is equivalent to a plant opera-
ting  12 to 13 hours per day 270 days per year for a total of approximately
3,500 hours  per year out of a possible 8,760.
    With regard  to the cost of money, a range of values will occur in
practice whether the plant is purchased with borrowed or internal funds.
If  the funds are acquired outside  the firm, their cost will be a function
of  the current prime interest rate, term of loan, and the credit of the
borrower.   Even  larger firms experience loan rates of 2 to 3 percentage
points over  prime for purchases of this type.   If the plant is to be
funded directly  by the firm, consideration must be given to the rate of
return which might be realized by  alternative uses.
                                   138

-------
     The final variable in determining capital  amortization  is  the write-
off period.  Although this is influenced  by  the anticipated  life of the
plant and Internal Revenue Service depreciation guidelines,  its final
determination is made on the basis of individual company fiscal policy.
Certainly, many elements comprising the total plant when properly main-
tained will last 20 to 30 years whereas others  will require  replacement
within 5 to 10 years.  Therefore  in practice, the period over which
the plant is written-off will be  a composite of the anticipated re-
placement cycles limited by the IRS and specific company fiscal policy
previously noted.
     Realizing the diversity of approach  as  well as the myriad of values
which could be assigned to the factors influencing capital amortization,
we have,for the purposes of the various preparation plants covered by
this study, taken a straightforward approach which is easily understood
and adaptable to individual circumstances.   Under this approach, it is
assumed that the plant is entirely financed  by  an equal monthly payment
self-liquidating loan granted at  an annual interest rate of  9%  (7% prime
plus 2%).  By considering both the principal and interest portions of this
self-liquidating loan as costs, this approach gives equivalent results to
depreciating the principal over the life  of  the plant.  Further, we are
considering loan repayment periods of both 10 and 15 years to provide a
range indicative of the write-off periods actually being observed for
preparation plants by industry.   Finally, we have considered a  30% and 40%
plant utilization which relates to approximately 2600 and 3500  operating
hours per year, respectively.
     Based upon the above assumptions, the following relationships are
presented which are applied in Section 5..0 to determine the  allocation of
capital cost for each of the preparation  plants examined  therein.
                                       139

-------
CCM = Capital Cost Per Month = Capital Cost X Periodic Payment Factor
     Periodic Payment Factor = Pr =  }-i + -;ui   -i
       Where: n = period of loan in months
              i = interest rate per month
       Therefore:
         When i = prime rate + 2%
              i = 0.07 *z 0.02  = 0.0075 per month
         And  n = 120 months (10 years)
              p  = 0.0075 (1 + 0.0075)120
               F      (1 + 0.0075)120 - 1
              PF = 0.012668
         When n =  180 months (15 years)
              PF = 0.010143
     Based upon these periodic payment factors, the monthly capital cost
per million dollars of plant investment would be —
CCM for 10 years = $106 X 0.012668 = $12,668
     and
CCM for 15 years = $106 X 0.010143 = $10,143/month
     Obviously, the annual capital cost per million dollars of plant in-
vestment would be —
CCy = Capital Cost Per Year = CCfv] X 12
       Therefore:
              CCy for 10 years = $152,016
       And
              CCy for 15 years = $121,716
                               140

-------
This being the case, plants which operate 30% (2,600 hrs) and 40%
(3,500 hrs) of the time will have hourly capital costs per million
dollars of plant investment of —
CCR = Capital Cost Per Hour = CCy T Utilization
At 30% Utilization
CCR for 10 years = $152,016 7 2,600 = $58.47       and
CCH for 15 years = $121,716 T 2,600 = $46.81
At 40% Utilization
CCH for 10 years = $152,016 7 3,500 = $43.43       and
CCH for 15 years = $121,716 7 3,500 = $34.78
Now, knowing  these four factors, they can be applied to any plant given
the total capital required and the input/output capacity.  For example,
an 11 million dollar plant which is processing 900 tons per hour (tph)
of raw coal and producing 720 tph of clean coal would have capital costs
as follows:
     For  10 Year Amortization - 30%
       $58.47 X 11 7 900 = $0.71 per ton of raw coal
       $58.47 X 11 7 720 = $0.89 per ton of clean coal
Summarizing the various values based upon either 30% or 40% utilization gives:

                          CAPITAL AMORTIZATION
                                                % Utilization
Amortization Period & Basis
10 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
15 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
30%
$0.71
$0.89
$0.57
$0.72
40%
$0.53
$0.66
$0.43
$0.53
                                     141

-------
As mentioned above, there are many portions of the preparation plant
which, with proper maintenance, will last substantially longer than
the 10 to 15 years write-off period.  This being the case, one might
assume that following this write-off period, capital amortization
would no longer be an applicable cost of preparation and the clean
coal produced after that time would be "cheaper" since it would not
be burdened with this expense.  However, this is not what occurs.
Industry experience indicates that coal preparation plants are essentially
"replaced" from a capital standpoint every 7 to 10 years.  What this
means is the operator will reinvest an amount equivalent to the initial
cost of the plant approximately every ten years.  Another way of looking
at this subject is to think of the operator incrementally "rolling
over" his capital during the life of the plant, thus never eliminating
capital amortization but making it a recurring expense.  These fresh
capital funds are typically required to handle major equipment replace-
ment and refurbishment as well as periodic modification and/or additions
to the preparation plant.  This latter requirement can be brought on
by the availability of more effective equipment, variances in the com-
position of the raw coal, and/or changes to the clean coal specification.
Although these major expenses can be anticipated to some extent, they
are not considered part of the routine operation and maintenance cost
of the preparation plant.  This being the case, although a  10 or 15
year write-off period is used, the allowance for capital amortization
will be a recurring expense for the total life of the plant to properly
account for the periodic influx of "fresh" capital  into the plant.
                                    142

-------
4-4 Cost of Btu Loss In Cleaning
      During the cleaning process some portion of the heat content of
the raw feed is lost.  Since the raw coal had some value before cleaning,
the heat content lost also had a definite value.  This amount lost
should be accounted for and allocated as an additional cost of coal
cleaning.  The specific cost attributed to this Btu loss is a function of
the raw coal value, the Btu content of the raw coal, and the Btu recovery
of the particular  coal cleaning process.  For ease of understanding, we
have approached this quantity as the difference between the output cost
and input cost per million Btu.  To illustrate how this quantity is de-
termined, the following example is given:
      Assume -
        Raw Coal Cost of  $15.00 per ton
        Btu Content of  Raw Coal 9,000 Btu per Ib
        Btu Recovery of Cleaning Process 94%
      This gives an  input cost of  -
 Input Cost = $15.OO/ton '- (9,000 Btu/lb  X 2000 Ib/ton)
       Input Cost = $0.833/1O6  Btu
 Since the Btu  recovery  of the  process  is 94%, the output  cost will be  -
      Output Cost  =  Input Cost '- 0.94
      Output Cost  =  $0.833/106 Btu '-  0.94
      Output  Cost  =  $0.886/1O6 Btu
 Therefore,  the Btu loss will  be -
       Btu  Loss  =  Output Cost - Input Cost
                                      143

-------
      Btu Loss = $0.886/1O5 Btu - 0.833/106 Btu
      Btu Loss = $0.053/106 Btu
This approach is observed in determining the Btu loss for each of the
preparation processes examined under Section 5.0.  In all cases a raw
coal value of $15.00 per ton is assumed.  Obviously, the other two
variables, raw coal Btu content and Btu recovery, are based upon the
specifics of the example presented.
      As  covered in Section 5.0 on a plant by plant basis, there is much
discussion on whether or not it is appropriate to apply  the "cost" of
these  "lost" Btu's to coal preparation.  This question arises since the
material  discarded in cleaning, which contained these "lost" Btu's,
is  essentially  large quantities of the undesirable raw coal constituents
such as  ash  and sulfur whose removal was the very purpose of the prepara-
tion process.   It  is for this  reason that the individual process should
be  evaluated to determine whether or not a maximum economic Btu recovery
point  has been  reached.  If the process is performing reasonably close
to  well  conceived  design Btu recovery limits, it might be more appropriate
to  not consider these "lost" Btu's as a cost.  However,  if the process is
either poorly conceived from the standpoint of economic  Btu recovery or
the plant is not performing close to its design  capabilities, then an
inefficiency "penalty" might be assessed to reflect this discarded heat
content which was  lost unnecessarily.  This being the case, the  "cost" of
this "lost" heat content has been treated as a separate  element which  the
reader may apply or not as seen fit.
                                   144

-------
Btu Content of Clean Coal -
     In order to make an accurate calculation of the Btu content of the
clean product from the preparation plant, consideration must be given
to the final moisture content.   If the Btu content of the clean coal
on a moisture free (MF) basis is known, the true Btu content can be
calculated as follows:
Assume - Btu Content (MF) of Clean Product = 13,056 Btu/lb
         Moisture Content of Clean Product = 4.6%
Then -   True Btu Content of Clean Product =
             (1-.046) BtuMp = .954 (13,056)
         True Btu = 12,455 Btu/lb
If the Btu content of the coal on a moisture and ash free (MAF) basis
is known, the true Btu content of the clean product can be calculated
as follows:
Assume - Btu Content (MAF) of Coal = 14,511 Btu/lb
         Moisture Content of Clean Product = 4.6%
         Ash Content of Clean Coal = 10.03% (Dry Basis)
Then -   True Btu of Clean Product =
               [(1-.1003) (1--046)]  BtuMAF = .8583 (14,511)
         True Btu = 12,455 Btu/lb
     The above computation was used for determining the final Btu con-
tent of the clean product in Example 3 presented in Section 5.0.  A
similar approach was used in the other examples where sufficient data
was available.  In the absence of such data, reasonable assumptions
were made.
                                     145

-------
         SECTION 5,0
PREPARATION PROCESS EXAMPLES
             146

-------
5.0  PREPARATION PROCESS EXAMPLES
     Presented within this section are summaries of eight actual coal
preparation plants along with their individual capital and operating
and maintenance (O&M) costs as of mid-1977. These plants span a spectrum
of currently applied coal preparation technology from a relatively simple
jig process to rather complex circuits utilizing heavy media, froth flo-
tation, and thermal drying.  Each of these plants is discussed separately
with an analysis of the specific process and the level of cleaning achieved
based upon the particular coal being processed.
     Through these examples of actual  operating plants, the reader is
made aware of the sensitivity of the total  cost of coal preparation to
such major elements as plant capital cost and the presence of thermal
drying in the circuit.  Further, the influence of plant utilization on
the amortization of fixed costs is noted for each example.  Since these
costs are presented on a uniform mid-1977 time base, they may be updated
to subsequent periods with appropriate index adjustment.
     All cost data relative to these eight plants are presented from the
perspective of the preparation plant operator and do not assess the many
user oriented benefits resulting from coal cleaning.  In addition to in-
creased heat content, these benefits include lower emission control,
transportation, boiler maintenance, and ash disposal costs.  These costs
must be quantified on a site specific basis and set-off against the
preparation costs presented herein to arrive at the net cost of coal
cleaning.
                                   147

-------
5.1  Example 1 - Jig Process - Simple
     5.1.1  General  Description
     Although there are more basic preparation processes utilizing a jig
as the primary separation vessel, this plant is categorized as "simple" to
place it in a range with the other jig processes examined under Examples
2, 3, and 4.
     This particular plant is designed to handle a variety of coals from
both surface and underground mines.  The separation achieved by the process
as presented in the flow sheet, Figure 5-1, is based upon processing a
deep mined coal using continuous mining equipment.
     From the raw coal storage area, the 8 inch X 0 material is conveyed
via a 42 inch wide belt to a 6 X 16 foot single deck vibrating screen. As
a  result of the force of being dropped onto this screen and the vibrating
action, the larger pieces of coal are fractured to 6 inches or less.  The
small amount of material which does not reduce to 6 inches or less passes
over the screen and reports to the refuse belt.  The 600 tph of 6 inch X 0
raw coal is fed to an eight cell three compartment Baum type jig.  Of the
material entering the jig, 372 tph "floats" out and 234 tph sink as refuse.
This refuse goes to a 5 X 10 foot double deck vibrating screen with l/2mm
openings in the bottom deck where it is partially dewatered before report-
ing to the refuse belt.
     The 372 tph of "float" from the jig goes to two 6 X 16 foot vibrating
double deck screens having 3/4 inch and 1/4 inch openings in the top and
bottom decks, respectively.  Approximately 90 tph of 6 X 3/4 inch coal
passes over the top deck and goes to a crusher where it is reduced to
2  inch X 0 before dropping onto the clean coal belt.  Passing over the
                                    148

-------
                                                                               FIGURE  5-1

                                                                 EXAMPLE  1  - OIG PROCESS -  SIMPLE

                                                                    PREPARATION  PLANT  FLOW  SHEET
FROM MINING AREAS
30 TPH 48m X 0
1


M SPLITTER
T GATE
1 18 TPH
30 TPH " \ SLUDGE
1^"™^^ HYDROCVCLONES ^ 	
12 TPH
350 GPM
PONDS/'
__/
                                                                                        TPH| DESLIMING SCREENS

                                                                                     X 48 mr
II   \  \  \        '
I	.
48 X 120 ml

  12 TPH I
                                                                       DEWATERING SCREENS
                                                                                                                                     , DESLIMING SCREEN
                                                                                                                                                 12 TPH

                                                                                                                                               48 X 120m

	
142 TPH

1/4 in X 0


u ,,
- m^^m^^^^m
—^3/4 X 1/4 in

140 TPH






0
i





/^ CRUSHER
21n X 0
90 TPH
230 TPH











CENTRIFUGES
112 TPH

                                                                                                                                                12 TPH
                                                                                                                                                           2 in X 0

                                                                                                                                                          354 TPH
                                                                                                                     CLEAN COAL

                                                                                                                      BELT

-------
lower deck is 140 tph of 3/4 X 1/4 inch material which goes directly to
the clean coal  belt.  The 1/4 inch X 0 material passing through both decks
reports to a sump from which it is pumped to four 20 inch diameter Nihard
classifying cyclones at the rate of 142 tph.  The 112 tph of 1/4 inch X 48
mesh underflow from these cyclones goes to two 6 X 16 foot desliming screens.
All measurable material passes over these screens and is fed to two centri-
fugal dryers which recover essentially all of the feed.  From the dryers,
the 1/4 inch X 48 mesh material goes to the clean coal belt.
     The 30 tph of 48 mesh X 0 overflow from the 20 inch classifying cyclones
reports to a sump from which it is pumped to five 14 inch diameter rubber
lined hydrocyclones.  Of this total cyclone feed, 12 tph of 48 X 120 mesh
material reports as underflow and goes to a 3 X 12 foot single deck de-
sliming screen.  Essentially all of this material passes over this screen
and  goes to a centrifugal dryer before going to the clean coal belt. There
is 18 tph of 120 mesh X 0 overflow from the hydrocyclones which is split
between the jig feed sump and the sludge ponds.  Of the 18 tph, 6 tph re-
ports to the sump from which it is pumped back to the jig and the balance
(12  tph) is sluiced to the sludge ponds along with approximately 350 gallons
per minute of water.
     A total of 354 tph of 2 inch X 0 material having a heat content of
13,236 Btu/lb drops onto the 36 inch wide clean coal belt and is conveyed
to a 40,000 ton open storage area awaiting unit-train load-out.  Based
upon a plant feed of 600 tph with a heat content of 8,523 Btu/lb, this
plant yields an impressive 91.6% Btu recovery.  Other performance figures
are  presented in Table 5-1.
                                    150

-------
     The personnel necessary to operate and maintain this plant are listed
under Table 5-4.  As indicated in Table 5-5, the turn-key construction cost
of this plant is 3.95 million dollars based upon mid-1977 price quotations.
                                   151

-------
CJl
ro
          Raw Coal  Feed To Plant:




          Size Fraction


          6  X 3/4 inch


          3/4 inch  X 0
                                                     TABLE 5-1

                                         EXAMPLE 1 -  JIG PROCESS - SIMPLE

                                          PREPARATION PLANT PERFORMANCE*
Tph
180
420
Surface
Moisture %


Btu/lb
8,120
8,693
Ash %
41.17
35.34
Total
Sulfur %
0.60
0.67
                                 600
          Clean  Coal  Product From Plant:
               7.0
               8,521
             37.09
                0.65
          2  inch  X  0
354
8-9.0
13,236
7.68
0.79
          Net  Performance:

              Weight  Yield 59.0%      Btu  Recovery 91.6%      Btu of Clean Coal  with 8-9% Moisture 12,111 Btu/lb



          * Btu, Ash,  & Sulfur Presented on Dry Basis

-------
                                                  TABLE  5-2


                                      EXAMPLE 1 - JIG PROCESS - SIMPLE

                        WASHABILITY DATA OF ASSUMED PLANT FEED - +3/4 INCH FRACTION*
en
CO
      Specific Gravity
       of Separation
Height %   Ash %   Sulfur %   Btu/.lb
          Cumulative Float

Height %   Ash %   Sujfur %   Btu/lb
Float 1.40
1.40- 1.45
1.45- 1.50
1.50- 1.55
1.55- 1.60
SINK- 1.60
46.42
2.67
1.22
1.06
1.55
47.08
4.75
13.33
23.63
29.50
55.96
78.89
0.78
0.76
0.93
0.51
0.42
0.41
14,003
12,352
10,990
9,880
5,263
2,060
46.42
49.09
50.31
51.37
52.92
100.0
4.75
5.23
5.66
6.15
7.61
41.17
0.78
0.78
0.78
0.78
0.77
0.60
'14,003
13,913
13,842
13,760
13,512
8,120
       * 29.75% of Total  Feed

-------
                                                      TABLE  5-3
                                          EXAMPLE 1  -  JIG  PROCESS  -  SIMPLE
                           WASHABILITY DATA OF ASSUMED PLANT FEED  -  3/4  INCH X 0 FRACTION*
tn
       Specific Gravity
        of Separation
Weight %   Ash %   Sulfur %   Btu/ 1 b
          Cumulative Float
Height %   Ash %   Sulfur_%   Btu/lb
Float 1.40
1.40- 1.45
1.45- 1.50
1.50- 1.55
1.55- 1.60
SINK- 1.60
47.23
4.49
3.0
2.04
1.99
41.25
4.69
14.67
16.61
21.69
35.99
74.68
0.78
0.80
0.94
0.87
0.76
0.47
13,810
11,737
10,219
9,712
7,707
2,388
47.23
51.72
54.72
56.76
58.75
100.0
4.69
5.55
6.16
6.72
7.71
35.34
0.78
0.78
0.79
0.79
0.80
0.67
13,810
13,630
13,443
13,309
13,119
8,693
       * 70.25% of Total  Feed

-------
                                  TABLE 5-4
                      EXAMPLE 1 - JIG PROCESS - SIMPLE
             PREPARATION PLANT OPERATING & MAINTENANCE PERSONNEL
General Non-Union Management
Preparation Manager  (1/4 time)
Operating Shift (2 per day)
     Title
Foreman
Plant Operator
Electrician/Mechanic
Repairman Helper  (Greaser)
Utility Man
Mobile Equipment  Operator  (Raw  and
  Clean Coal Handling)
     Dozer Operator

Maintenance Shift (1 per day)
Foreman
Mechanic
Utility Man

Personnel Summary
General Management
Operating Shifts
Maintenance Shift

*NU-Non-Union
Union Classification
        NU*
        4-E
        4-A
        2-F
        1-H
Quantity
   1

Quantity
   1
   1
   1
   1
   2
3-A
Total
NU*
4-C
1-H
Total
_2
8
1
3
_1
5
        Total
    1
   16

   22
                                         155

-------
                              TABLE 5-5
                   EXAMPLE 1 - JIG PROCESS - SIMPLE
                PREPARATION PLANT CAPITAL REQUIREMENTS
RAW COAL STORAGE AND HANDLING:
      Raw Coal Storage Area
          20,000 Ton Capacity with Stacking Tube,
          Reclaiming Feeders, and Tunnel                      $300,000
      Raw Coal Belt To Plant
          42  Inch Wide - 200 Feet @ $520 per foot              104,000
      Tramp Iron Magnet
          Explosion Proof - Self Cleaning Type                  20,000
                  Total Raw Coal Storage & Handling Cost      $424,000

PREPARATION PLANT:
      Equipment Cost -
          6 X 16  Foot Single Deck Vibrating
          Scalping Screen
            1 @ $17,500                             $ 17,500
          Eight Cell Baum Type Jig
            1 @ $176,000                             176,000
          6 X 16  Foot Double Deck Vibrating
          Dewatering Screens
            2 @ $23,000 each                          46,000
          5 X 10  Foot Double Deck Vibrating Refuse
          Dewatering Screen
            1 9 $18,000                               18,000
                                     156

-------
     Crusher
       1 0 $12,100                                $ 12,100
     Classifying Cyclones
       20 Inch Diameter - NiHard
       4 @ $2,400 each                               9,600
     HydrocycTones
       14 Inch Diameter - Rubber Lined
       5 @ $1,300 each                               6,500
     3 X 12 Foot Single Deck Desliming Screen
       1 @ $12,000                                  12,000
     Centrifugal Dryer          *
       1 @ $23,200                                  23,200
     Centrifugal Dryers
       2 @ $28,200 each                             56,400
     6 X 16 Foot Single Deck Desliming Screens
       2 @ $16,000 each                             32,000
     Sumps
       3 G $10,000 each                             30,000
     Pumps                                          75,000
      Total Preparation Plant Equipment Cost      $514,300
Total Cost of Preparation Plant
     Including Site Preparation, Construction of
     Building, Electrical  Service, Piping, etc.
     $514,300 X 3.0                                        $1,542,900
                                157

-------
OTHER FACILITIES & EQUIPMENT:
      Clean Coal Belt
          36 Inch Wide - 300 Feet @ $480 per foot              $   144,000
      Clean Coal Storage Area
          40,000 Ton Capacity with Stacking Tube,
          Reclaiming Feeders, etc.                                350,000
      Refuse Belt
          36 Inch Wide - 250 Feet @ $480 per foot                 120,000
      Refuse Bin                                                  50,000
      Raw Coal and Refuse Handling Equipment
          2 - Dozers @ $150,000 each                              300,000
      Unit-Train Loading Facility                                 500,000
                      Total Other Facilities & Equipment       $1,464,000
SUMMARY OF CAPITAL COST:
      Raw Coal Storage and Handling                            $   424,000
      Preparation Plant                                        1,542,900
      Other Facilities and Equipment                           1,464,000
      Contingency (Interest during construction, etc.)            515,000
                             Total Capital Requirement         $3,945,900
SBASED UPON THE 600 TON  PER HOUR  INPUT TO THIS PLANT THE CAPITAL
IREQUIREMENT TRANSLATES  TO $6,600 PER TON HOUR INPUT
                                     158

-------
     5.1.2 Capital Amortization
     Based upon the rationale developed in Section 4.0, the capital
amortization for Example 1 is as follows:
       Total Capital Required: $3.95 million
       Capacity:
           Raw Coal Input - 600 tph
           Clean Coal  Output - 354 tph

                         CAPITAL AMORTIZATION
Amortization Period & Basis
10 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
15 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
% Utilization

30% 40%
$0.38 $0.
$0.65 $0.
$0.31 $0.
$0.52 $0.
29
48
23
39
      5.1.3 Operating and Maintenance Costs
      The operating and maintenance costs summarized in the following
Table 5-6 are based upon:
      o  Raw Coal Input of 600 Tons Per Hour
      o  Clean Coal Output of 354 Tons Per Hour
      o  Btu Recovery of 91.6%
      o  10 Year Amortization Period
      o  30% Utilization 2,600 Operating Hours Per Year
           out of a Possible 8,760 Hours or 13 Hours Per Day for 200
           Days Per Year.  (Although this is low, this rate is applied
           in order to be more consistent with the actual experience
           during the period over which the cost data was collected.)
                                     159

-------
                               TABLE 5-6

                   EXAMPLE 1 - JIG PROCESS - SIMPLE

                    OPERATING AND MAINTENANCE COSTS
                                               Per Ton         Per Ton
COST CATEGORY                                  Raw Coal       Clean Coal
     Labor -

         Supervisory (Non-Union)                $0.044          $0.075

         Operating & Maintenance (Union)         0.303           0.514

     Overhead -

         Fringe Benefits - 25% Non-Union         0.011           0.019
                         - 21%     Union         0.064           0.108

         Other - Includes Welfare Fund,
           Payroll Taxes, Property Taxes,
           Insurance, etc.                       0.059           0.100

     Supplies -

         Operating                               0.155           0.262

         Maintenance                             0.148           0.251

     Major Maintenance - Scheduled repairs
       and plant improvements                    0.134           0.228

     Electricity -                               0.073           0.123

     Subcontract Services to Dip Sludge Ponds,
       Haul Refuse & Miscellaneous Expenses      0.599           1.016

     0 & M Cost -
       Not Including Capital Amortization       $1.59           $2.70

     Capital Amortization -
       10 Yrs. - 30% Utilization                 0.38            0.65

     Total Operating & Maintenance Cost         $1.97           $3.35
     Cost Per Million Btu  (12,111 Btu/lb)                       $0.138
                                   160

-------
     5.1.4 Discussion of Performance and Cost
     As indicated by the performance data summarized in Table 5-1, the
Example 1  plant is capable of significantly reducing the ash content of
this particular coal while still  maintaining a reasonable Btu recovery.
Since the majority of the already small  sulfur content of this raw coal
is organic in nature, the net effect of the cleaning process is to
slightly increase the overall sulfur percentage in the final product.
Although this result is expected since organic sulfur is not removed
by physical cleaning, it does not imply that this process will
produce comparable results with all  coals.  When handling coals having
greater pyritic sulfur contents, processes of this type can contribute
favorably to reducing the overall sulfur content of the clean coal pro-
duct.
     From the washability data given in Tables 5-2 and 5-3, it can be
observed that the jig is effecting a separation at between 1.50 and 1.60
specific gravity.  Looking further at the data, it is clear this point
provides a relatively simple or "black and white" separation due to the
limited amount of near gravity material.  Such a clear separation makes
for the efficient application of the Baum jig which loses much of its
effectiveness as the percentage of near gravity material exceeds 10%.
Even though slightly over 40% of the feed to the plant is discarded as
refuse, the process still recovers 91.6% of the feed's Btu content.
This occurs since the composite ash content of the material which sinks
at a specific gravity of 1.60 is 76% and has a heat content of only 2,290
Btu/lb.  Although a charge can be applied to the total preparation cost to
                                  161

-------
cover these lost Btu's, it is debatable whether such a penalty is
appropriate since the tangible value of this discarded material is
questionable. If such a penalty is assessed in the manner covered by
Section 4.4, it would have the effect of increasing the cost per million
Btu by $0.081 to $0.219.
     Under normal conditions, this plant functions five days per week,
operating two full shifts a day with one shift devoted to maintenance.
As indicated by Table 5-4, the number of personnel required to operate
and maintain a plant of this size and complexity are quite small.   Al-
though greater utilization of this plant is technically possible,  mining
difficulties and other unscheduled stoppages have prevented operating
hours from exceeding 2,600 per year.  This limited utilization is  re-
flected in higher fixed charges such as capital amortization, super-
visory salaries, and some overhead costs.  In spite of this less than
optimum utilization, the overall cost of cleaning is quite reasonable
considering  the results achieved.  The $3.35 per ton is a small price
to pay for taking an 8,500 Btu/lb coal containing nearly 40% ash and pro-
ducing a product having less than 8% ash.  This cost could be even lower
if it were not for the large expense ($1.02 per ton) associated with
maintaining  the sludge ponds and hauling refuse.  A modification to
the plant is currently being considered which would help to alleviate
this expensive problem.
     Simpler coarse cleaning plants of this type have a definite place
in the future of coal preparation.  With many coals, they can cost-
effectively  produce  a  product which is less expensive to handle and
consume. The savings associated with these benefits such as lower trans-
portation cost,  ash  disposal, boiler maintenance, etc. have not been  deducted

                                   162

-------
from the bottom-line cost in Table 5-6 since these benefits must be
assessed on a site specific basis to be meaningful.  However, it
should be noted that when these benefits are quantified and deducted
from the cleaning cost, the net cost of coal preparation can be signif-
icantly less.
                                  163

-------
5.2  Example 2 - Jig Process - Intermediate
     5.2.1 General Description
     This particular plant is processing coal from the Pittsburgh Number 8
Seam which is mined mainly with continuous miners.  The plant is located
near the mouth of the mine from which the coal is brought in mine cars to
a rotary dump.  After being unloaded, the 10 inch X 0 coal is conveyed to
two 6 X 16 foot single deck inclined screens designed to separate the raw
material"at four inches as shown on the flow sheet, Figure 5-2.  On its
way, the raw coal passes under a tramp iron magnet for the removal of
ferrous matter such as broken mining bits.  The less than 4 inch material
passes through these screens and is conveyed to a 5,000 ton concrete silo.
The plus 4 inch material passing over the screens goes to a crusher where
it is reduced to four inches or less before being conveyed to the silo.
     From the silo, the 4 inch X 0 raw coal is fed into the plant at the
rate of 1,000 tph via a 48 inch belt to two eight cell three compartment
Baum type jigs where the initial separation takes place.   Under the manner
in which the plant is operated, the sink from the first compartment is
considered refuse.  However, the sink from the second and third compart-
ments is treated as middlings.  A portion of these middlings is re-
covered on two double deck 5 X 14 foot combination refuse and middlings
screens.  This is accomplished by routing the middlings to the top deck
having 1/2 inch openings and the refuse to the lower deck which has 28
mesh screen.  By this arrangement, the 4 X 1/2 inch material passing over
the top screen goes to a crusher where it is reduced to 1 inch or less
before being pumped back to the jigs for further separation.  The 4 inch
X 28 mesh material passing over the bottom deck goes directly to the
36 inch wide refuse belt.  The fine material passing through both decks
                                  164

-------
       TRAMP IRON
                FIGURE 5-2
EXAMPLE 2  - JIG PROCESS -  INTERMEDIATE
     PREPARATION PLANT  FLOW SHEET
                                                                                                                             LEGEND

                                                                                                                             COAL

                                                                                                                             REFUSE
                                                                                                                                              CLEAN COAL
                                                                                                                                               CRUSHER
                                                         25 TPH I  HVDROCYCLONES

                                                                    80 TPH
                                                                                                                                                   1-1/4 in X 0
    r
FOR TRUCK REMOVAL
 TO  DISPOSAL SITE

-------
goes to the 120 foot diameter concrete thickener.
     The 4 inch X 0 material "floating" out of the jigs passes to fixed
sieves having screen openings of 1/4 inch.  The 4 X 1/4 inch material
passing over these sieves goes to four double deck 8 X 16 foot vibrating
screens.  The 1/4 inch X 0 material passing through these sieves goes to
four fixed sieves having 28 mesh screening.  The 1/4 inch X 28 mesh
material passing over these 28 mesh sieves goes to four 6 X 12 foot
single deck dewatering screens.  The 28 mesh X 0 material passing through
the 28 mesh sieves reports to two sumps along with any fines passing
through the 6 X 12 foot dewatering screens.  From these sumps, a slurry
of 28 mesh X 0 material is pumped at the rate of 80 tph to four 24 inch
diameter hydrocyclones.  These cyclones are essentially performing a
thickening function since the 25 tph 100 mesh X 0 overflow goes to the
static thickener.  The 55 tph of 28 X 100 mesh underflow from these
cyclones is considered clean coal and goes to a vacuum disc filter for
partial dewatering before being conveyed to the fluid-bed thermal  dryer.
This filter is 12 feet 6 inches in diameter and has 14 discs, giving an
effective filtering surface area of 3,190 square feet.  A load factor of
40 pounds per hour per square foot of filtering space allows for approxi-
mately 10% excess filtering capacity.
      Returning to the  8 X 16 foot double deck screens, the top deck has
screen openings of  1-1/4 inches and the bottom has 1/4 inch.  The 4 X
1-1/4  inch clean coal  passing over the top deck goes directly to two
crushers at the rate of 220 tph where  it is reduced to 1-1/4 inch X 0
before  going to the 48 inch wide clean coal belt for load-out into a
13,000  ton concrete silo.   The  1-1/4 X 1/4 inch material passing over
                                  166

-------
the second deck goes to two centrifugal dryers at the rate of 220 tph
for further dewatering.  These dryers recover 215 tph (97-98%) of the
feed which then goes directly to clean coal storage.  The 5 tph of
effluent reports to a sump from which it is pumped to the thickener.
The 1/4 inch X 0 material passing through both decks of the 8 X 16 foot
screens joins the overflow from the 28 mesh sieves and is fed to four
6 X 12 foot single deck vibrating dewatering screens having 28 mesh
openings.  The 1/4 inch X 28 mesh material  passing over these screens
at the rate of 230 tph is fed to two centrifugal  dryers for further
dewatering.  The 224 tph (97%) recovered by these centrifuges goes to
the thermal dryer.  The 6 tph of effluent from these centrifuges is con-
sidered refuse and is pumped to the thickener.  The thermal  dryer re-
ceives a total of 279 tph of 1/4 inch X 0 coal having a surface moisture
of around 13%.  Following drying, the moisture is between 5% and 6%.
This is roughly the moisture content of the entire 714 tph of 1-1/4 inch
X 0 clean coal produced by this plant.
     Underflow from the static thickener is pumped at the rate of 66 tph
as a slurry containing approximately 35% solids to a vacuum disc filter.
From this 12 feet 6 inch diameter filter with 15 discs, the filter cake
goes to the refuse silo where it is combined with larger size material
permitting it to be trucked to a landfill site.
     The staff necessary to operate and maintain this plant are presented
in Table 5-9.
                                  167

-------
                                                      TABLE 5-7
                                         EXAMPLE  2  -  JIG  PROCESS  -  INTERMEDIATE
                                           PREPARATION PLANT PERFORMANCE*
          Raw Coal  Feed To Plant:
                                              Surface                                       Total
          Size Fraction          Tph         Moisture  %        Btu/ib      Ash  %           Sulfur
          4 inch X 0           1000             4.3             9,610      32.32             3.42
          Clean Coal  Product From Plant:
™         1-1/4 inch  X 0        714              6.9            12,974        12.24             3.16

          Moisture  &  Ash Free Btu --  14,784 Btu/lb
          Net  Performance:
               Weight Yield  71.4%        Btu  Recovery  96.4%       Btu  of  Clean  Coal  with 6.9% Moisture 12,079 Btu/lb

          1] Btu, Ash, & Sulfur Presented on Dry Basis

-------
                                                        TABLE 5-8

                                         EXAMPLE 2 - JIG PROCESS - INTERMEDIATE

                                   CUMULATIVE WASHABILITY DATA OF ASSUMED PLANT FEED*
en
              Specific Gravity
                of Separation
  Recovery %
Weight      Btu
 Cumulative Float
Btu/lb       Ash %
  Cumulative Sink
Wt. %        Ash %
FLOAT 1.40
1.40- 1.50
1.50- 1.60
1.60- 1.70
SINK- 1.70
54.88
59.97
62.90
64.84
100.00
78.2
84.7
88.0
90.0
100.0
13,690
13,570
13,440
13,340
9,610
7.40
8.17
8.98
9.73
32.32
100.0
45.12
40.03
37.10
35.16
32.34
62.64
68.51
71.90
73.99
              *Btu & Ash Presented on Dry Basis

-------
                          TABLE 5-9
                EXAMPLE 2 - JIG PROCESS - INTERMEDIATE
          PREPARATION PLANT OPERATING & MAINTENANCE PERSONNEL
General Non-Union Management
Preparation Manager
General Foreman
Operating Shift (1st)
Foreman
Plant Operator - Central
Stationary Equipment Operator
   (Thermal Dryer)
Electrician
Mechanic
Mobile Equipment Operator
     Truck Driver  (Refuse)
     Dozer Operator
Repairman Helper (Greaser)
Utility. Man
Car Dumper

Operating Shift (2nd)
Foreman
Plant Operator - Central
Stationary Equipment Operator
   (Thermal Dryer)
Mechanic
Mobile Equipment Operator
     Truck Driver  (Refuse)
     Dozer Operator
Utility Man
Car Dumper
Union Classification
        NU*
        4-E

        3-C
        4-A
        4-C
        3-A
        3-A
        2-F
        1-H
        1-B**
        Total
        NU*
        4-E

        3-C
        4-C

        3-A
        3-A
        1-H
        1-B**
        Total
Quantity
   1
   1


Quantity
   1
   1

   1
   2
   1

   2
   1
   2
   2

  14


   1
   1

   1
   1

   2
   1
   2

  10
                                    170

-------
Maintenance Shift                    Union Classification     Quantity
Foreman                                      NU*                 1
Mechanic                                     4-C                11
                                                **
Car Dumper                                   1-B                 1
                                             Total              13

Personnel Summary
General Management                                               2
Operating Shifts                                                24
Maintenance Shift                                               13
                                             Total              39
* NU-Non-Union
**Car Dumper Operator is paid at Job Class 3 Rate of Pay when equipment
 is being operated to dump the car.
                                      171

-------
                                TABLE 5-10
                 EXAMPLE 2 - JIG PROCESS - INTERMEDIATE
                 PREPARATION PLANT CAPITAL REQUIREMENTS

RAW COAL STORAGE AND HANDLING:
      Raw Coal Belt To Grizzly
          48 Inch Wide - 100 feet  @ $560 per foot               $    56,000
      Tramp Iron Magnet
          Explosion Proof - Self Cleaning Type                        20,000
      Grizzly (Scalping) Tower
          Includes screens and structure                            250,000
      Raw Coal Crusher                                                66,000
      Raw Coal Belt To Silo
          48  Inch Wide - 550 feet @ $560 per foot                   308,000
      Raw Coal Silo (Concrete)
          5,000 ton capacity @ $110 per ton                         550,000
      Raw Coal Belt To Plant
          48  Inch Wide - 300 feet @ $560 per foot                   168,000
                            Total Raw Coal Storage & Handling    $1,418,000
PREPARATION PLANT:
      Equipment Cost -
          Baum Jig - Eight Cell
            2 @ $176,000 each                         $352,000
          5 X 14 Foot Double Deck Vibrating Screen
            2 @ $26,000 each                             52,000
                                     172

-------
8 X 16 Foot Double Deck Vibrating Screen
  4 @  $36,000  each                           $144,000
 Fixed  Sieves
  8 @  $7,000 each                              56,000
6 X 12 Foot Single Deck Dewatering Screen
  4 @  $16,000  each                             64,000
 Hydrocyclones  -  24  Inch
  4 @  $3,500 each                              14,000
 Sump - Hydrocyclone  Feed
  2 @  $10,000  each                             20,000
 Sump - Centrifuge Effluent
  1 @  $10,000                                  10,000
 Sump - Crushed Middlings
  2 @  $10,000  each                             20,000
 Pumps
  Centrifugal  Dryers - Bird  Model 11500
  4 @  $48,000  each                            192,000
 Vacuum Disc Filter  - Refuse
  12 Feet  6 Inch Diameter -  15  Disc
  1 @  $135,000 each                           135,000
 Vacuum Disc Filter  - Clean Coal
  12 Feet  6 Inch Diameter -  14  Disc
  1 @  $130,000                               130,000
 Crusher  -  Middlings
  2 6  $12,100  each                             24,200
 Crusher  -  Clean  Coal
  2 @  $20,400  each                             40,800
  Total  Preparation  Plant Equipment Cost   $1,254,000

                           173

-------
      Total  Cost of Preparation Plant
          Including Site Preparation, Construction of
          Building, Electrical Service, Piping, etc.
          $1,254,000 X 3.0                                       $3,762,000
OTHER FACILITIES & EQUIPMENT:
      Fluid-Bed Thermal Dryer
          Complete with structural steel, motors, motor
          controls, wiring, piping, field erection, and
          start-up service                                       2,500,000
      Static Thickener (Concrete)
          120 feet in diameter @ $2,000 per foot                   240,000
      Refuse Belt To Refuse Silo
          36 Inch Wide - 300 feet @ $480 per foot                  144,000
      Refuse Silo
          250 ton capacity @ $200 per ton                           50,000
      Refuse Handling Equipment
          2-50 Ton Trucks 6 $75,000 each                         150,000
          1 - Dozer (Spreding & Compacting)                        150,000
      Coal Sampling System                                         300,000
      Clean Coal Belt To Silo
          48 Inch Wide - 450 feet @ $560 per foot                  252,000
      Clean Coal Silo
          13,000 ton capacity @ $110 per ton                     1,430,000
      River Barge Loadout Facility
          1000-1500 tph capacity including loading equip-
          ment with telescoping tube and necessary docking
          facilities                                             1,500,000
                           Total Other Facilities & Equipment   $6,716,000
                                174

-------
SUMMARY OF CAPITAL COST:
      Raw Coal Storage and Handling
      Preparation Plant
      Other Facilities and Equipment
      Contingency (Interest during construction, etc.)
                             Total Capital Requirement
$ 1,418,000
  3,762,000
  6,716,000
  1,785,000
$13,681,000
BASED UPON THE 1000 TON PER HOUR INPUT TO THIS PLANT THE CAPITAL
REQUIREMENT TRANSLATES TO $13,70.0. PER TON HOUR INPUT
                                  175

-------
     5.2.2 Capital Amortization

     Based upon the rationale developed in Section 4.0, the capital

amortization for Example 2 is as follows:

       Total  Capital  Required:  $13.7 Million

       Capacity:

           Raw Coal Input - 1000 tph

           Clean Coal  Output - 714



                          CAPITAL AMORTIZATION


                                                % Utilization
Amortization Period & Basis
10 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
15 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
30%
$0.80
$1.12
$0.64
$0.90
40%
$0.59
$0.83
$0.48
$0.67
       5.2.3 Operating and Maintenance Costs

       The operating and maintenance costs summarized in the following

Table  5-11 are based upon:

       o  Raw Coal Input of 1000 Tons Per Hour

       o  Clean Coal Output of 714 Tons Per Hour

       o  Btu Recovery of 96,4%

       o  10 Year Amortization Period

       o  30% Utilization 2,600 Operating Hours Per Year
           out of a Possible 8,760 Hours or 13 Hours Per Day for 200
           Days Per Year.  (Although this is low, this rate is applied
           in order to be more consistent with the actual experience
           during the period over which the cost data was collected.)
                                   176

-------
                                TABLE  5-11

                 EXAMPLE 2 - JIG PROCESS - INTERMEDIATE

                      OPERATING AND MAINTENANCE COSTS


                                               Per Ton        Per Ton
COST CATEGORY                                  Raw Coal      Clean Coal
     Labor -

         Supervisory (Non-Union)                $0.039        $0.054

         Operating & Maintenance (Union)         0.464         0.650

     Overhead -

         Includes Training Wages, Welfare Fund,
           Payroll Taxes, Workmen's Compensa-
           tion, etc.                            0.211         0.296

     Supplies -

         Operating - Water Conditioners,
           Flocculants, Electric Repairs &
           Parts, etc.                           0.141         0.198

         Maintenance - Replacement Parts, etc.   0.183         0.256

     Fuel and Power -                            0.233         0.326

     Refuse Expense -

         In house and purchased services
          associated with refuse disposal such
          as truck parts, maintenance, etc.      0.132         0.185

     Thermal Dryer Fuel - Based Upon 4.7
         Tons/Hr. Coal Consumption & Cost
         of Coal $20/Ton.                        0.094         0.132

     Miscellaneous Expense - Repair & Main-
         tenance Items Not Normally Inventoried
         or Requiring Outside Subcontract Svcs.  0.321         0.449

0 & M Cost -
  Not Including Capital Amortization            $1.82         $2.55
Capital Amortization
  10 Yrs. - 30% Utilization                      0.80          1.12

Total  Operating & Maintenance Cost              $2.62         $3.67
Cost Per Million Btu (12,079 Btu/lb)                          $0.152
                                   177

-------
5.2.4  Discussion of Performance and Cost
       The Example 2 plant is representative of many jig circuits
currently in existence which can achieve a substantial reduction in ash
and some sulfur removal with certain coals.   As presented in Table 5-7,
this plant recovers, an almost unbelievable, 96% of the Btu content in
the raw feed.  Looking at the washability data in Table 5-8, there
appears to be a fairly clear separation at 1.60 specific gravity which
could theoretically be effected by a jig.  However, the reprocessing of
the middlings from the jig seems to be increasing the weight yield and
thus Btu recovery, but degrading the quality of the final product.
Obviously, the manner in which a plant is operated at any given time
is  influenced by the economic realities of the clean coal specification
the operator must meet.
       As presented in Table 5-11, the total operating and maintenance
cost, including capital amortization, is $3.67 per ton of clean coal.
On  the basis of a nearly 7% moisture clean coal having 12,079 Btu/lb,
this equates to $0.152 per million Btu.  If a cost penalty is assessed
against the process for the limited Btu loss (3.6%), the total cost
of  preparation would increase by $0.029 to $0.181 per million Btu.
       Using the performance of this plant with this particular coal
as  an example, processes of this general type can produce a fairly good
quality coal at a reasonable cost.  This cost is quite sensitive to the
amount of thermal drying required and whether or not the plant can be
kept operating for significant periods of the year.  As presently oper-
ating, this plant is drying almost 40% of the total production which
                               178

-------
greatly impacts electricity consumption and maintenance expense.  Further,
the presence of the dryer adds personnel and increases capital require-
ments by 20%.  Currently, the plant is barely operating 30% of the time
which keeps the capital amortization at an artifically high level.  If
the plant could be operated an additional 10% of the year, a savings of
$0.30 per clean ton could be realized from capital amortization alone;
not to mention the favorable impact on other fixed charges.
       The cost data presented in the foregoing tables is intended to
give the reader insight regarding the capital and 0 & M costs which are
required to establish and run a plant of this general make-up and capacity.
When plants of this type are properly applied, efficient cost-effective
results can be achieved which yield a product having cost saving benefits
at the user level.  These benefits include lower transportation, ash
disposal, and maintenance costs, as well as limit the required particulate
and FGD emission control capacity.  As mentioned elsewhere, these bene-
fits can be quantified on a site specific basis and go to improve the
overall economics of coal preparation.
                                   179

-------
5.3  Example 3 - Jig Process - Intermediate
     5.3.1  General Description
     Preparation plants utilizing the Baum type jig as the major cleaning
vessel  can turn out an acceptable product at an attractive price with a
variety of coal seams.  Plants employing the jig can be combined with a
myriad of other equipment combinations to make for increasingly complex
cleaning circuits.  The particular plant discussed herein is referred to
as "intermediate" since in addition to the jig, several other pieces of
equipment aid the cleaning process, thus further improving the quality
of the clean coal product.
     In this plant, 18 inch X 0 raw coal, mined mostly by continuous
mining, is conveyed at the rate of 1,050 tons per hour from the open
raw coal storage area to scalping screens where the 4 inch X 0 material
is separated to by-pass the rotary breaker as shown on the -flow sheet,
Figure 5-3.  The plus 4 inch material goes to a rotary breaker with
4 inch openings in the screen plates.  That material  which does not
fracture to 4 inches  or less passes through the refuse end of the breaker
and goes to a rock bin for disposal.  Approximately 50 tph of rock and
other debris are removed by the rotary breaker.
     The 4 inch X 0 material is fed to two eight cell Baum type jigs at
the rate of 1000 tph.  Of this amount, 636. tph "floats" out of the jigs
and passes over fixed screens ahead of 8 X 16 foot double deck clean
coal  screens for sizing and dewatering.  The 4 X 1-1/4 inch material passing
over the top decks of these screens goes to a crusher where it is  reduced to
1-1/4 inch or less before being conveyed to the 10,000 ton capacity con-
crete clean coal silo.  Passing over the lower decks is the 1-1/4 X 1/4
                                  180

-------
                                             FIGURE 5-3
                           EXAMPLE 3 - JIG PROCESS -  INTERMEDIATE
                                  PREPARATION PLANT FLOW SHEET
SPIRAL CLASSIFIERS   I   30 TPH

-------
inch material which goes to centrifugal dryers where the surface moisture
is reduced from about 16.5% to less than 5% before being conveyed  to  clean
coal storage.  The 1/4 inch X 0 material passing through both decks of
the 8 X 16 foot clean coal screens goes to a primary cyclone sump  from
which it is pumped to a bank of classifying cyclones where further sizing
into 150 mesh X 0 and 1/4 inch X 150 mesh is effected.  The 1/4 inch  X 150
mesh underflow from these cyclones is distributed over double deck Deister
tables to separate some of the refuse which was not removed by the jigs.
     The refuse from the tables goes to a spiral classifier where  the
material is partially dewatered to aid disposal.  The clean coal from  the
tables goes to Vor-Sivs for dewatering.  The coarser material (1/4 inch X
28 mesh) leaving the Vor-Sivs is centrifugally dried to bring the  surface
moisture down to less than 10% before being conveyed to the fluid-bed
thermal dryer.  The finer material (28 mesh X 0) leaving the Vor-Sivs
goes to a secondary cyclone sump.  This same sump is also fed by the  150
mesh X 0 overflow from the classifying cyclones.
     From the secondary cyclone sump, a 28 mesh X 0 coal slurry is fed at
the rate of 94 tph to hydrocyclones where a separation into clean  coal and
refuse occurs.  The 40 tph of overflow from these cyclones goes to the 180
foot diameter static thickener and the 54 tph of underflow goes to the 10
foot six inch, ten disc vacuum filters for partial dewatering before  going
to the thermal dryer.  The filters reduce the surface moisture of  the  28
mesh X 0 coal to around 20%.
     The total feed to the fluid-bed dryer is 202 tph of 1/4 inch  X 0
coal having a total surface moisture of approximately 15%.  Following
drying, the surface moisture is close to 5%.
                                  182

-------
     Of the 1000 tph being fed  to  the jigs,  566  tph of  1-1/4  inch  X  0
with a surface of moisture of around 5% is considered clean coal.  This
equates to a 56.6% weight yield.
      The material  ejected from all three compartments of the eight cell
jigs is considered refuse and goes to 7 X 16 foot double deck refuse
screens for dewatering.  The larger material passing over both decks
goes to the refuse bin for disposal with the finer material going as
a slurry to the spiral classifiers for thickening.
      With the  aid  of modern  electronic  monitoring and controls,  this
 plant is  operated  and maintained by the personnel as  presented in  Table
 5-15.   A plant of  this general  make-up  could be  constructed at a capital
 cost of $12.1  million in terms  of mid-1977 dollars.   Table 5-16 gives  a
 breakdown of  this  cost by major component.
      The operating and maintenance costs are summarized in Table 5-17.
                                   183

-------
        Raw  Coal  Feed  To  Plant;
        Size  Fraction           Tph
        4 Inch X 0             1000
                                                       TABLE 5-12

                                            EXAMPLE  3  -  JIG PROCESS -  INTERMEDIATE

                                              PREPARATION  PLANT PERFORMANCE*
 Surface
Moisture %
                                     4.5
                                                   Btu/lb
               8,908
                           Ash %
                               35.97
                           Pyritic
                            Sulfur
                             3.01
                                   Total
                                  Sulfur
                                     4.30
co"       Clean  Coal  Product From Plant:
1-1/4 Inch X 0

1-1/4 X 1/4 Inch
1/4 Inch X 0

            Total
46
318
202

3.7
4.5
5.1

12,745
13,242
12,833
11.06
9.0
11.41
                               566
4.6
       Moisture & Ash  Free Btu --  14,511 Btu/lb
13,056
10.03
                                              2.87
4.64

4.30

3.83

4.16
       Net Performance:

            Weight Yield 56.6%
                               Btu  Recovery 83.0%
       *Btu, Ash & Sulfur Presented on Dry Basis
                     3ut of Clean Coal with 4.6% Moisture  12,455  Btu/lb

-------
                                                     Table 5-13
                                        EXAMPLE 3 - JIG PROCESS INTERMEDIATE

                                 Composition of Assumed Plant Feed By Size Fraction
00
CJ1

Size Fraction
4 Inch X 2 Inch
2 Inch X 1 Inch
1 Inch X 1/2 Inch
1/2 Inch X 1/4 Inch
1/4 Inch X 8 Mesh
8 Mesh X 14 Mesh
14 Mesh X 0

Btu/lb
3,492
7,160
9,821
11,122
10,688
9,992
9,069

Ash %
70.03
46.99
30.59
22.48
24.97
28.04
33.88
Pyritic
Sulfur %
3.89
3.19
2.49
2.51
2.51
5.91
2.98
Total
Sulfur %
4.37
4.24
3.87
4.02
3.97
7.43
4.67

% Weight
11.1
18.0
21.6
19.4
12.2
4.9
12.8

% Cumulative Wt.
11.1
29.1
50.7
70.1
82.3
87.2
100.0
        *Btu, Ash, & Sulfur Presented on  Dry Basis

-------
                                                 TABLE  5-14
                                   EXAMPLE 3 - JIG PROCESS - INTERMEDIATE
                            CUMULATIVE WASHABILITY DATA OF ASSUMED PLANT FEED'
                           Composite Of 4 Inch X  14 Mesh Fraction - 87.2% of Feed'
                                                                           **
CO
cr>
Specific Gravity
of Separation
FLOAT 1.30
1.30- 1.35
1.35- 1.40
1.40- 1.50
1.50- 1.60
1.60- 1.70
1.70- 1.80
SINK- 1.80
Recovery
Weight
19.46
43.91.
53.07
59.43
61.93
63.14
63.94
100.00
%
Btu
30.9
68.7
82.1
90.8
93.8
95.1
95.9
100.0
Btu/lb
14110
13907
13747
13577
13464
13387
13321
8884
Ash %
4.44
5.61
6.57
7.60
8.28
8.75
9.15
36.28
Pyri ti c
Sulfur %
.59
1.07
1.50
1.89
2.08
2.17
2.22
3.01
Total
Sulfur %
2.56
2.99
3.39
3.74
3.91
3.99
4.04
4.25
      *Btu, Ash, & Sulfur Presented on Dry Basis
       12.8% is 14 Mesh X 0 Containing 9,069 Btu Per Pound, 33.88% Ash, 2.98% Pyritic Sulfur,  and 4.67%  Total  Sulfur
**

-------
                          TABLE 5-15

          EXAMPLE 3 - JIG PROCESS  - INTERMEDIATE
   PREPARATION PLANT OPERATING & MAINTENANCE PERSONNEL
General  Non-Union Management
Preparation Manager (1/4 time) -
General  Foreman
Operating Shift (Two per day)
    Ti tle                   Union Classification
                                    NU*
Foreman
Plant Operator
Electri cian
Mechani c
Mobile Equipment Operator
  (Dozer,Front End Loader,
   and Refuse Truck Driver)
Weider
Stationary Equipment Operator
  (Thermal Dryer Operator)
Repairman Helper (Greaser)
Utility Man

Maintenance Shift
Foreman
Electrician
Mechanic
Mobile Equipment Operator
Utility Man

Personnel  Summary
General Management
Operating Shifts
Maintenance Shift
*NU-Non-Union
                                    4-E
                                    4-A
                                    4-C

                                    3-A
                                    4-D

                                    3-C
                                    2-F
                                    1-H
                                    Total

                                    NU*
                                    4-A
                                    4-C
                                    3-A
                                    1-H
                                    Total
Quantity
   1
   1

Quantity
   1
   1
   1
   2

   4
   1

   1
   1
   2
  14

   1
   1
   3
   1
   2
   8

   2
  28
   8
                                    Total
                                                      38
                               187

-------
                              TABLE 5-16
               EXAMPLE 3 - JIG PROCESS - INTERMEDIATE
               PREPARATION PLANT CAPITAL REQUIREMENTS

RAW COAL STORAGE AND HANDLING:
      Raw Coal Storage Area
          20,000 ton capacity with reclaiming feeders
          and tunnel                                                  $300,000
      Raw Coal Belt To Scalping Tower
          48 Inch Wide - 200 feet at $560 per ft.                      112,000
      Scalping Tower
          Including Single Deck Vibrating Screen,
          Rock Bin, and Structural Work for Rotary Breaker             350,000
      Rotary Breaker -
          10 Ft diameter - 12 ft. long                                 150,000
      Raw Coal Belt To Plant
          48 Inch Wide 300 feet at $560 per foot                       168.000
                             Total Raw Coal Storage & Handling Cost $1,080,000
PREPARATION PLANT:
      Equipment Cost -
          Eight Cell Baum Jigs
            2 @ $176,000 each                               $ 352,000
          8 X 16 Foot Double Deck Vibrating Clean Coal
            Screens -40 $36,000 each                        144,000
                               188

-------
          7  X  16  Foot  Double  Deck  Vibrating Refuse Screens  -
            2 @ $30,500 each                                $  61,000
          Clean Coal Crusher  - 1                               33,000
          Centrifugal  Dryers  - 5 @ $28,200  each               141,000
          Classifying  Cyclones - Ceramic lined
            12 @  $3,800 each                                   45,600
          Deister Tables -  13 Double Deck  0
            $21,000 each                                      273,000
          Vor-Siv -40 $17,000 each                           68,000
          Hydrocyclones - 20  0 $1,700 each                     34,000
          Clean Coal Vacuum Disc Filter
            1 - 10'6"  ten disc                                120,000
          Spiral  Classifiers  - 36  Inch Diameter
            2  0 $18,000 each                                   36,000
          Primary Cyclone Sumps  -20 $10,000 each            20,000
          Secondary Cyclone Sumps  -  2 0  $10,000  each           20,000
          Pumps                                               100,000
            Total Preparation Plant  Equipment Cost         $1,447,600
      Total  Cost  of Preparation  Plant
          Including Site  Preparation, Construction of
          Building, Electrical  Service,  Piping,  etc.
          $1,447,600 X 3.0                                             $4,342,800
OTHER FACILITIES  & EQUIPMENT:
      Fluid-Bed  Thermal  Dryer
          Complete with  structural steel,  motors, motor
          controls, wiring,  piping,  field  erection, and
          start-up service                                             $2,100,000
                                 189

-------
      Static Thickener
          180 feet @ $2,000 per foot
      Refuse Belt
          36 Inch Wide - 150 feet @ $480 per foot
      Refuse Bin
          Fabricated Part
      Refuse Handling Equipment
          2 - Dozers @ $150,000 each
          1 - Front-End Loader @ $50,000
          2 - Trucks @ $75,000 each
      Coal Sampling System
      Clean Coal Silo
          10,000 Ton Capacity at $110 per ton
      Clean Coal Belt To Silo
          42 Inch Wide - 200 feet at $520 per foot
      Unit-Train Loading Facility
          Total Other Facilities & Equipment
SUMMARY OF CAPITAL COST:
      Raw Coal Storage and Handling
      Preparation Plant
      Other Facilities and Equipment
      Contingency (Interest during construction, etc.)
                                  Total Capital Requirement
$   360,000

     72,000

     50,000

    300,000
     50,000
    150,000
    300,000

  1,100,000

    104,000
    500,000
$ 5,086,000

$ 1,080,000
  4,342,000
  5,086,000
  1,576,000
$12,084,000
BASED UPON THE 1000 TONS PER HOUR INPUT TO THIS PLANT  THE  CAPITAL
REQUIREMENT TRANSLATES TO  $12.100 PER TON HOUR INPUT
                                   190

-------
      5.3.2  Capital  Amortization
      Based  upon  the rationale developed in Section 4.0, the capital
  amortization  for Example 3 is as follows:
        Total Capital  Required: $12.1 Million
        Capacity:
            Raw Coal  Input - 1000 tph
            Clean Coal  Output - 566 tph
                          CAPITAL AMORTIZATION
                                                % Utilization
Amortization Period & Basis
10 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
\
15 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
30%
$0.71
$1.25
$0.57
$1.00
40%
$0.53
$0.93
.$0.42
$0.74
      5.3.3  Operating and  Maintenance  Costs
      The operating and maintenance costs  summarized  in  the  following
Table 5-17 are based upon:
      o  Raw Coal  Input of  1000 Tons Per Hour
      o  Clean Coal  Output  of 566  Tons  Per Hour
      o  Btu Recovery of 83%
      o  10 Year Amortization Period
      o  30% Utilization 2,600 Operating  Hours Per Year
           out of  a Possible  8,760 Hours or 13  Hours  Per Day for 200
           Days  Per  Year.   (Although this  is low, this rate  is applied
           in  order  to  be more  consistent  with  the actual experience
           during  the period  over which the cost data was collected.)
                                    191

-------
                                TABLE 5-17

                 EXAMPLE 3 - JIG PROCESS - INTERMEDIATE

                      OPERATING AND MAINTENANCE COSTS

                                               Per Ton          Per  Ton
COST CATEGORY                                  Raw Coal       Clean Coal

     Labor -

         Supervisory (Non-Union)                $0.054          $0.095

         Operating & Maintenance (Union)         0.428           0.757

         Includes miscellaneous salaries for
           watchmen, etc.

     Overhead -

         Fringe Benefits - 26% Non-Union         0.014           0.025
                         - 22%     Union         0.094           0.167

         Other - Includes Welfare Fund,
           training costs, etc. (15% of
           total labor)                          0.072           0.128

     Supplies -

         Includes water conditioners, re-
           placement parts, lab supplies,
           health & safety expenses, neces-
           sary equipment rental, etc.           0.538           0.950

     Fuel and Power -                            0.170           0.301

     Thermal Dryer Fuel -
       Based upon 3.4 Tons/Hr Coal Consumption
       and Cost of Coal $20/Ton                  0.068           0.120

     Miscellaneous - Subcontract Services, etc.  0.076           0.127

     0 & M Cost -
       Not Including Capital Amortization       $1.51           $2.67

     Capital Amortization -
       10 Yrs. - 30% Utilization                 0.71            1.25

     Total Operating & Maintenance Cost         $2.22           $3.92
     Cost Per Million Btu  (12,455 Btu/lb)                        $0.157
                                  192

-------
5.3.4 Discussion of Performance  and  Cost
     This Example 3 plant is essentially a coarse cleaning process de-
signed for the purpose of reducing ash.  However, following the initial
separation in the Baum jig, the finer size fractions (less than 1/4 inch)
of "float" from the jig are classified and subjected to additional clean-
ing by Deister tables and cyclones.  This secondary cleaning has a
favorable impact on further reducing ash as well as lowering the pyritic
sulfur content which is relatively high in the smaller size fractions.
Although this plant does not effect a dramatic reduction in sulfur, it
is achieving its design objective of significantly reducing the ash in
the particular coal currently being treated.  Some consideration is
being given to a plant modification which would increase the capacity of
the finer cleaning portion of the circuit and promote further pyritic
sulfur removal.
     With the coal  now being treated, this plant recovers approximately
56% of the raw feed by weight and only 83% of the heat content. Greater
Btu recovery from this particular coal could probably be achieved by
crushing the larger size fractions from the jig and further treating
them in an expanded version of the finer cleaning portion of the circuit.
However, this would involve additional capital expenditures not necessarily
appropriate at this time since the company is meeting their contractual
product specification as is.  Before taking such a step, careful analysis
would have to be performed to determine whether further upgrading of the
product would show economic advantage to the producer as well as provide
the purchaser with a product still having the required characteristics
critical to the particular combustion application.

                                  193

-------
     Under current procedures, this plant is scheduled to function three
shifts per day, five days per week with two shifts operating and one for
maintenance.  However, because of unscheduled stoppages and other
recurring problems, this plant has not been running coal more than the
equivalent of 2600 hours per year or roughly 30% of the time.  Limited
utilization has a negative cost impact upon overall plant operating cost
since fixed charges such as capital amortization, management, certain
overhead expenses, etc. are still incurred even though the plant is
functioning well below capacity.  This point is made by the fact that
if this plant could be utilized an additional  10% of the time, the
capital amortization per ton of clean coal would decrease by $0.32.  If
this were true, the 0 & M cost per ton of clean coal would drop from $3.92
 to $3.60 before accounting for the Btu loss from cleaning.
     Another aspect of this plant which contributes significantly to
its operating and maintenance cost is the thermal dryer.  Although it
only dries 36% of the total clean coal product, it nearly doubles the
electricity consumption, adds personnel, and accounts for 20% of the
 capital  cost  of the entire facility.   In  spite  of  the  high  cost of thermal
drying, a good case can manytimes be made for its use on the basis of
lower handling and transportation expenses, not to mention the moisture
specification required by the purchaser.
      As  summarized in the preceding  Table 5-17, the  total  O&M cost of
 $3.92 per ton of clean coal  translates to $0.157 per million Btu.   To
 this,  an amount of $0.172 per million Btu can be added to account for the
 27%  of the heat content in the raw coal  "lost"  during  the cleaning process.
 If this  were  done, it would more than double  the cost  of preparation,
                                   194

-------
bringing the total to nearly $0.33 per million Btu.  This is a stiff
penalty to "pay" for having thrown away a low Btu material high in ash
and sulfur.  There is much room for discussion on whether it is approp-
riate to assess such a high price to this refuse and thus more than
double the effective cost of coal preparation to the producer.  However,
in this particular case, where the Btu recovery is only 83%, it does
accentuate the need to analyze the process to see if greater recoveries
are not possible through alternate cleaning approaches.
     Although the Example 3 process when applied to this coal  is  quite ex-
pensive considering the results achieved, it is representative of many plants
currently in existence which are profitable since the material  produced
is capable of selling for more than the raw coal  plus the cost of clean-
ing including a return to the producer.  However,  the producer's  cost is
not the end-of-the-line when evaluating the overall  economics  of  coal
preparation to determine whether or not the process  is cost effective.
This is true since the producer's cost as presented in Table 5-17 makes
possible a product which has measureable cost benefits to the  user.
When these benefits such as lower transportation,  ash disposal, etc.  are
quantified, they can be set off against the producer's cost to  determine
the net cost of cleaning.  These cost benefits are not addressed  further
at this point since they can only be accurately quantified on  a site
specific basis knowing such things as the distance between the coal  source
and the user.
                                  195

-------
5.4 Example 4 - Jig Process - Complex
     5.4.1 General Description
     As  indicated by the simplified  flow sheet presented as Figure  5-4s
 this particular coal preparation process is comprised of a coarse
 circuit  where  the major separation is made by a single eight-cell Baum
 jig and  a  fine coal circuit centered around two Batac jigs.  Based  upon
 an input to  the plant  (following rough scalping) of 1600 tons per hour
 (tph), the weight yield is  59.6% and the Btu recovery is over 90%.  As
 is indicated by these  results and the sulfur reduction data given in
 Table  5-18,the combination of these  two circuits performs an effective
 and efficient  cleaning job on this Lower Freeport seam coal which is
 mined by continuous and longwall mining.
      Raw coal  is  fed from the mining areas via 54 inch wide belts at
 the rate of  1650  tph to 6 x 16 foot  scalping screens where the plus 4 inch
 material is  screened off and  routed  to refuse.  The 4 inch x 0 material  pass-
 ing through  the scalping screens goes to surge bins ahead of 8 x 20 foot raw
 coal  screens.  When the plant is not operating, the 4 inch x 0 materiel
 goes  to  a 12,000  ton open coal storage area from which it is reclaimed
 as required.
     The inclined 8 x  20 foot double deck raw coal screens separate the
 1600 tph of  material into three size fractions.  Material of 2 inches or
 more passes  over  the top deck and goes to refuse at the rate of 112 tph.
 The 2 x  3/4  inch  material passing over the second deck is fed to the Baum
 jig via  a  36 inch belt at the rate of 253 tph.  The l,235tph of 3/4 inch x  0
 passing  through both decks drops on  a 48 inch wide belt and is fed  to
 the two  Batac jigs.
                                     196

-------
   FROM

MIMING AREAS ^-x 1650 TPH
              FIGURE  5-4
EXAMPLE 4 - JIG PROCESS  - COMPLEX

  PREPARATION  PLANT FLOW SHEET
                                                                   CLEAN COAL
                                                                 [WATERING SCREENS
                                                                           2.X 3/4 In  16 TPH

-------
     Of the 253 tph going to the jig, 63 tph "floats" and 190 tph
passes out the bottom of the three compartments as refuse.  The 63
tph of 2 inch and less coal  goes to 6 x 16 foot double deck clean coal
screens for sizing and dewatering.  The top deck has screen with 3/4 inch
openings and the bottom deck 1/4 inch openings.  Therefore, the 2 x 3/4 inch
material with a surface moisture of approximately 2.4% passes over the
top deck and is fed directly to the clean coal  collection belt.   The
3/4 x 1/4 inch material passing over the second deck goes to centrifuges for
further dewatering before going to the clean coal  belt.   The 1/4 inch x 0
material passing through both decks goes to a sump from which it is
pumped as a slurry to sieve bends ahead of 7 x  16  foot single deck dewatering
screens.  All plus 28 mesh material passing over the screens goes to centri-
fuges and onto the clean coal belt.  The 28 mesh x 0 material  passing
through the screens goes to a sump from which it is pumped to 10 inch
rubber lined thickening cyclones for further dewatering.  The overflow
(all measurable material) from these cyclones goes to the two 150 foot
diameter concrete thickeners.
     The 190 tph of refuse from the Baum jig goes to 6 x 16 foot single deck
screens for sizing and partial dewatering.  The 2 inch x 28 mesh material
passing over the screens has a surface moisture of around 3% and goes
direct to the refuse belt.  The small amount (4 tph) of 28 mesh x 0 material
passing through the screens goes to a sump from which it is pumped to
thickening cyclones and then to solid bowl centrifuges to get the sur-
face moisture down to 18% before going to the refuse belt.
                                  198

-------
     Returning to the fine coal cleaning portion of the plant, the two
Batac jigs are fed 3/4 inch x 0 material at the rate of 1235 tph (roughly 600 tph
each).  Batac jigs come in 3, 4, and 5 meter widths.  As a general sizing
philosophy, each meter of width equates to 100 tph of feed capacity.  However,
this may be exceeded to some degree, as is the case of this plant, without
significant degradation in performance.  Of the total feed to the Batac
jigs, 890 tph separate out as clean coal and 345 tph are refuse.  The clean
coal is fed to fixed sieves ahead of 7 x 16 foot single deck screens
for sizing and partial dewatering.  The 685 tph of 3/4 inch x 28 mesh
material passing over the screens goes to fine coal centrifuges where
the surface moisture is brought down from 25% to 6.5% before going to
the fluid-bed thermal dryers.  The 205 tph of 28 mesh x 0 material passing
through the screens goes to a sump from which it is pumped to classify-
ing cyclones  (14 inch ceramic lined).  The 100 mesh x 0 overflow from these
cyclones go to the static thickeners.  From the thickeners, it is pumped
to  vacuum disc filters for dewatering before going to the thermal dryers.
The 28 mesh X 0 underflow goes directly to the disc filters and then on to
thermal drying.  In this circuit there is a total of four 12 disc vacuum
filters.  Each disc is 12 feet 6 inches in diameter.  The total feed to
these filters is 223 tph.  These filters have been sized on the basis of
50  pounds per hour per square foot of disc surface.  Therefore, the
following calculation applies:
          Weight Being Processed:
            223 tons/hour = 446,000  pounds/hour
          Surface  Required:
            446,000 pounds/hour  _ g
                               i)
              50 pounds/hour/ft
                                   199

-------
          Available Surface:
            4 filter x 2736 ft2 = 10.944 ft2
This additional 2,000 ft  of available filtering surface allows for
substantial fluctuations in feed without overburdening the  equipment.
     A total of 894 tph of 3/4 inch x 0 material is fed to  the two thermal
dryers each having a capacity of 550 tph.  The surface moisture is re-
duced from over 11% to around 6% by the dryers.
     The 300 tph of refuse from the Batac jigs goes to inclined single
deck fixed screens which the majority of the material (310  tph) passes
over before being further dewatered by centrifugal dryers.  The efflu-
ent from these dryers and the 28 mesh x 0 material passing  through the
refuse screens go to a sump from which they are pumped to thickening cy-
clones (14 inch rubber lined) where they are partially dewatered•.  All meas-
urable solids report to the underflow of these cyclones and go to solid-bowl
centrifuges for further dewatering before going to the refuse belt.
Overall plant performance is summarized by Table 5-13.
     This plant is operated and maintained by the staff set forth in
Table 5-22.  In addition to a high degree of semi-automated electronic
controls, smooth operation of the plant is aided by a closed-circuit
television monitoring system.
                              200

-------
ro
o
                                                    TABLE 5-18


                                         EXAMPLE 4 - JIG PROCESS - COMPLEX


                                           PREPARATION PLANT PERFORMANCE*
      Raw Coal Feed To Plant:
Size Fraction
4X2 inch
2 X 3/4 inch
3/4 inch x 0
Total
Tph
112
253
1,235
1,600
% of
Feed
7.0
15.8
77.2
100.0
Surface
Moisture %

-
-
5.0
Btu/lb
1,250
4,444
10,700
9,050
Ash %
85.32
66.21
28.98
38.81
Total
Sulfur %
0.27
0.51
1.16
1.0
      Clean Coal Product  From Plant:
      2 X 1/4 inch

      3/4 inch x 0
59
894
3.0
6.0
13,401
14,300
13.35
7.9
1.14
0.91
                              953
5.8
14,244
8.24
0.92
      Net  Performance:


             Weight  Yield  59.6%   Btu Recovery  93.7%   Btu  of  Clean  Coal with 5.8% Moisture  13,418  Btu/lb
       *Btu, Ash,  and  Sulfur  Presented On  Dry Basis

-------
                             TABLE  5-19
                 EXAMPLE 4 -  JIG PROCESS  -  COMPLEX
        COMPOSITION OF ASSUMED PLANT FEED BY  SIZE FRACTION
Size Fraction                 Weight %               Cumulative Wt.%
+ 3 Inch                        4.43                      4.43
3X2 Inch                      2.66                      7.09
2 X \\ Inch                     3.49                     10.58
1% X 1 Inch                     5.72                     16.30
1 X 3/4 Inch                    6.50                     22.80
3/4 X 5/8 Inch                  4.48                     27.28
5/8 X 1/2 Inch                  4.00                     31.28
1/2 X 3/8 Inch                  9-09                     40.37
3/8 Inch X 28 Mesh             49.03                     89.40
28 X 100 Mesh                   7.02                     96.42
100 Mesh X 0                    3.58                    100.00
                                    202

-------
                                                     TABLE 5-20


                                          EXAMPLE 4 - JIG PROCESS - COMPLEX



                             COMPOSITION OF ASSUMED FEED TO BATAC JIGS BY SIZE  FRACTION
ro
o
Size Fraction
3/4 Inch X 1/2 Inch
1/2 Inch X 3/8 Inch
3/8 Inch X 1/4 Inch
1/4 Inch X 8 Mesh
8 Mesh X 14 Mesh
14 Mesh X 28 Mesh
28 Mesh X 48 Mesh
48 Mesh X 100 Mesh
100 Mesh X 200 Mesh
200 Mesh X 0
Btu/lb
6,602
9,809
10,683
11,519
12,159
11,806
12,211
12,736
12,445
10,115
Ash %
52.85
34.69
29.39
24.45
20.65
22.52
19.02
15.73
16.98
31.89
Pyritic
Sulfur %
0.45
0.48
0.78 •
0.82
0.91
1.06
1.04
0.95
1.09
0.72
Total
Sulfur %
0.65
0.88
1.06
1.27
1.37
1.55
1.51
1.43
1.61
1.07
Weight %
13.71
9.36
11.31
31.76
11.15
6.37
4.85
3.52
2.39
5.58
Cumulativ<
13.71
23.07
34.38
66.14
77.29
83.66
88.51
92.03
94.42
100.00

-------
                                                      TABLE 5-21


                                         EXAMPLE 4 - JIG PROCESS  - COMPLEX

                             CUMULATIVE WASHABILITY DATA OF ASSUMED  FEED TO BATAC JIGS

                                                                                     *
                           Composite of 3/4 Inch X 200 Mesh Fraction - 94.42%  of Feed
ro
G
Specific Gravity
of Separation
FLOAT 1.30
1.30- 1.35
1.35- 1.40
1.40- 1.50
1.50- 1.60
1.60- 1.70
1.70- 1.80
1.80- 2.00
SINK- 2.00
Weight
35.48
60.03
65.34
69.10
71.08
72.37
73.32
74.94
100.00
Recovery %
Btu
49.8
82.6
89.3
93.6
95.6
96.7
97.4
98.3
100.0
Btu/lb
15,068
14,769
14,666
14,539
14,435
14,344
14,262
14,085
10,734
Ash %
3.69
5.42
6.01
6.73
7.34
7.86
8.33
9.35
28.81
Pyri ti c
Sulfur %
0.22
0.31
0.35
0.39
0.41
0.43
0.45
0.48
0.78
Total
Sulfur %
0.68
0.78
0.82
0.86
0.89
0.91
0.93
0.96
1.17
       "5.58% is 200 Mesh X 0 Containing 10,115 Btu Per pound, 31.89% Ash, 0.72% Pyritic Sulfur, and 1.07% Total Sulfur

-------
                               TABLE 5-22
                   EXAMPLE 4 - JIG PROCESS - COMPLEX
            PREPARATION PLANT OPERATING & MAINTENANCE PERSONNEL

General  Non-Union Management
Preparation Plant Superintendent
Operating Shift (1st)
    Title
Shift Foreman
Electrical Maintenance Foreman
Plant Operator
Electrician
Mechanic
Stationary Equipment Operator -
  (Includes two thermal dryer operators)
Mobile  Equipment Operator
    Dozer & Truck Drivers
Utility Man (Screentnan)
Laborer

Operating Shift  (2nd)
Shift Foreman
Plant Operator
Electrician
Mechanic
Stationary Equipment Operator
Mobile  Equipment Operator
Railroad  Car Loader Operator
Utility Man  (Screenman)
Laborer
Union Classification
NU*
NU*
4-E
4-A
4-C
3-C
-s)
3-A
1-H
1-J
Total
NU*
4-E
4-A
4-C
3-C
3-A
3-E
1-H
1-J
Total
Quantity
1
Quantity
1
1
1
2
3
4
5
1
_2
20
1
1
2
3
4
4
1
1
_2
19
                                     205

-------
Maintenance Shift
Shift Foreman
Electrician
Mechanic
Electrician Helper
Mechanic Helper

Personnel Summary
General Management
Operating Shifts
Maintenance Shift
NU*
4-A
4-C
2-C
2-E
Total
2
2
6
3
_3
16
                                              Total
 1
39
16
56
 *NU-Non-Union
                                 206

-------
                                 TABLE 5-23
                     EXAMPLE 4 - JIG PROCESS - COMPLEX
                  PREPARATION PLANT CAPITAL REQUIREMENTS

RAW COAL STORAGE AND HANDLING:
      Scalping Tower
          Including  Two 6 X 16 Foot Single Deck
          Vibrating  Screens having 15  hp  each                       $  300,000
      Raw Coal Storage Area
          12,000 Ton Capacity with Stacking Tube,
          Reclaiming Feeds, and Tunnel                                250,000
      Raw Coal Belt To Raw Coal Bins
          54  Inch Wide - 300 feet at $600 per foot                    180,000
      Raw Coal Bins
          1,200 Ton Capacity - 5 at $50,000 each                      250,000
      Raw Coal Screens
          8  X 20  Foot  Double  Deck  Vibrating having 30 hp
          5  @ $30,000  each plus installation                          300,000
      Raw Coal Belt To Baum Jig
          36 Inch Wide - 250 feet at $480 per foot                    120,000
      Tramp  Iron Magnet  Over Baum Jig Belt
          Explosion Proof  - Self  Cleaning Type                         20,000
      Raw Coal Belt To Batac Jigs
          48 Inch Wide - 250 feet at $560 per  foot                    140,000
                         Total Raw  Coal  Storage  & Handling  Cost     $1,560,000
                                207

-------
PREPARATION PLANT:
      Equipment Cost -
          Eight Cell Baum Jig
            1 @ $176,000                             $176,000
          6 X 16  Foot Double Deck Vibrating
          Clean Coal Dewatering Screens having  20  hp
            2 @ $23,000 each                          46,000
          6 X 16  Foot Single Deck Vibrating  Refuse
          Dewatering Screens having  15 hp
            2 @ $19,000 each                          38,000
          Sump -  1/4  Inch  X 0  Clean  Coal
            1 @ $10,000                               10,000
          Sieve Bends
            6 Foot  Wide -  5 Foot Radius
            4 @ $4,800 each                           19,200
          7 X 16  Foot Single Deck Vibrating  Slurry
          Dewatering Screens having  15 hp
            2 @ $21,500 each                          43,000
          Centrifugal Dryers
            2 @ $28,200 each                          56,400
          Thickening Cyclones
            14 Inch Diameter w/Rubber Liner
            12 @  $1,300 each                          15,600
          Batac Jigs - 5 Meter Width
            2 (3 $610,000 each                       1,220,000
                                      208

-------
Fixed Sieves
  5 Feet Wide - 3/4 mm openings
  8 @ $4,000 each                         $ 32,000
7 X 16 Foot Single Deck Vibrating Clean
Coal Screens having 15 hp
  8 @ $21,500 each                         172,000
Centrifugal Dryers - Bird 1300
  4 @ $50,000 each                         200,000
Fixed Single Deck Refuse Screens
  2 @ $15,000 each                          30,000
Centrifugal Dryers
  2 @ $28,200 each                          56,400
Sump - 28 mesh X 0 Clean Coal
  5 @ $10,000 each                          50,000
Classifying Cyclones
  14  Inch  Diameter w/Ceramic  Liners
  20  @  $3,000 each                          60,000
Sump - 28 mesh X 0 Refuse
  2 @ $10,000 each                          20,000
Thickening Cyclones
  14  Inch  Diameter y^/Ceramic  Liner
  4 (a $3,000 each                           12,000
Vacuum  Disc Filters
  1.2  Feet  6 Inch Diameter  - 12  Disc
  4 @ $125,000  each                         500,000
                      209

-------
          Centrifugal  Dryers
            Bird  Solid Bowl -  36 X  72 Inch
            2  @ $110,000 each                        $  220,000
          Pumps                                        200.000
           Total  Preparation  Plant  Equipment Cost   $3,176,600
      Total  Cost of Preparation Plant
          Including Site Preparation, Construction of
          Building, Electrical  Service,  Piping,  etc.
          $3,176,600 X 3.0                                         $9,530,000
OTHER FACILITIES & EQUIPMENT:
      Fluid-Bed Thermal Dryers - 2
          Complete with structural  steel, motors, motor
          controls, wiring,  piping, field erection, and
          start-up service                                         $6,000,000
      Static Thickeners - 2
          150 Ft Diameter @  $2,000  per foot                           600,000
      Refuse Belt
          36 Inch Wide - 200 feet @ $480 per foot                      96,000
      Refuse Bin - 200 Ton Capacity
          Fabricated Part                                              50,000
      Refuse Handling Equipment
          2 - Dozers @ $150,000 each                                 300,000
          3 - Trucks @ $ 75,000 each                                 225,000
      Clean Coal Belt From Dryer To Storage
          48 Inch Wide - 400 feet @ $600 per foot                    240,000
                                      210

-------
      Clean Coal  Storage Area
          100,000 Ton Capacity With Reclaiming Feeders
          and Tunnel
      Coal Sampling System
      Unit-Train Loading Facility
                           Total Other Facilities & Equipment
SUMMARY OF CAPITAL COST:
      Raw Coal Storage and Handling
      Preparation Plant
      Other Facilities and Equipment
      Contingency (Interest during construction, etc.)
                                    Total Capital Requirement
$   500,000
    300,000
    500,000
$ 8,811,000

$ 1,560,000
  9,530,000
  8,811,000
  2,985,000
$22.886,000
BASED UPON THE 1600 TONS PER HOUR INPUT TO THIS PLANT THE CAPITAL
REQUIREMENT TRANSLATES TO $14,300 PER TON HOUR INPUT
                                   211

-------
     5.4.2 Capital Amortization
     Based upon the rationale developed in Section 4.0  , the capital
amortization for Example 4 is as follows:
       Total Capital Required:  $22.9 Million
       Capacity:
           Raw Coal Input - 1600 tph
           Clean Coal  Output - 953 tph

                          CAPITAL AMORTIZATION

                                                % Utilization
Amortization Period & Basis
10 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
15 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
30%
$0.84
$1.40
$0.67
$1.12
40%
$0.62
$1.04
$0.50
$0.84
      5.4.3 Operating and Maintenance Costs
      The operating and maintenance costs summarized in the following
Table 5-24 are based upon:
      o  Raw Coal Input of. 1600 Tons Per Hour
      o  Clean Coal Output of 953 Tons Per Hour
      o  Btu Recovery of 93.7%
      o  10 Year Amortization Period
      o  30% Utilization 2,600 Operating Hours Per Year
           out of a Possible 8,760 Hours or 13 Hours Per Day for 200
           Days Per Year.  (Although this is low, this rate is applied
           in order to be more consistent with the actual experience
           during the period over which the cost data was collected.)
                                     212

-------
                          TABLE 5-24

                 EXAMPLE 4 - JIG PROCESS - COMPLEX

                  OPERATING AND MAINTENANCE COSTS

                                                Per Ton         Per Ton
COST CATEGORY                                   Raw Coal       Clean Coal
      Labor -

          Supervisory (Non-Union)               $0.030         $0.050

          Operating & Maintenance (Union)        0.387          0.650
      Overhead -

          Includes Payroll Taxes, Insurance,
           Welfare Fund, Vacations, Holidays,
           etc. for all Preparation Plant
           Employees                             0.250          0.420

      Supplies

          Operating                              0.137          0.230

          Maintenance - Repair Parts and
           Materials Associated with
           Routine Maintenance                   0.273          0.458

      Thermal Dryer Fuel -
          Based upon 17 Tons/Hr Coal Consumption
           and Cost of Coal $20/Ton              0.213          0.357

      Electricity                                0.387          0.650

      Other Expenses                             0.084          0.141

      0 & M Cost -
          Not  Including Capital Amortization    $1.76          $2.96

      Capital Amortization -
          10 Yrs. - 30% Utilization              0.84           1.40

      Total Operating  & Maintenance Cost        $2.60          $4.36
       Cost  Per  Million  Btu  (13,418  Btu/lb)                     $0.162
                                      213

-------
        5.4.4 Discussion of Performance and Cost
        The Example 4 plant is a good illustration of using coarse and
fine coal  jigging to produce a clean coal  product low in ash and sulfur
at a reasonable cost.  Although when treating this particular coal the
process discards over 40% of the plant feed as refuse, it recovers 93.7%
of the Btu content of the raw coal.
        The effectiveness of this process  lies in the initial sizing of
the feed to insure its consistency with the individual equipment capabil-
ities. That is to say, the coarser material  (2X3/4 inch )  is handled by the
Baum jig and the finer material  (3/4 inch X 0)  material is  fed to the
Batac  jigs.  By  restricting the amount of fines getting into the Baum jig,
a more efficient and accurate separation is accomplished.   The Baum jig
effects a  separation at approximately 1.60 specific gravity and recovers
less than  25% of the total material it processes.  This low recovery is
not unexpected since the feed to the Baum  jig is over 66% ash.
        As noted, the fine coal portion of this plant centers around two
Batac  jigs which treat the 3/4 inch X 0 fraction constituting nearly 80% of
the plant  feed. These jigs effect a separation at between  1.70 and 1.80
specific gravity.  Although this means rejecting nearly 30% as refuse,
the high Btu product from the Batacs is significantly lower in ash and
sulfur.
        The number of personnel required to operate and maintain this
plant  is   somewhat higher than might be expected.  However, the incremen-
tal increase in cost over having a more austere staff is not significant
when put on a per ton basis.
                                  214

-------
     As would be expected, the capital amortization of a larger plant
of this type becomes a sizeable cost factor when it is utilized only
30% of the time.  Unfortunately, this plant is operated only two shifts
per day, five days per week with one shift reserved for maintenance.  If
the plant could be operated an additional 10% of the time, the capital
amortization per ton of clean coal could be reduced by $0.36.  Greater
utilization would also favorably impact other fixed charges such as
supervisory salaries and various overhead items.
     Another significant cost in the operation of this plant is the
thermal dryer which handles 94% of the clean coal produced.  The cost
of such extensive drying is reflected not only in fuel expense but par-
ticularly in higher electricity consumption due to the large horsepower
requirements of the two fluid-bed thermal dryers.  However, these high
drying costs are more than justified by lower transportation and handling
expense.
     Looking at the overall performance of the process in terms of the
cost, this plant performs cost effectively when treating this particular
coal.  The material discarded as refuse carried with it only 6.3% of the
original heat content of the feed.  This is a fair "price" to pay for a
significantly higher Btu product with nearly 80% less ash and reasonable
reduction in pyritic sulfur.  If a cost was applied for these lost Btu's
as discussed in Section 4.4, the total cost of preparation would increase
by $0.056 per million Btu to $0.219. Although the total cost of producing
the clean coal is $4.36 per ton without considering any Btu loss, the net cost
                                   215

-------
would be less if consideration was given to the economic benefits
attributable to preparation such as lower transportation, boiler main-
tenance, particulate and other emission controls, etc.   As noted pre-
viously, these are not quantified since their full  impact can only be
appreciated on a site specific basis where such things  as transportation
distance and emission regulations are known.
                                  216

-------
5.5 Example 5 - Heavy Media  Process - Simple
    5.5.1 General Description
    As noted previously, the term heavy media is applied to any pro-
cess which uses a medium having a specific gravity approaching  the
specific gravity of separation.  In coal preparation,  the most  widely
accepted method for establishing the higher specific gravity medium
is to suspend magnetite in water.  The process is based on the  theory
that as the crushed material passes through such a medium, the  coal
will float and the refuse will sink as predicted by laboratory  specific
gravity analysis.
    There are many levels of sophistication which a coal preparation
circuit based principally on heavy media can reach.  Example 5, dis-
cussed herein, is a relatively simple approach which can be quite
effective with certain coals and end product requirements.  A simpli-
fied flow sheet appears as  Figure 5-5 on the following page.
    In this particular circuit,  the 24 inch X 0 run-of-mine coal, mined by
conventional and continuous mining, is conveyed to a grizzly where a
coarse scalping of the SinchXO material takes place.  The plus 6 inch
material passes over the grizzly to a rotary breaker with 6 inch open-
ing grid plates.  All material which is broken down  to  6 inches  or
less passes through the grid plates with the oversized material going
out the refuse end of the breaker to a rock bin where it is trucked
away to the disposal site.  Now,  the GinchXO material from the grizzly
and the breaker passes under a tramp iron magnet as it is conveyed to
a 10,000  ton concrete silo.   The magnet is  intended to  remove  scrap
                                217

-------
                     FIGURE  5-5

EXAMPLE 5  - HEAVY MEDIA PROCESS  - SIMPLE

        PREPARATION PLANT  FLOW SHEET
                                                                                     MAGNETIC SEPARATOR
                                                                      I  4^-*^        I
                                                                      I HEAVV MEDIA SUMP    I     I   !
                                                                      •	—4-—-    \
                                                                                          RINSING SCREENS
350 TPH
                                                                                           REFUSE BELT

-------
steel material such as mining bits, tin cans, and roof bolts which
could be damaging to equipment in other portions of the plant.  From
the raw coal storage silo, the 6inchXO  coal is fed at the rate of 1400
tons per hour to five bins each feeding an 8 X 20 foot double deck
vibrating screen.  The top screen has openings of approximately 1-1/4
inch with the bottom deck 1/2 inch.  By subjecting the coal to a double
screening at this point, better definition  is given to the desired sizing
function by not overloading the surface of the deck.  The 1/2 inch or
less material passing through the bottom deck is considered clean coal
and goes directly to the product collection belts at the rate of 680 tph.
    The material passing over the first and second decks of the raw coal
sizing screen is conveyed at the rate of 720 tph into the main portion
of the preparation plant.  Here it is put onto five 8 X 20 foot double
deck pre-wet screens.  The purpose of this wet screening operation is
to further  remove any fines prior to the material entering the two
heavy media drums.  The limited amount of additional fines passing
through the bottom deck goes to a fixed sieve bend for partial de-
watering with the overflow of the sieve bend going to the centrifuges
for final moisture reduction before going to the clean coal belt.  The
underflow of the sieve bend is considered  refuse and goes to the 90 foot
diameter thickener.
    Approximately 700 tph pass over the pre-wet screens and enter the
two heavy media drums.  The heavy media drums effect approximately a
50-50 separation at around 1.6 specific gravity.  Floats, at the rate
of 350 tph, goto two 8 X 16 foot double deck drain and rinse screens.
                                   219

-------
The major purpose of this screening operation is to rinse off the mag-
netite carried along with the coal from the heavy media drums.  The top
decks have a 1-1/4 inch opening and the bottom 1 mm.  The 210 tph of
6X1-1/4 inch material passing over the top decks is then reduced to 1-1/4
inch by a flextooth crusher to minimize the fines and is conveyed to the
15,000 ton concrete clean coal silo.  The 120 tph of 1-1/4 inch and less
material passing over the lower decks of the 8 X 16 foot rinsing screens
goes to centrigugal dryers before being conveyed to the clean coal silo.
    The 350 tph of sinks from the heavy media drums pass over two 8 X 16
foot single deck drain and rinse screens.  This not only helps to dewater
the material but also salvages some of the magnetite clinging to the
refuse.
    Refuse from the thickener is pumped at the rate of 14 tph to a 10
foot 6 inch diameter 9 disc vacuum filter where it is dewatered and
hauled away for disposal.  This filter is sized according to the sizing
philosophy of 20 pounds of refuse per hour per square foot of disc area
(a 10' X 6" diameter unit with 9 discs, has approximately 1,395 square
feet of surface; 14 ton = 28,000 Ib; 28,000 Ib ~ 20 Ib/sq ft = 1,400 sq
ft).  As observed in some of the other examples considered under this
section, vacuum filters are sized in a range as high as 50 pounds per
hour per square foot depending upon the nature of the material to be
dewatered.  In this particular case, the design was deliberately kept on
the conservative side to produce a filter cake which would be sufficiently
low in moisture to permit immediate disposal.
                                    220

-------
     On a plant wide basis, of the 1400 tph fed from the raw coal
silo, 1,036 tph are considered clean and 364 tph refuse for a weight
yield of 74%.  However, this is somewhat misleading in that nearly
50% of the raw coal feed is screened off as clean coal in the initial
preparation operation.  Therefore, a more relevant indicator of this
circuit's effectiveness is the Btu recovery which approaches 95%.
     Adequate operation and maintenance of the plant is achieved by a
staff of forty union and non-union personnel.  A listing of these in-
dividuals by job classification appears as Table 5-26.  Based upon
mid-1977 costs, the capital investment required to construct a plant
of this configuration  is approximately 10 million dollars.  A break-
down of this capital cost by major component appears as Table 5-27.
A summary of the operating and maintenance costs is presented in
Table 5-28.  Although  these costs will vary somewhat due to site spe-
cific conditions such  as operating approach, current quality of the
raw coal, local labor  problems/availability, etc., they are representa-
tive of the 0 & M cost level one might anticipate for an operation of
this type.
                                     221

-------
                                                     TABLE 5-25

                                        EXAMPLE 5 - HEAVY MEDIA PROCESS - SIMPLE

                                            PREPARATION PLANT PERFORMANCE11
                                    .2]
              Raw Coal  Feed To Plant:
              Size Fraction          Tph


              6 Inch X 0             1400
              Surface
            Moisture 3

               8.0
               Btu/ib

                8,600
               Ash %
               29.4
               Total
              Sulfur

                4.56
IN3
(NO
no
              Clean Coal  Product From Plant:
              1-1/4 Inch X 0
1036
7.5
10,992
22.13
4.17
              Moisture & Ash Free Btu — 14,115 Btu/lb


              Net  Performance:

                   Weight Yield  74.0%      Btu  Recovery 94.6%      Btu of Clean Coal  with 7.5% Moisture 10.168 Btu/lb
              1]  Btu,  Ash,  &  Sulfur  Presented  on Dry Basis

              2]  This  is  somewhat of a  misnomer since nearly half (680 tph) of the total raw coal being processed
                 never enters the plant.

-------
                               TABLE 5-26
                EXAMPLE 5 - HEAVY MEDIA PROCESS - SIMPLE
           PREPARATION PLANT OPERATING & MAINTENANCE PERSONNEL
General  Non-Union Management
Preparation Superintendent
General  Foreman
Operating Shift (Two per day)
     Title
Foreman
Plant Operator
Stationary Equipment Operator -
 (Vacuum filter, thickener, media
  system)
Electri ci an
Screenman  (cleaner)
Utility Man
Repairman  (Belt Mechanic)
Mobile Equipment Operator  (Refuse
  Handling)
     Truck Driver
     Dozer Operator

Maintenance Shift  (One  per day)
Foreman
Mechanic
Repai rman
Utility Man
Mobile Equipment Operator
     Dozer Operator

Personnel  Summary
General Management
Operating  Shifts
Maintenance Shift
Union Classification
        NU*
        4-E
        3-C
        4-A
        1-H
        1-H
        3-B
        3-A
        3-A
        Total


        NU*
        4-C
        3-B
        1-H

        3-A
        Total
                                              Total
Quantity
   1
   1


Quantity
   1
   1

   I
   1
   2
   1
   1
   3
   2
  13

   1
   7
   1
   1

   2
  12


   2
  26
  12
  40
 *NU-Non-Union
                                      223

-------
                                  TABLE  5-27
                 EXAMPLE 5 - HEAVY MEDIA PROCESS - SIMPLE
                  PREPARATION PLANT CAPITAL REQUIREMENTS

RAW COAL STORAGE AND HANDLING:
      Scalping Tower
          Including Single Deck Vibrating Screens,
          Rock Bin, and Structural Work for Rotary
          Breaker                                                   $   350,000
      Rotary Breaker
          10 Foot Diameter - 12 Feet Long                              150,000
      Raw Coal Belt To Silo
          48 Inch Wide - 200 Feet @ $560 per foot                      112,000
      Tramp Iron Magnet
          Explosion Proof - Self Cleaning Type                          20,000
      Raw Coal Silo (Concrete)
          10,000 Ton Capacity @ $110 per ton                        1,100,000
      Raw Coal Belt To Raw Coal Bins
          54 Inch Wide - 150 Feet @ $600 per foot                       90,000
      Raw Coal Bins
          100 Ton Capacity w/Feeders
          5 @ $30,000 each                                             150,000
      Raw Coal Screens
      8 X 20 Foot Double Deck Vibrating having 30 hp
          5 @ $30,000 each plus installation                           300,000
                                     224

-------
      Raw Coal  Belt To Plant
          48 Inch Wide - 250 Feet @ $560 per foot                  $  140,000
                            Total Raw Storage & Handling Cost      $2,412,000
PREPARATION PLANT:
      Equipment Cost -
          8 X 20 Foot Double Deck Vibrating
          Pre-Wet Screens
            4 @ $30,000 each                        $120,000
          Heavy Media Drums
            Wemco - 12 Foot Diameter, 21 Feet Long
            2 
-------
          Crusher
            2  @ $12,100 each                         $   24,200
          Centrifugal  Dryers
            2  @ $28,200 each                             56,400
          Sump - Dryer Effluent
            1  @ $10,000                                 10,000
          Vacuum Disc  Filter
            10 Foot 6  Inch Diameter - 7 Disc
            1  @ $90,000                                 90,000
          Pumps                                         75,000
           Total Preparation  Plant Equipment Cost   $  914,800
      Total Cost of Preparation Plant
          Including Site Preparation, Construction of
          Building, Electrical  Service, Piping, etc.
          $914,800 X 3.0                                           $2,744,400
OTHER FACILITIES & EQUIPMENT:
      Static Thickener
          90 Ft. Diameter @ $2,000 per foot                           180,000
      Refuse Bin - 450 Ton Capacity
          Fabricated Part                                              75,000
      Refuse Belt
          36 Inch Wide - 200  feet @ $480 per foot                      96,000
      Refuse Handling  Equipment
          3 -  Trucks @ $ 75,000 each                                  225,000
          2 -  Dozers @ $150,000 each                                  300,000

                                    226

-------
      Coal Sampling System                                         $  300,000

      Clean Coal Belt

          54 Inch Wide - 300 Feet @ $600 per foot                     180,000

      Clean Coal Silo

          15,000 Ton Capacity @ $110 per ton                        1,650,000

      Unit-Train Load Facility                                        500,000

                             Total Other Facilities & Equipment    $3,506,000

SUMMARY OF CAPITAL COST:

      Raw Coal Storage and Handling                                $2,412,000

      Preparation Plant                                             2,744,000

      Other Facilities and Equipment                                3,506,000

      Contingency (Interest during construction, etc.)              1,300.000

                             Total Capital Requirement             $9,962,000
BASED UPON THE 1400 TONS PER HOUR OF RAW COAL BEING PROCESSED BY THIS PLANT,
THE CAPITAL COST PER TON HOUR INPUT IS QUITE LOW - $7,116.  HOWEVER, SINCE
ONLY 720 TPH IS RECEIVING ANY SIGNIFICANT DEGREE OF CLEANING, THE CAPITAL
COST SHOULD BE BASED UPON THE INPUT TO THE PREPARATION PLANT PROPER WHICH
TRANSLATES TO APPROXIMATELY $13.800 PER TON HOUR INPUT.
                                  227

-------
     5.5.2 Capital Amortization
     Based upon the rationale  developed in Section  4.0, the capital
amortization for Example 5 is as follows:
       Total Capital Required:  $10.0 Million
       Capacity:
           Raw Coal Input - 1400 tph
           Clean Coal Output - 1036 tph
                         CAPITAL AMORTIZATION
                                                % Utilization
Amortization Period & Basis
10 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
15 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
30%
$0.42
$0.56
$0.33
$0.45
40%
$0.31
$0.42
$0.25
$0.34
      5.5.3 Operating and Maintenance Costs
      The operating and maintenance costs summarized in the following
 Table 5-28  are based  upon:
      o  Raw Coal Input of 1400 Tons Per Hour
      o  Clean Coal Output of 1036 Tons Per Hour
      o  Btu Recovery of 94.6%
      o  10 Year Amortization Period
      o  30% Utilization 2,600 Operating Hours Per Year
         out of a Possible 8,760 Hours or 13 Hours Per Day for 200
         Days  Per Year.  (Although this is low, this rate is applied
         in order to be more consistent with the actual experience
         during the period over which the cost data was collected.)
                                228

-------
                                TABLE 5-28

               EXAMPLE 5 - HEAVY MEDIA PROCESS -  SIMPLE

                     OPERATING AND MAINTENANCE COSTS
                                               Per Ton         Per Ton
COST CATEGORY                                  Raw Coal        Clean Coal
     Labor -

         Supervisory (Non Union)               $0.148         $0.200

         Operating (Union)                      0.360          0.487

         Maintenance (Union)                    0.254          0.343
     Overhead -

         Non-Union Benefits - Includes
          Payroll Taxes, Group Life &
          Medical Insurance, Pension Fund,
          etc.                                  0.030          0.040

         Union Benefits - Includes Payroll
          Taxes, Welfare Fund, Vacations,
          Holidays, Clothing Allowance, etc.    0.184          0.249

         Other                                  0.112          0.152

     Supplies

         Operating - Magnetite, Flocculants,
          and clay settler accounts for 22%.*   0.610          0.824

         Maintenance  - Equipment Repair, etc.  0.504          0.681

     Electricity                                0.165          0.223

     0 & M Cost-
         Not Including Capital Amortization    $2.37          $3.20

     Capital Amortization
         10 years - 30% Utilization             0.42           0.56

     Total Operating & Maintenance Cost        $2.79          $3.76
     Cost Per Million Btu (10,168 Btu/lb)                     $0-185
 Consumption of these major additives on each ton of clean coal is:
 Magnetite 1 to 1.5 Ib; Flocculant 0.015 Ib; and clay settler 0.15 Ib.
 When the coal is damp and muddy, consumption is much higher.  On an
 annual basis, their cost averages $0.18 to $0.20 per ton of product.
                                  229

-------
      5.5.4 Discussion  of Performance and  Cost
     Based upon the performance of the Example 5 plant as summarized on
Table 5-25, one has to search for "Why?" the plant is even in existence.
The answer is found in the fact that the current feed to the plant is
substantially different  from that around which the plant was designed.
As originally conceived,  approximately one-third of the raw coal was to
be less than 1/2 inch and be fairly low in ash and sulfur.  However,
recent feed to the plant has been such that nearly half falls below
1/2 inch and contains a much larger percentage of the undesireable con-
stituents  (ash and sulfur).  As a result, the total performance of the
plant is far from impressive and cannot be improved by simply reducing
the openings of the sizing screens since the plant equipment selection
was predicated upon coarser material.  To cope with these changed con-
ditions, an extensive plant modification is being planned which will
include Deister tables treating the 1/2 inchXO fraction.  Although the
anticipated  results from this modification will be a reduction in weight
yield to around 63% it will more than be justified by the quality of the
final product.
      Obviously, this process is not  recommended for treating the  particular
coal  now being  run.  However, a process of this type could very well show
merit when handling a  coal having a  physical  consistency similar  to that
around which  the plant was designed.  Therefore, the purpose of including
this  example  is not only to  fill out  the  spectrum of heavy media  processes
currently  being utilized,  but also show the capital and 0 & M costs of  a
potentially successful process of this  general make-up and capacity. Since
this  plant as  currently  being operated  performs very little actual cleaning,
the  costs  of preparation per ton of  clean product, as presented in the
                                  230

-------
preceeding Table 5-28, are only appropriate if it is assumed that better
operating results will be achieved at a 74% weight yield with another
coal.  However, the costs presented on a raw ton can be used as the basis
for projecting product costs for whatever weight yield the reader feels
is proper for another coal.
                                   231

-------
              EXAMPLE 6 - HEAVY MEDIA PROCESS - COMPLEX
     5.6 Example 6  - Heavy Media  Process  -  Complex
     5.6.1 General  Description
     As shown on the plant flow sheet, Figure 5-6, the major emphasis of
this preparation process is  on the material  of less  than 3/4 inch top size
which  constitutes nearly 80% of the feed  to  the plant.  This high concen-
tration of finer material is the  result of the continuous and  longwall
mining methods  used in  combination with the  friable nature of  the raw coal.
     From the open  raw  coal storage area, the material  is conveyed via  a
42  inch belt to a fixed screen which  passes  coal of 8 inches or  less.
That material greater than 8 inches passes over the screen and is reduced
to  SinchXO by a crusher before  going to a  rotary breaker. In the rotary
breaker, that material  reduced to 2-1/2 inches or less  passes through
the screen plates and drops onto  the  42 inch wide plant feed belt.  Any
larger size  material passes through the refuse end of the breaker and
reports to the  refuse bin.
      Raw  coal 2-1/2 inch  X 0  is conveyed  at  the rate of 600 tph  to two  in-
clined 7  X  16 foot  double deck vibrating  screens.  The  126 tph of 2-1/2 X
3/4 inch material passing over both decks goes to the Barvoy heavy media
vessel. The  474 tph of  3/4 inch X 0 passing  through the screens  reports to
sumps  from where  it is  pumped  to  the  finer cleaning portion of the circuit.
Of the 126  tph  entering the heavy media vessel, 58 tph  are recovered as
clean  coal.  The  balance  (68  tph) sinks as  refuse and goes to  a  4 X  16
foot double  deck  drain  and rinse  screen for  partial dewatering and media
recovery  before dropping  onto  the refuse  belt.  The 58  tph of  2-1/2  X  3/4
inch  "float" from the  vessel  passes over  a  4 X 16 foot  double  deck drain
and rinse screen  whose  major  purpose  is media  recovery.   From  this screen
the material goes to a  crusher where  the  clean coal is  reduced to  1-1/4 inch
X 0 before being  conveyed to  the  thermal  dryer.
                                     232

-------
                                                                  FIGURE 5-6

                                                   EXAMPLE 6  -  HEAVY  MEDIA  PROCESS  - COMPLEX

                                                         PREPARATION PLANT FLOW SHEET
ro
oo
oo
                                                                                                                                          AS SPYING |

                                                                                                                                          CYCLONES
                 I    «______________i_____________--_^^-     i      ft             T   »      •
                                                                                                   DILUTE MEDIA SUHP
                                                                                                 TO HAKE-UP WATER

-------
     Returning to the finer portion of the circuit, the 3/4 inch X 0
material is pumped from the raw coal sumps to sieve bend ahead of six 8  X
16 foot single deck desliming screens at the rate of 503 tph.  Passing over
these screens is 378 tph of 3/4 inch X 1/2 mm (approximately 28 mesh) material
which goes to heavy media cyclones.  The 125 tph of 1/2 mm X 0 material
passing through the desliming screens goes to two banks of four froth
flotation cells.  Of this total, all but 26 tph is recovered as clean coal
and is  partially dewatered by two vacuum disc filters before being conveyed
to the  thermal dryer.  The refuse from the froth cells reports to the 100
foot diameter concrete static thickener from which it is pumped at the rate
of 26 tph to a vacuum disc filter for partial dewatering before being con-
veyed to the refuse bin.
     The 378 tph of 3/4 inch X 1/2 mm material passing over the desliming
screens is handled by six 24-inch diameter heavy media cyclones having
Nihard  liners.  These cyclones recover 308 tph as clean coal overflow which
goes to sieve bends ahead of six 8 X 16 foot single deck screens for partial
dewatering and media recovery.  All but 18 tph passes over these screens
and goes to centrifugal dryers for further dewatering before being conveyed
to the  thermal dryer.  The 18 tph passing through these screens reports to
the dilute media sump. The 70 tph of underflow from the heavy media cyclones
goes to sieve bends ahead of two 6 X 16 foot single deck screens. All but
4 tph passes over these screens and goes directly to the refuse bin. The 4
tph passing through these screens reports to the dilute media sump from which
it is pumped along with the 18 tph of material which passed through the 8 X
16 foot single deck screens to six 20 inch diameter classifying cyclones.
                                    234

-------
   All  22 tph report as underflow in these cyclones and go to double drum
magnetic separators from which the solids are pumped to the 3/4 inch X 0
raw coal sumps for reprocessing by the finer coal portion of the circuit.
     The single fluid-bed thermal dryer handles 440 tph of 1-1/4 inch X 0
material.  Following drying, the clean coal is conveyed via a 42 inch wide
belt to a 10,000 ton concrete silo for storage pending unit-train load-out.
     As shown in Table  5-29, this plant recovers approximately 73% by weight
of the  plant feed having a  heat content of 14,336 Btu/lb.  This translates
to a 89.2% Btu recovery.
     The staff necessary to operate  and maintain this plant is listed
under Table  5-32.  As  summarized  in  Table 5-33,  a plant of this size and
complexity could be  built  for around 13.5 million dollars.
                                    235

-------
ro
                                                     TABLE  5-29
                                     EXAMPLE 6 - HEAVY MEDIA PROCESS - COMPLEX
                                         PREPARATION  PLANT  PERFORMANCE*
          Raw  Coal  Feed  To  Plant:
Size Fraction
2-1/2 X 3/4 Inch
3/4 Inch X 1/2 mm
(28 mesh)
1/2 mm X 0
Clean Coal Product
1-1/4 Inch X 0
3/4 Inch X 1/2 mm
1/2 mm X 0
% of
Feed
21.0
58.2
20.8
100.0
From Plant:



Surface
Tph Moisture %
126
349
125
600 5.0

58
283
99
Btu/lb
8,800
12,600
12,544
11,790

14,200
14,555
13,788
Ash %
41.4
17.2
17.7
22.4

7.8
6.4
10.4
Total
Sulfur %
4.88
4.24
4.27
4.38

2.65
2.00
2.55
                                          440          5.0             14,336         7.48          2.21

         Net Performance:
              Weight Yield 73.3%     Btu Recovery 89.2%   Btu of Clean Coal with  5.0% Moisture  13,619 Btu/lb

         * Btu, Ash, & Sulfur Presented on Dry Basis

-------
                                                    TABLE  5-30
                                    EXAMPLE 6 - HEAVY MEDIA PROCESS - COMPLEX
                             WASHABILITY DATA OF ASSUMED PLANT FEED - 3/4 Inch X 1/2 mm*
                                        Direct Float
ro
GO
Specific Gravity
 of Separation
Float 1.30
1.30- 1.40
1.40- 1.45
1.45- 1.50
1.50- 1.60
1.60- 1.70
1.70- 1.90
SINK- 1.90
                                                                     Cumulative Float
Weight %
61.3
14.6
2.3
1.5
1.7
1.6
1.7
15.3
Ash %
4.0
11.4
17.3
20.3
24.2
31.1
42.0
70.1
Sulfur %
1.21
3.45
6.32
6.40
8.36
8.82
9.56
15.07
Weight %
61.3
75.9
78.2
79.7
81.4
83.0
84.7
100.0
Ash %
4.0
5.4
5.8
6.0
6.4
6.9
7.6
17.2
Sulfur %
1.21
1.64
1.78
1.87
2.00
2.13
2.28
4.24
           * 58.2% of Total  Feed

-------
                                           TABLE  5-31

                            EXAMPLE  6  -  HEAVY MEDIA PROCESS - COMPLEX

               WASHABILITY  DATA  OF ASSUMED  PLANT FEED - 2-1/2 X 3/4  INCH FRACTION*
 Specific  Gravity
 of  Separation
        Direct Float

Height %     Ash %     Sulfur
                                                                     Cumulative  Float
Height %     Ash %     Sulfur %





ro
OJ
CO
Float 1.30
1.30- 1.40
1.40- 1.45
1.45- 1.50
1.50- 1.60
1.60- 1.70
SINK- 1.70
21.5
20.8
2.2
2.1
2.4
2.6
48.4
3.6
10.1
15.7
19.4
24.5
32.9
75.1
1.35
3.20
5.90
7.19
7.73
7.55
6.74
21.5
42.3
44.5
46.6
49.0
51.6
100.0
3.6
6.8
7.2
7.8
8.6
9.8
41.4
1.35
2.26
2.44
2.65
2.90
3.14
4.88
* 21.0% of Total Feed

-------
                                  TABLE  5-32
                  EXAMPLE 6 - HEAVY MEDIA PROCESS - COMPLEX
             PREPARATION PLANT OPERATING & MAINTENANCE PERSONNEL
General  Non-union Management
Preparation Superintendent  (1/2 time)
General  Foreman

Operating Shift (2 per day)
    Title
Foreman
Plant Operator
Electrician
Mechanic
Mobile Equipment Operator
  (Refuse Hauling & Compacting)
Repairman-Helper (Greaser)
Stationary Equipment  Operator
  (Thermal Dryer, Media,  etc.)
Utility Man

Maintenance Shift  (1  per day)
Foreman
Electrician
Mechanic
Repairman
Repairman Helper
Total
Union Classification
NU*
4-E
4-A
4-C
3-A
2-F
3-C
1-H
Total
NU*
4-A
4-C
3-B
2-F
Total
Quantity
1
J^
2
Quantity
1
1
1
2
2
1
2
_2
12
1
1
3
2
_2
9
                                       239

-------
Personnel  Summary
General Management                                                  2
Operating Shifts                                                   24
Maintenance Shift                                                  -i
                                               Total                35
 *NU-Non-Union
                                         240

-------
                               TABLE  5-33
               EXAMPLE 6 - HEAVY MEDIA PROCESS - COMPLEX
                PREPARATION PLANT CAPITAL REQUIREMENTS

RAW COAL STORAGE AND HANDLING:
      Raw Coal  Storage Area
            20,000 ton capacity with reclaiming feeders
            and tunnel                                             $  300,000
      Raw Coal  Belt To Scalping Tower
            42 Inch Wide - 200 feet @ $520 per foot                   104,000
      Tramp Iron Magnet Over Raw Coal Belt
            Explosion Proof, Self-Cleaning Type                        20,000
      Scalping Tower
            Including Fixed Screen and Structural Work For
            Crusher and Rotary Breaker                                250,000
      Raw Coal  Crusher - 1                                             65,400
      Rotary Breaker
            9 Ft. Diameter - 17 Feet Long                             150,000
      Raw Coal  Belt To Plant
            42 Inch Wide - 250 feet @ $520 per foot                   130,000
                         Total Raw Coal Storage & Handling Cost    $1,019,400
 PREPARATION PLANT:
      Equipment Cost -
            7 X  16 Foot Double Deck  Vibrating
            Raw Coal Screens
              2 @ $21,000 each                          $ 42,000
            Heavy Media Vessel
              Barvoy Deep Bath Type                       35,000
                                       241

-------
4 X 16 Foot Double Deck Vibrating
Drain & Rinse Screens
  2 @ $20,500                               $ 41,000
Crusher - 1                                    9,000
Sump - Raw Coal 3/4 Inch X 0
  2 @ $10,000 each                            20,000
Sieve Bends
  6 Feet Wide - 80 Inch Radius
  6 @ $4,800 each                            28,800
8 X 16 Foot Single Deck Vibrating
Desliming Screens
  6 @ $27,000 each                          162,000
Heavy Media Cyclones
  24 Inch Diameter w/NiHard Liner
  6 @ $3,000 each                            18,000
Sump - Heavy and Dilute Media
  5 @ $14,000 each                           70,000
Froth Flotation Cells
  2 Banks of Four Cells                      76,000
Sieve Bends
  5 Feet Wide - 80 Inch Radius
  2 @ $4,000 each                             8,000
6 X 16 Foot Single Deck Vibrating
Fine Refuse Screens
  2 G> $19,000 each                           38,000
                           242

-------
     Sieve Bends
       7  Feet Wide  -  40 Inch  Radius
       6  @ $5,600 each                            33,600
     8 X  16  Foot Single Deck  Vibrating
     Fine Clean Coal  Screens
        6  @ $30,000  each                          180,000
     Centrifugal  Dryers
        Bird  Model  1150  D
        2  @ $48,000  each                          96,000
     Vacuum  Disc Filters
        2-12 Ft.  6 Inch Diameter 10 Disc
            $120,000 each                         240,000
        1-10 Ft.  6 Inch Diameter 9 Disc         100,000
      Classifying Cyclones
        20 Inch Diameter
        6 @ $2,400 each                           14,400
      Magnetic Separators
        Double Drum - 30 Inch Diameter -
        6 Ft. Long
        3 6 $17,000 each                           51,000
      Pumps                                       150.000
      Total  Preparation Plant Equipment Cost    1,412,800
Total Cost of Preparation Plant
      Including Site Preparation, Construction of
      Building, Electrical Service, Piping, etc.
      $1,412,800 X  3.0                                       $4,238,400

                                243

-------
OTHER FACILITIES & EQUIPMENT:
      Static Thickener
            100 Ft. Diameter G> $2,000 per foot                      $   200,000
      Fluid-Bed Thermal Dryer
            Complete with structural steel, motors, motor
            controls, wiring, piping, field erection, and
            start-up service                                        3,500,000
      Clean Coal Belt To Silo
            42  Inch Wide - 300 feet @ $520 per foot                    156,000
      Clean Coal Silo
            10,000 ton capacity @ $110 per ton                      1,100,000
      Coal Sampling System                                             300,000
      Unit-Train Loading Facility                                      500,000
      Magnetite Thickener
            30  Ft. Diameter @ $2,500 per foot                           75,000
      Refuse Belt
            36  Inch Wide - 200 feet @ $480 per foot                     96,000
      Refuse Bin
            300 Ton Capacity - Fabricated Part                          60,000
      Refuse Handling  Equipment
            2 - Trucks @ $ 75,000 each                                 150,000
            2 - Dozers @ $150,000 each                                 300,000
                       Total Other Facilities &  Equipment           $6,437,000
                                      244

-------
SUMMARY OF CAPITAL COST:
      Raw Coal Storage and Handling                        $ 1,019,400
      Preparation Plant                                      4,238,400
      Other Facilities and Equipment                         6,437,000
      Contingency (Interest during construction, etc.)       1,754.200
                         Total Capital Requirement         $13.449,000
 BASED UPON THE 600 TONS  PER  HOUR  INPUT  TO THIS  PLANT THE CAPITAL
 REQUIREMENT TRANSLATES TO  $22.400 PER TON HOUR  INPUT
                                       245

-------
     5.6.2 Capital Amortization
     Based upon the rationale developed in Section 4.0, the capital
amortization for Example 6 is as follows:
       Total Capital Required:  $13.5. Million
       Capacity:
           Raw Coal Input - 600 tph
           Clean Coal Output - 440 tph

                         CAPITAL AMORTIZATION

                                                % Utilization
Amortization Period & Basis
10 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
15 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
30%
$1.31
$1.79
$1.05
$1.43
40%
$0.97
$1,33
$0.78
$1.06
       5.6.3 Operating and Maintenance Costs
      The operating and maintenance costs summarized tn the following
Table 5-34 are based upon:
      o  Raw Coal Input of 600 Tons Per Hour
      o  Clean Coal Output of 440 Tons Per Hour
                         «
      o  Btu Recovery of 89.2%
      o  10 Year Amortization Period
      o  30% Utilization 2,600 Operating Hours Per Year
         out of a Possible 8,760 Hours or 13 Hours Per Day for  200
         Days Per Year.
                                     246

-------
                               TABLE  5-34

             EXAMPLE 6 - HEAVY MEDIA PROCESS - COMPLEX

                    OPERATING AND MAINTENANCE COSTS


     rATfrrriDv                                  Per Ton         Per Ton
COST CATEGORY                                  Raw Coal       Clean Coal

     Labor -

         Supervisory (Non Union)               $0.099         $0.135

         Operating & Maintenance (Union)        0.638          0.870
     Overhead -

         Fringe Benefits - 25% Non-Union        0.025          0.034
                         - 20% Union            0.128          0.174
         Other - Includes Workmens1
          Compensation Insurance, Payroll
          Taxes, Welfare Fund, etc.             0.213          0.291

     Supplies -

         Operating                              0.169          0.23
         Maintenance & Other                    0.242          0.33

     Thermal Dryer Fuel -

         Based Upon 7.0 Tons/Hr Coal
           Consumption & Cost of Coal
           $20/Ton                              0.233          0.318

     Cleaning Plant Repair Parts                0.147          0.20

     Electricity (Large Thermal Dryer)          0.334          0.456

     0 & M Cost -
       Not Including Capital Amortization      $2.23          $3.04

     Capital Amortization -
       10 years - 30% Utilization               1.31           1.79

     Total Operating & Maintenance  Cost        $3.54          $4.83
     Cost Per Million Btu  (13,619 Btu/lb)                     $0-177
                                     247

-------
     5.6.4 Discussion of Performance and Cost
     The Example 6 plant performs a reasonably good job of reducing
ash and sulfur while recovering nearly 90% of the heat content in the
raw coal feed.  This is accomplished by treating the coarser size frac-
tions (+3/4 inch) in a heavy media vessel  and the finer sizes with
heavy media cyclones and froth flotation.   The heavy media vessel
effects a separation at 1.6 specific gravity giving a clean coal  yield
consistent with the washability data from Table 5-31.  Due to the high
percentage of 3/4 inch XO  material in the raw feed, the majority of the
plant is devoted to finer cleaning equipment.  The heavy media cyclones
operate at 1.60 specific gravity treating the 3/4 inch X l/2mm(28 mesh)
material with the l/2mm X 0 handled by flotation cells.  These cyclones
recover over 80% of their feed as predicted by the washability data
from Table 5-30. The froth cells also recover nearly 80% of their feed
while significantly reducing the ash and sulfur content of the l/2mm X 0
size fraction.
     As presented in Table 5-33, this is an expensive plant to build.
One of  the major factors contributing to this high capital cost is the
large thermal dryer necessary to handle all of the 440 tons per hour of
clean coal produced by the plant.  This one item accounts for 30% of
the total cost of the preparation facility.  In spite of the high cost,
drying  is necessary to meet their contract specification and can be
further justified on the basis of lower transportation and handling  costs.
Since the capital cost is so high and current utilization is only 30%,
there is substantial room for reducing the effect of capital amortization
                                  248

-------
on total cost.  If this plant was operated 40% of the time, the capital
cost would be brought down by $0.46 on each ton of clean coal.  Greater
plant utilization would also have a favorable impact on other fixed
expenses such as supervisory salaries and certain overhead items.
     Since the Example 6  process when treating this particular coal loses
approximately 10% of the  heat content in the raw feed, a cost might be
applied  to account for these "lost" Btu's.  If applied, the total cost
of preparation would increase by $0.077 to $0.254 per million Btu. The
application  of this  "cost" is based upon the assumption that the raw coal
was saleable in its  original form and therefore had value associated with
its heat content. Even if one accepts this assumption, the validity of
applying this "cost" is subject to question since the material discarded,
which carried with it these "lost" Btu's, also carried large quantities of
the undesireable raw coal constituents such as ash and sulfur whose
removal  was  the very purpose of the cleaning process.  Therefore, an
argument might be made that if the cleaning process was performing its
design function efficiently (i.e. to the Btu recovery limits consistent
with its design objective), no cost should be applied for the "lost"
heat content.  However, a cost "penalty" would be assessed if the process
did not  function close to the maximum Btu recovery consistent with the
desired  sulfur and ash reduction.  Since there are differing views on
how this subject should be treated, we have identified this cost item
separately above, to permit the reader complete latitude in it's
application.
     Although this is an  expensive plant to build, the overall operating
and maintenance costs are quite reasonable considering the results achieved.
                                  249

-------
Even with the low plant utilization noted above, the price per ton is
less than $5.00 for a product having one-third the ash and half the
sulfur of the raw coal.  This expense is more than recovered by the
producer in the market place who now has a far more valuable and readily
saleable product.  Part of the increased value of the cleaned coal  is
related to the benefits derived by the user.   These include the obvious
savings in transportation and ash disposal as well as the more subtle
and sometimes greater economic benefits reflected in reduced particulate
and FGD emission control capacity.  When these benefits are quantified
based upon the particular user's situation, they can significantly re-
duce the effective cost of coal preparation.   In this particular case,
the reduction in sulfur would substantially reduce the S02 emission
control equipment and expense at the combustion location.  Since the
purpose of this study is to look at coal preparation cost at the pro-
ducers level, we have not attempted to quantify any of these benefits
which our other studies have shown vary on a  case by case basis.
                                   250

-------
5.7  Example 7 - Heavy Media Process - Complex
     5.7.1  General Description
     This plant was designed to process coal with a large percentage
(40-50%) of finer material in the range of  1/4 inch X 0. The presence of
so much fine material in the raw plant feed is related to the nature of
the coal and the continuous mining methods  used.  Although such mining
machinery is quite efficient from a production standpoint, the as-mined
product can be more difficult to handle and process.  Therefore, such a
condition should be a major consideration in the design of a coal prepara-
tion plant.
     From the open raw coal storage area, 8 inch X 0 material is fed via
a 42 inch wide belt to a rotary breaker at just over 600 tons per hour
(tph).  That material which reduces to 6 inches or less in the breaker
passes through the screen plates and drops onto the 42 inch wide plant
feed belt.  That material which does not fracture to 6 inches or less
passes out the refuse end of the breaker and reports to a rock bin.
     As the raw coal moves into the plant,  it passes under a tramp iron
magnet to remove any stray ferrous material such as broken mining bits
which may have been carried along with the  coal.  From the plant feed
belt the 6 inch X 0 coal drops at the rate  of 600 tph onto two 8 X 20
foot inclined vibrating double deck screens having 1-1/4 inch top deck and
1/4 inch lower deck openings.  The actual feed to these screens is 610 tph
due to an additional 10 tph from the magnetite recovery units which is re-
cycled back through the circuit.  Of the total feed to these screens, 330
tph of 6 X 1/4 inch material passes over and goes to two 6 X 16 foot
double deck prewet screens having 1/4 inch  lower deck openings.  All  but

                                    251

-------
                  FIGURE  5-7
EXAMPLE 7 - HEAVY MEDIA PROCESS  -  COMPLEX
       PREPARATION PLANT FLOW SHEET
                                                             HEAVY
                                                         _   MEDIA
                                            HEAVY MEDIA -»-dj_ ASUMP
                                             CYCLONES

-------
10 tph passes over both decks of these screens and goes to the heavy media
vessel.   Of the 320 tph of 6 X 1/4 inch material entering the vessel, 190
tph "floats" as clean product and passes to two 6 X 16 foot double deck
drain and rinse screens.  These screens provide the multiple functions of
sizing, partial dewatering, and media recovery.  Passing over the top decks
is 95 tph of 6 X 2 inch clean coal which goes to a crusher where it is re-
duced to 2 inch X 0 before it drops onto the clean coal belt. The 95 tph of
2 inch X 0 clean coal passing over the bottom deck of the 6 X 16 foot drain
and rinse screens goes to two centrifugal dryers which further dewater the
material before it drops onto the clean coal belt.
     Of the total feed to the heavy media washer, 130 tph reports as re-
fuse and goes to one 6 X 16 foot double deck drain and rinse screen for
media recovery and partial dewatering.  All 130 tph passes over both decks
of these screens and goes to the refuse belt.
     Returning to the 8 X  20 foot raw coal screens, 280 tph of 1/4 inch X
0 material (46% of the total plant feed) passes through these screens and
is fed with the 10 tph underflow from the 6 X 16 foot prewet screens to
sieve bends ahead of four 6 X 16 foot single deck desliming screens.  Of
the 290 tph fed to these screens, 220 tph of 1/4 inch X 28 mesh material
passes over and is fed to four 24 inch diameter heavy media cyclones. The
overflow from these cyclones is 130 tph of  1/4 inch X 28 mesh material which
goes to sieve bends ahead of four 6 X 16 foot single deck drain and rinse
screens.  All but 10 tph passes over these  screens and goes to four centri-
fugal dryers for further dewatering.  Of the 120 tph fed to these centri-
fuges, 115 tph is recovered and drops onto the clean coal belt.  The 5 tph
of effluent reports to a sump from which it is pumped over a sieve bend
on to the froth flotation cells.  The 10 tph passing through the 6 X  16
                                    253

-------
foot clean coal drain and rinse screens reports to the dilute media  sump
from which it is pumped to magnetic separators.  As mentioned earlier,  the
magnetic separators recover the 10 tph and send it back to the beginning
of the circuit.
     The underflow from the heavy media cyclones is 90 tph of 1/4 inch  X
28 mesh material which is fed to a sieve bend ahead of a 6 X 16 foot single
deck vibrating refuse drain and rinse screen.  All 90 tph passes over this
screen and reports to the refuse belt.
     Returning to the 6 X 16 foot desliming screens, 70 tph of 28 mesh  X
0 material passes through and is fed to froth flotation cells along with
the 5 tph of fine dryer effluent material which was recovered through a
sieve bend as mentioned above.  The 75 tph of 28 mesh X 0 material is fed
to two banks of three froth cells which recover over 70% as clean coal.
The 55 tph of clean product from the froth cells goes to a 10 foot six
inch diameter vacuum disc filter having 14 discs for dewatering before
dropping onto the clean coal belt.  The 20 tph of refuse from the cells
goes to the 100 foot diameter concrete static thickener.  Settled material
is pumped from this thickener at the rate of j>0 tph to a 10 foot 6 inch
diameter vaccum disc filter having 12 discs where it is dewatered suffic-
iently to permit disposal.
     Of the 600 tph of 6 inch X 0 raw coal feed to the plant, 360 tph of
2 inch X 0 winds up on the 36 inch wide clean coal belt and is fed to a
15,000 ton capacity concrete silo to await unit-train load-out.  This plant
is efficiently operated and maintained by a minimum of personnel as set
forth in Table 5-36.  Such a small staff is made possible by the aid of
a sophisticated electronic control center.
     As presented in Table 5-37, a plant of this size and general make-up
can currently be constructed for a price of $8.4 million.
                                    254

-------
                                                      TABLE  5-35

                                        EXAMPLE  7  -  HEAVY  MEDIA PROCESS - COMPLEX

                                             PREPARATION PLANT PERFORMANCE*
             Raw Coal Feed To  Plant:
             Size Fraction
              6  Inch  X  0
Tph


600
 Surface
Moisture

   5.0
Btu/lb
                                                                    8,600
Ash %
             40.0
 Total
Sulfur

  1.0
ro
en
cri
              Clean  Coal  Product From Plant:
              2  Inch  X 0
360
   4.88
13,348
11.67
  1.14
              Moisture  & Ash  Free Btu  = 15,112  Btu/lb

              Net Performance:

                   Weight Yield 60.0 %    Btu  Recovery 93.1%     Btu  of^Clean  Coal  with 4.9% Moisture 12,697 Btu/lb


              * Btu,  Ash, and Sulfur Presented  on Dry  Basis

-------
                                TABLE 5-36
                EXAMPLE 7 - HEAVY MEDIA PROCESS - COMPLEX
            PREPARATION PLANT OPERATING & MAINTENANCE PERSONNEL
General Non-Union Management
Preparation Manager
Operating Shift (Two per day)
    Title
Foreman
Plant Operator
Electrician/Mechanic
Mobile Equipment Operator
  (Refuse Spreading & Compacting and
   Pushing Raw Coal Into Feeders)
Repairman Helper
General Outside Laborer
Maintenance Shift
Foreman
Electrician/Mechanic
Repairman
Repairman Helper
Personnel Summary
General Management
Operating Shifts
Maintenance Shift
Union Classification
NU*
4-E
4-A
3-A
2-F
1-J
Total
NU*
4-A
3-B
2-F
Total
Quantity
1
Quantity
1
1
1
2
1
1
7
1
1
3
I
6
                                               Total
 1
14
_6
21
*NU - Non-Union
                                     256

-------
                             TABLE 5-37
             EXAMPLE 7  -  HEAVY MEDIA PROCESS - COMPLEX
              PREPARATION PLANT CAPITAL REQUIREMENTS

RAW COAL  STORAGE AND HANDLING:
      Raw Coal  Storage  Area
          10,000 Ton Capacity with Stacking Tube,
          Reclaiming Feeders, and Tunnel                       $250,000
      Raw Coal  Belt To  Rotary Breaker
          42 Inch Wide  -  200 Feet @ $520 per foot               104,000
      Tramp Iron Magnet
          Explosion Proof - Self Cleaning Type                  20,000
      Rotary Breaker                                           180,000
      Raw Coal  Belt To  Plant
          42 Inch Wide  -  250 Feet @ $520 per foot               130,000
                  Total Raw Coal Storage & Handling Cost      $684,000

PREPARATION PLANT:
      Equipment Cost -
          8 X 20 Foot Double  Deck Vibrating
          Raw Coal Screens
            2 G> $30,000 each                        $60,000
          6 X 16 Foot Double  Deck Prewet Screens
            2 @ $24,000 each                         48,000
          Heavy Media Washer                         45,000
          6 X 16 Foot Double  Deck Clean Coal
          Drain & Rinse Screens
            2 @ $23,000 each                         46,000

                                       257

-------
6 X 16 Foot Double Deck  Refuse  Drain  &
Rinse Screen
  1 I? $26,000                             $26,000
Crusher - Clean Coal                        12,100
Centrifugal Dryers
  2 @ $28,200 each                         56,400
Sieve Bends - 5 Feet Wide
  5 Ft. Radius - 1/2 mm openings
  4 @ $4,000 each                          16,000
6  X 16 Foot Single Deck  Desliming Screens
  4 @ $16,000 each                         64,000
Heavy Media Cyclones
  24 Inch Diameter - Ceramic Liners
  4 @ $4,000 each                          16,000
Sieve Bends - 5 Feet Wide
  30 Inch Radius - 1/2 mm openings
  6 @ $4,000 each                          24,000
6  X 16 Foot Single Deck
Drain  &  Rinse Screens
  5 @ $19,000 each                         95,000
Centrifugal Dryer
  4 @ $23,200 each                         92,800
Froth Flotation Cells
  2 Banks of Three Cells                   68,000
                          258

-------
          Magnetic Separators - Single Drum
            30 Inch Diameter - 6 Feet Long
            5 @ $6,500 each                         $   32,500
          Vacuum Disc Filters
            Clean Coal - 10 Ft. 6 Inch Diameter -
            14 Disc                                    128,000
            Refuse - 10 Ft. 6 Inch Diameter -
            12 Disc                                    120,000
          Sumps - Heavy & Dilute Media
            4 I? $14,000 each                            56,000
          Sump - Dryer Effluent
            1 0 $10,000                                 10,000
          Pumps                                        100,000
           Total Preparation Plant Equipment Cost   $1,115,800
      Total Cost of Preparation Plant
          Including Site Preparation, Construction of
          Building, Electrical Service, Piping, etc.
          $1,115,800 X 3.0                                    $3,347,400
OTHER FACILITIES & EQUIPMENT:
      Static Thickener
          100 Feet 0 $2,000 per foot                             200,000
      Refuse Belt
          36 Inch Wide - 200 Feet @ $480 per foot                 96,000
      Refuse Bin                                                  50,000
                                  259

-------
      Refuse  Handling  Equipment
          2 - Dozers @ $150,000 each                          $  300,000
          1 - Front-End Loader                                     50,000
      Clean Coal  Belt  To Silo
          36  Inch Wide - 300 Feet @ $480 per foot                144,000
      Clean Coal  Silo  - Concrete
          15,000  Ton Capacity @ $110 per ton                   1,650,000
      Automatic Coal Sampling System                             300,000
      Unit-Train  Loading Facility                                500.000
                      Total  Other Facilities & Equipment      $3,290,000
SUMMARY OF CAPITAL COST:
      Raw Coal Storage and Handling                           $  684,000
      Preparation Plant                                        3,347,400
      Other Facilities and Equipment                           3,290,000
      Contingency (Interest during construction, etc.)         1,098,200
                            Total Capital  Requirement        $8,419,600
BASED UPON THE 600 TON PER HOUR INPUT TO THIS PLANT THE CAPITAL
REQUIREMENT TRANSLATES TO $14,000 PER TON HOUR INPUT
                                    260

-------
     5.7.2  Capital  Amortization
     Based  upon the rationale developed in Section 4.0, the capital
amortization for Example 7 is as follows:
       Total Capital Required:  $8.4 million
       Capacity:
           Raw Coal Input - 600 tph
           Clean Coal  Output - 360 tph

                          CAPITAL AMORTIZATION

                                               % Utilization
Amortization Period & Basis | 30%
10 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
15 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
$0.82
$1.36
$0.66
$1.09
40% -
0.61
i
1.01 |
!
0.49
0.81
      5.7.3 Operating and Maintenance Costs
      The operating and maintenance costs summarized in the following
 Table 5-38  are  based  upon:
      o  Raw Coal Input of 600 Tons Per Hour
      o  Clean Coal Output of 360 Tons Per Hour
      o  Btu Recovery of 93.1%
      o  10 Year Amortization Period
      o  30% Utilization 2,600 Operating Hours Per Year
           out of a Possible 8,760 Hours or 13 Hours Per Day for 200
           Days Per Year.  (Although this is low, this rate is applied
           in order to be more consistent with the actual experience
           during the period over which the cost data was collected.)
                                    261

-------
                               TABLE 5-38

               EXAMPLE 7 - HEAVY MEDIA PROCESS - COMPLEX

                    OPERATING AND MAINTENANCE COSTS

                                               Per Ton         Per Ton
COST CATEGORY                                  Raw Coal       Clean Coal


     Labor -

         Supervisory (Non-Union)                $0.058          $0.096

         Operating & Maintenance (Union)         0.211           0.352

     Overhead -

         Fringe Benefits - 25% Non-Union         0.014           0.024
                         - 21%     Union         0.044           0.074

         Other - Includes Welfare Fund,
           Payroll Taxes, Property Taxes,
           Insurance, etc.                       0.060           0.100

     Supplies -

         Operating - Magnetite                   0.055           0.091
                   - Other                       0.307           0.511

         Maintenance                             0.092           0.154

     Major Maintenance - Scheduled repairs
       and plant improvements                    0.051           0.085

     Electricity -                               0.090           0.150

     Subcontract Services For Major Equipment
       Repairs & Miscellaneous Expenses          0.289           0.482

     0 & M Cost -
       Not Including Capital Amortization       $1.27           $2.12

     Capital Amortization -                      0.82            1.36
       10 Yrs. - 30% Utilization

     Total Operating & Maintenance Cost         $2.09           $3.48
     Cost Per Million Btu  (12,697 Btu/lb)                        $0.137
                                   262

-------
     5.7.4 Discussion of Performance and Cost
     With the coal currently being handled by the Example 7 plant, the
major thrust of the preparation process is the reduction in ash.  As
 summarized  by Table  5-35,  this  objective  is  accomplished at a loss of
only 7% of the total heat content in the raw coal feed.  Looking at
the increase in sulfur content  in the final product over that of the
raw coal, one might think there was a typographical error.   However,
this phenomenon occurs because  the sulfur content of the raw coal  is
mostly organic in nature and is not affected by physically cleaning.
Therefore, as 40% of the raw feed is discarded as refuse, the organic
sulfur bonded to the clean coal becomes a higher proportionate share of
the final product.  Although this result is expected with this particular
coal, it  should not be assumed  that this process is incapable of removing
sulfur.   To the contrary, as demonstrated by Example 6, given a coal
having a  higher pyritic sulfur  content, processes of this type are
quite successful at effecting significant sulfur reductions.
     The  capital cost of this plant is quite reasonable considering its
demonstrated ability to reduce  over 70% of the raw coal ash.  Although
this plant's equipment make-up  is much the same as Example 6, its capital
cost is over 35% less.  The principal reason for this lower capital cost
over comparable capacity heavy  media plants  is the elimination of thermal
drying.   This also has a significant impact  on reducing operating and
maintenance costs.  Through centrifugal drying methods and vacuum
filters the moisture is reduced to an acceptable level. Although this is
somewhat  difficult to accept, it is supported by actual product data
                                  263

-------
showing less than 16% of the final product is smaller than 28 mesh
which is the most trouble to mechanically dewater.  In spite of this
lower capital requirement, the capital amortization per ton of clean
coal is still $1.36 due to only a 30% utilization factor.  Certainly,
there is room for improvement as demonstrated by the fact that a
savings of $0.35 per ton could be realized by operating merely an
additional 10% of the time.
     Regardless of the low plant utilization, the overall cost of pro-
ducing clean coal is quite low in view of quality of the product and
limited Btu  loss.  Besides the absence of thermal drying, the 0 & M
cost is kept low by having a minimum staff and closely monitoring the
consumption  of magnetite, flocculants, and other expensive materials.
As  noted previously, Table 5-38, gives the producer's cost to clean a
given  coal by a particular process.  Certainly, the clean product re-
sults  in savings at the user level which go to reduce the effective cost
of  coal cleaning. Since these benefits are most accurately quantified on
a site specific basis, no estimate is given here of their impact on
the total economics of coal preparation.
      If a cost is applied to account for the 7% loss in heat content of
the raw feed,the cost of preparation  increases by $0.066 to $0.203 per
million Btu.  As mentioned at several other points in this study,  it is
debatable whether or not it is appropriate to assess such a "penalty"
when the material containing this heat content was essentially composed
of  the undesirable material (ash and  some sulfur) which the cleaning
process was  designed to eliminate.  This being the case, the reader is
left with the prerogative to treat this matter as seen fit.
                                   264

-------
 5.8 Example  8  -  Heavy Media Process - Complex
    5.8.1  General  Description
     Although not shown on  the  flow sheet  (Figure  5-8), the  raw coal
is sized and most of the debris removed by a rotary breaker  before
being conveyed to the raw coal storage area.  The 4 inch X 0 raw coal,
mined by continuous and longwall mining, is fed to the breaker which
has approximately 2 inch screen plate openings thereby permitting
1-1/4-inch X 0 material to  pass through.
     From the raw coal storage area, the 1-1/4 inch X 0 material is fed to
the plant at the rate of 900 tons per hour (tph).  On its way into the
plant, the raw coal passes  under a tramp iron magnet to remove any
ferrous matter and passes through two 6 X 16 foot single deck trash screens
having two inch openings to remove any larger foreign material not
previously captured.  The 1-1/4 inch X 0 raw coal passes over sieve bends
onto twelve 6 X 16 foot single deck desliming screens.  These screens with
1/2 mm openings pass the 28 mesh X 0 material at the rate of 166 tph and the
1-1/4 inch X 28 mesh material flows over at the rate of 740  tph.  This 740 tph
goes to twelve 24 inch first stage heavy media cyclones operating at
1.8 specific gravity.  The  602 tph of overflow from these cyclones goes
to sieve bends ahead of twelve 6 X 16 foot single deck drain and rinse screens
whose primary function Is the recovery of media.  All but 4 tph pass
over these screens on the way to centrifuges for partial dewatering
before going to the thermal  dryers.  The 4 tph passing through these
screens reports to the dilute media sumps.
     The 138 tph of 1-1/4 inch  X 28 mesh underflow from the  first stage heavy
media cyclones goes to sieve bends ahead of four 5 X  16 foot single deck
                                    265

-------
                                                       FIGURE 5-8
                                    EXAMPLE  8 - HEAVY MEDIA PROCESS  -  COMPLEX
                                         PREPARATION PLANT FLOW SHEET
FE V J_    u     I 740 TPH
NDS  \C	^pJ 1-1/4 -rn X 28 m
                                                                                                 2nd STAGE
                                                                                                 HEAVY MEDIA
                                                                                                  CYCLONES


30 TPH
10
32 TPH
12 TPH ^x/ /
|20 TPH
IZS X 100 m
J— SOLID BOWL
CENTRIFUGES
2 TPH| I ,8 TPH

-------
drain and rinse screens for the purpose of media recovery.  Of the
total feed to these screens, 136 tph passes over and is reduced to 1/2 inch X
0 by two double roll crushers.  This material reports to the second
stage feed sumps from which it is pumped to sieve bends ahead of the
four second stage 5 X 16 foot single deck desliming screens.  The 2 tph of
28 mesh X 0 passing through the first stage 5X16 foot drain and rinse screens
reports to the first stage dilute media sumps where it is pumped to the
eight first stage magnetic separators and recovered for further pro-
cessing.
     Of  the 136  tph of  1/2  inch  X 0 material  fed to the second stage de-
sliming  screens,  128 tph of 1/2  inch X  28 mesh  passes over  and is fed  to the
four 24  inch  second stage heavy  media cyclones  operating  at 1.8 specific
gravity.  Only 8  tph of 28  mesh  X 0 material  passes through these desliming
screens and reports to  the hydrocyclone feed  sumps.  The second stage
heavy media cyclones recover  18  tph of  1/2  inch X  28 mesh clean coal which
passes over two  5 X 16  foot second  stage drain  and rinse  screens on the way
to  centrifuges before going  to the  thermal  dryers.  The underflow from the
second stage  heavy media cyclones is 110 tph  of 1/2 inch  X  28 mesh  refuse
which goes to sieve bends ahead  of  two  7 X  16 foot second stage drain  and
rinse screens for media recovery. All 110 tph passes over these screens and
goes to  two horizontal  centrifuges  where the  surface moisture  is reduced
from 20%  to around 7% before  being  conveyed to  the refuse bin.
     Now, returning to  the  hydrocyclone feed  sumps, which receive
28  mesh  X 0 material  from  the first and second stage  desliming screens and
                                  267

-------
the effluent from the clean coal centrifuges, a slurry containing  190
tph is fed to thirty-two hydrocyclones.  The overflow from these cyclones
is 160 tph of 28 mesh X 0. The underflow is 30 tph of 28 X 100 mesh
material which reports to sumps from which it is pumped to four Deister
tables for final clean coal and refuse separation. Also feeding the tables
is 2 tph from the refuse centrifuge effluent sumps.  The 12 tph of 28 X
100 mesh clean product from the tables joins the 160 tph of 28 mesh X 0
overflow from the hydrocyclones to feed thirty 14 inch thickening
cyclones.  The 56 tph of 100 mesh X 0 overflow from these cyclones goes
to the two 135 foot diameter concrete static thickeners.  The 116 tph of
28 X 100 mesh underflow from the thickening cyclones is joined by 58 tph
of 100 mesh X 0 material pumped from the thickeners before going to the
vacuum filters.
     The total of 174 tph is partially dewatered by four vacuum disc
filters each having ten discs 12 feet 6 inches in diameter.  This gives
an effective filtering surface area of 2,280 square feet per filter or
a total of 9,120 square feet.  Based upon a load factor of 40 pounds
per hour per square foot of filtering surface gives the following
minimum surface area required:
             Weight Being Processed:
              174 tons/hour = 348,000 pounds/hour
             Surface Area Required (Minimum):
              348,000 pounds/hour _ 8 70Q ft;2
               40 pounds/hour/ft^
                                  268

-------
          2
The 420 ft  of excess filtering capacity permits slight fluctuations
in the feed without degrading performance.  These filters produce a cake
of approximately 25% surface moisture which goes on to the thermal dryers,
     The two fluid-bed thermal dryers receive 774 tph of 1-1/4 inch X 0
material with a surface moisture of around 12%.  During the drying
process, the moisture is reduced to 5% or less.  The dried product is
conveyed to a 15,000 ton concrete silo for storage pending unit-train
loadout.
Plant Operation -
     The equipment in this preparation plant is arranged in two
parallel circuits.  This permits the plant to operate at full  capacity
for two shifts per day and at half capacity for the third shift while
one circuit is shut down for maintenance.  Based upon working  five
days per week, the plant can operate on an annual basis 4,160  hours at
full capacity and 2,080 hours at half capacity for a total possible
plant utilization of 5,200 hours per year.  This would be equivalent
to over 59% of the time (5,200 Hrs 7 8,760 Mrs).  However, this is
under ideal conditions and in practice the actual utilization  is
closer to 50%.  For the purpose of allocating the capital cost of this
plant, this latter utilization factor was used.
                                   269

-------
                                                        TABLE 5-39
                                       EXAMPLE 8 - HEAVY MEDIA PROCESS - COMPLEX
                                             PREPARATION PLANT PERFORMANCE
no
—i
o
          Raw Coal Feed To Plant:
Size Fraction
1-1/4 X 3/8 Inch
3/8 X 1/8 Inch
1/8 Inch X 0
Tph
215
281
404
900
Surface
Moisture %



5.0
Btu/lb Ash %
31.2
20.7
13.4
11,970 19.9
Total
Sulfur %
2.75
2.65
2.20
2.45
          Clean Coal  Product From Plant:
          1-1/4 X 28 Mesh
          28  Mesh X 0
600
174
774
                                                5.0
13,130
14.7
1.8
          Net Performance:
                Weight Yield  86.0% Btu  Recovery 94.3%    Btu of  Clean  Coal with  5.0% Moisture 12,473 Btu/lb

-------
                                                   TABLE 5-40

                                   EXAMPLE 8 - HEAVY MEDIA PROCESS - COMPLEX

                      WASHABILITY DATA OF ASSUMED PLANT FEED - 1-1/4 X 3/8 INCH FRACTION*
ro
    Specific            D1rect  Float
    Gravity of    Height %   Ash %   Sulfur
Cumulative Float
      Cumulative Sink
Weight %   Ash %   Sulfur
FLOAT 1.40
1.40- 1.50
1.50- 1.60
1.60- 1.70
1.70- 1.80
SINK- 1.80
41.8
11.6
7.4
7.0
6.2
26.0
9.4
19.6
28.4
36.9
44.1
67.5
1.50
2.50
3.30
3.35
3.35
4.40
41.8
53.4
60.8
67.8
74.0
100.0
9.4
11.6
13.7
16.1
18.4
31.2
1.50
1.70
1.90
2.05
2.15
2.75
58.2
46.6
39.2
32.2
26.0

46.8
53.6
58.3
63.0
67.5

3.65
3.95
4.05
4.20
4.40

     * 23.9% of  Total  Feed

-------
                                                      TABLE  5-41
                                      EXAMPLE 8  -  HEAVY MEDIA  PROCESS  - COMPLEX
                          WASHABILITY  DATA  OF ASSUMED  PLANT  FEED - 3/8 X  1/8  INCH  FRACTION*
ro
--J
ro
      Specific            D1rect Float
      Gravity of    Weight %   Ash %   Sulfur
     Cumulative Float
Weight %   Ash %   Sulfur
      Cumulative Sink
Weight %   Ash %   Sulfur %
FLOAT 1.40
1.40- 1.50
1.50- 1.60
1.60- 1.70
1.70- 1.80
SINK- 1.80
67.0
5.3
5.3
3.6
3.0
15.8
7.5
20.7
29.7
36.2
43.7
65.7
1.30
2.65
3.50
3.40
3.70
7.85
67.0
72.3
77.6
81.2
84.2
100.0
7.5
8.5
9.9
11.1
12.2
20.7
1.30
1.40
1.55
1.60
1.70
2.65
33.0
27.7
22.4
18.8
15.8

47.5
52.6
58.0
62.2
65.7

5.45
6.00
6.60
7.20
7.85

      * 31.2% of Total Feed

-------
                                                TABLE  5-42

                               EXAMPLE  8  -  HEAVY MEDIA PROCESS  -  COMPLEX
                    WASHABILITY DATA OF ASSUMED  PLANT FEED -  1/8  X 0  INCH  FRACTION*
Specific            Direct Float
Gravity of    Weight %   Ash_l   Sulfur
     Cumulative Float
Weight %   Ash %   Sulfur
       Cumulative Sink
Weight %   Ash %.  Sulfur


ro
•^j
CO



FLOAT 1.40
1.40- 1.50
1.50- 1.60
1.60- 1.70
1.70- 1.80
SINK- 1.80
81.2
2.4
3.3
2.2
1.5
9.4
5.7
22.6
28.1
34.2
40.9
63.2
1.00
2.20
2.20
3.50
3.05
12.45
81.2
83.6
86.9
89.1
90.6
100.0
5.7
6.2
7.0
7.7
8.2
13.4
1.00
. 1.05
1.10
1.15
1.15
2.25
18.8
16.4
13.1
10.9
9.4

46.7
50.2
55.8
60.1
63.2

7.55
8.35
9.85
11.15
12.45

* 44.9% of Total Feed

-------
                     TABLE 5-43
     EXAMPLE 8 - HEAVY MEDIA PROCESS - COMPLEX
PREPARATION PLANT OPERATING & MAINTENANCE PERSONNEL
General Non-Union Management
Preparation Manager (1/2 time)
General Foreman

Operating Shift - Full (2 per day)
Title Union
Foreman
Plant Operator
Electrician
Mechanic
Mobile Equipment Operator
(Refuse Hauling & Compacting)
Stationary Equipment Operator
(Thermal Dryer & Media Operators)
Repairman Helper (Greaser)
Utility Man

Operating/Maintenance Shift - Partial
(1 per day)
Foreman
Plant Operator
Electrician
Mechanic
Mobile Equipment Operator


Total
Classification
NU*
4-E
4-A
4-C
3-A
3-C
2-F
1-H
Total

NU*
4-E
4-A
4-C
3-A
Quantity
1
_!
2
Quantity
1
1
1
2
2
2
1
_3
13

1
1
1
4
2
                          274

-------
Stationary Equipment Operator                 3-C                  2
Repairman                                     3-B                  1
Repairman Helper  (Greaser)                    2-F                  1
Utility Man                                   1-H                 _3
                                              Total               16
Personnel Summary
General Management                                                2
Operating Shifts  -  Full                                          26
Operating/Maintenance  Shift -  Partial                            16.
                                              Total               44
 W-Non-Union
                                       275

-------
                             TABLE 5-44
             EXAMPLE 8 - HEAVY MEDIA PROCESS - COMPLEX
              PREPARATION PLANT CAPITAL REQUIREMENTS

RAW COAL STORAGE AND HANDLING:
      Raw Coal Belt to Rotary Breaker
          48 Inch Wide 350 feet at $560 per foot               $   196,000
      Rotary Breaker
          10 Ft diameter - 16 ft. long
          Includes structural work and rock bin to
          receive debris from breaker                             330,000
      Raw Coal Belt to Storage Area
          48 Inch Wide 300 feet at $560 per foot                  168,000
      Raw Coal Storage Area
          20,000 ton capacity with reclaiming feeders
          and tunnel                                              300,000
      Raw Coal Belt to Plant
          48 Inch Wide 350 feet at $560 per foot                  196.000
                      Total Raw Coal Storage & Handling Cost   $1,190,000

PREPARATION PLANT:
      Equipment Cost -
          6 X 16 .Foot Single  Deck Trash Screens
            2 @ $15,000 each                        $   30,000
          Sieve Bends
            6 Ft Wide, 2 Ft 6 Inch Radius
            14 @ $4,800 each                            67,200
                                    276

-------
7 X 16 Foot Single Deck Vibrating
  Uesliming Screens
  12 @ $21,500 each                           $258,000
7 X 16 Foot Single Deck Vibrating
  Drain & Rinse Screens
  2 @ $21,500 each                              43,000
Sieve Bends
  4 Ft Wide, 2 Ft 6 Inch Radius
  4 - 1st Stage, 6 - 2nd Stage
  10 @ $3,200 each                              32,000
5 X 16 Foot Single Deck Vibrating
  Drain & Rinse Screens
  6 @ $18,500 each                             111,000
5 X 16 Foot Single Deck Vibrating
  Desliming Screens
  4 @ $18,500 each                              74,000
Sieve Bends
  5 Ft Wide, 2 Ft 6 Inch Radius
  12 @ $4,000 each                              48,000
6 X 16 Foot Single Deck Vibrating
  Drain & Rinse Screens
  12 @ $19,000 each                            228,000
Heavy Media Cyclones
  24 Inch Diameter w/Ni-Hard  Liner
  16 @ $3,000 each                              *8,QQQ
                          277

-------
Centrifugal Dryers
  6 @ $28,200 each                          $169,200
Crushers - 2 @ $33,100 each                   66,200
Magnetic Separators
  30 Inch Diameter - 10 Feet Long
  10 @ $8,500 each                            85,000
Centrifugal Dryers - Solid Bowl
  2 @ $110,000 each                          220,000
Centrifugal Dryers - Horizontal Refuse
  2 @ $25,000 each                            50,000
Hydrocyclones - 14 Inch Diameter w/Ni-Hard
Liner & Refrax Underflow
  32 @ $2,000 each                            64,000
Deister Tables
  2 Double Deck @ $21,000 each                42,000
Thickening Cyclones
  14 Inch Diameter w/Rubber Liner
  30 @ $1,300 each                            39,000
Vacuum Disc Filters
  12 Ft 6 Inch Diameter - 10 Disc
  4 @ $120,000 each                          480,000
Sumps - 1st Stage Heavy Media
  8,000 gallon - 1/4 Inch Steel
  2 @ $14,000 each                            28,000
                           278

-------
Sumps - 1st Stage Dilute Media
  7,000 gallon - 1/4 Inch Steel
  2 @ $14,000 each                        $   28,000
Sumps - 2nd Stage Feed
  4,000 gallon - 1/4 Inch Steel
  2 @ $10,000 each                            20,000
Sumps - 2nd Stage Heavy Media
  4,000 gallon - 1/4 Inch Steel
  2 @ $14,000 each                            28,000
Sumps - 2nd Stage Dilute Media
  3,000 gallon - 1/4 Inch Steel
  2 @ $14,000 each                            28,000
Sumps - Hydrocyclone Feed Sumps
  9,000 gallon - 1/4 Inch Steel
  2 @ $10,000 each                            20,000
Sumps - Refuse Centrifuge Effluent Sumps
  2,500 gallon - 1/4 Inch Steel
  2 @ $10,000 each                            20,000
Sumps - Table Feed
  3,000 gallon - 1/4 Inch Steel
  2 @ $10,000 each                            20,000
Sumps - Other
  7 @ $10,000 each                            70,000
Pumps                                        200,000
  Total Preparation Plant Equipment  Cost   $2,616,600
                            279

-------
      Total  Cost of Preparation P"Unt
          Including Site Preparation, Construction of
          Building, Electrical Service, Piping, etc,
          $2,616,600 X 3.0                                      $7,849,800
OTHER FACILITIES & EQUIPMENT:
      Fluid-Bed Thermal Dryers - 2
          Complete with structural steel, motors, motor
          controls, wiring, ptping, field erection, and
          start-up service                                       5,400,000
      Static Thickeners - 2
          Each 135 feet in diameter 9 $2,000 per foot              540,000
      Refuse Belt
          36 Inch Wide - 200 feet @ $480 per foot                   96,000
      Refuse Bins
          2 - 100 ton capacity - fabricated part                   100,000
      Refuse Handling Equipment
          2 - Trucks @ $ 75,000 each                               150,000
          2 - Dozers @ $150,000 each                               300,000
      Coal Sampling System                                         300,000
      Clean Coal Belt to Silo
          48 Inch Wide - 200 feet @ $560 per foot                  112,000
      Clean Coal Silo
          15,000 ton capacity @ $110 per ton                     1,650,000
      Unit-Train Loading Facility                                  500,000
                           Total Other Facilities & Equipment   $9,148,000
                                   280

-------
SUMMARY OF CAPITAL COST;
      Raw Coal Storage and Handling                        $ 1,190,QQO
      Preparation Plant                                      7,850,000
      Other Facilities and Equipment                         9,148,000
      Contingency (Interest during construction, etc.)       2,728,000
                             Total Capital Requirement     $20,916,000
BASED UPON THE 900 TONS PER HOUR INPUT TO THIS PLANT THE CAPITAL
REQUIREMENT TRANSLATES TO APPROXIMATELY $23.200 PER TON HOUR INPUT
                                    281

-------
    5.8.2 Capital Amortization
     Based upon the rationale developed in Section  4.0, the capital
amortization for Example 8 is as follows:
       Total Capital Required:  $20.9 Million
       Capacity:
           Raw Coal Input - 900 tph
            Clean Coal Output  -  774 tph

                          CAPITAL AMORTIZATION

                                                % Utilization
Amortization Period & Basis
10 Year Period
Per Ton of Raw Coal
t
i Per Ton of Clean Coal
15 Year Period
Per Ton of Raw Coal
Per Ton of Clean Coal
30%
$1.36
$1.58
$1.09
$1.26
40%
$1.01
$1.17
$0.81
$0.94
50%
$0.81
$0.94
$0.65
$0.75
       5.8.3  Operating  and  Maintenance  Costs
      The operating and maintenance costs summarized in the following
Table 5-45 are based upon:
      o  Raw Coal Input of 900 Tons Per Hour
      o  Clean Coal Output of 774 Tons Per Hour
      o  Btu Recovery of 94.3%
      o  10 Year Amortization Period
      o  50% Utilization 4,380 Operating Hours Per Year
           out of a Possible 8,760 Hours or  17.5  Hours Per Day
           for 250  Days Per Year.
                                    282

-------
                                 TABLE  5-45

                   EXAMPLE 8 - HEAVY MEDIA PROCESS - COMPLEX

                       OPERATING AND MAINTENANCE COSTS

                                                Per Ton         Per Ton
COST CATEGORY                                   Raw Coal       Clean Coal
      Labor -

          Supervisory (Non-Union)               $0.035         $0.041

          Operating & Maintenance (Union)        0.267          0.310
      Overhead -

          Includes Payroll Taxes, Vacation
           and Holiday Pay, Welfare Fund,
           Taxes, Insurance, etc.                0.196          0.228

      Supplies -

          Operating                              0.249          0.290

          Maintenance -  Includes Scheduled
           Major Repair  and Replacements         0.529          0.615

      Thermal Dryer Fuel -
          Based upon 12.5 Tons/Hr Coal Con-
           sumption andjCost.of Coal $20/Ton     0.278          0.323

      Electricity                                0.456          0.53

      Other                                      0.087          0.101

      0 & M Cost -
          Not Including  Capital /Amortization    $2.10          $2.44

      Capital Amortization -
           10 Yrs. - 50% Utilization             0.81           0.94

      Total Operating &  Maintenance Cost        $2.91          $3.38
       Cost  Per  Million  Btu  (12,473  Btu/lb)                     $0.135
                                   283

-------
     5.8.4 Discussion of Performance and Cost  ,
     The Example 8 plant is simply a two stage heavy media cyclone
process with limited use of Deister tables.  As indicated by the per-
formance data summarized in Table 5-39, it has the potential for high Btu
recovery by crushing the underflow from the first stage cyclones and
subjecting it to another round of cleaning.
     Of the heavy media processes presented in this study, others show
more dramatic reductions in ash and sulfur than occurs with the coal
currently being treated by the Example 8 plant.  However, as we know,
the results achieved by a given preparation process vary with the feed
to the plant and this raw coal is not particularly high in ash or sulfur.
Therefore, the purpose of presenting this  plant is to give further under-
standing of capital and operating and maintenance costs for a larger
heavy media plant which is capable of achieving significant reductions
in both ash and sulfur.  A further reason  for presenting this plant is
to show the favorable cost impact of increasing utilization to 50%.
This plant is capable of operating over 50% of the time by virtue of
its parallel circuit design.   Although this increases the initial capital
requirement, it is justified  by the greater output which permits a
lower per unit allocation of  fixed charges.
     Besides the parallel circuitry, necessitating redundant equipment,
the thermal drying of all clean coal produced increases this plant's
capital cost.   However, due to the high percentage of fines, thermal
drying is required.
                               284

-------
     Looking at the total producer's cost of preparation summarized on
the preceding Table, it is clear that, in spite of the high capital
requirement, the cost per ton of clean product is substantially less
than some smaller heavy media plants.  This lower cost is directly
attributable to the plant capacity and greater utilization mentioned
above.  For example, if this plant was operated only 30% of the time
there would be nearly a 20% increase ($0.64) in the cost of each clean
ton resulting from higher capital amortization alone, not to mention
the impact on other fixed charges.
     With the raw coal currently  being handled by this plant, the process
yields a 94.3% Btu  recovery.  Therefore, it would seem inappropriate to
apply an additional cost to cover these "lost" Btu's.  However, if such
a  charge is applied, the total cost  of cleaning increases by $0.039 to
$0.174 per million  Btu.
     In conclusion, the reader is reminded that the operating and
maintenance costs presented herein are those experienced by the pro-
ducer.  As stated earlier, the clean product carries with it various
benefits which are  reflected in lower costs to the user which go to
reduce the overall  net cost of coal  preparation.
5.9  SUMMARY OF PREPARATION PROCESS  EXAMPLES
     Table 5-46 on  the following  page gives a  tabular summary of the
major performance and cost elements  from the eight actual operating
preparation plants  examined in Section 5.0.
                               285

-------
                                                      TABLE 5-46
                                        SUMMARY OF PREPARATION PROCESS EXAMPLES
1)
ro
co
en
xam|
1
2
3
4
5
6
•7
/
8
pie Process/Level
Jig/Simple
Jig/ Intermediate
Jig/ Intermediate
Jig/Complex
Heavy Media/Simple
Heavy Media/Complex
Heavy Media/ Complex
Heavy Media/Complex
Input
Capacity
600
1000
1000
1600
1400
600
600
900
tph
tph
tph
tph
tph
tph
tph
tph
Capital Cost Per
Ton Per Hr. Input
$
$
$
$
$
$
$
$
6,600
13,700
12,100
14,300
13,800
22,400
14,000
23,200
Clean Coal
Output
354
714
566
953
1,036
440
360
774
tph
tph
tph
tph
tph
tph
tph
tph
Btu
Recovery
91.6%
96.4%
83.0%
93.7%
94.6%
89.2%
93.1%
94.3%
Per Ton
Raw Coal
$1.97
$2.62
$2.22
$2.60
$2.79
$3.54
$2.09
$2.91
Per Ton
Clean Coal
$3.35
$3.67
$3.92
$4.36
$3.76
$4.83
$3.48
$3.38
Per Million
Btu
$0.138
$0.152
$0.157
$0.162
$0.185
$0.177
$0.137
$0.135
       1)  All  cost figures as of mid-1977
       2)  Includes capital amortization
       3)  Does not include allowance for Btu loss of Process

-------
            SECTION 6,0
FUTURE PROSPECTS FOR COAL PREPARATION
             287

-------
6.0 FUTURE PROSPECTS FOR COAL PREPARATION
     It is the opinion of the author, that there is a significant
potential  for larger centralized preparation plants fed by more than
one mine thereby capable of operating almost continuously.  To accomplish
this in some areas would necessitate cooperative agreements between
smaller producers to assure round-the-clock availability of plant
feed.  Additionally, the plant would have to be laid out in such a
manner to permit parallel circuits or at least redundancy of higher
maintenance equipment.  Due to union restrictions,  overtime would
be a recurring cost factor.  However, such a cost would more than be
covered by the increased output and efficiency of such an arrangement.
     As expressed in a recent EPRI report, "The technological factors
that will contribute to the increasing use of preparation for power
coals are the advance of nonselective and continuous types of mining
equipment; problems associated with the use of high ash, high sulfur,
and alkali content coal in the boilers; and the expensive and uncertain
                                       *
performance of flue gas desulfurizers".
     Indications are clear that an increasing percentage of utility coals
will be cleaned.  This is being brought about by such factors as:
     1)  Emission Standards - Getting Tougher
         Coal Prep Can Eliminate or Reduce FGD costs and Associated
         Operational Problems
     2)  Economic Pressures -
         Greater Heat Content Per Unit Weight
         Reduced Boiler Maintenance
         Price of Higher Quality Coal
     :  Physical Coal Preparation, EPRI FP-314, May 1977, page 3-1
                                  288

-------
     In order to cost-effectively meet  this  increase  in demand brought
on by these tougher emission standards  and increasing economic pressures,
coal preparation processes will have  to be designed around maximizing Btu
recovery while substantially reducing the ash and pyritic sulfur contents.
One approach to meeting this design objective might be an all flotation
process of the general configuration  presented in Figure 6-1.  In this
hypothetical approach, the 8 inch X 0 run-of-mine coal would be fed to a
rotary breaker where the  initial size reduction and removal of harder
refuse would occur.  From the rotary  breaker, the 6 inch X 0 raw coal
would go to a crusher  for reduction to  3/4 inch X 0 before going to a
rod mill for final reduction to 28 mesh or less.  To minimize the creation
of fines, the rod mill would be operated in  such a manner to avoid over-
grinding.  This being  the case, a significant portion of the product
from the rod mill would be plus 28 mesh.  By using a classifier and re-
circulating the oversize  product, as  shown in Figure 6-1, only 28 mesh
X 6 would be fed to the first stage froth flotation cells.  The froth
collected from the first  stage flotation would be fed to second stage
froth flotation cells, where further  cleaning would occur.  The reject
from both stages of flotation would go  to static thickeners. Since the
underflow from the static thickeners  would be comprised of a high per-
centage of very fine particles, it would have to be pumped to filter
presses for dewatering before disposal.  The product  from the second
stage flotation cells  would be partially dewatered by vacuum disc
filters and then further  dried by a disc or  other indirect type thermal
dryer.  A fluid-bed thermal dryer could not  be used under these conditions
due to the fine nature of the clean coal.  Currently, most of the in-
direct type thermal dryers available  are constructed  on a small scale and
                                  289

-------
              1
                                                 FIGURE 6-1
                           HYPOTHETICAL FLOTATION PLANT WITH FINE REFUSE DISPOSAL
                                        SIMPLIFIED PROCESS FLOW SHEET
    770 tph
    8  inch X 0
  20 tph
+ 6 inch
ro
tn
CD
 LEGEND
         COAL
         REFUSE
ROTARY    I  6  inch  X

BREAKER
                                         CRUSHER
                                 3A  INCHXO • 750 tph
                                               2,500 tph
                                               2500  tph
                                                                   0 tph

                                                      750  tph
                                        CLASSIFIERS  !••••••
                          +  28  MESH                 | 28  MESH  X  0
   1st
  STAGE
  FROTH
FLOTATION
                                                                      600  tph
                                                                                                                 210 tph
                                                                   2nd
                                                                  STAGt
                                                                  FROTH
                                                                FLOTATION
                                                                          tph
                                                                                              hJt
                                                                                                      210 tph    TO DISPOSAL
                                                                 VACUUM
                                                                 FILTERS
                              THERMAL
                              DRYERS
                                                                                                          tph • TO STORAGE

-------
use oil as the heat source.  However, as high volume drying operations of
the type required by this hypothetical plant become more common, larger
scale units using coal fired boilers should become available.  Although
the capital cost will not be .influenced to any significant degree, the
fuel consumption cost should be  cut in half.
     Based upon late-1977 equipment and construction prices, a plant of
this general make-up and capacity would require an initial capital in-
vestment of approximately $38 million dollars.  A rough breakdown of
this estimated capital cost is presented in Table 6-1.  The personnel
necessary to operate and maintain a plant of this type would not vary
substantially from that required in a comparable capacity heavy media
facility with thermal drying.  Assuming this 750 tph input plant, produc-
ing 540 tph of clean coal, was utilized at least 40% of the time and
achieved a 96% Btu recovery, the operating and maintenance cost including
capital amortization would be just under $8.00 per ton of clean product.
Based upon a clean coal (10-12%  moisture) having a thermal content of
13,500 Btu per pound, this equates to approximately $0.30 per million Btu.
The major components of this estimated 0 & M cost are listed in Table 6-2.
This total 0 & M cost is greatly influenced by the high capital and power
costs of the fine clean coal and refuse dewatering equipment. Additionally,
the fine grinding of the entire  plant feed contributes significantly to
the overall cost of such a plant.
       Since all the clean coal produced by this  process would be of a
fine size, transportation and handling would  present  problems.  Therefore,
a  fine cleaning plant of this type might be most appropriately located adja-
cent to the using power plant or the  clean coal  transported  pneumatically.
                                    291

-------
                                 TABLE  6-1
                        HYPOTHETICAL  FLOTATION  PLANT
                        WITH  FINE  REFUSE  DISPOSAL
                  PREPARATION PLANT CAPITAL REQUIREMENTS
RAW COAL STORAGE AND HANDLING:
      Raw Coal Storage Area                                       $  300,000
      Raw Coal Belt To Breaker
           42 Inch Wide - 200 Feet @ $520 per foot                   104,000
      Tramp Iron Magnet                                               20,000
      Rotary Breaker including structural work                       250,000
      Raw Coal Belt To Plant
           42 Inch Wide - 300 Feet @ $520 per foot                   156.000
                    Total Raw Coal Storage & Handling Cost        $  830,000
PREPARATION PLANT:
      Crusher -                                      $    90,000
      Rod Mills
           4 @ $395,000                                1,580,000
      Classifiers
           4 @ 40,000                                    160,000
      Conditioning Tanks                                 150,000
      1st Stage Froth Flotation Cells
           10 Banks of 5 cells
             10 @ $65,000                                650,000
      2nd Stage Froth Flotation Cells
           8 Banks of 5 cells
             8 @ $65,000                                 520,000
                                      292

-------
      Vacuum Filters
           12 feet 6 inch diameter, 15 discs
           7 @ $150,000                              $ 1,050,000
      Pumps                                              200,000
            Total Preparation Plant Equipment Cost   $ 4,400,000
      Total Cost of Preparation Plant
           Including Site Preparation, Construction of
           Building, Electrical Service, Piping, etc.
           $4,400,000 X 3.0                                       $13,200,000
OTHER FACILITIES
      Static Thickeners
           200 Foot diameter - concrete
            2 @ $2,000 per foot of diameter                           800,000
      Filter Presses
           7 @ $275,000 (basic equip. Cost)
           7 X 3 X $275,000                                         5,775,000
      Thermal Dryers
           Indirect Disc Type
           (60 tph $1,200,000 full price)
           9 X $1,200,000                                          10,800,000
      Clean Coal Silo
           10,000 Ton Capacity @ $110 per ton                       1,100,000
      Clean Coal Belt To Silo
           42 Inch Wide - 200 feet @ $520/ft                       	104,000
           Total Other Facilities & Equipment                     $18,579,000
                                      293

-------
SUMMARY OF CAPITAL COST
      Raw Coal Storage and Handling                               $   830,000
      Preparation Plant                                            13,200,000
      Other Facilities and Equipment                               18,579,000
      Contingency (Interest during construction, etc.)              4,891,000
                            Total Capital Requirement             $37.500,000
 BASED UPON THE  750  TONS PER HOUR INPUT TO THIS PLANT THE CAPITAL REQUIREMENT
 TRANSLATES TO $50,000 PER TON HOUR INPUT
                                      294

-------
                                  TABLE 6-2

                          HYPOTHETICAL FLOTATION PLANT
                           WITH FINE REFUSE DISPOSAL
                       OPERATING AND MAINTENANCE COSTS*


COST CATEGORY                                    Raw Coal         Clear/cSal
     Labor -

         Supervisory (Non-Union)                 $ 0.04            $ 0.06

         Operating & Maintenance (Union)           0.27              0.38
     Overhead -

         Includes Payroll Taxes, Insurance,
          Welfare Fund, Vacations, Holidays,
          etc. for all Preparation Plant
          Employees                                0.20              0.28

     Supplies

         Operating                                 0.25              0.35

         Maintenance - Repair Parts and
          Materials Associated with
          Routine Maintenance                      0.60              0.83

     Thermal Dryer Fuel -
         Based upon 2600 gal/hr Fuel Oil Con-
          sumption and Cost of Oil @ $0.32/gal     1.11              1.54

     Electricity                                   1.00              1.39

     Other Expenses                                0.10              0-14

     0 & M Cost -
         Not Including Capital Amortization       $3.57             $4.97

     Capital Amortization -
         10 Yrs. - 40% Utilization                 2.18              3.02

     Total Operating & Maintenance Cost           $5.75             $7.99



     Cost Per Million Btu (13,500 Btu/lb)                           $0^30-
 *Extrapolated from comparable  capacity heavy  media  plant  allowing for
  significantly greater  power consumption
                                        295

-------
Another procedure, which would significantly reduce the capital and
operating costs of the plant by eliminating the expensive drying capacity,
might be to transport the product via slurry pipeline to the utility plant.
If the product was to be transported by conventional means, it would be
necessary to consolidate the coal into pellets or briquettes to improve
its handling properties.  Such additional processing capability would
slightly increase the total cost of preparation.  However, the selection
of this or any other transportation approach could only be made after a
careful evaluation of the overall economics of the specific situation.
                                    296

-------
RFPORT nnrilMFNTATTflN PARF
1.
4.
REPORT NO. 2.
TITLE AND SUBTITLE
An Engineering/Economic Analysis
Of Coal Preparation Plant
Operation and Cost
/. AUIHORtb)
Elmer C. Holt, Jr.
9.
12.
PERFORMING ORGANIZATION NAME AND ADDRESS
The Hoffman-Muntner Corporation
8750 Georgia Avenue
Silver Spring, Maryland 20910
SPONSORING ORGANIZATION NAME AND ADDRESS
United States Department of Energy
Solid Fuels Mining and Preparation Division
Washington, D.C. 20545
3.
5.
RECIPIENT'S ACCESSION NO.
REPORT DATE
February 1978
6.
8.
10.
11.
13.
PERFORMING ORGANIZATION
REPORT NO. 5004-2 FR
PROJECT/TASK/WORK UNIT NO.
CONTRACT OR GRANT NO.
ET-75-C-01-9025
TYPE OF REPORT
Final Report
14.
 15.  SUPPLEMENTARY NOTES
16. ABSTRACT - This report  presents  a  discussion  of the  major  physical  coal  preparation
processes currently available and  the  equipment used by  each to  effect  a  separation of
the coal from the undesirable constituents  such as  ash and  pyritic  sulfur.  Further,
eight specific examples of  a wide  range  of  actual preparation  plants  are  examined from
the standpoint of capital and operating  and maintenance  costs  to develop  a  total  cost
of coal cleaning for each plant. The preparation  plants  examined were all operating as
of mid-1977 and span a spectrum of cleaning processes from  a relatively simple  jig plant
to rather sophisticated circuits utilizing  heavy  media,  froth  flotation,  and thermal
drying.
  For the particular plants considered by this study, there was  a range of  cleaning costs
from over $3.00 to nearly $5.00 per  ton  of  clean  coal produced.  These costs are especi-
ally sensitive to the make-up and  performance of  the cleaning  circuit in  addition to the
manner in which it is being operated.  In this latter regard, plant  utilization  can be a
significant factor since it influences the  output over which the fixed  costs are amor-
tized. As evidenced by most of the preparation plants examined,  many  coal cleaning fac-
ilities operate only 30% of the time,  thereby experiencing  a relatively high capital
burden per ton of clean product. To  alleviate this  problem, one  of  the  example  prepa-
ration plants was designed  to include  parallel cleaning  circuitry with  significant
amounts of redundant equipment.  Such  plant configuration,  permits  maintenance  without
shutting down the entire facility.                                                	
 17.  ORIGINATOR'S KEY WORDS
     Coal  Preparation (Cleaning)

     Coal  Preparation Equipment

     Coal  Preparation Plant Operating and Maintenance  Costs

     Coal  Preparation Plant Capital Cost

     Coal  Preparation Plant Utilization

     Coal  Preparation Plant Capital Amortization
18.  AVAILABILITY STATEHEN1
 19.  U.S.  SECURITY CLASSIFICATION OF THE REPORT

                UNCLASSIFIED
21. NO. OF PAGES

          296
 20.  U S.  SECURITY CLASSIFICATION OF THIS  PAGE
                UNCLASSIFIED
                                                              122.  PRICE
*OA GOVERNMENT PRINTING OFFICE: 1978 260-880/84 1-3
                                             297

-------