EPA-650/2-73-019-C
August 1973 ENVIRONMENTAL PROTECTION TECHNOLOGY SERIES
i||||l^
1^
iiliii ill iiii 11 ;iiiiiiiiiiiii
-------
EPA-650/2-73-019-C
FULL-SCALE
DESULFURIZATION OF STACK GAS
BY DRY LIMESTONE INJECTION
VOLUME III -
APPENDICES I THROUGH L
by
Tennessee Valley Authority
Chattanooga, Tennessee
Interagency Agreement TV-30541A
Project Officer: Richard D. Stern
Control Systems Laboratory
National Environmental Research Center
Research Triangle Park, NC 27711
TVA Contracting Officer: Dr. F. E. Gartrell, Director
Division of Environmental Planning
Tennessee Valley Authority
Chattanooga, TN 37401
Prepared for
Office of Research and Development
U.S. Environmental Protection Agency
Washington, DC 20460
August 1973
-------
This report has been reviewed by the Environmental Protection Agency and
approved for publication. Approval does not signify that the contents
necessarily reflect the views and policies of the Agency, nor does
mention of trade names or commercial products constitute endorsement
or recommendation for use .
-------
CONTENTS
Volume 1
Main Text
Page
Abstract v
List of Figures xiii
List of Tables xix
Acknowledgement xxi
Summary and Conclusions 1
Introduction 21
Test Program 31
A. Objectives and Overall Approach 31
B. Test Facility 32
1. Unit 10 Boiler 32
2. Limestone Injection Process Equipment 32
3. Sampling Stations 40
4. Laboratory Capability 41
C. Phase I Shakedown 43
1. Objectives 43
2. Approach 43
3. Results 46
4. Conclusions 77
D. Phase II Dust Distribution Studies 79
1. Objectives 79
2. Approach 79
3. Results 79
4. Conclusions 104
E. Phase III Process Optimization Ill
1. Objectives Ill
2. Approach Ill
3. Results 119
4. Conclusions 164
F. Phase IV Long-Term Operation 171
1. Objectives 171
2. Approach 171
3. Test Results 174
4. Conclusions 198
-------
CONTENTS
Volume 2
Page
APPENDIX A-STATISTICS ON BOILER AND LIMESTONE SYSTEM A-l
APPENDIX B-WATER-COOLED PROBE DEVELOPMENT B'1
APPENDIX C-TESTING, SAMPLING, AND ANALYTICAL PROCEDURES C-l
APPENDIX D-COMPUTER PRINTOUTS FOR PHASE I TESTS D-4
APPENDIX E-INSTANTANEOUS DUST DISTRIBUTION STUDIES E-l
APPENDIX F-LIMESTONE INJECTION EFFECTS ON SOLIDS
COLLECTION SYSTEM F-l
Report and Analysis of Field Tests at Shawnee Station Prepared
for the EPA by Cottrell Environmental Systems, Inc.
APPENDIX G-LIMESTONE INJECTION EFFECTS ON DISPOSAL
WATER QUALITY G-l
Introduction G-l
Evaluation Program G-2
Summary and Conclusions G-31
Data Storage Format G-35
APPENDIX H-ADDITIONAL HEAT REQUIREMENT CALCULATIONS H-l
-------
CONTENTS
Volume 3
Page
APPENDIX I-LIMESTONE FACTORS
Section A, Reactivity with Sulfur Oxides 1-3
I. Introduction and Objectives 1-3
II. Approach 1-3
III. Results and Conclusions 1-4
Limestone Type 1-4
Chemical Form of the Additive 1-4
Particle Sife 1-5
Calcination Temperature 1-5
Catalysts 1-5
IV. Abstracted Results of Individual Projects 1-6
Illinois State Geological Survey 1-6
Tennessee Valley Authority 1-6
Babcock & Wilcox 1-8
Peabody Coal Company 1-8
In-House EPA 1-9
V. Recommendation on Limestone Properties for Application
to the Dry Limestone Injection Process 1-11
Section B, Limestone Availability in the United States 1-13
I. Introduction and Objectives 1-13
II. Approach 1-13
III. Results 1-13
Potential Demand - Power Plants 1-13
Carbonate Rock Reserves 1-16
Mining and Production 1-19
IV. Supply/Demand Relationship of Carbonate Rocks
for Pollution Control 1-22
Proximity of Carbonate Rock Deposits to Power Plants 1-22
Potential Demand Relative to Production 1-22
Costs 1-23
V. Conclusions 1-31
-------
Volume 3
(Continued)
Page
VI. Recommendation for Application to Dry Limestone
Injection and other Limestone-Based Processes
Section C, Definitions
1-35
Section D, References
APPENDIX J-MATHEMATICAL MODELING OF THE LIMESTONE INJECTION
PROCESS
I. Introduction and Objectives J'3
II. Summary of Modeling Activities t J'5
III. Discussion J'23
IV. Conclusions J-26
V. References J-27
APPENDIX K-UTILIZATION OF LIMESTONE-MODIFIED FLY ASH K-l
I. Introduction and Objectives K-3
II. Approach K-3
III. Results and Conclusions K-3
A. Unmodified Fly Ash Utilization K-3
B. Limestone-Modified Fly Ash Utilization K-12
IV. Summary K-19
V. Recommendations K-19
A. Unmodified Fly Ash K-20
B. Wet-Collected Limestone-Modified Fly Ash K-21
VI. References K-22
APPENDIX L-PROCESS ECONOMICS
I. Introduction L-l
Design Premises |__2
Base Case l_.j 1
Actual Investment L-13
Investment Projections L-13
Annual Operating Cost L-18
Lifetime Operating Cost L-24
-------
Volume 3
(Continued)
Page
II. Summary of Results and Conclusions L-27
Investment L-27
Relative Investment Cost Distribution L-27
Annual Operating Cost L-32
Relative Operating Cost Distribution L-36
Lifetime Operating Cost L-36
Results of Sensitivity Analysis L-59
III. References and Abstracts L-88
-------
CONVERSION TABLE
EPA policy is to express all measurements in Agency documents in metric units.
When implementing this policy results in undue cost or difficulty in clarity, the National
Environmental Research Center-Research Triangle Park (NERC-RTP) provides conversion
factors for the particular nonmetric units used in the document. For this report these
factors are:
British Metric
Multiply By To Obtain
feet 3.0480 x 10"1 meters
feet2 9.29 x 10'2 meters2
feet/sec. 3.0480 x 10"1 feet/sec.
feet3/min. 4.720 x 10"1 liters/sec.
grains (troy) 6.48 x 10~2 grams
grains/dry s.c.f. @ 70° F 2.464 grams/meter3 @ 0° C
gallon 3.785 liters
inch 2.5400 x 10'2 meters
micron l.OxlO"6 meters
ounce (troy) 3.1103 x 10' grams
pound 4.536 x 10~J kilograms
pound/in.2 7.03 x 10"2 kg/cm2
quart 9.463 x 10"1 liters
tons/hr. 2.520 x 10"1 kg/sec.
-------
APPENDIX I
Limestone Factors
Section A Reactivity with Sulfur Oxides
Section B Availability in the United States
Section C Definitions
Section D References
-------
1-1
APPENDIX I
LIMESTONE FACTORS
The author discusses those factors which experimentation identified as most
important to the process. These include limestone type, chemical form of the additive,
particle size, calcination temperature, and the effects of catalysts.
Discussed are the activities of the following organizations:
Illinois State Geological Survey
Tennessee Valley Authority
Babcock & Wilcox
Peabody Coal Company
Environmental Protection Agency
Included are recommendations for additive preparation for the dry limestone
injection process.
Regarding availability, the author discusses the potential demand for limestone, its
distribution, mining, and production as well as the supply/demand relationship of carbonate
rocks for pollution control.
Transportation and costs for limestone use at power plants are covered.
Recommendations for application to dry limestone injection and other
limestone-based processes indicate the use of the available information for study by a
potential user.
-------
1-3
Section A
Reactivity with Sulfur Oxides
I. Introduction and Objectives
The activities of the Research Laboratory Branch, Control Systems Division in
support of the high priority development of throw-away processes, have been directed
toward specific areas relating to the limestone processes. During the last 2-1/2 years major
emphasis has been on acquiring information on the dry injection process which would be
required for application of the process on a wide scale. Earlier, a little was known about the
mechanism and rate of reaction between limestone and sulfur oxides, and differences
between limestones had not been related to their potential reactivity. This information was
vital for optimization of the process. Limestone injected into a power boiler must calcine
(evolve CO2 to become lime) and react with most of the sulfur oxides present—all within 2
seconds or less. If limestone is injected too close to the highest temperature combustion
zone, the lime produced will be deadburned and unreactive. If the limestone is injected
higher than or farther from this zone, the residence time for the lime particles in the zone of
the boiler favoring reaction with sulfur oxides will be seriously reduced. The overall
objective of this activity was to support the full scale process optimization at the TVA
Shawnee Steam Plant by recommending limestone type, particle size, and other sorbent and
process parameters.
II. Approach
The general approach toward meeting the first objective was to measure reaction
rates and capacities of limestones and then correlate results with their mineralogical,
petrographic, and chemical analyses. Bench scale calcination and sulfation tests were
conducted in-house in fixed-bed and differential reactors and under contract in a standard
laboratory thermogravimetric-analyzer apparatus by TVA and a dispersed phase reactor by
Battelle. Under contract with Illinois State Geological Survey (ISGS) and TVA,
petrographic and electron microscopy, X-ray, and additional chemical analyses were
performed on raw, calcined, and sulfated samples from the bench-scale tests. Correlations
between results of these analyses and the bench-scale reactivity results were then attempted.
Pilot-scale tests were conducted under contract with Babcock & Wilcox and Peabody Coal at
conditions simulating, as closely as possible, actual furnace injection conditions. These tests
were conducted for comparison with the bench-scale data and limestone reactivity
correlations developed.
The approach toward the second objective, determining the characteristics of dead
burning, was to conduct full-scale tests with pure additive in an oil-fired furnace. Pure
additive and the oil-fired furnace were selected in order to avoid possible chemical changes
during dead burning which can occur by reaction of CaO with oxides of silicon, iron, and
aluminum present as a limestone impurity and in coal fly ash. Injection with the fuel was
-------
1-4
selected to maximize residence time at high temperatures for fast calcination and sulfation.
With this approach it was possible to characterize the phenomena of dead burning
specifically in terms of physical changes and their relationship to reactivity with SO2
Concurrent with this activity, methods for testing the degree of dead burning (loss of CaO
reactivity) were evaluated through literature searches, analysis of various chemical and
physical properties of different limestones calcined at a range of temperatures, and
laboratory testing. More promising tests were applied to samples from pilot scale tests by
Babcock and Wilcox and from early injection tests at the TVA Shawnee Steam Plant.
III. Results and Conclusions
Integrated results of the projects and correlation with other investigations are
presented by major item. These are followed by abstracted results of the individual projects.
Limestone Type: All studies have noted marked differences in reactivity between
limestone types. In-house, fixed-bed experiments showed a five-fold range in SO2 capacity:
marl and chalk were the best. Differential reactor results were widely spread: marl was the
•¥•
best^ Pilot plant data also showed the pronounced effect of limestone type: aragonite was
the best at Peabody Coal,4 and marl was the best at Babcock & Wilcox.3 Initially these
results may not appear to agree; however, it is significant to note that the best performing
limestone types were fine grained and generally high in calcium carbonate, as opposed to
dolomitic materials. Since calcitic stones (marl and chalk) and aragonite are highly reactive,
it appears that both calcium carbonate crystal structures can be used as long as the
crystallites (or grains) are small.
Other investigators have compared limestones (i.e., calcites) and dolomites.
Goldschmidt1 ° and Brocke12 showed that calcitic additives were more effective than
dolomitic additives. A good detailed examination of the effect of limestone type is given by
Borgwardt and Harvey.6
Chemical Form of the Additive: Many different forms of carbonate rocks have been
tried in tests ranging from laboratory to demonstration scale. Most investigators have
compared hydrated lime, calcined limestone and uncalcined limestone although dolomitic
lime, half calcined dolomite, hydrated dolomitic lime and others have been used on
occasion. In general, the ranking of reactivity is hydrated lime > limestone (uncalcined) >
lime.3'7'9 However, the optimum temperatures of injection for different forms of the
additive may span 752° F and a comparison at a given temperature is misleading. Zentgraf7
reports that limestone injected at its optimum temperature (2732° F) is slightly more
effective than hydrated lime at its optimum temperature (2102° F). Even in tests where the
hydrate is consistently better, the difference is insufficient to warrant the extra cost of the
hydrate versus the uncalcined limestone. Tests with dolomitic counterparts of the limestone
(i.e. calcite) chemical forms also show the hydrate to be the most reactive but still less
reactive than the hydrated lime.1 °
^Superscripts refer to references on pages 1-35.
-------
1-5
Particle Size: Except in certain cases, all studies noted some increase in reactivity
with decreasing particle size. It appears that the effect of particle size is not the same for all
stones but is determined primarily by the pore size. Small pores lead to the highest
sensitivity between calcine reactivity and particle size. Calcines with very large pores may
show no dependence of reactivity on particle size. In differential reactor experiments not
much improvement was noted below 100 u.
At Babcock & Wilcox, particle size was related to specific surface area by the
Lea-Nurse technique (air permeability). Depending on the grindability, minus 60 mesh
(approximately 250 ju) produces 2000-6000 cm2 /gram in area. The maximum reactivity was
recorded when the surface area reached 2000 cm2/gm or more. Analyses of reacted fly ash
showed that particles between 2 and 6p contained 8 to 12 percent sulfur (as SO3), and
particles greater than 30jn had less than 4 percent sulfur.
These results are generally supported by Battelle6 and Zentgraf7 who reported that
above 50 and 60jj respectively, the particle size was inversely porportional to the SO2
reactivity while below these values particle size had no effect. In addition, Ishihara8
reported that for particles below lOp the initial reaction rate increased as the particle size
decreased and Tanaka9 reported that for the 3 sizes he studied (all greater than 74p) a
decrease in particle size gave an increase in removal. Zentgraf7 also reported that as the
particle size increases the pore size decreases.
Calcination Temperature: All experiments showed that higher calcination
temperatures give rise to loss of reactivity known as dead burning. Both in-house and TVA
studies showed that higher temperatures lead to growth of crystallites with a corresponding
loss of surface area and pore volume which accounts for the loss of reactivity. In-house,
Peabody Coal, and Babcock & Wilcox data show that injection of limestone with the fuel or
near the flame gives a dead burned stone with little SO2 removal efficiency. This conclusion
is supported by reports of Goldschmidt1 ° and Ishihara.11 Optimum injection temperatures
have been reported to be 2500-2700° F3, 2000-2450° F4 , 2732° F7, and 1652-2192° F8
depending on the system tested. The time-temperature profile is actually the controlling
factor.
Catalysts: In-house fixed-bed studies showed no evidence of the limestone-SO2
reaction being catalyzed by minor constituents in limestone. Both ISGS and TVA showed
an improvement in reactivity with sodium content in the stone but no general conclusions
could be drawn. At Babcock & Wilcox, vanadium decreased the additive effectiveness but
iron oxide improved it slightly. It was concluded that the improvement was due to higher
surface areas, not the iron oxide. This is not in agreement with Ishihara8 who found
limestone containing over 1 percent Fe2O3 were 50 percent more effective than those with
less than 0.5 percent during oil-fired pilot plant experiments. However, SO2 removals were
not increased by addition of ferric oxide powder or yellow ochre to the limestone.
-------
1-6
IV. Abstracted Results of Individual Projects
Illinois State Geological Survey1-Detailed petrographic, mineralogical, and chemical
analysis of 26 carbonate rocks were made and compared with the capacity (3-1/2
reaction period) and differential reactivity (120 second reaction period) of calcined
specimens for sorption of SO2. A wide range of petrographic and SO2 sorptive properties
were revealed.
Three petrographic and chemical properties appear to be useful indexes of the SO2
sorption capacity: the pore volume, the grain size, and the sodium oxide content of the
rocks. The larger the pore volume, the greater was the sorption capacity of the rock. Pores
with a maximum chord length between 2 and 16/j appear to have the most influence on this
behavior. In general, the finer the grain size of the rock, the higher was the sorption
capacity, although certain samples showed an opposite correlation owing to the effect of
intercrystalline pores in the crinoidal fossil fragments abundant in some of the samples. Of
the 15 chemical elements analyzed, only sodium showed a correlation trend with the SO2
test data. The sodium present in the samples increased with increasing sorption capacity.
The reaction products of the samples calcined at 1796° F for 2 hours and exposed to
sulfur oxides in laboratory tests are solid grains of anhydrite (CaSO4). Electron microscopy
shows two types of behavior: the calcines of the Iceland spar calcite absorbed sulfur on the
outer surface of its particles, whereas in calcines of a porous limestone, absorption took
place throughout the particles. Sulfation occurred on the outer surfaces of particles by
multiple nucleation of anhydrite crystallites, which enlarged until they abutted each other
to produce a tightly interlocking texture of subrounded grains.
The relatively high SO2 reactivity observed for chalks, calcareous marls, and oolitic
aragonite sand samples is believed due mainly to the high pore volume and fine grain size of
these carbonate rocks. Geologically, high pore volume is indicated by the relatively
unconsolidated nature of these rock materials.
Tennessee Valley Authority2—The reactivities of 35 stones were measured and
correlated with mineralogical and crystallographic properties.
Calcination of the limestone proceeds from the outside surface toward the center of
each particle. The rate of calcination is affected by the reaction temperature, the particle
size of the stone, the crystallite size of the carbonate mineral in the stone, the relative
amounts of magnesium and calcium in the stone, and the partial pressures of CO2 and SO2
in the furnace atmosphere. The reaction of CaO with SO2 and O2 at 1682° F is first order
with respect to the partial pressure of SO2 in the range 1 to 8.4 percent by volume, zero
order with respect to the partial pressure of O2 in the range 1 to 10 percent by volume, and
zero order with respect to the loading of product until the layer of CaSO4 completely
shields the available reaction surface. Below 1182° F, the formation of sulfite predominates
over that of sulfate; the oxidation of sulfite to sulfate begins at about 1332° F, a
temperature range in which the sulfite also begins to decompose and disproportionate.
Disproportionation of sulfite at 1612° F is prevented by the presence of oxygen or CO2,
-------
1-7
either of which promotes the formation of sulfate. The first-order specific rate constants for
the decomposition of CaSO3 and CaSO4 and the loss of reactivity (dead burning) of a high
calcitic (Colbert) limestone were expressed in Arrhenius form.
Water vapor affects the rate of reaction of SO2 with MgO but not with CaO; the
reaction with MgO is too slow to be important under injection conditions. The direct
substitution of SO2 for CO2 in the limestone also is too slow to be significant under furnace
injection conditions. The sulfation reaction occurs simultaneously with the calcination
reaction when the rate of the calcination reaction is low; sulfation is more rapid, however,
when there is a relatively large surface of unreacted CaO. The products of the sulfation
reaction retard the calcination reaction when the two reactions occur simultaneously.
The physical properties of a calcine and its reactivity with SO2 are influenced
markedly by the texture of the parent limestone from which the calcine is formed. An
Iceland spar, of mean crystallite size 7125° A., calcined slowly below 1742° F because of its
high thermal stability, and yielded a calcine with small pores and small crystallites of CaO. A
very pure calcitic limestone, of mean crystallite size 3875°A, yielded larger crystallites of
CaO than did the Iceland spar under the same conditions, but the pore volume was larger
and more favorably distributed between different sized pores for reaction with SO2 • Between
1832° F and 2012° F the calcines of both materials showed a minimum in pore volume,
which was interpreted as the end of sintering and the beginning of recrystallization of the
CaO. During sintering, small pores coalesce into larger pores with small changes in the
crystallite size of the oxide; during recrystallization the crystallites grow into massive single
crystals of CaO at rates proportional to the crystallite size of the original carbonate. The
Iceland spar was less reactive with SO2 than was the calcitic limestone under all the
experimental conditions tested because of its slower calcination, its unfavorable pore-size
distribution and pore volume, and its more rapid recrystallization. Electron microscope
photographs of cleaved sulfated particles of these stones clearly showed the reaction zone
between oxide and sulfate and the growth of the crystallites of sulfate at the outer surface.
The calcination, isothermal sulfation, and polythermal calcination-sulfation of 35
limestones were studied and the distinguishing characteristics of each reaction were
correlated with the chemical and mineralogical properties of the stones. Six measures of the
capacity and rate of reaction with S02 were correlated with the chemical and mineralogical
properties of the stones, as well as the reaction parameters. Multiple correlations of the
capacity and rate parameters with the properties of the stones yielded equations from which
the reactivity of a stone could be predicted from its chemical and mineralogical
characteristics. The equations were tested with five stones considered for use in the Shawnee
full-scale tests, using the reaction rate data at five temperatures obtained by Battelle in the
dispersed-phase reactor. The prediction of the polythermal capacity for absorption of SO2
from the chemical and mineralogical properties of the stones correlated well with the
Battelle reaction rates at temperatures below 1724° F, but not at higher temperatures. No
other predicted reactivity measure correlated significantly with the Battelle rate at any
temperature.
-------
1-8
Although the data obtained at the temperatures accessible in this experimental study
(maximum of 1742° F) do not extrapolate well to the higher temperatures that are
encountered in actual power plant combustion chambers, the properties of stones that were
shown to be desirable at low temperatures probably will be advantageous at the furnace
temperatures also. Perhaps the major difference to be expected between the results obtained
at low temperature and those anticipated at high temperatures is the marked increased in
the rate and extent of dead burning at the high temperatures, as indicated by the results of
the X-ray examinations. The data indicate no way of avoiding the detrimental effect of
rapid dead burning at temperatures above about 1922° F. They indicate that stones that
contain the smallest amounts of impurity minerals and whose rhombic carbonates are
primarily calcitic and are present as the smallest crystallites will be most effective for
injection into the combustion chamber. Increasing the sodium content of the stone increases
its reactivity; however, if iron is present, it should be in the form of limonite or goethite
rather than in the lattice of the stone.
Babcock & Wilcox3—Using a small pulverized coal pilot plant, 415 tests were run
with 129 different additives. The variables studied relative to additive reactivity included
temperature at the point of injection, residence time of the additive in the reactive zone,
additive surface area, chemical form of the additive (e.g., carbonate, oxide, or hydrate) and
catalyst content.
In general, raw limestones and dolomites were most effective when injected into the
pilot plant at points corresponding to mid- and upper-furnace regions of full-scale units. This
behavior appeared in part to be an effect of gas temperature, but particle residence time was
probably the most important factor. Feeding the raw additives with coal or upstream of the
combustion zone resulted in very poor performance, indicating that dead burning took place
under these conditions.
Increasing additive specific surface area to about 2000 cm2/g, or slightly higher,
improved additive performance to a maximum. Larger surface area gave no further
improvement, and in some cases the amount of SO2 removal was actually decreased,
probably due to agglomeration of very fine particles.
Hydrated stones were slightly more effective than their parent raw material,
particularly at lower (approximately 1900° F) injection temperatures, but not to the extent
that the cost of additive processing would be justified. Precalcining the stones in most cases
decreased effectiveness of the additives.
Iron oxide (as Fe2 O3 and Fe3O4) was found to improve additive effectiveness
slightly while vanadium (as V2OS) actually decreased it. It was concluded that improved
effectiveness resulted from higher surface areas, not the iron oxide.
Marl, a kind of limestone, was the most effective type of additive tested under most
conditions.
Peabody Coal Company4—Tests were conducted in a pilot size chain-grate stoker
with an aragonite, a calcite, two types of dolomite, and a chalk. "Red mud," the dried
-------
1-9
tailings from the manufacture of alumina from bauxite was also tested. Variables related to
additive reactivity included temperature at the point of injection and particle size.
Calcination and calcium oxide utilization were determined.
Sulfur dioxide removal ranged from 6 to 65 percent depending upon operating
conditions. A comparison of sorbents, compared on a per-unit-weight-of-raw-stone basis,
shows that the calcites and aragonite remove more SO2 than do dolomites. Sorbent 1683,
an aragonite, was the most effective material tested when injected into the gas stream.
However, it was relatively ineffective when mixed with the coal prior to combustion.
The particle size study was not as definitive as desired due to overlapping particle
sizes between injected screen cuts. A step-wise regression analysis of 59 runs, with samples
1337 and 1684 (dolomite), 1683 (aragonite), and 1359 (calcite) combined, indicated that
reducing the sorbent particle size leads to higher SO2 removal rates.
Each sorbent, except red mud, was injected at temperatures from 1800° F to
2450° F. Computer results on all test data combined did not indicate a significant
correlation between SO2 removal and injection temperature. However, graphical analysis
did indicate that temperature was a significant parameter for some of the individual samples.
The degree of sorbent calcination varied directly with temperature and ranged from
50 to 60 percent at 1800° F to more than 90 percent at 2450° F. Above 2000° F, particle
size did not appear to significantly affect the degree of calcination.
Calcium oxide utilization varied from 6.30 percent (for particle sizes greater than
100 mesh) to 59.50 percent (for 200 mesh sizes). Aragonite, Sample 1683, and dolomite
Sample 1684, demonstrated the greatest utilization.
Red mud, when injected into the gas stream at 1200° F to 1300° F and 2000° F was
relatively ineffective in removing SO2 -
In-House EPA5—Eighty-six carbonate rock samples were tested in a fixed-bed
reactor to determine their capacity to react with flue gas containing SO2 . Although most of
the work was performed with the carbonate and the oxide at standard test conditions,
supplementary tests were made on hydrates, oxides, and carbonates over a wide range of
reaction temperatures and calcination conditions. Differences between the samples were
related only slightly to chemical composition; porosity, as measured by mercury pore
volume best explained variations in capacities of the samples. Chalks and oolitic samples
were the most efficient absorbents; magnesite and Iceland spar the least efficient of the
stones tested.
The SO2 reaction kinetics of calcines prepared from 11 rock types representing a
broad spectrum of limestones and dolomites, which were examined by ISGS, were
determined at 1800° F. Stones of various geological types yield calcines of distinctly
different physical structures that show correspondingly large differences in both rate of
reaction and capacity for SO2 sorption. Pore size and particle size tog-ether determine the
extent to which the interior of individual particles react. Particles smaller than 0.01 cm (100
u) with pores larger than O.ljj react throughout their internal pore structure at a rate
-------
1-10
directly proportional to the B. E. T. surface. The rate decays exponentially as sulfation
proceeds until the pores are filled with reaction product. The ultimate capacity of small
particles is determined by the pore volume available for product accumulation, generally
equivalent to about 50 percent conversion of the CaO in limestones. Variations in
effectiveness of carbonate rocks for flue gas desulfurization are explained by the physical
properties of their calcines, which are related to the crystal structure of the original rock.
The high reaction rates achieved in the limestone injection process apparently result from
the large surface area existing for short periods immediately following the shock dissociation
of CaCO3.
The relative ranking of calcines with respect to isothermal rate of reaction with SO2
at 1796°F is: marl > high purity limestone > Iceland spar > aragonite > marble. Magnesite
reacts only slowly with SO2 at any temperature between 1004 and 1796P F.
The relative ranking of limestones with respect fo fixed bed capacity at 1796° F with
-18 +20 mesh particles (approximately 840-1000 u) is: marl chalk > oolite > dolomite >
calcite > marble> magnesite> Iceland spar.
The rate of reaction increases with decreasing pore size until a critical pore diameter
of about O.lu is reached. Presumably pores smaller than O.lu are rapidly blocked by
reaction products. Maximum rate results when B. E. T. surface area is in the region of 3.5
M2/g (corresponding to pore diameters of 0.2 - O.Sjj) under isothermal reaction conditions.
The total SO2-sorption capacity increases with increasing pore size. Furthermore,
the capacity of limestones is correlated to the area of pores greater than 0.3)u but not to B.
E.T. surface area.
Both rate and capacity of SO2 sorption are highly dependent upon particle size. The
effect of particle size is not the same for all stones, but is determined by the size of the
pores.
Small pores lead to the highest sensitivity between the reactivity of calcines and
particle size. Calcines with very large pores may show no dependence of reactivity upon
particle size.
Loss of reactivity because of high calcination temperatures (dead burning) is
attributed to growth of CaO crystals and the subsequent loss of surface area and pore
volume. During sintering and CO2 evolution, small pores coalesce into larger pores with
small changes in crystallite size of the oxide. At excessive temperatures recrystallation
occurs and the crystallites grow into massive single crystals at rates proportional to the
crystallite size of the original carbonate. Since loss of surface area and loss of pore volume
are similar functions of increasing calcination temperature, both reaction rate and capacity
of dead-burned stones are lost proportionally.
Four reactivity tests—flue gas absorption, SO2 absorption, CO2 absorption, and
hydration weight gain were found to be suitable as dead-burning tests for samples of limited
size diluted with fly ash. The last three are considered sufficiently uncomplicated to be used
as field tests.
-------
1-11
V. Recommendations on Limestone Properties for Application to the Dry Limestone
Injection Process
a. A fine-grained (e.g., having small crystallites) high calcium carbonate stone should
be used. While many common limestones are of this type, marl, aragonite, and chalk are
almost always fine grained. Many deposits of chalk and marl are sufficiently pure for the
injection process and most deposits of aragonite are very pure.
b. Injection of uncalcined limestone is indicated except where only injection at low
temperature (< 1800° F) is possible. In this case lime hydrate should be used.
c. The additive should be finely ground. While improvement does not appear to be
significant below lOOjJ, a directional improvement has been shown. A particle size of 90
percent minus 300 mesh (approximately 50jj) is preferable.
d. The additive should not be injected with the fuel or near the flame. The optimum
injection point is a function of the system to be controlled but should be approximately
2000-2200° F. The optimum injection temperature may be higher in boilers where the
residence time in the hottest zone is very short. In any case the injection point should be
located so as to insure complete calcination without dead burning.
e. The hydration weight gain test for dead burning is recommended since it is
independent of the degree of sulfation.
-------
1-13
Section B
Limestone Availability in the United States1
I. Introduction and Objectives
A great deal of emphasis is being placed on the development of processes which
remove sulfur oxides from the stack gases of plants which burn coal or oil as a primary fuel.
Several of these processes are based on the use of limestone or dolomite as the sorbent for
the sulfur oxides. The use of these materials to control sulfur emissions is contingent upon
several factors. Among these, the proximity of adequate carbonate rock deposits to
potential users and the relationship of carbonate rock production to possible demand,
appear to be most important in establishing the relative merits of any carbonate rock-based
process. The objective here was the determination of the availability and costs of limestone
and similar materials throughout the contiguous United States to provide a basis for
determining the feasibility and economics of limestone-based SO2 removal processes for
typical plant sites.
11. Approach
Search of publications and communications with Federal and state government
agencies, trade associations, and various crushed stone or limestone producers were the
sources of the data presented. The data was gathered on a national, regional and state-wide
basis. Since the objective is primarily concerned with limestone availability as it relates to
potential consumption by fossil fueled power plants, the regions were chosen to coincide
with those defined by the National Coal Association. Materials covered include limestone,
dolomite, chalk, marble, marl and shell. Location of deposits, production rates, f.o.b.
quarry costs, transportation methods and costs, expected cost increases, uses, chemical
composition and physical properties were covered. Summary results most germane to this
report follow. Additional details in these and other areas may be found in the references
provided.
III. Results
Potential Demand - Power Plants
Most of the power capacity from fossil fuel-fired power plants in the United States
occurs in the eastern half of the country. Figure 1 shows the location of the major (>200
MW) power plants in the United States which burn either coal or oil as the primary fuel.
Included are a few plants which, although not yet constructed, are being designed
exclusively for either coal or oil and are scheduled to be on stream by 1975. Of the 275
plants shown, 84 percent are coal-fired. The oil-fired plants are all located along the eastern
coast, with most of these in the northeast. About 90 percent of all power plants shown are
located east of the Mississippi River, with locally high concentrations in the northeastern
quarter of the country, particularly in many of the major metropolitan areas.
1, Adapted from references 13 and 14.
-------
FIGURE 1
MAJOR THERMAL POWER PLANTS IN THE UNITED STATES
BURNING COAL OR OIL AS THE PRIMARY FUEL
2 PLANTS WITHIN
THE NEW YORK CITY
LIMITS BURN COAL.
5 PLANTS BURN OL.
NOTE:
MAJOR POWER PLANTS ARE DEFINED
AS THOSE HAVING INSTALLED GENERATING
CAPACITIES OF 200 MEGAWATTS OR MORE.
SOURCES:
I Principal Electric Facilities, Faderol Power Commiscion,
(1970). (S«ri«i of (cyan mep<)
2. Steam-Electric Plant factors SI97O Edition. Notional
Coal Association. Wathing:on. D.C.. (November I97O).
-------
1-15
Based on 1969 fuel consumption statistics, an estimated 20 million tons of sulfur
oxides were emitted by power plants in the United States. Assuming 1.25 stoichiometry,
more than 40 million tons of limestone would have been required to remove these oxides
from the stack gases. This potential limestone demand, which assumes that all power plants
use a limestone-based process for sulfur removal, has been broken down by region, with the
regions being defined as follows:
Region
New England
Middle Atlantic
East North Central
West North Central
South Atlantic
East South Central
West South Central
Mountain
Pacific
States Included
Connecticut, Maine, Massachusetts,
New Hampshire, Rhode Island,
Vermont
New Jersey, New York, Pennsylvania
Illinois, Indiana, Michigan, Ohio, Wisconsin
Iowa, Kansas, Minnesota, Missouri, Nebraska,
North Dakota, South Dakota
Delaware, Florida, Georgia, Maryland (includ-
ing Washington, DC), North Carolina, South
Carolina, Virginia, West Virginia
Alabama, Kentucky, Mississippi, Tennessee
Arkansas, Louisiana, Oklahoma, Texas
Arizona, Colorado, Idaho, Montana, Nevada,
New Mexico, Utah, Wyoming
California, Oregon, Washington
Table 1 itemizes potential demand by region. The East North Central region far
outranks any other region in potential limestone requirements with over one-third of the
total. With the exception of New England, all regions in the eastern half of the country had
potentially large demands for limestone.
-------
1-16
Table 1
Potential Limestone Demand by Power Plants in the United States
Region Limestone (103 Tons) °/0 of Total
New England 1,369 3-4
Middle Atlantic 6,583 16-2
East North Central 14,307 35.1
West North Central 2,738 6-7
South Atlantic 8,471 20-8
East South Central 5,645 13-9
West South Central 5
Mountain 1,351 3.3
Pacific 266 0-6
Total 40,735 100.0
Carbonate Rock Reserves
Deposits of carbonate rocks, including limestone, dolomite, shell, marble, and marl,
occur in some form in every state. Total reserves have never been estimated, but are known
to be enormous.
Figure 2 shows the distribution of surface carbonate rocks in the United States and
includes limestone, dolomite, and marble. The map shows that surface deposits of carbonate
rocks occur throughout the nation but are particularly in evidence in the eastern half of the
country. A band of deposits beginning in Vermont extends southward along the
Appalachian Mountains into central Alabama. Extensive deposits are found in the state
surrounding the Great Lakes, reaching southward into northern Alabama. Large areas of
Minnesota, Iowa, and Missouri are covered with carbonate rocks and broad outcrops occur
in Kansas, Oklahoma, Arkansas, and Texas.
Particularly in the central lowlands, carbonate rock deposits frequently occur as
thick, horizontal formations covering large areas. In general, the deposits found in western
states are different. They commonly occur as steeply dipping or vertical beds of small areal
extent. However, notable exceptions to this are found, particularly in Colorado, Arizona,
and New Mexico where large outcrops occur.
Limestone occurrences, including chalk but excluding dolomite, are shown in Figure
3. The map is similar to Figure 2 and shows that although limestone is found throughout the
-------
FIGURE 2
CARBONATE ROCK DEPOSITS IN THE UMITED STATES
-------
00
ij=3 CHALK DEPOSITS
•H LIMESTONE DEPOSITS
FIGURE 3
DISTRIBUTION OF CHALK AND LIMESTONE DEPOSITS IN THE UNITED STATES
(REPRINTED FROM U.S. BUREAU OF MINES BULLETIN NO. 395)
-------
1-19
country, the more numerous and extensive deposits occur in the eastern half of the nation.
In the western states, the deposits tend to be discontinuous and relatively small in areal
extent.
The formations shown in Figure 3 include limestones of different degrees of purity.
Estimates have been made that only about 2 percent of the known reserves of commercially
usable limestone is chemical grade (> 95 percent carbonate content), and that the bulk of
these reserves will be exhausted in 40-50 years. Much of this high purity limestone occurs in
the area extending from the Great Lakes southward to Alabama.
Chalk deposits are shown in several of the central states and in a curving belt
through Alabama and Mississippi. In general, they are not high purity limestones, but locally
they may contain over 95 percent calcium carbonate.
Figure 4 shows the location of high grade (> 25 percent magnesium carbonate)
dolomite quarries. Although originally drawn in 1941, it is a useful guide to the important
occurrences of dolomite. As with limestone, the largest deposits are located in the eastern
half of the country. Two major areas are noted. First a belt of dolomite extends from
Vermont to central Alabama along the Appalachian Mountains. This coincides quite well
with a similar band of limestone previously noted. Second, large formations of dolomite
occur in the states encircling the Great Lakes. These deposits coincide with or adjoin large
limestone deposits in the region.
The most significant deposits of marble are found along virtually the entire length of
the Appalachian Mountains in the east, and as scattered occurrences in the Rocky
Mountains in the west. Although eastern marbles are predominantly calcitic (high calcium),
dolomitic types also occur. Both types are found in the west.
Shell limestone occurs primarily in Gulf Coastal waters, but it also is found in bay
waters along both the east and west coasts. It is usually a very pure type of calcium
carbonate.
Marl deposits exist in several areas, notably around the Great Lakes, and along the
southeastern coastal plain. This soft, relatively impure form of calcium carbonate varies
considerably in character, that of the Great Lakes area being precipitated calcium carbonate,
while that of the coastal plain is an impure shell deposit. Limited occurrences in other
regions are generally impure chalks or soft limestones.
Mining and Production
Carbonate stones are recovered by several methods, including underground mining
and dredging but quarrying is employed most commonly. After removal of overburden and
primary blasting of the stone, various crushing, grinding, sizing, and cleaning operations are
performed to produce a range of marketable products. A large, modern quarry is an
expensive, complex, and highly mechanized unit.
Over 4,700 quarries, producing 861 million tons of crushed stone of all types, were
in operation in the United States in 1969. Since production of crushed carbonate rocks
totaled 652 million tons, it can be assumed that, roughly, over 3,500 of these quarries
-------
oo
ro
10
FIGURE 4-
LOCATION OF HIGH-GRADE DOLOMITE QUARRIES IN THE UNITED STATES
(REPRINTED FROM U.S. BUREAU OF MINES INFORMATION CIRCULAR NO. 7192)
-------
1-21
produced limestone, dolomite, and related stones. More than one-third of all quarries had
annual production rates of less than 25,000 tons. The large operations (over 900,000
tons/year) produced one-third of the total crushed stone, although they represented less
than 4 percent of the total number of quarries.
Crushed carbonate rock production in the United States in 1969 was distributed as
follows:
106 Tons
Limestone
Dolomite
Shell
Calcareous Marl
Marble
Total 652
No production of any type was reported in three states, viz., Delaware, New Hampshire, and
North Dakota. These states, plus Louisiana, were the only states which did not produce any
limestone. Dolomite was produced in twenty-four states, chiefly in the north-eastern quarter
of the country.
Production of limestone and dolomite, by region, was a follows:
106 Tons
New England 2.4
Middle Atlantic 90.9
East North Central 185.6
West North Central 92.5
South Atlantic 87.5
East South Central 81.3
West South Central 58.3
Mountain 10.7
Pacific 18.8
Total 628
Nationwide, Pennsylvania and Illinois were the leading producers of limestone and dolomite,
respectively. Within most regions, production rates of individual states varied from near zero
to tens of millions of tons. The New England and Mountain regions, however, had fairly
uniform and low outputs. The East North Central region was also an exception, with all
states reporting large quantities of limestone and dolomite, ranging from 16 to 55 million
tons.
Shell was dredged from bay waters along all three coasts. However, 83 percent came
from Texas and Louisiana, with the latter being the leading producer. Small quantities of
-------
1-22
marl were produced in Indiana, Michigan, Minnesota, Mississippi, Nevada, South Carolina,
Texas, and Virginia. Eighteen states, principally in eastern and western mountainous regions
quarried marble, with Alabama recording the highest production at 632,000 tons.
IV. Supply/Demand Relationship of Carbonate Rocks for Pollution Control
Proximity of Carbonate Rock Deposits to Power Plants
Comparison of Figures 1-4 indicates that the major deposits of carbonate rocks
largely coincide in location with the power plants. This is particularly true in the East North
Central region where huge reserves of stone occur. Both high calcium limestone and high
grade dolomite abound and many deposits are found near the major power generation
centers throughout the region.
The New England region is not as fortunate. While the power plants are located
primarily in coastal areas, the rock deposits occur in the mountainous western sections.
Most of the deposits are highly crystalline stone or marble and many are dolomitic. The
suitability of these materials would have to be determined before including them as a
possible source.
Availability of stone should not be a problem for power plants in the Middle
Atlantic region. All types of stone occur and nearby deposits can be found. Plants in
western and eastern Pennsylvania, particularly, are fortunate in that large reserves of high
grade stones are present.
In the South Atlantic region, most plants are located near an adequate source of
stone, particularly if the crystalline limestones and dolomites of the mountainous areas
prove suitable. Several coastal plants could use shell or coral limestone, or marl. However,
for some inland power plants in North Carolina, for example, no nearby deposits exist.
Large quantities of high calcium limestone occur throughout the East South Central
region and power plants should experience no difficulty in obtaining adequate supplies.
Many plants located in Alabama and Tennessee also could obtain dolomite quite easily.
The less abundant and more widely scattered carbonate resources of the western
states are of minor importance, since there are few coal-fired power plants in this area. With
the exception of the two power plants located in North Dakota, which are far removed from
any commercially important carbonate deposits, the few plants that do exist are fairly near
reserves of high calcium stone.
Potential Demand Relative to Production
As previously mentioned, the potential demand for limestone by coal-and oil-fired
power plants in 1969 exceeded 40 million tons. This represents only 7.3 percent oFthe
national limestone production of 559 million tons. Dolomite production, on the other hand,
was roughly 60 percent greater than the potential demand. Shell production was only
one-half of the demand. The quantities of calcareous marl and crushed marble quarried were
relatively insignificant. Obviously, limestone is the only stone produced in sufficient
quantities to warrant nationwide consideration as an agent for SO2 removal. Dolomite and
-------
1-23
shell, however, are quarried in large enough amounts to make them important materials in
some regions. Marl and crushed marble may be useful in certain localities where the other
rocks do not exist but their limited occurrence and production do not permit wide-scale use
of these materials.
Table 2 shows the relationship of limestone and dolomite production to potential
demand, by region and state. The third column of the table is the ratio of total limestone
and dolomite production to potential demand, for 1969.
With the exception of New England, the eastern regions of the country all have large
relative supplies of limestone and dolomite. There are some exceptions to this among the
individual states. New Jersey and Delaware have a potential need which exceeds their
production. Adjacent states, however, are large producers of stone and could provide the
necessary tonnages. Mississippi and both of the Carolinas have low relative supplies of stone.
If they could not otherwise be supplied, marl deposits which occur extensively in all three
states could be used. Georgia and West Virginia, with comparatively low relative supplies,
could easily obtain needed stone from surrounding states. It is interesting to note that the
region with the highest limestone demand, i.e., the East North Central region, also has the
highest limestone and dolomite production.
The New England region faces a shortage of limestone and dolomite, with two states
producing less stone than potentially required. The marble resources of the region could
improve the situation somewhat, but power plants would have to rely on shipments of stone
from nearby states such as New York, or, perhaps, on imports.
Most states in other regions of the country have ample production. North Dakota,
with no production, is an outstanding exception to this, however. A few other states have
low relative supplies of stone, but either the demand is quite small, or the production could
easily be expanded to meet the need.
Costs
F.O.B. Quarry Costs
The average unit value, or net selling price at the quarry, for all crushed carbonate
stones produced in the United States in 1969 was $1.49/ton and varied by type of stone as
follows:
Limestone $1.45/ton
Dolomite $1.55/ton
Shell $1.42/ton
Marl $1.01/ton
Marble $9.69/ton
The high unit value of marble reflects its primary use as a decorative material.
Unit value also varies with end use. Stone used for all construction purposes
averaged $1.44/ton while stone used in applications requiring a high purity material had an
-------
1-24
Table 2
Availability of Limestone and Dolomite for Pollution Control (1969)
Production Potential Demand
Region and State (103 Tons) (*Q3 Tons) _
New England „ ,-r
Connecticut 275 47 056
Maine 800
Massachusetts 750
New Hampshire
Rhode Island < 100 39
Vermont 525
_
Totals 2,400 1-369 1.75
Middle Atlantic
New Jersey 800 935 °-86
New York 33,457 2,132 15.7
Pennsylvania 56,667 3,516 16.1
Totals 90,900 6,583 13.8
South Atlantic
Delaware 177 0
Florida 40,729 1,009 40.4
Georgia 4,334 931 4.66
Maryland 9,804 1,010 9.71
North Carolina 4,500 2,003 2.25
South Carolina 1,900 459 4.14
Virginia 17,829 1,088 16.4
West Virginia 8,405 1.794 4.69
Totals 87,500 8,471 10.3
East South Central
Alabama 17,752 1,931 9.19
Kentucky 30,158 1,785 16.9
Mississippi 300 71 4.23
Tennessee 33,109 1,858 17.8
Totals 81,300 5,645 14.4
East North Central
Illinois 54,844 3,665 15.0
Indiana 25,157 2,786 9.03
Michigan 39,066 2,511 15.6
Ohio 50,595 . 4,181 12.1
Wisconsin 15,937 1,164 13.7
Totals 185,600 14,307 13.0
West North Central
Iowa 26,200 453 57.8
Kansas 15,334 42 365
Minnesota 4,127 648 6.37
Missouri 41,200 1,093 37.7
Nebraska 4,663 110 42.4
North Dakota - 357 0
South Dakota 989 35 28 3
Totals 92,500 2,738 33^3
-------
1-25
Table 2 (continued)
Production Potential Demand
Region and State (103 Tons) (103 Tons) Ratio
West South Central
Arkansas 5,676 4 1419
Louisiana - <1 0
Oklahoma 16,300 <1 Large
Texas 36,300 <1 Large
Totals 58,300 <7 Large
Mountain
Arizona 2,339 50 46.8
Colorado 1,650 358 4.61
Idaho 250
Montana 1,442 74 19.5
Nevada 1,000 78 12.8
New Mexico 956 345 2.77
Utah 2,400 67 35.8
Wyoming 649 379 1-71
Totals 10,700 1,351 7.92
Pacific
California 17,400 266 65.4
Oregon 350 <1 Large
Washington 1,050 < 1 Large
Totals ^ 18,800 <268 >70
-------
1-26
average value of $1.69/ton. Average prices ranged from $0.69/ton for fill to $6.00/ton for
exposed aggregate (decorative stone). Stone for most applications, however, averaged under
$2.00/ton. The variation in price depends not only on supply and demand but also on the
chemical and/or physical properties required for the particular application.
Average prices of limestone and dolomite are shown in Table 3, by region and state.
Within most states, average prices were $1.00-$2.00/ton, although spot prices ranged from
$0.12-$25.00/ton. Several states in the New England and Mountain Regions, in addition to
New Jersey, reported average values above $2.00/ton. Rhode Island reported the highest
average value: $7.57/ton for limestone. The prices reported in California and Washington
were unusual in that average values for limestone were below the national average, while
average values for dolomite far exceeded $2.00/ton. Production of the particular stone was
limited in all cases where average unit values were high.
With the exception of Virginia, which reported $3.92/ton, average prices of shell
were $1.00-$2.00/ton. Unit values for marl were all below $1.15/ton and varied widely in
price.
Transportation Costs
Trucks dominated in the transportation of carbonate rocks from quarry to
consumer, accounting for almost three-fourths of all stone. Rail and waterway hauls,
amounting to one-fifth of the stone shipments, were about equally divided.
Trucks generally are used for shorter hauls of under 50-100 miles while rail is
employed for longer distances. Where conditions permit, shipment of stone by barge or boat
is preferred since this is usually the cheapest method of transportation.
Typical capacities of the various vehicles used to transport stone are:
Truck up to 50 tons
Rail Car 60-100 tons
Barge 1200-1400 tons
Boat up to 29,000 tons
Trucks were a popular mode of transportation in all sections of the nation, while railroads
were important in eastern states, particularly in the southeast. Large amounts of stone were
moved via inland waters, notably in the Great Lakes area and along the Gulf Intracoastal
Waterway. The abundance of highways, railroads, and inland waterways found in the east is
not duplicated in western states, thereby limiting the selection of a transportation method
in the latter area.
Generally, sufficient trucks, barges, and boats are available to haul stone although in
some areas in peak seasons the supply may be limited. In most sections of the country a
shortage of rail cars does occur. For a power plant where the limestone demand would be
known and deliveries could be scheduled well in advance, the affect of a shortage of vehicles
should not be severe.
-------
1-27
Table 3
Unit Value of Crushed and Broken Limestone and Dolomite
in the United States in 1969, By Region and State
Average Unit Value ($/Ton)
Region and State
New England
Connecticut
Maine
Massachusetts
New Hampshire
Rhode Island
Vermont
Middle Atlantic
New Jersey
New York
Pennsylvania
East North Central
Illinois
Indiana
Michigan
Ohio
Wisconsin
West North Central
Iowa
Kansas
Minnesota
Missouri
Nebraska
North Dakota
South Dakota
South Atlantic
Delaware
Florida
Georgia
Maryland
North Carolina
South Carolina
Virginia
West Virginia
Limestone
NR1
1.32
4.14
-
7.57
1.46
2.49
1.56
1.46
1.44
1.32
1.02
1.54
1.17
1.49
1.40
1.32
1.39
1.87
-
1.22
-
1.31
1.50
1.57
1.62
1.51
1.52
1.62
Dolomite
4.20
.2
5.24
-
-
1.53
-
1.97
1.73
1.45
1.28
1.45
1.48
1.21
1.72
-
1.38
1.13
.
-
-
-
-
-
-
-
1.37
1.62
1. "NR" indicates that value was not reported
2. "-" indicates no production
-------
1-28
Table 3 (continued)
Region and State
East South Central
Alabama
Kentucky
Mississippi
Tennessee
Average Unit Value ($/Ton)
Limestone
1.17
1.46
1.00
1.33
Dolomite
1.60
West South Central
Arkasas
Louisiana
Oklahoma
Texas
1.36
1.30
1.35
NR
1.17
Mountain
Arizona
Colordao
Idaho
Montana
Nevada
New Mexico
Utah
Wyoming
Pacific
California
Oregon
Washington
Total United States
1.64
2.04
1.10
1.24
1.64
1.51
2.25
2.11
1.07
1.00
1.28
1.45
2.83
1.77
NR
2.66
2.91
6.00
:>
1.55
1. 'NR" indicates that value was not reported
2. "-" indicates no production
-------
1-29
So many factors influence transportation rates and costs that it becomes very
difficult to establish average rates, even within a single area. Most freight rates for crushed
stone in the United States fall within the following ranges, in cents per ton-mile:
Truck 5.0-10.0 (@ 10 miles) * 2.0 - 5.0 (@ 100 miles)
Rail 4.5- 6.0 (@ 10 miles) * 0.75-1.5 (@ 250 miles)
Water 0.9- 1.5 (@ 20 miles) * 0.25 - 0.50 (@ 500 miles)
Delivered Costs
The delivered price of limestone to a power plant is the sum of the price of the stone
at the quarry plus the transportation charges. The delivered price of limestone to 37 selected
power plants is estimated in Table 4, based on the assumption that a calcium limestone
would be required. Most of the plants are located in the eastern half of the United States
where the major coal- and oil-fired power capacity is found. Prices range from
$1.95-$13.20/ton. Half of the plants could be supplied at under $4.00/ton, while all but 3
could obtain limestone at under $6.00/ton. The latter 3 plants are located in the west in
areas where base prices are higher or limestone deposits are remote. For several eastern
seaboard plants, particularly in New England, the availability of low-cost high calcium
limestone is contingent upon the acceptability of an imported stone. Domestic sources are
either inadequate or too distant to provide a low-cost material.
Carbonate rocks historically have been stable, low-priced commodities. Based on
average unit values for the years 1960-1969, projected average base prices for 1975 are as
follows:
1969 1975
Limestone and Dolomite $1.46/ton $1.67-1.82/ton
Marl $1.01/ton $1.28-1.48/ton
The average value of shell has dropped considerably since 1960. It is unlikely that it will
continue to decrease through 1975. More probably, it should parallel limestone and
dolomite but not exceed them in value. Average unit values for crushed marble are highly
variable, reflecting the sensitivity of price to market conditions.
Transportation rates during the next 5 years should rise about 6 percent/year,, on the
average. Estimates by type of transportation are as follows:
Truck 4 - 6%/year
Rail 6 - 8%/year
Water 5 - 10%/year
These estimates, based on predictions by various stone producers, assume a continuance of
the present rate of inflation.
It should be noted that the lime industry could be affected greatly from the national
concern for the environment. Specifically, the power industry may require large amounts of
lime by 1980, in the form of an additive to control sulfur oxides from the burning of fossil
-------
1-30
Table 4
Delivered Price of High-Calcium Limestone to Selected Power Plants
Power Plant
Benning
Gorgas
Cherokee
J. McDonough
Devon
Fisk
R.S.Wallace
Will County
D.H.Mitchell
Wabash
Riverside
Lawrence
Cane Run
Elmer Smith
Riverside
Edgar
L Street
Delray
High Bridge
Hawthorn
Sioux
Essex
Port Jefferson
Waterside
Allen
Leland Olds
Tidd
Miami Fort
Acme
Horseshoe Lake
Elrama
Schuylkill
Wateree
Bull Run
Cabin Creek
Kammer
Lakeside
Location
Washington, D.C.
Gorgas, Alabama
Denver, Colorado
Cobb County, Georgia
Millford, Connecticut
Chicago, Illinois
East Peoria, Illinois
Lockport, Illinois
Gary, Indiana
Terre Haute, Indiana
lowana, Iowa
Lawrence, Kansas
Louisville, Kentucky
Owensboro, Kentucky
Baltimore, Maryland
N. Weymouth, Massachusetts
Boston, Massachusetts
Detroit, Michigan
St. Paul, Minnesota
Kansas City, Missouri
West Alton, Missouri
Newark, New Jersey
Port Jefferson, New York
New York, New York
Belmont, North Carolina
Stanton, North Dakota
Brilliant, Ohio
North Bend, Ohio
Toledo, Ohio
Horseshoe Lake, Oklahoma
Elrama, Pennsylvania
Philadelphia, Pennsylvania
Rockland City, South Carolina
Oak Ridge, Tennessee
Cabin Creek, West Virginia
Captina, West Virginia
St. Francis, Wisconsin
Delivered Price ($/Ton)
4.50*
3.23
6.36
4.50
4.50*
2.40
3.30
3.30
2.65
2.25(75-94%CaC03)
1.95
3.66
3.00
3.72
3.85
4.50*
4.50*
2.40
3.00
4.60
3.10
4.50*
4.50*
4.50*
5.39
13.20
3.80
2.45
2.45
8.00
5.55(92%CaCO3)
4.50*
3.90(88%CaC03)
4.24
6.00
4.00(80%CaC03)
2.60
*Source of stone is outside of U.S. (Bahamas)
-------
1-31
fuels. Although the amounts to be used are far from certain, it is possible that such
pollution control efforts will make a significant new market for the lime industry.15 New
supply and demand relationships within this market could alter F.O.B. and transportation
charges and have a considerable effect on delivered cost.
V. Conclusions
a. Enormous deposits of carbonate rocks occur in the United States and reserves are
more than adequate for the foreseeable future. A very rough approximation of surface
carbonate deposits indicates a minimum of 3.6 x 1012 tons, sufficient to satisfy national
requirements for more than 500 years at the present rate of consumption (and assuming a
10 percent availability of these reserves). Availability of high purity stone may become a
problem several decades hence, but, with the probability that the required quality will
depend on other process and economic factors, no shortage of suitable stone is foreseen.
b. The major deposits of carbonate rocks occur in the eastern half of the United
States where the vast majority of fossil fuel-fired power plants are located. Large reserves in
these eastern areas provide a nearby source of stone for most power plants. Roughly
two-thirds of all surface deposits of carbonate rock are found in the eastern half of the
country.
c. Relative to the potential demand for carbonate rocks by power plants, production
of these materials is quite large in most states. However, current production is inadequate to
supply the potential needs of power plants in several Atlantic coastal regions, notably New
England.
d. Limestone is the only type of carbonate rock which is produced in large enough
quantities to merit consideration for wide-spread application in the removal of SO2 from
stack gases. In many areas ample amounts of other carbonate rocks are produced,
particularly dolomite.
e. Most of the power plants in the eastern half of the United States could be
supplied with high calcium limestone at less than $6.00/ton, many at less than $4.00/ton.
Costs for power plants located in western states generally would be higher, owing to the lack
of suitable, nearby deposits and other factors.
The preceding costs are based on an unsized, nominally 2"-6" x 0 stone (this
indicates stone with a maximum size of 2"-6" and no minimum size), which is typical of the
product from the primary crusher at most quarries. If a sized or fine material is desired, the
cost may increase. Most quarries have little or no capacity for fine grinding, particularly in
the amounts possibly required by the larger power plants.
f. Based on projections of material cost and transportation charges to 1975, the
delivered price of limestone to most power plants is not expected to increase by more than
$1.00-$2.00/ton.
-------
1-32
VI. Recommendations for Application to Dry Limestone Injection and
Other Limestone-Based Processes
The data and material contained herein and the referenced reports should be used to
obtain a first approximation of the occurrence, characteristics, and cost of carbonate rocks
in a particular case, thereby enabling a power company to assess the desirability of installing
a limestone-based process for SO2 removal. If further investigation is warranted, the state
geological surveys, a list of which is included in the reference 14 report, individual stone
producers, and local carriers should be consulted for more detailed and specific information.
-------
1-33
Section C
Definitions14
To avoid some of the confusion which frequently results from the inexact and
qualitative definitions applied to limestone and related materials in the United States, and
from the multitude of overlapping names used, some of the terms as used in this section are
defined below.
Limestone is a general term applied to sedimentary rocks composed chiefly of
calcium carbonate, CaCO3, calcium-magnesium carbonate, CaMg(CO3)2, or mixtures of the
two. The term is also used, in a more restricted way, to denote rocks composed mainly of
calcium carbonate, in order to differentiate them from dolomites. Dolomite is a name used
to describe a limestone primarily composed of the mineral dolomite, calcium-magnesium
carbonate CaMg(CO3)2. It is generally applied to carbonate rocks which contain
approximately 20 percent or more magnesium carbonate, MgC03. Pure dolomite would
contain 54.3 percent CaCO3 and 45.7 percent MgCO3. A point of contention, which is
sometimes noted in the literature, is whether the calcium and magnesium carbonates are
chemically combined, or whether they occur merely as a physical mixture. Limestone and
dolomite occur with varying quantities of impurities, the most common of which are silica,
alumina, iron oxides, and carbonaceous matter.
Lime can be defined as the product which results from calcination of a limestone or
dolomite. Calcination is a process of heating the stone to a temperature at which carbon
dioxide, CO2 is released, thereby converting the carbonates to oxides. A calcium carbonate
stone will produce a lime containing calcium oxide, CaO. Dolomite will produce a lime
containing both calcium oxide and magnesium oxide, MgO, commonly called magnesia. In
practice, commercial limes are usually derived from high purity stones containing a
minimum of about 95 percent total carbonates.
The following list defines the more important terms used in this report:
Aragonite is a mineral composed of calcium carbonate, and having an orthorhombic
crystalline structure.
Argillaceous limestone contains clay as a major impurity.
Bituminous (carbonaceous) limestone contains organic compounds as a major
impurity.
Calcareous is a term used to describe any material containing calcium carbonate.
Calcite is a mineral composed of calcium carbonate, and having a rhombohedral
crystalline structure. It is the predominant mineral in most limestones.
Chalk is a soft, friable, fine-grained limestone consisting primarily of the remains of
minute marine organisms.
Coral limestone is a fossiliferous limestone consisting primarily of coral.
Dolomitic limestone refers to a limestone which contains more than approximately
20 percent magnesium carbonate. The term is usually interchangeable with "dolomite."
Ferruginous limestone contains iron oxides as a major impurity.
-------
1-34
Flux stone is a high-purity limestone or dolomite used as a flux in metallurgical
processes. It contains 95 percent or more minimum total carbonate.
Fossiliferous limestone is a stone in which the shells or shell fragments (fossils) are
readily discernible.
High calcium limestone refers to a limestone which contains a minimum of
approximately 95 percent calcium carbonate.
Magnesian limestone refers to a limestone which contains magensium carbonate
within the approximate range of 5-20 percent.
Marble is a metamorphic rock consisting of crystallized grains of calcite and/or
dolomite. Commercially, the definition includes any calcareous rock that can be polished.
Marl is an indefinite term used to describe a loose, soft, impure material which
contains fine-grained fragments of shell and marine organisms intermixed with sand and
clay.
Oolitic limestone contains small, rounded pellets (oolites), having a center of
calcium carbonate or sand grains around which are deposited concentric layers of calcite.
Shell limestone is a term used to describe limestone derived from clam and oyster
shells.
Siliceous (cherty) limestone contains silica as a major impurity.
Travertine consists of calcium carbonate that is chemically precipitated from hot
springs.
-------
1-35
Section D
References
Reports identified by numbers prefixed "PB" are currently available prepaid from:
National Technical Information Service (NTIS), U.S. Department of Commerce, 5285 Port
Royal Road, Springfield, Virginia 22151. Others will be available approximately one
month after receipt by NTIS.
1. Illinois State Geological Survey, Final Report, PB 206-487, "Petrographic and
Mineralogical Characteristics of Carbonate Rocks Related to Sulfur Dioxide
Sorption in Flue Gases," July 1971, EPA Contract CPA 22-69-65.
2. Tennessee Valley Authority, Final Report, PB 202-407, "Sulfur Oxide Removal
from Power Plant Stack Gas—Investigation of the Reactivities of Limestone to
Remove Sulfur Dioxide from Flue Gas," 1971.
3. Babcock & Wilcox, Final Report, PB 184-059, "Additive Injection for Sulfur
Dioxide Control—A Pilot Plant Study." March 1970, EPA Contract PH 86-67-127.
4. Peabody Coal Company, Final Report, PB 184-944, "Pilot Plant Moving Grate
Furnace Study of Limestone-Dolomite for Control of Sulfur Oxide in Combustion
Flue Gases," August 1970, EPA Contract PH 22-68-68.
5. Environmental Protection Agency, Air Pollution Control Technical Report, APTD
0737, "Alkaline Additives for Sulfur Dioxide Control," March 29, 1971.
6. Borgwardt, R. M., and Harvey, R. D., "Properties of Carbonate Rocks Related to
S02 Reactivity," Environmental Science & Technology, Vol. 16, No. 4, pp 350-9,
(April 1972).
7. Zentgraf, Karl Martin, "A Contribution to the Determination of Sulfur Dioxide in
Flue Gases and Desulfurization of Flue Gas with Earth Alkali Metal Compounds,"
Fortschrittsberichte VDI Zeitschrift, Germany, October 1967.
8. Ishihara, Yoshimi, "Kinetics of the Reaction of Calcined Limestone with Sulfur
Dioxide in Combustion Gases," Technical Laboratory No. 1 Central Research
Institute of Electric Power Industry, Japan, presented at the Dry Limestone
Injection Process Symposium, June 22-26, 1970.
9. Tanaka, K., et al., "Studies on Removal of Sulfur Oxides from Flue Gas by Dry
Limestone Process," Japan, 1969.
10. Goldschmidt, K., "Experiments in the Use of White Lime Hydrate and Dolomite
Lime Hydrate to Desulfurize Flue Gases from Oil and Pulverized Coal-Fired
Furnaces," Fortschrittsberichte VDI Zeitschrift, August 1968.
11. Ishihara, Y., "Removal of SO2 from Flue Gases by Lime Injection Method," report
of Central Research Institute of Electric Power Industry, Komae, Kaitatama, Tokyo,
Japan, presented at Public Health Service Limestone Conference, December 4-8,
1967.
12. Brocke, W., Report for Third Limestone Symposium, Clearwater, Florida, December
4-8, 1967.
-------
1-36
13. O'Donnell, J., and Sliger, A., "Availability of Limestones and Dolomites,"presented
at the Second International Lime/Limestone Wet Scrubbing Symposium, New
Orleans, Louisiana, November 8-12, 1971.
14. Kellogg, M. W., Final Report, PB 206-963, "Availability of Limestones and
Dolomites," February 1972, EPA Contract CPA 70-68, Task 1.
15. Environmental Protection Agency, "The Economics of Clean Air," Annual Report
to the Congress of the United States, February 1972.
-------
APPENDIX J
Mathematical Modeling of the
Limestone Injection Process
-------
J-l
APPENDIX J
MATHEMATICAL MODELING OF THE LIMESTONE INJECTION PROCESS
In this appendix the author discusses the modeling activities which proceeded
concurrently with the experimental work on which it is based. "The ultimate goal of this
modeling was to establish a sound basis upon which the extensive data obtained at Shawnee
could be used to predict performance and adapt the process to other boilers of different
design."
His summary includes work by:
1. Professor Jack B. Howard, Department of Chemical Engineering, Massachusetts
Institute of Technology
2. EPA Isothermal Kinetic Studies
3. Dr. Yoshimi Ishihara, Central Research Institute of Electric Power Industry, Japan
4. Dr. Robert W. Coutant, Battelle Memorial Institute
5. Professor Robert L. Pigford, University of California
6. Professor C. Y. Wen, West Virginia University
-------
J-3
I. Introduction and Objectives
The unique adaptability of the dry limestone injection process to existing power
plants—especially small and older units—together with its economic advantages in both
capital and operating costs, made it imperative that a thorough evaluation of the process be
made. At the time when this evaluation was undertaken (1967) by CSD in cooperation with
TVA, there was strong evidence that good SO2 removal efficiencies and high additive
utilizations could be obtained by this process. A fundamental study made for EPA at the
Battelle Memorial Institute in 1966 showed that high removal efficiencies were
thermodynamically possible, but kinetic data and mass transfer correlations were not
available by which limits of efficiency could be predicted a priori. An experimental
program, involving both boiler testing and fundamental research was necessary and many
such investigations were carried out over the period 1967-70, both in the U.S. and other
countries.
With the publication of reliable experimental data in 1969 on the reaction kinetics
of CaO with SO2 in both laboratory isothermal and dispersed-phase reactor systems, several
efforts were begun to develop mathematical models which could be used to interpret the
experimental data from various sources and guide optimization of performance in full scale
tests. The ultimate goal of this modeling activity was to establish a sound basis upon which
the extensive data obtained at Shawnee could be used to predict performance and adapt the
process to other boilers of different design. Statistical correlations of data do not permit
extrapolation with any degree of confidence to boilers different in design from that used to
develop the correlation. A model useful for engineering design must account quantitatively
for the effects of injection temperature, residence time, initial SO2 concentration, sulfation,
time-temperature profile, excess oxygen and other boiler characteristics which influence the
kinetics of the reaction of SO2 with the limestone particles injected into it.
Clearly, the development of a satisfactory model required that the primary
rate-limiting mechanism (Battelle had already shown that there was no equilibrium
limitation) be established. Although this is generally the first step in development of a
comprehensive model, it is also the most critical, and was found to be the most difficult.
Several possible and equally plausible assumptions were made as a basis for model
development, but unfortunately, a: the lirne when most of these modeling activities were
begun, experimental research had not yet estaolished the facts regarding the effects of all of
the primary variables (temp., time, SO2 concentration, particle size and physical properties
of the calcine) upon the reaction characteristics with S02. Consequently, models based
upon different assumptions were developed, and only by comparing the responses predicted
by the model with those observed experimentally can a judgement be reached regarding the
most valid and useful model of the limestone injection process.
In the summary following, somewhat of a historical presentation is provided since
the modeling activities proceeded concurrently with the experimental work on which it is
based. The development of information identifying the importance of key parameters is
emphasized and integrated, via discussion, into the most general basis for interpretation and
definite conclusions.
-------
J-5
II. Summary of Modeling Activities
Professor Jack B. Howard, Department of Chemical Engineering, Massachusetts Institute
of Technology
At the request of EPA, a project was undertaken in August 1969 to identify the
rate-limiting mechanism controlling the sorption of SO2 by calcined limestone. On the basis
of the known physical properties of such calcines the rate of diffusion of SO2 into the
pore structure of individual particles was to be estimated by means of the well-developed
theory of heterogeneous catalysis. By calculation of the pure diffusional resistances and
comparison with experimental data, the importance of chemical reaction, pore diffusion and
other SO2 sorption resistances were inferred.
The model1 describes the reaction behavior of a porous limestone particle in terms
of the reaction of clusters of microscopic nonporous CaO grains that comprise the larger
particle. It accounts for the effects of pore size, porosity, internal surface area and CaO
content. The pore spaces between grains permit access of SO2 to the grain surfaces for
reaction while larger pores between grain clusters provide the main path of diffusion into
the particle. Four resistances are considered: (1) transport of SO2 from the ambient gas to
the particle surface, (2) diffusion of SO2 within the pores, (3) chemical reaction at the grain
surface and (4) diffusion of CaSO4 reaction product into the solid CaO grains.
The resistance due to mass transfer to the particle surface was eliminated as a
possible limitation by comparison of experimental data from Battelle's dispersed reactor
with the calculated rate of mass transfer through the gas film. The results (Figure 1, Curves
A and B) showed that the quantity of SO2 that can be transferred to 90 jj particles would
permit 25% CaO conversion in 2 seconds at 1800° F. Actual data at these conditions show
only 9% conversion, consequently Howard concluded that the major resistance is within the
particle itself, resulting from either pore diffusion or chemical reaction.* Ishihara2 reached
the same conclusion on the basis of calculations of the decrease in SO2 concentration
through the gas film surrounding dispersed particles.
Two versions of the model were tested against experimental data on the isothermal
sorption of SO2 by calcines prepared in the laboratory. One version holds the pore structure
constant except for surface area, which decreases in proportion to conversion. The second
version of the model allows the pore structure to change as the reaction progresses, thus
accounting for the expansion of the CaO grains as they are converted to the more
voluminous CaSO4. Calculations with the two versions show that the sorption
characteristics are relatively insensitive to porosity in comparison with the effects of grain
size or surface area. Detailed analysis of experimental data with the model indicated that the
*Although the Battelle data are at low particle to gas concentrations, it has been shown that
the reported rates are in good agreement with Ishihara's pilot plant data for similar sized
particles, which were obtained at particle-to-gas stoichiometries up to 2.5 x (3).
-------
J-6
FIGURE 1
0.4
CURVE A: GAS PHASE MASS TRANSFER
(S02)
= 1-BS
(SO?) INITIAL
t = (-7.3 sec/S In (1-6S
DIFFERENCE ATTRIBUTED TO INTRAPARTICLE
RATE LIMITATIONS
CURVE B: BATTELLE DISPERSED-PHASE
REACTOR DATA
CURVE C:. EPA LABORATORY CALCINES
2 3
TIME (t), SECONDS
PREDICTED BEHAVIOR OF PARTICLES REACTING WITH SULFUR DIOXIDE
UNDER EXTERNAL DIFFUSION CONTROLLED CONDITIONS COMPARED WITH
EXPERIMENTAL DATA (1,000°C; PARTICLE SIZE 96w j 3000 PPM S02;
S = INITIAL MOLES SOLID/STOICHIOMETRIC MOLAR SOLID
-------
J-7
overall rate is controlled jointly by the pore diffusion and chemical reaction rates, with pore
diffusion being the stronger. The estimated Thiele modulus of the smallest particles was
about 30 indicating r\ < 0.1, consequently the reaction profiles predicted by the mode for
particle cross sections in all cases showed only the external surface zone to be participating.
A unique feature of this model is its allowance for solid diffusion. Howard's analysis
showed that without diffusion of the CaS04 into the CaO grains, the maximum solid
conversion could not exceed 8%. It is interesting to note that the data analyzed with the
model indicates that diffusion through the solid grain was rapid enough to contribute little
to the overall resistance.
The most significant conclusion from the MIT analysis was that the internal surface
area available for reaction was the primary factor limiting SO2 sorption rate and that the
reaction behavior could be approximated with knowledge only of the effective CaO grain
radius. A comparison between the reaction rates obtained with the EPA laboratory calcines
examined in this study and the rate obtained when limestones are injected into and
dispersed in flue gas (Figure 1, curves B and C) showed a significantly higher rate in the
latter case. No explanation for this difference could be offered on the basis of information
available at that time.
EPA Isothermal Kinetics Studies
The extreme discrepancy between reaction rates measured in the laboratory and the
rates observed for limestone particles of the same size injected at the same temperature in
dispersed systems had been known since the publication of isothermal kinetics data in
19594,5 _ y^jj discrepancy, and the lack of an adequate explanation for it, was the primary
limitation upon the development of a fundamental model which could be applied to predict
performance on the basis of reaction kinetics.
Research continued at EPA concentrating upon the physical properties of the
calcines affecting reaction rate, i.e., pore structure of the calcine and properties of the
original rock. The results of these additional experimental studies, reported at the 1970
symposium, established the relationship between reaction rate and the surface area of the
calcine. Dr. Dennis Drehmel5 showed that the reactivity of calcines prepared in the
laboratory were strongly correlated to the BET surface area, which varied according to
calcination temperature. Borgwardt7 verified these findings by quantitative measurement of
the reaction rate of calcines prepared from different types of rock (which yielded different
pore structures and surface areas) and showed that the initial reaction rate was a linear
function of the BET surface area of the calcine.
A simple model based on chemical reaction control was shown to correlate the
initial rates of SO2 sorption of calcines of different types of rock prepared at a given
calcination temperature, and the rates of a given rock type calcined at different
temperatures:
ro = ks Sg CS02 1 (1>
-------
J-8
where rQ is the rate per unit mass of CaO extrapolated to zero sulfation, and Sg is the B.E.T.
surface area of the calcine.
The reaction rate constant, ks = Ae '
The activation energy for different calcines averages about 17 k cal/g mole. The intrinsic
reaction rate constant was accurately measured at 900°C at 0.22 cm/sec, essentially
independent of stone type.
The effect of sulfation was shown to result in an exponential decrease in isothermal reaction
rate with conversion, X according to:
r = r0 e "^ (2)
The coefficient (3 is a strong function of particle size, since it includes the effectiveness
factor, n- and is a weak function of stone type, probably due to the differences in solid
diffusion rates within CaO grains postulated by Howard. This effect was quite small
however, compared to the effect of surface area upon the overall rate of SO2 sorption.
The maximum limit of CaO conversion (total SO2-sorption capacity) was defined
by the available pore volume for product accumulation. This was determined by
measurement of grain expansion and decrease in pore volume with conversion, which
showed that calcines of maximum theoretical pore volume can achieve no more than 49%
CaO conversion. At that point the entire pore volume is filled with reaction product, and
greater conversions can be achieved only by solid diffusion through the exterior particle
surface, which is extremely slow.
Dr. Yoshimi Ishihara - Central Research Institute of Electric Power Industry. Japan
Establishment of the direct relationship between BET surface area and initial SO2
reaction rate provided the first insight into the mechanism of SO2 capture by the limestone
injection process. At the same symposium where those data were presented, Dr. Ishihara
reported2 the results of an extensive investigation of the reaction kinetics in a pilot-scale
limestone injection furnace. As a part of his experimental study, measurements of the BET
surface areas were obtained for calcines prepared by rapid (less than 5 seconds) calcination
in the dispersed system. Ishihara's data clearly showed that the surface areas developed in
these short exposure times are considerably greater than the surface areas of calcines
prepared in the laboratory at the same temperature (which require longer periods of
calcination to achieve complete conversion of CaCO3 to CaO). The surface areas produced
by calcination in the dispersed phase were 20-30 m2/g, an order of magnitude greater than
that of laboratory calcines. This difference in surface areas* provided the basis for
reconciling the discrepancies between reaction rates measured in isothermal laboratory
experiments and the observed reaction rates in dispersed systems. Good correlation of the
two independent sets of data was in fact later achieved.
~k
The existence of large surface areas immediately following dissociation of CaCO3 had been
previously postulated by Mayer & Stowe8 from consideration of molecular rearrangements
that must occur when unit crystal cells are altered to the CaO configuration. Absolute
surfaces as great as 103 m2/g were estimated.
-------
J-9
Although Ishihara's objective was not specifically that of modeling the reaction, he
did quantitatively evaluate the effect of each process variable—in much greater detail than
was done in any other pilot plant study. He correlated his data according to the simplest
possible model for chemical reaction control,
r = d(CaO conversion) = k C<~r\
dt S°2 (3)
where k = Ae "E/RT
and T = f(t)
Comparison of this model with equations (1) and (2) shows that it is the same as that used
successfully to correlate the initial isothermal rate data for precalcined stones, where k =
kssg.
Ishihara determined the value of k as a function of each of the major process
variables: temperature (time), particle size, SO2 concentration, limestone type and injection
temperature. He analyzed his data on the basis of instantaneous rates measured at a given
value of temperature (time) in the reactor. This approach assumes that the rate is a function
only of temperature and SO2 concentration, i e., that the rate at t > 0 is independent of
sulfation and surface area. It should be noted that surface and sulfation effects are, therefore,
reflected in the factor A in equation (4), which will also be a function of temperature and
time if these effects are significant.
This simple model proved to be an extremely effective tool for the qualitative
analysis of limestone injection data. Figure 2 shows a plot of the reaction rate constant as a
function of the instantaneous temperature and injection temperature. Several important
responses are revealed by this plot. The slope of each line reflects the activation energy of
the reaction and also any effect of sulfation and/or surface area. Considering the straight
line representing injection at the lowest temperature (910°C) it is clear that the rates are a
linear function of temperature over the full (order of magnitude) range of reaction rates
observed. One may thus conclude that sulfation alone has a minor effect on the apparent
activation energy. Otherwise the slope of this line would change with 1/T (and time),
reflecting the effect of accumulated sulfate. The observed independence of activation energy
from sulfation effects is in accord with Howard's conclusion regarding the constancy of
activation energy over a broad range of conversion for the isothermal reaction of CaO with
SO2.
Comparing the 910°C curve with the other curves in Figure 2, representing higher
injection temperatures, it is clear that the slope increases with temperature. Since sulfation
has a negligible effect on apparent activation energy (slope) it is clear that the rapid
deactivation indicated by the change in slope with injection temperature is a result of
factors other than sulfation. Ishihara attributed this change to the loss of surface area at
high temperature and to internal diffusion resistances as sulfation progressed. In view of the
above discussion regarding the effect of sulfation on activation energy, surface area is clearly
-------
FIGURE 2
2200°F
2000°F
1000
J-10
INJECTION TEMPERATURE
1800°F
0.5 1.0 1.5 2.0 2.5
7.0
7.5
8.0 .8.5
1/T x 104 ? ct
9.0
10.0
ARRHENIUS PLOT FOR THE REACTION OF CAO WITH S02
SHOWING THE EFFECT OF GAS TEMPERATURE AT INJECTION POINT
-------
J-ll
the primary factor responsible for the observed change in reaction rate with temperature. As
additional evidence of this fact it should be noted that the apparent activation energy in the
final stage (about 25 K cal), where the effect of temperature no longer influences surface
area, is the same magnitude as the activation energies measured in the laboratory for calcines
of fixed pore structure.
It is informative to put Ishihara's model in integrated form for comparison with the
other models. Equations (3) and (4) are not directly integrable, however, as shown in Figure
2, a plot of Ishihara's data for the time-temperature profile of his reactor2 shows that 1/T
can be approximated accurately over the short time periods used in his experiments by
1 'v
T = Ct
so that dx ^ Ae"Ect
dt ~
where E is the apparent activation energy, or slope, of the lines shown in Figure 2.
Integrating,
X ^ - £• e -Ect + c
'-c
since x = 0 at t = 0, C = A/Ec and
x 2 A (1_e -Ect} (5)
^-\~f
As is evident from the previous discussion,
A = f (Sg-cs02)
A comparison of equation (5) with that derived independently by Coutant using emperical
curve-fitting techniques will be made in the next section.
Dr. Robert W. Coutant - Battelle Memorial Institute
Fundamental experimental studies9 of reaction kinetics in a dispersed phase reactor
were begun at Battelle in 1967 under CSD sponsorship and continued through 1971. The
reactor used in this investigation was designed specifically to permit close control over the
reaction variables and to permit independent study of each variable upon the reaction
kinetics. Its unique features were (1) particles could be reacted at constant SO2
concentration and (2) particles could be injected and collected over varying residence times
from 0.2 seconds to over 2 seconds thus both calcination and sulfation could be followed
directly by particle analysis.
Following Ishihara's report in 1970, the Battelle research was directed specifically
toward verification of the effects of surface area on S02 reaction suggested by Ishihara's
data. A series of experiments in which limestone particles were "flash calcined" over varying
ranges of time and injection temperature (with no SO2 present in the flue gas) soon
confirmed the existence of large BET surface areas immediately following calcination and
-------
J-12
further showed that the surface decreased rapidly with residence time. For example, 90 y
particles injected at 1950° F yielded surface areas of 60 m2/gCaO jn 0.2 second residence
time, which decreased to 30 m2 /gCaO after one second.
The BET surface areas and corresponding SO2 reaction rates obtained in the Battelle
reactor were compared with the isothermal reaction rate-surface area data obtained from the
EPA differential reactor experiments. The results of this comparison, shown in Figure 3,
demonstrate excellent correlation between the two sets of data. The agreement confirmed
that the high reaction rates observed in the non-isothermal dispersed system is predicable
from its surface area and the intrinsic chemical reaction rate constant (0.22 cm/sec at
980°C) measured in the laboratory. The agreement also indicates that chemical reaction is
the primary limitation on the initial rate of SO2 absorption by the dispersed particles,
verifying the absence of gas-phase mass transfer limitations as inferred by Howard and
Ishihara from independent consideration. Clearly, the maximum rate is determined by
chemical reaction rate, and consequently, also by surface area.
The development of mathematical models of both the sulfation and calcination
reactions was an objective of the Battelle project. The approach used in modeling the
sulfation step did not presuppose any specific reaction controlling mechanism. The observed
responses of sulfation, S, vs. time were fitted empirically to obtain the best correlation with
time and temperature. Unfortunately, only one particle size, 90jj, was modeled. Coutant
expressed the results in the form1 ° :
s = b(l-e'kt) (6)
where k = exp (14.563 - 18734/Tm) (7)
b = exp (-2.982 + 10139/Tm) (8)
It should be noted that Coutant's model expresses the coefficients in terms of mean reactor
temperature, Tm, rather than the instantaneous temperature at time t.
Comparison of equation (6) with the integrated form of Ishihara's chemical-reaction
control model Equation 5 shows that they are identical if b = A/Ec and k = EC. The
injection-temperature dependence of the slope of Ishihara's curves, EC, is confirmed in
Coutant's equation (7). Likewise the dependence of Ishihara's coefficient A/Ec on
temperature in an inverse manner from EC is reflected by equation (8). The primary features
of both sets of data are summarized by the same basic model which requires no assumption
more complex than chemical-reaction control to explain all observed effects.
The coefficient b was identified by Coutant as the maximum (terminal) conversion
achievable under given injection conditions. The value b decreased with increased injection
temperature and since A = bk, Ishihari's factor A also decreases with increasing injection
temperature, thus reflecting the effect of loss of surface area on the overall reactivity. Thus,
for 90jJ particles,
A = f (Sg) - 2.45 e -8595/Tm
-------
J-13
FIGURES
5
CT>
o
m
o:
UJ
ti-
ro
O
c/o
CO
18
16
14
12
10
8
6
2
0
CALCINATION TEMPERATURE
• 790°C
A 890°C
V 980°C
• 1100°C
Sg=7.3X104cm2/g
Sg=5.0xl04cm2/g
^^
Sg=2.4xl04cm2/g
^ •
Sg=0.95xl04cm2/g
I i i I i I i I I I I I
20 40 60 80 100 120 140
TIME, SECONDS
ISOTHERMAL SORPTION OF SO? BY TYPE 4 LIMESTONE AS A
FUNCTION OF SURFACE AREA OF ITS CALCINE.
REACTION TEMP=760°C;PARTICLE SIZE=0.0096 cm;S02=3000 ppm
300,
SLOPE= 1
in
o
O
to
CD
O)
'o
E
en
100
10
1
0.5
DISPERSED PHASE
REACTOR TEMPERATURE
Q1008°C
«1060°C
UJ
o:
103
104 105
Sg,cm2/g
106
COMPARISON OF INITIAL SQ2 REACTION RATES IN
DIFFERENTIAL REACTOR,ISOTHERMAL (980°C,Dp =0.0096 cm)
AND DISPERSED-PHASE REACTOR
S02 = 3000 ppm
-------
J-14
This loss of surface area at high temperatures is brought about by the growth of the CaO
sub-grains that comprise a lime particle, which has long been known to be an activated
process11, i.e., the rate of grain growth increases with temperature. The resulting loss of
surface areas (which is inversely proportional to grain size) of calcines prepared at different
temperatures has been demonstrated by Drehmel12 and Chan etal.13 for calcines prepared
in the laboratory.
The Battelle model thus shows that for a given particle size, surface area decreases
with time and that the rate of change increases with injection temperature. Examination of
the Battelle data also shows that the rate of change is dependent upon particle size. The
comparison of terminal BET surface areas of 90u particles and 48u particles calcined in the
dispersed phase reactor show a marked reduction in surface of the smaller particles:
Table I
Effect of Particle Size on Terminal Surface Area
Particle Size, Injection Temp.
Microns °F
90
48
90
90
48
48
FW
FW
FW
1336
1336
IGS4
2224
2243
2224
2155
2140
2140
Residence
Time, Sec.
1.27
0.99
2.86
1.17
2.08
2.08
Terminal BET
Surface, m2/g
21.5
7.6
21.3
23.7
14.2
8.6
Run No.
925-B
106-F
675-A
317-C
226-B
32-A
That the small particles would calcine more rapidly than large ones is in accord with
the established unreacted-shrinking core mechanism by which calcination proceeds, i.e.,
calcines from the outer particle surface inward toward the particle center. Consequently, the
small particles which have greater particle surface per unit mass, generate greater BET
surfaces per unit time during calcination and of course, complete calcination sooner. This
fact is clearly shown by the Battelle calcination rate data reproduced in Figure 4.
The overall effect of this dependence of calcination rate on particle size is
dramatically demonstrated by comparing the Battelle data with Isjiihara's data for the S02
reaction, which together covers a particle size range from 90ju to 3.4 u. Figure 4
demonstrates the remarkably good agreement between the two sets of data when directly
compared. Remember that these data were obtained from completely different reactor
designs, operating at vastly different injection stoichiometries, and that one set of data was
obtained by gas analysis while the other set was obtained by particle analysis. This
comparison should be particularly noted by those who have despaired over apparent lack of
consistency among results of various investigators of the limestone injection process. All of
the essential features of the dispersed reaction are reflected in these curves: the increase in
initial rate as particle size is reduced, resulting from higher rates of surface generation, the
flagging of the reaction in smaller particles when calcination is completed and everburning
-------
PERCENT CALCINATION
75
90p PARTICLES
0.140
10.5p >ISHIHARA
DATA
20.5p
C\J
o
0.070 -
o
o
T)
CJ>
COMPARISON OF ISHIHARA AND COUTANT DATA
FOR DISPERSED PHASE REACTION OF CAC03 WITH SOo
(Jl
0.2
0.6 0.8 1.0
RESIDENCE TIME, SECONDS
-------
J-16
occurs. The rate of flagging clearly increases as particle size is reduced, reflecting the rapid
loss of surface area and reaction rate by the small particles. The overall result is a very small
gain in terminal conversion despite a 30 fold decrease in particle size.
The flagging of the reaction when particle size is reduced is the most critical feature
of the limestone injection process, as it determines the ultimate limit of CaO conversion
(and SO2 removal efficiency) that can be obtained by injection into the boiler furnace. The
fact that the dispersed phase reaction ceases after a fraction of the total residence time
available has been reported in the pilot injection studies of, Juntgen1 4 , Peabody Coal15,
Florida Power/EPA16, Babcock & Wilcox17 as well as the data discussed here. Previous
attempts to account for this flagging have generally assumed that product shell formation
was responsible. This assumption is not consistent, however, with the small gain in terminal
conversion. If shell diffusion were limiting SO2 sorption at the terminal point, the total
conversion would increase in direct proportion to the reduction in particle size. The
assumption of shell diffusion is also inconsistent with the activation energies observed by
both Coutant and Ishihara, which exceed that of diffusion by an order of magnitude.
The effect of S02 concentration has been shown by both Coutant and Ishihara to
have only a slight effect on terminal CaO conversion in the dispersed system. Each
investigator showed that CaO conversion increased approximately with the 1/2 power of
initial SO2 concentration. Ishihara concluded that the instantaneous reaction rate follows a
first order response to S02 concentration, in agreement with isothermal kinetic
measurements4'18 'l 9. The effect of SO2 concentration cannot be evaluated independently
of the other factors in the Battelle model, in which it appears as part of the factor b, which
includes surface area. Ishihara, by measuring instantaneous rates at different SO2 levels, was
able to separate out the surface area effect. The evidence, therefore, suggests that the
reduced overall effect of SO2 results from the change in surface area with time and its
cumulative effect upon the chemical reaction rate.
Professor Robert L. Pigford, University of California
This model20 is based upon fundamental descriptions of processes occurring within
a lime particle during S02 sorption. Like the MIT model it considers the particle as an
assemblage of nonporous CaO grains surrounded by interstices through which SO2 diffuses
prior to reaction at the grain surface. The model assumes the overall rate to be controlled by
diffusion through this pore structure coupled with diffusion through a product layer which
forms on the CaO grains as the reaction proceeds. Chemical reaction at the grain/shell
interface is assumed to be so rapid that it contributes no resistance to SO2 sorption. The
model, like the MIT model, considers grain size and pore structure to be a function only of
conversion and independent of temperature or time.
The model accounts for variation in the extent of participation of the interior grains
depending on pore structure and position within the particle. In the extreme cases where
pore diffusion controls or grain product-layer diffusion controls, the model reduces to two
basic forms that correspond to a particle surface reaction or a particle volume reaction.
-------
J-17
Case 1 - Superficial surface reaction:
S02 sorption rate = 13.6 (a1/2 D!/2 r^l/4 s 1/2 r 1/2 R2 CQ 3/4 / l/2tl/4)
per particle
or, Rate per
-------
J-18
FIGURE 5
l.Or
0.1
o
o
CJ>
o
3.4
48
90 y
QjQll I I I I I
J L
.05 0.1
1.0
9 SECONDS
TEST OF PIGFORD MEL WITH 3,4 AND 48 MICRON PARTICLES
-------
J-19
Professor C. Y. Wen, West Virginia University
After extensive review of isothermal reaction rate data, including experiments
conducted in the Chemical Engineering Laboratory of West Virginia University. Ishida and
Wen formulated a model based upon the zone reaction concept2 1 . The lime particle is again
visualized as an assemblage of CaO grain to which SO2 diffuses through the pores between
grains. Whereas Pigford coupled pore diffusion with diffusion through a product shell on the
grain surface, Wen coupled it with chemical reaction at the interface between the product
layer and the unreacted grain core. Wen's model is unique in that it has been applied to the
correlation of both isothermal laboratory data, and non-isothermal data from dispersed
systems, including full scale boiler injection. It has successfully correlated the observed
reaction rates from all of these sources.22
The chemical reaction rate is expressed in terms of the reaction rate constant per
unit surface and the surface area per unit volume of lime. The latter is determined by the
radius of the unreacted core, rc, within the CaO grain at time t. Thus, when the original
grain radius is FT, and the particle size is small enough for S02 concentration to equalize
throughout the particle volume,
rate per unit mass CaO =-^-3 ks CSO2 r^ (9)
(FV)
Since rc= R' at t = 0, the initial rate is inversely proportional to BET surface area. At low
conversions and small particle size the model thus reduces to the same form used by EPA to
correlate isothermal data.
A more complex form of the model can be applied to large particles in which
diffusion effects are also important. The theory of gas-solids reactions in which diffusion
and reaction occur simultaneously was rigorously developed by Prof. Wen over the period
1967-71. By comparing observed reaction rates with the theoretical curve for particles of
different diameter, Wen was able to estimate the diffusion modulus for the isothermal
reaction of SO2 with calcined limestones. The model also enabled him to separate out the
intrinsic reaction rate free from diffusional effects. The reaction rate constant was thus
evaluated for data from varying sources over a wide range of temperatures as shown in
Figure 6. The value of the reaction rate constant and activation energy is established by this
correlation and can be directly applied to the modeling of non-isothermal systems.
A complete simulation of the limestone injection in process was carried out22 on
the basis of the above model, using data from the Shawnee full scale boiler tests. Simulation
inputs included the time-temperature profile of the Shawnee boiler, the average particle size
of the limestone, the kinetic parameters established in isothermal studies and an assumed
mean CaO grain size of 0.02 p. A comparison of the results predicted by the simulation and
the results obtained at Shawnee are shown in Figure 7. It is evident that the model is
capable of predicting boiler test results within about 30 percent at the current level of
refinement of model and assumptions.
-------
J-20
0.005
0.6
0.8 1.0
1/T x 103
1.2 1.4
RATE CONSTANT FOR THE GRAIN REACTION (WEN)
(KEY TO FIGURE SHOWN ON TABLE II)
-------
J-21
Table II
List of Types of Limestone Particles Examined
and Corresponding Keys Used in Figure 6
(C: calcined stone, R: raw stone)
Investigator
Borgwardt4
Borgwardt7
Coutant, et al.9
TVA24
This Study
Key
(3
Q
©
©
©
w
3
€
O
(j)
B
A
0
O
O
Form
C
C
C
C
C
C
C
C
C
C
C
R
R
C
C
C
Type Stone
Dolomite
Limestone
Limestone
Limestone
Calcite spar
Limestone
Limestone
Dolomite
Aragonite
Marl
Limestone
Limestone
Limestone
Pelletized
CaO
CaO
(wt% in calcine)
55
54
94
81
98
95
96
58
97
88
90
90
90
100
-------
J-22
FIGURE?
Q
UJ
Q.
I/O
CO
LlJ
Q
LU
-------
J-23
III. Discussion
As a result of the combined efforts of the modeling activities and extensive
experimental investigation, considerable progress has been made toward an understanding of
the phenomena on which the limestone injection process is based. A thorough and objective
evaluation of the complete data available reveals considerable consistency and agreement on
the effects of each of the major process variables on the effectiveness for SO2 removal. The
summary outlined here has focused upon the most critical of these variables—those which
directly bear upon the ultimate potential of the process for pollution control purposes.
The first fact that can be regarded as established is that mass transfer of SO2 to
particle surfaces does not limit the rate of SO2 capture in dispersed systems. This has been
shown by the calculations performed by Howard and Ishihara and independently confirmed
by the correlation of measurements of the initial reaction rates measured under isothermal
conditions in the laboratory. Further experimental proof is provided by the high sensitivity
of the dispersed phase reaction to temperature as shown by the activation energies
determined by Coutant and Ishihara, and the lack of any effect of stoichiometry upon CaO
conversion, shown by Ishihara.
It follows from this fact that the ultimate limitation to SO2 capture by injection of
limestone into a boiler is associated with intraparticle effects—either diffusional or chemical.
It is further established that the initial rate of SO2 sorption, i.e., the highest possible rate
achievable, is determined by the intrinsic chemical reaction rate of CaO with SO2. The rate
of decay of this high initial rate determining the efficiency of the process can be attributed
to three possible causes: (1) formation of a product shell on the particle surface, (2)
formation of product shell on individual CaO grains within the particles or (3) reduction in
chemical reaction rate due to loss of surface area as a result of grain growth. The effect of
the process variables on the anticipated rate are different in each case and comparison of
models with the established characteristics of the reaction permits this question to be
decisively answered.
In the summary of Pigford's model it was shown that severe discrepancies exist
between the observed effects of temperature and particle size and the responses predicted
by the model. The model is likewise in conflict with the effect of SO2 concentration and
the established activation energy of the isothermal reaction. Although the postulation of
diffusional resistances as the rate limiting factor is intuitively appealing, particularly for the
final stage of reaction, it is not consistent with the observed characteristics of the reaction.
The assumption of a combination of diffusional and chemical resistances to be
controlling, as exemplified by the MIT model, is also in serious conflict with experiment.
The failure of the model to properly predict reaction profiles as determined by microprobe
analysis, was later pointed up when Wen evaluated the diffusion modulus at 1/30 the value
estimated by the MIT model. Likewise, the effective diffusivity was determined to be about
0.07 cm2/sec. rather than the 0.2 cm2/sec initially estimated by MIT. The variation of
surface area with particle size was disproven by BET measurement and the predicted effect
of temperature on surface area also failed: after calcination at high temperature, the surface
-------
J-24
area is independent of particle size or reaction temperature. In view of the fact that Wen s
model also assumes diffusion to be a major resistance under certain conditions, and is
entirely consistent with experiment, one can only conclude that the MIT model contains
mathematical errors, or that the equations have solutions that were not recognized.
The attached table summarizes the principal experimental results with which any
useful model must be in substantial agreement. Each model discussed here is qualitatively
compared with these results. Also included in this comparison are the predicted responses
for pure shell diffusion, since this mechanism had long been regarded as the most probable
limitation of the process. It is clear from this table that shell diffusion is inconsistent with
nearly every one of the observed responses,* and need not be further considered.
The best general agreement with experiment is, of course, obtained with the
empirical models. The Ishihara and Coutant models are combined for this comparison since
it was shown that they are both representative of homogeneous chemical reaction,
influenced by strong surface area effects. It is assumed in this comparison that the effects of
time, temperature and particle size that have been established are taken into account when
applying the model.
The Wen model is again the same homogeneous representation as that of
Ishihara-Coutant, except that it specifically identifies the surface area with the CaO grains
within the calcine particle. It therefore lends itself to quantitative treatment of the surface
area effect independent of the other parameters and will ultimately be the most generally
applicable form of the model for predictive purposes. The Wen model is the only form
which can be applied to the complete range of homogeneous, zone and shell reactions for
both isothermal and nonisothermal reaction conditions. The primary limitation in accuracy
of the Wen model is that there is no way to predict grain size a priori from given process
conditions. Thus, in applying his model to simulate the Shawnee boiler, a constant grain
radius is assumed, i.e., surface area does not change with time and is independent of particle
size or injection temperature. The data of Ishihara and Coutant clearly show that this
assumption is not correct, but it does permit one to formulate a first approximation. As
shown by Figure 5, this approximation is limited in accuracy to ± 30% of the observed
efficiency. The predictive accuracy of Wen's model would no doubt be greatly improved if
Ishihara's data on the effects of particle size and injection temperature were incorporated to
account for changes in grain radius with residence time. This modification would probably
also bring the model into agreement with the first order kinetics established for the
isothermal reaction (fixed grain size).
The preponderence of evidence resulting from the work of Ishihara, Coutant and
Wen overwhelmingly favors chemical reaction as the controlling mechanism of the process.
This mechanism is the only one consistent with all of the facts, and the ultimate
*Microprobe analysis of the cross sections of particles reacted in the Shawnee boiler23 show
homogeneous distributions of reaction product within particles smaller than about 40)J.
Particles larger than 40u show distributions similar to those proposed by Wen for zone-type
reactions.
-------
Table III
Comparison of Model Predictions With Experimental Results
Experimental Results
Particle size effect
Temperature effect
Surface area-initial rate
Surface area - particle size
Terminal Conversion - particle size
Isothermal reaction rates
SO2 concentration
Act. energy-conversion
Isothermal reaction profiles
Nonisothermal reaction profile
Overburning - SO2 reactivity
CaO content of lime
Sulfation effect
Conversion time profile
Total residence time
Terminal conversion -total residence
Homog. chem
reaction
(Ishihara-
Coutant)
V
V
V
V
V
V
(a)
V
V
V
V
V
X
V
time
Chem. react.
shrink, grain
core
(Wen)
V
V
V
X
X
V
(a)
V
V
V
V
V
V
7
V
Pore
diffusion-
surface react.
solid diff.
(MIT)
X
X
V
X
X
V
V
V
X
X
X
V
V
X
Grain shell
diffusion-
pore diffusion
(Pigford)
X
X
V
X
X
V
X
X
V
V
V
X
X
X
Product
layer
diffusion
(Shell)
X
X
X
X
X
X
V
X
X
X
X
X
X
X
ro
en
(a) Expected to agree when model is modified to account for change in surface area with time.
-------
J-26
self-limitation of SO2 capture by the lime particles after injection necessarily follows from
the known changes in surface area that occur with everburning. The low final rate, like the
high initial rate, can indeed be calculated from the chemical reaction rate constant and
surface area.
IV. Conclusions
The limestone injection process is limited by the rate of chemical reaction which is,
in turn, limited by the rapid loss of surface area (due to grain growth) immediately
following calcination.
This self-limiting aspect of the reaction necessarily defeats any attempt to improve
performance by manipulation of process variables, e.g., particle size, injection temperature,
particle/gas distribution.
The efficiency of SO2 removed, within these limitations, can be successfully
simulated by homogeneous reaction models, such as that of Wen. As a first approximation,
assuming constant grain size, such a model will predict results within 30%. Improved
accuracy must rely on empirical correlation of particle size and temperature effects. Data
for such correlations are already available.
The limit of efficiency for the process, as determined from experiment, is 20 percent
per stoichiometric injection.
Regardless of kinetic limitation, CaO utilization cannot exceed 50% due to physical
limitations of the reaction.
-------
J-27
V. References
1. Howard, J. B., Williams, G. C., and Ghazal, F.P.H.: "Mathematical Model of the
Reaction Between Sulfur Dioxide and Calcine Particles," Final Report on Task No. 2
of HEW-NAPCA Services Contract NA. CPA-22-69-44, September 23, 1971, prepared
at the Department of Chemical Engineering, Massachusetts Institute of Technology.
2. Ishihara, Y.: "Kinetics of the Reaction of Calcined Limestone with Sulfur Dioxide in
Combustion Gases," paper presented at the Dry Limestone Injection Process
Symposium, Gilbertsville, Kentucky, June 22-26, 1970, sponsored by Control Systems
Division, EPA.
3. Ishihara, Y.: "Removal of Sulfur Dioxide from Flue Gases by the Lime Injection
Method," paper presented at CSD LimestoneSymposium.Clearwater, Florida. December
4-8, 1967, Central Research Institute of Electric Power Industry, Japan.
4. Borgwardt, R. H.: Environmental Science & Technology 4 (1) 59 (1970).
5. Borgwardt, R. H.: J. Eng. Power 92 (2) 121 (1970).
6. Drehmel, D. C.: "Tests for Overburning of Calcined Limestone," paper presented at
the Dry Limestone Injection Process Symposium, June 22-26, 1970.
7. Borgwardt, R. H.: "Isothermal Reactivity of Selected Calcined Limestones with SO2 "
paper presented at the Dry Injection Process Symposium, June 22-26, 1970.
8. Mayer, R. P., Stowe, R. A., "Physical Characterization of Limestone and Lime,"
Report to National Lime Assoc., Washington, D.C. (1964).
9. Coutant, R. W.: "Investigation of the Reactivity of Limestone and Dolomite for
Capturing SO2 from Flue Gas," Final Report for Contract No. PH86-67-115,
November 20, 1970, Battelle Memorial Institute, Columbus, Ohio.
10. Coutant, R. W.: "Investigation of the Reactivity of Limestone and Dolomite for
Capturing SO2 from Flue Gas," Final Report for Contract No. CPA 70-111, October
1, 1971, Battelle Memorial Institute, Columbus, Ohio.
11. Fischer, H. C., "Calcination of Calcite: Size and Growth Rate of Calcium Oxide
Crystallites," J. Amer. Ceramic Society 38(8) 284-88 (1955).
12. Drehmel, D. C., Ceramic Bulletin 50 (8) 666-70 (1971).
13. Chan, R. K., Murthi, K. S., Harrison, D., Canadian J. Chem. 48 2979-82 (1970).
14. Jungen, M. and Juntgen, H.: "On the Reaction of Calcined Dolomite and Other
Alkaline Earth Compounds with SO2 of Combustion Gases as carried out in a Cloud of
Suspended Dust." Report presented at CSD Limestone Symposium, Clearwater,
Florida. December 4-8, 1967 Bergbau - Forschung GmbH, Germany.
15. Whitten, C. M. and Hagstrom, R. G., J. Engineering for Power 2 (Jan. 1970).
16. Borgwardt, R. H. and Kittleman, T. A., paper No. 69-141 presented at the Annual
Meeting of the Air Pollution Control Association, New York. June 22-26, 1969.
Control Systems Division, EPA.
-------
J-28
17. Attig, R. C. and Sedor, "Additive Injection for SO2 Control," Final Report for
Contract No. DH 86-67-127, March 27, 1970, Babcock & Wilcox Research Center,
Alliance, Ohio.
18. Hatfield, et al., "Investigation of the Reactivities of Limestone to Remove SO2 from
Flue Gas;" Final Report for Contract Nos. TV-29232F and TV-30530A (1971)
prepared by Tennessee Valley Authority, Division of Chemical Development, Muscle
Shoals, Alabama.
19. Coutant, Contract No. PH 86-67-115, Quart. Report for Dec. 12, 1967, p. 6.
20. Pigford, R. L., "The Rate of a Diffusion-Controlled Reaction Between a Gas and a
Porous, Solid Sphere - The Reaction of SO2 with CaCO3," June 1971, University of
California.
21. Ishida, M., Wen, C. Y., AlChE Journal, 14 (2) 311 (1968).
22. Ishida, M., Wen, C. Y., "Analysis of SO2-Limestone Reaction-System, Part I: Reaction
Rate of SO2 with Particles Containing CaO, Part II: Simulation of SO2 - Limestone
Reaction System." Report prepared for Control Systems Division, 1972 at Department
of Chemical Engineering, West Virginia University.
23. Shell Development Company. Personal communication to R. D. Stern, March 3 and
April 16, 1971.
24. McClellan, G. H., 4th Dry Limestone Process Symposium, Gilbertsville, Kentucky,
June 22-26, 1970.
-------
APPENDIX K
Utilization of Limestone-Modified Fly Ash
-------
K-l
APPENDIX K
UTILIZATION OF LIMESTONE-MODIFIED FLY ASH
Although the utilization of limestone modified fly ash (hereafter as LMF) is not
directly related to the dry limestone injection process and demonstration of optimum SO2
removal, this section provides an overview of the activities in this area of the overall EPA
program. Additional information may be found in the references.
-------
K-3
Utilization of Limestone-Modified Fly Ash
I. Introduction and Objectives
The Dry Limestone Injection Process is a "throw-away" process and does not
depend on the recovery of a salable chemical byproduct. Aware of the increased solid waste
generated by the process and attempting to avoid aggravating one pollution problem while
solving another, EPA initiated an extensive research effort in the early planning stage of the
overall program. The objective of this part of the overall program was to determine and
demonstrate the utilization of pulverized coal fly ash modified by limestone. A secondary
consideration was the potential for reducing costs of the process through potential re-use of
sorbent or byproduct credit.
II. Approach
The general approach taken was to determine current and potential utilization of
unmodified fly ash, assess applicability of LMF to these utilizations and, based on its
properties, assess its potential for new applications. Although there are a large number and
variety of industries and individuals involved in the production and use of fly ash, the
program was directed toward coal-burning power utilities, since this is the major source of
fly ash in the U.S. The specific approach was to: (a) perform literature searches for
utilization of unmodified and LMF; (b) correlate reported uses with analyses of chemical
and physical properties; (c) prepare products by simulating current production processes as
closely as possible; and (d) compare product properties and characteristics with their
commercially available counterparts. Based on technical potential, economic analyses and
more extensive utilization research were then performed or recommended for follow-on
projects. Because of the relationship between the LMF from dry processes and wet
scrubbing processes regarding waste disposal and beneficiation, samples for analysis and
small scale product preparation were obtained from dry limestone injection programs
conducted by TVA, Babcock and Wilcox, Chevrolet, and Detroit Edison, and from wet
scrubbing programs conducted at Kansas Power and Light, Union Electric and Detroit
Edison. Samples of normally produced fly ash were also obtained from these sources.
III. Results and Conclusions
A. Unmodified Fly Ash Utilization'
Although fly ash is used in various applications, current utilizations consume only a
small portion of the total amount of fly ash available: of the 26.5 million tons of fly ash
produced annually by coal-burning power plants, only about 1.6 to 2.0 million tons are
utilized.
All known specifications for fly ash used as a material for product manufacture or
application, and for fly ash products were examined for the purpose of assessing the extent
-------
K-4
to which they inhibit the utilization of fly ash. Except for the specifications on fly ash as an
admixture in portland cement concrete, specifications do not inhibit the use of fly ash. The
amount of fly ash that could be technically utilized in various applications used today,
regardless of supply and economic factors, was estimated to identify those areas that would
benefit most from the increased mass utilization of fly ash; this indicated where effort
should be applied to improve the market. Maximum technically feasible uses of at least 1
million tons per year are listed in Table 1, column 1, based on ash composition and possible
product utilization alone. The 1970 actual utilization values for each use, listed in column 2,
total 1.6 million tons per year. As a result of this survey, it is estimated that if fly ash were
used in the applications listed in Table 1 such that the maximum practical potential would
be utilized under current technology and associated market conditions, approximately 7
million tons would be utilized, as shown in column 3. The significance of this list is that it
indicates approximately 75 percent of the fly ash produced in the United States is not
marketable without significant changes being made to reduce or eliminate the following
limitations: (a) inadequate technology and knowledge dissemination related to known uses,
(b) geographic limitations on transportation economics, (c) insufficient marketing efforts,
(d) lack of control of fly ash production and supply, (e) cost effects of other materials or
processes, and (f) insufficient development of new technologies.
The values in column 4 are estimates of the fly ash that would be consumed if all the
limitations just cited were removed, except some geographic limitations on transportation.
These values are estimates but they indicate areas where it is believed fly ash can be used in
large quantities if appropriate steps are taken. This approach limits the area of concern to:
fly ash concrete, lightweight aggregate, road base courses, control of mine subsidence and
fires and, such new uses or developments as gas concrete building construction, ceramic
products, and mineral recovery.
The following paragraphs discuss the uses shown in Table 1:
Structural Concrete
Fly ash is used in portland cement concrete for the improved properties it imparts to
the concrete. Among these improvements are pumpability, compressive strength, long-term
strength, workability, finishability, resistance to sulfates and alkali-aggregate reaction, and
decreases in heat of hydration, drying shrinkage, particle segregation, bleeding, permeability,
and leaching. These improvements are well-documented and have been demonstrated
repeatedly in actual practice. The net effect is a stronger and more durable product which
requires less cost to put in place and finish. For properly proportioned fly ash concrete,
early strength, form removal periods, and curing requirements are not use inhibitions.
Principal inhibitions to the use of fly ash in concrete are the lack of a dependable
supply of usable quality ash, and nonrecognition of the technological gains and potential
improvements which would allow the use of various qualities (or classes) of fly ash and
greater than 28-day design strength criteria.
-------
K-5
Table 1
Estimated Fly Ash Utilization Potential
(Million Tons Per Year)
Use
1
Maximum Utilization
Technically Feasible
1970
Utilization
3 4*
Estimated Utilization
Potential
Current Improved
Conditions Utilization
Fly Ash Concrete (Structural,
Mass and Concrete Products)
Lightweight Aggregate
Raw Material for Cement
Bricks
Filler in Bituminous Products
Base Stabilized for Roads
Agriculture and Land
Reclamation
Control of Mine Subsidence
and Fires
Structural Fill for Roads,
Construction Sites, Land
Reclamation, etc.
Others (mineral, wool, gas,
concrete, misc.)
Total
10-15
13
13
10
1-2
> Annual Production
> Annual Production
> 1
> Annual Production
0.54
0.21
0.16
0.13
0.11
3.5
6.0'
0.01
0.32
0.16
1.64
0.5 >3.0***
0.25 ****
0.75 ****
0.3 >10.0
0.75
0.6
0.25
6.9
*Values in Column 4 are scaled against the current market, but may take as much as 5 to 10
years for realization with maximum efforts.
**Value can be increased considerably with use of fly ash gas concrete in building construction.
***Has potential for accelerated future growth well beyond the proportions shown here.
****No appreciable increase.
*****SJgnjfjcant increases are possible through new developments such as ceramic products and
mineral recovery.
-------
K-6
The choice of concrete cure time should be based on the economics involved with
construction. Since the cost impact on materials by using fly ash is often small relative to
the cost of placing and finishing the concrete, the design conditions should be dependent
upon the construction requirements. However, the state-of-the-art in concrete construction
requires design compressive strengths of 28 days and does not include an optimal cure time
in the total economics. A cure time of 28 days represents the point at which portland
cement concrete attains up to 90 percent of its ultimate strength and is considered
representative of the true strength of the concrete. However, in concrete containing fly ash,
28-day cure times are arbitrary and meaningless since the strength tested at that time does
not represent the ultimate strength of the concrete when fully cured, which occurs after 28
days. Using a 90-day cure, for example, allows more fly ash and less cement, provides higher
strength, and affords advantages in pouring, pumping, and finishing. While the concept of
28-day design strengths largely dominates the concrete construction industry, there are few
examples that can be cited in which structures under construction experience their design
loads in 28 days. Until the concrete construction industry becomes aware of the increased
latitude in concrete mix design that is offered by a technology using fly ash in an effective,
economical manner, an inhibition to the use of fly ash in concrete will persist.
Significant deterrents to the massive use of fly ash in concrete, assuming an adequate
supply and improved technology, are the requirements for additional storage and handling
equipment at the ready-mix plants, and hauling costs. The economics of fly ash concrete
related to the ready-mix operation was investigated to determine if storage, handling, and
hauling costs are inhibitory factors since the literature is weak in this respect. The
investigation could not include a detailed, comprehensive cost analysis within the scope of
the project funds because of: (a) the numerous variables involved, plus the variation in costs
from region to region; (b) the use or nonuse of beneficiation of the fly ash, brokerage fees,
and financial assistance to ready-mix dealers for new equipment; and (c) sliding costs related
to local competition. The analysis was therefore limited to estimates of the more significant
factors, i.e., costs of fly ash F.O.B. utility, cement, truck hauling, new equipment, and
chemical admixtures.
Strict conclusions cannot be drawn from this analysis because of the many cost
variations involved for each case; however, indications are that a dealer can increase his
profit before taxes by approximately 50 cents per cubic yard if high quality fly ash concrete
is delivered within 10 miles of the fly ash source, or he can break-even at about 150 miles.
On the other extreme, there is the possibility of a combination of circumstances, including
the use of low-grade fly ash, which indicates that the user will not be able to match portland
cement air-entrained concrete on an equal production economics basis. In most cases,
however, the dealer should be able to produce fly ash concrete to compete with portland
cement concrete for haul distances of approximately 50 to 150 miles, depending on the
many cost factors involved. Since the profit, before taxes, on portland cement concrete is in
the range of $2 to $3 per cubic yard (according to various personal contacts), a potential
-------
K-7
increase of 20 to 50 cents per cubic yard would be appreciable to the dealer. If
circumstances, as noted above, increase the cost to the dealer, that increase is generally small
enough to be absorbed by the contractor who stands to benefit from the economic and
technical advantages of using fly ash concrete. Production costs of fly ash concrete can be
reduced rather dramatically in consideration of the utilization of greater-than-28-day design
strengths described earlier. Using this technology where applicable can reduce cost for any
type of concrete, and for some, the reduction can be well in excess of one dollar per cubic
yard.
Barge or rail transport provides a less expensive means of hauling fly ash than truck,
but is applicable to only certain geographic situations. Since the development and
acceptance of a standardized fly ash concrete technology by the concrete industry would
expand the market and bring a large percentage of the power companies into the supply
market, any transportation inhibition would be significantly decreased in most of the
eastern half of the country.
In summary, current specifications on fly ash as an admixture in Portland cement
concrete inhibit the use of fly ash. There are individuals and organizations who, by
combining the production or procurement of quality fly ash, appropriate concrete
technology, and dissemination of the knowledge, have marketed fly ash readily within the
limits of existing specifications (ASTM or Federal Bureau Specifications) or have written
their own (e.g., TVA). Since the general fly ash user and producers have not done this the
use of fly ash concrete is not widespread. The lack of understanding of fly ash concrete by
the general public and isolated cases of fly ash misuse and the dissemination of inaccurate or
misleading information concerning fly ash (e.g., broadcast of the term "waste product,"
intolerable low early strength, and bad color) have inhibited involvement by potential
dealers, contractors, architects, and engineers. Power companies (with few exceptions) have
not taken the initiative to improve the quality of fly ash or to maintain a consistent quality.
Improvement in that area would undoubtedly relax the inhibitions to the use of fly ash by
giving potential users the assurance of having a readily available supply of a quality grade of
fly ash. It is believed that a considerable portion of the fly ash produced today is usable as
an admixture in portland cement concrete.
The continued development and acceptance of properly proportioned fly ash in
concrete is likely to provide the basis for renewed interest in fly ash as a concrete ingredient.
Intensive sales campaigns, although beneficial, have been effective only locally. When
concrete users become fully aware of the range of advantages and properties that properly
proportioned fly ash concrete offers, their reluctance to use fly ash in concrete should
diminish; this should create an increase in demand.
Mass Concrete and Concrete Products
Fly ash is used in much of the mass concrete construction (e.g., dams and spillways)
undertaken by the U.S. Army Corps of Engineers and the Bureau of Reclamation.
-------
K-8
Specifications exist for this use and fly ash is proportioned accordingly, principally to lower
the heat of hydration and also for its pumpability feature. Technically, a larger percentage
of fly ash could be used in these structures; however, the present proportioning is adequate.
The bulk of this work is being performed in the western United States where fly ash must be
transported for long distances, thus reducing economic incentive. Fly ash may become more
economically desirable with construction of new coal-burning power stations opening in the
West. Usage may increase but the small number of such projects makes this potential use a
small percentage of the national fly ash supply.
Concrete products such as building blocks, pipe, and precast units represent a very
attractive field for fly ash usage. Fly ash is used for this application and is well accepted; its
principal drawbacks are the lack of guaranteed quality ash and transportation cost limits. If
this industry were exploited to its fullest extent, it would consume an estimated maximum
of 5 percent of fly ash production.
Lightweight Aggregate
The predicted high future demand for lightweight aggregate is based on dwindling
supplies of natural aggregates plus the increasing recognition by architects and engineers of a
future demand for large-scale usage of lightweight concrete. Present developments of fly ash
lightweight aggregate production technology in the United States, Canada, and Germany
were reviewed. All are still in various phases of development and are attempting to solve
technical production problems. Lightweight fly ash aggregate in the U.S. is not yet
considered to be economically competitive product.
This is a relatively undeveloped industry, and solutions to its problems are being
sought and incorporated in the process. Although a quality product can be manufactured,
whether the manufacturing process and market can be sufficiently developed to
economically compete with other lightweight aggregates remains to be seen. A significant
increase in the utilization of fly ash for this application appears possible, but not probable in
the near future.
Portland Cement Manufacturing
Fly ash lends itself economically to the production of portland cement only under
certain special situations where the manufacturing plant is not located adjacent to the major
raw material source or where possibly the required mineral deposits are located close to a
utility. However, in most cases such special situations do not exist. This, coupled with the
fact that there is no need for new cement plants since the present market demands
considerably less than production capacity, indicates that the potential for utilizing fly ash
in large quantities for the manufacture of portland cement is relatively low.
Bricks
Although fly ash can technically be used for making bricks, there is no shortage of
clay deposits for brick making. The principal sources of fly ash in the United States are all
-------
K-9
close to ample sources of natural raw materials for brick manufacturing. The coincidence of
a depleting source of natural raw materials, a dependable local source of high quality fly ash,
and a knowledgeable entrepreneur may determine whether fly ash will eventually find local
application as a brick ingredient. Additional factors indicating that this utilization potential
will not materialize appreciably include: (a) fly ash brick manufacturing requires new
handling equipment and production machinery, (b) fly ash bricks are not significantly
cheaper than ordinary bricks, and (c) the present United States brick production capacity
exceeds demand.
Bituminous Filler
There are numerous uses for fly ash in bituminous products, however, its use as a
mineral filler in asphalt concrete (black top) pavement is the major application for large
tonnage usage. Low quality fly ash can be used and current technology is sufficient. The
competition to fly ash includes an array of low cost, abundant materials, all of which are
adequate as a mineral filler. Although this is a good use for fly ash, particularly considering
the mileage of new asphalt roads (2 to 4 in. thick) or resurfacing of old roads (1 in. thick),
the potential usage is not large, probably much less than 1 million tons per year. This
limitation, caused by competition, is aggravated by the special problems of storage and
handling.
Road Construction
Except for use as a mineral filler in asphalt or occasional use as a structural land fill,
road base course applications appear to be the only practical large-scale use for fly ash in
road building. Although this application has an extremely large potential—technology is
developed and a technical superiority over competing materials has been
demonstrated—certain inhibitions prevent its substantial growth. Fly ash is not widely used
in road contracts even though its cost is less than or equal to competing materials of equal
strength for urban construction. Proven applications are classified as lime-pozzolan-aggregate
base courses (pozzolan base), which involve patent rights. Factual data which would
substantiate the inhibition of the use of this material because of royalty payments were not
found; however, such an excuse was occasionally given for nonuse.
The pozzolan base course is used mostly for urban applications. Portable mixers are
not widely used, and hauling costs are often limited by the use of materials available at or
near the construction site. However, the amount of paving urban roadways, subdivision
streets, parking lots, and airports represents an extremely large market. Present usage
appears to extend as far as 40 to 50 miles from the mixing plant. Almost any fly ash
produced today is adequate for this application, and it can be stored outdoors during the
winter months and, with minimal processing, can be used during the construction season.
Valid inhibitions to the use of pozzolan bases were not uncovered even after
contacting more than two dozen state highway departments. Most states are aware of its
benefits but have chosen not to use it. The reasons were almost always vague. The principal
-------
K-10
inhibition may be that most potential users have not had experience with it and are
reluctant to make a change. A thorough, detailed marketing analysis of road construction
would be required for the various regions of the country within range of potential pozzolan
base course supplies to determine the justification and advisability of action by government
road contracting agencies relating to the use of fly ash for this purpose.
Agriculture and Land Reclamation
Although this application appears to be a method for utilizing large amounts of fly
ash, it is not economically attractive when compared to the use of lime or other additives to
adjust soil pH. Transportation and handling costs appear to be prohibitive for the large
amounts of fly ash that would be required. Generally, the ratio of fly ash to limestone
required to achieve an equivalent soil condition or crop yield is sufficiently high (as much as
30 to 1) to be beyond consideration. Moreover, the presence of certain trace elements often
found in fly ash would be detrimental to the growth of many common types of vegetation.
Although it may be useful in certain local areas, it is not expected to be useful on a wide
scale.
Remote Filling of Mine Cavities
Mine subsidence damage to homes, bridges, and roads is an increasing problem. The
increase, due only partially to additional mining, can also be attributed to the growing need
for urban and suburban land which has resulted in building over old mines; deterioration of
supporting conditions results in surface subsidence many years after mining has occurred. In
addition to the subsidence, fires have also become a serious problem in abandoned coal
mines. The technology has been developed for remote filling of mines and the cost is
estimated at $2.00 to $4.00 per ton within 30 miles of the source if the fly ash is provided
free of charge by the utility. Since many large coal-burning power plants are located near
coal mining areas, the filling of abandoned mines appears to be an excellent means for
utilizing/disposing of the entire amount of fly ash produced by these utilities. Many utilities
are currently incurring costs of up to $2.00 per ton to dump fly ash and as much as $4.00
per ton where local regulations require the utility to landscape the land fill area. This factor
plus the economic considerations of land value improvement resulting from the elimination
of mine subsidence could possibly justify the economics of this form of utilization,
particularly when more profitable uses cannot be employed.
Land Fill
Where structural land fill is required and hauling distances are short, fly ash can
often be used more economically than other fill materials and can provide technical
advantages. Among these advantages are ease of handling and spreading, low compaction
density, and shear strength that continues to increase with time (a consequence of
pozzolanic reaction with residual lime content in the ash). Fly ash covered with soil provides
excellent drainage for vegetation. Also, any grade of fly ash is adequate and does not have to
-------
K-ll
be stored, handled, or hauled in an enclosed and dry condition. However, the use of fly ash
for land fill (excluding fly ash disposal) is not widely applied in this country. It has
demonstrated its usefulness in the United States in embankments and abutment backing in
highway construction, but it is not widely used for these purposes because of the availability
of natural fill materials. Except for such special circumstances as extremely high fill
embankments for roadways built over weak subsoils or unavailability of local fill materials,
little use of fly ash as a land fill is expected except for disposal purposes.
Mineral Wool
The use of fly ash as the raw material for mineral wool manufacture requires no
deviation from the state-of-the-art commercial manufacture of mineral wool; there appear to
be no technical inhibitions to the use of fly ash in this application.
However, inhibitions are apparent in the comparative economics of manufacture and
in the likelihood of overcapacity in competition with current mineral wool and fiberglass
insulation materials. To date, there is no market for fly ash mineral wool.
Gas Concrete
Gas concrete is a porous concrete building material. It is approximately one-fourth
to one-third the density of ordinary concrete and utilizes fly ash up to 80 percent of the
solid constituent weight. Gas concrete is made in patented European processes and,
although widely used in many foreign countries, is not used in the United States.
European utilization of gas concrete proves to be a highly desirable form of building
material from the standpoint of construction economy and structural qualities. It is used in
at least 20 countries. It is used on a wide scale in Denmark. Gas concrete is used in West
Germany in the construction of 80 percent of all new factory buildings. In Sweden, its use
approaches 100 percent, and in the Philippine Islands, it is now being used for the
construction of low-cost housing projects. In England, it is estimated in 1971,
approximately 1 million tons of fly ash was consumed in gas concrete. Since fly ash
improves the quality (higher strength per unit volume) of gas concrete, reduces capital and
production costs, and is available in abundance in urban areas, it could conceivably find a
large market throughout the United States as a constituent of gas concrete. Additionally, fly
ash used for this purpose does not have to be fine quality; that it can be hauled and applied
in a wet state simplifies handling.
The future of gas concrete in this country is not readily assessable. As a new
technology, it would have to compete with numerous well-established building techniques
using conventional materials. To establish fly ash concrete as a building construction
material on a wide scale would require substantial technical and economic surveys, coupled
with dissemination of the technology and proven results.
-------
K-12
Miscellaneous and Potential New Uses
Such other uses as in foundries, grouting, pipe coating, and oil well cementing are
considered to have a low potential for the consumption of large quantities of fly ash. A large
potential exists for such possible new uses such as sewage filtration/soil supplement
applications, ceramics and mineral recovery, none of which has been developed.
B. Limestone-Modified Fly Ash Utilization
Limestone injection and/or scrubbing processes for the control of sulfur oxides can
increase the amount of fly ash produced by as much as 1-1/2 to 3 times. These processes, if
widely used, could have an appreciable impact on the existing and potential unmodified fly
ash market.
Dry collected (LMF) was analyzed as collected and also after separation by mineral
dressing techniques such as sizing, specific gravity, magnetic, electrostatic, and surface
chemical (flotation) properties. Results of the whole sample analysis indicated that levels of
silica, alumina and iron oxide, the major constituents of normal fly ash, are decreased while
the lime and magnesia content is greatly increased with dolomite injection and the lime
content is greatly increased with limestone injections. Based on extensive physical
separations attempting to concentrate usable minerals, and utilization tests on the whole
and sized fractions of modified fly ash, feasibility of utilizing modified fly ash in the
manufacture of salable products was evaluated. This effort resulted in the classification of a
number of possible uses for the material into the following technically potential
categories.2'3
1. High Potential
a. Mineral wool
b. Sulfur dioxide recovery
2. Medium Potential
a. Acid mine drainage neutralization
b. Concrete admixture
c. Cement kiln raw material
d. Soil stabilizer and amendment
3. Low Potential
a. Mineral recovery
b. Fluxing agent
c. Lightweight aggregate
d. Fired structural products
e. Unreacted calcium recovery
Following this effort the chemical and physical properties of wet-collected LMF
were analyzed in addition to more intensive analysis of dry-collected LMF. Chemical
-------
K-13
analyses were performed using wet chemical, atomic absorption and atomic emission
spectroscopic methods; physical analyses, employed mineral dressing, microscopic and X-ray
techniques. The main constituents of modified fly ash were found to be silicon, calcium
(and magnesium if dolomite is used as the modifying stone), aluminum, iron and sulfur.
Wet-collected modified ashes usually had a higher sulfur content than dry-collected ashes
though the amount of sulfur present in the ash is determined not only by the efficiency of
the sulfur removal system but also by the amount of sulfur found in the coal burned. The
physical melting properties of modified fly ashes were quite similar and all ashes tested
melted within a temperature range of 2150°-2300°F. This similarity of physical
characteristics was substantiated by microscopic analysis. Predominant size fractions of
almost all ashes tested were 325 x 400 or -400 mesh. Sieve analysis of the three ashes most
often used showed little or no beneficiation of elements upon sieving. The possibility of
substituting the modified fly ash for regular fly ash in some of the more prominent current
utilizations and in a limited number of new applications was evaluated by small-scale
production simulating, as closely as possible, commercial production processes. A
comparison of properties and characteristics yielded the following categories of technical
potential.4'5 Specific results and conclusions are included for each high potential
application. Additional data on these as well as details of low potential applications may be
found in the references identified.
1. High Potential of Utilization
a. Mineral wool
A carbon-arc tilting furnace was used to melt a wide variety of modified fly ash
samples and mineral wool was produced by pouring the molten material from the furnace in
a thin stream and into a jet of 90 to 95 psig compressed air. The air imparted a shearing
force to the molten mass, breaking the stream into small droplets which formed fibrous
"tails." Any solid remnants of the original droplets are termed "shot." Characteristics of the
mineral wool produced are shown in Table 2. All pouring temperatures are below those
necessary for wool production from bottom ashes and current commercial raw materials.
A significant difference was observed in the production yields from the individual
samples. A much higher yield was obtained from sample KPL, the only wet-collected
limestone modified fly ash availble, than from the dolomite fly ash. The lowest yield was
obtained from sample CM, dry-collected dolomite modified fly ash, in which the coal and
dolomite were premixed upon entering the combustion area. In comparing the acid/base
ratios (percent silica plus percent alumina)/(percent lime plus percent magnesia) sample KPL
at 1.30 falls closest to the generally accepted mineral wool production range of 0.85 to
1.25. SLD and Cl (1.87 and 1.58 respectively) had lower yields than KPL.
Although samples CM and Cl were produced from the same coal and the same
dolomite, a difference in their yields of mineral wool was noted, possibly due to the
different methods of introducing the dolomite at the boiler. Sample CM was formed by
-------
Table 2
Production Characteristics of Mineral Wool
Sample
KPL
SLD
Cl
CM
CU
Type
Wet Collected Limestone Modified
Wet Collected Dolomite Modified 1.87
Dry Collected Dolomite, Injected 1.58
Dry Collected Dolomite, Mixed
Unmodified
Acid
Base
Ratio
1.30
1.87
1.58
1.52
9.79
Pouring
Temp.
°F
2700
2800
2700
2700
3000
Blowing
Pressure
psig
92
90
93
95
95
Yield
High
Moderate
Moderate
Low
None
Comments
Light brown, short fluffy
fiber, very little shot
Gray, some brittle fiber,
moderate shot
Gray, resilient fiber,
moderate shot
Gray, fluffy fiber, heavy
shot
No fiber formed
-------
K-15
premixing the dolomite and coal before pulverization and entry into the boiler while sample
Cl was formed by injection of the dolomite above the flame envelope.
Unmodified ash sample CU was utilized as a control. As shown in Table 2, no fiber
could be produced even at temperatures as high as 3000° F.
Quality tests performed in accordance with the Department of Commerce,
Commodity Standards Division: Commercial Standard CS 131-146 yielded the results
shown in Table 3. Loose shot was removed from the samples which included a commercial
mineral wool for comparison.
Although high quality mineral wool (accompanied by sulfur regeneration)—equal to
or better than commercial mineral wool—was produced from both dry-collected and
wet-collected limestone-modified fly ash, there is no market potential for the product since
it is being replaced by glass wool.
b. Calcium-silicate brick
Calcium-silicate (CS) bricks of superior quality (compressive strengths in excess of
7000 psi) were produced from limestone and dolomite modified fly ashes. Experimental
work proceeded in three phases with pellets (1" diameter by 3/8" thickness) being made
initially to determine basic composition mixtures, forming pressures and autoclaving
conditions for each individual modified fly ash examined. Dry-collected modified ash, and
wet-collected ash, were selected for the second phase of research—the production of 2" x 4"
x 1-3/8" bench-scale brick. This phase of the research dealt primarily with such processing
variables as forming pressure, mixing, humidity curing, etc. In the final phase, full size brick
was produced using common commercial equipment to determine whether the process
could actually be scaled up.
Data obtained from the pellet tests indicated that CS brick could be produced from
modified fly ash. When using dry-collected modified fly ash, the brick mix consisted of 50
percent'(on a dry basis) modified fly ash, 50 percent silica sand and approximately 20
percent water; when wet-collected modified fly ash was used, CS brick could be produced
containing 50 percent (on a dry basis) modified fly ash, 39 percent sand and 11 percent
calcium oxide. Using wet-collected KPL fly ash, the process involved a dewatering of the
slurry to 34 percent water before mixing. Such a composition provides sufficient water for
mixing and forming of the green brick.
In the final phase of the testing program, 2" x 4" x 8" full size brick samples were
prepared using a hydraulic-toggle dry-press. The final products met or surpassed ASTM
(73-51 and 73-67) specifications of 4500 psi compressive strengths and less than 1 percent
shrinkage for grade SW, severe weathering, calcium-silicate brick. An average batch of brick
made from dry-collected ash displayed characteristics of 4600 psi compressive strength, 20
percent absorption and no measurable shrinkage; wet-collected ash produced brick with an
average 4500 psi compressive strength, 28 percent absorption and no measurable shrinkage.
High technical potential was demonstrated for calcium-silicate brick made from
modified fly ash. Although this type of brick is used in Europe it has no current market in
the United States.
-------
Table 3
Quality Tests on Mineral Wool
Sample
KPL
SLD
Cl
CM
Commercial
Average
Fiber
Diameter
2.5u
3.0u
5.6u
5.4u
8.4u
Attached
Shot
wt. %
14.0
32.0
34.0
36.0
N/A
Moisture
Adsorption
St. %
0.001
0.00
0.00
0.00
0.00
Odor
Emissions
No Apparent Difference
No Apparent Difference
No Apparent Difference
No Apparent Difference
No Apparent Difference
Fire
Resistance
Incombustible
Incombustible
Incombustible
Incombustible
Incombustible
Corrosion
Retardance
Noncorrosive,
no etching
Noncorrosive,
no etching
Noncorrosive,
no etching
Noncorrosive,
no etching
Minor Corrosic
no etching
-------
K-17
c. Aerated (gas) concrete
Aerated or foamed cellular concrete is a lightweight structural material consisting of
small noncommunicating gas cells entrained in a calcium-silicate matrix. It is produced by
inducing gas bubbles within a cementitious paste normally composed of cement and/or lime
and a fine grained siliceous material.
The bubbles of gas are produced by one of two general methods:
1. By the formation of gas by chemical reaction within the mix during the liquid or
plastic stage, for example:
2A1 +3Ca(OH)2 +6H2O »- 3CaO • A12O3 • 6H2O + 3\-\2 ^ •
or
2. By introducing air from without, either by adding a preformed foam or by
incorporating air by whipping.
When the first method is used, the hydrogen in the cells is replaced by air in a short
time and no fire hazard exists. The gas-cement mixture is allowed to set in air and is then
steam cured at high pressure. Aerated concrete made in Europe using normal coal fly ash as
the siliceous component is high in strength and light in weight—their best products having
compressive strengths of 200-800 psi for concrete with a density range of 30-45 Ib/cu ft.
Aerated concrete also exhibits advantageous thermal insulation and acoustic properties.
Aerated concrete was produced from dry-collected limestone modified fly ash using
the technology employed by European manufacturers with one basic exception. Utilizing
the "free" lime content in dry-collected modified ash, the addition of lime is not required—a
significant cost reduction. Aluminum powder is used to generate gas bubbles and portland
cement is added to provide strength.
Dry-collected limestone modified fly ash from the Shawnee Steam Plant at Paducah,
Kentucky (TVA), was selected for the bench-scale production of aerated concrete because
of its high reactive or "free" lime content and its large siliceous component. It was found
that aerated concrete could be prepared from this ash without the use of any additional
material except water and aluminum powder—the aerating agent. The cured concrete had a
compressive strength of 400 psi at a density of approximately 50 Ibs/ft3. Portland cement
was then added to the mix to increase the compressive strength of the product. The density
increased to 56.3 Ibs/ft3 when using cement and the compressive strength was increased to
more than 855 psi. The addition of portland cement also stabilized the aerated mix prior to
autoclaving. This is a critical factor because setting must occur after aeration is completed
and before the entrained bubbles collapse.
Although these early results indicated high technical potential worthy of additional
research—comparable compressive strengths at somewhat higher densities—there is no
current market for aerated concrete in the United States.
-------
K-18
d. Formed concrete block
Research on calcium-silicate brick production showed that autoclaving increased
calcium-silicate bond formation. As a result, the feasibility of using modified ash as the
cementing agent for the production of concrete block was investigated.
The composition of the cement block was the same as for calcium-silicate brick with
the exception that less dewatering was required. The composition consisted, on a dry basis,
of 50 percent wet-collected modified fly ash, 39 percent silica sand (30 x 100 mesh) and 11
percent lime (95 percent CaO). Also, the material was poured into molds instead of pressed.
No prior grinding or crushing of the modified ash raw material was required. The resulting
poured concrete, which was similar to concrete block, had a bulk density of 90 Ib/ft3 as
compared to 150 Ibs/ft3 for conventional concrete block and a compressive strength of
approximately 900 psi as compared to 1000 psi for conventional block. Although addition
of the necessary aggregate could raise the bulk density to 100 Ib/ft3 , this would still be only
2/3 the bulk density of standard block. The blocks produced out of the autoclave were full
strength, nonshrinking products which do not require the 3-4 weeks air curing time before
sale as does the conventional concrete block. On this basis, storage requirements could be
reduced. However, as in the case of calcium-silicate brick, implementaion would require new
techniques of production such as dewatering and autoclaving. As a result, there is no current
U.S. market for formed concrete material made from modified fly ash.
2. Low Potential of Utilization
a. Soil amendment
b. Ceramic materials
c. Recovery of SO2 (thermal)
d. High-pressure alumina leaching
e. Flotation as a means of producing separate fractions
Techniques for dewatering the wet-collected limestone-modified fly ash were
evaluated in a follow-on project with the following resultant classifications of technical
potential.5
1. High Potential
a. Settling
b. Pressure filtration
c. Centrifugation
2. Medium Potential
a. Flocculants
Details of the results are currently unavailable, however, settling is considered the optimum
technique based on both economical and technical considerations. Pressure filtration and
centrifugation, while having high technical potential, are not expected to be economical
because the large volumetric capacities required could result in large equipment multiples.
-------
K-19
IV. Summary
Limestone-modified fly ash differs considerably, both chemically and physically,
from unmodified ash and does not lend itself to direct substitution for regular ash, as it is
used today. In addition, the chemical and physical properties of modified ash vary to a large
degree based upon the sulfur and ash content of the coal and subsequent removals during
flue gas treatment.
There are, however, potential uses for the modified ash: some, the same as for
regular ash; others not yet developed. Such miscellaneous factors as quality variation, water
content, sulfur (sulfite, sulfate, gypsum) content, pozzolanic properties, quantities available,
trace element content and toxicity and unreacted lime content need to be thoroughly
evaluated for specific applications before applicability can be finally assessed. Research and
development programs are necessary to determine and subsequently demonstrate the
technical and economic feasibility of utilizations of this material.
General areas of potential technical utilization include autoclave products, structural
or land fill, bituminous filler, pozzolanic materials, cement manufacture, pressure-sintered
products, gypsum products, and mineral recovery. Immediately promising areas are
autoclave products (sulfur would not be released), gypsum products (LMF contains large
amounts of gypsum), road base course material (it contains lime, has pozzolanic properties
and the potential market is large), and sulfur recovery (although the economics are not
promising, it could supplement a sintering process).
Since the modified ash cannot currently replace regular ash in its utilization, its
immediate impact on the regular ash market would be negative. It is possible, however, that
processes can be developed that would make it usable by the time it is produced in
appreciable quantity.
V. Recommendations
Although not the main thrust of the current program, recommendations are
presented for unmodified, as well as for modified fly ash, because use of the former would
contribute to the economic solution of the solid waste problem. Additionally, its use is
expected to precede (and pave the way for) the use of modified fly ash since the former is
more familiar, well characterized, and in current abundance. Recommendations are
presented for wet-collected limestone-modified fly ash since dry-collected
limestone-modified fly ash is not expected to be nationally abundant because of the limited
application of the dry limestone injection process. However, the dry process may be utilized
in a particular geographic area or localities which would make the dry-collected modified
material locally available. The properties and characteristics of the dry-collected material are
not expected to be sufficiently different from the dewatered wet-collected material to
preclude its use for certain applications.
-------
K-20
All recommendations have been submitted for review to appropriate agencies; e.g.
the Department of the Interior and the Department of Housing and Urban Development.
A. Unmodified Fly Ash
Existing inhibitions to the utilization of regular fly ash are of such magnitude that
only a small percentage of the ash produced today is utilized. These restraints will continue
to prevent an appreciable growth of the fly ash market unless appropriate research,
development, and survey programs are carried out. These programs may reduce inhibitions
that retard fly ash sale on a profitable basis.
Major areas of interest for new efforts are structural concrete, road base course
materials, and such new products as gas concrete, ceramics, and mineral recovery. Sufficient
effort is already being applied to the advancement of the fly ash lightweight aggregate
technology. An effort should also be directed toward the extended use of fly ash as a mine
void fill, particularly since it could be an interim measure until the efforts requiring more
lead time are completed and put into practice.
The recommendations are:
1. Expeditiously develop a new set of specifications or a handbook for the use of fly
ash in portland cement concrete which would provide a standard utilization to
produce predictable results. This would include the application of various grades of
fly ash (pertinent parameters such as residual carbon, fineness, and pozzolanic
activity) to concrete usage and encompass cure times beyond 28 days. These
documents could be modeled after TVA specifications G-2 and G-30. A testing
program will be required to provide statistical data to support this program.
2. Conduct a marketing survey for various regions within the fly ash supply areas to
determine the economic feasibility of fly ash gas concrete in various forms of
building construction in the United States.
3. Conduct a technical and marketing survey in various regions of fly ash producing
areas to determine the justification for an advisability of action by government
road contracting agencies regarding the use of fly ash in the base course section of
Federal, state, and local paving program contracts.
4. Investigate the possibility of recovering minerals from fly ash.
5. Evaluate the net economic effects of coal-washing or gasification on the fly ash
market and on the cost of ash disposal.
6. Conduct a technical and economic survey relating to land reclamation and to the
remote filling of mine voids for control of mine subsidence and fires. This would
include the economics of fly ash usage and land reclamation values; and the effects
of fly ash on ground waters. Consider the use of empty returning coal cars or a fly
ash slurry for transportation.
7. Conduct research to develop or improve such fly ash uses as ceramic products,
optimized fly ash gas concrete.
-------
K-21
8. Conduct fundamental research to identify the intrinsic characteristics and properties
of fly ash to provide the basis for subsequent research into new uses of fly ash.
Although this has been performed in part at various organizations, results of
complete characterization are not published.
B. Wet-Collected Limestone-Modified Fly Ash
Determining the potential use of modified ash depends on research and development
programs and marketing surveys to establish the potential marketability of developed
products in terms of public acceptance and ability to compete with other products,
including those produced from regular fly ash. The following programs are recommended:
1. The most critical research need for wet-limestone-modified ash is the fundamental
characterization of its chemical and physical properties. This characterization will
provide the basis for the subsequent utilization and toxicology research
recommendations.
2. Conduct research and development programs on potential mass uses of modified fly
ash including filler material, autocalve products, pozzolanic materials,
pressure-sintered products, and gypsum products. These programs should be broad
enough to allow the possible emergence of uses not yet identified. These programs
should also consider the mass usage of modified ash in situ and beneficiated in
processes in which sulfur is not released and recovered.
3. Investigate the recovery of mineral ore from the modified fly ash.
4. Determine the physical state of toxic elements within the modified fly ash, the
source of these elements (coal ash or limestone), the role of wet collection in
preventing mass contamination via particulate and gaseous effluents, and potential
hazards that may exist (particularly through leaching) in the ash disposal and
utilization.
5. Conduct an economics survey of the phase of electric power production involving:
the effects of fuel preparation and delivery, pollutant removal, residue disposal, and
product credits. Examples of trade-offs which should be made include: (a) scrubbing
of fly ash and gases resulting from the combustion of untreated coal, (b) scrubbing
of fly ash and gases resulting from the combustion of cleaned coal, (c) gasification of
coal, and (d) liquefaction of coal.
6. Conduct surveys to determine the potential for marketing recovered sulfur and
products to be developed for the use of modified fly ash. Also, consider the
development of products which are already partially developed; e.g., mineral
aggregate and road base course materials.
-------
K-22
VI. References
Reports identified by numbers prefixed "PB" are currently available prepaid from:
National Technical Information Service (NTIS), U.S. Department of Commerce, 5285 Port
Royal Road, Springfield, Virginia 22151. Others will be available approximately one month
after receipt by NTIS.
1. Aerospace Corporation Report No. TOR-0059(6781)-1. PB 209-480, Final Report
on "Technical and Economic Factors Associated with Fly Ash Utilization," July 26,
1971, EPA Contract FO4701-70-C-0059.
2. Coal Research Bureau, West Virginia University, PB 185-802, Final Report on
"Study of the Potential for Profitable Utilization of Pulverized Coal Fly Ash
Modified by the Addition of Limestone - Dolomite SO2 Removal Additives," April
1969, EPA Contract PH86-67-122.
3. Ibid., PB 196-779, Final Report on "Study of the Potential for Recovering
Unreacted Lime from Limestone Modified Fly Ash by Agglomerate Flotation," May
1970, EPA Contract PH22-68-18.
4. Ibid., Final Report, "Pilot Scaleup of Processes to Demonstrate Utilization of
Pulverized Coal Fly Ash Modified by the Addition of Limestone-Dolomite SO2
Removal Additives," March 1972, EPA Contract CPA70-66. Submitted to NTIS
December 11, 1972.
5. Ibid., Final Report Draft, "Technical and Economic Evaluation of Dewatering,
Production of Structural Materials, and Recovery of Alumina from the
Limestone-Modified Fly Ash Produced by a Limestone Wet Scrubbing Process,"
Final Report anticipated early 1973, EPA Contract EHSD71-11.
-------
APPENDIX L
Process Economics
-------
L-l
PROCESS ECONOMICS
I. Introduction
One of the primary goals of the EPA-TVA dry limestone injection test program is to
better define the process economics for potential users. The economics given in the 1968
EPA-TVA conceptual design and cost study (12) of the process were based on limited
background and performance data; therefore, refinement of the earlier cost estimates is
highly desirable and is now possible using the results of the Shawnee test demonstration.
Investment requirements estimated in 1968 were based mostly on discussions with
solids handling equipment suppliers with some guidance from the TVA Office of
Engineering Design and Construction in Knoxville, Tennessee, plus the use of indirect cost
and installation factors derived from actual projects and from published estimating material.
At that time, the most desirable limestone particle size and point of injection were
unknown, predrying was not deemed necessary, solids disposal was assumed to be simple
with water quality unaffected, and the full effect of injected calcium material on dust
removal efficiency of electrostatic precipitators was speculative. All of these requirements
have been given careful attention and definition by the Shawnee test program.
One factor of concern in 1968, which calcium base material should be utilized, is no
longer of major importance since dried limestone serves as well as calcined limestone (CaO)
or hydrated lime [Ca(OH)2 ], both of which are two to three times more expensive. In the
earlier cost study, only a few limestone suppliers across the United States were contacted
for price data. Since then, the M. W. Kellogg Company has completed for EPA a much more
comprehensive survey (8) of limestone supply and price data, and the information is utilized
in this process cost evaluation.
In the earlier operating cost estimates, utilities usages were calculated and capital
charges were based on nonregulated economics; that is, no provisions were assumed for
maintaining the utility's rate of return on investment for the additional investment. As a
result, an impractical, low rate of capital charges was assessed. In addition, a chemical plant
operating stream time (8,000 hrs/yr) was used instead of a power plant's historical declining
load factor and effort was not made to predict the lifetime operating costs of the system.
In the evaluation to follow, the actual cost of the Shawnee injection system,
improved definition of raw material costs and desired particle size of injection material,
actual utilities usage rates, more realistic capital charges and operating periods, recent air
pollution emission requirements, refined dust removal technology, and equipment estimates
by a precipitator manufacturer permit a far more accurate cost appraisal than was possible
in 1968. However, it should be recognized that the accuracy of the newer estimates can be
affected greatly by the difficulty of retrofit to a power unit, labor costs in the particular
unit location, the closeness to a limestone source, the need and convenience of additional
disposal area for the waste solids produced, local air and water pollution regulations, and the
moisture content of purchased stone.
-------
L-2
At this stage of development, the major factors affecting process economics include
(1) power unit size, (2) sulfur content of fuel, (3) stoichiometric rate of limestone injection,
(4) particle size of injected limestone, (5) particulate removal requirements, (6) solids
disposal needs, (7) raw material costs, (8) annual operating time, and (9) remaining life of
the power unit. Items (1) through (3) are the most significant factors in establishing costs
since they determine the amount of limestone to be processed and, therefore, the required
capacity of the equipment. However, item (4), particle size of injected limestone, has some
effect on absorption efficiency, thereby influencing design of the grinding system and
affecting both investment and operating costs. Particulate removal requirements, item (5),
are, in part, fixed by the level of injection and emission laws prevailing in the plant location.
However, the investment and operating costs associated with particulate collection vary
depending on existing collection facilities and the type of additional facilities installed. The
method and costs for disposing solids may also differ for various power plant installations.
Raw material costs, annual operating time, and remaining life of the power unit do not
influence investment; however, these items directly influence operating costs.
II. Approach
To evaluate the major factors, a variety of unit sizes, fuel sulfur levels, and limestone
injection stoichiometries are chosen for case projections of fixed investment requirements,
annual operating costs, and lifetime operating costs. Using selected cases, other key factors
are also varied to analyze their sensitivity on process economics. The projections made are
based on applicable design premises resulting from the Shawnee test program, plus the
actual cost of the test facility and the actual utilities usage rates. A flow diagram of the
proposed process and detailed material balances were prepared to serve as guides in
determining equipment sizes and requirements for the various cases. Operating experience
for TVA coal-fired power units is also utilized in the evaluation technique. For convenience,
all projections are based on 1972 costs for the midwestern United States.
Results of the Shawnee tests indicate that, within limits, SO2 removal efficiencies
increase with the addition of greater amounts of limestone to the boiler. However, the
associated costs and operating difficulties also increase. To determine the effect of limestone
addition rate on process economics, a 52-case parametric study is used to cover the various
unit sizes, sulfur levels, and injection stoichiometries. Cases were selected to expand the
applicability of the Shawnee results over a broad range. Table 1 gives a detailed accounting
of the chosen case combinations.
Design Premises—For the 52 cases, applicable design premises were established for
the power unit, fuel, absorbent, combustion, reactions, SO2 emission reduction, reaction
products, and particulate collection and disposal method. A detailed listing of these
premises follows:
A. Power unit
1. Size-50, 150, 250, or 350 MW.
2. Location - midwestern region.
3. Type plant - existing, pulverized coal, frontal-fired unit.
4. Years remaining life - 15.
-------
L-3
Table 1 - Dry Limestone Injection Case Combinations
Existing Coal-Fired Units
Injection stoichiometry, moles CaO injected per mole sulfur in coal
0.8% Sin coal 3.0% S in coal 5.0% S in coal
50 MW power units
150
250
350
3.0
4.0
5.0
6.0
7.0
MW power units
3.0
4.0
5.0
6.0
7.0
MW power units
3.0
4.0
5.0
6.0
7.0
MW power units
3.0
4.0
5.0
6.0
7.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
B. Coal
1. Heat value-12,000 BTU/lb.
2. Ash content - 16.0%.
3. Sulfur content - 0.8, 3.0, and 5.0%.
C. Limestone characteristics and preparation
1. Type - calcite.
2. Composition - 95.0% CaCO3 and 5.0% impurities (dry basis).
3. Purchased moisture content - 5.0% H20.
4. Purchased size - minus 1-1/2 in.
5. Moisture reduction - dried to approximately 0.5% H2 0 prior to grinding.
6. Drying source - off-gas from combustion of No. 2 fuel oil with 20% excess air.
7. Size reduction - dry ground to 80% minus 400 mesh prior to injection.
-------
L-4
8. Transport ainlimestone injection ratio - 1:10.
9. Injection stoichiometry variations -
0.8% S coal, 3.0 to 7.0 moles CaO: mole S in fuel.
3.0 and 5.0% S coal, 1.0 to 4.0 moles CaO: mole S in fuel.
D. Combustion
1. Coal consumption prior to dry limestone injection - 0.780 Ibs/kWh.
2. Excess air to boiler for combustion of coal - 25%.
3. Air inleak at air preheater - 13%.
4. Particulate emission - 75% of ash is emitted as particulates and is present in the
off-gas.
5. Sulfur emission - 92% of sulfur is emitted as SO2; remainder is chemically bound
with the ash.
E. Boiler reactions, S02 emission reductions, and reaction products
1. Dried CaCO3 decomposes to CaO and CO2 within boiler.
2. Heat required for decomposition is supplied by combustion of additional coal.
3. For 0.8% S fuel, 5% of S02 in the gas combines with CaO per unit of stoichiometric
limestone injected.
4. For 3.0 and 5.0% S fuel, 10% of SO2 in the gas combines with CaO per unit of
stoichiometric limestone injected.
5. All CaS03 formed by reaction of CaO and SO2 is oxidized to CaSO4 within the
boiler.
6. All of the solid products resulting from limestone injection are present in the boiler
off-gas as particulates.
F. Particulate collection
One of the drawbacks of dry limestone injection is the introduction of additional
solids into the boiler, which requires additional particulate collection and disposal
facilities. Figure 1 shows the effect of injection stoichiometry on the inlet particulate
loading to the dust collectors for the three levels of sulfur evaluated. Design of the
particulate collection facilities is based on the following premises:
1. Existing particulate collection facilities - mechanical collector followed by
electrostatic precipitator.
2. Overall particulate collection efficiency of existing facilities - 99%, equivalent to a
particulate emission of 0.03 grains/acf.
3. Additional electrostatic precipitator capacity is installed to maintain a dust emission
level after dry limestone injection equivalent to the emission level prior to injection.
Reflecting the limestone injection case variations, Table 2 shows the calculated
particulate rates at the entrance to the dust collectors for a 150 MW unit, and the overall
collection efficiency required to maintain the base emission level defined above. These
collection efficiencies are shown graphically in Figure 2.
G. Particulate disposal
Additional disposal facilities for handling the incremental solids are provided for
each installation. Figures 3, 4, and 5 indicate the incremental disposal requirements
-------
20
15
o
Cfl
10
at
!H
00
f\
60
-S
*a
eg
o
en c
3 5
13
4J
-------
Table 2
Dust Removal Requirements for
Dry Limestone Injection Case Study - 1 50 MW Plant
(To Maintain Base Emission Level)
Case
0
1
2
3
4
5
6
7
8
9
10
11
12
13
Sulfur
content
of coal,
%
3.0
0.8
0.8
0.8
0.8
0.8
3.0
3.0
3.0
3.0
5.0
5.0
5.0
5.0
Injection
stoichiometry,
moles CaO/mole
S in fuel
no dry
limestone
injection
3.0
4.0
5.0
6.0
7.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
Gas rate,
acfm @310° F.
507,700
503,800
505,200
506,900
508,100
509,600
512,500
517,800
522,700
528,000
519,000
527,900
537,000
547,000
Inlet to
Dust
Fly ash
14,040
14,100
14,120
14,150
14,160
14,1.80
14,100
14,180
14,240
14,310
14,150
14,270
14,390
14,540
dust collector
rate, Ibs/hr
Injection
products
-
5,740
7,660
9,590
11,530
13,480
7,580
15,240
22,990
30,810
12,670
25,580
38,750
52,250
Dust loading,
grains/acf
3.23
4.59
5.03
5.46
5.90
6.33
4.94
6.63
8.31
9.97
6.03
8.81
11.55
14.25
Allowable
emission,
lbs/hra
140
141
141
141
142
142
141
142
142
143
141
143
144
145
Overall dust
collection
efficiency
required, %
99.00
99.29
99.35
99.41
99.45
99.49
99.35
99.52
99.62
99.68
99.47
99.64
99.73
99.78
Outlet dust
loading
grains/acf
.03
.03
.03
.03
.03
.03
.03
.03
.03
.03
.03
.03
.03
.03
a. Equivalent to 99% removal of fly ash emitted from combustion of coal containing 16% ash
-------
,100.0
•u
<0
1-1
•rl
I
99.8
•1-1
o
>i-i
M-l
<4-l
0)
g 99.6
•H
4J
O
t-l
O
U
§ 99.4
I
99.2
0
I I I I
Inlet fly ash loading prior to injections* 3.23 gr/acf
Outlet loading after dust collection - O.OJ gr/acf
24 68
Stoichiometry, moles CaO injected per mole S in coal
Figure
Effect of Injection Stoichiometry on Overall Dust
Collection Efficiency to Maintain Emission Rate
Equivalent to 9956 Fly Ash Collection Prior to
Dry Limestone Injection
-------
00
Figure
50
5
100 150 200
Power unit size,
250
300
350
Incremental Solids Disposal Requirements for Power Units Utilizing
Dry Limestone Injection Process; 0.8$ S Coal
-------
0
50
150 200
Power unit size, MW
250
300
350
Figure
Incremental Solids Disposal Requirements for Power Units Utilizing
Dry Limestone Injection Process: 3»°# S Coal
-------
50
100
150 200
Power unit size, NW
250
300
350
Figure
Incremental Solids Disposal Requirements for Power Units Utilizing
Dry Limestone Injection Process: 5.0$ 3 Coal
-------
L-ll
attributable to dry limestone injection for each variation in.sulfur content as a function
of power unit size and injection stoichiometry. The following method for disposal is
used (11):
1. Fly ash and injection solids are disposed on-site in a common, existing settling pond.
Additional pond facilities are not provided for the incremental injection solids.
2. Distribution facilities are included for supplying raw water to the solids disposal
area. Pipeline distance between the disposal area and the raw water supply point is
estimated as 2,500 ft.
3. Slurry concentration to the disposal pond is designed not to exceed 15% solids.
4. Fresh sluice water is used for disposing the incremental solids, with no provisions for
recycling. Pipeline distance between disposal pond and the solids collection facilities
is estimated as 6,000 ft.
5. A separate disposal line is included for each case, regardless of the magnitude of the
incremental solids disposal burden.
6. Based on vendor recommendations, an 8 in. line is the smallest size which is
practical. Disposal systems are sized with either 8, 10, or 12 in. lines, with a design
fluid velocity of approximately 6 ft/sec and capability of disposing the daily load of
solids over a period of 12 hrs. Based on TVA operating experience, the load factor
for an existing ash sluice line is about 40% or less.
7. Spare incremental solids disposal lines are not provided. It is assumed that the
existing spare sluice lines or the existing operating lines (with relatively low load
factors) can be utilized as spares when required.
8. Based on TVA sluicing practices, sluice water flow through each operating line is
continuous while the power unit is in operation (sluice water and electrical
requirements for pumping are based on continuous flow.)
Using the Shawnee design and operating experience and the design premises
presented above, a projected process flow diagram including provision for dust collection
and disposal was prepared. This flow diagram identifies the major equipment required for
the process and is presented in Figure 6.
Base Case—For convenience in preparing material and energy balances, a separate
base case for each level of sulfur in coal was established. Power unit size was selected to
conform to that of Shawnee Unit 10. Injection stoichiometry for each case was based on the
most probable applications as determined in the Shawnee tests for the various levels of
sulfur in coal. These case combinations are shown below:
Dry Limestone Injection Process Base Case Combinations
Injection stoichiometry,
Power unit size, Sulfur in coal, moles CaO injected/
MW % mole 5 in coal
150 0.8 5.0
150 3.0 2.0
150 5.0 2.0
-------
CYCLONE EXHAUST
TO MECHANICAL
A NO/OR
ELECTROSTATIC
DUST COLLECTOR
SLIDE GATE VALVE
ROTARY VALVE
VACUUM RELIEF VALVE
Figure 6- Proposed Flow Diagram of Dry Limestone Injection Process
-------
L-13
A detailed material balance for each of the base case combinations is shown in
Figure 7
Actual investment—The actual fixed investment for the Shawnee test facilities was
analyzed to provide an equipment, labor, and material cost breakdown for the major process
functions. The results are presented in Table 3 (1). A nine-month construction period during
1969-1970 and a total investment cost of $1,477,581 were required for the test facilities.
The facilities were designed with a 20 ton/hr injection capability equivalent to a 350
MW plant burning 2.0% S coal with an injection stoichiometry of 2.0. Although oversized
for a 150 MW plant, a broad capacity range was necessary because of the research and
development nature of the installation. The actual investment requirements discussed above
include facilities for receiving, storing, drying, grinding, and injection and sampling test
probes for the boiler. Both rail and truck unloading equipment are included. Boiler
modifications such as wall port openings are included along with utilities distribution from
the powerhouse area. Not included are capability for continuous fine grinding, additional
particulate removal facilities, and solids disposal pond for the incremental dust burden. Also
not included are additional soot blowers for removal of deposits which tend to form in the
convection passes of the boiler. The number of required sootblowers may vary for different
installations as a function of boiler tube spacing, temperature regime, and length of
convection pass; however, each is estimated to cost $20-30,000. Since the Shawnee tests did
not indicate the actual number of additional sootblowers required as a result of dry
limestone injection, additional costs are excluded from the investment projections; however,
the sensitivity of total investment as a function of sootblower requirements is discussed in
Section 11.
Investment projections—Based on the dry limestone injection process flow diagram,
the process equipment was subdivided into several areas according to function. For most
process areas, actual 1969 investment costs for the test facilities were updated to 1972
utilizing a Chemical Engineering plant cost index ratio of 138/119 (4). Instead of treating as
separate areas, costs for painting, stairways, handrails, inspection, and testing were
distributed to the appropriate major areas. For the limestone grinding system, updated costs
were obtained from vendors to reflect the capability for continuous fine grind, not available
with the Shawnee facilities.
Costs for facilities at other limestone capacities were projected by scaling the
updated investment according to limestone throughput using appropriate scaling exponents.
Values of these exponents were factored from the literature (6, 9) and from cost quotations
obtained from vendors. Table 4 shows the major equipment areas which were established,
the base 1972 investment corresponding to the updated Shawnee costs, and the scaling
exponent used for projecting costs as a function of capacity ratios.
Costs for the incremental electrostatic precipitator and solids disposal systems were
not scaled according to limestone throughput. Incremental electrostatic precipitator system
-------
ISO MW UNIT, 0.8% S IN COAL, 5.0 CoO:S INJECTION STOICHIOMETRY
STREAM NO.
DESCRIPTION
SCFM
GPM
PARTICULATES, LBS./HR
TEMPERATURE, 'F
SPECIFIC GRAVITY
JNOISSOLVED SOUDS, %
1
LIMESTONE
TO
DRYER
-
AMBIENT
2.7
2
AIR
TO
DRYER
1,200
—
AMBIENT
3
FUEL OIL
TO
DRYER
310
7
—
AMBIENT
.865
4
- CYCLUNlT"
EXHAUST TO
1,530
20
250
5
DRIED
LIMESTONETO
SURGE TANK
_
_
230
6
CIRCULATION
AIR TO
CONVEYOR
8,800
2,750
200
7
CONVEYING
AIR TO
CYCLONE
8,800
18,350
200
a
PULVERIZED
LIMESTONE TO
FEED TANK
_
_
200
9
AIR
TO
COMPRESSOR
1,500
330
_
AMBIENT
10
LIMESTONE-
AIR TO
DISTRIBUTOR
1, 500
330
15,600
110
II
PULVERIZED
COAL TO
BOILER
-
-
AMBIENT
12
COMBUSTION
AIR TO
AIR HEATER
322,000
_
-
no
13
COMBUSTION
AIR TO
BOILER
292,000
_
-
610
14
FLUE GAS
TO DUST
COLLECTOR
34 O.OOO
-
23,720
310
15
FLUE GAS
TO
STACK
341,530
-
141
310
16
SOLIDS TO
SLUICE
EQUIPMENT
-
-
-
310
IT
SLUICE
WATER
267
AMBIENT
18
SLURRY TO
DISPOSAL
POND
286
AMBIENT
1.10
IS
COAL ANALYSIS, % BY WT (AS FIRED BASIS)
H 4.17 ASH 16.00
N 1.23 H20 9.70
C 66.39 0 1.71
S 0.80
COAL CONSUMPTION, .786 LBS./KWH WITH INJECTION
25 % OVERALL SOj REMOVAL FROM GAS (5% /UNIT STOICHIOMETRY)
PARTICULATE COLLECTION EFFICIENCY, 99.41%
ESTIMATED COMPOSITION OF SAS TO STACK EXCLUDING NO,,
% BY VOLUME
COg
12.36
SOj
.04
Oz
5.43
HjO
7.62
150 MW UNIT, 3.0% S IN COAL, 2.0 CaO: S INJECTION STOICHIOMETRY
STREAM NO.
DESCRIPTION
RATE, LBS. /HR.
SCFM
GPM
PARTICULATES, LBS /HR
TEMPERATURE, *F
SPECIFIC GRAVITY
UNWSSOLVED SOUDS, %
1
LIMESTONE
TO
DRYER
24,600
—
-
-
AMBIENT
2.7
2
AIR
TO
DRYER
8,260
1,800
-
-
AMBIENT
3
FUEL OIL
TO
DRYER
470
-
I.I
-
AMBIENT
.863
4
CYCLONE
EXHAUST TO
COLLECTOR
9,850
2,300
-
30
250
5
DRIED
LIMESTONETO
SURGE TANK
23,450
-
-
-
250
«
CIRCULATION
AIR TO
CONVEYOR
60,600
1 3, 200
-
4,140
ZOO
7
CONVEYING
AIR TO
CYCLONE
60,600
1 3,200
-
27,590
200
8
PULVERIZED
LIMESTONETO
FEED TANK
23,450
-
-
-
ZOO
9
AIR
TO
COMPRESSOR
2,300
500
-
-
AMBIENT
10
LIMESTONE-
DISTRIBUTOR
2,300
500
-
23,450
110
II
PULVERIZED
COAL TO
BOILER
118,130
-
-
-
AMBIENT
12
COMBUSTION
AIR TO
AIR HEATER
1,509,640
329,000
-
-
no
13
COMBUSTION
AIR TO
BOILER
1,367,400
298,000
-
-
610
14
FLUE QAS
TO OUST
COLLECTOR
1,619,400
347,000
-
29,390
310
15
FLUE GAS
TO
STACK
1,629,250
349,300
-
142
310
16
SOLIDS TO
SLUICE
EQUIPMENT
29,278
-
-
-
310
17
SLUICE
WATER
165,922
-
332
-
AMBIENT
IB
SLURRY TO
DISPOSAL
POND
195,200
-
355
-
AMBIENT
1.10
15
COAL ANALYSIS,
H ........ 4.17
N ........ 1.23
C ...... 66.39
S ....... 3.00
BY WT. (AS FIRED BASIS)
ASH ____ 16.00
H20 ____ 9.21
0 ....... —
COAL CONSUMPTION, .788 LBS./KWH WITH INJECTION
20% OVERALL SOj REMOVAL FROM GAS HOT./UNIT STOICHIOMETRY)
PARTICULATE COLLECTION EFFICIENCY, 99.52%
ESTIMATED COMPOSITION OF GAS TO STACK EXCLUDING NO,,
% BY VOLUME
COj
12.28
SOg
.15
HjO
7.71
TOTAL
100.00
150 MW UNIT, 5.0% S IN COAL, 2.0 CaO: S INJECTION STOICHIOMETRY
STREAM NO.
DESCRIPTION
RATE, LBS./HR.
SCFM
GPM
PARTICULATES, LBS./HR.
TEMPERATURE, • F
SPECIFIC GRAVITY
UNDISSOLVED SOLIDS, %
1
LIMESTONE
TO
DRYER
41,290
-
-
-
AMBIENT
2.T
2
AIR
TO
DRYER
13,860
3,020
-
-
AMBIENT
3
FUEL OIL
TO
DRYER
790
-
1.8
-
AMBIENT
.865
4
EXHAUST TO
COLLECTOR
16,520
3,860
-
50
250
5
DRIED
LIMESTONETO
SURGE TANK
39,370
-
-
-
250
6
CIRCULATION
AIR TO
CONVEYOR
101,500
22,100
-
6,950
ZOO
7
CONVEYING
AIR TO
CYCLONE
101,500
22,100
-
46,320
2CO
8
PULVERIZED
LIMESTONE TO
FEEDTANK
39,370
-
-
-
2OO
9
AIR
TO
COMPRESSOR
3,900
850
-
-
AMBIENT
10
LIMESTONE-
AIR TO
DISTRIBUTOR
3,900
850
-
39, 370
no
II
PULVERIZED
COAL TO
BOILER
1 1 8.90O
-
-
-
AMBIENT
12
COMBUSTION
AIR TO
AIR HEATER
1.531,590
334,000
-
-
no
13
COMBUSTION
AIR TO
BOILER
1,387,300
302.500
-
-
610
14
FLUE GAS
TO DUST
COLLECTOR
1, 649,200
352,000
-
39,800
310
15
FLUE SAS
TO
STACK
1,665,720
355,800
-
143
310
16
SOLIDS TO
SLUICE
EQUIPMENT
39,707
-
_
-
310
17
SLUICE
WATER
224.993
_
450
-
AMBIENT
IB
SLURRY TO
DISPOSAL
POND
264,700
_
481
AMBIENT
1.10
15
WT. (AS FIRED BASIS)
ASH 16.00
H20 7.21
0 -
COAL ANALYSIS, %
H 4.17
N...' 1.23
C 66.39
S-- 5.0O
& BASIS
HEAT VALUE OF COAL, I2.00O BTU/LB. (AS FIRED BASIS)
75% OF ASH IN COAL EVOLVES AS FLY ASH
LIMESTONE TO SYSTEM CONTAINS 95.0% CoCO3(DRY BASIS) AND 5% HjO
LIMESTONE DRIED TO 0.5% H20 PRIOR TO GRINDING
PARTICULATE RATES IN LBS./HR. SHOULD BE ADDED TO GAS RATES TO OBTAIN THE TOTAL STREAM RATE
HEAT FOR DRYING SUPPLIED BY COMBUSTION OF NO. 2 FUEL OIL WITH 20% EXCESS AIR
MATERIAL LOSSES ARE EXCLUDED FROM MATERIAL BALANCE
COAL CONSUMPTION, .793 LBS./KWH WITH INJECTION
20% OVERALL SOZ REMOVAL FROM GAS (10%/UNIT STOICHIOMETRY)
PARTICULATE COLLECTION EFFICIENCY, 99.64%
ESTIMATED COMPOSITION OF GAS TO STACK EXCLUDING NO*.
% BY VOLUME
COa
12.43
SO;
.24
Oz_
5.39
Nz
74.42
H20
FIGURE 7 DRY LIMESTONE INJECTION PROCESS MATERIAL BALANCES9'
-------
L-15
Tables
Actual Fixed Investment for 20 Ton/Hour
Dry Limestone Injection Facilities
on Shawnee Power Plant Unit No. 10
1969-70 Construction
Direct Cost
General Yard Work
Landscaping
Guard Rails
Relocate access road
Yard lighting
Storage area
Raw water piping
Drains
Subtotal
Limestone Storage and Feed Systems
Truck hopper
Railroad car unloader
Truck hopper unloader
Limestone receiving hopper
Truck unloading conveyor
Limestone storage conveyor
Limestone feed to dryer conveyor
Subtotal
Limestone Drying System
Limestone dryer, drive and combustion
chamber with combustion equipment
Cyclone dust collector-6500 cfm
Trickle valve
Chutes & duct
Dust collecting fan
Dust duct to precipitator
Bucket elevator and drive
Dryer shed
Subtotal
Limestone Grinding System
Surge bin - 1000 cu.ft.
Structural supports
Rotary valve with drive
Volumetric feeder
Ball mill, drive and oiling system
Recirculation fan & drive - 23,000 cfm
Ducts and chutes
Classifier and drive
Structural supports
Storage silo - 6600 cu.ft.
Structural supports
Cyclone - 25,000 cfm
Trickle valve
Bag filter - 595 sq.ft. filter area
Exhaust fan with drive
Rotary valve with drive
Subtotal
Equipment Labor
Materials
$
$
$ 905
5,180
5,180
No cost ,
12,000
17,212
1,591
$ 42,068
$ 46, 522 1
1,876
85
700,
4,300
4,010
$ 57,693
$ 1,748
5,360
1,304
1,705
91,326
3,836
3,410
4,600 1
$
82
121
9,128
1,468
362
401
$ 11,562
) $
( 12,305
(
)
> 12,112
$ 24,417
)
(. $ 6,989
(
)
677
10,910
1,550
9,464
$ 29,590
)
! $ 8,807
f
)
16,656
}
> 2,872
$ 1,600
218
230
2,515
3,023
25
166
$ 7,777
4,463
6,029
$ 10,492
$ 3,193
258
2,348
450
3,843
$ 10,092
$ 3,436
4,730
1,196
5,360j
7,360
11,731
3,836
85
5,968
1,130
1,304
27,120
12,829
Direct
Subtotal
$ 1,600
300
351
11,643
4,491
387
567
$ 19,339
28,033
48,944
$ 76,977
$ 59,365
5,435
13,258
6,010
13,307
$ 97,375
$ 22,360
119,958
14,028
71,363
$150,063 $ 55,455 $ 22,191 $ 227,709
-------
L-16
Table 3 (continued)
Limestone Injection System
Rotary valve with drive
Transport pump with drive
Transport air compressor
Cyclone - 630 cfm
Feed tank - 300 cu.ft.
Bag filter - 530 cfm
Rotary valve with drive
Screw conveyors with drive (2)
Air locks with drives (2)
Air receiving tank
Injection air compressor with drive
Transport air compressor with drive
Limestone distributors
Subtotal
Equipment Foundations
Instrumentation
Control panel and shed
Subtotal
Piping
Drying system
Grinding system
Injection system
Equipment Labor
Direct
Materials Subtotal
Subtotal
Electrical Power Supply
4160 volt board
480 volt board
Limestone injection board
Power and control wiring
Conduit
Cable trays
Grounding
1 elephone
Subtotal
Revision & Addition to Power House & Boiler
Structural steel
Floor grating
Miscellaneous metal work
Conduit, wiring and fixtures
Cooling water supply
Steam lines
Insulation
Ash disposal piping
Boiler additions (injection ports)
Subtotal
Painting
Misc. Stairs, Grating and Handrails
Test Probes - Installation
Inspection and Testing
Direct Total All Catagories
1,304-v
4,936 >
5,968)
5m
1,748 I
1,611 (
1.304/
1,705^
2,608)
4,186}
7,5Q2l
7,502(
256/
$ 41,142
$
6,373
$ 6,373
6,089
24,877
$ 30,966
9,490
$ 9,490
$
$337,795
1,658
14,179
5,414
6,737
$ 27,988
$ 37,951
23,820
1,369
$ 25,189
2,953
12,852
52,245
$ 68,050
1,714
70
190
27,206
28,301
4,205
2,172
870
$ 64,728
$ 1,327
416
6,679
1,236
30,765
5,967
(Contract)
6,216
39,379
$ 91,985
$ 28,008
$ 20,244
$ 46,262
29,054
$560,483
320
3,358
184
771
$ 4,633
$ 27,096
10,172
356
$ 10,528
1,606
2,626
5,336
$ 9,568
9,042
77
325
11,775
3,398
648
245
395
$ 25,905
$ 1,540
1,348
864
644
5,709
223
13,408
4,552
$ 28,288
$ 1,885
$ 7,225
$ 5,678
2,835
$174,193
14,186
22,712
9,911
26,954
$ 73,763
$ 65,047
40,365
1,725
$ 42,090
4,559
21,567
82,458
$ 108,584
10,756
147
515
38,981
31,699
4,853
2,417
1,265
$ 90,633
$ 2,867
1,764
7,543
1,880
36,474
6,190
9,490
19,624
43,931
$ 129,763
$ 29,893
$ 27,469
$ 51,940
31,889
$1,072,471
-------
L-17
Table 3 (continued)
Equipment Labor Materials
Indirect Cost
Construction General Expense
Contractor's Engineering and Fee
TVA Engineering and Overhead
Indirect Total
TOTAL PROJECT FIXED INVESTMENT
Direct
Subtotal
$ 106,365
169,687
129,058
405,110
$1,477,581
Table 4
Major Area Investment Requirements and Exponential
Scale Factors for Dry Limestone Injection Facilities3
Major process equipment
area
General yard work
Limestone storage and feed
system
Limestone drying system
Limestone grinding system
Limestone injection system
Equipment foundations
Instrumentation
Piping
Electrical power supply
Revisions & additions to
powerhouse and boiler
Incremental electrostatic
precipitator system
Incremental solids disposal
system for collecting and
sluicing limestone solids
to pond
a. Capacity = 20 tons limestone/hr.
b. Based on updated vendor proposals
c. Not scaled according to limestone throughput
Base 1972 investment,
$
22,400
111,100
137,600
309,500b
160,100
75,500
51,400
126,000
105,100
150,500
Exponential scaling factor
based on limestone throughput
.50
.80
.50
b
.40
.60
.25
.50
.45
.50
-------
L-18
costs for a 150 MW plant were estimated by Cottrell Environmental Systems, Incorporated
(3) for each combination of sulfur content and injection stoichiometry, based on the change
in properties of the particulates and the additional amount to be removed as a result of dry
limestone injection. Costs were then scaled according to power unit size using an exponent
of 0.85.
The design for incremental solids disposal systems was based on minimum
requirements as indicated by vendors. These investment costs were projected for each
individual installation taking into consideration the quantity of injection solids to be
disposed and the minimum recommended pipeline size.
The sum of the investment requirements for each major process area is called direct
investment. The indirect costs for the project, including engineering design and project
supervision, construction expense, contractor fees, and contingency are added to the direct
investment to obtain the total fixed capital investment. Indirect investment is estimated as a
percentage of direct investment (10) and is based on power unit size as follo.Ws:
Indirect investment costs,
percentage of direct investment
existing power units
50 MW 1&
Engineering design and
supervision
Construction expense
Contractors' fees
Contingency
Total indirects 45 42 41 39
Annual operating cost—On-stream time and power plant load are key factors in
establishing annual operating costs for any process. For power systems, these factors may
vary for different plants within the overall system due to electricity demand and
maintenance. For purposes of projection, annual operating costs are estimated on the basis
of 5,000 hrs operation/yr at full load.
The following is a listing of the breakdown established for projecting annual
operating costs:
A. Direct costs
1. Delivered raw material
a. Limestone
2. Conversion costs
a. Operating labor and supervision including payroll overhead
b. Utilities
(1) Fuel oil (drying)
(2) Sluice water
(3) Electricity
50 MW
9
14
9
13
150 MW
8
13
8
13
250 MW
8
12
8
13
350 MW
8
12
7
13
-------
L-19
c. Maintenance
(1) Labor and material
d. Analyses
B. Indirect costs
1. Capital charges
2. Overhead
a. Plant
b. Administrative
C. Annual operating cost (A and B)
D. Thermal effect of dry limestone injection on operating cost of power plant
E. Total annual cost (C and D)
Each of the above cost components accounts for a portion of the total annual
operating cost, and is discussed below in order of relative importance.
1. Raw material - Limestone is the only raw material required for dry limestone
injection. As indicated in a recent report prepared for EPA by the M. W. Kellogg Company
(8), there are enormous deposits of carbonate rocks in the United States, and reserves are
more than adequate for the foreseeable future. The major deposits, including two-thirds of
all sulfur deposits, are located in the eastern half of the country where the vast majority of
fossil fuel-fired power plants are located. Numerous reserves in these areas provide a nearby
source of stone for most power plants.
Relative to the potential demand for limestone by power plants, production of these
materials is quite large in most states; however, current production is inadequate to supply
the potential needs of power plants in several Atlantic coastal regions, notably New
England.
For a large majority of the power plants in the eastern half of the United States,
high calcium limestone could be delivered for less than $6.00/ton. About half could obtain
stone at less than $4.00/ton. Costs for power plants located in western states generally would
be higher, because of the lack of suitable nearby deposits.
During the injection tests, the delivered cost of limestone at the Shawnee steam
plant averaged $4.05/ton which is compatible with costs reported by Kellogg; therefore, a
delivered cost of $4.05/ton of limestone is utilized for the case projections. For additional
coverage, however, the sensitivity of other limestone prices on process operating costs will
be shown in Section II.
2. Capital charges - The method for financing sulfur dioxide control processes is
likely to depend upon the type of industry providing the investment capital and the nature
of the control process, nonrecovery or product recovery type. In the past, it has been
assumed that nonrecovery pollution control processes installed on power plants are financed
on a regulated utility basis similar to the financing method for the initial power plant. This
method of financing is also assumed for the nonrecovery dry limestone injection process in
the projection of operating costs.
-------
L-20
For the power industry (regulated utility economics), the usual practice of including
in the capital charges a regulated return on investment and the state and Federal income
taxes was followed (5). A breakdown of the capital charges is given in Table 5. The
depreciation rate is straight line, based on the remaining life of the power plant after the
pollution control process is installed, and is a percentage of initial fixed investment.
Property insurance is also based on original fixed investment. However, because most
regulatory commissions base the annual permissible return on investment on the remaining
depreciation base (that portion of the original investment yet to be recovered or "written
off"), the portion of annual capital charge to be applied to the operating cost declines
uniformly over the life of the investment.
Tables
Annual Capital Charges for Power Industry Financing
(Existing Power Unit with 15-Yr. Remaining Life)
As percentage of
original investment
Depreciation (based on 15-yr. remaining
life for an existing power unit) 6.7
Insurance 0.5
Total rate applied to original
investment 7.2
As percentage
of outstanding
depreciation base3
Cost of capital (capital structure
assumed to be 50% debt and 50% equity)
Bonds at 8% interest 40
Equity at 12% return to stockholder 6.0
Taxes
Federal (50% of gross return or same
as return on equity) § Q
State (national average for states
in relation to Federal rates) 4 g
Total rate applied to depreciation
base
a. Original investment yet to be recovered or "written off
base 20.8
-------
L-21
Annual return on equity, interest on outstanding debt, and income taxes are
established in the same manner. The cost of money to the power industry is assumed to be
8% interest on borrowed funds and 12% return on equity money to attract investors.
Assuming a capital structure of 50% debt and 50% equity, the overall cost of money under
regulated economics comes to 10%. Federal income taxes are assumed to be 50% of gross
income and state tax is assumed to be 80% of the national tax; the resulting state tax is
higher than for nonregulated industry, but it is about the nationwide average for power
companies.
The fairly well defined return on investment for the power company makes a low
rate of depreciation acceptable, and return on investment can be logically included in
production cost because it is a fixed charge usually passed on to the power customer.
For convenience in presenting annual operating cost results, average capital charges
based on initial fixed investment are utilized since it is not practical to present the variable
declining balance portion of the charge. For presentation in this manner, capital charges
which normally account for depreciation and insurance are unchanged at 7.2% of original
investment. Charges associated with the cost of capital and taxes are applied as an average
charge equivalent to 10.4% of initial investment. (10.4% x original investment = 20.8% x
average undepreciated investment). When assessed in this manner, the overall rate is
equivalent to 17.6% of the original investment.
The average capital charge multiplied by the number of years of operation gives the
same actual outlay of dollars as the declining balance calculation; however, the present
worth of the two methods is different (discounted to 1972 dollars). There is, of course,
another method (sinking fund depreciation plus interest, or capital recovery factor) of
presenting a single annual percentage of initial investment which gives the same present
worth of the lifetime capital charges as the declining balance calculation approach, but the
actual dollar outlay is different. Of the two procedures, the average capital charge method
has been chosen for annual operating cost tables because it can incorporate straight line
depreciation, thus permitting simpler adjustment of the percentage of initial investment for
power units with various remaining lives.
3. Utilities - During the dry limestone injection test program, utility usages were
measured for the following three processing functions:
a. Limestone receiving, drying and conveying
b. Limestone grinding, classifying, and transport to feed tank
c. Limestone injection into boiler
In addition, utility requirements peripheral to the process such as additional water and
electricity for solids disposal were estimated. The following utility usage rates are projected:
-------
L-22
Utility projections
Process area
a. Limestone receiving, drying and
conveying
b. Limestone grinding, classifying,
and transport to feed tank
c. Limestone injection into boiler
Peripheral area
d. Participate collection
e. Additional solids disposal
Fuel oil
Sluice
water
5.3 gal/
ton limestone
Electricity
6.0 kWh/ton limestone
53.4 kWh/ton limestone
9.6 kWh/ton limestone
Credit3
1.925 kWh/thousand
gal of sluice water
Electricity usage rates for particulate collection varies for each case as indicated by
Cottrell Environmental Systems, Inc. However, CES indicates that the total amount of
electricity required for dust collection is less due to dry limestone injection than is normally
required for collecting fly ash alone; therefore, an operating cost credit is claimed equivalent
to the electricity saved. Unit costs which areincorporated in the case projections for utilities
are shown below:
Utility
No. 2 fuel oil (drying)
Sluice water
Electricity
Unit cost
$0.11/gal.
.03/Mgal.
.007/kWh
Fuel oil cost is based on an acutal 1972 published price for Chicago, Illinois (7). Costs for
sluice water and electricity are also 1972 prices; however, they are somewhat higher than
typical power plant costs to compensate for the additional generation demand placed on the
power unit and to account for the more rapid capital recovery for the additional facilities
than required for new plants.
4. Operating labor and supervision - Operating labor requirements for the dry
limestone injection tests at Shawnee were somewhat high due to the extensive amount of
monitoring required for the numerous sampling probes which were utilized. Consequently,
a. Electricity requirements are reduced as a result of different resistivities of the solids.
Amount of reduction depends upon sulfur content and injection stoichiometry.
b. Sluice water is dependent upon disposal system design rather than total solids disposal.
-------
L-23
projections of operating labor are somewhat lower than incurred during the tests. Since
labor requirements are primarily a function of limestone throughput and on-stream time,
annual labor requirements at 8,760 hours/year (365 days) were estimated for four levels of
injection at full load. These base labor requirements were then adjusted according to
on-stream ratio using a 0.5 scaling exponent. The estimated labor breakdown at 8,760
hours/year and the adjusted total labor requirement for operation at 5,000 hours/year are
shown in table 6.
Tables
Estimated Labor Requirements
for Dry Limestone Injection Process
Estimated annual operating labor requirement,
man-hrs. at 8,760 hours operation/year
Limestone
throughput,
tons(dry)/hour
0-25
25-50
50-75
75-100
Heavy equipment
operator
(unloading)
2,080
2,080
2,080
2,080
Conveying,
feeding
and disposal
2,080
4,160
6,240
8,760
Plant
operation
8,760
8,760
8,760
8,760
Super-
vision
400
500
600
700
Adjusted total
operating labor
required man hours
at 5,000 hours
Total operation/year
13,320
15,500
17,680
20,300
10,070
11,720
13,370
15,350
Based on 1972 TVA labor rates (13), a composite operating rate of $6.00/hr
including overhead and supervisory expense is utilized for the evaluation. For the 52-case
study, labor costs are not escalated over the life of the project. However, the effect of
escalation at rates up to 10%/year is presented in Section II.
5. Maintenance - Solids drying and grinding usually are maintenance prone
operations. Although actual operating data over an extended period of time is the best
source of information for defining maintenance requirements, insufficient data was
generated during the Shawnee program to accurately define these costs. Maintenance costs
chargeable to the process are, therefore, estimates based on actual recorded data. For
purposes of this study, precipitator maintenance is estimated as two percent of the
precipitator fixed capital investment for 5,000 hours annual operation. A slightly higher
maintenance charge ranging from 3.1 - 3.5% is projected for the combined drying grinding,
injection, and solids disposal facilities. Specific areas which were maintenance prone, such as
the hydroveyors in the sluice system, were recognized in arriving at these figures.
Maintenance costs usually increase over the life of a project; however, in the case of
a power plant related system where on-stream time declines over the remaining life,
estimating maintenance as a percentage of investment for a given on-stream time will
probably suffice. Estimates for other on-stream times are scaled exponentially according to
on-stream ratio using a 0.6 scaling exponent. Using this method, the maintenance per unit
time increases over the project life as on-stream time decreases.
6. Overhead - Overheads are usually a complex function of plant and company size,
and product research and marketing staff, and are likely to vary slightly from installation to
installation. However, for consistency in the cost projections, a common method for
-------
L-24
estimating overheads was established. In all of the cost projections plant overhead is
estimated as 20% of conversion costs, and administrative overhead is estimated as 10% of
operating labor. Although-costs may vary widely for an actual installation, these projections
are representative of the expected values.
7. Thermal effect of dry limestone injection - When limestone is injected into a
boiler, the required coal-firing rate for the power unit is adversely affected by the level of
injection stoichiometry for each sulfur content and must be adjusted to maintain the same
power generating capacity prior to dry limestone injection. Based on operating data for
Shawnee unit 10, a coal-firing rate of 0.780 Ibs/kWh prior to injection is assumed for each
power plant size considered. This firing rate is adjusted upward to compensate for the
thermal effect of dry limestone injection as discussed in Appendix H, Additional Heat
Requirement Calculations. Costs for the additional coal are estimated and displayed on the
annual operating cost projections as the thermal effect of dry limestone injection on
operating cost of power plant. This charge is equivalent to a coal cost of $6.00/ton and a
processing cost of $0.30/ton, including incremental costs for grinding and conveying.
8. Analyses - Purchased limestone and waste solids are the only materials which
require analyses in the dry limestone injection process. Since both of these materials are
proportional, projections of analyses requirements are estimated on the basis of limestone
throughput. Based on Shawnee experience, approximately 1 hour/day or 208 hours/year at
an annual on-stream time of 5,000 hours is required for analyses at a limestone throughput
of 20 tons/hour. Requirements for other limestone rates are proportional to the relative
limestone usage. A rate of $10.00/hour including overhead, supplies, and supervisory
expense is projected for laboratory work.
9. Working capital - For projection purposes, working capital for the dry limestone
injection process may be estimated as the equivalent cost of a four weeks supply of raw
material (limestone). Although the magnitude of the estimated working capital required for
5,000 hours annual operation varies from $2,600 for a 50 MW, 0.8% S coal, 3.0 injection
stoichiometry installation to $153,000 for a 350 MW, 5.0% S coal, 4.0 injection
stoichiometry installation, the effect on annual and lifetime operating costs at a cost of
money of 10% is relatively small.
Lifetime Operating Costs—Under regulated economics, annual operating costs vary
each year as the rate base declines due to depreciation "write-off" (the cost of money and
income taxes are applied to undepreciated portion of investment); in addition, any changes
in on-stream time of the power unit must be recognized. For any given case it is desirable,
therefore, to have a year-to-year tabulation of operating costs. Furthermore, recognizing the
time value of money, these annual operating costs should be discounted at the cost of
money (10% for this study) to the initial year of operation for ready comparison of present
worth to other pollution control means such as the annual costs required for low sulfur
fuels.
The total life of a coal-fired power unit is about 30 years (5). For the 52 case
parametric study, lifetime operating costs are based on 15 years remaining life of the power
plant after installation of the dry limestone injection process; however, the effect of various
-------
L-25
other remaining lives is also studied. Historically, the operating usage of most power plants
declines toward the end of their life. To reflect this experience, the following declining load
operating profile is assumed during the remaining years of operation.:
Annual operation,
(on-stream time)
Plant age, Plant remaining hours at full
years life, years generating capacity
16-20 15-11 5,000
21-25 10-6 3,500
26-30 5-1 1,500
Lifetime operating cost analyses are extremely valuable in evaluation of regulated
investments. They are an accumulation of each year's cost and, therefore, are more
representative of actual outlays for process operation.
Since rate of investment profitability is prescribed under regulated economics, the
data generated by the tabulation of lifetime operating costs indicates the total effect of
pollution abatement on the cost of power to the consumer. Actual and present worth
lifetime costs are, therefore, projected for each of the cases as overall measures of process
economics. In addition, equivalent lifetime unit operating costs expressed as $/ton coal
burned, mills/kWh, and $/ton sulfur removed are presented.
-------
L-27
II. Summary of Results and Conclusions
Results of the 52 Case Parametric Study
Investment—The estimated total fixed investment requirements for the dry
limestone injection process are summarized in table 7 for each of the 52 cases established.
Abbreviated investment estimates which show the major area investment costs are given in
tables A-l to A-52 of Appendix A in Process Economics Section. It should be mentioned
that the system used in these projections is one of minimum cost, and may not be
compatible to all potential users of the process. The estimated investment requirements
would be higher for power plants which require additional pond facilities for disposal of
solids, or for systems with other combinations of existing dust collection facilities. The
effect of these additional requirements is discussed later.
Table 7
Total Fixed Investment Requirements for Dry Limestone Injection Process
Applied to Existing Power Units Equipped with
Mechanical and Electrostatic Dust Collectors in Series
Sulfur
in coal
%
0.8
0.8
0.8
0.8
0.8
3.0
3.0
3.0
3.0
5.0
5.0
5.0
5.0
Injection stoichiometry,
moles CaO injected per
mole sulfur in coal
3.0
4.0
5.0
6.0
7.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
Total fixed
50 MW
$
751,500
834,500
908,300
975,000
1,036,300
817,100
1,070,500
1,271,500
1,442,000
995,300
1,332,900
1,602,600
1,838,700
units
$/kW
15.0
16.7
18.2
19.5
20.7
16.3
21.4
25.4
28.8
19.9
26.7
32.1
36.8
150 MW
$
1,280,100
1,431,500
1,568,800
1,694,400
1,808,000
1,404,600
1,874,200
2,251,400
2,574,200
1,736,200
2,369,500
2,926,600
3,376,200
units
$/kW
8.5
9.5
10.5
11.3
12.1
9.4
12.5
15.0
17.2
11.6
15.8
19.5
22.5
investment
250 MW
$
1,695,100
1,868,100
2,086,100
2,253,600
2,407,700
1,865,600
2,498,900
3,011,400
3,498,000
2,314,500
3,221,100
3,968,400
4,582,000
units
$/kW
6.8
7.5
8.3
9.0
9.6
7.5
10.0
12.0
14.0
9.3
12.9
15.9
18.3
350 MW
$
2,032,300
2,278,800
2,503,200
2,707,700
2,893,300
2,238,600
3,005,900
3,676,800
4,262,100
2,782,700
3,927,000
4,766,400
5,645,500
units
$/kW
5.8
6.5
7.2
7.7
8.3
6.4
8.6
10.5
12.2
8.0
11.2
13.6
16.1
a. Fixed investment includes cost of additional electrostatic precipitator for reducing dust emission to same level obtained
prior to installation of dry limestone injection process. Additional pond disposal area not included.
The total fixed investment for the dry limestone injection process ranges from
$751,500 ($15.0/kW) for a 50 MW - 0.8% S coal-fired unit with an injection stoichiometry
of 3.0 to $5,645,500 ($16.1/kW) for a 350 MW - 5.0% S coal-fired unit with an injection
stoichiometry of 4.0; however, unit investment costs vary from $5.8 to $36.8/kW depending
upon power unit size, sulfur in coal, and injection stoichiometry.
The effect of power unit size and injection stoichiometry on total dry limestone
process investment is shown in figures 8, 9, and 10 for the three variations in sulfur content
of coal. The relationship between sulfur content of coal and injection stoichiometry on total
fixed investment for a 150 MW power unit is presented in figure 11.
Relative investment cost distribution—The relative distribution of direct investment
costs for the three base cases is shown in table 8. As indicated, the limestone grinding
system and the incremental electrostatic precipitator system are the major investment items
for the process. Although the distribution of estimated costs varies somewhat for each of
-------
00
0
0
Power unit size, MW
Figure 8 . Effect of Power Unit Size and Injection Stoichiometry on Total Dry
Limestone Process Investment: 0.8% S Coal
-------
2
.
•d
C -3
O J
(0
X
1-1
-------
oo
o
0
100
150 200
Power unit size, MW
350
Figure 10
Effect of Power Unit Size and Injection Stolen!ometry on Total Dry
Limestone Process Investment: $.0% 3 Coal
-------
I
Existing units
(9
c
O
43
G
V
5
0)
I
•o.
0>
X
i—• i
OS 1
-P
0
I
26.67
20.00 g
to
I
13.33
•8
X
•H
-------
L-32
Table 8
Relative Distribution of Projected Direct Investment
Costs for Dry Limestone Injection Process
Relative investment distribution,
% of subtotal direct investment
Process area
General yard work
Limestone storage and feed
system
Limestone drying system
Limestone grinding system
Limestone injection system
Equipment foundations
Instrumentation
Piping
Electrical power supply
Revisions and additions to
powerhouse and boiler
Incremental electrostatic
precipitator system
Incremental solids disposal
system
Total direct investment
150MW-0.8%S
5.0 stoich.
1.3
4.7
7.7
15.1
9.9
3.9
3.7
7.1
6.2
8.5
22.8
9.1
150 MW-3.0%S
2.0 stoich.
1.3
5.5
8.0
16.5
9.8
4.1
3.4
7.3
6.2
8.7
21.6
7.6
150 MW - 5.0% S
2.0 stoich.
1.3
6.5
8.2
18.3
9.5
4.5
3.1
7.5
6.2
8.9
20.0
6.0
100.0
100.0
100.0
the 52 cases, these distributions indicate the relative contribution of each processing area to
the subtotal direct costs.
Annual operating cost—Based on an annual operation of 5,000 hours/year, projected
operating cost results of the 52-case parametric study are summarized in tables 9, 10, and 11
for each of the three levels of sulfur in coal. Detailed breakdowns of these projected annual
costs are presented in tables A-53 through A-104 of Appendix A.
Average annual operating costs range from $298,400 ($3.05/ton coal burned) for a
50 MW - 0.8% S coal-fired unit with an injection stoichiometry of 3.0 to $4,122,700
($5.85/ton coal burned) for a 350 MW 5.0% S coal-fired unit with an injection
stoichiometry of 4.0. Unit operating costs vary from $1.23 to $8.72/ton coal burned, or
from 0.48 to 3.51 mills/kWh. Operating costs per ton of sulfur removed decrease with
increasing power unit size and injection stoichiometry. These unit costs range from
$316/ton sulfur removed for a 350 MW - 5.0% S coal-fired unit with an injection
stoichiometry of 4.0 to $2,664/ton sulfur removed for a 50 MW - 0.8% S coal-fired unit
with an injection stoichiometry of 3.0.
Based on the results given in the tables, the effects of several variables on operating
costs are presented graphically.
-------
L-33
Table 9
Average Annual Operating Cost for Dry Limestone
Injection Process Under Regulated Economics
0.8% Sulfur Coal3
Power
unit
size, MW
50
50
50
50
50
150
150
150
150
150
250
250
250
250
250
350
350
350
350
350
Injection stoichiometry,
moles CaO injected per mole
sulfur in coal
3.0
4.0
5.0
6.0
7.0
3.0
4.0
5.0
6.0
7.0
3.0
4.0
5.0
6.0
7.0
3.0
4.0
5.0
6.0
7.0
Average
annual
cost, $
298,400
331,300
362,800
392,300
420,800
501,600
580,900
656,600
730,100
801,500
681,300
796,000
920,300
1,034,100
1,145,200
843,800
1,006,000
1,162,400
1,315,100
1,477,100
Unit
$/ton
coal
3.05
3.38
3.69
3.99
4.27
1.71
1.97
2.23
2.47
2.71
1.39
1.62
1.87
2.10
2.32
1.23
1.47
1.69
1.91
2.14
operating
mills
/kWh
1.19
1.33
1.45
1.57
1.68
0.67
0.78
0.88
0.97
1.07
0.55
0.64
0.74
0.83
0.92
0.48
0.58
0.66
0.75
0.84
cost
$/ton S
removal
2664
2301
1972
1816
1644
1529
1345
1207
1127
1054
1217
1106
998
958
895
1076
998
902
870
824
a. Existing units - 15 yrs. remaining life
5000 hrs. operation/yr
-------
L-34
Table 10
Average Annual Operating Cost for Dry Limestone
Injection Process Under Regulated Economics
3.0% Sulfur Coal3
Power
unit
size, MW
50
50
50
50
150
150
150
150
250
250
250
250
350
350
350
350
Injection stoichiometry,
moles CaO injected per mole
sulfur in coal
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
Average
annual
cost, $
323,100
435,100
536,400
631,700
561,800
835,200
1,091,400
1,337,300
773,100
1,197,800
1,612,100
2,018,100
965,900
1,547,400
2,120,500
2,667,100
Unit
$/ton
coal
3.30
4.42
5.42
6.36
1.91
2.83
3.68
4.48
1.58
2.43
3.26
4.06
1.41
2.25
3.06
3.83
operating
mills
/kWh
1.29
1.74
2.15
2.53
0.75
1.11
1.46
1.78
0.62
0.96
1.29
1.61
0.55
0.88
1.21
1.52
cost
$/ton S
removal
1188
800
651
576
695
512
443
406
568
440
391
368
507
406
368
348
a. Existing units - 15 yrs. remaining life
5000 hrs. operation/yr
-------
L-35
Table 11
Average Annual Operating Cost for Dry Limestone
Injection Process Under Regulated Economics
5.0% Sulfur Coal3
Power
unit
size, MW
50
50
50
50
150
150
150
150
250
250
250
250
350
350
350
350
Injection stoichiometry,
moles CaO injected per mole
sulfur in coal
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
Average
annual
cost, $
399,300
569,300
726,400
878,000
748,000
1,174,500
1,611,000
2,012,800
1,061,200
1,762,000
2,426,800
3,081,500
1,351,200
2,307,000
3,198,800
4,122,700
Unit
$/ton
coal
4.06
5.74
7.27
8.72
2.54
3.95
5.38
6.66
2.16
3.56
4.86
6.12
1.96
3.33
4.57
5.85
operating
mills
/kWh
1.60
2.28
2.91
3.51
1.00
1.57
2.15
2.68
0.85
1.41
1.94
2.47
0.77
1.32
1.83
2.36
cost
$/ton S
removal
876
624
525
471
550
429
389
360
465
386
351
331
412
361
330
316
a. Existing units - 15 yrs. remaining life
5000 hrs. operation/yr
-------
L-36
The effects of sulfur content of coal and injection stoichiometry on annual and unit
operating costs for a 150 MW installation are shown in figure 12. Figures 13, 14, and 15
indicate the relationship between power unit size, injection stoichiometry, and annual
operating costs for each of the three levels of sulfur. The effects of injection stoichiometry
and power unit size on unit operating cost expressed as both $/ton coal burned and
mills/kWh are indicated in figures 16 and 17 for 0.8 and 3.0% S coals. Although somewhat
higher costs are obtained, the relationship for 5.0% sulfur coal is similar. Unit operating
costs per ton of sulfur removed are shown in figures 18, 19, and 20 for each of the three
levels of sulfur in coal.
Relative operating cost distribution—The relative distribution of projected annual
operating costs for the three base cases at an annual on-stream time of 5,000 hours is shown
in table 12. As shown in the table, limestone cost and capital charges are the two most
prominent cost items. Although the relative cost distribution of each item changes
somewhat with variations in power unit size, sulfur content of fuel, and injection
stoichiometry, the other cost components are of minor importance in relation to the annual
costs for limestone and capital charges.
Lifetime operating cost—Based on the operating profile established for the 52 case
parametric study, lifetime operating costs were projected. Results of these projections are
summarized in tables 13, 14, and 15 for the three levels of sulfur in coal. Computer
print-outs which show the year-to-year operating costs corresponding to these lifetime
projections are presented in tables A-105 to A-156 of Appendix A. In addition to the actual
outlay annual values shown in these printouts, both actual and discounted overall total costs
and unit costs either per ton of coal burned or mills per kilowatt hour are presented.
Lifetime operating costs range from $3,909,400 (present worth = $2,223,900) fora
50 MW - 0.8% S coal-fired unit with an injection stoichiometry of 3:0 to $47,281,000
(present worth = $27,443,100) for a 350 MW - 5.0% S coal-fired unit with arrinjection
stoichiometry of 4.0. Lifetime unit operating costs are somewhat higher than average annual
operating costs due to the pronounced effect of the declining operating profile assumed for
the power plant.
The effect of power unit size and injection stoichiometry on (1) lifetime total
operating cost, (2) lifetime unit operating cost, $/ton coal burned and (3) lifetime unit
operating cost, $/ton sulfur removed, is shown in figures 21, 22, and 23, respectively, for a
0.8% S coal-fired installation. Both present worth and actual costs are indicated over the
complete range of injection stoichiometries utilized for the parametric study. Figures 24,
25, and 26 show similar relationships for a 3.0% S coal-fired installation with an injection
stoichiometry of 2.0. Relationships for a 5.0% S coal-fired installation with an injection
stoichiometry of 2.0 are shown in figures 27, 28, and 29.
-------
o>
O
•a
Ui
C
O
-p
(0
o
o
a
•H
-P
0)
Existing units
5QOO hrs annual operation
Regulated economics
2.0
1-5
1.0
0.5
0
o
6.76
1
5.07
3.38
1.69
-P
CO
O
o
I
-p
•H
a
Figure 12
23 ^5
Sulfur in coal, %
Effect of Sulfur Content of Coal and Injection Stoichiometry
on Annual and Unit Operating Cost of Dry Limestone
Process: 150 MW Units
2.67
2.00
1.33
0.67
(0
rH
.p
s
o
&0
g
o
•p
T-l
a
00
•vj
-------
Existing units
5000 hr. annual operation
Regulated economics
0
0
100 150 200
Power unit size, MW
r
CAJ
00
Figure
Effect of Power Unit Size and Injection Stoichiometry on Annual
Operating Coat of Dry Limestone Process: 0.8# S Coal
-------
w
r-t
O
TJ
-------
10
fH
43
I
•H
tn
o 2
o
H
I
I I
Existing units
5000 hr. annual operation
Regulated economics
0
Figure _1*
100
150 200
Power unit size, MW
Effect of Power Unit Size and Injection Stoichiometry on Annual
Operating Cost of Dry Limestone Process: 5.0% S Coal
-------
I I
Existing units
5000 hr annual operation
Regulated economics
\
n)
o
u
4J
o
o
0)
0.
o
I
350 tf* units
I
5.16
2.36
1.58
m
m
O
V
•H
0)
V
O
-u
0.79
34 5678
Stoichiometry, moles CaO injected per mole S in coal
Figure l£ . Effect of Injection Stoichiometry and Power Unit Size on
Unit Operating Cost of Dry Limestone Process: 0.8$ S Coal
-------
T
Existing units
5000 hr annual operation
Regulated economics
-a
8
O
O
§
4J
•OT-
4J
CO
O
U
v-4
J-l
n)
M
1
I
3.16
2.36
1.58
I
w
•u
oj
O
o
(90
c
co
o
-P
0.79
Figure
12345
Stoichiometry, moles CaO injected per mole S in coal
17 . Effect of Injection Stoichiometry and power Unit Size on
Unit Operating Cost of Dry Limestone Process: 3.0$ S Coal
-------
§ 2500
•3
to
2000
-P
CO
o
o
1
-p
S
I
1500
1000
500
0
Figure
I I
Existing units
5000 hrs annual operation
Regulated economics
u>
50
100 150 200
Power unit size, MW
250
300
350
Effect of Power Unit Size and Injection Stoichiometry on Dry Limestone
Process Operating Cost Per Ton of Sulfur Removed: 0.8$ S Coal
-------
§2000
CO
§1500
-^
•%
•p
8
o
glooo
•H
-p
g
•p
B 500
Existing units
5000 hrs annual operation
Regulated economics
1.0 Injection stoichiometry
0 50
100 150 200
Pover unit size, MW
250
300
350
Figure 19
Effect of Power Unit Size and Injection Stoichiometry on Dry Limestone
Process Operating Cost Per Ton of Sulfur Removed: 3.0$ S Coal
-------
I
1 800
DO
g
8
o
bO
C
2
(U
&
14-00
200
Existing units
5000 hrs annual operation
Regulated economies
en
0
Figure 20
100
150 200 250
Power Unit size, MW
300
350
Effect of Power Unit Size and Injection Stoichiometry on Dry Limestone
Process Operating Cost Per Ton of Sulfur Removed: 5.0$ S Coal
-------
L-46
Table 12
Relative Distribution of Projected Operating Costs
for Dry Limestone Injection Process
150 MW-0.8%S 150 MW - 3.0% S 150 MW - 5.0%
5-Ostoich. 2.0stoich. 2.0stoich.
DIRECT COSTS
Delivered raw material
Limestone 25.2 29.8 35.6
Conversion costs
Operating labor and
supervision 9.2 7.2 5.2
Utilities
Fuel oil
Sluice water
Electricity
Maintenance
Drying, grinding,
injection & solids
disposal area
Dust collection
Analyses
INDIRECT COSTS
Average capital charges
Overhead
Plant
Administrative
Thermal effect of dry limestone
injection on operating cost of
power plant
Total operating cost
3.6
1.2
3.4
6.1
1.1
0.2
42.1
4.9
0.9
2.1
100.0
4.3
1.0
3.8
5.8
1.0
0.2
39.5
4.6
0.7
2.1
100.0
5.1
0.7
4.5
5.2
0.8
0.1
35.5
4.3
0.5
2.5
100.0
-------
Table 13
Lifetime Operating Cost for Dry Limestone
Injection Process Under Regulated Economics
0.8% Sulfur Coal3
Lifetime operating cost
Cumulative present worth of net
increase in cost of power.
Power
unit
size, MW
50
50
50
50
50
150
150
150
150
150
250
250
250
250
250
350
350
350
350
350
Injection stoichiometry,
moles CaO injected per
mole sulfur in coal
3.0
4.0
5.0
6.0
7.0
3.0
4.0
5.0
6.0
7.0
3.0
4.0
5.0
6.0
7.0
3.0
4.0
5.0
6.0
7.0
(net increase
$
3,909,400
4,326,400
4,715,000
5,081,600
5,428,600
6,489,000
7,438,200
8,337,700
9,200,500
10,030,300
8,715,800
10,038,500
11,505,000
12,818,800
14,087,600
10,696,900
12,562,700
14,358,000
16,096,400
17,930,200
$/ton
coal
3.99
4.41
4.80
5.16
5.51
2.21
2.53
2.83
3.12
3.39
1.78
2.05
2.34
2.61
2.86
1.56
1.83
2.09
2.34
2.60
in cost of Power)
mills/kWh
1.56
1.73
1.89
2.03
2.17
0.87
0.99
1.11
1.23
1.34
0.70
0,80
0.92
1.03
1.13
0.61
0.72
0.82
0.92
1.02
$/ton
S removed
3491
3004
2563
2353
2121
1978
1722
1533
1420
1320
1556
1394
1251
1187
1101
1364
1246
1115
1065
1001
discounted at 10%/yr
$
2,223,900
2,464,300
2,689,400
2,901,100
3,102,100
3,712,400
4,262,400
4,784,000
5,284,900
5,766,600
4,999,800
5,768,300
6,619,100
7,382,400
8,120,000
6,146,600
7,230,600
8,274,100
9,285,400
10,347,900
$/ton
coal
2.27
2.51
2.74
2.95
3.15
1.26
1.45
1.62
1.79
1.95
1.02
1.18
1.35
1.50
1.65
0.90
1.05
1.20
1.35
1.50
mills/kWh
0.89
0.99
1.08
1.16
1.24
0.49
0.57
0.64
0.70
0.77
0.40
0.46
0.53
0.59
0.65
0.35
0.41
0.47
0.53
0.59
$/ton
S removed
1986
1711
1462
1343
1212
1132
987
879
816
759
893
801
719
684
634
784
717
642
614
577
a. Existing units - 15 yrs. remaining life. Assumed operating profile:
5 yr @ 5000 hr/yr
5 yr @ 3500 hr/yr
5yr @ 1500 hr/yr
-------
Table 14
Lifetime Operating Cost for Dry Limestone
Injection Process Under Regulated Economics
3.0% Sulfur Coal3
Lifetime operating cost
Cumulative present worth of net
increase in cost of power,
Power
unit
size, MW
50
50
50
50
150
150
150
150
250
250
250
250
350
350
350
350
Injection stoichiometry,
moles CaO injected per
mole sulfur in coal
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
(net
$
4,227,100
5,607,200
6,826,500
7,955,200
7,220,700
10,438,200
13,388,600
16,181,700
9,808,700
14,708,000
19,404,000
23,965,700
12,121,000
18,751,600
25,199,100
31,268,000
increase
$/ton
coal
4.31
5.70
6.90
8.00
2.46
3.53
4.51
5.43
2.00
2.99
3.92
4.82
1.77
2.72
3.64
4.49
in cost of Power)
mills/kWh
1.69
2.24
2.73
3.18
0.96
1.39
1.79
2.16
0.78
1.18
1.55
1.92
0.69
1.07
1.44
1.79
$/ton
S removed
1554
1031
828
726
894
640
543
491
721
541
471
437
637
492
437
408
discounted at 10%/yr
$
2,406,900
3,205,200
3,911,300
4,565,900
4,135,700
6,002,800
7,717,400
9,342,200
5,633,500
8,480,000
11,207,900
13,863,600
6,973,000
10,824,500
14,573,700
18,110,200
$/ton
coal
2.46
3.26
3.95
4.59
1.41
2.03
2.60
3.13
1.15
1.72
2.27
2.79
1.02
1.57
2.10
2.60
mills/kWh
0.96
1.28
1.56
1.83
0.55
0.80
1.03
1.25
0.45
0.68
0.90
1.11
0.40
0.62
0.83
1.03
$/ton
S removed
885
589
475
417
512
368
313
283
414
312
272
253
366
284
253
236
a. Existing units - 15 yrs. remaining life. Assumed operating profile: 5 yr @ 5000 hr/yr
5 yr @ 3500 hr/yr
5 yr @ 1500 hr/yr
-------
Table 15
Lifetime Operating Cost for Dry Limestone
Injection Process Under Regulated Economics
5.0% Sulfur Coal3
Lifetime operating cost
Cumulative present worth of net
increase in cost of power,
Power
unit
size, MW
50
50
50
50
150
150
150
150
250
250
250
250
350
350
350
350
Injection stoichiometry,
moles CaO injected per
mole sulfur in coal
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
(net
$
5,172,200
7,219,100
9,067,100
10,830,500
9,423,500
14,341,700
19,304,000
23,788,000
13,152,300
21,118,800
28,537,000
35,742,200
16,533,600
27,296,600
37,086,500
47,281,000
increase
$/ton
coal
5.26
7.28
9.08
10.76
3.20
4.82
6.44
7.87
2.68
4.26
5.71
7.10
2.40
3.94
5.30
6.71
in cost of Power)
mills/kWh
2.07
2.89
3.63
4.33
1.26
1.91
2.57
3.17
1.05
1.69
2.28
2.86
0.94
1.56
2.12
2.70
$/ton
S removed
1134
792
655
581
693
524
466
425
577
463
412
384
518
428
383
362
discounted at 10%/yr
$
2,953,500
4,139,200
5,211,300
6,235,100
5,413,800
8,271,800
11,153,800
13,765,400
7,575,100
12,204,500
16,526,400
20,723,500
9,538,500
15,799,300
21,504,200
27,443,100
$/ton
coal
3.00
4.18
5.22
6.19
1.84
2.78
3.72
4.56
1.54
2.46
3.31
4.12
1.39
2.28
3.08
3.89
mills/kWh
1.18
1.66
2.08
2.49
0.72
1.10
1.49
1.84
0.61
0.98
1.32
1.66
0.55
0.90
1.23
1.57
$/ton
S removed
648
454
377
335
398
302
269
246
332
268
239
222
305
247
222
210
(£>
a. Existing units - 15 yrs. remaining life. Assumed operating profile:
5 yr @ 5000 hr/yr
5 yr @ 3500 hr/yr
5yr @ 1500 hr/yr
-------
CO
h
at
O
•O
to
a
o
20
15
3 10
Pi
o
0
-P
5 —
Actual dollars
-— Present worth if discounted at 10$ to initial yr
Existing units - 15 yrs remaining life
Regulated economics
tn
o
Power unit size, MW
Figure 21 . Effect of Power Unit Size and Injection Stoichiometry on Lifetime
Increase in Cost of Power Using Dry Limestone Injection: 0.8$ S Coal
-------
c
I
r-l
8
O
C
o
•p
00
o
o
8
Actual dollars
-— Present worth if discounted at 10^6 to initial yr
Existing units - 15 yrs remaining life
Regulated economics
o
-p
•U
V
Injection Stoichiometry
01
100 150 200
Power unit size, MW
250
300
350
Figure 22
Effect of Power Unit Size and Injection Stoichiometry on Dry Limestone
Process Operating Cost Per Ton of Coal Burned Over Life of Plant:
0.8^ S Coal
-------
•o
0)
4>
h
4000
eg
C
O
(0
O
u
CD
M
&
O
5000
2000
1000
•P
Vi
•H
H3
Actual dollars
— Present worth if discounted at 10$ to initial yr
Existing units - 15 yrs remaining life
Regulated economics
3 Injection Stoichiometry
100
150
200
250
300
350
Power unit size, MW
Figure
Effect of Power Unit Size and Injection Stoichiometry on Dry Limestone
Process Operating Cost Per Ton of Sulfur Removed Over Life of Plant:
0.8# S Coal
-------
CO
20
HI I I
Actual dollars
--- Present worth if discounted at 10% to initial yr
Existing units - 15 yrs remaining life
Regulated economics
2.0 injection stoichiometry
e
o
•H
+3
(0
«J
0)
•H
4->
V
Vi
10
CJI
CO
100
150 200
Power unit size, MW
250
300
350
Figure
Effect of Power Unit Size and Injection Stoichiometry on Lifetime
Increase in Cost of Power Using Dry Limestone Injection: J.0# S Coal
-------
Actual dollars
8
a
o
v
c
o
•P
W
O
o
01
IH
•»
P.
O
§
0>
V
•rl
1-3
— Present worth if discounted at 10$ to initial yr
Existing units - 15 yrs remaining life
Regulated economics
2.0 injection stoichiotnetry
en
100
150
200
250
500
550
Power unit size, MW
Figure 25 • Effect of Power Unit Size and Injection Stoichiooetry on Dry Limestone
Process Operating Cost Per Ton of Coal Burned Over Life of Plant-
5.0# s Coal
-------
T
T
?
1
CO
c
O
-P
-P
0>
O
O
8P
•H
-p
2
O
J->
•H
C
-------
CO
to
A
<-4
O
•o
c
O
-p
ea
O
v
-U
«5
V.
&
O
V
4-4
I I I I
Actual dollars
--- Present worth if discounted at lO^t to initial yr
Existing units - 15 yrs remaining life
Regulated economics
2.0 injection stoichiometry
20
cr>
MW
Effect of Power Unit Size and Injection Stoichiometry on Lifetime
Increase in Cost of Power Using Dry Limestone Injection: 5.0$ S Coal
-------
4)
-4J
V
Actual dollars
Present worth if discounted at 10# to initial yr
Existing units - 15 yrs remaining life
Regulated economics
2.0 injection stoichiometry
Figure
150 200
Power unit size, MW
Effect of Power Unit Size and Injection Stoichiometry on Dry Limestone
Process Operating Cost Per Ton of Coal Burned Over Life of Plant:
5.0$ S Coal
-------
o
e
-------
L-59
Results of Sensitivity Analyses
Sensitivities of the dry limestone injection process investment and operating costs to
variations in several of the major factors are discussed below.
1. Sootblowers—The effect of additional sootblower requirements on total fixed
capital investment for the three base case installations is shown in table 16. For these
projections, a total installed cost of $40,000 each including indirect costs was utilized.
These results indicate that total investment requirements are increased less than 10% with
installation of up to four additional sooblowers. Although total operating costs were not
established, capital charges account for an increase in annual operating costs of
approximately $7,000 for each.
2. Particle size of injected limestone—The dry grinding and classifying equipment at
Shawnee were designed and operated at various limestone size reduction capabilities so the
effect of particle size on SO2 removal could be determined. Two levels of grind, 80% - 400
mesh and 50% - 400 mesh, were given greatest attention. Although the Shawnee data was
limited and is not totally conclusive, directional results of these and other investigations
indicate that increased SO2 removal efficiencies are obtained with injection of finer ground
limestone. To determine the sensitivity of limestone particle size on process economics,
investment and operating cost data for three levels of grind at various throughput capacities
were established (2). Results shown in figure 30 indicate that the investment required for
grinding to 80% - 400 mesh is about 35-40% greater than that required for grinding to 80% -
200 mesh; however, the higher grinding capability increases total process investment
approximately 7-10%.
Operating cost results shown in figures 31 and 32 indicate that overall grinding costs
are approximately 25-30% higher for the fine grind facilities. The effect of higher levels of
grind on overall process costs is realtively small because grinding costs are^only 5-6% of the
total operating cost.
It should be noted that, based on the limited Shawnee data using stones of varying
hardness, grindability is not a significant cost factor.
3. Particulate removal alternatives—The particulate collection facilities on Shawnee
unit 10 consist of a 65% effective mechanical collector followed by a 90% effective
electrostatic precipitator. This system which has an overall fly ash collection efficiency of
97% was designed, installed, and placed into operation prior to installation of the dry
limestone injection process.
Additional solids collection capacity was not installed for the injection tests;
however, performance data with and without dry limestone injection were derived for
estimating incremental requirements and costs.
Although EPA has not promulgated particulate emission standards for existing
power units, many states and local governing bodies have. In many cases, particulate
removal efficiencies greater than 97% are required. For the lack of a better basis, it is
assumed that these regulations will require plants utilizing dry limestone injection to
maintain particulate emissions at a level equivalent to that obtained prior to installation of
-------
Table 16
Effect of Additional Sootblower Requirements
on Total Fixed Capital Investment:
150 MW Power Units
Power unit installation
No. of
additional
sootblowers
required
0
1
2
3
4
0.8 %S
Total
process
investment
1,568,800
1,608,800
1,648,800
1,688,800
1,728,800
- 5.0 stoichiometry
Sootblower cost
sensitivity, % of
total investment
0.0
2.5
4.9
7.1
9.3
3.0% S
Total
process
investment
1,874,200
1,914,200
1,954,200
1,994,200
2,034,200
- 2.0 stoichiometry
Sootblower cost
sensitivity, % of
total investment
0.0
2.1
4.1
6.0
7.9
5.0% S
Total
process
investment
2,369,500
2,409,500
2,449,500
2,489,500
2,529,500
- 2.0 stoichiometry
Sootblower cost
sensitivity, % of
total investment
0.0
1.7
3.3
4.8
6.3
-------
to
*4
0)
o
•o
05
CO
o
JS
4i
c
s
•H
00
O
EH
I
Existing units
800
600
400
200
10
Figure
15 20 25 30
Grinding capacity, tons/hour
Effect of Limestone Grinding Capacity and Fineness of Grind
on Total Grinding System Investment: Dry Limestone Injection
Process
-------
Existing units. • 15 yrs remaining life
Regulated economics
5000 hrs/yr operation
£ 250
o
CD
as
to
-P
CO
O
O
200
150
I
05 100
10
15 20 25
Grinding capacity, tons/hour
30
Figure
Effect of Limestone Grinding Capacity and Fineness of Grind
on Annual Operating Cost for Grinding: Dry Limestone
Injection Process
-------
Existing units - 15 yrs remaining life
Regulated economics
5000 hrs/yr operation
0)
c
o
4J
«0
c
o 3
-u
to
o
o
*
•H
•H
to
•P
a>
oo
10
Figure
15 20 25 JO
Grinding capacity, tons/hour
Effect of Limestone Grinding Capacity and Fineness of Grind
on Unit Grinding Cost: Dry Limestone Injection Process
-------
L-64
the process. For consistency in the evaluation, a dust removal efficiency of 99% prior to
injection or an outlet grain emission of 0.03 gr/acf is assumed.
From their study of electrostatic precipitator performance during the Shawnee Dry
Limestone Injection test program, Cottrelt Environmental Systems, Inc.1 reported five
separate alternatives which may be considered for design of additional dust collection
facilities, including:
1. Size modification of the presently installed dust collecting system.
2. Installation of a "hot" precipitator.
3. Gas cooling ahead of the dust collecting system (in conjunction with size
modification).
4. Gas conditioning ahead of the dust collecting system (in conjunction with size
modification).
5. Electrical energization of the precipitator.
Based on their study, CES indicates that with gas cooling ahead of the dust collecting
system (alternative 3), the least additional precipitator plate area might be required. Their
results, however, do not include costs for gas cooling facilities, nor do they represent
carefully researched data needed for design modifications of such a system. Since design
requirements for the other alternatives are also speculative at this time, size modifications of
the presently installed dust collecting system (alternative 1) is considered the most practical
method for meeting additional dust removal requirements for existing power plants. The
Shawnee test data were used by Cottrell Environmental Systems, Inc., to estimate
incremental precipitator investment requirements based on increasing the precipitator plate
area for a 150 MW unit with any one of the following four combinations of dust collectors
prior to limestone injection:
Overall fly ash
collection efficiency
Dust collector type prior to injection, %
1. No collection devices 0
2. Mechanical collector 65
3. Electrostatic collector 99
4. Mechanical and electrostatic
collectors in series 99
1. Brown, R. F. "Report and Analysis of Field Tests at Shawnee Station of TV A,
Including a Techno-Economic Evaluation of Options for Maintaining the Stack Emission
Rate with Limestone Injection Equivalent to a Baseline of No Limestone Injection." Final
draft prepared by Cottrell Environmental Systems, Inc., for the Environmental Protection
Agency, Contract No. CPA 22-69-139, Particulates Collection Study, TVA Dry Limestone
Tests. October 31, 1972.
-------
L-65
Assuming a final outlet grain loading of 0.03 gr/acf after injection for each sulfur
content and stoichiometry, the estimated fixed investment requirements are tabulated in
table 17 and are shown graphically in figures 33 through 36 for the various combinations of
existing collection facilities. Depending on the dust removal capability existing prior to
injection, incremental dust collection investment could cover a wide range, as much as 2.4
times that projected in the case study (mechanical and electrostatic in series). Assuming no
collection devices existing prior to injection, total process investment could be
approximately 28% higher than estimated in the parametric evaluation.
4. Disposal costs—In the 52-case parametric study, additional pond facilities were
not provided since the availability and cost of additional space depends upon the actual
plant location. In many cases, some additional disposal area will be necessary, and these
additional investment costs should be added to the dry limestone injection process
investment.
Figure 37 shows the relationship between the incremental annual disposal burden
and the projected pond disposal costs incorporated in the parametric study. As this figure
indicates, the projected disposal expense decreases with increasing solids disposal burden to
a cost less than $0.50/ton of solids. For the three base cases, these costs range from 4.6 to
5.1% of the total process operating cost. As an indication of the effect of higher disposal
costs, a charge of $2.00/ton of solids would result in overall disposal costs ranging from 7 to
15% of the projected annual operating costs for these cases.
5. Raw material costs—Since limestone cost is one of the major operating expenses,
the sensitivity of price on annual operating cost was determined. Figure 38 shows the effect
of injection stoichiometry and delivered limestone price on the annual and unit operating
costs for a 150 MW, 3.0% S coal-fired installation. At a stoichiometry of 4.0, a $2.00 change
in the price of limestone results in a 20-30% change in annual costs.
The effect of power unit size and delivered limestone price on annual and unit
operating costs for the process are shown in figures 39 and 40.
-------
Table 1 7
Incremental Electrostatic Precipitator Invesetment3
Required to Maintain Outlet Particulate Loading of
0.03 gr/acf on 1 50 MW Power Units
Utilizing Dry Limestone Injection
Injection stoichiometry,
Sulfur in moles CaO injected per mole
coal,% sulfur in coal
0.8 3.0
0.8 4.0
0.8 5.0
0.8 6.0
0.8 7.0
None
763
778
794
808
824
Incremental electrostatic precipitator costs,
thousands of dollars, for power units equipped with
the following existing dust collection facilities3
99% Eff.
Mechancial and
electrostatic collectors
in series
65% Eff.
Mechanical
collector
582
601
619
635
648
99% Eff.
Electrostatic
collector
408
423
439
453
469
321
339
358
373
386
cr>
CTi
3.0
3.0
3.0
3.0
5.0
5.0
5.0
5.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
790
843
886
924
831
905
967
1021
606
666
716
753
653
734
797
852
435
488
531
569
476
550
612
666
345
405
454
491
392
473
535
591
a. Including indirects
b. Assumes coal with 16% ash
-------
1.2
to
§
•1-1
.8
CO
a)
>
•So. 6
"8
0.4
T
T
150 MW units
Fly ash loading:^. 23 gr/acf
Outlet loading after dust collection - O.05 gr/acf
CTl
02468
Stoichiometry, moles CaO injected per mole S in coal
Figure 33 . Investment Requirements for Adding Incremental
Electrostatic Precipitator to Power Plant without
Collectors: Dry Limestone Injection Process
-------
1.0
•§ 0.8
o
en
O
•H
iH
i-l
ll 0.6
•S 0.4
-------
0.8
en
M
rt
*gO,6
w
o
.0.4
CO
!
•gO. 2
x
T
T
150 MW units
Ftyash loading - 3.23 gr/acf
Outlet loading after duet collection - O.OJ gr/acf
CD
IO
02468
Stoichiometry, moles CaO injected per mole S in coal
Figure 55 .
Investment Requirements for Adding Incremental
Electrostatic Precipitator to Power Plant Having
an Existing 99$ Effective Precipitator: Dry
Limestone Injection Process
-------
10
h
A
r-i
o
•o
w
8
c
0)
*i
10
I
T3
0>
0.8
I I I I
150 MH units
fly ash loadings 3.23 gr/acf
Outlet loading after dust collection - 0.03 gr/acf
0.6
0.2
-j
o
2 U 6 8
Stoichiometry, moles CaO injected per mole S in coal
Figure
Investment Requirements for Adding Incremental
Electrostatic Precipitator to Power Plant Having
an Existing 99$ Effective Combination of Mechanical
and Electrostatic Collectors: Dry Limestone Injection
Process
-------
600
T
T
T
T
r-l
o
•O
CO
•s
ol
m
3
CO
o
o
OS
CO
a
•J
•rt
•O
(O
•O
O
TO
§
c
Annual costs for solids disposal to pond
excluding cost of pond
Variable solids disposal costs
500
400
300
200
100
0
Figure
50 100 1-50 200 250
Incremental solids disposal burden, M tons/year
_. Effect of Incremental Solids Disposal Burden on Annual
Disposal Cost for Dry Limestone Injection Solids
300
-------
Existing 150 MW units
5000 hrs annual operation
Regulated economics
2.0
o
T>
W
e
o
CO
o
o
oo
Pi
» i.o
0)
CU
O
fl
.§0.5
2.67
-------
Existing units
2.0 injection stoichiometry
5000 hrs annual operation
Regulated economics
co
50
Figure 39 »
100
150 200
Power unit size, MW
250
300
350
Effect of Power Unit Size and Delivered Limestone Cost on Annual
Operating Cost for Dry Limestone Injection Process: 3.0$ S Coal
-------
•o
8
a
o
-p
-66-
-p
CO
O
D
00
a
•H
-p
2
5-0
3-0
B 2.0
1.0
Existing units
2.0 injection stoichiometry
5000 hrs annual operation
Regulated economics
0
Figure
100
150 200 250
Power unit size, MW
300
— 1.97
_ 1.58
CO
(0
O
o
1.18 Jf
-p
g
-------
L-75
6. Annual on-stream time—The effect of variations in process on-stream time on
annual operating costs are shown in figure 41 for three plant sizes at various sulfur levels of
fuel. As illustrated, the cost effect is much more pronounced for large plants using high
sulfur coal. Figure 42 shows the effect of on-stream time on unit operating costs per ton of
sulfur removed. These unit operating costs decrease with increased on-stream time and are
much higher for the low MW and low sulfur applications. This result is partially the effect of
greater economy of scale for operating the larger installations; however, the largest factor is
the reduced SO2 absorption efficiency attained for low sulfur coal.
7- Operation at half load—In the dry limestone injection test program, higher sulfur
dioxide removal efficiencies were observed during operation of the power unit at half load.
To determine the effect of these higher efficiencies on unit operating costs, projections are
made for a 150 MW unit operating at full and half load assuming various annual on-stream
hours. The resulting unit operating costs are shown in figures 43 and 44. Although
approximately 50% lower operating costs per ton of sulfur removed are projected at reduced
load, the costs per ton of coal burned are about the same. The operational costs at half load
do not include a charge for power generating capacity intentionally idled to increase
absorption which, if assessed, would make half-load operation more costly per unit of
electricity generated.
8. Remaining life of plant—figures 45 through 47 show the effect of remaining life
of the power plant on lifetime total and unit operating costs for various megawatt sizes.
Similar relationships indicating the effect of remaining life of power plant on lifetime total
and unit operating costs for various sulfur levels are given in figures 48 through 50.
Although total operating costs increase as a result of greater operation, these results
show that unit operating costs for power plants with 10 years remaining life are
approximately half of similar unit costs for plants with 5 years remaining life. This result is
attributed primarily to the increased annual capital charge rate resulting from operation for
fewer years plus the difference in tons of coal burned or sulfur removed.
9. Labor cost escalation—To determine the effect of escalating labor rates on
lifetime operating costs for dry limestone injection, projections assuming annual labor
escalation rates varying from 0 to 10.0%/year were made. The results, presented in table 18
and figure 51, show that lifetime operating costs for dry limestone injection are not greatly
increased as a result of labor cost escalation. Lifetime unit operating costs range from
$3.53/ton of coal burned assuming no escalation to $3.95/ton at an escalation rate of
10%/year for the remaining 15-year life of the plant. At the higher escalation rate, lifetime
costs are approximately 11.8% higher than projected costs excluding escalation.
-------
Table 18
Effect of Annual Labor Escalation Rates on Lifetime Operating Cost for
Dry Limestone Injection Process Under Regulated Economics -
1 50 MW Unit, 3.0% S in Coal, 2.0 Injection Stoichiometry a
Annual
labor
escalation
rate
%
0
2.5
5.0
7.5
10.0
Total increase
in lifetime Cumulative present worth of net
operating cost increase in cost of power
Lifetime operating cost resulting from discounted at 10%/yr
$
10,438,
10,669,
10,944,
11,275,
11,670,
200
100
700
500
700
$/ton
coal
3.53
3.61
3.71
3.82
3.95
mills/
kWh
2.03
2.06
2.10
2.15
2.20
$/ton S
removed
640
654
671
691
715
escalation,
%
_
2.2
4.9
8.0
11.8
$
6,002
6,097
6,206
6,335
6,484
,800
,300
,900
,300
,800
$/ton
coal
1.39
1.42
1.46
1.50
1.56
mills/
kWh
0.80
0.81
0.83
0.84
0.86
$/ton S
removed
368
374
380
388
397
-J
en
a. Existing units - 15 yrs. remaining life. Assumed operating profile:
5 yr at 5000 hr/yr
5 yr at 3500 hr/yr
5 yr at 1500 hr/yr
-------
a
h
A
r-i
o
•o
w
o
•u
w
o
u
-p
to
fn
V
P<
O
SJ
c
Existing units - 15 yrs remaining life
Regulated economics
2.0
1.5 —
1.0
0.5
50 MW
, 0.8* S, 3.0 stolen^
0
1000
2000 3000 UOOO
On-stream time, hrs
5000
Figure 41 . Effect of Annual On-Stream Time at Pull Load on Annual
Operating Cost for Various Size Dry Limestone Injection
Process Installations
-------
Existing units - 15 yrs remaining life
Regulated economics
8000
•o
I
v
w 6000
c
50 MW units, 0.8# S, J.O injection stoichiometry
m
O
o
bO
C
1*000
00
&
o
4J
•H
B
2000
0
0* S, 2.0 stoich
1000
2000 JOCK) UOOO
On-stream time, hrs
5000
Figure
Effect of Annual On-Stream Time at Full Load on Unit
Operating Cost Per Ton of Sulfur Removed for Various
Size Dry Limestone Injection Process Installations
-------
T
2000
§
Existing unit - 15 yrs remaining life
?.O=t S coal
2.0 injection stoichiometry
Regulated economics
CO
e
Q
«^
^
to
O
o
2
4)
&
1500
1000
500
1
150,000 300,000 450,000 600,000
Annual power generation, MW hours
750,000
Figure
Effect of Annual Power Generation at Full and Half Load
on Dry Limestone Process Unit Operating Cost Per Ton of
Sulfur Removed: 150 MW Unit
-------
•o
s
oj
8
C
O
-P
•w-
-P
CO
O
o
bo
c
o
4J
20
15
10
0
T
T
T
Existing unit - 15 yrs remaining life
3«0# S coal
2.0 injection stoichiometry
Regulated economics
full load
I
1
I
I
I
00
O
150,000 300,000 1^50,000 6oo>ooo
Annual power generation, MW hours
750,000
Figure
Effect of Annual Power Generation at Full and Half Load
on Dry Limestone Process Unit Operating Cost Per Ton of
Coal Burned: 150 MW Unit
-------
CO
(•4
20 —
o
•o
CO
c
o
15 —
-p
CO
o
u
g»10
g
P4
o
0)
5
-p
o>
Actual dollars
— Present worth if discounted at
Existing units
Regulated economics
2.0 injection stoichiometry
to initial yr
0
00
Figure
150 200
Power unit size, MW
Effect of Power Unit Size and Years Remaining Life on Lifetime Increase
in Cost of Power Using Dry Limestone Injection: 3«°# S Coal
-------
I
§
,0
0)
o
o
c
o
09
O
V
•rl
•P
0)
h
I
§
V
a
4J
0)
4-1
•H
20
10
I I I I
Actual dollars
Present worth if discounted at 10# to initial yr
Existing units
Regulated economics
2.0 injection stoichiometry
oo
ho
Figure
Power unit size, MW
Effect of Power Unit Size and Years Remaining Life on Dry Limestone
Process Operating Cost Per Ton of Coal Burned Over Life of Plant:
3.0% S Coal
-------
I
4000
1 1 1
Actual dollars
Present worth if discounted at 10% to initial yr
Existing units
Regulated economics
2.0 injection stoichiometry
3
w
C
o
-p
-p
TO
8
I
§
V
3000
2000
1000
0
00
CO
100
150
200
250
300
550
Figure
Power unit size, MW
Effect of Power Unit Size and Years Remaining Life on Dry Limestone
Process Operating Cost Per Ton of Sulfur Removed Over Life of Plant:
3.0* S Coal
-------
CO
20
O
•O
V.
O
01
O
a
•*
43
to
8
g
Q>
10
0
Actual dollars
Present worth if discounted at 10$ to initial yr
Existing units
Regulated economics
J.O injection stoichiometry
5 —
00
-is.
Figure
Sulfur in coal, %
Effect of Sulfur Content of Coal and Years Remaining Life
on Lifetime Increase in Cost of Power Using Dry
Limestone Injection: 150 MW Units
-------
-g
a
20
-- Actual dollars
— Present worth if discounted at
Existing units
Regulated economics
3-0 injection stoichiometry
to initial yr
a
o
-W-
4J
CO
O
o
•H
-P
0)
Vi
o
+>
•H
a
43
0)
-------
•o
s
8000
Actual dollars
Present worth if discounted at 10^ to initial yr
Existing units
Regulated economics
3-0 injection stoichiometry
C
O
-p
ID
O
U
0$
-------
•8
c
Vl
I 5.0
B
£ 2.0
V
CM
•H
<
1.0
1 1 II 1
<• "" Actual dollars
.. >. M. present worth if discounted at 10$ to initial yr
__ Existing unit - 15 yrs remaining life
3.0# S coal
2.0 injection stoichiometry
Regulated economics
_ _r>^. _
^ ^^
^ •—pg*— """^ *^J
ri ^^"""^
"
r ^
— . —
f\ _ ._ „ _/~\«« — « — •— ""Q"~ "~ ~" ^™ "^ ^^^^
rM. M> «M* «•» L/*~ ™" VJ ^
1 I 1 I 1
1.9T JH
^
ra
r-l
r-l
e
1.58 i
o
V
bO
c
0)
1.18 o
^
§
0)
•H
•••^
0.79 ?
^
0.1Q
0 2.0
Figure 51
k.O
6.0
8.0
10.0
Annual labor escalation rate,
Effect of Escalating Labor Rate on Dry Limestone Process
Operating Cost Per Ton of Coal Burned and Per Kilowatt-hour
of Electricity Produced Over Life of Plant: 150 MW Unit
00
-------
L-88
References and Abstracts
1. Atchison, J. L. (The Babcock and Wilcox Company). Private communication to Robert
L. Torstrick, May 19, 197-2, giving the contract price breakdown of the dry limestone
injection process equipment supplied to TVA.
2. Brown, C. B., Jr. (Koppers Company, Inc.). Private communication to William H.
Kennedy. May 23, 1972, giving up-to-date price data on rotary dryers and grinding mills
for processing limestone prior to injection into a boiler.
3. Brown, R. F. (Cottrell Environmental Systems, Inc.). Private communications to Robert
L. Torstrick, June 30 and July 6, 1972, giving incremental electrostatic precipitator
investment and electricity requirements applicable for installing and operating
precipitators on power units utilizing the dry limestone injection process.
4. "Economic Indicators." Chemical Engineering 79(21), September 18, 1972.
C. E. Plant Cost Index data was used for obtaining a projected 1972 annual index.
This projected index was compared with the annual index for 1969, and used in
updating the Shawnee 1969 investment costs.
5. Federal Power Commission. Hydroelectric Power Evaluation. FPCP-35 (1968) and
Supplement No. 1, FPC P-38 (1969). Superintendent of Documents, U.S. Government
Printing Office, Washington, D.C. 20402.
This publication is a guide for the evaluation of the hydroelectric power aspects of
water resource developments. Included is information concerning investment and
operating costs of hydroelectric and thermal-electric power plants and transmission
facilities, methods for economic analysis of projects, and methods for presenting the
annual costs associated with power generation and transmission under regulated
economics.
6. Guthrie, K. M. "Capital Cost Estimating." Chemical Engineering 76(6), March 24, 1969.
Data and techniques for preliminary capital cost estimating are presented along with
a compilation of costs for a large variety of plant equipment. A "module" technique for
making fast, accurate, and consistent estimates is introduced. Especially useful for this
study are the equipment scale factors given in the data.
7. "Industry Statistics." Oil and Gas Journal 70(37), September 11, 1972.
Published data giving refined-products prices was used to obtain the price for
distillate kerosine (No. 2 fuel oil) for use in projecting 1972 operating costs for the dry
limestone injection process.
8. The M. W. Kellogg Company. Availability of Limestones and Dolomites. Task No. 1
Final Report, MWKLG-RED-72-1265, Submitted to Environmental Protection Agency,
Contract No. CPA 706-8, February 1, 1972.
Several processes which remove sulfur oxides from power plant stack gas are based
on the use of limestone or dolomite as the absorbent. The objective of this study was to
determine the availability and costs of limestone and similar materials throughout the
contiguous United States to supplement experimental work.
Materials covered in this study include limestone, dolomite, chalk, marble, marl, and
shell. Information is presented on location of deposits, production rates, f.o.b. quarry
-------
L-89
costs, transportation methods and costs, expected cost increases, uses, chemical
composition, and physical properties.
9. Perry. John H., Chilton, Cecil H.p and Kirkpatrick, Sidney D. Chemical Engineers'
Handbook. Fourth Edition, McGraw-Hill Book Co., New York, 1963.
"Six-tenths factor" method for scaling equipment costs as a function of capacity is
presented along with a set of typical exponents for use with various types of equipment.
10. Peters, Max S. and Timmerhaus, Klaus D. Plant Design and Economics for Chemical
Engineers. Second Edition, McGraw-Hill Book Co., New York, 1968.
Economic and design principles, as applied in chemical engineering processes and
operations are discussed. The first part of the text presents an overall analysis of the
major factors involved in process design, with particular emphasis on economics in the
process industries and in design work. The various costs involved in industrial processes,
capital investments and investment returns, cost estimation, cost accounting, optimum
economic design methods, and other subjects dealing with economics are covered both
qualitatively and quantitatively. The remainder of the book deals with methods and
important factors in the design of plants and equipment. Generalized subjects, such as
waste disposal, structural design, and equipment fabrication, are included along with
design methods for different types of process equipment. Basic cost data and cost
correlations are also presented for use in making cost estimates.
11. Purcell, Robert W. (The Taulman Company). Private communication to W. H. Kennedy,
June 28, 1972, describing design of sluice systems for disposal of waste solids.
12. Tennessee Valley Authority. Sulfur Oxide Removal from Power Plant Stack Gas:
Sorption by Limestone or Lime—Dry Procesi, - (1968). Report No. PB 178-972,
Clearinghouse for Scientific and Technical Information, 5285 Port Royal Road,
Springfield, Virginia 22151.
Injection of dry limestone or lime into the boiler is considered the simplest and least
costly process for removing SO2 from power plant stack gases. Product is calcium
sulfate which is discarded. The process can be operated intermittently. A detailed
economic evaluation is presented.
13. Tennessee Valley Authority. "Wage Schedules." Office Service Branch, Administrative
Releases (Memorandum No. 1321), August 1, 1972.
TVA wage schedules effective during 1972 are given for chemical and power plant
operators and laborers.
-------
L-91
_TableA-l Summary of Estimated Fixed Investment-Dry Limestone Injection Process
(50-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
1.55 Tons Dry Limestone per Hour)
I nvestment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 6,300
Limestone storage and feed system including hoppers, unloaders, and
conveyors 14,400
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 38,400
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 58,800
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 57,600
Equipment foundations for all areas 16,300
Instrumentation for all areas including panel and shed 27,100
Piping for all areas 35,100
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 33,300
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 42,000
Incremental electrostatic precipitator system0 89,000
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 518,300
Engineering design and overheads 46,600
Construction expense 72,600
Contractors fees 46,600
Contingency 67,400
Total fixed capital investment 751,500
Basis:
aMidwest location—1972 costs.
bO" x iy2" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-92
Table A-2 Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(50-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
2.07 Tons Dry Limestone per Hour)
I nvestment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 7,200
Limestone storage and feed system including hoppers, unloaders, and
conveyors 18,200
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 44,300
Limestone grinding system13 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 71,200
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 64,700
Equipment foundations for all areas 19,400
Instrumentation for all areas including panel and shed 29,200
Piping for all areas 40,600
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 38,000
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 48,500
Incremental electrostatic precipitator system0 94,200
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 575,500
Engineering design and overheads 51,800
Construction expense 80,600
Contractors fees 51,800
Contingency 74,800
Total fixed capital investment 834,500
Basis:
fMidwest location-1972 costs.
"0" x IVa" limestone ground to 80% minus 400 mesh.
"incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed t& be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-93
Table A-3 Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(50-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
5.0 Moles CaO Injected per Mole S in Fuel;
2.59 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 8,100
Limestone storage and feed system including hoppers, unloaders, and
conveyors 21,800
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 49,700
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 82,000
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 70,800
Equipment foundations for all areas 22,200
Instrumentation for all areas including panel and shed 30,800
Piping for all areas 45,500
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 41,900
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 54,300
Incremental electrostatic precipitator system0 99,300
Incremental solids disposal systerrrfor collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 626,400
Engineering design and overheads 56,400
Construction expense 87,700
Contractors fees 56,400
Contingency 81,400
Total fixed capital investment 908,300
Basis:
^Midwest location-1972 costs.
bO" x IV-i" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-94
Table A-^ Summary of Estimated Fixed Investment3—Dry Limestone Injection Process
(50-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
6.0 Moles CaO Injected per Mole S in Fuel;
3.11 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 8,900
Limestone storage and feed system including hoppers, unloaders, and
conveyors 25,100
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 54,400
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 92,500
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 76,200
Equipment foundations for all areas 24,700
Instrumentation for all areas including panel and shed 32,200
Piping for all areas 49,800
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 45,500
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 59,500
Incremental electrostatic precipitator system0 103,600
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 672,400
Engineering design and overheads 60,500
Construction expense 94,100
Contractors fees 60,500
Contingency 87,400
Total fixed capital investment 974,900
Basis:
aMidwest location-1972 costs.
°0" x IVi" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-95
_TableA-5 Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(50-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
7.0 Moles CaO Injected per Mole S in Fuel;
3.63 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 9,600
Limestone storage and feed system including hoppers, unloaders, and
conveyors 28,400
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 58,800
Limestone grinding system0 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 102,100
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 81,000
Equipment foundations for all areas 27,200
Instrumentation for all areas including panel and shed 33,500
Piping for all areas 53,800
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 48,900
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 64,300
Incremental electrostatic precipitator system0 107,200
Incremental solids disposal system"for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 714,800
Engineering design and overheads 64,300
Construction expense 100,000
Contractors fees 64,300
Contingency 92,900
Total fixed capital investment ___^_ 1,036,300
Basis:
fMidwest location-1972 costs.
"0" x I'A" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-96
Table A-6 Summary of Estimated Fixed In vestment3-Dry Limestone Injection Process
(150-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
4.64 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 10,800
Limestone storage and feed system including hoppers, unloaders, and
conveyors 34,600
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 66,300
Limestone grinding systemb including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 119,800
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 89,200
Equipment foundations for all areas 31,400
Instrumentation for all areas including panel and shed 35,600
Piping for all areas 60,700
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 54,500
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 72,600
Incremental electrostatic precipitator system0 226,000
Incremental solids disposal system^ for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 901,500
Engineering design and overheads 72,100
Construction expense 117,200
Contractors fees 72,100
Contingency ] 17,200
Total fixed capital investment 1,280,100
Basis:
^Midwest location-1972 costs.
bO" x W" limestone pound to 80% minus 400 mesh.
""Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-97
Table A-7 Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(150-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
6.20 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 12,500
Limestone storage and feed system including hoppers, unloaders, and
conveyors 43,600
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 76,600
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 144,500
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 100,200
Equipment foundations for all areas 37,400
Instrumentation for all areas including panel and shed 38,300
Piping for all areas 70,200
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 62,000
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 83,800
Incremental electrostatic precipitator system0 239,000
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,008,100
Engineering design and overheads 80,600
Construction expense 131,100
Contractors fees 80,600
Contingency 131,100
Total fixed capital investment 1,431,500
Basis:
aMidwest location-1972 costs.
°0" x I1// limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-98
Table A-8 Summary of Estimated Fixed Investment8-Dry Limestone Injection Process
(150-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
5.0 Moles CaO Injected per Mole S in Fuel;
7.76 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 14,000
Limestone storage and feed system including hoppers, unloaders, and
conveyors 52,100
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 85,700
Limestone grinding system13 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 167,100
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 109,600
Equipment foundations for all areas 42,800
Instrumentation for all areas including panel and shed 40,500
Piping for all areas 78,500
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 68,700
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 93,800
Incremental electrostatic precipitator system0 252,000
Incremental solids disposal system^ for collecting and sluicing
limestone solids to pond 100,000
Su btota I d i rect i nvestmen t 1,104,800
Engineering design and overheads 88,400
Construction expense 143,600
Contractors fees 88,400
Contingency 143,600
_jrota|. fixed capital investment 1,568,800
Basis:
fMidwesHocation-1972 costs.
bO" x IVi" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-99
_Tabje A-9 Summary of Estimated Fixed Investment8-Dry Limestone Injection Process
(150-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
6.0 Moles CaO Injected per Mole S in Fuel;
9.33 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 15,300
Limestone storage and feed system including hoppers, unloaders, and
conveyors 60,400
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 94,000
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 188,800
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 118,000
Equipment foundations for all areas 47,800
Instrumentation for all areas including panel and shed 42,500
Piping for all areas 86,000
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 74,600
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 102,800
Incremental electrostatic precipitator system0 263,000
Incremental solids disposal system^ for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,193,200
Engineering design and overheads 95,500
Construction expense 155,100
Contractors fees 95,500
Contingency 155,100
Total fixed capital investment 1,694,400
Basis:
^Midwest location-1972 costs.
°0" x VA" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-100
Table A-lOSummary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(150-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
7.0 Moles CaO Injected per Mole S in Fuel;
10.90 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 16,600
Limestone storage and feed system including hoppers, unloaders, and
conveyors 68,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 101,600
Limestone grinding system*3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 208,600
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 125,500
Equipment foundations for all areas 52,400
Instrumentation for all areas including panel and shed 44,100
Piping for all areas 93,000
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 80,000
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 111,100
Incremental electrostatic precipitator system0 272,000
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,273,200
Engineering design and overheads 101,900
Construction expense 165,500
Contractors fees 101,900
Contingency 165,500
Total fixed capital investment 1,808,000
Basis:
aMidwest location-1972 costs.
bO" x iy-2." limestone ground to 80% minus 400 mesh.
clnciemental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-101
_Table A-llSummary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(250-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
7.73 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 14,000
Limestone storage and feed system including hoppers, unloaders, and
conveyors 52,000
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 85,600
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 167,100
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 109,500
Equipment foundations for all areas 42,700
Instrumentation for all areas including panel and shed 40,500
Piping for all areas 78,300
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 68,500
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 93,600
Incremental electrostatic precipitator system0 350,300
Incremental solids disposal system^for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,202,100
Engineering design and overheads 96,200
Construction expense 144,300
Contractors fees 96,200
Contingency 156,300
Total fixed capital investment 1,695,100
^Midwest location-1972 costs.
bO" x 1V4" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-102
Table A-12Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(250-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
10.33 Tons Dry Limestone per Hour)
lnvestment,$
General yard work including landscaping, lighting, grading, raw water
piping and drains 16,100
Limestone storage and feed system including hoppers, unloaders, and
conveyors 65,600
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 99,000
Limestone grinding system13 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 179,500
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 123,000
Equipment foundations for all areas 50,800
Instrumentation for all areas including panel and shed 43,500
Piping for al I areas 90,600
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 78,100
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 108,200
Incremental electrostatic precipitator system0 370,500
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,324,900
Engineering design and overheads 106,000
Construction expense 159,000
Contractors fees 106,000
Contingency 172,200
Total fixed capital investment 1,868,100
Basis:
^Midwest location-1972 costs.
bO" x IVi" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-103
__TableA-13Summary of Estimated Fixed Investment9- Dry Limestone Injection Process
(250-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
5.0 Moles CaO Injected per Mole S in Fuel;
12.93 Tons Dry Limestone per Hour)
I nvestment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 18,100
Limestone storage and feed system including hoppers, unloaders, and
conveyors 78,600
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 110,800
Limestone grinding system0 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 233,400
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 134,600
Equipment foundations for all areas 58,200
Instrumentation for all areas including panel and shed 46,100
Piping for all areas 101,400
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 86,500
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 121,200
Incremental electrostatic precipitator system0 390,600
Incremental solids disposal system^ for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,479,500
Engineering design and overheads 118,400
Construction expense 177,500
Contractors fees 118,400
Contingency 192,300
Total fixed capital investment 2,086,100
Basis:
^Midwest location-1972 costs.
bO" x IVz" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
dSolids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-104
TableA-1^ Summary of Estimated Fixed Investment3—Dry Limestone Injection Process
(250-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
6.0 Moles CaO Injected per Mole S in Fuel;
15.55 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 19,800
Limestone storage and feed system including hoppers, unloaders, and
conveyors 90,900
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 121,400
Limestone grinding systemb including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 262,800
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 144,700
Equipment foundations for all areas 64,900
Instrumentation for all areas including panel and shed 48,200
Piping for all areas 111,100
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 93,900
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 132,800
Incremental electrostatic precipitator system0 407,700
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,598,200
Engineering design and overheads 127,900
Construction expense 191,800
Contractors fees 127,900
Contingency 207,800
Total fixed capital investment 2,253,600
Basis:
aMidwest location-1972 costs.
°0" x 1V4" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission late
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
.mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-105
JTableA-15 Summary of Estimated Fixed lnvestmenta-Dry Limestone Injection Process
(250-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
7.0 Moles CaO Injected per Mole S in Fuel;
18.17 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 21,400
Limestone storage and feed system including hoppers, unloaders, and
conveyors 103,000
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 131,100
Limestone grinding systemb including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 290,900
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 154,100
Equipment foundations for all areas 71,200
Instrumentation for all areas including panel and shed 50,100
Piping for all areas 120,000
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 100,700
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 143,500
Incremental electrostatic precipitator system0 421,600
Incremental solids disposal systemdfor collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,707,600
Engineering design and overheads 136,600
Construction expense 204,900
Contractors fees 136,600
Contingency 222,000
Total fixed capital investment 2,407,700
Basis:
"Midwest location-1972 costs.
°0" x IVz" limestone ground to 80% minus 400 mesh.
clnciemental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-106
TableA-16Summary of Estimated Fixed Investment3—Dry Limestone Injection Process
(350-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
3.0'Moles CaO Injected per Mole S in Fuel;
10.83 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 16,500
Limestone storage and feed system including hoppers, unloaders, and
conveyors 68,100
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 101,300
Limestone grinding systemb including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 208,000
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 125,300
Equipment foundations for all areas 52,200
Instrumentation for all areas including panel and shed 44,100
Piping for all areas 92,700
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 79,800
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 110,800
Incremental electrostatic precipitator system0 463,300
Incremental solids disposal systemdfor collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,462,100
Engineering design and overheads 102,300
Construction expense 175,500
Contractors fees 102,300
Contingency 190,100
Total fixed capital investment 2,032,300
Basis: ~~~~~
fMidwest location-1972 costs.
"0" x I1// limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-107
TableA-17Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(350-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
14.47 Tons Dry Limestone per Hour)
I nvestment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 19,100
Limestone storage and feed system including hoppers, unloaders, and
conveyors 85,800
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 117,100
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 251,000
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 140,700
Equipment foundations for all areas 62,200
Instrumentation for all areas including panel and shed 47,300
Piping for all areas 107,200
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 90,900
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 128,100
Incremental electrostatic precipitator system0 490,000
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,639,400
Engineering design and overheads 114,800
Construction expense 196,700
Contractors fees 114,800
Contingency 213,100
Total fixed capital investment 2,278,800
Basis:
fMidwest location-1972 costs.
"0" x 1V4" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-108
Table A-l8Siimmary of Estimated Fixed Investment3—Dry Limestone Injection Process
(350-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
5.0 Moles CaO Injected per Mole S in Fuel;
18.11 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 21,400
Limestone storage and feed system including hoppers, unloaders, and
conveyors 102,700
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 131,000
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 290,300
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 153,800
Equipment foundations for all areas 71,100
Instrumentation for all areas including panel and shed 50,100
Piping for all areas 119,900
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 100,600
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 143,300
Incremental electrostatic precipitator system0 516,600
Incremental solids disposal system0'for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,800,800
Engineering design and overheads 126,100
Construction expense 216,100
Co ntracto rs fees 126,100
Contingency 234,100
Total fixed capital investment 2,503,200
Basis:
aMidwest location-1972 costs.
bO" x VA" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-109
TableA-igSummary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(350-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
6.0 Moles CaO Injected per Mole S in Fuel;
21.77 TonsTDry Limestone per Hour)
Investment^
General yard work including landscaping, lighting, grading, raw water
piping and drains 23,400
Limestone storage and feed system including hoppers, unloaders, and
conveyors 119,000
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 143,700
Limestone grinding systemb including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 327,200
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 165,700
Equipment foundations for all areas 79,400
Instrumentation for all areas including panel and shed 52,500
Piping for all areas 131,500
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 109,200
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 157,100
Incremental electrostatic precipitator system0 539,200
Incremental solids disposal system0'for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,947,900
Engineering design and overheads 136,400
Construction expense 233,700
Contractors fees 136,400
Contingency 253,300
Total fixed capital investment 2,707,700
Basis:
^Midwest location-1972 costs.
bO" x 1%" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-110
TableA-20Summary of Estimated Fixed Investment3—Dry Limestone Injection Process
(350-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
7.0 Moles CaO Injected per Mole S in Fuel;
25.43 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 25,300
Limestone storage and feed system including hoppers, unloaders, and
conveyors 134,700
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 155,200
Limestone grinding system13 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 361,800
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 176,200
Equipment foundations for all areas 87,200
Instrumentation for all areas including panel and shed 54,500
Piping for all areas 142,100
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 117,100
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 169,800
Incremental electrostatic precipitator system0 557,600
Incremental solids disposal system0'for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 2,081,500
Engineering design and overheads 145,700
Construction expense 249,800
Contractors fees 145,700
Contingency 270,600
Total fixed capital investment 2,893,300
Basis:
^Midwest location-1972 costs.
bO" x 1%" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-lll
TableA-21 Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(50-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
1.0 Moles CaO Injected per MoleS in Fuel;
1.93 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 7,000
Limestone storage and feed system including hoppers, unloaders, and
conveyors 17,200
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 42,800
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 67,800
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 62,900
Equipment foundations for all areas 18,600
Instrumentation for all areas including panel and shed 28,700
Piping for all areas 39,200
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 36,800
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 46,800
Incremental electrostatic precipitator system0 95,700
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 563,500
Engineering design and overheads 50,700
Construction expense 78,900
Contractors fees 50,700
Contingency 73,300
Total fixed capital investment 817,100
Basis:
^Midwest location-1972 costs.
bO" x 1%" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitatoi added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-112
TableA-22Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(50-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
2.0 Moles-CaO Injected per Mole S in Fuel;
3.89 Tons Dry Limestone per Hour)
Investment,!)?
General yard work including landscaping, lighting, grading, raw water
piping and drains 9,900
Limestone storage and feed system including hoppers, unloaders, and
conveyors 30,000
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 60,800
Limestone grinding system^ including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 107,100
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 83,200
Equipment foundations for all areas 28,300
Instrumentation for all areas including panel and shed 34,100
Piping for all areas 55,700
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 50,400
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 66,500
Incremental electrostatic precipitator system0 112,300
Incremental solids disposal system1^ for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 738,300
Engineering design and overheads 66,400
Construction expense 103,400
Contractors fees 66,400
Contingency 96,000
Total fixed capital investment 1,070,500
Basis:
aMidwest location-1972 costs.
"0" x 1%" limestone ground to 80% minus 400 mesh.
""Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-113
_TableA-23Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(50-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
5.87 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 12,200
Limestone storage and feed system including hoppers, unloaders, and
conveyors 41,800
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 74,600
Limestone grinding system*5 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 139,600
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 98,100
Equipment foundations for all areas 36,200
Instrumentation for all areas including panel and shed 37,800
Piping for all areas 68,300
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 60,600
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 81,600
Incremental electrostatic precipitator system0 126,100
Incremental solids disposal system^for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 876,900
Engineering design and overheads 78,900
Construction expense 122,800
Contractors fees 78,900
Contingency 114,000
Total fixed capital investment 1,271,500
Basis:
aMidwest location-1972 costs.
bO" x 1%" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection oflimestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-114
TableA-2^Summary of Estimated Fixed investment3—Dry Limestone Injection Process
(50-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
7.86 Tons Dry Limestone per Hour)
lnvestment,$
General yard work including landscaping, lighting, grading, raw water
piping and drains 14,100
Limestone storage and feed system including hoppers, unloaders, and
conveyors 52,700
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 86,300
Limestone grinding system13 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 168,700
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 110,100
Equipment foundations for all areas 43,100
Instrumentation for all areas including panel and shed 40,700
Piping for all areas 79,000
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 69,100
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 94,400
Incremental electrostatic precipitator system0 136,300
Incremental solids disposal system0'for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 994,500
Engineering design and overheads 89,500
Construction expense 139,200
Contractors fees 89,500
Contingency 129,300
Total fixed capital investment 1,442,000
Basis: ~
aMidwest location-1972 costs.
bO" x 1%" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
dSolids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-115
TableA-25Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(150-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
1.0 Moles CaO Injected per Mole S in Fuel;
5.80 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 12,100
Limestone storage and feed system including hoppers, unloaders, and
conveyors 41,200
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 74,200
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 138,400
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 97,500
Equipment foundations for all areas 35,900
Instrumentation for all areas including panel and shed 37,700
Piping for all areas 67,900
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 60,200
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 81,100
Incremental electrostatic precipitator system0 243,000
Incremental solids disposal system^for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 989,200
Engineering design and overheads 79,100
Construction expense 128,600
Contractors fees 79,100
Contingency 128,600
Total fixed capital investment 1,404,600
Basis:
^Midwest location-1972 costs.
bO" x 1%" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-116
TabieA-26Summary of Estimated Fixed Investment8—Dry Limestone Injection Process
(150-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
2.0 Moles CaO Injected per Mole S in Fuel;
11.67 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 17..100
Limestone storage and feed system including hoppers, unloaders, and
conveyors 72,200
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 105,100
Limestone grinding systemb including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 218,200
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 129,000
Equipment foundations for all areas 54,600
Instrumentation for all areas including panel and shed 44,900
Piping for all areas 96,200
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 82,500
Revisions aand additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 115,000
Incremental electrostatic precipitator system0 285,000
Incremental solids disposal systemdfor collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,319,800
Engineering design and overheads 105,600
Construction expense 171,600
Contractors fees 105,600
Contingency 171,600
Total fixed capital investment 1,874,200
Basis:
aMidwest location-1972 costs.
bO" x 1V4" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-117
-gySummary of Estimated Fixed lnvestmenta~Dry Limestone Injection Process
(150-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
17.60 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 21,000
Limestone storage and feed system including hoppers, unloaders, and
conveyors 100,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 129,100
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 284,800
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 152,100
Equipment foundations for all areas 69,900
Instrumentation for all areas including panel and shed 49,800
Piping for all areas 118,200
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 99,200
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 141,200
Incremental electrostatic precipitator system0 320,000
Incremental solids disposal system^for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct Investment 1,585,600
Engineering design and overheads 126,800
Construction expense 206,100
Contractors fees 126,800
Contingency 206,100
Total fixed capital investment 2,251,400
Basis:
^Midwest location-1972 costs.
bO" x IVa" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-118
TableA-28Summary of Estimated Fixed In vestment3-Dry Limestone Injection Process
(150-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
23.59 Tons Dry Limestone per Hour)
I nvestment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 24,400
Limestone storage and feed system including hoppers, unloaders, and
conveyors 126,900
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 149,400
Limestone grinding systemb including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 344,800
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 171,000
Equipment foundations for all areas 83,300
Instrumentation for all areas including panel and shed 53,500
Piping for all areas 136,800
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 113,200
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 163,500
Incremental electrostatic precipitator system0 346,000
Incremental solids disposal system^for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,812,800
Engineering design and overheads 145,000
Construction expense 235,700
Contractors fees 145,000
Contingency 235,700
Total fixed capital investment 2,574,200
Basis:
aMidwest location-1972 costs.
°0" x 1V4" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
dSolids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-119
JTableA-ggSummary of Estimated Fixed lnvestmenta~Dry Limestone Injection Process
(250-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
1.0 Moles CaO I njected per Mole S in Fuel;
9.67 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 15,600
Limestone storage and feed system including hoppers, unloaders, and
conveyors 62,200
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 95,800
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 193,100
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 119,700
Equipment foundations for all areas 48,800
Instrumentation for all areas including panel and shed 42,800
Piping for all areas 87,700
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 75,800
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 104,800
Incremental electrostatic precipitator system0 376,700
Incremental solids disposal system0'for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,323,000
Engineering design and overheads 105,900
Construction expense 158,800
Contractors fees 105,900
Contingency 172,000
Total fixed capital investment 1,865,600
Basis:
^Midwest location-1972 costs.
bO" x I'/z" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-120
Table A-30Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(250-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
2.0 Moles CaO Injected per Mole S in Fuel;
19.45 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and ydrains 22,100
Limestone storage and feed system including hoppers, unloaders, and
conveyors 108,700
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 135,700
Limestone grinding systemb including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 303,900
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 158,300
Equipment foundations for all areas 74,200
Instrumentation for all areas including panel and shed 51,000
Piping for all areas 124,200
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 103,900
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 148,400
Incremental electrostatic precipitator system0 441,800
Incremental solids disposal system0'for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,772,200
Engineering design and overheads 141,800
Construction expense 212,700
Contractors fees 141,800
Contingency 230,400
Total fixed capital investment 2,498,900
Basis:
aMidwest location-197 2 costs.
°Q" x 1%" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-121
_TableA-31 Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(250-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
29.33 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 27,200
Limestone storage and feed system including hoppers, unloaders, and
conveyors 151,000
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 166,600
Limestone grinding system*3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 397,100
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 186,600
Equipment foundations for all areas 95,000
Instrumentation for all areas including panel and shed 56,500
Piping for all areas 152,500
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 124,900
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 182,300
Incremental electrostatic precipitator system0 496,000
Incremental solids disposal system0'for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 2,135,700
Engineering design and overheads 170,900
Construction expense 256,300
Contractors fees 170,900
Contingency 277,600
Total fixed capital investment 3,011,400
Basis:
^Midwest location-1972 costs.
bO" x IVz" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
.mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-122
TableA-32Summary of Estimated Fixed Investment3—Dry Limestone Injection Process
(250-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
39.32 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 31,500
Limestone storage and feed system including hoppers, unloaders, and
conveyors 190,800
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 192,900
Limestone grinding systemb including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 480,400
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 209,700
Equipment foundations for all areas 113,200
Instrumentation for all areas including panel and shed 60,800
Piping for all areas 176,600
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 142,600
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 211,000
Incremental electrostatic precipitator system0 536,300
Incremental solids disposal system^ for collecting and sluicing
limestone solids to pond 135,000
Subtotal ddirect investment 2,480,800
Engineering design and overheads 198,500
Construction expense 297,700
Contractors fees 198,500
Contingency 322,500
Total fixed capital investment 3,498,000
Basis:
aMidwest location-1972 costs.
°0" x I1// limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-123
_Tj^teA-33Summary of Estimated Fixed Irwejrtn^^^ Process
(350-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
1 .0 Moles CaO Injected per Mole S in Fuel;
13.53 Tons Dry Limestone per Hour)
I nvestment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 18,500
Limestone storage and feed system including hoppers, unloaders, and
conveyors 81,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 1 13,200
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 240,200
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 137,000
Equipment foundations for all areas 59,700
Instrumentation for all areas including panel and shed 46,600
Piping for all areas 103,700
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 88,200
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 123,900
Incremental electrostatic precipitator system0 498,200
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond _ 100,000
Subtotal direct investment 1,610,500
Engineering design and overheads 1 1 2,700
Construction expense 193,300
Contractors fees 1 1 2,700
Contingency 209,400
Total fixed capital investment ______________ 2,238,600
Basis:
^Midwest location -197 2 costs.
bO" x iy2" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-124
ummary of Estimated Fixed Investment3—Dry Limestone Injection Process
(350-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
2.0 Moles CaO Injected per Mole S in Fuel;
27.23 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 26,200
Limestone storage and feed system including hoppers, unloaders, and
conveyors 142,200
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 160,600
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 378,200
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 181,200
Equipment foundations for all areas 90,800
Instrumentation for all areas including panel and shed 55,500
Piping for all areas 147,000
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 120,800
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 175,700
Incremental electrostatic precipitator system0 584,300
Incremental solids disposal system^for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 2,162,500
Engineering design and overheads 151,400
Construction expense 259,500
Contractors fees 151,400
Contingency 281,100
^JTotalJixed capital investment ___ 3,005,900^
Basis:
^Midwest location-1972 costs.
bO" x IVi" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-125
Jjble A-35Summary of Estimated Fixed In vestment3-Dry Limestone Injection Process
(350-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
41.07 Tons Dry Limestone per Hour)
I nvestment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 32,100
Limestone storage and feed system including hoppers, unloaders, and
conveyors 197,700
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 197,200
Limestone grinding system0 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 494,300
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 213,500
Equipment foundations for all areas 116,200
Instrumentation for all areas including panel and shed 61,500
Piping for all areas 180,500
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 145,400
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 215,700
Incremental electrostatic precipitator system0 656,000
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond 135,000
Subtotal direct investment 2,645,100
Engineering design and overheads 185,200
Construction expense 317,400
Contractors fees 185,200
Contingency 343,900
Total fixed capital investment 3,676,800
Basis:
^Midwest location-1972 costs.
"0" x VA." limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-126
Table A-36Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(350-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
55.04 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 37,200
Limestone storage and feed system including hoppers, unloaders, and
conveyors 249,800
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 228,300
Limestone grinding systemb including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 597,700
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 239,900
Equipment foundations for all areas 138,500
Instrumentation for all areas including panel and shed 66,100
Piping for all areas 209,000
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 165,800
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 249,700
Incremental electrostatic precipitator system0 709,300
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond 175,000
Subtotal direct investment 3,066,300
Engineering design and overheads 214,600
Construction expense 368,000
Contractors fees 214,600
Contingency 398,600
Total fixed capital investment 4,262,100
Basis:
aMidwest location-1972 costs.
bO" x W limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-127
JablgA-37Summary of Estimated Fixed Investment9- Dry Limestone Injection Process
(50-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
1.0 Moles CaO Injected per Mole S in Fuel;
3.23 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 9,000
Limestone storage and feed system including hoppers, unloaders, and
conveyors 25,900
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 55,300
Limestone grinding systemb including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 94,700
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 77,300
Equipment foundations for all areas 25,400
Instrumentation for all areas including panel and shed 32,600
Piping for all areas 50,600
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 46,400
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 60,500
Incremental electrostatic precipitator system0 108,700
Incremental solids disposal system*^ for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 686,400
Engineering design and overheads 61,800
Construction expense 96,100
Contractors fees 61,800
Contingency 89,200
Total fixed capital investment 995,300
Basis:
^Midwest location-1972 costs.
bO" x I'/z" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-128
TableA-38Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(50-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
2.0 Moles CaO Injected per Mole S in Fuel;
6.53 Tons Dry Limestone per Hour)
lnvestment,$
General yard work including landscaping, lighting, grading, raw water
piping and drains 12,800
Limestone storage and feed system including hoppers, unloaders, and
conveyors 45,400
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 78,700
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 149,800
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 102,300
Equipment foundations for all areas 38,600
Instrumentation for all areas including panel and shed 38,800
Piping for all areas 72,000
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 63,600
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 86,100
Incremental electrostatic precipitator system0 131,200
Incremental solids disposal system01 for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 919,300
Engineering design and overheads 82,700
Construction expense 128,700
Contractors fees 82,700
Contingency 119,500
Total fixed capital investment 1,332,900
Basis:
aMidwest location—1972 costs.
"0" x W limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-129
JTableA-39 Summary of Estimated Fixed Investtnenta-Dry Limestone Injection Process
(50-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
9.89 Tons Dry Limestone per Hour)
I nvestment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 15,800
Limestone storage and feed system including hoppers, unloaders, and
conveyors 63,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 96,900
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 195,900
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 120,900
Equipment foundations for all areas 49,500
Instrumentation for all areas including panel and shed 43,100
Piping for all areas 88,700
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 76,600
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 106,000
Incremental electrostatic precipitator system0 148,500
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,105,200
Engineering design and overheads 99,500
Construction expense 154,700
Contractors fees 99,500
Contingency 143,700
Total fixed capital investment 1,602,600
Basis:
^Midwest location-1972 costs.
bO" x 1V4" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-130
TableA-UOSummary of Estimated Fixed Investmenta--Dry Limestone Injection Process
(50-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
13.33 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 18,300
Limestone storage and feed system including hoppers, unloaders, and
conveyors 80,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 112,400
Limestone grinding system*3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 238,000
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 136,100
Equipment foundations for all areas 59,200
Instrumentation for all areas including panel and shed 46,400
Pi ping for all areas 102,900
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 87,600
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 123,000
Incremental electrostatic precipitator system0 163,900
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,268,100
Engineering design and overheads 114,100
Construction expense 177,500
Contractors fees 114,100
Contingency 164,900
Total fixed capital investment 1,838,700
Basis:
aMidwest location-1972 costs.
bO" x \Vi" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
^Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-131
jfgbie A-^lSummary of Estimated Fixed lnvestmenta~Dry Limestone Injection Process
(150-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
1.0 Moles CaO Injected per Mole S in Fuel;
9.70 Tons Dry Limestone per Hour)
Investments
General yard work including landscaping, lighting, grading, raw water
piping and drains 15,600
Limestone storage and feed system including hoppers, unloaders, and
conveyors 62,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 95,800
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 193,400
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 119,900
Equipment foundations for all areas 48,300
Instrumentation for all areas including panel and shed 42,900
Piping for all areas 87,700
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 75,900
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 104,800
Incremental electrostatic precipitator system0 276,000
Incremental solids disposal system0'for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,222,600
Engineering design and overheads 97,800
Construction expense 159,000
Contractors fees 97,800
Contingency 159,000
Total fixed capital investment 1,736,200
Basis:
^Midwest location-1972 costs.
"0" x IVi" limestone ground to 80% minus 400 mesh.
clnciemental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-132
TableA-42Summary of Estimated Fixed Investmenta—Dry Limestone injection Process
(150-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
2.0 Moles CaO Injected per Mole S in Fuel;
19.59 Tons Dry Limestone per Hour)
I nvestment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 22,200
Limestone storage and feed system including hoppers, unloaders, and
conveyors 109,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 136,200
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 305,500
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 158,800
Equipment foundations for all areas 74,500
Instrumentation for all areas including panel and shed 51,100
Piping for all areas 124,700
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 104,200
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 149,000
Incremental electrostatic precipitator system0 333,000
Incremental solids disposal system0'for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,668,500
Engineering design and overheads 133,500
Construction expense 217,000
Contractors fees 133,500
Contingency 217,000
Total fixed capital investment 2,369,500
Basis:
aMidwest location-1972 costs.
"0" x VA" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-133
_TableA-^3Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(150-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
29.66 Tons Dry Limestone per Hour)
lnvestment,$
General yard work including landscaping, lighting, grading, raw water
piping and drains 27,300
Limestone storage and feed system including hoppers, unloaders, and
conveyors 152,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 167,600
Limestone grinding system'3 including feed bin, ball milt and classifier,
storage silo, conveyors and chutes, and dust collectors 399,900
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 187,400
Equipment foundations for all areas 95,600
Instrumentation for all areas including panel and shed 56,700
Piping for al I areas 153,400
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 125,500
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 183,300
Incremental electrostatic precipitator system0 377,000
Incremental solids disposal system^for collecting and sluicing
limestone solids to pond 135,000
Subtotal direct investment 2,061,000
Engineering design and overheads 164,900
Construction expense 267,900
Contractors fees 164,900
Contingency 267,900
Total fixed capital investment 2,926,600
Basis:
^Midwest location-1972 costs.
bO" x IVz" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-134
TableA-4^Summary of Estimated Fixed investment3—Dry Limestone Injection Process
(150-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
39.99 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 31,700
Limestone storage and feed system including hoppers, unloaders, and
conveyors 193,400
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 194,600
Limestone grinding systemb including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 485,600
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 211,300
Equipment foundations for all areas 114,400
Instrumentation for all areas including panel and shed 61,100
Piping for all areas 178,100
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 143,600
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 212,800
Incremental electrostatic precipitator system0 416,000
Incremental solids disposal systemdfor collecting and sluicing
limestone solids to pond 135,000
Subtotal direct investment 2,377,600
Engineering design and overheads 190,200
Construction expense 309,100
Contractors fees 190,200
Contingency 309,100
Total fixed capital investment 3,376,200
Basis:
"Midwest location-1972 costs.
bO" x IVz" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-135
_TableA-^5Summary of Estimated Fixed In vestment3-Dry Limestone Injection Process
(250-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
1.0 Moles CaO Injected per Mole S in Fuel;
16.17 Tons Dry Limestone per Hour)
Investment^
General yard work including landscaping, lighting, grading, raw water
piping and drains 20,200
Limestone storage and feed system including hoppers, unloaders, and
conveyors 93,800
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 123,700
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 269,600
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 147,100
Equipment foundations for all areas 66,500
Instrumentation for all areas including panel and shed 48,700
Piping for all areas 113,200
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 95,600
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 135,300
Incremental electrostatic precipitator system0 427,800
Incremental solids disposal system0'for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 1,641,500
Engineering design and overheads 131,300
Construction expense 197,000
Contractors fees 131,300
Contingency 213,400
Total fixed capital investment 2,314,500
Basis:
^Midwest location-1972 costs.
bO" x 1%" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-136
Table A-J46Summary of Estimated Fixed Investment9—Dry Limestone Injection Process
(250-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
2.0 Moles CaO Injected per Mole S in Fuel;
32.65 Tons Dry Limestone per Hour)
I nvestment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 28,700
Limestone storage and feed system including hoppers, unloaders, and
conveyors 164,400
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 175,900
Limestone grinding systemb including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 425,600
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 194,800
Equipment foundations for all areas 101,300
Instrumentation for all areas including panel and shed 58,000
Piping for all areas 161,000
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 131,100
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 192,400
Incremental electrostatic precipitator system0 516,200
Incremental solids disposal system^ for collecting and sluicing
limestone solids to pond 135,000
Subtotal direct investment 2,284,400
Engineering design and overheads 182,800
Construction expense 274,100
Contractors fees 182,800
Contingency 297,000
Total fixed capital investment 3,221,100
Basis:
"'Midwest location-1972 costs.
bO" x 1%" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-137
TableA-^TSummary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(250-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
49.43 Tons Dry Limestone per Hour)
I nvestment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 35,300
Limestone storage and feed system including hoppers, unloaders, and
conveyors 229,200
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 216,300
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 557,400
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 229,900
Equipment foundations for all areas 129,900
Instrumentation for all areas including panel and shed 64,400
Piping for all areas 198,000
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 158,000
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 236,600
Incremental electrostatic precipitator system0 584,400
Incremental solids disposal system0' for collecting and sluicing
limestone solids to pond 175,000
Subtotal direct investment 2,814,400
Engineering design and overheads 225,200
Construction expense 337,700
Contractors fees 225,200
Contingency 365,900
Total fixed capital investment 3,968,400
Basis:
fMidwest location-1972 costs.
°0" x IVz" limestone ground to 80% minus 400 mesh.
clnciemental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-138
TableA-1+8Summary of Estimated Fixed Investment3—Dry Limestone Injection Process
(250-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
66.65 Tons Dry Limestone per Hour)
lnvestment,$
General yard work including landscaping, lighting, grading, raw water
piping and drains 41,000
Limestone storage and feed system including hoppers, unloaders, and
conveyors 291,100
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 251,300
Limestone grinding systemb including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 676,900
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 259,100
Equipment foundations for all areas 155,400
Instrumentation for all areas including panel and shed 69,400
Piping for all areas 230,000
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 180,700
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 274,900
Incremental electrostatic precipitator system0 644,800
Incremental solids disposal system^ for collecting and sluicing
limestone solids to pond 175,000
Subtotal direct investment 3,249,600
Engineering design and overheads 260,000
Construction expense 390,000
Contractors fees 260,000
Contingency 422,400
Total fixed capital investment 4,582,000
Basis:
fMidwest location-1972 costs.
bO" x l!/2" limestone ground to 80% minus 400 mesh.
clnciemental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-139
-49Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(350-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
1.0 Moles CaO Injected per Mole S in Fuel;
22.63 Tons Dry Limestone per Hour)
Investment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 23,900
Limestone storage and feed system including hoppers, unloaders, and
conveyors 122,700
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 146,400
Limestone grinding system^ including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 335,500
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 168,200
Equipment foundations for all areas 81,300
Instrumentation for all areas including panel and shed 52,900
Piping for all areas 134,000
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 111,100
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 160,200
Incremental electrostatic precipitator system0 565,800
Incremental solids disposal system*^ for collecting and sluicing
limestone solids to pond 100,000
Subtotal direct investment 2,002,000
Engineering design and overheads 140,100
Construction expense 240,200
Contractors fees 140,100
Contingency 260,300
Total fixed capital investment 2,782,700
Basis:
^Midwest location-1972 costs.
bO" x IVi" limestone ground to 80% minus 400 mesh.
Incremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-140
TableA-^OSummary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(350-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
2.0 Moles CaO Injected per Mole S in Fuel;
45.71 Tons Dry Limestone per Hour)
Investment,^
General yard work including landscaping, lighting, grading, raw water
piping and drains 33,900
Limestone storage and feed system including hoppers, unloaders, and
conveyors 215,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 208,100
Limestone grinding system*3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 529,900
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 222,800
Equipment foundations for all areas 123,900
Instrumentation for all areas including panel and shed 63,200
Piping for all areas 190,500
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 152,500
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 227,600
Incremental electrostatic precipitator system0 682,700
Incremental solids disposal system^ for collecting and sluicing
limestone solids to pond 175,000
Subtotal direct investment 2,825,400
Engineering design and overheads 197,800
Construction expense 339,000
Contractors fees 197,800
Contingency 367,000
Total fixed capital investment 3,927,000
Basis:
aMidwest location-1972 costs.
bO" x 1V4" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-141
_TableA-5lSummary of Estimated Fixed Investmenta-Dry Limestone Injection Process
(350-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
69.21 Tons Dry Limestone per Hour)
I nvestment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 41,700
Limestone storage and feed system including hoppers, unloaders, and
conveyors 300,000
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 255,900
Limestone grinding system^ including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 693,600
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 263,000
Equipment foundations for all areas 158,900
Instrumentation for all areas including panel and shed 70,000
Piping for all areas 234,300
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 183,800
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 280,000
Incremental electrostatic precipitator system0 772,900
Incremental solids disposal system^for collecting and sluicing
limestone solids to pond 175,000
Subtotal direct investment 3,429,100
Engineering design and overheads 240,000
Construction expense 411,500
Contractors fees 240,000
Contingency 445,800
Total fixed capital investment 4,766,400
Basis:
''Midwest location-1972 costs.
°0" x IVi" limestone ground to 80% minus 400 mesh.
clnciemental electrostatic precipitator added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
"Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-142
TableA-52Summary of Estimated Fixed Investment3—Dry Limestone Injection Process
(350-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
93.31 Tons Dry Limestone per Hour)
I nvestment, $
General yard work including landscaping, lighting, grading, raw water
piping and drains 48,500
Limestone storage and feed system including hoppers, unloaders, and
conveyors 381,000
Limestone drying system including dryer, dust collectors, chutes and ducts,
bucket elevator, and dryer shed 297,200
Limestone grinding system'3 including feed bin, ball mill and classifier,
storage silo, conveyors and chutes, and dust collectors 842,500
Limestone injection system including transport pump, air compressors, feed
tank, conveyors, ducts and chutes, limestone distributor, piping and
injectors 296,400
Equipment foundations for all areas 190,100
Instrumentation for all areas including panel and shed 75,500
Piping for all areas 272,100
Electrical power supply including 4160 and 480 volt boards and conduit,
trays, groundings, and telephone 210,300
Revisions and additions to powerhouse and boiler including injection
ports, metal work, insulation and steam lines 325,100
Incremental electrostatic precipitator systemc 852,800
Incremental solids disposal system1^ for collecting and sluicing
limestone solids to pond 270,000
Subtotal direct investment 4,061,500
Engineering design and overheads 284,300
Construction expense 487,400
Contractors fees 284,300
Contingency 528,000
Total fixed capital investment 5,645,500
Basis:
aMidwest location-1972 costs.
bO" x I'/z" limestone ground to 80% minus 400 mesh.
clncremental electrostatic precipitatoi added to maintain dust emission rate
prior to injection of limestone. Dust collection efficiency prior to
injection of limestone is assumed to be 99% using a combination of
mechanical and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
1 mile from power unit. Cost of solids disposal pond not included.
-------
L-143
8,200 tons 4.05/ton
10,070 man-hr 6.00/man-hr
33,200
Table A-53-Average Annual Operating Cost for Reducing SO2 Emission
_fromjpwer Plants by Dry Limestone Injection-Regulated Power Company Economics3
(50-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
1.55 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilities^
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
43,500 gal
267,000 M gal
49,200 kWh
437,900 kWh
78,700 kWh
-58,800 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
50 hr
10.00/hr
60,400
4,800
8,000
300
3,100
600
(400)
3,600
19,900
2,600
500
103,400
136,600
Total
Cost/ton
of coal
burned,$
132,300
20,700
6.000
159,000
295,600
2,800
Total annual
cost, $
298,400
aBasis:
Coal burned-97,900 tons/yr; .784 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time—5000 hr/yr
Midwest plant location-1972 costs
O" x iy2" limestone ground to 80% minus 400 mesh
Capital investment, $751,500
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection ot limestone. Uust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
, Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-144
10,900 tons 4.05/ton
10,070 man-hr 6.00/man-hr
Table A-^h Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(50-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
2.07 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilities^
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
57,800 gal
267,000 M gal
65,400 kWh
582,100 kWh
104,600 kWh
-57,500 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
50 hr
10.00/hr
44.100
44,100
60,400
6,400
8,000
500
4,100
700
(400)
3,600
22,300
2,700
500
108,800
152,900
146,900
21,800
6,000
174,700
327,600
3,700
Total
Cost/ton
of coal
burned. $
Total annual
cost. $
3.38
331,300
aBasis:
Coal burned-98,100 tons/yr; .785 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
O" x \Vi limestone ground to 80% minus 400 mesh
Capital investment, $834,500
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
L-145
TableA-55Average Annual Operating Cost for Reducing SO2 Emission
_from Power Plants by Dry Limestone Injection-Regulated Power Company Economics8
(50-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
5.0 Moles CaO Injected per Mole S in Fuel;
2.59 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
13,700 tons 4.05/ton
55.500
55,500
Conversion costs
Operating labor & supervision
including payroll overhead
Utilities'^
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
10,070 man-hr 6.00/man-hr
72,600 gal
267,000 M gal
82,200 kWh
731,600kWh
131,500kWh
-56,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
60 hr
10.00/hr
Cost/ton
of coal
burned.$
60,400
8,000
8,000
600
5,100
900
(400)
3,600
24,300
2,900
600
114,000
169,500
159,600
22,800
6.000
188,700
358,200
4,600
Total annual
cost. $
3.69
362,800
aBasis:
Coal burned-98,200 tons/yr; .786 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
O" x I1// limestone ground to 80% minus 400 mesh
Capital investment, $908,300
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-146
TableA-56 Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
(50-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
6.0 Moles CaO Injected per Mole S in Fuel;
3.11 Tons Dry Limestone per Hour)
Total annual
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Annual quantity Unit cost, $ cost, $
16,400 tons 4.05/ton 66.400
66,400
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust col lection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
10,070 man-hr 6.00/man-hr
86,900 gal
267,000 M gal
98,400 kWh
875,800 kWh
157,400 kWh
-55,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
70 hr
10.00/hr
Cost/ton
of coal
burned.$
3.99
60,400
9,600
8,000
700
6,100
1,100
(400)
3,600
26,200
3,000
700
119,000
185,400
171,600
23,800
6,000
201,400
386,800
5,500
Total annual
cost. $
392,300
aBasis:
Coal burned-98,400 tons/yr; .787 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
O" x \Vi limestone ground to 80% minus 400 mesh
Capital investment, $974,900
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-147
19,100 tons 4.05/ton
10,070 man-hr 6.00/man-hr
Table A-57 Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(50-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
7.0 Moles CaO Injected per Mole S in Fuel;
3.63 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost. $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaCO3)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
101,200 gal
267,000 M gal
114,600 kWh
1,019,900 kWh
183,400 kWh
-53,800 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
80 hr
10.00/hr
77r400
77,400
60,400
11,100
8,000
800
7,100
1,300
(400)
3,600
28,000
3,100
800
123,800
201,200
Total
Cost/ton
of coal
burned,$
182,400
24,800
6.000
213,200
414,400
6,400
Total annual
cost, $
4.27
420,800
"Basis:
Coal burned-98,500 tons/yr; .788 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
O" x \W limestone ground to 80% minus 400 mesh
Capital investment, $1,036,300
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Uust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
. Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-148
24,400 tons 4.05/ton
10,070 man-hr 6.00/man-hr
TableA-58 Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company^Economics3
(150-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
4.64 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
129,300 gal
267,000 M gal
146,400 kWh
1,303,000 kWh
234,200 kWh
-176,500 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
90 hr
10.00/hr
98.800
98,800
60,400
14,200
8,000
1,000
9,100
1,600
(1,200)
3,600
32,100
6,300
900
136,000
234,800
225,300
27,200
6.000
258,500
493,300
8,300
Total
Cost/ton
of coal
burned.$
Total annual
cost.S
±.11
501.600
aBasis:
Coal burned-293,800 tons/yr; .784 Ibs/kWh
Remaining life of power plant-15 yi
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
O" x I'/z limestone ground to 80% minus 400 mesh
Capital investment, $1,280,100
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
L-149
Table A-59 Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(150-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
6.20 Tons Dry Limestone per Hour)
Total annual
. Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
32,700 tons 4.05/ton
132.400
132,400
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
10,070 man-hr 6.00/man-hr
173,300 gal
267,000 M gal
196,200 kWh
1,746,200 kWh
313,900 kWh
-173,500 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
100hr
10.00/hr
Cost/ton
of coal
burned.$
60,400
19,100
8,000
1,400
12,200
2,200
(1,200)
3,600
36,100
6,800
1,000
149,600
282,000
252,000
29,900
6.000
287,900
569,900
11,000
Total annual
cost. $
1.97
580.900
""Basis:
Coal burned-294,300 tons/yr; .785 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
O" x 1%" limestone ground to 80% minus 400 mesh
Capital investment, $1,431,500
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
. Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-150
Table A-60Average Annual Operating Cost for Reducing SO2 Emission
_fromJPgwer Plants by Dry Limestone Injection—Regulated Power Company Economics3
(150-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
5.0 Moles CaO Injected per Mole S in Fuel;
7.76 Tons Dry Limestone per Hour)
Total annual
. Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
40,900 tons 4.05/ton
165.600
165,600
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
10,070 man-hr 6.00/man-hr
216,800 gal
267,000 M gal
245,400 kWh
2,184,100kWh
392,600 kWh
-168,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
120hr
10.00/hr
Cost/ton
of coal
burned, $
60,400
23,800
8,000
1,700
15,300
2,700
(1,200)
3,600
39,900
7,200
1.200
162,600
328,200
276,100
32,500
6.000
314,600
642,800
13,800
Total annual
cost, $
2.23
656,600
aBasis:
Coal burned-294,700 tons/yr; .786 Ibs/kWh
Remaining life of power plant-15 yi
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
O" x IVi limestone ground to 80% minus 400 mesh
Capital investment, $1,568,800
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection to limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-151
Table A-6lAverage Annual Operating Cost for Reducing SO2
jromJPower Plants by Dry Limestone
Emission
^
(150-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
6.0 Moles CaO Injected per Mole S in Fuel;
9.33 Tons Dry Limestone per Hour)
Total annual
.__^^Q]Ja.!jayantity_ Uoitcpst^S cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
49,100 tons 4.05/ton
10,070 man-hr 6.00/man-hr
260,200 gal
267,000 M gal
294,600 kWh
2,621,900 kWh
471,400kWh
-165,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
130hr
10.00/hr
Total
Cost/ton
of coal
burned, $
2.47
198,900
198,900
60,400
28,600
8,000
2,100
18,400
3,300
(1,200)
3,600
43,300
7,500
1,300
175,300
374,200
298,200
35,100
__6,QOO
339,300
713,500
16,600
Total annual
730,100
aBasis:
Coalburned-295,100 tons/yr; .787 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
O" x 1%" limestone ground to 80% minus 400 mesh
Capital investment, $1,694,400
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection to limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
, Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-152
Table A-62Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
(150-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
7.0 Moles CaO Injected per Mole S in Fuel;
10.90 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unjt^gstJiL—__costt_$.
Direct Costs
Delivered raw material
Limestone (95%CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
aBasis:
57,400 tons 4.05/ton
10,070 man-hr 6.00/man-hr
304,200 gal
267,000 M gal
344,400 kWh
3,065,200 kWh
551,OOOkWh
161,500kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
150hr
10.00/hr
Cost/ton
of coal
burned.S
232,500
232,500
60,400
33,500
8,000
2,400
21,500
3,900
(1,100)
3,600
46,500
7,700
1,500
187,900
420,400
318,200
37,600
6,000
361,800
782,200
19,300
Total annual
cost. S
2.71
801,500
Coal burned-295,600 tons/yr; .788 Ibs/kWh
Remaining life of power plant-! 5 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
O" x 1V4" limestone ground to 80% minus 400 mesh
Capital investment, $1,808,000
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
BCost of utility supplied from power plant at full value.
-------
L-153
Table A-63Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection-Regulated Power Company Ecgnmrijcsg_
(250-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
7.73 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost,_$__
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilities'^
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Sol ids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
40,700 tons 4.05/ton
10,070 man-hr 6.00/man-hr
215,700 gal
267,000 M gal
244,200 kWh
2,173,400 kWh
390,700 kWh
-294,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
120hr
10.00/hr
Cost/ton
of coal
burned,$
164.800
164,800
60,400
23,700
8,000
1,700
15,200
2,700
(2,100)
3,600
41,000
9,900
1.200
165,300
330,100
298,300
33,100
6.000
337,400
667,500
13,800
Total annual
cost, $
1.39
681,300
Coal burned-489,700 tons/yr; .784 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x I'/z limestone ground to 80% minus 400 mesh
Capital investment, $1,695,100
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
, Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
L-154
TableA-6l4Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
(250-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
10.33'Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03}
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
54,400 tons
4.05/ton
10,070 man-hr 6.00/man-hr
288,300 gal
267,000 M gal
326,400 kWh
2,905,000 kWh
522,200 kWh
-287,500 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
140hr
10.00/hr
Cost/ton
of coal
burned. $
220,300
220,300
60,400
31,700
8,000
2,300
20,300
3,700
(2,000)
3,600
45,600
10,400
1.400
185,400
405,700
328,800
37,100
6.000
371,900
777,600
18,400
Total annual
cost, $
1.62
796,000
Coal burned-490,400 tons/yr; .785 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
MnJwestj>lantlocation-1972 costs
O" x IVi limestone ground to 80% minus 400 mesh
Capital investment, $1,868,100
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-155
TableA-65 Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection-Regulated Power Company Economicsa
(250-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
5.0 Moles CaO Injected per Mole S in Fuel;
12.93 Tons Dry Limestone per Hour)
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
_Annual quantity U_njt_cost. $
68,100 tons 4.05/ton
Total annual
cost, $
.275,800
275,800
10,070 man-hr 6.00/man-hr 60,400
360,900 gal
267,000 M gal
408,600 kWh
3,636,500 kWh
653,800 kWh
-280,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
160 hr
10.00/hr
Total
Cost/ton
of coal
burned, $
39,700
8,000
2,900
25,500
4,600
(2,000)
3,600
51,600
11,000
1,600
206,900
482,700
367,200
41,400
6.000
414,600
897,300
23,000
Total annual
cost, $
1.87
920,300
aBasis:
Coal burned-491,200 tons/yr; .786 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x 1%" limestone ground to 80% minus 400 mesh
Capital investment, $2,086,100
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
, Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-156
Table A-6£Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
(250-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
6.0 Moles CaO Injected per Mole S in Fuel;
15.55 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
81,900 tons 4.05/ton
331,700
"331,700
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
10,070 man-hr 6.00/man-hr
434,100 gal
267,000 M gal
491,400kWh
4,373,500 kWh
786,200 kWh
-275,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
180 hr
10.00/hr
Total
Cost/ton
of coal
burned.$
60,400
47,800
8,000
3,400
30,600
5,500
(1,900)
3,600
56,100
11,500
1,800
226,800
558,500
396,600
45,400
6.000
448,000
1,006,500
27,600
Total annual
cost. $
2.10
1,034,100
aBasis:
Coal burned-491,900 tons/yr; .787 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time—5000 hr/yr
Midwest plant location-1972 costs
0" x Wi' limestone ground to 80% minus 400 mesh
Capital investment, $2,253,600
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices. Solids disposed as 15% slurry with no recycle of pond
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
L-157
Table A-67Average Annual Operating Cost for Reducing SO2 Emission
_jrom Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(250-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
7.0 Moles CaO Injected per Mole S in Fuel;
18.17 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cosi, j>
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust col lection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
95,700 tons 4.05/ton
10,070 man-hr 6.00/man-hr
507,200 gal
267,000 M gal
574,200 kWh
5,110,400kWh
918,700 kWh
-269,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
200 hr
10.00/hr
387,600
"387,600
60,400
55,800
8,000
4,000
35,800
6,400
(1,900)
3,600
60,300
11,900
2.000
246,300
633,900
Cost/ton
of coal
burned,$
423,800
49,300
6.000
479,100
1,113,000
32,200
Total annual
cost. $
Total
2.32
1,145,200
"Basis:
Coal burned-492,600 tons/yr; .788 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yi
Midwest plant location-1972 costs
0" x 11A" limestone ground to 80% minus 400 mesh
Capital investment, $2,407,700 _
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection ot limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water
Disposal pond located 1 mile from power unit.
, Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-158
TableA-68 Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(350-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
10.83 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cpsj, $ jcost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
57,000 tons 4.05/ton
10,070 man-hr 6.00/man-hr
302,100 gal
267,000 M gal
342,000 kWh
3,043,800 kWh
547,200 kWh
-411,600kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
150hr
10.00/hr
Total
Cost/ton
of coal
burned.$
230,900
"230900
60,400
33,200
8,000
2,400
21,300
3,800
(2,900)
3,600
48,100
12,900
1,500
192,300
422,300
357,700
38,500
6.000
402,200
824,500
19,300
Total annual
cost. $
1.23
843,800
aBasis:
Coal burned-685,600 tons/yr; .784 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x \Vi" limestone ground to 80% minus 400 mesh
Capital investment, $2,032,300
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
L-159
Table A-69Average Annual Operating Cost for Reducing SO, Emission
Jrom Power Plants by Dry Limestone Injection-Regulated Power Company Economics8
(350-MW Existing Coal-Fired Power Unit; 0.8% S in fuel-
4.0 Moles CaO Injected per Mole S in Fuel;
14.47 Tons Dry Limestone per Hour)
Annual quantity Unit cost $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total annual
cost, $
76,200 tons 4.05/ton
10,070 man-hr 6.00/man-hr
403,900 gal
267,000 M gal
457,200 kWh
4,069,100 kWh
731,500kWh
-402,500 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
170hr
10.00/hr
Cost/ton
of coal
burned, $
308.600
308,600
60,400
44,400
8,000
3,200
28,500
5,100
(2,800)
3,600
54,800
13,600
1,700
220,500
529,100
401,100
44,100
6.000
451,200
980,300
25,700
Total annual
cost. $
Total
1.47
1,006,000
dBasis:
Coal burned-686,600 tons/yr; .785 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x VA" limestone ground to 80% minus 400 mesh
Capital investment, $2,278,800
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-160
Table A-70Average Annual Operating Cost for Reducing S02 Emission
Jrqm Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
(350-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
5.0 Moles CaO Injected per Mole S in Fuel;
18.11 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
95,300 tons 4.05/ton
386.000
386,000
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
I njection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
10,070 man-hr 6.00/man-hr
505,100 gal
267,000 M gal
571,800kWh
5,089,000 kWh
914,900 kWh
-392,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
200 hr
10.00/hr
Cost/ton
of coal
burned,$
1.69
60,400
55,600
8,000
4,000
35,600
6,400
(2,700)
3,600
60,700
14,400
2.000
248,000
634,000
440,600
49,600
6.000
496,200
1,130,200
32,200
Total annual
cost, $
1,162,400
aBasis:
Coal burned -687,600 tons/yr; .786 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x IVz limestone ground to 80% minus 400 mesh
Capital investment, $2,503,200
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
114,600 tons 4.05/ton
10,070 man-hr 6.00/man-hr
L-161
Table A-71 Average Annual Operating Cost for Reducing S02 Emission
__fromPower Plants by Dry Limestone Injection-Regulated Power Company Economics3
(350-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
6.0 Moles CaO Injected per Mole S in Fuel;
21.77 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost. $ cost. S
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
607,400 gal
267,000 M gal
687,600 kWh
6,119,600kWh
1,100,200 kWh
-385,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
220 hr
10.00/hr
464,100
464,100
60,400
66,800
8,000
4,800
42,800
7,700
(2,700)
3,600
66,200
15,000
2.200
274,800
738,900
476,600
55,000
6.000
537,600
1,276,500
38,600
Total
Cost/ton
of coal
burned. $
Total annual
cost, $
1.91
1,315,100
"Basis:
Coal burned-688,600 tons/yr; .787 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yi
Midwest plant location-1972 costs
0" x 1V4" limestone ground to 80% minus 400 mesh
Capital investment, $2,707,700
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
L-162
TableA-72 Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
(350-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
7.0 Moles CaO Injected per Mole S in Fuel;
25.43 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
I njection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
133,900 tons 4.05/ton
11,720 man-hr 6.00/man-hr
709,700 gal
267,000 M gal
803,400 kWh
7,150,300 kWh
1,285,400 kWh
-376,600 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
240 hr
10.00/hr
Cost/ton
of coal
burned.$
2.14
542.300
542,300
70,300
78,100
8,000
5,600
50,100
9,000
(2,600)
3,600
71,300
15,500
2.400
311,300
853,600
509,200
62,300
7,000
578,500
1,432,100
45,000
Total annual
cost, $
1,477,100
aBasis:
Coal burned-689,600 tons/yr; .788 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
O" x \V" limestone ground to 80% minus 400 mesh
Capital investment, $2,893,300
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone.
Dust collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
DCost of utility supplied from power plant at full value.
-------
L-163
Table A-73Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company Economics8
~ (50-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
1.0 Moles CaO Injected per Mole S in Fuel;
1.93 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
~~~"Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
10,200 tons 4.05/ton
41.300
41,300
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
10,070 man-hr 6.00/man-hr
54,100 gal
267,000 M gal
61,200kWh
544,700 kWh
97,000 kWh
-57,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
50 hr
10.00/hr
Total
"Basis:
Cost/ton
of coal
burned, $
60,400
6,000
8,000
400
3,800
700
(400)
3,600
21,700
2,800
500
107,500
148,800
143,800
21,500
6.000
171,300
320,100
3,000
Total annual
cost, $
3.30
323,100
Coal burned-98,000 tons/yr; .784 Ibs/kWh
Remaining life of power plant—15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x P/2 limestone ground to 80% minus 400 mesh
Capital investment, $817,100 . . . t. *!•„,,„,*„„„ n,,ct
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of l™«tane- Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
bCost of utility supplied from power plant at full value.
-------
L-164
Table A-T^Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(50-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
2.0 Mojes CaO Injected per Mole S in Fuel;
3.89 Tons Dry Limestone per Hour)
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
Annual quantity Unit cost. $
20,500 tons 4.05/ton
10,070 man-hr 6.00/man-hr
Total annual
cost, $
83.000
108,700 gal
267,000 M gal
123,000 kWh
1,094,700 kWh
196,800 kWh
-52,500 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
80 hr
10.00/hr
Cost/ton
of coal
burned.$
83,000
60,400
12,000
8,000
900
7,700
1,400
(400)
3,600
28,800
3,300
800
126,500
209,500
188,400
25,300
6,000
219,700
429,200
5,900
Total annual
cost,$
4.42
435,100
"Basis:
Coal burned-98,400 tons/yt; .788 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant locatkm-1972 costs
0" x W-i limestone ground to 80% minus 400 mesh
Capital investment, $1,070,500
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
L-165
Table A-7 5 Average Annual Operating Cost for Reducing S02 Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
(50-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
5.87 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
30,900 tons 4.05/ton
10,070 man-hr 6.00/man-hr
163,800 gal
267,000 M gal
185,400 kWh
1,650,100 kWh
296,600 kWh
-48,800 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
100hr
10.00/hr
Cost/ton
of coal
5.42
_125J_00
125,100'
60,400
18,000
8,000
1,300
11,600
2,100
(300)
3,600
34,400
3,700
1.000
143,800
268,900
223,800
28,800
6.000
258,600
527,500
8,900
Total annual
cost. $
536,400
"Basis:
Coal burned-98,900 tons/yr; .791 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x 1%" limestone ground to 80% minus 400 mesh
collection efficiency
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
°Cost of utility supplied from power plant at full value.
-------
41,400 tons 4.05/ton
10,070 man-hr 6.00/man-hr
L-166
Table A-76Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company Economics8
(50-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
7.86 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilities'^
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
219,400 gal
267,000 M gal
248,400 kWh
2,210,800 kWh
379,400 kWh
-46,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
120hr
10.00/hr
167,700
60,400
24,100
8,000
1,700
15,500
2,700
(300)
3,600
39,300
4,000
1.200
160,200
327,900
lolal
Cost/ton
of coal
burned,$
253,800
32,000
6.000
291,800
619,700
12,000
Total annual
cost, $
6.36
631 700
aBasis:
Coal burned-99,400 tons/yr; .795 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yt
Midwest plant location-197 2 costs
0" x IVz limestone ground to 80% minus 400 mesh
Capital investment, $1,442,000
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-167
Table A-77 Average Annual Operating Cost for Reducing S02 Emission
from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(150-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
1.0 Moles CaO I njected per Mole S in Fuel;
5.80 Tons Dry Limestone per Hour)
___ Annual quantity Unit cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Total annual
cost, $
30,600 tons 4.05/ton
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
123.900
123,900
10,070 man-hr 6.00/man-hr 60,400
162,200 gal
267,000 M gal
183,600 kWh
1,634,000 kWh
293,800 kWh
-171,OOOkWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
100hr
10.00/hr
Cost/ton
of coal
burned,$
17,800
8,000
1,300
11,400
2,100
(1,200)
3,600
35,200
6,900
1.000
146,500
270,400
247,200
29,300
6.000
282,500
552,900
8,900
Total annual
cost, $
1.91
561,800
Coal burned-293,900 tons/yr; .784 Ibs/kWh
Remaining life of power plant^-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x 1% limestone ground to 80% minus 400 mesh
Capital investment, $1,404,600
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full Value.
-------
L-170
Table A-80 Average Annual Operating Cost for Reducing S02 Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company Economics8
(150-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
23.59 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
124,200 tons 4.05/ton
503.000
503,000
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
10,070 man-hr 6.00/man-hr
658,300 gal
267,000 M gal
745,200 kWh
6,632,300 kWh
1,192,300 kWh
-138,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
230 hr
10.00/hr
Cost/ton
of coal
burned, $
60,400
72,400
8,000
5,200
46,400
8,300
(1,000)
3,600
67,400
9,800
2.300
282,800
785,800
453,100
56,600
6JQQO
515,700
1,301,500
35,800
Total annual
cost,$
4.48
1,337,300
aBasis:
Coal burned-298,200 tons/yr; .795 Ibs/kWh
Remaining life of power plant^lS yr
Power plant on-stream time-5000 hr/yt
Midwest plant location-1972 costs
0" x Wi" limestone ground to 80% minus 400 mesh
Capital investment, $2,574,200
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond Water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
L-171
Table A-SlAverage Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Inject ion-Regulated Power Company Economic^
(250-MW Existing Coal-Fired Power Unit; 3.0% S in fuel-
1.0 Moles CaO Injected per Mole S in Fuel;
9.67 Tons Dry Limestone per Hour)
Annual quantity Unit cost, $
Total annual
cost, $
Direct Costs
Delivered raw material
Limestone (95% CaCO3)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Sol ids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
50,900 tons 4.05/ton
10,070 man-hr 6.00/man-hr
269,800 gal
267,000 M gal
305,400 kWh
2,718,100 kWh
488,600 kWh
-285,000 kWh
514,000 kWh
.11/gal
.03/M gal
,007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
140hr
10.00/hr
Cost/ton
of coal
burned, $
206,100
60,400
29,700
8,000
2,100
19,000
3,400
(2,000)
3,600
45,400
10,600
1.400
181,600
387,700
328,300
36,300
6.000
370,600
758,300
14,800
Total annual
cost, $
1.58
773,100
aBasis:
Coal burned-489,900 tons/yr; .784 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest giant location-1972 costs
0" x 1% limestone ground to 80% minus 400 mesh
Capital investment, $1,865,600
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
L-174
Table A-8U Average Annual Operating Cost for Reducing S02 Emission
from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(250-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
39.32 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
207,000 tons 4.05/ton
838.400
838,400
Conversion costs
Operating labor & supervision
including payroll overhead
Utilities^
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
11,720 man-hr 6.00/man-hr
1,097,100 gal
390,000 M gal
1,242,000 kWh
11,053,800 kWh
1,987,200 kWh
-230,000 kWh
750,800 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
320 hr
10.00/hr
Cost/ton
of coal
burned.$
70,300
120,700
11,700
8,700
77,400
13,900
(1,600)
5,300
89,800
15,100
3.200
414,500
1,252,900
615,600
82,900
7,000
705,500
1,958,400
59,700
Total annual
cost. $
4.06
2.018.100
Coal burned-497,000 tons/yr; .795 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x IVi' limestone ground to 80% minus 400 mesh
Capital investmen-t, $3,498,000
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
L-175
Table A-8 5 Average Annual Operating Cost for Reducing S02 Emission
jrom_Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(350-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
1.0 Moles CaO Injected per Mole S in Fuel;
13.53 Tons Dry Limestone per Hour)
Annual quantity Unit cost, $
Total annual
cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilities*5
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
71,200 tons 4.05/ton
10,070 man-hr 6.00/man-hr
377,400 gal
267,000 M gal
427,200 kWh
3,802,100 kWh
683,500 kWh
-399,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
170hr
10.00/hr
Cost/ton
of coal
burned,$
288.400
288,400
60,400
41,500
8,000
3,000
26,600
4,800
(2,800)
3,600
53,400
13,800
1.700
214,000
502,400
394,000
42,800
6.000
442,800
945,200
20,700
Total annual
cost, $
1.41
965,900
Coal burned-685,800 tons/yr; .784 Ibs/kWh
Remaining life of power plant—15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x 1V4 Hmestone ground to 80% minus 400 mesh
Capital investment, $2,238,600
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection ot limestone, uust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water
Disposal pond located 1 mile from power unit.
. Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-178
TableA-88 Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(350-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
55.04 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaCO3)
Subtotal raw material
289,700 tons 4.05/ton
1.173.300
1,173,300
Conversion costs
Operating labor & supervision
including payroll overhead
Utilities0
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust col lection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust col lection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
13,370 man-hr 6.00/man-hr
1,535,400 gal
570,000 M gal
1,738,200 kWh
15,470,000 kWh
2,781,100 kWh
-322,000 kWh
1,097,300 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
390 hr
10.00/hr
Cost/ton
of coal
burned.$
80,200
168,900
17,100
12,200
108,300
19,500
(2,300)
7,700
108,200
19,700
3.900
543,400
1,716,700
750,100
108,700
8.000
866,800
2,583,500
83,600
Total annual
cost. $
3.83
2,667,100
aBasis:
Coal burned-695,800 tons/yr; .795 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time—5000 hr/yr
Midwest plant location-1972 costs
0" x IVz limestone ground to 80% minus 400 mesh
Capital investment, $4,262,100
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
DCost of utility supplied from power plant at full value.
-------
L-179
Table A-89 Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(50-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
1.0 Moles CaO Injected per Mole S in Fuel;
3.2 Tons Dry Limestone per Hour)
Annual quantity Unit cost, $
Total annual
cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
17,000 tons 4.05/ton
10,070 man-hr 6.00/man-hr
90,100 gal
267,000 M gal
102,000 kWh
907,800 kWh
163,200 kWh
-53,500 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
70 hr
10.00/hr
68.900
68,900
60,400
9,900
8,000
700
6,400
1,100
(400)
3,600
26,700
3,200
700
Cost/ton
of coal
burned,$
120,300
189,200
175,200
24,000
_ 6000
205,200
394,400
4,900
Total annual
cost. $
4.06
399,300
Coal burned-98,300 toiis/yr; .786 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x I1//' limestone ground to 80% minus 400 mesh
Capital investment, $995>300
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-182
TableA- 92 Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection Regulated
(50-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
13.3 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit costf,.$____cgstt_$___
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Iota!
aBasis:
70,200 tons
4.05/ton
10,070 man-hr 6.00/man-hr
372,100 gal
267,000 M gal
421,200kWh
3,748,700 kWh
673,900 kWh
-38,500 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
160hr
10.00/hr
Cost/ton
of coal
burned,$
~8.72
284,300
284,300
60,400
40,900
8,000
2,900
26,200
4,700
(300)
3,600
50,400
4,800
1,600.
203,200
487,500
323,600
40,700
6.000
370,300
857,800
20,200
Total annual
cost, $
Coal burned-100,700 tons/yr; .806 Ibs/kWh
Remaining life of power plant—15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x I'/z' limestone ground to 80% minus 400 mesh
Capital investment, $1,838,700
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power Unit,
Cost of solids disposal pond not included.
bCost of utility supplied from power plant at full value.
-------
L-183
Table A-93Average Annual Operating Cost for Reducing SO2 Emission
from Poy^r_Pl^tsj3^Dry i-imestone Injection-Regulated Power Company Economics3
(150-MW Existing Coal-Fired Power Unit; 5.0% S in fuel-
1.0 Moles CaO I njected per Mole S in Fuel;
9.7 Tons Dry Limestone per Hour)
Direct Costs
Delivered raw material
Limestone (95% CaCO3)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
quantity Unj^cost $
51,100 tons 4.05/ton
10,070 man-hr 6.00/man-hr
270,800 gal
267,000 M gal
306,600 kWh
2,728,700 kWh
490,600 kWh
-160,500 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
140hr
10.00/hr
Total annual
cost, $
207.000
207,000
60,400
29,800
8,000
2,100
19,100
3,400
(1,100)
3,600
44,300
7,800
1.400
178,800
385,800
305,600
35,800
6,000
Cost/ton
of coal
burned, $
2.54
347,400
733,200
14,800
Total annual
cost, $
748,000
Coal burned-294,800 tons/yr; .786 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x 1% limestone ground to 80% minus 400 mesh
Capital 6investment, $1,736,200
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-184
TableA-9^ Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
(150-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
2.0 Moles CaO Injected per Mole S in Fuel;
19.6 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
103,100 tons 4.05/ton
10,070 man-hr 6.00/man-hr
546,400 gal
267,000 M gal
618,600 kWh
5,505,500 kWh
989,800 kWh
-142,000 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
140 hr
10.00/hr
Cost/ton
of coal
burned,$
417.600
417,600
60,400
60,100
8,000
4,300
38,500
6,900
(1,000)
3,600
61,600
9,500
1f400
253,300
670,900
417,000
50,700
6.000
473,700
1,144,600
29,900
Total annual
cost, $
3.95
1,174,500
aBasis:
b,
Coal burned-297,300 tons/yr; .793 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x \Vi limestone ground to 80% minus 400 mesh
Capital investment, $2,369,500
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
'Cost of utility supplied from power plant at full value.
-------
L-185
TableA-95 Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(150-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
29.7 Tons Dry Limestone per Hour)
Annual quantity Unit cost, $
Total annual
cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
156,000 tons
4.05/ton
11,720man-hr 6.00/man-hr
827,300 gal
390,000 M gal
936,600 kWh
8,335,700 kWh
1,498,600 kWh
-128,000 kWh
750,800 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
270 hr
10.00/hr
Cost/ton
of coal
burned. $
-631J300
631,800
70,300
91,000
11,700
6,600
58,300
10,500
(900)
5,300
77,100
10,700
2.700
343,300
975,100
515,100
68,700
7fOOO
590,800
1,565,900
45,100
Total annual
cost.
5.38
1,611,000
"Basis:
Coal burned-299,700 tons/yr; .799 Ibs/kWh
Remaining life of power plant—15 yr
Power plant on-stream time—5000 hi/yr
Midwest plant location-1972 costs
0" x 1V4 limestone ground to 80% minus 400 mesh
Capital investment, $2,926,600
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection oi limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
L-186
Table A-96Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
(150-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
40 Tons Dry Limestone per Hour)
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Total annual
Annual quantity Unit cost, $ cost, $
21 0,500 tons 4.05/ton 852.500
852,500
Conversion costs
Operating labor & supervision
including payroll overhead
Utilities^
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust col lection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
11,720 man-hr 6.00/man-hr
1,115,700 gal
390,000 M gal
1,263,000 kWh
11,240,700 kWh
2,020,800 kWh
-115,500 kWh
750.800 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
320 hr
10.00/hr
Cost/ton
of coal
burned,$
70,300
122,700
11,700
8,800
78,700
14,100
(800)
5,300
89,500
11,800
3.200
415,300
1,267,800
594,200
83,100
7.000
684,300
1,952,100
60,700
Total annual
cost, $
6.66
2,012,800
aBasis:
Coal burned-302,100 tons/yr; .806 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x IVz limestone ground to 80% minus 400 mesh
Capital investment, $3,376,200
Incremental electrostatic piecipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
L-187
Table A-97 Average Annual Operating Cost for Reducing SO2 Emission
jfrom Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(250-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
1.0 Moles CaO Injected per Mole S in Fuel;
16.8 Tons Dry Limestone per Hour)
rect Costs
terial
CaCOs )
later! a I
Annual quantity
85, 100 tons
Unit cost, $
4.05/ton
Total annual
cost, $
344.700
344,700
Delivered raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilities'^
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
10,070 man-hr 6.00/man-hr
451,000 gal
267,000 M gal
510,600 kWh
4,544,300 kWh
817,000 kWh
-267,500 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
190hr
10.00/hr
Cost/ton
of coal
burned. $
60,400
49,600
8,000
3,600
31,800
5,700
(1,900)
3,600
57,300
12,100
1.900
232,100
576,800
407,400
46,400
6,000
459,800
1,036,600
24,600
Total annual
cost. $
2.16
1,061,200
Total
aBasis:
Coal burned-491,400 tons/yr; .786 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location—1972 costs
0" x 1% limestone ground to 80% minus 400 mesh
Capital investment, $2,314,500
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-188
TableA-98 Average Annual Operating Cost for Reducing S02 Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
(250-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
2.0 Moles CaO Injected per Mole S in Fuel;
32.7 Tons Dry Limestone per Hour)
Annual quantity Unit cost. $
Total annual
cost. $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
171,900 tons
4.05/ton
11,720 man-hr 6.00/man-hr
911,100 gal
390,000 M gal
1,031,400 kWh
9,179,500 kWh
1,650,200 kWh
-236,500 kWh
750,800 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
280 hr
10.00/hr
Cost/ton
of coal
burned.$
696,200
696.200
70,300
100,200
11,700
7,200
64,300
11,600
(1,700)
5,300
82,000
14,600
2.800
368,300
1,064,500
566,900
73,700
7.000
647,600
1,712,100
49,900
Total annual
cost. $
3.56
1.762.000
"Basis:
Coal burned-495,400 tons/yr; .793 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x IVi" limestone ground to 80% minus 400 mesh
Capital investment, $3,221,100
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
L-189
TableA-99 Average Annual Operating Cost for Reducing SO, Emission
from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(250-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
3.0 Moles CaO Injected per Mole S in Fuel;
49.4 Tons Dry Limestone per Hour)
Annual quantity Unit cost, $
Total annual
cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
260,200 tons 4.05/ton
11,720 man-hr 6.00/man-hr
1,379,100 gal
570,000 M gal
1,561,200 kWh
13,894,700 kWh
2,497,900 kWh
-213,500 kWh
1,097,300 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
360 hr
10.00/hr
Cost/ton
of coal
burned.$
4.86
1.053.800
1,053,800
70,300
151,700
17,100
10,900
97,300
17,500
(1,500)
7,700
102,600
16,500
3.600
493,700
1,547,500
698,400
98,700
7,000
804,100
2,351,600
75,200
Total annual
cost. $
2,426,800
aBasis:
Coal burned-499,400 tons/yr; .799 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x 1V4 limestone ground to 80% minus 400 mesh
Capital investment, $3,968,400
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-190
TableA-100 Average Annual Operating Cost for Reducing SOj Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company Economics8
(250-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
66.7 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
350,800 tons 4.05/ton
13,370 man-hr 6.00/man-hr
1,859,200 gal
609,000 M gal
2,104,800 kWh
18,732,700 kWh
3,367,700 kWh
-192,500 kWh
1,172,300 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
430 hr
10.00/hr
Cost/ton
of coal
burned, $
1.420.700
1,420,700
80,200
204,500
18,300
14,700
131,100
23,600
(1,300)
8,200
119,300
18,200
4.300
621,100
2,041,800
806,400
124,200
8.000
938,600
2,980,400
101,100
Total annual
cost, $
6.12
aBasis:
3,081,500
Coal burned-503,500 tons/yr; .806 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x l'/2f limestone ground to 80% minus 400 mesh
Capital investment, $4,582,000
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-191
Table A-101 Average Annual Operating Cost for Reducing SQ2 Emission
_Jrom Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
(350-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
1.0 Moles CaO Injected per Mole S in Fuel;
22.7 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
119,100 tons 4.05/ton
482.400
482,400
Conversion costs
Operating labor & supervision
including payroll overhead
Utilities^
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
10,070 man-hr 6.00/man-hr
631,200 gal
267,000 M gal
714,600 kWh
6,359,900 kWh
1,143,400 kWh
-374,500 kWh
514,000 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
230 hr
10.00/hr
Cost/ton
of coal
burned.$
60,400
69,400
8,000
5,000
44,500
8,000
(2,600)
3,600
67,800
15,700
2.300
282,100
764,500
489,800
56,400
6.000
552,200
1,316,700
34,500
Total annual
cost. $
1.96
1,351,200
aBasis:
Coal burned-688,000 tons/yr; .786 Ibs/kWh
Remaining life of power plant—15 yr
Power plant on-stream time—5000 hr/yr
Midwest plant location-1972 costs
0" x IVz limestone ground to 80% minus 400 mesh
Capital investment, $2,782,700
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
, Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-192
TableA-102Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
(350-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
2.0 Moles CaO Injected per Mole S in Fuel;
'45.8 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost. $ cost. $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
240,600 tons 4.05/ton
974.400
974,400
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
11,720 man-hr 6.00/man-hr
1,275,200 gal
570,000 M gal
1,443,600 kWh
12,848,000 kWh
2,309,800 kWh
-331,100 kWh
1,097,300 kWh
-11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
340 hr
10.00/hr
Cost/ton
of coal
Jjurned,$
3.33
70,300
140,300
17,100
10,100
89,900
16,200
(2,300)
7,700
98,800
19,000
3.400
470,500
1,444,900
691,200
94,100
7,000
792,300
2,237,200
69,800
Total annual
cost, $
2,307,000
aBasis:
Coal burned-693,600 tons/yr; .793 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stieam time-5000 hr/yr
Midwest plant location-1972 costs
0" x IVi" limestone ground to 80% minus 400 mesh
Capital investment, $3,927,000
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
L-193
TableA-103 Average Annual Operating Cost for Reducing SO2 Emission
from Power Plants by Dry Limestone Injection-Regulated Power Comnany Economic
(350-MW Existing Coal-Fired Power Unit; 5.0% S in fuel-
3.0 Moles CaO I njected per Mole S in Fuel •
69.2 Tons Dry Limestone per Hour)
Annual quantity Unit cost, $
Total annual
cost, $
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
So I ids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
364,300 tons 4.05/ton
13,370 man-hr 6.00/man-hr
1,930,800 gal
630,000 M gal
2,185,800 kWh
19,453,600 kWh
3,497,300 kWh
-298,900 kWh
1,212,800 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
440 hr
10.00/hr
Total
Cost/ton
of coal
burned, $
4.57
1.475.400
1,475,400
80,200
212,400
18,900
15,300
136,200
24,500
(2,100)
8,500
121,500
21,500
4.400
641,300
2,116,700
840,600
128,300
8.000
976,900
3,093,600
105,200
Total annual
cost, $
3,198,800
aBasis:
Coal burned-699,200 tons/yr; .799 Ibs/kWh
Remaining life of power plant—15 yr
Power plant on-stream time-5000 hr/yr
Midwest plant location-1972 costs
0" x IVz limestone ground to 80% minus 400 mesh
Capital investment, $4,766,400
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
. Cost of solids disposal pond not included.
Cost of utility supplied from power plant at full value.
-------
L-194
Table A-lQl+Average Annual Operating Cost for Reducing SO3 Emission
from Power Plants by Dry Limestone injection—Regulated Power Company Economics3
(350-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
4.0 Moles CaO Injected per Mole S in Fuel;
93.3 Tons Dry Limestone per Hour)
Total annual
Annual quantity Unit cost, $ cost, $ _
Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Conversion costs
Operating labor & supervision
including payroll overhead
Utilitiesb
Fuel oil (drying)
Sluice water
Electricity
Receiving-drying
Grinding
Injection
Dust collection (credit)
Solids disposal
Maintenance
Labor and material
Drying, grinding, injection, and solids
disposal areas
Dust collection
Analyses
Subtotal conversion costs
Subtotal direct costs
Indirect Costs
Average capital charges at 17.6%
of initial fixed investment
Overhead
Plant, 20% of conversion costs
Administrative, 10% of operating labor
Subtotal indirect costs
Average annual operating cost
for dry limestone injection
Thermal effect of dry limestone injection
on operating cost of power plant
Total
491,100 tons 4.05/ton
1.989.000
1,989,000
15,350 man-hr 6.00/man-hr 92,100
2,602,800 gal
831,DOOM gal
2,946,600 kWh
26,224,700 kWh
4,714,600 kWh
-269,500 kWh
1,599,700 kWh
.11/gal
.03/M gal
.007/kWh
.007/kWh
.007/kWh
.007/kWh
.007/kWh
530 hr
10.00/hr
Cost/ton
of coal
burned, $
286,300
24,900
20,600
183,600
33,000
(1,900)
11,200
145,700
23,700
5,300
824,500
2,813,500
993,600
164,900
9.200
1,167,700
3,981,200
141,500
Total annual
cost, $
5.85
4,122,700
aBasis:
Coal burned-705,000 tons/yr; .806 Ibs/kWh
Remaining life of power plant-15 yr
Power plant on-stream time—5000 hr/yr
Midwest plant location-1972 costs
0" x \V" limestone ground to 80% minus 400 mesh
Capital investment, $5,645,500
Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
and electrostatic devices.
Solids disposed as 15% slurry with no recycle of pond water.
Disposal pond located 1 mile from power unit.
Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.
-------
Table A-105
DRY LIMESTONc INJECTION, REGULATED POWER CO.- ECON., 50 MW EX. COAL FIRED POWER UNIT, 0.3* S IN FUEL, 3.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 751500
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KV»-HR/KW M KwH/YR TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
5.- _
6
7
8
9
11
12
13
14
15
16
17
18
19
20.
21
22
23
24
25
26
27
28
29
30.
5000
5000
5 JOO
5000
3500
3500
3500
3_.5.0_.0_
1500
1500
1500
1500
250000
250000
250000
250000
25.QO.flii _
175000
175000
175000
175000
1250.0.0.
75000
75000
75000
75000
97900
97900
97900
97900
212Q2_
68600
6S600
68600
68600
29400
29400
29400
29400
224.00
TOTAL 50000 2500000 979500
EQUIVALENT CCST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IE DISCOUNTED AT 10.0? TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT rtJRTH, DOLLARS PER TON OF COAL bURNED
EQUIVALENT fVEScNT ft'JRTH, 1ILLS PER KILOWATT-HOUR
376200
365800
355400
344900
3_ 2.4.5-0.0.
283000
277600
267200
256700
_24.6.3_QQ. _
180200
169800
159400
143900
13a5QQ.
3909400
3.99
1.56
2223900
2.27
0.89
376200
742000
1097400
1442300
1226.3.30.
2064800
2342400
2609600
2866300
3.1126.Q.Q.
3292800
3462600
3622000
3770900
01
-------
Table A-106
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 50 MW EX. COAL FIREO POWER UNIT, 0.81 S IN FUEL, 4.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: t 834500
YEARS
AFTER
POWER ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KWH/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPAMY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWER)
TONS COAL/YR *
CUMULATIVE
NET INCREASE
IS COST OF
POWER,
$
1
2
3
4
5
6
7
8
9
11
12
13
16 5000
17 5000
18 5000
19 5000
21 3500
22 3500
23 3500
24 3500
26 1500
27 1500
28 1500
29 1500
3.Q 1500
250000
250000
250000
250000
175000
175000
175000
175000
75000
75000
75000
75000
98100
98100
98100
98100
68700
68700
68700
68700
29400
29400
29400
29400
_ 224QQ-
TOTAL 50000 2500000 981000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
417800
406200
394600
383100
318800
307200
295600
284100
198100
186600
175000
163400
1512QQ
4326400
4.41
1.73
2464300
2.51
0.99
417800
824000
1218600
1601700
laiazao-
2292000
2599200
2894800
3178900
3649500
3836100
4011100
4174500
ID
-------
Table A-107
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 50 MM EX. COAL FIRED POWER UNIT, 0.8* S IN FUEL, 5.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 908300
YEARS
AFTER
POWER
UNIT
START
ANNUAL
OPERATION,
KW-HR/KW
POWER
GENERATION
M KWH/YR
POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
$
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
~6
7
8
9
-10.
11
12
13
V4
16
17
18
19
21
22
23
24
26
27
28
29
3Q_
5000
5000
5000
5000
5.QQQ.
3510
3500
3500
3500
_ as.QQ.
1500
1500
1500
1500
250000
250000
250000
250000
25QOQQ_
175000
175000
175000
175000
75000
75000
75000
75000
25QO.Q
98200
98200 '
98200 '
98200 '
68800 ;
68800 ;
68800 :
68800 :
6jaaQQ i
29500 i
29500 i
29500 ]
29500 ;
2.2500 __ J
TOTAL 50000 2500000 982500
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.OX TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
456900
444300
431700
419100
_iQ6.5QQ
347400
334800
322200
309600
-2.220.0.0.
214300
201700
189100
176500
16.3,200.
4715000
4.80
1.89
2689400
2.74
1.08
456900
901200
332900
^752000
2J.5fl5Qfl_
2505900
2840700
3162900
3472500
3983800
4185500
4374600
4551100
47-15.0.00.
<£>
-------
Table A-108
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 50 MW EX. COAL FIRED POWER UNIT, 0.8S S IN FUEL, 6.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 974900
YEARS
AFTER
POWER. ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KWH/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWERJ
TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
5
6
7
8
9
10
11
12
13
14
16 5000
17 5000
18 5000
19 5000
20 5QOO ^
21 3500
22 3500
23 3500
24 3500
25 • 350Q
26 1500
27 1500
28 1500
29 1500
ifl _L5fifl ^
250000
250000
250000
250000
175000
175000
175000
175000
__125flQQ_
75000
75000
75000
75000
15QQQ
98400
98400
98400
98400
_, 98400
68900
68900
68900
68900
29500
29500
29500
29500
29500
TOTAL 50000 2500000 984000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
493400
479900
466300
452800
4a22QQ
374400
360900
347300
333800
3.2D.3.0.Q
229700
216200
202600
189100
115.400.
5081600
5.16
2.03
2901100
2.95
1.16
493400
973300
1439600
1892400
23.3.1J.QO.
2706100
306700C
3414300
3748100
4P.684.Qp'.
4298100
4514300
4716900
4906000
saaiiafl.
00
-------
Table A-109
DRY LIMESTONE INJECTION, REGULATED POHER CO. ECON., 50 MW EX. COAL FIRED POWER UNIT, 0.8* S IN FUEL, 7.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: * 1036300
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR ",
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
6
7
8
9
-10.
11
13
14
15_
16
17
18
19
-2.Q.
21
22
23
24
26
27
28
29
_2tt
TOT
PRE
5000 250000
5000 250000
5000 250000
5000 250000
_5.QQO_ 250000
3500
3500
3500
3500
1500
1500
15OO
1500
1SOQ
175000
175000
175000
175000
115QQfl
75000
75000
75000
75000
75000
98500
98500
98500
98500
69000
69000
69000
69000
6.2QQQ .
29600
29600
29600
29600
226QQ
AL 50000 2500000 985500
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
SENT WORTH IF DISCOUNTED AT 10. OS TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
528300
513900
499500
485100
4iaaaa _„
399800
385400
371000
356700
3.4.22QQ _
243900
229500
215200
20080
18.6.4.QU
5428600
5.51
2.17
3102100
3.15
1.2*
528300
1042200
1541700
2026800
2 8 9 74 00~
3282800
3653800
40105OO
4596700~
4826200
5041400
5242200
54.2.B6.QQ
VD
-------
Table A-110
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 150 MW EX. COAL FIRED POWER UNIT, 0.8S S IN FUEL, 3.0 INJECTION STOICHIONETRY.
FIXED INVESTMENT: $ 1280100
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR $
1
2
3
4
^5
6
7
8
9
11
12
13
14
16 5000
17 5000
18 5000
19 5000
^20 _ 5000
21
22
23
24
26
27
28
29
3500
3500
3500
3500
.
750000
750000
750000
750000
525000
525000
525000
525000
1500 225000
1500 225000
1500 225000
1500 225000
1500 22jOQO
293800
293800
293800
293800
205700
205700
205700
205700
88100
88100
88100
88100
_BfllQQ
TOTAL 50000 7500000 2938000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
634300
616500
598800
581000
-56.3,10.0
478500
460800
443100
425300
40.16.QJi
291400
273700
256000
238200
6489000
2.21
0.87
3712400
1.26
0.49
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
*
634300
1250800
1849600
2430600
,. , 2223900
3472400
3933200
4376300
4801600
52Q22QQ
5500600
5774300
6030300
6268500
&.4S2QQQ
IV)
o
o
-------
Table A-lll
DRY LIMESTONE INJECTIONt REGULATED POWER CO. ECON., 150 MM EX. COAL FIRED POWER UNIT, 0.8* S IN FUEL, 4.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 1431500
YEARS
AFTER
POWER
UNIT
START
ANNUAL
OPERATION,
KW-HR/KW
POWER
GENERATION
M KWH/YR
POWER UNIT
FUEL CONSUMPTIONt
TONS COAL/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWERJ
$
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
*
750000
750000
750000
750000
,15.0.0.0.0.-
525000
525000
525000
525000
225000
225000
225000
225000
294200
294200
294200
294200
729300
709400
689600
669700
206000
206000
206000
206000
88300
88300
88300
88300
aaaofl
547700
527900
508000
488200
329700
3099QO
290000
270200
__ 2.5.0100.
729300
1438700
2126300
2798000
-34.4.12QQ.
3995600
4523500
5031500
5519700
6317800
6627700
6917700
7187900
TOTAL 50000 7500000 2942500 7438200
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED 2.53
EQUIVALENT COST, MILLS PER KILOWATT-HOUR 0.99
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS 4262400
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED 1.45
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR 0.57
-------
Table A-112
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 150 MW EX. COAL FIRED POWER UNIT, 0.88 S IN FUEL, 5.0 INJECTION STOICHIOM6TRY.
FIXED INVESTMENT: $ 1568800
YEARS
AFTER
POWER ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KWH/YR
I
Z
3
4
5
6
7
8
9
,10 ^rT-
11
12
13
14
15
16 5000 750000
17 5000 750000
18 5000 750000
19 5000 750000
_2Q 5UCJ2 7.5QQQO
21 3500
22 3500
23 3500
24 3500
25 350O
26 1500
27 1500
28 1500
29 1500
30 , , 15Q0 , - ,
525000
525000
525000
525000
525QQ&.
225000
225000
225000
225000
225QQ.fi
ANNUAL OPERATING COST
INCLUDING REGULATED CUMULATIVE
R01 FOR POWER COMPANY NET INCREASE
POWER UNIT (NET ANNUAL INCREASE IN COST OF
FUEL CONSUMPTION, IN COST OF POWER! POWER.
TONS COAL/YR § $
294700
294700
294700
294700
^_2S4ZOa^.,li».r-
206300
206300
206300
206300
2Q6300
88400
88400
88400
88400
8fl400_
TOTAL 50000 7500000 2947000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0? TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
819300
797600
775800
754000
. Z3.22Qa_
613300
591600
569800
548100
526.3flQ
365400
343700
321900
300200
2ia4Qa_
8337700
2.83
1.11
4784000
1.62
0.64
819300
1616900
2392700
3146700
3.S1SQQQ
4492300
5083900
5653700
6201800
6-22JLLQ2
7093500
7437200
7759100
805930O
. aaaziflo.
l\3
O
-------
Table A-113
DRV LIMESTONE INJECTION, REGULATED POWER CO. ECON., 150 MW EX. COAL FIRED POWER UNIT, 0.8* S IN FUEL, 6.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 1694400
YEARS
AFTER.
POWER ANNUAL POWER
UNIT OPERATION, GENERATION
START KH-HR/KW M KWH/YR
1
2
3
4
•j
6
7
8
9
-10
11
12
13
14
1*>
16
17
ia
19
-2.0.
21
22
23
24
25
5000
5000
5000
5000
5QOO
3500
3500
3500
3500
3500
750000
750000
750000
750000
isaoao-
525000
525000
525000
525000
525QOO
26 1500 225000
27 1500 225000
28 1500 225000
29 1500 225000
20. i5CO 225QQQ
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWER)
TONS COAL/YR $
295100
295100
295100
295100
zasiaa _
206600
206600
206600
206600
ZQfifiQfl
88500
88500
88500
88500
Sfl5.QQ
TOTAL 50000 7500000 2951000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
905800
882300
858800
835300
aiiaofl_
676000
652500
629000
605500
aazQ-QQ
399300
375800
352300
328800
3Q52QQ
9200500
3.12
i.23
5284900
1,79
0.70
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
i
905800
1788100
2646900
3482200
. i224QDfl
4970000
§622500
6251500
6857000
Z4.22QQfl_
1838300
821*100
3566400
8895200
22£Ki5_QQ
IV)
o
00
-------
Table A-llU
OR* LIMESTONE INJECTION, REGULATED POWER CO. ECON., 150 MM EX. COAL FIRED POWER UNIT, 0.81 S IN FUEL, 7.0 INJECTION STOICHIOMETRV.
FIXED INVESTMENT: * isoaooo
YEARS
AFTER
POWER.
UNIT
START
~~I
2
3
4
ANNUAL
OPERATION,
KW-HR/KW
POWER
GENERATION
M KWH/YR
POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
6
7
8
9
"ll"
12
13
14
16
17
18
19
21
22
23
24
-2,5
26
27
28
29
5000
5000
5000
5000
aaoa—
3500
3500
3500
3500
asafl
1500
1500
1500
1500
750000
750000
750000
750000
-isaflfla..
525000
525000
525000
525000
_525_aaa.
225000
225000
225000
225000
295600
295600
295600
295600
2256.0.0—
206900
206900
206900
206900
2fl62QQ_.
88700
88700
88700
88700
988800
963700
938600
913600
988800
1952500
2891100
3804700
736200
711200
686100
661100
63.6QQ.O.-
431400
406400
381300
356200
5429400
6140600
6826700
7487800
8555200
8961600
9342900
9699100
1QQ3.Q.3.QO.
TOTAL 50000 7500000 2956000 10030300
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED 3.39
EQUIVALENT COST, MILLS PER KILOWATT-HOUR 1.34
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS 5766600
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED 1.95
EQUIVALENT PRESENT-WORTH, MILLS PER KILOWATT-HOUR 0.77
-------
Table A-115
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 250 MM EX. COAL FIRED POWER UNIT, 6.8X S IN FUEL, 3.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 1695100
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED CUMULATIVE
AFTER ROI FOR POWER COMPANY NET INCREASE
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE IN COST OF
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER) POWER,
START KW-HR/KW M KWH/YR TONS COAL/YR $ $
1
2
3
4
5
6
7
8
9
ID
11
12
13
14
15
16 5000
17 5000
18 5000
19 5000
20 ^5OOQ
21 3500
22 3500
23 3500
24 3500
25 2500
26 1500
27 1500
28 1500
29 1500
^n 1*500
1250000
1250000
1250000
1250000
_125flflQQ_
875000
875000
875000
875000
aiiaaa.
375000
375000
375000
375000
375000
489700
489700
489700
489700
„. 489700, _,..,-
342800
342800
342800
342800
34.2flQ.fl
146900
146900
146900
146900
__ JAfiSQQ __
TOTAL 50000 12500000 4897000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
857200
833700
810200
786700
-1632,00
642200
618700
595200
571600
54B1QQ
384800
361300
337800
314300
__22QflQQ
8715800
1.78
0.70
4999800
1.02
0.40
857200
1690900
2501100
3287BOO
4fl51QQfl.
4693200
5311900
5907100
6478700
_ ZQ2.6flflQ
7411600
7772900
8110700
8425000
,- „, ,9715800
-------
Table A-ll6
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 250 MW EX. C3AL FIRED POWER UNIT, 0.8* S IN FUEL, 4.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: * 1868100
YEARS
AFTER
POWER ANNUAL POWER POWER UNIT
UNIT OPERATION, GENERATION FUEL CONSUMPTION,
START KW-HR/KW M KWH/YR TONS COAL/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
INET ANNUAL INCREASE
IN COST OF POWER)
*
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
6
7
8
9
10
11
12
13
14
A.5
16
17
IB
19
2.0. ^ -
21
22
23
24
26
27
28
29
3.Q
5000
5000
5000
5000
50QC
3500
3500
3500
3500
1500
1500
1500
1500
1«500
1250000
1250000
1250000
1250000
125QQQQ
875000
875000
875000
875000
"375000
375000
375000
375000
375000
490400
490400
490400
490400
34330O
343300
343300
343300
343100
147100
147100
147100
147100
1471QQ
989600
963700
9378OO
911900
48.6jO.PQ
738000
712100
686200
660300
6.14400
435500
409600
383700
357800
331900
989600
1953300
2891100
3803000
4&fl2flflQ_
5427000
6139100
6825300
7485600
fli2flQOQ_
8555500
8965100
9348800
9706600
10.03.8.500.
TOTAL 5000C 12500000 4904000 10038500
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED 2.05
EQUIVALENT COST, MILLS PER KILOWATT-HOUR 0.80
PRESENT WORTH IF DISCOUNTED AT 10. OX TO INITIAL YEAR, DOLLARS 5768300
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED 1.18
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR 0.46
17
N)
o
-------
Table A-117
ORV LIMESTONE INJECTION, REGULATED POWER CO. ECON., 250 MW EX. C3AL FIRED POWER UNIT, 0.8* S IN FUEL, 5.0 INJECTION STOICHIOMETRV.
FIXED INVESTMENT: $ 2086100
YEARS
AFTER
POWER ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KHH/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POKER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWER)
TONS COAL/YR *
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
«
1
2
3
4
6
7
8
9
1O , .,
11
12
13
14
A5
16 5000
17 5000
18 5000
19 5000
2Q _5DQO_
21 3500
22 3500
23 3500
24 3500
25 35 QQ
26 1500
27 1500
28 1500
29 1500
30 15QQ
1250000
1250000
1250000
1250000
lisaaoa
875000
875000
875000
875000
ai5flOQ_
375000
375000
375000
375000
375QQO
491100
491100
491100
491100
^TT ^491100,^ ^
343800
343800
343800
343800
343800
147300
147300
147300
147300
1413-0.0. _ _
TOTAL 50000 12500000 4911000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT HORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT HORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
1136400
1107500
1078500
1049600
__1QZQ1QQ
844800
815900
787000
758000
2221QQ
493400
464400
435500
406600
—17-7.&OQ
11505000
2.34
0.92
6619100
1.35
0.53
1136400
2243900
3322400
4372000
5322200-
6237500
7053450
7840400
8598400
22225flQ_
9820900
10285300
10720800
11127400
li505flflQ_
O
-si
-------
Table A-118
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 250 MW EX. COAL FIRED POWER UNIT, 0.8S S IN FUEL, 6.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: S 2253600
ANNUAL OPERATING COST
YEARS INCLUDING RP6ULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR $
1
2
3
4
5
6
7
8
9
_10
11
12
13
14
15
16
17
IB
19
^2.0
5000
5000
5000
5000
5.OOO . .
21 3500
22 3500
23 3500
24 3500
25 35OO
26
27
26
29
3.0
1500
1500
1500
1500
1500
1250000
1250000
1250000
1250000
1250000
875000
875000
875000
875000
875000
375000
375000
375000
375000
375000
491900
491900
491900
491900
42123Q _
344300
344300
344300
344300
24&3.Q.a_
147600
147600
147600
147600
14-7.6.0.0—
TOTAL 50000 12500000 4919000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0? TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT .WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
1267700
1236500
1205300
1174000
-ll&ZflQO _
939900
908700
877500
846200
aiSQQQ
543500
512300
481000
449800
41&60H
12818800
2.61
1.03
7382400
1.50
0.59
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
S
1267700
2504200
3709500
4883500
6flZ63flfl_
6966200
7874900
8752400
9598600
,,10413600
10957100
11469400
11950400
12400200
IZfllflSQQ.
ro
o
oo
-------
Table A-119
DRV LIMESTONE INJECTION, REGULATED POWER CO. ECON., 250 MM EX. COAL FIRED POWER UNIT, 0.8* S IN FUEL, 7.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: * 2407700
YEARS
AFTER
POWER
UNIT
START
1
2
3
4
6
7
8
9
10
11
12
13
14
16
17
18
19
2O
21
22
23
24
25
26
27
28
29
30
TOTAL
EQU
ANNUAL
OPERATION,
KW-HR/KW
5000
5000
5000
5000
50OO
3500
3500
3500
3500
35flQ
1500
1500
1500
1500
150°
50000
IVALENT COST,
POWER
GENERATION
M KWH/YR
1250000
1250000
1250000
1250000
1250000 ,.
875000
875000
875000
875000
,_ aisjwp
375000
375000
375000
375000
-325000.
12500000
DOLLARS PER TON OF
POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR
492600
492600
492600
492600
4226.QQ
344800
344800
344800
344800
_ _,_34^aoa
147800
147800
147800
147800
4926000
COAL BURNED
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
tNET ANNUAL INCREASE
IN COST OF POWER)
S
1394700
1361300
1327900
1294500
1261200
1031600
998200
964800
931400
591600
558200
524800
491400
14087600
2.86
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
t
1394700
2756000
4083900
5378400
_ 6.6.226.00
7671200
8669400
9634200
10565600
_ 114.43.6.0.Q
12055200
12613400
13138200
13629600
EQUIVALENT COST, MILLS PER KILOWATT-HOUR 1.13
PRESENT WORTH IF DISCOUNTED AT 10.OX TO INITIAL YEAR, DOLLARS 8120000
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED 1.65
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR 0.65
o
to
-------
Table A-120
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 350 MW EX. C3AL FIRED POWER UNIT, 0.8J S IN FUEL, 3.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 2032300
YEARS
AFTER
POWER. ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KWH/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT CNET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWER)
TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
5 ,-
6
7
8
9
10
11
12
13
14
15.
16 5000
17 5000
18 5000
19 5000
2Q__ _5QQQ
21 3500
22 3500
23 3500
24 3500
_25 J5QO
26 1500
27 1500
28 1500
29 1500
3g T — L5QQ _.,„„„
1750000
1750000
1750000
1750000
-1Z500QO-
1225000
1225000
1225000
1225000
12.25.DQQ ..
525000
525000
525000
525000
525QOQ
685600
685600
685600
685600
, n 6.856QQJ
479900
479900
479900
479900
_ £239.00
205700
205700
205700
205700
205700
TOTAL 50000 17500000 6856000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
1055400
1027200
999100
970900
stiziao.
787200
759000
730800
702600
6.145.00
465900
43 700
409500
381300
-15.1IQO.
10696900
1.56
0.61
6146600
0.90
0.35
1055400
2082600
3081700
4052600
4995300
5782500
6541500
7272300
7974900
aai240Q
9115300
9553000
9962500
10343800
106.i62QQ
-------
Table A-121
ORY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 350 HW EX. COAL FIRED POWER UNIT, 0.8* S IN FUEL, 4.0 INJECTION STOICHIOHETRY.
FIXED INVESTMENT: s 2278800
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR *
1
2
3
4
6
7
8
9
1ft
11
12
13
-15.
16
17
18
19
21
22
23
24
25
26
27
28
29
5000
5000
5000
5000
3500
3500
3500
3500
1500
1500
1500
1500
L5QQ
1750000
1750000
1750000
1750000
_1Z5QQQO_
1225000
1225000
1225000
1225000
_I2Z5£Qfl_ _
525000
525000
525000
525000
525.QQQ
686600
686600
686600
686600
480600
480600
480600
480600
206000
206000
206000
206000
206000
TOTAL 50000 17500000 6866000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10. 0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
1242200
1210600
1179000
1147400
11I5MQ
922400
890800
859200
827600
_Z26.QQQ
537500
505900
474300
442800
4.112QO.
12562700
1.83
0.72
7230600
1.05
0.41
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
*
1242200
2452800
3631800
4779200
5Jl25flflQ_
6817400
7708200
8567400
9395000
J>fll210.QQ
10728500
11234400
11708700
12151500
-------
Table A-122
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 350 HW EX. COAL FIRED POWER UNIT, 0.8* S IN FUEL* 5.0 INJECTION STOICHIOHETRY.
FIXED INVESTMENT: S 2503200
YEARS
AFTER.
POWER. ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KH M KHH/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWER)
TONS COAL/YR *
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
»
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
2P
5000
5000
5000
5000
5OOO
21 3500
22 3500
23 3500
24 3500
,25 35DO
26
27
28
29
3Q
1500
1500
1500
1500
150O_
1750000
1750000
1750000
1750000
J,75QOOO_
1225000
1225000
1225000
1225000
.1225000.
525000
525000
525000
525000
525QQQ
687600
687600
687600
687600
,687600
481300
481300
481300
481300
4R1300
206300
206300
206300
206300
2O6300
TOTAL 50000 17500000 6876000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10. OX TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
1421900
1387200
1352400
1317700
—uaaaoa
1052200
1017500
9B2800
948000
213200
605800
571100
536400
501700
.4J&.1QDQ
14358000
2.09
0.82
8274100
1.20
0.47
1421900
2809100
4161500
5479200
626220Q.
7814400
8831900
9814700
10762700
11626000-
12281800
12852900
13389300
13891000
. _ -14358000.
ro
-------
Table A-123
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 350 MW EX. COAL FIRED POWER UNIT, 0.8X S IN FUEL, 6.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 2707700
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POKER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KH-HR/KW M KWH/YR TONS COAL/YR *
1
a
3
4
5
6
7
8
9
Ifl
11
12
13
1*
15
16 5COO
17 5000
18 5000
19 5000
?0 5.Q.QQ
1750000
1750000
1750000
1750000
1Z5QQQQ
21 3500 1225000
22 3500 1225000
23 3500 1225000
24 3500 1225000
25 25QQ 1225OOO
26 1500
27 1500
26 1500
29 1500
2Q L5fl-Q
525000
525000
525000
525000
525000
688600
688600
688600
688600
_ 68.S6J2Q
482000
482000
482000
482000
4£2flQ.Q.
206600
206600
206600
206600
246.6.0.0.
TOTAL 50000 17500000 6886000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
1595800
1558300
1520700
1483200
14.456.flQ
1177900
1140300
1102800
1065200
1Q22ZQQ
670900
633300
595800
558200
52QZCQ
16096400
2.34
0.92
9285400
1.35
0.53
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1595800
3154100
4674800
6158000
Z6.D26.QQ.
8781500
9921800
11024600
12089800
13.1115flQ
13788400
14421700
15017500
15575700
16.32£4.flQ
GO
-------
Table A-
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 350 MW EX. COAL FIRED POWER UNIT, 0.8* S IN FUEL, 7.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 2893300
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR t
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
»
1
2
3
4
5 '
6
7
8
9
.,10 .„_ ,, ,
11
12
13
14
16 5000 1750000
17 5000 1750000
18 5000 1750000
19 5000 1750000
2ft_ _5flflfl_ ^ 1750000
21 3500
22 3500
23 3500
2* 3500
24 35QP
26 1500
27 1500
28 1500
29 1500
3Q_ t L5QQ n
1225000
1225000
1225000
1225000
-1225QUQ-
525000
525000
525000
525000
•5P5000
689600
689600
689600
689600
&&2&QQ_ _
482800
482800
482800
482800
4828QQ
206900
206900
206900
206900
206900
TOTAL 5000C 17500000 6896500
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10. OX TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
1776900
1736800
1696700
1656500
16.164QQ
1309600
1269500
1229300
1189200
.1142100
740300
700200
660000
619900
5Z2flQQ
17930200
2.60
1.02
10347900
1.50
0.59
1776900
3513700
5210400
686690O
aiaiiflQ-
9792900
11062400
12291700
13480900
_ _14£3.flQ.Qfi_
15370300
16070500
16730500
17350400
11230200.
r
IVJ
-------
Taisle A-125
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 50 MM EX. COAL FIRED POKER UNIT, 3.0* S IN FUEL, 1.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: t 817100
YEARS
AFTER
POWER ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KWH/YR
1
2
3
4
5 ^_^_ - _,„ -
6
7
8
9
11
13
14
15
16 5000
17 5000
18 5000
19 5000
Zfl 5000 „ ,_
21 3500
22 3500
23 3500
24 3500
25 3500
26 1500
27 1500
28 1500
29 1500
3.0 _15Dfl_
250000
250000
250000
250000
175000
175000
175000
175000
75000
75000
75000
75000
750QO
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWER)
TONS COAL/YR »
98000
98000
98000
98000
28000
68600
68600
68600
68600
6860Q
29400
29400
29400
29400
29400
TOTAL 50000 2500000 980000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
407900
396500
385200
373800
311600
300200
288900
277600
194000
182700
171300
160000
iifilQa
4227100
4.31
1.69
2406900
2.46
0.96
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
407900
804400
1189600
1563400
13253Q2_
2237500
2537700
2826600
3104200
3.3.Ifl4.QQ_
3564400
3747100
3918400
4078400
422JlQPr
01
-------
Table A-126
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 50 MM EX. COAL FIRED POWER UNIT, 3.0? S IN FUEL, 2.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: « IOTOSOO
YEARS
AFTER
POWER ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KH M KWH/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWER)
TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
6
7
8
9
11
12
13
14
15
16 5000
17 5000
18 5000
19 5000
20 5QQQ
21 3500
22 3500
23 3500
24 3500
25 _J15QQ_
26 1500
27 1500
28 1500
29 1500
250000
250000
250000
250000
175000
175000
175000
175000
_liaQQQ_
75000
75000
75000
75000
15.QQQ
98400
98400
98400
98400
98400
68900
68900
68900
68900
68900
29500
29500
29500
29500
_295Qfl _
TOTAL 50000 2500000 984000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESF.NT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
546100
531200
516400
501500
-4.a6.ZQQ
412900
398100
383200
368400
3535QQ
251600
236700
221800
207000
1221QQ
5607200
5.70
2.24
3205200
3.26
1.28
546100
1077300
1593700
2095200
2994800
3392900
3776100
4144500
4749600
4986300
5208100
5415100
, 56QI2QQ
r\j
i—»
01
-------
Table A-12?
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 50 MW EX. COAL FIRED POWER UNIT, 3.0* S IN FUEL, 3.0 INJECTION ST01CHIOMETRY.
FIXED INVESTMENT: $ 1271500
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR $
1
2
3
4
5
6
7
8
9
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
11
12
13
14
16 5000
17 5000
18 5000
19 5000
PO 5000
21 3500
22 3500
23 3500
24 3500
25. -3.500
26 1500
27 1500
28 1500
29 1500
an _150-0
250000 98900
250000 98900
250000 98900
250000 98900
250000 2H2QQ _ _.
175000 69200
175000 69200
175000 69200
175000 69200
115000 -u ,69200
75000 29700
75000 29700
75000 29700
75000 29700
isaaa_ 22ZQO
TOTAL 50000 2500000 989000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT *ORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
668100
650400
632800
615200
52Z50Q
502100
484400
466800
449200
431500 ,_
301000
283300
265700
248100
. 23Q4QQ
6826500
6.90
2.73
3911300
3.95
1.56
668100
1318500
1951300
'.566500
3164000-
3666100
4150500
4617300
5066500
5799000
6082300
6348000
6596100
IV)
-------
Table A-128
DRV LIMESTONE INJECTION, REGULATED POWER CO. ECON., 50 MW EX. COAL FIRED POWER UNIT, 3.0* S IN FUEL, 4.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: * 144-2000
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF PDWERI
START KW-HR/KW M KWH/YR TONS COAL/YR $
1
2
3
4
, .5 _..^_ ..„ .
6
7
8
9
IP
11
12
13
14
15
16 5000
17 5000
18 5000
19 5000
20. 5poo
21 3500
22 3500
23 3500
24 3500
25 3500
26 1500
27 1500
28 1500
29 1500
3.Q _ L50Q
250000
250000
250000
250000
25QQOQ
175000
175000
175000
175000
1Z5QQU „„
75000
75000
75000
75000
75QQQ
TOTAL 50000 2500000
EQUIVALENT COST, DOLLARS PER TON OF COAL
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10. 0* TO INI
EQUIVALENT PRESENT WORTH, DOLLARS PER TON
EQUIVALENT PRESENT WORTH, MILLS PER KILOW
99400
99400
99400
99400
224QQ _
69600
69600
69600
69600
_6.9.6.QQ
29800
29800
29800
29800
2.2&Q.Q.
994000
BURNED
TIAL YEAR, DOLLARS
OF COAL BURNED
ATT-HOUR
781000
761000
741100
721100
_ .101100
584200
564200
544200
524200
5Q4.2.QQ
345700
325800
305800
285800
7955200
8.00
3.18
4565900
4.59
1.83
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
781000
1542000
2283100
3004200
4289500
4853700
5397900
5922100
. 6.4 2.6.3.QQ_
6772000
7097800
7403600
7689400
7_3S520J}
oo
-------
Table A-129
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 150 MW EX. COAL FIRED POWER UNIT, 3.0* S IN FUEL, 1.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 140*600
YEARS
AFTER
POWER ANNUAL
UNIT OPERATION,
START KH-HR/KW
1
2
3
4
6
7
8
9
10
11
12
13
14
16 5000
17 5000
18 5000
19 5000
2.O 5.0QQ
21 3500
22 3500
23 3500
24 3500
?*> 3500
26 1500
27 1500
28 1500
29 1500
_aa isafl —
TOTAL 50000
EQUIVALENT COST,
EQUIVALENT COST,
POWER
GENERATION
M KWH/YR
750000
750000
750000
750000
Z5QQ.QQ _
525000
525000
525000
525000
5_2.5QQfl
225000
225000
225000
225000
22.5QO.Q
7500000
DOLLARS PER TON OF
POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR
293900
293900
293900
293900
2,9.3.9.00,
205700
205700
205700
205700
20.5100.
88200
88200
88200
88200
aazfio.
2939000
COAL BURNED
MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0*
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
(
707400
687900
668400
649000
62.95_O.Q
532000
512500
493100
473600
iSilQQ .
321600
302100
282600
263200
Z&3.1D.Q
7220700
2.46
0.96
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
707400
1395300
2063700
2712700
3.3.422QQ
3874200
4386700
4879800
5353400
._ 5flQl5QQ
6129100
6431200
6713800
6977000
122.fllQO._
TO INITIAL YEAR, DOLLARS 4135700
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER
KILOWATT-HOUR
1.41
0.55
[7
N>
I—*
to
-------
Table A-130
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 150 MW EX. COAL FIRED POWER UNIT, 3.0* S IN FUEL, 2.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 1374200
YEARS
AFTER
POWER
UNIT
START
1
2
3
4
..5
6
7
8
9
10
11
12
13
15
16
17
18
19
21
22
23
24
25_
26
27
28
29
.30
ANNUAL
OPERATION,
KW-HR/KW
POWER
GENERATION
M KWH/YR
POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR
5000
5000
5000
5000
5000^
3500
3500
3500
3500
1500
1500
1500
1500
150Q
750000
750000
750000
750000
525000
525000
525000
525000
225000
225000
225000
225000
-22.5000—
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
t
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
S
295300 1029400 1029400
295300 1003500 2032900
295300 977500 3010400
295300 951500 3961900
-225300 9.25500. iflaiAQQ-
206700 766200 5653600
206700 740300 6393900
206700 714300 7108200
206700 688300 7796500
.2Q61QQ 6.&210Q ai5MQQ
88600 447800 8906600
88600 421900 9328500
88600 395900 9724400
88600 369900 10094300
3.A32QQ
TOTAL 50000 7500000 2953000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.OX TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
10438200
3.53
1.39
6002800
2.03
0.80
-------
Table A-131
ORY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 150 MW EX. COAL FIRED POWER UNIT, 3.0* S IN FUEL, 3.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 2251400
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR *
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16 5000
17 5000
18 5000
19 5000
20 5QQQ_
750000
750000
750000
750000
75QQQO
21 3500 525000
22 3500 525000
23 3500 525000
24 3500 525000
?•> 350Q - - 525OOO
26 1500
27 1500
28 1500
29 1500
•*n i son
225000
225000
225000
225000
225000
296700
296700
296700
296700
226.1Q.Q
207700
207700
207700
207700
-2Q.ZZQQ
89000
89000
89000
89000
890QO
TOTAL 50000 7500000 2967000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10. OX TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
1324800
1293600
1^62300
1231100
J.1922QO.
979700
948500
917200
8B6000
560600
529400
498100
466900
_4.25ZQ.a
13388600
4.51
1.79
7717400
2.60
1.03
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1324800
2618400
3880700
5111800
6.3.11ZQ.Q
7291400
8239900
9157100
10043100
lQfl2I2QQ
11458500
11987900
12486000
12952900
123.aflfi.QQ
-------
Table A-132
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 150 MW EX. COAL FIRED POWER UNIT, 3.0JE S IN FUEL, 4.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 2574200
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER. ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
5
6
7
8
9
11
12
13
14
16 5000
17 5000
18 5000
19 5COO
2Q 5000
21 3500
22 3500
23 3500
24 3500
25 _25QQ
26 1500
27 1500
28 1500
29 1500
30 _ _.150Q ,_
750000
750000
750000
750000
I5QOQQ _ _
525000
525000
525000
525000
225000
225000
225000
225000
225000
298200
298200
298200
298200
22B2.QQ
208700
208700
208700
208700
89500
89500
89500
89500
TOTAL 50000 7500000 2982000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
1604200
1568500
1532800
1497200
14615.QQ
1181300
1145600
1109900
1074200
1023.500
665000
629300
593600
557900
522ZQQ .
16181700
5.43
2.16
9342200
3.13
1.25
1604200
3172700
4705500
6202700
Z&6_42QQ
8845500
9991100
11101000
12175200
13878700
14508000
15101600
15659500
. 16iSlZflfl
rvs
-------
Table A-133
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 250 MW EX. COAL FIRED POWER UNIT, 3.01 S IN FUEL, 1.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 1865600
YEARS
AFTER.
POWER ANNUAL
UNIT OPERATION,
START KW-HR/KW
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER POWER UNIT (NET ANNUAL INCREASE
GENERATION FUEL CONSUMPTION, IN COST OF POWER)
M KWH/YR TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
6
7
e
9
ifl
11
12
13
14
15
16
17
18
19
-2.Q
ai
22
23
24
_2i
26
27
28
29
_lfl
TOT
PRE
5000
5000
5000
5000
5.00Q
3500
3500
3500
3500
3500
1500
1500
1500
1500
1 *^00
1250000
1250000
1250000
1250000
J.2.5QQQQ
875000
875000
875000
875000
&Z5.QQQ
375000
375000
375000
375000
3I5QQQ
489800
489800
489800
489800
4fl2flflQ
342900
342900
342900
342900
34.22QQ
147000
147000
147000
147000
1470.0.0. _
A, 50000 12500000 4898500
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
SENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
966600
940800
914900
889000
a&aiaa
722000
696100
670200
644300
ftiasaa
428400
402500
376600
350800
124."iPQ
9808700
2.00
0.78
5633500
1.15
0.45
966600
1907400
2822300
3711300
4,57.44.0.0.
5296400
5992500
6662700
7307000
iszssaa
8353900
8756400
9133000
9483800
2flflfl2QQ
co
-------
Table A-
DRV LIMESTONE INJECTION, REGULATED POWER CO. ECON., 250 MW EX. COAL FIRED POWER UNIT, 3.0? S IN FUEL, 2.0 INJECTION STOIC HI OMETR Y.
FIXED INVESTMENT: $ 2*98900
YEARS
AFTER
POWER
UNIT
START
1
2
3
4
6
7
e
9
_ifi_
11
12
13
ANNUAL
OPERATION,
KW-HR/KW
POWER
GENERATION
M KHH/YR
POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
t
I\J
ro
1,5
16
17
18
19
21
22
23
24
-Zi_
26
27
28
29
5000 1.750000 492200 1456800 1456800
5000 1250000 492200 1422100 2878900
5000 1250000 492200 1387500 4266400
5000 1250000 492200 1352800 5619200
5QO.Q 1250000 4222QQ 13.1B2QQ 6.2224.00-
3500 875000 344500 1076800 8014200
3500 875000 344500 1042200 9056400
3500 875000 344500 1007500 10063900
3500 875000 344500 972800 11036700
1500 375000 147700 615900 12590800
1500 375000 147700 581300 13172100
1500 375000 147700 546600 13718700
1500 375000 147700 512000 14230700
L5QQ 325000 142200 422200
TOTAL 5000C 12500000 4922000 14708000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED 2.99
EQUIVALENT COST, MILLS PER KILOWATT-HOUR 1.18
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS 8480000
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED 1.72
EQUIVALENT PRESFNT WORTH, MILLS PER KILOWATT-HOUR 0.68
-------
Table A-135
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 250 MW EX. C3AL FIRED POWER UNIT, 3.0* S IN FUEL, 3.0 INJECTION STOICHIOMETRV.
FIXED INVESTMENT: $ 3011*00
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED CUMULATIVE
AFTER ROI FOR POWER COMPANY NET INCREASE
POWER ANNUAL POWER POWER UNIT
-------
Table A-136
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 250 MW EX. C3AL FIRED POWER UNIT, 3.0J S IN FUEL, 4.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 3*93000
YEARS
AFTER
POWER
UNIT
START
ANNUAL POWER
OPERATION, GENERATION
KH-HR/KW M KWH/YR
POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
$
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
6
7
e
9
10
11
12
13
14
15.
16
17
18
19
3D
21
22
23
24
_25_
26
27
28
29
2P
5000
5000
5000
5000
_5CQQ
3500
3500
3500
3500
_3.5QQ
1500
1500
1500
1500
1500
1250000
1250000
1250000
1250000
12j5.QO.aQ
875000
875000
875000
875000
aisQo.0.
375000
375000
375000
375000
31500.0.
497000
497000
497000
497000
_ 421QQQ .
347900
347900
347900
347900
34J2QQ-
149100
149100
149100
149100
149100
2380700
2332200
2283700
2235200
21&6.ZQQ
1743400
1694900
1646300
1597800
__ _15i23.QQ
960100
911600
863100
814600
16.6.1OO
TOTAL 50000 12500000 4970000 23965700
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED 4.82
EQUIVALENT COST, MILLS PER KILOWATT-HOUR 1.92
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS 13863600
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED 2.79
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR 1.11
2380700
4712900
6996600
9231800
_114ia5QQ
13161900
14856800
16503100
18100900
126.5.QZQQ
20610300
21521900
22385000
23199600
2.3.265IQQ
ro
-------
Table A-137
DRY LIMESTONE INJECTION, REGULA1tD POWER CO. ECON., 350 MW EX. COAL FIRED POWER UNIT, 3.0* S IN FUEL, 1.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: t 2238600
ANNUAL OPERATING COST
YEARS
AFTER
POWER. ANNUAL
UNIT OPERATION,
START K.W-HR/KW
1
2
3
4
5
6
7
8
9
10
11
13
14
15
16 5000
17 5000
18 5000
19 5000
PO 50OO
21 3500
22 3500
23 3500
24 3500
s«; 3500
26 1500
27 1500
28 1500
i9 1500
^n 1500
TOTAL 5000C
INCLUDING REGULATED
ROI FOR POWER COMPANY
POxER
GENERATION
M KWH/YR
1750000
1750000
1750000
1750000
115.000.0.
1225000
1225000
1225000
1225000
1225LQO.fl
525000
525000
525000
525000
52500.0
17500000
EQUIVALENT COST, DOLLARS PER TON OF
POWER UNIT INET
FUEL CONSUMPTION, IN
TONS COAL/YR
685600
685800
685800
685800
, , ._ ., 6B5aQQ
480000
480000
480000
480000
AflQQQQ
205700
205700
205700
205700
__20 510.0
6857500
COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0% TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
ANNUAL INCREASE
COST OF POWER)
S
1197900
1166900
1135900
1104800
iaz.3.$.Q.a
890800
859700
828700
797700
26.6.6.0.0.
521700
490700
459600
428600
1216.00
12121000
1.77
0.69
6973000
L.02
0.40
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
t
1197900
2364800
3500700
4605500
56.12300
6570100
7429800
8258500
9056200
28.22&00
10344500
10835200
11294800
11723400
. 12121000
N>
M
--J
-------
Table A-138
DRY tIMESTONE INJECTION, REGULATED POWER CO. ECON., 350 MW EX. C3AL FIRED POWER UNIT, 3.0J S IN FUELt 2.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 3005900
ANNUAL OPERATING COST
YEARS
AFTER
POWER ANNUAL
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KWH/YR
1
2
3
4
6
7
8
9
1O
11
12
13
14
15 _
16 5000
17 5000
18 5000
19 5000
_2.Q 5QQQ
21 3500
22 3500
23 3500
24 3500
25 25QQ
26 1500
27 1500
28 1500
29 1500
30 15.00
TOTAL 50000
EQUIVALENT COST, DOLLARS
1750000
1750000
1750000
1750000
-1Z5QQQQ
1225000
1225000
1225000
1225000
I225fl]0.fl
525000
525000
525000
525000
_52SQQQ_
17500000
PER TON OF
POWER UNIT (NET
FUEL CONSUMPTION, IN
TONS COAL/YR
689100
689100
689100
689100
6S21QQ
482300
482300
482300
482300
4fi23QQ
206700
206700
206700
206700
2.Q6ZQQ
6890500
COAL 8URNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED
EQUIVALENT PRESENT WORTH
EQUIVALENT PRESENT WORTH
AT 10.0*
TO INITIAL YEAR, DOLLARS
, DOLLARS PER TON OF COAL BURNED
, MILLS PER
KILOWATT-HOUR
ANNUAL INCREASE
COST OF POWER)
S
1858900
1817200
1775600
1733900
16922QQ
1369300
1327600
1285900
1244300
12Q26QQ
772200
730500
688300
647100
&Q55.QQ
18751600
2.72
1.07
10824500
1.57
0.62
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1858900
3676100
5451700
7185600
aaziflQQ_
10247100
11574700
12860600
14104900
1520.Z5QQ.
16079700
16810200
17499000
18146100
19. 7.5 16. 0.0
IV)
oo
-------
Table A-139
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 350 MW EX. COAL FIRED POWER UNIT, 3.0* S IN FUEL, 3.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 3676800
ANNUAL OPERATING COST
YEARS
AFTER
POWER ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KWH/YR
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POHERJ
TONS COAL/YR *
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
*
1
2
3
4
5
6
7
8
9
_10
11
12
13
14
16
17
IB
19
~21
22
23
24
25
26
27
28
29
o n
5000
5000
5000
5000
3500
3500
3500
3500
1500-
1500
1500
1500
1500
1500
1750000
1750000
1750000
1750000
1225000
1225000
1225000
1225000
525000
525000
525000
525000
692400
692400
692400
692400
6224.00
484700
484700
484700
484700
_4fl4.1QO
207700
207700
207700
207700
_ 2Q2IQQ _ _
TOTAL 50000 17500000 6924000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
2501700
2450700
2399700
2348700
2222BQQ
1833200
1782200
1731200
1680200
1622200
1010900
959900
908900
857900
806300
25199100
3.64
1.44
14573700
2.10
0.83
2501700
4952400
7352100
9700800
11998600
13831800
15614000
17345200
19025400
21665500
22625400
23534300
24392200
IV)
CO
-------
Table A-
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 350 MW EX. CDAL FIRED POWER UNIT, 3.0* S IN FUEL, 4.0 INJECTION STOIC HIOMETRY.
FIXED INVESTMENT: $ 4262100
YEARS
AFTER
POWER
UNIT
START
ANNUAL
OPERATION,
KW-HR/KW
POWER
GENERATION
M KWH/YR
POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
TOTAL 50000 17500000 6957500 31268000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED 4.49
EQUIVALENT COST, MILLS PER KILOWATT-HOUR 1.79
PRESENT WORTH IF DISCOUNTED AT 10.0? TO INITIAL YEAR, DOLLARS 18110200
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED 2.60
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR 1.03
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1750000 695800 3108900 3108900
1750000 695800 3049800 6158700
1750000 695800 2990700 9149400
1750000 695800 2931600 12081000
ilSflQttfl ___ 625_EQQ ________________ 21Z2.5aQ _______________ 142535Qfl_
1225000 487000 2268900 17222400
1225000 487000 2209800 19432200
1225000 487000 2150700 21582900
1225000 487000 2091600 23674500
U2.5.00Q ____ ifizaaa --------------- 2.fl3.250.Q _________________ 25IQZflflC.
525000 208700 1230400 26937400
525000 208700 1171300 28108700
525000 208700 1112200 29220900
525000 208700 1053100 30274000
525QQQ _______ 2CfilQQ ________________ 224.QQQ
ro
U)
o
-------
Table A-lUl
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 50 MW EX. COAL FIRED POWER UNITt 5.0? S IN FUELi 1.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: * 995300
YEARS
AFTER
POWER. ANNUAL
UNIT OPERATION,
START KW-HR/KW
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16 5000
17 5000
16 5000
19 5000
2_U 5.0QQ
21 3500
22 3500
23 3500
24 3500
2_5 35QQ
26 1500
27 1500
28 1500
29 1500
an 1 5DQ
jV_i^^ . — _ Jh^MVi —
TOTAL 50000
POWER
GENERATION
M KWH/YR
250000
250000
250000
250000
25.UO.aQ
175000
175000
175000
175000
H5J}Q,Q
75000
75000
75000
75000
15.fl.UO.
2500000
EQUIVALENT COST, DOLLARS PER TON OF
POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR
98300
98300
98300
98300
2S3.UU .
68800
68800
68800
68800
_&.aauu
29500
29500
29500
29500
_225J1U_ _
983000
COAL BURNED
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
$
502600
488800
475000
461200
. iiiiOQ
361000
367200
353300
339500
_3252fla__
233700
219900
Z06100
192300
liaSUQ .
5172200
5.26
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
502600
991400
1466400
1927600
2.225.UUQ.
2756000
3123200
3476500
3816000
ilillflfl
4375400
4595300
4801400
4993700
_ 51.1220.0_
EQUIVALENT COST, MILLS PER KILOWATT-HOUR 2.07
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS 2953500
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED 3.00
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR 1.18
ro
u>
-------
Table A-1U2
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 50 MW EX. COAL FIRED POWER UNIT, 5.0? S IN FUEL, 2.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: * 1332900
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER. ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
6
7
8
9
Ifl
11
12
13
14
15
16 5000
17 5000
18 5000
19 5000
_2,Q _____5QQQ
21 3500
22 3500
23 3500
24 3500
25 35QO
26 1500
27 1500
28 1500
29 1500
30 1500
250000
250000
250000
250000
._2SQflQfl_
175000
175000
175000
175000
1T5QOQ -r- _
75000
75000
75000
75000
15QQO_
99100
99100
99100
99100
2210.0.
69400
69400
69400
69400
6.240.0.
29700
29700
29700
29700
297.00.
TOTAL 50000 2500000 991000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0? TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
707500
689100
670600
652100
. 613.6J)0.
530600
512100
493600
475100
4566.Qfl
316600
298100
279600
261200
242.1QQ
7219100
7.28
2.89
4139200
4.18
1.66
707500
1396600
2067200
2719300
3_a5_22QQ
3883500
4395600
4889200
5364300
-5.8.209.0.Q
6137500
6435600
6715200
6976400
7.219J.QJ)
oo
-------
Table A-1^3
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 50 MW EX. COAL FIRED POWER UNIT, 5.0* S IK FUEL, 3.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: t 1602600
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POhER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UMT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR $
1
2
3
4
5
6
7
8
9
10
11
12
13
15
16 5000
17 5000
18 5000
19 5000
20 5000
21 3500
22 3500
23 3500
24 3500
26 1500
27 1500
28 1500
29 1500
3.Q 1 ?Q°
250000 99900
250000 99900
250000 9990C
250000 99900
25QflQfl _222Qfl
175000 69900
175000 69900
175000 69900
175000 69900
75000 30000
75000 30000
75000 30000
75000 30000
75J3QQ 3QQQQ
TOTAL 50000 2500000 999000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10. OS TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
892400
870200
848000
825800
665000
642800
620500
598300
576100 .
389300
367100
344900
322700
9067100
9.08
3.63
5211300
5.22
2.08
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
892400
1762600
2610600
3436400
ft2.itQQ.SlQ
4905000
5547800
6168300
6766600
73_42_ZQQ
7732000
8099100
8444000
8766700
2Q6.11QQ
LO
00
-------
Table A-lM
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 50 MM EX. COAL FIRED POWER UNIT, 5-0* S IN FUEL, 4.0 INJECTION STOICHIOMETRY,
FIXED INVESTMENT: $ 1838700
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER. ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR $
1
2
3
4
5
6
7
8
9
10
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
S
11
12
13
14
15
16 5000
17 5000
18 5000
19 5000
£0 _5QQQ
21 3500
22 3500
23 3500
24 3500
2.5 _25QQ_
26 1500
27 1500
28 1500
29 1500
1Q 1500
250000
250000
250000
250000
iSflCOQ-
175000
175000
175000
175000
1TSO.OO
75000
75000
75000
75000
25QQQ
100700
100700
100700
100700
1UQ1QQ
70500
70500
70500
70500
2Q5QQ_ _
30200
30200
30200
30200
302QQ
TOTAL 50000 2500000 1007000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0? TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
1068700
1043200
1017700
992200
S6&1QQ
792900
767400
741900
716400
6.2Q2QQ
457500
432000
406500
3BIOOO
laasoa
10830500
10.76
4.33
6235100
6.19
2.49
1068700
2111900
3129600
4121800
SflflflSafl
5881400
6646800
7390700
8107100
BiaaoflQ
9255500
9687500
10094000
10475000
10.13.05.00.
a>
-------
Table A-
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 150 MW EX. COAL FIRED POWER UNIT, 5.0* S IN FUEL, 1.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 1736200
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR t
1
2
3
4
5
6
7
8
9
10
11
12
13
14
J-5
16 5000
17 5000
18 5000
19 5000
2Q 5QQQ
21 3500
22 3500
23 3500
24 3500
25 35DQ
26 1500
27 1500
28 1500
29 1500
•*n 1 "5DQ
750000 294800
750000 294800
750000 294800
750000 294800
»i5£oaa_ zaifiQQ.
525000 206400
525000 206400
525000 206400
525000 206400
525QQQ_ ZQfiiHQ
225000 88500
225000 88500
2Z5000 88500
225000 88500
?25000 flflSQQ
TOTAL 50000 7500000 2948500
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10. OX TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
928000
904000
879900
855800
__ aaiaaa
692600
668500
644500
620400
52&3.QQ .
408500
384400
360300
336300
3JL220.Q
9423500
3.20
1.26
5413800
1.84
0.72
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
928000
1832000
2711900
3567700
4.2225QQ_
5092100
5760600
6405100
7025500
-Z&ZlflQD
8030300
8414700
8775000
9111300
24225QQ
ro
co
en
-------
Table A-lU6
DRY LIMESTONE INJECTION, REGULATED POwER CO. ECON., 150 MW EX. COAL FIREO POWER UNIT, 5.OX S IN FUEL, 2.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 2369500
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER RQI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/Kri M K.WH/YR TONS COAL/YR $
1
3
4
5.
6
7
8
9
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
11
12
13
14
16
17
1«
19
21
22
23
24
26
27
28
29
30
5000
DOOO
5000
5000
3500
3500
3500
3500
1500
1500
1500
1500
1500
750000
750000
750000
750000
525000
525000
525000
525000
225000
225000
225000
225000
225-Q.Oi)
^7200
297200
297200
297200
208100
208100
208100
208100
89200
89200
89200
89200
&32SQ
TOTAL 50000 7500000 2972500
EQUIVALENT COST, DOLLARS PER TON OF COAL UURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PKtSFNT WHRTH, COLLARS PER TON OF COAL BORNEO
EQUIVALENT PKtStNT WORTH, rtlLLS PER KILOWATT-HOUR
1420300
1387400
1354500
1321700
1048700
1015900
983000
950100
596500
563700
530800
497900
14341700
4.82
1.91
8271800
2.78
1.10
1420300
2807700
4162200
5483900
&112.13S
7821400
8837300
9820300
10770400
llfcfillQQ
12284200
12847900
13378700
13876600
r
ro
GO
01
-------
Table A-1^7
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 150 MW EX. COAL FIRED POWER UNIT, 5.0* S IN FUEL, 3.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: t 2926600
YEARS
AFTER
POWER ANNUAL
UNIT OPERATION,
START KW-HR/Kw
POWER
u,ENERAT ION
M KrtH/YR
POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
$
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
1
2
3
4
6
7
8
9
11
12
13
14
1,5
16 5000
17 5000
18 5000
19 5000
2fl 5.J20J2
21 3500
22 3500
23 3bOO
24 3500
2i_ 3.5_iJO_
26 1500
27 1500
28 1500
29 1500
30 1..5.0.0.
750000
750000
750000
750000
Z5.flQ.ilO.
525000
525000
525000
525000
5.25.0.00.
225000
225000
225000
225000
22520.0.
299700
299700
299700
299700
_ 222iQfl
209800
209800
209800
209800
_2 0230.0.
89900
89900
89900
89900
89900.
1914300
1873800
1833200
1792600
1Z.52.QP_Q
1406500
1365900
1325400
1284800
783400
742800
702300
661700
TOTAL 50000 7500000 2997000 19304000
EQUIVALENT CUST, DOLLARS PF.R TON CF COAL BURNED 6.44
EQUIVALENT CCST, MILLS PER KI LOwATT-HUUR 2.57
PRESENT «ORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS 11153800
EgUIVAL^NT PKtSFNT WURTH, DOLLARS PER TON OF CGAL BURNED 3.72
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR 1.49
1914300
3788100
5621300
7413900
10572400
11938300
13263700
14548500
16576100
17318900
18021200
18682900
._ _ 123.0.4.0.QQ
1\D
00
-------
Table A-
DKY LIMESTONE INJECTION, REGULATEJ POWER CO. ECON., 150 MW EX. COAL FIAED POWER UNIT, 5.0? S IS FUEL, 4.0 INJECTION STDICHIOMETRY.
FIXED INVESTMENT: $ 3376200
YEARS
AFTER.
PUrtER. ANNUAL
L.N1T OPERATION,
START KW-HR/KW
i
2
4
0
7
ANNUAL OPERATING COST
INCLUDING REGULATED
KOI FOR POWER COMPANY
POWER POWER UNIT (NET ANNUAL INCREASE
GENERATION FUEL CONSUMPTION, IN COST OF POWER)
M KWH/YR TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
I
9
"ll"
13
16 5COO
i7 5000
16 5000
19 5000
20. SflQH
21 3500
2^ 35CC
23 3500
^4 3500
26 1500
27 1500
2o 1500
^9 1500
10 1,500
750000
750000
750000
750000
Z5Q.Q.Q.Q
525000
525000
525000
525000
225000
225000
225000
225000
302100
302100
302100
302100
.3.0.20.20.
211500
211500
211500
211500
211500.
90600
90600
90600
90600
TbTAL 50000 7500000 3021000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PkESENT *ORTH IF DISCOUNTED AT 10.02 TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
tUUlVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
2362800
2316000
2269200
2222400
_ 2J.156.Q.Q
1728700
1681900
1635100
1588300
946900
900100
853300
806500
23788000
7.87
3.17
13765400
4.56
1.84
2362800
4678800
6948000
9170400
113.463.23
13074700
14756600
46391700
17980000
20468400
21368500
22221800
23028300
OJ
00
-------
Table A-
DRY LIMESTOME INJECTION, REGULATED POWER CO. ECON., 250 MW EX. COAL FIRED POWER UNITt 5.0% S IN FUELt 1.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 2314500
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED CUMULATIVE
AFTER ROI FOR POWER COMPANY NET INCREASE
POWFR ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE IN COST OF
UNIT JPERATIOIM, GENERATION FUEL CONSUMPTION, IN COST OF POWER) POWER,
START KW-HR/KW M KWH/YR TONS COAL/YR , $ $
1
2
3
4
__5
6
7
8
9
JU)
11
12
13
14
16
17
18
19
2fl
21
22
23
24
25
26
27
28
29
30
5000
5000
5000
5000
3500
3500
3500
3500
^.^.il^l
1500
1500
1500
1500
15ilil
1250000
1250000
1250000
1250000
875000
375000
d75000
875000
375000
375000
375000
375000
491400
491400
491400
491400
_ 4214Q12
344000
344000
344000
344000
147400
147400
147400
147400
TOTAL 50000 12500000 4914000
EQUIVALENT CUST, DOLLAKS PER TON OF COAL BURNED
EQUIVALENT COST, HILLS PER KILOWATT-HOUR
PRESENT MIRTH IF DISCOUNTED AT 10.0% TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EOUIVALFNT PKESENT WORTH, HILLS PER KILOWATT-HOUR
1301100
1269000
1236900
1204800
JLLlZZSfl
964400
932300
900300
86S200
557500
525400
493300
461200
13152300
2.68
1.05
7575100
1 .54
0.61
1301100
2570100
3807000
5011800
7148900
8081200
8981500
9849700
11243300
11768700
12262000
12723200
co
10
-------
Table A-150
DRY LIMESTONE 1NJECMON, REGULATED POWER CO. ECON., 250 Md EX. COAL FIREO POWER UNIT, 5.0* S IN FUEL, 2.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 3221100
ANNUAL OPERATING COST
YEAKS
AFTFR
INCLUDING REGULATED
ROI FOK POWER COMPANY
POWER ANNUAL
UNIT OPERATION,
START K,
1
2
3
4
5 __
6
7
a
9
ifl —
11
12
13
_15 _
16
17
18
19
20
21
22
23
24
Z5
26
27
28
29
_3Q
TOTAL 5
EQUIVALENT
tgulVALENT
PRESENT v»i.UTH
EQUIVALENT
EQUIVALENT
i-HK/Kri
5000
5000
5000
5000
*t££3.
3500
3500
3500
3500
JiSilii
1500
15uO
1500
1500
liUii
0000
cusr, u
CHST, v,
POWER
GENERATION
M KWH/YR
1250000
1250000
1250000
1250000
Ii.ii20.li
875000
875000
875000
875000
iii5jiiii
375000
375000
375000
375000
ili^iiii _
12500000
DLLARS PER TON OF
POwER UNIT (NET
FUEL CONSUMPTION, [N
TONS COAL/YR
495400
495400
495400
495400
_4.9..5.4.Qi!
346800
346800
346800
346800
_ liJifiail
148600
148600
146600
14S600
1466QO
4954000
COAL BURNED
ILLS PER KILOwATT-HOUR
IF DISCJUI.TtU AT 10. OS
PhLSENT
PRbSHNT
TO INITIAL YEAR, DOLLARS
nURTh, DOLLARS PER TON OF COAL BURNED
WORTH, MILLS PER
KILOWATT-HOUR
ANNUAL INCREASE
COST OF POWER!
$
2095700
2051000
2006400
1961700
J.91710Q
1539000
1494300
1449700
1405000
JJi£0_4.i)0_
857000
812400
767700
723000
678400
21118800
4.26
1.69
12204500
2.46
0.98
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
2095700
4146700
6153100
8114800
1QQ212QQ
11570900
13065200
14514900
15919900
172SQ3DQ
18137300
18949700
19717400
20440400
21 i i 8800
ro
-ti
o
-------
Table A-151
DRY LIMESTONE. INJECTION, REGULATED PO«ER CO. ECON., 250 Mw EX. COAL FIRED POWER UNIT, 5.0* S IN FUEL, 3.0 INJECTION STOICHIOMETRY.
FIXFD INVESTMENT: $ 3968400
YEARS
AFTER
P0.it R
UNIT
START
1
2
3
4
6
7
8
9
LO
11
12
13
16
17
18
19
21
22
23
24
26
27
28
29
TOTAL
L'JUl
tjU I
PRESENT
ANNUAL
o°FKATini-;,
K.W-HI-./KW
5000
50 JO
5000
5JUJ
j500
3500
3500
j500
1 500
15JO
1500
I SOU
5 0 0 0 ~j
VALFNT CuST, DC
VALi-.\T C'JST, M
W )KTM U DliCO
EQUIVALENT P-'.LS'.\T
VALi:.\iT Pi-K SFM
POrtER
GENERATION
M KwH/YR
1250000
1250000
1250000
123000J
875000
675000
875000
875000
375000
375000
375000
375000
1250JOOO
LLA°S PER TJN
LLS PEK KILGnA
U "1 T t 0 AT 10.0
AJRTH, OGLL^SS
nJHTH, •I ILLS P
PQwER UNIT
FUEL CONSUMPTION,
TONS CCJAL/YR
499400
499400
499400
499400
349600
349600
349600
349600
149dOO
149aGO
149800
149&00
4994000
OF CJAL HUKNFO
TT-H'JU^
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
$
2838200
2783200
2728200
2673100
2072 300
2017300
1962300
1907200
1127100
1072000
1017000
961900
28537000
5. 71
2. 29
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
2838200
5621400
8349600
11022700
15713100
17730400
19692700
21599900
24579200
25651200
26668200
27630100
S. TO INITIAL YEAR, DOLLARS 16526400
PER TON iJF COAL RURNEO
EK KIL'.lwATT-riOUR
3.31
1.32
N>
-------
Table A-152
DRY LIMESTUN^ INJECTION, REGULATED POrtER CO. ECON., 250 MW EX. COAL FIRED POWER UNIT, 5.0? S IN FUEL, 4.0 INJECTION STOICHIOHETRY.
FIXED INVESTMENT: $ 4582000
ANNUAL OPERATING COST
YEARS
AFTER
PO*ER
UNIT
START
1
2
3
4
5.
6
7
8
9
ID
11
12
13
15
16
17
18
19
22
21
22
23
24
25
26
27
28
29
3J.
TOTAL
INCLUDING REGULATED
ANNUAL
UPbRATIOM,
Krt-HR/Kw
5000
5000
5000
5000
Siiiiii
3500
35CO
3500
3500
A^.Q.11
1500
1500
150o
1500
liiiii
5^u0
EQUIVALENT Ct.ST, U(
EUUI VAL
PRESENT M.I
FOUIVAL
C 0 U 1 V A L
POWER
oENERAT ION
M KrtH/YR
1250000
1250000
1250300
1250000
125222.2
875000
375000
875000
875000
.8.25222
375000
375000
375000
375000
3 75QQO
12500000
ROI
FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN
TONS COAL/YR
503500
503500
503500
503500
50350Q
352500
352500
352500
352500
iiZiuil
151100
151100
151100
151100
151122
5035500
"iLLARS PER TON OF COAL BURNED
F.NT CiiST, MILLS PER KILOHlAT
i
-------
Table A-153
DRY LIMESTONE INJECTION, REGULATED POWER CO. FCON., 350 MW EX. COAL FIRED POWER UNIT, 5.0? S IN FUEL, 1.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 2782700
ANNUAL OPERATING COST
YEARS
AFTER
POWER
UNIT
START
1
2
3
4
6
7
8
9
11
12
13
16
17
18
19
20
21
22
23
24
26
27
28
29
TOTAL
EQL1
L JUI
PREStM
PQUl
LiJUl
INCLUDING REGULATED
ROI FOR POWER COMPANY
ANNUAL
OPERATION,
K*-Hk/K*
5000
5000
5300
5000
iilsii! *.
3500
35'OU
« Sou
Jpu
1500
1500
1500
;^j'
50000
VALFNf Ci ST , Di
VALHM C:-!-'»T
TO INITIAL YEAS, DOLLARS
K.JRTH, !>JLLARS PER TUN OF COAL bURNtO
rt'.jpTh, MILLS PER
KILOwATT-HOUR
NET ANNUAL INCREASE
IN COST OF POWER)
$
1639600
1601000
1562400
1523800
L^L&5.£.Q.Q.
1209900
1171300
1132700
1094100
688800
650200
611600
573000
16533600
2.40
0.94
9538500
1.39
0.55
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1639600
3240600
4803000
6326800
- _ laiZlflfl
9022000
10193300
11326000
12420100
14164400
14814600
15426200
15999200
r
IV)
00
-------
Table A-15U
ORV LlMESTGl\iF INJECTl-d\, REGULATED POWER CO. ECON., 350 Mrf EX. COAL FIRED POWER UNIT, 5.03! S IN FUEL, 2.0 INJECTION STOICHIOMETRY.
FIXEO INVESTMENT: $ 3927000
YEARS
AFTER
POWER ANNUAL P'JWFR
UNIT OPERATION, GENERATION
START Kn-HR/KW M KiriH/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION', IN COST OF POWER)
TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
6
7
e
9
11
12
13
15. __
16
17
18
19
21
22
23
24
26
28
29
5000
5000
5000
5000
3500
3500
3500
3500
1500
1500
1500
1500
liUil
1750000
1750000
1750000
1750000
1225000
1225000
1225000
1225000
525000
525000
525000
525000
iZSjJOO
69 3 60 0
693600
693600
693600
485500
485500
485500
485500
2C8100
208100
208100
208100
TOTAL 50000 17500000 6936000
EQUIVALENT GUST, DOLLARS PER TUN OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.02 TO INITIAL YEAR, DOLLARS
EQUIVALENT PREScMT wOKTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
2714000
2659600
2605100
2550700
1984700
1930300
1875800
1821400
1I662.Q.Q. _
1087300
1032800
978400
923900
27296600
3.94
1.56
15799300
2.28
0.90
2714000
5373600
7978700
10529400
15010300
16940600
18816400
20637800
23492000
24524800
25503200
26427100
2122660.0_
-------
Table A-155
DRY LIMESTCM- INJECTION, REGULATED POWER CO. ECON., 350 NU EX. COAL FIRED POWER UNIT, 5.0? S IN FUEL, 3.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: $ 4766400
YEARS
AFTER
POWER ANNUAL
UNIT OPERATION
START K'rt-HP/Kn
1
2
3
4
-5.
6
7
9
10 _
11
12
13
16 5JOO
17 5JOJ
18 50UO
19 ?JuU
2fl iUGy
21 J50U
22 J5UO
23 j5>jo
24 35UO
25 3-5. 00
26 l^OU
27 1500
28 15JU
29 15Ju
TUTAL 'jOOOO
EQUIVALENT CuST,
EQUIVALENT COST,
POWER
, GENT RAT I ON
M KrtH/YR
1750000
1750000
1 750000
1 750JOO
llidiilifl _
1225000
1225000
1225000
1225000
IZZSiiiia _
525000
525JOO
525000
525000
1 75JOOOO
DOLLARS PER TON GF-
POWER UNIT
FUFL CONSUMPTION
TONS COAL/YR
699200
699200
699200
699200
69V200
489400
489400
489400
469400
4-&24.^Q
209300
209800
209800
209800
6992000
COAL BURNED
M1LLS PER KI LOrtATT-HOUR
PRESENT wOKTn IF DISCOUNTED AT 10. (H
EQUIVALENT PRl-Sh
tuU IVAL EM P.-!:-S !•
TO INITIAL YEAR, D'.
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
, IN COST OF POWER)
$
3691200
3625100
3559000
3492900
34,26.800
2685700
2619600
2553500
2487400
24.Z.1.3..0..Q
1437000
1370900
1304800
1238700
37086500
5.30
2.12
1LLARS 21504200
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
3691200
7316300
10875300
14368200
-UJSiJiJi)
20480700
23100300
25653800
28141200
•3.Q.5.&2.500
31999500
33370400
34675200
35913900
NT m.iRTH, DOLLARS PER TON OF COAL bURNEL) 3.08
NT nijivTH, MILLS PFR
KILOWATT-HOUR
1.23
r
ro
en
-------
Table A-156
DRY Ll'-ttSTLJNb i ,MJ EOT 10i\, REGULATED POWER CO. ECON., 350 MW fcX. COAL FIRED POWER UNIT, 5.0? S IN FUEL, 4.0 INJECTION STOICHIOMETRY.
FIXED INVESTMENT: t 5645500
ANNUAL OPERATING COST
YEAKS
AFTFK
POwER ANNUAL
UNIT OPERATION
STAKT K'4 — Hri/KW
1
2
3
-5. _
6
7
9
11
13
16 5000
17 5000
18 500U
19 5000
20 3QQO
21 J.50U
22 3500
23 J500
24 J500
25 -i5.flii
26 1500
n isuo
28 1500
29 15uO
.3J1 15iii)
TOTAL 50000
EQUIVALENT COST,
EQUIVALENT CuST,
PRESENT h,jiTH IF 01
EQUIVALENT PRbSi-
EQUIVALKNT PKi.-SH
INCLUDING REGULATED
POWE*
, GENERATION
M KWH/YR
1750000
1 750000
1750000
1750000
l.Z5.Qj2i}iJ
1225000
1225000
1225000
1225000
iZZiJiiv
525000
525000
525000
525000
525.0..Q.Q
17500000
DOLLARS PER TON OF
R(.!
POWER UNIT (
FUEL CONSUMPTION,
TONS COAL/YK
705000
705000
705000
705000
.ZU50_^0_
493500
493500
493500
493500
493500
211500
211500
211500
211500
2115242
7050000
COAL BURNEO
i-tlLLS PER KILOWATT-HOUR
SC(JUNTliD AT 10.0*
TO INITIAL YEAR, DOLLARS
NT KlmTH, DOLLARS PER TON OF CUAL BURNED
NT wDRTH, MILLS PER
KILOWATT-HOUR
I FOI< POWER COMPANY
NET ANNUAL INCREASE
IN COST OF POWER)
t
4708000
4629700
4551400
4473100
4394800
3416000
3337700
3259400
3181100
3102800
1802000
1723700
1645400
1567100
1488800
47281000
6.71
2.70
27443100
3.89
1.57
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
4708000
9337700
13889100
18362200
22 75 7000
26173000
29510700
32770100
35951200
39054000
40856000
42579700
44225100
45792200
472Q 1QQQ
ro
•P»
01
-------
L-247
I. Title and Subtitle
^itU'ur Oxide Removal from Power Plant Stack Gas by Dry
Limestone Injection--Full Scale Demonstration and Support
Projects (Volumes T; TTJ and ITT) ;
'. Autlior(s)
F. E. Gartrell
BIBLIOGRAPHIC DATA
SHEET
1. Id-port No,
EPA-650/2-73-019-a, -b, -c
3. Recipient's Accession No.
5. Report Date
August 1973
6.
8- Performing Organization Kept.
No.
9. Performing Organisation Name and Address
Tennessee Valley Authority
Chattanooga, Tennessee 37401
10. Project/Task/Work Unit No.
11. Contract/Grant No.
iiteragency Agreement
TV-30541A
12. Sponsoring Organization Name and Address
EPA, Office of Research and Development
NERC-RTP, Control Systems Laboratory
Research Triangle Park, North Carolina 27711
13. Type of Report & Period
Covered
Final
14.
15. Supplementary Notes
16. Abstracts ,pne repOrt gives results of a test program of dry limestone injection,
demonstrated on a 150-Mw pulverized-coal-fired boiler at TVA's Shawnee Plant. The
program included: equipment shakedown, dust distribution studies, process optimi-
zation, and long-term injection trials. It identified major process variables; evaluated
distribution of lime dust in the boiler, effect of operating variables on distribution,
and resulting effects on SO2 removal; evaluated the sensitivity of SO2 removal to key
operating and process variables; evaluated conditions for optimum SO2 removal;
studied process effects on boiler operation and maintenance, on solids collection
equipment, and on water quality; and completed a process economics study. The pro-
gram is discussed in context with previous investigations and EPA-sponsored sup-
port activities. Appendices contain test program detail results and results of EPA
support projects. Because of low SO2 removal efficiencies and the potential for major
reliability problems , it does not appear
that dry limestone injection will play an
important role in controlling SO2 emis-
sions from power plants.
17. Key Words and Document Analysis. 17o. Descriptors
Air Pollution
Coal
Desulfurization
Limestone
Boiler
Dust
Sulfur Dioxide
Calcium Oxides
Economic Analysis
17b. Identifiers/Open-Ended Terms
Air Pollution Control
Stationary Sources
Dry Limestone Injection
17c. COSATI Field/Group 13B, 14A
Reliability
Electric Power Plants
Flue Gases
18. Availability Statement
Unlimited
19.. Security Cla.'is (This
Report)
20. Security (,lass (This
Page
UNCI.ASSII-MKO
21. No. of Pages
356
22. Price
KO«M NTIS-35 IRtV. 3-/2)
USCOMM-OC 14952-P72
------- | |