EPA-650/2-73-019-C
 August 1973          ENVIRONMENTAL PROTECTION TECHNOLOGY SERIES
i||||l^
1^
                             iiliii ill iiii 11 ;iiiiiiiiiiiii


-------
                                       EPA-650/2-73-019-C
                 FULL-SCALE


DESULFURIZATION  OF  STACK  GAS


  BY  DRY  LIMESTONE  INJECTION


                  VOLUME  III  -

           APPENDICES  I  THROUGH  L

                        by
                 Tennessee Valley Authority
                  Chattanooga, Tennessee

               Interagency Agreement TV-30541A

               Project Officer: Richard D. Stern
                 Control Systems Laboratory
             National Environmental Research Center
               Research Triangle Park, NC 27711

         TVA Contracting Officer: Dr. F. E. Gartrell, Director
               Division of Environmental Planning
                 Tennessee Valley Authority
                  Chattanooga, TN 37401

                     Prepared for
              Office of Research and Development
             U.S. Environmental Protection Agency
                  Washington, DC 20460

                     August 1973

-------
This report has been reviewed by the Environmental Protection Agency and




approved for publication.  Approval does not signify that the contents




necessarily reflect the views and policies of the Agency, nor does




mention of  trade names or commercial products constitute endorsement




or recommendation for use .

-------
                                    CONTENTS

                                     Volume 1

                                     Main Text

                                                                               Page
Abstract	    v

List of Figures  	  xiii

List of Tables	  xix

Acknowledgement	  xxi

Summary and Conclusions  	    1

Introduction  	   21

Test Program	   31

    A. Objectives and Overall Approach	   31
    B. Test Facility	   32

       1.  Unit 10 Boiler   	   32
       2.  Limestone Injection Process Equipment	   32
       3.  Sampling Stations  	   40
       4.  Laboratory Capability	   41

    C. Phase I Shakedown	   43

       1.  Objectives	   43
       2.  Approach  	   43
       3.  Results	   46
       4.  Conclusions	   77

    D. Phase II Dust Distribution Studies  	   79

       1.  Objectives	   79
       2.  Approach  	   79
       3.  Results	   79
       4.  Conclusions	104

    E. Phase III  Process Optimization  	Ill

       1.  Objectives	Ill
       2.  Approach  	Ill
       3.  Results	119
       4.  Conclusions	164

    F. Phase IV  Long-Term Operation	171

       1.  Objectives	171
       2.  Approach  	171
       3.  Test Results	174
       4.  Conclusions	198

-------
                               CONTENTS

                                Volume 2

                                                                     Page

APPENDIX A-STATISTICS ON BOILER AND LIMESTONE SYSTEM  	A-l

APPENDIX B-WATER-COOLED PROBE DEVELOPMENT	B'1

APPENDIX C-TESTING, SAMPLING, AND ANALYTICAL PROCEDURES	C-l

APPENDIX D-COMPUTER PRINTOUTS FOR PHASE I TESTS  	D-4

APPENDIX E-INSTANTANEOUS DUST DISTRIBUTION STUDIES  	E-l

APPENDIX F-LIMESTONE INJECTION EFFECTS ON SOLIDS
COLLECTION SYSTEM  	F-l

        Report and Analysis of Field Tests at Shawnee Station Prepared
        for the EPA by Cottrell Environmental Systems, Inc.

APPENDIX G-LIMESTONE INJECTION EFFECTS ON DISPOSAL
WATER QUALITY  	G-l

        Introduction  	G-l
        Evaluation Program	G-2
        Summary and Conclusions	G-31
        Data Storage Format  	G-35

APPENDIX H-ADDITIONAL HEAT REQUIREMENT CALCULATIONS	H-l

-------
                                    CONTENTS

                                      Volume 3

                                                                                Page

APPENDIX I-LIMESTONE FACTORS

Section A,  Reactivity with Sulfur Oxides	1-3

       I. Introduction and Objectives	1-3

      II. Approach	1-3

     III. Results and  Conclusions  	1-4

             Limestone Type  	1-4
             Chemical  Form of the Additive	1-4
             Particle Sife	1-5
             Calcination Temperature  	1-5
             Catalysts   	1-5

     IV. Abstracted Results of Individual Projects   	1-6

             Illinois State Geological Survey  	1-6
             Tennessee Valley Authority  	1-6
             Babcock & Wilcox	1-8
             Peabody Coal Company	1-8
             In-House  EPA   	1-9

      V. Recommendation on Limestone Properties for Application
        to the Dry Limestone Injection  Process  	1-11

Section B,  Limestone Availability in the  United States	1-13

       I. Introduction and Objectives	1-13

      II. Approach	1-13

     III. Results	1-13

             Potential  Demand - Power Plants	1-13
             Carbonate Rock Reserves	1-16
             Mining and Production  	1-19

     IV. Supply/Demand Relationship of Carbonate Rocks
        for Pollution Control	1-22

             Proximity of Carbonate Rock Deposits to Power Plants  	1-22
             Potential  Demand Relative  to Production	1-22
             Costs	1-23

      V. Conclusions   	1-31

-------
                                      Volume 3
                                      (Continued)

                                                                              Page


      VI. Recommendation for Application to Dry Limestone
         Injection and other Limestone-Based Processes	

 Section C, Definitions	

                                                                               1-35
 Section D, References	

 APPENDIX  J-MATHEMATICAL  MODELING  OF THE  LIMESTONE  INJECTION
                PROCESS

       I. Introduction and Objectives	J'3

      II. Summary of Modeling Activities  	t	J'5

      III. Discussion  	J'23

      IV. Conclusions  	J-26

      V. References	J-27

 APPENDIX K-UTILIZATION OF LIMESTONE-MODIFIED FLY ASH   	K-l

       I. Introduction and Objectives	K-3

      II. Approach	K-3

     III. Results and Conclusions  	K-3

            A.  Unmodified Fly Ash Utilization   	K-3
            B.  Limestone-Modified Fly Ash Utilization	K-12

     IV. Summary	K-19

      V. Recommendations  	K-19

            A.  Unmodified Fly Ash  	K-20
            B.  Wet-Collected Limestone-Modified Fly Ash	K-21

     VI. References	K-22

APPENDIX L-PROCESS ECONOMICS

      I. Introduction	L-l

            Design Premises   	|__2
            Base Case  	l_.j 1
            Actual Investment	L-13
            Investment Projections   	L-13
            Annual Operating  Cost   	  L-18
            Lifetime Operating Cost	  L-24

-------
                                 Volume 3
                                (Continued)

                                                                            Page

 II. Summary of Results and Conclusions	L-27

        Investment	L-27
        Relative Investment Cost Distribution	L-27
        Annual Operating Cost   	L-32
        Relative Operating Cost Distribution   	L-36
        Lifetime Operating Cost	L-36
        Results of Sensitivity  Analysis  	L-59

III. References and Abstracts	L-88

-------
                               CONVERSION TABLE

        EPA policy is to express all  measurements in Agency documents in metric units.
When implementing this policy  results in undue cost or difficulty in clarity, the National
Environmental  Research  Center-Research  Triangle  Park (NERC-RTP) provides  conversion
factors for the  particular nonmetric  units  used in  the document.  For  this report these
factors are:

     British                                                       Metric
Multiply                            By                        To Obtain
feet                                 3.0480 x 10"1             meters
feet2                                9.29 x 10'2               meters2
feet/sec.                             3.0480 x 10"1             feet/sec.
feet3/min.                          4.720 x 10"1               liters/sec.
grains (troy)                         6.48 x 10~2               grams
grains/dry s.c.f. @ 70° F              2.464                     grams/meter3 @ 0° C
gallon                               3.785                     liters
inch                                2.5400 x 10'2             meters
micron                              l.OxlO"6                 meters
ounce (troy)                         3.1103 x 10'               grams
pound                              4.536 x 10~J               kilograms
pound/in.2                          7.03 x 10"2               kg/cm2
quart                               9.463 x 10"1               liters
tons/hr.                             2.520 x 10"1               kg/sec.

-------
                  APPENDIX I
               Limestone Factors
Section A     Reactivity with Sulfur Oxides
Section B     Availability in the United States
Section C     Definitions
Section D     References

-------
                                        1-1

                                    APPENDIX I
                               LIMESTONE FACTORS
       The  author  discusses those  factors which experimentation  identified  as  most
important to the  process. These include limestone type, chemical form  of the  additive,
particle size, calcination temperature, and the effects of catalysts.
       Discussed are the activities of the following organizations:
                            Illinois State Geological Survey
                            Tennessee Valley Authority
                            Babcock & Wilcox
                            Peabody Coal Company
                            Environmental Protection Agency
       Included are  recommendations for additive preparation  for  the  dry  limestone
injection process.
       Regarding  availability, the author discusses the potential demand for limestone, its
distribution, mining, and production as well as the supply/demand relationship of carbonate
rocks for pollution control.
       Transportation and costs for limestone use at power plants are covered.
       Recommendations  for  application   to   dry  limestone  injection  and  other
limestone-based  processes indicate  the use  of the available  information for study by a
potential user.

-------
                                         1-3

                                      Section A
                             Reactivity with Sulfur Oxides

I.  Introduction and Objectives
       The activities of  the  Research Laboratory  Branch, Control  Systems Division in
support of  the  high  priority development of  throw-away  processes, have been directed
toward specific areas  relating to the limestone processes.  During the last 2-1/2 years major
emphasis has been on acquiring  information on the dry  injection process  which would be
required for application of the process on a wide scale. Earlier, a little was known about the
mechanism  and  rate of  reaction between limestone and  sulfur oxides,  and differences
between limestones had not been related to their potential reactivity. This  information  was
vital for  optimization of  the  process.  Limestone injected into a power boiler must calcine
(evolve CO2 to become lime) and react with  most of the sulfur oxides  present—all within 2
seconds or  less. If limestone  is injected too close  to the highest  temperature combustion
zone, the lime produced  will be deadburned and unreactive.  If the limestone is injected
higher than or farther from this zone, the residence time for the lime particles in the zone of
the  boiler favoring reaction  with  sulfur oxides will  be seriously reduced.  The overall
objective  of this activity was to support the full scale  process optimization at the TVA
Shawnee Steam Plant by  recommending limestone type, particle size, and other sorbent  and
process parameters.

II.  Approach
       The general approach toward  meeting the  first objective  was to measure reaction
rates and  capacities  of  limestones and  then  correlate  results with  their  mineralogical,
petrographic,  and  chemical  analyses.  Bench scale calcination  and  sulfation  tests were
conducted in-house in fixed-bed and differential reactors  and under contract in a standard
laboratory thermogravimetric-analyzer  apparatus by TVA and a dispersed phase reactor by
Battelle.   Under  contract  with   Illinois  State Geological Survey  (ISGS)  and  TVA,
petrographic and electron  microscopy,  X-ray, and additional  chemical analyses were
performed on raw, calcined, and sulfated samples from the bench-scale tests. Correlations
between results of these analyses and the bench-scale reactivity results were then attempted.
Pilot-scale tests were conducted under contract with Babcock &  Wilcox and  Peabody Coal at
conditions simulating, as closely as possible, actual furnace injection conditions. These tests
were conducted   for  comparison  with  the  bench-scale data  and  limestone  reactivity
correlations developed.
       The approach toward  the second objective, determining the characteristics of dead
burning,  was to  conduct  full-scale  tests with  pure additive in an  oil-fired furnace.  Pure
additive and the oil-fired  furnace were selected  in order to avoid possible chemical changes
during dead burning which can occur  by reaction of CaO with  oxides of silicon,  iron,  and
aluminum present as a limestone impurity and  in coal fly ash. Injection with the fuel  was

-------
                                          1-4

 selected to maximize residence time at  high temperatures for fast calcination and sulfation.
 With  this  approach  it  was possible  to characterize  the  phenomena  of  dead  burning
 specifically  in terms of physical  changes and  their relationship to reactivity with  SO2
 Concurrent with this activity, methods  for testing the degree of  dead burning (loss of CaO
 reactivity)  were evaluated through  literature searches,  analysis of various chemical and
 physical  properties  of  different  limestones  calcined  at  a range  of  temperatures,  and
 laboratory  testing. More promising tests were applied to samples from pilot scale  tests by
 Babcock and Wilcox  and from early injection tests at the TVA Shawnee Steam Plant.

 III. Results and Conclusions
        Integrated  results of the  projects and correlation  with other  investigations are
 presented  by major item. These are followed by abstracted results of the individual projects.
        Limestone  Type: All studies have noted marked differences in reactivity between
 limestone  types. In-house, fixed-bed experiments showed a five-fold  range in SO2 capacity:
 marl and chalk were the best. Differential reactor  results were  widely spread: marl was the
      •¥•
 best^  Pilot plant data also showed the pronounced effect of limestone  type: aragonite was
 the best at  Peabody  Coal,4 and marl  was the best at  Babcock  & Wilcox.3  Initially these
 results may not appear  to agree; however, it is significant to note that the best performing
 limestone  types  were fine grained and  generally high in calcium carbonate, as opposed to
 dolomitic  materials.  Since calcitic  stones (marl and chalk) and aragonite are highly reactive,
 it  appears  that  both calcium carbonate  crystal  structures can be used  as  long as the
 crystallites (or grains) are small.
        Other investigators   have  compared  limestones  (i.e.,  calcites)  and  dolomites.
 Goldschmidt1 ° and   Brocke12  showed that  calcitic additives were more effective  than
 dolomitic  additives.  A good detailed examination of the effect of limestone type is given by
 Borgwardt and Harvey.6
        Chemical Form  of the Additive: Many different forms of  carbonate rocks have been
 tried  in tests ranging  from laboratory to  demonstration  scale. Most  investigators  have
 compared  hydrated  lime, calcined limestone and uncalcined limestone although dolomitic
 lime,  half  calcined  dolomite,  hydrated  dolomitic lime and  others  have  been used  on
 occasion. In general, the ranking of reactivity  is hydrated lime > limestone (uncalcined) >
 lime.3'7'9  However,  the optimum  temperatures of  injection  for different forms of the
 additive may span  752° F and a comparison at a given temperature is misleading. Zentgraf7
 reports  that  limestone  injected at  its optimum  temperature  (2732° F) is slightly  more
 effective than hydrated lime at its optimum temperature (2102°  F). Even  in tests where the
 hydrate is  consistently better, the  difference is insufficient to warrant the extra cost of the
 hydrate versus the uncalcined limestone. Tests with dolomitic counterparts of the limestone
 (i.e. calcite) chemical forms  also show the hydrate to be the most reactive but  still less
 reactive than  the hydrated lime.1 °

^Superscripts refer to  references on  pages 1-35.

-------
                                         1-5

       Particle Size:  Except in certain cases, all studies noted some increase  in reactivity
with decreasing particle size. It appears that the effect of particle size is not the same for all
stones but  is determined  primarily by  the pore size. Small  pores  lead to  the highest
sensitivity  between calcine  reactivity and particle size. Calcines with very large pores may
show no dependence of reactivity on particle size. In differential reactor  experiments not
much improvement was noted below 100 u.
       At  Babcock &  Wilcox,  particle size  was related  to  specific  surface  area by the
Lea-Nurse  technique  (air permeability).  Depending  on the grindability,  minus  60  mesh
(approximately 250 ju) produces 2000-6000 cm2 /gram in area. The maximum reactivity was
recorded when the surface area reached 2000 cm2/gm or more. Analyses of reacted fly ash
showed that particles  between 2  and 6p contained 8 to  12  percent  sulfur (as SO3), and
particles greater than 30jn had less than 4 percent sulfur.
       These results are generally supported by Battelle6 and Zentgraf7 who reported that
above 50  and 60jj  respectively,  the particle  size  was inversely porportional  to  the  SO2
reactivity  while  below  these  values  particle size had  no effect.  In  addition, Ishihara8
reported that for particles below  lOp the initial reaction rate increased as the  particle size
decreased and Tanaka9  reported  that for the 3 sizes he studied (all  greater than 74p)  a
decrease in particle size gave an increase in  removal. Zentgraf7 also  reported  that as the
particle size increases the pore size decreases.
       Calcination  Temperature:  All  experiments  showed that  higher   calcination
temperatures give rise to loss of reactivity known as dead  burning. Both in-house and TVA
studies showed that higher  temperatures lead to growth of crystallites with a corresponding
loss of surface area and  pore volume  which accounts for the loss of reactivity. In-house,
Peabody Coal, and Babcock & Wilcox data show that  injection of limestone with the fuel or
near the flame gives a dead  burned stone with little  SO2 removal efficiency. This conclusion
is supported by reports of Goldschmidt1 ° and Ishihara.11  Optimum injection temperatures
have  been reported to  be  2500-2700° F3, 2000-2450° F4 , 2732° F7,  and 1652-2192° F8
depending on the system tested.  The time-temperature profile is actually the controlling
factor.
       Catalysts: In-house  fixed-bed  studies  showed no  evidence  of the limestone-SO2
reaction  being catalyzed by minor constituents in limestone.  Both  ISGS and TVA showed
an improvement  in reactivity with sodium content  in the stone but no general conclusions
could be drawn.  At Babcock & Wilcox,  vanadium  decreased the additive  effectiveness but
iron oxide improved it slightly. It  was concluded that the improvement was due to higher
surface areas, not the  iron oxide. This  is  not  in agreement  with  Ishihara8   who found
limestone containing over 1  percent Fe2O3 were 50 percent more effective than those with
less than 0.5 percent during oil-fired  pilot plant experiments. However, SO2 removals were
not increased by  addition of ferric oxide powder or yellow ochre to the limestone.

-------
                                          1-6

 IV.  Abstracted Results of Individual Projects
        Illinois State Geological Survey1-Detailed petrographic, mineralogical, and chemical
 analysis  of 26 carbonate rocks were  made and compared with the capacity (3-1/2
 reaction  period)  and  differential reactivity  (120 second  reaction  period)  of calcined
 specimens for sorption of SO2. A wide range of petrographic and  SO2 sorptive properties
 were revealed.
        Three petrographic and chemical properties appear to be useful indexes of the SO2
 sorption capacity:  the  pore  volume,  the grain  size, and  the sodium oxide content of the
 rocks. The larger the pore volume, the greater was the sorption capacity of the rock. Pores
 with a maximum chord length between 2 and  16/j appear to have the most influence on this
 behavior.  In general, the  finer the grain  size  of the  rock, the higher was the sorption
 capacity, although  certain samples showed an opposite correlation owing to the effect of
 intercrystalline pores in the crinoidal  fossil  fragments abundant in  some of the samples. Of
 the  15 chemical elements analyzed, only sodium showed  a correlation trend with the SO2
 test  data. The sodium present in the samples increased with increasing sorption capacity.
        The reaction products of the samples calcined at 1796° F for 2 hours and exposed to
 sulfur oxides in  laboratory tests are solid grains of anhydrite (CaSO4). Electron  microscopy
 shows two types of behavior: the calcines  of the Iceland spar calcite absorbed sulfur on the
 outer surface of  its particles, whereas  in calcines of a porous  limestone,  absorption  took
 place throughout  the particles. Sulfation  occurred on the outer  surfaces of particles by
 multiple nucleation of anhydrite  crystallites, which enlarged until they abutted each other
 to produce a tightly interlocking texture of subrounded grains.
       The relatively high SO2 reactivity observed for chalks,  calcareous marls, and oolitic
 aragonite sand samples is  believed due mainly to the high  pore volume and fine grain size of
 these carbonate  rocks.  Geologically,  high  pore  volume  is indicated by  the  relatively
 unconsolidated nature of these rock materials.
       Tennessee  Valley  Authority2—The reactivities of  35  stones were  measured  and
 correlated with mineralogical and crystallographic properties.
       Calcination  of the limestone proceeds from the outside surface toward the center of
each  particle. The  rate of calcination is affected by the reaction temperature, the particle
size  of  the stone,  the crystallite  size of the carbonate mineral in the stone,  the  relative
amounts of magnesium and calcium in  the  stone, and the partial pressures of CO2 and SO2
 in the furnace atmosphere. The reaction of CaO with SO2 and  O2 at 1682° F is first order
 with  respect to  the partial pressure of SO2 in the range  1 to 8.4 percent  by volume, zero
 order with respect to the partial pressure of O2  in the range 1 to 10 percent by volume, and
 zero order with respect to the  loading of  product until the  layer  of CaSO4  completely
 shields the available reaction surface.  Below 1182° F, the formation of sulfite predominates
 over  that  of sulfate;  the oxidation  of  sulfite to sulfate  begins at about  1332° F,  a
 temperature range  in which  the  sulfite also  begins to decompose and disproportionate.
 Disproportionation of sulfite at  1612° F is prevented by the presence of oxygen or  CO2,

-------
                                          1-7

either of which promotes the formation of sulfate. The first-order specific rate constants for
the decomposition of CaSO3 and CaSO4  and the loss of reactivity (dead burning) of a  high
calcitic (Colbert)  limestone were expressed in Arrhenius form.
       Water  vapor  affects the rate  of reaction of SO2 with MgO but not with CaO; the
reaction  with MgO  is too  slow to  be  important under  injection conditions. The direct
substitution of SO2 for CO2  in the limestone also is too slow to be significant under furnace
injection  conditions. The sulfation  reaction occurs  simultaneously with  the calcination
reaction  when the rate of the calcination reaction is  low; sulfation is more rapid, however,
when there is a  relatively large surface  of unreacted CaO.  The products of the sulfation
reaction  retard the calcination reaction when the two  reactions occur simultaneously.
       The physical  properties  of a calcine and  its reactivity with  SO2  are influenced
markedly by  the texture of the parent  limestone from which  the calcine  is formed. An
Iceland spar, of mean crystallite  size 7125° A., calcined slowly below 1742° F because of its
high thermal stability, and yielded a calcine with small pores and small crystallites of CaO. A
very pure calcitic limestone, of  mean crystallite size 3875°A, yielded  larger crystallites of
CaO than did the Iceland spar under the same conditions, but the pore volume was larger
and more favorably distributed between different sized pores for reaction with SO2 • Between
1832° F  and 2012° F the calcines  of both materials showed a minimum in pore volume,
which  was interpreted as the end of sintering and the beginning of recrystallization  of the
CaO. During  sintering,  small pores  coalesce into larger pores  with small  changes  in the
crystallite size of the oxide; during recrystallization the crystallites grow into massive single
crystals  of CaO  at rates proportional to the crystallite size of the original carbonate.  The
Iceland  spar  was less reactive  with SO2 than  was  the calcitic limestone under  all  the
experimental  conditions  tested  because  of its slower calcination, its unfavorable pore-size
distribution and  pore volume,  and  its more rapid  recrystallization.  Electron  microscope
photographs of cleaved  sulfated  particles of these stones clearly showed the reaction zone
between oxide and sulfate and the growth of the crystallites of sulfate at the outer surface.
       The calcination,  isothermal sulfation, and  polythermal calcination-sulfation  of 35
limestones  were studied  and  the  distinguishing characteristics  of  each  reaction  were
correlated with the chemical and mineralogical properties of the  stones. Six measures of the
capacity and rate of reaction with  S02 were correlated with  the  chemical and mineralogical
properties  of  the stones, as well as  the  reaction parameters.  Multiple correlations  of the
capacity and rate parameters with the properties of the stones yielded equations from which
the reactivity of  a  stone could  be  predicted  from its   chemical  and  mineralogical
characteristics. The equations were  tested  with five stones considered for use  in the Shawnee
full-scale tests, using the reaction rate data at five temperatures  obtained by Battelle in the
dispersed-phase reactor.  The prediction of the polythermal capacity for absorption  of  SO2
from the chemical and  mineralogical properties of the  stones correlated well with  the
Battelle  reaction  rates at temperatures below 1724° F, but not at  higher temperatures. No
other predicted  reactivity measure  correlated  significantly with  the  Battelle rate  at any
temperature.

-------
                                          1-8

        Although the data obtained at the temperatures accessible in this experimental study
 (maximum of  1742° F)  do  not extrapolate  well  to the  higher  temperatures that  are
 encountered in actual power  plant combustion chambers, the properties of stones that were
 shown to be desirable at low temperatures probably will be advantageous at the furnace
 temperatures also.  Perhaps the major difference to be expected between the  results obtained
 at low temperature and  those anticipated at high temperatures is the marked increased in
 the rate and extent of dead burning at the high temperatures, as indicated by the results of
 the X-ray examinations.  The data indicate  no way  of avoiding the detrimental effect of
 rapid  dead burning at temperatures above about 1922° F. They indicate that  stones that
 contain the smallest  amounts of  impurity minerals and whose rhombic  carbonates  are
 primarily  calcitic and  are  present  as the  smallest  crystallites will  be  most effective  for
 injection into the combustion chamber. Increasing the sodium content of the stone increases
 its reactivity; however, if iron is present, it should  be in the form of limonite  or goethite
 rather than in the lattice of the stone.
        Babcock & Wilcox3—Using  a small pulverized  coal pilot plant, 415 tests were run
 with 129  different additives. The variables  studied relative  to additive  reactivity included
 temperature at  the point of injection, residence time of the additive in  the reactive zone,
 additive surface area, chemical form of the additive (e.g., carbonate,  oxide,  or hydrate) and
 catalyst content.
        In  general, raw limestones and dolomites were most effective  when injected  into the
 pilot plant at points corresponding to mid- and upper-furnace regions of full-scale  units. This
 behavior appeared in  part to be an effect of gas temperature,  but particle residence time was
 probably the most  important factor. Feeding the raw additives with coal  or  upstream of the
 combustion zone resulted in very poor performance,  indicating that dead  burning  took place
 under these conditions.
        Increasing additive specific surface  area to  about 2000 cm2/g,  or  slightly  higher,
 improved  additive  performance  to a  maximum.  Larger surface   area gave  no  further
 improvement, and  in some cases the amount of  SO2  removal was actually  decreased,
 probably due to agglomeration of very fine particles.
        Hydrated stones  were  slightly  more  effective than their  parent raw material,
 particularly at lower (approximately 1900° F) injection temperatures, but not to  the extent
that the cost of additive processing  would be justified.  Precalcining the stones in  most cases
decreased effectiveness of the additives.
        Iron oxide  (as  Fe2 O3  and  Fe3O4) was found to  improve additive effectiveness
slightly while  vanadium (as V2OS)  actually decreased it. It was concluded that improved
effectiveness resulted from higher surface areas, not the  iron oxide.
        Marl, a kind of limestone, was the most effective type of additive tested under most
 conditions.
        Peabody  Coal  Company4—Tests were conducted in  a pilot  size  chain-grate stoker
 with an aragonite,  a  calcite, two types of  dolomite, and a  chalk.  "Red mud," the dried

-------
                                          1-9

tailings from the manufacture of alumina from bauxite was also tested. Variables related to
additive  reactivity  included  temperature  at  the  point of  injection  and  particle size.
Calcination and calcium oxide utilization were determined.
       Sulfur dioxide removal  ranged from 6 to  65 percent depending  upon operating
conditions.  A comparison of sorbents, compared on a per-unit-weight-of-raw-stone basis,
shows that the calcites and aragonite remove more SO2 than do dolomites. Sorbent 1683,
an  aragonite, was the most effective material  tested  when  injected into  the  gas  stream.
However, it was relatively ineffective when mixed with the coal prior to combustion.
       The particle size study  was not as definitive as desired due to overlapping  particle
sizes  between injected screen cuts. A step-wise  regression analysis of 59 runs, with samples
1337 and  1684 (dolomite), 1683 (aragonite), and 1359  (calcite) combined, indicated that
reducing the sorbent particle size leads to higher SO2 removal rates.
       Each sorbent, except  red mud,  was  injected  at temperatures from  1800° F to
2450° F.  Computer  results on all  test  data  combined did  not  indicate a significant
correlation  between SO2   removal and injection temperature. However, graphical analysis
did indicate that temperature was a significant parameter for some of the  individual samples.
       The degree of  sorbent calcination varied directly with temperature and ranged from
50 to 60 percent at 1800° F to more than 90  percent at 2450° F. Above 2000° F,  particle
size did not appear to significantly affect the degree of calcination.
       Calcium oxide utilization  varied from 6.30  percent  (for particle sizes greater than
100 mesh)  to  59.50 percent  (for 200 mesh sizes).  Aragonite, Sample 1683, and  dolomite
Sample 1684, demonstrated the greatest utilization.
        Red  mud, when  injected into the gas stream at 1200° F to  1300° F and 2000° F was
relatively ineffective in removing SO2 -
        In-House  EPA5—Eighty-six  carbonate  rock samples  were  tested  in a fixed-bed
reactor to determine their capacity to react with flue gas containing SO2 . Although most of
the work  was performed with the carbonate  and  the oxide at standard  test conditions,
supplementary tests were made on hydrates, oxides, and carbonates over  a wide range of
reaction temperatures and calcination conditions.  Differences between the samples were
related only slightly to  chemical  composition; porosity, as  measured  by mercury pore
volume  best explained  variations in capacities of the samples. Chalks and oolitic samples
were the most  efficient absorbents;  magnesite and  Iceland  spar the least efficient of the
stones tested.
        The  SO2  reaction kinetics of calcines  prepared from  11 rock types representing  a
broad spectrum  of limestones  and dolomites, which were examined  by  ISGS, were
determined  at  1800° F.  Stones  of various geological types yield calcines  of  distinctly
different physical  structures  that show correspondingly large differences  in  both  rate of
reaction and capacity for SO2  sorption.  Pore size and particle size tog-ether determine the
extent to which the interior of individual  particles react. Particles smaller than 0.01 cm (100
u)  with  pores larger  than O.ljj  react throughout  their internal  pore  structure at a rate

-------
                                          1-10

 directly proportional to the B. E. T. surface. The  rate decays exponentially as sulfation
 proceeds until  the  pores are filled with reaction  product.  The ultimate capacity of small
 particles is determined  by the pore volume available for product accumulation, generally
 equivalent  to  about  50  percent  conversion of the  CaO in limestones. Variations  in
 effectiveness  of carbonate  rocks  for flue gas  desulfurization are explained  by  the physical
 properties of their  calcines, which are related to the crystal structure of the original rock.
 The  high reaction rates achieved in the limestone injection process apparently result from
 the large surface area existing for short periods immediately following the shock dissociation
 of CaCO3.
        The relative ranking of  calcines with respect to isothermal rate of reaction with SO2
 at 1796°F is: marl  > high  purity limestone > Iceland spar > aragonite > marble. Magnesite
 reacts only slowly with SO2 at any temperature between 1004 and  1796P F.
        The relative ranking of limestones with respect fo fixed bed capacity at 1796° F with
 -18 +20 mesh particles  (approximately 840-1000  u) is: marl chalk >  oolite > dolomite >
 calcite > marble> magnesite> Iceland spar.
        The rate of reaction increases with decreasing pore size  until a critical pore diameter
 of about O.lu  is reached.  Presumably pores smaller than  O.lu  are rapidly  blocked  by
 reaction products.  Maximum rate results when B.  E. T. surface area is in the  region of 3.5
 M2/g  (corresponding to  pore diameters of 0.2 - O.Sjj) under isothermal reaction conditions.
        The total SO2-sorption  capacity  increases with increasing  pore  size. Furthermore,
 the capacity of  limestones  is correlated to the area of pores greater than 0.3)u  but not to B.
 E.T. surface area.
        Both rate and capacity of SO2 sorption are highly dependent upon particle size. The
 effect of particle size is not the  same for all stones, but is determined by the size of the
 pores.
       Small  pores  lead to the highest sensitivity between  the reactivity  of  calcines  and
 particle size. Calcines with  very large  pores may  show no  dependence of reactivity upon
 particle size.
       Loss  of   reactivity  because of  high calcination temperatures  (dead  burning)  is
attributed to  growth  of CaO crystals and the subsequent  loss  of surface area  and  pore
volume.  During  sintering and CO2  evolution, small  pores  coalesce into  larger pores  with
small  changes in crystallite size  of  the oxide. At  excessive temperatures recrystallation
occurs and  the  crystallites grow  into  massive single crystals at rates proportional to the
crystallite size of the original carbonate. Since loss of surface area  and loss of  pore volume
are similar  functions of increasing calcination  temperature, both reaction rate and capacity
of dead-burned stones are lost proportionally.
       Four reactivity tests—flue gas  absorption, SO2  absorption,  CO2  absorption,  and
 hydration weight gain were found to be suitable as dead-burning tests for samples of limited
 size diluted with fly ash. The last three are considered sufficiently uncomplicated  to  be used
 as field tests.

-------
                                        1-11
V.   Recommendations  on Limestone Properties for Application to the Dry  Limestone
     Injection Process
       a. A fine-grained (e.g., having small crystallites) high calcium carbonate stone should
be used. While many common  limestones are of this type, marl, aragonite, and chalk are
almost always fine  grained. Many deposits of chalk and marl are sufficiently pure for the
injection process and most deposits of aragonite are very pure.
       b. Injection  of uncalcined limestone is indicated except where only injection at low
temperature (< 1800° F) is possible. In this case lime hydrate should be used.
       c. The additive should be finely ground. While improvement does not appear to be
significant  below lOOjJ, a directional improvement  has been  shown. A  particle size of 90
percent minus 300 mesh (approximately 50jj)  is preferable.
       d. The additive should not be injected with the fuel or near the flame. The optimum
injection point is a function of the system to be controlled but should be approximately
2000-2200° F. The  optimum injection temperature  may  be  higher  in  boilers  where the
residence time in the hottest zone is very short. In any case the injection point should be
located so as to insure complete calcination without dead burning.
       e. The hydration  weight gain  test for dead  burning  is recommended  since it  is
independent of the degree of sulfation.

-------
                                          1-13

                                      Section B
                       Limestone Availability in the United States1

I.  Introduction and Objectives
       A great deal  of emphasis is  being  placed  on  the development  of  processes which
remove sulfur oxides from the stack gases of plants which burn coal or oil as a primary fuel.
Several of these processes are based  on the use of limestone  or dolomite as the sorbent for
the sulfur oxides. The use of these materials to  control sulfur emissions is contingent upon
several factors.  Among these,  the  proximity  of adequate  carbonate rock  deposits  to
potential  users and  the relationship of carbonate rock production to possible  demand,
appear to be most important in establishing the relative merits of any carbonate rock-based
process. The objective here was the  determination of the availability and costs of limestone
and  similar  materials throughout  the contiguous United States  to provide a  basis  for
determining  the feasibility and economics of limestone-based SO2 removal processes  for
typical plant sites.

11. Approach
       Search of  publications  and  communications with  Federal and state  government
agencies,  trade  associations, and  various  crushed  stone or  limestone producers  were  the
sources of the data presented. The data was gathered on a national, regional  and state-wide
basis.  Since  the objective  is primarily  concerned with  limestone availability as it relates to
potential consumption by fossil fueled power plants, the regions were chosen to coincide
with  those  defined by the National  Coal  Association. Materials covered include limestone,
dolomite,  chalk, marble,  marl  and shell. Location of  deposits, production  rates,  f.o.b.
quarry costs, transportation  methods  and costs, expected  cost increases,  uses,  chemical
composition and physical properties were covered. Summary results most germane  to this
report follow.  Additional  details in these and other  areas may be found in  the references
provided.

III.  Results
    Potential Demand - Power Plants
        Most of the power capacity  from  fossil fuel-fired power plants  in the United States
occurs in the eastern half  of the country.  Figure 1 shows the  location  of the major (>200
MW) power plants in the United States which  burn  either coal or oil as the primary fuel.
Included are  a  few  plants  which, although  not yet  constructed,  are  being  designed
exclusively  for either  coal or oil  and are  scheduled to be on  stream by 1975. Of the  275
plants shown, 84 percent  are coal-fired. The oil-fired plants are all located along the  eastern
coast, with most of these  in the northeast. About 90 percent of all power plants shown are
located east of the  Mississippi  River,  with locally high  concentrations in  the northeastern
quarter of the country, particularly in many of the major metropolitan areas.

1, Adapted from references 13 and  14.

-------
                                                                      FIGURE  1
                                         MAJOR  THERMAL  POWER  PLANTS  IN  THE  UNITED STATES

                                                BURNING  COAL  OR  OIL  AS THE PRIMARY FUEL
                                                                                                                                             2 PLANTS WITHIN
                                                                                                                                           THE NEW YORK CITY
                                                                                                                                            LIMITS BURN COAL.
                                                                                                                                            5 PLANTS BURN OL.
NOTE:
  MAJOR  POWER PLANTS ARE  DEFINED
  AS THOSE HAVING  INSTALLED  GENERATING
  CAPACITIES  OF 200  MEGAWATTS  OR MORE.
SOURCES:
  I  Principal Electric  Facilities, Faderol Power  Commiscion,
     (1970). (S«ri«i  of (cyan  mep<)

  2. Steam-Electric  Plant factors SI97O Edition.  Notional
      Coal  Association.  Wathing:on.  D.C..  (November  I97O).

-------
                                         1-15
       Based on  1969 fuel  consumption  statistics, an estimated 20 million tons of sulfur
oxides were emitted by power plants  in the United States.  Assuming 1.25 stoichiometry,
more than  40 million tons of limestone would have been required to remove these oxides
from the stack gases. This potential limestone demand, which assumes that all  power plants
use a limestone-based  process for sulfur removal, has been broken down by region, with the
regions being defined as follows:
          Region
       New England
       Middle Atlantic

       East North Central

       West North Central


       South Atlantic
        East South Central

        West South Central

        Mountain


        Pacific
          States Included
Connecticut, Maine, Massachusetts,
New Hampshire, Rhode Island,
Vermont

New Jersey, New York, Pennsylvania

Illinois,  Indiana, Michigan,  Ohio, Wisconsin

Iowa, Kansas, Minnesota, Missouri, Nebraska,
North Dakota, South Dakota

Delaware, Florida, Georgia, Maryland (includ-
ing Washington, DC), North Carolina, South
Carolina, Virginia, West Virginia

Alabama, Kentucky, Mississippi, Tennessee

Arkansas, Louisiana, Oklahoma, Texas

Arizona, Colorado, Idaho,  Montana, Nevada,
New Mexico, Utah, Wyoming

California, Oregon, Washington
       Table  1  itemizes potential demand by  region.  The East North Central region far
outranks any  other region in  potential  limestone requirements with over one-third of the
total. With the exception of New England, all regions in the eastern half of the country had
potentially large  demands for limestone.

-------
                                         1-16
                                       Table 1
               Potential Limestone Demand by Power Plants in the United States
       Region                         Limestone (103 Tons)                   °/0 of Total
 New England                                1,369                              3-4
 Middle Atlantic                              6,583                            16-2
 East North Central                          14,307                            35.1
 West North Central                           2,738                              6-7
 South Atlantic                               8,471                            20-8
 East South Central                           5,645                            13-9
 West South Central                               5
 Mountain                                    1,351                              3.3
 Pacific                                        266                              0-6
    Total                                    40,735                           100.0
   Carbonate Rock Reserves
       Deposits of carbonate rocks, including limestone, dolomite, shell, marble, and marl,
occur in some form in every state. Total reserves have never been estimated, but are known
to be enormous.
       Figure 2 shows the distribution of surface carbonate rocks in the United States and
includes limestone, dolomite, and marble. The map shows that surface deposits of carbonate
rocks occur throughout the nation but are particularly in evidence in the eastern half of the
country.   A  band  of  deposits  beginning  in  Vermont  extends southward  along  the
Appalachian  Mountains into central  Alabama. Extensive  deposits are found in the  state
surrounding the Great Lakes,  reaching southward into northern Alabama. Large areas of
Minnesota, Iowa, and Missouri are covered with carbonate rocks and broad outcrops occur
in Kansas, Oklahoma, Arkansas, and Texas.
       Particularly in the central lowlands, carbonate rock  deposits  frequently occur as
thick, horizontal formations covering  large areas.  In general, the deposits  found in western
states are  different. They  commonly  occur as steeply dipping or vertical beds of small areal
extent. However, notable exceptions  to this are found, particularly in Colorado, Arizona,
and New Mexico where large outcrops occur.
       Limestone occurrences, including chalk but excluding dolomite, are shown in Figure
3. The map is similar to  Figure 2 and shows that although limestone is found throughout the

-------
                  FIGURE 2
CARBONATE  ROCK DEPOSITS IN  THE UMITED STATES

-------
                                                                                     00
        ij=3 CHALK DEPOSITS
        •H LIMESTONE DEPOSITS
                               FIGURE 3
DISTRIBUTION OF CHALK AND  LIMESTONE DEPOSITS IN THE  UNITED STATES
           (REPRINTED FROM U.S. BUREAU OF MINES BULLETIN NO. 395)

-------
                                          1-19
country, the more numerous and extensive deposits occur in the eastern half of the nation.
In the western states, the deposits tend to be  discontinuous and  relatively small  in areal
extent.
       The formations shown in Figure 3 include limestones of different degrees of purity.
Estimates have been made that only about 2 percent of the known reserves of commercially
usable limestone is chemical grade (> 95 percent carbonate content), and that the  bulk of
these reserves will  be exhausted in 40-50 years. Much of this high purity limestone occurs in
the area extending from the Great Lakes southward to Alabama.
       Chalk deposits are shown  in several  of the central states and in a curving belt
through  Alabama and Mississippi. In general, they are not high purity limestones, but locally
they may contain over 95 percent calcium carbonate.
        Figure 4 shows the location of high grade  (>   25 percent magnesium carbonate)
dolomite quarries. Although originally drawn  in 1941, it is a useful guide to the important
occurrences of dolomite. As with  limestone, the largest deposits are located in the  eastern
half of the country. Two major areas are noted. First  a belt  of  dolomite extends  from
Vermont to central Alabama   along the Appalachian Mountains. This coincides quite well
with  a similar band of limestone previously noted. Second, large  formations  of dolomite
occur in the states encircling the Great Lakes. These deposits coincide with or adjoin large
limestone deposits in the region.
       The most significant deposits of marble are found along virtually the entire length of
the  Appalachian  Mountains  in the east,  and  as  scattered  occurrences  in  the  Rocky
Mountains in the west. Although eastern marbles are predominantly calcitic (high calcium),
dolomitic types also occur. Both types are found in the west.
        Shell limestone occurs primarily in  Gulf Coastal waters, but it also is found in bay
waters along both the east  and  west  coasts. It is usually a  very pure type of calcium
carbonate.
        Marl deposits exist in  several areas, notably around the  Great Lakes, and along the
southeastern  coastal  plain. This soft,  relatively impure  form of calcium carbonate varies
considerably in character, that of the Great Lakes area being precipitated calcium carbonate,
while that  of the  coastal plain is an  impure shell  deposit.  Limited occurrences in  other
regions are generally impure chalks or soft limestones.

    Mining and Production
        Carbonate stones are  recovered by several methods, including underground mining
and dredging but quarrying is employed  most commonly. After removal of overburden and
primary blasting of the stone, various crushing,  grinding, sizing, and cleaning operations are
performed  to produce  a range of marketable  products. A large, modern  quarry  is an
expensive, complex, and highly mechanized unit.
        Over 4,700 quarries, producing 861  million tons of crushed stone of all types, were
in operation in  the United States  in 1969.  Since  production  of crushed  carbonate rocks
totaled 652 million  tons, it  can  be assumed that,  roughly, over  3,500 of these  quarries

-------
oo
ro
10
                                               FIGURE  4-


                  LOCATION OF HIGH-GRADE  DOLOMITE QUARRIES IN  THE UNITED STATES



                     (REPRINTED FROM U.S. BUREAU  OF MINES  INFORMATION CIRCULAR  NO. 7192)

-------
                                         1-21

produced  limestone, dolomite, and related stones. More than one-third of all quarries had
annual production  rates of less  than  25,000  tons. The  large operations (over 900,000
tons/year)  produced one-third  of the total crushed stone, although they represented less
than 4 percent of the total number of quarries.
       Crushed carbonate rock production in the United States in 1969 was distributed as
follows:

                                                           106 Tons
                 Limestone
                 Dolomite
                 Shell
                 Calcareous Marl
                 Marble
                         Total                              652

No production of any type was reported in three states, viz., Delaware, New Hampshire, and
North Dakota. These states, plus Louisiana, were the only states which did not produce any
limestone. Dolomite was produced in twenty-four states, chiefly  in  the north-eastern quarter
of the country.
       Production of limestone and dolomite, by region, was a follows:
                                                           106 Tons
                 New England                                  2.4
                 Middle Atlantic                               90.9
                 East North Central                           185.6
                 West North Central                            92.5
                 South Atlantic                                87.5
                 East South Central                            81.3
                 West South Central                            58.3
                 Mountain                                     10.7
                 Pacific                                       18.8
                       Total                                  628

 Nationwide, Pennsylvania and  Illinois were the leading producers of limestone and dolomite,
 respectively. Within most regions, production rates of individual states varied from near zero
 to tens of millions of tons. The New England and Mountain regions, however, had fairly
 uniform and low outputs. The  East North  Central region was also an exception, with all
 states  reporting large quantities of limestone and dolomite, ranging from 16 to 55 million
 tons.
        Shell was dredged from bay waters along all three coasts.  However, 83 percent came
 from Texas and  Louisiana,  with the latter being the  leading producer. Small quantities of

-------
                                           1-22

marl were  produced in Indiana, Michigan, Minnesota,  Mississippi,  Nevada, South Carolina,
Texas, and Virginia. Eighteen states, principally in eastern and western mountainous regions
quarried marble, with Alabama recording the highest production at 632,000 tons.

IV. Supply/Demand Relationship of Carbonate Rocks for Pollution Control
      Proximity of Carbonate Rock Deposits to Power Plants
       Comparison  of  Figures 1-4  indicates that the major  deposits of carbonate rocks
largely coincide in location with the power plants. This  is particularly true in the East North
Central region  where huge reserves of stone occur.  Both  high calcium limestone and high
grade  dolomite abound  and many  deposits are found near the  major  power generation
centers throughout the region.
       The New England region  is not as fortunate. While the power plants are  located
primarily  in  coastal areas, the  rock deposits occur  in the mountainous western sections.
Most of the  deposits are highly crystalline  stone or marble and many are dolomitic. The
suitability  of these materials would have to be determined before including them as a
possible source.
       Availability  of stone should  not  be a  problem for power plants in  the  Middle
Atlantic  region.  All types of stone  occur  and  nearby deposits can  be  found.  Plants in
western and  eastern Pennsylvania,  particularly,  are fortunate in that large reserves  of high
grade stones are present.
        In  the  South Atlantic region, most  plants are located  near an adequate source of
stone, particularly  if the crystalline limestones and dolomites  of the mountainous areas
prove  suitable. Several coastal plants could use shell or coral limestone, or marl. However,
for some inland power  plants in North Carolina, for example, no nearby deposits exist.
       Large quantities of high calcium limestone occur throughout the East South  Central
region and power  plants should  experience no  difficulty  in obtaining adequate supplies.
Many plants located in  Alabama and Tennessee also could obtain dolomite quite easily.
       The less abundant and  more  widely scattered  carbonate resources  of the western
states  are  of  minor importance, since there are few coal-fired power plants in this area. With
the exception of the two power plants located in  North  Dakota, which are far removed from
any commercially important carbonate deposits, the few plants that do exist are fairly near
reserves of high calcium stone.

       Potential Demand  Relative to Production
       As  previously mentioned,  the potential demand for limestone by coal-and oil-fired
power plants in 1969  exceeded 40  million tons. This represents  only 7.3 percent oFthe
national limestone production of 559 million tons. Dolomite production, on the other hand,
was roughly  60  percent  greater  than the potential demand.  Shell production  was only
one-half of the demand. The quantities of calcareous marl and crushed marble quarried were
relatively   insignificant.  Obviously,  limestone   is the  only stone  produced in sufficient
quantities  to  warrant nationwide  consideration as an agent for SO2 removal. Dolomite and

-------
                                         1-23

shell, however, are quarried in large enough amounts to make them important materials in
some regions. Marl and crushed  marble may be useful  in certain localities where the other
rocks do not exist but their limited occurrence and production do not permit wide-scale use
of these materials.
       Table  2 shows the relationship of limestone and dolomite production to  potential
demand, by region and state. The third column of the table is the ratio of total limestone
and dolomite production to potential demand, for 1969.
       With the exception of New England, the eastern regions of the country all have large
relative supplies of limestone  and dolomite. There  are some exceptions to this among the
individual states. New Jersey and Delaware have  a  potential need which exceeds  their
production. Adjacent  states, however, are large producers of stone and could provide the
necessary tonnages. Mississippi and both of the Carolinas have low relative supplies of stone.
If they could  not otherwise be supplied, marl deposits which occur extensively in all three
states  could  be  used.  Georgia and West Virginia, with  comparatively low  relative supplies,
could  easily obtain needed stone from surrounding  states. It is interesting to  note that the
region with  the highest limestone demand, i.e.,  the  East North Central  region, also has the
highest limestone and dolomite production.
        The New England region faces a shortage of limestone and  dolomite, with two states
producing less stone  than potentially  required.  The marble resources  of  the region  could
improve the situation somewhat, but power plants would have to rely on shipments of stone
from nearby states such as New York, or, perhaps, on imports.
        Most states in  other regions of the country  have ample production. North Dakota,
with  no production, is an outstanding  exception to this, however. A few other states have
low relative supplies of stone, but either the demand is quite small, or the production could
easily  be expanded to meet the need.

Costs
       F.O.B. Quarry Costs
        The average unit value, or net selling price at the quarry,  for all crushed carbonate
stones produced in the United States in 1969 was $1.49/ton and varied by type of stone as
follows:
                   Limestone                               $1.45/ton
                   Dolomite                                $1.55/ton
                   Shell                                   $1.42/ton
                   Marl                                    $1.01/ton
                   Marble                                 $9.69/ton

The high unit value of  marble reflects its primary use as a decorative material.
        Unit  value  also  varies with  end use.  Stone  used  for  all construction  purposes
averaged $1.44/ton while stone used in applications requiring a high purity material had an

-------
                                        1-24

                                      Table 2
           Availability of Limestone and Dolomite for Pollution Control (1969)

                              Production           Potential Demand
  Region and State             (103 Tons)              (*Q3 Tons) _

 New England                                                                  „ ,-r
  Connecticut                      275                    47                 056
  Maine                            800
  Massachusetts                     750
  New Hampshire
  Rhode Island                   < 100                     39
  Vermont                         525
                                                        _
    Totals                        2,400                  1-369                 1.75

 Middle Atlantic
  New Jersey                       800                    935                 °-86
  New York                     33,457                  2,132                 15.7
  Pennsylvania                   56,667                  3,516                 16.1
    Totals                       90,900                  6,583                 13.8

 South Atlantic
  Delaware                                                177                    0
  Florida                        40,729                  1,009                 40.4
  Georgia                         4,334                    931                 4.66
  Maryland                       9,804                  1,010                 9.71
  North Carolina                  4,500                  2,003                 2.25
  South Carolina                  1,900                    459                 4.14
  Virginia                        17,829                  1,088                 16.4
  West Virginia                    8,405                  1.794                 4.69
    Totals                       87,500                  8,471                 10.3

East South Central
  Alabama                       17,752                  1,931                 9.19
  Kentucky                      30,158                  1,785                 16.9
  Mississippi                        300                     71                 4.23
  Tennessee                      33,109                  1,858                 17.8
    Totals                       81,300                  5,645                 14.4

East North Central
  Illinois                        54,844                  3,665                 15.0
  Indiana                        25,157                  2,786                 9.03
  Michigan                       39,066                  2,511                 15.6
  Ohio                          50,595   .               4,181                 12.1
  Wisconsin                      15,937                  1,164                 13.7
    Totals                      185,600                 14,307                 13.0

West North Central
  Iowa                          26,200                    453                 57.8
  Kansas                        15,334                     42                  365
  Minnesota                      4,127                    648                 6.37
  Missouri                       41,200                  1,093                 37.7
  Nebraska                       4,663                    110                 42.4
  North Dakota                        -                    357                    0
  South Dakota                     989                     35                 28 3
    Totals                       92,500                  2,738                 33^3

-------
                                       1-25

                                Table 2 (continued)

                             Production            Potential Demand
  Region and State             (103 Tons)               (103 Tons)              Ratio

West South Central
  Arkansas                       5,676                      4                1419
  Louisiana                           -                     <1                    0
  Oklahoma                     16,300                     <1                 Large
  Texas                         36,300                     <1                 Large
    Totals                       58,300                     <7                Large

Mountain
  Arizona                        2,339                     50                46.8
  Colorado                       1,650                    358                4.61
  Idaho                            250
  Montana                       1,442                     74                19.5
  Nevada                         1,000                     78                12.8
  New Mexico                      956                    345                2.77
  Utah                           2,400                     67                35.8
  Wyoming                         649                    379                1-71
    Totals                       10,700                   1,351                7.92

 Pacific
  California                     17,400                    266                65.4
  Oregon                           350                    <1                Large
  Washington                     1,050                    < 1                Large
    Totals                    ^  18,800                  <268                >70

-------
                                          1-26

 average value of $1.69/ton. Average prices ranged from $0.69/ton for fill to $6.00/ton for
 exposed aggregate (decorative stone). Stone for most applications, however, averaged under
 $2.00/ton. The variation in price depends not only on supply and demand  but also on the
 chemical and/or physical properties required for the particular application.
        Average  prices of limestone and dolomite are shown in Table 3, by region and state.
 Within  most states, average prices were $1.00-$2.00/ton, although spot prices ranged from
 $0.12-$25.00/ton. Several  states in the New  England and Mountain Regions, in addition to
 New Jersey, reported average values above $2.00/ton.  Rhode Island  reported the highest
 average value: $7.57/ton  for  limestone. The prices reported in  California and Washington
 were unusual in that average values for limestone were below the national average, while
 average values for  dolomite far exceeded $2.00/ton. Production  of the particular stone was
 limited in all cases where average unit values were high.
        With the exception of Virginia, which  reported  $3.92/ton, average prices of shell
 were $1.00-$2.00/ton.  Unit values for marl were all below $1.15/ton and varied widely in
 price.

     Transportation Costs
        Trucks  dominated  in the  transportation of  carbonate rocks  from  quarry  to
 consumer,  accounting  for almost three-fourths  of all  stone.  Rail and  waterway hauls,
 amounting to one-fifth of the stone shipments, were about equally divided.
        Trucks generally are  used  for  shorter  hauls of under  50-100 miles while rail is
 employed for longer distances. Where conditions permit, shipment of stone by barge or boat
 is preferred since this is usually the cheapest method of transportation.
        Typical capacities of the various vehicles used to transport stone are:
                      Truck                       up to 50 tons
                      Rail Car                     60-100 tons
                      Barge                       1200-1400 tons
                      Boat                        up to 29,000 tons
 Trucks  were a popular mode of transportation  in all sections of the nation, while railroads
 were important  in  eastern  states,  particularly in the southeast. Large amounts of stone were
 moved  via inland  waters, notably in the Great Lakes area and along the Gulf Intracoastal
 Waterway. The abundance  of  highways, railroads, and inland waterways found in the east is
 not  duplicated in western states, thereby limiting the selection of a transportation method
 in the latter area.
        Generally, sufficient trucks, barges, and boats are available to haul stone although in
some areas  in peak seasons the supply may  be limited.  In most sections of the country a
shortage of rail cars does occur. For a  power plant where the limestone demand would be
known and deliveries could be scheduled well in advance, the affect of a shortage of vehicles
should not be severe.

-------
                                       1-27
                                     Table 3

                Unit Value of Crushed and Broken Limestone and Dolomite
                  in the United States in 1969, By Region and State

                                                 Average Unit Value ($/Ton)
Region and State
New England
Connecticut
Maine
Massachusetts
New Hampshire
Rhode Island
Vermont
Middle Atlantic
New Jersey
New York
Pennsylvania
East North Central
Illinois
Indiana
Michigan
Ohio
Wisconsin
West North Central
Iowa
Kansas
Minnesota
Missouri
Nebraska
North Dakota
South Dakota
South Atlantic
Delaware
Florida
Georgia
Maryland
North Carolina
South Carolina
Virginia
West Virginia
Limestone

NR1
1.32
4.14
-
7.57
1.46

2.49
1.56
1.46

1.44
1.32
1.02
1.54
1.17

1.49
1.40
1.32
1.39
1.87
-
1.22

-
1.31
1.50
1.57
1.62
1.51
1.52
1.62
Dolomite

4.20
.2
5.24
-
-
1.53

-
1.97
1.73

1.45
1.28
1.45
1.48
1.21

1.72
-
1.38
1.13
.
-
-

-
-

-
-
-
1.37
1.62
1.  "NR" indicates that value was not reported
2.  "-" indicates no production

-------
                                      1-28
                                Table 3 (continued)
  Region and State

East South Central
  Alabama
  Kentucky
  Mississippi
  Tennessee
                                                  Average Unit Value ($/Ton)
Limestone
  1.17
  1.46
  1.00
  1.33
                                                                           Dolomite
                                   1.60
West South Central
  Arkasas
  Louisiana
  Oklahoma
  Texas
  1.36

  1.30
  1.35
 NR
1.17
Mountain
  Arizona
  Colordao
  Idaho
  Montana
  Nevada
  New Mexico
  Utah
  Wyoming

Pacific
  California
  Oregon
  Washington

Total United States
  1.64
  2.04
  1.10
  1.24
  1.64
  1.51
  2.25
  2.11
   1.07
   1.00
   1.28

   1.45
2.83
1.77
 NR
2.66
2.91

6.00
   :>
1.55
1. 'NR" indicates that value was not reported
2. "-" indicates no production

-------
                                          1-29
       So  many factors influence  transportation rates  and costs that it  becomes  very
difficult to establish average rates, even within a single area. Most freight rates for crushed
stone in the United  States fall within the following ranges,  in cents per ton-mile:
       Truck      5.0-10.0 (@ 10 miles) *  2.0 - 5.0  (@ 100 miles)
       Rail        4.5- 6.0 (@ 10 miles) *  0.75-1.5  (@ 250 miles)
       Water      0.9- 1.5 (@ 20 miles) *  0.25 - 0.50 (@ 500 miles)

    Delivered Costs
       The delivered price of limestone to a power plant is the sum of the price of the stone
at the quarry plus the transportation charges. The delivered price of limestone to 37 selected
power plants is estimated in Table  4,  based on the  assumption that a calcium  limestone
would be required. Most of the plants  are located in the  eastern half of the United States
where the  major  coal- and   oil-fired  power capacity  is  found.  Prices range  from
$1.95-$13.20/ton. Half of the plants could  be supplied at under $4.00/ton, while all but 3
could obtain limestone at under $6.00/ton. The latter 3 plants are located  in the west in
areas where base prices are higher  or  limestone deposits are remote.  For  several eastern
seaboard plants,  particularly in  New England, the availability of  low-cost high calcium
limestone is contingent upon the acceptability of an imported stone. Domestic sources are
either inadequate or too distant to provide a low-cost material.
       Carbonate  rocks historically  have been  stable, low-priced commodities.  Based on
average unit values for the years 1960-1969, projected average base prices for 1975 are as
follows:
                                            1969                1975
       Limestone and  Dolomite          $1.46/ton          $1.67-1.82/ton
       Marl                             $1.01/ton          $1.28-1.48/ton
The average value of shell has dropped considerably since  1960.  It is unlikely that it will
continue to decrease  through  1975.  More  probably,  it  should  parallel  limestone  and
dolomite but not exceed them in value. Average unit values for crushed marble are highly
variable, reflecting the sensitivity of price to  market conditions.
       Transportation  rates  during the next  5 years should rise about 6 percent/year,, on the
average. Estimates by type of transportation are as follows:
                   Truck                         4 -  6%/year
                   Rail                           6 -  8%/year
                   Water                          5 -  10%/year
These estimates, based on predictions by various stone producers, assume a continuance of
the present rate of inflation.
       It should be noted that the lime industry could be  affected greatly from the national
concern for the environment. Specifically, the power industry may require large amounts of
lime by 1980, in the form of an additive to control sulfur oxides from the burning of fossil

-------
                                       1-30
                                      Table 4

          Delivered Price of High-Calcium Limestone to Selected Power Plants
Power Plant

Benning
Gorgas
Cherokee
J. McDonough
Devon
Fisk
R.S.Wallace
Will County
D.H.Mitchell
Wabash
Riverside
Lawrence
Cane  Run
Elmer Smith
Riverside
Edgar
L Street
Delray
High Bridge
Hawthorn
Sioux
Essex
Port Jefferson
Waterside
Allen
Leland Olds
Tidd
Miami Fort
Acme
Horseshoe Lake
Elrama
Schuylkill
Wateree
Bull Run
Cabin Creek
Kammer
Lakeside
Location

Washington, D.C.
Gorgas, Alabama
Denver,  Colorado
Cobb County, Georgia
Millford, Connecticut
Chicago, Illinois
East Peoria, Illinois
Lockport, Illinois
Gary, Indiana
Terre Haute, Indiana
lowana, Iowa
Lawrence, Kansas
Louisville, Kentucky
Owensboro, Kentucky
Baltimore, Maryland
N. Weymouth, Massachusetts
Boston, Massachusetts
Detroit, Michigan
St.  Paul, Minnesota
Kansas City, Missouri
West Alton, Missouri
Newark, New Jersey
Port Jefferson, New York
New York, New York
Belmont, North Carolina
Stanton, North Dakota
Brilliant, Ohio
North Bend, Ohio
Toledo, Ohio
Horseshoe Lake, Oklahoma
Elrama, Pennsylvania
Philadelphia, Pennsylvania
Rockland City, South Carolina
Oak Ridge, Tennessee
Cabin Creek, West Virginia
Captina, West Virginia
St.  Francis, Wisconsin
Delivered Price ($/Ton)

       4.50*
       3.23
       6.36
       4.50
       4.50*
       2.40
       3.30
       3.30
       2.65
       2.25(75-94%CaC03)
       1.95
       3.66
       3.00
       3.72
       3.85
       4.50*
       4.50*
       2.40
       3.00
       4.60
       3.10
       4.50*
       4.50*
       4.50*
       5.39
      13.20
       3.80
       2.45
       2.45
       8.00
       5.55(92%CaCO3)
       4.50*
       3.90(88%CaC03)
       4.24
       6.00
       4.00(80%CaC03)
       2.60
*Source of stone is outside of U.S. (Bahamas)

-------
                                          1-31

fuels. Although the amounts to  be used are far from  certain,  it is possible that such
pollution  control efforts will make a significant new market for the lime industry.15 New
supply and  demand relationships within this market could alter F.O.B. and transportation
charges and  have a considerable effect on delivered cost.

V. Conclusions
       a.  Enormous deposits of carbonate rocks occur in  the United States and reserves are
more than  adequate for the foreseeable future. A very rough approximation of surface
carbonate deposits indicates a minimum of 3.6  x 1012 tons, sufficient to satisfy national
requirements for  more than 500 years at the present rate of consumption (and assuming a
10 percent  availability  of these reserves). Availability of high  purity stone may become a
problem several  decades hence,  but, with the  probability that the required  quality will
depend on other process and economic factors, no shortage of suitable stone is foreseen.
       b. The major deposits of  carbonate rocks occur  in the eastern half of the United
States where the  vast majority of fossil fuel-fired power plants are  located. Large reserves in
these eastern  areas provide a nearby  source of stone for  most power plants.  Roughly
two-thirds of  all  surface deposits  of carbonate  rock are  found in the eastern  half of  the
country.
       c. Relative to the potential demand for carbonate rocks by  power plants, production
of these materials is quite large in most states.  However, current production is inadequate to
supply the potential needs of power  plants in several Atlantic coastal regions, notably New
England.
       d. Limestone is the  only type of carbonate rock which is  produced  in large enough
quantities to  merit consideration  for wide-spread application in the removal of SO2 from
stack  gases.  In  many  areas ample  amounts  of other  carbonate rocks  are produced,
particularly dolomite.
       e. Most of the  power plants in the  eastern  half of the United States could  be
supplied with high calcium  limestone at less than $6.00/ton, many at  less than $4.00/ton.
Costs for power plants located in western states generally would be higher, owing to the lack
of suitable,  nearby deposits and other factors.
       The preceding costs are  based  on  an unsized,  nominally 2"-6" x 0  stone (this
indicates stone with a maximum size of 2"-6" and no minimum size), which is typical of the
product from  the primary crusher at most quarries.  If a sized or fine material is desired, the
cost may  increase.  Most quarries have little or no capacity for fine grinding, particularly in
the amounts possibly required by the larger power plants.
       f.  Based  on projections of material cost and transportation charges to 1975,  the
delivered price of limestone to most  power plants is not expected to increase by more than
$1.00-$2.00/ton.

-------
                                          1-32
VI. Recommendations for Application to Dry Limestone Injection and
    Other Limestone-Based Processes
       The data and material contained herein and the referenced reports should be used to
obtain a first approximation of the occurrence, characteristics, and cost of carbonate rocks
in  a particular case, thereby enabling a  power company to assess the desirability of installing
a limestone-based  process for SO2  removal.  If further investigation is warranted, the state
geological surveys, a list of  which  is included in the reference 14 report,  individual  stone
producers, and local carriers should  be consulted for more detailed and specific information.

-------
                                          1-33

                                      Section C
                                    Definitions14

       To avoid some of the confusion which  frequently results from  the  inexact and
qualitative definitions  applied to  limestone and related materials in  the United States, and
from the  multitude of overlapping names used, some of the terms as used in this section are
defined below.
       Limestone is a general term  applied  to  sedimentary  rocks composed chiefly of
calcium carbonate, CaCO3, calcium-magnesium carbonate, CaMg(CO3)2, or mixtures of the
two. The  term is also used, in a more restricted way, to denote rocks composed  mainly of
calcium carbonate, in order to  differentiate  them from dolomites. Dolomite is a name used
to describe a  limestone primarily composed of the  mineral dolomite, calcium-magnesium
carbonate   CaMg(CO3)2.  It  is  generally  applied  to  carbonate  rocks  which contain
approximately 20 percent or more magnesium carbonate, MgC03. Pure  dolomite would
contain 54.3  percent CaCO3 and 45.7  percent MgCO3.  A point of contention, which is
sometimes noted in  the literature, is  whether the calcium and magnesium carbonates are
chemically combined, or whether they occur merely  as a physical mixture. Limestone and
dolomite occur with varying  quantities of impurities, the most common of which  are silica,
alumina, iron oxides, and carbonaceous matter.
       Lime can be  defined as the product which results from calcination of a limestone or
dolomite.  Calcination  is a process of heating the stone to a temperature at which carbon
dioxide, CO2  is released, thereby converting the carbonates to oxides.  A calcium carbonate
stone will produce a lime containing calcium oxide, CaO. Dolomite  will  produce a lime
containing both calcium oxide  and magnesium oxide, MgO, commonly called magnesia. In
practice,  commercial  limes  are  usually derived  from  high purity stones containing  a
minimum  of about 95 percent total carbonates.
       The following list defines the more important terms used in this report:
       Aragonite is a mineral composed  of calcium carbonate, and having an orthorhombic
crystalline structure.
       Argillaceous limestone contains clay as a major impurity.
       Bituminous  (carbonaceous) limestone  contains organic compounds  as  a  major
impurity.
       Calcareous is a term used to describe any material containing calcium carbonate.
       Calcite is a mineral composed of calcium carbonate, and having  a rhombohedral
crystalline structure.  It is the predominant mineral  in most limestones.
       Chalk  is a soft, friable, fine-grained  limestone consisting primarily of the remains of
minute marine organisms.
       Coral limestone is a fossiliferous limestone consisting primarily of coral.
       Dolomitic limestone refers to a limestone  which contains more than approximately
20 percent magnesium carbonate.  The term is usually interchangeable with "dolomite."
       Ferruginous limestone contains iron oxides as a major impurity.

-------
                                          1-34

       Flux stone is a  high-purity limestone or dolomite used as a flux in metallurgical
processes. It contains 95 percent or more minimum total carbonate.
       Fossiliferous  limestone is a stone in which the shells or shell fragments (fossils) are
readily discernible.
       High  calcium  limestone refers  to a  limestone  which  contains a  minimum  of
approximately 95 percent calcium carbonate.
       Magnesian  limestone refers to a  limestone  which contains magensium  carbonate
within the approximate range of 5-20 percent.
       Marble  is a  metamorphic  rock consisting of  crystallized grains  of  calcite  and/or
dolomite. Commercially, the definition includes any calcareous rock that can be polished.
       Marl is an indefinite term used to describe a loose,  soft, impure  material which
contains fine-grained fragments of shell and marine organisms intermixed with sand and
clay.
        Oolitic limestone contains small, rounded  pellets (oolites), having  a  center  of
calcium carbonate or sand grains around which are deposited concentric layers of calcite.
        Shell limestone  is a term used to describe limestone derived from clam and oyster
shells.
        Siliceous (cherty) limestone contains silica as a major impurity.
        Travertine consists  of calcium  carbonate  that  is  chemically precipitated  from hot
springs.

-------
                                         1-35

                                     Section D
                                     References

       Reports identified by numbers prefixed "PB" are currently available prepaid from:
National Technical Information Service (NTIS), U.S. Department of  Commerce, 5285 Port
Royal  Road,  Springfield, Virginia  22151. Others will  be available approximately one
month after receipt by NTIS.
     1. Illinois  State  Geological  Survey,  Final  Report,  PB 206-487, "Petrographic and
       Mineralogical  Characteristics  of  Carbonate  Rocks Related  to  Sulfur Dioxide
       Sorption in Flue Gases," July 1971, EPA Contract CPA 22-69-65.
     2. Tennessee Valley Authority, Final  Report, PB 202-407, "Sulfur Oxide Removal
       from  Power  Plant Stack  Gas—Investigation of the  Reactivities  of  Limestone to
       Remove Sulfur Dioxide from Flue Gas," 1971.
     3. Babcock &  Wilcox,   Final  Report,  PB  184-059,  "Additive Injection for  Sulfur
       Dioxide Control—A  Pilot  Plant Study." March  1970, EPA Contract PH 86-67-127.
     4. Peabody Coal Company,  Final  Report,  PB 184-944,  "Pilot Plant  Moving Grate
       Furnace  Study of Limestone-Dolomite for Control of Sulfur Oxide in  Combustion
       Flue Gases," August  1970, EPA Contract PH 22-68-68.
     5. Environmental  Protection  Agency, Air Pollution Control Technical Report, APTD
       0737, "Alkaline Additives  for Sulfur Dioxide Control," March 29, 1971.
     6. Borgwardt, R.  M., and  Harvey,  R.  D., "Properties of Carbonate  Rocks Related to
       S02 Reactivity," Environmental Science  & Technology, Vol. 16, No. 4, pp 350-9,
       (April 1972).
     7. Zentgraf,  Karl  Martin, "A Contribution to the Determination of Sulfur Dioxide in
       Flue Gases and  Desulfurization of  Flue Gas with Earth Alkali Metal Compounds,"
       Fortschrittsberichte  VDI Zeitschrift, Germany, October 1967.
     8. Ishihara, Yoshimi, "Kinetics of  the Reaction of  Calcined Limestone with Sulfur
       Dioxide  in  Combustion  Gases," Technical Laboratory  No.  1  Central  Research
       Institute  of  Electric Power Industry,  Japan,  presented  at the Dry  Limestone
       Injection Process Symposium, June 22-26, 1970.
     9. Tanaka,  K., et  al., "Studies on  Removal of Sulfur  Oxides  from Flue Gas by Dry
       Limestone Process,"  Japan, 1969.
    10. Goldschmidt, K., "Experiments  in the Use of White Lime Hydrate and Dolomite
       Lime   Hydrate   to  Desulfurize  Flue  Gases from  Oil  and  Pulverized  Coal-Fired
       Furnaces," Fortschrittsberichte VDI Zeitschrift, August  1968.
    11. Ishihara, Y., "Removal of SO2 from Flue Gases by Lime Injection Method," report
       of Central Research Institute of Electric Power Industry, Komae, Kaitatama, Tokyo,
       Japan, presented at  Public  Health  Service Limestone  Conference, December 4-8,
       1967.
    12. Brocke, W., Report for Third Limestone Symposium, Clearwater, Florida, December
       4-8, 1967.

-------
                                     1-36

13. O'Donnell, J., and Sliger, A.,  "Availability of Limestones and Dolomites,"presented
   at the  Second  International   Lime/Limestone Wet Scrubbing  Symposium, New
   Orleans, Louisiana, November  8-12, 1971.
14. Kellogg,  M.  W.,  Final   Report,  PB  206-963, "Availability of Limestones  and
   Dolomites," February 1972, EPA Contract CPA 70-68, Task 1.
15. Environmental Protection Agency, "The Economics of Clean Air," Annual Report
   to the Congress of the United States, February 1972.

-------
       APPENDIX J
Mathematical Modeling of the
 Limestone Injection Process

-------
                                        J-l
                                    APPENDIX J
      MATHEMATICAL MODELING OF THE LIMESTONE INJECTION PROCESS

       In this  appendix  the  author discusses the modeling  activities which  proceeded
concurrently  with  the  experimental work on which it is based. "The ultimate goal of this
modeling was to establish a sound basis upon which the extensive data obtained at Shawnee
could be used to predict performance and  adapt the process to other  boilers of different
design."
       His summary includes work by:
   1. Professor  Jack  B.  Howard,  Department  of  Chemical  Engineering, Massachusetts
      Institute of Technology
   2. EPA Isothermal  Kinetic Studies
   3. Dr. Yoshimi Ishihara, Central  Research Institute of Electric Power  Industry, Japan
   4. Dr. Robert W. Coutant, Battelle Memorial Institute
   5. Professor Robert L. Pigford, University of California
   6. Professor C. Y. Wen, West Virginia University

-------
                                         J-3

                            I.   Introduction and Objectives

       The unique adaptability of the dry limestone injection process to existing power
plants—especially small and  older  units—together with its economic  advantages  in both
capital and operating costs, made it imperative that a thorough evaluation of the process be
made.  At the time when this evaluation was undertaken (1967) by CSD in cooperation with
TVA,  there was strong evidence that good  SO2  removal efficiencies and high additive
utilizations could  be obtained  by this process. A fundamental study made for EPA at  the
Battelle  Memorial   Institute  in  1966  showed  that  high  removal  efficiencies  were
thermodynamically  possible,  but  kinetic data  and mass transfer  correlations  were  not
available  by which  limits  of  efficiency could  be  predicted a  priori.  An experimental
program,  involving both boiler testing and  fundamental research  was necessary and  many
such investigations were carried  out  over the  period 1967-70, both  in the U.S. and  other
countries.
       With the publication  of reliable experimental data in 1969 on the  reaction  kinetics
of CaO with SO2  in both laboratory isothermal and dispersed-phase reactor systems, several
efforts were begun to develop mathematical  models which could be used to  interpret  the
experimental data from various sources and guide optimization of performance in full scale
tests. The ultimate goal of this modeling  activity was to establish a sound basis upon which
the extensive data obtained at Shawnee could  be  used to predict performance and adapt  the
process to other boilers of different design. Statistical correlations of data do not permit
extrapolation with any degree of confidence to boilers different in design from that used to
develop the correlation. A model useful for engineering design must account quantitatively
for the effects of injection temperature, residence time, initial SO2  concentration, sulfation,
time-temperature profile,  excess oxygen and other boiler characteristics which influence  the
kinetics of the reaction of SO2 with the limestone particles injected into it.
       Clearly,  the  development  of  a  satisfactory model  required  that  the primary
rate-limiting  mechanism  (Battelle had  already  shown  that there was no  equilibrium
limitation) be  established.  Although  this is generally  the first step in development of a
comprehensive  model, it  is also the most critical, and was found  to  be the most difficult.
Several  possible  and  equally  plausible  assumptions were  made as  a  basis for  model
development, but unfortunately, a: the lirne  when  most of these modeling activities were
begun, experimental research had not yet estaolished the facts regarding the effects of all of
the primary variables (temp., time, SO2 concentration, particle size and physical properties
of the calcine)  upon  the  reaction characteristics with S02.  Consequently, models  based
upon different  assumptions were developed, and only by comparing the responses predicted
by the model with those observed experimentally can a judgement be reached regarding the
most valid and useful model of the limestone injection process.
       In the summary following, somewhat of a historical  presentation  is provided since
the modeling activities proceeded concurrently with the experimental work on which  it is
based.  The development of information  identifying  the importance of key parameters is
emphasized and integrated, via  discussion, into the most general basis for interpretation  and
definite conclusions.

-------
                                          J-5

                           II.  Summary of Modeling Activities

    Professor Jack B. Howard, Department of Chemical  Engineering, Massachusetts Institute
    of Technology
        At  the  request of  EPA, a project was undertaken  in August  1969 to identify the
 rate-limiting mechanism controlling the sorption of SO2 by  calcined limestone. On the basis
 of the known  physical properties of such calcines the  rate of diffusion  of  SO2 into the
 pore structure  of individual  particles was to be estimated by means of the well-developed
 theory of  heterogeneous  catalysis. By  calculation of the pure diffusional  resistances  and
 comparison with experimental data, the importance of chemical reaction, pore diffusion and
 other SO2 sorption  resistances were inferred.
        The model1  describes the reaction behavior of a porous limestone particle in terms
 of the reaction of  clusters of  microscopic nonporous CaO grains that comprise the larger
 particle.  It accounts for the effects of  pore size,  porosity, internal surface area and CaO
 content.  The  pore  spaces  between grains permit access of SO2 to the grain surfaces for
 reaction  while  larger pores between grain clusters provide the main path of diffusion into
 the particle. Four resistances are considered: (1) transport of SO2  from the ambient gas to
 the particle surface, (2) diffusion of SO2 within the pores, (3) chemical reaction at the grain
 surface and (4) diffusion of CaSO4 reaction product into the solid CaO  grains.
        The resistance due to mass transfer  to the particle surface  was eliminated as a
 possible  limitation  by comparison of  experimental data  from Battelle's  dispersed reactor
 with the calculated rate of mass transfer through the gas film. The results (Figure  1, Curves
 A and B) showed that the quantity of  SO2 that can be transferred  to 90 jj particles would
 permit 25% CaO conversion in 2 seconds at 1800° F. Actual data  at these conditions show
 only 9% conversion, consequently Howard concluded that the major resistance is within the
 particle itself, resulting from either pore diffusion or chemical reaction.* Ishihara2 reached
 the same conclusion on  the basis of  calculations of  the  decrease in SO2  concentration
 through the gas film surrounding dispersed particles.
        Two versions of the model were tested against experimental data on the  isothermal
 sorption  of SO2 by calcines prepared in the laboratory. One version holds the pore structure
 constant except for surface area, which  decreases in proportion to conversion. The  second
 version of  the  model allows the pore structure  to change  as the reaction progresses, thus
 accounting for the expansion  of the  CaO  grains  as  they  are  converted  to the more
 voluminous   CaSO4.  Calculations  with  the  two  versions show  that   the sorption
 characteristics  are  relatively insensitive  to  porosity in comparison with the effects of grain
 size or surface area. Detailed analysis of experimental data with the model  indicated that the
*Although the  Battelle data are at  low particle to gas concentrations, it has been shown that
 the reported rates are in good  agreement with Ishihara's pilot plant data for similar sized
 particles, which were obtained at particle-to-gas stoichiometries up to 2.5 x (3).

-------
                                  J-6
FIGURE 1
   0.4
                                       CURVE A:  GAS PHASE MASS TRANSFER
         (S02)
                   = 1-BS
         (SO?) INITIAL
                                      t = (-7.3 sec/S  In (1-6S
                                  DIFFERENCE  ATTRIBUTED  TO INTRAPARTICLE
                                             RATE LIMITATIONS
                                   CURVE B:  BATTELLE DISPERSED-PHASE
                                              REACTOR DATA
                                       CURVE C:. EPA LABORATORY CALCINES
                              2           3
                                TIME (t), SECONDS

       PREDICTED BEHAVIOR  OF PARTICLES  REACTING WITH SULFUR  DIOXIDE
       UNDER  EXTERNAL DIFFUSION CONTROLLED CONDITIONS COMPARED WITH
       EXPERIMENTAL DATA  (1,000°C; PARTICLE SIZE  96w j 3000  PPM S02;
       S =  INITIAL MOLES   SOLID/STOICHIOMETRIC MOLAR SOLID

-------
                                         J-7

overall rate is controlled jointly by the pore diffusion and chemical reaction rates, with pore
diffusion being the stronger.  The estimated Thiele modulus of the smallest particles was
about 30 indicating r\ < 0.1,  consequently  the reaction profiles predicted by the mode for
particle cross sections in all cases showed only the external surface zone to be participating.
       A unique feature of this model is its allowance for solid diffusion.  Howard's analysis
showed that without  diffusion of  the  CaS04  into the CaO  grains, the maximum  solid
conversion could not exceed  8%. It is interesting to note that  the  data analyzed with the
model indicates that diffusion through the solid grain was rapid enough to contribute little
to the overall resistance.
       The most significant conclusion from the MIT analysis was that the internal surface
area available for  reaction was the primary  factor  limiting  SO2  sorption  rate and that the
reaction  behavior  could be approximated with  knowledge only of the effective CaO grain
radius. A comparison between the reaction rates obtained with the EPA laboratory calcines
examined in  this study and the rate  obtained  when limestones are injected into and
dispersed in  flue gas (Figure  1, curves B  and C)  showed a  significantly  higher rate in the
latter case. No explanation for this difference could  be  offered  on the basis of information
available at that time.

    EPA Isothermal Kinetics Studies
       The extreme discrepancy between reaction  rates measured in the laboratory and the
rates observed for limestone particles of the same size injected  at the same temperature in
dispersed systems had  been  known since  the  publication  of  isothermal kinetics data in
19594,5 _ y^jj discrepancy, and the lack of an adequate  explanation for it, was the  primary
limitation upon the  development of a fundamental  model which could be  applied to predict
performance on the basis of reaction kinetics.
       Research  continued  at EPA concentrating  upon the  physical  properties of the
calcines  affecting  reaction  rate,  i.e., pore structure of the calcine and  properties of the
original rock. The results of  these additional experimental  studies, reported at the 1970
symposium,  established  the relationship between reaction rate  and  the surface  area of the
calcine.  Dr.  Dennis  Drehmel5 showed that the  reactivity of calcines prepared in the
laboratory were  strongly correlated to the BET surface area,  which varied according to
calcination temperature. Borgwardt7  verified these  findings by quantitative measurement of
the reaction  rate of  calcines prepared from different types of rock (which yielded different
pore  structures and surface areas) and showed that the initial  reaction  rate was  a  linear
function of the BET surface area of the calcine.
       A simple model based on chemical  reaction control was shown to correlate the
initial  rates  of SO2  sorption of  calcines of different  types of rock prepared at a given
calcination  temperature,  and  the  rates  of  a given  rock type calcined at  different
temperatures:

                       ro =  ks Sg  CS02  1                                          (1>

-------
                                         J-8

where rQ is the rate per unit mass of CaO extrapolated to zero sulfation, and Sg is the B.E.T.
surface area of the calcine.
The reaction rate constant, ks = Ae  '
The  activation  energy for  different  calcines averages about 17 k cal/g mole. The  intrinsic
reaction  rate  constant  was accurately  measured  at  900°C  at  0.22 cm/sec, essentially
independent of stone type.
The  effect of sulfation was shown to result in an exponential decrease in isothermal  reaction
rate  with conversion, X according to:
                                    r  = r0 e "^                                    (2)
The coefficient (3 is a strong function  of particle  size,  since  it includes the effectiveness
factor,  n-  and  is a weak  function of stone  type, probably due to the differences in solid
diffusion   rates within  CaO grains  postulated by  Howard.  This effect  was  quite  small
however,  compared to the effect of surface area upon the overall rate of SO2 sorption.
        The maximum limit of CaO conversion  (total  SO2-sorption  capacity) was defined
 by  the  available   pore  volume for  product accumulation.  This  was  determined  by
 measurement  of  grain expansion and  decrease in pore volume with  conversion,  which
 showed that calcines of maximum theoretical pore volume can achieve no more than 49%
 CaO conversion. At that point the entire pore volume is filled with reaction product, and
 greater conversions can  be achieved only by  solid  diffusion through the exterior particle
 surface, which is extremely slow.

    Dr. Yoshimi Ishihara - Central Research Institute of Electric Power Industry. Japan
        Establishment of the direct relationship between BET surface area and initial SO2
 reaction  rate provided the  first insight into the mechanism of SO2 capture by the limestone
 injection  process. At the same symposium where  those data were  presented, Dr. Ishihara
 reported2 the results of  an extensive investigation of the  reaction  kinetics in a pilot-scale
 limestone injection  furnace. As a part of his experimental study, measurements of the BET
 surface areas were obtained for calcines prepared  by rapid  (less than 5 seconds) calcination
 in the dispersed system.  Ishihara's data clearly showed that the surface areas developed  in
 these  short exposure times  are  considerably greater  than the surface areas  of calcines
 prepared  in  the laboratory  at  the same  temperature (which require longer periods  of
 calcination to achieve complete conversion of CaCO3  to CaO). The surface areas produced
 by calcination in the dispersed phase were 20-30  m2/g, an order of magnitude  greater than
 that of  laboratory  calcines.  This  difference in  surface  areas*  provided  the  basis  for
 reconciling the  discrepancies  between  reaction rates  measured  in isothermal laboratory
 experiments and the observed reaction  rates in dispersed systems. Good correlation of the
 two independent sets of data was in fact later achieved.
~k
 The existence  of large surface areas immediately following dissociation of CaCO3  had been
 previously postulated by  Mayer  & Stowe8 from consideration of molecular rearrangements
 that must  occur when  unit  crystal cells are altered to the CaO configuration.  Absolute
 surfaces as great  as 103  m2/g were estimated.

-------
                                          J-9

       Although Ishihara's objective was not specifically that of modeling the reaction, he
did quantitatively evaluate the effect  of each  process variable—in  much  greater detail than
was done in any other  pilot plant study. He  correlated his data according to the simplest
possible model for chemical reaction control,
                 r = d(CaO conversion) = k C<~r\
                    	dt	     S°2                                     (3)
                 where k = Ae "E/RT
                 and    T = f(t)
Comparison of this  model with equations (1)  and (2) shows that it is the same as that used
successfully to correlate the initial isothermal rate data for precalcined stones,  where k =
kssg.
        Ishihara determined the value  of  k  as a function of  each  of  the  major process
variables: temperature  (time), particle size, SO2 concentration, limestone type and injection
temperature.  He analyzed his data on the basis of instantaneous rates measured at a given
value of temperature (time) in the reactor. This approach assumes that the rate is a function
only  of  temperature and  SO2 concentration,  i e., that  the rate at t > 0 is independent of
sulfation and  surface area. It should be noted that surface and sulfation effects are, therefore,
reflected in the factor  A in  equation  (4), which will also be a function of temperature and
time if these effects  are significant.
        This simple  model  proved  to be an  extremely effective tool for the qualitative
analysis  of limestone injection data.  Figure 2 shows a plot of the reaction rate constant as a
function of the instantaneous temperature and injection  temperature.  Several  important
responses are  revealed by this plot. The slope  of each line  reflects the activation energy of
the reaction and also any  effect of sulfation  and/or surface area. Considering the straight
line representing injection at the lowest temperature (910°C) it is clear that the rates are a
linear function of temperature  over the full  (order of magnitude) range of reaction rates
observed. One may thus conclude that sulfation alone  has a minor effect on the apparent
activation  energy.  Otherwise the  slope of this  line would change  with  1/T (and  time),
reflecting the  effect  of accumulated sulfate. The observed independence of activation energy
from sulfation effects  is in accord with Howard's conclusion regarding the  constancy of
activation energy over a broad range of conversion for  the isothermal reaction of CaO with
SO2.
        Comparing  the 910°C curve with  the  other curves in  Figure  2, representing  higher
injection temperatures, it is clear that the slope increases with temperature. Since sulfation
has  a negligible effect  on  apparent  activation  energy (slope) it  is clear that the  rapid
deactivation indicated  by  the  change  in slope  with  injection temperature  is a result of
factors  other  than  sulfation. Ishihara  attributed this change  to the loss of surface area at
high temperature and to internal diffusion resistances as sulfation progressed.  In view of the
above discussion regarding the effect of sulfation on activation energy, surface area is clearly

-------
FIGURE 2
       2200°F
2000°F
 1000
                                J-10

                          INJECTION TEMPERATURE
  1800°F
                0.5   1.0   1.5   2.0  2.5
        7.0
7.5
8.0      .8.5
1/T x 104 ? ct
9.0
10.0
             ARRHENIUS PLOT FOR  THE REACTION OF CAO WITH S02
          SHOWING  THE EFFECT OF  GAS TEMPERATURE AT  INJECTION POINT

-------
                                         J-ll

the primary factor responsible for the observed change in reaction rate with temperature. As
additional evidence of this fact it should be noted that the apparent activation energy in the
final stage (about 25  K cal), where the effect of temperature no longer influences surface
area, is the same magnitude as the activation energies measured in the laboratory for calcines
of fixed pore structure.
       It is informative to  put  Ishihara's model in integrated form for comparison with the
other models. Equations (3) and (4) are not directly integrable, however, as shown in Figure
2, a plot of Ishihara's  data  for the time-temperature profile of his reactor2 shows that 1/T
can be approximated accurately over the short time periods used in  his experiments by
                                    1  'v
                                    T  =  Ct
               so that               dx  ^   Ae"Ect
                                    dt  ~

where E is  the apparent  activation  energy,  or  slope, of  the  lines shown in  Figure 2.
Integrating,
                             X ^  - £•   e -Ect   + c
                                     '-c
                        since x = 0 at t = 0, C =  A/Ec and
                            x  2  A    (1_e -Ect}                                 (5)
                                  ^-\~f
As is evident from the  previous discussion,
                              A = f (Sg-cs02)
A comparison of equation  (5)  with that derived  independently by Coutant using emperical
curve-fitting techniques will be made in the next section.

    Dr. Robert W. Coutant - Battelle Memorial Institute
       Fundamental experimental studies9  of reaction kinetics in a dispersed phase reactor
were begun at Battelle in  1967 under CSD sponsorship and continued through 1971. The
reactor used  in this investigation was designed specifically to permit  close control  over the
reaction  variables and to   permit  independent study of  each  variable upon the  reaction
kinetics.   Its  unique  features  were  (1)  particles  could be  reacted  at  constant  SO2
concentration and (2) particles  could be injected and collected over varying residence times
from 0.2 seconds to over 2 seconds thus  both calcination and sulfation could be followed
directly by particle analysis.
       Following  Ishihara's report in 1970, the Battelle research  was directed specifically
toward verification of  the  effects  of surface area  on S02  reaction suggested by Ishihara's
data. A series of experiments in  which limestone particles were "flash  calcined" over varying
ranges of time  and injection  temperature (with  no SO2 present in the flue  gas)  soon
confirmed  the  existence of large  BET surface areas immediately following calcination and

-------
                                        J-12

further  showed that the surface decreased rapidly with residence time. For example, 90 y
particles injected at 1950° F yielded surface areas of 60 m2/gCaO  jn 0.2 second residence
time, which decreased to 30 m2 /gCaO after one second.
       The BET surface areas and corresponding SO2 reaction rates obtained in the Battelle
reactor were compared with the isothermal reaction rate-surface area data obtained from the
EPA differential reactor experiments.  The results of this  comparison, shown  in Figure 3,
demonstrate excellent correlation between the two sets of data. The agreement confirmed
that the high  reaction rates observed  in the non-isothermal dispersed system is predicable
from its surface  area and  the  intrinsic chemical reaction rate constant  (0.22  cm/sec at
980°C)  measured in the laboratory. The agreement also indicates that chemical reaction is
the  primary  limitation on  the  initial  rate of  SO2  absorption by  the dispersed particles,
verifying the  absence of gas-phase mass transfer limitations as inferred  by Howard and
 Ishihara from  independent consideration. Clearly,  the maximum  rate is  determined by
chemical reaction rate, and consequently, also by surface area.
        The development of mathematical  models  of both the sulfation and calcination
 reactions was  an  objective of the Battelle  project. The  approach used  in modeling  the
 sulfation step did not presuppose any specific reaction controlling mechanism. The observed
 responses of sulfation, S, vs. time were fitted empirically to obtain the best correlation with
 time and temperature. Unfortunately, only one  particle size, 90jj,  was modeled. Coutant
expressed the  results in the form1 ° :
                                 s =  b(l-e'kt)                                      (6)
           where      k =  exp  (14.563 - 18734/Tm)                                 (7)
                      b =  exp (-2.982 + 10139/Tm)                                 (8)
 It should be noted that Coutant's model expresses the coefficients in terms of mean reactor
temperature,  Tm, rather than the instantaneous temperature at time t.
        Comparison of equation  (6) with the integrated form of Ishihara's chemical-reaction
control  model  Equation 5 shows that they are identical if  b = A/Ec  and  k  =  EC.  The
injection-temperature  dependence  of  the slope of  Ishihara's curves, EC, is confirmed in
Coutant's  equation  (7). Likewise the  dependence of  Ishihara's  coefficient  A/Ec  on
temperature in an inverse manner from EC is reflected by equation (8). The  primary features
of both sets of data are summarized by the same basic model which requires no assumption
more complex than chemical-reaction control to explain all  observed effects.
        The coefficient b was identified by Coutant  as the  maximum (terminal) conversion
achievable  under given injection  conditions. The value b decreased with increased injection
temperature and since A = bk,  Ishihari's factor A also decreases with increasing injection
temperature, thus reflecting the  effect  of loss of surface area on the overall reactivity. Thus,
for 90jJ  particles,
                      A =  f (Sg) - 2.45 e -8595/Tm

-------
                       J-13
                                                FIGURES
 5
  CT>
 o
 m
 o:
 UJ
 ti-
  ro
 O
 c/o
  CO
      18

      16

      14

      12

      10

       8

       6
      2

      0
           CALCINATION TEMPERATURE
            •  790°C
            A  890°C
            V  980°C
            • 1100°C
                            Sg=7.3X104cm2/g
              Sg=5.0xl04cm2/g

              ^^
              Sg=2.4xl04cm2/g
              ^  •
              Sg=0.95xl04cm2/g
I  i  i  I   i   I  i   I  I   I  I   I
             20    40    60    80   100   120  140
                   TIME, SECONDS
ISOTHERMAL SORPTION OF SO? BY TYPE 4 LIMESTONE AS A
FUNCTION OF SURFACE AREA OF ITS CALCINE.
REACTION TEMP=760°C;PARTICLE SIZE=0.0096 cm;S02=3000 ppm

     300,	
                    SLOPE= 1
in
 o
O
 to
 CD
 O)
'o
 E
 en
     100
       10
       1
     0.5
                      DISPERSED  PHASE
                      REACTOR TEMPERATURE
                            Q1008°C
                            «1060°C
UJ
o:
        103
     104         105
      Sg,cm2/g
106
  COMPARISON OF INITIAL SQ2 REACTION RATES IN
  DIFFERENTIAL  REACTOR,ISOTHERMAL (980°C,Dp =0.0096 cm)
  AND  DISPERSED-PHASE REACTOR
                  S02 = 3000 ppm

-------
                                         J-14

This loss of surface area at high temperatures is brought about by the growth of the CaO
sub-grains that comprise a  lime particle, which has long been  known to be an activated
process11,  i.e., the rate of grain  growth increases with  temperature.  The resulting loss of
surface areas (which is  inversely proportional to grain size) of calcines  prepared at different
temperatures has been demonstrated by Drehmel12 and  Chan etal.13  for calcines prepared
in the  laboratory.
       The Battelle model  thus shows that for a given particle  size, surface area decreases
with time and that the rate of change increases with injection temperature. Examination of
the Battelle data also shows  that the rate of change is  dependent upon particle size. The
comparison of terminal BET surface areas of 90u particles and 48u particles calcined in the
dispersed phase reactor show a marked reduction in surface of the smaller particles:

                                        Table I
                      Effect of Particle Size on Terminal  Surface Area
Particle Size, Injection Temp.
Microns °F
90
48
90
90
48
48
FW
FW
FW
1336
1336
IGS4
2224
2243
2224
2155
2140
2140
Residence
Time, Sec.
1.27
0.99
2.86
1.17
2.08
2.08
Terminal BET
Surface, m2/g
21.5
7.6
21.3
23.7
14.2
8.6
Run No.
925-B
106-F
675-A
317-C
226-B
32-A
        That the small particles would calcine more rapidly than large ones is in accord with
 the  established unreacted-shrinking  core  mechanism by which calcination  proceeds,  i.e.,
 calcines from the outer particle surface inward toward the particle center. Consequently, the
 small  particles  which have  greater particle surface  per unit  mass,  generate greater BET
 surfaces per unit  time during  calcination and of course, complete calcination sooner. This
 fact is clearly shown by the Battelle calcination rate data reproduced in Figure 4.
        The  overall  effect  of this  dependence  of calcination  rate  on  particle  size  is
 dramatically demonstrated by  comparing the Battelle data with Isjiihara's data for the S02
 reaction,  which together  covers  a particle  size  range from 90ju to  3.4 u.  Figure  4
 demonstrates the  remarkably  good agreement between the two sets  of data when directly
 compared.  Remember  that  these  data  were obtained  from  completely  different  reactor
 designs, operating at  vastly different  injection stoichiometries, and that one  set  of data was
 obtained  by  gas  analysis while  the other set  was obtained by  particle analysis. This
 comparison should be particularly  noted by those who have despaired over apparent lack of
 consistency among results of various investigators  of the limestone injection process. All of
 the essential features of the  dispersed reaction are reflected in these  curves: the increase  in
 initial  rate as particle size is reduced, resulting from higher rates of surface  generation, the
 flagging of the reaction  in smaller  particles when calcination is completed and everburning

-------
                                           PERCENT CALCINATION


                                                     75
                                        90p PARTICLES
  0.140
                                                                                            10.5p  >ISHIHARA
                                                                                                      DATA
                                                                                            20.5p
C\J
o
   0.070 -
o
o
T)
CJ>
                                                    COMPARISON OF  ISHIHARA AND  COUTANT  DATA

                                                    FOR  DISPERSED  PHASE REACTION OF CAC03 WITH  SOo
                                                                                                              (Jl
                   0.2
0.6          0.8          1.0


    RESIDENCE TIME, SECONDS

-------
                                         J-16

occurs. The rate of flagging clearly increases as particle size is reduced, reflecting the rapid
loss of surface area and reaction rate by the small particles. The overall result is a very small
gain in terminal conversion despite a 30 fold decrease in particle size.
       The flagging of the reaction when particle size is reduced is the most critical feature
of the limestone injection process,  as it determines  the ultimate  limit of  CaO conversion
(and SO2   removal efficiency) that can be obtained  by injection into the boiler furnace. The
fact that the dispersed  phase reaction  ceases after a  fraction of the total residence time
available has been reported in the pilot injection  studies of, Juntgen1 4 , Peabody Coal15,
Florida Power/EPA16,  Babcock & Wilcox17  as well  as the data discussed here.  Previous
attempts to account  for this flagging have generally assumed that  product shell  formation
was responsible. This assumption is  not consistent,  however, with the small gain in  terminal
conversion. If shell diffusion  were limiting SO2  sorption at  the terminal  point, the total
conversion  would  increase in direct  proportion  to  the reduction in  particle size.  The
assumption of  shell diffusion is also inconsistent with the activation energies  observed by
both Coutant and Ishihara, which exceed that of diffusion by an order of magnitude.
        The effect of S02  concentration has been shown by both  Coutant and Ishihara to
have  only  a  slight effect  on terminal CaO  conversion in  the  dispersed system.  Each
investigator showed that  CaO  conversion  increased approximately with  the 1/2 power of
initial  SO2  concentration.  Ishihara  concluded that the instantaneous reaction rate follows a
first  order  response  to  S02  concentration,  in  agreement  with  isothermal   kinetic
measurements4'18 'l 9.  The effect  of SO2 concentration cannot be  evaluated independently
of the other factors in the Battelle model, in which it  appears as part of the factor b, which
includes surface area. Ishihara, by  measuring instantaneous rates at different SO2 levels, was
able to separate out the  surface area effect. The evidence, therefore,  suggests  that the
reduced overall effect of SO2  results  from the change in surface  area with time and its
cumulative effect upon the chemical reaction rate.

   Professor Robert L. Pigford, University of California
       This model20  is based upon fundamental descriptions of processes occurring within
a lime particle during S02  sorption. Like the MIT model it  considers the particle as an
assemblage of nonporous  CaO grains surrounded by interstices through which SO2  diffuses
prior to reaction at the grain surface. The model assumes the overall rate to be controlled by
diffusion through this pore structure coupled  with  diffusion through a product layer which
forms  on  the CaO grains as  the  reaction proceeds.  Chemical reaction  at the grain/shell
interface is  assumed to be so rapid that it contributes no resistance to SO2 sorption. The
model, like  the MIT model, considers grain size and pore structure to be a function only of
conversion  and  independent of temperature or time.
       The model accounts for variation in the extent of participation of the interior grains
depending  on  pore  structure and  position within the particle. In the extreme cases where
pore diffusion controls or grain product-layer diffusion controls, the model reduces to two
basic forms that correspond to a particle surface reaction or a particle volume reaction.

-------
                                         J-17

       Case 1 - Superficial surface reaction:
       S02 sorption rate =  13.6 (a1/2 D!/2 r^l/4 s 1/2  r 1/2 R2 CQ 3/4 /  l/2tl/4)
         per particle
       or, Rate per      
-------
                                    J-18
FIGURE 5


   l.Or
   0.1
o
o
CJ>

o
            3.4
                     48
                              90 y
   QjQll   I  I  I  I  I
J	L
      .05        0.1
                        1.0
                              9 SECONDS
           TEST  OF PIGFORD  MEL WITH 3,4 AND  48 MICRON  PARTICLES

-------
                                         J-19

   Professor C. Y. Wen, West Virginia University
       After  extensive  review  of  isothermal  reaction  rate data, including  experiments
conducted in the Chemical  Engineering Laboratory of West  Virginia  University.  Ishida and
Wen formulated a model based upon the zone reaction concept2 1 . The lime particle is again
visualized as an assemblage  of CaO grain to which SO2 diffuses through the pores between
grains. Whereas Pigford coupled  pore diffusion with diffusion through a product shell on the
grain  surface,  Wen coupled  it with chemical reaction at the  interface between the product
layer  and the  unreacted grain core.  Wen's  model is unique in that it has been applied to the
correlation of  both isothermal  laboratory data, and non-isothermal data from dispersed
systems, including full scale boiler injection.  It has successfully  correlated the observed
reaction  rates from all  of these sources.22
       The chemical  reaction rate  is  expressed in  terms of the reaction  rate constant per
unit surface and  the surface area  per unit  volume of lime. The latter is determined  by the
radius of the  unreacted core, rc, within  the CaO grain at time t. Thus, when the original
grain  radius is FT, and the  particle  size is  small enough for  S02 concentration to equalize
throughout the particle volume,
       rate per unit mass CaO =-^-3  ks  CSO2  r^                                 (9)
                               (FV)
Since rc= R' at t = 0,  the initial rate is inversely proportional to BET surface area. At low
conversions and small  particle size the model thus reduces to the same form used by EPA to
correlate isothermal data.
       A  more complex form  of  the model  can be  applied  to  large  particles in which
diffusion effects are also important. The  theory of gas-solids reactions  in which diffusion
and reaction occur simultaneously was rigorously developed by Prof. Wen over the period
1967-71. By comparing observed reaction rates with the theoretical curve for particles of
different diameter, Wen  was able  to estimate  the diffusion  modulus for the isothermal
reaction  of SO2 with  calcined limestones.  The model also enabled him to separate out the
intrinsic reaction  rate free from  diffusional effects. The reaction rate  constant was  thus
evaluated  for data  from varying  sources  over  a wide  range of temperatures  as shown in
Figure 6. The value of the reaction rate constant and activation energy is established  by this
correlation and can be directly applied to the modeling of non-isothermal systems.
       A complete simulation  of the limestone injection in process was carried out22  on
the basis of the above model, using data from the Shawnee full scale boiler tests. Simulation
inputs included the time-temperature profile of the Shawnee boiler, the average particle size
of the limestone, the  kinetic parameters  established in isothermal studies and an assumed
mean CaO grain size of 0.02 p.  A comparison of the results predicted by the simulation and
the results  obtained at Shawnee are shown in Figure 7.  It is evident that the model  is
capable  of  predicting  boiler test results  within about 30  percent at the current level of
refinement of model and assumptions.

-------
                       J-20
0.005
0.6
0.8         1.0
        1/T x 103
                                      1.2        1.4
      RATE  CONSTANT FOR THE GRAIN REACTION  (WEN)
                (KEY TO  FIGURE SHOWN  ON TABLE II)

-------
                   J-21
                  Table II
List of Types of Limestone Particles Examined
  and Corresponding Keys Used in Figure 6
       (C: calcined stone, R: raw stone)

Investigator

Borgwardt4





Borgwardt7


Coutant, et al.9

TVA24

This Study


Key
(3
Q
©
©
©
w
3
€
O
(j)

B
A
0
O
O

Form
C
C
C
C
C
C
C
C
C
C
C
R
R
C
C
C

Type Stone
Dolomite
Limestone
Limestone
Limestone
Calcite spar
Limestone
Limestone
Dolomite
Aragonite
Marl
Limestone
Limestone
Limestone
Pelletized
CaO

CaO
(wt% in calcine)
55
54
94
81
98
95
96
58
97
88
90
90
90

100


-------
                             J-22
FIGURE?
 Q
 UJ
 Q.


 I/O
 CO
 LlJ
 Q
 LU

 
-------
                                         J-23
                                    III.  Discussion

       As  a result  of the  combined efforts  of the  modeling  activities and  extensive
experimental investigation, considerable progress has been made toward an understanding of
the phenomena on which the limestone injection process is based. A thorough and objective
evaluation of the complete data available reveals considerable consistency and agreement on
the effects of each of the major process variables on the effectiveness for SO2 removal. The
summary  outlined here has focused upon  the most critical of these variables—those which
directly bear upon the ultimate potential of the process for pollution control purposes.
       The first  fact that can  be  regarded as established is that  mass transfer of  SO2 to
particle surfaces does not limit  the rate of SO2  capture in dispersed systems. This has been
shown by the calculations performed by Howard and Ishihara and independently confirmed
by the correlation of measurements of the initial  reaction rates measured under isothermal
conditions in the laboratory.  Further experimental proof is provided by the high sensitivity
of the  dispersed  phase  reaction  to  temperature  as  shown  by  the activation  energies
determined  by Coutant and  Ishihara, and  the lack of any effect of  stoichiometry upon CaO
conversion,  shown by Ishihara.
        It follows from this fact that the ultimate limitation to SO2 capture by injection of
limestone into a boiler is associated with intraparticle effects—either diffusional or chemical.
It is further established that the initial rate of  SO2 sorption, i.e.,  the highest possible rate
achievable,  is determined by the intrinsic chemical reaction rate of CaO with  SO2. The rate
of decay of this high initial rate determining  the efficiency of the process can be attributed
to three  possible causes:  (1)  formation  of  a  product shell  on the particle surface,  (2)
formation of product shell on individual CaO grains within the particles or (3) reduction in
chemical reaction rate due to loss of surface  area as a result of grain growth. The effect of
the process variables on the anticipated rate are  different in each  case  and comparison of
models  with the established characteristics  of the  reaction  permits this question to be
decisively answered.
        In the  summary  of  Pigford's model  it was  shown that severe  discrepancies exist
between the observed effects of temperature and particle size and the responses predicted
by the  model. The model is likewise in conflict with the effect of SO2 concentration and
the established activation energy  of the isothermal  reaction.  Although the postulation of
diffusional resistances as the rate limiting  factor is intuitively appealing, particularly for the
final stage of reaction,  it  is not consistent with the observed characteristics of the reaction.
       The assumption of a combination of  diffusional  and chemical  resistances to be
controlling, as  exemplified  by  the MIT model, is also in serious conflict  with experiment.
The failure  of the model  to  properly predict  reaction profiles as determined by microprobe
analysis, was later pointed up when Wen evaluated the diffusion modulus at 1/30 the value
estimated by the MIT model. Likewise, the effective diffusivity was determined to be about
0.07 cm2/sec.  rather  than  the 0.2 cm2/sec  initially estimated by MIT. The variation of
surface area with particle size was  disproven  by BET measurement and the predicted effect
of temperature on surface area  also failed: after calcination at high  temperature, the surface

-------
                                         J-24

 area is independent of  particle size or reaction temperature. In view of the fact that Wen s
 model also assumes diffusion to be a major resistance  under certain conditions,  and is
 entirely  consistent with experiment, one  can only conclude that the MIT model  contains
 mathematical errors, or that the equations have solutions that were not recognized.
        The attached table summarizes the principal  experimental  results with which any
 useful model must  be  in substantial  agreement.  Each model discussed here is qualitatively
 compared with these results. Also included in this comparison are the predicted responses
 for pure shell diffusion, since this mechanism had long been regarded as the most probable
 limitation of  the process.  It is clear  from this table that shell diffusion  is inconsistent with
 nearly every one of the observed responses,* and  need  not be further considered.
        The  best general  agreement  with experiment  is, of  course,  obtained with the
 empirical models. The  Ishihara and Coutant models are combined for this comparison since
 it  was  shown  that they are  both  representative of homogeneous  chemical reaction,
 influenced by strong surface area effects. It is assumed in this comparison that the effects of
 time, temperature and  particle size that have been established are taken into account when
 applying the model.
        The   Wen  model   is again   the  same   homogeneous  representation  as  that  of
 Ishihara-Coutant, except that it specifically identifies the  surface area with the CaO grains
 within the calcine  particle. It therefore lends itself to quantitative treatment  of the surface
 area  effect independent of the other parameters and  will  ultimately be the most generally
 applicable form of the model for predictive purposes.  The Wen model is the only form
 which can be applied to the complete  range of homogeneous, zone and shell reactions for
 both isothermal and nonisothermal reaction conditions. The primary limitation in accuracy
 of the Wen  model  is that there is no way to predict  grain size a priori  from  given process
 conditions. Thus, in applying his model to simulate  the  Shawnee boiler, a constant grain
 radius is assumed,  i.e.,  surface area does not change with time and is  independent of particle
 size  or  injection temperature.  The  data  of  Ishihara and Coutant clearly show that  this
 assumption  is not  correct, but it does permit one to formulate a first approximation. As
 shown  by Figure 5, this approximation is limited  in accuracy  to ±  30% of the observed
 efficiency. The predictive accuracy of Wen's  model would no doubt be greatly improved if
 Ishihara's data on the effects of particle size and injection temperature were incorporated to
 account for  changes in grain radius with residence time. This modification would probably
 also  bring  the  model   into agreement with the  first order  kinetics established for the
 isothermal reaction  (fixed  grain size).
        The  preponderence of evidence resulting from the work of Ishihara, Coutant and
 Wen  overwhelmingly favors chemical reaction as the controlling mechanism of the process.
 This  mechanism is the  only  one  consistent  with  all   of  the facts, and  the  ultimate

*Microprobe analysis of the cross sections of particles  reacted in the  Shawnee boiler23 show
 homogeneous distributions  of  reaction product  within particles smaller than about 40)J.
 Particles larger than 40u show distributions similar to those proposed by Wen for zone-type
 reactions.

-------
                                                       Table III

                               Comparison of Model Predictions With Experimental Results
Experimental Results
Particle size effect
Temperature effect
Surface area-initial rate
Surface area - particle size
Terminal Conversion - particle size
Isothermal reaction rates
SO2 concentration
Act. energy-conversion
Isothermal reaction profiles
Nonisothermal reaction profile
Overburning - SO2 reactivity
CaO content of lime
Sulfation effect
Conversion time profile
Total residence time
Terminal conversion -total residence
Homog. chem
reaction
(Ishihara-
Coutant)
V
V
V
V
V
V
(a)
V
V
V
V
V
X
V

time
Chem. react.
shrink, grain
core
(Wen)
V
V
V
X
X
V
(a)
V
V
V
V
V
V
7
V

Pore
diffusion-
surface react.
solid diff.
(MIT)
X
X
V
X
X
V
V
V
X
X
X
V
V
X


Grain shell
diffusion-
pore diffusion
(Pigford)
X
X
V
X
X
V
X
X
V
V
V
X
X
X


Product
layer
diffusion
(Shell)
X
X
X
X
X
X
V
X
X
X
X
X
X
X


                                                                                                                               ro
                                                                                                                               en
(a) Expected to agree when model is modified to account for change in surface area with time.

-------
                                         J-26

self-limitation of SO2  capture  by the lime particles after injection necessarily follows from
the known changes in surface area that occur with  everburning. The low final rate, like the
high initial  rate, can indeed be  calculated from the chemical reaction rate constant and
surface area.

                                    IV.  Conclusions
       The limestone injection process is limited by the rate of chemical reaction which is,
in turn, limited  by the rapid  loss of  surface area (due  to  grain  growth) immediately
following calcination.
       This self-limiting aspect of the reaction necessarily defeats any attempt  to improve
performance by manipulation of process  variables, e.g.,  particle size, injection temperature,
particle/gas distribution.
       The efficiency of  SO2  removed,  within these limitations, can  be  successfully
simulated by homogeneous reaction models, such as that of  Wen. As a first approximation,
assuming constant  grain size, such  a model will  predict  results  within  30%. Improved
accuracy must rely  on empirical  correlation  of particle size and  temperature effects. Data
for such correlations are already available.
        The limit of  efficiency for the process, as determined from experiment, is 20 percent
per stoichiometric injection.
        Regardless of kinetic limitation, CaO  utilization  cannot exceed 50% due to physical
limitations of the reaction.

-------
                                       J-27

                                   V. References


 1.  Howard, J.  B., Williams,  G. C., and Ghazal, F.P.H.:  "Mathematical Model of the
    Reaction Between Sulfur Dioxide and Calcine Particles,"  Final Report on Task No. 2
    of HEW-NAPCA Services Contract NA. CPA-22-69-44, September 23,  1971, prepared
    at the Department of Chemical Engineering, Massachusetts Institute of Technology.
 2.  Ishihara, Y.: "Kinetics of the Reaction of Calcined Limestone with Sulfur Dioxide in
    Combustion  Gases,"  paper presented  at  the  Dry  Limestone  Injection   Process
    Symposium, Gilbertsville,  Kentucky, June 22-26, 1970, sponsored by Control  Systems
    Division, EPA.
 3.  Ishihara, Y.: "Removal of  Sulfur  Dioxide  from Flue Gases by the  Lime Injection
    Method," paper presented at CSD LimestoneSymposium.Clearwater, Florida. December
    4-8, 1967, Central Research  Institute of Electric Power Industry, Japan.
 4.  Borgwardt, R. H.:  Environmental Science  & Technology 4  (1) 59  (1970).
 5.  Borgwardt, R. H.: J. Eng. Power  92 (2) 121 (1970).
 6.  Drehmel,  D.  C.:  "Tests for Overburning of  Calcined Limestone," paper presented at
    the Dry Limestone Injection Process Symposium, June 22-26, 1970.
 7.  Borgwardt, R. H.: "Isothermal Reactivity of Selected Calcined Limestones with SO2 "
    paper presented at the Dry Injection Process Symposium, June 22-26, 1970.
 8.  Mayer,  R. P.,  Stowe, R. A., "Physical  Characterization of Limestone  and  Lime,"
    Report to National Lime Assoc.,  Washington, D.C. (1964).
 9.  Coutant,  R.  W.:  "Investigation  of the  Reactivity of  Limestone and  Dolomite for
    Capturing  SO2  from   Flue  Gas,"  Final Report for Contract No.  PH86-67-115,
    November 20, 1970, Battelle Memorial Institute, Columbus, Ohio.
10.  Coutant,  R.  W.:  "Investigation  of the  Reactivity of  Limestone and  Dolomite for
    Capturing SO2  from Flue  Gas,"  Final Report for Contract  No.  CPA 70-111, October
    1, 1971, Battelle Memorial Institute, Columbus, Ohio.
11.  Fischer,  H.  C.,  "Calcination of Calcite:  Size and Growth  Rate of Calcium  Oxide
    Crystallites," J. Amer. Ceramic Society 38(8) 284-88 (1955).
12.  Drehmel, D. C., Ceramic Bulletin 50 (8) 666-70 (1971).
13.  Chan, R. K., Murthi, K. S., Harrison, D., Canadian J. Chem. 48 2979-82 (1970).
14.  Jungen,  M.  and  Juntgen,  H.: "On  the  Reaction of Calcined  Dolomite and Other
    Alkaline Earth  Compounds with  SO2 of Combustion Gases as carried out in a Cloud of
    Suspended  Dust." Report  presented at CSD  Limestone  Symposium,  Clearwater,
    Florida. December 4-8, 1967 Bergbau - Forschung GmbH, Germany.
15.  Whitten, C. M. and Hagstrom, R.  G., J. Engineering for Power 2 (Jan.  1970).
16.  Borgwardt, R.  H. and Kittleman,  T.  A., paper No. 69-141  presented at the Annual
    Meeting  of  the Air Pollution Control  Association,  New York. June 22-26, 1969.
    Control Systems Division,  EPA.

-------
                                       J-28

17.  Attig,  R. C.  and Sedor, "Additive Injection for SO2  Control," Final  Report for
    Contract  No.  DH 86-67-127,  March 27, 1970, Babcock  & Wilcox Research Center,
    Alliance, Ohio.
18.  Hatfield, et al., "Investigation  of the Reactivities of Limestone to Remove SO2  from
    Flue  Gas;"  Final Report for Contract Nos. TV-29232F and  TV-30530A   (1971)
    prepared by Tennessee  Valley Authority,  Division of Chemical  Development, Muscle
    Shoals, Alabama.
19.  Coutant, Contract No. PH 86-67-115, Quart. Report for Dec. 12,  1967, p. 6.
20.  Pigford,  R.  L., "The  Rate of  a Diffusion-Controlled Reaction  Between a Gas and a
    Porous, Solid  Sphere - The Reaction of SO2 with CaCO3," June 1971, University of
    California.
21.  Ishida, M., Wen, C. Y., AlChE Journal, 14 (2) 311 (1968).
22.  Ishida, M., Wen, C. Y., "Analysis of SO2-Limestone Reaction-System, Part I: Reaction
    Rate  of  SO2  with Particles  Containing  CaO,  Part II: Simulation  of SO2 - Limestone
    Reaction System." Report prepared for Control Systems Division, 1972 at Department
    of Chemical Engineering, West Virginia University.
23.  Shell  Development Company.  Personal communication to R. D. Stern, March 3 and
    April 16, 1971.
24.  McClellan, G.  H., 4th  Dry  Limestone  Process  Symposium, Gilbertsville,  Kentucky,
    June 22-26, 1970.

-------
             APPENDIX K



Utilization of Limestone-Modified Fly Ash

-------
                                         K-l
                                   APPENDIX K
                UTILIZATION OF LIMESTONE-MODIFIED FLY ASH

       Although the utilization of limestone  modified fly ash  (hereafter as LMF) is not
directly related to the dry limestone injection  process and demonstration of optimum SO2
removal, this section provides an overview of the activities in this area of the overall EPA
program. Additional information may be found in the references.

-------
                                           K-3

                       Utilization of Limestone-Modified Fly Ash

I.  Introduction and Objectives
       The  Dry  Limestone Injection  Process  is a "throw-away"  process  and does  not
depend on the recovery of a salable chemical byproduct. Aware of the increased solid waste
generated by the  process and attempting to avoid aggravating one pollution  problem while
solving another,  EPA initiated an extensive research effort in the early planning stage of the
overall program.  The objective of  this part  of  the  overall program was to determine and
demonstrate  the  utilization of pulverized coal fly ash  modified by limestone. A secondary
consideration was the potential for reducing  costs of the process through potential re-use of
sorbent or byproduct credit.

II. Approach
       The  general approach taken was to  determine current and potential utilization of
unmodified  fly  ash,  assess applicability  of  LMF to  these  utilizations and, based on  its
properties, assess its potential for new applications. Although there are a large number and
variety of industries and  individuals  involved  in the production and use of  fly ash,  the
program  was directed toward coal-burning power  utilities, since this is the major source of
fly ash  in  the  U.S. The  specific approach  was to: (a) perform literature searches  for
utilization of unmodified  and  LMF; (b) correlate reported uses with  analyses of  chemical
and physical properties;  (c) prepare products by simulating current production processes as
closely  as possible;  and  (d) compare product properties and  characteristics with their
commercially available counterparts. Based  on  technical potential, economic analyses and
more extensive  utilization  research were  then  performed or recommended for follow-on
projects.  Because of the  relationship between  the  LMF  from  dry processes  and wet
scrubbing processes regarding  waste disposal and beneficiation,  samples  for analysis and
small scale  product  preparation were  obtained  from  dry limestone injection  programs
conducted by  TVA, Babcock  and Wilcox, Chevrolet, and Detroit  Edison,  and from wet
scrubbing programs conducted  at Kansas Power and Light, Union  Electric  and  Detroit
Edison. Samples of normally produced fly ash were also obtained from these sources.

 III.  Results and Conclusions
    A. Unmodified Fly Ash Utilization'
       Although fly ash is used  in various applications, current utilizations consume only a
small portion of the total amount of fly ash available: of the 26.5 million tons of fly ash
produced annually by coal-burning power plants, only about 1.6 to 2.0 million tons are
utilized.
       All known specifications  for fly ash used  as a material for product manufacture or
application, and  for fly ash products were examined for the purpose of assessing the extent

-------
                                           K-4

to which they inhibit the utilization of fly ash.  Except for the specifications on fly ash as an
admixture in portland cement concrete, specifications do not inhibit the use of fly ash. The
amount of  fly ash that could be technically  utilized  in various applications used today,
regardless of supply and economic  factors, was estimated to identify those areas that would
benefit  most  from  the  increased mass  utilization of fly ash; this indicated  where effort
should be applied to improve the market. Maximum technically feasible uses of at least 1
million tons per year are listed in Table 1, column 1, based on ash composition and possible
product utilization alone. The 1970 actual utilization values for each use, listed in column 2,
total  1.6 million tons per year. As  a result of this survey, it is estimated that if fly ash were
used  in  the  applications  listed in  Table 1 such  that the maximum practical potential would
be  utilized  under  current technology  and associated  market conditions,  approximately 7
million tons would be utilized, as shown in column 3. The significance of this list  is that it
indicates approximately 75  percent of  the  fly ash produced in  the United States is not
marketable  without significant changes being  made  to reduce or eliminate the following
limitations:  (a) inadequate technology and knowledge dissemination related to known uses,
(b) geographic limitations on transportation economics, (c) insufficient marketing efforts,
(d) lack of  control of fly ash production and supply,  (e) cost effects of other materials or
processes, and (f) insufficient development of new technologies.
       The values in column 4 are estimates of  the fly ash that would be consumed  if all the
limitations just cited were removed, except some geographic limitations on transportation.
These values are estimates but they indicate areas where it is believed fly ash can be used in
large  quantities if  appropriate steps are taken.  This approach  limits the area of concern to:
fly ash  concrete,  lightweight aggregate,  road base courses, control of mine subsidence and
fires  and, such new uses or  developments as  gas concrete building construction, ceramic
products, and mineral recovery.
       The following paragraphs discuss the uses shown in Table 1:

       Structural  Concrete
       Fly ash is used in portland cement concrete for the improved properties it imparts to
the concrete.  Among these improvements are pumpability, compressive strength, long-term
strength, workability,  finishability,  resistance to sulfates and alkali-aggregate reaction, and
decreases in heat of hydration, drying shrinkage, particle segregation, bleeding, permeability,
and  leaching. These improvements are well-documented and  have  been  demonstrated
repeatedly  in  actual practice. The net effect is a stronger and  more durable product which
requires less cost  to put in  place and  finish.  For  properly proportioned  fly ash concrete,
early  strength, form removal periods, and curing requirements are not use inhibitions.
       Principal inhibitions to the use of fly ash  in concrete are the lack of a dependable
supply of usable quality ash, and  nonrecognition  of the technological gains and potential
improvements which would  allow  the  use of  various qualities (or classes)  of fly ash and
greater than 28-day design strength criteria.

-------
                                             K-5
                                             Table 1
                              Estimated Fly Ash Utilization Potential
                                     (Million Tons Per Year)
                  Use
                                            1
Maximum Utilization
Technically Feasible
   1970
Utilization
    3           4*

  Estimated Utilization
        Potential
  Current     Improved
Conditions  Utilization
      Fly Ash Concrete (Structural,
      Mass and Concrete Products)

      Lightweight Aggregate

      Raw Material for Cement

      Bricks

      Filler in Bituminous Products

      Base Stabilized for Roads

      Agriculture and Land
      Reclamation

      Control of Mine Subsidence
      and  Fires

      Structural  Fill for Roads,
      Construction Sites,  Land
      Reclamation, etc.

      Others (mineral, wool, gas,
      concrete, misc.)

      Total
10-15


13

13

10

1-2

> Annual Production

> Annual Production


> 1


> Annual Production
   0.54


   0.21

   0.16



   0.13

   0.11
   3.5
6.0'
   0.01
   0.32
                        0.16
                        1.64
   0.5        >3.0***

   0.25       ****



   0.75       ****

   0.3       >10.0
   0.75
   0.6
              0.25
              6.9
     *Values in Column 4 are scaled against the current market, but may take as much as 5 to 10
      years for realization with maximum efforts.
    **Value can be increased considerably with use of fly ash gas concrete in building construction.
  ***Has potential for accelerated future growth well beyond the proportions shown here.
 ****No appreciable increase.
*****SJgnjfjcant increases are possible through new developments such as ceramic products and
      mineral recovery.

-------
                                           K-6

       The  choice of concrete cure time should  be based  on the economics involved with
construction. Since the cost impact on materials by using  fly ash is often small relative to
the cost  of  placing and finishing the concrete, the design  conditions should be dependent
upon the construction requirements. However, the state-of-the-art in concrete construction
requires design  compressive strengths of 28 days  and does  not include an optimal cure time
in the total  economics. A cure time  of 28 days represents the point at which  portland
cement concrete attains  up  to  90  percent of  its ultimate  strength and is  considered
representative of the true strength of the concrete. However, in concrete containing fly ash,
28-day cure times are arbitrary and meaningless since the strength tested  at that time does
not represent the ultimate strength of  the concrete when fully cured, which occurs after 28
days. Using  a 90-day cure, for example, allows more fly ash and less cement, provides higher
strength, and affords advantages  in pouring, pumping, and finishing. While the concept  of
28-day design strengths largely dominates the concrete construction  industry, there are few
examples that  can be cited in which structures under construction experience their design
loads in  28  days. Until the concrete construction  industry becomes  aware of the increased
latitude in concrete mix design that is offered by a technology using fly ash in an effective,
economical  manner, an inhibition to the use of fly ash in concrete will persist.
       Significant deterrents to the massive  use of fly ash in concrete, assuming an adequate
supply and  improved technology, are the requirements for additional storage and  handling
equipment at the  ready-mix  plants, and  hauling costs. The economics of fly ash  concrete
related to the  ready-mix  operation was investigated to determine if storage, handling, and
hauling  costs  are  inhibitory  factors  since  the  literature  is  weak in this  respect. The
investigation could not  include a  detailed, comprehensive cost analysis within the  scope  of
the project  funds because of:  (a) the numerous variables involved, plus the variation in costs
from region to  region; (b) the use or nonuse of beneficiation of the  fly ash, brokerage fees,
and  financial assistance to ready-mix dealers for new equipment; and  (c) sliding costs related
to local competition. The analysis was therefore limited to  estimates  of the more significant
factors,  i.e., costs of fly ash F.O.B. utility, cement, truck hauling, new equipment, and
chemical admixtures.
       Strict conclusions  cannot  be drawn from this analysis  because of the  many cost
variations involved  for  each  case; however,  indications are that a dealer  can increase his
profit before taxes by approximately 50 cents per cubic yard if high quality fly ash  concrete
is delivered  within 10 miles of the fly  ash source, or he can break-even at about 150 miles.
On the other extreme, there  is the possibility of  a combination of circumstances, including
the use of low-grade fly ash, which indicates that the user will not be  able to match  portland
cement air-entrained  concrete on  an  equal production economics basis.  In most  cases,
however, the dealer  should be able to produce fly ash concrete to compete with  portland
cement concrete for haul distances of approximately 50  to  150 miles, depending on the
many cost factors involved. Since the profit, before taxes, on portland cement concrete is in
the range of $2 to  $3 per cubic yard  (according to various personal contacts), a  potential

-------
                                           K-7

increase  of  20 to  50  cents  per cubic  yard would  be appreciable  to the  dealer. If
circumstances, as noted above, increase the cost to  the dealer, that increase is generally small
enough  to  be absorbed by  the  contractor who stands to benefit  from the economic and
technical advantages of using fly ash concrete. Production costs of fly ash concrete can be
reduced rather dramatically in consideration of the utilization of greater-than-28-day design
strengths described earlier. Using this technology where applicable  can reduce cost for any
type of concrete, and  for some, the reduction can be  well in excess of one dollar per cubic
yard.
        Barge or rail transport provides a less expensive means of hauling fly ash than truck,
but  is  applicable  to  only  certain  geographic  situations. Since  the  development and
acceptance of a standardized fly ash concrete technology by the concrete industry would
expand the market  and  bring a  large  percentage  of the power companies into the supply
market,  any transportation  inhibition would be significantly decreased  in  most of  the
eastern  half of the country.
        In summary, current specifications on fly ash as an  admixture in Portland cement
concrete inhibit the use  of fly ash.  There  are  individuals and  organizations who,  by
combining  the  production  or  procurement  of   quality  fly  ash,  appropriate  concrete
technology, and dissemination of the knowledge,  have  marketed fly ash  readily within  the
limits of existing  specifications (ASTM or Federal  Bureau Specifications) or have written
their own (e.g., TVA). Since the general fly ash user and producers have not done this  the
use of fly ash concrete is not widespread.  The lack  of understanding of fly ash concrete by
the general public and  isolated cases of fly ash misuse and the dissemination of inaccurate or
misleading  information concerning fly ash (e.g.,  broadcast of the  term "waste  product,"
intolerable low early  strength,  and bad color)  have  inhibited  involvement  by potential
dealers, contractors, architects, and engineers.  Power companies (with few exceptions) have
not taken the initiative to improve the quality of fly ash or to maintain a consistent quality.
Improvement in that area would undoubtedly  relax the inhibitions to the use of  fly ash by
giving potential users the assurance of having a readily available supply of a quality grade of
fly ash. It is  believed that a considerable portion of the fly ash produced today is usable as
an admixture in portland cement concrete.
        The continued development and  acceptance of properly proportioned fly ash in
concrete is likely to  provide the basis for renewed interest in fly ash as a concrete ingredient.
Intensive  sales  campaigns,  although  beneficial,  have  been effective only  locally.  When
concrete users  become fully aware of the range of advantages and properties that properly
proportioned  fly  ash  concrete  offers, their reluctance to  use fly  ash  in  concrete should
diminish; this should create an increase in demand.

        Mass Concrete  and Concrete Products
        Fly ash is  used in much  of the  mass concrete construction (e.g., dams and spillways)
undertaken  by the U.S. Army  Corps of  Engineers and  the Bureau of  Reclamation.

-------
                                           K-8

Specifications exist for this use and fly ash is proportioned accordingly, principally to lower
the heat  of hydration and also for its pumpability feature. Technically, a larger percentage
of fly ash could be used in these structures; however, the present proportioning is adequate.
The bulk of this work is being performed in the western United States where fly ash must be
transported for long distances, thus reducing economic incentive. Fly ash may become more
economically desirable with  construction of new coal-burning power stations opening in the
West. Usage may increase but the small number of such  projects makes this potential use a
small percentage of the national fly ash supply.
       Concrete products such as  building blocks, pipe,  and precast units  represent a very
attractive field for fly ash usage. Fly ash is used for this application and is well accepted; its
principal drawbacks are the  lack of guaranteed quality ash and transportation cost limits. If
this industry were exploited  to its fullest extent, it would consume an estimated maximum
of 5 percent of fly ash production.

       Lightweight Aggregate
       The predicted high future demand for lightweight aggregate is based on dwindling
supplies  of natural aggregates plus the increasing recognition by architects and engineers of a
future demand for large-scale usage of lightweight concrete. Present developments of  fly ash
lightweight aggregate production technology in the United States,  Canada, and Germany
were reviewed. All are  still  in various phases of development and are attempting to solve
technical production problems.  Lightweight  fly ash aggregate  in  the U.S. is not  yet
considered to be economically competitive product.
       This  is a  relatively undeveloped  industry, and solutions to  its problems are being
sought and incorporated in the process.  Although a quality product can be manufactured,
whether   the  manufacturing  process  and  market  can be  sufficiently  developed  to
economically compete with  other  lightweight  aggregates remains  to be seen. A significant
increase  in the utilization of fly ash for this application appears possible, but not probable in
the near  future.

       Portland Cement Manufacturing
       Fly ash lends itself economically to the production of portland cement only under
certain special situations where the manufacturing plant is not located adjacent to the major
raw material source or where possibly the required mineral deposits are located  close to a
utility. However, in most cases such special situations do not exist. This, coupled with the
fact that there is no  need  for new cement plants since  the  present  market  demands
considerably  less than production capacity, indicates  that the potential for utilizing fly ash
in large quantities for the manufacture of portland cement is relatively low.

       Bricks
       Although fly ash can  technically be used  for making bricks, there  is no shortage of
clay deposits for brick making. The principal sources of fly ash in the United States are all

-------
                                            K-9

close to ample sources of natural raw materials for brick manufacturing. The coincidence of
a depleting source of natural raw materials, a dependable local source of high  quality fly ash,
and a knowledgeable entrepreneur  may determine whether fly ash will eventually find local
application as a brick ingredient. Additional factors indicating that this utilization potential
will  not materialize  appreciably  include:  (a) fly ash brick  manufacturing requires  new
handling equipment  and production  machinery,  (b) fly ash bricks  are  not significantly
cheaper than  ordinary bricks, and  (c) the present United States brick production capacity
exceeds demand.

        Bituminous Filler
        There are numerous  uses for fly  ash  in bituminous products, however, its  use  as a
mineral filler  in asphalt concrete (black  top) pavement  is the major application for large
tonnage usage.  Low quality  fly ash can  be used and current technology is  sufficient.  The
competition  to fly ash includes an array of low cost, abundant materials, all of which are
adequate as a mineral filler. Although this is  a good use for fly ash, particularly considering
the mileage of new asphalt roads (2 to 4 in. thick) or resurfacing of old roads (1 in. thick),
the potential  usage is  not  large, probably  much less than 1 million tons  per year. This
limitation, caused  by competition, is aggravated  by the special problems of storage  and
handling.

        Road Construction
        Except for use as a mineral filler in asphalt or occasional  use as a structural land fill,
road base course applications appear to  be the only practical large-scale use for fly ash in
road building. Although this application has an extremely large potential—technology is
developed   and  a   technical   superiority   over   competing  materials   has   been
demonstrated—certain inhibitions prevent its  substantial growth. Fly ash is not widely used
in road contracts even though its cost is  less  than  or equal to competing materials of equal
strength for urban construction. Proven applications are classified as lime-pozzolan-aggregate
base courses  (pozzolan base),  which  involve  patent rights.  Factual   data  which would
substantiate the inhibition of the use of this material because of royalty  payments were not
found; however, such an excuse  was occasionally given for nonuse.
        The pozzolan base course is used  mostly for urban applications.  Portable mixers are
not widely used, and hauling costs are often  limited  by the use  of materials available at or
near the construction site. However, the amount of paving urban roadways, subdivision
streets,  parking  lots,  and airports represents an extremely  large  market.  Present usage
appears to extend  as far as 40 to 50 miles from the mixing plant. Almost any  fly ash
produced  today is adequate  for this application, and it can be stored outdoors  during the
winter  months and, with minimal processing, can  be used during the construction season.
        Valid  inhibitions to  the  use  of  pozzolan bases were  not uncovered  even  after
contacting  more than  two dozen state highway  departments. Most states are aware of its
benefits but have chosen not to use it. The reasons were almost always vague. The principal

-------
                                           K-10

inhibition may  be that  most  potential users have not  had experience  with  it  and are
reluctant to make a change. A thorough, detailed marketing analysis of road construction
would  be required for the various regions of the country within range of potential pozzolan
base course supplies to determine the justification and advisability of action by government
road contracting agencies relating to the use of fly ash for this purpose.

       Agriculture and Land Reclamation
       Although this application appears to be a method for utilizing large amounts of fly
ash, it  is not economically attractive when compared to the use of lime or other additives to
adjust  soil  pH.  Transportation and  handling  costs appear to be prohibitive for the  large
amounts of fly  ash  that would  be  required.  Generally,  the ratio of fly ash to  limestone
required to achieve an equivalent soil condition or crop yield is sufficiently  high (as much as
30  to  1) to be beyond consideration. Moreover, the presence of certain trace elements often
found  in fly ash would be detrimental to the growth of many common types of vegetation.
Although it may be useful in certain  local areas, it is not expected to be useful on a wide
scale.

        Remote  Filling of Mine Cavities
        Mine subsidence damage to  homes, bridges, and roads is an increasing problem. The
increase, due only partially  to additional mining, can also be attributed to the growing need
for urban and suburban land which has resulted  in building over old mines; deterioration  of
supporting conditions results in surface subsidence many years after mining has occurred.  In
addition to the  subsidence, fires have also become a  serious problem in  abandoned coal
mines. The technology has  been developed  for  remote filling  of  mines and the cost is
estimated at $2.00 to $4.00  per ton within 30 miles of the source if the fly ash is provided
free of charge by the utility. Since many large coal-burning  power plants  are located near
coal mining areas, the filling of abandoned  mines appears to be an  excellent  means for
utilizing/disposing of the entire amount of fly  ash produced by these utilities. Many utilities
are currently incurring  costs of up to $2.00 per  ton to dump fly ash and as much as $4.00
per ton where local regulations require the utility to landscape the land fill  area. This factor
plus the  economic considerations of land value improvement resulting from the elimination
of  mine subsidence could  possibly  justify  the  economics of  this form of utilization,
particularly when more profitable uses cannot be employed.

        Land  Fill
       Where  structural land fill is required  and  hauling distances  are  short, fly ash can
often  be used  more economically  than other  fill materials  and  can provide technical
advantages. Among these advantages  are ease of handling and spreading,  low compaction
density,  and shear  strength that  continues  to  increase  with   time   (a  consequence  of
pozzolanic reaction with residual lime content in  the ash). Fly ash covered with soil provides
excellent drainage for vegetation. Also, any grade of fly ash is adequate and  does not have to

-------
                                            K-ll

be stored, handled, or hauled in an enclosed and dry condition. However, the use of fly ash
for land fill  (excluding fly  ash disposal)  is not  widely applied  in  this country.  It has
demonstrated its usefulness in the  United  States in embankments and abutment backing in
highway construction, but it  is not widely used for these purposes because of the availability
of  natural fill  materials.  Except  for such  special  circumstances as extremely high fill
embankments for roadways  built over weak subsoils  or unavailability of local fill materials,
little use of fly ash as a land fill is expected except for disposal purposes.

        Mineral Wool
        The  use of fly  ash as the  raw material for mineral  wool manufacture  requires no
deviation from the state-of-the-art commercial manufacture of mineral wool; there appear to
be no technical inhibitions to the use of fly ash in this application.
        However, inhibitions are apparent in the comparative economics of manufacture and
in the likelihood of overcapacity  in competition with current mineral wool and  fiberglass
insulation materials. To date, there is no market for fly ash mineral wool.

        Gas Concrete
        Gas concrete is a porous concrete  building material. It is approximately one-fourth
to one-third  the density of  ordinary concrete and utilizes  fly ash  up to  80 percent of the
solid  constituent weight.  Gas  concrete  is  made in  patented European processes and,
although widely used in many foreign countries, is not used in the United States.
        European utilization  of  gas concrete proves to be a highly desirable form of building
material from the standpoint of construction economy and structural  qualities.  It is used in
at  least 20 countries. It is used on a  wide scale in Denmark. Gas concrete is used in West
Germany  in  the construction of 80 percent of all new factory buildings.  In Sweden, its use
approaches   100 percent,  and  in  the Philippine Islands,  it is now  being  used for the
construction   of  low-cost  housing  projects.  In  England,   it  is  estimated  in   1971,
approximately 1  million tons  of  fly  ash  was consumed  in  gas  concrete. Since fly ash
improves the quality (higher strength  per unit volume) of gas concrete, reduces capital and
production costs, and is available in abundance in urban areas, it could conceivably  find a
large  market  throughout the  United States as a constituent of gas concrete. Additionally, fly
ash used for  this purpose does not have to be fine quality; that it can be hauled and applied
in a wet state simplifies handling.
        The  future  of  gas concrete in this  country  is  not readily assessable.  As  a new
technology,  it  would have to compete with numerous well-established building techniques
using conventional  materials. To  establish  fly  ash  concrete  as  a building construction
material on a wide scale would  require substantial technical and economic surveys, coupled
with dissemination of the technology and proven results.

-------
                                            K-12

        Miscellaneous and Potential New Uses
        Such other uses as in foundries, grouting, pipe coating, and oil well cementing are
 considered to have a low potential for the consumption of large quantities of fly ash. A large
 potential exists  for  such  possible  new  uses  such as sewage filtration/soil  supplement
 applications, ceramics and mineral recovery, none of which has been developed.

    B.  Limestone-Modified Fly Ash Utilization
        Limestone injection and/or scrubbing processes for the  control of sulfur oxides can
 increase the  amount of fly ash produced by as much as 1-1/2 to 3 times. These processes, if
 widely  used, could have an appreciable impact on the existing and potential unmodified fly
 ash market.
        Dry collected (LMF) was analyzed as collected and also after separation by mineral
 dressing techniques such  as  sizing,  specific  gravity, magnetic, electrostatic,  and surface
 chemical (flotation) properties.  Results of the whole sample analysis indicated that levels of
 silica, alumina  and iron oxide, the major constituents of normal fly ash, are decreased while
 the lime and magnesia content is  greatly  increased  with  dolomite injection and the lime
 content  is  greatly  increased  with  limestone  injections.  Based  on  extensive  physical
 separations  attempting to concentrate  usable minerals, and utilization tests on the whole
 and  sized fractions of modified  fly ash,  feasibility  of utilizing  modified fly ash in  the
 manufacture of salable products was evaluated. This effort resulted in the classification of a
 number  of  possible  uses  for  the  material  into  the  following  technically   potential
 categories.2'3

    1.  High  Potential
        a.  Mineral wool
        b.  Sulfur dioxide recovery
    2.  Medium Potential
        a.  Acid mine drainage neutralization
        b.  Concrete admixture
        c.  Cement kiln raw material
        d.  Soil stabilizer and amendment
   3.  Low Potential
        a.  Mineral recovery
        b.  Fluxing agent
       c.  Lightweight aggregate
       d.  Fired structural products
       e.  Unreacted calcium recovery
        Following  this  effort the chemical and physical properties of wet-collected LMF
were  analyzed  in addition to  more  intensive analysis of  dry-collected LMF.  Chemical

-------
                                           K-13

analyses  were  performed  using  wet  chemical,  atomic  absorption  and atomic  emission
spectroscopic methods; physical analyses, employed mineral dressing, microscopic and X-ray
techniques.  The main constituents of modified fly ash  were found  to be silicon, calcium
(and magnesium if dolomite is used as the  modifying stone), aluminum, iron  and sulfur.
Wet-collected  modified  ashes  usually had  a  higher sulfur content than dry-collected ashes
though the amount of sulfur present in the ash is determined not only by the efficiency of
the sulfur removal system but also by the  amount  of sulfur found in the coal burned. The
physical  melting  properties of modified fly ashes  were quite similar and all ashes tested
melted  within  a  temperature  range of  2150°-2300°F.  This  similarity  of  physical
characteristics  was substantiated  by microscopic  analysis.  Predominant size fractions of
almost all ashes tested were 325 x 400 or  -400 mesh. Sieve analysis of the three  ashes  most
often used showed little or no beneficiation of elements upon sieving. The possibility of
substituting the modified fly ash  for regular  fly ash in some of the more prominent current
utilizations  and in a limited number  of  new applications  was  evaluated by  small-scale
production  simulating,  as  closely  as  possible,  commercial  production  processes. A
comparison of properties and characteristics yielded the following categories of technical
potential.4'5  Specific  results  and conclusions are  included for  each high  potential
application. Additional data on these as well as details of low potential applications may be
found in the references identified.

    1.  High Potential of Utilization
       a.  Mineral wool
       A carbon-arc tilting furnace was used  to melt a  wide variety of modified fly ash
samples and mineral wool was produced by pouring the molten material from the furnace in
a thin  stream and  into a jet of 90 to 95  psig compressed air. The air imparted a  shearing
force to the molten mass, breaking the stream into small droplets which formed fibrous
"tails." Any solid remnants of the original droplets are termed  "shot." Characteristics of the
mineral wool  produced are shown in Table 2. All  pouring temperatures are below those
necessary for wool production from bottom ashes and current commercial raw materials.
       A significant difference was observed in the production yields from the individual
samples. A much higher  yield  was  obtained  from sample  KPL, the only  wet-collected
limestone modified fly ash availble, than from the dolomite fly ash. The lowest yield was
obtained from sample CM, dry-collected dolomite  modified fly ash, in which the coal and
dolomite  were premixed upon entering the  combustion  area. In  comparing the acid/base
ratios (percent silica plus percent alumina)/(percent  lime plus percent magnesia) sample KPL
at 1.30 falls closest to  the generally accepted mineral wool  production range  of 0.85 to
1.25. SLD and Cl (1.87 and 1.58 respectively) had lower yields than KPL.
       Although  samples  CM  and  Cl  were  produced from  the  same coal  and the  same
dolomite, a difference in  their yields  of  mineral  wool  was noted,  possibly  due to the
different methods of introducing  the dolomite at the  boiler. Sample CM was  formed by

-------
                                                            Table 2

                                            Production Characteristics of Mineral Wool
Sample
 KPL
 SLD
   Cl
  CM
  CU
             Type
Wet Collected Limestone Modified
Wet Collected Dolomite Modified      1.87
Dry Collected Dolomite, Injected       1.58
Dry Collected Dolomite, Mixed
Unmodified
Acid
Base
Ratio
1.30
1.87
1.58
1.52
9.79
Pouring
Temp.
°F
2700
2800
2700
2700
3000
Blowing
Pressure
psig
92
90
93
95
95
Yield
High
Moderate
Moderate
Low
None
       Comments

Light brown, short fluffy
fiber, very little shot

Gray, some brittle fiber,
moderate shot

Gray, resilient fiber,
moderate shot

Gray, fluffy fiber, heavy
shot

No fiber  formed

-------
                                           K-15

premixing the dolomite and coal before pulverization and entry into the boiler while sample
Cl was formed by injection of the dolomite above the flame envelope.
       Unmodified ash sample CU was utilized as a control. As  shown in Table 2, no fiber
could be produced even at temperatures as high as 3000°  F.
       Quality  tests  performed   in  accordance  with  the  Department  of Commerce,
Commodity  Standards  Division:  Commercial  Standard  CS 131-146 yielded  the results
shown in Table 3. Loose shot was removed from the samples which included a commercial
mineral wool for comparison.
        Although high quality mineral wool (accompanied by sulfur regeneration)—equal to
or  better than  commercial mineral  wool—was produced from  both  dry-collected and
wet-collected limestone-modified fly ash, there is no market potential  for the product since
it is being replaced by glass wool.

       b. Calcium-silicate brick
        Calcium-silicate (CS)  bricks of superior quality (compressive strengths in excess of
7000 psi) were  produced  from limestone and dolomite  modified fly ashes.  Experimental
work proceeded  in three phases with pellets (1" diameter by 3/8" thickness) being made
initially  to  determine  basic composition  mixtures, forming  pressures and autoclaving
conditions for each individual modified fly ash examined. Dry-collected modified ash, and
wet-collected ash, were selected for the second phase of research—the production of 2" x 4"
x 1-3/8" bench-scale  brick. This phase of the  research dealt primarily  with  such processing
variables as forming pressure, mixing,  humidity curing, etc. In the final phase, full size brick
was produced  using  common commercial  equipment  to determine  whether the process
could actually be scaled up.
        Data obtained from the pellet tests  indicated that CS brick could be produced from
modified fly ash. When using dry-collected  modified fly ash, the brick mix consisted of 50
percent'(on a  dry basis)  modified  fly ash, 50 percent silica sand and  approximately 20
percent  water; when  wet-collected  modified fly ash  was used, CS brick could be produced
containing 50 percent  (on  a dry  basis)  modified fly ash, 39 percent  sand  and 11 percent
calcium  oxide. Using wet-collected  KPL fly ash, the process involved a dewatering of  the
slurry to 34 percent  water  before mixing. Such a composition provides sufficient water for
mixing and forming of the  green brick.
        In the final phase of the testing program, 2" x  4" x 8" full size brick samples were
prepared using a  hydraulic-toggle  dry-press.  The final  products met or surpassed ASTM
(73-51 and  73-67) specifications of  4500 psi  compressive strengths and less than 1 percent
shrinkage for grade SW, severe weathering,  calcium-silicate brick. An average batch of brick
made from  dry-collected ash displayed characteristics of 4600 psi  compressive strength, 20
percent absorption and no  measurable shrinkage; wet-collected ash produced brick with an
average 4500 psi  compressive strength, 28 percent absorption and no measurable shrinkage.
        High technical  potential  was  demonstrated  for  calcium-silicate  brick  made from
modified fly ash. Although this type of  brick is used in Europe  it  has no current market in
the United States.

-------
          Table 3




Quality Tests on Mineral Wool
Sample
KPL
SLD
Cl
CM
Commercial
Average
Fiber
Diameter
2.5u
3.0u
5.6u
5.4u
8.4u
Attached
Shot
wt. %
14.0
32.0
34.0
36.0
N/A
Moisture
Adsorption
St. %
0.001
0.00
0.00
0.00
0.00
Odor
Emissions
No Apparent Difference
No Apparent Difference
No Apparent Difference
No Apparent Difference
No Apparent Difference
Fire
Resistance
Incombustible
Incombustible
Incombustible
Incombustible
Incombustible
Corrosion
Retardance
Noncorrosive,
no etching
Noncorrosive,
no etching
Noncorrosive,
no etching
Noncorrosive,
no etching
Minor Corrosic
                                                             no etching

-------
                                           K-17

      c. Aerated (gas) concrete
       Aerated or foamed cellular concrete is a lightweight structural material consisting of
small  noncommunicating  gas cells entrained in a  calcium-silicate matrix. It is  produced by
inducing gas bubbles within a cementitious paste normally composed of cement and/or lime
and a  fine grained siliceous material.
       The bubbles of gas are produced by one of two general methods:
       1.  By the formation of gas by chemical reaction within the mix during the liquid or
           plastic stage, for example:
             2A1 +3Ca(OH)2 +6H2O	»- 3CaO  •  A12O3  •  6H2O +  3\-\2 ^ •
           or
       2.  By  introducing air  from  without,  either by adding a  preformed foam or by
           incorporating air by whipping.
       When the first method is  used, the hydrogen in the cells is replaced by air in a short
time and no fire hazard exists. The gas-cement mixture is allowed to set in air and is then
steam cured at high pressure. Aerated concrete made in Europe using normal coal fly ash as
the siliceous component is high  in strength and light in weight—their best products having
compressive strengths of  200-800 psi for concrete with a density range of 30-45 Ib/cu ft.
Aerated concrete also exhibits advantageous thermal insulation and acoustic properties.
       Aerated concrete was produced from dry-collected limestone modified fly ash using
the technology employed  by  European manufacturers with one basic exception. Utilizing
the "free" lime content  in dry-collected modified ash, the addition of lime is not required—a
significant cost reduction.  Aluminum powder  is used to generate  gas  bubbles and portland
cement is added to provide strength.
       Dry-collected  limestone modified fly ash from the Shawnee Steam Plant at Paducah,
Kentucky (TVA), was selected for the bench-scale production of aerated concrete  because
of its high reactive or "free" lime content and its large siliceous component.  It was found
that aerated concrete could be  prepared from this  ash without the  use of any additional
material  except water and  aluminum powder—the aerating agent.  The cured concrete had a
compressive strength  of 400 psi  at a density of approximately  50 Ibs/ft3. Portland cement
was then added to the mix to increase the compressive strength of the product. The density
increased to 56.3 Ibs/ft3 when using cement and  the compressive strength was increased to
more  than 855 psi. The addition of portland cement also stabilized the aerated mix prior to
autoclaving. This is a  critical factor because setting must occur after aeration  is completed
and before the entrained bubbles collapse.
       Although these early results  indicated  high technical potential worthy of additional
research—comparable  compressive  strengths  at  somewhat higher  densities—there  is no
current market for aerated concrete in the United  States.

-------
                                           K-18

       d. Formed concrete block
       Research on calcium-silicate  brick  production showed that autoclaving  increased
calcium-silicate bond  formation.  As a result, the feasibility of using modified ash as the
cementing agent for the production of concrete block was investigated.
       The composition of the cement block was the same as for calcium-silicate brick with
the exception that less dewatering was required. The composition consisted, on a dry basis,
of 50 percent wet-collected  modified fly ash, 39 percent silica sand (30 x 100 mesh) and 11
percent lime  (95 percent CaO). Also, the material was poured into molds instead of pressed.
No prior grinding or crushing of the modified ash raw material was required. The resulting
poured concrete, which was similar to concrete block, had a bulk density of 90  Ib/ft3 as
compared to  150  Ibs/ft3  for conventional  concrete block and a compressive strength of
approximately 900 psi as compared to 1000 psi for conventional block. Although addition
of the necessary aggregate could raise the bulk density to 100 Ib/ft3 , this would still be only
2/3 the bulk density of standard block. The blocks produced out of the autoclave were full
strength, nonshrinking products which do not require  the 3-4 weeks air  curing time before
sale  as does the conventional concrete block. On this  basis,  storage requirements  could be
reduced. However, as in the case of calcium-silicate brick, implementaion would require new
techniques of production such as dewatering and autoclaving. As a result, there is no current
U.S. market for formed concrete material made from modified fly ash.

    2.   Low Potential of Utilization
    a.  Soil amendment
    b.  Ceramic materials
    c.  Recovery of SO2 (thermal)
    d.   High-pressure alumina leaching
    e.   Flotation as a means of  producing separate fractions
       Techniques  for  dewatering  the  wet-collected  limestone-modified  fly  ash were
evaluated in  a follow-on project with  the following  resultant classifications of technical
potential.5
       1. High Potential
          a.  Settling
          b. Pressure filtration
          c.  Centrifugation
       2. Medium Potential
          a.  Flocculants
Details of the results are currently  unavailable, however, settling is considered the optimum
technique based on  both economical and technical considerations.  Pressure filtration  and
centrifugation, while  having  high technical  potential,  are not expected to  be economical
because the large volumetric capacities required could result in large equipment multiples.

-------
                                           K-19

IV. Summary
       Limestone-modified fly ash differs considerably,  both chemically  and physically,
from unmodified ash and does not lend itself to direct substitution for regular ash, as it is
used today. In addition, the chemical and physical properties of modified ash vary to a large
degree based upon the sulfur and ash content of the coal  and subsequent removals during
flue gas treatment.
       There  are,  however,  potential  uses for  the modified  ash: some, the  same as  for
regular ash; others not yet developed. Such miscellaneous factors as quality variation, water
content,  sulfur (sulfite, sulfate, gypsum) content, pozzolanic properties, quantities available,
trace  element content and toxicity and  unreacted  lime  content need to be thoroughly
evaluated for specific applications before applicability can be finally assessed. Research and
development programs are  necessary  to determine  and subsequently  demonstrate the
technical and economic feasibility of utilizations of this material.
       General areas of potential technical utilization include autoclave products, structural
or land fill, bituminous  filler,  pozzolanic materials, cement manufacture, pressure-sintered
products,  gypsum  products,  and  mineral  recovery.  Immediately  promising areas  are
autoclave products (sulfur  would not  be released), gypsum  products  (LMF contains large
amounts of gypsum), road base course material (it  contains lime, has pozzolanic properties
and  the  potential market  is large), and sulfur  recovery (although the economics  are not
promising, it could supplement a sintering process).
       Since the  modified ash cannot currently replace  regular ash in its  utilization,  its
immediate impact on the regular ash market would be negative. It is possible, however, that
processes can  be developed that  would make  it  usable  by  the time it  is produced in
appreciable quantity.

 V. Recommendations
       Although  not the main  thrust  of the current   program,  recommendations are
presented for unmodified,  as well as for modified fly ash,  because use of the former would
contribute to the economic  solution  of the solid  waste  problem. Additionally, its use is
expected  to precede  (and pave the way for) the use of modified fly ash since the former is
more  familiar,  well  characterized,  and  in  current  abundance.  Recommendations  are
presented  for  wet-collected   limestone-modified  fly  ash   since dry-collected
limestone-modified fly ash is not expected to  be nationally abundant because of the limited
application  of the dry limestone injection process. However, the dry process  may be utilized
in a particular  geographic  area or localities  which would  make the dry-collected modified
material  locally available. The properties and characteristics of the dry-collected  material  are
not expected to  be sufficiently different  from the  dewatered  wet-collected  material to
preclude its use for certain  applications.

-------
                                           K-20

       All  recommendations have been submitted for review to appropriate agencies; e.g.
the Department of the Interior and the Department of Housing and Urban Development.

    A. Unmodified Fly Ash
       Existing inhibitions to the utilization of regular fly ash are of such magnitude that
only a small percentage of the ash produced today is utilized. These restraints will continue
to  prevent  an appreciable growth  of the  fly  ash market unless appropriate  research,
development,  and  survey programs are carried out.  These programs  may reduce inhibitions
that retard fly ash sale on a profitable basis.
       Major  areas of  interest  for  new efforts are structural concrete,  road base course
materials, and such new products as gas concrete, ceramics, and mineral recovery. Sufficient
effort is already being applied  to the advancement of the  fly ash lightweight aggregate
technology. An effort should also be directed toward the extended  use of fly ash as a mine
void  fill, particularly since it could be an interim measure until the efforts requiring more
lead time are completed and put  into practice.
       The recommendations are:
    1. Expeditiously develop a  new set of specifications or a handbook for the use of fly
       ash  in portland cement  concrete which would  provide a standard utilization  to
       produce  predictable results. This would include the application of various grades of
       fly  ash  (pertinent parameters such as  residual  carbon, fineness, and  pozzolanic
       activity)  to  concrete  usage  and  encompass cure times  beyond  28 days. These
       documents  could  be modeled after  TVA specifications G-2  and  G-30. A testing
       program  will be required  to provide statistical data to support this program.
    2. Conduct a marketing survey for various regions within the fly ash supply  areas  to
       determine  the economic feasibility  of fly  ash  gas concrete  in various forms  of
       building construction in the United States.
    3. Conduct a technical and marketing  survey  in various regions  of fly ash producing
       areas to  determine the justification   for an advisability  of  action  by government
       road contracting agencies regarding the use of fly ash  in the base course section  of
       Federal, state, and local paving program contracts.
    4. Investigate the possibility of recovering minerals from  fly ash.
    5. Evaluate the  net  economic  effects  of  coal-washing or gasification on the  fly ash
       market and on the cost of ash disposal.
    6. Conduct a technical and economic  survey relating to land reclamation and to the
       remote filling of mine voids for control  of  mine subsidence and fires. This would
       include the economics of fly ash  usage  and  land reclamation values; and the effects
       of fly  ash on  ground waters. Consider the use of empty returning coal cars or a fly
       ash slurry for transportation.
    7. Conduct research  to develop or  improve such fly ash uses as ceramic products,
       optimized fly  ash gas concrete.

-------
                                           K-21

   8.  Conduct fundamental research to identify the intrinsic characteristics and properties
       of fly ash to provide the basis  for  subsequent research into new uses of  fly ash.
       Although this  has been  performed in part  at  various organizations, results of
       complete characterization are not published.

   B. Wet-Collected Limestone-Modified Fly Ash
       Determining the potential use of modified ash depends on research and development
programs  and  marketing surveys to establish  the potential marketability  of developed
products  in terms  of  public  acceptance and  ability to compete with  other products,
including  those  produced from regular fly ash. The  following programs are recommended:
   1.  The  most critical  research need for  wet-limestone-modified ash is the fundamental
       characterization of its chemical and physical properties. This characterization will
       provide  the   basis  for  the  subsequent  utilization  and  toxicology   research
       recommendations.
   2.  Conduct research and development programs on potential mass uses of modified fly
       ash  including  filler  material, autocalve   products,  pozzolanic  materials,
       pressure-sintered products, and  gypsum  products. These programs should  be broad
       enough  to allow the possible emergence of uses not yet  identified. These programs
       should also  consider the mass usage of modified ash in  situ  and beneficiated in
       processes in which sulfur is not released and recovered.
   3.  Investigate the  recovery of mineral ore from  the modified fly ash.
   4.  Determine the  physical state of  toxic elements within the modified fly  ash, the
       source  of these  elements  (coal ash  or  limestone), the role of wet collection in
       preventing mass contamination  via particulate and gaseous effluents, and  potential
       hazards  that  may exist  (particularly through leaching) in the ash disposal  and
       utilization.
   5.  Conduct an economics  survey of the phase  of  electric power production involving:
       the effects of fuel preparation and delivery, pollutant removal, residue disposal, and
       product credits. Examples of trade-offs which should be made include: (a) scrubbing
       of fly ash and  gases resulting from the combustion of untreated coal, (b) scrubbing
       of fly ash and gases resulting from  the combustion  of cleaned coal, (c) gasification of
       coal, and (d) liquefaction of coal.
   6.  Conduct surveys to determine  the potential  for  marketing recovered sulfur and
       products to be  developed  for the  use  of modified fly  ash.  Also, consider  the
       development  of  products  which are  already partially developed; e.g.,  mineral
       aggregate and road base course materials.

-------
                                         K-22

VI. References
       Reports identified by numbers prefixed "PB" are currently available prepaid from:
National Technical  Information Service  (NTIS), U.S. Department of Commerce, 5285 Port
Royal Road, Springfield, Virginia  22151. Others will be available approximately one month
after receipt by NTIS.
    1.  Aerospace Corporation  Report  No. TOR-0059(6781)-1. PB 209-480, Final Report
       on "Technical and Economic Factors Associated with Fly Ash Utilization," July 26,
       1971,  EPA Contract  FO4701-70-C-0059.
    2.  Coal  Research  Bureau, West Virginia University, PB 185-802, Final  Report  on
       "Study  of  the  Potential  for Profitable Utilization  of Pulverized  Coal  Fly Ash
       Modified by the Addition  of Limestone - Dolomite SO2 Removal Additives," April
       1969,  EPA Contract  PH86-67-122.
    3.  Ibid.,   PB 196-779,   Final  Report  on  "Study  of  the Potential for  Recovering
       Unreacted Lime from Limestone Modified Fly Ash by Agglomerate Flotation," May
       1970,  EPA Contract  PH22-68-18.
    4.  Ibid.,  Final  Report, "Pilot  Scaleup  of Processes to Demonstrate  Utilization  of
       Pulverized Coal  Fly Ash  Modified  by the  Addition  of Limestone-Dolomite  SO2
       Removal  Additives," March  1972,  EPA Contract CPA70-66. Submitted  to  NTIS
       December 11, 1972.
    5.  Ibid.,  Final  Report  Draft,  "Technical and  Economic Evaluation of  Dewatering,
       Production  of  Structural  Materials,  and  Recovery  of  Alumina  from  the
       Limestone-Modified  Fly Ash Produced by  a Limestone Wet Scrubbing  Process,"
       Final Report anticipated early 1973, EPA Contract EHSD71-11.

-------
  APPENDIX L




Process Economics

-------
                                            L-l
                                  PROCESS ECONOMICS
I. Introduction
         One of the primary goals of the EPA-TVA dry limestone injection test program is to
  better define  the  process economics for  potential  users. The economics given in the 1968
  EPA-TVA  conceptual design and cost study (12) of the process were based on limited
  background and  performance data; therefore,  refinement of the earlier cost estimates is
  highly desirable and is now possible using the results of the  Shawnee test demonstration.
          Investment requirements estimated in 1968 were based mostly on  discussions  with
  solids handling  equipment   suppliers  with  some guidance  from  the TVA Office  of
  Engineering Design and Construction in  Knoxville, Tennessee, plus the use of  indirect cost
  and installation factors derived from actual projects and from  published estimating  material.
  At that time, the most  desirable  limestone  particle size  and  point  of injection were
  unknown,  predrying  was not deemed necessary,  solids disposal was  assumed to be simple
  with water quality unaffected,  and the full effect  of injected  calcium material on  dust
  removal  efficiency of electrostatic precipitators was  speculative. All  of these requirements
  have been given careful  attention and definition by  the Shawnee test program.
          One factor of concern in 1968, which calcium base material should be utilized, is no
  longer of major importance since dried limestone serves as well as calcined limestone (CaO)
  or hydrated lime  [Ca(OH)2 ], both of which are two to three times more expensive. In the
  earlier cost study, only a  few limestone suppliers  across the  United  States were contacted
  for price data. Since then,  the M. W. Kellogg Company has  completed for EPA a much more
  comprehensive survey (8) of limestone supply and price data, and the  information is utilized
  in this process cost evaluation.
          In  the earlier operating cost estimates,  utilities usages were  calculated and capital
  charges  were  based on  nonregulated  economics; that is,  no provisions were  assumed for
  maintaining the utility's rate of return on investment for the additional investment.  As a
  result, an impractical, low rate of capital charges was assessed. In addition, a chemical plant
  operating stream time (8,000 hrs/yr) was used instead of a  power plant's  historical  declining
  load factor and effort was not made to predict the lifetime  operating costs of the system.
          In  the evaluation  to  follow, the  actual  cost of  the Shawnee injection system,
  improved definition  of raw  material costs  and desired particle size  of  injection  material,
  actual utilities usage  rates, more realistic capital  charges and operating periods, recent air
  pollution emission requirements, refined dust removal technology, and equipment estimates
  by a precipitator manufacturer permit a far  more accurate cost appraisal than was possible
  in  1968. However, it should be recognized that the accuracy of the newer estimates can be
  affected greatly by the difficulty of retrofit to a  power unit, labor  costs  in the particular
  unit  location, the closeness to a limestone source, the need and  convenience of additional
  disposal area for the waste  solids produced, local air and water pollution regulations, and the
  moisture content of purchased stone.

-------
                                        L-2
       At this stage of development, the major factors affecting process economics include
(1)  power unit size, (2) sulfur content of fuel, (3) stoichiometric rate of limestone injection,
(4)  particle size of  injected limestone, (5) particulate removal requirements,  (6) solids
disposal needs,  (7) raw material  costs, (8) annual operating time, and (9)  remaining life of
the power  unit.  Items (1) through (3) are the most significant factors in establishing costs
since they  determine the amount of limestone to be processed and, therefore, the required
capacity of the equipment.  However, item (4), particle size of injected limestone, has some
effect  on  absorption efficiency, thereby influencing design of  the  grinding  system  and
affecting both investment and operating costs. Particulate removal requirements, item (5),
are, in part, fixed by the level of injection and emission laws prevailing in the plant location.
However,  the investment and  operating costs associated  with  particulate collection vary
depending  on existing collection facilities and the type of additional facilities installed. The
method and costs for disposing solids may also differ for various power plant installations.
Raw material costs, annual  operating time,  and  remaining life of the power unit do not
influence investment; however, these items directly influence operating costs.

II.  Approach
        To evaluate the major factors, a variety of unit sizes, fuel sulfur levels, and  limestone
injection stoichiometries are chosen  for case projections of fixed  investment  requirements,
annual operating costs, and  lifetime  operating costs. Using selected cases, other key factors
are also varied to analyze their sensitivity on process economics. The  projections made are
based  on   applicable design premises  resulting  from the Shawnee test  program,  plus the
actual cost of the test  facility and  the  actual utilities usage rates. A flow diagram of the
proposed   process  and  detailed material balances  were  prepared  to serve as  guides  in
determining  equipment sizes and requirements for the various cases. Operating experience
for TVA coal-fired power units is also utilized in the evaluation technique.  For convenience,
all projections are based on 1972 costs for the midwestern United States.
        Results of the Shawnee tests indicate that,  within limits, SO2 removal efficiencies
increase with the addition  of greater amounts of  limestone to  the boiler.  However, the
associated  costs and  operating difficulties also increase. To determine the effect of  limestone
addition rate on process economics, a 52-case parametric study is used to  cover the various
unit sizes, sulfur levels,  and injection stoichiometries.  Cases were selected  to  expand the
applicability of  the Shawnee results  over a broad range. Table 1  gives a detailed accounting
of the chosen case combinations.
        Design  Premises—For the 52 cases,  applicable design premises were established for
the power unit, fuel, absorbent, combustion,  reactions, SO2 emission reduction, reaction
products,  and  particulate  collection  and  disposal  method. A  detailed  listing  of these
premises follows:
A.  Power  unit
    1.   Size-50, 150, 250, or 350  MW.
    2.   Location - midwestern region.
    3.   Type plant - existing, pulverized coal, frontal-fired unit.
    4.   Years remaining life  - 15.

-------
                                            L-3

                 Table 1  - Dry Limestone Injection Case Combinations
                              Existing Coal-Fired Units

Injection stoichiometry, moles CaO injected per mole sulfur in coal

0.8% Sin coal                        3.0% S in coal                   5.0% S in coal
50 MW power units





150





250





350





3.0
4.0
5.0
6.0
7.0
MW power units
3.0
4.0
5.0
6.0
7.0
MW power units
3.0
4.0
5.0
6.0
7.0
MW power units
3.0
4.0
5.0
6.0
7.0
1.0
2.0
3.0
4.0


1.0
2.0
3.0
4.0


1.0
2.0
3.0
4.0


1.0
2.0
3.0
4.0

1.0
2.0
3.0
4.0


1.0
2.0
3.0
4.0


1.0
2.0
3.0
4.0


1.0
2.0
3.0
4.0

   B.  Coal
      1.  Heat value-12,000 BTU/lb.
      2.  Ash content - 16.0%.
      3.  Sulfur content - 0.8, 3.0, and 5.0%.
   C.  Limestone characteristics  and preparation
      1.  Type - calcite.
      2.  Composition - 95.0% CaCO3 and 5.0% impurities (dry basis).
      3.  Purchased moisture content - 5.0% H20.
      4.  Purchased size - minus 1-1/2 in.
      5.  Moisture reduction - dried to approximately 0.5% H2 0 prior to grinding.
      6.  Drying source - off-gas from combustion of No. 2 fuel oil with 20% excess air.
      7.  Size reduction - dry ground to 80% minus 400 mesh prior to injection.

-------
                                          L-4

   8.  Transport ainlimestone injection ratio - 1:10.
   9.  Injection stoichiometry variations -
          0.8% S coal, 3.0 to 7.0 moles CaO: mole S in fuel.
          3.0 and 5.0% S coal, 1.0 to 4.0 moles CaO: mole S in fuel.
D. Combustion
   1.  Coal  consumption prior to dry limestone injection - 0.780 Ibs/kWh.
   2.  Excess air to boiler for combustion of coal - 25%.
   3.  Air inleak at air preheater - 13%.
   4.  Particulate emission  -  75%  of ash is emitted as particulates and  is present in the
       off-gas.
   5.  Sulfur emission - 92% of sulfur  is emitted as SO2; remainder is chemically bound
       with the ash.
E. Boiler reactions, S02 emission reductions, and reaction products
   1.  Dried CaCO3 decomposes to CaO and CO2 within boiler.
   2.  Heat required for decomposition is supplied by combustion of additional coal.
   3.  For  0.8% S fuel, 5% of S02 in the gas combines with CaO per unit of stoichiometric
       limestone injected.
   4.  For  3.0  and 5.0% S fuel, 10% of SO2 in the gas combines with  CaO per unit of
       stoichiometric limestone injected.
   5.  All CaS03 formed by reaction of CaO and SO2  is oxidized to CaSO4 within the
       boiler.
   6.  All of the solid products resulting from limestone injection are present in the boiler
       off-gas as particulates.
F.  Particulate collection
       One of the drawbacks of dry limestone injection is the introduction  of additional
   solids into  the boiler,  which  requires   additional  particulate  collection  and disposal
   facilities. Figure 1 shows the effect  of  injection stoichiometry on the inlet particulate
    loading  to the dust collectors  for the  three  levels  of sulfur evaluated. Design  of the
    particulate collection facilities is based on the following premises:
    1.  Existing  particulate  collection   facilities  -  mechanical   collector  followed  by
       electrostatic precipitator.
    2.  Overall particulate collection efficiency of existing facilities - 99%, equivalent to a
       particulate emission  of 0.03 grains/acf.
    3.  Additional electrostatic precipitator  capacity is installed to maintain a  dust emission
       level after dry  limestone  injection equivalent to the emission level prior to injection.
       Reflecting the limestone injection  case variations, Table  2 shows the calculated
    particulate rates at the entrance to the dust collectors for a 150 MW unit, and the overall
    collection efficiency required to maintain the base emission level defined above. These
    collection efficiencies are shown graphically in Figure 2.
G.  Particulate disposal
       Additional disposal  facilities for  handling the incremental solids  are  provided  for
    each   installation.  Figures 3, 4, and  5  indicate the incremental  disposal requirements

-------
  20
  15
o
Cfl
  10
at
!H
00

 f\
60

-S
*a
eg
o
en  c
3  5
13

4J

-------
                                                           Table 2
                                                Dust Removal Requirements for
                                       Dry Limestone Injection Case Study - 1 50 MW Plant
                                               (To Maintain Base Emission Level)
Case
0

1
2
3
4
5
6
7
8
9
10
11
12
13
Sulfur
content
of coal,
%
3.0

0.8
0.8
0.8
0.8
0.8
3.0
3.0
3.0
3.0
5.0
5.0
5.0
5.0
Injection
stoichiometry,
moles CaO/mole
S in fuel
no dry
limestone
injection
3.0
4.0
5.0
6.0
7.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0

Gas rate,
acfm @310° F.
507,700

503,800
505,200
506,900
508,100
509,600
512,500
517,800
522,700
528,000
519,000
527,900
537,000
547,000
Inlet to
Dust
Fly ash
14,040

14,100
14,120
14,150
14,160
14,1.80
14,100
14,180
14,240
14,310
14,150
14,270
14,390
14,540
dust collector
rate, Ibs/hr
Injection
products
-

5,740
7,660
9,590
11,530
13,480
7,580
15,240
22,990
30,810
12,670
25,580
38,750
52,250

Dust loading,
grains/acf
3.23

4.59
5.03
5.46
5.90
6.33
4.94
6.63
8.31
9.97
6.03
8.81
11.55
14.25
Allowable
emission,
lbs/hra
140

141
141
141
142
142
141
142
142
143
141
143
144
145
Overall dust
collection
efficiency
required, %
99.00

99.29
99.35
99.41
99.45
99.49
99.35
99.52
99.62
99.68
99.47
99.64
99.73
99.78
Outlet dust
loading
grains/acf
.03

.03
.03
.03
.03
.03
.03
.03
.03
.03
.03
.03
.03
.03
a. Equivalent to 99% removal of fly ash emitted from combustion of coal containing 16% ash

-------
 ,100.0
•u
<0
1-1
•rl

I
   99.8
•1-1
o
>i-i
M-l
<4-l
0)


g  99.6

•H
4J
O
t-l

 O
 U
 § 99.4
 I
   99.2
      0
                   I             I            I             I


           Inlet fly  ash loading prior to injections* 3.23  gr/acf


           Outlet loading  after dust collection - O.OJ  gr/acf
        24             68
Stoichiometry, moles CaO  injected per mole S in coal
       Figure
            Effect of Injection Stoichiometry on Overall Dust
            Collection Efficiency to Maintain Emission Rate
            Equivalent to 9956 Fly Ash Collection Prior to
            Dry Limestone Injection

-------
                                                                                                        00
Figure
50


5
                     100         150         200
                               Power unit size,
                                          250
300
350
Incremental Solids Disposal Requirements for Power Units Utilizing
Dry Limestone Injection Process;  0.8$ S Coal

-------
0
50
      150          200
Power unit size, MW
250
300
350
 Figure
    Incremental Solids Disposal Requirements for Power Units Utilizing
    Dry Limestone Injection Process:   3»°# S Coal

-------
           50
        100
     150         200
Power unit size, NW
250
300
                                                                                   350
Figure
Incremental Solids Disposal Requirements for Power Units Utilizing
Dry Limestone Injection Process:  5.0$ 3 Coal

-------
                                           L-ll

    attributable to dry limestone injection for each variation in.sulfur content as a function
    of power unit size and  injection stoichiometry. The following method  for disposal  is
    used (11):
    1.  Fly ash and injection solids are disposed on-site in a common, existing settling pond.
        Additional pond facilities are not provided for the incremental injection solids.
    2.  Distribution facilities are included for supplying raw water to the solids disposal
        area. Pipeline distance  between the disposal area and the raw water supply point  is
        estimated as 2,500 ft.
    3.  Slurry concentration to the disposal pond is designed not to exceed 15% solids.
    4.  Fresh sluice water is used for disposing the  incremental solids, with no provisions for
        recycling. Pipeline distance between disposal pond and the solids collection facilities
        is estimated as 6,000 ft.
    5.  A separate disposal line  is included for each case, regardless of the magnitude of the
        incremental solids disposal burden.
    6.  Based  on  vendor recommendations,  an  8  in.  line  is the  smallest size which  is
        practical.  Disposal systems are sized with either 8,  10, or  12 in. lines, with a design
        fluid velocity of approximately 6 ft/sec and capability of disposing the daily load of
        solids over a period of 12 hrs. Based on TVA operating experience, the load factor
        for an existing ash sluice  line  is about 40% or less.
    7.  Spare  incremental  solids disposal  lines  are  not provided. It  is assumed that the
        existing spare  sluice lines or  the existing  operating lines  (with relatively low load
        factors) can be utilized as spares when required.
    8.  Based  on TVA sluicing  practices, sluice water flow through each operating line  is
        continuous  while  the   power  unit  is in  operation  (sluice water  and electrical
        requirements for pumping are based on continuous flow.)
        Using  the  Shawnee  design   and operating experience and the design  premises
 presented above, a projected  process flow  diagram  including provision for dust collection
 and disposal was prepared. This flow diagram identifies the major equipment  required for
 the process and is presented in Figure 6.
        Base Case—For convenience  in  preparing  material and energy balances, a separate
 base  case for  each  level  of sulfur in coal was established. Power unit size  was selected to
 conform  to that of Shawnee Unit 10. Injection stoichiometry for each case was based on the
 most  probable applications as determined  in the Shawnee tests  for the various levels of
 sulfur in coal. These case combinations are shown below:

                 Dry Limestone  Injection Process Base Case Combinations

                                                                  Injection stoichiometry,
Power unit size,                   Sulfur in coal,                      moles CaO injected/
	MW                         	%                             mole 5 in coal

      150                             0.8                                 5.0
      150                             3.0                                 2.0
      150                             5.0                                 2.0

-------
           CYCLONE EXHAUST
           TO MECHANICAL
             A NO/OR
           ELECTROSTATIC
           DUST COLLECTOR
                                                              SLIDE GATE VALVE
                                                              ROTARY VALVE

                                                              VACUUM RELIEF VALVE
Figure 6- Proposed  Flow  Diagram of Dry Limestone Injection Process

-------
                                         L-13
       A  detailed material  balance for each of the base case combinations is shown  in
Figure 7

       Actual investment—The actual fixed investment for the Shawnee test facilities was
analyzed to provide an equipment, labor, and material cost breakdown for the major process
functions. The results are presented in Table 3  (1). A nine-month construction period during
1969-1970 and a total investment cost of $1,477,581 were required for the test facilities.
       The facilities were designed with a 20 ton/hr injection capability equivalent to a 350
MW  plant burning 2.0% S coal with an injection stoichiometry of 2.0. Although oversized
for a 150 MW plant, a broad capacity  range was necessary  because  of the research and
development  nature  of the installation. The actual  investment  requirements discussed above
include  facilities  for receiving,  storing,  drying, grinding, and injection and sampling test
probes  for the  boiler.  Both rail  and  truck unloading equipment  are  included. Boiler
modifications such as wall  port openings are included along with utilities distribution from
the powerhouse area. Not included are  capability  for continuous fine grinding, additional
particulate removal facilities, and solids disposal  pond for the incremental dust burden. Also
not included  are additional soot blowers for removal of deposits which tend to form in the
convection passes of the boiler.  The number of required sootblowers may vary for different
installations  as a  function of  boiler tube  spacing, temperature  regime,  and length of
convection pass; however, each is estimated to cost  $20-30,000. Since the Shawnee tests did
not  indicate  the  actual number of additional sootblowers  required  as a  result of dry
limestone injection, additional costs are excluded from the investment projections; however,
the sensitivity of  total investment as a function of  sootblower requirements  is discussed in
Section  11.

        Investment projections—Based on the  dry limestone injection process flow diagram,
the process equipment  was subdivided into several areas according to function. For most
process  areas, actual 1969  investment costs  for the test facilities were updated  to  1972
utilizing a Chemical  Engineering plant cost index ratio of 138/119 (4).  Instead of treating as
separate areas,  costs for   painting,  stairways,  handrails,  inspection, and testing  were
distributed to the appropriate major areas. For the limestone grinding system, updated costs
were  obtained from  vendors to reflect the capability for continuous fine grind, not available
with the Shawnee facilities.
       Costs for  facilities  at other limestone capacities were projected  by  scaling the
updated investment  according to limestone throughput using appropriate scaling exponents.
Values of these exponents were factored from the literature (6, 9) and  from cost quotations
obtained from vendors. Table 4 shows the major equipment areas which were  established,
the base  1972 investment corresponding to  the updated Shawnee costs, and  the scaling
exponent used for projecting costs as a function of capacity ratios.
       Costs for the incremental electrostatic precipitator and solids disposal systems were
not scaled according to  limestone throughput. Incremental electrostatic precipitator system

-------
ISO MW UNIT, 0.8% S IN COAL, 5.0 CoO:S INJECTION STOICHIOMETRY
STREAM NO.
DESCRIPTION
SCFM
GPM
PARTICULATES, LBS./HR
TEMPERATURE, 'F
SPECIFIC GRAVITY
JNOISSOLVED SOUDS, %
1
LIMESTONE
TO
DRYER


-
AMBIENT
2.7

2
AIR
TO
DRYER
1,200

—
AMBIENT


3
FUEL OIL
TO
DRYER
310
7
—
AMBIENT
.865

4
- CYCLUNlT"
EXHAUST TO
1,530

20
250


5
DRIED
LIMESTONETO
SURGE TANK

_
_
230


6
CIRCULATION
AIR TO
CONVEYOR
8,800

2,750
200


7
CONVEYING
AIR TO
CYCLONE
8,800

18,350
200


a
PULVERIZED
LIMESTONE TO
FEED TANK

_
_
200


9
AIR
TO
COMPRESSOR
1,500
330

_
AMBIENT


10
LIMESTONE-
AIR TO
DISTRIBUTOR
1, 500
330

15,600
110


II
PULVERIZED
COAL TO
BOILER

-
-
AMBIENT


12
COMBUSTION
AIR TO
AIR HEATER
322,000
_
-
no


13
COMBUSTION
AIR TO
BOILER
292,000
_
-
610


14
FLUE GAS
TO DUST
COLLECTOR
34 O.OOO
-
23,720
310


15
FLUE GAS
TO
STACK
341,530
-
141
310


16
SOLIDS TO
SLUICE
EQUIPMENT
-
-
-
310



IT
SLUICE
WATER

267

AMBIENT



18
SLURRY TO
DISPOSAL
POND

286

AMBIENT
1.10
IS
COAL ANALYSIS, % BY WT (AS FIRED BASIS)
   H	4.17      ASH	16.00
   N	1.23      H20	9.70
   C	66.39      0	1.71
   S	0.80
                                                                   COAL CONSUMPTION,  .786 LBS./KWH WITH INJECTION
                                                                   25 % OVERALL SOj REMOVAL FROM GAS (5% /UNIT STOICHIOMETRY)
                                                                   PARTICULATE  COLLECTION EFFICIENCY,  99.41%
                                                                                                                                                          ESTIMATED COMPOSITION OF SAS TO STACK EXCLUDING NO,,
                                                                                                                                                                               %  BY  VOLUME
                                                                                                                                                           COg
                                                                                                                                                           12.36
          SOj
          .04
 Oz
5.43
HjO

7.62
150 MW UNIT,  3.0% S IN  COAL,  2.0  CaO: S INJECTION  STOICHIOMETRY
STREAM NO.
DESCRIPTION
RATE, LBS. /HR.
SCFM
GPM
PARTICULATES, LBS /HR
TEMPERATURE, *F
SPECIFIC GRAVITY
UNWSSOLVED SOUDS, %
1
LIMESTONE
TO
DRYER
24,600
—
-
-
AMBIENT
2.7

2
AIR
TO
DRYER
8,260
1,800
-
-
AMBIENT


3
FUEL OIL
TO
DRYER
470
-
I.I
-
AMBIENT
.863

4
CYCLONE
EXHAUST TO
COLLECTOR
9,850
2,300
-
30
250


5
DRIED
LIMESTONETO
SURGE TANK
23,450
-
-
-
250


«
CIRCULATION
AIR TO
CONVEYOR
60,600
1 3, 200
-
4,140
ZOO


7
CONVEYING
AIR TO
CYCLONE
60,600
1 3,200
-
27,590
200


8
PULVERIZED
LIMESTONETO
FEED TANK
23,450
-
-
-
ZOO


9
AIR
TO
COMPRESSOR
2,300
500
-
-
AMBIENT


10
LIMESTONE-
DISTRIBUTOR
2,300
500
-
23,450
110


II
PULVERIZED
COAL TO
BOILER
118,130
-
-
-
AMBIENT


12
COMBUSTION
AIR TO
AIR HEATER
1,509,640
329,000
-
-
no


13
COMBUSTION
AIR TO
BOILER
1,367,400
298,000
-
-
610


14
FLUE QAS
TO OUST
COLLECTOR
1,619,400
347,000
-
29,390
310


15
FLUE GAS
TO
STACK
1,629,250
349,300
-
142
310


16
SOLIDS TO
SLUICE
EQUIPMENT
29,278
-
-
-
310


17
SLUICE
WATER
165,922
-
332
-
AMBIENT


IB
SLURRY TO
DISPOSAL
POND
195,200
-
355
-
AMBIENT
1.10
15
COAL ANALYSIS,
   H ........ 4.17
   N ........ 1.23
   C ...... 66.39
   S ....... 3.00
                BY WT. (AS FIRED BASIS)
                    ASH ____ 16.00
                    H20 ____  9.21
                    0 ....... —
                                                                   COAL CONSUMPTION,  .788 LBS./KWH WITH INJECTION
                                                                   20% OVERALL SOj REMOVAL FROM GAS HOT./UNIT STOICHIOMETRY)
                                                                   PARTICULATE COLLECTION EFFICIENCY, 99.52%
ESTIMATED  COMPOSITION OF GAS TO STACK EXCLUDING  NO,,
                     %  BY VOLUME	
                                                                                                                                                          COj
                                                                                                                                                          12.28
          SOg
          .15
                  HjO
                  7.71
         TOTAL

         100.00
150 MW UNIT, 5.0% S IN  COAL,  2.0 CaO: S INJECTION  STOICHIOMETRY
STREAM NO.
DESCRIPTION
RATE, LBS./HR.
SCFM
GPM
PARTICULATES, LBS./HR.
TEMPERATURE, • F
SPECIFIC GRAVITY
UNDISSOLVED SOLIDS, %
1
LIMESTONE
TO
DRYER
41,290
-
-
-
AMBIENT
2.T

2
AIR
TO
DRYER
13,860
3,020
-
-
AMBIENT


3
FUEL OIL
TO
DRYER
790
-
1.8
-
AMBIENT
.865

4
EXHAUST TO
COLLECTOR
16,520
3,860
-
50
250


5
DRIED
LIMESTONETO
SURGE TANK
39,370
-
-
-
250


6
CIRCULATION
AIR TO
CONVEYOR
101,500
22,100
-
6,950
ZOO


7
CONVEYING
AIR TO
CYCLONE
101,500
22,100
-
46,320
2CO


8
PULVERIZED
LIMESTONE TO
FEEDTANK
39,370
-
-
-
2OO


9
AIR
TO
COMPRESSOR
3,900
850
-
-
AMBIENT


10
LIMESTONE-
AIR TO
DISTRIBUTOR
3,900
850
-
39, 370
no


II
PULVERIZED
COAL TO
BOILER
1 1 8.90O
-
-
-
AMBIENT


12
COMBUSTION
AIR TO
AIR HEATER
1.531,590
334,000
-
-
no


13
COMBUSTION
AIR TO
BOILER
1,387,300
302.500
-
-
610


14
FLUE GAS
TO DUST
COLLECTOR
1, 649,200
352,000
-
39,800
310


15
FLUE SAS
TO
STACK
1,665,720
355,800
-
143
310


16
SOLIDS TO
SLUICE
EQUIPMENT
39,707
-
_
-
310


17
SLUICE
WATER
224.993
_
450
-
AMBIENT


IB
SLURRY TO
DISPOSAL
POND
264,700
_
481

AMBIENT
1.10
15
                   WT. (AS FIRED BASIS)
                    ASH	16.00
                    H20	7.21
                    0	  -
COAL ANALYSIS, %
   H	4.17
   N...'	1.23
   C	66.39
   S--	5.0O

& BASIS
  HEAT VALUE  OF COAL, I2.00O BTU/LB. (AS FIRED BASIS)
  75% OF ASH IN COAL EVOLVES AS FLY ASH
  LIMESTONE TO  SYSTEM CONTAINS 95.0% CoCO3(DRY BASIS) AND 5% HjO
  LIMESTONE  DRIED TO 0.5% H20 PRIOR TO GRINDING
  PARTICULATE RATES IN LBS./HR. SHOULD BE ADDED TO GAS RATES TO OBTAIN THE TOTAL STREAM  RATE
  HEAT FOR DRYING SUPPLIED BY COMBUSTION OF NO. 2 FUEL OIL WITH 20% EXCESS AIR
  MATERIAL LOSSES ARE EXCLUDED FROM  MATERIAL BALANCE
                                                                  COAL CONSUMPTION, .793  LBS./KWH WITH INJECTION
                                                                  20% OVERALL SOZ REMOVAL FROM  GAS (10%/UNIT STOICHIOMETRY)
                                                                  PARTICULATE COLLECTION EFFICIENCY, 99.64%
 ESTIMATED COMPOSITION OF GAS TO  STACK EXCLUDING NO*.
                     % BY VOLUME
                                                                                                                                                          COa
                                                                                                                                                          12.43
                                                                                                                                                                    SO;
                                                                                                                                                                    .24
                    Oz_
                    5.39
          Nz
         74.42
                                                                                                                                                                                               H20
                                                   FIGURE  7   DRY  LIMESTONE   INJECTION  PROCESS  MATERIAL  BALANCES9'

-------
                                            L-15

                                             Tables

                             Actual Fixed Investment for 20 Ton/Hour
                                 Dry Limestone Injection Facilities
                               on Shawnee Power Plant Unit No. 10
                                       1969-70 Construction
Direct Cost

General Yard Work
  Landscaping
  Guard Rails
  Relocate access road
  Yard lighting
  Storage area
  Raw water piping
  Drains	
     Subtotal

Limestone Storage and Feed Systems
  Truck hopper
  Railroad car unloader
  Truck hopper unloader
  Limestone receiving hopper
  Truck unloading conveyor
  Limestone storage conveyor
  Limestone feed to dryer conveyor
     Subtotal

Limestone Drying System	
  Limestone dryer, drive and combustion
    chamber with combustion equipment
  Cyclone dust collector-6500 cfm
  Trickle  valve
  Chutes  & duct

  Dust collecting fan
  Dust duct to precipitator
  Bucket  elevator and drive
  Dryer shed	
     Subtotal

Limestone Grinding System	
  Surge bin -  1000 cu.ft.
  Structural supports
  Rotary  valve with drive
  Volumetric feeder

  Ball mill, drive and oiling system
  Recirculation fan & drive - 23,000 cfm
  Ducts and chutes
  Classifier and drive
  Structural supports

  Storage silo - 6600 cu.ft.
  Structural supports
  Cyclone - 25,000 cfm
  Trickle  valve
  Bag filter - 595 sq.ft. filter area
  Exhaust fan with drive
  Rotary  valve with drive	
     Subtotal
Equipment    Labor
Materials
$






$
$ 905
5,180
5,180
No cost ,
12,000
17,212
1,591
$ 42,068
$ 46, 522 1
1,876
85
700,
4,300

4,010

$ 57,693
$ 1,748
5,360
1,304
1,705
91,326
3,836
3,410
4,600 1
$
82
121
9,128
1,468
362
401
$ 11,562
) $
( 12,305
(
)
> 12,112
$ 24,417
)
(. $ 6,989
(
)
677
10,910
1,550
9,464
$ 29,590
)
! $ 8,807
f
)

16,656
}
> 2,872
$ 1,600
218
230
2,515
3,023
25
166
$ 7,777

4,463


6,029
$ 10,492

$ 3,193


258
2,348
450
3,843
$ 10,092

$ 3,436



4,730

1,196
5,360j
7,360
11,731
3,836
85
5,968
1,130
1,304



27,120






12,829



 Direct
Subtotal
                                   $    1,600
                                         300
                                         351
                                       11,643
                                        4,491
                                         387
                                         567
                                  $    19,339
                                      28,033
                                      48,944
                                  $   76,977
                                  $   59,365
                                        5,435
                                       13,258
                                        6,010
                                       13,307
                                  $    97,375
                                    $ 22,360




                                      119,958

                                       14,028
                                       71,363
$150,063   $ 55,455   $  22,191    $  227,709

-------
                                             L-16
                                     Table 3 (continued)
Limestone Injection System	
  Rotary valve with drive
  Transport pump with drive
  Transport air compressor

  Cyclone - 630 cfm
  Feed tank - 300 cu.ft.
  Bag filter - 530 cfm
  Rotary valve with drive

  Screw conveyors with drive (2)
  Air locks with drives (2)

  Air receiving tank
  Injection  air compressor with drive
  Transport air compressor with drive
  Limestone distributors	
     Subtotal

Equipment Foundations

Instrumentation
  Control panel and shed
     Subtotal

Piping	
  Drying system
  Grinding  system
  Injection system	
                                                     Equipment    Labor
                                                                                           Direct
                                                                             Materials    Subtotal
     Subtotal

Electrical Power Supply
   4160 volt board
   480 volt board
   Limestone injection board
   Power and control wiring
   Conduit
   Cable trays
   Grounding
   1 elephone	
     Subtotal

Revision & Addition to Power House & Boiler
   Structural steel
   Floor grating
   Miscellaneous metal work
   Conduit, wiring and fixtures
   Cooling water supply
   Steam lines
   Insulation
   Ash disposal piping
   Boiler additions (injection ports)	
     Subtotal

Painting

Misc. Stairs, Grating and Handrails

Test Probes - Installation

Inspection and Testing

     Direct Total  All Catagories
1,304-v
4,936 >
5,968)
5m
1,748 I
1,611 (
1.304/
1,705^
2,608)
4,186}
7,5Q2l
7,502(
256/
$ 41,142
$
6,373

$ 6,373

6,089
24,877
$ 30,966















9,490


$ 9,490


$

$337,795

1,658


14,179

5,414


6,737


$ 27,988
$ 37,951
23,820
1,369
$ 25,189
2,953
12,852
52,245
$ 68,050
1,714
70
190
27,206
28,301
4,205
2,172
870
$ 64,728
$ 1,327
416
6,679
1,236
30,765
5,967
(Contract)
6,216
39,379
$ 91,985
$ 28,008
$ 20,244
$ 46,262
29,054
$560,483

320


3,358

184


771


$ 4,633
$ 27,096
10,172
356
$ 10,528
1,606
2,626
5,336
$ 9,568
9,042
77
325
11,775
3,398
648
245
395
$ 25,905
$ 1,540
1,348
864
644
5,709
223

13,408
4,552
$ 28,288
$ 1,885
$ 7,225
$ 5,678
2,835
$174,193

14,186


22,712

9,911


26,954


$ 73,763
$ 65,047
40,365
1,725
$ 42,090
4,559
21,567
82,458
$ 108,584
10,756
147
515
38,981
31,699
4,853
2,417
1,265
$ 90,633
$ 2,867
1,764
7,543
1,880
36,474
6,190
9,490
19,624
43,931
$ 129,763
$ 29,893
$ 27,469
$ 51,940
31,889
$1,072,471

-------
                                       L-17
                                Table 3 (continued)
                                             Equipment   Labor    Materials
Indirect Cost
  Construction General Expense

  Contractor's Engineering and Fee

  TVA Engineering and Overhead

    Indirect Total

TOTAL PROJECT FIXED INVESTMENT
                                                Direct
                                               Subtotal
                                              $  106,365

                                                 169,687

                                                 129,058

                                                 405,110

                                              $1,477,581
                                       Table 4
                 Major Area Investment Requirements and Exponential
                  Scale Factors for Dry Limestone Injection Facilities3
Major process equipment
          area

General yard work
Limestone storage and feed
  system
Limestone drying system
Limestone grinding system
Limestone injection system
Equipment foundations
Instrumentation
Piping
Electrical  power supply
Revisions  & additions to
  powerhouse and boiler
Incremental electrostatic
  precipitator system
Incremental solids disposal
  system  for collecting and
  sluicing limestone solids
  to pond
a. Capacity = 20 tons limestone/hr.
b. Based on updated vendor proposals
c. Not scaled according to limestone throughput
Base 1972 investment,
	$	

        22,400

       111,100
       137,600
       309,500b
       160,100
        75,500
        51,400
       126,000
       105,100

       150,500
  Exponential scaling factor
based on limestone throughput

             .50

             .80
             .50
              b
             .40
             .60
             .25
             .50
             .45

             .50

-------
                                        L-18

costs for a  150 MW plant were estimated  by Cottrell Environmental Systems, Incorporated
(3) for each combination of sulfur content and injection stoichiometry, based on the change
in properties  of the particulates and the additional amount to be removed as a result of dry
limestone injection. Costs were then scaled according to power unit size using an exponent
of 0.85.
       The  design  for  incremental solids  disposal  systems  was  based  on  minimum
requirements as indicated  by vendors. These  investment costs  were  projected  for  each
individual  installation  taking into  consideration  the quantity of  injection solids to be
disposed and  the minimum recommended pipeline size.
       The sum of the investment  requirements for each major process area  is called direct
investment. The  indirect costs for  the project,  including engineering design  and project
supervision, construction expense, contractor fees, and contingency  are added to the direct
investment to obtain the total fixed capital investment. Indirect investment is estimated as a
percentage  of direct investment (10) and is based on power unit size as follo.Ws:

                                             Indirect  investment costs,
                                           percentage  of direct investment
                              	existing power units
                              50 MW         1&

Engineering design and
  supervision
Construction  expense
Contractors' fees
Contingency
   Total indirects                45             42              41              39

        Annual operating cost—On-stream time and  power  plant load are key  factors in
establishing annual operating costs for any process. For power systems, these factors  may
vary  for different  plants  within   the overall system  due to  electricity demand  and
maintenance. For  purposes of projection,  annual operating costs  are estimated on the basis
of 5,000 hrs  operation/yr at full load.
        The  following  is a  listing  of  the  breakdown  established  for projecting annual
operating costs:
A.  Direct costs
    1.   Delivered raw material
        a.  Limestone
    2.   Conversion costs
        a.  Operating labor and supervision including payroll overhead
        b.  Utilities
           (1) Fuel oil (drying)
           (2) Sluice water
           (3) Electricity
50 MW
9
14
9
13
150 MW
8
13
8
13
250 MW
8
12
8
13
350 MW
8
12
7
13

-------
                                         L-19

       c.   Maintenance
           (1) Labor and material
       d.   Analyses
B.  Indirect costs
    1.  Capital charges
    2.  Overhead
       a.   Plant
       b.   Administrative
C.  Annual operating cost (A and B)
D.  Thermal effect of dry limestone injection on operating cost of power plant
E.  Total annual cost (C and D)
       Each  of the above  cost components accounts  for a portion of the total annual
operating cost, and  is discussed below in order of relative  importance.

       1.  Raw material - Limestone is the  only  raw material required for dry limestone
injection. As indicated in a recent report  prepared for EPA by the M. W. Kellogg Company
(8), there are enormous deposits of carbonate rocks  in the United States, and reserves are
more  than  adequate for the foreseeable future.  The major deposits, including two-thirds of
all sulfur deposits, are located in the eastern half  of the  country where the vast majority of
fossil  fuel-fired  power  plants are located.  Numerous reserves in these areas provide a nearby
source of stone for most power plants.
       Relative to the potential  demand for limestone by power plants, production of these
materials is quite large in  most states; however, current  production is inadequate to supply
the potential needs  of  power   plants  in several Atlantic coastal  regions, notably  New
England.
       For a large majority  of  the power  plants in  the eastern half of the United States,
high calcium limestone could be delivered for less than $6.00/ton. About half could obtain
stone at less  than $4.00/ton. Costs for power plants located in western states generally would
be higher, because of the lack of  suitable nearby deposits.
       During  the  injection  tests,  the delivered cost of limestone at the  Shawnee steam
plant  averaged  $4.05/ton  which is compatible  with  costs reported by Kellogg; therefore, a
delivered cost of $4.05/ton of limestone is utilized for the  case projections. For additional
coverage, however,  the sensitivity of other limestone  prices on process operating costs will
be shown in Section II.
       2.  Capital charges -  The method  for financing  sulfur dioxide control processes  is
likely to depend upon the type  of  industry providing the investment capital and the nature
of the control   process, nonrecovery or  product recovery type.  In  the  past, it  has  been
assumed that nonrecovery pollution control  processes  installed on power plants are financed
on a regulated utility  basis similar to the  financing method for the initial  power plant. This
method of  financing is also assumed for the nonrecovery dry limestone injection process in
the projection of operating costs.

-------
                                         L-20
       For the power industry (regulated utility economics), the usual practice of including
in the  capital  charges a regulated return on investment and the state and  Federal income
taxes was followed  (5). A breakdown  of  the  capital charges is  given  in Table 5. The
depreciation rate is straight line, based on the remaining life of the  power plant after the
pollution  control  process  is  installed,  and is  a percentage of initial  fixed investment.
Property  insurance is  also based on  original  fixed  investment.  However, because most
regulatory commissions  base the annual permissible return on investment on the remaining
depreciation base  (that  portion of the original  investment yet to be recovered or "written
off"),  the  portion  of annual  capital charge to  be applied to  the  operating  cost declines
uniformly over the life of the investment.
                                       Tables

                  Annual Capital Charges for Power Industry Financing
                    (Existing Power Unit with 15-Yr. Remaining Life)

                                                                     As percentage of
                                                                   original investment
 Depreciation (based on 15-yr. remaining
  life for an existing power unit)                                             6.7

 Insurance                                                                  0.5
    Total rate applied to original
     investment                                                            7.2

                                                                      As percentage
                                                                      of outstanding
                                                                   depreciation base3
 Cost of capital (capital structure
  assumed to be 50% debt and 50% equity)
  Bonds at 8% interest                                                      40
  Equity at  12% return to stockholder                                        6.0
 Taxes

  Federal (50% of gross return or same
   as return on equity)                                                      § Q
  State (national average for states
   in relation to Federal rates)                                               4 g
     Total rate applied to depreciation
      base

a. Original investment yet to be recovered or "written off
base                                                                20.8

-------
                                         L-21
       Annual  return on  equity,  interest on  outstanding debt, and  income  taxes are
established in the same manner. The cost of money to the power industry is assumed to be
8% interest on  borrowed  funds and  12% return  on equity money to attract  investors.
Assuming a capital structure of 50% debt and 50% equity, the overall cost of money under
regulated  economics comes to  10%. Federal income taxes are assumed to be 50% of gross
income and state tax is  assumed to be  80%  of the national tax; the resulting state tax  is
higher than for  nonregulated industry, but it is about the nationwide average for  power
companies.
       The fairly well defined return  on investment for the power company  makes a  low
rate of depreciation  acceptable, and  return  on investment can  be  logically  included in
production cost  because it is a fixed charge usually passed on to the power customer.
        For convenience  in presenting  annual  operating cost results, average capital charges
based on  initial  fixed investment are utilized since it is not practical to present the variable
declining  balance portion  of the charge. For presentation  in this manner, capital charges
which normally account for depreciation and insurance are unchanged  at 7.2% of original
investment. Charges associated  with the  cost of capital  and taxes are applied as an average
charge equivalent to 10.4% of initial  investment. (10.4% x original  investment = 20.8% x
average  undepreciated  investment). When assessed  in  this  manner, the  overall  rate  is
equivalent to 17.6% of the  original investment.
        The average capital charge multiplied  by the number of years of operation gives the
same  actual  outlay of dollars as the  declining balance calculation; however,  the present
worth of the two methods is  different  (discounted  to  1972 dollars). There is, of course,
another  method (sinking  fund depreciation  plus  interest, or capital recovery factor) of
presenting a single annual percentage of  initial  investment  which gives the same present
worth of the lifetime capital charges as the declining balance calculation approach, but the
actual dollar outlay is different. Of the two procedures, the average capital charge method
has been  chosen for annual operating cost tables because  it can incorporate  straight line
depreciation, thus permitting simpler adjustment of the percentage of initial investment for
power units with various remaining lives.
        3.  Utilities - During the dry  limestone injection test program, utility usages were
measured for the following three processing functions:
    a. Limestone receiving, drying and conveying
    b. Limestone grinding, classifying,  and transport to feed tank
    c. Limestone injection into boiler
 In addition, utility requirements  peripheral  to the  process such as  additional water and
electricity for solids disposal were estimated. The following utility usage rates are projected:

-------
                                        L-22
                                                     Utility projections
            Process area
a. Limestone receiving, drying and
    conveying
b. Limestone grinding, classifying,
    and transport to feed tank
c. Limestone injection into boiler

         Peripheral area

d. Participate collection
e. Additional solids disposal
                                          Fuel oil
                 Sluice
                 water
   5.3 gal/
ton limestone
      Electricity
6.0 kWh/ton limestone
                          53.4 kWh/ton limestone
                          9.6 kWh/ton  limestone
                          Credit3
                          1.925 kWh/thousand
                          gal of sluice water
       Electricity usage rates for particulate collection varies for each case as indicated by
Cottrell  Environmental Systems,  Inc. However, CES  indicates that the total amount of
electricity required for dust collection is less due to dry limestone injection than is normally
required  for collecting fly ash alone; therefore, an operating cost credit is claimed equivalent
to the electricity saved. Unit costs which areincorporated in the case projections for utilities
are shown below:
                             Utility
                     No. 2 fuel oil  (drying)
                     Sluice water
                     Electricity
                  Unit cost

               $0.11/gal.
                  .03/Mgal.
                  .007/kWh
 Fuel oil cost is based on an acutal  1972 published price for Chicago, Illinois (7). Costs for
 sluice  water  and electricity are also 1972 prices;  however, they are somewhat  higher than
 typical power plant costs to compensate for the additional generation demand placed on the
 power unit and to account for the more  rapid capital recovery for the additional  facilities
 than required for new plants.
       4.  Operating labor and  supervision - Operating  labor  requirements for  the dry
 limestone  injection tests at Shawnee were somewhat high due to the extensive amount of
 monitoring required for the numerous sampling probes which were utilized. Consequently,
 a.  Electricity requirements are  reduced as a  result of different resistivities of the solids.
    Amount of reduction depends upon sulfur content and injection stoichiometry.

 b.  Sluice water is dependent upon  disposal system design rather than total solids disposal.

-------
                                         L-23
projections of operating labor are somewhat lower than  incurred during the tests. Since
labor  requirements are  primarily a function of limestone throughput and on-stream time,
annual labor requirements at 8,760 hours/year (365 days) were estimated for four levels of
injection at full load.  These  base  labor  requirements were  then  adjusted  according  to
on-stream ratio  using  a 0.5 scaling  exponent. The  estimated labor breakdown  at 8,760
hours/year  and the adjusted total labor requirement for operation at 5,000 hours/year are
shown in table 6.
                                         Tables
                                 Estimated Labor Requirements
                              for Dry Limestone Injection Process
                       Estimated annual operating labor requirement,
                          man-hrs. at 8,760  hours operation/year
Limestone
throughput,
tons(dry)/hour
0-25
25-50
50-75
75-100
Heavy equipment
operator
(unloading)
2,080
2,080
2,080
2,080
Conveying,
feeding
and disposal
2,080
4,160
6,240
8,760
Plant
operation
8,760
8,760
8,760
8,760
Super-
vision
400
500
600
700
Adjusted total
operating labor
required man hours
at 5,000 hours
Total operation/year
13,320
15,500
17,680
20,300
10,070
11,720
13,370
15,350
        Based on  1972 TVA labor rates  (13), a composite operating  rate  of  $6.00/hr
 including overhead and supervisory expense is  utilized for the evaluation. For the 52-case
 study,  labor costs are  not escalated over the life of the project. However, the  effect of
 escalation at rates  up to 10%/year is presented in Section II.
        5.  Maintenance -  Solids  drying  and  grinding  usually  are  maintenance  prone
 operations.  Although  actual  operating data over an extended  period  of time is the best
 source  of  information for  defining  maintenance  requirements,  insufficient  data  was
 generated during the Shawnee program to accurately define these costs. Maintenance costs
 chargeable to the process  are, therefore,  estimates based  on  actual  recorded  data.  For
 purposes  of this  study, precipitator  maintenance  is estimated as  two  percent  of  the
 precipitator  fixed  capital investment for 5,000 hours  annual operation. A slightly higher
 maintenance charge ranging from 3.1 - 3.5% is  projected for the combined drying grinding,
 injection, and solids disposal facilities. Specific areas which were maintenance prone, such as
 the hydroveyors in the sluice system, were recognized in arriving at these figures.
        Maintenance costs usually increase over  the life of a  project; however, in the case of
 a  power  plant  related  system  where on-stream  time  declines  over the remaining  life,
 estimating maintenance as a  percentage of  investment for a  given on-stream time  will
 probably suffice.  Estimates for other on-stream times are scaled exponentially according to
 on-stream ratio using a 0.6 scaling  exponent. Using this method, the maintenance per  unit
 time increases over the project life as on-stream time decreases.
        6. Overhead - Overheads  are usually a complex function of plant and company  size,
 and product research and marketing staff, and are likely to vary slightly from installation to
 installation.  However,  for  consistency in  the cost projections, a  common  method for

-------
                                        L-24

estimating  overheads  was  established.  In all  of  the cost projections  plant  overhead is
estimated  as  20% of conversion costs, and administrative overhead is estimated as 10% of
operating  labor. Although-costs may vary widely for an actual installation, these projections
are representative of the expected values.
       7.  Thermal  effect of dry limestone injection - When limestone is  injected into a
boiler, the required coal-firing rate for the power unit is adversely affected  by the level of
injection stoichiometry  for each sulfur content and must be adjusted to maintain  the same
power generating capacity prior  to dry limestone injection. Based on  operating  data  for
Shawnee unit 10, a coal-firing rate of 0.780 Ibs/kWh  prior to injection  is assumed for each
power plant  size considered.  This  firing  rate  is adjusted  upward  to compensate for  the
thermal effect  of  dry  limestone injection as discussed in Appendix  H, Additional Heat
Requirement Calculations.  Costs for the additional coal are estimated and displayed on  the
annual  operating cost  projections  as the thermal effect  of dry  limestone  injection  on
operating  cost of power plant. This charge is equivalent to a coal cost of $6.00/ton and a
processing cost of $0.30/ton, including incremental costs for grinding and conveying.
       8.  Analyses -  Purchased limestone and waste solids are the only materials which
require analyses in the  dry limestone injection  process. Since  both of  these materials  are
proportional, projections of analyses  requirements are estimated on the  basis of limestone
throughput. Based on Shawnee experience, approximately  1 hour/day or 208 hours/year at
an annual on-stream time of 5,000  hours is required for analyses at  a limestone throughput
of 20 tons/hour. Requirements for other limestone rates  are proportional  to the relative
limestone  usage.  A  rate of  $10.00/hour including overhead, supplies, and  supervisory
expense is projected for  laboratory work.
       9. Working capital - For projection purposes, working capital for the dry limestone
injection process may be estimated as the equivalent cost of a four weeks supply of raw
material (limestone). Although the  magnitude of the estimated working capital required  for
5,000 hours  annual operation varies from $2,600 for a 50 MW, 0.8% S coal, 3.0 injection
stoichiometry installation  to  $153,000  for  a  350 MW,  5.0%  S coal, 4.0  injection
stoichiometry installation,  the effect  on  annual and  lifetime operating  costs  at a cost of
money of 10% is relatively small.
       Lifetime Operating Costs—Under  regulated economics, annual operating costs vary
each year as  the rate base declines due to  depreciation "write-off"  (the cost of money and
income taxes are applied to undepreciated portion of investment); in addition, any changes
in on-stream  time of the power unit must be recognized. For any given case it is desirable,
therefore, to have a year-to-year tabulation of operating costs. Furthermore, recognizing the
time  value of money,  these annual  operating  costs  should be  discounted  at  the cost of
money (10% for this study) to the initial year of operation  for ready comparison of present
worth to  other pollution control means such as the annual costs  required for low sulfur
fuels.
       The total life of  a coal-fired  power  unit  is about 30  years (5). For the  52 case
parametric study, lifetime operating costs  are based on 15 years remaining life of the power
plant after installation of the dry limestone injection process; however, the effect of various

-------
                                        L-25

other remaining lives is also studied. Historically, the operating usage of most power plants
declines toward the end of their life. To reflect this experience, the following declining load
operating profile is assumed during the remaining years of operation.:

                                                  Annual operation,
                                                   (on-stream time)
                  Plant age,     Plant remaining        hours  at full
                    years          life, years        generating capacity

                   16-20          15-11               5,000
                   21-25          10-6               3,500
                   26-30           5-1               1,500
        Lifetime operating cost  analyses are extremely valuable in evaluation of regulated
 investments.  They are an  accumulation  of each  year's cost  and, therefore,  are more
 representative of actual outlays for process operation.
        Since rate of investment profitability is prescribed under regulated economics, the
 data  generated by the tabulation of lifetime operating costs  indicates the total effect of
 pollution  abatement on the  cost  of  power  to the  consumer.  Actual  and present worth
 lifetime costs are, therefore, projected for each of the cases as overall measures of  process
 economics.  In  addition, equivalent lifetime unit  operating costs expressed  as $/ton coal
 burned, mills/kWh, and $/ton sulfur removed are presented.

-------
                                             L-27

II. Summary of Results and Conclusions

                            Results of the 52 Case Parametric Study

           Investment—The  estimated total  fixed   investment  requirements  for  the  dry
   limestone injection process are summarized in table 7 for each of the 52 cases established.
   Abbreviated investment estimates which show the major area investment costs are given in
   tables A-l to A-52 of Appendix A in Process Economics Section. It should be mentioned
   that  the system  used  in  these projections is  one of  minimum cost,  and may  not be
   compatible to all  potential users of the process. The estimated  investment requirements
   would  be  higher for  power plants which require additional pond facilities for disposal of
   solids,  or  for systems with other  combinations  of existing dust  collection facilities.  The
   effect of these additional requirements is discussed later.
                                            Table 7
                    Total Fixed Investment Requirements for Dry Limestone Injection Process
                              Applied to Existing Power Units Equipped with
                            Mechanical and Electrostatic Dust Collectors in Series
Sulfur
in coal
%
0.8
0.8
0.8
0.8
0.8
3.0
3.0
3.0
3.0
5.0
5.0
5.0
5.0
Injection stoichiometry,
moles CaO injected per
mole sulfur in coal
3.0
4.0
5.0
6.0
7.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
Total fixed
50 MW
$
751,500
834,500
908,300
975,000
1,036,300
817,100
1,070,500
1,271,500
1,442,000
995,300
1,332,900
1,602,600
1,838,700
units
$/kW
15.0
16.7
18.2
19.5
20.7
16.3
21.4
25.4
28.8
19.9
26.7
32.1
36.8
150 MW
$
1,280,100
1,431,500
1,568,800
1,694,400
1,808,000
1,404,600
1,874,200
2,251,400
2,574,200
1,736,200
2,369,500
2,926,600
3,376,200
units
$/kW
8.5
9.5
10.5
11.3
12.1
9.4
12.5
15.0
17.2
11.6
15.8
19.5
22.5
investment
250 MW
$
1,695,100
1,868,100
2,086,100
2,253,600
2,407,700
1,865,600
2,498,900
3,011,400
3,498,000
2,314,500
3,221,100
3,968,400
4,582,000

units
$/kW
6.8
7.5
8.3
9.0
9.6
7.5
10.0
12.0
14.0
9.3
12.9
15.9
18.3

350 MW
$
2,032,300
2,278,800
2,503,200
2,707,700
2,893,300
2,238,600
3,005,900
3,676,800
4,262,100
2,782,700
3,927,000
4,766,400
5,645,500

units
$/kW
5.8
6.5
7.2
7.7
8.3
6.4
8.6
10.5
12.2
8.0
11.2
13.6
16.1
    a. Fixed investment includes cost of additional electrostatic precipitator for reducing dust emission to same level obtained
      prior to installation of dry limestone injection process. Additional pond disposal area not included.
           The  total fixed  investment for the dry limestone  injection  process ranges  from
    $751,500 ($15.0/kW) for a 50 MW - 0.8% S coal-fired unit with an injection stoichiometry
    of 3.0 to $5,645,500 ($16.1/kW) for a 350 MW - 5.0%  S  coal-fired unit with an injection
    stoichiometry of 4.0; however, unit investment costs vary from $5.8 to $36.8/kW depending
    upon power unit size, sulfur in coal, and injection stoichiometry.
           The effect of power unit size and injection  stoichiometry on total  dry limestone
    process investment is shown in figures 8, 9, and  10 for the  three variations in sulfur content
    of coal. The relationship between sulfur content of coal and injection stoichiometry on total
    fixed investment for  a 150 MW power  unit is presented in figure 11.
           Relative investment cost distribution—The relative  distribution of direct investment
    costs  for  the three  base cases  is shown  in table 8.  As indicated, the  limestone grinding
    system and the incremental electrostatic precipitator system  are the major investment  items
    for the process. Although the distribution of estimated  costs varies somewhat for  each of

-------
                                                                                                             00
0
  0
                                    Power unit size, MW
  Figure    8  .  Effect of Power Unit Size and Injection Stoichiometry on Total Dry
                 Limestone Process Investment:  0.8% S Coal

-------
2
  .
•d
C   -3
O   J
(0
X
1-1

-------
                                                                                                            oo
                                                                                                            o
0
                        100
                    150         200


                  Power unit size, MW
350
  Figure   10
Effect of Power Unit Size and Injection Stolen!ometry on Total Dry

Limestone Process Investment:  $.0% 3 Coal

-------
                  I

           Existing units
(9
c
O
43
G
V
5
0)

I
•o.
0>
X
i—•  i
OS  1
-P
   0
                                          I
                                                                                  26.67
                                                                                  20.00  g
                                                                                          to

                                                                                          I
                                                            13.33
•8
X
•H

-------
                                         L-32
                                       Table 8

                  Relative Distribution of Projected Direct Investment
                       Costs for Dry Limestone Injection Process

                                           Relative  investment distribution,
                                            % of subtotal direct investment
       Process area
General yard work
Limestone storage and feed
  system
Limestone drying system
Limestone grinding system
Limestone injection system
Equipment foundations
Instrumentation
Piping
Electrical power supply
Revisions and additions to
  powerhouse and boiler
Incremental electrostatic
  precipitator system
Incremental solids disposal
  system
    Total direct investment
150MW-0.8%S
   5.0 stoich.
        1.3

        4.7
        7.7
      15.1
        9.9
        3.9
        3.7
        7.1
        6.2

        8.5

      22.8

        9.1
150 MW-3.0%S
   2.0 stoich.
       1.3

       5.5
       8.0
      16.5
       9.8
       4.1
       3.4
       7.3
       6.2

       8.7

      21.6

       7.6
150 MW - 5.0% S
   2.0 stoich.
      1.3

      6.5
      8.2
     18.3
      9.5
      4.5
      3.1
      7.5
      6.2

      8.9

     20.0

      6.0
     100.0
    100.0
   100.0
the 52 cases, these distributions indicate the relative contribution of each processing area to
the subtotal direct costs.
       Annual operating cost—Based on an annual operation of 5,000 hours/year, projected
operating cost results of the 52-case parametric study are summarized in tables 9, 10, and 11
for each  of the three levels of sulfur in coal. Detailed breakdowns of these projected annual
costs are  presented in tables A-53 through A-104 of Appendix A.
       Average annual operating costs range  from $298,400 ($3.05/ton coal burned) for a
50 MW  - 0.8% S coal-fired  unit  with an injection  stoichiometry of 3.0 to $4,122,700
($5.85/ton  coal  burned)  for  a  350  MW  5.0% S  coal-fired  unit  with  an  injection
stoichiometry of 4.0. Unit operating costs vary from $1.23 to $8.72/ton coal burned, or
from  0.48 to 3.51 mills/kWh.  Operating costs per ton of sulfur removed decrease with
increasing  power unit size and injection stoichiometry.  These  unit  costs  range  from
$316/ton sulfur  removed  for a 350  MW -  5.0% S  coal-fired unit with an  injection
stoichiometry of 4.0 to  $2,664/ton sulfur removed for a 50 MW - 0.8% S coal-fired unit
with an injection stoichiometry of 3.0.
       Based on the results given in the tables, the effects of several variables on operating
costs are  presented graphically.

-------
                                      L-33
                                     Table 9

                  Average Annual Operating Cost for Dry Limestone
                    Injection Process Under Regulated Economics
                                 0.8% Sulfur Coal3
Power
unit
size, MW
50
50
50
50
50
150
150
150
150
150
250
250
250
250
250
350
350
350
350
350
Injection stoichiometry,
moles CaO injected per mole
sulfur in coal
3.0
4.0
5.0
6.0
7.0
3.0
4.0
5.0
6.0
7.0
3.0
4.0
5.0
6.0
7.0
3.0
4.0
5.0
6.0
7.0
Average
annual
cost, $
298,400
331,300
362,800
392,300
420,800
501,600
580,900
656,600
730,100
801,500
681,300
796,000
920,300
1,034,100
1,145,200
843,800
1,006,000
1,162,400
1,315,100
1,477,100
Unit
$/ton
coal
3.05
3.38
3.69
3.99
4.27
1.71
1.97
2.23
2.47
2.71
1.39
1.62
1.87
2.10
2.32
1.23
1.47
1.69
1.91
2.14
operating
mills
/kWh
1.19
1.33
1.45
1.57
1.68
0.67
0.78
0.88
0.97
1.07
0.55
0.64
0.74
0.83
0.92
0.48
0.58
0.66
0.75
0.84
cost
$/ton S
removal
2664
2301
1972
1816
1644
1529
1345
1207
1127
1054
1217
1106
998
958
895
1076
998
902
870
824
a.  Existing units - 15 yrs. remaining life
   5000 hrs. operation/yr

-------
                                      L-34

                                     Table 10

                  Average Annual Operating Cost for Dry Limestone
                     Injection Process Under Regulated Economics
                                 3.0% Sulfur Coal3
Power
unit
size, MW
50
50
50
50
150
150
150
150
250
250
250
250
350
350
350
350
Injection stoichiometry,
moles CaO injected per mole
sulfur in coal
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
Average
annual
cost, $
323,100
435,100
536,400
631,700
561,800
835,200
1,091,400
1,337,300
773,100
1,197,800
1,612,100
2,018,100
965,900
1,547,400
2,120,500
2,667,100
Unit
$/ton
coal
3.30
4.42
5.42
6.36
1.91
2.83
3.68
4.48
1.58
2.43
3.26
4.06
1.41
2.25
3.06
3.83
operating
mills
/kWh
1.29
1.74
2.15
2.53
0.75
1.11
1.46
1.78
0.62
0.96
1.29
1.61
0.55
0.88
1.21
1.52
cost
$/ton S
removal
1188
800
651
576
695
512
443
406
568
440
391
368
507
406
368
348
a.  Existing units - 15 yrs. remaining life
   5000 hrs. operation/yr

-------
                                      L-35

                                     Table 11

                  Average Annual Operating Cost for Dry Limestone
                    Injection Process Under Regulated  Economics
                                 5.0% Sulfur Coal3
Power
unit
size, MW
50
50
50
50
150
150
150
150
250
250
250
250
350
350
350
350
Injection stoichiometry,
moles CaO injected per mole
sulfur in coal
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
Average
annual
cost, $
399,300
569,300
726,400
878,000
748,000
1,174,500
1,611,000
2,012,800
1,061,200
1,762,000
2,426,800
3,081,500
1,351,200
2,307,000
3,198,800
4,122,700
Unit
$/ton
coal
4.06
5.74
7.27
8.72
2.54
3.95
5.38
6.66
2.16
3.56
4.86
6.12
1.96
3.33
4.57
5.85
operating
mills
/kWh
1.60
2.28
2.91
3.51
1.00
1.57
2.15
2.68
0.85
1.41
1.94
2.47
0.77
1.32
1.83
2.36
cost
$/ton S
removal
876
624
525
471
550
429
389
360
465
386
351
331
412
361
330
316
a.    Existing units - 15 yrs. remaining life
     5000 hrs. operation/yr

-------
                                         L-36

       The effects of sulfur content of coal and injection stoichiometry on annual and unit
operating costs for a 150  MW installation are shown in figure  12. Figures 13, 14,  and  15
indicate  the  relationship  between  power  unit size, injection  stoichiometry, and  annual
operating costs for each of the three levels of sulfur. The effects of injection stoichiometry
and  power unit  size on  unit  operating cost  expressed  as  both $/ton  coal  burned and
mills/kWh are indicated in  figures 16 and 17 for 0.8 and 3.0% S coals. Although somewhat
higher costs are obtained,  the  relationship for  5.0% sulfur coal is similar. Unit operating
costs per ton  of sulfur removed are shown in figures 18,  19,  and 20 for  each  of the three
levels of  sulfur in coal.
       Relative operating cost distribution—The relative  distribution of  projected  annual
operating costs for the three base cases at an annual on-stream time of 5,000 hours is shown
in table  12. As shown in the table, limestone cost and capital charges  are the two most
prominent cost  items. Although  the relative cost  distribution  of each  item changes
somewhat  with variations  in  power  unit  size,  sulfur  content  of fuel,  and injection
stoichiometry, the other cost components are of minor importance in  relation to the  annual
costs for limestone and capital charges.
       Lifetime operating  cost—Based on the operating profile  established for the 52 case
parametric study, lifetime  operating costs were projected. Results of these projections are
summarized in tables  13,  14,  and 15 for the three levels  of  sulfur in coal.  Computer
print-outs  which  show the  year-to-year  operating costs corresponding  to  these lifetime
projections are presented in tables A-105 to A-156 of Appendix A. In addition to the actual
outlay annual  values  shown in these  printouts, both actual and  discounted  overall total costs
and unit  costs  either  per ton of coal  burned or mills per kilowatt hour are presented.
       Lifetime operating costs range from $3,909,400 (present worth = $2,223,900) fora
50  MW  - 0.8% S coal-fired unit with  an injection  stoichiometry of 3:0 to $47,281,000
(present  worth =  $27,443,100) for a 350 MW  - 5.0% S  coal-fired unit  with  arrinjection
stoichiometry  of 4.0. Lifetime unit operating costs are somewhat higher than average annual
operating costs due to the  pronounced effect of the declining  operating profile  assumed for
the power plant.
       The effect of power unit  size  and injection  stoichiometry  on  (1)  lifetime total
operating cost, (2) lifetime unit operating cost, $/ton coal  burned  and  (3) lifetime unit
operating cost, $/ton sulfur removed,  is shown  in figures 21, 22, and 23, respectively, for a
0.8% S coal-fired  installation. Both present worth  and actual costs are indicated over the
complete range of injection stoichiometries utilized for the parametric study. Figures 24,
25, and 26 show similar relationships for a 3.0% S coal-fired  installation  with  an injection
stoichiometry  of 2.0. Relationships for a 5.0% S coal-fired  installation with  an injection
stoichiometry  of 2.0  are shown in figures 27, 28, and  29.

-------
o>
O
•a
Ui
C
O
-p
(0
o
o
a
•H
-P
 0)
       Existing  units

       5QOO hrs annual  operation

       Regulated economics
   2.0
   1-5
1.0
   0.5
   0
       o
6.76
                                                                                     1
                                                                                5.07
3.38
                                                                                1.69
                                                                                     -P
                                                                                     CO
                                                                                     O
                                                                                     o
                                                                                         I
                                                                                        -p
                                                                                        •H
                                                                                        a
        Figure   12
                             23            ^5

                                Sulfur in coal, %


                    Effect of Sulfur Content of Coal and Injection Stoichiometry

                    on Annual and  Unit Operating Cost of Dry Limestone

                    Process:  150  MW Units
2.67
          2.00
1.33
          0.67
                                                                                                   (0

                                                                                                   rH
                .p
                s
                o
                &0
                                                                                                   g
                                                                                                o

                                                                                                •p
                                                                                                T-l

                                                                                                a
                                                                                                                    00
                                                                                                                    •vj

-------
        Existing units
        5000 hr. annual operation
        Regulated economics
0
   0
       100          150         200

       Power unit size, MW
                                                                                                               r
                                                                                                               CAJ
                                                                                                               00
    Figure
Effect of Power Unit Size and Injection Stoichiometry on Annual
Operating Coat of Dry Limestone Process:  0.8# S Coal

-------
w
r-t
O
TJ


-------
 10
 fH
 43
 I
 •H
 tn
 o  2
 o
H

I
                   I            I
         Existing units
         5000 hr. annual operation
         Regulated economics
      0
Figure _1*
                      100
   150          200

Power unit size, MW
                      Effect of Power Unit Size and Injection Stoichiometry on Annual
                      Operating Cost of Dry Limestone Process:  5.0% S Coal

-------
                I            I
        Existing units
        5000 hr annual operation
        Regulated economics
\
 n)
 o
 u
 4J
 o
 o
 0)
 0.
 o
                I
                              350 tf* units
I
                                                                               5.16
                                                                               2.36
                                                                               1.58
                                                         m
                                                                                     m
                                                                                     O
                                                                                     V
                                                         •H

                                                         0)

                                                         V

                                                         O

                                                         -u
                                                   0.79
               34            5678
                Stoichiometry, moles CaO injected per mole S in coal

    Figure  l£  .  Effect of Injection Stoichiometry and Power Unit Size on
                   Unit Operating Cost of Dry Limestone Process:  0.8$ S Coal

-------
                             T
         Existing units
         5000 hr annual operation
         Regulated economics
-a
8
 O
 O

 §
4J
•OT-
4J
CO
O
U
v-4
J-l
n)
M
                                                     1
                                                                  I
                                                                                3.16
                                                                                2.36
                                                                                1.58
                                                                                       I
                                                                                       w
                                                                                       •u
                                                                                       oj
                                                                                       O
                                                                                       o

                                                                                       (90
                                                                                       c
                                                                                       co


                                                                                       o
                                                                                       -P
                                                                                 0.79
       Figure
                 12345
              Stoichiometry,  moles CaO injected per mole S  in  coal


               17  .   Effect of Injection Stoichiometry and  power Unit Size on
                      Unit Operating Cost of Dry Limestone Process:   3.0$ S Coal

-------
§  2500
•3
to
   2000
-P
CO
o
o

1
-p
S

I
   1500
   1000
    500
        0
        Figure
                                                                     I             I
                                                                 Existing units
                                                                 5000 hrs annual  operation
                                                                 Regulated economics
                                                                                                                u>
                    50
100          150         200

         Power unit size, MW
250
300
350
                       Effect of Power Unit Size and Injection Stoichiometry on Dry Limestone
                       Process Operating Cost Per Ton of Sulfur Removed:  0.8$ S Coal

-------
 §2000
 CO
 §1500
-^
 •%
•p
8
o
glooo
•H
-p
g
•p
B  500
                                                                   Existing units
                                                                   5000 hrs annual operation
                                                                   Regulated economics
   1.0  Injection stoichiometry
0          50
                               100         150          200

                                        Pover unit size, MW
                                             250
300
350
       Figure   19
Effect of Power Unit Size and Injection Stoichiometry on Dry Limestone
Process Operating Cost Per Ton of Sulfur Removed:  3.0$ S Coal

-------
I
1 800
DO


g
8
o
bO
C
2
(U
&
  14-00
   200
                                                                 Existing units
                                                                 5000 hrs annual operation
                                                                 Regulated economies
                                                                                                              en
       0
        Figure  20
                              100
                                          150         200         250
                                                 Power Unit size, MW
300
350
                       Effect of Power Unit Size and Injection Stoichiometry on Dry Limestone
                       Process Operating Cost Per Ton of Sulfur Removed:  5.0$ S Coal

-------
                                      L-46

                                      Table 12

                   Relative Distribution of Projected Operating Costs
                         for Dry Limestone Injection Process

                                150 MW-0.8%S   150 MW - 3.0% S   150 MW - 5.0%
                                   5-Ostoich.         2.0stoich.        2.0stoich.
DIRECT COSTS
Delivered raw material

  Limestone                            25.2               29.8              35.6

Conversion costs

  Operating labor and
   supervision                            9.2                7.2               5.2

  Utilities
Fuel oil
Sluice water
Electricity
Maintenance
Drying, grinding,
injection & solids
disposal area
Dust collection
Analyses
INDIRECT COSTS
Average capital charges
Overhead
Plant
Administrative
Thermal effect of dry limestone
injection on operating cost of
power plant
Total operating cost
3.6
1.2
3.4

6.1
1.1
0.2
42.1
4.9
0.9
2.1
100.0
4.3
1.0
3.8

5.8
1.0
0.2
39.5
4.6
0.7
2.1
100.0
5.1
0.7
4.5

5.2
0.8
0.1
35.5
4.3
0.5
2.5
100.0

-------
                                                           Table 13
                                           Lifetime Operating Cost for Dry Limestone
                                          Injection Process Under Regulated Economics
                                                       0.8% Sulfur Coal3
                                                 Lifetime operating cost
                         Cumulative present worth of net
                            increase in cost of power.
Power
unit
size, MW
50
50
50
50
50
150
150
150
150
150
250
250
250
250
250
350
350
350
350
350
Injection stoichiometry,
moles CaO injected per
mole sulfur in coal
3.0
4.0
5.0
6.0
7.0
3.0
4.0
5.0
6.0
7.0
3.0
4.0
5.0
6.0
7.0
3.0
4.0
5.0
6.0
7.0
(net increase

$
3,909,400
4,326,400
4,715,000
5,081,600
5,428,600
6,489,000
7,438,200
8,337,700
9,200,500
10,030,300
8,715,800
10,038,500
11,505,000
12,818,800
14,087,600
10,696,900
12,562,700
14,358,000
16,096,400
17,930,200
$/ton
coal
3.99
4.41
4.80
5.16
5.51
2.21
2.53
2.83
3.12
3.39
1.78
2.05
2.34
2.61
2.86
1.56
1.83
2.09
2.34
2.60
in cost of Power)

mills/kWh
1.56
1.73
1.89
2.03
2.17
0.87
0.99
1.11
1.23
1.34
0.70
0,80
0.92
1.03
1.13
0.61
0.72
0.82
0.92
1.02
$/ton
S removed
3491
3004
2563
2353
2121
1978
1722
1533
1420
1320
1556
1394
1251
1187
1101
1364
1246
1115
1065
1001
discounted at 10%/yr

$
2,223,900
2,464,300
2,689,400
2,901,100
3,102,100
3,712,400
4,262,400
4,784,000
5,284,900
5,766,600
4,999,800
5,768,300
6,619,100
7,382,400
8,120,000
6,146,600
7,230,600
8,274,100
9,285,400
10,347,900
$/ton
coal
2.27
2.51
2.74
2.95
3.15
1.26
1.45
1.62
1.79
1.95
1.02
1.18
1.35
1.50
1.65
0.90
1.05
1.20
1.35
1.50

mills/kWh
0.89
0.99
1.08
1.16
1.24
0.49
0.57
0.64
0.70
0.77
0.40
0.46
0.53
0.59
0.65
0.35
0.41
0.47
0.53
0.59
$/ton
S removed
1986
1711
1462
1343
1212
1132
987
879
816
759
893
801
719
684
634
784
717
642
614
577
a.  Existing units - 15 yrs. remaining life. Assumed operating profile:
5 yr @ 5000 hr/yr
5 yr @ 3500 hr/yr
5yr @ 1500 hr/yr

-------
                                                            Table 14

                                             Lifetime Operating Cost for Dry Limestone
                                           Injection Process Under Regulated Economics
                                                        3.0% Sulfur Coal3
                                                  Lifetime operating cost
Cumulative present worth of net
   increase in cost of power,
Power
unit
size, MW
50
50
50
50
150
150
150
150
250
250
250
250
350
350
350
350
Injection stoichiometry,
moles CaO injected per
mole sulfur in coal
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
(net

$
4,227,100
5,607,200
6,826,500
7,955,200
7,220,700
10,438,200
13,388,600
16,181,700
9,808,700
14,708,000
19,404,000
23,965,700
12,121,000
18,751,600
25,199,100
31,268,000
increase
$/ton
coal
4.31
5.70
6.90
8.00
2.46
3.53
4.51
5.43
2.00
2.99
3.92
4.82
1.77
2.72
3.64
4.49
in cost of Power)

mills/kWh
1.69
2.24
2.73
3.18
0.96
1.39
1.79
2.16
0.78
1.18
1.55
1.92
0.69
1.07
1.44
1.79
$/ton
S removed
1554
1031
828
726
894
640
543
491
721
541
471
437
637
492
437
408
discounted at 10%/yr

$
2,406,900
3,205,200
3,911,300
4,565,900
4,135,700
6,002,800
7,717,400
9,342,200
5,633,500
8,480,000
11,207,900
13,863,600
6,973,000
10,824,500
14,573,700
18,110,200
$/ton
coal
2.46
3.26
3.95
4.59
1.41
2.03
2.60
3.13
1.15
1.72
2.27
2.79
1.02
1.57
2.10
2.60

mills/kWh
0.96
1.28
1.56
1.83
0.55
0.80
1.03
1.25
0.45
0.68
0.90
1.11
0.40
0.62
0.83
1.03
$/ton
S removed
885
589
475
417
512
368
313
283
414
312
272
253
366
284
253
236
a.  Existing units - 15 yrs. remaining life. Assumed operating profile: 5 yr @ 5000 hr/yr
                                                                5 yr @ 3500 hr/yr
                                                                5 yr @ 1500 hr/yr

-------
                                                           Table 15

                                            Lifetime Operating Cost for Dry Limestone
                                          Injection Process Under Regulated Economics
                                                      5.0% Sulfur Coal3
                                                 Lifetime operating cost
                         Cumulative present worth of net
                            increase in cost of power,
Power
unit
size, MW
50
50
50
50
150
150
150
150
250
250
250
250
350
350
350
350
Injection stoichiometry,
moles CaO injected per
mole sulfur in coal
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
1.0
2.0
3.0
4.0
(net

$
5,172,200
7,219,100
9,067,100
10,830,500
9,423,500
14,341,700
19,304,000
23,788,000
13,152,300
21,118,800
28,537,000
35,742,200
16,533,600
27,296,600
37,086,500
47,281,000
increase
$/ton
coal
5.26
7.28
9.08
10.76
3.20
4.82
6.44
7.87
2.68
4.26
5.71
7.10
2.40
3.94
5.30
6.71
in cost of Power)

mills/kWh
2.07
2.89
3.63
4.33
1.26
1.91
2.57
3.17
1.05
1.69
2.28
2.86
0.94
1.56
2.12
2.70
$/ton
S removed
1134
792
655
581
693
524
466
425
577
463
412
384
518
428
383
362
discounted at 10%/yr

$
2,953,500
4,139,200
5,211,300
6,235,100
5,413,800
8,271,800
11,153,800
13,765,400
7,575,100
12,204,500
16,526,400
20,723,500
9,538,500
15,799,300
21,504,200
27,443,100
$/ton
coal
3.00
4.18
5.22
6.19
1.84
2.78
3.72
4.56
1.54
2.46
3.31
4.12
1.39
2.28
3.08
3.89

mills/kWh
1.18
1.66
2.08
2.49
0.72
1.10
1.49
1.84
0.61
0.98
1.32
1.66
0.55
0.90
1.23
1.57
$/ton
S removed
648
454
377
335
398
302
269
246
332
268
239
222
305
247
222
210
                                                                                                                                    (£>
a.  Existing units - 15 yrs. remaining life. Assumed operating profile:
5 yr @ 5000 hr/yr
5 yr @ 3500 hr/yr
5yr @ 1500 hr/yr

-------
 CO
 h
 at
 O
•O
 to
 a
 o

    20
    15
3   10
Pi
o
0

-P
     5 —
	 Actual dollars
-— Present worth if discounted at 10$ to initial yr
Existing units - 15 yrs remaining life
Regulated economics
                                                                                                                 tn
                                                                                                                 o
                                        Power unit size, MW

        Figure  21  .  Effect of Power Unit Size and Injection  Stoichiometry on Lifetime
                       Increase in Cost of Power Using Dry Limestone  Injection:  0.8$ S Coal

-------
c

I
r-l
8
O
C
o
•p
00
o
o
    8
           	 Actual dollars
           -— Present worth if discounted at 10^6 to initial yr
           Existing  units  -  15 yrs  remaining life
           Regulated economics
o
-p
•U
V
                                 Injection Stoichiometry
    01
                              100         150          200

                                        Power  unit  size,  MW
                                                                  250
300
350
      Figure   22
                     Effect of  Power Unit Size  and Injection Stoichiometry  on  Dry  Limestone
                     Process Operating Cost Per Ton of Coal Burned Over Life of  Plant:
                     0.8^ S Coal

-------
 •o
 0)
4>
h
    4000
 eg

 C
 O
(0
O
u
CD
M

&
O
    5000
    2000
    1000
•P

Vi
•H
H3
             	 Actual dollars
             — Present worth if discounted at 10$ to initial yr
             Existing units - 15 yrs remaining life
             Regulated economics
                      3  Injection Stoichiometry
                                100
                                           150
200
250
300
350
                                          Power unit size, MW
          Figure
                        Effect of Power Unit Size and Injection Stoichiometry on Dry Limestone
                        Process Operating Cost Per Ton of Sulfur Removed  Over Life of Plant:
                        0.8# S Coal

-------
CO
     20
    HI             I            I
	 Actual dollars
--- Present worth if  discounted at 10% to initial yr
Existing units - 15 yrs  remaining life
Regulated economics
2.0 injection stoichiometry
e
o
•H
+3
(0
 «J
 0)

•H
4->
 V
Vi
     10
                                                                                                                CJI
                                                                                                                CO
                               100
                               150         200


                             Power unit size,  MW
250
300
350
          Figure
           Effect  of Power Unit Size and Injection Stoichiometry on Lifetime
           Increase  in Cost of Power Using Dry Limestone Injection:   J.0# S Coal

-------
                 Actual dollars
     8
 a
 o
 v
 c
 o
•P
W
O
o
01
IH
•»
P.
O
§

0>
V

•rl
1-3
— Present worth if discounted at 10$ to initial yr
Existing units - 15 yrs remaining life
Regulated economics
2.0 injection stoichiotnetry
                                                                                                  en
                              100
                             150
200
250
500
550
                                         Power  unit  size,  MW
        Figure   25 •  Effect of Power Unit Size  and  Injection Stoichiooetry on Dry Limestone
                       Process Operating Cost  Per Ton of Coal Burned Over Life of Plant-
                       5.0# s Coal

-------
                                 T
                                                          T
?
1
CO

c
O
-P
-P
0>
O
O

8P
•H
-p

2
O

J->
•H
C



-------
 CO
 to

A
<-4
 O
•o
c
O
-p
ea
O
v
-U
«5
V.

&
O
V
4-4
      I             I            I            I

	 Actual dollars
--- Present worth  if discounted  at  lO^t to  initial yr
Existing units - 15 yrs remaining life
Regulated economics
2.0 injection stoichiometry
    20
                                                                                                      cr>
                                                          MW
                         Effect of Power Unit Size and  Injection Stoichiometry on Lifetime
                         Increase in Cost of Power Using Dry Limestone Injection:  5.0$ S Coal

-------
 
 4)
 -4J

 V
            	 Actual dollars

            	 Present worth if discounted  at  10# to initial yr

            Existing units - 15 yrs remaining life

            Regulated economics

            2.0 injection stoichiometry
       Figure
                   150         200



                 Power unit size, MW



Effect of Power Unit Size and Injection Stoichiometry on Dry Limestone

Process Operating Cost Per Ton of Coal Burned Over Life of  Plant:

5.0$ S Coal

-------
 o
 e
 
-------
                                         L-59
                             Results of Sensitivity Analyses

       Sensitivities of the dry limestone injection process investment and operating costs to
variations in several of the major factors are discussed below.
       1. Sootblowers—The effect  of additional sootblower  requirements on total  fixed
capital investment  for  the  three base case installations is shown in  table 16. For  these
projections, a total installed cost of $40,000 each including indirect costs was  utilized.
These results indicate that total  investment  requirements are increased less than 10% with
installation of up to four additional sooblowers. Although total operating costs were not
established,  capital  charges  account for  an  increase   in  annual  operating  costs  of
approximately $7,000 for each.
       2. Particle size of injected limestone—The dry grinding and classifying equipment at
Shawnee were designed and operated at various  limestone size reduction capabilities so the
effect of particle size on  SO2 removal could be  determined. Two levels of grind, 80% - 400
mesh and  50% - 400 mesh, were given greatest attention. Although  the Shawnee data was
limited  and is not totally conclusive, directional results of these and other investigations
indicate that increased  SO2  removal efficiencies  are obtained with injection of finer ground
limestone.  To determine the sensitivity  of  limestone  particle size on  process economics,
investment and operating cost data for three levels of grind at various throughput capacities
were established (2). Results shown in figure  30 indicate that the investment required  for
grinding to 80% - 400 mesh is about 35-40% greater than that required for grinding to 80% -
200 mesh; however,  the higher grinding  capability  increases  total   process investment
approximately 7-10%.
        Operating cost results shown in figures 31 and 32 indicate that overall grinding costs
are approximately  25-30% higher for the fine  grind facilities.  The effect of higher levels of
grind on overall process costs is  realtively small  because grinding costs are^only 5-6% of  the
total operating cost.
        It should be noted that,  based on the  limited Shawnee data  using stones of varying
hardness, grindability is not a significant cost factor.
        3.  Particulate removal alternatives—The particulate collection facilities on Shawnee
unit  10 consist of  a  65% effective mechanical collector followed  by  a  90%  effective
electrostatic  precipitator. This system which has an overall fly ash collection efficiency of
97% was designed, installed, and placed into  operation  prior to  installation of  the  dry
limestone injection process.
        Additional  solids collection  capacity was not  installed for  the injection  tests;
however, performance data with and without  dry limestone  injection  were derived  for
estimating incremental requirements and costs.
        Although  EPA has  not  promulgated particulate  emission  standards  for  existing
power  units, many  states  and  local governing bodies  have. In many cases, particulate
removal  efficiencies  greater than 97%  are  required.  For  the lack  of a better basis, it  is
assumed that these  regulations  will  require plants utilizing dry  limestone  injection to
maintain particulate emissions at a level equivalent to  that obtained prior  to installation of

-------
                 Table 16

Effect of Additional Sootblower Requirements
     on Total Fixed Capital Investment:
           150 MW Power Units
                   Power unit installation
No. of
additional
sootblowers
required
0
1
2
3
4
0.8 %S
Total
process
investment
1,568,800
1,608,800
1,648,800
1,688,800
1,728,800
- 5.0 stoichiometry
Sootblower cost
sensitivity, % of
total investment
0.0
2.5
4.9
7.1
9.3
3.0% S
Total
process
investment
1,874,200
1,914,200
1,954,200
1,994,200
2,034,200
- 2.0 stoichiometry
Sootblower cost
sensitivity, % of
total investment
0.0
2.1
4.1
6.0
7.9
5.0% S
Total
process
investment
2,369,500
2,409,500
2,449,500
2,489,500
2,529,500
- 2.0 stoichiometry
Sootblower cost
sensitivity, % of
total investment
0.0
1.7
3.3
4.8
6.3

-------
to
*4
0)
o
•o
05
CO
o
JS
4i
c
s

•H
00
O
EH
                    I
              Existing  units
    800
    600
    400
    200
                    10
         Figure
                                15          20           25           30

                               Grinding capacity, tons/hour

                         Effect of Limestone Grinding Capacity  and Fineness of Grind
                         on Total Grinding System Investment:   Dry Limestone Injection
                         Process

-------
              Existing units. • 15 yrs remaining life
              Regulated economics
              5000 hrs/yr operation
£   250

o
CD
as
to
-P
CO
O
O
   200
   150
I
05  100
                  10
       15          20           25

      Grinding capacity, tons/hour
30
        Figure
Effect of Limestone Grinding Capacity and Fineness of  Grind
on Annual Operating Cost for Grinding:  Dry Limestone
Injection Process

-------
           Existing units - 15 yrs remaining life

           Regulated economics

           5000  hrs/yr operation
0)

c
o
4J
«0
c
o  3
-u
to
o
o
*
•H



•H


to


•P
                                                                                                          a>
                                                                                                          oo
                 10
     Figure
        15          20          25           JO



      Grinding capacity, tons/hour



Effect of Limestone Grinding Capacity and Fineness  of Grind

on Unit Grinding Cost:  Dry Limestone Injection  Process

-------
                                         L-64

the process.  For consistency  in the evaluation,  a dust removal efficiency of 99% prior to
injection or an outlet grain emission of 0.03 gr/acf is assumed.
        From their study  of electrostatic precipitator  performance during the Shawnee Dry
Limestone Injection test  program,  Cottrelt  Environmental  Systems,  Inc.1   reported  five
separate alternatives which may  be considered  for  design  of additional dust  collection
facilities, including:
    1.  Size modification  of the presently installed dust collecting system.
    2.  Installation of a "hot" precipitator.
    3.  Gas  cooling ahead  of the  dust  collecting  system  (in  conjunction  with  size
        modification).
    4.  Gas  conditioning  ahead of the dust collecting  system (in conjunction with  size
        modification).
    5.  Electrical energization of the precipitator.
 Based  on  their study, CES  indicates  that  with gas  cooling ahead of the dust collecting
 system (alternative  3), the least additional  precipitator plate area might be required. Their
 results, however,  do  not include costs  for  gas cooling  facilities, nor do they represent
 carefully researched data needed for  design  modifications of  such a  system. Since design
 requirements for the other alternatives are also speculative at this time, size modifications of
 the presently installed  dust collecting system (alternative 1) is considered the most practical
 method for  meeting additional dust removal requirements for existing power plants.  The
 Shawnee  test  data  were used by  Cottrell  Environmental  Systems,   Inc.,  to  estimate
 incremental  precipitator  investment requirements  based on increasing the precipitator plate
 area  for a 150  MW  unit with any one of the following four combinations of dust collectors
 prior to limestone injection:
                                                           Overall fly ash
                                                         collection efficiency
                    Dust collector type                    prior to injection, %
             1. No collection devices                                0
             2. Mechanical collector                                65
             3. Electrostatic collector                               99
             4. Mechanical and electrostatic
                collectors in series                                 99
     1.  Brown,  R.  F. "Report and  Analysis  of Field  Tests at Shawnee  Station of TV A,
 Including a Techno-Economic Evaluation  of  Options for Maintaining the Stack Emission
 Rate with  Limestone Injection Equivalent  to  a  Baseline of No Limestone Injection." Final
 draft  prepared  by Cottrell Environmental  Systems,  Inc., for the Environmental Protection
 Agency,  Contract  No. CPA 22-69-139, Particulates  Collection Study, TVA Dry Limestone
 Tests. October 31, 1972.

-------
                                        L-65
       Assuming a final outlet  grain loading of 0.03 gr/acf after injection for each sulfur
content and stoichiometry, the  estimated fixed investment requirements are tabulated in
table 17 and are shown graphically in figures 33 through 36 for the various combinations of
existing collection  facilities. Depending  on  the dust removal capability existing prior to
injection, incremental dust collection investment could cover a wide range, as much as 2.4
times that  projected in the case study (mechanical and electrostatic in series). Assuming no
collection  devices existing  prior  to   injection,  total   process  investment  could   be
approximately 28% higher than estimated in the parametric evaluation.
       4.  Disposal  costs—In the 52-case parametric  study, additional pond facilities were
not provided since the availability and  cost of additional  space depends upon  the actual
plant location.  In many cases, some additional disposal area will  be necessary, and these
additional  investment  costs  should be added to  the  dry limestone  injection  process
investment.
       Figure 37 shows the relationship between the incremental annual disposal burden
and  the projected pond disposal costs incorporated in the parametric study. As this figure
indicates, the projected disposal expense decreases with increasing solids disposal burden to
a cost  less  than  $0.50/ton  of solids. For the three base cases, these costs range from 4.6 to
5.1% of the total process  operating cost. As an indication  of the effect of higher disposal
costs, a charge of $2.00/ton of solids would result  in overall  disposal costs ranging from 7 to
15% of the projected annual operating costs for these cases.
       5. Raw material costs—Since limestone cost is one of the major operating expenses,
the sensitivity of price on annual operating cost was determined. Figure 38 shows the effect
of injection stoichiometry and delivered limestone price on the annual and unit operating
costs for a 150 MW, 3.0% S coal-fired installation.  At a stoichiometry of 4.0, a $2.00 change
in the price of limestone results in a 20-30% change in annual costs.
       The effect  of  power  unit  size and  delivered limestone  price on  annual and unit
operating costs for the process are shown in figures 39 and 40.

-------
                                                        Table 1 7

                                     Incremental Electrostatic Precipitator Invesetment3
                                     Required to Maintain Outlet Particulate Loading of
                                            0.03 gr/acf on 1 50 MW Power Units
                                             Utilizing Dry Limestone Injection
                   Injection stoichiometry,
 Sulfur in        moles CaO injected per mole
 coal,%         	sulfur in coal	

    0.8                      3.0
    0.8                      4.0
    0.8                      5.0
    0.8                      6.0
    0.8                      7.0
                     None

                      763
                      778
                      794
                      808
                      824
               Incremental electrostatic precipitator costs,
           thousands of dollars, for power units equipped with
              the following existing dust collection facilities3	
                                                      99% Eff.
                                                   Mechancial  and
                                                 electrostatic collectors
                                                       in series
 65% Eff.
Mechanical
 collector

    582
    601
    619
    635
    648
  99% Eff.
Electrostatic
  collector

    408
    423
    439
    453
    469
                                                         321
                                                         339
                                                         358
                                                         373
                                                         386
                                                                                        cr>
                                                                                        CTi
    3.0
    3.0
    3.0
    3.0

    5.0
    5.0
    5.0
    5.0
1.0
2.0
3.0
4.0

1.0
2.0
3.0
4.0
 790
 843
 886
 924

 831
 905
 967
1021
    606
    666
    716
    753

    653
    734
    797
    852
    435
    488
    531
    569

    476
    550
    612
    666
345
405
454
491

392
473
535
591
a.  Including indirects
b.  Assumes coal with 16% ash

-------
  1.2
to

§
•1-1
   .8
CO
a)
>

•So. 6
"8
  0.4
                                         T
T
           150 MW units

           Fly ash loading:^. 23 gr/acf

           Outlet loading after dust collection  - O.05  gr/acf
                                                                                                 CTl
     02468

      Stoichiometry, moles CaO injected per mole S in coal



      Figure  33  .  Investment Requirements for Adding Incremental

                     Electrostatic Precipitator to Power Plant without

                     Collectors:  Dry Limestone Injection Process

-------
  1.0
•§ 0.8


o

en

O
•H
iH
i-l

ll 0.6
•S 0.4

-------
  0.8
en
M
rt
*gO,6
w
o
 .0.4
CO
!
•gO. 2
x
                             T
                    T
          150 MW units
          Ftyash loading - 3.23 gr/acf
          Outlet loading after duet collection - O.OJ gr/acf
                                                                             CD
                                                                             IO
     02468
          Stoichiometry, moles CaO injected per mole S in coal
      Figure   55  .
Investment Requirements for Adding Incremental
Electrostatic Precipitator to Power Plant Having
an Existing 99$ Effective Precipitator:  Dry
Limestone Injection Process

-------
 10
 h
A
r-i
 o
•o
w
8
c
0)
*i
10
I
T3
0>
0.8
                    I            I            I            I

               150 MH units
               fly ash loadings 3.23 gr/acf
               Outlet loading after dust collection - 0.03 gr/acf
0.6
   0.2
                                                                                                    -j
                                                                                                    o
                    2           U           6            8
            Stoichiometry,  moles CaO injected per mole S in coal
         Figure
                    Investment Requirements for Adding Incremental
                    Electrostatic Precipitator to Power  Plant Having
                    an Existing 99$ Effective Combination  of Mechanical
                    and Electrostatic Collectors:  Dry Limestone  Injection
                    Process

-------
     600
                     T
                            T
T
T
r-l
o
•O
CO

•s
ol
m
3
CO
o
o
OS
CO

a
•J
•rt
•O

(O
•O
O
TO
§
c
                    Annual  costs  for solids disposal to pond
                    excluding cost of pond

                    Variable  solids disposal costs
500
400
300
200
     100
         0
          Figure
                50          100         1-50         200         250


                 Incremental solids disposal burden, M tons/year


               _.   Effect of Incremental Solids Disposal Burden on Annual
                    Disposal Cost for Dry Limestone Injection Solids
                                    300

-------
            Existing  150  MW units

            5000 hrs  annual operation

            Regulated economics
   2.0
 o
T>
W
e
o
CO
o
o

oo
Pi
» i.o
0)
CU
O
fl




.§0.5
                                                                                  2.67
                                                                
-------
 Existing units
 2.0 injection stoichiometry
 5000 hrs annual operation
 Regulated economics
                                                                                                       co
         50
Figure  39  »
      100
      150        200
Power unit size,  MW
250
300
350
Effect of Power Unit Size and Delivered Limestone Cost  on Annual
Operating Cost for Dry Limestone Injection Process:   3.0$ S  Coal

-------
•o

8
 a
 o
 -p

-66-
-p
CO
O
D

00
a
•H
-p


2
    5-0
    3-0
B  2.0
    1.0
           Existing units

           2.0 injection stoichiometry

           5000 hrs annual operation

           Regulated economics
         0
         Figure
                               100
150         200         250

       Power unit size, MW
300
                                                —  1.97
                                                                                            _  1.58
                                                                                                      CO
                                                          (0
                                                          O
                                                          o


                                                    1.18  Jf

                                                          -p

                                                          g
                                                          
-------
                                         L-75
       6.  Annual  on-stream time—The  effect of variations in process  on-stream time on
annual operating costs are shown in figure 41 for three plant sizes at various sulfur levels of
fuel. As illustrated, the cost effect is much more pronounced for  large  plants using high
sulfur coal. Figure 42 shows the effect of on-stream time on unit  operating costs per ton of
sulfur removed. These unit operating costs decrease with increased on-stream time and  are
much higher for the low MW and low sulfur applications. This result is partially the effect of
greater economy of scale for operating the larger installations; however, the largest factor is
the reduced SO2 absorption efficiency attained for low sulfur coal.
       7- Operation at half load—In  the dry limestone injection test program, higher sulfur
dioxide removal efficiencies were observed during operation of the power unit at half load.
To determine the  effect of these higher efficiencies on unit operating costs, projections are
made for  a 150 MW unit operating at full and half load assuming various  annual on-stream
hours. The resulting  unit  operating costs  are  shown  in  figures  43  and 44.  Although
approximately 50% lower operating costs per ton of sulfur removed are projected at reduced
load, the  costs per ton of coal burned are about the same. The operational  costs at half load
do not include a charge  for power generating capacity  intentionally idled  to increase
absorption which, if  assessed,  would  make  half-load operation more costly  per unit of
electricity generated.
       8. Remaining life of  plant—figures 45 through 47 show the  effect of remaining  life
of the power plant  on lifetime total and unit operating costs for various megawatt sizes.
Similar relationships indicating the effect of remaining life  of power plant on lifetime total
and unit operating costs for various sulfur levels are given in  figures 48 through 50.
       Although total operating costs increase as a result of greater operation, these results
show  that  unit   operating  costs  for  power  plants  with  10  years  remaining life  are
approximately half of similar unit  costs for plants with 5 years remaining  life. This result is
attributed primarily to the increased annual  capital charge rate resulting from operation for
fewer years plus the difference in tons of coal burned or sulfur  removed.
       9.  Labor  cost  escalation—To  determine the  effect  of  escalating  labor  rates on
lifetime  operating costs for  dry  limestone injection, projections  assuming annual  labor
escalation rates varying from 0 to  10.0%/year were made. The results, presented in table 18
and figure 51, show that lifetime operating costs for dry limestone injection are not greatly
increased as  a result  of  labor  cost  escalation.  Lifetime unit operating  costs range from
$3.53/ton of coal burned  assuming  no escalation  to  $3.95/ton at an escalation rate of
10%/year for the  remaining  15-year life of the plant. At the higher escalation rate, lifetime
costs are approximately 11.8% higher than projected costs excluding escalation.

-------
                                            Table 18

                Effect of Annual Labor Escalation Rates on Lifetime Operating Cost for
                    Dry Limestone Injection Process Under Regulated Economics -
                      1 50 MW Unit, 3.0% S in Coal, 2.0 Injection Stoichiometry a
Annual
labor
escalation
rate
%
0
2.5
5.0
7.5
10.0
Total increase
in lifetime Cumulative present worth of net
operating cost increase in cost of power
Lifetime operating cost resulting from discounted at 10%/yr

$
10,438,
10,669,
10,944,
11,275,
11,670,


200
100
700
500
700
$/ton
coal
3.53
3.61
3.71
3.82
3.95
mills/
kWh
2.03
2.06
2.10
2.15
2.20
$/ton S
removed
640
654
671
691
715
escalation,
%
_
2.2
4.9
8.0
11.8

$
6,002
6,097
6,206
6,335
6,484


,800
,300
,900
,300
,800
$/ton
coal
1.39
1.42
1.46
1.50
1.56
mills/
kWh
0.80
0.81
0.83
0.84
0.86
$/ton S
removed
368
374
380
388
397
                                                                                                                              -J
                                                                                                                              en
a.  Existing units - 15 yrs. remaining life.  Assumed operating profile:
5 yr at 5000 hr/yr
5 yr at 3500 hr/yr
5 yr at 1500 hr/yr

-------
a
h
A
r-i
o
•o
w

o
•u
w
o
u
-p
to
fn
V
P<
O
SJ


c
              Existing units - 15 yrs remaining life

              Regulated economics
2.0
     1.5 —
     1.0
0.5
                       50 MW
                       , 0.8* S, 3.0 stolen^
         0
               1000
2000        3000        UOOO


     On-stream time, hrs
5000
           Figure  41  .  Effect of Annual On-Stream Time at Pull Load on Annual

                          Operating Cost for Various Size Dry Limestone Injection

                          Process Installations

-------
                                    Existing  units  -  15 yrs  remaining  life

                                    Regulated economics
8000
•o


I
v
w   6000
c
                           50 MW units,  0.8# S,  J.O  injection stoichiometry
m
O
o

bO
C
1*000
                                                                                                            00
&
o

4J
•H

B
2000
       0
                                               0* S, 2.0 stoich
                    1000
2000        JOCK)         UOOO


     On-stream time, hrs
                                                                 5000
          Figure
                     Effect of Annual On-Stream Time  at Full Load on Unit

                     Operating Cost Per Ton  of Sulfur Removed for Various

                     Size Dry Limestone Injection Process  Installations

-------
                                                                       T
     2000
§
                                       Existing unit - 15 yrs remaining life
                                       ?.O=t S coal
                                       2.0 injection stoichiometry
                                       Regulated economics
 CO

 e
 Q
 «^

^
to
O
o
2
4)
&
     1500
     1000
      500
                                                                      1
                   150,000     300,000     450,000      600,000

                              Annual power generation, MW hours
                                                                    750,000
             Figure
                           Effect of Annual Power Generation at Full and Half Load
                           on Dry Limestone Process Unit Operating Cost Per Ton of
                           Sulfur Removed:  150 MW Unit

-------
•o
s
 oj

 8

 C
 O
 -P

•w-
-P
CO
O
o


bo
c
o

4J
     20
     15
     10
       0
                                           T
                                                        T
                        T
                                    Existing unit - 15 yrs remaining life

                                    3«0# S coal

                                    2.0 injection stoichiometry

                                    Regulated economics
                                              full load
                   I
                               1
I
I
I
                                                                                                        00

                                                                                                        O
                 150,000     300,000     1^50,000     6oo>ooo


                            Annual power generation,  MW hours
                      750,000
         Figure
                        Effect of Annual  Power Generation at Full and Half Load

                        on Dry Limestone  Process  Unit  Operating Cost Per Ton of

                        Coal Burned:   150 MW Unit

-------
CO
(•4
  20  —
o
•o
CO
c
o
   15  —
-p
CO
o
u
g»10
g
P4
o
0)
5
-p
o>
    Actual dollars
— Present worth if discounted  at
Existing units
Regulated economics
2.0 injection stoichiometry
                                                    to  initial yr
      0
                                                                                                                   00
        Figure
                             150          200

                           Power unit size,  MW

           Effect of Power Unit Size and Years Remaining Life on Lifetime Increase
           in Cost of Power Using Dry Limestone Injection:  3«°# S Coal

-------
I

§
,0
 0)
 o
 o

 c
 o
09

O

V
•rl
•P
0)
h



I
§

V

a
4J
0)
4-1
•H
     20
10
               I            I            I            I

         	 Actual dollars
         	 Present worth if discounted  at  10# to  initial yr

         Existing units

         Regulated economics
         2.0 injection stoichiometry
                                                                                                              oo
                                                                                                              ho
         Figure
                                     Power unit size, MW



                   Effect  of Power Unit Size and Years Remaining Life on Dry Limestone

                   Process Operating Cost Per Ton of Coal Burned Over Life of Plant:

                   3.0% S  Coal

-------
I
    4000
        	1	1	1

	 Actual dollars
	 Present worth if discounted at 10% to initial yr
Existing units
Regulated economics
2.0 injection stoichiometry
3
w

C
o
-p
-p
TO

8
I
§
V
     3000
     2000
     1000
        0
                                                                                                   00
                                                                                                   CO
                                 100
                               150
200
250
300
550
          Figure
                             Power unit  size, MW


          Effect  of Power  Unit Size and Years Remaining Life on Dry Limestone
          Process Operating Cost Per Ton of Sulfur Removed Over Life of Plant:
          3.0* S  Coal

-------
CO
    20
O
•O
V.
O
01

O
a
 •*
43
to
8
g
Q>
    10
     0
	 Actual dollars
	 Present worth if discounted at 10$ to  initial yr
Existing units
Regulated economics
J.O injection stoichiometry
     5  —
                                                                                                        00
                                                                                                        -is.
        Figure
                      Sulfur  in coal,  %

          Effect of Sulfur Content  of  Coal and Years Remaining Life
          on Lifetime Increase  in Cost of Power Using Dry
          Limestone Injection:   150 MW Units

-------
 -g
 a
    20
-- Actual dollars
— Present worth  if  discounted at
Existing units
Regulated economics
3-0 injection stoichiometry
                             to  initial yr
 a
 o
-W-
4J
CO
O
o
•H
-P
0)
Vi
 o
 +>
 •H
 a
43
0)

-------
•o
s
     8000
                	 Actual dollars
                	 Present worth if discounted at 10^ to initial yr
                Existing units
                Regulated economics
                3-0 injection stoichiometry
C
O
-p
ID
O
U
0$

-------


•8
c
Vl
I 5.0

B
£ 2.0
V
CM
•H
<
1.0
1 1 II 1
<• "" Actual dollars
.. >. M. present worth if discounted at 10$ to initial yr

__ Existing unit - 15 yrs remaining life
3.0# S coal
2.0 injection stoichiometry
Regulated economics


_ _r>^. _
^ ^^
^ •—pg*— """^ *^J
ri ^^"""^
"

r ^ 	






— . —


f\ _ ._ „ _/~\«« — « — •— ""Q"~ "~ ~" ^™ "^ ^^^^
rM. M> «M* «•» L/*~ ™" VJ ^
1 I 1 I 1




1.9T JH
^
ra
r-l
r-l
e
1.58 i
o
V
bO
c
0)
1.18 o

^
§
0)
•H
•••^
0.79 ?
^

0.1Q
0          2.0
  Figure   51
      k.O
6.0
8.0
                                                            10.0
                     Annual labor escalation rate,
Effect of Escalating Labor Rate on Dry Limestone Process
Operating Cost Per Ton of Coal Burned and Per Kilowatt-hour
of Electricity Produced Over Life of Plant:   150 MW Unit
                                                                                                        00

-------
                                     L-88
References and Abstracts
 1. Atchison, J. L. (The Babcock and Wilcox Company). Private communication to Robert
   L. Torstrick, May 19, 197-2, giving the contract price breakdown of the dry limestone
   injection process equipment supplied to TVA.
 2. Brown, C. B.,  Jr.  (Koppers Company,  Inc.).  Private  communication  to William H.
   Kennedy. May  23,  1972, giving up-to-date price data on rotary dryers and grinding mills
   for processing limestone prior to injection into a boiler.
 3. Brown, R. F. (Cottrell Environmental Systems, Inc.). Private communications to Robert
   L.  Torstrick, June 30 and  July 6, 1972, giving  incremental electrostatic precipitator
   investment and   electricity  requirements  applicable  for installing  and  operating
   precipitators on power units utilizing the dry limestone injection process.
 4. "Economic Indicators." Chemical Engineering 79(21), September 18, 1972.
       C. E.  Plant Cost Index data  was used for obtaining a projected  1972 annual index.
   This  projected index was  compared with  the  annual index for  1969, and  used in
   updating the Shawnee 1969 investment costs.
 5.  Federal Power  Commission.  Hydroelectric Power Evaluation.  FPCP-35 (1968)  and
   Supplement No. 1, FPC P-38  (1969). Superintendent of Documents, U.S. Government
   Printing Office, Washington, D.C. 20402.
       This publication is a guide for the evaluation  of the hydroelectric power aspects of
   water resource developments.  Included  is  information  concerning  investment  and
   operating costs of hydroelectric and thermal-electric power  plants  and transmission
   facilities,  methods  for economic analysis  of projects, and  methods for presenting the
   annual  costs  associated  with  power generation  and transmission  under regulated
   economics.
 6. Guthrie, K. M. "Capital Cost Estimating." Chemical Engineering 76(6), March 24, 1969.
       Data and techniques for preliminary capital cost estimating are presented along with
   a compilation of  costs for a large variety of plant equipment. A "module" technique for
   making fast, accurate, and consistent estimates is introduced. Especially useful for  this
   study are the equipment scale factors given in the data.
 7. "Industry Statistics." Oil and Gas Journal 70(37),  September 11, 1972.
       Published  data giving  refined-products prices  was used to obtain  the price  for
   distillate kerosine  (No. 2 fuel  oil) for use in projecting 1972 operating costs for the dry
   limestone injection process.
 8. The M. W. Kellogg Company.   Availability of Limestones and Dolomites.  Task No. 1
    Final Report, MWKLG-RED-72-1265, Submitted  to  Environmental  Protection Agency,
   Contract No. CPA 706-8, February 1, 1972.
       Several processes which  remove sulfur oxides  from power plant stack gas are based
   on the use of limestone or dolomite as the absorbent. The objective  of this study was to
   determine the  availability and costs of limestone and similar materials throughout the
   contiguous United States to  supplement experimental work.
       Materials covered in this study include limestone, dolomite, chalk, marble, marl, and
   shell. Information is  presented on location  of deposits, production rates, f.o.b. quarry

-------
                                       L-89

   costs, transportation  methods  and  costs, expected  cost increases, uses,  chemical
   composition, and physical properties.
 9. Perry. John H., Chilton,  Cecil  H.p and Kirkpatrick, Sidney D.  Chemical Engineers'
   Handbook.  Fourth Edition, McGraw-Hill Book Co., New York, 1963.
       "Six-tenths factor" method for scaling  equipment costs as a function of capacity is
   presented along with a set of typical exponents for use with various types of equipment.
10. Peters, Max S. and Timmerhaus, Klaus D.  Plant Design and Economics for Chemical
   Engineers.  Second Edition, McGraw-Hill Book Co., New York, 1968.
       Economic  and design principles, as applied  in chemical engineering processes and
   operations  are discussed. The first  part of the text presents an overall analysis of the
   major factors involved in process design, with  particular emphasis on economics in the
   process industries and in design work. The various costs involved in industrial processes,
   capital investments and  investment returns, cost estimation, cost accounting, optimum
   economic design methods, and other subjects dealing with economics are covered both
   qualitatively and  quantitatively.  The  remainder of the book deals  with  methods and
   important factors in the design of plants and equipment.  Generalized subjects, such as
   waste disposal, structural  design, and equipment fabrication,  are included along  with
   design methods for different types of process equipment.  Basic  cost data  and cost
   correlations are also presented for use in making cost estimates.
11. Purcell, Robert W.  (The Taulman Company). Private communication to W.  H. Kennedy,
   June 28, 1972, describing design  of sluice systems for disposal of waste solids.
12. Tennessee  Valley  Authority.    Sulfur Oxide Removal from Power Plant Stack  Gas:
   Sorption by Limestone  or Lime—Dry Procesi,  -   (1968). Report No.  PB  178-972,
   Clearinghouse   for  Scientific  and  Technical  Information, 5285  Port  Royal Road,
   Springfield, Virginia 22151.
       Injection of dry limestone or  lime  into the  boiler is considered the simplest and least
   costly process for  removing SO2 from power  plant  stack gases.  Product is calcium
   sulfate  which  is  discarded. The process  can  be operated  intermittently. A  detailed
   economic evaluation is presented.
13. Tennessee  Valley Authority. "Wage Schedules." Office Service Branch, Administrative
   Releases (Memorandum  No. 1321), August  1, 1972.
       TVA wage schedules effective during 1972 are given for chemical and power plant
   operators and  laborers.

-------
                                          L-91


_TableA-l Summary of Estimated  Fixed Investment-Dry Limestone Injection Process
                 (50-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       3.0 Moles CaO Injected per Mole S in  Fuel;
                           1.55 Tons Dry Limestone per Hour)
                                                                           I nvestment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                                6,300
Limestone storage and feed system including hoppers, unloaders,  and
 conveyors                                                                     14,400
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 38,400
Limestone grinding system'3 including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                           58,800
Limestone injection system including transport pump,  air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping  and
 injectors                                                                       57,600
Equipment foundations for all areas                                              16,300
Instrumentation for all areas including panel and shed                             27,100
Piping for all areas                                                               35,100
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                                33,300
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                    42,000
Incremental electrostatic precipitator system0                                    89,000
Incremental solids disposal system0' for collecting and sluicing
  limestone solids to pond                                                       100,000
   Subtotal direct investment                                                   518,300

Engineering design  and overheads                                                46,600
Construction expense                                                            72,600
Contractors fees                                                                 46,600
Contingency                                                                    67,400

   Total fixed capital investment	751,500
Basis:
      aMidwest location—1972 costs.
      bO" x iy2" limestone ground to 80% minus 400 mesh.
      Incremental electrostatic precipitator added to maintain dust emission rate
       prior to injection of limestone. Dust collection efficiency prior to
       injection of limestone is assumed to be 99% using a combination of
       mechanical and electrostatic devices.
       Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
       1 mile from power unit. Cost of solids disposal pond not included.

-------
                                          L-92
  Table A-2 Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                 (50-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       4.0 Moles CaO Injected per Mole S in  Fuel;
                          2.07 Tons Dry Limestone per Hour)
                                                                           I nvestment, $
General yard work including  landscaping, lighting, grading, raw water
 piping and drains                                                                7,200
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     18,200
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 44,300
Limestone grinding system13 including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                            71,200
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                       64,700
Equipment foundations for all areas                                              19,400
Instrumentation for all areas  including panel and shed                             29,200
Piping for all areas                                                               40,600
Electrical  power supply including 4160 and 480 volt  boards and conduit,
 trays, groundings, and telephone                                                38,000
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                     48,500
Incremental electrostatic precipitator system0                                     94,200
Incremental solids disposal system0' for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                  575,500

Engineering design and overheads                                                 51,800
Construction expense                                                            80,600
Contractors fees                                                                 51,800
Contingency                                                                    74,800

   Total fixed capital investment	834,500
Basis:
     fMidwest location-1972 costs.
     "0" x IVa" limestone ground to 80% minus 400 mesh.
     "incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed t& be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                          L-93
  Table A-3 Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                 (50-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       5.0 Moles CaO Injected per Mole S in  Fuel;
                          2.59 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                                8,100
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     21,800
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                49,700
Limestone grinding system'3 including feed bin, ball  mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          82,000
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone  distributor, piping and
  injectors                                                                      70,800
Equipment foundations for all areas                                             22,200
Instrumentation for all areas including panel and shed                            30,800
Piping for all areas                                                              45,500
Electrical  power supply including 4160 and 480 volt boards and conduit,
  trays, groundings, and telephone                                               41,900
Revisions and additions to powerhouse and boiler including  injection
  ports, metal work, insulation and steam lines                                    54,300
Incremental electrostatic precipitator system0                                    99,300
Incremental solids disposal systerrrfor collecting and sluicing
  limestone solids to pond                                                       100,000
   Subtotal direct investment                                                   626,400

Engineering design and overheads                                                56,400
Construction expense                                                           87,700
Contractors fees                                                                56,400
Contingency                                                                   81,400

   Total fixed capital investment	908,300
Basis:
     ^Midwest location-1972 costs.
     bO" x IV-i" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
       prior to injection of limestone. Dust collection efficiency prior to
       injection of limestone is assumed to be 99% using a combination of
       mechanical and electrostatic devices.
       Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
       1 mile from power unit. Cost of solids disposal pond not included.

-------
                                          L-94


  Table A-^ Summary of Estimated  Fixed Investment3—Dry Limestone Injection Process	
                 (50-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       6.0 Moles CaO Injected per Mole S in  Fuel;
                          3.11 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including  landscaping, lighting, grading, raw water
 piping and drains                                                                8,900
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     25,100
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 54,400
Limestone grinding system'3 including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                            92,500
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                       76,200
Equipment foundations for all  areas                                              24,700
Instrumentation for all areas  including panel and shed                             32,200
Piping for all areas                                                               49,800
Electrical  power supply including 4160 and 480 volt  boards and conduit,
 trays, groundings, and telephone                                                45,500
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                     59,500
Incremental electrostatic precipitator system0                                   103,600
Incremental solids disposal system0' for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                  672,400

Engineering design and overheads                                                 60,500
Construction expense                                                            94,100
Contractors fees                                                                 60,500
Contingency                                                                    87,400

   Total fixed capital investment	974,900
Basis:
     aMidwest location-1972 costs.
     °0" x IVi" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
       1 mile from power unit. Cost of solids disposal pond not included.

-------
                                          L-95

_TableA-5 Summary of Estimated Fixed  Investmenta-Dry Limestone Injection Process
                 (50-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       7.0 Moles CaO Injected per Mole S in Fuel;
                          3.63 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw  water
 piping and drains                                                                9,600
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    28,400
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                58,800
Limestone grinding system0 including feed bin, ball  mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          102,100
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone  distributor, piping and
 injectors                                                                      81,000
Equipment foundations for all areas                                             27,200
Instrumentation for all areas including panel and shed                            33,500
Piping for all areas                                                              53,800
Electrical  power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                               48,900
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                    64,300
Incremental electrostatic precipitator system0                                    107,200
Incremental solids disposal system"for collecting and sluicing
  limestone solids to pond                                                       100,000
   Subtotal direct investment                                                   714,800

Engineering design  and overheads                                                64,300
Construction expense                                                           100,000
Contractors fees                                                                64,300
Contingency                                                                   92,900

   Total fixed capital  investment	___^_	1,036,300
Basis:
     fMidwest location-1972 costs.
     "0" x I'A" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
       prior to injection of limestone. Dust collection efficiency prior to
       injection of limestone is assumed to be 99% using a combination of
       mechanical and electrostatic devices.
       Solids disposed as 15% slurry with no recycle of pond water. Disposal pond  located
       1 mile from power unit. Cost of solids disposal pond not included.

-------
                                          L-96
  Table A-6  Summary of Estimated Fixed In vestment3-Dry Limestone Injection Process
                (150-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                          4.64 Tons Dry  Limestone per Hour)
                                                                           Investment, $
General yard work including  landscaping, lighting, grading, raw water
 piping and drains                                                               10,800
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     34,600
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 66,300
Limestone grinding systemb including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                           119,800
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone  distributor, piping and
 injectors                                                                       89,200
Equipment foundations for all areas                                              31,400
Instrumentation for all areas  including panel and shed                             35,600
Piping for all areas                                                               60,700
Electrical power supply including 4160 and 480 volt  boards and conduit,
 trays, groundings, and telephone                                                54,500
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                     72,600
Incremental electrostatic precipitator system0                                   226,000
Incremental solids disposal system^ for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                  901,500

Engineering design and overheads                                                 72,100
Construction expense                                                          117,200
Contractors fees                                                                 72,100
Contingency                                                                  ] 17,200

   Total fixed capital investment                                              1,280,100
Basis:
     ^Midwest location-1972 costs.
     bO" x W" limestone pound to 80% minus 400 mesh.
     ""Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                          L-97
  Table A-7 Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (150-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       4.0 Moles CaO Injected per Mole S in Fuel;
                          6.20 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw  water
 piping and drains                                                               12,500
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     43,600
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 76,600
Limestone grinding system'3 including feed bin, ball  mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                           144,500
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                      100,200
Equipment foundations for  all areas                                             37,400
Instrumentation for all areas including panel and shed                            38,300
Piping for all areas                                                              70,200
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and  telephone                                               62,000
Revisions and additions to powerhouse and boiler including  injection
  ports, metal work, insulation and steam lines                                   83,800
Incremental electrostatic precipitator system0                                   239,000
Incremental solids disposal system0' for collecting and sluicing
  limestone solids to pond                                                       100,000
   Subtotal direct investment                                                  1,008,100

Engineering design and overheads                                                80,600
Construction expense                                                          131,100
Contractors fees                                                                80,600
Contingency                                                                    131,100

   Total fixed capital  investment	1,431,500
Basis:
     aMidwest location-1972 costs.
     °0" x I1// limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone.  Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     Solids disposed as 15% slurry with no recycle of pond water. Disposal pond  located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                          L-98
  Table A-8  Summary of Estimated Fixed Investment8-Dry Limestone Injection Process
                (150-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       5.0 Moles CaO Injected per Mole S in  Fuel;
                          7.76 Tons Dry  Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               14,000
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                      52,100
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 85,700
Limestone grinding system13  including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                           167,100
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                      109,600
Equipment foundations for all areas                                              42,800
Instrumentation for all areas including panel and shed                             40,500
Piping for all areas                                                               78,500
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                                68,700
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                     93,800
Incremental electrostatic precipitator system0                                   252,000
Incremental solids disposal system^  for collecting and sluicing
 limestone solids to pond                                                      100,000
   Su btota I d i rect i nvestmen t                                                 1,104,800

Engineering design and overheads                                                 88,400
Construction expense                                                          143,600
Contractors fees                                                                 88,400
Contingency                                                                  143,600

_jrota|. fixed capital investment  	1,568,800
Basis:
     fMidwesHocation-1972 costs.
     bO" x IVi" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                          L-99
_Tabje A-9 Summary of Estimated Fixed Investment8-Dry Limestone Injection Process
                (150-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       6.0 Moles CaO Injected per Mole S in Fuel;
                          9.33 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               15,300
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     60,400
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 94,000
Limestone grinding system'3  including feed bin, ball mill  and classifier,
 storage silo, conveyors and chutes, and dust collectors                          188,800
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
  injectors                                                                      118,000
Equipment foundations for all areas                                              47,800
Instrumentation for all areas including panel and shed                             42,500
Piping for all areas                                                               86,000
Electrical power supply including 4160 and 480 volt boards and conduit,
  trays, groundings, and telephone                                                74,600
 Revisions and additions to powerhouse and boiler including injection
  ports, metal work, insulation and steam lines                                   102,800
 Incremental electrostatic precipitator system0                                   263,000
 Incremental solids disposal system^ for collecting and sluicing
  limestone solids to pond                                                       100,000
   Subtotal direct investment                                                 1,193,200

 Engineering design and overheads                                                95,500
Construction expense                                                          155,100
Contractors fees                                                                 95,500
Contingency                                                                   155,100

   Total fixed capital investment	      1,694,400
Basis:
      ^Midwest location-1972 costs.
      °0" x VA" limestone ground to 80% minus 400 mesh.
      Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-100
  Table A-lOSummary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (150-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       7.0 Moles CaO Injected per Mole S in  Fuel;
                          10.90 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               16,600
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                      68,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               101,600
Limestone grinding system*3  including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          208,600
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     125,500
Equipment foundations for all areas                                              52,400
Instrumentation for all areas including panel and shed                              44,100
Piping for all areas                                                               93,000
Electrical  power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                                80,000
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                   111,100
Incremental electrostatic precipitator system0                                   272,000
Incremental solids disposal system0' for collecting and sluicing
 limestone solids to pond                                                      100,000
  Subtotal direct investment                                                1,273,200

Engineering design and overheads                                               101,900
Construction expense                                                          165,500
Contractors fees                                                               101,900
Contingency                                                                  165,500

  Total fixed capital investment	1,808,000
Basis:
     aMidwest location-1972 costs.
     bO" x iy-2." limestone ground to 80% minus 400 mesh.
     clnciemental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                          L-101
_Table A-llSummary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (250-MW Existing Coal-Fired Power Unit; 0.8% S in  Fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                          7.73 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               14,000
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                      52,000
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 85,600
Limestone grinding system'3 including feed bin, ball  mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                           167,100
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                      109,500
Equipment foundations for all areas                                              42,700
Instrumentation for all areas including panel and shed                             40,500
Piping for all areas                                                               78,300
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                                68,500
Revisions and additions to powerhouse and boiler including  injection
 ports, metal work, insulation and steam lines                                    93,600
Incremental electrostatic precipitator system0                                   350,300
Incremental solids disposal system^for collecting and sluicing
 limestone solids to pond                                                       100,000
   Subtotal direct investment                                                  1,202,100

Engineering design  and overheads                                                 96,200
Construction expense                                                           144,300
Contractors fees                                                                 96,200
Contingency                                                                   156,300

   Total fixed capital investment	1,695,100

     ^Midwest location-1972 costs.
     bO" x 1V4" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
       prior to injection of limestone.  Dust collection efficiency prior to
       injection of limestone is assumed to be 99% using a combination of
       mechanical and electrostatic devices.
       Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
       1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-102
  Table A-12Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (250-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       4.0 Moles CaO Injected per Mole S in  Fuel;
                          10.33 Tons Dry Limestone per Hour)
                                                                           lnvestment,$
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               16,100
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     65,600
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 99,000
Limestone grinding system13 including  feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          179,500
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     123,000
Equipment foundations for all areas                                              50,800
Instrumentation for all areas including panel and shed                             43,500
Piping for al I areas                                                               90,600
Electrical power supply including 4160 and 480 volt  boards and conduit,
 trays, groundings, and telephone                                                78,100
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                   108,200
Incremental electrostatic precipitator system0                                   370,500
Incremental solids disposal system0' for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                 1,324,900

Engineering design and overheads                                               106,000
Construction expense                                                          159,000
Contractors fees                                                               106,000
Contingency                                                                  172,200

   Total fixed capital investment	1,868,100
Basis:
     ^Midwest location-1972 costs.
     bO" x IVi" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-103


__TableA-13Summary of Estimated Fixed Investment9- Dry Limestone Injection Process
                (250-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       5.0 Moles CaO Injected per Mole S in  Fuel;
                          12.93 Tons Dry Limestone per Hour)
                                                                           I nvestment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               18,100
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                      78,600
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                110,800
Limestone grinding system0 including  feed bin, ball  mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                           233,400
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone  distributor, piping and
 injectors                                                                      134,600
Equipment foundations for all areas                                              58,200
Instrumentation for all areas including panel and shed                             46,100
Piping for all areas                                                              101,400
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                                86,500
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                    121,200
Incremental electrostatic precipitator system0                                    390,600
Incremental solids disposal system^ for collecting and sluicing
 limestone solids to pond                                                       100,000
   Subtotal direct investment                                                 1,479,500

Engineering design  and overheads                                               118,400
Construction expense                                                           177,500
Contractors fees                                                                118,400
Contingency                                                                   192,300

   Total fixed capital investment            	2,086,100
Basis:
     ^Midwest location-1972 costs.
     bO" x IVz" limestone ground to 80% minus  400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
       prior to injection of limestone. Dust collection efficiency prior to
       injection of limestone is assumed to be 99% using a combination of
       mechanical and electrostatic devices.
     dSolids disposed as 15% slurry with no recycle of pond water. Disposal pond located
       1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-104
  TableA-1^ Summary of Estimated Fixed Investment3—Dry Limestone Injection Process
                (250-MW Existing Coal-Fired Power Unit; 0.8% S in  Fuel;
                       6.0 Moles CaO Injected per Mole S in Fuel;
                          15.55 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               19,800
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     90,900
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               121,400
Limestone grinding systemb including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          262,800
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     144,700
Equipment foundations for all areas                                              64,900
Instrumentation for all areas including panel and shed                              48,200
Piping for all areas                                                             111,100
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                                93,900
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                   132,800
Incremental electrostatic precipitator system0                                   407,700
Incremental solids disposal system0' for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                1,598,200

Engineering design and overheads                                               127,900
Construction expense                                                          191,800
Contractors fees                                                               127,900
Contingency                                                                  207,800
  Total fixed capital investment	                                  2,253,600
Basis:
     aMidwest location-1972 costs.
     °0" x 1V4" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission late
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
     .mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-105
JTableA-15 Summary of Estimated Fixed lnvestmenta-Dry Limestone Injection Process
                (250-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       7.0 Moles CaO Injected per Mole S in Fuel;
                          18.17 Tons Dry  Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              21,400
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    103,000
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               131,100
Limestone grinding systemb including  feed bin, ball  mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          290,900
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     154,100
Equipment foundations for all areas                                             71,200
Instrumentation for all areas including panel and shed                            50,100
Piping for all areas                                                             120,000
Electrical power supply including 4160 and 480 volt boards  and conduit,
 trays, groundings, and telephone                                              100,700
Revisions and additions to powerhouse and boiler including  injection
 ports, metal work, insulation and steam lines                                  143,500
Incremental electrostatic precipitator system0                                  421,600
Incremental solids disposal systemdfor collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal  direct investment                                                  1,707,600

Engineering design  and overheads                                              136,600
Construction expense                                                         204,900
Contractors fees                                                               136,600
Contingency                                                                  222,000

   Total fixed capital  investment	2,407,700
Basis:
      "Midwest location-1972 costs.
      °0" x IVz" limestone ground to 80% minus 400 mesh.
      clnciemental electrostatic precipitator added to maintain dust emission rate
       prior to injection of limestone. Dust collection efficiency prior to
       injection of limestone is assumed to be 99% using a combination of
       mechanical and electrostatic devices.
      "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
       1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-106
  TableA-16Summary of Estimated Fixed Investment3—Dry Limestone Injection Process
                (350-MW Existing Coal-Fired Power Unit; 0.8% S in  Fuel;
                       3.0'Moles CaO Injected per Mole S in Fuel;
                          10.83 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               16,500
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                      68,100
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               101,300
Limestone grinding systemb including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          208,000
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     125,300
Equipment foundations for all areas                                              52,200
Instrumentation for all areas including panel and shed                              44,100
Piping for all areas                                                               92,700
Electrical  power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                                79,800
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                   110,800
Incremental electrostatic precipitator system0                                   463,300
Incremental solids disposal systemdfor collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                1,462,100

Engineering design and overheads                                               102,300
Construction expense                                                          175,500
Contractors fees                                                               102,300
Contingency                                                                  190,100

   Total fixed  capital investment	2,032,300
Basis:                                   ~~~~~
     fMidwest location-1972 costs.
     "0" x I1// limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-107
  TableA-17Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (350-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       4.0 Moles CaO Injected per Mole S in Fuel;
                          14.47 Tons Dry Limestone per Hour)
                                                                           I nvestment, $
General yard work including landscaping, lighting, grading,  raw water
 piping and  drains                                                               19,100
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                      85,800
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                117,100
Limestone grinding system'3 including  feed bin, ball  mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                           251,000
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
  injectors                                                                      140,700
Equipment foundations for all areas                                              62,200
Instrumentation for all areas including panel and shed                             47,300
Piping for all areas                                                              107,200
Electrical power supply including 4160 and 480 volt boards and conduit,
  trays, groundings, and  telephone                                                90,900
Revisions and additions to powerhouse and boiler including injection
  ports, metal work, insulation and steam lines                                   128,100
Incremental electrostatic precipitator system0                                   490,000
Incremental solids disposal system0' for collecting and sluicing
  limestone solids to pond                                                       100,000
   Subtotal direct investment                                                  1,639,400

Engineering design  and overheads                                               114,800
Construction expense                                                          196,700
Contractors fees                                                                114,800
Contingency                                                                   213,100

   Total fixed capital  investment	2,278,800
Basis:
     fMidwest location-1972 costs.
     "0" x 1V4" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
       prior to injection of limestone. Dust collection efficiency prior to
       injection of limestone is assumed to be 99% using a combination of
       mechanical and electrostatic devices.
       Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
       1 mile from power unit. Cost of solids disposal pond not included.

-------
                                          L-108
  Table A-l8Siimmary of Estimated Fixed Investment3—Dry Limestone Injection Process
                (350-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       5.0 Moles CaO Injected per Mole S in  Fuel;
                          18.11 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               21,400
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     102,700
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                131,000
Limestone grinding system'3 including  feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                           290,300
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone  distributor, piping and
 injectors                                                                      153,800
Equipment foundations for all areas                                              71,100
Instrumentation for all areas including panel and shed                              50,100
Piping for all areas                                                              119,900
Electrical  power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                               100,600
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                    143,300
Incremental electrostatic precipitator system0                                   516,600
Incremental solids disposal system0'for collecting and sluicing
 limestone solids to pond                                                       100,000
   Subtotal direct investment                                                 1,800,800

Engineering design and overheads                                               126,100
Construction expense                                                          216,100
Co ntracto rs fees                                                                126,100
Contingency                                                                  234,100

   Total fixed capital investment	2,503,200
Basis:
     aMidwest location-1972 costs.
     bO" x VA" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-109
  TableA-igSummary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (350-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       6.0 Moles CaO Injected per Mole S in Fuel;
                         21.77 TonsTDry  Limestone per Hour)

                                                                           Investment^
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              23,400
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    119,000
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               143,700
Limestone grinding systemb including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          327,200
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
  injectors                                                                     165,700
Equipment foundations for all areas                                             79,400
Instrumentation for all areas including panel and shed                            52,500
Piping for all areas                                                             131,500
Electrical power supply including 4160 and 480 volt boards and conduit,
  trays, groundings, and telephone                                              109,200
Revisions and additions to powerhouse and  boiler including injection
  ports, metal work, insulation and steam lines                                  157,100
Incremental electrostatic precipitator system0                                   539,200
Incremental solids disposal system0'for collecting and sluicing
  limestone solids to pond                                                      100,000
   Subtotal direct investment                                                 1,947,900

Engineering design and overheads                                              136,400
Construction expense                                                          233,700
Contractors fees                                                               136,400
Contingency                                                                  253,300

   Total fixed capital investment	2,707,700
Basis:
     ^Midwest location-1972 costs.
     bO" x 1%" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-110

  TableA-20Summary of Estimated Fixed Investment3—Dry Limestone Injection Process
                (350-MW Existing Coal-Fired Power Unit; 0.8% S in Fuel;
                       7.0 Moles CaO Injected per Mole S in  Fuel;
                          25.43 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               25,300
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     134,700
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                155,200
Limestone grinding system13 including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          361,800
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     176,200
Equipment foundations for all areas                                              87,200
Instrumentation for all areas including panel and shed                             54,500
Piping for all areas                                                             142,100
Electrical  power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                              117,100
Revisions and  additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                   169,800
Incremental electrostatic precipitator system0                                   557,600
Incremental solids disposal system0'for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                 2,081,500

Engineering design and overheads                                               145,700
Construction expense                                                          249,800
Contractors fees                                                               145,700
Contingency                                                                  270,600

   Total fixed  capital investment	2,893,300
Basis:
     ^Midwest location-1972 costs.
     bO" x  1%" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-lll
  TableA-21 Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                 (50-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
                       1.0 Moles CaO Injected per MoleS in Fuel;
                           1.93 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                                7,000
Limestone storage and feed  system including hoppers, unloaders, and
 conveyors                                                                      17,200
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                  42,800
Limestone grinding system'3 including feed bin, ball  mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                            67,800
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                       62,900
Equipment foundations for all areas                                              18,600
Instrumentation for all areas including panel and shed                             28,700
Piping for all areas                                                               39,200
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and  telephone                                                36,800
Revisions and additions to powerhouse and boiler including  injection
 ports, metal work, insulation and steam lines                                     46,800
Incremental electrostatic precipitator system0                                     95,700
Incremental solids disposal system0' for collecting and sluicing
  limestone solids to pond                                                       100,000
   Subtotal direct investment                                                    563,500

Engineering design and overheads                                                 50,700
Construction expense                                                            78,900
Contractors fees                                                                 50,700
Contingency                                                                    73,300

   Total fixed capital investment	817,100
Basis:
     ^Midwest location-1972 costs.
     bO" x 1%" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitatoi added to maintain dust emission rate
      prior to injection of limestone.  Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15%  slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-112
  TableA-22Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                 (50-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
                       2.0 Moles-CaO Injected per Mole S in Fuel;
                          3.89 Tons Dry Limestone per Hour)
                                                                           Investment,!)?
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                                9,900
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                      30,000
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 60,800
Limestone grinding system^ including feed bin, ball  mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          107,100
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                       83,200
Equipment foundations for all areas                                              28,300
Instrumentation for all areas including panel and shed                             34,100
Piping for all areas                                                               55,700
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                                50,400
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                     66,500
Incremental electrostatic precipitator system0                                   112,300
Incremental solids disposal system1^ for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                  738,300

Engineering design and overheads                                                 66,400
Construction expense                                                          103,400
Contractors fees                                                                 66,400
Contingency                                                                    96,000

   Total fixed capital investment	                                       1,070,500
Basis:
     aMidwest location-1972 costs.
     "0" x 1%" limestone ground to 80% minus 400 mesh.
     ""Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water.  Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-113
_TableA-23Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                 (50-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                          5.87 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw  water
 piping and drains                                                               12,200
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                      41,800
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 74,600
Limestone grinding system*5 including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                           139,600
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                       98,100
Equipment foundations for all areas                                              36,200
Instrumentation for all areas including panel and shed                             37,800
Piping for all areas                                                               68,300
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and  telephone                                                60,600
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                     81,600
Incremental electrostatic precipitator system0                                    126,100
Incremental solids disposal system^for collecting and sluicing
 limestone solids to pond                                                       100,000
   Subtotal direct investment                                                    876,900

Engineering design and overheads                                                 78,900
Construction expense                                                           122,800
Contractors fees                                                                 78,900
Contingency                                                                   114,000

   Total fixed capital investment	1,271,500
Basis:
     aMidwest location-1972 costs.
     bO" x 1%" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection oflimestone.  Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond  located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-114


  TableA-2^Summary of Estimated Fixed  investment3—Dry Limestone Injection Process
                 (50-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
                       4.0 Moles CaO Injected per Mole S in  Fuel;
                           7.86 Tons Dry Limestone per Hour)
                                                                           lnvestment,$
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               14,100
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                      52,700
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 86,300
Limestone grinding system13 including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          168,700
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     110,100
Equipment foundations for all areas                                              43,100
Instrumentation for all areas including panel and shed                            40,700
Piping for all areas                                                               79,000
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                                69,100
Revisions and additions to powerhouse and  boiler including injection
 ports, metal work, insulation and steam lines                                    94,400
Incremental electrostatic precipitator system0                                   136,300
Incremental solids disposal system0'for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                  994,500

Engineering design and overheads                                                89,500
Construction expense                                                          139,200
Contractors fees                                                                89,500
Contingency                                                                  129,300

   Total fixed capital investment	1,442,000
Basis:                                                ~
     aMidwest location-1972 costs.
     bO" x 1%" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     dSolids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-115
  TableA-25Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (150-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
                       1.0 Moles CaO Injected per Mole S in Fuel;
                          5.80 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              12,100
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     41,200
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 74,200
Limestone grinding system'3 including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          138,400
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                      97,500
Equipment foundations for all areas                                             35,900
Instrumentation for all areas including panel and shed                            37,700
Piping for all areas                                                              67,900
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                               60,200
Revisions and additions to powerhouse and boiler including injection
  ports, metal work, insulation and steam lines                                   81,100
Incremental electrostatic precipitator system0                                  243,000
Incremental solids disposal system^for collecting and sluicing
  limestone solids to pond                                                      100,000
   Subtotal direct investment                                                   989,200

Engineering design and overheads                                                79,100
Construction expense                                                          128,600
Contractors fees                                                                79,100
Contingency                                                                  128,600

   Total fixed capital  investment	1,404,600
Basis:
     ^Midwest location-1972 costs.
     bO" x 1%" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-116
  TabieA-26Summary of Estimated Fixed Investment8—Dry Limestone Injection Process
                (150-MW Existing Coal-Fired Power Unit; 3.0% S in  Fuel;
                       2.0 Moles CaO Injected per Mole S in Fuel;
                          11.67 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               17..100
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     72,200
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               105,100
Limestone grinding systemb including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          218,200
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     129,000
Equipment foundations for all areas                                              54,600
Instrumentation for all areas including panel and shed                              44,900
Piping for all areas                                                               96,200
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                                82,500
Revisions aand additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                  115,000
Incremental electrostatic precipitator system0                                   285,000
Incremental solids disposal systemdfor collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                 1,319,800

Engineering design and overheads                                               105,600
Construction expense                                                          171,600
Contractors fees                                                               105,600
Contingency                                                                  171,600

   Total fixed capital investment	1,874,200
Basis:
     aMidwest location-1972 costs.
     bO" x 1V4" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-117
        -gySummary of Estimated Fixed lnvestmenta~Dry Limestone Injection Process
                (150-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                          17.60 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              21,000
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    100,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               129,100
Limestone grinding system'3 including feed bin, ball  mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          284,800
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     152,100
Equipment foundations for all areas                                             69,900
Instrumentation for all areas including panel and shed                            49,800
Piping for all areas                                                             118,200
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                               99,200
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                  141,200
Incremental electrostatic precipitator system0                                  320,000
Incremental solids disposal system^for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct Investment                                                  1,585,600

Engineering design and overheads                                              126,800
Construction expense                                                         206,100
Contractors fees                                                               126,800
Contingency                                                                  206,100

   Total fixed capital  investment	2,251,400
Basis:
     ^Midwest location-1972 costs.
     bO" x IVa" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
       prior to injection of limestone. Dust collection efficiency prior to
       injection of limestone is assumed to be 99% using a combination of
       mechanical and electrostatic devices.
       Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
       1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-118
  TableA-28Summary of Estimated Fixed In vestment3-Dry Limestone Injection Process
                (150-MW Existing Coal-Fired Power Unit; 3.0% S in  Fuel;
                       4.0 Moles CaO Injected per Mole S in Fuel;
                          23.59 Tons Dry Limestone per Hour)
                                                                           I nvestment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               24,400
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    126,900
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                149,400
Limestone grinding systemb including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          344,800
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                      171,000
Equipment foundations for all areas                                             83,300
Instrumentation for all areas including panel and shed                             53,500
Piping for all areas                                                             136,800
Electrical  power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                              113,200
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                   163,500
Incremental electrostatic precipitator system0                                   346,000
Incremental solids disposal system^for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                1,812,800

Engineering design and overheads                                               145,000
Construction expense                                                          235,700
Contractors fees                                                               145,000
Contingency                                                                  235,700

   Total fixed capital investment	2,574,200
Basis:
     aMidwest location-1972 costs.
     °0" x 1V4" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     dSolids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-119
JTableA-ggSummary of Estimated Fixed lnvestmenta~Dry Limestone Injection Process
                (250-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
                       1.0 Moles CaO I njected per Mole S in Fuel;
                          9.67 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              15,600
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     62,200
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 95,800
Limestone grinding system'3 including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          193,100
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     119,700
Equipment foundations for all areas                                             48,800
Instrumentation for all areas including panel and shed                            42,800
Piping for all areas                                                              87,700
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and  telephone                                               75,800
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam  lines                                  104,800
Incremental electrostatic precipitator system0                                  376,700
Incremental solids disposal system0'for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                 1,323,000

Engineering design  and overheads                                               105,900
Construction expense                                                          158,800
Contractors fees                                                               105,900
Contingency                                                                  172,000

   Total fixed capital investment	1,865,600
Basis:
     ^Midwest location-1972 costs.
     bO" x I'/z" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone.  Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-120
  Table A-30Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (250-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
                       2.0 Moles CaO Injected per Mole S in Fuel;
                          19.45 Tons Dry  Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and ydrains                                                             22,100
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    108,700
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                135,700
Limestone grinding systemb including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          303,900
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                      158,300
Equipment foundations for all areas                                             74,200
Instrumentation for all areas including panel and shed                             51,000
Piping for all areas                                                              124,200
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                               103,900
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                    148,400
Incremental electrostatic precipitator system0                                   441,800
Incremental solids disposal system0'for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                1,772,200

Engineering design and overheads                                               141,800
Construction expense                                                          212,700
Contractors fees                                                               141,800
Contingency                                                                  230,400

   Total fixed capital investment	2,498,900
Basis:
     aMidwest location-197 2 costs.
     °Q" x 1%" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-121


_TableA-31 Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (250-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                          29.33 Tons Dry Limestone per Hour)

                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              27,200
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     151,000
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                166,600
Limestone grinding system*3 including  feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                           397,100
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                      186,600
Equipment foundations for all areas                                             95,000
Instrumentation for all areas including panel and shed                            56,500
Piping for all areas                                                              152,500
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                               124,900
Revisions and additions to powerhouse and boiler including  injection
 ports, metal work, insulation and steam lines                                   182,300
Incremental electrostatic precipitator system0                                    496,000
Incremental solids disposal system0'for collecting and sluicing
 limestone solids to pond                                                       100,000
   Subtotal direct investment                                                 2,135,700

Engineering design and overheads                                                170,900
Construction expense                                                           256,300
Contractors fees                                                                170,900
Contingency                                                                   277,600

   Total fixed capital investment	3,011,400
Basis:
     ^Midwest location-1972 costs.
     bO" x IVz" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      .mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-122
  TableA-32Summary of Estimated Fixed Investment3—Dry Limestone Injection Process	
                (250-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
                       4.0 Moles CaO Injected per Mole S in Fuel;
                          39.32 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              31,500
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    190,800
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                192,900
Limestone grinding systemb including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          480,400
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     209,700
Equipment foundations for all areas                                             113,200
Instrumentation for all areas including panel and shed                             60,800
Piping for all areas                                                              176,600
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                               142,600
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                   211,000
Incremental electrostatic precipitator system0                                   536,300
Incremental solids disposal system^ for collecting and sluicing
 limestone solids to pond                                                      135,000
   Subtotal ddirect investment                                                2,480,800

Engineering design and overheads                                                198,500
Construction expense                                                          297,700
Contractors fees                                                                198,500
Contingency                                                                  322,500

   Total fixed capital investment	                                3,498,000
Basis:
     aMidwest location-1972 costs.
     °0" x I1// limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-123
_Tj^teA-33Summary of Estimated Fixed Irwejrtn^^^                        Process
                (350-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
                       1 .0 Moles CaO Injected per Mole S in Fuel;
                          13.53 Tons Dry Limestone per Hour)

                                                                           I nvestment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               18,500
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                      81,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                1 13,200
Limestone grinding system'3 including  feed  bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          240,200
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                      137,000
Equipment foundations for all areas                                              59,700
Instrumentation for all areas including panel and shed                             46,600
Piping for all areas                                                              103,700
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                                88,200
Revisions and additions to powerhouse and boiler including  injection
 ports, metal work, insulation and steam lines                                   123,900
Incremental electrostatic precipitator system0                                    498,200
Incremental solids disposal system0' for collecting and sluicing
  limestone solids to pond                                                     _ 100,000
   Subtotal  direct investment                                                 1,610,500

 Engineering design  and overheads                                               1 1 2,700
Construction expense                                                          193,300
Contractors fees                                                                1 1 2,700
Contingency                                                                   209,400

   Total fixed capital  investment ______________ 2,238,600
Basis:
     ^Midwest location -197 2 costs.
     bO" x iy2" limestone ground to 80% minus  400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
       prior to injection of limestone. Dust collection efficiency prior to
       injection of limestone is assumed to be 99% using a combination of
       mechanical and electrostatic devices.
       Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
       1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-124
              ummary of Estimated Fixed Investment3—Dry Limestone Injection Process
                (350-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
                       2.0 Moles CaO Injected per Mole S in  Fuel;
                          27.23 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               26,200
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    142,200
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                160,600
Limestone grinding system'3 including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          378,200
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                      181,200
Equipment foundations for all areas                                              90,800
Instrumentation for all areas including panel and shed                             55,500
Piping for all areas                                                             147,000
Electrical  power supply including 4160 and 480 volt  boards and conduit,
 trays, groundings, and telephone                                              120,800
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                   175,700
Incremental electrostatic precipitator system0                                   584,300
Incremental solids disposal system^for collecting and sluicing
 limestone solids to pond                                                      100,000
  Subtotal direct investment                                                2,162,500

Engineering design and overheads                                               151,400
Construction expense                                                          259,500
Contractors fees                                                               151,400
Contingency                                                                  281,100

^JTotalJixed capital investment	___	3,005,900^
Basis:
     ^Midwest location-1972 costs.
     bO" x IVi" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-125


 Jjble A-35Summary of Estimated Fixed In vestment3-Dry Limestone Injection Process
                (350-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                         41.07 Tons Dry Limestone per Hour)

                                                                           I nvestment, $
General yard work including landscaping, lighting, grading,  raw water
 piping and drains                                                              32,100
Limestone storage and feed  system including hoppers, unloaders, and
 conveyors                                                                     197,700
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                197,200
Limestone grinding system0 including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          494,300
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                      213,500
Equipment foundations for  all areas                                             116,200
Instrumentation for all areas including panel and shed                            61,500
Piping for all areas                                                              180,500
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and  telephone                                               145,400
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                   215,700
Incremental electrostatic precipitator system0                                    656,000
Incremental solids disposal system0' for collecting and sluicing
 limestone solids to pond                                                    	135,000
   Subtotal direct investment                                                 2,645,100

Engineering design and overheads                                               185,200
Construction expense                                                           317,400
Contractors fees                                                                185,200
Contingency                                                                   343,900

   Total fixed capital investment	3,676,800
Basis:
     ^Midwest location-1972 costs.
     "0" x VA." limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone.  Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
       1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-126
  Table A-36Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (350-MW Existing Coal-Fired Power Unit; 3.0% S in Fuel;
                       4.0 Moles CaO Injected per Mole S in Fuel;
                          55.04 Tons Dry  Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              37,200
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                   249,800
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               228,300
Limestone grinding systemb including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          597,700
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     239,900
Equipment foundations for all areas                                            138,500
Instrumentation for all areas including panel and shed                            66,100
Piping for all areas                                                             209,000
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                              165,800
Revisions and additions to powerhouse and  boiler including injection
 ports, metal work, insulation and steam  lines                                   249,700
Incremental electrostatic precipitator system0                                   709,300
Incremental solids disposal system0' for collecting and sluicing
 limestone solids to pond                                                      175,000
   Subtotal direct investment                                                3,066,300

Engineering design and overheads                                               214,600
Construction expense                                                          368,000
Contractors fees                                                               214,600
Contingency                                                                  398,600

   Total fixed capital investment	4,262,100
Basis:
     aMidwest location-1972 costs.
     bO" x W limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-127


 JablgA-37Summary of Estimated Fixed Investment9- Dry Limestone Injection Process
                (50-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       1.0 Moles CaO Injected per Mole S in Fuel;
                          3.23 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and  drains                                                               9,000
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     25,900
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 55,300
Limestone grinding systemb including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                           94,700
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                      77,300
Equipment foundations for all areas                                              25,400
Instrumentation for all areas including panel and shed                             32,600
Piping for all areas                                                              50,600
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and  telephone                                               46,400
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam  lines                                    60,500
Incremental electrostatic precipitator system0                                    108,700
Incremental solids disposal system*^ for collecting and sluicing
 limestone solids to pond                                                       100,000
   Subtotal direct investment                                                   686,400

Engineering design and overheads                                                61,800
Construction expense                                                           96,100
Contractors fees                                                                61,800
Contingency                                                                   89,200

   Total fixed capital  investment	995,300
Basis:
     ^Midwest location-1972 costs.
     bO" x I'/z" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
       1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-128
  TableA-38Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                 (50-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       2.0 Moles CaO Injected per Mole S in Fuel;
                          6.53 Tons Dry Limestone per Hour)
                                                                           lnvestment,$
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               12,800
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     45,400
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 78,700
Limestone grinding system'3 including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          149,800
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     102,300
Equipment foundations for all areas                                               38,600
Instrumentation for all areas including panel and shed                             38,800
Piping for all areas                                                               72,000
Electrical  power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                                63,600
Revisions and additions to  powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                     86,100
Incremental electrostatic precipitator system0                                   131,200
Incremental solids disposal system01 for collecting and sluicing
 limestone solids to pond                                                      100,000
  Subtotal direct investment                                                   919,300

Engineering design and overheads                                                 82,700
Construction expense                                                          128,700
Contractors fees                                                                 82,700
Contingency                                                                  119,500

  Total fixed capital investment	1,332,900
Basis:
     aMidwest location—1972 costs.
     "0" x W limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-129
 JTableA-39 Summary of Estimated Fixed Investtnenta-Dry Limestone Injection Process
                 (50-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                          9.89 Tons Dry Limestone per Hour)
                                                                           I nvestment, $
General yard work including landscaping, lighting, grading, raw  water
 piping and  drains                                                               15,800
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                      63,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                  96,900
Limestone grinding system'3 including feed bin, ball  mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          195,900
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone  distributor, piping and
 injectors                                                                     120,900
Equipment foundations for all areas                                              49,500
Instrumentation for all areas including panel and shed                             43,100
Piping for all areas                                                               88,700
Electrical power supply including 4160 and 480 volt boards  and conduit,
 trays, groundings, and telephone                                                76,600
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                   106,000
Incremental electrostatic precipitator system0                                   148,500
Incremental solids disposal system0' for collecting and sluicing
 limestone solids to pond                                                      100,000
  Subtotal direct investment                                                 1,105,200

Engineering design and overheads                                                 99,500
Construction expense                                                          154,700
Contractors fees                                                                 99,500
Contingency                                                                  143,700

  Total fixed capital investment	1,602,600
Basis:
     ^Midwest location-1972 costs.
     bO" x 1V4" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-130


  TableA-UOSummary of Estimated  Fixed  Investmenta--Dry Limestone Injection Process
                 (50-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       4.0 Moles CaO Injected per Mole S in  Fuel;
                          13.33 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               18,300
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     80,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                112,400
Limestone grinding system*3 including feed bin, ball  mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                           238,000
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                      136,100
Equipment foundations for all areas                                              59,200
Instrumentation for all areas including panel and shed                             46,400
Pi ping for all areas                                                              102,900
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                                87,600
Revisions and additions to powerhouse and boiler including injection
  ports, metal work, insulation and steam lines                                    123,000
Incremental electrostatic precipitator system0                                    163,900
Incremental solids disposal system0' for collecting and sluicing
  limestone solids to pond                                                       100,000
   Subtotal direct investment                                                 1,268,100

Engineering design  and overheads                                               114,100
Construction expense                                                           177,500
Contractors fees                                                                114,100
Contingency                                                                   164,900

   Total fixed capital investment	1,838,700
Basis:
     aMidwest location-1972 costs.
     bO" x \Vi" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     ^Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-131
 jfgbie A-^lSummary of Estimated Fixed lnvestmenta~Dry Limestone Injection Process
                (150-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       1.0 Moles CaO Injected per Mole S in Fuel;
                          9.70 Tons Dry Limestone per Hour)
                                                                           Investments
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               15,600
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     62,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                 95,800
Limestone grinding system'3 including feed bin, ball  mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          193,400
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     119,900
Equipment foundations for all areas                                             48,300
Instrumentation for all areas including panel and shed                            42,900
Piping for all areas                                                              87,700
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and  telephone                                               75,900
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                  104,800
Incremental electrostatic precipitator system0                                  276,000
Incremental solids disposal system0'for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                 1,222,600

Engineering design and overheads                                                97,800
Construction expense                                                          159,000
Contractors fees                                                                97,800
Contingency                                                                   159,000

   Total fixed capital investment	1,736,200
Basis:
     ^Midwest location-1972 costs.
     "0" x IVi" limestone ground to 80% minus 400 mesh.
     clnciemental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-132
  TableA-42Summary of Estimated Fixed Investmenta—Dry Limestone injection Process
                (150-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       2.0 Moles CaO Injected per Mole S in Fuel;
                          19.59 Tons Dry Limestone per Hour)
                                                                           I nvestment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               22,200
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    109,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                136,200
Limestone grinding system'3 including  feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          305,500
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                      158,800
Equipment foundations for all areas                                              74,500
Instrumentation for all areas including panel and shed                              51,100
Piping for all areas                                                              124,700
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                               104,200
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                    149,000
Incremental electrostatic precipitator system0                                   333,000
Incremental solids disposal system0'for collecting and sluicing
 limestone solids to pond                                                       100,000
   Subtotal direct investment                                                 1,668,500

Engineering design and overheads                                                133,500
Construction expense                                                          217,000
Contractors fees                                                                133,500
Contingency                                                                  217,000

   Total fixed capital investment	2,369,500
Basis:
     aMidwest location-1972 costs.
     "0" x VA" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-133
_TableA-^3Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (150-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                         29.66 Tons Dry Limestone per Hour)
                                                                           lnvestment,$
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              27,300
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    152,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               167,600
Limestone grinding system'3 including feed bin, ball milt and classifier,
 storage silo, conveyors and chutes, and dust collectors                          399,900
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     187,400
Equipment foundations for all areas                                             95,600
Instrumentation for all areas including panel and shed                            56,700
Piping for al I areas                                                             153,400
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                              125,500
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam  lines                                  183,300
Incremental electrostatic precipitator system0                                  377,000
Incremental solids disposal system^for collecting and sluicing
 limestone solids to pond                                                      135,000
   Subtotal direct investment                                                 2,061,000

Engineering design and overheads                                               164,900
Construction expense                                                          267,900
Contractors fees                                                               164,900
Contingency                                                                   267,900

   Total fixed capital investment	2,926,600
Basis:
     ^Midwest location-1972 costs.
     bO" x IVz" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-134
  TableA-4^Summary of Estimated Fixed investment3—Dry Limestone Injection Process
                (150-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       4.0 Moles CaO Injected per Mole S in Fuel;
                          39.99 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              31,700
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    193,400
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               194,600
Limestone grinding systemb including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          485,600
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     211,300
Equipment foundations for all areas                                            114,400
Instrumentation for all areas including panel and shed                             61,100
Piping for all areas                                                             178,100
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                              143,600
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                   212,800
Incremental electrostatic precipitator system0                                   416,000
Incremental solids disposal systemdfor collecting and sluicing
 limestone solids to pond                                                      135,000
   Subtotal direct investment                                                2,377,600

Engineering design and overheads                                               190,200
Construction expense                                                          309,100
Contractors fees                                                               190,200
Contingency                                                                  309,100

   Total fixed capital investment	3,376,200
Basis:
     "Midwest location-1972 costs.
     bO" x IVz" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-135
_TableA-^5Summary of Estimated Fixed In vestment3-Dry Limestone Injection Process
                (250-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       1.0 Moles CaO Injected per Mole S in Fuel;
                          16.17 Tons Dry Limestone per Hour)
                                                                           Investment^
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              20,200
Limestone storage and feed  system including hoppers, unloaders, and
 conveyors                                                                     93,800
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               123,700
Limestone grinding system'3 including feed bin, ball  mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          269,600
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     147,100
Equipment foundations for all areas                                             66,500
Instrumentation for all areas including panel and shed                            48,700
Piping for all areas                                                             113,200
Electrical  power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                               95,600
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                  135,300
Incremental electrostatic precipitator system0                                  427,800
Incremental solids disposal system0'for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                 1,641,500

Engineering design and overheads                                              131,300
Construction expense                                                          197,000
Contractors fees                                                               131,300
Contingency                                                                  213,400

   Total fixed capital investment	2,314,500
Basis:
     ^Midwest location-1972 costs.
     bO" x 1%" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-136
  Table A-J46Summary of Estimated Fixed Investment9—Dry Limestone Injection Process
                (250-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       2.0 Moles CaO Injected per Mole S in Fuel;
                          32.65 Tons Dry Limestone per Hour)
                                                                           I nvestment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               28,700
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                     164,400
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                                175,900
Limestone grinding systemb including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          425,600
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone  distributor, piping and
 injectors                                                                      194,800
Equipment foundations for all areas                                             101,300
Instrumentation for all areas including panel and shed                             58,000
Piping for all areas                                                              161,000
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                               131,100
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                    192,400
Incremental electrostatic precipitator system0                                   516,200
Incremental solids disposal system^ for collecting and sluicing
 limestone solids to pond                                                       135,000
   Subtotal direct investment                                                2,284,400

Engineering design and overheads                                                182,800
Construction expense                                                          274,100
Contractors fees                                                                182,800
Contingency                                                                  297,000

   Total fixed capital investment	3,221,100
Basis:
     "'Midwest location-1972 costs.
     bO" x 1%" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-137


  TableA-^TSummary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (250-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                         49.43 Tons Dry  Limestone per Hour)
                                                                           I nvestment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              35,300
Limestone storage and feed  system including hoppers, unloaders, and
 conveyors                                                                    229,200
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               216,300
Limestone grinding system'3 including  feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          557,400
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     229,900
Equipment foundations for all areas                                            129,900
Instrumentation for all areas including panel and shed                            64,400
Piping for all areas                                                             198,000
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                              158,000
Revisions and additions to powerhouse and boiler including injection
  ports, metal work, insulation and steam lines                                  236,600
Incremental electrostatic precipitator system0                                  584,400
Incremental solids disposal system0' for collecting and sluicing
  limestone solids to pond                                                      175,000
   Subtotal direct investment                                                 2,814,400

Engineering design  and overheads                                              225,200
Construction expense                                                         337,700
Contractors fees                                                               225,200
Contingency                                                                  365,900

   Total fixed capital  investment	3,968,400
Basis:
     fMidwest location-1972 costs.
     °0" x IVz" limestone ground to 80% minus 400 mesh.
     clnciemental electrostatic precipitator added to maintain dust emission rate
       prior to injection of limestone. Dust collection efficiency prior to
       injection of limestone is assumed to be 99% using a combination of
       mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
       1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-138
  TableA-1+8Summary of Estimated Fixed Investment3—Dry Limestone Injection Process
                (250-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       4.0 Moles CaO Injected per Mole S in  Fuel;
                          66.65 Tons Dry Limestone per Hour)
                                                                           lnvestment,$
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               41,000
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    291,100
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               251,300
Limestone grinding systemb including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          676,900
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone  distributor, piping and
 injectors                                                                     259,100
Equipment foundations for all areas                                            155,400
Instrumentation for all areas including panel and shed                             69,400
Piping for all areas                                                             230,000
Electrical power supply including 4160 and 480 volt  boards and conduit,
 trays, groundings, and telephone                                              180,700
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                   274,900
Incremental electrostatic precipitator system0                                   644,800
Incremental solids disposal system^ for collecting and sluicing
 limestone solids to pond                                                      175,000
   Subtotal direct investment                                                3,249,600

Engineering design and overheads                                               260,000
Construction expense                                                          390,000
Contractors fees                                                               260,000
Contingency                                                                  422,400

   Total fixed capital investment	4,582,000
Basis:
     fMidwest location-1972 costs.
     bO" x l!/2" limestone ground to 80% minus 400 mesh.
     clnciemental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-139
        -49Summary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (350-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       1.0 Moles CaO Injected per Mole S in Fuel;
                         22.63 Tons Dry Limestone per Hour)
                                                                           Investment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              23,900
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    122,700
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               146,400
Limestone grinding system^ including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          335,500
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     168,200
Equipment foundations for all areas                                             81,300
Instrumentation for all areas including panel and shed                            52,900
Piping for all areas                                                             134,000
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and  telephone                                              111,100
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam  lines                                  160,200
Incremental electrostatic precipitator system0                                  565,800
Incremental solids disposal system*^ for collecting and sluicing
 limestone solids to pond                                                      100,000
   Subtotal direct investment                                                 2,002,000

Engineering design and overheads                                              140,100
Construction expense                                                          240,200
Contractors fees                                                               140,100
Contingency                                                                   260,300

   Total fixed capital investment	2,782,700
Basis:
     ^Midwest location-1972 costs.
     bO" x IVi" limestone ground to 80% minus 400 mesh.
     Incremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone.  Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-140
  TableA-^OSummary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (350-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       2.0 Moles CaO Injected per Mole S in Fuel;
                          45.71 Tons Dry  Limestone per Hour)
                                                                           Investment,^
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              33,900
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    215,300
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               208,100
Limestone grinding system*3 including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          529,900
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     222,800
Equipment foundations for all areas                                            123,900
Instrumentation for all areas including panel and shed                             63,200
Piping for all areas                                                             190,500
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                              152,500
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                   227,600
Incremental electrostatic precipitator system0                                   682,700
Incremental solids disposal system^ for collecting and sluicing
 limestone solids to pond                                                      175,000
   Subtotal direct investment                                                2,825,400

Engineering design and overheads                                              197,800
Construction expense                                                          339,000
Contractors fees                                                               197,800
Contingency                                                                  367,000

   Total fixed capital investment	                           3,927,000
Basis:
     aMidwest location-1972 costs.
     bO" x 1V4" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-141
_TableA-5lSummary of Estimated Fixed Investmenta-Dry Limestone Injection Process
                (350-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                         69.21 Tons Dry Limestone per Hour)

                                                                           I nvestment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                              41,700
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                    300,000
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               255,900
Limestone grinding system^ including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          693,600
Limestone injection system  including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     263,000
Equipment foundations for all areas                                            158,900
Instrumentation for all areas including panel and shed                            70,000
Piping for all areas                                                             234,300
Electrical power supply including 4160 and 480 volt boards and conduit,
 trays, groundings, and telephone                                              183,800
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                  280,000
Incremental electrostatic precipitator system0                                   772,900
Incremental solids disposal system^for collecting and sluicing
 limestone solids to pond                                                      175,000
   Subtotal direct investment                                                 3,429,100

Engineering design  and overheads                                              240,000
Construction expense                                                          411,500
Contractors fees                                                               240,000
Contingency                                                                  445,800

   Total fixed capital  investment	4,766,400
Basis:
     ''Midwest location-1972 costs.
     °0" x IVi" limestone ground to 80% minus 400 mesh.
     clnciemental electrostatic precipitator added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
     "Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
       1 mile from power unit. Cost of solids disposal pond not included.

-------
                                        L-142
  TableA-52Summary of Estimated Fixed Investment3—Dry Limestone Injection Process
                 (350-MW Existing Coal-Fired Power Unit; 5.0% S in Fuel;
                       4.0 Moles CaO Injected per Mole S in Fuel;
                          93.31 Tons Dry Limestone per Hour)
                                                                           I nvestment, $
General yard work including landscaping, lighting, grading, raw water
 piping and drains                                                               48,500
Limestone storage and feed system including hoppers, unloaders, and
 conveyors                                                                   381,000
Limestone drying system including dryer, dust collectors, chutes and ducts,
 bucket elevator, and dryer shed                                               297,200
Limestone grinding system'3 including feed bin, ball mill and classifier,
 storage silo, conveyors and chutes, and dust collectors                          842,500
Limestone injection system including transport pump, air compressors, feed
 tank, conveyors, ducts and chutes, limestone distributor, piping and
 injectors                                                                     296,400
Equipment foundations for all areas                                            190,100
Instrumentation for all areas including panel and shed                             75,500
Piping for all areas                                                             272,100
Electrical  power supply including 4160 and 480 volt  boards and conduit,
 trays, groundings, and telephone                                              210,300
Revisions and additions to powerhouse and boiler including injection
 ports, metal work, insulation and steam lines                                   325,100
Incremental electrostatic precipitator systemc                                   852,800
Incremental solids disposal system1^ for collecting and sluicing
 limestone solids to pond                                                      270,000
   Subtotal direct investment                                                4,061,500

Engineering design and overheads                                               284,300
Construction expense                                                          487,400
Contractors fees                                                               284,300
Contingency                                                                  528,000

   Total fixed capital investment	5,645,500
Basis:
     aMidwest location-1972 costs.
     bO" x I'/z" limestone ground to 80% minus 400 mesh.
     clncremental electrostatic precipitatoi added to maintain dust emission rate
      prior to injection of limestone. Dust collection efficiency prior to
      injection of limestone is assumed to be 99% using a combination of
      mechanical and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water. Disposal pond located
      1 mile from power unit. Cost of solids disposal pond not included.

-------
                                         L-143
                                              8,200 tons      4.05/ton
                                             10,070 man-hr   6.00/man-hr
                   33,200
         Table A-53-Average Annual Operating Cost for Reducing SO2 Emission
_fromjpwer Plants by Dry Limestone Injection-Regulated Power Company Economics3
                 (50-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                           1.55 Tons Dry Limestone per Hour)
                                                                            Total annual
	        	Annual quantity    Unit cost, $      cost, $
             Direct Costs
Delivered raw material
 Limestone (95% CaC03)
   Subtotal raw material
Conversion costs
 Operating labor & supervision
   including payroll overhead
Utilities^
 Fuel oil (drying)
 Sluice water
 Electricity
   Receiving-drying
   Grinding
   Injection
   Dust collection  (credit)
   Solids disposal
Maintenance
 Labor and material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
Analyses
 Subtotal conversion costs
 Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
   for dry limestone injection
 Thermal effect of dry limestone injection
   on operating cost of power plant
                                             43,500 gal
                                            267,000 M gal

                                             49,200 kWh
                                            437,900 kWh
                                             78,700 kWh
                                            -58,800 kWh
                                            514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
                                                 50 hr
10.00/hr
 60,400

  4,800
  8,000

    300
  3,100
    600
   (400)
  3,600
 19,900
  2,600
    500
103,400
136,600
Total
                                                      Cost/ton
                                                       of coal
                                                     burned,$
                  132,300

                   20,700
                    6.000
                  159,000

                  295,600

                    2,800


               Total annual
                  cost, $
                 298,400
aBasis:
      Coal burned-97,900 tons/yr; .784 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time—5000 hr/yr
      Midwest plant location-1972 costs
      O" x iy2" limestone ground to 80% minus 400 mesh
      Capital investment, $751,500
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection ot limestone. Uust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
,      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                       L-144
                                             10,900 tons      4.05/ton
                                             10,070 man-hr   6.00/man-hr
          Table A-^h Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                  (50-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       4.0 Moles CaO Injected per Mole S in  Fuel;
                          2.07 Tons Dry Limestone per  Hour)
                                                                            Total annual
	Annual quantity    Unit cost, $      cost, $
              Direct Costs
Delivered raw material
  Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
  Operating labor & supervision
  including payroll overhead
Utilities^
  Fuel oil (drying)
  Sluice water
  Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection  (credit)
  Solids disposal
Maintenance
  Labor and material
   Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
  Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
  of initial fixed investment
Overhead
  Plant, 20% of conversion costs
  Administrative, 10% of operating labor
  Subtotal indirect costs
  Average annual operating cost
  for dry limestone injection
  Thermal effect of dry limestone injection
  on operating cost of  power plant
                                             57,800 gal
                                            267,000 M gal

                                             65,400 kWh
                                            582,100 kWh
                                            104,600 kWh
                                            -57,500 kWh
                                            514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
                                                 50 hr
10.00/hr
                   44.100
                   44,100
 60,400

  6,400
  8,000

    500
  4,100
    700
   (400)
  3,600
 22,300
  2,700
    500
108,800
152,900
                                                                               146,900

                                                                                21,800
                                                                                 6,000
                                                                               174,700

                                                                               327,600

                                                                                 3,700
Total
                                                     Cost/ton
                                                      of coal
                                                     burned. $
                                                                            Total annual
                                                                               cost. $
                                                        3.38
                 331,300
aBasis:
      Coal burned-98,100 tons/yr; .785 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      O" x \Vi limestone ground to 80% minus 400 mesh
      Capital investment, $834,500
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                        L-145
         TableA-55Average Annual Operating Cost for Reducing SO2 Emission
_from Power Plants by Dry Limestone Injection-Regulated Power Company Economics8
                 (50-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       5.0 Moles CaO Injected per Mole S in  Fuel;
                          2.59 Tons Dry Limestone per  Hour)
                                                                            Total annual
	Annual quantity    Unit cost, $     cost, $
             Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
 13,700 tons      4.05/ton
                   55.500
                   55,500
Conversion costs
 Operating labor & supervision
   including payroll overhead
Utilities'^
 Fuel oil (drying)
 Sluice water
 Electricity
   Receiving-drying
   Grinding
   Injection
   Dust collection
   Solids disposal
Maintenance
 Labor and material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
Analyses
 Subtotal conversion costs
 Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
   for dry limestone  injection
 Thermal  effect of dry limestone injection
   on operating cost  of power plant
Total
 10,070 man-hr   6.00/man-hr
 72,600 gal
267,000 M gal

 82,200 kWh
731,600kWh
131,500kWh
 -56,000 kWh
514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      60 hr
10.00/hr
                                                      Cost/ton
                                                       of coal
                                                     burned.$
 60,400

  8,000
  8,000

    600
  5,100
    900
   (400)
  3,600
 24,300
  2,900
    600
114,000
169,500
                                   159,600

                                    22,800
                                     6.000
                                   188,700

                                   358,200

                                     4,600


                                Total annual
                                   cost. $
            3.69
                 362,800
aBasis:
      Coal burned-98,200 tons/yr; .786 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      O" x I1// limestone ground to 80% minus 400 mesh
      Capital investment, $908,300
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                         L-146
          TableA-56 Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
                  (50-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       6.0 Moles CaO Injected per Mole S  in Fuel;
                           3.11 Tons Dry Limestone per Hour)
                                                                            Total annual

Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Annual quantity Unit cost, $ cost, $
16,400 tons 4.05/ton 66.400
66,400
Conversion costs
 Operating labor & supervision
   including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
   Receiving-drying
   Grinding
   Injection
   Dust col lection (credit)
   Solids disposal
Maintenance
 Labor and material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
Analyses
 Subtotal conversion costs
 Subtotal direct costs

             Indirect Costs
Average capital charges at  17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion  costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
   for dry limestone injection
 Thermal effect of dry limestone injection
   on operating cost of power plant
Total
 10,070 man-hr   6.00/man-hr
 86,900 gal
267,000 M gal

 98,400 kWh
875,800 kWh
157,400 kWh
 -55,000 kWh
514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      70 hr
10.00/hr
                                                      Cost/ton
                                                       of coal
                                                      burned.$
            3.99
 60,400

  9,600
  8,000

    700
  6,100
  1,100
   (400)
  3,600
 26,200
  3,000
    700
119,000
185,400
                                   171,600

                                    23,800
                                      6,000
                                   201,400

                                   386,800

                                      5,500


                                Total annual
                                   cost. $
                 392,300
aBasis:
      Coal burned-98,400 tons/yr; .787 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      O" x \Vi  limestone ground to 80% minus 400 mesh
      Capital investment, $974,900
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                        L-147
                                             19,100 tons      4.05/ton
                                             10,070 man-hr   6.00/man-hr
         Table A-57 Average Annual Operating Cost for Reducing SO2 Emission
 from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                 (50-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                      7.0 Moles CaO Injected per Mole S in Fuel;
                          3.63 Tons  Dry Limestone per Hour)
                                                                           Total annual
       	Annual quantity    Unit cost. $     cost, $
             Direct Costs
Delivered raw material
 Limestone (95% CaCO3)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
 Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
                                            101,200 gal
                                            267,000 M gal

                                            114,600 kWh
                                          1,019,900 kWh
                                            183,400 kWh
                                             -53,800 kWh
                                            514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
                                                 80 hr
10.00/hr
                   77r400
                   77,400
 60,400

 11,100
  8,000

    800
  7,100
  1,300
    (400)
  3,600
 28,000
  3,100
    800
123,800
201,200
Total
                                                      Cost/ton
                                                       of coal
                                                     burned,$
                  182,400

                   24,800
                    6.000
                  213,200

                  414,400

                    6,400


               Total annual
                  cost, $
                                                       4.27
                 420,800
"Basis:
      Coal burned-98,500 tons/yr; .788 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      O" x \W limestone ground to 80% minus 400 mesh
      Capital investment, $1,036,300
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Uust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
.      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                        L-148
                                             24,400 tons      4.05/ton
                                             10,070 man-hr   6.00/man-hr
          TableA-58 Average Annual Operating Cost for Reducing SO2  Emission
  from Power Plants by Dry Limestone Injection—Regulated Power Company^Economics3
                 (150-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                          4.64 Tons Dry Limestone per Hour)
                                                                            Total annual
	Annual quantity     Unit cost, $      cost, $
              Direct Costs
Delivered raw material
  Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
  Operating labor & supervision
  including payroll overhead
Utilitiesb
  Fuel oil (drying)
  Sluice water
  Electricity
   Receiving-drying
   Grinding
   Injection
   Dust collection (credit)
   Solids disposal
Maintenance
  Labor and material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
Analyses
  Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
  of initial fixed investment
Overhead
  Plant, 20% of conversion costs
  Administrative, 10% of operating labor
  Subtotal indirect costs
  Average annual operating cost
   for dry limestone injection
  Thermal effect of dry limestone injection
   on operating cost of power plant
                                            129,300 gal
                                            267,000 M gal

                                            146,400 kWh
                                          1,303,000 kWh
                                            234,200 kWh
                                           -176,500 kWh
                                            514,000 kWh
        .11/gal
        .03/M gal

       .007/kWh
       .007/kWh
       .007/kWh
       .007/kWh
       .007/kWh
                                                 90 hr
      10.00/hr
                         98.800
                         98,800
 60,400

 14,200
  8,000

  1,000
  9,100
  1,600
 (1,200)
  3,600
 32,100
  6,300
    900
136,000
234,800
                                                                              225,300

                                                                                27,200
                                                                                 6.000
                                                                              258,500

                                                                              493,300

                                                                                 8,300
Total
                                                     Cost/ton
                                                      of coal
                                                     burned.$
                     Total annual
                        cost.S	
±.11
                                                                              501.600
aBasis:
      Coal burned-293,800 tons/yr; .784 Ibs/kWh
      Remaining life of power plant-15 yi
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      O" x I'/z limestone ground to 80% minus 400 mesh
      Capital investment, $1,280,100
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                        L-149
         Table A-59 Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                (150-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       4.0 Moles CaO Injected per Mole S in  Fuel;
                          6.20 Tons Dry Limestone per Hour)
                                                                            Total annual
	.	Annual quantity    Unit cost, $     cost, $
             Direct Costs
Delivered raw material
  Limestone (95% CaC03)
  Subtotal raw material
   32,700 tons      4.05/ton
                  132.400
                  132,400
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
 Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry  limestone injection
 Thermal  effect of dry limestone injection
  on operating cost of power plant
Total
   10,070 man-hr   6.00/man-hr
  173,300 gal
  267,000 M gal

  196,200 kWh
1,746,200 kWh
  313,900 kWh
 -173,500 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      100hr
10.00/hr
                                                      Cost/ton
                                                       of coal
                                                     burned.$
 60,400

 19,100
  8,000

  1,400
 12,200
  2,200
 (1,200)
  3,600
 36,100
  6,800
  1,000
149,600
282,000
                                    252,000

                                     29,900
                                       6.000
                                    287,900

                                    569,900

                                     11,000


                                 Total annual
                                    cost. $
              1.97
                 580.900
""Basis:
      Coal burned-294,300 tons/yr; .785 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      O" x 1%" limestone ground to 80% minus 400 mesh
      Capital investment, $1,431,500
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
.      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                         L-150
          Table A-60Average Annual Operating Cost for Reducing SO2 Emission
_fromJPgwer Plants by Dry Limestone Injection—Regulated Power Company Economics3
                 (150-MW  Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       5.0 Moles CaO Injected per Mole S in Fuel;
                           7.76 Tons Dry Limestone per Hour)
                                                                            Total annual
       .	Annual quantity     Unit cost, $      cost, $
              Direct Costs
Delivered raw material
  Limestone (95% CaC03)
   Subtotal raw material
   40,900 tons      4.05/ton
                  165.600
                  165,600
Conversion costs
 Operating labor & supervision
   including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
   Receiving-drying
   Grinding
   Injection
   Dust collection (credit)
   Solids disposal
Maintenance
  Labor and material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
   for dry limestone injection
 Thermal effect of dry limestone injection
   on operating cost of  power plant
Total
   10,070 man-hr   6.00/man-hr
  216,800 gal
  267,000 M gal

  245,400 kWh
2,184,100kWh
  392,600 kWh
 -168,000 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      120hr
10.00/hr
                                                      Cost/ton
                                                       of coal
                                                      burned, $
 60,400

 23,800
  8,000

  1,700
 15,300
  2,700
  (1,200)
  3,600
 39,900
  7,200
  1.200
162,600
328,200
                                     276,100

                                      32,500
                                       6.000
                                     314,600

                                     642,800

                                      13,800


                                  Total annual
                                     cost, $
              2.23
                 656,600
aBasis:
      Coal burned-294,700 tons/yr; .786 Ibs/kWh
      Remaining life of power plant-15 yi
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      O" x IVi  limestone ground to 80% minus 400 mesh
      Capital investment, $1,568,800
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection to limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                        L-151
         Table A-6lAverage Annual Operating Cost for Reducing SO2
jromJPower Plants by Dry Limestone
                                                                     Emission
                                                                          ^
                (150-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       6.0 Moles CaO Injected per Mole S in Fuel;
                          9.33 Tons Dry Limestone per Hour)
                                                                            Total annual
                       	.__^^Q]Ja.!jayantity_	Uoitcpst^S	cost, $	
             Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
                                             49,100 tons      4.05/ton
                                             10,070 man-hr   6.00/man-hr
                                           260,200 gal
                                           267,000 M gal

                                           294,600 kWh
                                          2,621,900 kWh
                                           471,400kWh
                                           -165,000 kWh
                                           514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
                                                130hr
10.00/hr
Total
                                                     Cost/ton
                                                      of coal
                                                     burned, $	
                                                       2.47
                  198,900
                  198,900
 60,400

 28,600
  8,000

  2,100
 18,400
  3,300
  (1,200)
  3,600
 43,300
  7,500
  1,300
175,300
374,200
                  298,200

                   35,100
                 __6,QOO
                  339,300

                  713,500

                   16,600


               Total annual
                 730,100
aBasis:
      Coalburned-295,100 tons/yr; .787 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      O" x 1%" limestone ground to 80% minus 400 mesh
      Capital investment, $1,694,400
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection to limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
,      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                        L-152
          Table A-62Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3	
                 (150-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       7.0 Moles CaO Injected per Mole S in Fuel;
                          10.90 Tons Dry Limestone per Hour)
                                                                            Total annual
         	            Annual quantity    Unjt^gstJiL—__costt_$.	
              Direct Costs
Delivered raw material
 Limestone (95%CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
Total
aBasis:
   57,400 tons      4.05/ton
   10,070 man-hr   6.00/man-hr
  304,200 gal
  267,000 M gal

  344,400 kWh
3,065,200 kWh
  551,OOOkWh
  161,500kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      150hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned.S
                  232,500
                  232,500
 60,400

 33,500
   8,000

   2,400
 21,500
   3,900
  (1,100)
   3,600
 46,500
  7,700
  1,500
187,900
420,400
                                    318,200

                                      37,600
                                       6,000
                                    361,800

                                    782,200

                                      19,300


                                  Total annual
                                    cost. S
             2.71
                 801,500
      Coal burned-295,600 tons/yr; .788 Ibs/kWh
      Remaining life of power plant-! 5 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      O" x 1V4" limestone ground to 80% minus 400 mesh
      Capital investment, $1,808,000
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1  mile from power unit.
      Cost of solids disposal pond not included.
BCost of utility supplied from power plant at full value.

-------
                                         L-153
          Table A-63Average Annual Operating Cost for Reducing SO2  Emission
  from Power Plants by Dry Limestone Injection-Regulated Power Company Ecgnmrijcsg_
                 (250-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                          7.73 Tons Dry Limestone per  Hour)
                                                                            Total annual
                             	Annual quantity     Unit cost, $      cost,_$__
              Direct Costs
 Delivered raw material
  Limestone (95% CaC03)
   Subtotal raw material
 Conversion costs
  Operating labor & supervision
   including payroll overhead
 Utilities'^
  Fuel oil  (drying)
  Sluice water
  Electricity
   Receiving-drying
   Grinding
   Injection
   Dust collection  (credit)
   Sol ids disposal
 Maintenance
  Labor and  material
   Drying, grinding, injection, and solids
    disposal  areas
   Dust collection
 Analyses
  Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
 Average capital charges at 17.6%
  of initial fixed  investment
 Overhead
  Plant, 20% of conversion costs
  Administrative, 10% of operating labor
  Subtotal indirect costs
  Average annual operating cost
   for dry limestone injection
  Thermal effect of dry  limestone injection
   on operating cost of power plant
Total
   40,700 tons      4.05/ton
   10,070 man-hr   6.00/man-hr
  215,700 gal
  267,000 M gal

  244,200 kWh
2,173,400 kWh
  390,700 kWh
 -294,000 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      120hr
10.00/hr
                                                      Cost/ton
                                                       of coal
                                                     burned,$
                  164.800
                  164,800
 60,400

 23,700
  8,000

  1,700
 15,200
  2,700
  (2,100)
  3,600
 41,000
  9,900
  1.200
165,300
330,100
                                    298,300

                                     33,100
                                       6.000
                                    337,400

                                    667,500

                                     13,800
                                 Total annual
                                    cost, $
              1.39
                 681,300
      Coal burned-489,700 tons/yr; .784 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x I'/z limestone ground to 80% minus 400 mesh
      Capital investment, $1,695,100
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1  mile from power unit.
,      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                        L-154
          TableA-6l4Average Annual Operating Cost for Reducing SO2 Emission
 from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
                 (250-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       4.0 Moles CaO Injected per Mole S in Fuel;
                          10.33'Tons Dry Limestone per Hour)
                                                                            Total annual
 	Annual quantity    Unit cost, $     cost, $
              Direct Costs
Delivered raw material
 Limestone (95% CaC03}
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection  (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
Total
   54,400 tons
 4.05/ton
   10,070 man-hr   6.00/man-hr
  288,300 gal
  267,000 M gal

  326,400 kWh
2,905,000 kWh
  522,200 kWh
 -287,500 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      140hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned. $
220,300
220,300
 60,400

 31,700
  8,000

  2,300
 20,300
  3,700
  (2,000)
  3,600
 45,600
 10,400
   1.400
185,400
405,700
                                     328,800

                                      37,100
                                       6.000
                                     371,900

                                     777,600

                                      18,400


                                  Total annual
                                     cost, $
              1.62
                 796,000
      Coal burned-490,400 tons/yr; .785 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      MnJwestj>lantlocation-1972 costs
      O" x IVi  limestone ground to 80% minus 400 mesh
      Capital investment, $1,868,100
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1  mile from power unit.
      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                        L-155
          TableA-65 Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection-Regulated Power Company Economicsa
                (250-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       5.0 Moles CaO Injected per Mole S in Fuel;
                          12.93 Tons Dry Limestone per Hour)
             Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion  costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal  effect of dry limestone injection
  on operating cost of power plant
                                          _Annual quantity    U_njt_cost. $
   68,100 tons      4.05/ton
               Total annual
                 cost, $


                 .275,800
                 275,800
   10,070 man-hr   6.00/man-hr      60,400
  360,900 gal
  267,000 M gal

  408,600 kWh
3,636,500 kWh
  653,800 kWh
 -280,000 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      160 hr
10.00/hr
Total
                                                      Cost/ton
                                                       of coal
                                                     burned, $
 39,700
  8,000

  2,900
 25,500
  4,600
  (2,000)
  3,600
 51,600
 11,000
   1,600
206,900
482,700
                                    367,200

                                      41,400
                                       6.000
                                    414,600

                                    897,300

                                      23,000
                                  Total annual
                                     cost, $
              1.87
                 920,300
aBasis:
      Coal burned-491,200 tons/yr; .786 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x 1%" limestone ground to 80% minus 400 mesh
      Capital investment, $2,086,100
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1  mile from power unit.
,      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                         L-156
          Table A-6£Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
                 (250-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       6.0 Moles CaO Injected per Mole S in  Fuel;
                          15.55 Tons Dry Limestone per  Hour)
                                                                            Total annual
	Annual quantity    Unit cost, $      cost, $
              Direct Costs
Delivered raw material
  Limestone (95% CaC03)
  Subtotal raw material
   81,900 tons      4.05/ton
                  331,700
                 "331,700
Conversion costs
 Operating labor & supervision
   including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
   Receiving-drying
   Grinding
   Injection
   Dust collection (credit)
   Solids disposal
Maintenance
 Labor and material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
   for dry limestone injection
 Thermal effect of dry  limestone injection
   on operating cost of  power plant
   10,070 man-hr   6.00/man-hr
  434,100 gal
  267,000 M gal

  491,400kWh
4,373,500 kWh
  786,200 kWh
 -275,000 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      180 hr
10.00/hr
Total
                                                      Cost/ton
                                                       of coal
                                                     burned.$
  60,400

  47,800
   8,000

   3,400
  30,600
   5,500
  (1,900)
   3,600
  56,100
  11,500
	1,800
 226,800
 558,500
                                     396,600

                                      45,400
                                       6.000
                                     448,000

                                   1,006,500

                                      27,600
                                  Total annual
                                     cost. $	
              2.10
                1,034,100
aBasis:
      Coal burned-491,900 tons/yr; .787 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time—5000 hr/yr
      Midwest plant location-1972 costs
      0" x Wi' limestone ground to 80% minus 400 mesh
      Capital investment, $2,253,600
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.      Solids disposed as 15% slurry with no recycle of pond
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1  mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                         L-157

          Table A-67Average Annual Operating Cost for Reducing SO2 Emission
_jrom Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                 (250-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       7.0 Moles CaO Injected per Mole S in Fuel;
                          18.17 Tons  Dry Limestone per Hour)
                                                                            Total annual
	Annual quantity    Unit cost, $      cosi, j>	
              Direct Costs
Delivered raw  material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor  & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
   Receiving-drying
  Grinding
   Injection
   Dust col lection (credit)
  Solids disposal
Maintenance
 Labor and material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual  operating cost
   for dry limestone injection
 Thermal effect of dry limestone injection
   on operating cost of  power plant
   95,700 tons      4.05/ton
   10,070 man-hr   6.00/man-hr
  507,200 gal
  267,000 M gal

  574,200 kWh
5,110,400kWh
  918,700 kWh
 -269,000 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      200 hr
10.00/hr
                 387,600
                 "387,600
  60,400

  55,800
   8,000

   4,000
  35,800
   6,400
  (1,900)
   3,600
  60,300
  11,900
	2.000
 246,300
 633,900
                                                      Cost/ton
                                                       of coal
                                                      burned,$
                                     423,800

                                      49,300
                                       6.000
                                     479,100

                                   1,113,000

                                      32,200


                                  Total annual
                                     cost. $
 Total
              2.32
                1,145,200
 "Basis:
      Coal burned-492,600 tons/yr; .788 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yi
      Midwest plant location-1972 costs
      0" x 11A" limestone ground to 80% minus 400 mesh
      Capital investment, $2,407,700                                                      _
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection ot limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water
      Disposal pond located 1 mile from power unit.
 ,     Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                        L-158
          TableA-68 Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                 (350-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                          10.83 Tons Dry Limestone per Hour)
                                                                           Total annual
 	Annual quantity    Unit cpsj, $	jcost, $
              Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection  (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
   57,000 tons      4.05/ton
   10,070 man-hr   6.00/man-hr
  302,100 gal
  267,000 M gal

  342,000 kWh
3,043,800 kWh
  547,200 kWh
 -411,600kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      150hr
10.00/hr
Total
                                                     Cost/ton
                                                      of coal
                                                     burned.$
                  230,900
                 "230900
 60,400

 33,200
  8,000

  2,400
 21,300
  3,800
  (2,900)
  3,600
 48,100
 12,900
   1,500
192,300
422,300
                                     357,700

                                      38,500
                                       6.000
                                     402,200

                                     824,500

                                      19,300


                                  Total annual
                                     cost. $
              1.23
                 843,800
aBasis:
      Coal burned-685,600 tons/yr; .784 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x \Vi" limestone ground to 80% minus 400 mesh
      Capital investment, $2,032,300
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                        L-159
          Table A-69Average Annual Operating Cost for Reducing SO, Emission
 Jrom Power Plants by Dry Limestone Injection-Regulated Power Company Economics8
                (350-MW Existing Coal-Fired Power Unit; 0.8% S in fuel-
                       4.0 Moles CaO Injected per Mole S in  Fuel;
                          14.47 Tons Dry Limestone per Hour)

                                           Annual quantity    Unit cost $
             Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion  costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
                                  Total annual
                                    cost, $
   76,200 tons      4.05/ton
   10,070 man-hr   6.00/man-hr
  403,900 gal
  267,000 M gal

  457,200 kWh
4,069,100 kWh
  731,500kWh
 -402,500 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      170hr
10.00/hr
                                                      Cost/ton
                                                      of coal
                                                     burned, $
                  308.600
                  308,600
 60,400

 44,400
  8,000

  3,200
 28,500
  5,100
  (2,800)
  3,600
 54,800
 13,600
   1,700
220,500
529,100
                                    401,100

                                      44,100
                                       6.000
                                    451,200

                                    980,300

                                      25,700


                                  Total annual
                                    cost. $
Total
              1.47
                1,006,000
dBasis:
      Coal burned-686,600 tons/yr; .785 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x VA" limestone ground to 80% minus 400 mesh
      Capital investment, $2,278,800
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids  disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                         L-160
          Table A-70Average Annual Operating Cost for Reducing S02 Emission
 Jrqm Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
                 (350-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       5.0 Moles CaO Injected per Mole S in Fuel;
                          18.11 Tons Dry Limestone per Hour)
                                                                            Total annual
	Annual quantity    Unit cost, $      cost, $
              Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
   95,300 tons      4.05/ton
                  386.000
                  386,000
Conversion costs
 Operating labor & supervision
   including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
   Receiving-drying
   Grinding
   I njection
   Dust collection (credit)
   Solids disposal
Maintenance
 Labor and  material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
Analyses
  Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
   for dry limestone injection
 Thermal effect of dry limestone injection
   on operating cost of power plant
Total
   10,070 man-hr   6.00/man-hr
  505,100 gal
  267,000 M gal

  571,800kWh
5,089,000 kWh
  914,900 kWh
 -392,000 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      200 hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned,$
              1.69
 60,400

 55,600
   8,000

   4,000
 35,600
   6,400
  (2,700)
   3,600
 60,700
 14,400
  2.000
248,000
634,000
                                    440,600

                                      49,600
                                       6.000
                                    496,200

                                   1,130,200

                                      32,200


                                  Total annual
                                    cost, $
                1,162,400
aBasis:
      Coal burned -687,600 tons/yr; .786 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x IVz limestone ground to 80% minus 400 mesh
      Capital investment, $2,503,200
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                            114,600 tons      4.05/ton
                                             10,070 man-hr   6.00/man-hr
                                        L-161

         Table A-71 Average Annual Operating Cost for Reducing S02 Emission
__fromPower Plants by Dry Limestone Injection-Regulated Power Company Economics3
                (350-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       6.0 Moles CaO Injected per Mole S in  Fuel;
                          21.77 Tons Dry  Limestone per Hour)
                                                                            Total annual
	Annual quantity    Unit cost. $     cost. S
             Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal  direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs

 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
                                            607,400 gal
                                            267,000 M gal

                                            687,600 kWh
                                          6,119,600kWh
                                          1,100,200 kWh
                                           -385,000 kWh
                                            514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
                                                220 hr
10.00/hr
                  464,100
                  464,100
 60,400

 66,800
  8,000

  4,800
 42,800
  7,700
  (2,700)
  3,600
 66,200
 15,000
  2.200
274,800
738,900
                                                                               476,600

                                                                                55,000
                                                                                 6.000
                                                                               537,600
                                                                             1,276,500

                                                                                38,600
Total
                                                      Cost/ton
                                                       of coal
                                                     burned. $
                                                                            Total annual
                                                                               cost, $
                                                        1.91
                1,315,100
"Basis:
      Coal burned-688,600 tons/yr; .787 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yi
      Midwest plant location-1972 costs
      0" x 1V4" limestone ground to 80% minus 400 mesh
      Capital investment, $2,707,700
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                         L-162
          TableA-72 Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
                 (350-MW Existing Coal-Fired Power Unit; 0.8% S in fuel;
                       7.0 Moles CaO Injected per Mole S in Fuel;
                          25.43 Tons Dry Limestone per Hour)
                                                                            Total annual
                    	          	Annual quantity    Unit cost, $     cost, $
              Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  I njection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and  material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed  investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
Total
  133,900 tons      4.05/ton
   11,720 man-hr   6.00/man-hr
  709,700 gal
  267,000 M gal

  803,400 kWh
7,150,300 kWh
1,285,400 kWh
 -376,600 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      240 hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned.$
              2.14
                  542.300
                  542,300
 70,300

 78,100
  8,000

  5,600
 50,100
  9,000
  (2,600)
  3,600
 71,300
 15,500
  2.400
311,300
853,600
                                     509,200

                                      62,300
                                       7,000
                                     578,500

                                   1,432,100

                                      45,000


                                  Total annual
                                     cost, $
                1,477,100
aBasis:
      Coal burned-689,600 tons/yr; .788 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      O" x \V" limestone ground to 80% minus 400 mesh
      Capital investment, $2,893,300
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone.
       Dust collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1  mile from power unit.
      Cost of solids disposal pond not included.
DCost of utility supplied from power plant at full value.

-------
                                        L-163
         Table A-73Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection—Regulated Power Company Economics8
~                (50-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
                       1.0 Moles CaO Injected per Mole S in Fuel;
                           1.93 Tons Dry Limestone per  Hour)
                                                                            Total annual
   	Annual quantity    Unit cost, $      cost, $
~~~"Direct Costs
Delivered raw material
  Limestone (95% CaC03)
  Subtotal raw material
 10,200 tons     4.05/ton
                   41.300
                   41,300
Conversion costs
 Operating labor & supervision
   including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
   Receiving-drying
   Grinding
   Injection
   Dust collection  (credit)
   Solids disposal
Maintenance
 Labor and material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
   for dry limestone injection
 Thermal effect of dry limestone injection
   on operating cost of power plant
 10,070 man-hr   6.00/man-hr
 54,100 gal
267,000 M gal

 61,200kWh
544,700 kWh
 97,000 kWh
 -57,000 kWh
514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      50 hr
10.00/hr
 Total
 "Basis:
                                                      Cost/ton
                                                       of coal
                                                      burned, $
 60,400

  6,000
  8,000

    400
  3,800
    700
   (400)
  3,600
 21,700
  2,800
    500
107,500
148,800
                                   143,800

                                    21,500
                                     6.000
                                   171,300

                                   320,100

                                     3,000


                                Total annual
                                   cost, $
            3.30
                 323,100
      Coal burned-98,000 tons/yr; .784 Ibs/kWh
      Remaining life of power plant—15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x P/2 limestone ground to 80% minus 400 mesh
      Capital investment, $817,100                                   .    .  .  t.   *!•„,,„,*„„„ n,,ct
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of l™«tane- Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
bCost of utility supplied from power plant at full value.

-------
                                         L-164
          Table A-T^Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                 (50-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
                       2.0 Mojes CaO Injected per Mole S in Fuel;
                          3.89 Tons Dry Limestone per Hour)
              Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed  investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
Total
                                          Annual quantity    Unit cost. $
   20,500 tons      4.05/ton
   10,070 man-hr   6.00/man-hr
                                  Total annual
                                    cost, $	
                   83.000
  108,700 gal
  267,000 M gal

  123,000 kWh
1,094,700 kWh
  196,800 kWh
  -52,500 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
       80 hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned.$
                                      83,000
 60,400

 12,000
  8,000

    900
  7,700
  1,400
   (400)
  3,600
 28,800
  3,300
    800
126,500
209,500
                                     188,400

                                      25,300
                                       6,000
                                     219,700

                                     429,200

                                       5,900


                                  Total annual
                                     cost,$
             4.42
                 435,100
"Basis:
      Coal burned-98,400 tons/yt; .788 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant locatkm-1972 costs
      0" x W-i limestone ground to 80% minus 400 mesh
      Capital investment, $1,070,500
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                        L-165
         Table A-7 5 Average Annual Operating Cost for Reducing S02 Emission
 from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3	
                 (50-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
                      3.0 Moles CaO Injected per Mole S in Fuel;
                         5.87 Tons Dry Limestone per Hour)
                                                                          Total annual
               	Annual quantity    Unit cost, $      cost, $
             Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
   Receiving-drying
   Grinding
   Injection
   Dust collection (credit)
   Solids disposal
Maintenance
  Labor and material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
Analyses
  Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
  of initial fixed investment
Overhead
  Plant, 20% of conversion costs
  Administrative, 10% of operating labor
  Subtotal indirect costs
  Average annual operating cost
   for dry limestone injection
  Thermal effect of dry limestone injection
   on operating cost of power plant
 Total
   30,900 tons     4.05/ton
   10,070 man-hr   6.00/man-hr
  163,800 gal
  267,000 M gal

  185,400 kWh
1,650,100 kWh
  296,600 kWh
  -48,800 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      100hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                       5.42
                _125J_00
                 125,100'
 60,400

 18,000
  8,000

  1,300
 11,600
  2,100
   (300)
  3,600
 34,400
  3,700
  1.000
143,800
268,900
                                    223,800

                                     28,800
                                      6.000
                                    258,600

                                    527,500

                                      8,900


                                  Total annual
                                    cost. $	
                                    536,400
 "Basis:
       Coal burned-98,900 tons/yr; .791 Ibs/kWh
       Remaining life of power plant-15 yr
       Power plant on-stream time-5000 hr/yr
       Midwest plant location-1972 costs
       0" x 1%" limestone ground to 80% minus 400 mesh
        collection efficiency
        and electrostatic devices.
       Solids disposed as 15% slurry with no recycle of pond water.
       Disposal pond located 1 mile from power unit.
       Cost of solids disposal pond not included.
 °Cost of utility supplied from power plant at full value.

-------
                                             41,400 tons      4.05/ton
                                             10,070 man-hr   6.00/man-hr
                                        L-166
          Table A-76Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection—Regulated Power Company Economics8
                  (50-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
                       4.0 Moles CaO Injected per Mole S in  Fuel;
                          7.86 Tons Dry Limestone per  Hour)
                                                                            Total annual
	                Annual quantity    Unit cost, $      cost, $	
              Direct Costs
Delivered raw material
  Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
  Operating labor & supervision
  including payroll overhead
Utilities'^
  Fuel oil (drying)
  Sluice water
  Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection  (credit)
  Solids disposal
Maintenance
  Labor and  material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
  Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
  of initial fixed  investment
Overhead
  Plant, 20% of conversion costs
  Administrative, 10% of operating labor
  Subtotal indirect costs
  Average annual operating cost
  for dry limestone injection
  Thermal effect of dry limestone injection
  on operating cost of power plant
                                            219,400 gal
                                            267,000 M gal

                                            248,400 kWh
                                          2,210,800 kWh
                                            379,400 kWh
                                             -46,000 kWh
                                            514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
                                                120hr
10.00/hr
                                                                               167,700
 60,400

 24,100
  8,000

  1,700
 15,500
  2,700
    (300)
  3,600
 39,300
  4,000
  1.200
160,200
327,900
lolal
                                                     Cost/ton
                                                      of coal
                                                     burned,$
                  253,800

                   32,000
                    6.000
                  291,800

                  619,700

                   12,000


               Total annual
                  cost, $
                                                       6.36
                 631 700
aBasis:
      Coal burned-99,400 tons/yr; .795 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yt
      Midwest plant location-197 2 costs
      0" x IVz limestone ground to 80% minus 400 mesh
      Capital investment, $1,442,000
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                         L-167

          Table A-77 Average Annual Operating Cost for Reducing S02  Emission
  from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                 (150-MW  Existing Coal-Fired Power Unit; 3.0% S in fuel;
                        1.0 Moles CaO I njected  per Mole S in Fuel;
                           5.80 Tons Dry Limestone per Hour)

___	Annual quantity     Unit cost, $
              Direct Costs
Delivered raw material
  Limestone (95% CaC03)
   Subtotal raw material
                                 Total annual
                                    cost, $
   30,600 tons      4.05/ton
Conversion costs
  Operating labor & supervision
   including payroll overhead
Utilitiesb
  Fuel oil (drying)
  Sluice water
  Electricity
   Receiving-drying
   Grinding
   Injection
   Dust collection (credit)
   Solids disposal
Maintenance
  Labor and  material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
Analyses
  Subtotal conversion costs
  Subtotal direct costs

             indirect Costs
Average capital charges at 17.6%
  of initial fixed investment
Overhead
  Plant, 20% of conversion costs
  Administrative, 10% of operating labor
  Subtotal indirect costs
  Average annual operating cost
   for dry limestone injection
  Thermal effect of dry  limestone injection
   on operating cost of power plant
Total
                  123.900
                  123,900
   10,070 man-hr   6.00/man-hr      60,400
  162,200 gal
  267,000 M gal

  183,600 kWh
1,634,000 kWh
  293,800 kWh
 -171,OOOkWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      100hr
10.00/hr
                                                      Cost/ton
                                                       of coal
                                                     burned,$
 17,800
  8,000

  1,300
 11,400
  2,100
  (1,200)
  3,600
 35,200
  6,900
  1.000
146,500
270,400
                                    247,200

                                     29,300
                                      6.000
                                    282,500

                                    552,900

                                      8,900


                                 Total annual
                                    cost, $
             1.91
                 561,800
      Coal burned-293,900 tons/yr; .784 Ibs/kWh
      Remaining life of power plant^-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x 1% limestone ground to 80% minus 400 mesh
      Capital investment, $1,404,600
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1  mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full Value.

-------
                                        L-170
          Table A-80 Average Annual Operating Cost for Reducing S02 Emission
  from Power Plants by Dry Limestone Injection—Regulated Power Company Economics8
                 (150-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
                       4.0 Moles CaO Injected per Mole S in Fuel;
                          23.59 Tons  Dry Limestone per Hour)
                                                                            Total annual
	Annual quantity    Unit cost, $     cost, $
             Direct Costs
Delivered raw material
  Limestone (95% CaC03)
  Subtotal raw material
  124,200 tons      4.05/ton
                  503.000
                  503,000
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and  material
  Drying, grinding, injection, and solids
    disposal  areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
Total
   10,070 man-hr   6.00/man-hr
  658,300 gal
  267,000 M gal

  745,200 kWh
6,632,300 kWh
1,192,300 kWh
 -138,000 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      230 hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned, $
 60,400

 72,400
  8,000

  5,200
 46,400
  8,300
  (1,000)
  3,600
 67,400
  9,800
  2.300
282,800
785,800
                                     453,100

                                      56,600
                                    	6JQQO
                                     515,700

                                   1,301,500

                                      35,800


                                  Total annual
                                     cost,$	
             4.48
                1,337,300
aBasis:
      Coal burned-298,200 tons/yr; .795 Ibs/kWh
      Remaining life of power plant^lS yr
      Power plant on-stream time-5000 hr/yt
      Midwest plant location-1972 costs
      0" x Wi" limestone ground to 80% minus 400 mesh
      Capital investment, $2,574,200
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond Water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                        L-171
          Table A-SlAverage Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Inject ion-Regulated Power Company Economic^
                 (250-MW Existing Coal-Fired Power Unit; 3.0% S in fuel-
                       1.0 Moles CaO Injected per Mole S in  Fuel;
                          9.67 Tons Dry Limestone per Hour)
                                           Annual quantity    Unit cost, $
                                 Total annual
                                 	cost, $
             Direct Costs
Delivered raw material
 Limestone (95% CaCO3)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection  (credit)
  Sol ids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal  effect of dry limestone injection
  on operating cost of power plant
Total
   50,900 tons      4.05/ton
   10,070 man-hr   6.00/man-hr
  269,800 gal
  267,000 M gal

  305,400 kWh
2,718,100 kWh
  488,600 kWh
 -285,000 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 ,007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      140hr
10.00/hr
                                                      Cost/ton
                                                       of coal
                                                     burned, $
                                    206,100
 60,400

 29,700
  8,000

  2,100
 19,000
  3,400
  (2,000)
  3,600
 45,400
 10,600
   1.400
181,600
387,700
                                    328,300

                                     36,300
                                       6.000
                                    370,600

                                    758,300

                                      14,800


                                  Total annual
                                    cost, $
              1.58
                 773,100
aBasis:
      Coal burned-489,900 tons/yr; .784 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest giant location-1972 costs
      0" x 1%  limestone ground to 80% minus 400 mesh
      Capital investment, $1,865,600
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                        L-174
          Table A-8U Average Annual Operating Cost for Reducing S02 Emission
  from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                 (250-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
                       4.0 Moles CaO Injected per Mole S in Fuel;
                          39.32 Tons Dry Limestone per Hour)
                                                                           Total annual
	Annual quantity    Unit cost, $     cost, $
              Direct Costs
Delivered raw material
  Limestone (95% CaC03)
   Subtotal raw material
   207,000 tons      4.05/ton
                  838.400
                  838,400
Conversion costs
 Operating labor & supervision
   including payroll overhead
Utilities^
 Fuel oil (drying)
 Sluice water
 Electricity
   Receiving-drying
   Grinding
   Injection
   Dust collection (credit)
   Solids disposal
Maintenance
 Labor and material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed  investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
   for dry limestone injection
 Thermal effect of dry limestone injection
   on operating cost of power plant
Total
    11,720 man-hr   6.00/man-hr
 1,097,100 gal
   390,000 M gal

 1,242,000 kWh
11,053,800 kWh
 1,987,200 kWh
  -230,000 kWh
   750,800 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
       320 hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned.$
   70,300

  120,700
   11,700

    8,700
   77,400
   13,900
   (1,600)
    5,300
   89,800
   15,100
    3.200
  414,500
1,252,900
                                     615,600

                                       82,900
                                        7,000
                                     705,500

                                    1,958,400

                                       59,700
                                  Total annual
                                     cost. $
              4.06
                2.018.100
      Coal burned-497,000 tons/yr; .795 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x IVi' limestone ground to 80% minus 400 mesh
      Capital investmen-t, $3,498,000
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                         L-175
         Table A-8 5 Average Annual Operating Cost for Reducing S02 Emission
 jrom_Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                (350-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
                       1.0 Moles CaO Injected per Mole S in Fuel;
                          13.53 Tons Dry Limestone per Hour)
                                          Annual quantity    Unit cost, $
                                 Total annual
                                    cost, $
             Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilities*5
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
Total
   71,200 tons      4.05/ton
   10,070 man-hr   6.00/man-hr
  377,400 gal
  267,000 M gal

  427,200 kWh
3,802,100 kWh
  683,500 kWh
 -399,000 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      170hr
10.00/hr
                                                      Cost/ton
                                                       of coal
                                                     burned,$
                 288.400
                 288,400
 60,400

 41,500
  8,000

  3,000
 26,600
  4,800
  (2,800)
  3,600
 53,400
 13,800
   1.700
214,000
502,400
                                    394,000

                                      42,800
                                       6.000
                                    442,800

                                    945,200

                                      20,700


                                  Total annual
                                    cost, $
              1.41
                 965,900
      Coal burned-685,800 tons/yr; .784 Ibs/kWh
      Remaining life of power plant—15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x 1V4 Hmestone ground to 80% minus 400 mesh
      Capital investment, $2,238,600
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection ot limestone, uust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water
      Disposal pond located 1 mile from power unit.
.      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                         L-178
          TableA-88 Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                 (350-MW Existing Coal-Fired Power Unit; 3.0% S in fuel;
                       4.0 Moles CaO Injected per Mole S in Fuel;
                          55.04 Tons Dry Limestone per Hour)
                                                                           Total annual
	Annual quantity    Unit cost, $     cost, $
              Direct Costs
Delivered raw material
  Limestone (95% CaCO3)
  Subtotal raw material
   289,700 tons      4.05/ton
                1.173.300
                1,173,300
Conversion costs
 Operating labor & supervision
   including payroll overhead
Utilities0
 Fuel oil (drying)
 Sluice water
 Electricity
   Receiving-drying
   Grinding
   Injection
   Dust col lection (credit)
   Solids disposal
Maintenance
 Labor and material
   Drying, grinding, injection, and solids
    disposal areas
   Dust col lection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
   for dry limestone injection
 Thermal effect of dry limestone injection
   on operating cost of power plant
Total
    13,370 man-hr   6.00/man-hr
 1,535,400 gal
   570,000 M gal

 1,738,200 kWh
15,470,000 kWh
 2,781,100 kWh
  -322,000 kWh
 1,097,300 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
       390 hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned.$
   80,200

  168,900
   17,100

   12,200
  108,300
   19,500
   (2,300)
    7,700
  108,200
   19,700
    3.900
  543,400
1,716,700
                                      750,100

                                      108,700
                                        8.000
                                      866,800

                                    2,583,500

                                       83,600
                                   Total annual
                                      cost. $
              3.83
                2,667,100
aBasis:
      Coal burned-695,800 tons/yr; .795 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time—5000 hr/yr
      Midwest plant location-1972 costs
      0" x IVz limestone ground to 80% minus 400 mesh
      Capital investment, $4,262,100
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water
      Disposal pond located 1  mile from power unit.
      Cost of solids disposal pond not included.
DCost of utility supplied from power plant at full value.

-------
                                        L-179
         Table A-89 Average Annual Operating Cost for Reducing SO2 Emission
 from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                 (50-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
                       1.0 Moles CaO Injected per Mole S in Fuel;
                           3.2 Tons Dry Limestone per Hour)

                              	Annual quantity    Unit cost, $
                                Total annual
                                  cost, $
             Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
   disposal areas
  Dust collection
Analyses
 Subtotal conversion  costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal  effect of dry limestone injection
  on operating cost of power plant
Total
 17,000 tons     4.05/ton
 10,070 man-hr   6.00/man-hr
 90,100 gal
267,000 M gal

102,000 kWh
907,800 kWh
163,200 kWh
 -53,500 kWh
514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      70 hr
10.00/hr
                   68.900
                   68,900
60,400

 9,900
 8,000

   700
 6,400
 1,100
  (400)
 3,600
26,700
 3,200
   700
                                                     Cost/ton
                                                      of coal
                                                     burned,$
                                   120,300
                                   189,200
                                   175,200

                                    24,000
                                  _ 6000
                                   205,200

                                   394,400

                                     4,900


                                Total annual
                                   cost. $
            4.06
                 399,300
      Coal burned-98,300 toiis/yr; .786 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x I1//' limestone ground to 80% minus 400 mesh
      Capital investment, $995>300
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
      collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
      and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                         L-182
          TableA- 92 Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection  Regulated
                  (50-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
                       4.0 Moles CaO Injected per Mole S in Fuel;
                           13.3 Tons Dry Limestone per  Hour)
                                                                            Total annual
                                           Annual quantity    Unit costf,.$____cgstt_$___
              Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection  (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed  investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry  limestone injection
  on operating cost of  power plant
Iota!
aBasis:
   70,200 tons
 4.05/ton
   10,070 man-hr   6.00/man-hr
  372,100 gal
  267,000 M gal

  421,200kWh
3,748,700 kWh
  673,900 kWh
  -38,500 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      160hr
10.00/hr
            Cost/ton
             of coal
           burned,$
             ~8.72
 284,300
 284,300
  60,400

  40,900
   8,000

   2,900
  26,200
   4,700
    (300)
   3,600
  50,400
   4,800
	1,600.
 203,200
 487,500
                  323,600

                   40,700
                    6.000
                  370,300

                  857,800

                   20,200


               Total annual
                  cost, $
      Coal burned-100,700 tons/yr; .806 Ibs/kWh
      Remaining life of power plant—15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x I'/z' limestone ground to 80% minus 400 mesh
      Capital investment, $1,838,700
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1  mile from power Unit,
      Cost of solids disposal pond not included.
bCost of utility supplied from power plant at full value.

-------
                                         L-183
         Table A-93Average Annual Operating Cost for Reducing SO2 Emission
 from Poy^r_Pl^tsj3^Dry i-imestone Injection-Regulated Power Company Economics3
                (150-MW Existing Coal-Fired Power Unit; 5.0% S in fuel-
                       1.0 Moles CaO I njected per Mole S in Fuel;
                           9.7 Tons Dry Limestone per Hour)
             Direct Costs
Delivered raw material
 Limestone (95% CaCO3)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
   disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal  direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal  effect of dry limestone injection
  on operating cost of power plant
Total
                                                  quantity    Unj^cost $
   51,100 tons      4.05/ton
   10,070 man-hr   6.00/man-hr
  270,800 gal
  267,000 M gal

  306,600 kWh
2,728,700 kWh
  490,600 kWh
 -160,500 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      140hr
10.00/hr
                                 Total annual
                                    cost, $
                 207.000
                 207,000
 60,400

 29,800
  8,000

  2,100
 19,100
  3,400
  (1,100)
  3,600
 44,300
   7,800
   1.400
178,800
385,800
                                    305,600

                                     35,800
                                       6,000
                                                     Cost/ton
                                                      of coal
                                                     burned, $
             2.54
                                    347,400

                                    733,200

                                      14,800


                                  Total annual
                                    cost, $	
                 748,000
      Coal burned-294,800 tons/yr; .786 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x 1%  limestone ground to 80% minus 400 mesh
      Capital 6investment, $1,736,200
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
      collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
      and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                        L-184
          TableA-9^ Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
                 (150-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
                       2.0 Moles CaO Injected per Mole S in Fuel;
                           19.6 Tons Dry Limestone per Hour)
                                                                           Total annual
 	Annual quantity    Unit cost, $     cost, $
              Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection  (credit)
  Solids disposal
Maintenance
 Labor and  material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed  investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
Total
                                           103,100 tons      4.05/ton
                                            10,070 man-hr   6.00/man-hr
                                           546,400 gal
                                           267,000 M gal

                                           618,600 kWh
                                         5,505,500 kWh
                                           989,800 kWh
                                          -142,000 kWh
                                           514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
                                               140 hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned,$
                  417.600
                  417,600
 60,400

 60,100
  8,000

  4,300
 38,500
  6,900
  (1,000)
  3,600
 61,600
  9,500
  1f400
253,300
670,900
                                                                              417,000

                                                                               50,700
                                                                                6.000
                                                                              473,700

                                                                            1,144,600

                                                                               29,900


                                                                           Total annual
                                                                              cost, $
                                                       3.95
                1,174,500
aBasis:
b,
     Coal burned-297,300 tons/yr; .793 Ibs/kWh
     Remaining life of power plant-15 yr
     Power plant on-stream time-5000 hr/yr
     Midwest plant location-1972 costs
     0" x \Vi limestone ground to 80% minus 400 mesh
     Capital investment, $2,369,500
     Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
      collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
      and electrostatic devices.
     Solids disposed as 15% slurry with no recycle of pond water.
     Disposal pond located 1 mile from power unit.
     Cost of solids disposal pond not included.
'Cost of utility supplied from power plant at full value.

-------
                                        L-185
         TableA-95 Average Annual Operating Cost for Reducing SO2 Emission
 from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                (150-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                          29.7 Tons Dry Limestone per Hour)
                                          Annual quantity    Unit cost, $
                                 Total annual
                                    cost, $
             Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
Total
  156,000 tons
    4.05/ton
   11,720man-hr   6.00/man-hr
  827,300 gal
  390,000 M gal

  936,600 kWh
8,335,700 kWh
1,498,600 kWh
 -128,000 kWh
  750,800 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      270 hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned. $
-631J300
 631,800
  70,300

  91,000
  11,700

   6,600
  58,300
  10,500
    (900)
   5,300
  77,100
  10,700
   2.700
 343,300
 975,100
                                    515,100

                                      68,700
                                       7fOOO
                                    590,800

                                   1,565,900

                                      45,100


                                  Total annual
                                    cost.
              5.38
                1,611,000
"Basis:
      Coal burned-299,700 tons/yr; .799 Ibs/kWh
      Remaining life of power plant—15 yr
      Power plant on-stream time—5000 hi/yr
      Midwest plant location-1972 costs
      0" x 1V4 limestone ground to 80% minus 400 mesh
      Capital investment, $2,926,600
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection oi limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                         L-186

          Table A-96Average Annual Operating Cost for Reducing SO2 Emission
  from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
                 (150-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
                       4.0 Moles CaO Injected per Mole S in  Fuel;
                           40 Tons Dry  Limestone per Hour)

Direct Costs
Delivered raw material
Limestone (95% CaC03)
Subtotal raw material
Total annual
Annual quantity Unit cost, $ cost, $
21 0,500 tons 4.05/ton 852.500
852,500
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilities^
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and  material
  Drying, grinding, injection, and solids
    disposal areas
  Dust col lection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
Total
    11,720 man-hr   6.00/man-hr
 1,115,700 gal
   390,000 M gal

 1,263,000 kWh
11,240,700 kWh
 2,020,800 kWh
  -115,500 kWh
   750.800 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
       320 hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned,$
   70,300

  122,700
   11,700

    8,800
   78,700
   14,100
     (800)
    5,300
   89,500
   11,800
    3.200
  415,300
1,267,800
                                      594,200

                                       83,100
                                        7.000
                                      684,300

                                    1,952,100

                                       60,700
                                   Total annual
                                      cost, $
              6.66
                2,012,800
aBasis:
      Coal burned-302,100 tons/yr; .806 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x IVz limestone ground to 80% minus 400 mesh
      Capital investment, $3,376,200
      Incremental electrostatic piecipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1  mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                        L-187
          Table A-97 Average Annual Operating Cost for Reducing SO2 Emission
 jfrom Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                 (250-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
                       1.0 Moles CaO Injected per Mole S in Fuel;
                           16.8 Tons Dry Limestone per Hour)

rect Costs
terial
CaCOs )
later! a I
Annual quantity
85, 100 tons
Unit cost, $
4.05/ton
Total annual
cost, $
344.700
344,700
Delivered raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilities'^
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection  (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal  effect of dry  limestone injection
  on operating cost of  power plant
   10,070 man-hr   6.00/man-hr
  451,000 gal
  267,000 M gal

  510,600 kWh
4,544,300 kWh
  817,000 kWh
 -267,500 kWh
  514,000 kWh
                                                               .11/gal
                                                               .03/M gal

                                                              .007/kWh
                                                              .007/kWh
                                                              .007/kWh
                                                              .007/kWh
                                                              .007/kWh
      190hr
                                                             10.00/hr
                                                      Cost/ton
                                                       of coal
                                                     burned. $
 60,400

 49,600
  8,000

  3,600
 31,800
  5,700
  (1,900)
  3,600
 57,300
 12,100
   1.900
232,100
576,800
                                    407,400

                                      46,400
                                       6,000
                                    459,800

                                   1,036,600

                                      24,600
                                  Total annual
                                     cost. $
                                                        2.16
                                   1,061,200
Total	
aBasis:
      Coal burned-491,400 tons/yr; .786 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location—1972 costs
      0" x 1% limestone ground to 80% minus 400 mesh
      Capital investment, $2,314,500
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1  mile from power unit.
      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                        L-188
          TableA-98 Average Annual Operating Cost for Reducing S02 Emission
  from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
                 (250-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
                       2.0 Moles CaO Injected per Mole S in Fuel;
                          32.7 Tons Dry Limestone per Hour)

                	Annual quantity    Unit cost. $
                                  Total annual
                                    cost. $
              Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection  (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed  investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
Total
  171,900 tons
 4.05/ton
   11,720 man-hr   6.00/man-hr
  911,100 gal
  390,000 M gal

1,031,400 kWh
9,179,500 kWh
1,650,200 kWh
 -236,500 kWh
  750,800 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      280 hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned.$
  696,200
  696.200
   70,300

  100,200
   11,700

    7,200
   64,300
   11,600
   (1,700)
    5,300
   82,000
   14,600
    2.800
  368,300
1,064,500
                                    566,900

                                      73,700
                                       7.000
                                    647,600

                                   1,712,100

                                      49,900
                                  Total annual
                                     cost. $
             3.56
                1.762.000
"Basis:
      Coal burned-495,400 tons/yr; .793 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x IVi" limestone ground to 80% minus 400 mesh
      Capital investment, $3,221,100
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1  mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                         L-189

          TableA-99 Average Annual Operating Cost for Reducing SO, Emission
  from Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                 (250-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
                       3.0 Moles CaO Injected per Mole S in Fuel;
                          49.4 Tons Dry Limestone per Hour)
                                          Annual quantity    Unit cost, $
                                  Total annual
                                     cost, $
              Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and  material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion  costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
Total
   260,200 tons      4.05/ton
    11,720 man-hr   6.00/man-hr
 1,379,100 gal
   570,000 M gal

 1,561,200 kWh
13,894,700 kWh
 2,497,900 kWh
  -213,500 kWh
 1,097,300 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
       360 hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned.$
              4.86
                1.053.800
                1,053,800
   70,300

  151,700
   17,100

   10,900
   97,300
   17,500
   (1,500)
    7,700
  102,600
   16,500
    3.600
  493,700
1,547,500
                                     698,400

                                      98,700
                                        7,000
                                     804,100

                                    2,351,600

                                      75,200


                                  Total annual
                                     cost. $
                2,426,800
aBasis:
      Coal burned-499,400 tons/yr; .799 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x 1V4  limestone ground to 80% minus 400 mesh
      Capital investment, $3,968,400
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                        L-190
         TableA-100 Average Annual Operating Cost for Reducing SOj  Emission
 from Power Plants by Dry Limestone Injection—Regulated Power Company Economics8
                 (250-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
                       4.0 Moles CaO Injected per Mole S in Fuel;
                          66.7 Tons Dry Limestone per Hour)
                                                                           Total annual
 	Annual quantity    Unit cost, $     cost, $
              Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
   Receiving-drying
  Grinding
   Injection
  Dust collection (credit)
  Solids disposal
Maintenance
 Labor and  material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
Total
   350,800 tons      4.05/ton
    13,370 man-hr   6.00/man-hr
 1,859,200 gal
   609,000 M gal

 2,104,800 kWh
18,732,700 kWh
 3,367,700 kWh
  -192,500 kWh
 1,172,300 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
       430 hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned, $
                1.420.700
                1,420,700
   80,200

  204,500
   18,300

   14,700
  131,100
   23,600
   (1,300)
    8,200
  119,300
   18,200
    4.300
  621,100
2,041,800
                                     806,400

                                     124,200
                                        8.000
                                     938,600

                                    2,980,400

                                     101,100
                                   Total annual
                                      cost, $
              6.12
aBasis:
                3,081,500
      Coal burned-503,500 tons/yr; .806 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x l'/2f limestone ground to 80% minus 400 mesh
      Capital investment, $4,582,000
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                         L-191
         Table A-101 Average Annual Operating Cost for Reducing SQ2 Emission
_Jrom Power Plants by Dry Limestone Injection-Regulated Power Company Economics3
                 (350-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
                       1.0 Moles CaO Injected per Mole S in Fuel;
                          22.7 Tons Dry Limestone per Hour)
                                                                           Total annual
 	Annual quantity    Unit cost, $     cost, $
              Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
  119,100 tons      4.05/ton
                 482.400
                 482,400
Conversion costs
 Operating labor & supervision
   including payroll overhead
Utilities^
 Fuel oil (drying)
 Sluice water
 Electricity
   Receiving-drying
   Grinding
   Injection
   Dust collection  (credit)
   Solids disposal
Maintenance
 Labor and material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
   for dry limestone injection
 Thermal effect of dry  limestone injection
   on operating cost of  power plant
Total
   10,070 man-hr   6.00/man-hr
  631,200 gal
  267,000 M gal

  714,600 kWh
6,359,900 kWh
1,143,400 kWh
 -374,500 kWh
  514,000 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
      230 hr
10.00/hr
                                                      Cost/ton
                                                       of coal
                                                      burned.$
 60,400

 69,400
  8,000

  5,000
 44,500
  8,000
  (2,600)
  3,600
 67,800
 15,700
  2.300
282,100
764,500
                                    489,800

                                      56,400
                                       6.000
                                    552,200

                                   1,316,700

                                      34,500


                                  Total annual
                                    cost. $
              1.96
                1,351,200
aBasis:
      Coal burned-688,000 tons/yr; .786 Ibs/kWh
      Remaining life of power plant—15 yr
      Power plant on-stream time—5000 hr/yr
      Midwest plant location-1972 costs
      0" x IVz limestone ground to 80% minus 400 mesh
      Capital investment, $2,782,700
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
,      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                        L-192
         TableA-102Average Annual Operating Cost for Reducing SO2  Emission
  from Power Plants by Dry Limestone Injection—Regulated Power Company Economics3
                 (350-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
                       2.0 Moles CaO Injected per Mole S in Fuel;
                          '45.8 Tons Dry Limestone per Hour)
                                                                           Total annual
	Annual quantity    Unit cost. $     cost. $
              Direct Costs
Delivered raw material
  Limestone (95% CaC03)
  Subtotal raw material
   240,600 tons      4.05/ton
                  974.400
                  974,400
Conversion costs
 Operating labor & supervision
   including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
   Receiving-drying
   Grinding
   Injection
   Dust collection (credit)
   Solids disposal
Maintenance
 Labor and  material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual  operating cost
   for dry limestone injection
 Thermal effect of dry limestone injection
   on operating cost of power plant
Total
    11,720 man-hr   6.00/man-hr
 1,275,200 gal
   570,000 M gal

 1,443,600 kWh
12,848,000 kWh
 2,309,800 kWh
  -331,100 kWh
 1,097,300 kWh
  -11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
       340 hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                    Jjurned,$
              3.33
   70,300

  140,300
   17,100

   10,100
   89,900
   16,200
   (2,300)
    7,700
   98,800
   19,000
    3.400
  470,500
1,444,900
                                     691,200

                                       94,100
                                        7,000
                                     792,300

                                    2,237,200

                                       69,800


                                   Total annual
                                     cost, $
                2,307,000
aBasis:
      Coal burned-693,600 tons/yr; .793 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stieam time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x IVi" limestone ground to 80% minus 400 mesh
      Capital investment, $3,927,000
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                         L-193

        TableA-103 Average Annual Operating Cost for Reducing SO2  Emission
  from Power Plants by Dry Limestone Injection-Regulated Power Comnany Economic
                 (350-MW  Existing Coal-Fired Power Unit; 5.0% S  in fuel-
                       3.0 Moles CaO I njected per Mole S in  Fuel •
                           69.2 Tons Dry Limestone per Hour)
                                           Annual quantity    Unit cost, $
                                  Total annual
                                     cost, $
              Direct Costs
 Delivered raw material
  Limestone (95% CaC03)
   Subtotal raw material
 Conversion costs
  Operating labor & supervision
   including payroll overhead
 Utilitiesb
  Fuel oil (drying)
  Sluice water
  Electricity
   Receiving-drying
   Grinding
   Injection
   Dust collection (credit)
   So I ids disposal
 Maintenance
  Labor and material
   Drying, grinding, injection, and solids
    disposal areas
   Dust collection
 Analyses
  Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
 Average capital charges at 17.6%
  of initial fixed  investment
 Overhead
  Plant, 20% of conversion costs
  Administrative, 10% of operating labor
  Subtotal indirect costs
  Average annual  operating cost
   for dry limestone injection
  Thermal effect of dry  limestone injection
   on operating cost of power plant
   364,300 tons      4.05/ton
    13,370 man-hr   6.00/man-hr
 1,930,800 gal
   630,000 M gal

 2,185,800 kWh
19,453,600 kWh
 3,497,300 kWh
  -298,900 kWh
 1,212,800 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
       440 hr
10.00/hr
Total
                                                      Cost/ton
                                                       of coal
                                                     burned, $
              4.57
                1.475.400
                1,475,400
   80,200

  212,400
   18,900

   15,300
  136,200
   24,500
   (2,100)
    8,500
  121,500
   21,500
    4.400
  641,300
2,116,700
                                     840,600

                                     128,300
                                        8.000
                                     976,900

                                   3,093,600

                                     105,200


                                  Total annual
                                     cost, $
                3,198,800
aBasis:
      Coal burned-699,200 tons/yr; .799 Ibs/kWh
      Remaining life of power plant—15 yr
      Power plant on-stream time-5000 hr/yr
      Midwest plant location-1972 costs
      0" x IVz limestone ground to 80% minus 400 mesh
      Capital investment, $4,766,400
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids  disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
.      Cost of solids disposal pond not included.
 Cost of utility supplied from power plant at full value.

-------
                                        L-194
          Table A-lQl+Average Annual Operating Cost for Reducing SO3 Emission
  from Power Plants by Dry Limestone injection—Regulated Power Company Economics3
                 (350-MW Existing Coal-Fired Power Unit; 5.0% S in fuel;
                       4.0 Moles CaO Injected per Mole S in Fuel;
                          93.3 Tons Dry Limestone per Hour)
                                                                           Total annual
 	Annual quantity    Unit cost, $     cost, $   _
              Direct Costs
Delivered raw material
 Limestone (95% CaC03)
  Subtotal raw material
Conversion costs
 Operating labor & supervision
  including payroll overhead
Utilitiesb
 Fuel oil (drying)
 Sluice water
 Electricity
  Receiving-drying
  Grinding
  Injection
  Dust collection  (credit)
  Solids disposal
Maintenance
 Labor and material
  Drying, grinding, injection, and solids
    disposal areas
  Dust collection
Analyses
 Subtotal conversion costs
  Subtotal direct costs

             Indirect Costs
Average capital charges at 17.6%
 of initial fixed investment
Overhead
 Plant, 20% of conversion costs
 Administrative, 10% of operating labor
 Subtotal indirect costs
 Average annual operating cost
  for dry limestone injection
 Thermal effect of dry limestone injection
  on operating cost of power plant
Total
   491,100 tons     4.05/ton
                1.989.000
                1,989,000
    15,350 man-hr   6.00/man-hr      92,100
 2,602,800 gal
   831,DOOM gal

 2,946,600 kWh
26,224,700 kWh
 4,714,600 kWh
  -269,500 kWh
 1,599,700 kWh
  .11/gal
  .03/M gal

 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
 .007/kWh
       530 hr
10.00/hr
                                                     Cost/ton
                                                      of coal
                                                     burned, $
  286,300
   24,900

   20,600
  183,600
   33,000
    (1,900)
   11,200
  145,700
   23,700
    5,300
  824,500
2,813,500
                                      993,600

                                      164,900
                                        9.200
                                    1,167,700

                                    3,981,200

                                      141,500
                                   Total annual
                                      cost, $
               5.85
                4,122,700
aBasis:
      Coal burned-705,000 tons/yr; .806 Ibs/kWh
      Remaining life of power plant-15 yr
      Power plant on-stream time—5000 hr/yr
      Midwest plant location-1972 costs
      0" x \V" limestone ground to 80% minus 400 mesh
      Capital investment, $5,645,500
      Incremental electrostatic precipitator added to maintain dust emission rate prior to injection of limestone. Dust
       collection efficiency prior to injection of limestone is assumed to be 99% using a combination of mechanical
       and electrostatic devices.
      Solids disposed as 15% slurry with no recycle of pond water.
      Disposal pond located 1 mile from power unit.
      Cost of solids disposal pond not included.
"Cost of utility supplied from power plant at full value.

-------
                                                         Table A-105





DRY LIMESTONc  INJECTION,  REGULATED POWER CO.- ECON., 50 MW  EX.  COAL  FIRED  POWER UNIT, 0.3* S IN FUEL, 3.0  INJECTION  STOICHIOMETRY.




                                                 FIXED INVESTMENT:   $     751500
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KV»-HR/KW M KwH/YR TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
5.- _
6
7
8
9
11
12
13
14
15
16
17
18
19
20.
21
22
23
24
25
26
27
28
29
30.

5000
5000
5 JOO
5000
3500
3500
3500
3_.5.0_.0_
1500
1500
1500
1500

250000
250000
250000
250000
25.QO.flii _
175000
175000
175000
175000
1250.0.0.
75000
75000
75000
75000

97900
97900
97900
97900
212Q2_
68600
6S600
68600
68600
29400
29400
29400
29400
224.00
TOTAL 50000 2500000 979500
EQUIVALENT CCST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IE DISCOUNTED AT 10.0? TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT rtJRTH, DOLLARS PER TON OF COAL bURNED
EQUIVALENT fVEScNT ft'JRTH, 1ILLS PER KILOWATT-HOUR

376200
365800
355400
344900
3_ 2.4.5-0.0.
283000
277600
267200
256700
_24.6.3_QQ. _
180200
169800
159400
143900
13a5QQ.
3909400
3.99
1.56
2223900
2.27
0.89

376200
742000
1097400
1442300
1226.3.30.
2064800
2342400
2609600
2866300
3.1126.Q.Q.
3292800
3462600
3622000
3770900

                                                                                                                                       01

-------
                                                      Table A-106





DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON.,  50  MW  EX.  COAL  FIREO POWER UNIT, 0.81 S IN FUEL, 4.0 INJECTION STOICHIOMETRY.



                                                FIXED  INVESTMENT:   t     834500
YEARS
AFTER
POWER ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KWH/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPAMY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWER)
TONS COAL/YR *
CUMULATIVE
NET INCREASE
IS COST OF
POWER,
$
1
2
3
4
5
6
7
8
9
11
12
13
16 5000
17 5000
18 5000
19 5000
21 3500
22 3500
23 3500
24 3500
26 1500
27 1500
28 1500
29 1500
3.Q 1500
250000
250000
250000
250000
175000
175000
175000
175000
75000
75000
75000
75000
98100
98100
98100
98100
68700
68700
68700
68700
29400
29400
29400
29400
_ 224QQ-
TOTAL 50000 2500000 981000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
417800
406200
394600
383100
318800
307200
295600
284100
198100
186600
175000
163400
	 1512QQ 	
4326400
4.41
1.73
2464300
2.51
0.99
417800
824000
1218600
1601700
	 laiazao-
2292000
2599200
2894800
3178900
3649500
3836100
4011100
4174500

                                                                                                                                ID

-------
                                                        Table A-107

DRY LIMESTONE  INJECTION,  REGULATED POWER CO. ECON., 50 MM EX. COAL FIRED POWER UNIT, 0.8* S  IN FUEL,  5.0 INJECTION STOICHIOMETRY.

                                                 FIXED INVESTMENT:  $     908300
YEARS
AFTER
POWER
UNIT
START
  ANNUAL
OPERATION,
 KW-HR/KW
  POWER
GENERATION
 M KWH/YR
   POWER UNIT
FUEL CONSUMPTION,
  TONS COAL/YR
ANNUAL OPERATING COST
 INCLUDING REGULATED
ROI FOR POWER COMPANY
 (NET ANNUAL INCREASE
  IN COST OF POWER)
           $
 CUMULATIVE
NET INCREASE
 IN COST OF
   POWER,
      $
  1
  2
  3
  4

 ~6
  7
  8
  9
-10.
 11
 12
 13
 V4
16
17
18
19
21
22
23
24
26
27
28
29
3Q_
5000
5000
5000
5000
	 5.QQQ. 	
3510
3500
3500
3500
_ 	 	 as.QQ. 	
1500
1500
1500
1500
250000
250000
250000
250000
	 25QOQQ_
175000
175000
175000
175000
75000
75000
75000
75000
	 25QO.Q 	
98200
98200 '
98200 '
98200 '
68800 ;
68800 ;
68800 :
68800 :
6jaaQQ 	 	 i
29500 i
29500 i
29500 ]
29500 ;
2.2500 	 __ 	 J
 TOTAL        50000           2500000            982500
    EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
    EQUIVALENT COST, MILLS PER KILOWATT-HOUR
 PRESENT WORTH IF DISCOUNTED AT  10.OX TO INITIAL YEAR, DOLLARS
    EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
    EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
                                                                       456900
                                                                       444300
                                                                       431700
                                                                       419100
                                                                      _iQ6.5QQ	
                                                                       347400
                                                                       334800
                                                                       322200
                                                                       309600
                                                                      -2.220.0.0.	
                                                                       214300
                                                                       201700
                                                                       189100
                                                                       176500
                                                                       16.3,200.	
                                                            4715000
                                                               4.80
                                                               1.89
                                                            2689400
                                                               2.74
                                                               1.08
                                                                                      456900
                                                                                      901200
                                                                                      332900
                                                                                     ^752000
                                                                                     2J.5fl5Qfl_
                                                                                     2505900
                                                                                     2840700
                                                                                     3162900
                                                                                     3472500
                                                                                     3983800
                                                                                     4185500
                                                                                     4374600
                                                                                     4551100
                                                                                     47-15.0.00.
                                                                                                                        <£>

-------
                                                       Table A-108





DRY LIMESTONE INJECTION,  REGULATED POWER CO.  ECON.,  50  MW EX. COAL FIRED POWER UNIT, 0.8S S IN FUEL, 6.0 INJECTION STOICHIOMETRY.



                                                FIXED INVESTMENT:  $     974900
YEARS
AFTER
POWER. ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KWH/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWERJ
TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
5
6
7
8
9
10
11
12
13
14
16 5000
17 5000
18 5000
19 5000
20 5QOO ^
21 3500
22 3500
23 3500
24 3500
25 • 350Q
26 1500
27 1500
28 1500
29 1500
ifl 	 _L5fifl 	 ^


250000
250000
250000
250000
175000
175000
175000
175000
__125flQQ_
75000
75000
75000
75000
15QQQ


98400
98400
98400
98400
_, 98400
68900
68900
68900
68900
29500
29500
29500
29500
29500
TOTAL 50000 2500000 984000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR


493400
479900
466300
452800
	 4a22QQ 	
374400
360900
347300
333800
3.2D.3.0.Q
229700
216200
202600
189100
	 115.400. 	
5081600
5.16
2.03
2901100
2.95
1.16


493400
973300
1439600
1892400
	 23.3.1J.QO.
2706100
306700C
3414300
3748100
4P.684.Qp'.
4298100
4514300
4716900
4906000
	 saaiiafl.

                                                                                                                                  00

-------
                                                      Table A-109




DRY LIMESTONE INJECTION, REGULATED POHER CO. ECON., 50 MW EX. COAL FIRED POWER UNIT, 0.8* S IN FUEL, 7.0 INJECTION STOICHIOMETRY.



                                                FIXED INVESTMENT:  *    1036300
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR ",
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
6
7
8
9
-10.
11
13
14
15_
16
17
18
19
-2.Q.
21
22
23
24
26
27
28
29
_2tt
TOT
PRE




5000 250000
5000 250000
5000 250000
5000 250000
_5.QQO_ 250000
3500
3500
3500
3500
1500
1500
15OO
1500
1SOQ
175000
175000
175000
175000
115QQfl 	
75000
75000
75000
75000
75000


98500
98500
98500
98500
69000
69000
69000
69000
	 6.2QQQ 	 	 	 .
29600
29600
29600
29600
226QQ
AL 50000 2500000 985500
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
SENT WORTH IF DISCOUNTED AT 10. OS TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR


528300
513900
499500
485100
	 4iaaaa _„ 	
399800
385400
371000
356700
	 3.4.22QQ 	 _
243900
229500
215200
20080
	 18.6.4.QU
5428600
5.51
2.17
3102100
3.15
1.2*


528300
1042200
1541700
2026800
2 8 9 74 00~
3282800
3653800
40105OO
4596700~
4826200
5041400
5242200
54.2.B6.QQ

                                                                                                                                  VD

-------
                                                       Table A-110




DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON.,  150 MW EX.  COAL  FIRED  POWER UNIT, 0.8S S IN FUEL,  3.0  INJECTION  STOICHIONETRY.


                                                FIXED INVESTMENT:  $    1280100
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR $
1
2
3
4
^5
6
7
8
9
11
12
13
14



16 5000
17 5000
18 5000
19 5000
^20 _ 5000
21
22
23
24
26
27
28
29
3500
3500
3500
3500

	 . 	 	 	
750000
750000
750000
750000
525000
525000
525000
525000
1500 225000
1500 225000
1500 225000
1500 225000
1500 22jOQO

	
293800
293800
293800
293800
205700
205700
205700
205700
88100
88100
88100
88100
_BfllQQ
TOTAL 50000 7500000 2938000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR



634300
616500
598800
581000
-56.3,10.0 	
478500
460800
443100
425300
	 40.16.QJi 	
291400
273700
256000
238200
6489000
2.21
0.87
3712400
1.26
0.49
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
*



634300
1250800
1849600
2430600
,. , 2223900
3472400
3933200
4376300
4801600
52Q22QQ
5500600
5774300
6030300
6268500
&.4S2QQQ

                                                                                                                                   IV)
                                                                                                                                   o
                                                                                                                                   o

-------
                                                        Table A-lll

DRY LIMESTONE  INJECTIONt  REGULATED  POWER CO.  ECON.,  150 MM EX. COAL FIRED POWER UNIT, 0.8* S IN FUEL, 4.0 INJECTION  STOICHIOMETRY.
                                                 FIXED INVESTMENT:  $    1431500
YEARS
AFTER
POWER
UNIT
START
  ANNUAL
OPERATION,
 KW-HR/KW
  POWER
GENERATION
 M KWH/YR
   POWER UNIT
FUEL CONSUMPTIONt
  TONS COAL/YR
ANNUAL OPERATING COST
 INCLUDING REGULATED
ROI FOR POWER COMPANY
 (NET ANNUAL INCREASE
  IN COST OF POWERJ
           $
 CUMULATIVE
NET INCREASE
 IN COST OF
   POWER,
      *
    750000
    750000
    750000
    750000
    ,15.0.0.0.0.-
    525000
    525000
    525000
    525000
                              225000
                              225000
                              225000
                              225000
                                                294200
                                                294200
                                                294200
                                                294200
                                                            729300
                                                            709400
                                                            689600
                                                            669700
206000
206000
206000
206000
88300
88300
88300
88300
	 aaaofl 	
547700
527900
508000
488200
329700
3099QO
290000
270200
__ 	 2.5.0100.
                                                       729300
                                                      1438700
                                                      2126300
                                                      2798000
                                                     -34.4.12QQ.
                                                      3995600
                                                      4523500
                                                      5031500
                                                      5519700
                                                                                    6317800
                                                                                    6627700
                                                                                    6917700
                                                                                    7187900
 TOTAL       50000           7500000           2942500                7438200
    EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED                      2.53
    EQUIVALENT COST, MILLS PER KILOWATT-HOUR                             0.99
 PRESENT WORTH IF DISCOUNTED AT  10.0* TO INITIAL YEAR, DOLLARS       4262400
    EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED             1.45
    EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR                    0.57

-------
                                                       Table A-112


DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON.,  150 MW EX.  COAL FIRED  POWER  UNIT,  0.88 S  IN  FUEL,  5.0  INJECTION STOICHIOM6TRY.

                                                FIXED INVESTMENT:   $    1568800
YEARS
AFTER
POWER ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KWH/YR
I
Z
3
4
5
6
7
8
9
,10 ^rT-
11
12
13
14
15



16 5000 750000
17 5000 750000
18 5000 750000
19 5000 750000
_2Q 	 	 5UCJ2 	 7.5QQQO
21 3500
22 3500
23 3500
24 3500
25 350O
26 1500
27 1500
28 1500
29 1500
30 , , 15Q0 , - ,
525000
525000
525000
525000
	 525QQ&.
225000
225000
225000
225000
225QQ.fi
ANNUAL OPERATING COST
INCLUDING REGULATED CUMULATIVE
R01 FOR POWER COMPANY NET INCREASE
POWER UNIT (NET ANNUAL INCREASE IN COST OF
FUEL CONSUMPTION, IN COST OF POWER! POWER.
TONS COAL/YR § $



294700
294700
294700
294700
^_2S4ZOa^.,li».r-
206300
206300
206300
206300
2Q6300
88400
88400
88400
88400
8fl400_
TOTAL 50000 7500000 2947000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0? TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR



819300
797600
775800
754000
. 	 	 Z3.22Qa_
613300
591600
569800
548100
	 526.3flQ
365400
343700
321900
300200
	 	 2ia4Qa_
8337700
2.83
1.11
4784000
1.62
0.64



819300
1616900
2392700
3146700
	 3.S1SQQQ
4492300
5083900
5653700
6201800
6-22JLLQ2
7093500
7437200
7759100
805930O
	 . 	 aaaziflo.
                                                                                                                                 l\3
                                                                                                                                 O

-------
                                                     Table A-113



DRV LIMESTONE INJECTION, REGULATED POWER CO. ECON.,  150 MW EX.  COAL FIRED POWER  UNIT,  0.8*  S  IN  FUEL,  6.0 INJECTION STOICHIOMETRY.


                                                FIXED INVESTMENT:   $    1694400
YEARS
AFTER.
POWER ANNUAL POWER
UNIT OPERATION, GENERATION
START KH-HR/KW M KWH/YR
1
2
3
4
•j
6
7
8
9
-10
11
12
13
14
1*>
16
17
ia
19
-2.0.
21
22
23
24
25



5000
5000
5000
5000
5QOO
3500
3500
3500
3500
3500



750000
750000
750000
750000
	 isaoao-
525000
525000
525000
525000
525QOO
26 1500 225000
27 1500 225000
28 1500 225000
29 1500 225000
20. i5CO 225QQQ
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWER)
TONS COAL/YR $



295100
295100
295100
295100
zasiaa 	 _ 	
206600
206600
206600
206600
	 ZQfifiQfl 	
88500
88500
88500
88500
Sfl5.QQ
TOTAL 50000 7500000 2951000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR



905800
882300
858800
835300
aiiaofl_
676000
652500
629000
605500
	 aazQ-QQ 	
399300
375800
352300
328800
	 3Q52QQ 	
9200500
3.12
i.23
5284900
1,79
0.70
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
i



905800
1788100
2646900
3482200
	 	 . 	 i224QDfl
4970000
§622500
6251500
6857000
	 Z4.22QQfl_
1838300
821*100
3566400
8895200
	 22£Ki5_QQ

                                                                                                                                 IV)
                                                                                                                                 o
                                                                                                                                 00

-------
                                                        Table  A-llU

OR* LIMESTONE  INJECTION,  REGULATED  POWER  CO.  ECON.,  150  MM  EX.  COAL FIRED  POWER  UNIT,  0.81  S  IN  FUEL,  7.0 INJECTION STOICHIOMETRV.

                                                 FIXED  INVESTMENT:  *     isoaooo
YEARS
AFTER
POWER.
UNIT
START

~~I
  2
  3
  4
             ANNUAL
          OPERATION,
           KW-HR/KW
  POWER
GENERATION
 M KWH/YR
   POWER UNIT
FUEL CONSUMPTION,
  TONS COAL/YR
                                                            ANNUAL OPERATING COST
                                                              INCLUDING REGULATED
                                                            ROI FOR POWER COMPANY
                                                              (NET ANNUAL INCREASE
                                                              IN COST OF POWER)
                                                                                   CUMULATIVE
                                                                                  NET INCREASE
                                                                                   IN COST OF
                                                                                     POWER,
                                                                                        $
  6
  7
  8
  9

 "ll"
 12
 13
 14
 16
 17
 18
 19
 21
 22
 23
 24
-2,5	
 26
 27
 28
 29
     5000
     5000
     5000
     5000
	aaoa—
     3500
     3500
     3500
     3500
	asafl	
             1500
             1500
             1500
             1500
                             750000
                             750000
                             750000
                             750000
                            -isaflfla..
                             525000
                             525000
                             525000
                             525000
                            _525_aaa.
                             225000
                             225000
                             225000
                             225000
       295600
       295600
       295600
       295600
	2256.0.0—
       206900
       206900
       206900
       206900
    	2fl62QQ_.
        88700
        88700
        88700
        88700
                                             988800
                                             963700
                                             938600
                                             913600
                                                       988800
                                                      1952500
                                                      2891100
                                                      3804700
                                             736200
                                             711200
                                             686100
                                             661100
                                             63.6QQ.O.-
                                             431400
                                             406400
                                             381300
                                             356200
                                                                                               5429400
                                                                                               6140600
                                                                                               6826700
                                                                                               7487800
                                                      8555200
                                                      8961600
                                                      9342900
                                                      9699100
                                                     1QQ3.Q.3.QO.
TOTAL       50000           7500000            2956000                10030300
   EQUIVALENT COST, DOLLARS PER  TON  OF  COAL  BURNED                       3.39
   EQUIVALENT COST, MILLS PER  KILOWATT-HOUR                              1.34
PRESENT WORTH IF DISCOUNTED AT   10.0* TO  INITIAL  YEAR,  DOLLARS        5766600
   EQUIVALENT PRESENT  WORTH, DOLLARS PER  TON OF COAL  BURNED              1.95
   EQUIVALENT PRESENT-WORTH, MILLS PER  KILOWATT-HOUR                     0.77

-------
                                                       Table A-115
DRY LIMESTONE INJECTION,  REGULATED POWER  CO.  ECON., 250 MM EX. COAL FIRED POWER UNIT, 6.8X S IN FUEL,  3.0 INJECTION STOICHIOMETRY.
                                               FIXED  INVESTMENT:  $    1695100
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED CUMULATIVE
AFTER ROI FOR POWER COMPANY NET INCREASE
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE IN COST OF
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER) POWER,
START KW-HR/KW M KWH/YR TONS COAL/YR $ $
1
2
3
4
5
6
7
8
9
ID
11
12
13
14
15
16 5000
17 5000
18 5000
19 5000
20 ^5OOQ
21 3500
22 3500
23 3500
24 3500
25 2500
26 1500
27 1500
28 1500
29 1500
^n 1*500



1250000
1250000
1250000
1250000
_125flflQQ_ 	
875000
875000
875000
875000
aiiaaa.
375000
375000
375000
375000
375000



489700
489700
489700
489700
„. 489700, _,..,-
342800
342800
342800
342800
34.2flQ.fl 	 	
146900
146900
146900
146900
__ JAfiSQQ 	 __ 	
TOTAL 50000 12500000 4897000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR

	
857200
833700
810200
786700
-1632,00 	
642200
618700
595200
571600
	 54B1QQ 	
384800
361300
337800
314300
__22QflQQ 	
8715800
1.78
0.70
4999800
1.02
0.40



857200
1690900
2501100
3287BOO
	 4fl51QQfl.
4693200
5311900
5907100
6478700
	 _ 	 	 ZQ2.6flflQ
7411600
7772900
8110700
8425000
,- „, 	 ,9715800


-------
                                                       Table A-ll6


DRY LIMESTONE INJECTION, REGULATED POWER  CO.  ECON., 250 MW EX. C3AL FIRED POWER UNIT,  0.8*  S  IN  FUEL,  4.0  INJECTION  STOICHIOMETRY.


                                                FIXED  INVESTMENT:  *    1868100
YEARS
AFTER
POWER ANNUAL POWER POWER UNIT
UNIT OPERATION, GENERATION FUEL CONSUMPTION,
START KW-HR/KW M KWH/YR TONS COAL/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
INET ANNUAL INCREASE
IN COST OF POWER)
*
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
6
7
8
9
10
11
12
13
14
A.5
16
17
IB
19
2.0. ^ -
21
22
23
24
26
27
28
29
3.Q


5000
5000
5000
5000
50QC
3500
3500
3500
3500
1500
1500
1500
1500
1«500


1250000
1250000
1250000
1250000
125QQQQ
875000
875000
875000
875000
"375000
375000
375000
375000
375000


490400
490400
490400
490400
34330O
343300
343300
343300
	 343100 	
147100
147100
147100
147100
1471QQ


989600
963700
9378OO
911900
48.6jO.PQ
738000
712100
686200
660300
	 6.14400 	
435500
409600
383700
357800
331900


989600
1953300
2891100
3803000
	 	 4&fl2flflQ_
5427000
6139100
6825300
7485600
	 fli2flQOQ_
8555500
8965100
9348800
9706600
10.03.8.500.
TOTAL 5000C 12500000 4904000 10038500
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED 2.05
EQUIVALENT COST, MILLS PER KILOWATT-HOUR 0.80
PRESENT WORTH IF DISCOUNTED AT 10. OX TO INITIAL YEAR, DOLLARS 5768300
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED 1.18
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR 0.46
                                                                                                                                 17
                                                                                                                                 N)
                                                                                                                                 o

-------
                                                       Table A-117

ORV LIMESTONE INJECTION, REGULATED POWER CO. ECON.,  250 MW EX.  C3AL  FIRED  POWER UNIT, 0.8* S IN FUEL, 5.0 INJECTION STOICHIOMETRV.

                                                FIXED INVESTMENT:  $    2086100
YEARS
AFTER
POWER ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KHH/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POKER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWER)
TONS COAL/YR *
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
«
1
2
3
4
6
7
8
9
1O , .,
11
12
13
14
A5
16 5000
17 5000
18 5000
19 5000
2Q _5DQO_
21 3500
22 3500
23 3500
24 3500
25 35 QQ
26 1500
27 1500
28 1500
29 1500
30 15QQ
	
1250000
1250000
1250000
1250000
lisaaoa 	
875000
875000
875000
875000
ai5flOQ_
375000
375000
375000
375000
375QQO
	
491100
491100
491100
491100
^TT ^491100,^ ^
343800
343800
343800
343800
343800
147300
147300
147300
147300
1413-0.0. _ _
TOTAL 50000 12500000 4911000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT HORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT HORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR


1136400
1107500
1078500
1049600
__1QZQ1QQ 	
844800
815900
787000
758000
	 2221QQ 	
493400
464400
435500
406600
—17-7.&OQ
11505000
2.34
0.92
6619100
1.35
0.53


1136400
2243900
3322400
4372000
	 5322200-
6237500
7053450
7840400
8598400
	 22225flQ_
9820900
10285300
10720800
11127400
	 li505flflQ_

                                                                                                                                  O
                                                                                                                                  -si

-------
                                                       Table A-118




DRY LIMESTONE INJECTION,  REGULATED  POWER  CO.  ECON., 250 MW EX. COAL FIRED POWER UNIT,  0.8S  S  IN  FUEL, 6.0  INJECTION STOICHIOMETRY.



                                               FIXED INVESTMENT:  S    2253600
ANNUAL OPERATING COST
YEARS INCLUDING RP6ULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR $
1
2
3
4
5
6
7
8
9
_10 	
11
12
13
14
15
16
17
IB
19
^2.0 	 	



5000
5000
5000
5000
5.OOO . .
21 3500
22 3500
23 3500
24 3500
25 35OO
26
27
26
29
3.0
1500
1500
1500
1500
1500



1250000
1250000
1250000
1250000
1250000
875000
875000
875000
875000
875000
375000
375000
375000
375000
375000



491900
491900
491900
491900
42123Q 	 _
344300
344300
344300
344300
24&3.Q.a_
147600
147600
147600
147600
14-7.6.0.0—
TOTAL 50000 12500000 4919000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0? TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT .WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR



1267700
1236500
1205300
1174000
-ll&ZflQO 	 _
939900
908700
877500
846200
	 aiSQQQ 	
543500
512300
481000
449800
	 41&60H 	
12818800
2.61
1.03
7382400
1.50
0.59
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
S



1267700
2504200
3709500
4883500
	 6flZ63flfl_
6966200
7874900
8752400
9598600
	 ,,10413600
10957100
11469400
11950400
12400200
	 IZfllflSQQ.
                                                                                                                                  ro
                                                                                                                                  o
                                                                                                                                  oo

-------
                                                        Table A-119


DRV LIMESTONE INJECTION, REGULATED POWER CO. ECON., 250 MM EX. COAL  FIRED POWER UNIT, 0.8* S  IN FUEL, 7.0  INJECTION STOICHIOMETRY.

                                                FIXED  INVESTMENT:  *    2407700
YEARS
AFTER
POWER
UNIT
START
1
2
3
4
6
7
8
9
10
11
12
13
14
16
17
18
19
2O
21
22
23
24
25
26
27
28
29
30
TOTAL
EQU
ANNUAL
OPERATION,
KW-HR/KW



5000
5000
5000
5000
50OO
3500
3500
3500
3500
35flQ
1500
1500
1500
1500
150°
50000
IVALENT COST,
POWER
GENERATION
M KWH/YR



1250000
1250000
1250000
1250000
1250000 ,.
875000
875000
875000
875000
,_ aisjwp
375000
375000
375000
375000
-325000.
12500000
DOLLARS PER TON OF
POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR



492600
492600
492600
492600
4226.QQ 	
344800
344800
344800
344800
_ _,_34^aoa 	
147800
147800
147800
147800
4926000
COAL BURNED
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
tNET ANNUAL INCREASE
IN COST OF POWER)
S



1394700
1361300
1327900
1294500
	 	 1261200 	
1031600
998200
964800
931400
591600
558200
524800
491400
14087600
2.86
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
t



1394700
2756000
4083900
5378400
_ 	 6.6.226.00
7671200
8669400
9634200
10565600
_ 	 114.43.6.0.Q
12055200
12613400
13138200
13629600

   EQUIVALENT  COST,  MILLS  PER  KILOWATT-HOUR                             1.13
PRESENT WORTH  IF  DISCOUNTED  AT  10.OX  TO  INITIAL YEAR, DOLLARS       8120000
   EQUIVALENT  PRESENT  WORTH, DOLLARS PER  TON  OF COAL BURNED             1.65
   EQUIVALENT  PRESENT  WORTH, MILLS PER KILOWATT-HOUR                    0.65
                                                                                                                                   o
                                                                                                                                   to

-------
                                                        Table A-120




DRY LIMESTONE INJECTION,  REGULATED POWER CO.  ECON.,  350  MW  EX. C3AL FIRED POWER UNIT, 0.8J S IN FUEL, 3.0 INJECTION STOICHIOMETRY.



                                                FIXED  INVESTMENT:  $    2032300
YEARS
AFTER
POWER. ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KWH/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT CNET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWER)
TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
5 ,-
6
7
8
9
10
11
12
13
14
15.
16 5000
17 5000
18 5000
19 5000
2Q__ _5QQQ 	
21 3500
22 3500
23 3500
24 3500
_25 J5QO
26 1500
27 1500
28 1500
29 1500
3g T — L5QQ 	 _.,„„„


1750000
1750000
1750000
1750000
-1Z500QO-
1225000
1225000
1225000
1225000
12.25.DQQ ..
525000
525000
525000
525000
525QOQ


685600
685600
685600
685600
, n 6.856QQJ
479900
479900
479900
479900
_ £239.00 	 	
205700
205700
205700
205700
205700
TOTAL 50000 17500000 6856000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR


1055400
1027200
999100
970900
	 stiziao. 	
787200
759000
730800
702600
	 6.145.00
465900
43 700
409500
381300
-15.1IQO.
10696900
1.56
0.61
6146600
0.90
0.35


1055400
2082600
3081700
4052600
4995300
5782500
6541500
7272300
7974900
aai240Q
9115300
9553000
9962500
10343800
106.i62QQ


-------
                                                       Table A-121
ORY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 350 HW EX. COAL FIRED POWER UNIT, 0.8* S IN FUEL, 4.0 INJECTION STOICHIOHETRY.
                                                FIXED INVESTMENT:  s    2278800
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR *
1
2
3
4
6
7
8
9
1ft
11
12
13
-15.
16
17
18
19
21
22
23
24
25
26
27
28
29



5000
5000
5000
5000
3500
3500
3500
3500
1500
1500
1500
1500
L5QQ



1750000
1750000
1750000
1750000
_1Z5QQQO_ 	
1225000
1225000
1225000
1225000
_I2Z5£Qfl_ _
525000
525000
525000
525000
525.QQQ



686600
686600
686600
686600
480600
480600
480600
480600
206000
206000
206000
206000
206000
TOTAL 50000 17500000 6866000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10. 0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
	

1242200
1210600
1179000
1147400
	 11I5MQ 	
922400
890800
859200
827600
_Z26.QQQ
537500
505900
474300
442800
	 	 4.112QO. 	
12562700
1.83
0.72
7230600
1.05
0.41
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
*
	

1242200
2452800
3631800
4779200
	 5Jl25flflQ_
6817400
7708200
8567400
9395000
	 J>fll210.QQ
10728500
11234400
11708700
12151500


-------
                                                        Table A-122
DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 350 HW EX.  COAL FIRED POWER  UNIT,  0.8*  S  IN  FUEL*  5.0  INJECTION  STOICHIOHETRY.
                                                FIXED INVESTMENT:  S    2503200
YEARS
AFTER.
POWER. ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KH M KHH/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWER)
TONS COAL/YR *
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
»
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
2P


5000
5000
5000
5000
5OOO
21 3500
22 3500
23 3500
24 3500
,25 35DO
26
27
28
29
3Q
1500
1500
1500
1500
150O_


1750000
1750000
1750000
1750000
J,75QOOO_
1225000
1225000
1225000
1225000
.1225000.
525000
525000
525000
525000
525QQQ


687600
687600
687600
687600
,687600 	 	
481300
481300
481300
481300
4R1300
206300
206300
206300
206300
2O6300
TOTAL 50000 17500000 6876000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10. OX TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR


1421900
1387200
1352400
1317700
—uaaaoa 	
1052200
1017500
9B2800
948000
	 213200 	
605800
571100
536400
501700
.4J&.1QDQ
14358000
2.09
0.82
8274100
1.20
0.47


1421900
2809100
4161500
5479200
	 626220Q.
7814400
8831900
9814700
10762700
	 11626000-
12281800
12852900
13389300
13891000
. _ -14358000.

                                                                                                                                   ro

-------
                                                       Table  A-123
DRY LIMESTONE INJECTION,  REGULATED POWER  CO.  ECON., 350 MW EX. COAL FIRED POWER UNIT, 0.8X S IN FUEL,  6.0 INJECTION STOICHIOMETRY.
                                                FIXED  INVESTMENT:  $    2707700
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POKER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KH-HR/KW M KWH/YR TONS COAL/YR *
1
a
3
4
5
6
7
8
9
Ifl
11
12
13
1*
15
16 5COO
17 5000
18 5000
19 5000
?0 5.Q.QQ



1750000
1750000
1750000
1750000
1Z5QQQQ
21 3500 1225000
22 3500 1225000
23 3500 1225000
24 3500 1225000
25 25QQ 1225OOO
26 1500
27 1500
26 1500
29 1500
2Q 	 L5fl-Q
525000
525000
525000
525000
525000



688600
688600
688600
688600
_ 68.S6J2Q 	
482000
482000
482000
482000
4£2flQ.Q.
206600
206600
206600
206600
246.6.0.0.
TOTAL 50000 17500000 6886000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR



1595800
1558300
1520700
1483200
	 14.456.flQ 	 	
1177900
1140300
1102800
1065200
	 1Q22ZQQ 	
670900
633300
595800
558200
	 52QZCQ 	
16096400
2.34
0.92
9285400
1.35
0.53
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$



1595800
3154100
4674800
6158000
	 Z6.D26.QQ.
8781500
9921800
11024600
12089800
13.1115flQ
13788400
14421700
15017500
15575700
	 16.32£4.flQ

                                                                                                                                 GO

-------
                                                       Table A-


DRY LIMESTONE INJECTION, REGULATED POWER CO.  ECON.,  350  MW  EX. COAL FIRED POWER UNIT, 0.8* S IN FUEL, 7.0 INJECTION STOICHIOMETRY.

                                                FIXED  INVESTMENT:  $    2893300
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR t
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
»
1
2
3
4
5 '
6
7
8
9
.,10 .„_ ,, , 	
11
12
13
14


16 5000 1750000
17 5000 1750000
18 5000 1750000
19 5000 1750000
2ft_ _5flflfl_ ^ 1750000
21 3500
22 3500
23 3500
2* 3500
24 35QP
26 1500
27 1500
28 1500
29 1500
3Q_ t 	 L5QQ 	 n
1225000
1225000
1225000
1225000
-1225QUQ-
525000
525000
525000
525000
•5P5000


689600
689600
689600
689600
&&2&QQ_ _ 	
482800
482800
482800
482800
4828QQ
206900
206900
206900
206900
206900 	
TOTAL 5000C 17500000 6896500
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10. OX TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR


1776900
1736800
1696700
1656500
	 16.164QQ 	
1309600
1269500
1229300
1189200
	 .1142100 	
740300
700200
660000
619900
	 5Z2flQQ 	
17930200
2.60
1.02
10347900
1.50
0.59


1776900
3513700
5210400
686690O
	 aiaiiflQ-
9792900
11062400
12291700
13480900
_ _14£3.flQ.Qfi_
15370300
16070500
16730500
17350400
	 11230200.
                                                                                                                                 r
                                                                                                                                 IVJ

-------
                                                          Taisle A-125





DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 50 MM EX. COAL  FIRED  POKER UNIT, 3.0* S IN FUEL,  1.0 INJECTION STOICHIOMETRY.



                                                  FIXED INVESTMENT:   t     817100
YEARS
AFTER
POWER ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KWH/YR
1
2
3
4
5 ^_^_ - _,„ -
6
7
8
9
11
13
14
15
16 5000
17 5000
18 5000
19 5000
Zfl 5000 „ ,_
21 3500
22 3500
23 3500
24 3500
25 3500
26 1500
27 1500
28 1500
29 1500
3.0 _15Dfl_



250000
250000
250000
250000
175000
175000
175000
175000
75000
75000
75000
75000
750QO
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWER)
TONS COAL/YR »



98000
98000
98000
98000
28000
68600
68600
68600
68600
6860Q
29400
29400
29400
29400
29400
TOTAL 50000 2500000 980000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR



407900
396500
385200
373800
311600
300200
288900
277600
194000
182700
171300
160000
	 iifilQa 	
4227100
4.31
1.69
2406900
2.46
0.96
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$



407900
804400
1189600
1563400
	 13253Q2_
2237500
2537700
2826600
3104200
	 	 3.3.Ifl4.QQ_
3564400
3747100
3918400
4078400
	 422JlQPr

                                                                                                                                      01

-------
                                                       Table  A-126



DRY LIMESTONE INJECTION,  REGULATED POWER  CO.  ECON.,  50  MM EX. COAL FIRED POWER UNIT, 3.0? S IN FUEL,  2.0 INJECTION STOICHIOMETRY.


                                                FIXED  INVESTMENT:  «    IOTOSOO
YEARS
AFTER
POWER ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KH M KWH/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POWER)
TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
6
7
8
9
11
12
13
14
15
16 5000
17 5000
18 5000
19 5000
20 5QQQ
21 3500
22 3500
23 3500
24 3500
25 _J15QQ_
26 1500
27 1500
28 1500
29 1500
250000
250000
250000
250000
175000
175000
175000
175000
_liaQQQ_
75000
75000
75000
75000
15.QQQ
98400
98400
98400
98400
98400
68900
68900
68900
68900
68900
29500
29500
29500
29500
_295Qfl _ 	
TOTAL 50000 2500000 984000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESF.NT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
546100
531200
516400
501500
-4.a6.ZQQ 	
412900
398100
383200
368400
	 3535QQ 	
251600
236700
221800
207000
	 1221QQ 	
5607200
5.70
2.24
3205200
3.26
1.28
546100
1077300
1593700
2095200
2994800
3392900
3776100
4144500
4749600
4986300
5208100
5415100
, 56QI2QQ

                                                                                                                                 r\j
                                                                                                                                 i—»

                                                                                                                                 01

-------
                                                      Table A-12?





DRY LIMESTONE INJECTION,  REGULATED POWER CO.  ECON.,  50  MW  EX.  COAL  FIRED POWER UNIT, 3.0* S IN FUEL, 3.0 INJECTION ST01CHIOMETRY.



                                                FIXED INVESTMENT:   $    1271500
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR $
1
2
3
4
5 	 	
6
7
8
9




CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$


11
12
13
14
16 5000
17 5000
18 5000
19 5000
PO 5000
21 3500
22 3500
23 3500
24 3500
25. -3.500
26 1500
27 1500
28 1500
29 1500
an _150-0 	
250000 98900
250000 98900
250000 98900
250000 98900
250000 	 	 2H2QQ 	 _ _.
175000 69200
175000 69200
175000 69200
175000 69200
115000 -u ,69200
75000 29700
75000 29700
75000 29700
75000 29700
isaaa_ 	 22ZQO 	 	
TOTAL 50000 2500000 989000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT *ORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
668100
650400
632800
615200
52Z50Q
502100
484400
466800
449200
	 431500 	 ,_
301000
283300
265700
248100
. 	 	 23Q4QQ
6826500
6.90
2.73
3911300
3.95
1.56
668100
1318500
1951300
'.566500
	 3164000-
3666100
4150500
4617300
5066500
5799000
6082300
6348000
6596100

                                                                                                                                IV)

-------
                                                      Table A-128
DRV LIMESTONE INJECTION,  REGULATED POWER CO.  ECON.,  50 MW EX. COAL  FIRED POWER UNIT, 3.0* S IN FUEL,  4.0 INJECTION STOICHIOMETRY.
                                                FIXED INVESTMENT:   *    144-2000
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF PDWERI
START KW-HR/KW M KWH/YR TONS COAL/YR $
1
2
3
4
, .5 	 _..^_ 	 ..„ .
6
7
8
9
IP
11
12
13
14
15
16 5000
17 5000
18 5000
19 5000
20. 5poo
21 3500
22 3500
23 3500
24 3500
25 3500
26 1500
27 1500
28 1500
29 1500
3.Q _ L50Q



250000
250000
250000
250000
25QQOQ
175000
175000
175000
175000
1Z5QQU 	 „„
75000
75000
75000
75000
75QQQ
TOTAL 50000 2500000
EQUIVALENT COST, DOLLARS PER TON OF COAL
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10. 0* TO INI
EQUIVALENT PRESENT WORTH, DOLLARS PER TON
EQUIVALENT PRESENT WORTH, MILLS PER KILOW



99400
99400
99400
99400
224QQ 	 _ 	
69600
69600
69600
69600
_6.9.6.QQ 	
29800
29800
29800
29800
	 2.2&Q.Q. 	
994000
BURNED
TIAL YEAR, DOLLARS
OF COAL BURNED
ATT-HOUR



781000
761000
741100
721100
_ .101100 	
584200
564200
544200
524200
	 5Q4.2.QQ 	
345700
325800
305800
285800
7955200
8.00
3.18
4565900
4.59
1.83
CUMULATIVE
NET INCREASE
IN COST OF
POWER,



781000
1542000
2283100
3004200
4289500
4853700
5397900
5922100
	 . 	 6.4 2.6.3.QQ_
6772000
7097800
7403600
7689400
	 7_3S520J}

                                                                                                                                oo

-------
                                                         Table A-129




DRY LIMESTONE INJECTION, REGULATED POWER CO.  ECON.,  150  MW EX. COAL  FIRED  POWER UNIT,  3.0* S IN FUEL, 1.0 INJECTION STOICHIOMETRY.



                                                 FIXED  INVESTMENT:  $     140*600

YEARS
AFTER
POWER ANNUAL
UNIT OPERATION,
START KH-HR/KW
1
2
3
4
6
7
8
9
10 	
11
12
13
14
16 5000
17 5000
18 5000
19 5000
2.O 5.0QQ
21 3500
22 3500
23 3500
24 3500
?*> 3500
26 1500
27 1500
28 1500
29 1500
_aa 	 isafl —
TOTAL 50000
EQUIVALENT COST,
EQUIVALENT COST,



POWER
GENERATION
M KWH/YR













750000
750000
750000
750000
Z5QQ.QQ _
525000
525000
525000
525000
5_2.5QQfl
225000
225000
225000
225000
	 22.5QO.Q 	
7500000
DOLLARS PER TON OF



POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR













293900
293900
293900
293900
2,9.3.9.00,
205700
205700
205700
205700
20.5100. 	
88200
88200
88200
88200
	 aazfio. 	
2939000
COAL BURNED
MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0*
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
(













707400
687900
668400
649000
	 	 62.95_O.Q 	
532000
512500
493100
473600
	 	 iSilQQ 	 .
321600
302100
282600
263200
	 Z&3.1D.Q 	
7220700
2.46
0.96

CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$













707400
1395300
2063700
2712700
	 3.3.422QQ
3874200
4386700
4879800
5353400
._ 	 5flQl5QQ
6129100
6431200
6713800
6977000
	 122.fllQO._



TO INITIAL YEAR, DOLLARS 4135700
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER
KILOWATT-HOUR
1.41
0.55


                                                                                                                                  [7

                                                                                                                                  N>
                                                                                                                                  I—*
                                                                                                                                  to

-------
                                                         Table  A-130

DRY LIMESTONE  INJECTION, REGULATED POWER CO. ECON., 150 MW EX. COAL FIRED POWER UNIT, 3.0* S IN FUEL, 2.0 INJECTION  STOICHIOMETRY.
                                                FIXED  INVESTMENT:  $    1374200
YEARS
AFTER
POWER
UNIT
START
  1
  2
  3
  4
 ..5
  6
  7
  8
  9
 10
 11
 12
 13

 15
 16
 17
 18
 19
 21
 22
 23
 24
 25_
 26
 27
 28
 29
.30	
  ANNUAL
OPERATION,
 KW-HR/KW
  POWER
GENERATION
 M KWH/YR
   POWER UNIT
FUEL CONSUMPTION,
  TONS COAL/YR
   5000
   5000
   5000
   5000
   5000^
   3500
   3500
   3500
   3500
   1500
   1500
   1500
   1500
   150Q
    750000
    750000
    750000
    750000
    525000
    525000
    525000
    525000
    225000
    225000
    225000
    225000
   -22.5000—
ANNUAL OPERATING COST
 INCLUDING REGULATED
ROI FOR POWER COMPANY
 (NET ANNUAL INCREASE
  IN COST OF POWER)
           t
 CUMULATIVE
NET INCREASE
 IN COST OF
   POWER,
      S
       295300                1029400                  1029400
       295300                1003500                  2032900
       295300                 977500                  3010400
       295300                 951500                  3961900
      -225300	9.25500.	iflaiAQQ-
       206700                 766200                  5653600
       206700                 740300                  6393900
       206700                 714300                  7108200
       206700                 688300                  7796500
      .2Q61QQ	6.&210Q	ai5MQQ
        88600                 447800                  8906600
        88600                 421900                  9328500
        88600                 395900                  9724400
        88600                 369900                 10094300
                              3.A32QQ
TOTAL       50000           7500000           2953000
   EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
   EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT  10.OX TO  INITIAL YEAR, DOLLARS
   EQUIVALENT PRESENT WORTH, DOLLARS PER  TON OF COAL BURNED
   EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
                                                          10438200
                                                              3.53
                                                              1.39
                                                           6002800
                                                              2.03
                                                              0.80

-------
                                                       Table A-131




ORY LIMESTONE INJECTION, REGULATED POWER CO. ECON.,  150 MW EX.  COAL  FIRED  POWER  UNIT,  3.0* S  IN  FUEL, 3.0  INJECTION  STOICHIOMETRY.



                                                FIXED INVESTMENT:   $    2251400
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR *
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16 5000
17 5000
18 5000
19 5000
20 5QQQ_



750000
750000
750000
750000
75QQQO
21 3500 525000
22 3500 525000
23 3500 525000
24 3500 525000
?•> 350Q - - 525OOO
26 1500
27 1500
28 1500
29 1500
•*n i son
225000
225000
225000
225000
225000



296700
296700
296700
296700
	 226.1Q.Q 	 	
207700
207700
207700
207700
-2Q.ZZQQ 	 	
89000
89000
89000
89000
890QO
TOTAL 50000 7500000 2967000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10. OX TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR



1324800
1293600
1^62300
1231100
J.1922QO. 	
979700
948500
917200
8B6000
560600
529400
498100
466900
	 _4.25ZQ.a 	
13388600
4.51
1.79
7717400
2.60
1.03
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$



1324800
2618400
3880700
5111800
	 6.3.11ZQ.Q
7291400
8239900
9157100
10043100
	 lQfl2I2QQ
11458500
11987900
12486000
12952900
	 123.aflfi.QQ


-------
                                                        Table  A-132





DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON., 150 MW EX.  COAL FIRED POWER UNIT,  3.0JE S IN FUEL,  4.0 INJECTION STOICHIOMETRY.



                                                FIXED INVESTMENT:  $    2574200
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER. ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
5
6
7
8
9
11
12
13
14
16 5000
17 5000
18 5000
19 5COO
2Q 5000
21 3500
22 3500
23 3500
24 3500
25 	 	 _25QQ 	
26 1500
27 1500
28 1500
29 1500
30 _ _.150Q ,_
750000
750000
750000
750000
I5QOQQ 	 _ _
525000
525000
525000
525000
225000
225000
225000
225000
225000
298200
298200
298200
298200
	 22B2.QQ 	
208700
208700
208700
208700
89500
89500
89500
89500
TOTAL 50000 7500000 2982000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
1604200
1568500
1532800
1497200
	 14615.QQ
1181300
1145600
1109900
1074200
	 1023.500 	
665000
629300
593600
557900
	 522ZQQ 	 .
16181700
5.43
2.16
9342200
3.13
1.25
1604200
3172700
4705500
6202700
Z&6_42QQ
8845500
9991100
11101000
12175200
13878700
14508000
15101600
15659500
. 	 16iSlZflfl

                                                                                                                                 rvs

-------
                                                        Table  A-133
DRY LIMESTONE INJECTION,  REGULATED  POWER  CO.  ECON., 250 MW EX. COAL FIRED POWER UNIT, 3.01 S IN FUEL,  1.0 INJECTION STOICHIOMETRY.
                                                FIXED  INVESTMENT:  $    1865600
YEARS
AFTER.
POWER ANNUAL
UNIT OPERATION,
START KW-HR/KW
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER POWER UNIT (NET ANNUAL INCREASE
GENERATION FUEL CONSUMPTION, IN COST OF POWER)
M KWH/YR TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
6
7
e
9
ifl
11
12
13
14
15
16
17
18
19
-2.Q
ai
22
23
24
_2i
26
27
28
29
_lfl
TOT
PRE

5000
5000
5000
5000
5.00Q
3500
3500
3500
3500
3500
1500
1500
1500
1500
1 *^00

1250000
1250000
1250000
1250000
J.2.5QQQQ
875000
875000
875000
875000
&Z5.QQQ
375000
375000
375000
375000
3I5QQQ

489800
489800
489800
489800
4fl2flflQ 	 	 	
342900
342900
342900
342900
34.22QQ 	 	
147000
147000
147000
147000
1470.0.0. 	 _ 	
A, 50000 12500000 4898500
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
SENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR

966600
940800
914900
889000
	 a&aiaa 	
722000
696100
670200
644300
	 ftiasaa
428400
402500
376600
350800
	 124."iPQ 	
9808700
2.00
0.78
5633500
1.15
0.45

966600
1907400
2822300
3711300
4,57.44.0.0.
5296400
5992500
6662700
7307000
iszssaa
8353900
8756400
9133000
9483800
	 	 2flflfl2QQ

                                                                                                                                co

-------
                                                         Table A-
DRV LIMESTONE  INJECTION,  REGULATED  POWER  CO.  ECON.,  250 MW EX.  COAL FIRED POWER  UNIT,  3.0? S IN FUEL, 2.0 INJECTION STOIC HI OMETR Y.

                                                 FIXED INVESTMENT:   $    2*98900
YEARS
AFTER
POWER
UNIT
START

  1
  2
  3
  4
  6
  7
  e
  9
_ifi_
 11
 12
 13
  ANNUAL
OPERATION,
 KW-HR/KW
  POWER
GENERATION
 M KHH/YR
   POWER UNIT
FUEL CONSUMPTION,
  TONS COAL/YR
ANNUAL OPERATING COST
 INCLUDING REGULATED
ROI FOR POWER COMPANY
 (NET ANNUAL INCREASE
  IN COST OF POWER)
 CUMULATIVE
NET INCREASE
 IN COST OF
   POWER,
      t
                                                                                                                        I\J
                                                                                                                        ro
 1,5
 16
 17
 18
 19
 21
 22
 23
 24
-Zi_
 26
 27
 28
 29
   5000           1.750000            492200                1456800                   1456800
   5000           1250000            492200                1422100                   2878900
   5000           1250000            492200                1387500                   4266400
   5000           1250000            492200                1352800                   5619200
	5QO.Q	1250000	4222QQ	13.1B2QQ	6.2224.00-
   3500            875000            344500                1076800                   8014200
   3500            875000            344500                1042200                   9056400
   3500            875000            344500                1007500                  10063900
   3500            875000            344500                 972800                  11036700

   1500            375000            147700                 615900                  12590800
   1500            375000            147700                 581300                  13172100
   1500            375000            147700                 546600                  13718700
   1500            375000            147700                 512000                  14230700
	L5QQ	325000	142200	422200	
TOTAL        5000C           12500000            4922000                14708000
   EQUIVALENT COST, DOLLARS  PER  TON  OF  COAL  BURNED                      2.99
   EQUIVALENT COST, MILLS PER  KILOWATT-HOUR                              1.18
PRESENT WORTH IF DISCOUNTED  AT  10.0* TO  INITIAL YEAR,  DOLLARS       8480000
   EQUIVALENT PRESENT  WORTH, DOLLARS PER  TON OF  COAL  BURNED             1.72
   EQUIVALENT PRESFNT  WORTH, MILLS PER  KILOWATT-HOUR                     0.68

-------
                                                       Table A-135
DRY LIMESTONE INJECTION,  REGULATED POWER CO. ECON., 250 MW EX.  C3AL  FIRED  POWER UNIT, 3.0* S IN FUEL, 3.0 INJECTION STOICHIOMETRV.
                                               FIXED INVESTMENT:   $    3011*00
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED CUMULATIVE
AFTER ROI FOR POWER COMPANY NET INCREASE
POWER ANNUAL POWER POWER UNIT 
-------
                                                       Table A-136
DRY LIMESTONE INJECTION,  REGULATED POWER CO. ECON., 250 MW EX.  C3AL  FIRED  POWER UNIT, 3.0J S IN FUEL, 4.0 INJECTION STOICHIOMETRY.
                                               FIXED INVESTMENT:   $    3*93000
YEARS
AFTER
POWER
UNIT
START
ANNUAL POWER
OPERATION, GENERATION
KH-HR/KW M KWH/YR
POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
$
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
6
7
e
9
10
11
12
13
14
15.
16
17
18
19
3D
21
22
23
24
_25_
26
27
28
29
2P

5000
5000
5000
5000
_5CQQ 	
3500
3500
3500
3500
_3.5QQ 	 	 	
1500
1500
1500
1500
1500

1250000
1250000
1250000
1250000
12j5.QO.aQ 	
875000
875000
875000
875000
	 aisQo.0. 	
375000
375000
375000
375000
31500.0.

497000
497000
497000
497000
_ 421QQQ 	 .
347900
347900
347900
347900
	 34J2QQ-
149100
149100
149100
149100
149100

2380700
2332200
2283700
2235200
21&6.ZQQ
1743400
1694900
1646300
1597800
__ 	 _15i23.QQ 	
960100
911600
863100
814600
16.6.1OO
TOTAL 50000 12500000 4970000 23965700
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED 4.82
EQUIVALENT COST, MILLS PER KILOWATT-HOUR 1.92
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS 13863600
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED 2.79
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR 1.11

2380700
4712900
6996600
9231800
	 _114ia5QQ
13161900
14856800
16503100
18100900
	 126.5.QZQQ
20610300
21521900
22385000
23199600
	 2.3.265IQQ

                                                                                                                               ro

-------
                                                        Table A-137


DRY LIMESTONE INJECTION, REGULA1tD POWER CO. ECON., 350 MW EX. COAL FIRED POWER UNIT, 3.0* S IN FUEL, 1.0 INJECTION STOICHIOMETRY.

                                                FIXED INVESTMENT:  t    2238600
ANNUAL OPERATING COST
YEARS
AFTER
POWER. ANNUAL
UNIT OPERATION,
START K.W-HR/KW
1
2
3
4
5
6
7
8
9
10
11
13
14
15
16 5000
17 5000
18 5000
19 5000
PO 50OO
21 3500
22 3500
23 3500
24 3500
s«; 3500
26 1500
27 1500
28 1500
i9 1500
^n 1500
TOTAL 5000C
INCLUDING REGULATED
ROI FOR POWER COMPANY
POxER
GENERATION
M KWH/YR














1750000
1750000
1750000
1750000
115.000.0.
1225000
1225000
1225000
1225000
1225LQO.fl
525000
525000
525000
525000
52500.0 	
17500000
EQUIVALENT COST, DOLLARS PER TON OF
POWER UNIT INET
FUEL CONSUMPTION, IN
TONS COAL/YR














685600
685800
685800
685800
, , ._ ., 6B5aQQ
480000
480000
480000
480000
AflQQQQ
205700
205700
205700
205700
__20 510.0 	 	
6857500
COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0% TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
ANNUAL INCREASE
COST OF POWER)
S














1197900
1166900
1135900
1104800
iaz.3.$.Q.a
890800
859700
828700
797700
	 26.6.6.0.0. 	
521700
490700
459600
428600
	 1216.00 	
12121000
1.77
0.69
6973000
L.02
0.40
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
t














1197900
2364800
3500700
4605500
	 56.12300
6570100
7429800
8258500
9056200
28.22&00
10344500
10835200
11294800
11723400
. 	 12121000



                                                                                                                                  N>
                                                                                                                                  M
                                                                                                                                  --J

-------
                                                        Table A-138


DRY tIMESTONE INJECTION,  REGULATED  POWER  CO.  ECON., 350 MW EX. C3AL FIRED POWER UNIT,  3.0J S  IN  FUELt  2.0  INJECTION  STOICHIOMETRY.

                                                FIXED  INVESTMENT:  $    3005900
ANNUAL OPERATING COST
YEARS
AFTER
POWER ANNUAL
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KWH/YR
1
2
3
4
6
7
8
9
1O
11
12
13
14
15 _ 	
16 5000
17 5000
18 5000
19 5000
_2.Q 	 5QQQ 	
21 3500
22 3500
23 3500
24 3500
25 25QQ
26 1500
27 1500
28 1500
29 1500
30 15.00
TOTAL 50000
EQUIVALENT COST, DOLLARS













1750000
1750000
1750000
1750000
-1Z5QQQQ 	
1225000
1225000
1225000
1225000
I225fl]0.fl
525000
525000
525000
525000
_52SQQQ_
17500000
PER TON OF
POWER UNIT (NET
FUEL CONSUMPTION, IN
TONS COAL/YR













689100
689100
689100
689100
	 6S21QQ 	
482300
482300
482300
482300
4fi23QQ
206700
206700
206700
206700
2.Q6ZQQ
6890500
COAL 8URNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED
EQUIVALENT PRESENT WORTH
EQUIVALENT PRESENT WORTH
AT 10.0*
TO INITIAL YEAR, DOLLARS
, DOLLARS PER TON OF COAL BURNED
, MILLS PER
KILOWATT-HOUR
ANNUAL INCREASE
COST OF POWER)
S













1858900
1817200
1775600
1733900
	 16922QQ 	
1369300
1327600
1285900
1244300
	 12Q26QQ 	
772200
730500
688300
647100
	 &Q55.QQ 	
18751600
2.72
1.07
10824500
1.57
0.62
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$













1858900
3676100
5451700
7185600
	 aaziflQQ_
10247100
11574700
12860600
14104900
1520.Z5QQ.
16079700
16810200
17499000
18146100
19. 7.5 16. 0.0






                                                                                                                               IV)
                                                                                                                               oo

-------
                                                       Table A-139


DRY LIMESTONE INJECTION,  REGULATED  POWER  CO.  ECON., 350 MW EX. COAL FIRED POWER UNIT, 3.0* S IN FUEL,  3.0  INJECTION  STOICHIOMETRY.

                                                FIXED  INVESTMENT:  $    3676800
                                                           ANNUAL OPERATING COST
YEARS
AFTER
POWER ANNUAL POWER
UNIT OPERATION, GENERATION
START KW-HR/KW M KWH/YR
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN COST OF POHERJ
TONS COAL/YR *
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
*
1
2
3
4
5
6
7
8
9
_10
11
12
13
14
16
17
IB
19
~21
22
23
24
25
26
27
28
29
o n


5000
5000
5000
5000
3500
3500
3500
3500
1500-
1500
1500
1500
1500
1500


1750000
1750000
1750000
1750000
1225000
1225000
1225000
1225000
525000
525000
525000
525000


692400
692400
692400
692400
6224.00
484700
484700
484700
484700
	 _4fl4.1QO 	 	
207700
207700
207700
207700
_ 2Q2IQQ _ _
TOTAL 50000 17500000 6924000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR


2501700
2450700
2399700
2348700
	 2222BQQ 	
1833200
1782200
1731200
1680200
	 1622200 	
1010900
959900
908900
857900
	 806300 	
25199100
3.64
1.44
14573700
2.10
0.83


2501700
4952400
7352100
9700800
11998600
13831800
15614000
17345200
19025400
21665500
22625400
23534300
24392200

                                                                                                                                IV)
                                                                                                                                CO

-------
                                                        Table A-
DRY  LIMESTONE INJECTION,  REGULATED POWER CO. ECON., 350 MW EX. CDAL FIRED POWER UNIT, 3.0* S IN FUEL, 4.0 INJECTION STOIC HIOMETRY.

                                                 FIXED INVESTMENT:  $    4262100
 YEARS
 AFTER
 POWER
 UNIT
 START
  ANNUAL
OPERATION,
 KW-HR/KW
  POWER
GENERATION
 M KWH/YR
   POWER UNIT
FUEL CONSUMPTION,
  TONS COAL/YR
ANNUAL OPERATING COST
 INCLUDING REGULATED
ROI FOR POWER COMPANY
 (NET ANNUAL INCREASE
  IN COST OF POWER)
TOTAL       50000           17500000           6957500               31268000
   EQUIVALENT COST,  DOLLARS  PER  TON OF  COAL BURNED                      4.49
   EQUIVALENT COST,  MILLS  PER  KILOWATT-HOUR                             1.79
PRESENT WORTH IF DISCOUNTED  AT  10.0? TO INITIAL YEAR,  DOLLARS      18110200
   EQUIVALENT PRESENT  WORTH, DOLLARS PER TON OF COAL BURNED             2.60
   EQUIVALENT PRESENT  WORTH, MILLS  PER  KILOWATT-HOUR                    1.03
 CUMULATIVE
NET INCREASE
 IN COST OF
   POWER,
      $
                             1750000            695800                3108900                  3108900
                             1750000            695800                3049800                  6158700
                             1750000            695800                2990700                  9149400
                             1750000            695800                2931600                 12081000
                             ilSflQttfl ___ 625_EQQ ________________ 21Z2.5aQ _______________ 142535Qfl_
                             1225000            487000                2268900                 17222400
                             1225000            487000                2209800                 19432200
                             1225000            487000                2150700                 21582900
                             1225000            487000                2091600                 23674500
                             U2.5.00Q ____ ifizaaa --------------- 2.fl3.250.Q _________________ 25IQZflflC.
                              525000            208700                1230400                 26937400
                              525000            208700                1171300                 28108700
                              525000            208700                1112200                 29220900
                              525000            208700                1053100                 30274000
                              525QQQ _______ 2CfilQQ ________________ 224.QQQ
                                                                                                                                   ro
                                                                                                                                   U)
                                                                                                                                   o

-------
                                                       Table A-lUl




DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON.,  50 MW EX. COAL FIRED POWER UNITt 5.0? S IN FUELi 1.0 INJECTION STOICHIOMETRY.


                                                FIXED INVESTMENT:  *     995300

YEARS
AFTER
POWER. ANNUAL
UNIT OPERATION,
START KW-HR/KW
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16 5000
17 5000
16 5000
19 5000
2_U 5.0QQ
21 3500
22 3500
23 3500
24 3500
2_5 35QQ 	
26 1500
27 1500
28 1500
29 1500
an 1 5DQ
	 jV_i^^ 	 . — _ Jh^MVi —
TOTAL 50000



POWER
GENERATION
M KWH/YR















250000
250000
250000
250000
25.UO.aQ 	
175000
175000
175000
175000
H5J}Q,Q 	
75000
75000
75000
75000
	 15.fl.UO. 	
2500000
EQUIVALENT COST, DOLLARS PER TON OF



POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR















98300
98300
98300
98300
	 2S3.UU 	 .
68800
68800
68800
68800
_&.aauu 	
29500
29500
29500
29500
_225J1U_ _
983000
COAL BURNED
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
$















502600
488800
475000
461200
. 	 iiiiOQ 	
361000
367200
353300
339500
	 _3252fla__ 	
233700
219900
Z06100
192300
	 liaSUQ 	 .
5172200
5.26

CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$















502600
991400
1466400
1927600
2.225.UUQ.
2756000
3123200
3476500
3816000
ilillflfl
4375400
4595300
4801400
4993700
	 	 _ 51.1220.0_


EQUIVALENT COST, MILLS PER KILOWATT-HOUR 2.07
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS 2953500
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED 3.00
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR 1.18
                                                                                                                                 ro
                                                                                                                                 u>

-------
                                                      Table A-1U2





DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON.,  50 MW EX.  COAL  FIRED  POWER  UNIT,  5.0?  S  IN  FUEL,  2.0  INJECTION  STOICHIOMETRY.



                                                FIXED INVESTMENT:   *    1332900
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER. ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
6
7
8
9
Ifl 	 	 	
11
12
13
14
15
16 5000
17 5000
18 5000
19 5000
_2,Q 	 _____5QQQ 	 	
21 3500
22 3500
23 3500
24 3500
25 35QO
26 1500
27 1500
28 1500
29 1500
30 1500


250000
250000
250000
250000
._2SQflQfl_
175000
175000
175000
175000
1T5QOQ -r- _
75000
75000
75000
75000
15QQO_


99100
99100
99100
99100
	 2210.0. 	 	
69400
69400
69400
69400
	 6.240.0. 	 	
29700
29700
29700
29700
297.00.
TOTAL 50000 2500000 991000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0? TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR


707500
689100
670600
652100
. 	 613.6J)0. 	
530600
512100
493600
475100
	 4566.Qfl 	 	
316600
298100
279600
261200
	 242.1QQ
7219100
7.28
2.89
4139200
4.18
1.66


707500
1396600
2067200
2719300
	 3_a5_22QQ
3883500
4395600
4889200
5364300
-5.8.209.0.Q
6137500
6435600
6715200
6976400
7.219J.QJ)

                                                                                                                                 oo

-------
                                                       Table A-1^3


DRY LIMESTONE INJECTION, REGULATED POWER CO. ECON.,  50 MW EX.  COAL FIRED  POWER  UNIT,  5.0*  S  IK  FUEL,  3.0  INJECTION  STOICHIOMETRY.

                                                FIXED INVESTMENT:   t    1602600
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POhER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UMT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR $
1
2
3
4
5
6
7
8
9
10
11
12
13
15
16 5000
17 5000
18 5000
19 5000
20 5000
21 3500
22 3500
23 3500
24 3500
26 1500
27 1500
28 1500
29 1500
3.Q 1 ?Q°



250000 99900
250000 99900
250000 9990C
250000 99900
25QflQfl 	 _222Qfl
175000 69900
175000 69900
175000 69900
175000 69900
75000 30000
75000 30000
75000 30000
75000 30000
75J3QQ 3QQQQ
TOTAL 50000 2500000 999000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10. OS TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR



892400
870200
848000
825800
665000
642800
620500
598300
	 576100 .
389300
367100
344900
322700
9067100
9.08
3.63
5211300
5.22
2.08
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$



892400
1762600
2610600
3436400
ft2.itQQ.SlQ
4905000
5547800
6168300
6766600
73_42_ZQQ
7732000
8099100
8444000
8766700
2Q6.11QQ

                                                                                                                                LO
                                                                                                                                00

-------
                                                       Table A-lM





DRY LIMESTONE INJECTION, REGULATED POWER CO.  ECON.,  50  MM  EX.  COAL  FIRED  POWER UNIT, 5-0* S  IN FUEL, 4.0 INJECTION STOICHIOMETRY,



                                                FIXED INVESTMENT:   $     1838700
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER. ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR $
1
2
3
4
5
6
7
8
9
10






CUMULATIVE
NET INCREASE
IN COST OF
POWER,
S


11
12
13
14
15
16 5000
17 5000
18 5000
19 5000
£0 	 _5QQQ 	
21 3500
22 3500
23 3500
24 3500
2.5 _25QQ_
26 1500
27 1500
28 1500
29 1500
1Q 1500
250000
250000
250000
250000
	 iSflCOQ-
175000
175000
175000
175000
1TSO.OO
75000
75000
75000
75000
25QQQ
100700
100700
100700
100700
1UQ1QQ 	 	
70500
70500
70500
70500
	 2Q5QQ_ _ 	 	 	
30200
30200
30200
30200
302QQ 	
TOTAL 50000 2500000 1007000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0? TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
1068700
1043200
1017700
992200
S6&1QQ 	
792900
767400
741900
716400
	 6.2Q2QQ
457500
432000
406500
3BIOOO
	 laasoa 	
10830500
10.76
4.33
6235100
6.19
2.49
1068700
2111900
3129600
4121800
	 SflflflSafl
5881400
6646800
7390700
8107100
BiaaoflQ
9255500
9687500
10094000
10475000
	 10.13.05.00.

                                                                                                                                a>

-------
                                                        Table  A-


DRY LIMESTONE INJECTION, REGULATED POWER CO.  ECON.,  150  MW  EX.  COAL FIRED POWER UNIT, 5.0* S IN FUEL, 1.0 INJECTION STOICHIOMETRY.


                                                FIXED  INVESTMENT:  $     1736200
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER ROI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/KW M KWH/YR TONS COAL/YR t
1
2
3
4
5
6
7
8
9
10
11
12
13
14
J-5
16 5000
17 5000
18 5000
19 5000
2Q 5QQQ
21 3500
22 3500
23 3500
24 3500
25 35DQ
26 1500
27 1500
28 1500
29 1500
•*n 1 "5DQ



750000 294800
750000 294800
750000 294800
750000 294800
»i5£oaa_ zaifiQQ.
525000 206400
525000 206400
525000 206400
525000 206400
525QQQ_ 	 ZQfiiHQ 	 	 	
225000 88500
225000 88500
2Z5000 88500
225000 88500
?25000 flflSQQ
TOTAL 50000 7500000 2948500
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10. OX TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR



928000
904000
879900
855800
	 __ aaiaaa 	
692600
668500
644500
620400
	 	 52&3.QQ 	 . 	
408500
384400
360300
336300
	 3JL220.Q 	
9423500
3.20
1.26
5413800
1.84
0.72
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$



928000
1832000
2711900
3567700
	 4.2225QQ_
5092100
5760600
6405100
7025500
	 -Z&ZlflQD
8030300
8414700
8775000
9111300
	 24225QQ

                                                                                                                                ro
                                                                                                                                co
                                                                                                                                en

-------
                                                        Table A-lU6




DRY LIMESTONE INJECTION,  REGULATED  POwER  CO.  ECON.,  150 MW EX.  COAL FIREO POWER UNIT, 5.OX S IN FUEL, 2.0  INJECTION  STOICHIOMETRY.



                                                 FIXED INVESTMENT:   $    2369500
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED
AFTER RQI FOR POWER COMPANY
POWER ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE
UNIT OPERATION, GENERATION FUEL CONSUMPTION, IN COST OF POWER)
START KW-HR/Kri M K.WH/YR TONS COAL/YR $
1
3
4
5.
6
7
8
9








CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$


11
12
13
14
16
17
1«
19
21
22
23
24
26
27
28
29
30
5000
DOOO
5000
5000
3500
3500
3500
3500
1500
1500
1500
1500
1500
750000
750000
750000
750000
525000
525000
525000
525000
225000
225000
225000
225000
225-Q.Oi)
^7200
297200
297200
297200
208100
208100
208100
208100
89200
89200
89200
89200
&32SQ
TOTAL 50000 7500000 2972500
EQUIVALENT COST, DOLLARS PER TON OF COAL UURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS
EQUIVALENT PKtSFNT WHRTH, COLLARS PER TON OF COAL BORNEO
EQUIVALENT PKtStNT WORTH, rtlLLS PER KILOWATT-HOUR
1420300
1387400
1354500
1321700
1048700
1015900
983000
950100
596500
563700
530800
497900
14341700
4.82
1.91
8271800
2.78
1.10
1420300
2807700
4162200
5483900
&112.13S
7821400
8837300
9820300
10770400
	 llfcfillQQ
12284200
12847900
13378700
13876600

                                                                                                                                   r

                                                                                                                                   ro
                                                                                                                                   GO
                                                                                                                                   01

-------
                                                         Table  A-1^7


DRY LIMESTONE  INJECTION,  REGULATED  POWER  CO.  ECON.,  150 MW EX.  COAL FIRED POWER UNIT, 5.0*  S  IN  FUEL,  3.0 INJECTION STOICHIOMETRY.

                                                 FIXED INVESTMENT:  t    2926600
YEARS
AFTER
POWER ANNUAL
UNIT OPERATION,
START KW-HR/Kw
POWER
u,ENERAT ION
M KrtH/YR
POWER UNIT
FUEL CONSUMPTION,
TONS COAL/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
$
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
1
2
3
4
6
7
8
9
11
12
13
14
1,5
16 5000
17 5000
18 5000
19 5000
2fl 5.J20J2
21 3500
22 3500
23 3bOO
24 3500
2i_ 3.5_iJO_
26 1500
27 1500
28 1500
29 1500
30 1..5.0.0.

750000
750000
750000
750000
Z5.flQ.ilO.
525000
525000
525000
525000
5.25.0.00.
225000
225000
225000
225000
22520.0.

299700
299700
299700
299700
_ 222iQfl
209800
209800
209800
209800
_2 0230.0.
89900
89900
89900
89900
89900.

1914300
1873800
1833200
1792600
	 	 1Z.52.QP_Q
1406500
1365900
1325400
1284800
783400
742800
702300
661700
TOTAL 50000 7500000 2997000 19304000
EQUIVALENT CUST, DOLLARS PF.R TON CF COAL BURNED 6.44
EQUIVALENT CCST, MILLS PER KI LOwATT-HUUR 2.57
PRESENT «ORTH IF DISCOUNTED AT 10.0* TO INITIAL YEAR, DOLLARS 11153800
EgUIVAL^NT PKtSFNT WURTH, DOLLARS PER TON OF CGAL BURNED 3.72
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR 1.49

1914300
3788100
5621300
7413900
10572400
11938300
13263700
14548500
16576100
17318900
18021200
18682900
._ _ 123.0.4.0.QQ

                                                                                                                                   1\D
                                                                                                                                   00

-------
                                                         Table A-


DKY LIMESTONE  INJECTION,  REGULATEJ  POWER CO.  ECON.,  150 MW EX.  COAL FIAED POWER UNIT, 5.0? S IS FUEL, 4.0 INJECTION STDICHIOMETRY.

                                                 FIXED INVESTMENT:   $    3376200

YEARS
AFTER.
PUrtER. ANNUAL
L.N1T OPERATION,
START KW-HR/KW
i
2
4
0
7
ANNUAL OPERATING COST
INCLUDING REGULATED
KOI FOR POWER COMPANY
POWER POWER UNIT (NET ANNUAL INCREASE
GENERATION FUEL CONSUMPTION, IN COST OF POWER)
M KWH/YR TONS COAL/YR $





CUMULATIVE
NET INCREASE
IN COST OF
POWER,
I




  9


"ll"


 13
16 5COO
i7 5000
16 5000
19 5000
20. SflQH
21 3500
2^ 35CC
23 3500
^4 3500
26 1500
27 1500
2o 1500
^9 1500
10 1,500
750000
750000
750000
750000
Z5Q.Q.Q.Q 	
525000
525000
525000
525000
225000
225000
225000
225000
302100
302100
302100
302100
	 .3.0.20.20. 	
211500
211500
211500
211500
	 211500. 	
90600
90600
90600
90600
TbTAL 50000 7500000 3021000
EQUIVALENT COST, DOLLARS PER TON OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PkESENT *ORTH IF DISCOUNTED AT 10.02 TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
tUUlVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR
2362800
2316000
2269200
2222400
_ 2J.156.Q.Q 	
1728700
1681900
1635100
1588300
946900
900100
853300
806500
23788000
7.87
3.17
13765400
4.56
1.84
2362800
4678800
6948000
9170400
113.463.23
13074700
14756600
46391700
17980000
20468400
21368500
22221800
23028300

                                                                                                                                OJ
                                                                                                                                00

-------
                                                        Table  A-


DRY LIMESTOME INJECTION,  REGULATED POWER  CO.  ECON.,  250  MW  EX.  COAL FIRED POWER UNITt 5.0% S IN FUELt 1.0 INJECTION STOICHIOMETRY.

                                                FIXED  INVESTMENT:   $     2314500
ANNUAL OPERATING COST
YEARS INCLUDING REGULATED CUMULATIVE
AFTER ROI FOR POWER COMPANY NET INCREASE
POWFR ANNUAL POWER POWER UNIT (NET ANNUAL INCREASE IN COST OF
UNIT JPERATIOIM, GENERATION FUEL CONSUMPTION, IN COST OF POWER) POWER,
START KW-HR/KW M KWH/YR TONS COAL/YR , $ $
1
2
3
4
__5 	
6
7
8
9
JU)
11
12
13
14
16
17
18
19
2fl
21
22
23
24
25
26
27
28
29
30



5000
5000
5000
5000
3500
3500
3500
3500
^.^.il^l
1500
1500
1500
1500
15ilil



1250000
1250000
1250000
1250000
875000
375000
d75000
875000
375000
375000
375000
375000



491400
491400
491400
491400
_ 4214Q12
344000
344000
344000
344000
147400
147400
147400
147400
TOTAL 50000 12500000 4914000
EQUIVALENT CUST, DOLLAKS PER TON OF COAL BURNED
EQUIVALENT COST, HILLS PER KILOWATT-HOUR
PRESENT MIRTH IF DISCOUNTED AT 10.0% TO INITIAL YEAR, DOLLARS
EQUIVALENT PRESENT WORTH, DOLLARS PER TON OF COAL BURNED
EOUIVALFNT PKESENT WORTH, HILLS PER KILOWATT-HOUR



1301100
1269000
1236900
1204800
JLLlZZSfl
964400
932300
900300
86S200
557500
525400
493300
461200
13152300
2.68
1.05
7575100
1 .54
0.61



1301100
2570100
3807000
5011800
7148900
8081200
8981500
9849700
11243300
11768700
12262000
12723200

                                                                                                                                co
                                                                                                                                10

-------
                                                        Table A-150




DRY LIMESTONE  1NJECMON,  REGULATED  POWER  CO.  ECON.,  250 Md EX.  COAL FIREO POWER UNIT, 5.0* S  IN FUEL,  2.0  INJECTION STOICHIOMETRY.



                                                 FIXED INVESTMENT:   $    3221100
ANNUAL OPERATING COST
YEAKS
AFTFR
INCLUDING REGULATED
ROI FOK POWER COMPANY
POWER ANNUAL
UNIT OPERATION,
START K,
1
2
3
4
5 __
6
7
a
9
ifl —
11
12
13
_15 _
16
17
18
19
20
21
22
23
24
Z5
26
27
28
29
_3Q
TOTAL 5
EQUIVALENT
tgulVALENT
PRESENT v»i.UTH
EQUIVALENT
EQUIVALENT
i-HK/Kri













5000
5000
5000
5000
*t££3.
3500
3500
3500
3500
JiSilii
1500
15uO
1500
1500
liUii
0000
cusr, u
CHST, v,
POWER
GENERATION
M KWH/YR













1250000
1250000
1250000
1250000
Ii.ii20.li
875000
875000
875000
875000
iii5jiiii
375000
375000
375000
375000
ili^iiii _
12500000
DLLARS PER TON OF
POwER UNIT (NET
FUEL CONSUMPTION, [N
TONS COAL/YR













495400
495400
495400
495400
_4.9..5.4.Qi! 	
346800
346800
346800
346800
_ liJifiail 	
148600
148600
146600
14S600
1466QO
4954000
COAL BURNED
ILLS PER KILOwATT-HOUR
IF DISCJUI.TtU AT 10. OS
PhLSENT
PRbSHNT
TO INITIAL YEAR, DOLLARS
nURTh, DOLLARS PER TON OF COAL BURNED
WORTH, MILLS PER
KILOWATT-HOUR
ANNUAL INCREASE
COST OF POWER!
$













2095700
2051000
2006400
1961700
J.91710Q
1539000
1494300
1449700
1405000
JJi£0_4.i)0_
857000
812400
767700
723000
678400
21118800
4.26
1.69
12204500
2.46
0.98
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$













2095700
4146700
6153100
8114800
1QQ212QQ
11570900
13065200
14514900
15919900
172SQ3DQ
18137300
18949700
19717400
20440400
21 i i 8800






                                                                                                                                   ro
                                                                                                                                   -ti
                                                                                                                                   o

-------
                                                          Table  A-151





DRY LIMESTONE.  INJECTION,  REGULATED PO«ER CO. ECON., 250 Mw  EX.  COAL  FIRED  POWER UNIT, 5.0* S IN FUEL, 3.0  INJECTION STOICHIOMETRY.




                                                 FIXFD  INVESTMENT:   $    3968400

YEARS
AFTER
P0.it R
UNIT
START
1
2
3
4
6
7
8
9
LO
11
12
13
16
17
18
19
21
22
23
24
26
27
28
29
TOTAL
L'JUl
tjU I
PRESENT



ANNUAL
o°FKATini-;,
K.W-HI-./KW











5000
50 JO
5000
5JUJ
j500
3500
3500
j500
1 500
15JO
1500
I SOU
5 0 0 0 ~j
VALFNT CuST, DC
VALi-.\T C'JST, M
W )KTM U DliCO
EQUIVALENT P-'.LS'.\T

VALi:.\iT Pi-K SFM



POrtER
GENERATION
M KwH/YR











1250000
1250000
1250000
123000J
875000
675000
875000
875000
375000
375000
375000
375000
1250JOOO
LLA°S PER TJN
LLS PEK KILGnA
U "1 T t 0 AT 10.0
AJRTH, OGLL^SS
nJHTH, •I ILLS P



PQwER UNIT
FUEL CONSUMPTION,
TONS CCJAL/YR











499400
499400
499400
499400
349600
349600
349600
349600
149dOO
149aGO
149800
149&00
4994000
OF CJAL HUKNFO
TT-H'JU^
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
IN COST OF POWER)
$











2838200
2783200
2728200
2673100
2072 300
2017300
1962300
1907200
1127100
1072000
1017000
961900
28537000
5. 71
2. 29

CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$











2838200
5621400
8349600
11022700
15713100
17730400
19692700
21599900
24579200
25651200
26668200
27630100



S. TO INITIAL YEAR, DOLLARS 16526400
PER TON iJF COAL RURNEO
EK KIL'.lwATT-riOUR
3.31
1.32


                                                                                                                                    N>

-------
                                                        Table A-152






DRY LIMESTUN^  INJECTION,  REGULATED  POrtER  CO.  ECON.,  250 MW EX. COAL FIRED POWER UNIT, 5.0?  S  IN  FUEL,  4.0  INJECTION STOICHIOHETRY.




                                                 FIXED INVESTMENT:  $    4582000
ANNUAL OPERATING COST
YEARS
AFTER
PO*ER
UNIT
START
1
2
3
4
5.
6
7
8
9
ID
11
12
13
15
16
17
18
19
22
21
22
23
24
25
26
27
28
29
3J.
TOTAL
INCLUDING REGULATED

ANNUAL
UPbRATIOM,
Krt-HR/Kw













5000
5000
5000
5000
Siiiiii
3500
35CO
3500
3500
A^.Q.11
1500
1500
150o
1500
liiiii
5^u0
EQUIVALENT Ct.ST, U(
EUUI VAL
PRESENT M.I
FOUIVAL
C 0 U 1 V A L

POWER
oENERAT ION
M KrtH/YR













1250000
1250000
1250300
1250000
125222.2
875000
375000
875000
875000
.8.25222
375000
375000
375000
375000
3 75QQO
12500000
ROI
FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION, IN
TONS COAL/YR













503500
503500
503500
503500
50350Q
352500
352500
352500
352500
iiZiuil
151100
151100
151100
151100
151122
5035500
"iLLARS PER TON OF COAL BURNED
F.NT CiiST, MILLS PER KILOHlAT
i

-------
                                                        Table  A-153

DRY LIMESTONE INJECTION,  REGULATED  POWER  CO.  FCON., 350 MW EX. COAL FIRED POWER UNIT, 5.0? S IN FUEL,  1.0 INJECTION STOICHIOMETRY.

                                                FIXED  INVESTMENT:  $    2782700
ANNUAL OPERATING COST
YEARS
AFTER
POWER
UNIT
START
1
2
3
4
6
7
8
9
11
12
13
16
17
18
19
20
21
22
23
24
26
27
28
29
TOTAL
EQL1
L JUI
PREStM
PQUl
LiJUl
INCLUDING REGULATED
ROI FOR POWER COMPANY
ANNUAL
OPERATION,
K*-Hk/K*










5000
5000
5300
5000
iilsii! *.
3500
35'OU
« Sou
Jpu
1500
1500
1500
;^j'
50000
VALFNf Ci ST , Di
VALHM C:-!-'»T
TO INITIAL YEAS, DOLLARS
K.JRTH, !>JLLARS PER TUN OF COAL bURNtO
rt'.jpTh, MILLS PER
KILOwATT-HOUR
NET ANNUAL INCREASE
IN COST OF POWER)
$










1639600
1601000
1562400
1523800
L^L&5.£.Q.Q.
1209900
1171300
1132700
1094100
688800
650200
611600
573000
16533600
2.40
0.94
9538500
1.39
0.55
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$










1639600
3240600
4803000
6326800
- _ laiZlflfl
9022000
10193300
11326000
12420100
14164400
14814600
15426200
15999200






                                                                                                                                r
                                                                                                                                IV)
                                                                                                                                00

-------
                                                          Table A-15U
ORV LlMESTGl\iF  INJECTl-d\,  REGULATED POWER CO.  ECON.,  350 Mrf EX. COAL FIRED POWER  UNIT,  5.03! S IN FUEL, 2.0  INJECTION STOICHIOMETRY.




                                                  FIXEO INVESTMENT:  $    3927000
YEARS
AFTER
POWER ANNUAL P'JWFR
UNIT OPERATION, GENERATION
START Kn-HR/KW M KiriH/YR
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
POWER UNIT (NET ANNUAL INCREASE
FUEL CONSUMPTION', IN COST OF POWER)
TONS COAL/YR $
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$
1
2
3
4
6
7
e
9
11
12
13
15. __
16
17
18
19
21
22
23
24
26
28
29

5000
5000
5000
5000
3500
3500
3500
3500
1500
1500
1500
1500
liUil

1750000
1750000
1750000
1750000
1225000
1225000
1225000
1225000
525000
525000
525000
525000
iZSjJOO

69 3 60 0
693600
693600
693600
485500
485500
485500
485500
2C8100
208100
208100
208100
TOTAL 50000 17500000 6936000
EQUIVALENT GUST, DOLLARS PER TUN OF COAL BURNED
EQUIVALENT COST, MILLS PER KILOWATT-HOUR
PRESENT WORTH IF DISCOUNTED AT 10.02 TO INITIAL YEAR, DOLLARS
EQUIVALENT PREScMT wOKTH, DOLLARS PER TON OF COAL BURNED
EQUIVALENT PRESENT WORTH, MILLS PER KILOWATT-HOUR

2714000
2659600
2605100
2550700
1984700
1930300
1875800
1821400
	 1I662.Q.Q. _
1087300
1032800
978400
923900
27296600
3.94
1.56
15799300
2.28
0.90

2714000
5373600
7978700
10529400
15010300
16940600
18816400
20637800
23492000
24524800
25503200
26427100
2122660.0_


-------
                                                       Table A-155


DRY LIMESTCM- INJECTION,  REGULATED  POWER  CO.  ECON., 350 NU EX. COAL FIRED POWER UNIT,  5.0? S IN FUEL,  3.0  INJECTION  STOICHIOMETRY.

                                                FIXED  INVESTMENT:  $    4766400

YEARS
AFTER
POWER ANNUAL
UNIT OPERATION
START K'rt-HP/Kn
1
2
3
4
-5.
6
7
9
10 _
11
12
13
16 5JOO
17 5JOJ
18 50UO
19 ?JuU
2fl iUGy
21 J50U
22 J5UO
23 j5>jo
24 35UO
25 3-5. 00
26 l^OU
27 1500
28 15JU
29 15Ju
TUTAL 'jOOOO
EQUIVALENT CuST,
EQUIVALENT COST,



POWER
, GENT RAT I ON
M KrtH/YR












1750000
1750000
1 750000
1 750JOO
llidiilifl _
1225000
1225000
1225000
1225000
IZZSiiiia _
525000
525JOO
525000
525000
1 75JOOOO
DOLLARS PER TON GF-



POWER UNIT
FUFL CONSUMPTION
TONS COAL/YR












699200
699200
699200
699200
69V200
489400
489400
489400
469400
4-&24.^Q
209300
209800
209800
209800
6992000
COAL BURNED
M1LLS PER KI LOrtATT-HOUR
PRESENT wOKTn IF DISCOUNTED AT 10. (H
EQUIVALENT PRl-Sh
tuU IVAL EM P.-!:-S !•
TO INITIAL YEAR, D'.
ANNUAL OPERATING COST
INCLUDING REGULATED
ROI FOR POWER COMPANY
(NET ANNUAL INCREASE
, IN COST OF POWER)
$












3691200
3625100
3559000
3492900
34,26.800
2685700
2619600
2553500
2487400
24.Z.1.3..0..Q
1437000
1370900
1304800
1238700
37086500
5.30
2.12
1LLARS 21504200

CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$












3691200
7316300
10875300
14368200
-UJSiJiJi)
20480700
23100300
25653800
28141200
•3.Q.5.&2.500
31999500
33370400
34675200
35913900




NT m.iRTH, DOLLARS PER TON OF COAL bURNEL) 3.08
NT nijivTH, MILLS PFR
KILOWATT-HOUR
1.23

                                                                                                                               r
                                                                                                                               ro
                                                                                                                               en

-------
                                                           Table  A-156


DRY Ll'-ttSTLJNb  i ,MJ EOT 10i\, REGULATED  POWER CO. ECON., 350  MW  fcX.  COAL FIRED POWER UNIT,  5.0? S IN FUEL, 4.0  INJECTION STOICHIOMETRY.

                                                  FIXED  INVESTMENT:   t    5645500
ANNUAL OPERATING COST
YEAKS
AFTFK
POwER ANNUAL
UNIT OPERATION
STAKT K'4 — Hri/KW
1
2
3
-5. _
6
7
9
11
13
16 5000
17 5000
18 500U
19 5000
20 3QQO
21 J.50U
22 3500
23 J500
24 J500
25 -i5.flii
26 1500
n isuo
28 1500
29 15uO
.3J1 	 15iii)
TOTAL 50000
EQUIVALENT COST,
EQUIVALENT CuST,
PRESENT h,jiTH IF 01
EQUIVALENT PRbSi-
EQUIVALKNT PKi.-SH
INCLUDING REGULATED

POWE*
, GENERATION
M KWH/YR









1750000
1 750000
1750000
1750000
l.Z5.Qj2i}iJ
1225000
1225000
1225000
1225000
iZZiJiiv
525000
525000
525000
525000
525.0..Q.Q
17500000
DOLLARS PER TON OF
R(.!
POWER UNIT (
FUEL CONSUMPTION,
TONS COAL/YK









705000
705000
705000
705000
.ZU50_^0_
493500
493500
493500
493500
493500
211500
211500
211500
211500
2115242
7050000
COAL BURNEO
i-tlLLS PER KILOWATT-HOUR
SC(JUNTliD AT 10.0*
TO INITIAL YEAR, DOLLARS
NT KlmTH, DOLLARS PER TON OF CUAL BURNED
NT wDRTH, MILLS PER
KILOWATT-HOUR
I FOI< POWER COMPANY
NET ANNUAL INCREASE
IN COST OF POWER)
t









4708000
4629700
4551400
4473100
4394800
3416000
3337700
3259400
3181100
3102800
1802000
1723700
1645400
1567100
	 1488800
47281000
6.71
2.70
27443100
3.89
1.57
CUMULATIVE
NET INCREASE
IN COST OF
POWER,
$









4708000
9337700
13889100
18362200
22 75 7000
26173000
29510700
32770100
35951200
39054000
40856000
42579700
44225100
45792200
472Q 1QQQ






                                                                                                                                      ro
                                                                                                                                      •P»
                                                                                                                                      01

-------
                                        L-247
I. Title and Subtitle
^itU'ur Oxide Removal from Power Plant Stack Gas by Dry
Limestone Injection--Full Scale Demonstration  and Support
Projects (Volumes T;  TTJ and ITT)	;
'. Autlior(s)
F. E. Gartrell	
 BIBLIOGRAPHIC DATA
 SHEET
                   1. Id-port No,
                    EPA-650/2-73-019-a, -b, -c
                                                               3. Recipient's Accession No.
                                                                5. Report Date
                                                                 August 1973
                                                                6.
                                                                8- Performing Organization Kept.
                                                                 No.
9. Performing Organisation Name and Address
Tennessee Valley Authority
Chattanooga, Tennessee  37401
                                                               10. Project/Task/Work Unit No.
                                                               11. Contract/Grant No.
                                                               iiteragency Agreement
                                                                  TV-30541A
 12. Sponsoring Organization Name and Address
 EPA, Office of Research and Development
 NERC-RTP, Control Systems Laboratory
 Research Triangle  Park, North Carolina 27711
                                                               13. Type of Report & Period
                                                                  Covered
                                                                      Final
                                                               14.
 15. Supplementary Notes
 16. Abstracts ,pne repOrt gives results of a test program of dry limestone injection,
 demonstrated on a 150-Mw pulverized-coal-fired boiler at TVA's Shawnee Plant. The
 program included: equipment shakedown, dust distribution studies, process optimi-
 zation, and long-term injection trials. It identified major process  variables; evaluated
 distribution of lime dust in the boiler, effect of operating variables on distribution,
 and resulting effects on SO2 removal; evaluated  the sensitivity of SO2 removal to key
 operating and process variables; evaluated conditions for optimum SO2 removal;
 studied process effects on boiler operation and maintenance, on solids collection
 equipment, and on water quality; and completed  a process economics  study.  The pro-
 gram is discussed in context with previous investigations and EPA-sponsored sup-
 port activities. Appendices contain test program detail results  and results of EPA
 support projects. Because of low SO2 removal efficiencies and  the potential for major
                                              reliability problems  , it does not appear
                                              that  dry limestone injection will  play an
                                              important role in  controlling SO2 emis-
                                              sions from power plants.
 17. Key Words and Document Analysis.  17o. Descriptors
Air Pollution
Coal
Desulfurization
Limestone
Boiler
Dust
Sulfur Dioxide
Calcium Oxides
Economic Analysis
17b. Identifiers/Open-Ended Terms
Air Pollution Control
Stationary Sources
Dry Limestone Injection
17c. COSATI Field/Group  13B, 14A
Reliability
Electric Power Plants
Flue Gases
 18. Availability Statement
                       Unlimited
                                                     19.. Security Cla.'is (This
                                                       Report)
                                                     20. Security (,lass (This
                                                        Page
                                                     	UNCI.ASSII-MKO
                                                      21. No. of Pages
                                                           356
                                                                         22. Price
KO«M NTIS-35 IRtV. 3-/2)
                                                                          USCOMM-OC 14952-P72

-------