EPA 430/9-75-021
                  HANDBOOK
                      FOR
        SEWER SYSTEM  EVALUATION
             AND REHABILITATION
                   DECEMBER 1975

                  TECHNICAL REPORT
         U.S. ENVIRONMENTAL PROTECTION AGENCY
          OFFICE OF WATER PROGRAM OPERATIONS
               WASHINGTON, D.C. 20460
                                          MCD-19

-------
             HANDBOOK

                FOR

      SEWER SYSTEM EVALUATION

        AND REHABILITATION
  Municipal Construction Division
Office of Water Program Operations
  Environmental Protection Agency
      Washington, D.  C.  20460

           December 1975
                                            MOD-19

-------
             HANDBOOK

                FOR

      SEWER SYSTEM EVALUATION

        AND REHABILITATION
  Municipal Construction Division
Office of Water Program Operations
  Environmental Protection Agency
      Washington, D. C.  20460

           December 1975
                                            MCD-19

-------
                          Foreword
     The extraneous flow associated with infiltration-inflow
(I/I) has long been recognized as a major factor in treatment
facility performance.  The impact on stream pollution has been so
great that the subject of I/I must be fully addressed in any
realistic water pollution control program.   For this reason, the
Federal Water Pollution Control Act Amendments of 1972 requires
that after July 1, 1973 all  grant applicants must identify and
correct excessive I/I for each sewer collection system discharg-
ing into treatment works proposed for grant assistance.   The
requirement was implemented in the Construction Grant Regulat-
ions, Section 40 CFR 35.927, and in the Guidance for Sewer System
Evaluation published in March 1974.

     This handbook is not a design manual.   It is primarily a
supplement to the Guidance for Sewer System Evaluation and
accordingly, it contains technical information and describes the
methodology necessary for an effective investigation and correction
of I/I conditions in a sewer system.  Also included is a set of
cost curves showing the correlation between the cost for each
phase of sewer system evaluation work and variables such as sewer
length, population, and magnitude of I/I.  Additionally, the
handbook contains a special  chapter entitled "User's Guide". It
is emphasized that this chapter should be carefully read before
using the manual.

     The handbook does not contain any regulatory materials or
mandatory requirements.  To the contrary, it is designed to
provide a wide range of information on conditions found in all
the various types of sewer systems.  For this reason, it is
essential that the user of the handbook select only those tech-
niques applicable to a particular system in order to generate the
necessary information. Brevity and simplicity are encouraged.

     It is the intention of the Environmental Protection Agency
to revise and update this handbook as new and improved techniques
are developed through experience.  All users are encouraged to
submit any pertinent information to the Director, Municipal
Construction Division (WH 547), Office of Water Program Operations,
U.S. Environmental Protection Agency, Washington, DC  20460.
                                   Andrew W. ^Breidenbach
                                   Assistant Administrator
                                   Water and Hazardous Materials

-------
            NOTICE

THIS REPORT HAS BEEN REVIEWED BY
EPA, AND APPROVED FOR PUBLICATION.
APPROVAL DOES NOT SIGNIFY THAT THE
CONTENTS NECESSARILY REFLECT THE
VIEWS AND POLICIES OF THE ENVIRON-
MENTAL PROTECTION AGENCY, NOR DOES
MENTION OF TRADE NAMES OR COMMERCIAL
PRODUCTS CONSTITUTE ENDORSEMENT OR
RECOMMENDATION FOR USE.

-------
                          ABSTRACT


Guidance has been provided to assist in the preparation and
review of Infiltration/Inflow Analyses and Sewer System Evaluation
Surveys.  In addition, information is given on the techniques
of sewer rehabilitation and the costs related to Evaluation
Survey and Rehabilitation.

The handbook contains chapters on:  (1)  methodology for
conducting I/I Analysis, (2)  methodology for conducting
Sewer System Evaluation Survey, (3) information on current
state-of-the-art techniques for sewer rehabilitation and
(*0 costs associated with conducting Sewer System Evaluation
Survey and rehabilitation.

The chapters on methodology explain in detail each of the
specific tasks that may be required in conducting I/I Analysis
and Sewer System Evaluation Survey.  The methodology presented
is proven current state-of-the-art techniques.  Other techniques
not presented may be applicable and their use is encouraged.
The sewer rehabilitation techniques presented have been obtained
from specialists in the particular field and are provided
for Information purposes only.

To assist in proper use of this handbook, a chapter on User
Guide is prepared (Chapter 2).  THE READER SHOULD READ THAT
CHAPTER BEFORE GOING THROUGH OTHER CHAPTERS.
                            ii

-------
                      TABLE OF CONTENTS

CHAPTER                                 PAGE              PAGE

          Title Page                                        i

          Abstract                                         H

          Table of Contents                               ill

          List of Tables                                    v

          List of Figures                                 vii

  1       Introduction                                    1-1

          1.1  Introduction                               1-1
          1.2  Purpose                                    1-6
          1.3  Format                                     1-6
          1.4  Overview                                   1-7
          1.5  Implementation                             1-9

  2       User's Guide                                    2-1

          2.1  Introduction                               2-1
          2.2  I/I Analysis                               2-1
          2.3  Sewer System Evaluation Survey             2-2
          2.4  Sewer System Rehabilitation                2-2
          2.5  Costs                                      2-2

  3       Infiltration/Inflow Analysis                    3-1

          3.1  Introduction                               3-1
          3.2  Background Information                     3-2
          3.3  Determination of  Infiltration/Inflow        3-58
          3.4  Cost-Effectiveness  Analysis                3-71
          3-5  Establishment of  Excessive  or Non-          3-8?
                 excessive Infiltration/Inflow
          3.6  Sewer System Evaluation Survey Program      3-93
                 Recommendation

  4       Sewer System Evaluation  Survey                   4-1

          4.1  Introduction                               4-1
          4.2  Physical Survey                            4-2
          4.3  Rainfall Simulation                        4-10
          4.4  Preparatory Cleaning                        4-19
          4.5  Internal Inspection                        4-24
          4.6  Survey Report                              4-32
                             ill

-------
CHAPTER
APPENDIX
      TABLE OF CONTENTS (Continued)

                                                PAGE

Sewer System Rehabilitation                     5-1

5.1  Introduction                               5-1
5.2  Excavation/Replacement                     5-4
5.3  Chemical Grouting                          5-4
5.4  Pipe Lining With Polyethylene Pipe         5-13
5-5  Pipe Lining With Fiberglass Reinforced     5-19
       Polyester Mortar Pipe
5.6  Pipe Lining With Cement Mortar and         5-21
       Epoxy Mortar

Costs for Sewer System Evaluation Survey and    6-1
Rehabilitation

6.1  Introduction                               6-1
6.2  Sewer System Evaluation Survey Costs       6-1
6.3  Rehabilitation Costs                       6-31
          A.  References                                  A-l

          B.  State Certification                         B-l

          C.  Glossary of Terms                           C-l

          D.  Metric Conversion Table                     D-l
                             Iv

-------
                       LIST OF TABLES
NO.                                                       PAGE
2-1       Check List for Conducting Infiltration/         2-4
            Inflow Analysis
2-2       Check List for Conducting Sewer System          2-5
            Evaluation Survey
3-1       Infiltration/Inflow Analysis -                  3-6
            Interview Form
3-2       Properties of Commonly Used Tracer Dyes         3-18
3-3       Typical Data Sheets for the Inventory           3-22
            of Existing Sewer System
3-4       Safety Equipment for Manhole and Sewer          3-56
            Inspection
3-5       Work Sheet for Quantity Take-off and            3-78
            Cost Estimation - Sewer System
            Evaluation Survey
3-6-       Work Sheet for Quantity Take-off and            3-79
            Cost Estimation - Sewer System
            Rehabilitation
3-7       Determination of Priority for Evaluation
            Survey - An Example                           3-90
3-8       Determination of Costs - An Example             3-90
4-1       Typical Data Sheet for Manhole                  4-7
            Inspection
4-2       Typical Data Sheet for Sewer                    4-8
            Inspection
4-3       Characteristics of Sewer Cleaning               4-22
            Equipment
4-4       Typical Television Inspection Log               4-28
            Sheet
5-1       Infiltration/Inflow Sources and                 5-2
            Correction Methods
5-2       Typical Compositions of Acrylamide Gel          5-8
            Grouting Mixes
6-1       Costs for Sewer System Evaluation Survey        6-2
6-2       Physical Survey Cost Criteria                   6-3

-------
                  LIST OF TABLES (Continued)



NO.                                                    PAGE



6-3       Rainfall Simulation Cost Criteria            6-4



6-4       Sewer Cleaning Cost Criteria                 6-5



6-5       Internal Inspection Cost Criteria            6-6



6-6       Sewer Replacement Cost Criteria              6-34



6-7       Pipe Lining Cost Criteria                    6-36



6-8       Sewer Line Grouting Cost Criteria            6-38



6-9       Miscellaneous Rehabilitation Costs           6-39
                             vi

-------
                       LIST OP FIGURES

NO.                                                       PAGE

3-1       Typical Groundwater Gauge Installation          3-30
            in Manhole

3-2       Typical Groundwater Gauge Installation          3-31
            in Soil

3-3       Temperature Correction Curves for Dyes          3-46

3-4       Floating Bowl Solution Feeder                   3-48

3-5       Floating Platform Solution Feeder               3-49

3-6       Determination of Total Yearly                   3-63
            Infiltration/Inflow

3-7       Determination of Total Yearly                   3-65
            Infiltration

3-8       Determination of Peak Inflow                    3-67

3-9       Cost-Effectiveness Analysis - Possibly          3-84
            Excessive Infiltration/Inflow (Method 2)

3-10      Cost-Effectiveness Analysis - Non-              3-85
            excessive Infiltration/Inflow (Method 2)

3-11      Cost-Effectiveness Analysis - Possibly          3-88
            Excessive Infiltration/Inflow (Method 3)

3-12      Cost-Effectiveness Analysis - Non-              3-89
            excessive Infiltration/Inflow (Method 3)

3-13      Determination of Optimal Design Flow -          3-92
            An Example

4-1       Typical Arrangement for Television              4-26
            Inspection of Sewer Lines

4-2       Laboratory Test for Estimating                  4-30
            Infiltration/Inflow Rates

4-3       Cost Curves for Cost-Effectiveness              4-37
            Analysis in Evaluation Survey

5-1       Effect of Catalyst Concentration and            5-7
            Temperature on Acrylamide Gel Set
            Time

5-2       Typical Arrangement for Chemical                5-10
            Grouting with Acrylamide Gel

5-3       Remote Connection of House Service              5-18
            Line Through Sewer Pipe

                             vii

-------
                 LIST OF FIGURES  (Continued)

NO.                                                    PAGE

5-4       Remote Connection  of House Service           5-18
            Line Through New Drilled Hole

6-1       Total Evaluation Survey Cost vs. Sewer       6-7
            Length

6-2       Total Evaluation Survey Cost vs. Peak        6-8
            Infiltration/Inflow

6-3       Total Evaluation Survey Cost vs. Sewered     6-9
            Population

6-4       Total Evaluation Survey Cost vs. Sewage Plow 6-10

6-5       Physical Survey Cost vs. Sewer Length        6-11

6-6       Physical Survey Cost vs. Peak Infiltration/  6-12
            Inflow

6-7       Physical Survey Cost vs. Sewered Population  6-13

6-8       Physical Survey Cost vs. Sewage Plow         6-14

6-9       Rainfall Simulation Cost vs.  Sewer Length    6-15

6-10      Rainfall Simulation Cost vs.  Peak            6-16
            Infiltration/Inflow

6-11      Rainfall Simulation Cost vs.  Sewered         6-17
            Population

6-12      Rainfall Simulation Cost vs.  Sewage Plow     6-18

6-13      Preparatory Cleaning Cost vs. Sewer Length   6-19

6-14      Preparatory Cleaning Cost vs. Peak           6-20
            Infiltration/Inflow

6-15      Preparatory Cleaning Cost vs. Sewered        6-21
            Population

6-16      Preparatory Cleaning Cost vs. Sewage Plow    6-22

6-17      Internal Inspection Cost vs.  Sewer Length    6-23

6-18      Internal Inspection Cost vs.  Peak            6-24
            Infiltration/Inflow

6-19      Internal Inspection Cost vs.  Sewered         6-25
            Population

6-20      Internal Inspection Cost vs.  Sewage Flow     6-26

                             viii

-------
                 LIST OF FIGURES (Continued)
NO.                                                    PAGE
6-21      Report Cost vs. Sewer Length                 6-2?
6-22      Report Cost vs. Peak Infiltration/Inflow     6-28
6-23      Report Cost vs. Sewered Population           6-29
6-24      Report Cost vs. Sewage Plow                  6-30
6-25      Sewer Replacement Cost vs. Pipe Size         6-32
6-26      Pipe Lining (Polyethylene) Cost vs. Pipe     6-35
            Size
6-27      Grouting Cost vs. Number of Pipe Joints      6-37
            Grouted
                              ix

-------
                          CHAPTER 1

                        INTRODUCTION
1.1  INTRODUCTION

The Water Pollution Control Act Amendments, Public Law
92-500, dated October 18, 1972 requires construction grant
applicants to investigate the condition of their sewer systems.
Title II, Section 201 (g) (3) of the Law states, "The Administra-
tor shall not approve any grant after July 1, 1973, for treatment
works under this section unless the applicant shows to the
satisfaction of the Administrator that each sewer collection
system discharging into such treatment works is not subject
to excessive infiltration".

     Title II, Section 201 (g) (M of the Law states, "The
Administrator is authorized to make grants to applicants for
treatment works grants under this section for such sewer
system evaluation studies as may be necessary to carry out
the requirements of paragraph (3) of this subsection.  Such
grants shall be made in accordance with rules and regulations
promulgated by the Administrator.  Initial rules and regula-
tions shall be promulgated under this paragraph not later
than 120 days after the date of enactment of the Federal Water
Pollution Control Act Amendments of 1972".

The final Construction Grant Regulations pertaining to the afore-
mentioned were published in the Federal Register dated
February 11, 1974.  The following sections in the Construction
Grant Regulations pertain to Sewer System Evaluation and
Rehabilitation.

1 35.927  Sewer System Evaluation and Rehabilitation.

     (a)  All applicants for grant assistance awarded after
          July 1, 1973, must demonstrate to the satisfaction
          of the Regional Administrator that each sewer
          system discharging into the treatment works project
          for which grant application is made is not or will
          not be subject to excessive infiltration/inflow.
          The determination whether excessive infiltration/
          inflow exists, may take into account, in addition
          to flow and related data, other significant factors
          such as cost-effectiveness (including the cost of
          substantial treatment works construction delay,
          ...), public health emergencies, the effects of
          plant bypassing or overloading, or relevant economic
          or environmental factors.
                             1-1

-------
   (b)  The determination whether or not excessive
        infiltration/inflow exists will generally be
        accomplished through a sewer system evaluation
        consisting of (1) certification by the State
        agency, as appropriate; and, when necessary (2)
        an infiltration/inflow analysis; and,  if appro-
        priate, C3) a sewer system evaluation  survey
        followed by rehabilitation of the sewer system
        to eliminate an excessive infiltration/inflow
        defined in the sewer system evaluation.  Infor-
        mation submitted to the Regional Administrator
        for such determination should be the minimum
        necessary to enable a judgment to be made.

   Cc)  Guidelines on sewer system evaluation  published
        by the Administrator provide further advisory
        information.

35.927-1  Infiltration/Inflow Analysis.

   (a)  The infiltration/inflow analysis shall demonstrate
        the nonexistence or possible existence of excessive
        infiltration/inflow in each sewer system tributary
        to the treatment works.  The analysis  should
        identify the presence, flow rate, and  type of
        infiltration/inflow conditions, which  exist in the
        sewer systems.  Information to be obtained and
        evaluated in the analysis should include, to the
        extent appropriate, the following:

        (1)  Estimated flow data at the treatment facility,
             all significant overflows and bypasses, and,
             if necessary,  flows at key points within the
             sewer system.

        (2)  Relationship of existing population and
             industrial contribution to flows  in the sewer
             system.

        (3)  Geographical and geological conditions which
             may affect the present and future flow rates
             or correction  costs for the infiltration/inflow,

        (4)  A discussion of age, length, type, materials
             of construction and known physical condition
             of the sewer system.

   (.b)  For determination of the possible existence of
        excessive  infiltration/inflow, the analysis shall
        include an estimate of the cost of eliminating
        the infiltration/inflow conditions. These costs
                          1-2

-------
        shall be compared with estimated total costs
        for transportation and treatment of the infiltra-
        tion/inflow.   Cost-effectiveness Analysis Guide-
        lines (...),  which contain advisory information,
        should be consulted with respect to this deter-
        mination.

   (c)  If the infiltration/inflow analysis demonstrates
        the existence or possible existence of excessive
        infiltration/inflow, a detailed plan for a sewer
        system evaluation survey shall be included in the
        analysis.  The plan shall outline the tasks to be
        performed in  the survey and their estimated costs.

35.927-2  Sewer System Evaluation Survey.

   (a)  The sewer system evaluation survey shall consist
        of a systematic examination of the sewer systems
        to determine  the specific location, estimated flow
        rate, method  of rehabilitation and cost of re-
        habilitation  versus cost of transportation and
        treatment for each defined source of infiltration/
        inflow.

   (b)  The results of the sewer system evaluation survey
        shall be summarized in a report.  In addition, the
        report shall  include:

        CD  A justification for each sewer section cleaned
             and internally Inspected.

        (2)  A proposed rehabilitation program for the
             sewer systems to eliminate all defined ex-
             cessive  infiltration/inflow.

35.927-3  Rehabilitation.

   (a)  The scope of  each treatment works project defined
        within the Facilities  Plan as being required for
        implementation of the Plan, and for which Federal
        assistance will be requested, shall define (1) any
        necessary new treatment works construction, and
        (2) any rehabilitation work determined by the
        sewer system  evaluation to be necessary for the
        elimination of excessive infiltration/inflow.
        However, rehabilitation which should be a part
        of the applicant's normal operation and maintenance
        responsibilities shall not be included within the
        scope of a Step 3 treatment works project.
                          1-3

-------
     (b)  Grant assistance for a Step 3 project segment
          consisting of rehabilitation work may be awarded
          concurrently with Step 2 work for the design of
          the new treatment works construction.

| 35-927-4  Sewer Use Ordinance.

Each applicant for grant assistance for a Step 2,  Step 3> or
combination Steps 2 and 3 project shall demonstrate to the
satisfaction of the Regional Administrator that a  sewer use
ordinance or other legally binding requirement will be en-
acted and enforced in each jurisdiction served by  the treat-
ment works project before the completion of construction.
The ordinance shall prohibit any new connections from inflow
sources into the sanitary sewer portions of the sewer system
and shall ensure that new sewers and connections to the
sewer system are properly designed and constructed.

§ 35.927-5  Project Procedures.

     (a)  State certification.   The State agency may (but
          need not)certify that excessive infiltration/
          Inflow does or does not exist.  The Regional
          Administrator will determine that excessive infil-
          tration/inflow does not exist on the basis of State
          certification, if he  finds that the State had
          adequately established the basis for its certifica-
          tion through submission of only the minimum infor-
          mation necessary to enable a Judgment to be made.
          Such information could include a preliminary review
          by the applicant or State, for example,  of such
          parameters as per capita design flow, ratio of
          flow to design flow,  flow records or flow estimates,
          bypasses or overflows, or summary analysis of
          hydrological, geographical,  and geological conditions,
          but this review would not usually be equivalent to
          a complete infiltration/Inflow analysis.  State
          certification must be on a project-by-project
          basis.  If the Regional Administrator determines
          on the basis of State certification that the treat-
          ment works is or may  be subject to excessive
          infiltration/inflow,  no Step 2 or Step 3 grant
          assistance may be awarded except as provided in
          paragraph (c) of this section.

     (b)  Fre-award sewer system evaluation.  Generally,
          except as otherwise provided In paragraph (c) of
          this section, an adequate sewer system evaluation,
          consisting of a sewer system analysis, and, If
          required, an evaluation survey, is an essential
          element of Step 1 facilities planning and is a

-------
     prerequisite to the award of Step 2  or 3  grant
     assistance.   If the Regional Administrator
     determines through State  Certification or an
     infiltration/inflow analysis that excessive
     infiltration/inflow does  not exist,  Step  2  or 3
     grant assistance may be awarded.   If on the  basis
     of State certification or the infiltration/inflow
     analysis, the Regional Administrator determines
     that possible excessive infiltration/inflow  exists,
     an adequate  sewer system  evaluation  survey  and,
     if required, a rehabilitation program must be
     furnished, except as set  forth in paragraph  (c)
     of this section before grant assistance for  Step 2
     or 3 can be  awarded.  A Step 1 grant may  be  awarded
     for the completion of this segment of Step  1 work,
     and, upon completion of Step 1, grant assistance
     for a Step 2 or 3 project (for which priority has
     been determined pursuant  to § 35-915) may be
     awarded.

(c)   Exception.  In the event  it is determined by the
     Regional Administrator that the treatment works
     would be regarded (in the absence of an acceptable
     program of correction) as being subject to excessive
     or possible  excessive infiltration/inflow, grant
     assistance may be awarded provided that the  applicant
     establishes  to the satisfaction of the Regional
     Administrator that the treatment  works project for
     which grant  application is made will not  be  sig-
     nificantly changed by any subsequent rehabilitation
     program or will be a component part  of any rehabili-
     tated system:  Provided,  That the applicant  agrees
     to complete  the sewer system evaluation and  any
     resulting rehabilitation  on an implementation
     schedule the State accepts (subject  to approval by
     the Regional Administrator), which schedule  shall
     be inserted  as a special  condition in the grant
     agreement.  Compliance with this  schedule shall be
     accomplished pursuant to  s 35-935-16 and  g  30.30^ of
     this chapter.

Cd)   Municipalities may submit the infiltration/inflow
     analysis and when appropriate the sewer system
     evaluation survey, through the State agency, to the
     Regional Administrator for his review at  any time
     prior to application for  a treatment works grant.
     Based on such a review, the Regional Administrator
     shall provide the municipality with  a written
     response indicating either his concurrence or
                       1-5

-------
          nonconcurrence.   The Regional Administrator
          must concur with the sewer system evaluation
          survey plan before the work is performed for the
          survey to be an allowable cost.

Draft Guidance for Sewer System Evaluation was circulated
on April 27, 1973 and the final Guidance was published in
March 197^ by the Environmental Protection Agency.

1.2  PURPOSE

The intent of this Handbook is to present a systematic approach
for conducting the evaluations and provide a source of information
to assist the applicants in fulfilling the requirements under
the Act.  An effort has been made to convey the current state-
of-the-art in conducting (1) Infiltration/Inflow Analyses,
(2) Sewer System Evaluation Surveys, and (3) Rehabilitation.
Methodology.

The contents of this Handbook are not intended to be specific
requirements that each grant applicant must adhere to, for
site-specific conditions may preclude the utilization of
the state-of-the-art presented hereinafter.  The fulfillment
of 'the  requirements under the Act will be based on sound
engineering practices and this handbook may be another tool
utilized to achieve the desired intent of the Act.   In many
instances the methodology and specific examples presented
will be suited  for a sewer  system; and for many others, modifica-
tions will be appropriate.

1.3  FORMAT

Chapters  3}  ^ and  5 of  the  handbook  addresses the methodology
in accomplishing  (1)  Infiltration/Inflow  Analyses,  (2) Sewer
System  Evaluation  Surveys,  and  (3) Rehabilitation.   (Each
 specific  task is preceded by  an overview  explaining  the  purpose
and  expected  information  to be  generated  and  then the current
methodology  is  presented.)  The methodology  consists of  an
array  of  techniques  that  are  currently utilized  to  accomplish
the  specific  tasks.   The  specific  techniques  that pertain
 to the  applicant's  project  may  be  utilized or other  modes
 of accomplishing  the  task may be employed.

 Chapter 6  of the  handbook addresses  the cost  information
 which  may be utilized in cost-effective analyses.  The cost
 for  conducting  the Sewer System Evaluation Survey and the
 resulting rehabilitation are  presented.  These costs can be
 used to develop the specific  costs for the applicant's project.
 Again,  other cost criteria may be employed for particular
 circumstances that are not of a general nature.   Cost informa-
 tion must be modified, where necessary, to suit  local conditions.
                              1-6

-------
The Appendix of the handbook contains a description of State
Certification and a glossary of terms used in this handbook.

1.4  OVERVIEW

"Extraneous water from infiltration/inflow sources reduces
the capability of sewer systems and treatment facilities
to transport and treat domestic and industrial wastewaters.
Infiltration occurs when existing sewer lines undergo
material and joint degradation and deterioration as well as
when new sewer lines are poorly designed and constructed.
Inflow normally occurs when rainfall enters the sewer
system through direct connections such as roof leaders
and catch basins.  The elimination of infiltration/inflow
by sewer system rehabilitation can often substantially
reduce the cost of wastewater collection and treatment.
However, a logical and systematic evaluation of the sewer
system is necessary to determine the cost-effectiveness  of
any sewer system rehabilitation to eliminate infiltration/
inflow.

The Federal Water Pollution Control Act Amendments of 1972
require that after July 1, 1973» all applicants for treat-
ment works grants must demonstrate that each sewer system
discharging into the treatment works is not subject to
excessive infiltration/inflow.  The requirement was imple-
mented in the Rules and Regulations for Sewer System
Evaluation and Rehabilitation, 40 CPR 35-927-

This document is intended to provide engineers, municipalities,
and regulatory agencies with guidance on sewer system
evaluation."

The three aforementioned paragraphs constituted the
Introduction of the March 197? Guidance for Sewer System
Evaluations and also provide a suitable introduction for the
Overview of this Handbook.

The U.S. Congress, U.S. Environmental Protection Agency  and
those involved in the wastewater field recognize the economic
significance of extraneous water in sewer systems.  Public
Law 92-500, the Rules and Regulations for Sewer System Evaluation
and Rehabilitation, the March 1974 Guidance for Sewer System
Evaluations and this handbook have all been developed with
the expressed intent of optimizing the expenditure of funds
allocated by Congress for municipal pollution abatement  facilities
                            1-7

-------
The U.S. Environmental Protection Agency has taken the approach
that sewer systems tributary to treatment works for which
an EPA construction grant will be used,  should be investigated
sufficient to determine the infiltration/inflow conditions.
Those systems that contain excessive infiltration/inflow
will be eligible for construction grant  assistance for rehabili-
tation of the sewer system to eliminate  these flows.  The
Construction Grant Regulations specifically state that, "Rehabil-
itation which should be a part of the applicant's normal
operation and maintenance responsibilities shall not be included
within the scope of a Step 3 treatment works project."

Thus it is not the intent of the Sewer System Evaluation
Program to rehabilitate all sewer systems nationwide that
are or will be involved in the Construction Grants Program
but rather to ensure that infiltration/inflow is addressed
and reasonableness is utilized when evaluating those sewer
lines which will ultimately be rehabilitated.

This program can be successfully implemented by the following:

     •  Flexible Interpretation of the Rules and Regulations
        and Guidance - A good communicative relationship
        between the Regulatory Agencies, the grant applicant
        and those providing services for the applicant can
        result in a workable solution for the most complex
        situation.  This handbook should point out some of
        the solutions but others will have to be devised for
        specific problems that are encountered.

      •  Documentation of pertinent data  in the Infiltration/
        Inflow Analysis Reports and Sewer System Evaluation
        Survey Reports - Sound engineering practice has
        always dictated that Infiltration/Inflow  should be
        investigated to some degree in  sewer  systems  that
        are to be expanded or upgraded.  The  documentation of
        this type investigative work may have  been limited in
        the past.  It is good practice  to  document this
        information in the Analysis or  Survey  Reports.
        This handbook will demonstrate  techniques  to  accom-
        plish specific tasks which may  or  may not  be  a
        component part of Analysis  or Survey  Reports.   Other
        techniques specific  to an applicant's need may be
        utilized.

      • Development and/or  continuation of operation  and
        maintenance programs for  the  applicant's sewer system -
        Many municipalities  have  extensive 0 & M programs
        and  the  continuation of  these programs will have a
         greater  beneficial  Impact  on the sewer system and
         treatment facility  than  the selective rehabilita-
         tion that may be funded  under Public Law 92-500


                              1-8

-------
        due to excessive extraneous water.   Many other
        Municipalities have limited or no 0 & M programs
        and they are advised to take cognizance of the
        derived benefits of a good program.  The resulting
        selective rehabilitation that is funded under Public
        Law 92-500 will not solve sewer problems that were
        marginally nonexcessive or that may deteriorate
        before the life of the treatment works is attained.
        This handbook does not present criteria for 0 & M
        programs but the data generated from conducting
        Infiltration/Inflow Analyses and Sewer System Evalua-
        tion Surveys form a sound basis for developing such
        programs.

1.5  IMPLEMENTATION

The implementation of Sewer System Evaluation and Rehabilita-
tion is documented in the February 11, 197^, Construction Grant
Regulations, sections 35-927 through 35-927-5-  The reader is
advised to review these important paragraphs which have been
presented in Section 1.1 of this Chapter.

These aforementioned Rules and Regulations  have a considera-
ble degree of flexibility which should permit a realistic
solution to the more complex situations.  It is imperative
that U.S. EPA and State Regulatory Agency personnel, grant
applicants and those providing services for grant applicants
be thoroughly familiar with these Rules and Regulations.  The
Grant applicant and his consultant should meet with EPA and
the respective State regulatory personnel to discuss the
specific project and the scope of work.
                            1-9

-------
                          CHAPTER 2

                        USER'S GUIDE
2 .1  INTRODUCTION

The data contained in this Handbook for conducting Sewer
System Evaluations are voluminous and in specific detail.
The intent of this Handbook is to present sufficient information
which will enable engineers and reviewers to prepare and/or
review Sewer System Evaluations on the vast array of circumstances
that are encountered in various sewer systems.   Because of
the varying circumstances that are encountered  in sewer systems
all of the methodology presented hereinafter will not apply
to  each project.

This User's Guide is presented to emphasize that only specific
portions of the methodology that applies to the project under
study should be utilized.

2.2  INFILTRATION/INFLOW ANALYSIS

The intent of the Infiltration/Inflow (I/I) Analysis (see
Chapter 3) is to establish possibly excessive or nonexcessive
I/I in an expedient and thorough manner.  In order to accom-
plish this, an I/I Analysis should contain:

     •  Background Information

     •  Determination of I/I

     •  Establishment of Possibly Excessive or  Nonexcessive I/I

The engineer should always make a first attempt to conduct an
I/I Analysis by utilizing all pertinent existing data.  If this
cannot be accomplished, then minimum data must  be generated
which will permit the engineer to complete the  I/I Analysis.

A check list is presented which may be utilized by the
engineer to determine the components of an I/I  Analysis which
are pertinent to the project under study.  It is essential
that only the components which will allow successful completion
of the I/I Analysis be considered.

The check list contains a listing of functions  and correspond-
ing subheading and page numbers.  In addition,  a rating of
importance for each function is listed.  The following is  a
general description of the rating system employed:
                             2-1

-------
     •  Rating No. 1 - This indicates an essential function
        which should be considered for every I/I Analysis.
        An attempt should be made to perform the function
        by utilizing existing data.  The use of minimum data
        is encouraged.

     •  Rating No. 2 - This indicates a function which may/
        or may not be required to complete the I/I Analysis.
        It is a function which provides supporting data for a
        No. 1 function.  An attempt should be made to perform
        the I/I Analysis without these functions; but if it
        is considered necessary, the use of minimum data is
        encouraged.

2.3  SEWER SYSTEM EVALUATION SURVEY

The Sewer System Evaluation Survey (see Chapter 4) is a
systematic examination of the sewer system to locate all
infiltration and inflow sources which were previously deter-
mined to be possibly excessive, determine the flow rate from
each source and estimate the costs required for the rehabili-
tation of the system.  Chapter 4 presents the methodology
for conducting Sewer System Evaluation Surveys.  A particular
project may require any number of the functions presented.

A check list is presented which may be utilized by the engineer
to determine the components of a Sewer System Evaluation Survey
which are pertinent to the project under study.  The check list
contains a listing of functions and corresponding subheading
and page numbers.  In addition, a blank space is provided for
a check mark or comment.

2.4  SEWER SYSTEM REHABILITATION

The Sewer System Rehabilitation Chapter (see Chapter 5) of
this handbook describes the various rehabilitation techniques
that are commonly utilized for sewer systems.  The information
presented in that Chapter is for information purposes only.
The engineer is encouraged to read this Chapter in order
to become familiar with specific rehabilitation techniques.

2.5  COSTS

Costs for conducting Sewer System Evaluation Surveys and
Rehabilitation are presented in Chapter 6.  The cost infor-
mation presented should be used in the cost-effectiveness
analysis of the I/I Analysis.  The costs should be refined
for a particular study when used in the cost-effectiveness
analysis of the Sewer System Evaluation Survey.
                             2-2

-------
The engineers preparing Sewer System Evaluations  and the
Regulatory personnel reviewing the projects should read and
understand the sources and intent of the costs presented
in Chapter 6.  In order to effectively use the costs, the
following items should be understood:

     •  Tables 6-1 and 6-9 and Figures 6-25 to 6-27 show
        the costs for conducting Sewer System Evaluation
        Surveys and Rehabilitation.  These costs  can be
        used in the I/I Analysis after they have  been
        adjusted for the particular sewer system  under
        study by analyzing the cost criteria presented in
        Tables 6-2 to 6-8.

     •  The aforementioned cost tables and figures can only
        be utilized in the Sewer System Evaluation Survey
        Phase after incorporating the cost criteria for the
        specific rehabilitation required in the system under
        study,

     •  Figures 6-1 to 6-24 display the costs for conducting
        Sewer System Evaluation Surveys and should only be
        used in a preliminary manner, i.e., by Regulatory
        personnel when establishing an order of magnitude in
        determining the reasonableness of costs presented in
        I/I Analysis report.
                             2-3

-------
                            TABLE 2-1

                    CHECK LIST FOR CONDUCTING
                  INFILTRATION/INFLOW ANALYSIS
Function
BACKGROUND INFORMATION
Interview
Sewer Map Analysis
Inventory of Existing Sewer
System
Geographic and Geological Data
Wastewater Flow Data
Flow Measurement
Physical Condition of Sewer
DETERMINATION OF INFILTRATION/
INFLOW
General Consideration
Determination of I/I Using
Wastewater Flow Data
Determination of I/I by
Direct Flow Measurement
Adjustment of Flow Data
COST-EFFECTIVENESS ANALYSIS
Cost Estimate
Analysis Procedures
Subheading No.
3.2
3.2.1
3.2.2

3.2.3
3.2.4
3.2.5
3.2.6
3.2.7

3.3
3.3-1

3.3.2

3.3.3
3.3.4
3.4
3.4.2
3.4.3
Page No.
3-3
3-3
3-16

3-21
3-25
3-34
3-35
3-56

3-59
3-59

3-61

3-70
3-72
3-73
3-74
3-85
Rating
1
2
2

2
2
1
2
2

1
2

1

2
2
2
2
2
ESTABLISHMENT OF POSSIBLY
EXCESSIVE OR NONEXCESSIVE I/I    3.5

SEWER SYSTEM EVALUATION SURVEY
PROGRAM RECOMMENDATION           3.6

  Program Recommendation         3.6.1
  Cost Estimates                 3.6.2
  Project Schedule               3.6.3
3-89
3-90

3-91
3-94
3-94
2
2
2
                                 2-4

-------
                             TABLE 2-2
                    CHECK LIST FOR CONDUCTING
                  SEWER SYSTEM EVALUATION SURVEY
Function
PHYSICAL SURVEY
  General
  Aboveground Inspection
  Flow Monitoring
  Manhole and Sewer Inspection
  Report
RAINFALL SIMULATION
  General
  Smoke Testing
  Dyed Water Testing
  Water Flood Test
PREPARATORY CLEANING
  General
  Equipment
  Selection of Cleaning Equipment
INTERNAL INSPECTION
  General
  Inspection Techniques
SURVEY REPORT
  General
  Data Analysis
  Cost-Effectiveness Analysis
  Recommendation for Sewer
    System Rehabilitation
Subheading; No
4.2
4.2.1
4.2.2
4.2.3
4.2.4
4.2.5
4.3
4.3.1
4.3.2
4.3.3
4.3.4
4.4
4.4.1
4.4.2
4.4.3
4.5
4.5.1
4.5.2
4.6
4.6.1
4.6.2
4.6.3
4.6.4
Page No.
 4-2
 4-2
 4-3
 4-3
 4-4
 4-10
 4-10
 4-10
 4-12
 4-15
 4-18
 4-20
 4-20
 4-20
 4-24
 4-24
 4-24
 4-25
 4-32
 4-32
 4-33
 4-35
 4-37
                                2-5

-------
                         CHAPTER 3

                INFILTRATION/INFLOW ANALYSIS


3.1  INTRODUCTION

An Infiltration/Inflow (I/I) Analysis is an engineering
analysis demonstrating possibly excessive or nonexcessive
infiltration/inflow in a sewer system or portions thereof.
The principal purpose of the Infiltration/Inflow Analysis
is to establish this expediently and yet thoroughly.

Generally, the I/I Analysis will be incorporated in the
Project Facilities Planning Report or area wide waste manage-
ment plans.  There will be instances, however, when the I/I
Analysis Reports will be separate documents.  For example,
Analysis Reports that are prepared on projects begun prior
to PL 92-500 will generally be separate documents.  Also,
some planning documents will be voluminous; therefore, the  I/I
Analysis portion will be a separate document merely for con-
venience.

The I/I Analysis Reports will generally be in one of two
forms:

     •  Sewer systems that have reliable data available which
        will conclusively demonstrate nonexcessive or possibly
        excessive I/I, the data may be briefly summarized.   The
        engineer preparing the report should display sufficient
        flow data and specific characteristics of the sewer
        system to enable a review engineer to properly assess
        the system and concur with the report.  A cost-
        effectiveness analysis may or may not be needed to
        establish the existence or nonexistence of excessive
        I/I.

     •  Sewer systems that have limited data (including flow
        and sewer characteristics) available will generally
        require a more structured analysis report than the
        aforementioned circumstance.  This report generally
        will include a cost-effectiveness analysis.  The degree
        of investigative work required for this type of analysis
        will obviously depend on the specific sewer system.
        The main goals of this investigative work will be the
        following:
                             3-1

-------
         (1)  To generate sufficient flow data and characteristics
             of the sewer system that will enable a sound
             engineering decision to be made on possibly
             excessive or nonexcessive I/I.

         (2)  To obtain realistic cost estimates for rehabilita-
             tion of sewers that may contain possibly excessive
             I/I and for the transport and treatment of ex-
             traneous water.

         (.3)  Items (1) and (2) should enable the engineer, in
             the event of possibly excessive I/I, to scope in
             detail the work tasks for the next investigative
             Phase, the Sewer System Evaluation Survey,

The following subheadings are the most commonly utilized
components of an I/I Analysis Report.   The presentation of
these components or subheadings does not imply that they
must be included in every I/I Analysis.   Quite the contrary
is true and only those subheadings that  need be utilized
to generate the desired data should be considered.  In addition,
other techniques that the engineer may have developed or
generally utilizes, and which may not  be displayed here,
are encouraged.  It should be kept in mind that this handbook
shows some of the techniques utilized by engineers and municipal-
ities to accomplish specific tasks.  There are other techniques
available and others that will be developed that may be as
effective or more effective for a specific sewer system than
those presented hereinafter.

The I/I Analysis report should not reiterate the data that
would normally be presented in the Facilities Planning report
but merely display the pertinent minimum data necessary to
make a sound Judgment of nonexcessive  or possibly excessive
infiltration/inflow.

The methodology presented hereinafter, unless otherwise noted,
is applicable to both combined and separate systems.

3.2  BACKGROUND INFORMATION

The first step in conducting an Infiltration/Inflow Analysis
is to obtain all the pertinent information and data on the
specific wastewater collection system and treatment works
under investigation.   Much of this Information and data will
normally be collected by the engineer  as the first step in
conducting Facilities Planning; thus,  duplication of effort
should be avoided.
                            3-2

-------
The investigator should screen all the background information
and only utilize minimum information necessary to make a
judgment of nonexcessive or possibly excessive infiltration/
inflow.  The first attempt at making this determination should
follow the analysis of all the background information or
data.  If a reliable judgment cannot be made after this, addi-
tional work, such as flow measuring at key manholes in subsystems
or pumping station flow monitoring, may be required.

3.2.1  Interview

Interviews may be one of the first steps in the study of
infiltration/inflow in a sewer system.  The purpose of con-
ducting an interview is to gather as much information as
possible from the people who are familiar with the system.
Results from well performed interviews may save the engineer
considerable field work and also give him a clear overview
of some or all of the problems at the onset and provide him
with guidance as the study progresses.  In the final analysis,
the results from"*the Interviews may also be utilized, along
with other findings, to make a proper judgment as to the
seriousness of the infiltration/inflow problems in the study
area, the major problem areas in the system, the percentage
of the infiltration/inflow which can possibly be removed
and the areas which may deserve further investigation.  A
spin-off effect of the interview is that it may help the
municipality recognize its problems and develop a program
to eliminate and/or prevent them.

3.2.1.a.  Person to Perform the Interview

Because of their Importance, interviews should be well planned
and should be undertaken by an experienced person.  In some
instances, discussions with municipal engineers, public works
directors and treatment plant and sewer superintendents should
be conducted by experienced engineers.  In other instances,
such as discussions with plant operators and sewer line laborers,
it may be advantageous to have an experienced technician to
conduct the study.

3.2.1.b.  Persons to be Interviewed

The persons who might be interviewed are those who know the
sewer system and its related problems, and are familiar with
the general conditions of the study area.  They may include
the following:
                            3-3

-------
      •  Sewer maintenance personnel

      •  Sewage treatment plant operators

      •  Municipal engineers

      •  Municipal Officials

      •  Sewer Commissioners

      •  Consulting engineers

      •  Local contractors

      •  Home owners

      •  Industry representatives

Sewer maintenance personnel and treatment plant operators
possess  the first-hand knowledge of the sewer system and the
sewage treatment facilities and are often the major information
sources.  Questions to ask this group of people could include
the structure of the existing sewer system, the sewer maintenance
program, the sewer construction practices and the observed prob-
lems in  the sewer system and the sewered areas.  Much of the
same information could often be obtained from knowledgeable
municipal sanitary engineers.

When necessary, both the retired and the present personnel may
be interviewed.  In many older systems, where adequate sewer
ordinances were not previously available, changes of sewers,
additions of cross connections between sanitary sewers and
storm sewers, direct drainage of impounding areas to the
sanitary sewer, etc. were often made without proper authorization
and records are sometimes unavailable.  Information of this
sort can often be obtained from retired sewer maintenance
personnel, retired treatment plant operators, or retired
municipal engineers.

Local construction contractors may provide information on the
soil and groundwater conditions in the study area, and the
practice of installing roof leaders, cellar, yard, area and
foundation drains, during the construction of local homes
and public buildings.

Home owners may indicate areas that flood during heavy rain-
falls, homes with sewage backup problems and other obvious
problems related to the sewer system.

-------
The major industrial plants in the area could be contacted
to gather the information on their water usage,  wastewater
discharge practices, plant operation schedule, etc.  which would
be useful for the estimation of normal sewage flows  and for
the planning of the flow monitoring schedules to be  needed later.

The Municipal Officials, the City Engineers or the Sewer
Commissioners may provide information on the jurisdictional
and legal aspects of the sewer system and help solve problems
in the areas where more than one municipality is involved.
Questions such as the content and effectiveness  of the sewer
ordinances and the solutions to the problems of  inflow sources
on private properties, could be discussed with the responsible
officials in the local government.  The consulting engineers
retained in the past by the municipality to provide  planning
or design work on the sewerage system in the study area may
also have a general knowledge of the sewer system and its
related problems and may also be contacted.

The number of persons to interview depends on the complete-
ness of the information obtainable from the people already
interviewed.  The interviews can be conducted either individually
or collectively.

3.2.1.C  Content of the Interview

The interview should cover a broad spectrum of subjects
including but not limited to the following:

     •  The sanitary sewer system

     •  The storm sewer system

     •  The existing sewer maintenance program (including
        cleaning, inspection and rehabilitation)

     •  The problem areas in the sewer system

     •  The geological and geographical conditions in the
        sewered areas

     •  The population and water consumption data

     •  The industrial wastewater flows

     •  The legal and jurisdictional aspects of  the  sewer system

A typical interview form is presented in Table 3-1.   This form
is merely a guide and each engineer should develop a form
specific to the system under study.
                             3-5

-------
          TABLE 3-1  INFILTRATION/INFLOW ANALYSIS

                      INTERVIEW FORM

(Note:  This form is intended as a general guide only.  Engineers
should develop their own forms for specific systems under study).
Project:	 Project No.

Interview Date:
Interviewee:  Name
              Title
              Organization

              Address
              Length of affiliation with the organization or
              living in this area 	 years.
Interviewer:
I.  SEWER SYSTEM

    A.   Type of System:   Separated	;  Combined
                         Partially combined with about
                         of the system being combined.

    B.   General Comments  about  the Sewer System:	
    C.   Inventory of Sewer System:

         1.   Sanitary Sewer System (or combined system)

             a.   Availability  of Sewer maps,  construction plans
                 and contract  documentsj	



             b.   Age of sewersj	
             c.   Sizes  of sewers:
                            3-6

-------
              TABLE 3-1 (Continued)

         d.  Total length of gravity sewers:

         e.  Total length of force mains:	
         f.  Number and locations of treatment facilities:
         g.  Type of treatment process in the treatment
             facilities:
         h.  Number and locations of pumping stations
         i.  Number and locations of overflow points:
         J.  Number and locations of bypassing points
         k.  Number and locations of river crossings:
     2.  Storm Sewers

         a.  Indicate areas where cross connections between
             sanitary sewers and storm sewers exist:
         b.  Indicate locations where sanitary sewers and
             storm sewers are constructed in same trenches
             or in close proximity:
D.  Sewer System Maintenance Program

     1.  Maintenance Schedule:
     2.  Work normally performed:
                         3-7

-------
               TABLE 3-1 (Continued)

     3.  Equipment available:	

     4.  Personnel available:	
     5.  Availability of maintenance records^
     6.  Indicate areas where sewers require frequent
         cleaning:
     7.  Types of deposits encountered:

     8.  Cleaning methods used:	
     9.  Sections of sewers T V  inspected:
    10.  Indicate sections of pipes that have been repaired
         and dates of repairing:
    11.  Methods and materials used for repairing:
    12.  Difficulties involved during maintenance:
E.  Sewer Construction

     1.   General comments on the workmanship of sewer con-
         struction for this system
     2.   Sewers

         a.  Sewer materials:

         b.  Joint types:	

         c.  Pipe depths:	
         d.   Bedding materials:	

         e.   Packing materials:	

     3.   Manholes

         a.   Manhole construction materials:
         b.   Types of manhole covers installed:

                        3-8

-------
              TABLE 3-1 (Continued)

            Indicate locations where sewer lines change
            in direction and grade without installing
            manholes:
        d.  Indicate locations of cleanouts in sewer lines:



        e.  The average distance between manholes is:  	 ft

        House service connections

        a.  General comments on construction methods used:



        b.  Sizes and materials of pipes installed:	
        c.  Indicate known areas where roof drains, areaway
            drains and foundation drains and cellar sump
            pumps are discharged to sanitary sewers:
        d.  Indicate areas where open joints and/or Joint
            defects exist:
P.  Observed Problem Areas

    1.  Sewers

        a.  Indicate locations where the following pipe
            defects or problems were observed:
            (1)     Cracks:
            (2)     Collapse:
            (3)     Offset joints:
            (4)     Misalignment (horizontal or vertical):
                        3-9

-------
     TABLE 3-1 (Continued)

    (5)     Root penetration:

    (6)     Heavy deposition:

    (7)     Vandalism:	
    (8)     Other Observations:
    Indicate sections of sewers which surcharge and
    state possible causes and consequences:

    (1)   Location:	

    (2)   Causes:	

    (3)   Consequences:	
    Indicate areas where emergency manhole pumpings
    were required during heavy rainfalls and state
    the dates, the rate of pumping and the intensi-
    ties and durations of rainfall causing the over-
    flows :

    (l)    Location:	

    (2)    Dates:	

    (3)    Pumping rates:	
    (4)    Rainfall intensity:

    (5)    Rainfall duration:
    Indicate locations where basement backups due to
    sewer surcharge were reported:
e.  Indicate locations where direct Inflows of
    surface drainage waters to the sanitary sewers
    were observed:
               3-10

-------
          TABLE 3-1 (Continued)
    f.  Indicate locations where water mains were report-
        edly broken:
    g.  Indicate sections of storm sewers which were
        found broken and are adjacent to sanitary sewers
2.  Manholes
    Indicate locations where the following manhole
    defects or problems were observed:
    a.  Cracks:	
    b.  Leaking:
        (1)    Location:	
        (2)    Dates:
        (3)    Weather:
        (4)    Magnitudes:
    c.  Depressed manholes:
    d.  Located in low-lying areas:
    e.  Receiving surface runoffs:_
    f.  Perforated or broken covers:
    g.  Covers missing:	
    h.  Heavy deposition:
    i.  Inaccessible manholes:	
    j.  Other Observations:	_______
3.  Overflows and Bypasses
    a.  Indicate locations where dry weather overflows
        occur and estimate magnitudes of overflows:
        (1)   Locations:	
        (2)   Magnitude;	
                  3-11

-------
                  TABLE 3-1 (Continued)

                 Indicate locations, dates and magnitude of wet
                 weather overflows and state the corresponding
                 intensities and durations of rainfalls:

                 (1)    Location:	

                 (2)    Date:	
                 (3)    Magnitude:
                        Rainfall intensity and duration:
                 Indicate locations and magnitudes of bypasses
                 and methods of activation:

                 Cl)   Location:	
                 (2)   Magnitude:
                 (3)   Method of activation:
                 Indicate locations where overflows from catch
                 basins in storm sewers occurred:
II.  BACKGROUND INFORMATION ABOUT SEWERED AREAS

     A.   Geological and Geographical Information

         1.  Indicate types of soils in different areas:
         2.  Locate areas  which were swampy,  lowland areas prior
             to filling for development:
         3.  Locate potential problem areas such as waterways,
             creek crossings, and natural ponding areas:
                           3-12

-------
              TABLE 3-1  (Continued)
        Indicate groundwater levels  in different  sewered
        areas during:
        a.   Dry season:
        b.   Wet season:
    5-  Indicate water level fluctuations in the streams:

    6.  Indicate sewered areas that were flooded previously:
        a.  Location:	
        b.  Date:	
        c.  Rainfall intensity and duration:	
        Indicate locations of wells that  can be used as
        groundwater gaging points:
B.  Population
    1.   Present population:
    2.   Sewered population:
    3.  Locate the following areas:
        a.  Most densely populated:
        b.  Least densely populated:
        c.  Trailer parks:	
        d.  Commercial areas:	
        e.  Industrial areas:	
    Water Consumption
    1.   Total water consumption rate:
    2.   Per capita water consumption rate:
    3«   Industrial water sources  and consumption  rates
        a .   Sources:
        b.   Consumption rates:
                      3-13

-------
              TABLE 3-1 (Continued)
D.  Legal Aspects
    1.  Availability of a sewer ordinancej	
E.  Industrial
    1.  Industrial plant operation schedule:
    2.  Industrial water sources:
    3.   Industrial water consumption rate:
        Industrial wastewater discharge rate and schedule
                      3-14

-------
Before the interview, maps of the study area, if available,
should be studied to get familiarized with the area.   During
the interview, important information could also be marked
on the maps to supplement the descriptions recorded in the
interview form.

Before an interview, the purpose, nature and significance of
the study should be explained to the persons being interviewed
to avoid any misunderstanding and to obtain full cooperation.
Good public relations should be practiced at all times.

Pertinent existing records, such as treatment plant records,
sewer maps, sewer maintenance records, including information
of previous cleaning, TV Inspection and rehabilitation,
sewer system construction, contract documents, water consump-
tion records, sewer ordinance, discharge permit information,
etc., should be collected during the Interviews to facilitate
further study.

3.2.1.d.  Treatment of the Interview Results

After the interviews, tables could be constructed to summarize
the* findings, and problem areas could be plotted on the maps
for easy identification.  Discrepancies among interviewees
and/or between the interview results and the existing records
should be evaluated.  Some spot checking should be made to
substantiate the interview results.  From an analysis of
the collected information, a plan of action can now be made
to gather more needed data for the completion of the infiltration/
inflow analysis.

3.2.2  Sewer Map Analysis

Maps of the existing sanitary and storm sewer systems may be
necessary in order to conduct an I/I Analysis particularly
when the flow data are limited and flow monitoring at key
manholes is desirable.  In systems where sewer maps are avail-
able, it may be advisable to verify some of the critical points
in the field before total acceptance.  Sewer maps should also
be updated to include new sewer extensions, sewer line changes,
buried manholes, and any other pertinent data.

In systems where sewer maps are not available or incomplete,
efforts should be made to produce adequate maps for the study.
(The methods and equipment used for sewer mapping are discussed
in the following subsection.)  Generally, the costs for sewer  map
preparations suitable for Infiltration/Inflow Analyses and
Evaluation Surveys are fundable costs, to the extent necessary
for the study.
                             3-15

-------
 All  available  information  need  not  be  included  in the  sewer
 maps for  an  analysis  report .  The following  basic items are
 generally required:

      •  All  sanitary  and combined sewers;

      •  Size of  sewers and direction of flows;

      •  Locations of  treatment  facilities, pumping
        stations, flow measurement  manholes, over-
        flow and bypass points  and  river crossings;

      •  Storm  sewers  in the vicinity of sanitary
        sewers and those crossing or constructed in
        the  same trenches  as the sanitary sewers.

 All  manholes and their inverts  need not be shown for an analysis
 report.   In  some instances, results from interviews or pre-
 liminary  analysis may indicate  that no infiltration/inflow
 problems  exist in certain  areas of  the system; sewer layouts for
 such areas are not required if  not  available.

 The  scale of sewer maps may vary depending on the size of the
 system.   In general, a scale of 1 inch = 400 feet (or, 1/4,800)
 is satisfactory.  For larger areas, the sewer system may have to
 be broken down into several smaller systems, and a separate map
 may  be prepared for each smaller system.  However, a system flow
 diagram should be prepared to show the inter-relationships among
 all  the systems.

 3.2.2.a  Map Preparation

 A street map is generally useful for the preparation of a
 sewer map.  In cases where street maps are not available,
 a schematic layout of the sewer system may be suitable, or
 an aerial photograph of the area may be taken and a map developed.
 After the map is prepared,  the existing sewers should then
 be laid out on it.

Sewer location and direction of flow can be identified by  a
number of methods.  The following methods  are common:

     •  Dye tracer
     •  Floats
     •  Smoke
     •  Metal detectors
     •  Interview
                            3-16

-------
These methods can be used to develop a complete sewer map,  to
complete a partially completed sewer map, or to check the exist-
ing sewer map for accuracy.  The selection of a particular  method
or a combination of several methods for a given job will depend
on the field situation and should be judged individually.

3.2.2.a (1)  Dye Tracer - The dye tracer method involves
the addition of a water-soluble dye to a manhole and determining
the paths of flow by observing the dye at the downstream
manholes and outlets.  A sewer map can be developed by plotting
all the flow paths determined in this manner.

Several types of dyes are available for sewer tracing, including
fluorescein, Rhodamine, Rhodamine W, Rhodamine WT,  methyl
orange, nigrosine, etc.  The characteristics of some of these
dyes are shown in Table 3-2.  Proper selection of a suitable
dye and the respective feed concentration suitable  for visible
or instrument observation after dilution in the sewers is
essential for successful application.

Powdered dyes are usually dissolved in water to make concen-
trated solutions for easy handling.  The solution concentration
and the quantity to apply depend on the magnitude of sewage flow.

3.2.2.a (2)  Floats - Floats, such as wood chips, cork floats,
stoppered bottles, oranges, etc., can also be used  to determine
the flow path in a sewer.  However, in heavily deposited
or obstructed sewers, this method may not be feasible.  The
floats should be specially marked to distinguish them from
similar objects in the sewage.

3.2.2.a (3)  Smoke - Smoke produced from a smoke bomb in
a manhole and blown by an air blower will show up in adjacent
manholes if the sewer is not flowing full or if there are
no water traps in the sewer section being investigated.
One added advantage of this tracing technique is that, in
certain cases some infiltration/inflow sources may  also be
detected.

3.2.2.a (4)  Metal Detectors - Commercially available metal
detectors can be used to locate buried metal sewers and manholes
with metal covers.  Because of possible interferences from
other underground utility pipes, the detectors should be
used by an experienced operator.
                            3-17

-------
                                      TABLE 3-2
                       PROPERTIES OF COMMONLY USED TRACER DYES* [12]
Dye color, formula
and common name
Basic Violet 10
C28H31N2°3C1
Rhodamine B

Acid Red 52
C27H29N2°4S2Na
Acid Yellow 73
C20H12°5
Fluorescein
Manufacturer's
brand name
Rhodamine B
Extra
Rhodamine B
Rhodamine
BA
Rhodamine
WT
Sulpho 2
Rhodamine B
Fluoro Brilliant
PinkJ
Fluorescein
Available
forms
Powder
40 percent
solution
(by wt.)
40 percent
solution
30 percent
solution
(by wt.)
20 percent
solution
Powder
Powder
Specific
Gravity
of Solutions

1.12
1.03
1.03
1.19


Remarks
Strong points: Very high
detectibility, moderate
cost.
Weak points: Fair
diffusivity, moderate
sorptive tendency,
moderate rate of
photochemical decay,
high acidity of
solutions given.
Strong points: High
detectibility, low
sorptive tendency, good
diffusivity, low
acidity.
Weak points: High cost,
heavy .
Strong points: Fairly
high detectibility, low
sorptive tendency,
good diffusivity, low
decay rate, fairly
stable at pH extremes.
Weak points: high cost
Strong points: Inexpensive,
low sorptive tendency,
low temperature effect.
Weak points: Very high
photochemical decay
rates; high potential
interference by
background .
 *Note:   Before using, the health effects of these dyes should be carefully considered.
         Dyes with  carcinogenic potentials should be avoided.


 Product of  E. I. DuPont de Nemours Co., Wilmington, Del.
I
 Product of  General Aniline and Film Corp., New York, N.Y.

 Product of  Keystone Aniline and Chemical Co., Chicago, 111.
                                       3-18

-------
3.2.2.a (5)  Interview - Interviewing people having a first-
hand knowledge of the sewer system is also one  way to construct
a sewer map.  Usually, the personnel in the local sewer  main-
tenance department have a better knowledge of the sewer  system
than anybody else and should be contacted first.   To avoid
possible error, some limited field work should  be done using
the aforementioned techniques to substantiate the interview
results.

3.2.2.b  Map Study

Once the sewer map is prepared, it can be used  as a valuable
tool during the study.  The following information pertinent to
infiltration/inflow can be indicated or overlayed on the
sewer maps:

     •  Topography of the study area

     •  Soil formation

     •  Groundwater distribution

     •  Sewer age

      •  Known or potential problem areas such as areas
        subject to floodings during heavy rainfalls,
        surcharged sewers, overflowing manholes, over-
        loaded pumping stations, houses with sewer
        back-up problems, obvious inflow sources,
        existing and historical swampy areas, etc.

A careful  inspection of the sewer maps with this added information,
adequately keyed, may enable one to gain valuable insights into
the infiltration/inflow problems of the area.  For example:

      (1)   Storm sewers crossing, parallel to, or in the same
           trenches as the sanitary sewers may be potential
           infiltration and inflow sources:  i.e. storm water may
           exfiltrate from the  storm sewers and infiltrate through
           defective joints, etc. to the adjacent sanitary sewers;
           some relief cross-connections between these two types of
           sewers may have been made in the past to allow the
           storm sewers to overflow to the sanitary sewers.

      (2)   Sewers  constructed near rivers, streams, ditch sections
           ponding areas and  swamps may present serious infiltration/
           inflow  problems due  to groundwater seepage  or direct
           drainage.

      (3)   Sewers  constructed in poor  soils  may be  subjected  to
           settlement  resulting in open joints  and/or  pipe
           cracking.


                            3-19

-------
      (4)   Low-lying areas may be subjected to flooding during
           heavy rainfalls.  Manholes with perforated covers in
           such areas may present serious inflow problems.

      (5)   Older sewers may present more structural defects.
           Sewers with oakum-bituminous, oakum-mortar or cement-
           mortar joints may present more serious infiltration
           problems than sewers with gasket joints.

      (6)   Sewers constructed above seasonal groundwater level
           may present little infiltration problems.

      (7)   Serious infiltration/inflow problems may exist in
           areas where there are one or more of the following
           conditions:

           (a)  Sewers being surcharged

           (.b)  Manholes overflowing

           (c)  Pumping stations overloaded

           (d)  Houses having sewage back-up problems

Based on this analysis, an engineering Judgment can be made as to

      (1)  What the degree of the problems might be in different
          areas; and

      (2)  If more detailed investigation should be made,
          where to concentrate the efforts.

3.2.3  Inventory of Existing Sewer System

An inventory of the existing sewer system will enable both the
investigator and the reader to have a general understanding
of the nature of the system.  The following items may be sum-
marized and included in the report:

     •  Type of sewer system,  i.e., separate or combined
        system or combination;

     •  Age of sewers;

     •  Sizes and lengths of sewer pipes;

     •  Pipe materials;

     •  Types of joints and joint materials;
                            3-20

-------
     •  Numbers of manholes and catch basins;

     •  Maximum, minimum and average depth of sewers;

     •  Bedding and backfill materials;

     •  Construction techniques;

     •  Types and numbers of overflows and bypasses;

     •  Physical conditions of the sewers.

This information could be obtained from reviewing the sewer
maps, as-built sewer construction plans and specifications, etc.
Some information is also obtainable from interviews.  Typical
data sheets for recording the above information (except the
last item) are shown in Table 3-3•

3.2.3.a  Type of Sewer System

The type of the sewer system should be known because the nature
of the infiltration/inflow problem of a separate sanitary sewer
system may be different from that of a combined sewer system.
In a separate sanitary system, both the infiltration and the
inflow problems should be investigated, while in a combined
system, generally only the infiltration problem needs to
be stressed.  Combined sewers are usually designed to remove
the rainfall-induced flows in an area as well as the wastewater
discharges from various sources.  By definition, most of
the inflow problems are rainfall-related and should not have
any impact on the combined system.  However, inflow sources
not directly related to rainfall, such as industrial cooling
water discharges, drains from springs and swampy areas, etc.,
should be identified and studied in a combined system as
well as in a separate system.

The requirements for handling overflows in separate sewer systems
are also different from those in combined sewer systems.  Over-
flows and bypassing should be eliminated from separate sanitary
systems, but not necessarily from combined systems.  Overflows
or bypasses from combined sewers may or may not need some
degree of treatment before discharging to the receiving waters
or land disposal, depending on the requirements in the National
Pollution Discharge Elimination System (NPDES) permit.  This
will affect the treatment costs in the final cost-effectiveness
analysis.
                            3-21

-------
                                TABLE  3-3

                  TYPICAL  DATA  SHEETS  FOR  THE  INVENTORY  OF
                           EXISTING  SEWER  SYSTEM


 I.   SANITARY  GRAVITY  SEWERS  OR COMBINED SEWERS

                                  JointNo.Sewer""~
           Size   Length*    Pipe   Type &    of     Depth, Bedding   Backfill
 Pipe Age    In.     Ft   Materials  Material  MH's    Ft   Material  Material
 Sub-
 Total
 II,   SANITARY  FORCE MAIN
 Pipe          Size,    Length,
 Age	In.       In.      Material
Sub-
Total
III.  OVERFLOWS
                                  Frequency   Over-    Probable     Dis-
No.    Location    Description    of Over-    flow     Causes of    charge
                                  flows       Rate,    Overflow     Point
	Tjmes/yr    gpm	
IV.  BYPASSES


                                  FrequencyBypassConditionDis-~
No.    Location    Description    of Flow      Flow      Required   charge
                                  Bypass,      Rate,     for By-    point
       	Times/yr	gpm	passing	
                                 3-22

-------
                        TABLE 3-3 (Continued)


V.  PUMPING STATIONS
No.    Location    Type of      Pump Rate,      Average Daily Flow, gpd
                   Pumps        gpm             Low           High
                                                Groundwater   Groundwater
                                  3-23

-------
 3.2.3-b   Age  of  Sewers

 The  age  of  a  sewer  system may  partially reflect Its general
 conditions  and the  degree of the potential infiltration/inflow
 problems.   Buried sewers are constantly subjected to different
 adverse  environmental conditions and deteriorate with time.
 Sewers constructed  in poor  soils may settle and create offset
 joints or cracks.   Sewer pipes and pipe joints may be attacked
 by the chemicals in the groundwater, such as sulfates and
 organic  acids.  Metal sewers may be electrolytically corroded
 by the stray  currents in the groundwater.  Sewer joints may
 be penetrated by plant roots.  Increased surface loadings may
 cause crushing or cracks in gradually deteriorated sewers.
 Such factors  render the older  sewers more vulnerable to
 infiltration  than the newer ones .  In addition, one can ex-
 pect to  find  more cross-connections between sanitary sewers
 and  storm sewers and more direct inflow sources in older
 sewer systems than  in relatively new systems because most older
 systems  were  constructed when there were no adequate sewer
 ordinances, and without thorough inspection.

 3.2.3•c  Other Appurtenances

 Bypasses and  overflows should be identified and observed
 in the field.  The  specific construction of the overflows and
 bypasses should be determined and the operation of each should be
 understood.   Information regarding the activation of overflows
 and bypasses  should be established either from past observations
 or throughout the I/I Analysis and/or Evaluation Survey.

 Pumping  stations should be identified and design and opera-
 tional characteristics of these should be documented.

 3.2.4  Geographic and Geological Data

 A general knowledge of the geographic and geological condi-
 tions of the sewered area may enable the engineer to better
 understand the infiltration/inflow problems in the area.
 Provided with sufficient data,  the engineer can pinpoint
 some potential problem areas and plan possible corrective
actions.   As will be discussed in Chapter 5,  for sewer  rehabili-
 tation work, the type of the soils and the groundwater  conditions
around the sewers also dictate  the type of the chemical grout
to be used.

 3.2.4.a.   Topography

 3.2.4.a_(l)   Importance  of Topographic  Data - The topography
of an area reveals  the extent and direction of surface  drainage,
the  locations of low-lying areas  and the areas where sewers
are  close to or crossing rivers,  streams and/or swampy  areas.
                            3-24

-------
Low-lying areas are subjected to possible floodings during
heavy rainfalls and the extent of the surface drainage determines
the seriousness of the flooding problem.   In such areas,
a considerable amount of surface runoff may enter the sewer
system through exposed open joints, perforated sewer manhole
covers, structurally defective manholes,  abandoned house
connections, etc.  Prolonged rainfall may also saturate the'
soils and increase the possibility of rainfall-related infiltra-
tion through deteriorated pipes, pipe joints and/or manhole
walls.  Sewers constructed in the vicinity of or crossing
rivers, streams or swampy areas may have  a higher possibility
of being surrounded by saturated soils than those constructed
in the other areas and may present a greater infiltration/inflow
problem than the sewers lying in areas farther away from
the water sources.

3.2.4.a (2)  Data Collection and Presentation - Topographic
maps and aerial photographs may both provide sufficient informa-
tion for topographic study.  Topographic  maps are generally
available from the U.S. Geological Survey.  Aerial photographs
can be obtained from:  (1) U.S. Department of Agriculture,
Commodity Stabilization Program, (2) Local or County Planning
Departments, (3) U.S. Corps of Engineers  Offices, and (4)
Private Photogrammetry and Mapping companies.

The topographic maps should be studied and analyzed by the
engineer to locate areas of potential infiltration/inflow
problems.  The important findings from this study may be
shown and discussed in the analysis report.

3.2.4.b  Rainfall

3.2.4.13 (1)  Importance of Rainfall Data  - Both infiltration and
inflow are affected by rainfall.  By definition, the amount of
inflow to a sewer system is, mostly, directly related to  rainfall,
The direct relationships between rainfall and infiltration, on
the other hand, are not so apparent.  While most of the infiltra-
tion phenomena are caused by the seepage  of the groundwater
through defective pipes, pipe joints, connections, or manhole
walls, rainfall during a high groundwater period indeed
aggravates the infiltration problem.  On the one hand, rainfall
and/or the surface run-off may seek the cracks in the soil sur-
rounding the manholes and leak through the deteriorated manhole
walls to cause an infiltration problem.  On the other hand, dur-
ing a heavy rainfall, the rainwater may reach the groundwater
by percolating through some highly permeable soils and cause a
general increase of the groundwater level.  This increases the
total hydraulic head above the sewer pipes and causes more water
to enter the pipes through defected joints, etc.  In locations
where the sewer pipes cut the underlain bedrock, the rain-
water, after percolating through the overlying soils, may flow
over the rock surface to the areas of lower elevations, generally
in the sewer trench, and there cause an increased infiltration
problem in the sewers.
                            3-25

-------
 During heavy rainfalls, another phenomenon may occur in the
 soil  and  increase the infiltration rate in the sewers.  This
 is  the case when a large ground surface is covered by impounded
 rainwater; as this large blanket of impounded water percolates
 through the soils underneath, it leaves little chance for
 the air in the soil to escape.  Because of this, the air
 is  subjected to increasing pressure.  The pressure is trans-
 mitted to the groundwater above the sewer pipe and causes
 an  increase in infiltration rate through defective pipe Joints,
 etc.

 Therefore, rainfall data are very important for the infiltration/
 inflow study.  For adequate infiltration/inflow analysis,
 the following rainfall data are generally needed:

      •  Average annual rainfall;

      •  Daily rainfall for the wettest season in the
        most recent year;

      •  Hourly rainfall for some typical raining days.

 3.2.4.b   (2)  Data Collection - Rainfall data are usually ob-
 tainable from the following sources:

      •  National Weather Services, local offices;

      •  Climatological data  published by the National
        Weather Service;

      •  Airports;

      •  Universities;

      •  Military installations;  and

      •  Sewage treatment  plants.

When this information is  not available or additional data are
required,  rainfall gauges may be installed at selected  locations
in the study area  and the data gathered over some reasonable
length of time.   These data should then be compared with data
from nearby sources.

3.2.4.C  Soil

3.2.4.0.  (1)   Importance  of Soil Data  - Soil conditions  in an
area affect the  magnitude of the infiltration/inflow problem
in the sewer system in two ways, i.e.:
                            3-26

-------
     (a)  The permeability of the soil determines the rate of
          movement of the groundwater through the soil and the
          subsequent effects on the sewers.

     (b)  The nature of the backfill and bedding materials
          surrounding the sewers affects the structural integrity
          of the sewers.  All other conditions being equal,
          sewers constructed in permeable soils receive more
          infiltration than those constructed in less permeable
          soils.  Relatively impermeable soils, such as clay,
          may also seal off pipe openings and reduce the
          quantities of infiltration that would otherwise
          enter these openings.

Sewers constructed on poor soils may be subjected to settlement,
resulting in open joints or cracking of pipe.  Unequal settle-
ments of manholes and sewers in soils may result in open
connections through broken pipes or joints.   Elastic soils such
as clay may subject the pipes to expansion and contraction,
resulting in loose joints and/or broken pipes.

Thus a study of the soil conditions in the sewered area may be
necessary to the understanding of some observed infiltration
problems.  It may also assist the engineer to locate areas
where there are potential infiltration problems.

In .the selection of chemical grouts for the  sealing of sewer
pipes and joints during sewer rehabilitation, the type of  the
soil surrounding the pipe is also one of the deciding factors.

3.2.4.C (2)  data Collection and Presentation - The information
on soil distribution and soil characteristics in an area can  be
obtained from the following sources:

     •  Soil Conservation Service, U.S. Department of
        Agriculture;

     •  Boring logs in sewer construction contract documents;

     •  State Agriculture Extension Service;

     •  Local construction companies or contractors;

     •  Field investigation.

The Soil Conservation Service has published  many soil maps
with descriptions of soil characteristics to a depth of 5
feet.  It has offices in most counties across the country.
Boring logs contained in the sewer construction contract
                            3-27

-------
documents provide detailed information about the soils along
the sewer construction route.  The State Agriculture Extension
Service may have collected data on the soil types and soil
characteristics in the study area.  Local construction companies
and contractors may also have some information about the
area's soil.  For locations where no soil information; is
available, some field soil study may be needed.  The study
may include the conducting of test borings at key points
and the interpretation of the collected soil samples.  For
complex and unusual cases, the soil samples should be interpreted
by the soil scientists in the Soil Conservation Service,
Agricultural Extension Service representatives, consulting
soil scientists or agronomists.

The soil distribution and characteristics in the study area
may be presented in the report.  The significance of the effects
of the soils on the integrity of the sewers and on the
infiltration/inflow problems in the study area may also be
discussed.

3.2.*Kd  Groundwater

3.2.4.d (1)  Importance of Groundwater Information - By defini-
tion, most of the infiltration phenomena in sewers are ground-
water-related.  In areas where the groundwater level is lower
than the sewer installation, infiltration may occur only during
heavy storms.  Both the level and the chemical characteristics
of the groundwater affect the degree of infiltration in the
sewers.  Sewers in contact with groundwater may be attacked by
the chemicals in the groundwater, such as sulfates and organic
acids.  Metal sewers may also be electrolytically corroded in the
presence of groundwater.  Once the openings in the sewers have
occurred,  under favorable soil conditions,  the degree of infil-
tration is directly related to the level of the groundwater
above the  sewers.

Because of the influence of the groundwater on infiltration,
the determination of infiltration in the sewer system should
be based on a comparison of the sewage flow data collected
in the high groundwater seasons versus those collected in
the low groundwater seasons.  To obtain realistic infiltration
flow data  in the Sewer System Evaluation Survey, the sewer
line inspection should also be conducted during high groundwater
seasons.   Thus, accurate groundwater information of the study
area is essential to the Infiltration/Inflow Analysis and
the Sewer  System Evaluation Survey.   Groundwater monitoring
will be needed if no data are available.
                            3-28

-------
3«2.4.d (2)  Data Collection and Presentation - General ground-
water information may be obtainable from a number of sources
such as:

     •  State Water Resources agencies;

     •  U.S. Geological Survey;

     •  Local or county water conservation districts;

     •  Groundwater users,  including municipalities,
        water companies and individuals;

     •  Local construction  companies or  contractors.

To obtain more detailed groundwater information in the study
area, field groundwater monitoring may have to be conducted.
This can be accomplished by one  or a combination of the fol-
lowing setups:

     •  Installation of groundwater gauges in sewer
        manholes at the crown of the pipe;

     •  Installation of groundwater gauges adjacent
        to the sewer pipes;

     •  Observation of the  water levels  in existing
        water wells;

     •  Observation of the  water levels  in specially
        dug water wells.

In a typical groundwater gauge installation in a manhole (Figure
3-1), the gauge is installed by  inserting a pipe through
the wall of the manhole at  an elevation  near the top of the
lowest sewer and attaching  a visible plastic viewing tube with
calibrated scale to this pipe.  The space between the pipe and
the hole in the wall should be properly  sealed to prevent leakage.
The groundwater elevation outside the manhole is observed at  the
plastic pipe inside the manhole.  Figure 3-2 shows a typical  setup
for a groundwater monitor in a specially dug or drilled water
well.  This installation would generally be made adjacent to  the
sewer pipe.  The groundwater level can be determined by insert-
ing a stick into the well casing and measuring the length of  the
unwetted portion of the stick after retrieval.

After the gauges or monitors are installed, they should be
inspected regularly to obtain needed information.  Continuous
recording devices can also be installed if necessary.  To deter-
mine seasonal groundwater variations, the monitoring may have
to be extended to an entire year.
                            3-29

-------
                         Secure
                         Transparent




\\\\\\\\N


r=y
. . • *
j
-4

» * »
. A
1 > fW*ffO r fCFTIf/y
/ Tube fo Sfcps
(
y^- Groundvater
₯ Gouge


^.:^::.^^-:.'v"x;".i::.
s\\\\\\VC
,/f

'•' V.
»r*-




                Sender
Figure 3-1.  Typical  Groundvater Gauge  Installation  in
             Manhole
                  3-30

-------
                          Cover

                                     Ground Surface
                               ' Diam, Augered Hole
                                Groundwoter Surface
                                Diam. PI/C Casing
                           -Cloth Wrapping to Exclude
                            Silty Material

                           •Open Slots to Allow
                            Entrance of Grounawater
Figure J-2,  Typical Grouncwater Gauge Installation in Soil
             (Courtesy of Dufresne-Henry Engineering Corp.)
                     3-31

-------
 The  recorded  data  should  always be reviewed  and  screened  care-
 fully  before  being used.   Pumping water  from nearby wells may
 cause  a  temporary  draw down  of the groundwater surface at the
 monitoring  stations.  Under  such conditions, the recorded water
 levels do not represent the  highest possible groundwater  levels
 in the area under  normal  conditions.  For infiltration studies,
 the  highest groundwater levels are of major  concern.  Therefore,
 whenever possible,  the groundwater levels should be recorded
 during the  periods  of a day  when groundwater pumping in the
 study  area  is at a  minimum.

 Clogging of the gauging pipes or monitors by silt, clay or
 other  minerals in  the groundwater may also cause erroneous
 results.  The gauges or monitors should  be frequently checked
 to detect and correct any possible cloggings.

 In the analysis report, the  groundwater  elevations should be
 presented along with the dates of measurements and monitor
 locations.  The determination of infiltration and inflow should
 be made  with  proper considerations of the groundwater conditions
 in the study  area.

 3.2.5  Population, Water Consumption and Wastewater Flow Data

 3 . 2. 5 . a  Intrqduction

 The  population, water consumption and wastewater flow data
 are  essential for the determination of infiltration and
 inflow.  From population and water consumption data, the
 theoretical (or base) wastewater production rate in the study
 area can be determined.  This production rate represents the
 quantity of wastewater normally expected in the sewer system,
 including domestic, commercial and industrial wastewater
 flows,  but excluding all infiltration and inflow.  Once the
 theoretical wastewater production rate is derived, the infil-
 tration and inflow can be calculated by comparing it with the
 actual wastewater flow data.  Wastewater flows over and above
 the theoretical wastewater production rate,  correlated with
 weather and groundwater conditions,  are considered as the
 infiltration/inflow.  (Detailed procedures for the determina-
 tion of infiltration and inflow are  presented in Section 3.3.)

 However,  if the infiltration/inflow in a system can be
 determined by direct flow measurement, then the data for
population and water consumption may not be the controlling
 factors in the I/I determination.

 3.2.5.b  Population

The population data need to be gathered only for the period
 in which records for water consumption,  wastewater flow,
 groundwater and rainfall are all available.   If these records
 were not available in the past and need to be generated
 during the study period, the population for the same period
 should then be known.

                            3-32

-------
For the determination of infiltration and inflow, both the
total population and the population serviced by the sewers
(.the sewered population) need to be known.  In areas where
there are seasonal fluctuations of populations, a detailed
breakdown of the population according to season or month
should be provided.

The population records are usually available in the U.S. Census
Bureau, local government offices and sanitary districts.  They
may also be contained in previous engineering study reports.   If
no data are available, a house-to-house count may have to be  done
to determine the population.

3.2.5.c  Water Consumption

The water consumption data should be obtained for the year(s)
for which records for wastewater flow, groundwater and
rainfall are all available.  If these records are not available
and need to be generated during the study period, the water
consumption data for the current year or the immediate previous
year should be obtained.

If'metered water use data are available for all users in the
study area, they should be collected and used for the estimation
of wastewater production rate.

In communities where metered water use records are not available,
the water supply data from all supply sources should be collected
Along with these, the portion of water consumption which is not
expected to enter the sewer system, such as system losses,
irrigation use, etc., should be estimated.

Water consumption records are usually obtainable from local
water departments, private water companies, industrial plants
and individual well users.

If no records are available, estimations can be made based on
population and an inventory of the residential, commercial and
industrial establishments in the study area using some typical
water use rates.

3.2.5.d  Wastewater Flow

Whenever possible, uninterrupted wastewater flow records
covering a period of  1 to 2 years of the most recent years
should be obtained for infiltration and Inflow determination.
Records which cover a period  (or periods) shorter than this
may also be sufficient if the period  (or periods) includes all
representative groundwater and rainfall conditions in the study
area.


                             3-33

-------
The flow records should cover the wastewater flows in the
entire sewer system under study.  In large sewer systems,
flow records may have to be gathered from more than one
treatment plant, pumping station or flow measurement station
in the system.  In addition, flow records for overflows,
bypasses and emergency pumping should also be gathered, if
available.  Wastewater flow records, if available, can
normally be obtained from sewage treatment plants, sanitary
districts or sewer departments in local governments.

All records should be checked for accuracy before being
used.  The accuracy of the records can be determined by
checking the accuracy of the instruments used for recording
and totalizing the flows.

If no wastewater flow records are available, a flow measure-
ment program should be initiated.

3.2.6  Plow Measurement

3.2.6.a  Introduction

In the Infiltration/Inflow Analysis, flow measurements may
be required for various reasons:

     (1)  For sewer systems which have sufficient existing
          flow data for the determination of infiltration/
          inflow,  flow measurements may be needed for the
          following purposes:

          (a)  To  check the accuracy of the existing flow
               records;

          (b)  To  determine the infiltration/inflow in sub-
               divided areas (the subsystems) to facilitate
               the determination of whether there is possibly
               excessive infiltration/inflow, through a cost-
               effectiveness analysis or other approaches;  and

          (c)  To  determine the infiltration/inflow in sub-
               divided areas so that subareas with no
               infiltration/inflow problems can be eliminated
               from further study and the planning of a Sewer
               System Evaluation Survey program can be accom-
               plished.

     (2)   For systems which have  no existing flow records
          or where data are insufficient or inaccurate, flow
          measurements are always needed for infiltration/
          inflow determinations and also for the aforementioned
          purposes.
                           3-34

-------
Flows which need to be determined may include:

     •  Total wastewater flows, including domestic,
        commercial and industrial wastewaters and
        infiltration/inflow;

     •  Industrial wastewater flows;

     •  Bypasses;

     •  Overflows;

     •  Emergency pumpings; and

     •  Infiltration/inflow.

Along with flow measurements, groundwater and/or rainfall
gaugings may also have to be performed in some instances.

Depending on the availability and adequacy of the existing
flow data and the conditions in the sewer system and study
area, either instantaneous flow measurement or continuous
flow monitoring may have to be conducted.

3.2.6.b  Planning of Flow Measurements

3.2.6.b (1)  General - To obtain sufficient flow data for
the analysis in as short a period of time as possible, proper
planning cannot be overemphasized.  The time suitable for
flow measurement is generally limited because peak infiltra-
tion occurs only during high groundwater periods and peak
inflow normally occurs only during heavy rainfall seasons.
If high groundwater periods or heavy rainfall seasons are
missed, the investigation may have to be postponed and the
facilities planning may be delayed.

3.2.6.b (2)  Timing of Flow Measurement - For accurate
determination of infiltration/inflow, it is desirable to
obtain continuous flow data over a period of an entire year;
but, in most cases, extending the measurements to such a long
period of time is not warranted.  For adequate infiltration/
inflow analysis, flow data for the periods covering high
groundwater and rainfall conditions are usually all that are
needed.

For the determination of peak infiltration, flows should be
measured during the highest groundwater period of a year,
To determine the peak inflow, flow data for the heavy
rainfall periods should be obtained.  To determine the
total yearly infiltration/inflow, flows may also have to be
measured during other typical groundwater conditions.
                            3-35

-------
 Continuous  flow measurements are desirable.  However, if
 the  infiltration is to be directly measured, instantaneous
 flow measurement would be sufficient because the groundwater
 level is normally relatively stable over periods of several
 days.  For  direct inflow measurements, the flows should be
 monitored continuously throughout each rainfall period.

 If infiltration is to be measured directly, the measurement
 should be performed in nonrainfall days, preferably at least
 24 hours after a rainfall to minimize the direct influence
 of rainfall.  To minimize the interferences caused by domestic,
 commercial  and industrial flows, flow measurements should
 be performed during early morning hours, approximately from
 midnight to 6 a.m.  To avoid possible errors caused by waste-
 water discharges during flow measurement, repeated flow
 measurements should be conducted in three consecutive non-
 rainfall days for each typical groundwater condition.
 Consideration must'be given to Industries that operate 24
 hours per day, the living habits of the community and flow
 lag  time in the pipes.

 To minimize the interferences caused by domestic, commercial
 and  industrial flows, direct inflow measurements should be
 performed during rainfall in the early morning hours.

 To avoid surge flows, all pumpings in the sewer system
 should be temporarily stopped during flow measurement if
 instantaneous flow measurements are taken.

 3.2.6.b (3)  Division of Subsystems - For the determination
 of infiltration/inflow, flow measurement can normally be
 conducted at a single station to which the flow in the
 entire sewer system discharges, such as a sewage treatment
plant or a pumping station.

However,  in many sewer systems, there may be more than one
treatment plant or pumping station, and they may not be inter-
connected.   Under such circumstances, flow measurements have
to be conducted in all plants or pumping stations.

To facilitate the cost-effectiveness analysis and to formulate
a Sewer System Evaluation Survey program, a sewer system
may be divided into a number of subsystems and the flows
in each subsystem measured separately.  The number of subsystems
will vary from system to system, depending on the size, configu-
ration and nature of the system and the complexity of the
infiltration/inflow problems in the system.  One or a combination
of the following criteria can be used to divide the sewer
system:
                            3-36

-------
(a)   Drainage Area - Sewer systems  can  be  divided  into
     subsystems according to the  flow conditions in  the
     sewers.   A sewer map may reveal  that  the  sewers
     are generally constructed in several  major groups.
     The flows in the sewers of an  area may  converge to
     a single major point before  reaching  the  next group
     of sewers downstream.  The converging point can be
     a manhole or a pumping station.  Under  such conditions,
     it may be convenient to consider the  sewers within
     the area upstream from the converging manhole or
     pumping  station as a subsystem and measure the  flows
     in this  manhole or pumping station.

     In systems that contain several  treatment
     plants,  the sewers contributing  the flows to  each
     plant can also be considered as  a  subsystem.  The
     flow records in each plant can be  used  for infil-
     tration/inflow determination.  Additional flows, if
     needed,  may also be measured at  the treatment plants.

(b)   Age or Type of Sewers - The  sewers in a sewer
     system may have been constructed in different years.
     The degree of pipe deterioration varies in accordance
     with the age, the pipe and joint materials and  the
     construction method used. Sewers  constructed in
     different years may present  different infiltration/
     inflow problems.  To isolate the individual problem
     areas, sewer systems may also  be divided  into sub-
     systems  according to the age of  the sewers and
     type of  pipe.

(c)   Groundwater and Soil Conditions  -  In  a  large  study
     area, groundwater levels may vary  in  different  regions.
     Some of  the sewers may be constantly  submerged  in the
     groundwater; some may never  be submerged; some  others
     may be subjected to seasonal submergence; and in
     coastal  areas, the sewers may  be affected by  a  ground-
     water which fluctuates with  the  tide.  Different
     groundwater conditions cause different  types  and
     degrees  of infiltration/inflow problems in the  sewers.
     Therefore, in some sewer systems,  the subsystems can
     also be  divided according to the groundwater  con-
     ditions  in the different regions of the study area.

     Similarly, the soil conditions in  the different
     regions  of a study area may  also vary widely  and
     cause varied types and degrees of  infiltration/
     inflow problems in the sewers.  Subsystems may
     also be  divided according to the soil conditions
     in the study area.
                       3-37

-------
      (d)  Problem Areas - If, through interviews or other
          means, some major infiltration/inflow problem
          areas are suspected, these areas may also be
          singled out for detailed flow measurements and
          cost-effectiveness analysis.

3.2.6.b (.4)  Selection of Key Manholes - Before flow measurements
are undertaken, the manholes used for measurements should
be carefully selected.  Manholes selected for flow measurement
should be accessible and safe, suitable for installing flow
measurement devices and in key locations,  Careful selection
of flow measurement manholes will save field work and provide
sufficient essential flow information for further analysis.

Initially, the flow measurement manholes should be selected
on the basis of an analysis of the sewer maps and the subsystems
divided previously.  Sufficient manholes should be chosen to
adequately isolate the flows in each subsystem.  It is not
necessary to select one manhole for each subsystem,  Similarly,
more than one manhole may have to be selected in one subsystem
to more precisely define the flows in some problem areas.

After the manholes are selected and before actual flow measure-
ments are conducted it is advisable to locate the manholes
in the field.  This is important, especially when early
morning flow measurements are planned.  To make the Job easy,
personnel from the local sewer maintenance crew can be asked to
help locate the manholes and provide background information about
the manholes.  In case a predetermined manhole cannot be found
in the field due to various reasons, another key manhole should
be selected and field-located.

When the flow measurement manholes are located, they should be
opened and checked for accessibility and suitability for install-
ing flow measurement devices.   Items to check include:

     •  Safety precautions before entering the manhole;

     •  Size of the manhole opening and the inside
        diameter;

     •  Depth of the manhole;

     •  Workability inside the manhole;

     •  Stability  of the manhole  structure;

     •  Condition  of manhole steps;
                            3-38

-------
     •  Plow condition in the manhole;

     •  Amount of debris accumulation;

     •  Any additional pipe connections unrecorded
        in the sewer maps;

     •  Suitable location for installing flow
        measurement devices; and

     •  Traffic conditions during flow measure-
        ment periods.

A constantly surcharged manhole may not be suitable for flow
measurement.  All manholes found to be unsuitable for flow
measurement should be replaced with other suitable manholes.

3.2.6.b (5)  Other Measurements - Besides wastewater flow
and infiltration/inflow measurements, other measurements
which may have to be conducted are:

     •  Groundwater levels,

     •  Rainfall,

     •  Industrial wastewater flows,

     •  Bypasses,

     •  Overflows, and

     •  Emergency pumpings.

Plow measurements for the determination of infiltration
should be accompanied by a measurement of the groundwater
levels in the study area.  Plow measurement for the deter-
mination of inflow should be accompanied by a measurement of
the rainfall.  When flows are continuously monitored, both
groundwater and rainfall should be gauged simultaneously.
The groundwater and rainfall information can be obtained
either from existing gauging stations or through new setups.

Industrial wastewater flows may have to be measured for the
determination of infiltration/inflow.  If the infiltration
and/or inflow are to be directly measured during the early
morning hours, the wastewater flows from the night shifts
of the industrial plants should be determined and deducted
from the measured flows to derive the actual infiltration
and/or inflow.
                            3-39

-------
 The  flows  from all bypasses, overflows and emergency pumpings
 which  occur  during flow measurement periods should be deter-
 mined  and  added to the measured wastewater flow or infiltra-
 tion/inflow  so that true peak infiltration/inflow can be
 derived.

 3.2. 6.c  Flow Measurement Techniques

 When flow  data must be generated, the flow measurements
 become a critical component of the I/I Analysis and/or
 Sewer  System Evaluation Survey.  It is necessary to use a
 sound  approach and good flow measurement techniques to
 ensure reasonable results.  The obtained results do not
 necessarily  have to be as accurate as flow data obtained
 from a continuous flow monitor at the treatment plant.
 These measured flows will, however, be used in determining
 possibly excessive or nonexcessive I/I and thus some degree
 of accuracy  should be employed.

 To determine I/I, flow measurements may be taken at several
 locations.   These locations will depend on the sewer system
 being investigated, the flow data that are available and the
 flow data  that must be obtained.  Plow measurements may be
 obtained at  the following:

     •  Treatment plant influent,

     •  Treatment plant effluent,

     •  Pumping stations,

     •  Key manholes,

     •  Inflow sources that directly enter catch basins or
        manholes,

     •  Infiltration sources that directly enter manholes,

     •  Industrial waste sources, and

     •  Overflows and bypasses.

Other locations  and sources of I/I may be measured in a
particular sewer system.  There are a variety of methods
and equipment available for flow measurement in sewers.
The selection of the proper method or equipment will depend
on the cost,  source to be measured,  accessibility, manpower
availability, degree of precision and type of data required.
In the following subsections,  a few of the most commonly
used methods  and equipment will be presented.   The general
format which  will be employed  will be as  follows:
                            3-^0

-------
     •  Description of the  method,

     •  Equipment available,

     •  Installation instructions,  and

     •  Advantages and disadvantages.

3.2.6.C (1)   Depth Measurement  (Manual)  -

     •  Method - This method  involves  obtaining an instan-
        taneous depth of flow measurement in sewer pipes.
        In addition, a mean velocity  of  flow must  be  obtained
        in order to utilize the flow  formula, Q =  AV.   The
        mean velocity may be  obtained  theoretically by use
        of the Kutter formula or the more simplified  Manning
        equation, v _ 1.486 -2/3 cl/2.  The velocity  may also
                  V     — R    s
        be determined by actual measurement with a velocity
        meter or by time-distance measurements using  dye or
        floating objects.

     •  Equipment - Staff gauges marked  to the nearest 0.01 ft
        or 1/8-Inch would be  suitable  for depth measurements.

     •  Installation - In manholes  that  are relatively clean
        and accessible, the staff gauge  may be inserted into
        the invert of the manhole channel and the depth of
        flow measured.  The depth of  sediment in the  pipe
        should be noted and the depth of flow corrected
        accordingly.

        Some manholes may not be accessible.  In these
        instances, depth of flow may  be  obtained by utilizing
        a stadia rod.  An initial reading may be taken by
        placing the rod on the  manhole channel invert and
        noting a reading on the rod with respect to a
        reference such as the manhole frame.  A second
        reading can then be taken by  raising the rod  to the
        channel water surface and obtain a reading from the
        same reference.  The  difference  in the two read-
        ings will be the depth of flow.

     •  Advantages  -

        (1)  Inexpensive
        (2)  Rapid  results
        (3)  Ease of operation

     •  Disadvantages -

        (1)  Instantaneous result that may not be representative
                             3-41

-------
        (2)   Determination of mean velocity is critical
        (3)   Cannot be used in surcharged sewers
        (4)   Low degree of accuracy

3.2.6.C (2)   Depth Measurement (Instrument) -

     •  Method - This  method Involves  obtaining continuous
        depth-of-flow  measurements in  sewer pipes  by  various
        depth measuring and recording  devices.  In order  to
        determine flow, the mean velocity must  be  established
        as described in the preceding  section.

     •  Equipment -

        (.1)   Float-operated device which  rides  on  the
             surface of liquid and transmits  a  signal to  a
             receiver  which records the relative depth  or
             percentage of flow.

        (.2)   Pressure-differential depth  or percentage-of-
             flow recorders which bubble  air  at a  regulated
             rate through  a tube  which is  secured  to  the
             invert  of the sewer  pipe or  channel.   The  depth
             of  flow above the bubble tube  will cause a back
             pressure  and  thus the differential pressure  can
             produce a signal  which will  be proportional  to
             the  depth of  flow.

        (3)   Sensing devices which continuously travel  up and
             down and  sense the water surface.

        (4)   Ultrasonic sensing devices which utilize high
             frequency sound to sense the water surface.

        (5)   A low pressure transducer installed in the invert
             of the  sewer  pipe which measures height  (pressure)
             of flow and transmits a signal proportional  to the
             depth of  flow.

    •   Installation - Generally,  the devices are  installed
        in manholes  and the floats  or sensing devices are
        placed in or near  the  liquid.  The  specific Instal-
        lation of the  various  types of devices should be  in
        accordance with the manufacturer's  recommendations.

    •   Advantages -

        (.1)   Provides  continuous  recording
        (2)   Provides  a record of  results
        (3)   Generally accurate
                           3-42

-------
     •  Disadvantages  -

        (1)   Relatively high capital cost
        (2)   Routine maintenance  required
        (3)   Danger of theft and/or vandalism
        (4)   Danger of exposure to adverse  conditions

3.2.6.c (3)  Weirs and  Flumes

     •  Method - This  method involves the  observation  or
        recording of depth of flow over a  specific  weir or
        through a flume.  Weir or flume formulas  or tables
        are  utilized to determine the flow.

     •  Equipment - For flow measurements  in sewer  pipes,
        various V-notch weirs can be utilized.   Commonly
        used V-notch weirs are 22-1/2°, 30°, 45°, 60°  and
        90°.  In addition, rectangular and trapezoidal weirs
        may  be used.   Portable flumes are  also  available.

     •  Installation  - When installing weirs and flumes, it is
        important to  ensure that  a good seal is made between
        the  device and the pipe or,channel.  Sponge rubber or
        sand bags may  be used for sealing  purposes.  The weirs
        and  flumes should also be installed level.

     •  Advantages -

        (1)   Low costs
        (2)   Direct flow reading
        (3)   Many designs available for flexibility
        (4)   Generally accurate

     •  Disadvantages  -

        (1)   Must be installed in the sewer or channel
        (2)   Cannot be used for sewers flowing full or surcharged
        (3)   Weirs not recommended  for fast flowing sewers
        (4)   Instantaneous result

3.2.6.C (4)  Timed Volume  -

     •  Method  - This method  is used to determine  flow rates
        from leaking manhole  walls, wet well walls and
        accessible point  sources  of inflow.  The method
        involves the use  of a vessel of known  volume;  the
        time to fill this  vessel  is measured with  a stop
        watch or watch.
                            3-43

-------
     •  Equipment - One-, two- or five-gallon plastic pails
        are suitable for measurement of small streams.
        Larger vessels such as 55-gallon drums may be used
        but are cumbersome to handle.  A stop watch or a
        watch with a sweep second hand is suitable for
        monitoring time.

     •  Installation - The equipment used for this method of
        flow determination is generally portable and no
        specific installation is required.  When making
        the flow determination, the entire stream should
        be measured and the measurement repeated to ensure
        accuracy.

     •  Advantages -

        (1)  Accurate
        (2)  Inexpensive
        (3)  No specific expertise required

     •  Disadvantages -

        (1)  Generally cannot be used for flow in sewer pipes
        (2)  Not adequate for high-velocity flows

3.2.6.C (.5)  Pumping Rates -

     •  Method - This method of flow measurement uses pump
        design curves and the pumping time.  In addition,
        some pump stations have flow recorders which
        facilitate the gathering of flow data.  For ejector
        stations,  the number of times the system ejects may
        be counted;  and coupling this with the volume per
        discharge, one can determine the flow.

     •  Advantages -

        (1)  Extra flow-measuring equipment not generally
             necessary

3.2.6.C (6)  Dye-Dilution Method -

     •  Method - The dye-dilution method is a simple and
        quick method for the determination of the flows in
        the sewers.   The flow measurement  can be conducted
        above ground;  no manhole-entering is necessary.
        Using this method,  flows can be measured even if
        the sewers are running full or  surcharged.   The
        method is  normally used to measure the instantaneous
        flow rates in sewers.   However, with some added
        equipment, continuous  flow monitoring is also
        possible.

-------
Basically, the method involves the following procedure:

(.1)  Feed a fluorescent dye at a constant rate to an
     upstream manhole.

(2)  Collect the water samples from the sewers in
     the downstream manholes.

(3)  Measure the dye concentrations in the collected
     samples with a fluorometer.

(4)  Calculate the rate of sewage flow in each sewer
     section using the following formula:

          Qf = QI £l             (3-D
                  Cf

where:

             = the flow rate in the sewer;

             = the dye concentration in the sewage
               collected at the downstream manhole;

          QJ_ = the dye feed rate;

          C-^ = the dye concentration in the feed tank,

Materials - Three types of fluorescent dyes have been
used extensively as water tracers:  Rhodamine B,
Rhodamine WT, and Pluoresceln (Table 3-2).  For
accurate flow measurements in sewers, a dye which
has low sorptive tendency with the solids in the
sewage should always be used.  The fluorescence of
the rhodamine dyes is not stable outside of the pH
range of 5-10.  Most dyes undergo photochemical decay
in the sunlight.  Therefore, the samples should be
stored in the dark and analyzed as soon as possible
after collection.  The fluorescence of the dyes is
also affected by temperature.  During sample analysis,
if the temperature of the sample is different than
the room temperature, a correction factor should be
applied to the measured concentrations.  (The
temperature correction curve for Rhodamine B and
Rhodamine WT are shown in Figure 3-3.  The temper-
ature effect of Pluorescein is small and, normally,
need not be corrected.)

Installation - Although commercial solution feeders
are available, a simple homemade constant-head
solution feeder is usually sufficient for feeding

-------
                    Rhodamine  B
                    Rhodamine  WT
         0.9 ~
         0.8
         0.7
         0.6
Example:
 Dial reading	51   J.
 Sample temperature 	  62°
 Base temperature	72°
 Temperature difference .  . . +10°
 Correction factor	0.86
 Corrected dial reading =  0.86x5l=*W
           -30   -25   -20   -15    -10    -5     0    +5   +10   +15   +20   +25   +30

           TEMPERATURE DIFFERENCE  (BASE  TEMPERATURE MINUS SAMPLE TEMPERATURE), IN °F
Figure 3-3.   Te/nperofure-correcf ion  curve   for Rhodamine B and Rhodamine WT
                Dyes  [2]

-------
the dye at a constant rate to the manholes.   Figures
3-4 and 3-5 show two solution feeders which  can be
assembled easily in the laboratory.   In each of these
feeders, the feeding rate can be changed by  adjust-
ing the head between the water surface in the tank
and the opening of the inflow tube or orifice.

For collecting the samples at the downstream man-
holes, there is no need to enter the manhole.  A
container with a rope attached can be dropped down
into the manhole to collect the sample.  This would
minimize the need for elaborate safety equipment.
However, if the flows are small, it  would still be
more convenient to collect the samples by physically
descending into the manholes.  To minimize the loss of
dye due to adsorption, the sample container  should  be
made of high-quality glass, whenever possible.   Plastic
containers can also be used but ordinary soft-glass
containers should be avoided.  The samples should be
allowed to stand to reach room temperature and to
settle the suspended solids before being taken for
measurement.

There are two fundamental types of fluorometers:
(1) fluorescence spectrometers, or spectrofluoro-
meters, and (2) filter fluorometers, or fluorimeters.
The filter fluorometer is usually sufficient for an I/I
study.  Each fluorometer should be individually cali-
brated with standard dye solutions of known concen-
trations.  A calibration curve should be obtained
for each dye used.  In the suitable concentration
range, the calibration curve should show a linear
relationship between the fluorometer readings and the
dye concentrations.  To avoid possible interferences
by the solids or chemicals in the tap water, distilled
water should be used to prepare the standard dye
solutions.

The concentration, flow rate and quantity of the dye
solution to be used should be determined before the
flow measurement.  To make such determinations,
the total length of sewers to be studied and the
approximate flow rate and flow velocity in the down-
stream sewer section should be estimated.  The
following example  illustrates the calculation pro-
cedure:

-------
TUBE
»• —
RUBBER
" or 6
FLEX IB
OR RUB
• *

WATER LEVEL -1
IN BOWL I
rxXsZ1"^
^x^-MTU r~srv^-
rTf*— M^
L JL -Ji ,, . ^}\ s<*

L^
STOPPER ~~~^
mm dia. ) —
LE PLASTIC — •/
BER TUBE 11

f
i
^ — TUBE (1/8" or
1

I
i_
HEAD
I '
_(^fc£J£
^ ICx^x^rvT
•^^ •
'^ L
-

^-TUBE (1/8"
- — GUIDE STRING
3mm dia.)
WATER LEVEL
IN TANK
	 	 BOWL
• BALLAST
or 3mm dia. )
                                     FLOATING
                                     BOWL (SEE
                                     DETAIL ABOVE]
                     FLEXIBLE
                     RUBBER  OR
                     PLASTIC HOSE
                                 - GUIDE STRING
— CONTAINER
     Figure 3-4.   Floating Bowl  So lull on Feeder [3]
                            3-^8

-------
Flush  Drain
                                             • ij
                                             IT
                                   PLAN VIEW
                                           Vent
Guide
                            Rubber stopper
                   Liquid Level
                               Brass Tube

                          Bind  rubber tube
                          and brass tube
                          with  copper wire
         Wooden Float
          Orifice(Sized to
          prevent siphoning)
                                                                    Brass tube
                                                                    cast  in wal1


                                                                     Shut-off Valve
                                       Plastic Tubing
                                ELEVATION SECTION


        Figure 3-5.    Floating Platform Solution Feeder [4]
                                 3-^9

-------
Example:

Given:  Dye to be used - Rhodamine WT, 20% solution,
     specific gravity 1.19-  Total length of sewer
     to be studied - 40 manholes at 250-foot inter-
     vals, or 40 x 250 = 10,000 ft.  Plow in the
     last sewer section downstream equals approxi-
     mately 100 gallons/min.

Desired :  The concentration, flow rate and quantity
     of the dye solution required and the amount of
     the 20$ dye solution required.

Solution:  From the fluorometer calibration curve
     find the optimum dye concentration which can be
     detected, e.g. 50 parts per billion (ppb).

     A constant-head solution feeder is constructed
     which can adjust the flow rate between 0-50 ml/
     mln.  Use a flow rate of 20 ml/rain or 0.0053
     gallon/min Cgpm) .

     Rearrange Eq. C3-1) to give


          ci •     °r       (3-2>
     Where :

          Qf = 100 gpm;

          Cf = 50 ppb;

          Q± = 0.0053 gpm

     Therefore,
          c  . 100 Spm - x 50 ppb
          °i ~ 0.0053 gpm      vv

             = 9.4 x 105 ppb

             = 940 ppm;  say 1,000 ppm

     Assume a flow velocity of 2 ft/sec in the sewer,
     For 10,000 feet of  sewer, the total flow time
     would be:

          10i°0.0 ft = 5000 sec = 83 min
          2 ft/sec
                     3-50

-------
     At a flow rate of 0.0053 gpm,  the total dye
     solution required would be:

          0.0053 gallon/min x 83  min =0.44 gallon

     Therefore, about 0.5 gallon  of a 1000-ppm dye
     solution should be used for  this part  of the
     sewer system.  The dye should  be applied con-
     tinuously at a constant rate of 20 ml/min
     until all the samples are collected from the
     downstream manholes.  To insure that a suffi-
     cient quantity of dye solution is available,
     when feeding, approximately  1  gallon should be
     prepared.

     To prepare 1.0 gallon of 1000-ppm dye  solution
     from a 20% Rhodamine WT solution (Sp gr 1.19)
     the amount of the latter required can be cal-
     culated as follows:

          20% solution = 2 x 10^  ppm solution.
          The amount of the 20% solution required
          to prepare 1.0 gallon of  1000-ppm solution

          _ 1.0 gallon x 1000 ppm	
            2 x io5 ppm x 1.19 CSp  gr)

          = 4.2 x 10-3 gallon

     The specific gravity of the  solution should be
     taken into account because in the diluted dye
     solution the specific gravity  is close to one,
     which is different from that of the concentrated
     solution.

For continuous flow monitoring, a fluorometer equipped
with a flow-through door should be  used.  The samples
are withdrawn from the sewer with a pump and fed to
the fluorometer, where the dye concentrations are
measured and recorded automatically on a strip-chart
recorder.  The pump is powered either by commercial-
line power or by a gasoline driven generator.  If the
generator is used, a constant-voltage transformer is
normally installed between the fluorometer and the
generator supply to smooth out variations in generator
output which might affect fluorometer readout.  How-
ever, because of relatively high cost and possible
interferences by the solids and the air bubbles in the
samples, this technique is not normally recommended
for continuous flow monitoring.
                     3-51

-------
     •   Advantages -

        (1)  Accurate
        (2)  Saves time and provides flow data on many sewer
             sections

     •   Disadvantages -

        (1)  Manpower involved
        (2)  Maintenance cost
        (3)  Expensive instrumentation cost

3.2.6.d  Safety Measures

Entering manholes imposes a potential safety hazard which may
be far more serious than many people think.  The following facts
should be realized:

     (1)  Poisonous and explosive gases, such as hydrogen
          sulfide, carbon dioxide, ammonia and methane, may
          accumulate in the manholes.  Overexposure to these
          gases can kill a person.  Flame or sparks can cause
          an explosion.

     (2)  The structure of a manhole may not be sound:  the
          wall bricks may fall off; the steps may be corroded.

     (3)  Objects can fall through the manhole opening onto
          one's head; sharp objects such as broken glass, razor
          blades, etc.,  may cut one's hands and feet; a sudden
          increase in sewage flow in a large sewer may drown
          and sweep a person away; one can accidentally fall
          in a manhole due to various reasons.

     (4)  An open manhole without a guard and safety markers
          around it is dangerous to both the traffic above and
          the person working in the manhole.

To avoid any accident, proper safety precautions should always
be observed when entering a manhole even for only a short period
of time.  Safety procedures should be developed in accordance
with the Occupational Safety and Health Act (OSHA) and the Water
Pollution Control Federation (WPCF) Manual of Practice No. 1.
Before undertaking a manhole investigation project, the project
engineer should review and summarize for his subordinates
detailed information on safety procedures.
                            3-52

-------
3«2.6.d (1)  General Safety Precautions - The proper procedures
and general safety precautions of entering a manhole for
flow measurements or sewer inspection are summarized as  follows:

     (a)  Always organize and plan the work before entering a
          manhole.  Avoid prolonged stays in manholes.

     (b)  Prior to starting the work, all persons expecting
          to work in the manholes and the sewers should  obtain
          typhoid and tetanus innoculations .

     (c)  Never enter a manhole without someone attending topside

     (d)  Before opening a manhole, always place markers or
          traffic cones around it to caution the pedestrians and
          motorists.  An open manhole should always be  attended
          by a guard and have safety markers around it.

     (e)  Never smoke in or around a manhole.

     (f)  Use proper tools to open the manhole covers.   Avoid
          hurting back, feet and fellow workers.  The generally
          used tool is a manhole hook or crowbar.

     (g)  Before entering a manhole, determine if there  are any
          explosive gases in it using an approved gas analyzer
          and, with the same analyzer, determine if there is
          sufficient oxygen in the manhole.  Never assume that a
          manhole is safe because it was safe last time  entered.
          Never assume that a manhole is safe because there is
          no smell of gas.  If it is impossible to perform
          these tests or if the tests show that the explosive
          gas is present or the oxygen content is not sufficient,
          the manhole should be thoroughly purged with fresh air
          using an air blower and continuously ventilated using
          a 600 cubic feet per minute (cfm) air blower.

     (h)  Personal safety equipment (see Section 3.2.6.d(2))
          should always be worn by the persons entering the
          manholes.  Wear long trousers and heavy duty work
          shirts to avoid bruises and scrapes.

     (i)  Make sure that the manhole's brickwork is sound and
          that the steps can carry a person's weight.  Watch
          out for slippery, broken, or loose steps, benches, etc.

     (j)  Never leave loose, small tools or other objects near
          an open manhole.  To avoid being hit in the face or
          eyes by dropping objects, do not look up while in
          the manhole.
                             3-53

-------
     (k)  Do not lift a person out of a manhole by his arm unless
          it is an emergency; this may cause a serious shoulder
          separation,

     (1)  Never tie a safety harness rope to a car or truck.

3.2.6.d (2)  Personal Safety Equipment - The following is
a list of the safety equipment that should be worn by all
persons working in the sewer manholes at all times unless stated
otherwise.  All equipment should be OSHA approved .

     (a)  Hard Hats - Hard hats should be worn by all persons
          working in the manholes.  On jobs where heavy
          machinery is involved, hard hats should also be
          worn while working outside of the -manholes.

     (b)  Safety Harnesses and Rope - Safety harnesses should
          be worn by persons working in manholes.  A safety
          rope is attached to the harness to allow the person
          on top of the manhole to quickly remove an injured
          or overcome person from a manhole and to prevent
          a person from being swept away by a high flow
          in a large manhole or sewer.

     (c)  Steel-Toed Work Shoes - These shoes are designed
          to protect the upper part of the foot from being hurt
          by falling objects and to protect the soles from being
          penetrated by sharp objects such as broken glass, razor
          blades, etc.  These shoes are also designed for better
          foot support than ordinary shoes, being able to relieve
          some of the foot fatigue.

     (d)  Rubber Gloves - Rubber gloves should be worn by persons
          when hand contact with raw sewage or grouting chemicals
          is likely.

     (e)  Orange Safety Vests - These vests should be worn by
          persons working in or near any public road so they
          will be more visible to motorists.

     (f)  Goggles - Safety glasses or goggles should be worn  by
          persons working in areas where chipped debris or
          chemicals may cause eye injury.

     (g)  Gas Ampoules - Gas ampoules are used to detect the
          presence of the following gases:

          •  Hydrogen Sulfide
          •  Methane
          •  Carbon dioxide
                            3-54

-------
          Gas ampoules should be put  on before  descending  into
          a manhole and should be periodically  checked  to  detect
          any overexposure.

3.2.6.d (3)  Other Safety Equipment  - Other equipment essen-
tial to the safety of the persons working in manholes and
sewers is listed in Table 3-4.

3.2.7  Physical Condition of Sewer System

3.2.1.a  General

If cost-effectiveness analysis (Section 3• *0 is to be
used to determine whether the infiltration/inflow in a  sewer
system is possibly excessive or nonexcessive, some field work
may also have to be conducted to assess the general physical
conditions of the sewer system.

Normally, due to time limitation, the  physical condition
of a sewer system cannot be thoroughly investigated in  the
infiltration/inflow analysis.  Only the information essential
for the cost-effectiveness analysis needs to be collected.

Some information about the physical condition of the sewer
system may have been obtained from interviews and sewer maintenance
records; however, additional information may have to be collected
through other efforts, such as:

     •  Plow measurement in subsystems (Section 3.2.6),

     •  Physical inspection of key manholes and sewer lines
        (Section 4.2.4),

     •  Aboveground inspection  (Section 4.2.2), and

     •  Smoke testing or rainfall simulation (Section 4.3).

For the convenience of cost-effectiveness analysis, it may be
necessary to divide a sewer system into a number of subsystems
(Section 3.2.6.b  (3)) and consider each subsystem as an in-
dependent unit for the investigation.

Sufficient work should be performed to collect the informa-
tion needed for formation of some sound bases for the
estimation of:

     •  The work  required to conduct a Sewer System
        Evaluation Survey (Chapter 4);
                            3-55

-------
                          TABLE 3-4
     SAFETY EQUIPMENT FOR MANHOLE AND SEWER INSPECT ION [5]
First-aid kit
Self-contained breathing apparatus
Bump caps
MSA wristlets with 25 ft rope
Gas mask (H2S)
Knee boots
Air blower, 3 HP, 1750 CFM
Air hose with air check
Aluminum ladder, 16 ft extension
Drop cord
Safety cones 28 in.
Isolation transformer (1-5 KVA, 50/60 HZ)
Beacon
Fire bottle (C02)
Fire extinguishers
Rain suits
                             3-56

-------
     •  The portion of sewer lines  requiring rehabil-
        itation to remove the infiltration/inflow and
        the types of rehabilitation needed (Chapter 5);
        and

     •  The types and approximate number of inflow
        sources which may need correction (Chapter 5).

3.2.7'b  Investigation Procedures

As a first step of investigation, flows in the key manholes
of each subsystem should be measured so that the seriousness
of infiltration/inflow problems in each subsystem can  be
evaluated.  Infiltration and inflow are usually measured
directly during the early morning hours (Section 3.2.6.b
(2)).  Subsystems with no apparent  infiltration/inflow problems,
as judged by the amounts of infiltration and inflow measured,
can be eliminated from further investigation, and they should
be excluded from the cost-effectiveness analysis.

One method which can be used to Judge the seriousness  of
the infiltration problem is to compare the measured infiltra-
tion rates, in unit of gallons per day per inch diameter per
mile with the installed infiltration specification allowance
for the sewer lines under consideration.  If the former is
less than the latter, it can be concluded that there is no
excessive infiltration in the sewer lines((Section 3-5).

If, after flow measurement, some subsystems are found  to
exhibit infiltration/inflow problems, the investigation can
be continued by conducting a physical inspection of a  few
selected key manholes in each of these subsystems.  The
purpose of this inspection is to:

     •  Understand the general physical conditions
        of the manholes"and sewers;

     •  Determine the types of infiltration/inflow
        sources and amount of flow from each source,
        if possible; and

     •  Determine the type and degree of deposits
        in the manholes and sewers.

To determine the types and general locations of the inflow
sources in each subsystem, some aboveground inspection,
smoke testing and/or rainfall simulation may also have to
be performed.

(Detailed procedures for these investigations are given in
Chapter 4).
                            3-57

-------
3.3  DETERMINATION OF INFILTRATION/INFLOW

3.3.1  General Considerations

The determination of infiltration/inflow is one of the most
important tasks in the Infiltration/Inflow Analysis.   Without
adequate flow information, it would be difficult to conduct
either a cost-effectiveness analysis, or some other method
of analysis to determine the existence or nonexistence of
excessive infiltration/inflow in a sewer system; and, if
the flow data are incorrect, false conclusions may result.

For the convenience of cost-effectiveness analysis and for
establishing the design flow and criteria, the following
flows are usually individually determined:

     •  Peak Infiltration

     •  Peak Inflow

     •  Peak Infiltration/Inflow

     •  Total Yearly Infiltration

     •  Total Yearly Inflow

     •  Total Yearly Infiltration/Inflow

The peak flow rates affect the sizing of the sewers and the
pumping facilities.  They also affect the sizing of the
hydraulic treatment units, including clarifiers, chlorination
units and plant pumping stations.  In fact, even the  biological
treatment units can be affected by the sewage flow conditions.
Sudden increases in sewage flow due to infiltration/inflow
may wash out the active biomass from the aeration units
and disturb the biological balance, resulting in reduced
treatment efficiencies.  Flow increase due to infiltration/
inflow may also reduce the hydraulic detention time in the
aeration units to a value insufficient for adequate biological
reactions to take place.   These situations may have to be
remedied by either designing larger aeration units or adding
a flow equalization basin, both of which increase the treatment
costs.

The total annual quantities of infiltration and inflow
should be determined for the estimation of the annual
operation costs for the pumping and treatment facilities.
Using the peak rates of infiltration and inflow for cal-
culations will overestimate the operation costs.
                             3-58

-------
The infiltration and the inflow should be individually
estimated because the characteristics and sources of these
two types of flows are quite different and their correction
and treatment methods may also differ.  By separate deter-
minations, the significance of each type of flow can be
individually recognized.  And, in conducting the cost-
effectiveness analysis, more realistic treatment alter-
natives can be formulated.

Often, however, it is not possible to precisely determine
the infiltration and the inflow by their literal definitions.
The infiltration determined from the dry weather high ground-
water flow data may contain some amounts of inflow which are
not related to rainfall.  Similarly, the inflow determined
from the wet weather flow data may also contain some amounts
of infiltration which are induced by rainfall.  Without in-
depth field investigations, it is almost impossible to
separate the two flows in either of these two cases.  The
flows determined in the former case may be more aptly termed
the "dry weather infiltration/inflow"; and the latter, the
"wet weather infiltration/inflow" or the "rainfall associated
infiltration/inflow".  For the purpose of determining whether
there is possibly excessive infiltration/inflow, normally these
flows can readily be used for conducting the cost-effectiveness
analysis; in either case, it is not necessary to accurately
determine the individual flows.

When sewage flow data and other pertinent information are
available, normally the infiltration and inflow can be
readily determined without additional flow measurements.
Conversely, if there are no sewage flow data and other pertinent
Information or if the data and information are insufficient
or inaccurate, a flow measurement program should be initiated
to gather sufficient information for infiltration/inflow
determination  (Section 3.2).

The information which is normally needed for infiltration and
inflow determinations includes:

     •  Sewage flow data,

     •  Water  consumption records,

     •  Rainfall data, and

     •  Groundwater records.

Under appropriate conditions, infiltration/inflow in a sewer
system may also be directly measured.
                             3-59

-------
3.3-2  Determination of Infiltration/Inflow  Using  Wastewater
       Flow Data

3.3*2.a  Introduction

The wastewater flow data to be used for  infiltration/inflow
determination may come from either existing  flow records  or
records of flow measurements conducted during the  study
period.  The records may be either long  term (i.e.,  one year
or more), or short term.  They may be collected from either
one terminal flow measurement station, such  as a sewage treat-
ment plant, or several stations in the sewer system.   The
basic procedures of determining infiltration/inflow  using
all such flow data are similar.

3.3.2.b  Determination of Infiltration/Inflow Using  Long-Term
         Flow Data From One Measurement  Station

Basically, the procedure includes the following steps:

      (1)  Determination of theoretical wastewater  production
          rate,

      (2)  Determination of total yearly  infiltration/inflow,

      (3)  Determination of total yearly infiltration,

      (4)  Determination of total yearly inflow,

      (5)  Determination of peak infiltration,

      (6)  Determination o.f peak inflow, and

      (7)  Determination of peak infiltration/inflow.

 3.3.2.b (1)   Determination  of Theoretical (or Base)  Wastewater
 Production Rate - The theoretical  wastewater production  rate
 is the rate of wastewater  flow which should be expected  in a
 sewer system if there is  no  infiltration/inflow.  This rate  is
 usually determined from water consumption data.   The frequently
 used design average wastewater flow of  100  gallons  per capita
 per day should not be used for such purpose because the
 actual per capita wastewater production rate in an  area  may
 be different from this arbitrarily chosen  figure.

 For infiltration/inflow determinations, generally,  it is
 only necessary to derive an annual average  theoretical  waste-
 water production rate.  However, in locations where large
                             3-60

-------
fluctuations of water consumption and wastewater flow rates
occur due to seasonal change in population or other reasons,
seasonal or monthly wastewater production rates may have to
be determined.

The water consumption data used for this determination should
be of the same year, or immediate previous year, as the waste-
water flow data to be used for the determination of infiltration/
Inflow.  Data from a different year can also be used if it
can be substantiated that there has been no significant change
in water consumption in the two years.   This precaution is
necessary for the derivation of reasonable infiltration/inflow
rates .

If metered water use data are available, the theoretical waste-
water production can be determined by estimating the percentage
of the water which would reach the sewer system.  In general,
80 to 90$ of the residential water use  would reach the sewers.
Industrial plants may or may not treat  and discharge their
wastewaters separately; the amounts of  wastewater discharged
to the sewer system under study should  be individually determined

If no metered water use data are available, the total water
consumption (or, water production) data can be used.  To
determine the theoretical wastewater production from the
water consumption data, one should realize that not all the
water consumed reaches the sewer system.  Portions of the
consumed water may be lost through a number of routes, such
as:

     •  Lawn watering,

     •  Irrigation,

     •  Car washing,

     •  Fire fighting, hydrant testing,

     •  Separate treatment and disposal of wastewater by
        industries,

     •  Subsurface disposal by septic tank users, and

     •  Leakage from water mains, and service pipes.

These losses should be properly estimated and deducted from
the total water consumption rate to derive the theoretical
wastewater production rate.  In general, 60 to 80% of the water
consumption will become sewage.
                           3-61

-------
The wastewater separately treated and disposed of by industries
and the water lost to fire fighting and septic tank sub-
surface disposal areas can normally be estimated rather
accurately by reviewing related records .   The water loss
from pipe leakage may be estimated by comparing pumping and
water meter records.

The water losses to lawn watering, irrigation, car washing,
etc. are usually not easy to determine.  However, for most
northern states, the water losses in this category are
usually small during the winter months.  Therefore, the annual
average theoretical wastewater production rate may be assumed
to be approximately equal to the average  water consumption
rate for the winter months minus the water losses due to
private and industrial wastewater disposals,  fire fighting,
pipe leakage, etc., if these losses are found to be significant.
In southern states, the water losses to lawn  watering, irrigation,
car washing, etc., may still be significant even in winter
and they still have to be properly estimated  and deducted
from the total water consumption rate to  derive the theoretical
water production rate.

3.3.2.b (2)  Determination of Total Yearly Infiltration/Inflow  -
To determine the total yearly infiltration/inflow and the general
nature of the infiltration/inflow problem in  a sewer system,
the following procedure is- recommended:

     (a)  Calculate the average monthly,  average weekly,
          or daily wastewater flows for the year(s) for which
          records have been obtained.

     (b)  Plot these average flows against time (see Figure 3-6).

     (c)  Plot the theoretical wastewater production rate,
          rainfall and groundwater levels on  the same plot.

     (d)  On this plot, measure the total area above the
          theoretical wastewater production curve and below
          the wastewater flow curve for each  one-year period.
          This area would represent the total yearly Infiltra-
          tion/inflow.  If more than one  year's total
          infiltration/inflow can be determined, the highest
          figure should be used.

     (e)  On the same plot, measure the total area, if any,
          below the theoretical wastewater production curve
          and above the wastewater flow curve for each one
          year period.  This area could represent the total
          yearly exfiltratlon in the sewer system.  (This
          situation is not demonstrated in Figure 3-6).

     (f)  Compare the curves for wastewater flow, rainfall
          and groundwater to reveal their inter-relationships.


                            3-62

-------
  I
  I
   s
  .3
   V.
   0)
  •».
  I
  I
  u!
   V.
   
  I
  i
             Recorded Wastewater Flew
Total Infiltration/Inflow
           £—Theoretical Wastewater Production Rate
                                                     I  Yr.
                              Time
Figure 3-6.   Determination of Total Yearly InfiItration/Inflow
                     3-63

-------
 If the plot indicates no exfiltration in the sewer system,
 the total yearly infiltration/inflow may also be directly
 calculated by subtracting the total yearly theoretical waste-
 water production from the total yearly wastewater flow.

 3.3.2.b  (3)  Determination of Total Yearly Infiltration -
 The total yearly infiltration can be determined by the
 following procedure :

     (a)  Prom the plot generated by the procedure outlined
          in the previous section (Figure 3-6), select
          several months with typical wastewater flow con-
          ditions, including highest, lowest and average
          flow conditions.  The months in which exfiltration
          is suspected to have occurred should also be
          included.

     (b)  For each of these months, plot the daily wastewater
          flow, the theoretical wastewater production rate
          and the rainfall data against the time (Figure 3-7).
          If groundwater data are available, they can also
          be shown in the same plot.

     (c)  For each month, estimate the lower limit of the
          wastewater flow curve corresponding to the flows
          for nonrainfall days.  Measure the area between
          this limit and the theoretical wastewater production
          rate.  This area would represent the base infiltra-
          tion, or exfiltration, for the month (Figure 3-7).

     (d)  Calculate the average of the base infiltration for
          all typical flow months, adjust it with estimated
          exfiltration rates, if any, and project it to a
          yearly total.  The latter would represent the
          total yearly Infiltration.

The total yearly infiltration determined in the above manner
may also include some amounts of sustained inflow which
enter the sewers during nonrainfall days, such as cooling
water discharges, drains from springs and swampy areas,
foundation drains,  etc.  Therefore, the determined flow
could be more properly termed "the total yearly dry weather
infiltration/inflow."

If the  sustained inflow can be determined during the study
period,  it should be subtracted from the flow derived
through the above procedure to determine the "true" total
yearly  infiltration.  However, for the cost-effectiveness
portion of the Infiltration/Inflow Analysis, it is generally
not necessary to make this correction.

3.3.2.b (*Q  Determination of Total Yearly Inflow - After
the total yearly infiltration/Inflow and total yearly
infiltration have been determined, the total yearly Inflow
may be  calculated by subtracting the latter from the former.
                            3-6M

-------
  o
 H-
  c
 I
 0)
 1
 i
 5
 2
            Recorded Wastewater Flew
                     Non-rainfall day
                     Wastewater Flow
                        -J\
              Total Infiltration
L Theoretical Wastewater
  Production Rats	
                                              Maximum InfiIt rat ion
                       Time
                                          I month
Figure 3-7.   Determination of Total Yearly Infiltration
                    3-65

-------
Just as the total yearly infiltration determined in the
previous section, the total yearly inflow determined in
this manner may not be purely inflow in the literal sense.
It may contain some amount of infiltration which is
induced by rainfall, and it could be more properly termed
the "wet weather infiltration/inflow" or "rainfall associated
infiltration/inflow".  However, for the cost-effectiveness
portion of the Infiltration/Inflow Analysis, it is generally
not necessary, and may not be possible, to find out what
percentage of the total yearly inflow determined above is
actually rainfall-induced infiltration.

3.3.2.b (5)  Determination of Peak Infiltration - Since the
groundwater levels are normally relatively constant over
periods of several days, the peak infiltration can be con-
sidered as the maximum infiltration which occurs during
the maximum groundwater period of a year.  Prom the waste-
water flow curves for the months of highest flow conditions,
the peak infiltration can be readily determined (Figure 3-7).

3.3.2.b C6)  Determination of Peak Inflow - The following
procedure may be used to determine the peak inflow:

     (a)  Carefully examine the wastewater flow and rainfall
          records to select the days with highest wastewater
          flows and heaviest rainfalls.

     (b)  For each of these days, plot the actual hourly
          wastewater flow rates against time.   All emergency
          pumpings, bypasses and overflows should be Included
          in each corresponding hourly wastewater flow curve.
          The hourly rainfall data should also be shown in
          the same plot (Figure 3-8).

     (c)  Superimpose on each of the above flow curves a
          typical hourly wastewater flow curve for one of
          the nearest nonrainfall days (Figure 3-8).

     (d)  Measure the difference in flow for each hour
          between each set of two flow curves  described in
          Steps b and c and record the maximum difference
          for each day.

     (e)  Compare the maximum flow differences for all the
          days considered and select the peak value.  This
          peak value would represent the peak inflow in the
          sewer system.
                             3-66

-------
i
I
Total Bypasses,
Overflows,
Emergency
Pumping, etc.
                                     - Peak Inflow
                               Wastewater Flew
                               of Highest Flow
                                      Wastewater Flew of Nearest
                                     Hon-RainfaU Day
                             Time
                                                  I Day
        Figure 3-8.  Determination of Peak Inflow
                     3-67

-------
3.3.2.b  (7)  Determination of Peak Infiltration/Inflow -
The peak infiltration/inflow can usually be approximated
as the sum of peak Infiltration and peak inflow separately
determined above.

3.3.2.C  Determination of Infiltration/Inflow Using Long-Term
         Flow Data From Several Flow Measurement Stations

If the wastewater flow data is from several flow measurement
stations in a sewer system, the infiltration/inflow can be
determined separately in each subarea contributing flows to
the flow measurement station, following the procedure des-
cribed in Section 3.3.2.b.

In order to do so, the water consumption data for each sub-
area should be obtained to derive the theoretical wastewater
production rate.  If it is not possible to obtain such data,
then  the sewered population in each subarea should be
determined.  Prom the total water consumption and the total
sewered population in the entire sewer system, the per capita
water consumption rate can be determined.  Multiplying this
rate by the sewered population in each subarea, the water
consumption in each can be determined.

If the sewer system handles industrial wastewaters, the
industrial water consumption should be subtracted from the
total water consumption before the aforementioned calculations.
The  industrial wastewaters in each subarea should be Individually
determined and added to the theoretical wastewater production
rate derived by using the adjusted water consumption value.

3.3.2.d  Determination of Infiltration/Inflow Using Short
         Term Flow Data

For the purpose of this discussion, the short term is
defined as a period (or periods) of less than one year.
Wastewater flow data covering a period (or periods) of
shorter than one year may also be used to determine the
infiltration/inflow if the period (or periods) covers all
representative groundwater and rainfall conditions, including
high,  low and average conditions, in the study area.   The
following are the recommended procedures:

     (1)   Determine the total infiltration/inflow, total
          infiltration and total inflow in each period for
          which wastewater flow data has been obtained,
          following procedures similar to those outlined
          in Section 3.3-2.b (1) through 3-3.2.b
                            3-68

-------
     (2)  Calculate the sum of all total infiltration deter-
          mined in Step 1 and the sum of total days in the
          period or periods.  Determine the average daily
          infiltration by dividing the total infiltration by
          the total sum of days.  Determine the total yearly
          infiltration by multiplying this final average
          daily infiltration by the total number of days in
          a year.

     (3)  Calculate the sum of all total inflow determined
          in Step 1 and the sum of all rainfalls which
          occurred in the flow measurement periods .  Deter-
          mine the total yearly inflow by dividing the sum
          of total inflows by the sum of all rainfalls which
          occurred in the flow measurement periods and mul-
          tiplying the result by the average yearly rainfall,

     (4)  Calculate the total yearly infiltration/inflow
          by adding the total yearly infiltration and total
          yearly inflow.

     (5)  Determine the peak infiltration, peak inflow and
          peak infiltration/inflow following the same pro-
          cedures outlined in Sections 3-3.2.b (5) through
          3.3.2.b (7).

3.3.3  Determination of Infiltration/Inflow by Direct Flow
       Measurement

1'3'3-a  Introduction
The infiltration/inflow in a sewer system can also be
determined by measuring the infiltration and the inflow
directly.  Plow measurement requirements and general pro-
cedures have been presented previously (Section 3.2.6).
The procedures for the calculation of yearly total and peak
flows are discussed in the following subsections.

3.3«3.b  Determination of Total Yearly Infiltration

     (1)  List all measured infiltration.  (The measurements
          should have covered all typical groundwater con-
          ditions of a year.)  Adjust the flow values
          by subtracting from them all wastewater flows
          which might have entered the sewers during
          flow measurement periods, including domestic,
          commercial and industrial flows, and adding to
          them all flows which might have left the sewer
          system in the same periods, such as overflows,
          bypasses, etc.
                             3-69

-------
     (2)  Calculate the total infiltration in each typical
          groundwater period, assuming that the infiltration
          is constant throughout the entire period and
          equal to the infiltration rate measured during
          the period.

     (3)  Calculate the sum of all total infiltration
          derived.  This sum would be the total yearly
          infiltration.

     (4)  If flow measurements were conducted in more than
          one station, the total yearly infiltration in
          each subsystem should be determined and added
          together to obtain the total yearly infiltration
          for the entire system.

3.3.3.0  Determination of Total Yearly Inflow

     (1)  Determine the total inflow during each rainfall
          period using the hydrograph on the flow recording
          chart.  Adjust the flow values by subtracting
          from them all wastewater flows which might have
          entered the sewers during flow measurement
          periods, including domestic, commercial and
          industrial flows, and adding to them all flows
          which might have left the sewer system in the
          same periods, such as overflows, bypasses,
          emergency pumpings, etc.

     (2)  Calculate the sum of all total inflows and the
          sum of rainfalls which occurred during all inflow
          measurement periods.

     (3)  Calculate the total yearly inflow by multiplying
          the sum of all total inflows derived above by
          the average yearly rainfall in the study area
          and then dividing it by the sum of rainfalls
          which occurred during all inflow measurement
          periods.

     (4)  If flow measurements were conducted in more than
          one station, the total yearly inflow in each
          subsystem should be determined and added
          together to obtain the total yearly infiltra-
          tion for the entire system.

3.3.3.d  Determination of Total Yearly Infiltration/Inflow

The total yearly infiltration/inflow is the sum of the
total yearly infiltration and total yearly inflow determined
in the previous two subsections.
                            3-70

-------
3.3.3.e  Determination of Peak Infiltration

The peak Infiltration can be approximated as the infiltra-
tion measured during the highest groundwater period of a
year, with proper adjustments for wastewater flows entering
the sewer system and overflows, bypasses, etc.  leaving the
system during the flow measurement period.

3*3«3.f  Determination of Peak Inflow

The peak inflow can be assumed to be the maximum instantaneous
inflow recorded during flow measurement periods.  Adjust-
ments should also be made for all wastewater flows entering
the sewer system and overflows, bypasses, emergency pumpings,
etc., leaving the system during the flow measurement period.

3«3«3.g  Determination of Peak Infiltration/Inflow

The peak infiltration/inflow can be approximated as the
sum of peak infiltration and peak inflow determined in
the previous two subsections.

3.3.4  Adjustment for Peak Inflow

The peak inflow determined by the above procedures should be
adjusted for the desired design period or design condition.
The design rainfall frequency normally used for designing storm
sewers in the area under study  should be used for such adjust-
ment.  The ratio of the design and observed rainfall intensities
is used to adjust the peak inflow.

3.n  COST-EFFECTIVENESS ANALYSIS

3.^.1  Introduction
For the purpose of determining whether the infiltration/inflow
in a sewer system is possibly excessive or nonexcessive,  a
cost-effectiveness analysis may be conducted.  Infiltration/
inflow is defined as being possibly excessive if the total
costs for the correction of infiltration/inflow conditions
are less than the total costs for transportation and treat-
ment of these flows.  The cost-effectiveness analysis,  however,
is not the only method which may be used; other methods may
also serve the same purpose (Section 3-5) •

The basic information which is needed for the cost-effective-
ness analysis includes:

      •  Average and peak wastewater flows (including
        domestic, commercial and industrial flows)
        for the design year of treatment facilities;
                            3-71

-------
      •  Peak and total yearly Infiltration and
         inflow in the entire sewer system and/or
         in the subsystems;

      •  General physical conditions of sewer
         system; and

      •  Capacities of existing sewers, pumping
         stations and treatment facilities.

The design wastewater flows should be developed on the basis
of population and water consumption projections as well as
infiltration allowances for new sewers, as ordinarily practiced
in the planning of treatment facilities.  In addition, the
bypasses and overflows in the sewer system should also be
quantitatively determined.

The peak and total yearly infiltration and inflow may be
determined by one of the methods presented in Section 3.3.

The physical conditions of the sewer system can be in-
vestigated following the procedures discussed in Section
3.2.7-

Information about the capacities of the existing sewers,
pumping stations and treatment facilities is normally avail-
able from other phases of study in facilities planning.

Once the above information has been gathered, the costs
for transportation and treatment of wastewater (including
infiltration/inflow)  and for correcting the infiltration/
inflow conditions can be estimated.  This is followed by an
analysis of the cost  data to determine the existence or
nonexistence of excessive infiltration/inflow.  Detailed pro-
cedures for cost estimations and analysis are presented in the
following subsections.

The cost-effectiveness analysis should be conducted in accordance
with the "Cost-Effectiveness Analysis Guidelines" published
in the Federal Register 40 CPR 35.  [6]

In the following discussions,  the infiltration and Inflow
are considered together for cost-effectiveness analysis;
but,  in some cases,  engineers  may find it more convenient
to conduct  separate  analyses for infiltration and inflow,
following the same procedures.

3.11.2  Cost Estimation
3. 4. 2. a  Introduction

For cost-effectiveness analysis, two types of costs are
developed:

                            3-72

-------
      • Costs for correction of infiltration/
        inflow conditions; and

      • Costs for transportation and treatment of
        vrastewater (including infiltration/
        inflow).

For the convenience of cost comparison, all costs should be
converted to their present worth or average annual equivalent
values.  The facility planning period and the most current
interest rate (currently 6 1/8%') should be used for the con-
version.  (The interest rate is published in the Federal
Register annually by the Water Resources Council).

3.4.2.b  Sources  of Cost Information

Cost information for the correction of infiltration/inflow
conditions usually can be obtained from sewer inspection
and rehabilitation companies.  (Some cost data are presented
in Chapter 6.)

Cost information for the construction of sewers and sewage
treatment facilities can be obtained from contractors, equip-
ment manufacturers, as-bid construction estimates and
various cost estimation publications.

Operation and maintenance costs can be determined by
estimating the operation and maintenance needs in each type
and size of treatment facility or sewer system and their
associated costs.

3.4.2.C  Cost Estimation for Correction of Infiltration/Inflow
         Conditions

3.fr.2.e (1)  Introduction - For the correction of infiltration/
inflow conditions, two major tasks have to be conducted:

      • Sewer System Evaluation Survey

      • Sewer System Rehabilitation

The costs required for conducting both tasks should be estimated

3.4.2.C (2)  Costs for Sewer System Evaluation Survey - The
Sewer System Evaluation Survey is needed to locate sources
of infiltration/inflow, quantify the flows from each source
and determine the most cost-effective way of correcting the
infiltration/inflow conditions.  The Evaluation Survey can
be accomplished through the following functions:

      • Physical  survey,

      • Rainfall simulation,
                            3-73

-------
     •  Preparatory cleaning,

     •  Internal inspection, and

     •  Preparation of report.

(Details of these functions are discussed in Chapter 4.)

Not all of these functions, nor all of the tasks within each
function, need to be included in each Evaluation Survey.   Only
those functions judged to be necessary should be included in
the cost estimates.

Before the costs can be derived, the scope of work must be
first estimated.  Data collected during the study can be
used to estimate the amount of  work needed.  The following
are the suggested procedures:

     (a)  Determine the number  of subsystems to  b^jlncluded.

          If the cost-effectiveness analysis is  to be conducted
          using Methods 1 and 2 in Section 3.4,3, the entire
          sewer system is considered as a single study unit.

          If the analysis is to be conducted using Method 3,
          the system should be  divided into several subsystems
          and the infiltration/inflow condition  in each sub-
          system studied individually.

          The subsystems to be  included in the cost-effectiveness
          analysis are those which are suspected of having
          serious infiltration/inflow problems.   One of the
          methods which can be  used to single out these areas
          is to determine the infiltration and inflow (through
          either direct flow measurements or analysis of
          wastewater flow data; see Section 3.3) in each
          designated subsystem, and compare the  flow rates
          with some reasonable  criteria.

          •  To determine whether there is an Infiltration
             problem in a subsystem,  the  infiltration rate,
             in gallons per day per inch  diameter per
             mile pipe, can be  compared with the infiltration
             specification allowance  for  the pipe when in-
             stalled.   If the former  is greater  than the  latter,
             it can be concluded that there is a possible infil-
             tration problem in the subsystem and the subsystem
             may be included in the cost-effectiveness analysis
             insofar as infiltration  is concerned.   Some
             Regulatory Agencies utilize  a rule  of thumb
             indicating infiltration  rates of 1,000 gallons
             per day per inch diameter per mile  of pipe or
             le-ss as nonexcessive.


                            3-74

-------
     •   To determine  whether  there  is  an' inflow problem
        in a  subsystem,  while there is no criterion as
        in the infiltration case, the  flow rates  can
        still be used to formulate  a judgment.  Thus,
        for example,  if  the quantity of inflow is very
        small, say a  few thousand gallons per day, there
        is probably no Inflow problem  in the subsystem
        at all.   The  apparent value of inflow may be
        caused by the rainwater  entering the sewers through
        infiltration  sources, such  as  pipe cracks, etc.,
        due to the increase in groundwater level  during
        the rain period, or it may  be  simply caused by
        the flow measurement  instrument limitations or
        calculation omissions/or assumptions.

        If, after a careful analysis,  one is confident
        that  there is no inflow  problem in a subsystem,
        the subsystem should  be  excluded from the
        cost-effectiveness  analysis as far as inflow
        is concerned.

     All subsystems found to  have either infiltration
     or inflow problems, or both, should be included
     in the analysis. For  subsystems  with only infil-
     tration  problems, only the  costs  for correcting
     infiltration conditions  should be included in the
     cost-effectiveness  analysis.   Similarly, for sub-
     systems  with only inflow problems, only the  costs
     for correcting inflow  conditions  should be in-
     cluded.   When both  infiltration and inflow are
     problems, the costs for  correcting both conditions
     should be included.

     In the subsequent estimation procedures, each
     subsystem selected  for analysis should be con-
     sidered  as  a separate  study unit.

(b)   Estimate the amount of work required for Physical
     Survey.

     The following tasks may  have to be conducted in
     Physical Survey:

     •  Aboveground inspection,

     •  Plow  monitoring, and

     •  Manhole and sewer inspection.
                       3-75

-------
     A plan of action for performing these tasks should
     be first prepared.  The manpower and equipment
     requirements can then be estimated.

     All manholes in a system or subsystem may not need
     to be entered, as the flow monitoring program may
     eliminate some subareas from further investigation.
     The total number of manholes that need to be inspected
     should be properly estimated.  Results from the study
     of the physical condition of the sewer system (Section
     3.2.7) can be especially helpful for such estimation.
     After a number of randomly selected manholes and
     sewer lines have been inspected, the general condition
     of the sewer system could be estimated by proportional
     projection.

(c)  Estimate the amount of work required for rainfall
     simulation.

     Both infiltration and Inflow sources can be located
     by rainfall simulation.   The simulation can be
     accomplished by one or a combination of the follow-
     ing techniques:

     •  Smoke testing,

     •  Dyed water testing,  and

     •  Water flooding test.

     The lengths of pipes and trenches,  total number of
     houses and other possible inflow sources in a system
     or subsystem which need  to be investigated by each
     rainfall simulation technique should be estimated.

     Results from interviews  (Section 3.2.1),
     map study (Section 3.2.2.b), study  of physical
     condition and other information obtained during
     the study can all be utilized to make the estimate.

(d)  Estimate the length of  sewer pipes  which need to be
     cleaned and internally  inspected.

     Results from the study  of the physical condition of
     the sewer system (Section 3.2.7) and the exist-
     ing sewer system maintenance records should have
     provided some information for such  estimation.

     Not all the sewers  in a  system or subsystem may need
     to be cleaned or inspected,  or both.
                      3-76

-------
     (e)  Estimate the manhours required for the preparation
          of an Evaluation Survey Report.

          This can tie done based on experience obtained from
          previous jobs of a similar nature.  The manhour
          requirement would depend on the  size of the system
          and the magnitude of the infiltration/inflow pro-
          blem.

After the scope of work has been established, the unit cost
for conducting each task can be obtained from proper sources
(Section 3.^.2.b), and the total costs can be derived.  (See
Table 3-5-)

3.4.2.C (3)  Costs for Sewer System Rehabilitation - The
sewer system rehabilitation is needed to remove the infil-
tration/inflow sources from the sewer system.  The work
involves the repair and/or replacement of  sewers and man-
holes and the disconnection or plugging of inflow sources.
(Details of the rehabilitation techniques  are presented in
Chapter 5•)

Again, for cost estimation, the required rehabilitation work
should be first estimated.  All data obtained during the study
should be synthesized and analyzed to provide a basis for such
estimation.  (See Table 3-6.)

3.*4.2.d  Cost Estimation for Transportation and Treatment of
         Wastewa_t_er

3.4.2.d (1)  General Considerations - Cost estimates for
transportation and treatment should be based on some preliminary
designs.  For all designs, only the most cost-effective and
technically and environmentally feasible alternatives should
be used.  In addition, the following items should be considered:

     (a)  Bypasses and overflows;  In separated sanitary
          sewer systems, bypass and overflow may or may not be
          allowed depending on the Reliability Class of the
          facility and the conditions stated in the NPDES permit.
          All such flows in the sewer system should be con-
          sidered and included in the derivation of the total
          design flows.

          In combined sewer systems, the requirements for
          the control or treatment of bypass or overflow
          are stated in the NPDES permit.   If the permit
          does not require control or treatment of bypasses
          or overflows, the bypasses or overflows attributable
          to the combined sewer inflow should not be included
          in the total design flows.  On the other hand,
          if the permit requires control or treatment of
          combined sewer bypasses or overflows, these flows
          should be included in the total design flows.

                            3-77

-------
                                 TABLE  3-5
                  WORK SHEET  FOR QUANTITY TAKE-OFF AND
            COST ESTIMATION - SEWER SYSTEM EVALUATION SURVEY
Subsystem No.
Page
Function
1. PHYSICAL SURVEY
Above Ground Inspection
Flow Monitoring
Manhole & Sewer Inspection
Subtotal
2. RAINFALL SIMULATION
Smoke Testing
Dyed Water Testing
Water Flooding Test
Subtotal
3. PHYSICAL SURVEY REPORT
4. PREPARATORY CLEANING
6-inch pipe
8-inch pipe
10— inch pipe
12-inch pipe
15-inch pipe
18-inch pipe
21-inch pipe
24-inch pipe
27-inch pipe
30— inch pipe
36-inch pipe & up
Subtotal
5. INTERNAL INSPECTION
6-inch pipe
8-inch pipe
10-inch pipe
12-inch pipe
15-inch pipe
18-inch pipe
21-inch pipe
24-inch pipe
27-inch j>ipe
30-inch pipe
36-inch pipe & up
Subtotal
6. ENGINEERING SERVICE &
REPORT
Estimated Quantity
Quantity


































Unit
Manhour
Manhour
ft (m)

ft (m)
ft (m)
ft (m)

Manhour
ft (m)
ft- (m)
ft (m)
ft (m)
ft (m)
ft (m)
ft (m)
ft (m)
ft (m)
ft fm)
ft (m)

ft (m)
ft Cm)
ft (m)
ft (m)
ft (m)
ft (m)
ft Cm)
ft (m)
ft (m)
ft (m)
ft (m)

Manhour
Estimated Cost
Unit Cost,
$/Unit


































Total Costs,
$






































TOTAL EVALUATION SURVEY COST
                                   3-78

-------
                               TABLE 3-6
                   WORK  SHEET  FOR QUANTITY TAKE-OFF AND
             COST ESTIMATION - SEWER SYSTEM REHABILITATION
Subsystem No.
Page_
Function
I. CORRECTION OF INFILTRATION
CONDITIONS
Sewer Replacement
6-inch pipe
8-inch pipe
10-inch pipe
12- inch pipe
15-inch pipe
16-inch pipe
21-inch pipe
24- inch pipe
27-inch pipe
30-inch pipe
36-inch pipe
48-inch pipe & up
Subtotal
Pipe Lining
6-inch pipe
8-inch pipe
10- inch pipe
12-inch pipe
15-inch pipe
18-inch pipe
21-inch pipe
24-inch pipe
27-inch pipe
30-inch pipe
36- inch pipe
48-inch pipe & up
Subtotal
Chemical Grouting
6-inch pipe
8-inch pipe
10-inch pipe
12-inch pipe
15-inch pipe
18- inch pipe
21-inch pipe
24-inch pipe
27-inch pipe
30- inch pipe
36-inch pipe
48-inch pipe & up
Estimated Quantity
Quantity










































Unit


ft (m)
ft (m)
ft (m)
ft (m)
ft (m)
ft cm)
ft (m)
ft (m;
ft (m)
ft (m;
ft (m)
ft (m)


ft (m)
ft (m)
ft (m)
ft (m)
ft (m)
ft (m)
ft (m)
ft (m)
ft (m)
ft (m)
ft (m)
ft u;














Estimated Cost
Unit Cost,
$/Unit










































Subtotal
Total Cost
$













































                                   3-79

-------
                                 TABLE 3-6   (Continued)
                  WORK SHEET FOR QUANTITY TAKE-OFF AND
            COST ESTIMATION - SEWER SYSTEM REHABILITATION
Subsystem No.
Page_




Function
Manhole Wet Well
Replacement
Manhole Wet Well
Repair
Faculty Taps Repair
House Service Pipe
Replacement
House Service Pipe
Repair
Total Cost for Infiltration
Correction
II. CORRECTION OF INFLOW
CONDITIONS
Low-lying Manhole Raising
Manhole Cover Replacement
Cross Connection Plugging
Roof Leader Drain
Di s conne c t ion
Foundation Drain
Disconnection
Cellar Drain
Disconnection
Yard Drain Disconnection
Area Drain Disconnection
Cooling Water Discharge
Disconnection
Drains from Springs and/
or Swampv Areas Plugging
Total Cost for Inflow
Corrections
III. ENGINEERING SERVICES
IV. LEGAL FISCAL AND
ADMINISTRATIVE SERVICES
V. CONTINGENCY
VI. INTEREST DURING
CONSTRUCTION
VII. SALVAGE VALUE
Estimated Quantity
Quantity

























Unit
each
each
each
each
each

each
each
each

each

each

each
each
each
each
each

Lump Sum
Lump Sum
Lump Sum
Lump Sum
Lump Sum
TOTAL REHABILITATION COST
Estimated Cost
Unit Cost,
$/Unit


























Total Cost
$



























-. . ... 	 _
                                   3-80

-------
(b)   Capacities  of existing facilities:   The  capacities
     of the existing sewers,  pumping units  and  treat-
     ment  facilities should be  evaluated  to determine
     whether additional  construction of these facilities
     will  be needed in the  design  year to handle the
     anticipated wastewater flows  and the infiltration/
     inflow remaining in the  system.

     Special attention should be directed to  the areas
     where there are known  problems  such  as manhole
     overflow, pipe surcharge,  basement sewage  backup,
     etc.   Relief sewers, pipe  realignment, holding
     ponds, etc., may be considered  among other trans-
     portation and treatment  alternatives to  alleviate
     these problems.

(c)   Design Plows:   The  flows which  are needed  for the
     design of transportation and  treatment facilities
     are:

     •  Average  and peak normal wastewater  flows in
        the design year,

     •  Peak infiltration,

     •  Peak inflow, and

     •  Peak infiltration/inflow.

     The sum of  the peak infiltration, which  normally
     sustains for a period  of days,  and the average
     normal wastewater flow is  used  as the  design
     average flow,  and,  the sum of peak infiltration/
     inflow and  peak normal wastewater flow can be used
     as the design peak  flow for the sizing of  sewers,
     pumping and treatment  facilities.  Due to  the
     instantaneous nature of peak  inflow, in  many
     cases, it may be more  economical to  build  a flow
     equalization basin  or  basins  than to design large
     transportation and  treatment  facilities.

     The estimation of operation and maintenance costs
     for the transportation and treatment facilities
     should be based on  average;•rather than  peak,
     flows.  Thus, the total yearly  infiltration and
     inflow, along with  the average  wastewater  flows
     from domestic, commercial  and industrial sources,
     should be used for  such estimation.
                       3-81

-------
      (d)   Pollutant  loadings:  The BOD and suspended solids
           loadings and  other pollutants in the infiltration
           and  the inflow are usually low.  Their impacts
           on the secondary treatment processes and the
           sludge handling processes may not be significant.
           However, direct inflows entering manholes from
           perforated manhole covers and defective manhole
           structures may contain high pollutant loadings,
           characteristic of those in urban runoffs.  The
           actual pollutant loadings in the infiltration and
           the inflow can be determined only by field measure-
          ments.  Measuring and analyzing the pollutant
           loadings as well as flows in the sewer system
           under different groundwater and weather conditions
          may also reveal the actual loadings contributed
           from the infiltration and the inflow.

          The treatment requirement for each type of
          pollutant is determined by the effluent limitations
          set in the NPDES permit(s).

3.4.2.d (2)  Cost Estimates - To develop the costs for the
transportation and  treatment facilities, the reader is
referred to the "Guidance for Preparing a Facility Plan"
published by EPA in May 1975.  £73

Generally, both capital costs and operation and maintenance
costs should be included.  The capital costs should include
the following items,  when appropriate:

     •  Estimated contract construction costs of all
        transportation and treatment facilities,

     •  Costs for engineering services,

     •  Costs for legal and administrative services,

     •  Costs of land,

     •  Startup costs,

     •  Interest during construction, and

     •  Contingency allowances.

In addition, the salvage value and revenue produced, if any,
should also be included.
                           3-82

-------
3.^.3  Methods of Analysis

The cost-effectiveness analysis can be conducted using one
of the following methods.

3.4.3.a  Method 1

If, after proper study, the amount of infiltration/inflow
removable by corrective action and the required evaluation
and rehabilitation work can be determined,  a simple cost
comparison between the cost required to correct the infiltration/
inflow conditions and that required to transport and treat  the
remaining flow in the system is sufficient  to determine whether
the infiltration/inflow in the system is possibly excessive.
This method normally applies to very small  sewer systems  or
subsystems where estimations of flow and correction work  can
be made with confidence.

3.4.3.b  Method 2

The second method consists of estimating the costs required
to remove different percentages of infiltration/inflow from
the system and those required to transport  and treat the
remaining flows.  From these costs', two cost curves are plotted,
and'a total cost curve can be generated by  adding the costs on
the two plotted curves.  (See Figures 3-9 and 3-10.)  Examine
the total cost curve to locate a minimum cost point.  If  this
cost is less than the total cost corresponding to 0% infiltration/
inflow reduction, it can be concluded that  possibly excessive
infiltration/inflow exists in the system, and the optimum
percentage of infiltration/inflow which should be removed is
the value corresponding to the minimum total cost point.   (Figure
3-9.)  From this, the infiltration/inflow which should be in-
cluded in the design of treatment facilities can also be  deter-
mined.

Conversely, if the total cost corresponding to 0$ infiltration/
Inflow reduction is the minimum cost point  on the curve,  it
can be concluded that the infiltration/inflow is not excessive.
(Figure 3-10.)  All infiltration/inflow should be included  in
facility design.

3.4.3.Q  Method 3

The third method is more complex.  It involves the division
of a system into several subsystems.  After proper study, all
subsystems suspected of having infiltration/inflow problems
are selected for the cost-effectiveness analysis.  For each
selected subsystem, the following are determined:
                            3-83

-------
o
$
v. •*-
S'S
                                              M/n/mum
                                              Total Cost
                                              Point
o
                         Total Cost Curve
Transportation
8 Treatment
Cost Curve
                           Correction
                           Cost Curve
                        /
                       r
                                              Optimum
                                              I/I to be
                                                        too
                   %  Infiltration/Inflow Reduction
 Figure 3-9     Cost-Effectiveness Ana lysis-Possibly Excessive
                Infiltration/Inflow   (Method 2)
                      3-84

-------
                               Total  Cost  Curve
             Minimum Total
             Cost Point
Transportation
81 Treatment
Cost Curve
                     •Correction Cost
                         Curve
                    % Infiltration/Inflow Reduction

Figure 3-/0   Cost-Effectiveness Analysis-Nonexcessive
              Infiltration/Inflow    (Method 2)
                         3-85

-------
     (1)  Infiltration/inflow;

     (2)  Amount of infiltration/Inflow removable  by
          corrective action;

     (3)  Corrective cost;  and

     (4)  Transportation and treatment  cost.

The procedure for the analysis is  shown below.   A  numerical
example is contained in Tables 3-7 and  3-8  and  Figure  3-13.

     (a)  List,  in a table,  the titles  of all subsystems
          and the total peak infiltration/inflow removable
          and total cost required  for the correction of
          infiltration/inflow conditions (the correction  cost)
          for each subsystem.

     (b)  For each subsystem,  calculate the correction cost
          required to remove a unit quantity  (say,  1,000
          gallons/day)  of infiltration/inflow by dividing
          the total correction cost by  the  total infiltration/
          inflow.

     (c)  Assign a priority  value  to each subsystem accord-
          ing to the increasing unit correction costs.

     (d)  In another table,  rearrange the subsystems
          according to  the ascending priority values assigned
          in Step  c.   List the titles of the subsystems
          and the  peak  infiltration/inflow  removable and
          correction cost for  each subsystem.   Also list,
          corresponding to each subsystem,  the  total transporta-
          tion and treatment  cost  which would be needed if
          the peak infiltration/inflow  in the subsystem and
          in all subsystems  listed prior to the subsystem
          are removed from the total flow in the entire system
          (including both normal wastewater flow and peak
          infiltration/inflow).

     (e)  Determine the accumulative peak infiltration/inflow
          removable,  the peak  infiltration/inflow remaining and
          the accumulative correction costs .

     (f)  Calculate,  corresponding to each  subsystem,  the
          total  flow which would remain in  the  entire  sewer
          system if the peak  infiltration/inflow in the
          subsystem and in all subsystems listed prior to
          the subsystem were  removed by corrective  measures.
                           3-86

-------
     (g)  Determine the sum of the accumulative correction
          cost and the total transportation and treatment
          costs, corresponding to each subsystem,  to derive
          the total cost.

     (h)  Plot the total cost, corresponding to each sub-
          system, against  the total flow remaining.   The
          total cost for transporting and treating the
          total flow without infiltration/inflow removal
          should also be included.  Draw a curve passing all
          the data points.  (Figures 3-11 and 3-12.)

     (i)  Locate on the cost curve a point corresponding to
          the minimum total cost.  If the cost  corresponding
          to this point is less than the cost required to
          transport and treat the total flow without infil-
          tration/inflow removal, it can be concluded that
          possibly excessive infiltration/inflow exists in
          the sewer system (Figure 3-11).  The  flow corres-
          ponding to the minimum cost point is  the flow which
          would remain in the system after an optimal amount
          of infiltration/inflow is removed from the system.
          Refer to the table discussed in Step  d;  all sub-
          systems with total flow remaining greater than the
          flow corresponding to the minimum cost point should
          be considered for Sewer System Evaluation Survey
          and Rehabilitation to correct the infiltration/
          inflow conditions.

          If all costs on the cost curve are found to be
          greater than the cost required to transport and
          treat the total flow without infiltration/inflow
          removal, it can be concluded that the infiltration/
          inflow in the system is nonexcessive  (Figure 3-12).

3.5  ESTABLISHMENT OF POSSIBLY EXCESSIVE OR NONEXCESSIVE
     INFILTRATION/INFLOW

To determine whether infiltration/inflow is nonexcessive or
possibly excessive in a sewer system, a cost-effectiveness
analysis is usually conducted (Section 3.H).  However,
other methods may also be used, for example:

Example:  If the sewers in a system were installed according
to some specifications which limit the maximum infiltration
rate to certain gallons per day per inch diameter  per mile
of sewer and the actual infiltration/inflow rate in the
system is found to be less than that limit, then it can be
concluded that the infiltration/inflow in the system is
nonexcessive.
                            3-8?

-------
I
  0)
                                        TOTAL COST TO
                                        TRANSPORT AND
                                        TREAT ALL
                                        INFILTRATION/INFLOW
                                        AND  NORMAL WASTE
                                        WATER FLOW     _
TOTAL COST CURVE
                V MINI MUM TOTAL
                \ PROJECT COST
                                              TRANSPORTATION &
                                              TREATMENT  COST
                                              CURVE
                                    CORRECTION
                                    COST CURVE
                                     TOTAL FLOW INCLUDING
                                     ALL INFILTRATION/
                                      INFLOW
             TOTAL  FLOW EXCLUDING
             ALL INFILTRATION/INFLOW

                   j  r~ OPTIMAL DESIGN FLOW
                             Total  Flow
    Figure 3-11  Cost -Effectiveness Analysis - Possibly
                  Excessive Infiltration/Inflow  (Method 3)

-------

 &
 2
I
 O
•5 -a
SS
  Uj
                              TOTAL COST TO TRANSPORT
                              AND TREAT ALL INFILTRATION/
                              INFLOW AND NORMAL WASTEWATER
                              FLOWS = MINIMUM TOTAL
                              PROJECT COST 	
                                    TOTAL COST CURVE
CORRECTION COST CURVE
                                     TRANSPORTATION 4
                                     TREATMENT COST CURVE
                    TOTAL FLOW
                    INCLUDING
                   ALL  INFILTRATION/
                    INFLOW = OPTIMAL
                   DESIGN FLOW
             TOTAL FLOW EXCLUDING ALL
             INFILTRATION/INFLOW
                                 Total  Flow

    Figure 3-12 Cost-Effectiveness Analysis-Nonexcessive
                  Infiltration/Inflow   (Method 3)
                                   3-89

-------
                                  TABLE 3-7

                       DETERMINATION OF PRIORITY FOR
                       EVALUATION SURVEY - AN EXAMPLE
                                                                      Priority
                       Total Peak                                     for
           Total Peak  I/I Removable*, Correction  Unit Correction    Evaluation
Subsystem  I/1, mgd        mgd	  Cost. $     Cost, $/lfOOO gpd  Survey
I
II
III
IV
V
VI
VII
VIII
0.88
0.44
0.50
0.76
0.90
1.40
0.64
0.36
0.44
0.22
0.25
0.38
0.45
0.70
0.32
0.18
20,000
24,000
180,000
70,000
105,000
152, ,000
49,000
18,000
45
109
720
184
233
217
153
100
1
3
8
5
7
6
4
2
             5.88         2.94          618,000
*For the purpose of this example it is assumed that 50% of the I/I can be
 removed from each subsystem.
                                    3-90

-------
                                                   TABLE 3-8

                                      DETERMINATION OF COSTS - AN EXAMPLE
 Subsystem
Total
Peak I/I
Removable,
mgd
Accumulat ive
Total Peak
I/ I Removable,
mgd
Total
Peak I/I i
Remaining ,
mgd
Total
Flow _
Remaining ,
mgd

Correction
Cost, $

Accumulative
Correction
Cost, $

Transportation
& Treatment
Cost,3 $

Total
Cost,

$





UJ
l
VD
I-1
I
VIII
II
VII
IV
VI
V
III
0.44
0.18
0.22
0.32
0.38
0.70
0.45
0.25
0.44
0.62
0.84
1.16
1.54
2.24
2.69
2.94
                                          5.88
8.88
5,030,000
5,030,000
5.44
5.26
5.04
4.72
4.34
3.64
3.19
2.94
8.44
8.26
8.04
7.72
7.34
6.64
6.19
5.94
20,000
18,000
24,000
49,000
70,000
152,000
105,000
180,000
20,000
38,000
62,000
111,000
181,000
333,000
438,000
618,000
4,961,000
4,940,000
4,900,000
4,860,000
4,830,000
4,700,000
4,630,000
4,600,000
4,981,000
4,978,000
4,962,000
4,971,000
5,011,000
5,033,000
5,068,000
5,218,000
"'"Total peak  I/1  in  system  is  5.88 mgd.

r\
 Average wastewater production  (3.0 mgd) plus total peak I/I remaining.
 Present worth of  all costs.

-------
S2
o
        5.94
                                        MINIMUM COST POINT

                             TOTAL COST CURVE
                  TRANSPORTATION &
                  TREATMENT COST CURVE
                       CORRECTION
                       COST CURVE
)PTIMAL
DESIGN FLOW
     mgd
          8.88
                                       Flow,  mgd
                 Figure 3-/3   Deferm/nof ion of Opt//no/
                                Design Flow -An Example
                                      3-92

-------
If the infiltration rate alone is found to be less than that
limit, then it can be concluded that the infiltration in the
system is nonexcessive.  To determine whether-inflow is also
nonexcessive, other methods, such as cost-effectiveness
analysis, may still have to be used.

If the infiltration rate in any subsystem is found to be
less than that limit, it can be concluded that the infiltra-
tion in that particular subsystem is nonexcessive.  All sub-
systems which show nonexcessive infiltration should be
eliminated from further infiltration study.   If eventually
a cost-effectiveness analysis is to be conducted,  the
survey and rehabilitation costs for the sewers in  such
subsystems should not be included except for those costs
related to inflow study.

The rationale behind the above determinations is that if
the sewers were installed according to a certain specifica-
tion, the material and workmanship used for the construction
were designed to meet that specification and one should not
expect to obtain a sewer better than that.  If more is
expected, the entire system may have to be rehabilitated.
There are instances, however, where sewers were installed with
opened joints to serve as area drains; these sewers could be
rehabilitated to attain a tighter sewer system than when
originally installed.

3.6  SEWER SYSTEM EVALUATION SURVEY PROGRAM RECOMMENDATION

Having established that infiltration/inflow is possibly excessive in
a sewer system, a recommended program that will culminate in
the solution of the problem should be presented.  For conduct-
ing a systematic examination of the sewer system to determine
the specific location, flow rate and rehabilitation costs of
the infiltration/inflow problem, the following five phases
of work are usually recommended:

     •  Physical survey

     •  Rainfall simulation

     •  Preparatory cleaning

     •  Internal Inspection

     •  Preparation of report
                            3-93

-------
 Because  of  the  different  nature  of  the problems  in the sewer
 systems,  the  required work may vary among projects.  The sequence
 of carrying out these five phases of work may also vary among
 projects.   All  five phases of work  need not be included in the
 program  if  not  necessary.  The purpose of the Evaluation Survey
 is to  continually redefine the problem areas of  the sewer
 systems.  For each phase  of work recommended, the following
 details  should  usually be included:

     •  The specific areas to be studied;

     • The functions to be performed and their
        purposes;

     • The recommended method or methods for perform-
         ing each function;

     • The manpower, materials and  equipment and the
        time  duration required to perform each
        function; and

     •  The costs required to complete each phase of
        work.

Finally, a  project schedule should be set up for the performance
of all the  recommended work within the allowable time limit.

3.6.1  Program  Recommendation

An outline  of all the possible functions which may be included
in each phase of the Sewer System Evaluation Survey is presented
in the following subsections. These functions should be evaluated
with discretion.  Only those functions found necessary should
be included in  the recommended evaluation survey program.
The method(s)  to be recommended for performing each of the
required functions- should be determined by the conditions
of each individual system. (See Chapter 4 for more details,)

3.6.1.a  Physical Survey

The purpose of the physical survey is to determine the flow
characteristics, groundwater levels, physical conditions  of
the sewer system and the possible infiltration and inflow
sources,  and to reduce the study  areas for cleaning and internal
inspection.   The functions that may  be included in the physical
survey  are:

     •   Flow monitoring in key manholes to isolate
        problem areas;
                            3-94

-------
     •  Groundwater monitoring at  key manholes  or
        along routes of problem sewers;

     •  Physical inspection of the manholes  and
        the sewers;

     •  Searching for possible cross-connections
        between storm sewers and sanitary sewers;

     •  Searching for low manholes;

     •  House to house search for  possible inflow
        sources such as roof leader,  cellar, yard
        and area drains, foundation drains,  sump
        pump connections, cooling  water  discharges,
        etc; and

     •  Searching for inflow sources  from springs
        and swampy areas.

The areas to be surveyed can be initially determined through a
careful study of the data collected during the  I/I Analysis.
Areas with no obvious infiltration/inflow problems should not
be recommended for survey.  If the' cost-effectiveness analysis
is conducted for each individual subsystem,  the subsystems with
nonexcessive infiltration/inflow should  also be excluded from
further investigation.

3.6.1.b  Rainfall Simulation

The rainfall simulation is used to identify  sections of sewer
lines which have infiltration/inflow conditions during periods
of surface runoff.  The following  conditions can be  identified
by rainfall simulation:

     •  Cross-connections between  storm  sewers  and
        sanitary sewers, or between catch basins
        and sanitary sewers;

     •  Inflow sources, such as streams, open ditches,
        ponding areas, etc., which contribute clean
        water to the sanitary sewers during dry or wet
        weather conditions;

     •  Inflow sources in residential and commercial
        areas such as roof leader, cellar, yard and
        area drains, foundation drains,  cooling water
        discharges, etc; and

     •  Low-lying manholes which receive surface
        runoffs during storm periods.
                            3-95

-------
  The  locations where rainfall simulation studies are to be
 conducted  can be preliminarily determined by reviewing the
 results  from the interviews, map analysis and field observa-
 tions.   Results from the physical survey may further help
 pinpoint these locations.

 The rainfall simulation techniques usually applied are:

      •  Smoke testing

      •  Dyed water flooding

      •  Water flooding

 3.6.1.c  Preparatory Cleaning

 The preparatory cleaning is needed to prepare the sewer lines
 for unobstructed internal inspection.  It is usually recommended
 for the  sections of the sewer lines which are to be internally
 inspected unless studies show that the lines are sufficiently
 clean for the inspection technique(s) to be recommended.
 Sewers can be cleaned by a number of methods, depending on
 the type and degree of deposition and the sizes of the pipes.
 The degree of cleaning required can be preliminarily estimated
 by reviewing the results from interviews and from observations
 in key manholes during flow measurements.  Sewers in. municipalities
 having good sewer maintenance programs usually require less
 cleaning than those in municipalities having poor maintenance
 programs.

 3.6.1.d  Internal Inspection

 The internal inspection is performed to determine the specific
 location, condition and estimated flow rate of each source of
 infiltration/inflow defined in the selected sewer sections.
 Inspection by television is usually recommendedj however,
 other available methods can also be utilized, if suitable.
 Internal inspection should be performed during periods of
maximum groundwater levels.  To simulate rainfall conditions,
storm sewer sections,  stream sections, ditch sections, and
ponding areas related  to infiltration/inflow conditions should
be flooded during the  inspection.  Alternatively, the inspection
can be conducted during heavy rainfall periods.   In some systems,
because of the area where they are located,  it is essential to
conduct internal inspection during rains.
                            3-96

-------
3.6.1.e  Preparation of Report

After the previous four phases of the Sewer System Evaluation
Survey are completed, a report should be prepared to summarize
all the findings.   The following information is usually in-
cluded in the report:

     •  A complete documentation of all the informa-
        tion gathered during the evaluation survey;

     •  A justification for each sewer section
        cleaned and internally inspected;

     •  A cost-effectiveness analysis to determine
        the sewer sections which can be cost-
        effectively rehabilitated to remove the
        infiltration/inflow;

     •  A proposed rehabilitation program to
        eliminate all defined excessive infiltra-
        tion/inflow.

3.6.2  Cost Estimates

The costs required to accomplish each phase of the work
described above should be estimated.  For cost estimation,
the functions to be performed during each phase should be
first listed.  Difficulty factors involved and manpower
and equipment required for each function can be evaluated
on the basis of available information.  The cost related to
each function should be determined.

3.6.3  Project Schedule

To accomplish all the work required  for the Sewer System
Evaluation Survey in an allotted time limit with lowest
possible  costs, a realistic project  schedule should be estab-
lished.   The time limit is determined by the overall schedule
outlined  in the facilities plans, which should meet the schedule
stated in the discharge permit issued by the regulatory agencies.
In some  instances, however, the required work may only be
realistically achievable  by a long-range program.  This type 01
situation should  be  discussed with  State and EPA Officials
and a workable solution developed.   In  order to obtain meaningful
information, the  studies  should always  be  conducted unaer
most  favorable ground  water and weather conditions.  The
sequence of  carrying out  the  different  phases  of the work
is determined by  the conditions in  the  sewer systems and
the availability  of  manpower  and equipment  for the  specific
Job.
                             3-97

-------
                          CHAPTER 4

               SEWER SYSTEM EVALUATION SURVEY
4.1  INTRODUCTION

The Sewer System Evaluation Survey is a systematic examina-
tion of the sewer system to locate all the infiltration and
inflow sources which were previously determined to be possibly
excessive, determine the flow rate from each source and
estimate the costs required for the rehabilitation of the
system.  The following tasks are usually included in the
evaluation survey:

     •  Physical Survey

     •  Rainfall Simulation

     •  Preparatory Cleaning

     •  Internal Inspection

     •  Survey Report

The tasks are not necessarily performed in the order in which
they are presented.

The physical survey is performed to isolate the problem
areas and to determine the general physical conditions of the
sewer sections selected for further study.  The rainfall
simulation is conducted to locate the rainfall associated
infiltration/inflow sources in the sewer system.  Preparatory
cleaning is needed to prepare the sewer lines for internal
inspection, which determines the infiltration/inflow sources,
the flow rate from each source and the structural defects in
the pipes.  The survey report summarizes the results obtained
during the survey and presents a cost -effectiveness analysis
which determines the portion of the infiltration/inflow
sources which can be economically corrected.

To perform all these tasks in as short a period of time as
possible, proper planning is essential.  The physical survey
is usually performed during the high groundwater period, so
is the internal inspection.  However, the physical survey is
normally performed before the internal inspection.  In order
to complete both tasks in the same high groundwater season,
the physical survey, rainfall simulation, if required, and
preparatory cleaning should be conducted as rapidly as
possible.  To shorten the total study period, the rainfall
simulation can be performed concurrently with the physical
survey, the preparatory cleaning or internal inspection.

-------
The preparatory  cleaning and internal inspection normally
demand much more time than other tasks.  However, all sewer
systems do not require internal inspection.  Before pro-
ceeding to the preparatory cleaning and internal inspection,
the results from the physical survey should be carefully
analyzed.  If the infiltration/inflow sources can be located
and quantified during the physical survey, no internal
inspection will be needed.  This may be the case if the
infiltration/inflow sources are located in the manholes or
near both ends of the sewer lines.  To minimize both the
time and the cost for the study, all efforts should be made
to eliminate as many sewer sections from internal inspection
as possible.

4.2  PHYSICAL SURVEY

4.2.1  General

The physical survey involves all the tasks which are required
to accomplish the following objectives:

     (a)  Identify the segments of the sewer system which
          may require further study;

     (b)  Determine the general physical conditions of the
          manholes and sewer lines in the selected segments
          of the sewer system; and

     •(c)  Compile the background information required for
          the planning of the subsequent studies.

The following tasks are normally included in.the physical
survey:

     (a)  Aboveground inspection,

     (b)  Plow monitoring, and

     (c)  Manhole and sewer inspection.

After the completion of a physical survey, a report may be pre-
pared.   This report is required by some states.   The report
summarizes all the data collected  during the survey and provides
Justification for:

     (a)  The sewer sections recommended for internal inspection.

     (b)  The degree of cleaning required for each sewer section
          recommended for internal inspection.

     (c)  The location and sewer sections where  rainfall simu-
          lation should be conducted.

-------
4.2.2  Aboveground Inspection

The aboveground Inspection is conducted to accomplish the
following objectives:

     (a)  Investigate  the general conditions of the study
          area, such as topography, streets, alleys, access
          to manholes, etc.;

     (b)  Locate potential problem areas, such as waterways,
          river crossings, natural ponding areas, etc.;  and

     (c)  Select the key manholes for additional flow
          measurement  and groundwater monitoring.

Conducted by a trained observer, valuable information can be
obtained which would facilitate the planning of other tasks
in the evaluation survey.

However, if sufficient information has been gathered during
the Infiltration/Inflow Analysis, this task may not be necessary.

4.2.3  Flow Monitoring

The purpose of flow monitoring is to locate and isolate the
areas where infiltration/inflow problems exist.  Generally,
portions of the system pose no problem; therefore, they will be
eliminated from further study.  This task should be accomplished
at the earliest possible stage in order to minimize the survey
costs.

In the analysis phase of the study, the flow monitoring work
has already been performed in a few selected key manholes.
All subsystems which present no infiltration/inflow problems
are eliminated from further study in the evaluation survey.
The additional flow monitoring work performed during the physical
survey is actually a continued effort to further reduce the
number of areas to be investigated.

The flow monitoring is usually conducted in a number of selected
key manholes.  The flows  should be monitored during the highest
groundwater level period.  Both dry weather high groundwater
and wet weather high  groundwater  flows should be monitored to
determine the  magnitude  of inflow as well as of  infiltra-
tion in each subsystem.   To minimize the interferences caused
by the  normal  wastewater  flows, the flow monitoring is usually
conducted during  the  early morning hours.   However, on large
systems early  morning  flows may be substantial because of
continuous  discharges  to  the  sewers and  lag time  of flow due
to the  length  of  sewers.
                              4-3

-------
 For  detailed  information regarding the procedures for select-
 Ing  key manholes,  the methods and equipment used, the
 safety measures, and other pertinent considerations, see
 Section 3-2.6.

 4.2.4  Manhole and Sewer Inspection

 4.2.4.a   General

 The  manhole and sewer inspection is a task to determine the
 actual physical condition of the sewer system.  The data
 generated from the inspection would be valuable for the identi-
 fication  of infiltration/inflow sources.  It also provides a
 factual base  for the establishment of a preparatory cleaning
 program for internal inspection and a routine sewer maintenance
 program.

 The  inspection can be started after all the problem areas have
 been isolated through a flow monitoring program.  It may also
 be conducted  concurrently with the flow monitoring program to
 accelerate the evaluation survey.

 All the manholes and sewer lines in the designated problem
 areas of the  sewer system should be included in the inspec-
 tion.  Each manhole should be entered.  The manhole and the
 sewer pipes connected to it should be inspected carefully to
 determine the physical conditions, infiltration/inflow sources,
 type and degree of deposition and other special problems and
 conditions.

 4.2.*J.b  Time for  Inspection

 The manhole and sewer inspection is usually performed during
 the high groundwater period, for, during this period, the
 groundwater-associated infiltration/Inflow sources can be
 easily detected.   The inspection can be performed during
 either dry weather high groundwater or wet weather high
 groundwater conditions.   But it is more convenient to do it
 in the dry weather as the flows in the sewers during dry
weather are lower  and the physical conditions of the manhole
and the sewers can be checked more easily.  The Inspection
 is normally conducted during the daytime, at the hours when
the wastewater flows are low, if possible.

 4.2.4.C  Preparation

Before the Inspection is started, a complete sewer map of
all the manholes and sewer lines to be Inspected should be
prepared.   The manholes  should be properly numbered for easy
 Identification.   The equipment which is needed for manhole and
sewer inspection includes:

-------
       •  Personal safety equipment

       •  Portable lamps

       •  Hand-held mirrors

       •  Ruler

       •  Thermometer

       •  Other equipment

Manhole entering imposes potential safety and health hazards.
The personal safety equipment should always be carried and
used in the field.  The safety equipment required for manhole
entering is presented in Section 3.2.6.d.  All the safety
measures discussed in that section should also be followed
closely.

The hand-held mirror and the portable lamp are used to lamp
the sewer lines for easy inspection.  The lamp should be
flameless to avoid accidental explosion of the gases in the
sewers.  The commonly used flashlights are sufficient for
such purpose.

The ruler is used to measure the dimensions and the water depths
in the sewers and manholes.  The thermometer is used to measure
the temperature of the flow in the pipe.  Equipment for the
determination of conductivity, sulfate, fluoride or other con-
stituents in sewage may also be needed in some cases.

4.2.4.d  Procedure

J|.2.4.d (1)  Manhole Inspection - The manhole inspection involves
the observation and recording of the following information in
each manhole:

     (a)  Manhole identification;

     (b)  Construction materials and conditions of cover, ring,
          corbel work, walls, steps, aprons and troughs;

     (c)  Manhole depth and opening size;

     (d)  Number and size of holes, if any, in manhole cover;

     (e)  Visible infiltration sources and estimated flow
          rates;

     (f)  Evidence of leaks and location;

-------
      (g)   Level  of  high  water  mark  in  the manhole;

      Oh)   Type and  depth of  debris;

      (i)   Groundwater  level  at  the  manhole, If monitored; and

      0j)   Special problems and  conditions, such as sources of
           inflow, overflows, bypasses, manholes located in
           natural ponding areas,  etc.

 A  typical  data sheet used to record the above information
 during manhole inspection is shown  in  Table 4-1.

 For manholes which  cannot be inspected because of, say,
 inability  to locate, inability  to open, surcharged, no steps,
 etc., the  reasons should be recorded.

 4. 2.4.d (2)  Sewer  Inspection - After  the inspection of a
 manhole is finished, the  incoming and  outgoing sewer lines
 connected  to the manhole  are inspected in turn.  The sewers
 are inspected by lamping  the line both at the manhole being
 inspected  and at the manhole down the  line.  By lamping at
 both ends  of the pipe, a  greater visibility can be achieved.
 A  mirror is used to deflect the light from the lamp to different
 parts of the pipe for  close inspection.  The  following informa-
 tion is usually recorded:

     (a)   Length, size, type and depth of pipe;

     (b)  Depth and temperature of flow;

     Oc)  Other parameters in sewage such as conductivity,
          sulfate concentration, fluoride concentration, etc.

     (d)  Root growth in pipe;

     (e)  Type and depth of deposition in pipe and recommended
          cleaning method;

     Of)  Visible infiltration/inflow sources;

     (g)  Structural condition  of pipe; and

     Oh)  Special problems and  conditions in pipe.

A sketch showing the relative locations of the manholes and
the pipelines should also be  included in the data  sheet.
Table 4-2  shows a typical data  sheet for sewer inspection.
                             4-6

-------
   TABLE 4-1  TYPICAL DATA SHEET FOR MANHOLE INSPECTION

MH#	   Location	s	  Drainage Area_
Project:

Client
                                   Project No.
Date
              Time
Weather:  No rain

A. INVENTORY
a.m.
p.m.
    Inspector
                    rain
snow
Item
Cover
Ring (frame)
Steps
Corbel Work
Walls
Aprons
Troughs
Construction
Material







Condition
Good







Pair







Poor







B. OBSERVATIONS

   1.  Diameter of manhole opening

   2.  Holes in cover    :  number
                                 in.

                                ,  size
                  in.
   3.  Visible infiltration through joints, cracks, lines, etc.,
       height above sewer invert, estimated flow rates	
   4.  Evidence of leaks in manhole, height above sewer invert
   5.  High water marks in manhole, height above sewer invert,
       possible cause 	
   6.  Manhole has
   7.

   8.
                does not have
   ground water level
gauge ground water level above sewer invert 	

Debris:  No	;   yes 	,  type	,  depth
Special problems, conditions, sources of inflow,
overflows, bypasses.
                   in,
                          4-7

-------
MH#
TABLE 4-2  TYPICAL DATA SHEET FOR SEWER INSPECTION
        LocationDrainage Area
Project :
Project
No.
Client:
Date: /
a .m
/ , Time p.m
•
Inspector
Weather:  No rain;  rain
                         snow
Pipe Data
Pipe Sizes, in.
Type of Pipe
Depth from MH
Top to Invert
Depth of Plow,
in.
Temperature of
Plow, °P
Conductivity of
Sewage, mho/cm
Sulfate
Concentration, ppm
Fluoride Concen-
tration, ppm
Root Growth in
Pipe
Type of
Deposition
Depth of
Deposition, in.
3e commended
Cleaning Method
Visible Infiltra-
tion/Inflow Sources
in Pipe
Structural Condi-
tions of Pipe
Special Problems
and Conditions
Incoming Lines
From MH # 	
Distance
ft
















From MH# 	
Distance
ft
















From MH# 	
Distance
ft
















Outgoing lines
To MH# 	
Distance















Sketch of Manholes and Sewers
                        4-8

-------
An inventory of the length, size,  type,  depth and the  general  con-
ditions of the sewer pipes would provide a basis  for the  estima-
tion of the amount of work required for  the preparatory cleaning
and internal inspection.   It also  provides a basis for sewer
rehabilitation work and routine sewer maintenance.

The depth of flow would provide a  rough  indication about  the
capacity and/or structural condition of  the sewer pipe and
indicate if infiltration/inflow is present in the sewer section.
For example, a surcharged line under normal conditions may
indicate a deficiency in pipe capacity or the existence of  some
infiltration/inflow sources along  the pipe.

The flow temperature may also be used as an indicator  for the
detection of the extraneous water  entering the sewer section
being investigated.  Thus, if the  measured flow temperature is
much higher or lower than the average sewage temperature  measured
in the upstream manholes and there is no discharge from the
service connections at the time of measurement, there  are
definitely some infiltration/inflow sources along the  sewer
pipe.  Similarly, the conductivity, the  sulfate concentration
and the fluoride concentration in  the sewage may  also  be  used
to detect the infiltration/inflow sources.

The root growth condition and the  type and depth  of deposition
in the pipe would dictate the selection  of the methods for  the
root control and for the sewer cleaning  before internal inspec-
tion.  An experienced sewer Inspector should be able to judge
the condition in the field and recommend the best cleaning  method
for each section of pipe.  (The commonly used cleaning methods
are presented in Section 4.4.)

All visible infiltration/inflow sources  should be recorded.
Each sewer line is actually inspected from two different  man-
holes.  This provides a chance to detect any infiltration/inflow
sources and/or structural defects  which  are undetectable  from
only one end of the pipe.

The structural condition of the sewer pipe should also be
recorded.  All structural defects  and other unusual conditions,
such as cave-ins, crushed pipes, cracks, signs of deterioration,
horizontal misalignments (kicked Joints), vertical misalignments
(dropped joints), sags, open Joints, protruding taps,  missing
pipes, etc., should also be recorded.

The physical survey is most effectively  conducted during
high groundwater periods, thus an additional task which
should be performed is measurement of the groundwater  depth.
(See Section 3.2.4.d for details.)
                             4-9

-------
4.2.5  Report

The main purpose of preparing a report at the end of the
physical survey is to provide a document to justify all the
subsequent work required in the evaluation survey.  This report
is required by some states.  After finishing all the tasks in
the physical survey, the general conditions in the sewer system
are clear to the investigator.  A judgment should be possible
at this stage as to what sections of sewer lines should be
further studied, which lines would need preparatory cleaning
before internal inspection, what are the justifications for the
cleaning and for the inspection, and where and how the rainfall
simulation should be conducted.

The sewer lines located in the subsystems which are found from
the flow monitoring program to have possibly excessive
infiltration/inflow are generally recommended for further
investigation.  The lines which need preparatory cleaning are
those which have deposition of any kind which may interfere with
the internal inspection.  The degree of cleaning (light clean-
ing or heavy cleaning) and the recommended cleaning equipment
can be determined on the basis of the degree and type of deposi-
tion, and the structural conditions and accessibility of the
sewers to be inspected.  The inspection method to be recommended
would depend on type of information required, pipe size and
internal conditions.

The areas where the rainfall simulation should be conducted
are those which show infiltration/inflow conditions during
rainfall periods.  The method to be recommended for the simu-
lation would depend on the type of infiltration/inflow source
expected and other conditions in the sewer system and the
study area.

4.3  RAINFALL SIMULATION

4.3.1  General

The rainfall simulation techniques are utilized to identify
sections of sewers which have infiltration/inflow conditions
during rainfall periods.  Generally these techniques are only
employed on separate sewer systems since combined systems were
designed to collect some inflow.

The infiltration/inflow sources which can be identified by
the rainfall simulation techniques Include:

     (a)  Roof leader, cellar, yard and area drains and
          foundation drains;
                            4-10

-------
     (b)  Abandoned building sewers,  faulty connections  and
          illegal connections;

     Cc)  Cross-connections between sanitary sewers  and  storm
          sewers;

     (d)  Storm sewer sections,  stream sections,  ditch sections
          and ponding areas which may cause infiltration/inflow
          in sanitary sewers; and

     (e)  Structurally damaged  sewers and manholes.

Although a convenient tool, rainfall  simulation does not have
to be performed in every sewer  system evaluation study.   A
careful study of the sewer maps  and reviews of the Infiltration/
Inflow Analysis report and the  physical survey results would
indicate whether rainfall simulation  is needed and,  if so,
where it should be applied and  what techniques should be used.
The following are the situations where rainfall simulation may
be considered:

     (a)  Storm sewer sections  which  parallel or cross sanitary
          sewer sections (including service connections) and
          have crown elevations  greater than the invert  eleva-
          tions of the sanitary  se'wers may be potential  infil-
          tration/inflow sources.  If the sanitary sewer sections
          which parallel or cross such storm sewer sections  show
          excessive infiltration/inflow and there are no other
          conceivable or detectable infiltration/inflow  sources,
          the rainfall simulation techniques may be  considered.

     (b)  Stream sections, ditch sections and ponding areas
          located near or above  sanitary sewer sections  may  also
          be potential infiltration/inflow sources.   The rainfall
          simulation techniques  may also be utilized to  identify
          such sources for sewer sections which show excessive
          infiltration/inflow if no other sources are con-
          ceivable or detectable.

     (c)  Roof leader, cellar,  yard and area drains  and
          foundation drains, abandoned building sewers,  faulty
          connections and illegal connections which are  sus-
          pected to exist but cannot  be identified by other
          means during the physical survey may be detected by
          the rainfall simulation techniques.

Besides being an identification tool, rainfall simulation can
also be utilized in conjunction with flow measurements to
quantify the infiltration/inflow from each of the identified
sources.

-------
The rainfall simulation techniques may be utilized to estimate
the quantity of infiltration/inflow that may reach the sewer
lines under unpaved areas, particularly service lines.  However,
although rainfall may be simulated in small areas, it is often
almost impossible to simulate actual wet weather conditions.
Plow measurements performed during actual wet weather conditions
usually provide data which are more meaningful than those
gathered under the simulation rainfall conditions.

Many of the tests are performed on private properties.  It  is
essential to obtain full cooperation of the property owners.
Before the tests, the owners should be notified and the nature
of the tests should be explained to them.

The rainfall simulation techniques commonly used are:

      •  Smoke testing

      •  Dyed water testing

      •  Water flooding test

In the following sections, details of these techniques are
presented.

*J .3.2  Smoke Testing

^.3.2.a  Application and Limitations

Smoke testing is an inexpensive and quick method of detecting
infiltration/inflow sources in sewer systems.  The method is
best used to detect inflow sources such as roof leader, cellar,
yard and area drains, foundation drains, abandoned building
sewers, faulty connections, Illegal connections and storm
sewer cross connections.  It can also be utilized to detect
the structural damages and leaking Joints in sewer pipes and
the overflow points in the sewer systems.

The method is only a detecting technique and cannot be used
to quantify the flows.  To accomplish the latter, one should
measure flows in the sewer sections which are found by the
smoke testing to have infiltration/inflow conditions.  The
flow measurements can be performed during the wet weather
conditions or during the simulated rainfall conditions.

If reliable information is to be derived from smoke testing,
the method should not be applied to the sewer lines which
contain water traps or sags.  Both of these two pipe conditions
may prevent the smoke from passing through and result in
false conclusions.  Similarly, the methods should not be
applied to sewer sections that are flowing full.  The method
cannot be utilized to detect the structural damages and leaking
Joints in buried sewers and service connections when the

                            4-12

-------
soils surrounding and above the  pipes  are  saturated,  frozen
or snow covered.   In each case,  the  smoke  will be trapped
and will not come out of the ground  even though  there are
cracks or leaking joints In the  pipes.   Rain  and snowy  days
are not suitable  for smoke testing.  The test should  not
be performed on windy days when  the  smoke  coming out  of the
ground may be blown away so quickly  as  to  escape visual detection,

Because of the many unknowns in  the  sewer  systems and the
uncertainties about the soil and groundwater  conditions, the
results from smoke testing should be analyzed carefully.   The
positive findings during the tests definitely indicate  the
existence of the  infiltration/inflow sources. The  negative
findings, however, may not prove that  the  problems  do not
exist.  Whenever  the results from the  smoke testing are in
doubt, the more positive detection method, i.e., the  dyed  water
testing, may be tried, or observations conducted during wet
weather.

The method normally does not cause safety  or health hazards.
It is usually performed above the ground and no  manhole enter-
ing is necessary.  However, because  of possible  confusion  re-
sulting from smoke appearing in  and  around dwellings, the  public
should be notified prior to the  test and the local  fire depart-
ment should also  be informed. A typical smoke testing, between
two manholes, usually takes about 10 to 15 minutes.  More  time
will be needed under unusual sewer and manhole conditions.

4.3.2.b  Equipment

The following equipment is usually needed  to conduct  smoke
testing:

     •  Smoke bombs

     •  Air blower

     •  Camera and film

     •  Sand bags and/or plugs

The smoke bombs are used to generate the smoke  required for
the test.  The smoke should be nontoxic, odorless  and non-
staining.  The 3-minute and 5-minute bombs are normally used
although bombs which can last longer or shorter  are also
available.  The air blower is used to  force the  smoke into
the sewer pipes.   A gasoline-driven blower is most convenient
for this purpose.  The air blower should have a  minimum capacity
of about 1500 CFM.  The camera is used to  take  the pictures
of the smoke coming out of the ground, catch basins,  pipes
and other sources during the test.  The photographs are taken
for permanent documentation of the infiltration/inflow sources.
The sand bags and/or plugs are used to block the sewer sections
to prevent the smoke from escaping through the manholes and
adjacent sewer pipes.

-------
The smoke bomb and the air blower are usually set up above-
ground near the manhole to be tested.

4.3.2.C  Procedure

The following procedures are normally followed to perform the
smoke testing:

     (1)  Preparation for the test

          (a)  Determine the sewer sections  where the smoke
               tests are to be performed.   Locate the sewer
               sections and manholes.  Check the manholes for
               accessibility and check the flow conditions in
               the sewer pipes.  Make provisions for flow by-
               passing, if necessary.

          (b)  Determine the time for the  tests.  Avoid rainy,
               snowy and windy days.   Schedule the test for
               the period when the groundwater levels are
               low and the ground is  not  snow covered.

          (c)  Notify the residents in the areas where  the
               tests are to be performed  regarding the  nature
               and time of the test.   Also notify the loca,l
               fire department.

     (2)  Test procedure

          (a)  Usually two manhole sections  are tested  simultan-
               eously.  Set up the equipment at the intermediate
               manhole of-the sewer sections to be tested.  The
               smoke is usually introduced into the sanitary sewer
               sections, even for the detection of the  cross-
               connections between storm  sewers and sanitary
               sewers.

          (b)  Partially plug the sewer lines at the far ends
               with sand bags or plugs.  The sand bags  or
               plugs are attached with ropes to facilitate
               lowering and retrieving from above the manhole.

          (c)  Ignite the smoke bomb  and  force the smoke into
               the sewer section with the  blower.  The  supply
               of smoke should be continuous until the  area
               serviced by the test sections is thoroughly
               examined and all problems  recorded.

-------
          (d)   Observe the appearance  of  the  smoke  coming out
               of the ground,  storm sewer,  catch basins,
               roof drains, abandoned  building  sewers,  etc.
               Record the  observations with the camera.  Mark
               down on the back of  the photographs, or  on a
               log sheet,  the  dates, locations  and  situations
               of the results.

fr.3.3  Dyed Water Testing

4.3.3.a  Application and Limitations

The dyed water testing is  usually used to determine whether
the storm sewer sections,  stream sections,  ditch sections
and/or ponding areas which are located near or  above  the
sanitary sewer sections are contributing  any  infiltration/
inflow to the  sanitary sewers.   The method can  also be
utilized to detect the other infiltration/inflow sources
listed in Section 4.3.1.  It can be used  to check  the results
from the smoke testing. Under unfavorable weather, ground-
water, soil, sewer structure and/or flow  conditions,  the
dyed water testing can be  utilized  to  substitute for  the  smoke
testing to obtain more reliable Information.  Quantification of
the flows is possible when the dyed water testing  method  is  used
to identify the infiltration/inflow sources.

The method, however, is usually more expensive  and time-consuming
than the smoke testing technique.   It  is  also limited to  locations
where large quantities of  water are available for  the test.   Man-
holes and storm sewers may have to  be  entered for  the test;
therefore always be safety conscious.

4.3.3.b  Equipment

The equipment needed for the dyed  water testing is limited
to that required to carry  the water to the testing site and  to
block the sewers or the study areas before the  testing.

When fire hydrants are close to the sewer sections to be  tested,
a fire hose is all that is needed to deliver  the  water  to the
testing site.  On the other hand,  when the water  source is  not
close by, water tankers will be required to deliver the water.
Sand bags or sewer pipe plugs are normally used to block the
sewer sections.

The fluorescent dyes are usually used for the test.  Each dye has
a distinct color which is readily detectable by eye.   A suit-
able dye should be safe to handle,  visible in low concentra-
tions, misclble in water,  inert to the soils and the debris
in  the sewers and biodegradable.   (Typical dyes available for
this purpose are listed in Table 3-2.)
                            1-15

-------
4.3.3.C  Procedures

Depending on the infiltration and inflow sources  to  be  identified,
the procedures for the dyed water testing differ.

4.3.3.G CD  Determination of Infiltration/Inflow Conditions
Caused by Storm Sewer Sections - The storm sewer  sections
which parallel or cross sanitary sewer sections and  have
crown elevations greater than the invert elevations  of  the
sanitary sewers can be either infiltration sources or inflow
sources. They are inflow sources if there are  cross-connections
between the storm sewer sections and sanitary  sewers.   They
are infiltration sources if the storm water can exfiltrate
from them, percolate through the soil and enter the  sanitary
sewers through pipe defects, broken pipes and/or  leaking
Joints.  The dyed water testing can be used to detect both
of these possibilities.  To differentiate between the two,
an analysis of the percolative capacity of soil is necessary
in addition to the determinations of the presence, concentration,
flow rate, and travel time of the dyed water entering the
sanitary sewers.  A careful analysis of these  factors would
also enable one to locate the sources and quantities of infiltra-
tion/inflow.  If the technique is to be used merely  to  determine
whether cross-connections are existing between the sanitary
sewers and the storm sewers or catch basins, then it is only
necessary to determine the presence and travel time  of  the
dyed water into the sanitary sewers.

The general procedures for dyed water testing  in  storm  sewer
sections are as follows:

     (a)  Plug both ends of the storm sewer section  to  be tested
          with sand bags or other materials.  Block  all the
          overflow and bypass points in the sewer section.
          Provide bypassing of flow, if necessary.

     (b)  Pill the storm sewer section with water from  fire
          hydrants or other nearby water sources.  Add  dye
          to the water.

     (c)  Monitor the downstream manhole of the sanitary  sewer
          system for evidence of dyed water.  Determine the
          time of travel and, if desired, the  concentration  of the
          dyed water.

     (d)  Measure the flows in the manhole before and during the
          dyed water testing.  As an alternative,  the flows  can
          be simultaneously measured at both the  upstream and
          downstream manholes during the test.
                            4-16

-------
     (e)  Record the location of storm and sanitary  sewer lines
          being tested, the time and duration of tests,  the
          manholes where the flows are monitored and the flow
          rates, the observed presence, concentrations and
          travel time of the dyed water into the flow monitoring
          manholes, and the soil characteristics.

4.3.3.C C2)  Determination of Infiltration/Inflow Conditions
Caused by Stream Sections 3 Ditch Sections and Ponding Areas  -
To determine whether the stream sections, ditch sections and
ponding areas located near or above sanitary sewer sections
are causing infiltration/inflow conditions in the sanitary
sewers, the procedure similar to that described in the previous
section is recommended.  In these cases, the stream sections,
ditch sections and pond areas to be tested should be plugged
or dammed and filled with dyed water to the desired levels.
The presence, concentration and/or travel time of the dyed
water into the sanitary sewers are then monitored in the
downstream manholes.  The flow rates can be monitored if
necessary.  The percolative capacity of the soil can be  deter-
mined to facilitate the estimation of the sources and quantities
of infiltration/inflow.

4.3.3.C (3)  Identification of Roof Leader, Cellar,  Yard and Area
Drains, Abandoned Building Sewers, Faulty Connections and Illegal
Connections - Most of these inflow sources are located  on
private properties.  The property owners should be notified
before the tests to identify the aforementioned inflow  sources.
To identify the above mentioned inflow sources, dyed water is
poured into the corresponding fixtures and their presence is
checked in the closest downstream manhole in the sanitary sewer
system.  The date of the test, the address where the inflow
sources are identified and the type of inflow sources should
all be recorded.
4.3.3.C ... (.4)  Identification of Structurally Damaged Manholes -
The dyed water test .can also be used to identify the structurally
damaged manholes which impose potential infiltration/inflow
problems.  This is accomplished by flooding the area close to
the suspected manholes with dyed water and observing the presence
of the dyed water at the manhole walls.

4.3.3.C (5)  Outflow Dye Test - Besides being a technique for
identifying infiltration/inflow sources, the dyed water testing
method can also be utilized to determine the location and quantity
of water escaping from a sewer system through bypasses, overflows
and cross-connections.
                            4-17

-------
To accomplish this, the downstream manhole of the sewer section
is first plugged.  The sewer section is then surcharged with
dyed water to the desired level.  Upon attaining the desired
condition, all suspected areas, such as creeks,  ditches, storm
sewers, catch basins and nearby sewer lines, are visually in-
spected for the appearance of the dyed water.  Record the
location, time and duration of test, water level, amount of
water used and location of all cross-connections or outflow
sources detected and estimate the loss of flow from each of
these outflow sources.

4.3.4  Water Flooding Test
The water flooding test is similar to the dyed water testing
method except that no dye is used.  Because of the  lack of a
visible indicator in the water flooding test,  the task of
identifying the infiltration/inflow sources becomes more tedious.
Accurate flow measurements are essential to the successful appli-
cation of this technique.  With proper flow monitoring, all the
infiltration/inflow sources which can be identified by the dyed
water testing method can also be identified by the  water flooding
test .

In addition, the following two types of water  flooding tests
can also be performed without the need of the  dyed  water:

     •  Sprinkler test

     •  Exfiltration test

4. 3. 4. a  Sprinkler Test

The sprinkler test is used to determine the quantity of infiltra-
tion being experienced in sewer lines under unpaved areas, par-
ticularly service connections, during wet weather conditions.

The rainfall is simulated by sprinkling the areas above the
sewer lines to be tested with water, using the irrigation
sprinkling pipe with spray nozzles or yard sprinkling hoses.
The rate of application of water and total water distributed
are monitored by installing rainfall gauges in the  immediate
area of the test.  Flows are periodically measured  at the
manholes both upstream and downstream of the test section.
Comparison of these flow readings would determine the quantity
of infiltration (if any) and the time required for  the infiltra-
tion to reach the sewer section.

The data to be recorded may include type, size, depth, number
of taps on and location of sewer lines tested as well as
topography, soil type, time and duration of test, rainfall gauge
readings and flow readings versus time.


                            4-18

-------
4.3.4.b  Exfiltration Test

The exfiltration test is used to check the sewer lines  and
manholes for possible leakages.   Sewer sections  and  manholes
which do not show significant exfiltration rates during this
test usually would not display high infiltration rates  during
wet weather conditions.  The results from exfiltration  tests
can also be compared with the infiltration rates determined by
the sprinkler tests in a given area.  If a definite  relationship
can be established, the exfiltration test can be used to re-
place the more costly sprinkler test in that area.

The procedures involved in the exfiltration test are as
follows:

     (1)  Isolate the manholes and sewer lines to be tested
          by plugging incoming and outgoing lines.

     (2)  Pill the manholes and sewer lines with water  and
          allow the water surface to stabilize.

     (3)  Measure the rate of recession of water in  the manhole
          and amount of water required to refill the sewer
          section.

     (4)  Record the location, length, depth, type of pipe and
          manhole construction,  and number of taps in the test
          section.  Also record the time and duration of the
          test, head established, rate of water loss and amount
          of water required to refill the test sections.

     (5)  Calculate the exfiltration rate from the test section.

4.4  PREPARATORY CLEANING

4.4.1  General

After the physical survey and the rainfall simulation,  the
general conditions of the sewer system can be determined.
Sewer sections which present obvious potential for excess
infiltration/inflow are selected for internal inspection
to pinpoint the causes, sources and magnitudes of infiltration/
inflow before being recommended for rehabilitation.   To
facilitate the internal inspection, the sewers should be
properly cleaned.

The preparatory cleaning should remove all the sludge,  mud,
sand, gravel, rocks, bricks, grease and roots from the  sewer
pipes, manholes and pumping station wet wells to be inspected.
The cleaning is normally more thorough than that done for routine
                            4-19

-------
maintenance.  The pipe walls should be clean enough for the
camera used in the inspection to discern structural defects,
misalignment and infiltration/inflow sources.  A full-diameter
tool or cleaning device is often needed to assure adequate
cleanliness and clearance.

The cleaning is usually far more time-consuming than the
actual internal inspection.  For this reason, it is not advis-
able to have a television camera on site at all times while
the cleaning crews are working.  However, for lines which
clog easily, the inspection should be done as soon as possible
after the cleaning is finished to avoid the necessity for
recleaning at a later time.

4.4.2  Equipment

A complete sewer cleaning job involves the following four
tasks:

     (a)  Dislodging the materials,

     (b)  Transporting the materials to a point of access,

     (c)  Removing the materials from the sewer system,

     (d)  Disposing of the materials.

The equipment required to accomplish these tasks can be
divided into three general categories:

     •  Cleaning equipment,

     •  Debris removal devices,

     •  Debris transporting vehicle.

*J.4. 2. a  Cleaning Equipment

The cleaning equipment is used to dislodge the materials
in the pipeline and to transport the materials to the point
of access.  Most cleaning equipment cannot be used to remove
the materials from the sewer system but some may also be
used to accomplish this task.  There are four basic types
of sewer cleaning equipment:

     •  Rodding machines,

     •  Bucket machines,

     •  High-velocity water machines,

     •  Hydraulically propelled devices.
                            4-20

-------
These types of equipment differ in their capacities  to  handle
the materials in the sewers, applicable pipe size  ranges,  man-
hole accessibility requirements and methods of operation.
(Table 4-3).

The rodding machines are most effective in dislodging roots
and blockages in sewer lines.  The bucket machines are  most
suitable for heavy cleaning which involves the removal  of
sand, gravel, rocks, bricks and roots.   The high-velocity
water machines and the hydraullcally propelled devices  can
both be used for light cleaning to remove the sludge, mud,
sand and gravel in the sewers.

4.4.2.b  Debris Removal Devices

The debris removal devices are used to  remove the  materials
from the sewers after the materials are dislodged  and
transported to the points of access (manholes) by  the clean-
ing equipment.  The commonly used debris removal devices are:

     •  Vacuum Machines

     •  Trash Pumps

The bucket machines used for the cleaning  can also be  used
to remove the debris from the sewers.

4.4.2.C  Debris Transporting Vehicle

The debris transporting vehicles, or dump trailers, are
used to transport the debris to a dump site.  The vehicles
are sometimes equipped with pumps and settling baffles  for
separating the solids from the water.

4.4.3  Selection of Cleaning Equipment

To select proper types of cleaning equipment for the pre-
paratory cleaning of a sewer system, many factors have  to
be considered, including:

     •  Access to manholes,

     •  Condition of manholes,

     •  Size of pipe,

     •  Depth of deposition,

     •  Type of solid materials to be removed,

     •  Degree of root intrusion,
                            4-21

-------
                                              TABLE 4-3

                            CHARACTERISTICS OP SEWER CLEANING EQUIPMENT [9]
  Equipment
Applicable
Pipe Size
Materials to
be Removed
Advantage
Limitation
  Rodding Machines  6"-15"
.t-
i
ru
IV)
  Bucket Machines   8"-36"
                Best for dislodging
                roots and blockages
                        1,
                        2,
                        3
                                    Also for dislodging
                                    and transporting
                                    sludge, mud and grease,
                                    using special tools
                                    and flushing water
    May reach 1,000 ft
    Easy to stop
    Can be used for
    threading sewer
1. Best for dislodging,  1
   transporting and
   removing sand, gravel,
   rocks, bricks and
   roots                2.

2. Also for dislodging
   and transporting     3-
   mud and grease
                                        , Can remove large
                                         amounts of heavy
                                         solids and roots

                                        Effective in large
                                        diameter pipes

                                        Can remove materials
                                        from sewer system

                                        Winch machine can be
                                        used with a variety
                                        of tools
1. Require direct
   access to down-
   stream manhole

2. Require large
   quantity of water
   for flushing

3. Poor in trans-
   porting heavy
   solids

4. Do not remove
   materials from
   sewer.

1. Require complete
   access to both
   manholes

2. Require threading
   of sewer line

3. Time-consuming
   for light clean-
   ing

4. Heavy tools may
   damage pipe

5. Cannot be used in
   structurally
   damaged pipe,
   offset joints,
   curved pipe and
   pipes with intrud-
   ing service con-
   nections

-------
                                   TABLE 4-3  (Continued)
High-Velocity
Water Machines
6"-15" or
larger
1. Best for dislodging  1.
   and transporting
   sludge, mud, sand and
   gravel               2.

2. Also for dislodging
   and transporting
   rocks and grease in  3-
   pipes up to 12"
   diameter
                        4.
3. May be used with
   special tools to dis-
   lodge roots in pipes 5.
   up to 12" diameter

4. Good for cleaning
   manhole walls and
   bench
Manhole access is
not critical

Can be used for
threading sewer
line

Easy to set up and
operate

Past cleaning
method

Low pipe-damage
potential
                                                                               3,


                                                                               4,
Require access to
downstream man-
hole

Water must be
available near job

Least effective on
large heavy debris

May damage
deteriorated pipe
                                                                               5. Do not remove
                                                                                  materials from
                                                                                  sewer
Hydraulically
Propelled
Devices
6"-36"
1. Best for dislodging  1. No equipment access
                and transporting
                sludge, mud and sand

                Also for dislodging
                and transporting
                gravel, rocks,
                bricks and grease
                           limitations

                        2. Minimum equipment
                           requirements

                        3. Ease of operation
                     1.  Require large
                        quantity of water
                        at site

                     2.  May cause base-
                        ment flooding

                     3.  Not applicable to
                        blockage result-
                        ing in surcharge
                        conditions

                     4.  Do not remove
                        materials from
                        sewer

-------
     •  Depth of sewer,

     •  Amount of flow,

     •  Structural integrity of pipe,

     •  Availability of hydrant water,

     •  Degree of cleanliness required.

A review of the general characteristics of the sewer cleaning
equipment (Table 4-3) and the results of the physical survey
will indicate the cleaning equipment which should be used for
each section of sewer recommended for cleaning.  Firms experi-
enced in sewer cleaning should be consulted for detailed infor-
mation on operational procedures and other specific features.

4.5  INTERNAL INSPECTION

4.5.1  General

Following the preparatory cleaning, the sewer sections are
internally inspected to determine the location, condition
and estimated flow rate for each source of infiltration/inflow
defined in the sewer sections.   During the inspection, all
the infiltration/inflow sources, structural defects, service
connections, abnormal conditions and other pertinent observations
are recorded.  The results from the inspection provide a
factual base for the cost-effectiveness analysis to determine
the sewer lines which can be cost-effectively rehabilitated
and for the selection of the most suitable methods for rehabili-
tation.   The information documented during the inspection
can also be used to locate the  pipelines and problem sections
in the pipes during actual rehabilitation.

Internal inspection is normally conducted during periods of
maximum groundwater levels.  However, for sewer lines which
are above the groundwater levels throughout the entire year,
the inspection can be performed any time.  During the inspec-
tion,  all storm sewer sections, stream sections, ditch sections,
and ponding areas which are found to contribute infiltration/
inflow to the sanitary sewer section should be flooded.   The
purpose is to duplicate the worst possible weather and ground-
water  conditions in the sewer sections so all the infiltration/
inflow sources will show up during the inspection.

4.5.2   Inspection Techniques

Sewer  inspection can be accomplished by any one of the follow-
ing four techniques:
                            4-24

-------
     •  Television inspection,

     •  Photographic inspection,

     •  Physical inspection, and

     •  Air test.

The television inspection technique is most  commonly used;
however, the photographic, physical inspection and air test
techniques can also be used under special conditions.  The
method used for internal inspection should be the  best and
most cost-effective method of obtaining the  necessary infor-
mation.

4.5. 2. a  Television Inspection,

The television inspection technique utilizes a closed-circuit
television camera to observe the  conditions  in the sewer lines
The results are shown in the television monitor.   Documen-
tation can be made with videotape or photographs  of the
monitor.  The technique can be applied to sewers  with sizes
ranging from 8 to 36 inches and with lengths up to 1,000
feet (Figure 4-1).

4.5.2.a (1)  Equipment - The cameras used for TV inspection
are specially designed to fit the sewer pipe conditions.
The camera is mounted in a casing and is pulled through the
sewer with cables.  A light source is provided along with
the camera for illumination purposes.  A TV monitor is used
to show the actual conditions in  the sewer as the camera is
pulled along.

4.5.2.a (2)  Procedure - During the inspection, the cameras
are stopped at the points where one or more of the following
conditions are observed:

     •  Infiltration/inflow sources;

     •  Service connections;

     •  Structural defects, including broken pipe,
        collapsed pipe, cracks, deterioration,
        punctures, etc.;

     •  Abnormal Joint conditions, such as horizontal
        and vertical misalignments, open joints,
        joints not fully seated,  etc; and

     •  Unusual conditions, such as root intrusion,
        protruding pipes, in-line pipe size changes,
        mineral deposits, grease, obstructions, etc.
                            4-25

-------
                                                        TV Monitor
                                                                                                       Winch
CT\
                                           Roller Assent Iy
               Manhole -—
                                              -TV Camera
                              Figure 4-1.  Typical Arrangement for Television Inspection of
                                           Sewer Lines

-------
All such conditions should be recorded.   Photographs  of all
questionable conditions should be taken  for subsequent  review.
The photographs are usually taken from the TV monitor with
Polaroid or 35 MM films.  All infiltration/inflow sources
should be quantified while observing through the TV monitor
(see Section 4.5-2.a (3) for detail). If necessary,  the
infiltration/inflow sources may also be  recorded with videotape
for flow estimation in the laboratory and for later review.
Before taking the photographs or videotape, the TV camera
should be properly positioned so that the optimum view  of
the defects, etc., can be obtained.   If  necessary, the  same
problem object can also be viewed from the opposite direction
by pulling the TV camera from the other  manhole in the  sewer
section.  For reference purposes, photographs and videotapes
of typical sewer sections and joints in  lines being inspected
should also be taken.

At the connecting points between the.service connections
and the sewer being inspected, the TV camera should be
stopped to check for any flows coming out of the service
connections.  Whenever a flow is observed, its source should
be checked out immediately.  The building to which the
service connection is  connected should be checked first for
any wastewater discharge during the inspection.  If no  flows
are being discharged from the building,  then it can be
assumed that the observed flow is infiltration or Inflow.
If the estimated flow from the service connection is  greater
than the total wastewater discharge from the fixtures in the
building, then the infiltration/inflow can be determined by
calculating the difference of these two  flows.

The locations of all the conditions recorded should also be
identified by recording the distance from each defect or
point of interest to an established point in each sewer
section.  The distance is usually measured from the center
of the starting manhole to the plane of  focus of the  camera.

Table 4-4 shows a typical television inspection log sheet.  In
addition to the columns for recording the footage, observa-
tions and infiltration/inflow rates, the sheet also includes
columns for recording the recommended corrective action and
the photograph number.  The recommended  corrective action for
each pipe defect or infiltration/inflow  source is based on
the conditions of the defect or the type of infiltration/
inflow source.  This information is essential for conducting
the cost-effectiveness analysis and for  planning the  sewer
rehabilitation program.  For the convenience of cross-
reference, the photographs should be numbered and the photo-
graph number for each item should be recorded on the  log
sheet.
                            4-2?

-------
                                    TABLE  4-4
                       TYPICAL  TELEVISION  INSPECTION LOG SHEET
                                            AREA
                                               SHEET NO.
PROJECT:
CLIENT :
                        PROJECT NO:
                       DATE:
                                             INSPECTOR:
SECTION ON:
FROM MANHOLE  #_
PIPE SIZE
                            TO MANHOLE
IN., PIPE TYPE
PIPE LENGTH
FT   TYPE OF JOINTS
REF.
NO.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
FOOTAGE

























OBSERVATIONS

























INFILTRATION/
INFLOW
gpm

























RECOMMENDED
CORRECTION
ACTION

























PHOTO
NO.

























SPECIAL NOTES
                            MH I
                             o
                                   MH //
                                           DIRECTION OF FLOW  [
                                           DIRECTION OF MEASUREMENT  J_
                                       4-28

-------
4.5.2.a (3)  Estimation of Infiltration/Inflow Rates  -
Estimating the flow rates of the infiltration/inflow  sources
through a television camera is a difficult  task.   The accu-
racy of the estimate depends largely on the experience
of the operator in front of the TV monitor  or the  person
reviewing the videotapes.  The experience is usually  gained
by observing the infiltration/inflow conditions simulated  in
the laboratory and comparing the estimated  flows with the
measured flow rates.

A simple laboratory simulation technique for testing  the estimation
of flows from the infiltration/inflow sources in the  sewer
pipes is illustrated in Figure 4-2.  A section of  sewer pipe
of the same size and type as the sewer to be examined is
used for the test.  On this section of pipe, a defect is
created to simulate a certain condition in the actual sewer
line.  The pipe is installed in an inclined position  in a
water container which has two holes in the  opposite walls.
The adjustable rubber ring is tightened around the pipe to
assure watertightness.  A television camera is pulled into
the pipe section and focused to give a clear view  of  the
defect on the pipe wall.  Water is added to the water container
to a desired level..  The person being trained may  then proceed
to turn on the TV monitor and watch the shape and  speed of
the water leaking through the pipe defect very carefully
from the screen.  Record the flow with videotape  if desired.
Gather the water flowing out of the pipe with a bucket and
record the starting and ending time with a stop watch.  Measure
the volume of water gathered and calculate the flow rate.
Correlate the measured flow rate with the shape and flow
speed shown in the TV monitor.  Repeat the process for different
water heads, type and size of pipe defects, pipe  size and
pipe material to cover as many field pipe conditions  as possible.
The videotape recorded during the test can be used for repeated
training of the field TV inspectors.

However, even with the simulation technique, it is often
not possible to accurately determine the infiltration/inflow
rates in the field.  Whenever possible, the infiltration/
inflow rate in a sewer section should be measured  by  plugging
and weiring (or by other flow measurement techniques) during  the
low flow hours.  After the normal wastewater flows are deducted,
the measured flow rate is compared with the total  estimated
infiltration/ inflow rate.  If the two are not equal, a
correction should be made to adjust the estimated  flow rate.
This can be done by dividing the measured total flow  rate  by
the estimated total flow rate.  The resulting factor  is used
to multiply the estimated flow rate from each individual
source to derive the corrected flow rate.
                            4-29

-------
Pulling Cable
                              Water
                                                              •Water Container
-Adjustable  Rubber  Ring

•Pipe Section
                                                                                     TV Monitor
                            Defect
                     Figure 4-2.  Laboratory Test for Estimating Infiltration/Inflow
                                  Rates

-------
4.5.3  Photographic Inspection.

The photographic inspection technique uses  a camera  to  take
a series of color photographs along the inside  of the sewer
lines.  The technique can be applied to sewers  with  sizes
ranging from 8 to 36 inches.

The technique is best for analyzing the structural con-
ditions of the sewers.  The photographs can also be  used to
determine the joint conditions and root intrusion problems
in the sewers .

In applying this technique, a camera is pulled  through
the sewer line being inspected.  Pictures are taken  at
equidistant intervals or at some predetermined  problem
sections.  The distances at which the pictures  are taken
are measured from a reference point, usually the center of
the starting manhole.

4.5.4  Physical Inspection
Two physical inspection techniques can be used to inspect
the sewer:

     •  Lamping

     •  Entering (large sewers only)

The lamping inspection technique has been discussed in the
section on Physical Survey (Section 4.2.4).  The entering
Inspection technique is a direct method for sewer inspec-
tion.  However, this technique Is usually limited to new
construction, large storm sewers and large sewers not in
service.  In applying this technique, the safety of the
person entering the line should always be carefully guarded.
Before entering the line, the sewer section should be thorough-
ly ventilated to remove all the harmful gases.  Forced ventila-
tion should be provided throughout the inspection period.
The person entering the line should be provided with redundant
lights as well as all the personal safety equipment required
for manhole and sewer inspection (See Section 3.2.6.d.)

4.5.5  Air Test

Specific  circumstances may warrant the use of air testing of
sewer joints, In conjunction with television inspection, to
accomplish internal Inspection.  This technique may be employed
on projects which have missed the high groundwater period and
economics would justify an air testing program to avoid a costly
delay of  the project.
                            4-31

-------
The procedure for air testing is  described  in Chapter  5,
Section 5.3.2.c(l).

4.6  SURVEY REPORT

4.6.1  General

After finishing all  the investigative  work,  a survey report
has to be prepared.   A complete survey report usually  contains
the following items:

     (.a)  A description of all the tasks  performed,  covering:

          •  The purpose of conducting each task,

          •  The methods and equipment used,

          •  The location of the  study area and/or the
             sections of sewer lines investigated;

     (b)  A summary  of all the results gathered during the
          investigation;

     Cc)  A cost-effectiveness analysis to  determine the
          portion of sewer sections which can be cost-
          effectively rehabilitated and the infiltration/
          inflow which is expected to remain in the sewer
          system after rehabilitation;

     (d)  A proposed sewer system rehabilitation program  and
          its related costs;

     Ce)  A documentation of all  the field  data gathered
          during the Investigation.

For clarity, the results, conclusions and recommendations
are usually summarized in tabulated forms and illustrated on
maps.

4.6.2  Data Analysis

The initial step in the preparation of a survey report is
a summarization, in tabulated forms, of the results of all
the tasks performed in the evaluation survey.  The following
table headings are suggested for each respective task:

     (a)  Physical Survey

          (1)  Aboveground inspection:  Location; observation
                            4-32

-------
      (2)  Flow monitoring:  Location; key manhole number;
          sewer lines  (size and length); method of
          measurement; test condition (dry weather and
          wet weather); measured Infiltration (gpd and
          gpd/in-mile  of sewer); suggestion for further
          study.

      (.3)  Groundwater  test:  Manhole number; date;
          measurement  device; groundwater level.

      (.4)  Manhole Inspection:  Location; manhole number;
          type of construction; structural condition;
          infiltration/inflow sources; estimate flow rate;
          remarks; reference page of field report.

      (.5)  Sewer inspection;  Location; sewer section
          number (or, manhole numbers);  type; length;
          size; deposition (type and depth); visible
          infiltration/inflow sources; structural con-
          dition; special problems; recommended cleaning
          method; recommendation for internal inspection;
          reference page of field report.

(b)  Rainfall Simulation

     (1)  Smoke testing;  Location; test conditions;
          observation; conclusions; recommendations.

     (2)  Dyed water testing;   Location; test conditions;
          observed infiltration/inflow sources;  estimated
          flow rate; conclusions;  recommendations.

     (3)  Water flooding test:   Location;  test conditions;
          observed infiltration/inflow sources;  estimated
          flow rate; conclusions;  recommendations.

(c)  Preparatory  Cleaning

     Location; sewer section number (or, manhole numbers);
     pipe (size and length);  deposition  (type and depth);
     cleaning method used.

(d)  Internal Inspection

     Location; sewer section number (or, manhole numbers);
     observed leakage (type,  location and  flow rates);
     recommended  corrective action; reference page  of
     field report.
                       4-33

-------
 A  detailed  sewer map Is usually included in the report.  The
 map  should  show all the manholes, pumping stations, bypasses,
 overflows,  and sewer lines in the sewer system under study.
 For  reference purposes, the manholes should be properly
 numbered.   The size, material and flow direction of each
 sewer section should be clearly indicated.  The important
 information related to the evaluation survey can also be
 shown in the sewer map.  This information may include:

     •  Special problems observed during aboveground
        inspection;

     •  Key manholes for flow monitoring and flow-
        monitored sewer lines;

     •  Groundwater monitoring station;

     •  Manholes and sewer lines inspected during
        physical survey;

     •  Sewer sections investigated by smoke test-
        ing, dyed water testing or water flood
        testing;

     •  Sewer sections cleaned and internally
        inspected;

     •  Sewer sections Justified for internal
        inspection but nonaccessible.

 4.6.3  Cost-Effectiveness Analysis

 4.6.3.a  Introduction

After all the results have been analyzed and summarized, a
cost-effectiveness analysis should be conducted to determine
which portion of the infiltration/inflow conditions in the
sewer system can be cost-effectively corrected.  The method-
ology for conducting the cost-effectiveness analysis is
basically similar to that presented in Section 3.4.3.C for the
Infiltration/Inflow Analysis.   However, in the Sewer System
Evaluation Survey Phase, the types of infiltration/inflow
sources, the flow rate from each source, the best method for
correcting each source and the costs for the corrections are
all better defined than they were in the Infiltration/Inflow
Analysis Phase.   Therefore, somewhat different procedures can
be used.
                            4-34

-------
*J.6.3.b  Flow Adjustment

Before the cost-effectiveness analysis can be conducted,  the
estimated flow from each infiltration/inflow source  should
be adjusted.  The following are the recommended  procedures:

4.6.3.b (1)  Plow Adjustment for Peak Infiltration -

     (a)  Determine the sum of estimated flows from  all
          infiltration sources.

     (b)  Compare the total flow with the total  peak
          infiltration determined in the Infiltration/
          Inflow Analysis.  If the former is greater than the
          latter, no flow adjustment will be needed.  If  the
          reverse is true, calculate the ratio of the latter
          over the former and multiply the estimated flow
          from each source by this ratio to derive the adjusted
          flow, which is then used in the cost-effectiveness
          analysis.

*>.6.3.b (2)  Flow Adjustment for Peak Inflow - The estimated
peak inflow values should be adjusted for the desired design
period or design condition.  The design rainfall frequency
normally used for designing storm sewers should be used for
such adjustment.  The ratio of the design and observed rainfall
intensities is used to adjust the peak inflow.

4.6.3.C  Cost Estimation

Two types of costs need to be developed:

     •  Costs for the correction of infiltration/inflow
        conditions,

     •  Costs for transportation and treatment of waste-
        water (including infiltration/inflow).

The cost for the correction of infiltration/inflow conditions
should be developed for each individual infiltration/inflow
source.  The cost for both the Evaluation Survey and the
Rehabilitation should be included.  (The Cost for the Evalua-
tion Survey has been expended; however, it should be included
in the cost-effectiveness analysis in the Evaluation Survey
Report because (1) it was included in the cost-effectiveness
analysis in the Infiltration/Inflow Analysis Report and  (2)
the cost-effectiveness analysis in the Evaluation Survey
is intended to be a refinement of that in the Infiltration/
Inflow Analysis.)  The estimated cost of the Evaluation  Survey
for each source should be based on the total money actually
expended for Evaluation Survey in the entire  sewer system.
Estimated  costs for rehabilitation should be  based on the
actual physical conditions discovered.


                             4-35

-------
The costs for transportation and treatment of wastewater
can be developed following essentially the same procedures
as those presented in Section 3-4.2.d.  Costs should be
developed for at least four typical flow conditions so
that a cost curve can be drawn to indicate the general cost
pattern.

4.6.3'd  Analysis Procedures

The analysis procedures are as follows:

     (1)  Determine the total correction cost for each
          infiltration/inflow source and calculate the
          cost required for eliminating  each unit of flow
          (the unit cost).

     (2)  Arrange the infiltration/inflow sources in order,
          putting the sources with lower unit costs ahead
          of those with higher unit costs.

     (3)  With the sources  arranged in order, break them
          into several groups and determine the total
          correction cost  as well as total infiltration/
          inflow to be reduced for each  group.   Add to the
          total correction  cost the engineering services
          costs; legal, fiscal and administrative costs;
          contingency costs; interest during construction;
          etc., to derive  the total cost required to
          eliminate the infiltration/inflow from all sources
          within each group.

     (4)  Arrange the groups in order, putting the groups
          with lower total  cost ahead of those with higher
          total cost, and,  calculate the accumulative total
          cost and accumulative total infiltration/inflow
          to be reduced.

     (5)  Plot the accumulative total cost  against the
          accumulative total infiltration/inflow to be
          reduced and draw  a curve passing all data points.
          (Cost Curve for Rehabilitation shown in Figure 4-3).

     (.6)  On the same graph, plot a curve to show the
          relationship between the costs for transportation
          and treatment and the total infiltration/inflow to
          be reduced (Cost  Curve for Transportation and
          Treatment shown  in Figure 4-3).

     (7)  Derive a Composite Cost Curve  (Figure 4-3) by adding
          the costs on the  two derived curves.


                            4-36

-------
 §
1
   h
   il
                             Composite Cost Curve
                                              Minimum
                                               olaI  Cost
                             Cost Curve
                             for Transportation
                             and Treatment
                                   Optimal Point
                                   for Sewer
                                   Rehabilitation
                     Cost Curve for Rehabilitation
                      Infiltration/Inflow Reduced, GPD
Figure 4-3.  Cost Curves  for Cost-Effectiveness Analysis in Evaluation Survey
                              14-3?

-------
     (8)  Locate a minimum cost point on the -Composite Cost
          Curve.  Draw a straight line passing this point
          and parallel to the cost axis.  The line intercepts
          the Cost Curve for Rehabilitation at a point which
          represents the optimal point for sewer rehabilita-
          tion.  The flow figure corresponding to this
          point represents the infiltration/inflow which
          can be cost-effectively removed from the sewer
          system, and the cost figure corresponding to it
          represents the total cost which will^be needed for
          the corrective actions (including the money
          already expended for Evaluation Survey).   Determine
          the infiltration/inflow sources which should be
          rehabilitated to remove the optimal amount of
          infiltration/inflow determined above, starting
          from the sources with the lowest correction costs.

4.6.^  Recommendations for Sewer System Rehabilitation

After the cost-effectiveness analysis, the infiltration/
inflow sources which can be most cost-effectively eliminated
are determined.  A sewer system rehabilitation program should
then be recommended.  For the planning of the rehabilitation
work, a tabulation of all the sewer sections, manholes,
service connections, and inflow sources which can be cost-
effectively rehabilitated or corrected should first be made.
A typical tabulation may include the following information:

     (a)  Sewer Line Rehabilitation

          (1)  Method of rehabilitation;

          (2)  Description of infiltration/inflow sources;

          (3)  Sewer line or manhole identification;

          (4)  Sewer length, size,  type, depth and type of
               cover;

          (5)  Location of infiltration/inflow sources in
               pipe;

          (6)  Section of pipe to be rehabilitated.

     (b)  Manhole Rehabilitation

          (1)  Method of rehabilitation;

          (2)  Description of infiltration/inflow sources;
                           4-38

-------
          (3)   Manhole identification;
          (.4)   Type and depth of manhole.
     (c)  Service Connection
          (1)   Method of rehabilitation;
          C2)   Description of infiltration/inflow sources;
          (3)   Address of service connection;
          (4)   Sewer line to which the  service connection is
               connected;
          (.5)   Length of service line;
          (6)   Type of cover.
     (d)  Inflow Sources
          (1)   Method of correction;
          (2)   Description of inflow source;
          (3)   Location of inflow source.
Whenever possible, the time schedule for the proposed
rehabilitation work and related costs should also be in-
cluded in the  recommendation.  For the  benefit of a continued
operation and  maintenance program, it Is also advisable
to tabulate all the problems in the sewer system observed
during the evaluation survey.
                            4-39

-------
                          CHAPTER 5

                 SEWER SYSTEM REHABILITATION
5.1  INTRODUCTION

The sewer system rehabilitation involves all the work that
is necessary to correct the infiltration/inflow conditions
which were found to be cost-effective to correct in the
Sewer System Evaluation Survey.

The infiltration and inflow sources which are commonly
found in sewer systems are shown in Table 5-1-  In the same
table, the possible correction methods for each source
are also shown.

The correction methods for inflow sources are relatively
simple and will not be considered in further detail.  The
techniques which are most frequently used for correcting
infiltration sources include [93*.

     (a)  Excavat i on/Replac ement

     (b)  Chemical Grouting

          (1)  Acrylamide gel
          (2)  Polyurethane foam

     (c)  Pipe Lining (Slip-lining)

          (1)  ^Polyethylene pipe
          (2)  Fiberglass-reinforced polyester mortar pipe

     (d)  Pipe Lining

          (1)  Cement mortar
          (2)  Epoxy mortar

The advantages, limitations, applications and procedures
of these techniques are discussed in the following sections.

Engineers should be aware of any new products which may be
made available in the future.  The use of new products is
encouraged If they are proved to be effective.

For applications, only the most effective technique or material
should be used.  When several techniques or materials are
equally effective, the one with the minimum overall cost
should be chosen.
                             5-1

-------
                             TABLE 5-1

         INFILTRATION/INFLOW SOURCES AND CORRECTION METHODS
      Sources
Possible Correction Methods
Infiltration Sources

Collapsed pipe

Broken or crushed pipe

Cracked pipe



Deteriorated pipe joints

Leaking off-set Joints


Open joints
Deteriorated mortar joints in
  brick pipes

Leaking house service connections
Faulty taps between sewers and
  manholes

Faulty taps between service con-
  nections and main sewers

Collapsed manhole and wet wells

Deteriorated manhole walls, bases
  and troughs
Deteriorated mortar Joints in
  brick manholes

Deteriorated wet wells and pumping
  station structures

Other sources such as deteriorated
  regulators, tide gates, etc.
Replacement; slip-lining

Replacement; slip-lining

Slip-lining; lining with cement
  mortar or epoxy mortar;
  replacement

Chemical grouting

Slip-lining; chemical grouting;
  replacement

Slip-lining; chemical grouting;
  replacement


Brick mortar replacement
Chemical grouting; slip-lining;
  replacement

Excavation and repair
Excavation and repair
Replacement

Lining with cement mortar or epoxy
  mortar; chemical grouting;
  cement grouting

Brick mortar replacement
Lining with cement or epoxy
  mortar

Repair according to situation
                                  5-2

-------
                        TABLE 5-1 (Continued)
     Sources
Possible Correction Methods
Inflow Sources

Low lying manholes

Perforated manhole covers

Cross connections

Roof leader drains

Foundation drains

Cellar drains

Yard drains

Area drains

Cooling water discharge

Drains from springs and swampy
  areas
Manhole raising

Replace with water tight covers

Plugging

Disconnection

Disconnection

Disconnection

Plugging

Plugging

Disconnection

Plugging
                                  5-3

-------
 5.2  EXCAVATION/REPLACEMENT

 This technique involves the removal of the existing pipes
 or manholes from the ground and replacing them with new
 ones.  If suitable material and construction methods are
 utilized, the technique may produce the most effective
 rehabilitation results.  The cost of this technique,
 however, is normally much higher than other rehabilitation
 techniques and the time requirement is usually much longer.

 The technique is normally considered for application under
 one or more of the following conditions E9]:

      • In locations where pipes or manholes have lost
        their structural integrity, such as pipes or
        manholes which are collapsed, crushed, broken,
        or badly deteriorated and cracked;

      • In cases where pipe size enlargement, change in
        grade and/or line realignment are needed in addi-
        tion to pipe deficiency corrections;

      • In cases where the causes of damages to the
        existing pipes or manholes (such as corrosion,
        soil movement, increasing traffic load, etc.)
        have been identified and it is desirable to pre-
        vent the reoccurrence of these damages by replacing
        the existing structures with new ones having better
        quality and greater strength.

Just as for new sewer construction, this rehabilitation
technique may require the removal of pavement, disruption of
traffic,  dewatering, well-pointing, shoring, interference
with utilities and structures,  and repavement.  In addition,
during the construction period, the sewage flows in the sewer
sections  should also be bypassed.  All the costs involved in
these tasks should be considered when comparing this technique
with other rehabilitation techniques.

5.3  CHEMICAL GROUTING

5.3.1  Introduction

Chemical  grouting is most commonly used to seal leaking
joints in structurally sound sewer pipes.  With special
techniques and tools, the method can also be used to seal
leaks in  house connections, manhole external drops, man-
holes, wet wells and pumping station structures.

The information described hereinafter was supplied by American
Cyanamid  Company and 3M Company.  For specific use of these
products, the reader should consult with the manufacturers.

-------
Two chemical grouts have been used extensively:   acrylamide
gel and polyurethane foam.   Basically, grouting with the
acrylamide gel stops the leaks by internally injecting the
grout to the soils surrounding the leaks to decrease their
permeability.  Grouting with the polyurethane foam,  on the
other hand, seals the leaks by injecting the grout into
the cracks and letting it solidify to form a barrier.

The acrylamide gel was developed in the early 1950 's by
American Cyanamid Company and was initially used for soil
stabilization.  It was not  used for sewer rehabilitation
until I960.  The polyurethane foam was developed in the
late 1960's and early 1970's by the 3M Company and has been
used for sewer rehabilitation since 1973.

5.3.2  Chemical Grouting With Acrylamide Gel

5.3.2.a  Properties of the  Acrylamide Gel

The acrylamide gel is commonly known by its trade name,
AM-9.  The basic chemical used in the acrylamide gel is a
mixture of two organic monomers, acrylamide and N,N'-methyl-
ene bisacrylamide.  The chemical is in the form of a white
powder with a specific weight of about 35 pounds per cubic
foot.  A 10-percent (by weight) aqueous solution of this
chemical is usually used for sewer grouting.  When the
aqueous solution of this chemical is properly catalyzed,
gelation occurs through a polymerization-crosslinking
reaction.

The catalysts used for the reaction are B-dimethylamino-
propionltrlle and ammonium persulfate.  The former is a
caustic solution and is used as an activator for the
reaction.  The latter is a strong oxidizing agent used as
an initiator to trigger the reaction.

In field applications, the monomer powder and the activator
are usually dissolved in water in one container and the
initiator  is mixed with water in a second container.  The
individual solutions are stable for about two weeks.  Gel-
ation occurs when these two solutions are mixed together.

The gel time  (or  "set time" or "induction time") is
primarily  affected by the concentrations of the catalysts
and the solution  temperature.  Generally, the higher the
catalyst concentrations and the temperature, the shorter
the gel time.  However, the concentration of the ammonium
persulfate should normally be less than  3-0 percent  (by
weight) since at  higher concentrations the mix may be too
acidic to  gel.  Other factors which affect the gel time  include
monomer concentration, pH, metal  ions, salts, particulate


                             5-5

-------
matter, hydrogen sulfide and chemical composition of mixing
water.  By altering the concentrations of the catalysts,
the gel times can be controlled from 5 to 500 seconds.  A
gel time of approximately 20 seconds is commonly chosen in
sewer grouting.  Longer gel times are used in structural
waterproofing which needs deeper penetration at lower flow
rates.  The effect of catalyst concentration and temperature
on gel time has been documented by American Cyanamid Company
(A typical example is shown in Figure 5-1.)  Table 5-2 shows
the compositions of the grouting mixes suggested by the man-
ufacturer for summer and winter applications at ground
temperatures of 60° F and 50° F, respectively.

Before gelation, the grouting mix has a viscosity very
close to that of water.  This allows it to penetrate into
small leaks and cracks in pipe walls and to mingle with
outside soil particles.  The acrylamide gel formed from the
solution is a translucent, rubbery and elastic material.
Under moist conditions, the gel is resistant to attack by
microorganisms, dilute acids, alkalies, and the ordinary
salts and gases normally found in the ground.  When the
gel is formed in a soil matrix, the permeability of the soil
is reduced.  The degree of reduction of the permeability
depends upon the extent to which the voids are filled with
the gel.  If they are completely filled, the gel-soil mix-
ture is virtually impermeable.

If allowed to dry, the gel will shrink due to dehydration.
In a gel-soil mixture, dehydration may cause shrinkage
cracks which would not be rehealed even if the moisture
content of the mixture is restored later.   However, chemical
additives such as ethylene glycol or calcium chloride may be
added to the grout to prevent dehydration.

Before gelation, the acrylamide gel is toxic.  Inhalation
of its vapor, contact with skin and swallowing should all
be avoided.

5.3.2.b  General Considerations in Applications

The acrylamide gel can be used for sealing pipe joints, but
it cannot be used as a structural repair for broken, crushed
or badly cracked pipes and appurtenant structures.

In soils containing large interstices, such as coral sand,
gravel or rocks, especially in the presence of moving ground-
water, the effectiveness of the gel may be reduced.  This
situation may be remedied by one of the following measures:

     (1)  Judicious use of shorter gel time
                             5-6

-------
1 V\f
ion
lev
en
OU
48
TIC
3b


^5 jj
£«»
1 O
lO





^
™?w
x~
X
*^











^
—
\

^^^
x
^* ^_
v







>>
.>»,.^


X.
" N
^^^_
,^^ V,
\






^,
*•% '
^,



X.
s
N
V





^-^
•s

*-




i »
X






^- -•
.^x
*^^

^^^^



X
N,
^




I^B^iM ••«•
J»^_ 	

^"^
.^^ ^
. -•
^^^
^"*.

s.
Ss "



10*
• 0
• 1.6
	



^ »

•w^ ""'
»

X "^
X^
X


AM-3
rf nuA
!• DMA
( DIM
	
\^


*^1
^^
>^
.^^'v
<

x^-
s^X,
%
_.
Dhl
rn •
n
	

^*Vv
c*,^


»^^
„ *N.
^"&

>»

" '"^S-


Perc
Ammo

l n
i ,\i
1 5

o n
& *\j
	 2.5
3 0

2 0
	 2.5
. * n
38
44
50
                           56
62
                    Temperature
                         °F
                                                 Ammonium Persulfate
Figure 5-1.   Effect of Catalyst Concentration and
              Temperature on Acrylamide Gel Set
              Time
                        5-7

-------
                          TABLE 5-2


           TYPICAL COMPOSITIONS OP ACRYLAMIDE GEL

                       GROUTING MIXES [11]
     A.  SUMMER GROUTING MIX


Ground Temperature:  60° F.
Gel Time:  20 seconds
Composition

AM- 9 tank <

AP tank (
1

fAM-912
DMAPN
, Water
' AP3
, Water

B. WINTER GROUTING
Wt*
10.0
0.8
39.2
3.0
47.0
100.0
MIX
Ibs.
50.0
4.0
196.0
15.0
235.0
500.0

gal.
__
0.56
23.5
MM
28.0
60.0

Ground Temperature:  50° F.
Gel Time:  18 seconds
Composition
(AM-9%
AM-9 tank j DMAPN
I. Water
AP tank ( AP3
1 Water
Wtjf
10.0
1.6
38.4
2.5
47.5
100.0
Ibs.
50.0
8.0
192.0
12.5
237.5
500.0
gal.
1.13
23.0
28.0
5o7o
 Mixture of two monomers:   acrylamlde and N, N'-methylenebisacrylamide
>
"B-dimethylaminopropionitrile

 Ammonium persulfate
                             5-8

-------
     (2)   Intermittent  grouting

     (3)   Using higher  gel concentration

Before grouting, the pipes should be cleaned.   There should
be no obstacles in the  pipe to prevent the passage  of sealing
packer.  The sealing packer can only be used at joints where
the pipe wall on each side of the joint can provide continuous
contact with the packer.

In locations where prolonged dry conditions are expected,
dehydration resisting additives should be used.

5.3•2.c  Applications

5.3.2.C (1)  Sewer Grouting - Grouting of sewer pipe joints
is generally accomplished with a sealing packer and a closed
circuit television camera.  The sealing packer is used to
apply the chemical grout to the pipe joint.  It is  usually
made of a hollow metal cylinder which has an inflatable rubber
sleeve on each end of a center band.  The television camera
is used to remotely position the packer on the pipe joint  and
to inspect the joints before and after the sealing operation.
The sealing packer and television camera are pulled by cables
through a sewer section from manhole to manhole.  In addition,
the air testing equipment is sometimes used to determine the
integrity of the joints and to check the effectiveness of the
sealing.  The practice of finding the leaking pipe joints
with the air testing equipment followed by immediate chemical
grouting is commonly known as  "test and seal".

Figure 5-2 shows a schematic diagram of a sealing packer and
a television camera in place during a grouting operation.
The procedure is as follows:

      (a)  Clean the pipe.

      (b)  With the aid of the  television camera, position
          the sealing packer on the Joint to be grouted.

      (c)  Pump  air to the rubber  sleeves of the packer
          until they expand and  seal  against the pipe wall
          on both sides of the Joint.

      (d)   If air  testing  is to be conducted, it is  done
           at this time by  applying air  pressure to  the
           space created between  the two Inflated sleeves.
           The  joint  is usually considered  to be adequate
           when a  pressure  equal  to or slightly greater than
           the  maximum  expected groundwater static  head
           pressure  can be  maintained  for a period  of several
           seconds.
                             5-9

-------
Manhole
                                                                    Catalyst
                Roller Assembly
                                 Sealing Packer
Chemical
Grout
Catalyst
                                                                                                  TV Monitor
                                                                                            fanhole
                                                                                        Roller Assembly
                            Figure 5-2.   Typical Arrangement for Chemical
                                          Grouting with Aery lamide Gel

-------
     (e)  For the joint which needs sealing,  pump the
          chemical grout into the space created between the
          two inflated sleeves.   In this space, the  grout
          and the initiator solutions are mixed together
          and squeezed out through the joint  leak into  the
          surrounding soil.  There, the grout displaces the
          groundwater and fills  the voids between the soil
          particles.

     (f)  After proper gelation  time, deflate the packer
          and move it to the next joint.  To  make certain
          the sealing is proper, air testing  can be  con-
          ducted.  (Before the test, the packer should  be
          deflated and reinflated to break up the gel inside
          the pipe.  The packer  can also be used to  wipe
          the pipe before being  reinflated.)   If the sealing
          is unsuccessful, more  grout can be  pumped  through
          the joint until a seal is obtained.  The gel  formed
          on the inside of the pipe is very weak and can
          be washed away easily  by the flowing sewage.

5.3*2.0 (2)  Grouting of House Connections and Manhole
External Drops - The  acrylamide  gel can often be used to
seal the leaks in the house connections and manhole  external
drops.   However, because of size and/or access limitations,
the sealing packer-television camera technique is normally
not applicable.  The  frequently  used technique for the  house
connection is to pump the grout  to fill the entire length of
the house connection until the grout exfiltrates through the
various leaks.  This  technique is also applicable to seal
manhole external drops.  Reaming of the house connection
line to remove excess grout may  be necessary  after the  gel
time.

5.3.2.C (3)  Grouting of Manholes, Wet Veils  and Pumping
Station Structures - To grout manholes, wet wells and
pumping station structures, a special probe-type grout
applicator can be used.  The grouting operation is per-
formed by physically entering each of the above structures.

5.3.3  Chemical Grouting with Polyurethane Foam

5.3.3»a  Properties of the Urethane Foam

The polyurethane foam grout is normally known as 3M  Brand
Elastomeric Sewer Grouting Compound.  The grout is a liquid
urethane prepolymer with a specific weight of 9*15 pounds
per gallon and a viscosity of 300-350 centipoises at 70° F
[123.
                             5-11

-------
 When mixed with an equal amount of water, the grout initially
 foams and then cures to a tough, flexible cellular rubber.
 The first stage of the reaction is referred to as the "foam
 time",  "induction time" or  "cream time" and the second stage
 is called "cure time", "set time" or "gel time".  Both the
 foam time and the cure time are temperature-dependent.
 Generally, the higher the temperature, the shorter the
 reaction times.  An accelerator, which is a water-soluble
 amine,  is usually added to the mixing water to reduce the
 foam and cure times.  When a 0.4$ accelerator is added, the
 foam time and cure time at 40° P are 45 seconds and 5.5
 minutes, respectively, and, at 100° F, they are 15 seconds
 and 2.5 minutes, respectively.

 The cured grout has a tensile strength of 90 psi and elonga-
 tion of 800$.  Since the grout contains only about 15* of
 the solvent initially, the linear shrinkage upon drying is
 only 15*.  Cyclic wetting and drying conditions do not sub-
 stantially affect the grout.  The grout is resistant to most
 organic solvents, mild acids and alkalies.

 The unreacted polymer solution is toxic and flammable.
 Breathing of its vapor and contact  with eyes, skin and
 clothing should be avoided.   The container of this solution
 should be kept away from sparks, heat and flame.

 5.3.3.b  General Considerations in  Applications

 The polyurethane foam can be used for sealing pipe Joints, but
 it cannot be used as a structural repair for broken, crushed
 or badly cracked pipes.   Before grouting, the pipes should be
 cleaned.  There should be no obstacles in the pipes to prevent
 the passage of sealing packer.  The sealing packer can only be
 used at Joints where the pipe wall  on each side of the Joint
 can provide continuous contact with the packer.

The grout can be used in places where prolonged dry conditions
 occur.   The sealed Joints can accept movement because of high
 flexibility of the cured grout.

 5.3.3.C  Applications

 5.3.3.0 (1)  Sewer Grouting - For grouting sewers with the
 polyurethane foam, procedures similar to those with the
 acrylamide gel are followed.  A sealing packer, similar to the
 one used for the acrylamide gel, is used for injecting the
 polyurethane foam.  The packer is made of a hollow metal
 cylinder with three inflatable sleeves covered by a continuous
 outer sleeve.  In operation, the packer is positioned on the
 Joint to be grouted with the aid of a television camera and
 its end sleeves are inflated.  The  polymer and water are then
                            5-12

-------
introduced into the space created between the  two  inflated
sleeves, and the foam time begins.  At  the end of  the  foam
time, the center sleeve of the packer is  inflated,  forcing
the grout into the pipe joint.  After the cure time ends,
the sleeves of the packer are deflated  and the packer  is
moved to the next joint.

To determine the integrity of the joints  before and after
the grouting, a water testing system rather than an air
testing system is usually used for the  pressure testing.

5.3*3.0 (2)  Manhole Grouting - The polyurethane foam  can
also be used to grout the leaking joints  and cracks in the
manholes.  A probe-type applicator is usually  used to
inject the grout directly into the leaks.  The grouting is
performed by physically entering the manhole.

5.4  PIPE LINING WITH POLYETHYLENE PIPE

5.4.1  Introduction
This sewer rehabilitation technique is commonly called slip-
lining.  It involves the pulling of a polyethylene pipe
through a straight section of sewer line to replace the
latter.  The following technical advantages are associated
with this method [9]:

     •  For installation, the excavation is less than
        that required for complete pipe replacement.

     •  The installed pipe will have low joint leakage
        since all joints are butt-fusion welded.

     •  The smooth inner surface of the polyethylene
        pipe offers very low resistance to flow.

     •  The polyethylene pipe is corrosion- and abrasion-
        resistant .

     •  The pipe is capable of deflection and movement
        without breaking.

Because of these advantages, the slip-lining technique may
be considered under one or more of the following sewer con-
ditions :

     •  Extensively cracked pipe, especially if the pipe
        is constructed in unstable soil conditions;
                            5-13

-------
        Deteriorating pipe having shallow grade, septic
        conditions and corrosive liquids;

        Pipe with massive and destructive root intrusion
        problems ;

        Pipes in locations where the excavation/replace-
        ment technique is not applicable .

       Installation Equipment
The following equipment is required for the insertion of
the polyethylene pipes into sewers :

     •  Joining equipment (heat fusion rig)

     •  Pulling head (nose cone)

     •  Winch

     •  Rollers

     •  Proofing tool

     •  Grout tank and pump

The joining equipment is used to join the standard poly-
ethylene pipe sections (usually 38 feet in length) above-
ground into a continuous pipe of the desired length.   The
joints are made by aligning the pipe sections on the
joining equipment, heating the ends  of the pipes and
butting the heated ends together.  The formed Joints  are
normally stronger than the rest of the pipe and completely
waterproof.  The pulling head is utilized to facilitate the
pulling of the pipe into the sewer.   One end of the pulling
head is attached to the pipe to be pulled while the other
end is attached to the pulling cable.   The winch,  consist-
ing of a power operator and a pulling cable, is used  to pull
the pipe.   The rollers are used to facilitate the  movement
of the pipe aboveground during the pull.  The proofing tool
is utilized to make certain that the proposed liner can pass
through the sewer without difficulties .  The proofing tool
can be fabricated with pulling heads on both ends  from a
piece of pipe of the same diameter as  the one to be inserted
and of a length equivalent to two sections of the  sewer
(normally 8 feet).  The grouting tank and pump are used to
grout the annular space between the  pipe and manhole  connec-
tions to prevent groundwater migration.  When greater struc-
tural strength is desired, the annular space in the entire
manhole-to-manhole distance can also be grouted.
                            5-14

-------
5.4.3  Installation Procedures

     (a)   Clean and inspect  the  sewer to  determine the
          structural conditions,  obstructions, offset
          joints,  intruding  service  connections, size and
          grade.   Determine  the  applicability of the slip-
          lining technique to the specific  sewer lines
          being considered
          Evaluation Survey  Phase).

     (b)   Determine the size and wall thickness of the
          polyethylene  pipe  to be inserted.  Remove all
          obstacles in  the sewer, such  as deposits, pro-
          truding laterals and root  intrusion.  Pull the
          proofing tool through  the  sewers  to make certain
          the proposed  pipe  size is  feasible.

     (c)   Establish the excavation points on the basis of
          location of the lines  to be slip-lined, pulling
          distances and traffic  conditions.  The locations
          of the excavation  points should be such as to
          minimize traffic disruption.   The number of
          excavations can be reduced by planning to insert
          the pipe in both directions from  a single opening.
          Normally, a pipe length of 2-3 manhole sections
          can be lined  from  a  single excavation.

     (d)   Excavate to expose the sewer  and  remove the crown
          of the sewer.  The access  ditch should be long
          enough to avoid imposing a bending radius of less
          than 35-^0 times the outside  diameter of the pipe
          liner during  insertion. The  ditch is sloped
          gradually from the ground  surface to the top of
          the sewer. The width  of the  ditch should be
          sufficient to allow  the entry of  the workmen.
          Sheathing and bracing  requirements would depend
          on depth and  ground  conditions.

     (e)   Join the polyethylene  pipe sections  to the desired
          length at the job  site and attach the pulling head
          to one end of the  joined pipe sections.

     (f)   Run the pulling cable  through the sewer pipe and
          connect it to the  pulling  head.  Pull  the pipe
          liner through the  sewer pipe  steadily.  The  annular
          clearance between  the  liner  and the  pipe  is  usually
          sufficient to permit normal  sewage  flow during
          installation.  However, if a  high sewage  flow  is
          anticipated,  sewer bypasses  should  be  provided
          before installation.   Once in place,  allow  the
          pipe to reach ground temperature.

     (g)  Cut in and connect the service connections  to  the
          pipe liner.  (See  Section 5.4.M for procedures.)
                            5-15

-------
     (h)  If pulling has been carried out in both directions
          from the same opening, the adjoining pipe ends
          should be touching together, wrapped and encased
          in concrete.  Alternatively, the connections can
          be made by using sleeves extending at least one
          foot beyond the butted ends and strapped into
          position.

     (.1)  Grout the annular space between the pipe and the
          manhole connections.  Grouting of the annulus
          between the liner and the pipe is usually not
          required if the liner is strong enough to with-
          stand the anticipated loads in the event of the
          collapse of the pipe.

     (j)  Backfill and compaction of the excavation.

5.**. 4  Methods for Connecting House Service Lines

Three methods have been developed for connecting the house
service lines to the newly inserted polyethylene pipe
liners in sewers [133:

     •  Remote connector

     •  Heat-fusion saddle

     •  Tapping saddle

 .4 . 4 . a  Remo t e C onne c t or
This method is most suitable for application under the
following conditions:

     •  Access to the house service line is relatively
        shallow;

     •  Existing house service line is large enough and
        sufficiently straight to permit insertion of a new
        4-1/2-inch (outside diameter) polyethylene pipe.

Using this method, the connection can be made with minimum
excavation as follows:

     (1)  Locate the point where the house service line
          leaves the shallow burial and starts dipping down
          to connect with the main sewer.

     (2)  Excavate to expose the service line at this turn-
          ing point and break away the shoulder of the turn
          in the pipe to create an access opening.

     (3)  Insert a cutting tool down the line through the
          access opening to cut a hole into the new pipe
          liner in the main sewer.

                             5-16

-------
     (4)   After the cut  is  completed,  insert  a piece  of
          4-1/2-inch polyethylene  pipe of appropriate length
          down to the main  sewer.   The connection end of
          this pipe is butt-fused  with an expandable  fitting.
          The fitting f-its  into the hole previously cut into
          the pipe liner and is expanded into place by
          using a heating tool. The fitting  has  also an
          integral neoprene gasket which further  minimizes
          the chance of infiltration at the joint.

     (5)   Remove the excessive protrusion of  the  new  polyethy-
          lene service line into the main sewer with  a
          trimming tool.

     (.6)   Connect the upper end of the new service pipe
          to the service line leading to the  house.

     (7)   Backfill.

(The complete Installation  is illustrated in  Figure  5-3•)

If the existing house service pipe is too small to permit
insertion of a 4-1/2-inch (O.D.) polyethylene pipe,  or if
the pipe  route is too tortuous to  insert a pipe,  the  same
method can still be used but with  some modifications.  In
this case, a 12-inch hole can be drilled from the ground
level to  the main sewer line to facilitate the installation
of the remote connector.  (The installation is illustrated
in Figure 5-4.)

5.4.4.b  Fusion Saddle

This method involves more excavation than the previous
method.  The procedure is as follows:

     (1)   Excavate to the point where the house service
          line is connected to the main sewer.  Expose
          enough space for two workmen.

     (2)   Break away a portion of the house service  pipe
          and the old sewer main,  and clean the surface
          area on the newly Installed polyethylene liner
          where the fusion saddle  is to be connected.

     (.3)   Heat both the fusion saddle and the surface of
          the polyethylene liner with the heating tool.
          When the heating cycle is completed, press the
          saddle firmly against the melt patch on the liner.

     (4)   After solidification, cut a hole through the
          outlet of the saddle fitting into the liner.
                             5-17

-------
   GROUND
                                                 ECCENTRIC REDUCER ATTACHED
                                                 WITH  SHRINK SLEEVE
                                       SHRINK SLEEVE

                                       U-l/2" O.D.  POLYETHYLENE PIPE

                                 EXISTING 6" PIPE

                                 EXPANDABLE FITTING

                                 INSERTED POLYETHYLENE  PIPE

                                 SEWER PIPE
 Figure 5-3.   Remote  Connection of House Service Line
                through Sewer Pipe [13]
                                   GROUND SURFACE
                                                  HOUSE
                                             EXIST.  6"  PIPE

                                             ECCENTRIC  REDUCER ATTACHED WITH
                                             SHRINK  SLEEVE
                                             4-1/2" O.D. POLYETHYLENE  PIPE
                                   SHRINK SLEEVES
                                   DRILLED HOLE - 12"  DIA.

                            INSERTED POLYETHYLENE PIPE

                             SEWER  PIPE
Figure 5-4.   Remote Connection of House Service Line
               through  New Dri I led Hole   [13]
                           5-18

-------
     (5)  Connect a piece of polyethylene  pipe  to  the  out-
          let of the fusion saddle  using a socket  heating
          tool.

     (6)  Connect the new polyethylene service  pipe  to the
          house service pipe leading to the house .

     (7)  Backfill.

     .c  Tapping Saddle
This method, as follows,  uses a full-encirclement  saddle
fitting to make the connection:

     (1)  Excavate to the point where the house service
          line is connected to the main sewer.   Expose
          enough space for two workmen.

     C2)  Break away a portion of the house service pipe
          and the old sewer main and clean the surface
          area on the newly installed polyethylene liner
          where the tapping saddle is to be connected.

     (3)  Drill a hole in the polyethylene liner at the
          point of connection.

     (4)  Fit the saddle to the hole in the polyethylene
          liner.  Use neoprene gaskets between the under-
          side of the saddle and the liner to provide a
          tight seal.

     (5)  Draw the straps around the saddle and the full-
          encirclement backing to complete the connection.

     C6)  Use a cement grout or cement-stabilized sand to
          reinforce the connection area to protect against
          earth shifting.

     (7)  Backfill.

5.5  PIPE LINING WITH FIBERGLASS-REINFORCED POLYESTER
     MORTAR PIPE

5.5.1   Introduction

Similar to  the polyethylene pipe, the  fiberglass-reinforced
polyester mortar pipe can also be used to line the exten-
sively  cracked sewer pipes with less excavation than the
excavation/replacement technique.  This lining method  is
usually applied to pipes equal to or greater than 21 inches
in  diameter with no  service  sewers connected [9],  Because of
the  nature  of  the pipe material, it is difficult to cut in
and  connect the service sewers to this type of pipe.   The
pipe can be pulled only in straight sections of sewer  lines.
                             5-19

-------
The fiberglass-reinforced polyester mortar pipe is
corrosion-resistant.  The pipe sections are usually 20 feet
in length.  They are joined by 0-ring-sealed inverted bell
and spigot joints.  The inner surface of the pipe is
smooth.  However, because of the inverted bell joints,
some flow reduction is expected after lining.

5.5.2  Installation Procedures

Before installation, the sewer pipe should be internally
inspected and thoroughly cleaned.   The liner pipe is in-
serted by excavating over the sewer and pulling or jacking
the pipe upstream against the sewage flow.  Sewage flows
are normally uninterrupted during the entire operation.
The specific procedures are as follows:

     (a)  Clean and inspect the sewer to determine the
          structural conditions, obstructions, offset
          joints, size and grade.   Determine the applica-
          bility of this lining technique to the sewer
          lines being considered (completed in the Sewer
          System Evaluation Survey Phase).

     (b)  Determine the size and wall thickness of the
          polyester pipe to be inserted.   Remove all
          obstacles in the sewer,  such as deposits,  root
          intrusion, etc.  Pull the proofing tool through
          the sewers to make certain the proposed pipe size
          is feasible.

     (c)  Establish the excavation points on the basis of
          locations of the sewers  to be lined, pulling dis-
          tances and traffic conditions.   The locations  of
          the excavation points should be such as to
          minimize traffic disruption.  Pipes are usually
          pulled upstream against  the sewage flow.   There-
          fore, the excavation point should be located at
          the downstream locations on the sewer lines to
          be lined.

     (d)  Excavate to expose the sewer and remove the crown
          of the sewer.  The working pit  should be long
          enough to accommodate the liner sections and the
          jacking equipment.  If the liner sections  are  to
          be pulled into the pipe, a shorter pit (approxi-
          mately 26 feet) would be sufficient.  Sheathing
          and bracing requirements would depend on depth
          and ground conditions.
                            5-20

-------
     (e)   Join  the  liner  pipe  sections at the job  site.
          Jack  or pull  the  pipe  through the  sewer  steadily.
          The annular clearance  between the  liner  and the
          pipe  is usually sufficient  to permit normal
          sewage flow during installation.   However, if
          unusually high  sewage  flow  is anticipated, sewer
          bypasses  should be provided before installation.

     Cf)   Grout the annular space  between the liner pipe and
          the manhole connections.  Grouting of  the annular
          space between the liner  and the pipe is  usually not
          required  if the liner  is  strong enough to with-
          stand the anticipated  loads in the event of the
          collapse  of the pipe.

     (g)   Backfill  and  compact the excavation.

5.6  PIPE LINING WITH CEMENT MORTAR AND EPOXY MORTAR

Cement mortar  and  epoxy mortar can be used  to internally
line round concrete or  brick pipes which are still structurally
sound.  This lining method  is  generally applied  to pipes  24
inches in diameter  or larger although it may also  be applied
to smaller pipes  [93.   The  cement  mortar  linings are vulnerable
to chemical attack and  should  not  be  used  in sewers  trans-
mitting corrosive  liquids.  For  corrosive  environments,  the
epoxy mortar should always  be  used.  The  drawback  of this
type of lining is  that  the  corrosion  caused by  hydrogen
sulfide may continue underneath  the lining.

The mortars are usually machine-applied  to  the  interior
surface of the sewer pipes.  Before application, the pipe
surface should be  thoroughly  clean, all  loose materials
should be removed,  the  sewage  flow should  be stopped  or  by-
passed, and the water standing in the pipe  should  be  removed.
During application, no  active  infiltration through joints,
pipe walls and service  connections is allowed.   The pipe
surface should be  dried if the epoxy mortar is  used;  however,
for cement mortar  lining, a moist pipe surface  is  acceptable.
The thickness of the lining is usually 3/16 inch to 3/8  inch
[9].
                            5-21

-------
                          CHAPTER  6

          COSTS FOR SEWER SYSTEM EVALUATION  SURVEY
                     AND REHABILITATION
6.1  INTRODUCTION

The cost data presented in this  chapter  provides  a  general
guidance for engineers performing the cost-effectiveness
analysis in Infiltration/Inflow  Analysis.   To a limited
extent, the data can also be used for conducting the  cost-
effectiveness analysis in Sewer  System Evaluation Survey.
The methodology for performing each respective cost-
effectiveness analysis has been  described previously  (Sections
3.4 and 4.6.3).

The limitations of these cost data must  be recognized.  The
costs are mainly a compilation of the data from several
reference sources (14, 15, 16, 17) and a number of  Infiltration/
Inflow Analysis reports submitted to EPA, and reflect the
average costs prevailing in mid-1974.  Individual costs may
vary significantly due to location, site condition, sewer
system condition, weather condition, availability of labor
force, work requirements, and numerous other factors.
Therefore, use of the data presented herein should be
limited to preliminary cost estimates.  Engineers are encour-
aged to develop their own cost data from reliable sources to
fit the specific conditions of each project at hand.

6.2  SEWER SYSTEM EVALUATION SURVEY COSTS

Table  6-1 shows the costs required for conducting each phase
of Sewer System Evaluation Survey, except report preparation.
The unit costs presented are the costs required for each foot
of gravity sewer actually included in the evaluation  survey.
The range of  costs presented for each function reflects the
possible variation of costs for performing the work in
different sewer  systems.  Factors which may affect the costs
for each phase of study are shown in Tables 6-2 to 6-5.

Figures 6-1  to 6-24 show the cost curves for the Sewer System
Evaluation Survey and for conducting each phase of work in
the Evaluation Survey in terms of the following four
parameters:

      • Total length  of gravity  sewer in system

      • Peak infiltration/inflow
                              6-1

-------
                              TABLE 6-1

                COSTS FOR SEWER SYSTEM EVALUATION SURVEY
      Function
Cost, $/foot of sewer
Physical Survey

Rainfall Simulation

          Smoke Testing
          Dyed Water Test
          Water Flooding

Preparatory Cleaning

          6-inch Pipe
          8-inch Pipe
          10-inch Pipe
          12-inch Pipe
          15-inch Pipe
          18-inch Pipe
          21-inch Pipe
          24-inch Pipe
          30-inch Pipe
          36-inch Pipe

Internal Inspection

          6-inch Pipe
          8-inch Pipe
          10-inch Pipe
          12-inch Pipe
          15-inch Pipe
          18-inch Pipe
          21-inch Pipe
          24-inch Pipe
          30-inch Pipe
          36-inch Pipe
     0.15-0.25
     0.15-0.30
     0.25-0.50
     0.25-0.50
     0.30-1.10
     0.25-0.90
     0.30-1.30
     0.35-1-70
     0.40-2.10
     0.50-2.25
     0.70-3.50
     0.80-4.25
     1.15-5.50
     1.45-6.80
     0.45-1.25
     0.35-1.20
     0.30-1.15
     0.30-1.20
     0.30-1.30
     0.35-1.40
     0.40-1.55
     0.50-1.75
     0.55-2.00
     0.75-2.20
                                 6-2

-------
                          TABLE 6-2




                PHYSICAL SURVEY COST CRITERIA
Size of study area



Access to manholes



Manhole opening



Manhole size



Manhole depth



Manhole condition



Hazardous gases in manholes



Cleanliness of manholes and sewers



Pipe size



Depth of flow



Flow rate



Weather conditions



Availability and cost of labor
                              6-3

-------
                         TABLE 6-3




              RAINFALL SIMULATION COST CRITERIA
Access to manholes



Manhole conditions



Hazardous gases in manholes



Cleanliness of manholes and sewers



Pipe size



Depth of flows



Plow rate



Availability of water



Random vs.  successive manhole sections



Weather conditions



Availability and cost of labor
                              6-4

-------
                          TABLE 6-4

                 SEWER CLEANING COST CRITERIA
Access to manholes

Manhole conditions

Type of manhole construction

Size of manholes

Depth of sewer

Depth of flow

Depth of deposition

Type of deposition

Pipe size

Structural condition of sewer

Length of manhole section

Intruding building sewers

Requirement for transportation and
disposal of material removed from the sewer

Distance to disposal site

Traffic  control requirement

Availability of water

Degree of root intrusion

Random vs. successive  manhole  section

Weather  condition

Mobilization distance

Availability and  cost  of  labor
                              6-5

-------
                          TABLE 6-5




              INTERNAL INSPECTION  COST  CRITERIA








Access to manholes




Length of manhole section




Manhole conditions




Hazardous gases in manholes




Depth of sewer




Depth of flow




Plow rate




Pipe size




Pipe cleanliness




Structural condition of sewer




Random vs.  successive manhole sections




Flooding conditions



Plugging requirements



Bypass requirements




Terrain




Traffic control requirement



Weather conditions




Documentation requirements



Report requirement




Mobilization distance




Availability and cost of labor
                             6-6

-------
   1,000
<§
.1
 s
 2

I
     100
      \o
\.Q
                           IT) ID f— OOO3
                                                         >
                                              c^  ^ in CD r* GO en
                                                                  CM   CO  *t LO CD f-» ODCD
                                  10                      100

                                  Length of Gravity Sewer,  Miles
                                                                       1,000  2,000
                    Figure 6-1.  Total Evaluation Survey Cost vs  Sewer Length
                                          6-7

-------
IU.WUU —
8
7
6

R

4
3


2-




1,000 -
8
c* ^
ll C
MK
-i .,
3 '
(0
G 2
\j
X
2
100 —
 •






















-- _





	 :.: : : : z
1
^ j
:. : :: |


' '
r
5
" i

.















* in to r- eocn
1.0


























'
. '
	 _i... - 1
__^ Si i : : ji : :





	 1 	 r -





















CNJ n -)






















' " ' ^
••jii: • i -

i ' ^
, ? '

_ j _ _ . . ]. —


























f _n co ' — eo 01
10














1

J
_ u. -
-, r - - - • • "

,___ _. . _ | I _
21 C. 	 	 3 * ' ' '


s1*






























CM CO -«f











-


I 1
*-- = = : :: j ! 	
_::iji!::
^B -
j
,
	 , t 	 	


































U~) CO r~^ CD O)
100
















































































































                                                                            10,000
                                                                             ,000
                                                                            100
                                                                             1.0
                           Peak  Infiltration/Inflow,  mgd





Figure 6-2. Total Evaluation Survey Cost  vs.  Peak Infiltration/Inflow
                             6-8

-------
    10,000
     I ,000
3
I
 o
 o
       100
       1.0
1.0
                               Ejj!
IT3 (D r— DO Ol
       10
                                           CN   co •^•lOCDr—oOCT)
                                                            100
                               Sewered  Population,  Thousand Persons
in to r*~ GOO)
      ,000
                Figure 6-3. Total  Evaluation Survey Cost vs.  Sewered Population
                                           6-9

-------
    10,000
I
 g
I
     1,000
100
       10
9
a
/
<•

5

.i

3








9
ti

B

i
4
3




2




r;


4
3 •









8
7

b


4
3







0.






































f



s



/















1


































	 H .
*
h 	 i
P p — - : i '



£
yj


~7
















Csj CO "






















« *




A- ! _ - 1
	 	 -5*--a -ill

22 '
/^. 3 «5
^ /^
.....,!. r^_ 	 ,....
-: jif ::; ! :
' , r











= : : : : : 	 =: - = : = : ; i







h - •• 	 	 - • •






uiniDr-^cooi csj  CN ro^
10







-

































	 t .











	 	








!• If) CO r— COOT
100






























































































































                                                                                  10,000
                                          Sewage Flew, mgd





                     Figure 6-4. Total Evaluation Survey Cost vs. Sewage Flow



                                        6-10
                                                                                  1,000
100
                                                                                   10
                                                                                         1,0

-------
J!
 8
wu iT
8
7
6

5

1
3
9




000 q-
8
7



5
4
3


2



100 —
5
a
7
6


4
3







IU9
8
7
6
c

4
3


2




1 0 -

























































,0




























































































































































•

	 ,IU

:i^i?: :: :?
	 . _i i. _
j i —
p
^





o*» en "«r






= = : = :::;:::_

































1 ' ^
, •
,''" \£
_ ;i ._ : z
_ j — ...!!. —
f
L
7
c _ _ — . . .... —






V


in to r— cool
10







































t

s
~




*

















































'

^





















































^

^

x












































— 	 •• -


-----:.:::-
r 1 1 1 illfiH
--__!.... «
. , ? ... '. .
> |
i 1 '
Ii .!;ii:.
" rf'
/ '
•













CN r*) ^r

	 -_


























— ------ • • — j
	 	 i —
. . !
' x*
'
£. i
. _ j - j ,1 : .

. t-



















If5 to r— CO CT>
00




























t

s


_, ^


















































,

^



^


















































^

^
'





















































'

ji
-------
IU.UUV —
B
7
R



4
3
2-




1,000-
8

6

5
8 4
3
^^-
*rt-

, 2
•K.
8
(S
X 100 -
9> 9
^ H
3 ^
 • L


MM : : i*--i-2?: :: :
	 -. ' ' 	 ~'*~
1 ^
j ' r
— — - - , — — 	 _
— - ^ _ . . — — 	 _ _

i



;_ - . L .. .

in to r- COOT c-j en ^























~2_


» •

:::::: i -5--i::!!!: ::


; 2 	 ::::; !

.. , 	
• r

_ . .


	 — . 	





	 - L " ' 	






» in us r-
-------
     10,000
§
 0
 u
      1,000
        100
         10
        1.0
9
7
6
r.

4
3






0
8
7
b

5
4
3



2




ft
7
6


4
a







9
B
7

6


4
3

9





i
























































0


























































































1
























~; :i::: :: ~


EEEEE!; =


































::•::: .,.j

jjjjjjjjjii
E::ji!!::i '
| '
F
r
2
= 3 •;• 1 ; •;; C
«. 	 ...|. _




»


CNi ft ^

































	 .--.,>._

'.'.',':'.' -j
t
-
' i1 ' '
.a^! 	 L_
;j!.::;i:
:._<•: 	














in to r^> CD en
10


































,/
E








*













































/



-



















































^
^





















































^
5
i — a " - -
k_ j C .. - .
C 	 ;

Z.I




















rsi tr

























f
'


... ^ 	 	
| *•
r
























^ in CD r*-












=








£
t
t

/
/'

... "~



























CO CD
100
























>
^

X





















































X
r


r*^































::::: :::


Eii:i; E
___^ t ^

,
r
	 t


jjijjj :




-?:: ii

'
1
. '
_ ~4. -
^

i " S






























cvj m -^

:::::-















E 	 . . 	






































m tc »-* coos
,00
























































0


















































































































10,000
 ,000
 100
 10
 1.0
                                 Sewered Population,  Thousand Persons
                        Figure 6-7.  Physical Survey Cost vs. Sewered Population
                                           6-13

-------
      10,000
Jl
8
       1,000
         100
         10
'i
B
I
B
5
.1
3
2
a
.(
B
5
4
,1
2
g
8
/
6
5
4
3

g
B
b
5
i
1 -





0.




































I
/•




/







































^



/





































-1



^


7






































•


,



































•





•
~ 2 - - - "
- --i
	 3 i ~
	 | ".

^
f

— -4 — — •- -
2 	





i































f

m
WT\


., . . .







































'

#











































>\

HI!














(xi r> f in 
-------
     10,000
s
•*-.

i

       ,000
         1.0
            1.0
10
                                                                                1,000   2,000
                                     Length of Gravity Sewer,  Miles





                         Figure 6-9.  Rainfall Simulation Cost vs. Sewer Length
                                          6-15

-------
IU,UUU —
B
7



4
3





1,000 -
8
7




§5
4
. .0 q
\F t J

•
•».

O
o
g
100 —
« 8
.^ B
lf\ R
>')
— 4
5 3
c

-^
-5J -
ttr *



10 9
7
6


4
3 '


2 .




1 0 -
0

























































1
































































































1


















CM 0 •»











































-,.!.: ! '
==!!; ;;;*
r
g j|
! = :-: : :g
1 Iml

2






in to f~~ co o>
1.0










































g«

^*^


2




















































i



?







•









































^

^ •


= ?!?! = ':;*

i











CN c^ ^






























:::::::i ~






f "
t
1 [
-
i * ^
^ '
^ - 	













IO CD '"^ CD OT
10

































r

,




£




















































'

















































,





























































_ . 	 	 — 1
:: 	 gl "_

i * 	 - -

. * *

' t '





illllllllll i


-- 	 ~-
r








"NJ n ^t i


























( '
1
y '

l-iili!! =




« *









_ 	 	

-:: :: t =
1 I [•llllijILJ








T co r^1 ooo5
100














































































































































































                                                                        10,000
                        Peok /nf»Itration/lnflav, mgd




Figure 6-/0. Rainfall Simula*ion Cost vs. Peak Infiltration/Inflow





                        6-16
                                                                        1,000
                                                                        100

-------
    10,000
     I ,000
o
>«.
c
      too
       1.0
a
B
1



4
3






B
8
b

5
4
3


2




9
7
B


4
3







9
g
7
6


4
J
7





1












































f
\S

,•
'




0









































•

.
ft

,-
















































+

X1


/














































0
( ' r '
- - .......... ^
	 	 . . ! j 1. . .
. 0 E . ... .£.
1 	 , : '

i '





i


CM P> *



	 , 	

-EEE;;;; =
	 F —


:":::::: [






















• f



( . '
'
* ^
( i '
ri ' ' i tf^
ffmffli
2 ~ "










in to r— eocn
10


































r


s

















































<


p
'

X















































pf

•


















































— :?::
-, 	 •
- j I j -
f
* -- -

^ n
X *














Cv| (*




























• • - — - " K 	
*
..,, _-.
f *
'.', **'
.-.•^t- ---
it 	 .



















> ** in to r»

























/


• ?
i .



. _



















men
100




























X



-W





















































p*








































	 	 _ 4
r

P



x
3 - -



^ • - "





















N


















^
• h —
. . . _____




2'
;;i!! -
•


	 ~ ; 	
• '






















n «/ in CD













- - r~"
: : -






































r- oocn
I,OC





















































«)












































































































                               Sewered Population,  Thousand Persons



                  Figure 6-11.  Rainfall Simulation Cost  /s.  Sewered Population
                                       6-17

-------
     10,000
to
1
      ,000
       100
        10
       I .0
g
7
6


.;
1







8



5
4
1



2



B
a
7
6


4
3







8
1
6


4
3








0.










































f •*



S-




/
f


\










































•







f


















































4


t







MM HHJIFfF



























= ::::::::: =
	 '•-•T~


--:--" :: =
' 1 11 ill Hr
	 . • f —





B «i
• ^
_ a 	 . j c
1 4 limn
I
0
r
— Z3
y -







CNI m -«f
[III [IIIIIIP

































	 	 —
1 x

. - p*
' (^
x"" C
K 1 ' [ r^
- j«?. .. . L_




, 	 - . .. 	





,


in to f^ COCTI
.0
































•




/


'



















































X


/












































::::::: [I]/



•. ^
_ _ _
i*. . . ,

i
X
'







tr ||||H|ffj
	 -- —







CNJ O •*
1 1 1 1 1 1 1- 1 : =























V?

__ f . .
zE;!;i: :: ^
;.j 81 :
— 1 1 < '
, i - -. •--:














	 	 i- —
	 . —
::;::::::-







to CD r— 03 en
0























J



!







































































































1 1 -i : :





^ '
/

— ^ • - - -


























CN r
















.... 	






.





















rrr \\\~ - - " • \-
	








ry *$ in to r^-























































CDO3
100








































































































































































10,000
I ,000
100
                                                                                          .0
                                          Setrage F/ow, mgd

                       F/gure 6-/2.   Rainfall Simulation Cost  vs.  Sewage Flow
                                        6-18

-------
     10,000
 LO
a
 g
 o
o
 0
I
      I ,000
10,000
 ,000
 100
                                                                                           10
                                                                                           1.0
                                                                                1,000   2,000

                                     Length of Gravity Sewer,  Miles


                        Figure 6-13.  Preparatory Cleaning Cost vs. Sewer  Length
                                          6-19

-------
10,000
 1,000
   100
   10
       O.I
                        u~3 to r— cooi

                                              ~s
                                          n  -^t  tn ID r— co o
                                                                       10 CD p** oo o^
1.0
10
                                                                              100
                                    Peak Infiltration/Inflow,  mgd




        Figure  6-14.  Preparatory Cleaning Cost vs. Peak  Infiltration/Inflow
                                                         10,000
                                                                                        I ,000
                                                         100
                                                                                         .0
                                     6-20

-------
lUfUVU 	
8

5

5

4
3
7




1,000 g-
e
6
§r
J
4
** 3
•
•»-

8n
2
o

Of
i '°° 9
J 8
O7
B
B
i1 r.
V» J
4
1
Q.
0)
V. ,
Q.



10 —
9
8

6


4
3

2



1 0 -


































































































































































__ £_. . -.,

j * y'
> - J ' ' '
4 *
	 £ 	 	








. _ - .





- . . — _





-

J 	 _ . 	
- - 	








































r in to r- coo?




















































































































.0
                 0
100
                                                            1,000
                                                                     i.o
              Sewered Population, Thousand Persons
Figure 6-15.  Preparatory Cleaning Cost /s. Sewered Population
                      6-21

-------
      10,000
§
QJ
8.
      1,000
100
        I .0
',
B
7
B

"
'.
3-








B




J
4
1



.









'




















































1


























































•
• ~ T L




-i" = :

. 1
j "
>
9
7



E::z!!
































OJ
: H 	 --














j 	 	 	
















































n rj in CD r-
;.^: —
;;; =
	 f- - — '
• - 4 —




























































- ODCJ)
100



































































































































































































                                           Sewage Flow,  mgd

                        Figure 6-16.   Preparatory Cleaning Cost  vs.  Sewage Flow
                                                                                          10,000
                                                                                          1,000
                                                                                          100
                                                                                          1.0
                                         6-22

-------
    10,000
8
o
-0)
"c
     1,000
       100
        10

e
T
R

•

4
3
o




H
i
7


5
4
3 j
'2
8
7
6
4
3
g
0
7
6
5
4
3
2
1
























































































































































- . .
---01-. .



. — f 	 ,







CN n -
,0





	
































, '
t
-•;• ^
1 i
c _ 	 	 , , , 	

















































1

X*

r



























1 1 1 1 1 1 1 nun


















h 	 	 	 .i-.
	 „ !. ....
— j * - -- i ' ' |
^* 4 ' '
( '
^ ? '
?
_^ ^

4












r
•














































«^



























	 _ . .


r . -














8rroTT





c • '
^ »
»






















rmtor-ooen 
-------
IU.UUU —
8
7
6
5
4
3
2
1,000 -
8
6
M- 3
%
**" 9
<§
•S 100 —
0 8
& ?
*
•— 4
Q
!
•»-
e
«Z 2
10 9
8
7 •
6
4 •
3 •
1
1 0 -
o













































































































































:




















CN c*3 ^4
1

































:: ::::::: : —
!• —
—

" ^

'
j|
	 _ f . . _ . 	
j V^
, (
M
" "" 2









































	 ._ 	 . ..




^


^2:::::: :












"kO
EEEiEi j j =




























1 1 IIIIIUJII^I

^t ' X

|::ji|:iF ^
— j'i — - >• [•
* ' • • •

•
' i



fl_









































3


v


































































































K" ( '
1


^? ' .' '
??!:;:;;;; 3

^
_^ 4 1 	 . . _ , -





















D°io

















^
= ::: ; •::::: —





1
'






























































































































































































tTJ CD f™* CD O5
100
                                                                          10,000
                                                                          I ,000
                                                                          100
                                                                          10
                                                                          1.0
                         Peak  Infiltration/Inflow,  mgd




Figure 6-18.  Internal  Inspection Cost vs. Peak  InfiItralion/In flow
                          6-24

-------
     10,000
s
•»-.

I
       ,000
100
!)
7
g

i,

4
.1


•}




y
i
b

5
4
1



'1




9
I
7
B


4
3


2,





8

6


4
3


T





1



























































.0
































































































































:: ::: : : z










-


















'
i * '
^ *
< * ' ^
V
_.-|(.!!!.. r
£ 	 i ' 1
	 	 	 ...
?
*

'









CN ra "*



















::::::: E i =














^s
::•;:!:: : 2

? g
I ' ^
^
^ i *

^ '
'
	 	 	


1











in CD r— COOT
10

































|

K*

z














































































































g<

-.r£.: ..j.i

^
* i »
^ _ . _ _z! . .
~ ^ t ~ ~























CM CO *t














- = ::: : : —





	 . ^




f
.' >
> 1
^ -- |l


	 ..^ 	 . 	
— 7


























10 co r— oO o>
100




















f




4



•























































^
















































~----. : : : ?
	


.
>
;
.. 1 . ,
~ ~ t


"

.
«• [
"'






























rsi n ^i



















( 	 . . . —

: :::: : [ ~





































r in co r- oocn
I.OOC



























































)
•



























































                                 Sewered Population, Thousand Persons




                    Figure 6-19.   Internal Inspection Cost vs. Sewered Population




                                         6-25

-------
o
s
e
      10,000
       1,000
         100
          10
         1.0


                                     ,
                                           r
                                 E£2


                                                             •
        C^   C^  ^(f LD (O r^« OO CT)


O.I                      1.0
                                                    ^  LT CO 1^" ^O O5
                                                                  -W
                                                                           TTT

                                                              10
^r U"} co f*** OD OT

         100
                                               Sewage Flow, MGD


                          Figure 6-20.   Internal  Inspection Cost vs. Sewage Flow
                                            6-26

-------
     10,000
3
o
                                                                              1000
                                                                                     2000
                                    Length of Gravity Sewer.  M//es



                           Figure 6-21.   Report Cost vs.  Sewer Length
                                        6-27

-------
10,000
 1,000
  100
   10
  1.0
8
H
7
B


4
'I







8



9
4
3



2




B
7
b


4
3








B
/

b


4
3


2





0




























































.1


































_ _ , - -

























CN O ^*











































•< ~* *
: ~ i i ; !! : :~~~

i ^
X '
0 r >
j * ,*
::: : E ; ! 	 r
";?? : : : 	 =








m CD *^ QDOI
1.0









































, '
0 <
-, l'.'
- !::"i:

^
^ '












c^ n ^





























	 . - L 	
	 	 f 	



_ |.
	 _ _ _ - , 	


f ^

'
. ' ' '
g '
-^i ' . ^
-... „ 1

















m ID r~- GO d
10







































•**
•























































— -*- - - j 1 11
-(»'--
i *
j W
t . '
„ » '
- r^"









	 : : f :








CM n ^





























	 . , . i — .
1

- '

----lt'l[ —

	 " - i • —
i •
i ^





















in to r— COOT
100


























































































































10,000
                                   Peak Infiltration/Inflow, mgd
               Figure 6-22.  Report Cost  ks.  Peak Infiltration/Inflow
                                   6-28
1,000
100
 10
                                                                                    1.0

-------
10,000 — r
y
8
6
e
"
4
3
0




1 ,000 r
8




5
4
3



2
*
Mfe

8 I0°,
2 '
t 6
a^ c
5
4
3







'°9
8
7
6

4
3


N
•




1










_- _ . -








	 	 ' '













mnlllf







-
1 1 JniT Urn

	 .i*. . .









.0





. . 	 I ! !












::: : : 	 ---.-.: : :









	 	 	 	



.

:5:: :;?.:::

^ > g

• ^ ^ ' • '
• ^ ^ • . • '
t * * i •"' '
__g!.. ^ » 	 ...
— , 	 , .. . - -











^ in to r-* coo o«j t^
10




























	 	 - ^



^ • rf£
-igi'!:: -
^^ i ^


,£ *
















•*f in CD r- cocn
100



























t

	 _ u I . . _
g *
^ ^






















CM CO























j
7*





























,000











-











































       Sewered Population,  Thousand Persons




Figure 6-23.   Report Cost  vs. Sewered Population
               6-29

-------
10,000
 1 ,000
   100
   10
  1.0
               CN   *"J   ^ IO tD f*~ CQ CTl
                                        C-*   rj  n  in to i
       O.I
                                                         10
r»)  ^  lT> CD f™" QOCT1
            100
                                         Sewage Flow,  VGD
                            Figure 6-24.  Report Cost i/s. Sewage Flow
                                       6-30
                       10,000
                       1,000
                       100
                       10
                                                                                             .0

-------
     •  Total sewered population

     •  Total sewage flow

These cost curves are derived from the  cost  estimates  included
in approximately thirty Infiltration/Inflow  Analysis reports
submitted to the ten EPA regional offices  for review in 1974-
1975 and represent the average costs  one would expect  in
conducting the Sewer System Evaluation  Survey.

However, because of the specific conditions  of each sewer
system, it is highly probable that the  costs developed from
other reliable sources for a particular sewer system are
completely off the aforementioned cost  curves.  Therefore,
these curves should be used only as a general guidance to
determine the reasonableness of the costs generated.

In each figure shown, the solid line is the  line of best fit
determined by the least square method for all the data points
plotted.  The dashed lines represent the 95% confidence limits
for the mean.

The cost curves shown in Figures 6-1 to 6-4  are the total
evaluation survey costs which include the costs for physical
survey, rainfall simulation, preparatory cleaning, internal
inspection and report preparation.  Due to the incompleteness
of the  cost data in some reports, the set of cost data used to
derive  these curves are not taken from exactly the same
number  of reports as those used to derive the curves  (Figures
6-5 to  6-24) for each individual phase of work.  One may find
that  the total evaluation survey costs taken  from the  cost
curves  shown in Figures 6-1 to  6-4, corresponding to each
parameter, do not necessarily equal the sum of the costs
required for the  five phases  of work, taken from the cost
curves  shown in Figures 6-5 to  6-24, corresponding to  the
same  parameter.   This  further points out the  importance  of
using these  cost  curves with  caution and the  need for  engineers
to  develop more accurate  costs  for each sewer system  under
investigation.

6.3  REHABILITATION COSTS

6.3.1  Sewer Replacement  Costs^

The cost  curve  for  replacing  the  existing gravity  sewer with
a new pipe  of  the same size  is  shown in Figure  6-25.   Included
 in the costs  are  the costs  for  site preparation,  excavation,
 backfill,  pavement, pipe  materials, removal of  existing pipe,
pipe installation^  reconnection of one  house service  connec-
 tion for every  20 feet of pipe  and field  inspection.   In
                             6-31

-------
10
                                     30
                   10
40   50  60  70 80 90 100
                     Pipe Size, Inches
    Figure 6-25.   Sewer Replacement Cost vs. Pipe Size
                      6-32

-------
deriving the cost curve,  it was assumed that  the  depth of
cover over the crown of the pipe is 9 feet, the pipe  is laid
in moderately wet soil conditions,  the excavations  are limited
to earth excavations and the cost required to remove  the
existing pipe is 50/5 of that required to install  the  new pipe.
The cost required for sewage bypassing during construction is
not included.

For preliminary estimations, this curve should be sufficient
in most applications.  For more detailed cost estimations,
which may be required in the Sewer System Evaluation  Survey,
individual costs should be developed based on the actual
field conditions.  Factors which may affect the cost  for
sewer replacement are shown in Table 6-6.

6.3-2  Pipe Lining (Polyethylene) Costs

The cost curve for pipe lining with polyethylene  pipe is
shown in Figure 6-26.  Included in the costs  are  the  costs
for site preparation, insertion pit, pipe materials,  pipe
welding, pipe installation, connection of one house service
connection for every 20 feet of pipe, pipe sealing off in
manholes and mobilization.  It was assumed that the depth
of cover over the crown of the sewer is 9 feet.

Factors which may affect the pipe  lining  cost are shown in
Table 6-7-  They should be considered in  developing more
refined cost data for the  studies.

6.3.3   Grouting Costs

The  costs  for chemical grouting  of sewer  pipes are shown  in
Figure  6-27.  The costs are developed based  on the following
assumptions  [9]:

      (a)   Length of  manhole section:   300 ft
      (b)   Type  of pipe:  Vitrified clay
      (c)   Depth  of  flow:   Less  than  2Q%  of pipe  diameter
      (d)   Type  of joint:   Factory  made
      (e)   Joint  spacing:   4 feet
      (f)   Access to  manholes:   Readily  accessible
      (g)   Manhole opening:  21 inches
      (h)   Manhole diameter:   4 feet
      (i)   Manhole condition:   Structurally sound with steps
                               for  access
      (J)   Manhole depths:   6-8 feet
      (k)   Hazardous  gas:   None present
      (1)   Random vs. successive manhole sections:  All sections
             requiring grouting are successive
      (m)   Mobilization distance:  Within 100 miles
      (n)   Weather  conditions:   Mild temperature  and  no storm
      (o)   Traffic  control:  None required
      (p)   Chemical  grout  used:  Acrylamide gel or urethane foam


                             6-33

-------
                          TABLE 6-6

               SEWER REPLACEMENT COST CRITERIA
Size of pipe

Depth of pipe

Type of service

Type of pipe

Removal of existing pipe

Number of service connections to be made

Groundwater elevation

Proximity to other utilities

Pipe transportation requirements

Infiltration allowance requirements

Access to site work

Availability of storage area for pipe materials
and equipment

Availability of storage area for excavated materials

Weather conditions

Availability and cost of labor
                             6-34

-------
5  6  7
                                                60 70 80 90 100
                     Pipe Size,  Inches
Figure 6-26.  Pipe Lining (Polyethylene) Cost
                                                 .  Pipe Size
                   6-35

-------
                          TABLE 6-7

                  PIPE LINING COST CRITERIA
Size of sewer

Length of sewer

Depth of sewer

Grade and direction change of sewer

Depth of flow in sewer

Size of liner pipe

Liner pipe wall thickness required

Annulus grouting requirements

Number of service connections to be made

Type of surface restoration required

Pipe transportation requirements

Type of manhole "seals" required

Extent of sewer cleaning required

Technique to "prove" or preinspect sewer lines

Excavation requirements

Groundwater elevation

Access to site of work

Availability of electrical power for fusing

Availability of storage area for pipe materials
and equipment

Availability of storage area for excavated materials

Mobilization distance

Availability and cost of labor
                             6-36

-------
4000
               10
20
30
70   75
                                Number of  Joints  Grouted




              Figure 6-27.   Grouting Cost  vs.  Number of Pipe Joints Grouted
                                  6-37

-------
                          TABLE  6-8




               SEWER  LINE GROUTING  COST  CRITERIA
Mobilization distance



Weather condition



Terrain



Type of soil



Access to manholes



Manhole opening




Manhole size



Manhole cleanliness



Manhole depth



Hazardous gases in manhole



Type of pipe



Pipe size



Pipe alignment



Pipe grade



Pipe cleanliness




Depth of flow



Flow rate



Ability to plug



Type of joint



Joint spacing




Offset  joints



Intruding service connections



Structurally damaged pipe



Random vs. successive manhole sections



Availability and cost of labor







                             6-38

-------
            TABLE 6-9




MISCELLANEOUS REHABILITATION COSTS
Item
Manhole Replacement
Manhole Repair
Raise Manhole Frame & Cover
Manhole Cover Replacement
House Service Pipe Replacement
House Service Pipe Repair
Roof Leader Drain Disconnection
Foundation Drain Disconnection
Cellar Drain Disconnection
Area Drain Disconnection
Cross Connection Plugging
Drains From Springs Plugging
Unit
each
each
each
each
each
each
each
each
each
each
each
each
Cost, $/Unit
500-1,000
50-500
100-150
50-100
600-1,200
200-400
50-75
300-1,200
50-350
50-350
100-500
500-2,500
                6-39

-------

-------
                         APPENDIX A

                         REFERENCES
1.  "Sewer System Evaluation for Infiltration/Inflow."   Prepared
    for the United States Environmental Protection Agency
    Technology Transfer Program, American Consulting Services,
    Inc., Minneapolis,  Minnesota.

2.  Wilson, J. P., Jr., "Fluorometric Procedures for Dye
    Tracing."  In "Applications of Hydraulics",  Chapter A12,
    Book 3) Techniques  of Water-Resources Investigations of
    the United States Geological Survey, U.S.  Government
    Printing Office, Washington, D.C. (1968).

3.  "Floating Bowl Hypochlorite Solution Feeder."  AID-UNC/
    IPSED Series Item No. 9, G. V. R. Marais and F. E.
    McJunkin (ed.), International Program in Sanitary
    Engineering Design (IPSED), University of North Carolina,
    Chapel Hill, N.C. (October, 1966).

4.  "Floating Platform Hypochlorite Solution Feeder."  AID-UNC/
    IPSED Series Item No. 7, G.V.R. Marais and F. E. McJunkin
    (ed.), International Program in Sanitary Engineering
    Design (IPSED), University of North Carolina, Chapel Hill,
    N.C.  (October, 1966).

5.  "Safety Manual."  The Penetryn System, Inc., Winter Park,
    Florida.

6.  "Cost-Effectiveness Analysis Guidelines."  Federal Register
    40 CFR 35 (February 11, 1974).

7.  "Guidance for Preparing a Facility  Plan."  U.S.
    Environmental Protection Agency, Washington, D.C.  (Revised -
    May  1975).

8.  Farmer, H.,  personal  communication  (1975).

9.  "Preliminary Report  for a Manual  of Practice."  The Sewer
    Rehabilitation  Subcommittee, Technical Advisory Committee,
    American  Public Works Association  (1975) .

10. "AM-9 Chemical  Grout."  American Cyanamid Company,  Wayne,
    New  Jersey  (1965)•

11. "AM-9 Chemical  Grout  Mix Calculation."  American Cyanamid
    Company,  Wayne,  New  Jersey.
                              A-l

-------
12. "3M Brand Elastomeric Sewer Grouting Compound."  Specifica-
    tion Sheet, 3M Company, Saint Paul, Minnesota.

13. Anonym., "Lateral Connections with Inserted Polyethylene
    Piping."  Water & Sewage Works, 122, 3, 66-67 (March,
    1975).

14. Farmer, H., "Sewer System Evaluation and Rehabilitation
    Cost Estimates."  Water & Sewage Works.  Reference
    Number, R8-R9 (April, 1975).

15. "Procedural Guidance for 197^ Survey of Needs for Municipal
    Wastewater Treatment Facilities."  U.S. Environmental
    Protection Agency, Washington, D.C. (May, 197*0.

16. "Building Construction Cost Data."  R.  S. Means Co.,  Inc.,
    Duxbury, Mass. (197*0 .

17. "Costs of Wastewater Treatment by Land  Application."
    Office of Water Program Operations, U.S.  Environmental
    Protection Agency.  Technical Bulletin, EPA-^30/9-75-003
    (June, 1975).
                             A-2

-------
                         APPENDIX B

                     STATE CERTIFICATION
The U.S. Environmental Protection Agency has granted
authorization to the States to certify if excessive
Infiltration/inflow does or does not exist in a sewer
system tributary to a treatment works.  The States have
the prerogative to undertake this authorization if they
desire.

The State certification information is documented in the
Rules and Regulations of 40 CFR 35 Section 35-527-5.  This
Section states that "the Regional Administrator will deter-
mine that excessive Infiltration/inflow does not exist, on
the basis of State certification, if he finds that the
State had adequately established the basis for its certifi-
cation through submission of only the minimum information
necessary to enable a judgment to be made.  Such information
could include a preliminary review by the applicant or
State, for example of such parameters as per capita design
flow, ratio of flow to design flow, flow records or flow
estimates, bypasses or overflows, or  summary analysis of
hydrological, geographical and geological data, but this
review would not usually be equivalent to a complete infil-
tration/Inflow analysis.  State certification must be on a
project-by-project basis.  If the Regional Administrator
determines on the basis of State certification that the
treatment works is or may be  subject  to excessive infiltra-
tion/inflow, no Step  2 or Step 3 grant assistance may be
awarded except as provided in paragraph  (c) of this section."

Section (c) indicates that the applicant may receive grant
assistance if it  is established that  the treatment works
will  not  be significantly changed by  subsequent rehabilita-
tion.   The grant  may  be conditioned such that resulting
rehabilitation be performed over some suitable implementation
program.

The  State certification program  is  Intended to hasten  the
process of fulfilling the  infiltration/inflow requirements
of PL 92-500.  Generally,  State  regulatory  personnel  are
more  familiar with  the  projects  applying for grant  assistance
and  thus  a review of  minimal  data  on  a sewer system can
provide sufficient  information In  which to  make  a judgment
on excessive  or  nonexcessive  infiltration/inflow.
                              B-l

-------
State certification is not limited to applicants who provide
minimal information on sewer systems but also applies to
the complete structured infiltration/inflow analysis.  In
addition, State certification may be established on both
nonexcessive and possibly excessive infiltration/inflow in
sewer systems.  In any event, EPA must issue the final approval
of the infiltration/inflow requirements.  As a result, EPA
may provide a cursory or substantial review of the presented
data and/or report.  It is expected that in the first years
of the Sewer System Evaluation Program these EPA reviews
of State certified data or reports will be substantial in
view of the fact that all parties involved are developing
experience in this previously neglected area of planning.
As time passes, it is probable that State certification of
projects will receive reduced EPA review.

Currently, those States that are providing certification
of infiltration/inflow data and/or reports do so by review-
ing the data, working closely with those who prepared the
data and then make a judgment on whether possibly excessive
or nonexcessive infiltration/inflow exists.  The States then
submit the data and/or report to EPA with a certifying
letter.  The certifying letter generally contains statements
which indicate the following when possibly excessive infil-
tration/Inflow exists:

        The treatment works for which the grant application
        is made will not be changed by any rehabilitation
        program and will be a component part of any re-
        habilitation program.

        The grant applicant has assured that the sewer system
        evaluation will be completed.

        Any resulting rehabilitation program will be con-
        ducted on a schedule consistent with treatment works
        construction and satisfactory to the Regional
        Administrator.

EPA encourages the States to adopt a certification program.
Cooperation among EPA, the State and the grant applicant
will result in a workable program.
                             B-2

-------
                         APPENDIX C

                      GLOSSARY OP TERMS
1.   Combined Sewer

    A sewer intended to serve  as  a sanitary  sewer  and  a storm
    sewer, or as an industrial sewer and a storm sewer.

2.   Excessive Infiltration/Inflow

    The quantities of infiltration/inflow which can be
    economically eliminated from  a sewer system by rehabilita-
    tion, as determined by cost-effectiveness  analysis that
    compares the costs for correcting the infiltration/inflow
    conditions with the total  costs for transportation and
    treatment of the infiltration/inflow.

3.   Infiltration

    The water entering a sewer system and service connections
    from the ground, through such means as,  but not limited
    to, defective pipes, pipe  joints, connections, or
    manhole walls.  Infiltration does not include, and is
    distinguished from, inflow.

4.  Infiltration/Inflow

    The total quantity of water from both infiltration and
    inflow without distinguishing the source.

5.  Infiltration/Inflow Analysis

    An engineering and, if appropriate, an economic analysis
    demonstrating possibly excessive or nonexcessive
    infiltration/inflow.

6.  Inflow

    The water discharged  into  a  sewer system,  including  service
    connections,  from such sources,  as  but not  limited to,
    roof  leaders, cellar, yard and  area drains, foundation
    drains,  cooling  water discharges, drains  from springs
    and  swampy  areas,  manhole  covers, cross connections
    from  storm  sewers  and combined  sewers, catch  basins,
    storm waters, surface run-off,  street wash waters, or
    drainage.   Inflow does not include,  and is distinguished
    from,  Infiltration.
                              C-l

-------
7.  Internal Inspection

    An activity of the Sewer System Evaluation Survey.  This
    activity involves inspecting sewer lines that have pre-
    viously been cleaned.  Inspection may be accomplished by
    physical, photographic and/or television methods.

8.  Physical Survey

    An activity of the Sewer System Evaluation Survey.  This
    activity involves determining specific flow character-
    istics, groundwater levels and physical condition  of
    the sewer system that had previously been determined to
    contain possibly excessive infiltration/inflow.

9.  Preparatory Cleaning

    An activity of the Sewer System Evaluation Survey.  This
    activity involves adequate cleaning of sewer lines prior
    to inspection.   These sewers were previously identified
    as potential sections of excessive infiltration/inflow.

10. Rainfall Simulation

    An activity of the Sewer System Evaluation Survey.  This
    activity involves determining the impact of rainfall
    and/or runoff on the sewer system.  Rainfall Simulation
    may include dyed water or water flooding of storm  sewer
    sections, ponding areas, stream sections and ditches.
    In addition, other techniques such as smoke testing and
    water sprinkling may be utilized.

11. Rehabilitation

    Repair work on sewer lines,  manholes and other sewer
    system appurtenances that have been determined to  contain
    excessive infiltration/inflow.  The repair work may involve
    grouting of sewer pipe joints or defects, sewer pipe re-
    lining, sewer pipe replacement and various repairs or
    replacement of other sewer system appurtenances.

12. Sanitary Sewer

    A sewer intended to carry only sanitary and industrial
    wastewaters from residences, commercial buildings,
    industrial plants and institutions.
                             C-2

-------
13•  Sewer System Evaluation Survey

    A systematic examination of the tributary sewer systems
    or subsections of the tributary sewer systems that have
    demonstrated possibly excessive infiltration/inflow.
    The examination will determine the location,  flow rate
    and cost of correction for each definable element of  the
    total infiltration/inflow problem.

1*J.  Storm Sewer

    A sewer intended to carry only storm waters,  surface
    run-off, street wash waters, and drainage.
                              C-3

-------
        APPENDIX D




METRIC CONVERSION  TABLE
English Unit
Cubic feet per minute
Degree Fahrenheit
Feet
Gallons
Gallons per capita
per day
Gallons per day
Ga liana per day per
inch-nile
Gallons per minute
Inches
Hi lea
Million gallon* per day
Pounds
Pounds per cubic feet
Pounds per gallon
Pound* per square Inch
Abbievlation
cu ft/nin
•r
ft
s»i
gpcd
gpd
gpd/ln-mile
gP»
In.
ml
»gd
Ibs
Utt/cu ft
Ibs /gal
P«l
Multiplier
0.0283
0.555 (°P-32)
0.305
0.0038
0.0038
0.0038
0.0009
0.0038
2.54
1.61
0.0038
0.454
16.02
0.12
70.31
Abbreviation
cu a/mln
•c
9
Cu Dl
cu n/capita/day
cu m/day
cu B/day /en km.
cu rn/nin
Cl
ka
million cu B/day
kg
kg/cu B
gB/CC
ga/sq cm
Metric Unit
Coble meters per minute
Degree Celsius
Meters
Cubic meter
Cubic secera per capita per dt*y
Cubic Betera per day
Cubic meters per day per
centlmeter-kiloineter
Cubic meters per minute
Centimeters
Kilometers
Million cubic meters per day
Kilograms
Kilograms per cubic meter
Uraoa per cubic centimeter
Grama per square centimeter
                            •} U S GOVERNMENT PRINTING OFFICE 1976-677-876 300 REGION NO 8
              D-l

-------