EPA
        United States
        Environmental Protection
        Agency
         Region 1
         J.F.Kennedy Building
         Boston, Mass. 02203
EPA
Environmental   Final
Impact Statement

Local Wastewater
Management
Program
N. Branford,
Connecticut

-------
                        FINAL

           ENVIRONMENTAL IMPACT STATEMENT


         LOCAL WASTEWATER MANAGEMENT PROGRAM

             NORTH  BRANFORD,  CONNECTICUT
This  Final Environmental  Impact Statement  evaluates
wastewater collection and treatment alternatives  for
North Branford.   The  major recommendation  is  for  a
limited  sewer  system  to serve  the  Foxon  area  of the
community.

Further  information on this statement  can  be  provided by:

           Mr.  Robert  Mendoza
           Environmental Protection Agency
           Environmental and Economic Impact Office
           J. F. Kennedy Federal Building
           Boston, Massachusetts 02203

           617-223-4635
                    -LEAD AGENCY-

       U.S. ENVIRONMENTAL PROTECTION AGENCY
                     Region  I
               JFK  Federal Building
           Boston,  Massachusetts   02203
               Technical Consultant

           Anderson-Nichols & Co., Inc.
               Boston, Massachusetts
Approved by
William R. Adams, Jr.
Regional Administrator
Fdnal Date by Which
Comments on the Final
Environmental Protection Agency    Must be Received
Region I

-------
                       TABLE OF CONTENTS




                                                     PAGE



SECTION 1.0 SUMMARY
1.1.
1.2
1.3
1.4
1.5
SECTION
2.1
2.2
2.3

2.4
2.5
2.6
SECTION
3.1
3.2
3.3
Overview
EIS Background
EIS Process and Objectives
Final Report Context •
EIS Recommendations
2.0 EIS FOXON RECOMMENDATIONS,
Specifics
Interceptor Route
Development Capability/Capacity of the
System
Lateral Funding
Sewer System Impacts
Conclusions
3.0 EIS COMMENTS/RESPONSES
Introduction
Thomas Quamma/ Northford Resident
State Preservation Officer, Advisory
1
1
2
2
3

5
7

8
11
15
20

23
23

         Council on Historic Preservation             23



3.4      Connecticut Department of Environmental



         Protection                                   24



3.5      United States Department of the Interior     25



3.6      Connecticut Office of Policy and Management  26

-------
                        LIST OF FIGURES
NUMBER
  1
  2
  3
  Area Relationships
  Project Details
  Potential Sewer Service Area
PAGE
 4
 6
 10
                        LIST OF TABLES
  1
  2
  3
  Present Worth Cost Analysis           13
  Annual Cost to Homeowners             14
  Average Annual Stormwater Runoff
  Concentrations of Pollutant Parame-
  ters                                  17
  Induced Growth and Population
  Distribution 1980-2000                19
APPENDIX  A
APPENDIX  B
APPENDIX  C
WRITTEN COMMENTS ON DRAFT EIS
PUBLIC HEARING TRANSCRIPT
ARCHEOLOGICAL RESEARCH REPORT
CONSULTATION WITH STATE HISTORIC PRE-
SERVATION OFFICER

-------
               SECTION 1.0



            FINAL EIS SUMMARY
This chapter summarizes the EIS process and
documents the recommendations of the Final
EIS.

-------
Section 1.0  FINAL EIS SUMMARY

1.1  Overview

     This document is the Final Environmental Impact Statement
     (EIS) for the North Branford, Connecticut Local Wastewater
     Management Program.  In March 1979, a Draft EIS (DEIS) was
     distributed to various government agencies and interested
     individuals which detailed the complete impact evaluation
     process and presented the EIS recommendations.  From the
     data of publication until June 4th the public has had an
     opportunity to submit written comments to EPA regarding
     the DEIS.  On May 9th, after a suitable opportunity for
     review of the DEIS, a public hearing was held in North
     Branford to receive additional comments.  This final EIS
     responds to all. the comments that have been received and
     clarifies points which may not have been fully understood
     regarding the project's conclusions.  This final EIS and
     the DEIS together represent the public record of the
     project's assumptions, analysis, and decision making.

1.2  EIS Background

     The EIS project was initiated in North Branford when the
     Town applied to the Connecticut Department of Environmental
     Protection (DEP) and the Federal Environmental Protection
     Agency (EPA)  in 1977 for funds to construct three sewer
     systems in several areas of the community.  Two of the
     systems were approved by these agencies while the third
     system prompted a number of questions regarding funding
     program guidelines and the environmental impact require-
     ments of the National Environmental Policy Act (NEPA), the
     law under which the program must operate.  The sewer
     system in Section A of the Town's sewerage plan was
     approved and construction began in the summer of 1978.
     This system serves the southeastern part of North Branford
     and conveys the wastewater to Branford for treatment.  The
     initial sewer system for Section C, the northwest corner
     of the Northford part of town, was approved for funding
     and will be constructed soon.

     The initial sewer system that was planned for Section B,
     the southwest portion of town called Fdxon, created some
     concern among both the state and federal agencies and
     local residents.  Some of the concerns included:

          — the sewer 'system would be within the basin of the
             Farm River, the source of a surface drinking water
             supply system.
                               - 1 -

-------
          — state policy discourages sewering within water
             supply watersheds.

          — the sewer program, especially the long range plan,
             might encourage development within the watershed
             which would threaten water quality.

          — an extensive long range sewer system within the
             Farm River Valley might induce irrevocable change
             in current agricultural land use.

          — an extensive sewer system might not be needed to
             solve the areas with septic system problems within
             the valley.

     EIS is the vehicle by which EPA analyzes the project in
     question, invites public participation, and makes specific
     recommendations as to the agency's participation in the
     final project.

1.3  EIS Process and Objectives

     The federally funded EIS program provided the opportunity
     for the Town to have its proposal thoroughly reviewed by a
     specialized EIS project team while EPA fulfilled its legal
     responsibility under NEPA.  The EIS process provided for a
     continuing public information program through a newsletter
     series, and a continuing public participation program
     through a workshop series which spanned the duration of
     the project.  The process also provided for an in-depth
     local water quality sampling program and several field
     surveys of local neighborhood conditions of wastewater
     disposal.  The objective of the EIS project was

               to determine if local wastewaterproblems

               warranted federal participation in a funded

               program and to insure that the project would

               be both cost-effective and environmentally sound.

1.4  Final Report Context

     This report contains a number of diverse sections which
     are briefly described here.  Following this sub-section,
     there is a general discussion of EIS recommendations-which
     points out that a specific recommendation is made for the
     Foxon area only while additional study will be needed to
     find solutions for wastewater disposal problems from
     existing development elsewhere in town.
                               - 2 -

-------
     The Foxon recommendation is described in detail in Section
     2 so that all parties will have a clear idea of what is
     actually involved in the EIS recommendation.  A more
     thorough explanation of this recommendation will address
     the major questions that were raised by EIS reviewers.

     Section 3.0 contains EIS responses to comments received.
     Appendix A is all of the actual responses received.  The
     verbatim record of the public hearing that was held in
     May is Appendix B.

1.5  EIS Recommendations

     The North Branford EIS recommends:

          — construction of a limited ponventional gravity
             sewer system to serve existing problem users  (and
             a limited amount of undeveloped intervening land)
             in the Foxon area with connection to the East
             Haven sewer system for treatment.

          — continued and long term reliance on septic system
             use in the Farm River Valley in general.

          — additional studies should be conducted to analyze
             possible small scale community sewer systems or
             septic system rehabilitation programs in existing
             problem areas in the Green Acres area and in the
             Middle and Upper Farm River Valley.  (See Figure
             1, Area Relationships)
                               - 3 -

-------
                 N
                           Farm River —
                           Drainage Area   •
I
Lower Valley
                                  f.--^-~?    J   •>
                                                                            i
areo  relation/hip/
                       figure 1
north  branford   w Q / t euu Q ter treatment  racilitle/
dote: July 1979
/ource: ander/on-nichol/
        environmental impact /totement    environmental protection agency
                             2880
ander/on-nlchol/ & co.,,lnc.
                 technical con/ultant

-------
       SECTION 2.0






EIS FOXON RECOMMENDATION

-------
Section 2.0  EIS FOXON RECOMMENDATION

2.1  Specifics

     Based on an analysis of existing septic system problems,
     soil conditions, and anticipated future problems, the EIS
     concluded that a limited sewer system was warranted to
     serve a limited portion of the southern Farm River Valley.
     The service area would be in the general drainage area of
     Burrs Brook, a small tributary watershed that comprises
     slightly less than 10% of the watershed of the Farm River
     Valley above the diversion to Lake Saltonstall.

     The EIS project would consist of the construction of a
     gravity interceptor along Burrs Brook to the Middle School
     area along Route 80.  This major element of the sewer
     system has already been designed by the Town.  Beginning
     at the school area, a ten inch pipe will be located on the
     south side of Route 80 to Arthur Road and along Arthur
     Road to Edward Road where the pipe size will expand to
     12".  Leaving Arthur Road north of Burrs Brook, the 12"
     pipe will head west through undeveloped land to serve the
     Sunset Drive/Brook Lane area.  The pipe will then continue
     cross-country toward the west to Totoket Road remaining on
     the north side of Burrs Brook until it crosses beneath the
     brook within the Totoket Road right of way.  The pipe will
     then continue west, along the south side of the brook
     until it turns directly south to continue along James Road
     and eventually Williams Road to a metering station at the
     East Haven town line.

     This last segment, from the sharp turn south to the town
     line, was originally designed as a 20" pipe anticipating
     that future wastewater flows from the Middle Farm River
     Valley would be intercepted at this point.  Because the
     EIS has concluded that no present or future need for
     sewers exist, within the 20-year planning period in the
     Middle Valley, the 20," section of interceptor should be
     redesigned to a smaller pipe size (12") to accommodate the
     reduced flow.

     In addition to the main interceptor sewer just described,
     th£ EIS study concluded that EPA will participate in the
     cbraitruction of a number of lateral street sewers for
    .which the Town sought funding during a unique circumstance
    *at the time of the Town's application when such funding
     was available.  The streets for which the EIS has deter-
     mined that the funding conditions have been met include:
                               - 5 -

-------
                                                                       Drainage Area
                                                                       Interceptor
                                                                       Laterals
project detail/
figure 2
north  branford   w a / t euu a ter  treatment   facilitie/
date: July 1979                                                      0      g90
/ource: ander/on-nichol/
        environmental impact /tatement    environmental protection  agency
ander/on-nichol/ & co.,inc.
                                                           technical con/uitant

-------
               Dorrie Drive*

               Arthur Road

               Edward Road

               Arthur Court

               Sunset Road

               Brook Lane**


     *   was not included in Town application
     **  older section running north-south


     The Burrs Brook Interceptor will accommodate future flows
     in addition to those generated by the above streets.
     Within the drainage basin of the brook, a number of inter-
     vening and peripheral areas could be connected to the
     interceptor by gravity flow.  Included within these areas
     are existing streets such as Katherine Street or Pioneer
     Drive.  Construction of these lateral street sewers could
     be done by the Town when they wish since capacity is pro-
     vided in the main interceptor.  The EIS did not, however,
     recommend these streets for lateral funding.  Details
     concerning the interceptor, the sewer service area, the
     sewer capability and the issue of lateral funding follow.

2.2  Interceptor Route

     The configuration of the existing housing developments
     which have been identified as problem areas determine that
     a gravity sewer system traveling along Burrs Brook is the
     most logical sewer route.  Because these houses straddle
     the brook, this would be the route that would require the
     least excavation and vtould also avoid the expense and
     problems of pumping. :

     Because this gravity route traverses undeveloped land,
     some of which is wetland and floodplain,: some direct and
     indirect environmental impacts were discussed in the DEIS.
     Theoretically/  this type of project might create several
     types of impacts including:

          — construction impacts which injure significant
             flora and fauna.

          — long term alteration of hydraulic flood plain
             characteristics.
                               - 7 -

-------
          — potential performance failure of the sewer system
             during floods.

          — potential flood damage to housing induced by sewer
             system.

     None of these impacts is expected in the North Branford
     project.   The route involves only one stream crossing, at
     Totoket Road where the pipe will be encased in concrete to
     prevent damage and leakage.  Because the area is a water
     supply watershed, the pipe will be cast iron throughout
     with sealed man-holes.  Lack of any structures in the
     floodplain minimizes impact to the system.  Adoption of a
     HUD flood plain study into the zoning ordinance will
     minimize secondary flood related impacts from the sewer
     project by regulating floodplain development.  Finally, as
     noted in the text, the construction impacts include a
     minimum amount of disruption of natural ecosystems or
     habitat because of the developed nature of the areas.

     Most construction impacts have been addressed in the
     general specifications of the Town's design for the Foxon
     interceptor.  Erosion and related water quality impacts
     are covered by general State standards for construction
     which require steps to avoid sedimentation and restore
     vegetation.  Actual monitoring of construction activity
     will be necessary to insure that the general guidelines
     are followed out.  Also, the unnecessary cutting of trees
     along the stream bank should be avoided.

     Many long term potential impacts have already been
     addressed in the existing interceptor design.  To further
     reduce the long term impacts in the wetlands area, steps
     should be taken to preserve the existing hydrologic
     regime.  Original grades should be maintained so as not to
     interfere with natural drainage patterns.  In addition,
     due to the porous nature of the gravel trench bed, which
     could potentially intercept the brook's base flow, pro-
     vision should be made to include impermeable clay barriers
     at points along the interceptor trench.

2.3  Development Capability/Capacity of the System

     Within the potential service area of the proposed Foxon
     Interceptor there are presently approximately 290 build-
     ings which would be connected to the sewer system.  Under
     present zoning an additional 224 homes could be built on
     undeveloped, but developable, intervening land between
     existing problem areas.  These additional homes could be
     accommodated by the proposed sewer system.
                               - 8 -

-------
 The  system design would be capable of serving about 300
 more homes than presently exist in the area,  or a mix of
 the  224  homes that zoning would permit and about 25 acres
 of industrial or commercial land.   Under the  present
 zoning,  there is about 26 acres of developable industri-
 ally zoned land and 6 acres of commercially zoned land.

 Consequently, the system would be  capable of  serving the
 development that local regulation  would permit within the
 limited  service area that is accessible to the interceptor
 by gravity.

 No capacity in excess of the .25 MGD that the existing
 development and this potential development would generate
 within Burrs Brook basin is provided for in the EIS pro-
 posal.   The existing Town design w^as reviewed in terms of
 pipe capacities and anticipated flows and was found to be
 consistent with the EIS sewer concept with the exception
 of the 20" segment that runs from  Burrs Brook to James
 Road and along Williams Road to East Haven.  This segment
 of pipe  should be redesigned to handle the anticipated
 flows from the Bl and B2 areas of  the Town's  1976 sewer
 plan.

 The  actual development that occurs within the Burrs Brook
 basin could take many different forms.   A number of
 variables  could influence this scenario including:

      —  changes in one acre zoning to one half acre where
         water and sewerage will become available.

      —  acquisition or deduction of land as open space.

      —  continuation of protection of agricultural  lands.

      —  limited industrial development in appropriate
         zones.

      —  cluster development in permitted zones.

      —  incomplete development within the sub-basin on
         less  desirable land.

 The  design of  the  EIS  approved sewer  system will  accommo-
date  the growth that is  expected in Area B  throughout the
 planning period.   The  design  has the  potential  for  use as
a positive planning approach  which focuses  development in
 the  southern portion of  the valley while preserving  the
greenspace and  agriculture  in the  Middle Valley.  In any
case, the  design is  a  reasonable one  in  that  it is  limited
to a  relatively small  area  and accommodates the planned'
moderate growth of  that  sub-area.
                          - 9 -

-------
N
                           Committed / Controlled Land
                           No capacity provided for
   potential /euuer /ervice area
figure 3
   north  bronford   wo/tewoter  treatment  raci  itie/
   dote; joly 1979                                                  0      090
   /ourcc: onder/on-nichol/
          environmental impact /totement    envlronmentol protection  agency
   QfK)er/on-nichol/ & co., inc.

-------
2.4  La tera1 Fund ing

     As indicated in an earlier section, certain local street
     sewers have been evaluated in terms of their eligibility
     for federal funding.  Ordinarily funding is only available
     for major project elements such as interceptors, treatment
     plants, and pumping stations due to limited funds.  During
     a brief period in 1977, the Connecticut DEP had funds
     available but uncommitted to specific projects.  Concerned
     that uncommitted federal funds would revert to the federal
     government, DEP permitted eligibility to be extended to
     lateral sewer construction.

     Because of similar circumstances in other states, EPA has
     established, through Program Requirements Memorandum 77-8
     (PRM 77-8 since superseded by PRM  78-9), regulations
     governing lateral eligibility in order to adhere to its
     requirements governing cost-effectiveness and environmental
     protection.

     The question that faced the EIS during the  formalization
     of the final EIS was not, therefore, whether sewers should
     be permitted in that area or whether connecting to the
     sewer system might be  the best solution to  a homeowner
     with a septic system problem.  The basic question was
     whether the EIS could  endorse federal  funding for these
     local street sewers under the regulations set down in PRM
     78-9.

     The lateral sewers  that were approved  for funding met the
     requirements of the PRM.  Several  streets in the Town's
     "reduced sewer plan" were omitted  from the  EIS  recommen-
     dation.  These included Merrick Drive,  Katherine Street
     and a small section of Totoket Road.   The EIS project team
     found in general that  there was lack of documentated
     septic system problems in addition to  the availability of
     reasonable  lot sizes and good soils in these areas.  In
     addition, rehabilitation of problem septic  systems was
     believed possible and  much less expensive in terms of
     total costs, than the  sewer system proposal.  This does
     not rule out future local street  sewer construction  for
     these  streets.  It  may happen that a group  of residents
     may experience septic  system problems  simultaneously in
     the future  and wish to petition the Town  for sewer con-
     struction,  even though it will be more expensive  than a
     new septic  system construction, simply to serve the
     convenience of sewer use.  The EIS cannot,  however,
     justify  federal funding  for these streets under the  PRM
     requirements.
                                -  11  -

-------
During the DEIS review period, the Town surveyed homes in
the B-2 sewer area in order to gain more information con-
cerning the extent of septic system problems in that area.
The Town submitted the results to EPA and they are included
in this report.  The streets that were surveyed included:

          — Pioneer Drive

          — Virginia Road

          — Pine View Road

          — Pine Place

          — Williams Road

On all but Williams Road, a majority of the residents
responded '"yes" to the questions indicating that they had
symptoms of septic system problems and believed that they
needed sewers in their neighborhoods.

Since these streets had not been included in the Town's
"reduced sewer program", they had not been specifically
addressed in the DEIS lateral funding analysis.  In light
of this additional input, the streets for which the infor-
mation had been collected were re-examined more closely in
terms of their eligibility for federal funding under PRM
78-9.

From the responses the Town received during their survey,
it is apparent that most of the residents of this area
would like to obtain sewer service.  They report that they
have experienced some of the signs of septic system
problems and have indicated that they would prefer sewers
to wastewater disposal.  The EIS project recommendation,
in fact, reserves capacity for some future connection.

The requirements of PRM 78-9 regarding the density of
population and age of development are largely met.  While
evidence of septic system problems exists to the extent
that the survey discussed earlier has shown, the main
obstacles to complying with the PRM are the nature of the
problem and the demonstrated cost-effectiveness of the
sewer system.  Site conditions show that the area is
served by public water and consists of one half acre lots
on soils with good characteristics.  According to the Soil
Conservation Survey information, the soils of the area are
the Branford silt loam series and are characterized as
moderately permeable in the upper layer and very rapidly
                          - 12  -

-------
     permeable  in  the  sub-soil  layer.   Bedrock  is  generally
     greater than  ten  feet  below the  surface  of the  soil  and
     the depth  to  groundwater at high groundwater  season  is
     greater than  three  feet.   Sites  of this  type  should  be
     able to accommodate on-site wastewater disposal,  parti-
     cularly with  the  provision of  public  water supply.   When
     EIS engineers visited  this area,  they were aware  of  the
     signs of potential  septic  system problems.  It  is their
     conclusion, however, that  these  problems can  be remedied
     by low cost on-site rehabilitations.  The  source  of  the
     problem may lie in  poor initial  design,  improper  use, or
     age of the systems.  Better performance  could be  obtained
     by enlarging  fields, reducing  wastewater flows  and/or
     installing curtain  drains  where  upslope  drainage  is  a
     problem.                            •

     The adequate  lot  size  makes a  demonstration of  the cost-
     effectiveness of  a  centralized gravity sewer  system  very
     difficult.  A preliminary  cost analysis  of local  street
     sewers is  shown in  the following tables.
                            TABLE  1



                 PRESENT WORTH COST ANALYSIS
                      LOCAL SEWERS FOR
       PIONEER DRIVE, VIRGINIA DRIVE, PINE VIEW DRIVE
                                   UNIT          PRESENT WORTH
     ITEM           NUMBER         COST       INITIAL        SALVAGE


House Connections     30           $600     $ 18,000        ( 3,000)
Collector Sewers    2700 L.F.        55       148,500        (24,800)
Implementation        -              -        44,500

  Sub-Total                                   211,000        (27,800)

O & M                 30             40         -
Present Worth         -              -        13,100

TOTAL PRESENT WORTH COST                    $196,300

EQUIVALENT COST PER HOUSE                   $  6,545
                               _ 13 _

-------
                      TABLE 2

                                       i
             ANNUAL COST TO HOMEOWNERS
                 LOCAL SEWERS FOR
  PIONEER DRIVE, VIRGINIA DRIVE, PINE VIEW DRIVE
     ITEM                               COST
Private Capital
  House Connections                   $ 18,000

Municipal Capital
  Collector Sewers                     148,500
  Implementation                        44,500
                                      $193,000
Federal & State Grants

Local Shares                          $193,000

  Amount to Taxes                      115,800
    Tax Rate Increase                    0.13

  Lien on Users                         77,200
    Annual Cost                          7,070

  Operation & Maintenance                1,200

Annual User Cost
  First Year                          $    875
  Each Year Thereafter                $    275
                          - 14 -

-------
     The cost per house of the sewer system  ($6,545) is far in
     excess of the anticipated cost of rehabilitating most of
     the existing on-site disposal systems.  Further, the
     annual cost of sewers ($275 for twenty years in addition
     to the estimate $600 cost for connection) is far in excess
     of the cost of continued on-site disposal with adequate
     care and maintenance measures.  Because of lot size and
     soil conditions, the EIS project team has determined that
     rehabilitation of existing on-site systems in this area is
     physically possible (in striking contrast to the findings
     in other neighborhoods in the Burrs Brook area).  Opera-
     tional problems cited by residents are most likely a
     function of the age and size of the systems rather than
     evidence of inherent site limitations.  The conclusions of
     the EIS analysis of sewerage need and cost-effectiveness
     in this area don't support the eligibility of lateral
     sewers in accordance with PRM 78-9 and should be used by
     homeowners in the neighborhood in a thorough consideration
     of sewer construction desirability.

2.5  Sewer System Impacts

     Many of the specific impacts of constructing the limited
     sewer system in the Foxon area were noted both in the
     discussion of the Burrs Brook interceptor in this report
     and in Section 5.91 in the DEIS.  A long term potential
     impact that warrants further discussion, in light of the
     confusion of some DEIS reviewers over the actual EIS
     recommendation, is the issue of indirect water supply
     impacts.

     The most sensitive area of potential environmental impact
     in the North Branford EIS study is the drainage area of
     the Farm River Valley.  As cited in the DEIS, the fact
     that this watershed drains to diversion structures both in
     Northford and in East Haven means that a continuing aware-
     ness of the direct linkage between activity in the water-
     shed and consequences for water supply must be maintained.

     North Branford's situation with respect to water supply is
     somewhat unique.  Approximately one third of the Town is
     part of the Lake Gaillard watershed.  Most of the land is
     owned by the private New Haven Water Company.  Regulation
     of this type of watershed land has been the focus of the
     state for at least a decade.  The basic issue surrounding
     the large land holdings is the desire- of water companies
     to dispose of lands they believe are not critical to main-
     taining water quality and the state's concern for long
     term water quality protection.  In North Branford,  much of
                               - 15 -

-------
the water company land is not available for sale under
state regulations while the remainder falls under a
special zoning district in the new local zoning regu-
lations.  The Farm River Valley, on the other hand, is
privately owned land held by many property owners, which
is diverted to the reservoir system.  The decentralization
of ownership complicates the problem of management and
responsibility.  Nonetheless, the common welfare of the
area lies in maintaining the best water quality possible.

Water quality impacts on the Farm River system could
manifest themselves as both short term pollution events
and long term water quality deterioration.  The issue of
long term deterioration has been associated with the so-
called non-point pollution sources.  Included among these
are agricultural activities, construction activities, and
industrial, commercial and residential development.  In
the latter category, the pollutants referred to are the
accumulation of small quantities that are deposited on the
ground and rinsed away during the rain.

The cleanest possible use of watershed land is forest
land.  Other land uses, regardless of the pastoral appeal
of farm landscapes or the stereotype of suburban sprawl,
generate considerably larger quantities of pollutants than
forest land.  Some representative examples are shown in
Table 3.
                          - 16 -

-------
                            TABLE 3



       AVERAGE ANNUAL STORMWATER RUNOFF CONCENTRATIONS


                              OF


                     POLLUTANT PARAMETERS*
Land Use
Residential (2-5 ppa)**
Residential (5-8 ppa)
Residential (8-12 ppa)
Residential (12-15 ppa)
Residential (Combined
Sewer Overflows)
Commercial & Industrial
Agricultural (Adequate
Controls)
Agricultural (Needing
Control )
Rural (Adequate
Controls)
Rural (Needing Control)
Suspended
Solids
(mg/1)
300
340
380
420
250
500
3,000
40,000
500
5,000
BOD 5
(mg/1)
t
20
22
24
26
100
30
20
25.0
0.3
3.5
Phosphorus
as
P (mg/1)
0.70
0.66
0.62
0.58
4.00
0.50
.20
2.80
.002
.04
Nitrogen
as
N (mg/1)
3.1
2.9
2.7
2.5
10.0
2.2
5.0
65.0
1.0
8.0
*  Corps of Engineers, Omaha District, "Regional Wastewater Study"
   October, 1974.

** Persons per acre.
                               - 17 -

-------
As described in the DEIS, residential development may or
may not result in lower water quality.  For some pollu-
tants, farming is potentially a greater source.  Much of
the land within the Farm River Valley is classified as
farmland.  Intensity varies, however, within broad cate-
gories with much land remaining idle.  Assessing the
relative contribution of the various current land uses
would be no simple matter.

When the EIS attempted to assess future water quality
impacts resulting from the EIS recommended project, a
number of unpredictable variables became apparent.
Included are farm practices, lawn and garden practices,
development forces, development patterns, and development
controls.  Other uncertainties included use of indicator
bacterial criteria which do not differentiate among
sources, background concentrations, environmental cleaning
mechanisms, and the variable operation of the reservoir
diversions.  The interplay of all these real world factors
render quantitative analysis beyond the scope of this EIS.
Future water quality effects from non-point sources were
retained among the larger set of qualitative environmental
criteria by which alternatives were selected and the final
project impacts evaluated.

In the earlier discussion in this Section, it was noted
that the sewer system for the Foxon area had a potential
service area which is less than the 10% of the Farm River
Basin drainage.  In addition, it was noted that the
capacity of the system was equal to the flows which will
be generated by development under the existing zoning
regulations.  Also, the actual number of homes that could
be served by the sewer system was found to be about equal
to the population growth that was anticipated in the lower
and middle River Valley during the 2 year planning period.
The recommended project then is consistent in size with
reasonable growth expectations for the area.  It is not a
greatly oversized system intended to stimulate existing
development forces.  In terms of overall impact on water
quality, the construction of the limited Foxon sewer
system could not significantly change the degree of the
development from that which would otherwise be permitted
or anticipated.

Development patterns might, however, be influenced by the
presence of the limited sewer in Foxon.,. Approximately 300
homes are anticipated in the lower and middle Farm River
Valley during the planning period.  Also, approximately
the same number of homes could be accommodated by the
limited sewer system in the lower valley.  It is reasonable
that the sewer system will draw some but not all of this
development.
                           _  18  _

-------
While land capacity exists under present zoning for about
300 homes, about one half of these potential lots have one
or more soil constraints for septic systems in addition to
odd lot shapes, saturation, etc.  Not every lot would be
developed.  Given that the Foxon area (as defined in the
project sewer area) represents about 20% of the lower and
middle valley, it might be expected that an estimate of 60
new homes  (20%) might be a better estimate of future
development in the absence of a sewer.  Applying the
general guide that has been used in other Connecticut
EIS's of increasing population growth by 10% due to the
presence of sewers and doubling the land area within the
sewered area that is developed due to the presence of
sewer service, the following increases and shift in
residential development might be expected:
                      TABLE 4


     INDUCED GROWTH & POPULATION DISTRIBUTION

                    1980 - 2000



                    Without Sewers      With the Foxon Sewers

Within Foxon Area      60 homes               120 homes

Remainder of
  Middle Valley       240 homes               210 homes

Total Area B          300 homes               330 homes
Such a scenario would result in slightly more residential
development in the general area and a concentration of new
development along the route of the interceptor.  In terms
of long term water quality degredation, this level of
total development is not significantly more threatening
than the "no-action" scenario of development without
sewers, nor is the development inherently more polluting
than the current agricultural use.  The shift is to locate
the new growth in the sewered area where the control of
sanitary wastes will be greater, while lessening slightly
the development pressure in the undeveloped Middle Valley.

The actual development that occurs here will be a product
of unknown forces and controls.  The real estate market,
both in terms of total housing units, price of units, and
types of units is uncertain over the planning period.  The
                          - 19 -

-------
     Town has taken steps through its recently revised zoning,
     which is soil and slope based, to help improve the in-
     tegrity of on-site disposal in the area.  In addition, the
     Town will control existing wastewater disposal problems in
     the Foxon area by the construction of the limited sewer
     system and will likely attract some of the development
     which would have relied on on-site disposal elsewhere.  In
     addition, a combination of developer ingenuity and planning
     board cooperation could conceivably lead to further growth
     inducement within the sewer area and less growth subse-
     quently in the Middle Valley area.  The effect would be to
     place the sanitary wastes under the centralized control of
     the proposed sewer system.

     Accurate non-point pollution prediction, however, remains
     risky at best.  The trade-off relationship between agri-
     cultural use and residential is uncertain, especially in
     light of the amount of idle land.  Actual land-owner
     practices remain highly unpredictable.  At this point in
     time, "farm" parctices are under some regulation by the
     state DEP, but home-owner use of chemicals is largely
     unaddressed.  Finally, the pollution event associated with
     chemical spills whether industrial, agriculture or domestic,
     presents an ever present threat.  Increased public aware-
     ness, public board or agency site review and monitoring,
     and contingency cleanup procedures are some possible
     protection steps that can be taken to minimize this danger.
     The single presence of a limtied sewer system in Foxon
     will not be the major determinant of the actual future
     outcome.

2.6  Conclusions

     The fact that the Farm River serves as a source for public
     water supply should receive more local attention.  The
     role of the watershed needs clarification in the local
     planning process.  While the recently adopted zoning
     represents, at least indirectly, a positive step toward
     water quality protection, these lands are not specifically
     addressed in terms of this use.  Development can still
     occur to the extent that zoning permits with or without a
     sewer system.

     The project recommended by the EIS will serve a chronic
     need for pollution abatement in a small portion of the
     watershed without significantly affecting future land use
     in that area.  To insure against eventual saturation
     development of the remainder of the Farm River Valley, if
     that is the objective of state DEP, some positive land
     planning approach should be developed.  Perhaps these
     lands could be eligible for some form of preservation
     program similar to the agricultural lands under which
     agricultural landowner is encouraged to continue that use.
                               _ 20 -

-------
The additional problem of the risk of accidental chemical
spills which might threaten water supplies will continue
to require local and state surveillance.  As noted earlier,
agricultural practices represent one type of potential
problem but are presently under the control of the state
DEP.  The industrial sector will continue to present a
risk, with or without a sewer system.  Continued surveil-
lance of the type of processes in use and the ultimate
means of waste disposal will be required at local health
agencies.

Finally, for those areas where problems exist but no
project recommendation can be made at this time, addition-
al 201 Facilities Planning is anticipated by EPA and the
Connecticut DEP.  In the course of this work, which will
be addressed at non-problem areas as well, thought should
be given to a public information effort in the use of
septic systems.  Problems with septic systems have been
regarded in areas where soils information suggests that
they should work properly.  Given the attention that
sewers have been given, some families may have chosen to
wait, before attempting repairs, to see if they will be
sewered.  It is anticipated that the additional 201 effort
would make it clear that most of the Farm River Valley
will rely indefinitely on on-site disposal.  Both the Town
and the individual homeowners will have to make the
commitment to making this approach work.
                          - 21 -

-------
                    SECTION 3.0


               RESPONSES TO COMMENTS


This chapter summarizes EPA's responses to:

     - Written comments of Mr. Thomas Quamma, dated
       April 16, 1979

     - Written comments of John W. Shannahan, State
       Historic Preservation Officer, dated May 2,
       1979 and Jordan E. Tannenbaum, Advisory
       Council on Historic Preservation, dated
       April 25, 1979

     - Written comments of William R. Hogan,
       Connecticut Department of Environmental
       Protection, dated April 25, 1979

     - Written comments of Larry E. Meicrotto of
       the U.S. Department of the Interior, received
       May 31, 1979

     - Written comments of Aden H. Maben,  Connecticut
       Office of Policy and Management, dated June 4,
       1979

-------
3.1  Introduction

     The first two sections of this report address questions
     raised by reviewers especially the Connecticut Department
     of Environmental Protection and the Town of North Branford.
     Section 2.0 in particular attempts to provide a suffi-
     ciently detailed discussion of EIS recommendations to meet
     the needs of those concerned.

     Section 3.0 is comprised of responses to individual
     comments of a more specialized nature.

     All written comments received are in Appendix A.

3.2  Response to Mr. Tom Quamma, Northford Resident

     The interceptor along Clintonville Road was a project
     element of the EPA approved sewer system for Area C.  This
     line was designed to serve the area north of Clintonville
     Road by gravity.  Most of the Green Acres development is
     downhill from this line and could be served only by pumping
     which is costly.

     The water quality sampling program represented one element
     in the decision-making process of the EIS.  The sampling
     that was inadvertently done at site 12 in the already
     approved area did confirm earlier conclusions that local
     streams were being polluted.  In that regard, the samples
     for site 12 and site 13 in Green Acres are similar.  In
     Green Acres, however, no structural remedy could be
     approved at this time because of the lack of a grant
     application by the Town and serious questions regarding
     the cost-effectiveness of the sewering solution that has
     been proposed for that area.

3.3  Response to Comments of Advisory Council on Historic
     Preservation and State,Historic Preservation Officer

     While addressing the historic and cultural context of
     North Branford in the DEIS, the historic preservation
     review process remained incomplete at the time of pub-
     lication.  Review by the State Historic Preservation
     Officer of the archeological, historical and architectural
     resources of the project area has now been completed.  The
     determination is that no effect is expected on resources
     listed on or eligible for the National Register of Historic
     Places due to the North Branford Wastewater Management
     Program.

     The letter stating this determination is included with
     Appendix C.


                              - 23 -

-------
3.4  Response to the Comments of the Connecticut Department of
     Environmental Protection

     The general discussion of the EIS recommendations in the
     early sections of this report was presented to address
     many questions concerning details of the recommendations.
     Questions not previously covered in Section 2 are discussed
     below.

     The EIS recommends continued long term reliance for all
     areas other than Foxon where the limited sewer system is
     recommended,  and Glen Acres and White Hollow where addi-
     tional study of certain small scale, but centralized,
     treatment options should be further studied.  Such an
     approach might include a small sewer system discharging to
     a common leaching area or a non-conventional sewer system
     such as a small diameter pressure sewer system where local
     conditions favor this less expensive approach.  The
     potential for state and federal funding of such a project
     through the state's reserve fund for small scale community
     systems make this approach very attractive at this time.

     For other problem areas such as Jerz Lane, Miller/Grant
     Road and Surrey Drive, continual on-site treatment is
     believed to be the best solution.  In view of existing
     problems,  and in light of the possibility of a town-
     sponsored and state and federally funded rehabilitation
     program,  the EIS believed that the residents would want to
     pursue this approach to performing the necessary rehab-
     ilitation that is apparently needed by many homes in these
     areas.

     Questions concerning water supply and representations of
     cost data are addressed in Section 2.
                              - 24 -

-------
3.5  Response to the Department of the Interior

     The DEIS addressed the question of water supply in Section
     4.41.  About one-third of the community is presently
     served by the New Haven Water Company.  The remainder
     depends upon ground water resources for drinking water.

     With respect to the potential for wild life impacts from
     the EIS recommendations, the detailed discussion of the
     Foxon Interceptor at the beginning of this report should
     serve to illustrate that this is the only structural
     recommendation of the EIS.  Other recommendations include
     additional study in the Green Acres area and the White
     Hollow area as part of Step I Facilities Plan.  Recommen-
     dations from these studies, should they develop, will be
     analyzed as part of an environmental assessment.

     The habitat potential of the area of«major construction,
     the Foxon Interceptor, was discussed in DEIS Sections
     5.91, 5.911, and 5.912.  Little undisturbed land exists in
     the vicinity.  The small valley has served as an old
     railroad corridor and a recent gas pipeline project.
     Compared to the extensive land holdings at the Water
     Company and the private open farmlands in the Middle Farm
     River Valley, the habitat potential for the Burrs Brook
     area is relatively low.  Lists of expected animals were
     obtained from the following sources:

          D.S. Coyer and W.L. Hotaling, Ecology and Land Use at
          the Supply Ponds Natural Area, Branford, Connecticut
          (New Haven, revised, 1970)

          New Haven Bird Club, Inc.  Check-list of Birds-New
          Haven County (New Haven, revised 1970)

     The proposed gravity interceptor follows Burrs Brook and
     includes one stream crossing and encroaches on two stream-
     side wetlands.  However, the general existing habitat type
     of the project area is residential backyard and woodlot.
     Short term construction impacts will temporarily disrupt
     wildlife.  Vegetation inside the right-of-way will be
     removed.  Long term adverse impacts to this habitat may
     result from growth induced by the project.  However,
     existing streambelt protection regulations and floodplain
     development regulations will protect, to some degree,
     habitat on both sides of Burrs Brook.

     The potential wetlands impacts were identified in the DEIS
     in Section 5.91 and mitigation measures were recommended.
     The route that is designated for the interceptor avoids
     disruption of the stream bank  vegetation and large tree
     stands.  The only stream crossing is in a roadway.  No
     filling at wetlands nor channelization at the stream is
     specified in the plan.


                              -25-

-------
3.6  Response to Connecticut Office of Policy and Management

     Many of these comments were addressed in the detailed ex-
     planation of the EIS recommended project in earlier sections.
     Details of the service area, lateral street sewers, and total
     future capacity have been specified.

     The recommendation for the limited sewer system in Foxon
     was based on a variety of sources including stream belt
     surveys, workshops,  resident questionaires, water quality
     sampling, resident petitions, and engineering judgments
     of site conditions.   While some of this information is not
     site specific, these sources indicated that about 50 out
     of the 300 homes in the Foxon area have been specifically
     identified as having septic system problems.  While some
     may have been repaired in the interim, others may well be
     experiencing problems that were not previously reported
     due to the chronic nature of some of these areas.  The EIS
     recommended the limited sewering concept because it was the
     only feasible approach for some of the more densely populated
     neighborhoods.

     The EIS did analyze land use controls that affect North Branford,
     including the watershed areas, in Section 4.22.  Greater
     emphasis should be placed on the status of the Farm River
     Valley as a source of public water supply.  While this special
     function may be implicit in the State Conservation and Develop-
     ment Guide, the regional Plan, and the Town zoning, it is not
     treated directly by any land use plan or regulation.  The
     Town zoning was thoroughly analyzed in terms of changes that
     have occurred from the previous map.  In general, lot sizes
     have been increased in many areas of the Farm River Valley
     in an apparent effort to integrate soil and slope constraints
     on spetic system use.  Consequently less population could be
     accommodated in the valley under new zoning.  This approach
     does not directly confront the issue of development of the
     watershed, however,  the section on water supply lands, in
     fact, refers only to those lands in the drainage of Lake
     Gaillard.

     The Town Plan is outdated with respect to the issues of on-
     site wastewater disposal, development and the watershed areas.
     In light of the present day circumstances regarding actual
     sewer construction,  lower development pressures, and the EIS
     recommendation that large areas remain on septic systems, a
     new statement of the Town's planning directions should be
     formulated.  Perhaps such an effort could be developed con-
     currently, or as an extension to, the anticipated 201
     Facilities Plan.
                               - 26 -

-------
         APPENDIX A
   WRITTEN COMMENTS ON DRAFT
ENVIRONMENTAL IMPACT STATEMENT

-------
LIST OF WRITTEN COMMENTS ON
COMMENT NO.
W-l
W-2
W-3
W-4
W-5
W-6
W-7
W-8
W-9
DRAFT ENVIRONMENTAL IMPACT STATEMENT
SOURCE
Tom Quamma, Northford
Resident
State Historic Preservation
Officer for Connecticut
Advisory Council on"
Historic Preservation
Federal Energy Regulatory
Commission
State of Connecticut
Department of Environmental
Protection
Jonathn Bodwell, Town
Engineer
Department of Transportation
United States Coast Guard
United States Department
of the Interior
State of Connecticut
DATE
4/16/79
5/2/79
4/25/79
4/19/79
4/25/79
5/29/79
6/1/79
5/31/79
6/4/79
 Office of Policy and Manage-
 ment i

-------
                            W-l
                               April 16, 1979
                                                          APR 18 1979
Mr. Robert Mendoza
Environmental Protection Agency
Environmental and Economic Impact Office
J. F. Kennedy Federal Building
Boston, Massachusetts   02203

Dear Mr. Mendoza:

I have read, with great interest, the latest EIS News for our
community.  The thoroughness of the study is quite impressive
compared to what I have seen over the years as North Branford
has attempted to settle the "sewer" question.

Based on the various studies of water sampling sites and prob-
lem areas, two questions pertaining to the proposed sewering
of my area (Section G) come to mind:

     1.  Forgetting costs, if Section C were to proceed,
         why would "Green Acres" not be automatically
         incorporated?  The interceptor for Section C
         appears to pass closer to Green Acres than most
         of Section C.

     2.  Based on samplings taken in Green Acres, Section
         C appears no worse in pollution than our neigh-
         boring "Green Acres" area.

When you consider the current controversy over the validity for
pursuing sewering in Section C, I have the impression that your
conclusions and finding for Green Acres could just as well have
included or be duplicated for Section C.  The total sewering costs
will be too high compared to rehabilitation on a house-to-house
basis for the exact reasons you stated for Green Acres.

                               Sincerely,
Tom
Birchwood Drive
Northford, Connecticut
                                                        06^72
 cc:  N. B. Town Manager

-------
   Office of the                     w~2
   STATE
   HISTORIC
   PRESERVATION
   OFFICER
   for Connecticut
     59 SOUTH PROSPECT STREET .- HARTFORD, CONNECTICUT 06106 • TEL: (203) 566-3005

                                                May 2, 1979

                                                MAY 10 1979
       Mr.  William.'R.  Adams, Jr.
       Regional Administrator
       U.  S. Environmental Protection Agency
       Region  1                   .
       John F.  Kennedy Federal Building
       Boston,  Mass. 02203

           Subject:  Draft Environmental Impact Statement
                     Wastewater Management Program, NORTH BRANFORD,  CT.

       Dear Mr. Adams:

       The State Historic Preservation Officer has reviewed  the
       above-named project.  In the opinion of the State Historic
       Preservation Officer, this  Draft Environmental Impact State-
       ment is deficient with respect to the Environmental Protection
       Agency's legislative  responsibility under the National Environ-
       mental  Policy Act  (P.L. 91-190), National Historic Preserva-
       tion Act of 1966  (80  Stat 915, 16 USC 470 as amended),  and
       Advisory Council Guidelines 36 CFR 800.

       In  general, the identification of cultural  resources  within
       the potential environmental impact area has not  been  addressed
       by  the  Environmental  Protection Agency.  This Draft Environ-
       mental  Impact Statement fails to indicate whether the Environ-
       mental  Protection Agency has consulted the  National Register
       of  Historic Places with regards to listed resources and
       the Connecticut State Historic Preservation Officer with re-
       spect to properties which may be eligible for the National Re-
       gister  of Historic Places.

       Therefore, in order to comply with the Federal legislative
       mandates, National Environmental Policy Act (P.L. 91-190),
       National Historic Preservation Act of 1966  (80 Stat 915, 16 USC
       470 as  amended), and  Advisory Council Guidelines 36 CFR 800,
       consultation with the State Historic Preservation Officer should
       be  sought to insure the identification of cultural resources
STATE HISTORIC PRESERVATION OFFICER:  The person responsible far implementation in Connecticut of the National Historic
Preservation Act of 1966 administered by the Department of the Interior, Heritage Conservation and Recreation Service. Washington. D.C.
              AN EQUAL OPPORTUNITY EMPLOYER!AFFIRMATIVE ACTION AGENCY

-------
Mr. William R. Adams, Jr. (Cont'd)  - 2 -
                May 2, 1979
which possess architectural, historical and archaeological
significance.  This consultation with the State Historic
Preservation Officer should commence at the earliest planning
stage in order to insure a comprehensive review of cultural
resources and to coordinate and expedite cultural resource
management with the Environmental Protection Agency's project
planning.

For further information, please contact David A. Poirier,
Archaeologist.
                                Sincere!
DAP:aas
cc:  Mr. Anthony Ciccarelli
     Environmental Protection
       Agency
     Boston, Mass. 02203

     Ms. Ina B. Camblor
     Conn.Dept. of Environmental
       rotection
     Hartford, Ct. 06115

     Dr. William J. Murtagh
     Keeper of the National Register
     Washington, D.C. 20243
John W. Shannahan
State Historic Preservation
     Officer

-------
Advisory
Council On            w~3
Historic
Preservation                               m z 5 J979
1522 K Street N.W.
Washington D.C.
20005
April 23, 1979.
Mr. Robert Mendoza
Environmental and Economic
  Impact Office
U.S. Environmental Protection Agency
J.F. Kennedy Federal Building
Boston, Massachusetts 02203

Dear Mr. Mendoza:

We have recently reviewed a copy of your draft environ-
mental impact statement for a local wastewater management
program in North Branford, Connecticut.  Pursuant to
Section 102(2)(c) of the National Environmental Policy Act
of 1969 and the Council's regulations "Protection of Historic
and Cultural Properties" (36 CFR Part 800)(enclosed) we
have determined that your statement is inadequate as it
does not meet the requirements of Section 800.A of our
regulations.  That section directs the Federal agency to
demonstrate that the latest edition of the National Register,
Federal Register, February 6, 1979, and its monthly supplements
has been consulted.  The draft environmental statement
should also show evidence of an effort to identify properties
that may be eligible for the National Register, including
evidence of contact with the State Historic Preservation
Officer, whose comments should be included in the final
environmental statement.

Prior to the approval of the expenditure of any Federal
funds or prior to the granting of any license, permit, or
other approval for an undertaking, Federal agencies must
afford the Council an opportunity to comment on the effect
of  the undertaking on properties included in or eligible
for inclusion in the National Register o€ Historic Places
in  accordance with the Council's regulations.  Until these
requirements are met, the Council considers the draft

-------
  environmental  statement incomplete in its treatment of
  historical,  archeological, architectural, and cultural
  resources.   You should obtain the Council's substantive
  comments  through the process outlined in 36 CFR Sec.  800.9.
  These  comments should be incorporated into any subsequent
  documents prepared  to meet requirements under the National
  Environmental  Policy Act.  Ms. Sharon S. Conway may be
  contacted at 202-254-3967 for further assistance.

  Sincerely,
;  Jordan E.  Tannenbaum
  Chief, Eastern Office  of
    Review and Compliance

  Enclosure

-------
                          W-4
               FEDERAL ENERGY REGULATORY COMMISSION
                        WASHINGTON, D.C. 20426
                                April 19, 1979
Mr. William R. Adams, Jr.
U. S. Environmental Protection Agency
Region 1
JFK - Federal Building
Boston, Massachusetts  02203

Dear Mr. Adams:

     I am replying to your request to the Federal Energy
Regulatory Commission for comments on the Draft Environmental
Impact Statement for the Branford Connecticut Local Wastewater
Management Program.  This Draft EIS has been reviewed by
appropriate FERC staff components upon whose evaluation this
response is based.

     The staff concentrates its review of other agencies'
environmental impact statements basically on those areas of
the electric power, natural gas, and oil pipeline industries
for which the Commission has jurisdiction by law, or where
staff has special expertise in evaluating environmental impacts
involved with the proposed action.  It does not appear that
there would be any significant impacts in these areas of
concern nor serious conflicts with this agency's responsibilities
should this action be undertaken.

     Thank you for the opportunity to review this statement.

                                 Sincerely,
                                 Jack M. weinemann
                                 Advisor on Environmental Quality

-------
                                         W-5

                    STATE  OF CONNECTICUT
            DEPARTMENT OF ENVIRONMENTAL PROTECTION
                   STATE OFFICE BUILDING    HARTFORD, CONNECTICUT 06115
                                      April  25,  1979
Anderson-Nichols & Company, Inc.
150 Causeway Street
Boston, Massachusetts  02114

Attention:  Walter Murphy
Gentlemen:
                                      Re:   North  BranYord, Connecticut
                                           Environmental Impact Statement
     The Connecticut D.E.P. has completed  the review of the draft Environmental
Impact Statement Local Wastewater Management Program North Branford, Connecticut.
The conclusions as presented on pages  29 and 30 are acceptable to this Depart-
ment.  Therefore, a revised Step 3 grant application will be accepted for the
limited sewer system in Area B and a Step  1 grant application will be accepted
for the remaining unsewered areas of North Branford.

     There are several comments on the draft report which are being made in an
effort to bring greater clarity to the report.  These comments are as follows:

1.  Page 8:  On the discussion of lateral  funding, it should be corrected to
indicate 75% funding for laterals rather than 90%.  No state funding has been
committed to laterals.

2.  Page 29:  Reference is  made to Areas Bl and B2 and later in the report
to Areas Cl, C2 and C3.  However,  there is no figure which clearly delineates
these areas.

3.  Page 24:  The limited sewer system being recommended for Area B is not
concisely defined by a figure showing  the  service area,  the proposed interceptor
route and the recommended laterals.  It would also aid the public's understanding
if the recommended streets  in need of  sewers were listed in the text either
on this page or elsewhere.

     The EIS recommends continued  reliance on septic systems for all other areas
of the study area not specifically mentioned.  However,  page 172 recommends
evaluation of on-site rehabilitation for other limited problem areas under a  Step
I grant.  These two pages appear to be  in conflict concerning areas such as
Jerz Lane,  Miller Drive/Grant Road and  Surrey Drive.

-------
Anderson-Nichols & Company, Inc.
North Branford, Conn.
Page 2


4.  Page 38:  The discussion on the priorities of small scale projects and the
relationship of priority to funding is misleading as it ignores the reserve
funds on the fiscal year 1979 priority list for small community systems. One
million dollars have been reserved in Connecticut for projects qualifying
as small community systems.

5.  Page 152:  The Muddy River is considered a potential water supply source
by the State Plan of Conservation and Development and the State Health Depart-
ment.  Therefore, the impact on future water supply must be revised.

6.  Page 164:  It should be noted that the first year user costs are a sum
of the connection cost to the sewer and the estimated user charge to cover the
0 & M costs.

     If there are any questions concerning this letter, please contact me
at 566-2793.

                                      Respectfully,
                                      William R.. Hogan
                                      Principal Sanitary Engineer
                                      WATER COMPLIANCE UNIT
WRH:mgy

cc:  EPA, Chester Janowski
     EPA, Robert Mendoza
     Thomas Wontorek, Town Manager

-------
HAYOB
  TIMOTHY P. RYAN

DKFDTT UATOB
  PA8QUALE YOUNG

TOWN HANAUEB
  THOMAS J. WONTOREK
                                            W-6
MARY E. BIGELOW
EDWARD CAPORALE
WILLIAM C. GARDNER
JOHN M. GE8MONDE
JOHN C. KOLICH
PHYLLIS NEWBERRY
JOANNE 8. WENTWORTH
             TOWN  OF  NORTH BRANFORD
                Administration Building,  Route 80,  North  Branford, Connecticut  06471
                                   Telephone (203) 488-7283

               MAY 311979
              May  29,  1979
              U.S.  Environmental Protection Agency
              Region  1
              John  F.  Kennedy Federal Building
              Municipal  Facilities Branch
              Boston,  MA  02203
              Attention:  Environmental and Economic Impact Office
                                              Re:  E.I.S., North Branford,
                                              	Connecticut  06471
             Gentlemen:
             Enclosed are twenty-four (24)  E.P.A. North Branford Citizens'
             Questionnaires resulting from  a house-to-house survey conducted
             during the week of  May  14-18,  1979 by the North Branford Engin-
             eering Department in  the area  of Pioneer Drive, Pine Place,
             Pineview Drive, Virginia Road  and Williams Road.

             The responses from  the  survey  show fourteen reporting problems
             with two systems actually bleeding onto the surface of the
             ground and ten responses reporting no problems.

             The Town of North Branford would appreciate it if this information
             can be incorporated into the Environmental Impact Statement.

             Respectfully yours,
             Jonathan Bodwell
             Town Engineer

             JB:cp

             Enclosures

             cc:   Thomas 3.  Wontorek, Town Manager
                                           1971

-------
                              W-7
                  DEPARTMENT OF TRANSPORTATION
                 UNITED STATES COAST GUARD
MAILING ADDRESS: , •.
COMMANDER  V"P-»-/
THIRD COAST GUARD DISTRICT
GOVERNORS ISLAND
NEW YORK, N.Y.  IOOO4
212 668-70Q1
                                                       16475.2/4-79
                                                       1 June 1979

United States Environmental Protection Agency         J^ ,.
Region 1                                               "     F7',
J. F. Kennedy Federal Building
Boston, MA  02203

Attn: Environmental and Economic  Impact Office

Dear Sir/Madam:

We have reviewed your Draft Environmental Impact Statement for
"Local Wastewater Management Program, N. Branford, Connecticut and
conclude that this project  will have no effect upon Coast Guard activities
in the area.

The opportunity to review this document is appreciated.

                                          sincerely-
                                          Jay Silberman
                                          Environmental Protection Specialist
                                          By direction of the District Commander

-------
                                                        .
                  W-8

United States Department of the Interior

           OFFICE OF THE SECRETARY
            WASHINGTON, B.C. 20240
ER 79/356
                                             MAY 3 1 1979

                                          RECEIVED
Mr. Robert C. Thompson
Acting Regional Administrator
Region I                                      •••., - r.;\Q7Q
Environmental Protection Agency              uUH   -- '»'»»
J. F. Kennedy Federal Building
Boston, Massachusetts  02203                  REGION I
                                        ' OFFICE OF REGION*! rniiNsa
Dear Mr. Thompson:

We have reviewed the draft environmental impact statement
for North Branford Local Wastewater Management  Program, New
Haven County, Connecticut, and have the following comments.

We believe that decisionmaking would be aided if a better
concept (even though qualitative) of the relative signifi-
cance and importance of local ground water as a source of
supply were given.  Even a comparison of the number of homes
served by the New Haven Water Company with the  total number
of homes involved would be useful in this context.

We are concerned with wetlands, streams, and other types of
habitat, such as woodlands and farmlands, of significant
value to fish and wildlife resources.  Our general comment's
regarding this type of project are:  the number of stream
crossings should be minimized and that precautions should be
taken to control erosion; stream beds should be returned to
their original grades.  Channelization of streams should be
avoided.  Sewer pipes should be placed as far as possible
from stream banks; a buffer strip of undisturbed vegetation
should remain along stream banks.  Sewer lines  should avoid
wetland areas, as well as other areas of significant value
to fish and wildlife resources.  No fill material should be
placed in wetland areas; construction equipment should not
be stored in, nor traverse wetland areas.  The amount of
vegetative clearing throughout the project area should be
minimized; disturbed areas should be seeded and mulched until
native vegetation has become established.

-------
The draft environmental statement's recommended plans of
action include the use of Federal funds to assist in the con-
struction of a limited sewer system in the Foxon Area; in the
Green Acres Area, it is recommended that the town re-examine
the feasibility of on-site rehabilitation; and, in the White
Hollow Area, both on-site rehabilitation and a community sewer
system were thought to be feasible.  These recommended plans
of action may have both direct and indirect impacts on fish
and wildlife resources.  Direct impacts would involve sewer
line crossings of streams and wetlands, as well as the removal
of vegetation within construction and permanent easements.
The construction of sewer lines in presently undeveloped areas,
such as woodlands and farmlands, may induce the development of
these areas, thus having indirect impacts on wildlife habitat.

This statement fails to adequately describe existing fish and
wildlife resources within the project area.  While it is
mentioned that a Corps of Engineers' Section 404 permit will
not be required for proposed activities involving Burrs Brook,
the document does not state if Federal permits will be required
for other portions of the proposed project.  There is inadequate
information provided in the statement concerning site-specific
location, design, and measures to minimize harm for a full
understanding and an evaluation of how the proposed actions/
interrelated Federal actions may affect fish and wildlife re-
sources.  However, two major areas of concern are evident from
the general descriptions provided of the recommended plans of
action:  the interceptor routing along Burrs Brook and the
common leaching field location near the intersection of Durham
and Reeds Gap Road.  We would recommend that a 100-foot minimum
undisturbed vegetative buffer strip be left along the banks of
Burrs Brook; this buffer strip is necessary for controlling
erosion, as well as providing a corridor for wildlife travel
and habitat.  Overhanging, shading vegetation is necessary along
the brook banks to provide detritus and cover for the stream
vertebrate and invertebrate communities, and to prevent extreme
fluctuations in water temperature.  From the drawings provided
in the statement, it appears that various streams run through
the area proposed as a common leaching field; we would recommend
that this field be located away from these streams and associated
wetland areas.  Location of the field away from these areas would
not only be necessary for the proper functioning of the field,
but would also be necessary to prevent impacts on stream- and
wetland-associated fish and wildlife habitat.

-------
If project implementation requires permits from the Corps of
Engineers, our FWS, pursuant to the Fish and Wildlife Coordi-
nation Act, would review and comment on the permit applica-
tions.  They would require more site-specific information than
is available in this statement in order to comment on these
permit applications.  We anticipate that, at a minimum, we
would require a minimization of stream crossings, no channeli-
zatio'n of streams, no fill in wetlands, an avoidance of con-
struction in wetland areas, and an undisturbed vegetative
buffer strip be left along the stream banks.  Because of these
concerns, you are urged to further coordinate project planning
with our Fish and Wildlife Service.

We hope these comments will be of assistance to you.

                                           y,
                                   Larry  E.  Meierotto
                                   SECRETARY

-------
                          w-9          JUN 14 1979

              STATE OF  CONNECTICUT
                     OFFICE OF POLICY AND MANAGEMENT
               80 WASHINGTON STREET   -   HARTFORD, CONNECTICUT 06115
                               June 4, 1979    ..... ..„ ^ _    .....
                                               i'v i-., <<-» Li !i V i.



Mr. Robert C. Thompson                             JUN 131976
Acting Regional Director                            .   _
U.S. Environmental Protection Agency               l'.^..;iCH I
Region I                                      OMCE uf REGIONAL 0-  ' : 'ZL
J.F. Kennedy Federal Building
Boston, Massachusetts  02203

Dear Mr. Thompson:

Subject:  Environmental Draft Impact Statement Local Wastewater
          Management Program, North Branford, Conn.

     The subject Environmental Draft Impact Statement, which
evaluates the wastewater collection and treatment alternatives for
North Branford, has been offered for review and  comment to various
state agencies by the State Clearinghouse.

     Enclosed are the comments of the Comprehensive Planning  Div-
ision of the Office of Policy and Management, as prepared by
Sidney Albert sen in his June 1, 1979 memorandum  addressed to  the
writer, and which he has requested be referred to your agency for
consideration in the preparation of the Final Environmental Im-
pact Statement.
     A copy of the most recent Locational Guide Map  (December
as part of Connecticut's Conservation and Development Plicies  Plan.
is also enclosed to supplement and illustrate the  concerns  of  the
Comprehensive Planning Division1 s concerns with the  Draft Environ-
mental Impact Statement.

     The opportunity to review and comment on the  subject document
is appreciated, and we hope that the comments offered will  be
helpful to all concerned with the North Branford *s wastewater
collection and treatment system.

                               Sincerely,    ,  ,
                               Aden H. Maben
                               State Clearinghouse Coordinator
AHM/ftm
cc:  S. Albertsen

-------
      APPENDIX B
PUBLIC HEARING TRANSCRIPT

-------
                     VERBATIM  PROCEEDINGS
                    TOWN  OP NORTH BRANFORD
                 ENVIRONMENTAL IMPACT  STATEMENT
                Before:   ROBERT MENDOZA,  Chairman
                         WALTER MURPHY
                         CHESTER JENOWSKI
                         WILLIAM HOGAN
                         KENNETH WOOD
                         JOSEPirZENESKI
                                  May  9,  1979
                                  Intermidlate School
                                  North Branford, Connecticut

                                  7:30 o'clock P.M.
                POST REPORTING SERVICE
                    205 CHURCH ST.. NEW HAVEN, CONN.. O651O
                             624-4102
DEPOSITIONS - ARBITRATIONS
 HEARINGS - CONFERENCES
SERVING CONNECTICUT
   SINCE

-------
               . . . Verbatim proceedings of a public hearing



held in the matter of the United States Environmental Protection



Agency, North Branford BIS Project, Environmental Impact Draft



Statement, held at the Intermediate School, Route 80, North



Branford, Connecticut, on May 9, 1979 at 7:30 o'clock p.m.  .  .  .







               MR. MENDOZA:  Good evening ladles and gentlemen.



My name is Bob Mendoza.  I am an Environmental Planner with the



Environmental and Economic Impact Office of EPA, Region One In



Boston.  With me this evening on my left is Ken Wood, EPA»s



Project Manager for the EIS, who is responsible for the prepara-



tion of this Environmental Impact Statement, Mr. Chet Jenowskl,



Grants Engineer for EPA, to my right, Walter Murphy, the Project



Manager of the EIS at Anderson-Nichols, EPA's contractors for the



EIS, to his right, Mr. Bill Hogan, who Is the principal Sanitary



Engineer with the Department of Environmental Protection, and



to his right, Mr. Joe Zeneskl, an Engineer with the consulting



firm of Anderson-Nichols.  Anderson-Nichols has been under



contract with the EPA for  the preparation of this  draft and



subsequent Environmental Impact Statement.  I would also  like to
                                              P


thank  the  local officials  for allowing us the use  of this



facility here tonight to conduct  this public hearing.



               The  hearing has  been  convened to receive comments
                        POST REPORTING SERVICE


                        205 CHURCH ST . NEW HAVEN. CONN.


                               624-41O2

-------
		3


 on the Draft Environmental Impact Statement for the waste water


 treatment and collection facilities In North Branford, Connecticut,


 This Environmental Impact Statement has been prepared pursuant to


 the National Environmental Policy Act of 1969, as amended and


 pursuant to the Environmental Protection Agency Regulations


 which appear in the Federal Register, 40 CRF, Part 6, dated


 April l*»th, 1975.  The National Environmental Policy Act provides


 that prior to commencing a major federal action, which may have


 a significant effect on the environment, a federal agency must


 prepare an Environmental Impact Statement.  The major federal


 action in this case, is the funding of design and construction


 in that portion of the waste water collection facilities in


 North Branford.  The decision to prepare an Environmental Impact


 Statement is based on the criteria outlined In the regulations


 as compared to the characteristics inherent in the project.  It


 does not represent, and I wish to emphasize this, it does not


 represent an attempt to discredit or second guess decisions that


 have already been made over the years.  Nor must It represent a


 lack of confidence in those who participated in that decision


 making.                             t                             \
                                                                  i

                It simply is an Independent federal review of the j


 project and the alternatives available to abate water pollution,


 as required by law*  The Environmental Impact Statement and
                        POST REPORTING SERVICE

                        2OS CHURCH ST . NEW HAVEN. CONN

                              624-41O2

-------
i
  accompanying newspaper summary was available to the public  in




  mid April.  The official filing date with the Council on



  Environmental Quality or the time that the clock started, in



  other words, on the comment periods and times was April 20th,



  1979.  They required forty-five day comment.  Ends on June  4th,



  and the record of this hearing will remain open until June  4th




  as well.



                There has been a significant effort to provide



  all interested parties the opportunity to participate in  the



  drafting process through the three workshops which have already



  taken place.  This is a formal end to that Informal process, but



  I hasten to add, It is not a mere formality.  A stenographic




  record is  being taken.  Copies of this record will be available




  in the local area as soon as they can be prepared.



                But, in any event, the Federal Environmental



  Impact Statement must respond to all responsible  comments entered




  Into this  record or submitted in writing within the  comment



  period.  To those people who could not make the hearing  tonight,



  the  comment period is open to June 4th, and  we will  accept  all



  written  documents  and respond to all written comments up  to that
                                               t»



  date.



                 We  recognize that this  Environmental  Impact



  Statement  is  a substantial  document  and you  all  may not have had
                         POST REPORTING SERVICE


                         2O5 CHURCH ST.. NEW HAVEN CONN


                               624-4IO2

-------
an opportunity to read and digest it completely.  Copies have

been made available in the Town Hall.  Therefore, we have asked

Mr. Walter Murphy to provide a brief summary and relate the

principal finding of the report, so we will all be starting from

a common ground.  In an attempt to try to simplify the draft

Environmental Impact Statement, we prepared a newspaper tabloid

summary which we attempted to mail to everybody within the

North Branford area.  Some of you may or may not have received

a copy.  The attempt was to try to get this information to you.

               After Mr. Murphy has provided us with a brief

summary, we will move on to statements, your statements, the real

reason that we are here, and in the interest of allowing every-

body an opportunity to speak, we must request that you limit your

verbal presentation to a summary of your remarks and you will

have the opportunity, if it's not prepared tonight, to submit a

full text  for the record.  So, without any further ado, I will

call on Walter Murphy to provide us with a summary of the project

and the Environmental Impact Statement.
               MR. MURPHY:  As Indicated on the agenda that was

handed out this evening, basically, I.will address briefly the

purpose of the BIS, the approach that was taken in preparing the

EIS and I  will discuss the recommendations of the EIS.  I will

attempt to keep this brief and focus most of the attention on the
                        POST REPORTING SERVICE
                        205 CHURCH ST . NEW HAVEN CONN
                              6Z4-4IO2

-------
recommendations, so that I may answer questions later on those
recommendations.  The purpose of the BIS for North Branford, was

basically to resolve EPA funding decisions on whether or not to

commit federal funds for the construction of sewers.  As you are

aware, the Town Is in the process of applying for sewer construc-

tion In three areas.  A, B and area 0.  The Initial sewer areas

indicated on these figures in area A, was submitted and was

approved by the EPA for funds for construction.  The initial

sewer area in area 0 was also reviewed and approved by the EPA

for funding.  The Initial area In area B for sewer projects, which

the Town was in the process of applying for funds, was reviewed

by the State EPA, and the decision was made to prepare an

environmental impact statement on that portion of the town's

projects.

               This necessity was prompted by both the require-

ments to demonstrate that the project was the most cost effective

solution to the problem in that area, and also the most environ-

mentally sound project.  The latter reaulrement being and Bob

mentioned, the results of the EPA policy.  The approach taken was

the easiest as described in the outline, which I will briefly go

through.

               First of all, we placed great emphasis on demon-

strating the need for an area wide project in the community.  We
                        POST REPORTING SERVICE
                        205 CHURCH ST.. NEW HAVEN. CONN.
                              624-41O2

-------
	ZJ


looked for evidence to see If there was water disposal problems


in the North Branford area.  The first step in the process was an


extensive water quality sampling program, as most of you are

aware.  And in the spring of last year, we sampled at some

fourteen locations in the community on four different occasions

for numerous substances In order to indicate the presence of
                                       <
possible contamination from waste water. The results of this


waste water survey Indicated that the most populated areas were


areas number 9 and 13.  The second source of information that we


used in determining possible needs for an area wide project, was


the available soil information  that we had from the soil conser-


vation service.  The third area upon which we received informatlor


regarding the needs of the community came in the form of a


questionnaire mailed town-wide.

               In the questionnaire, which we received 557

responses, completed, which constituted eighteen percent of the


total mailing, a number of areas  Indicated a significant response


to the question, are you  experiencing problems with your septic

system.  'These figures on the screen reflect the percentages of

the neighborhoods in which the  responses were yes, we are experi-


encing problems with the  septic system.

               The fourth source  of information was based on


field observations conducted by both our engineers and our t:raine
                        POST REPORTING SERVICE

                        205 CHURCH ST.. NEW HAVEN. CONN.

                               624-4102

-------
 	8

 staff, and also, to a limited degree, by the Connecticut Depart-

 ment of EPA.   Prom these sources of information and from the

 Information that citizens provided us through the workshops, we

 developed a composite of the problem areas in the community.

j These problem areas are indicated on these figures.  These

 problem areas were also indicated in the newspaper tabloid you

 received, and they are the Arthur Court area, the White Hollow

 area, the Green Acres area, Miller Road and Grant Road, Jerz Lane

 Brook Lane and the Surrey Drive area.  After our identification

 of problem areas, the second area was the analysis of alternative

 solutions to the problem.  In general, we applied four conceptual

 alternatives to the problem areas in the community.  These four

 are indicated basically on the screen and I will go through them.

                Alternative number one, is the concept of on-site

 rehabilitation of existing septic systems.  By this concept, it

: was assumed that we were applying a community sponsored program
i
 of financing rehabilitation of those systems which were experi-

 encing problems.  The second conceptual alternative was the

 concept of connecting those homes and problem areas that were

 experiencing water problems to a community sepfelc system where

 leaching could be accomplished over the property, where the

 problem was experienced.

                The third conceptual alternative consisted of the
                         POST REPORTING SERVICE
                         205 CHOm.H ST . New HAVEN. CONN

-------
                                                            	9.
concept of limited sewer systems.  By this, we analyzed the
concept of construction and sewer systems to service simply

problem areas.  This concept would have included funding possibly

for the major element of that system, with the community still

providing funds for some portion of It.

               The fourth conceptual alternative consisted of

what is called conventional sewer systems, basically a concept of

area-wide sewer systems throughout areas B and the remaining area

C.  For each of these alternatives in that these areas indicated

on the screen, we conducted both cost effective analysis and

overall impact analysis.  These were indicated in a preliminary

screening.  We will return to the cost figures for any discussion
you may have.  For the purposes right now, we simply are going

quickly through it.
               On these tables we have indicated the concept of

cost effectiveness of the alternatives under consideration.  We

are considering total cost for the project.  The cost borne by

everyone,  also for these alternatives, we evaluated in a sense

the environmental impact.  On at least two tables, the one that

has Just been shown and on this one, basically, this is the
environmental Impact report.  From the preliminary screening,

we then move on to the requirements of the more specific alterna-

tives in the problem areas under consideration.  In this case, we
                        POST REPORTING SERVICE
                        SO5 'IHURCH ST . NEW HAVEN. CONN
                              024-4IO2

-------
      	_   					  ..  	 		.....10


 move to  the recommendations that  you will  find  in the  Environ-


 mental Impact  Statement,  and  I  would like  to go through  these
ij
•j
il with the three major problem  areas.  In the so-called  Poxon area
': which corresponds basically with the southern portion  of the
•j
i| town B area, included in that area, which the town  would have

i!
• applied for grants for construction of sewers, we analyzed  the


 conceptual alternatives we Just mentioned.  We analyzed  this


 concept and found it to be unfeasible in that portion  of the


 town, due to the density of the population  in the outer  court


 area and due to small lot size that was inherent in those areas.


                In the Poxon area, the community septic system


 notion was also evaluated, but found to be  expensive individuallys


 in terms of what the actual home owners would have  to  pay.  In


 the Poxon area, we also evaluated the concept of a  limited  sewer


 system, a sewer simply serving those streets which  had problems


 at this point in time.  And, we found this  also to  be  an expensive


 alternative.  In addition, in a preliminary screening, the  con-


 cept of conventional sewers was also expensive.  Prom  the pre-


 liminary screening, we move toward a closer look at the  actual


 problems that we have experienced in these  areas and to  the


 recommendations of the project, which the EPA would participate


 in the funding.


                The Environmental Impact Statement recommendations
                         POST REPORTING SERVICE

                         .*O5 CHURCH ST . NEW HAVEN CONN

                                GZ4-41O2

-------
	1		


    for the Poxon area include the basic intercepted sewer line,

    which is indicated on this draft by the blue line.  Also, the

    side street sewers are indicated in green.

                   We will return later to a comparison of these

    concepts of the Environmental Impact Statement recommended

    projects and the relationship to the town proposals in the

    initial B-l area.  This does not preclude sewering of other

    streets in  the  area,  but rather they are the ones  the EPA will

    participate in  funding at this time.  We will be available to

    discuss this after we have the other draft,  which  describes the

    original town project at the end of the  presentation.   In the

    other areas of  the lower valley, specifically the  area of Jerz

    Lane, Miller Drive and Grant Road,  these four alternatives

    previously  mentioned  were evaluated and  none  of  them were found

    to be particularly appealing in  terms  of either  costs  and/or

    environmental impact.  These  areas  have  been  included  in  a
                            \
    secondary recommendation  of  the  EPA  Statement that further

   studies on  on-site rehabilitation or some other concept be

   explored, and particularly of the step one planning study in the

   future.

                  The second recommendation then for the Poxon area

   was construction of these limited sewer systems,  which we will

   describe in greater detail after this presentation, and basicallyi
                          POST REPORTING SERVICE
                          1OS CHURCH ST . NEW HAVEN. CONN.

                                K24-4IO2

-------
 	,	12


 closer study if the town ia willing to pursue this of basic


 planning for the remaining areas.

                In the next large area of town which we are con-


 cerned with, the White Hollow area, we also provided through the

l|
|j screening process for four concepts.  The four concepts that
i!
 were evaluated in the White Hollow area consisted of on-site


 rehabilitation alternatives.  These alternatives we feel have


 potential in this area.  However, we feel that in order for the


 community to apply for an actual program of design and construc-


 tion, more engineering would be required, and this we would


 anticipate would be a part of the step one In that area.


                The second alternative that was evaluated was


 the concept of a community sewer system, discharging Into a


 septic leaching field.  This also has potential, but as you will


 note later, under the present assumption on our part of funding,


 it proves to be expensive.  The third concept of a limited sewer


 system carrying waste water out of this area of town, this area


 here, this is the one we are referring to, carrying waste water


 out of this, area of town was eliminated due to expense and also


 due to the lack of wells within the upper valley.  The fourth


 conceptual alternative was found to be more expensive and


 unwarranted in terms of the stated needs and the environmental


 impact.
                         POST REPORTING SERVICE

                         2O5 CHURCH ST . NEW HAVEN. CONN

                                024-/1IO2

-------
                The Environmental Impact Statement recommendations

 for the White Hollow area resulted in the following.  After

 further analysis, it was recommended that step one work, basic

 engineering work, on the concept of on-slte rehabilitation or a

 community leaching system in this area as indicated by the

 graphic, would be the best step for the community to take.

                In the last significant problem area of the

 community, the Green Acres area, we also screened several con-

 ceptual alternatives.  In this area,  two rather than four con-

 cepts  were evaluated, due to the proximity of this area to a

 sewer  system in an adjacent  community.   The basic alternative

 evaluated  here was the on-site rehabilitation alternative,  which,

 again,  seems like a logical  path to take in terms of expense and

 in terms of environmental impact.   But,  to precede directly to

 the design and construction  would require  additional step one

 work and would envision other areas that would  also  be  Included
                        i
 in the  overall study  of remaining problems  in the community.

               The second alternative that was  addressed  in  this

 area was the concept  of a local sewer.  By a local sewer  is

meant that a small sewer system would ,be constructed in this area

which would connect through the sewer system in the adjacent

community of North Haven.  During our calculations on cost of

local a9wer systems, it was demonstrated that it would be an
                        POST REPORTING SERVICE
                        2OS CHURCH ST NEW HAVEN. CONN
                              624-41O2

-------
 expensive system because of grant eligibility.  A  sub  alternative

 was evaluated under the concept of a pressurized sewer system,
j
i which would be able to connect two interceptors on Cllntonville

 Road, and we have costed out this alternative and  will also  have

 this information to show you.  The recommendations for the

 Green Acres area in light of the information we had, was  that

 this area should be included as part of this general step one

 study on remaining problem areas, with a closer look perhaps at

 the concept of rehabilitating the septic systems in that  area or

 exploring Innovative alternatives such as a pressure sewer system

 which might not prove more grant eligible than a conventional

 sewer system in that area.  As a result of this environmental

|i impact statement project, we are recommending what we  believe to
il
 be a viable unlimited sewer project for the Poxon  area.

                This sewer project would consist of a basic

 interceptor which would service those areas which  the  town has

 described as B-l and B-2 ultimately, and the immediate construc-

jj tion of local sewers in areas where there is a demonstrated  need.

 They are indicated on the graphic.

                The concept, however, •nvisions, that sewer service

 would be provided to those areas that were described as B-l  and

 B-2 in therearller part of the presentation.  At this  point  in

 time, however, federal participation would be limited  to  these
                         POST REPORTING SERVICE
                         205 CHURCH ST . NEW HAVEN. CONN

                               G24-4IO2

-------
 sites indicated on the graphic.  That is not to say other parts
 could not be constructed by the community if they decided.  The
 second major recommendation of the Bnvlronmental Impact Statement
 report would be that those problem areas for which the
 Environmental Impact Statement was unable to specifically recom-
 mend, a program which would be impllmented immediately for those
 problem areas should be studied as part of an overall step one
 basic planning study.
                We believe that through these two alternatives or
 these two recommendations,  that the community can solve its
 immediate and long term waste disposal problem.   I will turn it
 back to  Bob.
                MR. MENDOZA:   For those people who have Just
 arrived,  I would  like to  stress  again,  the public comment period
 is  open  until June 4th.   People  who  do not wish  to make a
 statement this  evening, but wish to  submit comment in  writing  are
 encouraged to do so up until that date.  Because  of the size of
 the  group we  have  here tonight,  I would  like to have our
 statements and responses presented in rather an informal way.
 I would"like  to ask if there are any local or state officials who
 are here  tonight who would like to make a statement on behalf of
their group?  If there is anyone here within that capacity,  I
would like them to state their name and who they represent and if
                       POST REPORTING SERVICE
                       2OS CHURCH ST  NEW HAVEN. CONN
                              6Z4-4IO2

-------
         	.	16



| they could make their statements loud enough so the reporter can



 hear you, we will greatly appreciate it.  Is there anyone here



• representing any State or local agencies wishing to make a

i

1 statement this evening?

i

                A VOICE:  We are here, some of us, but we don't



 represent anybody.



                MR. MENDOZA:  You will all have an opportunity to



j present yourselves as interested citizens if you wish to do that.



 Anyone who would like to make a statement, please list your name



 and address for the reporter.  Any statements?  How about



:, questions?



                MS. BIGELOW:  Mary Bigelow, Country Side Circle.



 It used to be Circle Drive.  I am interested in the two-way



 sewer program and I have been talking with the regional planning
!'
Ij

 agency about the EIS study, and they do not know what the status



 is with their program.  If we apply for money, is this the



 executive plan or would they have to proceed from there, what



 would they do?



                MR. HOGAN:  The State Department of Environmental



 Protection is looking at communities such as Np,rth Branford in



 two directions.  The first would be to go with the regional



 planning agency, secure a grant from them and develop an expensive



 plan.  The other alternative to that plan is to do It under a
                         POST REPORTING SERVICE

                         205 CHURCH ST NtW HAVEN. CONN


                               624 4IO2

-------
201 study,  which  is  a federal  and  state grant system that  are

seeking  grants  for the construction  of these  sewers.  We are

allowing 201  study,  which  would  be basic engineering studies to

look to  the engineering solution to  the problem identified on

Miller Road-Grant Road to  Include  those sewer programs.  They

will -allow  you  to develop  an expensive summary there and go even

further  into  the  development of  a  sewer program.

                MR. MBNDOZA:  Whay  type of grant is  that, is that

a proportionate grant  such as  a  federal and state program?

                MR. HOGAN:  This  wouldbe seventy-five percent

federal,  fifteen  percent state and ten percent town.   There would

be a requirement  that  the  town put out ten percent  of the  dollars

                MS. NBWHERRY:   Phylis Newberry,  Town Council/

Sewer Authority,  and I am  more here  for the sewer part of  it.

I am not  clear  on one  thing about  the  Poxon area.   On your map,

you showed  the  interception going  over the Bast Haven line, but

you don't show  the —  how  It would be  served by sewers.  There

are problems  in that area  right  about  where your blue  line  goes.

There are other problems right along that  border there.  People

who live there  feel they really need the sewers.  Why  is there

not anything done in that  area?

               MR. MURPHY:   I will mention this one briefly and

then refer to another.  The basic purple line in our Environmental
                        POST REPORTING SERVICE
                        JOS CHURCH ST . NEW HAVEN. CONN.
                              624-41O2

-------
	ia

 Impact  Study recommendations  Indicate  that  major sewers  which

 will draw in a large  area,  that  the major front  sewer is called

 an interceptor,  which is  an element you will  be  applying for in

 federal and  state  grant money.   And, as such, it is  accepted as

 an interceptor.  At the time  of  our proposal  for a complete

 sewer program in the  area,  there was a temporary funding availably

 for side streets.  We, through the Environmental Impact  study

 will make a  determination which  streets by  consideration of need

 will be eligible for  the  funding. In  relationship to the streets

 indicated, we received Information from the sources  I mentioned

 earlier, demonstrating a  need.   Those  sources being  basically  •

 Water Ouallty Survey, the soil information  that  we had,  a

 questionnaire that we mailed  and the workshops that  we had.  At

 this point in time, when  we wrote the  Environmental  Impact

 Statement, we could not substantiate to the degree necessary by

 the EPA regulations,  an Immediate need in those  areas.  Joe has

 a slide, which I believe  shows some of the  streets so you can

 see the differences in what was, I believe, the  town proposal

 for the Initial sewer area  for which they sought funding for both

 the basic interceptor line  and also for laterals, which  Included

 Merit Drive, Katherine  Street and Judson Drive.   You may also

 notice  we have included Dorie Lane.

                This  constitutes  the  differences  between  the
                        POST REPORTING SERVICE
                        ?O5 CHURCH ST . NEW HAVFN. CONN
                               624-4IO2

-------
  information we have been able to acquire  on  these  areas  of

  immediate need and what the town proposal for  that area  would

  have been.  This is based on the information we have  been able

  to obtain through the elements of the Environmental Impact
                                                                    i
  Statement survey.


                 Another point I would like to make is  that the

  interceptor pipe would not be restricted  so  that it could not

  serve adjacent areas.  It would still be  able to in the future,
 i|
 ;j but its capacity now is to serve the town B-l and B-2 areas
 i|
 : which would include the areas of Katherine Street, Judson Drive

 j'and portions,  I believe,  and those areas not drained in East

 ,; Haven already,  What is at  issue here is the difference between
 jl

 lj that proposal  and our recommendations.   Number one, the inter-

  ceptor sewer we are  recommending would  not have the capacity at

 jthe very  trunk to go into the middle valley.   Number two, the

  laterals  for which we  have recommended  funding Include some  of
                          i
 .1
 jj those which you sought funding, exclude  some  which  you sought

 I funding and there  is one that you had not  sought funding  for.

 The differences between the design of the  interceptor  sewer  as

  it exists within the town plans at this  point in time  and our

 recommendations, consist of primarily of reducing the  very trunk


 of that pipe so as to preclude the upp«» valley.  The  other

 difference involves the question of those  lateral sewers for
                         POST REPORTING SERVICE
                         70S CHURCH ST . NEW HAVCN. CONN
j                               B24-4I02


i

-------
 	20.

 which you would seek this grant eligibility.   Perhaps  Bill might

 have some insight depending  on the environmental  impact  state-

;: ment as to how these minor differences would be reconciled.
,i

[j Those areas Immediately adjacent to the pipe are  not precluded

li ultimately and one of the purposes of this meeting Is  to receive

i! further input.

                A VOICE:  What do you mean by Middle Valley?

                MR. MURPHY:   We have referred to,  as the  Middle

i Valley, throughout the Environmental Impact Statement, as an

11 area from approximately here, up to about here.   This  was indi-

 cated as the ultimate sewer  area In the B area of the  Town

 proposal.  The area we are talking about provides sewer  service

 for these areas In here.  The interceptor as we envisioned would

 not include capacity for the extension of what I  have  termed,

 Middle Valley, but would have In its design, capacity  for this

 area here.  The basic difference is in the recommendations for
ii
! the construction of lateral  sewers on side streets.
.1
                MS. NEWBERRY:  The reason I am  asking Is  somewhere

 in this report, I did read the report all the  way through, but

 only once, so I am not quite sure.  You said something about

 building north of Mile Road, a development north  of Mile Road.

 When you talk about that valley, you are talking  about east of

 Totoket Road and west of Deforest Road and that area  in  there?
ii	 ,	            __         _        _T	
                         POST REPORTING SERVICE
                         2OS CHUHCH ST . NEW HAVEN. CONN
                                R24-41O2

-------
                                                                 21
 That  is  the  area that  the army engineers planned to flood so

 that  it  would  not flood  East Haven.   How would you be developing
i'
 that  there?
j                 MR.  MURPHY:  That  area  we are not providing sewer

!j service for.  As  I  described,  we  are aware  there is a proposal

 for the construction  of  a damn in the  middle valley.


                 MS.  NEWBERRY:   Where did  you get  that  proposal?

                 MR.  MURPHY:  We are aware of that through  the

 soil conservation office.  The ultimate  decision on that  damning

 proposal I am not certain of.   Has this  moved beyond  that?


                 MS.  NEWBERRY:   I mean how firm do you  believe

 that what we call phase two and phase  three in this area  or

 sewers in North Branford, you  know, how  firm —


                MR. MURPHY:  I  believe  we  are  talking,  again, we

 are talking about two and three, we are talking  about  this area

 in here.  What is the question?


                MS. NEWBERRY:  How firm do you  think the sewer

 authority plans were, phase two and phase three?


                MR. MURPHY:   The only expression we have had of

 that phase two and phase three program, was the capacity to provid*

 in this design element of the  interceptor, a long range plan.

 They wex-e  included in the engineering report.

                MS. NEWBERRY:   The  long  range plan being that map?
                        POST REPORTING SERVICE

                        205 r.HVUt.H ST. NEW HAVCN. CONN

                              I-.! 4 41O2

-------
                MR. MURPHY:  Yes.


                MS. NEWEERRY:  On July 23rd, 197^, at the Sewer


 Authority meeting — you understand I have been on the Town


ij Council for eight years, so I have been a member of the Sewer


,i Authority from the beginning.  I have here the minutes of the


ji July 23rd, 197^ meeting.  It reads, "As requested, Mr. Platerty
i
i
j submitted for review to the council, a very rough map indicating

II
ij the future sewer service in the town.  The map showed the three


ij phases of the sewer program."  And then, it says that the matter


jj was referred to planning and zoning.  I do not recall any formal


ij action ever taken by the Sewer Authority on phases two or three.

1
 Do you have a record of that somewhere?


I                MR. MURPHY:  The only item we do have is the plan


;as we understand it, which the community would be applying for


i construction, in the portion of the interceptor, which shows


|| twenty-inch pipe and eighteen-inch, which is there to provide
•}

j; future service for the upper valley area.  The EPA had to make a


|decision on the element of the interceptor as to whether it  was


 Justified, and their decision was it was not necessary and that


 is what their decision is.


                MS. NEWBERRY:  Let me put it this way.  I think
|this is an accurate representation of the way we  look  at  it,  and



iwe listened to the advice of the engineer who said  this is  being
. .j


                         POST REPORTING SERVICE
                         2OS CHURCH ST . NEW HAVEN. CONN
                                C.24 4102

-------
 	23.

 built  for  fifteen  years.   I  understand  you  are  saying now you

 only build them  twenty  years.   We  are talking about  fifty years.

jj But, every time  you  dig up the  streets  and  along the river you

 disturb  the natural  systems  and existing habitats,  and you might

 as  well  put in pipe  of  sufficient  size  to take  care  of the

 contingencies  for  the next fifty years, as  the  town plan did,

 and we did not change that part of the  specifications.  We did

 not change the size  of  the plan because who can predict that we

 might  not  need a pipe that size at some future  time.  You might

 as  well  have that  size, it does not cost that much more.

                MR0 MENDOZA:  There has  been a change essentially

 in  the EVA policy  with  respect  to  the planning  period associated

 with the construction of interceptor sewers. Mr- Chester

 Jenowskl will  respond to your  question.

                A VOICE:  What  was  changed?

                MR. MENDOZA:  It was a change in the policy with

 respect  to the planning period  associated with  design, for fifty

 years  and the  twenty years.  I would like to have Chester respond

                MR. JENOWSKI:  The  main  reason that the change was

 made  is  that the EPA has found  through  a study  they conducted

 nationwide, that it  Is  no more  expensive to put in additional

 facilities after twenty years  than it would be  to put in those

 facilities for a fifty  year  design, and that by limiting it to
                         POST REPORTING SERVICE
                         205 CHURCH ST . NEW HAVEN. CONN
                               624-41O2

-------
  	.	2.4k

I  twenty  years,  you eliminate  a  lot  of potential  environmental

'i  impact  and  a lot of potential  secondary  growth, resulting from
i!
jj  providing that capacity  immediately.  As I  said, there  was a

!:  study done  nationwide and this is  the result  that they  have come
i
il  up with.
j!
|j                 MS. PITCH:  Joan Pitch, Clintonhill Road,  I am

  also Chairman  of the Planning  and  Zoning Commission.  I would

  like to ask what is the  pipe size, that  is  the  reduced  size that

  you are proposing?

                 MR. MURPHY:   Prom this portion to this portion

!  here, there are, I believe,  twenty and eighteen-inch, and
|
  twelve-inches  most of the distances beyond  here.  These twelve-

  inches  is obviously the  twelve-inch portion of  the pipe Just

  west of Totoket Road up  to Arthur  Road,  so  this is obviously

  adequate to supply drainage  needs  from that point on.   At issue

  here is the question of  the  eighteen or  twenty-inch pipe.  The

  conclusion  of  the Environmental Impact Statement is that  twenty-

  inch pipe is too large in that it  is sized  to provide capacity

  for much of this area for which there is no demonstrated  need.

  This is the portion which would have to  be  re-examined  prior to

  constructing this basic  interceptor sewer.  I am not an engineer

  and I  am not certain whethsr this  would  be  twelve or fourteen-ineft

  pipe.   That would be an  engineering judgment.  It would be sized
                         POST REPORTING SERVICE
                         2OS CHURCH ST . NCW HAVEN. CONN.

                                r,24-4IO2

-------
                       		25
 to compliment the remaining twelve-and ten-Inch pipe.  It would
 be reduced to include that little valley segment, but I am not
 certain of the size other than twelve or slightly larger.
                MS. PITCH:  How many homes, businesses or indus-
 tries should be able to be served if you reduce this pipe size?
                MR. MURPHY:  As I pointed out earlier, it would
 be areas B-l and B-2.  In a preliminary analysis of those figures
 I believe there is approximately three hundred homes in the area
 presently, and in checking the design as it exists,  there 5s
 approximately, I believe, a capacity for that amount.
                MS. PITCH:  How about some estimated  percentages,
 are you suggesting a twenty-five  percent growth factor?
                MR. MURPHY:  A  potential  for one hundred percent
 growth,  in terms  of ~ in terms of present  zoning.   The question
 remains  whether that area, B-l and B-2 will remain in that
 particular zone.       ,
               MR. MSKDOZA:  Would you like to  see the final
 impact statement relating to the existing zoning versus what
 could potentially happen  if zoning were to change?
               MS. PITCH:  I think it,would he helpful for the
community to know what the potential for growth is.   I think
this was a big factor in the proposal as it went along.   I think
It was a big factor in the proposal  on the referendum held on
                       POST REPORTING SERVICE
                       iOS CHURCH ST . NEW HAVEN. CONN.
                             624 AtOZ

-------
 Section C.  I believe the potential growth factor In North

 Branford would serve more than Just the need of Information for

 the people In terms of sewers, and I think It would be certainly

 worthwhile.

                MR. MAC MILLEN:  My name is Dana MacMillen.  I

 want to know for the people that are not going to get the sewers,

 is your group going to give them, these people, any information

 on how to keep our sewer system running good now?  I have never

 seen any bulletins anywhere in relation to this.

                MR. MENDOZA:  Do you mean maintenance of existing

 on-site sewers?

                MR. MAC MILLEN:  Yes, I have never seen anything
I
 about what should be done and how to maintain it.

                MR. MENDOZA:  I think we could Include in the fina

 Environmental Impact Statement a recommendation with respect to

 the operation and maintenance.

                MR. MAC MILLEN:  I have never seen this on the

 local level, state or anywhere else, and I think this is half

 the problem.  People come from the city and they think they can

 Just throw anything down the drain and it will .Just go away.  If

 they tried to educate the people years ago, flome of this might

 have been elevlated.

                MR. JENOWSKI:  Have you checked with the regional
                         POST REPORTING SERVICE
                         20-> CHUUCH <>T . NEW HAVEN. CONN
                               
-------
 health difltrict to see If they have pamphlets on the maintenance

 of septic systems?


                MR. MAC MILLEN:  I have not been really checking


 around.  I try myself not to throw bad stuff down the sewer and


 I do everything that Is right that I was taught from my parents,


 because we always lived In the country.  But, I have been talking
                                      r

 to a lot of people and some people seem to think the ground can


 take anything.  They don't even know how sewers systems work.


                MR. JENOWSKI:  I would suggest you get a hold of


 the regional health district.  If anyone should have any infor-


 mation, they should.


                MR. MAC MILLEN:  Maybe,  when you present stuff


 like this,  you could also have things to push on the people to


 say here  is  how you can protect yourself from troubles.


                MR. MENDOZA:   That  is  a  good point.   What is the


 name of the  local  health  district? East Shore Health District?


                MR. MAC MILLEN:  They  are not  down here trying


 to  educate the people.  They should be  here saying this  is  how


 it  should be done.  You know,  we have been  hearing a  lot  about


 sewers  and I don't  know how  muen money,  at all  Is spent trying to


educate the public  as  to how to really  upkeep  the present systems


               MR.  WONTOREK:  My name is Thomas wbntorek, I am


Town Manager.  Just In  answer to this gentleman's Question, the
                       POST REPORTING SERVICE

                       2OS CHURCH ST . NEW HAVEN. CONN.

                              624-4102

-------
 	28.


 East  Shore District Health Department has  an  office  1n Branford


 and you  can  call  there  and they will mail  out information  to  you


ji as to how to maintain and what to do with  septic  systems.   I  also

ij
ji have  another question.  In the proposal  Included  in  the draft

ii
 Environmental Impact Statement, it shows the  areas that will  be


 funded by the federal government.  Just  to clarify,  this does not


 preclude the Town from  adding other streets at the Town's  expense


 to this  system after the time of construction?


                MR. MENDOZA:  I believe that Is correct.


                MR. WONTOREK:  Another question.   If  that is


 possible, would it be possible for the town to retain the  larger


 size  going into the East Haven, with the town sharing the  addi-


 tional cost, the  town bearing the additional  cost?


                MR. JSNOWSKI:  No.  It has been determined In the


 impact statement  that a larger pipe In that end of the Inter-


 ceptor could have a detrimental environmental effect on the


ij central  valley.   We would not participate  in  any  project that


 provided capacity for that area.


                MR. WONTOREK:  You would  not participate in that,


 but you  would continue if we  Just extended  the laterals?


                MR. JENOWSKI:  Within the recommended service  areas,,


 yes.  I  think there is  someplace in our  report here, an answer to


 this  gentleman's  question, that If we are  going to go to some
                         POST REPORTING SERVICE

                         2OS CHURCH ST . NEW HAVEN. CONN.

                               624-4IO2

-------
sort of solution other than sewers or community sewers, that then


must be a town managed engineering and maintenance program to


assist local residents with septic systems, am I correct?


               MR. MBNDOZA:  Yes, that Is right.


               MR. MURPHY:  The report here addresses first of


all, the questions of the sewer system that the federal govern-
                                     r

ment Is willing to participate In, recognizes that there are


other problems that will remain that will not be solved by the


sewer systems, but also could not be addressed directly In terms


of construing something tomorrow in terms of federal funding.


Obviously, an individual could start tomorrow taking action to


improve his own system.  In order to address those unanswered


questions, the Environmental Impact Statement has recommended


that the town could apply for a study which would address those


loose ends so-to-speak.  In order to obtain federal funding, as


I understand it, the City must implement these programs or


actually renovate some septic systems, for example, and this


would have to be sponsored by a community program.  An individual


could not simply apply to the federal government, so it would


represent a commitment on the part of the community to address



these problems in this way.


               The first logical step which would be started
 very  shortly, would  be  to  introduce a study of how these approach
•s
                        POST REPORTING SERVICE

                        205 CHURCH ST.. NEW HAVEN. CONN.

                              624 4IO2

-------
 			 			3Q


 might be  done.  But, the actual implementation of ouch  a program


 were It to be found feasible, would require commitment  over the
ii
'i
jj long-run  of the town.

||                MR. HOGAN:  The program would basically  follow
II
 the intent of the sewer ordinance program  and that  is why  we are


 recommending or would like to see the town do a  sewer program  for


 the remaining areas of the town on the new 201 study.   And, the


 same question you are asking, sir, concerning maintenance  of


 your existing septic systems would be addressed  and a program


 could possibly be developed under that 201 study to develop a


 town-wide mailing system or distribution system  of  Information


 to all residents with septic systems as part of  the sewer  program

                MR. MAC MILIEN:  Would this take  place or is it


 going to  be something where somebody has to go and  dig  this out


 of a book and find the information?

                MR. HOGAN:  Several towns in the  State of Connec-


 ticut have already developed a document similar  to  what you  are


 seeking.  It  is  a four or  five page  document.  The  Town of Orange


 has  done  such a  program, and I believe  they have mailed It for


 easier  —

                MR. MAC MILLEN:   Does  the Town  do this  or Is  there


  State  or  federal money?

                MR. HOGAN:  The  development of a program such as
                         POST REPORTING SERVICE

                         70S CHURCH ST NtW HAVEN. CONN

                                6^4 4IO2

-------
 this actually comes out of the 201 study, which would be ninety

 percent funded.  I don't know the specifics on that as far as

 mailing.

                MR. MAC MILLEN:  I think it would be money well

 spent to educate as many as possible before the problem arises.

                MS. FITCH:   Joan Fitch again, the Planning and

 Zoning Commission has discussed reduced pipe size for section B.

 At that meeting, we were discussingapproval in terms of mandatory

 referral under the State statute.   This topic did come up,  and

 at that time,  the engineer said he felt it was economically

 unfeasible  to  do this,  and it was  the Commissions feeling that

 they would  not be able  to  pursuade the town to do this,  to  ask

 for the environmental Impact  statement.   But,  on the second

 subject,  I  would like to bring up  the upper Farm River Valley,

 north of North Branford  center,  where the White  Hollow area comes

 The  proposal for section C, which  will be implemented  very

 shortly,  contains  this original  pipe  size.   I  would  assume  it was

 designed  in the  same  capacity  that  section B was  designed?  A

 large pipe size  to handle the  whole upper Farm River Valley?

 If this  Implementation of sewer  does not  go  forth, what is your

 recommendation of future expansion?

               MR. JSNOWSKI:  Are you referring to the approved  !

project in section C?
                       POST REPORTING SERVICE                         j
                       2OS CHUHCH ST . NEW HAVEN. CONN.                         I
                              624-4IOZ

-------
	32

                MS. FITCH:  Yes.

                MR, JENOWSKI:   I believe  that  Interceptor  was

 sized  for a fairly small drainage basis  and not White Hollow.

 The  lower connection  with  the  blue  line  which is now under  the

 Town proposal  was the one  that would have eventually served

 White  Hollow.   Not the  upper one.

                MS. FITCH:  That was part of section 0,  that pipe

 size capacity  for the main trunk line.   What  are you recommending

 now  for the Qreen Acres area?

                MR. JENOWSKI:   For the approved area, as approved?

                MS. FITCH:  As  the blue line shows  right now.

 What pipe size? That would have been the main trunk line for

 the  upper Farm River  Valley.

                MR. JENOWSKI:   This  area  again, would fall under

 the  recommendations of  a 201 study.  This area again would  be

 looked at to evaluate not  only a conventional sewer system, but

 on-site collection as well as  a pressurized sewer  system  that

 Walter brought up.  We  have made no recommendations as  to what

 a pipe should  serve in  that area, because we  made  no recommenda-

 tions  as to how the area should be  served.

                MS. FTTOH:  What you are  saying is  it is not to

 be included in the section C  area,  but  looked at with  a new view.

                MR. JENOWSKI:   Under the  201  study.
                        POST REPORTING SERVICE
                        2O3 CHURCH ST . NEW HAVEN. CONN.
                               624-4102

-------
               MR. BODWELL:  Johnathan Bodwell, Town Engineer.

My question Is, you are going to go ahead with section B reduced.

That is going to Include Arthur Road and so forth.  When do these

people expect to see sewers, I mean, you know, it is a mess as

we all know.  I have calls dally, just about — when can I be

relieved of this?
                                     - r
               A VOICE:  He is speaking the truth.

               MR. HOGAN:  The town presently has a grant appli-

cation in the DEP office, which will need revision because of

alteration of the sewer proposed.  There is also some additional

designing which would  have to be done.  The extension of the

interceptor —

               MR. BODWELL:  Yes, I  understand that.

               MR. HOGAN:  I am  laying out the work that has to

be done.  There would  have to be additional design and redesign

of the lower pipe section here,  which is very simple to do.  An

estimate of the Town to  do that, I would say, is maybe a month

to two months.
               A VOICE:  I am not worried  about that portion, I

am worried  about you people.
               MR. HOGAN:  If there  are no serious objections to

the  Impact  Statement tonight, and the Town does not anticipate

any, I have  already suggested that Tom  and anyone else interested
                        POST REPORTING SERVICE
                        .70S CHUKCH ST . NEW HAVEN. CONN
                               G24-4IO2

-------
in the Town, come to our office and sit down and work out a

schedule for the resubmittal of that application, redesign and

review in our office, so that we can then forward it to the EPA.

This can be started prior to the formal end point of this

hearing, or the formal comment period of this impact statement,

if there is no projection of any serious reaction to the impact

statement.  This would all be preliminary at this point.  We

would have to meet and lay out what would be revised in the

application, and then the Town would then have to go forward and

have those additional sewer designs.  We would get the redesigned

sewers in our office, and approve the designing and application

having been reviewed, and then we would immediately send it to

Boston for the step three grant.

               It might take a month or two.

               MR. JENOWSKI:  I would anticipate a very quick

turn-around time, provided, as Bill mentioned, there are no

objections to the Environmental Impact Statement and provided

the application comes in in accordance with the recommendations

of the .Environmental Impact Statement.  There is essentially no

review or a very minimal amount of review required at this point

in time for applications.

               MR. .HOGAN:  It might be possible in late August

or sometime in late September for the Town to submit bids on the
                        POST REPORTING SERVICE
                        2O5 CHURCH ST.. NEW HAVEN. CONN.
                              621.4102

-------
project.

               MRS.  CARLETTI:   In  the meantime,  people, what do

you propose for the  people who  have  so many problems, what  do

they tell their children  about  baths or  showers  or  flushing the

toilet.  What do you propose to suggest  to these people?  Do you

have any alternatives?
                                    r
               MR. MENDOZA:  I  can't offer you any  suggestions.

               MRS.  CARLETTI:   I realize that, therefore, I

suggest everybody gets off the  pot and does something about it.

               MR. MENDOZA:  All I can offer you is that we will

do everything we can.

               MRS.  CARLETTI:   We  have been hearing that for a

long time.

               MR. MENDOZA:  Could I finish please? I am trying

to lay out a schedule for you,  so  when you leave, you have  an

idea what we're talking about.  I  would  hope with the close of

the comment period as of  June 4th, and if we have no major

comments which require substantial time  to respond, we should be

able to complete the process by the  end  of the summer, consistent

with the schedule in terms of the preparation and changes in the

application and submitting it to the EPA.

               MRS. CARLETTI:   I hope not.  Have you been down

Arthur Road?  Come to our back  yards, come now.  We would
                        POST REPORTING SERVICE
                        2OS CHURCH ST.. NEW HAVEN. CONN
                              624-4IO2

-------
	36

 appreciate it if you would come and visit the Arthur Road back

 yards.   They are a disgrace and it is  unclean and unsanitary.

                MS. NEWBERRY:   In their report, they are very

 clear on the Arthur Road problem, they are aware that Arthur

 Road  is  in trouble and they do recommend —

                MRS. CARLETTI:   I understand that.  But, we can't

 really wait until August before they decide to do something.

 This  is  what I am saying.

                MRS. NEWBERRY:   We have some people who live over

 here, on the border, the border of East Haven.  Just below where

 you have the blue Interceptor  going in.  They are really quite

 concerned because they wanted  to attach — they have very severe

 problems.  They wanted to attach East  Haven right then, and

 somehow, we could not work it  out for  them.  East Haven's

 equipment was there.  Now, why didn't  you have some complaints

 from  them?

                MR. MURPHY:  In terms of the information we had,

 we did have some response from some individuals in that area.

 We are  in receipt of some requests that have been funneled to us

 by yourselves regarding people who wanted to be connected to the

 East  Haven system.  The number of responses we had from the

 questionnaires, the amount of  information we were able to acquire

 from the sanitary surveys conducted by the DEP and the total sum
                        POST REPORTING SERVICE
                        2OS CHURCH ST . NEW HAVEN. CONN
                               824-410Z

-------
	37
 of this information was not significant enough for us to make

 the recommendations at that point in time.  That is where it
 stands.

                MRS. CARLETTI:  Those folks were here tonight.

                MR. HOGAN:  We would be able to allow the town to

 submit additional information.  This recommendation as to what

 is eligible is based upon existing information collected to date.

 If the town is doing this additional redesign, and if additional

 Information is brought forth that would document the need to

 install sewers on Williams Road and whatever street the people

 are on that you are talking about, and you can convince the EPA

 and Chet Jenowski that there is a definite need, we would include

 those for funding at this point, and allow them to be constructed

 If you make a determination and you don't feel it is necessary,

 we would not be able to allow funding.  It does not preclude the

 Town from saying that we will sewer those streets for those

 people.

                MR. CHAMBSRLIN:  Howard Chamberlin,  Arthur Road.

 I have been to quite a few of these meetings.   On this 201 study
                   *
 that you are going to make, does that .include  Arthur Court and

 Arthur Road?
                MR. HOGAN:   No.  Your area would be  provided with

 a sewer system.  The areas of section B-l and  B-2 would not he
                        POST REPORTING SERVICE
                        2OS CHURCH ST NEW HAVEN. CONN
                              r.?.4 4IO2

-------
	38


 included in the  new 201  study.


               MR.  CHAMBERLIN:   In  one  of the  earlier shops,  we


 talked about the surface water  and  who  is responsible.   We claim


 that  surface water that was  coming into  Arthur  Road and Arthur


 Court was a responsibility  of the Water Company because their


 drainage is clogged up,  and by  not  maintaining these  outlets, we


 observed the brunt  of it.   The  mainstream of the water is  about


 200 feet closer  to  the houses now than  it was  ten years ago.


 These are some of the conditions that we are having right  now.


 It  is easy to see we are not going  to be helped to the extent we


 are going to get rid of  surface water.


               MR.  HOGAN:   They are not intended to.   That is


 something that had  to be dealt  with on  the local level. Through


 a Town action.


               MR.  CHAMBERLIN:   In  your report, you must have


 been  aware of the condition that existed at that time.  I  would


 like  to know from you people, what  your report said about  that,


 because there is not one mention about  how this surface water


 comes about.


               MR.  MURPHY:   The report  did not seek to determine
                                             r-

 the cause of that high  ground water other than assuming natural


 conditions.  It  was concerned with  the  performance of septic


 systems in that  area and also that  of the future.  That is the
                        POST REPORTING SERVICE

                        2O5 CHURCH ST:. NEW HAVEN. CONN

                              G24-41O2

-------
	39.

 extent  to which it  addresses  that  problem.

                MR.  CHAMBERLIN:   One condition worsens the other.

 The surface water pollutes  the  ground.   It  does not give the

 septic  system a chance to go  through the ground because it Is

 saturated.  So, the best thing  first is to  get rid of the

 surface water.  Let the land  dry up and the sewers will have a

 chance.

                MR.  MURPHY:  The purpose of  the study under the

 program was on water pollution  and not  addressed to the local

 drainage problem.

                MR.  MENDOZA:  Are there  any  other questions or

 statements?

                MRS. CARLETTI:  Pertaining to the remarks of

 Mr. Chamberlin, after living on Arthur  Road for about 28 years,

 and I know every inch of the  ground there and so does he, we have

 never had these problems before.  That  gas  line went through and

 obviously, there has been neglect of property up in the back.

 What he is maintaining and I agree with him is true, we need

 sewers, which I wholeheartedly  go for.   But, we also need some

 help.  You are the  Environmental Protection Agency.  Now, we need

 help to eliminate the problem because even  with sewers, you are

 going to have contamination here.   Because, there are cows, and

 I don't know how you are going  to get them  into the sewer water, j
                        POST REPORTING SERVICE
                        205 CHURCH ST . NEW HAVEN. CONN
                              G24-41O2

-------
  	40

  If you can't eliminate the  problem of the  water company diverting

  the water,  I donft  know how we  are going to have a clean North
i
i
1  Branford or a healthy place  for our children and  grandchildren
  to grow.   This  is  basically what  he  is  trying to say.   Had there

  ever been an investigation to find out  why the neighbors or the

  roads there have never had a problem previous to this  time?

  We have flooded cellars and back  yards  and it has been, In the

  past five to ten years, growing progressively worse.   The only

  thing they can  do  is  buy up our property dirt cheap until some

  corrective measure is taken.  Did you people ever check the

  possibility of  eliminating that water as he has suggested?

                 Both are related.   They  are relative.   In order

  to get rid of your sewer problem, you have to get rid  of surface

  water, am I correct?

                 MR. HOGAN:  If you construct a sanitary sewer

  system —

                 MRS. CARLETTI:  You would not have needed sewers

  if this problem had been corrected originally.  There  would have

  been no need for them to begin with  in  that area.  There could

  have been a pipeline put where the old  railroad line ran through.

  I don't know whether you have been down there or not,  there used

  to be an old trolley line there,  running in back of our houses.

  They are not keeping the debris out, and I believe the Town peoplb
                         POST REPORTING SERVICE'
                         205 CHURCH ST.. NEW HAVEN, CONN
                                f>24 4tO2

-------
		  	11


 have  tried calling and they have neglected many of their respon-

 sibilities aside from everything else.   Does the Bnvironmental

 Protection Agency attack these people in any way, not attack,

 but ask them for their assistance to cooperate, because we do

 have  cows  in the back and Farm River is right where they're at.

                MR. MENDOZA:  Had the town through any local board
                                    * jr
 tried to take any action to look at the draingage problem?  I

 guess it is a question of where the authority is.

                MRS. CARLETTI:  I am trying to clarify the picture

                MR. CHAMBERLIN:  That is what I would like to

 know.

                MR. HOGAN:  Prom the state level, we do not take

 active participation in basically drainage problems.  From what

 you are telling me, it is a drainage problem.  Our response is

 that  it is either an individual matter, where you can pursue it

 through a  civil action or it is a town  matter, a local matter

 and state  and government is not actively Involved.  At least not

 the Department of Environmental Protection.  If you have serious

 problems,  you should make them known to the town.  It appears

 to be a town problem, a community problem in the area neighbor-


 hood.

                MRS. CARLETTI:  Thank you.

                MS. FITCH:  I would like to compliment you on a
                        POST REPORTING SERVICE

                        2O3 CHURCH ST . NEW HAVEN. CONN

                              624-41OZ

-------
   	42


 fine study.  I think that it is very comprehensive.  I think

 that it has been very comprehensive and offered the town  a  number

 of alternatives that perhaps have been reviewed but not seriously

 studied, and I am sorry that the expanse had to be incrued  by

 all the tax payers, not only from North Branford, but the state

 and the nation.
i
                MR. MENDOZA:  Do we have any other statements or

 questions?

                MR. DePELICE:  Louis DePelice,  Green Acres area.

 I would like to see the slide for the Green Acres area.   You are

 proposing either on-slte rehabilitation of Green Acres or a

 sewer  system for an injector system, is that correct?

                MR. HOGANt  Basically.  Those are proposals  we

 felt would be done by the present study.

                MR. DePELICE:  To my knowledge, the town did do

 an engineering study and they do have drawings for a sewer  system

 connected to seetion~C  of the bonding that is  going to be approve

 I believe there is a trunk  line and all the engineering was done.

 What I want to know is, at  the rear of Green Acres there  is a

 trunk  line, a main sewer  line from North Haven,.  Have  you fellows

 reviewed  that area or  looked  into that area?

                MR. HOGAN:   Is there  a design  for a sewer system

  in  the Green Acres area?
                         POST REPORTING SERVICE-
                         2OS CHURCH 5T . NEW HAVEN. CONN.

                                O24-41O2

-------
               MR.  WONTOREK:   There  was one.   There was engi-
neering work done,  but that  is  not  part of our present grant
application.
               MR.  HOQAN:   Have  you  completed that engineering
design  work?
               MR.  WONTOREK:   Yes, that was  done.
                                   r r
               MR.  HOOAN:   I am  aware  of the  concept, I was Just
not certain  —
               MR.  WONTOREK:   It is  done.
               MR.  DePELICE:   What I am getting at is, the
government in the town  does not  have the —
               MR.  MURPHY:  One  of the problems that relates to
your question is, earlier,  it  was  anticipated that the Intercep-
tor line coming from North Haven could not only accommodate this
area, but would pick up the major  part of area C of the valley.
But, the major interceptor portion of  the design here would have
included the  flow from  the major part  of the  upper Farm River
valley, including .White Hollow.  Obviously, one can presume that
this was a large diameter pipe.  We  concluded  that  number one,
the problems  that exist in the White Hollow area were  auite
remote and could be solved by a  sewer  system that would be
environmentally sound.  The interceptor  component of this concept
would not be  accepted the way they are now.  This interpretation
                       POST REPORTING SERVICE
                       70S CHURCH ST . NEW HAVEN. CONN.
                              624-4IO2

-------
actually affected the cost of the conventional sewer system for

this area.  Our cost estimate for conventional sewer systems in

this area connecting North Haven proved to be, because of grant

eligibility, very expensive.  The costs were so high, in fact,

that EPA asked the question what about a non-conventional concept

for sewers, such as a pressurized system that would be able to

take those flows into a small diameter pipe, up hill.  This

was explored only on a very superficial level to see what the

cost effectiveness might be, because seriously, we are not

familiar with engineering costs.  Nor are we assured that the

town would want to go that route with something that was not a

conventional sewer system.

               We also costed out the concept of a pressurized

sewer system to see what the effect would be.  The result in this

particular case would be an increase in taxes to the town as a

whole.  It would amount to a first year charge to a user of this

amount, which Includes the actual plumbing going up the street

and includes charges — this amount would be every year after.

The Green Acres conventional sewer system under the assumption

that it 3s no longer eligible because it does ,not have an

Interceptor going up the valley, reflected very high costs

because of the large lots and relatively low density in that  area

Unless the town sought a different arrangement of financing that,
                        POST REPORTING SERVICE
                        2OS CHURCH ST MEW HAVEN. CONN
                              624-4IOZ

-------
 these are the costs that we developed which obviously are expensive.

 That Is why that area is included as a part of the basic re-analy-

 sis.  We are recommending for that area that it be included in
 this general study.

                MR. DePELIOE:   You are saying that the pipe is

 too large to serve that many homes in the original design?

                MR. MURPHY:   The concept for it, yes.

                MR. DePELICE:   You are talking about reducing the

 other areas because of impact.  But, to me, if you put a fourteen

 inch pipe in the ground or  a twenty-inch pipe in the ground,

 digging the hole,  the men working and putting in laterals is the

 same.   It is Just  the cost  of the pipe that is the difference.

 Now,  let's say  twenty years from now, let's say someone wants to

 come  in and develop in North  Branford.   They are going to say

 we  can't  because the system won't take  it.   So,  they go for a

 grant  and they  say let's  increase the system and go around diggin,

 up  the  streets  again.   And, these people over here,  you are  going

 to  hold them up to change the  pipe size,  because you  feel  they

 are not going to need  it twenty  years from  now.

                MR. MENDOZA:  We  are  nqt holding  them  up  any more

 than we have  already.

                MR. DePELICE:   Going  into section -C again, I have

only lived  in the  area for a couple  of years now, and I think     !
                       POST REPORTING SERVICE
                       fOS CHURCH ST. NEW HAVEN. CONN
                              «24 4IO2

-------
rehabilitating the septic system there Is totally Inadequate.

               MR. HOOAN:  I think the question that the

environmental Impact statement is basically saying back to the

town and the individuals that live up there is, are you willing

to pay $30? for sanitary service and $807 in future years to

have the connection made?  Are you and are your neighbors up

there willing to do it?  The report is saying because of the

high cost, we are not certain that the neighbors in that area

are willing to do that, to go that route, and from an engineering

standpoint, that is the correct way to go.  That is why the

environmental impact statement is recommending additional studies

be done, to find out what the town desires and what the tax pay-

ers desire in that area.

               MR. BODWELL:  Would you clarify that $300 a year?

You don't mean $300 continuous from now until forever?

               MR. HOQAN:  Every year, as a user charge.  The

assessment is spread over twenty years.

               MR. BODWELL:  At the end of twenty years, you

would simply pay the users charge?  That is really a false figure

the way you are presenting it.                ••

               MR. HOGAN:  It is a real figure for twenty years.

               MR. BODWELL:  The way it was presented —

               MR. HOOAN:  I was on the assumption it was a
                        POST REPORTING SERVICE
                        2O5 CHURCH ST. N£W HAVEN. CONN.
                              624-41O2

-------
 straight user charge, I am incorrect.  That would be for the



 initialtwenty years.  After twenty years, it would be reduced.



                MR. BODWELL:  It would be less if someone decided


 to pay off their assessment immediately without the interest


 charge.



                MR. MURPHY:  Under the different assumption of the



 assessment charge, it could be less in the tenth year but much



 more expensive in the second year.



                MR. BODWELL:  You are going to scare a lot of



 people with those figures the way they are presented.



                MR. MENDOZA:  The cost is there.



                MR. BODWELL:  I am Just saying that it should be



 explained to the people what it represents.



                MR. WONTOREK:  On that 43,000 for conventional



 sewers, is that the total project cost, town share or what?



                MR. ZENESKI:  I believe that is the total project



 cost.   But, I will verify that.


                MR. WONTOREK:  If it is, those numbers are totally



 inadequate, because the town at most would only be assessing its



 share.
                                      t

                MR. ZENESKI:  There would be very little  funding



 involved.   It would be all lateral sewers and no funding would



.be made available from the state or the EPA,  so it would be  all
                        POST REPORTING SERVICE

                        205 CHURCH ST . NEW HAVEN, CONN

                              C.24 4IO2

-------
 	48

 local costs.

                MR. WONTOREK:  I thought when you had the map up

 that it reflected federal funding?

                MR. HOGAN:  The only portion that would be ellglbl

 for funding would be the blue lines, laterals in that section are

 not eligible.  The state Is not allowing the seventy-five percent

 federal grant and lateral sewers anymore.  It was a one-time

 program, and the way grant money is going now, in the next five

 to ten years if the program goes on, we will -- these costs could

 be projected upon eligibility only on the blue lines.  The green

 would be totally local costs.

                MR. ZENESKI:  There are two alternatives here

 within the conventional sewer alternative.  One is to include

 Surrey Drive where you do indeed have an eligible portion.  The

 other would not include Surrey Drive and this would also be

 green colored and it is reflected in that table here.  You will

 also notice that the first year cost and the annual costs for

 twenty years is less than it is when you study the Green Acres

 area alone.  That is, to sewer a small area would cost  the town
I
 more per family.  What we are saying here is that as pointed out

 in  a number of  alternatives, this is a method of  comparing the

 costs  of those  alternatives.  We canmake a recommendation based

 on  this and recommend  further study.
                         POST REPORTING SERVICE
                         70S CHURCH ST NEW HAVEN. CONN
                               624 4IO2

-------
               MR. MURPHY:  That one figure shown with Green

Acres really represents one of the four options.  The others are

minor variations.  But, what happens depends upon Judgment as to

how far — well, by taking Surrey Drive out of there and putting

it back in, it effects grant eligibility as we interpret it at

this point in time.

               MR. MAC MILLEN:  You talked about not getting

involved with ground water,  well, up on Route 80, where the

shopping center is, you are going to have to deal with on-site

rehabilitation.  In that area, they have filled In the wet lands

so extensively, and they are presently doing it every day.

Whenever it rains, it floods all the stores and completely floods

Route 80.  I have lived in this town all my life and this never

happened before.  What do you do for an .area like that?  It

completely floods right around the buildings and sewage is

pouring right into the river every day.  I went to the town hall

and asked them about it and they said that they had an existing

permit to fill in the wet lands.  The wet lands are Just being

completely filled in.  What would happen, would you have to

advise the town not to continue this or what?
               MR. MENDOZA:  Any continuing practice filling

wetlands is only going to generate long term problems.  It appear^

from what you are referring to that the problem of high ground
                        POST REPORTING SERVICE
                        ZOS CHURCH ST ! NEW HAVEN. CONN.
                              624-4102

-------
                                  	50.

water might be incompatible to the buildings in that particular

area.
               MR. MAC MILLBN:  It Seems the town does not have

control over people filling in those wetlands and putting

buildings, and it is Just creating worse problems.  It has got

to the point now that once or twice a year, you can't get down

Route 80.  The water floods everything.  I don't know if you went

in the back of the shopping center, but there is an open sewer

pit that goes straight out into the river.  What could possibly

be done with something like that?

               MS. NEWBERRY: Where you tested the water, I think

you tested it further down from where he is talking about.

               MR. MURPHY:  The water color In that area was

lower than other areas in the town.  It was better than many othe

areas.

               MR. MAC MILLEN:  Sewage is going through there.

I walked in back there and the smell was so bad that I had to get

out of there.  You have to be there when itoccurs.  What is going

to happen, what would you recommend to the town, to take some

kind of  legal action to get the people that ai^e filling It or

something  like that?

               MR. BODWELL:  As far as the  filling, most of that

was given  permission prior to the wetlands existing subdivision
                        POST REPORTING SERVICE
                        2O5 CHURCH ST . NEW HAVEN. CONN
                              624-4IO2

-------
	.		51

 or something of this ca«e.  Now, the wetlands commission has

 Jurisdiction over this and there should be no more filling with-
 out a permit.

                MR. MAC MILLEN:  If you go down there, it is being
 filled every single day.

                MR. BODWELL:  There is a wetland commission and
                                    t
 they are obligated to check these things out.

                MR. MAC MILLEN:  It is definitely out to lunch.

 Someone was given permission, but they have gotten the ground

 water so high,  all the trees have died due to the high water.
 Go and  take a look.

                MR. BODWELL:  I am not arguing with you, I know

 the situation.   Some things we Just can't control.  If anymore

 filling is being done, we can control that.  A condition prior

 to this, we can't do anything about.

                MR. MAC MILLEN:  What  if they already have gotten

 permission to fill that area prior, we can't do anything about it
                MR. MENDOZA:  May I suggest we try to stay back on

 any comments that any of you may have that are not in regard to

 the recommendations to the board.

                MR. CHAMBERLIN:  I would like to know the closing

 date on the State grants for lateral  sewer plans?
                MR. HOOAN:   The closing date was probably a year
                        POST REPORTING SERVICE
                        IOS CHURCH ST . NEW HAVEN. CONN.
                              624-4IO2

-------
 	52



  a  half  ago.   I  don't have the exact  date, but  It  is  long gone.



  We have kept  open  as a result of the Impact  statement  the ability



  to give lateral funding on section B sewers.   That would be  the



  last  section  in North Branford for lateral sewer  grants  given



  in the  entire State.



                 MR. CHAMBERLIN:  That grant is  still  open for



  section B?



                 MR. HOOAN:  That is correct.  The  cost  estimates



  do account for  lateral funding in section B.



                 MR. PATIKA:  John Patika.  I  would like to say



  that  I  am disappointed with your environmental impact  statement



  and your conclusions that you have come up with on Surrey Drive.



  After all these studies, to come up  with I call a non-solution



  is terrible.  Secondly, please come  up there tomorrow.   You  are



  suggesting alternatives that possibly may put  in  a better septic



||  system.  My neighbor across the street has spent  —  my three
h
ji

||  neighbors have  spent over $10,000 In the last  ten years  to try

i!
j| to straighten out their situation.  Half his  yard  is  soaked  and

I

 it will be soaked until the first of probably July, before he



 can get in there.  I have  one-third of my  acreage  soaked  until



 the first of June, and possibly, to the mid part of June.  I



 cannot understand how you  can  come up with a  new intercepting



 system when they found septic  systems do not  solve the problems
                         POST REPORTING SERVICE

                         2OS CHURCH ST . NEW HAVEN. CONN.

                               6Z4-4IO2

-------
 up there.  Ag far  as the  coats  are  concerned,  I  agree with  this

 gentleman here.  I think  again, the figures  are  awfully  inflated.!
i
 I said  this  aix months  ago  and  you  have  not  proven to me at this

 date  that you are  not inflating the figures.

                MR. MENDOZA:   Sir, why do you feel the figures

 are Inflated?

                MR. PATIKA:   These fellows Just mentioned some  of

 the costs.   You are giving  an ambiguous  figure up there. You  say

 so much a year to  pay for sewer use taxes,  and people read  the

I newspaper and see  sewer use taxes which  the  city is paying, and

 they  figure  that this is  what you are talking about. You are  not

 talking about that. Either that  is what you are talking about

 there,  or the costs to  us to pay  for that sewer  system  when it

 gets  put in. They built  100 homes  down  in the Green Acres  area

 and they are planning to build another fifty. And, they are

 planning to  build  twenty down at  the bottom of the hill, all

 within  a half-mile of the other.  There  are  over 300 homes  not

 too far from the C section.  And  then, you say suddenly, that

 these figures  are  up, that  is what  you said before.  They asked

 people  up  in our part  of town,  saying.it was going to cost

 $60,000 per  unit to pay for those sewers and you helped  to  con-

 tinue that falsehood by bringing  out figures like this.

                MR. MENDOZA:  I appreciate your comments, but I
                         POST REPORTING SERVICE
                         JOS CHUHCH ST NEW HAVEN. CONN
                                624 4IO2

-------
  don't necessarily agree.


                 MR. PATIKA:   I know you don't.  I don't agree


i| with your figures.
|!

|j                MR. MENDOZA:   I would like to try to explain those


ij figures  if we  could,  so that you do have an understanding of


|! what they mean.


                 MR. MURPHY:   We are dealing with the Surrey Drive


  area,  something less  than ten houses.   We have costed out two


  options  that would be available to the community, not relating to


  septic systems.  Those costs are, I think, you would agree, quite


  high.  For the second year  and the third year, those costs would


  only continue  to the  twentieth year and not the twenty-first


  year.  Those costs are still significant.  In figuring out the


  computation for Surrey Drive, we also  included the likelihood


l| that there would be additional filling in between green Acres and


ii Surrey Drive.   And that would have the effect of reducing
;i
ij
jj individual costs.  There are some vacant lots there and the
i1
ii
j1 assumption is  that the sewers put in there with all likelihood
i'

  would  be developed in that  area.  This was done as an exercise


  to  see what effect this would have on  the high cost being the


ij result of, first of all, no longer having any eligibility for


  laterals and having large lot sizes up there.  Our conclusion


  when we  came away was that  the costs over the number of homes
                         POST REPORTING SERVICE

                         /os <.HURC:H ST . NEW HAVEN. CONN

                                624.4102

-------
                                            	—  	  	 -55-1

  would be substantial.



                 The costs as presented the first year and years
I!

|j two through twenty can be Justified in terms of the number of


;| costs per unit.  They were not done to scare someone, but they


|j were done to demonstrate the dilemma we found ourselves in


  looking at that kind of a solution  'for that kind of an area.


  We do not feel we can recommend that kind of a solution.  We


  feel it wouldte worthwhile to spend some additional efforts,


  locally concentrated studies on the area to see what other


  options would be available.



                 MR. PATIKA:   I am looking at very shortly, within


j|  the next year or two, a $4,000 bill to take care of my septic


  system.  I know the sewers  are not  going to come in..  If I take


  the numbers up there, and let's take these numbers,  which are


  $232 a  year,  times twenty years,  that is $4,000 or a little  bit


  more, plus another 800 some  odd,  so we are talking $5,000.   My


  neighbors  have spent twice that much at  least  in inflated figures


  over the last  ten years.   So what I am looking forward  to, I am


  not  looking forward to it, what I am seeing  in the future, unless


  we get  sewers  before too  long is  that  kind of  a bill.   And,  I    I
                                                                   i

  am talking about  three places.                                    j


                Almost everyone  of those homes  on that street      1


 has  a problem.  Whether they want to admit it or not.  The most
                                                                   I


                         POST REPORTING SERVICE

                         ,11', rHUHOI ST . NLW HAVCN. CONN                          j

                               K2t itOl

-------
 	56
                       »

 recent  cost to my neighbor across the street was over $3,000,

 in a  separate system.  You fellows have mentioned setting  up  a

|! distribution system up there, and it will  cost him  Just  about
II
 — well,  the previous owner.  The new owner had inherited  this.

 He is on  a  hill and that water has to go  someplace.  I  have  a

 similar situation,  Everything pours downhill to my property.


 And there are others also.

                Why did they start this whole thing  to begin with,

 why didn't they Just give all of North Branford sewers when the

 funding was available.  How much has it cost already, this study,

 do you  know the approximate figure, what did this study  cost  the


 government, roughly speaking?

                MR. MENDOZA:  Roughly about $85,000.

                A VOICE:  This is very important and you  fellows

!J
i! have  done a very good Job.  You don't know our town as well as
I
 we do though.  People that live here.  We  appreciate  your efforts
i!
ii but what  does the EPA stand for?  What does  It really mean?  What
i
I
 are they  for?  Are they  for the people that  live  in a town or

 are they  for the  government.  Who  do you represent  actually

 when  you  do your  study,  can you  answer that  question  please?

                MR. HOGAN:  If you  are  considering sewering the

 entire  town  of North Branford,  I would  like  you  to  take  a look

  at New  Haven  or Branford,  or  the other  169 towns  In the  State,
                         POST REPORTING SERVICE

                         /O5 CHURCH ST . NEW HAVEN. CONN.

                                624-4IO2

-------
    	 	 	.	 	      _                        cy

i  They are not —
                 A VOICE:  Branford has sewers.
'i
j;                MR. HOGAN:  Not every single street such  as you

„ are proposing.  We have limited grant funds.  Based on that,  it
it
jj all goes back to the tax dollars you pay to Washington.

II                MR. PATIKA:  I understand at one time there was
ii
i
ii the availability of tax dollars.  That has obviously —

j                MR. HOGAN:  No, the State of Connecticut  several

i| years ago, we had a backlog of federal dollars that we had not
Ii
;| committed to sewer projects.  The State of Connecticut would have
Ii
!, lost the dollars as of a September 30th date.  I believe it was
'i
jj  1976 or 1977.  If we had not committed those dollars, they would
!i
ji  have been lost and would have gone back to another fund which
i
|  would have been redistributed to other states.  In an effort not
i*
,i
•(  to  lose the funds, the State of Connecticut went to the local

i  municipalities that had sewers available for construction.  That
i
i
  is  the only reason, it is purely a political decision not to

  lose construction grant funds out of the state of Connecticut.

  It  was not really a surplus,  there was  not a massive availability

  We  could not advance other major projects fast enough,  otherwise

  we  would have lost the funds.   So,  that  is the only reason grants

  were ever given in the State  of Connecticut.

                 MR. MBNDOZA:   In every one of  these  impact
                         POST REPORTING SERVICE
                         •'>•", < Hltm M ST Nf W IIAVI N. < ONN

-------
  	58

 statements, we seem to have a group of people who are very much

 In favor of having sewers In the community and we have a group

 who do not want the sewers.  There appears to be a number of

 different factions in every study we are involved with.  We have

 dealt with issues where if you sewer a community, you can increas<

 the growth rate by over one hundred percent.  This has an effect

 on community facilities, schools, police and fire protection.

 All of these are secondary impacts related to a potential sewer

j system within a town.  I Just want to point that out.

                MRS. CARLETTI:  I agree, but you can't stop living

 can you?  You can't say we are not going to have Industry and lif<

 You might as well stop living.  You are the young people, you are

 going, to have children and you are going to have to put them

 somewhere.

                MR. MENDOZA:  I appreciate your comments.

                MRS. CARLETTI:  Thank you.

                A VOICE:  How much was the —

                A VOICE:  It costs about $85,000 more or less for

 this impact statement, but it costs the town about three million

 in additional costs.

                MR. MENDOZA:  I don't know if that numl^er Is

  correct.  I have no idea.

                A VOICE:  Well, two million.
                         POST REPORTING SERVICE
                         2O5 CHURCH ST . NEW HAVEN. CONN
                               624-41O2

-------
               MR. MENDOZA:  I don't know If that number Is
correct.
               A VOICE:  Ask this gentleman here.  Just take
this system,  five million for this system and at an inflation
rate of ten percent, or thirty percent over the last three or
four years, what does that add up to?  Forty percent of five
million is two million.
               MR. MENDOZA:  Thank you for your comments.
               A VOICE:  I think this is really good because we
are not going wile with sewers all over the town.  I only wish
we did this in the beginning.  I think it is better than putting
it through New Haven and shipping it out to the sound, and
polluting the sound.
               MR. MENDOZA:  If there are no other statements,
I would like to thank you for being patient with us and coming to
this hearing tonight and we will take comments that you may wish
to submit to us up until June 4th.  Thank you.
               (The hearing was concluded at 9:35 o'clock P.M.)
                        POST REPORTING SERVICE
                        ?OS CHUHCH ST NCW HAVEN. CONN.
                              674-4102

-------
        APPENDIX C
ARCHEOLOGICAL RESEARCH REPORT

-------
ARCHAEOLOGICAL SURVEY
NORTH BRANFORD, CONNECTICUT FACILITIES PLAN
ENVIRONMENTAL IMPACT STATEMENT
PREPARED FOR

ANDERSON-NICHOLS, INC.
150 CAUSEWAY STREET
BOSTON, MASSACHUSETTS
BY
CHARLOTTE W. THOMSON, PH.D.,
CONSULTANT IN ARCHAEOLOGY
P.O. BOX 615
NEWBURYPORT, MASSACHUSETTS 01950
617-465-5808
DECEMBER 27, 1978

-------
ARCHAEOLOGICAL SURVEY
NORTH BRANFORD,  CONNECTICUT FACILITIES PLAN
I. PROJECT

    The proposed sewer interceptor in the Foxon section of North Branford,

Connecticut shall run from the intersection of routes 22 and 80 westward to

the North Branford/East Haven town line (Map 1).

    The interceptor sewer is to be laid beneath existing streets, and cross-

country along Burr's Brook, a tributary of the Farm River.


II. FIELD OBSERVATIONS

    Where the interceptor sewer is to be placed beneath existing streets, or

through back yards subject to urban disturbance,  soil horizons have already

been disrupted by excavation for the emplacement of one or more utility lines

(Jonathan Bodwell, Town Engineer). Thus there is little or no archaeological po-

tential where the interceptor route crosses through yards or runs beneath the

road.

    As can be seen from walkover survey of the area, housing development

south of Foxon Road has been limited by local soil conditions. The areas that

have been developed are relatively high and dry,  whereas the undeveloped land

along Burr's Brook is swampy.


III. DOCUMENTATION

     David Potrier, Archaeologist of the Connecticut Historical Commission was

consulted. C. H. C. files showed no archaeological or historic sites within the

-------
project area.

    Observed field conditions were documented by consulting a number of

soil studies for North Branford,  Connecticut. The most authoritative of these

is the Soil Survey, Town of North Branford. New Haven County,  Connecticut.

(United States Department  of Agriculture, Soil  Conservation Service,  June

1969)

    Where the interceptor sewer leaves the road, its route is through soils

classified as Bowmansville silt loam and Saco silt loam. These flood plain

soils are characterized as poorly drained and very poorly drained, water

table being at or near the surface part of the year.


IV. CONCLUSIONS

    Because of the extreme wetness of these soil series, it is ineffective to

survey them for archaeological  sites,  on account of the difficulty of defining

site features in saturated soils. It is therefore expected that construction of

the sewer interceptor in North Branford will not have an impact on prehistoric

or historic archaeological sites in the project area.

    A prior archaeological survey prepared by the Connecticut Archaeological

Survey for Flaherty Giavara Associates reached the same conclusions, by other

means.
                                       Charlotte W. Thomson, Ph. D.
                                       Consultant in Archaeology

-------
REFERENCES
BARBER,  JOHN WARNER. Connecticut Historical Collections. New Haven:
    Durrie & Peck and J. W. Barber, 1838.

CONNECTICUT ARCHAEOLOGICAL SURVEY,  INC. An Archaeological
    Survey of Section B,  North Branford Wastewater System, June 1977.

CENTRAL NAUGATUCK VALLEY REGIONAL PLANNING AGENCY. Soil
    Interpretation for Urban Uses, 1969.

COOPERATIVE EXTENSION SERVICE, University of Connecticut at Storrs.
    Natural Soil Groups for Connecticut, (not dated)

FLINT, RICHARD FOSTER. The Surficial Geology of the Branford Quadrangle.
    Hartford: State Geological and Natural History Survey,  1964.

ROCKEY, J.L.,  ed. History of New Haven County. New York: W.W. Preston
    & Co., 1892.

RODGERS, JOHN. Explanatory Text for Preliminary Geological Map of
    Connecticut,  1956. Storrs: State Geological and Natural History Survey,
    1959.

U.S. DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT. Federal
    Insurance Agency. Flood Insurance Study,  North Branford, Connecticut,
    New Haven County.

U. S. DEPARTMENT OF  AGRICULTURE, Soil Conservation Service. Soil
    Survey Town of North Branford, Connecticut, New Haven County, June
    1969.

-------
   1: INTERCEPTOR  ROUTE,  NORTH BRANFORD, CONNECTICUT

,EGEND:

 //////// Poorly  drained and very poorly drained
//// ff  Bowmansville and Saco silt loams

-------
   Office of the
   STATE
   HISTORIC
   PRESERVATION

   OFFICER
   for Connecticut
     59 SOUTH PROSPECT STREET - HARTFORD. CONNECTICUT 06106  TEL- (203) 566-3005

                                             August 2, 1979
     Ms. Janet Burns
     Environmental Planner
     Anderson-Nichols
     150 Causeway Street
     Boston, Mass. 02114

            Subject:  Draft  Environmental Impact Statement
                      Wastewater Management Program
                      Korth  Branford,  Conn.

     Dear Ms. Burns:

     With respect to the  above-named project/ the State  Historic
     Preservation Officer has  reviewed the archaeological  survey
     report prepared by Ms.  Charlotte W. Thomson for Anderson-
     Nichols & Co., Inc.  and supplemental information available
     within this office.

     In accordance with the  responsibilities of the National
     Environmental Policy Act  (P.L.  91-190). the National  Historic
     Preservation Act of  1966  (80 Stat 915, 16 USC 470 as  amended),
     and Advisory Council Procedures 36 CFR 800, the State Historic
     Preservation Officer expects that this project will have no
     impact on archaeological, historical or architectural resources
     listed on or eligible for the National Register of  Historic
     Places.

     The State Historic Preservation Officer notes that  this office
     has reservations concerning the methodology employed  by Ms.
     Thomson for the identification and assessment of the  impact
     of the North Branford Wastewater Management Program upon
     archaeological resources.  That is, the research methodology
     is deficient with respect to the absence of site specific
     historic and prehistoric  documentation.  Further, Ms. Thomson's
     logic concerning the ineffectiveness of surveying for archae-
     ological sites due to the difficulty of defining site features
     in saturated soils is fallacious.  Although it may  be correct
     that the current state  of the art is deficient with respect to
     the recovery of internal  site data in saturated areas, nonethe-
     less, it is not the  spirit and intent of the National Historic
STATE HISTORIC PRESERVATION OFFICER:  The person responsible for implementation in Connecticut of the National Historic
Preservation Act of 1966 administered by the Department of the Interior, Heritage Conservation and Recreation Service, Washington, D.C.
              AN EQUAL OPPORTUNITY EMPLOYER/AFFIRM A TIVE ACTION A GENCY

-------
Ms. Janet Burns (Cont'd)      - 2 -                  August 2, 1979
Preservation Act of 1966 and Advisory Council Procedures 36 CFR
800 to concede to the destruction of archaeological data due to
methodological problems.

Despite the State Historic Preservation Officer's reservations
with Ms. Thompson's archaeological research methodology, the State
Historic Preservation Officer expects that the North Branford
Wastewater Management Program will have no effect upon archaeo-
logical, historical or architectural resources listed on or eligible
for the National Register of Historic Places.  This determination
has been made from an on-site inspection and an evaluation of
existing cultural resource data within this office.  Further, the
State Historic Preservation Officer notes that the Connecticut
Archaeological Survey, Inc., previously surveyed a similar project
area in North Branford and failed to identify any archaeological
resources.

For further information, please contact David A. Poirier,
Archaeologist.
                                Clark  J./Strickland
                                Deputy S/:ate  Historic  Preservation
                                Officer;
                                        for
                                John W.  Shannahan
DAP:aas/nk                      State  Historic Preservation Officer

cc: Anthony Ciccarelli,
    State Coordinator for Connecticut
    EPA, Boston,  MA 02203

    Ms.  Ina B.  Camblor
    CT Dept.  of Environmental Protection
    Hartford,  CT 06115

-------