Costs of Remedial Actions at Uncontrolled
Hazardous Waste Sites — Impacts of
Worker Health and Safety Considerations
SCS Engineers, Inc., Covington,  KY
Prepared for

Municipal Environmental Research Lab.
Cincinnati, OH
1983
                                                            PB84-128701

-------
                                                 EPA-GOO/Q-84-019
                                                             1983
 COSTS OF REMEDIAL  ACTIONS AT  UNCONTROLLED HAZARDOUS WASTE
SITES -- IMPACTS OF WORKER HEALTH AMD SAFETY  CONSIDERATIONS
                             by
            J.  Walsh,  J.  Lippit.t,  and M.  Scott
                       SCS Engineers
                    Covington,  Kentucky
                  EPA Contract 68-03-3028
                    EPA Project Officer
                        D.  C.  Ammon
        MUNICIPAL ENVIRONMENTAL RESEARCH LABORATORY
             OFFICE OF RESEARCH AND DEVELOPMENT
            U.S. ENVIRONMENTAL PROTECTION AGENCY
                   CINCINNATI, OH 45268

-------
                            IPtcau rtatl Instrucf.cnt on the revtrte 'itfore completing/
I. REPORT NO.
  EPA-600/D-84-019
  TIT 1.5 ANO SUBTITLE
 COSTS OF REMEDIAL ACTIONS  OF  UNCONTROLLED HAZARDOUS
 WASTE SUES—IMPACTS OF  WORKER HEALTH AND SAFETY
 CONSIDERATIONS
              6. PERFORMING ORGANIZATION CODE
7. AUTHORIS)
 J.  Walsh, J. Lippitt and  K.  Scott
                                                            . PERFORMING ORGANIZATION REPORT NO.
9. PERFORMING ORGANIZATION NAME ANO AOORESS
                                                            0. PROGRAM ELEMENT NO.
 SCS Engineers
 El 1 Grandview Drive
 Covington, KY 41017
               TEJY1A
               1. CONTRACT/GRANT HO.
               68-03-3028
              work Assignment No. 14
12. SPONSORING AGENCY NAME ANO AOORCSS
 Municipal Environmental  Research Laboratory—Gin. ,OH
 Office of Research and  Development
 U. S. Environmental  Protection Agency
 Cincinnati, Ohio 45268
               3. Trf>£ OF REPORT JNO PERIOD COVERED
              Conference Paper 6/82  - 6/83
               «. SPONSORING AGENCY COOS
                EPA/600/14
15. SUPPLEMENTARY NOTES
 Project Officer:   Douglas  C.  Ammon
C513/684-7871)
IS. ABSTRACT
 Cost-effectiveness evaluations of Superfund expenditures require consideration of
 additional costs of  protecting workers' health and  safety.  Unfortunately,  not much
 cost data has been available concerning health and  safety considerations.   This paper
 represents part of the  effo>t to identify and estimate costs associated  with protection
 of worker health and safety.   Although the findings and results cannot be  considered
 the final answer, they  will  help site management  and planning personnel  to  generalize
 health and safety cost  impacts.  The'paper is for presentation at the Fourth
 Management of Uncontrolled Hazardous Waste Sites  Conference, October 1983,  Washington,
 D. C.
17.
                                KFY WORDS ANO COCUMENT ANALYSIS
                  DESCRIPTORS
                                              b. O6NTIFIERS/OPEN ENOEO TERME  c.  COSATI Field/Group
 18. DISTRIBUTION STATEMENT
 RELEASE TO  PUBLIC
19. SECUS'T'. CUAJS
   UNCLASSIFIED
                                                                  tportl
                             il. .NO. OP

                                 27
                                               JO. SE
                                                                          33. PRiCE
 EPA Form 2230-1 (R«». 4-77)   PKIVIOUJ COITION i*

-------
                      NOTICE

Th\s document has bean reviewed in accordance with
U.S. Environmental Protection Agency policy and
approved for publication.   Mention of trace names
or commercial products does not constitute endorse-
ment or recommendation for use.

-------
                COSTS OF REMEDIAL ACTIONS AT UNCONTROLLED
                HAZARDOUS WASTE SITES --  IMPACTS OF WORKER
                    HEALTH AND SAFETY CONSIDERATIONS
                   J. Walsh, J. Uppitt, and M. Scitt
                              SCS Engineers
                          Covington, Kentucky
INTRODUCTION
    In December 1930,  the  U.S. Congress  passed  legislation  entitled
"The Comprehensive  Environmental Response, Compensation,  and  Liability
Act" which is olso  known as  Superfund.   Superfund  provides  the U.S.
Environmental Protection Agency  (EPA) with the  legislative  mandate
and the monetary base  to assist  in  the elimination of public  health
hazards posed by uncontrolled  hazardous  waste sites.   Section 105 of
the Superfund legislation  requires  the EPA to investigate the costs
of remedial/clean-up actions at  uncontrolled  waste sites.  Specifically,
Item 2 of Section 105  requires the  development  of  cost ranges for va-
rious types of remedial actions.

    Responsibility  for implementing Superfund actions and response
to uncontrolled hazardous  waste  sites  rests  primarily with the EPA
Office of tmergency £nd Remedial Response (OERR).   At the request of
OERR, the EPA Office of Research and Development (ORO) has been con-
ducting research on the costs  of remedial actions  to fulfill  the require-
ments of Section 105.   Iii  support  of these activities, several studies
have been conducted to evaluate  the types of remedial actions and as-
sociated costs applicable  co Superfund  c.ites (i.e., sites for which
Superfund monies have  been allocated)  and other hazardous waste sites.

    In these studies,  costs associated  with  health and safety of workers
were either not included  or not  uniformly identifiable as separate
cost items.  As a result,  the  project conducted and being presented
in this pa^r was designed to  specifically address the additional
costs of protecting worker health  and safety on a  hazardous waste site.
These costs do not include costs associated  with addressing concerns

-------
of the public  health and safety  in the  vicinity  around  an  uncontrolled
hazardous  waste  site.   However,  the  controls  and costs  associated  with
protection of  workers  en the  site  should  reflect much,  if  not at all,
of the additional  costs of  protecting  the public in areas  removed  from
the source of  contamination (i.e., the  hazardous waste  site itself).

    The objectives of  this  project were:
    1.  Identify categories  of health and safety costs.
    2.  Collect and compile  health and safety cost estimates and
        determine a range of costs which can be encountered on
        hazardous wastes sites.
    3.  Calculate percentage incremental health and safety cost
        adjustment factors.
    4.  Identify factors which impact health end safety costs and
        should be considered for future study and evaluation.
STUDY DESIGN AND APPROACH

    Initial data collection was based on reviews of case studies, bid
documents for Superfund sites, and a telephone survey of firms and
regulatory agencies.  After reviewing available data and the summaries
of the telephone survey, it wa'; determined that health and safety costs
could not be readily identified.  Normal accounting practices did not
distinguish many health and safety costs.  Such costs were routinely
incorporated into general categories such as labor rates, equipment
O&M costs, and overhead expenditures.  In addition, extensive analysis
of cost data from existing sites  was viewed by many contractors as
extremely sensitive due to competitive and proprietary considerations.
On the other hand, most of the contacts felt that general discussions
of costs would be of little value because of site specific considera-
tions which impact on the overall costs and particularly health and
safety costs.  As a "esult, it was concluded that realistic, but fic-
ticious, hazardous waste site scenarios would provide the best format
for providing ana evaluating cost estimates for remedial action unit
operations.  In fact, several of the contacts indicated they felt  it
was   the only reasonable approach.

-------
    From previous  studies  and  case  history  reports, 26 discrete reme-
dial action activities  (hereafter referred  to  as  remedial action
unit operations) were  identified.   Table  1  is  a list  of  the 28 remedial
acticn unit operations.  Th° basis  of classification  was the media
that the remedial  action-,  control.   The media  include surface water,
ground water, subsurface gas,  and waste.  Nine of these  are classified
as surface water controls, eight as ground  water  controls, three  as
gas migration controls,  and eight as waste  controls.

    Ten health and safety  cost components were idertified based on
literature reviews, previous site  observations, discussions with  field
personnel from state anc* federal regulatory officials,  and discussions
with cleanup contractors.   Table 2 is a  list of the ten health  and
safety cost categories identified.

    In providing cost estimates, contractors were requested  not to
address costs .if transportation and disposal,   This approach  was  taken
due to the amount of information available on transportation  and  dis-
posal costs and to minimize the amount of cost estimations required
of  the contractors responding to the scenarios.  A separate telephone
survey was conducted involving  11  transportation firms  to identify
current ranges cf transportation costs for hazardous waste..  Disposal
cost estimates were obtained from the 1981  update of the U.S. EPA
report entitled, "Review of Activities of Major Firms Involved in
Commercial Hazardous Waste Management Industry" [1].  Since transportation
and disposal costs are often  included as separate line  item costs,
separation of these costs  in  the scenarios is  consistent with
normal contractor procedures.

TELEPHONE  SURVEY

    An extensive telephone  survey was made to  identify  available sources
of data on health and safety  costs.  The survey  included:

-------
                      TABLE  1

           REMEDIAL  ACTION  UNIT  OPERATIONS
Surface Water Control s

1.  Surface Sealing with Synthetic Membrane
2.  Surface Sealing with Clay
3.  Surface Sealing with Asphalt
4.  Surface Sealing with Fly Ash
5.  kevegetation
6.  Contour Grading
'/.  Surface Water Diversion Structures
8.  Basins and Ponds
9*  Dikes and Berros

Ground Hater Controls
1.  Well Point System
2.  Deep Well System
3.  Drain System
4.  Injection System
5.  Bentonite Slurry Trenches
6.  Grout Curtain
7.  Sheet Piling Cutoff
8.  Grout Bottom Sealing

Ga s _M j g ra t i o n Controls
1.  Passive Trench Vents
2.  Passive Trench Barriers
3.  Active Gas Extraction Wells

Waste
1.  Chemical Injection
2.  Chemical Fixation
3.  Excavation
4.  Leachate Recirculation
5.  Treatment of Contaminated Water
6.  Drum Processing
7.  Bulk Tank Processing
8.. Transformer Processing

-------
                  TABLE  2

HEALTH AND SAFETY COST COMPONENT CATEGORIES
 1.  Decontamination
 2,  Emergency Preoaredness
 3.  Hazard Assessment
 4.  Insurance
 5.  Manpower Inefficiencies
 6.  Medical Services/Surveillance
 7.  Personal Protection
 8.  Personnel Training
 9.  Record Keeping
10.  Site Security

-------
    •   Forty-seven firms with experience in  remedial action responses
        on  hazardous waste sites.
    •   Eleven  state and federal regulatory agency  rapresentatives
        involved  with managanent and/or assessment  of hazardous waste
        site cleanup operations.
    e   Eight military  contacts  involved  in the management  and/or
        assessment of military hazardous waste sites.
    •   Six consulting  firms  that have conducted  studies  concerned
        with remedial actions on hazardous waste  sites.
    •   Three research  oriented  institutions  involved  in  hazardous
        waste management research activities.

    Each telephone  interview  was recorded on  a written  telephone  sum-
mary report, evaluated, and rated based on  the following  four  general
criteria:
    1.  Amount  of experience  in  assessment  and management of remedial
        actions on  hazardous  waste  s.tes.
    2.  The variety of  exoeriences  with  types of site,  and/or  remedial
        actions.
    3.  Access  to available data.
    4.  Willingness to  cooperate in providing data and discussing
        cost allocations.
HAZARDOUS WASTE SITE COSTING SCENARIOS

    Six hazardous waste site scenarios were developed to be represen-
tative of three basic types of sites:
    1.  Subsurface Burial
    2.  Surface Impoundments
    3.  Above-Grade Storage
Whenever possible, these scenarios were developed based on actual
cleanup operations either completed, in progress, or planned for the
future.  This approach was adopted to ensure that the scenarios would
reflect realistic site conditions while providing a means of controlling
site  variables which could impact cost estimates.

    Each scenario wai composed of a  number of distinct unit operations.
The combination of the unit operations represented a complete  remedial

-------
action program  for  each hypothetical site.  Site- characteristics
(e.g., size,  topography, hydrology, weather, etc.) were defined for
ear.h scenario to  provide a detailed profile on the site.  Similarly,
the characteristics of the wastes present on each site were defined
such that the degree-of-hazard conditions could be determined  for
each unit operation.  The degree-of-hazard conditions described re-
presented conditions which parallel four levels of personal protection
recommended in  the  Interim Standard Operating Safety Guides developed
by the Office of  Emergency and Remedial Response,  Hazardous  Response
Support Division, U.S. Environmental Protection Agency.  [2]  Table
3 provides a brief  description of  the  conditions associated with  the
four levels of  personal protection  (designated  as  Levels  A, B, C,
and D in order  of decreasing degree-of-hazard conditions).  Contrac-
tors were instructed  to utilize  the recommended guides  in determining
the  level of personal  protection required.

    Contractors providing  cost estimates  were-  instructed to provide
cost estimates  for  each  unit operation under the  conditions set forth
in the scenario and costs  representative  of  conducting  the same ac-
tivity if the hazardous  wastes were not on-site (i.e.,  base construc-
tion costs).  In order to  identify the relative impact of variations
 in degree-of-hazard conditions,  contractors  wen;  also instructed to
provide  cost estimates based on  three other modifications of hazard
conditions which were also specified.   The modifications were based
only  on  variations  of waste characteristics  while all  other site con-
ditions  and activities remained  constant.

    One  additional  factor identified which ifiay  significantly impact health
and  safety costs is ambient temperature.   To identify the relative
 impact of  temperature, contractors were instructed to provide an  es-
.timate of  the cost variations of the total scenario, health and safety
costs estimated  for each of the four degree-of-hazard conditions.
The  cost estimate  variations were based on the costs under the range
of  temperatures  given in the scenario and two additional temperature
 ranges.  The result was an estimate of total scenario health  and  safety

-------
                          TABLE 3

  CONDITIONS ASSOCIATED WITH LEVELS OF PERSONAL PROTECTION
1.   Level  A -  requires full encapsulation ami protection from
    any body contact or exposure to materials  (i.e.,  toxic by
    inhalation and  skin absorption).

2.   level  B -  requires self-contained breathing  apparatus  (SCBA),
    and cutaneous or percutaneous exposure  to  unprotected  areas
    of the body (i.e., neck and back of headj  is within acceptable
    exposure standards  (i.e.,  below harmful  concentrations).

3.   Level  C -  hazardous constituents known;  protection required
    for low level concentrations in air;  exposure of  unprotected
    body areas (i.e.,  head, face, and neck)  is not harmful.

4.   Level  0 -  no identified hazard present,  but conditions are
    monitored  and minimal  safety equipment  is  available.

-------
costs under the four degree-of-hazard conditions  for low  (<0°C), nor-
mal (0-18°C), and high (18-38°C)  ambient temperature ranges.   The
relative temperature ranges included wind chill considerations.

    The selection of contractors  to respond to the scenarios  was based
on the following criteria:
    •   Their relative rating provided froni the evaluation of the
        telephone survey results.
    •   A match of their previous exper^nce with sites similar to
        one or more of the scenarios.                   •
    •   The availability of personnel routinely involved in cost esti-
        mation and familiar with health and safety requirements on
        a hazardous waste site.
    t   Project funding limitations for payment of subcontractors
        (i.e., site cleanup contractors) to provide cost estimates.
The final selection included seven hazardous waste cleanup contrac-
tors responsible for one to three scenarios apiece.  Each scenario
was assigned to two different contractors for cost estimation.

    A questionnaire was also sent to the contractors providing cost
estimates.  The questionnaire was designed to identify differences
in approaches to health and safety considerations which impact costs.
The purpose of requesting the 'information was to provide additional
information to assist in determining probable reasons for cost vari-
ations  anticipated.  In addition, contractors were  requested  tc com-
ment on other considerations or differences,  if any, that they con-.-
 sidered significant.

TRANSPORTATION COST SURVEY

     Initial  literature  search and review was  based  on  (1) in-house
 library sources, and  (2) the U.S. EPA Research Library in the
 Environmental  Research  Center  in  Cincinnati,  Ohio.   The  available
 literature  did not  specifically address  transportation costs  for  haz-
 ardous  waste cleanup sites.  Very little  current  data  (1980  to 1982) was
 available  for  hazardous materials  transportation costs.   Additional

-------
efforts were  made  to identify cost  information  from current studies.
Unfortunately,  none of the data  was available.

    In order  to obtain current cost data,  a  telephone survey of trans-
portation companies and services was conducted.  A telephone inter-
view questionnaire was developed for data  collection from companies
contacted.  Eleven companies were contacted.  A total of six responses
were obtained and  can be categorized into three major groups:
    1.  Companies  concentrating or specializing in transportation
        of hazardous wastes.
    2.  Companies  whose main interests and efforts involve general
        freight and commodities and only limited involvement in
        hazardous  waste transportation.
    3.  Waste disposal and treatment companies who provide trans-
        portation services for their customers.
Two responses were obtained from companies  in each category.

RESULTS AND DISCUSSION

Responses to Scenarios

    A  total of eleven completed remedial action costing scenarios
were  returned.  Two contractors could  not proviJe  the recj'jcsted cost
estimates within  the  required time  period due  to conflicting work
schedules.  As a  result,  cost estimates for Scenario 5 were  provided
by only one contractor.   The remaining Scenarios 1,  2, 3,  4, and 6
were  estimated by two contractors  apiece.

    The original  cost estimates were  reviewed  and  modifications were
made  (e.g.,  assigning travel and per  diem costs  to bas;e construction
 costs instead  of  health  and  safety costs, correction of calculation
 errors,  etc.).     Additional  information was requested, as necessary,
 to reallocate  costs  to  uniformly cover the  health  and safety cost
 component items.   Modifications were  reviewed  with the respective
 contractors.   Cost estimates were  provided  for the four degree-of-
 hazard conditions which  were established  in the scenarios.  The  degree-
                                   10

-------
of-hazard conditions  were identified  as  Levels  A,  B,  C,  anr* D which
indicate maximum level  of personal  protection required based on the
information given in  the scenario  information/instruction packets ser.t
to the contractors.   The degree-of-hazerd  condition designated Level
A as the worst case,  while Level  D is the  least hazardous condition.

    In Scenario 2, costs were only requested for Level C conditions
which were considered sufficient  for  worker protection for handling
PCB's.  The scenario  was included  because  of the number of sites and
public concern involving electrical equipment containing PCB's and
the special requirements established  for PCB's by the Toxic Substances
Control Act (TSCA).

    The contractor's  cost estimates were compiled and evaluated, then
used to calculate a cost per unit range for each remedial action unit
operation.  Cost per unit calculations were made for health and safety
costs at the four degree-of-hazard conditions and for base construction
costs.  Table 4 shows the cost per unit ranges calculated.  A percen-
tage incremental cost factor was calculated by dividing the health
and safety costs per jnit for each of the I'egree-of-hazard conditions
by the costs per unit calculated for  the base construction costs.  The
resulting percent range of incremental health and safety cost adjust-
ment factors are presented in Table 5.  Estimates for those ramedial
action unit operations not costed as  part of the six cost scenarios
can be calculated based on a comparison of potential worker exposures
while conducting remedial action unit operations.  The types of ac-
tivities which determine the potential for worker exposures were
identified for each of the 28 remedial action unit operations as pre-
sented in Table 6.

    The estimated impacts of temperature on  remedial  action costs ars
summarized in Table 7.  The original  estimates did provide costs for
each unit operation, b'it the specific component costs which contractors
Considered temperature sensitive and the amount of the  impact were  not
                               11

-------
                                                                                       TABLE  4

                                                              RANGE  OF HEALTH  AND  SAFETY  COSTS PER  UNIT*
ro
Unit Operation
Surface Water Control;:
Surface Seal - Synthetic Kenbrane

Surface Seal - Cloy

fle-'flqc tat Ion*

Contour Grading

Surface Water Diversion

Basins and Ponds

Dikes and Berrr.s

Ground Water Controls:
Wall Point System

Drain System

Bentonite Slurry Trench

Waste Controls:
Crenlcal Fixation (Sol idlf lea tlon)

Encovc'.ion of Wastes/Contaminated Soil

Treatment of Contaminated Watsr

OI-UTI Processing

Sulk Tank Processing


Transformer Processing
UnH of
Heaijre

nZ
ST. yd
m*
sq yd
ha
acre
m3
cu yd
n3
cu vd
m-l
cu vd
m3 '
cu yd

m2
sq yd
n3
lu yd
.1,3
cu yd

m3
cu yd
ml
cu yd
V My
&•
208 1 (b5
98 1) drums
30.280 1
(8,000 gal)
tinks
Transforrer
Bas? Construction
Costs Per Unit

JU.11-J19.65
J17.24-J23.50
SZ.74
52.29
J6.373-J124.000*
S2.549-J49.600
«. 95-15. 76
J2. 22-54. 40
Jl .91-516.05"
•J. 45-512. 28
J4.S.VSK.53
J1.46-S5.5Z
J'iZ.78-J15.96
$9.78-$12.21

J133
Jill
J38.87-J49.22
J29.72-J37.63
S50.95
$38.97

J25.06-J147.33
J19.16-J112.63
J3.10-J324.41
J2.37-J248.08
J0.09-J14.31
S0.35-J53.49

JJ5.1S-J630.89


J1.ZZ2-J4.032
J2IO-S330

level D

J1.13-J3.99
S1.35-J4.77
JO. 26
JO.JJ
l;43-J65,115
SI36-J26.046
SO. 38- J2. 10
S0.29-SI.61
J0.23-S9.13
J0.17-S6.99
J0.4I-J3.45
J0.31-J2.54
JO. 34-J14. 68
S0.65-J11.23

J11.70
S9.78
J3.31-J22.99
J2.53-J17.58
J4.46
J3.41

(2.7S-J46.6Z
S2.10-S35.64
$14. 53-5112. 10
$11.11-585.72
J0.01-J5.35
J0.03-SJ0.27

SS1.91-J928.42


51,047-54,162
•~
Health and Safety Costs Per Unit
level C

J2.06-J4.63
J2.46-J5.53
JO. 52
50.43
J1.215-J73.342
J486-J29.337
JO. 73-52.66
J0.56-J2.03
JO.i8-J10.7Z
tO.29-J8.20
J0.93-J4.60
50.7I-J3.SZ
J2.65-J19.94
52.03-J15.26

S19.63
516.41
S5.1/-S29.7S
S4.72-J22.75
J6.97
55.33

$4.12-560.97
J3.I5-J46.S1
J5.90-524S.42
54.51-5188.44
50.01-55.44
50.05-120.59

569.63-51.165.63


Tl 925-55.560
J48. 57-51. 195
Le/cl 8

JZ.41-J5.19
J2.88-J6.56
JO. 66
JO. 55
JI.ZI5-J74.940
J485-J29.976
S0.96-J1.02
JO. 73-52. 31
JO. 46-512. 34
>u. 35-59. 44
;i. 28-J5. 22
J0.98-J3.99
J3.04-V20.91
J2. 33-516. 00

J24.06
J20.12
J7.51 -J12. 46
J5.74-j:'l.8Z
J15.40
J12.51

J4. 29-570. 04
J3.Z8-5S3.S4
J24. 70-5169. 38
J18.E8-JI29.53
SO.OZ-S5.14
JO. 05-523. 22

SS8. 89-51. 402. 8G


55,570-56,358


leve^ A

52.48-55.93
J2 97-57. OC.
50.74
50.62
5I.2J5-578.6V7
5435-;31.455
SO. 97-53. 7C
50.75-52.83
SO. 47-513. 34
J0.36-S1C.20
SI.59-J5.58
J1.21-J4.Z7
J3.35-J23.3.
J2.57-J17.83

531.34
$25.20
S10.60-S34.06
58.10-526.04
518.24
513.94

54. 64-580. 38
53.55-561 45
JZ2. 99-5198. OZ
JZZ.17-J1S1.4J
J0.02-J6.97
JO.C8-S26.37

S10i.68-J1.690.07


58,354-58,414

                    •  Cost ranges are not adjusted for economy of  scale or regloial variations.
                    »  .'ange Includes cost estimates  fron one contractor which were significantly hlghor  than the others.
                    *  A coroosite of base construction costs for revegdallon from previous  SCS report [3] y'.elds a r»nje of 53,974 - 5"i8,0'9 per ha (51,6Cj  • 57,300 p*r  acre).
                    •• Costi fron previous SCS report [3] yield cosl ranges of 51.75 - $3.63  per n>J (51.34 • $2.78 per cu yd) for  surface x»tcr diversion base construction.

-------
                          TABLE  5

INCREMENTAL HEALTH AND  SAFETY  COSTS  — RANGE OF PERCENTAGE
         ADJUSTMENTS  OVER  BASE CONSTRUCTION COSTS
Degree -of -Hazard Conditions
CnH Operation
Surface War^r Controls:
1. Surface Sealing - Synthetic MtiTiorane
2. Surface Selling - Clay
3. Surface Sealing - Asphalt
4. Surface Seating - Fly Ash
5. Revegetatlon
6. Contour Grading
7. Surface Water Diversion Structures
8. !as1ns ard Ponds
». Dikes and Berns
Ground V'ater Controls:
1. Well Point System
2. Deep Well System
3. Drain iysten
4. Injection Systcn
5. Gentonlte Slurry Trench
6. Orout Curtain
7. Sheet Piling Cutoff
8. Grout Bottora Sealing
Gas Migration Controls:
1 . Passive Trench Verts
2. Passive Trench Barriers
3. Active Gas Extraction System
Wjs'.c Co-trols:
'. Chemical FinsMon (Solidification)
2. Chtfcilcal Injection
3. Excavation of Wsstes/Centa.Tlnated Soii
4. leacha'.e P.eclrculatlon
5. Treatnent of Contaminated Water
6. Drun Processing
7. Bulk Tank Processing
8. TransfOmer Processing
Level 0

8-20t
91
•-
-.
5-53S
9-«5l
12-57X
9-401
7-921

IDS
•-
9-47X
--
9*
--
•-
~~





11-3JI
"-
32-S45J
--
11-3Bt
3M66I
86-103J
~~
Lsvel C

14-26X
19t
--
--
12-591
17-57:
20-671
21-541
21-1251

171
••
16-601
••
141
•-
•-
"





16-411
*-
4«-6Ut
--
11-381
75-1921
138-1581
23-36 I
Level b

17-281
241
--
•>-
13-601
22-651
24-771
28-511
24-1311

211
•-
19-651
--
321
•-
--
--





17-481
--
50-785S
--
22-43X
50-2771
173-4641
--
Level A

17-301
271
•-
--
u-63:
24-80;
25-831
35-65X
26-1461

28T
--
27-691
•-
361

--






19-551
--
58-19901
--
?2-*9t
58-3:31
209-6 SCI
-•

-------
                             TABLE  6

ACTIVITIES WHICH  IMPACT  POTENTIAL WORKER EXPOSURES WHILE
   CONDUCTING REMEDIAL ACTIONS  ON HAZARDOUS WASTE  SITES"
                                     —   CO
                                         o TJ   —
                                         I C   TJ
      IMt Operation
      Surface Viler Controls:
1.
2.
3.
4.
S.
6.
7.
8.
9.
Gro,
1.
2.
3.
4.
•5.
6.
7.
a.
Gas_
I.
j.
3.
V'«S
1 .
z.

».
b.
6.
7.
a.
Surface Sealing - Synthetic Menbrane
Surface Sealing - Clay
Surface Selling - Asphalt
Surface Sea1 ing - Ply Ash
Reve gelation
Contour Grading
Surface Wau>r Divert ion Structures
Sasins an< Ponds
OUes 
-------
                                                                 TABLE  7

                                       IMPACT  OF  TEMPERATURE ON REMEDIAL ACTION  COSTS
HeiUn and
Contrictor-
1-1


11-1


1-2


in-2


U-3


IV- 3


III-4


IY-4


IV-i


III-6


V-6


Temperature
~**C
0-18'
18-33°

-------
idr-ntified.  Therefore,  revisions  of  original  cost estimates,  after
ceviaw of data and follow-up telephone  contacts,  prevented  direct
modification of individual  unit operations.   However,  general  indica-
tions of temperature impacts can be drawn  from the data provided.
The percent variations were based on  increases above base construction
costs estimated for the moderate 0 to 18°C range.   As  shown in Table
7, base construction costs and health and  safety  increased with higher
or lower temperatures.  Use of an average  variation (as shown in Table
8) would enable general estimate adjustments relative to the impact
of anticipated seasonal or climatic temperature differences.

Transportation and Disposal Costs

    The costs of transportation of ha?ardous wastes varies widely
with respect to specific jobs and the type of company employed to
transport  the wastes.  In addition, the lack of standardized rates
con result in evi-.n more variation depending on the amount of compe-
tition for a given job.  The ranges obtained from this survey should
re'Hect cost for most of the hazardous waste transporcation, but will
not reflect unusual costs associated with some sites.
     Rates  can be based on costs per mile, cost per unit measure  (i.e.,
 volume  and/or weight of cargo) or a cost per hour.  A cost per mile
 rate assumes full  use of vehicle load capacity.  Economies of scale
 will apply to cost per mile and cost per unit measure rates.  This
 is true for ..lileage rates because the cost effectiveness  of  operation
 is greater when  the ratio of  time on the road increases over the down
 time spent for mobilizing, loading, and unloading.  When  rates are
 based on cost per  unit measure, the cost per unit will decrease  as
 load capacity is appror.ched since the cost of transporting  (i.e.,
 costs previously identified)  are divided a;7
-------
                                                  TABLE 8
                        AVERAGE  PERCENT COST  VARIATIONS DUE TO  TEMPERATURE
Temperature
•c
0-18°
18-33-

-------
unloading periods,  and for  additional  costs  of detention  times  ex-
ceeding the time allocated  (included in  the  cost  per mile or cost
per unit measure rates).  Table 9 contains  the  ranges of  rates  obtained
during the survey.   Table 10 is a range  of  costs  provided by one of
the general freight transporters which provides an indication of the
impact of distance on rates.

    The disposal costs used for this project (shown in Table 11) were
obtained from an EPA publication "Review of Activities of Major Finns
ir; the Commercial Hazardous Waste Management Industry:  1981 Update",
SW-894.1.  As indicated on the table, the data  was based on interviews
conducted  in May 1980 and February 1982.  The assumptions made to
convert estimates to $/wet metric tons (KMT), when conversion factor
estimates were not available, were reported to b<>:
    •   Volumes  in gallons were con-.^rted to WMT a.-suming the waste
        density was that of water (i.e., 8.34 Ib/gal or 0.0037 WMT/gai).
    •   Cubic yards were converted to WMT on the assumption of density
        equal to water at 62.4  Ib/cu ft or  0.76 WMT/cu yd.
    •   Volumes disposed of in  landfills were assumed to  be bulk ma-
         terials  unless drum and  bulk distribution was stated.
    t    Capacity reported  in acres was converted  to  WMT  by  assuming
         available  capacity of  430,000 cu ft/acre  or  H disposal  ca-
         oacity  of  12,100 WMT/acre.

 SUMMARY  MD  COUCH'S I ON

    Cost-effectiveness evaluations  of Superfund  expenditures require
 consideration of additional costs of  protecting  workers'  health and
 safety.   Unfortunately,  not much cost data  has been available  concerning
 health and safety  considerations.   This  study  represents part  of  the
 effort  to identify and  estimate costs  associated with  protection
 of worker health and  safety.   Although  the  findings and  result? of
 this  project cannot be considered the final answer, they will  enable
 site  management and planning  personnel  to  generalize hec.lth and safety
 cost impacts.
                                   18

-------
                                    TABLE  9

     RANGES OF TRANSPORTATION COSTS  BY  TYPF  OF  TRANSPORTER
         	Type of Transporter
                                                               Kates
         Treatment, Storage, aid Disposal  facilities
           Prodding Service to Cultcurers

         General  Freight Transportation Companies
           Wtilch  Pay Haul Hazardous  Wastes on Request

         Hditrdous Waste Transportation Cotrpintes
           Sptctalitinj in Hazardous. Wastes
J0.75-J2.57


tt.75-J3.7J


J1.99-J2.60
         •  Range twijd on 3M to 1,609 k» (100 to 1.000 n\les) <»it«nco for one-
             «> shipment nt. JJ/2M.i tj (100 Ibs).
                                   TABLE  10
RATE  SCHEDULES  FOR VARIOUS DISTANCES  AND GEOGRAPHIC  LOCATIONS
QiiUncc
(inl
370
C60
7W
1.110
l.«BO
1.8M
>4.630


Cast of the
Hississi(,ol
il.6?
1.3-',
1.1C
0.96
O.B6
G.81'
0.81
iii-si '.nation kales'
One-kJy
Utst of tne
C.isstsslppi
J1.78
1.S1
I.i4
Mb
1.05
1.00
O.W«
"
Round
Trip
J1.J7
1.01
O.B6
0.74*
0.74
0.74
.0.14
       • Rales tuoted (n dollars per km.
       « Minlnun rate-n-mains constant  for all dlstai.ces  above that shown.
                                         19

-------
                                                            TABLE  11

                             COMPARISON OF HAZARDOUS  WASTE  MANAGEMENT QUOTED PRICES FOR
                               ALL  FIRMS  IN 1980  AND  FOR NINE  MAJOR  FIRMS  IN   1981*
Type of Waste Management
landfill
Land Treatment
Inclnerat/on
Chemical Treatment
f"O Resource Recover/
O
Deep Well Injection
7rsnsnorta?1on
Type Or Form of Vjste
D-um
Bulk
All
Relatively clean liquids, high
Blu value
Ltqu
-------
    Several  factors  which  impact  cost were  identified,  but not addressed
within the scope of  this project.   These  include:
    •   Scale Economies
    •   Regional Differences
    •   Management Policies and Procedures
    f   Type and Size of Company
Previous studies have shown scale economies and regional  variations
to be significant in construction costs.  It would  be reasonable  to
assume similar impacts on  health and safety costs, however,  it was
not possible to quantify  the  impact cf these factors based on the
existing data.

    During the course of  this project, differences in the management
procedures and policies were  identified which impacted the cost  esti-
mates provided.  Currently, there are no regulatory standards which
are uniformly enforced on  hazardous waste sites.  Therefore, the impact
of safety management policies and procedures of individual contractors
can significantly impact  health and safety costs.   In addition,  the
emphasis placed by a given contractor on the use of equipment versus
manpower to accomplish the tasks required, can also impact the health
and safety costs due to the differences in the exposure potential
for workers operating machinery versus workers directly handling con-
tainers arid/or contaminated materials.

    The type and size of companies involved will  impact their ability
to make most efficient use of equipment and personnel.  Large companies
with  deep resources and a  backlog of work projects can coordinate
the use of equipment and personnel ;among  projects to be more cost-
efficient.  However, smaller companies or specialty firms with smaller
resources and  fewer projects may incur higher costs in order to main-
tain  a qualified staff, and cover overhead expenses of  idle equipment.
                                  21

-------
Use of the  data  from  this  report  should  include evaluation of pos-

sible impacts  of these  factors.


    The primary  result  of  this  report  is a  means  to  adjust remedial

action cost estimates to  reflect  additional  costs of health  and  safety
considerations.   This may  involve adding these  health and safety costs

to engineering study  cost  estimates  based on standard construction

cost estimates,  or adjusting cost estimates from  actual  sites.   Adjust-

ments made  will  reflect the costs associated with variations in  the
degree-of-hazard conditions on  the site  being evaluated.  Additional

applications may include:

    •  Calculation of costs for various  applications of  unit opera-
       tions.   For example, the cost of  constructing a drain system
       for  leachate collection  could be  evaluated for en-site  versus
       off-site locations.  The added  costs for increasing  the  inter-
       cept area off-site  could be compared with  the added  costs cf
       worker safety and  health considerations  for a smaller system
       installed in (.he contaminated areas on-site.

    •  Planning of site assessment activities prior to initiation of
       remedial  action activities.  The  worst degree-of-hazard  con-
       dition which is anticipated,  based on available information,
     •  would determine the cost of worker health  and safety protection
       which would be provided.  The potential  savings of reduced health
       and  safety costs for le^ hazardous conditions could be  calcu-
       lated.   The cost-effectiveness  evaluation  of conducting more
       detailed site characterization and waste stream identifications
       to define degree-of-hazard conditions could then  include con-
       sideration of potential  savings if conducted prior to initiation
       of remedial actions.


ACKNOWLEDGEMENTS


     The project discussad in this paper was performed under U.S. EPA
Contract No. 68-03-3028, Directive of Work No.  14,  The authors would
like  to thank the U.S. EPA Project Monitors, D. Ammon and D. Banning
of  the U.S. EPA Municipal  Fnvirormental  Research Laboratory, Solid

and  Hazardous Waste Research Division in Cincinnati, Ohio.
                               22

-------
DISCLAIMER

    The information and data presented in this paper do not necessarily
reflect the views and policy of the U.S.  EPA.   This paper was based
on the Draft Final Report - Costs of Remedial  Actions at'Uncontrolled
Hazardous Waste Sites -- Worker Health and Safety Considerations which
is currently in the U.S. EPA peer review process.
REFERENCES

1.  Review of Activities of Ma^,or Firms Involved in the Commercial
    Hazardous Waste Management Industry:  1981 Update.  SW-894.1, U.S.
    Enivornmental Protection Agency, Washington, D.C.  May 1982.  17
    PP.

2.  Interim Stande'-d Operating Safety Guides, U.S. Environmental  Pro-
    tection Agency, Office of Emergency and Remedial  Response,  Hazardous
    Response Support Division, Edison, New Jersey, September  1982.
    119 pp.

3.  Remedial Actions at Hazardous Waste Mtes:  Survey and Case Studies.
    EPA 430/9-81-05 SW-910.  Oil and Special  Materials Control  Division,
    U.S.  Environmental Protection Agency, Washington, D.C.  January
    1981.
                                     23

-------